WorldWideScience

Sample records for test project phase

  1. Phase Startup Initiative Phases 3 and 4 Test Plan and Test Specification ( OCRWM)

    Energy Technology Data Exchange (ETDEWEB)

    PAJUNEN, A.L.; LANGEVIN, M.J.

    2000-08-07

    Construction for the Spent Nuclear Fuel (SNF) Project facilities is continuing per the Level III Baseline Schedule, and installation of the Fuel Retrieval System (FRS) and Integrated Water Treatment System (IWTS) in K West Basin is now complete. In order to accelerate the project, a phased start up strategy to initiate testing of the FRS and IWTS early in the overall project schedule was proposed (Williams 1999). Wilkinson (1999) expands the definition of the original proposal into four functional testing phases of the Phased Startup Initiative (PSI). Phases 1 and 2 are based on performing functional tests using dummy fuel. This test plan provides overall guidance for Phase 3 and 4 tests, which are performed using actual irradiated N fuel assemblies. The overall objective of the Phase 3 and 4 testing is to verify how the FRS and IWTS respond while processing actual fuel. Conducting these tests early in the project schedule will allow identification and resolution of equipment and process problems before they become activities on the start-up critical path. The specific objectives of this test plan are to: Define the Phase 3 and 4 test scope for the FRS and IWTS; Provide detailed test requirements that can be used to write the specific test procedures; Define data required and measurements to be taken. Where existing methods to obtain these do not exist, enough detail will be provided to define required additional equipment; and Define specific test objectives and acceptance criteria.

  2. Phase Startup Initiative Phases 3 and 4 Test Plan and Test Specification (OCRWM)

    International Nuclear Information System (INIS)

    PAJUNEN, A.L.; LANGEVIN, M.J.

    2000-01-01

    Construction for the Spent Nuclear Fuel (SNF) Project facilities is continuing per the Level III Baseline Schedule, and installation of the Fuel Retrieval System (FRS) and Integrated Water Treatment System (IWTS) in K West Basin is now complete. In order to accelerate the project, a phased start up strategy to initiate testing of the FRS and IWTS early in the overall project schedule was proposed (Williams 1999). Wilkinson (1999) expands the definition of the original proposal into four functional testing phases of the Phased Startup Initiative (PSI). Phases 1 and 2 are based on performing functional tests using dummy fuel. This test plan provides overall guidance for Phase 3 and 4 tests, which are performed using actual irradiated N fuel assemblies. The overall objective of the Phase 3 and 4 testing is to verify how the FRS and IWTS respond while processing actual fuel. Conducting these tests early in the project schedule will allow identification and resolution of equipment and process problems before they become activities on the start-up critical path. The specific objectives of this test plan are to: Define the Phase 3 and 4 test scope for the FRS and IWTS; Provide detailed test requirements that can be used to write the specific test procedures; Define data required and measurements to be taken. Where existing methods to obtain these do not exist, enough detail will be provided to define required additional equipment; and Define specific test objectives and acceptance criteria

  3. Phased Startup Initiative Phases 3 and 4 Test Plan and Test Specification (OCRWM)

    International Nuclear Information System (INIS)

    PITNER, A.L.

    2000-01-01

    Construction for the Spent Nuclear Fuel (SNF) Project facilities is continuing per the Level III Baseline Schedule, and installation of the Fuel Retrieval System (FRS) and Integrated Water Treatment System (IWTS) in K West Basin is now complete. In order to accelerate the project, a phased start up strategy to initiate testing of the FRS and IWTS early in the overall project schedule was proposed (Williams 1999). Wilkinson (1999) expands the definition of the original proposal into four functional testing phases of the Phased Startup Initiative (PSI). Phases 1 and 2 are based on performing functional tests using dummy fuel. These tests are described in separate planning documents. This test plan provides overall guidance for Phase 3 and 4 tests, which are performed using actual irradiated N fuel assemblies. The overall objective of the Phase 3 and 4 testing is to verify how the FRS and IWTS respond while processing actual fuel. Conducting these tests early in the project schedule will allow identification and resolution of equipment and process problems before they become activities on the start-up critical path. The specific objectives of this test plan are to: (1) Define the test scope for the FRS and IWTS; (2) Provide detailed test requirements that can be used to write the specific test procedures; (3) Define data required and measurements to be taken. Where existing methods to obtain these do not exist, enough detail will be provided to define required additional equipment; and (4) Define specific test objectives and acceptance criteria

  4. Results of single borehole hydraulic testing in the Mizunami Underground Research Laboratory project. Phase 2

    International Nuclear Information System (INIS)

    Daimaru, Shuji; Takeuchi, Ryuji; Onoe, Hironori; Saegusa, Hiromitsu

    2012-09-01

    This report summarize the results of the single borehole hydraulic tests of 79 sections conducted as part of the Construction phase (Phase 2) in the Mizunami Underground Research Laboratory (MIU) Project. The details of each test (test interval depth, geology, etc.) as well as the interpreted hydraulic parameters and analytical method used are presented in this report. (author)

  5. OECD/NEA Sandia Fuel Project phase I: Benchmark of the ignition testing

    Energy Technology Data Exchange (ETDEWEB)

    Adorni, Martina, E-mail: martina_adorni@hotmail.it [UNIPI (Italy); Herranz, Luis E. [CIEMAT (Spain); Hollands, Thorsten [GRS (Germany); Ahn, Kwang-II [KAERI (Korea, Republic of); Bals, Christine [GRS (Germany); D' Auria, Francesco [UNIPI (Italy); Horvath, Gabor L. [NUBIKI (Hungary); Jaeckel, Bernd S. [PSI (Switzerland); Kim, Han-Chul; Lee, Jung-Jae [KINS (Korea, Republic of); Ogino, Masao [JNES (Japan); Techy, Zsolt [NUBIKI (Hungary); Velazquez-Lozad, Alexander; Zigh, Abdelghani [USNRC (United States); Rehacek, Radomir [OECD/NEA (France)

    2016-10-15

    Highlights: • A unique PWR spent fuel pool experimental project is analytically investigated. • Predictability of fuel clad ignition in case of a complete loss of coolant in SFPs is assessed. • Computer codes reasonably estimate peak cladding temperature and time of ignition. - Abstract: The OECD/NEA Sandia Fuel Project provided unique thermal-hydraulic experimental data associated with Spent Fuel Pool (SFP) complete drain down. The study conducted at Sandia National Laboratories (SNL) was successfully completed (July 2009 to February 2013). The accident conditions of interest for the SFP were simulated in a full scale prototypic fashion (electrically heated, prototypic assemblies in a prototypic SFP rack) so that the experimental results closely represent actual fuel assembly responses. A major impetus for this work was to facilitate severe accident code validation and to reduce modeling uncertainties within the codes. Phase I focused on axial heating and burn propagation in a single PWR 17 × 17 assembly (i.e. “hot neighbors” configuration). Phase II addressed axial and radial heating and zirconium fire propagation including effects of fuel rod ballooning in a 1 × 4 assembly configuration (i.e. single, hot center assembly and four, “cooler neighbors”). This paper summarizes the comparative analysis regarding the final destructive ignition test of the phase I of the project. The objective of the benchmark is to evaluate and compare the predictive capabilities of computer codes concerning the ignition testing of PWR fuel assemblies. Nine institutions from eight different countries were involved in the benchmark calculations. The time to ignition and the maximum temperature are adequately captured by the calculations. It is believed that the benchmark constitutes an enlargement of the validation range for the codes to the conditions tested, thus enhancing the code applicability to other fuel assembly designs and configurations. The comparison of

  6. Test Plan for Hydrogen Getters Project - Phase II

    International Nuclear Information System (INIS)

    Mroz, G.

    1999-01-01

    Hydrogen levels in many transuranic (TRU) waste drums are above the compliance threshold, therefore deeming the drums non-shippable to the Waste Isolation Pilot Plant (WIPP). Hydrogen getters (alkynes and dialkynes) are known to react irreversibly with hydrogen in the presence of certain catalysts. The primary purpose of this investigation is to ascertain the effectiveness of a hydrogen getter in an environment that contains gaseous compounds commonly found in the headspace of drums containing TRU waste. It is not known whether the volatile organic compounds (VOCs) commonly found in the headspace of TRU waste drums will inhibit (''poison'') the effectiveness of the hydrogen getter. The result of this study will be used to assess the feasibility of a hydrogen-getter system, which is capable of removing hydrogen from the payload containers or the Transuranic Package Transporter-II (TRUPACT-II) inner containment vessel to increase the quantity of TRU waste that can be shipped to the WIPP. Phase II for the Hydrogen Getters Project will focus on four primary objectives: Conduct measurements of the relative permeability of hydrogen and chlorinated VOCs through Tedlar (and possibly other candidate packaging materials) Test alternative getter systems as alternatives to semi-permeable packaging materials. Candidates include DEB/Pd/Al2O3 and DEB/Cu-Pd/C. Develop, test, and deploy kinetic optimization model Perform drum-scale test experiments to demonstrate getter effectiveness

  7. The International intraval project. Phase 1 test cases

    International Nuclear Information System (INIS)

    1992-01-01

    This report contains a description of the test cases adopted in Phase 1 of the international cooperation project INTRAVAL. Seventeen test cases based on bench-scale experiments in laboratory, field tests and natural analogue studies, have been included in the study. The test cases are described in terms of experimental design and types of available data. In addition, some quantitative examples of available data are given as well as references to more extensive documentation of the experiments on which the test cases are based. Fithteen test cases examples are given: 1 Mass transfer through clay by diffusion and advection. 2 Uranium migration in crystalline bore cores, small scale pressure infiltration experiments. 3 Radionuclide migration in single natural fractures in granite. 4 Tracer tests in a deep basalt flow top. 5 Flow and tracer experiment in crystalline rock based on the Stripa 3-D experiment. 6 Tracer experiment in a fracture zone at the Finnsjon research area. 7 Synthetic data base, based on single fracture migration experiments in Grimsel rock laboratory. 8 Natural analogue studies at Pocos de Caldas, Minais Gerais, Brazil. Redox-front and radionuclide movement in an open pit uranium mine. 9 Natural analogue studies at the Koongarra site in the Alligator Rivers area of the Northern Territory, Australia. 10 Large block migration experiments in a block of crystalline rock. 11 Unsaturated flow and transport experiments performed at Las Cruces, New Mexico. 12 Flow and transport experiment in unsaturated fractured rock performed at the Apache Leap Tuff site, Arizona. 13 Experiments in partially saturated tuffaceous rocks performed in the G-tunnel underground facility at the Nevada Test site, USA. 14 Experimental study of brine transport in porous media. 15 Groundwater flow in the vicinity of the Gorleben Salt Dome, Federal Republic of Germany

  8. Prototypical Rod Construction Demonstration Project. Phase 3, Final report: Volume 1, Cold checkout test report, Book 3

    Energy Technology Data Exchange (ETDEWEB)

    1993-05-01

    The objective of Phase 3 of the Prototypical Rod consolidation Demonstration Project (PRCDP) was to procure, fabricate, assemble, and test the Prototypical Rod consolidation System as described in the NUS Phase 2 Final Design Report. This effort required providing the materials, components, and fabricated parts which makes up all of the system equipment. In addition, it included the assembly, installation, and setup of this equipment at the Cold Test Facility. During the Phase 3 effort the system was tested on a component, subsystem, and system level. This volume 1, discusses the PRCDP Phase 3 Test Program that was conducted by the HALLIBURTON NUS Environmental Corporation under contract AC07-86ID12651 with the United States Department of Energy. This document, Volume 1, Book 3 discusses the following topics: Downender Test Results and Analysis Report; NFBC Canister Upender Test Results and Analysis Report; Fuel Assembly Handling Fixture Test Results and Analysis Report; and Fuel Canister Upender Test Results and Analysis Report.

  9. Test Specification of A1-1 Test for OECD-ATLAS Project

    International Nuclear Information System (INIS)

    Kang, Kyoung-Ho; Moon, Sang-Ki; Lee, Seung-Wook; Choi, Ki-Yong; Song, Chul-Hwa

    2014-01-01

    In the OECD-ATLAS project, design extension conditions (DECs) such as a station blackout (SBO) and a total loss of feed water (TLOFW) will be experimentally investigated to meet the international interests in the multiple high-risk DECs raised after the Fukushima accident. The proposed test matrix for the OECD-ATLAS project is summarized in Table 1.. In this study, detailed specification of the first test named as A1-1 in the OECD-ATLAS project was described. The target scenario of the A1-1 test is a prolonged SBO with delayed supply of turbine-driven auxiliary feedwater to only SG number 2 (SG-2). A SBO is one of the most important DECs in that without any proper operator actions, a total loss of heat sink leads to core uncover, to core damage, and ultimately a core melt-down scenario under high pressure. Due to this safety importance, a SBO is considered to be a base test item of the OECD-ATLAS project. A detailed specification of the first test named as A1-1 in the OECD-ATLAS project was described. The target scenario of the A1-1 test is a prolonged SBO with delayed supply of turbine-driven auxiliary feedwater to only SG-2 in order to consider an accident mitigation measure. The pre-test analysis using MARS code was performed with an aim of setting up the detailed test procedures for A1-1 test and also gaining the physical insights for a prolonged SBO transient. In the A1-1 test, a prolonged SBO transient will be simulated with two temporal phases: Phase (I) for conservative SBO transient without supply of turbine-driven auxiliary feedwater and Phase (II) for asymmetric cooling via single trained supply of turbine-driven auxiliary feedwater

  10. Recovery Efficiency Test Project: Phase 1, Activity report

    Energy Technology Data Exchange (ETDEWEB)

    Overbey, W.K. Jr.; Wilkins, D.W.; Keltch, B.; Saradji, B.; Salamy, S.P.

    1988-04-01

    This report is the second volume of the Recovery Efficiency Test Phase I Report of Activities. Volume 1 covered selection, well planning, drilling, coring, logging and completion operations. This volume reports on well testing activities, reclamation activities on the drilling site and access roads, and the results of physical and mechanical properties tests on the oriented core material obtained from a horizontal section of the well. 3 refs., 21 figs., 10 tabs.

  11. A review of software project testing

    Directory of Open Access Journals (Sweden)

    Jose Calvo-Manzano Villalón

    2016-03-01

    Full Text Available In this article a review of software projects based on a taxonomy project is established, allowing the development team or testing personnel to identify the tests to which the project must be subjected for validation. The taxonomy is focused on identifying software projects according to their technology. To establish the taxonomy, a development method comprised of 5 phases was applied. The developed taxonomy is comprised of 10 categories and 35 subcategories and was validated by a group of information technology (IT managers and professionals in the field of IT through the use of a survey. The results obtained from the survey are subjected to the Mann-Whitney U test, which indicates that the taxonomy is validated. The taxonomy can be implemented in development organizations with or without a testing team that provides a classification for technology projects.

  12. The Healy Clean Coal Project: Design verification tests

    International Nuclear Information System (INIS)

    Guidetti, R.H.; Sheppard, D.B.; Ubhayakar, S.K.; Weede, J.J.; McCrohan, D.V.; Rosendahl, S.M.

    1993-01-01

    As part of the Healy Clean Coal Project, TRW Inc., the supplier of the advanced slagging coal combustors, has successfully completed design verification tests on the major components of the combustion system at its Southern California test facility. These tests, which included the firing of a full-scale precombustor with a new non-storage direct coal feed system, supported the design of the Healy combustion system and its auxiliaries performed under Phase 1 of the project. Two 350 million BTU/hr combustion systems have been designed and are now ready for fabrication and erection, as part of Phase 2 of the project. These systems, along with a back-end Spray Dryer Absorber system, designed and supplied by Joy Technologies, will be integrated with a Foster Wheeler boiler for the 50 MWe power plant at Healy, Alaska. This paper describes the design verification tests and the current status of the project

  13. OECD/NEA Aagesta decontamination project. Phase 1, final report

    International Nuclear Information System (INIS)

    1982-12-01

    The objective of the project is to utilize the four primary loops of the Aagesta reactor to demonstrate decontamination methods for PWR primary systems. The first phase of the project consisted of laboratory scale tests. The methods tested were developed at a) Studsvik Energiteknik AB, Sweden (a soft chemistry). b) Kraftwerk Union AG, Federal Republic of Germany, (two chemistries, one soft and one hard). c) Swiss Federal Institute of Reactor Research (two chemistries, one soft and one hard). d) Berkeley Nuclear Laboratories, United Kingdom, (a soft chemistry). The test programme consisted of decontamination tests on steam generator tubing and other active material from Aagesta and a number of operating reactors as well as material compatibility tests on standardized samples of a representative selection of modern PWR primary system materials. Six countries have participated in Phase I of the project - the four countries named above as well as the United States of America and Italy. Studsvik Energiteknik AB was appointed Project leader. The results show that all six processes in general met the acceptance criteria both regarding decontamination and corrosion. The decontamination results with the hard chemistries were rather uneven. (Author)

  14. Dependency Analysis Guidance. Nordic/German Working Group on Common cause Failure analysis. Phase 1 project report: Comparisons and application to test cases

    Energy Technology Data Exchange (ETDEWEB)

    Becker, Guenter (RISA Sicherheitsanalysen GmbH (DE)); Jaenkaelae, Kalle (Fortum Nuclear Services Oy (FI)); Johanson, Gunnar; Lindberg, Sandra (ES Konsult, Stockholm (SE)); Knochenhauer, Michael (Relcon Scandpower AB, Stockholm (SE)); Schubert, Bernd (Vattenfall Europe (DE)); Vaurio, Jussi (Prometh Solutions (FI)); Wohlstein, Ralf (E.ON Kernkraft, Maschinentechnik (DE))

    2007-10-15

    This report is part of the reporting from the European Working Group on CCF analysis (EWG), including members from Finland, Germany and Sweden. The project is planned in two phases with a reporting and progress evaluation before initiation of the second phase. Phase 1: Comparisons and application to test cases (2006). Phase 2: Development of harmonized approach and applications (2007). This report summarizes the work during the 1st phase of the project, which included the following main tasks: Task 1: Survey of databases, Task 2: Survey of methods for classification and quantification of CCF-events and description of these methods. Task 3: Classify events for application, using different approaches as recommended above. Task 4: Draw conclusions for harmonization

  15. Dependency Analysis Guidance. Nordic/German Working Group on Common cause Failure analysis. Phase 1 project report: Comparisons and application to test cases

    International Nuclear Information System (INIS)

    Becker, Guenter; Jaenkaelae, Kalle; Johanson, Gunnar; Lindberg, Sandra; Knochenhauer, Michael; Sc hubert, Bernd; Vaurio, Jussi; Wohlstei n, Ralf

    2007-10-01

    This report is part of the reporting from the European Working Group on CCF analysis (EWG), including members from Finland, Germany and Sweden. The project is planned in two phases with a reporting and progress evaluation before initiation of the second phase. Phase 1: Comparisons and application to test cases (2006). Phase 2: Development of harmonized approach and applications (2007). This report summarizes the work during the 1st phase of the project, which included the following main tasks: Task 1: Survey of databases, Task 2: Survey of methods for classification and quantification of CCF-events and description of these methods. Task 3: Classify events for application, using different approaches as recommended above. Task 4: Draw conclusions for harmonization

  16. IPRT polarized radiative transfer model intercomparison project - Three-dimensional test cases (phase B)

    Science.gov (United States)

    Emde, Claudia; Barlakas, Vasileios; Cornet, Céline; Evans, Frank; Wang, Zhen; Labonotte, Laurent C.; Macke, Andreas; Mayer, Bernhard; Wendisch, Manfred

    2018-04-01

    Initially unpolarized solar radiation becomes polarized by scattering in the Earth's atmosphere. In particular molecular scattering (Rayleigh scattering) polarizes electromagnetic radiation, but also scattering of radiation at aerosols, cloud droplets (Mie scattering) and ice crystals polarizes. Each atmospheric constituent produces a characteristic polarization signal, thus spectro-polarimetric measurements are frequently employed for remote sensing of aerosol and cloud properties. Retrieval algorithms require efficient radiative transfer models. Usually, these apply the plane-parallel approximation (PPA), assuming that the atmosphere consists of horizontally homogeneous layers. This allows to solve the vector radiative transfer equation (VRTE) efficiently. For remote sensing applications, the radiance is considered constant over the instantaneous field-of-view of the instrument and each sensor element is treated independently in plane-parallel approximation, neglecting horizontal radiation transport between adjacent pixels (Independent Pixel Approximation, IPA). In order to estimate the errors due to the IPA approximation, three-dimensional (3D) vector radiative transfer models are required. So far, only a few such models exist. Therefore, the International Polarized Radiative Transfer (IPRT) working group of the International Radiation Commission (IRC) has initiated a model intercomparison project in order to provide benchmark results for polarized radiative transfer. The group has already performed an intercomparison for one-dimensional (1D) multi-layer test cases [phase A, 1]. This paper presents the continuation of the intercomparison project (phase B) for 2D and 3D test cases: a step cloud, a cubic cloud, and a more realistic scenario including a 3D cloud field generated by a Large Eddy Simulation (LES) model and typical background aerosols. The commonly established benchmark results for 3D polarized radiative transfer are available at the IPRT website (http

  17. Environmental Assessment of the Hawaii Geothermal Project Well Flow Test Program

    Energy Technology Data Exchange (ETDEWEB)

    None

    1976-11-01

    The Hawaii Geothermal Project, a coordinated research effort of the University of Hawaii, funded by the County and State of Hawaii, and ERDA, was initiated in 1973 in an effort to identify, generate, and use geothermal energy on the Big Island of Hawaii. A number of stages are involved in developing geothermal power resources: exploration, test drilling, production testing, field development, power plant and powerline construction, and full-scale production. Phase I of the Project, which began in the summer of 1973, involved conducting exploratory surveys, developing analytical models for interpretation of geophysical results, conducting studies on energy recovery from hot brine, and examining the legal and economic implications of developing geothermal resources in the state. Phase II of the Project, initiated in the summer of 1975, centers on drilling an exploratory research well on the Island of Hawaii, but also continues operational support for the geophysical, engineering, and socioeconomic activities delineated above. The project to date is between the test drilling and production testing phase. The purpose of this assessment is to describe the activities and potential impacts associated with extensive well flow testing to be completed during Phase II.

  18. USL/DBMS NASA/PC R and D project system testing standards

    Science.gov (United States)

    Dominick, Wayne D. (Editor); Kavi, Srinu; Moreau, Dennis R.; Yan, Lin

    1984-01-01

    A set of system testing standards to be used in the development of all C software within the NASA/PC Research and Development Project is established. Testing will be considered in two phases: the program testing phase and the system testing phase. The objective of these standards is to provide guidelines for the planning and conduct of program and software system testing.

  19. Gallium-cladding compatibility testing plan. Phases 1 and 2: Test plan for gallium corrosion tests. Revision 2

    International Nuclear Information System (INIS)

    Wilson, D.F.; Morris, R.N.

    1998-05-01

    This test plan is a Level-2 document as defined in the Fissile Materials Disposition Program Light-Water-Reactor Mixed-Oxide Fuel Irradiation Test Project Plan. The plan summarizes and updates the projected Phases 1 and 2 Gallium-Cladding compatibility corrosion testing and the following post-test examination. This work will characterize the reactions and changes, if any, in mechanical properties that occur between Zircaloy clad and gallium or gallium oxide in the temperature range 30--700 C

  20. Yeager Airport Hydrogen Vehicle Test Project

    Energy Technology Data Exchange (ETDEWEB)

    Davis, Williams [West Virginia University Research Corporation, Morgantown, WV (United States)

    2015-10-01

    The scope of this project was changed during the course of the project. Phase I of the project was designed to have the National Alternative Fuels Training Consortium (NAFTC), together with its partners, manage the Hydrogen Vehicle Test Project at the Yeager Airport in conjunction with the Central West Virginia Regional Airport Authority (CWVRAA) in coordination with the United States Department of Energy National Energy Technology Laboratory (U.S. DOE NETL). This program would allow testing and evaluation of the use of hydrogen vehicles in the state of West Virginia utilizing the hydrogen fueling station at Yeager Airport. The NAFTC and CWVRAA to raise awareness and foster a greater understanding of hydrogen fuel and hydrogen-powered vehicles through a targeted utilization and outreach and education effort. After initial implementation of the project, the project added, determine the source(s) of supply for hydrogen powered vehicles that could be used for the testing. After completion of this, testing was begun at Yeager Airport. During the course of the project, the station at Yeager Airport was closed and moved to Morgantown and the West Virginia University Research Corporation. The vehicles were then moved to Morgantown and a vehicle owned by the CWVRAA was purchased to complete the project at the new location. Because of a number of issues detailed in the report for DE-FE0002994 and in this report, this project did not get to evaluate the effectiveness of the vehicles as planned.

  1. Military Family Coping Project - Phase II

    Science.gov (United States)

    2015-05-01

    Anxiety, Life Satisfaction , Addiction, Trauma 4 The Military Family Coping Project reflects two phases. The first consisted of a series of focus...need for and guided the work of the Military Family Coping Project Phase II funded by TATRC. The Military Family Coping Project Phase II was...solidarity. For the purposes of family functioning analyses, married and unmarried soldiers were analyzed separately because marital status affects

  2. High precision capacitive beam phase probe for KHIMA project

    Energy Technology Data Exchange (ETDEWEB)

    Hwang, Ji-Gwang, E-mail: windy206@hanmail.net [Korea Institute of Radiological and Medical Sciences, 215–4, Gongneung-dong, Nowon-t, Seoul 139–706 (Korea, Republic of); Yang, Tae-Keun [Korea Institute of Radiological and Medical Sciences, 215–4, Gongneung-dong, Nowon-t, Seoul 139–706 (Korea, Republic of); Forck, Peter [GSI Helmholtz Centre for Ion Research, Darmstadt 64291, German (Germany)

    2016-11-21

    In the medium energy beam transport (MEBT) line of KHIMA project, a high precision beam phase probe monitor is required for a precise tuning of RF phase and amplitude of Radio Frequency Quadrupole (RFQ) accelerator and IH-DTL linac. It is also used for measuring a kinetic energy of ion beam by time-of-flight (TOF) method using two phase probes. The capacitive beam phase probe has been developed. The electromagnetic design of the high precision phase probe was performed to satisfy the phase resolution of 1° (@200 MHz). It was confirmed by the test result using a wire test bench. The measured phase accuracy of the fabricated phase probe is 1.19 ps. The pre-amplifier electronics with the 0.125 ∼ 1.61 GHz broad-band was designed and fabricated for amplifying the signal strength. The results of RF frequency and beam energy measurement using a proton beam from the cyclotron in KIRAMS is presented.

  3. Mismanagement Reasons of the Projects Execution Phase

    Directory of Open Access Journals (Sweden)

    Hatem Khaleefah Al-Agele

    2017-10-01

    Full Text Available The execution phase of the project is most dangerous and the most drain on the resources during project life cycle, therefore, its need to monitor and control by specialists to exceeded obstructions and achieve the project goals. The study aims to detect the actual reasons behind mismanagement of the execution phase. The study begins with theoretical part, where it deals with the concepts of project, project selection, project management, and project processes. Field part consists of three techniques: 1- brainstorming, 2- open interviews with experts and 3- designed questionnaire (with 49 reason. These reasons result from brainstorming and interviewing with experts., in order to find the real reasons behind mismanagement of the execution phase. The most important reasons which are negatively impact on management of the execution phase that proven by the study were (Inability of company to meet project requirements because it's specialized and / or large project, Multiple sources of decision and overlap in powers, Inadequate planning, Inaccurate estimation of cost, Delayed cash flows by owners, Poor performance of project manager, inefficient decision making process, and the Negative impact of people in the project area. Finally, submitting a set of recommendations which will contribute to overcome the obstructions of successful management of the execution phase.

  4. Phase 1 of the Hanford Environmental Dose Reconstruction Project

    International Nuclear Information System (INIS)

    1991-08-01

    The work described in this report was prompted by the public's concern about potential effect from the radioactive materials released from the Hanford Site. The Hanford Environmental Dose Reconstruction (HEDR) Project was established to estimate radiation dose the public might have received from the Hanford Site since 1944, when facilities began operating. Phase 1 of the HEDR Project is a ''pilot'' or ''demonstration'' phase. The objectives of this initial phase were to determine whether enough historical information could be found or reconstructed to be used for dose estimation and develop and test conceptual and computational models for calculating credible dose estimates. Preliminary estimates of radiation doses were produced in Phase 1 because they are needed to achieve these objectives. The reader is cautioned that the dose estimates provided in this and other Phase 1 HEDR reports are preliminary. As the HEDR Project continues, the dose estimates will change for at least three reasons: more complete input information for models will be developed; the models themselves will be refined; and the size and shape of the geographic study area will change. This is one of three draft reports that summarize the first phase of the four-phased HEDR Project. This, the Summary Report, is directed to readers who want a general understanding of the Phase 1 work and preliminary dose estimates. The two other reports -- the Air Pathway Report and the Columbia River Pathway Report -- are for readers who understand the radiation dose assessment process and want to see more technical detail. Detailed descriptions of the dose reconstruction process are available in more than 20 supporting reports listed in Appendix A. 32 refs., 46 figs

  5. Individualized In-Service Teacher Education. (Project IN-STEP). Evaluation Report, Phase II.

    Science.gov (United States)

    Thurber, John C.

    Phase 2 of Project IN-STEP was conducted to revise, refine, and conduct further field testing of a new inservice teacher education model. The method developed (in Phase 1--see ED 003 905 for report) is an individualized, multi-media approach. Revision activities, based on feedback provided for Phase 1, include the remaking of six videotape…

  6. Test Plan: Phase 1, Hanford LLW melter tests, GTS Duratek, Inc

    International Nuclear Information System (INIS)

    Eaton, W.C.

    1995-01-01

    This document provides a test plan for the conduct of vitrification testing by a vendor in support of the Hanford Tank Waste Remediation System (TWRS) Low-Level Waste (LLW) Vitrification Program. The vendor providing this test plan and conducting the work detailed within it [one of seven selected for glass melter testing under Purchase Order MMI-SVV-384215] is GTS Duratek, Inc., Columbia, Maryland. The GTS Duratek project manager for this work is J. Ruller. This test plan is for Phase I activities described in the above Purchase Order. Test conduct includes melting of glass with Hanford LLW Double-Shell Slurry Feed waste simulant in a DuraMelter trademark vitrification system

  7. Gas reactor in-pile safety test project (GRIST-2)

    International Nuclear Information System (INIS)

    Kelley, A.P. Jr.; Arbtin, E.; St Pierre, R.

    1979-01-01

    Although out-of-pile tests may be expected to confirm individual phenomena models in core disruptive accident analysis codes, only in-pile tests are capable of verifying the extremely complex integrated model effects within the appropriate time phase for these accidents. For this reason, the GRIST-2 project, the purpose of which is to design and construct an in-pile helium loop capable of transient safety testing in the TREAT facility in Idaho, forms a cornerstone of the US GCFR safety program. The project organization, experiment program, facility, helium system design, and schedule which have been selected to meet the objectives are described

  8. FY 1991 project plan for the Hanford Environmental Dose Reconstruction Project, Phase 2

    International Nuclear Information System (INIS)

    1991-02-01

    Phase 1 of the Hanford Environmental Dose Reconstruction Project was designed to develop and demonstrate a method for estimating radiation doses people may have received from Hanford Site operations since 1944. The method researchers developed relied on a variety of measured and reconstructed data as input to a modular computer model that generates dose estimates and their uncertainties. As part of Phase 1, researchers used the reconstructed data and computer model to calculate preliminary dose estimates for populations in a limited geographical area and time period. Phase 2, now under way, is designed to evaluate the Phase 1 data and model and improve them to calculate more accurate and precise dose estimates. Phase 2 will also be used to obtain preliminary estimates of two categories of doses: for Native American tribes and for individuals included in the pilot phase of the Hanford Thyroid Disease Study (HTDS). TSP Directive 90-1 required HEDR staff to develop Phase 2 task plans for TSP approval. Draft task plans for Phase 2 were submitted to the TSP at the October 11--12, 1990 public meeting, and, after discussions of each activity and associated budget needs, the TSP directed HEDR staff to proceed with a slate of specific project activities for FY 1991 of Phase 2. This project plan contains detailed information about those activities. Phase 2 is expected to last 15--18 months. In mid-FY 1991, project activities and budget will be reevaluated to determine whether technical needs or priorities have changed. Separate from, but related to, this project plan, will be an integrated plan for the remainder of the project. HEDR staff will work with the TSP to map out a strategy that clearly describes ''end products'' for the project and the work necessary to complete them. This level of planning will provide a framework within which project decisions in Phases 2, 3, and 4 can be made

  9. Liquid sodium testing of in-house phased array EMAT transducer for L-wave applications

    Energy Technology Data Exchange (ETDEWEB)

    Le Bourdais, F.; Le Polles, T. [Non Destructive Testing Department at the French Atomic Energy Commission (CEA), Saclay, 91191 Gif sur Yvette CEDEX, (France); Baque, F. [Department of Sodium Technology at the French Atomic Energy Commission (CEA), Cadarache, 13108 St Paul lez Durance CEDEX, (France)

    2015-07-01

    This paper describes the development of an in-house phased array EMAT transducer for longitudinal wave inspection in liquid sodium. The work presented herein is part of an undergoing project aimed at improving in-service inspection techniques for the ASTRID reactor project. The design process of the phased array EMAT probe is briefly explained and followed by a review of experimental test results. We first present test results obtained in the laboratory while the last part of the paper describes the liquid sodium testing and the produced ultrasound images. (authors)

  10. Liquid sodium testing of in-house phased array EMAT transducer for L-wave applications

    International Nuclear Information System (INIS)

    Le Bourdais, F.; Le Polles, T.; Baque, F.

    2015-01-01

    This paper describes the development of an in-house phased array EMAT transducer for longitudinal wave inspection in liquid sodium. The work presented herein is part of an undergoing project aimed at improving in-service inspection techniques for the ASTRID reactor project. The design process of the phased array EMAT probe is briefly explained and followed by a review of experimental test results. We first present test results obtained in the laboratory while the last part of the paper describes the liquid sodium testing and the produced ultrasound images. (authors)

  11. Project Half Double: Current Results of Phase 1 and Phase 2, December 2017

    DEFF Research Database (Denmark)

    Svejvig, Per; Thorp Adland, Karoline; Zippora Klein, Judith Birte

    ’s competitiveness and play an important role in the battle for jobs and future welfare. The overall goal is to deliver “Projects in half the time with double the impact” where projects in half the time should be understood as half the time to impact (benefit realization, effect is achieved) and not as half the time...... of Project Half Double was initiated in June 2015. It is a two-phase project: phase 1 took place from June 2015 to June 2016 with seven pilot projects, and phase 2 is in progress from July 2016 to July 2018 with 10 pilot projects. The Half Double consortium: Implement Consulting Group is the project leader....... 2016, Svejvig et al. 2017). This report’s target group inludes practitioners in Danish industry and society in general. The editorial team from Aarhus University prepared the report from October 2017 to December 2017, which means that data about pilot projects from December 2017 is not included....

  12. A phased approach to cooperative environmental management R ampersand D projects with Russian institutes

    International Nuclear Information System (INIS)

    Matalucci, R.V.; Albert, T.E.

    1994-01-01

    An important aspect of technology exchange between the US and the Former Society Union (FSU) countries is the identification and implementation of cooperative projects that are mutually beneficial. The US Department of Energy (DOE) and its national laboratories have established a four-phase approach to identify and further develop Russian technologies that could contribute to solving DOE environmental management problems. Following an initial screening and identification of potential technologies, the country-to-country interaction is formally initiated in the first phase through a small-scale pilot project study. This phase consists of an evaluation of the specific technology for DOE applications, and provides an opportunity for both US and Russian scientists and engineers to validate the use of the technology for a specific DOE requirement. The successful completion of this phase establishes the basis for continuing the technology development into the second phase, which includes laboratory testing in Russia. In the third phase, the technology is laboratory tested in the US, most likely at those DOE national laboratories having the capability and greatest interest in the particular technology area. The fourth and final phase consist of a commercialization process that establishes a partnership with a US business to finalize development of the technology and to prepare for implementation within the DOE complex. An example of this phased approach is a current high-level waste separation cooperative project between the Khlopin Radium Institute and the DOE through Sandia National Laboratories (SNL) and Science Applications International Corporation (SAIC). This effort has not only enhanced separations technology for the DOE, but has also provided an example of a working process for future cooperative projects

  13. HFC-134A and HCFC-22 supermarket refrigeration demonstration and laboratory testing. Phase I. Final report

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-04-01

    Aspen Systems and a team of nineteen agencies and industry participants conducted a series of tests to determine the performance of HFC-134a, HCFC-22, and CFC-502 for supermarket application. This effort constitutes the first phase of a larger project aimed at carrying out both laboratory and demonstration tests of the most viable HFC refrigerants and the refrigerants they replace. The results of the Phase I effort are presented in the present report. The second phase of the project has also been completed. It centered on testing all viable HFC replacement refrigerants for CFC-502. These were HFC-507, HFC-404A, and HFC-407A. The latter results are published in the Phase II report for this project. As part of Phase I, a refrigeration rack utilizing a horizontal open drive screw compressor was constructed in our laboratory. This refrigeration rack is a duplicate of one we have installed in a supermarket in Clifton Park, NY.

  14. Yakima Basin Fish Passage Project, Phase 2

    International Nuclear Information System (INIS)

    1991-08-01

    Implementation of the Yakima Basin Fish Passage Project -- Phase 2 would significantly improve the production of anadromous fish in the Yakima River system. The project would provide offsite mitigation and help to compensate for lower Columbia River hydroelectric fishery losses. The Phase 2 screens would allow greater numbers of juvenile anadromous fish to survive. As a consequence, there would be higher returns of adult salmon and steelhead to the Yakima River. The proposed action would play an integral part in the overall Yakima River anadromous fish enhancement program (fish passage improvement, habitat enhancement, hatchery production increases, and harvest management). These would be environmental benefits associated with implementation of the Fish Passage and Protective Facilities Phase 2 Project. Based on the evaluation presented in this assessment, there would be no significant adverse environmental impacts if the proposed action was carried forward. No significant adverse environmental effects have been identified from construction and operation of the Yakima Phase 2 fish passage project. Proper design and implementation of the project will ensure no adverse effects will occur. Based on the information in this environmental analysis, BPA's and Reclamation's proposal to construct these facilities does not constitute a major Federal action that could significantly affect the quality of the human environment. 8 refs., 4 figs., 6 tabs

  15. NASA SBIR abstracts of 1990 phase 1 projects

    Science.gov (United States)

    Schwenk, F. C.; Gilman, J. A.; Paige, J. B.

    1991-01-01

    The research objectives of the 280 projects placed under contract in the National Aeronautics and Space Administration (NASA) 1990 Small Business Innovation Research (SBIR) Phase 1 program are described. The basic document consists of edited, non-proprietary abstracts of the winning proposals submitted by small businesses in response to NASA's 1990 SBIR Phase 1 Program Solicitation. The abstracts are presented under the 15 technical topics within which Phase 1 proposals were solicited. Each project was assigned a sequential identifying number from 001 to 280, in order of its appearance in the body of the report. The document also includes Appendixes to provide additional information about the SBIR program and permit cross-reference in the 1990 Phase 1 projects by company name, location by state, principal investigator, NASA field center responsible for management of each project, and NASA contract number.

  16. Draft plan for the Waste Isolation Pilot Plant test phase: Performance assessment and operations demonstration

    International Nuclear Information System (INIS)

    1989-04-01

    The mission of the Waste Isolation Pilot Plant (WIPP) Project is to provide a research and development facility to demonstrate the safe disposal of transuranic (TRU) radioactive wastes resulting from United States defense programs. With the Construction Phase of the WIPP facility nearing completion, WIPP is ready to initiate the next phase in its development, the Test Phase. The purpose of the Test Phase is to collect the necessary scientific and operational data to support a determination whether to proceed to the Disposal Phase and thereby designate WIPP a demonstration facility for the disposal of TRU wastes. This decision to proceed to the Disposal Phase is scheduled for consideration by September 1994. Development of the WIPP facility is the responsibility of the United States Department of Energy (DOE), whose Albuquerque Operations Office has designated the WIPP Project Office as Project Manager. This document describes the two major programs to be conducted during the Test Phase of WIPP: (1) Performance Assessment for determination of compliance with the Environmental Protection Agency Standard and (2) Operations Demonstration for evaluation of the safety and effectiveness of the DOE TRU waste management system's ability to emplace design throughput quantities of TRU waste in the WIPP facility. 42 refs., 38 figs., 14 tabs

  17. Savanna ecosystem project: phase I summary and phase II progress

    CSIR Research Space (South Africa)

    Huntely, BJ

    1978-07-01

    Full Text Available A summary of the results of the first phase (mid 1974 to mid 1976) of the South African Savanna Ecosystem Project being undertaken at Nylsvley in the northern Transvaal is presented. Phase I of this ten year study of the structure and functioning...

  18. Tank waste remediation system privatization Phase 1 infrastructure, project W-519, project execution plan

    International Nuclear Information System (INIS)

    Parazin, R.J.

    1998-01-01

    This Project Execution Plan (PEP) defines the overall strategy, objectives, and contractor management requirements for the execution phase of Project W-519 (98-D403), Privatization Phase 1 Infrastructure Support, whose mission is to effect the required Hanford site infrastructure physical changes to accommodate the Privatization Contractor facilities. This plan provides the project scope, project objectives and method of performing the work scope and achieving objectives. The plan establishes the work definitions, the cost goals, schedule constraints and roles and responsibilities for project execution. The plan also defines how the project will be controlled and documented

  19. Recovery efficiency test project, Phase 2 activity report

    Energy Technology Data Exchange (ETDEWEB)

    Overbey, W.K. Jr.; Salamy, S.P.; Locke, C.D.

    1989-02-01

    The Recovery Efficiency Test well project addressed a number of technical issues. The primary objective was to determine the increased efficiency of gas recovery of a long horizontal wellbore over that of a vertical wellbore and, more specifically, what improvements can be expected from inducing multiple hydraulic fractures from such a wellbore. This volume contains appendices for: (1) supporting material and procedures for data frac'' stimulation of zone 6 using nitrogen and nitrogen foam; (2) supporting material and procedures for stimulation no. 1 nitrogen gas frac on zone no. 1; (3) supporting material and procedures for stimulation no. 2 in zone no. 1 using liquid CO{sub 2}; (4) supporting material and procedures for frac no. 3 on zone no.1 using nitrogen foam and proppant; (5) supporting material and procedures for stimulation no. 4 in zones 2--3 and 4 using nitrogen foam and proppant; (6) supporting materials and procedures for stimulation no. 5 in zones 5 and 8; and (7) fracture diagnostics reports and supporting materials.

  20. Gearbox Reliability Collaborative Phase 3 Gearbox 3 Test Plan

    Energy Technology Data Exchange (ETDEWEB)

    Keller, Jonathan [National Renewable Energy Lab. (NREL), Golden, CO (United States); Wallen, Robb [National Renewable Energy Lab. (NREL), Golden, CO (United States)

    2016-10-01

    This document describes the Phase 3 test plan for the Gearbox Reliability Collaborative Gearbox #3. The primary test objective is to measure the planetary load sharing characteristics in the same conditions as the original gearbox design. If the measured load-sharing characteristics are close to the design model, the projected three-times improvement in planetary section predicted fatigue life and the efficacy of preloaded tapered roller bearings in mitigating the planetary bearing fatigue failure mode will have been demonstrated.

  1. Image/patient registration from (partial) projection data by the Fourier phase matching method

    International Nuclear Information System (INIS)

    Weiguo Lu; You, J.

    1999-01-01

    A technique for 2D or 3D image/patient registration, PFPM (projection based Fourier phase matching method), is proposed. This technique provides image/patient registration directly from sequential tomographic projection data. The method can also deal with image files by generating 2D Radon transforms slice by slice. The registration in projection space is done by calculating a Fourier invariant (FI) descriptor for each one-dimensional projection datum, and then registering the FI descriptor by the Fourier phase matching (FPM) method. The algorithm has been tested on both synthetic and experimental data. When dealing with translated, rotated and uniformly scaled 2D image registration, the performance of the PFPM method is comparable to that of the IFPM (image based Fourier phase matching) method in robustness, efficiency, insensitivity to the offset between images, and registration time. The advantages of the former are that subpixel resolution is feasible, and it is more insensitive to image noise due to the averaging effect of the projection acquisition. Furthermore, the PFPM method offers the ability to generalize to 3D image/patient registration and to register partial projection data. By applying patient registration directly from tomographic projection data, image reconstruction is not needed in the therapy set-up verification, thus reducing computational time and artefacts. In addition, real time registration is feasible. Registration from partial projection data meets the geometry and dose requirements in many application cases and makes dynamic set-up verification possible in tomotherapy. (author)

  2. Reedsport PB150 Deployment and Ocean Test Project

    Energy Technology Data Exchange (ETDEWEB)

    Hart, Phil [Ocean Power Technologies Inc., Pennington, NJ (United States)

    2016-06-03

    As the first utility scale wave power project in the US, the Wave Power Demonstration Project at Reedsport (OR) was planned to consist of 10 PowerBuoys (Phase II)1, located 2.5 miles off the coast. U.S. Department of Energy (DOE) funding under a prior DOE Grant (DE-FG36-08GO88017) along with funding from PNGC Power, an Oregon-based electric power cooperative, was utilized for the design completion, fabrication, assembly and factory testing of the first PowerBuoy for the Reedsport project. The design and fabrication of the first PowerBuoy and factory testing of the power take-off subsystem were completed, and the power take-off subsystem was successfully integrated into the spar at the fabricator’s facility in Oregon. The objectives of this follow-on grant were: advance PB150B design from TRL 5/6 to TRL 7/8; deploy a single PB150 and operate autonomously for 2 years; establish O&M costs; collect environmental information; and establish manufacturing methodologies.

  3. Gallium-cladding compatibility testing plan: Phase 3: Test plan for centrally heated surrogate rodlet test. Revision 2

    International Nuclear Information System (INIS)

    Morris, R.N.; Baldwin, C.A.; Wilson, D.F.

    1998-07-01

    The Fissile Materials Disposition Program (FMDP) is investigating the use of weapons grade plutonium in mixed oxide (MOX) fuel for light-water reactors (LWR). Commercial MOX fuel has been successfully used in overseas reactors for many years; however, weapons derived fuel may differ from the previous commercial fuels because of small amounts of gallium impurities. A concern presently exists that the gallium may migrate out of the fuel, react with and weaken the clad, and thereby promote loss of fuel pin integrity. Phases 1 and 2 of the gallium task are presently underway to investigate the types of reactions that occur between gallium and clad materials. This is a Level-2 document as defined in the Fissile Materials Disposition Program Light-Water Reactor Mixed-Oxide Fuel Irradiation Test Project Plan. This Plan summarizes the projected Phase 3 Gallium-Cladding compatibility heating test and the follow-on post test examination (PTE). This work will be performed using centrally-heated surrogate pellets, to avoid unnecessary complexities and costs associated with working with plutonium and an irradiation environment. Two sets of rodlets containing pellets prepared by two different methods will be heated. Both sets will have an initial bulk gallium content of approximately 10 ppm. The major emphasis of the PTE task will be to examine the material interactions, particularly indications of gallium transport from the pellets to the clad

  4. The Lunar Phases Project: A Mental Model-Based Observational Project for Undergraduate Nonscience Majors

    Science.gov (United States)

    Meyer, Angela Osterman; Mon, Manuel J.; Hibbard, Susan T.

    2011-01-01

    We present our Lunar Phases Project, an ongoing effort utilizing students' actual observations within a mental model building framework to improve student understanding of the causes and process of the lunar phases. We implement this project with a sample of undergraduate, nonscience major students enrolled in a midsized public university located…

  5. Final report on the surface-based investigation phase (phase 1) at the Mizunami Underground Research Laboratory project

    International Nuclear Information System (INIS)

    Saegusa, Hiromitsu; Matsuoka, Toshiyuki

    2011-03-01

    The Mizunami Underground Research Laboratory (MIU) Project is a comprehensive research project investigating the deep underground environment within crystalline rock being conducted by Japan Atomic Energy Agency at Mizunami City in Gifu Prefecture, central Japan and its role is defined in 'Framework for Nuclear Energy Policy' by Japan Atomic Energy Commission. The MIU Project has three overlapping phases: Surface-based Investigation phase (Phase I), Construction phase (Phase II), and Operation phase (Phase III), with a total duration of 20 years. The overall project goals of the MIU Project from Phase I through to Phase III are: 1) to establish techniques for investigation, analysis and assessment of the deep geological environment, and 2) to develop a range of engineering for deep underground application. During Phase I, the overall project goals were supported by Phase I goals. For the overall project goals 1), the Phase I goals were set to construct models of the geological environment from all surface-based investigation results that describe the geological environment prior to excavation and predict excavation response. For the overall project goals 2), the Phase I goals were set to formulate detailed design concepts and a construction plan for the underground facilities. This report summarizes the Phase I investigation which was completed in March 2005. The authors believe this report will make an important milestone, since this report clarifies how the Phase I goals are achieved and evaluate the future issues thereby direct the research which will be conducted during Phase II. With regard to the overall project goals 1), 'To establish techniques for investigation, analysis and assessment of the deep geological environment,' a step-wise investigation was conducted by iterating investigation, interpretation, and assessment, thereby understanding of geologic environment was progressively and effectively improved with progress of investigation. An optimal

  6. Phase 2 Reese River Geothermal Project Slim Well 56-4 Drilling and Testing

    Energy Technology Data Exchange (ETDEWEB)

    Henkle, William R.; Ronne, Joel

    2008-06-15

    This report covers the drilling and testing of the slim well 56-4 at the Reese River Geothermal Project in Lander County, Nevada. This well was partially funded through a GRED III Cooperative Funding Agreement # DE-FC36-04GO14344, from USDOE.

  7. Laser projection using generalized phase contrast

    DEFF Research Database (Denmark)

    Glückstad, Jesper; Palima, Darwin; Rodrigo, Peter John

    2007-01-01

    is introduced. An arbitrary phase shift filter eliminates the need for high-frequency modulation and conjugate phase encoding. This lowers device performance requirements and allows practical implementation with currently available dynamic spatial light modulators. (c) 2007 Optical Society of America.......We demonstrate experimental laser projection of a gray-level photographic image with 74% light efficiency using the generalized phase contrast (GPC) method. In contrast with a previously proposed technique [Alonzo et al., New J. Phys. 9, 132 (2007)], a new approach to image construction via GPC...

  8. Implementing Effective Mission Systems Engineering Practices During Early Project Formulation Phases

    Science.gov (United States)

    Moton, Tryshanda

    2016-01-01

    Developing and implementing a plan for a NASA space mission can be a complicated process. The needs, goals, and objectives of any proposed mission or technology must be assessed early in the Project Life Cycle. The key to successful development of a space mission or flight project is the inclusion of systems engineering in early project formulation, namely during Pre-phase A, Phase A, and Phase B of the NASA Project Life Cycle. When a space mission or new technology is in pre-development, or "pre-Formulation", feasibility must be determined based on cost, schedule, and risk. Inclusion of system engineering during project formulation is key because in addition to assessing feasibility, design concepts are developed and alternatives to design concepts are evaluated. Lack of systems engineering involvement early in the project formulation can result in increased risks later in the implementation and operations phases of the project. One proven method for effective systems engineering practice during the pre-Formulation Phase is the use of a mission conceptual design or technology development laboratory, such as the Mission Design Lab (MDL) at NASA's Goddard Space Flight Center (GSFC). This paper will review the engineering process practiced routinely in the MDL for successful mission or project development during the pre-Formulation Phase.

  9. {open_quotes}O{close_quotes} ring sealed process tube, Phase II, test project

    Energy Technology Data Exchange (ETDEWEB)

    Johnson, R.E.

    1951-04-09

    The {open_quotes}O{close_quotes} ring seal has been proposed to replace the van stone flange and the bellows thermal expansion assembly currently used on the existing Hanford piles to achieve water and gas seals, respectively. Possible advantages of the {open_quotes}O{close_quotes} ring seal are: (1) simplification of component parts and elimination of van stone corrosion; (2) simplification of maintenance; (3) lower costs of initial erection; (4) increased strength. This test supplements Test Project No. 27 (a preliminary thermal cycling test) in applying the {open_quotes}O{close_quotes} ring seal assembly to actual pile operating conditions.

  10. Environmental information volume: Liquid Phase Methanol (LPMEOH{trademark}) project

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-05-01

    The purpose of this project is to demonstrate the commercial viability of the Liquid Phase Methanol Process using coal-derived synthesis gas, a mixture of hydrogen and carbon monoxide. This report describes the proposed actions, alternative to the proposed action, the existing environment at the coal gasification plant at Kingsport, Tennessee, environmental impacts, regulatory requirements, offsite fuel testing, and DME addition to methanol production. Appendices include the air permit application, solid waste permits, water permit, existing air permits, agency correspondence, and Eastman and Air Products literature.

  11. Environmental information volume: Liquid Phase Methanol (LPMEOH trademark) project

    International Nuclear Information System (INIS)

    1996-05-01

    The purpose of this project is to demonstrate the commercial viability of the Liquid Phase Methanol Process using coal-derived synthesis gas, a mixture of hydrogen and carbon monoxide. This report describes the proposed actions, alternative to the proposed action, the existing environment at the coal gasification plant at Kingsport, Tennessee, environmental impacts, regulatory requirements, offsite fuel testing, and DME addition to methanol production. Appendices include the air permit application, solid waste permits, water permit, existing air permits, agency correspondence, and Eastman and Air Products literature

  12. NASA SBIR abstracts of 1991 phase 1 projects

    Science.gov (United States)

    Schwenk, F. Carl; Gilman, J. A.; Paige, J. B.

    1992-01-01

    The objectives of 301 projects placed under contract by the Small Business Innovation Research (SBIR) program of the National Aeronautics and Space Administration (NASA) are described. These projects were selected competitively from among proposals submitted to NASA in response to the 1991 SBIR Program Solicitation. The basic document consists of edited, non-proprietary abstracts of the winning proposals submitted by small businesses. The abstracts are presented under the 15 technical topics within which Phase 1 proposals were solicited. Each project was assigned a sequential identifying number from 001 to 301, in order of its appearance in the body of the report. Appendixes to provide additional information about the SBIR program and permit cross-reference of the 1991 Phase 1 projects by company name, location by state, principal investigator, NASA Field Center responsible for management of each project, and NASA contract number are included.

  13. NASA SBIR abstracts of 1992, phase 1 projects

    Science.gov (United States)

    Schwenk, F. C.; Gilman, J. A.; Paige, J. B.; Sacknoff, S. M.

    1993-01-01

    The objectives of 346 projects placed under contract by the Small Business Innovation Research (SBIR) program of the National Aeronautics and Space Administration (NASA) are described. These projects were selected competitively from among proposals submitted to NASA in response to the 1992 SBIR Program Solicitation. The basic document consists of edited, non-proprietary abstracts of the winning proposals submitted by small businesses. The abstracts are presented under the 15 technical topics within which Phase 1 proposals were solicited. Each project was assigned a sequential identifying number from 001 to 346, in order of its appearance in the body of the report. Appendixes to provide additional information about the SBIR program and permit cross-reference of the 1992 Phase 1 projects by company name, location by state, principal investigator, NASA Field Center responsible for management of each project, and NASA contract number are included.

  14. U.S. LCI Database Project--Final Phase I Report

    Energy Technology Data Exchange (ETDEWEB)

    2003-08-01

    This Phase I final report reviews the process and provides a plan for the execution of subsequent phases of the database project, including recommended data development priorities and a preliminary cost estimate. The ultimate goal of the project is to develop publicly available LCI Data modules for commonly used materials, products, and processes.

  15. Experimental Results of A1.1 Test for OECD-ATLAS Project

    Energy Technology Data Exchange (ETDEWEB)

    Kang, Kyoung-Ho; Bae, Byoung-Uhn; Park, Yu-Sun; Kim, Jong-Rok; Choi, Nam-Hyun; Choi, Ki-Yong [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2015-10-15

    KAERI (Korea Atomic Energy Research Institute) is operating an OECD/NEA project (hereafter, OECD-ATLAS project) by utilizing a thermal-hydraulic integral effect test facility, ATLAS (Advanced Thermal-hydraulic Test Loop for Accident Simulation). Considering the importance of the SBO scenario and the related accident mitigation measures, a prolonged SBO scenario was selected as the first test subject worthy of investigation in the OECD-ATLAS project as summarized in Table 1. After the Fukushima accident, design extension conditions (DECs) such as an SBO and a total loss of feed water (TLOFW) attracted wide international attention in that such high-risk multiple failure accidents should be revisited from the viewpoint of the reinforcement of the 'defense in depth' concept. In particular, an SBO is one of the most important DECs because a total loss of heat sink can lead to a core melt-down scenario under high pressure without any proper operator action. As for a prolonged SBO transient of the OECD-ATLAS project, two tests, named A1.1 and A1.2, were determined to be performed. In most nuclear power plants (NPPs), a turbine-driven auxiliary feedwater system was designed to remove the decay heat during the early period of an SBO transient. From a conservative point of view, however, it is necessary to investigate the thermal-hydraulic behaviors of the NPP when a turbine-driven auxiliary feedwater supply is not available during the initial period of an SBO transient and moreover a mobile pump-driven auxiliary feedwater supply can only become realized in the later period of the scenario. In particular, asymmetric heat removal characteristic through the supply of auxiliary feedwater only to one steam generator has its own peculiar importance in terms of safety analysis code validation. With an aim of considering these safety importance, in the A1.1 test, a prolonged SBO transient was simulated with two temporal phases: Phase (I) for a conservative SBO transient

  16. NNWSI Phase II materials interaction test procedure and preliminary results

    International Nuclear Information System (INIS)

    Bates, J.K.; Gerding, T.J.

    1985-01-01

    The Nevada Nuclear Waste Storage Investigations (NNWSI) project is investigating the volcanic tuff beds of Yucca Mountain, Nevada, as a potential location for a high-level radioactive waste repository. This report describes a test method (Phase II) that has been developed to measure the release of radionuclides from the waste package under simulated repository conditions, and provides information on materials interactions that may occur in the repository. The results of 13 weeks of testing using the method are presented, and an analog test is described that investigates the relationship between the test method and expected repository conditions. 9 references, 10 figures, 11 tables

  17. TA 55 Reinvestment Project II Phase C Update Project Status May 23, 2017

    Energy Technology Data Exchange (ETDEWEB)

    Giordano, Anthony P. [Los Alamos National Lab. (LANL), Los Alamos, NM (United States)

    2017-05-25

    The TA-55 Reinvestment Project (TRP) II Phase C is a critical infrastructure project focused on improving safety and reliability of the Los Alamos National Laboratory (LANL) TA-55 Complex. The Project recapitalizes and revitalizes aging and obsolete facility and safety systems providing a sustainable nuclear facility for National Security Missions.

  18. Rehabilitation and modernization project of units 1 and 2 of Laguna Verde Nuclear Power Plant. A strengthening project to 120%. (2nd phase)

    International Nuclear Information System (INIS)

    Liebana, B.; Merino, A.; Garcia, J. L.; Gomez, M.; Martinez, I.; Ruiz, L.

    2010-01-01

    The power increase of the Laguna Verde Nuclear Power Plant is a project for the rehabilitation and modernization of the turbo and associated equipment to get an increase of its power and of its service life. The project scope includes the design, the engineering, the equipment supply, the installation, the testing and the commissioning. This article presents the work of the second phase.

  19. Unmanned Aircraft Systems (UAS) Integration in the National Airspace System (NAS) Project, UAS Control and Non-Payload Communication System Phase-1 Flight Test Results

    Science.gov (United States)

    Griner, James H.

    2014-01-01

    NASA's UAS Integration in the NAS project, has partnered with Rockwell Collins to develop a concept Control and Non-Payload Communication (CNPC) system prototype radio, operating on recently allocated UAS frequency spectrum bands. This prototype radio is being used to validate initial proposed performance requirements for UAS control communications. This presentation will give an overview of the current status of the prototype radio development, and results from phase 1 flight tests conducted during 2013.

  20. Uncertainty in project phases: A framework for organisational change management

    DEFF Research Database (Denmark)

    Kreye, Melanie; Balangalibun, Sarah

    2015-01-01

    in the early stage of the change project but was delayed until later phases. Furthermore, the sources of uncertainty were found to be predominantly within the organisation that initiated the change project and connected to the project scope. Based on these findings, propositions for future research are defined......Uncertainty is an integral challenge when managing organisational change projects (OCPs). Current literature highlights the importance of uncertainty; however, falls short of giving insights into the nature of uncertainty and suggestions for managing it. Specifically, no insights exist on how...... uncertainty develops over the different phases of OCPs. This paper presents case-based evidence on different sources of uncertainty in OCPs and how these develop over the different project phases. The results showed some surprising findings as the majority of the uncertainty did not manifest itself...

  1. Sears Point Tidal Marsh Restoration Project: Phase I

    Science.gov (United States)

    Information about the SFBWQP Sears Point Tidal Marsh Restoration Project: Phase I project, part of an EPA competitive grant program to improve SF Bay water quality focused on restoring impaired waters and enhancing aquatic resources.

  2. The Convergence of Heat, Groundwater & Fracture Permeability. Innovative Play Fairway Modelling Applied to the Tularosa Basin Phase 1 Project Report

    Energy Technology Data Exchange (ETDEWEB)

    Bennett, Carlon R. [Ruby Mountain Inc., Salt Lake City, UT (United States); Nash, Gregory D. [Univ. of Utah, Salt Lake City, UT (United States). Energy & Geoscience Institute; Sorkhabi, Rasoul [Univ. of Utah, Salt Lake City, UT (United States). Energy & Geoscience Institute; Moore, Joseph [Univ. of Utah, Salt Lake City, UT (United States). Energy & Geoscience Institute; Simmons, Stuart [Univ. of Utah, Salt Lake City, UT (United States). Energy & Geoscience Institute; Brandt, Adam [Univ. of Utah, Salt Lake City, UT (United States). Energy & Geoscience Institute; Barker, Benjamin [Univ. of Utah, Salt Lake City, UT (United States). Energy & Geoscience Institute; Swanson, Brigitte [Ruby Mountain Inc., Salt Lake City, UT (United States)

    2015-10-16

    This report summarizes the activities and key findings of the project team occurring during Phase 1 (August 2014-October 2015) of the Tularosa Basin Geothermal Play Fairway Analysis Project. The Tularosa Basin Play Fairway Analysis (PFA) project tested two distinct geothermal exploration methodologies covering the entire basin within South Central New Mexico and Far West Texas. Throughout the initial phase of the project, the underexplored basin proved to be a challenging, yet ideal test bed to evaluate effectiveness of the team’s data collection techniques as well as the effectiveness of our innovative PFA. Phase 1 of the effort employed a low-cost, pragmatic approach using two methods to identify potential geothermal plays within the study area and then compared and contrasted the results of each method to rank and evaluate potential plays. Both methods appear to be very effective and highly transferable to other areas.

  3. California Food Processing Industry Wastewater Demonstration Project: Phase I Final Report

    Energy Technology Data Exchange (ETDEWEB)

    Lewis, Glen; Atkinson, Barbara; Rhyne, Ivin

    2009-09-09

    Wastewater treatment is an energy-intensive process and electricity demand is especially high during the utilities summer peak electricity demand periods. This makes wastewater treatment facilities prime candidates for demand response programs. However, wastewater treatment is often peripheral to food processing operations and its demand response opportunities have often been overlooked. Phase I of this wastewater demonstration project monitored wastewater energy and environmental data at Bell-Carter Foods, Inc., California's largest olive processing plant. For this monitoring activity the project team used Green Energy Management System (GEMS) automated enterprise energy management (EEM) technologies. This report presents results from data collected by GEMS from September 15, 2008 through November 30, 2008, during the olive harvest season. This project established and tested a methodology for (1) gathering baseline energy and environmental data at an industrial food-processing plant and (2) using the data to analyze energy efficiency, demand response, daily peak load management, and environmental management opportunities at the plant. The Phase I goals were to demonstrate the measurement and interrelationship of electricity demand, electricity usage, and water quality metrics and to estimate the associated CO{sub 2} emissions.

  4. MEGAPIE-TEST: A European Project on Spallation Target Testing

    International Nuclear Information System (INIS)

    Knebel, Joachim U.; Klein, Jean-Christophe; Gorse, Dominique; Agostini, Pietro; Groeschel, Friedrich; Kupschus, Peter; Kirchner, Thomas; Vogt, Jean-Bernard

    2002-01-01

    Within the Euratom 5. Framework Programme (5FP) the European Commission is funding the MEGAPIE-TEST Project (Megawatt Pilot Experiment - Testing) over a period of three years, starting in September 2001. The project is combining the efforts of 8 main associations. MEGAPIE is a liquid metal spallation target of 1 MW of beam power. The main results of the MEGAPIE-TEST project will be: Development and comprehensive testing of a liquid metal spallation target both under beam-off and beam-on conditions, and the set up of a handbook on the design of a neutron spallation source in general. The operation of MEGAPIE within the accelerator complex SINQ at Paul Scherrer Institute (PSI), Switzerland, is envisaged in 2004. MEGAPIE is a first decisive step to realize a liquid metal spallation target in Europe. This report is giving an overview of the MEGAPIE-TEST Project, the overall work plan, and preliminary results from the design support and validation, which form an important basis for the project. (authors)

  5. Results of eddy current test for second round robin by Halden reactor project

    International Nuclear Information System (INIS)

    Iwai, Takashi; Souzawa, Shizuo; Miyata, Seiichi; Sakai, Haruyuki; Sakakura, Atsushi

    1986-08-01

    JMTR Hot Laboratory has executed the eddy current test of two PWR type zircaloy cladding tubes for the second round robin by Halden Reactor Project. Defects manufactured on the test specimen were revealed on a fair way to success as a function of local position, phase character and size. Influence of the fatigue crack between the two different tubes was studied through the phase angle analysis. More effort should be needed for detecting rather smaller internal defect when it was combined with external and other various type of defects. (author)

  6. Stress analysis of HLW containers advanced test work Compas project

    International Nuclear Information System (INIS)

    Ove Arup and Partners

    1990-01-01

    The Compas project is concerned with the structural performance of metal overpacks which may be used to encapsulate vitrified high-level waste forms before disposal in deep geological repositories. This document describes the activities performed between June and August 1989 forming the advanced test work phase of this project. This is the culmination of two years' analysis and test work to demonstrate whether the analytical ability exists to model containers subjected to realistic loads. Three mild steel containers were designed and manufactured to be one-third scale models of a realistic HLW container, modified to represent the effect of anisotropic loading and to facilitate testing. The containers were tested under a uniform external pressure and all failed by buckling in the mid-body region. The outer surface of each container was comprehensively strain-gauged to provide strain history data at all positions of interest. In parallel with the test work, Compas project partners, from five different European countries, independently modelled the behaviour of each of the containers using their computer codes to predict the failure pressure and produce strain history data at a number of specified locations. The first axisymmetric container was well modelled but predictions for the remaining two non-axisymmetric containers were much more varied, with differences of up to 50% occurring between failure predictions and test data

  7. PROJECT GOVERNANCE – PHASES AND LIFE CYCLE

    Directory of Open Access Journals (Sweden)

    Robbert Titus DEENEN

    2007-01-01

    Full Text Available When talking about projects, the barrier is clear: successful and failed. Some fail due to different reasons, but lack of good project and risk management played a large part. Others succeed largely because of the rigorous and disciplined application of good project practices. But both groups illustrate many points that underline and demonstrate important concepts applicable to current projects. Systematic application of good methods leads to successful outcomes in projects of all types. All projects are fundamentally dependent on people, and human beings are not very different today than we were hundreds, or even thousands, of years ago. This paper uncovers main elements in projects area such as the concepts and governance of projects, with an underline of the main characteristics and the projects phases and life cycle that erase the uncertainty that joins all the projects built at any time.

  8. Systems engineering aspects to installation of the phased multi-year LANSCE-refurbishment project

    International Nuclear Information System (INIS)

    Pieck, Martin; Erickson, John E.; Gulley, Mark S.; Jones, Kevin W.; Rybarcyk, Larry J.

    2009-01-01

    The LANSCE Refurbishment Project (LANSCE-R) is a phased, multiyear project. The project is scheduled to start refurbishment in the 2nd quarter of fiscal year 2011. Closeout will occur during the 4th quarter of FY2016. During the LANSCE-R project, installation of project components must be scheduled during six annual 6-month maintenance-outages and not conflict with annual LANSCE operational commitments to its user facilities. The project and operations schedules must be synchronized carefully. Therefore, the scheduled maintenance outages, functional testing (with beam off, by primarily project personnel) and commissioning (with beam on, by primarily Accelerator Operation Technology (AOT) personnel) must be managed to accommodate operation. Active and effective coordination and communication between the project and AOT personnel must be encouraged to identify, as early as possible, any operational issues. This paper will report on the systems engineering approach to the integration and control of engineering activities.

  9. Projected phase-change memory devices.

    Science.gov (United States)

    Koelmans, Wabe W; Sebastian, Abu; Jonnalagadda, Vara Prasad; Krebs, Daniel; Dellmann, Laurent; Eleftheriou, Evangelos

    2015-09-03

    Nanoscale memory devices, whose resistance depends on the history of the electric signals applied, could become critical building blocks in new computing paradigms, such as brain-inspired computing and memcomputing. However, there are key challenges to overcome, such as the high programming power required, noise and resistance drift. Here, to address these, we present the concept of a projected memory device, whose distinguishing feature is that the physical mechanism of resistance storage is decoupled from the information-retrieval process. We designed and fabricated projected memory devices based on the phase-change storage mechanism and convincingly demonstrate the concept through detailed experimentation, supported by extensive modelling and finite-element simulations. The projected memory devices exhibit remarkably low drift and excellent noise performance. We also demonstrate active control and customization of the programming characteristics of the device that reliably realize a multitude of resistance states.

  10. Project NOAH: Regulating modern sea-level rise. Phase II: Jerusalem Underground

    Science.gov (United States)

    Newman, Walter S.; Fairbridge, Rhodes W.

    This proposal builds a high-speed inter-urban express between Jerusalem and Tel Aviv, generates 1500 megawatts of hydroelectric energy, curtails littoral erosion, builds a port along the Israeli Mediterranean coast and demands peaceful cooperation on both sides of the Jordan River. Phase II represents a pilot project demonstrating the feasibility of continuing to regulate world sea-level by a new series of water regulation schemes. Phase I previously described all those projects already completed or underway which have inadvertently and/or unintentionally served the purpose of sea-level regulation. These forms of Phase I sea-level regulation include large and small reservoirs, irrigation projects, water infiltration schemes, farm ponds, and swimming and reflecting pools. All these water storage projects have already exercised a very appreciable brake on 20th century sea-level rise. Phase II outlines a high-visibility proposal which will serve to illustrate the viability of “Project NOAH”.

  11. Qinshan Phase III (CANDU) nuclear power project quality assurance

    International Nuclear Information System (INIS)

    Wang Lingen; Du Jinxiang

    2001-01-01

    The completion and implementation of quality assurance system of Qinshan Phase III (CANDU) nuclear power project are presented. Some comments and understanding with consideration of the project characteristics are put forward

  12. Borehole project - Final report of phase 3

    International Nuclear Information System (INIS)

    Pusch, R.; Ramqvist, G.

    2008-03-01

    The report describes borehole plugging techniques for use in deep boreholes extending from the ground surface, and construction and placement of plugs in holes of different lengths and orientations bored from the repository rooms. The principle employed is the one proposed in earlier phases of the project, i.e. to tightly seal those parts of boreholes where the rock has few fractures and a low hydraulic conductivity, and filling of those parts that intersect water-bearing fracture zones with physically stable material that does not need to be low-permeable. Four methods for tight plugging have been identified and tested and a technique has been found for filling boreholes that are intersected by fracture zones. The upper end of boreholes extending from the ground surface needs a 'mechanical' seal for which copper metal and concrete work well. The experience from plugging of a 550 m deep borehole at Olkiluoto (OL-KR24) has been compiled and plans worked out for sampling and testing of contacting clay and concrete in this hole and in short holes in the Aespoe URL. (orig.)

  13. Fireside corrosion testing of candidate superheater tube alloys, coatings, and claddings -- Phase 2 field testing

    Energy Technology Data Exchange (ETDEWEB)

    Blough, J.L. [Foster Wheeler Development Corp., Livingston, NJ (United States)

    1996-08-01

    In Phase 1 of this project, a variety of developmental and commercial tubing alloys and claddings was exposed to laboratory fireside corrosion testing simulating a superheater or reheater in a coal-fired boiler. Phase 2 (in situ testing) has exposed samples of 347, RA85H, HR3C, 253MA, Fe{sub 3}Al + 5Cr, 310 modified, NF 709, 690 clad, and 671 clad for over 10,000 hours to the actual operating conditions of a 250-MW coal-fired boiler. The samples were installed on air-cooled, retractable corrosion probes, installed in the reheater cavity, controlled to the operating metal temperatures of an existing and advanced-cycle, coal-fired boiler. Samples of each alloy are being exposed for 4,000, 12,000, and 16,000 hours of operation. The present results are for the metallurgical examination of the corrosion probe samples after approximately 4,400 hours of exposure.

  14. Development and Testing of Industrial Scale Coal Fired Combustion System, Phase 3

    Energy Technology Data Exchange (ETDEWEB)

    Bert Zauderer

    1998-09-30

    Coal Tech Corp's mission is to develop, license & sell innovative, lowest cost, solid fuel fired power systems & total emission control processes using proprietary and patented technology for domestic and international markets. The present project 'DEVELOPMENT & TESTING OF INDUSTRIAL SCALE, COAL FIRED COMBUSTION SYSTEM, PHASE 3' on DOE Contract DE-AC22-91PC91162 was a key element in achieving this objective. The project consisted of five tasks that were divided into three phases. The first phase, 'Optimization of First Generation 20 MMBtu/hr Air-Cooled Slagging Coal Tech Combustor', consisted of three tasks, which are detailed in Appendix 'A' of this report. They were implemented in 1992 and 1993 at the first generation, 20 MMBtu/hour, combustor-boiler test site in Williamsport, PA. It consisted of substantial combustor modifications and coal-fired tests designed to improve the combustor's wall cooling, slag and ash management, automating of its operation, and correcting severe deficiencies in the coal feeding to the combustor. The need for these changes was indicated during the prior 900-hour test effort on this combustor that was conducted as part of the DOE Clean Coal Program. A combination of combustor changes, auxiliary equipment changes, sophisticated multi-dimensional combustion analysis, computer controlled automation, and series of single and double day shift tests totaling about 300 hours, either resolved these operational issues or indicated that further corrective changes were needed in the combustor design. The key result from both analyses and tests was that the combustor must be substantially lengthened to maximize combustion efficiency and sharply increase slag retention in the combustor. A measure of the success of these modifications was realized in the third phase of this project, consisting of task 5 entitled: 'Site Demonstration with the Second Generation 20 MMBtu/hr Air-Cooled Slagging Coal Tech

  15. Integrated Monitoring and Surveillance System demonstration project. Phase 2 accomplishments

    International Nuclear Information System (INIS)

    Aumeier, S.E.; Walters, B.G.; Singleterry, R.C.

    1997-01-01

    The paper presents the results of the Integrated Monitoring and Surveillance System (IMSS) demonstration project Phase 2 efforts. the rationale behind IMSS development is reviewed and progress in each of the 5 basic tasks is detailed. Significant results include further development of the data acquisition system and procurement of necessary hardware/software, options and associated costs for plutonium canning systems and gloveboxes, initiation of facility modifications, determination of possibly affected facility documentation, results from sensor system trade study, and preliminary storage configuration designs. Resources invested during Phase 1 and Phase 2 are summarized and budgetary requirements for completion of Phase 3 presented. The results show that the IMSS demonstration project team has met and in many cases exceeded the commitments made for Phase 2 deliverables

  16. BWR Full Integral Simulation Test (FIST). Phase I test results

    International Nuclear Information System (INIS)

    Hwang, W.S.; Alamgir, M.; Sutherland, W.A.

    1984-09-01

    A new full height BWR system simulator has been built under the Full-Integral-Simulation-Test (FIST) program to investigate the system responses to various transients. The test program consists of two test phases. This report provides a summary, discussions, highlights and conclusions of the FIST Phase I tests. Eight matrix tests were conducted in the FIST Phase I. These tests have investigated the large break, small break and steamline break LOCA's, as well as natural circulation and power transients. Results and governing phenomena of each test have been evaluated and discussed in detail in this report. One of the FIST program objectives is to assess the TRAC code by comparisons with test data. Two pretest predictions made with TRACB02 are presented and compared with test data in this report

  17. DECOVALEX-THMC Project. Task B. Understanding and characterizing the excavation disturbed zone (EDZ). Phase 2 Report

    International Nuclear Information System (INIS)

    Hudson, John A.; Lanru Jing; Antikainen, Juha; Backers, Tobias; Baeckstroem, Ann; Koyama, Tomofumi; Xiating Feng; Pengzhi Pan; Kobayashi, Akira; Rinne, Mikael; Baotang Shen

    2007-02-01

    The DECOVALEX-THMC project is an ongoing international co-operative project that was stared in 2004 to support the development of mathematical models of coupled Thermal (T), Hydrological (H), Mechanical (M) and Chemical (C) processes in geological media for siting potential nuclear fuel waste repositories. The general objective is to characterise and evaluate the coupled THMC processes in the near field and far field of a geological repository and to assess their impact on performance assessment: - during the three phases of repository development: excavation phase, operation phase and post-closure phase; - for three different rocks types: crystalline, argillaceous and tuff; - with specific focus on the issues of: Excavation Damaged Zone (EDZ), permanent property changes of rock masses, and glaciation and permafrost phenomena. The project involves a large number of research teams supported by radioactive waste management agencies or governmental regulatory bodies in Canada, China, Finland, France, Germany, Japan, Sweden and USA, who conducted advanced studies and numerical modelling of coupled THMC processes under five tasks. This report summarizes the work contributed to Phase 2 of Task B of the project, which took place during the period of March 2004 to May 2006. The Phase 2 work incorporated the use of a wide range of numerical models to simulate the failure of a number of intact rock core samples, from the APSE tunnel at Aespoe HRL, as tested in uniaxial compression and other loading conditions with the intention of establishing the common and code-specific features of the models. The core samples of the Aespoe diorite were treated with different initial mechanical and chemical conditions as dry samples, saturated with distilled water, formation water and saline water, with different durations of submersion, respectively, in order to observe the mechanical effects of saturation by different chemical fluids on the mechanical properties of the intact core

  18. DECOVALEX-THMC Project. Task B. Understanding and characterizing the excavation disturbed zone (EDZ). Phase 2 Report

    Energy Technology Data Exchange (ETDEWEB)

    Hudson, John A. (ed.) [Swedish Nuclear Fuel and Waste Management Co., Stockholm (Sweden)]|[Rock Engineering Consultants (United Kingdom); Lanru Jing (ed.) [Royal Institute of Technology, Stockholm (Sweden); Antikainen, Juha [Helsinki University of Technology, Helsinki (Finland); Backers, Tobias [GeoFrames GmbH, (Germany); Baeckstroem, Ann [Swedish Nuclear Fuel and Waste Management Co., Stockholm (Sweden)]|[Bergbyggkonsult AB (Sweden); Koyama, Tomofumi [Swedish Nuclear Power Inspectorate, Stockholm (Sweden); Xiating Feng; Pengzhi Pan [Chinese Academy of Sciences (China); Kobayashi, Akira [Kyoto Univ. (Japan); Rinne, Mikael; Baotang Shen [Fracom Ltd. (Finland)

    2007-02-15

    The DECOVALEX-THMC project is an ongoing international co-operative project that was stared in 2004 to support the development of mathematical models of coupled Thermal (T), Hydrological (H), Mechanical (M) and Chemical (C) processes in geological media for siting potential nuclear fuel waste repositories. The general objective is to characterise and evaluate the coupled THMC processes in the near field and far field of a geological repository and to assess their impact on performance assessment: - during the three phases of repository development: excavation phase, operation phase and post-closure phase; - for three different rocks types: crystalline, argillaceous and tuff; - with specific focus on the issues of: Excavation Damaged Zone (EDZ), permanent property changes of rock masses, and glaciation and permafrost phenomena. The project involves a large number of research teams supported by radioactive waste management agencies or governmental regulatory bodies in Canada, China, Finland, France, Germany, Japan, Sweden and USA, who conducted advanced studies and numerical modelling of coupled THMC processes under five tasks. This report summarizes the work contributed to Phase 2 of Task B of the project, which took place during the period of March 2004 to May 2006. The Phase 2 work incorporated the use of a wide range of numerical models to simulate the failure of a number of intact rock core samples, from the APSE tunnel at Aespoe HRL, as tested in uniaxial compression and other loading conditions with the intention of establishing the common and code-specific features of the models. The core samples of the Aespoe diorite were treated with different initial mechanical and chemical conditions as dry samples, saturated with distilled water, formation water and saline water, with different durations of submersion, respectively, in order to observe the mechanical effects of saturation by different chemical fluids on the mechanical properties of the intact core

  19. Process-Hardened, Multi-Analyte Sensor for Characterizing Rocket Plum Constituents Under Test Environment, Phase II

    Data.gov (United States)

    National Aeronautics and Space Administration — The objective of the Phase II STTR project is to develop a prototype multi-analyte sensor system to detect gaseous analytes present in the test stands during...

  20. Test and Approval Center for Fuel Cell and Hydrogen Technologies: Phase I. Initiation

    DEFF Research Database (Denmark)

    already spent on these technologies also lead to commercial success. The projectTest and Approval Center for Fuel Cell and Hydrogen Technologies: Phase I. Initiation’ was aiming at starting with the Establishment of such a center. The following report documents the achievements within the project...... of the fluctuating wind energy. As the fuel cell and hydrogen technologies come closer to commercialization, development of testing methodology, qualified testing and demonstration become increasingly important. Danish industrial players have expressed a strong need for support in the process to push fuel cell...... and hydrogen technologies from the research and development stage into the commercial domain. A Center to support industry with test, development, analysis, approval, certification, consultation, and training in the areas of fuel cell and hydrogen technologies was needed. Denmark has demonstrated leading...

  1. Integrated monitoring and surveillance system demonstration project: Phase I accomplishments

    International Nuclear Information System (INIS)

    Aumeier, S.E.; Walters, B.G.; Crawford, D.C.

    1997-01-01

    The authors present the results of the Integrated Monitoring and Surveillance System (IMSS) demonstration project Phase I efforts. The rationale behind IMSS development is reviewed and progress in each of the 5 basic tasks is detailed. Significant results include decisions to use Echelon LonWorks networking protocol and Microsoft Access for the data system needs, a preliminary design for the plutonium canning system glovebox, identification of facilities and materials available for the demonstration, determination of possibly affected facility documentation, and a preliminary list of available sensor technologies. Recently imposed changes in the overall project schedule and scope are also discussed and budgetary requirements for competition of Phase II presented. The results show that the IMSS demonstration project team has met and in many cases exceeded the commitments made for Phase I deliverables

  2. Coal-fired MHD combustor development project: Phase 3D

    Science.gov (United States)

    1985-05-01

    This fourth quarterly technical progress report of the Coal-Fired MHD Combustor Development Project (Phase 3D) presents the accomplishments during the period February 1 to April 30, 1985. The scope of work covered by this quarterly report encompasses development work on the 50 MW/sub t/ combustor related to test support at the CDIF, assembly and checkout of first and second stage hardware, second stage design verification testing, designs for a continuous slag rejector and low preheat inlet section, and planning for power train testing. Progress includes the following: assembly and checkout of the second first stage, two second stages, and PEM was completed and the hardware was shipped to CDIF and FETS; integration of first and second stage hardware on the FETS Cell No. 2 test stand was completed, cold flow functional tests were performed, and hot fire checkout testing was initiated; assembly of the continuous slag rejector test set-up was 70% completed; the low preheat air inlet section Preliminary Design Review was held (work on the detail design was initiated and is 85% complete); and the Users' Manual was updated to include material for the second stage and final revisions to the power train test plan were made.

  3. SmartPark Technology Demonstration Project, Phase II: Final Report

    Science.gov (United States)

    2018-05-01

    The purpose of FMCSA's SmartPark project was to determine the feasibility of a technology for providing truck parking space availability information in real time to truckers on the road. SmartPark consisted of two phases. Phase I was a field operatio...

  4. Plutonium immobilization program - Cold pour Phase 1 test results

    International Nuclear Information System (INIS)

    Hamilton, L.

    2000-01-01

    The Plutonium Immobilization Project will disposition excess weapons grade plutonium. It uses the can-in-canister approach that involves placing plutonium-ceramic pucks in sealed cans that are then placed into Defense Waste Processing Facility canisters. These canisters are subsequently filled with high-level radioactive waste glass. This process puts the plutonium in a stable form and makes it unattractive for reuse. A cold (non-radioactive) glass pour program was performed to develop and verify the baseline design for the canister and internal hardware. This paper describes the Phase 1 scoping test results

  5. Plutonium Immobilization Program - Cold pour Phase 1 test results

    International Nuclear Information System (INIS)

    Hamilton, L.

    2000-01-01

    The Plutonium Immobilization Project will disposition excess weapons grade plutonium. It uses the can-in-canister approach that involves placing plutonium-ceramic pucks in sealed cans that are then placed into Defense Waste Processing Facility canisters. These canisters are subsequently filled with high-level radioactive waste glass. This process puts the plutonium in a stable form and makes it unattractive for reuse. A cold (non-radioactive) glass pour program was performed to develop and verify the baseline design for the canister and internal hardware. This paper describes the Phase 1 scoping test results

  6. Gamma-ray CT from incomplete projections for two-phase pipe flow.

    Science.gov (United States)

    Xin, S; Wang, H X

    2017-02-01

    A low-energy low-dose γ-ray computed tomography (CT) system used in the gas-liquid two-phase pipe flow measurement has been studied at Tianjin University in recent years. The γ-ray CT system, having a third-generation X-ray CT scanning configuration, is comprised of one 300mCi 241 Am source and 17 CdZnTe detector units and achieves a spatial image resolution of about 7 mm. It is primarily intended to measure the two-phase pipe flow and provide improvement suggestions for industrial CT system. Recently we improve the design for image reconstruction from incomplete projection to optimize the scanning parameters and reduce the radiation dose. First, tomographic problem from incomplete projections is briefly described. Next, a system structure and a hardware circuit design are listed and explained, especially on time parameter setting of the pulse shaper. And then a detailed system analysis is provided in Section II, mainly focusing on spatial resolution, temporal resolution, system noise, and imaging algorithm. Finally, we carry on necessary static and dynamic experiments in a full scan (360°) and two sets of partial scan reconstruction tests to determine the feasibility of this γ-ray CT system for reconstructing the images from insufficient projections. And based on an A-variable algebraic reconstruction technique method, a specially designed algorithm, we evaluate the system performance and noise level of this CT system working quantitatively and qualitatively. Results of dynamic test indicate that the acceptable results can be acquired using a multi-source γ-ray CT system with the same parameters when the flow rate is less than 0.04 m/s and the imaging speed is slower than 33 frames/s.

  7. JSS project phase 4: Experimental and modelling studies of HLW glass dissolution in repository environments

    International Nuclear Information System (INIS)

    1987-10-01

    A goal of the JSS project was to develop a scientific basis for understanding the effects of waste package components, groundwater chemistry, and other repository conditions on glass dissolution behaviour, and to develop and refine a model for the processes governing glass dissolution. The fourth phase of the project, which was performed by the Hahn-Meitner-Institut, Berlin, FRG, dealt specifically with model development and application. Phase 4 also adressed whether basaltic glasses could serve as natural analogues for nuclear waste glasses, thus providing a means to test the capability of the model for long-term predictions. Additional experiments were performed in order to complete the data base necessary to model interactions between the glass and bentonite and between glass and steel corrosion products. More data on temperature, S/V, and pH dependence of the glass/water reaction were also collected. In this report, the data acquired during phase 4 are presented and discussed. (orig./DG)

  8. Horonobe Underground Research Laboratory Project. Plans for surface-based investigations. Phase 1

    International Nuclear Information System (INIS)

    Goto, Junichi; Hama, Katsuhiro

    2003-10-01

    for the geological environment. Information on earthquake/fault activities, uplift/subsidence/denudation processes and crustal activities are collected and integrated by literature survey, surface geological investigations and earthquake monitoring in c) Study on the long-term stability of the geological environment. Designing of the underground facility, examination of construction management methods, and investigation plans for restoration techniques on damages of the construction are focussed in d) Development of the basis for engineering technologies in deep underground. Investigation plans for Phases 2 and 3 include e) Demonstration of technologies for engineered barrier and f) Development of methodologies for detailed designing of deep repositories. Safety assessment models are tested and improved, and items, amount and accuracy of data for safety assessment are confirmed through investigations for g) Improvement of reliability on safety assessment methods. Environmental survey in the laboratory construction area, and designing and land development for ground facilities are conducted in Phase 1. A part of the research and development for the 'Earthquake Frontier Research Project' is also to be conducted. (author)

  9. Project Portfolio Management Applications Testing

    OpenAIRE

    Paul POCATILU

    2006-01-01

    Many IT companies are running project simultaneously. In order to achieve the best results, they have to group to the project in portfolios, and to use specific software that helps to manage them. Project portfolio management applications have a high degree of complexity and they are very important for the companies that are using it. This paper focuses on some characteristics of the testing process for project portfolio management applications

  10. Phase accuracy evaluation for phase-shifting fringe projection profilometry based on uniform-phase coded image

    Science.gov (United States)

    Zhang, Chunwei; Zhao, Hong; Zhu, Qian; Zhou, Changquan; Qiao, Jiacheng; Zhang, Lu

    2018-06-01

    Phase-shifting fringe projection profilometry (PSFPP) is a three-dimensional (3D) measurement technique widely adopted in industry measurement. It recovers the 3D profile of measured objects with the aid of the fringe phase. The phase accuracy is among the dominant factors that determine the 3D measurement accuracy. Evaluation of the phase accuracy helps refine adjustable measurement parameters, contributes to evaluating the 3D measurement accuracy, and facilitates improvement of the measurement accuracy. Although PSFPP has been deeply researched, an effective, easy-to-use phase accuracy evaluation method remains to be explored. In this paper, methods based on the uniform-phase coded image (UCI) are presented to accomplish phase accuracy evaluation for PSFPP. These methods work on the principle that the phase value of a UCI can be manually set to be any value, and once the phase value of a UCI pixel is the same as that of a pixel of a corresponding sinusoidal fringe pattern, their phase accuracy values are approximate. The proposed methods provide feasible approaches to evaluating the phase accuracy for PSFPP. Furthermore, they can be used to experimentally research the property of the random and gamma phase errors in PSFPP without the aid of a mathematical model to express random phase error or a large-step phase-shifting algorithm. In this paper, some novel and interesting phenomena are experimentally uncovered with the aid of the proposed methods.

  11. 360-degrees profilometry using strip-light projection coupled to Fourier phase-demodulation.

    Science.gov (United States)

    Servin, Manuel; Padilla, Moises; Garnica, Guillermo

    2016-01-11

    360 degrees (360°) digitalization of three dimensional (3D) solids using a projected light-strip is a well-established technique in academic and commercial profilometers. These profilometers project a light-strip over the digitizing solid while the solid is rotated a full revolution or 360-degrees. Then, a computer program typically extracts the centroid of this light-strip, and by triangulation one obtains the shape of the solid. Here instead of using intensity-based light-strip centroid estimation, we propose to use Fourier phase-demodulation for 360° solid digitalization. The advantage of Fourier demodulation over strip-centroid estimation is that the accuracy of phase-demodulation linearly-increases with the fringe density, while in strip-light the centroid-estimation errors are independent. Here we proposed first to construct a carrier-frequency fringe-pattern by closely adding the individual light-strip images recorded while the solid is being rotated. Next, this high-density fringe-pattern is phase-demodulated using the standard Fourier technique. To test the feasibility of this Fourier demodulation approach, we have digitized two solids with increasing topographic complexity: a Rubik's cube and a plastic model of a human-skull. According to our results, phase demodulation based on the Fourier technique is less noisy than triangulation based on centroid light-strip estimation. Moreover, Fourier demodulation also provides the amplitude of the analytic signal which is a valuable information for the visualization of surface details.

  12. Technical realization of the VISA-2 Project, contract: 2.01/ I phase, Volume No. I

    International Nuclear Information System (INIS)

    1963-12-01

    Cooperation between the Institutes in Vinca and Saclay has started by carrying out the task 'Technical realization of the VISA-2 project' which should enable: obtaining new experimental spaces in the RA reactor with high fast neutron flux for sample irradiation; obtaining experience in reactor continual operation for few months at nominal power of 6.5 MW and increase of RA reactor utilization; solving the problem of activated channels and samples transport, problems of working in hot cells; obtaining irradiated samples for examining radiation effects first in Saclay and later in Vinca. The project is divided in three phases. Phase one covers the reconstruction of the RA reactor fuel channels according to the VISA-2 project demands. The second phase includes the activities related to measuring devices for measuring the temperatures at the incoming and outgoing heavy water in 5 VISA-2 channels, as well as temperature of the samples (55 thermocouples) and testing the channels and capsules after their insertion in the reactor. The third phase includes activities are related to problems of transport of radioactive channels and VISA-2 capsules, problems of cutting as well as packing and transporting of irradiated samples from Vinca to Saclay. This volume includes all the relevant documents for completing the task including contracts, needed preliminary calculations as well as safety analysis [sr

  13. Project Portfolio Management Applications Testing

    Directory of Open Access Journals (Sweden)

    Paul POCATILU

    2006-01-01

    Full Text Available Many IT companies are running project simultaneously. In order to achieve the best results, they have to group to the project in portfolios, and to use specific software that helps to manage them. Project portfolio management applications have a high degree of complexity and they are very important for the companies that are using it. This paper focuses on some characteristics of the testing process for project portfolio management applications

  14. Fireside corrosion testing of candidate superheater tube alloys, coatings, and claddings -- Phase 2 field testing

    Energy Technology Data Exchange (ETDEWEB)

    Blough, J.L.; Seitz, W.W.; Girshik, A. [Foster Wheeler Development Corp., Livingston, NJ (United States)

    1998-06-01

    In Phase 1 of this project, laboratory experiments were performed on a variety of developmental and commercial tubing alloys and claddings by exposing them to fireside corrosion tests which simulated a superheater or reheater in a coal-fired boiler. Phase 2 (in situ testing) has exposed samples of 347, RA85H, HR3C, RA253MA, Fe{sub 3}Al + 5Cr, Ta-modified 310, NF 709, 690 clad, 671 clad, and 800HT for up to approximately 16,000 hours to the actual operating conditions of a 250-MW, coal-fired boiler. The samples were installed on air-cooled, retractable corrosion probes, installed in the reheater cavity, and controlled to the operating metal temperatures of an existing and advanced-cycle, coal-fired boiler. Samples of each alloy were exposed for 4,483, 11,348, and 15,883 hours of operation. The present results are for the metallurgical examination of the corrosion probe samples after the full 15,883 hours of exposure. A previous topical report has been issued for the 4,483 hours of exposure.

  15. Telecentric 3D profilometry based on phase-shifting fringe projection.

    Science.gov (United States)

    Li, Dong; Liu, Chunyang; Tian, Jindong

    2014-12-29

    Three dimensional shape measurement in the microscopic range becomes increasingly important with the development of micro manufacturing technology. Microscopic fringe projection techniques offer a fast, robust, and full-field measurement for field sizes from approximately 1 mm2 to several cm2. However, the depth of field is very small due to the imaging of non-telecentric microscope, which is often not sufficient to measure the complete depth of a 3D-object. And the calibration of phase-to-depth conversion is complicated which need a precision translation stage and a reference plane. In this paper, we propose a novel telecentric phase-shifting projected fringe profilometry for small and thick objects. Telecentric imaging extends the depth of field approximately to millimeter order, which is much larger than that of microscopy. To avoid the complicated phase-to-depth conversion in microscopic fringe projection, we develop a new system calibration method of camera and projector based on telecentric imaging model. Based on these, a 3D reconstruction of telecentric imaging is presented with stereovision aided by fringe phase maps. Experiments demonstrated the feasibility and high measurement accuracy of the proposed system for thick object.

  16. Sears Point Tidal Marsh Restoration Project: Phase II

    Science.gov (United States)

    Information about the SFBWQP Sears Point Tidal Marsh Restoration Project: Phase II, part of an EPA competitive grant program to improve SF Bay water quality focused on restoring impaired waters and enhancing aquatic resources.

  17. Ultrasonic Communication Project, Phase 1, FY1999

    Energy Technology Data Exchange (ETDEWEB)

    Haynes, H.D.; Akerman, M.A.; Baylor, V.M.

    2000-06-01

    This Phase 1 project has been successful in identifying, exploring, and demonstrating methods for ultrasonic-based communication with an emphasis on the application of digital signal processing techniques. During the project, at the direction of the agency project monitor, particular attention was directed at sending and receiving ultrasonic data through air and through pipes that would be commonly found in buildings. Efforts were also focused on development of a method for transmitting computer files ultrasonically. New methods were identified and evaluated for ultrasonic communication. These methods are based on a technique called DFS. With DFS, individual alphanumeric characters are broken down into a sequence of bits, and each bit is used to generate a discrete ultrasonic frequency. Characters are then transmitted one-bit-at-a-time, and reconstructed by the receiver. This technique was put into practice through the development of LabVIEW{trademark}VIs. These VIs were integrated with specially developed electronic circuits to provide a system for demonstrating the transmission and reception/reconstruction of typed messages and computer files. Tests were performed to determine the envelope for ultrasound transmission through pipes (with and without water) versus through air. The practical aspects of connections, efficient electronics, impedance matching, and the effect of damping mechanisms were all investigated. These tests resulted in a considerable number of reference charts that illustrate the absorption of ultrasound through different pipe materials, both with and without water, as a function of distance. Ultrasound was found to be least attenuated by copper pipe and most attenuated by PVC pipe. Water in the pipe provides additional damping and attenuation of ultrasonic signals. Dramatic improvements are observed, however, in ultrasound signal strength if the transducers are directly coupled to the water, rather than simply attaching them to the outside of

  18. Assessing the influence of project management on quality during the early phases of construction projects

    Directory of Open Access Journals (Sweden)

    Ljevo Žanesa

    2018-12-01

    Full Text Available Although the quality of a process affects the quality of the end product, there is currently an insignif­icant amount of knowledge about the quality of project management (PM processes that directly affect the quality of the delivered product (constructed building. This study presents a proposal for modeling the impact of the quality of the PM process on the quality of the con­structed building. The quality of the PM process is rep­resented by the main quality factors and product quality indicators. It presents the results of the interviews that were conducted and study cases that were analyzed in Bosnia and Herzegovina with a variety of project partici­pants (with different managerial perspectives in terms of the indicators of quality of the delivered product. All par­ticipants, regardless of managerial perspective, believe that the most important indicator of the quality of prod­ucts for each phase of the project is “customer satisfaction in the end phase”, the measurement of which is different for each project phase that is presented. The results of the factor analysis of the definition and the planning phases show that 11 variables, namely, the quality factors of the PM process, can be grouped into three new factors, which is described as 66.61% (77.046% of the basic set of vari­ables.

  19. Light phase testing of social behaviors: not a problem

    Directory of Open Access Journals (Sweden)

    Mu Yang

    2008-12-01

    Full Text Available The rich repertoire of mouse social behaviors makes it possible to use mouse models to study neurodevelopmental disorders characterized by social deficits. The fact that mice are naturally nocturnal animals raises a critical question of whether behavioral experiments should be strictly conducted in the dark phase and whether light phase testing is a major methodologically mistake. Although mouse social tasks have been performed in both phases in different laboratories, there seems to be no general consensus on whether testing phase is a critical factor or not. A recent study from our group showed remarkably similar social scores obtained from inbred mice tested in the light and the dark phase, providing evidence that light phase testing could yield reliable results as robust as dark phase testing for the sociability test. Here we offer a comprehensive review on mouse social behaviors measured in light and dark phases and explain why it is reasonable to test laboratory mice in experimental social tasks in the light phase.

  20. Phased Startup Initiative Phase 3 and 4 Test Procedure (OCRWM)

    International Nuclear Information System (INIS)

    PAJUNEN, A.L.

    2000-01-01

    The purpose of this test procedure is to safely operate the Fuel Retrieval System (FRS) and Integrated Water Treatment System (IWTS) with specific fuel canisters, and show that canisters containing fuel can be retrieved from the canister queue, decapped in the Canister Decapper, and loaded into the Primary Clean Machine (PCM) for fuel cleaning; and that fuel can be sorted on the Process Table, then loaded back into fuel canisters and relocated in basin storage. An option is included to load selected elements into multi-canister overpack (MCO) Fuel Baskets. Additional Data are collected during this test, beyond that collected during production operations. These data support qualifying the cleaning performance of the PCM, assessing the quantity of scrap generated during the cleaning, and evaluating the impact of fuel retrieval operations on the Basin water quality. The additional data collected primarily consist of weighing fuel and scrap at selected points in the operation, as well as photographing fuel and scrap as it is processed. The time to perform operations is also monitored for comparison with design predictions. Water quality data are collected to establish a baseline to predict the effectiveness of equipment design for control of contamination and visibility during production operation. The scope of this test procedure is to validate the operation of FRS and IWTS components as a complete system. Fuel canisters shall be processed in accordance with this test procedure such that fuel inspection results are clearly attributed to a particular set of PCM operating parameters. The Phase 3 test sequence processes a minimum of six canisters. Twenty-four contingency canisters have been identified, and will be processed if additional performance data are required. The Phase 4 test sequence processes a minimum of 29 specific canisters. Twenty-nine contingency canisters have been identified for Phase 4 activities and will be processed to complete process validation, if

  1. Code of Conduct for wind-power projects - Phase 3

    International Nuclear Information System (INIS)

    Strub, P.; Ziegler, Ch.

    2008-11-01

    This paper discusses the results of phase three of a project concerning wind-power projects. Feasibility and strategy aspects are examined and discussed. The current state of the wind power market is discussed on the basis of the results of a survey made on the subject. The social acceptance of wind power installations is discussed, whereby the rejection of particular projects is compared with a general lack of acceptance. Requirements placed on such projects and possible solutions are discussed. Finally, the feasibility of setting up a code of conduct in the area of wind-power projects is discussed and the definition of further instruments is examined

  2. Improving Climate Projections by Understanding How Cloud Phase affects Radiation

    Science.gov (United States)

    Cesana, Gregory; Storelvmo, Trude

    2017-01-01

    Whether a cloud is predominantly water or ice strongly influences interactions between clouds and radiation coming down from the Sun or up from the Earth. Being able to simulate cloud phase transitions accurately in climate models based on observational data sets is critical in order to improve confidence in climate projections, because this uncertainty contributes greatly to the overall uncertainty associated with cloud-climate feedbacks. Ultimately, it translates into uncertainties in Earth's sensitivity to higher CO2 levels. While a lot of effort has recently been made toward constraining cloud phase in climate models, more remains to be done to document the radiative properties of clouds according to their phase. Here we discuss the added value of a new satellite data set that advances the field by providing estimates of the cloud radiative effect as a function of cloud phase and the implications for climate projections.

  3. Final report on the surface-based investigation (phase 1) at the Mizunami Underground Laboratory project

    International Nuclear Information System (INIS)

    Saegusa, Hiromitsu; Seno, Yasuhiro; Nakama, Shigeo; Tsuruta, Tadahiko; Amano, Kenji; Takeuchi, Ryuji; Matsuoka, Toshiyuki; Onoe, Hironori; Mizuno, Takashi; Ohyama, Takuya; Hama, Katsuhiro; Sato, Toshinori; Kuji, Masayoshi; Kuroda, Hidetaka; Semba, Takeshi; Uchida, Masahiro; Sugihara, Kozo; Sakamaki, Masanori; Iwatsuki, Teruki

    2007-03-01

    The Mizunami Underground Laboratory (MIU) Project is a comprehensive research project investigating the deep underground environment within crystalline rock being conducted by Japan Atomic Energy Agency at Mizunami City in Gifu Prefecture, central Japan and its role is defined in 'Framework for Nuclear Energy Policy' by Japan Atomic Energy Commission. The MIU Project has three overlapping phases: Surface-based Investigation phase (Phase I), Construction phase (Phase II), and Operation phase (Phase III), with a total duration of 20 years. The overall project goals of the MIU Project from Phase I through to Phase III are: 1) to establish techniques for investigation, analysis and assessment of the deep geological environment, and 2) to develop a range of engineering for deep underground application. During Phase I, the overall project goals were supported by Phase I goals. For the overall project goals 1), the Phase I goals were set to construct models of the geological environment from all surface-based investigation results that describe the geological environment prior to excavation and predict excavation response. For the overall project goals 2), the Phase I goals were set to formulate detailed design concepts and a construction plan for the underground facilities. This report summarizes the Phase I investigation which was completed in March 2005. The authors believe this report will make an important milestone, since this report clarifies how the Phase I goals are achieved and evaluate the future issues thereby direct the research which will be conducted during Phase II. With regard to the overall project goals 1), 'To establish techniques for investigation, analysis and assessment of the deep geological environment,' a step-wise investigation was conducted by iterating investigation, interpretation, and assessment, thereby understanding of geologic environment was progressively and effectively improved with progress of investigation. An optimal procedure from

  4. Automatic testing in the integration phase of mobile work machine (TINAT) - MASIT31

    Energy Technology Data Exchange (ETDEWEB)

    Multanen, P.; Hyvoenen, M. (Tampere University of Technology, Department of Intelligent Hydraulics and Automation, Tampere (Finland)); Ellman, A. (Tampere University of Technology, Department of Mechanics and Design, Tampere (Finland)); Rantala, S.; Alanen, J. (VTT Technical Research Centre of Finland, Espoo (Finland))

    2008-07-01

    Abstract The performance and reliability of mobile work machines are significantly affected by control systems of machines and their characteristics. Currently the testing of control systems and verification of their properties is often carried out just in the integration phase of controls and mechanical structure of machine. This is very time consuming, requires a lot of test personnel and is not extensive enough. In TINAT project a test concept will be developed for the testing of entire control systems of work machines without real the mechanical structures of the machines by utilizing modelling and real-time hardware-in-the-loop simulation. The simulator system enables automatic generation of test scenarios and automatic analysis and reporting of test results. (orig.)

  5. Phase unwrapping algorithm based on multi-frequency fringe projection and fringe background for fringe projection profilometry

    International Nuclear Information System (INIS)

    Zhang, Chunwei; Zhao, Hong; Gu, Feifei; Ma, Yueyang

    2015-01-01

    A phase unwrapping algorithm specially designed for the phase-shifting fringe projection profilometry (FPP) is proposed. It combines a revised dual-frequency fringe projectionalgorithm and a proposed fringe background based quality guided phase unwrapping algorithm (FB-QGPUA). Phase demodulated from the high-frequency fringe patterns is partially unwrapped by that demodulated from the low-frequency ones. Then FB-QGPUA is adopted to further unwrap the partially unwrapped phase. Influences of the phase error on the measurement are researched. Strategy to select the fringe pitch is given. Experiments demonstrate that the proposed method is very robust and efficient. (paper)

  6. IDC Reengineering Phase 2 Project Scope.

    Energy Technology Data Exchange (ETDEWEB)

    Harris, James M. [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States)

    2015-02-01

    This report provides a brief description of the scope of the IDC Reengineering Phase 2 project. It describes the goals and objectives of reengineering, the system definition, and the technical scope of the system. REVISIONS Version Date Author/Team Revision Description Authorized by 1.0 9/25/2014 SNL IDC Reengineering Team Unlimited Release for I2 M. Harris 1.1 28/01/2015 IDC Reengineering Team Align with previous IDC scope document E. Tomuta.

  7. The international INTRAVAL project. Phase 2, Summary report

    International Nuclear Information System (INIS)

    Larsson, A.; Pers, K.; Skagius, K.; Dverstorp, B.

    1997-01-01

    The international project INTRAVAL addresses the validation of models of transport of radionuclides through groundwater in the geosphere. Such models are used in the assessment of the long-term safety of radioactive waste disposal systems. The second phase of INTRAVAL, which started in 1990, was concluded at the end of 1993. The objective of Phase 2 was to increase the understanding how various geophysical, geohydrological and geochemical phenomena of importance for radionuclide transport from a repository to the biosphere could be described by mathematical models and to study the model validation process. Summarized results from Phase 2 of the INTRAVAL study are presented in this report. (K.A.)

  8. Small car exposure data project. Phase 1 : methodology

    Science.gov (United States)

    1985-10-01

    The Small Car Exposure Data Project represents the first phase of an effort to build a data : base of exposure variables for crash-avoidance studies. Among these are: (1) vehicle make, : model, year, body style, wheel base, weight, and horsepower; (2...

  9. Prototypical Rod Consolidation Demonstration Project

    International Nuclear Information System (INIS)

    1993-05-01

    The objective of Phase 3 of the Prototypical Rod consolidation Demonstration Project (PRCDP) was to procure, fabricate, assemble, and test the Prototypical Rod consolidation System as described in the NUS Phase 2 Final Design Report. This effort required providing the materials, components, and fabricated parts which makes up all of the system equipment. In addition, it included the assembly, installation, and setup of this equipment at the Cold Test Facility. During the Phase 3 effort the system was tested on a component, subsystem, and system level. This volume 1, discusses the PRCDP Phase 3 Test Program that was conducted by the HALLIBURTON NUS Environmental Corporation under contract AC07-86ID12651 with the United States Department of Energy. This document, Volume 1, Book 1 discusses the following topics: the background of the project; test program description; summary of tests and test results; problem evaluation; functional requirements confirmation; recommendations; and completed test documentation for tests performed in Phase 3

  10. Fringe-period selection for a multifrequency fringe-projection phase unwrapping method

    International Nuclear Information System (INIS)

    Zhang, Chunwei; Zhao, Hong; Jiang, Kejian

    2016-01-01

    The multi-frequency fringe-projection phase unwrapping method (MFPPUM) is a typical phase unwrapping algorithm for fringe projection profilometry. It has the advantage of being capable of correctly accomplishing phase unwrapping even in the presence of surface discontinuities. If the fringe frequency ratio of the MFPPUM is too large, fringe order error (FOE) may be triggered. FOE will result in phase unwrapping error. It is preferable for the phase unwrapping to be kept correct while the fewest sets of lower frequency fringe patterns are used. To achieve this goal, in this paper a parameter called fringe order inaccuracy (FOI) is defined, dominant factors which may induce FOE are theoretically analyzed, a method to optimally select the fringe periods for the MFPPUM is proposed with the aid of FOI, and experiments are conducted to research the impact of the dominant factors in phase unwrapping and demonstrate the validity of the proposed method. Some novel phenomena are revealed by these experiments. The proposed method helps to optimally select the fringe periods and detect the phase unwrapping error for the MFPPUM. (paper)

  11. Horonobe Underground Research Laboratory project. Synthesis of phase II (construction phase) investigations to a depth of 350 m

    International Nuclear Information System (INIS)

    Sato, Toshinori; Sasamoto, Hiroshi; Ishii, Eiichi; Matsuoka, Toshiyuki; Hayano, Akira; Miyakawa, Kazuya; Fujita, Tomoo; Tanai, Kenji; Nakayama, Masashi; Takeda, Masaki; Yokota, Hideharu; Aoyagi, Kazuhei; Ohno, Hirokazu; Shigeta, Naotaka; Hanamuro, Takahiro; Ito, Hiroaki

    2017-03-01

    The Horonobe Underground Research Laboratory (URL) Project is being pursued by the Japan Atomic Energy Agency (JAEA) to enhance the reliability of relevant disposal technologies through investigations of the deep geological environment within the host sedimentary formations at Horonobe, northern Hokkaido. The project consists of two major research areas, 'Geoscientific Research' and 'R and D on Geological Disposal', and proceeds in three overlapping phases, 'Phase I: Surface-based investigation', 'Phase II: Construction' and 'Phase III: Operation', over a period of 20 years. This report summarizes the results of the Phase II investigations carried out from April 2005 to June 2014 to a depth of 350 m. Integration of work from different disciplines into a 'geosynthesis' ensures that the Phase II goals have been successfully achieved and identifies key issues that need to be addressed in the Phase II investigations. Efforts are made to summarize as many lessons learnt from the Phase II investigations and other technical achievements as possible to form a 'knowledge base' that will reinforce the technical basis for both implementation and the formulation of safety regulations. (author)

  12. Phase III Simplified Integrated Test (SIT) results - Space Station ECLSS testing

    Science.gov (United States)

    Roberts, Barry C.; Carrasquillo, Robyn L.; Dubiel, Melissa Y.; Ogle, Kathryn Y.; Perry, Jay L.; Whitley, Ken M.

    1990-01-01

    During 1989, phase III testing of Space Station Freedom Environmental Control and Life Support Systems (ECLSS) began at Marshall Space Flight Center (MSFC) with the Simplified Integrated Test. This test, conducted at the MSFC Core Module Integration Facility (CMIF), was the first time the four baseline air revitalization subsystems were integrated together. This paper details the results and lessons learned from the phase III SIT. Future plans for testing at the MSFC CMIF are also discussed.

  13. Phase I Project: Fiber Optic Distributed Acoustic Sensing for Periodic Hydraulic Tests

    Energy Technology Data Exchange (ETDEWEB)

    Becker, Matthew

    2017-12-31

    The extraction of heat from hot rock requires circulation of fluid through fracture networks. Because the geometry and connectivity of these fractures determines the efficiency of fluid circulation, many tools are used to characterize fractures before and after development of the reservoir. Under this project, a new tool was developed that allows hydraulic connectivity between geothermal boreholes to be identified. Nanostrain in rock fractures is measured using fiber optic distributed acoustic sensing (DAS). This strain is measured in one borehole in response to periodic pressure pulses induced in another borehole. The strain in the fractures represents hydraulic connectivity between wells. DAS is typically used at frequencies of Hz to kHz, but strain at mHz frequencies were measured for this project. The tool was demonstrated in the laboratory and in the field. In the laboratory, strain in fiber optic cables was measured in response to compression due to oscillating fluid pressure. DAS recorded strains as small as 10 picometer/m in response to 1 cm of water level change. At a fractured crystalline rock field site, strain was measured in boreholes. Fiber-optic cable was mechanically coupled borehole walls using pressured flexible liners. In one borehole 30 m from the oscillating pumping source, pressure and strain were measured simultaneously. The DAS system measured fracture displacement at frequencies of less than 1 mHz (18 min periods) and amplitudes of less than 1 nm, in response to fluid pressure changes of less 20 Pa (2 mm of water). The attenuation and phase shift of the monitored strain signal is indicative of the permeability and storage (compliance) of the fracture network that connects the two wells. The strain response as a function of oscillation frequency is characteristic of the hydraulic structure of the formation. This is the first application of DAS to the measurement of low frequency strain in boreholes. It has enormous potential for monitoring

  14. PHASE II VAULT TESTING OF THE ARGONNE RFID SYSTEM

    Energy Technology Data Exchange (ETDEWEB)

    Willoner, T.; Turlington, R.; Koenig, R.

    2012-06-25

    The U.S. Department of Energy (DOE) (Environmental Management [EM], Office of Packaging and Transportation [EM-45]) Packaging and Certification Program (DOE PCP) has developed a Radio Frequency Identification (RFID) tracking and monitoring system, called ARG-US, for the management of nuclear materials packages during transportation and storage. The performance of the ARG-US RFID equipment and system has been fully tested in two demonstration projects in April 2008 and August 2009. With the strong support of DOE-SR and DOE PCP, a field testing program was completed in Savannah River Site's K-Area Material Storage (KAMS) Facility, an active Category I Plutonium Storage Facility, in 2010. As the next step (Phase II) of continued vault testing for the ARG-US system, the Savannah River Site K Area Material Storage facility has placed the ARG-US RFIDs into the 910B storage vault for operational testing. This latest version (Mark III) of the Argonne RFID system now has the capability to measure radiation dose and dose rate. This paper will report field testing progress of the ARG-US RFID equipment in KAMS, the operability and reliability trend results associated with the applications of the system, and discuss the potential benefits in enhancing safety, security and materials accountability. The purpose of this Phase II K Area test is to verify the accuracy of the radiation monitoring and proper functionality of the ARG-US RFID equipment and system under a realistic environment in the KAMS facility. Deploying the ARG-US RFID system leads to a reduced need for manned surveillance and increased inventory periods by providing real-time access to status and event history traceability, including environmental condition monitoring and radiation monitoring. The successful completion of the testing program will provide field data to support a future development and testing. This will increase Operation efficiency and cost effectiveness for vault operation. As the next step

  15. Phase II Vault Testing of the Argonne RFID System

    International Nuclear Information System (INIS)

    Willoner, T.; Turlington, R.; Koenig, R.

    2012-01-01

    The U.S. Department of Energy (DOE) (Environmental Management (EM), Office of Packaging and Transportation (EM-45)) Packaging and Certification Program (DOE PCP) has developed a Radio Frequency Identification (RFID) tracking and monitoring system, called ARG-US, for the management of nuclear materials packages during transportation and storage. The performance of the ARG-US RFID equipment and system has been fully tested in two demonstration projects in April 2008 and August 2009. With the strong support of DOE-SR and DOE PCP, a field testing program was completed in Savannah River Site's K-Area Material Storage (KAMS) Facility, an active Category I Plutonium Storage Facility, in 2010. As the next step (Phase II) of continued vault testing for the ARG-US system, the Savannah River Site K Area Material Storage facility has placed the ARG-US RFIDs into the 910B storage vault for operational testing. This latest version (Mark III) of the Argonne RFID system now has the capability to measure radiation dose and dose rate. This paper will report field testing progress of the ARG-US RFID equipment in KAMS, the operability and reliability trend results associated with the applications of the system, and discuss the potential benefits in enhancing safety, security and materials accountability. The purpose of this Phase II K Area test is to verify the accuracy of the radiation monitoring and proper functionality of the ARG-US RFID equipment and system under a realistic environment in the KAMS facility. Deploying the ARG-US RFID system leads to a reduced need for manned surveillance and increased inventory periods by providing real-time access to status and event history traceability, including environmental condition monitoring and radiation monitoring. The successful completion of the testing program will provide field data to support a future development and testing. This will increase Operation efficiency and cost effectiveness for vault operation. As the next step (Phase

  16. Brazilian Decimetric Array (BDA) project - Phase II

    Science.gov (United States)

    Faria, C.; Stephany, S.; Sawant, H. S.; Cecatto, J. R.; Fernandes, F. C. R.

    2010-02-01

    The configuration of the second phase of the Brazilian Decimetric Array (BDA), installed at Cachoeira Paulista, Brazil (Longitude 45° 0‧ 20″ W and Latitude 22° 41‧ 19″ S), is a T-shaped array where 21 antennas are being added to existing 5 antennas of the first phase. In the third phase, in each arm of the T array, four more antennas will be added and baselines will be increased to 2.5 × 1.25 km in east-west and south directions, respectively. The antennas will be equally spaced at the distances of 250 meters from the central antenna of the T-array. Also, the frequency range will be increased to 1.2-1.7, 2.8 and 5.6 GHz. The Second phase of the BDA should be operational by the middle of 2010 and will operate in the frequency range of (1.2-1.7) GHz for solar and non solar observations. Here, we present the characteristics of the second phase of the BDA project, details of the array configuration, the u-v coverage, the synthesized beam obtained for the proposed configuration.

  17. CEC project Mirage - Second phase on migration of radionuclides in the geosphere

    International Nuclear Information System (INIS)

    Come, B.

    1989-01-01

    A second phase of the Community coordinated project Mirage (migration of radionuclides in the geosphere) was launched in 1986. The present report brings together reviews of work done in the four research areas of this phase for 1988, and therefore constitues an update of the previous report, ref. EUR 11589. This project is part of the CEC R and D programme on radioactive waste management (1985-89)

  18. Fringe order error in multifrequency fringe projection phase unwrapping: reason and correction.

    Science.gov (United States)

    Zhang, Chunwei; Zhao, Hong; Zhang, Lu

    2015-11-10

    A multifrequency fringe projection phase unwrapping algorithm (MFPPUA) is important to fringe projection profilometry, especially when a discontinuous object is measured. However, a fringe order error (FOE) may occur when MFPPUA is adopted. An FOE will result in error to the unwrapped phase. Although this kind of phase error does not spread, it brings error to the eventual 3D measurement results. Therefore, an FOE or its adverse influence should be obviated. In this paper, reasons for the occurrence of an FOE are theoretically analyzed and experimentally explored. Methods to correct the phase error caused by an FOE are proposed. Experimental results demonstrate that the proposed methods are valid in eliminating the adverse influence of an FOE.

  19. Status of initial phase of site-specific seismic monitoring: Basalt Waste Isolation Project

    International Nuclear Information System (INIS)

    Rohay, A.C.

    1981-01-01

    This report presents the status of the initial phase of site-specific seismic monitoring work conducted under the Basalt Waste Isolation Project. This work is currently organized under two main elements: (1) a portable array; and (2) a baseline data collection array. Progress toward the development of each array is discussed along with an interpretation of preliminary data obtained from the test of a borehole seismometer at potential repository depths. The text is supplemented by nine figures and one table. 9 figs., 1 tab

  20. Cost/schedule performance measurement system utilized on the Fast Flux Test Facility project

    International Nuclear Information System (INIS)

    Brown, R.K.; Frost, R.A.; Zimmerman, F.M.

    1976-01-01

    An Earned Value-Integrated Cost/Schedule Performance Measurement System has been applied to a major nonmilitary nuclear design and construction project. This system is similar to the Department of Defense Cost/Schedule Performance Measurement System. The project is the Fast Flux Test Facility (a Fuels and Materials test reactor for the Liquid Metal Fast Breeder Reactor Program) being built at the Hanford Engineering Development Laboratory, Richland, Washington, by Westinghouse Hanford Company for the U. S. Energy Research and Development Administration. Because the project was well into the construction phase when the Earned Value System was being considered, it was decided that the principles of DOD's Cost/Schedule Control System Criteria would be applied to the extent possible but no major changes in accounting practices or management systems were imposed. Implementation of this system enabled the following questions to be answered: For work performed, how do actual costs compare with the budget for that work. What is the impact of cost and schedule variances at an overall project level composed of different kinds of activities. Without the Earned Value system, these questions could be answered in a qualitative, subjective manner at best

  1. Continuous-Scan Phased Array Measurement Methods for Turbofan Engine Acoustic Testing, Phase I

    Data.gov (United States)

    National Aeronautics and Space Administration — ATA Engineering, Inc., (ATA) proposes an SBIR project to advance the technology readiness level (TRL) of a method for measuring phased array acoustic data for...

  2. Interface control document for tank waste remediation system privatization phase 1 infrastructure support Project W-519

    International Nuclear Information System (INIS)

    Parazin, R.J.

    1998-01-01

    This document describes the functional and physical interfaces between the Tank Waste Remediation System (TWRS) Privatization Phase 1 Infrastructure Project W-519 and the various other projects (i.e., Projects W-314, W-464, W-465, and W-520) supporting Phase 1 that will require the allocation of land in and about the Privatization Phase 1 Site and/or interface with the utilities extended by Project W-519. Project W-519 will identify land use allocations and upgrade/extend several utilities in the 200-East Area into the Privatization Phase 1 Site (formerly the Grout Disposal Compound) in preparation for the Privatization Contractors (PC) to construct treatment facilities. The project will upgrade/extend: Roads, Electrical Power, Raw Water (for process and fire suppression), Potable Water, and Liquid Effluent collection. The replacement of an existing Sanitary Sewage treatment system that may be displaced by Phase 1 site preparation activities may also be included

  3. Virtual Sensor Test Instrumentation, Phase II

    Data.gov (United States)

    National Aeronautics and Space Administration — Mobitrum has started the development of virtual sensor test instrumentation in Phase I for characterization and measurement of ground testing of propulsion systems....

  4. VALIDATION REPORT (PHASE 2) FOR THE FISH SEXUAL DEVELOPMENT TEST FOR THE DETECTION OF ENDOCRINE ACTIVE SUBSTANCES

    DEFF Research Database (Denmark)

    Holbech, Henrik; Kinnberg, Karin Lund; Petersen, Gitte

    This document presents the validation report (phase 2) of the Fish Sexual Development Test (FSDT). The Fish Sexual Development Test (FSDT) covers a life-stage where sexual development is particularly sensitive to perturbation caused by endocrine active chemicals. The chemical exposure lasts...... Guideline on the fish sexual development test to the Working Group of the National Coordinators of the Test Guidelines Programme (WNT). The project was included on the Test Guidelines workplan in 2003, and extensive validation of the test method was carried out until 2009. Two validation studies were...... for about 60 days, at the end of which endpoints of ecological relevance like the sex ratio of the exposed fish is calculated and the biomarker endpoint vitellogenin is measured in individual animals. In 2003, Denmark, on behalf of the European Nordic countries, proposed a new project o develop a Test...

  5. RF Phase Reference Distribution System for the TESLA Technology Based Projects

    CERN Document Server

    Czuba, K; Romaniuk, R S

    2013-01-01

    Since many decades physicists have been building particle accelerators and usually new projects became more advanced, more complicated and larger than predecessors. The importance and complexity of the phase reference distribution systems used in these accelerators have grown significantly during recent years. Amongst the most advanced of currently developed accelerators are projects based on the TESLA technology. These projects require synchronization of many RF devices with accuracy reaching femtosecond levels over kilometre distances. Design of a phase reference distribution system fulfilling such requirements is a challenging scientific task. There are many interdisciplinary problems which must be solved during the system design. Many, usually negligible issues, may became very important in such system. Furthermore, the design of a distribution system on a scale required for the TESLA technology based projects is a new challenge and there is almost no literature sufficiently covering this subject. This th...

  6. ALTERNATE REDUCTANT COLD CAP EVALUATION FURNACE PHASE I TESTING

    Energy Technology Data Exchange (ETDEWEB)

    Johnson, F.; Miller, D.; Zamecnik, J.; Lambert, D.

    2014-04-22

    Savannah River Remediation (SRR) conducted a Systems Engineering Evaluation (SEE) to determine the optimum alternate reductant flowsheet for the Defense Waste Processing Facility (DWPF). Specifically, two proposed flowsheets (nitric–formic–glycolic and nitric–formic–sugar) were evaluated based upon results from preliminary testing. Comparison of the two flowsheets among evaluation criteria indicated a preference towards the nitric–formic–glycolic flowsheet. Further evaluation of this flowsheet eliminated the formic acid1, and as a result, the nitric–glycolic flowsheet was recommended for further testing. Based on the development of a roadmap for the nitric–glycolic acid flowsheet, Waste Solidification Engineering (WS-E) issued a Technical Task Request (TTR) to address flammability issues that may impact the implementation of this flowsheet. Melter testing was requested in order to define the DWPF flammability envelope for the nitric glycolic acid flowsheet. The Savannah River National Laboratory (SRNL) Cold Cap Evaluation Furnace (CEF), a 1/12th scale DWPF melter, was selected by the SRR Alternate Reductant project team as the melter platform for this testing. The overall scope was divided into the following sub-tasks as discussed in the Task Technical and Quality Assurance Plan (TTQAP): Phase I - A nitric–formic acid flowsheet melter test (unbubbled) to baseline the Cold Cap Evaluation Furnace (CEF) cold cap and vapor space data to the benchmark melter flammability models Phase II - A nitric–glycolic acid flowsheet melter test (unbubbled and bubbled) to: o Define new cold cap reactions and global kinetic parameters for the melter flammability models o Quantify off-gas surging potential of the feed o Characterize off-gas condensate for complete organic and inorganic carbon species Prior to startup, a number of improvements and modifications were made to the CEF, including addition of cameras, vessel support temperature measurement, and a heating

  7. Project Protect” intervention. Testing a new approach for HIV prevention

    Directory of Open Access Journals (Sweden)

    Vasylyeva, Tetyana

    2012-07-01

    Full Text Available BACKGROUND. “Project Protect” aims to find highly infectious individuals through screening for acute/recent infection cases and prevent HIV transmission in the risk networks of these cases through contact tracing of these networks` participants, distributing community alerts about risk of acute infection among them and accurate post-test counseling.METHODS. An ongoing pilot phase of the intervention began in Kriviy Rig and Lviv, Ukraine in November, 2011. Participants are recruited through: 1 screening for cases of acute/recent infection at voluntary counseling and testing (VCT sites and in partner organizations (including AIDS-Centers which conduct VCT; 2 visits to drug use venues, chain-referral and contact tracing. Genscreen ultra HIV Ag-Ab “special-tests” are used to detect cases of acute infection. Recent infection is defined as positive test result and preceding negative result within 6 months and/or age younger than 21 years old.RESULTS. In the two cities 173 respondents were recruited to the project, 118 special tests were done. No cases of acute infection and eleven cases of recent infection were found (8 injection drug users (IDUs with preceding negative result within 6 months, 2 IDUs younger than 21 recruited by project team; one non-IDU with preceding negative result within 6 months referred from AIDS-Center. Six recent cases were recruited through screening at VCT sites, 5 others through contact tracing. Psychologists conducted 41 interviews with recent infection cases and their risk networks` members; 176 community alert flyers were distributed to members of risk networks during the interview by psychologist, at the venue by social worker and by participants themselves; 3 drug use venues were visited by project team with concomitant HIV-testing of people present at the venue. CONCLUSIONS. Network tracing seems to be feasible and to help find recently infected people. Further research is needed to tell whether this

  8. Development of phased-array ultrasonic testing probe

    International Nuclear Information System (INIS)

    Kawanami, Seiichi; Kurokawa, Masaaki; Taniguchi, Masaru; Tada, Yoshihisa

    2001-01-01

    Phased-array ultrasonic testing was developed for nondestructive evaluation of power plants. Phased-array UT scans and focuses an ultrasonic beam to inspect areas difficult to inspect by conventional UT. We developed a highly sensitive piezoelectric composite, and designed optimized phased-array UT probes. We are applying our phased-array UT to different areas of power plants. (author)

  9. Individualized Inservice Teacher Education (Project In-Step). Evaluation Report. Phase III.

    Science.gov (United States)

    Thurber, John C.

    This is a report on the third phase of Project IN-STEP, which was intended to develop a viable model for individualized, multi-media in-service teacher education programs. (Phase I and II are reported in ED 033 905, and ED 042 709). The rationale for Phase III was to see if the model could be successfully transferred to an area other than teaching…

  10. State partnership in environmental health and safety phase of Plowshare projects

    Energy Technology Data Exchange (ETDEWEB)

    Kinsman, S [California State Department of Public Health, Berkeley, CA (United States)

    1969-07-01

    When experiments on projects involving Plowshare devices are conceived, the state chosen for the project should be invited to participate in planning the health and safety aspects and be prepared to actively participate in the D-Day phase as well as the post-detonation activity. In California nuclear science technology and competence have preceded the social acceptance and use of nuclear devices for large scale Plowshare projects. However, the environmental surveillance program of the Bureau of Radiological Health in the State Department of Public Health has established an operative program which will be ready and able to function as an active participant or in a support role in environmental health phases of nuclear projects scheduled in the State. A description of our present program will be included in this paper. This will enable the attendees and readers to realize capabilities which will be activated for participation and/or support roles during Plowshare activities in the State or in a neighboring state if the need arises. (author)

  11. State partnership in environmental health and safety phase of Plowshare projects

    International Nuclear Information System (INIS)

    Kinsman, S.

    1969-01-01

    When experiments on projects involving Plowshare devices are conceived, the state chosen for the project should be invited to participate in planning the health and safety aspects and be prepared to actively participate in the D-Day phase as well as the post-detonation activity. In California nuclear science technology and competence have preceded the social acceptance and use of nuclear devices for large scale Plowshare projects. However, the environmental surveillance program of the Bureau of Radiological Health in the State Department of Public Health has established an operative program which will be ready and able to function as an active participant or in a support role in environmental health phases of nuclear projects scheduled in the State. A description of our present program will be included in this paper. This will enable the attendees and readers to realize capabilities which will be activated for participation and/or support roles during Plowshare activities in the State or in a neighboring state if the need arises. (author)

  12. ISP42 (PANDA Tests) - Open Phase Comparison Report

    International Nuclear Information System (INIS)

    2003-05-01

    PANDA is a large-scale facility, which has been constructed at the Paul Scherrer Institute (PSI) for the investigation of both overall dynamic response and the key phenomena of passive containment systems during the long-term heat removal phase for Advanced Light Water Reactors (ALWRs). Using a modular concept with a basic set of cylindrical vessels and connecting piping, the facility can be adapted to simulate different passive containment designs. Following a proposal, the OECD/NEA Committee on the Safety of Nuclear Installations approved, at its meeting on December 3-5, 1997, a new International Standard Problem (ISP) involving a test in the PANDA facility, based on a recommendation from the Principal Working Group 2 (PWG2) on System Behaviour. The main interest for this ISP is code validation in relation to a range of LWR and advanced LWR (ALWR) (mainly) containment issues that have been designated as important and involving thermalhydraulic phenomena. The ISP-PANDA test for defined six phases (A to F) was performed on 21/22 April 1998. Since the first part of ISP-42 was going to be conducted as a 'double- blind' or 'blind' exercise, the experimental data was locked. The 'blind' phase calculational results compared to experimental data are presented in the report entitled 'ISP-42 (PANDA Tests ) Blind Phase Comparison'. In the second part, the 'open' exercise has been conducted by providing the ISP-42 PANDA test data to the participants and by performing post-test analysis. The results of the 'open' phase are presented in the present report. 'Open' phase submissions, comparisons, and analyses for ISP-42 are based on the outcome of the results presented in the 'blind' phase report of ISP-42. The experimental data was distributed to all ISP-42 participants for their post-test calculations, 20 June 2000. 'Open' phase analyses of some of the ISP-42 participants, were completely received by the end of January 2001. There were 27 new submissions for different phases

  13. Alternate Reductant Cold Cap Evaluation Furnace Phase II Testing

    Energy Technology Data Exchange (ETDEWEB)

    Johnson, F. C. [Savannah River Site (SRS), Aiken, SC (United States). Savannah River National Lab. (SRNL); Stone, M. E. [Savannah River Site (SRS), Aiken, SC (United States). Savannah River National Lab. (SRNL); Miller, D. H. [Savannah River Site (SRS), Aiken, SC (United States). Savannah River National Lab. (SRNL)

    2014-09-03

    Savannah River Remediation (SRR) conducted a Systems Engineering Evaluation (SEE) to determine the optimum alternate reductant flowsheet for the Defense Waste Processing Facility (DWPF). Specifically, two proposed flowsheets (nitric–formic–glycolic and nitric–formic–sugar) were evaluated based upon results from preliminary testing. Comparison of the two flowsheets among evaluation criteria indicated a preference towards the nitric–formic–glycolic flowsheet. Further research and development of this flowsheet eliminated the formic acid, and as a result, the nitric–glycolic flowsheet was recommended for further testing. Based on the development of a roadmap for the nitric–glycolic acid flowsheet, Waste Solidification Engineering (WS-E) issued a Technical Task Request (TTR) to address flammability issues that may impact the implementation of this flowsheet. Melter testing was requested in order to define the DWPF flammability envelope for the nitric-glycolic acid flowsheet. The Savannah River National Laboratory (SRNL) Cold Cap Evaluation Furnace (CEF), a 1/12th scale DWPF melter, was selected by the SRR Alternate Reductant project team as the melter platform for this testing. The overall scope was divided into the following sub-tasks as discussed in the Task Technical and Quality Assurance Plan (TTQAP): Phase I - A nitric–formic acid flowsheet melter test (unbubbled) to baseline the CEF cold cap and vapor space data to the benchmark melter flammability models; Phase II - A nitric–glycolic acid flowsheet melter test (unbubbled and bubbled) to: Define new cold cap reactions and global kinetic parameters in support of the melter flammability model development; Quantify off-gas surging potential of the feed; Characterize off-gas condensate for complete organic and inorganic carbon species. After charging the CEF with cullet from Phase I CEF testing, the melter was slurry-fed with glycolic flowsheet based SB6-Frit 418 melter feed at 36% waste

  14. Test and evaluation plan for Project W-314 tank farm restoration and safe operations

    International Nuclear Information System (INIS)

    Hays, W.H.

    1998-01-01

    The ''Tank Farm Restoration and Safe Operations'' (TFRSO), Project W-314 will restore and/or upgrade existing Hanford Tank Farm facilities and systems to ensure that the Tank Farm infrastructure will be able to support near term TWRS Privatization's waste feed delivery and disposal system and continue safe management of tank waste. The capital improvements provided by this project will increase the margin of safety for Tank Farms operations, and will aid in aligning affected Tank Farm systems with compliance requirements from applicable state, Federal, and local regulations. Secondary benefits will be realized subsequent to project completion in the form of reduced equipment down-time, reduced health and safety risks to workers, reduced operating and maintenance costs, and minimization of radioactive and/or hazardous material releases to the environment. The original regulatory (e.g., Executive Orders, WACS, CFRS, permit requirements, required engineering standards, etc.) and institutional (e.g., DOE Orders, Hanford procedures, etc.) requirements for Project W-314 were extracted from the TWRS S/RIDs during the development of the Functions and Requirements (F and Rs). The entire family of requirements were then validated for TWRS and Project W-314. This information was contained in the RDD-100 database and used to establish the original CDR. The Project Hanford Management Contract (PHMC) team recognizes that safety, quality, and cost effectiveness in the Test and Evaluation (T and E) program is achieved through a planned systematic approach to T and E activities. It is to this end that the Test and Evaluation Plan (TEP) is created. The TEP for the TFRSO Project, was developed based on the guidance in HNF-IP-0842, and the Good Practice Guide GPG-FM-005, ''Test and Evaluation,'' which is derived from DOE Order 430.1, ''Life Cycle Asset Management.'' It describes the Test and Evaluation program for the TFRSO project starting with the definitive design phase and ending

  15. Project inspection using mobile technology - phase II : assessing the impacts of mobile technology on project inspection.

    Science.gov (United States)

    2015-01-01

    As mobile technology becomes widely available and affordable, transportation agencies can use this : technology to streamline operations involved within project inspection. This research, conducted in two : phases, identified opportunities for proces...

  16. Code of Conduct for wind-power projects - Phases 1 and 2

    International Nuclear Information System (INIS)

    Strub, P.; Ziegler, Ch.

    2008-08-01

    This paper discusses the results of the first two phases of a project concerning wind-power projects. The paper deals with the results of a system analysis, takes a look at lessons learned and presents an appraisal of existing instruments. A system-analysis of wind-power projects is presented with emphasis on social factors and the role of stakeholders. The success factors concerning social acceptance of wind-power projects and their special characteristics are discussed. Lessons learned are examined. Instruments for the sustainable implementation of projects are looked at, in particular with a focus on social acceptance

  17. Product-Improvement Test (Phase II), Jetcal Tester, Model H119A.

    Science.gov (United States)

    1969-03-05

    Ao—A0 51 113 ARMY AVIATION ‘Cs’ BOARD FORT tUCKER ALA — P*OOUCTeII ROVEMCNT TEST ( FHAS ~ I I ) . JETCAL TESTER, MODEL M119A~~’ETC(U) MAR S9...Phase i i ) , Jetcal Tester , Model H 119A , USATECOM Project No. 4-6-5011-03 b . No fur ther consideration be given to the TEMPCAL heater probe as a...essen t i a l component of the Jetcal Tester. e. The service manual instruct ions for con t inu i ty te s t ing of EG1 thermocouples be revised to

  18. Strip reduction testing of lubricants developed during ENFORM project

    DEFF Research Database (Denmark)

    Gazvoda, S.; Andreasen, Jan Lasson; Olsson, David Dam

    Strip reduction testing of lubricants developed during ENFORM project. Experiments were conducted with the strip reduction test [1] in order to classify experimental lubricants, developed during concerned project. One reference lubricant was used during testing....

  19. Recovery efficiency test project, Phase 2 activity report. Volume 2, Final report

    Energy Technology Data Exchange (ETDEWEB)

    Overbey, W.K. Jr.; Salamy, S.P.; Locke, C.D.

    1989-02-01

    The Recovery Efficiency Test well project addressed a number of technical issues. The primary objective was to determine the increased efficiency of gas recovery of a long horizontal wellbore over that of a vertical wellbore and, more specifically, what improvements can be expected from inducing multiple hydraulic fractures from such a wellbore. This volume contains appendices for: (1) supporting material and procedures for ``data frac`` stimulation of zone 6 using nitrogen and nitrogen foam; (2) supporting material and procedures for stimulation no. 1 nitrogen gas frac on zone no. 1; (3) supporting material and procedures for stimulation no. 2 in zone no. 1 using liquid CO{sub 2}; (4) supporting material and procedures for frac no. 3 on zone no.1 using nitrogen foam and proppant; (5) supporting material and procedures for stimulation no. 4 in zones 2--3 and 4 using nitrogen foam and proppant; (6) supporting materials and procedures for stimulation no. 5 in zones 5 and 8; and (7) fracture diagnostics reports and supporting materials.

  20. Phase retrieval with the reverse projection method in the presence of object's scattering

    International Nuclear Information System (INIS)

    Wang, Zhili; Gao, Kun; Wang, Dajiang

    2017-01-01

    X-ray grating interferometry can provide substantially increased contrast over traditional attenuation-based techniques in biomedical applications, and therefore novel and complementary information. Recently, special attention has been paid to quantitative phase retrieval in X-ray grating interferometry, which is mandatory to perform phase tomography, to achieve material identification, etc. An innovative approach, dubbed “Reverse Projection” (RP), has been developed for quantitative phase retrieval. The RP method abandons grating scanning completely, and is thus advantageous in terms of higher efficiency and reduced radiation damage. Therefore, it is expected that this novel method would find its potential in preclinical and clinical implementations. Strictly speaking, the reverse projection method is applicable for objects exhibiting only absorption and refraction. In this contribution, we discuss the phase retrieval with the reverse projection method for general objects with absorption, refraction and scattering simultaneously. Especially, we investigate the influence of the object's scattering on the retrieved refraction signal. Both theoretical analysis and numerical experiments are performed. The results show that the retrieved refraction signal is the product of object's refraction and scattering signals for small values. In the case of a strong scattering, the reverse projection method cannot provide reliable phase retrieval. Those presented results will guide the use of the reverse projection method for future practical applications, and help to explain some possible artifacts in the retrieved images and/or reconstructed slices. - Highlights: • Accurate phase retrieval by the reverse projection method without object's scattering. • Retrieved refraction signal contaminated by the object's scattering. • Refraction signal underestimated by the reverse projection method. • Guide the use of the reverse projection method for

  1. Crawler Acquisition and Testing Demonstration Project Management Plan

    International Nuclear Information System (INIS)

    DEFIGH-PRICE, C.

    2000-01-01

    If the crawler based retrieval system is selected, this project management plan identifies the path forward for acquiring a crawler/track pump waste retrieval system, and completing sufficient testing to support deploying the crawler for as part of a retrieval technology demonstration for Tank 241-C-104. In the balance of the document, these activities will be referred to as the Crawler Acquisition and Testing Demonstration. During recent Tri-Party Agreement negotiations, TPA milestones were proposed for a sludge/hard heel waste retrieval demonstration in tank C-104. Specifically one of the proposed milestones requires completion of a cold demonstration of sufficient scale to support final design and testing of the equipment (M-45-03G) by 6/30/2004. A crawler-based retrieval system was one of the two options evaluated during the pre-conceptual engineering for C-104 retrieval (RPP-6843 Rev. 0). The alternative technology procurement initiated by the Hanford Tanks Initiative (HTI) project, combined with the pre-conceptual engineering for C-104 retrieval provide an opportunity to achieve compliance with the proposed TPA milestone M-45-03H. This Crawler Acquisition and Testing Demonstration project management plan identifies the plans, organizational interfaces and responsibilities, management control systems, reporting systems, timeline and requirements for the acquisition and testing of the crawler based retrieval system. This project management plan is complimentary to and supportive of the Project Management Plan for Retrieval of C-104 (RPP-6557). This project management plan focuses on utilizing and completing the efforts initiated under the Hanford Tanks Initiative (HTI) to acquire and cold test a commercial crawler based retrieval system. The crawler-based retrieval system will be purchased on a schedule to support design of the waste retrieval from tank C-104 (project W-523) and to meet the requirement of proposed TPA milestone M-45-03H. This Crawler

  2. W.A. Parish Post-Combustion CO{sub 2} Capture and Sequestration Project Phase 1 Definition

    Energy Technology Data Exchange (ETDEWEB)

    Armpriester, Anthony; Smith, Roger; Scheriffius, Jeff; Smyth, Rebecca; Istre, Michael

    2014-02-01

    For a secure and sustainable energy future, the United States (U.S.) must reduce its dependence on imported oil and reduce its emissions of carbon dioxide (CO{sub 2}) and other greenhouse gases (GHGs). To meet these strategic challenges, the U.S. wiU have to create fundamentally new technologies with performance levels far beyond what is now possible. Developing advanced post-combustion clean coal technologies for capturing CO{sub 2} from existing coal-fired power plants can play a major role in the country's transition to a sustainable energy future, especially when coupled with CO{sub 2}-enhanced oil recovery (CO{sub 2}-EOR). Pursuant to these goals, NRG Energy, Inc. (NRG) submitted an application and entered into a cost-shared collaboration with the U.S. Department of Energy (DOE) under Round 3 of the Clean Coal Power Initiative (CCPI) to advance low-emission coal technologies. The objective of the NRG W A Parish Post-Combustion CO{sub 2} Capture and Sequestration Demonstration Project is to establish the technical feasibility and economic viability of post-combustion CO{sub 2} capture using flue gas from an existing pulverized coal-fired boiler integrated with geologic sequestration via an enhanced oil recovery (EOR) process. To achieve these objectives, the project will be executed in three phases. Each phase represents a distinct aspect of the project execution. The project phases are: • Phase I. Project Definition/Front-End Engineering Design (FEED) • Phase ll. Detailed Engineering, Procurement & Construction • Phase III. Demonstration and Monitoring The purpose of Phase I is to develop the project in sufficient detail to facilitate the decision-making process in progressing to the next stage of project delivery. Phase n. This report provides a complete summary of the FEED study effort, including pertinent project background information, the scope of facilities covered, decisions, challenges, and considerations made regarding configuration and

  3. Conducting Closed Habitation Experiments: Experience from the Lunar Mars Life Support Test Project

    Science.gov (United States)

    Barta, Daniel J.; Edeen, Marybeth A.; Henninger, Donald L.

    2006-01-01

    The Lunar-Mars Life Support Test Project (LMLSTP) was conducted from 1995 through 1997 at the National Aeronautics and Space Administration s (NASA) Johnson Space Center (JSC) to demonstrate increasingly longer duration operation of integrated, closed-loop life support systems that employed biological and physicochemical techniques for water recycling, waste processing, air revitalization, thermal control, and food production. An analog environment for long-duration human space travel, the conditions of isolation and confinement also enabled studies of human factors, medical sciences (both physiology and psychology) and crew training. Four tests were conducted, Phases I, II, IIa and III, with durations of 15, 30, 60 and 91 days, respectively. The first phase focused on biological air regeneration, using wheat to generate enough oxygen for one experimental subject. The systems demonstrated in the later phases were increasingly complex and interdependent, and provided life support for four crew members. The tests were conducted using two human-rated, atmospherically-closed test chambers, the Variable Pressure Growth Chamber (VPGC) and the Integrated Life Support Systems Test Facility (ILSSTF). Systems included test articles (the life support hardware under evaluation), human accommodations (living quarters, kitchen, exercise equipment, etc.) and facility systems (emergency matrix system, power, cooling, etc.). The test team was managed by a lead engineer and a test director, and included test article engineers responsible for specific systems, subsystems or test articles, test conductors, facility engineers, chamber operators and engineering technicians, medical and safety officers, and science experimenters. A crew selection committee, comprised of psychologists, engineers and managers involved in the test, evaluated male and female volunteers who applied to be test subjects. Selection was based on the skills mix anticipated for each particular test, and utilized

  4. Project W-320, operational test procedure OTP-320-003 test report

    International Nuclear Information System (INIS)

    Bevins, R.R.

    1998-01-01

    This report documents and summarizes the results of OTP-320-003 Project W-320 Operational Testing of the WRSS Supernate Transfer System. Project W-320 Operational Test OTP-320-003 was performed to verify components of the Waste Retrieval Sluicing System (WRSS) supernate transfer system functioned as designed following construction completion and turnover to operations. All equipment operation was performed by Tank Farms Operations personnel following the operational test procedure and referenced operating procedures. Supernate Transfer line Flushing System Testing was completed over the course of approximately 4 weeks as tank farm conditions and configuration, equipment availability, and operations resources allowed. All testing was performed with the 702-AZ ventilation system and the 296-P-16 ventilation systems in operation. Test procedure OTP-320-003 required two revisions during testing to incorporate Procedure Changes Authorizations (PCAs) necessary to facilitate testing. Various sections of testing are documented on each procedure revision. The completed test procedure is included as Attachment A. Exception Reports generated during the course of testing are included as Attachment B

  5. Advanced Petroleum-Based Fuels -- Diesel Emissions Control Project (APBF-DEC): Lubricants Project, Phase 2 Final Report

    Energy Technology Data Exchange (ETDEWEB)

    2006-06-01

    This report summarizes the results of the second phase of a lubricants project, which investigated the impact of engine oil formulation on diesel vehicle emissions and the performance of a nitrogen oxide adsorber catalyst (NAC).

  6. Estuary 2100 Project, Phase 2: Building Partnerships for Resilient Watersheds

    Science.gov (United States)

    Information about the SFBWQP Estuary 2100 Project, Phase 2: Building Partnerships for Resilient Watersheds, part of an EPA competitive grant program to improve SF Bay water quality focused on restoring impaired waters and enhancing aquat

  7. Interest groups, the Lesotho Highlands Water Project Phase 1

    African Journals Online (AJOL)

    interest groups can bring about changes in the water policy arena. ... Lesotho Highlands Water Project Phase 1 as a case study. ... attempts to influence public policy and their representation ... ties concern the relations between state actors and non-state ..... 'bears responsibility here [LHWP], since it is the sponsor of.

  8. Final Report for the ADMX Phase 2a Project at the University of Washington

    International Nuclear Information System (INIS)

    Rosenberg, Leslie J.

    2015-01-01

    This is a final report of the ADMX (Axion Dark Matter eXperiment) Phase 2a program. This program is a project allowing for a sensitive axion dark-matter search at higher axion masses. The Phase 2a program also prepares the project for lower temperature anticipated in later operations. The Phase 2a program includes sensitive data-taking operations at two cavity modes, TM010 and TM020, allowing for faster data-taking operations and extending the search to higher and plausible dark-matter axion masses.

  9. ILAW Glass Testing for Disposal at IDF: Phase 1 Testing

    Energy Technology Data Exchange (ETDEWEB)

    Papathanassiu, Adonia [The Catholic Univ. of America, Washington, DC (United States). Virteous State Lab.; Muller, Isabelle S. [The Catholic Univ. of America, Washington, DC (United States). Virteous State Lab.; Brandys, Marek [The Catholic Univ. of America, Washington, DC (United States). Virteous State Lab.; Gilbo, Konstantin [The Catholic Univ. of America, Washington, DC (United States). Virteous State Lab.; Barkatt, Aaron [The Catholic Univ. of America, Washington, DC (United States). Virteous State Lab.; Joseph, Innocent [EnergySolutions Federal EPC, Inc., Columbia, MD (United States); The Catholic Univ. of America, Washington, DC (United States). Virteous State Lab.; Pegg, Ian L. [The Catholic Univ. of America, Washington, DC (United States). Virteous State Lab.; Brown, Elvie E. [Washington River Protection Solutions, LLC, Richland, WA (United States); Swanberg, David J. [Washington River Protection Solutions, LLC, Richland, WA (United States)

    2011-04-11

    This document reports the results of the testing of phase 1 ORP LAW (low activity waste) glasses, also identified as enhanced LAW glasses. Testing involved are SPFT (Single Pass Flow Through), VHT (Vapor Hydration Test), and PCT (Product Consistency Test), along with the analytical tests (XRD and SEM-EDS). This report contains the data of the high waste loading ORP LAW glasses that will be used for the performance assessment of the IDF (Integrated Disposal Facility).

  10. ILAW Glass Testing for Disposal at IDF: Phase 1 Testing

    International Nuclear Information System (INIS)

    Papathanassiu, Adonia; Swanberg, David J.

    2011-01-01

    This document reports the results of the testing of phase 1 ORP LAW (low activity waste) glasses, also identified as enhanced LAW glasses. Testing involved are SPFT (Single Pass Flow Through), VHT (Vapor Hydration Test), and PCT (Product Consistency Test), along with the analytical tests (XRD and SEM-EDS). This report contains the data of the high waste loading ORP LAW glasses that will be used for the performance assessment of the IDF (Integrated Disposal Facility).

  11. Summary of ROSA-4 LSTF first phase test program and station blackout (TMLB) test results

    International Nuclear Information System (INIS)

    Tasaka, K.; Kukita, Y.; Anoda, Y.

    1990-01-01

    This paper summarizes major test results obtained at the ROSA-4 Large Scale Test Facility (LSTF) during the first phase of the test program. The results from a station blackout (TMLB) test conducted at the end of the first-phase program are described in some detail. The LSTF is an integral test facility being operated by the Japan Atomic Energy Research Institute for simulation of pressurized water reactor (PWR) thermal-hydraulic responses during small-break loss-of-coolant accidents (SBLOCAs) and operational/abnormal transients. It is a 1/48 volumetrically scaled, full-height, full-pressure simulator of a Westinghouse-type 4-loop PWR. The facility includes two symmetric primary loops each one containing an active inverted-U tube steam generator and an active reactor coolant pump. The loop horizontal legs are sized to conserve the scaled (1/24) volumes as well as the length to the square root of the diameter ratio in order to simulate the two-phase flow regime transitions. The primary objective of the LSTF first-phase program was to define the fundamental PWR thermal-hydraulic responses during SBLOCAs and transients. Most of the tests were conducted with simulated component/operator failures, including unavailability of the high pressure injection system and auxiliary feedwater system, as well as operator failure to take corrective actions. The forty-two first phase tests included twenty-nine SBLOCA tests conducted mainly for cold leg breaks, three abnormal transient tests and ten natural circulation tests. Attempts were made in several of the SBLOCA tests to simulate the plant recovery procedures as well as candidate accident management measures for prevention of high-pressure core melt situation. The natural circulation tests simulated the single-phase and two-phase natural circulation as well as reflux condensation behavior in the primary loops in steady or quasi-steady states

  12. The third phase of the OECD/NEA TDB project: TDB III

    International Nuclear Information System (INIS)

    Mompean, F.J.; Illemassene, M.; Perrone, J.

    2005-01-01

    In 2003 with a foreseen duration of four years. The main objective of this new phase is to extend the existing critically reviewed database for elements of relevance in radioactive waste management, paying attention to the needs of the various national programmes. Following the decision by the Project Management Board (integrated by representatives of 16 organisations with responsibilities in radioactive waste management in 12 OECD member countries) the elements contemplated in this new phase are Th, Sn and Fe, with a higher priority being allocated to inorganic species and compounds. In addition to the corresponding review teams for these elements, an additional expert team has been constituted to prepare guidelines for the evaluation of thermodynamic data for solid solutions. As was the case in TDB Phase II, the basic project review methodology remains unaltered in TDB III. The Figure illustrates the relationship between the various TDB bodies, with an International Organisation, the OECD NEA, acting as Project Coordinator and linking the independent scientific teams and the project governing bodies. This organizational paradigm has proven successful with the recent completion of the five Phase II Reviews (Update, Ni, Se, Zr and Organic Ligands). The review and expert team activities were started in 2004 (except for Fe, being started in 2005) following an initiation stage. This preliminary stage was designed in order to tailor the team compositions to the existing literature for each element. The first reviews stemming from TDB III are scheduled to appear in published form in 2007. The successful completion of these objectives will add three further reports to the current series of nine volumes (dealing with the chemical thermodynamics of U, Np, Pu, Am, Tc, Ni, Se, Zr and compounds and complexes of these elements with oxalate, citrate, EDTA and isa). (authors)

  13. Hydrogeological characterization on surface-based investigation phase in the Mizunami underground research laboratory project, in Japan

    International Nuclear Information System (INIS)

    Saegusa, Hiromitsu; Onoe, Hironori; Takeuchi, Shinji; Takeuchi, Ryuji; Ohyama, Takuya

    2007-01-01

    The Mizunami Underground Research Laboratory (MIU) project is being carried out by Japan Atomic Energy Agency in the Cretaceous Toki granite in the Tono area, central Japan. The MIU project is a purpose-built generic underground research laboratory project that is planned for a broad scientific study of the deep geological environment as a basis of research and development for geological disposal of nuclear wastes. One of the main goals of the MIU project is to establish comprehensive techniques for investigation, analysis, and assessment of the deep geological environment. The MIU project has three overlapping phases: Surface-based Investigation (Phase I), Construction (Phase II) and Operation (Phase III). Hydrogeological investigations using a stepwise process in Phase I have been carried out in order to obtain information on important properties such as, location of water conducting features, hydraulic conductivity and so on. Hydrogeological modeling and groundwater flow simulations in Phase I have been carried out in order to synthesize these investigation results, to evaluate the uncertainty of the hydrogeological model and to identify the main issues for further investigations. Using the stepwise hydrogeological characterization approach and combining the investigation with modeling and simulation, understanding of the hydrogeological environment has been progressively improved. (authors)

  14. Wind Turbine Drivetrain Condition Monitoring During GRC Phase 1 and Phase 2 Testing

    Energy Technology Data Exchange (ETDEWEB)

    Sheng, S.; Link, H.; LaCava, W.; van Dam, J.; McNiff, B.; Veers, P.; Keller, J.; Butterfield, S.; Oyague, F.

    2011-10-01

    This report will present the wind turbine drivetrain condition monitoring (CM) research conducted under the phase 1 and phase 2 Gearbox Reliability Collaborative (GRC) tests. The rationale and approach for this drivetrain CM research, investigated CM systems, test configuration and results, and a discussion on challenges in wind turbine drivetrain CM and future research and development areas, will be presented.

  15. Operational test report, integrated system test (ventilation upgrade)

    International Nuclear Information System (INIS)

    HARTY, W.M.

    1999-01-01

    Operational Final Test Report for Integrated Systems, Project W-030 (Phase 2 test, RECIRC and HIGH-HEAT Modes). Project W-030 provides a ventilation upgrade for the four Aging Waste Facility tanks, including upgraded vapor space cooling and filtered venting of tanks AY101, AY102, AZ101, AZ102

  16. Operational test report integrated system test (ventilation upgrade)

    Energy Technology Data Exchange (ETDEWEB)

    HARTY, W.M.

    1999-10-05

    Operational Final Test Report for Integrated Systems, Project W-030 (Phase 2 test, RECIRC and HIGH-HEAT Modes). Project W-030 provides a ventilation upgrade for the four Aging Waste Facility tanks, including upgraded vapor space cooling and filtered venting of tanks AY101, Ay102, AZ101, AZ102.

  17. Improving decision making in the early phases of configuration projects

    DEFF Research Database (Denmark)

    Mortensen, Niels Henrik; Harlou, Ulf; Haug, Anders

    2008-01-01

    During the early phases of configuration projects very important decisions are made which will heavily influence the performance of the company, benefits in different functional areas (production, sales, purchase, product development, service etc), maintenance of the configuration system...

  18. Improving decision making in the early phases of configuration projects

    DEFF Research Database (Denmark)

    Mortensen, Niels Henrik; Hvam, Lars; Harlou, Ulf

    2011-01-01

    During the early phases of configuration projects very important decisions are made which will heavily influence the performance of the company, benefits in different functional areas (production, sales, purchase, product development, service etc), maintenance of the configuration system...

  19. The International intraval project. Phase 1, test case 13: Experimental study of brine transport in porous media

    International Nuclear Information System (INIS)

    Glasbergen, P.

    1992-01-01

    INTRAVAL is an international coordinated research program for predicting the potential radionuclide migration in the geosphere with the use of mathematical models. Such models are used to help assess the long-term safety of radioactive waste disposal systems. This report describes the findings of the project teams involved in test case 13 of INTRAVAL Phase 1. The test case is based on laboratory experiments dealing with flow and dispersion of brine in a porous medium. The purpose of these experiments was twofold : (i) to investigate some of the relevant processes in brine transport in porous media, and (ii) to provide sets of data to be used for (partial) validation of transport models. The experiments were carried out in a column packed with glass beads of diameter 0.40 to 0.52 mm. Salt water was injected through nine holes at the bottom and withdrawn through nine holes at the top. Initially a low salt concentration was used which was then displaced with higher concentrated salt water. The salt mass-fraction was detected using an array of electrodes such that breakthrough curves were obtained at five different levels in the column. The report reviews a number of conceptual models and the corresponding numerical codes employed by different modelling teams. The experiments on one- and two-dimensional flow and transport were simulated by various groups. The question underlying the experiments, namely the applicability of Fick's laws over the whole range of salt concentration, could be addressed satisfactorily. All models could simulate low-concentration experiment using a dispersivity value of 0.8 mm to 1.00 mm. However, using the same dispersivity value, it was not possible to simulate high concentration experiments. Another question intended to be studied by the experiments was the validity of Darcy's law at high concentrations. Two-dimensional experiments were carried out for this purpose. In practice, calculations were hampered by extremely high demand on

  20. Psychometry and Pescatori projective test in coloproctological patients.

    Science.gov (United States)

    Caetano, Ana Célia; Oliveira, Dinis; Gomes, Zaida; Mesquita, Edgar; Rolanda, Carla

    2017-01-01

    Psychological assessment is not commonly performed nor easily accepted by coloproctological patients. Our aim was to evaluate the psychological component of coloproctological disorders using uncommon tools. The 21-Item Depression Anxiety and Stress Scale and the Pescatori projective test were applied to coloproctological outpatients of the Gastroenterology Department of our hospital as well as to healthy volunteers. Seventy patients (median age 47 years, 22 male) divided in 4 groups (functional constipation, constipated irritable bowel syndrome, benign anorectal disease and perianal Crohn's disease) and 52 healthy volunteers (age 45 years, 18 male) completed the tests. Proctological patients showed higher scores of depression (Pprojective test (P=0.012). A weak association between the projective test and the depression subscale was found (P=0.05). Proctological patients had higher scores of depression, anxiety and stress and lower scores in the Pescatori projective test compared to healthy controls.

  1. European supercritical water cooled reactor (HPLWR Phase 2 project)

    International Nuclear Information System (INIS)

    Schulenberg, Thomas; Starflinger, Joerg; Marsault, Philippe; Bittermann, Dietmar; Maraczy, Czaba; Laurien, Eckart; Lycklama, Jan Aiso; Anglart, Henryk; Andreani, Michele; Ruzickova, Mariana; Heikinheimo, Liisa

    2010-01-01

    The High Performance Light Water Reactor (HPLWR), how the European Supercritical Water Cooled Reactor is called, is a pressure vessel type reactor operated with supercritical water at 25 MPa feedwater pressure and 500 deg C maximum core outlet temperature. It is designed and analyzed by a European consortium of 13 partners from 8 Euratom member states in the second phase of the HPLWR project. Most emphasis has been laid on a core with a thermal neutron spectrum, consisting of small, housed fuel assemblies with 40 fuel pins each and a central water box to improve the neutron moderation despite the low coolant density. Peak cladding temperatures of the fuel rods have been minimized by heating up the coolant in three steps with intermediate coolant mixing. The innovative core design with upward and downward flow through its assemblies has been studied with neutronic, thermal-hydraulic and stress analyses and has been reviewed carefully in a mid-term assessment. The containment design with its safety and residual heat removal systems is based on the latest boiling water reactor concept, but with different passive high pressure coolant injection systems to cause a forced convection through the core. The design concept of the steam cycle is indicating the envisaged efficiency increase to around 44%. Moreover, it provides the constraints to design the components of the balance of the plant. The project is accompanied by numerical studies of heat transfer of supercritical water in fuel assemblies and by material tests of candidate cladding alloys, performed by the consortium and supported by additional tests of the Joint Research Centre of the European Commission. An overview of results achieved up to now, given in this paper, is illustrating the latest scientific and technological advances. (author)

  2. Phase 2 of the Nea TDB project and some lessons learned from the use of phase 1 data

    International Nuclear Information System (INIS)

    Spahiu, K.

    2002-01-01

    As the five initial reviews of the TDB Project come to their conclusion, the negotiations for an independently funded continuation of the TDB Project through two meetings of an ad hoc group were completed in late 1997. The participating organisations are ANSTO (Australia), NIRAS/ONDRAF (Belgium), RAWRA (Czech Republic), POSIVA (Finland), ANDRA and IPSN (France), FZK (Germany), JNC/PNC (Japan), ENRESA (Spain), SKB and SKI (Sweden), HSK, NAGRA and PSI (Switzerland), BNFL and NIREX (UK) and the DOE (USA). This project is referred to as the TDB Phase II Project, or simply TDB II. The following new reviews will be performed within this project: - an update of the existing U/Am/Tc/Np/Pu reviews (one review team for all elements); - the inorganic chemistry of Ni; - the inorganic chemistry of Se; - the complexation of selected simple organic ligands (ISA, EDTA, citrate and oxalate) with U, Am, Tc, Np, Pu, Ni, Se, Zr and some selected competing cations; the inorganic chemistry of Zr. These review areas have been decided on taking into account the toxicity, mobility, radioactivity and half-lives of the commonly occurring nuclides in radioactive waste, as well as the particular areas of interest of the funding organisations. To avoid the delays that have plagued Phase I, the organisation of the TDB Project has been restructured, and the funding provided has been calculated to cover all necessary expenses for the project. (author)

  3. [Using projective tests in forensic psychiatry may lead to wrong conclusions. Only empirically tested tests should be used].

    Science.gov (United States)

    Trygg, L; Dåderman, A M; Wiklund, N; Meurling, A W; Lindgren, M; Lidberg, L; Levander, S

    2001-06-27

    The use of projective and psychometric psychological tests at the Department of Forensic Psychiatry in Stockholm (Huddinge), Sweden, was studied for a population of 60 men, including many patients with neuropsychological disabilities and multiple psychiatric disorders. The results showed that the use of projective tests like Rorschach, Object Relations Test, and House-Tree-Person was more frequent than the use of objective psychometric tests. Neuropsychological test batteries like the Halstead-Reitan Neuropsychological Test Battery or Luria-Nebraska Neuropsychological Battery were not used. The majority of patients were, however, assessed by intelligence scales like the WAIS-R. The questionable reliability and validity of the projective tests, and the risk of subjective interpretations, raise a problem when used in a forensic setting, since the courts' decisions about a sentence to prison or psychiatric care is based on the forensic psychiatric assessment. The use of objective psychometric neuropsychological tests and personality tests is recommended.

  4. Test phase plan for the Waste Isolation Pilot Plant

    International Nuclear Information System (INIS)

    1993-03-01

    The US Department of Energy (DOE) has prepared this Test Phase Plan for the Waste Isolation Pilot Plant to satisfy the requirements of Public Law 102-579, the Waste Isolation Pilot Plant (WIPP) Land Withdrawal Act (LWA). The Act provides seven months after its enactment for the DOE to submit this Plan to the Environmental Protection Agency (EPA) for review. A potential geologic repository for transuranic wastes, including transuranic mixed wastes, generated in national-defense activities, the WIPP is being constructed in southeastern New Mexico. Because these wastes remain radioactive and chemically hazardous for a very long time, the WIPP must provide safe disposal for thousands of years. The DOE is developing the facility in phases. Surface facilities for receiving waste have been built and considerable underground excavations (2150 feet below the surface) that are appropriate for in-situ testing, have been completed. Additional excavations will be completed when they are required for waste disposal. The next step is to conduct a test phase. The purpose of the test phase is to develop pertinent information and assess whether the disposal of transuranic waste and transuranic mixed waste in the planned WIPP repository can be conducted in compliance with the environmental standards for disposal and with the Solid Waste Disposal Act (SWDA) (as amended by RCRA, 42 USC. 6901 et. seq.). The test phase includes laboratory experiments and underground tests using contact-handled transuranic waste. Waste-related tests at WIPP will be limited to contact-handled transuranic and simulated wastes since the LWA prohibits the transport to or emplacement of remote-handled transuranic waste at WIPP during the test phase

  5. Project W320 52-inch diameter equipment container load test: Test report

    International Nuclear Information System (INIS)

    Bellomy, J.R.

    1995-01-01

    This test report summarizes testing activities and documents the results of the load tests performed on-site and off-site to structural qualify the 52-inch equipment containers designed and fabricated under Project W-320

  6. I. Final Report for DOE SBIR Phase I Project DE-SC0013795 Final Report for DOE SBIR Phase I Project DE-SC0013795 Microtron-based Compact, Portable Gamma-Ray Source

    Energy Technology Data Exchange (ETDEWEB)

    Abrams, Robert J. [Muons Inc., Batavia, IL (United States)

    2017-01-09

    Microtron-based Compact, Portable Gamma-Ray Source. The objective of Phase I of this project was to produce a conceptual design of a prototype compact microtron electron accelerator, which could be designed, built, and demonstrated in Phase II of the project. The conceptual design study included an analysis of the parameters of the microtron and its components, and the expected performance of the prototype microtron as a source of x-rays and/or RF neutrons in the MeV energy range. The major components of the microtron are the magnet, the accelerating system, the power system, the vacuum system, the control system, the beam extraction system and the targets to produce x-rays (and/or neutrons). Our objectives for the design of the prototype were for it to be compact, cost-effective, capable of producing high intensity x-ray (an/or neutron) fluxes. In addition, the prototype was to be easily assembled and disassembled so that components could be easily replaced. The main parameters for the prototype are the following: the range of electron kinetic energies, the output power, the RF frequency band (X-band, C-band, or S-Band), the type of injection (Type I or Type II), the magnet type, i.e. permanent magnet, electromagnet, or a hybrid combination of permanent and electromagnet. The results of the Phase I study and analysis for a prototype microtron are the following: The electron energy range can be varied from below 6 MeV to 9 MeV, the optimal frequency range is S-Band (2-4 GHz) RF frequency, Type II injection (described below), and the magnet type is the hybrid version. The prototype version will be capable of producing gamma ray doses of ~1800 R/min-m and neutron fluxes of up to ~6 x 1010 n/s with appropriate targets. The results of the Phase I study and analysis are provided below. The proposed Phase II plan was to demonstrate the prototype at low beam power. In the subsequent Phase III, high power tests would be performed, and the design of commercial

  7. Library Website Usability Test Project

    KAUST Repository

    Ramli, Rindra M.; Bukhari, Duaa

    2013-01-01

    This usability testing project was conducted to elicit an understanding of our community use of the library website. The researchers wanted to know how our users are interacting with the library website and the ease of obtaining relevant information from the website. The methodology deployed was computer user testing where participants are made to answer several questions and executing the actions on the library website. Their actions are recorded via Techsmith Camtasia software for later analysis by the researchers.

  8. Library Website Usability Test Project

    KAUST Repository

    Ramli, Rindra M.

    2013-06-01

    This usability testing project was conducted to elicit an understanding of our community use of the library website. The researchers wanted to know how our users are interacting with the library website and the ease of obtaining relevant information from the website. The methodology deployed was computer user testing where participants are made to answer several questions and executing the actions on the library website. Their actions are recorded via Techsmith Camtasia software for later analysis by the researchers.

  9. The Stripa project annual report 1984

    International Nuclear Information System (INIS)

    1985-07-01

    This is an autonomous OECD/NEA project relating to the final disposal of highly radioactive waste. Research is being performed in a granite formation 350 m below the ground surface. The first phase consists of three parts, namely hydrogeological and hydrogeochemical investigations in boreholes, tracer migration tests and large-scale tests of the behaviour of backfill material. The second phase includes the following investigations: detection and characterization of fracture zones, sealing of boreholes and shafts, hydrogoelogical characterization of the Stripa site and isotopic characterization of its groundwaters. The estimated cost of both phases is 111 MSEK and they are scheduled for completion in 1986. A summary of the progress of the project phase I and phase II is given in this report. (G.B.)

  10. Exercise Countermeasures Demonstration Project During the Lunar-Mars Life Support Test Project Phase 2A

    Science.gov (United States)

    Lee, Stuart M. C.; Guilliams, Mark E.; Moore, Alan D., Jr.; Williams, W. Jon; Greenisen, M. C.; Fortney, S. M.

    1998-01-01

    This demonstration project assessed the crew members' compliance to a portion of the exercise countermeasures planned for use onboard the International Space Station (ISS) and the outcomes of their performing these countermeasures. Although these countermeasures have been used separately in other projects and investigations, this was the first time they'd been used together for an extended period (60 days) in an investigation of this nature. Crew members exercised every day for six days, alternating every other day between aerobic and resistive exercise, and rested on the seventh day. On the aerobic exercise days, subjects exercised on an electronically braked cycle ergometer using a protocol that has been previously shown to maintain aerobic capacity in subjects exposed to a space flight analogue. On the resistive exercise days, crew members performed five major multijoint resistive exercises in a concentric mode, targeting those muscle groups and bones we believe are most severely affected by space flight. The subjects favorably tolerated both exercise protocols, with a 98% compliance to aerobic exercise prescription and a 91% adherence to the resistive exercise protocol. After 60 days, the crew members improved their peak aerobic capacity by an average 7%, and strength gains were noted in all subjects. These results suggest that these exercise protocols can be performed during ISS, lunar, and Mars missions, although we anticipate more frequent bouts with both protocols for long-duration spaceflight. Future projects should investigate the impact of increased exercise duration and frequency on subject compliance, and the efficacy of such exercise prescriptions.

  11. The SSM/PMAD automated test bed project

    Science.gov (United States)

    Lollar, Louis F.

    1991-01-01

    The Space Station Module/Power Management and Distribution (SSM/PMAD) autonomous subsystem project was initiated in 1984. The project's goal has been to design and develop an autonomous, user-supportive PMAD test bed simulating the SSF Hab/Lab module(s). An eighteen kilowatt SSM/PMAD test bed model with a high degree of automated operation has been developed. This advanced automation test bed contains three expert/knowledge based systems that interact with one another and with other more conventional software residing in up to eight distributed 386-based microcomputers to perform the necessary tasks of real-time and near real-time load scheduling, dynamic load prioritizing, and fault detection, isolation, and recovery (FDIR).

  12. Bragg projection ptychography on niobium phase domains

    Science.gov (United States)

    Burdet, Nicolas; Shi, Xiaowen; Clark, Jesse N.; Huang, Xiaojing; Harder, Ross; Robinson, Ian

    2017-07-01

    Bragg projection ptychography (BPP) is a coherent x-ray diffraction imaging technique which combines the strengths of scanning microscopy with the phase contrast of x-ray ptychography. Here we apply it for high resolution imaging of the phase-shifted crystalline domains associated with epitaxial growth. The advantages of BPP are that the spatial extent of the sample is arbitrary, it is nondestructive, and it gives potentially diffraction limited spatial resolution. Here we demonstrate the application of BPP for revealing the domain structure caused by epitaxial misfit in a nanostructured metallic thin film. Experimental coherent diffraction data were collected from a niobium thin film, epitaxially grown on a sapphire substrate as the beam was scanned across the sample. The data were analyzed by BPP using a carefully selected combination of refinement procedures. The resulting image shows a close packed array of epitaxial domains, shifted with respect to each other due to misfit between the film and its substrate.

  13. A strategic plan for the second phase (2013-2015) of the Korea biobank project.

    Science.gov (United States)

    Park, Ok; Cho, Sang Yun; Shin, So Youn; Park, Jae-Sun; Kim, Jun Woo; Han, Bok-Ghee

    2013-04-01

    The Korea Biobank Project (KBP) was led by the Ministry of Health and Welfare to establish a network between the National Biobank of Korea and biobanks run by university-affiliated general hospitals (regional biobanks). The Ministry of Health and Welfare started the project to enhance medical and health technology by collecting, managing, and providing researchers with high-quality human bioresources. The National Biobank of Korea, under the leadership of the Ministry of Health and Welfare, collects specimens through various cohorts and regional biobanks within university hospitals gather specimens from patients. The project began in 2008, and the first phase ended in 2012, which meant that there needed to be a plan for the second phase that begins in 2013. Consequently, professionals from within and outside the project were gathered to develop a plan for the second phase. Under the leadership of the planning committee, six working groups were formed to formulate a practical plan. By conducting two workshops with experts in the six working groups and the planning committee and three forums in 2011 and 2012, they have developed a strategic plan for the second phase of the KBP. This document presents a brief report of the second phase of the project based on a discussion with them. During the first phase of the project (2008-2012), a network was set up between the National Biobank of Korea and 17 biobanks at university-affiliated hospitals in an effort to unify informatics and governance among the participating biobanks. The biobanks within the network manage data on their biospecimens with a unified Biobank Information Management System. Continuous efforts are being made to develop a common standard operating procedure for resource collection, management, distribution, and personal information security, and currently, management of these data is carried out in a somewhat unified manner. In addition, the KBP has trained and educated professionals to work within the

  14. Functional design criteria for project W-252, phase II liquid effluent treatment and disposal. Revision 2

    International Nuclear Information System (INIS)

    Hatch, C.E.

    1995-05-01

    This document is the Functional Design Criteria for Project W-252. Project W-252 provides the scope to provide BAT/AKART (best available technology...) to 200 Liquid Effluent Phase II streams (B-Plant). This revision (Rev. 2) incorporates a major descoping of the project. The descoping was done to reflect a combination of budget cutting measures allowed by a less stringent regulatory posture toward the Phase II streams

  15. The modification of main steam safety valves in Qinshan phase Ⅱ expansion project

    International Nuclear Information System (INIS)

    Chen Haiqiao

    2012-01-01

    The main steam safety valves of NPP steam system are second- class nuclear safety component. It used to limit the pressure of SG secondary side and main steam system via emitting steam into the environment. At present, the main steam safety valves have mechanical valves and assisted power valves. According to the experience of power plants at home and abroad, including Qinshan Phase Ⅱ unit 1/2 experience feedback, Qinshan Phase Ⅱ expansion project made modification on valve type, setting value and valve body. This paper introduce the characteristics of different safety valve types, the modification of main steam safety valves and the modification analysis on safety issues.security and impact on the other systems in Qinshan Phase Ⅱ expansion project. (author)

  16. Planning and reporting of Russian transmutation research projects within ISTC. Phase 2

    Energy Technology Data Exchange (ETDEWEB)

    Conde, H. [Uppsala Univ. (Sweden). Dept. of Neutron Research; Gudowski, W. [Royal Inst. of Tech., Stockholm (Sweden). Dept. of Reactor and Neutron Physics; Liljenzin, J.O. [Chalmers Univ. of Technology, Goeteborg (Sweden). Dept. of Nuclear Chemistry; Mileikovsky, C. [Pully (Switzerland)

    1998-11-01

    The present report about phase 2 of the SKI project on Planning and Reporting of Russian Transmutation Research Projects within ISTC is an update of the information given in the SKI report no 97:15 (Feb 1997) about phase 1 of the same project. The background information is partly repeated in the present report to avoid that the reader has to go back to the report of Phase 1 for information about the basis for the project. USA, EU, Japan, Republic of Korea and Norway are at present supporting the International Scientific and Technical Center (ISTC) in Moscow. The Centre gives funds to research projects of civilian interest to former nuclear weapon laboratories to counteract the risk of nuclear weapon proliferation by the emigration of former USSR technical and scientific experts to `border countries` which are aiming towards the development of nuclear weapons. Before Sweden and Finland entered the EU, both countries gave national support to ISTC, in the case of Sweden 4 MUSD. Some of the projects which were funded by the Swedish national support to ISTC are still in progress. Nuclear technical concepts (i.e. Accelerator Transmutation of Nuclear Waste, ATW) have been proposed to incinerate and transmute long-lived radioactive nuclear waste to relax the time needed to store the waste in a geological repository. The named Russian experts are knowledgeable and well equipped of doing research in the different technical fields of relevance for the transmutation concepts. Thus, a number of ISTC projects have been initiated, and further ones have been proposed, to investigate different technical aspects of ATW with a result that a fair number of former weapon specialists have converted from military to peaceful civilian research. A similar centre STCU (The Scientific and Technical Centre of the Ukraine) has been set up in Kiev. Sweden has been active in promoting this Centre, which is supported by USA, Japan, Canada and recently also by EU. The present report describes the

  17. Planning and reporting of Russian transmutation research projects within ISTC. Phase 2

    International Nuclear Information System (INIS)

    Conde, H.

    1998-11-01

    The present report about phase 2 of the SKI project on Planning and Reporting of Russian Transmutation Research Projects within ISTC is an update of the information given in the SKI report no 97:15 (Feb 1997) about phase 1 of the same project. The background information is partly repeated in the present report to avoid that the reader has to go back to the report of Phase 1 for information about the basis for the project. USA, EU, Japan, Republic of Korea and Norway are at present supporting the International Scientific and Technical Center (ISTC) in Moscow. The Centre gives funds to research projects of civilian interest to former nuclear weapon laboratories to counteract the risk of nuclear weapon proliferation by the emigration of former USSR technical and scientific experts to 'border countries' which are aiming towards the development of nuclear weapons. Before Sweden and Finland entered the EU, both countries gave national support to ISTC, in the case of Sweden 4 MUSD. Some of the projects which were funded by the Swedish national support to ISTC are still in progress. Nuclear technical concepts (i.e. Accelerator Transmutation of Nuclear Waste, ATW) have been proposed to incinerate and transmute long-lived radioactive nuclear waste to relax the time needed to store the waste in a geological repository. The named Russian experts are knowledgeable and well equipped of doing research in the different technical fields of relevance for the transmutation concepts. Thus, a number of ISTC projects have been initiated, and further ones have been proposed, to investigate different technical aspects of ATW with a result that a fair number of former weapon specialists have converted from military to peaceful civilian research. A similar centre STCU (The Scientific and Technical Centre of the Ukraine) has been set up in Kiev. Sweden has been active in promoting this Centre, which is supported by USA, Japan, Canada and recently also by EU. The present report describes the

  18. Acceptance test procedure, 241-SY-101 Flexible Receiver System, Phase III testing

    International Nuclear Information System (INIS)

    Ritter, G.A.

    1994-01-01

    This Acceptance Test Procedure is for the 241-SY-101 Flexible Receiver System, Phase III Testing. This procedure will test the sealing integrity of the Flexible Receiver System to ensure that release of waste and aerosols will be minimized during the removal of the test mixer pump from tank SY-101

  19. Yucca Mountain project prototype testing

    International Nuclear Information System (INIS)

    Hughes, W.T.; Girdley, W.A.

    1990-01-01

    The U.S. DOE is responsible for characterizing the Yucca Mountain site in Nevada to determine its suitability for development as a geologic repository to isolate high-level nuclear waste for at least 10,000 years. This unprecedented task relies in part on measurements made with relatively new methods or applications, such as dry coring and overcoring for studies to be conducted from the land surface and in an underground facility. The Yucca Mountain Project has, since 1988, implemented a program of equipment development and methods development for a broad spectrum of hydrologic, geologic, rock mechanics, and thermomechanical tests planned for use in an Exploratory Shaft during site characterization at the Yucca Mountain site. A second major program was fielded beginning in April 1989 to develop and test methods and equipment for surface drilling to obtain core samples from depth using only air as a circulating medium. The third major area of prototype testing has been during the ongoing development of the Instrumentation/ Data Acquisition System (IDAS), designed to collect and monitor data from down-hole instrumentation in the unsaturated zone, and store and transmit the data to a central archiving computer. Future prototype work is planned for several programs including the application of vertical seismic profiling methods and flume design to characterizing the geology at Yucca Mountain. The major objectives of this prototype testing are to assure that planned Site Characterization testing can be carried out effectively at Yucca Mountain, both in the Exploratory Shaft Facility (ESF), and from the surface, and to avoid potential major failures or delays that could result from the need to re-design testing concepts or equipment. This paper will describe the scope of the Yucca Mountain Project prototype testing programs and summarize results to date. 3 figs

  20. Code of Conduct for wind-power projects - Phase 3; Code of Conduct fuer windkraftprojekte. Phase 3 Machbarkeit und Strategie

    Energy Technology Data Exchange (ETDEWEB)

    Strub, P. [Pierre Strub, freischaffender Berater, Binningen (Switzerland); Ziegler, Ch. [Inter Act, Basel (Switzerland)

    2008-11-15

    This paper discusses the results of phase three of a project concerning wind-power projects. Feasibility and strategy aspects are examined and discussed. The current state of the wind power market is discussed on the basis of the results of a survey made on the subject. The social acceptance of wind power installations is discussed, whereby the rejection of particular projects is compared with a general lack of acceptance. Requirements placed on such projects and possible solutions are discussed. Finally, the feasibility of setting up a code of conduct in the area of wind-power projects is discussed and the definition of further instruments is examined

  1. Analysis of Reasons for fluctuation in seal oil system on generator and countermeasures in Qinshan phase III project

    International Nuclear Information System (INIS)

    Jin Xiaodong

    2012-01-01

    Reasons for hydraulic differential fluctuations seal hydrogen oil on generator in Qinshan phase III project were analyzed, provide a basis for modifying Run method is to determine the causes and effects of seal oil flow changes and in the relationship between flow changes and hydraulic differential hydrogen oil changes according to reason Results were analyzed to adjust the running test, to verify the feasibility of running adjustment programs

  2. Round-Robin Test of Paraffin Phase-Change Material

    Science.gov (United States)

    Vidi, S.; Mehling, H.; Hemberger, F.; Haussmann, Th.; Laube, A.

    2015-11-01

    A round-robin test between three institutes was performed on a paraffin phase-change material (PCM) in the context of the German quality association for phase-change materials. The aim of the quality association is to define quality and test specifications for PCMs and to award certificates for successfully tested materials. To ensure the reproducibility and comparability of the measurements performed at different institutes using different measuring methods, a round-robin test was performed. The sample was unknown. The four methods used by the three participating institutes in the round-robin test were differential scanning calorimetry, Calvet calorimetry and three-layer calorimetry. Additionally, T-history measurements were made. The aim of the measurements was the determination of the enthalpy as a function of temperature. The results achieved following defined test specifications are in excellent agreement.

  3. Columbia River pathway report: phase I of the Hanford Environmental Dose Reconstruction Project

    Energy Technology Data Exchange (ETDEWEB)

    1991-07-01

    This report summarizes the river-pathway portion of the first phase of the Hanford Environmental Dose Reconstruction (HEDR) Project. The HEDR Project is estimating radiation doses that could have been received by the public from the Department of Energy's Hanford Site, in southeastern Washington State. Phase 1 of the river-pathway dose reconstruction effort sought to determine whether dose estimates could be calculated for populations in the area from above the Hanford Site at Priest Rapids Dam to below the site at McNary Dam from January 1964 to December 1966. Of the potential sources of radionuclides from the river, fish consumption was the most important. Doses from drinking water were lower at Pasco than at Richland and lower at Kennewick than at Pasco. The median values of preliminary dose estimates calculated by HEDR are similar to independent, previously published estimates of average doses to Richland residents. Later phases of the HEDR Project will address dose estimates for periods other than 1964--1966 and for populations downstream of McNary Dam. 17 refs., 19 figs., 1 tab.

  4. NASA TEERM Hexavalent Chrome Alternatives Projects

    Science.gov (United States)

    Kessel, Kurt; Rothgeb, Matt

    2011-01-01

    This slide presentation reviews the NASA project to select an alternative to hexavalent chrome in the aerospace industry. Included is a recent historic testing and research that the Agency has performed on (1) the external tank, (2) the shuttle orbiter, (3) the Shuttle Rocket Booster, and (4) the Space Shuttle Main Engine. Other related Technology Evaluation for Environmental Risk Mitigation (TEERM) projects are reviewed. The Phase I process of the project performed testing of alternatives the results are shown in a chart for different coating systems. International collaboration was also reviewed. Phase II involves further testing of pretreatment and primers for 6 and 12 months of exposure to conditions at Launch Pad and the beach. Further test were performed to characterize the life cycle corrosion of the space vehicles. A new task is described as a joint project with the Department of Defense to identify a Hex Chrome Free Coatings for Electronics.

  5. Proposal for a Full-Scale Prototype Single-Phase Liquid Argon Time Projection Chamber and Detector Beam Test at CERN

    CERN Document Server

    Kutter, T

    2015-01-01

    The Deep Underground Neutrino Experiment (DUNE) will use a large liquid argon (LAr) detector to measure the CP violating phase, determine the neutrino mass hier- archy and perform precision tests of the three-flavor paradigm in long-baseline neutrino oscillations. The detector will consist of four modules each with a fiducial mass of 10 kt of LAr and due to its unprecedented size will allow sensitive searches for proton decay and the detection and measurement of electron neutrinos from core collapse supernovae [1]. The first 10 kt module will use single-phase LAr detection technique and be itself modular in design. The successful manufacturing, installation and operation of several full-scale detector components in a suitable configuration represents a critical engineering milestone prior to the construction and operation of the first full 10 kt DUNE detector module at the SURF underground site. A charged particle beam test of a prototype detector will provide critical calibration measurements as well as inva...

  6. The Yucca Mountain Project Prototype Testing Program

    International Nuclear Information System (INIS)

    1989-10-01

    The Yucca Mountain Project is conducting a Prototype Testing Program to ensure that the Exploratory Shaft Facility (ESF) tests can be completed in the time available and to develop instruments, equipment, and procedures so the ESF tests can collect reliable and representative site characterization data. This report summarizes the prototype tests and their status and location and emphasizes prototype ESF and surface tests, which are required in the early stages of the ESF site characterization tests. 14 figs

  7. Estuary 2100 Project, Phase 1: Resilient Watersheds for a Changing Climate

    Science.gov (United States)

    Information about the SFBWQP Estuary 2100 Project, Phase 1: Resilient Watersheds for a Changing Climate , part of an EPA competitive grant program to improve SF Bay water quality focused on restoring impaired waters and enhancing aquatic resources.

  8. FINAL PROJECT REPORT - EVALUATION AND TESTING OF HTGR REACTOR BUILDING RESPONSE TO DEPRESSURIZATION ACCIDENTS

    Energy Technology Data Exchange (ETDEWEB)

    ALLIANCE LIMITED, NGNP INDUSTRY

    2017-07-25

    This report provides a description of the project, summarizes each phase of the project, and ends with project conclusions. In addition, the report contains a descriptive index of the technical reports generated during the course of the project.

  9. Analyses of CsI aerosol deposition in aerosol behavior tests in WIND project

    International Nuclear Information System (INIS)

    Kudo, Tamotsu; Shibazaki, Hiroaki; Hidaka, Akihide

    1999-01-01

    The aerosol deposition tests have been performed in WIND project at JAERI to characterize the aerosol behavior. The aerosol deposition tests named WAV1-D and WAV2-D were analyzed by aerosol behavior analysis codes, JAERI's ART and SNL's VICTORIA. The comparison calculation was performed for the confirmation of the analytical capabilities of the both codes and improvement of the models in ART. The deposition mass calculated by ART was larger than that by VICTORIA. This discrepancy is caused by differences in model for FP vapor condensation onto the wall surface. In the WAV2-D test, in which boric acid was placed on the floor area of the test section prior to the deposition phase to simulate the PWR primary coolant, there was a discrepancy in deposition mass between analytical results in both codes and experimental results. The discrepancy may be caused by existence of boric acid which is not considered in the codes. (author)

  10. Fast Flux Test Facility project plan. Revision 2

    Energy Technology Data Exchange (ETDEWEB)

    Hulvey, R.K.

    1995-11-01

    The Fast Flux Test Facility (FFTF) Transition Project Plan, Revision 2, provides changes to the major elements and project baseline for the deactivation activities necessary to transition the FFTF to a radiologically and industrially safe shutdown condition.

  11. Fast Flux Test Facility project plan. Revision 2

    International Nuclear Information System (INIS)

    Hulvey, R.K.

    1995-11-01

    The Fast Flux Test Facility (FFTF) Transition Project Plan, Revision 2, provides changes to the major elements and project baseline for the deactivation activities necessary to transition the FFTF to a radiologically and industrially safe shutdown condition

  12. BWR Full Integral Simulation Test (FIST) Phase II test results and TRAC-BWR model qualification

    International Nuclear Information System (INIS)

    Sutherland, W.A.; Alamgir, M.; Findlay, J.A.; Hwang, W.S.

    1985-10-01

    Eight matrix tests were conducted in the FIST Phase I. These tests investigated the large break, small break and steamline break LOCA's, as well as natural circulation and power transients. There are nine tests in Phase II of the FIST program. They include the following LOCA tests: BWR/6 LPCI line break, BWR/6 intermediate size recirculation break, and a BWR/4 large break. Steady state natural circulation tests with feedwater makeup performed at high and low pressure, and at high pressure with HPCS makeup, are included. Simulation of a transient without rod insertion, and with controlled depressurization, was performed. Also included is a simulation of the Peach Bottom turbine trip test. The final two tests simulated a failure to maintain water level during a postulated accident. A FIST program objective is to assess the TRAC code by comparisons with test data. Two post-test predictions made with TRACB04 are compared with Phase II test data in this report. These are for the BWR/6 LPCI line break LOCA, and the Peach Bottom turbine trip test simulation

  13. FALSIRE Phase II. CSNI project for Fracture Analyses of Large-Scale International Reference Experiments (Phase II). Comparison report

    International Nuclear Information System (INIS)

    Sievers, J.; Schulz, H.; Bass, R.; Pugh, C.; Keeney, J.

    1996-11-01

    A summary of Phase II of the Project for Fracture Analysis of Large-Scale International Reference Experiments (FALSIRE) is presented. A FALSIRE II Workshop focused on analyses of reference fracture experiments. More than 30 participants representing 22 organizations from 12 countries took part in the workshop. Final results for 45 analyses of the reference experiments were received from the participating analysts. For each experiment, analysis results provided estimates of variables that include temperature, crack-mouth-opening displacement, stress, strain, and applied K and J values. The data were sent electronically to the Organizing Committee, who assembled the results into a comparative data base using a special-purpose computer program. A comparative assessment and discussion of the analysis results are presented in the report. Generally, structural responses of the test specimens were predicted with tolerable scatter bands. (orig./DG)

  14. A Correlational Study of Seven Projective Spatial Structures with Regard to the Phases of the MOON^

    Science.gov (United States)

    Wellner, Karen Linette

    1995-01-01

    This study investigated the relationship between projective spatial structures and the ability to construct a scientific model. In addition, gender-related performance and the influence of prior astronomy experience on task success were evaluated. Sixty-one college science undergraduates were individually administered Piagetian tasks to assess for projective spatial structures and the ability to set up a phases of the moon model. The spatial tasks included: (a) Mountains task (coordination of perspectives); (b) Railroad task (size and intervals of objects with increasing distance); (c) Telephone Poles task (masking and ordering objects); and (d) Shadows task (spatial relationships between an object and its shadow, dependent upon the object's orientation). Cramer coefficient analyses indicated that significant relationships existed between Moon task and spatial task success. In particular, the Shadows task, requiring subjects to draw shadows of objects in different orientations, proved most difficult and was most strongly associated with with a subject's understanding of lunar phases. Chi-square tests for two independent samples were used to analyze gender performance differences on each of the Ave tasks. Males performed significantly better at a.05 significance level in regard to the Shadows task and the Moon task. Chi-square tests for two independent samples showed no significant difference in Moon task performance between subjects with astronomy or Earth science coursework, and those without such science classroom experience. Overall, only six subjects passed all seven projective spatial structure tasks. Piaget (1967) contends that concrete -operational spatial structures must be established before an individual is able to develop formal-operational patterns of thinking. The results of this study indicate that 90% of the interviewed science majors are still operating at the concrete-operational level. Several educational implications were drawn from this study

  15. Self-reliance and innovation of Qinshan phase II NPP project

    International Nuclear Information System (INIS)

    Ye Qizhen; Yang Lanhe

    2007-01-01

    This article mainly describes the self-reliance and innovation of Qinshan nuclear power project of phase II, in-between it contains new reactor core design, as well as related experimental and calculation analysis, especially for new reactor design produced fluid-induced vibration model test, theoretical analysis and testing in-built reactor; aiming at two-loop NSSS a series improvement made for safety systems and related safety analysis to enhance their reliability and redundancy; according to specialty of two-loop NSSS an optimization made for NPP parameters and design of related equipments, for the purpose to make the output of NPP maximal; design of main reactor building and T-G building also improved according to characteristics of two-loop NSSS and site conditions. CRDM and refueling machine are researched and manufactured on base of self-reliance, their performance are better than design requirements, large portion of key equipments are localized through different way. In construction first time realized the integrated erection of containment dome. During the commissioning non-nuclear steam driving of T-G set, as well as 500 kV high voltage rising using emergent diesel generator, etc. are carried out.In period of operation still continuous innovation and improvement are made, so that to keep the good record of operation. (authors)

  16. Acceptance test procedure for Project W-280

    International Nuclear Information System (INIS)

    Stites, C.G.

    1994-01-01

    This Document is the Acceptance Test Procedure for 200 Area C and SY Tank Farm Lighting Upgrade. This Acceptance Test Procedure has been prepared to demonstrate that the Tank Farm Lighting Systems function correctly as required by project criteria and as intended by design

  17. Testing for significance of phase synchronisation dynamics in the EEG.

    Science.gov (United States)

    Daly, Ian; Sweeney-Reed, Catherine M; Nasuto, Slawomir J

    2013-06-01

    A number of tests exist to check for statistical significance of phase synchronisation within the Electroencephalogram (EEG); however, the majority suffer from a lack of generality and applicability. They may also fail to account for temporal dynamics in the phase synchronisation, regarding synchronisation as a constant state instead of a dynamical process. Therefore, a novel test is developed for identifying the statistical significance of phase synchronisation based upon a combination of work characterising temporal dynamics of multivariate time-series and Markov modelling. We show how this method is better able to assess the significance of phase synchronisation than a range of commonly used significance tests. We also show how the method may be applied to identify and classify significantly different phase synchronisation dynamics in both univariate and multivariate datasets.

  18. HESTIA Phase I Test Results: The Air Revitalization System

    Science.gov (United States)

    Wright, Sarah E.; Hansen, Scott W.

    2016-01-01

    In any human spaceflight mission, a number of Environmental Control & Life Support System (ECLSS) technologies work together to provide the conditions astronauts need to live healthily, productively, and comfortably in space. In a long-duration mission, many of these ECLSS technologies may use materials supplied by In-Situ Resource Utilization (ISRU), introducing more interactions between systems. The Human Exploration Spacecraft Test-bed for Integration & Advancement (HESTIA) Project aims to create a test-bed to evaluate ECLSS and ISRU technologies and how they interact in a high-fidelity, closed-loop, human-rated analog habitat. Air purity and conditioning are essential components within any ECLSS and for HESTIA's first test they were achieved with the Air Revitalization System (ARS) described below. The ARS provided four essential functions to the test-bed chamber: cooling the air, removing humidity from the air, removing trace contaminants, and scrubbing carbon dioxide (CO2) from the air. In this case, the oxygen supply function was provided by ISRU. In the current configuration, the ARS is a collection of different subsystems. A fan circulates the air, while a condensing heat exchanger (CHX) pulls humidity out of the air. A Trace Contaminant Removal System (TCRS) filters the air of potentially harmful contaminants. Lastly, a Reactive Plastic Lithium Hydroxide (RP-LiOH) unit removes CO2 from the breathing air. During the HESTIA Phase I test in September 2015, the ARS and its individual components each functioned as expected, although further analysis is underway. During the Phase I testing and in prior bench-top tests, the energy balance of heat removed by the CHX was not equal to the cooling it received. This indicated possible instrument error and therefore recalibration of the instruments and follow-up testing is planned in 2016 to address the issue. The ARS was tested in conjunction with two other systems: the Human Metabolic Simulator (HMS) and the

  19. Characterization of unpaved road condition through the use of remote sensing project - phase II, deliverable 8-D: final report.

    Science.gov (United States)

    2016-03-07

    Building on the success of developing a UAV based unpaved road assessment system in Phase I, the project team was awarded a Phase II project by the USDOT to focus on outreach and implementation. The project team added Valerie Lefler of Integrated Glo...

  20. Pipe Overpack Container Fire Testing: Phase I & II

    Energy Technology Data Exchange (ETDEWEB)

    Figueroa, Victor G. [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States); Ammerman, Douglas J. [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States); Lopez, Carlos [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States); Gill, Walter [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States)

    2017-05-01

    The Pipe Overpack Container (POC) was developed at Rocky Flats to transport plutonium residues with higher levels of plutonium than standard transuranic (TRU) waste to the Waste Isolation Pilot Plant (WIPP) for disposal. In 1996 Sandia National Laboratories (SNL) conducted a series of tests to determine the degree of protection POCs provided during storage accident events. One of these tests exposed four of the POCs to a 30-minute engulfing pool fire, resulting in one of the 7A drum overpacks generating sufficient internal pressure to pop off its lid and expose the top of the pipe container (PC) to the fire environment. The initial contents of the POCs were inert materials, which would not generate large internal pressure within the PC if heated. However, POCs are now being used to store combustible TRU waste at Department of Energy (DOE) sites. At the request of DOE’s Office of Environmental Management (EM) and National Nuclear Security Administration (NNSA), starting in 2015 SNL conducted a new series of fire tests to examine whether PCs with combustibles would reach a temperature that would result in (1) decomposition of inner contents and (2) subsequent generation of sufficient gas to cause the PC to over-pressurize and release its inner content. Tests conducted during 2015 and 2016, and described herein, were done in two phases. The goal of the first phase was to see if the PC would reach high enough temperatures to decompose typical combustible materials inside the PC. The goal of the second test phase was to determine under what heating loads (i.e., incident heat fluxes) the 7A drum lid pops off from the POC drum. This report will describe the various tests conducted in phase I and II, present preliminary results from these tests, and discuss implications for the POCs.

  1. Pretreatment Engineering Platform Phase 1 Final Test Report

    Energy Technology Data Exchange (ETDEWEB)

    Kurath, Dean E.; Hanson, Brady D.; Minette, Michael J.; Baldwin, David L.; Rapko, Brian M.; Mahoney, Lenna A.; Schonewill, Philip P.; Daniel, Richard C.; Eslinger, Paul W.; Huckaby, James L.; Billing, Justin M.; Sundar, Parameshwaran S.; Josephson, Gary B.; Toth, James J.; Yokuda, Satoru T.; Baer, Ellen BK; Barnes, Steven M.; Golovich, Elizabeth C.; Rassat, Scot D.; Brown, Christopher F.; Geeting, John GH; Sevigny, Gary J.; Casella, Amanda J.; Bontha, Jagannadha R.; Aaberg, Rosanne L.; Aker, Pamela M.; Guzman-Leong, Consuelo E.; Kimura, Marcia L.; Sundaram, S. K.; Pires, Richard P.; Wells, Beric E.; Bredt, Ofelia P.

    2009-12-23

    Pacific Northwest National Laboratory (PNNL) was tasked by Bechtel National Inc. (BNI) on the River Protection Project, Hanford Tank Waste Treatment and Immobilization Plant (RPP-WTP) project to conduct testing to demonstrate the performance of the WTP Pretreatment Facility (PTF) leaching and ultrafiltration processes at an engineering-scale. In addition to the demonstration, the testing was to address specific technical issues identified in Issue Response Plan for Implementation of External Flowsheet Review Team (EFRT) Recommendations - M12, Undemonstrated Leaching Processes.( ) Testing was conducted in a 1/4.5-scale mock-up of the PTF ultrafiltration system, the Pretreatment Engineering Platform (PEP). Parallel laboratory testing was conducted in various PNNL laboratories to allow direct comparison of process performance at an engineering-scale and a laboratory-scale. This report presents and discusses the results of those tests.

  2. Pretreatment Engineering Platform Phase 1 Final Test Report

    International Nuclear Information System (INIS)

    Kurath, Dean E.; Hanson, Brady D.; Minette, Michael J.; Baldwin, David L.; Rapko, Brian M.; Mahoney, Lenna A.; Schonewill, Philip P.; Daniel, Richard C.; Eslinger, Paul W.; Huckaby, James L.; Billing, Justin M.; Sundar, Parameshwaran S.; Josephson, Gary B.; Toth, James J.; Yokuda, Satoru T.; Baer, Ellen B.K.; Barnes, Steven M.; Golovich, Elizabeth C.; Rassat, Scot D.; Brown, Christopher F.; Geeting, John G.H.; Sevigny, Gary J.; Casella, Amanda J.; Bontha, Jagannadha R.; Aaberg, Rosanne L.; Aker, Pamela M.; Guzman-Leong, Consuelo E.; Kimura, Marcia L.; Sundaram, S.K.; Pires, Richard P.; Wells, Beric E.; Bredt, Ofelia P.

    2009-01-01

    Pacific Northwest National Laboratory (PNNL) was tasked by Bechtel National Inc. (BNI) on the River Protection Project, Hanford Tank Waste Treatment and Immobilization Plant (RPP-WTP) project to conduct testing to demonstrate the performance of the WTP Pretreatment Facility (PTF) leaching and ultrafiltration processes at an engineering-scale. In addition to the demonstration, the testing was to address specific technical issues identified in Issue Response Plan for Implementation of External Flowsheet Review Team (EFRT) Recommendations - M12, Undemonstrated Leaching Processes. Testing was conducted in a 1/4.5-scale mock-up of the PTF ultrafiltration system, the Pretreatment Engineering Platform (PEP). Parallel laboratory testing was conducted in various PNNL laboratories to allow direct comparison of process performance at an engineering-scale and a laboratory-scale. This report presents and discusses the results of those tests.

  3. INTRAVAL Working group 2 summary report on Phase 2 analysis of the Finnsjoen test case

    International Nuclear Information System (INIS)

    Andersson, Peter; Winberg, A.

    1994-01-01

    A comprehensive series of tracer tests on a relatively large scale have been performed by SKB at Finnsjoen, Sweden, to increase understanding of transport phenomena which govern migration of radionuclides in major fracture zones. The conducted experiments were subsequently selected as a test in the international INTRAVAL Project, in part because the tests at Finnsjoe invite to direct address of validation of geosphere models. This report summarizes the study of the Finnsjoe test case within INTRAVAL Phase 2, which has involved nine project teams from seven countries. Porous media approaches in two dimensions dominated, although some project teams utilized one-dimensional transport models, and even three-dimensional approaches on a larger scale. The dimensionality employed did not appear to be decisive for the ability to reproduce the observed field responses. It was also demonstrated that stochastic approaches can be used in a validation process. Only four out of nine project teams studied more than one process. The general conclusion drawn is that flow and transport in the studied zone is governed by advection and that hydrodynamic dispersion is needed to explain the breakthrough curves. Matrix diffusion is assumed to have small or negligible effect. The performed analysis is dominated by numerical approaches applied on scales on the order of a 1000m. Taking scale alone into account, the results of most teams are possible to compare. A variety of validation aspects have been considered. Five teams utilized a model calibrated on one test, to predict another, whereas the two teams utilizing stochastic continuum approaches addressed; 1) validity of extrapolation of a model calibrated on one transport scale to a larger scale, 2) performance assessment implications of choice of underlying distribution model for hydraulic conductivity, respectively. 37 refs

  4. Phase 2 : evaluation of the national crash experience : comparison of CARDfile national motor vehicle accident projections with projections from other data bases

    Science.gov (United States)

    1997-01-01

    The purpose of this Phase 2 Study is to compare national motor vehicle accident projections : made from the Crash Avoidance Research Data base (CARDfile) with national motor : vehicle accident projections made from other data bases. For the most part...

  5. The Qinshan phase III project-a successful model of sino-canadian cooperation

    International Nuclear Information System (INIS)

    Pang, S.H.H.; Alikhan, S.; Gu Jun

    2005-01-01

    The Qinshan Phase III (CANDU) Project, the largest-scale cooperative project between China and Canada, was completed in 2003 well in advance of the schedule and 10% under budget. The Third Qinshan (Phase III) Nuclear Power Plant (TQNPP) was built in record times: Unit 1 achieved commercial operation on December 31, 2002 and Unit 2 on July 20, 2003, 43 days and 115 days ahead of schedule respectively. Improvements in design and construction methods allowed Unit 1 to be constructed in 51.5 months from First Concrete to Criticality - a record in China for nuclear power plants. The key factors are project management and project management tools, quality assurance, construction methods, electronic documentation with configuration control that provides up-to-date on-line information, CADDS design linked with material management and control. New design and construction techniques were introduced by combining conventional AECL practices with working experiences in China. The most advanced tools and techniques for achieving optimum construction quality, schedule and cost were used. Successful application of advanced project management methods and tools has benefited TQNPC in its subsequent plant operation, and the Chinese contractors in advancing their capabilities in future nuclear projects in China as well as enhancing their opportunities internationally. Excellent co-operation and teamwork within the integrated TQNPC/AECL Commissioning Team with well documented QA program, process and procedures also contributed to the remarkable success of the Project. AECL's initial assessment, based on lessons learned, showed that the project schedule could readily be reduced to 66 months and the capital costs reduced by 25% for a replication project. AECL is building on this experience and successful results of TQNPP in its Advanced CANDU Reactor TM (ACR TM ) ** design. (authors)

  6. Depressurisation studies. Phase 2: results of Tests 127 and 128

    International Nuclear Information System (INIS)

    Edwards, A.R.; Borgartz, B.O.; Goodman, R.M.E.; O'Brien, T.P.; Rawlingson, M.

    1978-06-01

    A basic experimental programme involving the sudden depressurisation of a simple pipe system containing water at 3.45 to 17.24MPa pressure and temperature in the range of 200 to 250 0 C has been concluded. Measurements were made of the transient density, pressure, and temperature variations in a two phase fluid in the system during discharge. Phase 1 tests investigated blowdown from straight pipes 4m long with constant internal diameters of 73 and 32 mm. Phase 2 tests incorporated a reservoir added to the 32mm pipe. In this, the second of three reports on Phase 2 tests, the test assembly, instrumentation and experimental procedure are briefly described. The conditions and results are reported for two of the tests in which the liquid in the long discharge pipe was initially subcooled by 10 0 C and 15 0 C while the reservoir was at saturation conditions with a steam dome present. (UK)

  7. Application of Phase Shifting Projection Moire on Solid Regular Figures and Plant Organs Three Dimensional Digital Model Generation

    Science.gov (United States)

    Lino, A. C. L.; Dal Fabbro, I. M.

    2008-04-01

    The conception of a tridimensional digital model of solid figures and plant organs started from topographic survey of virtual surfaces [1], followed by topographic survey of solid figures [2], fruit surface survey [3] and finally the generation of a 3D digital model [4] as presented by [1]. In this research work, i.e. step number [4] tested objects included cylinders, cubes, spheres and fruits. A Ronchi grid named G1 was generated in a PC, from which other grids referred as G2, G3, and G4 were set out of phase by 1/4, 1/2 and 3/4 of period from G1. Grid G1 was then projected onto the samples surface. Projected grid was named Gd. The difference between Gd and G1 followed by filtration generated de moiré fringes M1 and so on, obtaining the fringes M2, M3 and M4 from Gd. Fringes are out of phase one from each other by 1/4 of period, which were processed by the Rising Sun Moiré software to produce packed phase and further on, the unpacked fringes. Tested object was placed on a goniometer and rotate to generate four surfaces topography. These four surveyed surfaces were assembled by means of a SCILAB software, obtaining a three column matrix, corresponding to the object coordinates xi, also having elevation values and coordinates corrected as well. The work includes conclusions on the reliability of the proposed method as well as the setup simplicity and of low cost.

  8. Uncertainty Analyses for Back Projection Methods

    Science.gov (United States)

    Zeng, H.; Wei, S.; Wu, W.

    2017-12-01

    So far few comprehensive error analyses for back projection methods have been conducted, although it is evident that high frequency seismic waves can be easily affected by earthquake depth, focal mechanisms and the Earth's 3D structures. Here we perform 1D and 3D synthetic tests for two back projection methods, MUltiple SIgnal Classification (MUSIC) (Meng et al., 2011) and Compressive Sensing (CS) (Yao et al., 2011). We generate synthetics for both point sources and finite rupture sources with different depths, focal mechanisms, as well as 1D and 3D structures in the source region. The 3D synthetics are generated through a hybrid scheme of Direct Solution Method and Spectral Element Method. Then we back project the synthetic data using MUSIC and CS. The synthetic tests show that the depth phases can be back projected as artificial sources both in space and time. For instance, for a source depth of 10km, back projection gives a strong signal 8km away from the true source. Such bias increases with depth, e.g., the error of horizontal location could be larger than 20km for a depth of 40km. If the array is located around the nodal direction of direct P-waves the teleseismic P-waves are dominated by the depth phases. Therefore, back projections are actually imaging the reflection points of depth phases more than the rupture front. Besides depth phases, the strong and long lasted coda waves due to 3D effects near trench can lead to additional complexities tested here. The strength contrast of different frequency contents in the rupture models also produces some variations to the back projection results. In the synthetic tests, MUSIC and CS derive consistent results. While MUSIC is more computationally efficient, CS works better for sparse arrays. In summary, our analyses indicate that the impact of various factors mentioned above should be taken into consideration when interpreting back projection images, before we can use them to infer the earthquake rupture physics.

  9. Moses Lake Fishery Restoration Project : FY 1999 Annual Report.

    Energy Technology Data Exchange (ETDEWEB)

    None given

    2000-12-01

    The Moses Lake Project consists of 3 phases. Phase 1 is the assessment of all currently available physical and biological information, the collection of baseline biological data, the formulation of testable hypotheses, and the development of a detailed study plan to test the hypotheses. Phase 2 is dedicated to the implementation of the study plan including data collection, hypotheses testing, and the formulation of a management plan. Phase 3 of the project is the implementation of the management plan, monitoring and evaluation of the implemented recommendations. The project intends to restore the failed recreational fishery for panfish species (black crappie, bluegill and yellow perch) in Moses Lake as off site mitigation for lost recreational fishing opportunities for anadromous species in the upper Columbia River. This report summarizes the results of Phase 1 investigations and presents the study plan directed at initiating Phase 2 of the project. Phase 1of the project culminates with the formulation of testable hypotheses directed at investigating possible limiting factors to the production of panfish in Moses Lake. The limiting factors to be investigated will include water quality, habitat quantity and quality, food limitations, competition, recruitment, predation, over harvest, environmental requirements, and the physical and chemical limitations of the system in relation to the fishes.

  10. A short-term rating method for heat pump heating systems; phase 5: test of the fault diagnosis systems; Kurztestmethode fuer Waermepumpenanlagen; Phase 5: Test der Fehlerdiagnosesysteme

    Energy Technology Data Exchange (ETDEWEB)

    Zogg, D.; Esfandiar, S.

    2001-07-01

    This final report for the Swiss Federal Office of Energy (SFOE) describes the testing phase of a project that developed systems for the operational monitoring and optimisation of heat pump installations along with a diagnosis system for faults. The heat pump is considered as a sub-system. The report describes two monitoring systems and a simulation model that are used to monitor the state of the heat pump both during commissioning as well as during operation. The aim is also to detect faults as early as possible during the whole of the operational life of the installation. A state-orientated approach is propagated as being cheaper than fixed service intervals or repairing after breakdown and standstill. The development of the two monitoring systems called 'HeatWatch' and 'FuzzyWatch' is described. The effort needed for the parametrisation and training of these systems is discussed. The testing of the systems on two test beds using real-life measured values for a single-family home and further simulation data is described and the results listed. The authors state that the monitoring systems can also be used for refrigeration and air-conditioning systems.

  11. Acceptance test report, 241-SY-101 Flexible Receiver System, Phase 3 testing

    International Nuclear Information System (INIS)

    Ritter, G.A.

    1995-01-01

    This document summarizes the results of the phase 3 acceptance test of the 241-SY-101 Flexible Receiver System (FRS). The purpose of this acceptance test is to verify the sealing integrity of the FRS to ensure that the release of waste and aerosols will be minimized during the removal of the test mixer pump from Tank 241-SY-101. The FRS is one of six major components of the Equipment Removal System, which has been designed to retrieve, transport, and store the mixer pump. This acceptance test was performed at the 306E Facility in the 300 area from January 10, 1995 to January 17, 1995. The Phase 3 test consisted of two parts. Part one was a water leak test of the seal between the blast shield and mock load distribution frame (LDF) to ensure that significant contamination of the pump pit and waste interaction with the aluminum impact-limiting material under the LDF are prevented during the pump removal operation. The second part of this acceptance test was an air leak test of the assembled flexible receiver system. The purpose of this test was to verify that the release of hazardous aerosols will be minimized if the tank dome pressure becomes slightly positive during the decontamination of the mixer pump

  12. The Chancellor's Model School Project (CMSP)

    Science.gov (United States)

    Lopez, Gil

    1999-01-01

    What does it take to create and implement a 7th to 8th grade middle school program where the great majority of students achieve at high academic levels regardless of their previous elementary school backgrounds? This was the major question that guided the research and development of a 7-year long project effort entitled the Chancellor's Model School Project (CMSP) from September 1991 to August 1998. The CMSP effort conducted largely in two New York City public schools was aimed at creating and testing a prototype 7th and 8th grade model program that was organized and test-implemented in two distinct project phases: Phase I of the CMSP effort was conducted from 1991 to 1995 as a 7th to 8th grade extension of an existing K-6 elementary school, and Phase II was conducted from 1995 to 1998 as a 7th to 8th grade middle school program that became an integral part of a newly established 7-12th grade high school. In Phase I, the CMSP demonstrated that with a highly structured curriculum coupled with strong academic support and increased learning time, students participating in the CMSP were able to develop a strong foundation for rigorous high school coursework within the space of 2 years (at the 7th and 8th grades). Mathematics and Reading test score data during Phase I of the project, clearly indicated that significant academic gains were obtained by almost all students -- at both the high and low ends of the spectrum -- regardless of their previous academic performance in the K-6 elementary school experience. The CMSP effort expanded in Phase II to include a fully operating 7-12 high school model. Achievement gains at the 7th and 8th grade levels in Phase II were tempered by the fact that incoming 7th grade students' academic background at the CMSP High School was significantly lower than students participating in Phase 1. Student performance in Phase II was also affected by the broadening of the CMSP effort from a 7-8th grade program to a fully functioning 7-12 high

  13. Joint test rig for tests and calibration of different methods of two-phase mass flow measurement

    International Nuclear Information System (INIS)

    John, H.; Erbacher, F.; Wanner, E.

    1975-01-01

    On behalf of the Federal Ministry of Research and Technology, the Institute of Reactor Components (IRB) has begun building a test rig which will be used for testing and calibrating the methods of measuring non-steady state two-phase mass flows developed by various research agencies. The test rig is designed for the generation of steam-water mixtures of any mixing ratio and a maximum pressure of 160 data. Depending on the mixing ratio, the mass flow will reach a maximum level of 10 to 20 t/h. The conceptual design phase of the test rig has largely been finished, the component ordering phase has begun. (orig.) [de

  14. Small heat pumps using ammonia, phase 3; Kleinwaermepumpe mit Ammoniak, Phase 3: Fluegelzellenverdichter mit Economizer und Schraubenverdichter

    Energy Technology Data Exchange (ETDEWEB)

    Geisser, E.; Kopp, Th.

    2003-07-01

    This comprehensive final report for the Swiss Federal Office of Energy (SFOE) presents the results of research done in the third phase of a research project that investigated components for small heat pump systems that use ammonia as a working fluid. The report includes a summary of the findings of the first two phases of the project and goes on to describe tests done with rotary vane and scroll compressors. The aims of the project are discussed and the work done is listed chronologically. The construction and the components of the test installation are described in detail. Also, the heat pump testing facilities at the University of Applied Science in Rapperswil, Switzerland, are described. The results of the measurements made for various temperature gradients are presented in detail and commented on; also, the various types of compressor tested and other heat pump compressors are compared.

  15. Project W-049H disposal facility test report

    International Nuclear Information System (INIS)

    Buckles, D.I.

    1995-01-01

    The purpose of this Acceptance Test Report (ATR) for the Project W-049H, Treated Effluent Disposal Facility, is to verify that the equipment installed in the Disposal Facility has been installed in accordance with the design documents and function as required by the project criteria

  16. Test of GERDA Phase II detector assembly

    Energy Technology Data Exchange (ETDEWEB)

    Bode, Tobias; Gusev, Konstantin [Technische Universitaet Muenchen (Germany); Schwingenheuer, Bernhard; Wagner, Victoria [Max-Planck Institut fuer Kernphysik, Heidelberg (Germany); Collaboration: GERDA-Collaboration

    2014-07-01

    The GERDA experiment searches for the lepton number violating neutrinoless double beta decay (0νββ) of {sup 76}Ge. The experiment uses HPGe detectors enriched in {sup 76}Ge as source and detection material. In GERDA Phase I five BEGe detectors were operated successfully. These detectors are distinguished for improved energy resolution and enhanced pulse shape discrimination (PSD) against background events. In Phase II additional 25 BEGe detectors will be installed. New electronics and radio-pure low-mass holders were specially designed for Phase II. Prior to the installation in GERDA all BEGe detectors are tested in their final assembly in the LNGS underground laboratory. This talk presents the mechanics and performance of the GERDA Phase II detector assembly.

  17. Dynamic Testing of the NASA Hypersonic Project Combined Cycle Engine Testbed for Mode Transition Experiments

    Science.gov (United States)

    2011-01-01

    NASA is interested in developing technology that leads to more routine, safe, and affordable access to space. Access to space using airbreathing propulsion systems has potential to meet these objectives based on Airbreathing Access to Space (AAS) system studies. To this end, the NASA Fundamental Aeronautics Program (FAP) Hypersonic Project is conducting fundamental research on a Turbine Based Combined Cycle (TBCC) propulsion system. The TBCC being studied considers a dual flow-path inlet system. One flow-path includes variable geometry to regulate airflow to a turbine engine cycle. The turbine cycle provides propulsion from take-off to supersonic flight. The second flow-path supports a dual-mode scramjet (DMSJ) cycle which would be initiated at supersonic speed to further accelerate the vehicle to hypersonic speed. For a TBCC propulsion system to accelerate a vehicle from supersonic to hypersonic speed, a critical enabling technology is the ability to safely and effectively transition from the turbine to the DMSJ-referred to as mode transition. To experimentally test methods of mode transition, a Combined Cycle Engine (CCE) Large-scale Inlet testbed was designed with two flow paths-a low speed flow-path sized for a turbine cycle and a high speed flow-path designed for a DMSJ. This testbed system is identified as the CCE Large-Scale Inlet for Mode Transition studies (CCE-LIMX). The test plan for the CCE-LIMX in the NASA Glenn Research Center (GRC) 10- by 10-ft Supersonic Wind Tunnel (10x10 SWT) is segmented into multiple phases. The first phase is a matrix of inlet characterization (IC) tests to evaluate the inlet performance and establish the mode transition schedule. The second phase is a matrix of dynamic system identification (SysID) experiments designed to support closed-loop control development at mode transition schedule operating points for the CCE-LIMX. The third phase includes a direct demonstration of controlled mode transition using a closed loop control

  18. QUEST/Ada (query utility environment for software testing of Ada: The development of a program analysis environment for Ada, task 1, phase 3

    Science.gov (United States)

    Brown, David B.

    1991-01-01

    The results of research and development efforts of the first six months of Task 1, Phase 3 of the project are presented. The goals of Phase 3 are: (1) to further refine the rule base and complete the comparative rule base evaluation; (2) to implement and evaluate a concurrency testing prototype; (3) to convert the complete (unit-level and concurrency) testing prototype to a workstation environment; and (4) to provide a prototype development document to facilitate the transfer of research technology to a working environment. These goals were partially met and the results are summarized.

  19. Construction and test of a superconducting phase-transition thermometer for bolometric cryodetectors

    International Nuclear Information System (INIS)

    Meier, H.J.

    1990-10-01

    In the framework of a project for the study of bolometric cryodetectors for the detection of heavy ions a superconducting phase-transition thermometer for the detection of heavy ions was constructed and tested with α particles. The thermometer consists of a 10 nm thick aluminium film, which was evaporated on a sapphire absorber with a typical magnitude of 2.5x2.5 x 0.33 mm 3 . By the method of photolithography the aluminium film was structured in form of a meander. By this at the working point of the thermometer resistances of up to 60 kΩ resulted, so that the signal acquisition was possible with usual readout electronics. Several of these thermometers were constructed, characterized in their properties, and tested. For the study of the detector properties of the thermometers in characterization measurements the width of the phase transitions dT ≅ 2 mK, the temperature dependence of the resistance to dR/dT ≅ 10MΩ/K, the thermal conductivity of the thermal coupling to the cooling bath, and the heat capacity of the bolometers to C ≅ 2 nJ/K were determined.The best energy resolution, which was reached with one of the superconducting phase-transition thermometers, amounts to 50 keV for 5.5 MeV α particles, which corresponds to a relative resolution of 0,9%. By this in the order of magnitude the quality of semiconductor detectors was reached. The best temperature resolution amounts to about 1 μK. (orig./HSI) [de

  20. On-ground testing of the role of adhesion in the LISA-Pathfinder test mass injection phase

    Science.gov (United States)

    Bortoluzzi, D.; Zanoni, C.; Conklin, J. W.

    2017-05-01

    Many space missions share the need to fly a free-falling body inside the spacecraft, as a reference for navigation and/or as a probe for the local gravitational field. When a mechanism is required to cage such an object during the launch phase, the need arises to release it to free-fall once the operational phase must be initiated in orbit. The criticality of this phase increases when the mechanical interfaces between the body and the mechanism are affected by adhesion and the actuation authority of the control system on the free-falling body is limited. Both conditions are realized in the LISA Pathfinder mission, which aims at injecting a gold-coated 2 kg cubic test mass into a nearly perfect geodesic trajectory to demonstrate the readiness of the developed technology for in-space gravity wave detection. The criticality of adhesion is widely recognized in space technology, because it can affect and jeopardize the functionality of mechanisms, when arising between moving parts. In the LISA Pathfinder case, metallic adhesion potentially plays a relevant role, mainly for two reasons. First, thanks to its properties (ductility, high surface energy) the gold coating on the proof mass easily produces cold weldings, especially in vacuum conditions. Second, the detachment of the proof mass from the releasing device occurs abruptly and a relevant influence of the separation velocity is expected on the strength of the welding. This can produce an excessive velocity of the proof mass at the retraction of the releasing device for the following capture and centring phase on behalf of the control system. A testing activity is performed to characterize the dynamic behaviour of the adhesive bonds between the proof mass and the releasing device, which can be used to predict their contribution on the residual velocity of the proof mass after in-flight release. The study of such a dynamic phenomenon sets some challenging requirements on the measurement technique, both on the

  1. Phase 2 testing of ENDF/B-VI shielding data

    International Nuclear Information System (INIS)

    Ingersoll, D.T.; Wright, R.Q.; Slater, C.O.

    1992-01-01

    Version 6 of the US Evaluated Nuclear Data File (ENDF/B-VI) was released in early 1990 and is currently undergoing phase 2 testing. In Phase 2 testing, the evaluated data are approximately processed and used in an integral manner to predict the solution of previously specified benchmark experiments. Results are presented for the initial testing of several light elements and structural materials which are important for shielding applications. These initial tests indicate that the relatively subtle changes made to the iron data and the major modernization of the boron-11 data in Version 6 both represent significant and positive advancements in the quality of the evaluated data files

  2. TWRS phase 1 infrastructure project (W-519) characterization

    International Nuclear Information System (INIS)

    Mitchell, C.J.

    1998-01-01

    In order to treat the mixed radioactive and hazardous waste stored in 177 underground tanks, the Tank Waste Remediation System (TWRS) program is developing a 'demonstration' site for treatment and immobilization of these wastes by a private contractor. Project W-519 is providing the infrastructure support to this site by developing the designs and emplacing required pipelines, roads, electrical, etc. In support of the TWRS Phase 1 Infrastructure Project (W-519) Characterization, Numatec Hanford Corporation (NHC) contracted with Waste Management Federal Services, Inc., Northwest Operations (WMNW) to investigate a number of locations in and just outside the 200 East Area eastern fenceline boundary. These areas consisted of known or suspected waste lines or waste sites that could potentially impact the construction and emplacement of the proposed facility improvements, including waterlines and roads. These sites were all located subsurface and sugaring would be required to obtain sample material from the desired depth. The soils would then be sampled and submitted to the laboratory for analysis of radioactivity

  3. Application of isotopes and radiation to increasing agricultural production - Phase 2. Indonesia. Project findings and recommendations

    International Nuclear Information System (INIS)

    1992-01-01

    This Phase 2 Project was primarily aimed at consolidating the advances made during the previous phase, formulating practical agricultural technologies which can be adopted by farmers, disseminating and applying these technologies, and enhancing the capability of the Centre for Application of Isotopes and Radiation (CAIR) to conduct agricultural research using nuclear and related techniques. Outputs generated by this project were generally in accordance with those anticipated in the Project Document. Some outputs have been transferred to the target beneficiaries (farmers) through existing systems of extension, in co-operation with the main implementing agency (BATAN). Other outputs have potential for further assessment, and may lead to practical applications in future. The rest remain as important contributions to scientific knowledge. The project has been managed to assure sustainability after project termination. A strong indication of such sustainability is evident in the on-going research and development work at CAIR and the adoption of transferred technologies by the end-users. To keep up with rapid global advancements in bio-science and technology, a new project on application of nuclear and related techniques in agricultural bio-science and technology would be needed in relation to the second long-term phase of the national development programmes. (author)

  4. Investment feasibility tracking: the importance of measuring and tracking the success level of the project during commercialization phase

    Science.gov (United States)

    Saputra, Y. A.; Setyaningtyas, V. E. D.; Latiffianti, E.; Wijaya, S. H.; Ladamay, O. S. A.

    2018-04-01

    Measuring project success level is a challenging activity. This area of works has attracted many researchers to look deeper into the method of measurement, success factor identification, risk management, and many others relevant topics. However, the project management scope is limited until the project handover stage. After a project handover, the control of a project management changes from Project Management Team to the project owner/commercialization team. From an investor’s point of view, the success of a project delivery needs to be followed by the success of commercialization phase. This paper aims to present an approach on how we track and measure the progress and success level of a project investment in the commercialization phase. This is an interesting topic which probably often being forgotten in many practical case. Our proposed concept modify Freeman and Beale concept by estimating the variance between the Planned Net Present Value / Annual Worth (as it is in the Feasibility Study Document) and the Actual Net Present Value / Annual Worth (until the point time of evaluation). The gap will lead us to the next analysis and give us some important information, especially exposing whether our project investment performs better than the planning or underperformed. Some corrective actions can be suggested based on the provided information. Practical cases to exercise the concept is also provided and discussed; one case in a property sector in the middle of commercialization phase, and another case in a Power Plant investment approaching the end of commercialization phase.

  5. 10 MW Supercritical CO2 Turbine Test

    Energy Technology Data Exchange (ETDEWEB)

    Turchi, Craig

    2014-01-29

    The Supercritical CO2 Turbine Test project was to demonstrate the inherent efficiencies of a supercritical carbon dioxide (s-CO2) power turbine and associated turbomachinery under conditions and at a scale relevant to commercial concentrating solar power (CSP) projects, thereby accelerating the commercial deployment of this new power generation technology. The project involved eight partnering organizations: NREL, Sandia National Laboratories, Echogen Power Systems, Abengoa Solar, University of Wisconsin at Madison, Electric Power Research Institute, Barber-Nichols, and the CSP Program of the U.S. Department of Energy. The multi-year project planned to design, fabricate, and validate an s-CO2 power turbine of nominally 10 MWe that is capable of operation at up to 700°C and operates in a dry-cooled test loop. The project plan consisted of three phases: (1) system design and modeling, (2) fabrication, and (3) testing. The major accomplishments of Phase 1 included: Design of a multistage, axial-flow, s-CO2 power turbine; Design modifications to an existing turbocompressor to provide s-CO2 flow for the test system; Updated equipment and installation costs for the turbomachinery and associated support infrastructure; Development of simulation tools for the test loop itself and for more efficient cycle designs that are of greater commercial interest; Simulation of s-CO2 power cycle integration into molten-nitrate-salt CSP systems indicating a cost benefit of up to 8% in levelized cost of energy; Identification of recuperator cost as a key economic parameter; Corrosion data for multiple alloys at temperatures up to 650ºC in high-pressure CO2 and recommendations for materials-of-construction; and Revised test plan and preliminary operating conditions based on the ongoing tests of related equipment. Phase 1 established that the cost of the facility needed to test the power turbine at its full power and temperature would exceed the planned funding for Phases 2 and 3. Late

  6. Urban High School Student Engagement through CincySTEM iTEST Projects

    Science.gov (United States)

    Beckett, Gulbahar H.; Hemmings, Annette; Maltbie, Catherine; Wright, Kathy; Sherman, Melissa; Sersion, Brian

    2016-01-01

    This paper focuses on the notable heightening of underrepresented students' engagement in STEM education through project-based learning CincySTEM iTEST projects. The projects, funded by an iTEST NSF grant, were designed and facilitated by teachers at a new STEM urban public high school serving low-income African-American students. Student…

  7. 76 FR 55947 - Industrial Relations Promotion Project, Phase II in Vietnam

    Science.gov (United States)

    2011-09-09

    ... DEPARTMENT OF LABOR Office of the Secretary Industrial Relations Promotion Project, Phase II in... to perform the type of activity to be funded.. DAI, through its Industrial Relations Promotion... provided a letter in support of continued funding of DAI/IRRP based, on part, on the importance of the...

  8. Automation of Test Cases for Web Applications : Automation of CRM Test Cases

    OpenAIRE

    Seyoum, Alazar

    2012-01-01

    The main theme of this project was to design a test automation framework for automating web related test cases. Automating test cases designed for testing a web interface provide a means of improving a software development process by shortening the testing phase in the software development life cycle. In this project an existing AutoTester framework and iMacros test automation tools were used. CRM Test Agent was developed to integrate AutoTester to iMacros and to enable the AutoTester,...

  9. Safety requirements, facility user needs, and reactor concepts for a new Broad Application Test Reactor

    International Nuclear Information System (INIS)

    Ryskamp, J.M.; Liebenthal, J.L.; Denison, A.B.; Fletcher, C.D.

    1992-07-01

    This report describes the EG ampersand G Laboratory Directed Research and Development Program (LDRD) Broad Application Test Reactor (BATR) Project that was conducted in fiscal year 1991. The scope of this project was divided into three phases: a project process definition phase, a requirements development phase, and a preconceptual reactor design and evaluation phase. Multidisciplinary teams of experts conducted each phase. This report presents the need for a new test reactor, the project process definition, a set of current and projected regulatory compliance and safety requirements, a set of facility user needs for a broad range of projected testing missions, and descriptions of reactor concepts capable of meeting these requirements. This information can be applied to strategic planning to provide the Department of Energy with management options

  10. Pipe Overpack Container Fire Testing: Phase I II & III.

    Energy Technology Data Exchange (ETDEWEB)

    Figueroa, Victor G. [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States); Ammerman, Douglas J. [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States); Lopez, Carlos [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States); Gill, Walter [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States)

    2018-02-01

    The Pipe Overpack Container (POC) was developed at Rocky Flats to transport plutonium residues with higher levels of plutonium than standard transuranic (TRU) waste to the Waste Isolation Pilot Plant (WIPP) for disposal. In 1996 Sandia National Laboratories (SNL) conducted a series of tests to determine the degree of protection POCs provided during storage accident events. One of these tests exposed four of the POCs to a 30-minute engulfing pool fire, resulting in one of the 7A drum overpacks generating sufficient internal pressure to pop off its lid and expose the top of the pipe container (PC) to the fire environment. The initial contents of the POCs were inert materials, which would not generate large internal pressure within the PC if heated. POCs are now being used to store combustible TRU waste at Department of Energy (DOE) sites. At the request of DOE’s Office of Environmental Management (EM) and National Nuclear Security Administration (NNSA), starting in 2015 SNL conducted a series of fire tests to examine whether PCs with combustibles would reach a temperature that would result in (1) decomposition of inner contents and (2) subsequent generation of sufficient gas to cause the PC to over-pressurize and release its inner content. Tests conducted during 2015 and 2016 were done in three phases. The goal of the first phase was to see if the PC would reach high enough temperatures to decompose typical combustible materials inside the PC. The goal of the second test phase was to determine under what heating loads (i.e., incident heat fluxes) the 7A drum lid pops off from the POC drum. The goal of the third phase was to see if surrogate aerosol gets released from the PC when the drum lid is off. This report will describe the various tests conducted in phase I, II, and III, present preliminary results from these tests, and discuss implications for the POCs.

  11. Thermal Hydraulic Integral Effect Tests for Pressurized Water Reactors

    International Nuclear Information System (INIS)

    Baek, Won Pil; Song, C. H.; Kim, Y. S.

    2007-02-01

    The objectives of the project are to construct a thermal-hydraulic integral effect test facility and to perform the tests for design, operation, and safety regulation of pressurized water reactors. In the first phase of this project (1997.8∼2002.3), the basic technology for thermal-hydraulic integral effect tests was established and the basic design of the test facility was accomplished. In the second phase (2002.4∼2005.2), an optimized design of the ATLAS (Advanced Thermal-hydraulic Test Loop for Accident Simulation) was established and the construction of the facility was almost completed. In the third phase (2005.3∼2007.2), the construction and commission tests of the ATLAS are to be completed and some first-phase tests are to be conducted

  12. A study on corium melt pool behavior under external vessel cooling : investigation of the first phase research results in the OECD RASPLAV project

    Energy Technology Data Exchange (ETDEWEB)

    Park, Rae Joon; Kim, Sang Baik; Kim, Hee Dong; Yoo, Kun Joong

    1998-04-01

    The scope and contents of the OECD RASPLAV program are to investigate natural convection heat transfer in the corium, chemical and mechanical interaction between the corium and the reactor vessel, crust formation of the corium, and thermal behaviour of the corium by experiments and model development during external vessel cooling to prevent reactor vessel failure in severe accidents of nuclear power plant. This study includes evaluation and analysis of the RASPLAV V phase I results for three years between July 1, 1994 and June 30, 1997. These results supply technical basis for our experimental program on severe accident research. Two large-scale experiments of RASPLAV-AW-between the corium and the reactor vessel. Several small-scale experiments were conducted to analyze thermal stratification in the corium. The salt experiments were conducted to estimate the crust and the mushy region formation, and natural convection heat transfer in the corium. In the analytical studies, pre and post analysis of the RASPLAV-AW-200 experiments and evaluation of the salt test results have been performed using CONV 2 and 3D computer codes, which were developed during RASPLAV program phase I. Low density corium was separated from the high density corium during the RASPLAV-AW-200 tests and the TULPAN test, which was a new finding in the RASPLAV project phase I. From the salts test, heat flux distribution in the side wall heating case is similar to the direct internal heat generation case, and the crust formation is a little effect on heat transfer rate. The results of CONV 2 and 3 D were very well with with the experimental results. The results of RASLAV project phase I, such as furnace design and the techniques on fuel melting, are very helpful to our severe accident experimental program. (author). 57 refs., 13 tabs., 52 figs.

  13. First test results for an adjustable phase undulator

    International Nuclear Information System (INIS)

    Carr, R.; Nuhn, H.D.; Corbett, J.

    1992-01-01

    An Adjustable Phase Undulator (APU) was installed and tested on the beamline 5 of the SPEAR storage ring. The APU has the same magnetic structure as a conventional adjustable gap undulator (AGU), but its magnetic field is varied by changing the longitudinal position between the rows of magnets, while keeping the gap between them fixed. The tests described here show that this undulator performs according to theoretical predictions and numerical models. The main reason to consider a phase adjustable design is the substantial reduction in size, complexity, and cost over comparable conventional designs. (author) 4 refs.; 3 figs

  14. Acceptance test report, 241-SY-101 Flexible Receiver System, Phase 1 testing

    International Nuclear Information System (INIS)

    Ritter, G.A.

    1995-01-01

    This document summarizes the results of the Phase 1 acceptance test of the 241-SY-101 Flexible Receiver System (FRS). This acceptance test consisted of a pressure-decay/leak test of the containment bag to verify that the seams along the length of the bag had been adequately sealed. The sealing integrity of the FRS must be verified to ensure that the release of waste and aerosols will be minimized during the removal of the test mixer pump from Tank 241-SY-101. The FRS is one of six major components of the Equipment Removal System, which has been designed to retrieve, transport, and store the mixer pump. This acceptance test was performed at Lancs Industries in Kirkland, Washington on January 17, 1995. The bag temperature-compensated pressure loss of 575 Pa was below the acceptance criteria of 625 Pa and the test results were therefore found to be acceptable. The bag manufacturer estimates that 80--90% of the pressure loss is attributed to leakage around the bag inflation valve where the pressure gage was connected. A leak detector was applied over the entire bag during the pre-tests and no leakage was found. Furthermore, the leak rate corresponding to this pressure loss is very small when compared to the acceptable leak rate of the completely assembled FRS. The sealing integrity of the assembled FRS is verified in Phase 3 testing

  15. Project W-049H Collection System Acceptance Test

    International Nuclear Information System (INIS)

    Buckles, D.I.

    1994-01-01

    The Acceptance Test Procedure (ATP) Program for Project W-049H covers the following activities: Disposal system, Collection system, Instrumentation and control system. Each activity has its own ATP. The purpose of the ATPs is to verify that the systems have been constructed in accordance with the construction documents and to demonstrate that the systems function as required by the Project criteria. This ATP has been prepared to demonstrate that the Collection System Instrumentation functions as required by project criteria

  16. Prototypical Rod Construction Demonstration Project

    International Nuclear Information System (INIS)

    1993-05-01

    The objective of Phase 3 of the Prototypical Rod consolidation Demonstration Project (PRCDP) was to procure, fabricate, assemble, and test the Prototypical Rod consolidation System as described in the NUS Phase 2 Final Design Report. This effort required providing the materials, components, and fabricated parts which makes up all of the system equipment. In addition, it included the assembly, installation, and setup of this equipment at the Cold Test Facility. During the Phase 3 effort the system was tested on a component, subsystem, and system level. This volume 1, discusses the PRCDP Phase 3 Test Program that was conducted by the HALLIBURTON NUS Environmental Corporation under contract AC07-86ID12651 with the United States Department of Energy. This document, Volume 1, Book 3 discusses the following topics: Downender Test Results and Analysis Report; NFBC Canister Upender Test Results and Analysis Report; Fuel Assembly Handling Fixture Test Results and Analysis Report; and Fuel Canister Upender Test Results and Analysis Report

  17. Prototypical Rod Consolidation Demonstration Project

    International Nuclear Information System (INIS)

    1993-05-01

    The objective of Phase 3 of the Prototypical Rod consolidation Demonstration Project (PRCDP) was to procure, fabricate, assemble, and test the Prototypical Rod consolidation System as described in the NUS Phase 2 Final Design Report. This effort required providing the materials, components, and fabricated parts which makes up all of the system equipment. In addition, it included the assembly, installation, and setup of this equipment at the Cold Test Facility. During the Phase 3 effort the system was tested on a component, subsystem, and system level. This volume 1, discusses the PRCDP Phase 3 Test Program that was conducted by the HALLIBURTON NUS Environmental Corporation under contract AC07-86ID12651 with the United States Department of Energy. This document, Volume 1, Book 8 discusses Control System SOT Tests Results and Analysis Report. This is a continuation of Book 7

  18. Methodology Proposal for Increasing Swift Trust within Virtual Teams in the Inception Phase of a Project Life-Cycle: Project Manager’s Perspective

    Directory of Open Access Journals (Sweden)

    Milovanović Bojan Morić

    2015-12-01

    Full Text Available This paper proposes team building methodology for project managers in virtual teams as means to develop swift trust between new team members in the inception phase of the project life cycle. Proposed methodology encompasses activities within the first three days after the team formation and proposes the measuring tools for monitoring and managing trust development within the project team. Aim of this paper is to provide new insights to various decision makers potentially interested in increasing the performance of project teams operating in virtual environment, such as: investors, business owners and project managers working in virtual environment.

  19. Prototypical Rod Consolidation Demonstration Project

    International Nuclear Information System (INIS)

    1993-05-01

    The objective of Phase 3 of the Prototypical Rod consolidation Demonstration Project (PRCDP) was to procure, fabricate, assemble, and test the Prototypical Rod consolidation System as described in the NUS Phase 2 Final Design Report. This effort required providing the materials, components, and fabricated parts which makes up all of the system equipment. In addition, it included the assembly, installation, and setup of this equipment at the Cold Test Facility. During the Phase 3 effort the system was tested on a component, subsystem, and system level. This volume 1, discusses the PRCDP Phase 3 Test Program that was conducted by the HALLIBURTON NUS Environmental Corporation under contract AC07-86ID12651 with the United States Department of Energy. This document, Volume 1, Book 2 discusses the following topics: Fuel Rod Extraction System Test Results and Analysis Reports and Clamping Table Test Results and Analysis Reports

  20. Plutonium immobilization project development and testing technical project office quality assurance program description

    International Nuclear Information System (INIS)

    Gould, T.H.; MacLean, L.M.; Ziemba, J.M.

    1999-01-01

    The Plutonium Immobilization Project (PIP) is one of several fissile materials disposition projects managed by the Department of Energy (DOE) Office of Fissile Materials Disposition (OFMD). The PIP is expected to evolve from the current Development and Testing (D and T) effort, to design, to construction, and finally to operations. Overall management and technical management of the D and T effort resides at the Lead Laboratory, Lawrence Livermore National Laboratory (LLNL), through the LLNL Manager, Fissile Materials Disposition Program (FMDP). Day to day project activities are managed by the D and T Technical Project Office (TPO), which reports to the LLNL Manager, FMDP. The D and T TPO consists of the Technical Manager, the TPO Quality Assurance (QA) Program Manager, and TPO Planning and Support Staff. This Quality Assurance Program Description (QAPD) defines the QA policies and controls that will be implemented by these TPO personnel in their management of D and T activities. This QAPD is consistent with and responsive to the Department of Energy Fissile Materials Disposition Program Quality Assurance Requirements Document (FMDP QARD). As the Project and upper level requirement's documents evolve, this QAPD will be updated as necessary to accurately define and describe the QA Program and Management of the PIP. The TPO has a policy that all development and testing activities be planned, performed and assessed in accordance with its customer's requirements, needs and expectations, and with a commitment to excellence and continuous improvement. The TPO QAPD describes implementation requirements which, when completed, will ensure that the project development and testing activities conform to the appropriate QA requirements. For the program to be effective, the TPO QA Program Manager will ensure that each site participating in D and T activities has developed a QAPD, which meets the customer's requirements, and has a designated quality leader in place. These customer

  1. UTILITY ADVANCED TURBINE SYSTEMS (ATS) TECHNOLOGY READINESS TESTING: PHASE 3R

    Energy Technology Data Exchange (ETDEWEB)

    None

    1999-09-01

    The overall objective of the Advanced Turbine System (ATS) Phase 3 Cooperative Agreement between GE and the US Department of Energy (DOE) is the development of the GE 7H and 9H combined cycle power systems. The major effort will be expended on detail design. Validation of critical components and technologies will be performed, including: hot gas path component testing, sub-scale compressor testing, steam purity test trials, and rotational heat transfer confirmation testing. Processes will be developed to support the manufacture of the first system, which was to have been sited and operated in Phase 4 but will now be sited and operated commercially by GE. This change has resulted from DOE's request to GE for deletion of Phase 4 in favor of a restructured Phase 3 (as Phase 3R) to include full speed, no load (FSNL) testing of the 7H gas turbine. Technology enhancements that are not required for the first machine design but will be critical for future ATS advances in performance, reliability, and costs will be initiated. Long-term tests of materials to confirm design life predictions will continue. A schematic of the GE H machine is shown. This report summarizes work accomplished in 2Q99.

  2. Prototypical Rod Consolidation Demonstration Project

    International Nuclear Information System (INIS)

    1993-05-01

    The objective of Phase 3 of the Prototypical Rod consolidation Demonstration Project (PRCDP) was to procure, fabricate, assemble, and test the Prototypical Rod consolidation System as described in the NUS Phase 2 Final Design Report. This effort required providing the materials, components, and fabricated parts which makes up all of the system equipment. In addition, it included the assembly, installation, and setup of this equipment at the Cold Test Facility. During the Phase 3 effort the system was tested on a component, subsystem, and system level. This volume 1, discusses the PRCDP Phase 3 Test Program that was conducted by the HALLIBURTON NUS Environmental Corporation under contract AC07-86ID12651 with the United States Department of Energy. This document, Volume 1, Book 9 discusses the following topics: Integrated System Normal Operations Test Results and Analysis Report; Integrated System Off-Normal Operations Test Results and Analysis Report; and Integrated System Maintenance Operations Test Results and Analysis Report

  3. Test report for run-in acceptance testing of Project W-151 300 HP mixing pumps

    International Nuclear Information System (INIS)

    Berglin, B.G.

    1998-01-01

    This report documents the results of a performance demonstration and operational checkout of three 300 HP mixer pumps in accordance with WHC-SD-WI51-TS-001 ''Mixer Pump Test Specification for Project W-151'' and Statement of Work 8K520-EMN-95-004 ''Mixer Pump Performance Demonstration at MASF'' in the 400 Area Maintenance and Storage Facility (MASF) building. Testing of the pumps was performed by Fast Flux Test Facility (FFTF) Engineering and funded by the Tank Waste Remediation System (TWRS) Project W-151. Testing began with the first pump on 04-01-95 and ended with the third pump on 11-01-96. Prior to testing, the MASF was modified and prepared to meet the pump testing requirements set forth by the Test Specification and the Statement of Work

  4. Synthesized research report in the second mid-term research phase. Mizunami Underground Research Laboratory project, Horonobe Underground Research Laboratory project and geo-stability project

    International Nuclear Information System (INIS)

    Hama, Katsuhiro; Sasao, Eiji; Iwatsuki, Teruki; Saegusa, Hiromitsu; Sato, Toshinori; Umeda, Koji; Yasue, Kenichi; Asamori, Koichi; Osawa, Hideaki; Koide, Kaoru; Nagae, Isako; Natsuyama, Ryoko; Mizuno, Takashi; Fujita, Tomoo; Sasamoto, Hiroshi; Matsuoka, Toshiyuki; Yokota, Hideharu; Ishii, Eiichi; Aoyagi, Kazuhei; Nakayama, Masashi; Ito, Hiroaki; Tsusaka, Kimikazu; Ohyama, Takuya; Senba, Takeshi; Amano, Kenji

    2015-08-01

    We have synthesised the research results from Mizunami/Horonobe URLs and geo-stability projects in the second mid-term research phase. It could be used as technical bases for NUMO/Regulator in each decision point from siting to beginning of disposal (Principal Investigation to Detailed Investigation Phase). High quality construction techniques and field investigation methods have been developed and implemented and these will be directly applicable to the National Disposal Program (along with general assessments of hazardous natural events and processes). It will be crucial to acquire technical knowledge on decisions of partial backfilling and final closure by actual field experiments in Mizunami/Horonobe URLs as main themes for the next phases. (author)

  5. Backfilling and closure of the deep repository. Phase 3 - pilot tests to verify engineering feasibility. Geotechnical investigations made on unsaturated backfill materials

    International Nuclear Information System (INIS)

    Johannesson, Lars-Erik

    2008-12-01

    The investigations described in this report is a part of the third phase of the joint SKB-Posiva project 'Backfilling and Closure of the Deep Repository, BACLO'. The overall objective of the BACLO project is to develop backfilling concept for the deep repository that can be configured to meet SKB's and Posiva's requirements in the chosen repository sites. The project was divided into four phases, of which two have already been performed. The second phase of the BACLO project consisted of laboratory tests and deepened analyses of the investigated backfill materials and methods and resulted in recommendation to focus on the development and testing of the block placement concept with three alternative backfill materials. The third phase investigations comprise of laboratory and large-scale experiments aiming at testing the engineering feasibility of the concept. In addition, how site-specific constraints, backfilling method and materials affect the long-term functions of the barriers will be described and analysed in order to set design specifications for the backfill. The third phase of the BACLO project is divided into several subprojects. The work described in this report belongs to subproject 1 concerning processes during installation and saturation of the backfill that may affect the long-term function of the bentonite buffer and the backfill itself. One of the main functions of backfill is to restrict buffer expansion which can lead to decrease in buffer density in the deposition hole. The criterion used as a basis for the Baclo investigations was that the buffer density at saturation should not be below 1,950 kg/m 3 at the level of the canister. The same criterion was applied for the work described in this report. The upward swelling of the buffer and the enclosed compression of the backfill was first studied assuming that both the buffer and the backfill were saturated. The main objective of this work was to study a case where the buffer is fully saturated

  6. Backfilling and closure of the deep repository. Phase 3 - pilot tests to verify engineering feasibility. Geotechnical investigations made on unsaturated backfill materials

    Energy Technology Data Exchange (ETDEWEB)

    Johannesson, Lars-Erik (Clay Technology AB, Lund (Sweden))

    2008-12-15

    The investigations described in this report is a part of the third phase of the joint SKB-Posiva project 'Backfilling and Closure of the Deep Repository, BACLO'. The overall objective of the BACLO project is to develop backfilling concept for the deep repository that can be configured to meet SKB's and Posiva's requirements in the chosen repository sites. The project was divided into four phases, of which two have already been performed. The second phase of the BACLO project consisted of laboratory tests and deepened analyses of the investigated backfill materials and methods and resulted in recommendation to focus on the development and testing of the block placement concept with three alternative backfill materials. The third phase investigations comprise of laboratory and large-scale experiments aiming at testing the engineering feasibility of the concept. In addition, how site-specific constraints, backfilling method and materials affect the long-term functions of the barriers will be described and analysed in order to set design specifications for the backfill. The third phase of the BACLO project is divided into several subprojects. The work described in this report belongs to subproject 1 concerning processes during installation and saturation of the backfill that may affect the long-term function of the bentonite buffer and the backfill itself. One of the main functions of backfill is to restrict buffer expansion which can lead to decrease in buffer density in the deposition hole. The criterion used as a basis for the Baclo investigations was that the buffer density at saturation should not be below 1,950 kg/m3 at the level of the canister. The same criterion was applied for the work described in this report. The upward swelling of the buffer and the enclosed compression of the backfill was first studied assuming that both the buffer and the backfill were saturated. The main objective of this work was to study a case where the buffer is

  7. Prototype Repository. Tracer dilution tests during operation phase, test campaign 3

    Energy Technology Data Exchange (ETDEWEB)

    Harrstroem, Johan; Andersson, Peter (Geosigma AB (Sweden))

    2010-05-15

    The Prototype Repository project is focused on testing and demonstrating the function of the SKB deep repository system. The third tracer dilution campaign during the Prototype Repository operation period was performed in January 2010. The purpose was to estimate the groundwater flows and hydraulic gradients in the boreholes vicinity and will function as a reference for comparison with results from modeling and prior assumptions. The test campaign consisted of tracer dilution tests in 13 different borehole sections. Each test consisted of approximately 15-55 min tracer injection time and about 1-3 days dilution test time depending on the transmissivity of the test section. The data interpretation also included estimates of the local hydraulic gradients in the vicinity of the borehole sections

  8. Study on operation I and C DCS test method of EPR project

    International Nuclear Information System (INIS)

    Meng Ying; Lv Zhihong; Huang Xinnian; Fan Haiying; Li Zhuojia; Xiao Shushu

    2014-01-01

    Through summarization and optimization of the method for operation I and C DCS test of the European pressurized reactor project, the conclusions play a guiding role on the operation I and C DCS test of the domestic advanced nuclear power plant. The study of the method focuses on the test platform, the test process and the optimization of method of operation I and C DCS test with the practical experience. The reasonable and reliable test method for operation I and C DCS test of the European pressurized reactor project is worthy of the reference and the development in the project of the domestic advanced nuclear power plant. (authors)

  9. In Situ Decommissioning Sensor Network, Meso-Scale Test Bed - Phase 3 Fluid Injection Test Summary Report

    International Nuclear Information System (INIS)

    Serrato, M. G.

    2013-01-01

    The DOE Office of Environmental management (DOE EM) faces the challenge of decommissioning thousands of excess nuclear facilities, many of which are highly contaminated. A number of these excess facilities are massive and robust concrete structures that are suitable for isolating the contained contamination for hundreds of years, and a permanent decommissioning end state option for these facilities is in situ decommissioning (ISD). The ISD option is feasible for a limited, but meaningfull number of DOE contaminated facilities for which there is substantial incremental environmental, safety, and cost benefits versus alternate actions to demolish and excavate the entire facility and transport the rubble to a radioactive waste landfill. A general description of an ISD project encompasses an entombed facility; in some cases limited to the blow-grade portion of a facility. However, monitoring of the ISD structures is needed to demonstrate that the building retains its structural integrity and the contaminants remain entombed within the grout stabilization matrix. The DOE EM Office of Deactivation and Decommissioning and Facility Engineering (EM-13) Program Goal is to develop a monitoring system to demonstrate long-term performance of closed nuclear facilities using the ISD approach. The Savannah River National Laboratory (SRNL) has designed and implemented the In Situ Decommissioning Sensor Network, Meso-Scale Test Bed (ISDSN-MSTB) to address the feasibility of deploying a long-term monitoring system into an ISD closed nuclear facility. The ISDSN-MSTB goal is to demonstrate the feasibility of installing and operating a remote sensor network to assess cementitious material durability, moisture-fluid flow through the cementitious material, and resulting transport potential for contaminate mobility in a decommissioned closed nuclear facility. The original ISDSN-MSTB installation and remote sensor network operation was demonstrated in FY 2011-12 at the ISDSN-MSTB test cube

  10. In Situ Decommissioning Sensor Network, Meso-Scale Test Bed - Phase 3 Fluid Injection Test Summary Report

    Energy Technology Data Exchange (ETDEWEB)

    Serrato, M. G.

    2013-09-27

    The DOE Office of Environmental management (DOE EM) faces the challenge of decommissioning thousands of excess nuclear facilities, many of which are highly contaminated. A number of these excess facilities are massive and robust concrete structures that are suitable for isolating the contained contamination for hundreds of years, and a permanent decommissioning end state option for these facilities is in situ decommissioning (ISD). The ISD option is feasible for a limited, but meaningfull number of DOE contaminated facilities for which there is substantial incremental environmental, safety, and cost benefits versus alternate actions to demolish and excavate the entire facility and transport the rubble to a radioactive waste landfill. A general description of an ISD project encompasses an entombed facility; in some cases limited to the blow-grade portion of a facility. However, monitoring of the ISD structures is needed to demonstrate that the building retains its structural integrity and the contaminants remain entombed within the grout stabilization matrix. The DOE EM Office of Deactivation and Decommissioning and Facility Engineering (EM-13) Program Goal is to develop a monitoring system to demonstrate long-term performance of closed nuclear facilities using the ISD approach. The Savannah River National Laboratory (SRNL) has designed and implemented the In Situ Decommissioning Sensor Network, Meso-Scale Test Bed (ISDSN-MSTB) to address the feasibility of deploying a long-term monitoring system into an ISD closed nuclear facility. The ISDSN-MSTB goal is to demonstrate the feasibility of installing and operating a remote sensor network to assess cementitious material durability, moisture-fluid flow through the cementitious material, and resulting transport potential for contaminate mobility in a decommissioned closed nuclear facility. The original ISDSN-MSTB installation and remote sensor network operation was demonstrated in FY 2011-12 at the ISDSN-MSTB test cube

  11. Status of JSFR development in phase I FaCT project

    International Nuclear Information System (INIS)

    Aoto, Kazumi; Chikazawa, Yoshitaka; Kotake, Shoji; Ito, Takaya

    2011-01-01

    The Fast Reactor Cycle Technology Development (FaCT) project is pursuing commercialization of fast reactor cycle system around 2050 under cooperation of MEXT (Ministry of Education, Culture, Sports, Science and Technology), METI (Ministry of Economy, Trade and Industry), utilities, venders and JAEA (Japan Atomic Energy Agency). As results of the FaCT Phase I, the key technologies for Japan Sodium-cooled Fast Reactor (JSFR) has been evaluated. (author)

  12. United States Advanced Ultra-Supercritical Component Test Facility for 760°C Steam Power Plants ComTest Project

    Energy Technology Data Exchange (ETDEWEB)

    Hack, Horst [Electric Power Research Institute (EPRI); Purgert, Robert Michael [Energy Industries of Ohio

    2017-12-13

    C). The steam turbine stop and control valve component has been designed to operate at full A-USC temperatures, and would be tested both in throttling operation and to accumulate accelerated, repetitive stroke cycles. A cycling header component has been designed to confirm the suitability of new high-temperature nickel alloys to cycling operation, expected of future coal-fired power plants. Current test plans would subject these components to A-USC operating conditions for at least 8,000 hours by September 2020. The ComTest project is managed by Energy Industries of Ohio, and technically directed by the Electric Power Research Institute, Inc., with General Electric designing the A-USC components. This consortium is completing the Detailed Engineering phase of the project, with procurement scheduled to begin in late 2017. The effort is primarily funded by the U.S. Department of Energy, through the National Energy Technology Laboratory, along with the Ohio Development Services Agency. This presentation outlines the motivation for the project, explains the project’s structure and schedule, and provides technical details on the design of the ComTest facility.

  13. Queer signs: The women of the British projective test movement.

    Science.gov (United States)

    Hubbard, Katherine

    2017-07-01

    As queer history is often hidden, historians must look for "signs" that hint at queer lives and experiences. When psychologists use projective tests, the search for queer signs has historically been more literal, and this was especially true in the homophobic practices of Psychology in the mid-twentieth century. In this paper, I respond to Elizabeth Scarborough's call for more analytic history about the lesser known women in Psychology's history. By focusing on British projective research conducted by lesbian psychologist June Hopkins, I shift perspective and consider, not those who were tested (which has been historically more common), but those who did the testing, and position them as potential queer subjects. After briefly outlining why the projective test movement is ripe for such analysis and the kinds of queer signs that were identified using the Rorschach ink blot test in the mid-twentieth century, I then present June Hopkins' (1969, 1970) research on the "lesbian personality." This work forms a framework upon which I then consider the lives of Margaret Lowenfeld, Ann Kaldegg, and Effie Lillian Hutton, all of whom were involved in the British projective test movement a generation prior to Hopkins. By adopting Hopkins' research to frame their lives, I present the possibility of this ambiguous history being distinctly queer. © 2017 Wiley Periodicals, Inc.

  14. Operations planning and analysis handbook for NASA/MSFC phase B development projects

    Science.gov (United States)

    Batson, Robert C.

    1986-01-01

    Current operations planning and analysis practices on NASA/MSFC Phase B projects were investigated with the objectives of (1) formalizing these practices into a handbook and (2) suggesting improvements. The study focused on how Science and Engineering (S&E) Operational Personnel support Program Development (PD) Task Teams. The intimate relationship between systems engineering and operations analysis was examined. Methods identified for use by operations analysts during Phase B include functional analysis, interface analysis methods to calculate/allocate such criteria as reliability, Maintainability, and operations and support cost.

  15. Risk level project. Summary report, Norwegian Shelf, Phase 7; Risikonivaaprosjektet. Sammendragsrapport Norsk Sokkel, fase 7

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2007-04-15

    The project 'developments in risk level - Norwegian shelf', also known as the risk level project, was initiated by the Norwegian Petroleum Directorate in 2000. From 2004 the project has been continued by Petroleum Safety Authority Norway. The project's main objectives are to measure the effect of the health, security and environment (HSE) work in the industry, and contribute to identify the areas critical to HSE, where efforts must be made to prevent unwanted events or accidents. A summary report with results from phase 7 in the project (ml)

  16. Environmental assessment report: Nuclear Test Technology Complex

    International Nuclear Information System (INIS)

    Tonnessen, K.; Tewes, H.A.

    1982-08-01

    The US Department of Energy (USDOE) is planning to construct and operate a structure, designated the Nuclear Test Technology Complex (NTTC), on a site located west of and adjacent to the Lawrence Livermore National Laboratory. The NTTC is designed to house 350 nuclear test program personnel, and will accommodate the needs of the entire staff of the continuing Nuclear Test Program (NTP). The project has three phases: land acquisition, facility construction and facility operation. The purpose of this environmental assessment report is to describe the activities associated with the three phases of the NTTC project and to evaluate potential environmental disruptions. The project site is located in a rural area of southeastern Alameda County, California, where the primary land use is agriculture; however, the County has zoned the area for industrial development. The environmental impacts of the project include surface disturbance, high noise levels, possible increases in site erosion, and decreased air quality. These impacts will occur primarily during the construction phase of the NTTC project and can be mitigated in part by measures proposed in this report

  17. Small business innovation research. Abstracts of completed 1987 phase 1 projects

    Science.gov (United States)

    1989-01-01

    Non-proprietary summaries of Phase 1 Small Business Innovation Research (SBIR) projects supported by NASA in the 1987 program year are given. Work in the areas of aeronautical propulsion, aerodynamics, acoustics, aircraft systems, materials and structures, teleoperators and robotics, computer sciences, information systems, spacecraft systems, spacecraft power supplies, spacecraft propulsion, bioastronautics, satellite communication, and space processing are covered.

  18. Draft Air Pathway Report: Phase 1 of the Hanford Environmental Dose Reconstruction Project

    Energy Technology Data Exchange (ETDEWEB)

    1990-07-20

    This report summarizes the air pathway portion of the first phase of the Hanford Environmental Dose Reconstruction (HEDR) Project, conducted by Battelle staff at the Pacific Northwest Laboratory under the direction of an independent Technical Steering Panel. The HEDR Project is estimating historical radiation doses that could have been received by populations near the Department of Energy's Hanford Site, in southeastern Washington State. Phase 1 of the air-pathway dose reconstruction sought to determine whether dose estimates could be calculated for populations in the 10 counties nearest the Hanford Site from atmospheric releases of iodine-131 from the site from 1944--1947. Phase 1 demonstrated the following: HEDR-calculated source-term estimates of iodine-131 releases to the atmosphere were within 20% of previously published estimates; calculated vegetation concentrations of iodine-131 agree well with previously published measurements; the highest of the Phase 1 preliminary dose estimates to the thyroid are consistent with independent, previously published estimates of doses to maximally exposed individuals; and relatively crude, previously published measurements of thyroid burdens for Hanford workers are in the range of average burdens that the HEDR model estimated for similar reference individuals'' for the period 1944--1947. 4 refs., 10 figs., 9 tabs.

  19. Multilayer Pressure Vessel Materials Testing and Analysis. Phase 1

    Science.gov (United States)

    Cardinal, Joseph W.; Popelar, Carl F.; Page, Richard A.

    2014-01-01

    To provide NASA a comprehensive suite of materials strength, fracture toughness and crack growth rate test results for use in remaining life calculations for aging multilayer pressure vessels, Southwest Research Institute (R) (SwRI) was contracted in two phases to obtain relevant material property data from a representative vessel. This report describes Phase 1 of this effort which includes a preliminary material property assessment as well as a fractographic, fracture mechanics and fatigue crack growth analyses of an induced flaw in the outer shell of a representative multilayer vessel that was subjected to cyclic pressure test. SwRI performed this Phase 1 effort under contract to the Digital Wave Corporation in support of their contract to Jacobs ATOM for the NASA Ames Research Center.

  20. Simplified absolute phase retrieval of dual-frequency fringe patterns in fringe projection profilometry

    Science.gov (United States)

    Lu, Jin; Mo, Rong; Sun, Huibin; Chang, Zhiyong; Zhao, Xiaxia

    2016-04-01

    In fringe projection profilometry, a simplified method is proposed to recover absolute phase maps of two-frequency fringe patterns by using a unique mapping rule. The mapping rule is designed from the rounded phase values to the fringe order of each pixel. Absolute phase can be recovered by the fringe order maps. Unlike the existing techniques, where the lowest frequency of dual- or multiple-frequency fringe patterns must be single, the presented method breaks the limitation and simplifies the procedure of phase unwrapping. Additionally, due to many issues including ambient light, shadow, sharp edges, step height boundaries and surface reflectivity variations, a novel framework of automatically identifying and removing invalid phase values is also proposed. Simulations and experiments have been carried out to validate the performances of the proposed method.

  1. Improvement of ultrasonic testing by use of phased arrays

    International Nuclear Information System (INIS)

    Gebhardt, W; Bonitz, F.; Woll, H.

    1983-01-01

    The paper examines the applicability of phased-array technology in non-destructive material testing for quality control, basic inspection and in-service inspections of the primary containment of nuclear power plants. Initial experiments on sonic aigrette control, defect margin reconstruction and the classification of defects have been carried out using medical equipment as commercially available which had been modified for non-destructive applications. At the same time, a for more flexible microcomputer-controlled phased-array system was developed, particularly designed for material testing. (orig./RW) [de

  2. Maqarin natural analogue project: Phase IV. Reconnaissance mission report (April 28 to May 7, 1999)

    International Nuclear Information System (INIS)

    Smellie, J.A.T.

    2000-08-01

    Final planning of the Technical Proposal for Phase IV of the Maqarin Natural Analogue Project was preceded by a ten day Reconnaissance Mission to the Jordan sites. The main objective of this mission was to: i) allow new organisations within the project to become familiar with the geological context of the Maqarin and Central Jordan sites and also to appreciate the prevailing technical and logistical limitations, ii) carry out limited field investigations, and iii) based on the experience from these two points, provide the opportunity to finalise the Maqarin Phase IV Technical Proposal. This report details the results of the mission

  3. Maqarin natural analogue project: Phase IV. Reconnaissance mission report (April 28 to May 7, 1999)

    Energy Technology Data Exchange (ETDEWEB)

    Smellie, J.A.T. [ed.] [Conterra AB, Uppsala (Sweden)

    2000-08-01

    Final planning of the Technical Proposal for Phase IV of the Maqarin Natural Analogue Project was preceded by a ten day Reconnaissance Mission to the Jordan sites. The main objective of this mission was to: i) allow new organisations within the project to become familiar with the geological context of the Maqarin and Central Jordan sites and also to appreciate the prevailing technical and logistical limitations, ii) carry out limited field investigations, and iii) based on the experience from these two points, provide the opportunity to finalise the Maqarin Phase IV Technical Proposal. This report details the results of the mission.

  4. Prototypical Rod Consolidation Demonstration Project

    International Nuclear Information System (INIS)

    1993-05-01

    The objective of Phase 3 of the Prototypical Rod consolidation Demonstration Project (PRCDP) was to procure, fabricate, assemble, and test the Prototypical Rod consolidation System as described in the NUS Phase 2 Final Design Report. This effort required providing the materials, components, and fabricated parts which makes up all of the system equipment. In addition, it included the assembly, installation, and setup of this equipment at the Cold Test Facility. During the Phase 3 effort the system was tested on a component, subsystem, and system level. This volume 1, discusses the PRCDP Phase 3 Test Program that was conducted by the HALLIBURTON NUS Environmental Corporation under contract AC07-86ID12651 with the United States Department of Energy. This document, Volume 1, Book 4 discusses the following topics: Rod Compaction/Loading System Test Results and Analysis Report; Waste Collection System Test Results and Analysis Report; Waste Container Transfer Fixture Test Results and Analysis Report; Staging and Cutting Table Test Results and Analysis Report; and Upper Cutting System Test Results and Analysis Report

  5. Prototypical Rod Consolidation Demonstration Project

    International Nuclear Information System (INIS)

    1993-05-01

    The objective of Phase 3 of the Prototypical Rod consolidation Demonstration Project (PRCDP) was to procure, fabricate, assemble, and test the Prototypical Rod consolidation System as described in the NUS Phase 2 Final Design Report. This effort required providing the materials, components, and fabricated parts which makes up all of the system equipment. In addition, it included the assembly, installation, and setup of this equipment at the Cold Test Facility. During the Phase 3 effort the system was tested on a component, subsystem, and system level. This volume 1, discusses the PRCDP Phase 3 Test Program that was conducted by the HALLIBURTON NUS Environmental Corporation under contract AC07-86ID12651 with the United States Department of Energy. This document, Volume 1, Book 5 discusses the following topics: Lower Cutting System Test Results and Analysis Report; NFBC Loading System Test Results and Analysis Report; Robotic Bridge Transporter Test Results and Analysis Report; RM-10A Remotec Manipulator Test Results and Analysis Report; and Manipulator Transporter Test Results and Analysis Report

  6. Profilometry of discontinuous solids by means of co-phased demodulation of projected fringes with RGB encoding

    Science.gov (United States)

    Padilla, J. M.; Servin, M.; Garnica, G.

    2015-05-01

    Here we describe a 2-projectors and 1-camera setup for profilometry of discontinuous solids by means of co-phased demodulation of projected fringes and red, green, and blue (RGB) multichannel operation. The dual projection configuration for this profilometer is proposed to solve efficiently specular regions and self-occluding shadows due to discontinuities, which are the main drawbacks for a 1-projector 1-camera configuration. This is because the regions where shadows and specular reflections are generated, and the fringe contrast drops to zero, are in general different for each projection direction; thus, the resulting fringe patterns will have complementary phase information. Multichannel RGB operation allows us to work simultaneously with both projectors and to record independently the complementary fringe patterns phase-modulated by the 3D profile of the object under study. In other words, color encoding/decoding reduces the acquisition time respect to one-at-a-time grayscale operation and, in principle, enables the study of dynamic phenomena. The co-phased demodulation method implemented in this work benefits from the complex (analytic) nature of the output signals estimated with most phase demodulation methods (such as the Fourier method, and temporal phaseshifting algorithms). This allowed us to straightforwardly generate a single phase-map well-defined for the entire area of interest. Finally we assessed our proposed profilometry setup by measuring a fractured spherical cap made of (uncoated) expanded polystyrene. The results were satisfactory but in the authors' opinion this must be considered a preliminary report.

  7. Engineering Work Plan for the Development of Phased Startup Initiative (PSI) Phases 3 and 4 Test Equipment

    International Nuclear Information System (INIS)

    PITNER, A.L.

    2000-01-01

    A number of tools and equipment pieces are required to facilitate planned test operations during Phases 3 and 4 of the Phased Startup Initiative (PSI). These items will be used in assessing residual canister sludge quantities on cleaned fuel assemblies, sorting coarse and fine scrap fuel pieces, assessing the size distribution of scrap pieces, loading scrap into a canister, and measuring the depth of the accumulated scrap in a canister. This work plan supercedes those previously issued for development of several of these test items. These items will be considered prototype equipment until testing has confirmed their suitability for use in K West Basin. The process described in AP-EN-6-032 will be used to qualify the equipment for facility use. These items are considered non-OCRWM for PSI Phase 3 applications. The safety classification of this equipment is General Service, with Quality Level 0 (for PSI Phase 3). Quality Control inspections shall be performed to verify basic dimensions and overall configurations of fabricated components, and any special quality control verifications specified in this work plan (Section 3.1.5). These inspections shall serve to approve the test equipment for use in K West Basin (Acceptance Tag). This equipment is for information gathering only during PSI Phases 3 and 4 activities, and will be discarded at the completion of PSI. For equipment needed to support actual production throughput, development/fabrication/testing activities would be more rigorously controlled

  8. International Uranium Resources Evaluation Project (IUREP) orientation phase mission summary report: Somalia

    International Nuclear Information System (INIS)

    1985-01-01

    A full report has been compiled describing the findings of the International Uranium Resources Evaluation Project (IUREP) Orientation Phase Mission to Somalia. The Mission suggests that in addition to the reasonably assured resources (RAR) of 5 000 t uranium and estimated additional resources (EAR) of 11 000 t uranium in calcrete deposits, the speculative resources (SR) could be within the wide range of 0 - 150 000 t uranium. The majority of these speculative resources are related to sandstone and calcrete deposits. The potential for magmatic hydrothermal deposits is relatively small. The Mission recommends an exploration programme of about US$ 22 000 000 to test the uranium potential of the country which is thought to be excellent. The Mission also suggests a reorganization of the Somalia Geological Survey in order to improve its efficiency. Recommended methods include geological mapping, Landsat imagery interpretation, airborne and ground scintillometer surveys, and geochemistry. Follow-up radiometric surveys, exploration geophysics, mineralogical studies, trenching and drilling are proposed in favourable areas. (author)

  9. Youth's social network structures and peer influences: study protocol MyMovez project - Phase I.

    Science.gov (United States)

    Bevelander, Kirsten E; Smit, Crystal R; van Woudenberg, Thabo J; Buijs, Laura; Burk, William J; Buijzen, Moniek

    2018-04-16

    Youth are an important target group for social network interventions, because they are particularly susceptible to the adaptation of healthy and unhealthy habits and behaviors of others. They are surrounded by 'social influence agents' (i.e., role models such as family, friends and peers) that co-determine their dietary intake and physical activity. However, there is a lack of systematic and comprehensive research on the implementation of a social network approach in health campaigns. The MyMovez research project aims to fill this gap by developing a method for effective social network campaign implementation. This protocol paper describes the design and methods of Phase I of the MyMovez project, aiming to unravel youth's social network structures in combination with individual, psychosocial, and environmental factors related to energy intake and expenditure. In addition, the Wearable Lab is developed to enable an attractive and state-of-the-art way of collecting data and online campaign implementation via social networks. Phase I of the MyMovez project consists of a large-scale cross-sequential cohort study (N = 953; 8-12 and 12-15 y/o). In five waves during a 3-year period (2016-2018), data are collected about youth's social network exposure, media consumption, socialization experiences, psychological determinants of behavior, physical environment, dietary intake (snacking and drinking behavior) and physical activity using the Wearable Lab. The Wearable Lab exists of a smartphone-based research application (app) connected to an activity tracking bracelet, that is developed throughout the duration of the project. It generates peer- and self-reported (e.g., sociometric data and surveys) and experience sampling data, social network beacon data, real-time physical activity data (i.e., steps and cycling), location information, photos and chat conversation data from the app's social media platform Social Buzz. The MyMovez project - Phase I is an innovative cross

  10. Marviken test-data interpretation, second project

    International Nuclear Information System (INIS)

    Collen, J.; Johansson, A.

    1978-12-01

    A brief description is given of the investigations carried out and the corclusions drawn within the MARTIN-II project, which involved the evaluation and interpretation of the data from the full scale containment response tests at the Marviken Power Station. The data from the tests, which were completed in 1976, provide information about the periodic pressure oscillations and rapid pressure spikes induced in the pressure-suppression containment during study comprise the following items: - Influence of test parameters on pressure oscillations and pressure spikes - Pressure spikes in the wetwell pool - High frequency oscillations - Comparisons between single-pipe and multi-pipe data The study was carried out by Studsvik Energiteknik AB with consulting efforts from AB ASEA-ATOM. It was financed by the Swedish Nuclear Power Inspectorate. (Auth.)

  11. Manual for operation of the multipurpose thermalhydraulic test facility TOPFLOW (Transient Two Phase Flow Test Facility)

    International Nuclear Information System (INIS)

    Beyer, M.; Carl, H.; Schuetz, H.; Pietruske, H.; Lenk, S.

    2004-07-01

    The Forschungszentrum Rossendorf (FZR) e. V. is constructing a new large-scale test facility, TOPFLOW, for thermalhydraulic single effect tests. The acronym stands for transient two phase flow test facility. It will mainly be used for the investigation of generic and applied steady state and transient two phase flow phenomena and the development and validation of models of computational fluid dynamic (CFD) codes. The manual of the test facility must always be available for the staff in the control room and is restricted condition during operation of personnel and also reconstruction of the facility. (orig./GL)

  12. Testing for Sphericity in Phase I Control Chart Applications

    DEFF Research Database (Denmark)

    Windfeldt, Gitte Bjørg; Bisgaard, Søren

    2009-01-01

    , to check this assumption. We supply a graph of the exact percentage points for the distribution of the test statistics. The test statistics can be computed with standard statistical software. Together with the graph of the exact percentage points, the test can easily be performed during a phase I study. We...

  13. Building Energy Simulation Test for Existing Homes (BESTEST-EX); Phase 1 Test Procedure: Building Thermal Fabric Cases

    Energy Technology Data Exchange (ETDEWEB)

    Judkoff, R.; Polly, B.; Bianchi, M.; Neymark, J.

    2010-08-01

    The U.S. Department of Energy tasked NREL to develop a process for testing the reliability of models that predict retrofit energy savings, including their associated calibration methods. DOE asked NREL to conduct the work in phases so that a test procedure would be ready should DOE need it to meet legislative requirements related to residential retrofits in FY 2010. This report documents the initial 'Phase 1' test procedure.

  14. Vectra GSI, Inc. low-level waste melter testing Phase 1 test report

    Energy Technology Data Exchange (ETDEWEB)

    Stegen, G.E.; Wilson, C.N.

    1996-02-21

    A multiphase program was initiated in 1994 to test commercially available melter technologies for the vitrification of the low-level waste (LLW) stream from defense wastes stored in underground tanks at the Hanford Site in southeastern Washington State. Vectra GSI, Inc. was one of seven vendors selected for Phase 1 of the melter demonstration tests using simulated LLW that were completed during fiscal year 1995. The attached report prepared by Vectra GSI, Inc. describes results of melter testing using slurry feed and dried feeds. Results of feed drying and prereaction tests using a fluid bed calciner and rotary dryer also are described.

  15. Vectra GSI, Inc. low-level waste melter testing Phase 1 test report

    International Nuclear Information System (INIS)

    Stegen, G.E.; Wilson, C.N.

    1996-01-01

    A multiphase program was initiated in 1994 to test commercially available melter technologies for the vitrification of the low-level waste (LLW) stream from defense wastes stored in underground tanks at the Hanford Site in southeastern Washington State. Vectra GSI, Inc. was one of seven vendors selected for Phase 1 of the melter demonstration tests using simulated LLW that were completed during fiscal year 1995. The attached report prepared by Vectra GSI, Inc. describes results of melter testing using slurry feed and dried feeds. Results of feed drying and prereaction tests using a fluid bed calciner and rotary dryer also are described

  16. Self-correction of projector nonlinearity in phase-shifting fringe projection profilometry.

    Science.gov (United States)

    Lü, Fuxing; Xing, Shuo; Guo, Hongwei

    2017-09-01

    In phase-shifting fringe projection profilometry, the luminance nonlinearity of the used projector has been recognized as one of the most crucial factors decreasing the measurement accuracy. To solve this problem, this paper presents a self-correcting technique that allows us to suppress the effect of the projector nonlinearity in the absence of any calibration data regarding the projector intensities or regarding the phase errors. In its first step, the standard phase-shifting algorithm is used to recover the phases, as well as the background intensities and the modulations. Using these results enables normalizing the fringe patterns, for ridding them of the effects of the background and modulations. Second, we smooth the calculated phase map by use of a low-pass filter in order to remove the ripple-like phase errors induced by the projector nonlinearity. Third, we determine a polynomial representing the projector nonlinearity by fitting the curve of the normalized fringe intensities against the cosine values of the smoothed phases. Finally, we correct the phase errors using the curve just obtained. Doing these steps in an iterative way eventually results in a phase map and, further, a 3D shape with their artifacts induced by the projector nonlinearity suppressed significantly. Experimental results demonstrate that this technique offers some advantages over others. It does not require a prior calibration of the projector, thus being suitable for dealing with a time-variant nonlinearity; its pointwise operation protects the edges and details of the measurement results from being blurred; and it works well with very few fringe patterns and is efficient in image capturing.

  17. A process dissociation approach to objective-projective test score interrelationships.

    Science.gov (United States)

    Bornstein, Robert F

    2002-02-01

    Even when self-report and projective measures of a given trait or motive both predict theoretically related features of behavior, scores on the 2 tests correlate modestly with each other. This article describes a process dissociation framework for personality assessment, derived from research on implicit memory and learning, which can resolve these ostensibly conflicting results. Research on interpersonal dependency is used to illustrate 3 key steps in the process dissociation approach: (a) converging behavioral predictions, (b) modest test score intercorrelations, and (c) delineation of variables that differentially affect self-report and projective test scores. Implications of the process dissociation framework for personality assessment and test development are discussed.

  18. Project B610 process control configuration acceptance test report

    International Nuclear Information System (INIS)

    Silvan, G.R.

    1995-01-01

    The purpose of this test is to verify the Westinghouse configuration of the MICON A/S Distributed Control System for project B610. The following will be verified: (1) proper assignment and operation of all field inputs to and outputs from the MICON Termination panels; (2) proper operation of all display data on the operators' console; (3) proper operation of all required alarms; and (4) proper operation of all required interlocks. This test only verifies the proper operation of the Westinghouse control configuration (or program). It will not be responsible for verifying proper operation of the MICON hardware or operating software. Neither does it test any of the B610 instrument. The MICON hardware and software has been tested as part of the equipment procurement. Instrumentation and wiring installed under project B620 will be tested under a separate functional test. In some cases, precise transmitter ranges, alarm setpoints, and controller tuning parameters are not available at this time. Therefore, approximate values are used during the test. This should not affect the proper operation of the configuration or the validity of this test. Final values will be assigned during operability testing

  19. Acceptance test procedure for Project W-049H

    International Nuclear Information System (INIS)

    Buckles, D.I.

    1994-01-01

    The Acceptance Test Procedure (ATP) program for Project W-049H (200 Area Treated Effluent Disposal Facility [TEDF]) covers three activities as follows: (1) Disposal System; (2) Collection System; and (3) Instrumentation and Control System. Each activity has its own ATP. The purpose of the ATPs is to reverify that the systems have been constructed in accordance with the construction documents and to demonstrate that the systems function as required by the Project criteria. The Disposal System ATP covers the testing of the following: disposal line flowmeters, room air temperatures in the Disposal Station Sampling Building, effluent valves and position indicators, disposal pond level monitors, automated sampler, pressure relief valves, and overflow diversion sluice gates. The Collection System ATP covers the testing of the two pump stations and all equipment installed therein. The Instrumentation and Control (I and C) ATP covers the testing of the entire TEDF I and C system. This includes 3 OCS units, modem, and GPLI cabinets in the ETC control room; 2 pump stations; disposal station sampling building; and all LCUs installed in the field

  20. CALLA ENERGY BIOMASS COFIRING PROJECT

    International Nuclear Information System (INIS)

    Unknown

    2002-01-01

    The Calla Energy Biomass Project, to be located in Estill County, Kentucky is to be conducted in two phases. The objective of Phase I is to evaluate the technical and economic feasibility of cofiring biomass-based gasification fuel-gas in a power generation boiler. Waste coal fines are to be evaluated as the cofired fuel. The project is based on the use of commercially available technology for feeding and gas cleanup that would be suitable for deployment in municipal, large industrial and utility applications. Define a combustion system for the biomass gasification-based fuel-gas capable of stable, low-NOx combustion over the full range of gaseous fuel mixtures, with low carbon monoxide emissions and turndown capabilities suitable for large-scale power generation applications. The objective for Phase II is to design, install and demonstrate the combined gasification and combustion system in a large-scale, long-term cofiring operation to promote acceptance and utilization of indirect biomass cofiring technology for large-scale power generation applications. During this Performance Period work efforts focused on completion of the Topical Report, summarizing the design and techno-economic study of the project's feasibility. GTI received supplemental authorization A002 from DOE contracts for additional work to be performed under Phase I that will further extend the performance period until the end of February 2003. The additional scope of work is for GTI to develop the gasification characteristics of selected feedstock for the project. To conduct this work, GTI will assemble an existing ''mini-bench'' unit to perform the gasification tests. The results of the test will be used to confirm or if necessary update the process design completed in Phase Task 1

  1. Protection of Lithium (Li) Anodes Using Dual Phase Electrolytes

    Energy Technology Data Exchange (ETDEWEB)

    Mikhaylik, Yuriy [Sion Power Corporation, Tucson, AZ (United States)

    2014-09-30

    Sion Power focused on metallic lithium anode protection, employing the Dual-Phase Electrolyte approach. The objective of this project was to develop a unique electrolyte providing two liquid phases having good Li+ conductivity, self-partitioning and immiscibility, serving separately the cathode and anode electrodes. This Dual-Phase Electrolyte was combined with thin film multi-layer, physical barrier membranes developed partially under a separate ARPA-E funded project. All these protective structures were stabilized by externally applied pressure. This strategy was used for Li-S cells. The development directly addressed cell safety, particularly higher thermal stability, while also allowing higher energies and cycle life. Safety tests showed that 100% of cells with Dual-Phase Electrolyte were intact and did not exhibit thermal runaway up to 178 °C and thus met the project objective of increasing the runaway temperature to >165°C. Cells also passed cycling at USABC Dynamic Stress Test conditions developed for Electric Vehicle applications and generated specific energy > 300 Wh/kg.

  2. Innovative Ultra-High Efficiency Cryogenic Actuators for Rocket Test Facilities, Phase I

    Data.gov (United States)

    National Aeronautics and Space Administration — The SBIR Phase I project will develop advanced ultra-high efficiency cryogenic actuators for NASA cryogenic fluid transfer application. The actuator will have low...

  3. Characterization of a backfill candidate material, IBECO-RWC-BF Baclo Project - Phase 3 Laboratory tests

    Energy Technology Data Exchange (ETDEWEB)

    Johannesson, Lars-Erik; Sanden, Torbjoern; Dueck, Ann; Ohlsson, Lars (Clay Technology AB, Lund (Sweden))

    2010-01-15

    A backfill candidate material, IBECO-RWC-BF, which origin from Milos, Greece, has been investigated. The material was delivered both as granules and as pellets. The investigation described in this report aimed to characterize the material and evaluate if it can be used in a future repository. The following investigations have been done and are presented in this report: 1. Standard laboratory tests. Water content, liquid limit and swelling potential are examples on standard tests that have been performed. 2. Block manufacturing. The block compaction properties of the material have been determined. A first test was performed in laboratory but also tests in large scale have been performed. After finishing the test phase, 60 tons of blocks were manufactured at Hoeganaes Bjuf AB. The blocks will be used in large scale laboratory tests at Aespoe HRL. 3. Mechanical parameters. The compressibility of the material was investigated with oedometer tests (four tests) where the load was applied in steps after saturation. The evaluated oedometer modulus varied between 34.50 MPa. Tests were made to evaluate the elastic parameters of the material (E, nu). Altogether three tests were made on specimens with dry densities of about 1,710 kg/m3. The evaluated E-modulus and Poisson's ratio varied between 231-263 MPa and 0.16-0.19 respectively. The strength of the material, both the compressive strength and the tensile strength were measured on specimens compacted to different dry densities. The test results yielded a relation between density and the two types of strength. Furthermore, tests have been made in order to determine the compressibility of the unsaturated filling of pellets. Two tests were made where the pellets were loosely filled in a Proctor cylinder and then compressed at a constant rate of strain during continuously measurement of the applied load. 4. Swelling pressure and hydraulic conductivity. There is, as expected, a very clear influence of the dry density on the

  4. Second phase in steel AISI 316 tested at 8000C

    International Nuclear Information System (INIS)

    Silveira, V.L.A.; Monteiro, S.N.

    The nature of second phases in type 316 stainless steel samples tested in creep to rupture at 800 0 C has been discussed. These phases were identified by experimental techniques completed with the available information in the literature. The role of these phases in the creep properties of the type 316 steel at 800 0 C is analysed [pt

  5. Project accent: graphite irradiated creep in a materials test reactor

    International Nuclear Information System (INIS)

    Brooking, M.

    2014-01-01

    Atkins manages a pioneering programme of irradiation experiments for EDF Energy. One of these projects is Project ACCENT, designed to obtain evidence of a beneficial physical property of the graphite, which may extend the life of the Advanced Gas-cooled Reactors (AGRs). The project team combines the in-house experience of EDF Energy with two supplier organisations (providing the material test reactors and testing facilities) and supporting consultancies (Atkins and an independent technical expert). This paper describes: - Brief summary of the Project; - Discussion of the challenges faced by the Project; and - Conclusion elaborating on the aims of the Project. These challenging experiments use bespoke technology and both un-irradiated (virgin) and irradiated AGR graphite. The results will help to better understand graphite irradiation-induced creep (or stress modified dimensional change) properties and therefore more accurately determine lifetime and safe operating envelopes of the AGRs. The first round of irradiation has been completed, with a second round about to commence. This is a key step to realising the full lifetime ambition for AGRs, demonstrating the relaxation of stresses within the graphite bricks. (authors)

  6. Phase 2 THOR Steam Reforming Tests for Sodium Bearing Waste Treatment

    Energy Technology Data Exchange (ETDEWEB)

    Nicholas R. Soelberg

    2004-01-01

    About one million gallons of acidic, hazardous, and radioactive sodium-bearing waste is stored in stainless steel tanks at the Idaho Nuclear Technology and Engineering Center (INTEC), which is a major operating facility of the Idaho National Engineering and Environmental Laboratory. Steam reforming is a candidate technology being investigated for converting the waste into a road ready waste form that can be shipped to the Waste Isolation Pilot Plant in New Mexico for interment. A steam reforming technology patented by Studsvik, Inc., and licensed to THOR Treatment Technologies has been tested in two phases using a Department of Energy-owned fluidized bed test system located at the Science Applications International Corporation (SAIC) Science and Technology Applications Research Center located in Idaho Falls, Idaho. The Phase 1 tests were reported earlier in 2003. The Phase 2 tests are reported here. For Phase 2, the process feed rate, stoichiometry, and chemistry were varied to identify and demonstrate process operation and product characteristics under different operating conditions. Two test series were performed. During the first series, the process chemistry was designed to produce a sodium carbonate product. The second series was designed to produce a more leach-resistant, mineralized sodium aluminosilicate product. The tests also demonstrated the performance of a MACT-compliant off-gas system.

  7. Project W-049H collection system Acceptance Test Procedure

    International Nuclear Information System (INIS)

    Carrigan, M.C.

    1994-01-01

    The purpose of this Acceptance Test Procedure (ATP) for the Project W-049H, Treated Effluent Disposal Facility, is to verify that the collection system equipment installed as Pump Station No. 1 (225-W) and Pump Station No. 2 (225-E) have been installed in accordance with the design documents and function as required by the project criteria. This will be a wet test with potable water being introduced into the pump pits to test for leakage. Potable water will also be employed in the testing of the pumps and related mechanical equipment. All Instrument and Control equipment related to the pump stations will be checked electronically with simulated inputs/outputs when actual input/output signals are unavailable. Water from Pump Station 1 will be moved through the TEDF piping system and discharged into the disposal ponds. This will check the proper function of the air/vac valves not tested during construction, and the automated samplers

  8. Project management best practices: forging win-win partnerships and mitigating power project risk

    International Nuclear Information System (INIS)

    Trowsdale, R.

    2006-01-01

    This paper discusses aspects of project management to mitigate power project risk. end-to-end project development involves development phase, permitting phase, implementation phase, and operational phase. Each phase involves a number of different elements. In renewable energy project good management requires maintaining project discipline and schedule throughout all phases. Project success requires commercial competitiveness, fuel availability, power sales contracts, stake holder support, permitting, effective execution, construction and good technical performance

  9. EX8000 ramps up preparation phase in Horizon oil sands project

    Energy Technology Data Exchange (ETDEWEB)

    Anon.

    2006-07-15

    This article presented details of Hitachi's EX8000 hydraulic shovel, a key piece of equipment that will be used throughout the extensive mine preparation phase of the Horizon oil sands project. Within 2 years, the project expects to produce over 200,000 barrels of oil per day. However, more than 400 million cubic metres of soil will need to be moved before production can begin. In order to remain on schedule, overburden must be removed in massive volumes. With a 52.3 cubic yard bucket, the Hitachi EX8000 has the capacity to feed a dozen 320 metric tonne haul trucks as well as several smaller 282 metric tonne trucks, and can fill each truck in 4 passes. Material is now being moved by to an area in which dikes are being constructed to house water generated in the refining process. Stockpiling, relocation and reclamation phases will follow as the project progresses. In order to reach the oil, as much as 75 feet of overburden must be removed, including layers of sandstone, limestone, trap rock and other materials. Once the overburden has been removed, oil sand layers are also often intermixed with other materials. The EX8000 can separate the tramp material from the oil sands, improving the overall efficiency of the operation. The Alberta-based North American Construction Group, who have a 10-year contract with Canadian Natural Resources Ltd. for the Horizon project, owns more than 100 Hitachi units in various sizes and has already purchased another EX8000 which is slated for delivery in the Fall of 2006. It was concluded that the company has purchased hundreds of new trucks to handle added volumes of materials being moved as the oil sands industry gains momentum. 3 figs.

  10. Sex Differences in Objective and Projective Dependency Tests: A Meta-Analytic Review.

    Science.gov (United States)

    Bornstein, Robert F.

    1995-01-01

    A meta-analysis of 97 studies published since 1950 that assessed sex differences in scores on objective and projective dependency tests indicated that women consistently obtained higher dependency scores on objective tests, and men obtained higher scores on projective tests. Findings are discussed in terms of sex role socialization. (SLD)

  11. Pretest Predictions for Phase II Ventilation Tests

    International Nuclear Information System (INIS)

    Yiming Sun

    2001-01-01

    The objective of this calculation is to predict the temperatures of the ventilating air, waste package surface, and concrete pipe walls that will be developed during the Phase II ventilation tests involving various test conditions. The results will be used as inputs to validating numerical approach for modeling continuous ventilation, and be used to support the repository subsurface design. The scope of the calculation is to identify the physical mechanisms and parameters related to thermal response in the Phase II ventilation tests, and describe numerical methods that are used to calculate the effects of continuous ventilation. The calculation is limited to thermal effect only. This engineering work activity is conducted in accordance with the ''Technical Work Plan for: Subsurface Performance Testing for License Application (LA) for Fiscal Year 2001'' (CRWMS M and O 2000d). This technical work plan (TWP) includes an AP-2.21Q, ''Quality Determinations and Planning for Scientific, Engineering, and Regulatory Compliance Activities'', activity evaluation (CRWMS M and O 2000d, Addendum A) that has determined this activity is subject to the YMP quality assurance (QA) program. The calculation is developed in accordance with the AP-3.12Q procedure, ''Calculations''. Additional background information regarding this activity is contained in the ''Development Plan for Ventilation Pretest Predictive Calculation'' (DP) (CRWMS M and O 2000a)

  12. Atmospheric muons in the NEMO Phase 1 detector at the Catania test site

    International Nuclear Information System (INIS)

    Margiotta, Annarita

    2006-01-01

    The NEMO Collaboration is involved in a long term R and D activity towards the construction of a km 3 telescope in the Mediterranean sea. It has dedicated special efforts in the development of technologies for a km 3 detector and in the search, characterization and monitoring of a deep sea site adequate for the installation of the Mediterranean km 3 . Now the NEMO Collaboration is involved in the Phase 1 of the project, planning to install a fully equipped deep-sea facility to test prototypes and develop new technologies for the detector. A full Monte Carlo simulation has been performed to analyse the response of a reduced-size detector to the passage of atmospheric muons. Preliminary steps of the simulation are presented in this work

  13. Pulse-width modulation for small heat pump installations - Phase 4; Pulsbreitenmodulation fuer Kleinwaermepumpenanlagen. Phase 4: Erweiterung der PBM-Regler fuer Kombianlagen

    Energy Technology Data Exchange (ETDEWEB)

    Bianchi, M.; Shafai, E. [Eidgenoessische Technische Hochschule (ETH), Institut fuer Mess- und Regeltechnik, Zuerich (Switzerland); Gabathuler, H.R.; Mayer, H. [Gabathuler AG, Beratende Ingenieure, Diessenhofen (Switzerland)

    2005-07-01

    This final report for the Swiss Federal Office of Energy (SFOE) presents the results of the fourth phase of a project that investigated three types of pulse-width modulation (PWM) controllers that were developed during its first two phases. A third phase monitored the controllers when used in a simulated environment and for a real-life heat pump. The report discusses the fourth phase of the project, in which the controller was further developed and tested using the building emulation developed in the third phase. The functioning of the self-regulating controller and its use of meteorological data is described and the savings to be made in heating costs are discussed.

  14. Strategy for phase 2 whole element furnace testing K West fuel

    International Nuclear Information System (INIS)

    Lawrence, L.A.

    1998-01-01

    A strategy was developed for the second phase of the whole element furnace testing of damaged fuel removed from the K West Basin. The Phase 2 testing can be divided into three groups covering oxidation of whole element in moist inert atmospheres, drying elements for post Cold Vacuum Drying staging tests, and drying additional K West elements to provide confirmation of the results from the first series of damaged K West fuel drying studies

  15. Testing and Commissioning of Lillgrund Wind Farm. Lillgrund Pilot Project

    Energy Technology Data Exchange (ETDEWEB)

    Larsen, Poul Erik; Larsson, Aake; Jeppsson, Joakim; Toernkvist, Mattias (ed.) (Vattenfall Vindkraft AB, Stockholm (Sweden))

    2009-04-15

    This report gives an overview of the tests carried out in the Lillgrund project. The report covers factory tests, site tests and the performance tests, which can be carried out during the defects liability period. The report describes tests relevant for the wind turbine generators, the electrical system and the foundations. On the whole, the Lillgrund test results have been satisfactory. One of the more problematic issues experienced were when the foundation interface verification showed that the bolts were not meeting the height requirements. Since this shortcoming was detected relatively early in the project life, it was possible to correct the misalignment and keep the additional costs to a minimum. From a management point of view, this highlighted the importance of clear and unambiguous interface specifications and to make sure that the project has a proper interface management function. According to the Contract, Vattenfall has the right to verify a number of performance parameters during the 5-year defect liability period. The performance tests include availability, power curve, electrical system losses and acoustic noise levels. The contract specifies the test criteria, the test methods and procedures and the penalty if the tests result in undesirable levels. In some cases, there is a financial incentive for the supplier if the tests show that the wind farm is performing better than stipulated in the contract. Lillgrund has performed very well thus far and Vattenfall has determined that the contractual performance requirements are being met. Vattenfall has, therefore, not requested to carry out any of these elective Performance Tests

  16. Prototypical Rod Consolidation Demonstration Project

    International Nuclear Information System (INIS)

    1993-05-01

    The objective of Phase III of the Prototypical Rod Consolidation Demonstration Project (PRCDP) was to procure, fabricate, assemble, and test the Prototypical Rod Consolidation System as described in the NUS Phase II Final Design Report. This effort required providing the materials, components, and fabricated parts which makes up all of the system equipment. In addition, it included the assembly, installation, and setup of this equipment at the Cold Test Facility. During the Phase III effort the system was tested on a component, subsystem, and system level. Volume IV provides the Operating and Maintenance Manual for the Prototypical Rod Consolidation System that was installed at the Cold Test Facility. This document, Book 1 of Volume IV, discusses: Process overview functional descriptions; Control system descriptions; Support system descriptions; Maintenance system descriptions; and Process equipment descriptions

  17. Prototypical Rod Consolidation Demonstration Project

    International Nuclear Information System (INIS)

    1993-05-01

    The objective of Phase III of the Prototypical Rod Consolidation Demonstration Project (PRCDP) was to procure, fabricate, assemble, and test the Prototypical Rod Consolidation System as described in the NUS Phase II Final Design Report. This effort required providing the materials, components, and fabricated parts which makes up all of the system equipment. In addition, it included the assembly, installation, and setup of this equipment at the Cold Test Facility. During the Phase III effort the system was tested on a component, subsystem, and system level. Volume IV provides the Operating and Maintenance Manual for the Prototypical Rod Consolidation System that was installed at the Cold Test Facility. This document, Book 4 of Volume IV, discusses: Off-normal operating and recovery procedures; Emergency response procedures; Troubleshooting procedures; and Preventive maintenance procedures

  18. Project management plan for exploratory shaft at Yucca Mountain

    International Nuclear Information System (INIS)

    1983-08-01

    This Project Management Plan (PMP) provides the basic guidance and describes the organizational structure and procedures for the design, construction, and testing of a large-diameter Exploratory Shaft (ES) in tuffaceous media as a major element within the Nevada Nuclear Waste Storage Investigations (NNWSI) project, which is a part of the National Waste Terminal Storage (NWTS) Program, US Department of Energy (DOE). The PMP encompasses activities identified as construction phase and in situ phase testing to be conducted from the ES through September 30, 1986. Specific topics addressed are the ES project objectives, the management organization and responsibilities, functional support requirements, work plan (including quality assurance aspects), work breakdown structure, milestone schedule, logic diagram, performance criteria, cost estimates, management control systems, procurement plan, test plan, and environmental, health and safety plans

  19. Multilayer Pressure Vessel Materials Testing and Analysis Phase 2

    Science.gov (United States)

    Popelar, Carl F.; Cardinal, Joseph W.

    2014-01-01

    To provide NASA with a suite of materials strength, fracture toughness and crack growth rate test results for use in remaining life calculations for the vessels described above, Southwest Research Institute® (SwRI®) was contracted in two phases to obtain relevant material property data from a representative vessel. An initial characterization of the strength, fracture and fatigue crack growth properties was performed in Phase 1. Based on the results and recommendations of Phase 1, a more extensive material property characterization effort was developed in this Phase 2 effort. This Phase 2 characterization included additional strength, fracture and fatigue crack growth of the multilayer vessel and head materials. In addition, some more limited characterization of the welds and heat affected zones (HAZs) were performed. This report

  20. Thermal Testing Measurements Report

    Energy Technology Data Exchange (ETDEWEB)

    R. Wagner

    2002-09-26

    The purpose of the Thermal Testing Measurements Report (Scientific Analysis Report) is to document, in one report, the comprehensive set of measurements taken within the Yucca Mountain Project Thermal Testing Program since its inception in 1996. Currently, the testing performed and measurements collected are either scattered in many level 3 and level 4 milestone reports or, in the case of the ongoing Drift Scale Test, mostly documented in eight informal progress reports. Documentation in existing reports is uneven in level of detail and quality. Furthermore, while all the data collected within the Yucca Mountain Site Characterization Project (YMP) Thermal Testing Program have been submitted periodically to the Technical Data Management System (TDMS), the data structure--several incremental submittals, and documentation formats--are such that the data are often not user-friendly except to those who acquired and processed the data. The documentation in this report is intended to make data collected within the YMP Thermal Testing Program readily usable to end users, such as those representing the Performance Assessment Project, Repository Design Project, and Engineered Systems Sub-Project. Since either detailed level 3 and level 4 reports exist or the measurements are straightforward, only brief discussions are provided for each data set. These brief discussions for different data sets are intended to impart a clear sense of applicability of data, so that they will be used properly within the context of measurement uncertainty. This approach also keeps this report to a manageable size, an important consideration because the report encompasses nearly all measurements for three long-term thermal tests. As appropriate, thermal testing data currently residing in the TDMS have been reorganized and reformatted from cumbersome, user-unfriendly Input-Data Tracking Numbers (DTNs) into a new set of Output-DTNs. These Output-DTNs provide a readily usable data structure

  1. Rehabilitation and modernization project of units 1 and 2 of Laguna Verde Nuclear Power Plant. A strengthening project to 120%. (2nd phase); Proyecto de rehabilitacion y modernizacion de las Unidades 1and 2 de la CNLV. Un proyecto de reponteciacion al 120% (2ª Fase)

    Energy Technology Data Exchange (ETDEWEB)

    Liebana, B.; Merino, A.; Garcia, J. L.; Gomez, M.; Martinez, I.; Ruiz, L.

    2010-07-01

    The power increase of the Laguna Verde Nuclear Power Plant is a project for the rehabilitation and modernization of the turbo and associated equipment to get an increase of its power and of its service life. The project scope includes the design, the engineering, the equipment supply, the installation, the testing and the commissioning. This article presents the work of the second phase.

  2. Regulation Of Hydraulic Fracturing In South Africa: A Project Life-Cycle Approach?

    Directory of Open Access Journals (Sweden)

    Willemien du Plessis

    2015-12-01

    Full Text Available This note deals with the 2015 regulations pertaining to hydraulic fracturing in South Africa from a project life-cycle approach. A brief history of the fragmentation of the regulation of environmental and mining related matters is provided, followed by a discussion of the application of the 2015 regulations during the project life cycle, ie the pre-commencement phase, the design and authorisation phase, the testing phase, the operational phase and the decommissioning and closure phase.

  3. Characterization of a backfill candidate material, IBECO-RWC-BF Baclo Project - Phase 3 Laboratory tests

    International Nuclear Information System (INIS)

    Johannesson, Lars-Erik; Sanden, Torbjoern; Dueck, Ann; Ohlsson, Lars

    2010-01-01

    A backfill candidate material, IBECO-RWC-BF, which origin from Milos, Greece, has been investigated. The material was delivered both as granules and as pellets. The investigation described in this report aimed to characterize the material and evaluate if it can be used in a future repository. The following investigations have been done and are presented in this report: 1. Standard laboratory tests. Water content, liquid limit and swelling potential are examples on standard tests that have been performed. 2. Block manufacturing. The block compaction properties of the material have been determined. A first test was performed in laboratory but also tests in large scale have been performed. After finishing the test phase, 60 tons of blocks were manufactured at Hoeganaes Bjuf AB. The blocks will be used in large scale laboratory tests at Aespoe HRL. 3. Mechanical parameters. The compressibility of the material was investigated with oedometer tests (four tests) where the load was applied in steps after saturation. The evaluated oedometer modulus varied between 34.50 MPa. Tests were made to evaluate the elastic parameters of the material (E, ν). Altogether three tests were made on specimens with dry densities of about 1,710 kg/m 3 . The evaluated E-modulus and Poisson's ratio varied between 231-263 MPa and 0.16-0.19 respectively. The strength of the material, both the compressive strength and the tensile strength were measured on specimens compacted to different dry densities. The test results yielded a relation between density and the two types of strength. Furthermore, tests have been made in order to determine the compressibility of the unsaturated filling of pellets. Two tests were made where the pellets were loosely filled in a Proctor cylinder and then compressed at a constant rate of strain during continuously measurement of the applied load. 4. Swelling pressure and hydraulic conductivity. There is, as expected, a very clear influence of the dry density on the

  4. A review of Studsvik's international power ramp test projects

    International Nuclear Information System (INIS)

    Mogard, H.; Kjaer-Pedersen, N.

    1985-11-01

    Since 1975 a series of internationally sponsored fuel irradiation research projects have been and are being conducted at Studsvik, Sweden, under the management of Studsvik Energiteknik AB. The sponsoring parties comprise fuel vendors, nuclear power utilities, national research organizations and, in some cases, safety authorities. Geographically the parties represent organizations in Europe, Japan, and the USA. The main research topic of the Studsvik projects is the Pellet Clad Interaction (PCI) induced Stress Corrosion Cracking (SCC) failure occurrence in LWR fuel under power ramping conditions. The research is conducted in the 50 MW R2 test reactor and the associated hot cell laboratory. Prior to the experiments the test fuel is base irradiated, normally in commercially operated light water reactors. Results have been published for the INTER-RAMP, OVER-RAMP, DEMO-RAMP I, DEMO-RAMP II and SUPER-RAMP projects. The release of the TRANS-RAMP I results is imminent. There are two ongoing projects, i.e. SUPER-RAMP EXTENSION and TRANS-RAMP II. The paper presents an overview of the objectives and main results of the various projects. An attempt is made to summarize the more important observations on PCI failure performance in the perspective of design parameters, fuel burnup levels, power histories, power ramp rates, etc. With 14 refs. (Author)

  5. Project W-314 specific test and evaluation plan for 241-AN-A valve pit

    International Nuclear Information System (INIS)

    Hays, W.H.

    1997-01-01

    The purpose of this Specific Test and Evaluation Plan (STEP) is to provide a detailed written plan for the systematic testing of modifications made to the 241-AN-A Valve Pit by the W-314 Project. The STEP develops the outline for test procedures that verify the system's performance to the established Project design criteria. The STEP is a ''lower tier'' document based on the W-314 Test and Evaluation Plan (TEP) This STEP encompasses all testing activities required to demonstrate compliance to the project design criteria as it relates to the modifications of the AN-A valve pit. The Project Design Specifications (PDS) identify the specific testing activities required for the Project. Testing includes Validations and Verifications (e.g., Commercial Grade Item Dedication activities), Factory Acceptance Tests (FATs), installation tests and inspections, Construction Acceptance Tests (CATs), Acceptance Test Procedures (ATPs), Pre-Operational Test Procedures (POTPs), and Operational Test Procedures (OTPs). It should be noted that POTPs are not required for testing of the modifications to the 241-AN-A Valve Pit. The STEP will be utilized in conjunction with the TEP for verification and validation

  6. Comment on "Localized water reverberation phases and its impact on back-projection images" by Yue et al. [2017

    Science.gov (United States)

    Fan, W.; Shearer, P. M.

    2017-12-01

    Fan and Shearer [2016] analyzed the 2012 Mw 7.2 Sumatra earthquake and reported that the earthquake dynamically triggered early aftershock/aftershocks 150 km away from the mainshock and 50 s later. The early aftershock/aftershocks were detected with teleseismic P-wave back-projection, coincided with passing surface waves, and showed observable seismic waveforms in a wide frequency range (0.02—5 Hz). Recently, however, Yue et al. [2017] interpreted these coda arrivals as water reverberations from the mainshock, based mostly on EGF analysis of a nearby M6 earthquake and a water-phase synthetic test. Here, we show detailed back-projection and waveform analysis of three M6 earthquakes within 100km of the Mw 7.2 earthquake, including the EGF event analyzed in Yue et al. [2017]. In addition, we examine the waveforms of three M5.5 reverse faulting earthquakes close to our detected early aftershock landward of the trench. Our results show that the coda energy in question is more likely caused by a separate earthquake near the trench than by a mainshock water reverberation phase, thus supporting our earlier conclusion that the detected coherent radiators are likely to be dynamically triggered early aftershock/aftershocks.

  7. Mechanisms Engineering Test Loop - Phase 1 Status Report

    Energy Technology Data Exchange (ETDEWEB)

    Kultgen, D. [Argonne National Lab. (ANL), Argonne, IL (United States); Grandy, C. [Argonne National Lab. (ANL), Argonne, IL (United States); Hvasta, M. [Argonne National Lab. (ANL), Argonne, IL (United States); Lisowski, D. [Argonne National Lab. (ANL), Argonne, IL (United States); Toter, W. [Argonne National Lab. (ANL), Argonne, IL (United States); Borowski, A. [Argonne National Lab. (ANL), Argonne, IL (United States)

    2016-09-01

    This report documents the current status of the Mechanisms Engineering Test Loop (METL) as of the end of FY2016. Currently, METL is in Phase I of its design and construction. Once operational, the METL facility will test small to intermediate-scale components and systems in order to develop advanced liquid metal technologies. Testing different components in METL is essential for the future of advanced fast reactors as it will provide invaluable performance data and reduce the risk of failures during plant operation.

  8. Project Physics Tests 4, Light and Electromagnetism.

    Science.gov (United States)

    Harvard Univ., Cambridge, MA. Harvard Project Physics.

    Test items relating to Project Physics Unit 4 are presented in this booklet. Included are 70 multiple-choice and 22 problem-and-essay questions. Concepts of light and electromagnetism are examined on charges, reflection, electrostatic forces, electric potential, speed of light, electromagnetic waves and radiations, Oersted's and Faraday's work,…

  9. JCCRER Project 2.3 -- Deterministic effects of occupational exposure to radiation. Phase 1: Feasibility study; Final report

    Energy Technology Data Exchange (ETDEWEB)

    Okladnikova, N.; Pesternikova, V.; Sumina, M. [Inst. of Biophysics, Ozyorsk (Russian Federation)] [and others

    1998-12-01

    Phase 1 of Project 2.3, a short-term collaborative Feasibility Study, was funded for 12 months starting on 1 February 1996. The overall aim of the study was to determine the practical feasibility of using the dosimetric and clinical data on the MAYAK worker population to study the deterministic effects of exposure to external gamma radiation and to internal alpha radiation from inhaled plutonium. Phase 1 efforts were limited to the period of greatest worker exposure (1948--1954) and focused on collaboratively: assessing the comprehensiveness, availability, quality, and suitability of the Russian clinical and dosimetric data for the study of deterministic effects; creating an electronic data base containing complete clinical and dosimetric data on a small, representative sample of MAYAK workers; developing computer software for the testing of a currently used health risk model of hematopoietic effects; and familiarizing the US team with the Russian diagnostic criteria and techniques used in the identification of Chronic Radiation Sickness.

  10. JCCRER Project 2.3 - Deterministic effects of occupational exposure to radiation. Phase 1: Feasibility study. Final report

    International Nuclear Information System (INIS)

    Okladnikova, N.; Pesternikova, V.; Sumina, M.

    1998-01-01

    Phase 1 of Project 2.3, a short-term collaborative Feasibility Study, was funded for 12 months starting on 1 February 1996. The overall aim of the study was to determine the practical feasibility of using the dosimetric and clinical data on the MAYAK worker population to study the deterministic effects of exposure to external gamma radiation and to internal alpha radiation from inhaled plutonium. Phase 1 efforts were limited to the period of greatest worker exposure (1948--1954) and focused on collaboratively: assessing the comprehensiveness, availability, quality, and suitability of the Russian clinical and dosimetric data for the study of deterministic effects; creating an electronic data base containing complete clinical and dosimetric data on a small, representative sample of MAYAK workers; developing computer software for the testing of a currently used health risk model of hematopoietic effects; and familiarizing the US team with the Russian diagnostic criteria and techniques used in the identification of Chronic Radiation Sickness

  11. Water Use Optimization Toolset Project: Development and Demonstration Phase Draft Report

    Energy Technology Data Exchange (ETDEWEB)

    Gasper, John R. [Argonne National Laboratory; Veselka, Thomas D. [Argonne National Laboratory; Mahalik, Matthew R. [Argonne National Laboratory; Hayse, John W. [Argonne National Laboratory; Saha, Samrat [Argonne National Laboratory; Wigmosta, Mark S. [PNNL; Voisin, Nathalie [PNNL; Rakowski, Cynthia [PNNL; Coleman, Andre [PNNL; Lowry, Thomas S. [SNL

    2014-05-19

    This report summarizes the results of the development and demonstration phase of the Water Use Optimization Toolset (WUOT) project. It identifies the objective and goals that guided the project, as well as demonstrating potential benefits that could be obtained by applying the WUOT in different geo-hydrologic systems across the United States. A major challenge facing conventional hydropower plants is to operate more efficiently while dealing with an increasingly uncertain water-constrained environment and complex electricity markets. The goal of this 3-year WUOT project, which is funded by the U.S. Department of Energy (DOE), is to improve water management, resulting in more energy, revenues, and grid services from available water, and to enhance environmental benefits from improved hydropower operations and planning while maintaining institutional water delivery requirements. The long-term goal is for the WUOT to be used by environmental analysts and deployed by hydropower schedulers and operators to assist in market, dispatch, and operational decisions.

  12. Error Analysis in a Device to Test Optical Systems by Using Ronchi Test and Phase Shifting

    International Nuclear Information System (INIS)

    Cabrera-Perez, Brasilia; Castro-Ramos, Jorge; Gordiano-Alvarado, Gabriel; Vazquez y Montiel, Sergio

    2008-01-01

    In optical workshops, Ronchi test is used to determine the optical quality of any concave surface, while it is in the polishing process its quality is verified. The Ronchi test is one of the simplest and most effective methods used for evaluating and measuring aberrations. In this work, we describe a device to test converging mirrors and lenses either with small F/numbers or large F/numbers, using LED (Light-Emitting Diode) that has been adapted in the Ronchi testing as source of illumination. With LED used the radiation angle is bigger than common LED. It uses external power supplies to have well stability intensity to avoid error during the phase shift. The setup also has the advantage to receive automatic input and output data, this is possible because phase shifting interferometry and a square Ronchi ruling with a variable intensity LED were used. Error analysis of the different parameters involved in the test of Ronchi was made. For example, we analyze the error in the shifting of phase, the error introduced by the movement of the motor, misalignments of x-axis, y-axis and z-axis of the surface under test, error in the period of the grid used

  13. Hanford Waste End Effector Phase I Test Report

    Energy Technology Data Exchange (ETDEWEB)

    Berglin, Eric J. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Hatchell, Brian K. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Mount, Jason C. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Neill, Kevin J. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Wells, Beric E. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Burns, Carolyn A.M. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States)

    2017-09-22

    This test plan describes the Phase 1 testing program of the Hanford Waste End Effector (HWEE) at the Washington River Protection Solutions’ Cold Test Facility (CTF) using a Pacific Northwest National Laboratory (PNNL)-designed testing setup. This effort fulfills the informational needs for initial assessment of the HWEE to support Hanford single-shell tank A-105 retrieval. This task will install the HWEE on a PNNL-designed robotic gantry system at CTF, install and calibrate instrumentation to measure reaction forces and process parameters, prepare and characterize simulant materials, and implement the test program. The tests will involve retrieval of water, sludge, and hardpan simulants to determine pumping rate, dilution factors, and screen fouling rate.

  14. Technical description of the test section SUCOT to investigate a water/steam two-phase flow

    International Nuclear Information System (INIS)

    Daubner, M.; Janssens-Maenhout, G.; Knebel, J.U.

    2002-02-01

    Within the POOLTHY Project of the European Union (Euratom Fourth Framework Programme contract FJ4J-CT95-0003) an active/passive concept (SUCO-Programme) was investigated which controls the heat removal after a potential core melt-down accident in an evolutionary light water reactor by spreading and stabilising the core melt in the reactor sump and flooding the melt with sump water from above. The experiments were performed in the test facility SUCOT which was designed and erected at the Institute for Nuclear and Energy Technologies (IKET). The report gives an overview on the SUCO-Programme and the scaling analysis, which was applied to design the test facility SUCOT. A detailed technical description of the test facility SUCOT is given, in which the natural circulation driven two-phase flow within the reactor sump and relevant phenomena such as flow boiling, disperse bubbly flow with and without mass transfer, and geysering are investigated. The major components of the test facility, the three-loop system and the instrumentation are described. Finally, a perspective for future application of the gained knowledge is given. (orig.) [de

  15. Cross-Cultural Validation of TEMAS, a Minority Projective Test.

    Science.gov (United States)

    Costantino, Giuseppe; And Others

    The theoretical framework and cross-cultural validation of Tell-Me-A-Story (TEMAS), a projective test developed to measure personality development in ethnic minority children, is presented. The TEMAS test consists of 23 chromatic pictures which incorporate the following characteristics: (1) representation of antithetical concepts which the…

  16. Experimental Results of A1.2 Test for OECD-ATLAS Project

    Energy Technology Data Exchange (ETDEWEB)

    Kang, Kyoung-Ho; Bae, Byoung-Uhn; Park, Yu-Sun; Kim, Jong-Rok; Choi, Nam-Hyun; Choi, Ki-Yong [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2015-10-15

    In order to meet the international interests in the multiple high-risk design extension conditions (DECs) raised after the Fukushima accident, KAERI (Korea Atomic Energy Research Institute) is operating an OECD/NEA project (hereafter, OECD-ATLAS project) by utilizing a thermal-hydraulic integral effect test facility, ATLAS (Advanced Thermal-hydraulic Test Loop for Accident Simulation). As for a prolonged SBO transient of the OECD-ATLAS project, two tests, named A1.1 and A1.2, were determined to be performed. In particular, passive safety systems are considered as the most promising alternatives to reinforce the safety and reliability of an ultimate heat removal system without any operator actions in the SBO transients. As one of the new safety improvement concepts to mitigate an SBO accident efficiently, a cooling and operational performance of the passive auxiliary feedwater system (PAFS) is investigated in the framework of the OECD-ATLAS project to produce clearer knowledge of the actual phenomena and to provide the best guidelines for accident management. As the second test of the OECD-ATLAS project, the A1.2 test was conducted to simulate a prolonged SBO with asymmetric secondary cooling through the supply of passive auxiliary feedwater only to SG-2. When the collapsed water level of steam generator reached a wide range of 25%, PAFS was actuated. PAFS played a key role in cooling down the primary system by the heat transfer and the natural circulation. With the actuation of PAFS, the fluid temperatures at the core inlet and outlet started to decrease without any excursion of the maximum heater surface temperature in the core. This integral effect test data of A1.2 test can be used to evaluate the prediction capability of existing safety analysis codes and identify any code deficiency for an SBO simulation with an operation of a passive system such as PAFS.

  17. Project Physics Tests 1, Concepts of Motion.

    Science.gov (United States)

    Harvard Univ., Cambridge, MA. Harvard Project Physics.

    Test items relating to Project Physics Unit 1 are presented in this booklet, consisting of 70 multiple-choice and 20 problem-and-essay questions. Concepts of motion are examined with respect to velocities, acceleration, forces, vectors, Newton's laws, and circular motion. Suggestions are made for time consumption in answering some items. Besides…

  18. Phase 1 Characterization sampling and analysis plan West Valley demonstration project.

    Energy Technology Data Exchange (ETDEWEB)

    Johnson, R. L. (Environmental Science Division)

    2011-06-30

    The Phase 1 Characterization Sampling and Analysis Plan (CSAP) provides details about environmental data collection that will be taking place to support Phase 1 decommissioning activities described in the Phase 1 Decommissioning Plan for the West Valley Demonstration Project, Revision 2 (Phase I DP; DOE 2009). The four primary purposes of CSAP data collection are: (1) pre-design data collection, (2) remedial support, (3) post-remediation status documentation, and (4) Phase 2 decision-making support. Data collection to support these four main objectives is organized into two distinct data collection efforts. The first is data collection that will take place prior to the initiation of significant Phase 1 decommissioning activities (e.g., the Waste Management Area [WMA] 1 and WMA 2 excavations). The second is data collection that will occur during and immediately after environmental remediation in support of remediation activities. Both data collection efforts have a set of well-defined objectives that encompass the data needs of the four main CSAP data collection purposes detailed in the CSAP. The main body of the CSAP describes the overall data collection strategies that will be used to satisfy data collection objectives. The details of pre-remediation data collection are organized by WMA. The CSAP contains an appendix for each WMA that describes the details of WMA-specific pre-remediation data collection activities. The CSAP is intended to expand upon the data collection requirements identified in the Phase 1 Decommissioning Plan. The CSAP is intended to tightly integrate with the Phase 1 Final Status Survey Plan (FSSP). Data collection described by the CSAP is consistent with the FSSP where appropriate and to the extent possible.

  19. Project W-314 Polyurea Special Protective Coating (SPC) Test Report Chemical Compatibility and Physical Characteristics Testing

    International Nuclear Information System (INIS)

    MAUSER, R.W.

    2001-01-01

    This Engineering Test report outlines the results obtained from testing polyurea on its decon factor, tank waste compatibility, and adhesion strength when subjected to a high level of gamma radiation. This report is used in conjunction with RPP-7187 Project W-314 Pit Coatings Repair Requirements Analysis, to document the fact polyurea meets the project W-314 requirements contained in HNF-SD-W314-PDS-005 and is therefore an acceptable SPC for use in W-314 pit refurbishments

  20. Puget Sound Tidal Energy In-Water Testing and Development Project Final Technical Report

    Energy Technology Data Exchange (ETDEWEB)

    Collar, Craig W

    2012-11-16

    Tidal energy represents potential for the generation of renewable, emission free, environmentally benign, and cost effective energy from tidal flows. A successful tidal energy demonstration project in Puget Sound, Washington may enable significant commercial development resulting in important benefits for the northwest region and the nation. This project promoted the United States Department of Energy's Wind and Hydropower Technologies Program's goals of advancing the commercial viability, cost-competitiveness, and market acceptance of marine hydrokinetic systems. The objective of the Puget Sound Tidal Energy Demonstration Project is to conduct in-water testing and evaluation of tidal energy technology as a first step toward potential construction of a commercial-scale tidal energy power plant. The specific goal of the project phase covered by this award was to conduct all activities necessary to complete engineering design and obtain construction approvals for a pilot demonstration plant in the Admiralty Inlet region of the Puget Sound. Public Utility District No. 1 of Snohomish County (The District) accomplished the objectives of this award through four tasks: Detailed Admiralty Inlet Site Studies, Plant Design and Construction Planning, Environmental and Regulatory Activities, and Management and Reporting. Pre-Installation studies completed under this award provided invaluable data used for site selection, environmental evaluation and permitting, plant design, and construction planning. However, these data gathering efforts are not only important to the Admiralty Inlet pilot project. Lessons learned, in particular environmental data gathering methods, can be applied to future tidal energy projects in the United States and other parts of the world. The District collaborated extensively with project stakeholders to complete the tasks for this award. This included Federal, State, and local government agencies, tribal governments, environmental groups, and

  1. Sustainable development in city districts: BaLaLuZ project - Gundeldinger Feld - Phase 1; Schlussbericht Quartier Gundeldingerfeld Basel - Phase 1

    Energy Technology Data Exchange (ETDEWEB)

    Binz, A.; Voyame, J.-P.

    2004-07-01

    This final report for the Swiss Federal Office of Energy (SFOE) is one of a series of reports concerning municipal development in various cities in Switzerland. The four city districts involved include Basel (Gundeldinger Feld), Lausanne (Bellevaux), Lucerne (Basel-/Bernstrasse) and Zurich (Werdwies). This final report summarises the results of the first phase of the project in Gundeldinger Feld, Basel. In an analysis of the initial situation in the Gundeldinger Feld, ecological and economical aspects are examined as are questions concerning mobility and urban planning. The various players involved are introduced and their expectations reviewed; work done and the involvement of the local inhabitants in the project are looked at. Measures to be taken to realise the visions proposed are discussed and suggestions for projects are made.

  2. JV TASK 45-MERCURY CONTROL TECHNOLOGIES FOR ELECTRIC UTILITIES BURNING LIGNITE COAL, PHASE I BENCH-AND PILOT-SCALE TESTING

    Energy Technology Data Exchange (ETDEWEB)

    John H. Pavlish; Michael J. Holmes; Steven A. Benson; Charlene R. Crocker; Edwin S. Olson; Kevin C. Galbreath; Ye Zhuang; Brandon M. Pavlish

    2003-10-01

    The Energy & Environmental Research Center has completed the first phase of a 3-year, two-phase consortium project to develop and demonstrate mercury control technologies for utilities that burn lignite coal. The overall project goal is to maintain the viability of lignite-based energy production by providing utilities with low-cost options for meeting future mercury regulations. Phase I objectives are to develop a better understanding of mercury interactions with flue gas constituents, test a range of sorbent-based technologies targeted at removing elemental mercury (Hg{sup o}) from flue gases, and demonstrate the effectiveness of the most promising technologies at the pilot scale. The Phase II objectives are to demonstrate and quantify sorbent technology effectiveness, performance, and cost at a sponsor-owned and operated power plant. Phase I results are presented in this report along with a brief overview of the Phase II plans. Bench-scale testing provided information on mercury interactions with flue gas constituents and relative performances of the various sorbents. Activated carbons were prepared from relatively high-sodium lignites by carbonization at 400 C (752 F), followed by steam activation at 750 C (1382 F) and 800 C (1472 F). Luscar char was also steam-activated at these conditions. These lignite-based activated carbons, along with commercially available DARCO FGD and an oxidized calcium silicate, were tested in a thin-film, fixed-bed, bench-scale reactor using a simulated lignitic flue gas consisting of 10 {micro}g/Nm{sup 3} Hg{sup 0}, 6% O{sub 2}, 12% CO{sub 2}, 15% H{sub 2}O, 580 ppm SO{sub 2}, 120 ppm NO, 6 ppm NO{sub 2}, and 1 ppm HCl in N{sub 2}. All of the lignite-based activated (750 C, 1382 F) carbons required a 30-45-minute conditioning period in the simulated lignite flue gas before they exhibited good mercury sorption capacities. The unactivated Luscar char and oxidized calcium silicate were ineffective in capturing mercury. Lignite

  3. SkyMine Beneficial CO2 Use Project

    Energy Technology Data Exchange (ETDEWEB)

    Walters, Jerel [Skyonic Corporation, Austin, TX (United States)

    2016-02-15

    This Final Report addresses accomplishments achieved during Phase 1 and Phase 2 of the SkyMine® Carbon Mineralization Commercial Scale Pilot Project. The primary objectives of this project were to design, construct, and operate a system to capture CO₂ from a slipstream of flue gas from a commercial coal-fired cement kiln, convert that CO₂ into products having commercial value as an example of Carbon Capture and Beneficial Re-Use, show the economic viability of the CO₂ capture and conversion process, and thereby advance the technology to a level of commercial scale completion with the ability for further proliferation. The project also substantiates market opportunities for the technology by sales of chemicals into existing markets, and has identified opportunities to improve technology performance and reduce costs during the normal course of operations. The primary objectives of Phase 1 of the project were to elaborate proven SkyMine® process chemistry to commercial pilot-scale operation and complete the preliminary design for the pilot plant to be built and operated in Phase 2. During Phase 2, Pilot System Engineering Design, Construction and Testing, supporting research and development was conducted at a field test unit to collect data that aided in detailed designs of the commercial scale pilot unit; final detailed designs were completed; the commercial scale pilot plant is in its final stages of construction; and a test program has been designed and will be implemented to collect data from the facility to evaluate the technical viability of the process for resulting in an overall net reduction in CO2 emitted into the atmosphere through a process that is run and conducted in a carbon negative manner. The objective of Phase 2b was to build the commercial scale pilot plant to be operated and tested in Phase 2c. By June 30, 2015, the plant was +99% constructed and completed.

  4. Cyprus natural analogue project (CNAP). Phase III final report

    International Nuclear Information System (INIS)

    Alexander, W.R.; Milodowski, A.E.; Pitty, A.F.

    2012-01-01

    The CNAP Phase III project was carried out following identification of the requirement to support ongoing laboratory and modelling efforts on the potential reaction of the bentonite buffer with cementitious leachates in the repository EBS. Although it is known that the higher pH (12.5 to 13) leachates from OPC cement will degrade bentonite, it is unclear if this will also be the case for the lower pH (10 to 11) leachates typical of low alkali cements. Ongoing laboratory and URL programmes which are currently investigating this face the obstacle of slow kinetics and the production of short-lived metastable phases, meaning obtaining unambiguous results may take decades. This is exacerbated by the limitations of the thermodynamic databases for minerals of interest to models of bentonite/low alkali cement leachate reaction. It was therefore decided to implement a focussed NA study on bentonite/low alkali cement leachate reaction to provide indications of likely long-term reaction products and reaction pathways to provide feedback on the existing short-term investigations noted above and to ascertain if any critical path R and D needs to be instigated now. The results of the analyses presented here suggest that there has been very limited alkaline groundwater reaction with the bentonite. This is generally supported by both the geomorphological evidence and the natural decay series data which imply groundwater groundwater/rock interaction in the last 10 5 a. When integrated with the novel data currently being produced in the BIGRAD project, the CNAP data tend to indicate that any long-term bentonite reaction in low alkali cement leachates is minimal. (orig.)

  5. Cyprus natural analogue project (CNAP). Phase III final report

    Energy Technology Data Exchange (ETDEWEB)

    Alexander, W R [Bedrock Geosciences, Auenstein (Switzerland); Milodowski, A E [British Geological Survey, Keyworth (United Kingdom); Pitty, A F [Pitty (EIA) Consulting, Norwich (United Kingdom)

    2012-01-15

    The CNAP Phase III project was carried out following identification of the requirement to support ongoing laboratory and modelling efforts on the potential reaction of the bentonite buffer with cementitious leachates in the repository EBS. Although it is known that the higher pH (12.5 to 13) leachates from OPC cement will degrade bentonite, it is unclear if this will also be the case for the lower pH (10 to 11) leachates typical of low alkali cements. Ongoing laboratory and URL programmes which are currently investigating this face the obstacle of slow kinetics and the production of short-lived metastable phases, meaning obtaining unambiguous results may take decades. This is exacerbated by the limitations of the thermodynamic databases for minerals of interest to models of bentonite/low alkali cement leachate reaction. It was therefore decided to implement a focussed NA study on bentonite/low alkali cement leachate reaction to provide indications of likely long-term reaction products and reaction pathways to provide feedback on the existing short-term investigations noted above and to ascertain if any critical path R and D needs to be instigated now. The results of the analyses presented here suggest that there has been very limited alkaline groundwater reaction with the bentonite. This is generally supported by both the geomorphological evidence and the natural decay series data which imply groundwater groundwater/rock interaction in the last 10{sup 5} a. When integrated with the novel data currently being produced in the BIGRAD project, the CNAP data tend to indicate that any long-term bentonite reaction in low alkali cement leachates is minimal. (orig.)

  6. Progress of the Hanford Bulk Vitrification Project ICVTM Testing Program

    International Nuclear Information System (INIS)

    Witwer, K.S.; Woolery, D.W.; Dysland, E.J.

    2006-01-01

    In June 2004, the Bulk Vitrification Project was initiated with the intent to engineer, construct and operate a full-scale bulk vitrification pilot-plant to treat low-activity tank waste from Hanford tank 241-S-109. The project, managed by CH2M HILL Hanford Group, Inc., and performed by AMEC Earth and Environmental, Inc. (AMEC), will develop and operate a full-scale demonstration facility to exhibit the effectiveness of the bulk vitrification process under actual operating conditions. Since project initiation, testing has been undertaken using crucible-scale, 1/6 linear (engineering) scale, and full-scale vitrification equipment. Crucible-scale testing, coupled with engineering-scale testing, helps establish process limitations of selected glass formulations. Full-scale testing provides critical design verification of the In Container Vitrification (ICV) TM process both prior to and during operation of the demonstration facility. Beginning in late 2004, several full-scale tests have been performed at AMEC's test site, located adjacent to the U.S. Department of Energy's Hanford Site, in Richland, WA. Early testing involved verification of melt startup methodology, followed by subsequent full-melt testing to validate critical design parameters and demonstrate the 'Bottom-Up, Feed While Melt' process. As testing has progressed, design improvements have been identified and incorporated into each successive test. Full scale testing at AMEC's test site is currently scheduled to complete in 2006, with continued full-scale operational testing at the demonstration facility on the Hanford Site starting in 2007. Additional engineering scale testing will validate recommended glass formulations that have been provided by the Pacific Northwest National Laboratory (PNNL). This testing is expected to continue through 2006. This paper discusses the progress of the full-scale and engineering scale testing performed to date. Crucible-scale testing, a critical step in developing

  7. Healy Clean Coal Project: Healy coal firing at TRW Cleveland Test Facility

    Energy Technology Data Exchange (ETDEWEB)

    Koyama, T.; Petrill, E.; Sheppard, D.

    1991-08-01

    A test burn of two Alaskan coals was conducted at TRW's Cleveland test facility in support of the Healy Clean Coal Project, as part of Clean Coal Technology III Program in which a new power plant will be constructed using a TRW Coal Combustion System. This system features ash slagging technology combined with NO{sub x} and SO{sub x} control. The tests, funded by the Alaska Industrial Development and Export Authority (AIDEA) and TRW, were conducted to verify that the candidate Healy station coals could be successfully fired in the TRW coal combustor, to provide data required for scale-up to the utility project size requirements, and to produce sufficient flash-calcined material (FCM) for spray dryer tests to be conducted by Joy/NIRO. The tests demonstrated that both coals are viable candidates for the project, provided the data required for scale-up, and produced the FCM material. This report describes the modifications to the test facility which were required for the test burn, the tests run, and the results of the tests.

  8. Synthesized research report in the second mid-term research phase. Mizunami Underground Research Laboratory project, Horonobe Underground Research Laboratory project and geo-stability project (Translated document)

    International Nuclear Information System (INIS)

    Hama, Katsuhiro; Sasao, Eiji; Iwatsuki, Teruki; Onoe, Hironori; Sato, Toshinori; Yasue, Kenichi; Asamori, Koichi; Niwa, Masakazu; Osawa, Hideaki; Nagae, Isako; Natsuyama, Ryoko; Fujita, Tomoo; Sasamoto, Hiroshi; Matsuoka, Toshiyuki; Takeda, Masaki; Aoyagi, Kazuhei; Nakayama, Masashi; Miyakawa, Kazuya; Ito, Hiroaki; Ohyama, Takuya; Senba, Takeshi; Amano, Kenji

    2016-08-01

    We have synthesized the research results from the Mizunami/Horonobe Underground Research Laboratories (URLs) and geo-stability projects in the second mid-term research phase. This report can be used as a technical basis for the Nuclear Waste Management Organization of Japan/Regulator at each decision point from siting to beginning of disposal (Principal Investigation to Detailed Investigation Phase). High-quality construction techniques and field investigation methods have been developed and implemented, which will be directly applicable to the National Disposal Program (together with general assessments of hazardous natural events and processes). Acquisition of technical knowledge on decisions of partial backfilling and final closure from actual field experiments in the Mizunami/Horonobe URLs will be crucial as the main theme for the next phases. (author)

  9. SkyMine Carbon Mineralization Pilot Project

    Energy Technology Data Exchange (ETDEWEB)

    Christenson, Norm; Walters, Jerel

    2014-12-31

    This Topical Report addresses accomplishments achieved during Phase 2b of the SkyMine® Carbon Mineralization Pilot Project. The primary objectives of this project are to design, construct, and operate a system to capture CO2 from a slipstream of flue gas from a commercial coal-fired cement kiln, convert that CO2 to products having commercial value (i.e., beneficial use), show the economic viability of the CO2 capture and conversion process, and thereby advance the technology to the point of readiness for commercial scale demonstration and deployment. The overall process is carbon negative, resulting in mineralization of CO2 that would otherwise be released into the atmosphere. The project will also substantiate market opportunities for the technology by sales of chemicals into existing markets, and identify opportunities to improve technology performance and reduce costs at the commercial scale. The project is being conducted in two phases. The primary objectives of Phase 1 were to evaluate proven SkyMine® process chemistry for commercial pilot-scale operation and complete the preliminary design for the pilot plant to be built and operated in Phase 2, complete a NEPA evaluation, and develop a comprehensive carbon life cycle analysis. The objective of Phase 2b was to build the pilot plant to be operated and tested in Phase 2c.

  10. Execution of pilot tests for an uranium in situ leaching project

    International Nuclear Information System (INIS)

    Koch, H.J.

    1983-01-01

    Urangesellschaft is presently evaluating the technical and economic feasibility of an in situ leaching (ISL) project in Wyoming/USA. This report describes the basic technical principles for ISL-uranium projects and gives the reasons for conducting pilot tests prior to the construction of a commercial plant. It further describes the licensing requirements for an ISL-pilot plant and evaluates the results of the pilot tests. (orig.) [de

  11. Development of Zinc/Bromine Batteries for Load-Leveling Applications: Phase 2 Final Report

    Energy Technology Data Exchange (ETDEWEB)

    CLARK,NANCY H.; EIDLER,PHILLIP

    1999-10-01

    This report documents Phase 2 of a project to design, develop, and test a zinc/bromine battery technology for use in utility energy storage applications. The project was co-funded by the U.S. Department of Energy Office of Power Technologies through Sandia National Laboratories. The viability of the zinc/bromine technology was demonstrated in Phase 1. In Phase 2, the technology developed during Phase 1 was scaled up to a size appropriate for the application. Batteries were increased in size from 8-cell, 1170-cm{sup 2} cell stacks (Phase 1) to 8- and then 60-cell, 2500-cm{sup 2} cell stacks in this phase. The 2500-cm{sup 2} series battery stacks were developed as the building block for large utility battery systems. Core technology research on electrolyte and separator materials and on manufacturing techniques, which began in Phase 1, continued to be investigated during Phase 2. Finally, the end product of this project was a 100-kWh prototype battery system to be installed and tested at an electric utility.

  12. Phase 1: ISOCELL demonstration test performance review

    International Nuclear Information System (INIS)

    Chatwin, T.D.

    1991-04-01

    This document consolidates and organizes information available concerning cryogenic retrieval of hazardous, radioactive, and mixed wastes and is mainly derived from a report on the ISOCELL Demonstration Project prepared by Concept RKK, Ltd. ISOCELL cryogenic technology is designed to immobilize hazardous, radioactive, and mixed waste by creating a block of frozen waste and soil that can be safely retrieved, stored, transported, and treated with a minimum of dust. A test of the ISOCELL process was conducted in Carnation, Washington by Concept RKK, Ltd. Test conditions were compared to possible testing conditions at Idaho National Engineering Laboratory. Results indicate ISOCELL technology successfully froze wet soil into a soil block capable of being lifted. 5 refs., 6 figs., 1 tab

  13. Report of the IAEA/RCA-NDT education project

    International Nuclear Information System (INIS)

    Ooka, Kiichi; Terada, Kunio; Ohtani, Kiyoshi; Niwa, Noboru.

    1988-01-01

    The Japan Non-Destructive Test (NDT) Association has been carried out an NDT technical education project with support from IAEA. Phase I of the project was successfully completed last year. The present report briefly outlines the second five-year plan (Phase II) to be carried out under the project. The project was first established in 1981 after receiving a request from IAEA to provide NDT education for participants from the RCA countries (13 countries in Asian and Pacific area). Phase I was mainly designed to provide lectures on NDT techniques. Prior to the start of Phase II, the International Education Subcommittee was established in December 1986 to take the leadership in carrying out Phase II of the project. In addition, the NDT Expert Working Group (formally called Advisory Group) has been installed which consists of representative from Japan. Australia India and Singapore. The Group held nine meetings during Phase I. Three lecture meetings at Singapore and another three at Tokyo were held to provide education according to a plan developed by the Group. It has been decided that Japan be support the lecture meetings to be held during Phase II. To conduct such meetings, a group comprising all of the National Coordinators from the RCA countries was set up to replace the Working Group. The National Coordinator Conference was held four times since its establishment. (N.K.)

  14. Report of the IAEA/RCA-NDT education project

    Energy Technology Data Exchange (ETDEWEB)

    Ooka, Kiichi; Terada, Kunio; Ohtani, Kiyoshi; Niwa, Noboru

    1988-11-01

    The Japan Non-Destructive Test (NDT) Association has been carried out an NDT technical education project with support from IAEA. Phase I of the project was successfully completed last year. The present report briefly outlines the second five-year plan (Phase II) to be carried out under the project. The project was first established in 1981 after receiving a request from IAEA to provide NDT education for participants from the RCA countries (13 countries in Asian and Pacific area). Phase I was mainly designed to provide lectures on NDT techniques. Prior to the start of Phase II, the International Education Subcommittee was established in December 1986 to take the leadership in carrying out Phase II of the project. In addition, the NDT Expert Working Group (formally called Advisory Group) has been installed which consists of representative from Japan. Australia India and Singapore. The Group held nine meetings during Phase I. Three lecture meetings at Singapore and another three at Tokyo were held to provide education according to a plan developed by the Group. It has been decided that Japan be support the lecture meetings to be held during Phase II. To conduct such meetings, a group comprising all of the National Coordinators from the RCA countries was set up to replace the Working Group. The National Coordinator Conference was held four times since its establishment. (N.K.).

  15. Error Cost Escalation Through the Project Life Cycle

    Science.gov (United States)

    Stecklein, Jonette M.; Dabney, Jim; Dick, Brandon; Haskins, Bill; Lovell, Randy; Moroney, Gregory

    2004-01-01

    It is well known that the costs to fix errors increase as the project matures, but how fast do those costs build? A study was performed to determine the relative cost of fixing errors discovered during various phases of a project life cycle. This study used three approaches to determine the relative costs: the bottom-up cost method, the total cost breakdown method, and the top-down hypothetical project method. The approaches and results described in this paper presume development of a hardware/software system having project characteristics similar to those used in the development of a large, complex spacecraft, a military aircraft, or a small communications satellite. The results show the degree to which costs escalate, as errors are discovered and fixed at later and later phases in the project life cycle. If the cost of fixing a requirements error discovered during the requirements phase is defined to be 1 unit, the cost to fix that error if found during the design phase increases to 3 - 8 units; at the manufacturing/build phase, the cost to fix the error is 7 - 16 units; at the integration and test phase, the cost to fix the error becomes 21 - 78 units; and at the operations phase, the cost to fix the requirements error ranged from 29 units to more than 1500 units

  16. Evaluation of Flygt Mixers for Application in Savannah River Site Tank 19. Test Results from Phase B: Mid-Scale Testing at PNNL

    International Nuclear Information System (INIS)

    Powell, M.R.; Combs, W.H.; Farmer, J.R.; Gladki, H.; Hatchell, B.K.; Johnson, M.A.; Poirier, M.R.; Rodwell, P.O.

    1999-01-01

    Pacific Northwest National Laboratory (PNNL) performed mixer tests using 3-kW (4-hp) Flygt mixers in 1.8- and 5.7-m-diameter tanks at the 336 building facility in Richland, Washington to evaluate candidate scaling relationships for Flygt mixers used for sludge mobilization and particle suspension. These tests constituted the second phase of a three-phase test program involving representatives from ITT Flygt Corporation, the Savannah River Site (SRS), the Oak Ridge National Laboratory (ORNL), and PNNL. The results of the first phase of tests, which were conducted at ITT Flygt's facility in a 0.45-m-diameter tank, are documented in Powell et al. (1999). Although some of the Phase B tests were geometrically similar to selected Phase A tests (0.45-m tank), none of the Phase B tests were geometrically, cinematically, and/or dynamically similar to the planned Tank 19 mixing system. Therefore, the mixing observed during the Phase B tests is not directly indicative of the mixing expected in Tank 19 and some extrapolation of the data is required to make predictions for Tank 19 mixing. Of particular concern is the size of the mixer propellers used for the 5.7-m tank tests. These propellers were more than three times larger than required by geometric scaling of the Tank 19 mixers. The implications of the lack of geometric similarity, as well as other factors that complicate interpretation of the test results, are discussed in Section 5.4

  17. Horonobe Underground Research Laboratory project. Synthesis of phase I investigation 2001-2005. Volume 'geoscientific research'

    International Nuclear Information System (INIS)

    Ota, Kunio; Abe, Hironobu; Kunimaru, Takanori

    2011-03-01

    The Horonobe Underground Research Laboratory (URL) Project is being pursued by the Japan Atomic Energy Agency (JAEA) to enhance the reliability of relevant disposal technologies through investigations of the deep geological environment within the host sedimentary formations at Horonobe in Hokkaido, northern Japan. The project consists of two major research areas, 'Geoscientific Research' and 'R and D on Geological Disposal', and proceeds in three overlapping phases, 'Phase I: Surface-based investigation', 'Phase II: Construction' and 'Phase III: Operation', over a period of 20 years. The present report summarises the results of the Phase I geoscientific research carried out from March 2001 to March 2005. Integration of the results from different disciplines ensures that the Phase I goals have been successfully achieved and identifies key issues that need to be addressed in Phases II and III. More importantly, efforts are made to summarise as many lessons learnt from the Phase I investigations and other technical achievements as possible to form a 'knowledge base' that will reinforce the technical basis for both implementation and the formulation of safety regulations. Based on experiences of selecting the URL area and site in Horonobe Town, important factors that should be taken into consideration in such selection processes and their rationale are demonstrated. In the course of stepwise surface-based investigations, a number of achievements have been made, which can eventually provide examples of integrated methodologies for characterising the sedimentary formations. The relevant surface-based investigation techniques have thus been further developed. The Horonobe URL has been designed based on geoscientific information accumulated during the surface-based investigations and the plans for safe construction and operation of the URL have been defined in a feasible manner. In addition, a variety of environmental measures taken during Phase I have proved to be

  18. Suitability Screening Test for Marine Corps Air Traffic Controllers Phase 3: Non-cognitive Test Validation and Cognitive Test Prototype

    Science.gov (United States)

    2014-06-01

    developed, pilot tested, and in its Beta form. Findings or Results The subset of NCAPS traits that demonstrated statistically significant prediction for...development and initial pilot testing of the Prototype Marine ATC Cognitive Test. Method The validation approach chosen for this project was a criterion... multitasking ability, and 5) inductive reasoning ability. A working memory capacity test was developed because working memory has been linked to

  19. Optimised Environmental Test Approaches in the GOCE Project

    Science.gov (United States)

    Ancona, V.; Giordano, P.; Casagrande, C.

    2004-08-01

    The Gravity Field and Steady-State Ocean Circulation Explorer (GOCE) is dedicated to measuring the Earth's gravity field and modelling the geoid with extremely high accuracy and spatial resolution. It is the first Earth Explorer Core mission to be developed as part of ESA's Living Planet Programme and is scheduled for launch in 2006. The program is managed by a consortium of European companies: Alenia Spazio, the prime contractor, Astrium GmbH, the platform responsible, Alcatel Space Industries and Laben, suppliers of the main payloads, respectively the Electrostatic Gravity Gradiometer (EGG) and the Satellite to Satellite Tracking Instrument (SSTI), actually a precise GPS receiver. The GOCE Assembly Integration and Verification (AIV) approach is established and implemented in order to demonstrate to the customer that the satellite design meets the applicable requirements and to qualify and accept from lower level up to system level. The driving keywords of "low cost" and "short schedule" program, call for minimizing the development effort by utilizing off-the-shelf equipment combined with a model philosophy lowering the number of models to be used. The paper will deal on the peculiarities of the optimized environmental test approach in the GOCE project. In particular it introduces the logic of the AIV approach and describe the foreseen tests at system level within the SM environmental test campaign, outlining the Quasi Static test performed in the frame of the SM sine vibration tests, and the PFM environmental test campaign pinpointing the deletion of the Sine Vibration test on PFM model. Furthermore the paper highlights how the Model and Test Effectiveness Database (MATD) can be utilized for the prediction of the new space projects like GOCE Satellite.

  20. OC5 Project Phase II: Validation of Global Loads of the DeepCwind Floating Semisubmersible Wind Turbine

    DEFF Research Database (Denmark)

    Robertson, Amy N.; Wendt, Fabian; Jonkman, Jason M.

    2017-01-01

    This paper summarizes the findings from Phase II of the Offshore Code Comparison, Collaboration, Continued, with Correlation project. The project is run under the International Energy Agency Wind Research Task 30, and is focused on validating the tools used for modeling offshore wind systems thro...

  1. Component Test Facility (Comtest) Phase 1 Engineering For 760°C (1400°F) Advanced Ultrasupercritical (A-USC) Steam Generator Development

    Energy Technology Data Exchange (ETDEWEB)

    Weitzel, Paul [Babcock & Wilcox Power Generation Group, Inc., Barberton, OH (United States)

    2016-05-13

    The Babcock & Wilcox Company (B&W) performed a Pre-Front End Engineering Design (Pre-FEED) of an A-USC steam superheater for a proposed component test program achieving 760°C (1400°F) steam temperature. This would lead to follow-on work in a Phase 2 and Phase 3 that would involve detail design, manufacturing, construction and operation of the ComTest. Phase 1 results have provided the engineering data necessary for proceeding to the next phase of ComTest. The steam generator superheater would subsequently supply the steam to an A-USC prototype intermediate pressure steam turbine. The ComTest program is important in that it will place functioning A-USC components in operation and in coordinated boiler and turbine service. It is also important to introduce the power plant operation and maintenance personnel to the level of skills required and provide the first background experience with hands-on training. The project will provide a means to exercise the complete supply chain events required in order to practice and perfect the process for A-USC power plant design, supply, manufacture, construction, commissioning, operation and maintenance. Representative participants will then be able to transfer knowledge and recommendations to the industry. ComTest is conceived in the manner of using a separate standalone plant facility that will not jeopardize the host facility or suffer from conflicting requirements in the host plant’s mission that could sacrifice the nickel alloy components and not achieve the testing goals. ComTest will utilize smaller quantities of the expensive materials and reduce the risk in the first operational practice for A-USC technology in the United States. Components at suitable scale in ComTest provide more assurance before putting them into practice in the full size A-USC demonstration plant.

  2. USE OF-EPR-DL FIELD TEST EQUIPMENT FOR DETECTION OF SIGMA PHASE

    Directory of Open Access Journals (Sweden)

    Abraão Danilo Gomes Barreto

    2014-06-01

    Full Text Available This work has objective to correlate the intergranular corrosion susceptibility test named EPR-DL (Electrochemical Potentiokinetic Reactivation of Double Loop with the sigma phase formation and other phases. It has been used samples from a UNS S32760 steel pipe for conducting various aging heat treatments. Held isothermal heat treatment at 850°C for 1 min, 10 min, 30 min, 1 h, 1h30min and 10 h. Each heat treated sample and as received were tested using the electrochemical polarization reactivation of double loop technique (EPR-DL. It was possible the detection of deleterious phases with DL-EPR portable cell. The EPR-DL test of some samples showed a second peak of reactivation in which the results showed that this peak might be associated with ferrite or be related to the presence of chi phase

  3. Construction of the two-phase critical flow test facility

    International Nuclear Information System (INIS)

    Chung, C. H.; Chang, S. K.; Park, H. S.; Min, K. H.; Choi, N. H.; Kim, C. H.; Lee, S. H.; Kim, H. C.; Chang, M. H.

    2002-03-01

    The two-phase critical test loop facility has been constructed in the KAERI engineering laboratory for the simulation of small break loss of coolant accident entrained with non-condensible gas of SMART. The test facility can operate at 12 MPa of pressure and 0 to 60 C of sub-cooling with 0.5 kg/s of non- condensible gas injection into break flow, and simulate up to 20 mm of pipe break. Main components of the test facility were arranged such that the pressure vessel containing coolant, a test section simulating break and a suppression tank inter-connected with pipings were installed vertically. As quick opening valve opens, high pressure/temperature coolant flows through the test section forming critical two-phase flow into the suppression tank. The pressure vessel was connected to two high pressure N2 gas tanks through a control valve to control pressure in the pressure vessel. Another N2 gas tank was also connected to the test section for the non-condensible gas injection. The test facility operation was performed on computers supported with PLC systems installed in the control room, and test data such as temperature, break flow rate, pressure drop across test section, gas injection flow rate were all together gathered in the data acquisition system for further data analysis. This test facility was classified as a safety related high pressure gas facility in law. Thus the loop design documentation was reviewed, and inspected during construction of the test loop by the regulatory body. And the regulatory body issued permission for the operation of the test facility

  4. Accelerated Test Method for Corrosion Protective Coatings Project

    Science.gov (United States)

    Falker, John; Zeitlin, Nancy; Calle, Luz

    2015-01-01

    This project seeks to develop a new accelerated corrosion test method that predicts the long-term corrosion protection performance of spaceport structure coatings as accurately and reliably as current long-term atmospheric exposure tests. This new accelerated test method will shorten the time needed to evaluate the corrosion protection performance of coatings for NASA's critical ground support structures. Lifetime prediction for spaceport structure coatings has a 5-year qualification cycle using atmospheric exposure. Current accelerated corrosion tests often provide false positives and negatives for coating performance, do not correlate to atmospheric corrosion exposure results, and do not correlate with atmospheric exposure timescales for lifetime prediction.

  5. Medication monitoring and drug testing ethics project.

    Science.gov (United States)

    Payne, Richard; Moe, Jeffrey L; Sevier, Catherine Harvey; Sevier, David; Waitzkin, Michael

    2015-01-01

    In 2012, Duke University initiated a research project, funded by an unrestricted research grant from Millennium Laboratories, a drug testing company. The project focused on assessing the frequency and nature of questionable, unethical, and illegal business practices in the clinical drug testing industry and assessing the potential for establishing a business code of ethics. Laboratory leaders, clinicians, industry attorneys, ethicists, and consultants participated in the survey, were interviewed, and attended two face-to-face meetings to discuss a way forward. The study demonstrated broad acknowledgment of variations in the legal and regulatory environment, resulting in inconsistent enforcement of industry practices. Study participants expressed agreement that overtly illegal practices sometimes exist, particularly when laboratory representatives and clinicians discuss reimbursement, extent of testing, and potential business incentives with medical practitioners. Most respondents reported directly observing probable violations involving marketing materials, contracts, or, in the case of some individuals, directly soliciting people with offers of clinical supplies and other "freebies." While many study respondents were skeptical that voluntary standards alone would eliminate questionable business practices, most viewed ethics codes and credentialing as an important first step that could potentially mitigate uneven enforcement, while improving quality of care and facilitating preferred payment options for credentialed parties. Many were willing to participate in future discussions and industry-wide initiatives to improve the environment.

  6. Project Half Double

    DEFF Research Database (Denmark)

    Svejvig, Per; Ehlers, Michael; Adland, Karoline Thorp

    activities carried out within the framework of the projects. The formal part of Project Half Double was initiated in June 2015. We started out by developing, refining and testing the Half Double methodology on seven pilot projects in the first phase of the project, which will end June 2016. The current......Project Half Double has a clear mission to succeed in finding a project methodology that can increase the success rate of our projects while increasing the speed at which we generate new ideas and develop new products and services. Chaos and complexity should be seen as a basic condition...... and as an opportunity rather than a threat and a risk. We are convinced that by doing so, we can strengthen Denmark’s competitiveness and play an important role in the battle for jobs and future welfare. The overall goal is to deliver “projects in half the time with double the impact”, where projects in half the time...

  7. FED firmware interface testing with pixel phase 1 emulator

    CERN Document Server

    Kilpatrick, Matthew

    2017-01-01

    A hardware emulation of the CMS pixel detector phase 1 upgrade front-end electronics has been developed to test and validate the architecture of the back-end electronics (FED) firmware. The emulation is implemented on a Virtex 6 FPGA on the CERN GLIB uTCA platform, utilizing an 8-way SFP FPGA Mezzanine Card to drive compatible optical transmitters to the back-end electronics at 400 bps. The firmware emulates the complex functions of the phase 1 pixel readout chips (PSI46digv2 and PROC600) and token bit manager ASICs and allows for possible abnormalities that can occur in the output data stream. The emulation implements both fixed data patterns that are used as test vectors and realistic simulated data to drive the readout of the FED at the expected data and trigger rates. Testing software was developed to control the emulator and verify correct transmission of data and exception handling in the FED. An installation has been integrated into the pixel DAQ test system at CMS to be used for fast validation of F...

  8. FED firmware interface testing with pixel phase 1 emulator

    CERN Document Server

    Kilpatrick, Matthew

    2018-01-01

    A hardware emulation of the CMS pixel detector phase 1 upgrade front-end electronics has been developed to test and validate the architecture of the back-end electronics (FED) firmware. The emulation is implemented on a Virtex 6 FPGA on the CERN GLIB uTCA platform, utilizing an 8-way SFP FPGA Mezzanine Card to drive compatible optical transmitters to the back-end electronics at 400 bps. The firmware emulates the complex functions of the phase 1 pixel readout chips (PSI46digv2 and PROC600) and token bit manager ASICs and allows for possible abnormalities that can occur in the output data stream. The emulation implements both fixed data patterns that are used as test vectors and realistic simulated data to drive the readout of the FED at the expected data and trigger rates. Testing software was developed to control the emulator and verify correct transmission of data and exception handling in the FED. An installation has been integrated into the pixel DAQ test system at CMS to be used for fast validation of F...

  9. High Rate User Ka-Band Phased Array Antenna Test Results

    Science.gov (United States)

    Caroglanian, Armen; Perko, Kenneth; Seufert, Steve; Dod, Tom; Warshowsky, Jay; Day, John H. (Technical Monitor)

    2001-01-01

    The High Rate User Phased Array Antenna (HRUPAA) is a Ka-Band planar phased array designed by the Harris Corporation for the NASA Goddard Space Flight Center. The HRUPAA permits a satellite to downlink data either to a ground station or through the Tracking and Data Relay Satellite System (TDRSS). The HRUPAA is scanned electronically by ground station / user satellite command over a 120 degree cone angle. The phased array has the advantage of not imparting attitude disturbances to the user spacecraft. The 288-element transmit-only array has distributed RF amplifiers integrated behind each of the printed patch antenna elements. The array has 33 dBW EIRP and is left-hand circularly polarized. An engineering model of a partially populated array has been developed and delivered to NASA Goddard Space Flight Center. This report deals with the testing of the engineering model at the Goddard Antenna Range near-field and compact range facilities. The antenna specifications are described first, followed by the test plan and test results.

  10. Excitation power quantities in phase resonance testing of nonlinear systems with phase-locked-loop excitation

    Science.gov (United States)

    Peter, Simon; Leine, Remco I.

    2017-11-01

    Phase resonance testing is one method for the experimental extraction of nonlinear normal modes. This paper proposes a novel method for nonlinear phase resonance testing. Firstly, the issue of appropriate excitation is approached on the basis of excitation power considerations. Therefore, power quantities known from nonlinear systems theory in electrical engineering are transferred to nonlinear structural dynamics applications. A new power-based nonlinear mode indicator function is derived, which is generally applicable, reliable and easy to implement in experiments. Secondly, the tuning of the excitation phase is automated by the use of a Phase-Locked-Loop controller. This method provides a very user-friendly and fast way for obtaining the backbone curve. Furthermore, the method allows to exploit specific advantages of phase control such as the robustness for lightly damped systems and the stabilization of unstable branches of the frequency response. The reduced tuning time for the excitation makes the commonly used free-decay measurements for the extraction of backbone curves unnecessary. Instead, steady-state measurements for every point of the curve are obtained. In conjunction with the new mode indicator function, the correlation of every measured point with the associated nonlinear normal mode of the underlying conservative system can be evaluated. Moreover, it is shown that the analysis of the excitation power helps to locate sources of inaccuracies in the force appropriation process. The method is illustrated by a numerical example and its functionality in experiments is demonstrated on a benchmark beam structure.

  11. Safety test No. S-6, launch pad abort sequential test Phase II: solid propellant fire

    International Nuclear Information System (INIS)

    Snow, E.C.

    1975-08-01

    In preparation for the Lincoln Laboratory's LES 8/9 space mission, a series of tests was performed to evaluate the nuclear safety capability of the Multi-Hundred Watt (MHW) Radioisotope Thermoelectric Generator (RTG) to be used to supply power for the satellite. One such safety test is Test No. S-6, Launch Pad Abort Sequential Test. The objective of this test was to subject the RTG and its components to the sequential environments characteristic of a catastrophic launch pad accident to evaluate their capability to contain the 238 PuO 2 fuel. This sequence of environments was to have consisted of the blast overpressure and fragments, followed by the fireball, low velocity impact on the launch pad, and solid propellant fire. The blast overpressure and fragments were subsequently eliminated from this sequence. The procedures and results of Phase II of Test S-6, Solid Propellant Fire are presented. In this phase of the test, a simulant Fuel Sphere Assembly (FSA) and a mockup of a damaged Heat Source Assembly (HSA) were subjected to single proximity solid propellant fires of approximately 10-min duration. Steel was introduced into both tests to simulate the effects of launch pad debris and the solid rocket motor (SRM) casing that might be present in the fire zone. (TFD)

  12. Distributed Rocket Engine Testing Health Monitoring System, Phase II

    Data.gov (United States)

    National Aeronautics and Space Administration — Leveraging the Phase I achievements of the Distributed Rocket Engine Testing Health Monitoring System (DiRETHMS) including its software toolsets and system building...

  13. Final waste forms project: Performance criteria for phase I treatability studies

    International Nuclear Information System (INIS)

    Gilliam, T.M.; Hutchins, D.A.; Chodak, P. III

    1994-06-01

    This document defines the product performance criteria to be used in Phase I of the Final Waste Forms Project. In Phase I, treatability studies will be performed to provide open-quotes proof-of-principleclose quotes data to establish the viability of stabilization/solidification (S/S) technologies. This information is required by March 1995. In Phase II, further treatability studies, some at the pilot scale, will be performed to provide sufficient data to allow treatment alternatives identified in Phase I to be more fully developed and evaluated, as well as to reduce performance uncertainties for those methods chosen to treat a specific waste. Three main factors influence the development and selection of an optimum waste form formulation and hence affect selection of performance criteria. These factors are regulatory, process-specific, and site-specific waste form standards or requirements. Clearly, the optimum waste form formulation will require consideration of performance criteria constraints from each of the three categories. Phase I will focus only on the regulatory criteria. These criteria may be considered the minimum criteria for an acceptable waste form. In other words, a S/S technology is considered viable only if it meet applicable regulatory criteria. The criteria to be utilized in the Phase I treatability studies were primarily taken from Environmental Protection Agency regulations addressed in 40 CFR 260 through 265 and 268; and Nuclear Regulatory Commission regulations addressed in 10 CFR 61. Thus the majority of the identified criteria are independent of waste form matrix composition (i.e., applicable to cement, glass, organic binders etc.)

  14. Final waste forms project: Performance criteria for phase I treatability studies

    Energy Technology Data Exchange (ETDEWEB)

    Gilliam, T.M. [Oak Ridge National Lab., TN (United States); Hutchins, D.A. [Martin Marietta Energy Systems, Inc., Oak Ridge, TN (United States); Chodak, P. III [Massachusetts Institute of Technology (United States)

    1994-06-01

    This document defines the product performance criteria to be used in Phase I of the Final Waste Forms Project. In Phase I, treatability studies will be performed to provide {open_quotes}proof-of-principle{close_quotes} data to establish the viability of stabilization/solidification (S/S) technologies. This information is required by March 1995. In Phase II, further treatability studies, some at the pilot scale, will be performed to provide sufficient data to allow treatment alternatives identified in Phase I to be more fully developed and evaluated, as well as to reduce performance uncertainties for those methods chosen to treat a specific waste. Three main factors influence the development and selection of an optimum waste form formulation and hence affect selection of performance criteria. These factors are regulatory, process-specific, and site-specific waste form standards or requirements. Clearly, the optimum waste form formulation will require consideration of performance criteria constraints from each of the three categories. Phase I will focus only on the regulatory criteria. These criteria may be considered the minimum criteria for an acceptable waste form. In other words, a S/S technology is considered viable only if it meet applicable regulatory criteria. The criteria to be utilized in the Phase I treatability studies were primarily taken from Environmental Protection Agency regulations addressed in 40 CFR 260 through 265 and 268; and Nuclear Regulatory Commission regulations addressed in 10 CFR 61. Thus the majority of the identified criteria are independent of waste form matrix composition (i.e., applicable to cement, glass, organic binders etc.).

  15. The Age-ility Project (Phase 1): Structural and functional imaging and electrophysiological data repository

    NARCIS (Netherlands)

    Karayanidis, F.; Keuken, M.C.; Wong, A.; Rennie, J.L.; de Hollander, G.; Cooper, P.S.; Fulham, W.R.; Lenroot, R.; Parsons, M.; Philips, N.; Michie, P.T.; Forstmann, B.U.

    2015-01-01

    Our understanding of the complex interplay between structural and functional organisation of brain networks is being advanced by the development of novel multi-modal analyses approaches. The Age-ility Project (Phase 1) data repository offers open access to structural MRI, diffusion MRI, and

  16. Novel automatic phase lock determination for superconducting cavity tests at vertical test stand at RRCAT

    International Nuclear Information System (INIS)

    Singh, Kunver Adarsh Pratap; Mohania, Praveen; Rajput, Vikas; Baxy, Deodatta; Shrivastava, Purushottam

    2015-01-01

    RRCAT has developed a Vertical Test Stand (VTS) which is used to test the Nb superconducting cavities under cryogenic conditions. In the VTS, RF cavity is characterized for its quality factor variation vs the accelerating gradient. The RF system is an essential part of the VTS which is required to provide stable RF power to the cavity in terms of amplitude, frequency and phase. RF system of VTS consists of several modules including the LLRF system. The LLRF system consists of the 'Frequency Control Module' which controls the input frequency to the SCRF cavity. Due to high quality factor, bandwidth of the cavity is less than 1 Hz. Even slight mechanical vibrations (microphonics) causes change in cavity resonance frequency resulting in total reflection of incident power. A PLL based frequency tracking module has been used to track the resonant frequency of RF cavity. This module changes RF source frequency according to change in Cavity resonance frequency. A novel method using a LabView based computer program has been developed which changes the phase of input RF signal using IQ modulator and monitors the transmitted power, incident and reflected power. The program plots the graph between phase and ratio of transmitted power to incident/reflected power and gives optimum locking phase for operation which has resulted in significant saving in the overall process time for the tests of the cavities in VTS. (author)

  17. Now entering phase two...

    CERN Multimedia

    Katarina Anthony

    2012-01-01

    Building on the success of their feasibility phase, the CLIC test facility, CTF3, has just launched into a five-year project development phase. This will involve detailed performance optimisation studies, marking the project’s transition from pure research and development to prototyping and construction.   CLIC accelerator modules under construction at CERN. “With the feasibility phase now complete, we have established that CLIC can be built,” says Roberto Corsini, CLIC Collaboration spokesperson. “Now we want to be sure that it can provide the luminosity and energy performance needed. We will be looking at the engineering, performance and cost of a real CLIC machine also seeing if we can reduce it.” CTF3’s second phase will focus on selected performance-related research areas for further investigation. The largest of these involves the construction and testing of several authentic CLIC accelerator modules that are currently being ...

  18. Materials Information for Science and Technology (MIST): Project overview: Phase 1 and 2 and general considerations

    Energy Technology Data Exchange (ETDEWEB)

    Grattidge, W.; Westbrook, J.; McCarthy, J.; Northrup, C. Jr.; Rumble, J. Jr.

    1986-11-01

    The National Bureau of Standards and the Department of Energy have embarked on a program to build a demonstration computerized materials data system called Materials Information for Science and Technology (MIST). This report documents the first two phases of the project. The emphasis of the first phase was on determining what information was needed and how it could impact user productivity. The second phase data from the Aerospace Metal Handbook on a set of alloys was digitized and incorporated in the system.

  19. Photovoltaic test and demonstration project. [residential energy program

    Science.gov (United States)

    Forestieri, A. F.; Brandhorst, H. W., Jr.; Deyo, J. N.

    1976-01-01

    The considered project consists of three subprojects related to applications, device performance and diagnostics, and endurance testing. The objectives of the applications subproject include the determination of the operating characteristics for a variety of photovoltaic conversion systems. A system test facility is being constructed in this connection and a prototype residence experiment is to be conducted. Market demand for solar cells is to be stimulated by demonstrating suitability of solar cells for specific near-term applications. Activities conducted in connection with device performance studies and diagnostics are also discussed along with developments in the area of endurance testing.

  20. Microgravity Multi-Phase Flow Experiment for Suborbital Testing (MFEST)

    Data.gov (United States)

    National Aeronautics and Space Administration — The primary objective is to conduct a pathfinder, suborbital flight experiment for two-phase fluid flow and separator operations.The primary purpose of this test...

  1. Phase Retrieval Techniques In Coordinates Measurement

    International Nuclear Information System (INIS)

    Harizanova, J. I.; Stoykova, E. V.; Sainov, V. C.

    2007-01-01

    A precise pattern projection profilometry for three-dimensional shape measurements with different methods of fringe generation is presented. The application of phase-shifting algorithm along with two-spacing illumination allow for phase retrieval and estimation of relative and absolute coordinates of the tested samples. The following experimental approaches for fringe generation are investigated: interferometric approach based on a classical Michelson interferometer, digital computation with a DMD projection and light modulation by a sinusoidal phase grating. The theoretical background, experimental results as well as comparison of the applied generation methods are analyzed. The obtained outcomes successfully display the applicability of this technique for surface profile measurement. The application of the proposed techniques for remote, non-destructive in-situ inspection of real objects from cultural heritage is discussed

  2. Building Energy Simulation Test for Existing Homes (BESTEST-EX); Phase 1 Test Procedure: Building Thermal Fabric Cases

    Energy Technology Data Exchange (ETDEWEB)

    Judkoff, Ron [National Renewable Energy Lab. (NREL), Golden, CO (United States; Polly, Ben [National Renewable Energy Lab. (NREL), Golden, CO (United States; Bianchi, Marcus [National Renewable Energy Lab. (NREL), Golden, CO (United States; Neymark, Joel [J. Neymark & Associates, Golden, CO (United States)

    2010-08-01

    This report documents the initial Phase 1 test process for testing the reliability of software models that predict retrofit energy savings of existing homes, including their associated calibration methods.

  3. Texas Clean Energy Project: Topical Report, Phase 1 - February 2010-December 2012

    Energy Technology Data Exchange (ETDEWEB)

    Mattes, Karl

    2012-11-01

    Summit Texas Clean Energy, LLC (STCE) is developing the Texas Clean Energy Project (TCEP or the project) to be located near Penwell, Texas. The TCEP will include an Integrated Gasification Combined Cycle (IGCC) plant with a nameplate capacity of 400 megawatts electric (MWe), combined with the production of urea fertilizer and the capture, utilization and storage of carbon dioxide (CO2) sold commercially for regional use in enhanced oil recovery (EOR) in the Permian Basin of west Texas. The TCEP will utilize coal gasification technology to convert Powder River Basin subbituminous coal delivered by rail from Wyoming into a synthetic gas (syngas) which will be cleaned and further treated so that at least 90 percent of the overall carbon entering the facility will be captured. The clean syngas will then be divided into two high-hydrogen (H2) concentration streams, one of which will be combusted as a fuel in a combined cycle power block for power generation and the other converted into urea fertilizer for commercial sale. The captured CO2 will be divided into two streams: one will be used in producing the urea fertilizer and the other will be compressed for transport by pipeline for offsite use in EOR and permanent underground sequestration. The TCEP was selected by the U.S. Department of Energy (DOE) Office of Fossil Energy (FE) for cost-shared co-funded financial assistance under Round 3 of its Clean Coal Power Initiative (CCPI). A portion of this financial assistance was budgeted and provided for initial development, permitting and design activities. STCE and the DOE executed a Cooperative Agreement dated January 29, 2010, which defined the objectives of the project for all phases. During Phase 1, STCE conducted and completed all objectives defined in the initial development, permitting and design portions of the Cooperative Agreement. This topical report summarizes all work associated with the project objectives, and additional work

  4. A "Projective" Test of the Golden Section Hypothesis.

    Science.gov (United States)

    Lee, Chris; Adams-Webber, Jack

    1987-01-01

    In a projective test of the golden section hypothesis, 24 high school students rated themselves and 10 comic strip characters on basis of 12 bipolar constructs. Overall proportion of cartoon figures which subjects assigned to positive poles of constructs was very close to golden section. (Author/NB)

  5. Underground Test Area Quality Assurance Project Plan Nevada National Security Site, Nevada, Revision 0

    Energy Technology Data Exchange (ETDEWEB)

    Irene Farnham

    2011-05-01

    This Quality Assurance Project Plan (QAPP) provides the overall quality assurance (QA) program requirements and general quality practices to be applied to the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office (NNSA/NSO) Underground Test Area (UGTA) Sub-Project (hereafter the Sub-Project) activities. The requirements in this QAPP are consistent with DOE Order 414.1C, Quality Assurance (DOE, 2005); U.S. Environmental Protection Agency (EPA) Guidance for Quality Assurance Project Plans for Modeling (EPA, 2002); and EPA Guidance on the Development, Evaluation, and Application of Environmental Models (EPA, 2009). The QAPP Revision 0 supersedes DOE--341, Underground Test Area Quality Assurance Project Plan, Nevada Test Site, Nevada, Revision 4.

  6. Nuclear model parameter testing for nuclear data evaluation (Reference Input Parameter Library: Phase II). Summary report of the second research co-ordination meeting

    International Nuclear Information System (INIS)

    Herman, M.

    2000-09-01

    This report summarizes the results and recommendations of the Second Research Coordination Meeting on Testing and Improvement of the Reference Input Parameter Library: Phase II. A primary aim of this meeting was to review progress in the CRP work, to review results of testing the library, to establish the RIPL-2 format and to decide on the contents of the library. The actions were agreed with an aim to complete the project by the end of 2001. Separate abstracts were prepared for 10 individual papers

  7. Controlled ecological life support system breadboard project, 1988

    Science.gov (United States)

    Knott, W. M.

    1990-01-01

    The Closed Ecological Life Support System (CELSS) Breadboard Project, NASA's effort to develop the technology required to produce a functioning bioregenerative system, is discussed. The different phases of the project and its current status are described. The relationship between the project components are shown, and major project activities for fiscal years 1989 to 1993 are listed. The Biomass Production Chamber (BPC) became operational and tests of wheat as a single crop are nearing completion.

  8. Project W-314 specific test and evaluation plan 241-AN-B valve pit

    International Nuclear Information System (INIS)

    Hays, W.H.

    1998-01-01

    The purpose of this Specific Test and Evaluation Plan (STEP) is to provide a detailed written plan for the systematic testing of modifications made to the 241-AN-B Valve Pit by the W-314 Project. The STEP develops the outline for test procedures that verify the system's performance to the established Project design criteria. The STEP is a lower tier document based on the W-314 Test and Evaluation Plan (TEP)

  9. Seismic safety margins research program. Phase I final report - Plant/site selection and data collection (Project I)

    International Nuclear Information System (INIS)

    Chuang, T.Y.

    1981-07-01

    Project I of Phase I of the Seismic Safety Margins Research Program (SSMRP) comprised two parts: the selection of a representative nuclear power plant/site for study in Phase I and the collection of data needed by the other SSMRP projects. Unit 1 of the Zion Nuclear Power Plant in Zion, Illinois, was selected for the SSMRP Phase I studies. Unit 1 of the Zion plant has been validated as a good choice for the Phase I study plant. Although no single nuclear power plant can represent all such plants equally well, selection criteria were developed to maximize the generic implications of Phase I of the SSMRP. On the basis of the selection criteria, the Zion plant and its site were found to be reasonably representative of operating and future plants with regard to its nuclear steam supply system; the type of containment structure (prestressed concrete); its electrical capacity (1100 MWe); its location (the Midwest); the peak seismic acceleration used for design (0.17g); and the properties of the underlying soil (the low-strain shear-wave velocity is 1650 ft/s in a 50- to 100-ft-thick layer of soil overlying sedimentary bedrock). (author)

  10. A test section design to simulate horizontal two-phase air-water flow

    International Nuclear Information System (INIS)

    Faccini, Jose Luiz H.; Cesar, Silvia B.G.; Coutinho, Jorge A.; Freitas, Sergio Carlos; Addor, Pedro N.

    2002-01-01

    In this work an air-water two-phase flow horizontal test section assembling at Nuclear Engineering Institute (IEN) is presented. The test section was designed to allow four-phase flow patterns to be simulated: bubble flow, stratified flow, wave flow and slug flow. These flow patterns will be identified by non-conventional ultrasonic techniques which have been developed to meet this particular application. Based on the separated flow and drift-flux models the test section design steps are shown. A description of the test section and its instrumentation and data acquisition system is also provided. (author)

  11. Horonobe underground research laboratory project. The plan for the in-situ experiments in Phase 2 and Phase 3 in/around URL

    International Nuclear Information System (INIS)

    Matsui, Hiroya

    2005-09-01

    This report describes for preliminary research plan in Phase 2 and Phase 3 taken into consideration of expected geological environment at location of URL based on the results of the investigations until FY 2003/2004. Duration of construction phase and total cost are considered as important factors for planning as well. The below items are planned for in-situ experiments in Phase 2 and Phase 3 in/around URL are planning. Phase 2. (In-situ experiments for understanding of geological environment) Geological survey at tunnel. Inflow measurement in shafts. Water pressure monitoring and groundwater sampling around shafts during excavation of URL. Investigation for EDZ around shafts. Stress measurement on support. Detail investigations for geological environment around drifts. Excavation disturbance experiment in a drift. Investigation for desaturation zone and REDOX condition around drifts. (Engineered barrier system) In-situ experiment on low-alkali concrete. In-situ experiment for gas migration in engineering barrier system. Phase 3. (In-situ experiments for understanding of geological environment) EDZ experiment for stress interference. Investigation of long-term behavior of EDZ around drifts. Detail investigation on fault/fault zone. Monitoring for the change of geological environment at earthquake. Backfill test in boreholes. (Engineered barrier system) T-H-M-C experiment. In-situ experiment for corrosion of overpack. Investigation of the influence of a concrete to engineering barrier system and geological environment. In-situ experiment for interference between backfill material and geological environment. Backfill test in a drift. (Safety assessment) Tracer tests in engineering barrier system, natural barrier and fault/fault zone. (author)

  12. Sakhalin 2, phase 2 project : meeting the Arctic challenge in a sub-Arctic environment

    International Nuclear Information System (INIS)

    Reece, A.; Gerges, A.; Efthymiou, M.; Winkler, M.

    2008-01-01

    Sakhalin Energy's objective is to commercially develop, operate and market the hydrocarbon resources and associated infrastructure governed by the Sakhalin 2 licenses for the sustainable benefit of shareholders, the Russian Federation, the Sakhalin Oblast and the wider community. This presentation discussed Sakhalin Energy's holdings including its investment company and hydrocarbon projects in eastern Russia. The Sakhalin area is a remote island that lacks infrastructure, has a low population density, with a rich onshore and offshore wildlife. It is a seismically active area, with seasonal operating windows, drifting pack ice from December to June, waves up to 18 metre maximum height, and frequent fog in spring and summer. The temperature also varies from 28 degrees Celsius to -40 degrees Celsius. The presentation also addressed the rerouting of offshore pipelines to ensure the least possible disturbance to western gray whale migration. Several photographs and illustrations of the phase 1 project were presented. Open water conditions were also illustrated. The phase 2 project was then outlined. This included illustrations of the platform, plant and export terminal, and onshore processing facility. Other photographs that were shown in the presentation included the offshore pipeline installation; a view of the shore approach to the pipeline installation; oil spill response; and escape, evacuation, and response. The design challenges and design philosophy of the project were also identified. The presentation concluded with a discussion of ice loading and platform response. figs

  13. Sakhalin 2, phase 2 project : meeting the Arctic challenge in a sub-Arctic environment

    Energy Technology Data Exchange (ETDEWEB)

    Reece, A.; Gerges, A.; Efthymiou, M.; Winkler, M. [Sakhalin Energy, Moscow (Russian Federation)

    2008-09-15

    Sakhalin Energy's objective is to commercially develop, operate and market the hydrocarbon resources and associated infrastructure governed by the Sakhalin 2 licenses for the sustainable benefit of shareholders, the Russian Federation, the Sakhalin Oblast and the wider community. This presentation discussed Sakhalin Energy's holdings including its investment company and hydrocarbon projects in eastern Russia. The Sakhalin area is a remote island that lacks infrastructure, has a low population density, with a rich onshore and offshore wildlife. It is a seismically active area, with seasonal operating windows, drifting pack ice from December to June, waves up to 18 metre maximum height, and frequent fog in spring and summer. The temperature also varies from 28 degrees Celsius to -40 degrees Celsius. The presentation also addressed the rerouting of offshore pipelines to ensure the least possible disturbance to western gray whale migration. Several photographs and illustrations of the phase 1 project were presented. Open water conditions were also illustrated. The phase 2 project was then outlined. This included illustrations of the platform, plant and export terminal, and onshore processing facility. Other photographs that were shown in the presentation included the offshore pipeline installation; a view of the shore approach to the pipeline installation; oil spill response; and escape, evacuation, and response. The design challenges and design philosophy of the project were also identified. The presentation concluded with a discussion of ice loading and platform response. figs.

  14. Two-phase flow in volatile oil reservoir using two-phase pseudo-pressure well test method

    Energy Technology Data Exchange (ETDEWEB)

    Sharifi, M.; Ahmadi, M. [Calgary Univ., AB (Canada)

    2009-09-15

    A study was conducted to better understand the behaviour of volatile oil reservoirs. Retrograde condensation occurs in gas-condensate reservoirs when the flowing bottomhole pressure (BHP) lowers below the dewpoint pressure, thus creating 4 regions in the reservoir with different liquid saturations. Similarly, when the BHP of volatile oil reservoirs falls below the bubblepoint pressure, two phases are created in the region around the wellbore, and a single phase (oil) appears in regions away from the well. In turn, higher gas saturation causes the oil relative permeability to decrease towards the near-wellbore region. Reservoir compositional simulations were used in this study to predict the fluid behaviour below the bubblepoint. The flowing bottomhole pressure was then exported to a well test package to diagnose the occurrence of different mobility regions. The study also investigated the use of a two-phase pseudo-pressure method on volatile and highly volatile oil reservoirs. It was concluded that this method can successfully predict the true permeability and mechanical skin. It can also distinguish between mechanical skin and condensate bank skin. As such, the two-phase pseudo-pressure method is particularly useful for developing after-drilling well treatment and enhanced oil recovery process designs. However, accurate relative permeability and PVT data must be available for reliable interpretation of the well test in volatile oil reservoirs. 18 refs., 3 tabs., 9 figs.

  15. Production circulator fabrication and testing for core flow test loop. Final report, Phase III

    Energy Technology Data Exchange (ETDEWEB)

    1981-05-01

    The performance testing of two production helium circulators utilizing gas film lubrication is described. These two centrifugal-type circulators plus an identical circulator prototype will be arranged in series to provide the helium flow requirements for the Core Flow Test Loop which is part of the Gas-Cooled Fast Breeder Reactor Program (GCFR) at the Oak Ridge National Laboratory. This report presents the results of the Phase III performance and supplemental tests, which were carried out by MTI during the period of December 18, 1980 through March 19, 1981. Specific test procedures are outlined and described, as are individual tests for measuring the performance of the circulators. Test data and run descriptions are presented.

  16. Production circulator fabrication and testing for core flow test loop. Final report, Phase III

    International Nuclear Information System (INIS)

    1981-05-01

    The performance testing of two production helium circulators utilizing gas film lubrication is described. These two centrifugal-type circulators plus an identical circulator prototype will be arranged in series to provide the helium flow requirements for the Core Flow Test Loop which is part of the Gas-Cooled Fast Breeder Reactor Program (GCFR) at the Oak Ridge National Laboratory. This report presents the results of the Phase III performance and supplemental tests, which were carried out by MTI during the period of December 18, 1980 through March 19, 1981. Specific test procedures are outlined and described, as are individual tests for measuring the performance of the circulators. Test data and run descriptions are presented

  17. Acceptance test report for project C-157 ''T-Plant electrical upgrade''

    International Nuclear Information System (INIS)

    Jeppson, L.A.

    1997-01-01

    This Acceptance Test Report (ATR) documents for record purposes the field results, acceptance, and approvals of the completed acceptance test per WHC-SD-Cl57-ATP-001, Rev. 0, ''Acceptance Test Proceedure for Project C-157 'T Plant Electrical Upgrade''' The test was completed and approved without any problems or exceptions

  18. Acceptance test report for project C-157 ``T-Plant electrical upgrade``

    Energy Technology Data Exchange (ETDEWEB)

    Jeppson, L.A.

    1997-08-05

    This Acceptance Test Report (ATR) documents for record purposes the field results, acceptance, and approvals of the completed acceptance test per WHC-SD-Cl57-ATP-001, Rev. 0, ``Acceptance Test Proceedure for Project C-157 `T Plant Electrical Upgrade``` The test was completed and approved without any problems or exceptions.

  19. Reactor building pressure proof test (PPT) and leak rate test (LRT) of Qinshan phase III (CANDU) project

    International Nuclear Information System (INIS)

    Gu Jun; Shi Jinqi; Fan Fuping

    2004-12-01

    As the first reactor building (R/B) without stainless steel liner in china, TQNPC studied the containment characteristics, such as strong concrete absorb/release air effect, poor containment penetration. etc. And carefully prepared test scheme and emergency response, creatively introduced the instrument air self-supply system in reactor building, developed the special measurement and analysis system for PPT and LRT, organized work under high-pressure on large-scale in the test. Finally got the containment leak rate result and the test-cost-time value is the best in all same type tests. (authors)

  20. The Plasma Hearth Process Technology Development Project

    International Nuclear Information System (INIS)

    Geimer, R.; Batdorf, J.; Wolfe, P.

    1993-01-01

    The US DOE Office of Technology Development (OTD) is currently evaluating the Plasma Hearth Process (PHP) for potential treatment of several DOE waste types. The PHP is a high-temperature vitrification process that has potential application for a wide range of mixed waste types in both the low-level and transuranic mixed waste categories. The PHP is being tested under both the OTD Mixed Waste Integrated Program and the Buried Waste Integrated Demonstration. Initial testing has been completed on several different surrogate waste forms that are representative of some of the DOE mixed waste streams. Destruction of organic material exceeds that of conventional incineration technologies. The vitrified residual has leaching characteristics comparable to glass formulations produced in the high-level waste program. The first phase of the PHP demonstration project has been successfully completed, and the project is currently beginning a comprehensive second phase of development and testing

  1. Sustainable development in city districts: BaLaLuZ project - Bellevaux Phase 2; Quartiers durables BaLaLuZh. Rapport Lausanne-Bellevaux. Phase 2

    Energy Technology Data Exchange (ETDEWEB)

    Robinson, D; Nicol, L [Swiss Federal Institute of Technology (EPFL), Laboratoire d' energie solaire et de physique du batiment (LESO-PB), Lausanne (Switzerland); Pattaroni, L [Swiss Federal Institute of Technology (EPFL), Laboratoire de sociologie urbaine (LASUR), Lausanne (Switzerland); Muehll, D von der [Swiss Federal Institute of Technology (EPFL), Laboratoire Choros, Lausanne (Switzerland)

    2007-04-15

    This comprehensive final report for the Swiss Federal Office of Energy (SFOE) is one of a series of reports concerning municipal development in various cities in Switzerland. The four city districts involved include Basel (Gundeldinger Feld), Lausanne (Bellevaux), Lucerne (Basel-/Bernstrasse) and Zurich (Werdwies). This final report summarises the results of the second phase of the project in the Bellevaux district of Lausanne. The work done in this second phase is reviewed. The results of phase 1 were followed up in that it was decided to facilitate the renovation of specific buildings where possible. A further aim was to evaluate the extent to which cycling is used as a means of transport as well as to identify possible barriers and solutions to the more widespread use of cycling as a means of transportation. The report describes the work necessary and strategies for specific buildings, including participatory procedures. As far as cycling is concerned, the results of questionnaires are examined and discussed. Communication and animation projects are also looked at.

  2. Studsvik`s fuel R and D projects

    Energy Technology Data Exchange (ETDEWEB)

    Grounes, M [Studsvik Nuclearr AB, Nykoping (Sweden)

    1997-08-01

    The report reviews some recently performed, ongoing and planned fuel R and D projects, executed by Studsvik Nuclear AB, a subsidiary of Studsvik AB. Data from these projects are used as experimental support for fuel modelling at high burnup. Much of Studsvik Nuclear`s R and D work has been concentrated on fuel testing, which can be made in the R2 test reactor with high precision under realistic water reactor conditions. This type of work started in the early 1960s. The fuel testing projects executed at Studsvik have been organized under three different types of sponsorship: International (multilateral) fuel projects: jointly sponsored internationally on a world-wide basis, with project information remaining restricted to the project participants throughout the project`s duration and for some pre-determined time after project completion; Bilateral fuel projects: sponsored by one single organization, or a few co-operating organizations, with project information remaining restricted to the sponsor, sometimes published later; in-house R and D work: sponsored by Studsvik Nuclear. The fuel testing activities can be divided into a number of well-defined steps as follows: Base irradiation, performed in a power reactor, or in Studsvik`s R2 test reactor; power ramping and/or other in-pile measurements, performed in Studsvik`s R2 test reactor. Non-destructive testing between different phases of an experiment, performed in Studsvik`s R2 reactor pool, or in Studsvik`s Hot Cell Laboratory; destructive post-irradiation examinations, performed in Studsvik`s Hot Cell Laboratory, or in the sponsor`s hot cell laboratory. 47 refs, 2 tabs.

  3. Medical information, communication, and archiving system (MICAS): Phase II integration and acceptance testing

    Science.gov (United States)

    Smith, Edward M.; Wandtke, John; Robinson, Arvin E.

    1999-07-01

    The Medical Information, Communication and Archive System (MICAS) is a multi-modality integrated image management system that is seamlessly integrated with the Radiology Information System (RIS). This project was initiated in the summer of 1995 with the first phase being installed during the first half of 1997 and the second phase installed during the summer of 1998. Phase II enhancements include a permanent archive, automated workflow including modality worklist, study caches, NT diagnostic workstations with all components adhering to Digital Imaging and Communications in Medicine (DICOM) standards. This multi-vendor phased approach to PACS implementation is designed as an enterprise-wide PACS to provide images and reports throughout our healthcare network. MICAS demonstrates that aa multi-vendor open system phased approach to PACS is feasible, cost-effective, and has significant advantages over a single vendor implementation.

  4. Two-phase flow patterns recognition and parameters estimation through natural circulation test loop image analysis

    Energy Technology Data Exchange (ETDEWEB)

    Mesquita, R.N.; Libardi, R.M.P.; Masotti, P.H.F.; Sabundjian, G.; Andrade, D.A.; Umbehaun, P.E.; Torres, W.M.; Conti, T.N.; Macedo, L.A. [Instituto de Pesquisas Energeticas e Nucleares (IPEN/CNEN-SP), Sao Paulo, SP (Brazil). Nuclear Engineering Center], e-mail: rnavarro@ipen.br

    2009-07-01

    Visualization of natural circulation test loop cycles is used to study two-phase flow patterns associated with phase transients and static instabilities of flow. Experimental studies on natural circulation flow were originally related to accidents and transient simulations relative to nuclear reactor systems with light water refrigeration. In this regime, fluid circulation is mainly caused by a driving force ('thermal head') which arises from density differences due to temperature gradient. Natural circulation phenomenon has been important to provide residual heat removal in cases of 'loss of pump power' or plant shutdown in nuclear power plant accidents. The new generation of compact nuclear reactors includes natural circulation of their refrigerant fluid as a security mechanism in their projects. Two-phase flow patterns have been studied for many decades, and the related instabilities have been object of special attention recently. Experimental facility is an all glass-made cylindrical tubes loop which contains about twelve demineralized water liters, a heat source by an electrical resistor immersion heater controlled by a Variac, and a helicoidal heat exchanger working as cold source. Data is obtained through thermo-pairs distributed over the loop and CCD cameras. Artificial intelligence based algorithms are used to improve (bubble) border detection and patterns recognition, in order to estimate and characterize, phase transitions patterns and correlate them with the periodic static instability (chugging) cycle observed in this circuit. Most of initial results show good agreement with previous numerical studies in this same facility. (author)

  5. Two-phase flow patterns recognition and parameters estimation through natural circulation test loop image analysis

    International Nuclear Information System (INIS)

    Mesquita, R.N.; Libardi, R.M.P.; Masotti, P.H.F.; Sabundjian, G.; Andrade, D.A.; Umbehaun, P.E.; Torres, W.M.; Conti, T.N.; Macedo, L.A.

    2009-01-01

    Visualization of natural circulation test loop cycles is used to study two-phase flow patterns associated with phase transients and static instabilities of flow. Experimental studies on natural circulation flow were originally related to accidents and transient simulations relative to nuclear reactor systems with light water refrigeration. In this regime, fluid circulation is mainly caused by a driving force ('thermal head') which arises from density differences due to temperature gradient. Natural circulation phenomenon has been important to provide residual heat removal in cases of 'loss of pump power' or plant shutdown in nuclear power plant accidents. The new generation of compact nuclear reactors includes natural circulation of their refrigerant fluid as a security mechanism in their projects. Two-phase flow patterns have been studied for many decades, and the related instabilities have been object of special attention recently. Experimental facility is an all glass-made cylindrical tubes loop which contains about twelve demineralized water liters, a heat source by an electrical resistor immersion heater controlled by a Variac, and a helicoidal heat exchanger working as cold source. Data is obtained through thermo-pairs distributed over the loop and CCD cameras. Artificial intelligence based algorithms are used to improve (bubble) border detection and patterns recognition, in order to estimate and characterize, phase transitions patterns and correlate them with the periodic static instability (chugging) cycle observed in this circuit. Most of initial results show good agreement with previous numerical studies in this same facility. (author)

  6. Project Physics Tests 3, The Triumph of Mechanics.

    Science.gov (United States)

    Harvard Univ., Cambridge, MA. Harvard Project Physics.

    Test items relating to Project Physics Unit 3 are presented in this booklet. Included are 70 multiple-choice and 20 problem-and-essay questions. Concepts of mechanics are examined on energy, momentum, kinetic theory of gases, pulse analyses, "heat death," water waves, power, conservation laws, normal distribution, thermodynamic laws, and…

  7. X-ray phase radiography and tomography with grating interferometry and the reverse projection technique

    International Nuclear Information System (INIS)

    Wang, Zhili; Gao, Kun; Ge, Xin; Wu, Zhao; Chen, Heng; Wang, Shenghao; Wu, Ziyu; Zhu, Peiping; Yuan, Qingxi; Huang, Wanxia; Zhang, Kai

    2013-01-01

    X-ray grating interferometry provides substantially increased contrast over conventional absorption-based imaging methods, and therefore new and complementary information. Compared with other phase-contrast imaging techniques, x-ray grating interferometry can overcome some of the problems that have impaired the applications of x-ray phase-contrast radiography and phase tomography. Recently, special attention has been paid to the development of quantitative phase retrieval methods, which is mandatory to perform x-ray phase tomography, to achieve material identification, to differentiate distinct tissues, etc. Typically, the phase-stepping approach has been utilized for phase retrieval in grating interferometry. This method requires a grating scanning and acquisition of multiple radiographic projections, and therefore is disadvantageous in terms of imaging speed and radiation damage. Here we present an innovative, highly sensitive approach, dubbed ‘reverse projection’ (RP), for quantitative phase retrieval. Compared with the phase-stepping approach, the present RP method abandons grating scanning completely, and thus is advantageous due to its much higher efficiency and the reduced radiation dose, without the degradation of reconstruction quality. This review presents a detailed explanation of the principle of the RP method. Both radiography and phase tomography experiments are performed to validate the RP method. We believe that this new technique will find widespread applications in biomedical imaging and in vivo studies. (paper)

  8. Preliminary project of installation for separation tubes tests-ITTS

    International Nuclear Information System (INIS)

    Rocha, Z.

    1984-01-01

    A consolidation of actual ideas about installation, entitled ''Installation to separation tubes tests-ITTS'', expected to CDTN is presented. The project bases, the testing to be realized, the procedures to be obeyed during the operation, the components and the space required by installation and auxiliary equipments, the presumable origin of components (nacional and international), including a preliminary list of building and operation costs are described. (author) [pt

  9. Best practices of Building Information Modelling (BIM) implementation in design phase for construction project

    Science.gov (United States)

    Kasim, N.; Zainal Abidin, N. A.; Zainal, R.; Sarpin, N.; Rahim, M. H. I. Abd; Saikah, M.

    2017-11-01

    Implementation of Building Information Modelling (BIM) was expected to bring improvement in current practices of Malaysian construction industry. In the design phase, there is a lack of a ready pool of skilled workers who are able to develop BIM strategic plan and effectively utilise it. These create boundaries for BIM nature in Malaysian construction industry specifically in the design phase to achieve its best practices. Therefore, the objectives of this research are to investigate the current practices of BIM implementation in the design phase as well as the best practices factors of BIM implementation in the design phase. The qualitative research approach is carried out through semi-structured interviews with the designers of different organisations which adopt BIM in the design phase. Data collection is analysed by executing content analysis method. From the findings, the best practices factors of BIM implementation in design phase such as the incentive for BIM training, formal approach to monitoring automated Level of Detailing (LOD), run a virtual meeting and improve Industry Foundation Class (IFC). Thus, best practices factors which lead to practices improvements in the design phase of project development which subsequently improves the implementation of BIM in the design phase of Malaysian construction industry.

  10. Project Physics Tests 2, Motion in the Heavens.

    Science.gov (United States)

    Harvard Univ., Cambridge, MA. Harvard Project Physics.

    Test items relating to Project Physics Unit 2 are presented in this booklet. Included are 70 multiple-choice and 22 problem-and-essay questions. Concepts of motion in the heavens are examined for planetary motions, heliocentric theory, forces exerted on the planets, Kepler's laws, gravitational force, Galileo's work, satellite orbits, Jupiter's…

  11. Code of Conduct for wind-power projects - Phases 1 and 2; Code of Conduct fuer windkraftprojekte. Phase 1 und 2 - Systemanalyse, Lessons Learned und Bewertung bestehender Instrumente

    Energy Technology Data Exchange (ETDEWEB)

    Strub, P. [Pierre Strub, freischaffender Berater, Binningen (Switzerland); Ziegler, Ch. [Inter Act, Basel (Switzerland)

    2008-08-15

    This paper discusses the results of the first two phases of a project concerning wind-power projects. The paper deals with the results of a system analysis, takes a look at lessons learned and presents an appraisal of existing instruments. A system-analysis of wind-power projects is presented with emphasis on social factors and the role of stakeholders. The success factors concerning social acceptance of wind-power projects and their special characteristics are discussed. Lessons learned are examined. Instruments for the sustainable implementation of projects are looked at, in particular with a focus on social acceptance

  12. Project 8, Phase III Design: Placing an eV-Scale Limit on the Neutrino Mass using Cyclotron Radiation Emission Spectroscopy

    Science.gov (United States)

    Oblath, Noah; Project 8 Collaboration

    2016-09-01

    We report on the design concept for Phase III of the Project 8 experiment. In the third phase of Project 8 we aim to place a limit on the neutrino mass that is similar to the current limits set by tritium beta-decay experiments, mν radioastronomy will be employed to search for and track electron signals in the fiducial volume. This talk will present the quantitative design concept for the phased-array receiver, and illustrate how we are progressing towards the Phase IV experiment, which will have sensitivity to the neutrino mass scale allowed by the inverted mass hierarchy. This work is supported by the DOE Office of Science Early Career Research Program, and the Laboratory Directed Research and Development Program at Pacific Northwest National Laboratory.

  13. Closure of Regenerative Life Support Systems: Results of the Lunar-Mars Life Support Test Project

    Science.gov (United States)

    Barta, Daniel; Henninger, D.; Edeen, M.; Lewis, J.; Smth, F.; Verostko, C.

    2006-01-01

    Future long duration human exploration missions away from Earth will require closed-loop regenerative life support systems to reduce launch mass, reduce dependency on resupply and increase the level of mission self sufficiency. Such systems may be based on the integration of biological and physiocochemical processes to produce potable water, breathable atmosphere and nutritious food from metabolic and other mission wastes. Over the period 1995 to 1998 a series of ground-based tests were conducted at the National Aeronautics and Space Administration, Johnson Space Center, to evaluate the performance of advanced closed-loop life support technologies with real human metabolic and hygiene loads. Named the Lunar-Mars Life Support Test Project (LMLSTP), four integrated human tests were conducted with increasing duration, complexity and closure. The first test, LMLSTP Phase I, was designed to demonstrate the ability of higher plants to revitalize cabin atmosphere. A single crew member spent 15 days within an atmospherically closed chamber containing 11.2 square meters of actively growing wheat. Atmospheric carbon dioxide and oxygen levels were maintained by control of the rate of photosynthesis through manipulation of light intensity or the availability of carbon dioxide and included integrated physicochemical systems. During the second and third tests, LMLSTP Phases II & IIa, four crew members spent 30 days and 60 days, respectively, in a larger sealed chamber. Advanced physicochemical life support hardware was used to regenerate the atmosphere and produce potable water from wastewater. Air revitalization was accomplished by using a molecular sieve and a Sabatier processor for carbon dioxide absorption and reduction, respectively, with oxygen generation performed by water hydrolysis. Production of potable water from wastewater included urine treatment (vapor compression distillation), primary treatment (ultrafiltration/reverse osmosis and multi-filtration) and post

  14. Phase selection in the mushy-zone: LODESTARS and ELFSTONE projects

    International Nuclear Information System (INIS)

    Matson, D M; Hyers, R W; Volkmann, T; Fecht, H-J

    2011-01-01

    In a collaboration sponsored by ESA and NASA, international partners have developed a work plan to successfully address key issues relating to understanding the role of convection on alloy phase selection for commercially important structural alloys using the MSL-EML facility aboard the International Space Station. The approach is two-pronged. First, ground and space-based experiments will develop a baseline database to anchor subsequent modelling predictions. Tasks include sample preparation and verification, ground-based transformation evaluation, space-based experiments, and thermophysical property evaluation to support modelling activities. Second, modelling and theoretical analysis tasks will lead to a new understanding of the role of convection in phase selection for this class of materials. These models will allow prediction and control of microstructural evolution during solidification processing. Tasks include modelling of macroconvection induced by the EM levitation field, modelling of microconvection within the dendrite array, nucleation modelling, and modelling of the transformation kinetics specific to each alloy system. This paper outlines how two NASA-sponsored projects relate to the goals of the international collaboration.

  15. Phase selection in the mushy-zone: LODESTARS and ELFSTONE projects

    Science.gov (United States)

    Matson, D. M.; Hyers, R. W.; Volkmann, T.; Fecht, H.-J.

    2011-12-01

    In a collaboration sponsored by ESA and NASA, international partners have developed a work plan to successfully address key issues relating to understanding the role of convection on alloy phase selection for commercially important structural alloys using the MSL-EML facility aboard the International Space Station. The approach is two-pronged. First, ground and space-based experiments will develop a baseline database to anchor subsequent modelling predictions. Tasks include sample preparation and verification, ground-based transformation evaluation, space-based experiments, and thermophysical property evaluation to support modelling activities. Second, modelling and theoretical analysis tasks will lead to a new understanding of the role of convection in phase selection for this class of materials. These models will allow prediction and control of microstructural evolution during solidification processing. Tasks include modelling of macroconvection induced by the EM levitation field, modelling of microconvection within the dendrite array, nucleation modelling, and modelling of the transformation kinetics specific to each alloy system. This paper outlines how two NASA-sponsored projects relate to the goals of the international collaboration.

  16. Technical realisation of the VISA-II Project, Phase II, Chapter X, Vol. VI; Tehnicka realizacija projekta VISA-II, II faza, Glava X, Album VI

    Energy Technology Data Exchange (ETDEWEB)

    Pavicevic, M; Nikolic, M [Institute of Nuclear Sciences Boris Kidric, Vinca, Beograd (Serbia and Montenegro)

    1963-01-15

    The second phase of the 'Project VISA-2 described in this chapter of Vol. VI includes the project specifications and technical drawings of the 'measuring system of VISA-2 for testing the VISA-2 channels outside and in the reactor'. In addition to the task objective, description of the measuring system, action plan, description of the work done it contains the definition of the task 'Leak testing' and instructions for the instrumentation personnel on duty. [Serbo-Croat] Druga faza zadatka {sup T}ehnicka realizacija projekta VISA-2' opisana u ovom poglavlju Albuma VI, sadrzi tehnicki opis i crteze 'Mernog sistema VISA-2 i ispitivanje kanala VISA-2 van reaktora i u reaktoru'. Pored definicije zadatka, opisa mernog sistema VISA-2, razrade zadatka, tekstualnog dela projekta i opisa izvedenih radova, ovo poglavlje obuhvata definiciju i razradu podzadatka 'Ispitivanje hermeticnosti' i dodatak sa instrukcijama za dezurne instrumentatore u vezi eksperimenta VISA-2.

  17. Coal/Biomass-to-Liquids Demonstration Testing for DLA Energy: Report on Project Tests, Evaluations, and Recommendations

    Science.gov (United States)

    2015-08-20

    Report January 2010-August 2015 Coal/ Biomass -to-Liquids Demonstration Testing for DLA Energy Report on Project Tests, Evaluations, and...produced commercially from coal and biomass mixtures while meeting the requirements of Section 526, which requires that GHG emissions from...gasification equipment, coals, and biomass used, and reports and analyzes the test results. Additionally, the team worked with DOE NETL to conduct

  18. Ex-vessel debris coolability test during severe accident (COTELS project)

    International Nuclear Information System (INIS)

    Ogasawara, H.

    1998-01-01

    The objectives of the COTELS project are for severe accident management, to investigate phenomena of ex-vessel fuel-coolant interactions after reactor pressure vessel (RPV) failure and to investigate molten core-concrete interaction when coolant is injected onto molten debris. The project has being cooperated with the National Nuclear Center in the Republic of Kazakstan from 1994 to 1997 under the sponsorship of the Ministry of International Trade and Industry of Japan. Total programs are composed with the following tests. (1) Test 01 was meant to observe flow mode of falling debris. (2) Test A was meant to investigate phenomena of fuel-coolant interactions when molten debris falls into a coolant pool. (3) Test B/C investigated fuel coolant interactions and molten core-concrete interaction when coolant is injected onto debris. Detail data evaluation is underway. The following results were thus for obtained: (1) It was confirmed in Test 01 series that about 60 kg of UO 2 mixture was completely melted and fallen as a continuous jet. (2) No energetic fuel-coolant interaction was observed both in Test A and B series. (3) Debris in which decay heat was simulated was cooled by water injection in Test C series

  19. Fabrication and closure development of nuclear waste disposal containers for the Yucca Mountain Project: Status report

    International Nuclear Information System (INIS)

    Domian, H.A.; Robitz, E.S.; Conrardy, C.C.; LaCount, D.F.; McAninch, M.D.; Fish, R.L.; Russell, E.W.

    1991-09-01

    In GFY 89, a project was underway to determine and demonstrate a suitable method for fabricating thin-walled monolithic waste containers for service within the potential repository at Yucca Mountain. A concurrent project was underway to determine and demonstrate a suitable closure process for these containers after they have been filled with high-level nuclear waste. Phase 1 for both the fabrication and closure projects was a screening phase in which candidate processes were selected for further laboratory testing in Phase 2. This report describes the final results of the Phase 1 efforts. It also describes the preliminary results of Phase 2 efforts

  20. New Options for Usability Testing Projects in Business Communication Courses

    Science.gov (United States)

    Jameson, Daphne A.

    2013-01-01

    The increasing availability of recording technologies makes it easier to include usability testing projects in business communication courses. Usability testing is a method of discovering whether people can navigate, read, and understand a print or electronic communication well enough to achieve a particular purpose in a reasonable time frame.…

  1. In-situ thermal testing program strategy

    International Nuclear Information System (INIS)

    1995-06-01

    In the past year the Yucca Mountain Site Characterization Project has implemented a new Program Approach to the licensing process. The Program Approach suggests a step-wise approach to licensing in which the early phases will require less site information than previously planned and necessitate a lesser degree of confidence in the longer-term performance of the repository. Under the Program Approach, the thermal test program is divided into two principal phases: (1) short-term in situ tests (in the 1996 to 2000 time period) and laboratory thermal tests to obtain preclosure information, parameters, and data along with bounding information for postclosure performance; and (2) longer-term in situ tests to obtain additional data regarding postclosure performance. This effort necessitates a rethinking of the testing program because the amount of information needed for the initial licensing phase is less than previously planned. This document proposes a revised and consolidated in situ thermal test program (including supporting laboratory tests) that is structured to meet the needs of the Program Approach. A customer-supplier model is used to define the Project data needs. These data needs, along with other requirements, were then used to define a set of conceptual experiments that will provide the required data within the constraints of the Program Approach schedule. The conceptual thermal tests presented in this document represent a consolidation and update of previously defined tests that should result in a more efficient use of Project resources. This document focuses on defining the requirements and tests needed to satisfy the goal of a successful license application in 2001, should the site be found suitable

  2. Large-scale staged low-far gasification, phase 1c. Continuous tests and dry gas cleaning. Final report; Storskala trinopdelt lavtjaereforgasning, fase 1c. Kontinuerte forsoeg og toer gasrensning. Slutrapport

    Energy Technology Data Exchange (ETDEWEB)

    Dall Bentzen, J.; Hummelshoej, R.M. (COWI A/S (DK)); Henriksen, Ulrik (Danmarks Tekniske Univ., DTU-MEK (DK)); Geest, C. (Babcock and Wilcox Voelund (DK))

    2007-05-15

    On basis of successful process verification at the laboratory plant during the project's Phase 1a, a gas cleaning system has been designed, established and commissioned during this Phase 1c project, with the objective of demonstrating that the gas from the LT-BIG gasifier can be cleaned by means of bag filter, in order for the gas to become suitable for motor operation and possibly other purposes. It has further been a purpose of the project to document continuous operation of the laboratory plant. Thus, 3 tests have been made during the project with a duration of 12 hours, 66 hours and 211 hours, respectively, in total ca. 100 hours' operation. In total, the pilot plant has now been operating for 150-200 hours. During the tests, tar measurements have been made before bag filter, after bag filter and after the activated carbon filter. The gas cleaning system is designed so that a partial current of the gas can be led to a cooler and a bag filter, where the temperature and speed over the filter can be adjusted. Particles are caught in the bag filter, and the vaporous tar materials near the bag filter are caught in a following activated carbon filter. (au)

  3. Evaluation of candidate magnetohydrodynamic materials for the U-02 Phase III test

    International Nuclear Information System (INIS)

    Marchant, D.D.; Bates, J.L.

    1978-06-01

    As part of a cooperative U.S.--U.S.S.R. program, electrode and insulator materials tested at the Westinghouse Electrode Systems Test Facility in Pittsburgh, Pennsylvania, were evaluated. From this evaluation materials will be selected for use in the third phase of tests being conducted in the U-02 magnetohydrodynamics test facility in the Soviet Union. Electrode and insulator materials were examined with both an optical microscope and a scanning electron microscope. The cathodes were found to behave differently from the anodes; most notably, the cathodes showed greater potassium interaction. The lanthanum chromite-based electrodes (excluding those fabricated by plasma-spraying) are recommended for testing in the U-02 Phase III test. Hotpressed, fused-grained MgO and sintered MgAl 2 O 4 are recommended as insulator materials. The electrode attachment techniques used in the Westinghouse Tests were inadequate and need to be modified for the U-02 test

  4. Results from the CDE phase activity on neutron dosimetry for the international fusion materials irradiation facility test cell

    CERN Document Server

    Esposito, B; Maruccia, G; Petrizzi, L; Bignon, G; Blandin, C; Chauffriat, S; Lebrun, A; Recroix, H; Trapp, J P; Kaschuck, Y

    2000-01-01

    The international fusion materials irradiation facility (IFMIF) project deals with the study of an accelerator-based, deuterium-lithium source, producing high energy neutrons at sufficient intensity and irradiation volume to test samples of candidate materials for fusion energy reactors. IFMIF would also provide calibration and validation of data from fission reactor and other accelerator based irradiation tests. This paper describes the activity on neutron/gamma dosimetry (necessary for the characterization of the specimens' irradiation) performed in the frame of the IFMIF conceptual design evaluation (CDE) neutronics tasks. During the previous phase (conceptual design activity (CDA)) the multifoil activation method was proposed for the measurement of the neutron fluence and spectrum and a set of suitable foils was defined. The cross section variances and covariances of this set of foils have now been used for tests on the sensitivity of the IFMIF neutron spectrum determination to cross section uncertainties...

  5. Note: An online testing method for lifetime projection of high power light-emitting diode under accelerated reliability test.

    Science.gov (United States)

    Chen, Qi; Chen, Quan; Luo, Xiaobing

    2014-09-01

    In recent years, due to the fast development of high power light-emitting diode (LED), its lifetime prediction and assessment have become a crucial issue. Although the in situ measurement has been widely used for reliability testing in laser diode community, it has not been applied commonly in LED community. In this paper, an online testing method for LED life projection under accelerated reliability test was proposed and the prototype was built. The optical parametric data were collected. The systematic error and the measuring uncertainty were calculated to be within 0.2% and within 2%, respectively. With this online testing method, experimental data can be acquired continuously and sufficient amount of data can be gathered. Thus, the projection fitting accuracy can be improved (r(2) = 0.954) and testing duration can be shortened.

  6. Sputter-Resistant Materials for Electric Propulsion, Phase II

    Data.gov (United States)

    National Aeronautics and Space Administration — This SBIR Phase 2 project shall develop sputter-resistant materials for use in electric propulsion test facilities and for plume shields on spacecraft using electric...

  7. Criterion for traffic phases in single vehicle data and empirical test of a microscopic three-phase traffic theory

    International Nuclear Information System (INIS)

    Kerner, Boris S; Klenov, Sergey L; Hiller, Andreas

    2006-01-01

    Based on empirical and numerical microscopic analyses, the physical nature of a qualitatively different behaviour of the wide moving jam phase in comparison with the synchronized flow phase-microscopic traffic flow interruption within the wide moving jam phase-is found. A microscopic criterion for distinguishing the synchronized flow and wide moving jam phases in single vehicle data measured at a single freeway location is presented. Based on this criterion, empirical microscopic classification of different local congested traffic states is performed. Simulations made show that the microscopic criterion and macroscopic spatiotemporal objective criteria lead to the same identification of the synchronized flow and wide moving jam phases in congested traffic. Microscopic models in the context of three-phase traffic theory have been tested based on the microscopic criterion for the phases in congested traffic. It is found that microscopic three-phase traffic models can explain both microscopic and macroscopic empirical congested pattern features. It is obtained that microscopic frequency distributions for vehicle speed difference as well as fundamental diagrams and speed correlation functions can depend on the spatial co-ordinate considerably. It turns out that microscopic optimal velocity (OV) functions and time headway distributions are not necessarily qualitatively different, even if local congested traffic states are qualitatively different. The reason for this is that important spatiotemporal features of congested traffic patterns are lost in these as well as in many other macroscopic and microscopic traffic characteristics, which are widely used as the empirical basis for a test of traffic flow models, specifically, cellular automata traffic flow models

  8. Coupling analysis on the soft ground settlement laws in Qinshan nuclear power phase I sea wall project

    International Nuclear Information System (INIS)

    Sun Feng; Pan Rong; Zhu Xiuyun; Zhang Dingli

    2011-01-01

    Qinshan Nuclear Power Phase I sea wall project is a barrier engineering in defending the design basis flooding, which is of importance to the safety of NPP. The geological condition has the feature of high compressibility and low penetration, such as the soft ground of 1 + 450 section of Qinshan Nuclear Power Phase I sea wall. Based on parameters acquired from the site experiment, 3-D finite difference analysis is put forward to study the feature of consolidation settlement laws, which can embody the fluid-solid coupling interaction. The conclusions of numerical analysis agree well with the in-site measured data, and it, can contribute to the design and construction of raising sea wall project. (authors)

  9. Radiation safety study for conventional facility and siting pre project phase of International Linear Collider

    International Nuclear Information System (INIS)

    Sanami, Toshiya; Ban, Syuichi; Sasaki, Shin-ichi

    2015-01-01

    The International Linear Collider (ILC) is a proposed high-energy collider consisting of two linear accelerators, two dumping rings, electron and positron sources, and a single colliding hall with two detectors. The total length and CMS energy of the ILC will be 31 km and 500 GeV, respectively (and 50 km and 1 TeV after future upgrade). The design of the ILC has entered the pre-project phase, which includes site-dependent design. Radiation safety design for the ILC is on-going as a part of conventional facility and siting activities of the pre-project phase. The thickness of a central wall of normal concrete is designed to be 3.5 m under a pessimistic assumption of beam loss. The beam loss scenario is under discussion. Experience and knowledge relating to shielding design and radiation control operational work at other laboratories are required. (authors)

  10. Results from phase 2 of the radioiodine test facility experimental program

    Energy Technology Data Exchange (ETDEWEB)

    Ball, J M; Kupferschmid, W C.H.; Wren, J C [Atomic Energy of Canada Ltd., Pinawa, MB (Canada). Whiteshell Labs.

    1996-12-01

    A series of intermediate-scale experiments were conducted in the Radioiodine Test Facility (RTF) in a vinyl-painted, zinc-primer coated, carbon steel vessel in order to assess the effects of vinyl surfaces on iodine volatility in both the presence and absence of radiation. This test series, Phase 2 of a larger, comprehensive program assessing a variety of containment surfaces, also examined the effects of organic (i.e., methyl ethyl ketone) and inorganic (i.e., hydrazine) additives, pH, and venting on the aqueous chemistry and volatility of solutions initially containing cesium iodide. These tests have clearly demonstrated that organics are released to the aqueous phase from the vinyl coating and that, under radiation conditions, these organics can have a significant effect on the formation of volatile iodine species. In particular, the RTF results suggest that radiolytic decomposition of the released organics results in dramatic reductions in pH and dissolved oxygen concentration, which in turn are responsible for increased formation of molecular iodine and organic iodides. When the pH was maintained at 10 (Test 3), much lower iodine volatility was observed; low iodine volatility was also observed in the absence of radiation. This test series also demonstrated that vinyl surfaces, particularly those in contact with the gas phase, were a sink for iodine. (author) 4 figs., 6 tabs., 17 refs.

  11. Results from phase 2 of the radioiodine test facility experimental program

    International Nuclear Information System (INIS)

    Ball, J.M.; Kupferschmid, W.C.H.; Wren, J.C.

    1996-01-01

    A series of intermediate-scale experiments were conducted in the Radioiodine Test Facility (RTF) in a vinyl-painted, zinc-primer coated, carbon steel vessel in order to assess the effects of vinyl surfaces on iodine volatility in both the presence and absence of radiation. This test series, Phase 2 of a larger, comprehensive program assessing a variety of containment surfaces, also examined the effects of organic (i.e., methyl ethyl ketone) and inorganic (i.e., hydrazine) additives, pH, and venting on the aqueous chemistry and volatility of solutions initially containing cesium iodide. These tests have clearly demonstrated that organics are released to the aqueous phase from the vinyl coating and that, under radiation conditions, these organics can have a significant effect on the formation of volatile iodine species. In particular, the RTF results suggest that radiolytic decomposition of the released organics results in dramatic reductions in pH and dissolved oxygen concentration, which in turn are responsible for increased formation of molecular iodine and organic iodides. When the pH was maintained at 10 (Test 3), much lower iodine volatility was observed; low iodine volatility was also observed in the absence of radiation. This test series also demonstrated that vinyl surfaces, particularly those in contact with the gas phase, were a sink for iodine. (author) 4 figs., 6 tabs., 17 refs

  12. Project assembling and commissioning of a rewetting test facility

    International Nuclear Information System (INIS)

    Rezende, H.C.

    1985-08-01

    A test facility (ITR - Instalacao de Testes de Remolhamento) has been erected at the Thermal-hydraulics Laboratory of CDTN, dedicated to the investigation of the basic phenomena that can occur during the reflood phase of a Loss of Coolant Accident (LOCA) in a Pressurized Water Reactor (PWR), utilizing tubular and annular test sections. The present work consists in a presentation of the facility design and a report of its commissioning. The mechanical aspects of the facility, its power supply system and its instrumentation are described. The results of the instruments calibration and two operational tests are presented and a comparison is done with calculations perfomed usign a computer code. (Author) [pt

  13. Bench-scale testing of on-line control of column flotation using a novel analyzer. Third quarterly technical progress report, April 1, 1993--June 30, 1993

    Energy Technology Data Exchange (ETDEWEB)

    1993-08-24

    This document contains the third quarterly technical progress report for PTI`s Bench-Scale Testing Project of a circuit integrating PTI`s KEN-FLOTETM Column Flotation Technology and PTI`s On-Line Quality Monitor and Control System. The twelve-month project involves installation and testing of a 200--300 lb/hr. bench-scale flotation circuit at PETC`s Coal Preparation Process Research Facility (CPPRF) for two bituminous coals (Upper Freeport and Pittsburgh No. 8 Seam Raw Coals). Figure 1 contains the project plan, as well as the approach to completing the major tasks within the twelve-month project schedule. The project is broken down into three phases, which include: Phase I -- Preparation: The preparation phase was performed principally at PTI`s Calumet offices from October through December, 1992. It involved building of the equipment and circuitry, as well as some preliminary design and equipment testing; Phase II -- ET Circuit Installation and Testing: This installation and testing phase of the project was performed at PETC`s CPPRF from January through June, 1993, and was the major focus of the project. It involved testing of the continuous 200--300 lb/hr. circuit; and Phase III -- Project Finalization: The project finalization phase is occurring from July through September, 1993, at PTI`s Calumet offices and involves finalizing analytical work and data evaluation, as well as final project reporting. This Third Quarterly Technical Progress Report principally summarizes the results from the benchscale testing with the second coal (Pittsburgh No. 8 Seam Coal), which occurred in April through June, 1993. It also contains preliminary economic evaluations that will go into the Final Report, as well as the plan for the final reporting task.

  14. 3D phase-shifting fringe projection system on the basis of a tailored free-form mirror.

    Science.gov (United States)

    Zwick, Susanne; Heist, Stefan; Steinkopf, Ralf; Huber, Sandra; Krause, Sylvio; Bräuer-Burchardt, Christian; Kühmstedt, Peter; Notni, Gunther

    2013-05-10

    Phase-shifting fringe projection is an effective method to perform 3D shape measurements. Conventionally, fringe projection systems utilize a digital projector that images fringes into the measurement plane. The performance of such systems is limited to the visible spectral range, as most projectors experience technical limitations in UV or IR spectral ranges. However, for certain applications these spectral ranges are of special interest. We present a wideband fringe projector that has been developed on the basis of a picture generating beamshaping mirror. This mirror generates a sinusoidal fringe pattern in the measurement plane without any additional optical elements. Phase shifting is realized without any mechanical movement by a multichip LED. As the system is based on a single mirror, it is wavelength-independent in a wide spectral range and therefore applicable in UV and IR spectral ranges. We present the design and a realized setup of this fringe projection system and the characterization of the generated intensity distribution. Experimental results of 3D shape measurements are presented.

  15. Official emblem of the Apollo Soyuz Test Project

    Science.gov (United States)

    1974-01-01

    This is the Official emblem of the Apollo Soyuz Test Project (ASTP) chosen by NASA and the Soviet Academy of Sciences. Of circular design, the emblem has the words Apollo in English and Soyuz in Russian around a center disc which depicts the two spacecraft docked together in Earth orbit. The Russian word 'soyuz' means 'union' in English.

  16. Hanstholm phase 2B. Offshore wave energy test 1994 - 1996

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-11-01

    The wave power converter consists of a float 2.5 meter in diameter, connected by a rope to a seabed-mounted piston pump, installed on 25 meter deep water 2,5 km offshore Hanstholm, Denmark. The converter is designed to absorb an average maximum power of 1 kW. Measured data in real sea conditions are compared to results based on computer simulations and previous tank testing. Losses caused by rope elasticity and hysteresis, friction in the pump and back flow through the valves are assessed. The economic perspectives of a large wave power plant are presented, based on a revised prototype incorporating the results and experience gained during the test period. The wave energy conversion test `Hanstholm phase 2B` has showed, that it it technically possible to exploit the offshore wave energy resource. This source of energy could become attractive for commercial enterprise. The wave power converter demonstrated a reliable performance over a period of nine months. It produced energy under all wave conditions and survived storm waves of 9,6 m. A 300 MW wave power plant in the Danish part of the North sea is estimated to produce electricity at a cost between 2,1 - 2,4 DKK/kWh. The electrical transmission to shore contribute to approximately 20% of the cost. New data predict a potential of 23 kW per meter wave front. The energy plan Energy 21 proposed by the Danish Department of Energy, includes a scenario incorporating wave energy in the energy system year 2030. A strategy for the development of wave energy, has been proposed as part of the project OWEC-1 supported by the European Joule R and D programme. A proposal for future Danish initiatives to develop second generation point absorber systems is outlined. (ARW) 29 refs.

  17. The Cosmetics Europe strategy for animal-free genotoxicity testing: project status up-date.

    Science.gov (United States)

    Pfuhler, S; Fautz, R; Ouedraogo, G; Latil, A; Kenny, J; Moore, C; Diembeck, W; Hewitt, N J; Reisinger, K; Barroso, J

    2014-02-01

    The Cosmetics Europe (formerly COLIPA) Genotoxicity Task Force has driven and funded three projects to help address the high rate of misleading positives in in vitro genotoxicity tests: The completed "False Positives" project optimized current mammalian cell assays and showed that the predictive capacity of the in vitro micronucleus assay was improved dramatically by selecting more relevant cells and more sensitive toxicity measures. The on-going "3D skin model" project has been developed and is now validating the use of human reconstructed skin (RS) models in combination with the micronucleus (MN) and Comet assays. These models better reflect the in use conditions of dermally applied products, such as cosmetics. Both assays have demonstrated good inter- and intra-laboratory reproducibility and are entering validation stages. The completed "Metabolism" project investigated enzyme capacities of human skin and RS models. The RS models were shown to have comparable metabolic capacity to native human skin, confirming their usefulness for testing of compounds with dermal exposure. The program has already helped to improve the initial test battery predictivity and the RS projects have provided sound support for their use as a follow-up test in the assessment of the genotoxic hazard of cosmetic ingredients in the absence of in vivo data. Copyright © 2013 Elsevier Ltd. All rights reserved.

  18. Phase extraction based on iterative algorithm using five-frame crossed fringes in phase measuring deflectometry

    Science.gov (United States)

    Jin, Chengying; Li, Dahai; Kewei, E.; Li, Mengyang; Chen, Pengyu; Wang, Ruiyang; Xiong, Zhao

    2018-06-01

    In phase measuring deflectometry, two orthogonal sinusoidal fringe patterns are separately projected on the test surface and the distorted fringes reflected by the surface are recorded, each with a sequential phase shift. Then the two components of the local surface gradients are obtained by triangulation. It usually involves some complicated and time-consuming procedures (fringe projection in the orthogonal directions). In addition, the digital light devices (e.g. LCD screen and CCD camera) are not error free. There are quantization errors for each pixel of both LCD and CCD. Therefore, to avoid the complex process and improve the reliability of the phase distribution, a phase extraction algorithm with five-frame crossed fringes is presented in this paper. It is based on a least-squares iterative process. Using the proposed algorithm, phase distributions and phase shift amounts in two orthogonal directions can be simultaneously and successfully determined through an iterative procedure. Both a numerical simulation and a preliminary experiment are conducted to verify the validity and performance of this algorithm. Experimental results obtained by our method are shown, and comparisons between our experimental results and those obtained by the traditional 16-step phase-shifting algorithm and between our experimental results and those measured by the Fizeau interferometer are made.

  19. Magnetic sensor for nondestructive evaluation of deteriorated prestressing strand : phase II.

    Science.gov (United States)

    2011-08-01

    This report gives an account of the execution and achievements in Phase II of the project completed through August 2011. The main objective of this project is to advance the practical development of a nondestructive testing and evaluation method usin...

  20. Random projections and the optimization of an algorithm for phase retrieval

    International Nuclear Information System (INIS)

    Elser, Veit

    2003-01-01

    Iterative phase retrieval algorithms typically employ projections onto constraint subspaces to recover the unknown phases in the Fourier transform of an image, or, in the case of x-ray crystallography, the electron density of a molecule. For a general class of algorithms, where the basic iteration is specified by the difference map, solutions are associated with fixed points of the map, the attractive character of which determines the effectiveness of the algorithm. The behaviour of the difference map near fixed points is controlled by the relative orientation of the tangent spaces of the two constraint subspaces employed by the map. Since the dimensionalities involved are always large in practical applications, it is appropriate to use random matrix theory ideas to analyse the average-case convergence at fixed points. Optimal values of the γ parameters of the difference map are found which differ somewhat from the values previously obtained on the assumption of orthogonal tangent spaces

  1. Preliminary observations of gate valve flow interruption tests, Phase 2

    International Nuclear Information System (INIS)

    Steele, R. Jr.; DeWall, K.G.

    1990-01-01

    This paper presents preliminary observations from the US Nuclear Regulatory Commission/Idaho National Engineering Laboratory Flexible Wedge Gate Valve Qualification and Flow Interruption Test Program, Phase 2. The program investigated the ability of selected boiling water reactor (BWR) process line valves to perform their containment isolation function at high energy pipe break conditions and other more normal flow conditions. The fluid and valve operating responses were measured to provide information concerning valve and operator performance at various valve loadings so that the information could be used to assess typical nuclear industry motor operator sizing equations. Six valves were tested, three 6-in. isolation valves representative of those used in reactor water cleanup systems in BWRs and three 10-in. isolation valves representative of those used in BWR high pressure coolant injection (HPCI) steam lines. The concern with these normally open isolation valves is whether they will close in the event of a downstream pipe break outside of containment. The results of this testing will provide part of the technical insights for NRC efforts regarding Generic Issue 87 (GI-87), Failure of the HPCI Steam Line Without Isolation, which includes concerns about the uncertainties in gate valve motor operator sizing and torque switch settings for these BWR containment isolation valves. As of this writing, the Phase 2 test program has just been completed. Preliminary observations made in the field confirmed most of the results from the Phase 1 test program. All six valves closing in high energy water, high energy steam, and high pressure cold water require more force to close than would be calculated using the typical variables in the standard industry motor operator sizing equations

  2. CEC project Mirage - second phase on migration of radionuclides in the geosphere. Third (and final) summary progress report (work period 1989)

    International Nuclear Information System (INIS)

    Come, B.

    1990-01-01

    A second phase of the Community coordinated project Mirage (migration of radionuclides in the geosphere) was launched in 1986. The present report brings together reviews of work done in the four research areas of this phase for 1989, and therefore constitutes an update of the previous reports, ref. EUR 11589 and 12229. This project is part of the CEC R and D programme on radioactive waste management (1985-89)

  3. Ultrasonic testing with the phased array method at the pipe connection inner edges in pipings

    International Nuclear Information System (INIS)

    Brekow, G.; Wuestenberg, H.; Hesselmann, H.; Rathgeb, W.

    1991-01-01

    Ultrasonic testing with the phased array method at the pipe connection inner edges in pipings. The pipe connection inner corner tests in feedwater lines to the main coolant pipe were carried out by Preussen-Elektra in cooperation with Siemens KWU and the BAM with the ultrasonic phased array method. The testing plan was developed by means of a computed model. For a trial of the testing plan, numerous ultrasonic measurements with the phased array method were carried out using a pipe test piece with TH-type inner edges, which was a 1:1 model of the reactor component to be tested. The data measured at several test notches in the pipe connection inner edge area covered by a plating of 6 mm were analyzed. (orig./MM) [de

  4. Design for unusual environment (space). Complementary use of modelling and testing phases

    International Nuclear Information System (INIS)

    Cambiaghi, Danilo; Cambiaghi, Andrea

    2004-01-01

    Designing for space requires a great imagination effort from the designer. He must perceive that the stresses experimented by the facilities he is designing will be quite different in space (during the mission), in launch phase and on ground (before launch handling phase), and he must design for all such environmental conditions. Furthermore he must design for mechanical and thermal environment, which often lead to conflicting needs. Virtual models may help very much in balancing the conflicting requirements, but models must be validated to be reliable. Test phase help validating the models, but may overstress the items. The aim of the designer is to reach an efficient and safe design through a balanced use of creativity, modelling and testing

  5. Project W-314 performance mock-up test procedure

    International Nuclear Information System (INIS)

    CARRATT, R.T.

    1999-01-01

    The purpose of this Procedure is to assist construction in the pre-operational fabrication and testing of the pit leak detection system and the low point drain assembly by: (1) Control system testing of the pit leak detection system will be accomplished by actuating control switches and verifying that the control signal is initiated, liquid testing and overall operational requirements stated in HNF-SD-W314-PDS-003, ''Project Development Specification for Pit Leak Detection''. (2) Testing of the low point floor drain assembly by opening and closing the drain to and from the ''retracted'' and ''sealed'' positions. Successful operation of this drain will be to verify that the seal does not leak on the ''sealed'' position, the assembly holds liquid until the leak detector actuates and the assembly will operate from on top of the mock-up cover block

  6. Scientists help the children of Chernobyl. The GAST/VDEW project. Report on phase II: 1. April 1996 - 31. March 1998

    International Nuclear Information System (INIS)

    Reiners, Ch.; Biko, J.; Streffer, C.

    2000-05-01

    In this project phase II, from 1. April 1996 until 31. March 1998, the activities under the four partial projects entitled 'Therapy and training', 'Biological dosimetry', 'Dosimetry and risk assessment', and 'Coordination and examination authority at Minsk' have been continued and concluded, except for the partial project 'Therapy and training'. (orig./CB) [de

  7. The ALPHA project: A progress report

    International Nuclear Information System (INIS)

    Yadigaroglu, G.

    1995-01-01

    A review of the ALPHA project is presented, including a summary of progress and current status. The project comprises the experimental and analytical investigation of the long-term decay heat removal phenomena from the containment of the next generation of passive Advanced Light Water Reactors. In its present phase, the project is directed to the investigation of the Simplified Boiling Water Reactor (SBWR) Passive Containment Cooling system. The project includes separate-effects tests of containment phenomena (the LINX program). The effects of aerosols that may result from hypothetical severe accidents are also considered (the AIDA program). The construction and commissioning of the major ALPHA experimental facilities, PANDA, LINX-2 and AIDA is complete and the first series of tests are underway. Scaling studies have guided their design. Several small-scale experiments and studies have already produced valuable results

  8. Durability of lightweight concrete : Phase II : wetting and drying tests, Phase III : freezing and thawing tests.

    Science.gov (United States)

    1966-12-01

    This report describes a laboratory research program on the durability of lightweight concrete. Two phases of a three phase study are covered by this report, while the remaining phase is still under study. The two phases being reported are Phase II - ...

  9. Automated Test Case Generation from Highly Reliable System Requirements Models, Phase I

    Data.gov (United States)

    National Aeronautics and Space Administration — Software testing is a complex and expensive phase of the software development cycle. Effective software testing is especially important in mission-critical software,...

  10. Project W-314 specific test and evaluation plan for 241-AN-A valve pit

    International Nuclear Information System (INIS)

    Hays, W.H.

    1998-01-01

    The purpose of this Specific Test and Evaluation Plan (STEP) is to provide a detailed written plan for the systematic testing of modifications made to the 241-AN-A Valve Pit by the W-314 Project. The STEP develops the outline for test procedures that verify the system's performance to the established Project design criteria. The STEP is a lower tier document based on the W-314 Test and Evaluation Plan (TEP)

  11. Test Plan: Sludge Treatment Project Corrosion Process Chemistry Follow-on Testing

    Energy Technology Data Exchange (ETDEWEB)

    Delegard, Calvin H.; Schmidt, Andrew J.; Poloski, Adam P.

    2007-08-17

    This test plan was prepared by the Pacific Northwest National Laboratory (PNNL) under contract with Fluor Hanford (FH). The test plan describes the scope and conditions to be used to perform laboratory-scale testing of the Sludge Treatment Project (STP) hydrothermal treatment of K Basin sludge. The STP, managed for the U. S. Department of Energy (DOE) by FH, was created to design and operate a process to eliminate uranium metal from the sludge prior to packaging for Waste Isolation Pilot Plant (WIPP) by using high temperature liquid water to accelerate the reaction, produce uranium dioxide from the uranium metal, and safely discharge the hydrogen. The proposed testing builds on the approach and laboratory test findings for both K Basin sludge and simulated sludge garnered during prior testing from September 2006 to March 2007. The outlined testing in this plan is designed to yield further understanding of the nature of the chemical reactions, the effects of compositional and process variations and the effectiveness of various strategies to mitigate the observed high shear strength phenomenon observed during the prior testing. These tests are designed to provide process validation and refinement vs. process development and design input. The expected outcome is to establish a level of understanding of the chemistry such that successful operating strategies and parameters can be implemented within the confines of the existing STP corrosion vessel design. In July 2007, the DOE provided direction to FH regarding significant changes to the scope of the overall STP. As a result of the changes, FH directed PNNL to stop work on most of the planned activities covered in this test plan. Therefore, it is unlikely the testing described here will be performed. However, to preserve the test strategy and details developed to date, the test plan has been published.

  12. X-rays of inner worlds: the mid-twentieth-century American projective test movement.

    Science.gov (United States)

    Lemov, Rebecca

    2011-01-01

    This essay begins to tell the neglected history of the projective test movement in the U.S. behavioral sciences from approximately 1941 to 1968. This cross-disciplinary enterprise attempted to use projective techniques as "X-ray" machines to see into the psyches of subjects tested around the world. The aim was to gather subjective materials en masse, pursuing data on a scope, scale, and manner rarely hazarded before in any science. In particular, the targeted data included the traces of the inner life and elusive aspects of subjective experience including dreams, life stories, and myriad test results from a battery of tests. This essay explores how the movement and the experimental data bank that resulted were unlikely yet telling sites for the practice and pursuit of the Cold War human sciences. To look closely at the encounters that resulted is to show how the most out-of-the-way places and seemingly insignificant moments played a role in heady scientific ambitions and global geopolitical projects. At times, the projective test movement became a mirror of Cold War rationality itself, as tests were employed at the very limits of their possible extension. The essay argues for an off-kilter centrality in the movement itself, shedding light on the would-be unified social sciences after World War II and the "subjective turn" they took. © 2011 Wiley Periodicals, Inc.

  13. Managing project complexity : A study into adapting early project phases to improve project performance in large engineering projects

    NARCIS (Netherlands)

    Bosch-Rekveldt, M.G.C.

    2011-01-01

    Engineering projects become increasingly more complex and project complexity is assumed to be one of the causes for projects being delivered late and over budget. However, what this project complexity actually comprised of was unclear. To improve the overall project performance, this study focuses

  14. Virtual Mockup test based on computational science and engineering. Near future technology projected by JSPS-RFTFADVENTURE project

    International Nuclear Information System (INIS)

    Yoshimura, Shinobu

    2001-01-01

    The ADVENTURE project began on August, 1997, as a project in the computational science' field of JSPS-RFTFADVENTURE project, and is progressed as five year project. In this project, by using versatile parallel computer environment such as PC cluster, super parallel computer, and so on , to solve an arbitrary shape of actual dynamical equation by using 10 to 100 million freedom class mode under maintaining a general use analytical capacity agreeable with present general use computational mechanics system, further development of a large-scale parallel computational mechanics system (ADVENTURE system) capable of carrying out an optimization design on shapes, physical properties, loading conditions, and so on is performed. Here was scoped, after outlining on background of R and D on ADVENTURE system and its features, on near future virtual mockup test forecast from it. (G.K.)

  15. CARA project

    International Nuclear Information System (INIS)

    Bergallo, Juan E.; Brasnarof, Daniel O.

    2000-01-01

    The CARA (Advanced Fuels for Argentine Reactors) Project successfully completed its first stage, phase one, last year. The performance of this fuel has been partially examined, using CNEA and CONUAR facilities and personnel. With the results obtained in this stage, determined by the corresponding tests and verification of the fuel behavior, the performance of the second stage started immediately afterwards. Works performed and results obtained during the development of the second stage are generally described in this paper. (author)

  16. CERTS Microgrid Laboratory Test Bed - PIER Final Project Report

    Energy Technology Data Exchange (ETDEWEB)

    Eto, Joseph H.; Eto, Joseph H.; Lasseter, Robert; Schenkman, Ben; Klapp, Dave; Linton, Ed; Hurtado, Hector; Roy, Jean; Lewis, Nancy Jo; Stevens, John; Volkommer, Harry

    2008-07-25

    The objective of the CERTS Microgrid Laboratory Test Bed project was to enhance the ease of integrating small energy sources into a microgrid. The project accomplished this objective by developing and demonstrating three advanced techniques, collectively referred to as the CERTS Microgrid concept, that significantly reduce the level of custom field engineering needed to operate microgrids consisting of small generating sources. The techniques comprising the CERTS Microgrid concept are: 1) a method for effecting automatic and seamless transitions between grid-connected and islanded modes of operation; 2) an approach to electrical protection within the microgrid that does not depend on high fault currents; and 3) a method for microgrid control that achieves voltage and frequency stability under islanded conditions without requiring high-speed communications. The techniques were demonstrated at a full-scale test bed built near Columbus, Ohio and operated by American Electric Power. The testing fully confirmed earlier research that had been conducted initially through analytical simulations, then through laboratory emulations, and finally through factory acceptance testing of individual microgrid components. The islanding and resychronization method met all Institute of Electrical and Electronics Engineers 1547 and power quality requirements. The electrical protections system was able to distinguish between normal and faulted operation. The controls were found to be robust and under all conditions, including difficult motor starts. The results from these test are expected to lead to additional testing of enhancements to the basic techniques at the test bed to improve the business case for microgrid technologies, as well to field demonstrations involving microgrids that involve one or mroe of the CERTS Microgrid concepts.

  17. Numerical-experimental investigation of load paths in DP800 dual phase steel during Nakajima test

    Science.gov (United States)

    Bergs, Thomas; Nick, Matthias; Feuerhack, Andreas; Trauth, Daniel; Klocke, Fritz

    2018-05-01

    Fuel efficiency requirements demand lightweight construction of vehicle body parts. The usage of advanced high strength steels permits a reduction of sheet thickness while still maintaining the overall strength required for crash safety. However, damage, internal defects (voids, inclusions, micro fractures), microstructural defects (varying grain size distribution, precipitates on grain boundaries, anisotropy) and surface defects (micro fractures, grooves) act as a concentration point for stress and consequently as an initiation point for failure both during deep drawing and in service. Considering damage evolution in the design of car body deep drawing processes allows for a further reduction in material usage and therefore body weight. Preliminary research has shown that a modification of load paths in forming processes can help mitigate the effects of damage on the material. This paper investigates the load paths in Nakajima tests of a DP800 dual phase steel to research damage in deep drawing processes. Investigation is done via a finite element model using experimentally validated material data for a DP800 dual phase steel. Numerical simulation allows for the investigation of load paths with respect to stress states, strain rates and temperature evolution, which cannot be easily observed in physical experiments. Stress triaxiality and the Lode parameter are used to describe the stress states. Their evolution during the Nakajima tests serves as an indicator for damage evolution. The large variety of sheet metal forming specific load paths in Nakajima tests allows a comprehensive evaluation of damage for deep drawing. The results of the numerical simulation conducted in this project and further physical experiments will later be used to calibrate a damage model for simulation of deep drawing processes.

  18. QUEST/Ada (Query Utility Environment for Software Testing of Ada): The development of a prgram analysis environment for Ada, task 1, phase 2

    Science.gov (United States)

    Brown, David B.

    1990-01-01

    The results of research and development efforts are described for Task one, Phase two of a general project entitled The Development of a Program Analysis Environment for Ada. The scope of this task includes the design and development of a prototype system for testing Ada software modules at the unit level. The system is called Query Utility Environment for Software Testing of Ada (QUEST/Ada). The prototype for condition coverage provides a platform that implements expert system interaction with program testing. The expert system can modify data in the instrument source code in order to achieve coverage goals. Given this initial prototype, it is possible to evaluate the rule base in order to develop improved rules for test case generation. The goals of Phase two are the following: (1) to continue to develop and improve the current user interface to support the other goals of this research effort (i.e., those related to improved testing efficiency and increased code reliable); (2) to develop and empirically evaluate a succession of alternative rule bases for the test case generator such that the expert system achieves coverage in a more efficient manner; and (3) to extend the concepts of the current test environment to address the issues of Ada concurrency.

  19. The role of technology in reducing health care costs. Phase II and phase III.

    Energy Technology Data Exchange (ETDEWEB)

    Cilke, John F.; Parks, Raymond C.; Funkhouser, Donald Ray; Tebo, Michael A.; Murphy, Martin D.; Hightower, Marion Michael; Gallagher, Linda K.; Craft, Richard Layne, II; Garcia, Rudy John

    2004-04-01

    In Phase I of this project, reported in SAND97-1922, Sandia National Laboratories applied a systems approach to identifying innovative biomedical technologies with the potential to reduce U.S. health care delivery costs while maintaining care quality. The effort provided roadmaps for the development and integration of technology to meet perceived care delivery requirements and an economic analysis model for development of care pathway costs for two conditions: coronary artery disease (CAD) and benign prostatic hypertrophy (BPH). Phases II and III of this project, which are presented in this report, were directed at detailing the parameters of telemedicine that influence care delivery costs and quality. These results were used to identify and field test the communication, interoperability, and security capabilities needed for cost-effective, secure, and reliable health care via telemedicine.

  20. Healy Clean Coal Project: Healy coal firing at TRW Cleveland Test Facility. Final report

    Energy Technology Data Exchange (ETDEWEB)

    Koyama, T.; Petrill, E.; Sheppard, D.

    1991-08-01

    A test burn of two Alaskan coals was conducted at TRW`s Cleveland test facility in support of the Healy Clean Coal Project, as part of Clean Coal Technology III Program in which a new power plant will be constructed using a TRW Coal Combustion System. This system features ash slagging technology combined with NO{sub x} and SO{sub x} control. The tests, funded by the Alaska Industrial Development and Export Authority (AIDEA) and TRW, were conducted to verify that the candidate Healy station coals could be successfully fired in the TRW coal combustor, to provide data required for scale-up to the utility project size requirements, and to produce sufficient flash-calcined material (FCM) for spray dryer tests to be conducted by Joy/NIRO. The tests demonstrated that both coals are viable candidates for the project, provided the data required for scale-up, and produced the FCM material. This report describes the modifications to the test facility which were required for the test burn, the tests run, and the results of the tests.

  1. Environmental assessment report: Nuclear Test Technology Complex. [Construction and operation of proposed facility

    Energy Technology Data Exchange (ETDEWEB)

    Tonnessen, K.; Tewes, H.A.

    1982-08-01

    The US Department of Energy (USDOE) is planning to construct and operate a structure, designated the Nuclear Test Technology Complex (NTTC), on a site located west of and adjacent to the Lawrence Livermore National Laboratory. The NTTC is designed to house 350 nuclear test program personnel, and will accommodate the needs of the entire staff of the continuing Nuclear Test Program (NTP). The project has three phases: land acquisition, facility construction and facility operation. The purpose of this environmental assessment report is to describe the activities associated with the three phases of the NTTC project and to evaluate potential environmental disruptions. The project site is located in a rural area of southeastern Alameda County, California, where the primary land use is agriculture; however, the County has zoned the area for industrial development. The environmental impacts of the project include surface disturbance, high noise levels, possible increases in site erosion, and decreased air quality. These impacts will occur primarily during the construction phase of the NTTC project and can be mitigated in part by measures proposed in this report.

  2. Quality assurance plan for the Molten Salt Reactor Experiment Remediation Project at the Oak Ridge National Laboratory. Phase 1 -- Interim corrective measures and Phase 2 -- Purge and trap reactive gases

    International Nuclear Information System (INIS)

    1995-11-01

    This Quality Assurance Plan (QAP) identifies and describes the systems utilized by the Molten Salt Reactor Experiment Remediation Project (MSRERP) personnel to implement the requirements and associated applicable guidance contained in the Quality Program Description Y/QD-15 Rev. 2 (Energy Systems 1995f). This QAP defines the quality assurance (QA) requirements applicable to all activities and operations in and directly pertinent to the MSRERP Phase 1--Interim Corrective Measures and Phase 2--Purge and Trap objectives. This QAP will be reviewed, revised, and approved as necessary for Phase 3 and Phase 4 activities. This QAP identifies and describes the QA activities and procedures implemented by the various Oak Ridge National Laboratory support organizations and personnel to provide confidence that these activities meet the requirements of this project. Specific support organization (Division) quality requirements, including the degree of implementation of each, are contained in the appendixes of this plan

  3. Project W-314 specific test and evaluation plan for AZ tank farm upgrades

    International Nuclear Information System (INIS)

    Hays, W.H.

    1998-01-01

    The purpose of this Specific Test and Evaluation Plan (STEP) is to provide a detailed written plan for the systematic testing of modifications made by the addition of the SN-631 transfer line from the AZ-O1A pit to the AZ-02A pit by the W-314 Project. The STEP develops the outline for test procedures that verify the system's performance to the established Project design criteria. The STEP is a lower tier document based on the W-314 Test and Evaluation P1 an (TEP). Testing includes Validations and Verifications (e.g., Commercial Grade Item Dedication activities, etc), Factory Tests and Inspections (FTIs), installation tests and inspections, Construction Tests and Inspections (CTIs), Acceptance Test Procedures (ATPs), Pre-Operational Test Procedures (POTPs), and Operational Test Procedures (OTPs). The STEP will be utilized in conjunction with the TEP for verification and validation

  4. Heliostat Manufacturing for near-term markets. Phase II final report

    International Nuclear Information System (INIS)

    1998-01-01

    This report describes a project by Science Applications International Corporation and its subcontractors Boeing/Rocketdyne and Bechtel Corp. to develop manufacturing technology for production of SAIC stretched membrane heliostats. The project consists of three phases, of which two are complete. This first phase had as its goals to identify and complete a detailed evaluation of manufacturing technology, process changes, and design enhancements to be pursued for near-term heliostat markets. In the second phase, the design of the SAIC stretched membrane heliostat was refined, manufacturing tooling for mirror facet and structural component fabrication was implemented, and four proof-of-concept/test heliostats were produced and installed in three locations. The proposed plan for Phase III calls for improvements in production tooling to enhance product quality and prepare increased production capacity. This project is part of the U.S. Department of Energy's Solar Manufacturing Technology Program (SolMaT)

  5. Development and applications of a computer-aided phased array assembly for ultrasonic testing

    International Nuclear Information System (INIS)

    Schenk, G.; Montag, H.J.; Wuestenberg, H.; Erhard, A.

    1985-01-01

    The use of modern electronic equipment for programmable signal delay increasingly allows transit-time controlled phased arrays to be applied in non-destructive, ultrasonic materials testing. A phased-array assembly is described permitting fast variation of incident angle of acoustic wave and of sonic beam focus, together with numerical evaluation of measured data. Phased arrays can be optimized by adding programmable electronic equipment so that the quality of conventional designs can be achieved. Applications of the new technical improvement are explained, referring to stress corrosion cracking, turbine testing, echo tomography of welded joints. (orig./HP) [de

  6. Advanced conceptual design report solid waste retrieval facility, phase I, project W-113

    International Nuclear Information System (INIS)

    Smith, K.E.

    1994-01-01

    Project W-113 will provide the equipment and facilities necessary to retrieve suspect transuranic (TRU) waste from Trench 04 of the 218W-4C burial ground. As part of the retrieval process, waste drums will be assayed, overpacked, vented, head-gas sampled, and x-rayed prior to shipment to the Phase V storage facility in preparation for receipt at the Waste Receiving and Processing Facility (WRAP). Advanced Conceptual Design (ACD) studies focused on project items warranting further definition prior to Title I design and areas where the potential for cost savings existed. This ACD Report documents the studies performed during FY93 to optimize the equipment and facilities provided in relation to other SWOC facilities and to provide additional design information for Definitive Design

  7. Apollo-Soyuz test project: Composite of MSFC final science report

    Science.gov (United States)

    1977-01-01

    Experimental procedures of nine experiments conducted during the Apollo-Soyuz Test Project mission from July 15th to July 24th, 1975 are presented. Conclusions and recommendations based on these experiments are given.

  8. State of Art Report for the OECD-NEA Loss-of-Forced Cooling (LOFC) Test Project using HTTR Reactor

    International Nuclear Information System (INIS)

    Jun, Ji Su

    2011-05-01

    The OECD/NEA Project is planned to perform the LOFC (Loss Of Forced Cooling) test using the HTTR (High Temperature engineering Test Reactor) in Japan from 31 March 2011 to 31 March 2013 in order to obtain the data for the code validation of the VHTR safety analysis. Based on the Project Agreement Document, this report gives a description of the HTTR-LOFC test, HTTR test facility, project schedule and deliverable items as the technical state art of the project, and appends the full translation of the project agreement articles on the project management

  9. Unmanned Aircraft Systems (UAS) Integration in the National Airspace System (NAS) Project: KDP-A for Phase 2 Minimum Operational Performance Standards

    Science.gov (United States)

    Grindle, Laurie; Hackenberg, Davis L.

    2016-01-01

    UAS Integration in the NAS Project has: a) Developed Technical Challenges that are crucial to UAS integration, aligned with NASA's Strategic Plan and Thrusts, and support FAA standards development. b) Demonstrated rigorous project management processes through the execution of previous phases. c) Defined Partnership Plans. d) Established path to KDP-C. Request approval of Technical Challenges, execution of partnerships and plans, and execution of near-term FY17 activities. There is an increasing need to fly UAS in the NAS to perform missions of vital importance to National Security and Defense, Emergency Management, and Science. There is also an emerging need to enable commercial applications such as cargo transport (e.g. FedEx). Unencumbered NAS Access for Civil/Commercial UAS. Provide research findings, utilizing simulation and flight tests, to support the development and validation of DAA and C2 technologies necessary for integrating Unmanned Aircraft Systems into the National Airspace System.

  10. Acid Pit Stabilization Project (Volume 1 - Cold Testing) and (Volume 2 - Hot Testing)

    International Nuclear Information System (INIS)

    Loomis, G. G.; Zdinak, A. P.; Ewanic, M. A.; Jessmore, J. J.

    1998-01-01

    During the summer and fall of Fiscal Year 1997, a Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) Treatability Study was performed at the Idaho National Engineering and Environmental Laboratory. The study involved subsurface stabilization of a mixed waste contaminated soil site called the Acid Pit. This study represents the culmination of a successful technology development effort that spanned Fiscal Years 1994-1996. Research and development of the in situ grout stabilization technique was conducted. Hardware and implementation techniques are currently documented in a patent pending with the United States Patent and Trademark Office. The stabilization technique involved using jet grouting of an innovative grouting material to form a monolith out of the contamination zone. The monolith simultaneously provides a barrier to further contaminant migration and closes voids in the soil structure against further subsidence. This is accomplished by chemical incorporation of contaminants into less soluble species and achieving a general reduction in hydraulic conductivity within the monolith. The grout used for this study was TECT-HG, a relatively dense iron oxide-based cementitious grout. The treatability study involved cold testing followed by in situ stabilization of the Acid Pit. Volume 1 of this report discusses cold testing, performed as part of a ''Management Readiness Assessment'' in preparation for going hot. Volume 2 discusses the results of the hot Acid Pit Stabilization phase of this project. Drilling equipment was specifically rigged to reduce the spread of contamination, and all grouting was performed under a concrete block containing void space to absorb any grout returns. Data evaluation included examination of implementability of the grouting process and an evaluation of the contaminant spread during grouting. Following curing of the stabilized pit, cores were obtained and evaluated for toxicity characteristic leach ing

  11. A framework for testing the ability of models to project climate change and its impacts

    DEFF Research Database (Denmark)

    Refsgaard, J. C.; Madsen, H.; Andréassian, V.

    2014-01-01

    Models used for climate change impact projections are typically not tested for simulation beyond current climate conditions. Since we have no data truly reflecting future conditions, a key challenge in this respect is to rigorously test models using proxies of future conditions. This paper presents...... a validation framework and guiding principles applicable across earth science disciplines for testing the capability of models to project future climate change and its impacts. Model test schemes comprising split-sample tests, differential split-sample tests and proxy site tests are discussed in relation...... to their application for projections by use of single models, ensemble modelling and space-time-substitution and in relation to use of different data from historical time series, paleo data and controlled experiments. We recommend that differential-split sample tests should be performed with best available proxy data...

  12. Project W-314 specific test and evaluation plan for 241-AY-02A pump pit upgrade

    International Nuclear Information System (INIS)

    Hays, W.H.

    1998-01-01

    This Specific Test and Evaluation Plan (STEP) defines the test and evaluation activities encompassing the upgrade of the 241-AY-02A Pump Pit for the W-314 Project. The purpose of this Specific Test and Evaluation Plan (STEP) is to provide a detailed written plan for the systematic testing of modifications made to the 241-AY-02A Pump Pit by the W-314 Project. The STEP develops the outline for test procedures that verify the system's performance to the established Project design criteria. The STEP is a lower tier document based on the W-314 Test and Evaluation Plan (TEP)

  13. Project W-314 specific test and evaluation plan for 241-AY-01A pump pit upgrade

    International Nuclear Information System (INIS)

    Hays, W.H.

    1998-01-01

    This Specific Test and Evaluation Plan (STEP) defines the test and evaluation activities encompassing the upgrade of the 241-AY-0IA Pump Pit for the W-314 Project. The purpose of this Specific Test and Evaluation Plan (STEP) is to provide a detailed written plan for the systematic testing of modifications made to the 241-AY-01A Pump Pit by the W-314 Project. The STEP develops the outline for test procedures that verify the system's performance to the established Project design criteria. The STEP is a lower tier document based on the W-314 Test and Evaluation Plan (TEP)

  14. Phase III (full scale) agitated mixing test plan

    International Nuclear Information System (INIS)

    Ruff, D.T.

    1994-01-01

    Waste Receiving and Processing Facility Module 2A (WRAP 2A) is the proposed second module of the WRAP facility. This facility will provide the required treatment for contact Handled (CH) Low Level (LL) Mixed Waste (MW) to allow its permanent disposal. Solidification of a portion of this waste using a cement based grout has been selected in order to reduce the toxicity and mobility of the waste in the disposal site. Mixing of the waste with the cement paste and material handling constraints/requirements associated with the mixed material is, therefore, a key process in the overall treatment strategy. This test plan addresses Phase 3, Full Scale Testing. The objectives of these tests are to determine if there are scale-up issues associated with the mixing results obtained in Phase 1 and 2 mixing tests, verify the workability of mixtures resulting from previous formulation development efforts (Waste Immobilization Development [WID]), and provide a baseline for WRAP 2A mixing equipment design. To this end, the following objectives are of particular interest: determine geometric influence of mixing blade at full scale (i.e., size, type, and location: height/offset); determine if similar results in terms of mixing effectiveness and product quality are achievable at this scale; determine if vibration is as effective at this larger scale in fluidizing the mixture and aiding in cleaning the vessel; determine if baffles or sweeping blades are needed to aid in mixing at the larger size and for cleaning the vessel; and determine quality of the poured monolithic product and investigate exotherm and filling influences at this larger size

  15. C-Band Airport Surface Communications System Standards Development. Phase II Final Report. Volume 2: Test Bed Performance Evaluation and Final AeroMACS Recommendations

    Science.gov (United States)

    Hall, Edward; Magner, James

    2011-01-01

    This report is provided as part of ITT s NASA Glenn Research Center Aerospace Communication Systems Technical Support (ACSTS) contract NNC05CA85C, Task 7: New ATM Requirements-Future Communications, C-Band and L-Band Communications Standard Development and was based on direction provided by FAA project-level agreements for New ATM Requirements-Future Communications. Task 7 included two subtasks. Subtask 7-1 addressed C-band (5091- to 5150-MHz) airport surface data communications standards development, systems engineering, test bed and prototype development, and tests and demonstrations to establish operational capability for the Aeronautical Mobile Airport Communications System (AeroMACS). Subtask 7-2 focused on systems engineering and development support of the L-band digital aeronautical communications system (L-DACS). Subtask 7-1 consisted of two phases. Phase I included development of AeroMACS concepts of use, requirements, architecture, and initial high-level safety risk assessment. Phase II builds on Phase I results and is presented in two volumes. Volume I is devoted to concepts of use, system requirements, and architecture, including AeroMACS design considerations. Volume II (this document) describes an AeroMACS prototype evaluation and presents final AeroMACS recommendations. This report also describes airport categorization and channelization methodologies. The purposes of the airport categorization task were (1) to facilitate initial AeroMACS architecture designs and enable budgetary projections by creating a set of airport categories based on common airport characteristics and design objectives, and (2) to offer high-level guidance to potential AeroMACS technology and policy development sponsors and service providers. A channelization plan methodology was developed because a common global methodology is needed to assure seamless interoperability among diverse AeroMACS services potentially supplied by multiple service providers.

  16. The Barselina Project Phase 4 Summary report. Ignalina Unit 2 Probabilistic Safety Analysis

    Energy Technology Data Exchange (ETDEWEB)

    Johansson, Gunnar [ES-Konsult AB, Stockholm (Sweden); Hellstroem, P. [RELCON AB, Solna (Sweden); Zheltobriuch, G.; Bagdonas, A. [Ignalina Power Plant, Visaginas (Lithuania)

    1996-12-01

    The Barselina Project was initiated in the summer of 1991. The project is a multilateral co-operation between Lithuania, Russia and Sweden. The long range objective is to establish common perspectives and unified bases for assessment of severe accident risks and needs for remedial measures for the RBMK reactors. The Swedish BWR Barsebaeck is used as reference plant and the Lithuanian RBMK Ignalina as application plant. During phase 3, from March, 1993 to June, 1994, a full scope Probabilistic Safety Analysis (PSA) model of the Ignalina Nuclear Power Plant unit 2 (INPP-2) was developed to identify possible safety improvement of risk importance. The probabilistic methodology was applied on a plant specific basis for a channel type reactor of RBMK design. To increase the realism of the risk model a set of deterministic analyses were performed and plant/RBMK-specific data bases were developed and used. A general concept for analysing this type of reactor was developed. During phase 4, July 1994 to September 1996, the PSA was further developed, taking into account plant changes, improved modeling methods and extended plant information concerning dependencies (area events, dynamic effects, electrical and signal dependencies). The updated model is quantified and new results and conclusions are evaluated.

  17. Psychometry and Pescatori projective test in coloproctological patients

    OpenAIRE

    dos Santos, Ana Célia Caetano Catarino; Oliveira, Dinis; Gomes, Zaida; Mesquita, Edgar; Gonçalves, Carla Rolanda Rocha

    2017-01-01

    Background Psychological assessment is not commonly performed nor easily accepted by coloproctological patients. Our aim was to evaluate the psychological component of coloproctological disorders using uncommon tools. Methods The 21-Item Depression Anxiety and Stress Scale and the Pescatori projective test were applied to coloproctological outpatients of the Gastroenterology Department of our hospital as well as to healthy volunteers. Results Seventy patients (median age 47 years, 2...

  18. EB Frond wave energy converter - phase 2

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2005-07-01

    The EB Frond project is a wave energy programme developed by The Engineering Business (EB) from an original idea at Lancaster University. The EB Frond is a wave generator with a collector vane on top of an arm that pivots near the seabed. Phase 1 of the project demonstrated the technical feasibility of the project and provided proof of concept. Phase 2 involved further assesment of the technical and commercial viability of the concept through the development of mathematical and physical modelling methods. The work involved small-scale (1/25th) testing in wave tanks at Newcastle and Lancaster Universities and the development, verification and validation of a time domain mathematical model. The decision by EB to put on hold its renewable generation programme meant that plans to test at an intermediate scale (1/16th), assess different survival strategies in extreme wave conditions, carry out site characterisation for full-scale systems and to produce a robust economic model were not fulfilled. However, the mathematical and physical modelling work was used to develop an economic model for the Frond system. This produced a predicted unit cost of electricity by a pre-commercial 5 MW demonstration farm of about 17 pence/kWh. The report discusses the small-scale testing, test results, mathematical modelling, analysis and interpretation, survivability, the economic model and the development route to full-scale production.

  19. Testing for Granger Causality in the Frequency Domain: A Phase Resampling Method.

    Science.gov (United States)

    Liu, Siwei; Molenaar, Peter

    2016-01-01

    This article introduces phase resampling, an existing but rarely used surrogate data method for making statistical inferences of Granger causality in frequency domain time series analysis. Granger causality testing is essential for establishing causal relations among variables in multivariate dynamic processes. However, testing for Granger causality in the frequency domain is challenging due to the nonlinear relation between frequency domain measures (e.g., partial directed coherence, generalized partial directed coherence) and time domain data. Through a simulation study, we demonstrate that phase resampling is a general and robust method for making statistical inferences even with short time series. With Gaussian data, phase resampling yields satisfactory type I and type II error rates in all but one condition we examine: when a small effect size is combined with an insufficient number of data points. Violations of normality lead to slightly higher error rates but are mostly within acceptable ranges. We illustrate the utility of phase resampling with two empirical examples involving multivariate electroencephalography (EEG) and skin conductance data.

  20. Concrete containment tests: Phase 2, Structural elements with liner plates: Interim report

    International Nuclear Information System (INIS)

    Hanson, N.W.; Roller, J.J.; Schultz, D.M.; Julien, J.T.; Weinmann, T.L.

    1987-08-01

    The tests described in this report are part of Phase 2 of the Electric Power Research Institute (EPRI) program. The overall objective of the EPRI program is to provide a test-verified analytical method of estimating capacities of concrete reactor containment buildings under internal overpressurization from postulated degraded core accidents. The Phase 2 testing included seven large-scale specimens representing structural elements from reinforced and prestressed concrete reactor containment buildings. Six of the seven test specimens were square wall elements. Of these six specimens, four were used for biaxial tension tests to determine strength, deformation, and leak-rate characteristics of full-scale wall elements representing prestressed concrete containment design. The remaining two square wall elements were used for thermal buckling tests to determine whether buckling of the steel liner plate would occur between anchorages when subjected to a sudden extreme temperature differential. The last of the seven test specimens for Phase 2 represented the region where the wall and the basemat intersect in a prestressed concrete containment building. A multi-directional loading scheme was used to produce high bending moments and shear in the wall/basemat junction region. The objective of this test was to determine if there is potential for liner plate tearing in the junction region. Results presented include observed behavior and extensive measurements of deformations and strains as a function of applied load. The data are being used to confirm analytical models for predicting strength and deformation of containment structures in a separate parallel analytical investigation sponsored by EPRI

  1. PKL-tests, test series IIB (end of blowdown). Vol. 2

    International Nuclear Information System (INIS)

    Umminger, K.; Mandl, R.; Nopper, H.; Siemens AG Unternehmensbereich KWU, Erlangen

    1987-01-01

    As part of the federally subsidized research project 1500 287/A0, the system behavior of a 1300 MWe pressurized water reactor (PWR) was investigated during the depressurization phase (end-of-blowdown, EOB), as well as during the refill and reflood phases of a loss of coolant accident involving a large break in the reactor coolant loop. Appropriate modifications to the system and supplementary instrumentation have made it possible to simulate the EOB (as of 26 bar), the refill phase and reflood phase in sequence. This report includes a detailed description of the instrumentation and the data acquisition system used in Test Series PKL IIB. (orig.) With 6 refs., 2 tabs., 60 figs [de

  2. Rail flaw sizing using conventional and phased array ultrasonic testing.

    Science.gov (United States)

    2012-12-01

    An approach to detecting and characterizing internal defects in rail through the use of phased array ultrasonic testing has shown the potential to reduce the risk of missed defects and improve transverse defect characterization. : Transportation Tech...

  3. Level of Aspiration, Risk-Taking Behavior, and Projective Test Performance: A Search for Coherence

    Science.gov (United States)

    Lefcourt, Herbert M.; Steffy, Richard A.

    1970-01-01

    Correlations were obtained between level of aspiration, gambling, and projective test variables. Achievement oriented behaviors in the level of aspiration task and in the gambling task were related to each other, and both were related to the adequacy of response to sexual stimuli in projective testing. Reprints from Herbert M. Lefcourt, Department…

  4. Underground Test Area Project Waste Management Plan (Rev. No. 2, April 2002)

    International Nuclear Information System (INIS)

    IT Corporation, Las Vegas

    2002-01-01

    The U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Operations Office (NNSA/NV) initiated the UGTA Project to characterize the risk posed to human health and the environment as a result of underground nuclear testing activities at the Nevada Test Site (NTS). The UGTA Project investigation sites have been grouped into Corrective Action Units (CAUs) in accordance with the most recent version of the Federal Facility Agreement and Consent Order. The primary UGTA objective is to gather data to characterize the groundwater aquifers beneath the NTS and adjacent lands. The investigations proposed under the UGTA program may involve the drilling and sampling of new wells; recompletion, monitoring, and sampling of existing wells; well development and hydrologic/ aquifer testing; geophysical surveys; and subsidence crater recharge evaluation. Those wastes generated as a result of these activities will be managed in accordance with existing federal and state regulations, DOE Orders, and NNSA/NV waste minimization and pollution prevention objectives. This Waste Management Plan provides a general framework for all Underground Test Area (UGTA) Project participants to follow for the characterization, storage/accumulation, treatment, and disposal of wastes generated by UGTA Project activities. The objective of this waste management plan is to provide guidelines to minimize waste generation and to properly manage wastes that are produced. Attachment 1 to this plan is the Fluid Management Plan and details specific strategies for management of fluids produced under UGTA operations

  5. An overview of Test Techniques for Characterizing Active Phased Array Antennas

    NARCIS (Netherlands)

    Keizer, W.P.M.N.

    1999-01-01

    In this paper a review will be given of the microwave testing of active phased anay antennas. It will be shown that due to the application of Transmit/Receive (T/R) modules in such antennas considerable more tests have to be performed to characterise completely their microwave performance than for

  6. TP Atlas: integration and dissemination of advances in Targeted Proteins Research Program (TPRP)-structural biology project phase II in Japan.

    Science.gov (United States)

    Iwayanagi, Takao; Miyamoto, Sei; Konno, Takeshi; Mizutani, Hisashi; Hirai, Tomohiro; Shigemoto, Yasumasa; Gojobori, Takashi; Sugawara, Hideaki

    2012-09-01

    The Targeted Proteins Research Program (TPRP) promoted by the Ministry of Education, Culture, Sports, Science and Technology (MEXT) of Japan is the phase II of structural biology project (2007-2011) following the Protein 3000 Project (2002-2006) in Japan. While the phase I Protein 3000 Project put partial emphasis on the construction and maintenance of pipelines for structural analyses, the TPRP is dedicated to revealing the structures and functions of the targeted proteins that have great importance in both basic research and industrial applications. To pursue this objective, 35 Targeted Proteins (TP) Projects selected in the three areas of fundamental biology, medicine and pharmacology, and food and environment are tightly collaborated with 10 Advanced Technology (AT) Projects in the four fields of protein production, structural analyses, chemical library and screening, and information platform. Here, the outlines and achievements of the 35 TP Projects are summarized in the system named TP Atlas. Progress in the diversified areas is described in the modules of Graphical Summary, General Summary, Tabular Summary, and Structure Gallery of the TP Atlas in the standard and unified format. Advances in TP Projects owing to novel technologies stemmed from AT Projects and collaborative research among TP Projects are illustrated as a hallmark of the Program. The TP Atlas can be accessed at http://net.genes.nig.ac.jp/tpatlas/index_e.html .

  7. Texas Medication Algorithm Project: development and feasibility testing of a treatment algorithm for patients with bipolar disorder.

    Science.gov (United States)

    Suppes, T; Swann, A C; Dennehy, E B; Habermacher, E D; Mason, M; Crismon, M L; Toprac, M G; Rush, A J; Shon, S P; Altshuler, K Z

    2001-06-01

    Use of treatment guidelines for treatment of major psychiatric illnesses has increased in recent years. The Texas Medication Algorithm Project (TMAP) was developed to study the feasibility and process of developing and implementing guidelines for bipolar disorder, major depressive disorder, and schizophrenia in the public mental health system of Texas. This article describes the consensus process used to develop the first set of TMAP algorithms for the Bipolar Disorder Module (Phase 1) and the trial testing the feasibility of their implementation in inpatient and outpatient psychiatric settings across Texas (Phase 2). The feasibility trial answered core questions regarding implementation of treatment guidelines for bipolar disorder. A total of 69 patients were treated with the original algorithms for bipolar disorder developed in Phase 1 of TMAP. Results support that physicians accepted the guidelines, followed recommendations to see patients at certain intervals, and utilized sequenced treatment steps differentially over the course of treatment. While improvements in clinical symptoms (24-item Brief Psychiatric Rating Scale) were observed over the course of enrollment in the trial, these conclusions are limited by the fact that physician volunteers were utilized for both treatment and ratings. and there was no control group. Results from Phases 1 and 2 indicate that it is possible to develop and implement a treatment guideline for patients with a history of mania in public mental health clinics in Texas. TMAP Phase 3, a recently completed larger and controlled trial assessing the clinical and economic impact of treatment guidelines and patient and family education in the public mental health system of Texas, improves upon this methodology.

  8. Technology Uncertainty and Project Managers' Information Sharing - A comparative case study of two new product development projects

    DEFF Research Database (Denmark)

    Jepsen, Lisbeth Brøde; Dietrich, Perttu

    2014-01-01

    uncertainty during various phases of new product development (NPD) projects. In this study, we compare two longitudinal NPD sub-projects that differ in uncertainty within the same large NPD project, in which the data source is the complete email exchange between a project manager and various actors...... (consisting of 3979 emails). The results show high levels of information sharing with the customer in both the early and late phases of high uncertainty. Interestingly, in the low uncertainty project, information sharing with the production department and the supplier is higher during the late phase...... of the NPD project. Unexpectedly, in both sub-projects, the project manager shares information with a wider range of both intra- and inter-organization actors in the early phases of the projects than in the late phases....

  9. Psychological characteristics of eating disorders as evidenced by the combined administration of questionnaires and two projective methods: the Tree Drawing Test (Baum Test) and the Sentence Completion Test.

    Science.gov (United States)

    Mizuta, Ichiro; Inoue, Yoichi; Fukunaga, Tomoko; Ishi, Ryohei; Ogawa, Asao; Takeda, Masatoshi

    2002-02-01

    The objective of this study is to examine psychological/psychopathological characteristics of eating disorders and their subtypes through a combined administration of questionnaires and projective tests. Three questionnaires (Eating Disorder Inventory - 2, Social Adaptation Scale, Southern California University Eating Disorder Inventory - Revised) and two projective tests (the Tree Drawing Test [TDT, Baum Test], and the Sentence Completion Test [SCT]) were administered to 126 female patients between the ages of 15 and 30 years, with eating disorders according to DSM-IV criteria at our outpatient clinic, and to 54 sex- and age-matched control subjects. The purging subtypes of eating disorders (anorexia nervosa - binge-eating/purging type [ANBP] and bulimia nervosa - purging type [BNP]) were clearly differentiated from the controls, both by the questionnaires and the projective tests. Compared with the controls, ANBP/BNP showed more problematic profiles across the three questionnaires, drew smaller and poorer trees in TDT to a more left location on the drawing paper, and gave fewer positive, and more negative responses in SCT. In contrast, few significant differences were found between anorexia nervosa- restricting type (ANR) and the controls, and between ANBP and BNP. As a trend, however, ANR was consistently located between the controls and ANBP/BNP across the whole questionnaires and projective tests.

  10. A simple uniformity test for ultrasound phased arrays.

    Science.gov (United States)

    Dudley, Nicholas J; Woolley, Darren J

    2016-09-01

    It is difficult to test phased array ultrasound transducers for non functioning elements. We aimed to modify a widely performed test to improve its ease and effectiveness for these arrays. A paperclip was slowly moved along the transducer array, with the scanner operating in M-mode, imaging at a fundamental frequency with automatic gain and grey scale adjustment disabled. Non-functioning elements are identified by a dark vertical line in the image. The test was repeated several times for each transducer, looking for consistency of results. 2 transducers, with faults already shown by electronic transducer testing, were used to validate the method. 23 transducers in clinical use were tested. The results of the modified test on the 2 faulty transducers agreed closely with electronic transducer testing results. The test indicated faults in 5 of the 23 transducers in clinical use: 3 with a single failed element and 2 with non-uniform sensitivity. 1 transducer with non-uniform sensitivity had undergone lens repair; the new lens was visibly non-uniform in thickness and further testing showed a reduction in depth of penetration and a loss of elevational focus in comparison with a new transducer. The modified test is capable of detecting non-functioning elements. Further work is required to provide a better understanding of more subtle faults. Copyright © 2016 Associazione Italiana di Fisica Medica. All rights reserved.

  11. Medical microbiological analysis of Apollo-Soyuz test project crewmembers

    Science.gov (United States)

    Taylor, G. R.; Zaloguev, S. N.

    1976-01-01

    The procedures and results of the Microbial Exchange Experiment (AR-002) of the Apollo-Soyuz Test Project are described. Included in the discussion of procedural aspects are methods and materials, in-flight microbial specimen collection, and preliminary analysis of microbial specimens. Medically important microorganisms recovered from both Apollo and Soyuz crewmen are evaluated.

  12. Fuel cell propulsion for urban duty vehicles: Bavarian fuel cell bus project

    International Nuclear Information System (INIS)

    Wurster, R.; Altmann, M.; Sillat, D.; Kalk, K. W.; Hammerschmidt, A.; Stuehler, W.; Holl, E.

    1998-01-01

    Following a feasibility study and a detailed specification phase, the realization of a fuel cell city bus prototype was started in autumn 1996. The project is a joint development effort of Siemens, MAN and Linde, which receives a 50 % funding by the Bavarian State Ministry for Economic Affairs, Transport and Technology (BStMWVT) in the context of the Hydrogen Initiative Bavaria. An MAN low-floor bus will be equipped with the components for a fuel cell drive system. The PEM fuel cell is developed by the power generation division of Siemens. Four fuel cell modules deliver a total electrical output of 120 kW to the two electric motors, which are linked by a summation gearbox by the Siemens Transportation Systems Division. MAN Technologie AG is responsible for the compressed hydrogen storage system allowing for a driving range of more than 250 km, while Linde AG takes care of the hydrogen periphery and delivers the hydrogen for the test operation scheduled for the beginning of the year 2000. Project coordination is done by Ludwig-Boelkow System-technik GmbH. The project is divided into four phases. The conceptual design phase is scheduled to last until the end of 1997. The partly overlapping system integration phase will end in the first quarter of 1999. The subsequent test and commissioning phase will prepare the test operation at the beginning of 2000 with a bus operator yet to be defined. (author)

  13. High Burnup Dry Storage Cask Research and Development Project, Final Test Plan

    Energy Technology Data Exchange (ETDEWEB)

    None

    2014-02-27

    EPRI is leading a project team to develop and implement the first five years of a Test Plan to collect data from a SNF dry storage system containing high burnup fuel.12 The Test Plan defined in this document outlines the data to be collected, and the storage system design, procedures, and licensing necessary to implement the Test Plan.13 The main goals of the proposed test are to provide confirmatory data14 for models, future SNF dry storage cask design, and to support license renewals and new licenses for ISFSIs. To provide data that is most relevant to high burnup fuel in dry storage, the design of the test storage system must mimic real conditions that high burnup SNF experiences during all stages of dry storage: loading, cask drying, inert gas backfilling, and transfer to the ISFSI for multi-year storage.15 Along with other optional modeling, SETs, and SSTs, the data collected in this Test Plan can be used to evaluate the integrity of dry storage systems and the high burnup fuel contained therein over many decades. It should be noted that the Test Plan described in this document discusses essential activities that go beyond the first five years of Test Plan implementation.16 The first five years of the Test Plan include activities up through loading the cask, initiating the data collection, and beginning the long-term storage period at the ISFSI. The Test Plan encompasses the overall project that includes activities that may not be completed until 15 or more years from now, including continued data collection, shipment of the Research Project Cask to a Fuel Examination Facility, opening the cask at the Fuel Examination Facility, and examining the high burnup fuel after the initial storage period.

  14. Tests of US rock salt for long-term stability of CAES reservoirs

    Energy Technology Data Exchange (ETDEWEB)

    Gehle, R.M.; Thoms, R.L.

    1986-01-01

    This is a report on laboratory tests to assess the effects of compressed air energy storage (CAES) on rock salt within the US. The project included a conventional laboratory test phase, with triaxial test machines, and a bench-scale test phase performed in salt mines in southern Louisiana. Limited numerical modeling also was performed to serve as a guide in selecting test layouts and for interpreting test data.

  15. Free-Piston Stirling Power Conversion Unit for Fission Power System, Phase II Final Report

    Science.gov (United States)

    Wood, J. Gary; Stanley, John

    2016-01-01

    In Phase II, the manufacture and testing of two 6-kW(sub e)Stirling engines was completed. The engines were delivered in an opposed 12-kW(sub e) arrangement with a common expansion space heater head. As described in the Phase I report, the engines were designed to be sealed both hermetically and with a bolted O-ring seal. The completed Phase II convertor is in the bolted configuration to allow future disassembly. By the end of Phase II, the convertor had passed all of the final testing requirements in preparation for delivery to the NASA Glenn Research Center. The electronic controller also was fabricated and tested during Phase II. The controller sets both piston amplitudes and maintains the phasing between them. It also sets the operating frequency of the machine. Details of the controller are described in the Phase I final report. Fabrication of the direct-current to direct-current (DC-DC) output stage, which would have stepped down the main controller output voltage from 700 to 120 V(sub DC), was omitted from this phase of the project for budgetary reasons. However, the main controller was successfully built, tested with the engines, and delivered. We experienced very few development issues with this high-power controller. The project extended significantly longer than originally planned because of yearly funding delays. The team also experienced several hardware difficulties along the development path. Most of these were related to the different thermal expansions of adjacent parts constructed of different materials. This issue was made worse by the large size of the machine. Thermal expansion problems also caused difficulties in the brazing of the opposed stainless steel sodium-potassium (NaK) heater head. Despite repeated attempts Sunpower was not able to successfully braze the opposed head under this project. Near the end of the project, Glenn fabricated an opposed Inconel NaK head, which was installed prior to delivery for testing at Glenn. Engine

  16. Proposal for the risk management implementation phase in oil field development project by adding value on the refurbishment of critical equipment

    Directory of Open Access Journals (Sweden)

    Hamid Abdul

    2017-01-01

    Full Text Available Refurbishment process is a conceptual stage in product life cycle. It is utilized in existing equipment in the field by adding value to recondition and repaired equipment. The main interest of this paper is to implement and design risk management implementation phase in oil field development project on the refurbishment of critical equipment in oil and gas industry. This paper is provided base on research and experiences in risk management and learned from practical team in industry which matched by an application in oil field development project in refurbishment of critical equipment. A framework of implementation phase for risk management in oil field development project in refurbishment critical equipment were reviewed and added value on communication skills of the project team to the stakeholder and organization, which support to external body and vice-versa. Risk management framework can be used for reference of refurbishment process with simply process and developed with same concept for the next wide development project in industry.

  17. Results of the ITER toroidal field model coil project

    International Nuclear Information System (INIS)

    Salpietro, E.; Maix, R.

    2001-01-01

    In the scope of the ITER EDA one of the seven largest projects was devoted to the development, manufacture and testing of a Toroidal Field Model Coil (TFMC). The industry consortium AGAN manufactured the TFMC based on on a conceptual design developed by the ITER EDA EU Home Team. The TFMC was completed and assembled in the test facility TOSKA of the Forschungszentrum Karlsruhe in the first half of 2001. The first testing phase started in June 2001 and lasted till October 2001. The first results have shown that the main goals of the project have been achieved

  18. Canadian trace emissions project management : phase 2

    International Nuclear Information System (INIS)

    Lajeunesse, J.J.G.

    1997-12-01

    A comprehensive emission study was carried out at Nova Scotia Power's Lingan generating station in which pulverized coal, bottom ash, bottom ash cooling water, fly ash and flue gas were sampled and analyzed for organic and inorganic priority substances. The sampling was done according to the recommended standard of sampling provided by the Canadian Electricity Association's 1992 report entitled 'Trace Emission Project Management : phase 1'. The objectives of this emission study were to show how priority substances are transformed and partitioned within the various process streams in a modern pulverized coal-fired utility boiler and to determine the type and emission rate of various priority substances in the flue gas. An emission data set was prepared in PISCES format, and the data was used to evaluate the effectiveness of the electrostatic precipitator for controlling the emissions of these priority substances. All but five of the elements tracked in the report had mass balances from 90 per cent to 112 per cent. The five elements for which such closure could not be achieved were zinc, mercury, selenium, chlorine and bromine.The data set produced was used to evaluate the Ontario Hydro 640 MJ/h pilot scale combustor and FACT mathematical models. 39 refs., 32 tabs., 10 figs., 2 appendices

  19. Clinical identification of compensatory structures on projective tests: a self psychological approach.

    Science.gov (United States)

    Silverstein, M L

    2001-06-01

    In this article I discuss compensatory structure, a concept from Kohut's (1971, 1977) psychology of the self that is not as familiar as Kohut's other views about the self. Compensatory structures are attempts to repair selfobject failure, usually by strengthening idealization or twinship in the face of mirroring deficits. Compensatory structures, particularly their early indications, can be detected on projective tests for identifying adaptive resources and treatment potential. The clinical identification of compensatory structures on test findings is described using Rorschach and Thematic Apperception Test (Murray, 1943) content. Particular attention is devoted to the 2-part process of demonstrating first, an injury to the self, and second, how attempts to recover from such injuries can be detected on projective tests. Clinical examples are provided, and the differentiation between compensatory structures and defenses and sublimation is discussed.

  20. Comments on Thermal Physical Properties Testing Methods of Phase Change Materials

    Directory of Open Access Journals (Sweden)

    Jingchao Xie

    2013-01-01

    Full Text Available There is no standard testing method of the thermal physical properties of phase change materials (PCM. This paper has shown advancements in this field. Developments and achievements in thermal physical properties testing methods of PCM were commented, including differential scanning calorimetry, T-history measurement, the water bath method, and differential thermal analysis. Testing principles, advantages and disadvantages, and important points for attention of each method were discussed. A foundation for standardized testing methods for PCM was made.

  1. Beyond "objective" and "projective": a logical system for classifying psychological tests: comment on Meyer and Kurtz (2006).

    Science.gov (United States)

    Wagner, Edwin E

    2008-07-01

    I present a formal system that accounts for the misleading distinction between tests formerly termed objective and projective, duly noted by Meyer and Kurtz (2006). Three principles of Response Rightness, Response Latitude and Stimulus Ambiguity are shown to govern, in combination, the formal operating characteristics of tests, producing inevitable overlap between "objective" and "projective" tests and creating at least three "types" of tests historically regarded as being projective in nature. The system resolves many past issues regarding test classification and can be generalized to include all psychological tests.

  2. The Test Blanket Modules project in Europe: From the strategy to the technical plan over next ten years

    International Nuclear Information System (INIS)

    Poitevin, Y.; Zmitko, M.; Orco, G. dell; Laesser, R.; Diegele, E.; Sundstroem, J.; Boccaccini, L.; Salavy, J.-F.

    2006-01-01

    The testing of Breeding Blanket concepts in ITER is recognized as an essential milestone in the development of a future reactor ensuring tritium self-sufficiency, extraction of high grade heat and electricity production. Europe is currently developing two reference breeding blankets for DEMO reactor specifications that will be tested in ITER: the Helium-Cooled Lithium-Lead (HCLL) blanket which uses the eutectic Pb-15. 7 Li as both breeder and neutron multiplier, and the Helium-Cooled Pebble-Bed (HCPB) blanket which features lithiated ceramic pebbles (Li 4 SiO 4 or Li 2 TiO 3 ) as breeder and beryllium pebbles as neutron multiplier. Both blankets are using the pressurized He technology for heat extraction (8 MPa, inlet/outlet temperature 300/500 o C) and a 9% CrWVTa Reduced Activation Ferritic Martensitic (RAFM) steel as structural material, the EUROFER. Referring to the so called '' fast-track '' EU scenario, those concepts are intended to be tested in ITER, getting the maximum of information required for launching the DEMO blanket design and construction after the first 10 years of ITER operation. For that, the EU has adopted a blanket testing strategy based on the development of Test Blanket Modules (TBMs) that are expected to use DEMO relevant technologies and are designed for each ITER plasma phase to optimize the feedback and to avoid any impact on ITER availability. Following the decision on ITER construction, the EU has reviewed and detailed the fundamental elements for an implementation of the future EU TBMs Project aimed at delivering TBMs Systems to ITER under suitable schedule and acceptance standards. For that the following items have been analyzed in detail and are reported in the present paper: · Impact of the ITER environment (design, standards, schedule, operational scheme) on the TBM systems design and development plan · Project technical plan with focus on the next ten years up to the installation of the first TBMs in ITER · Project risk

  3. Fabrication and installment of the hard-wired I and C works for the neutral beam injection test stand of the K-STAR project

    International Nuclear Information System (INIS)

    Jung, Ki Sok; Oh, Byung Hun

    2004-12-01

    Instrumentation and Control(I and C) of the neutral beam injection test stand (NBI-TS) for the K-STAR national fusion research project has been underway since the start of the project to answer the diverse requests arising from the various facets of the development and construction phases of the project. In a parallel effort with the software oriented I and C development, there has been existing an enormous amount of hard-wiring I and C works for the NBI facility to be developed and fabricated in schedule. Circuits and hardwired functions have been designed, tested, fabricated, and finally installed to the relevant parts of the system. Examples of those hard-wired I and C works are related to the vacuum system, gas feeding system, arc detector circuit, ion source monitoring, bending magnet and calorimeter. Another one to be mentioned is the interlock circuitry. One of the interlock circuits are related to the coolant flow failure. The other is the interlock circuit related to the vacuum failure. All of the above mentioned circuitry now constitutes integral parts for the proper operation of the NBI system; details of those hard-wired I and C work are described in this report

  4. Project SAFE. Update of the SFR-1 safety assessment. Phase 1

    International Nuclear Information System (INIS)

    Andersson, Johan; Riggare, P.; Skagius, K.

    1998-10-01

    SFR-1 is a facility for disposal of low-level radioactive operational waste from the nuclear power plants in Sweden. Low-level radioactive waste from industry, medicine, and research is also disposed in SFR-1. The facility is situated in bedrock beneath the Baltic Sea, 1 km off the coast near the Forsmark nuclear power plant. SFR-1 was built between the years 1983 and 1988. An assessment of the long-term performance of the facility was included in the vast documentation that was a part of the application for an operational license. The assessment was presented in the form of a final safety report. In the operational licence for SFR-1 it is stated that renewed safety assessments should be carried out at least each ten years. In order to meet this demand SKB has launched a special project, SAFE (Safety Assessment of Final Disposal of Operational Radioactive Waste). The aim of the project is to update the safety analysis and to prepare a safety report that will be presented to the Swedish authorities not later than year 2000. Project SAFE is divided into three phases. The first phase is a prestudy, and the results of the prestudy are given in this report. The aim of the prestudy is to identify issues where additional studies would improve the basis for the updated safety analysis as well as to suggest how these studies should be carried out. The work has been divided into six different topics, namely the inventory, the near field, the far field, the biosphere, radionuclide transport calculations and scenarios. For each topic the former safety reports and regulatory reviews are scrutinised and needs for additional work is identified. The evaluations are given in appendices covering the respective topics. The main report is a summary of the appendices with a more stringent description of the repository system and the processes that are of interest and therefore should be addressed in an updated safety assessment. However, it should be pointed out that one of the

  5. The MYRRHA ADS Project in Belgium Enters the Front End Engineering Phase

    International Nuclear Information System (INIS)

    De Bruyn, D.; Ait Abderrahim, H.; Baeten, P.; Leysen, P.

    2015-01-01

    The MYRRHA project started in 1998 by SCK.CEN. MYRRHA is a MTR, based on the ADS concept, for material and fuel research, for studying the feasibility of transmutation of minor actinides and long-lived fission products arising from radioactive waste reprocessing and finally for demonstrating at a reasonable power scale the principle of the ADS. The MYRRHA design has progressed through various framework programmes of the European Commission in the context of Partitioning and Transmutation. The design has now entered into the Front End Engineering Phase (FEED) covering the period 2012- 2015. The engineering company, which will handle this phase, has been selected and the works have begun in the late 2013. In the meantime we have made some refinements in both primary systems and plant layout, including reactor building design. In this paper, we present the most recent developments of the MYRRHA design in terms of reactor building and plant layout as existing today. (authors)

  6. International Uranium Resources Evaluation Project (IUREP) orientation phase mission summary report: Colombia

    International Nuclear Information System (INIS)

    1984-01-01

    A full report has been released describing the findings of the International Uranium Resources Evaluation Project (IUREP) Orientation Phase Mission to Colombia. The Mission suggests that the speculative uranium resources of the country could be within the very wide range of 20 000 tonnes of 220 000 tonnes of uranium metal. The Mission finds that the area with the highest potential is the Llanos Orientales (Interior Zone), which has the potential of hosting quartz-pebble conglomerate deposits, Proterozoic unconformity-related deposits and sandstone deposits. The Mission recommends that approximately US$80 million should be expended in a phased ten-year exploration programme. It is likely that the majority of the funds will be needed for drilling, followed by ground surveys and airborne radiometry. It is the opinion of the Mission that the considerable funds required for the proposed programme could most suitably be raised by inviting national or foreign commercial organizations to participate under a shared production agreement. (author)

  7. International Uranium Resources Evaluation Project (IUREP) orientation phase mission summary report: Portugal

    International Nuclear Information System (INIS)

    1985-01-01

    A report has recently been published which describes the findings of the International Uranium Resources Evaluation Project (IUREP) mission to Portugal. The IUREP Orientation Phase mission to Portugal estimates that the Speculative Resources of that country fall within the range 20,000 to 80,000 tonnes uranium. The majority of this potential is expected to be located in intergranitic vein deposits and in pre-Ordovician schists, but other favourable geological environments include episyenites and Meso-Cainozoic continental sediments. The mission recommends that approximately US$25 million be spent on exploration in Portugal over the next 10 years. The majority of this ($18 million) would be spent on drilling, with a further $7 million on surface surveys and airborne radiometric surveys. It is the opinion of the IUREP Orientation Phase Mission that the considerable funding required for the outlined programme would most suitably be realized by inviting national or foreign commercial organisations to participate in the exploration effort under a partnership or shared production arrangements. (author)

  8. Statement on current progress of the EPR project. Basic Design phase concluded

    International Nuclear Information System (INIS)

    Lamprecht, F.

    1997-01-01

    Against the background of expected increasing demand for electric power worldwide it is obvious that any existing technology for electricity generation will be required in the future to meet the demand, just as well as technology improvements. Nuclear industry's answer to this challenge are activities for further evolution of the PWR concept as a joint venture of France and Germany for development of the European Pressurized Water Reactor (EPR). The project participants are reactor manufacturers and operators of both countries as well as organisations responsible for reactor safety. The Basic Design phase which started in 1995, after prior definition of the common safety philosophy, has recently been concluded. The results have been presented at a meeting in October 1997 in Cologne, organised by KTG and SFEN, the countries' respective nuclear societies. The broad statement is that project work was successful in achieving two major objectives: A well-balanced safety concept, and a competitive design. (orig./CB) [de

  9. Phase 2 Technical Letter Report TS-00358: Portable Acoustic Contraband Detector

    Energy Technology Data Exchange (ETDEWEB)

    Diaz, Aaron A.; Cinson, Anthony D.; Denslow, Kayte M.; Munley, John T.

    2008-01-25

    This report provides the results of all PNNL managed activities on this project, and contains a description of the data acquisition configuration and testing protocols, results and conclusions from this work. This report is part of the final deliverables package submitted to the client during Phase 2 of Project 52042.

  10. Phase II Water Rental Pilot Project: Snake River Resident Fish and Wildlife Resources and Management Recommendations.

    Energy Technology Data Exchange (ETDEWEB)

    Stovall, Stacey H.

    1994-08-01

    The Idaho Water Rental Pilot Project was implemented in 1991 as part of the Non-Treaty Storage Fish and Wildlife Agreement between Bonneville Power Administration and the Columbia Basin Fish and Wildlife Authority. The goal of the project is to quantify resident fish and wildlife impacts resulting from salmon flow augmentation releases made from the upper Snake River Basin. Phase I summarized existing resource information and provided management recommendations to protect and enhance resident fish and wildlife habitat resulting from storage releases for the I improvement of an adromous fish migration. Phase II includes the following: (1) a summary of recent biological, legal, and political developments within the basin as they relate to water management issues, (2) a biological appraisal of the Snake River between American Falls Reservoir and the city of Blackfoot to examine the effects of flow fluctuation on fish and wildlife habitat, and (3) a preliminary accounting of 1993--1994 flow augmentation releases out of the upper Snake, Boise, and Payette river systems. Phase III will include the development of a model in which annual flow requests and resident fish and wildlife suitability information are interfaced with habitat time series analysis to provide an estimate of resident fish and wildlife resources.

  11. Managing externally financed projects: the Integrated Primary Health Care Project in Bolivia.

    Science.gov (United States)

    Homedes, N

    2001-12-01

    Bolivia is one of the poorest countries in Latin America. Health indicators are very poor, communicable diseases are prevalent and, coupled with malnutrition, remain the major killers of children under 5 years old. The Integrated Primary Health Care Project (PROISS) was a US$39 million project executed by the Ministry of Health (MOH), 50% financed by the World Bank and aimed at improving primary health care in the four largest Bolivian municipalities. The implementation of the project started in 1990 and ended in 1997. During implementation it went through three distinct phases: Phase 1 (1990-94) was a period characterized by conflict and confusion; Phase 2 (1995-mid-1996) documented major improvements in coverage and service quality; and Phase 3 (mid-1996-97) witnessed the decline of the project. This paper explores the factors that contributed to the success and the decline of the project, draws lessons for project managers and international agencies involved in the definition and implementation of social sector projects, and discusses the unlikelihood that externally financed projects can have a sustainable impact on the development of the health sector of recipient countries.

  12. TMI-2 Vessel Investigation Project (VIP) Metallurgical Program

    International Nuclear Information System (INIS)

    Diercks, D.R.; Neimark, L.A.

    1990-06-01

    The TMI-2 Vessel Investigation Project (VIP) Metallurgical Program is a part of the international TMI-2 Vessel Investigation Project being conducting jointly by the US Nuclear Regulatory Commission and the Organization for Economic Co-operation and Development (OECD). The overall project consists of three phases, namely (1) recovery of material samples from the lower head of the TMI-2 reactor, (2) examination and analysis of the lower head samples and the preparation and testing of archive material subjected to a similar thermal history, and (3) procurement, examination, and analysis of companion core material located adjacent to or near the lower head material. The specific objectives of the ANL Metallurgical Program, which comprises a major portion of Phase 2, are to prepare metallographic and mechanical test specimen blanks from the TMI-2 lower head material, prepare similar test specimen blanks from suitable archive material subjected to the appropriate thermal processing, determine the mechanical properties of the lower vessel head and archive materials under the conditions of the core-melt accident, and assess the lower head integrity and margin-to-failure during the accident. The ANL work consists of three tasks: (1) archive materials program, (2) fabrication of metallurgical and mechanical test specimens from the TMI-2 pressure vessel samples, and (3) mechanical property characterization of TMI-2 lower pressure vessel head and archive material

  13. Stress analysis of HLW containers. Preliminary ring test exercise Compas project

    International Nuclear Information System (INIS)

    1989-01-01

    This document describes the series of experiments and associated calculations performed as the Compas preliminary ring test exercise. A number of mild steel rings, representative of sections through HLW containers, some notched and pre-cracked, were tested in compression right up to and beyond their ultimate load. The Compas project partners independently modelled the behaviour of these rings using their finite element codes. Four different ring types were tested, and each test was repeated three times. For three of the ring types, the three test repetitions gave identical results. The fourth ring, which was not modelled by the partners, had a 4 mm thick layer of weld metal deposited on its surface. The three tests on this ring did not give identical results and suggested that the effect of welding methods should be addressed at a later stage of the project. Fracture was not found to be a significant cause of ring failure. The results of the ring tests were compared with the partners predictions, and additionally some time was spent assessing where the use of the codes could be improved. This exercise showed that the partners codes have the ability to produce results within acceptable limits. Most codes were unable to model stable crack growth. There were indications that some codes would not be able to cope with a significantly more complex three-dimensional analysis

  14. Damage evolution of TBC system under in-phase thermo-mechanical tests

    International Nuclear Information System (INIS)

    Kitazawa, R.; Tanaka, M.; Kagawa, Y.; Liu, Y.F.

    2010-01-01

    In-phase thermo-mechanical tests (TMF) of EB-PVD Y 2 O 3 -ZrO 2 thermal barrier coating (TBC) system (8 wt% Y 2 O 3 -ZrO 2 /CoNiCrAlY/IN-738 substrate) were done under a through-the-thick-direction thermal gradient from TBC surface temperature at 1150 deg. C to substrate temperature at 1000 deg. C. Deformation and failure behaviors of the TBC system were observed at the macroscopic and microscopic scales and damage evolution of the system under in-phase thermo-mechanical test was discussed. Special attention was paid to TBC layer cracking, thermally grown oxide (TGO) layer formation and void formation in bond coat and substrate. Effect of TMF conditions on the damage evolution behaviors was also discussed.

  15. Fuel Retrieval Sub-Project (FRS) Stuck Fuel Station Performance Test Data Report

    International Nuclear Information System (INIS)

    THIELGES, J.R.

    2000-01-01

    This document provides the test data report for Stuck Fuel Station Performance Testing in support of the Fuel Retrieval Sub-Project. The stuck fuel station was designed to provide a means of cutting open a canister barrel to release fuel elements, etc

  16. TMI-2 Vessel Investigation Project Metallurgical Program

    International Nuclear Information System (INIS)

    Diercks, D.R.; Neimark, L.A.

    1990-01-01

    The TMI-2 [Three Mile Island unit 2] Vessel Investigation Project Metallurgical Program at Argonne National Laboratory is a part of the international TMI-2 Vessel Investigation Project being conducted jointly by the U.S. Nuclear Regulatory Commission and the Organization for Economic Co-operation and Development (OECD). The overall project consists of three phases, namely (1) recovery of material samples from the lower head of the TMI-2 reactor, (2) examination and analysis of the lower head samples and the preparation and testing of archive material subjected to a similar thermal history, and (3) procurement, examination, and analysis of companion core material located adjacent to or near the lower head material. The specific objectives of the ANL Metallurgical Program, which accounts for a major portion of Phase 2, are to prepare metallographic and mechanical test specimen blanks from the TMI-2 lower head material, prepare similar test specimen blanks from suitable archive material subjected to the appropriate thermal processing, determine the mechanical properties of the lower vessel head and archive materials under the conditions of the core-melt accident, and assess the lower head integrity and margin-to-failure during the accident. The ANL work consists of three tasks: (1) archive materials program, (2) fabrication of metallurgical and mechanical test specimens from the TMI-2 pressure vessel samples, and (3) mechanical property characterization of TMI-2 lower pressure vessel head and archive material

  17. Two-phase flow dynamics in ECC

    International Nuclear Information System (INIS)

    Albraaten, P.J.

    1981-07-01

    The present report summarizes the achievements within the project ''Two-phase Systems and ECC''. The results during 1978 - 1980 are accounted for in brief as they have been documented in earlier reports. The results during the first half of 1981 are accounted for in greater detail. They contain a new model for the Basset force and test runs with this model using the test code RISQUE. Furthermore, test runs have been performed with TRAC-PD2 MOD 1. This code was implemented on Edwards Pipe Blowdown experiment (a standard test case) and UC-Berkeley Reflooding experiment (a non-standard test case.) (Auth.)

  18. Frequency-domain imaging algorithm for ultrasonic testing by application of matrix phased arrays

    Directory of Open Access Journals (Sweden)

    Dolmatov Dmitry

    2017-01-01

    Full Text Available Constantly increasing demand for high-performance materials and systems in aerospace industry requires advanced methods of nondestructive testing. One of the most promising methods is ultrasonic imaging by using matrix phased arrays. This technique allows to create three-dimensional ultrasonic imaging with high lateral resolution. Further progress in matrix phased array ultrasonic testing is determined by the development of fast imaging algorithms. In this article imaging algorithm based on frequency domain calculations is proposed. This approach is computationally efficient in comparison with time domain algorithms. Performance of the proposed algorithm was tested via computer simulations for planar specimen with flat bottom holes.

  19. Phase II evaluation of waste concrete road materials for use in oyster aquaculture - field test.

    Science.gov (United States)

    2015-02-01

    The overall objective of this study was to determine the suitability of recycled concrete aggregate : (RCA) from road projects as bottom conditioning material for on-bottom oyster aquaculture in the : Chesapeake Bay. During this Phase of the study, t...

  20. Phase II evaluation of waste concrete road materials for use in oyster aquaculture - field test.

    Science.gov (United States)

    2014-11-01

    The overall objective of this study was to determine the suitability of recycled concrete : aggregate (RCA) from road projects as bottom conditioning material for on-bottom oyster : aquaculture in the Chesapeake Bay. During this Phase of the study, t...