WorldWideScience

Sample records for regulatory authorities require

  1. Establishing exemption and clearance criteria by the regulatory authority

    International Nuclear Information System (INIS)

    Salih, A.E.A.

    2012-04-01

    This Project work discusses the relationship between the concepts of exemption and clearance, and their practical use in the overall scheme of regulatory control of practices. It also discusses how exemptions and clearance is established and the scope of its applications for regulatory control. The concept of general clearance levels for any type of material and any possible pathway of disposal is also introduced in this work. Guidance of the Group of Experts establishing scenarios for general clearance, parameter values, and a nuclide-specific list of calculated clearance levels is also presented. Regulatory authorities are required to develop guidance on exemption and clearance levels to assist licensees and registrants to know which practices and sources within practices are exempted from regulatory control and those to be cleared from further controls. Exemption and clearance levels are tools for assisting the Regulatory Authority to optimize the use of resources. (author)

  2. The regulatory application of authorization in radiological protection

    International Nuclear Information System (INIS)

    Lazo, T.; Frullani, S.

    2004-01-01

    Authorization is the process used by governments and regulatory authorities to decide what regulatory controls or conditions, if any, should be applied to radioactive sources or radiation exposure situations in order to protect the public, workers and the environment appropriately. Over the years, governments and regulatory authorities have used various approaches to the authorization process under differing circumstances. Now, with the new draft recommendations from the International Commission on Radiological Protection (ICRP), there is the prospect of being able to use a single, simple and self-coherent approach for the process of regulatory authorization under all circumstances. Previously, the ICRP recommended the use of various approaches to manage radiological protection situations. For what were called practices, exposures were subject to limits, and optimisation was required below these limits. What were called interventions were subject to intervention levels, above which some action could be considered justified, and which should be optimised based on consideration of how much dose could be averted by the countermeasure considered. Radon in homes was subject to action levels, above which some sort of countermeasure could be recommended. These approaches are all philosophically distinct and logically constructed, but their differences, particularly in the types of numerical criteria used (limits, intervention levels, action levels, etc.) contributed to confusion and misunderstanding. (author)

  3. Creating a safety culture in the regulatory authority: The Cuban experience

    International Nuclear Information System (INIS)

    Ferro Fernandez, R.; Guillen Campos, A.

    2002-01-01

    The Cuban regulatory authority has been working during several years for the fostering and development of a high Safety Culture level in nuclear activities in the country. As starting point to achieve this objective the assessment of the Safety Culture level in the regulatory authority performance was considered an important issue. For this purpose a preliminary diagnosis was carried out by means of a national survey that allowed identifying some areas of the regulatory activity that required improvements in order to achieve a higher Safety Culture and to immediately implement appropriate actions. Two of the most important actions undertaken were: the statement of the regulatory authority Safety Policy which governs and determines the performance of this organization and its staff and also the implementation of a new interaction practice at top level between the regulatory authority and the utilities of the nuclear sector through the Annual Regulatory Conference. The present paper summarizes these two introduced practices into the Cuban regulatory activity. (author)

  4. Regulatory requirements related to maintenance and compliance monitoring

    International Nuclear Information System (INIS)

    Ling, A.K.H.

    1997-01-01

    The maintenance related regulatory requirements are identified in the regulatory documents and licence conditions. Licensee complies with these requirements by operating the nuclear power plant within the safe operating envelope as given in the operating policies and principles and do maintenance according to approved procedures and/or work plans. Safety systems are regularly tested. AECB project officers review and check to ensure that the licensee operates the nuclear power plant in accordance with the regulatory requirements and licence conditions. (author). 6 tabs

  5. Regulatory authority infrastructure for Namibia

    International Nuclear Information System (INIS)

    Shangula, K.

    2001-01-01

    The Republic of Namibia is participating in the International Atomic Energy Agency's Model Project for the Improvement of National Regulatory Authority Infrastructures in Member States. The paper illustrates our experience in solving problems and difficulties confronted in establishing an effective regulatory authority operating within the existing national infrastructure that should be supported by the Government. An effective regulatory authority is seen as part of the wider administrative scope of our Government through ministerial mandates given by the State from time to time, guaranteeing its independence when implementing legal provisions under statutes. Sections of the report illustrate our experience in the following areas: 1. National radiation protection policy 2. Structure of our national regulatory authority 3. Laws and regulations 4. Provisions for notification, authorization and registration 5. In-depth security measures for radiation sources and radioactive material 6. Systems for the inspection of radiation sources, radioactive materials, enforcement of legal provisions 7. Extent of the applications of radiation sources and radioactive materials in the country. The paper provides information regarding existing Government policy on radiation protection; structure and legal aspects of the national regulatory, including statutes and regulations; the extent of application and uses of radiation sources and security of radioactive materials; human resources: strengths and constraints; management practices and financing of regulatory authority; and plans for emergency recovery of orphan sources. National plans for management of disused sources, recovery of orphan sources, abnormal emergencies, communication of information to affected persons on exposure effects, and the safety training of persons using these applications are discussed. the paper provides a summary and some suggestions of the way forward for Namibia. (author)

  6. Regulatory authority information system RAIS

    International Nuclear Information System (INIS)

    Ortiz, P.; Mrabit, K.; Miaw, S.

    2000-01-01

    In this lecture the principles of the regulatory authority information system (RAIS) are presented. RAIS is a tool currently being developed by the IAEA for the Regulatory Authorities. It is a part of a set of supporting actions designed to assist member states in achieving the objectives of the Model project on radiation and waste safety infrastructure. RAIS is a tool that provides the management of the Regulatory Authority with the key information needed for the planning and implementation of activities and to ensure confidence that resources are optimally used. The RAIS contains five modules: Inventory of installations and radiation sources; Authorization process; Inspection and follow-up actions; Information on personal dosimetry; Assessment of effectiveness by means of performance indicators

  7. Management of the Regulatory Authority Information

    International Nuclear Information System (INIS)

    Suman, H.

    2003-01-01

    Safe Management of the Regulatory Authority Information is one of the essential elements to ensure the effectiveness of the regulatory program as a whole. This paper briefly describes the information management basis in RNRO, which is in charge of the regulatory authority tasks in Syria. SINA-2, a computational tool prepared in RNRO for managing the information related to the inventory of radiation sources and users, is also introduced

  8. 76 FR 21932 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Order Granting...

    Science.gov (United States)

    2011-04-19

    ... statement therein, as follows: I. Introduction On February 4, 2011, the Financial Industry Regulatory...-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Order Granting Approval of a... Financial Industry Regulatory Authority, Inc. (``FINRA'') to amend Rule 13806 of the Code of Arbitration...

  9. Cooperation of Ukrainian regulatory authorities in the SIP

    Energy Technology Data Exchange (ETDEWEB)

    Kutina, L.; Bachner, D.; Bykov, V.; Erickson, L.; Kondralyev, S.; Redko, V.; Simonov, I.; Vasilchenko, V. [SSTC NRS, Stusa St. 35-37, 03142, Kyiv (Ukraine)

    2003-07-01

    The State Nuclear Regulatory Committee of Ukraine (SNRCU) supported by the State Scientific and Technical Center (SSTC) and the Licensing consultant (LC - RISKAUDIT/SCIENTECH) coordinates the activities of other regulatory authorities (RA) within the Shelter Implementation Plan (SIP) licensing. A protocol on cooperation and differentiation of competence in the SIP has been agreed between SNRCU and other RA (Ecology, Health, Construction, Occupational safety, Fire). The RA intended to carry out their activities such that SIP be implemented in the most efficient way by: - providing the Chernobyl NPP with a possibility to choose optimal variants for Shelter transformation; - minimizing required regulatory steps for SIP; - reviewing SIP documents at the initial stages of development of SIP designs; - providing consultative support by technical support organizations (TSO) on the SIP designs; - relating regulatory decisions on safety issues to the competence of the inspection at the Chernobyl NPP site. Coordination of regulatory activity and cooperation in safety areas are presented.

  10. 76 FR 66344 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Order Approving...

    Science.gov (United States)

    2011-10-26

    ...-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Order Approving Proposed Rule Change... 31, 2011, Financial Industry Regulatory Authority, Inc. (``FINRA'') (f/k/a National Association of... consolidation process, see Information Notice, March 12, 2008 (Rulebook Consolidation Process). For convenience...

  11. 75 FR 17456 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Order Approving...

    Science.gov (United States)

    2010-04-06

    ...-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Order Approving Proposed Rule Change..., Financial Industry Regulatory Authority, Inc. (``FINRA'') filed with the Securities and Exchange Commission... terms. For more information about the rulebook consolidation process, see Information Notice, March 12...

  12. 78 FR 62784 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of...

    Science.gov (United States)

    2013-10-22

    ...-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Designation of a Longer... 5210 (Publication of Transactions and Quotations) October 4, 2013. I. Introduction On August 15, 2013, Financial Industry Regulatory Authority, Inc. (``FINRA'') filed with the Securities and Exchange Commission...

  13. 75 FR 5157 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Order Approving...

    Science.gov (United States)

    2010-02-01

    ...-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Order Approving Proposed Rule Change... Consolidated FINRA Rulebook January 25, 2010. On December 2, 2009, the Financial Industry Regulatory Authority... later in the rulebook consolidation process. It is therefore ordered, pursuant to Section 19(b)(2) of...

  14. 77 FR 47470 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of...

    Science.gov (United States)

    2012-08-08

    ...-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Withdrawal of Proposed Rule Change To Adopt FINRA Rule 2231 (Customer Account Statements) in the Consolidated FINRA Rulebook August 2, 2012. On April 22, 2009, the Financial Industry Regulatory Authority, Inc. (``FINRA'') (f/k/a...

  15. 76 FR 21084 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of...

    Science.gov (United States)

    2011-04-14

    ... Securities April 8, 2011. I. Introduction On March 3, 2011, the Financial Industry Regulatory Authority, Inc... SECURITIES AND EXCHANGE COMMISSION [Release No. 34-64283; File No. SR-FINRA-2011-012] Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Designation of a Longer...

  16. Annual Report 2013. Nuclear Regulatory Authority

    International Nuclear Information System (INIS)

    2010-01-01

    The present Annual Report of Activities of the Nuclear Regulatory Authority (ARN), prepared regularly from the creation as independent institution, describes across seven parts and eight annexes the activities developed by the organism during 2013. The main topic are: the organization and the activity of the ARN; the regulatory standards; the licensing and inspection of nuclear power plants and critical facilities; the emergency systems; the environmental monitoring; the occupational surveillance; the training and the public information; improved organizational and budgetary developments. Also, this publication has annexes with the following content: regulatory documents; inspections to medical; presentations of publications from ARN staff; measurement and evaluation of the drinking water of Ezeiza; international expert report on the implementation of international standards on radiation protection in the Ezeiza Atomic Center; Code of Ethics of the Nuclear Regulatory Authority.

  17. The bibliographical documentation in the Nuclear Regulatory Authority

    International Nuclear Information System (INIS)

    Carregado, M.A.

    1998-01-01

    Full text: The presentation of the following work serves to display the recourses which the Information Center (I.C.) - Ezeiza Sector of the Nuclear Regulatory Authority of the Argentine Republic possesses. These recourses help the investigation and application of the regulatory subject as well as the scientific technical community, which uses the information about radiation protection and nuclear safety. Periodical publications, reports, books, standards, etc., are specified quantitatively in detail. Mainly, the automated means are emphasized in order to get to safe ways of information. Data bases in CD-ROM are also enumerated. These are now essential in order to track down the expert information on each theme. The most outstanding ones among these data bases are: INIS, Nuclear Science Abstracts, Nuclear Regulatory Library, Medline and Poltox. Some recourses for obtaining important documents are mentioned, e.g.: The British Library, HMSO and NTIS, as well as addresses of institutions, catalogues of publication on Internet, etc., which allow an easy access to the bibliography required. An evaluation of periodical publications by the Information Center is carried out, as well as information about users connected to the request of bibliographical searches and documents. (author) [es

  18. 75 FR 60157 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing...

    Science.gov (United States)

    2010-09-29

    ...-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing and Immediate..., 2010, Financial Industry Regulatory Authority, Inc. (``FINRA'') filed with the Securities and Exchange... information about the rulebook consolidation process, see Information Notice, March 12, 2008 (Rulebook...

  19. 76 FR 20759 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing...

    Science.gov (United States)

    2011-04-13

    ...-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing and Immediate..., 2011, Financial Industry Regulatory Authority, Inc. (``FINRA'') filed with the Securities and Exchange.... For more information about the rulebook consolidation process, see Information Notice, March 12, 2008...

  20. 76 FR 40412 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing...

    Science.gov (United States)

    2011-07-08

    ...-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing and Immediate..., Financial Industry Regulatory Authority, Inc. (``FINRA'') filed with the Securities and Exchange Commission... a more limited application by their terms. For more information about the rulebook consolidation...

  1. 75 FR 71164 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing...

    Science.gov (United States)

    2010-11-22

    ...-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing and Immediate..., 2010, Financial Industry Regulatory Authority, Inc. (``FINRA'') filed with the Securities and Exchange.... For more information about the rulebook consolidation process, see Information Notice, March 12, 2008...

  2. 76 FR 60106 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing...

    Science.gov (United States)

    2011-09-28

    ...-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing and Immediate... 14, 2011, Financial Industry Regulatory Authority, Inc. (``FINRA'') (f/k/a National Association of.... For more information about the rulebook consolidation process, see Information Notice, March 12, 2008...

  3. 75 FR 41254 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Order Approving a...

    Science.gov (United States)

    2010-07-15

    ... registered capacity, may work in other investment-related industries, such as financial planning, or may seek...-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Order Approving a Proposed Rule..., 2010, the Financial Industry Regulatory Authority, Inc. (``FINRA'') filed with the Securities and...

  4. 75 FR 21686 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing of...

    Science.gov (United States)

    2010-04-26

    ... to pay arbitration awards to remain in the securities industry presents regulatory risks and is...-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing of Proposed Rule... Regulatory Authority, Inc. (``FINRA'') filed with the Securities and Exchange Commission (``SEC'' or...

  5. Authority defied: need for cognitive closure influences regulatory control when resisting authority.

    Science.gov (United States)

    Damen, Tom G E; van Leeuwen, Matthijs L; Dijksterhuis, Ap; van Baaren, Rick B

    2014-08-01

    The present studies examined whether differences in need for cognitive closure (NCC) were related to differences in regulatory control when confronted with authority. In two studies, levels of regulatory control were measured when participants resisted (Study 1; N = 46) or prepared to resist the influence attempt of an authority figure (Study 2; N = 50). Results showed that resisting the influence attempt from a high-authority figure was more depleting for participants higher in NCC compared to individuals lower in NCC. However, when they were given instructions and time to prepare the act of resistance, individuals high in NCC actually showed an increase in regulatory control. Authority is usually viewed as a general principle of influence; however, the present studies suggest that there are individual differences that influence how people may experience interactions with authorities. © 2013 Wiley Periodicals, Inc.

  6. The process of regulatory authorization. A report by the CRPPH expert group on the regulatory application of Authorization (EGRA)

    International Nuclear Information System (INIS)

    2006-01-01

    Governments and regulatory authorities are responsible for the definition of regulatory controls or conditions, if any, that should be applied to radioactive sources or radiation exposure situations in order to protect the public, workers and the environment. Although countries use different policy and structural approaches to fulfill this responsibility, the recommendations of the International Commission on Radiological Protection (ICRP) are generally used as at least part of the basis for protection. Previously, the ICRP recommended the use of variable approaches to protection. New ICRP recommendations are proposing a single, conceptually simple and self-coherent approach to defining appropriate protection under all circumstances. While the ICRP has been reviewing the broad principles of protection, the NEA Committee on Radiation Protection and Public Health (CRPPH) has been focusing its efforts on how radiological protection could be better implemented by governments and/or regulatory authorities. To this end, the CRPPH has developed a concept that it calls ''the process of regulatory authorization''. It is described in detail in this report, and is intended to help regulatory authorities apply more transparently, coherently and simply the broad recommendations of the ICRP to the real-life business of radiological protection regulation and application. In developing this concept, the CRPPH recognizes the importance of an appropriate level of stakeholder involvement in the process. (author)

  7. 77 FR 7218 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing...

    Science.gov (United States)

    2012-02-10

    ...-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing and Immediate... thereunder,\\2\\ notice is hereby given that on January 30, 2012, Financial Industry Regulatory Authority, Inc.... For more information about the rulebook consolidation process, see Information Notice, March 12, 2008...

  8. 75 FR 59771 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Order Approving the...

    Science.gov (United States)

    2010-09-28

    ...-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Order Approving the Proposed Rule.... I. Introduction On July 27, 2010, the Financial Industry Regulatory Authority, Inc. (``FINRA'') (f/k... pertinent distribution-related information from its members in a timely fashion to facilitate its Regulation...

  9. 76 FR 50796 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing...

    Science.gov (United States)

    2011-08-16

    ...-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing and Immediate Effectiveness of Proposed Rule Change To Increase the Position Limit for Options on the Standard and Poor's... Financial Industry Regulatory Authority, Inc. (``FINRA'') filed with the Securities and Exchange Commission...

  10. Annual Report 2008. Nuclear Regulatory Authority

    International Nuclear Information System (INIS)

    2009-01-01

    The present Annual Report of Activities of the Nuclear Regulatory Authority (ARN), prepared regularly from the creation as independent institution, describes across four parts and seven annexes the activities developed by the organism during 2008. The main topic are: the organization and the activity of the ARN; the regulatory standards; the licensing and inspection of nuclear power plants and critical facilities; the emergency systems; the occupational surveillance; the environmental monitoring; improved organizational and budgetary developments. Also, this publication have annexes with the following content: regulatory documents; regulatory guides; measurement and evaluation of the drinking water of Ezeiza.

  11. Annual Report 2007. Nuclear Regulatory Authority

    International Nuclear Information System (INIS)

    2008-01-01

    The present Annual Report of Activities of the Nuclear Regulatory Authority (ARN), prepared regularly from the creation as independent institution, describes across tree parts and seven annexes the activities developed by the organism during 2007. The main topic are: the organization and the activity of the ARN; the regulatory standards; the licensing and inspection of nuclear power plants and critical facilities; the emergency systems; the occupational surveillance; the environmental monitoring; improved organizational. Also, this publication have annexes with the following content: regulatory documents; inspections to medical, industrial and training installations; regulatory guides; measurement and evaluation of the drinking water of Ezeiza.

  12. 76 FR 12380 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing of...

    Science.gov (United States)

    2011-03-07

    ...-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing of Amendment No. 1..., the Financial Industry Regulatory Authority, Inc. (``FINRA'') filed with the Securities and Exchange... information about the rulebook consolidation process, see Information Notice, March 12, 2008 (Rulebook...

  13. Annual Report 2009. Nuclear Regulatory Authority

    International Nuclear Information System (INIS)

    2010-01-01

    The present Annual Report of Activities of the Nuclear Regulatory Authority (ARN), prepared regularly from the creation as independent institution, describes across four parts and seven annexes the activities developed by the organism during 2009. The main topic are: the organization and the activity of the ARN; the regulatory standards; the licensing and inspection of nuclear power plants and critical facilities; the emergency systems; the environmental monitoring; the occupational surveillance; the training and the public information; improved organizational and budgetary developments. Also, this publication have annexes with the following content: regulatory documents; inspections to medical, industrial and training installations; regulatory guides; measurement and evaluation of the drinking water of Ezeiza.

  14. 75 FR 2897 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing of...

    Science.gov (United States)

    2010-01-19

    ...-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing of Proposed Rule... hereby given that on December 23, 2009, Financial Industry Regulatory Authority, Inc. (``FINRA'') (f/k/a... consolidation process, see Information Notice, March 12, 2008 (Rulebook Consolidation Process). NASD Rule 2450...

  15. Romania - NPP PLiM Between Regulatory Requirement / Oversight and Operator Safety / Financial Interest

    International Nuclear Information System (INIS)

    Goicea, Lucian

    2012-01-01

    Cernavoda Unit 1 PLiM started in the first third of its design life, to develop as regulatory requirements of the components of standards and programmes and to benefit by earlier implementation of the measures for achieving maximum operating life. CNCAN regulatory present approach on the utility PLiM combines the regulatory requirements on management system, ageing management provisions of periodic safety review, detailed technical requirements of ageing programmes and different techniques focusing only on safety issues. (author)

  16. Independent regulatory authorities - a comparative study of European energy regulators

    International Nuclear Information System (INIS)

    Sander Johansen, K.; Holm Pedersen, L.; Moll Soerensen, E.

    2004-04-01

    Independent regulatory authorities are widely recommended as part of the institutional design of liberalised energy markets - not least by the European Commission. This report describes and compares the regulatory authorities for energy in the EU. Arguments for regulatory independence are presented and discussed, and an index is developed to measure the degree of conformance to theories of regulatory independence. It is established that the main pattern of variation is that countries, which formerly had strong state-owned companies, have chosen to create regulatory authorities at state level with many institutional safeguards for independence. (au)

  17. Views from the japanese regulatory authority

    International Nuclear Information System (INIS)

    Aoyama, S.

    2004-01-01

    The legislation system for regulation of radioisotope in Japan was established in 1957. The system has been revised gradually since its establishment. Major amendments of the law were made in 1988 on the basis of ICRP Publication 26 and in 2000 on the basis of Publication 60. Main principles provided in the publication have been already introduced into the law. However, some concepts proposed in the recommendations are still under discussion. The current status of implementation of the ICRP recommendations in the Japanese regulatory system is summarised. Views from the regulatory authority of Japan on the points to be improved in the current system of radiological protection are presented. (author)

  18. Annual Report 2010. Nuclear Regulatory Authority

    International Nuclear Information System (INIS)

    2010-01-01

    The present Annual Report of Activities of the Nuclear Regulatory Authority (ARN), prepared regularly from the creation as independent institution, describes across six chapters and seven annexes the activities developed by the organism during 2010. The main topic are: institutional issues; regulatory guides and standards; argentinean nuclear regulatory system; quality assurance of the ARN; the institutional communications; the licensing and inspection of nuclear power plants and critical facilities; the emergency systems; the safeguards and the physical protection; the environmental control; the institutional relations; the training and the public information. Also, this publication have annexes with the following content: the regulatory framework; regulatory documents; inspections to medical, industrial and training installations; measurement and evaluation of the drinking water of Ezeiza; international expert's report on the application of the international standards of radiological protection of the public in the zone of the Ezeiza Atomic Center; ethical code

  19. Annual Report 2011. Nuclear Regulatory Authority

    International Nuclear Information System (INIS)

    2011-01-01

    The present Annual Report of Activities of the Nuclear Regulatory Authority (ARN), prepared regularly from the creation as independent institution, describes across six chapters and seven annexes the activities developed by the organism during 2011. The main topic are: institutional issues; regulatory guides and standards; argentinean nuclear regulatory system; quality assurance of the ARN; the institutional communications; the licensing and inspection of nuclear power plants and critical facilities; the emergency systems; the safeguards and the physical protection; the environmental control; the institutional relations; the training and the public information. Also, this publication have annexes with the following content: the regulatory framework; regulatory documents; inspections to medical, industrial and training installations; measurement and evaluation of the drinking water of Ezeiza; international expert's report on the application of the international standards of radiological protection of the public in the zone of the Ezeiza Atomic Center; ethical code

  20. Authority Defied : Need for Cognitive Closure Influences Regulatory Control When Resisting Authority

    NARCIS (Netherlands)

    Damen, Tom G. E.; van Leeuwen, Matthijs L.; Dijksterhuis, Ap; van Baaren, Rick B.

    The present studies examined whether differences in need for cognitive closure (NCC) were related to differences in regulatory control when confronted with authority. In two studies, levels of regulatory control were measured when participants resisted (Study 1; N = 46) or prepared to resist the

  1. Authority Defied: Need for Cognitive Closure Influences Regulatory Control When Resisting Authority

    NARCIS (Netherlands)

    Damen, T.G.E.; Leeuwen, M.L. van; Dijksterhuis, A.J.; Baaren, R.B. van

    2014-01-01

    The present studies examined whether differences in need for cognitive closure (NCC) were related to differences in regulatory control when confronted with authority. In two studies, levels of regulatory control were measured when participants resisted (Study 1; N = 46) or prepared to resist the

  2. Management systems for regulatory authorities

    International Nuclear Information System (INIS)

    Mpandanyama, Rujeko Lynette

    2015-02-01

    For a regulatory body to fulfil its statutory obligations, there is need to develop and implement a regulatory management system that has the necessary arrangements for achieving and maintaining high quality performance in regulating the safety of nuclear and radiation facilities under its authority. Hence, the regulatory management system needs to fully integrate the human resources, processes and physical resources of the organization. This study sought to provide an understanding of the concept, principles, policies and fundamentals of management systems as they relate to regulatory systems in the field of radiation protection and to make appropriate recommendations to ensure that an effective management system exists for the control of ionizing radiation and radiation sources and addresses all relevant stakeholders in Zimbabwe. A comparative analysis was done on the current management status and the ideal management system, which led to the identification of the gaps existing. The main key that was found to be of significance was lack of linkages between processes and management tools within the institution. (au)

  3. Risk acceptance criteria of the Nuclear Regulatory Authority

    International Nuclear Information System (INIS)

    Felizia, Eduardo R.

    2005-01-01

    This report describes some of the regulatory and control functions legally conferred upon the Argentine Nuclear Regulatory Authority concerning radiological risks, as well as a critical analysis of the radiological risk acceptance criteria contained in the Argentine regulatory system. A summary of the application of regulatory standards AR 3.1.3. - 'Radiological criteria related to accidents in nuclear power reactors' and AR 4.1.3. - 'Radiological criteria related to accidents in research reactors' to concrete cases is made, while the favourable and unfavourable aspects of the risk acceptance criteria are discussed. The conclusion is that the Argentine regulatory system contains adequate radiological risk acceptance criteria, that the latter are consistent with the radiological protection principles applicable to man and that, for the moment, there is no need to perform any modifications that would broaden the conceptual framework on which such criteria are based. (author) [es

  4. Towards medicines regulatory authorities' quality performance improvement: value for public health.

    Science.gov (United States)

    Pejović, Gordana; Filipović, Jovan; Tasić, Ljiljana; Marinković, Valentina

    2016-01-01

    The purpose of this article is to explore the possibility of implementing total quality management (TQM) principles in national medicines regulatory authorities in Europe to achieve all public health objectives. Bearing in mind that medicines regulation is a governmental function that serves societal objectives to protect and promote public health, measuring the effective achievement of quality objectives related to public health is of utmost importance. A generic TQM model for meeting public health objectives was developed and was tested on 10 European national medicines regulatory authorities with different regulatory performances. Participating national medicines regulatory authorities recognised all TQM factors of the proposed model in implemented systems with different degrees of understanding. An analysis of responses was performed within the framework of two established criteria-the regulatory authority's category and size. The value of the paper is twofold. First, the new generic TQM model proposes to integrate four public health objectives with six TQM factors. Second, national medicines regulatory authorities were analysed as public organisations and health authorities to develop a proper tool for assessing their regulatory performance. The paper emphasises the importance of designing an adequate approach to performance measurement of quality management systems in medicines regulatory authorities that will support their public service missions. Copyright © 2014 John Wiley & Sons, Ltd.

  5. 78 FR 54502 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing of...

    Science.gov (United States)

    2013-09-04

    ...-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing of a Proposed Rule... Authority, Inc. (``FINRA'') filed with the Securities and Exchange Commission (``SEC'' or ``Commission... or manipulative motivation for the trading activity at issue.\\4\\ Specifically, proposed Supplementary...

  6. Safety and regulatory requirements of nuclear power plants

    International Nuclear Information System (INIS)

    Kumar, S.V.; Bhardwaj, S.A.

    2000-01-01

    A pre-requisite for a nuclear power program in any country is well established national safety and regulatory requirements. These have evolved for nuclear power plants in India with participation of the regulatory body, utility, research and development (R and D) organizations and educational institutions. Prevailing international practices provided a useful base to develop those applicable to specific system designs for nuclear power plants in India. Their effectiveness has been demonstrated in planned activities of building up the nuclear power program as well as with unplanned activities, like those due to safety related incidents etc. (author)

  7. Safety culture competition - expectations of a regulatory authority

    International Nuclear Information System (INIS)

    Keil, D.; Gloeckle, W.

    2000-01-01

    The accident at the Chernobyl nuclear power station on April 26, 1986 influenced the development of reactor safety and promulgated two basic concepts especially in Germany. On the one hand, extensive measures of in-plant accident management have greatly reduced the so-called residual risk. On the other hand, a comprehensive safety approach has been initiated which comprises the nuclear power plant as a system together with people, technology, and organization and also includes safety culture. In a modern regulatory concept based on the dynamic development of safety, the authority's classical regulatory function of controlling is supplemented by the objective of promoting safety. While preserving the division of responsibilities between the regulatory authority and plant operators, the authority uses 'constructive critical dialog' as a tool to enhance safety. Besides the regulatory assessment of safety culture on the basis of indications or indicators, also the continuous promotion of safety culture in a dialog with plant operators is seen as one of the duties of a regulatory authority. Continued efforts are necessary to maintain the high level of safety culture in German nuclear power plants. Operators are expected to establish a safety management which assigns top priority to safety issues, and which pursues the goal of supervising and promoting safety culture. Developments on the deregulated electricity markets must not lead to safety aspects ranking second to economic aspects. Moreover, also under changed boundary conditions, only the safe operation of nuclear power plants ensures economic viability. (orig.) [de

  8. 75 FR 27606 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing...

    Science.gov (United States)

    2010-05-17

    ...-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing and Immediate...\\ and Rule 19b-4 thereunder,\\2\\ notice is hereby given that on April 27, 2010, the Financial Industry... restated following the formation of FINRA through the consolidation of NASD and the member regulatory...

  9. Nuclear Regulatory Authority of the Slovak Republic. Annual Report 2015

    International Nuclear Information System (INIS)

    2016-01-01

    A brief account of activities carried out by the Nuclear Regulatory Authority of the Slovak Republic (UJD SR) in 2015 is presented. These activities are reported under the headings: Foreword by the Chairperson; (1) Legislative activities; (2) Regulatory Activities; (3) Safety of nuclear installations; (4) Nuclear Materials; (5) Competence of the building authority; (6) Emergency planning and preparedness; (7) International activities; (8) Public relations; (9) Nuclear Regulatory Authority of the Slovak Republic; (10) Annexes; (11) Abbreviations.

  10. Nuclear Regulatory Authority of the Slovak Republic. Annual Report 2016

    International Nuclear Information System (INIS)

    2017-01-01

    A brief account of activities carried out by the Nuclear Regulatory Authority of the Slovak Republic (UJD SR) in 2016 is presented. These activities are reported under the headings: Foreword by the Chairperson; (1) Legislative activities; (2) Regulatory Activities; (3) Nuclear safety of nuclear installations; (4) Nuclear Materials; (5) Competence of the building authority; (6) Emergency planning and preparedness; (7) International activities; (8) Public relations; (9) Nuclear Regulatory Authority of the Slovak Republic; (10) Annexes; (11) Abbreviations.

  11. Nuclear Regulatory Authority of the Slovak Republic. Annual Report 2013

    International Nuclear Information System (INIS)

    2014-04-01

    A brief account of activities carried out by the Nuclear Regulatory Authority of the Slovak Republic (UJD SR) in 2013 is presented. These activities are reported under the headings: Foreword by the Chairperson; (1) Legislative activities; (2) Regulatory Activities; (3) Nuclear safety of nuclear power plants; (4) Nuclear Materials in SR; (5) Building Authority; (6) Emergency planning and preparedness; (7) International activities; (8) Public communication; (9) Nuclear Regulatory Authority of the Slovak Republic; (10) Annexes; (11) (12) Abbreviations.

  12. 12 CFR 567.2 - Minimum regulatory capital requirement.

    Science.gov (United States)

    2010-01-01

    ... 12 Banks and Banking 5 2010-01-01 2010-01-01 false Minimum regulatory capital requirement. 567.2... Regulatory Capital Requirements § 567.2 Minimum regulatory capital requirement. (a) To meet its regulatory capital requirement a savings association must satisfy each of the following capital standards: (1) Risk...

  13. 75 FR 53998 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing...

    Science.gov (United States)

    2010-09-02

    ... characteristics and risks of security futures. \\6\\ 15 U.S.C. 78o-3(b)(6). B. Self-Regulatory Organization's...-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing and Immediate Effectiveness of Proposed Rule Change To Amend the Security Futures Risk Disclosure Statement August 27, 2010...

  14. An evaluation model for the definition of regulatory requirements on spent fuel pool cooling systems

    International Nuclear Information System (INIS)

    Izquierdo, J.M.

    1979-01-01

    A calculation model is presented for establishing regulatory requirements in the SFPCS System. The major design factors, regulatory and design limits and key parameters are discussed. A regulatory position for internal use is proposed. Finally, associated problems and experience are presented. (author)

  15. Grand Gulf-prioritization of regulatory requirements

    International Nuclear Information System (INIS)

    Meisner, M.J.

    1993-01-01

    As cost pressures mount, Grand Gulf nuclear station (GGNS) is relying increasingly on various prioritization approaches to implement, modify, eliminate, or defer regulatory requirements. Regulatory requirements can be prioritized through the use of three measures: (1) safety (or risk) significance; (2) cost; and (3) public policy (or political) significance. This paper summarizes GGNS' efforts to implement solutions to regulatory issues using these three prioritization schemes to preserve a balance between cost and safety benefit

  16. Challenges in developing TSO to provide technical support in nuclear safety and security to Pakistan Nuclear Regulatory Authority

    International Nuclear Information System (INIS)

    Mallick, Shahid A.; Sherwani, Uzman Habib; Mehdi, M. Ammar

    2010-01-01

    This paper highlights the needs for the establishment of a technical support organization (TSO) in Pakistan Nuclear Regulatory Authority (PNRA), challenges faced during its development, application of training need assessment required for the competency development of its technical manpower and difficulties encountered after its evolution. Key issues addressed include recruitment of technical manpower and enhancing their competencies, acquisition of proper tools required for safety review and assessment, development of a sustainable education and training program consistent with the best international practices and taking the measures to get confidence of the regulatory body. (author)

  17. Role of cooperation activities for capacity building of Romanian Regulatory Authority (CNCAN)

    International Nuclear Information System (INIS)

    Biro, L.; Ciurea-Ercau, C.

    2010-01-01

    With a slow but active nuclear development program of sector since 1980, Romanian regulatory authority had to permanently adapt to the changes in national and international environment in order ensure continuously increase of capacity building and effectiveness, commensurate with the growing nuclear sector. Limited human resources available at the national level put the Romanian Regulatory Authority in the position of building the Technical Support Organization as part of its on organization. International cooperation played an important role in capacity building of Romanian regulatory body and providing necessary assistance in performing regulatory activities or support in development of regulatory framework. Fellowships and technical visits, workshops and training courses provided through IAEA TC at national or regional level, technical assistance provided by European Commission (EC) through PHARE Projects, all provided valuable contribution in assuring training of regulatory staff and development of proper regulatory framework in Romania. Therefore, Romanian Regulatory Authority is putting a strong accent on strengthening and promoting international cooperation through IAEA Technical Cooperation Programme, Molls between regulatory bodies, as one of the key elements in supporting capacity building of regulatory authorities in countries having small or embarking on nuclear power program. Building networks between training centers and research facilities and establishments of regional training centers represent one of the future viable options in preserving knowledge in nuclear field. (author)

  18. 75 FR 80556 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing...

    Science.gov (United States)

    2010-12-22

    ...-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing and Immediate... Rule 19b-4 thereunder,\\2\\ notice is hereby given that on December 13, 2010, Financial Industry... application by their terms. For more information about the rulebook consolidation process, see Information...

  19. 75 FR 43588 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Order Approving a...

    Science.gov (United States)

    2010-07-26

    ...-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Order Approving a Proposed Rule... FINRA Rule 4320 in the Consolidated FINRA Rulebook July 20, 2010. On May 21, 2010, the Financial... application by their terms. For more information about the rulebook consolidation process, see Information...

  20. Design and development of an informatics management system as a support for the Regulatory Authority in the Republic of Cuba

    International Nuclear Information System (INIS)

    Valdes Ramos, Maryzury; Prendes Alonso, Miguel; Jova Sed, Luis

    2008-01-01

    The regulatory activity in the country is carried out by the National Center for Nuclear Safety (CNSN) according to the international recommendations. To develop this, CNSN is supported by the Center for Radiation Protection and Hygiene (CPHR) which it's in charged of guaranteeing the technical scientific support for this activity. These centers have been working in the last years in the design and development of a computing tool that allows the management of all important information, which should be controlled by the Regulatory Authority. The authorization processes of the practices and the inspection program require the use, register and evaluation of an important volume of information that grows as the number of practices and facilities are increases. Consequently the systematizing of this information needs an automated management system. The objective of this work is to show the level of automation reached by the National Regulatory Authority using RASSYN program. This program allows an efficient management of the information related to the radiation sources nationwide, the practices ascribed to these sources, the personnel involved in these practices and the dose received, the equipment measuring and detecting of radiations, the generated waste, the occurred radiological incidents, the conditions and requisites of the granted authorizations and the results of the inspection program, among others. The possibilities of RASSYN system to process the information given by the users and the ones produced by the regulatory authority are described. The automatic generation of the annual inspections plan, according to the previously defined criteria and the system of alerts on the state of fulfillment of radiological protection requirements make RASSYN a useful tool to optimize the functioning of the regulatory system. The versatility of the statistical reports allows to guarantees not only the requirements of the regulatory authority but also the expectations coming

  1. 76 FR 67236 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing...

    Science.gov (United States)

    2011-10-31

    ... a foreign financial institution, and as part of the corporate control transaction, the foreign... subsidiaries, both of which are U.S. non-broker-dealer financial institutions, and as part of the corporate...-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing and Immediate...

  2. 75 FR 29793 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing...

    Science.gov (United States)

    2010-05-27

    ...-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing and Immediate... (``Act'') \\1\\ and Rule 19b-4 thereunder,\\2\\ notice is hereby given that on May 4, 2010, Financial.... For more information about the rulebook consolidation process, see Information Notice, March 12, 2008...

  3. 77 FR 38694 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing...

    Science.gov (United States)

    2012-06-28

    ... matrix will be an effective means of assessing related fees. For instance, the proposed fee structure...-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing and Immediate... Organization's Statement of the Terms of the Substance of the Proposed Rule Change FINRA is proposing to amend...

  4. Regulatory requirements of the integrated technology demonstration program, Savannah River Site (U)

    International Nuclear Information System (INIS)

    Bergren, C.L.

    1992-01-01

    The integrated demonstration program at the Savannah River Site (SRS) involves demonstration, testing and evaluation of new characterization, monitoring, drilling and remediation technologies for soils and groundwater impacted by organic solvent contamination. The regulatory success of the demonstration program has developed as a result of open communications between the regulators and the technical teams involved. This open dialogue is an attempt to allow timely completion of applied environmental restoration demonstrations while meeting all applicable regulatory requirements. Simultaneous processing of multiple regulatory documents (satisfying RCRA, CERCLA, NEPA and various state regulations) has streamlined the overall permitting process. Public involvement is achieved as various regulatory documents are advertised for public comment consistent with the site's community relations plan. The SRS integrated demonstration has been permitted and endorsed by regulatory agencies, including the Environmental Protection Agency (EPA) and the South Carolina Department of Health and Environmental Control. EPA headquarters and regional offices are involved in DOE's integrated Demonstration Program. This relationship allows for rapid regulatory acceptance while reducing federal funding and time requirements. (author)

  5. 78 FR 68893 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing...

    Science.gov (United States)

    2013-11-15

    ... that the size of the BBO equals the minimum quote size. Number of market makers actively quoting...-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing and Immediate Effectiveness of a Proposed Rule Change To Extend the Tier Size Pilot of FINRA Rule 6433 (Minimum Quotation Size...

  6. Below regulatory concern standards: The limits of state and local authority

    International Nuclear Information System (INIS)

    Silverman, D.J.

    1990-01-01

    The paper discusses: (1) the scope of the Nuclear Regulatory Commission's authority to develop and implement below regulatory concern or BRC standards; and (2) the limitations on the legal authority of states and local governments to create impediments to full implementation of such standards. The paper demonstrates that the NRC is acting well within its statutory authority in developing BRC regulations and guidelines, and that the ability of state and local governments to impede generators' use of those regulations and guidelines on the basis of legal or regulatory initiatives is substantially circumscribed. While some generators may be reluctant, as a result of political factors, to utilize BRC standards, the decision whether or not to use such standards should not be made without careful consideration of the applicable legal and regulatory limitations on state and local authority

  7. 76 FR 63969 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing of...

    Science.gov (United States)

    2011-10-14

    ...-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing of Amendment No. 1 to Proposed Rule Change To Adopt FINRA Rule 2231 (Customer Account Statements) in the Consolidated... Account Statements) in the Consolidated FINRA Rulebook (``Notice''). The Notice contained incorrect...

  8. Competent authority regulatory control of the transport of radioactive material

    International Nuclear Information System (INIS)

    1987-04-01

    The purpose of this guide is to assist competent authorities in regulating the transport of radioactive materials and to assist users of transport regulations in their interactions with competent authorities. The guide should assist specifically those countries which are establishing their regulatory framework and further assist countries with established procedures to harmonize their application and implementation of the IAEA Regulations. This guide specifically covers various aspects of the competent authority implementation of the IAEA Regulations for the Safe Transport of Radioactive Material. In addition, physical protection and safeguards control of the transport of nuclear materials as well as third party liability aspects are briefly discussed. This is because they have to be taken into account in overall transport regulatory activities, especially when establishing the regulatory framework

  9. The value and benefits of the International Conference on Harmonisation to drug regulatory authorities: advancing harmonization for better public health.

    Science.gov (United States)

    Molzon, J A; Giaquinto, A; Lindstrom, L; Tominaga, T; Ward, M; Doerr, P; Hunt, L; Rago, L

    2011-04-01

    The International Conference on Harmonisation (ICH) is an unparalleled undertaking, which has brought together drug regulatory authorities and pharmaceutical trade associations from Europe, Japan, and the United States, to discuss the scientific and technical aspects of medical product registration. Launched in 1990, the value and benefits of ICH to regulators are being realized. ICH has harmonized submission requirements and created a harmonized submission format that is relieving both companies and regulatory authorities of the burdens of assembling and reviewing separate submissions for each region. As more countries embrace ICH guidelines, we anticipate additional benefits, including the promotion of good review practices and, ultimately, a common regulatory language that will facilitate further interactions among global drug regulatory authorities.

  10. 78 FR 69732 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing of...

    Science.gov (United States)

    2013-11-20

    ...-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing of a Proposed Rule Change To Amend FINRA Rule 8312 (FINRA BrokerCheck Disclosure) To Include Information About Members and Their Associated Persons of Any Registered National Securities Exchange That Uses the CRD System for...

  11. The Slovak nuclear regulatory authority and start-up of the Mochovce NPP

    International Nuclear Information System (INIS)

    Seliga, M.; Micankova, J.

    2000-01-01

    A major element of providing information is the demonstration that the area of nuclear energy uses has its binding rules in the Slovak Republic and the observance thereof is controlled by the state through an independent institution Slovak Nuclear Regulatory Authority (UJD). As early as 1995 were laid on the UJD the foundations of the concept of broadly keeping the public informed on UJD activity and the safety of nuclear installations by opening the UJD Information Centre that provides by its activity communications with the public and mass media, which is instrumental in creating in the public a favourable picture of the independent state nuclear regulation. Clear communication policy is the key to credibility and is based on perceptions which give ride to varying levels of confidence. It has been consistently found in opinion research that credibility is the single most powerful persuasive force. Public communication programmes are the principal currency for the Regulatory Authority to inform the public on issues like costs, benefit requirements and risks

  12. NRPA develops regulatory cooperation with Central Asian authorities for nuclear safety and radiation protection

    International Nuclear Information System (INIS)

    2009-01-01

    With the support of the Norwegian Ministry of Foreign Affairs, the NRPA has initiated a regional regulatory cooperation project with Kazakhstan, Kyrgyzstan and Tajikistan to improve regulations on nuclear safety, radiation protection and environmental issues, and assist the countries in re mediating radioactively contaminated sites. There is a critical lack in the regulatory basis for carrying out such remediation work, including a lack of relevant radiation and environmental safety norms and standards, licensing procedures and requirements for monitoring, as well as expertise to transform such a basis into practice. (Author)

  13. 77 FR 23770 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing of...

    Science.gov (United States)

    2012-04-20

    ...: The financial markets as a whole should benefit from [limit order display] because the price discovery... revised tier sizes and corresponding liquidity minimum amounts are in the best interest of the market for...-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing of Amendment No. 1...

  14. Independent regulatory authorities in European electricity market

    DEFF Research Database (Denmark)

    Olsen, Ole Jess; Larsen, Anders; Sørensen, Eva Moll

    2006-01-01

    Liberalisation of the electricity market has taken place in most European countries within the last decade. It is considered a precondition of successful liberalisation to establish so-called independent regulatory authorities. In this article, we compare the status and practice of them in 16...

  15. Dose constraint for Industrial gammagraphy developed by regulatory authorities

    International Nuclear Information System (INIS)

    Salinas Mariaca, Rodrigo

    2008-01-01

    Aware that the dose limitation established by the Basic Safety Standards, is one of the radiation protection requirements necessary but not sufficient; and also aware that given the characteristics of the different practices and the culture of security already achieved in such practices, the workers occupationally exposed are far below from the respective limits. It becomes imperative to improve and exploit another of the requirements established by the referred standards, which is the Dose Constraint. This job takes as a basis the dose history having in the Bolivian Authority in nuclear issues, referred to the practices related to Nuclear Gauges, Well Logging, Radiotherapy and Industrial Gammagraphy (practices considered dangerous). This analysis is intended to be the pivot for the remainder practices and had as its goal, the establishment of a specific dose constraint value. The dose constraint suggested for every practices studied, were determined considering the percentile 95 and with the logic that if that 95% are able to achieve certain values of effective dose, the other 5% should be able to adapt their working conditions in order to decrease their doses. The spread of this work is intended not only aware, to other regulatory bodies to achieve a symbiosis between the different requirements of the Standard, but basically emphasize the fact that it is not convenient let the requirement of dose constraint exclusively in the hands of the regulated institutions and associated workers; making it, very subjective among those institutions according to their analysis (many times with no statistical support). Furthermore these dose constraint values should be determined previously to a new practice authorization or failing shortly after its implementation. (author)

  16. An overview of the licensing approach of the South African nuclear regulatory authority

    International Nuclear Information System (INIS)

    Clapisson, G.A.; Hill, T.F.; Henderson, N.R.; Keenan, N.H.; Metcalf, P.E.; Mysenkov, A.

    1997-01-01

    This paper describes the approach adopted by the South African Nuclear Regulatory Authority, the Council for Nuclear Safety (CNS) in licensing nuclear installations in South Africa. An introduction to the current South African legislation and the CNS philosophy pertaining to the licensing of nuclear installations is discussed. A typical process for granting a nuclear licence is then presented. The risk assessment process, which is used to verify compliance with the fundamental safety standards and to establish licensing requirements for a specific nuclear installation, is discussed. Based on the outcome of this assessment process, conditions of licence are set down. The generic content of a nuclear licence and mechanisms to ensure ongoing compliance with the risk criteria are presented. The regulatory process discussed in this paper, based on such a fundamental approach, may be adapted to any type of nuclear installation taking into account plant specific designs and characteristics. (author)

  17. Licensing evaluation of CANDU-PHW nuclear power plants relative to U.S. regulatory requirements

    International Nuclear Information System (INIS)

    Erp, J.B. van

    1978-01-01

    Differences between the U.S. and Canadian approach to safety and licensing are discussed. U.S. regulatory requirements are evaluated as regards their applicability to CANDU-PHW reactors; vice-versa the CANDU-PHW reactor is evaluated with respect to current Regulatory Requirements and Guides. A number of design modifications are proposed to be incorporated into the CANDU-PHW reactor in order to facilitate its introduction into the U.S. These modifications are proposed solely for the purpose of maintaining consistency within the current U.S. regulatory system and not out of a need to improve the safety of current-design CANDU-PHW nuclear power plants. A number of issues are identified which still require resolution. Most of these issues are concerned with design areas not (yet) covered by the ASME code. (author)

  18. Development of safety-related regulatory requirements for nuclear power in developing countries. Key issue paper no. 4

    International Nuclear Information System (INIS)

    Han, K.I.

    2000-01-01

    In implementing a national nuclear power program, balanced regulatory requirements are necessary to ensure nuclear safety and cost competitive nuclear power, and to help gain public acceptance. However, this is difficult due to the technology-intensive nature of the nuclear regulatory requirements, the need to reflect evolving technology and the need for cooperation among multidisciplinary technical groups. This paper suggests approaches to development of balanced nuclear regulatory requirements in developing countries related to nuclear power plant safety, radiation protection and radioactive waste management along with key technical regulatory issues. It does not deal with economic or market regulation of electric utilities using nuclear power. It suggests that national regulatory requirements be developed using IAEA safety recommendations as guidelines and safety requirements of the supplier country as a main reference after careful planning, manpower buildup and thorough study of international and supplier country's regulations. Regulation making is not recommended before experienced manpower has been accumulated. With an option that the supplier country's regulations may be used in the interim, the lack of complete national regulatory requirements should not deter introduction of nuclear power in developing countries. (author)

  19. Knowledge management in the Argentine Nuclear Regulatory Authority

    International Nuclear Information System (INIS)

    Chahab, Martin

    2006-01-01

    In 2006, the Argentine Nuclear Regulatory Authority has initiated a regulatory knowledge management process to face the loss of knowledge resulting from retiring experts, the generation gap, and the existing need to train new human resources. A number of projects have been started together with the technical assistance of the National Public Administration Institute to preserve knowledge and render it explicit for the coming generations. These projects include 'The History of the Expert's Learning Process' in which the majority of the most critical experts have been interviewed so far. The results of this project help envision a training structure and prospective projects. An Internet Site has also been created on the Intranet in order to render knowledge explicit and facilitate the tools for knowledge management initiatives. Furthermore, ARN's knowledge map project has also been started. (author) [es

  20. Nuclear Regulatory Authority of the Slovak Republic. Annual Report 1999

    International Nuclear Information System (INIS)

    Seliga, M.

    2000-01-01

    A brief account of activities carried out by the Nuclear Regulatory Authority of the Slovak Republic in 1999 is presented. These activities are reported under the headings: (1) Foreword; (2) Mission of the Nuclear Regulatory Authority; (3) Legislation; (4) Assessment and inspection of safety at nuclear installations; (4) Safety analyses; (5) Nuclear materials; (6) Radioactive waste; (7) Quality assurance; (8) Personnel qualification and training; (9) Emergency preparedness; (10) International co-operation; (11) Public information; (12) Conclusions; (13) Appendices: Economic and personnel data; Abbreviations; The International nuclear event scales - INES

  1. Guidance and methods for satisfying low specific activity material and surface contaminated object regulatory requirements

    International Nuclear Information System (INIS)

    Pope, R.B.; Shappert, L.B.; Michelhaugh, R.D.; Boyle, R.W.; Easton, E.P.; Coodk, J.R.

    1998-01-01

    The U.S. Department of Transportation (DOT) and the U.S. Nuclear Regulatory Commission (NRC) have prepared a comprehensive set of draft guidance for shippers and inspectors to use when applying the newly imposed regulatory requirements for low specific activity (LSA) material and surface contaminated objects (SCOs). These requirements represent significant departures in some areas from the manner in which these materials and objects were regulated by the earlier versions of the regulations. The proper interpretation and application of the regulatory criteria can require a fairly complex set of decisions be made. To assist those trying these regulatory requirements, a detailed set of logic-flow diagrams representing decisions related to multiple factors were prepared and included in the draft report for comment on Categorizing and Transporting Low Specific Activity Materials and Surface Contaminated Objects, (DOT/NRC, 1997). These logic-flow diagrams, as developed, are specific to the U.S. regulations, but were readily adaptable to the IAEA regulations. The diagrams have been modified accordingly and tied directly to specific paragraphs in IAEA Safety Series No. 6. This paper provides the logic-flow diagrams adapted in the IAEA regulations, and demonstrated how these diagrams can be used to assist consignors and inspectors in assessing compliance of shipments with the LSA material and SCO regulatory requirements. (authors)

  2. Cooperation between Norwegian and Russian Regulatory Authorities: NRPA and Rostechnadzor

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2011-07-01

    The Norwegian Radiation Protection Authority has been cooperating with the Federal Environmental, Industrial and Nuclear Supervision Service, Rostechnadzor, on the upgrading of the regulatory framework for the safe decommissioning and disposal of Radioisotope Thermoelectric Generators. (Author)

  3. Regulatory requirements and quality assurance of radiation monitoring instruments

    International Nuclear Information System (INIS)

    Narasimharao, K.L.; Sharma, Ranjit

    2005-01-01

    The successful utilisation of radiation sources in the fields of medicine and industry requires the accurate measurement of activity, exposure rate and dose. Many varieties of instruments are in use for measurement of these parameters and new ones are being developed. The criteria for the design of the radiation monitoring instrument include the type and intensity of the radiation, purpose of measurement and ruggedness of the instrument. Quality and reliability of radiation monitoring instruments ensure that individuals are adequately protected. Accuracy, response time and ruggedness are required to be as per the approved/ prescribed guidelines. Regulatory authorities outline the design and performance criteria for radiation monitoring instruments and prescribe the recommendations of international agencies such as IAEA, ICRU and ISO for radiological measurement assurance programme. National Standards Laboratories all over the world prescribe procedures for calibration of various radiation monitoring instruments. The instruments should be calibrated as per these guidelines and should be traceable to national standards. The calibration traceable to national/ international standards and documentation as well as limits stipulated by the competent authority ensures the expected performance of the instrument. (author)

  4. Independent regulatory authorities in European electricity markets

    International Nuclear Information System (INIS)

    Larsen, Anders; Pedersen, Lene Holm; Sorensen, Eva Moll; Olsen, Ole Jess

    2006-01-01

    Liberalisation of the electricity market has taken place in most European countries within the last decade. It is considered a precondition of successful liberalisation to establish so-called independent regulatory authorities. In this article, we compare the status and practice of them in 16 European countries, and discuss the relationship between the organisation of the regulation and the market outcome

  5. Technical Memory 2010. Nuclear Regulatory Authority

    International Nuclear Information System (INIS)

    2010-01-01

    The technical memory 2010 of the Nuclear Regulatory Authority of Argentine Republic, compile the papers published in the subject on radiation protection and nuclear safety presented in journals, technical reports, congress or meetings of these subjects by the ARN personnel during 2010. In this edition the documents are presented on: environmental protection; safety transport of radioactive materials; regulations; licensing of medical installations; biological radiation effects; therapeutic uses of ionizing radiation and radioprotection of patients; internal dosimetry; radioactive waste management [es

  6. Technical Memory 2011. Nuclear Regulatory Authority

    International Nuclear Information System (INIS)

    2011-01-01

    The technical memory 2011 of the Nuclear Regulatory Authority of Argentine Republic, compile the papers published in the subject on radiation protection and nuclear safety presented in journals, technical reports, congress or meetings of these subjects by the ARN personnel during 2011. In this edition the documents are presented on: environmental protection; safety transport of radioactive materials; regulations; licensing of medical installations; biological radiation effects; therapeutic uses of ionizing radiation and radioprotection of patients; internal dosimetry; radioactive waste management [es

  7. Nuclear Regulatory Authority of the Slovak Republic. Annual Report 2000

    International Nuclear Information System (INIS)

    Seliga, M.

    2001-01-01

    A brief account of activities carried out by the Nuclear Regulatory Authority of the Slovak Republic in 2000 is presented. These activities are reported under the headings: (1) Foreword and organisation structure; (2) Mission of the Nuclear Regulatory Authority; (3) Legislation; (4) Assessment and inspection of nuclear installations; (5) Safety analyses; (6) Nuclear materials and physical protection of nuclear installations; (7) Radioactive waste; (8) Quality assurance; (9) Personnel qualification and training; (10) Emergency preparedness; (11) International co-operation; (12) Public information; (13) Personnel and economic data of the UJD; (14) Conclusion; (15) Attachments: Abbreviations; Radiation safety

  8. Regulatory requirements for the use of consumer products containing radioactive substances

    International Nuclear Information System (INIS)

    Mason, G.C.; Paynter, R.A.; Schmitt-Hannig, A.; Sztanyik, L.B.

    1996-01-01

    In almost 100 years since the discovery of radioactivity, the properties of radioactive materials have been exploited in products such as clocks and watches incorporating luminous paint which are freely available to members of the public. Over time, regulatory authorities have felt it necessary to apply some degree of control to the supply and use of such products in order to protect public health. In many areas of radiation protection, national authorities take note of international recommendations when developing national standards, but the existing detailed guidance of the International Atomic Energy Agency (IAEA) for consumer products is incomplete and out of date. Recently, a thorough revision of the International Basic Safety Standards (BSS) has occurred, which has prompted a review and revision of the related guidance published by the IAEA. A draft Guide on Regulatory Requirements for the Use of Consumer Products Containing Radioactive Substances has now been completed and is currently under review within the IAEA's system for development of documents in its Safety Series of publications. (author)

  9. Romanian regulatory requirements on nuclear field specific education needs

    International Nuclear Information System (INIS)

    Biro, L.; Velicu, O.

    2004-01-01

    This work is intended as a general presentation of the educational system and research field, with reference to nuclear sciences, and the legal system, with reference to requirements established by the regulatory body for the professional qualification and periodic training of personnel involved in different activities in the nuclear field. Thus, part 2 and 3 of the work present only public information regarding the education in nuclear sciences and nuclear research in Romania; in part 4 the CNCAN requirements for the personnel training, specific to nuclear activities are slightly detailed; part 5 consists of few words about the public information activities in Romania; and part 6 tries to draw a conclusion. (authors)

  10. Public Notice of Nuclear Regulatory Authority of the Slovak Republic No. 46/2006 Coll. on specific material and facilities that are under supervision of the Nuclear Regulatory Authority of the Slovak Republic

    International Nuclear Information System (INIS)

    Vaclav, J.

    2006-01-01

    The Public Notice defines the list of specific material and facilities which are under supervision of the Nuclear Regulatory Authority of the Slovak Republic with taking into consideration the requirements in accordance with the new atomic Act and other material. The national competence's have been practically divided in the Public Notice. These competence's concern the execution of directly binding EU rule and the Public Notice gives the details about the dividing of specific materials

  11. 77 FR 24748 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Order Granting...

    Science.gov (United States)

    2012-04-25

    ... Traded TBA April 18, 2012. I. Introduction On March 1, 2012, the Financial Industry Regulatory Authority... (``MBS'') traded ``to be announced'' or ``TBA.'' The proposed rule change was published for comment in... TBA (``MBS TBA'') are a specific type of Asset-Backed Security.\\6\\ FINRA has proposed to amend its...

  12. 24 CFR 266.505 - Regulatory agreement requirements.

    Science.gov (United States)

    2010-04-01

    ... force for the duration of the insured mortgage and note or bond. The Regulatory Agreement must include a... Project Management and Servicing § 266.505 Regulatory agreement requirements. (a) General. (1) The HFA... payments due under the mortgage and note/bond. (2) Where necessary, establish a sinking fund for future...

  13. Technical Memory 2008. Nuclear Regulatory Authority

    International Nuclear Information System (INIS)

    2011-01-01

    The technical memory 2008 of the Nuclear Regulatory Authority of Argentine Republic, compile the papers published in the subject on radiation protection and nuclear safety, and presented in journals, technical reports, congress or meetings of these specialties by personnel of the mentioned institution during 2008. In this edition the documents are presented on: environmental protection; transport of radioactive materials; regulations; research reactors and nuclear power plants; biological radiation effects; therapeutic uses of ionizing radiation and radioprotection of patients; internal dosimetry; physical dosimetry; knowledge management; radioactive waste management. [es

  14. A National Regulatory Authority set up in a developing country: case of Mali

    International Nuclear Information System (INIS)

    Kone, Nagantie

    2008-01-01

    Full text: The Republic of Mali is member of the International Atomic Energy Agency since 1961. Of since the creation of the IAEA, some African countries are members. The technical cooperation with the Agency started in the years 1975. Through that cooperation, many pacific uses of nuclear techniques have been introduced, then developed at different levels in many socio- economic domains as medicine, agriculture, research, and so on. That development of nuclear techniques use has occurred without legislation at all or in some limited cases with part of the legislation of the colonizing country), in a precise field (like radiography in medicine). Later the need of regulatory infrastructure implementation started. That implementation has followed several ways in the different African countries. Also, it started earlier in countries which had advanced activities in nuclear techniques and very later in others. Most if not all of these infrastructure (say regulatory board) were created by the greatest users of the nuclear techniques, the Ministry of Health in most cases or Energy Commission for Countries having a research reactor. After the years 90, the Agency has developed new vision in the implementation of Regulatory Authorities. The new innovation was: 1-) Development of Regulatory Authority with independent statute (decisions and finance); 2-) Assuming post graduate training in developing countries to come other the lack of human resources. That new strategy of the IAEA has facilitated the apparition and development of several new regulatory authorities. We are going to develop here the progress done by one of these new regulatory authorities, through five years being. (author)

  15. Nuclear Regulatory Authority Act, 2015 (Act 895)

    International Nuclear Information System (INIS)

    2015-04-01

    An Act to establish a Nuclear Regulatory Authority in Ghana. This Act provides for the regulation and management of activities and practices for the peaceful use of nuclear material or energy, and to provide for the protection of persons and the environment against the harmful effects of radiation; and to ensure the effective implementation of the country’s international obligations and for related matters. This Act replaced the Radiation Protection Instrument, of 1993 (LI 1559).

  16. Lessons learned from the Fukushima Dai-ichi accident and responses in NRA regulatory requirements

    International Nuclear Information System (INIS)

    Fuketa, Toyoshi

    2014-01-01

    The author would like to present significant lessons learned from the TEPCO’s Fukushima Dai-ichi accident and responses in regulatory requirements developed by the Nuclear Regulation Authority for power-producing light water reactors. The presentation will cover prevention of structures, systems and components failures, measures to prevent common cause failures, prevention of core damage, mitigation of severe accidents, emergency preparedness, continuous improvement of safety, use of probabilistic risk assessment, and post-accident regulation on the Fukushima Dai-ichi. (author)

  17. Review of regulatory requirements for digital I and C systems

    Energy Technology Data Exchange (ETDEWEB)

    Kwon, Kee Choon; Lee, Cheol Kwon; Lee, Jang Soo [and others

    2001-11-01

    This work analyzed and summarized systematically various regulatory requirements that are necessary to develop digital nuclear instrumentation and control (I and C) systems, especially safety systems. The requirements are categorized into system, hardware, software, and quality assurance aspects. This report provides the explanations of terms and abbreviations to help readers understand. Furthermore, appendices of this report summarize the code and standards corresponding to each principal regulatory requirement. The hierarchical structure of regulatory requirements has Nuclear Energy Laws, Enforcement Regulations of Nuclear Energy Laws, and Notifications of Ministry of Science and Technology as utmost level requirements [In case of the US, 10 CFR 50 Appendix A, 10 CFR 50 Appendix B, 10 CFR 50.55a(h), 10 CFR 50.49, etc.]. The requirements include the Draft Regulatory Guidelines for Digital I and C Systems [In case of the US, Standard Review Plan (NUREG-0800), Regulatory Guide, Branch Technical Position (BTP)], KEPIC as standards [In case of the US, IEEE Standards, IEC Standards, ISA, Military Standard, etc.], and various reports issued by Korea Institute of Nuclear Safety [In case of the US, NUREG reports, EPRI reports, etc.]. This report can be referred for the development of safety grade control equipment, plant protection system, and engineered safety feature actuation system.

  18. Review of regulatory requirements for digital I and C systems

    International Nuclear Information System (INIS)

    Kwon, Kee Choon; Lee, Cheol Kwon; Lee, Jang Soo

    2001-11-01

    This work analyzed and summarized systematically various regulatory requirements that are necessary to develop digital nuclear instrumentation and control (I and C) systems, especially safety systems. The requirements are categorized into system, hardware, software, and quality assurance aspects. This report provides the explanations of terms and abbreviations to help readers understand. Furthermore, appendices of this report summarize the code and standards corresponding to each principal regulatory requirement. The hierarchical structure of regulatory requirements has Nuclear Energy Laws, Enforcement Regulations of Nuclear Energy Laws, and Notifications of Ministry of Science and Technology as utmost level requirements [In case of the US, 10 CFR 50 Appendix A, 10 CFR 50 Appendix B, 10 CFR 50.55a(h), 10 CFR 50.49, etc.]. The requirements include the Draft Regulatory Guidelines for Digital I and C Systems [In case of the US, Standard Review Plan (NUREG-0800), Regulatory Guide, Branch Technical Position (BTP)], KEPIC as standards [In case of the US, IEEE Standards, IEC Standards, ISA, Military Standard, etc.], and various reports issued by Korea Institute of Nuclear Safety [In case of the US, NUREG reports, EPRI reports, etc.]. This report can be referred for the development of safety grade control equipment, plant protection system, and engineered safety feature actuation system

  19. Annual Report 2007. Nuclear Regulatory Authority; Informe Anual 2007. Autoridad Regulatoria Nuclear

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2008-07-01

    The present Annual Report of Activities of the Nuclear Regulatory Authority (ARN), prepared regularly from the creation as independent institution, describes across tree parts and seven annexes the activities developed by the organism during 2007. The main topic are: the organization and the activity of the ARN; the regulatory standards; the licensing and inspection of nuclear power plants and critical facilities; the emergency systems; the occupational surveillance; the environmental monitoring; improved organizational. Also, this publication have annexes with the following content: regulatory documents; inspections to medical, industrial and training installations; regulatory guides; measurement and evaluation of the drinking water of Ezeiza.

  20. Annual Report 2008. Nuclear Regulatory Authority; Informe Anual 2008. Autoridad Regulatoria Nuclear

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2009-07-01

    The present Annual Report of Activities of the Nuclear Regulatory Authority (ARN), prepared regularly from the creation as independent institution, describes across four parts and seven annexes the activities developed by the organism during 2008. The main topic are: the organization and the activity of the ARN; the regulatory standards; the licensing and inspection of nuclear power plants and critical facilities; the emergency systems; the occupational surveillance; the environmental monitoring; improved organizational and budgetary developments. Also, this publication have annexes with the following content: regulatory documents; regulatory guides; measurement and evaluation of the drinking water of Ezeiza.

  1. Regulatory capital requirements and bail in mechanisms

    NARCIS (Netherlands)

    Joosen, B.P.M.; Haentjens, M.; Wessels, B.

    2015-01-01

    With the introduction of the Capital Requirements Regulation (CRR) in the European Union, the qualitative requirements for bank regulatory capital have changed. These changes aim at implementing in Europe the Basel III principles for better bank capital that is able to absorb losses of banks,

  2. Preparation of safety regulatory requirements for new technology like digital system

    International Nuclear Information System (INIS)

    2012-01-01

    The current regulatory requirements on digital instrumentation and control system have been reviewed by JNES, considering international trend discussed in DICWG of MDEP. MDEP DICWG held in OECD/NEA gives the opportunity to identify the convergence of applicable standards. The working group's activities include: identifying and prioritising the member countries' challenges, practices, and needs regarding standards and regulatory guidance on digital instrumentation and control; identifying areas of importance and needs for convergence of existing standards and guidance or development of new standards; sharing of information; and identifying common positions among the member countries for areas of particular importance and need. The DICWG drafted common positions on specific issues which are based on the existing standards, national regulatory guidance, best practices, and group inputs using an agreed process and framework. The following two general common positions are discussed and to be issued in this fiscal year. Verification and Validation throughout the life cycle of safety systems using digital computers. The Impact of Cyber Security Features on Digital I and C Safety Systems. (author)

  3. Assessment of Quality Assurance Measures for Radioactive Material Transport Packages not Requiring Competent Authority Design Approval - 13282

    International Nuclear Information System (INIS)

    Komann, Steffen; Groeke, Carsten; Droste, Bernhard

    2013-01-01

    The majority of transports of radioactive materials are carried out in packages which don't need a package design approval by a competent authority. Low-active radioactive materials are transported in such packages e.g. in the medical and pharmaceutical industry and in the nuclear industry as well. Decommissioning of NPP's leads to a strong demand for packages to transport low and middle active radioactive waste. According to IAEA regulations the 'non-competent authority approved package types' are the Excepted Packages and the Industrial Packages of Type IP-1, IP-2 and IP-3 and packages of Type A. For these types of packages an assessment by the competent authority is required for the quality assurance measures for the design, manufacture, testing, documentation, use, maintenance and inspection (IAEA SSR 6, Chap. 306). In general a compliance audit of the manufacturer of the packaging is required during this assessment procedure. Their regulatory level in the IAEA regulations is not comparable with the 'regulatory density' for packages requiring competent authority package design approval. Practices in different countries lead to different approaches within the assessment of the quality assurance measures in the management system as well as in the quality assurance program of a special package design. To use the package or packaging in a safe manner and in compliance with the regulations a management system for each phase of the life of the package or packaging is necessary. The relevant IAEA-SSR6 chap. 801 requires documentary verification by the consignor concerning package compliance with the requirements. (authors)

  4. Assessment of Quality Assurance Measures for Radioactive Material Transport Packages not Requiring Competent Authority Design Approval - 13282

    Energy Technology Data Exchange (ETDEWEB)

    Komann, Steffen; Groeke, Carsten; Droste, Bernhard [BAM Federal Institute for Materials Research and Testing, Unter den Eichen 44-46, 12203 Berlin (Germany)

    2013-07-01

    The majority of transports of radioactive materials are carried out in packages which don't need a package design approval by a competent authority. Low-active radioactive materials are transported in such packages e.g. in the medical and pharmaceutical industry and in the nuclear industry as well. Decommissioning of NPP's leads to a strong demand for packages to transport low and middle active radioactive waste. According to IAEA regulations the 'non-competent authority approved package types' are the Excepted Packages and the Industrial Packages of Type IP-1, IP-2 and IP-3 and packages of Type A. For these types of packages an assessment by the competent authority is required for the quality assurance measures for the design, manufacture, testing, documentation, use, maintenance and inspection (IAEA SSR 6, Chap. 306). In general a compliance audit of the manufacturer of the packaging is required during this assessment procedure. Their regulatory level in the IAEA regulations is not comparable with the 'regulatory density' for packages requiring competent authority package design approval. Practices in different countries lead to different approaches within the assessment of the quality assurance measures in the management system as well as in the quality assurance program of a special package design. To use the package or packaging in a safe manner and in compliance with the regulations a management system for each phase of the life of the package or packaging is necessary. The relevant IAEA-SSR6 chap. 801 requires documentary verification by the consignor concerning package compliance with the requirements. (authors)

  5. Annual Report 2009. Nuclear Regulatory Authority; Informe Anual 2009. Autoridad Regulatoria Nuclear

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2010-07-01

    The present Annual Report of Activities of the Nuclear Regulatory Authority (ARN), prepared regularly from the creation as independent institution, describes across four parts and seven annexes the activities developed by the organism during 2009. The main topic are: the organization and the activity of the ARN; the regulatory standards; the licensing and inspection of nuclear power plants and critical facilities; the emergency systems; the environmental monitoring; the occupational surveillance; the training and the public information; improved organizational and budgetary developments. Also, this publication have annexes with the following content: regulatory documents; inspections to medical, industrial and training installations; regulatory guides; measurement and evaluation of the drinking water of Ezeiza.

  6. The Report on Activities of the Nuclear Regulatory Authority of the Slovak Republic. Annual Report 2012

    International Nuclear Information System (INIS)

    2013-04-01

    A brief account of activities carried out by the Nuclear Regulatory Authority of the Slovak Republic (UJD SR) in 2012 is presented. These activities are reported under the headings: Foreword; (1) Legislative activities; (2) Regulatory Activities; (3) Nuclear safety of nuclear power plants; (4) Stress tests on the nuclear power plants; (5) Nuclear Materials in SR; (6) Building Authority; (7) Emergency planning and preparedness; (8) International activities; (9) Public communication; (10) Nuclear Regulatory Authority of the Slovak Republic; (11) Attachments; (12) Abbreviations used.

  7. Quality manual. Nuclear Regulatory Authority of the Slovak Republic

    International Nuclear Information System (INIS)

    2006-03-01

    This quality manual of the Nuclear Regulatory Authority of the Slovak Republic (UJD) is presented. Basic characteristics of the UJD, Quality manual operative control, and Quality management system (QMS) are described. Management responsibility, Processes realization, Measurement, analysis (assessment) and improvement of the quality management system, Cancellation provision as well as abbreviations used in the Quality Manual are presented.

  8. A framework for regulatory requirements and industry standards for new nuclear power plants

    International Nuclear Information System (INIS)

    Duran, Felicia A.; Camp, Allen L.; Apostolakis, George E.; Golay, Michael W.

    2000-01-01

    This paper summarizes the development of a framework for risk-based regulation and design for new nuclear power plants. Probabilistic risk assessment methods and a rationalist approach to defense in depth are used to develop a framework that can be applied to identify systematically the regulations and standards required to maintain the desired level of safety and reliability. By implementing such a framework, it is expected that the resulting body of requirements will provide a regulatory environment that will ensure protection of the public, will eliminate the burden of requirements that do not contribute significantly to safety, and thereby will improve the market competitiveness of new plants. (author)

  9. Revolution in New Zealand's Radiation Protection Legislation and Evolution and Continual Improvement in its Regulatory Authority

    International Nuclear Information System (INIS)

    Smyth, V.

    2004-01-01

    The safe use of ionising radiation in New Zealand is regulated by the Radiation Protection Act 1965 and the Radiation Protection Regulations 1982, which are administered by the National Radiation Laboratory (NRL). This legislation is now out of date and creates difficulties for New Zealand in meeting international standards of radiation safety and security, and complying with obligations under international treaties. These problems can be addressed by new legislation that would change the powers and functions of the regulatory authority, and change the responsibilities of licensees under the Act. However historically NRL has provided radiation services as well as acting as regulatory authority. This has the potential to create a conflict of interest in making regulatory judgements. Over the preceding 50 years NRL has undergone an evolution that has resulted in a clarification of the regulatory functions, and development of a quality management system that is now accredited to ISO standards. This paper presents a possible structure of a new Act, and discusses the role of quality management in maintaining the independence of regulatory authority. (Author)

  10. Preparation of safety regulatory requirements for new technology like digital system

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2013-08-15

    The current regulatory requirements on digital instrumentation and control system have been reviewed by JNES, considering international trend discussed in DICWG of MDEP. MDEP DICWG held in OECD/NEA gives the opportunity to identify the convergence of applicable standards. The working group's activities include: identifying and prioritising the member countries' challenges, practices, and needs regarding standards and regulatory guidance on digital instrumentation and control; identifying areas of importance and needs for convergence of existing standards and guidance or development of new standards; sharing of information; and identifying common positions among the member countries for areas of particular importance and need. The DICWG drafted common positions on specific issues which are based on the existing standards, national regulatory guidance, best practices, and group inputs using an agreed process and framework. The following four general common positions have been discussed in this fiscal year. The Treatment of Common Cause Failure Resulting from Software within Digital Safety Systems, The Treatment of Hardware Description Language(HDL) Programmed Devices for Use in Nuclear Safety System, Factory Acceptance Test and Site Acceptance Test, The Use of Automatic Tests to Perform Surveilance for Digital Systems. (author)

  11. Provincial nuclear regulatory authority?: The case of the province of Cordoba

    International Nuclear Information System (INIS)

    Martin, Hugo; Ocana, F.; Scoles, R.

    1999-01-01

    The evolution of social and political events in the province of Cordoba after the Law 8157 of 1992, that establishes the provincial nuclear policy, are analysed as well as the recent sanction and veto of the Law 8775, which creates the provincial Nuclear Regulatory Authority. The authors conclude that is necessary and convenient to enforce provincial nuclear regulations and controls

  12. Role of the Nuclear Regulatory Authority in the final disposal of radioactive wastes in Argentina

    International Nuclear Information System (INIS)

    Petraitis, E.J.; Siraky, G.; Novo, R.G.

    1998-01-01

    This paper describes briefly the legislative and regulatory framework in which the final disposal of radioactive wastes is carried out in Argentina. The activities of the Nuclear Regulatory Authority (ARN) and the applied approaches in relation to inspection of facilities, safety assessments of associated systems and collaboration in the matter with international agencies are also exposed. (author) [es

  13. Safety Committees for Argentinean Research Reactor - Regulatory Issues

    International Nuclear Information System (INIS)

    Perrin, Carlos D.

    2009-01-01

    In the field of radiological and nuclear safety, the Nuclear Regulatory Authority (ARN) of Argentina controls three research reactors and three critical assemblies, by means of evaluations, audits and inspections, in order to ensure the fulfillment of the requirements established in the Licenses, in the Regulatory Standards and in the Mandatory Documentation in general. From the Nuclear Regulatory Authority's point of view, within the general process of research reactors safety management, the Operational Organization self verification of radiological and nuclear safety plays an outstanding role. In this aspect the ARN has established specific requirements in the Regulatory Standards, in the Operation Licenses and in the Operational Limits and Conditions. These requirements include the figure of different safety committees, which act as reviewers or advisers in diverse situations. This paper describes the main characteristics of the committees, their function, scope and the regulatory documents where the requirements are included. (author)

  14. Improving nuclear regulatory effectiveness

    International Nuclear Information System (INIS)

    2001-01-01

    Ensuring that nuclear installations are operated and maintained in such a way that their impact on public health and safety is as low as reasonably practicable has been and will continue to be the cornerstone of nuclear regulation. In the past, nuclear incidents provided the main impetus for regulatory change. Today, economic factors, deregulation, technological advancements, government oversight and the general requirements for openness and accountability are leading regulatory bodies to review their effectiveness. In addition, seeking to enhance the present level of nuclear safety by continuously improving the effectiveness of regulatory bodies is seen as one of the ways to strengthen public confidence in the regulatory systems. This report covers the basic concepts underlying nuclear regulatory effectiveness, advances being made and future requirements. The intended audience is primarily nuclear safety regulators, but government authorities, nuclear power plant operators and the general public may also be interested. (author)

  15. Nuclear Regulatory Authority of the Slovak Republic. Annual Report 2002

    International Nuclear Information System (INIS)

    Seliga, M.

    2003-04-01

    A brief account of activities carried out by the Nuclear Regulatory Authority of the Slovak Republic in 2002 is presented. These activities are reported under the headings: (1) Foreword; (2) Legislation; (3) Assessment and inspection of nuclear installations; (4) Safety analyses; (5) Nuclear materials and physical protection of nuclear installations; (6) Radioactive waste; (7) Quality assurance; (8) Personnel qualification and training; (9) Emergency preparedness; (10) International co-operation; (11) Public information; (12) Personnel and economy data; Appendix: Abbreviations; Special Enclosure: 10. Years of the Nuclear Regulation Authority of the Slovak Republic. An independent and professional state regulatory authority supervising the nuclear safety is one of prerequisites of the safe operation of nuclear installations in each country. In the Slovak Republic this role has been fulfilled by the Nuclear Regulatory Authority (UJD) since 1993. The main mission of UJD set down by the law is to guarantee for the Slovak citizens as well as for international society that the nuclear power on the territory of the Slovak Republic will be used exclusively for peaceful purposes and that the Slovak nuclear installations are designed, constructed, operated and decommissioned in compliance with relevant legal documents. The mission of UJD is also to tender the operation of nuclear installations so that their operation would not jeopardise the nuclear power plant staff or public and would not cause detrimental effects to the environment or property. UJD prepares laws or comments to the laws and issues decrees in the area of its competencies, issues authorisations for operators of nuclear facilities, reviews and evaluates the safety documentation of nuclear installations, performs the inspections at nuclear installations comparing whether the legal requirements are fulfilled and whether the real status of nuclear installations and their operation is or not in compliance with

  16. Regulatory requirements for desalination plant coupled with nuclear reactor plant

    International Nuclear Information System (INIS)

    Yune, Young Gill; Kim, Woong Sik; Jo, Jong Chull; Kim, Hho Jung; Song, Jae Myung

    2005-01-01

    A small-to-medium sized reactor has been developed for multi-purposes such as seawater desalination, ship propulsion, and district heating since early 1990s in Korea. Now, the construction of its scaled-down research reactor, equipped with a seawater desalination plant, is planned to demonstrate the safety and performance of the design of the multi-purpose reactor. And the licensing application of the research reactor is expected in the near future. Therefore, a development of regulatory requirements/guides for a desalination plant coupled with a nuclear reactor plant is necessary for the preparation of the forthcoming licensing review of the research reactor. In this paper, the following contents are presented: the design of the desalination plant, domestic and foreign regulatory requirements relevant to desalination plants, and a draft of regulatory requirements/guides for a desalination plant coupled with a nuclear reactor plant

  17. WIPP Waste Characterization: Implementing Regulatory Requirements in the Real World

    International Nuclear Information System (INIS)

    Cooper Wayman, J.D.; Goldstein, J.D.

    1999-01-01

    It is imperative to ensure compliance of the Waste Isolation Pilot Project (WIPP) with applicable statutory and regulatory requirements. In particular, compliance with the waste characterization requirements of the Resource Conservation and Recovery Act (RCRA) and its implementing regulation found at 40 CFR Parts 262,264 and 265 for hazardous and mixed wastes, as well as those of the Atomic Energy Act of 1954, as amended, the Reorganization Plan No. 3 of 1970, the Nuclear Waste Policy Act of 1982, as amended, and the WIPP Land Withdrawal Act, as amended, and their implementing regulations found at 40 CFR Parts 191 and 194 for non-mixed radioactive wastes, are often difficult to ensure at the operational level. For example, where a regulation may limit a waste to a certain concentration, this concentration may be difficult to measure. For example, does the definition of transuranic waste (TRU) as 100 nCi/grain of alpha-emitting transuranic isotopes per gram of waste mean that the radioassay of a waste must show a reading of 100 plus the sampling and measurement error for the waste to be a TRU waste? Although the use of acceptable knowledge to characterize waste is authorized by statute, regulation and DOE Orders, its implementation is similarly beset with difficulty. When is a document or documents sufficient to constitute acceptable knowledge? What standard can be used to determine if knowledge is acceptable for waste characterization purposes? The inherent conflict between waste characterization regulatory requirements and their implementation in the real world, and the resolution of this conflict, will be discussed

  18. ILK statement about the regulatory authorities' perception of operators' self-assessment of safety culture

    International Nuclear Information System (INIS)

    2005-01-01

    Over the past few years, German licensing and supervisory authorities have devoted increasing attention to safety management and safety culture issues. At present, German plant operators are introducing systems for self-assessment of the safety culture in their plants, such as the Safety Culture Assessment System developed by VGB Power Tech (VGB-SBS). In its statement, the International Committee on Nuclear Technology (ILK) addresses an effective approach of the authorities in evaluating the self-assessment of safety culture conducted by operators. ILK proposes a total of ten recommendations for evaluating the self-assessment system of the operators by the authority. The regulatory authorities should see to it that the operators establish a self-assessment system for aspects of organization and personnel, and use it continuously. The measures derived from this self-assessment by the operators, and the reasons underlying them, should be discussed with the authorities. In addition to the operators, also the regulatory authorities and the technical expert organizations commissioned by them should carry out self-assessments of their respective supervisory activities, taking into account also special events, such as changes in government, and develop appropriate programs of measures to be taken. In evaluating safety culture, the regulatory authorities should strive to support the activities of operators in improving their safety culture. A spirit of mutual confidence and cooperation should exist between operators and authorities. The recommendations expressed in the statement deliberately leave room for detailed implementation by the parties concerned. (orig.)

  19. Regulatory authority of the Rocky Mountain states for low-level radioactive waste packaging and transportation

    International Nuclear Information System (INIS)

    Whitman, M.; Tate, P.

    1983-07-01

    The newly-formed Rocky Mountain Low-Level Radioactive Waste Compact is an interstate agreement for the management of low-level radioactive waste (LLW). Eligible members of the compact are Arizona, Colorado, Nevada, New Mexico, Utah, and Wyoming. Each state must ratify the compact within its legislature for the compact to become effective in that state and to make that state a full-fledged member of the compact. By so adopting the compact, each state agrees to the terms and conditions specified therein. Among those terms and conditions are provisions requiring each member state to adopt and enforce procedures requiring low-level waste shipments originating within its borders and destined for a regional facility to conform to packaging and transportation requirements and regulations. These procedures are to include periodic inspections of packaging and shipping practices, periodic inspections of waste containers while in the custody of carriers and appropriate enforcement actions for violations. To carry out this responsibility, each state must have an adequate statutory and regulatory inspection and enforcement authority to ensure the safe transportation of low-level radioactive waste. Three states in the compact region, Arizona, Utah and Wyoming, have incorporated the Department of Transportation regulations in their entirety, and have no published rules and regulations of their own. The other states in the compact, Colorado, Nevada and New Mexico all have separate rules and regulations that incorporate the DOT regulations. A brief description of the regulatory requirements of each state is presented

  20. Needs, requirements and challenges for technical support to nuclear safety authority

    International Nuclear Information System (INIS)

    Madonna, A.; Orsini, G.

    2010-01-01

    To face the very broad range of technical matters on which the regulatory and licensing activity are based, and related research and development activity, the Nuclear Safety Authorities (NSA) may need to rely upon external technical and scientific support. In providing technical support to NSA, the experience shows, from one side, the importance to have technical support organizations (TSO) with recognized competence, independence and appropriate regulatory view, and from the other side, the importance to have within the NSAs well developed management and technical capability to address, coordinate and use the results of the external technical support. Retaining the NSA the full responsibility for the final decision. Under which conditions and modus operandi the external support shall be provided in order to comply with requirements of being independent, competent and timely provided, fulfilling the administrative procedures, is the subject of attention and consideration of TSO function today. The Italian regulatory body is currently going to be institutionally re-established according to new law approved in 2009 /1/ and it needs to be resourced and fully organized with necessary capacities in the nearest future. The perspective of a new nuclear program, recently launched by the government, with significant incoming tasks for regulation and licensing, against the existing limited resources, let foresee a substantial potential need for technical support and advice. ITER-Consult (Ltd), created in 2003 in Italy, has well developed capabilities to provide independent technical evaluation and support to NSAs, to maintain safety culture and updated knowledge, to transfer know how and to establish international cooperation and networking. This mission is guided assuming as values the independence, the professional competence, the transparency, the credibility and the establishment of respectful relationship with the partners. Challenges exist for funding and operational

  1. The knowledge management and the Library of the Nuclear Regulatory Authority

    International Nuclear Information System (INIS)

    Chahab, Martin; Carregado, Maria A.

    2009-01-01

    Since 2006 the Nuclear Regulatory Authority (ARN) of Argentina has implemented knowledge management activities to face the retirement of many of its scientific and technical members. The purpose of these actions are to preserve the knowledge and information of these personnel and to make it available for both, present and future generations. The ARN libraries play an important role in the accomplishment of these objectives through the coordination and realization of different projects and activities. (author) [es

  2. Virtual private networks application in Nuclear Regulatory Authority of Argentina

    International Nuclear Information System (INIS)

    Glidewell, Donnie D.; Smartt, Heidi A.; Caskey, Susan A.; Bonino, Anibal D.; Perez, Adrian C.; Pardo, German R.; Vigile, Rodolfo S.; Krimer, Mario

    2004-01-01

    As the result of the existence of several regional delegations all over the country, a requirement was made to conform a secure data interchange structure. This would make possible the interconnection of these facilities and their communication with the Autoridad Regulatoria Nuclear (ARN) headquarters. The records these parts exchange are often of classified nature, including sensitive data by the local safeguards inspectors. On the other hand, the establishment of this network should simplify the access of authorized nuclear and radioactive materials users to the ARN databases, from remote sites and with significant trust levels. These requirements called for a network that should be not only private but also secure, providing data centralization and integrity assurance with a strict user control. The first proposal was to implement a point to point link between the installations. This proposal was deemed as economically not viable, and it had the disadvantage of not being easily reconfigurable. The availability of new technologies, and the accomplishment of the Action Sheet 11 under an agreement between Argentine Nuclear Regulatory Authority and the United States Department of Energy (DOE), opened a new path towards the resolution of this problem. By application of updated tunneling security protocols it was possible to project a manageable and secure network through the use of Virtual Private Networking (VPN) hardware. A first trial installation of this technology was implemented between ARN headquarters at Buenos Aires and the Southern Region Office at Bariloche, Argentina. This private net is at the moment under test, and it is planned to expand to more sites in this country, reaching for example to nuclear power plants. The Bariloche installation had some interesting peculiarities. The solutions proposed to them revealed to be very useful during the development of the network expansion plans, as they showed how to adapt the VPN technical requisites to the

  3. Development of Regulatory Technical Requirements for the Advanced Integral Type Research Reactor

    International Nuclear Information System (INIS)

    Jo, Jong Chull; Yune, Young Gill; Kim, Woong Sik; Kim, Hho Jung

    2004-01-01

    This paper presents the current status of the study on the development of regulatory technical requirements for the licensing review of an advanced integral type research reactor of which the license application is expected in a few years. According to the Atomic Energy Act of Korea, both research and education reactors are subject to the technical requirements for power reactors in the licensing review. But, some of the requirements may not be applicable or insufficient for the licensing reviews of reactors with unique design features. Thus it is necessary to identify which review topics or areas can not be addressed by the existing requirements and to develop the required ones newly or supplement appropriately. Through the study performed so far, it has been identified that the following requirements need to be developed newly for the licensing review of SMART-P: the use of proven technology, the interfacial facility, the non-safety systems, and the metallic fuels. The approach and basis for the development of each of the requirements are discussed. (authors)

  4. Preparation of safety regulatory requirements for new technology like digital system

    International Nuclear Information System (INIS)

    Ito, Juichiro; Takita, Masami

    2011-01-01

    The current regulatory requirements on digital instrumentation and control system have been reviewed by JNES, considering international trend discussed in DICWG (Digital Instrumentation and Control Working Group) of MDEP (Multinational Design Evaluation Program). MDEP DICWG held in OECD/NEA (Organisation for Economic Co-operation and Development/Nuclear Energy Agency) gives the opportunity to identify the convergence of applicable standards. The working group's activities include: identifying and prioritising the member countries' challenges, practices, and needs regarding standards and regulatory guidance regarding digital instrumentation and control; identifying areas of importance and needs for convergence of existing standards and guidance or development of new standards; sharing of information; and identifying common positions among the member countries for areas of particular importance and need. The DICWG drafted common positions on specific issues which are based on the existing standards, national regulatory guidance, best practices, and group inputs using an agreed upon process and framework. Five general common positions are under discussion in this fiscal year. Simplicity in Design, Software Common Cause Failures, Software Tools, Data communication, Verification and Validation throughout the life cycle of safety systems using digital computers. In addition, the technical evaluation of standards of the Japan Electric Association about digital system for safety was made to support NISA (Nuclear and Industrial Safety Agency). (author)

  5. Radiological and administrative criteria and procedures required by the Radiation Protection Ordinance for exemption from regulatory control

    International Nuclear Information System (INIS)

    Birkholz, W.

    2000-01-01

    The system of required radioactivity measurements and limits as well as methods, based on the 10 μSv concept, constitutes the regulatory regime for exemption of radioactive waste materials from regulatory control according to atomic energy law. The methods and administrative procedures are suitable both for smaller amounts of materials, such as those resulting from the use of radioactive substances in scientific research and medical applications, and for the large waste volumes emanating from the dismantling of nuclear installations. The system provided for in the Radiation Protection Ordinance ensures harmonized administrative action of all public authorities involved. (orig./CB) [de

  6. Regulatory document R-104, Regulatory objectives, requirements and guidelines for the disposal of radioactive wastes - long-term aspects

    International Nuclear Information System (INIS)

    1987-01-01

    The purpose and scope of this document is to present the regulatory basis for judging the long-term acceptability of radioactive waste disposal options. The basic objectives of radioactive waste disposal are given as are the regulatory requirements to be satisfied. (NEA)

  7. Development of regulatory requirements/guides for desalination unit coupled with nuclear plant

    International Nuclear Information System (INIS)

    Jo, Jong Chull; Yune, Young Gill; Kim, Woong Sik

    2005-10-01

    The basic design of System-integrated Modular Advanced Reactor (SMART), a small-to-medium sized integral type pressurized water reactor (PWR) with the capacity of 330MWth, has been developed in Korea. In order to demonstrate the safety and performance of the SMART design, 'Development Project of SMART-P (SMART-Pilot Plant)' has been being performed as one of the 'National Mid and Long-term Atomic Energy R and D Programs', which includes design, construction, and start-up operation of the SMART-P with the capacity of 65MWth, a 1/5 scaled-down design of the SMART. At the same time, a study on the development of regulatory requirements/guides for the desalination unit coupled with nuclear plant has been carried out by KINS in order to prepare for the forthcoming SMART-P licensing. The results of this study performed from August of 2002 to October of 2005 can be summarized as follows: (1) The general status of desalination technologies has been survey. (2) The design of the desalination plant coupled with the SMART-P has been investigated. (3) The regulatory requirements/guides relevant to a desalination unit coupled with a nuclear plant have been surveyed. (4) A direction on the development of domestic regulatory requirements/guides for a desalination unit has been established. (5) A draft of regulatory requirements/guides for a desalination unit has been developed. (6) Expert technical reviews have been performed for the draft regulatory requirements/guides for a desalination unit. The draft regulatory requirements/guides developed in this study will be finalized and can be applied directly to the licensing of the SMART-P and SMART. Furthermore, it will be also applied to the licensing of the desalination unit coupled with the nuclear plant

  8. The planning, construction, and operation of a radioactive waste storage facility for an Australian state radiation regulatory authority

    Energy Technology Data Exchange (ETDEWEB)

    Wallace, J.D.; Kleinschmidt, R.; Veevers, P. [Radiation Health, Queensland (Australia)

    1995-12-31

    Radiation regulatory authorities have a responsibility for the management of radioactive waste. This, more often than not, includes the collection and safe storage of radioactive sources in disused radiation devices and devices seized by the regulatory authority following an accident, abandonment or unauthorised use. The public aversion to all things radioactive, regardless of the safety controls, together with the Not In My Back Yard (NIMBY) syndrome combine to make the establishment of a radioactive materials store a near impossible task, despite the fact that such a facility is a fundamental tool for regulatory authorities to provide for the radiation safety of the public. In Queensland the successful completion and operational use of such a storage facility has taken a total of 8 years of concerted effort by the staff of the regulatory authority, the expenditure of over $2 million (AUS) not including regulatory staff costs and the cost of construction of an earlier separate facility. This paper is a summary of the major developments in the planning, construction and eventual operation of the facility including technical and administrative details, together with the lessons learned from the perspective of the overall project.

  9. Use of prioritization in meeting regulatory requirements

    International Nuclear Information System (INIS)

    Bowling, M.L.; Sommers, D.A.; Girvin, L.M.

    1993-01-01

    The use of prioritization in the allocation of resources is certainly not a new idea. However, the degree to which prioritization must now be used is much greater than ever before. In the past, utilities generally allocated the necessary resources to meet all regulatory requirements and commitments. Prioritization was then applied to the remaining nonregulatory but required needs. This approach to resource allocation is no longer appropriate for the current and projected economic and operating environment. Key reasons for this conclusion are discussed in this paper by staff from Virginia Power

  10. Development of guidance on applications of regulatory requirements for low specific activity materials and surface contaminated objects

    International Nuclear Information System (INIS)

    Pope, R.B.; Easton, E.P.; Shankman, S.F.; Boyle, R.W.

    1997-01-01

    In 1985, the International Atomic Energy Agency issued revised regulations for the safe transport of radioactive material. Significant among the changes were major revisions to requirements for Low Specific Activity (LSA) material and Surface Contaminated Objects (SCOs). In preparation for the adoption of these requirements into regulations in the United States, it became apparent that guidance on how to apply these requirements, clarifying technical uncertainties and ensuring proper implementation, would be needed both by the regulators and those regulated. Thus, the US Department of Transportation and the U.S. Nuclear Regulatory Commission, with the assistance of staff from Oak Ridge National Laboratory, are preparing regulatory guidance for LSA material and SCO transport. The guidance will present examples of acceptable methods for demonstrating compliance with the revised rules. Ideas being investigated for inclusion in the pending guidance are discussed in this paper. Under current plans, the guidance will be issued for public comment prior to final issue of the guidance in 1997. (Author)

  11. Regulation of Federal radioactive waste activities. Report to Congress on extending the Nuclear Regulatory Commission's licensing or regulatory authority to Federal radioactive waste storage and disposal activities

    International Nuclear Information System (INIS)

    1979-09-01

    The report contains two recommendations for extending the Commission's regulatory authority: (1) NRC licensing authority should be extended to cover all new DOE facilities for disposal of transuranic (TRU) waste and nondefense low-level waste. (2) A pilot program, focused on a few specific DOE waste management activities, should be established to test the feasibility of extending NRC regulatory authority on a consultative basis to DOE waste management activities not now covered by NRC's licensing authority or its extension as recommended in Recommendation 1

  12. The Nuclear Regulatory Authority of the Slovak Republic - information to the public

    International Nuclear Information System (INIS)

    Seliga, M.

    1998-01-01

    In this paper the communication programme in the Nuclear Regulatory Authority of the Slovak Republic (NRA SR), internal communication within NRA SR, handling the media, the media documents, the emergency preparedness and media as well as the activities of the NRA SR in last period are discussed

  13. Responsibilities of nuclear regulatory authority and overview of nuclear safety regulations in Slovakia

    International Nuclear Information System (INIS)

    Misak, J.

    1996-01-01

    The paper describes the organizational structure of the Nuclear Regulatory Authority of the Slovak Republic, its rights and duties, the status of nuclear legislation with emphasis on nuclear activities completely or partially covered, and licensing procedures

  14. Fuel utilization experience in Bohunice NPP and regulatory requirements for implementation of progressive fuel management strategies

    Energy Technology Data Exchange (ETDEWEB)

    Patenyi, V [Nuclear Regulatory Authority, Bratislava (Slovakia); Darilek, P; Majercik, J [Vyskumny Ustav Jadrovych Elektrarni, Trnava (Slovakia)

    1994-12-31

    The experience gained in fuel utilization and the basic requirements for fuel licensing in the Slovak NPPs is described. The original project of WWER-440 reactors supposes 3-year fuel cycle with cycle length of about 320 full power days (FPD). Since 1984 it was reduced to 290 FPD. Based on the experience of other countries, a 4-year fuel cycle utilization started in 1987. It is illustrated with data from the Bohunice NPP units. Among 504 fuel assemblies left for the fourth burnup cycle no leakage was observed. The mean burnup achieved in the different units varied from 33.1 to 38.5 Mwd/kg U. The new fuel assemblies used are different from the recent ones in construction, thermohydraulics, water-uranium ratio, enrichment and material design. To meet the safety criteria, regulatory requirements for exploitation of new fuel in WWER-440 were formulated by the Nuclear Regulatory Authority of Slovak Republic. 1 tab., 5 refs.

  15. Toward a functional definition of a "rare disease" for regulatory authorities and funding agencies.

    Science.gov (United States)

    Clarke, Joe T R; Coyle, Doug; Evans, Gerald; Martin, Janet; Winquist, Eric

    2014-12-01

    The designation of a disease as "rare" is associated with some substantial benefits for companies involved in new drug development, including expedited review by regulatory authorities and relaxed criteria for reimbursement. How "rare disease" is defined therefore has major financial implications, both for pharmaceutical companies and for insurers or public drug reimbursement programs. All existing definitions are based, somewhat arbitrarily, on disease incidence or prevalence. What is proposed here is a functional definition of rare based on an assessment of the feasibility of measuring the efficacy of a new treatment in conventional randomized controlled trials, to inform regulatory authorities and funding agencies charged with assessing new therapies being considered for public funding. It involves a five-step process, involving significant negotiations between patient advocacy groups, pharmaceutical companies, physicians, and public drug reimbursement programs, designed to establish the feasibility of carrying out a randomized controlled trial with sufficient statistical power to show a clinically significant treatment effect. The steps are as follows: 1) identification of a specific disease, including appropriate genetic definition; 2) identification of clinically relevant outcomes to evaluate efficacy; 3) establishment of the inherent variability of measurements of clinically relevant outcomes; 4) calculation of the sample size required to assess the efficacy of a new treatment with acceptable statistical power; and 5) estimation of the difficulty of recruiting an adequate sample size given the estimated prevalence or incidence of the disorder in the population and the inclusion criteria to be used. Copyright © 2014 International Society for Pharmacoeconomics and Outcomes Research (ISPOR). Published by Elsevier Inc. All rights reserved.

  16. Regulatory framework and safety requirements for new (gen III) reactors

    International Nuclear Information System (INIS)

    Mourlon, Sophie

    2014-01-01

    Sophie Mourlon, ASN Deputy General Director, described the international process to enhance safety between local safety authorities through organizations such as WENRA. Then she explained to the participants the regulatory issues for the next generation of NPPs

  17. Actions of the Cuban Nuclear Regulatory Authority in the adequate implementation of the legislation in matter of radiological protection

    International Nuclear Information System (INIS)

    Fornet R, O.M.; Guillen C, A.; Betancourt H, L.A.

    2006-01-01

    The effectiveness of the regulatory activity in matter of safety and radiological protection it depends in great measure of the practical implementation level of the legislation in this matter. In our country this objective has been achieved through the one continuous improvement of the Hierarchical System of Nuclear Regulation, the reconciliation with specialists and national experts in each matter during the elaboration of the legal documents; the popularization and gratuitous distribution of it approved; the precision in the validation conditions of the authorizations of those main precepts applicable to the practices; the legal foundation of the deficiencies evidenced in the regulatory inspections; the development of a Safety Culture; the realization of Annual Regulatory Conferences and mainly in the training of the personnel related with the safety. Also, the constant analysis on the part of the specialists of the Regulatory Authority of the grade of implementation of this legislation, it discussion in national and international events and the actions recommended in these works. As a result of this focus, it is considered that the Regulatory Authority has impacted appropriately in the implementation of this legislation. (Author)

  18. Nuclear Regulatory Authority of the Slovak Republic. Annual Report 2003

    International Nuclear Information System (INIS)

    Seliga, M.

    2004-04-01

    A brief account of activities carried out by the Nuclear Regulatory Authority of the Slovak Republic in 2003 is presented. These activities are reported under the headings: (1) Foreword; (2) Legislation; (3) Assessment and inspection of nuclear installations; (4) Safety analyses; (5) Nuclear materials and physical protection of nuclear installations; (6) Radioactive waste; (7) Quality assurance; (8) Personnel qualification and training; (9) Emergency preparedness; (10) International co-operation; (11) Public information; (12) Personnel and economy data; Appendix: Abbreviations; Radiation safety

  19. Internal communication within the Slovak Nuclear Regulatory Authority

    International Nuclear Information System (INIS)

    Seliga, Mojmir

    2000-01-01

    One of the primary objectives of the Slovak Nuclear Regulatory Authority (UJD) Public Relations Program is to make available to the public full and complete information on UJD activities to assist the public in making informed judgments regarding UJD activities. The primary means of keeping the public informed about the regulatory activities and programs of the UJD is through the news media. A central state administration body, the UJD provides on request within its province in particular information on operational safety of nuclear energy installations independently of those responsible for the nuclear programme, thereby allowing the public and the media to control data and information on nuclear installations. A major element of providing information is the demonstration that the area of nuclear energy uses has its binding rules in the Slovak Republic and the observance thereof is controlled by the state through an independent institution - UJD. As early as 1995 were laid on the UJD the foundations of the concept of broadly keeping the public informed on UJD activity and the safety of nuclear installations by opening the UJD Information Centre. Information Centre provides by its activity communications with the public and mass media, which is instrumental in creating in the public a favourable picture of the independent state nuclear regulation. Internal and external communications are equally important

  20. 47 CFR 25.102 - Station authorization required.

    Science.gov (United States)

    2010-10-01

    ... 47 Telecommunication 2 2010-10-01 2010-10-01 false Station authorization required. 25.102 Section 25.102 Telecommunication FEDERAL COMMUNICATIONS COMMISSION (CONTINUED) COMMON CARRIER SERVICES SATELLITE COMMUNICATIONS General § 25.102 Station authorization required. (a) No person shall use or operate...

  1. Regulatory and administrative requirements for practice of nuclear medicine in India

    International Nuclear Information System (INIS)

    Tandon, Pankaj

    1998-01-01

    In order to ensure safety of the patients, staff and public in the practice of nuclear medicine, including in-vivo diagnostic investigations, radionuclide therapy and in research using unsealed radioactive substances a number of administrative and regulatory procedures are adopted. The salient features of regulatory and administrative requirements for practice of nuclear medicine in India are discussed

  2. Communications in the Nuclear Regulatory Authority of the Slovakia

    International Nuclear Information System (INIS)

    Seliga, Mojmir

    1998-01-01

    Full text: The Nuclear Regulatory Authority of the Slovak Republic (UJD SR) as the state authority provides information related to its competence, namely information on safety operation of nuclear installations, independently from nuclear operators and it enables the public and media to examine information on nuclear facilities. The important aspect is proving that the nuclear energy in the Slovak Republic is due to obligatory rules acceptable and its operation is regulated by the State through the independent institution - UJD SR. UJD SR considers the whole area of public relations as essential component of its activity. UJD SR intends to serve the public true, systematic, qualified, understandable and independent information regarding nuclear safety of nuclear power plants, as well as regarding methods and results of UJD SR work. Communication on reactor incidents or more broadly on operational events at nuclear power plants represents a substantial part of public information- Generally, public information is considered as significant contribution to creation of confidence into the regulatory work. A communication programme must be tested in practice. Our communication programme is regularly evaluated in emergency exercises held at the UJD SR. Inviting journalists to participate in or observe the exercises has intensified this, or by having staff members simulate the mass media and the public. The communication means, tools and channels developed and enhanced during the recent years has increased the UJD SR's functional capability to carry out its information policy. However, communication cannot achieve its goals unless the receiver is willing to accept the message. If the receiver is suspicious about the sender's intentions, good communication is almost impossible. Maintaining the trust with the media and the public as well as increasing radiation and nuclear safety knowledge in the society is therefore essential. UJD SR communication and information activities

  3. Experts Complete IAEA Follow-up Review of Spanish Nuclear Regulatory Authority

    International Nuclear Information System (INIS)

    2011-01-01

    areas of inspection and public communication as a consequence of the lessons learned in 2008 from the event at the Asco Nuclear Power Plant; CSN's interactions at the highest level with licensees to discuss strategic planning and their investments in safety and human resources; and The establishment of formal frameworks for cooperation between the CSN and several governmental organizations, such as the Ministry of Health and the Ministry of Interior in the areas of radiation protection and security. Carmen Martinez Ten, President of CSN, said, 'I am proud that Spain is among the first countries to have received a full- scope IRRS mission and a follow-up. CSN has benefitted from the IRRS mission using the contribution from senior regulators which has resulted and will continue in further improvements in our regulatory framework.' The IRRS team also made recommendations and suggestions to further strengthen Spain's regulatory body, including: CSN should establish a formal policy on how to use technical advisory bodies for technical regulatory decisions; CSN should continue to work with relevant bodies to prepare for the disposal of spent fuel and high-level waste, taking into account the progress being made in the siting of a storage facility; and CSN should continue to work with relevant competent authorities and other bodies on regulatory aspects of security. Denis Flory, IAEA Deputy Director General for Nuclear Safety and Security, said, 'This mission is a clear example of the value of regulatory bodies participating in a senior peer review process offered by IAEA. A particularly important feature of these IRRS follow-up missions is to assess the effective implementation of the recommendations made. This mission to Spain also demonstrates clearly the mutual interest of IRRS missions: they encourage improvements in the host countries and serve as valuable sources of information for the reviewers themselves and for other regulatory bodies.' (IAEA)

  4. Assessment of compliance with regulatory requirements for a best estimate methodology for evaluation of ECCS

    Energy Technology Data Exchange (ETDEWEB)

    Lee, Un Chul; Jang, Jin Wook; Lim, Ho Gon; Jeong, Ik [Seoul National Univ., Seoul (Korea, Republic of); Sim, Suk Ku [Korea Atomic Energy Research Institute, Taejon (Korea, Republic of)

    2000-03-15

    Best estimate methodology for evaluation of ECCS proposed by KEPCO(KREM) os using thermal-hydraulic best-estimate code and the topical report for the methodology is described that it meets the regulatory requirement of USNRC regulatory guide. In this research the assessment of compliance with regulatory guide. In this research the assessment of compliance with regulatory requirements for the methodology is performed. The state of licensing procedure of other countries and best-estimate evaluation methodologies of Europe is also investigated, The applicability of models and propriety of procedure of uncertainty analysis of KREM are appraised and compliance with USNRC regulatory guide is assessed.

  5. Participation of the Nuclear Regulatory Authority in the uranium urinalysis intercomparisons

    International Nuclear Information System (INIS)

    Bonino, Nestor O.; Palacios, Miguel A.; Serdeiro, Nelida H.

    1999-01-01

    In the present work the results of the participation of Nuclear Regulatory Authority (NRA) Argentina, in the Uranium Urinalysis Intercomparison Program administered by the National Calibration Reference Centre for Bioassay, Radiation Protection Bureau, Health Canada, are detailed. This work is referred to the three participations of NRA in 1995, 1996, and 1997. The number of laboratories that have participated was 14, 12 and 12. A statistical analysis is presented. The performance criteria used for assessing the acceptability of results are those given in the American National Standard Institute (ANSI) 1989, N13.30. In addition, the applied radiochemical technique and the methodology are described. (author)

  6. Nuclear Regulatory Authority of the Slovak Republic. Annual Report 2001

    International Nuclear Information System (INIS)

    Seliga, M.

    2002-04-01

    A brief account of activities carried out by the Nuclear Regulatory Authority of the Slovak Republic in 2001 is presented. These activities are reported under the headings: (1) Foreword; (2) Legislation; (3) Assessment and inspection of nuclear installations; (4) Safety analyses; (5) Nuclear materials and physical protection of nuclear installations; (6) Radioactive waste (RAW); (7) Quality assurance; (8) Personnel qualification and training; (9) Emergency preparedness; (10) International co-operation; (11) Public information; (12) Personnel and economy data; (13) Conclusion; (14) Appendix: Abbreviations; Radiation safety

  7. Services of the Nuclear Regulatory Authority Library

    International Nuclear Information System (INIS)

    Carregado, M.A.; Wallingre, G.V.

    2011-01-01

    Full text; The main of this work is to present the services and activities of the ARN (Autoridad Regulatoria Nuclear) Library to potential users from the biological dosimetry area in the framework of the intercomparison Meeting of the Latin American Biological Dosimetry Network held in Buenos Aires from October 27-30 of 2008. It makes a short chronology of the library; the services offered to each type of users and the tasks related to technical and international cooperation with other organizations such as: the terminology Committee of IRAM (Instituto Argentino de Normalizacion y Certificacion); the input of national literature to the INIS Database of the IAEA; the retrospective digitalisation, indexing and bibliographic description of institutional publications to be submitted to the repository of the Ibero American Forum of Nuclear and Radiation Safety Regulatory Organizations and the participation in nuclear information networks. Finally it shown some relevant data from the internal statistics. (authors)

  8. Regulatory philosophy and requirements for radiation control in Canadian uranium mine-mill facilities

    International Nuclear Information System (INIS)

    Dory, A.B.

    1981-10-01

    With the point made that radiation exposure is one of the health hazards of uranium mining and accordingly has to be controlled, the Canadian regulatory philosophy is outlined as it pertains to the uranium mining industry. Two extremes in regulatory approach are examined, and the joint regulatory process is explained. Two examples of poor management performance are given, and the role of mine unions in the regulatory process is touched upon. The development of new regulations to cover ventilation and employee training is sketched briefly. The author concludes with a general expression of objectives for the eighties which include improved personal dosimetry

  9. [European Union regulatory and quality requirements for botanical drugs and their implications for Chinese herbal medicinal products development].

    Science.gov (United States)

    Zhu, You-Ping

    2017-06-01

    This paper introduces regulatory pathways and characteristic quality requirements for marketing authorization of herbal medicinal products in the European Union(EU), and the legal status and applications of "European Union list of herbal substances, preparations and combinations" and "European Union herbal monographs". Also introduced are Chinese herbs that have been granted the EU list entry, those with EU herbal monographs, and registered EU traditional herbal medicinal products with Chinese herbs as active ingredients. Special attention is paid to the technical details of three authorized EU herbal medicinal products (Veregen, Sativex and Episalvan) in comparison with Andrographis paniculata extract HMPL-004 that failed the phase Ⅲ clinical trial for ulcerative colitis. The paper further emphasizes the importance of enriching active fractions of herbal extracts and taking regulatory and quality considerations into account in early stage of botanical drug development. Copyright© by the Chinese Pharmaceutical Association.

  10. Regulatory framework for nuclear power plant operation

    International Nuclear Information System (INIS)

    Perez Alcaniz, T.; Esteban Barriendos, M.

    1995-01-01

    As the framework of standards and requirements covering each phase of nuclear power plant project and operation developed, plant owners defined their licensing commitments (codes, rules and design requirements) during the project and construction phase before start-up and incorporated regulatory requirements imposed by the regulatory Body during the licensing process prior to operation. This produces a regulatory framework for operating a plant. It includes the Licensing Basis, which is the starting point for analyzing and incorporating new requirements, and for re-evaluation of existing ones. This presentation focuses on the problems of applying this regulatory framework to new operating activities, in particular to new projects, analyzing new requirements, and reconsidering existing ones. Clearly establishing a plant's licensing basis allows all organizations involved in plant operation to apply the requirements in a more rational way. (Author)

  11. 17 CFR 1.52 - Self-regulatory organization adoption and surveillance of minimum financial requirements.

    Science.gov (United States)

    2010-04-01

    ... 17 Commodity and Securities Exchanges 1 2010-04-01 2010-04-01 false Self-regulatory organization... Miscellaneous § 1.52 Self-regulatory organization adoption and surveillance of minimum financial requirements. (a) Each self-regulatory organization must adopt, and submit for Commission approval, rules...

  12. Radiation protection databases of nuclear safety regulatory authority

    International Nuclear Information System (INIS)

    Janzekovic, H.; Vokal, B.; Krizman, M.

    2003-01-01

    Radiation protection and nuclear safety of nuclear installations have a common objective, protection against ionising radiation. The operational safety of a nuclear power plant is evaluated using performance indicators as for instance collective radiation exposure, unit capability factor, unplanned capability loss factor, etc. As stated by WANO (World Association of Nuclear Operators) the performance indicators are 'a management tool so each operator can monitor its own performance and progress, set challenging goals for improvement and consistently compare performance with that of other plants or industry'. In order to make the analysis of the performance indicators feasible to an operator as well as to regulatory authorities a suitable database should be created based on the data related to a facility or facilities. Moreover, the international bodies found out that the comparison of radiation protection in nuclear facilities in different countries could be feasible only if the databases with well defined parameters are established. The article will briefly describe the development of international databases regarding radiation protection related to nuclear facilities. The issues related to the possible development of the efficient radiation protection control of a nuclear facility based on experience of the Slovenian Nuclear Safety Administration will be presented. (author)

  13. Galectin-1 is required for the regulatory function of B cells.

    Science.gov (United States)

    Alhabbab, R; Blair, P; Smyth, L A; Ratnasothy, K; Peng, Q; Moreau, A; Lechler, R; Elgueta, R; Lombardi, G

    2018-02-09

    Galectin-1 (Gal-1) is required for the development of B cells in the bone marrow (BM), however very little is known about the contribution of Gal-1 to the development of B cell regulatory function. Here, we report an important role for Gal-1 in the induction of B cells regulatory function. Mice deficient of Gal-1 (Gal-1 -/- ) showed significant loss of Transitional-2 (T2) B cells, previously reported to include IL-10 + regulatory B cells. Gal-1 -/- B cells stimulated in vitro via CD40 molecules have impaired IL-10 and Tim-1 expression, the latter reported to be required for IL-10 production in regulatory B cells, and increased TNF-α expression compared to wild type (WT) B cells. Unlike their WT counterparts, T2 and T1 Gal-1 -/- B cells did not suppress TNF-α expression by CD4 + T cells activated in vitro with allogenic DCs (allo-DCs), nor were they suppressive in vivo, being unable to delay MHC-class I mismatched skin allograft rejection following adoptive transfer. Moreover, T cells stimulated with allo-DCs show an increase in their survival when co-cultured with Gal-1 -/- T2 and MZ B cells compared to WT T2 and MZ B cells. Collectively, these data suggest that Gal-1 contributes to the induction of B cells regulatory function.

  14. Nuclear Regulatory Authority of the Slovak Republic. Annual Report 2004

    International Nuclear Information System (INIS)

    Seliga, M.

    2005-04-01

    A brief account of activities carried out by the Nuclear Regulatory Authority of the Slovak Republic in 2004 is presented. These activities are reported under the headings: (1) Foreword; (2) Legislation; (3) Assessment and inspection of nuclear power plants; (3.1) Assessment and inspection of other nuclear installations; (3.2) Safety analyses; (4) Nuclear materials and physical protection of nuclear installations; (5) Radioactive waste; (6) Quality assurance; (7) Personnel qualification and training; (8) Emergency preparedness; (9) International co-operation; (10) Public information; (11) Personnel and economy data; Appendix: Abbreviations; INES

  15. 9 CFR 147.51 - Authorized laboratory minimum requirements.

    Science.gov (United States)

    2010-01-01

    ... 9 Animals and Animal Products 1 2010-01-01 2010-01-01 false Authorized laboratory minimum requirements. 147.51 Section 147.51 Animals and Animal Products ANIMAL AND PLANT HEALTH INSPECTION SERVICE... Authorized Laboratories and Approved Tests § 147.51 Authorized laboratory minimum requirements. These minimum...

  16. Analysis of regulatory requirement for beyond design basis events of SMART

    International Nuclear Information System (INIS)

    Kim, W. S.; Seol, K. W.

    2000-01-01

    To enhance the safety of SMART reactor, safety and regulatory requirements associated with beyond design basis events (beyond BDE), which were developed and applied to advanced light water reactor designs, were analyzed along with a design status of passive reactor. And, based on these requirements, their applicability on the SMART design was evaluated. In the design aspect, severe accident prevention and mitigation features, containment performance, and accident management were analyzed. The evaluation results show that the requirement related to beyond DBE such as ATWS, loss of residual heat removal during shutdown operation, station blackout, fire, inter-system LOCA, and well-known events from severe accident phenomena is applicable to the SMART design. However, comprehensive approach against beyond DBE is not yet provided in the SMART design, and then it is required to designate and analyze the beyond DBE-related features. This study is expected to contribute to efforts to improve plant safety and to establish regulatory requirements for safety review

  17. Economics of the specification 6M safety re-evaluation and regulatory requirements

    International Nuclear Information System (INIS)

    Hopper, C.M.

    1985-01-01

    The objective of this work was to examine the potential economic impact of the DOT Specification 6M criticality safety re-evaluation and regulatory requirements. The examination was based upon comparative analyses of current authorized fissile material load limits for the 6M, current Federal regulations (and interpretations) limiting the contents of Type B fissile material packages, limiting aggregates of fissile material packages, and recent proposed fissile material mass limits derived from specialized criticality safety analyses of the 6M package. The work examines influences on cost in transportation, handling, and storage of fissile materials. Depending upon facility throughput requirements (and assumed incremental costs of fissile material packaging, storage, and transport), operating, facility storage capacity, and transportation costs can be reduced significantly. As an example of the pricing algorithm application based upon reasonable cost influences, the magnitude of the first year cost reductions could extend beyond four times the cost of the packaging nuclear criticality safety re-evaluation. 1 tab

  18. Self-assessment of the Nuclear Regulatory Authority of the Slovak Republic

    International Nuclear Information System (INIS)

    Husarcek, J.; Grebeciova, J.

    2006-01-01

    The major results are presented of the self-assessment procedure which was carried out by the Nuclear Regulatory Authority of the Slovak Republic (UJD) in 2005 based on the Common Assessment Framework (CAF) model. An overview is given of the most important preconditions and results and their interactions in the nine areas of assessment as follows: leadership, strategy and planning, human resource management, partnership and resources, process management and changes, customer and public oriented results, people results, society results, and key performance results. UJD's strengths and opportunities as emerged from the self-assessment are highlighted. The self-assessment process will be followed by the preparation and implementation of an Action Plan. (author)

  19. Criteria adopted by the Argentine Nuclear Regulatory Authority for assessing digital systems related to safety

    International Nuclear Information System (INIS)

    Terrado, Carlos A.; Chiossi, Carlos E.; Felizia, Eduardo R.; Roca, Jose L.; Sajaroff, Pedro M.

    2004-01-01

    Following the technological evolution in Instrumentation and Control (I and C) design, analog components are replaced by digital in almost every industry. Due to growing challenges of obsolescence and increasing maintenance costs, licensees of nuclear and radioactive installations are increasingly upgrading or replacing their existing I and C analog systems and components. In existing installations, this involves analog to digital replacements. In new installations design, the use of digital I and C systems is being considered from the very beginning, becoming a good alternative, even in safety applications. Up to now, in Argentina, there is no specific rules for safety-related digital systems, every safety system, analog or digital, must comply with the same generic regulations. The Nuclear Regulatory Authority is now developing criteria to assess digital systems related to safety in nuclear and radioactive installations. In this paper some of those criteria, based on local research and the recognized state of the art, are explained. From a regulatory point of view, the use of digital technology often raises new technical and licensing issues, particularly for safety-related applications. Examples include new failure modes, the potential for common-cause failure of redundant components, electromagnetic interference (EMI), software verification and validation, configuration management and a more exhaustive quality assurance system. The mentioned criteria comprehend the design, operation, maintenance and acquisition of digital systems and components important to safety. The main topics covered are: requirements specifications for digital systems, planning and documentation for digital system development, effectiveness of a digital system, commercial off the shelf (COTS) treatment and considerations involving tools for software development. (author)

  20. 17 CFR 249.821 - Form PILOT, information required of self-regulatory organizations operating pilot trading systems...

    Science.gov (United States)

    2010-04-01

    ... required of self-regulatory organizations operating pilot trading systems pursuant to § 240.19b-5 of this... Associations § 249.821 Form PILOT, information required of self-regulatory organizations operating pilot trading systems pursuant to § 240.19b-5 of this chapter. This form shall be used by all self-regulatory...

  1. Regulatory objectives, requirements and guidelines for the disposal of radioactive wastes - long-term aspects

    International Nuclear Information System (INIS)

    1987-01-01

    It is the purpose of this document to present the regulatory basis for judging the long-term acceptability of radioactive waste disposal options, assuming that the operational aspects of waste emplacement and facility closure satisfy the existing regulatory framework of requirements. Basic objectives of radioactive waste disposal are given, as are the regulatory requirements which must be satisfied in order to achieve these objectives. In addition, guidelines are given on the application of the radiological requirements to assist proponents in the preparation of submissions to the Atomic Energy Control Board (AECB). The primary focus of the requirements is on radiation protection, although environmental protection and institutional controls are also addressed in a more general way since these factors stem directly from the overall objectives for radioactive waste disposal

  2. Employee Development Capabilities of the Regulatory Authority in the Nuclear Field in Romania

    International Nuclear Information System (INIS)

    Ghinea, P.

    2016-01-01

    Full text: The paper provides information about CNCAN (general presentation of CNCAN responsibilities as a regulatory body) and about the general human resources management within our institution regarding the following: legal framework regarding resources; knowledge management; staff employment financial resources continuous focus on improvement of staff performances through dedicated training programmes. The process to develop and maintain the necessary competence and skills of staff of the regulatory body, as an element of knowledge management. Training for CNCAN staff is provided either in-house or through technical cooperation programmes with the IAEA. CNCAN has made arrangements for specific staff training using training courses and programmes provided by international organizations. The specific training is provided predominantly with the economic support from outside of the country. CNCAN has a process to develop and maintain the necessary competence and skills of staff of the regulatory body, as an element of knowledge management. To maintain an appropriate competence level, an annual plan for staff training is in place and each staff member has an individual training plan. Project supports CNCAN in the development of knowledge management and capacity building frameworks to secure long-term availability of regulatory competency. (author

  3. Development of the personnel training and qualification system of the Russian Federation Nuclear Regulatory Authority

    International Nuclear Information System (INIS)

    Kapralov, E.; Kapralov, Y.; Kozlov, V.

    2006-01-01

    The new personnel training and qualification system is being developed for russian regulatory body, having a very big number of employees and invited experts and widly territorially distributed structure. (author)

  4. Review of light water reactor regulatory requirements: Assessment of selected regulatory requirements that may have marginal importance to risk: Postaccident sampling system, Turbine missiles, Combustible gas control, Charcoal filters

    International Nuclear Information System (INIS)

    Scott, W.B.; Jamison, J.D.; Stoetzel, G.A.; Tabatabai, A.S.; Vo, T.V.

    1987-05-01

    In a study commissioned by the Nuclear Regulatory Commission (NRC), Pacific Northwest Laboratory (PNL) evaluated the costs and benefits of modifying regulatory requirements in the areas of the postaccident sampling system, turbine rotor design reviews and inspections, combustible gas control for inerted Boiling Water Reactor (BWR) containments, and impregnated charcoal filters in certain plant ventilation systems. The basic framework for the analyses was that presented in the Regulatory Analysis Guidelines (NUREG/BR-0058) and in the Handbook for Value-Impact Assessment (NUREG/CR-3568). The effects of selected modifications to regulations were evaluated in terms of such factors as public risk and costs to industry and NRC. The results indicate that potential modifications of the regulatory requirements in three of the four areas would have little impact on public risk. In the fourth area, impregnated charcoal filters in building ventilation systems do appear to limit risks to the public and plant staff. Revisions in the severe accident source term assumptions, however, may reduce the theoretical value of charcoal filters. The cost analysis indicated that substantial savings in operating costs may be realized by changing the interval of turbine rotor inspections. Small to moderate operating cost savings may be realized through postulated modifications to the postaccident sampling system requirements and to the requirements for combustible gas control in inerted BWR containments. Finally, the use of impregnated charcoal filters in ventilation systems appears to be the most cost-effective method of reducing radioiodine concentrations

  5. Evaluation of research reactor fuel reliability in support of regulatory requirements

    International Nuclear Information System (INIS)

    Sokolov, Eugene N.

    2005-01-01

    This standards, codes and practices survey is devoted to the problem of reliability of R and D especially research reactor fuel (RRF) performance-related processes. Regulatory R and D evaluations were based on one standard and just few of them provide correlation to other relative standards whereas synthetic process approach reflects actual status of particular R and D practices. Fuel performance regulatory parameters are based on quality standards. A reliability process-based method similar to PSA/FMEA is proposed to evaluate RRF performance- related parameters in terms of reactor safety. (author)

  6. Evaluation of research reactor fuel reliability in support of regulatory requirements

    Energy Technology Data Exchange (ETDEWEB)

    Sokolov, Eugene N [Chalk River Laboratories, AECL, Chalk River, ON, K0J 1J0 (Canada)

    2005-07-01

    This standards, codes and practices survey is devoted to the problem of reliability of R and D especially research reactor fuel (RRF) performance-related processes. Regulatory R and D evaluations were based on one standard and just few of them provide correlation to other relative standards whereas synthetic process approach reflects actual status of particular R and D practices. Fuel performance regulatory parameters are based on quality standards. A reliability process-based method similar to PSA/FMEA is proposed to evaluate RRF performance- related parameters in terms of reactor safety. (author)

  7. Regulatory Safety Requirements for Operating Nuclear Installations

    International Nuclear Information System (INIS)

    Gubela, W.

    2017-01-01

    The National Nuclear Regulator (NNR) is established in terms of the National Nuclear Regulator Act (Act No 47 of 1999) and its mandate and authority are conferred through sections 5 and 7 of this Act, setting out the NNR's objectives and functions, which include exercising regulatory control over siting, design, construction etc of nuclear installations through the granting of nuclear authorisations. The NNR's responsibilities embrace all those actions aimed at providing the public with confidence and assurance that the risks arising from the production of nuclear energy remain within acceptable safety limits -> Therefore: Set fundamental safety standards, conducting pro-active safety assessments, determining licence conditions and obtaining assurance of compliance. The promotional aspects of nuclear activities in South Africa are legislated by the Nuclear Energy Act (Act No 46 of 1999). The NNR approach to regulations of nuclear safety and security take into consideration, amongst others, the potential hazards associated with the facility or activity, safety related programmes, the importance of the authorisation holder's safety related processes as well as the need to exercise regulatory control over the technical aspects such as of the design and operation of a nuclear facility in ensuring nuclear safety and security. South Africa does not have national nuclear industry codes and standards. The NNR is therefore non-prescriptive as it comes to the use of industry codes and standards. Regulatory framework (current) provide for the protection of persons, property, and environment against nuclear damage, through Licensing Process: Safety standards; Safety assessment; Authorisation and conditions of authorisation; Public participation process; Compliance assurance; Enforcement

  8. Data Quality Objectives for Regulatory Requirements for Hazardous and Radioactive Air Emissions Sampling and Analysis

    International Nuclear Information System (INIS)

    MULKEY, C.H.

    1999-01-01

    This document describes the results of the data quality objective (DQO) process undertaken to define data needs for state and federal requirements associated with toxic, hazardous, and/or radiological air emissions under the jurisdiction of the River Protection Project (RPP). Hereafter, this document is referred to as the Air DQO. The primary drivers for characterization under this DQO are the regulatory requirements pursuant to Washington State regulations, that may require sampling and analysis. The federal regulations concerning air emissions are incorporated into the Washington State regulations. Data needs exist for nonradioactive and radioactive waste constituents and characteristics as identified through the DQO process described in this document. The purpose is to identify current data needs for complying with regulatory drivers for the measurement of air emissions from RPP facilities in support of air permitting. These drivers include best management practices; similar analyses may have more than one regulatory driver. This document should not be used for determining overall compliance with regulations because the regulations are in constant change, and this document may not reflect the latest regulatory requirements. Regulatory requirements are also expected to change as various permits are issued. Data needs require samples for both radionuclides and nonradionuclide analytes of air emissions from tanks and stored waste containers. The collection of data is to support environmental permitting and compliance, not for health and safety issues

  9. Regulatory aspects of criticality control in Australia

    International Nuclear Information System (INIS)

    Zimin, Sergei

    2003-01-01

    With the creation of Australian Radiation Protection and Nuclear Safety Agency (ARPANSA) the Australian approach to criticality safety was revisited. Consistency with international best practices is required by the Act that created ARPANSA and this was applied to practices in criticality safety adopted in other countries. This required extensive regulatory efforts both in auditing the major Australian Nuclear Operator, Australian Nuclear Science and Technology Organisation (ANSTO), and assessing the existing in Australia criticality safety practices and implementing the required changes using the new legislative power of ARPANSA. The adopted regulatory approach is formulated through both the issued by ARPANSA licenses for nuclear installations (including reactors, fuel stores and radioactive waste stores) and the string of new regulatory documents, including the Regulatory Assessment Principles and the Regulatory Assessment Guidelines for criticality safety. The main features of the adopted regulation include the requirements of independent peer-review, ongoing refresher training coupled with annual accreditation and the reliance on the safe design rather than on an administrative control. (author)

  10. Governmental, Legal and Regulatory Framework for Safety. General Safety Requirements. Part 1

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2010-09-15

    The objective of this publication is to establish requirements in respect of the governmental, legal and regulatory framework for safety. It covers the essential aspects of the framework for establishing a regulatory body and taking other actions necessary to ensure the effective regulatory control of facilities and activities utilized for peaceful purposes. Other responsibilities and functions, such as liaison within the global safety regime and on support services for safety (including radiation protection), emergency preparedness and response, nuclear security, and the State system of accounting for and control of nuclear material, are also covered.

  11. The mass media role in acceptance activities of Slovak Republic's Nuclear Regulatory Authority

    International Nuclear Information System (INIS)

    Seliga, Mojmir

    1998-01-01

    Communication is the vital link between Nuclear Regulatory Authority and the public. If people do not know and understand the facts on which optimal a safety energy choice decisions should be based they cannot make informed decisions on how their own objectives can be met. The following ten commandments of communications are pointed out: be yourself; be comfortable and confident; be honest; be brief; be human; be personal; be positive and consistent; be attentive; be energetic; be committed and sincere. The important aspect is to test whether the nuclear energy in the Slovak Republic is acceptable according to mandatory rules and if its operation is regulated by the state through the independent institution - the Nuclear Regulatory Authority of the Slovak Republic (UJD). The media in Slovakia has on important power. Many organizations are therefore apprehensive when dealing with the press, radio and television. Many people would simply prefer not to get panicked when the dreaded microphones and cameras do appear. UJD considers the whole area of public relations as an essential component of its activity. UJD intends to offer the public true, systematic, qualified, understandable and independent information, regarding the safety of nuclear power plants, as well as regarding the methods and results of UJD work. Generally, public information is considered a significant contribution to the creation of confidence into the regulatory work. The paper presents the UJD communication program and relations with media as well as the preparedness of public information in case of emergency

  12. Waste management from reprocessing: a stringent regulatory requirements for high quality conditioned residues

    International Nuclear Information System (INIS)

    Bordier, J. C.; Greneche, D.; Devezeaux, J. G.; Dalcorso, J.

    2000-01-01

    Nuclear waste production and management in France is governed by safety requirements imposed to all operators. French nuclear safety relies on two basic principles: · Responsibility of the nuclear operator, which expands to waste generated, · Safety basic objectives issued by national Safety Authority. For a long time the regulatory framework for waste production and management has been satisfactorily applied and has benefited to each actor of the process. LLW/MLW and HLW nuclear waste are currently conditioned in safe matrices or packages either likely to be disposed in surface repositories or designed with the intention to be disposed underground according to their radioactive content. France is looking into the case of VLLW and has already carried out a design for future disposal, the design being in the pipe. Other types of waste (i. e. radium bearing waste, graphite, and tritium content waste) are also considered in the whole framework of French waste management. (author)

  13. The Defence in Depth Concept Applied to the New Regulatory Requirements in Japan

    Energy Technology Data Exchange (ETDEWEB)

    Yamagata, H., E-mail: hiroshi_yamagata@nsr.go.jp [Nuclear Regulation Authority, Minato-ku, Tokyo (Japan)

    2014-10-15

    Full text: The new regulatory requirements based on lessons learnt from Fukushima Daiichi accident, which places emphasis on Defense-in-Depth concept, was put into effect in Japan on 8th July, 2013. It is required to prepare multi-layered protective measures. Each layer should achieve the objective only in that layer regardless of the measures in the other layers. The challenge is how to enhance independence of measures between layers. In the third layer, the current concept of design regarding safety relies on “single failure”, whose condition is elimination of common cause failure (CCF). To eliminate CCFs we introduced a more accurate approach in assessment of earthquake and tsunami, and introduction of measures against tsunami inundation. Redundancy of safety systems could not eliminate CCF by extreme natural hazards. Safety system should be designed by due consideration of diversity and independence including spatial dispersement. In the fourth layer, multi-layered protective measures are also applied for severe accidents, which consists of “prevention of core damage” under multiple failure, “prevention of containment failure”, and “prevention of large release, that is controlled release by venting”. In the fifth layer, we also require operators to prepare measures for “suppression of radioactive materials dispersion”. Of course, off-site emergency preparedness and response has been enhanced by introduction of PAZ and UPZ. Introduction of “Specialized Safety Facility” against intentional aircraft crash will contribute enhancement of some layers by providing electricity and water under extremely severe conditions. The new regulatory requirements are not our goal, just a first step. It is expected for regulator and operators to improve safety continuously by periodic comprehensive safety assessments including IPE, IPEEE, Margin test, and etc. We have to make an upward spiral of nuclear safety. (author)

  14. Economic analysis requirements in support of orbital debris regulatory policy

    Science.gov (United States)

    Greenberg, Joel S.

    1996-10-01

    As the number of Earth orbiting objects increases so does the potential for generating orbital debris with the consequent increase in the likelihood of impacting and damaging operating satellites. Various debris remediation approaches are being considered that encompass both in-orbit and return-to-Earth schema and have varying degrees of operations, cost, international competitiveness, and safety implications. Because of the diversity of issues, concerns and long-term impacts, there is a clear need for the setting of government policies that will lead to an orderly abatement of the potential orbital debris hazards. These policies may require the establishment of a supportive regulatory regime. The Department of Transportation is likely to have regulatory responsibilities relating to orbital debris stemming from its charge to protect the public health and safety, safety of property, and national security interests and foreign policy interests of the United States. This paper describes DOT's potential regulatory role relating to orbital debris remediation, the myriad of issues concerning the need for establishing government policies relating to orbital debris remediation and their regulatory implications, the proposed technological solutions and their economic and safety implications. Particular emphasis is placed upon addressing cost-effectiveness and economic analyses as they relate to economic impact analysis in support of regulatory impact analysis.

  15. Survey of extreme load design regulatory agency licensing requirements for nuclear power plants

    Energy Technology Data Exchange (ETDEWEB)

    Stevenson, J D

    1976-04-01

    Since 1965, when extreme load requirements began to be considered explicitly in nuclear power plant design, there has been a gradual divergence in requirements imposed by national regulatory agencies. However, nuclear plant safety is an international problem because of the potential international effects of any postulated plant failure. For this reason this paper has been prepared in an attempt to highlight the differences in national criteria currently used in the extreme load design of nuclear plant facilities. No attempt has been made to evaluate the relative merit of the criteria established by the various national regulatory agencies. This paper presents the results of a recent survey made of national atomic energy regulatory agencies and major nuclear steam supply design agencies, which requested a summary of current licensing criteria associated with earthquake, extreme wind (tornado), flood, airplane crash and accident (pipe break) loads applicable within the various national jurisdictions. Also presented are a number of comparisons which are meant to illustrate the differences in national regulatory criteria.

  16. Survey of extreme load design regulatory agency licensing requirements for nuclear power plants

    International Nuclear Information System (INIS)

    Stevenson, J.D.

    1976-01-01

    Since 1965, when extreme load requirements began to be considered explicitly in nuclear power plant design, there has been a gradual divergence in requirements imposed by national regulatory agencies. However, nuclear plant safety is an international problem because of the potential international effects of any postulated plant failure. For this reason this paper has been prepared in an attempt to highlight the differences in national criteria currently used in the extreme load design of nuclear plant facilities. No attempt has been made to evaluate the relative merit of the criteria established by the various national regulatory agencies. This paper presents the results of a recent survey made of national atomic energy regulatory agencies and major nuclear steam supply design agencies, which requested a summary of current licensing criteria associated with earthquake, extreme wind (tornado), flood, airplane crash and accident (pipe break) loads applicable within the various national jurisdictions. Also presented are a number of comparisons which are meant to illustrate the differences in national regulatory criteria. (Auth.)

  17. Assessment of Safety Culture within the Pakistan Nuclear Regulatory Authority (PNRA)

    Energy Technology Data Exchange (ETDEWEB)

    Afzal, Muhammad [Pakistan Nuclear Regulatory Authority, Islamabad (Pakistan); Choi, Kwang Sik [Korea Institute of Nuclear Safety, Daejeon (Korea, Republic of)

    2015-10-15

    The objective of this study is to assess the SC of the Pakistan Nuclear Regulatory Authority (PNRA) by developing a performance indicator-based questionnaire. Aspects that potentially play important roles in developing perceptions of SC, including age, type of job, gender and duty hours of regulatory staff, are given due importance in this study. The study also identifies the strengths and weaknesses in the SC of the PNRA and can be used as a model study to assess the SC of other RBs. The questionnaire, developed to assess the SC of the PNRA, was in line with the PNRA's own defined attributes for SC. In the past, significant efforts have been made to ensure the safe operation of NPPs by improving designs and operating procedures; however, the nuclear accident at the Fukushima NPP in Japan in March 2011 revealed that the currently allotted hardware safety margins are not sufficient, and much work is needed to improve safety management in terms of SC. Initially, the concept of SC was introduced for operating organizations to ensure safe operation of NPPs; nonetheless, more recent investigations of nuclear events and accidents, especially Fukushima, and at Davis-Besse, in the US, have revealed that a strong focus is required to address and improve the SC of Regulatory Bodies (RBs). Strong SC is considered a vital tool for RBs to achieve their objectives and discharge their responsibilities in an effective and efficient manner. Though the relationship between the SC of RBs and that of operating organizations is not straight forward, it is believed that the former has a strong influence over the latter. The questionnaire was consistent in terms of the credible nature of its questions, and the response group covered different levels of PNRA staff, from managers to lower level staff. The results show that the PNRA staff have a very good understanding of the nature and significance of attributes of SC and are doing their best to exercise the same within the

  18. Assessment of Safety Culture within the Pakistan Nuclear Regulatory Authority (PNRA)

    International Nuclear Information System (INIS)

    Afzal, Muhammad; Choi, Kwang Sik

    2015-01-01

    The objective of this study is to assess the SC of the Pakistan Nuclear Regulatory Authority (PNRA) by developing a performance indicator-based questionnaire. Aspects that potentially play important roles in developing perceptions of SC, including age, type of job, gender and duty hours of regulatory staff, are given due importance in this study. The study also identifies the strengths and weaknesses in the SC of the PNRA and can be used as a model study to assess the SC of other RBs. The questionnaire, developed to assess the SC of the PNRA, was in line with the PNRA's own defined attributes for SC. In the past, significant efforts have been made to ensure the safe operation of NPPs by improving designs and operating procedures; however, the nuclear accident at the Fukushima NPP in Japan in March 2011 revealed that the currently allotted hardware safety margins are not sufficient, and much work is needed to improve safety management in terms of SC. Initially, the concept of SC was introduced for operating organizations to ensure safe operation of NPPs; nonetheless, more recent investigations of nuclear events and accidents, especially Fukushima, and at Davis-Besse, in the US, have revealed that a strong focus is required to address and improve the SC of Regulatory Bodies (RBs). Strong SC is considered a vital tool for RBs to achieve their objectives and discharge their responsibilities in an effective and efficient manner. Though the relationship between the SC of RBs and that of operating organizations is not straight forward, it is believed that the former has a strong influence over the latter. The questionnaire was consistent in terms of the credible nature of its questions, and the response group covered different levels of PNRA staff, from managers to lower level staff. The results show that the PNRA staff have a very good understanding of the nature and significance of attributes of SC and are doing their best to exercise the same within the

  19. Extent and content of data for regulatory submissions: First-in-human and marketing authorization--Viewpoint of US industry.

    Science.gov (United States)

    Harris, Ian Ross

    2015-09-01

    The amount and type of data in regulatory submissions increases dramatically from the first-in-human clinical trials application through to the extensive dossier that is required for marketing authorization. The Pharmaceuticals and Biotechnology industries are very familiar with the requirements and expectations of Health Authorities for small molecule and biologics, but have limited experience for cell-based therapies. Fortunately, the United States Food and Drug Administration (FDA) and European Medicines agency (EMA) Committee for Advanced Therapies (CAT) have considerable experience in regulating cell therapies and have provided extensive Guidance documents for developers. The Agencies offers advice to Sponsors through a variety of meetings. However, it is incumbent on the Sponsor to understand the regulations, interpret the Guidance documents and formulate clear company positions to enable the Agency to provide clear feedback. It is important for Sponsors to understand the factors that are critical for the safety and efficacy of their product and to demonstrate to the Health Authorities that they have a control strategy that ensures safety and efficacy during all stages of development. The focus of this paper is to describe some of the challenges for the chemistry manufacturing and controls (CMC) for cell therapies being development internationally. Copyright © 2015.

  20. The regulatory framework in the UK

    International Nuclear Information System (INIS)

    O'Sullivan, R.

    1984-01-01

    The subject is covered in sections, headed: basic regulatory requirements covering the transport of radioactive material in the UK; responsibility for safety (competent authority; provision of regulations; implementation of regulations (international and national); design of transport flask; safety case; testing; assessment; approval certificate; compliance assurance; administration); advice and information on the regulatory safety standards. (U.K.)

  1. Regulatory Risk Management of Advanced Nuclear Power Plants

    International Nuclear Information System (INIS)

    George, Glenn R.

    2002-01-01

    Regulatory risk reflects both the likelihood of adverse outcomes during regulatory interactions and the severity of those outcomes. In the arena of advanced nuclear power plant licensing and construction, such adverse outcomes may include, for example, required design changes and construction delays. These, in turn, could significantly affect the economics of the plant and the generation portfolio in which it will operate. In this paper, the author addresses these issues through the lens of risk management. The paper considers various tools and techniques of regulatory risk management, including design diversity and hedging strategies. The effectiveness of alternate approaches is weighed and recommendations are made in several regulatory contexts. (author)

  2. Activities of Nuclear Regulatory Authority and safety of nuclear facilities in the Slovak Republic in 1993

    International Nuclear Information System (INIS)

    1994-04-01

    A brief account of activities carried out by the Nuclear Regulatory Authority of the Slovak Republic (NRA SR) in 1993 is presented. These activities are reported under the headings: (1) Introduction; (2) Regulatory activities at nuclear power plants units in operation; (2.1) Nuclear power plant SEP-EBO V-1; (4) Selected operation events and safety assessment in NPP SEP-EBO V-1; (2.2) Safety assessment of NPP SEP-EBO V-2; (3) Results of regulatory activities at the decommissioning of NPP A-1; (4) Regulatory activities at units under construction SEP-EMO - NPP Mochovce; (5) Further regulatory activities. (5.1) Preparation of designated personnel; (5.2) Inspection and accountancy of nuclear material; (5.3) Security provisions; (5.4) Accounted items and double use items; (5.5) Problem of radioactive wastes; (6.1) International co-operation activities of NRA; (6.2) Emergency planning; (6.3) International activities for quality enhancement of national supervision; (7) Conclusion [sk

  3. Nuclear Regulatory Infrastructure in the Philippines

    International Nuclear Information System (INIS)

    Leonin, Teofilo V. Jr.

    2015-01-01

    Regulating the use of radioactive materials in the Philippines involves the adherence to legislation, regulations, standards and regulatory guides. It is based on a detailed review and assessment of the radiation safety program of owners and users of these materials and associated equipment against safety requirements and on additional verification of the operating practices and procedures. Republic Acts 5207 and 2067, both as amended, are implemented through the regulations which are titled Code of PNRI Regulations or CPRs are developed and issued together with supporting regulatory guides, Bulletins and other documents detailing the safety requirements. These issuance adhere to internationally accepted requirements on radiation protection, and nuclear safety and security, as well as safeguards. Design documents and technical Specifications of important radioactive materials, equipment and components are required to be submitted and reviewed by the PNRI before the issuance of an authorization in the form of a license Verification of adherence to regulations and safety requirements are periodically checked through the implementation of an inspection and enforcement program. The ISO certified regulatory management system of PNRI is documented in a QMS manual that provides guidance on all work processes. It involves systematic planning and evaluation of activities, multiple means of getting feedback on the work processes, and continuous efforts to improve its effectiveness. Efforts are implemented in order to strengthen the transparency openness, independence, technical competence and effectiveness of the regulatory body. (author)

  4. Performance as a basic regulatory rule

    International Nuclear Information System (INIS)

    Spano, F.; Rudelli, M.D.; Telleria, D.M.

    1998-01-01

    In Argentina, the Nuclear Regulatory Authority has been sustained, from beginning by a normative system whose fundamental features are its requirements for performance. The Authority has defined indicators for carrying out the classification of practices as major o minor. (As a function of the complexity of processes and operation, equipment, associate risks and type of consequences, etc.). An example is given base on the requirements of standards related with the practice of gammagraphy in Argentina. From the Authority records we know that the effective dose of operators registered do not exceed 5 mSv per year. The associate risk is lower than 2 10 -4 per year. Risk assessment in scenarios resulting in a potential exposure, taken into account the Argentine standards gives a total risk per year in the order of 10 -4 for workers and 4 10 -5 for members of the public. The contents and requirements of system that sustains the regulatory authority can be prescriptive or just based in performance. A decision in favour of one of them should not only reflect the technical-scientific reality of the country implementing it but also other factors like social and economic issues. (author)

  5. 77 FR 12098 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing of...

    Science.gov (United States)

    2012-02-28

    ... 240.19b-4. I. Self-Regulatory Organization's Statement of the Terms of Substance of the Proposed Rule... FINRA and at the Commission's Public Reference Room. II. Self-Regulatory Organization's Statement of the..., and C below, of the most significant aspects of such statements. A. Self-Regulatory Organization's...

  6. 76 FR 9840 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing of...

    Science.gov (United States)

    2011-02-22

    .... 78s(b)(1). \\2\\ 17 CFR 240.19b-4. I. Self-Regulatory Organization's Statement of the Terms of Substance... Public Reference Room. II. Self-Regulatory Organization's Statement of the Purpose of, and Statutory..., and C below, of the most significant aspects of such statements. A. Self-Regulatory Organization's...

  7. Safety performance indicators used by the Russian Safety Regulatory Authority in its practical activities on nuclear power plant safety regulation

    International Nuclear Information System (INIS)

    Khazanov, A.L.

    2005-01-01

    The Sixth Department of the Nuclear, Industrial and Environmental Regulatory Authority of Russia, Scientific and Engineering Centre for Nuclear and Radiation Safety process, analyse and use the information on nuclear power plants (NPPs) operational experience or NPPs safety improvement. Safety performance indicators (SPIs), derived from processing of information on operational violations and analysis of annual NPP Safety Reports, are used as tools to determination of trends towards changing of characteristics of operational safety, to assess the effectiveness of corrective measures, to monitor and evaluate the current operational safety level of NPPs, to regulate NPP safety. This report includes a list of the basic SPIs, those used by the Russian safety regulatory authority in regulatory activity. Some of them are absent in list of IAEA-TECDOC-1141 ('Operational safety performance indicators for nuclear power plants'). (author)

  8. 76 FR 9838 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing of...

    Science.gov (United States)

    2011-02-22

    .... 78s(b)(1). \\2\\ 17 CFR 240.19b-4. I. Self-Regulatory Organization's Statement of the Terms of Substance..., and at the Commission's Public Reference Room. II. Self-Regulatory Organization's Statement of the... in sections A, B, and C below, of the most significant aspects of such statements. A. Self-Regulatory...

  9. Regulatory requirements and administrative practice in safety of nuclear installations

    International Nuclear Information System (INIS)

    Servant, J.

    1977-01-01

    This paper reviews the current situation of the France regulatory rules and procedures dealing with the safety of the main nuclear facilities and, more broadly, the nuclear security. First, the author outlines the policy of the French administration which requires that the licensee responsible for an installation has to demonstrate that all possible measures are taken to ensure a sufficient level of safety, from the early stage of the project to the end of the operation of the plant. Thus, the administration performs the assessment on a case-by-case basis, of the safety of each installation before granting a nuclear license. On the other hand, the administration settles overall safety requirements for specific categories of installations or components, which determine the ultimate safety performances, but avoid, as far as possible, to detail the technical specifications to be applied in order to comply with these goals. This approach, which allows the designers and the licensees to rely upon sound codes and standards, gains the advantage of a great flexibility without imparing the nuclear safety. The author outlines the licensing progress for the main categories of installations: nuclear power plants of the PWR type, fast breeders, uranium isotope separation plants, and irradiated fuel processing plants. Emphasis is placed on the most noteworthy points: standardization of projects, specific risks of each site, problems of advanced type reactors, etc... The development of the technical regulations is presented with emphasis on the importance of an internationally concerned action within the nuclear international community. The second part of this paper describes the France operating experience of nuclear installations from the safety point of view. Especially, the author examines the technical and administrative utilization of data from safety significant incidents in reactors and plants, and the results of the control performed by the nuclear installations

  10. The regulatory requirements, design bases, researches and assessments in the field of Ukrainian NPP's seismic safety

    International Nuclear Information System (INIS)

    Mykolaychuk, O.; Mayboroda, O.; Krytskyy, V.; Karnaukhov, O.

    2001-01-01

    State Nuclear Regulatory Authority of Ukraine (SNRA) pays large attention to problem of nuclear installations seismic stability. As a result the seismic design regulatory guides is revised, additional seismic researches of NPP sites are conducted, seismic reassessment of NPP designs were begun. The experts involved address all seismic related factors under close contact with the staff of NPP, design institutes and research organizations. This document takes stock on the situation and the research programs. (author)

  11. Compliance. Regulatory policy P-211

    International Nuclear Information System (INIS)

    2001-05-01

    This regulatory policy describes the basic principles and directives for establishing and conducting the Canadian Nuclear Safety Commission (CNSC) Compliance Program. The program is aimed at securing compliance by regulated persons with regulatory requirements made under the Nuclear Safety and Control Act ('the Act'). The policy applies to persons who are regulated by the CNSC through the Act, regulations and licences, as well as by decisions and orders made under the Act. The policy applies to officers and employees of the CNSC, and its authorized representatives or agents, who are involved in developing and carrying out compliance activities. Compliance, in the context of this policy, means conformity by regulated persons with the legally binding requirements of the Act, and the CNSC regulations, licences, decisions, and orders made under the Act. Compliance activities are CNSC measures of promotion, verification and enforcement aimed at securing compliance by regulated person with the applicable legally binding requirements. (author)

  12. Regulatory requirements on management of radioactive material safe transport in China

    International Nuclear Information System (INIS)

    Chu, C.

    2016-01-01

    Since 1980s, the IAEA Regulation for safe transport of radioactive material was introduced into China; the regulatory system of China began with international standards, and walked towards the institutionalized. In 2003 the National People’s Congress (NPC) promulgated “the Act on the Prevention of Radioactive Pollution of the People's Republic of China”. In 2009 “Regulation for the Safe Transport of Radioactive Material” (Referred to “Regulation”) was promulgated by the State Council. Subsequently, the National Nuclear Safety Administration (NNSA) began to formulate executive detailed department rules, regulations guidelines and standards. The present system of acts, regulations and standards on management of safe transport of radioactive material in China and future planning were introduced in this paper. Meanwhile, the paper described the specific administration requirements of the Regulation on classification management of radioactive materials, license management of transport packaging including design, manufacture and use, licensing management of transport activities and the provisions of illegal behaviors arising in safe transport of radioactive material. (author)

  13. Authorization basis requirements comparison report

    Energy Technology Data Exchange (ETDEWEB)

    Brantley, W.M.

    1997-08-18

    The TWRS Authorization Basis (AB) consists of a set of documents identified by TWRS management with the concurrence of DOE-RL. Upon implementation of the TWRS Basis for Interim Operation (BIO) and Technical Safety Requirements (TSRs), the AB list will be revised to include the BIO and TSRs. Some documents that currently form part of the AB will be removed from the list. This SD identifies each - requirement from those documents, and recommends a disposition for each to ensure that necessary requirements are retained when the AB is revised to incorporate the BIO and TSRs. This SD also identifies documents that will remain part of the AB after the BIO and TSRs are implemented. This document does not change the AB, but provides guidance for the preparation of change documentation.

  14. Authorization basis requirements comparison report

    International Nuclear Information System (INIS)

    Brantley, W.M.

    1997-01-01

    The TWRS Authorization Basis (AB) consists of a set of documents identified by TWRS management with the concurrence of DOE-RL. Upon implementation of the TWRS Basis for Interim Operation (BIO) and Technical Safety Requirements (TSRs), the AB list will be revised to include the BIO and TSRs. Some documents that currently form part of the AB will be removed from the list. This SD identifies each - requirement from those documents, and recommends a disposition for each to ensure that necessary requirements are retained when the AB is revised to incorporate the BIO and TSRs. This SD also identifies documents that will remain part of the AB after the BIO and TSRs are implemented. This document does not change the AB, but provides guidance for the preparation of change documentation

  15. Regulatory requirements for radiation protection

    International Nuclear Information System (INIS)

    Mason, E.A.; Cunningham, R.E.; Hard, J.E.; Mattson, R.J.; Smith, R.D.; Peterson, H.T. Jr.

    1977-01-01

    Regulatory requirements for radiation protection have evolved and matured over several decades. Due to the wide adoption of recommendations of the International Commission on Radiation Protection (ICRP), there exists international agreement on the principles to be followed for radiation protection. This foundation will be increasingly important due to the growing need for international agreements and standards for radiation protection and radioactive materials management. During the infancy of the commercial nuclear industry, primary reliance was placed on the protection of the individual, both in the work force and as a member of the public. With the growth of nuclear power in the 1960's and 1970's, environmental impact assessments and expert reviews of bio-effects data have focused attention on statistical risks to large population groups and the use of the collective dose commitment concept to estimate potential effects. The potential release of long-lived radionuclides from the nuclear fuel cycle requires further consideration of radionuclide accumulation in the biosphere and calls for controls conceived and implemented at the international level. The initial development efforts for addressing these concerns already have been instituted by the ICRP and the IAEA. However, formal international agreements and a unified set of international standards may be required to implement the recommendations of these groups. Further international efforts in the field of radiation protection are also called for in developing waste management practices and radioactive effluent control technology, in site selection for fuel reprocessing plants and waste dispersal facilities, and for ensuring safe transport of high-level wastes in various forms. Since the regulation of very low dose rates and doses will be involved, it will be useful to reexamine dose-effect relationships and societal goals for health protection. Improved criteria and methodologies for ''as low as readily

  16. Data Quality Objectives for Regulatory Requirements for Hazardous and Radioactive Air Emissions Sampling and Analysis

    Energy Technology Data Exchange (ETDEWEB)

    MULKEY, C.H.

    1999-07-06

    This document describes the results of the data quality objective (DQO) process undertaken to define data needs for state and federal requirements associated with toxic, hazardous, and/or radiological air emissions under the jurisdiction of the River Protection Project (RPP). Hereafter, this document is referred to as the Air DQO. The primary drivers for characterization under this DQO are the regulatory requirements pursuant to Washington State regulations, that may require sampling and analysis. The federal regulations concerning air emissions are incorporated into the Washington State regulations. Data needs exist for nonradioactive and radioactive waste constituents and characteristics as identified through the DQO process described in this document. The purpose is to identify current data needs for complying with regulatory drivers for the measurement of air emissions from RPP facilities in support of air permitting. These drivers include best management practices; similar analyses may have more than one regulatory driver. This document should not be used for determining overall compliance with regulations because the regulations are in constant change, and this document may not reflect the latest regulatory requirements. Regulatory requirements are also expected to change as various permits are issued. Data needs require samples for both radionuclides and nonradionuclide analytes of air emissions from tanks and stored waste containers. The collection of data is to support environmental permitting and compliance, not for health and safety issues. This document does not address health or safety regulations or requirements (those of the Occupational Safety and Health Administration or the National Institute of Occupational Safety and Health) or continuous emission monitoring systems. This DQO is applicable to all equipment, facilities, and operations under the jurisdiction of RPP that emit or have the potential to emit regulated air pollutants.

  17. Data Quality Objectives for Regulatory Requirements for Hazardous and Radioactive Air Emissions Sampling and Analysis

    International Nuclear Information System (INIS)

    MULKEY, C.H.

    1999-01-01

    This document describes the results of the data quality objective (DQO) process undertaken to define data needs for state and federal requirements associated with toxic, hazardous, and/or radiological air emissions under the jurisdiction of the River Protection Project (RPP). Hereafter, this document is referred to as the Air DQO. The primary drivers for characterization under this DQO are the regulatory requirements pursuant to Washington State regulations, that may require sampling and analysis. The federal regulations concerning air emissions are incorporated into the Washington State regulations. Data needs exist for nonradioactive and radioactive waste constituents and characteristics as identified through the DQO process described in this document. The purpose is to identify current data needs for complying with regulatory drivers for the measurement of air emissions from RPP facilities in support of air permitting. These drivers include best management practices; similar analyses may have more than one regulatory driver. This document should not be used for determining overall compliance with regulations because the regulations are in constant change, and this document may not reflect the latest regulatory requirements. Regulatory requirements are also expected to change as various permits are issued. Data needs require samples for both radionuclides and nonradionuclide analytes of air emissions from tanks and stored waste containers. The collection of data is to support environmental permitting and compliance, not for health and safety issues. This document does not address health or safety regulations or requirements (those of the Occupational Safety and Health Administration or the National Institute of Occupational Safety and Health) or continuous emission monitoring systems. This DQO is applicable to all equipment, facilities, and operations under the jurisdiction of RPP that emit or have the potential to emit regulated air pollutants

  18. Guidelines on how to meet the requirement to keep all exposures as low as reasonably achievable. Regulatory guide

    International Nuclear Information System (INIS)

    1997-01-01

    The purpose of Regulatory Guide G-129 (E) is to provide Atomic Energy Control Board (AECB) licensees with guidelines on how to meet the forthcoming AECB regulatory requirement to keep doses received by workers and members of the public As Low As Reasonably Achievable (ALARA), social and economic factors taken into account. it is realized that the scope for realistic dose reductions will vary depending on the nature of the licensed activity. Therefore, criteria are given in section D for determining if doses can be deemed to be as low as reasonably achievable without further evaluation. The elements that the AECB considers to be essential in the approach to ALARA are described in section E and are summarized as follows: a demonstrated management commitment to the ALARA principle; the implementation of ALARA through a licensee's organization and management, provision of resources, training, establishment of action levels, documentation and other measures; and regular operational reviews. The above elements will be the focus of any AECB assessment to verify compliance with the requirement to keep radiation exposures as low as reasonably achievable. (author)

  19. Regulatory requirement of the Juragua nuclear Power Plant PSA

    International Nuclear Information System (INIS)

    Valhuerdi Debesa, C.

    1996-01-01

    Probabilistic Safety Assessment has proved to be a powerful tool for improving the knowledge of the safety insides of Nuclear Power Plants and increasing the efficiency of the safety measures adopted by both operators and regulators. In this paper the regulatory approach adopted in Cuba with regard to the PSA , the scope of the requirement and the basis and proposal of this decision are presented

  20. Continuing education requirements among State Occupational Therapy Regulatory Boards in the United States of America

    Directory of Open Access Journals (Sweden)

    Savannah R. Hall

    2016-10-01

    Full Text Available Purpose The purpose of this study is to compare and contrast the contents of each state’s occupational therapy (OT regulatory board requirements regarding licensees’ acquisition of continuing education units in the United States of America. Methods Data related to continuing education requirements from each OT regulatory board of all 50 states and the District of Columbia in the United States were reviewed and categorized by two reviewers. Analysis was conducted based on the categorization of the continuing education requirements and activities required, allowed, and not allowed/not mentioned for continuing education units. Results Findings revealed non-uniformity and inconsistency of continuing education requirements for licensure renewal between OT regulatory boards and was coupled with lack of specific criteria for various continuing education activities. Continuing education requirements were not tailored to meet the needs of individual licensee’s current and anticipated professional role and job responsibilities, with a negative bias towards presentation and publication allowed for continuing education units. Few boards mandated continuing education topics on ethics related to OT practice within each renewal cycle. Conclusion OT regulatory boards should move towards unifying the reporting format of continuing education requirements across all states to reduce ambiguity and to ensure licensees are equipped to provide ethical and competent practice. Efforts could be made to enact continuing education requirements specific to the primary role of a particular licensee. Finally, assigning the amount of continuing education credits to be awarded for different activities should be based on research evidence rather than arbitrary determination.

  1. Ego depletion and positive illusions: does the construction of positivity require regulatory resources?

    Science.gov (United States)

    Fischer, Peter; Greitemeyer, Tobias; Frey, Dieter

    2007-09-01

    Individuals frequently exhibit positive illusions about their own abilities, their possibilities to control their environment, and future expectations. The authors propose that positive illusions require resources of self-control, which is considered to be a limited resource similar to energy or strength. Five studies revealed that people with depleted self-regulatory resources indeed exhibited a less-optimistic sense of their own abilities (Study 1), a lower sense of subjective control (Study 2), and less-optimistic expectations about their future (Study 3). Two further studies shed light on the underlying psychological process: Ego-depleted (compared to nondepleted) individuals generated/retrieved less positive self-relevant attributes (Studies 4 and 5) and reported a lower sense of general self-efficacy (Study 5), which both partially mediated the impact of ego depletion on positive self-views (Study 5).

  2. Regulatory Control of Radiation Sources. Safety Guide

    International Nuclear Information System (INIS)

    2009-01-01

    This Safety Guide is intended to assist States in implementing the requirements established in Safety Standards Series No. GS-R-1, Legal and Governmental Infrastructure for Nuclear, Radiation, Radioactive Waste and Transport Safety, for a national regulatory infrastructure to regulate any practice involving radiation sources in medicine, industry, research, agriculture and education. The Safety Guide provides advice on the legislative basis for establishing regulatory bodies, including the effective independence of the regulatory body. It also provides guidance on implementing the functions and activities of regulatory bodies: the development of regulations and guides on radiation safety; implementation of a system for notification and authorization; carrying out regulatory inspections; taking necessary enforcement actions; and investigating accidents and circumstances potentially giving rise to accidents. The various aspects relating to the regulatory control of consumer products are explained, including justification, optimization of exposure, safety assessment and authorization. Guidance is also provided on the organization and staffing of regulatory bodies. Contents: 1. Introduction; 2. Legal framework for a regulatory infrastructure; 3. Principal functions and activities of the regulatory body; 4. Regulatory control of the supply of consumer products; 5. Functions of the regulatory body shared with other governmental agencies; 6. Organization and staffing of the regulatory body; 7. Documentation of the functions and activities of the regulatory body; 8. Support services; 9. Quality management for the regulatory system.

  3. Information management systems for integrating the technical data and regulatory requirements of environmental restoration activities

    International Nuclear Information System (INIS)

    Geffen, C.A.; Garrett, B.A.; Walter, M.B.

    1990-03-01

    Current environmental regulations require that comprehensive planning be conducted before remediating a hazardous waste site to characterize the nature and extent of site contamination, calculate the risk to the public, and assess the effectiveness of various remediation technologies. Remediation of Department of Energy (DOE) sites contaminated with hazardous or mixed wastes will require the effective integration of scientific and engineering data with regulatory and institutional requirements. The information management challenge presented by waste site cleanup activities goes beyond merely dealing with the large quantity of data that will be generated. The information must be stored, managed, and presented in a way that provides some consistency in approach across sites, avoids duplication of effort, and facilitates responses to requests for information from the regulators and the public. This paper provides background information on the regulatory requirements for data gathering and analysis for environmental restoration activities, and outlines the data and information management requirements for completing the pre-remediation phases of an environmental restoration project. Information management systems for integrating the regulatory and institutional requirements of the environmental restoration process with the technical data and analysis requirements are also described. 7 refs

  4. Development of guidance on applications of regulatory requirements for regulating large, contaminated equipment and large decommissioning and decontamination (D and D) components

    International Nuclear Information System (INIS)

    Pope, R.B.; Easton, E.P.; Cook, J.R.; Boyle, R.W.

    1997-01-01

    In 1985, the International Atomic Energy Agency issued revised regulations for the safe transport of radioactive material. Significant were major changes to requirements for Low Specific Activity (LSA) material and Surface Contaminated Objects (SCOs). As these requirements were adopted into regulations in the United States, it was recognised that guidance on how to apply these requirements to large, contaminated/activated pieces of equipment and decommissioning and decontamination (D and D) objects would be needed both by the regulators and those regulated to clarify technical uncertainties and ensure implementation. Thus, the US Department of Transportation and the US Nuclear Regulatory Commission, with assistance of staff from Oak Ridge National Laboratory, are preparing regulatory guidance which will present examples of acceptable methods for demonstrating compliance with the revised rules for large items. Concepts being investigated for inclusion in the pending guidance are discussed in this paper. Under current plans, the guidance will be issued for public comment before final issuance in 1997. (Author)

  5. Regulatory pathways for vaccines for developing countries.

    Science.gov (United States)

    Milstien, Julie; Belgharbi, Lahouari

    2004-01-01

    Vaccines that are designed for use only in developing countries face regulatory hurdles that may restrict their use. There are two primary reasons for this: most regulatory authorities are set up to address regulation of products for use only within their jurisdictions and regulatory authorities in developing countries traditionally have been considered weak. Some options for regulatory pathways for such products have been identified: licensing in the country of manufacture, file review by the European Medicines Evaluation Agency on behalf of WHO, export to a country with a competent national regulatory authority (NRA) that could handle all regulatory functions for the developing country market, shared manufacturing and licensing in a developing country with competent manufacturing and regulatory capacity, and use of a contracted independent entity for global regulatory approval. These options have been evaluated on the basis of five criteria: assurance of all regulatory functions for the life of the product, appropriateness of epidemiological assessment, applicability to products no longer used in the domestic market of the manufacturing country, reduction of regulatory risk for the manufacturer, and existing rules and regulations for implementation. No one option satisfies all criteria. For all options, national infrastructures (including the underlying regulatory legislative framework, particularly to formulate and implement local evidence-based vaccine policy) must be developed. WHO has led work to develop this capacity with some success. The paper outlines additional areas of action required by the international community to assure development and use of vaccines needed for the developing world. PMID:15042235

  6. A study on the influence of the regulatory requirements of a nuclear facility during decommissioning activities

    Energy Technology Data Exchange (ETDEWEB)

    Park, Hee Seong; Park, Seung Kook; Park, Kook Nam; Hong, Yun Jeong; Park, Jang Jin; Choi, Jong Won [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2016-10-15

    The preliminary decommissioning plan should be written with various chapters such as a radiological characterization, a decommissioning strategy and methods, a design for decommissioning usability, a safety evaluation, decontamination and dismantling activities, radioactive waste management, an environmental effect evaluation, and fire protection. The process requirements of the decommissioning project and the technical requirements and technical criteria should comply with regulatory requirements when dismantling of a nuclear facility. The requirements related to safety in the dismantling of a nuclear facility refer to the IAEA safety serious. The present paper indicates that a decommissioning design and plan, dismantling activities, and a decommissioning project will be influenced by the decommissioning regulatory requirements when dismantling of a nuclear facility. We hereby paved the way to find the effect of the regulatory requirements on the decommissioning of a whole area from the decommissioning strategy to the radioactive waste treatment when dismantling a nuclear facility. The decommissioning requirements have a unique feature in terms of a horizontal relationship as well as a vertical relationship from the regulation requirements to the decommissioning technical requirements. The decommissioning requirements management will be conducted through research that can recognize a multiple relationship in the next stage.

  7. Enhancement of Regulatory Supervision of the nuclear legacy in northwest Russia: involving the military authorities

    International Nuclear Information System (INIS)

    Roudak, S.F.; Sneve, M.K.; Bulatov, O.R.; Vasiliev, A.P.; Malinkin, V.M.

    2011-10-01

    This report describes work carried out within the cooperation programme between the Norwegian Radiation Protection Authority and the Directorate of State Supervision for Nuclear and Radiation Safety of the Ministry of Defense of the Russian Federation performed in 2008-2009. It focuses on development of improved regulatory documents and supervision procedures for handling spent nuclear fuel and radioactive waste at facilities that are no longer used by the Russian Federation Navy but that are still under military supervision and control. (Author)

  8. Enhancement of Regulatory Supervision of the nuclear legacy in northwest Russia: involving the military authorities

    Energy Technology Data Exchange (ETDEWEB)

    Roudak, S.F.; Sneve, M.K.; Bulatov, O.R.; Vasiliev, A.P.; Malinkin, V.M.

    2011-10-15

    This report describes work carried out within the cooperation programme between the Norwegian Radiation Protection Authority and the Directorate of State Supervision for Nuclear and Radiation Safety of the Ministry of Defense of the Russian Federation performed in 2008-2009. It focuses on development of improved regulatory documents and supervision procedures for handling spent nuclear fuel and radioactive waste at facilities that are no longer used by the Russian Federation Navy but that are still under military supervision and control. (Author)

  9. Methods for ensuring compliance with regulatory requirements: regulators and operators

    International Nuclear Information System (INIS)

    Fleischmann, A.W.

    1989-01-01

    Some of the methods of ensuring compliance with regulatory requirements contained in various radiation protection documents such as Regulations, ICRP Recommendations etc. are considered. These include radiation safety officers and radiation safety committees, personnel monitoring services, dissemination of information, inspection services and legislative power of enforcement. Difficulties in ensuring compliance include outmoded legislation, financial and personnel constraints

  10. Regulatory Guide 1.79 safety injection recirculation test requirements, fact or fiction

    International Nuclear Information System (INIS)

    Roberts, J.K.

    1976-01-01

    The overwhelming concern of the general public in this day of state nuclear initiatives is the basic question, ''is nuclear power safe.'' Much of this concern has focused on the emergency core cooling systems. This public attention spotlights the testing organization's responsibility during startup of proving the operation and reliability of the emergency core cooling systems. The standard established by the Nuclear Regulatory Commission for testing emergency core cooling systems is Regulatory Guide 1.79 ''Preoperational Testing of Emergency Core Cooling Systems for Pressurized Water Reactors''. The nuclear industry must satisfy the testing requirements of Regulatory Guide 1.79 to meet their responsibility to the public; and to prevent future embarrassment when questioned on the adequacy of emergency core cooling systems

  11. Canadian and international approaches to regulatory effectiveness

    International Nuclear Information System (INIS)

    Lojk, R.

    2014-01-01

    Regulatory effectiveness is an important attribute of any regulator, particularly nuclear regulators. As the nuclear industry has matured, and as the social landscape has changed, so have views on what constitutes regulatory effectiveness. Canada has evolved its regulatory structure and modernized its legislative framework and technical requirements and guidance over time. In addition, Canada continues to collaborate with international agencies, particularly the NEA and the IAEA, to ensure that there is a common understanding of the indicators and key attributes of regulatory effectiveness. This paper discusses Canadian and international views on the subject, including perspectives from other industries. (author)

  12. Regulatory control of maintenance activities in Argentine nuclear power plants

    International Nuclear Information System (INIS)

    Calvo, J.C.; Caruso, G.

    2000-01-01

    The main maintenance objective is to assure that the safety features of structures, components and systems of nuclear power plants are kept as designed. Therefore, there is a direct relationship between safety and maintenance. Owing to the above mentioned, maintenance activities are considered a relevant regulatory issue for the Argentine Nuclear Regulatory Authority (ARN). This paper describes the regulatory control to maintenance activities of Argentine nuclear power plants. It also addresses essential elements for maintenance control, routine inspections, special inspections during planned outages, audits and license conditions and requirements. (author)

  13. Medical program in radiation protection from the Argentine Nuclear Regulatory Authority

    International Nuclear Information System (INIS)

    Perez, M. R.; Gisone, P.; Di Trano, J.L.; Dubner, D.L.; Michelin, S.C.

    1998-01-01

    This program is carried out by the Radio pathology Laboratory, belonging to the Nuclear Regulatory Authority. The program includes the following aspects: 1) planning and organization of medical response in radiological emergencies. A three-level system of medical assistance has been developed considering: a- determination of each level of care and their potential roles; b- choice of medical facilities for medical assistance; c- preparedness for medical response (equipment s, logistic support, human resources, training). 2) scientific research activities related to radio pathology subjects: a- hematological indicators in radioinduced aplasia; b- biological and biophysical dosimeters; c- radiation effects on the developing brain. 3) edition of practical guidelines for diagnostic and treatment: a- external and internal radioactive contamination; b- acute radiation syndrome; c- radiological burns. 4) medical advising in radioprotection (risk assessment in radiation workers, medical exposures, potential effects of prenatal irradiation). 5) international interactions: activities related with the constitution of a Latin American radio pathology network, linkage with international reference centers. (author) [es

  14. Use of probabilistic risk assessments to define areas of possible exemption from regulatory requirements

    International Nuclear Information System (INIS)

    Thompson, C.A.; Carlson, D.; Kolaczkowski, A.; LaChance, J.

    1988-01-01

    The Risk-Based Licensing Program (RBLP) was sponsored by the Department of Energy for the purpose of establishing and demonstrating an approach for identifying potential areas for exemption from current regulatory requirements in the licensing of nuclear power plants. Such an approach could assist in the improvement of the regulatory process for both current and future nuclear plant designs. Use of the methodology could result in streamlining the regulatory process by eliminating unnecessarily detailed reviews of portions of a plant design not important to risk. The RBLP methodology utilizes probabilistic risk assessments, (PRAs), which are required of all future applicants for nuclear power plant licenses. PRA results are used as a screening tool to determine the risk significance of various plant features which are correlated to the risk importance of regulations to identify potential areas for regulatory exemption. Additional consideration is then given to non-risk factors in the final determination of exemption candidates. The RBLP methodology was demonstrated using an existing PRA. The results of the demonstration are highlighted. 10 refs

  15. Design basis ground motion (Ss) required on new regulatory guide

    International Nuclear Information System (INIS)

    Kamae, Katsuhiro

    2013-01-01

    New regulatory guide is enforced on July 8. Here, it is introduced how the design basis ground motion (Ss) for seismic design of nuclear power reactor facilities was revised on the new guide. Ss is formulated as two types of earthquake ground motions, earthquake ground motions with site specific earthquake source and with no such specific source locations. The latter is going to be revised based on the recent observed near source ground motions. (author)

  16. Regulatory requirements for designing PET-CT facility in India

    International Nuclear Information System (INIS)

    Tandon, Pankaj

    2010-01-01

    In India, cyclotron-produced radionuclides are gaining importance in molecular imaging in Nuclear Medicine (NM) departments. The importance of this modality among others is due to the fact that it provides valuable clinical information, which was lacking in other available modalities. Presently, every well-established hospital would like to procure Medical Cyclotron or positron emission tomography-computed tomography (PET-CT) facility in their NM department. Because cyclotron-produced radionuclides have higher energy than the other routinely used radionuclides for diagnosis, it becomes essential for the user to know about the regulatory requirement and radiation safety precautions that one has to take for the installation of this new modality in their premises. The various stages of approval of PET-CT facility by the Atomic Energy Regulatory Board (AERB) and important steps that one has to know/follow before planning for this new facility are summarized

  17. Participation of the Nuclear Regulatory Authority in the 'Third European Intercomparison Exercise on Internal Dose Assessment'

    International Nuclear Information System (INIS)

    Rojo, Ana Maria; Gomez Parada, Ines Maria

    2001-01-01

    This paper resume the participation of the Argentine Nuclear Regulatory Authority (ARN) in the 'Third European Intercomparison Exercise on Internal Dose Assessment'. It takes place during 5 months in 1998 and the final meeting was held in Weimar, Germany, on May 1999. This exercise involved the previous distribution of seven cases, simulated and real, describing possible incorporations of radioactive materials. There was a description of the event, data of retention or excretion measurements and air concentration data. The fifty participants belong to twenty three countries had do solve the cases and informed the results to the organizers, mainly the incorporation and effective dose was required. The objective was to review the methodology, the codes and the different assumptions used by the participants for discussing the consistent of the result. The results are shown through tables including the maximum and minimum values gave for the final report and the results informed by ARN. This exercise allowed to compare the methodology used by the ARN internal dosimetry group with other choose by several international groups to assure that the codes, assumptions and methodology were satisfactory to solve the different cases given by the organizers. (author)

  18. Fabrication of sterile experimental radiopharmaceuticals: technical and regulatory requirements

    International Nuclear Information System (INIS)

    Briand, S.

    2008-03-01

    The radiopharmaceuticals devoted to the biomedical research were the object of the directive 2001/20/C.E. transposition that defined again the conditions of implementation of biomedical research using drugs at human use, whom authorization is delivered by A.f.s.s.a.p.s.. In an other hand the law 2006-686 of the 13. june 2006 ( called law T.S.N.) has modified the regulatory dispositions relative to the radiation protection norms. These new dispositions allow to the health facilities to realize their research projects without difficulties for experimental drugs supply. (N.C.)

  19. Self-assessment of the Nuclear Regulatory Authority of the Slovak Republic and a subsequent partner IAEA IRRS mission

    International Nuclear Information System (INIS)

    Husarcek, Jan

    2012-01-01

    A self-assessment exercise performed by the Nuclear Regulatory Authority of the Slovak Republic based on the IAEA Integrated Regulatory Review Service (IRRS) methodology, and the follow-up IAEA mission are described. The self-assessment methodology is outlined. The purpose, scope, area, content and process of the self-assessment are explained. The work done, the summary results of the IAEA IRRS mission, and proposed improvements are described. (orig.)

  20. The nuclear regulatory process in Canada experience and possible future direction

    International Nuclear Information System (INIS)

    Sainsbury, J.D.

    1987-01-01

    The underlying principle in the Canadian licensing process is that the licensee (owner/operatopr) bears the responsibility for safety while the regulatory authority sets safety objectives and audits their achievement. As a consequence, Canadian Regulatory Requirements emphasize numerical safety goals, and minimize specific design or operational rules. This paper traces the evolution of this approach, and indicates direction for the future. (author)

  1. Data Quality Objectives for Regulatory Requirements for Hazardous and Radioactive Air Emissions Sampling and Analysis; FINAL

    International Nuclear Information System (INIS)

    MULKEY, C.H.

    1999-01-01

    This document describes the results of the data quality objective (DQO) process undertaken to define data needs for state and federal requirements associated with toxic, hazardous, and/or radiological air emissions under the jurisdiction of the River Protection Project (RPP). Hereafter, this document is referred to as the Air DQO. The primary drivers for characterization under this DQO are the regulatory requirements pursuant to Washington State regulations, that may require sampling and analysis. The federal regulations concerning air emissions are incorporated into the Washington State regulations. Data needs exist for nonradioactive and radioactive waste constituents and characteristics as identified through the DQO process described in this document. The purpose is to identify current data needs for complying with regulatory drivers for the measurement of air emissions from RPP facilities in support of air permitting. These drivers include best management practices; similar analyses may have more than one regulatory driver. This document should not be used for determining overall compliance with regulations because the regulations are in constant change, and this document may not reflect the latest regulatory requirements. Regulatory requirements are also expected to change as various permits are issued. Data needs require samples for both radionuclides and nonradionuclide analytes of air emissions from tanks and stored waste containers. The collection of data is to support environmental permitting and compliance, not for health and safety issues. This document does not address health or safety regulations or requirements (those of the Occupational Safety and Health Administration or the National Institute of Occupational Safety and Health) or continuous emission monitoring systems. This DQO is applicable to all equipment, facilities, and operations under the jurisdiction of RPP that emit or have the potential to emit regulated air pollutants

  2. Risk-informed assessment of regulatory and design requirements for future nuclear power plants. Annual report

    International Nuclear Information System (INIS)

    2000-01-01

    OAK B188 Risk-informed assessment of regulatory and design requirements for future nuclear power plants. Annual report. The overall goal of this research project is to support innovation in new nuclear power plant designs. This project is examining the implications, for future reactors and future safety regulation, of utilizing a new risk-informed regulatory system as a replacement for the current system. This innovation will be made possible through development of a scientific, highly risk-formed approach for the design and regulation of nuclear power plants. This approach will include the development and/or confirmation of corresponding regulatory requirements and industry standards. The major impediment to long term competitiveness of new nuclear plants in the U.S. is the capital cost component--which may need to be reduced on the order of 35% to 40% for Advanced Light Water Reactors (ALWRS) such as System 80+ and Advanced Boiling Water Reactor (ABWR). The required cost reduction for an ALWR such as AP600 or AP1000 would be expected to be less. Such reductions in capital cost will require a fundamental reevaluation of the industry standards and regulatory bases under which nuclear plants are designed and licensed. Fortunately, there is now an increasing awareness that many of the existing regulatory requirements and industry standards are not significantly contributing to safety and reliability and, therefore, are unnecessarily adding to nuclear plant costs. Not only does this degrade the economic competitiveness of nuclear energy, it results in unnecessary costs to the American electricity consumer. While addressing these concerns, this research project will be coordinated with current efforts of industry and NRC to develop risk-informed, performance-based regulations that affect the operation of the existing nuclear plants; however, this project will go further by focusing on the design of new plants

  3. Risk-informed assessment of regulatory and design requirements for future nuclear power plants. Annual report

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2000-08-01

    OAK B188 Risk-informed assessment of regulatory and design requirements for future nuclear power plants. Annual report. The overall goal of this research project is to support innovation in new nuclear power plant designs. This project is examining the implications, for future reactors and future safety regulation, of utilizing a new risk-informed regulatory system as a replacement for the current system. This innovation will be made possible through development of a scientific, highly risk-formed approach for the design and regulation of nuclear power plants. This approach will include the development and/or confirmation of corresponding regulatory requirements and industry standards. The major impediment to long term competitiveness of new nuclear plants in the U.S. is the capital cost component--which may need to be reduced on the order of 35% to 40% for Advanced Light Water Reactors (ALWRS) such as System 80+ and Advanced Boiling Water Reactor (ABWR). The required cost reduction for an ALWR such as AP600 or AP1000 would be expected to be less. Such reductions in capital cost will require a fundamental reevaluation of the industry standards and regulatory bases under which nuclear plants are designed and licensed. Fortunately, there is now an increasing awareness that many of the existing regulatory requirements and industry standards are not significantly contributing to safety and reliability and, therefore, are unnecessarily adding to nuclear plant costs. Not only does this degrade the economic competitiveness of nuclear energy, it results in unnecessary costs to the American electricity consumer. While addressing these concerns, this research project will be coordinated with current efforts of industry and NRC to develop risk-informed, performance-based regulations that affect the operation of the existing nuclear plants; however, this project will go further by focusing on the design of new plants.

  4. Continuous improvement of the regulatory framework for the control of medical exposure

    International Nuclear Information System (INIS)

    Larcher, Ana M.; Ortiz Lopez, Pedro; Arias, Cesar; Marechal, Maria H.; Hernandez Alvarez, Ramon; Ferrer Garcia, Natividad; Castaneda Mucino, Antonia; Faller, Blanca

    2008-01-01

    One of the key elements to guide the improvement of the regulatory control is the availability of a self-assessment tool for regulatory performance. Although there is general guidance on self-assessment for regulators and users (IAEA), there is a need for more specific advice on how to address challenges and difficulties faced by regulatory bodies, when regulating radiation protection of patients. Examples of these challenges are the need for regulatory initiatives, in cooperation with health and education authorities, professional bodies and equipment suppliers, and to put in place necessary elements that are beyond responsibility of individual user of radiation, to enable them compliance with safety standards. Purpose: Within the programme of the Ibero American Forum of Nuclear and Radiation Safety Regulatory Organizations, a project to develop such a self-assessment tool for the regulatory control of medical exposure has been designed. Method: National experiences in transposing and enforcing the international radiation safety standards, as to how the requirements are included in national regulations are reviewed. Further, difficulties to the implementation of safety requirements are analyzed and a self-assessment approach and possible regulatory solutions a are presented. Results and discussion: In this study the following documents are being produced: 1) transposition of international requirements into national regulations in the six countries of the Forum, 2) difficulties to implement and enforce the requirements, 3) guidance on self-assessment of regulatory framework for medical exposure, 4) suggested contribution to the revision of international radiation safety standards. (author)

  5. ATMPs for Cancer Immunotherapy: A Regulatory Overview.

    Science.gov (United States)

    Galli, Maria Cristina

    2016-01-01

    This chapter discusses European regulatory requirements for development of advanced therapy medicinal products (ATMP) for cancer immunotherapy approaches, describing the framework for clinical trials and for marketing authorization.Regulatory critical issues and challenges for developing ATMP are also discussed, with focus on potency determination, long-term follow-up, comparability, and insertional mutagenesis issues. Some of the most critical features of GMP application to ATMP are also described.

  6. Governmental, Legal and Regulatory Framework for Safety. General Safety Requirements. Part 1 (Spanish Edition)

    International Nuclear Information System (INIS)

    2010-01-01

    The objective of this publication is to establish requirements in respect of the governmental, legal and regulatory framework for safety. It covers the essential aspects of the framework for establishing a regulatory body and taking other actions necessary to ensure the effective regulatory control of facilities and activities utilized for peaceful purposes. Other responsibilities and functions, such as liaison within the global safety regime and on support services for safety (including radiation protection), emergency preparedness and response, nuclear security, and the State system of accounting for and control of nuclear material, are also covered

  7. Governmental, Legal and Regulatory Framework for Safety. General Safety Requirements. Part 1 (French Edition)

    International Nuclear Information System (INIS)

    2010-01-01

    The objective of this publication is to establish requirements in respect of the governmental, legal and regulatory framework for safety. It covers the essential aspects of the framework for establishing a regulatory body and taking other actions necessary to ensure the effective regulatory control of facilities and activities utilized for peaceful purposes. Other responsibilities and functions, such as liaison within the global safety regime and on support services for safety (including radiation protection), emergency preparedness and response, nuclear security, and the State system of accounting for and control of nuclear material, are also covered

  8. Governmental, Legal and Regulatory Framework for Safety. General Safety Requirements. Part 1 (Chinese Edition)

    International Nuclear Information System (INIS)

    2010-01-01

    The objective of this publication is to establish requirements in respect of the governmental, legal and regulatory framework for safety. It covers the essential aspects of the framework for establishing a regulatory body and taking other actions necessary to ensure the effective regulatory control of facilities and activities utilized for peaceful purposes. Other responsibilities and functions, such as liaison within the global safety regime and on support services for safety (including radiation protection), emergency preparedness and response, nuclear security, and the State system of accounting for and control of nuclear material, are also covered

  9. Governmental, Legal and Regulatory Framework for Safety. General Safety Requirements. Part 1 (Arabic Edition)

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2010-09-15

    The objective of this publication is to establish requirements in respect of the governmental, legal and regulatory framework for safety. It covers the essential aspects of the framework for establishing a regulatory body and taking other actions necessary to ensure the effective regulatory control of facilities and activities utilized for peaceful purposes. Other responsibilities and functions, such as liaison within the global safety regime and on support services for safety (including radiation protection), emergency preparedness and response, nuclear security, and the State system of accounting for and control of nuclear material, are also covered.

  10. Regulation of Federal radioactive waste activities. Summary of report to Congress on extending the Nuclear Regulatory Commission's licensing or regulatory authority to Federal radioactive waste storage and disposal activities

    International Nuclear Information System (INIS)

    Smith, R.D.

    1979-09-01

    The NRC Authorization Bill for FY 1979 directed NRC to conduct a study of extending the Commission's licensing or regulatory authority to include categories of existing and future Federal radioactive waste storage and disposal activities not presently subject to such authority. The report includes a complete listing and inventory of all radioactive waste storage and disposal activities now being conducted or planned by Federal agencies. The NRC study has attempted to present a general comparison of the relative hazards associated with defense-generated and commercial wastes. Options for extending Commission authority were developed and analyzed. The implications of NEPA were analyzed in the context of these options. The national security implications of extending NRC's regulatory authority over DOE programs are examined and evaluated. Costs and benefits are identified and assessed. The Commission's recommendations, based on the study, are to extend licensing authority over new DOE disposal activities involving transuranic wastes and non-defense low-level waste and to initiate a pilot program to test the feasibility of NRC playing a consultative role in the evaluation of existing DOE activities

  11. Intercomparison run for uranium and tritium determination in urine samples, organised by Nuclear Regulatory Authority, Argentina

    International Nuclear Information System (INIS)

    Serdeiro, Nelida H.; Equillor, Hugo E.; Bonino, Nestor O.

    2003-01-01

    The Nuclear Regulatory Authority (ARN), Argentina, has carried out an intercomparison run for tritium and uranium determination in urine, in November 2002. The aim of this exercise was to assess the performance of the laboratories that usually inform these radionuclides and to provide technical support in order to have an appropriate occupational monitoring in vitro. In the present work, the results of the intercomparison and the assessment of each laboratory are published. (author)

  12. Regulatory philosophy and requirements for radiation control in Canadian uranium mine-mill facilities

    International Nuclear Information System (INIS)

    Dory, A.B.

    1981-10-01

    The approach the Canadian Atomic Energy Control Board takes in licensing uranium mine/mill facilities is based on a minimum of rigidly set regulatory requirements. The regulations state only the basic objectives: the obligation to acquire a licence, some administrative and reporting requirements, and exposure limits. The regulations are supported by a set of regulatory guides. The operator always has the option of following different procedures if he can demonstrate that they will produce the same or better results. Good relationships exist between the AECB and mine management as well as trade unions. Under this approach, however, it is difficult to take action against uncooperative parties. The Board has decided that a somewhat more formalized system is necessary. New regulations are being drafted, giving more detailed licensing and administrative requirements and covering the areas of ventilation and worker and supervisor education more thoroughly

  13. Review of regulatory requirements relevant to calibration of monitoring instruments in research reactors

    Energy Technology Data Exchange (ETDEWEB)

    Gomaa, Hassan; Khedr, Ahmed; El-Din Talha, Kamal [Egyptian Nuclear and Radiological Regulatory Authority, Cairo (Egypt). Nuclear Safety Engineering Dept.

    2015-05-15

    The objective of this work is to demonstrate the regulatory requirements pertaining to calibration of monitoring instruments in research reactors. The regulatory statements concerning this subject in IAEA safety standards and the implementation of such regulations in twelve countries with different levels of nuclear programs are surveyed: Australia, Bulgaria, Canada, Egypt, Finland, Germany, Hungary, Slovenia, South Korea, Spain, United Kingdom of England and United States of America. In addition, the requirements of ISO/IEC17025 and NUPIC (Nuclear Utilities Procurement Issues Committee) are compared. Seven technical and administrate aspects are suggested as the comparison criteria and the explicit expression of the statements, the level of document (i.e.: act, requirement or guide) are the considered resources. The main differences and similarities between the different approaches are identified in order to provide an input for future development of the national regulations.

  14. Cost-benefit and regulatory decision making

    International Nuclear Information System (INIS)

    Harvie, J.

    1996-01-01

    The Atomic Energy Control Board is investigating the feasibility of developing methods for factoring cost-benefit considerations into its regulatory decision-making. This initiative results, in part, from the federal government policy requiring cost-benefit considerations to be taken into account in regulatory processes, and from the recommendations of an Advisory Panel on Regulatory Review in 1993, submitted to the Minister of Natural Resources Canada. One of these recommendations stated: 'that mechanisms be developed to examine cost benefit issues and work towards some consensus of opinion among stake holders: a task force on the subject could be an appropriate starting point'. (author)

  15. Assessment of the effectiveness of the Hungarian nuclear safety regulatory authority by international expert teams

    International Nuclear Information System (INIS)

    Voeroess, L.; Lorand, F.

    2001-01-01

    On the basis of the role nuclear regulatory authorities (NRA) have to fulfil and the new challenges affecting them, in the paper an overview is made on how the Hungarian NRA has evaluated and utilised the results of different international efforts in the enhancement of its effectiveness and efficiency. The reviews have been conducted by different groups of experts organised by highly recognised international organisations (e.g. IAEA, EC) and highly competent foreign regulatory bodies. The different reviews of activities and working conditions of the HAEA NSD have resulted in a generally positive picture, however, it also revealed weaknesses as well. They recognised the developments made in recent years and also appreciated the overall favourable level of nuclear safety in Hungary, identified 'good practices' and made recommendations and suggestions for the most important and most efficient ways for future improvements. These are cited or referenced in the paper. At the end, some recommendations have been formed based on the experiences gained from the review missions and from our self-assessment. (author)

  16. Regulatory issues in the maintenance of Argentine nuclear power plants

    International Nuclear Information System (INIS)

    Castro, E.; Caruso, G.

    1997-01-01

    The influence of maintenance activities upon nuclear safety and their relevance as means to detect and prevent aging make them play an outstanding role among the fields of interest of the Argentine nuclear regulatory body (ENREN). Such interest is reinforced by the fact that the data obtained during maintenance are used - among other - as inputs in the Probabilistic Safety Analyses required for those nuclear power plants. This paper provides a brief description of the original requirements by the regulatory body concerning maintenance, of the factors that led to review the criteria involved in such requirements and of the key items identified during the reviewing process. The latter shall be taken into account in the maintenance regulatory policy, for the consequent issue of new requirements from the utilities and for the eventual publication of a specific regulatory standard. (author)

  17. Situation of the medical physics in the Republic of Argentina. Regulatory problem linked to the requirement of physic specialists

    International Nuclear Information System (INIS)

    Arbor Gonzalez, A.; Larcher, A.; Blanco, S.

    2001-01-01

    This paper provides up-to-date data on the participation of medical physicists in current staffs for radiotherapy, nuclear medicine and diagnostic radiology in Argentina, and it presents projections on the academic education of specialists in the next five years. At the same time, the regulatory framework including the requirements for physicists staffing levels in medical practices is presented. This panorama permits to stick out the important role of the professional associations and the academic institutions in the development of Medical Physics in the country. (author)

  18. Regulatory requirements to the thermal-hydraulic and thermal-mechanical computer codes

    International Nuclear Information System (INIS)

    Vitkova, M.; Kalchev, B.; Stefanova, S.

    2006-01-01

    The paper presents an overview of the regulatory requirements to the thermal-hydraulic and thermal-mechanical computer codes, which are used for safety assessment of the fuel design and the fuel utilization. Some requirements to the model development, verification and validation of the codes and analysis of code uncertainties are also define. Questions concerning Quality Assurance during development and implementation of the codes as well as preparation of a detailed verification and validation plan are briefly discussed

  19. Method for developing cost estimates for generic regulatory requirements

    International Nuclear Information System (INIS)

    1985-01-01

    The NRC has established a practice of performing regulatory analyses, reflecting costs as well as benefits, of proposed new or revised generic requirements. A method had been developed to assist the NRC in preparing the types of cost estimates required for this purpose and for assigning priorities in the resolution of generic safety issues. The cost of a generic requirement is defined as the net present value of total lifetime cost incurred by the public, industry, and government in implementing the requirement for all affected plants. The method described here is for commercial light-water-reactor power plants. Estimating the cost for a generic requirement involves several steps: (1) identifying the activities that must be carried out to fully implement the requirement, (2) defining the work packages associated with the major activities, (3) identifying the individual elements of cost for each work package, (4) estimating the magnitude of each cost element, (5) aggregating individual plant costs over the plant lifetime, and (6) aggregating all plant costs and generic costs to produce a total, national, present value of lifetime cost for the requirement. The method developed addresses all six steps. In this paper, we discuss on the first three

  20. Radiation safety in educational, medical and research institutions. Regulatory guide G-121

    International Nuclear Information System (INIS)

    2000-05-01

    This regulatory guide is intended to help educational, medical and research institutions design and implement radiation protection programs that meed regulatory requirements. This guide applied to educational, medical or research institutions that require a licence from the CNSC to posses or use radioactive materials. It describes programs to assure that radioactive materials are used safely during licensed activities. (author)

  1. International conference on strengthening of nuclear safety in Eastern Europe. Armenian Nuclear Regulatory Authority

    International Nuclear Information System (INIS)

    Nersesyan, V.

    1999-01-01

    The status of the Armenian Nuclear Regulatory Authority (ANRA) are described in detail with its main task and responsibilities concerning regulations and surveillance of nuclear and radiation safety. The following issues are presented: nuclear legislation; inspection activities; licensing of significant safety related modifications and modernization of NPPs; incidents at NPPs; personnel training; emergency planning; surveillance of nuclear materials; radioactive waste management; and plan of the ANRA perspective development

  2. Federal and state regulatory requirements for decontamination and decommissioning at US Department of Energy Oak Ridge Operations Facilities

    International Nuclear Information System (INIS)

    Etnier, E.L.; Houlberg, L.M.; Bock, R.E.

    1994-06-01

    The purpose of this report is to address regulatory requirements for decontamination and decommissioning (D and D) activities at the Oak Ridge Reservation and Paducah Gaseous Diffusion Plant. This report is a summary of potential federal and state regulatory requirements applicable to general D and D activities. Excerpts are presented in the text and tables from the complete set of regulatory requirements. This report should be used as a guide to the major regulatory issues related to D and D. Compliance with other federal, state, and local regulations not addressed here may be required and should be addressed carefully by project management on a site-specific basis. The report summarizes the major acts and implementing regulations (e.g., Resource and Conservation Recovery Act, Clean Air Act, and Toxic Substances Control Act) only with regard to D and D activities. Additional regulatory drivers for D and D activities may be established through negotiated agreements, such as the Federal Facility Agreement and the US Environmental Protection Agency Mixed Waste Federal Facility Compliance Agreement; these are discussed in this report. The DOE orders and Energy Systems procedures also are summarized briefly in instances where they directly apply to D and D

  3. Governmental, Legal and Regulatory Framework for Safety. General Safety Requirements. Part 1, Revision 1 (Chinese Edition)

    International Nuclear Information System (INIS)

    2016-01-01

    This publication establishes requirements in respect of the governmental, legal and regulatory framework for safety. It covers the essential aspects of the framework for establishing a regulatory body and taking other actions necessary to ensure the effective regulatory control of facilities and activities utilized for peaceful purposes. Other responsibilities and functions, such as liaison within the global safety regime and on support services for safety (including radiation protection), emergency preparedness and response, nuclear security, and the State system of accounting for and control of nuclear material, are also covered. A review of Safety Requirements publications was commenced in 2011 following the accident in the Fukushima Daiichi nuclear power plant in Japan. The review revealed no significant areas of weakness and resulted in just a small set of amendments to strengthen the requirements and facilitate their implementation, which are contained in the present publication.

  4. Technical and scientific support to nuclear regulatory authority in Montenegro. Present situation and outlooks for the future

    International Nuclear Information System (INIS)

    Jovanovic, S.

    2007-01-01

    Nuclear regulatory competences in the Republic of Montenegro are shared between the ministries of health and of the environment. Following the independence of the country by mid 2006, Radiation Protection Commission (RPC) is established within the Ministry of Health, so as to match the regulatory role for the sources used in medicine. A similar step is expected to be made soon within the Ministry of the Environment, too. The two commissions will likely and logically merge into one, representing an interim regulatory authority to be functioning until a full capacity and effectively independent regulatory body is established by new nuclear law. Promulgation of the latter is expected to take part in the course of 2007. Let us mention here that the law in force is one from 1996 - quite obsolete and not taking into consideration the Basic Safety Standards (IAEA, 1996) and subsequent IAEA and EU documents in the field. Montenegro is a small, non-nuclear country (no nuclear installations or fuel cycle segments), the use of radiation sources being limited mostly to medical and industrial applications. Technical support to regulatory functions, in whatever basic form these were effectuated up to now, was/is given by the Centre for Eco-Toxicological Research of Montenegro (CETI), Department of Radiation Protection and Monitoring, in Podgorica. As to scientific support, it is fundamentally to be found at the University of Montenegro, Faculty of Sciences (FS), Department of Physics. While CETI is relatively well equipped, running quite a modern nuclear spectrometry laboratory (alpha, beta and gamma spectrometry, radon measurements) and having a decent dosimetry unit (TLD, field and workplace monitoring), FS is practically limited to sporadic theoretical studies, with very poor laboratory capabilities. Environmental radioactivity monitoring is performed by CETI, following the programme defined by the government. Licensing and inspections are the two regulatory functions still

  5. Regulatory difficulties in a developing country

    International Nuclear Information System (INIS)

    Jacobs, W.R. Jr.

    1978-01-01

    The regulatory agency assigned the task of regulating the initial entry into the field of nuclear power generation by a developing country has a very difficult job. Based on the authors' experience during the start-up and initial operation of Ko-Ri Unit I, the first power reactor in the Republic of Korea, observations on regulatory difficulties and recommendations for improved regulatory effectiveness are offered. The problem areas can be loosely grouped into three general categories: (1) Lack of adequate technical knowledge which is the basis for all effective regulation; (2) Difficulties with understanding and utilization of the required regulatory documentation; (3) Failure to establish the proper regulatory environment. Examples are cited from actual experience during the Ko-Ri Unit I start-up to demonstrate the impact that regulatory activities can have on a plant construction and testing programme. The problems encountered are not unique to developing countries but also exist in the United States of America. Recommendations are offered which should be beneficial to either newly formed regulatory agencies or agencies wishing to improve their abilities and effectiveness. These include: (1) Additional training of regulatory inspectors in plant operations; (2) Additional experience gained by participation in regulatory activities in other countries; (3) Increased attention given to regulatory documents, especially plant technical specifications; (4) Establishment of formal lines of communication between the utility and the regulatory agency; (5) Clear definition of regulatory responsibilities to avoid areas of overlapping jurisdiction; (6) Active participation by the regulatory staff very early in the project. It is hoped that these and other recommendations offered will greatly improve regulatory effectiveness and at the same time demonstrate that when the decision is made to 'go nuclear', a strong commitment must be made to develop and support a technically

  6. Continuous Improvement of the Regulatory Framework for the Control of Medical Exposure

    International Nuclear Information System (INIS)

    Larcher, A.M.; Ortiz lopez, Pedro; Arias, Cesar; Marechal, Maria H.; Hernandez Alvarez, Ramon; Ferrer Garcia, Natividad; Castaneda Mucino, Antonia; Faller, Blanca

    2011-01-01

    Background: One of the key elements to guide the improvement of the regulatory control is the availability of a self-assessment tool for regulatory performance. Although there is general guidance on self-assessment for regulators and users (IAEA), there is a need for specific advice on how to address challenges and difficulties faced by regulatory bodies, when regulating radiation protection of patients. Examples of these challenges are the need of regulatory initiatives, in cooperation with health and education authorities, professional bodies and equipment suppliers, and to put in place necessary elements that are beyond responsibility of individual users of radiation, to enable them compliance with safety standards. Purpose: within the programme of the Ibero American Forum of Nuclear and Radiation Safety Regulatory Organizations, a project to develop such a self assessment tool for the regulatory control of medical exposure has been designed. Method: national experiences in transposing and enforcing the international radiation safety standards, as to how the requirements are included in national regulations are reviewed. Further, difficulties to the implementation of safety requirements are included in national regulations are analyzed and a self assessment approach and possible regulatory solutions are presented. Results and discussion: in tis study the following documents are being produced: 1) Transposition of international requirements into national regulations in the six countries of the Forum, 2) difficulties to implement and enforce the requirements, 3) guidance on self assessment of regulatory framework for medical exposure, 4) suggested contribution to the revision of international radiation safety standards. (authors)

  7. Regulatory Requirements to Combat Illicit Trafficking of Hazardous Materials

    International Nuclear Information System (INIS)

    Hussein, A.Z.; Zakaria, Kh.M.

    2011-01-01

    Since more than a decade illicit Trafficking of hazardous ( CBRNE), materials ( chemical, biological, radiological, nuclear and explosive ) has been identified as a key threat in national, regional, inter regional and international strategies. An Effective response to hazardous materials (CBRNE) risk and threat were realized to require a very high level of cooperation and coordination between various governments and their responsible organizations and authorities of regional and international partner. While improper policy of actions may easily be exploited by non- state members to (CBRNE) trafficking which may lead to develop weapon of mass destruction (WMD). Such strategy are of paramount important between all levels of the states and among regional agreements through comprehensive tailored assistance packages (e.g. export control, illicit trafficking of hazardous materials, redirection of scientist, emergency planning, crisis response safety and security culture. Capacity building, action plans and instruments for stability are necessary actions for efficient combating against illicit trafficking of hazardous materials. Regarding the needs of assessment phase, assistance must be based on data collection, analysis and prioritization of implanting the regulatory controls. Several activities have to be conducted to reduce CBRNE threat. The one- by- one approach, covering either nuclear and radioactive or chemical or biological materials has to be implanted on the country basis performance to mitigate CBRNE hazardous risk. On several consequent phases of intervention dealing with CBRNE risk mitigation the country has to establish a network of local, regional and international capabilities. Such network is setting up the mechanism for the country needs identifications, the guidelines for data collection, for data platform maintenance and update, the data assessment and the competent and operative organizations. This network will be to strengthen the long - term

  8. Regulatory requirements important to Hanford single-shell tank waste management decisions

    International Nuclear Information System (INIS)

    Keller, J.F.; Woodruff, M.G.

    1989-06-01

    This report provides an initial analysis of the regulations that may be pertinent to SST management activities (e.g., characterization, disposal, retrieval, processing, etc.) and the interrelationships among those regulations. Waste disposal decisions regarding SST waste must consider the regulatory requirements against which technical solutions will be evaluated. Regulatory requirements can also be used as guidelines for management and disposal of waste in a manner that protects human health and safety and the environment. Also, in cases where waste management regulations do not specifically address a waste form, such as radioactive mixed waste, the SST waste may come under the purview of a number of regulations related to radioactive waste management, hazardous waste management, and water and air quality protection. This report provides a comprehensive review of the environmental pollution control and radioactive waste management statutes and regulations that are relevant to SST waste characterization and management. Also, other statutes and regulations that contain technical standards that may be used in the absence of directly applicable regulations are analyzed. 8 refs., 4 figs

  9. 40 CFR 70.11 - Requirements for enforcement authority.

    Science.gov (United States)

    2010-07-01

    ... 40 Protection of Environment 15 2010-07-01 2010-07-01 false Requirements for enforcement authority. 70.11 Section 70.11 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) AIR...) Burden of proof. The burden of proof and degree of knowledge or intent required under State law for...

  10. 40 CFR 281.41 - Requirements for enforcement authority.

    Science.gov (United States)

    2010-07-01

    ... 40 Protection of Environment 26 2010-07-01 2010-07-01 false Requirements for enforcement authority. 281.41 Section 281.41 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) SOLID... for each day of violation. (b) The burden of proof and degree of knowledge or intent required under...

  11. 47 CFR 15.305 - Equipment authorization requirement.

    Science.gov (United States)

    2010-10-01

    ... Section 15.305 Telecommunication FEDERAL COMMUNICATIONS COMMISSION GENERAL RADIO FREQUENCY DEVICES Unlicensed Personal Communications Service Devices § 15.305 Equipment authorization requirement. PCS devices... 2 of this chapter before marketing. The application for certification must contain sufficient...

  12. Role of partnership in enhancing the performance of radiation regulatory authority in Zambia

    International Nuclear Information System (INIS)

    Banda, S.C.

    2003-01-01

    The National Radiation Infrastructure includes legislation, human resource, technical capacity to execute responsibilities of the regulatory (1). In cases of developing countries like Zambia, special challenges arise in view of the constraints both in terms of human resource and funding. This paper will highlight same measures that may be undertaken to improve the operations of nation radiation protection infrastructure. The measures include collaboration with Science and Technology organisations that have technical capacity, delegation of responsible to key institutions that may have competence and generation of funds through training and provision of reliable quality service. (2). In Zambia, some achievements in this line have been registered by Radiation Protection Board working with the University of Zambia and National Institute for Scientific and Industrial Research (3). Some measures of generation of funds have been done though utilization of the generated remains to be the limiting factor to exploit fully benefits that may arise from the use of the monies generated from services. Partnerships with private sector may be used as regulatory authorities for support to its programme in particular the public awareness campaign. Sponsorship by a Private Cellar Phone Company (Telecel Zambia) and Rotary Club of Lusaka for Radiation Week to Radiation Protection Service under Theme 'Safe Radiation Use' is one such an example. The other opportunity is the technical cooperation with regional and international organisations such as SADC, IAEA, WHO, Interpol, EU and WCO for technical capacity building, human resource development and information access. (author)

  13. Regulatory Control of Radiation Sources. Safety Guide (Arabic Edition)

    International Nuclear Information System (INIS)

    2012-01-01

    This Safety Guide is intended to assist States in implementing the requirements established in Safety Standards Series No. GS-R-1, Legal and Governmental Infrastructure for Nuclear, Radiation, Radioactive Waste and Transport Safety, for a national regulatory infrastructure to regulate any practice involving radiation sources in medicine, industry, research, agriculture and education. The Safety Guide provides advice on the legislative basis for establishing regulatory bodies, including the effective independence of the regulatory body. It also provides guidance on implementing the functions and activities of regulatory bodies: the development of regulations and guides on radiation safety; implementation of a system for notification and authorization; carrying out regulatory inspections; taking necessary enforcement actions; and investigating accidents and circumstances potentially giving rise to accidents. The various aspects relating to the regulatory control of consumer products are explained, including justification, optimization of exposure, safety assessment and authorization. Guidance is also provided on the organization and staffing of regulatory bodies. Contents: 1. Introduction; 2. Legal framework for a regulatory infrastructure; 3. Principal functions and activities of the regulatory body; 4. Regulatory control of the supply of consumer products; 5. Functions of the regulatory body shared with other governmental agencies; 6. Organization and staffing of the regulatory body; 7. Documentation of the functions and activities of the regulatory body; 8. Support services; 9. Quality management for the regulatory system.

  14. Substate federalism and fracking policies: does state regulatory authority trump local land use autonomy?

    Science.gov (United States)

    Davis, Charles

    2014-01-01

    State officials responsible for the regulation of hydraulic fracturing (fracking) operations used in the production of oil and gas resources will inevitably confront a key policy issue; that is, to what extent can statewide regulations be developed without reducing land use autonomy typically exercised by local officials? Most state regulators have historically recognized the economic importance of industry jobs and favor the adoption of uniform regulatory requirements even if these rules preempt local policymaking authority. Conversely, many local officials seek to preserve land use autonomy to provide a greater measure of protection for public health and environmental quality goals. This paper examines how public officials in three states-Colorado, Pennsylvania, and Texas-address the question of state control versus local autonomy through their efforts to shape fracking policy decisions. While local officials within Texas have succeeded in developing fracking ordinances with relatively little interference from state regulators, Colorado and Pennsylvania have adopted a tougher policy stance favoring the retention of preemptive oil and gas statutes. Key factors that account for between state differences in fracking policy decisions include the strength of home rule provisions, gubernatorial involvement, and the degree of local experience with industrial economic activities.

  15. 77 FR 61463 - Self-Regulatory Organizations; EDGA Exchange, Inc.; Notice of Filing and Immediate Effectiveness...

    Science.gov (United States)

    2012-10-09

    ... entry of erroneous orders. In addition, the Market Access Rule requires certain regulatory risk... authorized by the broker-dealer. These regulatory risk management controls also include measures designed to...-Regulatory Organizations; EDGA Exchange, Inc.; Notice of Filing and Immediate Effectiveness of Proposed Rule...

  16. 77 FR 61449 - Self-Regulatory Organizations; EDGX Exchange, Inc.; Notice of Filing and Immediate Effectiveness...

    Science.gov (United States)

    2012-10-09

    ..., regulatory and other risks of this business activity. These controls include financial risk management... entry of erroneous orders. In addition, the Market Access Rule requires certain regulatory risk... authorized by the broker-dealer. These regulatory risk management controls also include measures designed to...

  17. Cost-benefit considerations in regulatory decision-making

    International Nuclear Information System (INIS)

    Harvie, J.D.

    1996-01-01

    The Atomic Energy Control Board is investigating the feasibility of developing methods for factoring cost-benefit considerations into its regulatory decision-making. This initiative results, in part, from the federal government policy requiring cost-benefit considerations to be taken into account in regulatory processes, and from the recommendations of an Advisory Panel on Regulatory Review in 1993, submitted to the Minister of Natural Resources Canada. One of these recommendations stated: 'that mechanisms be developed to examine cost-benefit issues and work towards some consensus of opinion among stakeholders; a task force on the subject could be an appropriate starting point'. (author)

  18. U.S. regulatory requirements for nuclear plant license renewal: The B and W Owners Group License Renewal Program

    International Nuclear Information System (INIS)

    Staudinger, Deborah K.

    2004-01-01

    This paper discusses the current U.S. Regulatory Requirements for License Renewal and describes the Babcock and Wilcox Owners Group (B and WOG) Generic License Renewal Program (GLRP). The B and W owners, recognizing the need to obtain the maximum life for their nuclear generating units, embarked on a program to renew the licenses of the seven reactors in accordance with the requirements of the Atomic Energy Act of 1954 and further defined by Title 10 of the Code of Federal Regulation Part 54 (10 CFR 54). These reactors, owned by five separate utilities, are Pressurized Water Reactors (PWR) ranging in net rated capacity from approximately 800 to 900 MW. The plants, predominately constructed in the 70s, have USNRC Operating Licenses that expire between 2013 to 2017. (author)

  19. South African Regulatory Framework for Nuclear Power Plant Life Management

    International Nuclear Information System (INIS)

    Mbebe, B.Z.

    2012-01-01

    The paper presents the regulatory approach to plant life management (PLiM) adopted by the National Nuclear Regulator (NNR) in South Africa, the licensing basis and regulatory requirements for Koeberg Nuclear Power Station (KNPS),operational programmes ensuring continued safe operation, issues related to the ageing of the plant, and the requirements for spent fuel as well as radioactive waste management. The paper will further present insights from the Periodic Safety Review (PSR) and Long Term Asset Management. (author)

  20. Strengthening Regulatory Competence in a Changing Nuclear Regulatory Environment

    International Nuclear Information System (INIS)

    Illizastigui, P.F.

    2016-01-01

    The paper addresses the approach followed by the Cuban National Center for Nuclear Safety for the management of current and new competences of its regulatory staff with the aim of allowing those staff to effectively fulfill their core regulatory functions. The approach is realized through an Integrated System for Competence Building, which is based on the IAEA recommendations, shown to be effective in ensuring the necessary competence in the relevant areas. In the author’s opinion, competence of the regulatory staff in the area of human and organizational factors is of paramount importance and needs to be further strengthened in order to be able to assess safety performance at the facilities and detect early signs of deteriorating safety performance. The former is defined by the author as the core regulatory function “Analysis” which covers the entire spectrum of assessment tasks carried out by the regulatory staff to: a) detect declining safety performance, b) diagnose latent weaknesses (root causes) and c) make effective safety culture interventions. The author suggests that competence associated with the fulfillment of the analysis function is distinctly identified and dealt with separately in the current system of managing regulatory competence. (author)

  1. Legislative framework and regulatory requirements for the introduction of nuclear power

    International Nuclear Information System (INIS)

    Ha-Vinh, Phuong

    1975-01-01

    The adoption of appropriate legislation is to be considered as a prerequisite to the introduction of nuclear power in view of the issues that need to be regulated. Preparatory steps should be started at the earliest stage in conjunction with the planning of nuclear power projects. The primary objectives of a licensing scheme are to ensure safety, public health and environmental protection as well as financial protection for third parties in case of nuclear incident. For licensing purposes, a legislative framework and regulatory determinations are required. Within such a framework and pursuant to such regulatory determinations, the elaboration of safety standards, rules, guides and enforcement procedures is to be considered of paramount importance. To this end a number of international recommendations and advisory material prepared by the IAEA provide useful guidance. A licensing process would normally be split into several stages relating to site approval, construction permit, pre-operational tests, and operating licence, each stage being subject to safety assessments and reviews as determined by regulations. Financial protection against nuclear damage has also to be insured. A special regime of nuclear liability has been established by international conventions, based on the principle of strict liability of the operator of a nuclear installation. As a result of such channelling of liability to him, his liability is limited in amount and time. This liability system has the dual purpose of ensuring appropriate protection for potential victims and of relieving the nuclear industry from unlimited liability risks, which would impede practical applications of atomic energy. For the elaboration of nuclear legislation and specialized regulations the Agency's advisory services have proved to be of help to countries embarking on a nuclear power programme. (author)

  2. Amendment to the Decree of the Slovak Nuclear Regulatory Authority on details concerning emergency planning in case of nuclear incident or accident

    International Nuclear Information System (INIS)

    Biharyová, Michaela

    2018-01-01

    Following up amendment to the Slovak Atomic Act, the Decree No. 55/2006 on details concerning emergency planning in case of nuclear incident or accident has also been amended now. Following a short introductory text by the author, the entire text of the ‘Decree of the Nuclear Regulatory Authority of the Slovak Republic No 9/2018 Coll. of 2 January 2018 amending Decree of the Nuclear Regulatory Authority of the Slovak Republic No 55/2006 Coll. on details in emergency planning in case of nuclear incident or accident as amended by Decree No. 35/2012 Coll.’ is reproduced. The Amendment entered into force 1 February 2018. (orig.)

  3. Regulatory quality assurance requirements for the operation of nuclear R and D facilities in Korea

    International Nuclear Information System (INIS)

    Kwon, H.I.; Lim, N.J.

    2006-01-01

    Full text: Korea Atomic Energy Research Institute (KAERI) has many R and D facilities in operation. including HANARO research reactor, radioactive waste treatment facility (RWTF), post-irradiation examination facility (PIEF) and irradiated material test facility (IMEF). Recently. nation-wide interest is focused on the safety and security of major industrial facilities. Safe operation of nuclear facilities is imperative because of the consequence of public disaster by radiological release/contamination, in case of an accident. Recently, Ministry of Science and Technology (MOST) of the Korean government announced amendments of Atomic Energy laws to enforce requirements of the physical protection and radiological emergency. All provisions on nuclear safety regulation and radiation protection are entrusted to the Atomic Energy Act(AEA). The Act is enacted as the main law concerning the safety regulation of nuclear installations, and is supplemented by the Enforcement Decree and Enforcement Regulation of the Act. These Atomic Energy laws include provisions on the construction permission and the operation license of nuclear installations, such as nuclear power reactors, research reactors, nuclear ships, nuclear fuel fabrication facilities, spent fuel treatment facilities, etc. Regulatory requirements for the regulatory inspection and the safety measures for operation are also defined in the laws. The Notice of the MOST prescribes specific issues including regulatory requirements and technical standards, as entrusted by the AEA, the Decree and the Regulation. Detailed QA requirements for nuclear installations are specified differently, depending upon the type of facility. The guidelines for safety reviews and regulatory inspections are developed by the Korea Institute of Nuclear Safety (KINS), which is an exclusive organization for safety regulation of nuclear installations in Korea. In this paper, the context of the Atomic Energy laws were reviewed to confirm the

  4. Authorization procedure for containers and modalities of transport of radioactive substances within the EC Member States

    International Nuclear Information System (INIS)

    Amaducci, S.

    1977-02-01

    In all EC Member States, the transport of radioactive substances, the activity of which is higher than a specific level, is subject to regulatory requirements. Most of these requirements demand an administrative authorization before starting transport. In Belgium, authorization may take the form of a general, particular or special authorization, and in Luxembourg of a general or particular authorization. The latter applies in France and Italy but in these countries specific provisions also exist depending on the means of transport used. The latter specific provisions also exist in Germany and in the Netherlands. On the contrary in the United Kingdom, no administrative authorization is needed for such transport, except for special consignments. Finally, it is to be noted that neither in Denmark nor in Ireland have regulatory requirements been laid down with respect to such authorization procedure

  5. Report on activities of Nuclear Regulatory Authority of the Slovak Republic and safety of nuclear installations in the Slovak Republic in 2007. Annual report

    International Nuclear Information System (INIS)

    2007-04-01

    A brief account of activities carried out by the Nuclear Regulatory Authority of the Slovak Republic (UJD SR) in 2007 is presented. These activities are reported under the headings: (1) Foreword; (2) Legislation; (3) Issuance of authorizations, assessment, supervisory activities and enforcement; (4) Nuclear safety of nuclear installations in the Slovak Republic; (5) Safety of other nuclear installations; (6) Management of radioactive waste; (7) Nuclear materials; (8) Emergency planning and preparedness; (9) International activities; (10) Public communication; (11) Nuclear Regulatory Authority of the Slovak Republic; (12) Abbreviations

  6. 25 CFR 547.4 - How does a tribal government, tribal gaming regulatory authority, or tribal gaming operation...

    Science.gov (United States)

    2010-04-01

    ... 25 Indians 2 2010-04-01 2010-04-01 false How does a tribal government, tribal gaming regulatory authority, or tribal gaming operation comply with this part? 547.4 Section 547.4 Indians NATIONAL INDIAN GAMING COMMISSION, DEPARTMENT OF THE INTERIOR HUMAN SERVICES MINIMUM TECHNICAL STANDARDS FOR GAMING...

  7. Current status of developmental neurotoxicity: regulatory view

    DEFF Research Database (Denmark)

    Hass, Ulla

    2003-01-01

    in the testing strategy for new and existing substances, and biocides. Hopefully, this will lead to an improved database for risk assessment of potential developmental neurotoxicants. However, the regulatory authorities and toxicologists will also be faced with the challenge that decisions have to be made......The need for developmental neurotoxicity testing has been recognized for decades and guidelines are available, as the USEPA guideline and the OECD draft TG 426. Regulatory testing of industrial chemicals for developmental neurotoxicity is required to some extent, especially for pesticides in the US....... Until recently, however, developmental neurotoxicity testing of industrial chemicals has not been a clear regulatory requirement in EU, probably due to the lack of an accepted OECD TG. The revised EU Technical Guidance Document for Risk Assessment (EU-TGD) has now included the OECD draft TG 426...

  8. TSO Role in Supporting the Regulatory Authority in View of Safety Culture

    International Nuclear Information System (INIS)

    Khamaza, A.; Vasilishin, A.

    2016-01-01

    Human and organizational factors are always of paramount importance at nuclear and radiation safety as well as in the safety regulation provision. Major NPP accidents occurred merely reaffirm this fact. The role of an authority that regulates nuclear safety increases each time in the aftermath of accidents perceived as a shock together with the importance of scientific and technical support. SEC NRS was established in 1987, the next year after the Chernobyl NPP accident aiming to strengthen supervision over works carried out at the nuclear industry enterprises. Currently SEC NRS provides comprehensive scientific and technical support to Rostechnadzor including safety review and regulatory legal documents development to regulate safety along with safety culture.

  9. An epidemiological analysis of equine welfare data from regulatory inspections by the official competent authorities.

    Science.gov (United States)

    Hitchens, P L; Hultgren, J; Frössling, J; Emanuelson, U; Keeling, L J

    2017-07-01

    welfare if they also complied with documentation requirements. We present a novel approach for analysis of equine welfare data from regulatory inspections by the official competent authorities, and propose on-going analyses and benchmarking of trends in animal-based measures over time. We also suggest how such a database could be further improved to facilitate future epidemiological analyses of risk factors associated with poor equine welfare. The study has implications for other competent authorities and researchers collaborating in the area of animal welfare epidemiology.

  10. Communication and Consultation with Interested Parties by the Regulatory Body. General Safety Guide

    International Nuclear Information System (INIS)

    2017-01-01

    This Safety Guide provides recommendations on meeting the safety requirements concerning communication and consultation with the public and other interested parties by the regulatory body about the possible radiation risks associated with facilities and activities, and about processes and decisions of the regulatory body. The Safety Guide can be used by authorized parties in circumstances where there are regulatory requirements placed on them for communication and consultation. It may also be used by other organizations or individuals considering their responsibilities for communication and consultation with interested parties.

  11. As to achieve regulatory action, regulatory approaches

    International Nuclear Information System (INIS)

    Cid, R.; Encinas, D.

    2014-01-01

    The achievement of the effectiveness in the performance of a nuclear regulatory body has been a permanent challenge in the recent history of nuclear regulation. In the post-Fukushima era this challenge is even more important. This article addresses the subject from two complementary points of view: the characteristics of an effective regulatory body and the regulatory approaches. This work is based on the most recent studies carried out by the Committee on Nuclear Regulatory Activities, CNRA (OECD/NEA), as well as on the experience of the Consejo de Seguridad Nuclear, CSN, the Spanish regulatory body. Rafael Cid is the representative of CSN in these project: Diego Encinas has participated in the study on regulatory approaches. (Author)

  12. Regulatory requirements for demonstration of the achieved safety level at the Mochovce NPP before commissioning

    International Nuclear Information System (INIS)

    Lipar, M.

    1997-01-01

    A review of regulatory requirements for demonstration of the achieved safety level at the Mochovce NPP before commissioning is given. It contains licensing steps in Slovakia during commissioning; Status and methodology of Mochovce safety analysis report; Mochovce NPP safety enhancement program; Regulatory body policy towards Mochovce NPP safety enhancement; Recent development in Mochovce pre-operational safety enhancement program review and assessment process; Licensing steps in Slovakia during commissioning

  13. 47 CFR 25.118 - Modifications not requiring prior authorization.

    Science.gov (United States)

    2010-10-01

    ... 47 Telecommunication 2 2010-10-01 2010-10-01 false Modifications not requiring prior authorization. 25.118 Section 25.118 Telecommunication FEDERAL COMMUNICATIONS COMMISSION (CONTINUED) COMMON CARRIER SERVICES SATELLITE COMMUNICATIONS Applications and Licenses General Application Filing Requirements § 25...

  14. Regulatory requirements on the calibration and use of survey instruments

    International Nuclear Information System (INIS)

    Domondon, D.B.

    1989-01-01

    Regulatory requirements on the provision, calibration and occasions of use of survey instruments are enumerated for a number of licensed activities. Two methods of calibrating survey instruments are described. Factors that must be taken into consideration in conducting calibrations, contents of calibration reports and of the sticker attached to the instrument which are needed for the correct use of the instrument are discussed. The precautions to be observed in order to insure correct use of survey instruments are described. (Auth.)

  15. A study for the establishment of regulatory requirement and evaluation guide for station blackout in nuclear power plants

    International Nuclear Information System (INIS)

    Lim, J. H.; Koo, C. S.; Joo, W. P.; Oh, S. H.; Shin, W. K.

    1999-01-01

    The consequence of SBO event could be a severe accident unless AC power was restored within a proper time, because many safety systems depend upon AC power. Based on the severity, the SBO has been extensively studied since it was identified as Unresolved Safety Issue at USNRC. The resolution of those studies is a rule-making such as 10 CFR 50.63 and Regulatory Guide 1.155. But there is no regulatory requirements of SBO for an operating domestic nuclear power plant up to the present time. This tudy has established SBO rule(regulatory requirements and evaluation guides) for an operating PWR type of the operating nuclear power plants in Korea

  16. The Report on Activities of the Nuclear Regulatory Authority of the Slovak Republic and on Safety of Nuclear Installations in the Slovak Republic in 2011

    International Nuclear Information System (INIS)

    2012-05-01

    A brief account of activities carried out by the Nuclear Regulatory Authority of the Slovak Republic (UJD SR) in 2011 is presented. These activities are reported under the headings: Foreword; (1) Legislative activities; (2) Regulatory Activities; (3) Nuclear safety of nuclear power plants; (4) Nuclear Materials in SR; (5) Nuclear materials and physical protection of nuclear materials; (6) Scope of powers of the office building; (7) Emergency planning and preparedness; (8) International activities; (9) Public communication; (10) Nuclear Regulatory Authority of the Slovak Republic; (11) UJD SR organization chart; The International Nuclear Event Scale (INES); (12) Abbreviations.

  17. Evolution of New cis-Regulatory Motifs Required for Cell-Specific Gene Expression in Caenorhabditis.

    Directory of Open Access Journals (Sweden)

    Michalis Barkoulas

    2016-09-01

    Full Text Available Patterning of C. elegans vulval cell fates relies on inductive signaling. In this induction event, a single cell, the gonadal anchor cell, secretes LIN-3/EGF and induces three out of six competent precursor cells to acquire a vulval fate. We previously showed that this developmental system is robust to a four-fold variation in lin-3/EGF genetic dose. Here using single-molecule FISH, we find that the mean level of expression of lin-3 in the anchor cell is remarkably conserved. No change in lin-3 expression level could be detected among C. elegans wild isolates and only a low level of change-less than 30%-in the Caenorhabditis genus and in Oscheius tipulae. In C. elegans, lin-3 expression in the anchor cell is known to require three transcription factor binding sites, specifically two E-boxes and a nuclear-hormone-receptor (NHR binding site. Mutation of any of these three elements in C. elegans results in a dramatic decrease in lin-3 expression. Yet only a single E-box is found in the Drosophilae supergroup of Caenorhabditis species, including C. angaria, while the NHR-binding site likely only evolved at the base of the Elegans group. We find that a transgene from C. angaria bearing a single E-box is sufficient for normal expression in C. elegans. Even a short 58 bp cis-regulatory fragment from C. angaria with this single E-box is able to replace the three transcription factor binding sites at the endogenous C. elegans lin-3 locus, resulting in the wild-type expression level. Thus, regulatory evolution occurring in cis within a 58 bp lin-3 fragment, results in a strict requirement for the NHR binding site and a second E-box in C. elegans. This single-cell, single-molecule, quantitative and functional evo-devo study demonstrates that conserved expression levels can hide extensive change in cis-regulatory site requirements and highlights the evolution of new cis-regulatory elements required for cell-specific gene expression.

  18. Exclusion and authorization

    International Nuclear Information System (INIS)

    Cooper, J.R.

    2003-01-01

    'Everyone in the world is exposed to radiation from natural and artificial sources. Any realistic system of radiological protection must have a clearly defined scope if it is not to apply to the whole of mankind's activities'. This quote, from ICRP Publication 60 (ICRP, 1991), remains apposite. The main tool for defining scope is the concept of exclusion: situations, sources or exposures that are excluded from the system of radiological protection are, to all intents and purposes, ignored. Sources and exposures that are not excluded are within the scope of the system of protection and by inference within regulatory systems implementing ICRP recommendations. These sources and exposures should be subject to appropriate authorization by the relevant regulatory authority. In order to avoid excessive regulatory procedures, however, provisions should be made for granting an exemption in cases where it is clear that regulatory provisions are unnecessary. Exemption is a regulatory tool intended to facilitate efficient use of regulatory resources. Nevertheless, the regulatory act of granting exemptions is, in itself, a form of authorization and the material or situation so exempted remains within the regulatory system. This distinction between exclusion and exemption is an important one. Historically, the concept of exclusion has been applied to sources or exposures that are essentially unamenable to control because of their widespread nature. The usually quoted examples are cosmic radiation at ground level and 40 K in the body. Clearly, many exposures from natural sources could fall into this category. The challenges are firstly to establish a sound basis for deciding which should be excluded and which should be controlled, and secondly to see if the concept could or should be applied to artificial sources and exposures. These two questions are the subject of this paper. (author)

  19. Public consultation: regulatory requirement or business principle?

    International Nuclear Information System (INIS)

    Seeley, R.

    1999-01-01

    A summary is included of knowledge and experiences related to planning and implementing a public consultation program over a number of years in Shell Canada's Athabasca Oil Sands development. This project consists of three major sub- projects with a total estimated capital investment of $4 billion. The three sub- projects are: the Muskeg River Mine, the Scotford Upgrader, and the Corridor Pipeline. The facilities will produce 150,000 bbl/day of synthetic crude for over 25 years and are targeted to begin production in late 2002. From the title of the paper, although public consultation is required under environmental legislation, many companies are adopting a more pro-active approach to public consultation and participation as a business principle. This commitment to engage in and dialogue with stakeholders must be open, transparent and long term, not just during the regulatory process. Successful consultation begins with the prerequisites: senior management commitment, buy-in from the project or operating team that the process adds value, and the ability to listen and make changes. A consultation program is not a short term activity, but is rather an ongoing process linked to a business or operating principle. It requires long term resources and follow through on agreements and commitments made to stakeholders and communities

  20. Public consultation: regulatory requirement or business principle?

    Energy Technology Data Exchange (ETDEWEB)

    Seeley, R. [Shell Canada Oil Sands, Calgary, AB (Canada)

    1999-07-01

    A summary is included of knowledge and experiences related to planning and implementing a public consultation program over a number of years in Shell Canada's Athabasca Oil Sands development. This project consists of three major sub- projects with a total estimated capital investment of $4 billion. The three sub- projects are: the Muskeg River Mine, the Scotford Upgrader, and the Corridor Pipeline. The facilities will produce 150,000 bbl/day of synthetic crude for over 25 years and are targeted to begin production in late 2002. From the title of the paper, although public consultation is required under environmental legislation, many companies are adopting a more pro-active approach to public consultation and participation as a business principle. This commitment to engage in and dialogue with stakeholders must be open, transparent and long term, not just during the regulatory process. Successful consultation begins with the prerequisites: senior management commitment, buy-in from the project or operating team that the process adds value, and the ability to listen and make changes. A consultation program is not a short term activity, but is rather an ongoing process linked to a business or operating principle. It requires long term resources and follow through on agreements and commitments made to stakeholders and communities.

  1. 76 FR 57060 - International Cooperation on Harmonisation of Technical Requirements for Registration of...

    Science.gov (United States)

    2011-09-15

    ...] International Cooperation on Harmonisation of Technical Requirements for Registration of Veterinary Medicinal... veterinary use by the International Cooperation on Harmonisation of Technical Requirements for Registration... regulatory authorities and industry associations to promote the international harmonization of regulatory...

  2. Regulation for continuous improvements - the new regulatory strategy of SKI

    International Nuclear Information System (INIS)

    Hoegberg, L.; Svensson, G.; Viktorsson, C.

    1998-01-01

    This paper describes the new regulatory objectives and strategy of the Swedish Nuclear Power Inspectorate. Factors that have influenced the development of the regulatory strategy, including an international peer review, are discussed. In addition to general technical requirements for a defence in depth, the new strategy strongly focuses on the quality of plant safety management processes, to be monitored by process-oriented inspections. Also, quality assurance of regulatory activities is stressed. Experience gained so far shows that the regulatory approach chosen in Sweden promotes utility self assessment, quality of safety management and ownership of safety work within the utility staff. (author)

  3. Hydrogen mitigation systems - a Canadian regulatory perspective

    International Nuclear Information System (INIS)

    Khosla, J.K.; Rizk, M.

    1997-01-01

    This is a discussion paper to examine the regulatory requirements that may be necessary for the design, operation and maintenance of the hydrogen mitigation systems. These systems (if deemed necessary to maintain the containment function), may be considered to be a part of the containment systems. Therefore, these requirements are derived mostly from the AECB Regulatory Document R-7, which specifies the requirements for containment systems for CANDU nuclear power plants. Some additional requirements, which are specific to these systems have also been included. These requirements relate to a systematic examination of the hazards of hydrogen, the design basis for the mitigation systems, their functional and design requirements, analytical support to justify their selection, and operating and testing requirements. The requirements for severe accident have not yet been developed. It is, however, anticipated that the design of the hydrogen mitigation system would be such that future requirement can be accommodated. These requirements are intended for application to the new reactors in Canada. For the existing reactors, their application will be subjected to practicability. (author)

  4. Reliability programs for nuclear power plants. Regulatory standard S-98 revision 1

    International Nuclear Information System (INIS)

    2005-07-01

    The purpose of this regulatory standard is to help assure, in accordance with the purpose of the Nuclear Safety and Control Act (NSCA), that a licensee who constructs or operates a nuclear power plant (NPP) develops and implements a reliability program that assures that the systems important to safety at the plant can and will meet their defined design and performance specifications at acceptable levels of reliability throughout the lifetime of the facility. This regulatory standard describes the requirements of a reliability program for a nuclear power plant. The licensee shall implement the requirements described in this regulatory standard when a condition of a licence or other legally enforceable instrument so requires.(author)

  5. What is a comprehensive system of regulatory governance?

    International Nuclear Information System (INIS)

    Real diaz, F. J.

    2011-01-01

    The progressive evolution and diversification of regulations concerning industrial safety has made their management increasingly complex, requiring more resources of organizations. Therefore, it is advisable that this management be made more efficient through systematization, specialization and the use of computing technologies. This is supported by the implementation of integrated regulatory management systems. This article explain the concept of integrated regulatory management systems, their structure and their advantages. It also includes a model for implementing them in an organization. (Author)

  6. Canadian uranium mines and mills evolution of regulatory expectations and requirements for effluent treatment

    International Nuclear Information System (INIS)

    LeClair, J.; Ashley, F.

    2006-01-01

    The regulation of uranium mining in Canada has changed over time as our understanding and concern for impacts on both human and non-human biota has evolved. Since the mid-1970s and early 1980s, new uranium mine and mill developments have been the subject of environmental assessments to assess and determine the significance of environmental effects throughout the project life cycle including the post-decommissioning phase. Water treatment systems have subsequently been improved to limit potential effects by reducing the concentration of radiological and non-radiological contaminants in the effluent discharge and the total loadings to the environment. This paper examines current regulatory requirements and expectations and how these impact uranium mining/milling practices. It also reviews current water management and effluent treatment practices and performance. Finally, it examines the issues and challenges for existing effluent treatment systems and identifies factors to be considered in optimizing current facilities and future facility designs. (author)

  7. Report on activities of Nuclear Regulatory Authority of the Slovak Republic and safety of nuclear installations in the Slovak Republic in 2009. Annual report

    International Nuclear Information System (INIS)

    2010-04-01

    A brief account of activities carried out by the Nuclear Regulatory Authority of the Slovak Republic (UJD SR) in 2009 is presented. These activities are reported under the headings: (1) Foreword; (2) Legislation; (3) Issuance of authorizations, assessment, supervisory activities and enforcement; (4) Nuclear safety of nuclear installations in the Slovak Republic; (5) Safety of other nuclear installations; (6) Management of radioactive waste; (7) Nuclear materials and physical protection of nuclear materials; (8) Emergency planning and preparedness; (9) International activities; (10) Public communication; (11) Nuclear Regulatory Authority of the Slovak Republic; (12) UJD SR organization chart; (13) Abbreviations.

  8. Report on activities of Nuclear Regulatory Authority of the Slovak Republic and safety of nuclear installations in the Slovak Republic in 2008. Annual report

    International Nuclear Information System (INIS)

    Zemanova, D.; Pirozekova, M.

    2009-04-01

    A brief account of activities carried out by the Nuclear Regulatory Authority of the Slovak Republic (UJD SR) in 2008 is presented. These activities are reported under the headings: (1) Foreword; (2) Legislation; (3) Issuance of authorizations, assessment, supervisory activities and enforcement; (4) Nuclear safety of nuclear installations in the Slovak Republic; (5) Safety of other nuclear installations; (6) Management of radioactive waste; (7) Nuclear materials and physical protection of nuclear materials; (8) Activity of Building Office; (9) Emergency planning and preparedness; (10) International activities; (11) Public communication; (11) Nuclear Regulatory Authority of the Slovak Republic; (12) UJD SR organization chart; (13) Abbreviations

  9. Future nuclear regulatory challenges

    International Nuclear Information System (INIS)

    Royen, J.

    1998-01-01

    In December 1996, the NEA Committee on Nuclear Regulatory Activities concluded that changes resulting from economic deregulation and other recent developments affecting nuclear power programmes have consequences both for licensees and regulatory authorities. A number of potential problems and issues which will present a challenge to nuclear regulatory bodies over the next ten years have been identified in a report just released. (author)

  10. 78 FR 14306 - International Cooperation on Harmonisation of Technical Requirements for Registration of...

    Science.gov (United States)

    2013-03-05

    ...]; (Formerly Docket No. 00D-1631)] International Cooperation on Harmonisation of Technical Requirements for... for veterinary use by the International Cooperation on Harmonisation of Technical Requirements for... regulatory authorities and industry associations to promote the international harmonization of regulatory...

  11. Aggregate analysis of regulatory authority assessors' comments to improve the quality of periodic safety update reports.

    Science.gov (United States)

    Jullian, Sandra; Jaskiewicz, Lukasz; Pfannkuche, Hans-Jürgen; Parker, Jeremy; Lalande-Luesink, Isabelle; Lewis, David J; Close, Philippe

    2015-09-01

    Marketing authorization holders (MAHs) are expected to provide high-quality periodic safety update reports (PSURs) on their pharmaceutical products to health authorities (HAs). We present a novel instrument aiming at improving quality of PSURs based on standardized analysis of PSUR assessment reports (ARs) received from the European Union HAs across products and therapeutic areas. All HA comments were classified into one of three categories: "Request for regulatory actions," "Request for medical and scientific information," or "Data deficiencies." The comments were graded according to their impact on patients' safety, the drug's benefit-risk profile, and the MAH's pharmacovigilance system. A total of 476 comments were identified through the analysis of 63 PSUR HA ARs received in 2013 and 2014; 47 (10%) were classified as "Requests for regulatory actions," 309 (65%) as "Requests for medical and scientific information," and 118 (25%) comments were related to "Data deficiencies." The most frequent comments were requests for labeling changes (35 HA comments in 19 ARs). The aggregate analysis revealed commonly raised issues and prompted changes of the MAH's procedures related to the preparation of PSURs. The authors believe that this novel instrument based on the evaluation of PSUR HA ARs serves as a valuable mechanism to enhance the quality of PSURs and decisions about optimization of the use of the products and, therefore, contributes to improve further the MAH's pharmacovigilance system and patient safety. Copyright © 2015 John Wiley & Sons, Ltd.

  12. Strengthening Regulatory Competence in Pakistan

    International Nuclear Information System (INIS)

    Sadiq, M.

    2016-01-01

    Capacity building of Pakistan Nuclear Regulatory Authority is considered an essential element in pursuit of its vision to become a world class regulatory body. Since its inception in 2001, PNRA has continuously endeavoured to invest in its people, develop training infrastructure and impart sound knowledge and professional skills with the aim to improve its regulatory effectiveness. The use of nuclear and radioactive material in Pakistan has increased manifold in recent years, thus induction of more manpower was needed for regulatory oversight. PNRA adopted two pronged approach for meeting the manpower demand (a) employment of university graduates through fast track recruitment drive and (b) induction of graduates by offering fellowships for Master degree programs. Although, the newly employed staff was selected on the basis of their excellent academic qualifications in basic and applied sciences, but they required rigorous knowledge and skills in regulatory perspectives. In order to implement a structured training program, PNRA conducted Training Needs Assessment (TNA) and identified competency gaps of the regulatory staff in legal, technical, regulatory practice and behavioural domains. PNRA took several initiatives for capacity building which included establishment of a training centre for sustainability of trainings, initiation of a fellowship scheme for Master program, attachment of staff at local institutes for on-the-job training and placement at foreign regulatory bodies and organizations for technical development with the assistance of IAEA. The above strategies have been very beneficial in competence building of the PNRA staff to perform all regulatory activities indigenously for nuclear power plants, research reactors and radiation facilities. Provision of vibrant technical support to IAEA and Member States in various programs by PNRA is a landmark of these competence development efforts. This paper summarizes PNRA initiatives and the International Atomic

  13. Competent authority approval of package designs in the United Kingdom

    International Nuclear Information System (INIS)

    Morgan-Warren, E.J.

    1999-01-01

    Type B packages and all packages containing fissile material, as well as special form radioactive materials, special arrangements and certain shipments, are required to be approved by the competent authority. In the United Kingdom competent authority approval is carried out on behalf of the Secretary of State by the Radioactive Materials Transport Division (RMTD) of the Department of the Environment, Transport and the Regions (DETR). Competent authority approval of a package design is given only after a detailed assessment of the design by the specialist staff of RMTD. There are three facets to the assessment procedure, namely engineering, criticality and radiation protection, and quality assurance. The engineering assessor ensures that the designer has demonstrated the integrity of the containment and shielding systems under the regulatory conditions. The criticality assessor examines criticality safety and radiation protection measures, and together with the engineering assessor, decides whether this is maintained under regulatory conditions. The quality assurance assessor verifies that the applicant has established the necessary controls to ensure that the design requirements are met. The applicant is responsible for making the case for approval, but the assessment is facilitated if the competent authority is involved with the designer at an early stage in development and during the construction of any test prototype. When a regulatory test programme is required, it is designed and carried out by the applicant, but agreed and witnessed by representatives of RMTD. Following the test programme, the applicant submits a formal application, supported by a design safety report (DSR). The DSR provides a full analysis of the design and the test results, including the behaviour of the package under normal and accident conditions of transport, the manufacturing and maintenance procedures, quality assurance and the emergency provisions for the operation of the package

  14. Infrastructure of the Regulatory Authority and Performance Indexes

    International Nuclear Information System (INIS)

    Velasquez, Silvia

    2001-01-01

    This presentation overviews the following issues: elements of a control regulatory program, inspections program, procedures, indexes of users performance, priorities on: registration, criteria for practices of low risk, dose levels in medical exposures, dose constraints and training of personnel. These aspects are considered in the guides prepared within ARCAL XX framework

  15. The importance of the practical training, the retraining and the accreditation of the personnel with regulatory functions

    International Nuclear Information System (INIS)

    Menossi, Carlos A.

    2004-01-01

    Medicine, industry, hydrology, research, development and academic scenarios are, nowadays the focus for a wide application of radioisotope techniques of permanently increasing use. This situation should move the governments towards the improvement of their infrastructures and the updating of the nuclear regulatory authorities knowledge. The regulation and control of radioactive sources and its associated practices, to guarantee its safe use and minimize the derived risks from those practices, constitute the main tasks of nuclear regulatory institutions. On the other hand, it is known that personnel with regulatory functions has further interaction with people responsible of facilities and practices (users). In fact, most of these people only have contact with the regulatory authority through the inspector visits, the documents, notes or requirements received. For such a reason, nuclear regulatory authority management success or failure depends fundamentally on the successes or errors occurring in the course of these interactions. Due to it, it should be kept in mind that a successful management of a Nuclear Regulatory Authority implies: a) The users accomplish the effective standards and satisfy the authority requirements, and b) An attitude of respect is induced in the users by the appropriate regulatory function. That is to say because the 'inspectors' possess the necessary technical knowledge. In that sense, with the experience of many years, improvements have been introduced in the radiological protection Post Graduate Course program. This course sponsored by the IAEA has been given in Argentina for 24 years. Such improvements have been made to allow participants that will perform regulatory functions to have enough sessions of practical training, demonstrations, laboratory exercises, case studies and technical visits. This formation course will be supplemented by an accreditation and training on the job. The scope and dimension of the improvements are

  16. Improvements related with the safety required by the Argentine Regulatory Authority to the Atucha I Nuclear Central

    International Nuclear Information System (INIS)

    Calvo, J.; Michelin, C.; Navarro, R.; Waldman, R.

    2006-01-01

    The Argentinean Nuclear Regulation Authority (ARN) verified the existence of changes in the state of some internal components of the reactor of the Atucha I Nuclear Power station that, of continuing in the time, it could take to an inconvenient degradation for the safety operation of the installation. In consequence, to the effects of preventing that reach this situation, at the end of 1999, the ARN required to the Responsible Entity for the operation of this power station the implementation of an important improvements program in the internal components of the reactor. Additionally, and based on the results of the Probabilistic Safety analysis, it was added the one mentioned improvements program the implementation of an alternative cooling system of the reactor core denominated Second Drain of Heat, due to it was determined that, for some accidental sequences, their performance would reduce considerably the probability of damage to the core. The concretion of the improvements program implied to the Responsible Entity the realization of an important quantity of engineering studies, tests and specific inspections that allowed to carry out changes on the control bars of the reactor and its guide tubes; the coolant channels; the sensors of neutron flow; and diverse components of the primary and moderator systems. On the other hand also it was implemented the system Second Drain of Heat, what represents a considerable effort to make compatible the instrumentation and control of last generation, with the instrumentation and existent control systems in the power station. Also, it was requested to be carried out an integrity of the pressure recipient for to demonstrate the existence of an acceptable margin for the difference among the acceptable limit temperatures and of ductile/fragile transition of the material for all the possible accidental scenarios during the useful life of the reactor. (Author)

  17. Different regulatory strategies in regulation of nuclear power projects: An Indian experience

    International Nuclear Information System (INIS)

    Khan, Sohail Ahmad

    2002-01-01

    Regulatory strategy needed for management of safety and safety culture involves careful planning and use of engineering concepts keeping in mind feasibility to implement certain safety requirements. It also requires adequate attention on working environment and mental conditions of designers, operating and maintenance staff and regulators. Different strategies followed during safety review and regulatory inspection of nuclear power projects for improving status of safety management and safety cultures have given certain results. The present paper brings out certain experience gained during regulation of Indian Nuclear Power Projects by Atomic Energy Regulatory Board of India in the area of management of safety and safety culture. (author)

  18. Regulatory viewpoint on nuclear fuel quality assurance

    International Nuclear Information System (INIS)

    Tripp, L.E.

    1976-01-01

    Considerations of the importance of fuel quality and performance to nuclear safety, ''as low reasonably achievable'' release of radioactive materials in reactor effluents, and past fuel performance problems demonstrate the need for strong regulatory input, review and inspection of nuclear fuel quality assurance programs at all levels. Such a regulatory program is being applied in the United States of America by the US Nuclear Regulatory Commission. Quality assurance requirements are contained within government regulations. Guidance on acceptable methods of implementing portions of the quality assurance program is contained within Regulatory Guides and other NRC documents. Fuel supplier quality assurance program descriptions are reviewed as a part of the reactor licensing process. Inspections of reactor licensee control of their fuel vendors as well as direct inspections of fuel vendor quality assurance programs are conducted on a regularly scheduled basis. (author)

  19. Authorization of radioactive waste disposal under RSA93: regulatory experience and developments

    International Nuclear Information System (INIS)

    McHugh, J.O.

    1997-01-01

    The Environment Agency was formed in 1996 and is responsible for regulating radioactive waste disposal in England and Wales. In determining applications for disposal authorizations, it consults other statutory bodies including the Ministry of Agriculture, Fisheries and Food and the Health and Safety Executive. The Agency has published updated guidance on the principles and requirements for authorization of geological disposal of low and intermediate level waste. It will apply a risk target of 10 -6 per year in determining authorizations for waste disposal. Further work is required to elaborate the concept of 'critical group' to which the risk target should be applied. The Agency has also considered amending the methodology it uses for regulation of radioactive waste discharges from nuclear installations. Concerns expressed by the nuclear industry about the lack of operational flexibility in discharge authorizations, led the Agency to develop an alternative method of regulation. Responses to this initiative were mixed. In the future, the Department of the Environment will be reviewing the principles underpinning regulation of discharges, with the intention of setting out guidance on the objectives to be achieved and factors to be taken into account. (author)

  20. The Report on Activities of the Nuclear Regulatory Authority of the Slovak Republic and on Safety of Nuclear Installations in the Slovak Republic in 2010

    International Nuclear Information System (INIS)

    2010-05-01

    A brief account of activities carried out by the Nuclear Regulatory Authority of the Slovak Republic (UJD SR) in 2010 is presented. These activities are reported under the headings: Address of the Chairperson; (1) Legislative activities; (2) Issuance of authorizations, assessment, supervisory activities and enforcement; (3) Nuclear safety of nuclear power plants; (4) Nuclear materials and physical protection of nuclear materials; (5) Powers of the office building; (6) Emergency planning and preparedness; (7) International activities; (8) Public communication; (9) Nuclear Regulatory Authority of the Slovak Republic; (10) Appendix: UJD SR organization chart; The International Nuclear Event Scale (INES); Abbreviations.

  1. Intercomparison run for uranium and tritium determination in urine samples, organised by Nuclear Regulatory Authority, Argentina

    CERN Document Server

    Serdeiro, N H; Equillor, H E

    2003-01-01

    The Nuclear Regulatory Authority (ARN), Argentina, has carried out an intercomparison run for tritium and uranium determination in urine, in November 2002. The aim of this exercise was to assess the performance of the laboratories that usually inform these radionuclides and to provide technical support in order to have an appropriate occupational monitoring in vitro. In the present work, the results of the intercomparison and the assessment of each laboratory are published.

  2. 18 CFR 284.126 - Reporting requirements.

    Science.gov (United States)

    2010-04-01

    ... 18 Conservation of Power and Water Resources 1 2010-04-01 2010-04-01 false Reporting requirements. 284.126 Section 284.126 Conservation of Power and Water Resources FEDERAL ENERGY REGULATORY COMMISSION... AUTHORITIES Certain Transportation by Intrastate Pipelines § 284.126 Reporting requirements. (a) Notice of...

  3. Issues and regulatory requirements for the connection of wind generation

    Energy Technology Data Exchange (ETDEWEB)

    Gimenez Alvarez, J.M. [National University of San Juan (Argentina)], E-mail: jgimenez@unsj.edu.ar; Gomez Targarona, J.C. [National University of Rio Cuarto, Cordoba (Argentina). Electric Power Systems Protection Institute (IPSEP)], E-mail: jcgomez@ing.unrc.edu.ar

    2009-07-01

    Pollution problems such as greenhouse effect as well as the high value and volatility of fuel prices have forced and accelerated the development and use of renewable energy sources. In this work a complete revision of wind generation is presented. In the first part a brief history of the wind energy developments is detailed. Next, some commentaries related to the present and future state are made. Then, a revision of the modern structures of wind generation is realized. In fourth place it is included a brief comparison between small and big size turbines. Then, different types of energy storage are mentioned. Finally regulatory aspects are discussed, respect to the treatment of the technical problems. (author)

  4. Regulatory requirements on PSA level 2: Review, aspects and applications

    International Nuclear Information System (INIS)

    Husarcek, J.

    2003-01-01

    The general requirements concerning utility obligations, probabilistic safety criteria (CDF should not exceed 1.0E-4/reactor year and LERF should not exceed 1.0E-5/reactor year), documentation and results, living PSA requirements and major steps in level 2 PSA are presented. PSA developments in Slovakia, collection and assembly of information, plant damage states, containment performance and failure modes, severe accident progression analyses, containment failure modes and source terms as a part of performed level 2 PSA are discussed. The PSA applications in design and operation evaluation, support to plant upgrade and modifications are also described. At the end, the following conclusion is made: more extensive PSA application needs to foster the exchange of experience and communication between PSA specialists, non-PSA engineers, designers, and the regulatory body staff responsible for safety assessment, inspection and enforcement

  5. Review of Legislation and Regulatory Framework in Ukraine with Regard to Environmental Radiation Monitoring

    International Nuclear Information System (INIS)

    Goldammer, Wolfgang; Batandjieva, Borislava; Nasvit, Oleg; German, Olga

    2009-06-01

    The aim of this review is to compare the current legal basis and regulatory framework in Ukraine to the relevant international safety requirements and to identify shortcomings, such as deficiencies and internal contradictions. However, no assessment of its practical implementation is made beyond the aspects related to environmental radiation monitoring. The report focuses on 13 areas present in the in the Ukrainian legislation and regulatory framework: R-1 Radiation monitoring R-2 Definition of responsibilities R-3 Normal situations R-4 Emergencies R-5 Long-term monitoring R-6 Intervention in cases of lasting exposure R-7 Use of monitoring data R-8 Record keeping R-9 Reporting to the regulatory authority R-10 Public information R-11 Human and financial resources R-12 Transboundary aspects R-13 Quality assurance. For each topic a description of the current situation and an evaluation is carried out. Ranking is then supplied supported by its evaluation. In brief these categories are: A: The national legal and regulatory documents are harmonised in substance with the international safety requirements; B: Substantial differences exist between the national and international requirements which should be addressed with the view to harmonise the legislation; C: Substantial deficiencies exist in the legal and/or regulatory bases which results in no or at least partial compliance with international safety requirements. P: In addition practical issues are also provided to indicates where practical implementation of the legislation and regulatory basis is not adequate in all respects. This report then presents main observations and conclusions of the review. On this basis, the report derives general suggestions for improvement of the legal and regulatory bases. These should be considered by the Ukrainian Government and the regulatory authorities within an action plan to improve the legal basis for radiological monitoring of the environment and to facilitate its implementation

  6. Review of Legislation and Regulatory Framework in Ukraine with Regard to Environmental Radiation Monitoring

    Energy Technology Data Exchange (ETDEWEB)

    Goldammer, Wolfgang; Batandjieva, Borislava (Private Consultants (Ukraine)); Nasvit, Oleg (National Security and Defence Council of Ukraine, Kyiv (Ukraine)); German, Olga (Swedish Radiation Safety Authority, Stockholm (Sweden))

    2009-06-15

    The aim of this review is to compare the current legal basis and regulatory framework in Ukraine to the relevant international safety requirements and to identify shortcomings, such as deficiencies and internal contradictions. However, no assessment of its practical implementation is made beyond the aspects related to environmental radiation monitoring. The report focuses on 13 areas present in the in the Ukrainian legislation and regulatory framework: R-1 Radiation monitoring R-2 Definition of responsibilities R-3 Normal situations R-4 Emergencies R-5 Long-term monitoring R-6 Intervention in cases of lasting exposure R-7 Use of monitoring data R-8 Record keeping R-9 Reporting to the regulatory authority R-10 Public information R-11 Human and financial resources R-12 Transboundary aspects R-13 Quality assurance. For each topic a description of the current situation and an evaluation is carried out. Ranking is then supplied supported by its evaluation. In brief these categories are: A: The national legal and regulatory documents are harmonised in substance with the international safety requirements; B: Substantial differences exist between the national and international requirements which should be addressed with the view to harmonise the legislation; C: Substantial deficiencies exist in the legal and/or regulatory bases which results in no or at least partial compliance with international safety requirements. P: In addition practical issues are also provided to indicates where practical implementation of the legislation and regulatory basis is not adequate in all respects. This report then presents main observations and conclusions of the review. On this basis, the report derives general suggestions for improvement of the legal and regulatory bases. These should be considered by the Ukrainian Government and the regulatory authorities within an action plan to improve the legal basis for radiological monitoring of the environment and to facilitate its implementation

  7. Regulatory framework for radioactive waste disposal in Romania

    International Nuclear Information System (INIS)

    Dogaru, D.M.

    2005-01-01

    To fulfill the obligations assumed by Romania by joining to the international convention and treaty as well as for implementing the European Commission legislative framework a lot of regulations was already issued or are under the development. The National Commission for Nuclear Activities Control as regulatory authority in nuclear field in Romania considered the process of developing regulations in order to detail the requirements for safe management of radioactive waste. (authors)

  8. Report of the working group 'Regulatory requirements on AM - Concept of nuclear and radiation safety during beyond-design-basis accidents'

    International Nuclear Information System (INIS)

    Bobaly, P.

    2001-01-01

    The developed working group report contains the following main paragraphs: legal basis and basis for regulatory requirements for on-site and off-site Accident Management (AM), regulatory requirements or recommendations for on-site AM and for emergency preparedness, background information concerning the implementation and review of an AM program as a basis for an AM guideline. Overview about AM/SAM implementation in member countries of the SAMINE project; measure and candidates for high level actions based upon US SAMG; interactions of severe accident research and the regulatory positions, relationship between different components of an accident management programme are also given

  9. Projecting regulatory expectations for advanced reactor designs

    International Nuclear Information System (INIS)

    Viktorov, A.

    2011-01-01

    This paper explores the overarching safety principles that will likely guide the safety design of advanced reactor technologies. As will be shown, the already established safety framework provides a solid foundation for the safety design of future nuclear power plants. As a specific example, the principle of 'proven technology' is presented in greater detail and its implications for a novel technology are discussed. Research, modeling and prototyping are shown to be components in satisfying this principle. While the fundamental safety principles are in place, their interpretation may depend both on the considered technology as well as the national context. Thus, the regulatory authority will need to be engaged, at an appropriate stage of the technology development, in specifying the regulatory requirements that will have to be met for a specific reactor design. (author)

  10. Regulatory requirements for nuclear power plant site selection in Malaysia-a review.

    Science.gov (United States)

    Basri, N A; Hashim, S; Ramli, A T; Bradley, D A; Hamzah, K

    2016-12-01

    Malaysia has initiated a range of pre-project activities in preparation for its planned nuclear power programme. Clearly one of the first steps is the selection of sites that are deemed suitable for the construction and operation of a nuclear power plant. Here we outline the Malaysian regulatory requirements for nuclear power plant site selection, emphasizing details of the selection procedures and site characteristics needed, with a clear focus on radiation safety and radiation protection in respect of the site surroundings. The Malaysia Atomic Energy Licensing Board (AELB) site selection guidelines are in accord with those provided in International Atomic Energy Agency (IAEA) and United Stated Nuclear Regulatory Commission (USNRC) documents. To enhance the suitability criteria during selection, as well as to assist in the final decision making process, possible assessments using the site selection characteristics and information are proposed.

  11. Technical nuclear safety in France. Control by the governmental authority

    International Nuclear Information System (INIS)

    1991-12-01

    In publishing this latest edition, we have endeavoured to provide the reader with the information necessary to obtain a full understanding of the regulatory system applied to ensure technical nuclear safety in France. As the reader will discover in the following pages, technical nuclear safety is a matter which must be settled in advance of the actual operation of civil nuclear installations; the primary requirement is to mobilize those involved to anticipate and prevent. The fundamental options on which the French system is based, the relationship between the operator and the safety authority must be clearly stated: independence of judgement and decision, complementarity of responsibilities. It is for the governmental authorities to determine the technical nuclear safety objectives, which are becoming more and more consistent if not unified throughout the world. It is for the operator to propose technical provisions in order to achieve these objectives. It is for the governmental authorities to verify, by technical safety analyses, the adequacy of the provisions in terms of the defined objectives. It is for the operator to properly implement these approved provisions. And, finally, it is for the governmental authorities to verify, by sampling, the quality of their implementation and to make from them the necessary regulatory inferences. This sequence of events requires permanent frank in-depth dialogue. The effectiveness of the regulatory action must therefore reside not in close technical restraint but in the interactions between responsible partners

  12. Technical nuclear safety in France. Control by the governmental authority

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1991-12-15

    In publishing this latest edition, we have endeavoured to provide the reader with the information necessary to obtain a full understanding of the regulatory system applied to ensure technical nuclear safety in France. As the reader will discover in the following pages, technical nuclear safety is a matter which must be settled in advance of the actual operation of civil nuclear installations; the primary requirement is to mobilize those involved to anticipate and prevent. The fundamental options on which the French system is based, the relationship between the operator and the safety authority must be clearly stated: independence of judgement and decision, complementarity of responsibilities. It is for the governmental authorities to determine the technical nuclear safety objectives, which are becoming more and more consistent if not unified throughout the world. It is for the operator to propose technical provisions in order to achieve these objectives. It is for the governmental authorities to verify, by technical safety analyses, the adequacy of the provisions in terms of the defined objectives. It is for the operator to properly implement these approved provisions. And, finally, it is for the governmental authorities to verify, by sampling, the quality of their implementation and to make from them the necessary regulatory inferences. This sequence of events requires permanent frank in-depth dialogue. The effectiveness of the regulatory action must therefore reside not in close technical restraint but in the interactions between responsible partners.

  13. Regulatory approaches in the United States of America for safe management and disposal of long-lived radionuclides

    International Nuclear Information System (INIS)

    Greeves, J.T.; Bell, M.J.; Nelson, R.A.

    1998-01-01

    Regulation of the safe management and disposal of commercial, man-made, long-lived radioactive wastes in the United States is the responsibility of the US Nuclear Regulatory Commission (NRC). In some instances, state regulatory authorities have entered into agreements with the NRC to exercise regulatory authority over management and disposal of low-level radioactive wastes and uranium mill tailings within their borders. The legal and regulatory framework employed to achieve safe management and disposal of long-lived radioactive wastes in the US regulatory system is quite detailed, and in many cases the requirements are considerably prescriptive. The NRC has undertaken an initiative to move in the direction of adopting risk-informed, performance-based and risk-informed, less-prescriptive regulations. The current status and future direction of the legal and regulatory framework for management and disposal of commercial long-lived radioactive waste in the US is described. (author)

  14. Regulatory requirements on the design and construction of nuclear power plant control and instrumentation systems in Finland

    International Nuclear Information System (INIS)

    Heikkila, M.A.

    1978-01-01

    The Department of Reactor Safety of the Institute of Radiation Protection, being the nuclear regulatory authority in Finland, has set up regulations which govern the design and construction of NPP systems and components. The regulations are partly compiled from existing codes and standards, published primarily in the United States and Federal Republic of Germany, and partly worked out at the Institute. The regulations are collected to a special set of YVL guides (guides for nuclear power plants), and one of these gives requirements on the design and construction of NPPCI systems and components. The scope of the requirements is based on the safety classification of the CI systems and components. Three safety classes have been singled out: the first for CI systems which take part in reactor protection, the second for other directly safety related, and the third for remaining CI systems important enough to deserve supervision. The safety class for CI components is inherited from the system they belong to. The safety classification of IC systems has direct bearing on the initial assumptions of plant accident analysis. The design principles of IC systems are inspected as part of the preliminary and final safety reports. Focus is directed on the principles of redundancy, separation, diversity, testability, etc. The requirements on IC components are directed to different stages of manufacture, installation and operation. The type tests shall be adequate and acceptably documented. The manufacture of components is followed, the test reports reviewed and the efficiency of manufacturers quality assurance program evaluated. Further requirements concern the installation phase and tests at the end of it, and finally guides include directions for maintenance and testing during the operations phase. (author)

  15. Regulatory activities

    International Nuclear Information System (INIS)

    2001-01-01

    This publication, compiled in 8 chapters, presents the regulatory system developed by the Nuclear Regulatory Authority (NRA) of the Argentine Republic. The following activities and developed topics in this document describe: the evolution of the nuclear regulatory activity in Argentina; the Argentine regulatory system; the nuclear regulatory laws and standards; the inspection and safeguards of nuclear facilities; the emergency systems; the environmental systems; the environmental monitoring; the analysis laboratories on physical and biological dosimetry, prenatal irradiation, internal irradiation, radiation measurements, detection techniques on nuclear testing, medical program on radiation protection; the institutional relations with national and international organization; the training courses and meeting; the technical information

  16. Nuclear regulatory communication with the public: 10 years of progress

    International Nuclear Information System (INIS)

    Gauvain, J.; Jorle, A.; Chanial, L.

    2008-01-01

    The NEA has an acknowledged role to assist its member countries in maintaining and developing, through international co-operation, the scientific, technological and legal bases required for a safe, environmentally friendly and economical use of nuclear energy. In this context, the NEA Committee on Nuclear Regulatory Activities (CNRA) provides a forum for senior representatives from nuclear regulatory bodies to exchange information and experience on nuclear regulatory policies and practices in NEA member countries and to review developments which could affect regulatory requirements. Public confidence in government and in risk management structures is important to all developed countries with an open society. The use of nuclear power in a democracy is built upon a certain trust in the political system and the national authorities. To foster and maintain such trust in a period of greater public scrutiny of nuclear activities, a number of nuclear regulatory organisations (NROs) initiated various processes to pro-actively inform the public about their supervision and control of nuclear activities, or when appropriate to involve the public in decision making. In 1998 the question was raised within the CNRA of whether public trust in the regulator might be very different from one country to another, and an activity was started among member countries to exchange experience and best practices and to learn lessons about NRO communication with their publics. Three workshops were organised by the NEA, and a Working Group on Public Communication of Nuclear Regulatory Organisations was set up in 2001. The activities and findings are summarised below. (author)

  17. Experts Complete IAEA Follow-up Review of Australia's Nuclear Regulatory Authority

    International Nuclear Information System (INIS)

    2011-01-01

    Full text: Nuclear and radiation safety experts today concluded an eight-day mission to review the Australian Radiation Protection and Nuclear Safety Agency (ARPANSA), the country's nuclear regulator. At the request of the Australian Government, the International Atomic Energy Agency (IAEA) assembled a peer-review team of five regulatory experts from as many nations and three IAEA staff members to conduct a follow-up assessment of an Integrated Regulatory Review Service (IRRS) mission conducted in 2007. This follow-up IRRS mission examined ARPANSA's progress in acting upon the recommendations and suggestions made during the 2007 IRRS mission and reviewed the areas of significant regulatory changes since that review. Both reviews covered safety regulatory aspects of all facilities and activities regulated by ARPANSA. IRRS team leader Kaare Ulbak, Chief Advisor of Denmark's National Institute of Radiation Protection, said: ''ARPANSA should be commended for the significant amount of efforts in addressing all the findings identified in the 2007 mission and for inviting this follow-up review.'' The review team found that ARPANSA has made significant progress toward improving its regulatory activities, as most of the findings identified in the 2007 report have been effectively addressed and therefore can be considered closed. Complementing the ARPANSA strengths identified during the 2007 mission, the 2011 IRRS team noted the following strengths: Response to the Tepco Fukushima Dai-ichi accident; High level of in-house technical expertise in radiation safety; Recognition of the need and willingness to re-organize ARPANSA; Timely development of the national sealed source register in good coordination with other relevant organizations; and Creation of the Australian clinical dosimetry service and the national dose reference levels database. The 2011 IRRS team also made recommendations and suggestions to further strengthen ARPANSA's regulatory system, including: Making full

  18. Transport of radioactive material in Bangladesh: a regulatory perspective

    International Nuclear Information System (INIS)

    Mollah, A.S.

    2004-01-01

    Radioactive material is transported in Bangladesh in various types of packages and by different modes of transport. The transport of radioactive materials involves a risk both for the workers and members of the public. The safe transport of radioactive material is ensured in Bangladesh by compliance with Nuclear Safety and Radiation Control (NSRC) Act-93 and NSRC Rules-97. The Bangladesh Atomic Energy Commission (BAEC) is the competent authority for the enforcement of the NSRC act and rules. The competent authority has established regulatory control at each stage to ensure radiation safety to transport workers, members of general public and the environment. An overview is presented of the activities related to the transport of radioactive material in Bangladesh. In particular, the applicable legislation, the scope of authority and the regulatory functions of the competent authority are discussed. The categories of radioactive materials transported and the packaging requirements for the safe transport of these radioactive materials are also described. (author)

  19. Technical Support Organization Knowledge Management for Nuclear Regulatory Support

    International Nuclear Information System (INIS)

    Kohut, P.; Ramsey, J.; Katsenelenbogen, S.

    2016-01-01

    Full text: Knowledge management awareness has increased through the nuclear industrial and regulatory community leading to better understanding of the handling of critical information. Utilizing, managing and regulating the application of nuclear power require an extensive system of expertise and associated research through established organizations. The long term maintenance of the specific expertise is only viable by using scientific knowledge management principles all through the national nuclear infrastructure involving regulatory, industrial, academic and other research institutions. National governments in countries operating or planning to establish nuclear facilities have instituted regulatory regimes on the use of nuclear materials and facilities to insure a high level of operational safety. (author

  20. FFTF Authorization Agreement

    International Nuclear Information System (INIS)

    DAUTEL, W.A.

    2000-01-01

    The purpose of the Authorization Agreement is to serve as a mechanism whereby the U.S. Department of Energy, Richland Operations Office (RL) and Fluor Hanford (FH) jointly clarify and agree to key conditions for conducting work safely and efficiently in the Fast Flux Test Facility (FFTF). Work must be accomplished in a manner that achieves high levels of quality while protecting the environment and the safety and health of workers and the public, and complying with applicable contractual and regulatory requirements. It is the intent of this Agreement to address those items of significant importance in establishing and supporting the FFTF Authorization Envelope, but this Agreement in no way alters the terms and conditions of the Project Hanford Management Contract (PHMC), Contract Number DE-AC06-96RL13200

  1. Data Bank of Nuclear and Radiological Regulatory Authority, Part 2 . Software Package of Statistical Data of Sealed Sources

    International Nuclear Information System (INIS)

    Lashin, R.M.A.; Mahmoud, N.S.; Lashin, M.M.A.

    2012-01-01

    Protection of human, property and the environment is the main concern considered as a principal goal to form the Egyptian Nuclear and Radiological Regulatory Authority. That requires a lot of work, efforts, knowledge and aids for right and quick decision making. Internationally, the International Atomic Energy Agency (IAEA) developed a protection system for control and accounts the radioactive materials for the safe use and transport. Moreover, the protection system can prevent the theft of these materials or their use in terrorism. Here in, all radioactive sources shall be subjected to instructions, serious regulations and laws. In order to exercise these functions, it is necessary to accurately establish the appropriate information system to the regulatory body. This system must depend on using a modern technology to perform the work in most accurate and fullest manner in a Data Bank [1, 2]. The present work is the second part performed for the data bank, which consists of two parts: first part is concern about the open sources which executed before [3]. Second part is deal with the sealed sources. Describing here consolidated guidance help materials licenses. It also provides reviewers of such requests with the information and materials necessary to determine that the products are acceptable for licensing purposes. It provides the applicants and reviewers with information concerning how to file a request, a listing of the applicable regulations and industry standards, policies affecting evaluation and registration, administrative procedures to be followed, information on how to perform the evaluation and write a registration certificate, and the responsibilities of the registration certificate holder.

  2. Overview of maintenance principles and regulatory supervision of maintenance activities at nuclear power plants in Slovakia

    International Nuclear Information System (INIS)

    Rohar, S.; Cepcek, S.

    1997-01-01

    The maintenance represents one of the most important tools to ensure safe and reliable operation of nuclear power plants. The emphasis of Nuclear Regulatory Authority of the Slovak Republic to the maintenance issue is expressed by requirements in the regulations. The current practice of maintenance management in operated nuclear power plants in Slovak Republic is presented. Main aspects of maintenance, as maintenance programme, organization of maintenance, responsibilities for maintenance are described. Activities of nuclear regulatory authority in maintenance process are presented too. (author)

  3. Notification and authorization for the use of radiation sources (supplement to IAEA Safety Standards Series No. GS-G-1.5)

    International Nuclear Information System (INIS)

    2007-04-01

    The achievement and maintenance of a high level of safety in the use of radiation sources depend on there being a sound legal and governmental infrastructure, including a national regulatory body with well-defined responsibilities and functions. These responsibilities and functions include establishing and implementing a system for notification and authorization for control over radiation sources, including a system for review and assessment of applications for authorization. The Safety Requirements publication entitled Legal and Governmental Infrastructure for Nuclear, Radiation, Radioactive Waste and Transport Safety establishes the requirements for legal and governmental infrastructure. The term 'infrastructure' refers to the underlying structure of systems and organizations. This includes requirements concerning the establishment of a regulatory body for radiation sources and the responsibilities and functions assigned to it. The International Basic Safety Standards for Protection against Ionizing Radiation and for the Safety of Radiation Sources (the Basic Safety Standards or the BSS) establish basic requirements for protection against risks associated with exposure to ionizing radiation and for the safety of radiation sources. The application of the BSS is based on the presumption that national infrastructures are in place to enable governments to discharge their responsibilities to for radiation protection and safety. This TECDOC provides practical guidance on the process for dealing with applications for authorization and accepting notifications to regulatory bodies. Examples of guidelines that may be used by persons required to notify or apply for authorization and of the regulatory body's review and assessment procedures are provided in the Appendices. The TECDOC is oriented towards national regulatory infrastructures concerned with protection and safety for radiation sources used in medicine, industry, agriculture, research and education

  4. Notification and authorization for the use of radiation sources (supplement to IAEA Safety Standards Series No. GS-G-1.5)

    International Nuclear Information System (INIS)

    2010-10-01

    The achievement and maintenance of a high level of safety in the use of radiation sources depend on there being a sound legal and governmental infrastructure, including a national regulatory body with well-defined responsibilities and functions. These responsibilities and functions include establishing and implementing a system for notification and authorization for control over radiation sources, including a system for review and assessment of applications for authorization. The Safety Requirements publication entitled Legal and Governmental Infrastructure for Nuclear, Radiation, Radioactive Waste and Transport Safety establishes the requirements for legal and governmental infrastructure. The term 'infrastructure' refers to the underlying structure of systems and organizations. This includes requirements concerning the establishment of a regulatory body for radiation sources and the responsibilities and functions assigned to it. The International Basic Safety Standards for Protection against Ionizing Radiation and for the Safety of Radiation Sources (the Basic Safety Standards or the BSS) establish basic requirements for protection against risks associated with exposure to ionizing radiation and for the safety of radiation sources. The application of the BSS is based on the presumption that national infrastructures are in place to enable governments to discharge their responsibilities to for radiation protection and safety. This TECDOC provides practical guidance on the process for dealing with applications for authorization and accepting notifications to regulatory bodies. Examples of guidelines that may be used by persons required to notify or apply for authorization and of the regulatory body's review and assessment procedures are provided in the Appendices. The TECDOC is oriented towards national regulatory infrastructures concerned with protection and safety for radiation sources used in medicine, industry, agriculture, research and education

  5. Regulatory requirements for replacement of analog systems with digital upgrades

    International Nuclear Information System (INIS)

    Loeser, P.J.

    1993-01-01

    This paper reviews briefly the regulatory guidelines which must be met in order to replace analog systems in nuclear power plants with digital systems. There is a move to do such replacements for a number of reasons: analog systems are aging, and showing considerable drift; few vendors manufacture analog systems today; support and parts are hard to get; digital systems provide flexibility. There is a safety concern however about undesirable and unpredictable effects to digital safety equipment due to plant transients, accidents, post-accident condition, and EMI/RF environmental interferences. License holders must comply with the requirements of 10 C.F.R. 50.59, which deals with safety concerns with respect to any changes to operating plants which may have an impact on the safety of the plant. NRC staff is taking the position that all digital upgrades will require an evaluation under this regulation

  6. Regulatory framework for radioactive waste disposal in Romania

    International Nuclear Information System (INIS)

    Dogaru, Daniela

    2005-01-01

    Full text: To fulfill the obligations assumed by Romania by joining to the international convention and treaty as well as for implementing the European Commission legislative framework a lot of regulations was already issued or are under the development. The National Commission for Nuclear Activities Control as regulatory authority in nuclear field in Romania considered the process of developing regulations in order to detail the requirements for safe management of radioactive waste. (authors)

  7. 78 FR 4186 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing...

    Science.gov (United States)

    2013-01-18

    ... securities offered or sold pursuant to crowdfunding.\\5\\ Intermediaries in transactions involving the offer or sale of securities for the account of others pursuant to the crowdfunding exemption must, among other...- regulatory organization.\\7\\ \\4\\ Public Law 112-106, 126 Stat. 306 (2012). \\5\\ In general, crowdfunding refers...

  8. Establishing a regulatory value chain model: An innovative approach to strengthening medicines regulatory systems in resource-constrained settings.

    Science.gov (United States)

    Chahal, Harinder Singh; Kashfipour, Farrah; Susko, Matt; Feachem, Neelam Sekhri; Boyle, Colin

    2016-05-01

    Medicines Regulatory Authorities (MRAs) are an essential part of national health systems and are charged with protecting and promoting public health through regulation of medicines. However, MRAs in resource-constrained settings often struggle to provide effective oversight of market entry and use of health commodities. This paper proposes a regulatory value chain model (RVCM) that policymakers and regulators can use as a conceptual framework to guide investments aimed at strengthening regulatory systems. The RVCM incorporates nine core functions of MRAs into five modules: (i) clear guidelines and requirements; (ii) control of clinical trials; (iii) market authorization of medical products; (iv) pre-market quality control; and (v) post-market activities. Application of the RVCM allows national stakeholders to identify and prioritize investments according to where they can add the most value to the regulatory process. Depending on the economy, capacity, and needs of a country, some functions can be elevated to a regional or supranational level, while others can be maintained at the national level. In contrast to a "one size fits all" approach to regulation in which each country manages the full regulatory process at the national level, the RVCM encourages leveraging the expertise and capabilities of other MRAs where shared processes strengthen regulation. This value chain approach provides a framework for policymakers to maximize investment impact while striving to reach the goal of safe, affordable, and rapidly accessible medicines for all.

  9. 75 FR 15470 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing...

    Science.gov (United States)

    2010-03-29

    ...-Regulatory Organization's Statement of the Terms of Substance of the Proposed Rule Change FINRA is proposing... (Disclosure of Price and Concessions in Selling Agreements) and the deletion of NASD Rule 2770 (Disclosure of Price in Selling Agreements). FINRA Rule 5160 was approved by the Commission on January 25, 2010 \\5\\ and...

  10. Regulatory and Non-regulatory Responses to Hydraulic Fracturing in Local Communities

    Science.gov (United States)

    Phartiyal, P.

    2015-12-01

    The practice of extracting oil and gas from tight rock formations using advances in technology, such as hydraulic fracturing and directional drilling, has expanded exponentially in states and localities across the country. As the scientific data collection and analysis catches up on the many potential impacts of this unconventional oil and gas development, communities are turning to their local officials to make decisions on whether and how fracking should proceed. While most regulatory authority on the issue rests with the state agencies, local officials have experimented with a wide range of regulatory, non-regulatory, and fiscal tools to manage the impacts of fracking. These impacts can occur on the local air, water, seismicity, soil, roads, schools, and affect residents, on-site workers, emergency and social services. Local officials' approaches are often influenced by their prior experience with minerals extraction in their localities. The speaker will present examples of the kinds of information sources, tools and approaches communities across the country are using, from noise barriers to setback requirements to information sharing in order to be able to balance the promise and perils of oil and gas development in their jurisdictions.

  11. Regulatory challenges associated with conducting multicountry clinical trials in resource-limited settings.

    Science.gov (United States)

    Ndebele, Paul; Blanchard-Horan, Christina; Shahkolahi, Akbar; Sanne, Ian

    2014-01-01

    International public health and infectious diseases research has expanded to become a global enterprise transcending national and continental borders in organized networks addressing high-impact diseases. In conducting multicountry clinical trials, sponsors and investigators have to ensure that they meet regulatory requirements in all countries in which the clinical trials will be conducted. Some of these requirements include review and approval by national drug regulatory authorities and recognized research ethics committees. A limiting factor to the efficient conduct of multicountry clinical trials is the regulatory environment in each collaborating country, with significant differences determined by various factors including the laws and the procedures used in each country. The long regulatory processes in resource-limited countries may hinder the efficient implementation of multisite clinical trials, delaying research important to the health of populations in these countries and costing millions of dollars a year.

  12. Regulatory activities related with the modification of the frequency of the programmed stoppings of the Argentine nuclear centrals

    International Nuclear Information System (INIS)

    Marino, E.; Calvo, J.; Waldman, R.; Navarro, R.

    2006-01-01

    The mandatory character documentation of the Argentinean nuclear power stations in Embalse and Atucha I, required the realization of a programmed stoppings every twelve months to execute that settled down in the maintenance and surveillance programs for each installation. Nucleoelectrica Argentina S.A., in it character of Responsible Entity of the operation of these power stations, requested to the Argentinean Nuclear Regulatory Authority, in 2003 and 2005 respectively, the authorization to change the period of the repetitive tests and of the preventive maintenance of the systems related with the safety, to extend them from twelve to eighteen months. The mentioned applications were founded in economic aspects and in inclining to a decrease in the doses of the workers that perform in the activities that are carried out in the programmed stops. The adopted position by the Nuclear Regulatory Authority to decide on these applications was based on the result of diverse evaluations that included the use of the Probabilistic Analysis of Safety specific of each power station, the operative experience resultant of the execution of the preventive maintenance program, and of the results of the repetitive tests and of the inspections in service. The regulatory decisions were different in each case. Indeed, the Embalse nuclear power station was authorized by the Regulatory Authority to modify from twelve to eighteen months the period among the realization of the repetitive tests and of the preventive maintenance, conditioned to the execution of some specific regulatory requirements. On the other hand, the Atucha I nuclear power station was not authorized to modify this period. In this presentation that is detailed the acted by the Nuclear Regulatory Authority in both cases, the used analysis tools, and the foundation of the adopted decisions. (Author)

  13. Defining regulatory requirements for water supply systems in Vietnam

    Directory of Open Access Journals (Sweden)

    Deryushev Leonid Georgiyevich

    2014-01-01

    Full Text Available In the article the authors offer their suggestions for improving the reliability of the standardization requirements for water supply facilities in Vietnam, as an analog of building regulations of Russia 31.13330.2012. In Russia and other advanced countries the reliability of the designed water supply systems is usual to assess quantitatively. Guidelines on the reliability assessment of water supply systems and facilities have been offered by many researchers, but these proposals are not officially approved. Some methods for assessing the reliability of water supply facilities are informally used in practice when describing their quality. These evaluation methods are simple and useful. However, the given estimations defy common sense and regulatory requirements used by all the organizations, ministries and departments, for example, of Russia, in the process of allowances for restoration and repair of water supply facilities. Inadequacy of the water supply facilities assessment is shown on the example of assessing the reliability of pipeline system. If we take MTBF of specific length of the pipeline as reliability index for a pipeline system, for example, 5 km, a pipeline of the similar gauge, material and working conditions with the length of 5 m, according to the estimation on the basis of non-official approach, must have a value of MTBF 1000 times greater than with the length of 5 km. This conclusion runs counter to common sense, for the reason that all the pipes in the area of 5 km are identical, have the same load and rate of wear (corrosion, fouling, deformation, etc.. It was theoretically and practically proved that products of the same type in the same operating conditions (excluding determined impact of a person, work as an entity, which MTBF is equal to the average lifetime. It is proposed to take the average service life as a reliability indicator of a pipeline. Durability, but not failsafety of the pipe guarantees pipeline functioning

  14. Quality Management System at the Nuclear Regulatory Authority of the Slovak Republic

    International Nuclear Information System (INIS)

    Husarcek, J.; Novak, S.

    2008-01-01

    The process-oriented quality management system (QMS) implemented at the Nuclear Regulatory Authority of the Slovak Republic (UJD SR) in compliance with the EN ISO 9001:2001 standard is described. The history of the establishment and development of the QMS is given. The main, managerial and supporting processes with respect to defined activities are specified, and a scheme of their interactions is presented. The contents of the Quality Manual content and the structure of the system documentation are briefly described. The responsibilities for the operation and improvements of the QMS are described along with the methods applied (internal and external audits, self-assessment - Common Assessment Framework (CAF)). Examples of established quality objectives and indicators for some processes are provided. A future development of the QMS is expected in accordance with the relevant ISO Standard and IAEA recommendations and based on evaluation of the effectiveness of the critical system. (orig.)

  15. Regulatory experience with ALARP investigation reports at some UK nuclear sites

    International Nuclear Information System (INIS)

    Robinson, I.F.; Turton, D.

    1991-01-01

    This paper describes the UK regulatory requirements placed on employers regarding the investigation of whether doses incurred are as low as reasonably practicable. It discusses the operational experience gained by an inspection Branch of the HM Nuclear Installations Inspectorate (NII) of the Health and Safety Executive which is the UK regulatory body responsible for the enforcement of these requirements. The general approach taken by employers to preparing investigation reports is discussed, and the form and content of the reports is considered. An aspect of the employers approach to dose restriction is discussed, and the NII's response to investigation reports is described. (Author)

  16. 24 CFR 241.615 - Certification of cost requirements.

    Science.gov (United States)

    2010-04-01

    ..., including any collateral agreements. (g) Certificate of public accountant. Where required by the... independent Certified Public Accountant or independent public accountant licensed by a regulatory authority of...

  17. Nuclear Regulatory Commission authorizations for Fiscal Years 1984 and 1985. House of Representatives, Ninety-Eighth Congress, First Session

    International Nuclear Information System (INIS)

    Anon.

    1983-01-01

    H.R. 2510, as amended, authorizes $466.8 million to cover Nuclear Regulatory Commission salaries and expenses for fiscal year 1984 and $460 million for the following year in a two-year authorization. The bill substitutes certain expenditures for those recommended in the NRC request, while keeping the funding level the same. The committee report reviews and summarizes the two-year budget appropriation and the hearings before giving a section-by-section analysis. It notes that 46% is earmarked for waste management, and emphasizes the safety factors which have caused delays in construction and modifications in existing plants. 13 tables

  18. 19 CFR 113.1 - Authority to require security or execution of bond.

    Science.gov (United States)

    2010-04-01

    ... 19 Customs Duties 1 2010-04-01 2010-04-01 false Authority to require security or execution of bond. 113.1 Section 113.1 Customs Duties U.S. CUSTOMS AND BORDER PROTECTION, DEPARTMENT OF HOMELAND SECURITY; DEPARTMENT OF THE TREASURY CUSTOMS BONDS General Provisions § 113.1 Authority to require security or...

  19. Regulatory aspects of nuclear reactor decommissioning

    International Nuclear Information System (INIS)

    Ross, W.M.

    1990-01-01

    The paper discusses the regulatory aspects of decommissioning commercial nuclear power stations in the UK. The way in which the relevant legislation has been used for the first time in dealing with the early stages of decommissioning commercial nuclear reactor is described. International requirements and how they infit with the UK system are also covered. The discussion focusses on the changes which have been required, under the Nuclear Site Licence, to ensure that the licensee carries out of work of reactor decommissioning in a safe and controlled manner. (Author)

  20. Strengthening Regulatory Competence through Techno-managerial Knowledge Integration: Indian Experience

    International Nuclear Information System (INIS)

    Kuchibhotla, S.

    2016-01-01

    Competence development is the process of identifying the competencies required to perform a given job, role or set of tasks successfully at workplace. Strengthening regulatory competence, for the nuclear regulator, is essential to ensure skilled and competent human resources for performing the functions of the Regulatory Body. The strengthening of existing competence level for the Indian nuclear regulator, takes into account the understanding of the elements such as legal basis and regulatory processes governing operations of regulatory body, technological competences for performing regulatory functions, competences pertinent to regulatory practices, and competences related to personal and interpersonal effectiveness within the organization. Competency data from AERB divisions was compiled to identify gaps at various positions with recommendations for making specialized training modules and modifications to basic and refresher training modules. The exercise is aimed at providing continual improvement in skills and knowledge of human resources at AERB in a phased manner. (author)

  1. Characterizing costs and benefits of uncertain future regulatory requirements on the U.S. natural gas industry

    International Nuclear Information System (INIS)

    Godec, M.L.; Smith, G.E.; Fitzgibbon, T.

    1995-01-01

    Environmental regulatory requirements at both the state and federal level are constantly changing, making it difficult for industry and R ampersand D program managers to project future compliance requirements and costs. Even if a company is trying to keep abreast of various proposed regulatory initiatives, the number of possible combinations of initiatives that could occur in the future seems virtually limitless. Uncertainty associated with potential future environmental compliance requirements makes the identification and evaluation of future investment and R ampersand D opportunities exceedingly difficult, and makes the process of systematic strategic planning increasingly complex. This paper describes a methodology for accounting for uncertain future environmental compliance costs in a systematic, comprehensive manner. Through analysis of proposed initiatives for making future environmental requirements more stringent, forecasting the likelihood of occurrence and potential timing of each initiative, and estimating potential future compliance costs associated with each initiative, a thorough process for incorporating regulatory uncertainty into strategic planning and project evaluation is described. This approach can be used for evaluating R ampersand D opportunities to determine where development of new technologies or assessment of risks posed by industry operations may have the greatest impact on future industry costs of compliance. This approach could also be used to account for the uncertainty of future environmental costs in corporate strategic planning or for factoring future compliance costs into project evaluation. This approach could also be enhanced through use in conjunction with other modeling and forecasting systems that could consider a broad range of impacts, including impacts on gas production, industry activity levels, and tax revenues

  2. Role of the regulatory authority in preparation of the NPP self assessment of safety culture

    Energy Technology Data Exchange (ETDEWEB)

    Gantchev, T [Committee on the Use of Atomic Energy for Peaceful Purposes, Sofia (Bulgaria)

    1997-12-31

    We believe that with the assistance of the IAEA(ASSET Training Mission) the plant personnel will be able to prepare high quality Self Assessment Report. The main role of the Regulatory Body is to ensure correspondence with the IAEA requirements and to provide clear guidance for the most important items of the Plant Self Assessment Report. The involvement of the Operating Organization is also desirable in order to ensure the necessary resources for the implementation of the action plan. Figs.

  3. Role of the regulatory authority in preparation of the NPP self assessment of safety culture

    International Nuclear Information System (INIS)

    Gantchev, T.

    1996-01-01

    We believe that with the assistance of the IAEA(ASSET Training Mission) the plant personnel will be able to prepare high quality Self Assessment Report. The main role of the Regulatory Body is to ensure correspondence with the IAEA requirements and to provide clear guidance for the most important items of the Plant Self Assessment Report. The involvement of the Operating Organization is also desirable in order to ensure the necessary resources for the implementation of the action plan. Figs

  4. Methodological proposal for the construction of the labor profiles of inspectors of the Nuclear Regulatory Authority

    International Nuclear Information System (INIS)

    Larcher, A.M.; Maceiras, E.; Degiovanni, G.; Perrin, C.; Sajaroff, P.

    2006-01-01

    The Argentine Nuclear Regulatory Authority (ARN) like essential part of their strategic institutional plan and in the mark of the modernization of the National Public Administration (NPA), identify the necessity to modify their functional organization, introducing the administration for processes and defining more flexible and better guided structures to the work in team. Starting from the definition of a new institutional flowchart it decided to proceed to a general reorganization of the human resources and on January, 2005 it was prepared the creation of a process whose serious objective to sit down the bases for the development of the professional career of the ARN. To such an end, it was thought about a work outline by stages, the first one of which had as final objective the elaboration of the Labor Profiles of the Institution. The work group for this first stage was integrated by a group of professionals of long trajectory in the institution and not belonging to the sector of Human Resources (RRHH). By this way it was organized as an independent group that it worked in narrow collaboration with the specific sector and informed directly to the maximum institutional direction. For the construction of the profiles a 'mixed' model was chosen that included the requirements of each position (that to make) and the competitions to complete them (how to make it), since a focus purely of competitions has not been seen as the more appropriate for the public administration and in particular for the ARN. In this work it is given to know a part of the results obtained during six months of effective work of the PerLa Group (denominated as well as an acronym of the expression Labor Profiles) putting emphasis in the defined profiles for the inspectors of those different regulatory branches that constitute the environment of competition of the RNA, this is Radiological Protection, Nuclear Safety, Safeguards and Physical Protection. The idea that underlies to the presentation

  5. Regulatory controls for NORM contamination: Emerging issues and strategies

    International Nuclear Information System (INIS)

    Wennerberg, Linda

    1992-01-01

    Naturally occurring and accelerator-produced radioactive material (NORM) faces the increasing likelihood of federal or state regulatory control. Public concern and limited preliminary survey data fuel the debate over the necessity, approach, and jurisdiction of a NORM regulatory strategy. This debate requires the resolution of technical controversies and potentially competing state and federal agency interests. An additional facet of the debate is the impact of regulation upon traditionally non-nuclear industries, such as oil and gas production. Regulatory response has been initiated in several states, such as Louisiana's controls on equipment used in oil and gas production, to control specific industrial activities which generate NORM. A more comprehensive, generic federal strategy to control NORM contamination is also under review by the Environmental Protection Agency. This paper will detail the emerging technical issues, federal and state regulatory strategies under consideration, and evaluate the efficacy of selected regulatory approaches. (author)

  6. National competent authorities responsible for approvals and authorizations in respect of the transport of radioactive material. List no. 20

    International Nuclear Information System (INIS)

    1989-03-01

    Any national or international authority designated or otherwise recognised as such for any purpose in connection with the transport Regulations is known as a competent authority. In the Member States such a body has the responsibility for establishing national legislation to bring the Agency's transport Regulations into effect and for assuring compliance with its requirements. Depending on the national regulatory or institutional framework the functions of the competent authority may be assigned to one or more bodies. To assist Member States in implementing the transport Regulations and carrying out responsibility for compliance assurance, the IAEA continues to maintain this updated list of designated national competent authorities. Member States are annually requested to verify the list for correctness and completeness

  7. National competent authorities responsible for approvals and authorizations in respect of the transport of radioactive material. List no. 24

    International Nuclear Information System (INIS)

    1993-01-01

    Any national or international authority designated or otherwise recognised as such for any purpose in connection with the transport Regulations is known as a competent authority. In the Member States such a body has the responsibility for establishing national legislation to bring the Agency's transport Regulations into effect and for assuring compliance with its requirements. Depending on the national regulatory or institutional framework the functions of the competent authority may be assigned to one or more bodies. To assist Member States in implementing the transport Regulations and carrying out responsibility for compliance assurance, the IAEA continues to maintain this updated list of designated national competent authorities. Member States are annually requested to verify the list for correctness and completeness

  8. National competent authorities responsible for approvals and authorizations in respect of the transport of radioactive material. List no. 20

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1989-03-01

    Any national or international authority designated or otherwise recognised as such for any purpose in connection with the transport Regulations is known as a competent authority. In the Member States such a body has the responsibility for establishing national legislation to bring the Agency's transport Regulations into effect and for assuring compliance with its requirements. Depending on the national regulatory or institutional framework the functions of the competent authority may be assigned to one or more bodies. To assist Member States in implementing the transport Regulations and carrying out responsibility for compliance assurance, the IAEA continues to maintain this updated list of designated national competent authorities. Member States are annually requested to verify the list for correctness and completeness.

  9. National competent authorities responsible for approvals and authorizations in respect of the transport of radioactive material. List no. 25

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1994-01-01

    Any national or international authority designated or otherwise recognised as such for any purpose in connection with the transport Regulations is known as a competent authority. In the Member States such a body has the responsibility for establishing national legislation to bring the Agency's transport Regulations into effect and for assuring compliance with its requirements. Depending on the national regulatory or institutional framework the functions of the competent authority may be assigned to one or more bodies. To assist Member States in implementing the transport Regulations and carrying out responsibility for compliance assurance, the IAEA continues to maintain this updated list of designated national competent authorities. Member States are annually requested to verify the list for correctness and completeness.

  10. National competent authorities responsible for approvals and authorizations in respect of the transport of radioactive material. List no. 19

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1988-01-01

    Any national or international authority designated or otherwise recognised as such for any purpose in connection with the transport Regulations is known as a competent authority. In the Member States such a body has the responsibility for establishing national legislation to bring the Agency's transport Regulations into effect and for assuring compliance with its requirements. Depending on the national regulatory or institutional framework the functions of the competent authority may be assigned to one or more bodies. To assist Member States in implementing the transport Regulations and carrying out responsibility for compliance assurance, the IAEA continues to maintain this updated list of designated national competent authorities. Member States are annually requested to verify the list for correctness and completeness.

  11. National competent authorities responsible for approvals and authorizations in respect of the transport of radioactive material. List no. 18

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1986-12-01

    Any national or international authority designated or otherwise recognised as such for any purpose in connection with the transport Regulations is known as a competent authority. In the Member States such a body has the responsibility for establishing national legislation to bring the Agency's transport Regulations into effect and for assuring compliance with its requirements. Depending on the national regulatory or institutional framework the functions of the competent authority may be assigned to one or more bodies. To assist Member States in implementing the transport Regulations and carrying out responsibility for compliance assurance, the IAEA continues to maintain this updated list of designated national competent authorities. Member States are annually requested to verify the list for correctness and completeness.

  12. National competent authorities responsible for approvals and authorizations in respect of the transport of radioactive material. List no. 19

    International Nuclear Information System (INIS)

    1988-01-01

    Any national or international authority designated or otherwise recognised as such for any purpose in connection with the transport Regulations is known as a competent authority. In the Member States such a body has the responsibility for establishing national legislation to bring the Agency's transport Regulations into effect and for assuring compliance with its requirements. Depending on the national regulatory or institutional framework the functions of the competent authority may be assigned to one or more bodies. To assist Member States in implementing the transport Regulations and carrying out responsibility for compliance assurance, the IAEA continues to maintain this updated list of designated national competent authorities. Member States are annually requested to verify the list for correctness and completeness

  13. National competent authorities responsible for approvals and authorizations in respect of the transport of radioactive material. List no. 25

    International Nuclear Information System (INIS)

    1994-01-01

    Any national or international authority designated or otherwise recognised as such for any purpose in connection with the transport Regulations is known as a competent authority. In the Member States such a body has the responsibility for establishing national legislation to bring the Agency's transport Regulations into effect and for assuring compliance with its requirements. Depending on the national regulatory or institutional framework the functions of the competent authority may be assigned to one or more bodies. To assist Member States in implementing the transport Regulations and carrying out responsibility for compliance assurance, the IAEA continues to maintain this updated list of designated national competent authorities. Member States are annually requested to verify the list for correctness and completeness

  14. National competent authorities responsible for approvals and authorizations in respect of the transport of radioactive material. List no. 18

    International Nuclear Information System (INIS)

    1986-12-01

    Any national or international authority designated or otherwise recognised as such for any purpose in connection with the transport Regulations is known as a competent authority. In the Member States such a body has the responsibility for establishing national legislation to bring the Agency's transport Regulations into effect and for assuring compliance with its requirements. Depending on the national regulatory or institutional framework the functions of the competent authority may be assigned to one or more bodies. To assist Member States in implementing the transport Regulations and carrying out responsibility for compliance assurance, the IAEA continues to maintain this updated list of designated national competent authorities. Member States are annually requested to verify the list for correctness and completeness

  15. National competent authorities responsible for approvals and authorizations in respect of the transport of radioactive material. List no. 21

    International Nuclear Information System (INIS)

    1990-02-01

    Any national or international authority designated or otherwise recognised as such for any purpose in connection with the transport Regulations is known as a competent authority. In the Member States such a body has the responsibility for establishing national legislation to bring the Agency's transport Regulations into effect and for assuring compliance with its requirements. Depending on the national regulatory or institutional framework the functions of the competent authority may be assigned to one or more bodies. To assist Member States in implementing the transport Regulations and carrying out responsibility for compliance assurance, the IAEA continues to maintain this updated list of designated national competent authorities. Member States are annually requested to verify the list for correctness and completeness

  16. National competent authorities responsible for approvals and authorizations in respect of the transport of radioactive material. List no. 23

    International Nuclear Information System (INIS)

    1992-01-01

    Any national or international authority designated or otherwise recognised as such for any purpose in connection with the transport Regulations is known as a competent authority. In the Member States such a body has the responsibility for establishing national legislation to bring the Agency's transport Regulations into effect and for assuring compliance with its requirements. Depending on the national regulatory or institutional framework the functions of the competent authority may be assigned to one or more bodies. To assist Member States in implementing the transport Regulations and carrying out responsibility for compliance assurance, the IAEA continues to maintain this updated list of designated national competent authorities. Member States are annually requested to verify the list for correctness and completeness

  17. National competent authorities responsible for approvals and authorizations in respect of the transport of radioactive material. List no. 22

    International Nuclear Information System (INIS)

    1991-01-01

    Any national or international authority designated or otherwise recognised as such for any purpose in connection with the transport Regulations is known as a competent authority. In the Member States such a body has the responsibility for establishing national legislation to bring the Agency's transport Regulations into effect and for assuring compliance with its requirements. Depending on the national regulatory or institutional framework the functions of the competent authority may be assigned to one or more bodies. To assist Member States in implementing the transport Regulations and carrying out responsibility for compliance assurance, the IAEA continues to maintain this updated list of designated national competent authorities. Member States are annually requested to verify the list for correctness and completeness

  18. National competent authorities responsible for approvals and authorizations in respect of the transport of radioactive material. List no. 23

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1992-01-01

    Any national or international authority designated or otherwise recognised as such for any purpose in connection with the transport Regulations is known as a competent authority. In the Member States such a body has the responsibility for establishing national legislation to bring the Agency's transport Regulations into effect and for assuring compliance with its requirements. Depending on the national regulatory or institutional framework the functions of the competent authority may be assigned to one or more bodies. To assist Member States in implementing the transport Regulations and carrying out responsibility for compliance assurance, the IAEA continues to maintain this updated list of designated national competent authorities. Member States are annually requested to verify the list for correctness and completeness.

  19. National competent authorities responsible for approvals and authorizations in respect of the transport of radioactive material. List no. 24

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1993-01-01

    Any national or international authority designated or otherwise recognised as such for any purpose in connection with the transport Regulations is known as a competent authority. In the Member States such a body has the responsibility for establishing national legislation to bring the Agency's transport Regulations into effect and for assuring compliance with its requirements. Depending on the national regulatory or institutional framework the functions of the competent authority may be assigned to one or more bodies. To assist Member States in implementing the transport Regulations and carrying out responsibility for compliance assurance, the IAEA continues to maintain this updated list of designated national competent authorities. Member States are annually requested to verify the list for correctness and completeness.

  20. National competent authorities responsible for approvals and authorizations in respect of the transport of radioactive material. List no. 22

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1991-01-01

    Any national or international authority designated or otherwise recognised as such for any purpose in connection with the transport Regulations is known as a competent authority. In the Member States such a body has the responsibility for establishing national legislation to bring the Agency's transport Regulations into effect and for assuring compliance with its requirements. Depending on the national regulatory or institutional framework the functions of the competent authority may be assigned to one or more bodies. To assist Member States in implementing the transport Regulations and carrying out responsibility for compliance assurance, the IAEA continues to maintain this updated list of designated national competent authorities. Member States are annually requested to verify the list for correctness and completeness.

  1. National competent authorities responsible for approvals and authorizations in respect of the transport of radioactive material. List no. 21

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1990-02-01

    Any national or international authority designated or otherwise recognised as such for any purpose in connection with the transport Regulations is known as a competent authority. In the Member States such a body has the responsibility for establishing national legislation to bring the Agency's transport Regulations into effect and for assuring compliance with its requirements. Depending on the national regulatory or institutional framework the functions of the competent authority may be assigned to one or more bodies. To assist Member States in implementing the transport Regulations and carrying out responsibility for compliance assurance, the IAEA continues to maintain this updated list of designated national competent authorities. Member States are annually requested to verify the list for correctness and completeness.

  2. Support in the development of Regulatory Procedures for licensing Lepse Waste Management Operations

    International Nuclear Information System (INIS)

    2001-05-01

    This report describes a project intended to assist Gosatomnadzor of Russia develop a set of documents defining the regulatory requirements for information to be submitted to Gosatomnadzor in support of any application for a licence relating to the removal of spent nuclear fuel from the depot ship Lepse. The project resulted in the development of three regulatory documents covering the documentation required in support of a licence application, the requirements for quality assurance arrangements and the safety analysis report. The working method adopted involved staged development of draft material and review at workshops involving a wide variety of relevant Russian and western organizations. The input and output of the workshops was fully documented to provide an audit trail for the document development and the rationale for what has been included and what is excluded and why. The availability of the regulatory documents in English should significantly assist in the use of the documents by western partners in the actual industrial project. Important experience and information was exchanged among participants in the project. The developing understanding is an important element in providing confidence, from a western perspective, that appropriate regulatory supervision can be applied to industrial projects supported by organizations such as the European Commission and national agencies. The same working methods could be used in the next phase of Lepse regulatory support, i.e., support in development of the procedures for the regulatory review of licence applications, and, subsequently, support in the application of the regulatory inspection process to ensure licence conditions are being complied with. Similarly, these working methods could be used in providing regulatory support for nuclear and radiation safety related to other industrial projects involving radioactive waste management. The participants in this sub-project described in this report were Norwegian

  3. The major cellular sterol regulatory pathway is required for Andes virus infection.

    Directory of Open Access Journals (Sweden)

    Josiah Petersen

    2014-02-01

    Full Text Available The Bunyaviridae comprise a large family of RNA viruses with worldwide distribution and includes the pathogenic New World hantavirus, Andes virus (ANDV. Host factors needed for hantavirus entry remain largely enigmatic and therapeutics are unavailable. To identify cellular requirements for ANDV infection, we performed two parallel genetic screens. Analysis of a large library of insertionally mutagenized human haploid cells and a siRNA genomic screen converged on components (SREBP-2, SCAP, S1P and S2P of the sterol regulatory pathway as critically important for infection by ANDV. The significance of this pathway was confirmed using functionally deficient cells, TALEN-mediated gene disruption, RNA interference and pharmacologic inhibition. Disruption of sterol regulatory complex function impaired ANDV internalization without affecting virus binding. Pharmacologic manipulation of cholesterol levels demonstrated that ANDV entry is sensitive to changes in cellular cholesterol and raises the possibility that clinically approved regulators of sterol synthesis may prove useful for combating ANDV infection.

  4. Building Nuclear Safety and Security Culture Within Regulatory Body

    International Nuclear Information System (INIS)

    Huda, K.

    2016-01-01

    To achieve a higher level of nuclear safety and security, it needs to develop the safety and security culture not only in the facility but also in the regulatory body. The regulatory body, especially needs to develop the safety and security culture within the organization, because it has a function to promote and oversee the culture in the facilities. In this sense, the regulatory body should become a role model. Development of the nuclear safety and security culture should be started by properly understanding its concept and awakening the awareness of individual and organization on the importance of nuclear safety and security. For effectiveness of the culture development in the regulatory body, the following steps are suggested to be taken: setting up of the regulatory requirements, self-assessment, independent assessment review, communication with the licensee, oversight of management system implementation, and integration with regulatory activities. The paper discusses those steps in the framework of development of nuclear safety and security culture in the regulatory body, as well as some important elements in building of the culture in the nuclear facilities. (author)

  5. The nuclear regulatory authority of the Slovak Republic and start-up of the Mochovce NPP

    International Nuclear Information System (INIS)

    Seliga, Mojmir

    1999-01-01

    The important aspect is testing if the nuclear energy in the Slovak Republic is due to obligatory rules acceptable and its operation is regulated by the state through the independent institution - The Nuclear Regulatory Authority of the Slovak Republic (UJD). UJD considers the whole area of public relations an essential component of its activity. UJD intends to serve the public true, systematic, qualified, understandable and independent information regarding nuclear safety of nuclear power plants, as well as regarding methods and results of UJD work. Generally, public information is considered as significant contribution to the creation of confidence into the regulatory work. The public relations are understood as attempts to establish, keep and improve UJD-s good relations to its neighbours through purposeful informing. An Information centre at the offices of UJD was built and opened in October 1995 with IAEA Director General as the first visitor. NPP Mochovee is an example of international co-operation in achieving internationally acceptable safety standards. Companies from France, Germany, USA, Russian Federation, Czech Republic and Slovakia and last, but not least also the IAEA participated significantly on increasing the safety level of this NPP. We have been fully aware of the importance of good communication with press, TV and radio broadcasting in this pre-operation and operation period about nuclear safety, nuclear standard and other nuclear aspects commissioning of the NPP Mochovce in the UJD. The information policy of the UJD was in this period focused on the preparation an actual press releases for general and specialised news- paper and national press agencies. Very important were the frequent presentations the requirement safety stages of the NPP Mochovce inIV and radio broadcasting by headquarters of the UJD. UJD as the state authority provides information related to its competence, namely information on safety of operation of nuclear installations

  6. 75 FR 75529 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing...

    Science.gov (United States)

    2010-12-03

    ... advance notice of the new Verification of Assets rule. \\8\\ 15 U.S.C. 78o-3(b)(6). B. Self-Regulatory... SECURITIES AND EXCHANGE COMMISSION [Release No. 34-63383; File No. SR-FINRA-2010-062] Self... in SR-FINRA-2010-042 (Verification of Assets) November 29, 2010. Pursuant to Section 19(b)(1) of the...

  7. 76 FR 14943 - Antidisruptive Practices Authority

    Science.gov (United States)

    2011-03-18

    .... Higgins, Counsel to the Director of Enforcement, 202-418- 5864, [email protected] , Commodity Futures... Prohibit Disruptive Trading a. Panelists: Tom Gira--Financial Industry Regulatory Authority; Chris Heymeyer.... Panelists: Tom Gira--Financial Industry Regulatory Authority; Chris Heymeyer--National Futures Association...

  8. Notification and authorization for the use of radiation sources (Supplement to IAEA Safety Standards Series No. GS-G-1.5)

    International Nuclear Information System (INIS)

    2011-10-01

    The achievement and maintenance of a high level of safety in the use of radiation sources depend on there being a sound legal and governmental infrastructure, including a national regulatory body with well-defined responsibilities and functions. These responsibilities and functions include establishing and implementing a system for notification and authorization for control over radiation sources, including a system for review and assessment of applications for authorization. The Safety Requirements publication entitled Legal and Governmental Infrastructure for Nuclear, Radiation, Radioactive Waste and Transport Safety establishes the requirements for legal and governmental infrastructure. The term 'infrastructure' refers to the underlying structure of systems and organizations. This includes requirements concerning the establishment of a regulatory body for radiation sources and the responsibilities and functions assigned to it. The International Basic Safety Standards for Protection against Ionizing Radiation and for the Safety of Radiation Sources (the Basic Safety Standards or the BSS) establish basic requirements for protection against risks associated with exposure to ionizing radiation and for the safety of radiation sources. The application of the BSS is based on the presumption that national infrastructures are in place to enable governments to discharge their responsibilities to for radiation protection and safety. This TECDOC provides practical guidance on the process for dealing with applications for authorization and accepting notifications to regulatory bodies. Examples of guidelines that may be used by persons required to notify or apply for authorization and of the regulatory body's review and assessment procedures are provided in the Appendices. The TECDOC is oriented towards national regulatory infrastructures concerned with protection and safety for radiation sources used in medicine, industry, agriculture, research and education. The IAEA

  9. 78 FR 14308 - International Cooperation on Harmonisation of Technical Requirements for Registration of...

    Science.gov (United States)

    2013-03-05

    ...] International Cooperation on Harmonisation of Technical Requirements for Registration of Veterinary Medicinal... been developed for veterinary use by the International Cooperation on Harmonisation of Technical... regulatory authorities and industry associations to promote the international harmonization of regulatory...

  10. A simplified ALARA approach to demonstration of compliance with surface contaminated object regulatory requirements

    International Nuclear Information System (INIS)

    Pope, R.B.; Shappert, L.B.; Michelhaugh, R.D.; Boyle, R.W.; Cook, J.C.

    1998-02-01

    The US Department of Transportation (DOT) and the US Nuclear Regulatory Commission (NRC) have jointly prepared a comprehensive set of draft guidance for consignors and inspectors to use when applying the newly imposed regulatory requirements for low specific activity (LSA) material and surface contaminated objects (SCOs). The guidance is being developed to facilitate compliance with the new LSA material and SCO requirements, not to impose additional requirements. These new requirements represent, in some areas, significant departures from the manner in which packaging and transportation of these materials and objects were previously controlled. On occasion, it may be appropriate to use conservative approaches to demonstrate compliance with some of the requirements, ensuring that personnel are not exposed to radiation at unnecessary levels, so that exposures are kept as low as reasonably achievable (ALARA). In the draft guidance, one such approach would assist consignors preparing a shipment of a large number of SCOs in demonstrating compliance without unnecessarily exposing personnel. In applying this approach, users need to demonstrate that four conditions are met. These four conditions are used to categorize non-activated, contaminated objects as SCO-2. It is expected that, by applying this approach, it will be possible to categorize a large number of small contaminated objects as SCO-2 without the need for detailed, quantitative measurements of fixed, accessible contamination, or of total (fixed and non-fixed) contamination on inaccessible surfaces. The method, which is based upon reasoned argument coupled with limited measurements and the application of a sum of fractions rule, is described and examples of its use are provided

  11. Regulatory audit to the Argentine teletherapy units

    International Nuclear Information System (INIS)

    Kay, J.M.

    1995-01-01

    As a consequence of an erroneous calibration of the ionization chamber dosimeter of a new licensed 6 Mev electron lineal accelerator that caused accidental overexposures in the first patients under treatment, the Regulatory Board decided to perform an audit to every teletherapy unit (accelerator and telegammatherapy units) in Argentina. The audit was carried out at the en of 1994 in 27 accelerators and 107 telegammatherapy units. The objectives of the audit were the control of the mechanical and optical aspects of the each accelerator and telegammatherapy unit and the control of the calibration of their radiation beams. The last action was undertaken to detect as soon as possible, any eventual accidental overexposure or underexposure of patients under treatment. The audit was conducted by the author and performed for a team of 22 inspectors who worked in groups of 2 to 3 people and completed the inspection of the teletherapy units of the whole country in 3 months. As a result of the audit, the Regulatory Board had in a short period a clear panorama of the performance of each teletherapy unit of the country and also confirmed that no accidental situation had happened. The audit revealed the necessity of imposing urgent regulatory requirements not related to the calibration of the radiation beam in 5% of the cases, as well as non-urgent requirements of different importance in approximately other 60% of the cases. (author)

  12. Regulatory oversight of maintenance activities at nuclear power plants

    International Nuclear Information System (INIS)

    Pape, M.

    1997-01-01

    Regulation of nuclear safety in the UK is based on monitoring of compliance with licence conditions. This paper discusses legislation aspects, license conditions, license requirements for maintenance and maintenance activities in the UK. It also addresses the regulator utility interaction, the regulatory inspection of maintenance and the trends in maintenance. (author)

  13. Unsolved problems in applying U.S. regulatory guides to control system equipment

    International Nuclear Information System (INIS)

    Stade, R.E.

    1978-01-01

    Two current problems encountered when designing control systems to the United States Regulatory Guide requirements are discussed. They are: 1) Level of surge voltages that should be specified when procuring solid state control and instrumentation systems and equipment. 2) The approach to be used qualifying equipment that must meet the aging requirements. (author)

  14. Risk-informing special treatment requirements for reactors

    International Nuclear Information System (INIS)

    McKenna, E.M.; Reed, T.A.

    2001-01-01

    The U.S. Nuclear Regulatory Commission (NRC) is proposing to make regulatory changes to the scope of structures, systems, and components (SSCs) requiring special treatment. ''Special treatment requirements'' refers to those specific examples of regulations that are applied in order to provide a high degree of assurance that SSC will be capable of performing their intended functions when needed. The current scope of SSCs covered by the special treatment requirements governing commercial nuclear reactors is deterministically based and stems primarily from the evaluation of selected design basis events, as described in updated final safety analysis reports (UFSARs). This regulatory framework provides reasonable assurance of no undue risk to the health and safety of the public. However, recent advances in technology, coupled with operating reactor experience, have suggested that an alternative approach that would use a risk-informed process for evaluating SSC safety significance, would, in turn, result in a more focused determination of which SSCs should receive special treatment requirements. (author)

  15. [Software as medical devices/medical apps : Tasks, requirements, and experiences from the point of view of a competent authority].

    Science.gov (United States)

    Terhechte, Arno

    2018-03-01

    Software can be classified as a medical device according to the Medical Device Directive 93/42/EEC. The number of software products and medical apps is continuously increasing and so too is the use in health institutions (e. g., in hospitals and doctors' surgeries) for diagnosis and therapy.Different aspects of standalone software and medical apps from the perspective of the authority responsible are presented. The quality system implemented to establish a risk-based systematic inspection and supervision of manufacturers is discussed. The legal framework, as well as additional standards that are the basis for inspection, are outlined. The article highlights special aspects that occur during inspection like verification of software and interfaces, and the clinical evaluation of software. The Bezirksregierung, as the local government authority responsible in North Rhine-Westphalia, is also in charge of inspection of health institutions. Therefore this article is not limited to the manufacturers placing the software on the market, but in addition it describes the management and use of software as a medical device in hospitals.The future legal framework, the Medical Device Regulation, will strengthen the requirements and engage notified bodies more than today in the conformity assessment of software as a medical device.Manufacturers, health institutions, notified bodies and the authorities responsible are in charge of intensifying their efforts towards software as a medical device. Mutual information, improvement of skills, and inspections will lead to compliance with regulatory requirements.

  16. Regulatory aspects of Olkiluoto 3 nuclear power plant (EPR-1600) (Draft, 12 Sept. 2005)

    International Nuclear Information System (INIS)

    Sandberg, J.; Tiippana, P.

    2005-01-01

    A 1600 MWe European Pressurized Water Reactor (EPR) supplied by the Framatome ANP - Siemens Consortium is under construction at the Olkiluoto site in Finland. Current international safety requirements and especially French and German operating experience have been applied in the design. Finnish requirements and operating experience have also been applied, especially regarding site-specific features. Severe accidentmanagement and protection against a collision of a large passenger airplane are implemented in the plant design. The plant safety features, licensing procedure, Finnish regulatory requirements, changes to the original EPR design, project quality management and regulatory control are discussed. (author)

  17. The Energy Regulatory Commission (1). Law of the Comision Reguladora de Energia

    International Nuclear Information System (INIS)

    1995-01-01

    The Energy Regulatory Commission. Reforms to the Electric Energy Public Service Law (1992) and the Regulatory Law of Article 27 on Petroleum (1995) have brought about fundamental changes in the electric and natural gas industries. The legal reforms explicitly permit the private sector to construct, operate, and own, systems of electric generation and natural gas transportation, storage and distribution. The participation of the private sector in these areas required a redefinition in the government regulatory institutions. Accordingly the Federal Congress enacted the law of the Comision Reguladora de Energia (CRE) in 1995. The CRE law expands the scope of the CRE's authority and the breadth of its powers beyond those established when it was initially created in 1993. The CRE commenced operations in January 1994 as a decentralized technical and consultative body of the Energy Ministry. The decree that created the Commission limited the scope of its authority to an analysis and consultative role applicable only to the electric industry. (Author)

  18. Common definition for categories of clinical research: a prerequisite for a survey on regulatory requirements by the European Clinical Research Infrastructures Network (ECRIN)

    LENUS (Irish Health Repository)

    Kubiak, Christine

    2009-10-16

    Abstract Background Thorough knowledge of the regulatory requirements is a challenging prerequisite for conducting multinational clinical studies in Europe given their complexity and heterogeneity in regulation and perception across the EU member states. Methods In order to summarise the current situation in relation to the wide spectrum of clinical research, the European Clinical Research Infrastructures Network (ECRIN) developed a multinational survey in ten European countries. However a lack of common classification framework for major categories of clinical research was identified, and therefore reaching an agreement on a common classification was the initial step in the development of the survey. Results The ECRIN transnational working group on regulation, composed of experts in the field of clinical research from ten European countries, defined seven major categories of clinical research that seem relevant from both the regulatory and the scientific points of view, and correspond to congruent definitions in all countries: clinical trials on medicinal products; clinical trials on medical devices; other therapeutic trials (including surgery trials, transplantation trials, transfusion trials, trials with cell therapy, etc.); diagnostic studies; clinical research on nutrition; other interventional clinical research (including trials in complementary and alternative medicine, trials with collection of blood or tissue samples, physiology studies, etc.); and epidemiology studies. Our classification was essential to develop a survey focused on protocol submission to ethics committees and competent authorities, procedures for amendments, requirements for sponsor and insurance, and adverse event reporting following five main phases: drafting, consensus, data collection, validation, and finalising. Conclusion The list of clinical research categories as used for the survey could serve as a contribution to the, much needed, task of harmonisation and simplification of the

  19. Common definition for categories of clinical research: a prerequisite for a survey on regulatory requirements by the European Clinical Research Infrastructures Network (ECRIN

    Directory of Open Access Journals (Sweden)

    Sanz Nuria

    2009-10-01

    Full Text Available Abstract Background Thorough knowledge of the regulatory requirements is a challenging prerequisite for conducting multinational clinical studies in Europe given their complexity and heterogeneity in regulation and perception across the EU member states. Methods In order to summarise the current situation in relation to the wide spectrum of clinical research, the European Clinical Research Infrastructures Network (ECRIN developed a multinational survey in ten European countries. However a lack of common classification framework for major categories of clinical research was identified, and therefore reaching an agreement on a common classification was the initial step in the development of the survey. Results The ECRIN transnational working group on regulation, composed of experts in the field of clinical research from ten European countries, defined seven major categories of clinical research that seem relevant from both the regulatory and the scientific points of view, and correspond to congruent definitions in all countries: clinical trials on medicinal products; clinical trials on medical devices; other therapeutic trials (including surgery trials, transplantation trials, transfusion trials, trials with cell therapy, etc.; diagnostic studies; clinical research on nutrition; other interventional clinical research (including trials in complementary and alternative medicine, trials with collection of blood or tissue samples, physiology studies, etc.; and epidemiology studies. Our classification was essential to develop a survey focused on protocol submission to ethics committees and competent authorities, procedures for amendments, requirements for sponsor and insurance, and adverse event reporting following five main phases: drafting, consensus, data collection, validation, and finalising. Conclusion The list of clinical research categories as used for the survey could serve as a contribution to the, much needed, task of harmonisation and

  20. Information Management system of the safety regulatory requirements and guidance for the Korea next generation reactors

    International Nuclear Information System (INIS)

    Yun, Y. C.; Lee, J. H.; Lee, H. C.; Lee, J. S.

    2000-01-01

    In order to achieve the safety of the Korea Next Generation Reactors (KNGR), the Korea Institute of Nuclear Safety has carried out the Safety and Regulatory Requirements and Guidance (SRRG) development program from 1992 such as establishment of the SRRG hierarchy, development of technical requirements and guidance, and consideration of new licensing system. The SRRG hierarchy for the KNGR was consisted of five tiers; Safety Objectives, Safety Principles, General Safety Criteria, Specific Safety Requirements and Safety Regulatory Guides. The developed SRRG have been compared the criteria in 10CFR and Reg. Guide in the U.S.A and the IAEA documents for assuring internationally acceptable level of the SRRG. To improve the efficiency and accuracy of SRRG development, the construction of database system was required in the course of development. Therefore, the Information Management System of SRRG for the KNGR has been developed which enables developers to quickly and accurately seek and systematically manage whole contexts of the SRRG, reference requirements, and current atomic energy regulation rules. Moreover, through homepage whose URL is 'http://kngr.kins.re.kr', the concerned persons and public can acquire the information related with SRRG and KNGR project, and post his/her thought to the opinion forum in the homepage

  1. Information Management system of the safety regulatory requirements and guidance for the Korea next generation reactors

    Energy Technology Data Exchange (ETDEWEB)

    Yun, Y. C. [LG-EDS Systems, Seoul (Korea, Republic of); Lee, J. H.; Lee, H. C.; Lee, J. S. [Korea Institute of Nuclear Safety, Taejon (Korea, Republic of)

    2000-05-01

    In order to achieve the safety of the Korea Next Generation Reactors (KNGR), the Korea Institute of Nuclear Safety has carried out the Safety and Regulatory Requirements and Guidance (SRRG) development program from 1992 such as establishment of the SRRG hierarchy, development of technical requirements and guidance, and consideration of new licensing system. The SRRG hierarchy for the KNGR was consisted of five tiers; Safety Objectives, Safety Principles, General Safety Criteria, Specific Safety Requirements and Safety Regulatory Guides. The developed SRRG have been compared the criteria in 10CFR and Reg. Guide in the U.S.A and the IAEA documents for assuring internationally acceptable level of the SRRG. To improve the efficiency and accuracy of SRRG development, the construction of database system was required in the course of development. Therefore, the Information Management System of SRRG for the KNGR has been developed which enables developers to quickly and accurately seek and systematically manage whole contexts of the SRRG, reference requirements, and current atomic energy regulation rules. Moreover, through homepage whose URL is 'http://kngr.kins.re.kr', the concerned persons and public can acquire the information related with SRRG and KNGR project, and post his/her thought to the opinion forum in the homepage.

  2. 10 CFR 11.13 - Special requirements for transportation.

    Science.gov (United States)

    2010-01-01

    ... 10 Energy 1 2010-01-01 2010-01-01 false Special requirements for transportation. 11.13 Section 11.13 Energy NUCLEAR REGULATORY COMMISSION CRITERIA AND PROCEDURES FOR DETERMINING ELIGIBILITY FOR... Authorization § 11.13 Special requirements for transportation. (a) All individuals who, after 365 days following...

  3. Regulatory aspects for nuclear and radiation applications

    International Nuclear Information System (INIS)

    Duraisamy, S.

    2014-01-01

    The Atomic Energy Regulatory Board (AERB) is the national authority for ensuring that the use of ionizing radiation and nuclear energy does not cause any undue risk to the health of workers, members of the public and to the environment. AERB was constituted on November 15, 1983 and derives its regulatory power from the rules and notifications promulgated under the Atomic Energy Act, 1962 and the Environment (Protection) Act, 1986. AERB is provided with the necessary powers and mandate to frame safety policies, lay down safety standards and requirements for monitoring and enforcing the safety provisions. AERB follows multi-tier system for its review and assessment, safety monitoring, surveillance and enforcement. While regulating various nuclear and radiation facilities, AERB adopts a graded approach taking into account the hazard potential associated with the facilities being regulated. The regulatory process has been continuous evolving to cater to the new developments in reactor and radiation technologies. The regulatory effectiveness and efficiency of AERB have grown over the last three decades to make it into a robust organization. The radiation protection infrastructure in the country is on a sound footing and is constantly being strengthened based on experience and continued research and development. As one of its mandates AERB prescribes radiation dose limits for the occupational workers and the public, in line with the IAEA Safety Standard and ICRP recommendations. The current dose limits and the radiation safety requirements are more stringent than past. To meet the current safety standards, it is important for the facilities to have state of art radiation monitoring system and programme in place. While recognizing the current system in place, this presentation also highlights certain key radiation protection challenges associated with the implementation of radiation protection standards in the nuclear and radiation facilities especially in the areas of

  4. Common market but divergent regulatory practices: exploring European regulation and the effect on regulatory uncertainty in the marketing authorization of medical products

    NARCIS (Netherlands)

    Chowdhury, Nupur

    2013-01-01

    The medical product sector is characterised by a regulatory patchwork of European and national laws and guidelines operating concurrently with each other. Each of these sectors are characterised by different levels of regulatory uncertainty that may undermine the effectiveness of the regulatory

  5. 77 FR 8938 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing of...

    Science.gov (United States)

    2012-02-15

    ... expenses as ``other'' (miscellaneous), a very general categorization that provides FINRA limited visibility... supplemental filing would play with respect to a broker-dealer's annual audit.\\28\\ \\26\\ CAI. \\27\\ Id. \\28\\ Id... any future schedules or reports be done through the more typical self- regulatory organization (``SRO...

  6. Data Quality Objectives for Regulatory Requirements for Dangerous Waste Sampling and Analysis

    International Nuclear Information System (INIS)

    MULKEY, C.H.

    1999-01-01

    This document describes sampling and analytical requirements needed to meet state and federal regulations for dangerous waste (DW). The River Protection Project (RPP) is assigned to the task of storage and interim treatment of hazardous waste. Any final treatment or disposal operations, as well as requirements under the land disposal restrictions (LDRs), fall in the jurisdiction of another Hanford organization and are not part of this scope. The requirements for this Data Quality Objective (DQO) Process were developed using the RPP Data Quality Objective Procedure (Banning 1996), which is based on the U.S. Environmental Protection Agency's (EPA) Guidance for the Data Quality Objectives Process (EPA 1994). Hereafter, this document is referred to as the DW DQO. Federal and state laws and regulations pertaining to waste contain requirements that are dependent upon the composition of the waste stream. These regulatory drivers require that pertinent information be obtained. For many requirements, documented process knowledge of a waste composition can be used instead of analytical data to characterize or designate a waste. When process knowledge alone is used to characterize a waste, it is a best management practice to validate the information with analytical measurements

  7. Limits of the current EU regulatory framework on GMOs: risk of not authorized GM event-traces in imports

    Directory of Open Access Journals (Sweden)

    Roïz Julie

    2014-11-01

    Full Text Available Since their first commercialization in the 1990’s, the number of genetically modified organisms (GMOs cultivated around the world has steadily increased. This development has been accompanied by the development of regulatory and policy environments which vary from one country to another. Today, the European food and feed sectors are faced with the increasing risk of finding traces of not authorized GMOs in imports. Under the EU zero tolerance for unapproved GMOs, this situation may lead to trade disruptions with important cost implications. A regulatory environment which minimizes the risk of such disruption is therefore indispensable. To address this issue, the EU has adopted the “technical solution” but this remains insufficient to provide the necessary legal certainty which is needed to operate in such context. More comprehensive approaches are considered globally through low level presence policies.

  8. 78 FR 76757 - Regulatory Guidance on Hours of Service of Drivers Rest Break Requirement; Drivers Who Become...

    Science.gov (United States)

    2013-12-19

    ... limitations for unforeseen reasons, is the driver in violation of the Sec. 395.3 rest break provision if more... unforeseen reasons, is not in violation of the Sec. 395.3 rest-break requirements if 8 or more hours have... Regulatory Guidance on Hours of Service of Drivers Rest Break Requirement; Drivers Who Become Ineligible for...

  9. A guide to ventilation requirements for uranium mines and mills. Regulatory guide G-221

    International Nuclear Information System (INIS)

    2003-06-01

    The purpose of G-221 is to help persons address the requirements for the submission of ventilation-related information when applying for a Canadian Nuclear Safety Commission (CNSC) licence to site and construct, operate or decommission a uranium mine or mill. This guide is also intended to help applicants for a uranium mine or mill licence understand their operational and maintenance obligations with respect to ventilation systems, and to help CNSC staff evaluate the adequacy of applications for uranium mine and mill licences. This guide is relevant to any application for a CNSC licence to prepare a site for and construct, operate or decommission a uranium mine or mill. In addition to summarizing the ventilation-related obligations or uranium mine and mill licensee, the guide describes and discusses the ventilation-related information that licence applicants should typically submit to meet regulatory requirements. The guide pertains to any ventilation of uranium mines and mills for the purpose of assuring the radiation safety of workers and on-site personnel. This ventilation may be associated with any underground or surface area or premise that is licensable by the CNSC as part of a uranium mine or mill. These areas and premises typically include mine workings, mill buildings, and other areas or premises involving or potentially affected by radiation or radioactive materials. Some examples of the latter include offices, effluent treatment plants, cafeterias, lunch rooms and personnel change-rooms. (author)

  10. 75 FR 52380 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing of...

    Science.gov (United States)

    2010-08-25

    ... recent outsourcing of surveillance and other regulatory functions to FINRA.\\8\\ Specifically, to have... with NASD IM-1013-1 or NASD IM-1013-2, including limiting its business operations to ``permitted floor... NASD IM-1013-2 establish a waive-in membership application process for certain firms to become FINRA...

  11. Market power versus regulatory power in the Spanish electricity system, 1973-1996

    International Nuclear Information System (INIS)

    Garrues-Irurzun, Josean

    2010-01-01

    This study not only establishes that the institutional changes (the change of political regime) and economic changes (the energy crisis) that occurred during the 70s and 80s had an important effect on business strategies within the Spanish electricity sector, but, above all, it shows how the resulting regulatory model was not the product of any clearly defined plan on the part of the Spanish authorities (as the majority of authors seem to implicitly or explicitly maintain), but rather it arose from the dialectical interaction between companies which resisted losing the power of the market, and institutions which, in order to define any medium term energy policy in the future European domestic electricity market, required an increase in their regulatory power. (author)

  12. Preservation of primary information related to radiological protection and nuclear safety in the Argentine Nuclear Regulatory Authority

    International Nuclear Information System (INIS)

    Chahab, Martin

    2008-01-01

    The preservation of primary information related to Radiological Protection and Nuclear Safety in the Argentine Nuclear Regulatory Authority began as a need of and as significant contribution to the future activities of the institution. Since 2005 a high number of experts have retired from the organization and will continue to do so until 2010. Besides, the primary information that experts possess is technical information produced at the beginning of Argentina's regulatory activity in the 50 's. If this information on account of its relevance - could not be preserved properly or be made available to the future generation of scientists and technicians, such an issue could have a negative impact on the efficiency and effectiveness of the institution in the future. The methodology selected for the project comprises several stages. Overall, the first stage consists in identifying primary information and expert's explicit knowledge through interviews and personal consultations. The second stage consists in converting to digital format the documentation that experts have traditionally kept in paper format. The third stage deals with transferring to a new database the already digitalized information from the computers of experts who are about to retire. The final stage is based on managing this information by creating knowledge maps and socio-grams, experts personal Web sites and a database with a mega browser to make information readily accessible. During the early months of the project, 190 pages have on average been converted to digital format on a daily basis, the equivalent of around 8 MB of information. The men/hours employed for this task has been around 40 minutes per day. As time went by, the method turned more efficient and as a result, some 400 pages were converted to digital format on a daily basis, accounting for 16 MB of information. The men/hours employed for this task has been around 60 minutes per day. Up until mid 2008, more than 1,000 documents have been

  13. Development of guidance on applications of regulatory requirements for low specific activity materials and surface contaminated objects

    International Nuclear Information System (INIS)

    Pope, R.B.; Easton, E.P.; Shankman, S.F.

    1997-01-01

    In 1985, the International Atomic Energy Agency issued revised regulations for the safe transport of radioactive material. Significant among the changes were major revisions to requirements for Low Specific Activity (LSA) material and Surface Contaminated Objects (SCOs). In preparation for the adoption of these requirements into regulations in the United States, it became apparent that guidance on how to apply these requirements, clarifying technical uncertainties and ensuring proper implementation, would be needed both by the regulators and those regulated. Thus, the US Department of Transportation and the US Nuclear Regulatory Commission, with the assistance of staff from Oak Ridge National Laboratory, are preparing regulatory guidance for LSA material and SCO transport. The guidance will present examples of acceptable methods for demonstrating compliance with the revised rules. Ideas being investigated for inclusion in the pending guidance are discussed in this paper. Under current plans, the guidance will be issued for public comment prior to final issuance of the guidance in 1997

  14. The current regulatory requirements on optimisation and BAT in Sweden in the context of geological disposal

    International Nuclear Information System (INIS)

    Dverstorp, B.

    2010-01-01

    Bjorn Dverstorp, Swedish Radiation Safety authority (SSM) presented 'The current regulatory requirements on optimisation and BAT in Sweden in the context of geological disposal'. In Sweden, a nuclear waste repository will be evaluated according to both to general environmental legislation (the Environmental Code, SFS, 1998:808) and according to more specific requirements in the Act on Nuclear Activities (SFS, 1984:3) and the Radiation Protection Act (SFS, 1988:220). The evaluations according to these laws will be carried out according to two separate, but coordinated, legal-review and decision-making processes. This will be a basis for the siting process. Although the requirements on BAT and siting in the Environmental Code apply to radiological protection, they aim at a broader system optimisation. The more specific requirements on optimisation and BAT of radiological protection of geological disposal systems are given in the regulations associated with the Radiation Protection Act. The Swedish radiation protection regulations (SSM, 2009) comprise three corner stones: a risk target, environmental protection goals and the use of optimisation and BAT. In SSM' s guidance optimisation is defined as a means to reduce risk, guided by the results of risk calculations. In case of a conflict between BAT and optimisation, measures satisfying BAT should have priority. Application of optimisation and BAT on different timescales are described as well as for human intrusion scenarios. B. Dverstorp explained that because of uncertainties in the long term there is a need for additional arguments in the safety case in support of decision making. It is in this context that the requirements on optimisation and BAT should be seen as supplementary to the risk target, in providing evidence that the developer has taken into consideration, as far as reasonably possible, measures and options for reducing future doses and risks. Both principles focus on the proponent's work on developing

  15. National competent authorities responsible for approvals and authorizations in respect of the transport of radioactive material. List no. 27. 1996 edition

    International Nuclear Information System (INIS)

    1996-01-01

    Any national or international authority designated or otherwise recognised as such for any purpose in connection with the transport Regulations is known as a competent authority. In the Member States such a body has the responsibility for establishing national legislation to bring the Agency's transport Regulations into effect and for assuring compliance with its requirements. Depending on the national regulatory or institutional framework the functions of the competent authority may be assigned to one or more bodies. To assist Member States in implementing the transport Regulations and carrying out responsibility for compliance assurance, the IAEA continues to maintain this updated list of designated national competent authorities. Member States are annually requested to verify the list for correctness and completeness

  16. National competent authorities responsible for approvals and authorizations in respect of the transport of radioactive material. List no. 30. 1999 edition

    International Nuclear Information System (INIS)

    1999-02-01

    Any national or international authority designated or otherwise recognised as such for any purpose in connection with the transport Regulations is known as a competent authority. In the Member States such a body has the responsibility for establishing national legislation to bring the Agency's transport Regulations into effect and for assuring compliance with its requirements. Depending on the national regulatory or institutional framework the functions of the competent authority may be assigned to one or more bodies. To assist Member States in implementing the transport Regulations and carrying out responsibility for compliance assurance, the IAEA continues to maintain this updated list of designated national competent authorities. Member States are annually requested to verify the list for correctness and completeness

  17. National competent authorities responsible for approvals and authorizations in respect of the transport of radioactive material. List no. 31. 2000 edition

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2000-02-01

    Any national or international authority designated or otherwise recognised as such for any purpose in connection with the transport Regulations is known as a competent authority. In the Member States such a body has the responsibility for establishing national legislation to bring the Agency's transport Regulations into effect and for assuring compliance with its requirements. Depending on the national regulatory or institutional framework the functions of the competent authority may be assigned to one or more bodies. To assist Member States in implementing the transport Regulations and carrying out responsibility for compliance assurance, the IAEA continues to maintain this updated list of designated national competent authorities. Member States are annually requested to verify the list for correctness and completeness.

  18. National competent authorities responsible for approvals and authorizations in respect of the transport of radioactive material. List no. 29. 1998 edition

    International Nuclear Information System (INIS)

    1998-02-01

    Any national or international authority designated or otherwise recognised as such for any purpose in connection with the transport Regulations is known as a competent authority. In the Member States such a body has the responsibility for establishing national legislation to bring the Agency's transport Regulations into effect and for assuring compliance with its requirements. Depending on the national regulatory or institutional framework the functions of the competent authority may be assigned to one or more bodies. To assist Member States in implementing the transport Regulations and carrying out responsibility for compliance assurance, the IAEA continues to maintain this updated list of designated national competent authorities. Member States are annually requested to verify the list for correctness and completeness

  19. National competent authorities responsible for approvals and authorizations in respect of the transport of radioactive material. List no. 30. 1999 edition

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1999-02-01

    Any national or international authority designated or otherwise recognised as such for any purpose in connection with the transport Regulations is known as a competent authority. In the Member States such a body has the responsibility for establishing national legislation to bring the Agency's transport Regulations into effect and for assuring compliance with its requirements. Depending on the national regulatory or institutional framework the functions of the competent authority may be assigned to one or more bodies. To assist Member States in implementing the transport Regulations and carrying out responsibility for compliance assurance, the IAEA continues to maintain this updated list of designated national competent authorities. Member States are annually requested to verify the list for correctness and completeness.

  20. National competent authorities responsible for approvals and authorizations in respect of the transport of radioactive material. List no. 26. 1995 edition

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-01-01

    Any national or international authority designated or otherwise recognised as such for any purpose in connection with the transport Regulations is known as a competent authority. In the Member States such a body has the responsibility for establishing national legislation to bring the Agency's transport Regulations into effect and for assuring compliance with its requirements. Depending on the national regulatory or institutional framework the functions of the competent authority may be assigned to one or more bodies. To assist Member States in implementing the transport Regulations and carrying out responsibility for compliance assurance, the IAEA continues to maintain this updated list of designated national competent authorities. Member States are annually requested to verify the list for correctness and completeness.

  1. National competent authorities responsible for approvals and authorizations in respect of the transport of radioactive material. List no. 29. 1998 edition

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1998-02-01

    Any national or international authority designated or otherwise recognised as such for any purpose in connection with the transport Regulations is known as a competent authority. In the Member States such a body has the responsibility for establishing national legislation to bring the Agency's transport Regulations into effect and for assuring compliance with its requirements. Depending on the national regulatory or institutional framework the functions of the competent authority may be assigned to one or more bodies. To assist Member States in implementing the transport Regulations and carrying out responsibility for compliance assurance, the IAEA continues to maintain this updated list of designated national competent authorities. Member States are annually requested to verify the list for correctness and completeness.

  2. National competent authorities responsible for approvals and authorizations in respect of the transport of radioactive material. List no. 26. 1995 edition

    International Nuclear Information System (INIS)

    1995-01-01

    Any national or international authority designated or otherwise recognised as such for any purpose in connection with the transport Regulations is known as a competent authority. In the Member States such a body has the responsibility for establishing national legislation to bring the Agency's transport Regulations into effect and for assuring compliance with its requirements. Depending on the national regulatory or institutional framework the functions of the competent authority may be assigned to one or more bodies. To assist Member States in implementing the transport Regulations and carrying out responsibility for compliance assurance, the IAEA continues to maintain this updated list of designated national competent authorities. Member States are annually requested to verify the list for correctness and completeness

  3. National competent authorities responsible for approvals and authorizations in respect of the transport of radioactive material. List no. 31. 2000 edition

    International Nuclear Information System (INIS)

    2000-02-01

    Any national or international authority designated or otherwise recognised as such for any purpose in connection with the transport Regulations is known as a competent authority. In the Member States such a body has the responsibility for establishing national legislation to bring the Agency's transport Regulations into effect and for assuring compliance with its requirements. Depending on the national regulatory or institutional framework the functions of the competent authority may be assigned to one or more bodies. To assist Member States in implementing the transport Regulations and carrying out responsibility for compliance assurance, the IAEA continues to maintain this updated list of designated national competent authorities. Member States are annually requested to verify the list for correctness and completeness

  4. Nuclear knowledge management system in the regulatory activity

    International Nuclear Information System (INIS)

    Nosovskij, A.V.; Klevtsov, A.L.; Kravchenko, N.A.

    2010-01-01

    Important issues on collection, storage and spread of knowledge among organisation dealing with the use of nuclear technologies, role of close cooperation between enterprises and organizations in developing knowledge management, general requirements for creating a nuclear knowledge management system are considered. Recommendations and the main mechanisms are identified to create the knowledge management system in technical support organizations of the regulatory authority.

  5. Organization and implementation of a national programme of regulatory control of sources in Estonia

    International Nuclear Information System (INIS)

    Filippova, I.

    1998-01-01

    The application of ionizing radiation and radioactive material in fields such as medicine, industry, teaching and research is constantly increasing. Consequently, any country using ionizing radiation and radioactive material in these applications must ensure that they are used safely. In order to achieve this goal a country must establish appropriate national infrastructure related to radiation protection and safety. This requires appropriate regulatory mechanism together with an enforcement ability. The national infrastructure adopted in a country will depend on the actual needs of the country, the size and the complexity of the regulated practices and sources, as well as on the regulatory tradition in the country. The national infrastructure in Estonia comprises of three main components: legislation, regulatory authority, resources. (author)

  6. Regulatory assessment of safety culture in nuclear organisations - current trends and challenges

    International Nuclear Information System (INIS)

    Tronea, M.

    2010-01-01

    The paper gives an overview of the current practices in the area of regulatory assessment of safety culture in nuclear organisations and of the associated challenges. While the assessment and inspection procedures currently in use by regulatory authorities worldwide are directed primarily at verifying compliance with the licensing basis, there is a recognised need for a more systematic approach to the identification, collection and review of data relevant to the safety culture in licensees' organisations. The paper presents a proposal for using the existing regulatory inspection practices for gathering information relevant to safety culture and for assessing it in an integrated manner. The proposal is based on the latest requirements and guidance issued by the International Atomic Energy Agency (IAEA) on management systems for nuclear facilities and activities, particularly as regards the attributes needed for a strong nuclear safety culture. (author)

  7. Legal principles of regulatory administration and nuclear safety regulation

    Energy Technology Data Exchange (ETDEWEB)

    Lee, Kyeong Hui; Cheong, Sang Kee [Hannam Univ., Taejon (Korea, Republic of)

    2000-12-15

    This research presents a critical analysis and evaluation of principles of administrative laws in order to provide framework of structural reform on the nuclear safety regulation system. The focus of this analysis and evaluation is centered around the area of origin of regulatory administrative laws; authorities of regulation; procedures of regulatory actions; regulatory enforcement; and administrative relief system. In chapter 2 the concept of regulatory administration is analysed. Chapter 3 identifies the origin of regulatory administration and the principles of administration laws. It also examines legal nature of the nuclear safety standard. In relation to regulatory authorities. Chapter 4 identifies role and responsibility of administration authorities and institutions. It also examines fundamental principles of delegation of power. Then the chapter discusses the nuclear safety regulation authorities and their roles and responsibilities. Chapter 5 classifies and examines regulatory administration actions. Chapter 6 evaluates enforcement measure for effectiveness of regulation. Finally, chapter 7 discusses the administrative relief system for reviewing unreasonable regulatory acts.

  8. Regulatory practices of radiation safety of SNF transportation in Russia

    International Nuclear Information System (INIS)

    Kuryndina, Lidia; Kuryndin, Anton; Stroganov, Anatoly

    2008-01-01

    This paper overviews current regulatory practices for the assurance of nuclear and radiation safety during railway transportation of SNF on the territory of Russian Federation from NPPs to longterm-storage of reprocessing sites. The legal and regulatory requirements (mostly compliant with IAEA ST-1), licensing procedure for NM transportation are discussed. The current procedure does not require a regulatory approval for each particular shipment if the SNF fully comply with the Rosatom's branch standard and is transported in approved casks. It has been demonstrated that SNF packages compliant with the branch standard, which is knowingly provide sufficient safety margin, will conform to the federal level regulations. The regulatory approval is required if a particular shipment does not comply with the branch standard. In this case, the shipment can be approved only after regulatory review of Applicant's documents to demonstrate that the shipment still conformant to the higher level (federal) regulations. The regulatory review frequently needs a full calculation test of the radiation safety assurance. This test can take a lot of time. That's why the special calculation tools were created in SEC NRS. These tools aimed for precision calculation of the radiation safety parameters by SNF transportation use preliminary calculated Green's functions. Such approach allows quickly simulate any source distribution and optimize spent fuel assemblies placement in cask due to the transport equation property of linearity relatively the source. The short description of calculation tools are presented. Also, the paper discusses foreseen implications related to transportation of mixed-oxide SNF. (author)

  9. Development of infrastructure for the regulatory authority to implement risk-informed regulation

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2013-08-15

    It is important to assure the technical adequacy of probabilistic risk assessment (PRA) to implement risk-informed regulation of nuclear power plants (NPPs). JNES has been conducting various activities, such as development of PRA model, method, and data base, in order to assure the technical adequacy of PRA as development of the infrastructure for the regulatory authority to implement risk-informed regulation. In 2012, JNES updated the reliability data base used in PRA and improved PRA models to enhance the technical bases of PRA. In addition, JNES has been establishing the PRA model for fuel damage in the spent fuel storage pool in NPPs. As for improvement of PRA model for core damage in reactor, JNES conducted the study including feasibility of a simplified reliability model for digital I and C system developed by the digital I and C task group of OECD/NEA CSNI WGRISK by reproducing the sample calculation, and improvement of PRA models of individual NPPs in Japan. JNES is making effort to develop the procedures of internal fire PRA and internal flooding PRA. To improve the internal fire PRA, JNES is participating in OECD/NEA FIRE project to obtain the latest information and to validate and improve the fire propagation analysis codes and the parameters. JNES is establishing a method for analyzing internal influence due to flooding in NPPs, and this method is the base to develop the procedure of internal flooding PRA. (author)

  10. Improving regulatory oversight of maintenance programs

    International Nuclear Information System (INIS)

    Cook, S.

    2008-01-01

    Safe nuclear power plant operation requires that risks due to failure or unavailability of Structures, Systems and Components (SSCs) be minimized. Implementation of an effective maintenance program is a key means for achieving this goal. In its regulatory framework, the important relationship between maintenance and safety is acknowledged by the CNSC. A high level maintenance program requirement is included in the Class I Facilities Regulations. In addition, the operating licence contains a condition based on the principle that the design function and performance of SSCs needs to remain consistent with the plant's design and analysis documents. Nuclear power plant licensees have the primary responsibility for safe operation of their facilities and consequently for implementation of a successful maintenance program. The oversight role of the Canadian Nuclear Safety Commission (CNSC) is to ensure that the licensee carries out that responsibility. The challenge for the CNSC is how to do this consistently and efficiently. Three opportunities for improvement to regulatory maintenance oversight are being pursued. These are related to the regulatory framework, compliance verification inspection activities and monitoring of self-reporting. The regulatory framework has been improved by clarifying expectations through the issuance of S-210 'Maintenance Programs for Nuclear Power Plants'. Inspection activities have been improved by introducing new maintenance inspections into the baseline program. Monitoring is being improved by making better use of self-reported and industry produced maintenance related performance indicators. As with any type of program change, the challenge is to ensure the consistent and optimal application of regulatory activities and resources. This paper is a summary of the CNSC's approach to improving its maintenance oversight strategy. (author)

  11. Nuclear regulatory regime in Lithuania

    International Nuclear Information System (INIS)

    Kutas, S.

    1999-01-01

    The Law on Nuclear Energy establishes the legal basis for nuclear safety in the Republic of Lithuania. It assigns the responsibility for safety to the operating organization of a nuclear facility and outlines the tasks of the operator and the regulatory authority. According to this Law, the Nuclear Power Safety Inspectorate (VATESI) shall implement state regulation of nuclear safety. Standards and rules, guides and regulations of nuclear safety and radiation protection approved by the Government or by the institutions authorised. It is mandatory for all public and local authorities, enterprises, institutions, organisations, their associations, the officials and other persons whose activities are related to the operation of nuclear facilities, to the use and management of nuclear and radioactive materials therein. Safety guarantee in nuclear energy based on the requirements of the laws and regulations of the Republic of Lithuania, on the requirements of the international treaties to which the Republic of Lithuania is a party, also on the recommendations of the IAEA and other international organisations and authorities

  12. Federal and state regulatory requirements for the D ampersand D of the Alpha-4 Building, Y-12 Plant, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    Etnier, E.L.; Houlberg, L.M.; Bock, R.E.

    1994-01-01

    The US Department of Energy (DOE) has begun the decontamination and decommissioning (D ampersand D) of Building 9201-4 (Alpha-4) at the Oak Y-12 Plant, Oak Ridge, Tennessee, The Alpha-4 Building was used from 1953--1962 to house a column exchange (Colex) process for lithium isotope separation. This process involved electrochemical and solvent extraction processes that required substantial quantities of mercury. Presently there is no law or regulation mandating decommissioning at DOE facilites or setting de minimis or ''below regulatory concern'' (BRC) radioactivity levels to guide decommissioning activities at DOE facilities. However, DOE Order 5820.2A, Chap. V (Decommissioning of Radioactively Contaminated Facilities), requires that the regulatory status of each project be identified and that technical engineering planning must assure D ampersand D compliance with all environmental regulations during cleanup activities. To assist in the performance of this requirement, this paper gives a brief overview of potential federal and state regulatory requirements related to D ampersand D activities at Alpha-4. Compliance with other federal, state, and local regulations not addressed here may be required, depending on site characterization, actual D ampersand D activities, and wastes generated

  13. Information system fur the management of a regulatory programme

    International Nuclear Information System (INIS)

    Ortiz, P.; Mrabit, K.; Miaw, S.

    1998-01-01

    A Regulatory Programme to monitor safety of activities involving radiation sources, implies the existence of a Regulatory Authority empowered by legislation to issue radiation protection regulations and to monitor compliance with those regulations. The core element of the programme is a system of notification and authorization (registration and licensing), inspection and enforcement. The efficiency of this system is largely dependent on the availability of reliable information on the inventory of radiation sources and installations, the administrative status of the facilities (authorization), prompt processing of inspection reports and follow up of regulatory actions, including monitoring deadlines. Essential data relevant to safety, such as personal dosimetry for occupationally exposed individuals, inspection findings and incident reports would provide, in addition, an insight on the overall safety of the country. A simple but comprehensive Regulatory Authority Information System (RAIS) linked to the authorization and inspection process will largely facilitate regulatory decisions and actions. A readily available and reliable information from the various regulatory activities will facilitate planning, optimization of resources, monitoring safety related data, disseminating safety information, making decisions and follow up regulatory actions including monitoring dead lines. The implementation of the system in more than 50 countries will contribute to experience exchange and harmonization of regulatory activities. (author)

  14. Accelerator production of tritium authorization basis strategy

    International Nuclear Information System (INIS)

    Miller, L.A.; Edwards, J.; Rose, S.

    1996-01-01

    The Accelerator Production of Tritium (APT) project has proposed a strategy to develop the APT authorization basis and safety case based on DOE orders and fundamental requirements for safe operation. The strategy is viable regardless of whether the APT is regulated by DOE or by an external regulatory body. Currently the operation of Department of Energy (DOE) facilities is authorized by DOE and regulated by DOE orders and regulations while meeting the environmental protection requirements of the Environmental Protection Agency (EPA) and the states. In the spring of 1994, Congress proposed legislation and held hearings related to requiring all DOE operations to be subject to external regulation. On January 25, 1995, DOE, with the support of the White House Council on Environmental Quality, created the Advisory Committee on External Regulation of Department of Energy Nuclear Safety. This committee divided its recommendations into three areas: (1) facility safety, (2) worker safety, and (3) environmental protection. In the area of facility safety the committee recommended external regulation of DOE nuclear facilities by either the Nuclear Regulatory Commission (NRC) or a restructured Defense Nuclear Facilities Safety Board (DNFSB). In the area of worker safety, the committee recommended that the Occupational Safety and Health Administration (OSHA) regulate DOE nuclear facilities. In the environmental protection area, the committee did not recommend a change in the regulation by the EPA and the states of DOE nuclear facilities. If these recommendations are accepted, all DOE nuclear facilities will be impacted to some extent

  15. Performance-based quality assurance: the regulatory viewpoint

    International Nuclear Information System (INIS)

    Sajaroff, Pedro M.

    2000-01-01

    This paper complements and upgrades a previous one recently presented, the aim is a further contribution to a wide dissemination of this new methodology and way of thinking. Modern quality management techniques emphasizes errors prevention instead of finding and correcting them, in line with the new generation of ISO-9000 documents. Performance-based QA is coherent with this 'right-first-time' attitude, resting on the managerial role (establishing and applying policies and instructions allowing to integrate quality objectives to everyday work) and on the responsibility of every single involved person (the attainment of such objectives). The contents of the final draft of the revised IAEA NUSS Code on QA -namely 'Quality Assurance for Safety in Nuclear Power Plants and other Nuclear Facilities', is based on that approach, so it is not perspective. The text only contains ten basic requirements, where the objective is improving nuclear safety through an improvement in the methods applied for attaining quality during design, construction, commissioning, operation and decommissioning of nuclear installations. These requirements are assigned to: 'Management' (QA programme; training and qualification; non-conformance control and corrective actions; document control and records); 'Performance' (work; design; procurement; inspection and testing for acceptance) and 'Assessment' (management self-assessment; independent assessment). The management is responsible for planning, organization, direction, control and support; the line groups are responsible for attaining quality; and the assessment group is responsible for analyzing the management's and the line groups' effectiveness. From the regulatory point of view in the performance context, operating organizations will have to demonstrate the effective fulfillment of QA requirements to the satisfaction of regulatory authorities. This is not a novel mechanism, it is usual within the regulatory performance approach. The Code is

  16. The Role of Advisory Committees on Regulatory functions: Argentine Experience

    International Nuclear Information System (INIS)

    Larcher, A. M.; Arias, C.; Kunst, J. J.; Perez, R. M.; Rudelli, M.

    2004-01-01

    The Argentine Nuclear Regulatory Authority (NRA) has appointed a consultants body that advises its Board of Directors on aspects related to authorization's granting to individuals for the use of radioisotopes and ionizing radiation in medicine, research and industry. Such committee, whose existence goes back to the year 1958, is integrated by prominent professionals knowledgeable about ionizing radiation and radioisotopes applications in the medical, biomedical and industrial fields, representing important professional associations or institutions related to the practices in question. Originally, the committee was conceived as a consultation body to fulfil two important functions: To produce, in a regular way, authorized opinions at experts level to settle down questions relative to the regulation of practices, new at that time in the country, and To submit to a peer review applications for individual authorization for different uses of ionizing radiation previously it's granting by the Regulatory Authority. In this paper the role of the advisory council is analyzed from a historical perspective trying to emphasize an outstanding aspect not sufficiently analyzed linked to the capability that advisory bodies, with representative users' presence, can reach in the interpretation of regulatory standards based on a performance philosophy. Such approach outlines the permanent dilemma about the performance level of the licensee that should satisfy the Regulatory Authority. Once the broad objectives of radiation protection has been defined professional criteria is required for applying them to different practices. Balance between flexibility and avoidance of excessive uncertainty is desirable. In the authors' opinion the inclusion, inside the regulator's structure of consultants bodies giving direct participation to qualified stakeholders, far from harming the necessary independence that should characterize the regulator, on the contrary, allows to have an excellent social

  17. 75 FR 48731 - Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing of...

    Science.gov (United States)

    2010-08-11

    ... SECURITIES AND EXCHANGE COMMISSION [Release No. 34-62655; File No. SR-FINRA-2010-042] Self... Change To Adopt FINRA Rule 4160 (Verification of Assets) August 5, 2010. Pursuant to Section 19(b)(1) of... rule change from interested persons. \\1\\ 15 U.S.C. 78s(b)(1). \\2\\ 17 CFR 240.19b-4. I. Self-Regulatory...

  18. Regulatory aspects of the radioactive waste management in Argentina

    International Nuclear Information System (INIS)

    Siraky, Graciela

    2000-01-01

    This paper describes briefly the legislative and regulatory framework in which the radioactive waste management is carried out in Argentina. The activities of the Nuclear Regulatory Authority (NRA) and the applied approaches in relation to inspection of facilities, safety assessments of associated systems and collaboration in the matter with international agencies are also exposed. The 'National Law of the Nuclear Activity' (No. 24804), in force since April 1997, assigns to NRA the following functions: to regulate and to inspect nuclear activities regarding radiological and nuclear safety, physical protection of nuclear materials, in order to verify that such materials are used exclusively with peaceful purposes and also, to advise the National Executive Power in matters of its competence. For the fulfilment of these functions the Law grants to NRA the necessary legal competence to develop, to establish and to apply a regulatory system to all nuclear activities carried out in Argentina. The activity of NRA is carried out in the framework of a regulatory system whose fundamental aspect in the approach adopted to establish the requirements of safety, which is know as 'of performance'. This system has a group of rules known as 'AR Standards' (AR: abbreviation of Regulatory Authority) that, among other requirements, establish that the construction, operation and decommissioning of a nuclear installation can not start without the corresponding construction, operation or decommissioning license. In that sense, besides having the legal competence in the topic, NRA has developed its necessary technical competence to evaluate, with own criteria, all radiological and nuclear safety aspects involved in the grant of licenses and to guarantee an appropriate level of control in the facilities. In relation to the radioactive waste management, NRA has developed some basic criteria. These criteria underline the requirements put to the 'Responsible Entity' that generates or manages

  19. Co-operation Between Different Authorities on Radiation and Health Protection Related to the Measures in Andreeva Bay

    International Nuclear Information System (INIS)

    Sneve, Malgorzata K.

    2003-01-01

    The Norwegian Radiation Protection Authority (NRPA) has been involved in the implementation of the Norwegian Plan of Action run by the Norwegian Government to ensure appropriate environmental protection and nuclear safety in the decommissioning of nuclear installations in the Northwest Russia. One objective is to ensure that the procedures used for the decommissioning of nuclear installations and radioactive waste management are appropriate and consistent with relevant policies and guidelines adopted by Russian regulatory bodies and international agencies. NRPA is an advisor for the Norwegian Ministry of Foreign Affairs on radiation protection and nuclear safety issues and ensures good co-operation with Russian authorities on the common goals. The Russian Federation state regulatory process imposes strict requirements on operators to demonstrate adequate safety, environmental and human health protection. Practically, however, there is little experience in Russia of how to assess coherently and combine all different issues within an overall process that leads to informed decision making. Regulatory requirements and related assessments tend to focus either on safety (prevention of accidents), protection of human health (in normal operations and in the event of accidents) or protection of the environment as distinct from human health, not on the whole problem. The Regulatory Support Project has been carried out by NRPA and different Russian regulatory bodies like Gosatomnadzor, Medbioextreme and others with support also from regulatory bodies in other countries. The major goal of the Regulatory Support Project is to support Russian regulatory bodies when developing guidelines and requirements for the planning, licensing and implementation of the industry projects. Another goal is that related industrial projects in Northwest Russia are managed in such a way as to efficiently secure an acceptable level of protection of human health and the environment, consistent with

  20. Electricity and telecommunications regulatory institutions in small and developing countries

    Energy Technology Data Exchange (ETDEWEB)

    Stern, J. [London Business School, London (United Kingdom)

    2000-09-01

    The spread of utility liberalisation and privatisation to middle and low income developing countries raises the problem of whether and how they can establish an effective regulatory capability of whether the supply of regulatory services is likely to be insufficient. The paper presents evidence on the size of electricity regulatory agencies in 24 mainly middle and lower income countries as well as the number of high-level, specialist regulatory staff and the potential resource pool from post-school education. The paper also discusses how far the problem can be alleviated and/or avoided by the use of regulation by contract, regulation by multi-national regulatory agency or contracting-out. The paper concludes that such solutions are unlikely to be generally effective but that informal exchanges of information and pooling of resources between national regulators on a market-driven basis, as seen in Southern Africa and the EU, is a promising option. The paper concludes by pointing to the need to ascertain the minimum required regulatory capability in developing countries as perceived by Governments and potential investors. (author)

  1. Regulatory and management approaches to NORM residues in Malaysia

    International Nuclear Information System (INIS)

    Omar, M.; Teng, I.L.

    2006-01-01

    Naturally Occurring Radioactive Material (NORM) processing industries in Malaysia include oil and gas production and mineral processing plants. These industries are controlled by the Atomic Energy Licensing Board of Malaysia (AELB) through the enforcement of the Atomic Energy Licensing Act 1984 (Act 304). Related regulations have been developed in order to ensure the safety of workers and members of the public. However, more regulations are necessary for the safe handling of NORM. NORM processing generates various types of NORM residues that require proper management. As for low-level NORM residues, landfill disposal can be exempted from regulatory control if the Radiological Impact Assessment (RIA) shows that the additional dose to the members of the public is below the limit set by the authority. This paper outlines the regulatory and management approaches to NORM residues in Malaysia. (author)

  2. State Regulatory Authority (SRA) Coordination of Safety, Security, and Safeguards of Nuclear Facilities: A Framework for Analysis

    International Nuclear Information System (INIS)

    Mladineo, S.; Frazar, S.; Kurzrok, A.; Martikka, E.; Hack, T.; Wiander, T.

    2013-01-01

    In November 2012 the International Atomic Energy Agency (IAEA) sponsored a Technical Meeting on the Interfaces and Synergies in Safety, Security, and Safeguards for the Development of a Nuclear Power Program. The goal of the meeting was to explore whether and how safeguards, safety, and security systems could be coordinated or integrated to support more effective and efficient nonproliferation infrastructures. While no clear consensus emerged, participants identified practical challenges to and opportunities for integrating the three disciplines’ regulations and implementation activities. Simultaneously, participants also recognized that independent implementation of safeguards, safety, and security systems may be more effective or efficient at times. This paper will explore the development of a framework for conducting an assessment of safety-security-safeguards integration within a State. The goal is to examine State regulatory structures to identify conflicts and gaps that hinder management of the three disciplines at nuclear facilities. Such an analysis could be performed by a State Regulatory Authority (SRA) to provide a self-assessment or as part of technical cooperation either with a newcomer State, or to a State with a fully developed SRA.

  3. The Safety Culture of an Effective Nuclear Regulatory Body

    International Nuclear Information System (INIS)

    Carlsson, Lennart; Bernard, Benoit; Lojk, Robert; Koskinen, Kaisa; Rigail, Anne-Cecile; Stoppa, Gisela; Lorand, Ferenc; Aoki, Masahiro; Fujita, Kenichi; Takada, Hiroko; Kurasaki, Takaaki; Choi, Young Sung; Smit, Martin; Bogdanova, Tatiana; Sapozhnikov, Alexander; Smetnik, Alexander; Cid Campo, Rafael; Axelsson, Lars; Carlsson, Lennart; Edland, Anne; Ryser, Cornelia; Cohen, Miriam; Ficks, Ben; Valentin, Andrea; Nicic, Adriana; Lorin, Aurelie; Nezuka, Takayoshi; Creswell, Len

    2016-01-01

    The fundamental objective of all nuclear safety regulatory bodies is to ensure that activities related to the peaceful use of nuclear energy are carried out in a safe manner within their respective countries. In order to effectively achieve this objective, the nuclear regulatory body requires specific characteristics, one of which is a healthy safety culture. This regulatory guidance report describes five principles that support the safety culture of an effective nuclear regulatory body. These principles concern leadership for safety, individual responsibility and accountability, co-operation and open communication, a holistic approach, and continuous improvement, learning and self-assessment. The report also addresses some of the challenges to a regulatory body's safety culture that must be recognised, understood and overcome. It provides a unique resource to countries with existing, mature regulators and can be used for benchmarking as well as for training and developing staff. It will also be useful for new entrant countries in the process of developing and maintaining an effective nuclear safety regulator. (authors)

  4. Regulatory inspection of nuclear facilities and enforcement by the regulatory body. Safety guide

    International Nuclear Information System (INIS)

    2002-01-01

    The purpose of this Safety Guide is to provide recommendations for regulatory bodies on the inspection of nuclear facilities, regulatory enforcement and related matters. The objective is to provide the regulatory body with a high level of confidence that operators have the processes in place to ensure compliance and that they do comply with legal requirements, including meeting the safety objectives and requirements of the regulatory body. However, in the event of non-compliance, the regulatory body should take appropriate enforcement action. This Safety Guide covers regulatory inspection and enforcement in relation to nuclear facilities such as: enrichment and fuel manufacturing plants; nuclear power plants; other reactors such as research reactors and critical assemblies; spent fuel reprocessing plants; and facilities for radioactive waste management, such as treatment, storage and disposal facilities. This Safety Guide also covers issues relating to the decommissioning of nuclear facilities, the closure of waste disposal facilities and site rehabilitation. Section 2 sets out the objectives of regulatory inspection and enforcement. Section 3 covers the management of regulatory inspections. Section 4 covers the performance of regulatory inspections, including internal guidance, planning and preparation, methods of inspection and reports of inspections. Section 5 deals with regulatory enforcement actions. Section 6 covers the assessment of regulatory inspections and enforcement activities. The Appendix provides further details on inspection areas for nuclear facilities

  5. Regulatory Framework for the Maintenance of the Relevant Knowledge in the Atomic Energy Use Sector

    International Nuclear Information System (INIS)

    Sapozhnikov, A.

    2016-01-01

    Full text: In accordance with the Atomic Act of the Russian Federation the employees and workers (personnel) of nuclear industry organisations, who occupy certain positions or perform specific activities in the field of atomic energy use can start to fulfil their duties only after getting a special permit issued by the state safety regulatory authority. Rostechnadzor issues permits for the specified kinds of activities to personal of nuclear facilities, organizations engaged in transportation of nuclear and radioactive materials, and enterprises performing physical protection and account of nuclear materials and radioactive substances. To enforce the provisions of the Atomic Act Rostechnadzor has developed a regulatory system (requirements, procedures and methodology) for continued supervision over the maintenance of the required level of knowledge and adequate understanding of the nuclear safety requirements by the nuclear personnel, depending on the nature of their job duties and work in the sphere of nuclear energy use. The report presents a long-term experience of Rostechnadzor in implementing an effective regulatory system for maintaining an adequate level of knowledge and expertise of personnel of nuclear industry organisations and ensuring a competent workforce in the nuclear energy sector. (author

  6. Safety culture as a matter of regulatory control and regulatory effectiveness

    International Nuclear Information System (INIS)

    Camargo, C.T.M.; Furieri, E.B.; Arrieta, L.A.I.; Almeida, C.U.C.

    2002-01-01

    More than 15 years have passed since the term 'safety culture' was introduced by the International Nuclear Safety Advisory Group (INSAG), and although the concept now is widely accepted, practical applications and characteristics have been disseminated mainly for nuclear power plant operating organizations. There is still a lack of international guidance on the use of safety culture as a regulatory matter and on the application of the concept within regulatory organizations. This work explores the meaning of safety culture in two different fields: as an element of safety management systems it shall be a matter of regulatory control; as a complementary tool for quality management it should be used to enhance regulatory effectiveness. Brazilian recent experience on regulating nuclear power reactors provide some examples on how the concept of safety culture may influence regulatory strategies and regulatory management. (author)

  7. Regulatory guidance for license renewal

    International Nuclear Information System (INIS)

    Thoma, John A.

    1991-01-01

    The proposed 10 CFR Part 54 rule proceduralizes the process for license renewal by identifying both the administrative and technical requirements for a renewal application. To amplify and support this regulation, written guidance has been provided in the form of a draft Regulatory Guide (DG 1009) and a draft Standard Review Plan for License Renewal (NUREG 1299). This guidance is scheduled to be finalized in 1992. Similar guidance will be provided for the proposed revisions to 10 CFR Part 51 concerning the environmental aspects of license renewal. (author)

  8. Nuclear Energy Research Initiative. Risk Informed Assessment of Regulatory and Design Requirements for Future Nuclear Power Plants. Annual Report

    International Nuclear Information System (INIS)

    Ritterbusch, S.E.

    2000-01-01

    The overall goal of this research project is to support innovation in new nuclear power plant designs. This project is examining the implications, for future reactors and future safety regulation, of utilizing a new risk-informed regulatory system as a replacement for the current system. This innovation will be made possible through development of a scientific, highly risk-informed approach for the design and regulation of nuclear power plants. This approach will include the development and.lor confirmation of corresponding regulatory requirements and industry standards. The major impediment to long term competitiveness of new nuclear plants in the U.S. is the capital cost component--which may need to be reduced on the order of 35% to 40% for Advanced Light Water Reactors (ALWRs) such as System 80+ and Advanced Boiling Water Reactor (ABWR). The required cost reduction for an ALWR such as AP600 or AP1000 would be expected to be less. Such reductions in capital cost will require a fundamental reevaluation of the industry standards and regulatory bases under which nuclear plants are designed and licensed. Fortunately, there is now an increasing awareness that many of the existing regulatory requirements and industry standards are not significantly contributing to safety and reliability and, therefore, are unnecessarily adding to nuclear plant costs. Not only does this degrade the economic competitiveness of nuclear energy, it results in unnecessary costs to the American electricity consumer. While addressing these concerns, this research project will be coordinated with current efforts of industry and NRC to develop risk-informed, performance-based regulations that affect the operation of the existing nuclear plants; however, this project will go farther by focusing on the design of new plants

  9. Nuclear Energy Research Initiative. Risk Informed Assessment of Regulatory and Design Requirements for Future Nuclear Power Plants. Annual Report

    Energy Technology Data Exchange (ETDEWEB)

    Ritterbusch, S.E.

    2000-08-01

    The overall goal of this research project is to support innovation in new nuclear power plant designs. This project is examining the implications, for future reactors and future safety regulation, of utilizing a new risk-informed regulatory system as a replacement for the current system. This innovation will be made possible through development of a scientific, highly risk-informed approach for the design and regulation of nuclear power plants. This approach will include the development and.lor confirmation of corresponding regulatory requirements and industry standards. The major impediment to long term competitiveness of new nuclear plants in the U.S. is the capital cost component--which may need to be reduced on the order of 35% to 40% for Advanced Light Water Reactors (ALWRs) such as System 80+ and Advanced Boiling Water Reactor (ABWR). The required cost reduction for an ALWR such as AP600 or AP1000 would be expected to be less. Such reductions in capital cost will require a fundamental reevaluation of the industry standards and regulatory bases under which nuclear plants are designed and licensed. Fortunately, there is now an increasing awareness that many of the existing regulatory requirements and industry standards are not significantly contributing to safety and reliability and, therefore, are unnecessarily adding to nuclear plant costs. Not only does this degrade the economic competitiveness of nuclear energy, it results in unnecessary costs to the American electricity consumer. While addressing these concerns, this research project will be coordinated with current efforts of industry and NRC to develop risk-informed, performance-based regulations that affect the operation of the existing nuclear plants; however, this project will go farther by focusing on the design of new plants.

  10. Oil spill emergency response: Fulfilling regulatory requirements on the Grand Banks

    International Nuclear Information System (INIS)

    Horvath, C.L.

    1991-01-01

    Offshore well licensing under Canadian regulations requires the operator to conduct a practice exercise of oil spill countermeasures and emergency response procedures at least yearly, once the drilling program starts. The relevant parts of the Newfoundland Offshore Petroleum Drilling Regulations are summarized and the objectives and benefits of the practice exercises are reviewed. In addition to ensuring regulatory compliance, the exercises also provide the opportunity to test operational procedures, to provide in-house training, and improve response efficiency by regular repetition of the exercise. Exercises in communications during a spill incident in the offshore and in deployment of offshore spill response equipment conducted by Petro-Canada in Newfoundland are described. Problems identified during the exercises are noted

  11. Environment, safety, and health regulatory implementation plan

    International Nuclear Information System (INIS)

    1993-01-01

    To identify, document, and maintain the Uranium Mill Tailings Remedial Action (UMTRA) Project's environment, safety, and health (ES ampersand H) regulatory requirements, the US Department of Energy (DOE) UMTRA Project Office tasked the Technical Assistance Contractor (TAC) to develop a regulatory operating envelope for the UMTRA Project. The system selected for managing the UMTRA regulatory operating envelope data bass is based on the Integrated Project Control/Regulatory Compliance System (IPC/RCS) developed by WASTREN, Inc. (WASTREN, 1993). The IPC/RCS is a tool used for identifying regulatory and institutional requirements and indexing them to hardware, personnel, and program systems on a project. The IPC/RCS will be customized for the UMTRA Project surface remedial action and groundwater restoration programs. The purpose of this plan is to establish the process for implementing and maintaining the UMTRA Project's regulatory operating envelope, which involves identifying all applicable regulatory and institutional requirements and determining compliance status. The plan describes how the Project will identify ES ampersand H regulatory requirements, analyze applicability to the UMTRA Project, and evaluate UMTRA Project compliance status

  12. Novel excipients - Regulatory challenges and perspectives - The EU insight.

    Science.gov (United States)

    Kozarewicz, Piotr; Loftsson, Thorsteinn

    2018-05-21

    Novel excipients are indispensable in development of modern, advanced drug delivery systems and biotechnology-derived drugs. Although numerous novel excipients are developed for pharmaceutical use, they are not frequently seen in medicinal products due to the strict regulatory requirements and perception that their use makes new product evaluation more complex with risk of delays in the approval process. Regulators regard novel excipients as new substances and whenever new excipient is used in a formulation it must be subjected to full evaluation, similarly to the one required for new active substance. Consequently, the amount of information required in support of the regulatory approval (i.e. marketing authorization) is much more complex and comprehensive than for established excipients. This short review provides an insight into the use of novel excipients in medicinal products approved in the European Union. In addition, barriers and challenges in development of novel excipients are being discussed as well as means to overcome those barriers. Copyright © 2018 Elsevier B.V. All rights reserved.

  13. Risk literacy for scientists. Invitation to regulatory science

    International Nuclear Information System (INIS)

    Ono, Kyoko

    2012-01-01

    This paper discusses a regulatory science, which fills a gap between scientific knowledge and regulatory actions. The author provides examples of the regulatory science employed in chemical risk assessment, such as the linear non-threshold theory. In the regulatory science, scientific data as well as scientific reasoning based on scientific knowledge - or regulatory rules - should play an important role. It is important to recognize that the rules facilitate transparent decision making under conditions of uncertainty and time constraints. Furthermore, the development of traditional or pure science results in the validation of regulatory rules, and subsequently, the regulatory science procedure develops more systematically. The concept of this science should be understood by those engaged in governmental decision making. (author)

  14. Data Quality Objectives for Regulatory Requirements for Dangerous Waste Sampling and Analysis; FINAL

    International Nuclear Information System (INIS)

    MULKEY, C.H.

    1999-01-01

    This document describes sampling and analytical requirements needed to meet state and federal regulations for dangerous waste (DW). The River Protection Project (RPP) is assigned to the task of storage and interim treatment of hazardous waste. Any final treatment or disposal operations, as well as requirements under the land disposal restrictions (LDRs), fall in the jurisdiction of another Hanford organization and are not part of this scope. The requirements for this Data Quality Objective (DQO) Process were developed using the RPP Data Quality Objective Procedure (Banning 1996), which is based on the U.S. Environmental Protection Agency's (EPA) Guidance for the Data Quality Objectives Process (EPA 1994). Hereafter, this document is referred to as the DW DQO. Federal and state laws and regulations pertaining to waste contain requirements that are dependent upon the composition of the waste stream. These regulatory drivers require that pertinent information be obtained. For many requirements, documented process knowledge of a waste composition can be used instead of analytical data to characterize or designate a waste. When process knowledge alone is used to characterize a waste, it is a best management practice to validate the information with analytical measurements

  15. Regulatory activities; Actividades regulatorias

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2001-07-01

    This publication, compiled in 8 chapters, presents the regulatory system developed by the Nuclear Regulatory Authority (NRA) of the Argentine Republic. The following activities and developed topics in this document describe: the evolution of the nuclear regulatory activity in Argentina; the Argentine regulatory system; the nuclear regulatory laws and standards; the inspection and safeguards of nuclear facilities; the emergency systems; the environmental systems; the environmental monitoring; the analysis laboratories on physical and biological dosimetry, prenatal irradiation, internal irradiation, radiation measurements, detection techniques on nuclear testing, medical program on radiation protection; the institutional relations with national and international organization; the training courses and meeting; the technical information.

  16. An overview of exhaust emissions regulatory requirements and control technology for stationary natural gas engines

    International Nuclear Information System (INIS)

    Ballard, H.N.; Hay, S.C.; Shade, W.N. Jr.

    1992-01-01

    In this paper a practical overview of stationary natural gas engine exhaust emissions control technology and trends in emissions regulatory requirements is presented. Selective and non-selective catalytic reduction and lean burn technologies are compared. Particular emphasis is focussed on implications of the Clean Air Act of 1990. Recent emissions reduction conversion kit developments and a practical approach to continuous monitoring are discussed

  17. A comparison of immunotoxic effects of nanomedicinal products with regulatory immunotoxicity testing requirements

    Directory of Open Access Journals (Sweden)

    Giannakou C

    2016-06-01

    Full Text Available Christina Giannakou,1,2 Margriet VDZ Park,1 Wim H de Jong,1 Henk van Loveren,1,2 Rob J Vandebriel,1 Robert E Geertsma1 1Centre for Health Protection, National Institute for Public Health and the Environment (RIVM, Bilthoven, 2Department of Toxicogenomics, Maastricht University, Maastricht, the Netherlands Abstract: Nanomaterials (NMs are attractive for biomedical and pharmaceutical applications because of their unique physicochemical and biological properties. A major application area of NMs is drug delivery. Many nanomedicinal products (NMPs currently on the market or in clinical trials are most often based on liposomal products or polymer conjugates. NMPs can be designed to target specific tissues, eg, tumors. In virtually all cases, NMPs will eventually reach the immune system. It has been shown that most NMs end up in organs of the mononuclear phagocytic system, notably liver and spleen. Adverse immune effects, including allergy, hypersensitivity, and immunosuppression, have been reported after NMP administration. Interactions of NMPs with the immune system may therefore constitute important side effects. Currently, no regulatory documents are specifically dedicated to evaluate the immunotoxicity of NMs or NMPs. Their immunotoxicity assessment is performed based on existing guidelines for conventional substances or medicinal products. Due to the unique properties of NMPs when compared with conventional medicinal products, it is uncertain whether the currently prescribed set of tests provides sufficient information for an adequate evaluation of potential immunotoxicity of NMPs. The aim of this study was therefore, to compare the current regulatory immunotoxicity testing requirements with the accumulating knowledge on immunotoxic effects of NMPs in order to identify potential gaps in the safety assessment. This comparison showed that immunotoxic effects, such as complement activation-related pseudoallergy, myelosuppression, inflammasome

  18. 75 FR 29592 - Self-Regulatory Organizations; The NASDAQ Stock Market LLC; Notice of Filing and Immediate...

    Science.gov (United States)

    2010-05-26

    ... Corporate Governance Requirements May 19, 2010. Pursuant to Section 19(b)(1) of the Securities Exchange Act... companies to provide notification to Nasdaq of any noncompliance with the corporate governance requirements... Regulatory Authority. A Company may be denied continued listing if it fails to provide such information...

  19. 10 CFR 61.58 - Alternative requirements for waste classification and characteristics.

    Science.gov (United States)

    2010-01-01

    ... characteristics. 61.58 Section 61.58 Energy NUCLEAR REGULATORY COMMISSION (CONTINUED) LICENSING REQUIREMENTS FOR... Alternative requirements for waste classification and characteristics. The Commission may, upon request or on its own initiative, authorize other provisions for the classification and characteristics of waste on...

  20. 77 FR 8082 - Regulatory Flexibility Agenda

    Science.gov (United States)

    2012-02-13

    ... Required: Yes. Agency Contact: Alicia Goldin, Division of Trading and Markets, Securities and Exchange.../01/11 Regulatory Flexibility Analysis Required: Yes. Agency Contact: Alicia Goldin, Division of... Withdrawn 10/01/11 Regulatory Flexibility Analysis Required: Yes. Agency Contact: Alicia Goldin, Division of...

  1. Safety requirements expected to the prototype fast breeder reactor 'Monju'

    International Nuclear Information System (INIS)

    2014-11-01

    In July 2013, Nuclear Regulation Authority (NRA) has enforced new regulatory requirements in consideration of severe accidents for the commercial light water reactors (LWR) and also prototype power generation reactors such as the sodium-cooled fast reactors (SFR) of 'Monju' based on TEPCO Fukushima Daiichi nuclear power plant accident (hereinafter referred to as '1F accident') occurred in March 2011. Although the regulatory requirements for SFR will be revised by NRA with consideration for public comments, Japan Atomic Energy Agency (JAEA) set up 'Advisory Committee on Monju Safety Requirements' consisting of fast breeder reactor (FBR) and safety assessment experts in order to establish original safety requirements expected to the prototype FBR 'Monju' considering severe accidents with knowledge from JAEA as well as scientific and technical insights from the experts. This report summarizes the safety requirements expected to Monju discussed by the committee. (author)

  2. Regulatory guidance document

    International Nuclear Information System (INIS)

    1994-05-01

    The Office of Civilian Radioactive Waste Management (OCRWM) Program Management System Manual requires preparation of the OCRWM Regulatory Guidance Document (RGD) that addresses licensing, environmental compliance, and safety and health compliance. The document provides: regulatory compliance policy; guidance to OCRWM organizational elements to ensure a consistent approach when complying with regulatory requirements; strategies to achieve policy objectives; organizational responsibilities for regulatory compliance; guidance with regard to Program compliance oversight; and guidance on the contents of a project-level Regulatory Compliance Plan. The scope of the RGD includes site suitability evaluation, licensing, environmental compliance, and safety and health compliance, in accordance with the direction provided by Section 4.6.3 of the PMS Manual. Site suitability evaluation and regulatory compliance during site characterization are significant activities, particularly with regard to the YW MSA. OCRWM's evaluation of whether the Yucca Mountain site is suitable for repository development must precede its submittal of a license application to the Nuclear Regulatory Commission (NRC). Accordingly, site suitability evaluation is discussed in Chapter 4, and the general statements of policy regarding site suitability evaluation are discussed in Section 2.1. Although much of the data and analyses may initially be similar, the licensing process is discussed separately in Chapter 5. Environmental compliance is discussed in Chapter 6. Safety and Health compliance is discussed in Chapter 7

  3. Regulatory control of radiation sources in Slovakia

    International Nuclear Information System (INIS)

    Auxtova, L.

    2001-01-01

    In Slovakia, there are two regulatory authorities. Regulatory control of the utilization of nuclear energy, based on the Slovak National Council's law No. 130/1998 on the peaceful uses of nuclear energy, is exercised by the Nuclear Regulatory Authority of the Slovak Republic. The second regulatory authority - the Ministry of Health - is empowered by law No. 72/1994 on the protection of human health to license radiation sources and is responsible for radiation protection supervision (there are nearly 3000 establishments with sealed sources, radiation generators and unsealed sources in Slovakia). Pursuant to a new radiation protection regulation based on international standards, radiation sources are to be categorized in six classes according to the associated exposure and contamination hazards. A national strategy for improving the safety of radiation sources over their life-cycle and for the management of disused and orphan sources is being prepared for governmental approval. (author)

  4. Research and regulatory review

    International Nuclear Information System (INIS)

    Macleod, J.S.; Fryer, D.R.H.

    1979-01-01

    To enable the regulatory review to be effectively undertaken by the regulatory body, there is a need for it to have ready access to information generated by research activities. Certain advantages have been seen to be gained by the regulatory body itself directly allocating and controlling some portion of these activities. The princial reasons for reaching this conclusion are summarised and a brief description of the Inspectorates directly sponsored programme outlined. (author)

  5. Exemption from Regulatory Control of Goods Containing Small Amounts of Radioactive Material

    International Nuclear Information System (INIS)

    2012-01-01

    Small amounts of radioactive material may be added to various goods for functional reasons. Several such items are currently available for either professional or personal use. These include ionization chamber smoke detectors, thoriated-tungsten welding rods, luminous dials, electrical devices and electric discharge lamps. Some of these goods may be intended for particular types of market such as cinemas or other places to which the public may have access, but they are unlikely to be provided directly to members of the public. Other goods may be intended for wide scale use and therefore readily available on the market as consumer products through commercial outlets where personal and household products are normally purchased. Members of the public may be exposed to ionizing radiation as a consequence of activities such as transport, storage, use and disposal of such goods. The IAEA safety standards provide the basic requirements for regulatory control of such goods. The most relevant documents are the Governmental, Legal and Regulatory Framework for Safety and the International Basic Safety Standards (hereafter referred to as the BSS). These requirements include notification of a practice to the regulatory body and authorization of the practice by the regulatory body. Provision is made for the exemption of practices from these and other regulatory requirements based on general criteria given in the BSS or any exemption levels specified by the regulatory body on the basis of these criteria. The BSS, which are jointly sponsored by the IAEA and several other international organizations, apply to all facilities and all activities for peaceful purposes that give rise to exposure to radiation. In the interest of harmonization of approaches among Member States, some guidance on the application of the criteria for exemption has been provided in a number of Safety Guides, e.g. Regulatory Control of Radiation Sources, IAEA Safety Standards Series No. GS-G-1.5 (2004) and the

  6. 30 CFR 764.21 - Data base and inventory system requirements.

    Science.gov (United States)

    2010-07-01

    ... 30 Mineral Resources 3 2010-07-01 2010-07-01 false Data base and inventory system requirements... SURFACE COAL MINING OPERATIONS § 764.21 Data base and inventory system requirements. (a) The regulatory authority shall develop a data base and inventory system which will permit evaluation of whether reclamation...

  7. 77 FR 7960 - Unified Agenda of Federal Regulatory and Deregulatory Actions

    Science.gov (United States)

    2012-02-13

    ... Sequence No. Title Identifier No. 377 Claims Procedures Under 1625-AA03 the Oil Pollution Act of 1990 (USCG... Regulatory Flexibility Analysis Required: Yes. Agency Contact: Jeremy F. Olson, Senior Procurement Analyst... Procedures Under the Oil Pollution Act of 1990 (USCG-2004- 17697) Legal Authority: 33 U.S.C. 2713 and 2714...

  8. Overlapping positive and negative regulatory domains of the human β-interferon gene

    International Nuclear Information System (INIS)

    Goodbourn, S.; Maniatis, T.

    1988-01-01

    Virus of poly(I) x poly(C) induction of human β-interferon gene expression requires a 40-base-pair DNA sequence designated the interferon gene regulatory element (IRE). Previous studies have shown that the IRE contains both positive and negative regulatory DNA sequences. To localize these sequences and study their interactions, the authors have examined the effects of a large number of single-base mutations within the IRE on β-interferon gene regulation. They find that the IRE consists of two genetically separable positive regulatory domains and an overlapping negative control sequence. They propose that the β-interferon gene is switched off in uninduced cells by a repressor that blocks the interaction between one of the two positive regulatory sequences and a specific transcription factor. Induction would then lead to inactivation or displacement of the repressor and binding of transcription factors to both positive regulatory domains

  9. The dynein regulatory complex is required for ciliary motility and otolith biogenesis in the inner ear.

    Science.gov (United States)

    Colantonio, Jessica R; Vermot, Julien; Wu, David; Langenbacher, Adam D; Fraser, Scott; Chen, Jau-Nian; Hill, Kent L

    2009-01-08

    In teleosts, proper balance and hearing depend on mechanical sensors in the inner ear. These sensors include actin-based microvilli and microtubule-based cilia that extend from the surface of sensory hair cells and attach to biomineralized 'ear stones' (or otoliths). Otolith number, size and placement are under strict developmental control, but the mechanisms that ensure otolith assembly atop specific cells of the sensory epithelium are unclear. Here we demonstrate that cilia motility is required for normal otolith assembly and localization. Using in vivo video microscopy, we show that motile tether cilia at opposite poles of the otic vesicle create fluid vortices that attract otolith precursor particles, thereby biasing an otherwise random distribution to direct localized otolith seeding on tether cilia. Independent knockdown of subunits for the dynein regulatory complex and outer-arm dynein disrupt cilia motility, leading to defective otolith biogenesis. These results demonstrate a requirement for the dynein regulatory complex in vertebrates and show that cilia-driven flow is a key epigenetic factor in controlling otolith biomineralization.

  10. 18 CFR 284.504 - Standard requirements for market-power authorizations.

    Science.gov (United States)

    2010-04-01

    ... Commission within 10 days of acquiring knowledge of significant changes occurring in its market power status... 18 Conservation of Power and Water Resources 1 2010-04-01 2010-04-01 false Standard requirements for market-power authorizations. 284.504 Section 284.504 Conservation of Power and Water Resources...

  11. 30 CFR 817.81 - Coal mine waste: General requirements.

    Science.gov (United States)

    2010-07-01

    ... 30 Mineral Resources 3 2010-07-01 2010-07-01 false Coal mine waste: General requirements. 817.81... ACTIVITIES § 817.81 Coal mine waste: General requirements. (a) General. All coal mine waste disposed of in an... within a permit area, which are approved by the regulatory authority for this purpose. Coal mine waste...

  12. 30 CFR 816.81 - Coal mine waste: General requirements.

    Science.gov (United States)

    2010-07-01

    ... 30 Mineral Resources 3 2010-07-01 2010-07-01 false Coal mine waste: General requirements. 816.81... ACTIVITIES § 816.81 Coal mine waste: General requirements. (a) General. All coal mine waste disposed of in an... within a permit area, which are approved by the regulatory authority for this purpose. Coal mine waste...

  13. For optimum safety technologies: understanding relations between the different national authorities and the technical support organizations

    International Nuclear Information System (INIS)

    Mahmoud, N.S.; Mostafa Aziz, Mostafa

    2010-01-01

    TSOs describe expert independent organizations, which provide supports for government, regulatory authorities, utilities and industry. The TSO must dispose different competences and objectives in order to deliver to the four independent authorities the technical and scientific knowledge. This comprehensive knowledge, from TSO, should perform through the research and development activities (R and D). Concerning the government, TSOs consider the R and D on the management procedures to characterize the links, to differentiate roles to prevent the overlapping efforts, and finally to build a central data bank in nuclear technologies for the other three authorities. For regulatory organizations, R and D are involved in the regulatory requirements and surveillance processes. On the other side R and D, in case of utilities, activities should focus on the improvement of safety operations for nuclear power and its new generations, and for other nuclear/radiological facilities. Finally, the forth TSOs has R and D targets that should concentrate mainly on material, efficiency, and durability of different equipment and parts involved in the nuclear activities during manufacturing. (author)

  14. Introduction to the Unified Agenda of Federal Regulatory and Deregulatory Actions

    Science.gov (United States)

    2010-04-26

    ... Regulatory Commission Federal Housing Finance Agency Federal Maritime Commission Federal Mediation and... that the Regulatory Flexibility Act may require a Regulatory Flexibility Analysis, actions selected for.... Regulatory Flexibility Analysis Required -- whether an analysis is required by the Regulatory Flexibility Act...

  15. A flexible regulatory framework

    International Nuclear Information System (INIS)

    Silvennoinen, T.

    2000-01-01

    Regulatory reform of the Finnish electricity market meant opening up potentially competitive parts of the electricity sector to competition and eliminating all unnecessary forms of regulation covering generation, wholesale supply, retail supply, and foreign trade in electricity. New types of control and regulatory mechanisms and institutions were set up for those parts of the electricity industry that were excluded from competition, such as network operations. Network activities now have to be licensed, whereas no licence is needed for generation or supply. A new sector-specific regulatory authority was established in 1995 to coincide with the implementation of the Electricity Market Act, known as the Electricity Market Authority. This is responsible for regulating network activities and retail supply to captive customers. The core function of the authority, which employs some 14 people, is to promote the smooth operation of the Finnish electricity market and to oversee the implementation of the Electricity Market Act and its provisions. Its most important duties are linked to overseeing the process by which network companies price their electricity. As price regulation no longer exists, all the companies in the electricity sector set their tariffs independently, even network companies. The job of controlling the pricing of network services is handed by the Electricity Market Authority, following the principles of competition control. Pricing control takes place ex post - after a pricing system has been adopted by a company and concentrates on individual cases and companies. There is no ex ante system of setting or approving prices and tariffs by the regulator. The tariffs and pricing of network services can be evaluated, however, by both the Electricity Market Authority and the Finnish Competition Authority, which have overlapping powers as regards the pricing of network activities. The Finnish regulatory framework can be described as a system of light

  16. Current Status of Regulatory Science Education in Faculties of Pharmaceutical Science in Japan.

    Science.gov (United States)

    Tohkin, Masahiro

    2017-01-01

    I introduce the current pharmaceutical education system in Japan, focusing on regulatory science. University schools or faculties of pharmaceutical science in Japan offer two courses: a six-year course for pharmacists and a four-year course for scientists and technicians. Students in the six-year pharmaceutical course receive training in hospitals and pharmacies during their fifth year, and those in the four-year life science course start research activities during their third year. The current model core curriculum for pharmaceutical education requires them to "explain the necessity and significance of regulatory science" as a specific behavior object. This means that pharmacists should understand the significance of "regulatory science", which will lead to the proper use of pharmaceuticals in clinical practice. Most regulatory science laboratories are in the university schools or faculties of pharmaceutical sciences; however, there are too few to conduct regulatory science education. There are many problems in regulatory science education, and I hope that those problems will be resolved not only by university-based regulatory science researchers but also by those from the pharmaceutical industry and regulatory authorities.

  17. 76 FR 57057 - International Cooperation on Harmonisation of Technical Requirements for Registration of...

    Science.gov (United States)

    2011-09-15

    ...] International Cooperation on Harmonisation of Technical Requirements for Registration of Veterinary Medicinal... veterinary use by the International Cooperation on Harmonisation of Technical Requirements for Registration... undertaken by regulatory authorities and industry associations to promote the international harmonization of...

  18. A regulatory adjustment process for the determination of the optimal percentage requirement in an electricity market with Tradable Green Certificates

    International Nuclear Information System (INIS)

    Currier, Kevin M.

    2013-01-01

    A system of Tradable Green Certificates (TGCs) is a market-based subsidy scheme designed to promote electricity generation from renewable energy sources such as wind power. Under a TGC system, the principal policy instrument is the “percentage requirement,” which stipulates the percentage of total electricity production (“green” plus “black”) that must be obtained from renewable sources. In this paper, we propose a regulatory adjustment process that a regulator can employ to determine the socially optimal percentage requirement, explicitly accounting for environmental damages resulting from black electricity generation. - Highlights: • A Tradable Green Certificate (TGC) system promotes energy production from renewable sources. • We consider an electricity oligopoly operated under a TGC system. • Welfare analysis must account for damages from “black” electricity production. • We characterize the welfare maximizing (optimal) “percentage requirement.” • We present a regulatory adjustment process that computes the optimal percentage requirement iteratively

  19. Regulatory approach of the monitoring the effectiveness of maintenance at nuclear power plants program

    International Nuclear Information System (INIS)

    Vajgel, Stefan

    2009-03-01

    The electrical power generation using nuclear power plants requires this installation being safety, reliable and available for the working periods. For this purpose, an adequate, effective and well conducted maintenance program makes an essential and useful tool to the owner of the plant. However, it is necessary to follow the regulatory requirements for this program implementation which monitories this maintenance effectiveness. There are Brazilian norms requirements which must be followed. The international regulatory guides establish these requirements in good details but it is necessary to verify if this methodology for implementing can be totally applied here in Brazil. Then, the american guide NUMARC 93-01 which details how can be implemented a program for this monitoring, shows some methods for using. In this thesis, the Delphi and Probabilistic Safety Analysis were briefly included because they were preferred for implementing this monitoring.in a Brazilian plant. The results which are being obtained show that, looking the regulatory aspects, the NUMARC 93-01 follows our regulations and gives good results for the plant management. (author)

  20. UK regulatory standards - the 'Guidance on requirements for authorisation'

    International Nuclear Information System (INIS)

    Williams, C.R.

    1999-01-01

    In the United Kingdom, disposal of radioactive waste requires an authorisation under the Radioactive Substances Act 1993. The power to grant such authorisations rests with the Environment Agency for disposals in England and Wales, and with similar Agencies in Scotland and Northern Ireland - namely the Scottish Environment Protection Agency (SEPA) and the Environment and Heritage Service (EHS) of the Department of the Environment for Northern Ireland. In 1997, following two rounds of consultation, the Environment Agency jointly with SEPA and EHS published a document 'Disposal Facilities on Land for Low and Intermediate Level Radioactive Wastes: Guidance on Requirements for Authorisation' - the GRA document. The GRA document outlines the regulatory framework governing the disposal of radioactive waste, general guidance on procedures, the principles and criteria against which proposals for a disposal facility will be assessed, and the radiological and technical requirements which a facility will be expected to meet. In particular, the document states that, in the period after control is withdrawn, the assessed radiological risk from a facility to a representative member of the potentially exposed group at greatest risk should be consistent with a risk target of 10 -6 per year. The document also specifies the information which a developer will need to provide, to demonstrate that a proposal is consistent with the principles and requirements, and identifies other, non-risk-based, criteria. In March 1997, the Secretary of State for the Environment rejected a planning appeal by United Kingdom Nirex Ltd for an underground Rock Characterisation Facility located near Sellafield in Cumbria. That decision has effectively delayed the construction of any deep repository in the UK. Subsequently a House of Lords Select Committee has commenced a major review of nuclear waste management. The Environment Agency continues to be responsible for the authorisation of the shallow

  1. Requirements for growth and IL-10 expression of highly purified human T regulatory cells

    OpenAIRE

    Bonacci, Benedetta; Edwards, Brandon; Jia, Shuang; Williams, Calvin; Hessner, Martin J.; Gauld, Stephen; Verbsky, James

    2012-01-01

    Human regulatory T cells (TR) cells have potential for the treatment of a variety of immune mediated diseases but the anergic phenotype of these cells makes them difficult to expand in vitro. We have examined the requirements for growth and cytokine expression from highly purified human TR cells, and correlated these findings with the signal transduction events of these cells. We demonstrate that these cells do not proliferate or secrete IL-10 even in the presence of high doses of IL-2. Stimu...

  2. The regulatory control of radioactive sources in Argentina

    International Nuclear Information System (INIS)

    Rojkind, R.H.

    1998-01-01

    Argentina has been conducting nuclear activities for more than forty years, and had established a Regulatory Authority as early as in 1956. Procedures for compliance monitoring and enforcement have been in use in the regulatory control of radioactive sources, and regulatory standards and regulations were in force in Argentina before the accident in Goiania. The conclusions drawn from the Goiania accident encouraged the Argentine authorities to improve some regulatory procedures and helped to enhance the quality of the regulatory process. As a result, the effectiveness of the control of spent radioactive sources has gradually increased, and enforcement actions to prevent radioactive sources ending up in the public domain have improved. Lessons learned in Argentina from the accident in Goiania are presented as well as the main characteristics of an effective enforcement programme to prevent radiological accidents when radioactive sources are used for industrial, medical, research and teaching purposes. (author)

  3. 40 CFR 73.86 - State regulatory autonomy.

    Science.gov (United States)

    2010-07-01

    ... 40 Protection of Environment 16 2010-07-01 2010-07-01 false State regulatory autonomy. 73.86 Section 73.86 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) AIR PROGRAMS... regulatory autonomy. Nothing in this subpart shall preclude a State or State regulatory authority from...

  4. Design requirements for new nuclear reactor facilities in Canada

    International Nuclear Information System (INIS)

    Shim, S.; Ohn, M.; Harwood, C.

    2012-01-01

    The Canadian Nuclear Safety Commission (CNSC) has been establishing the regulatory framework for the efficient and effective licensing of new nuclear reactor facilities. This regulatory framework includes the documentation of the requirements for the design and safety analysis of new nuclear reactor facilities, regardless of size. For this purpose, the CNSC has published the design and safety analysis requirements in the following two sets of regulatory documents: 1. RD-337, Design of New Nuclear Power Plants and RD-310, Safety Analysis for Nuclear Power Plants; and 2. RD-367, Design of Small Reactor Facilities and RD-308, Deterministic Safety Analysis for Small Reactor Facilities. These regulatory documents have been modernized to document past practices and experience and to be consistent with national and international standards. These regulatory documents provide the requirements for the design and safety analysis at a high level presented in a hierarchical structure. These documents were developed in a technology neutral approach so that they can be applicable for a wide variety of water cooled reactor facilities. This paper highlights two particular aspects of these regulatory documents: The use of a graded approach to make the documents applicable for a wide variety of nuclear reactor facilities including nuclear power plants (NPPs) and small reactor facilities; and, Design requirements that are new and different from past Canadian practices. Finally, this paper presents some of the proposed changes in RD-337 to implement specific details of the recommendations of the CNSC Fukushima Task Force Report. Major changes were not needed as the 2008 version of RD-337 already contained requirements to address most of the lessons learned from the Fukushima event of March 2011. (author)

  5. Regulatory context and evolutions - Public Health Code

    International Nuclear Information System (INIS)

    Rodde, S.

    2009-01-01

    After having recalled that numerous laws, decrees and orders have been published between 2001 and 2007 due to the transposition of EURATOM directives defining standards for population and worker health protection against dangers resulting from ionizing radiations, the author reviews the regulatory evolutions which occurred in 2008 and 2009, and those currently in progress. They concern the protection of people exposed to radon, the field of radiotherapy, authorizations issued in application of the French public health code. Some decisions are about to be finalized. They concern the activities submitted to a declaration, the modalities of prolongation of the lifetime of sealed sources, a list of apparatus categories the handling of which requires an ability certificate

  6. The regulatory framework for safe decommissioning of nuclear power plants in Korea

    International Nuclear Information System (INIS)

    Sangmyeon Ahn; Jungjoon Lee; Chanwoo Jeong; Kyungwoo Choi

    2013-01-01

    We are having 23 units of nuclear power plants in operation and 5 units of nuclear power plants under construction in Korea as of September 2012. However, we don't have any experience on shutdown permanently and decommissioning of nuclear power plants. There are only two research reactors being decommissioned since 1997. It is realized that improvement of the regulatory framework for decommissioning of nuclear facilities has been emphasized constantly from the point of view of IAEA's safety standards. It is also known that IAEA will prepare the safety requirement on decommissioning of facilities; its title is the Safe Decommissioning of Facilities, General Safety Requirement Part 6. According to the result of IAEA's Integrated Regulatory Review Service (IRRS) mission to Korea in 2011, it was recommended that the regulatory framework should require decommissioning plans for nuclear installations to be constructed and operated and these plans should be updated periodically. In addition, after the Fukushima nuclear disaster in Japan in March of 2011, preparedness for early decommissioning caused by an unexpected severe accident became important issues and concerns. In this respect, it is acknowledged that the regulatory framework for decommissioning of nuclear facilities in Korea need to be improved. First of all, we focus on identifying the current status and relevant issues of regulatory framework for decommissioning of nuclear power plants compared to the IAEA's safety standards in order to achieve our goal. And then the plan is established for improvement of regulatory framework for decommissioning of nuclear power plants in Korea. It is expected that if the things will go forward as planned, the revised regulatory framework for decommissioning could enhance the safety regime on the decommissioning of nuclear power plants in Korea in light of international standards. (authors)

  7. [Regulatory requirements regarding cell-based medicinal products for human and veterinary use - a comparison].

    Science.gov (United States)

    Kuhlmann-Gottke, Johanna; Duchow, Karin

    2015-11-01

    At present, there is no separate regulatory framework for cell-based medicinal products (CBMP) for veterinary use at the European or German level. Current European and national regulations exclusively apply to the corresponding medicinal products for human use. An increasing number of requests for the regulatory classification of CBMP for veterinary use, such as allogeneic stem cell preparations and dendritic cell-based autologous tumour vaccines, and a rise in scientific advice for companies developing these products, illustrate the need for adequate legislation. Currently, advice is given and decisions are made on a case-by-case basis regarding the regulatory classification and authorisation requirements.Since some of the CBMP - in particular in the area of stem-cell products - are developed in parallel for human and veterinary use, there is an urgent need to create specific legal definitions, regulations, and guidelines for these complex innovative products in the veterinary sector as well. Otherwise, there is a risk that that the current legal grey area regarding veterinary medicinal products will impede therapeutic innovations in the long run. A harmonised EU-wide approach is desirable. Currently the European legislation on veterinary medicinal products is under revision. In this context, veterinary therapeutics based on allogeneic cells and tissues will be defined and regulated. Certainly, the legal framework does not have to be as comprehensive as for human CBMP; a leaner solution is conceivable, similar to the special provisions for advanced-therapy medicinal products laid down in the German Medicines Act.

  8. The regulatory process for uranium mines in Canada -general overview and radiation health and safety in uranium mine-mill facilities

    International Nuclear Information System (INIS)

    Dory, A.B.

    1982-01-01

    This presentation is divided into two main sections. In the first, the author explores the issues of radiation and tailings disposal, and then examines the Canadian nuclear regulatory process from the point of view of jurisdiction, objectives, philosophy and mechanics. The compliance inspection program is outlined, and the author discussed the relationships between the AECB and other regulatory agencies, the public and uranium mine-mill workers. The section concludes with an examination of the stance of the medical profession on nuclear issues. In part two, the radiological hazards for uranium miners are examined: radon daughters, gamma radiation, thoron daughters and uranium dust. The author touches on new regulations being drafted, the assessment of past exposures in mine atmospheres, and the regulatory approach at the surface exploration stage. The presentation concludes with the author's brief observations on the findings of other uranium mining inquiries and on future requirements in the industry's interests

  9. Regulatory analysis technical evaluation handbook. Final report

    International Nuclear Information System (INIS)

    1997-01-01

    The purpose of this Handbook is to provide guidance to the regulatory analyst to promote preparation of quality regulatory analysis documents and to implement the policies of the Regulatory Analysis Guidelines of the US Nuclear Regulatory Commission (NUREG/BR-0058 Rev. 2). This Handbook expands upon policy concepts included in the NRC Guidelines and translates the six steps in preparing regulatory analyses into implementable methodologies for the analyst. It provides standardized methods of preparation and presentation of regulatory analyses, with the inclusion of input that will satisfy all backfit requirements and requirements of NRC's Committee to Review Generic Requirements. Information on the objectives of the safety goal evaluation process and potential data sources for preparing a safety goal evaluation is also included. Consistent application of the methods provided here will result in more directly comparable analyses, thus aiding decision-makers in evaluating and comparing various regulatory actions. The handbook is being issued in loose-leaf format to facilitate revisions. NRC intends to periodically revise the handbook as new and improved guidance, data, and methods become available

  10. Characterization of the evolution of the pharmaceutical regulatory environment.

    Science.gov (United States)

    Shafiei, Nader; Ford, James L; Morecroft, Charles W; Lisboa, Paulo J; Taylor, Mark J

    2013-01-01

    This paper is part of a research study that is intended to identify pharmaceutical quality risks induced by the ongoing transformation in the industry. This study establishes the current regulatory context by characterizing the development of the pharmaceutical regulatory environment. The regulatory environment is one of the most important external factors that affects a company's organization, processes, and technological strategy. This is especially the case with the pharmaceutical industry, where its products affect the quality of life of the consumers. The quantitative analysis of regulatory events since 1813 and review of the associated literature resulted in identification of six factors influencing the regulatory environment, namely public health protection, public health promotion, crisis management, harmonization, innovation, and modernization. From 1813 to the 1970s the focus of regulators was centered on crisis management and public health protection-a basic mission that has remained consistent over the years. Since the 1980s a gradual move in the regulatory environment towards a greater focus on public health promotion, international harmonization, innovation, and agency modernization may be seen. The pharmaceutical industry is currently going through changes that affect the way it performs its research, manufacturing, and regulatory activities. The impact of these changes on the approaches to quality risk management requires more understanding. The authors are engaged in research to identify elements of the changes that influence pharmaceutical quality. As quality requirements are an integral part of the pharmaceutical regulations, a comprehensive understanding of these regulations is seen as the first step. The results of this study show that (i) public health protection, public health promotion, crisis management, harmonization, innovation, and modernization are factors that affect regulations in the pharmaceutical industry; (ii) the regulators' main

  11. Regulatory System of Radiation Protection in Taiwan

    International Nuclear Information System (INIS)

    Tang, F. T.; Huang, C. C.

    2004-01-01

    radiation sources until the discard of the radiation sources such that the competent authority can efficiently control. In order to control the moving status of high-activity sources, the AEC requires the owners of high-activity sources shall report the conditions of variation to the competent authority through Internet every month. According to the IRP Law the records of penalties shall also enter this system for statistical analysis so as to be used for regulatory reference. (Author)

  12. Health claims on food products in Southeast Asia: regulatory frameworks, barriers, and opportunities.

    Science.gov (United States)

    Tan, Karin Y M; van der Beek, Eline M; Chan, M Y; Zhao, Xuejun; Stevenson, Leo

    2015-09-01

    The Association of Southeast Asian Nations aims to act as a single market and allow free movement of goods, services, and manpower. The purpose of this article is to present an overview of the current regulatory framework for health claims in Southeast Asia and to highlight the current barriers and opportunities in the regulatory frameworks in the Association of Southeast Asian Nations. To date, 5 countries in Southeast Asia, i.e., Indonesia, Malaysia, the Philippines, Singapore, and Thailand, have regulations and guidelines to permit the use of health claims on food products. There are inconsistencies in the regulations and the types of evidence required for health claim applications in these countries. A clear understanding of the regulatory frameworks in these countries may help to increase trade in this fast-growing region and to provide direction for the food industry and the regulatory community to develop and market food products with better nutritional quality tailored to the needs of Southeast Asian consumers. © The Author(s) 2015. Published by Oxford University Press on behalf of the International Life Sciences Institute. All rights reserved. For Permissions, please e-mail: journals.permissions@oup.com.

  13. Regulatory body core competencies: when should a regulator contract a TSO?

    International Nuclear Information System (INIS)

    Wieland, Patricia; Salati de Almeida, Ivan P.; Almeida, Claudio U.; Costa, Eduardo M.

    2008-01-01

    The main nuclear regulatory functions are authorization, safety review and assessment, inspection and enforcement and development of regulations and guides. Additionally, the following supplementary functions may be executed by the regulatory body: research and development, emergency response and international cooperation. In order to function properly, the regulatory body should also have the following support functions: general management, logistics, training, communication and information, information technology support, institutional relationship, internal controls and audits, ombudsman and legal support. Technical Support Organizations (TSOs) may assist the regulatory body in meeting the challenges in a rapid growing and changing environment. Specially when there is a temporary need for a wider technical expertise diversity, short time to finish a project or when the cost of developing and maintaining infrastructure of their own laboratories for analysis and research is too high and may deviate the focus on the regulator's mission. Decision on the 'size' of the regulatory body and on what can be contracted to a Technical Support Organization (TSO) depends on the resources and capabilities needed to fulfil the regulatory functions efficiently. It is important to establish the core competencies that must be at the regulatory body, keeping the focus on the regulatory goals and define the real need to contract a TSO, weighting the benefits and disadvantages. As a contribution to the definition of the regulatory core competencies, the paper discusses what is essential to be kept at the regulatory body and what can be delegated to a TSO; how to manage and control the work of the TSO; the cost effectiveness of contracting, sharing of tacit knowledge; how to handle eventual conflicts between the parties involved in the licensing process; contract types and risk evaluation, concerning the dependence on a TSO, eventual change of partners and the intellectual capital

  14. Evaluation of the applicability of existing nuclear power plant regulatory requirements in the U.S. to advanced small modular reactors.

    Energy Technology Data Exchange (ETDEWEB)

    LaChance, Jeffrey L.; Wheeler, Timothy A.; Farnum, Cathy Ottinger; Middleton, Bobby D.; Jordan, Sabina Erteza; Duran, Felicia Angelica; Baum, Gregory A.

    2013-05-01

    The current wave of small modular reactor (SMR) designs all have the goal of reducing the cost of management and operations. By optimizing the system, the goal is to make these power plants safer, cheaper to operate and maintain, and more secure. In particular, the reduction in plant staffing can result in significant cost savings. The introduction of advanced reactor designs and increased use of advanced automation technologies in existing nuclear power plants will likely change the roles, responsibilities, composition, and size of the crews required to control plant operations. Similarly, certain security staffing requirements for traditional operational nuclear power plants may not be appropriate or necessary for SMRs due to the simpler, safer and more automated design characteristics of SMRs. As a first step in a process to identify where regulatory requirements may be met with reduced staffing and therefore lower cost, this report identifies the regulatory requirements and associated guidance utilized in the licensing of existing reactors. The potential applicability of these regulations to advanced SMR designs is identified taking into account the unique features of these types of reactors.

  15. 47 CFR 1.1151 - Authority to prescribe and collect regulatory fees.

    Science.gov (United States)

    2010-10-01

    ... regulatory activities in the private radio, mass media, common carrier, and cable television services. [59 FR... fees. 1.1151 Section 1.1151 Telecommunication FEDERAL COMMUNICATIONS COMMISSION GENERAL PRACTICE AND... section 9 of the Communications Act, 47 U.S.C. 159, which directs the Commission to prescribe and collect...

  16. Organization of nuclear regulatory activities

    International Nuclear Information System (INIS)

    Blidaru, Valentin

    2008-01-01

    The paper presents the structure, missions and organizational aspects of the CNCAN, the National Commission for the control of nuclear activities in Romania. The paper addresses the following main issues: 1.General aspects; 2.Organizational structure of the NRA in Romania; 3.General description of the Division for Nuclear Safety Assessments; 4.Specific activities; 5.Regulatory approaches and practices. Under the title of 'General aspects' the following three basic statements are highlighted: 1.CNCAN is a governmental organization responsible for the development of the regulatory framework, the control of its implementation and the licensing of nuclear facilities; 2.CNCAN is the national authority competent in exercising the regulatory activity, authorization and control in the nuclear field provided by the law No. 111/ 1996 republished in 1998; 3.The Commission exercises its functions independently of the ministries and other authorities of the public control administration being subordinated to the Romanian Government. The organizational structure is as follows: - President, the Managerial Council and the Advisory Council coordinating the four General Divisions that are responsible for: - Nuclear Safety with Division of Nuclear Safety Assessment and Division of Nuclear Objectives Surveillance; - Radiological Safety with Division of Radiological Safety Assessment and Division of Operational Radiation Protection; - Surveillance of Environmental Radioactivity with Division of Assessment and Analysis and Division of National Network; - Development and Resource with the Division of Economy and Division of Human Resources. In addition under direct coordination of the President operate the Division of Radiation Protection, Transport and Radioactive Waste and the Division of International Cooperation and Communication. Specific activities are listed describing among others the issues of: - Safety of nuclear installation; - Evaluation relating to licensing of nuclear

  17. Organisational culture at the Radiation and Nuclear Safety Authority of Finland's department of Nuclear Reactor Regulation

    International Nuclear Information System (INIS)

    Reiman, T.; Norros, L.

    2001-03-01

    A case study to investigate the organisational culture of the regulatory authority was conducted at the Radiation and Nuclear Safety Authority of Finland's (STUK) Nuclear Reactor Regulation (YTO) - department. Organisational culture is defined as a pattern of shared basic assumptions, which are basically unconscious. Objectives of the study were to conceptualise and describe the main characteristics of YTO's organisational culture and to carry out a tentative core task analysis of the inspectors' work. A combination of quantitative and qualitative methods was used in the research. YTO's culture was identified as a hierarchy-focused culture with less emphasis on innovation or social support. However, the ideal values of the personnel emphasised also social support and goal setting. Ambiguous goals were felt by some personnel as increased uncertainty about the meaningfulness of one's job. Also a lack of feedback was mentioned. The core task analysis identified the critical functions of the regulatory practice. These functions specify the three roles of the regulatory authority, the expert role, the public role and the authority role. The culture must support the fulfilment of the requirements of all the three roles. Development needs in YTO's culture were identified and recommendations were made. (au)

  18. A study of diverse clinical decision support rule authoring environments and requirements for integration

    Directory of Open Access Journals (Sweden)

    Zhou Li

    2012-11-01

    Full Text Available Abstract Background Efficient rule authoring tools are critical to allow clinical Knowledge Engineers (KEs, Software Engineers (SEs, and Subject Matter Experts (SMEs to convert medical knowledge into machine executable clinical decision support rules. The goal of this analysis was to identify the critical success factors and challenges of a fully functioning Rule Authoring Environment (RAE in order to define requirements for a scalable, comprehensive tool to manage enterprise level rules. Methods The authors evaluated RAEs in active use across Partners Healthcare, including enterprise wide, ambulatory only, and system specific tools, with a focus on rule editors for reminder and medication rules. We conducted meetings with users of these RAEs to discuss their general experience and perceived advantages and limitations of these tools. Results While the overall rule authoring process is similar across the 10 separate RAEs, the system capabilities and architecture vary widely. Most current RAEs limit the ability of the clinical decision support (CDS interventions to be standardized, sharable, interoperable, and extensible. No existing system meets all requirements defined by knowledge management users. Conclusions A successful, scalable, integrated rule authoring environment will need to support a number of key requirements and functions in the areas of knowledge representation, metadata, terminology, authoring collaboration, user interface, integration with electronic health record (EHR systems, testing, and reporting.

  19. Environmental challenges and opportunities of the evolving North American electricity market : European electricity generating facilities: an overview of European regulatory requirements and standardization efforts

    International Nuclear Information System (INIS)

    Nichols, L.

    2002-06-01

    Several factors are affecting power generating facilities, such as the opening of both electricity and gas markets, and the pressure applied on generators and governments to ensure a steady energy supply for consumers. An additional factor is the pressure for the closing of nuclear power facilities. European siting and emissions requirements for coal-fired and natural gas generating facilities were presented in this background paper. In addition, the author provided an overview of the standardization process in place in Europe. The European Union and its functioning were briefly described, as well as a listing of relevant organizations. The current trends were examined. The document first introduced the European Union, and the next section dealt with Regulatory regime: the internal energy market. The third section examined the issue of Regulatory regime: generation and environmental regulations. Section four presented environmental management systems, followed by a section on standardization. Section six discussed European organizations involved in electricity issues, while the following section dealt with European commission programs. The last section briefly looked at the trends in the electricity sector, broaching topics such as compliance, electricity generation, and emissions trading. 52 refs., 2 tabs

  20. Regulatory framework for the management of radioactive wastes in Argentina

    International Nuclear Information System (INIS)

    D'Amato, E.; Siraky, G.; Petraitis, E.; Novo, R.

    2000-01-01

    The legal and regulatory framework within which the radioactive waste management is carried out in Argentina are exposed. The activities of the Nuclear Regulatory Authority (ARN) in relation to facility inspections, safety assessments and collaboration with international agencies in the matter are also presented. Further, the regulatory criteria applied to waste management are reported. (author)

  1. Development of regulatory policy for SMART-P

    Energy Technology Data Exchange (ETDEWEB)

    Lee, S. H.; Lee, Y. H.; Moo, Philip; Koh, B. J.; Son, M. K.; Han, G. H.; Kim, D. H. [Korea Association for Nuclear Technology, Daejeon (Korea, Republic of)

    2004-06-15

    KAERI promoted the construction of a research reactor, SMART-P, the reduced scale of SMART, with intent to demonstrate the safety and performance of SMART. According to this progress, the development of regulatory process for SMART-P became necessary. The establishment of regulatory policy, based on the current regulatory guidelines as well as technical aspect, became essential matters. Considering the on-going small and medium size reactors in near future, the selection of the appropriate measure in the existing regulatory process to SMART-P is very important. Thus the schematic study for the applicable licensing procedure and regulatory requirements suitable for SMART-P is required.

  2. Development of regulatory policy for SMART-P

    Energy Technology Data Exchange (ETDEWEB)

    Lee, S. H.; Moon, S. H.; Lee, Y. H.; Son, M. K.; Han, K. H.; Kim, D. H. [Korea Association for Nuclear Technology, Taejon (Korea, Republic of)

    2003-06-15

    KAERI promoted the construction of a research reactor, SMART-P, the reduced scale of SMART, with intent to demonstrate the safety and performance of SMART. According to this progress, the development of regulatory process for SMART-P became necessary. The establishment of regulatory policy, based on the current regulatory guidelines as well as technical aspect, became essential matters. Considering the on-going small and medium size reactors m near future, the selection of the appropriate measure in the existing regulatory process to SMART-P is very important. Thus the schematic study for the applicable licensing procedure and regulatory requirements suitable for SMART-P is required.

  3. Safety and regulatory aspects of front end facilities of nuclear fuel cycle

    International Nuclear Information System (INIS)

    Khan, Kirity Bhushan; Jha, S.K.; Bhasin, Vivek; Behere, P.G.

    2017-01-01

    Nuclear Fuels Group of BARC consists of various divisions with diverse activities but impeccable safety records. This has been made possible with strict safety culture among trained personnel across all divisions. The major activities of this group encompass the front end fuel fabrication facilities for thermal and fast reactors and post irradiation examination of fuel and structural materials. The group has been responsible for delivering departmental targets, as and when required, fulfilling all safety and security requirements. The present article covers the safety and regulatory aspects of this group with special emphasis on group safety management by the administrative/organizational control, the procedure followed for regulatory review and control which are carried out and the laid down procedures for identifying, classifying and reporting of safety related incidents. (author)

  4. Towards optimal use of available technical resources for regulatory purposes. The Syrian experience

    International Nuclear Information System (INIS)

    Shweikani, R.; Suman, H.; Othman, I.

    2007-01-01

    The Atomic Energy commission of Syria (AECS) is nominated by Syrian legislation as the regulatory authority in respect of radiation protection and safety and security of radioactive sources. In addition AECS is providing a wide range of Technical Services (TS) through its various departments. In this paper, the cooperation and coordination between the regulatory authority and the providers of technical services in Syria are described. The adjustment of the regulatory programme as to make maximal use of the available technical resources is presented. It was shown that this relationship does not jeopardize the effective independency of the regulatory authority which is maintained by keeping the regulatory decisions based on pure regulatory considerations. (author)

  5. Advances in Canadian regulatory practice

    International Nuclear Information System (INIS)

    Waddington, J.G.

    1993-03-01

    The new General Amendments to the Regulations, new recommendations on dose limits, developments in techniques and safety thinking, and aging of plant are all contributing to the need for a significant number of new regulatory document on a wide range of topics. this paper highlights a number of initiatives taken in response to these pressures, giving a brief background to the initiative and, where possible, outlining some of the ideas in the document licensing guides on new dose limits, dosimetry, safety analysis, reliability, fault tree analysis, reporting requirements, human factors, software, the ALARA principle, backfitting and the licensing process. (Author) 29 refs., fig., 4 tabs

  6. Regulatory requirements for groundwater monitoring networks at hazardous waste sites

    International Nuclear Information System (INIS)

    Keller, J.F.

    1989-10-01

    In the absence of an explicit national mandate to protect groundwater quality, operators of active and inactive hazardous waste sites must use a number of statutes and regulations as guidance for detecting, correcting, and preventing groundwater contamination. The objective of this paper is to provide a framework of the technical and regulatory considerations that are important to the development of groundwater monitoring programs at hazardous waste sites. The technical site-specific needs and regulatory considerations, including existing groundwater standards and classifications, will be presented. 14 refs., 2 tabs

  7. 75 FR 51866 - Self-Regulatory Organizations; The Depository Trust Company; Order Approving Proposed Rule Change...

    Science.gov (United States)

    2010-08-23

    ... Transfer Service of National Securities Clearing Corporation August 16, 2010. I. Introduction On June 4... complements a Financial Industry Regulatory Authority (``FINRA'') rule requiring FINRA members to use... specified time frames. \\5\\ CNS is an ongoing accounting system which nets today's Settling Trades with...

  8. What is a comprehensive system of regulatory governance?; Que es un sistema Integral de Gestion Reglamentaria?

    Energy Technology Data Exchange (ETDEWEB)

    Real diaz, F. J.

    2011-07-01

    The progressive evolution and diversification of regulations concerning industrial safety has made their management increasingly complex, requiring more resources of organizations. Therefore, it is advisable that this management be made more efficient through systematization, specialization and the use of computing technologies. This is supported by the implementation of integrated regulatory management systems. This article explain the concept of integrated regulatory management systems, their structure and their advantages. It also includes a model for implementing them in an organization. (Author)

  9. Regulatory criteria for final disposal of radioactive wastes

    International Nuclear Information System (INIS)

    Petraitis, E.; Ciallella, N.; Siraky, G.

    1998-01-01

    This paper describes briefly the legislative and regulatory framework in which the final disposal of radioactive wastes is carried out in Argentina. It also presents the criteria developed by the Nuclear Regulatory Authority (ARN) to assess the long-term safety of final disposal systems for high level radioactive wastes. (author)

  10. 30 CFR 785.16 - Permits incorporating variances from approximate original contour restoration requirements for...

    Science.gov (United States)

    2010-07-01

    ... approximate original contour restoration requirements for steep slope mining. 785.16 Section 785.16 Mineral Resources OFFICE OF SURFACE MINING RECLAMATION AND ENFORCEMENT, DEPARTMENT OF THE INTERIOR SURFACE COAL... approximate original contour restoration requirements for steep slope mining. (a) The regulatory authority may...

  11. The evolving regulation of uranium recovery operations in the United States: Inovative approaches are necessary for cost effective regulatory oversight

    International Nuclear Information System (INIS)

    Thompson, A.J.; Lehrenbaum, W.U.; Lashway, D.C.

    2000-01-01

    The US domestic uranium industry is at a crossroads. Historic low prices for uranium, combined with stringent and often irrational regulatory requirements, pose a very real threat to the industry's continued viability. The Nuclear Regulatory Commission has taken a number of innovative steps to reform and rationalize its regulatory program. However, if the domestic uranium recovery industry is to remain viable, additional steps toward innovation and reform are needed, and effective implementation of reforms adopted by the Commission is essential. (author)

  12. Removal of regulatory controls for materials and sites

    International Nuclear Information System (INIS)

    2004-01-01

    Issues with the removal of regulatory controls are very important on the agenda of the regulatory authorities dealing with radioactive waste management (RWM). These issues arise prominently in decommissioning and in site remediation, and decisions can be very wide ranging having potentially important economic impacts and reaching outside the RWM area. The RWMC Regulators Forum started to address these issues by holding a topical discussion at its meeting in March 2003. Ths present document collates the national regulatory positions in the area of removal of regulatory controls. A summary of the national positions is also provided. The document is up to date to April 2004. (authors)

  13. Actions of the Cuban Nuclear Regulatory Authority in the adequate implementation of the legislation in matter of radiological protection; Acciones de la Autoridad Reguladora Nuclear cubana en la adecuada implementacion de la Legislacion en materia de proteccion radiologica

    Energy Technology Data Exchange (ETDEWEB)

    Fornet R, O.M. [Delegacion Territorial CITMA. Peralta No.16, Rpto Peralta, Holguin, CP 80400 (Cuba); Guillen C, A.; Betancourt H, L.A. [Centro Nacional de Seguridad Nuclear, Calle 28 No.504, Miramar Playa, La Habana (Cuba)]. e-mail: ofelia@citmahlg.holguin.inf.cu

    2006-07-01

    The effectiveness of the regulatory activity in matter of safety and radiological protection it depends in great measure of the practical implementation level of the legislation in this matter. In our country this objective has been achieved through the one continuous improvement of the Hierarchical System of Nuclear Regulation, the reconciliation with specialists and national experts in each matter during the elaboration of the legal documents; the popularization and gratuitous distribution of it approved; the precision in the validation conditions of the authorizations of those main precepts applicable to the practices; the legal foundation of the deficiencies evidenced in the regulatory inspections; the development of a Safety Culture; the realization of Annual Regulatory Conferences and mainly in the training of the personnel related with the safety. Also, the constant analysis on the part of the specialists of the Regulatory Authority of the grade of implementation of this legislation, it discussion in national and international events and the actions recommended in these works. As a result of this focus, it is considered that the Regulatory Authority has impacted appropriately in the implementation of this legislation. (Author)

  14. 78 FR 44275 - Semiannual Regulatory Agenda

    Science.gov (United States)

    2013-07-23

    ... Rights. National Park Service--Completed Actions Regulation Sequence No. Title Identifier No. 200 Winter.... Timetable: Action Date FR Cite NPRM 07/00/13 Final Action 05/00/14 Regulatory Flexibility Analysis Required...: Action Date FR Cite NPRM 10/00/14 Final Action 10/00/14 Regulatory Flexibility Analysis Required: Yes...

  15. Regulatory point of view of SAT application

    International Nuclear Information System (INIS)

    Juhasz, L.

    2002-01-01

    I present the regulatory system for monitoring operator training and check competency of operator personnel in Hungary and the effects of SAT to the regulatory framework/practice related to recruitment, training and authorisation of operating personnel. Also I introduce an application to manage the initial and refreshing training to regulatory bodies. (author)

  16. Enhancement of Nuclear Safety in Korea: A Regulatory Perspective

    International Nuclear Information System (INIS)

    Chung, K.Y.

    2016-01-01

    In the aftermath of Fukushima Daiichi accident in 2011 Korean regulatory body immediately performed special inspections on nuclear power plants (NPPs) and a research reactor in Korea, and issued an enforcement order for the licensees to implement fifty Fukushima action items to address the safety issues identified by the inspections. Subsequently, the licensees have established the implementation plans for resolution of the action items. By the implementation of the action items, the possibility of severe accident due to the extreme hazards has been greatly reduced and the capabilities to mitigate the severe accident, should it occur, have been upgraded. To improve the consistency and predictability of the regulation on severe accidents, Nuclear Safety and Security Commission (NSSC) the regulatory body in Korea, is revising the regulatory framework for severe accidents. The new framework will require the licensee to enhance the capabilities for prevention and mitigation of severe accidents in view of the defence in depth principle, to assess the radiological effects from the severe accidents, and to improve current accident management procedures and guidelines necessary for the prevention and mitigation of severe accidents. This rulemaking also considers the safety principles provided by the IAEA Vienna Declaration in 2015, which require new NPPs to prevent large radioactive releases. (author)

  17. Innovative approach to training radiation safety regulatory professionals

    International Nuclear Information System (INIS)

    Gilley, Debbie Bray

    2008-01-01

    Full text: The supply of human resources required to adequately manage a radiation safety regulatory program has diminished in the last five years. Competing professional opportunities and a reduction in the number of health physics secondary schools have made it necessary to look at alternative methods of training. There are limited educational programs in the US that prepare our professionals for careers in the Radiation Regulatory Programs. The state of Florida's radiation control program embraced a new methodology using a combination of didactic and work experience using qualification journals, subject matter experts, and formalized training to develop a qualified pool of employees to perform the regulatory functions and emergency response requirements of a state radiation control program. This program uses a task-based approach to identify training needs and draws upon current staff to develop and implement the training. This has led to a task-oriented staff capable of responding to basic regulatory and emergency response activities within one year of employment. Florida's program lends itself to other states or countries with limited resources that have experienced staff attrition due to retirement or competing employment opportunities. Information on establishing a 'task-based' pool of employees that can perform basic regulatory functions and emergency response after one year of employment will be described. Initial task analysis of core functions and methodology is used to determine the appropriate training methodology for these functions. Instructions will be provided on the methodology used to 'mentor' new employees and then incorporate the new employees into the established core functions and be a useful employee at the completion of the first year of employment. New training philosophy and regime may be useful in assisting in the development of programs in countries and states with limited resources for training radiation protection personnel. (author)

  18. The development of AECB regulatory documents

    International Nuclear Information System (INIS)

    Joyce, M.

    1981-01-01

    This document describes the Atomic Energy Control Board's (AECB) approach to the development and preparation of regulatory documents. The principal factors that have shaped the AECB'a regulatory approach are identified as background to the evolution of regulatory documents as are a number of current influences that affect the present and future development of these documents. Also described are the process by which regulatory documents are prepared and published and the points of contact between this process and the Canadian Standards Association program for nuclear standards. (author)

  19. Conformity check of JMTR to new regulatory standards

    International Nuclear Information System (INIS)

    Watahiki, Shunsuke; Ide, Hiroshi; Hanakawa, Hiroki; Yamaura, Takayuki; Kaminaga, Masanori

    2015-01-01

    With the lesson learned from the accident of TEPCO Fukushima Daiichi Nuclear Power Station, also based on the international standards, the 'New regulatory standards for nuclear facilities for research! was enforced by the Nuclear Regulatory Authority in December 2013. The main requirements of the new standards are as follows: (1) measures for earthquake, tsunami, and damage from the outside, (2) severity classification, (3) fire protection, (4) flood protection, (5) communication and contacting, (6) measures for the loss of external power supply, (7) monitoring equipment, and (8) expansion prevention of accident that releases a large amounts of radioactive materials. Under the new regulatory standards, it is demanded that the constructions, systems, and equipment with safety functions of the current nuclear facilities should maintain the safety functions in accordance with their importance against the basic ground motions and possible natural phenomena. For the buildings, equipment, and machineries of JMTR nuclear facilities, the severity classification was performed on each of safety function and seismic resistance. Based on the classification results, seismic evaluation and safety analysis were carried out. (A.O.)

  20. Cell therapy medicinal product regulatory framework in Europe and its application for MSC-based therapy development

    Science.gov (United States)

    Ancans, Janis

    2012-01-01

    Advanced therapy medicinal products (ATMPs), including cell therapy products, form a new class of medicines in the European Union. Since the ATMPs are at the forefront of scientific innovation in medicine, specific regulatory framework has been developed for these medicines and implemented from 2009. The Committee for Advanced Therapies (CAT) has been established at the European Medicines Agency (EMA) for centralized classification, certification and evaluation procedures, and other ATMP-related tasks. Guidance documents, initiatives, and interaction platforms are available to make the new framework more accessible for small- and medium-sized enterprises, academia, hospitals, and foundations. Good understanding of the centralized and national components of the regulatory system is required to plan product development. It is in the best interests of the cell therapy developers to utilize the resources provided starting with the pre-clinical stage. Whilst there have been no mesenchymal stem cell (MSC)-based medicine authorizations in the EU, three MSC products have received marketing approval in other regions since 2011. The information provided on the regulatory requirements, procedures, and initiatives is aimed at facilitating MSC-based medicinal product development and authorization in the EU. PMID:22912639