  1. SNF project engineering process improvement plan

    International Nuclear Information System (INIS)

    KELMENSON, R.L.

    1999-01-01

    This Engineering Process Improvement Plan documents the activities and plans to be taken by the SNF Project (the Project) to support its engineering process and to produce a consolidated set of engineering procedures that are fully compliant with the requirements of HNF-PRO-1819 (1819). These requirements are imposed on all engineering activities performed for the Project and apply to all life-cycle stages of the Project's systems, structures and components (SSCs). This Plan describes the steps that will be taken by the Project during the transition period to ensure that new procedures are effectively integrated into the Project's work process as these procedures are issued. The consolidated procedures will be issued and implemented by September 30, 1999

  2. SNF Project Engineering Process Improvement Plan

    International Nuclear Information System (INIS)

    DESAI, S.P.

    2000-01-01

    This plan documents the SNF Project activities and plans to support its engineering process. It describes five SNF Project Engineering initiatives: new engineering procedures, qualification cards process; configuration management, engineering self assessments, and integrated schedule for engineering activities

  3. SNF project engineering process improvement plan

    International Nuclear Information System (INIS)

    DESAI, S.P.

    1999-01-01

    This Engineering Process Improvement Plan documents the activities and plans to be taken by the SNF Project to support its engineering process and to produce a consolidated set of engineering procedures that are fully compliant with the requirements of HNF-PRO-1819. All new procedures will be issued and implemented by September 30, 1999

  4. Process for planning and control of software projects using XedroGESPRO

    OpenAIRE

    Jacqueline Marín-Sánchez; José Alejandro Lugo-García; Pedro Yobanis Piñero-Pérez; Alena María Santiesteban-García; Félix Noel Abelardo-Santana; Javier Menéndez-Rizo

    2014-01-01

    The software project management in Cuba has become a key area for improving production processes and decisionmaking in organizations. Several models and standards for process improvement, related with project management, proposed best practices on issues of planning and control of projects. However, they are generic guidelines that describe only those activities to execute, leaving the responsibility for implementing to organizations, using sometimes , expensive proprietary infor...

  5. Quality Assurance Project Plan for Citizen Science Projects

    Science.gov (United States)

    The Quality Assurance Project Plan is necessary for every project that collects or uses environmental data. It documents the project planning process and serves as a blueprint for how your project will run.

  6. Risks management in project planning

    OpenAIRE

    Stankevičiūtė, Roberta

    2017-01-01

    Project management consists of two very important aspects – managing the right project and managing the project right. To know that you are managing the right project you need to ensure that your project is based on an actual requirement and that your project goal is relevant and beneficial. And professional project planning assists in managing project the right way. The project planning process is very time consuming and is one of the most important parts of the project management process. T...

  7. Integrating fuel treatment into ecosystem management: A proposed project planning process

    Science.gov (United States)

    Keith D. Stockmann; Kevin D. Hyde; J. Greg Jones; Dan R. Loeffler; Robin P. Silverstein

    2010-01-01

    Concern over increased wildland fire threats on public lands throughout the western United States makes fuel reduction activities the primary driver of many management projects. This single-issue focus recalls a management planning process practiced frequently in recent decades - a least-harm approach where the primary objective is first addressed and then plans are...

  8. Why does project planning fail

    International Nuclear Information System (INIS)

    Foley, M.; Luciano, G.

    1991-01-01

    The technology of project controls have become increasingly sophisticated. Some say that the technological advancements of the Nineteen-Eighties represented a maturation of project control tools. Others say that the advancements were merely bells and whistles that added little or nothing to the project management process. Above it all, as we enter the Nineties, there is a popular outcry to get back to the basics of planning. The genesis of this outcry is the sobering impact of significant cost overruns and schedule extensions, even on projects that have employed the most advanced project control tools and systems. This paper examines the merits of taking a strategic approach to the project planning process. Within that context, there are basic goals of planning which are enduring through the life cycle of the project. Key reasons for failure and inability to achieve the goals of project planning are explained. By examining the goals of project planning and the reasons for failure, insight is provided into the role of project controls specialists and sophisticated project control tools in meeting the challenges of complex project management in the 1990's

  9. Planning for high performance project teams

    International Nuclear Information System (INIS)

    Reed, W.; Keeney, J.; Westney, R.

    1997-01-01

    Both industry-wide research and corporate benchmarking studies confirm the significant savings in cost and time that result from early planning of a project. Amoco's Team Planning Workshop combines long-term strategic project planning and short-term tactical planning with team building to provide the basis for high performing project teams, better project planning, and effective implementation of the Amoco Common Process for managing projects

  10. Project Management Plan Solution Stabilization

    International Nuclear Information System (INIS)

    SATO, P.K.

    1999-01-01

    This plan presents the overall objectives, description, justification and planning for the Plutonium Finishing Plant (PFP) Solutions Stabilization subproject. The intent of this plan is to describe how this project will be managed and integrated with other facility stabilization and deactivation activities. This plan supplements the overall integrated plan presented in the Integrated Project Management Plan (IPMP) for the Plutonium Finishing Plant Stabilization and Deactivation Project, HNF-3617. This project plan is the top-level definitive project management document for the PFP Solution Stabilization subproject. It specifies the technical, schedule, requirements and the cost baselines to manage the execution of the Solution Stabilization subproject. Any deviations to the document must be authorized through the appropriate change control process

  11. Project Management Plan Solution Stabilization

    Energy Technology Data Exchange (ETDEWEB)

    SATO, P.K.

    1999-08-31

    This plan presents the overall objectives, description, justification and planning for the Plutonium Finishing Plant (PFP) Solutions Stabilization subproject. The intent of this plan is to describe how this project will be managed and integrated with other facility stabilization and deactivation activities. This plan supplements the overall integrated plan presented in the Integrated Project Management Plan (IPMP) for the Plutonium Finishing Plant Stabilization and Deactivation Project, HNF-3617. This project plan is the top-level definitive project management document for the PFP Solution Stabilization subproject. It specifies the technical, schedule, requirements and the cost baselines to manage the execution of the Solution Stabilization subproject. Any deviations to the document must be authorized through the appropriate change control process.

  12. Quality initiatives: planning, setting up, and carrying out radiology process improvement projects.

    Science.gov (United States)

    Tamm, Eric P; Szklaruk, Janio; Puthooran, Leejo; Stone, Danna; Stevens, Brian L; Modaro, Cathy

    2012-01-01

    In the coming decades, those who provide radiologic imaging services will be increasingly challenged by the economic, demographic, and political forces affecting healthcare to improve their efficiency, enhance the value of their services, and achieve greater customer satisfaction. It is essential that radiologists master and consistently apply basic process improvement skills that have allowed professionals in many other fields to thrive in a competitive environment. The authors provide a step-by-step overview of process improvement from the perspective of a radiologic imaging practice by describing their experience in conducting a process improvement project: to increase the daily volume of body magnetic resonance imaging examinations performed at their institution. The first step in any process improvement project is to identify and prioritize opportunities for improvement in the work process. Next, an effective project team must be formed that includes representatives of all participants in the process. An achievable aim must be formulated, appropriate measures selected, and baseline data collected to determine the effects of subsequent efforts to achieve the aim. Each aspect of the process in question is then analyzed by using appropriate tools (eg, flowcharts, fishbone diagrams, Pareto diagrams) to identify opportunities for beneficial change. Plans for change are then established and implemented with regular measurements and review followed by necessary adjustments in course. These so-called PDSA (planning, doing, studying, and acting) cycles are repeated until the aim is achieved or modified and the project closed.

  13. Computer aided process planning at the Oak Ridge Y-12 plant: a pilot project

    International Nuclear Information System (INIS)

    Hewgley, R.E. Jr.; Prewett, H.P. Jr.

    1979-01-01

    In 1976, a formal needs analysis was conducted in one of the Fabrication Division Shops of all activities from the receipt of an order through final machining. The results indicated deficiencies in process planning activities involving special production work. A pilot program was organized to investigate the benefits of emerging CAM technology and application of GT concepts for machining operations at the Y-12 Plant. The objective of the CAPP Project was to provide computer-assisted process planning for special production machining in th shop. The CAPP team was charged with the specific goal of demonstrating computer-aided process planning within a four-year term. The CAPP charter included a plan with intermediate measurable milestones for achieving its mission. In three years, the CAPP project demonstrated benefits to process planning. A capability to retrieve historical records for similar parts, to review accurately the status of all staff assignments, and to generate detailed machining procedures definitely can impact the way in which a machine shop prepared for new orders. The real payoff is in the hardcopy output (N/C programs, studies, sequence plans, and procedures). 4 figures,

  14. Project Management Plan

    International Nuclear Information System (INIS)

    1988-01-01

    The mission of the Uranium Mill Tailings Remedial Action (UMTRA) Project is explicitly stated and directed in the Uranium Mill Tailings Radiation Control Act of 1978, Public Law 95-604, 42 USC 7901 (hereinafter referred to as the ''Act''). Title I of the Act authorizes the Department of Energy (DOE) to undertake remedial actions at 24 designated inactive uranium processing sites and associated vicinity properties containing uranium mill tailings and other residual radioactive materials derived from the processing sites. The Act, amended in January 1983, by Public Law 97-415, also authorizes DOE to perform remedial actions at vicinity properties in Edgemont, South Dakota. Cleanup of the Edgemont processing site is the responsibility of the Tennessee Valley Authority. This document describes the plan, organization, system, and methodologies used to manage the design, construction, and other activities required to clean up the designated sites and associated vicinity properties in accordance with the Act. The plan describes the objectives of the UMTRA Project, defines participants' roles and responsibilities, outlines the technical approach for accomplishing the objectives, and describes the planning and managerial controls to be used in integrating and performing the Project mission. 21 figs., 21 tabs

  15. 33 CFR 385.24 - Project Management Plans.

    Science.gov (United States)

    2010-07-01

    ... 33 Navigation and Navigable Waters 3 2010-07-01 2010-07-01 false Project Management Plans. 385.24... Processes § 385.24 Project Management Plans. (a) General requirements. (1) The Corps of Engineers and the... agencies, develop a Project Management Plan prior to initiating activities on a project. (2) The Project...

  16. Licensing plan for UMTRA project disposal sites

    International Nuclear Information System (INIS)

    1993-09-01

    The Uranium Mill Tailings Remedial Action (UMTRA) Project Office developed a plan to define UMTRA Project licensing program objectives and establish a process enabling the DOE to document completion of remedial actions in compliance with 40 CFR 1 92 and the requirements of the NRC general license. This document supersedes the January 1987 Project Licensing Plan (DOE, 1987). The plan summarizes the legislative and regulatory basis for licensing, identifies participating agencies and their roles and responsibilities, defines key activities and milestones in the licensing process, and details the coordination of these activities. This plan provides an overview of the UMTRA Project from the end of remedial actions through the NRC's acceptance of a disposal site under the general license. The licensing process integrates large phases of the UMTRA Project. Other programmatic UMTRA Project documents listed in Section 6.0 provide supporting information

  17. Project Surveillance and Maintenance Plan

    International Nuclear Information System (INIS)

    1985-09-01

    The Project Surveillance and Maintenance Plan (PSMP) describes the procedures that will be used by the US Department of Energy (DOE), or other agency as designated by the President to verify that inactive uranium tailings disposal facilities remain in compliance with licensing requirements and US Environmental Protection Agency (EPA) standards for remedial actions. The PSMP will be used as a guide for the development of individual Site Surveillance and Maintenance Plans (part of a license application) for each of the UMTRA Project sites. The PSMP is not intended to provide minimum requirements but rather to provide guidance in the selection of surveillance measures. For example, the plan acknowledges that ground-water monitoring may or may not be required and provides the [guidance] to make this decision. The Site Surveillance and Maintenance Plans (SSMPs) will form the basis for the licensing of the long-term surveillance and maintenance of each UMTRA Project site by the NRC. Therefore, the PSMP is a key milestone in the licensing process of all UMTRA Project sites. The Project Licensing Plan (DOE, 1984a) describes the licensing process. 11 refs., 22 figs., 8 tabs

  18. Multi-site risk-based project planning, optimization, sequencing, & budgeting process and tool for the integrated facility disposition project

    International Nuclear Information System (INIS)

    Nelson, J.G.; Castillo, C.; Huntsman, J.; Killoy, S.; Lucek, H.; Marks, T.C.

    2011-01-01

    Faced with the Department of Energy (DOE) Complex Transformation, National Nuclear Security Administration (NNSA) was tasked with developing an integrated plan for the decommissioning of over 400 facilities and 300 environmental remediation units, as well as the many reconfiguration and modernization projects at the Oak Ridge National Laboratory (ORNL) and Y-12 Complex. Manual scheduling of remediation activities is time-consuming and inherently introduces bias of the scheduler or organization into the process. Clearly a well-defined process, quantitative risk-based tool was needed to develop an objective, unbiased baseline sequence and schedule with a sound technical foundation for the Integrated Facility Disposition Project (IFDP). Faced with limited available data, innovation was needed to extrapolate intelligent relative data for key risk parameters based on known data elements. The IFDP Supermodel was customized and expanded to provide this capability for conceptual planning of diverse project portfolios and multiple sites. (author)

  19. PROJECT SCOPE MANAGEMENT PROCESS

    Directory of Open Access Journals (Sweden)

    Yana Derenskaya

    2018-01-01

    Full Text Available The purpose of the article is to define the essence of project scope management process, its components, as well as to develop an algorithm of project scope management in terms of pharmaceutical production. Methodology. To carry out the study, available information sources on standards of project management in whole and elements of project scope management in particular are analysed. Methods of system and structural analysis, logical generalization are used to study the totality of subprocesses of project scope management, input and output documents, and to provide each of them. Methods of network planning are used to construct a precedence diagram of project scope management process. Results of the research showed that components of the project scope management are managing the scope of the project product and managing the content of project work. It is the second component is investigated in the presented work as a subject of research. Accordingly, it is defined that project scope management process is to substantiate and bring to the realization the necessary amount of work that ensures the successful implementation of the project (achievement of its goal and objectives of individual project participants. It is also determined that the process of managing the project scope takes into account the planning, definition of the project scope, creation of the structure of project work, confirmation of the scope and management of the project scope. Participants of these subprocesses are: customer, investor, and other project participants – external organizations (contractors of the project; project review committee; project manager and project team. It is revealed that the key element of planning the project scope is the formation of the structure of design work, the justification of the number of works, and the sequence of their implementation. It is recommended to use the following sequence of stages for creating the structure of project work

  20. Integrated multi-resource planning and scheduling in engineering project

    Directory of Open Access Journals (Sweden)

    Samer Ben Issa

    2017-01-01

    Full Text Available Planning and scheduling processes in project management are carried out sequentially in prac-tice, i.e. planning project activities first without visibility of resource limitation, and then schedul-ing the project according to these pre-planned activities. This is a need to integrate these two pro-cesses. In this paper, we use Branch and Bound approach for generating all the feasible and non-feasible project schedules with/without activity splitting, and with a new criterion called “the Minimum Moments of Resources Required around X-Y axes (MMORR”, we select the best feasible project schedule to integrate plan processing and schedule processing for engineering projects. The results illustrate that this integrated approach can effectively select the best feasible project schedule among alternatives, improves the resource utilization, and shortens the project lead time.

  1. Project plan remove special nuclear material from PFP project plutonium finishing plant

    International Nuclear Information System (INIS)

    BARTLETT, W.D.

    1999-01-01

    This plan presents the overall objectives, description, justification and planning for the Plutonium Finishing Plant (PFP) Remove Special Nuclear Material (SNM) Materials. The intent of this plan is to describe how this project will be managed and integrated with other facility stabilization and deactivation activities. This plan supplements the overall integrated plan presented in the Plutonium Finishing Plant Integrated Project Management Plan (IPMP), HNF-3617, Rev. 0. This project plan is the top-level definitive project management document for PFP Remove SNM Materials project. It specifies the technical, schedule, requirements and the cost baselines to manage the execution of the Remove SNM Materials project. Any deviations to the document must be authorized through the appropriate change control process

  2. Understanding Applications of Project Planning and Scheduling in Construction Projects

    OpenAIRE

    AlNasseri, Hammad Abdullah

    2015-01-01

    Construction project life-cycle processes must be managed in a more effective and predictable way to meet project stakeholders’ needs. However, there is increasing concern about whether know-how effectively improves understanding of underlying theories of project management processes for construction organizations and their project managers. Project planning and scheduling are considered as key and challenging tools in controlling and monitoring project performance, but many worldwide constru...

  3. The role of project planning in project management

    OpenAIRE

    Klitsenko, A. I.; Клиценко, А. И.

    2013-01-01

    This article describes the importance of the process of project planning. The author gives irrefutable arguments concerning crucial role of project planning. This article presents the definition, objects and the main goal of project planning. The purpose of this article is to review such objects of project planning as project scope, risk and human resources. Данная статья описывает важность процесса проектного планирования. Автор дает неопровержимые доводы, касающиеся решающей роли проектн...

  4. Project plan remove special nuclear material from PFP project plutonium finishing plant; TOPICAL

    International Nuclear Information System (INIS)

    BARTLETT, W.D.

    1999-01-01

    This plan presents the overall objectives, description, justification and planning for the Plutonium Finishing Plant (PFP) Remove Special Nuclear Material (SNM) Materials. The intent of this plan is to describe how this project will be managed and integrated with other facility stabilization and deactivation activities. This plan supplements the overall integrated plan presented in the Plutonium Finishing Plant Integrated Project Management Plan (IPMP), HNF-3617,Rev. 0. This project plan is the top-level definitive project management document for PFP Remove SNM Materials project. It specifies the technical, schedule, requirements and the cost baselines to manage the execution of the Remove SNM Materials project. Any deviations to the document must be authorized through the appropriate change control process

  5. Metals and Alloys Material Stabilization Process Plan

    Energy Technology Data Exchange (ETDEWEB)

    RISENMAY, H.R.; BURK, R.A.

    2000-05-18

    This Plan outlines the process for brushing metal and alloys in accordance with the path forward discussed in the Integrated Project Management Plan for the Plutonium Finishing Plant Stabilization and Deactivation Project, HNF-3617, and requirements set forth in the Project Management Plan for Materials Stabilization, HNF-3605. This plan provides the basis for selection of the location to process, the processes involved, equipment to be used, and the characterization of the contents of the can. The scope of the process is from retrieval of metals and alloys from storage to transfer back to storage in a repackaged configuration.

  6. Metals and Alloys Material Stabilization Process Plan

    International Nuclear Information System (INIS)

    RISENMAY, H.R.; BURK, R.A.

    2000-01-01

    This Plan outlines the process for brushing metal and alloys in accordance with the path forward discussed in the Integrated Project Management Plan for the Plutonium Finishing Plant Stabilization and Deactivation Project, HNF-3617, and requirements set forth in the Project Management Plan for Materials Stabilization, HNF-3605. This plan provides the basis for selection of the location to process, the processes involved, equipment to be used, and the characterization of the contents of the can. The scope of the process is from retrieval of metals and alloys from storage to transfer back to storage in a repackaged configuration

  7. Test Plan: Sludge Treatment Project Corrosion Process Chemistry Follow-on Testing

    Energy Technology Data Exchange (ETDEWEB)

    Delegard, Calvin H.; Schmidt, Andrew J.; Poloski, Adam P.

    2007-08-17

    This test plan was prepared by the Pacific Northwest National Laboratory (PNNL) under contract with Fluor Hanford (FH). The test plan describes the scope and conditions to be used to perform laboratory-scale testing of the Sludge Treatment Project (STP) hydrothermal treatment of K Basin sludge. The STP, managed for the U. S. Department of Energy (DOE) by FH, was created to design and operate a process to eliminate uranium metal from the sludge prior to packaging for Waste Isolation Pilot Plant (WIPP) by using high temperature liquid water to accelerate the reaction, produce uranium dioxide from the uranium metal, and safely discharge the hydrogen. The proposed testing builds on the approach and laboratory test findings for both K Basin sludge and simulated sludge garnered during prior testing from September 2006 to March 2007. The outlined testing in this plan is designed to yield further understanding of the nature of the chemical reactions, the effects of compositional and process variations and the effectiveness of various strategies to mitigate the observed high shear strength phenomenon observed during the prior testing. These tests are designed to provide process validation and refinement vs. process development and design input. The expected outcome is to establish a level of understanding of the chemistry such that successful operating strategies and parameters can be implemented within the confines of the existing STP corrosion vessel design. In July 2007, the DOE provided direction to FH regarding significant changes to the scope of the overall STP. As a result of the changes, FH directed PNNL to stop work on most of the planned activities covered in this test plan. Therefore, it is unlikely the testing described here will be performed. However, to preserve the test strategy and details developed to date, the test plan has been published.

  8. PACTEL OECD project planning (PACO). PACTEL OECD project planning

    Energy Technology Data Exchange (ETDEWEB)

    Kouhia, V.; Purhonen, H. [Lappeenranta University of Technology (Finland)

    2004-07-01

    OECD launched the SETH project to investigate issues relevant for accident prevention and management and to ensure the existence of integral thermal hydraulic test facilities. The facilities included in the SETH project are PKL from Germany and PANDA from Switzerland. At the early stages of the SETH project an idea was raised to exploit the PACTEL facility in a similar OECD project. Without any external funding the analytical work in the required extent would not be possible within Lappeenranta University of Technology, the party responsible of operating PACTEL. This fact directed the PACO project proposal to be conducted for the SAFIR programme. The aim of the PACO project is to prepare a project proposal to OECD of a PACTEL related project. To attain this objective some preliminary analyses have to be performed to ensure the relevancy of the proposed topic. The low power situation, i.e. midloop state was chosen to be the topic in the PACO studies and project planning basis. The plan is to use PACTEL to examine vertical steam generator behaviour during the midloop operation and the following loss of residual heat removal system transient. Such a possibility is acknowledged with special alterations to PACTEL. The APROS code version 5.04.07 was selected as a tool for the preanalyses. The virtual simulation of the chosen experimental situation would give a preconception on the phenomena to be expected and the progression of the transient. Originally the PACO project was planned to continue only for a few months, ending up with the project proposal to OECD during the summer time 2004. During the pre-calculation process it became obvious that the time expected was not enough to establish good pre-calculation results. The reasons for this relates to time used to learn and adapt the use of the chosen code, improvements and corrections in modelling as well as the code ability to manage the special conditions defined for the project topic. Another aspect on completing a

  9. Uranium Mill Tailings Remedial Action Project surface project management plan

    International Nuclear Information System (INIS)

    1994-09-01

    This Project Management Plan describes the planning, systems, and organization that shall be used to manage the Uranium Mill Tailings Remedial Action Project (UMTRA). US DOE is authorized to stabilize and control surface tailings and ground water contamination at 24 inactive uranium processing sites and associated vicinity properties containing uranium mill tailings and related residual radioactive materials

  10. Project Planning and Implementation: Lessons Learned From the AQBMP Project

    National Research Council Canada - National Science Library

    1997-01-01

    ...). This NSRP report is funded as an addendum to the Air Quality Best Management Practices (AQBMP) project (N1 -944). The AQBMP project was completed using an intensive project planning process using a variety of quality management tools...

  11. UMTRA Project: Environment, Safety, and Health Plan

    International Nuclear Information System (INIS)

    1995-02-01

    The US Department of Energy has prepared this UMTRA Project Environment, Safety, and Health (ES and H) Plan to establish the policy, implementing requirements, and guidance for the UMTRA Project. The requirements and guidance identified in this plan are designed to provide technical direction to UMTRA Project contractors to assist in the development and implementation of their ES and H plans and programs for UMTRA Project work activities. Specific requirements set forth in this UMTRA Project ES and H Plan are intended to provide uniformity to the UMTRA Project's ES and H programs for processing sites, disposal sites, and vicinity properties. In all cases, this UMTRA Project ES and H Plan is intended to be consistent with applicable standards and regulations and to provide guidance that is generic in nature and will allow for contractors' evaluation of site or contract-specific ES and H conditions. This plan specifies the basic ES and H requirements applicable to UMTRA Project ES and H programs and delineates responsibilities for carrying out this plan. DOE and contractor ES and H personnel are expected to exercise professional judgment and apply a graded approach when interpreting these guidelines, based on the risk of operations

  12. Groundwater/Vadose Zone Integration Project Management Plan

    International Nuclear Information System (INIS)

    Hughes, M. C.

    1999-01-01

    This Project Management Plan (PMP) defines the authorities, roles, and responsibilities of the US Department of Energy (DOE), Richland Operations Office (RL) and those contractor organizations participating in the Hanford Site' s Groundwater/Vadose Zone (GW/VZ) Integration Project. The PMP also describes the planning and control systems, business processes, and other management tools needed to properly and consistently conduct the Integration Project scope of work

  13. Dynamic and stochastic multi-project planning

    CERN Document Server

    Melchiors, Philipp

    2015-01-01

    This book deals with dynamic and stochastic methods for multi-project planning. Based on the idea of using queueing networks for the analysis of dynamic-stochastic multi-project environments this book addresses two problems: detailed scheduling of project activities, and integrated order acceptance and capacity planning. In an extensive simulation study, the book thoroughly investigates existing scheduling policies. To obtain optimal and near optimal scheduling policies new models and algorithms are proposed based on the theory of Markov decision processes and Approximate Dynamic programming.

  14. Spent Nuclear Fuel Project operational staffing plan

    International Nuclear Information System (INIS)

    Debban, B.L.

    1996-03-01

    Using the Spent Nuclear Fuel (SNF) Project's current process flow concepts and knowledge from cognizant engineering and operational personnel, an initial assessment of the SNF Project radiological exposure and resource requirements was completed. A small project team completed a step by step analysis of fuel movement in the K Basins to the new interim storage location, the Canister Storage Building (CSB). This analysis looked at fuel retrieval, conditioning of the fuel, and transportation of the fuel. This plan describes the staffing structure for fuel processing, fuel movement, and the maintenance and operation (M ampersand O) staffing requirements of the facilities. This initial draft does not identify the support function resources required for M ampersand O, i.e., administrative and engineering (technical support). These will be included in future revisions to the plan. This plan looks at the resource requirements for the SNF subprojects, specifically, the operations of the facilities, balances resources where applicable, rotates crews where applicable, and attempts to use individuals in multi-task assignments. This plan does not apply to the construction phase of planned projects that affect staffing levels of K Basins

  15. Tank Waste Remediation System Characterization Project Programmatic Risk Management Plan

    International Nuclear Information System (INIS)

    Baide, D.G.; Webster, T.L.

    1995-12-01

    The TWRS Characterization Project has developed a process and plan in order to identify, manage and control the risks associated with tank waste characterization activities. The result of implementing this process is a defined list of programmatic risks (i.e. a risk management list) that are used by the Project as management tool. This concept of risk management process is a commonly used systems engineering approach which is being applied to all TWRS program and project elements. The Characterization Project risk management plan and list are subset of the overall TWRS risk management plan and list

  16. Reengineering the Project Design Process

    Science.gov (United States)

    Casani, E.; Metzger, R.

    1994-01-01

    In response to NASA's goal of working faster, better and cheaper, JPL has developed extensive plans to minimize cost, maximize customer and employee satisfaction, and implement small- and moderate-size missions. These plans include improved management structures and processes, enhanced technical design processes, the incorporation of new technology, and the development of more economical space- and ground-system designs. The Laboratory's new Flight Projects Implementation Office has been chartered to oversee these innovations and the reengineering of JPL's project design process, including establishment of the Project Design Center and the Flight System Testbed. Reengineering at JPL implies a cultural change whereby the character of its design process will change from sequential to concurrent and from hierarchical to parallel. The Project Design Center will support missions offering high science return, design to cost, demonstrations of new technology, and rapid development. Its computer-supported environment will foster high-fidelity project life-cycle development and cost estimating.

  17. Spent Nuclear Fuel project interface control plan

    International Nuclear Information System (INIS)

    Reilly, M.A.

    1995-01-01

    This implementation process philosophy is in keeping with the ongoing reengineering of the WHC Controlled Manuals to achieve interface control within the SNF Project. This plan applies to all SNF Project sub-project to sub-project, and sub-project to exteranl (both on and off the Hanford Site) interfaces

  18. Preliminary Project Execution Plan for the Remote-Handled Low-Level Waste Disposal Project

    Energy Technology Data Exchange (ETDEWEB)

    David Duncan

    2011-05-01

    This preliminary project execution plan (PEP) defines U.S. Department of Energy (DOE) project objectives, roles and responsibilities of project participants, project organization, and controls to effectively manage acquisition of capital funds for construction of a proposed remote-handled low-level waste (LLW) disposal facility at the Idaho National Laboratory (INL). The plan addresses the policies, requirements, and critical decision (CD) responsibilities identified in DOE Order 413.3B, 'Program and Project Management for the Acquisition of Capital Assets.' This plan is intended to be a 'living document' that will be periodically updated as the project progresses through the CD process to construction and turnover for operation.

  19. Preliminary Project Execution Plan for the Remote-Handled Low-Level Waste Disposal Project

    International Nuclear Information System (INIS)

    Duncan, David

    2011-01-01

    This preliminary project execution plan (PEP) defines U.S. Department of Energy (DOE) project objectives, roles and responsibilities of project participants, project organization, and controls to effectively manage acquisition of capital funds for construction of a proposed remote-handled low-level waste (LLW) disposal facility at the Idaho National Laboratory (INL). The plan addresses the policies, requirements, and critical decision (CD) responsibilities identified in DOE Order 413.3B, 'Program and Project Management for the Acquisition of Capital Assets.' This plan is intended to be a 'living document' that will be periodically updated as the project progresses through the CD process to construction and turnover for operation.

  20. Project Plan For Remove Special Nuclear Material (SNM) from Plutonium Finishing Plant (PFP) Project

    International Nuclear Information System (INIS)

    BARTLETT, W.D.

    1999-01-01

    This plan presents the overall objectives, description, justification and planning for the Plutonium Finishing Plant (PFP) Remove SNM Materials. The intent of this plan is to describe how this project will be managed and integrated with other facility stabilization and deactivation activities. This plan supplements the overall integrated plan presented in the Plutonium Finishing Plant Integrated Project Management Plan (IPMP), HNF-3617. This project plan is the top-level definitive project management document for the PFP Remove SNM Materials project. It specifies the technical, schedule, requirements and the cost baseline to manage the execution of the Remove SNM Materials project. Any deviation to the document must be authorized through the appropriate change control process. The Remove SNM Materials project provides the necessary support and controls required for DOE-HQ, DOE-RL, BWHC, and other DOE Complex Contractors the path forward to negotiate shipped/receiver agreements, schedule shipments, and transfer material out of PFP to enable final deactivation

  1. Waste receiving and processing facility module 1 data management system software project management plan

    International Nuclear Information System (INIS)

    Clark, R.E.

    1994-01-01

    This document provides the software development plan for the Waste Receiving and Processing (WRAP) Module 1 Data Management System (DMS). The DMS is one of the plant computer systems for the new WRAP 1 facility (Project W-026). The DMS will collect, store, and report data required to certify the low level waste (LLW) and transuranic (TRU) waste items processed at WRAP 1 as acceptable for shipment, storage, or disposal

  2. Recertification Project Plan

    International Nuclear Information System (INIS)

    2001-01-01

    The Waste Isolation Pilot Plant's (WIPP) Recertification Project was established to meet the requirement placed in the WIPP Land Withdrawal Act (LWA) to demonstrate WIPP's continued compliance with the Environmental Protection Agency's (EPA) disposal regulations at five-year intervals. This plan delineates the end goal of the effort, sets out interim goals, and offers up guiding assumptions. In general, it sets the overall direction for a highly complex and interdependent set of tasks leading to recertification of the repository in the spring of 2004. In addition, this plan establishes the institutional roles and responsibilities of WIPP project participants in the recertification effort and lays out a high-level schedule for producing the Compliance Recertification Application (CRA). Detailed plans from each organization supporting this project have been included with this document as attachments. Each participant plan provides significantly more detail with descriptions of activities that are designed to ensure a successful outcome. Woven throughout this plan are the elements of guidance and direction gained from technical exchanges with EPA managers and staff. An important principle on which this plan is built is that the process of recertification will not involve modification to the certification baseline, nor will it involve rule making of any kind. Only changes previously approved by the EPA will be detailed in the CRA. EPA-approved changes to the WIPP certification will be accepted through modification or will be approved through the annual change reporting process. For any compliance areas that have not changed since the submission of the Compliance Certification Application(CCA), these will merely be incorporated in the CRA by reference. The CRA will cover all information since the October 1996 submittal of the CCA. A second major principle on which this plan is built stems from the EPA WIPP Recertification Guidance. That guidance makes it clear that, if

  3. Process-based project proposal risk management

    Directory of Open Access Journals (Sweden)

    Alok Kumar

    2016-12-01

    Full Text Available We all are aware of the organizational omnipresence. Projects within the organizations are ubiquitous too. Projects achieve their goals successfully if they are planned, scheduled, controlled and implemented well. The project lifecycle of initiating, planning, scheduling, controlling and implementing are very well-planned by project managers and the organizations. Successful projects have well-developed risk management plans to deal with situations impacting projects. Like any other organisation, a university does try to access funds for different purposes too. For such organisations, running a project is not the issue, rather getting a project proposal approved to fund a project is the key. Project proposal processing is done by the nodal office in every organisation. Usually, these nodal offices help in administration and submission of a project proposal for accessing funds. Seldom are these nodal project offices within the organizations facilitate a project proposal approval by proactively reaching out to the project managers. And as project managers prepare project proposals, little or no attention is made to prepare a project proposal risk plan so as to maximise project acquisition. Risk plans are submitted while preparing proposals but these risk plans cater to a requirement to address actual projects upon approval. Hence, a risk management plan for project proposal is either missing or very little effort is made to treat the risks inherent in project acquisition. This paper is an integral attempt to highlight the importance of risk treatment for project proposal stage as an extremely important step to preparing the risk management plan made for projects corresponding to their lifecycle phases. Several tools and techniques have been proposed in the paper to help and guide either the project owner (proposer or the main organisational unit responsible for project management. Development of tools and techniques to further enhance project

  4. HANDI 2000 project execution plan

    International Nuclear Information System (INIS)

    BENNION, S.I.

    1999-01-01

    The HANDI 2000 project will meet some of the major objectives and goals of the PHMC Management and Integration Plan, HNF-MP-00/Rev. 11, by integrating the major Hanford business processes and their supporting information systems

  5. Spent Nuclear Fuel project, project management plan

    International Nuclear Information System (INIS)

    Fuquay, B.J.

    1995-01-01

    The Hanford Spent Nuclear Fuel Project has been established to safely store spent nuclear fuel at the Hanford Site. This Project Management Plan sets forth the management basis for the Spent Nuclear Fuel Project. The plan applies to all fabrication and construction projects, operation of the Spent Nuclear Fuel Project facilities, and necessary engineering and management functions within the scope of the project

  6. Participative Facility Planning for Obstetrical and Neonatal Care Processes: Beginning of Life Process

    Directory of Open Access Journals (Sweden)

    Jori Reijula

    2016-01-01

    Full Text Available Introduction. Old hospitals may promote inefficient patient care processes and safety. A new, functionally planned hospital presents a chance to create an environment that supports streamlined, patient-centered healthcare processes and adapts to users’ needs. This study depicts the phases of a facility planning project for pregnant women and newborn care processes (beginning of life process at Turku University Hospital. Materials and Methods. Project design reports and meeting documents were utilized to assess the beginning of life process as well as the work processes of the Women’s and Children’s Hospital. Results. The main elements of the facility design (FD project included rigorous preparation for the FD phase, functional planning throughout the FD process, and setting key values: (1 family-centered care, (2 Lean thinking and Lean tools as the framework for the FD process, (3 safety, and (4 cooperation. Conclusions. A well-prepared FD project with sufficient insight into functional planning, Lean thinking, and user-centricity seemed to facilitate the actual FD process. Although challenges occurred, the key values were not forgone and were successfully incorporated into the new hospital building.

  7. Pu-238 Supply Program Project Execution Plan

    International Nuclear Information System (INIS)

    Wham, Robert M.; Martin, Sherman

    2012-01-01

    This Pu-238 Supply Program Project Execution Plan (PEP) summarizes critical information and processes necessary to manage the program. The PEP is the primary agreement regarding planning and objectives between The Department of Energy Office of Nuclear Energy (DOE NE-75), Oak Ridge National Laboratory Site Office (OSO) and the Oak Ridge National Laboratory (ORNL). The acquisition executive (AE) will approve the PEP. The PEP is a living document that will be reviewed and revised periodically until the project is complete. The purpose of the project is to reestablish the capability to produce plutonium-238 (Pu-238) domestically. This capability consists primarily of procedures, processes, and design information, not capital assets. As such, the project is not subject to the requirements of DOE O 413.3B, but it will be managed using the project management principles and best practices defined there. It is likely that some capital asset will need to be acquired to complete tasks within the project. As these are identified, project controls and related processes will be updated as necessary. Because the project at its initiation was envisioned to require significant capital assets, Critical Decision 0 (CD-0) was conducted in accordance with DOE O 413.3B, and the mission need was approved on December 9, 2003, by William Magwood IV, director of the Office of Nuclear Energy (NE), Science and Technology, DOE. No date was provided for project start-up at that time. This PEP is consistent with the strategy described in the June 2010 report to Congress, Start-up Plan for Plutonium-238 Production for Radioisotope Power Systems.

  8. Multi-site risk-based project planning, optimization, sequencing and budgeting process and tool for the integrated facility disposition project - 59394

    International Nuclear Information System (INIS)

    Nelson, Jerel; Castillo, Carlos; Huntsman, Julie; Lucek, Heather; Marks, Tim

    2012-01-01

    Document available in abstract form only. Full text of publication follows: Faced with the DOE Complex Transformation, NNSA was tasked with developing an integrated plan for the decommissioning of over 400 facilities and 300 environmental remediation units, as well as the many reconfiguration and modernization projects at the Oak Ridge National Laboratory (ORNL) and Y-12 Complex. Manual scheduling of remediation activities is time-consuming, labor intensive, and inherently introduces bias and unaccounted for aspects of the scheduler or organization in the process. Clearly a tool was needed to develop an objective, unbiased baseline optimized project sequence and schedule with a sound technical foundation for the Integrated Facility Disposition Project (IFDP). In generating an integrated disposition schedule, each project (including facilities, environmental sites, and remedial action units) was identified, characterized, then ranked relative to other projects. Risk matrices allowed for core project data to be extrapolated into probable contamination levels, relative risks to the public, and other technical and risk parameters to be used in the development of an overall ranking. These matrices ultimately generated a complete data set that were used in the Ranking and Sequencing Model (RSM), commonly referred to as the SUPER model, for its numerous abilities to support D and D planning, prioritization, and sequencing

  9. Reengineering the project design process

    Science.gov (United States)

    Kane Casani, E.; Metzger, Robert M.

    1995-01-01

    In response to the National Aeronautics and Space Administration's goal of working faster, better, and cheaper, the Jet Propulsion Laboratory (JPL) has developed extensive plans to minimize cost, maximize customer and employee satisfaction, and implement small- and moderate-size missions. These plans include improved management structures and processes, enhanced technical design processes, the incorporation of new technology, and the development of more economical space- and ground-system designs. The Laboratory's new Flight Projects Implementation Development Office has been chartered to oversee these innovations and the reengineering of JPL's project design process, including establishment of the Project Design Center (PDC) and the Flight System Testbed (FST). Reengineering at JPL implies a cultural change whereby the character of the Laboratory's design process will change from sequential to concurrent and from hierarchical to parallel. The Project Design Center will support missions offering high science return, design to cost, demonstrations of new technology, and rapid development. Its computer-supported environment will foster high-fidelity project life-cycle development and more accurate cost estimating. These improvements signal JPL's commitment to meeting the challenges of space exploration in the next century.

  10. Project Hanford management contract quality improvement project management plan; TOPICAL

    International Nuclear Information System (INIS)

    ADAMS, D.E.

    1999-01-01

    On July 13, 1998, the U.S. Department of Energy, Richland Operations Office (DOE-RL) Manager transmitted a letter to Fluor Daniel Hanford, Inc. (FDH) describing several DOE-RL identified failed opportunities for FDH to improve the Quality Assurance (QA) Program and its implementation. In addition, DOE-RL identified specific Quality Program performance deficiencies. FDH was requested to establish a periodic reporting mechanism for the corrective action program. In a July 17, 1998 response to DOE-RL, FDH agreed with the DOE concerns and committed to perform a comprehensive review of the Project Hanford Management Contract (PHMC) QA Program during July and August, 1998. As a result, the Project Hanford Management Contract Quality Improvement Plan (QIP) (FDH-3508) was issued on October 21, 1998. The plan identified corrective actions based upon the results of an in-depth Quality Program Assessment. Immediately following the scheduled October 22, 1998, DOE Office of Enforcement and Investigation (EH-10) Enforcement Conference, FDH initiated efforts to effectively implement the QIP corrective actions. A Quality Improvement Project (QI Project) leadership team was assembled to prepare a Project Management Plan for this project. The management plan was specifically designed to engage a core team and the support of representatives from FDH and the major subcontractors (MSCs) to implement the QIP initiatives; identify, correct, and provide feedback as to the root cause for deficiency; and close out the corrective actions. The QI Project will manage and communicate progress of the process

  11. Project planning and project management of Baseball II-T

    International Nuclear Information System (INIS)

    Kozman, T.A.; Chargin, A.K.

    1975-01-01

    The details of the project planning and project management work done on the Baseball II-T experiment are reviewed. The LLL Baseball program is a plasma confinement experiment accomplished with a superconducting magnet in the shape of a baseball seam. Both project planning and project management made use of the Critical Path Management (CPM) computer code. The computer code, input, and results from the project planning and project management runs, and the cost and effectiveness of this method of systems planning are discussed

  12. Project structure plan requirements for the deconstruction projects

    International Nuclear Information System (INIS)

    Petrasch, Peter; Schmitt, Christian; Stapf, Meike

    2011-01-01

    The deconstruction of nuclear facilities requires due to the particular conditions and the size of the project a special project planning. The authors analyze the possible requirements to be fulfilled by a project structure plan for nuclear facilities, including personnel resources, organization structure, budget questions, operation and project oriented measures, possibility of modifications and supplements. Further topics include controlling and project realization procedures, documentation, third party activities (authorities, consultants, surveyors), logistics and transport, and radiation protection issues. Several questions remain for plants-specific planning, including the integration of the plant personnel, administrative work, project management, economic and financial issues, radioactive waste management issues.

  13. Comprehensive Evaluation of Large Infrastructure Project Plan with ANP

    Institute of Scientific and Technical Information of China (English)

    HAN Chuan-feng; CHEN Jian-ye

    2005-01-01

    Analytic Network Process(ANP) was used in comprehensive evaluation of large infrastructure project plan. A model including social economy, ecological environment, and resources was established with ANP method. The evaluation pattern of hierarchy structure and comprehensive evaluation method for quantity and quality of large infrastructure project were put forward, which provides an effective way to evaluate the large infrastructure project plan. Quantitative analysis indicated that the internal dependence relation of hierarchy structure has influence on ranking results of plan. It is suggested that considering the internal relation can helps managers make effective decisions.

  14. Wind energy planning in England, Wales and Denmark: Factors influencing project success

    International Nuclear Information System (INIS)

    McLaren Loring, Joyce

    2007-01-01

    Land-use planning poses a significant barrier to the further development of on-shore wind energy in many countries. There has been increasing discussion regarding the use of public participation in the planning process in order to address concerns of local residents and ease conflicts. This research explores the dynamics of the planning process for wind energy in England, Wales and Denmark in order to better understand the factors influencing project success. Through 18 in-depth case studies, it investigates the degree of local community participation in the planning process and the stability of the network of individuals and organisations involved in the project to determine their relationship to the public's acceptance of the project and the planning outcome. The study draws on the frameworks of public participation in planning and actor-network theories in order to develop indicators of the level of community involvement and network formation for each case. The analysis discusses predictions made by the theoretical approaches as to the importance of these variables to the success of new projects. The results indicate that projects with high levels of participatory planning are more likely to be publicly accepted and successful. In addition, stable supporting networks are more likely to form. The presence of a stable network of supporters is not found to be related to project acceptance and success; however, the absence of a stable network of opponents is found to be necessary for project acceptance and success in receiving planning permission

  15. Process simulation and parametric modeling for strategic project management

    CERN Document Server

    Morales, Peter J

    2013-01-01

    Process Simulation and Parametric Modeling for Strategic Project Management will offer CIOs, CTOs and Software Development Managers, IT Graduate Students an introduction to a set of technologies that will help them understand how to better plan software development projects, manage risk and have better insight into the complexities of the software development process.A novel methodology will be introduced that allows a software development manager to better plan and access risks in the early planning of a project.  By providing a better model for early software development estimation and softw

  16. Automated Procurement System (APS): Project management plan (DS-03), version 1.2

    Science.gov (United States)

    Murphy, Diane R.

    1994-01-01

    The National Aeronautics and Space Administration (NASA) Marshall Space Flight Center (MSFC) is implementing an Automated Procurement System (APS) to streamline its business activities that are used to procure goods and services. This Project Management Plan (PMP) is the governing document throughout the implementation process and is identified as the APS Project Management Plan (DS-03). At this point in time, the project plan includes the schedules and tasks necessary to proceed through implementation. Since the basis of APS is an existing COTS system, the implementation process is revised from the standard SDLC. The purpose of the PMP is to provide the framework for the implementation process. It discusses the roles and responsibilities of the NASA project staff, the functions to be performed by the APS Development Contractor (PAI), and the support required of the NASA computer support contractor (CSC). To be successful, these three organizations must work together as a team, working towards the goals established in this Project Plan. The Project Plan includes a description of the proposed system, describes the work to be done, establishes a schedule of deliverables, and discusses the major standards and procedures to be followed.

  17. Project licensing plan for UMTRA [Uranium Mill Tailings Remedial Action] sites

    International Nuclear Information System (INIS)

    1984-07-01

    The purpose of the Uranium Mill Tailings Remedial Action (UMTRA) Project Licensing Plan is to establish how a disposal site will be licensed, and to provide responsibilities of participatory agencies as legislated by the Uranium Mill Tailings Radiation Control Act (UMTRCA) of 1978 (Public Law 95-604). This Plan has been developed to ensure that the objectives of licensing are met by identifying the necessary institutional controls, participatory agency responsibilities, and key milestones in the licensing process. The Plan contains the legislative basis for and a description of the licensing process (''Process'') for UMTRA sites. This is followed by a discussion of agency responsibilities, and milestones in the Process. The Plan concludes with a generic timeline of this Process. As discussed in Section 2.1, a custodial maintenance and surveillance plan will constitute the basis for a site license. The details of maintenance and surveillance are discussed in the Project Maintenance and Surveillance Plan (AL-350124.0000). 5 refs., 4 figs

  18. The CHPRC Columbia River Protection Project Quality Assurance Project Plan

    International Nuclear Information System (INIS)

    Fix, N.J.

    2008-01-01

    Pacific Northwest National Laboratory researchers are working on the CHPRC Columbia River Protection Project (hereafter referred to as the Columbia River Project). This is a follow-on project, funded by CH2M Hill Plateau Remediation Company, LLC (CHPRC), to the Fluor Hanford, Inc. Columbia River Protection Project. The work scope consists of a number of CHPRC funded, related projects that are managed under a master project (project number 55109). All contract releases associated with the Fluor Hanford Columbia River Project (Fluor Hanford, Inc. Contract 27647) and the CHPRC Columbia River Project (Contract 36402) will be collected under this master project. Each project within the master project is authorized by a CHPRC contract release that contains the project-specific statement of work. This Quality Assurance Project Plan provides the quality assurance requirements and processes that will be followed by the Columbia River Project staff

  19. The CHPRC Columbia River Protection Project Quality Assurance Project Plan

    Energy Technology Data Exchange (ETDEWEB)

    Fix, N. J.

    2008-11-30

    Pacific Northwest National Laboratory researchers are working on the CHPRC Columbia River Protection Project (hereafter referred to as the Columbia River Project). This is a follow-on project, funded by CH2M Hill Plateau Remediation Company, LLC (CHPRC), to the Fluor Hanford, Inc. Columbia River Protection Project. The work scope consists of a number of CHPRC funded, related projects that are managed under a master project (project number 55109). All contract releases associated with the Fluor Hanford Columbia River Project (Fluor Hanford, Inc. Contract 27647) and the CHPRC Columbia River Project (Contract 36402) will be collected under this master project. Each project within the master project is authorized by a CHPRC contract release that contains the project-specific statement of work. This Quality Assurance Project Plan provides the quality assurance requirements and processes that will be followed by the Columbia River Project staff.

  20. ERD UMTRA Project quality assurance program plan, Revision 7

    International Nuclear Information System (INIS)

    1995-09-01

    This document is the revised Quality Assurance Program Plan (QAPP) dated September, 1995 for the Environmental Restoration Division (ERD) Uranium Mill Tailings Remedial Action Project (UMTRA). Quality Assurance requirements for the ERD UMTRA Project are based on the criteria outlined in DOE Order 5700.6C or applicable sections of 10 CFR 830.120. QA requirements contained in this QAPP shall apply to all personnel, processes, and activities, including planning, scheduling, and cost control, performed by the ERD UMTRA Project and its contractors

  1. IX Disposition Project - project management plan

    International Nuclear Information System (INIS)

    Choi, I.G.

    1994-01-01

    This report presents plans for resolving saving and disposal concerns for ion exchange modules, cartridge filters and columns. This plan also documents the project baselines for schedules, cost, and technical information

  2. Selection of projects in the regional energy planning

    International Nuclear Information System (INIS)

    Ramirez P, R.; Navas M, F.

    1993-01-01

    The processes of regional energy planning have changed vastly in the last years and it will continue changing in the future for the new norm of the State. This work tries to show the use of systematic tools in the selection of regional energy projects. It discusses a methodology of selection of projects based on a multivariate technical. It is applied in the Southwestern region of Colombia and both selection and priority results are obtained. The designed methodology allows to make the selection of projects in an automatic way with a software designed for such an end. In the case of Southwestern it arrives to a briefcase of projects for an energy plan and made for other races

  3. 2015 Plan. Project 1: methodology and planning process of the Brazilian electric sector expansion

    International Nuclear Information System (INIS)

    1993-10-01

    The Planning Process of Brazilian Electric Sector Expansion, their normative aspects, instruments, main agents and the planning cycles are described. The methodology of expansion planning is shown, with the interactions of several study areas, electric power market and the used computer models. The forecasts of methodology evolution is also presented. (C.G.C.)

  4. CQI project improves discharge process.

    Science.gov (United States)

    1998-08-01

    At Gibson Rehab Center in Williamsport, PA, a continuous quality improvement project to bolster the institution's discharge planning process has resulted in increased satisfaction and an award for quality. The 15-month project was spearheaded by a multidisciplinary team charged with identifying areas that had a significant impact on customer service and suggesting better ways of delivering that service. Among the changes the group suggested were establishing a weekly discharge planning group for new neuro patients, assigning a discharge coordinator for each treatment team, and creating an interdisciplinary communication sheet for the home health therapy staff.

  5. Project implementation plan: ASTD remote deployment

    International Nuclear Information System (INIS)

    CRASS, D.W.

    1999-01-01

    This document is the project implementation plan for the ASTD Remote Deployment Project. The Plan identifies the roles and responsibilities for the project and defines the integration between the ASTD Project and the B-Cell Cleanout Project

  6. Project Management Plan for the INEL technology logic diagrams

    International Nuclear Information System (INIS)

    Rudin, M.J.

    1992-10-01

    This Project Management Plan (PjMP) describes the elements of project planning and control that apply to activities outlined in Technical Task Plan (TTP) ID-121117, ''Technology Logic Diagrams For The INEL.'' The work on this project will be conducted by personnel in EG ampersand G Idaho, Inc.'s Waste Technology Development Program. Technology logic diagrams represent a formal methodology to identify technology gaps or needs within Environmental Restoration/Waste Management Operations, which will focus on Office of Environmental Restoration and Waste Management (EM-50) research and development, demonstration, test, and evaluation efforts throughout the US Department of Energy complex. This PjMP describes the objectives, organization, roles and responsibilities, workscope and processes for implementing and managing the technology logic diagram for the Idaho National Engineering Laboratory project

  7. A Microsoft Project-Based Planning, Tracking, and Management Tool for the National Transonic Facility's Model Changeover Process

    Science.gov (United States)

    Vairo, Daniel M.

    1998-01-01

    The removal and installation of sting-mounted wind tunnel models in the National Transonic Facility (NTF) is a multi-task process having a large impact on the annual throughput of the facility. Approximately ten model removal and installation cycles occur annually at the NTF with each cycle requiring slightly over five days to complete. The various tasks of the model changeover process were modeled in Microsoft Project as a template to provide a planning, tracking, and management tool. The template can also be used as a tool to evaluate improvements to this process. This document describes the development of the template and provides step-by-step instructions on its use and as a planning and tracking tool. A secondary role of this document is to provide an overview of the model changeover process and briefly describe the tasks associated with it.

  8. Next Generation Nuclear Plant Project Preliminary Project Management Plan

    International Nuclear Information System (INIS)

    Dennis J. Harrell

    2006-01-01

    This draft preliminary project management plan presents the conceptual framework for the Next Generation Nuclear Plant (NGNP) Project, consistent with the authorization in the Energy Policy Act of 2005. In developing this plan, the Idaho National Laboratory has considered three fundamental project planning options that are summarized in the following section. Each of these planning options is literally compliant with the Energy Policy Act of 2005, but each emphasizes different approaches to technology development risks, design, licensing and construction risks, and to the extent of commercialization support provided to the industry. The primary focus of this draft preliminary project management plan is to identify those activities important to Critical Decision-1, at which point a decision on proceeding with the NGNP Project can be made. The conceptual project framework described herein is necessary to establish the scope and priorities for the technology development activities. The framework includes: A reference NGNP prototype concept based on what is judged to be the lowest risk technology development that would achieve the needed commercial functional requirements to provide an economically competitive nuclear heat source and hydrogen production capability. A high-level schedule logic for design, construction, licensing, and acceptance testing. This schedule logic also includes an operational shakedown period that provides proof-of-principle to establish the basis for commercialization decisions by end-users. An assessment of current technology development plans to support Critical Decision-1 and overall project progress. The most important technical and programmatic uncertainties (risks) are evaluated, and potential mitigation strategies are identified so that the technology development plans may be modified as required to support ongoing project development. A rough-order-of-magnitude cost evaluation that provides an initial basis for budget planning. This

  9. Project Planning and Control in a Developing Economy: Implementation and Realisation

    Directory of Open Access Journals (Sweden)

    H. Abdul-Rahman

    2005-12-01

    Full Text Available In the competitive and uncertain environment of the construction industry, the ability to deliver end products with the required quality, schedule and budget is vital to the survival of any construction-related firm. Before embarking on any project, realistic planning and, consequently, a control procedure must be in place to enable the parties to manage the project with sufficient degree of authority and certainty. This paper addresses issues associated with the implementation of project planning and control, identificati on of impacts in the implementation of project planning and the critical success factors of project planning. A questionnaire survey was conducted on construction professionals and contractors involved in the running of construction projects. The survey results showed that common problems associated with the project planning and control are the lack of experienced staff and poor coordination by the contractor. During site operation, a delay in decision making aggravates the effect of poor planning and control and much of the effect of project planning rests on the pro-activeness of experienced staff. The positive impact associated with proper planning and control is the high probability of finishing the project on time while the negative impact is that it is a time-consuming and costly process. The critical success factors identified from the survey are Excellent Teamwork and Experienced Team.

  10. Project No. 8 - Final decommissioning plan

    International Nuclear Information System (INIS)

    2000-01-01

    Ignalina NPP should prepare the final Ignalina NPP unit 1 decommissioning plan by march 31, 2002. This plan should include the following : description of Ignalina NPP and the Ignalina NPP boundary that could be influenced by decommissioning process; decommissioning strategy selected and a logical substantiation for this selection; description of the decommissioning actions suggested and a time schedule for the actions to be performed; conceptual safety and environmental impact assessment covering ionizing radiation and other man and environment impact; description of the environmental monitoring program proposed during decommissioning process; description of the waste management proposed; assessment of decommissioning expenses including waste management, accumulated funds and other sources. Estimated project cost - 0.75 M EURO

  11. THE SYSTEM OF PROCESSES AND PROJECTS OF THE AIRCRAFT AIRWORTHINESS MAINTENANCE

    Directory of Open Access Journals (Sweden)

    Alexander A. Itskovich

    2018-01-01

    Full Text Available The concept of the aviation enterprise as a unified system of processes and projects of the aircraft airworthiness maintenance (AAM is presented. The relevance of project management tools usage, including the transport branch, is noted; the examples of successful implementation of the development projects at domestic enterprises manufacturing aircraft engines are given. A scheme for the classification of the AAM projects and processes, reflecting their interrelationship, is proposed. The operational activity of the enterprise is a combination of its business processes. The company selects plans and implements the relevant projects for the business processes optimization. At the same time, the projects themselves are the objects of management based on standardized processes. The processes of project management and the main processes of the enterprise are also interrelated and can be objects included in the unified regulations of its units. Increasing the efficiency of operational processes and processes of the aviation enterprise management is the goal of development projects, which are divided into investment projects and organizational changes projects.Limitation of organizational and financial resources of the company requires the identification and systematization of all projects and processes, while the application of project management standards allows to analyze the opportunities and to determine the sequence of their implementation. The importance of accumulating experience of completed projects is shown; the results can become typical methods for planning, organizing the implementation and monitoring of AAM projects. Specific forms of the project management standards implementation for AN-124-100 constructive modification project in LLC Volga-Dnepr Airlines are demonstrated: the control events plan and the project team formation.

  12. Resource Constrained Planning of Multiple Projects with Separable Activities

    Science.gov (United States)

    Fujii, Susumu; Morita, Hiroshi; Kanawa, Takuya

    In this study we consider a resource constrained planning problem of multiple projects with separable activities. This problem provides a plan to process the activities considering a resource availability with time window. We propose a solution algorithm based on the branch and bound method to obtain the optimal solution minimizing the completion time of all projects. We develop three methods for improvement of computational efficiency, that is, to obtain initial solution with minimum slack time rule, to estimate lower bound considering both time and resource constraints and to introduce an equivalence relation for bounding operation. The effectiveness of the proposed methods is demonstrated by numerical examples. Especially as the number of planning projects increases, the average computational time and the number of searched nodes are reduced.

  13. Systems Engineering Plan and project record Configuration Management Plan for the Mixed Waste Disposal Initiative

    International Nuclear Information System (INIS)

    Bryan, W.E.; Oakley, L.B.

    1993-04-01

    This document summarizes the systems engineering assessment that was performed for the Mixed Waste Disposal Initiative (MWDI) Project to determine what types of documentation are required for the success of the project. The report also identifies the documents that will make up the MWDI Project Record and describes the Configuration Management Plan describes the responsibilities and process for making changes to project documentation

  14. Education Projects: Elaboration, Financing and Management. Fundamentals of Educational Planning, No. 38.

    Science.gov (United States)

    Magnen, Andre

    In many developing countries, the translation of political objectives to action projects is made difficult by the lack of training of staff of the ministry of education planning and managing units. This booklet deals with the implementation of these projects within the framework of the planning process. After defining projects, chapter 1 shows the…

  15. Project Management Plan for Material Stabilization

    International Nuclear Information System (INIS)

    SPEER, D.R.

    1999-01-01

    This plan presents the overall objectives, description, justification and planning for the plutonium Finishing Plant (PFP) Materials Stabilization project. The intent of this plan is to describe how this project will be managed and integrated with other facility stabilization and deactivation activities. This plan supplements the overall integrated plan presented in the Plutonium Finishing Plant Integrated Project Management Plan (IPMP), HNF-3617/Rev. 0. This is the top-level definitive project management document that specifies the technical (work scope), schedule, and cost baselines to manager the execution of this project. It describes the organizational approach and roles/responsibilities to be implemented to execute the project. This plan is under configuration management and any deviations must be authorized by appropriate change control action. Materials stabilization is designated the responsibility to open and stabilize containers of plutonium metal, oxides, alloys, compounds, and sources. Each of these items is at least 30 weight percent plutonium/uranium. The output of this project will be containers of materials in a safe and stable form suitable for storage pending final packaging and/or transportation offsite. The corrosion products along with oxides and compounds will be stabilized via muffle furnaces to reduce the materials to high fired oxides

  16. Project Execution Plan, Rev. 3

    International Nuclear Information System (INIS)

    IT Corporation, Las Vegas

    2002-01-01

    This plan addresses project activities encompassed by the U.S. Department of Energy's (DOE's), National Nuclear Security Administration Nevada Operations Office, Environmental Restoration Division and conforms to the requirements contained in the Life-Cycle Asset Management, DOE Order 430.1A; The Joint Program Office Policy on Project Management in Support of DOE Order 430.1; Program and Project Management for the Acquisition of Capital Assets, DOE Order 413.3; the Project Execution and Engineering Management Planning Guide, GPG-FM-010; and other applicable Good Practice Guides; and the FY 2001 Integrated Planning, Accountability, and Budgeting System Policy Guidance. The plan also reflects the milestone philosophies of the Federal Facility Agreement and Consent Order, as agreed to by the State of Nevada, the DOE, and the U.S. Department of Defense; and traditional project management philosophies such as the development of life-cycle costs, schedules, and work scope; identification o f roles and responsibilities; and baseline management and controls

  17. Environmental Restoration Project - Systems Engineering Management Plan

    International Nuclear Information System (INIS)

    Anderson, T.D.

    1998-06-01

    This Environmental Restoration (ER) Project Systems Engineering Management Plan (SEMP) describes relevant Environmental Restoration Contractor (ERC) management processes and shows how they implement systems engineering. The objective of this SEMP is to explain and demonstrate how systems engineering is being approached and implemented in the ER Project. The application of systems engineering appropriate to the general nature and scope of the project is summarized in Section 2.0. The basic ER Project management approach is described in Section 3.0. The interrelation and integration of project practices and systems engineering are outlined in Section 4.0. Integration with sitewide systems engineering under the Project Hanford Management Contract is described in Section 5.0

  18. Spent Nuclear Fuel Project Document Management Plan

    International Nuclear Information System (INIS)

    Connor, M.D.; Harizison, G.L.; Rice, W.C.

    1995-12-01

    The SNF Project Document Management Plan identifies and describes the currently available systems and processes for implementing and maintaining an effective document control and records management program. This program governs the methods by which documents are generated, released, distributed, maintained current, retired, and ultimately disposed

  19. Quality assurance program plan for cesium legacy project

    International Nuclear Information System (INIS)

    Tanke, J.M.

    1997-01-01

    This Quality Assurance Program Plan (QAPP) provides information on how the Quality Assurance Program is implemented for the Cesium Legacy Project. It applies to those items and tasks which affect the completion of activities identified in the work breakdown structure of the Project Management Plan (PMP). These activities include all aspects of cask transportation, project related operations within the 324 Building, and waste management as it relates to the specific activities of this project. General facility activities (i.e. 324 Building Operations, Central Waste Complex Operations, etc.) are covered in other appropriate QAPPs. The 324 Building is currently transitioning from being a Pacific Northwest National Laboratory (PNNL) managed facility to a B and W Hanford Company (BWHC) managed facility. During this transition process existing PNNL procedures and documents will be utilized until replaced by BWHC procedures and documents

  20. Project Specific Quality Assurance Plan

    International Nuclear Information System (INIS)

    Pedersen, K.S.

    1995-01-01

    This Quality Assurance Project Plan (QAPP) identifies the Westinghouse Hanford Co. (WHC) Quality Assurance (QA) program requirements for all contractors involved in the planning and execution of the design, construction, testing and inspection of the 200 Area Effluent BAT/AKART Implementation, Project W-291

  1. Systems Engineering Implementation Plan for Single-Shell Tanks (SST) Retrieval Projects

    International Nuclear Information System (INIS)

    LEONARD, M.W.; HOFFERBER, G.A.

    2000-01-01

    This document communicates the planned implementation of the Systems Engineering processes and products for the SST retrieval projects as defined in the Systems Engineering Management Plan for the Tank Farm Contractor

  2. Systems Engineering Implementation Plan for Single Shell Tanks (SST) Retrieval Projects

    Energy Technology Data Exchange (ETDEWEB)

    LEONARD, M.W.; HOFFERBER, G.A.

    2000-11-30

    This document communicates the planned implementation of the Systems Engineering processes and products for the SST retrieval projects as defined in the Systems Engineering Management Plan for the Tank Farm Contractor.

  3. Pre-Project planning of Capital Facilities at NASA

    OpenAIRE

    Barrow, Benjamin John

    1999-01-01

    This thesis details the development of a NASA specific Project Definition Rating Index (PDRI) tool. This tool is to be used as a checklist for determining the necessary steps to follow in defining project scope and as a means to monitor progress and assess scope definition completeness at various stages during the NASA Pre-Project Planning process. This thesis also describes and identifies specific points in the NASA Capital Facility Programming Cycle for the performance of PDRI assessments ...

  4. A planning and scheduling system for the LHC project

    CERN Document Server

    Bachy, Gérard; Tarrant, M

    1995-01-01

    The purpose of this paper is to present modern ways to manage time, resources and progress in a large-scale project. Over the last ten years, new project management techniques and tools have appeared such as concurrent engineering, Continuous Acquisition Lifecycle Support (CALS) and Engineering Data Management System (EDMS). The world downturn of the early 90s influenced project management: increasing constraints on time and budget and more external direction on spending that, for example, requires sophisticated sub-contracting practises. However, the evolution of the software and hardware market makes project control tools cheaper and easier to use. All project groups want to have their scope of work considered as complete projects and to control them themselves. This has several consequences on project staff behaviour concerning project control, and has to be taken into account in every planning process designed today. The system described will be at the heart of the planning and scheduling procedures issue...

  5. Cesium legacy safety project management work plan

    International Nuclear Information System (INIS)

    Durham, J.S.

    1998-01-01

    This Management Work Plan (MWP) describes the process flow, quality assurance controls, and the Environment, Safety, and Health requirements of the Cesium Legacy Safety Project. This MWP provides an overview of the project goals and methods for repackaging the non-conforming Type W overpacks and packaging the CsCl powder and pellets. This MWP is not intended to apply to other activities associated with the CsCl Legacy Safety Program (i.e., clean out of South Cell)

  6. Evaluation of Urban Planning Projects Criteria Using Fuzzy AHP Technique

    Directory of Open Access Journals (Sweden)

    Walid Mustafa Kamas

    2017-05-01

    Full Text Available In this research, Fuzzy Analytic Hierarchy Process technique is applied (Fuzzy AHP which is one of multi-criteria decision making techniques to evaluate the criteria for urban planning projects, the project of developing master plan of Al-Muqdadiyah city to 2035 has been chosen as a case study. The researcher prepared a list of criteria in addition to the authorized departments criteria and previous researches in order to choose optimized master plan according to these criteria. This research aims at employing the foundations of (Fuzzy AHP technique in evaluating urban planning criteria precisely and flexible. The results of the data analysis to the individuals of the sample who are specialists, in this aspect. The land use criteria are more important than the rest of the criteria in these projects, where it received the relative importance with percentile (42.1 %.

  7. Business System Planning Project, Alternatives Analysis

    International Nuclear Information System (INIS)

    EVOSEVICH, S.

    2000-01-01

    The CHG Chief Information Officer (CIO) requested a study of alternatives to the current business system computing environment. This Business Systems Planning (BSP) Project Alternatives Analysis document presents an analysis of the current Project Controls, Work Management, and Business Management systems environment and alternative solutions that support the business functions. The project team has collected requirements and priorities from stakeholders in each business area and documented them in the BSP System Requirements Specification (SRS), RPP-6297. The alternatives analysis process identifies and measures possible solutions in each of the business process areas against the requirements as documented in the SRS. The team gathered input from both internal and external sources to identify and grade the possible solutions. This document captures the results of that activity and recommends a suite of software products. This study was to select the best product based on how well the product met the requirements, not to determine the platform or hardware environment that would be used. Additional analysis documentation can be found in BSP project files

  8. Adoption of Building Information Modelling in project planning risk management

    Science.gov (United States)

    Mering, M. M.; Aminudin, E.; Chai, C. S.; Zakaria, R.; Tan, C. S.; Lee, Y. Y.; Redzuan, A. A.

    2017-11-01

    An efficient and effective risk management required a systematic and proper methodology besides knowledge and experience. However, if the risk management is not discussed from the starting of the project, this duty is notably complicated and no longer efficient. This paper presents the adoption of Building Information Modelling (BIM) in project planning risk management. The objectives is to identify the traditional risk management practices and its function, besides, determine the best function of BIM in risk management and investigating the efficiency of adopting BIM-based risk management during the project planning phase. In order to obtain data, a quantitative approach is adopted in this research. Based on data analysis, the lack of compliance with project requirements and failure to recognise risk and develop responses to opportunity are the risks occurred when traditional risk management is implemented. When using BIM in project planning, it works as the tracking of cost control and cash flow give impact on the project cycle to be completed on time. 5D cost estimation or cash flow modeling benefit risk management in planning, controlling and managing budget and cost reasonably. There were two factors that mostly benefit a BIM-based technology which were formwork plan with integrated fall plan and design for safety model check. By adopting risk management, potential risks linked with a project and acknowledging to those risks can be identified to reduce them to an acceptable extent. This means recognizing potential risks and avoiding threat by reducing their negative effects. The BIM-based risk management can enhance the planning process of construction projects. It benefits the construction players in various aspects. It is important to know the application of BIM-based risk management as it can be a lesson learnt to others to implement BIM and increase the quality of the project.

  9. Risk Management Plan for Tank Farm Restoration and Safe Operations, Project W-314

    International Nuclear Information System (INIS)

    MCGREW, D.L.

    2000-01-01

    The Risk Management Plan for Project W-314 describes the systems, processes and procedures for implementation of applicable risk management practices described in HNF-0842, Volume IV, Section 2.6, ''Risk Management''. This plan is tailored specifically for use by Project W-314

  10. Systems engineering management plan for the Salt Repository Project

    International Nuclear Information System (INIS)

    Neff, J.O.

    1986-08-01

    This document presents the plan for using systems engineering in conducting and managing the technical work of the Salt Repository Project (SRP) of the US Department of Energy's Civilian Radioactive Waste Management Program. The need for preparing a Systems Engineering Management Plan (SEMP) is traced back to relevant DOE directives. These directives are interpreted as SRP requirements in the context of the Mined Geologic Disposal System. The strategy for conducting systems engineering on the SRP, including the role of the systems engineering process, is then described. The SEMP also designates who in the project organization will be responsible for carrying out the activities. Finally, the management tools that are used to implement the systems engineering process, including associated documentation on the SRP, are described

  11. Achieving Smart Energy Planning Objectives. The Approach of the Transform Project

    Directory of Open Access Journals (Sweden)

    Ilaria Delponte

    2014-05-01

    Full Text Available Cities play a dual role in the field of energy and integrated planning. They function as institutional planning and decision making bodies and interfere as actors, e.g. as project developers or launching customers. In the first case their attempts at integrated plans are often unsuccessful in integrating vision, goals and instruments of all stakeholders so that waste, water, energy cycles, urban planning and budgets proceed with no connection to each other.  TRANSFORM Project “Transformation Agenda for Low Carbon Cities” (FP7 tries to improve the integrated energy policy and decision making process of cities, both at a strategic and operational level, by providing the cities with a framework based on overall planning experiences and on-the-field projects and qualitative and quantitative analysis support models. The project intends also to make a step further in the quality of research, by providing a replicable and tested framework for the production of a strategic Transformation Agenda for the city as a whole, combined with district Implementation Plans.

  12. Business System Planning Project, Preliminary System Design

    International Nuclear Information System (INIS)

    EVOSEVICH, S.

    2000-01-01

    CH2M HILL Hanford Group, Inc. (CHG) is currently performing many core business functions including, but not limited to, work control, planning, scheduling, cost estimating, procurement, training, and human resources. Other core business functions are managed by or dependent on Project Hanford Management Contractors including, but not limited to, payroll, benefits and pension administration, inventory control, accounts payable, and records management. In addition, CHG has business relationships with its parent company CH2M HILL, U.S. Department of Energy, Office of River Protection and other River Protection Project contractors, government agencies, and vendors. The Business Systems Planning (BSP) Project, under the sponsorship of the CH2M HILL Hanford Group, Inc. Chief Information Officer (CIO), have recommended information system solutions that will support CHG business areas. The Preliminary System Design was developed using the recommendations from the Alternatives Analysis, RPP-6499, Rev 0 and will become the design base for any follow-on implementation projects. The Preliminary System Design will present a high-level system design, providing a high-level overview of the Commercial-Off-The-Shelf (COTS) modules and identify internal and external relationships. This document will not define data structures, user interface components (screens, reports, menus, etc.), business rules or processes. These in-depth activities will be accomplished at implementation planning time

  13. Planning and Managing Drupal Projects

    CERN Document Server

    Nordin, Dani

    2011-01-01

    If you're a solo website designer or part of a small team itching to build interesting projects with Drupal, this concise guide will get you started. Drupal's learning curve has thrown off many experienced designers, particularly the way it handles design challenges. This book shows you the lifecycle of a typical Drupal project, with emphasis on the early stages of site planning. Learn how to efficiently estimate and set up your own project, so you can focus on ways to make your vision a reality, rather than let project management details constantly distract you. Plan and estimate your projec

  14. Research Planning and Evaluation Project

    International Nuclear Information System (INIS)

    Song, Seunghyun; Kim, Doyang; Ryu, Byunghoon; Lim, Chaeyoung; Song, Leeyoung; Lee, Youngchul; Han, Changsun; Kim, Hackchoon

    2011-12-01

    - To activate R and D through a systematic and impartial evaluation by using information on efficient distribution of research resource, setting project priorities, and measuring achievement against goals produced after research on planning and evaluation system for the government-funded project for KAERI was conducted. - Nuclear R and D project is the representative national R and D project which has been implemented in Korea. For the sustainable development of nuclear energy which supplies about 40% of total electricity generation and the enhancement of it innovative ability in the future, a systematic and efficient strategy in the planning stage is required

  15. Columbia Basin Wildlife Mitigation Project : Rainwater Wildlife Area Final Management Plan.

    Energy Technology Data Exchange (ETDEWEB)

    Childs, Allen

    2002-03-01

    This Draft Management Plan has been developed by the Confederated Tribes of the Umatilla Indian Reservation (CTUIR) to document how the Rainwater Wildlife Area (formerly known as the Rainwater Ranch) will be managed. The plan has been developed under a standardized planning process developed by the Bonneville Power Administration (BPA) for Columbia River Basin Wildlife Mitigation Projects (See Appendix A and Guiding Policies Section below). The plan outlines the framework for managing the project area, provides an assessment of existing conditions and key resource issues, and presents an array of habitat management and enhancement strategies. The plan culminates into a 5-Year Action Plan that will focus our management actions and prioritize funding during the Fiscal 2001-2005 planning period. This plan is a product of nearly two years of field studies and research, public scoping, and coordination with the Rainwater Advisory Committee. The committee consists of representatives from tribal government, state agencies, local government, public organizations, and members of the public. The plan is organized into several sections with Chapter 1 providing introductory information such as project location, purpose and need, project goals and objectives, common elements and assumptions, coordination efforts and public scoping, and historical information about the project area. Key issues are presented in Chapter 2 and Chapter 3 discusses existing resource conditions within the wildlife area. Chapter 4 provides a detailed presentation on management activities and Chapter 5 outlines a monitoring and evaluation plan for the project that will help assess whether the project is meeting the intended purpose and need and the goals and objectives. Chapter 6 displays the action plan and provides a prioritized list of actions with associated budget for the next five year period. Successive chapters contain appendices, references, definitions, and a glossary.

  16. Decommissioning plan - decommissioning project for KRR 1 and 2 (revised)

    Energy Technology Data Exchange (ETDEWEB)

    Jung, K. J.; Paik, S. T.; Chung, U. S.; Jung, K. H.; Park, S. K.; Lee, D. G.; Kim, H. R.; Kim, J. K.; Yang, S. H.; Lee, B. J

    2000-10-01

    This report is the revised Decommissioning Plan for the license of TRIGA research reactor decommissioning project according to Atomic Energy Act No. 31 and No. 36. The decommissioning plan includes the TRIGA reactor facilities, project management, decommissioning method, decontamination and dismantling activity, treatment, packaging, transportation and disposal of radioactive wastes. the report also explained the radiation protection plan and radiation safety management during the decommissioning period, and expressed the quality assurance system during the period and the site restoration after decommissioning. The first decommissioning plan was made by Hyundai Engineering Co, who is the design service company, was submitted to the Ministry of Science and Technology, and then was reviewed by the Korea Institute of Nuclear Safety. The first decommissioning plan was revised including answers for the questions arising from review process.

  17. Decommissioning plan - decommissioning project for KRR 1 and 2 (revised)

    International Nuclear Information System (INIS)

    Jung, K. J.; Paik, S. T.; Chung, U. S.; Jung, K. H.; Park, S. K.; Lee, D. G.; Kim, H. R.; Kim, J. K.; Yang, S. H.; Lee, B. J.

    2000-10-01

    This report is the revised Decommissioning Plan for the license of TRIGA research reactor decommissioning project according to Atomic Energy Act No. 31 and No. 36. The decommissioning plan includes the TRIGA reactor facilities, project management, decommissioning method, decontamination and dismantling activity, treatment, packaging, transportation and disposal of radioactive wastes. the report also explained the radiation protection plan and radiation safety management during the decommissioning period, and expressed the quality assurance system during the period and the site restoration after decommissioning. The first decommissioning plan was made by Hyundai Engineering Co, who is the design service company, was submitted to the Ministry of Science and Technology, and then was reviewed by the Korea Institute of Nuclear Safety. The first decommissioning plan was revised including answers for the questions arising from review process

  18. SRP [Salt Repository Project] configuration management plan

    International Nuclear Information System (INIS)

    1987-01-01

    This configuration management plan describes the organization, policies, and procedures that will be used on the Salt Repository Project (SRP) to implement the configuration management disciplines and controls. Configuration management is a part of baseline management. Baseline management is defined in the SRP Baseline Procedures Notebook and also includes cost and schedule baselines. Configuration management is a discipline applying technical and administrative direction and surveillance to identify and document the functional and physical characteristics of an item, to control changes to those characteristics, to record and report change processing and implementation status, and to audit the results. Configuration management is designed as a project management tool to determine and control baselines, and ensure and document all components of a project interface both physically and functionally. The purpose is to ensure that the product acquired satisfies the project's technical and operational requirements, and that the technical requirements are clearly defined and controlled throughout the development and acquisition process. 5 figs

  19. Project Execution Plan,Rev. 3; FINAL

    International Nuclear Information System (INIS)

    IT Corporation, Las Vegas

    2002-01-01

    This plan addresses project activities encompassed by the U.S. Department of Energy's (DOE's), National Nuclear Security Administration Nevada Operations Office, Environmental Restoration Division and conforms to the requirements contained in the Life-Cycle Asset Management, DOE Order 430.1A; The Joint Program Office Policy on Project Management in Support of DOE Order 430.1; Program and Project Management for the Acquisition of Capital Assets, DOE Order 413.3; the Project Execution and Engineering Management Planning Guide, GPG-FM-010; and other applicable Good Practice Guides; and the FY 2001 Integrated Planning, Accountability, and Budgeting System Policy Guidance. The plan also reflects the milestone philosophies of the Federal Facility Agreement and Consent Order, as agreed to by the State of Nevada, the DOE, and the U.S. Department of Defense; and traditional project management philosophies such as the development of life-cycle costs, schedules, and work scope; identification o f roles and responsibilities; and baseline management and controls

  20. Safety risk assessment using analytic hierarchy process (AHP) during planning and budgeting of construction projects.

    Science.gov (United States)

    Aminbakhsh, Saman; Gunduz, Murat; Sonmez, Rifat

    2013-09-01

    The inherent and unique risks on construction projects quite often present key challenges to contractors. Health and safety risks are among the most significant risks in construction projects since the construction industry is characterized by a relatively high injury and death rate compared to other industries. In construction project management, safety risk assessment is an important step toward identifying potential hazards and evaluating the risks associated with the hazards. Adequate prioritization of safety risks during risk assessment is crucial for planning, budgeting, and management of safety related risks. In this paper, a safety risk assessment framework is presented based on the theory of cost of safety (COS) model and the analytic hierarchy process (AHP). The main contribution of the proposed framework is that it presents a robust method for prioritization of safety risks in construction projects to create a rational budget and to set realistic goals without compromising safety. The framework provides a decision tool for the decision makers to determine the adequate accident/injury prevention investments while considering the funding limits. The proposed safety risk framework is illustrated using a real-life construction project and the advantages and limitations of the framework are discussed. Copyright © 2013 National Safety Council and Elsevier Ltd. All rights reserved.

  1. Uranium Mill Tailings Remedial Action Project: Cost Reduction and Productivity Improvement Program Project Plan

    International Nuclear Information System (INIS)

    1991-11-01

    The purpose of the Cost Reduction/Productivity Improvement Program Plan is to formalize and improve upon existing efforts to control costs which have been underway since project inception. This program plan has been coordinated with the Department of Energy (DOE) Office of Environmental Management (EM) and the DOE Field Office, Albuquerque (AL). It incorporates prior Uranium Mill Tallings Remedial Action (UMTRA) Project Office guidance issued on the subject. The opportunities for reducing cosh and improving productivity are endless. The CR/PIP has these primary objectives: Improve productivity and quality; heighten the general cost consciousness of project participants, at all levels of their organizations; identify and implement specific innovative employee ideas that extend beyond what is required through existing processes and procedures; emphasize efforts that create additional value for the money spent by maintaining the project Total Estimated Cost (TEC) at the lowest possible level

  2. Process development work plan for waste feed delivery system

    International Nuclear Information System (INIS)

    Papp, I.G.

    1998-01-01

    This work plan defines the process used to develop project definition for Waste Feed Delivery (WFD). Project definition provides the direction for development of definitive design media required for the ultimate implementation of operational processing hardware and software. Outlines for the major deliverables are attached as appendices. The implementation of hardware and software will accommodate requirements for safe retrieval and delivery of waste currently stored in Hanford's underground storage tanks. Operations and maintenance ensure the availability of systems, structures, and components for current and future planned operations within the boundary of the Tank Waste Remediation System (TWRS) authorization basis

  3. 14 CFR 152.109 - Project eligibility: Airport planning.

    Science.gov (United States)

    2010-01-01

    ... 14 Aeronautics and Space 3 2010-01-01 2010-01-01 false Project eligibility: Airport planning. 152....109 Project eligibility: Airport planning. (a) Airport master planning. A proposed project for airport master planning is not approved unless— (1) The location of the existing or proposed airport is included...

  4. Route planning algorithms: Planific@ Project

    Directory of Open Access Journals (Sweden)

    Gonzalo Martín Ortega

    2009-12-01

    Full Text Available Planific@ is a route planning project for the city of Madrid (Spain. Its main aim is to develop an intelligence system capable of routing people from one place in the city to any other using the public transport. In order to do this, it is necessary to take into account such things as: time, traffic, user preferences, etc. Before beginning to design the project is necessary to make a comprehensive study of the variety of main known route planning algorithms suitable to be used in this project.

  5. A case study of resources management planning with multiple objectives and projects

    Science.gov (United States)

    Peterson, David L.; Silsbee, David G.; Schmoldt, Daniel L.

    1994-09-01

    Each National Park Service unit in the United States produces a resources management plan (RMP) every four years or less. The plans commit budgets and personnel to specific projects for four years, but they are prepared with little quantitative and analytical rigor and without formal decision-making tools. We have previously described a multiple objective planning process for inventory and monitoring programs (Schmoldt and others 1994). To test the applicability of that process for the more general needs of resources management planning, we conducted an exercise on the Olympic National Park (NP) in Washington State, USA. Eight projects were selected as typical of those considered in RMPs and five members of the Olympic NP staff used the analytic hierarchy process (AHP) to prioritize the eight projects with respect to their implicit management objectives. By altering management priorities for the park, three scenarios were generated. All three contained some similarities in rankings for the eight projects, as well as some differences. Mathematical allocations of money and people differed among these scenarios and differed substantially from what the actual 1990 Olympic NP RMP contains. Combining subjective priority measures with budget dollars and personnel time into an objective function creates a subjective economic metric for comparing different RMP’s. By applying this planning procedure, actual expenditures of budget and personnel in Olympic NP can agree more closely with the staff’s management objectives for the park.

  6. The Columbia River Protection Supplemental Technologies Quality Assurance Project Plan

    Energy Technology Data Exchange (ETDEWEB)

    Fix, N. J.

    2008-03-12

    Pacific Northwest National Laboratory researchers are working on the Columbia River Protection Supplemental Technologies Project. This project is a U. S. Department of Energy, Office of Environmental Management-funded initiative designed to develop new methods, strategies, and technologies for characterizing, modeling, remediating, and monitoring soils and groundwater contaminated with metals, radionuclides, and chlorinated organics. This Quality Assurance Project Plan provides the quality assurance requirements and processes that will be followed by the Technologies Project staff.

  7. Planning linear construction projects: automated method for the generation of earthwork activities

    NARCIS (Netherlands)

    Askew, W.H.; Al-Jibouri, Saad H.S.; Mawdesley, M.J.; Patterson, D.E.

    2002-01-01

    Earthworks planning for road construction projects is a complex operation and the planning rules used are usually intuitive and not well defined. An approach to automate the earthworks planning process is described and the basic techniques that are used are outlined. A computer-based system has been

  8. Systems engineering management and implementation plan for Project W-464, immobilized high-level waste storage

    International Nuclear Information System (INIS)

    Wecks, M.D.

    1998-01-01

    The Systems Engineering Management and Implementation Plan (SEMIP) for TWRS Project W-46 describes the project implementation of the Tank Waste Remediation System Systems Engineering Management Plan. (TWRS SEMP), Rev. 1. The SEMIP outlines systems engineering (SE) products and processes to be used by the project for technical baseline development. A formal graded approach is used to determine the products necessary for requirements, design, and operational baseline completion. SE management processes are defined, and roles and responsibilities for management processes and major technical baseline elements are documented

  9. Systems engineering management and implementation plan for Project W-465, immobilized low-activity waste storage

    International Nuclear Information System (INIS)

    Kaspar, J.R.; Latray, D.A.

    1998-01-01

    The Systems Engineering Management and Implementation Plan (SEMIP) for TWRS Project W-465 describes the project implementation of the Tank Waste Remediation System Systems Engineering Management Plan (TWRS SEMP), Rev. 1. The SEMIP outlines systems engineering (SE) products and processes to be used by the project for technical baseline development. A formal graded approach is used to determine the products necessary for requirements, design, and operational baseline completion. SE management processes are defined, and roles and responsibilities for management processes and major technical baseline elements are documented

  10. Spent Nuclear Fuel Project Safety Management Plan

    International Nuclear Information System (INIS)

    Garvin, L.J.

    1996-02-01

    The Spent Nuclear Fuel Project Safety Management Plan describes the new nuclear facility regulatory requirements basis for the Spemt Nuclear Fuel (SNF) Project and establishes the plan to achieve compliance with this basis at the new SNF Project facilities

  11. AVLIS Production Plant Project Management Plan

    International Nuclear Information System (INIS)

    1984-01-01

    The AVLIS Production Plant is designated as a Major System Acquisition (in accordance with DOE Order 4240.IC) to deploy Atomic Vapor Laser Isotope Separation (AVLIS) technology at the Oak Ridge, Tennessee site, in support of the US Uranium Enrichment Program. The AVLIS Production Plant Project will deploy AVLIS technology by performing the design, construction, and startup of a production plant that will meet capacity production requirements of the Uranium Enrichment Program. The AVLIS Production Plant Project Management Plan has been developed to outline plans, baselines, and control systems to be employed in managing the AVLIS Production Plant Project and to define the roles and responsibilities of project participants. Participants will develop and maintain detailed procedures for implementing the management and control systems in agreement with this plan. This baseline document defines the system that measures work performed and costs incurred. This plan was developed by the AVLIS Production Plant Project staff of Martin Marietta Energy Systems, Inc. and Lawrence Livermore National Laboratory in accordance with applicable DOE directives, orders and notices. 38 figures, 19 tables

  12. Yakima Habitat Improvement Project Master Plan, Technical Report 2003.

    Energy Technology Data Exchange (ETDEWEB)

    Golder Associates, Inc.

    2003-04-22

    result of the planning effort leading to this Master Plan, a Technical Working Group (TWG) was established that represents most, if not all, fish and wildlife agencies/interests in the subbasin. This TWG met regularly throughout the planning process to provide input and review and was instrumental in the development of this plan. Preparation of this plan included the development of a quantitative prioritization process to rank 40,000 parcels within the Urban Growth Area based on the value of fish and wildlife habitat each parcel provided. Biological and physical criteria were developed and applied to all parcels through a GIS-based prioritization model. In the second-phase of the prioritization process, the TWG provided local expert knowledge and review of the properties. In selecting the most critical areas within the Urban Growth Area for protection, this project assessed the value of fish and wildlife habitat on the Yakima River. Well-developed habitat acquisition efforts (e.g., Yakima River Basin Water Enhancement Project by the Bureau of Reclamation and Yakama Nation acquisition projects) are already underway on the Yakima River mainstem. These efforts, however, face several limitations in protection of floodplain function that could be addressed through the support of the Yakima Habitat Improvement Project. This Master Plan integrates tributary habitat acquisition efforts with those ongoing on the Yakima River to best benefit fish and wildlife in the Urban Growth Area. The parcel ranking process identified 25 properties with the highest fish and wildlife value for habitat acquisition in the Yakima Urban Area. These parcels contain important fish and wildlife corridors on Ahtanum and Wide Hollow Creeks and the Naches River. The fifteen highest-ranking parcels of the 25 parcels identified were considered very high priority for protection of fish and wildlife habitat. These 15 parcels were subsequently grouped into four priority acquisition areas. This Master Plan

  13. 78 FR 54949 - Major Project Financial Plan Guidance

    Science.gov (United States)

    2013-09-06

    ...'' (GA-090-751). That report recommended that Financial Plans include the cost of financing the project... Project Financial Plan Guidance AGENCY: Federal Highway Administration (FHWA), DOT. ACTION: Notice; Request for comments. SUMMARY: This notice requests comments on draft Major Project Financial Plan...

  14. Using project management methodology to plan and track inpatient care.

    Science.gov (United States)

    Kaufman, Darren S

    2005-08-01

    Effective care of each patient throughout a hospital admission involves executing a specific set of tasks to produce a favorable outcome within an appropriate time frame. The ProjectRounds methodology, which can be implemented using widely available software, incorporates the principles of project management in planning and control hospital inpatient care. It consists of four stages--clinical assessment, planning, scheduling, and tracking. OVERVIEW OF PROJECTROUNDS AND EXAMPLE: As an example, a 68-year-old-man is admitted with pneumonia. In clinical assessment, the admitting physician uses an assessment tool that prompts her to list all the patient's clinical issues, define the conditions that need to be met to discharge the patient, highlight special problems, and list any consultations, diagnostic tests, and procedures that are planned. In planning, the work breakdown structure--a tabulation of all the tasks in the "project" (the admission)--is created. In scheduling, a project schedule is generated, and in tracking, the clinical team evaluates and monitors the project's course. During interdisciplinary clinical rounds, the progress of the patient's hospital care can be tracked and quantified by employing the percent complete method. Tracking can be used as a "dashboard," providing a concise summary of the care that needs to be and has been rendered to the patient. Applying the tenets of project management can optimize the process of providing health care to hospital inpatients.

  15. A Process Towards Societal Value within a Community-Based Regional Development Project

    Directory of Open Access Journals (Sweden)

    Anna Åslund

    2012-12-01

    Full Text Available Processes, activities and tasks of a community-based area development project are described. The main process has been used three times and a model is presented. An earlier developed process map has been verified. The description of the project can help other communities to plan development projects. The illustration can be valuable for entrepreneurs who are planning a societal value initiative and for decision-makers and stakeholders who can contribute to, are concerned with, or may be affected by societal entrepreneurship. Observation, participating studies, dokumentations and an interview with the project leader has been carried out. Data have been analyzed and compared with the previously developed process map to achieve a deeper understanding of the processes within societal entrepreneurship. The purpose was to study and describe the processes of a community-based area development project and to compare it with a previously developed process map and to verify the process map.

  16. Quality Assurance Project Plan for Facility Effluent Monitoring Plan activities

    International Nuclear Information System (INIS)

    Nickels, J.M.

    1991-06-01

    This Quality Assurance Project Plan addresses the quality assurance requirements for the Facility Monitoring Plans of the overall site-wide environmental monitoring plan. This plan specifically applies to the sampling and analysis activities and continuous monitoring performed for all Facility Effluent Monitoring Plan activities conducted by Westinghouse Hanford Company. It is generic in approach and will be implemented in conjunction with the specific requirements of individual Facility Effluent Monitoring Plans. This document is intended to be a basic road map to the Facility Effluent Monitoring Plan documents (i.e., the guidance document for preparing Facility Effluent Monitoring Plans, Facility Effluent Monitoring Plan determinations, management plan, and Facility Effluent Monitoring Plans). The implementing procedures, plans, and instructions are appropriate for the control of effluent monitoring plans requiring compliance with US Department of Energy, US Environmental Protection Agency, state, and local requirements. This Quality Assurance Project Plan contains a matrix of organizational responsibilities, procedural resources from facility or site manuals used in the Facility Effluent Monitoring Plans, and a list of the analytes of interest and analytical methods for each facility preparing a Facility Effluent Monitoring Plan. 44 refs., 1 figs., 2 tabs

  17. Planning Complex Projects Automatically

    Science.gov (United States)

    Henke, Andrea L.; Stottler, Richard H.; Maher, Timothy P.

    1995-01-01

    Automated Manifest Planner (AMP) computer program applies combination of artificial-intelligence techniques to assist both expert and novice planners, reducing planning time by orders of magnitude. Gives planners flexibility to modify plans and constraints easily, without need for programming expertise. Developed specifically for planning space shuttle missions 5 to 10 years ahead, with modifications, applicable in general to planning other complex projects requiring scheduling of activities depending on other activities and/or timely allocation of resources. Adaptable to variety of complex scheduling problems in manufacturing, transportation, business, architecture, and construction.

  18. Salt Repository Project. FY-84 technical project plan

    International Nuclear Information System (INIS)

    1984-08-01

    The FY 84 technical plans for the Salt Repository Project (SRP) are briefly presented. The objectives of the project in relation to the Civilian Radioactive Waste Management (CRWM) program are discused and the technical activities directed toward accomplishing these objectives are detailed. A budget is presented for each of the Level 2 Work Breakdown Structure Tasks (Systems, Waste Package, Site, Repository, Regulatory and Institutional, Test Facilities, Exploratory Shaft, Land Acquisition, and Program Management) in an appendix. An overall description, current status, and planned activities are presented for each of the subtasks which make up the above-mentioned Level 2 tasks. Milestones and their definitions for the plan year, as well as milestones for the outyears are also presented at this same subtask level for each subtask

  19. Drafting a monitoring plan for the ROAD project under the EU CCS directive

    NARCIS (Netherlands)

    Steegs, T.P.H.; Neelse, F.P.; Gittins, C.; Ros, M.

    2014-01-01

    The Rotterdam Capture and Storage Demonstration Project (ROAD) is an integrated CCS project in the Netherlands that has recently completed the storage permitting process. Development of the monitoring and contingency plans is a key component of this process. Our paper discusses the development of

  20. The role of advocacy coalitions in a project implementation process: the example of the planning phase of the At Home/Chez Soi project dealing with homelessness in Montreal.

    Science.gov (United States)

    Fleury, Marie-Josée; Grenier, Guy; Vallée, Catherine; Hurtubise, Roch; Lévesque, Paul-André

    2014-08-01

    This study analyzed the planning process (summer 2008 to fall 2009) of a Montreal project that offers housing and community follow-up to homeless people with mental disorders, with or without substance abuse disorders. With the help of the Advocacy Coalition Framework (ACF), advocacy groups that were able to navigate a complex intervention implementation process were identified. In all, 25 people involved in the Montreal At Home/Chez Soi project were surveyed through interviews (n=18) and a discussion group (n=7). Participant observations and documentation (minutes and correspondence) were also used for the analysis. The start-up phase of the At Home/Chez may be broken down into three separate periods qualified respectively as "honeymoon;" "clash of cultures;" and "acceptance & commitment". In each of the planning phases of the At Home/Chez Soi project in Montreal, at least two advocacy coalitions were in confrontation about their specific belief systems concerning solutions to address the recurring homelessness social problem, while a third, more moderate one contributed in rallying most key actors under specified secondary aspects. The study confirms the importance of policy brokers in achieving compromises acceptable to all advocacy coalitions. Copyright © 2014 Elsevier Ltd. All rights reserved.

  1. Single-shell tank interim stabilization project plan

    Energy Technology Data Exchange (ETDEWEB)

    Ross, W.E.

    1998-05-11

    This project plan establishes the management framework for conduct of the TWRS Single-Shell Tank Interim Stabilization completion program. Specifically, this plan defines the mission needs and requirements; technical objectives and approach; organizational structure, roles, responsibilities, and interfaces; and operational methods. This plan serves as the project executional baseline.

  2. Salt Repository Project: FY 85 technical project plan

    International Nuclear Information System (INIS)

    1985-07-01

    The FY 85 technical plan for the Salt Repository Project is briefly presented. The objectives of the project in relation to the Civilian Radioactive Waste Management Program are discussed, and the technical activities directed toward accomplishing these objectives are detailed. A budget is presented for each of the Level 2 work breakdown structure tasks (Systems, Waste Package, Site, Repository, Regulatory and Institutional, Exploratory Shaft, Test Facilities, Land Acquisition, and Project Management) in the various sections. An overall description, current status, and planned activities are presented for each of the subtasks which make up the above-mentioned Level 2 tasks. A strategy diagram and a master schedule are included and each of the milestones is also listed chronologically in the sections

  3. 25 CFR 170.415 - What is pre-project planning?

    Science.gov (United States)

    2010-04-01

    ... 25 Indians 1 2010-04-01 2010-04-01 false What is pre-project planning? 170.415 Section 170.415... PROGRAM Planning, Design, and Construction of Indian Reservation Roads Program Facilities Long-Range Transportation Planning § 170.415 What is pre-project planning? (a) Pre-project planning is part of overall...

  4. UMTRA Project Office quality assurance program plan. Revision 6

    International Nuclear Information System (INIS)

    1994-09-01

    The Uranium Mill Tailings Remedial Action (UMTRA) Project was established to accomplish remedial actions at inactive uranium mill tailings sites. The UMTRA Project's mission is to stabilize and control the residual radioactive materials at designated sites in a safe and environmentally sound manner so as to minimize or eliminate radiation health hazards to the public. Because these efforts may involve possible risks to public health and safety, a quality assurance (QA) program that conforms to the applicable criteria has been established to control the quality of the work. This document, the Quality Assurance Program Plan (QAPP), brings into one document the essential criteria to be applied on a selective basis, depending upon the nature of the activity being conducted, and describes how those criteria shall be applied to the UMTRA Project. QA requirements contained in this QAPP shall apply to all personnel, processes, and activities, including planning, scheduling, and cost control, performed by the UMTRA Project Office and its contractors

  5. Non-Profit/Higher Education Project Management Series: The Project Plan

    Science.gov (United States)

    Burgher, Karl E.; Snyder, Michael

    2012-01-01

    This is the second installment of the AACRAO management series focusing on project management in the academy. In this article, the authors focus on white papers (often called charters, briefs, or fact sheets) and their partner, the work plan. The work plan is a detailed document that defines each aspect of a project. It is often preceded by a…

  6. Project Delivery Acquisition and Contracting Plan for the Tank Farm Contractor

    International Nuclear Information System (INIS)

    MERCADO, L.C.

    2000-01-01

    This document is a plan presenting the process, strategies and approaches for vendor contracting by the Tank Farm Contractor. The plan focuses on contracting structures, practices, methods, and desired approaches in contracting. The U.S. Department of Energy (DOE), Office of River Protection (ORP) has contracted with the CH2M HILL Hanford Group, Inc. (CHG), as the Tank Farm Contractor (TFC), to support vitrification of Hanford Site tank waste by the Privatization Contractor. During Waste Feed Delivery Phase 1, waste will be retrieved from certain double-shell tanks and delivered to the Privatization Contractor to meet contract feed delivery requirements. Near-term project goals include upgrading infrastructure systems; retrieving and delivering the waste; and accepting the waste packages for interim onsite storage and disposal. Project Delivery includes individual projects assigned to provide the infrastructure and systems responsible to provide engineering, design, procurement, installation/construction, and testing/turnover of systems for retrieval of waste from Hanford double-shell tanks. This plan sets the requirements for projects work scope, contracting practices, structures, methods, and performance measurements. The plan is designed to integrate Life-Cycle Projects acquisitions and provide a consistent contracting approach. This effort will serve as a step improvement in contract reform implementing commercial practices into DOE projects

  7. Project management plan, Waste Receiving and Processing Facility, Module 1, Project W-026

    Energy Technology Data Exchange (ETDEWEB)

    Starkey, J.G.

    1993-05-01

    The Hanford Waste Receiving and Processing Facility Module 1 Project (WRAP 1) has been established to support the retrieval and final disposal of approximately 400K grams of plutonium and quantities of hazardous components currently stored in drums at the Hanford Site.

  8. Project management plan, Waste Receiving and Processing Facility, Module 1, Project W-026

    International Nuclear Information System (INIS)

    Starkey, J.G.

    1993-05-01

    The Hanford Waste Receiving and Processing Facility Module 1 Project (WRAP 1) has been established to support the retrieval and final disposal of approximately 400K grams of plutonium and quantities of hazardous components currently stored in drums at the Hanford Site

  9. Tank waste remediation system privatization Phase 1 infrastructure, project W-519, project execution plan

    International Nuclear Information System (INIS)

    Parazin, R.J.

    1998-01-01

    This Project Execution Plan (PEP) defines the overall strategy, objectives, and contractor management requirements for the execution phase of Project W-519 (98-D403), Privatization Phase 1 Infrastructure Support, whose mission is to effect the required Hanford site infrastructure physical changes to accommodate the Privatization Contractor facilities. This plan provides the project scope, project objectives and method of performing the work scope and achieving objectives. The plan establishes the work definitions, the cost goals, schedule constraints and roles and responsibilities for project execution. The plan also defines how the project will be controlled and documented

  10. System Engineering Management and Implementation Plan for Project W-211, ''Initial Tank Retrieval Systems'' (ITRS)

    International Nuclear Information System (INIS)

    VAN BEEK, J.E.

    2000-01-01

    This systems Engineering Management and Implementation Plan (SEMIP) describes the Project W-211 implementation of the Tank Farm Contractor Systems Engineering Management Plan (TFC SEMP). The SEMIP defines the systems engineering products and processes used by the project to comply with the TFC SEMP, and provides the basis for tailoring systems engineering processes by applying a graded approach to identify appropriate systems engineering requirements for W-211

  11. System Engineering Management and Implementation Plan for Project W-211 Initial Tank Retrieval Systems (ITRS)

    Energy Technology Data Exchange (ETDEWEB)

    VAN BEEK, J.E.

    2000-05-05

    This systems Engineering Management and Implementation Plan (SEMIP) describes the Project W-211 implementation of the Tank Farm Contractor Systems Engineering Management Plan (TFC SEMP). The SEMIP defines the systems engineering products and processes used by the project to comply with the TFC SEMP, and provides the basis for tailoring systems engineering processes by applying a graded approach to identify appropriate systems engineering requirements for W-211.

  12. Marine radioecology. Annual report 1996. Project plan 1997

    International Nuclear Information System (INIS)

    1997-06-01

    The project plan for the EKO-1 project states that 'the main aim of the EKO-1 project is to enable faster and better assessments to be made of the effects of releases of radionuclides into the marine environment'. To meet this goal the main parts of the project were defined as follows: Model work - Identifying parameters of main interest including estimating and validating the values of these parameters; Research - Field studies, environments typical for various Nordic regions, environments with special physical or chemical characteristics. Laboratory studies; Dissemination of information - Seminars, reports, articles. During the project period emphasis has also been put on quality issues concerning sampling and analysis. The project work has progressed in accordance with project plans in 1996 and within the set budget. In modelling a parameter sensitivity analysis was carried out for a radiological assessment model used for the prediction of doses to man from dumping of radioactive waste in the Kara Sea. Doses to man were found to be generally dominated by contributions from long-lived transuranic radionuclides (plutonium and americium) which associate readily with sediments. Sediment related processes and parameters show therefore high sensitivities, especially at long distances (e.g. Barents Sea). Within the EKO-1 project there has been emphasis on encouraging the Nordic aspect of sediment research in spite of the limitations set by nationally run sampling projects. The EKO-1 project has managed this by e.g.: Organizing exchange of samples for analysis links with the EKO-2.3 project ('Limnic systems'). (EG) 52 refs

  13. Evaluation of participatory planning: Lessons from Hungarian Natura 2000 management planning processes.

    Science.gov (United States)

    Kovács, Eszter; Kelemen, Eszter; Kiss, Gabriella; Kalóczkai, Ágnes; Fabók, Veronika; Mihók, Barbara; Megyesi, Boldizsár; Pataki, György; Bodorkós, Barbara; Balázs, Bálint; Bela, Györgyi; Margóczi, Katalin; Roboz, Ágnes; Molnár, Dániel

    2017-12-15

    Stakeholder participation in nature conservation policies and especially in the management of protected areas has gained importance in the last decades. These changes are underlined by democratic principles and the perceived contribution of stakeholder involvement to the effectiveness of conservation management. Evaluating participatory processes is essential to learn about the past and thus increase the quality of future processes. The evaluation can be useful for the organisations responsible for planning and management, stakeholders and policy makers as well. The present paper shows the results of a systematic evaluation of 25 participatory processes related to the development of management plans for Natura 2000 sites in Hungary between 2007 and 2015. A conceptual framework was developed to evaluate the process and outcome of participatory management planning processes. Criteria were based on the scientific literature on public participation and tailored to conservation-related management planning and stakeholder involvement. Evaluated processes were grouped in three cases based on their time range and financial sources. Overall, the analysed processes scored at a medium level, showing better performance in the process criteria than in the outcome criteria. The best case scored significantly higher in four criteria compared to the other cases: representativeness, resource availability for facilitation, new, creative ideas and impact on the plan. The main factors behind the success were (1) embeddedness of the planning process in a larger project, where the plan was a tool for conservation, (2) carrying out only one process at a time, (3) previous experience of facilitators and planners with participatory planning and (4) the opportunity and capacity to propose a payment scheme as an incentive. But even this case received low scores in some criteria: conflict resolution, early involvement and well defined goals. Based on the results we suggest that more data is

  14. 49 CFR 633.25 - Contents of a project management plan.

    Science.gov (United States)

    2010-10-01

    ... 49 Transportation 7 2010-10-01 2010-10-01 false Contents of a project management plan. 633.25... ADMINISTRATION, DEPARTMENT OF TRANSPORTATION PROJECT MANAGEMENT OVERSIGHT Project Management Plans § 633.25 Contents of a project management plan. At a minimum, a recipient's project management plan shall include...

  15. 49 CFR 633.27 - Implementation of a project management plan.

    Science.gov (United States)

    2010-10-01

    ... 49 Transportation 7 2010-10-01 2010-10-01 false Implementation of a project management plan. 633... TRANSIT ADMINISTRATION, DEPARTMENT OF TRANSPORTATION PROJECT MANAGEMENT OVERSIGHT Project Management Plans § 633.27 Implementation of a project management plan. (a) Upon approval of a project management plan by...

  16. Policy and planning for large infrastructure projects

    DEFF Research Database (Denmark)

    Flyvbjerg, Bent

    2005-01-01

    This paper focuses on problems and their causes and cures in policy and planning for large infrastructure projects. First, it identifies as the main problem in major infrastructure development pervasive misinformation about the costs, benefits, and risks involved. A consequence of misinformation ...... for large infrastructure projects, with a focus on better planning methods and changed governance structures, the latter being more important.......This paper focuses on problems and their causes and cures in policy and planning for large infrastructure projects. First, it identifies as the main problem in major infrastructure development pervasive misinformation about the costs, benefits, and risks involved. A consequence of misinformation...... the likelihood that it is their projects, and not the competition's, that gain approval and funding. This results in the "survival of the unfittest," where often it is not the best projects that are built, but the most misrepresented ones. Finally, the paper presents measures for reforming policy and planning...

  17. Project Cost Estimation for Planning

    Science.gov (United States)

    2010-02-26

    For Nevada Department of Transportation (NDOT), there are far too many projects that ultimately cost much more than initially planned. Because project nominations are linked to estimates of future funding and the analysis of system needs, the inaccur...

  18. U.S. Department of Energy Uranium Mill Tailings Remedial Action Ground Water Project: Project plan

    International Nuclear Information System (INIS)

    1994-09-01

    The scope of the Project is to develop and implement a ground water compliance strategy for all 24 UMTRA Project processing sites. The compliance strategy for the processing sites must satisfy the proposed EPA ground water cleanup standards in 40 CFR Part 192, Subparts B and C (1987). This scope of work will entail the following activities on a site-specific basis: Develop a compliance strategy based on modification of the UMTRA Surface Project RAPs or develop Ground Water Project RAPs with NRC concurrence on the RAP and full participation of the affected states and tribes. Implement the RAP to include institutional controls, where appropriate, as an interim measure until compliance with the standards is achieved. Institute long-term verification monitoring for transfer to a separate long-term surveillance program on or before the Project end date. Prepare certification or confirmation reports and modify the long-term surveillance plan (LTSP), where needed, on those sites completed prior to the Project end date

  19. Achieving performance breakthroughs in an HMO business process through quality planning.

    Science.gov (United States)

    Hanan, K B

    1993-01-01

    Kaiser Permanente's Georgia Region commissioned a quality planning team to design a new process to improve payments to its suppliers and vendors. The result of the team's effort was a 73 percent reduction in cycle time. This team's experiences point to the advantages of process redesign as a quality planning model, as well as some general guidelines for its most effective use in teams. If quality planning project teams are carefully configured, sufficiently expert in the existing process, and properly supported by management, organizations can achieve potentially dramatic improvements in process performance using this approach.

  20. Yakima fisheries project spring chinook supplementation monitoring plan

    International Nuclear Information System (INIS)

    Busack, C.; Pearsons, T.; Knudsen, C.; Phelps, S.; Watson, B.; Johnston, M.

    1997-08-01

    The Yakima Fisheries Project (YFP), a key element in the Northwest Power Planning Council's Fish and Wildlife Program, has been in planning for more than ten years. It was initially conceived as, and is still intended to be, a multipurpose project. Besides increasing fish production in the Yakima basin, it is also intended to yield information about supplementation that will be of value to the entire Columbia basin, and hopefully the entire region. Because of this expectation of increased knowledge resulting from the project, a large and comprehensive monitoring program has always been seen as an integral part of the project. Throughout 1996 the Monitoring Implementation and Planning Team (MIPT), an interdisciplinary group of biologists who have worked on the project for several years, worked to develop a comprehensive spring chinook monitoring plan for the project. The result is the present document

  1. Decontamination and decommissioning plan for processing contaminated NaK at the INEL

    Energy Technology Data Exchange (ETDEWEB)

    LaRue, D.M.; Dolenc, M.R.

    1986-09-01

    This decontamination and decommissioning (D&D) plan describes the work elements and project management plan for processing four containers of contaminated sodium/potassium (NaK) and returning the Army Reentry Vehicle Facility Site (ARVFS) to a reusable condition. The document reflects the management plan for this project before finalizing the conceptual design and preliminary prototype tests of the reaction kinetics. As a result, the safety, environmental, and accident analyses are addressed as preliminary assessments before completion at a later date. ARVFS contains an earth-covered bunker, a cylindrical test pit and metal shed, and a cable trench connecting the two items. The bunker currently stores the four containers of NaK from the meltdown of the EBR-1 Mark II core. The D&D project addressed in this plan involves processing the contaminated NaK and returning the ARVFS to potential reuse after cleanup.

  2. Decontamination and decommissioning plan for processing contaminated NaK at the INEL

    Energy Technology Data Exchange (ETDEWEB)

    LaRue, D.M.; Dolenc, M.R.

    1986-09-01

    This decontamination and decommissioning (D D) plan describes the work elements and project management plan for processing four containers of contaminated sodium/potassium (NaK) and returning the Army Reentry Vehicle Facility Site (ARVFS) to a reusable condition. The document reflects the management plan for this project before finalizing the conceptual design and preliminary prototype tests of the reaction kinetics. As a result, the safety, environmental, and accident analyses are addressed as preliminary assessments before completion at a later date. ARVFS contains an earth-covered bunker, a cylindrical test pit and metal shed, and a cable trench connecting the two items. The bunker currently stores the four containers of NaK from the meltdown of the EBR-1 Mark II core. The D D project addressed in this plan involves processing the contaminated NaK and returning the ARVFS to potential reuse after cleanup.

  3. Tools for Supporting Distributed Agile Project Planning

    Science.gov (United States)

    Wang, Xin; Maurer, Frank; Morgan, Robert; Oliveira, Josyleuda

    Agile project planning plays an important part in agile software development. In distributed settings, project planning is severely impacted by the lack of face-to-face communication and the inability to share paper index cards amongst all meeting participants. To address these issues, several distributed agile planning tools were developed. The tools vary in features, functions and running platforms. In this chapter, we first summarize the requirements for distributed agile planning. Then we give an overview on existing agile planning tools. We also evaluate existing tools based on tool requirements. Finally, we present some practical advices for both designers and users of distributed agile planning tools.

  4. PNNL Apatite Investigation at 100-NR-2 Quality Assurance Project Plan

    Energy Technology Data Exchange (ETDEWEB)

    Fix, N. J.

    2009-04-02

    In 2004, the U.S. Department of Energy, Fluor Hanford, Inc., Pacific Northwest National Laboratory (PNNL), and the Washington Department of Ecology agreed that the long-term strategy for groundwater remediation at the 100-N Area would include apatite sequestration as the primary treatment, followed by a secondary treatment if necessary. Since then, the agencies have worked together to agree on which apatite sequestration technology has the greatest chance of reducing strontium-90 flux to the Columbia River. This Quality Assurance Project Plan provides the quality assurance requirements and processes that will be followed by staff working on the PNNL Apatite Investigation at 100-NR-2 Project. The plan is designed to be used exclusively by project staff.

  5. Meeting CCS communication challenges head-on: Integrating communications, planning, risk assessment, and project management

    Science.gov (United States)

    Greenberg, S.; Gauvreau, L.; Hnottavange-Telleen, K.; Finley, R.; Marsteller, S.

    2011-01-01

    The Midwest Geological Sequestration Consortium, Schlumberger Carbon Services, and Archer Daniels Midland has implemented a comprehensive communications plan at the Illinois Basin - Decatur Project (IBDP), a one million metric tonne Carbon Capture and Storage project in Decatur, IL, USA funded by the U.S. Department of Energy's National Energy Technology Laboratory. The IBDP Communication Plan includes consortium information, funding and disclaimer citations, description of target audiences, media communications guidelines, paper and presentations guidelines, site visit information, crisis communication, on-site photography regulations, and other components. The creation, development, and implementation processes for the IBDP Communication Plan (the Plan) are shared in this paper. New communications challenges, such as how to address add-on research requests, data sharing and management, scope increase, and contract agreements have arisen since the Plan was completed in January 2009, resulting in development of new policies and procedures by project management. Integrating communications planning, risk assessment, and project management ensured that consistent, factual information was developed and incorporated into project planning, and constitutes the basis of public communications. Successful integration has allowed the IBDP to benefit from early identification and mitigation of the potential project risks, which allows more time to effectively deal with unknown and unidentified risks that may arise. Project risks and risks associated with public perception can be managed through careful planning and integration of communication strategies into project management and risk mitigation. ?? 2011 Published by Elsevier Ltd.

  6. Linear-programming-based heuristics for project capacity planning

    NARCIS (Netherlands)

    Gademann, A.J.R.M.; Schutten, J.M.J.

    2005-01-01

    Many multi-project organizations are capacity driven, which means that their operations are constrained by various scarce resources. An important planning aspect in a capacity driven multi-project organization is capacity planning. By capacity planning, we mean the problem of matching demand for

  7. Quality Assurance Project Plan for Facility Effluent Monitoring Plan activities

    International Nuclear Information System (INIS)

    Frazier, T.P.

    1994-01-01

    This Quality Assurance Project Plan addresses the quality assurance requirements for the activities associated with the Facility Effluent Monitoring Plans, which are part of the overall Hanford Site Environmental Protection Plan. This plan specifically applies to the sampling and analysis activities and continuous monitoring performed for all Facility Effluent Monitoring Plan activities conducted by Westinghouse Hanford Company. It is generic in approach and will be implemented in conjunction with the specific requirements of the individual Facility Effluent Monitoring Plans

  8. Project management plan for the 105-C Reactor interim safe storage project. Revision 1

    International Nuclear Information System (INIS)

    Miller, R.L.

    1997-01-01

    In 1942, the Hanford Site was commissioned by the US Government to produce plutonium. Between 1942 and 1955, eight water-cooled, graphite-moderated reactors were constructed along the Columbia River at the Hanford Site to support the production of plutonium. The reactors were deactivated from 1964 to 1971 and declared surplus. The Surplus Production Reactor Decommissioning Project (BHI 1994b) will decommission these reactors and has selected the 105-C Reactor to be used as a demonstration project for interim safe storage at the present location and final disposition of the entire reactor core in the 200 West Area. This project will result in lower costs, accelerated schedules, reduced worker exposure, and provide direct benefit to the US Department of Energy for decommissioning projects complex wide. This project sets forth plans, organizational responsibilities, control systems, and procedures to manage the execution of the Project Management Plan for the 105-C Reactor Interim Safe Storage Project (Project Management Plan) activities to meet programmatic requirements within authorized funding and approved schedules. The Project Management Plan is organized following the guidelines provided by US Department of Energy Order 4700.1, Project Management System and the Richland Environmental Restoration Project Plan (DOE-RL 1992b)

  9. New Production Reactor project-management plan

    International Nuclear Information System (INIS)

    McCrosson, F.J.; Hibbard, L.; Buckner, M.R.

    1982-01-01

    This document provides a project management plan for the first phase of a project to design and build a new production reactor (NPR) at SRP. The design of the NPR is based upon proven SRP heavy water reactor design, with several enhancements such as full containment, moderator detritiation, improved cooling, and modernized control rooms and instrumentation. The first phase of the NPR project includes environmental and safety analyses, preparation of the technical data summary and basic data, site studies, engineering studies, and conceptual design. The project management plan was developed by a 14-member task force comprised of representatives from the Technical Division, the Manufacturing Division, the Departmental Engineer's Office, and the Engineering Department

  10. Outage planning in nuclear power plants. A paradigm shift from an external towards an integrated project planning tool

    Energy Technology Data Exchange (ETDEWEB)

    Rosemann, Andreas [Gesellschaft fuer integrierte Systemplanung (GIS) mbH, Weinheim (Germany)

    2014-07-01

    Latest demands on nuclear plant inspections are the ongoing actualisation of the outage plan on the basis of the current work progress and current events as well as the permanent access to the current planning status and work process of all people involved in the outage. Modern EAM systems (EAM: Enterprise Application Management) made up ground on established project planning tools with regard to functionalities for scheduling work orders. A shift towards an integrated planning in the EAM system increases the efficiency in the outage planning and improves the communication of current states of planning. (orig.)

  11. Outage planning in nuclear power plants. A paradigm shift from an external towards an integrated project planning tool

    International Nuclear Information System (INIS)

    Rosemann, Andreas

    2014-01-01

    Latest demands on nuclear plant inspections are the ongoing actualisation of the outage plan on the basis of the current work progress and current events as well as the permanent access to the current planning status and work process of all people involved in the outage. Modern EAM systems (EAM: Enterprise Application Management) made up ground on established project planning tools with regard to functionalities for scheduling work orders. A shift towards an integrated planning in the EAM system increases the efficiency in the outage planning and improves the communication of current states of planning. (orig.)

  12. Development process for integrated water resources management plan under a bottom-up participation perspective

    Directory of Open Access Journals (Sweden)

    Kittiwet Kuntiyawichai

    2014-06-01

    Full Text Available This article presents the development process for the integrated water resources management and development plan of Maha Sarakham Province by considering the priority and urgency of water problem issues. Gathering feedback from stakeholders and prioritizing water management and development projects are also taken into consideration. In view of integrated plans, the project is classified into short-, medium- and long-term plans with the project duration of 2 years, 3 years and 5 years, respectively. In this case, the plans can be categorized into proposed provincial and local plans. Firstly, the comprehensive provincial plans can be divided into 2 groups, i.e. district plans with the total number of 532 plans, which comprise of 505 projects for coping with drought and 27 projects for flood mitigation, and provincial plans from 13 agencies with the amount of 513 projects, which include 396 projects and 117 projects for dealing with drought and flood, respectively. Secondly, there are 4,099 of local plans to be put in place, in which 3,973 projects and 126 projects are proposed to handle drought and flood problems, respectively. From the analysis, it is found that if all planned drought relief projects are implemented, the water demand for domestic and agricultural needs could be covered by 96% and 51%, respectively. In case of the entire proposed flood alleviation projects are executed, 29% of the total flood prone areas can be effectively protected.

  13. Expedited technology demonstration project. Project baseline revision 2.2 and FY96 plan

    International Nuclear Information System (INIS)

    1996-07-01

    The Expedited Technology Demonstration Project Plan, Mixed Waste Management Facility (MWMF) current baseline. The revised plan will focus efforts specifically on the demonstration of an integrated Molten Salt Oxidation (MSO) system. In addition to the MSO primary unit, offgas, and salt recycle subsystems, the demonstrations will include feed preparation and feed delivery systems, and the generation of robust final forms from process mineral residues. A simplified process flow chart for the expedited demonstration is provided. To minimize costs and to accelerate the schedule for deployment, the integrated system will be staged in an existing facility at LLNL equipped to handle hazardous and radioactive materials. The MSO systems will be activated in fiscal year 97, followed by the activation of feed preparation and final forms in fiscal year 98

  14. Conceptual Design Plan SM-43 Replacement Project

    Energy Technology Data Exchange (ETDEWEB)

    University of California, Los Alamos National Laboratory, SCC Project Office

    2000-11-01

    The Los Alamos National Laboratory Conceptual Design Plan for the SM-43 Replacement Project outlines plans for replacing the SM-43 Administration Building. Topics include the reasons that replacement is considered a necessity; the roles of the various project sponsors; and descriptions of the proposed site and facilities. Also covered in this proposal is preliminary information on the project schedule, cost estimates, acquisition strategy, risk assessment, NEPA strategy, safety strategy, and safeguards and security. Spreadsheets provide further detail on space requirements, project schedules, and cost estimates.

  15. Improving Australia's renewable energy project policy and planning: A multiple stakeholder analysis

    International Nuclear Information System (INIS)

    Martin, Nigel; Rice, John

    2015-01-01

    Renewable Energy (RE) is part of Australia's and the world's energy supply matrix with over A$100 billion spent annually on RE projects since 2007. Businesses seeking to invest in RE projects, particularly in the wind and solar energy sectors, may face an onerous collection of planning approvals and permitting processes that impede investment and implementation. In this study, we draw on international and domestic stakeholder inputs to a governmental inquiry in Australia to show how RE projects might be approved in shortened timeframes with reduced associated costs. The process mapping and stakeholder analysis demonstrates that RE supply projects can benefit from standardized approval processes and documentation, a 360° deep engagement with stakeholders, and expanded electricity grid access in resource areas, augmented through supportive public policy and planning frameworks. In addition, stakeholder objections to project approval and implementation streamlining were used to contrast the efficacy of the proposed changes in policy. -- Highlights: •Highlights the over A$200 billion spent annually on global RE projects. •Describes a typical two stage, multi-layered governance RE project approval process. •Exposes long 3 year and multi-million dollar cost approvals for RE projects. •Identifies multi-million dollar remote grid connections as an RE project impediment. •Outlines RE project policy and guidelines shortcomings and proposed improvements

  16. SNF sludge treatment system preliminary project execution plan

    International Nuclear Information System (INIS)

    Flament, T.A.

    1998-01-01

    The Fluor Daniel Hanford, Inc. (FDH) Project Director for the Spent Nuclear Fuel (SNF) Project has requested Numatec Hanford Company (NHC) to define how Hanford would manage a new subproject to provide a process system to receive and chemically treat radioactive sludge currently stored in the 100 K Area fuel retention basins. The subproject, named the Sludge Treatment System (STS) Subproject, provides and operates facilities and equipment to chemically process K Basin sludge to meet Tank Waste Remediation System (TWRS) requirements. This document sets forth the NHC management approach for the STS Subproject and will comply with the requirements of the SNF Project Management Plan (HNF-SD-SNFPMP-011). This version of this document is intended to apply to the initial phase of the subproject and to evolve through subsequent revision to include all design, fabrication, and construction conducted on the project and the necessary management and engineering functions within the scope of the subproject. As Project Manager, NHC will perform those activities necessary to complete the STS Subproject within approved cost and schedule baselines and turn over to FDH facilities, systems, and documentation necessary for operation of the STS

  17. National Ignition Facility project acquisition plan

    International Nuclear Information System (INIS)

    Callaghan, R.W.

    1996-04-01

    The purpose of this National Ignition Facility Acquisition Plan is to describe the overall procurement strategy planned for the National Ignition Facility (NIF) Project. The scope of the plan describes the procurement activities and acquisition strategy for the following phases of the NIF Project, each of which receives either plant and capital equipment (PACE) or other project cost (OPC) funds: Title 1 and 2 design and Title 3 engineering (PACE); Optics manufacturing facilitization and pilot production (OPC); Convention facility construction (PACE); Procurement, installation, and acceptance testing of equipment (PACE); and Start-up (OPC). Activities that are part of the base Inertial Confinement Fusion (ICF) Program are not included in this plan. The University of California (UC), operating Lawrence Livermore National Laboratory (LLNL) and Los Alamos National Laboratory, and Lockheed-Martin, which operates Sandia National Laboratory (SNL) and the University of Rochester Laboratory for Laser Energetics (UR-LLE), will conduct the acquisition of needed products and services in support of their assigned responsibilities within the NIF Project structure in accordance with their prime contracts with the Department of Energy (DOE). LLNL, designated as the lead Laboratory, will have responsibility for all procurements required for construction, installation, activation, and startup of the NIF

  18. Controlling the Instructional Development Process. Training Development and Research Center Project Number Fifteen.

    Science.gov (United States)

    Sleezer, Catherine M.; Swanson, Richard A.

    Process control is a way of training managers in business and industry to plan, monitor, and communicate the instructional development process of training projects. Two simple and useful tools that managers use in controlling the process of instructional development are the Process Control Planning Sheet and the Process Control Record. The Process…

  19. Single-Shell Tank (SST) Interim Stabilization Project Plan

    International Nuclear Information System (INIS)

    VLADIMIROFF, D.T.; BOYLES, V.C.

    2000-01-01

    This project plan establishes the management framework for the conduct of the CHG Single-Shell Tank Interim Stabilization completion program. Specifically, this plan defines the mission needs and requirements; technical objectives and approach; organization structure, roles, responsibilities, and interfaces; and operational methods. This plan serves as the project executional baseline

  20. Understanding and Managing Process Interaction in IS Development Projects

    DEFF Research Database (Denmark)

    Bygstad, Bendik; Nielsen, Peter Axel

    2005-01-01

    Increasingly, information systems must be developed and implemented as a part of business change. This is a challenge for the IS project manager, since business change and information systems development usually are performed as separate processes. Thus, there is a need to understand and manage......-technical innovation in a situation where the organisational change process and the IS development process are parallel but incongruent. We also argue that iterative software engineering frameworks are well structured to support process interaction. Finally, we advocate that the IS project manager needs to manage...... the relationship between these two kinds of processes. To understand the interaction between information systems development and planned organisational change we introduce the concept of process interaction. We draw on a longitudinal case study of an IS development project that used an iterative and incremental...

  1. Study of decision framework of wind farm project plan selection under intuitionistic fuzzy set and fuzzy measure environment

    International Nuclear Information System (INIS)

    Wu, Yunna; Geng, Shuai; Xu, Hu; Zhang, Haobo

    2014-01-01

    Highlights: • Experts’ opinions are expressed by using the intuitionistic fuzzy values. • Fuzzy measure is used to solve the dependence problem of criteria. • The compensatory problem of performance scores is reasonably processed. - Abstract: Project selection plays an important role in the entire life cycle of wind farm project and the multi-criteria decision making (MCDM) methods are very important in the whole wind farm project plan selection process. There are problems in the present MCDM methods decrease evaluation quality of the wind farm project plans: first, the information loss exists in the wind farm project plan evaluation process. Second, it is difficult to satisfy the independent assumption of the multi-criteria decision making methods used in the wind farm project plan evaluation in fact. Third, the compensatory problem of performance scores of the wind farm project plans is processed unreasonably. Hence the innovation points of this paper are as follows: first, the intuitionistic fuzzy numbers are used instead of fuzzy numbers or numerical values to reflect the experts’ intuitive preferences to decrease the probability of information loss; second, the fuzzy measure is used to rate the important degrees of criteria in order to avoid the independent assumption and to increase the reasonability; third, the partial compensatory problem of performance scores is well processed by using intuitionistic fuzzy Choquet (IFC) operator and generalized intuitionistic fuzzy ordered geometric averaging (GIFOGA) operator. These operators can deal with the compensatory performance scores and non-compensatory performance scores respectively. Finally, a case study demonstrates the effectiveness of decision framework

  2. Study on Top-Down Estimation Method of Software Project Planning

    Institute of Scientific and Technical Information of China (English)

    ZHANG Jun-guang; L(U) Ting-jie; ZHAO Yu-mei

    2006-01-01

    This paper studies a new software project planning method under some actual project data in order to make software project plans more effective. From the perspective of system theory, our new method regards a software project plan as an associative unit for study. During a top-down estimation of a software project, Program Evaluation and Review Technique (PERT) method and analogy method are combined to estimate its size, then effort estimation and specific schedules are obtained according to distributions of the phase effort. This allows a set of practical and feasible planning methods to be constructed. Actual data indicate that this set of methods can lead to effective software project planning.

  3. Crawler Acquisition and Testing Demonstration Project Management Plan

    International Nuclear Information System (INIS)

    DEFIGH-PRICE, C.

    2000-01-01

    If the crawler based retrieval system is selected, this project management plan identifies the path forward for acquiring a crawler/track pump waste retrieval system, and completing sufficient testing to support deploying the crawler for as part of a retrieval technology demonstration for Tank 241-C-104. In the balance of the document, these activities will be referred to as the Crawler Acquisition and Testing Demonstration. During recent Tri-Party Agreement negotiations, TPA milestones were proposed for a sludge/hard heel waste retrieval demonstration in tank C-104. Specifically one of the proposed milestones requires completion of a cold demonstration of sufficient scale to support final design and testing of the equipment (M-45-03G) by 6/30/2004. A crawler-based retrieval system was one of the two options evaluated during the pre-conceptual engineering for C-104 retrieval (RPP-6843 Rev. 0). The alternative technology procurement initiated by the Hanford Tanks Initiative (HTI) project, combined with the pre-conceptual engineering for C-104 retrieval provide an opportunity to achieve compliance with the proposed TPA milestone M-45-03H. This Crawler Acquisition and Testing Demonstration project management plan identifies the plans, organizational interfaces and responsibilities, management control systems, reporting systems, timeline and requirements for the acquisition and testing of the crawler based retrieval system. This project management plan is complimentary to and supportive of the Project Management Plan for Retrieval of C-104 (RPP-6557). This project management plan focuses on utilizing and completing the efforts initiated under the Hanford Tanks Initiative (HTI) to acquire and cold test a commercial crawler based retrieval system. The crawler-based retrieval system will be purchased on a schedule to support design of the waste retrieval from tank C-104 (project W-523) and to meet the requirement of proposed TPA milestone M-45-03H. This Crawler

  4. Constellation Mission Operation Working Group: ESMO Maneuver Planning Process Review

    Science.gov (United States)

    Moyer, Eric

    2015-01-01

    The Earth Science Mission Operation (ESMO) Project created an Independent Review Board to review our Conjunction Risk evaluation process and Maneuver Planning Process to identify improvements that safely manages mission conjunction risks, maintains ground track science requirements, and minimizes overall hours expended on High Interest Events (HIE). The Review Board is evaluating the current maneuver process which requires support by multiple groups. In the past year, there have been several changes to the processes although many prior and new concerns exist. This presentation will discuss maneuver process reviews and Board comments, ESMO assessment and path foward, ESMO future plans, recent changes and concerns.

  5. Data processing project management in the construction of plants and power stations

    International Nuclear Information System (INIS)

    Huelsen, H.; Hayen, W.

    1987-01-01

    The requirements of project management in plant construction i.e. basic data, supervision and control became more and more detailed. These requirements can only satisfactorily be met with the help of data processing. Piping design requires up to 50% of the whole amount of engineering in design and management of plant construction. We present data processing project management system which explains the connections of single aspects. Its connections consists of: collection of basic data, plant design and installation, supervision of planning and installation, planning and calculation, collection, use, administration and approval of plan data, procurement material, construction of the model (1:25), and installation. (orig.) [de

  6. 242-A evaporator quality assurance project plan: Revision 1

    International Nuclear Information System (INIS)

    Tucker, B.J.

    1994-01-01

    The scope of this quality assurance project plan (Plan) is sampling and analytical services including, but not limited to, sample receipt, handling and storage, analytical measurements, submittal of data deliverables, archiving selected portions of samples, returning unneeded sample material to Westinghouse Hanford Company (WHC), and/or sample disposal associated with candidate feed samples and process condensate compliance samples. Sampling and shipping activities are also included within the scope. The purpose of this project is to provide planning, implementation, and assessment guidance for achieving established data quality objectives measurement parameters. This Plan requires onsite and offsite laboratories to conform to that guidance. Laboratory conformance will help ensure that quality data are being generated and therefore, that the 242-A evaporator is operating in a safe and compliant manner. The 242-A evaporator feed stream originates from double-shell tanks (DSTs) identified as candidate feed tanks. The 242-A evaporator reduces the volume of aqueous waste contained in DSTs by boiling off water and sending it to the Liquid Effluent Retention Facility (LERF) storage basin before further treatment. The slurry product is returned to DSTs. Evaporation results in considerable savings by reducing the volume of mixed waste for disposal

  7. Connected vehicle impacts on transportation planning technical memorandum #2 : connected vehicle planning processes and products and stakeholder roles and responsibilities.

    Science.gov (United States)

    2015-01-01

    The objective of this project, Connected Vehicle Impacts on Transportation Planning, is to comprehensively assess how connected vehicles should : be considered across the range of transportation planning processes and products developed by Stat...

  8. Dynamic modeling of uncertainty in the planned values of investments in petrochemical and refining projects

    International Nuclear Information System (INIS)

    Vianello, Juliano Melquiades; Costa, Leticia; Teixeira, José Paulo

    2014-01-01

    There is a large gap between the planned value of investment in a project and its financial implementation. This fact creates a mismatch between the planned and effectively achieved net present value (NPV) of the project. Considering the project portfolio of a company, this could even threaten your solvency in the future. Therefore, a quantitative-risk analysis that takes into account different possible scenarios for these values of investment is extremely important to measure statistically the real value of a project. The aim of this paper is to present the reasons for this mismatch between planned and executed investments and, from this study, obtain a suitable stochastic process to generate different scenarios for these investments in the oil industry. Although the results are valid for projects in the petrochemical and refining sector, also called in the oil industry as downstream, the methodology can be applied to the upstream or even other branches of industry. - Highlights: • We measure statistically the real value of an investment project. • We present the reasons for the mismatch between planned and executed investments. • We obtain a stochastic process to generate scenarios for oil industry investments. • Results are valid for projects in the petrochemical and refining sector, downstream. • The methodology can be applied to the upstream or even other branches of industry

  9. Planning a change project in mental health nursing.

    Science.gov (United States)

    Thorpe, Rebecca

    2015-09-02

    This article outlines a plan for a change project to improve the quality of physical health care on mental health wards. The plan was designed to improve the monitoring and recording of respiratory rates on mental health wards, through the implementation of a training programme for staff. A root cause analysis was used to explore the reasons for the low incidence of respiratory rate measurement on mental health wards, and the results of this establish the basis of the proposed change project and its aims and objectives. The article describes how the project could be implemented using a change management model, as well as how its effects could be measured and evaluated. Potential barriers to the planned change project are discussed, including the human dimensions of change. The article suggests methods to overcome such barriers, discusses the value of leadership as an important factor, and examines the principles of clinical governance in the context of the planned change project.

  10. Leveling a Simple Manufacturing Process Using Microsoft Project and Oracle Primavera

    Directory of Open Access Journals (Sweden)

    Ilie Margareta

    2017-01-01

    Full Text Available The present paper main objective is to put forward two software application tools: Microsoft Project 2013 and Oracle Primavera P6 Professional, used for the management process planning, especially for industrial projects. Second goals is to compare some feature of the two software and emphasize some aspects used for an easier use. The presentation and comparison considered four small processes with a total of 38 activities. The two software are used for the leveling of seven labor resources defined for the achievement of the activities. The results of the analyzes point out that even the two tools have the same purpose, Microsoft Project can be used for general simple to average processes’ complexity and size, Oracle Primavera has more specialized possibilities (libraries and specific project plans and more possibilities to model the actions needed for better leveling.

  11. Final Report for the Soboba Strategic Tribal Energy Planning Project

    Energy Technology Data Exchange (ETDEWEB)

    Miller, Kim [EPA Specialist

    2013-09-17

    In 2011 the Tribe was awarded funds from the Department of Energy to formulate the Soboba Strategic Tribal Energy Plan. This will be a guiding document used throughout the planning of projects focused on energy reduction on the Reservation. The Soboba Strategic Tribal Energy Plan's goal is to create a Five Year Energy Plan for the Soboba Band of Luiseno Indians in San Jacinto, California. This plan will guide the decision making process towards consistent progress leading to the Tribal goal of a 25% reduction in energy consumption in the next five years. It will additionally outline energy usage/patterns and will edentify areas the Tribe can decrease energy use and increase efficiency. The report documents activities undertaken under the grant, as well as incldues the Tribe's strategif energy plan.

  12. Implementation plan for the programmatic environmental impact statement for the Department of Energy UMTRA Ground Water Project

    International Nuclear Information System (INIS)

    1994-04-01

    Under the Uranium Mill Tailings Remedial Action (UMTRA) Project, the U.S. Department of Energy (DOE) is cleaning up contamination to protect human health and the environment at 24 inactive uranium processing sites located in 10 states. Five of the sites are either on or near Native American lands. The UMTRA Project is divided into two projects: Surface and Ground Water. On November 18, 1992, the DOE issued a notice of intent (57 FR 54374, 1992) to prepare a programmatic environmental impact statement (PEIS) for the UMTRA Ground Water Project. The PEIS will result in a record of decision that will determine how the UMTRA Ground Water Project will address ground water contamination resulting from milling operations at the UMTRA Project processing sites. DOE regulations (10 CFR section 1021.312) require that an implementation plan be prepared to provide guidance for preparing a PEIS and to record the results of the scoping process. This implementation plan describes and records the results of the PEIS scoping process; summarizes comments received and their disposition; describes the purpose of and need for agency action, the proposed action, and alternatives; lists alternatives considered and eliminated from review; identifies cooperating agencies, their roles, and responsibilities; provides a draft PEIS outline, which includes the planned PEIS scope and content (Attachment A); and provides a schedule for the PEIS process. This plan will be placed in the UMTRA Project libraries listed in Attachment B. The PEIS will identify and evaluate the potential impacts associated with alternatives for conducting the UMTRA Ground Water Project. The PEIS will not assess site-specific impacts; site-specific impacts must be analyzed in separate National Environmental Policy Act (NEPA) documents that will tier off the PEIS. This tiering process will streamline the preparation of site-specific NEPA documents

  13. Life sciences space biology project planning

    Science.gov (United States)

    Primeaux, G.; Newkirk, K.; Miller, L.; Lewis, G.; Michaud, R.

    1988-01-01

    The Life Sciences Space Biology (LSSB) research will explore the effect of microgravity on humans, including the physiological, clinical, and sociological implications of space flight and the readaptations upon return to earth. Physiological anomalies from past U.S. space flights will be used in planning the LSSB project.The planning effort integrates science and engineering. Other goals of the LSSB project include the provision of macroscopic view of the earth's biosphere, and the development of spinoff technology for application on earth.

  14. Salt Repository Project transportation program plan

    International Nuclear Information System (INIS)

    Fisher, R.L.; Greenberg, A.H.; Anderson, T.L.; Yates, K.R.

    1987-01-01

    The Salt Repository Project (SRP) has the responsibility to develop a comprehensive transportation program plan (TrPP) that treats the transportation of workers, supplies, and high-level radioactive waste to the site and the transportation of salt, low-level, and transuranic wastes from the site. The TrPP has developed a systematic approach to transportation which is directed towards satisfying statutes, regulations, and directives and is guided by a hierarchy of specific functional requirements, strategies, plans, and reports. The TrPP identifies and develops the planning process for transportation-related studies and provides guidance to staff in performing and documenting these activities. The TrPP also includes an explanation of the responsibilities of the organizational elements involved in these transportation studies. Several of the report chapters relate to identifying routes for transporting nuclear waste to the site. These include a chapter on identifying an access corridor for a new rail route leading to the site, identifying and evaluating emergency-response preparedness capabilities along candidate routes in the state, and identifying alternative routes from the state border, ports, or in-state reactors to the site. The TrPP also includes plans for identifying salt disposal routes and a discussion of repository/transportation interface requirements. 89 refs., 6 figs

  15. Rainwater Wildlife Area, Watershed Management Plan, A Columbia Basin Wildlife Mitigation Project, 2002.

    Energy Technology Data Exchange (ETDEWEB)

    Childs, Allen B.

    2002-03-01

    This Management Plan has been developed by the Confederated Tribes of the Umatilla Indian Reservation (CTUIR) to document how the Rainwater Wildlife Area (formerly known as the Rainwater Ranch) will be managed. The plan has been developed under a standardized planning process developed by the Bonneville Power Administration (BPA) for Columbia River Basin Wildlife Mitigation Projects (See Appendix A and Guiding Policies Section below). The plan outlines the framework for managing the project area, provides an assessment of existing conditions and key resource issues, and presents an array of habitat management and enhancement strategies. The plan culminates into a 5-Year Action Plan that will focus our management actions and prioritize funding during the Fiscal 2001-2005 planning period. This plan is a product of nearly two years of field studies and research, public scoping, and coordination with the Rainwater Advisory Committee. The committee consists of representatives from tribal government, state agencies, local government, public organizations, and members of the public. The plan is organized into several sections with Chapter 1 providing introductory information such as project location, purpose and need, project goals and objectives, common elements and assumptions, coordination efforts and public scoping, and historical information about the project area. Key issues are presented in Chapter 2 and Chapter 3 discusses existing resource conditions within the wildlife area. Chapter 4 provides a detailed presentation on management activities and Chapter 5 outlines a monitoring and evaluation plan for the project that will help assess whether the project is meeting the intended purpose and need and the goals and objectives. Chapter 6 displays the action plan and provides a prioritized list of actions with associated budget for the next five year period. Successive chapters contain appendices, references, definitions, and a glossary. The purpose of the project is

  16. Quality Assurance Project Plan Development Tool

    Science.gov (United States)

    This tool contains information designed to assist in developing a Quality Assurance (QA) Project Plan that meets EPA requirements for projects that involve surface or groundwater monitoring and/or the collection and analysis of water samples.

  17. UMTRA project water sampling and analysis plan, Gunnison, Colorado

    International Nuclear Information System (INIS)

    1994-06-01

    This water sampling and analysis plan summarizes the results of previous water sampling activities and the plan for water sampling activities for calendar year 1994. A buffer zone monitoring plan is included as an appendix. The buffer zone monitoring plan is designed to protect the public from residual contamination that entered the ground water as a result of former milling operations. Surface remedial action at the Gunnison Uranium Mill Tailings Remedial Action Project site began in 1992; completion is expected in 1995. Ground water and surface water will be sampled semiannually in 1994 at the Gunnison processing site (GUN-01) and disposal site (GUN-08). Results of previous water sampling at the Gunnison processing site indicate that ground water in the alluvium is contaminated by the former uranium processing activities. Background ground water conditions have been established in the uppermost aquifer (Tertiary gravels) at the Gunnison disposal site. The monitor well locations provide a representative distribution of sampling points to characterize ground water quality and ground water flow conditions in the vicinity of the sites. The list of analytes has been modified with time to reflect constituents that are related to uranium processing activities and the parameters needed for geochemical evaluation. Water sampling will be conducted at least semiannually during and one year following the period of construction activities, to comply with the ground water protection strategy discussed in the remedial action plan (DOE, 1992a)

  18. National Security Technology Incubation Project Continuation Plan

    Energy Technology Data Exchange (ETDEWEB)

    None

    2008-09-30

    This document contains a project continuation plan for the National Security Technology Incubator (NSTI). The plan was developed as part of the National Security Preparedness Project (NSPP) funded by a Department of Energy (DOE)/National Nuclear Security Administration (NNSA) grant. This continuation plan describes the current status of NSTI (staffing and clients), long-term goals, strategies, and long-term financial solvency goals.The Arrowhead Center of New Mexico State University (NMSU) is the operator and manager of the NSTI. To realize the NSTI, Arrowhead Center must meet several performance objectives related to planning, development, execution, evaluation, and sustainability. This continuation plan is critical to the success of NSTI in its mission of incubating businesses with security technology products and services.

  19. Tracking the Short Term Planning (STP) Development Process

    Science.gov (United States)

    Price, Melanie; Moore, Alexander

    2010-01-01

    Part of the National Aeronautics and Space Administration?s mission is to pioneer the future in space exploration, scientific discovery and aeronautics research is enhanced by discovering new scientific tools to improve life on earth. Sequentially, to successfully explore the unknown, there has to be a planning process that organizes certain events in the right priority. Therefore, the planning support team has to continually improve their processes so the ISS Mission Operations can operate smoothly and effectively. The planning support team consists of people in the Long Range Planning area that develop timelines that includes International Partner?s Preliminary STP inputs all the way through to publishing of the Final STP. Planning is a crucial part of the NASA community when it comes to planning the astronaut?s daily schedule in great detail. The STP Process is in need of improvement, because of the various tasks that are required to be broken down in order to get the overall objective of developing a Final STP done correctly. Then a new project came along in order to store various data in a more efficient database. "The SharePoint site is a Web site that provides a central storage and collaboration space for documents, information, and ideas."

  20. Single-shell tank interim stabilization project plan

    Energy Technology Data Exchange (ETDEWEB)

    Ross, W.E.

    1998-03-27

    Solid and liquid radioactive waste continues to be stored in 149 single-shell tanks at the Hanford Site. To date, 119 tanks have had most of the pumpable liquid removed by interim stabilization. Thirty tanks remain to be stabilized. One of these tanks (C-106) will be stabilized by retrieval of the tank contents. The remaining 29 tanks will be interim stabilized by saltwell pumping. In the summer of 1997, the US Department of Energy (DOE) placed a moratorium on the startup of additional saltwell pumping systems because of funding constraints and proposed modifications to the Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) milestones to the Washington State Department of Ecology (Ecology). In a letter dated February 10, 1998, Final Determination Pursuant to Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) in the Matter of the Disapproval of the DOE`s Change Control Form M-41-97-01 (Fitzsimmons 1998), Ecology disapproved the DOE Change Control Form M-41-97-01. In response, Fluor Daniel Hanford, Inc. (FDH) directed Lockheed Martin Hanford Corporation (LNMC) to initiate development of a project plan in a letter dated February 25, 1998, Direction for Development of an Aggressive Single-Shell Tank (SST) Interim Stabilization Completion Project Plan in Support of Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement). In a letter dated March 2, 1998, Request for an Aggressive Single-Shell Tank (SST) Interim Stabilization Completion Project Plan, the DOE reaffirmed the need for an aggressive SST interim stabilization completion project plan to support a finalized Tri-Party Agreement Milestone M-41 recovery plan. This project plan establishes the management framework for conduct of the TWRS Single-Shell Tank Interim Stabilization completion program. Specifically, this plan defines the mission needs and requirements; technical objectives and approach; organizational structure, roles, responsibilities

  1. Single-shell tank interim stabilization project plan

    International Nuclear Information System (INIS)

    Ross, W.E.

    1998-01-01

    Solid and liquid radioactive waste continues to be stored in 149 single-shell tanks at the Hanford Site. To date, 119 tanks have had most of the pumpable liquid removed by interim stabilization. Thirty tanks remain to be stabilized. One of these tanks (C-106) will be stabilized by retrieval of the tank contents. The remaining 29 tanks will be interim stabilized by saltwell pumping. In the summer of 1997, the US Department of Energy (DOE) placed a moratorium on the startup of additional saltwell pumping systems because of funding constraints and proposed modifications to the Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) milestones to the Washington State Department of Ecology (Ecology). In a letter dated February 10, 1998, Final Determination Pursuant to Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) in the Matter of the Disapproval of the DOE's Change Control Form M-41-97-01 (Fitzsimmons 1998), Ecology disapproved the DOE Change Control Form M-41-97-01. In response, Fluor Daniel Hanford, Inc. (FDH) directed Lockheed Martin Hanford Corporation (LNMC) to initiate development of a project plan in a letter dated February 25, 1998, Direction for Development of an Aggressive Single-Shell Tank (SST) Interim Stabilization Completion Project Plan in Support of Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement). In a letter dated March 2, 1998, Request for an Aggressive Single-Shell Tank (SST) Interim Stabilization Completion Project Plan, the DOE reaffirmed the need for an aggressive SST interim stabilization completion project plan to support a finalized Tri-Party Agreement Milestone M-41 recovery plan. This project plan establishes the management framework for conduct of the TWRS Single-Shell Tank Interim Stabilization completion program. Specifically, this plan defines the mission needs and requirements; technical objectives and approach; organizational structure, roles, responsibilities

  2. PLANNING QUALITY ASSURANCE PROCESSES IN A LARGE SCALE GEOGRAPHICALLY SPREAD HYBRID SOFTWARE DEVELOPMENT PROJECT

    Directory of Open Access Journals (Sweden)

    Святослав Аркадійович МУРАВЕЦЬКИЙ

    2016-02-01

    Full Text Available There have been discussed key points of operational activates in a large scale geographically spread software development projects. A look taken at required QA processes structure in such project. There have been given up to date methods of integration quality assurance processes into software development processes. There have been reviewed existing groups of software development methodologies. Such as sequential, agile and based on RPINCE2. There have been given a condensed overview of quality assurance processes in each group. There have been given a review of common challenges that sequential and agile models are having in case of large geographically spread hybrid software development project. Recommendations were given in order to tackle those challenges.  The conclusions about the best methodology choice and appliance to the particular project have been made.

  3. Project plans for transuranic waste at small quantity sites in the Department of Energy comples-10522

    International Nuclear Information System (INIS)

    Mctaggart, Jerri Lynne; Lott, Sheila; Gadbury, Casey

    2009-01-01

    Los Alamos National Laboratory, Carlsbad Office (LANL-CO), has been tasked to write Project Plans for all of the Small Quantity Sites (SQS) with defense related Transuranic (TRU) waste in the Department of Energy (DOE) complex. Transuranic Work-Off Plans were precursors to the Project Plans. LANL-CO prepared a Work-Off Plan for each small quantity site. The Work-Off Plan that identified issues, drivers, schedules, and inventory. Eight sites have been chosen to deinventory their legacy TRU waste; Bettis Atomic Power Laboratory, General Electric-Vallecitos Nuclear Center, Lawrence Berkeley National Laboratory, Lawrence Livermore National Laboratory-Area 300, Nevada Test Site, Nuclear Radiation Development, Sandia National Laboratory, and the Separations Process Research Unit. Each plan was written for contact and/or remote handled waste if present at the site. These project plans will assist the small quantity sites to ship legacy TRU waste offsite and de-inventory the site of legacy TRU waste. The DOE is working very diligently to reduce the nuclear foot print in the United States. Each of the eight SQSs will be de-inventoried of legacy TRU waste during a campaign that ends September 2011. The small quantity sites have a fraction of the waste that large quantity sites possess. During this campaign, the small quantity sites will package all of the legacy TRU waste and ship to Idaho or directly to the Waste Isolation Pilot Plant (WIPP) in Carlsbad, New Mexico. The sites will then be removed from the Transuranic Waste Inventory if they are de-inventoried of all waste. Each Project Plan includes the respective site inventory report, schedules, resources, drivers and any issues. These project plans have been written by the difficult waste team and will be approved by each site. Team members have been assigned to each site to write site specific project plans. Once the project plans have been written, the difficult team members will visit the sites to ensure nothing has

  4. A functional-dynamic reflection on participatory processes in modeling projects.

    Science.gov (United States)

    Seidl, Roman

    2015-12-01

    The participation of nonscientists in modeling projects/studies is increasingly employed to fulfill different functions. However, it is not well investigated if and how explicitly these functions and the dynamics of a participatory process are reflected by modeling projects in particular. In this review study, I explore participatory modeling projects from a functional-dynamic process perspective. The main differences among projects relate to the functions of participation-most often, more than one per project can be identified, along with the degree of explicit reflection (i.e., awareness and anticipation) on the dynamic process perspective. Moreover, two main approaches are revealed: participatory modeling covering diverse approaches and companion modeling. It becomes apparent that the degree of reflection on the participatory process itself is not always explicit and perfectly visible in the descriptions of the modeling projects. Thus, the use of common protocols or templates is discussed to facilitate project planning, as well as the publication of project results. A generic template may help, not in providing details of a project or model development, but in explicitly reflecting on the participatory process. It can serve to systematize the particular project's approach to stakeholder collaboration, and thus quality management.

  5. Implementing national nuclear safety plan at the preliminary stage of nuclear power project development

    International Nuclear Information System (INIS)

    Xue Yabin; Cui Shaozhang; Pan Fengguo; Zhang Lizhen; Shi Yonggang

    2014-01-01

    This study discusses the importance of nuclear power project design and engineering methods at the preliminary stage of its development on nuclear power plant's operational safety from the professional view. Specifically, we share our understanding of national nuclear safety plan's requirement on new reactor accident probability, technology, site selection, as well as building and improving nuclear safety culture and strengthening public participation, with a focus on plan's implications on preliminary stage of nuclear power project development. Last, we introduce China Huaneng Group's work on nuclear power project preliminary development and the experience accumulated during the process. By analyzing the siting philosophy of nuclear power plant and the necessity of building nuclear safety culture at the preliminary stage of nuclear power project development, this study explicates how to fully implement the nuclear safety plan's requirements at the preliminary stage of nuclear power project development. (authors)

  6. Analysing contemporary metropolitan spatial plans in Europe through their institutional context, instrumental content and planning process

    DEFF Research Database (Denmark)

    Elinbaum, Pablo; Galland, Daniel

    2016-01-01

    This article sets out to propose and apply a qualitative framework for thinking about how to analyze and compare metropolitan spatial plans in a milieu of divergent spatial planning traditions and discretionary planning practices. In doing so, the article reviews and develops an understanding...... concerning the institutional context, instrumental content and planning processes associated with four contemporary metropolitan spatial plans in Europe, namely London, Copenhagen, Paris and Barcelona. Through the results of a multiple case study and a subsequent cross comparative analysis, the article...... stresses that contemporary metropolitan spatial plans tend to merge characteristics associated with project-based and strategy-based spatial plans, thus contrasting with the typical land-use character of municipal plans and the often strategic, growth-oriented pursuit of regional plans in Europe...

  7. Managing the construction bidding process : a move to simpler construction plan sets

    Science.gov (United States)

    2001-01-31

    This project was conducted to determine whether construction plan sets could be significantly simplified to speed the process of moving projects to construction. The work steps included a literature review, a telephone survey of highway agencies in s...

  8. Fuzzy multi-project rough-cut capacity planning

    NARCIS (Netherlands)

    Masmoudi, Malek; Hans, Elias W.; Leus, Roel; Hait, Alain; Sotskov, Yuri N.; Werner, Frank

    2014-01-01

    This chapter studies the incorporation of uncertainty into multi-project rough-cut capacity planning. We use fuzzy sets to model uncertainties, adhering to the so-called possibilistic approach. We refer to the resulting proactive planning environment as Fuzzy Rough Cut Capacity Planning (FRCCP).

  9. Review, reaction, and projection: the role of the CFO in planning.

    Science.gov (United States)

    Nauert, R C

    1985-08-01

    In recent years, CFOs have become an integral part of the healthcare organization's strategic planning process. Although not the leader in the process, CFOs should assume a role of review, reaction, and projection. Furthermore, they should oppose any venture that would weaken the financial strength of the institution--whether or not they support the venture on social grounds. The CFO's responsibility in planning is to improve the financial strength of the organization, using support documentation, thorough preparation, and logic. The CEO's concern for community needs and desire to pursue a new business should be tempered by the CFO's financial and economic judgment.

  10. Final Hanford Site Transuranic (TRU) Waste Characterization QA Project Plan

    International Nuclear Information System (INIS)

    GREAGER, T.M.

    2000-01-01

    The Quality Assurance Project Plan (QAPjP) has been prepared for waste characterization activities to be conducted by the Transuranic (TRU) Project at the Hanford Site to meet requirements set forth in the Waste Isolation Pilot Plan (WIPP) Hazardous Waste Facility Permit, 4890139088-TSDF, Attachment B, including Attachments B1 through B6 (WAP) (DOE, 1999a). The QAPjP describes the waste characterization requirements and includes test methods, details of planned waste sampling and analysis, and a description of the waste characterization and verification process. In addition, the QAPjP includes a description of the quality assurance/quality control (QA/QC) requirements for the waste characterization program. Before TRU waste is shipped to the WIPP site by the TRU Project, all applicable requirements of the QAPjP shall be implemented. Additional requirements necessary for transportation to waste disposal at WIPP can be found in the ''Quality Assurance Program Document'' (DOE 1999b) and HNF-2600, ''Hanford Site Transuranic Waste Certification Plan.'' TRU mixed waste contains both TRU radioactive and hazardous components, as defined in the WLPP-WAP. The waste is designated and separately packaged as either contact-handled (CH) or remote-handled (RH), based on the radiological dose rate at the surface of the waste container. RH TRU wastes are not currently shipped to the WIPP facility

  11. LABCORE post release 1.0 development system project management plan

    International Nuclear Information System (INIS)

    Rich, H.S.

    1994-01-01

    The LABCORE post release 1.0 development system project management plan (SPMP) is the primary planning document governing the development of specific enhancements to the LABCORE project. The mission of the Westinghouse Hanford Company (WHC) laboratories is changing from supporting the 200 Area chemical processing plants for process control, waste management, and effluent monitoring to supporting environmental restoration and regulatory compliance commitments. The LABCORE program was implemented as the key element for meeting the commitments by upgrading the laboratories through the implementation of an Automated Data Processing improvement program in January 1994. Scope for LABCORE release 1.0 consisted of hardware and software implementation required to support a minimum number of analyses (Single-Shell Tank [SST] analysis at 222S Laboratory and Performance Evaluation samples at the Waste Sampling Characterization Facility laboratory) using manual entry of data, and to support routine laboratory functions, common to all laboratories. LABCORE post release 1.0 enhancements will expand the functionality presented to the laboratory. Post release 1.0 enhancements will also address the integration of a database for Analytical Services Program Integration, budgeting, and scheduling offices into LABCORE

  12. Detroit Works Long-Term Planning Project: Engagement Strategies for Blending Community and Technical Expertise

    Directory of Open Access Journals (Sweden)

    Toni L. Griffin

    2014-10-01

    Full Text Available In January 2013, civic leaders, community stakeholders, and residents came together to release Detroit Future City: 2012 Detroit Strategic Framework Plan, a guiding blueprint for transforming Detroit from its current state of population loss and excessive vacancy into a model for the reinvention of post-industrial American cities. Three years prior, the U.S. Census had reported that the city had lost 24% of its population over the last decade and had experienced a 20% increase in vacant and abandoned property, bringing total vacancy to roughly the size of Manhattan. In addition to physical and economic challenges, Detroiters had also acknowledged significant barriers to effective civic engagement. Foremost among these barriers were a profound sense of immobilization, planning fatigue, and a general perception of cynicism about planning and engagement efforts. These challenges were compounded by historic racial dynamics and tension. This case study elaborates on the comprehensive and innovative civic engagement executed in a citywide planning process called the Detroit Works Project, which took place from late 2010 through late 2012. For the citywide planning process to be successful and sustainable, civic leaders and project funders committed to a planning initiative that would be different from previous efforts, in large part because the “owners” of the process would be diverse and inclusive across all community sectors. The case study, written by three of the key consultants from the project, describes four key civic engagement strategies deployed in the creation of the strategic framework: (1 addressing profound challenges of culture, race, and politics by deliberately building trust; (2 elevating community expertise by fostering a sense of ownership of the process; (3 blending technical and community expertise; and (4 viewing civic engagement as an ongoing two-way conversation rather than a series of large-scale episodic events. This

  13. Project Plan Remote Target Fabrication Refurbishment Project

    International Nuclear Information System (INIS)

    Bell, Gary L.; Taylor, Robin D.

    2009-01-01

    In early FY2009, the DOE Office of Science - Nuclear Physics Program reinstated a program for continued production of 252 Cf and other transcurium isotopes at the Radiochemical Engineering Development Center (REDC) at Oak Ridge National Laboratory (ORNL). The FY2009 major elements of the workscope are as follows: (1) Recovery and processing of seven transuranium element targets undergoing irradiation at the High Flux Isotope Reactor (HFIR) at ORNL; (2) Development of a plan to manufacture new targets for irradiation beginning in early- to mid-FY10 to supply irradiated targets for processing Campaign 75 (TRU75); and (3) Refurbishment of the target manufacturing equipment to allow new target manufacture in early FY10 The 252 Cf product from processing Campaign 74 (recently processed and currently shipping to customers) is expected to supply the domestic demands for a period of approximately two years. Therefore it is essential that new targets be introduced for irradiation by the second quarter of FY10 (HFIR cycle 427) to maintain supply of 252 Cf; the average irradiation period is ∼10 HFIR cycles, requiring about 1.5 calendar years. The strategy for continued production of 252 Cf depends upon repairing and refurbishing the existing pellet and target fabrication equipment for one additional target production campaign. This equipment dates from the mid-1960s to the late 1980s, and during the last target fabrication campaign in 2005- 2006, a number of component failures and operations difficulties were encountered. It is expected that following the target fabrication and acceptance testing of the targets that will supply material for processing Campaign 75 a comprehensive upgrade and replacement of the remote hot-cell equipment will be required prior to subsequent campaigns. Such a major refit could start in early FY 2011 and would take about 2 years to complete. Scope and cost estimates for the repairs described herein were developed, and authorization for the work

  14. Computational methods for planning and evaluating geothermal energy projects

    International Nuclear Information System (INIS)

    Goumas, M.G.; Lygerou, V.A.; Papayannakis, L.E.

    1999-01-01

    In planning, designing and evaluating a geothermal energy project, a number of technical, economic, social and environmental parameters should be considered. The use of computational methods provides a rigorous analysis improving the decision-making process. This article demonstrates the application of decision-making methods developed in operational research for the optimum exploitation of geothermal resources. Two characteristic problems are considered: (1) the economic evaluation of a geothermal energy project under uncertain conditions using a stochastic analysis approach and (2) the evaluation of alternative exploitation schemes for optimum development of a low enthalpy geothermal field using a multicriteria decision-making procedure. (Author)

  15. FY 1991 project plan for the Hanford Environmental Dose Reconstruction Project, Phase 2

    International Nuclear Information System (INIS)

    1991-02-01

    Phase 1 of the Hanford Environmental Dose Reconstruction Project was designed to develop and demonstrate a method for estimating radiation doses people may have received from Hanford Site operations since 1944. The method researchers developed relied on a variety of measured and reconstructed data as input to a modular computer model that generates dose estimates and their uncertainties. As part of Phase 1, researchers used the reconstructed data and computer model to calculate preliminary dose estimates for populations in a limited geographical area and time period. Phase 2, now under way, is designed to evaluate the Phase 1 data and model and improve them to calculate more accurate and precise dose estimates. Phase 2 will also be used to obtain preliminary estimates of two categories of doses: for Native American tribes and for individuals included in the pilot phase of the Hanford Thyroid Disease Study (HTDS). TSP Directive 90-1 required HEDR staff to develop Phase 2 task plans for TSP approval. Draft task plans for Phase 2 were submitted to the TSP at the October 11--12, 1990 public meeting, and, after discussions of each activity and associated budget needs, the TSP directed HEDR staff to proceed with a slate of specific project activities for FY 1991 of Phase 2. This project plan contains detailed information about those activities. Phase 2 is expected to last 15--18 months. In mid-FY 1991, project activities and budget will be reevaluated to determine whether technical needs or priorities have changed. Separate from, but related to, this project plan, will be an integrated plan for the remainder of the project. HEDR staff will work with the TSP to map out a strategy that clearly describes ''end products'' for the project and the work necessary to complete them. This level of planning will provide a framework within which project decisions in Phases 2, 3, and 4 can be made

  16. Process Management Plans

    Directory of Open Access Journals (Sweden)

    Tomasz Miksa

    2014-07-01

    Full Text Available In the era of research infrastructures and big data, sophisticated data management practices are becoming essential building blocks of successful science. Most practices follow a data-centric approach, which does not take into account the processes that created, analysed and presented the data. This fact limits the possibilities for reliable verification of results. Furthermore, it does not guarantee the reuse of research, which is one of the key aspects of credible data-driven science. For that reason, we propose the introduction of the new concept of Process Management Plans, which focus on the identification, description, sharing and preservation of the entire scientific processes. They enable verification and later reuse of result data and processes of scientific experiments. In this paper we describe the structure and explain the novelty of Process Management Plans by showing in what way they complement existing Data Management Plans. We also highlight key differences, major advantages, as well as references to tools and solutions that can facilitate the introduction of Process Management Plans.

  17. Subjective risk assessment for planning conservation projects

    International Nuclear Information System (INIS)

    Game, Edward T; Fitzsimons, James A; Lipsett-Moore, Geoff; McDonald-Madden, Eve

    2013-01-01

    Conservation projects occur under many types of uncertainty. Where this uncertainty can affect achievement of a project’s objectives, there is risk. Understanding risks to project success should influence a range of strategic and tactical decisions in conservation, and yet, formal risk assessment rarely features in the guidance or practice of conservation planning. We describe how subjective risk analysis tools can be framed to facilitate the rapid identification and assessment of risks to conservation projects, and how this information should influence conservation planning. Our approach is illustrated with an assessment of risks to conservation success as part of a conservation plan for the work of The Nature Conservancy in northern Australia. Risks can be both internal and external to a project, and occur across environmental, social, economic and political systems. Based on the relative importance of a risk and the level of certainty in its assessment we propose a series of appropriate, project level responses including research, monitoring, and active amelioration. Explicit identification, prioritization, and where possible, management of risks are important elements of using conservation resources in an informed and accountable manner. (letter)

  18. Global Threat Reduction Initiative Fuel Thermo-Physical Characterization Project: Sample Management Plan

    Energy Technology Data Exchange (ETDEWEB)

    Casella, Amanda J. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Pereira, Mario M. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Steen, Franciska H. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States)

    2013-01-01

    This sample management plan provides guidelines for sectioning, preparation, acceptance criteria, analytical path, and end-of-life disposal for the fuel element segments utilized in the Global Threat Reduction Initiative (GTRI), Fuel Thermo-Physical Characterization Project. The Fuel Thermo-Physical Characterization Project is tasked with analysis of irradiated Low Enriched Uranium (LEU) Molybdenum (U-Mo) fuel element samples to support the GTRI conversion program. Sample analysis may include optical microscopy (OM), scanning electron microscopy (SEM) fuel-surface interface analysis, gas pycnometry (density) measurements, laser flash analysis (LFA), differential scanning calorimetry (DSC), thermogravimetry and differential thermal analysis with mass spectroscopy (TG /DTA-MS), Inductively Coupled Plasma Spectrophotometry (ICP), alpha spectroscopy, and Thermal Ionization Mass Spectroscopy (TIMS). The project will utilize existing Radiochemical Processing Laboratory (RPL) operating, technical, and administrative procedures for sample receipt, processing, and analyses. Test instructions (TIs), which are documents used to provide specific details regarding the implementation of an existing RPL approved technical or operational procedure, will also be used to communicate to staff project specific parameters requested by the Principal Investigator (PI). TIs will be developed, reviewed, and issued in accordance with the latest revision of the RPL-PLN-700, RPL Operations Plan. Additionally, the PI must approve all project test instructions and red-line changes to test instructions.

  19. Pad A treatability study long-range project plan

    International Nuclear Information System (INIS)

    Mousseau, J.D.

    1991-06-01

    This plan addresses the work to be accomplished by the Pad A Treatability Study Project. The purpose of this project is to investigate potential treatment and separation technologies, identify the best technologies, and to demonstrate by both lab- and pilot-scale demonstration, the most applicable remedial technologies for treating plutonium-contaminated salts at the Pad A site located at the Subsurface Disposal Area (SDA) at the Radioactive Waste Management Complex (RWMC) a the Idaho National Engineering Laboratory (INEL). The conduct of this project will be supported by other DOE laboratories, universities, and private industries, who will provide support for near-term demonstrations of treatment and separation technologies. The purpose of this long-range planning document is to present the detailed plan for the implementation of the Pad A Treatability Study Project

  20. Fast flux test facility, transition project plan

    International Nuclear Information System (INIS)

    Guttenberg, S.

    1994-01-01

    The FFTF Transition Project Plan, Revision 1, provides changes and project baseline for the deactivation activities necessary to transition the FFTF to a radiologically and industrially safe shutdown condition

  1. Fast flux test facility, transition project plan

    Energy Technology Data Exchange (ETDEWEB)

    Guttenberg, S.

    1994-11-15

    The FFTF Transition Project Plan, Revision 1, provides changes and project baseline for the deactivation activities necessary to transition the FFTF to a radiologically and industrially safe shutdown condition.

  2. Project W-320 ALARA Plan

    International Nuclear Information System (INIS)

    Harty, W.M.

    1995-01-01

    This supporting document establishes the As Low As Reasonable Achievable (ALARA) Plan to be followed during Sluicing Project W-320 design and construction activities to minimize personnel exposure to radiation and hazardous materials

  3. Project W-320 ALARA Plan

    Energy Technology Data Exchange (ETDEWEB)

    Harty, W.M.

    1995-06-06

    This supporting document establishes the As Low As Reasonable Achievable (ALARA) Plan to be followed during Sluicing Project W-320 design and construction activities to minimize personnel exposure to radiation and hazardous materials.

  4. Planning and leading of the technological processes by mechanical working with microsoft project

    Science.gov (United States)

    Nae, I.; Grigore, N.

    2016-08-01

    Nowadays, fabrication systems and methods are being modified; new processing technologies come up, flow sheets develop a minimum number of phases, the flexibility of the technologies grows up, new methods and instruments of monitoring and leading the processing operations also come up. The technological course (route, entry, scheme, guiding) referring to the series of the operation, putting and execution phases of a mark in order to obtain the final product from the blank is represented by a sequence of activities realized by a logic manner, on a well determined schedule, with a determined budget and resources. Also, a project can be defined as a series of specific activities, methodical structured which they aim to finish a specific objective, within a fixed schedule and budget. Within the homogeneity between the project and the technological course, this research is presenting the defining of the technological course of mechanical chip removing process using Microsoft Project. Under these circumstances, this research highlights the advantages of this method: the celerity using of other technological alternatives in order to pick the optimal process, the job scheduling being constrained by any kinds, the standardization of some processing technological operations.

  5. Quality planning in Construction Project

    Science.gov (United States)

    Othman, I.; Shafiq, Nasir; Nuruddin, M. F.

    2017-12-01

    The purpose of this paper is to investigate deeper on the factors that contribute to the effectiveness of quality planning, identifying the common problems encountered in quality planning, practices and ways for improvements in quality planning for construction projects. This paper involves data collected from construction company representatives across Malaysia that are obtained through semi-structured interviews as well as questionnaire distributions. Results shows that design of experiments (average index: 4.61), inspection (average index: 4.45) and quality audit as well as other methods (average index: 4.26) rank first, second and third most important factors respectively.

  6. 7 CFR 1948.78 - Growth management and housing planning projects.

    Science.gov (United States)

    2010-01-01

    ... 7 Agriculture 13 2010-01-01 2009-01-01 true Growth management and housing planning projects. 1948... Impacted Area Development Assistance Program § 1948.78 Growth management and housing planning projects. (a) Existing plans for growth management and housing may be used to meet the planning requirements of this...

  7. Research Planning Process

    Science.gov (United States)

    Lofton, Rodney

    2010-01-01

    This presentation describes the process used to collect, review, integrate, and assess research requirements desired to be a part of research and payload activities conducted on the ISS. The presentation provides a description of: where the requirements originate, to whom they are submitted, how they are integrated into a requirements plan, and how that integrated plan is formulated and approved. It is hoped that from completing the review of this presentation, one will get an understanding of the planning process that formulates payload requirements into an integrated plan used for specifying research activities to take place on the ISS.

  8. Spent nuclear fuel project multi-year work plan WBS number 1.4.1

    International Nuclear Information System (INIS)

    Wells, J.L.

    1997-01-01

    The Spent Nuclear Fuel (SNF) Project Multi-Year Work Plan (MYWP) is a controlled living document that contains the current SNF Project Technical, Schedule and Cost Baselines. These baselines reflect the current Project execution strategies and are controlled via the change control process. Other changes to the MYWP document will be controlled using the document control process. These changes will be processed as they are approved to keep the MYWP a living document. The MYWP will be maintained continuously as the project baseline through the life of the project and not revised annually. The MYWP is the one document which summarizes and links these three baselines in one place. Supporting documentation for each baseline referred to herein may be impacted by changes to the MYWP, and must also be revised through change control to maintain consistency

  9. Early environmental planning: A process for power line corridor selection

    International Nuclear Information System (INIS)

    Haagenstad, T.; Bare, C.M.

    1998-01-01

    Los Alamos National Laboratory (LANL) conducted an environmental planning study in the fall of 1997 to help determine the best alternative for upgrading the Laboratory's electrical power system. Alternatives considered included an on-site power generation facility and two corridors for a 10-mile-long 115-kV power line. This planning process was conducted prior to the formal National Environmental Policy Act (NEPA) review. The goals were to help select the best proposed action, to recommend modifications and mitigation measures for each alternative for a more environmentally sound project, and to avoid potential delays once the formal Department of Energy review process began. Significant constraints existed from a planning perspective, including operational issues such as existing outdoor high explosives testing areas, as well as environmental issues including threatened and endangered species habitats, multiple archeological sites, contaminated areas, and aesthetics. The study had to be completed within 45 days to meet project schedule needs. The process resulted in a number of important recommendations. While the construction and operation of the on-site power generation facility could have minimal environmental impacts, the need for a new air quality permit would create severe cost and schedule constraints for the project. From an environmental perspective, construction and operation of a power line within either corridor was concluded to be a viable alternative. However, impacts with either corridor would have to be reduced through specific recommended alignment modifications and mitigation measures

  10. UMTRA Project environmental, health, and safety plan

    International Nuclear Information System (INIS)

    1989-02-01

    The basic health and safety requirements established in this plan are designed to provide guidelines to be applied at all Uranium Mill Tailings Remedial Action (UMTRA) Project sites. Specific restrictions are given where necessary. However, an attempt has been made to provide guidelines which are generic in nature, and will allow for evaluation of site-specific conditions. Health and safety personnel are expected to exercise professional judgment when interpreting these guidelines to ensure the health and safety of project personnel and the general population. This UMTRA Project Environmental, Health, and Safety (EH ampersand S) Plan specifies the basic Federal health and safety standards and special DOE requirements applicable to this program. In addition, responsibilities in carrying out this plan are delineated. Some guidance on program requirements and radiation control and monitoring is also included. An Environmental, Health, and Safety Plan shall be developed as part of the remedial action plan for each mill site and associated disposal site. Special conditions at the site which may present potential health hazards will be described, and special areas that should should be addressed by the Remedial Action Contractor (RAC) will be indicated. Site-specific EH ampersand S concerns will be addressed by special contract conditions in RAC subcontracts. 2 tabs

  11. 7 CFR 1219.50 - Budgets, programs, plans, and projects.

    Science.gov (United States)

    2010-01-01

    ... of appropriate programs, plans, or projects for advertising, sales promotion, other promotion, and... HASS AVOCADO PROMOTION, RESEARCH, AND INFORMATION Hass Avocado Promotion, Research, and Information... promotion, industry information, consumer information, and related research programs, plans, and projects...

  12. Fiscal planning of private electricity production projects

    International Nuclear Information System (INIS)

    Gauthier, R.

    2002-01-01

    Various fiscal considerations frequently encountered in the context of the planning of private electricity production projects were described. Two major themes were discussed: 1) the different jurisdictional vehicles that can be used during the planning of private electricity production projects and the associated fiscal considerations, and 2) the two main fiscal incentives of the Income Tax Act (Canada) which could impact on the financing and operation costs of such a project, namely the accelerated amortization and the possibility of deducting the costs associated to renewable energies and energy savings in Canada. This was a general presentation that did not go into specific details and did not represent a legal opinion. refs

  13. FY95 software project management plan: TMACS, CASS computer systems

    International Nuclear Information System (INIS)

    Spurling, D.G.

    1994-01-01

    The FY95 Work Plan for TMACS and CASS Software Projects describes the activities planned for the current fiscal year. This plan replaces WHC-SD-WM-SDP-008. The TMACS project schedule is included in the TWRS Integrated Schedule

  14. Quality assurance program plan fuel supply shutdown project

    International Nuclear Information System (INIS)

    Metcalf, I.L.

    1998-01-01

    This Quality Assurance Program plan (QAPP) describes how the Fuel Supply Shutdown (FSS) project organization implements the quality assurance requirements of HNF-MP-599, Project Hanford Quality Assurance Program Description (QAPD) and the B and W Hanford Company Quality Assurance Program Plan (QAPP), FSP-MP-004. The QAPP applies to facility structures, systems, and components and to activities (e.g., design, procurement, testing, operations, maintenance, etc.) that could affect structures, systems, and components. This QAPP also provides a roadmap of applicable Project Hanford Policies and Procedures (PHPP) which may be utilized by the FSS project organization to implement the requirements of this QAPP

  15. Project management plan for exploratory shaft at Yucca Mountain

    International Nuclear Information System (INIS)

    1983-08-01

    This Project Management Plan (PMP) provides the basic guidance and describes the organizational structure and procedures for the design, construction, and testing of a large-diameter Exploratory Shaft (ES) in tuffaceous media as a major element within the Nevada Nuclear Waste Storage Investigations (NNWSI) project, which is a part of the National Waste Terminal Storage (NWTS) Program, US Department of Energy (DOE). The PMP encompasses activities identified as construction phase and in situ phase testing to be conducted from the ES through September 30, 1986. Specific topics addressed are the ES project objectives, the management organization and responsibilities, functional support requirements, work plan (including quality assurance aspects), work breakdown structure, milestone schedule, logic diagram, performance criteria, cost estimates, management control systems, procurement plan, test plan, and environmental, health and safety plans

  16. Planned Positron Factory project

    International Nuclear Information System (INIS)

    Okada, Sohei

    1990-01-01

    The Japan Atomic Energy Research Institute, JAERI, has started, drafting a construction plan for the 'Positron Factory', in which intense energy-controllable monoenergetic positron beams are produced from pair-production reactions caused by high-energy electrons from a linac. The JAERI organized a planning committee to provide a basic picture for the Positron Factory. This article presents an overview of the interactions of positrons, intense positron sources and the research program and facilities planned for the project. The interactions of positrons and intense positron sources are discussed focusing on major characteristics of positrons in different energy ranges. The research program for the Positron Factory is then outlined, focusing on advanced positron annihilation techniques, positron spectroscopy (diffraction, scattering, channeling, microscopy), basic positron physics (exotic particle science), and positron beam technology. Discussion is also made of facilities required for the Positron Factory. (N.K.)

  17. Graduate Student Project: Operations Management Product Plan

    Science.gov (United States)

    Fish, Lynn

    2007-01-01

    An operations management product project is an effective instructional technique that fills a void in current operations management literature in product planning. More than 94.1% of 286 graduates favored the project as a learning tool, and results demonstrate the significant impact the project had in predicting student performance. The author…

  18. Siberian Chemical Combine laboratory project work plan, fiscal year 1999

    International Nuclear Information System (INIS)

    Morgado, R.E.; Acobyan, R.; Shropsire, R.

    1998-01-01

    The Siberian Chemical Combine (SKhK), Laboratory Project Work Plan (Plan) is intended to assist the US Laboratory Project Team, and Department of Energy (DOE) staff with the management of the FY99 joint material protection control and accounting program (MPC and A) for enhancing nuclear material safeguards within the Siberian Chemical Combine. The DOE/Russian/Newly Independent States, Nuclear Material Task Force, uses a project work plan document for higher-level program management. The SKhK Plan is a component of the Russian Defense related Sites' input to that document. In addition, it contains task descriptions and a Gantt Chart covering the FY99 time-period. This FY99 window is part of a comprehensive, Project Status Gantt Chart for tasking and goal setting that extends to the year 2003. Secondary and tertiary levels of detail are incorporated therein and are for the use of laboratory project management. The SKhK Plan is a working document, and additions and modifications will be incorporated as the MPC and A project for SKhK evolves

  19. Planned and ongoing projects (pop) database: development and results.

    Science.gov (United States)

    Wild, Claudia; Erdös, Judit; Warmuth, Marisa; Hinterreiter, Gerda; Krämer, Peter; Chalon, Patrice

    2014-11-01

    The aim of this study was to present the development, structure and results of a database on planned and ongoing health technology assessment (HTA) projects (POP Database) in Europe. The POP Database (POP DB) was set up in an iterative process from a basic Excel sheet to a multifunctional electronic online database. The functionalities, such as the search terminology, the procedures to fill and update the database, the access rules to enter the database, as well as the maintenance roles, were defined in a multistep participatory feedback loop with EUnetHTA Partners. The POP Database has become an online database that hosts not only the titles and MeSH categorizations, but also some basic information on status and contact details about the listed projects of EUnetHTA Partners. Currently, it stores more than 1,200 planned, ongoing or recently published projects of forty-three EUnetHTA Partners from twenty-four countries. Because the POP Database aims to facilitate collaboration, it also provides a matching system to assist in identifying similar projects. Overall, more than 10 percent of the projects in the database are identical both in terms of pathology (indication or disease) and technology (drug, medical device, intervention). In addition, approximately 30 percent of the projects are similar, meaning that they have at least some overlap in content. Although the POP DB is successful concerning regular updates of most national HTA agencies within EUnetHTA, little is known about its actual effects on collaborations in Europe. Moreover, many non-nationally nominated HTA producing agencies neither have access to the POP DB nor can share their projects.

  20. Breckinridge Project, initial effort. Report VII, Volume 4. Safety and health plan

    Energy Technology Data Exchange (ETDEWEB)

    None

    1982-01-01

    The Safety and Health Plan recognizes the potential hazards associated with the Project and has been developed specifically to respond to these risks in a positive manner. Prevention, the primary objective of the Plan, starts with building safety controls into the process design and continues through engineering, construction, start-up, and operation of the Project facilities and equipment. Compliance with applicable federal, state, and local health and safety laws, regulations, and codes throughout all Project phases is required and assured. The Plan requires that each major Project phase be thoroughly reviewed and analyzed to determine that those provisions required to assure the safety and health of all employees and the public, and to prevent property and equipment losses, have been provided. The Plan requires followup on those items or situations where corrective action needs were identified to assure that the action was taken and is effective. Emphasis is placed on loss prevention. Exhibit 1 provides a breakdown of Ashland Synthetic Fuels, Inc.'s (ASFI's) Loss Prevention Program. The Plan recognizes that the varied nature of the work is such as to require the services of skilled, trained, and responsible personnel who are aware of the hazards and know that the work can be done safely, if done correctly. Good operating practice is likewise safe operating practice. Training is provided to familiarize personnel with good operational practice, the general sequence of activities, reporting requirements, and above all, the concept that each step in the operating procedures must be successfully concluded before the following step can be safely initiated. The Plan provides for periodic review and evaluation of all safety and loss prevention activities at the plant and departmental levels.

  1. 7 CFR 275.18 - Project area/management unit corrective action plan.

    Science.gov (United States)

    2010-01-01

    ... 7 Agriculture 4 2010-01-01 2010-01-01 false Project area/management unit corrective action plan... SYSTEM Corrective Action § 275.18 Project area/management unit corrective action plan. (a) The State agency shall ensure that corrective action plans are prepared at the project area/management unit level...

  2. UMTRA Project water sampling and analysis plan, Gunnison, Colorado: Revision 1

    International Nuclear Information System (INIS)

    1994-11-01

    This water sampling and analysis plan summarizes the results of previous water sampling activities and the plan for future water sampling activities, in accordance with the Guidance Document for Preparing Sampling and Analysis Plans for UMTRA Sites. A buffer zone monitoring plan for the Dos Rios Subdivision is included as an appendix. The buffer zone monitoring plan was developed to ensure continued protection to the public from residual contamination. The buffer zone is beyond the area depicted as contaminated ground water due to former milling operations. Surface remedial action at the Gunnison Uranium Mill Tailings Remedial Action Project site began in 1992; completion is expected in 1995. Ground water and surface water will be sampled semiannually at the Gunnison processing site and disposal site. Results of previous water sampling at the Gunnison processing site indicate that ground water in the alluvium is contaminated by the former uranium processing activities. Background ground water conditions have been established in the uppermost aquifer at the Gunnison disposal site. The monitor well locations provide a representative distribution of sampling points to characterize ground water quality and ground water flow conditions in the vicinity of the sites. The list of analytes has been modified with time to reflect constituents that are related to uranium processing activities and the parameters needed for geochemical evaluation

  3. Technical Approach and Plan for Transitioning Spent Nuclear Fuel (SNF) Project Facilities to the Environmental Restoration Program

    International Nuclear Information System (INIS)

    SKELLY, W.A.

    1999-01-01

    This document describes the approach and process in which the 100-K Area Facilities are to be deactivated and transitioned over to the Environmental Restoration Program after spent nuclear fuel has been removed from the K Basins. It describes the Transition Project's scope and objectives, work breakdown structure, activity planning, estimated cost, and schedule. This report will be utilized as a planning document for project management and control and to communicate details of project content and integration

  4. Tank Waste Remediation System Projects Document Control Plan

    International Nuclear Information System (INIS)

    Slater, G.D.; Halverson, T.G.

    1994-01-01

    The purpose of this Tank Waste Remediation System Projects Document Control Plan is to provide requirements and responsibilities for document control for the Hanford Waste Vitrification Plant (HWVP) Project and the Initial Pretreatment Module (IPM) Project

  5. The Groundwater Performance Assessment Project Quality Assurance Plan

    International Nuclear Information System (INIS)

    Luttrell, Stuart P.

    2006-01-01

    U.S. Department of Energy (DOE) has monitored groundwater on the Hanford Site since the 1940s to help determine what chemical and radiological contaminants have made their way into the groundwater. As regulatory requirements for monitoring increased in the 1980s, there began to be some overlap between various programs. DOE established the Groundwater Performance Assessment Project (groundwater project) in 1996 to ensure protection of the public and the environment while improving the efficiency of monitoring activities. The groundwater project is designed to support all groundwater monitoring needs at the site, eliminate redundant sampling and analysis, and establish a cost-effective hierarchy for groundwater monitoring activities. This document provides the quality assurance guidelines that will be followed by the groundwater project. This QA Plan is based on the QA requirements of DOE Order 414.1C, Quality Assurance, and 10 CFR 830, Subpart A--General Provisions/Quality Assurance Requirements as delineated in Pacific Northwest National Laboratory's Standards-Based Management System. In addition, the groundwater project is subject to the Environmental Protection Agency (EPA) Requirements for Quality Assurance Project Plans (EPA/240/B-01/003, QA/R-5). The groundwater project has determined that the Hanford Analytical Services Quality Assurance Requirements Documents (HASQARD, DOE/RL-96-68) apply to portions of this project and to the subcontractors. HASQARD requirements are discussed within applicable sections of this plan

  6. 7 CFR 1250.314 - Plans and projects.

    Science.gov (United States)

    2010-01-01

    ... research, consumer and producer education, advertising, marketing, product development, and promotion plans... 7 Agriculture 10 2010-01-01 2010-01-01 false Plans and projects. 1250.314 Section 1250.314 Agriculture Regulations of the Department of Agriculture (Continued) AGRICULTURAL MARKETING SERVICE (MARKETING...

  7. Negotiation processes in urban redevelopment projects: dealing with conflicts by balancing integrative and distributive approaches

    NARCIS (Netherlands)

    Baarveld, Marlijn; Smit, Marnix; Dewulf, Geert P.M.R.

    2015-01-01

    Dealing with conflict through dialogue receives considerable attention in current planning approaches. However, debate and negotiation are also inevitable features in the planning of urban redevelopment projects. Insight into the negotiation process contributes to current planning practice as

  8. The Soils and Groundwater – EM-20 S&T Roadmap Quality Assurance Project Plan

    Energy Technology Data Exchange (ETDEWEB)

    Fix, N. J.

    2008-02-11

    The Soils and Groundwater – EM-20 Science and Technology Roadmap Project is a U.S. Department of Energy, Office of Environmental Management-funded initiative designed to develop new methods, strategies and technology for characterizing, modeling, remediating, and monitoring soils and groundwater contaminated with metals, radionuclides, and chlorinated organics. This Quality Assurance Project Plan provides the quality assurance requirements and processes that will be followed by EM-20 Roadmap Project staff.

  9. Guidance and Control Software Project Data - Volume 1: Planning Documents

    Science.gov (United States)

    Hayhurst, Kelly J. (Editor)

    2008-01-01

    The Guidance and Control Software (GCS) project was the last in a series of software reliability studies conducted at Langley Research Center between 1977 and 1994. The technical results of the GCS project were recorded after the experiment was completed. Some of the support documentation produced as part of the experiment, however, is serving an unexpected role far beyond its original project context. Some of the software used as part of the GCS project was developed to conform to the RTCA/DO-178B software standard, "Software Considerations in Airborne Systems and Equipment Certification," used in the civil aviation industry. That standard requires extensive documentation throughout the software development life cycle, including plans, software requirements, design and source code, verification cases and results, and configuration management and quality control data. The project documentation that includes this information is open for public scrutiny without the legal or safety implications associated with comparable data from an avionics manufacturer. This public availability has afforded an opportunity to use the GCS project documents for DO-178B training. This report provides a brief overview of the GCS project, describes the 4-volume set of documents and the role they are playing in training, and includes the planning documents from the GCS project. Volume 1 contains five appendices: A. Plan for Software Aspects of Certification for the Guidance and Control Software Project; B. Software Development Standards for the Guidance and Control Software Project; C. Software Verification Plan for the Guidance and Control Software Project; D. Software Configuration Management Plan for the Guidance and Control Software Project; and E. Software Quality Assurance Activities.

  10. H2020 692819 SIMPATICO - D1.1: Project Management Plan

    OpenAIRE

    Forner, Pamela; Gerosa, Matteo; Folograna, Antonio

    2017-01-01

    This document is the deliverable “D1.1 – Project Management Plan” of the European project “SIMPATICO - SIMplifying the interaction with Public Administration Through Information technology for Citizens and cOmpanies” (hereinafter also referred to as “SIMPATICO”, project reference: 692819). The SIMPATICO Project Management Plan (PMP) is the main planning document and describes how major aspects of the project are managed, monitored and controlled. It is intended to provide gu...

  11. Spent nuclear fuel project multi-year work plan WBS {number_sign}1.4.1

    Energy Technology Data Exchange (ETDEWEB)

    Wells, J.L.

    1997-03-01

    The Spent Nuclear Fuel (SNF) Project Multi-Year Work Plan (MYWP) is a controlled living document that contains the current SNF Project Technical, Schedule and Cost Baselines. These baselines reflect the current Project execution strategies and are controlled via the change control process. Other changes to the MYWP document will be controlled using the document control process. These changes will be processed as they are approved to keep the MYWP a living document. The MYWP will be maintained continuously as the project baseline through the life of the project and not revised annually. The MYWP is the one document which summarizes and links these three baselines in one place. Supporting documentation for each baseline referred to herein may be impacted by changes to the MYWP, and must also be revised through change control to maintain consistency.

  12. A planning support system to optimize approval of private housing development projects

    Science.gov (United States)

    Hussnain, M. Q.; Wakil, K.; Waheed, A.; Tahir, A.

    2016-06-01

    Out of 182 million population of Pakistan, 38% reside in urban areas having an average growth rate of 1.6%, raising the urban housing demand significantly. Poor state response to fulfil the housing needs has resulted in a mushroom growth of private housing schemes (PHS) over the years. Consequently, only in five major cities of Punjab, there are 383 legal and 150 illegal private housing development projects against 120 public sector housing schemes. A major factor behind the cancerous growth of unapproved PHS is the prolonged and delayed approval process in concerned approval authorities requiring 13 months on average. Currently, manual and paper-based approaches are used for vetting and for granting the permission which is highly subjective and non-transparent. This study aims to design a flexible planning support system (PSS) to optimize the vetting process of PHS projects under any development authority in Pakistan by reducing time and cost required for site and documents investigations. Relying on the review of regulatory documents and interviews with professional planners and land developers, this study describes the structure of a PSS developed using open- source geo-spatial tools such as OpenGeo Suite, PHP, and PostgreSQL. It highlights the development of a Knowledge Module (based on regulatory documents) containing equations related to scheme type, size (area), location, access road, components of layout plan, planning standards and other related approval checks. Furthermore, it presents the architecture of the database module and system data requirements categorized as base datasets (built-in part of PSS) and input datasets (related to the housing project under approval). It is practically demonstrated that developing a customized PSS to optimize PHS approval process in Pakistan is achievable with geospatial technology. With the provision of such a system, the approval process for private housing schemes not only becomes quicker and user-friendly but also

  13. 233S Decommissioning Project Environmental Control Plan

    International Nuclear Information System (INIS)

    Zoric, J.P.

    2000-01-01

    This Environmental Control Plan is for the 233S Decommissioning activities conducted under the removal action report for the 233S Decontamination and Demolition Project. The purpose of this ECP is to identify environmental requirements for the 233S project. The ECP is a compilation of existing environmental permit conditions, regulatory requirements, and environmental requirements applicable to the specific project or functional activity

  14. Quality assurance program plan for SNF characterization support project

    International Nuclear Information System (INIS)

    Tanke, J.M.

    1997-01-01

    This Quality Assurance Program Plan (QAPP) provides information on how the Quality Assurance Program is implemented for the Spent Nuclear Fuel Characterization Support Project. This QAPP has been developed specifically for the Spent Nuclear Fuel Characterization Support Project, per Letter of Instruction (LOI) from Duke Engineering and Services Company, letter No. DESH-9655870, dated Nov. 22, 1996. It applies to those items and tasks which affect the completion of activities identified in the work breakdown structure of the Project Management Plan (PMP) and LOI. These activities include installation of sectioning equipment and furnace, surface and subsurface examinations, sectioning for metallography, and element drying and conditioning testing, as well as project related operations within the 327 facility as it relates to the specific activities of this project. General facility activities are covered in other appropriate QA-PPS. In addition, this QAPP supports the related quality assurance activities addressed in CM-2-14, Hazardous Material Packaging and Shipping,1261 and HSRCM-1, Hanford Site Radiological Control Manual. The 327 Building is currently transitioning from being a Pacific Northwest National Laboratory (PNNL) managed facility to a Babcock and Wilcox Hanford Company (BVMC) managed facility. During this transition process existing procedures and documents will be utilized until replaced by BVMC procedures and documents. These documents conform to the requirements found in PNL-MA-70, Quality Assurance Manual and PNL-MA-8 1, Hazardous Materials Shipping Manual. The Quality Assurance Program Index (QAPI) contained in Table 1 provides a matrix which shows how project activities relate to IO CFR 830.120 and 5700.6C criteria. Quality Assurance program requirements will be addressed separate from the requirements specified in this document. Other Hanford Site organizations/companies may be utilized in support of this project and the subject organizations are

  15. Strategic plan: A tool to improve IPP project earnings

    International Nuclear Information System (INIS)

    LeClerc, S.

    1997-01-01

    This paper presents a strategic plan to analyze and convert project operations to gain short-term and long-term economic benefits. Areas of Opportunity were identified which may result in improved project economics from Independent Power Producers' project reviews. This paper discusses each Area of Opportunity, suggests options for investigation, and provides a potential magnitude of upside for solid fuel circulating fluidized bed projects in the 50 MW project size. The Areas of Opportunity are: (1) Power Purchase Agreement Modifications; (2) Fuel Use Optimization; (3) Power Plant Upgrades; (4) Power Plant Depreciation Schedule And FAS 121 Analysis; (5) Operation ampersand Maintenance Review; (6) Financial Contract Review; (7) Environmental Review; (8) Insurance Coverage Review; (9) Internal Management Review; and (10) Strategic Development For Energy Sales. Ten appendices are included which comprise a sample Strategic Plan: (1) Potential Plant Upgrades, (2) Enhancement Criteria, (3) Age of Coal Burning Plants, (4) Btu Energy Price Summary, (5) Typical Operation and Maintenance Audit Findings, (6) Typical Performance Objectives and Guidelines, (7) Typical Heavy Metal Emissions, (8) Typical Strategic Plan Formulation, (9) Strategic Plan Implementation Schedule, and (10) Typical Decision Tree. 8 refs

  16. Strategic planning: the first step in the planning process.

    Science.gov (United States)

    Gelinas, Marc A

    2003-01-01

    Strategic planning is a systematic process through which an organization builds commitment among key stakeholders to goals and priorities which are essential to its mission and vision, and responsive to the operating environment. Strategic planning is the first step in a comprehensive planning process that also includes business planning and implementation planning. If all three steps are carried out in sequence, strategic planning can be a very effective means of educating the stakeholders about where the cancer program is and where it is going, gaining support and commitment for the direction that the cancer program will take, and assuring that everyone's expectations can be managed effectively. Unfortunately, some organizations and cancer program leaders misunderstand the process. Too often, strategic planning is used as a stand-alone activity. This article will describe what strategic planning is, how it should smoothly lead into business planning and implementation planning, and how to avoid the pitfalls that sometimes arise during the strategic planning effort.

  17. Conservation Action Planning: Lessons learned from the St. Marys River watershed biodiversity conservation planning process

    Science.gov (United States)

    Patterson, Tamatha A.; Grundel, Ralph

    2014-01-01

    Conservation Action Planning (CAP) is an adaptive management planning process refined by The Nature Conservancy (TNC) and embraced worldwide as the Open Standards for the Practice of Conservation. The CAP process facilitates open, multi-institutional collaboration on a common conservation agenda through organized actions and quantified results. While specifically designed for conservation efforts, the framework is adaptable and flexible to multiple scales and can be used for any collaborative planning effort. The CAP framework addresses inception; design and development of goals, measures, and strategies; and plan implementation and evaluation. The specific components of the CAP include defining the project scope and conservation targets; assessing the ecological viability; ascertaining threats and surrounding situation; identifying opportunities and designing strategies for action; and implementing actions and monitoring results. In 2007, TNC and a multidisciplinary graduate student team from the University of Michigan's School of Natural Resources and Environment initiated a CAP for the St. Marys River, the connecting channel between Lake Superior and Lake Huron, and its local watershed. The students not only gained experience in conservation planning, but also learned lessons that notably benefited the CAP process and were valuable for any successful collaborative effort—a dedicated core team improved product quality, accelerated the timeline, and provided necessary support for ongoing efforts; an academic approach in preparation for engagement in the planning process brought applicable scientific research to the forefront, enhanced workshop facilitation, and improved stakeholder participation; and early and continuous interactions with regional stakeholders improved cooperation and built a supportive network for collaboration.

  18. Hanford Waste Vitrification Plant Project Waste Form Qualification Program Plan

    International Nuclear Information System (INIS)

    Randklev, E.H.

    1993-06-01

    The US Department of Energy has created a waste acceptance process to help guide the overall program for the disposal of high-level nuclear waste in a federal repository. This Waste Form Qualification Program Plan describes the hierarchy of strategies used by the Hanford Waste Vitrification Plant Project to satisfy the waste form qualification obligations of that waste acceptance process. A description of the functional relationship of the participants contributing to completing this objective is provided. The major activities, products, providers, and associated scheduling for implementing the strategies also are presented

  19. Life sciences payloads analyses and technical program planning studies. [project planning of space missions of space shuttles in aerospace medicine and space biology

    Science.gov (United States)

    1976-01-01

    Contractural requirements, project planning, equipment specifications, and technical data for space shuttle biological experiment payloads are presented. Topics discussed are: (1) urine collection and processing on the space shuttle, (2) space processing of biochemical and biomedical materials, (3) mission simulations, and (4) biomedical equipment.

  20. The development of stochastic process modeling through risk analysis derived from scheduling of NPP project

    International Nuclear Information System (INIS)

    Lee, Kwang Ho; Roh, Myung Sub

    2013-01-01

    There are so many different factors to consider when constructing a nuclear power plant successfully from planning to decommissioning. According to PMBOK, all projects have nine domains from a holistic project management perspective. They are equally important to all projects, however, this study focuses mostly on the processes required to manage timely completion of the project and conduct risk management. The overall objective of this study is to let you know what the risk analysis derived from scheduling of NPP project is, and understand how to implement the stochastic process modeling through risk management. Building the Nuclear Power Plant is required a great deal of time and fundamental knowledge related to all engineering. That means that integrated project scheduling management with so many activities is necessary and very important. Simulation techniques for scheduling of NPP project using Open Plan program, Crystal Ball program, and Minitab program can be useful tools for designing optimal schedule planning. Thus far, Open Plan and Monte Carlo programs have been used to calculate the critical path for scheduling network analysis. And also, Minitab program has been applied to monitor the scheduling risk. This approach to stochastic modeling through risk analysis of project activities is very useful for optimizing the schedules of activities using Critical Path Method and managing the scheduling control of NPP project. This study has shown new approach to optimal scheduling of NPP project, however, this does not consider the characteristic of activities according to the NPP site conditions. Hence, this study needs more research considering those factors

  1. The development of stochastic process modeling through risk analysis derived from scheduling of NPP project

    Energy Technology Data Exchange (ETDEWEB)

    Lee, Kwang Ho; Roh, Myung Sub [KEPCO International Nuclear Graduate School, Ulsan (Korea, Republic of)

    2013-10-15

    There are so many different factors to consider when constructing a nuclear power plant successfully from planning to decommissioning. According to PMBOK, all projects have nine domains from a holistic project management perspective. They are equally important to all projects, however, this study focuses mostly on the processes required to manage timely completion of the project and conduct risk management. The overall objective of this study is to let you know what the risk analysis derived from scheduling of NPP project is, and understand how to implement the stochastic process modeling through risk management. Building the Nuclear Power Plant is required a great deal of time and fundamental knowledge related to all engineering. That means that integrated project scheduling management with so many activities is necessary and very important. Simulation techniques for scheduling of NPP project using Open Plan program, Crystal Ball program, and Minitab program can be useful tools for designing optimal schedule planning. Thus far, Open Plan and Monte Carlo programs have been used to calculate the critical path for scheduling network analysis. And also, Minitab program has been applied to monitor the scheduling risk. This approach to stochastic modeling through risk analysis of project activities is very useful for optimizing the schedules of activities using Critical Path Method and managing the scheduling control of NPP project. This study has shown new approach to optimal scheduling of NPP project, however, this does not consider the characteristic of activities according to the NPP site conditions. Hence, this study needs more research considering those factors.

  2. Overview criteria for the environmental, safety and health evaluation of remedial action project planning

    International Nuclear Information System (INIS)

    Stenner, R.D.; Denham, D.H.

    1984-10-01

    Overview criteria (i.e., subject areas requiring review) for evaluating remedial action project plans with respect to environmental, safety and health issues were developed as part of a Department of Energy, Office of Operational Safety, technical support project. Nineteen elements were identified as criteria that should be addressed during the planning process of a remedial action (decontamination and decommissioning) project. The scope was interpreted broadly enough to include such environmental, safety and health issues as public image, legal obligation and quality assurance, as well as more obvious concerns such as those involving the direct protection of public and worker health. The nineteen elements are discussed along with suggested ways to use a data management software system to organize and report results

  3. Project X Accelerator R and D Plan

    International Nuclear Information System (INIS)

    2008-01-01

    Project X is a high intensity proton facility conceived to support a world-leading program in neutrino and flavor physics over the next two decades at Fermilab. Project X is an integral part of the Fermilab Roadmap as described in the Fermilab Steering Group Report. Project X is based on an 8 GeV superconducting H-linac, paired with the existing (but modified) Main Injector and Recycler Ring, to provide in excess of 2 MW of beam power throughout the energy range 60-120 GeV, simultaneous with at least 100 kW of beam power at 8 GeV. The linac utilizes technology in common with the ILC over the energy range 0.6-8.0 GeV. Beam current parameters can be made identical to ILC resulting in identical rf generation and distribution systems. This alignment of ILC and Project X technologies allows for a shared development effort. The initial 0.6 GeV of the linac draws heavily on technology developed by Argonne National Laboratory for a facility for rare isotope beams. It is anticipated that the exact configuration and operating parameters of the linac will be defined through the R and D program and will retain alignment with the ILC plan as it evolves over this period. Utilization of the Recycler Ring as an H - stripper and accumulator ring is the key element that provides the flexibility to operate the linac with the same beam parameters as the ILC. The linac operates at 5 Hz with a total of 5.6 x 10 13 H - ions delivered per pulse. H - are stripped at injection into the Recycler in a manner that 'paints' the beam both transversely and longitudinally to reduce space charge forces. Following the 1 ms injection, the orbit moves off the stripping foil and circulates for 200 msec, awaiting the next injection. Following three such injections a total of 1.7 x 10 14 protons are transferred in a single turn to the Main Injector. These protons are then accelerated to 120 GeV and fast extracted to a neutrino target. The Main Injector cycle takes 1.4 seconds, producing approximately 2

  4. Rolling Stock Planning at DSB S-tog - Processes, Cost Structures and Requirements

    DEFF Research Database (Denmark)

    Thorlacius, Per

    A central issue for operators of suburban passenger train transport systems is providing sufficient number of seats for the passengers while at the same time minimising operating costs. The process of providing this is called rolling stock planning. This technical report documents the terminology......, the processes, the cost structures and the requirements for rolling stock planning at DSB S-tog, the suburban passenger train operator of the City of Copenhagen. The focus of the technical report is directed at practical train operator oriented issues. The technical report is thought to serve as a basis...... for investigating better methods to perform the rolling stock planning (to be the topic of later papers). This technical report is produced as a part of the current industrial Ph. D. project to improve the rolling stock planning process of DSB S-tog....

  5. Project Rulison: post-shot plans and evaluations

    Energy Technology Data Exchange (ETDEWEB)

    1969-12-01

    Project Rulison post-shot plans and evaluations are discussed and include physical characteristics of the Rulison cavity; pressure and temperature expected in the cavity; amount, nature, and distribution of radioactivity in the cavity; reentry plan; radioactive species which may be encountered during reentry; public safety considerations arising from release of radioactivity; procedures to assure public safety; and the radiological safety plan. Maximum hypothetical accidents and ecological considerations are discussed in the appendices.

  6. Fast Flux Test Facility, Sodium Storage Facility project-specific project management plan

    International Nuclear Information System (INIS)

    Shank, D.R.

    1994-01-01

    This Project-Specific Project Management Plan describes the project management methods and controls used by the WHC Projects Department to manage Project 03-F-031. The Sodium Storage Facility provides for storage of the 260,000 gallons of sodium presently in the FFTF Plant. The facility will accept the molten sodium transferred from the FFTF sodium systems, and store the sodium in a solid state under an inert cover gas until such time as a Sodium Reaction Facility is available for final disposal of the sodium

  7. Fast Flux Test Facility, Sodium Storage Facility project-specific project management plan

    Energy Technology Data Exchange (ETDEWEB)

    Shank, D.R.

    1994-12-29

    This Project-Specific Project Management Plan describes the project management methods and controls used by the WHC Projects Department to manage Project 03-F-031. The Sodium Storage Facility provides for storage of the 260,000 gallons of sodium presently in the FFTF Plant. The facility will accept the molten sodium transferred from the FFTF sodium systems, and store the sodium in a solid state under an inert cover gas until such time as a Sodium Reaction Facility is available for final disposal of the sodium.

  8. Spent nuclear fuel project high-level information management plan

    Energy Technology Data Exchange (ETDEWEB)

    Main, G.C.

    1996-09-13

    This document presents the results of the Spent Nuclear Fuel Project (SNFP) Information Management Planning Project (IMPP), a short-term project that identified information management (IM) issues and opportunities within the SNFP and outlined a high-level plan to address them. This high-level plan for the SNMFP IM focuses on specific examples from within the SNFP. The plan`s recommendations can be characterized in several ways. Some recommendations address specific challenges that the SNFP faces. Others form the basis for making smooth transitions in several important IM areas. Still others identify areas where further study and planning are indicated. The team`s knowledge of developments in the IM industry and at the Hanford Site were crucial in deciding where to recommend that the SNFP act and where they should wait for Site plans to be made. Because of the fast pace of the SNFP and demands on SNFP staff, input and interaction were primarily between the IMPP team and members of the SNFP Information Management Steering Committee (IMSC). Key input to the IMPP came from a workshop where IMSC members and their delegates developed a set of draft IM principles. These principles, described in Section 2, became the foundation for the recommendations found in the transition plan outlined in Section 5. Availability of SNFP staff was limited, so project documents were used as a basis for much of the work. The team, realizing that the status of the project and the environment are continually changing, tried to keep abreast of major developments since those documents were generated. To the extent possible, the information contained in this document is current as of the end of fiscal year (FY) 1995. Programs and organizations on the Hanford Site as a whole are trying to maximize their return on IM investments. They are coordinating IM activities and trying to leverage existing capabilities. However, the SNFP cannot just rely on Sitewide activities to meet its IM requirements

  9. National Ignition Facility project acquisition plan revision 1

    International Nuclear Information System (INIS)

    Clobes, A.R.

    1996-01-01

    The purpose of this National Ignition Facility Acquisition Plan is to describe the overall procurement strategy planned for the National Ignition Facility M Project. It was prepared for the NIP Prood Office by the NIF Procurement Manager

  10. Spring Chinook Supplementation Monitoring; Yakima Fisheries Project Management Plan, 1996 Technical Report.

    Energy Technology Data Exchange (ETDEWEB)

    Busack, Craig A. (Washington Department of Fish and Wildlife, Olympia, WA); Watson, Bruce; Johnston, Mark (Confederated Tribes and Bands of the Yakama Nation, Fisheries Resource Management, Toppenish, WA)

    1997-08-01

    The Yakima Fisheries Project (YFP), a key element in the Northwest Power Planning Council's Fish and Wildlife Program, has been in planning for more than ten years. It was initially conceived as, and is still intended to be, a multipurpose project. Besides increasing fish production in the Yakima basin, it is also intended to yield information about supplementation that will be of value to the entire Columbia basin, and hopefully the entire region. Because of this expectation of increased knowledge resulting from the project, a large and comprehensive monitoring program has always been seen as an integral part of the project. Despite the importance of monitoring to the project, monitoring planning has been slow to develop. The only general written statement of monitoring planning for the project is Chapter 9 of the current Project Status Report (PSR), written in 1993. That document is a reasonably good overview, and presents some important basic principles of monitoring, but is decidedly lacking in specifics. Throughout 1996 the Monitoring Implementation and Planning Team (MIPT), an interdisciplinary group of biologists who have worked on the project for several years, worked to develop a comprehensive spring chinook monitoring plan for the project. The result is the present document.

  11. Integrated Project Teams - An Essential Element of Project Management during Project Planning and Execution - 12155

    Energy Technology Data Exchange (ETDEWEB)

    Burritt, James G.; Berkey, Edgar [Longenecker and Associates, Las Vegas, NV 89135 (United States)

    2012-07-01

    Managing complex projects requires a capable, effective project manager to be in place, who is assisted by a team of competent assistants in various relevant disciplines. This team of assistants is known as the Integrated Project Team (IPT). he IPT is composed of a multidisciplinary group of people who are collectively responsible for delivering a defined project outcome and who plan, execute, and implement over the entire life-cycle of a project, which can be a facility being constructed or a system being acquired. An ideal IPT includes empowered representatives from all functional areas involved with a project-such as engineering design, technology, manufacturing, test and evaluation, contracts, legal, logistics, and especially, the customer. Effective IPTs are an essential element of scope, cost, and schedule control for any complex, large construction project, whether funded by DOE or another organization. By recently assessing a number of major, on-going DOE waste management projects, the characteristics of high performing IPTs have been defined as well as the reasons for potential IPT failure. Project managers should use IPTs to plan and execute projects, but the IPTs must be properly constituted and the members capable and empowered. For them to be effective, the project manager must select the right team, and provide them with the training and guidance for them to be effective. IPT members must treat their IPT assignment as a primary duty, not some ancillary function. All team members must have an understanding of the factors associated with successful IPTs, and the reasons that some IPTs fail. Integrated Project Teams should be used by both government and industry. (authors)

  12. Project Execution Plan for Project W-211 Initial Tank Retrieval Systems (ITRS)

    International Nuclear Information System (INIS)

    VAN BEEK, J.E.

    2000-01-01

    This Project Execution Plan documents the methodology for managing Project W-211. Project W-211, Initial Tank Retrieval Systems (ITRS), is a fiscal year 1994 Major Systems Acquisition that will provide systems for retrieval of radioactive wastes from selected double-shell tanks (DST). The contents of these tanks are a combination of supernatant liquids and settled solids. To retrieve waste from the tanks, it is first necessary to mix the liquid and solids prior to transferring the slurry to alternative storage or treatment facilities. The ITRS will provide systems to mobilize the settled solids and transfer the wastes out of the tanks. In so doing, ITRS provides feed for the future waste treatment plant, allows for consolidation of tank solids to manage space within existing DST storage capacity, and supports continued safe storage of tank waste. The ITRS scope has been revised to include waste retrieval systems for tanks AP-102, AP-104, AN-102, AN-103, AN-104, AN-105, AY-102, AZ-102, and SY-102. This current tank selection and sequence provides retrieval systems supporting the River Protection Project (RF'P) Waste Treatment Facility and sustains the ability to provide final remediation of several watch list DSTs via treatment. The ITRS is configured to support changing program needs, as constrained by available budget, by maintaining the flexibility for exchanging tanks requiring mixer pump-based retrieval systems and shifting the retrieval sequence. Preliminary design was configured such that an adequate basis exists for initiating Title II design of a mixer pump-based retrieval system for any DST. This Project Execution Plan (PEP), derived from the predecessor Project Management Plan, documents the methodology for managing the ITRS, formalizes organizational responsibilities and interfaces, and identifies project requirements such as change control, design verification, systems engineering, and human factors engineering

  13. First-of-A-Kind Control Room Modernization Project Plan

    Energy Technology Data Exchange (ETDEWEB)

    Thomas, Kenneth David [Idaho National Lab. (INL), Idaho Falls, ID (United States)

    2016-02-01

    This project plan describes a comprehensive approach to the design of an end-state concept for a modernized control room for Palo Verde. It describes the collaboration arrangement between the DOE LWRS Program Control Room Modernization Project and the APS Palo Verde Nuclear Generating Station. It further describes the role of other collaborators, including the Institute for Energy Technology (IFE) and the Electric Power Research Institute (EPRI). It combines advanced tools, methodologies, and facilities to enable a science-based approach to the validation of applicable engineering and human factors principles for nuclear plant control rooms. It addresses the required project results and documentation to demonstrate compliance with regulatory requirements. It describes the project tasks that will be conducted in the project, and the deliverable reports that will be developed through these tasks. This project plan will be updated as new tasks are added and as project milestones are completed. It will serve as an ongoing description on the project both for project participants and for industry stakeholders.

  14. Basalt Waste Isolation Project Technical Program Evaluation Process: a criteria-based method

    International Nuclear Information System (INIS)

    Babad, H.; Evans, G.C.; Wolfe, B.A.

    1982-01-01

    The need to objectively evaluate the progress being made by the Basalt Waste Isolation Project (BWIP) toward establishing the feasibility of siting a nuclear waste repository in basalt (NWRB) mandates a process for evaluating the technical work of the project. To assist BWIP management in the evaluation process, the Systems Department staff has developed a BWIP Technical Program Evaluation Process (TPEP). The basic process relates progress on project technical work to the SWIP Functional and System Performance Criteria as defined in National Waste Terminal Storage (MWTS) Criteria Documents. The benefits of the TPEP to BWIP and future plans for TPEP are discussed. During fiscal year (FY) 1982, TPEP wll be further formalized and further applied to the review of BWIP technical activities

  15. Project Management Plan to Maintain Safe and Compliant Conditions at the Plutonium Finishing Plant

    International Nuclear Information System (INIS)

    COX, G.J.

    1999-01-01

    This Project Management Plan presents the overall plan, description, mission, and workscope for the Plutonium Finishing Plant (PFP) maintain safe and compliant conditions project at PFP. This plan presents the overall description, mission, work scope, and planning for the Plutonium Finishing Plant (PFP) Maintain Safe and Compliant Conditions Project at PFP. This project includes all tasks required to maintain the safety boundary for the PFP Complex, except for the 2736-2 Vault Complex and the 234-52 vaults and vault-type rooms. The intent of this plan is to describe how this project will be managed and integrated with the stabilization, and deactivation activities. This plan supplements the overall integrated plan presented in the Plutonium Finishing Plant Integrated Project Management Plan (IPMP), HNF-3617, Rev. 0. This is the top-level definitive project management document that specifies the technical (work scope), schedule, and cost baselines that will manage the execution of this project. It describes the organizational approach and roles/responsibilities implemented to execute the project. This plan is under configuration management and any deviations must be authorized by appropriate change control action

  16. Quinault Indian Nation Comprehensive Biomass Strategic Planning Project

    Energy Technology Data Exchange (ETDEWEB)

    Cardenas, Jesus [American Community Enrichment, Elma, WA (United States)

    2015-03-31

    The overall purposes of the Quinault Indian Nation’s Comprehensive Biomass Strategic Planning Project were to: (1) Identify and confirm community and tribal energy needs; (2) Conducting an inventory of sustainable biomass feedstock availability; (3) Development of a biomass energy vision statement with goals and objectives; (4) Identification and assessment of biomass options for both demand-side and supply side that are viable to the Quinault Indian Nation (QIN); and (5) Developing a long-term biomass strategy consistent with the long-term overall energy goals of the QIN. This Comprehensive Biomass Strategic Planning Project is consistent with the QIN’s prior two-year DOE Renewable Energy Study from 2004 through 2006. That study revealed that the most viable options to the QIN’s renewable energy options were biomass and energy efficiency best practices. QIN's Biomass Strategic Planning Project is focused on using forest slash in chipped form as feedstock for fuel pellet manufacturing in support of a tribal biomass heating facility. This biomass heating facility has been engineered and designed to heat existing tribal facilities as well as tribal facilities currently being planned including a new K-12 School.

  17. The 2016-2018 National Plan of Management of Radioactive Materials and Wastes - Project

    International Nuclear Information System (INIS)

    Gazzo, Alexis; Robert, Jean-Gabriel; Abraham, Christophe; Benaze, Manon de

    2015-01-01

    A first document contains the project of the National Plan of Management of Radioactive Materials and Wastes (PNGMDR) for the period 2016-2018: principles and objectives (presentation of radioactive materials and wastes, principles to be taken into account to define pathways of management of radioactive wastes, legal and institutional framework, information transparency), the management of radioactive materials (context and challenges, management pathways, works on fast breeder reactors of fourth generation), assessment and perspectives of existing pathways of management of radioactive wastes (management of historical situations, management of residues of mining and sterile processing, management of waste with a high natural radioactivity, management of very short life waste, of very low activity wastes, and low and medium activity wastes), needs and perspectives regarding management processes to be implemented for the different types of radioactive wastes. Appendices to this document contain a recall of the content of previous PNGMDR since 2007, a synthesis of realisations and researches performed abroad, research orientations for the concerned period, and international agreement on spent fuel and radioactive waste management. A second document, released by the ASN, proposes an environmental and strategic assessment of the plan. A third one and a fourth one contain the opinion of the Environmental Authority, respectively on the plan preliminary focus, and on the plan itself. An answer to this last one is then proposed, followed by a synthesis of the plan project and the text of the corresponding decree

  18. Fast Flux Test Facility project plan. Revision 2

    Energy Technology Data Exchange (ETDEWEB)

    Hulvey, R.K.

    1995-11-01

    The Fast Flux Test Facility (FFTF) Transition Project Plan, Revision 2, provides changes to the major elements and project baseline for the deactivation activities necessary to transition the FFTF to a radiologically and industrially safe shutdown condition.

  19. Fast Flux Test Facility project plan. Revision 2

    International Nuclear Information System (INIS)

    Hulvey, R.K.

    1995-11-01

    The Fast Flux Test Facility (FFTF) Transition Project Plan, Revision 2, provides changes to the major elements and project baseline for the deactivation activities necessary to transition the FFTF to a radiologically and industrially safe shutdown condition

  20. Rationale, Design, and Methods for Process Evaluation in the Childhood Obesity Research Demonstration Project.

    Science.gov (United States)

    Joseph, Sitara; Stevens, Andria M; Ledoux, Tracey; O'Connor, Teresia M; O'Connor, Daniel P; Thompson, Debbe

    2015-01-01

    The cross-site process evaluation plan for the Childhood Obesity Research Demonstration (CORD) project is described here. The CORD project comprises 3 unique demonstration projects designed to integrate multi-level, multi-setting health care and public health interventions over a 4-year funding period. Three different communities in California, Massachusetts, and Texas. All CORD demonstration projects targeted 2-12-year-old children whose families are eligible for benefits under Title XXI (CHIP) or Title XIX (Medicaid). The CORD projects were developed independently and consisted of evidence-based interventions that aim to prevent childhood obesity. The interventions promote healthy behaviors in children by applying strategies in 4 key settings (primary care clinics, early care and education centers, public schools, and community institutions). The CORD process evaluation outlined 3 main outcome measures: reach, dose, and fidelity, on 2 levels (researcher to provider, and provider to participant). The plan described here provides insight into the complex nature of process evaluation for consortia of independently designed multi-level, multi-setting intervention studies. The process evaluation results will provide contextual information about intervention implementation and delivery with which to interpret other aspects of the program. Copyright © 2015 Society for Nutrition Education and Behavior. All rights reserved.

  1. Project Management Plan (PMP) for Work Management Implementation

    International Nuclear Information System (INIS)

    SHIPLER, C.E.

    2000-01-01

    The purpose of this document is to provide a project plan for Work Management Implementation by the River Protection Project (RPP). Work Management is an information initiative to implement industry best practices by replacing some Tank Farm legacy system

  2. AMADEUS Project Deliverable 1.2: Data Management Plan

    OpenAIRE

    Ana Belén Cristobal

    2018-01-01

    This document describes the initial Data Management Plan (DMP) for AMADEUS project. It addresses Project administration data collected as part of the execution and management of a disruptive research that could be in the market in the incoming years.

  3. Project Management Plan for Initial Tank Retrieval Systems, Project W-211

    International Nuclear Information System (INIS)

    VAN BEEK, J.E.

    1999-01-01

    Project W-211, Initial Tank Retrieval Systems (ITRS), is a fiscal year 1994 Major Systems Acquisition that will provide systems for retrieval of radioactive wastes from selected double-shell tanks (DST). The contents of these tanks are a combination of supernatant liquids and settled solids. To retrieve waste from the tanks, it is first necessary to mix the liquid and solids prior to transferring the slurry to alternative storage or treatment facilities. The ITRS will provide systems to mobilize the settled solids and transfer the wastes out of the tanks. In so doing, ITRS provides feed for future processing plants, allows for consolidation of tank solids to manage space within existing DST storage capacity, and supports continued safe storage of tank waste. The ITRS scope has been revised to include waste retrieval systems for tanks AP-102, AP-104, AP-108, AN-103, AN-104, AN-105, AY-102, AZ-102, and SY-102. This current tank selection and sequence provides retrieval systems supporting the Privatized waste processing plant and sustains the ability to provide final remediation of several watch list DSTs via treatment. The ITRS is configured to support changing program needs, as constrained by available budget, by maintaining the flexibility for exchanging tanks requiring mixer pump-based retrieval systems and shifting the retrieval sequence. Preliminary design was configured such that an adequate basis exists for initiating Title II design of a mixer pump based retrieval system for any DST. This Project Management Plan (PMP) documents the methodology for managing the ITRS, formalizes organizational responsibilities and interfaces, and identifies project requirements such as change control, design verification, systems engineering, and human factors engineering

  4. Large-scale projects between regional planning and environmental protection

    International Nuclear Information System (INIS)

    Schmidt, G.

    1984-01-01

    The first part of the work discusses the current law of land-use planning, municipal and technical construction planning, and licensing under the atomic energy law and the federal law on immission protection. In the second part some theses suggesting modifications are submitted. In the sector of land-use planning substantial contributions to the protection of the environment can only be expected from programs and plans (aims). For the environmental conflicts likely to arise from large-scale projects (nuclear power plant, fossil-fuel power plant) this holds good for the most part of site selection plans. They have bearings on environmental protection in that they presuppose thorough examination of facts, help to recognize possible conflicts at an early date and provide a frame for solving those problems. Municipal construction planning is guided by the following principles: Environmental protection is an equivalent planning target. Environmental data and facts and their methodical processing play a fundamental part as they constitute the basis of evaluation. Under the rules and regulations of the federal law on immission protection, section 5, number 2 - prevention of nuisances - operators are obliged to take preventive care of risks. That section is not concerned with planning or distribution. Neither does the licensing of nuclear plants have planning character. So far as the legal preconditions of licensing are fulfilled, the scope for rejection of an application under section 7, subsection 2 of the atomic energy law in view of site selection and requirement of a plant hardly carries any practical weight. (orig./HP) [de

  5. Hellsgate Big Game Winter Range Wildlife Mitigation Site Specific Management Plan for the Hellsgate Project.

    Energy Technology Data Exchange (ETDEWEB)

    Berger, Matthew T.; Judd, Steven L.

    1999-01-01

    This report contains a detailed site-specific management plan for the Hellsgate Winter Range Wildlife Mitigation Project. The report provides background information about the mitigation process, the review process, mitigation acquisitions, Habitat Evaluation Procedures (HEP) and mitigation crediting, current habitat conditions, desired future habitat conditions, restoration/enhancements efforts and maps.

  6. IUS/TUG orbital operations and mission support study. Volume 4: Project planning data

    Science.gov (United States)

    1975-01-01

    Planning data are presented for the development phases of interim upper stage (IUS) and tug systems. Major project planning requirements, major event schedules, milestones, system development and operations process networks, and relevant support research and technology requirements are included. Topics discussed include: IUS flight software; tug flight software; IUS/tug ground control center facilities, personnel, data systems, software, and equipment; IUS mission events; tug mission events; tug/spacecraft rendezvous and docking; tug/orbiter operations interface, and IUS/orbiter operations interface.

  7. 78 FR 63481 - Therapeutic Area Standards Initiative Project Plan; Availability

    Science.gov (United States)

    2013-10-24

    ... disadvantages of current and emerging alternatives for the exchange of regulated study data, and (2) issuing a... primary document for guiding all major aspects of FDA's multi-year initiative to develop and implement TA... is announcing the availability of the TA Project Plan. This TA Project Plan will be the primary...

  8. Automated transportation management system (ATMS) software project management plan (SPMP)

    Energy Technology Data Exchange (ETDEWEB)

    Weidert, R.S., Westinghouse Hanford

    1996-05-20

    The Automated Transportation Management System (ATMS) Software Project Management plan (SPMP) is the lead planning document governing the life cycle of the ATMS and its integration into the Transportation Information Network (TIN). This SPMP defines the project tasks, deliverables, and high level schedules involved in developing the client/server ATMS software.

  9. Strategic planning for remediation projects

    International Nuclear Information System (INIS)

    Tapp, J.W.

    1995-01-01

    Remediation projects may range from a single leaking storage tank to an entire plant complex or producing oil and gas field. Strategic planning comes into play when the contamination of soil and groundwater is extensive. If adjacent landowners have been impacted or the community at large is concerned about the quality of drinking water, then strategic planning is even more important. (1) To manage highly complex interrelated issues--for example, the efforts expended on community relations can alter public opinion, which can impact regulatory agency decisions that affect cleanup standards, which can...and so on. (2) To ensure that all potential liabilities are managed--for example, preparation for the defense of future lawsuits is essential during site investigation and remediation. (3) To communicate with senior management--when the remediation team provides a strategic plan that includes both technical and business issues, senior management has the opportunity to become more involved and make sound policy decisions. The following discusses the elements of a strategic plan, who should participate in it, and the issues that should be considered

  10. Evolution of project planning tools in a matrix organization

    Energy Technology Data Exchange (ETDEWEB)

    Furaus, J.P.; Figueroa-McInteer, C.; McKeever, P.S.; Wisler, D.B. [Sandia National Labs., Albuquerque, NM (United States); Zavadil, J.T. [Infomatrix (United States)

    1996-10-01

    Until recently, the Corporate Construction Program at Sandia was experiencing difficulties in managing projects: poor planning and cost estimating caused schedule and budget problems. The first step taken was a Microsoft {reg_sign} Project schedule that provides a standard template for scheduling individual construction projects. It is broken down according to the life cycle of the project and prevents the project team from leaving out an important item. A WBS (work breakdown structure) dictionary was also developed that describes how capital and operating funds are used to develop, design, construct, equip, and manage projects. We also developed a matrix chart that maps the planning guide against the major types of construction projects at Sandia. The guide, dictionary, and matrix chart offer enough flexibility that the project manager can make choices about how to structure work, yet ensure that all work rolls up to the cost categories and key DOE WBS elements. As requirements change, the tools can be updated; they also serve as training tools for new project team members.

  11. Standard Measurement & Verification Plan for Lighting Equipment Retrofit or Replacement Projects

    Energy Technology Data Exchange (ETDEWEB)

    Richman, Eric E.

    2009-11-04

    This document provides a framework for a standard Measurement and Verification (M&V) plan for lighting projects. It was developed to support cost-effective retrofits (partial and complete replacements) of lighting systems and is intended to provide a foundation for an M&V plan for a lighting retrofit utilizing a "best practice" approach, and to provide guidance to site owners, contractors, and other involved organizations on what is essential for a robust M&V plan for lighting projects. This document provides examples of appropriate elements of an M&V plan, including the calculation of expected energy savings. The standard M&V plan, as provided, also allows for consistent comparison with other similar lighting projects. Although intended for lighting retrofit applications, M&V plans developed per this framework document may also be used for other non-lighting technology retrofits and new installations.

  12. Solid waste information and tracking system server conversion project management plan

    International Nuclear Information System (INIS)

    MAY, D.L.

    1999-01-01

    The Project Management Plan governing the conversion of Solid Waste Information and Tracking System (SWITS) to a client-server architecture. The Solid Waste Information and Tracking System Project Management Plan (PMP) describes the background, planning and management of the SWITS conversion. Requirements and specification documentation needed for the SWITS conversion will be released as supporting documents

  13. A hierarchical approach to multi-project planning under uncertainty

    NARCIS (Netherlands)

    Leus, R.; Wullink, Gerhard; Hans, Elias W.; Herroelen, W.

    2004-01-01

    We survey several viewpoints on the management of the planning complexity of multi-project organisations under uncertainty. A positioning framework is proposed to distinguish between different types of project-driven organisations, which is meant to aid project management in the choice between the

  14. A hierarchical approach to multi-project planning under uncertainty

    NARCIS (Netherlands)

    Hans, Elias W.; Herroelen, W.; Wullink, Gerhard; Leus, R.

    2007-01-01

    We survey several viewpoints on the management of the planning complexity of multi-project organisations under uncertainty. Based on these viewpoints we propose a positioning framework to distinguish between different types of project-driven organisations. This framework is meant to aid project

  15. N Area Final Project Program Plan

    International Nuclear Information System (INIS)

    Day, R.S.; Duncan, G.M; Trent, S.J.

    1998-07-01

    The N Area Final Project Program Plan is issued for information and use by the U.S. Department of Energy (DOE), the Environmental Restoration Contractor (ERC) for the Hanford Site, and other parties that require workscope knowledge for the deactivation of N Reactor facilities and remediation of the 100-N Area. This revision to the program plan contains the updated critical path schedule to deactivate N Reactor and its supporting facilities, cleanout of the N Reactor Fuel Storage Basin (105-N Basin), and remediate the 100-N Area. This document reflects notable changes in the deactivation plan for N Reactor, including changes in deactivation status, the N Basin cleanout task, and 100-N Area remediation

  16. Project Management Plan for the Isotopes Facilities Deactivation Project at Oak Ridge National Laboratory

    International Nuclear Information System (INIS)

    1995-04-01

    The purpose of the Isotopes Facilities Deactivation Project (IFDP) is to place former isotopes production facilities at the Oak Ridge National Laboratory in a safe, stable, and environmentally sound condition suitable for an extended period of minimum surveillance and maintenance (S ampersand M) and as quickly and economically as possible. Implementation and completion of the deactivation project will further reduce the already small risks to the environment and to public safety and health. Furthermore, the project should result in significant S ampersand M cost savings in the future. The IFDP management plan has been prepared to document the project objectives, define organizational relationships and responsibilities, and outline the management control systems to be employed in the management of the project. The project has adopted a strategy to deactivate the simple facilities first, to reduce the scope of the project, and to gain experience before addressing more difficult facilities. A decision support system is being developed to identify those activities, that best promote the project mission and result in largest cost savings. The Work Plan for the Isotopes Facilities Deactivation Project at Oak Ridge National Laboratory (Energy Systems 1994) defines the project schedule, the cost estimate, and the technical approach for the project

  17. Hellsgate Winter Range Mitigation Project; Long-term Management Plan, Project Report 1993, Final Draft.

    Energy Technology Data Exchange (ETDEWEB)

    Berger, Matthew T.

    1994-01-01

    A study was conducted on the Hellsgate Winter Range Mitigation Project area, a 4,943 acre ranch purchased for mitigating some habitat losses associated with the original construction of Grand Coulee Dam and innundation of habitat by Lake Roosevelt. A Habitat Evaluation Procedure (HEP) study was used to determine habitat quality and quantity baseline data and future projections. Target species used in the study were sharp-tailed grouse (Tympanuchus phasianellus), mule deer (Odocoileus hemoinus), mink (Mustela vison), spotted sandpiper (Actiius colchicus), bobcat (Felis reufs), blue grouse (Dendragapus obscurus), and mourning dove (Zenaida macroura). From field data collected, limiting life values or HSI's (Habitat Suitability Index's) for each indicator species was determined for existing habitats on project lands. From this data a long term management plan was developed. This report is designed to provide guidance for the management of project lands in relation to the habitat cover types discussed and the indicator species used to evaluate these cover types. In addition, the plan discusses management actions, habitat enhancements, and tools that will be used to enhance, protect and restore habitats to desired conditions. Through planned management actions biodiversity and vegetative structure can be optimized over time to reduce or eliminate, limiting HSI values for selected wildlife on project lands.

  18. Developing integrated parametric planning models for budgeting and managing complex projects

    Science.gov (United States)

    Etnyre, Vance A.; Black, Ken U.

    1988-01-01

    The applicability of integrated parametric models for the budgeting and management of complex projects is investigated. Methods for building a very flexible, interactive prototype for a project planning system, and software resources available for this purpose, are discussed and evaluated. The prototype is required to be sensitive to changing objectives, changing target dates, changing costs relationships, and changing budget constraints. To achieve the integration of costs and project and task durations, parametric cost functions are defined by a process of trapezoidal segmentation, where the total cost for the project is the sum of the various project cost segments, and each project cost segment is the integral of a linearly segmented cost loading function over a specific interval. The cost can thus be expressed algebraically. The prototype was designed using Lotus-123 as the primary software tool. This prototype implements a methodology for interactive project scheduling that provides a model of a system that meets most of the goals for the first phase of the study and some of the goals for the second phase.

  19. Software for project-based learning of robot motion planning

    Science.gov (United States)

    Moll, Mark; Bordeaux, Janice; Kavraki, Lydia E.

    2013-12-01

    Motion planning is a core problem in robotics concerned with finding feasible paths for a given robot. Motion planning algorithms perform a search in the high-dimensional continuous space of robot configurations and exemplify many of the core algorithmic concepts of search algorithms and associated data structures. Motion planning algorithms can be explained in a simplified two-dimensional setting, but this masks many of the subtleties and complexities of the underlying problem. We have developed software for project-based learning of motion planning that enables deep learning. The projects that we have developed allow advanced undergraduate students and graduate students to reflect on the performance of existing textbook algorithms and their own variations on such algorithms. Formative assessment has been conducted at three institutions. The core of the software used for this teaching module is also used within the Robot Operating System, a widely adopted platform by the robotics research community. This allows for transfer of knowledge and skills to robotics research projects involving a large variety robot hardware platforms.

  20. Surfaced-based investigations plan, Volume 4: Yucca Mountain Project

    International Nuclear Information System (INIS)

    1988-12-01

    This document represents a detailed summary of design plans for surface-based investigations to be conducted for site characterization of the Yucca Mountain site. These plans are current as of December 1988. The description of surface-based site characterization activities contained in this document is intended to give all interested parties an understanding of the current plans for site characterization of Yucca Mountain. The maps presented in Volume 4 are products of the Geographic Information System (GIS) being used by the Yucca Mountain Project. The ARC/INFO GIS software, developed by Environmental Systems Research Institute, was used to digitize and process these SBIP maps. The maps were prepared using existing US Geological Survey (USGS) maps as a planimetric base. Roads and other surface features were interpreted from a variety of sources and entered into the GIS. Sources include the USGS maps, 1976 USGS orthophotoquads and aerial photography, 1986 and 1987 aerial photography, surveyed coordinates of field sites, and a combination of various maps, figures, descriptions and approximate coordinates of proposed locations for future activities

  1. Intermediate evaluation of USAID/Cairo energy policy planning project

    Energy Technology Data Exchange (ETDEWEB)

    Wilbanks, T.J.; Wright, S.B. (Oak Ridge National Lab., TN (United States)); Barron, W.F. (Hong Kong Univ. (Hong Kong)); Kamel, A.M. (Ain Shams Univ., Cairo (Egypt)); Santiago, H.T. (USDOE, Washington, DC (United States))

    1992-01-01

    Three years ago, a team from the Oak Ridge National Laboratory and the Oak Ridge Associated Universities, supplemented by an expert from the US Department of Energy and a senior Egyptian energy professional, carried out what was termed an intermediate evaluation'' of a major energy policy project in Egypt. Supported by USAID/Cairo, the project had concentrated on developing and strengthening an Organization for Energy Planning (OEP) within the Government of India, and it was actually scheduled to end less than a year after this evaluation. The evaluation was submitted to USAID/Cairo and circulated elsewhere in the US Agency for International Development and the Government of Egypt as an internal report. Over the next several years, the USAID energy planning project ended and the functions performed by OEP were merged with planning capabilities in the electric power sector. Now that the major issues addressed by the evaluation report have been resolved, we are making it available to a broader audience as a contribution to the general literature on development project evaluation and institution-building.

  2. Intermediate evaluation of USAID/Cairo energy policy planning project

    Energy Technology Data Exchange (ETDEWEB)

    Wilbanks, T.J.; Wright, S.B. [Oak Ridge National Lab., TN (United States); Barron, W.F. [Hong Kong Univ. (Hong Kong); Kamel, A.M. [Ain Shams Univ., Cairo (Egypt); Santiago, H.T. [USDOE, Washington, DC (United States)

    1992-09-01

    Three years ago, a team from the Oak Ridge National Laboratory and the Oak Ridge Associated Universities, supplemented by an expert from the US Department of Energy and a senior Egyptian energy professional, carried out what was termed an ``intermediate evaluation`` of a major energy policy project in Egypt. Supported by USAID/Cairo, the project had concentrated on developing and strengthening an Organization for Energy Planning (OEP) within the Government of India, and it was actually scheduled to end less than a year after this evaluation. The evaluation was submitted to USAID/Cairo and circulated elsewhere in the US Agency for International Development and the Government of Egypt as an internal report. Over the next several years, the USAID energy planning project ended and the functions performed by OEP were merged with planning capabilities in the electric power sector. Now that the major issues addressed by the evaluation report have been resolved, we are making it available to a broader audience as a contribution to the general literature on development project evaluation and institution-building.

  3. Virtual reality in decommissioning projects: experiences, lessons learned and future plans

    International Nuclear Information System (INIS)

    Rindahl, G.; Mark, N.K.F.; Meyer, G.

    2006-01-01

    The work on Virtual Reality (VR) tools for decommissioning planning, dose estimation and work management started at the Norwegian Institute for Energy Technology (IFE) in 1999 in the VR dose project with Japan Nuclear Cycle development institute (JNC), now JAEA. The main aim of this effort has been to help minimize workers' radiation exposure, as well as help to achieve more efficient use of human resources. VR dose is now used in the decommissioning of one of JNC's reactors, the Fugen Nuclear Power Station. This VR decommissioning project has later resulted in a series of projects and applications. In addition to decommissioning, IFE also put great focus on two other branches of VR tools, namely tools for knowledge management, training and education in operating facilities and tools for control room design. During the last years, this work, beginning at different ends, has been converging more and more towards VR technology for use through out the life cycle of a facility. A VR training simulator for a refuelling machine of the Leningrad NPP (LNPP) developed in cooperation with the Russian Research Centre Kurchatov Institute (RRC KI) is now planned to be used in connection with the decommissioning of the three intact reactors at Chernobyl in Ukraine. In this paper we describe experiences from use of VR in decommissioning processes, as well as results from bringing the VR technology initially developed for planned or productive facilities into the decommissioning toolbox. (author)

  4. Transition plan: Project C-018H, 200-E Area Effluent Treatment Facility

    International Nuclear Information System (INIS)

    Connor, M.D.

    1994-01-01

    The purpose of this transition plan is to ensure an orderly transfer of project information to operations to satisfy Westinghouse Hanford Company (WHC) operational requirements and objectives, and ensure safe and efficient operation of Project C-018H, the 200-E Area Effluent Treatment Facility (ETF). This plan identifies the deliverables for Project C-018H upon completion of construction and turnover to WHC for operations, and includes acceptance criteria to objectively assess the adequacy of the contract deliverables in relation to present requirements. The scope of this plan includes a general discussion of the need for complete and accurate design basis documentation and design documents as project deliverables. This plan also proposes that a configuration management plan be prepared to protect and control the transferred design documents and reconstitute the design basis and design requirements, in the event that the deliverables and project documentation received from the contractor are less than adequate at turnover

  5. Advanced Seismic Probabilistic Risk Assessment Demonstration Project Plan

    Energy Technology Data Exchange (ETDEWEB)

    Coleman, Justin [Idaho National Lab. (INL), Idaho Falls, ID (United States)

    2014-09-01

    Idaho National Laboratories (INL) has an ongoing research and development (R&D) project to remove excess conservatism from seismic probabilistic risk assessments (SPRA) calculations. These risk calculations should focus on providing best estimate results, and associated insights, for evaluation and decision-making. This report presents a plan for improving our current traditional SPRA process using a seismic event recorded at a nuclear power plant site, with known outcomes, to improve the decision making process. SPRAs are intended to provide best estimates of the various combinations of structural and equipment failures that can lead to a seismic induced core damage event. However, in general this approach has been conservative, and potentially masks other important events (for instance, it was not the seismic motions that caused the Fukushima core melt events, but the tsunami ingress into the facility).

  6. 78 FR 21414 - Central Valley Project Improvement Act, Water Management Plans

    Science.gov (United States)

    2013-04-10

    ... Valley Project Improvement Act, Water Management Plans AGENCY: Bureau of Reclamation, Interior. ACTION: Notice of availability. SUMMARY: The following Water Management Plans are available for review... establish and administer an office on Central Valley Project water conservation best management practices...

  7. 78 FR 63491 - Central Valley Project Improvement Act, Water Management Plans

    Science.gov (United States)

    2013-10-24

    ... Valley Project Improvement Act, Water Management Plans AGENCY: Bureau of Reclamation, Interior. ACTION: Notice of availability. SUMMARY: The following Water Management Plans are available for review: Westside... project contractors using best available cost-effective technology and best management practices.'' These...

  8. The Basalt Waste Isolation Project technical program evaluation process: A criteria-based method

    International Nuclear Information System (INIS)

    Babad, H.; Evans, C.; Wolfe, B.A.

    1982-01-01

    The need to objectively evaluate the progress being made by the Basalt Waste Isolation Project (BWIP) toward establishing the feasibility of siting a nuclear waste repository in basalt (NWRB) mandates a process for evaluating the technical work of the project. To assist BWIP management in the evaluation process, the Systems Department staff has developed a BWIP Technical Program Evaluation Process (TPEP). The basic process relates progress on project technical work to the BWIP Functional and System Performance Criteria as defined in National Waste Terminal Storage (NWTS) Criteria Documents. The benefits of the TPEP to BWIP and future plans for TPEP are discussed. During fiscal year (FY) 1982, TPEP will be further formalized and further applied to the review of BWIP technical activities

  9. UMTRA project water sampling and analysis plan -- Shiprock, New Mexico

    International Nuclear Information System (INIS)

    1994-02-01

    Water sampling and analysis plan (WSAP) is required for each U.S. Department of Energy (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project site to provide a basis for ground water and surface water sampling at disposal and former processing sites. This WSAP identifies and justifies the sampling locations, analytical parameters, detection limits, and sampling frequency for the monitoring stations at the Navaho Reservation in Shiprock, New Mexico, UMTRA Project site. The purposes of the water sampling at Shiprock for fiscal year (FY) 1994 are to (1) collect water quality data at new monitoring locations in order to build a defensible statistical data base, (2) monitor plume movement on the terrace and floodplain, and (3) monitor the impact of alluvial ground water discharge into the San Juan River. The third activity is important because the community of Shiprock withdraws water from the San Juan River directly across from the contaminated alluvial floodplain below the abandoned uranium mill tailings processing site

  10. Planning international transit oil pipeline projects in Croatia

    International Nuclear Information System (INIS)

    Sekulic, G.; Vrbic, D.

    2004-01-01

    Planning and development of international oil pipeline projects are aimed primarily at enhancing the safety of crude oil supply. Pipeline development is affected by a variety of overlapping factors, such as energy - and environment-protection-related factors, as well as political, economic, legislative, social, technical and technological ones. The success of any pipeline planning, construction and operation in the present conditions will depend upon the degree to which the above factors have been brought in line with global trends. The government should create stable political, economic and legislative frameworks that will meet the global requirements of crude oil transport development. As regards (new) transportation companies, their function is to secure safe transport by providing competitive tariffs and granting environmental protection. A prerequisite for the pipeline planning is to have both major crude oil consumers and producers (as well as their economic and political integrations) consider any state or company as potential partners for crude oil transport and transit, respectively. Croatia and the JANAF transport company have been 'chosen' as one of priority routes for European supply with crude oil from the Caspian region and Russia and one of the directions for Russian crude oil export due to a number of advantages, opportunities and prospects for a successful development. Two international oil pipeline projects - the Druzba Adria Project and the Constanta-Pancevo-Omisalj-Trieste Project - are currently under consideration. The government commitment towards these projects has been documented by the Croatian Energy Development Strategy (April 2002) and by the Programme for its implementation (March 2004). JANAF has assumed the responsibility for carrying out the project preparation activities assigned to it by the Croatian Government and the pertinent ministries. Cooperation between JANAF and government institutions is an integral part of the procedure

  11. The process behind the project 'houses without heating system' in Goeteborg, Sweden

    Energy Technology Data Exchange (ETDEWEB)

    Glad, Wiktoria [Linkoeping Univ. (Sweden). The Tema Inst., Dept. of Technology and Social Change

    2003-07-01

    In the outskirts of Goeteborg, Sweden, twenty terrace houses were constructed throughout 2001. The spectacular thing about these houses is that no traditional heating systems were installed. The commercial's catch phrase is: 'Houses without heating systems'. Following this project from the beginning and through the whole process, including the long planning procedure (between 1997-1999), the professional actors (the initiator, the building proprietor, the contractor and the researchers), come into focus. This is a unique project in Sweden and has not yet had any follow-up developments. The evaluation, mainly including measurements, is being conducted by a research Inst. and will be finalised in 2003. The theoretical approach is as described in socio-technical system and focuses on social and technical components. The point of departure for the study is the social subsystem and the process behind the project which is important in understanding the final outcome. The study focuses on how and why this project was conducted. Initially, one person's ideas, inspired by building projects abroad were crucial. These ideas were then spread to a network constituting of researchers, the building proprietor, the contractor and the builders, and other consultants. The process can be described as a social innovation since a new concept for heating in buildings is introduced by focusing on the planning process and new participating actors.

  12. ELIMINATION OF THE DISADVANTAGES OF SCHEDULING-NETWORK PLANNING BY APPLYING THE MATRIX OF KEY PROJECT EVENTS

    Directory of Open Access Journals (Sweden)

    Morozenko Andrey Aleksandrovich

    2017-07-01

    Full Text Available The article discusses the current disadvantages of the scheduling-network planning in the management of the terms of investment-construction project. Problems associated with the construction of the schedule and the definitions of the duration of the construction project are being studied. The problems of project management for the management apparatus are shown, which consists in the absence of mechanisms for prompt response to deviations in the parameters of the scheduling-network diagram. A new approach to planning the implementation of an investment-construction project based on a matrix of key events and a rejection of the current practice of determining the duration based on inauthentic regulatory data. An algorithm for determining the key events of the project is presented. For increase the reliability of the organizational structure, the load factor of the functional block in the process of achieving the key event is proposed. Recommendations for improving the interaction of the participants in the investment-construction project are given.

  13. UMTRA Ground Water Project management action process document

    International Nuclear Information System (INIS)

    1996-03-01

    A critical U.S. Department of Energy (DOE) mission is to plan, implement, and complete DOE Environmental Restoration (ER) programs at facilities that were operated by or in support of the former Atomic Energy Commission (AEC). These facilities include the 24 inactive processing sites the Uranium Mill Tailings Radiation Control Act (UMTRCA) (42 USC Section 7901 et seq.) identified as Title I sites, which had operated from the late 1940s through the 1970s. In UMTRCA, Congress acknowledged the potentially harmful health effects associated with uranium mill tailings and directed the DOE to stabilize, dispose of, and control the tailings in a safe and environmentally sound manner. The UMTRA Surface Project deals with buildings, tailings, and contaminated soils at the processing sites and any associated vicinity properties (VP). Surface remediation at the processing sites will be completed in 1997 when the Naturita, Colorado, site is scheduled to be finished. The UMTRA Ground Water Project was authorized in an amendment to the UMTRCA (42 USC Section 7922(a)), when Congress directed DOE to comply with U.S. Environmental Protection Agency (EPA) ground water standards. The UMTRA Ground Water Project addresses any contamination derived from the milling operation that is determined to be present at levels above the EPA standards

  14. Project management plan for the isotopes facilities deactivation project at Oak Ridge National Laboratory, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1996-08-01

    Purpose of the deactivation project is to place former isotopes production facilities at ORNL in a safe, stable, and environmentally sound condition suitable for an extended period of minimum surveillance and maintenance. This management plan was prepared to document project objectives, define organizational relationships and responsibilities, and outline the management control systems. The project has adopted the strategy of deactivating the simple facilities first. The plan provides a road map for the quality assurance program and identifies other documents supporting the Isotopes Facilities Deactivation Project

  15. Work plan for the Hanford Environmental Dose Reconstruction Project

    Energy Technology Data Exchange (ETDEWEB)

    1989-12-01

    The primary objective of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate the radiation doses that populations could have received from nuclear operations at the Hanford Site since 1944, with descriptions of uncertainties inherent in such estimates. The secondary objective is to make project records--information that HEDR staff members used to estimate radiation doses--available to the public. Preliminary dose estimates for a limited geographic area and time period, certain radionuclides, and certain populations are planned to be available in 1990; complete results are planned to be reported in 1993. Project reports and references used in the reports are available to the public in the DOE Public Reading Room in Richland, Washington. Project progress is documented in monthly reports, which are also available to the public in the DOE Public Reading Room.

  16. QUEST2: Release 1: Project plan deliverable set

    International Nuclear Information System (INIS)

    Braaten, F.D.

    1995-01-01

    This Project Management Plan combines the project management deliverables from the P+ methodology which are applicable to Release 1 of the QUEST2 work. This consolidation reflects discussions with WHC QA regarding an appropriate method for ensuring that P+ deliverables fulfill the intent of WHC-CM-3-10 and QR-19

  17. Project planning of Gen-IV sodium cooled fast reactor technology

    Energy Technology Data Exchange (ETDEWEB)

    Yoo, Jaewoon; Joo, H. K.; Cho, C. H.; Kim, Y. G.; Lee, D. U.; Jin, M. W.

    2013-05-15

    The project program will be established to shorten the design schedule by sharing the design man power and experimental facility, and by introducing the proven technology through international collaboration and the project plan including preliminary specific design, technology validation and fuel design validation plan will be more detail by reviewing the plan at the International Technical Review Meeting (ITRM). Periodic project progress review meeting will be held to find the technical issues and to resolve them. The results of the progress review meeting will be reflected into the final assessment of research project. The project progress review meeting will be held every quarter and external expert will also participate in the meeting. In parallel with the PGSFR development, innovative small modular SFR will be developed aiming to the international nuclear market. The system and component technologies of both system can be shared but innovative concept will be implemented into the design. Ultra long life core design concept and supercritical CO{sub 2} Brayton cycle will be considered as the innovative concept for enhancing the plant economy and safety.

  18. Project planning of Gen-IV sodium cooled fast reactor technology

    International Nuclear Information System (INIS)

    Yoo, Jaewoon; Joo, H. K.; Cho, C. H.; Kim, Y. G.; Lee, D. U.; Jin, M. W.

    2013-05-01

    The project program will be established to shorten the design schedule by sharing the design man power and experimental facility, and by introducing the proven technology through international collaboration and the project plan including preliminary specific design, technology validation and fuel design validation plan will be more detail by reviewing the plan at the International Technical Review Meeting (ITRM). Periodic project progress review meeting will be held to find the technical issues and to resolve them. The results of the progress review meeting will be reflected into the final assessment of research project. The project progress review meeting will be held every quarter and external expert will also participate in the meeting. In parallel with the PGSFR development, innovative small modular SFR will be developed aiming to the international nuclear market. The system and component technologies of both system can be shared but innovative concept will be implemented into the design. Ultra long life core design concept and supercritical CO 2 Brayton cycle will be considered as the innovative concept for enhancing the plant economy and safety

  19. Project management plan for the gunite and associated tanks treatability studies project at Oak Ridge National Laboratory, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1995-12-01

    This plan for the Gunite and Associated Tanks (GAAT) Treatability Studies Project satisfies the requirements of the program management plan for the Oak Ridge National Laboratory (ORNL) Environmental Restoration (ER) Program as established in the Program Management Plan for the Martin Marietta Energy Systems, Inc., Oak Ridge National Laboratory Site Environmental Restoration Program. This plan is a subtier of several other ER documents designed to satisfy the US Department of Energy (DOE) Order 4700.1 requirement for major systems acquisitions. This project management plan identifies the major activities of the GAAT Treatability Studies Project; establishes performance criteria; discusses the roles and responsibilities of the organizations that will perform the work; and summarizes the work breakdown structure, schedule, milestones, and cost estimate for the project

  20. Project management process.

    Science.gov (United States)

    2007-03-01

    This course provides INDOT staff with foundational knowledge and skills in project management principles and methodologies. INDOTs project management processes provide the tools for interdisciplinary teams to efficiently and effectively deliver pr...

  1. The text plan concept: contributions to the writing planning process

    Directory of Open Access Journals (Sweden)

    Ana Lúcia Tinoco Cabral

    2013-12-01

    Full Text Available Students - at different levels, ranging from early grades up to PhD - face problems both on comprehension and text production. This paper focuses on the text plan concept according to the DTA (Discourse Text Analysis approach, i.e., a principle of organization that allows students to put into practice the production intention as well as to arrange text information while producing; being responsible for the text compositional structure (Adam, 2008. The study analyzes the relation between text plan and the writing planning process, in which the first one provides the second with theoretical support. In order to develop such research, the study covers some issues related to the reading skill, analyzes an argumentative text as per its textual plan, and presents some reflections on the writing process, focusing on the relation between textual plan and the writing planning process.

  2. Management of uranium mining and processing wastes at Turamdih project

    International Nuclear Information System (INIS)

    Puri, R.C.; Verma, R.P.

    1991-01-01

    Based on environmental impact assessment, comprehensive plan for management of wastes has been drawn up. No solid waste from the mine is being disposed off outside the project area. The quantity of waste generated after processing of ore is large because of low content of uranium in the ore. A big tailings pond has been planned in specially selected suitable valley near the plant. No liquid effluents are to be discharged into general surrounding environment. Mine water is to be fed to the process plant. Effluents from tailings pond will be collected in a storage cum evaporation pond. All water from different zones of the project shall be collected in zonal ponds and then pumped to tailings effluent storage pond. All the ponds will be provided with requisite impervious liners. The effluents of the storage pond will be treated for removal of radium and manganese and discharged into monitoring pond. Large surface areas for various ponds are envisaged to take advantage of evaporation with aim for zero discharge. To reduce impact from gaseous emissions, high efficiency dust suppression and extraction systems shall be provided. High stacks have been incorporated for DG set, boiler plants, sulphuric acid plant and dust extraction systems for crushing and grinding section and the quality of discharges will be very much within the prescribed limits. The paper describes the management plan in detail. (author)

  3. City Labs as Vehicles for Innovation in Urban Planning Processes

    Directory of Open Access Journals (Sweden)

    Christian Scholl

    2016-12-01

    Full Text Available This paper assesses the role of urban experiments for local planning processes through a case-based analysis of the city lab of Maastricht. In conjunction with this, the article offers three contributions, as additional elements. Firstly, the paper develops a set of defining characteristics of city labs as an analytical concept which is relevant for discussions about (collaborative planning. Secondly, it refines the literature on collaborative planning by drawing attention to experimentation and innovation. Thirdly, the paper assesses the potential of city labs to contribute to the innovation of urban governance. The work draws from the literature on experimentation and learning as well as the literature on collaborative urban planning. In the conclusions, we discuss the potential of city labs as vehicles for learning about new urban planning approaches and their limitations as spaces for small-scale experimentation. The paper is based on research for the URB@Exp research project funded by JPI Urban Europe.

  4. Achieving Sustainable Value Planning For Malaysian Public Projects

    Directory of Open Access Journals (Sweden)

    Muhammad Faudzi

    2016-01-01

    Full Text Available Sustainability is the central development issue in the modern economy. Through sustainable development, quality of life can be improved or maintained over time. Since Malaysia is targeting to become a high-income nation by the year 2020, financial investment in public projects should be planned comprehensively so that it will generate immediate and long-term benefits to the country and the people. Within the currently tight financial environment, achieving value for money in public spending is seen as one of the enablers to maintain the right momentum of economic growth. Previous studies have established the importance of integrating sustainability consideration into Value Planning protocol in order to achieve value for money, underpinned by the sustainable development agenda. Despite the establishment of the framework for the integration, the opportunity of such integration within the Malaysian Value Planning protocol for public projects remains unclear. The present state of sustainability consideration within the Value Planning practice should be first evaluated, so that potential interventions to enhance the integration can be introduced. Responding to the gap, this exploratory study was conducted. The data was collected by means of document analysis, interviews and observations; subsequently analysed using the Template Analysis technique. Based on the current practice of Value Planning in Malaysia, ten interventions are proposed to transform the present practice into Sustainable Value Planning. Sustainable Value Planning is seen as a comprehensive concept in achieving value for money in public spending underpinned by the overarching concept of sustainability

  5. Up-Stream Dissolved Oxygen TMDL Project Quality Assurance ProjectPlan

    Energy Technology Data Exchange (ETDEWEB)

    Stringfellow, William T.

    2005-05-13

    A quality assurance project plan (QAPP) for the execution of an ecosystem level monitoring and research program examining algal ecology in highly impaired rivers. Procedures for executing both field and laboratory surface water quality and flow analysis are described. The procedures described here are compatible with the California Surface Water Ambient Monitoring program (SWAMP).

  6. I-15 integrated corridor management system : project management plan.

    Science.gov (United States)

    2011-06-01

    The Project Management Plan (PMP) assists the San Diego ICM Team by defining a procedural framework for : management and control of the I-15 Integrated Corridor Management Demonstration Project, and development and : deployment of the ICM System. The...

  7. Quality assurance program plan for 324 Building B-Cell safety cleanout project (BCCP)

    International Nuclear Information System (INIS)

    Tanke, J.M.

    1997-01-01

    This Quality Assurance Program Plan (QAPP) provides information on how the Quality Assurance Program is implemented for the 324 Building B-Cell Safety Cleanout Project (BCCP). This QAPP is responsive to the Westinghouse Hanford Company Quality Assurance Program and Implementation Plan, WHC-SP-1131, for 10 CFR 830.120, Nuclear Safety Management, Quality Assurance Requirements; and DOE Order 5700.6C, Quality Assurance. This QAPP supersedes PNNL PNL-MA-70 QAP Quality Assurance Plan No. WTC-050 Rev. 2, issue date May 3, 1996. This QAPP has been developed specifically for the BCCP. It applies to those items and tasks which affect the completion of activities identified in the work breakdown structure of the Project Management Plan (PMP). These activities include all aspects of decontaminating B-Cell and project related operations within the 324 Building as it relates to the specific activities of this project. General facility activities (i.e. 324 Building Operations) are covered in the Building 324 QAPP. In addition, this QAPP supports the related quality assurance activities addressed in CM-2-14, Hazardous Material Packaging and Shipping, and HSRCM-1, Hanford Site Radiological Control Manual, The 324 Building is currently transitioning from being a Pacific Northwest National Laboratory (PNNL) managed facility to a B and W Hanford Company (BWHC) managed facility. During this transition process existing, PNNL procedures and documents will be utilized until replaced by BWHC procedures and documents. These documents conform to the requirements found in PNL-MA-70, Quality Assurance Manual and PNL-MA-8 1, Hazardous Materials Shipping Manual. The Quality Assurance Program Index (QAPI) contained in Table 1 provides a matrix which shows how project activities relate to 10 CFR 83 0.120 and 5700.6C criteria. Quality Assurance program requirements will be addressed separate from the requirements specified in this document. Other Hanford Site organizations/companies may be

  8. Project summary plan for HTGR recycle reference facility

    International Nuclear Information System (INIS)

    Baxter, B.J.

    1979-11-01

    A summary plan is introduced for completing conceptual definition of an HTGR Recycle Reference Facility (HRRF). The plan describes a generic project management concept, often referred to as the requirements approach to systems engineering. The plan begins with reference flow sheets and provides for the progressive evolution of HRRF requirements and definition through feasibility, preconceptual, and conceptual phases. The plan lays end-to-end all the important activities and elements to be treated during each phase of design. Identified activities and elements are further supported by technical guideline documents, which describe methodology, needed terminology, and where relevant a worked example

  9. Increasing the Value of Research: A Comparison of the Literature on Critical Success Factors for Projects, IT Projects and Enterprise Resource Planning Projects

    Directory of Open Access Journals (Sweden)

    Annie Maddison Warren

    2016-11-01

    Full Text Available Since the beginning of modern project management in the 1960s, academic researchers have sought to identify a definitive list of Critical Success Factors (CSFs, the key things that project managers must get right in order to deliver a successful product. With the advent of Information Technology (IT projects and, more recently, projects to deliver Enterprise Resource Planning (ERP systems, attention has turned to identifying definitive lists of CSFs for these more specific project types. The purpose of this paper is to take stock of this research effort by examining how thinking about each type of project has evolved over time, before producing a consolidated list of CSFs for each as a basis for comparison. This process reveals a high degree of similarity, leading to the conclusion that the goal of identifying a generic list of CSFs for project management has been achieved. Therefore, rather than continuing to describe lists of CSFs, researchers could increase the value of their contribution by taking a step forward and focusing on why, despite this apparent knowledge of how to ensure their success, ERP projects continue to fail.

  10. Moving out or living on a mound? Jointly planning a Dutch flood adaptation project

    NARCIS (Netherlands)

    Roth, D.; Winnubst, M.

    2014-01-01

    All over the world spatial flood risk management policies are on the rise. This paper analyses the planning process for the Overdiepse polder, a so-called “Room for the River” project in the Netherlands. After high water in the 1990s, the Dutch government changed its flood risk management policy.

  11. Process-based software project management

    CERN Document Server

    Goodman, F Alan

    2006-01-01

    Not connecting software project management (SPM) to actual, real-world development processes can lead to a complete divorcing of SPM to software engineering that can undermine any successful software project. By explaining how a layered process architectural model improves operational efficiency, Process-Based Software Project Management outlines a new method that is more effective than the traditional method when dealing with SPM. With a clear and easy-to-read approach, the book discusses the benefits of an integrated project management-process management connection. The described tight coup

  12. Evaluating Levels of Project Planning and their Effects on Performance in the Nigerian Construction Industry

    Directory of Open Access Journals (Sweden)

    Godwin Idoro

    2012-11-01

    Full Text Available This study compares the level of project planning on public andprivate sectors projects and its impact on performance. Thepurpose is to create awareness of the level and effectivenessof the planning done by public and private clients in the deliveryof construction projects. A questionnaire survey administeredto a sample of 130 client representatives selected by stratifi edrandom sampling from the population of public and private clientsin the Nigerian construction industry is used and analysed usingdescriptive statistics, the t-test and Spearman correlation test. Theresults show that the level of preconstruction planning on privatesector projects is higher than that of public sector projects whilethe level of contract planning done by the latter is higher thanthat of the former. Furthermore, the performance of private sectorprojects is higher than that of public sector projects in many of theparameters used. However, the level of preparation of life-cyclecharts that concern project delivery time in both public and privatesectors projects is low and the level of project planning in the twocategories of projects has a limited impact on project performance.The understanding of how public and private sectors projectsperform in planning and its impact are expected to assist publicand private clients to know the challenges ahead of them in theireffort to improve the planning and performance of their projects.

  13. Finance and supply management project execution plan

    Energy Technology Data Exchange (ETDEWEB)

    BENNION, S.I.

    1999-02-10

    As a subproject of the HANDI 2000 project, the Finance and Supply Management system is intended to serve FDH and Project Hanford major subcontractor with financial processes including general ledger, project costing, budgeting, and accounts payable, and supply management process including purchasing, inventory and contracts management. Currently these functions are performed with numerous legacy information systems and suboptimized processes.

  14. Spent Nuclear Fuel Project dose management plan

    International Nuclear Information System (INIS)

    Bergsman, K.H.

    1996-03-01

    This dose management plan facilitates meeting the dose management and ALARA requirements applicable to the design activities of the Spent Nuclear Fuel Project, and establishes consistency of information used by multiple subprojects in ALARA evaluations. The method for meeting the ALARA requirements applicable to facility designs involves two components. The first is each Spent Nuclear Fuel Project subproject incorporating ALARA principles, ALARA design optimizations, and ALARA design reviews throughout the design of facilities and equipment. The second component is the Spent Nuclear Fuel Project management providing overall dose management guidance to the subprojects and oversight of the subproject dose management efforts

  15. FRG sealed isotopic heat sources project (C-229) project management plan

    International Nuclear Information System (INIS)

    Metcalf, I.L.

    1997-01-01

    This Project Management Plan defines the cost, scope, schedule, organizational responsibilities, and work breakdown structure for the removal of the Federal Republic of Germany (FRG) Sealed Isotopic Heat Sources from the 324 Building and placed in interim storage at the Central Waste Complex (CWC)

  16. IT Project Prioritization Process

    DEFF Research Database (Denmark)

    Shollo, Arisa; Constantiou, Ioanna

    2013-01-01

    In most of the large companies IT project prioritization process is designed based on principles of evidencebased management. We investigate a case of IT project prioritization in a financial institution, and in particular, how managers practice evidence-based management during this process. We use...... a rich dataset built from a longitudinal study of the prioritization process for the IT projects. Our findings indicate that managers reach a decision not only by using evidence but from the interplay between the evidence and the judgment devices that managers employ. The interplay between evidence...

  17. Sensemaking in Enterprise Resource Planning Project Deescalation: An Empirical Study

    Science.gov (United States)

    Battleson, Douglas Aloys

    2013-01-01

    Enterprise resource planning (ERP) projects, a type of complex information technology project, are very challenging and expensive to implement. Past research recognizes that escalation, defined as the commitment to a failing course of action, is common in such projects. While the factors that contribute to escalation (e.g., project conditions,…

  18. 40 CFR 130.5 - Continuing planning process.

    Science.gov (United States)

    2010-07-01

    ... QUALITY PLANNING AND MANAGEMENT § 130.5 Continuing planning process. (a) General. Each State shall establish and maintain a continuing planning process (CPP) as described under section 303(e)(3)(A)-(H) of... 40 Protection of Environment 21 2010-07-01 2010-07-01 false Continuing planning process. 130.5...

  19. Planning risk communication for UMTRA project groundwater restoration

    Energy Technology Data Exchange (ETDEWEB)

    Hundertmark, Charles [Jacobs Engineering Group Inc. and University of Phoenix (United States); Hoopes, Jack [Jacobs Engineering Group Inc. (United States); Flowers, Len [Roy F. Weston Company (United States); Jackson, David G [U.S. Department of Energy (United States)

    1992-07-01

    The U.S. Department of Energy's (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project is entering a new phase in which groundwater contamination will become a growing focus as surface remedial action draws toward completion. Planning for risk communication associated with the groundwater project will be a major factor in the successful initiation of the program. (author)

  20. Planning risk communication for UMTRA project groundwater restoration

    International Nuclear Information System (INIS)

    Hundertmark, Charles; Hoopes, Jack; Flowers, Len; Jackson, David G.

    1992-01-01

    The U.S. Department of Energy's (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project is entering a new phase in which groundwater contamination will become a growing focus as surface remedial action draws toward completion. Planning for risk communication associated with the groundwater project will be a major factor in the successful initiation of the program. (author)

  1. Application of System Dynamics model as decision making tool in urban planning process toward stabilizing carbon dioxide emissions from cities

    International Nuclear Information System (INIS)

    Fong, Wee-Kean; Matsumoto, Hiroshi; Lun, Yu-Fat

    2009-01-01

    In spite of the fact that cities are the main sources of CO 2 emissions, presently there are still no specific measures directly addressing the global warming issue in the urban planning process in Malaysia. The present study thus aims to shed new light in the urban planning sector in Malaysia by adopting System Dynamics Model as one of the decision making tools in the urban planning process, with specific considerations on the future CO 2 emission trends. This paper presented projections of future CO 2 emission trends based on the case of Iskandar Development Region of Malaysia, under various options of urban policies, using the System Dynamics Model. The projections demonstrated the capability of the said model in serving as a decision making tool in the urban planning process, with specific reference to CO 2 emissions from cities. Recommendations have been made on the possible approach of adopting the model in the process of Structure Plan study. If the current model was successfully adopted in the urban planning process in Malaysia, it will mark the first step for Malaysia in taking specific considerations on the issues of CO 2 emissions and global warming in the urban planning process. (author)

  2. Tanks Focus Area Alternative Salt Processing Research and Development Program Plan

    Energy Technology Data Exchange (ETDEWEB)

    Harmon, Harry D.

    2000-05-15

    In March 2000, DOE-Headquarters (HQ) requested the Tanks Focus Area (TFA)to assume management responsibility for the Salt Processing Project technology development program at Savannah River Site. The TFA was requested to conduct several activities, including review and revision of the technology development roadmaps, development of down-selection criteria, and preparation of a comprehensive Research and Development (R&D) Program Plan for three candidate cesium removal technologies, as well as the Alpha and strontium removal processes that must also be carried out. The three cesium removal candidate technologies are Crystalline Silicotitanate (CST) Non-Elutable Ion Exchange, Caustic Side Solvent Extraction (CSSX), and Small Tank Tetraphenylborate Precipitation (STTP). This plan describes the technology development needs for each process that must be satisfied in order to reach a down-selection decision, as well as continuing technology development required to support conceptual design activities.

  3. Tanks Focus Area Alternative Salt Processing Research and Development Program Plan

    Energy Technology Data Exchange (ETDEWEB)

    Harmon, Harry D.

    2000-11-30

    In March 2000, DOE-Headquarters (HQ) requested the Tanks Focus Area (TFA) to assume management responsibility for the Salt Processing Project technology development program at Savannah River Site. The TFA was requested to conduct several activities, including review and revision of the technology development roadmaps, development of down-selection criteria, and preparation of a comprehensive Research and Development (R&D) Program Plan for three candidate cesium removal technologies, as well as the Alpha and strontium removal processes that must also be carried out. The three cesium removal candidate technologies are Crystalline Silicotitanate (CST) Non-Elutable Ion Exchange, Caustic Side Solvent Extraction (CSSX), and Small Tank Tetraphenylborate Precipitation (STTP). This plan describes the technology development needs for each process that must be satisfied in order to reach a down-selection decision, as well as continuing technology development required to support conceptual design activities.

  4. REPNET: project scheduling and workflow optimization for Construction Projects

    Directory of Open Access Journals (Sweden)

    Marco Alvise Bragadin

    2013-10-01

    Full Text Available Project planning and control are core processes for construction management. In practice project planning is achieved by network - based techniques like Precedence Diagramming Method (PDM.Indeed many researchers and practitioners claims that networking techniques as such do not provide a suitable model for construction projects. Construction process modeling should incorporate for specific features of resource flows through project activities. So an improved resource scheduling method for construction is developed, called REPNET, based on a precedence network plotted on a resource–space chart and presented with a flow-line chart. The heuristics of REPNET are used to carry out resource timing while optimizing processes flows and resource usage. The method has been tested on a sample project.

  5. The Columbia River Protection Supplemental Technologies Quality Assurance Project Plan

    International Nuclear Information System (INIS)

    Fix, Anne

    2007-01-01

    The U.S. Department of Energy (DOE) has conducted interim groundwater remedial activities on the Hanford Site since the mid-1990s for several groundwater contamination plumes. DOE established the Columbia River Protection Supplemental Technologies Project (Technologies Project) in 2006 to evaluate alternative treatment technologies. The objectives for the technology project are as follows: develop a 300 Area polyphosphate treatability test to immobilize uranium, design and test infiltration of a phosphate/apatite technology for Sr-90 at 100-N, perform carbon tetrachloride and chloroform attenuation parameter studies, perform vadose zone chromium characterization and geochemistry studies, perform in situ biostimulation of chromium studies for a reducing barrier at 100-D, and perform a treatability test for phytoremediation for Sr-90 at 100-N. This document provides the quality assurance guidelines that will be followed by the Technologies Project. This Quality Assurance Project Plan is based on the quality assurance requirements of DOE Order 414.1C, Quality Assurance, and 10 CFR 830, Subpart A--Quality Assurance Requirements as delineated in Pacific Northwest National Laboratory?s Standards-Based Management System. In addition, the technology project is subject to the Environmental Protection Agency (EPA) Requirements for Quality Assurance Project Plans (EPA/240/B-01/003, QA/R-5). The Hanford Analytical Services Quality Assurance Requirements Documents (HASQARD, DOE/RL-96-68) apply to portions of this project and to the subcontractors. HASQARD requirements are discussed within applicable sections of this plan.

  6. Outage planning in nuclear power plants. A paradigm shift from an external towards an integrated project planning tool

    Energy Technology Data Exchange (ETDEWEB)

    Rosemann, Andreas [Gesellschaft fuer integrierte Systemplanung (GiS) mbH, Weinheim (Germany)

    2014-05-15

    In nuclear power plants it is common to carry out the technical planning of the annual outage work orders in an Enterprise Application Management (EAM) system and to schedule the outage tasks in a project planning tool. The reason for this is historical: Former EAM systems did not (or just to some extend) offer the necessary functionalities to realise the scheduling of the outage; graphical support for the planning was not provided at all. Consequently, scheduling the annual outage was performed in a separate planning tool. Modern Enterprise Application Management (EAM) software builds on established project planning tools with respect to the functionalities and timing of work orders. As a standard they provide editable charts as well as a lot of functionalities which are required for scheduling the annual outage. The functional gap between the demanded planning functionalities and the functionalities provided by the EAM system has been significantly reduced. Depending on the deployed software itself it is possible to extend the EAM system with little effort (in comparison to the promising advantages) so that external project timing planning tools are not required any more. By shifting towards an integrated planning tool, efficiency in planning an outage as well as the quality of communication of the current planning status increases. Furthermore, the basis of information for work orders by the control room staff and therefore safety can be enhanced. (orig.)

  7. Outage planning in nuclear power plants. A paradigm shift from an external towards an integrated project planning tool

    International Nuclear Information System (INIS)

    Rosemann, Andreas

    2014-01-01

    In nuclear power plants it is common to carry out the technical planning of the annual outage work orders in an Enterprise Application Management (EAM) system and to schedule the outage tasks in a project planning tool. The reason for this is historical: Former EAM systems did not (or just to some extend) offer the necessary functionalities to realise the scheduling of the outage; graphical support for the planning was not provided at all. Consequently, scheduling the annual outage was performed in a separate planning tool. Modern Enterprise Application Management (EAM) software builds on established project planning tools with respect to the functionalities and timing of work orders. As a standard they provide editable charts as well as a lot of functionalities which are required for scheduling the annual outage. The functional gap between the demanded planning functionalities and the functionalities provided by the EAM system has been significantly reduced. Depending on the deployed software itself it is possible to extend the EAM system with little effort (in comparison to the promising advantages) so that external project timing planning tools are not required any more. By shifting towards an integrated planning tool, efficiency in planning an outage as well as the quality of communication of the current planning status increases. Furthermore, the basis of information for work orders by the control room staff and therefore safety can be enhanced. (orig.)

  8. The EM SSAB Annual Work Plan Process: Focusing Board Efforts and Resources - 13667

    Energy Technology Data Exchange (ETDEWEB)

    Young, Ralph [Paducah Citizens Advisory Board (United States)

    2013-07-01

    One of the most daunting tasks for any new member of a local board of the Environmental Management Site Specific Advisory Board (EM SSAB) is to try to understand the scope of the clean-up activities going on at the site. In most cases, there are at least two or three major cleanup activities in progress as well as monitoring of past projects. When planning for future projects is added to the mix, the list of projects can be long. With the clean-up activities involving all major environmental media - air, water, soils, and groundwater, new EM SSAB members can find themselves totally overwhelmed and ineffective. Helping new members get over this initial hurdle is a major objective of EM and all local boards of the EM SSAB. Even as members start to understand the size and scope of the projects at a site, they can still be frustrated at the length of time it takes to see results and get projects completed. Many project and clean-up timelines for most of the sites go beyond 10 years, so it's not unusual for an EM SSAB member to see the completion of only 1 or 2 projects over the course of their 6-year term on the board. This paper explores the annual work planning process of the EM SSAB local boards, one tool that can be used to educate EM SSAB members into seeing the broader picture for the site. EM SSAB local work plans divide the site into projects focused on a specific environmental issue or media such as groundwater and/or waste disposal options. Projects are further broken down into smaller segments by highlighting major milestones. Using these metrics, local boards of the EM SSAB can start to quantify the effectiveness of the project in achieving the ultimate goal of site clean-up. These metrics can also trigger board advice and recommendations for EM. At the beginning of each fiscal year, the EM SSAB work plan provides a road map with quantifiable checkpoints for activities throughout the year. When the work plans are integrated with site

  9. UMTRA project water sampling and analysis plan, Tuba City, Arizona

    International Nuclear Information System (INIS)

    1996-02-01

    Planned, routine ground water sampling activities at the U.S. Department of Energy (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project site in Tuba City, Arizona, are described in the following sections of this water sampling and analysis plan (WSAP). This plan identifies and justifies the sampling locations, analytical parameters, detection limits, and sampling frequency for the stations routinely monitored at the site. The ground water data are used for site characterization and risk assessment. The regulatory basis for routine ground water monitoring at UMTRA Project sites is derived from the U.S. Environmental Protection Agency (EPA) regulations in 40 CFR Part 192 (1994) and the final EPA standards of 1995 (60 FR 2854). Sampling procedures are guided by the UMTRA Project standard operating procedures (SOP) (JEG, n.d.), and the most effective technical approach for the site

  10. Quality Assurance Program Plan (QAPP) Waste Management Project

    Energy Technology Data Exchange (ETDEWEB)

    VOLKMAN, D.D.

    1999-10-27

    This document is the Quality Assurance Program Plan (QAPP) for Waste Management Federal Services of Hanford, Inc. (WMH), that implements the requirements of the Project Hanford Management Contract (PHMC), HNF-MP-599, Project Hanford Quality Assurance Program Description (QAPD) document, and the Hanford Federal Facility Agreement with Consent Order (Tri-Party Agreement), Sections 6.5 and 7.8. WHM is responsible for the treatment, storage, and disposal of liquid and solid wastes generated at the Hanford Site as well as those wastes received from other US Department of Energy (DOE) and non-DOE sites. WMH operations include the Low-Level Burial Grounds, Central Waste Complex (a mixed-waste storage complex), a nonradioactive dangerous waste storage facility, the Transuranic Storage Facility, T Plant, Waste Receiving and Processing Facility, 200 Area Liquid Effluent Facility, 200 Area Treated Effluent Disposal Facility, the Liquid Effluent Retention Facility, the 242-A Evaporator, 300 Area Treatment Effluent Disposal Facility, the 340 Facility (a radioactive liquid waste handling facility), 222-S Laboratory, the Waste Sampling and Characterization Facility, and the Hanford TRU Waste Program.

  11. Strengthening government health and family planning programs: findings from an action research project in rural Bangladesh.

    Science.gov (United States)

    Simmons, R; Phillips, J F; Rahman, M

    1984-01-01

    An ongoing study at the International Centre for Diarrhoeal Disease Research, Bangladesh (ICDDR,B) is based on the premise that public sector health and family planning programs can be improved through an assessment of the dysfunctional aspects of their operations, the development of problem-solving capabilities, and the transfer of strategies successfully tested in a small-scale pilot project. This paper reports findings from a field trial implemented in a subunit of the project area at an early stage of the project. Operational barriers to public sector program implementation are discussed with regard to the quantity of work, the quality of work, supplies and facilities, integration of health and family planning, and leadership, supervision, and decision making. Initial results of the ICDDR,B intervention on these managerial processes are also indicated.

  12. NEW APPROACH TO TERRITORIAL PLANNING IN UKRAINE TAKING INTO ACCOUNT PROCESSE OF DECENTRALIZATIONAND AUSTRIAS EXPERIENCE

    Directory of Open Access Journals (Sweden)

    Dorosh A.M

    2016-08-01

    Full Text Available Scientific publications, legislation on spatial planning in Ukraine and spatial planning in Austria are analysed. Ukrainian spatial planning system is divided into urban planning and land management planning.According to the Law of Ukraine "On regulation of urban development" urban planning documentation is developed for: the entire territory of Ukraine, the region (a part of Ukraine’s territory and as well for settlements and their parts.According to the Law of Ukraine "On Land Management" most land management documents are developed on the local level.Only two types of land management documentation are developedon the regional level, namely: a land management schemes and feasibility studies of land use and land protection of administrative units; b land management projects for the establishment (changing of the boundaries of administrative units. Such projects as land management projects on ordering the territory for urban needs and land management projects on ordering the residential areas are developed on the local level.Other land management documentation is developed for a particular land parcel (setting boundaries, separation, change of purpose and so on., or has a narrow specialization (area organization of agricultural land parcels, or providing the environmental and economic assessment of crop rotation. It’s found that almost all planning tolls belong to urban planning. Austrian spatial planning has three levels with clear division of competences in all areas. Planning occurs at the level of the federal government, the federal land and the community. Also nominal spatial planning and professional planning in various fields, which has a significant impact on the environment is defined. Analysis of planning competencies at various levels shows that the lower the level of planning, the higher competence in nominal spatial planning and the lower in professional planning. At first a concept of local development which contains the ideas

  13. NIF Projects Controls and Information Systems Software Quality Assurance Plan

    Energy Technology Data Exchange (ETDEWEB)

    Fishler, B

    2011-03-18

    Quality achievement for the National Ignition Facility (NIF) and the National Ignition Campaign (NIC) is the responsibility of the NIF Projects line organization as described in the NIF and Photon Science Directorate Quality Assurance Plan (NIF QA Plan). This Software Quality Assurance Plan (SQAP) is subordinate to the NIF QA Plan and establishes quality assurance (QA) activities for the software subsystems within Controls and Information Systems (CIS). This SQAP implements an activity level software quality assurance plan for NIF Projects as required by the LLNL Institutional Software Quality Assurance Program (ISQAP). Planned QA activities help achieve, assess, and maintain appropriate quality of software developed and/or acquired for control systems, shot data systems, laser performance modeling systems, business applications, industrial control and safety systems, and information technology systems. The objective of this SQAP is to ensure that appropriate controls are developed and implemented for management planning, work execution, and quality assessment of the CIS organization's software activities. The CIS line organization places special QA emphasis on rigorous configuration control, change management, testing, and issue tracking to help achieve its quality goals.

  14. NIF Projects Controls and Information Systems Software Quality Assurance Plan

    International Nuclear Information System (INIS)

    Fishler, B.

    2011-01-01

    Quality achievement for the National Ignition Facility (NIF) and the National Ignition Campaign (NIC) is the responsibility of the NIF Projects line organization as described in the NIF and Photon Science Directorate Quality Assurance Plan (NIF QA Plan). This Software Quality Assurance Plan (SQAP) is subordinate to the NIF QA Plan and establishes quality assurance (QA) activities for the software subsystems within Controls and Information Systems (CIS). This SQAP implements an activity level software quality assurance plan for NIF Projects as required by the LLNL Institutional Software Quality Assurance Program (ISQAP). Planned QA activities help achieve, assess, and maintain appropriate quality of software developed and/or acquired for control systems, shot data systems, laser performance modeling systems, business applications, industrial control and safety systems, and information technology systems. The objective of this SQAP is to ensure that appropriate controls are developed and implemented for management planning, work execution, and quality assessment of the CIS organization's software activities. The CIS line organization places special QA emphasis on rigorous configuration control, change management, testing, and issue tracking to help achieve its quality goals.

  15. Planning for the succession process among Galician family businesses. Brief comparison with Portuguese family businesses

    Directory of Open Access Journals (Sweden)

    Susana Barbeito Roibal

    2006-09-01

    Full Text Available A research project on Galician family owned businesses, financed by the University of A Coruña from 2004 to 2005, analyzed results from 57 of these companies that earned a profit of more than 5 million euro in 2003. One of the aspects examined in this project, which is the aim of this article, shows the importance that Galician family business owners pay to the planning for the succession process. Literature on family owned businesses emphasizes the importance of planning in successful occurrences. The obtained results increasingly show changes in the significance that the Galician family business owners give to our focus of study, almost reaching the level of importance that literature has given to the succession process in the last decade.

  16. Environmental impact assessment in urban transport planning: Exploring process-related barriers in Spanish practice

    Energy Technology Data Exchange (ETDEWEB)

    Soria-Lara, Julio A., E-mail: j.a.sorialara@uva.nl; Bertolini, Luca, E-mail: l.bertolini@uva.nl; Brömmelstroet, Marco te, E-mail: M.C.G.teBrommelstroet@uva.nl

    2015-01-15

    The effectiveness of EIA for evaluating transport planning projects is increasingly being questioned by practitioners, institutions and scholars. The academic literature has traditionally focused more on solving content-related problems with EIA (i.e. the measurement of environmental effects) than on process-related issues (i.e. the role of EIA in the planning process and the interaction between key actors). Focusing only on technical improvements is not sufficient for rectifying the effectiveness problems of EIA. In order to address this knowledge gap, the paper explores how EIA is experienced in the Spanish planning context and offers in-depth insight into EIA process-related issues in the field of urban transport planning. From the multitude of involved actors, the research focuses on exploring the perceptions of the two main professional groups: EIA developers and transport planners. Through a web-based survey we assess the importance of process-related barriers to the effective use of EIA in urban transport planning. The analyses revealed process issues based fundamentally on unstructured stakeholders involvement and an inefficient public participation - Highlights: • Qualitative research on perceptions of EIA participants on EIA processes. • Web-based survey with different participants (EIA-developers; transport planners). • It was seen an inefficient participation of stakeholders during the EIA processes.

  17. Environmental impact assessment in urban transport planning: Exploring process-related barriers in Spanish practice

    International Nuclear Information System (INIS)

    Soria-Lara, Julio A.; Bertolini, Luca; Brömmelstroet, Marco te

    2015-01-01

    The effectiveness of EIA for evaluating transport planning projects is increasingly being questioned by practitioners, institutions and scholars. The academic literature has traditionally focused more on solving content-related problems with EIA (i.e. the measurement of environmental effects) than on process-related issues (i.e. the role of EIA in the planning process and the interaction between key actors). Focusing only on technical improvements is not sufficient for rectifying the effectiveness problems of EIA. In order to address this knowledge gap, the paper explores how EIA is experienced in the Spanish planning context and offers in-depth insight into EIA process-related issues in the field of urban transport planning. From the multitude of involved actors, the research focuses on exploring the perceptions of the two main professional groups: EIA developers and transport planners. Through a web-based survey we assess the importance of process-related barriers to the effective use of EIA in urban transport planning. The analyses revealed process issues based fundamentally on unstructured stakeholders involvement and an inefficient public participation - Highlights: • Qualitative research on perceptions of EIA participants on EIA processes. • Web-based survey with different participants (EIA-developers; transport planners). • It was seen an inefficient participation of stakeholders during the EIA processes

  18. OCRWM's evolving strategic planning process and the 1990 plan

    International Nuclear Information System (INIS)

    Sprecher, W.M.; Munro, J.F.; Champagne, D.L.

    1991-01-01

    In 1990, the Secretary of Energy (Secretary Watkins) ordered that all 23 of the Department's major organizations adopt systems of strategic planning. This paper explains the strategic planning process being adopted by one of those organizations, the Office of Civilian Radioactive Waste Management (OCRWM). Secretary Watkins also ordered a much-abbreviated planning cycle for 1990 to produce the first set of plans in September. That first plan for OCRWM is also discussed here

  19. Project Specific Quality Assurance Plan Project (QAPP) W-211 Initial Tank Retrieval Systems (ITRS)

    International Nuclear Information System (INIS)

    HALL, L.R.

    2000-01-01

    This Quality Assurance Program Plan (QAPP) provides information on how the Project Hanford Quality Assurance Program is implemented by CH2M HILL Hanford Group Inc (CHG) for managing the Initial Tank Retrieval Systems (ITRS), Project W-211. This QAPP is responsive to the CHG Quality Assurance Program Description (QAPD) (LMH-MP-599) which provides direction for compliance to 10 CFR 830 120, ''Nuclear Safety Management, Quality Assurance Requirements'', and DOE Order 5700 6C, ''Quality Assurance'' Project W-211 modifies existing facilities and provides systems for retrieval of radioactive wastes from selected double-shell tanks (DST). The contents of these tanks are a combination of supernatant liquids and settled solids. To retrieve waste from the tanks, it is first necessary to mix the liquid and solids prior to transferring the slurry to alternative storage or treatment facilities. The ITRS will provide systems to mobilize the settled solids and transfer the wastes out of the tanks. In so doing, ITRS provides feed for future processing plants, allows for consolidation of tank solids to manage space within existing DST storage capacity, and supports continued safe storage of tank waste. This project includes the design, procurement, construction, startup and turnover of these retrieval systems This QAPP identifies organizational structures and responsibilities. Implementing procedures used by CHG project management can be found in the CHG Quality Assurance Program (CHG QAP) Implementation Matrix located in HNF-IP-0842, Volume XI, Attachment Proposed verification and inspection activities for critical items within the scope of project W-211 are identified in Attachment 1 W-211. Project participants will identify the implementing procedures used by their organization within their QAF'Ps. This project specific QAPP is used to identify requirements in addition to the QAPD and provide, by reference, additional information to other project documents

  20. Spent Nuclear Fuel project systems engineering management plan

    International Nuclear Information System (INIS)

    Womack, J.C.

    1995-01-01

    The purpose of the WHC Systems Engineering Management Plan (SEMP) is to describe the systems engineering approach and methods that will be integrated with established WHC engineering practices to enhance the WHC engineering management of the SNF Project. The scope of the SEMP encompasses the efforts needed to manage the WHC implementation of systems engineering on the SNF Project. This implementation applies to, and is tailored to the needs of the SNF project and all its subprojects, including all current and future subprojects

  1. Lightning Mapper Sensor Lens Assembly S.O. 5459: Project Management Plan

    Science.gov (United States)

    Zeidler, Janet

    1999-01-01

    Kaiser Electro-Optics, Inc. (KEO) has developed this Project Management Plan for the Lightning Mapper Sensor (LMS) program. KEO has integrated a team of experts in a structured program management organization to meet the needs of the LMS program. The project plan discusses KEO's approach to critical program elements including Program Management, Quality Assurance, Configuration Management, and Schedule.

  2. Mitigation and monitoring plan for impacted wetlands at the Gunnison UMTRA Project site, Gunnison, Colorado

    International Nuclear Information System (INIS)

    1992-06-01

    The U.S Department of Energy (DOE) administers the Uranium Mill Tailings Remedial Action (UMTRA) Project. The UMTRA Project is the result of the Uranium Mill Tailings Radiation Control Act(UMTRA) which was passed in response to the public's concern over the potential public health hazards related to uranium mill tailings and associated contaminated material at abandoned or otherwise uncontrolled inactive processing sites throughout the United States. The Gunnison, Colorado abandoned uranium mill site is one of the sites slated for cleanup by the DOE under authority of UMTRA. The contaminated material at this site will be transported to a disposal site on US Bureau of Land Management (BLM) land east of Gunnison. Remedial action activities will temporarily disturb 0.8 acre and permanently eliminate 5.1 acres of wetlands. This report describes the proposed mitigation plan for the 5.9 acres of impacted wetlands. In conjunction with the mitigation of the permanently impacted wetlands through the enhancement of wetland and adjacent riparian areas, impacts to wildlife as a result of this project will also be mitigated. However, wildlife mitigation is not the focus of this document and is covered in relevant BLM permits for this project. This plan proposes the enhancement of a 3:1 ratio of impacted wetlands in accordance with US Environmental Protection Agency guidelines, plus the enhancement of riparian areas for wildlife mitigation. Included in this mitigation plan is a monitoring plan to ensure that the proposed measures are working and being maintained

  3. Large hadron collider (LHC) project quality assurance plan

    Energy Technology Data Exchange (ETDEWEB)

    Gullo, Lisa; Karpenko, Victor; Robinson, Kem; Turner, William; Wong, Otis

    2002-09-30

    The LHC Quality Assurance Plan is a set of operating principles, requirements, and practices used to support Berkeley Lab's participation in the Large Hadron Collider Project. The LHC/QAP is intended to achieve reliable, safe, and quality performance in the LHC project activities. The LHC/QAP is also designed to fulfill the following objectives: (1) The LHC/QAP is Berkeley Lab's QA program document that describes the elements necessary to integrate quality assurance, safety management, and conduct of operations into the Berkeley Lab's portion of the LHC operations. (2) The LHC/QAP provides the framework for Berkeley Lab LHC Project administrators, managers, supervisors, and staff to plan, manage, perform, and assess their Laboratory work. (3) The LHC/QAP is the compliance document that conforms to the requirements of the Laboratory's Work Smart Standards for quality assurance (DOE O 414.1, 10 CFR 830.120), facility operations (DOE O 5480.19), and safety management (DOE P 450.4).

  4. Large hadron collider (LHC) project quality assurance plan

    International Nuclear Information System (INIS)

    Gullo, Lisa; Karpenko, Victor; Robinson, Kem; Turner, William; Wong, Otis

    2002-01-01

    The LHC Quality Assurance Plan is a set of operating principles, requirements, and practices used to support Berkeley Lab's participation in the Large Hadron Collider Project. The LHC/QAP is intended to achieve reliable, safe, and quality performance in the LHC project activities. The LHC/QAP is also designed to fulfill the following objectives: (1) The LHC/QAP is Berkeley Lab's QA program document that describes the elements necessary to integrate quality assurance, safety management, and conduct of operations into the Berkeley Lab's portion of the LHC operations. (2) The LHC/QAP provides the framework for Berkeley Lab LHC Project administrators, managers, supervisors, and staff to plan, manage, perform, and assess their Laboratory work. (3) The LHC/QAP is the compliance document that conforms to the requirements of the Laboratory's Work Smart Standards for quality assurance (DOE O 414.1, 10 CFR 830.120), facility operations (DOE O 5480.19), and safety management (DOE P 450.4)

  5. ERGONOMIC ASPECTS IN THE PLANNING AND EXECUTION OF PROJECTS: A TEXTILE PRODUCTS DISTRIBUTION CENTER PROJECT CASE STUDY

    Directory of Open Access Journals (Sweden)

    Emerson Lourenço da Silva

    2013-01-01

    Full Text Available The planning and execution phases of a distribution center project of a large textile industry was made, evaluating the ergonomic aspects related to the operations to be performed in the facility and staff anthropometric data. The ergonomic collaborative analysis of the tasks associated with the method of movement plotting, guided the planning of the picking, manual induction and order consolidation areas from the distribution center. Using this methodology, it was possible to obtain a proper ergonomically project planning and execution of the three studied areas.

  6. Near-facility environmental monitoring quality assurance project plan

    International Nuclear Information System (INIS)

    McKinney, S.M.

    1997-01-01

    This Quality Assurance Project Plan addresses the quality assurance requirements for the activities associated with the preoperational and near facility environmental monitoring performed by Waste Management Federal Services, Inc., Northwest Operations and supersedes WHC-EP-0538-2. This plan applies to all sampling and monitoring activities performed by waste management Federal Services, Inc., Northwest Operations in implementing facility environmental monitoring at the Hanford Site

  7. 42 CFR 59.5 - What requirements must be met by a family planning project?

    Science.gov (United States)

    2010-10-01

    ... requirements must be met by a family planning project? (a) Each project supported under this part must: (1... (iii) Promote continued participation in the project by persons to whom family planning services may be... services purchased for project participants will be authorized by the project director or his designee on...

  8. Neste plans three projects

    International Nuclear Information System (INIS)

    Anon.

    1993-01-01

    Neste Chemicals (Helsinki) is discussing three joint ventures with local authorities in China, says Mikko Haapavaara, v.p./Asia. The projects should help the Finnish producer to increase sales in Asia by a considerable amount by 2000, he says. The plan involves production of polyethylene (PE), unsaturated polyester resins and PE compounding-all core operations. Sites have not been selected, but Shanghai is the favored location for the PE operations. The company is also looking at a site in the south, near Hong Kong, and at locations near Beijing. The PE plant would need to be near an ethylene unit, says Haapavaara. The PE resin plant would be designed to produce about 150,000 m.t./year and would cost about No. 150 million. A part of the output would need to be exported to take care of the financing, the company says. A feasibility study now under way with the potential Chinese partners should be completed by the end of March. The plant would use Neste's linear low-density PE process, proved in a world-scale plant at Beringen, Belgium. The compounding units would produce specialty PE material for the wire and cable and pipe industry. The company is a joint venture partner in a propane dehydrogenation/polypropylene (PP) plant and a minority partner in a Qualipoly, the 20,000 m.t./year unsaturated polyester resin producer

  9. 7 CFR 1209.40 - Programs, plans, and projects.

    Science.gov (United States)

    2010-01-01

    ..., plan, or project, no reference to a brand name, trade name, or State or regional identification of any... SERVICE (MARKETING AGREEMENTS AND ORDERS; MISCELLANEOUS COMMODITIES), DEPARTMENT OF AGRICULTURE MUSHROOM...

  10. Public affairs plan

    International Nuclear Information System (INIS)

    1995-09-01

    The purpose of the Uranium Mill Tailings Remedial Action (UMTRA) Project Public Affairs Plan is to establish goals for the fiscal year (FY) 1996 UMTRA Project public affairs program and to identify specific activities to be conducted during the year. It describes the roles of various agencies involved in the public affairs program and defines the functions of the UMTRA Project Technical Assistance Contractor (TAC) Public Affairs Department. It replaces the FY 1995 Public Affairs Plan (DOE/AL/62350-154). The plan also describes the US Department of Energy's (DOE) plans to keep stakeholders and other members of the public informed about UMTRA Project policies, plans, and activities, and provide opportunities for stakeholders and interested segments of the public to participate in UMTRA Project decision-making processes. The plan applies to the UMTRA Project Team; the DOE Grand Junction Projects Office (GJPO); the DOE Albuquerque Operations Office, Office of Public Affairs (OPA); the TAC; the UMTRA Project Remedial Action Contractor (RAC); and other cooperating agencies

  11. Systems Engineering Management Plan

    International Nuclear Information System (INIS)

    1994-01-01

    The purpose of this Monitored Retrievable Storage (MRS) Project Systems Engineering Management Plan (SEMP) is to define and establish the MRS Project Systems Engineering process that implements the approved policy and requirements of the Office of Civilian Radioactive Waste Management (OCRWM) for the US Department of Energy (DOE). This plan is Volume 5 of the MRS Project Management Plan (PMP). This plan provides the framework for implementation of systems engineering on the MRS Project consistent with DOE Order 4700.1, the OCRWM Program Management System Manual (PMSM), and the OCRWM Systems Engineering Management Plan (SEMP)

  12. Use of project management approach for planning of decommissioning activities of a uranium mining site

    Energy Technology Data Exchange (ETDEWEB)

    Ribeiro, Saulo F.Q.; Lage, Ricardo F.; Gomes, Danielle E.; Ogawa, Iukio, E-mail: quintao.saulo@gmail.com, E-mail: rflage@gmail.com, E-mail: danielle@inb.gov.br, E-mail: iukio@inb.gov.br [Indústrias Nucleares do Brasil (INB), Rio de Janeiro, RJ (Brazil)

    2017-07-01

    The decommissioning of nuclear facilities in the fuel cycle is an extremely important factor for the continuity of nuclear program in any country, especially in that countries such as Brazil, where there are some facilities are in process of being dismantled or must be decommissioned in the medium and long term. Since the decommissioning is a process quite complex and expensive and for this reason, it must be handle with modern management practices for so that the chances of success are increased. This work aims to describe the management plan and the strategy adopted for the execution of the decommissioning and environmental remediation (D and ER) activities for the first uranium mine in Brazil, located in the Minas Gerais State and known as Unidade de Tratamento de Minério (UTM). This facility was operated between 1982 and 1995. All the economically recoverable uranium was extracted and nowadays there is no mining activity is underway and there are only research and laboratory activities are running in the site. The conceptual plans for decommissioning and remediation for this unit have been prepared and emergency activities were recommended. These activities are related to studies about drainage acid, ensure safety of dams, adequacy of CAKE II storage conditions and request for operating licenses for the decommissioning from IBAMA and the authorization from CNEN. The majority of the critical factors for decommissioning had their origin due the characteristics of the project have been implemented and has remained due to uncertainties in the decision-making process over time. This project has a set of variables that need to be analyzed considering different aspects as licensing and regulatory framework, radiological, technical and engineering issues, beyond costs, schedule, risks and human resources. In this sense, it was decided to adopt the good practices of project management, published by the Project Management Institute - PMI and to give a differentiated

  13. Use of project management approach for planning of decommissioning activities of a uranium mining site

    International Nuclear Information System (INIS)

    Ribeiro, Saulo F.Q.; Lage, Ricardo F.; Gomes, Danielle E.; Ogawa, Iukio

    2017-01-01

    The decommissioning of nuclear facilities in the fuel cycle is an extremely important factor for the continuity of nuclear program in any country, especially in that countries such as Brazil, where there are some facilities are in process of being dismantled or must be decommissioned in the medium and long term. Since the decommissioning is a process quite complex and expensive and for this reason, it must be handle with modern management practices for so that the chances of success are increased. This work aims to describe the management plan and the strategy adopted for the execution of the decommissioning and environmental remediation (D and ER) activities for the first uranium mine in Brazil, located in the Minas Gerais State and known as Unidade de Tratamento de Minério (UTM). This facility was operated between 1982 and 1995. All the economically recoverable uranium was extracted and nowadays there is no mining activity is underway and there are only research and laboratory activities are running in the site. The conceptual plans for decommissioning and remediation for this unit have been prepared and emergency activities were recommended. These activities are related to studies about drainage acid, ensure safety of dams, adequacy of CAKE II storage conditions and request for operating licenses for the decommissioning from IBAMA and the authorization from CNEN. The majority of the critical factors for decommissioning had their origin due the characteristics of the project have been implemented and has remained due to uncertainties in the decision-making process over time. This project has a set of variables that need to be analyzed considering different aspects as licensing and regulatory framework, radiological, technical and engineering issues, beyond costs, schedule, risks and human resources. In this sense, it was decided to adopt the good practices of project management, published by the Project Management Institute - PMI and to give a differentiated

  14. Integrating a Procurement Management Process into Critical Chain Project Management (CCPM: A Case-Study on Oil and Gas Projects, the Piping Process

    Directory of Open Access Journals (Sweden)

    Sung-Hwan Jo

    2018-05-01

    Full Text Available Engineering, Procurement, and Construction (EPC of oil and gas megaprojects often experience cost overruns due to substantial schedule delays. One of the greatest causes of these overruns is the mismanagement of the project schedule, with the piping works (prefabrication and installation occupying a majority of that schedule. As such, an effective methodology for scheduling, planning, and controlling of piping activities is essential for project success. To meet this need, this study used the Critical Chain Project Management (CCPM to develop a piping construction delay prevention methodology, incorporating material procurement processes for EPC megaprojects. Recent studies indicate that the traditional scheduling method used on oil and gas mega projects has critical limitations regarding resource scarcity, calculation of activity duration, and dealing with uncertainties. To overcome these limitations, the Theory of Constraints-based CCPM was proposed and implemented to provide schedule buffers management. Nonexistent in literature, and of critical importance, is this paper’s focus on the resource buffer, representing material uncertainty and management. Furthermore, this paper presents a step-by-step process and flow chart for project, construction, and material managers to effectively manage a resource buffer through the CCPM process. This study extends the knowledge of traditional resource buffers in CCPM to improve material and procurement management, thus avoiding the shortage of piping materials and minimizing delays. The resultant process was validated by both deterministic and probabilistic schedule analysis through two case studies of a crude pump unit and propylene compressor installation at a Middle Eastern Refinery Plant Installation. The results show that the CCPM method effectively handles uncertainty, reducing the duration of piping works construction by about a 35% when compared to the traditional method. Furthermore, the

  15. 45 CFR 98.14 - Plan process.

    Science.gov (United States)

    2010-10-01

    ... 45 Public Welfare 1 2010-10-01 2010-10-01 false Plan process. 98.14 Section 98.14 Public Welfare DEPARTMENT OF HEALTH AND HUMAN SERVICES GENERAL ADMINISTRATION CHILD CARE AND DEVELOPMENT FUND General Application Procedures § 98.14 Plan process. In the development of each Plan, as required pursuant to § 98.17...

  16. A Process for Planning.

    Science.gov (United States)

    Gurowitz, William D.; And Others

    1988-01-01

    Describes how Division of Campus Life at Cornell University conducted long-range planning and the results of its 2-year effort. Explains 2 (strategic and organizational) by 3 (diagnosis, formulation, and execution) matrix providing systems view from describing and evaluating long-range planning. Presents 10-step process implemented at Cornell. (NB)

  17. River Basin Management Plans - Institutional framework and planning process

    DEFF Research Database (Denmark)

    Frederiksen, Pia; Nielsen, Helle Ørsted; Pedersen, Anders Branth

    2011-01-01

    The report it a deliverable to the Waterpraxis project, based on research carried out in WP3. It is based on country reports from analyses of water planning in one river basin district in each of the countries Sweden, Finland, Latvia, Lithuania, Poland, Germany and Denmark, and it compares the in...

  18. As Built Verification Plan for Cask Transportation Facility Modifications (CTFM) - Project A.5 and A.6

    International Nuclear Information System (INIS)

    LANE, K.I.

    2000-01-01

    This document establishes an As-built Verification Plan (AVP) for implementing requirements in PHMC Engineering Requirements HNF-PRO-1819, Rev. 4, Sections 2.8.3.d and 2.10.8 and Spent Nuclear Fuels (SNF) Project Administrative Procedure EN-6-012-01. This AVP defines and implements approved processes to document the physical configuration of the project scope installed within the facility and identify discrepancies between the associated project engineering drawings and the field configuration, and the component index (CI) database as defined in AP EN 6-005-02. This AVP defines requirements for project activities verifying conformance of structures, systems, and components (SSCs) to project specified requirements

  19. Incorporating the Six Core Elements of Health Care Transition Into a Medicaid Managed Care Plan: Lessons Learned From a Pilot Project.

    Science.gov (United States)

    McManus, Margaret; White, Patience; Pirtle, Robin; Hancock, Catina; Ablan, Michael; Corona-Parra, Raquel

    2015-01-01

    This pediatric-to-adult health care transition pilot project describes the process and results of incorporating the "Six Core Elements of Health Care Transition (2.0)" into a Medicaid managed care plan with a group of 35 18-23 year olds who have chronic mental health, developmental, and complex medical conditions. The pilot project demonstrated an effective approach for customizing and delivering recommended transition services. At the start of the 18-month project, the Medicaid plan was at the basic level (1) of transition implementation of the Six Core Elements with no transition policy, member transition readiness assessment results, health care transition plans of care, updated medical summaries, transfer package for the adult-focused provider, and assurance of transfer completion and consumer feedback. At the conclusion of the pilot project, the plan scored at level 3 on each core element. The primary reason for not scoring at the highest level (4) was because the transition elements have not been incorporated into services for all enrollees within the plan. Future efforts in managed care will benefit from starting the transition process much earlier (ages 12-14), expanding the role of nurse care managers and participating pediatric and adult-focused clinicians in transition, and offering payment incentives to clinicians to implement the Six Core Elements of Health Care Transition. Copyright © 2015 Elsevier Inc. All rights reserved.

  20. Use of focus groups in a library's strategic planning process.

    Science.gov (United States)

    Higa-Moore, Mori Lou; Bunnett, Brian; Mayo, Helen G; Olney, Cynthia A

    2002-01-01

    The use of focus groups to determine patron satisfaction with library resources and services is extensive and well established. This article demonstrates how focus groups can also be used to help shape the future direction of a library as part of the strategic planning process. By responding to questions about their long-term library and information needs, focus group participants at the University of Texas Southwestern Medical Center at Dallas Library contributed an abundance of qualitative patron data that was previously lacking from this process. The selection and recruitment of these patrons is discussed along with the line of questioning used in the various focus group sessions. Of special interest is the way the authors utilized these sessions to mobilize and involve the staff in creating the library's strategic plan. This was accomplished not only by having staff members participate in one of the sessions but also by sharing the project's major findings with them and instructing them in how these findings related to the library's future. The authors' experience demonstrates that focus groups are an effective strategic planning tool for libraries and emphasizes the need to share information broadly, if active involvement of the staff is desired in both the development and implementation of the library's strategic plan.

  1. Final Hanford Site Transuranic (TRU) Waste Characterization Qualit Assurance Project Plan

    International Nuclear Information System (INIS)

    GREAGER, T.M.

    1999-01-01

    The Transuranic Waste Characterization Quality Assurance Program Plan required each U.S. Department of Energy (DOE) site that characterizes transuranic waste to be sent the Waste Isolation Pilot Plan that addresses applicable requirements specified in the quality assurance project plan (QAPP)

  2. Pacific Northwest National Laboratory Apatite Investigation at the 100-NR-2 Quality Assurance Project Plan

    Energy Technology Data Exchange (ETDEWEB)

    Fix, N. J.

    2008-03-28

    This Quality Assurance Project Plan provides the quality assurance requirements and processes that will be followed by staff working on the 100-NR-2 Apatite Project. The U.S. Department of Energy, Fluor Hanford, Inc., Pacific Northwest National Laboratory, and the Washington Department of Ecology agreed that the long-term strategy for groundwater remediation at 100-N would include apatite sequestration as the primary treatment, followed by a secondary treatment. The scope of this project covers the technical support needed before, during, and after treatment of the targeted subsurface environment using a new high-concentration formulation.

  3. The Single And Multi Project Approach To Planning And Scheduling

    DEFF Research Database (Denmark)

    Andersson, Niclas

    2008-01-01

    The fragmentation of the construction industry in Denmark is reflected in the organisation of construction projects, which typically involves a large number of subcontractors. The main contractor, being responsible for the planning and scheduling of construction work, is thus faced with the chall......The fragmentation of the construction industry in Denmark is reflected in the organisation of construction projects, which typically involves a large number of subcontractors. The main contractor, being responsible for the planning and scheduling of construction work, is thus faced...

  4. 15 CFR 923.13 - Energy facility planning process.

    Science.gov (United States)

    2010-01-01

    ... facility planning process. The management program must contain a planning process for energy facilities... 15 Commerce and Foreign Trade 3 2010-01-01 2010-01-01 false Energy facility planning process. 923... affected public and private parties will be involved in the planning process. [61 FR 33806, June 28, 1996...

  5. Advanced Life Support Project Plan

    Science.gov (United States)

    2002-01-01

    Life support systems are an enabling technology and have become integral to the success of living and working in space. As NASA embarks on human exploration and development of space to open the space frontier by exploring, using and enabling the development of space and to expand the human experience into the far reaches of space, it becomes imperative, for considerations of safety, cost, and crew health, to minimize consumables and increase the autonomy of the life support system. Utilizing advanced life support technologies increases this autonomy by reducing mass, power, and volume necessary for human support, thus permitting larger payload allocations for science and exploration. Two basic classes of life support systems must be developed, those directed toward applications on transportation/habitation vehicles (e.g., Space Shuttle, International Space Station (ISS), next generation launch vehicles, crew-tended stations/observatories, planetary transit spacecraft, etc.) and those directed toward applications on the planetary surfaces (e.g., lunar or Martian landing spacecraft, planetary habitats and facilities, etc.). In general, it can be viewed as those systems compatible with microgravity and those compatible with hypogravity environments. Part B of the Appendix defines the technology development 'Roadmap' to be followed in providing the necessary systems for these missions. The purpose of this Project Plan is to define the Project objectives, Project-level requirements, the management organizations responsible for the Project throughout its life cycle, and Project-level resources, schedules and controls.

  6. Integrated project management plan for the Plutonium Finishing Plant stabilization and deactivation project

    International Nuclear Information System (INIS)

    SINCLAIR, J.C.

    1999-01-01

    This document sets forth the plans, organization, and control systems for managing the PFP Stabilization and Deactivation Project, and includes the top level cost and schedule baselines. The project includes the stabilization of Pu-bearing materials, storage, packaging, and transport of these and other nuclear materials, surveillance and maintenance of facilities and systems relied upon for storage of the materials, and transition of the facilities in the PFP Complex

  7. Phase-based Planning for Railway Infrastructure Projects

    DEFF Research Database (Denmark)

    Li, Rui

    2017-01-01

    is important in terms of economy and rail operations. This study presents two types of Phase-based Decision Support System (PDSS), i.e. Functional Phase-Based Planning Approach (F-PBPA) and Process-Oriented Phase-Based Planning Approach (PO-PBPA). They are used for decision support for the planning...... of the railway infrastructure maintenance activities at the strategic planning level. The objective is to achieve better economy, as well as improve cost efficiency. F-PBPA consists of ve main phases: Data Collection, Technical Optimization (TeO), Economic Optimization (EcO), Constrained Optimization (Co...... the costs. Finally, constrained optimization (CoO) includes additional constraints and it allows the railway expert to adjust input parameters, thereby to obtain alternative maintenance plans. PO-PBPA contains another systematic phase based process. With a focus on Life Cycle Cost (LCC), PO-PBPA can guide...

  8. Robustness evaluation of cutting tool maintenance planning for soft ground tunneling projects

    Directory of Open Access Journals (Sweden)

    Alena Conrads

    2018-03-01

    Full Text Available Tunnel boring machines require extensive maintenance and inspection effort to provide a high availability. The cutting tools of the cutting wheel must be changed timely upon reaching a critical condition. While one possible maintenance strategy is to change tools only when it is absolutely necessary, tools can also be changed preventively to avoid further damages. Such different maintenance strategies influence the maintenance duration and the overall project performance. However, determine downtime related to a particular maintenance strategy is still a challenging task. This paper shows an analysis of the robustness to achieve the planned project performance of a maintenance strategy considering uncertainties of wear behavior of the cutting tools. A simulation based analysis is presented, implementing an empirical wear prediction model. Different strategies of maintenance planning are compared by performing a parameter variation study including Monte-Carlo simulations. The maintenance costs are calculated and evaluated with respect to their robustness. Finally, an improved and robust maintenance strategy has been determined. Keywords: Mechanized tunneling, Maintenance, Wear of cutting tools, Process simulation, Robustness, Uncertainty modeling

  9. Approach to Issues in Planning and Operation of Railway BOT Projects

    Institute of Scientific and Technical Information of China (English)

    Zhao Xianghong; Chen Min

    2009-01-01

    As an internationally popular mode of public infrastructures' investment,construction and operation,BOT (build-operate-transfer) has been successfully applied in some countries and regions of the world for their infrastructures' construction and playing an important role in promoting the construction of public infrastructures.The Ministry of Railways clearly proposed in its Suggestions for Implementation of Encouraging,Supporting and Guiding Participation of Non-public-owned Economy in Railway Construction and Operation that it was necessary to study and take for reference multiple modes of public infrastructures'investment,construction and operation including BOT.It is more complicated and risky for the process of planning and operation of BOT projects.The paper takes for reference the domestic and foreign experiences in the operation of BOT projects,analyzes the issues that will arise such as risk control in implementing railway BOT projects,employment of professional consultants,financing coordination,tariff making,non-commercial subsidy,as well as operation and management,and puts forward corresponding suggestions for these issues.

  10. Nez Perce tribal hatchery project : combined-planning and design and operations and maintenance reports, annual report, 2000

    International Nuclear Information System (INIS)

    Larson, Roy Edward; Walker, Grant

    2002-01-01

    Nez Perce Tribal Hatchery (NPTH) Year-2000 Combined Maintenance and Operations (O and M) and Planning and Design (P and D) contract is hereby completed based on this annual report patterned after the Statement of Work (SOW) for the project as contracted with Bonneville Power Administration. Primary project activities focused on completion of the Northwest Power Planning Council Step-3 process that: (1) Accepted final design, (2) Authorized a capital construction amount of $16,050,000, and (3) Authorized contractor selection, and (4) Provided construction site dedication, and (5) Implemented construction activities over an anticipated 2-year period of July 2000 through October 2002

  11. Projects of Strategic Action Plan of S&T Innovation

    Institute of Scientific and Technical Information of China (English)

    2002-01-01

    @@ In July 2001, CAS decided to shift the focus of the current Knowledge Innovation Program (KIP) onto research projects designed to meet the country's strategic needs, and Iaunched the strategic action plan of innovation (SAPI). Under the SAPI, CAS organized the implementation of seven major projects in 2001.The followings are their profiles.

  12. Prestudy: Inventory and review of risk analysis applications in the grid planning process; Foerstudie: Inventering och redovisning av riskanalys-tillaempningar i naetplanerings-processen

    Energy Technology Data Exchange (ETDEWEB)

    Owe, Pernilla

    2007-11-15

    The project investigates the network planning process and the risks connected to this. The purpose is to investigate which parts of the process that are most suited for implementation of risk analysis applications. The project is divided in two parts of which this report describes the first part. Experiences from distribution and sub transmission network, in urban areas as well as in rural areas, were gathered through interviews with staff from Fortum, E.ON and Vattenfall. There are differences in the network planning processes in the companies, depending on their needs and organization, but at a higher level the processes shows to be quite similar to each other. Both network analysis and optimization are included in the network planning process that is further described in section 3.1, in other words the planning from idea or need to the project decision. The detailed project design is not included in the process. The found hazards are on many counts the same for all network companies. The larger companies have some kind of risk policy or comprehensive risk control function, but the extension and application differs. It is most likely that also this will be more and more similar in the future, due to benchmarking and best practice. The evaluation and ranking of the risks was not a task in this first part of the project, but should be handled in the second part

  13. Project management plan for Reactor 105-C Interim Safe Storage project

    International Nuclear Information System (INIS)

    Plagge, H.A.

    1996-09-01

    Reactor 105-C (located on the Hanford Site in Richland, Washington) will be placed into an interim safe storage condition such that (1) interim inspection can be limited to a 5-year frequency; (2) containment ensures that releases to the environmental are not credible under design basis conditions; and (3) final safe storage configuration shall not preclude or significantly increase the cost for any decommissioning alternatives for the reactor assembly.This project management plan establishes plans, organizational responsibilities, control systems, and procedures for managing the execution of Reactor 105-C interim safe storage activities to meet programmatic requirements within authorized funding and approved schedules

  14. European DataGrid project Status and plans

    CERN Document Server

    Kunszt, Peter Z

    2003-01-01

    The European DataGrid (EDG) project has reached, after 1.5 years, the middle of its lifetime. In this article we give an overview of the status, components, procedures and plans of the EDG project as of June 2002. The objective of the EDG project is to assist the next generation of scientific exploration, computation and analysis of large-scale data sets - from hundreds of terabytes to petabytes, across widely distributed scientific communities. The primary goal of the first phase of the EDG project was to assemble a distributed testbed to demonstrate that the EDG middleware components could be integrated into a production-quality computational Grid, as well as to gain experience with such a system. The very first version of the EDG testbed was deployed toward the end of 2001. At the first official European Union review of the project on March 1, 2002, it has been found that the project is on the right track to achieve its goals. Since then the EDG middleware, testbed components and procedures have been conti...

  15. UMTRA project office federal employee occupational safety and health program plan

    International Nuclear Information System (INIS)

    1994-06-01

    This document establishes the Federal Employee Occupational Safety and Health (FEOSH) Program for the US Department of Energy (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project Office. This program will ensure compliance with applicable requirements of DOE Order 3790.1B and DOE Albuquerque Operations Office (AL) Order 3790.lA. FEOSH Program responsibilities delegated by the DOE-AL to the UMTRA Project Office by AL Order 3790.1A also are assigned. The UMTRA Project Office has developed the UMTRA Project Environmental, Safety, and Health (ES ampersand H) Plan (DOE, 1992), which establishes the basic programmatic ES ampersand H requirements for all participants on the UMTRA Project. The ES ampersand H plan is designed primarily to cover remedial action activities at UMTRA sites and defines the ES ampersand H responsibilities of both the UMTRA Project Office and its contractors. The UMTRA FEOSH Program described herein is a subset of the overall UMTRA ES ampersand H program and covers only federal employees working on the UMTRA Project

  16. PROJECT CI-NERGY: TOWARDS AN INTEGRATED ENERGY URBAN PLANNING SYSTEM FROM A DATA MODELLING AND SYSTEM ARCHITECTURE PERSPECTIVE

    Directory of Open Access Journals (Sweden)

    G. Agugiaro

    2017-09-01

    Full Text Available Growing urbanisation, its related environmental impacts, and social inequalities in cities are challenges requiring a holistic urban planning perspective that takes into account the different aspects of sustainable development. One crucial point is to reconcile urban planning with environmental targets, which include decreasing energy demand and CO2 emissions, and increasing the share of renewable energy. Within this context, the project CI-NERGY aims to develop urban energy modelling, simulation and optimisation methods and tools to support decision making in urban planning. However, there are several barriers to the implementation of such tools, such as: fragmentation of involved disciplines, different stakeholders, multiplicity of scales in a city and extreme heterogeneity of data regarding all the processes to be addressed. Project CI-NERGY aims, among other goals, at overcoming these barriers, and focuses on two case study cities, Geneva in Switzerland and Vienna in Austria. In particular, project CI-NERGY faces several challenges starting with different cities, heterogeneous data sources and simulation tools, diverse user groups and their individual needs. This paper describes the experiences gathered during the project. After giving a brief overview of the project, the two case study cities, Geneva and Vienna, are briefly presented, and the focus shifts then on overall system architecture of the project, ranging from urban data modelling topics to the implementation of a Service-Oriented Architecture. Some of the challenges faced, the solutions found, as well some plans for future improvements are described and commented.

  17. Maintaining project consistency with transportation plans throughout the project life cycle with an emphasis on maintaining air quality conformity: technical report.

    Science.gov (United States)

    2016-07-01

    Federal and state transportation planning statutory and regulatory laws require transportation projects to be : consistent with transportation plans and improvement programs before a federal action can be taken on a : project requiring one. Significa...

  18. From Project Management to Process Management - Effectively Organising Transdisciplinary Projects

    OpenAIRE

    Moschitz, Heidrun

    2013-01-01

    In transdisciplinary projects, the roles of researchers change. In addition to being a source of knowledge, they are required to engage in knowledge exchange processes. This results in an alteration at project level: researchers need to creatively manage projects as group processes.

  19. Finance and supply management project execution plan; TOPICAL

    International Nuclear Information System (INIS)

    BENNION, S.I.

    1999-01-01

    As a subproject of the HANDI 2000 project, the Finance and Supply Management system is intended to serve FDH and Project Hanford major subcontractor with financial processes including general ledger, project costing, budgeting, and accounts payable, and supply management process including purchasing, inventory and contracts management. Currently these functions are performed with numerous legacy information systems and suboptimized processes

  20. System Safety Program Plan for Project W-314, tank farm restoration and safe operations

    International Nuclear Information System (INIS)

    Boos, K.A.

    1996-01-01

    This System Safety Program Plan (SSPP) outlines the safety analysis strategy for project W-314, ''Tank Farm Restoration and Safe Operations.'' Project W-314 will provide capital improvements to Hanford's existing Tank Farm facilities, with particular emphasis on infrastructure systems supporting safe operation of the double-shell activities related to the project's conceptual Design Phase, but is planned to be updated and maintained as a ''living document'' throughout the life of the project to reflect the current safety analysis planning for the Tank Farm Restoration and Safe Operations upgrades. This approved W-314 SSPP provides the basis for preparation/approval of all safety analysis documentation needed to support the project

  1. Project management for small business: a streamlined approach from planning to completion

    National Research Council Canada - National Science Library

    Phillips, Joseph

    2012-01-01

    ... a Project Management Plan 81 72 Developing the Work Breakdown Structure 85 76 Selecting Your Project Management Software 83 65 CHAPTER 4: MANAGING PROJECT COSTS Building a Cost Management Frame...

  2. Project management plan for the Isotopes Facilities Deactivation Project at Oak Ridge National Laboratory. Environmental Restoration Program

    International Nuclear Information System (INIS)

    1995-01-01

    The purpose of the Isotopes Facilities Deactivation Project (IFDP) is to place nineteen former isotopes production facilities at the Oak Ridge National Laboratory in a safe, stable, and environmentally sound condition suitable for an extended period of minimum surveillance and maintenance (S ampersand M) and as quickly and economically as possible. Implementation and completion of the deactivation project win further reduce the already small risks to the environment and to public safety and health. Furthermore, the project should result in significant S ampersand M cost savings in the future. The IFDP management plan has been prepared to document the project objectives, define organizational relationships and responsibilities, and outline the management control systems to be employed in the management of the project. The project has adopted a strategy to deactivate the simple facilities first, to reduce the scope of the project, and to gain experience before addressing more difficult facilities. A decision support system is being developed to identify those activities that best promote the project mission and result in largest cost savings. The Work Plan for the Isotopes Facilities Deactivation Project at Oak Ridge National Laboratory (Energy Systems 1994) defines the project schedule, the cost estimate, and the technical approach for the project

  3. Phased project planning and development in anticipation of operational programs

    Science.gov (United States)

    Stroud, W. G.

    1973-01-01

    The impact of future operational status on the planning and execution of the research and development activities for major space flight projects is assessed. These projects, within NASA, are part of the Applications Program involving communications and meteorology. The NASA management approach to these projects is determined by national policies governing the responsibilities and relationships among the various government agencies and private industries.

  4. Project Communication in Functions, Process and Project-Oriented Industiral Companies

    Science.gov (United States)

    Samáková, Jana; Koltnerová, Kristína; Rybanský, Rudolf

    2012-12-01

    The article is focused on the project communication management. Industrial enterprises, which use project management must constantly search the new ways for improving. One of the possibilities is the change of management from a functional oriented to the projectoriented or process-oriented. Process-oriented and project-oriented companies have better project communication management during the all project life cycle. Communication in the project is a very important factor. According to the arguments of several authors, one of the biggest problem is that threaten the success of the project is just the communication. In each project is an important pillar - and that is communication. Only on the base of communication can the project move forward and achieve the target.

  5. Fast Missile Boat Project Planning using CPM and What If Analysis Method

    Science.gov (United States)

    Silvianita; Firmansyah, R.; Rosyid, D. M.; Suntoyo; Chamelia, D. M.

    2018-03-01

    This paper discusses analysis of fast ship missile project planning with CPM and What If analysis.The poor performance can cause project delay and cost overruns, these two things often occur in a project management. Scheduling has an important role to control the project. Good scheduling is required because it will affect the product quality. Scheduling is useful to manage the activities so that the project completion time can be as short as possible and it is used to determine the costs of the project are in optimum condition. The alternatives that can be used to overcome the delay project namely increasing labor and equipment.Project planning can be done to determine whether the project is already in an optimum condition. Alternatives that can be used to overcome the delay in the project is to increase labor and equipment, the next is to look for the optimum solution taking into account the duration and gain of each alternative.

  6. Retail Tactical Planning: An Aligned Process?

    OpenAIRE

    Dreyer , Heidi; Dukovska-Popovska , Iskra; Kiil , Kasper; Kaipia , Riikka

    2016-01-01

    Part 9: Quality in Production Management; International audience; This paper addresses tactical planning in retailing through a case study approach in one grocery retailing company. The issues are how tactical planning is conducted and how the different plans are connected. The study complements earlier retail planning studies by showing the sequence of planning phases and by studying the fragmented plans as a process. The master category planning is important and sets borders for the other p...

  7. 23 CFR 450.208 - Coordination of planning process activities.

    Science.gov (United States)

    2010-04-01

    ... process. (h) The statewide transportation planning process should be consistent with the Strategic Highway... 23 Highways 1 2010-04-01 2010-04-01 false Coordination of planning process activities. 450.208... Coordination of planning process activities. (a) In carrying out the statewide transportation planning process...

  8. UMTRA project technical assistance contractor quality assurance implementation plan

    International Nuclear Information System (INIS)

    1994-03-01

    The Uranium Mill Tailings Remedial Action (UMTRA) Project Technical Assistance contractor (TAC) Quality Assurance Implementation Plan (QAIP) outlines the primary requirements for integrating quality functions for TAC technical activities applied to the surface and ground water phases of the UMTRA Project. The QAIP is subordinate to the latest issue of the UMTRA Project TAC Quality Assurance Program Plan (QAPP) (DOE, 1993a), which was developed using US Department of Energy (DOE) Order 5700.6C quality assurance (QA) criteria. The QAIP addresses technical aspects of the TAC UMTRA Project surface and ground water programs. All QA issues in the QAIP shall comply with requirements contained in the TAC QAPP (DOE, 1933a). Because industry standards for data acquisition and data control are not addressed in DOE Order 5700.6C, the QAIP has been formatted to the 14 US Environmental Protection Agency (EPA) Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) QA requirements. DOE Order 5700.6C criteria that are not contained in the CERCLA requirements are added to the QAIP as additional requirements in Sections 15.0 through 18.0. Project documents that contain CERCLA requirements and 5700.6 criteria shall be referenced in this document to avoid duplication. Referenced documents are not included in this QAIP but are available through the UMTRA Project Document Control Center

  9. Quality Assurance program plan - plutonium stabilization and handling project W-460

    International Nuclear Information System (INIS)

    SCHULTZ, J.W.

    1999-01-01

    This Quality Assurance Program Plan (QAPP) identifies Project Quality Assurance (QA) program requirements for all parties participating in the design, procurement, demolition, construction, installation, inspection and testing for Project W-460

  10. MO-B-BRB-00: Optimizing the Treatment Planning Process

    International Nuclear Information System (INIS)

    2015-01-01

    The radiotherapy treatment planning process has evolved over the years with innovations in treatment planning, treatment delivery and imaging systems. Treatment modality and simulation technologies are also rapidly improving and affecting the planning process. For example, Image-guided-radiation-therapy has been widely adopted for patient setup, leading to margin reduction and isocenter repositioning after simulation. Stereotactic Body radiation therapy (SBRT) and Radiosurgery (SRS) have gradually become the standard of care for many treatment sites, which demand a higher throughput for the treatment plans even if the number of treatments per day remains the same. Finally, simulation, planning and treatment are traditionally sequential events. However, with emerging adaptive radiotherapy, they are becoming more tightly intertwined, leading to iterative processes. Enhanced efficiency of planning is therefore becoming more critical and poses serious challenge to the treatment planning process; Lean Six Sigma approaches are being utilized increasingly to balance the competing needs for speed and quality. In this symposium we will discuss the treatment planning process and illustrate effective techniques for managing workflow. Topics will include: Planning techniques: (a) beam placement, (b) dose optimization, (c) plan evaluation (d) export to RVS. Planning workflow: (a) import images, (b) Image fusion, (c) contouring, (d) plan approval (e) plan check (f) chart check, (g) sequential and iterative process Influence of upstream and downstream operations: (a) simulation, (b) immobilization, (c) motion management, (d) QA, (e) IGRT, (f) Treatment delivery, (g) SBRT/SRS (h) adaptive planning Reduction of delay between planning steps with Lean systems due to (a) communication, (b) limited resource, (b) contour, (c) plan approval, (d) treatment. Optimizing planning processes: (a) contour validation (b) consistent planning protocol, (c) protocol/template sharing, (d) semi

  11. MO-B-BRB-00: Optimizing the Treatment Planning Process

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2015-06-15

    The radiotherapy treatment planning process has evolved over the years with innovations in treatment planning, treatment delivery and imaging systems. Treatment modality and simulation technologies are also rapidly improving and affecting the planning process. For example, Image-guided-radiation-therapy has been widely adopted for patient setup, leading to margin reduction and isocenter repositioning after simulation. Stereotactic Body radiation therapy (SBRT) and Radiosurgery (SRS) have gradually become the standard of care for many treatment sites, which demand a higher throughput for the treatment plans even if the number of treatments per day remains the same. Finally, simulation, planning and treatment are traditionally sequential events. However, with emerging adaptive radiotherapy, they are becoming more tightly intertwined, leading to iterative processes. Enhanced efficiency of planning is therefore becoming more critical and poses serious challenge to the treatment planning process; Lean Six Sigma approaches are being utilized increasingly to balance the competing needs for speed and quality. In this symposium we will discuss the treatment planning process and illustrate effective techniques for managing workflow. Topics will include: Planning techniques: (a) beam placement, (b) dose optimization, (c) plan evaluation (d) export to RVS. Planning workflow: (a) import images, (b) Image fusion, (c) contouring, (d) plan approval (e) plan check (f) chart check, (g) sequential and iterative process Influence of upstream and downstream operations: (a) simulation, (b) immobilization, (c) motion management, (d) QA, (e) IGRT, (f) Treatment delivery, (g) SBRT/SRS (h) adaptive planning Reduction of delay between planning steps with Lean systems due to (a) communication, (b) limited resource, (b) contour, (c) plan approval, (d) treatment. Optimizing planning processes: (a) contour validation (b) consistent planning protocol, (c) protocol/template sharing, (d) semi

  12. Improving energy audit process and report outcomes through planning initiatives

    Science.gov (United States)

    Sprau Coulter, Tabitha L.

    Energy audits and energy models are an important aspect of the retrofit design process, as they provide project teams with an opportunity to evaluate a facilities current building systems' and energy performance. The information collected during an energy audit is typically used to develop an energy model and an energy audit report that are both used to assist in making decisions about the design and implementation of energy conservation measures in a facility. The current lack of energy auditing standards results in a high degree of variability in energy audit outcomes depending on the individual performing the audit. The research presented is based on the conviction that performing an energy audit and producing a value adding energy model for retrofit buildings can benefit from a revised approach. The research was divided into four phases, with the initial three phases consisting of: 1.) process mapping activity - aimed at reducing variability in the energy auditing and energy modeling process. 2.) survey analysis -- To examine the misalignment between how industry members use the top energy modeling tools compared to their intended use as defined by software representatives. 3.) sensitivity analysis -- analysis of the affect key energy modeling inputs are having on energy modeling analysis results. The initial three phases helped define the need for an improved energy audit approach that better aligns data collection with facility owners' needs and priorities. The initial three phases also assisted in the development of a multi-criteria decision support tool that incorporates a House of Quality approach to guide a pre-audit planning activity. For the fourth and final research phase explored the impacts and evaluation methods of a pre-audit planning activity using two comparative energy audits as case studies. In each case, an energy audit professionals was asked to complete an audit using their traditional methods along with an audit which involved them first

  13. [Methodology for an appreciative, dynamic and collaborative process: 3rd Canary Islands (Spain) Health Plan].

    Science.gov (United States)

    O'Shanahan Juan, José Joaquín; Hernández Rodríguez, Miguel Ángel; Del Otero Sanz, Laura; Henríquez Suárez, José Andrés; Mahtani Chugani, Vinita

    The need for new approaches to strategic planning by incorporating the perspectives of professionals and inhabitants has led to a new model for the 3rd Canary Islands (Spain) Health Plan (IIIPSC). A dual-phase participatory process using qualitative techniques is proposed: 1) local phase: a quantitative and qualitative study based on training and a research-action-participation initiative; and 2) insular phase: health conferences with face-to-face discussion of results in each health area (island) and proposals for action. The process prioritises problems and establishes a specific action plan for each island through initiatives that are considered to be viable, grouped by themes and weighted according to the potential impact on priority problems. This process of interaction may help to guide planning model changes and health policy decision-making, and was included in the IIIPSC Project for its parliamentary procedure. Copyright © 2016 SESPAS. Publicado por Elsevier España, S.L.U. All rights reserved.

  14. Underground Test Area Quality Assurance Project Plan Nevada National Security Site, Nevada, Revision 0

    Energy Technology Data Exchange (ETDEWEB)

    Irene Farnham

    2011-05-01

    This Quality Assurance Project Plan (QAPP) provides the overall quality assurance (QA) program requirements and general quality practices to be applied to the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office (NNSA/NSO) Underground Test Area (UGTA) Sub-Project (hereafter the Sub-Project) activities. The requirements in this QAPP are consistent with DOE Order 414.1C, Quality Assurance (DOE, 2005); U.S. Environmental Protection Agency (EPA) Guidance for Quality Assurance Project Plans for Modeling (EPA, 2002); and EPA Guidance on the Development, Evaluation, and Application of Environmental Models (EPA, 2009). The QAPP Revision 0 supersedes DOE--341, Underground Test Area Quality Assurance Project Plan, Nevada Test Site, Nevada, Revision 4.

  15. Microbiological, Geochemical and Hydrologic Processes Controlling Uranium Mobility: An Integrated Field-Scale Subsurface Research Challenge Site at Rifle, Colorado, Quality Assurance Project Plan

    International Nuclear Information System (INIS)

    Fix, N. J.

    2008-01-01

    The U.S. Department of Energy (DOE) is cleaning up and/or monitoring large, dilute plumes contaminated by metals, such as uranium and chromium, whose mobility and solubility change with redox status. Field-scale experiments with acetate as the electron donor have stimulated metal-reducing bacteria to effectively remove uranium [U(VI)] from groundwater at the Uranium Mill Tailings Site in Rifle, Colorado. The Pacific Northwest National Laboratory and a multidisciplinary team of national laboratory and academic collaborators has embarked on a research proposed for the Rifle site, the object of which is to gain a comprehensive and mechanistic understanding of the microbial factors and associated geochemistry controlling uranium mobility so that DOE can confidently remediate uranium plumes as well as support stewardship of uranium-contaminated sites. This Quality Assurance Project Plan provides the quality assurance requirements and processes that will be followed by the Rifle Integrated Field-Scale Subsurface Research Challenge Project

  16. Microbiological, Geochemical and Hydrologic Processes Controlling Uranium Mobility: An Integrated Field-Scale Subsurface Research Challenge Site at Rifle, Colorado, Quality Assurance Project Plan

    Energy Technology Data Exchange (ETDEWEB)

    Fix, N. J.

    2008-01-07

    The U.S. Department of Energy (DOE) is cleaning up and/or monitoring large, dilute plumes contaminated by metals, such as uranium and chromium, whose mobility and solubility change with redox status. Field-scale experiments with acetate as the electron donor have stimulated metal-reducing bacteria to effectively remove uranium [U(VI)] from groundwater at the Uranium Mill Tailings Site in Rifle, Colorado. The Pacific Northwest National Laboratory and a multidisciplinary team of national laboratory and academic collaborators has embarked on a research proposed for the Rifle site, the object of which is to gain a comprehensive and mechanistic understanding of the microbial factors and associated geochemistry controlling uranium mobility so that DOE can confidently remediate uranium plumes as well as support stewardship of uranium-contaminated sites. This Quality Assurance Project Plan provides the quality assurance requirements and processes that will be followed by the Rifle Integrated Field-Scale Subsurface Research Challenge Project.

  17. Solid Waste Information and Tracking System Server Conversion Project Management Plan

    International Nuclear Information System (INIS)

    GLASSCOCK, J.A.

    2000-01-01

    The Project Management Plan governing the conversion of SWITS to a client-server architecture. The PMP describes the background, planning and management of the SWITS conversion. Requirements and specification documentation needed for the SWITS conversion

  18. UMTRA Project water sampling and analysis plan, Durango, Colorado. Revision 1

    International Nuclear Information System (INIS)

    1995-09-01

    Planned, routine ground water sampling activities at the US Department of Energy (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project site in Durango, Colorado, are described in this water sampling and analysis plan. The plan identifies and justifies the sampling locations, analytical parameters, detection limits, and sampling frequency for the routine monitoring stations at the site. The ground water data are used to characterize the site ground water compliance strategies and to monitor contaminants of potential concern identified in the baseline risk assessment (DOE, 1995a). Regulatory basis for routine ground water monitoring at UMTRA Project sites is derived from the US EPA regulations in 40 CFR Part 192 (1994) and EPA standards of 1995 (60 FR 2854). Sampling procedures are guided by the UMTRA Project standard operating procedures (SOP) (JEG, n.d.), the Technical Approach Document (TAD) (DOE, 1989), and the most effective technical approach for the site

  19. Nuclear criticality project plan for the Hanford Site tank farms

    Energy Technology Data Exchange (ETDEWEB)

    Bratzel, D.R., Westinghouse Hanford

    1996-08-06

    The mission of this project is to provide a defensible technical basis report in support of the Final Safety Analysis Report (FSAR). This technical basis report will also be used to resolve technical issues associated with the nuclear criticality safety issue. The strategy presented in this project plan includes an integrated programmatic and organizational approach. The scope of this project plan includes the provision of a criticality technical basis supporting document (CTBSD) to support the FSAR as well as for resolution of the nuclear criticality safety issue. Specifically, the CTBSD provides the requisite technical analysis to support the FSAR hazard and accident analysis as well as for the determination of the required FSAR limits and controls. The scope of The CTBSD will provide a baseline for understanding waste partitioning and distribution phenomena and mechanistics for current operational activities inclusive of single-shell tanks, double-shell tanks, double-contained receiver tanks, and miscellaneous underground storage tanks.. Although the FSAR does not include future operational activities, the waste partitioning and distribution phenomena and mechanistics work scope identified in this project plan provide a sound technical basis as a point of departure to support independent safety analyses for future activities. The CTBSD also provides the technical basis for resolution of the technical issues associated with the nuclear criticality safety issue. In addition to the CTBSD, additional documentation will be required to fully resolve U.S. Department of Energy-Headquarters administrative and programmatic issues. The strategy and activities defined in this project plan provide a CTBSD for the FSAR and for accelerated resolution of the safety issue in FY 1996. On April 30, 1992, a plant review committee reviewed the Final Safety Analysis Reports for the single-shell, double-shell, and aging waste tanks in light of the conclusions of the inadequate waste

  20. European DataGrid project: status and plans

    International Nuclear Information System (INIS)

    Kunszt, P.

    2003-01-01

    The European DataGrid (EDG) project has reached, after 1.5 years, the middle of its lifetime. In this article we give an overview of the status, components, procedures and plans of the EDG project as of June 2002. The objective of the EDG project is to assist the next generation of scientific exploration, computation and analysis of large-scale data sets--from hundreds of terabytes to petabytes, across widely distributed scientific communities. The primary goal of the first phase of the EDG project was to assemble a distributed testbed to demonstrate that the EDG middleware components could be integrated into a production-quality computational Grid, as well as to gain experience with such a system. The very first version of the EDG testbed was deployed toward the end of 2001. At the first official European Union review of the project on March 1, 2002, it has been found that the project is on the right track to achieve its goals. Since then the EDG middleware, testbed components and procedures have been continuously refined according to the requirements of our user communities and our experience

  1. New model of enterprises resource planning implementation planning process in manufacturing enterprises

    Directory of Open Access Journals (Sweden)

    Mirjana Misita

    2016-05-01

    Full Text Available This article presents new model of enterprises resource planning implementation planning process in manufacturing enterprises based on assessment of risk sources. This assessment was performed by applying analytic hierarchy process. Analytic hierarchy process method allows variation of relative importance of specific risk sources dependent on the section from which the risk source originates (organizational environment, technical issues, people issues, adoption process management, and external support. Survey was conducted on 85 manufacturing enterprises involved with an enterprises resource planning solution. Ranking of risk sources assessments returns most frequent risks of enterprises resource planning implementation success in manufacturing enterprises, and representative factors were isolated through factor analysis by risk source origin. Finally, results indicate that there are hidden causes of failed implementation, for example, risk source “top management training and education,” from risk origin “adoption process management.”

  2. Uranium Mill Tailings Remedial Action Project Environmental Protection Implementation Plan

    International Nuclear Information System (INIS)

    Vollmer, A.T.

    1993-10-01

    The Uranium Mill Tailings Remedial Action (UMTRA) Project Environmental Protection Implementation Plan (EPIP) has been prepared in accordance with the requirements of the US Department of Energy (DOE) Order 5400.1. The UMTRA EPIP covers the time period of November 9, 1993, through November 8, 1994. It will be updated annually. Its purpose is to provide management direction to ensure that the UMTRA Project is operated and managed in a manner that will protect, maintain, and where necessary, restore environmental quality, minimize potential threats to public health and the environment, and comply with environmental regulations and DOE policies. Contents of this report are: (1) general description of the UMTRA project environmental protection program; (2) notifications; (3) planning and reporting; (4) special programs; (5) environmental monitoring programs; (6) quality assurance and data verification; and (7) references

  3. Uranium Mill Tailings Remedial Action Project Environmental Protection Implementation Plan

    Energy Technology Data Exchange (ETDEWEB)

    Vollmer, A.T.

    1993-10-01

    The Uranium Mill Tailings Remedial Action (UMTRA) Project Environmental Protection Implementation Plan (EPIP) has been prepared in accordance with the requirements of the US Department of Energy (DOE) Order 5400.1. The UMTRA EPIP covers the time period of November 9, 1993, through November 8, 1994. It will be updated annually. Its purpose is to provide management direction to ensure that the UMTRA Project is operated and managed in a manner that will protect, maintain, and where necessary, restore environmental quality, minimize potential threats to public health and the environment, and comply with environmental regulations and DOE policies. Contents of this report are: (1) general description of the UMTRA project environmental protection program; (2) notifications; (3) planning and reporting; (4) special programs; (5) environmental monitoring programs; (6) quality assurance and data verification; and (7) references.

  4. Climate Action Planning Process | Climate Neutral Research Campuses | NREL

    Science.gov (United States)

    Action Planning Process Climate Action Planning Process For research campuses, NREL has developed a five-step process to develop and implement climate action plans: Determine baseline energy consumption Analyze technology options Prepare a plan and set priorities Implement the climate action plan Measure and

  5. Gas generation matrix depletion quality assurance project plan

    International Nuclear Information System (INIS)

    1998-01-01

    The Los Alamos National Laboratory (LANL) is to provide the necessary expertise, experience, equipment and instrumentation, and management structure to: Conduct the matrix depletion experiments using simulated waste for quantifying matrix depletion effects; and Conduct experiments on 60 cylinders containing simulated TRU waste to determine the effects of matrix depletion on gas generation for transportation. All work for the Gas Generation Matrix Depletion (GGMD) experiment is performed according to the quality objectives established in the test plan and under this Quality Assurance Project Plan (QAPjP)

  6. Applying Multi-Criteria Decision Aiding Techniques in the Process of Project Management within the Wedding Planning Business

    Directory of Open Access Journals (Sweden)

    Dorota Górecka

    2012-01-01

    Full Text Available Numerous problems that emerge in the process of project management can be presented as multi-criteria issues and solved with the help of appropriate methods. The contracting authority, selecting one tender out of many available tenders, assesses them, taking into account various criteria, e.g. price, expected execution time and the contractor's experience. The owner of a company intending to purchase the fixed assets requisite for the realization of the project behaves similarly, i.e. the most advantageous model of the device is chosen, taking into account not only its price but also production capacity, energy intensity, noise emission, service availability, etc. From among many concepts, the investor has to choose a solution which frequently constitutes a compromise between price, functional properties, durability and aesthetics of performance, as well as safety of the utilization and impact on the environment. The choice of an investment location depends not only on the market, financial and supply factors, but also on so called soft factors such as the perceived quality of institutions and the attitude of local communities. All such situations can be described in the same way: taking into account preferences of the decision maker, the best possible choice must be made out of a finite set of alternatives evaluated according to a finite set of criteria. There are many different methods that can be used to aid a decision maker in this choice, including, but not limited to, techniques based on the outranking relation, verbal decision analysis and the MACBETH method. In this article, they will be compared and their applicability to different types of decision making problems will be considered. Furthermore, the PROMETHEE II method with a veto threshold will be presented within the text. Because the application of project management in the wedding planning business has gained wide popularity, as an illustrative example an empirical study of

  7. Project W-314 specific test and evaluation plan 241-AN-B valve pit

    International Nuclear Information System (INIS)

    Hays, W.H.

    1998-01-01

    The purpose of this Specific Test and Evaluation Plan (STEP) is to provide a detailed written plan for the systematic testing of modifications made to the 241-AN-B Valve Pit by the W-314 Project. The STEP develops the outline for test procedures that verify the system's performance to the established Project design criteria. The STEP is a lower tier document based on the W-314 Test and Evaluation Plan (TEP)

  8. Nevada Nuclear Waste Storage Investigations. FY 1979 project plan

    International Nuclear Information System (INIS)

    1979-03-01

    This document presents the management and cost for the Nevada Nuclear Waste Storage Investigations (disposal of high-level wastes at Nevada Test Site) and provides a complete description of the overall project, management structure, technical approach, and work breakdown structure. The document is organized into five major sections. Section I summarizes the history of the project and indicates a potential future course of action. FY 1979 project work is briefly described in Section II. Section III outlines the delegated responsibilities of all project management functions. A list of critical questions that guide the technical approach of the project are presented in Section IV. Section V contains subtask work plans which outline the work in detail for this fiscal year

  9. Tank 241-C-106 waste retrieval sluicing system process control plan

    Energy Technology Data Exchange (ETDEWEB)

    Carothers, K.G.

    1998-07-25

    Project W-320 has installed the Waste Retrieval Sluicing System at the 200 East Area on the Hanford Site to retrieve the sludge from single-shell tank 241-C-106 and transfer it into double-shell tank 241-AY-102. Operation of the WRSS process will resolve the high-heat safety issue for tank 241-C-106 and demonstrate a technology for the retrieval of single-shell tank wastes. This process control plan coordinates the technical operating requirements (primarily mass transfer, temperature, and flammable gas) for the sluicing operation and provides overall technical guidance for the retrieval activity.

  10. Tank 241-C-106 waste retrieval sluicing system process control plan

    International Nuclear Information System (INIS)

    Carothers, K.G.

    1998-01-01

    Project W-320 has installed the Waste Retrieval Sluicing System at the 200 East Area on the Hanford Site to retrieve the sludge from single-shell tank 241-C-106 and transfer it into double-shell tank 241-AY-102. Operation of the WRSS process will resolve the high-heat safety issue for tank 241-C-106 and demonstrate a technology for the retrieval of single-shell tank wastes. This process control plan coordinates the technical operating requirements (primarily mass transfer, temperature, and flammable gas) for the sluicing operation and provides overall technical guidance for the retrieval activity

  11. Manual heat pumps. Planning and projecting; Handbuch Waermepumpen. Planung und Projektierung

    Energy Technology Data Exchange (ETDEWEB)

    Bonin, Juergen

    2009-07-01

    The special value of this publication for planning and projecting of heat pump devices lays in an information processing independent of manufacturers: specialists of civil engineering receive so a fact source to compare as much as possible systems and possibilities. Furthermore renewable energy sources to change heating systems are presented - which is from advantage during times of high energy cost. Main topics on overview: ecological and economical aspects, introduction in refrigerating engineering, water-water heat pump devices, brake-water- and air-water heat pump devices, projecting of all required components as well as projecting examples (tasks and solutions). (orig./GL) [German] Der besondere Wert dieser Publikation zur Planung und Projektierung von Waermepumpenanlagen liegt in einer markenneutral gehaltenen Informationsaufbereitung: Fachkraefte der Baubranche erhalten so eine Faktenquelle zum Vergleichen moeglichst vieler Systeme und Moeglichkeiten. Zudem werden alternative Energiequellen zur Heizungsumstellung vorgestellt - was gerade in Zeiten hoher Energiekosten von grossem Vorteil ist. Schwerpunkte im Ueberblick: Oekologische und wirtschaftliche Aspekte, Einfuehrung in die Kaeltetechnik, Wasser-Wasser-Waermepumpenanlagen, Sole-Wasser-Waermepumpenanlagen, Luft-Wasser-Waermepumpenanlagen, Projektierung aller erforderlichen Komponenten sowie Projektierungsbeispiele (Aufgaben und Loesungen). (orig.)

  12. The Course Development Plan: Macro-Level Decisions and Micro-Level Processes

    Science.gov (United States)

    Franker, Karen; James, Dennis

    2016-01-01

    A key step in distance learning project management is the creation of a course development plan. The plan should account for decisions related to materials, curriculum, delivery methods, staffing, technology applications, resources, reporting lines, and project management--issues that may require administrator involvement and support, particularly…

  13. Fuels planning: science synthesis and integration; fact sheet: The Fuels Synthesis Project overview

    Science.gov (United States)

    Rocky Mountain Research Station USDA Forest Service

    2004-01-01

    The geographic focus of the "Fuels Planning: Science Synthesis and Integration" project #known as the Fuels Synthesis Project# is on the dry forests of the Western United States. Target audiences include fuels management specialists, resource specialists, National Environmental Policy Act #NEPA# planning team leaders, line officers in the USDA Forest Service...

  14. Public affairs plan

    Energy Technology Data Exchange (ETDEWEB)

    1994-09-01

    The purpose of the Uranium Mill Tailings Remedial Action (UMTRA) Project Public Affairs Plan is to establish goals for the Fiscal Year 1995 UMTRA public affairs program and identify specific activities to be conducted during the year. It also describes the roles of various agencies involved in the conduct of the public affairs program and defines the functions of the Technical Assistance Contractor (TAC) Public Affairs Department. It integrates and replaces the Public Participation Plan (DOE/AL/62350-47D) and Public Information Plan (DOE/AL/623590-71). The plan describes the US Department of Energy`s (DOE) plans to keep stakeholders and other members of the public informed about project policies, plans, and activities, and provide opportunities for stakeholders and interested segments of the public to participate in project decision-making processes. The plan applies to the UMTRA Project Office; the DOE Albuquerque Operations Office, Office of Intergovernmental and External Affairs (OIEA); the UMTRA TAC; the UMTRA Remedial Action Contractor (RAC); and other cooperating agencies.

  15. Public affairs plan

    International Nuclear Information System (INIS)

    1994-09-01

    The purpose of the Uranium Mill Tailings Remedial Action (UMTRA) Project Public Affairs Plan is to establish goals for the Fiscal Year 1995 UMTRA public affairs program and identify specific activities to be conducted during the year. It also describes the roles of various agencies involved in the conduct of the public affairs program and defines the functions of the Technical Assistance Contractor (TAC) Public Affairs Department. It integrates and replaces the Public Participation Plan (DOE/AL/62350-47D) and Public Information Plan (DOE/AL/623590-71). The plan describes the US Department of Energy's (DOE) plans to keep stakeholders and other members of the public informed about project policies, plans, and activities, and provide opportunities for stakeholders and interested segments of the public to participate in project decision-making processes. The plan applies to the UMTRA Project Office; the DOE Albuquerque Operations Office, Office of Intergovernmental and External Affairs (OIEA); the UMTRA TAC; the UMTRA Remedial Action Contractor (RAC); and other cooperating agencies

  16. Near-Facility Environmental Monitoring Quality Assurance Project Plan

    International Nuclear Information System (INIS)

    MCKINNEY, S.M.

    2000-01-01

    This Quality Assurance Project Plan addresses the quality assurance requirements for the activities associated with the preoperational and near-facility environmental monitoring directed by Waste Management Technical Services and supersedes HNF-EP-0538-4. This plan applies to all sampling and monitoring activities performed by Waste Management Technical Services in implementing near-facility environmental monitoring at the Hanford Site. This Quality Assurance Project Plan is required by U.S. Department of Energy Order 5400.1 (DOE 1990) as a part of the Environmental Monitoring Plan (DOE-RL 1997) and is used to define: Environmental measurement and sampling locations used to monitor environmental contaminants near active and inactive facilities and waste storage and disposal sites; Procedures and equipment needed to perform the measurement and sampling; Frequency and analyses required for each measurement and sampling location; Minimum detection level and accuracy; Quality assurance components; and Investigation levels. Near-facility environmental monitoring for the Hanford Site is conducted in accordance with the requirements of U.S. Department of Energy Orders 5400.1 (DOE 1990), 5400.5 (DOE 1993), 5484.1 (DOE 1990), and 435.1 (DOE 1999), and DOE/EH-O173T (DOE 1991). It is Waste Management Technical Services' objective to manage and conduct near-facility environmental monitoring activities at the Hanford Site in a cost-effective and environmentally responsible manner that is in compliance with the letter and spirit of these regulations and other environmental regulations, statutes, and standards

  17. 49 CFR 611.7 - Relation to planning and project development processes.

    Science.gov (United States)

    2010-10-01

    ...) FEDERAL TRANSIT ADMINISTRATION, DEPARTMENT OF TRANSPORTATION MAJOR CAPITAL INVESTMENT PROJECTS § 611.7... with 23 CFR part 450. To be eligible for FTA capital investment funding, a proposed project must be...) To be eligible for FTA capital investment funding for a major fixed guideway transit project, local...

  18. MEET : project action plan for AUMA energy management program

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2002-11-22

    The Municipal Energy Efficiency Trust (MEET) action plan offers a framework to help municipalities in Alberta demonstrate leadership in reducing energy consumption. It sets out targets for energy reductions and the associated capital investment. As more information is compiled from energy audits, the targets will be refined. AUMA and Enmax Energy Corp have partnered to provide energy audits designed to allow all municipalities to undertake energy savings projects. The program is divided into 8 basic categories for energy savings projects including: water and sewage collection, treatment and distribution; recreation centres such as pools and skating rinks; streetlights; office buildings; garages, shops and parking lots; other and innovative projects; municipal audit evaluation support; and, direct grants applied to each project. The estimates for energy savings within each category are provided. The maximum allowable payback period for the project is assumed to be 15 years. Total municipal energy use in Alberta is estimated at 1,100,000 MWh per year. A province wide program will enable AUMA to provide centralized services such as project management and procurement services to address municipal resource constraints and provide some economies of scale for smaller municipalities. AUMA will act as the fund administrator and will set criteria for acceptable projects. The action plan focuses on the energy audit program, municipal facility data collection, municipal staff education, and the establishment of a funding pool. The target for 2002/2003 will be to identify projects with energy savings of at least 15,000 MWh for water treatment and distribution recreation centres for a total capital cost of $13,500,000. 1 tab., 3 figs.

  19. A model for effective intergovernmental planning

    International Nuclear Information System (INIS)

    Moore, R.C.

    1991-01-01

    Effective intergovernmental planning processes are essential to the resolution of potential affects created by federal projects. Intergovernmental planning for the proposed Yucca Mountain High-level Nuclear Waste Repository has not been effective to date. In this paper, two successful planning efforts are described. The common elements of these processes are analyzed to provide a model that can be used for the resolution of impacts from other projects. Management authorities of the entities involved should establish a working group to conduct the intergovernmental planning. The parties must identify issues that can be resolved through intergovernmental planning. Clear management authority and direction to the staff participating the planning process is essential. Issues which cannot be resolved should not be included in the goals of the working group. Funding to support the planning process is essential

  20. Prioritising Project Scope Definition Elements in Public Building Projects

    Directory of Open Access Journals (Sweden)

    Mohammed K Fageha

    2014-09-01

    Full Text Available A complete definition of the scope of a project upfront during early stages ensures smooth and successful implementation during the project execution. This research identifies and prioritises project scope definition elements for public buildings in Saudi Arabia. Elements that could significantly contribute to complete project scope definition package at pre-project planning stage are identified and their interrelationship determined and prioritised. Using the Project Definition Rating Index (PDRI as a basis, the study uses analytical network process (ANP technique based on data obtained from project managers who have been involved in public sector projects in Saudi Arabia. Data collection and analysis was conducted in three steps. The first step involved identification of scope definition elements while the second involved an investigation into interrelationships among the elements. In the third step, ANP was used to determine the weight of the elements’ importance in terms of contribution to project scope definition completeness. Finally, Pareto analysis was used to prioritise and assess the distribution pattern of the elements. The outcome from this research is the prioritisation of project scope definition elements for public building projects in Saudi Arabia. The prioritised list developed indicates the importance of project scope definition elements. It should help project management teams identify elements to consider when evaluating project scope definition for completeness at the pre-project planning stage. Keywords: Project scope definition, pre-project planning, prioritising, public building projects, Saudi Arabia, Analytical Network Process (ANP

  1. Public Information Plan

    International Nuclear Information System (INIS)

    1984-06-01

    The Public Information Plan is intended to be used in conjunction with the DOE-UMTRA Project ''Public Participation Plan'' to describe the Department of Energy's plan for involving the public in the decision-making process related to the Uranium Mill Tailings Remedial Action (UMTRA) Project. This project was authorized by Congress in the Uranium Mill Tailings Radiation Control of Act of 1978, PL95-604. The Act provides for a cooperative effort with affected states and Indian tribes for the cleanup of designated abandoned or inactive uranium mill tailings sites. The objective of the Public Information Plan of the UMTRA Project is timely and sufficient dissemination of factual information to promote understanding of the project by federal, state, and local officials, the media, special interest groups, and the general public; and thereby to encourage informed participation in the project by the public and government officials. The Uranium Mill Tailings Radiation Control Act provides for public involvement in remedial action planning, with special consideration given to landowners, Indian tribes, and the states. According to the Act, the Secretary of Energy shall hold public hearings in the states where processing sites, vicinity properties, and disposal sites are located. Public participation in the UMTRA Project will not, however, be limited to those mechanisms formally required by law. The public may also be involved informally through informational meetings, workshops, and local citizens' task forces. 12 refs., 2 figs., 1 tab

  2. Planning of modern process control systems in processing engineering and power plant engineering. Planung von modernen Prozessleitsystemen in der Verfahrens- und Kraftwerkstechnik

    Energy Technology Data Exchange (ETDEWEB)

    Gilson, W

    1985-01-01

    Correct planning of up-to-date process control systems results in considerable process automation and rationalization. These systems are used in process engineering, in production plants of the chemical industries and in power stations to a growing extent and rapidly reveal their advantages in terms of increased efficiency, improved product quality and reduced maintenance. However, this necessitates to make full and consistent use of the systems' qualities. Lack of experience often result in flows and errors in planning. The VDE und VDI district associations, Frankfurt, selected this subject for this year's discussion in the working group in February/March 1985 in order to provide a comprehensive coverage and demonstration of the field concerned. Experts and interested persons are given information on what facts will have to be observed during all stages in the planning of up-to-date process control systems. The book deals with the following subjects: From the process involved to the structure of the control system; - system specification and system selection; - configuration and project-accompagnying documentation; - trends and prospects exemplified by recent developments.

  3. Rainwater Wildlife Area Management Plan Executive Summary : A Columbia Basin Wildlife Mitigation Project.

    Energy Technology Data Exchange (ETDEWEB)

    Childs, Allen B.

    2002-02-01

    This Executive Summary provides an overview of the Draft Rainwater Wildlife Area Management Plan. The comprehensive plan can be viewed on the Confederated Tribes of the Umatilla Indian Reservation (CTUIR) website at: www.umatilla.nsn.us or requested in hard copy from the CTUIR at the address below. The wildlife area was established in September 1998 when the CTUIR purchased the Rainwater Ranch through Bonneville Power Administration (BPA) for purposes of fish and wildlife mitigation for the McNary and John Day dams. The Management Plan has been developed under a standardized planning process developed by BPA for Columbia River Basin Wildlife Mitigation Projects (See Guiding Policies Section below). The plan outlines the framework for managing the project area, provides an assessment of existing conditions and key resource issues, and presents an array of habitat management and enhancement strategies. The plan culminates into a 5-Year Action Plan that will focus management actions and prioritize funding during the 2002-2006 planning period. Since acquisition of the property in late 1998, the CTUIR has conducted an extensive baseline resource assessment in preparation for the management plan, initiated habitat restoration in the Griffin Fork drainage to address road-related resource damage caused by roads constructed for forest practices and an extensive flood event in 1996, and initiated infrastructure developments associated with the Access and Travel Management Plan (i.e., installed parking areas, gates, and public information signs). In addition to these efforts, the CTUIR has worked to set up a long-term funding mechanism with BPA through the NPPC Fish and Wildlife Program. The CTUIR has also continued to coordinate closely with local and state government organizations to ensure consistency with local land use laws and maintain open lines of communication regarding important issues such as big game hunting, tribal member exercise of treaty rights, and public

  4. Project planning and management techniques of the fast-paced TMX-Upgrade construction

    International Nuclear Information System (INIS)

    Seberger, C.D.; Chargin, A.K.

    1981-01-01

    The Tandem Mirror Experiment-Upgrade (TMX-Upgrade) construction will be completed in 18 months at a total cost of $14.5 million. This paper describes the project planning and the management techniques used to complete the TMX-Upgrade within its allocated cost and schedule. In the planning stages of a project, before approval of the proposal, we define major project objectives, create a work breakdown structure (WBS), detail a technical description for each level of the WBS, and provide detailed bottoms-up cost estimates and summary schedules. In the operating phase, which continues throughout the project, we establish budget and schedule baselines. The reporting phase includes The Department of Energy (DOE) reviews of project status at monthly, quarterly, and semiannual intervals. These reports include cost, schedule, manpower, major procurement, and technical status information

  5. Contingency plan for the Old Hydrofracture Facility Tanks Sluicing Project at Oak Ridge National Laboratory, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1998-06-01

    This revised contingency plan addresses potential scenarios involving the release of radioactively contaminated waste from the Old Hydrofracture Facility Tanks Contents Removal project to the environment. The tanks are located at the Oak Ridge National Laboratory. The project involves sluicing the contents of the five underground tanks to mix the sludge and supernatant layers, and pumping the mixture to the Melton Valley Storage Tanks (MVST) for future processing. The sluicing system to be used for the project consists of a spray nozzle designated the open-quotes Borehole Miner,close quotes with an associated pump; in-tank submersible pumps to transfer tank contents from the sluice tanks to the recycle tank; high-pressure pumps providing slurry circulation and slurry transport to the MVST; piping; a ventilation system; a process water system; an instrumentation and control system centered around a programmable logic controller; a video monitoring system; and auxiliary equipment. The earlier version of this plan, which was developed during the preliminary design phase of the project, identified eight scenarios in which waste from the tanks might be released to the environment as a result of unanticipated equipment failure or an accident (e.g., vehicular accident). One of those scenarios, nuclear criticality, is no longer addressed by this plan because the tank waste will be isotopically diluted before sluicing begins. The other seven scenarios have been combined into three, and a fourth, Borehole Miner Failure, has been added as follows: (1) underground release from the tanks; (2) aboveground release or spill from the sluicing system, a tank riser, or the transfer pipeline; (3) release of unfiltered air through the ventilation system; and (4) Borehole Miner arm retraction failure. Methods for preventing, detecting, and responding to each release scenario are set out in the plan

  6. Yucca Mountain Site Characterization Project Waste Package Plan

    International Nuclear Information System (INIS)

    Harrison-Giesler, D.J.; Jardine, L.J.

    1991-02-01

    The goal of the US Department of Energy's (DOE) Yucca Mountain Site Characterization Project (YMP) waste package program is to develop, confirm the effectiveness of, and document a design for a waste package and associated engineered barrier system (EBS) for spent nuclear fuel and solidified high-level nuclear waste (HLW) that meets the applicable regulatory requirements for a geologic repository. The Waste Package Plan describes the waste package program and establishes the technical approach against which overall progress can be measured. It provides guidance for execution and describes the essential elements of the program, including the objectives, technical plan, and management approach. The plan covers the time period up to the submission of a repository license application to the US Nuclear Regulatory Commission (NRC). 1 fig

  7. PROJECT PLANNING AND CONTROLLING GEDUNG RUSUNAWA UNIVERSITAS INDONESIA DENGAN MS.PROJECT

    Directory of Open Access Journals (Sweden)

    Sanny Stephanie

    2016-09-01

    Full Text Available Suatu proyek konstruksi selalu dimulai dengan proses perencanaan proyek (Project planning hingga pengendalian proyek (Project controlling Apabila terjadi perencanaan yang tidak matang dan pengendalian proyek yang kurang efektif, maka akan mengakibatkan penyimpangan dalam proyek tersebut seperti proyek selesai lebih cepat ataupun keterlambatan proyek.. Penelitian ini bertujuan untuk menganalisis perencanaan dan pengendalian proyek gedung Rusunawa Universitas Indonesia (asrama UI Jakarta Selatan dengan menggunakan bantuan program Microsoft Project. Berdasarkan kontrak, proyek ini dimulai pada tanggal 4 Desember 2014 s/d 10 Juli 2015. Dilihat dari hasil analisa kurva S Rencana dan kurva S aktual sampai dengan tanggal 31 Mei 2015, kurva S Aktual berada dibawah kurva S Rencana, dimana pada minggu ke-9 s/d minggu ke -35 proyek mengalami keterlambatan sebesar 18%, yaitu terlambat 10 hari dari rencana. Namun, dengan dilakukannya percepatan jadwal pada proyek ini dengan memperpendek durasi dan menambah tenaga kerja, maka penyelesaian proyek Rusunawa UI Jakarta Selatan ini masih dapat diselesaikan tepat waktu dan sesuai dengan jadwal yang telah ditentukan.

  8. 77 FR 33240 - Central Valley Project Improvement Act, Water Management Plans

    Science.gov (United States)

    2012-06-05

    ... Project water conservation best management practices that shall ``develop criteria for evaluating the... DEPARTMENT OF THE INTERIOR Bureau of Reclamation Central Valley Project Improvement Act, Water Management Plans AGENCY: Bureau of Reclamation, Interior. ACTION: Notice of availability. SUMMARY: The...

  9. 75 FR 70020 - Central Valley Project Improvement Act, Water Management Plans

    Science.gov (United States)

    2010-11-16

    ... office on Central Valley Project water conservation best management practices that shall ``* * * develop... DEPARTMENT OF THE INTERIOR Bureau of Reclamation Central Valley Project Improvement Act, Water Management Plans AGENCY: Bureau of Reclamation, Interior ACTION: Notice of Availability. SUMMARY: The...

  10. 76 FR 12756 - Central Valley Project Improvement Act, Water Management Plans

    Science.gov (United States)

    2011-03-08

    ... office on Central Valley Project water conservation best management practices that shall ``* * * develop... DEPARTMENT OF THE INTERIOR Bureau of Reclamation Central Valley Project Improvement Act, Water Management Plans AGENCY: Bureau of Reclamation, Interior. ACTION: Notice of availability. SUMMARY: The...

  11. 77 FR 64544 - Central Valley Project Improvement Act, Water Management Plans

    Science.gov (United States)

    2012-10-22

    ... Central Valley Project water conservation best management practices that shall ``develop criteria for... DEPARTMENT OF THE INTERIOR Bureau of Reclamation Central Valley Project Improvement Act, Water Management Plans AGENCY: Bureau of Reclamation, Interior. ACTION: Notice of availability. SUMMARY: The...

  12. Managing environmental enhancement plans for individual research projects at a national primate research center.

    Science.gov (United States)

    Thom, Jinhee P; Crockett, Carolyn M

    2008-05-01

    We describe a method for managing environmental enhancement plans for individual research projects at a national primate research center where most monkeys are assigned to active research projects. The Psychological Well-being Program (PWB) at the University of Washington National Primate Research Center developed an Environmental Enhancement Plan form (EEPL) that allows PWB to quantify and track changes in enrichment allowances over time while ensuring that each animal is provided with as much enrichment as possible without compromising research. Very few projects involve restrictions on toys or perches. Some projects have restrictions on food treats and foraging, primarily involving the provision of these enrichments by research staff instead of husbandry staff. Restrictions are not considered exemptions unless they entirely prohibit an element of the University of Washington Environmental Enhancement Plan (UW EE Plan). All exemptions must be formally reviewed and approved by the institutional animal care and use committee. Most exemptions from elements of the UW EE Plan involve social housing. Between 2004 and 2006, the percentage of projects with no social contact restrictions increased by 1%, but those prohibiting any tactile social contact declined by 7%, and projects permitting tactile social contact during part of the study increased by 9%. The EEPL form has facilitated informing investigators about the enrichment their monkeys will receive if no restrictions or exemptions are requested and approved. The EEPL form also greatly enhances PWB's ability to coordinate the specific enrichment requirements of a project.

  13. Columbia River Channel Improvement Project Rock Removal Blasting: Monitoring Plan

    Energy Technology Data Exchange (ETDEWEB)

    Carlson, Thomas J.; Johnson, Gary E.

    2010-01-29

    This document provides a monitoring plan to evaluate take as outlined in the National Marine Fisheries Service 2002 Biological Opinion for underwater blasting to remove rock from the navigation channel for the Columbia River Channel Improvement Project. The plan was prepared by the Pacific Northwest National Laboratory (PNNL) for the U.S. Army Corps of Engineers (USACE), Portland District.

  14. Information management in process planning

    NARCIS (Netherlands)

    Lutters, Diederick; Wijnker, T.C.; Kals, H.J.J.

    1999-01-01

    A recently proposed reference model indicates the use of structured information as the basis for the control of design and manufacturing processes. The model is used as a basis to describe the integration of design and process planning. A differentiation is made between macro- and micro process

  15. The space shuttle payload planning working groups: Volume 9: Materials processing and space manufacturing

    Science.gov (United States)

    1973-01-01

    The findings and recommendations of the Materials Processing and Space Manufacturing group of the space shuttle payload planning activity are presented. The effects of weightlessness on the levitation processes, mixture stability, and control over heat and mass transport in fluids are considered for investigation. The research and development projects include: (1) metallurgical processes, (2) electronic materials, (3) biological applications, and (4)nonmetallic materials and processes. Additional recommendations are provided concerning the allocation of payload space, acceptance of experiments for flight, flight qualification, and private use of the space shuttle.

  16. 76 FR 54251 - Central Valley Project Improvement Act, Water Management Plans

    Science.gov (United States)

    2011-08-31

    ... and administer an office on Central Valley Project water conservation best management practices that... DEPARTMENT OF THE INTERIOR Bureau of Reclamation Central Valley Project Improvement Act, Water Management Plans AGENCY: Bureau of Reclamation, Interior. ACTION: Notice of availability. SUMMARY: The...

  17. 75 FR 38538 - Central Valley Project Improvement Act, Water Management Plans

    Science.gov (United States)

    2010-07-02

    ... to establish and administer an office on Central Valley Project water conservation best management... DEPARTMENT OF THE INTERIOR Bureau of Reclamation Central Valley Project Improvement Act, Water Management Plans AGENCY: Bureau of Reclamation, Interior. ACTION: Notice of availability. SUMMARY: The...

  18. Fuzzy based method for project planning of the infrastructure design for the diagnostic in ITER

    International Nuclear Information System (INIS)

    Piros, Attila; Veres, Gábor

    2013-01-01

    The long-term design projects need special preparation before the start of the execution. This preparation usually includes the drawing of the network diagram for the whole procedure. This diagram includes the time estimation of the individual subtasks and gives us information about the predicted dates of the milestones. The calculated critical path in this network characterizes a specific design project concerning to its duration very well. Several methods are available to support this step of preparation. This paper describes a new method to map the structure of the design process and clarify the milestones and predict the dates of these milestones. The method is based on the PERT (Project Evaluation and Review Technique) network but as a novelty it applies fuzzy logic to find out the concerning times in this graph. With the application of the fuzzy logic the handling of the different kinds of design uncertainties becomes feasible. Many kinds of design uncertainties exist from the possible electric blackout up to the illness of an engineer. In many cases these uncertainties are related with human errors and described with linguistic expressions. The fuzzy logic enables to transform these ambiguous expressions into numeric values for further mathematical evaluation. The method is introduced in the planning of the design project of the infrastructure for the diagnostic systems of ITER. The method not only helps the project in the planning phase, but it will be a powerful tool in mathematical modeling and monitoring of the project execution

  19. Fuzzy based method for project planning of the infrastructure design for the diagnostic in ITER

    Energy Technology Data Exchange (ETDEWEB)

    Piros, Attila, E-mail: attila.piros@gt3.bme.hu [Department of Machine and Product Design, Budapest University of Technology and Economics, Budapest (Hungary); Veres, Gábor [Department of Plasma Physics, Wigner Research Centre for Physics, Hungarian Academy of Sciences, Budapest (Hungary)

    2013-10-15

    The long-term design projects need special preparation before the start of the execution. This preparation usually includes the drawing of the network diagram for the whole procedure. This diagram includes the time estimation of the individual subtasks and gives us information about the predicted dates of the milestones. The calculated critical path in this network characterizes a specific design project concerning to its duration very well. Several methods are available to support this step of preparation. This paper describes a new method to map the structure of the design process and clarify the milestones and predict the dates of these milestones. The method is based on the PERT (Project Evaluation and Review Technique) network but as a novelty it applies fuzzy logic to find out the concerning times in this graph. With the application of the fuzzy logic the handling of the different kinds of design uncertainties becomes feasible. Many kinds of design uncertainties exist from the possible electric blackout up to the illness of an engineer. In many cases these uncertainties are related with human errors and described with linguistic expressions. The fuzzy logic enables to transform these ambiguous expressions into numeric values for further mathematical evaluation. The method is introduced in the planning of the design project of the infrastructure for the diagnostic systems of ITER. The method not only helps the project in the planning phase, but it will be a powerful tool in mathematical modeling and monitoring of the project execution.

  20. The Efficacy of Waste Management Plans in Australian Commercial Construction Refurbishment Projects

    Directory of Open Access Journals (Sweden)

    Mary Hardie

    2012-11-01

    Full Text Available Renovation and refurbishment of the existingcommercial building stock is a growing area oftotal construction activity and a significantgenerator of waste sent to landfill in Australia. Awritten waste management plan (WMP is awidespread regulatory requirement forcommercial office redevelopment projects. Thereis little evidence, however, that WMPs actuallyincrease the quantity of waste that is ultimatelydiverted from landfill. Some reports indicate anabsence of any formal verification or monitoringprocess by regulators to assess the efficacy ofthe plans. In order to gauge the extent of theproblem a survey was conducted of twenty fourconsultants and practitioners involved incommercial office building refurbishment projectsto determine the state of current practice withregard to WMPs and to elicit suggestions withregard to ways of making the process moreeffective. Considerable variation in commitmentto recycling policies was encountered indicatinga need to revisit waste minimisation practices ifthe environmental performance of refurbishmentprojects is to be improved.

  1. Enabling strategic projects: assessment of key instruments for national spatial planning

    NARCIS (Netherlands)

    Savini, F.; Salet, W.; Majoor, S.

    2010-01-01

    This research focuses on the instruments and tools which national planning agencies have at their disposal to intervene and get involved in strategic projects. The research examines how strategic national visions are translated into interventions in local projects across the Dutch territory. This

  2. A strategic plan for the second phase (2013-2015) of the Korea biobank project.

    Science.gov (United States)

    Park, Ok; Cho, Sang Yun; Shin, So Youn; Park, Jae-Sun; Kim, Jun Woo; Han, Bok-Ghee

    2013-04-01

    biobanks, and has also carried out various publicity promotions to the public and researchers. During the first phase, biospecimens from more than 300,000 participants through various cohorts and biospecimens from more than 200,000 patients from hospitals were collected, which were distributed to approximately 600 research projects. The planning committee for the second phase evaluated that the first phase of the KBP was successful. However, the first phase of the project was meant to allow autonomy to the individual biobanks. The biobanks were able to choose the kind of specimens they were going to collect and the amount of specimen they would set as a goal, as well as being allowed to choose their own methods to manage their biobanks (autonomy). Therefore, some biobanks collected resources that were easy to collect and the resources needed by researchers were not strategically collected. In addition, there was also a low distribution rate to researchers outside of hospitals, who do not have as much access to specimens and cases as those in hospitals. There were also many cases in which researchers were not aware of the KBP, and the distribution processes were not set up to be convenient to the demands of researchers. Accordingly, the second phase of the KBP will be focused on increasing the integration and cooperation between the biobanks within the network. The KBP plans to set goals for the strategic collection of the needed human bioresources. Although the main principle of the first phase was to establish infrastructure and resource collection, the key objective of the second phase is the efficient utilization of gathered resources. In order to fully utilize the gathered resources in an efficient way, distribution systems and policies must be improved. Vitalization of distribution, securing of high-value resource and related clinical and laboratory information, international standardization of resource management systems, and establishment of a virtuous cycle between

  3. Identifying Contractors’ Planned Quality Costs in Indonesian Construction Projects

    Directory of Open Access Journals (Sweden)

    Puti F. Marzuki

    2014-12-01

    Full Text Available In a very competitive construction industry, quality costs have to be measured to be able to identify potential quality problem areas and to focus attention on work output improvement opportunities. The awareness of contractors on the importance of quality costs could be reflected in the extent of their quality costs planning. This paper presents an identification of planned quality costs in three construction projects executed by two large Indonesian contractors, a state-owned company and a private company in Jakarta. The objective is to enable the contractors to elaborate their quality costs planning and thereby improve their work output based on the findi ngs. Quality costs are first grouped into three categories: prevention, appraisal, and failure costs. Based on the works of previous researchers, a list of quality management activities that should be covered in each quality costs category is then created. The contractors’ planned quality costs data for each category are identified and collected through interviews and questionnaire surveys that refer to the list. Quality costs are expressed as a percentage of contract value. It is revealed that although large contractors already have certain knowledge on quality costs in construction projects, these costs are not planned in a structured way through an analysis of systematic quality costs records. Through cost categorization it is also shown that higher prevention and appraisal costs lead to lower failure costs. It is then concluded that a lot of work is still to be done by the contractors to set up a quality costs recording system which can serve as a basis for their quality improvement planning.

  4. Uranium mill tailings remedial action project real estate management plan

    International Nuclear Information System (INIS)

    1994-09-01

    This plan summarizes the real estate requirements of the US Department of Energy's (DOE) Uranium Mill Tailings Action (UMTRA) Project, identifies the roles and responsibilities of project participants involved in real estate activities, and describes the approaches used for completing these requirements. This document is intended to serve as a practical guide for all project participants. It is intended to be consistent with all formal agreements, but if a conflict is identified, the formal agreements will take precedence

  5. Uranium mill tailings remedial action project real estate management plan

    Energy Technology Data Exchange (ETDEWEB)

    1994-09-01

    This plan summarizes the real estate requirements of the US Department of Energy`s (DOE) Uranium Mill Tailings Action (UMTRA) Project, identifies the roles and responsibilities of project participants involved in real estate activities, and describes the approaches used for completing these requirements. This document is intended to serve as a practical guide for all project participants. It is intended to be consistent with all formal agreements, but if a conflict is identified, the formal agreements will take precedence.

  6. Marketing plan : Dallas Integrated Corridor Management (ICM) demonstration project.

    Science.gov (United States)

    2014-01-01

    North Central Texas is a unique region in terms of its combination of recent, current and projected size, growth rate, ethnic diversity, and transportation profile specifically in relation to congestion. This document summarizes a plan to market ...

  7. Incorporating climate change projections into riparian restoration planning and design

    Science.gov (United States)

    Perry, Laura G.; Reynolds, Lindsay V.; Beechie, Timothy J.; Collins, Mathias J.; Shafroth, Patrick B.

    2015-01-01

    Climate change and associated changes in streamflow may alter riparian habitats substantially in coming decades. Riparian restoration provides opportunities to respond proactively to projected climate change effects, increase riparian ecosystem resilience to climate change, and simultaneously address effects of both climate change and other human disturbances. However, climate change may alter which restoration methods are most effective and which restoration goals can be achieved. Incorporating climate change into riparian restoration planning and design is critical to long-term restoration of desired community composition and ecosystem services. In this review, we discuss and provide examples of how climate change might be incorporated into restoration planning at the key stages of assessing the project context, establishing restoration goals and design criteria, evaluating design alternatives, and monitoring restoration outcomes. Restoration planners have access to numerous tools to predict future climate, streamflow, and riparian ecology at restoration sites. Planners can use those predictions to assess which species or ecosystem services will be most vulnerable under future conditions, and which sites will be most suitable for restoration. To accommodate future climate and streamflow change, planners may need to adjust methods for planting, invasive species control, channel and floodplain reconstruction, and water management. Given the considerable uncertainty in future climate and streamflow projections, riparian ecological responses, and effects on restoration outcomes, planners will need to consider multiple potential future scenarios, implement a variety of restoration methods, design projects with flexibility to adjust to future conditions, and plan to respond adaptively to unexpected change.

  8. Wind energy and spatial planning procedures; La programmation spatiale des projects eoliens

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2002-07-01

    Wind turbines projects have been increasing, but some are very conflicted. May be it is a reason why some local authorities have to deal with different point of view, above the only energy question and including local specificity. To give local authorities the possibility to be implicated and to be in control of wind projects in their territory, wind spatial planning should permit to choose suitable areas and to optimize wind power development. In this context this synthesis presents the wind spatial planning in Finistere (France), the french regulation, some international experiences (Danish, Flemish, Walloon region, Dutch) and the different approaches of spatial planning. (A.L.B.)

  9. UMTRA Project water sampling and analysis plan, Canonsburg, Pennsylvania. Revision 1

    International Nuclear Information System (INIS)

    1995-09-01

    Surface remedial action was completed at the US Department of Energy (DOE) Canonsburg and Burrell Uranium Mill Tailings Remedial Action (UMTRA) Project sites in southwestern Pennsylvania in 1985 and 1987, respectively. The Burrell disposal site, included in the UMTRA Project as a vicinity property, was remediated in conjunction with the remedial action at Canonsburg. On 27 May 1994, the Nuclear Regulatory Commission (NRC) accepted the DOE final Long-Term Surveillance Plan (LTSP) (DOE, 1993) for Burrell thus establishing the site under the general license in 10 CFR section 40.27 (1994). In accordance with the DOE guidance document for long-term surveillance (DOE, 1995), all NRC/DOE interaction on the Burrell site's long-term care now is conducted with the DOE Grand Junction Projects Office in Grand Junction, Colorado, and is no longer the responsibility of the DOE UMTRA Project Team in Albuquerque, New Mexico. Therefore, the planned sampling activities described in this water sampling and analysis plan (WSAP) are limited to the Canonsburg site. This WSAP identifies and justifies the sampling locations, analytical parameters, detection limits, and sampling frequencies for routine monitoring at the Canonsburg site for calendar years 1995 and 1996. Currently, the analytical data further the site characterization and demonstrate that the disposal cell's initial performance is in accordance with design requirements

  10. Mizunami Underground Research Laboratory project. Plan for fiscal year 2017

    International Nuclear Information System (INIS)

    Ishibashi, Masayuki; Hama, Katsuhiro; Iwatsuki, Teruki; Matsui, Hiroya; Takeuchi, Ryuji; Ikeda, Koki; Mikake, Shinichiro; Iyatomi, Yosuke; Sasao, Eiji; Koide, Kaoru

    2017-10-01

    The Mizunami Underground Research Laboratory (MIU) Project is being pursued by the Japan Atomic Energy Agency (JAEA) to enhance the reliability of geological disposal technologies through investigations of the deep geological environment in the crystalline host rock (granite) at Mizunami, Gifu Prefecture, central Japan. On the occasion of the reform of the entire JAEA organization in 2014, JAEA identified three important issues on the geoscientific research program: 'Development of countermeasure technologies for reducing groundwater inflow', 'Development of modelling technologies for mass transport' and 'Development of drift backfilling technology', based on the latest results of the synthesizing research and development (R and D). The R and D on three remaining important issues has been carrying out on the MIU Project. This report summarizes the R and D activities planned for fiscal year 2017 on the basis of the MIU Master Plan updated in 2015 and Investigation Plan for the Third Medium to Long-term Research Phase. (author)

  11. Building a team through a strategic planning process.

    Science.gov (United States)

    Albert, Debra; Priganc, Dave

    2014-01-01

    Strategic planning is a process often left to senior hospital leadership, with limited input from unit-level, bedside patient care providers. This frequent approach to strategic planning misses the opportunity to engage a wide range of employees, build a shared sense of commitment, produce a collaborative team environment, and to generate greater acceptance of the plan. The Patient Care Services division at the University of Chicago Medicine used a strategic planning process that incorporated 360-degree input from both within the Patient Care Services division and outside of the division. The result is a strategic vision and plan that, shaped by broad-based input from both internal and external constituencies, is strengthened by the team that emerged from the process. Through the process of identifying a common understanding of the group's future direction, a shared purpose was created that transcended traditional professional boundaries and shaped a cohesive team focused on effective and efficient patient care. Now, with a focused strategic plan and a team centered on a shared purpose, the team is beginning to effectively deliver on the plan.

  12. An optimization algorithm for simulation-based planning of low-income housing projects

    Directory of Open Access Journals (Sweden)

    Mohamed M. Marzouk

    2010-10-01

    Full Text Available Construction of low-income housing projects is a replicated process and is associated with uncertainties that arise from the unavailability of resources. Government agencies and/or contractors have to select a construction system that meets low-income housing projects constraints including project conditions, technical, financial and time constraints. This research presents a framework, using computer simulation, which aids government authorities and contractors in the planning of low-income housing projects. The proposed framework estimates the time and cost required for the construction of low-income housing using pre-cast hollow core with hollow blocks bearing walls. Five main components constitute the proposed framework: a network builder module, a construction alternative selection module, a simulation module, an optimization module and a reporting module. An optimization module utilizing a genetic algorithm enables the defining of different options and ranges of parameters associated with low-income housing projects that influence the duration and total cost of the pre-cast hollow core with hollow blocks bearing walls method. A computer prototype, named LIHouse_Sim, was developed in MS Visual Basic 6.0 as proof of concept for the proposed framework. A numerical example is presented to demonstrate the use of the developed framework and to illustrate its essential features.

  13. Strategy in Generative Planning of Turning Processes

    NARCIS (Netherlands)

    van Houten, Frederikus J.A.M.; Kals, H.J.J.

    1986-01-01

    This paper reports on the process and operations planning system ROUND and the strategies which underlie the decision making processes in the planning of turning operations. At first, an outline is given about the environment for which generative systems like ROUND are being developed. The

  14. UMTRA Surface Project management action process document. Final report: Revision 1

    International Nuclear Information System (INIS)

    1996-04-01

    A critical mission of the US Department of Energy (DOE) is the planning, implementation, and completion of environmental restoration (ER) programs at facilities that were operated by or in support of the former Atomic Energy Commission (AEC) from the late 1940s into the 1970s. Among these facilities are the 24 former uranium mill sites designed in the Uranium Mill Tailings Radiation Control Act (UMTRCA) of 1978 (42 USC section 7901 et seq.) Title 1 of the UMTRCA authorized the DOE to undertake remedial actions at these designated sites and associated vicinity properties (VP), which contain uranium mill tailings and other residual radioactive materials (RRM) derived from the processing sites. Title 2 of the UMTRCA addresses uranium mill sites that were licensed at the time the UMTRCA was enacted. Cleanup of these Title 2 sites is the responsibility of the licensees. The cleanup of the Title 1 sites has been split into two separate projects: the Surface Project, which deals with the mill buildings, tailings, and contaminated soils at the sites and VPs; and the Ground Water Project, which is limited to the contaminated ground water at the sites. This management action process (MAP) document discusses the Uranium Mill Tailings Remedial Action (UMTRA) Surface Project only; a separate MAP document has been prepared for the UMTRA Ground Water Project

  15. FY 1991 Task plans for the Hanford Environmental Dose Reconstruction Project

    International Nuclear Information System (INIS)

    1991-04-01

    The purpose of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate radiation doses from Hanford Site operations since 1944 to populations and individuals. The objectives of work in Fiscal Year (FY) 1991 are to analyze data and models used in Phase 1 and restructure the models to increase accuracy and reduce uncertainty in dose estimation capability. Databases will be expanded and efforts will begin to determine the appropriate scope (space, time, radionuclides, pathways and individuals/population groups) and accuracy (level of uncertainty in dose estimates) for the project. Project scope and accuracy requirements, once defined, can be translated into additional model and data requirements later in the project. Task plans for FY 1991 have been prepared based on activities approved by the Technical Steering Panel (TSP) in October 1990 and mid-year revisions discussed at the TSP planning/budget workshop in February 1991. The activities can be divided into two broad categories: (1) model and data development and evaluation, (2) project, technical and communication support. 3 figs., 1 tab

  16. Effluent monitoring Quality Assurance Project Plan for radioactive airborne emissions data. Revision 2

    International Nuclear Information System (INIS)

    Frazier, T.P.

    1995-12-01

    This Quality Assurance Project Plan addresses the quality assurance requirements for compiling Hanford Site radioactive airborne emissions data. These data will be reported to the U.S. Environmental Protection Agency, the US Department of Energy, and the Washington State Department of Health. Effluent Monitoring performs compliance assessments on radioactive airborne sampling and monitoring systems. This Quality Assurance Project Plan is prepared in compliance with interim guidelines and specifications. Topics include: project description; project organization and management; quality assurance objectives; sampling procedures; sample custody; calibration procedures; analytical procedures; monitoring and reporting criteria; data reduction, verification, and reporting; internal quality control; performance and system audits; corrective actions; and quality assurance reports

  17. Process of establishing JHP project

    International Nuclear Information System (INIS)

    Ishihara, Masayasu

    2013-01-01

    Institute for Nuclear Study, University of Tokyo was a Japanese central research institute as regards to nuclear physics, high energy physics, and cosmic ray physics. After the foundations of National Laboratory for High Energy Physics, KEK, and Institute for Cosmic Ray Research, University of Tokyo, in early 1970s, the nuclear physics community worked out so-called NUMATRON project, which involved building a large heavy-ion synchrotron. It was, however, not successful in competition with TRISTAN project which was proposed by KEK to build a 30 GeV electron-positron collider. Alternative project of the nuclear physics community was so-called JHP (Japanese Hadron Project), to build 1 GeV proton linac in KEK site in collaboration with KEK, which included that the Institute for Nuclear Study should be consolidated to KEK leaving from The University of Tokyo. The reorganized KEK proposed in collaboration with JAEA, Japan Atomic Energy Agency, to build a big proton accelerator facility in JAEA site. This plan was realized as J-PARC, Japanese Proton Accelerator Research Complex, operating 50 GeV proton synchrotron. (author)

  18. Closure plan for the proposed Millennium Project

    International Nuclear Information System (INIS)

    Tuttle, S.; Sisson, R.

    1999-01-01

    A $2.2 billion expansion of the current oil sands operation has been proposed by Suncor Energy Inc. The expansion would more than double the productive capacity of the present facility. As part of the application for this expansion, called Project Millennium, a comprehensive closure plan has been developed and filed by the Corporation. The Plan includes a systematic evaluation of the area to be developed, a description of the development activities planned, and the goals and objectives of the Corporation in re-establishing the landforms and ecosystems concurrently with running the operation. The Plan envisages surface contouring as early as practicable during the mine development, soil reconstruction, and re-establishment of vegetation, surface drainage and wetlands. The Corporation undertakes to monitor the performance of the reclaimed areas based on landform performance, the impact of chemical constituents on the landscape and ecosystem sustainability. An annual monitoring report assessing herbaceous vegetation growth, major species composition, tree and shrub survival and growth rate, groundwater conditions, amount of precipitation, the utility of constructed wetlands for treatment of reclamation area seepage and runoff waters, and wildlife population changes, will be prepared annually. A future research program associated with the Reclamation and Closure Plan will also examine the effectiveness of the reclamation drainage system as fish habitat, and the potential of the proposed end-pit lake to provide a viable aquatic ecosystem. 8 refs., 2 figs

  19. Project W-314 specific test and evaluation plan for 241-AN-A valve pit

    International Nuclear Information System (INIS)

    Hays, W.H.

    1998-01-01

    The purpose of this Specific Test and Evaluation Plan (STEP) is to provide a detailed written plan for the systematic testing of modifications made to the 241-AN-A Valve Pit by the W-314 Project. The STEP develops the outline for test procedures that verify the system's performance to the established Project design criteria. The STEP is a lower tier document based on the W-314 Test and Evaluation Plan (TEP)

  20. The implementation goals of geoinformation support to planning and spatial management at the local level in the framework of the ONIX project

    Directory of Open Access Journals (Sweden)

    Franc J. Zakrajšek

    1999-01-01

    Full Text Available The project objective is to strengthen the development, establishment, maintenance and use of the geographical data bases in the processes of physical planning and urban management on local level. It is a part of the Slovenian environmental project Onix. The current state is the phase of implementation.

  1. A Case Study of Resources Management Planning with Multiple Objectives and Projects

    Science.gov (United States)

    David L. Peterson; David G. Silsbee; Daniel L. Schmoldt

    1995-01-01

    Each National Park Service unit in the United States produces a resources management plan (RMP) every four years or less. The plans commit budgets and personnel to specific projects for four years, but they are prepared with little quantitative and analytical rigor and without formal decisionmaking tools. We have previously described a multiple objective planning...

  2. 谈项目施工的前期策划%Discussion on pre planning of project construction

    Institute of Scientific and Technical Information of China (English)

    谷来喜

    2014-01-01

    论述了项目前期策划的重要性,依据项目前期策划的基本原则,对项目策划的组织机构、施工部署、技术、质量、安全管理策划等项目施工前期策划编制的主要内容作了阐述,为项目管理提供参考依据。%This paper discussed the importance of project pre planning, based on the basic principles of project pre planning, elaborated the main contents of project planning organization, construction planning, technology, quality, safety management preparation and project construc-tion pre planning, provide reference basis for project management.

  3. 300-FF-1 remedial action sampling and analysis plan DQO process summary report

    International Nuclear Information System (INIS)

    Carlson, R.A.

    1997-01-01

    The scope of the 300-FF-1 Operable Unit (OU) data quality objective (DQO) process includes the soil and debris from the waste sites identified in the Proposed Plan for the 300-FF-1 and 300-FF-5 Operable units and, as the DQO process evolved, refined by the 300-FF-1 Record of Decision (ROD). Exclusions are identified in Section 1.3. The 300-FF-1 waste sites are addressed throughout the DQO process as they were subdivided in the proposed plan. The waste sites are divided into areas or zones known to be above the cleanup standards, zones below the cleanup standards, and zones where the contamination level is currently unknown. The project objectives are (1) to identify the criteria by which 300-FF-1 contaminated soil and debris may be shipped to the Environmental Restoration Disposal Facility (ERDF), (2) to identify the criteria by which the 300-FF-1 waste sites can be demonstrated as meeting the cleanup criteria, and (3) to develop a sampling and analysis plan (SAP) that adequately allows the evaluation of soil and debris analysis against the criteria

  4. Analysis and Development of a Project Evaluation Process.

    Energy Technology Data Exchange (ETDEWEB)

    Coutant, Charles C.; Cada Glenn F.

    1985-01-01

    The Bonneville Power Administration has responsibility, assigned by the Pacific Northwest Electric Power Planning and Conservation Act of 1980 (Public Law 96-501; 16 USC 839), for implementing the Columbia River Basin Fish and Wildlife Program of the Northwest Power Planning Council. One aspect of this responsibility is evaluation of project proposals and ongoing and completed projects. This report recommends formalized procedures for conducting this work in an accurate, professional, and widely respected manner. Recommendations and justifications are based largely on interviews with federal and state agencies and Indian tribes in the Northwest and nationally. Organizations were selected that have evaluation systems of their own, interact with the Fish and Wildlife Program, or have similar objectives or obligations. Perspective on aspects to be considered were obtained from the social science of evaluation planning. Examples of procedures and quantitative criteria are proposed. 1 figure, 2 tables.

  5. Healy Clean Coal Project, Healy, Alaska final Environmental Monitoring Plan

    Energy Technology Data Exchange (ETDEWEB)

    1994-06-14

    This Environmental Monitoring Plan (EMP) provides the mechanism to evaluate the integrated coal combustion/emission control system being demonstrated by the Healy Clean Coal Project (HCCP) as part-of the third solicitation of the US Department of Energy (DOE) Clean Coal Technology Demonstration Program (CCT-III). The EMP monitoring is intended to satisfy two objectives: (1) to develop the information base necessary for identification, assessment, and mitigation of potential environmental problems arising from replication of the technology and (2) to identify and quantify project-specific and site-specific environmental impacts predicted in the National Environmental Policy Act (NEPA) documents (Environmental Impact Statement and Record of Decision). The EMP contains a description of the background and history of development of the project technologies and defines the processes that will take place in the combustion and spray dryer absorber systems, including the formation of flash-calcined material (FCM) and its use in sulfur dioxide (SO{sub 2}) removal from the flue gases. It also contains a description of the existing environmental resources of the project area. The EMP includes two types of environmental monitoring that are to be used to demonstrate the technologies of the HCCP: compliance monitoring and supplemental monitoring. Compliance monitoring activities include air emissions, wastewater effluents, and visibility. Monitoring of these resources provide the data necessary to demonstrate that the power plant can operate under the required state and federal statutes, regulations, and permit requirements.

  6. Groundwater protection management program plan

    International Nuclear Information System (INIS)

    1992-06-01

    US Department of Energy (DOE) Order 5400.1 requires the establishment of a groundwater protection management program to ensure compliance with DOE requirements and applicable Federal, state, and local laws and regulations. The Uranium Mill Tailings Remedial Action (UMTRA) Project Office has prepared a ''Groundwater Protection Management Program Plan'' (groundwater protection plan) of sufficient scope and detail to reflect the program's significance and address the seven activities required in DOE Order 5400.1, Chapter 3, for special program planning. The groundwater protection plan highlights the methods designed to preserve, protect, and monitor groundwater resources at UMTRA Project processing and disposal sites. The plan includes an overview of the remedial action status at the 24 designated processing sites and identifies project technical guidance documents and site-specific documents for the UMTRA groundwater protection management program. In addition, the groundwater protection plan addresses the general information required to develop a water resources protection strategy at the permanent disposal sites. Finally, the plan describes ongoing activities that are in various stages of development at UMTRA sites (long-term care at disposal sites and groundwater restoration at processing sites). This plan will be reviewed annually and updated every 3 years in accordance with DOE Order 5400.1

  7. Strategic planning processes and hospital financial performance.

    Science.gov (United States)

    Kaissi, Amer A; Begun, James W

    2008-01-01

    Many common management practices in healthcare organizations, including the practice of strategic planning, have not been subject to widespread assessment through empirical research. If management practice is to be evidence-based, evaluations of such common practices need to be undertaken. The purpose of this research is to provide evidence on the extent of strategic planning practices and the association between hospital strategic planning processes and financial performance. In 2006, we surveyed a sample of 138 chief executive officers (CEOs) of hospitals in the state of Texas about strategic planning in their organizations and collected financial information on the hospitals for 2003. Among the sample hospitals, 87 percent reported having a strategic plan, and most reported that they followed a variety of common practices recommended for strategic planning-having a comprehensive plan, involving physicians, involving the board, and implementing the plan. About one-half of the hospitals assigned responsibility for the plan to the CEO. We tested the association between these planning characteristics in 2006 and two measures of financial performance for 2003. Three dimensions of the strategic planning process--having a strategic plan, assigning the CEO responsibility for the plan, and involving the board--are positively associated with earlier financial performance. Further longitudinal studies are needed to evaluate the cause-and-effect relationship between planning and performance.

  8. Project management in health informatics.

    Science.gov (United States)

    Ho, Jessica

    2010-01-01

    This chapter gives an educational overview of: * the concept of project management and its role in modern management * the generic project lifecycle process * processes used in developing a plan for the management of resources - time, cost, physical resources and people * the concept of managing risk in projects * communication processes and practices that are important to the management of projects.

  9. Nurse-led action research project for expanding nurses′ role in patient education in Iran: Process, structure, and outcomes

    Directory of Open Access Journals (Sweden)

    Parvaneh Khorasani

    2015-01-01

    Full Text Available Background: Patient education is among the lowest met need of patients in Iran; therefore, expansion of that role can result in greater professional accountability. This study aimed to explain the practical science of the process, structure, and outcomes of a nurse-led action research project to expand the nurses′ role in patient education in Iran. Materials and Methods: This study was part of a participatory action research. Daily communications and monthly joint meetings were held from January 2012 to February 2014 for planning and management. These were based on the research protocol, and the conceptual framework included the Mobilizing for Action through Planning and Partnerships process by means of Leadership for Change skills. Data were produced and gathered through participant observations. Administrative data included project records, official documents, artifacts, news, and reports, which were analyzed through qualitative content analysis. Results: A participatory project was established with three groups of participants organized from both academic and clinical fields. These consisted of a "core research support team," "two steering committees," and community representatives of clients and professionals as "feedback groups." A seven-stage process, named the "Nurse Educators: Al-Zahra Role Expansion Action Research" (NEAREAR process, resulted from the project, in which strategic issues were gradually developed and implemented through 32 action plans and quality improvement cycles of action research. Audits and supervision evaluations showed meaningful changes in capacity building components. Conclusions: A nurse-led ad hoc structure with academic-clinical partnerships and strategic management process was suggested as a possible practical model for expanding nurses′ educational role in similar contexts. Implications and practical science introduced in this action research could also be applicable for top managers and health system

  10. Nurse-led action research project for expanding nurses’ role in patient education in Iran: Process, structure, and outcomes

    Science.gov (United States)

    Khorasani, Parvaneh; Rassouli, Maryam; Parvizy, Soroor; Zagheri-Tafreshi, Mansoureh; Nasr-Esfahani, Mahmood

    2015-01-01

    Background: Patient education is among the lowest met need of patients in Iran; therefore, expansion of that role can result in greater professional accountability. This study aimed to explain the practical science of the process, structure, and outcomes of a nurse-led action research project to expand the nurses’ role in patient education in Iran. Materials and Methods: This study was part of a participatory action research. Daily communications and monthly joint meetings were held from January 2012 to February 2014 for planning and management. These were based on the research protocol, and the conceptual framework included the Mobilizing for Action through Planning and Partnerships process by means of Leadership for Change skills. Data were produced and gathered through participant observations. Administrative data included project records, official documents, artifacts, news, and reports, which were analyzed through qualitative content analysis. Results: A participatory project was established with three groups of participants organized from both academic and clinical fields. These consisted of a “core research support team,” “two steering committees,” and community representatives of clients and professionals as “feedback groups.” A seven-stage process, named the “Nurse Educators: Al-Zahra Role Expansion Action Research” (NEAREAR) process, resulted from the project, in which strategic issues were gradually developed and implemented through 32 action plans and quality improvement cycles of action research. Audits and supervision evaluations showed meaningful changes in capacity building components. Conclusions: A nurse-led ad hoc structure with academic–clinical partnerships and strategic management process was suggested as a possible practical model for expanding nurses’ educational role in similar contexts. Implications and practical science introduced in this action research could also be applicable for top managers and health system

  11. Nurse-led action research project for expanding nurses' role in patient education in Iran: Process, structure, and outcomes.

    Science.gov (United States)

    Khorasani, Parvaneh; Rassouli, Maryam; Parvizy, Soroor; Zagheri-Tafreshi, Mansoureh; Nasr-Esfahani, Mahmood

    2015-01-01

    Patient education is among the lowest met need of patients in Iran; therefore, expansion of that role can result in greater professional accountability. This study aimed to explain the practical science of the process, structure, and outcomes of a nurse-led action research project to expand the nurses' role in patient education in Iran. This study was part of a participatory action research. Daily communications and monthly joint meetings were held from January 2012 to February 2014 for planning and management. These were based on the research protocol, and the conceptual framework included the Mobilizing for Action through Planning and Partnerships process by means of Leadership for Change skills. Data were produced and gathered through participant observations. Administrative data included project records, official documents, artifacts, news, and reports, which were analyzed through qualitative content analysis. A participatory project was established with three groups of participants organized from both academic and clinical fields. These consisted of a "core research support team," "two steering committees," and community representatives of clients and professionals as "feedback groups." A seven-stage process, named the "Nurse Educators: Al-Zahra Role Expansion Action Research" (NEAREAR) process, resulted from the project, in which strategic issues were gradually developed and implemented through 32 action plans and quality improvement cycles of action research. Audits and supervision evaluations showed meaningful changes in capacity building components. A nurse-led ad hoc structure with academic-clinical partnerships and strategic management process was suggested as a possible practical model for expanding nurses' educational role in similar contexts. Implications and practical science introduced in this action research could also be applicable for top managers and health system policy makers in a wider range of practice.

  12. Software Configuration Management Plan for the K West Basin Integrated Water Treatment System (IWTS) - Project A.9

    International Nuclear Information System (INIS)

    GREEN, J.W.

    2000-01-01

    This document provides a configuration control plan for the software associated with the operation and control of the Integrated Water Treatment System (IWTS). It establishes requirements for ensuring configuration item identification, configuration control, configuration status accounting, defect reporting and resolution of computer software. It is written to comply with HNF-SD-SNF-CM-001, Spent Nuclear Fuel Configuration Management Plan (Forehand 1998) and HNF-PRO-309 Computer Software Quality Assurance Requirements, and applicable sections of administrative procedure CM-6-037-00, SNF Project Process Automation Software and Equipment

  13. Development of an Improved Process for Installation Projects of High Technology Manufacturing Equipment

    Energy Technology Data Exchange (ETDEWEB)

    Quintana, Sarah V. [Los Alamos National Lab. (LANL), Los Alamos, NM (United States)

    2014-04-30

    High technology manufacturing equipment is utilized at Los Alamos National Laboratory (LANL) to support nuclear missions. This is undertaken from concept initiation where equipment is designed and then taken through several review phases, working closely with system engineers (SEs) responsible for each of the affected systems or involved disciplines (from gasses to HVAC to structural, etc.). After the design is finalized it moves to procurement and custom fabrication of the equipment and equipment installation, including all of the paperwork involved. Not only are the engineering and manufacturing aspects important, but also the scheduling, financial forecasting, and planning portions that take place initially and are sometimes modified as the project progresses should requirements, changes or additions become necessary. The process required to complete a project of this type, including equipment installation, is unique and involves numerous steps to complete. These processes can be improved and recent work on the Direct Current Arc (DC Arc) Glovebox Design, Fabrication and Installation Project provides an opportunity to identify some important lessons learned (LL) that can be implemented in the future for continued project improvement and success.

  14. Project management a systems approach to planning, scheduling, and controlling

    CERN Document Server

    Kerzner, Harold

    2017-01-01

    Project Management is the bestselling text for students and professionals, presenting a streamlined approach to project management functions in full alignment with PMI(r)'s latest Project Management Body of Knowledge (PMBOK(r)). This new 12th edition has been updated to reflect the latest changes found in the PMBOK(r) Guide--Sixth Edition, and features new coverage of emerging topics including global stakeholder management, causes of failure, agile project management, project governance failure, customer approval milestones, classifying project metrics, and more. Supplementary materials are available for students, working professionals, and instructors. * Understand organizational structures and project management functions * Learn how to control costs, manage risk, and analyze trade-offs * Examine different methods used for planning, scheduling, QA, and more * Work effectively with customers and stakeholders from around the globe Project Management is the comprehensive reference to keep within arm's reach. ...

  15. Watershed manipulation project: Field implementation plan for 1990-1992

    International Nuclear Information System (INIS)

    Erickson, H.; Narahara, A.M.; Rustad, L.E.; Mitchell, M.; Lee, J.

    1993-02-01

    The Bear Brook Watershed in Maine (BBWM) was established in 1986 at Lead Mountain, Maine as part of the Environmental Protection Agency's (EPA) Watershed Manipulation Project (WPM). The goals of the project are to: (1) assess the chemical response of a small upland forested watershed to increased loadings of SO4, (2) determine interactions among biogeochemical mechanisms controlling watershed response to acidic deposition, and (3) test the assumptions of the Direct/Delayed Response Programs (DDRP) computer models of watershed acidification. The document summarizes the field procedures used in the establishment and initial implementation of the plot- and catchment- scale activities at the BBWM, and outlines plans for 1990-02 project activities

  16. A key to success: optimizing the planning process

    Science.gov (United States)

    Turk, Huseyin; Karakaya, Kamil

    2014-05-01

    By adopting The NATO Strategic Concept Document in 2010, some important changes in the perception of threat and management of crisis were introduced. This new concept, named ''Comprehensive Approach'', includes the precautions of pre-crisis management, applications of crisis-duration management and reconstruction phase of post-intervention management. NATO will be interested in not only the political and military options , but also social, economical and informational aspects of crisis. NATO will take place in all phases of conflict. The conflicts which occur outside the borders of NATO's nations and terrorism are perceived as threat sources for peace and stability. In addition to conventional threats, cyber attacks which threaten network-supported communication systems, preventing applications from accessing to space that will be used in different fields of life. On the other hand, electronic warfare capabilities which can effect us negatively are added to threat list as new threats. In the process in which military is thought as option, a harder planning phase is waiting for NATO's decision makers who struggle for keeping peace and security. Operation planning process which depends on comprehensive approach, contains these steps: Situational awareness of battlefield, evaluation of the military intervention options, orientation, developing an operation plan, reviewing the plan and transition phases.1 To be successful in theater which is always changing with the technological advances, there has to be an accurate and timely planning on the table. So, spending time for planning can be shown as one of the biggest problem. In addition, sustaining situational awareness which is important for the whole operation planning process, technical command and control hitches, human factor, inability to determine the center of gravity of opponent in asymmetrical threat situations can be described as some of the difficulties in operation planning. In this study, a possible air

  17. Nuclear emergency planning in Spain. The PLABEN review project

    International Nuclear Information System (INIS)

    Lentijo Lentijo, J. C.; Vila Pena, M.

    2002-01-01

    The international rules and recommendations for nuclear emergency planning and the Spanish experience gained in the management of event with radiological risk have noticed that is necessary to review the planning radiological bases for emergencies in nuclear power plants and to define the planning radiological bases for radiological emergencies that could happen in radioactive facilities or in activities out of the regulatory framework. The paper focuses on CSN actions concerning the Plaben review project related to define the new radiological principles taking into account the current international recommendations for interventions, make a proposal about the organisation and operation of the provincial radiological action group and the national support level for radiological emergency response. (Author) 7 refs

  18. Single-Shell Tank (SST) Retrieval Project Plan for Tank 241-C-104 Retrieval

    International Nuclear Information System (INIS)

    DEFIGH PRICE, C.

    2000-01-01

    In support of the SST Interim Closure Project, Project W-523 ''Tank 241-C-104 Waste Retrieval System'' will provide systems for retrieval and transfer of radioactive waste from tank 241-C-104 (C-104) to the DST staging tank 241-AY-101 (AY-101). At the conclusion of Project W-523, a retrieval system will have been designed and tested to meet the requirements for Acceptance of Beneficial Use and been turned over to operations. Completion of construction and operations of the C-104 retrieval system will meet the recently proposed near-term Tri-Party Agreement milestone, M-45-03F (Proposed Tri-Party Agreement change request M-45-00-01A, August, 30 2000) for demonstrating limits of retrieval technologies on sludge and hard heels in SSTs, reduce near-term storage risks associated with aging SSTs, and provide feed for the tank waste treatment plant. This Project Plan documents the methodology for managing Project W-523; formalizes responsibilities; identifies key interfaces required to complete the retrieval action; establishes the technical, cost, and schedule baselines; and identifies project organizational requirements pertaining to the engineering process such as environmental, safety, quality assurance, change control, design verification, testing, and operational turnover

  19. HTI retrieval demonstration project execution plan

    International Nuclear Information System (INIS)

    Ellingson, D.R.

    1997-01-01

    This plan describes the process for demonstrating the retrieval of difficult Hanford tank waste forms utilizing commercial technologies and the private sector to conduct the operations. The demonstration is to be conducted in Tank 241-C-106

  20. Determination of risk identification process employed by NHS for a PFI hospital project in the UK

    Directory of Open Access Journals (Sweden)

    F. E. Mohamed Ghazali

    2009-12-01

    Full Text Available Long-term concession contracts associated with Private Finance Initiative (PFI projects, such as National Health Service (NHS hospitals, are subject to substantial risks, which may not only emerge from project activities such as design and construction, but also from global issues beyond the control of project parties, such as commercial, legal and political risks. Therefore, the principal parties involved must manage risks effectively and efficiently, as early as the project initiation stage, in order to ensure a successful delivery. The aim of this paper is to examine the risk identification process of the NHS PFI hospital in the UK, as a case study, in order to determine the techniques used in risk identification, and their significance, based on estimated probabilities of occurrence. These objectives were achieved through interviews with key personnel within the NHS Trust involved. Results found the sole technique used in risk identification to be brainstorming, through which more than thirty risks were identified and classified under six risk categories: planning, pre-commissioning, design, land purchasing, construction and operation. Thirteen risks were identified as significant based on their estimated probability of occurrence had the project been developed via public procurement. The results of this research will enable public sector clients like the NHS Trust to not only identify the significant risks, which will allow them to focus more attention on developing appropriate mitigation strategies and contingency plans, but also to improve its risk identification process through the use of other techniques in order to support findings from the brainstorming process.

  1. PUREX/UO3 deactivation project management plan

    International Nuclear Information System (INIS)

    Washenfelder, D.J.

    1993-12-01

    From 1955 through 1990, the Plutonium-Uranium Extraction Plant (PUREX) provided the United States Department of Energy Hanford Site with nuclear fuel reprocessing capability. It operated in sequence with the Uranium Trioxide (UO 3 ) Plant, which converted the PUREX liquid uranium nitrate product to solid UO 3 powder. Final UO 3 Plant operation ended in 1993. In December 1992, planning was initiated for the deactivation of PUREX and UO 3 Plant. The objective of deactivation planning was to identify the activities needed to establish a passively safe, environmentally secure configuration at both plants, and ensure that the configuration could be retained during the post-deactivation period. The PUREX/UO 3 Deactivation Project management plan represents completion of the planning efforts. It presents the deactivation approach to be used for the two plants, and the supporting technical, cost, and schedule baselines. Deactivation activities concentrate on removal, reduction, and stabilization of the radioactive and chemical materials remaining at the plants, and the shutdown of the utilities and effluents. When deactivation is completed, the two plants will be left unoccupied and locked, pending eventual decontamination and decommissioning. Deactivation is expected to cost $233.8 million, require 5 years to complete, and yield $36 million in annual surveillance and maintenance cost savings

  2. Engineering work plan for implementing the Process Condensate Recycle Project at the 242-A evaporator

    International Nuclear Information System (INIS)

    Haring, D.S.

    1995-01-01

    The 242-A Evaporator facility is used to reduce the volume of waste stored in the Hanford double shell tanks. This facility uses filtered raw water for cooling, de-entrainment pad sprays, pump seal water, and chemical tank make-up. Some of these uses result in the introduction of filtered raw water into the process, thus increasing the volume of waste requiring evaporation and subsequent treatment by the 200 East Effluent Treatment Facility. The pump seal water and the de-entrainment pad spray systems were identified as candidates for a waste minimization upgrade. This work plan describes the activities associated with the design, installation, testing and initial operation of the process condensate recycle system. Implementation of the process condensate recycle system will permit the use of process condensate in place of raw water for the de-entrainment pad sprays and pump seals. This will reduce the amount of low-level liquid waste and generated during facility operation through source reduction and recycling

  3. Assessment Approach for Identifying Compatibility of Restoration Projects with Geomorphic and Flooding Processes in Gravel Bed Rivers.

    Science.gov (United States)

    DeVries, Paul; Aldrich, Robert

    2015-08-01

    A critical requirement for a successful river restoration project in a dynamic gravel bed river is that it be compatible with natural hydraulic and sediment transport processes operating at the reach scale. The potential for failure is greater at locations where the influence of natural processes is inconsistent with intended project function and performance. We present an approach using practical GIS, hydrologic, hydraulic, and sediment transport analyses to identify locations where specific restoration project types have the greatest likelihood of working as intended because their function and design are matched with flooding and morphologic processes. The key premise is to identify whether a specific river analysis segment (length ~1-10 bankfull widths) within a longer reach is geomorphically active or inactive in the context of vertical and lateral stabilities, and hydrologically active for floodplain connectivity. Analyses involve empirical channel geometry relations, aerial photographic time series, LiDAR data, HEC-RAS hydraulic modeling, and a time-integrated sediment transport budget to evaluate trapping efficiency within each segment. The analysis segments are defined by HEC-RAS model cross sections. The results have been used effectively to identify feasible projects in a variety of alluvial gravel bed river reaches with lengths between 11 and 80 km and 2-year flood magnitudes between ~350 and 1330 m(3)/s. Projects constructed based on the results have all performed as planned. In addition, the results provide key criteria for formulating erosion and flood management plans.

  4. Assessment Approach for Identifying Compatibility of Restoration Projects with Geomorphic and Flooding Processes in Gravel Bed Rivers

    Science.gov (United States)

    DeVries, Paul; Aldrich, Robert

    2015-08-01

    A critical requirement for a successful river restoration project in a dynamic gravel bed river is that it be compatible with natural hydraulic and sediment transport processes operating at the reach scale. The potential for failure is greater at locations where the influence of natural processes is inconsistent with intended project function and performance. We present an approach using practical GIS, hydrologic, hydraulic, and sediment transport analyses to identify locations where specific restoration project types have the greatest likelihood of working as intended because their function and design are matched with flooding and morphologic processes. The key premise is to identify whether a specific river analysis segment (length ~1-10 bankfull widths) within a longer reach is geomorphically active or inactive in the context of vertical and lateral stabilities, and hydrologically active for floodplain connectivity. Analyses involve empirical channel geometry relations, aerial photographic time series, LiDAR data, HEC-RAS hydraulic modeling, and a time-integrated sediment transport budget to evaluate trapping efficiency within each segment. The analysis segments are defined by HEC-RAS model cross sections. The results have been used effectively to identify feasible projects in a variety of alluvial gravel bed river reaches with lengths between 11 and 80 km and 2-year flood magnitudes between ~350 and 1330 m3/s. Projects constructed based on the results have all performed as planned. In addition, the results provide key criteria for formulating erosion and flood management plans.

  5. High Burnup Dry Storage Cask Research and Development Project, Final Test Plan

    Energy Technology Data Exchange (ETDEWEB)

    None

    2014-02-27

    EPRI is leading a project team to develop and implement the first five years of a Test Plan to collect data from a SNF dry storage system containing high burnup fuel.12 The Test Plan defined in this document outlines the data to be collected, and the storage system design, procedures, and licensing necessary to implement the Test Plan.13 The main goals of the proposed test are to provide confirmatory data14 for models, future SNF dry storage cask design, and to support license renewals and new licenses for ISFSIs. To provide data that is most relevant to high burnup fuel in dry storage, the design of the test storage system must mimic real conditions that high burnup SNF experiences during all stages of dry storage: loading, cask drying, inert gas backfilling, and transfer to the ISFSI for multi-year storage.15 Along with other optional modeling, SETs, and SSTs, the data collected in this Test Plan can be used to evaluate the integrity of dry storage systems and the high burnup fuel contained therein over many decades. It should be noted that the Test Plan described in this document discusses essential activities that go beyond the first five years of Test Plan implementation.16 The first five years of the Test Plan include activities up through loading the cask, initiating the data collection, and beginning the long-term storage period at the ISFSI. The Test Plan encompasses the overall project that includes activities that may not be completed until 15 or more years from now, including continued data collection, shipment of the Research Project Cask to a Fuel Examination Facility, opening the cask at the Fuel Examination Facility, and examining the high burnup fuel after the initial storage period.

  6. Project W-314 specific test and evaluation plan for 241-AY-02A pump pit upgrade

    International Nuclear Information System (INIS)

    Hays, W.H.

    1998-01-01

    This Specific Test and Evaluation Plan (STEP) defines the test and evaluation activities encompassing the upgrade of the 241-AY-02A Pump Pit for the W-314 Project. The purpose of this Specific Test and Evaluation Plan (STEP) is to provide a detailed written plan for the systematic testing of modifications made to the 241-AY-02A Pump Pit by the W-314 Project. The STEP develops the outline for test procedures that verify the system's performance to the established Project design criteria. The STEP is a lower tier document based on the W-314 Test and Evaluation Plan (TEP)

  7. Project W-314 specific test and evaluation plan for 241-AY-01A pump pit upgrade

    International Nuclear Information System (INIS)

    Hays, W.H.

    1998-01-01

    This Specific Test and Evaluation Plan (STEP) defines the test and evaluation activities encompassing the upgrade of the 241-AY-0IA Pump Pit for the W-314 Project. The purpose of this Specific Test and Evaluation Plan (STEP) is to provide a detailed written plan for the systematic testing of modifications made to the 241-AY-01A Pump Pit by the W-314 Project. The STEP develops the outline for test procedures that verify the system's performance to the established Project design criteria. The STEP is a lower tier document based on the W-314 Test and Evaluation Plan (TEP)

  8. Capital planning for operating theatres based on projecting future theatre requirements.

    Science.gov (United States)

    Sheehan, Jennifer A; Tyler, Peter; Jayasinha, Hirani; Meleady, Kathleen T; Jones, Neill

    2011-05-01

    During 2006, NSW and ACT Health Departments jointly engaged KPMG to develop an Operating Theatre Requirements' Projection Model and an accompanying planning guideline. A research scan was carried out to identify drivers of surgical demand, theatre capacity and theatre performance, as well as locating existing approaches to modelling operating theatre requirements for planning purposes. The project delivered a Microsoft Excel-based model for projecting future operating theatre requirements, together with an accompanying guideline for use of the model and interpretation of its outputs. It provides a valuable addition to the suite of tools available to Health staff for service and capital planning. The model operates with several limitations, largely due to being data dependent, and the state and completeness of available theatre activity data. However, the operational flexibility built into the model allows users to compensate for these limitations, on a case by case basis, when the user has access to suitable, local data. The design flexibility of the model means that updating the model as improved data become available is not difficult; resulting in revisions being able to be made quickly, and disseminated to users rapidly.

  9. Recent progress of the waste processing and disposal projects within the Underground Storage Tank-Integrated Demonstration

    International Nuclear Information System (INIS)

    Hunt, R.D.; McGinnis, C.P.; Cruse, J.M.

    1994-01-01

    The US Department of Energy (DOE) Office of Environmental Restoration and Waste Remediation has created the Office of Technology Development (OTD) to provide new and improved remediation technologies for the 1 x 10 8 gal of radioactive waste in the underground storage tanks (USTs) at five DOE sites. The OTD established and the Underground Storage Tank-Integrated Demonstration (UST-ID) to perform demonstrations, tests, and evaluations on these new technologies before these processes are transferred to the tank sites for use in full-scale remediation of the USTs. The UST-ID projects are performed by the Characterization and Waste Retrieval Program or the Waste Processing and Disposal Program (WPDP). During FY 1994, the WPDP is funding 12 projects in the areas of supernate processing, sludge processing, nitrate destruction, and final waste forms. The supernate projects are primarily concerned with cesium removal. A mobile evaporator and concentrator for cesium-free supernate is also being demonstrated. The sludge projects are emphasizing sludge dissolution and the evaluation of the TRUEX and diamide solvent extraction processes for transuranic waste streams. One WPDP project is examining both supernate and sludge processes in an effort to develop a system-level plan for handling all UST waste. The other WPDP studies are concerned with nitrate and organic destruction as well as subsequent waste forms. The current status of these WPDP projects is presented

  10. 300 Area Process Trenches Closure Plan

    International Nuclear Information System (INIS)

    Luke, S.N.

    1994-01-01

    Since 1987, Westinghouse Hanford Company has been a major contractor to the US Department of Energy, Richland Operations Office and has served as co-operator of the 300 Area Process Trenches, the waste management unit addressed in this closure plan. For the purposes of the Resource Conservation and Recovery Act, Westinghouse Hanford Company is identified as ''co-operator.'' The 300 Area Process Trenches Closure Plan (Revision 0) consists of a Resource Conservation and Recovery Act Part A Dangerous Waste Permit Application, Form 3 and a Resource Conservation and Recovery Act Closure Plan. An explanation of the Part A Permit Application, Form 3 submitted with this document is provided at the beginning of the Part A Section. The closure plan consists of nine chapters and six appendices. The 300 Area Process Trenches received dangerous waste discharges from research and development laboratories in the 300 Area and from fuels fabrication processes. This waste consisted of state-only toxic (WT02), corrosive (D002), chromium (D007), spent halogenated solvents (F001, F002, and F003), and spent nonhalogented solvent (F005). Accurate records are unavailable concerning the amount of dangerous waste discharged to the trenches. The estimated annual quantity of waste (item IV.B) reflects the total quantity of both regulated and nonregulated waste water that was discharged to the unit

  11. Work plan for the Isotopes Facilities Deactivation Project at Oak Ridge National Laboratory

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-05-01

    The purpose of the Isotopes Facilities Deactivation Project (IFDP) is to place former isotopes production facilities at the Oak Ridge National Laboratory in a safe, stable, and environmentally sound condition; suitable for an extended period of minimum surveillance and maintenance (S&M) and as quickly and economical as possible. Implementation and completion of the deactivation project will further reduce the risks to the environment and to public safety and health. Furthermore, completion of the project will result in significant S&M cost savings in future years. The IFDP work plan defines the project schedule, the cost estimate, and the technical approach for the project. A companion document, the IFDP management plan, has been prepared to document the project objectives, define organizational relationships and responsibilities, and outline the management control systems to be employed in the management of the project. The project has adopted the strategy of deactivating the simple facilities first, to reduce the scope of the project and to gain experience before addressing more difficult facilities. A decision support system is being developed to identify the activities that best promote the project mission and result in the largest cost savings. This work plan will be reviewed and revised annually. Deactivation of IFDP facilities was initiated in FY 1994 and will be completed in FY 1999. The schedule for deactivation of facilities is shown. The total cost of the project is estimated to be $36M. The costs are summarized. Upon completion of deactivation, annual S&M costs of these facilities will be reduced from the current level of $5M per year to less than $1M per year.

  12. The 2055 freight transportation system and the impact of near term rail improvements on TXDOT planning project management plan.

    Science.gov (United States)

    2016-03-01

    The Texas Department of Transportation (TxDOT) is the sponsor of the project. The : project goals are to: (1) produce a framework for Texas freight transportation system in : 2055 and (2) develop a set of rail planning recommendations that will be...

  13. Public information plan. Version 2

    International Nuclear Information System (INIS)

    1993-01-01

    The Public Information Plan is intended to be used in conjunction with the U.S. Department of Energy (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project Public Participation Plan. The Public Participation Pion describes the DOE procedure for involving the public in the decision-making process related to the UMTRA Project during the stages at which public participation is required and solicited. This Public Information Plan describes the department's procedure for communicating with the public about project policies, plans, and activities. Together, these complementary plans describe the DOE public affairs program for the UMTRA Project. This project was authorized by Congress in the Uranium Mill Tailings Radiation Control Act (UMTRCA) of 1978, (Public Law (PL) 95-6041), as amended. The Act provides for a cooperative effort with affected states and Indian tribes for the cleanup of designated abandoned or inactive uranium mill tailings sites, which are located in 10 states, 9 of them west of the Mississippi River. The public has a right to know about proposed government actions and to be heard in the planning of activities that influence their lives. The UMTRA Project is unclassified and the DOE provides accurate information about policy and project activities to interested stakeholders, including the news media, in a timely way. The DOE encourages states and local governments, as well as individuals, to join actively in the decision-making process. This is intended to ensure that the resulting decisions are made with full knowledge of the public's views and that these decisions address the public's concerns to the extent possible within the law. The DOE, through the implementation of the Public Information Plan, keeps the public informed on matters such as health concerns, environmental issues, remedial action construction plans, project costs, and specific site activities

  14. Developing a User-Centred Planning Tool for Young Adults with Development Disorders: A Research-Based Teaching Project.

    Science.gov (United States)

    Ribu, Kirsten; Patel, Tulpesh

    2016-01-01

    People with development disorders, for instance autism, need structured plans to help create predictability in their daily lives. Digital plans can facilitate enhanced independency, learning, and quality of life, but existing apps are largely general purpose and lack the flexibility required by this specific but heterogeneous user group. Universal design is both a goal and a process and should be based on a holistic approach and user-centered design, interacting with the users in all stages of the development process. At Oslo and Akershus University College (HiOA) we conducted a research-based teaching project in co-operation with the Department of Neuro-habilitation at Oslo University Hospital (OUS) with two employees acting as project managers and students as developers. Three groups of Computer Science bachelor students developed digital prototypes for a planning tool for young adults with pervasive development disorders, who live either with their families or in supervised residences, and do not receive extensive public services. The students conducted the initial planning phase of the software development process, focusing on prototyping the system requirements, whilst a professional software company programmed the end solution. The goal of the project was to develop flexible and adaptive user-oriented and user-specific app solutions for tablets that can aid this diverse user group in structuring daily life, whereby, for example, photos of objects and places known to the individual user replace general pictures or drawings, and checklists can be elaborate or sparse as necessary. The three student groups worked independently of each other and created interactive working prototypes based on tests, observations and short interviews with end users (both administrators and residents) and regular user feedback from the project managers. Three very different solutions were developed that were of high enough quality that an external software company were able to

  15. Systems Engineering Management Plan for Tank Farm Restoration and Safety Operations, Project W-314

    International Nuclear Information System (INIS)

    MCGREW, D.L.

    2000-01-01

    The Systems Engineering Management Plan for Project W-314 has been prepared within the guidelines of HNF-SD-WM-SEMP-002, TWRS Systems Engineering Management Plan. The activities within this SEMP have been tailored, in accordance with the TWRS SEMP and DOE Order 430.1, Life Cycle Asset Management, to meet the needs of the project

  16. Underground Test Area Project Waste Management Plan (Rev. No. 2, April 2002)

    International Nuclear Information System (INIS)

    IT Corporation, Las Vegas

    2002-01-01

    The U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Operations Office (NNSA/NV) initiated the UGTA Project to characterize the risk posed to human health and the environment as a result of underground nuclear testing activities at the Nevada Test Site (NTS). The UGTA Project investigation sites have been grouped into Corrective Action Units (CAUs) in accordance with the most recent version of the Federal Facility Agreement and Consent Order. The primary UGTA objective is to gather data to characterize the groundwater aquifers beneath the NTS and adjacent lands. The investigations proposed under the UGTA program may involve the drilling and sampling of new wells; recompletion, monitoring, and sampling of existing wells; well development and hydrologic/ aquifer testing; geophysical surveys; and subsidence crater recharge evaluation. Those wastes generated as a result of these activities will be managed in accordance with existing federal and state regulations, DOE Orders, and NNSA/NV waste minimization and pollution prevention objectives. This Waste Management Plan provides a general framework for all Underground Test Area (UGTA) Project participants to follow for the characterization, storage/accumulation, treatment, and disposal of wastes generated by UGTA Project activities. The objective of this waste management plan is to provide guidelines to minimize waste generation and to properly manage wastes that are produced. Attachment 1 to this plan is the Fluid Management Plan and details specific strategies for management of fluids produced under UGTA operations

  17. Treatment planning systems dosimetry auditing project in Portugal.

    Science.gov (United States)

    Lopes, M C; Cavaco, A; Jacob, K; Madureira, L; Germano, S; Faustino, S; Lencart, J; Trindade, M; Vale, J; Batel, V; Sousa, M; Bernardo, A; Brás, S; Macedo, S; Pimparel, D; Ponte, F; Diaz, E; Martins, A; Pinheiro, A; Marques, F; Batista, C; Silva, L; Rodrigues, M; Carita, L; Gershkevitsh, E; Izewska, J

    2014-02-01

    The Medical Physics Division of the Portuguese Physics Society (DFM_SPF) in collaboration with the IAEA, carried out a national auditing project in radiotherapy, between September 2011 and April 2012. The objective of this audit was to ensure the optimal usage of treatment planning systems. The national results are presented in this paper. The audit methodology simulated all steps of external beam radiotherapy workflow, from image acquisition to treatment planning and dose delivery. A thorax CIRS phantom lend by IAEA was used in 8 planning test-cases for photon beams corresponding to 15 measuring points (33 point dose results, including individual fields in multi-field test cases and 5 sum results) in different phantom materials covering a set of typical clinical delivery techniques in 3D Conformal Radiotherapy. All 24 radiotherapy centers in Portugal have participated. 50 photon beams with energies 4-18 MV have been audited using 25 linear accelerators and 32 calculation algorithms. In general a very good consistency was observed for the same type of algorithm in all centres and for each beam quality. The overall results confirmed that the national status of TPS calculations and dose delivery for 3D conformal radiotherapy is generally acceptable with no major causes for concern. This project contributed to the strengthening of the cooperation between the centres and professionals, paving the way to further national collaborations. Copyright © 2013 Associazione Italiana di Fisica Medica. Published by Elsevier Ltd. All rights reserved.

  18. BODIES OF KNOWLEDGE IN PROJECT MANAGEMENT AND PROJECT QUALITY MANAGEMENT

    Directory of Open Access Journals (Sweden)

    Tamara Gvozdenovic

    2008-03-01

    Full Text Available One of the main trends is standardization of project management. Some of the most important bodies of knowledge in project management, which were created by professional associations for project management are given in this paper. The main of the project management, apart from minimization of time, resources and costs, is to finish the project in the required quality, i.e. it is very important during the whole process of project management to provide realizing the project without any deviations from the previously set quality standards. Basic processes of project quality management are: quality planning, quality assurance and quality control.

  19. DEVELOPMENT OF SCIENCE PROCESS SKILLS STUDENTS WITH PROJECT BASED LEARNING MODEL- BASED TRAINING IN LEARNING PHYSICS

    Directory of Open Access Journals (Sweden)

    Ratna Malawati

    2016-06-01

    Full Text Available This study aims to improve the physics Science Process Skills Students on cognitive and psychomotor aspects by using model based Project Based Learning training.The object of this study is the Project Based Learning model used in the learning process of Computationa Physics.The method used is classroom action research through two learning cycles, each cycle consisting of the stages of planning, implementation, observation and reflection. In the first cycle of treatment with their emphasis given training in the first phase up to third in the model Project Based Learning, while the second cycle is given additional treatment with emphasis discussion is collaboration in achieving the best results for each group of products. The results of data analysis showed increased ability to think Students on cognitive and Science Process Skills in the psychomotor.

  20. 300 Area Revitalization Project Management Plan

    International Nuclear Information System (INIS)

    Downey, H. D.

    1999-01-01

    The 300 Area Revitalization Team has been tasked with the responsibility to develop an integrated path forward for the 300 Area, as part of a commitment stemming from the 300 Area Disposition Workshop that was held on March 17, 1998. The integrated path forward that is needed must ensure that budget, schedule, and work scopes are complementary between the Programs that are involved in the 300Area. This Project Management Plan (PMP) defines the roles and responsibilities, and the overall approach, to development of a prioritized schedule for 300 Area activities that will achieve the end-state condition