WorldWideScience

Sample records for program installer licensing

  1. 24 CFR 3286.203 - Installation license required.

    Science.gov (United States)

    2010-04-01

    ... performance of the installation work in compliance with the requirements of this part. (3) A license is not required for individuals working as direct employees of a licensed installer or for the company that... and competent performance of all employees working under the licensed installer's supervision and for...

  2. Licensing of away-from-reactor (AFR) installations

    International Nuclear Information System (INIS)

    Gray, P.L.

    1980-01-01

    Storage of spent fuel at Away-From-Reactor (AFR) installations will allow reactors to continue to operate until reprocessing or other fuel disposal means are available. AFR installations must be licensed by the Nuclear Regulatory Commission (NRC). Although wide experience in licensing reactors exists, the licensing of an AFR installation is a relatively new activity. Only one has been licensed to date. This paper delineates the requirements for licensing an AFR installation and projects a licensing schedule. Because the NRC is developing specific AFR requirements, this schedule is based primarily on draft NRC documents. The major documents needed for an AFR license application are similar to those for a reactor. They include: a Safety Analysis Report (SAR), and Environmental Report (ER), safeguards and security plans, decommissioning plans, proposed technical specifications, and others. However, the licensing effort has one major difference in that for AFR installations it will be a one-step effort, with follow-up, rather than the two-step process used for reactors. The projected licensing schedule shows that the elapsed time between filing an application and issuance of a license will be about 32 months, assuming intervention. The legal procedural steps will determine the time schedule and will override considerations of technical complexity. A license could be issued in about 14 months in the absence of intervention

  3. Relevant aspects in licensing of radioactive installations at petroleum and gas well logging

    International Nuclear Information System (INIS)

    Miranda, Marcia Valeria da E. Sa

    2002-01-01

    The importance of the various factors considered during the process of licensing of radioactive installation for petroleum and gas well logging. This process involves the issuing of some public power acts, the co called Administrative Acts. For the radioactive installations the Administrative Acts are related to the Norm CNEN-NE-6.02 'Licensing of Radioactive Installation'. In the conduction of the licensing of radioactive installation of mobile nuclear measurement devices the safety evaluation of radioactive installation and equipment containing incorporated radiation source are included; certification of radioprotection supervisors; programing and evaluation of the radioprotection inspections; and the conduction of conformal inspection according to the project, safety analysis and audits. An evaluation of the impact of the importance grade attributed to each factor in the optimization of licensing process is related. Finally, the prediction of implantation of a control system for the displacement of radioactive sources in the installation is approached comprehending the up-to-date localization of each source at different work front of the Basis

  4. Development regulation regarding with licensing of nuclear installation

    International Nuclear Information System (INIS)

    Bambang Riyono; Yudi Pramono; Dahlia Cakrawati Sinaga

    2011-01-01

    Provisions of Article 17 paragraph (3) of Law Number 10 Year 1997 on Nuclear cleary mandates for the establishment of government regulations (GR) on Nuclear licensing containing the requirements and procedure, both from the standpoint of their utilization and installation. To use has been rising GR No.29 Year 2008 on the Use of Ionizing Radiation Sources and Nuclear Materials, while for the installation has been published PP No.43 Year 2006 on Nuclear Reactor Licensing, and BAPETEN Chairman Decree No.3 Year 2006 on Non-reactor Nuclear Installation Licensing. Based on the background of the preparation of both the aforementioned are just regulate the reactor and utilization, not yet fully meet the mandate of Article 17 paragraph (3) of Law No.10 of 1997 on Nuclear, including other nuclear installations. For these reasons, it initiated the need for a separate regulation containing provisions concerning licensing of non-reactor nuclear installations. On the other side from the understanding the legal aspects and interpretations of the Law No.10 of 2004 on the Establishment Regulation Legislation, should be in single mandate of Article 17 paragraph (3) of Law No.10 of 1997 on Nuclear would only produce one of the requirements and procedure for the use or installation, or a maximum of two (2) GR related licensing the use and installation. This is encourages conducted the assessing or studies related to how possible it is according to the legal aspect is justified to combine in one Nuclear licensing regulations regarding both the use and installation, by looking at the complexity of installation and wide scope of utilization of nuclear energy in Indonesia. The results of this paper is expected to provide input in the preparation of GR on licensing of nuclear installations. (author)

  5. Licensing system for primary category radioactive installations

    International Nuclear Information System (INIS)

    Ramirez Riquelme, Angelica Beatriz

    1997-01-01

    The development of a licensing system for primary category radioactive installations is described, which aims to satisfy the needs of the Chilean Nuclear Energy Commission's Department of Nuclear and Radiological Safety, particularly the sections for Licensing Outside Radioactive Installations and Safety Control. This system involves the identification, control and inspection of the installations, their personnel and connected activities, for the purpose of protecting the population's health and the environment. Following the basic cycle methodology, a systems analysis and engineering stage was prepared, establishing the functions of the system's elements and defining the requirements, based on interviews with the users. This stage was followed by the design stage, focusing on the data structure, the software architecture and the procedural detail. The codification stage followed, which translated the design into legible machine-readable format. In the testing stage, the entries that were defined were proven to produce the expected data. Finally and operational and maintenance stage was developed, when the system was installed and put to use. All the above generated a useful system for the Licensing section of the Department of Nuclear and Radiological Safety, since it provides faster and easier access to information. A project is described that introduces new development tools in the Computer department following standards established by the C.CH.E.N. (author)

  6. Licensing of nuclear and radioactive installations in Peru

    International Nuclear Information System (INIS)

    Medina Gironzini, E.

    1987-01-01

    In Peru, the Regulation for Ionizing Radiation Sources is applied, which establishes the norms and procedures to follow in the nuclear and radioactive installations of the country in order to assure their correct operation as concerns to the nuclear safety and radiological protection, allowing the emission of the respective licenses. As for the nuclear facilities, this authorization includes the Previous License, the Construction License and the Operation License (provisional and definitive) and for radioactive facilities and equipment generating ionizing radiations: the Construction License and the Operation License. The personnel also require a license that can be an operator license (as for nuclear reactors) or a supervisor license (for nuclear and radioactive facilities). In spite of the above mentioned regulation and its long enforcement period, less than 10% of radioactive facilities in this country are licensed, due to different problems which will be solved in the medium term. (Author)

  7. Nuclear relevant installations licensing methodology in the Argentine Republic

    International Nuclear Information System (INIS)

    Paganini, C.E.

    1986-01-01

    A review of the requeriments of the Nuclear Installations Advisory Committee on Licensing (CALIN) from the nuclear security point of view, is presented. The methodology applied by the CALIN for the licensing in the Argentine Republic is included as well as codes, standards of applications and the interaction between the licensing Authority and the Responsible Entity during the whole process. Finally, the Atucha II nuclear power plant's licensing, in construction at present, is explained and the standard, of the licensing schedule, is presented graphically. (author) [es

  8. Licensing systems and inspection of nuclear installations

    International Nuclear Information System (INIS)

    1991-01-01

    The first study analysing the regulations governing the licensing and inspection of nuclear installations in OECD countries was published by OECD/NEA in 1980, and revised in 1986. Since then there have been amendments to national regulations on the subject, which have warranted updating of this publication. This new study provides a description of the licensing regulations and practices applied in the twenty OECD countries with provisions in that field. The national systems have been described according to a standard format to make comparisons and research easier. In most cases, the descriptions are supplemented by flow charts illustrating the procedures and specifying the different authorities involved in the licensing procedures [fr

  9. 47 CFR 24.711 - Installment payments for licenses for frequency Block C.

    Science.gov (United States)

    2010-10-01

    ... Block C. 24.711 Section 24.711 Telecommunication FEDERAL COMMUNICATIONS COMMISSION (CONTINUED) COMMON....711 Installment payments for licenses for frequency Block C. Installment payments. Each eligible licensee of frequency Block C may pay the remaining 90 percent of the net auction price for the license in...

  10. 47 CFR 24.716 - Installment payments for licenses for frequency Block F.

    Science.gov (United States)

    2010-10-01

    ... Block F. 24.716 Section 24.716 Telecommunication FEDERAL COMMUNICATIONS COMMISSION (CONTINUED) COMMON....716 Installment payments for licenses for frequency Block F. Installment Payments. Each eligible licensee of frequency Block F may pay the remaining 80 percent of the net auction price for the license in...

  11. Postulated licensing schedule for an independent spent-fuel-storage installation

    International Nuclear Information System (INIS)

    Ludwick, J.D.

    1982-11-01

    A review of licensing requirements, processes, and anticipated actions for independent spent fuel storage installations (ISFSIs) was conducted in order to develop an estimated schedule and sequence of events for licensing a new ISFSI. This estimate will be useful to potential ISFSI owners in planning for the licensing of their facilities. It is concluded that, although many uncertainties exist with respect to such things as legal appeals, about 29 months are estimated to elapse between license application and license issuance for an ISFSI. This estimate is in reasonable agreement with a previous time estimate for licensing an ISFSI, and, taking into account the special circumstances involved, with the actual licensing schedule for the GE-Morris ISFSI. However, individual portions of the licensing schedule from each case studied sometimes vary significantly

  12. A model to survey diagnostic x-ray installations for licensing purpose

    International Nuclear Information System (INIS)

    Dias K, S.; Lassance, A.; Almeida, C.E. de; Cunha G, P.; Oliveira, S.V.; Motta, H.

    1996-01-01

    The process of diagnostic X-ray installations licensing in Rio de Janeiro requires several documents including an inspection report on radiation protection conditions. All the clinics have to renew their license annually. Because of the large amount of such installations, the state authority is unable to accomplish this process adequately. To overcome this problem, a postal system has been proposed to evaluate the radiological protection conditions by appropriate quality and risk indicators. A sample of 195 institutions of diagnostic radiology was chosen randomly. On this voluntary program, only 95 institutions answered the questionnaire sent in the first phase. Those clinics went to the second phase and received a thermoluminescent dosimeter (TLD) kit to be exposed in a lateral chest examination. Only 25% of the examinations were performed using kilo voltages in the range recommended by European Union for quality criteria (100-150 k Vp). Regarding to focus-film distance, about 15% of examination was performed at a distance smaller than 140 cm. High speed film-screen combinations were used in approximately 55% of the institutions. In this survey, patient doses ranged from 0.06 to 4.31 mGy. The third phase included a local inspection of 50 out 95 clinics to compose and test the risk indicators scoring system. These indicators include data on the qualification of the staff, individual monitoring, installation dimensions and layout, conditions of the equipment, maintenance, technique parameters for exams, dose to the patient, and x-ray output. (authors). 2 refs., 3 figs., 1 tab

  13. The work of the OECD Nuclear Energy Agency on safety and licensing of nuclear installations

    International Nuclear Information System (INIS)

    Strohl, P.

    1975-01-01

    The acceleration of nuclear power programmes in OECD Member countries is reflected in the emphasis given by OECD/NEA to its activities in nuclear safety and regulatory matters. Particular effort is devoted to work on radiation protection and radioactive waste management, safety of nuclear installations and nuclear law development. A Committee on the Safety of Nuclear Installations reviews the state of the art and identifies areas for research and co-ordination of national programmes. A Sub-Committee on Licensing collates information and data on licensing standards and practices of different countries with a view to considering problems of common interest. Comparative studies of various licensing systems and discussions between licensing authorities should help to improve regulatory control of nuclear installations for which there appears to be a need for internationally accepted standards in the long run. (author)

  14. 24 CFR 3286.207 - Process for obtaining installation license.

    Science.gov (United States)

    2010-04-01

    ... installation license must submit verification of the experience required in § 3286.205(a). This verification may be in the form of statements by past or present employers or a self-certification that the applicant meets those experience requirements, but HUD may contact the applicant for additional verification...

  15. Relevant aspects in licensing of radioactive installations at petroleum and gas well logging; Aspectos relevantes no licenciamento de instalacoes radiativas em perfilagem de pocos de petroleo ou gas

    Energy Technology Data Exchange (ETDEWEB)

    Miranda, Marcia Valeria da E. Sa [Comissao Nacional de Energia Nuclear (CNEN), Rio de Janeiro, RJ (Brazil)

    2002-07-01

    The importance of the various factors considered during the process of licensing of radioactive installation for petroleum and gas well logging. This process involves the issuing of some public power acts, the co called Administrative Acts. For the radioactive installations the Administrative Acts are related to the Norm CNEN-NE-6.02 'Licensing of Radioactive Installation'. In the conduction of the licensing of radioactive installation of mobile nuclear measurement devices the safety evaluation of radioactive installation and equipment containing incorporated radiation source are included; certification of radioprotection supervisors; programing and evaluation of the radioprotection inspections; and the conduction of conformal inspection according to the project, safety analysis and audits. An evaluation of the impact of the importance grade attributed to each factor in the optimization of licensing process is related. Finally, the prediction of implantation of a control system for the displacement of radioactive sources in the installation is approached comprehending the up-to-date localization of each source at different work front of the Basis.

  16. Implantation of licensing norm for industrial radiography installations - Norm CNEN-NE-604 Rev.1

    International Nuclear Information System (INIS)

    Heilbron Filho, P.F.L.; Oliveira, S.M.V. de.

    1988-04-01

    The results of audits carried out by DIN/CNEN (Department of Nuclear Installations) in firms of Rio de Janeiro and Sao Paulo, Brazil, that use industrial radiography for implantation of the norm of installation licensing, are presented. (M.C.K.) [pt

  17. Conceptual Design of On-line Based Licensing Review and Assesment System of Nuclear Installations and Nuclear Materials ('PRIBEN')

    International Nuclear Information System (INIS)

    Melani, Ai; Chang, Soon Heung

    2008-01-01

    At the present Indonesia has no nuclear power plant in operation yet, although it is expected that the first nuclear power plant will be operated and commercially available in around the year of 2016 to 2017 in Muria Peninsula. There are only three research reactors, one nuclear fuel fabrication plant for research reactors, and one experimental fuel fabrication plant for nuclear power, one isotope production facility and some other research facilities. All the facility is under Nuclear Energy Regulatory Agency (BAPETEN) controlling through regulation, licensing and inspection. The organizations operation submits licensing application to BAPETEN before utilizing the facility. According to the regulation before BAPETEN give license they perform review and assessment for the utility application. Based on the review and assessment result, BAPETEN may stipulate, reject, delay or terminate the license. In anticipation of expansion of the nuclear program in Indonesia, BAPETEN should have an integrated and updated system for review and asses the licensing application. For this reason, an expert system for the review and asses the licensing application, so-called PRIBEN (Perizinan Reaktor, Instalasi dan Bahan Nuklir/Licensing of Reactor, Nuclear Installations and Nuclear Materials), is developed which runs on the online-based reality environment

  18. Licensing for industrial gamma and X-ray radiography installation in Peru

    International Nuclear Information System (INIS)

    Medina G, E.

    1988-01-01

    According the regulations for ionizing radiation source installations an application to the Peruvian National Authority should be forwarded in order to get the construction on operation license both industrial gamma and X-ray. Radiography is considered as well as personnel aspects. The proceedings are described

  19. Effective legal protection in the licensing of technical installations

    International Nuclear Information System (INIS)

    Froehler, L.

    1987-01-01

    Undeterminate concepts of law shall match the dynamism of technical progress in licensing technical installations (e.g. section 7, para. 2 no. 3 Atomic Energy Act). The administration and the courts have the duty to equalize normative deficits of regulation. Decrees and administrative provisions have an important impact. Administrative courts shall exercise legal protection more efficiently what e.g. can be possible after a shortening of stages of appeal. (CW) [de

  20. 78 FR 70077 - Issuance of Materials License for U.S. Army Installation Management Command

    Science.gov (United States)

    2013-11-22

    ... the Hilo Campus of the University of Hawaii on the island of Hawaii. On February 24, 2010, the ASLB... installations in Hawaii. The Army informed the NRC in November 2006 that it had discovered DU fragments at the... Barracks and Pohakuloa Training Area installations in Hawaii. Materials License SUC-1593 authorizes...

  1. Licensing systems and inspection of nuclear installations in NEA Member countries. Part 1, Description of licensing systems

    International Nuclear Information System (INIS)

    1977-01-01

    This study provides an assessment of the legislative and regulatory provisions applicable and of the practices followed in the countries concerned and is divided into two separate sections. This document is the first part only. It contains the description of national licensing and inspection systems for nuclear installations in the twenty OECD countries which have specific regulations in this field. Each analysis has been presented following a plan which is as standardised as possible so as to facilitate comparison between the national systems. Part II, which is not included in this document, contains the diagrams illustrating the steps in the licensing procedure and the duties of the bodies involved as well as certain additional documents. It also includes a table showing the sequence of the main steps in the licensing process in the countries covered by this Study

  2. Scallop License Limitation Program (SLLP) Permit Program

    Data.gov (United States)

    National Oceanic and Atmospheric Administration, Department of Commerce — A federal Scallop License Limitation Program (SLLP) license is required onboard any vessel deployed in scallop fisheries in Federal waters off Alaska (except for...

  3. Lifetime Management Programs as a basis for the long term operation of nuclear installations

    Energy Technology Data Exchange (ETDEWEB)

    López González, Manuel; Lobato Galeote, Carlos, E-mail: mlopezg@idom.com, E-mail: carlos.lobato@idom.com [IDOM - Consulting, Engineering & Architecture SAU, Madrid (Spain)

    2017-07-01

    From the licensing standpoint there are several approaches worldwide to obtain an authorization to operate a NPP beyond its design life. According to the License Renewal Application (LRA) approach, followed in the United States of America and another countries, plants need to develop a Life Time Management Program (LTMP) with which manage the potential aging processes (corrosion, erosion, erosion-corrosion, radiation and thermally induced embrittlement, fatigue, corrosion fatigue, creep, binding and wear) associated to the Structures, Systems and Components. A LTMP is composed of several tasks which represents a technical challenge for a nuclear installation. (author)

  4. Lifetime Management Programs as a basis for the long term operation of nuclear installations

    International Nuclear Information System (INIS)

    López González, Manuel; Lobato Galeote, Carlos

    2017-01-01

    From the licensing standpoint there are several approaches worldwide to obtain an authorization to operate a NPP beyond its design life. According to the License Renewal Application (LRA) approach, followed in the United States of America and another countries, plants need to develop a Life Time Management Program (LTMP) with which manage the potential aging processes (corrosion, erosion, erosion-corrosion, radiation and thermally induced embrittlement, fatigue, corrosion fatigue, creep, binding and wear) associated to the Structures, Systems and Components. A LTMP is composed of several tasks which represents a technical challenge for a nuclear installation. (author)

  5. Groundfish/Crab License Limitation Program (LLP) Permit Program

    Data.gov (United States)

    National Oceanic and Atmospheric Administration, Department of Commerce — As of January 1, 2000 a Federal License Limitation Program (LLP) license is required for vessels participating in directed fishing for LLP groundfish species in the...

  6. Licensing system for primary category radioactive installations; Sistema de licenciamiento de instalciones radiactivas de primera categoria

    Energy Technology Data Exchange (ETDEWEB)

    Ramirez Riquelme, Angelica Beatriz

    1998-12-31

    The development of a licensing system for primary category radioactive installations is described, which aims to satisfy the needs of the Chilean Nuclear Energy Commission`s Department of Nuclear and Radiological Safety, particularly the sections for Licensing Outside Radioactive Installations and Safety Control. This system involves the identification, control and inspection of the installations, their personnel and connected activities, for the purpose of protecting the population`s health and the environment. Following the basic cycle methodology, a systems analysis and engineering stage was prepared, establishing the functions of the system`s elements and defining the requirements, based on interviews with the users. This stage was followed by the design stage, focusing on the data structure, the software architecture and the procedural detail. The codification stage followed, which translated the design into legible machine-readable format. In the testing stage, the entries that were defined were proven to produce the expected data. Finally and operational and maintenance stage was developed, when the system was installed and put to use. All the above generated a useful system for the Licensing section of the Department of Nuclear and Radiological Safety, since it provides faster and easier access to information. A project is described that introduces new development tools in the Computer department following standards established by the C.CH.E.N. (author) Dissertation to obtain the degree of Computing and Informatics Engineer; 10 refs., 48 figs., 34 tabs.

  7. Decree No. 83/7405 of 18 November 1983 on the licensing procedure for nuclear installations

    International Nuclear Information System (INIS)

    1983-01-01

    This Decree (No. 83/7405) on the licensing procedure for nuclear installations came into force on 19 December 1983 and supersedes Decree No. 7/9141 of 5 December 1974 on the same subject. The general lines of the licensing procedure laid down by this new Decree are similar to that provided by the 1979 Decree; it is also carried out in three stages: site, construction and operating licences are delivered in succession. (NEA) [fr

  8. Public information and licensing procedures for nuclear installations. European experience

    International Nuclear Information System (INIS)

    Mayoux, J.C.; Chevillard, F.; Mutschler, U.; Stubbe, C.

    1981-10-01

    This paper reviews the licensing procedures for nuclear installations in various European countries and examines the form, content and methods selected for information and consultation of the public. The author stresses the importance of this stage in the procedure, both for the nuclear operator and the public authorities, given the population's concern about the environment. He concludes that, irrespective of its complexity, the nuclear field cannot remain the concern of a few initiates competent to take decisions and that, consequently, this implies creation of new information systems to meet the public's desire to participate more directly in the process. (NEA) [fr

  9. The activities of the Technical Independent Supervision Organization (OSTI) on the licensing process of the nucleoelectric installations

    International Nuclear Information System (INIS)

    1993-01-01

    The basic responsibility for licensing nuclear facilities belongs to the government to urban is up to take care of the safety and public health as well as for the installations environment impact. In practicing such responsibility the government should be assured that the operational safety and nucleoelectric installation construction has to be subjected to checks and controls by an independent organism apart from the owners organization responsible for the construction and operation. This paper presents the main activities of the technical independent supervision organization in conformity with the regulations for the licensing process of nuclear facilities as one of the safety principles adopted for Angra 2 nuclear power plant. (B.C.A.)

  10. Semi-annual report of the licensing program - July to December 1988

    International Nuclear Information System (INIS)

    Anon.

    1989-01-01

    The main activities developed and described are: licensing of CIPC (FSAR), emergency plan of NUCLEI, reevaluation of the maximum credible accident of NUCLEI, updating of the safety analysis report of CDTN, emergency plan of IPR-R1 reactor and licensing of the DIENR.CN. installations. (E.G.) [pt

  11. DESIGN AND LICENSING TRENDS OF THE GENERAL EDUCATIONAL PROGRAMS IN LATVIA

    OpenAIRE

    Mihailovs, Ivans Jānis; Krūmiņa, Aira Aija

    2016-01-01

    The general education program designing and licensing trends in Latvia in the period from 2010 to 2014 are analyzed in the article. Based on the general education program licensing data, it found that there isn’t a trend to license author’s program in primary education, while the secondary level of education author's programs are designed and licensed more often. The fact that primary education is more licensed programs in mathematics, science and technology, but in general secondary educatio...

  12. Effectiveness of Oregon's teen licensing program : final report.

    Science.gov (United States)

    2008-06-01

    Significant changes in Oregons teen licensing laws went into effect on March 1, 2000. The new laws expanded the provisional driving license program which had been in effect since October 1989 and established a graduated driver licensing (GDL) prog...

  13. Nuclear Installations Act 1965

    International Nuclear Information System (INIS)

    1965-01-01

    This Act governs all activities related to nuclear installations in the United Kingdom. It provides for the licensing procedure for nuclear installations, the duties of licensees, the competent authorities and carriers of nuclear material in respect of nuclear occurrences, as well as for the system of third party liability and compensation for nuclear damage. The Act repeals the Nuclear Installations (Licensing and Insurance) Act 1959 and the Nuclear Installations (Amendment Act) 1965 except for its Section 17(2). (NEA) [fr

  14. License renewal demonstration program: NRC observations and lessons learned

    International Nuclear Information System (INIS)

    Prato, R.J.; Kuo, P.T.; Newberry, S.F.

    1996-12-01

    This report summarizes the Nuclear Regulatory Commission staff's observations and lessons learned from the five License Renewal Demonstration Program (LRDP) site visits performed by the staff from March 25, 1996, through August 16, 1996. The LRDP was a Nuclear Energy Institute (NEI) program intended to assess the effectiveness of the guidance provided by NEI 95-10, Revision 0, open-quotes Industry Guideline for Implementing the Requirements of 10 CFR Part 54 - The License Renewal Rule,close quotes to implement the requirements of Title 10 of the Code of Federal Regulations, Part 54 (10 CFR Part 54), open-quotes Requirements for Renewal of Operating Licenses for Nuclear Power Plants.close quotes In general, NEI 95-10 appeared to contain the basic guidance needed for scoping, screening, identifying aging effects, developing aging management programs, and performing time-limited aging analyses. However, inconsistent implementation of this guidance in some areas was an indication that clarification of existing guidance and/or the inclusion-of some new guidance may be needed for applicants to develop a license renewal program that is consistent with the intent of the rule

  15. Optimal installation program for reprocessing plants

    International Nuclear Information System (INIS)

    Kubokawa, Toshihiko; Kiyose, Ryohei

    1976-01-01

    Optimization of the program of installation of reprocessing plants is mathematically formulated as problem of mixed integer programming, which is numerically solved by the branch-and-bound method. A new concept of quasi-penalty is used to obviate the difficulties associated with dual degeneracy. The finiteness of the useful life of the plant is also taken into consideration. It is shown that an analogous formulation is possible for the cases in which the demand forecasts and expected plant lives cannot be predicted with certainty. The scale of the problem is found to have kN binary variables, (k+2)N continuous variables, and (k+3)N constraint conditions, where k is the number of intervals used in the piece-wise linear approximation of a nonlinear objective function, and N the overall duration of the period covered by the installation program. Calculations are made for N=24 yr and k=3, with the assumption that the plant life is 15 yr, the plant scale factor 0.5, and the maximum plant capacity 900 (t/yr). The results are calculated and discussed for four different demand forecasts. The difference of net profit between optimal and non-optimal installation programs is found to be in the range of 50 -- 100 M$. The pay-off matrix is calculated, and the optimal choice of action when the demand cannot be forecast with certainty is determined by applying Bayes' theory. The optimal installation program under such conditions of uncertainty is obtained also with a stochastic mixed integer programming model. (auth.)

  16. Nuclear law and environmental law in the licensing of nuclear installations

    International Nuclear Information System (INIS)

    Raetzke, Christian

    2013-01-01

    Large nuclear installations can have a considerable impact on the environment, both in actual terms, due to the construction and operation of the plant and in potential terms, related to the risk of an accident. A considerable part of the multiple authorisation processes required to develop a large nuclear project is devoted to addressing the possible impact on the environment. Accordingly, environmental protection is not only warranted by requirements and processes arising out of what is generally considered 'environmental law', but also by laws governing the design, siting, construction and operation of nuclear installations. By ensuring prevention and control of radiation releases to the environment, the aspects of nuclear law governing the design, construction, operation and decommissioning of nuclear facilities pertain to the field of environmental protection just like other fields of environmental law. The perception of the public that nuclear energy is 'anti-environmental' and the generally antinuclear stance of environmental non-governmental organisations (NGOs) should not deflect attention from the fact that protection of the environment is one of the main functions of the body of nuclear law. In this article, the general relationship between the law governing civil nuclear installations and environmental law will be analysed. The subsequent chapters will deal with environmental requirements and procedures as part of the authorisation process for a nuclear installation. The role of public participation and the involvement of neighbouring states in the licensing process will also be investigated, as they are today mainly based on environmental law. Some other aspects which may also have some relation to environmental protection, such as waste management, emergency planning, multinational early notification and assistance in the case of an accident and nuclear liability, have been omitted from discussion as they lie outside the focus of this article

  17. Recommendations for the hydrogeologic review and assessment of sites for nuclear power installations within the framework of the radiation protection licensing procedure

    International Nuclear Information System (INIS)

    Adam, C.; Petschel, M.; Koerner, W.

    1985-01-01

    Article 4 of the Nuclear Facility Licensing Ordinance requires the information to be submitted in support of licensing applications for nuclear power installations to include an expertise on the hydrogeologic characteristics of the site environment with main emphasis on the movement of radionuclides through groundwater in the event of accident conditions, and on measures to protect ground and surface waters. Recommendations are given for the conduct of a hydrogeologic review and assessment process and its timing relative to the individual stages in the licensing procedure. (author)

  18. DOD low energy model installation program

    International Nuclear Information System (INIS)

    Fournier, D.F. Jr.

    1993-01-01

    The Model Low Energy Installation Program is a demonstration of an installation-wide, comprehensive energy conservation program that meets the Department of Defense (DoD) energy management goals of reducing energy usage and costs by at least 20%. It employs the required strategies for meeting these goals, quantifies the environmental compliance benefits resulting from energy conservation and serves as a prototype for DoD wide application. This project will develop both analysis tools and implementation procedures as well as demonstrate the effectiveness of a comprehensive, coordinated energy conservation program based on state-of-the-art technologies. A military installation is in reality a small to medium sized city. It generally has a complete utilities infrastructure including water supply and distribution, sewage collection and treatment, electrical supply and distribution, central heating and cooling plants with thermal distribution, and a natural gas distribution system. These utilities are quite extensive and actually consume about 10-15% of the energy on the facility not counting the energy going into the central plants

  19. Status of the Monticello nuclear generating plant lead plant license renewal program

    International Nuclear Information System (INIS)

    Pickens, T.A.

    1992-01-01

    In 1988, the Monticello nuclear generating plant was chosen by the US Department of Energy through Sandia National Laboratories and the Electric Power Research Institute to serve as the lead boiling water reactor in the lead plant license renewal program. The purpose of the lead plant license renewal program is to provide insights during the development of and to demonstrate the license renewal regulatory process with the US Nuclear Regulatory Commission (NRC). The work being performed in three phases: (1) preparation of the technical basis for license renewal; (2) development of the technical basis into a formal license renewal application; and (3) review of the application by the NRC. This paper discusses the systems and structures identified as important to license renewal in accordance with 10CFR54 as well as the plant documents and programs that were used in going through the identification process. The systems and structures important to license renewal will then provide insights into how structures and components were identified that are required to be evaluated for aging, the elements of the aging evaluations, and the effective programs used to manage potentially significant aging

  20. U.S. regulatory requirements for nuclear plant license renewal: The B and W Owners Group License Renewal Program

    International Nuclear Information System (INIS)

    Staudinger, Deborah K.

    2004-01-01

    This paper discusses the current U.S. Regulatory Requirements for License Renewal and describes the Babcock and Wilcox Owners Group (B and WOG) Generic License Renewal Program (GLRP). The B and W owners, recognizing the need to obtain the maximum life for their nuclear generating units, embarked on a program to renew the licenses of the seven reactors in accordance with the requirements of the Atomic Energy Act of 1954 and further defined by Title 10 of the Code of Federal Regulation Part 54 (10 CFR 54). These reactors, owned by five separate utilities, are Pressurized Water Reactors (PWR) ranging in net rated capacity from approximately 800 to 900 MW. The plants, predominately constructed in the 70s, have USNRC Operating Licenses that expire between 2013 to 2017. (author)

  1. Alpena Community College Commercial Driver's License Program. Evaluation Summary.

    Science.gov (United States)

    Alpena Community Coll., MI.

    The Alpena Community College (ACC) Drivers Education Program was developed to deliver a basic skills program providing specific job-related basic skills instruction to approximately 300 workers throughout Michigan who desired to pass the Commercial Drivers License (CDL) examination. Other program goals were to establish greater partnerships…

  2. Demarcation of the licensing and supervisory procedures for nuclear engineering installations

    International Nuclear Information System (INIS)

    Schattke, H.

    1986-01-01

    The remarks can be summed up under 12 points: 1) The protective purpose outlined in Paragraph 1 No. 2 of the Atomic Energy Law is the top priority for both licensing and regulatory authorities. 2) Both authorities must aim at the best possible prevention of hazards and precautions against risks. 3) The licensing procedures cover applications for licenses, the regulatory procedures check and supervise actual activities. 4) The licensing procedures take precedence in chronology and in substance over the regulatory procedure. 5) The licensing procedure is a preliminary check on the intention to carry out nuclear activities before the event; whereas the regulatory procedure controls the licensee after the event to ensure that the latter's activities really do conform to the framework laid down in the license. 6) The licensing procedure must be verified by state supervision with regard to its prognostic activity. 7) The examination criteria are largely identical for both the authorites. 8) The examination tools for the licensing and regulatory authorities also coincide to a large extent. Legal differences in the possible means of enforcement have no effect in practice. 9) Decisions made by either authority can be either in the licensee's favour or to its disadvantage. Nevertheless, the contents of decisions differ widely between the two authorities. 10) The regulatory authorities execute and prepare the decisions of the licensing authorites. 11) Licensing decisions can be designated static/prognostic, whereas regulatory measures accompany the actual performance of the plant and the operating personnel in a dynamic/controlling manner. 12) Regulatory instructions are usually of a temporary nature, whereas licensing actions are permanent as a rule. (orig.) [de

  3. Regulations concerning licensing of nuclear reactor facilities and other nuclear installations, Decree No 7/9141, 6 January 1975

    International Nuclear Information System (INIS)

    1975-01-01

    This Decree lays down the licensing system for nuclear installations in Turkey and also sets up a Nuclear Safety Committee whose duty is to ensure that the requirements of this Decree are met. The Committee is made up of members of the Atomic Energy Commission specialized in reactors, nuclear safety, health physics, reactor physics as well as two experts respectively appointed by the Ministry of Health and Social Welfare and the Ministry of Energy and National Resources. (NEA) [fr

  4. Decentralization of operating reactor licensing reviews: NRR Pilot Program

    International Nuclear Information System (INIS)

    Hannon, J.N.

    1984-07-01

    This report, which has incorporated comments received from the Commission and ACRS, describes the program for decentralization of selected operating reactor licensing technical review activities. The 2-year pilot program will be reviewed to verify that safety is enhanced as anticipated by the incorporation of prescribed management techniques and application of resources. If the program fails to operate as designed, it will be terminated

  5. Consolidated guidance about materials licenses: Program-specific guidance about portable gauge licenses. Final report; Volume 1

    Energy Technology Data Exchange (ETDEWEB)

    Vacca, P.C.; Whitten, J.E.; Pelchat, J.M.; Arredondo, S.A.; Matson, E.R.; Lewis, S.H.; Collins, D.J.; Santiago, P.A. [Nuclear Regulatory Commission, Washington, DC (United States). Div. of Industrial and Medical Nuclear Safety; Tingle, W. [Dept. of Environment, Health, and Natural Resources, Raleigh, NC (United States). Div. of Radiation Protection

    1997-05-01

    As part of its redesign of the materials licensing process, NRC is consolidating and updating numerous guidance documents into a single comprehensive repository as described in NUREG-1539 and draft NUREG-1541. NUREG-1556, Vol. 1, is the first program-specific guidance developed for the new process and will serve as a template for subsequent program-specific guidance. This document is intended for use by applicants, licensees, and NRC staff and will also be available to Agreement States. This document supersedes the guidance previously found in draft Regulatory Guide DG-0008, ``Applications for the Use of Sealed Sources in Portable Gauging Devices,`` and in NMSs Policy and guidance Directive 2-07, ``Standard Review Plan for Applications for Use of Sealed Sources in Portable Gauging Devices.`` This final report takes a more risk-informed, performance-based approach to licensing portable gauges, and reduces the information(amount and level of detail) needed to support an application to use these devices. It incorporates many suggests submitted during the comment period on draft NUREG-1556, Volume 1. When published, this final report should be used in preparing portable gauge license applications. NRC staff will use this final report in reviewing these applications.

  6. Consolidated guidance about materials licenses: Program-specific guidance about portable gauge licenses. Final report; Volume 1

    International Nuclear Information System (INIS)

    Vacca, P.C.; Whitten, J.E.; Pelchat, J.M.; Arredondo, S.A.; Matson, E.R.; Lewis, S.H.; Collins, D.J.; Santiago, P.A.; Tingle, W.

    1997-05-01

    As part of its redesign of the materials licensing process, NRC is consolidating and updating numerous guidance documents into a single comprehensive repository as described in NUREG-1539 and draft NUREG-1541. NUREG-1556, Vol. 1, is the first program-specific guidance developed for the new process and will serve as a template for subsequent program-specific guidance. This document is intended for use by applicants, licensees, and NRC staff and will also be available to Agreement States. This document supersedes the guidance previously found in draft Regulatory Guide DG-0008, ''Applications for the Use of Sealed Sources in Portable Gauging Devices,'' and in NMSs Policy and guidance Directive 2-07, ''Standard Review Plan for Applications for Use of Sealed Sources in Portable Gauging Devices.'' This final report takes a more risk-informed, performance-based approach to licensing portable gauges, and reduces the information(amount and level of detail) needed to support an application to use these devices. It incorporates many suggests submitted during the comment period on draft NUREG-1556, Volume 1. When published, this final report should be used in preparing portable gauge license applications. NRC staff will use this final report in reviewing these applications

  7. Assessment of specialized educational programs for licensed nuclear reactor operators

    International Nuclear Information System (INIS)

    Melber, B.D.; Saari, L.M.; White, A.S.; Geisendorfer, C.L.; Huenefeld, J.C.

    1986-02-01

    This report assesses the job-relatedness of specialized educational programs for licensed nuclear reactor operators. The approach used involved systematically comparing the curriculum of specialized educational programs for college credit, to academic knowledge identified as necessary for carrying out the jobs of licenses reactor operators. A sample of eight programs, including A.S. degree, B.S. degree, and coursework programs were studied. Subject matter experts in the field of nuclear operations curriculum and training determined the extent to which individual program curricula covered the identified job-related academic knowledge. The major conclusions of the report are: There is a great deal of variation among individual programs, ranging from coverage of 15% to 65% of the job-related academic knowledge. Four schools cover at least half, and four schools cover less than one-third of this knowledge content; There is no systematic difference in the job-relatedness of the different types of specialized educational programs, A.S. degree, B.S. degree, and coursework; and Traditional B.S. degree programs in nuclear engineering cover as much job-related knowledge (about one-half of this knowledge content) as most of the specialized educational programs

  8. License renewal - an idea whose time has come. Hatch nuclear plant license renewal program: an actual example of application of the license renewal rule to the Intake Structure

    International Nuclear Information System (INIS)

    Chandiwala, F.; Evans, W.P.

    1999-01-01

    After the NRC issued a revised license renewal rule in May 1995, the nuclear industry focussed on developing generic industry for implementing the rule and testing the guidance through various demonstration programs and work products in conjunction with the NRC. In addition, plant-specific programs also proceeded forward. These activities show that implementation issues continue to exist. Since the issuance of the rule, the NRC has issued a draft standard review plan for license renewal (SRP-LR), working draft, September 1997. Southern Nuclear Operating Company (SNC) has begun development work on a license renewal application for Plant Hatch Units 1 and 2. Plant Hatch Units 1 and 2 are BWR 4, Mark I plants whose operating licenses expire in 2014 and 2018, respectively. The Plant Hatch initiative also involves teaming with other boiling water reactors (BWRs) to develop the license renewal technology within the BWR fleet, and to support Plant Hatch by providing an oversight role for the application process. The teaming effort involved two other utilities, each being assigned to prepare a common report on a mechanical system or a structure. The common report could be presented to the NRC with modifications to suit the individual plants, thereby saving time and money, and hopefully resulting in quicker approval by the NRC. The desired license renewal process end result is a renewed license with up to a 20 year extension (10CFR 54.31(b)). (orig.)

  9. 77 FR 47922 - Publication of General Licenses Related to the Burma Sanctions Program

    Science.gov (United States)

    2012-08-10

    ... DEPARTMENT OF THE TREASURY Office of Foreign Assets Control Publication of General Licenses Related to the Burma Sanctions Program AGENCY: Office of Foreign Assets Control, Treasury. ACTION: Notice, publication of general licenses. [[Page 47923

  10. Department of the Army Installation Restoration Program

    International Nuclear Information System (INIS)

    Anderson, A.W.

    1988-01-01

    The Army's Installation Restoration Program (IRP) was established in 1975 in response to regulatory action at several installations where past disposal practices had caused contamination of streams and groundwater. The need to decontaminate excess Army-owned real estate also was considered in early IRP activities. A variety of site types have been discovered on Army installations. The major site types evaluated to date include: contaminated soil areas, landfills, lagoons, buildings, burning grounds, sumps, pits, storage tanks, sewage treatment plants, storage pads, industrial wastewater treatment plants, and salvage yards. Twenty Army installations have been proposed for or listed on the National Priorities List (NPL). The need for taking action at hazardous waste sites, however, is based on threats they pose to human health, welfare or the environment. Sites do not have to be on the SPL in order to be cleaned up through IRP activities. All of the sites that caused Army installations to be proposed for the NPL are being evaluated and cleaned up. In addition, all Army properties have been or will be assessed and where needed they will be addressed by the IRP

  11. Design, fabrication and installation of irradiation facilities

    Energy Technology Data Exchange (ETDEWEB)

    Sim, Bong Shick; Kim, Y. S.; Lee, C. Y. and others

    1999-03-01

    The principal contents of this project are to design, fabricate and install the steady-state fuel test loop in HANARO for nuclear technology development. Procurement and fabrication of main equipment, licensing and technical review for fuel test loop have been performed during 2 years(1997, 1998) for this project. Following contents are described in the report. - Procurement and fabrication of the equipment, piping for OPS - IPS manufacture - License - Technical review and evaluation of the FTL facility. As besides, as these irradiation facilities will be installed in HANARO, review of safety concern, discussion with KINS for licensing and review ofHANARO interface have been performed respectively. (author)

  12. Licensing systems and inspection of nuclear installations

    International Nuclear Information System (INIS)

    1986-01-01

    The systems of each country member of the OECD is described according to a plan standardised to the extent possible, so as to facilitate comparison between the National systems. In most cases, the descriptions are supplemented by flow charts illustrating the steps in the licensing procedure and the intervention of the various bodies concerned

  13. Dry spent fuel storage licensing

    International Nuclear Information System (INIS)

    Sturz, F.C.

    1995-01-01

    In the US, at-reactor-site dry spent fuel storage in independent spent fuel storage installations (ISFSI) has become the principal option for utilities needing storage capacity outside of the reactor spent fuel pools. Delays in the geologic repository operational date at or beyond 2010, and the increasing uncertainty of the US Department of Energy's (DOE) being able to site and license a Monitored Retrievable Storage (MRS) facility by 1998 make at-reactor-site dry storage of spent nuclear fuel increasingly desirable to utilities and DOE to meet the need for additional spent fuel storage capacity until disposal, in a repository, is available. The past year has been another busy year for dry spent fuel storage licensing. The licensing staff has been reviewing 7 applications and 12 amendment requests, as well as participating in inspection-related activities. The authors have licensed, on a site-specific basis, a variety of dry technologies (cask, module, and vault). By using certified designs, site-specific licensing is no longer required. Another new cask has been certified. They have received one new application for cask certification and two amendments to a certified cask design. As they stand on the brink of receiving multiple applications from DOE for the MPC, they are preparing to meet the needs of this national program. With the range of technical and licensing options available to utilities, the authors believe that utilities can meet their need for additional spent fuel storage capacity for essentially all reactor sites through the next decade

  14. Mid-market transformation programs: programs to promote best practices in system specification and installation

    International Nuclear Information System (INIS)

    Rosenberg, Mitchell

    2003-01-01

    This paper summarizes the experience of programs designed to promote the adoption of best practices in equipment specification and installation among distributors and installation contractors in the residential central air conditioning and industrial compressed air equipment markets. For each of those markets, the paper identifies the current understanding of best practices, characterizes energy savings available from their adoption, assesses the nature of barriers to their adoption, and describes the operations and accomplishments of programs designed to address those barriers

  15. 32 CFR 643.126 - Transportation licenses.

    Science.gov (United States)

    2010-07-01

    ... 32 National Defense 4 2010-07-01 2010-07-01 true Transportation licenses. 643.126 Section 643.126... ESTATE Additional Authority of Commanders § 643.126 Transportation licenses. Installation commanders are... free competitive proposals of all available companies or individuals. (b) DD Form 694 (Transportation...

  16. 78 FR 38097 - Publication of General License Related to the Syria Sanctions Program

    Science.gov (United States)

    2013-06-25

    ... DEPARTMENT OF THE TREASURY Office of Foreign Assets Control Publication of General License Related to the Syria Sanctions Program AGENCY: Office of Foreign Assets Control, Treasury. ACTION: Notice, publication of general license. SUMMARY: The Department of the Treasury's Office of Foreign Assets Control...

  17. Exporting the Canadian licensing program

    International Nuclear Information System (INIS)

    Whelan, D.J.

    1981-06-01

    This paper deals with the problems of an overseas regulatory agency in licensing a Canadian-supplied nuclear plant which is referenced to a plant in Canada. Firstly, the general problems associated with the use of a reference plant are discussed. This is followed by a discussion of specific problems which arise from the licensing practices in Canada. The paper concludes with recommendations to simplify the task of demonstrating the licensability of an overseas CANDU plant

  18. 78 FR 41192 - Publication of General License Related to the Zimbabwe Sanctions Program

    Science.gov (United States)

    2013-07-09

    ... DEPARTMENT OF THE TREASURY Office of Foreign Assets Control Publication of General License Related to the Zimbabwe Sanctions Program AGENCY: Office of Foreign Assets Control, Treasury. ACTION: Notice, publication of general license. SUMMARY: The U.S. Department of the Treasury's Office of Foreign Assets...

  19. Recidivism Among Licensed-Released Prisoners Who Participated in the EM Program in Israel.

    Science.gov (United States)

    Shoham, Efrat; Yehosha-Stern, Shirley; Efodi, Rotem

    2015-08-01

    Toward the end of 2006, a pilot program was launched in Israel wherein licensed-released prisoners were put under electronic monitoring (EM). In addition to EM, the pilot program, operated by the Prisoners' Rehabilitation Authority, provides programs of occupational supervision and personal therapy and is designed to allow for early release of those prisoners who, without increased supervision, would have been found unsuitable for early release. The aim of this study was to ascertain whether participation in the EM program among licensed-released prisoners in Israel might bring about lessened recidivism. For that matter, rates of arrests and incarceration were examined during a follow-up period of up to 4 years, among the entirety of licensed-released prisoners participating in the EM program between the years 2007 and 2009 (n = 155). To compare recidivism rates, a control group was assembled from among the entirety of released prisoners who were found unsuitable for early release in judicial conditions, and had therefore served the full term of their incarceration, to be released between the years 2005 and 2006 (a period of time during which an EM program was not yet operated among licensed-released prisoners in Israel). Study findings clearly show that while among the control group, 42% of released prisoners were re-incarcerated, at the end of a 4-year follow-up period, only 15% among the study group had returned to prison. These findings can be explained by combining the Social Control theory and the Self-Control theory which consider the period of time under EM program and the occupational and familial integration tools for reducing criminal connections and enhancing pro-social behavior. © The Author(s) 2014.

  20. Decommissioning Licensing Process of Nuclear Installations in Spain

    International Nuclear Information System (INIS)

    Correa Sainz, Cristina

    2016-01-01

    The Enresa experience related to the decommissioning of nuclear facilities includes the decommissioning of the Vandellos I and Jose Cabrera NPPs. The Vandellos I gas-graphite reactor was decommissioned in about five years (from 1998 to 2003) to what is known as level 2. In February 2010, the decommissioning of Jose Cabrera power plant has been initiated and it is scheduled to be finished by 2018. The decommissioning of a nuclear power plant is a complex administrative process, the procedure for changing from operation to decommissioning is established in the Spanish law. This paper summarizes the legal framework defining the strategies, the main activities and the basic roles of the various agents involved in the decommissioning of nuclear facilities in Spain. It also describes briefly the Licensing documents required to obtain the decommissioning authorization and the Enresa point of view, as licensee, on the licensing decommissioning process. (author)

  1. Development of a quality management system for Brazilian nuclear installations

    International Nuclear Information System (INIS)

    Kibrit, Eduardo; Zouain, Desiree Moraes

    2005-01-01

    The present work is a proposal for developing a quality management system for Brazilian nuclear installations, based on applicable standards. The standard ISO 9001:2000 [4] establishes general requirements for the implementation of a quality management system in all kinds of organizations. The standard IAEA 50-C/SG-Q [1] establishes general requirements for the implementation of a quality assurance system in nuclear installations. The standard CNEN-NN- 1.16 [5] establishes the regulating requirements for the quality assurance systems and programs of nuclear installations, for licensing and authorization for operation of these installations in Brazil. The revision of standard IAEA 50-C/SG-Q [1], to be replaced by IAEA DS 338 [2] and IAEA DPP 349 [3], introduces the concept of 'Integrated Management System' for the nuclear area, in preference to the concept of 'Quality Assurance'. This approach is incorporated with the current tendency, because it guides the system to manage, in an integrated way, the requirements of quality, safety, health, environment, security and economics of the installation. The results of the characterization of the quality management systems established in the applicable standards are presented, with the determination of the common and conflicting points among them. Referring data to quality assurance program/quality management system in some nuclear installations of IAEA Member States are also presented. (author)

  2. Progress in licensing ITER in Cadarache

    International Nuclear Information System (INIS)

    Rodriguez-Rodrigo, Lina; Girard, Jean-Philippe; Uzan-Elbez, Joelle; Marbach, Gabriel; Garin, Pascal; Rosanvallon, Sandrine

    2005-01-01

    The licensing procedure for ITER in Europe in the framework of the French regulations is a non-prescriptive approach based on a continuous dialogue between the nuclear installation owner (or its representative) and the safety authority. In this paper, the licensing procedure and main safety issues, which are being studied in this process, are presented

  3. Fiscal year 1996 well installation program summary, Y-12 Plant Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1997-04-01

    This report summarizes the well installation activities conducted during the federal fiscal year (FY) 1996 drilling program at the Oak Ridge Y-12 Plant, Oak Ridge Tennessee. Synopses of monitoring well construction/well development data, well location rationale, geological/hydrological observations, quality assurance/quality control methods, and health and safety monitoring are included. Two groundwater monitoring wells were installed during the FY 1996 drilling program. One of the groundwater monitoring wells was installed in the Lake Reality area and was of polyvinyl chloride screened construction. The other well, installed near the Ash Disposal Basin, was of stainless steel construction

  4. Licensing and decommissioning of nuclear installations in Japan

    International Nuclear Information System (INIS)

    Shimoyama, Shunji.

    1986-01-01

    The present report discusses the current status of Japan's licensing system and legislation concerning reactor decommissioning operations. Besides Japan is working to promote worldwide nuclear safety research. However, developing nuclear safety regulations that are uniformely applicable is a difficult job due to big differences in geographical, political, economical, and technological conditions. (CW) [de

  5. Safety of nuclear installations in Slovakia

    International Nuclear Information System (INIS)

    1998-01-01

    In this part next aspects are described: (1) Site selection (Legislation related to site selection; Meeting criteria at Bohunice and Mochovce sites; International agreements); (2) Design preparation and construction (Designing and construction-relevant legislation; Nuclear installation project preparation of nuclear installation at Mochovce site); (3) Operation (Operator licensing procedure; Operation limits and conditions; Maintenance testing and control documentation for management and operation; Technical support of operation; Analysis of events at nuclear installations and Radioactive waste production); (4) Planned safety upgrading activities at nuclear installations

  6. The Role Of Quality Assurance Program For Safety Operation Of Nuclear Installations

    International Nuclear Information System (INIS)

    Harjanto, N.T.; Purwadi, K.P.; Boru, D.S.; Farida; Suharni

    2000-01-01

    Nuclear installations expose potential hazard of radiation, therefore in their construction, operation and maintenance, it is necessary to consider safety aspect, in which the safety requirements which has been determined must be met. One of the requirements that is absolutely needed is quality assurance, which covers arrangement of quality assurance program, organization and administration of the implementation of quality assurance, and supervision. Quality Assurance program is a guideline containing quality policies and basic determination on the realization of activities that effect the quality of equipment's and items used in the operation of nuclear installations in order that the operation of nuclear installation can run safety and in accordance with their design aims and operation limits. Quality Assurance Program includes document control, design control, supply control, control of equipment s and items, operation/process control, inspection and control of equipment test, and control of nonconformance and corrections. General system of nuclear installation operation is equipped with safety and supporting systems. These systems must apply the quality assurance program that cover control of activities in the systems. In the implementation of the quality assurance program, it is necessary to establish procedures, work guidelines/instructions, and quality recording that constitutes documents of quality system 2 nd , 3 th , and 4 th level after the quality assurance program. To ensure the effectivity and to prove whether the realization of the program has been pursuant to the determined requirements, an internal audit must be conducted accordingly

  7. 10 CFR 51.97 - Final environmental impact statement-materials license.

    Science.gov (United States)

    2010-01-01

    ... 10 Energy 2 2010-01-01 2010-01-01 false Final environmental impact statement-materials license. 51...-Regulations Implementing Section 102(2) Final Environmental Impact Statements-Materials Licenses § 51.97 Final environmental impact statement—materials license. (a) Independent spent fuel storage installation (ISFSI...

  8. Design, fabrication and installation of irradiation facilities

    International Nuclear Information System (INIS)

    Kim, Yong Sung; Lee, C. Y.; Kim, J. Y.; Chi, D. Y.; Kim, S. H.; Ahn, S. H.; Kim, S. J.; Kim, J. K.; Yang, S. H.; Yang, S. Y.; Kim, H. R.; Kim, H.; Lee, K. H.; Lee, B. C.; Park, C.; Lee, C. T.; Cho, S. W.; Kwak, K. K.; Suk, H. C.

    1997-07-01

    The principle contents of this project are to design, fabricate and install the steady-state fuel test loop and non-instrumented capsule in HANARO for nuclear technology development. This project will be completed in 1999, the basic and detail design, safety analysis, and procurement of main equipment for fuel test loop have been performed and also the piping in gallery and the support for IPS piping in reactor pool have been installed in 1994. In the area of non-instrumented capsule for material irradiation test, the fabrication of capsule has been completed. Procurement, fabrication and installation of the fuel test loop will be implemented continuously till 1999. As besides, as these irradiation facilities will be installed in HANARO, review of safety concern, discussion with KINS for licensing and safety analysis report has been submitted to KINS to get a license and review of HANARO interface have been performed respectively. (author). 39 refs., 28 tabs., 21 figs

  9. Design, fabrication and installation of irradiation facilities

    Energy Technology Data Exchange (ETDEWEB)

    Kim, Yong Sung; Lee, C. Y.; Kim, J. Y.; Chi, D. Y.; Kim, S. H.; Ahn, S. H.; Kim, S. J.; Kim, J. K.; Yang, S. H.; Yang, S. Y.; Kim, H. R.; Kim, H.; Lee, K. H.; Lee, B. C.; Park, C.; Lee, C. T.; Cho, S. W.; Kwak, K. K.; Suk, H. C. [and others

    1997-07-01

    The principle contents of this project are to design, fabricate and install the steady-state fuel test loop and non-instrumented capsule in HANARO for nuclear technology development. This project will be completed in 1999, the basic and detail design, safety analysis, and procurement of main equipment for fuel test loop have been performed and also the piping in gallery and the support for IPS piping in reactor pool have been installed in 1994. In the area of non-instrumented capsule for material irradiation test, the fabrication of capsule has been completed. Procurement, fabrication and installation of the fuel test loop will be implemented continuously till 1999. As besides, as these irradiation facilities will be installed in HANARO, review of safety concern, discussion with KINS for licensing and safety analysis report has been submitted to KINS to get a license and review of HANARO interface have been performed respectively. (author). 39 refs., 28 tabs., 21 figs.

  10. A review of electric cable aging effects and monitoring programs for plant license renewal

    International Nuclear Information System (INIS)

    Lofaro, R.J.

    1999-01-01

    As commercial nuclear power plants approach the end of their original license period, some utilities are considering the possibility of license renewal. The requirements for applying for license renewal are specified in the License Renewal Rule, which is in Title 10 of the Code of Federal Regulations, Part 54 (10 CFR54). Among the requirements specified in the rule is the performance of an Integrated Plant Assessment (IPA) which identifies and lists structures and components subject to an aging management review. The intent of this requirement is to ensure that aging degradation will not adversely affect plant safety during the license renewal period. The aging management review includes an identification of the aging effects and monitoring programs for components within the scope of the rule. Among the components within the scope are electric cables since they are passive, long-lived components that are not replaced on a periodic basis. This paper examines the aging causes and effects of electric cables, along with the programs that are typically used to ensure that proper aging management practices are in place to monitor and mitigate the effects of aging on electric cables

  11. Streamlining the license renewal review process

    International Nuclear Information System (INIS)

    Dozier, J.; Lee, S.; Kuo, P.T.

    2001-01-01

    The staff of the NRC has been developing three regulatory guidance documents for license renewal: the Generic Aging Lessons Learned (GALL) report, Standard Review Plan for License Renewal (SRP-LR), and Regulatory Guide (RG) for Standard Format and Content for Applications to Renew Nuclear Power Plant Operating Licenses. These documents are designed to streamline the license renewal review process by providing clear guidance for license renewal applicants and the NRC staff in preparing and reviewing license renewal applications. The GALL report systematically catalogs aging effects on structures and components; identifies the relevant existing plant programs; and evaluates the existing programs against the attributes considered necessary for an aging management program to be acceptable for license renewal. The GALL report also provides guidance for the augmentation of existing plant programs for license renewal. The revised SRP-LR allows an applicant to reference the GALL report to preclude further NRC staff evaluation if the plant's existing programs meet the criteria described in the GALL report. During the review process, the NRC staff will focus primarily on existing programs that should be augmented or new programs developed specifically for license renewal. The Regulatory Guide is expected to endorse the Nuclear Energy Institute (NEI) guideline, NEI 95-10, Revision 2, entitled 'Industry Guideline for Implementing the Requirements of 10 CFR Part 54 - The License Renewal Rule', which provides guidance for preparing a license renewal application. This paper will provide an introduction to the GALL report, SRP-LR, Regulatory Guide, and NEI 95-10 to show how these documents are interrelated and how they will be used to streamline the license renewal review process. This topic will be of interest to domestic power utilities considering license renewal and international ICONE participants seeking state-of-the-art information about license renewal in the United States

  12. Licensing the Sun

    Science.gov (United States)

    Demski, Jennifer

    2013-01-01

    The University of San Diego (USD) and Point Loma Nazarene University (PLNU) are licensing the sun. Both California schools are generating solar power on campus without having to sink large amounts of capital into equipment and installation. By negotiating power purchasing agreements (PPAs) with Amsolar and Perpetual Energy Systems, respectively,…

  13. Meta-analysis of graduated driver licensing laws: effectiveness of specific program components : traffic tech.

    Science.gov (United States)

    2015-11-01

    Graduated driver licensing (GDL) programs in the United States do not represent a single homogeneous intervention; rather, they contain different combinations and variations of program components. Programs vary by the duration of each stage of the GD...

  14. Research and development tasks of the basalt waste isolation program, and their relationship to the licensing process

    International Nuclear Information System (INIS)

    Kunkel, W.P.

    1978-06-01

    This document presents a preliminary licensing program and outlines the research and development strategy by which a license will be obtained for the repository. It addresses the base data covering the major areas of investigation and technology which will provide input to the licensing process. Basically, each facet of the program, as described in the plan, will be used as part of the documentation required for the Preliminary and Final Safety Analysis Report (PSAR and FSAR), as well as the Environmental Report

  15. The need for legislative framework (licensing)

    International Nuclear Information System (INIS)

    Krech, H.

    1977-01-01

    For reasons of public acceptance the basis of a licensing system should be laid down in a law, details can be fixed in regulations below the law-level. The competence for licensing nuclear installations should be attributed to one body, which is not a the same time charged with the promotion of nuclear energy. The licensing authority has to be provided with sufficient technical advice, given by experts organized in advisory bodies. Normally a licensing procedure is split into several steps (site approval, construction permit, operation licence), each step can be subdivided. Some general aspects of licensing conditions (personal, technical and financial) as well as of the licensing procedure are outlined. The participation of the public is of particular importance but also involves most intricate problems. The paper concludes with some critical remarks on the role of administrative courts with respect to the licensing of nuclear power plants. (orig.) [de

  16. Decommissioning of the nuclear licensed facilities at the Fontenay aux Roses CEA Center; cleanup of nuclear licensed facility 57 and monitoring of operations and operating feedback

    International Nuclear Information System (INIS)

    Estivie, D.; Bohar, M.P.; Jeanjacques, M.; Binet, C.; Bremond, M.P.; Poyau, C.; Mandard, L.; Boissonneau, J.F.; Fouquereau, A.; Pichereau, E.

    2008-01-01

    This is a summary of the program for the decommissioning of all the CEA Licensed Nuclear Facilities in Fontenay aux Roses. The particularity of this center is now it is located in a built-up area. It is presented like example the operations to clean up the equipment of the Nuclear Licensed Facility 57 (NLF 57). Due to the diversity of the research and development work carried out on the reprocessing of spent fuel in it, this installation is emblematic of many of the technical and organizational issues liable to be encountered in the final closure of nuclear facilities. It was developed a method applied to establish the multi-annual budget, monitor the progress of operations and integrate, as work continues, the operating feedback. (author)

  17. Empirical Study of Car License Plates Recognition

    OpenAIRE

    Dina, Nasa Zata; Dailey, Matthew

    2015-01-01

    The number of vehicles on the road has increased drastically in recent years. The license plate is an identity card for a vehicle. It can map to the owner and further information about vehicle. License plate information is useful to help traffic management systems. For example, traffic management systems can check for vehicles moving at speeds not permitted by law and can also be installed in parking areas to se-cure the entrance or exit way for vehicles. License plate recognition algorithms ...

  18. Specification of requirements to get a license for an Independent Spent Fuel Dry Storage Installation (ISFSI) at the site of the NPP-LV

    International Nuclear Information System (INIS)

    Serrano R, M. L.

    2015-09-01

    This article describes some of the work done in the Comision Nacional de Seguridad Nuclear y Salvaguardias (CNSNS) to define specifically the requirements that the Federal Electricity Commission (CFE) shall meet to submit for consideration of CNSNS an operation request of an Independent Spent Fuel Dry Storage Installation (ISFSI). The project of a facility of this type arose from the need to provide storage capacity for spent nuclear fuel in the nuclear power plant of Laguna Verde (NPP-LV) and to continue the operation at the same facility in a safe manner. The licensing of these facilities in the United States of America has two modes: specific license or general license. The characteristics of these licenses are described in this article. However, in Mexico the existing national legislation is not designed for such license types, in fact there is a lack of standards or regulations in this regard. The regulatory law of Article 27 of the Constitution in the nuclear matter, only generally establishes that this type of facility requires an authorization from the Ministry of Energy. For this reason and because there is not a national legislation, was necessary to use the legislation that provides the Nuclear Regulatory Commission of USA, the US NRC. However, it cannot be applied as is established, so was necessary that the CNSNS analyze one by one the requirements of both types of license and determine what would be required to NPP-LV to submit its operating license of ISFSI. The American regulatory applicable to an ISFSI, the 10-Cfr-72 of the US NRC, establishes the requirements for both types of licenses. Chapter 10-Cfr was analyzed in all its clauses and coupled to the laws, regulations and standards as well as to the requirements established by CNSNS, all associated with a store spent fuel on site; the respective certification of containers for spent fuel dry storage was not included in this article, even though the CNSNS also performed that activity under the

  19. Border installations

    International Nuclear Information System (INIS)

    Lenaerts, Koen

    1988-01-01

    Border installations cover all nuclear plants located near the border with a neighbouring state. However, the actual distance depends on the context. The distance can vary considerably. Also the prohibition on siting near a heavily populated area also defines the actual distance variably. The distance criteria may be modified by other factors of topography, prevailing climate and so on. Various examples which illustrate the problems are given. For example, the Creys-Melville nuclear power plant is 80km from Geneva and the Cattonam installation is 12km from the French border with Luxembourg and Germany. The Cattenom case is explained and the legal position within the European Institutions is discussed. The French licensing procedures for nuclear power stations are described with special reference to the Cattenom power plant. Border installations are discussed in the context of European Community Law and Public International Law. (U.K.)

  20. Responsible management: the Dutch licensing policy for nuclear installations

    International Nuclear Information System (INIS)

    Slange, R.

    1994-01-01

    The governmental policy, to tolerate operation of existing nuclear installations not backed by the required operating permits, certainly is applied only in exceptional cases, and this all the more when the plant is a nuclear installation. Any decision to tolerate further operation must be justified by compliance with a number of rigid criteria, there may be a debate in Parliament about the case, third parties have the right participate in the decision-finding procedure, and there is the right of appeal. (orig.) [de

  1. The regulation of radioactive effluent release in France (mainly from large nuclear installations)

    International Nuclear Information System (INIS)

    Hebert, Jean.

    1978-01-01

    In parallel with the licensing system for construction and operation of classified or so-called large nuclear installations (INB) there are in France regulations for the release of radioactive effuents from such installations. The regulations applicable to installations other than INBs are not specifically of a nuclear nature, while those covering INBs, which are analysed in this study, in particular, cover effluent release in liquid or gaseous form. The licensing and control procedures for such release are analysed in detail. (NEA) [fr

  2. Practice and trends in nuclear fuel licensing in France (pressurized water reactor fuels)

    International Nuclear Information System (INIS)

    Roudier, S.; Badel, D.; Beraha, R.; Champ, M.; Tricot, N.; Tran Dai, P.

    1994-01-01

    The activities of governmental French authorities responsible for safety of nuclear installations are outlined. The main bodies involved in nuclear safety are: the CSSIN (High Council for Nuclear Safety and Information), CINB (Inter-ministerial Commission for Basic Nuclear Installations) and DSIN (Nuclear Installations Safety Directorate). A brief review of the main fuel licensing issues supported by DSIN is given, which includes: 1) formal regularity procedure ensuring the safety of nuclear installations and especially the pressurized water reactors; 2) guidelines for nuclear design and manufacturing requirements related to safety and 3) safety goals and associated limits. The fuel safety documents for reloading as well as the research and development programmes in the field of technical safety are also described. The ongoing experiments in CABRI reactor, aimed at determining the high burnup fuel behaviour under reactivity initiated accidents until 65 GW d/Mt U, are one of these programs

  3. Practice and trends in nuclear fuel licensing in France (pressurized water reactor fuels)

    Energy Technology Data Exchange (ETDEWEB)

    Roudier, S [Direction de la Surete des Installations Nucleaires, Fontenay-aux-Roses (France); Badel, D; Beraha, R [Direction Regionale de l` Industrie, de la Recherche et de l` Environnement Rhone-Alpes, Lyon (France); Champ, M; Tricot, N; Tran Dai, P [CEA Centre d` Etudes de Fontenay-aux-Roses, 92 (France). Inst. de Protection et de Surete Nucleaire

    1994-12-31

    The activities of governmental French authorities responsible for safety of nuclear installations are outlined. The main bodies involved in nuclear safety are: the CSSIN (High Council for Nuclear Safety and Information), CINB (Inter-ministerial Commission for Basic Nuclear Installations) and DSIN (Nuclear Installations Safety Directorate). A brief review of the main fuel licensing issues supported by DSIN is given, which includes: (1) formal regularity procedure ensuring the safety of nuclear installations and especially the pressurized water reactors; (2) guidelines for nuclear design and manufacturing requirements related to safety and (3) safety goals and associated limits. The fuel safety documents for reloading as well as the research and development programmes in the field of technical safety are also described. The ongoing experiments in CABRI reactor, aimed at determining the high burnup fuel behaviour under reactivity initiated accidents until 65 GW d/Mt U, are one of these programs.

  4. The HOR core conversion program development and licensing experiences

    International Nuclear Information System (INIS)

    Vries, J.W. de; Gibcus, H.P.M.; Leege, P.F.A. de

    1997-01-01

    This paper deals with the experiences in the development of a fuel conversion program for a 2 MW university type research reactor, the HOR. It gives an overview of the technical and administrative aspects concerning the fuel conversion program development since the eighties, including the safety review and licensing process. The overall final safety report was submitted in 1995, together with the environmental impact report, and a licence application was submitted accordingly. The licence permitting the conversion was issued in 1996, coming into force at the beginning of this year, although an appeal case is still pending. At the moment the necessary preparations for starting the actual conversion of the HOR are made. The general program characteristics are addressed. (author)

  5. Licensing procedures and safety criteria for core conversion in Japan

    International Nuclear Information System (INIS)

    Kanda, K.; Nakagome, Y.; Hayashi, M.

    1983-01-01

    In Japan, the establishment and operation of nuclear installations are governed mainly by the Law for Regulation of Nuclear Source Material, Nuclear Fuel Material and Reactors. This law lays down the regulations and conditions for licensing of the various installations involved in the nuclear fuel cycle, namely licensing of installations for refining, fabricating and reprocessing; and reactors, as well as licensing of the use of nuclear fuels in research facilities. Although procedures for the installations listed above vary depending on the installation concerned, only those relating to construction and operation of reactor facilities will be analysed in this study, as the conditions and principles applying to licensing and control of other installations are, to a large extent, similar to those concerning reactor facilities. The second part of this presentation describes the safety review of the KUCA reactor core conversion form HEU to MEU. For the safety review of the core conversion, the Committee on Examination of Reactor Safety of Japanese Government examined mainly the the nuclear characteristics and the integrity of aluminide fuel plates, which was very severe because we had no experience to use aluminide fuel plates in Japan. The integrity of fuel plates and the results of the worst accident analysis for the MEU core are shown with the comparison between the HEU and MEU cores. The significant difference was not observed between them. All the regulatory procedures were completed in September 1980. Fabrication of MEU fuel elements for the KUCA experiments by CERCA in France was started in September 1980, and will be completed in March 1981. The critical experiments in the KUCA with MEU fuel will be started on a single-core in May 1981 as a first step. Those on a coupled-core will follow

  6. An overview of the licensing approach of the South African nuclear regulatory authority

    International Nuclear Information System (INIS)

    Clapisson, G.A.; Hill, T.F.; Henderson, N.R.; Keenan, N.H.; Metcalf, P.E.; Mysenkov, A.

    1997-01-01

    This paper describes the approach adopted by the South African Nuclear Regulatory Authority, the Council for Nuclear Safety (CNS) in licensing nuclear installations in South Africa. An introduction to the current South African legislation and the CNS philosophy pertaining to the licensing of nuclear installations is discussed. A typical process for granting a nuclear licence is then presented. The risk assessment process, which is used to verify compliance with the fundamental safety standards and to establish licensing requirements for a specific nuclear installation, is discussed. Based on the outcome of this assessment process, conditions of licence are set down. The generic content of a nuclear licence and mechanisms to ensure ongoing compliance with the risk criteria are presented. The regulatory process discussed in this paper, based on such a fundamental approach, may be adapted to any type of nuclear installation taking into account plant specific designs and characteristics. (author)

  7. Motorcycle Training for California Driver Licensing Personnel. Final Report.

    Science.gov (United States)

    California State Dept. of Motor Vehicles, Sacramento.

    The development of a 6-hour motorcycle course of instruction for personnel responsible for motorcycle licensing is described in this project report. The primary goals are stated and include (1) training driver licensing personnel in motorcycle safety and principles of operation, and (2) purchasing and installing appropriate motorcycle skill…

  8. Figures of Merit Software: Description, User's Guide, Installation Notes, Versions Description, and License Agreement

    Science.gov (United States)

    hoelzer, H. D.; Fourroux, K. A.; Rickman, D. L.; Schrader, C. M.

    2011-01-01

    Figures of Merit (FoMs) and the FoM software provide a method for quantitatively evaluating the quality of a regolith simulant by comparing the simulant to a reference material. FoMs may be used for comparing a simulant to actual regolith material, specification by stating the value a simulant s FoMs must attain to be suitable for a given application and comparing simulants from different vendors or production runs. FoMs may even be used to compare different simulants to each other. A single FoM is conceptually an algorithm that computes a single number for quantifying the similarity or difference of a single characteristic of a simulant material and a reference material and provides a clear measure of how well a simulant and reference material match or compare. FoMs have been constructed to lie between zero and 1, with zero indicating a poor or no match and 1 indicating a perfect match. FoMs are defined for modal composition, particle size distribution, particle shape distribution, (aspect ratio and angularity), and density. This TM covers the mathematics, use, installation, and licensing for the existing FoM code in detail.

  9. Legal protection of citizens in licensing procedures for large-scale industrial installations

    International Nuclear Information System (INIS)

    Class, T.

    1990-01-01

    The author examines whether the Constitution and the various procedural provisions do indeed guarantee full effect to the principle of participation of citizens in the licensing procedure, as e.g. by a sufficient formulation and definition of rights. The role of the Constitution is discussed in regard to the formulation of procedural provisions and rights of parties participating in the licensing procedure. (RST) [de

  10. Fiscal year 1994 well installation program summary report, Y-12 Plant, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1994-09-01

    This report summarizes the well installation activities conducted during the federal fiscal year (FY) 1994 drilling program at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee. Synopses of monitoring well construction/well development data, well location rationale, geological/hydrological observations, quality assurance/quality control methods, and health and safety monitoring are included. Two monitoring wells were installed and one piezometer installation was attempted, but not completed, during the FY 1994 drilling program. In addition, SAIC provided health and safety and geotechnical oversight for two soil borings in support of the Y-12 Underground Storage Tank (UST) Program. All new monitoring wells were developed by either a 2.0-in. diameter swab rig or by hand bailing until nonspecific indicator parameters (pH and specific conductance) attained steady-state levels. Turbidity levels were lowered, if required, to the extent practicable by continued development beyond a steady-state level of pH and conductance. All well installation was conducted following industry-standard methods and approved procedures in the Environment Surveillance Procedures Quality Control Program (Energy Systems 1988), the Resource Conservation and Recovery Act (RCRA) Groundwater Monitoring Technical Enforcement Guidance Document (EPA 1986), and Guidelines for Installation of Monitor Wells at the Y-12 Plant (Geraghty and Miller 1985). Health and safety monitoring and field screening of drilling returns and development waters were conducted in accordance with approved Martin Marietta Energy Systems, Inc. (Energy Systems) guidelines. All of the monitoring wells installed during FY 1994 at the Y-12 Plant were of screened construction

  11. Fiscal year 1995 well installation program summary Y-12 Plant, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    1995-09-01

    This report summarizes the well installation activities conducted during the federal fiscal year (FY) 1995 drilling program at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee (including activities that were performed in late FY 1994, but not included in the FY 1994 Well Installation Program Summary Report). Synopses of monitoring well construction/well development data, well location rationale, geological/hydrological observations, quality assurance/quality control methods, and health and safety monitoring are included. Three groundwater monitoring wells and two gas monitoring probes were installed during the FY 1995 drilling program. One of the groundwater monitoring wells was installed at Landfill VI, the other two in the Boneyard/Burnyard area. All of the groundwater monitoring wells were constructed with stainless steel screens and casings. The two gas monitoring probes were installed at the Centralized Sanitary Landfill II and were of polyvinyl chloride (PVC) screened construction. Eleven well rehabilitation/redevelopment efforts were undertaken during FY 1995 at the Y-12 Plant. All new monitoring wells and wells targeted for redevelopment were developed by either a 2.0-in. diameter swab rig or by hand bailing until nonspecific parameters (pH and specific conductance) attained steady-state levels. Turbidity levels were lowered, if required, to the extent practicable by continued development beyond a steady-state level of pH and conductance

  12. Operating reactors licensing actions summary

    International Nuclear Information System (INIS)

    1982-07-01

    The operating reactors licensing actions summary is designed to provide the management of the Nuclear Regulatory Commission (NRC) with an overview of licensing actions dealing with operating power and nonpower reactors. These reports utilize data collected from the Division of Licensing in the Office of Nuclear Reactor Regulation and are prepared by the Office of Management and Program Analysis. This summary report is published primarily for internal NRC use in managing the operating reactors licensing actions program. Its content will change based on NRC management informational requirements

  13. Operating reactors licensing actions summary

    International Nuclear Information System (INIS)

    1982-05-01

    The operating reactors licensing actions summary is designed to provide the management of the Nuclear Regulatory Commission (NRC) with an overview of licensing actions dealing with operating power and nonpower reactors. These reports utilize data collected from the Division of Licensing in the Office of Nuclear Reactor Regulation and are prepared by the Office of Management and Program Analysis. This summary report is published primarily for internal NRC use in managing the operating reactors licensing actions program. Its content will change based on NRC management informational requirements

  14. Operating reactors licensing actions summary

    International Nuclear Information System (INIS)

    1983-01-01

    The operating reactors licensing actions summary is designed to provide the management of the Nuclear Regulatory Commission (NRC) with an overview of licensing actions dealing with operating power and nonpower reactors. These reports utilize data collected from the Division of Licensing in the Office of Nuclear Reactor Regulation and are prepared by the Office of Management and Program Analysis. This summary report is published primarily for internal NRC use in managing the operating reactors licensing actions program. Its content will change based on NRC management informational requirements

  15. Operating reactors licensing actions summary

    International Nuclear Information System (INIS)

    1983-03-01

    The operating reactors licensing actions summary is designed to provide the management of the Nuclear Regulatory Commission (NRC) with an overview of licensing actions dealing with operating power and nonpower reactors. These reports utilize data collected from the Division of Licensing in the Office of Nuclear Reactor Regulation and are prepared by the Office of Management and Program Analysis. This summary report is published primarily for internal NRC use in managing the operating reactors licensing actions program. Its content will change based on NRC management informational requirements

  16. Operating reactors licensing actions summary

    International Nuclear Information System (INIS)

    1982-11-01

    The operating reactors licensing actions summary is designed to provide the management of the Nuclear Regulatory Commission (NRC) with an overview of licensing actions dealing with operating power and nonpower reactors. These reports utilize data collected from the Division of Licensing in the Office of Nuclear Reactor Regulation and are prepared by the Office of Management and Program Analysis. This summary report is published primarily for internal NRC use in managing the operating reactors licensing actions program. Its content will change based on NRC management informational requirements

  17. Operating reactors licensing actions summary

    International Nuclear Information System (INIS)

    1982-10-01

    The operating reactors licensing actions summary is designed to provide the management of the Nuclear Regulatory Commission (NRC) with an overview of licensing actions dealing with operating power and nonpower reactors. These reports utilize data collected from the Division of Licensing in the Office of Nuclear Reactor Regulation and are prepared by the Office of Management and Program Analysis. This summary report is published primarily for internal NRC use in managing the operating reactors licensing actions program. Its content will change based on NRC management informational requirements

  18. Operating reactors licensing actions summary

    International Nuclear Information System (INIS)

    1982-08-01

    The operating reactors licensing actions summary is designed to provide the management of the Nuclear Regulatory Commission (NRC) with an overview of licensing actions dealing with operating power and nonpower reactors. These reports utilize data collected from the Division of Licensing in the Office of Nuclear Reactor Regulation and are prepared by the Office of Management and Program Analysis. This summary report is published primarily for internal NRC use in managing the operating reactors licensing actions program. Its content will change based on NRC management informational requirements

  19. Operating reactors licensing actions summary

    International Nuclear Information System (INIS)

    1982-09-01

    The operating reactors licensing actions summary is designed to provide the management of the Nuclear Regulatory Commission (NRC) with an overview of licensing actions dealing with operating power and nonpower reactors. These reports utilize data collected from the Division of Licensing in the Office of Nuclear Reactor Regulation and are prepared by the Office of Management and Program Analysis. This summary report is published primarily for internal NRC use in managing the operating reactors licensing actions program. Its content will change based on NRC management informational requirements

  20. Upgrading Licensed Practical Nurse to Registered Nurse Program, September 1971 - June 1973. Report.

    Science.gov (United States)

    Holloway, Sally

    Twenty Licensed Practical Nurses (LPN) became Registered Nurses (RN) in a pilot program giving partial academic credit for their LPN training and building on their existing skills. The program revolved around three needs: (1) trained nurses; (2) eliminating the notion that jobs were dead-end; and (3) achieving upward mobility for hospital staff.…

  1. Advances and Challenges in the Implementation of DiD in Siting, Design, and Construction of Nuclear Installations in Vietnam

    Energy Technology Data Exchange (ETDEWEB)

    Nguyen, H.A., E-mail: nhanh@varans.vn [Vietnam Agency for Radiation and Nuclear Safety, Hanoi (Viet Nam)

    2014-10-15

    Vietnam is embarking on a development of a nuclear power program. The main focus is now on the initial 1000 MWe x 2 units of the nuclear power plant in Ninh Thuan province. Now, the nuclear projects of Vietnam are in the phase of siting approval and investment projects approval. The design assessment will be performed in 2013-2014; the construction and installation will be performed from now until the operating licensing is obtained in 2020-2021. With state of development of a nuclear power program in Vietnam, this paper only focuses on advances and challenges in the implementation of Defence in Depth (DID) in siting, design, and construction of nuclear installations in Vietnam. (author)

  2. The strategy of experimental power reactor licensing in Indonesia

    International Nuclear Information System (INIS)

    Moch Djoko Birmano

    2015-01-01

    Currently, BATAN has being planned to develop Experimental Power Reactor (EPR), that is the research nuclear reactor that can generate power (electricity or heat). The EPR is planned will be built in the National Center for Research of Science and Technology (Puspiptek) area at Serpong, South Tangerang, Banten Province, with the choice of reactor types is HTGR with the power size of 10 MWth. As stated in the Act No. 10 year 1997 on Nuclear Power, that every construction and operation of nuclear reactors and other nuclear installations and decommissioning of nuclear reactors required to have a permit. Furthermore, the its implementation arrangements is regulated in Government Regulation (GR) No. 2 year 2014 on Licensing of Nuclear Installations and Nuclear Material Utilization, which contains the requirements and procedures for the licensing process since site, construction, commissioning, operation, and decommissioning, it means licensing is implemented during the activity of construction, operation and decommissioning of NPPs.While, for the more detailed licensing arrangements available in the guidelines of BAPETEN Chairman Regulation (BCR). This study was conducted to understand the legal and institutional aspects, types and stages, and the licensing process of RDE, and identify licensing strategy so that timely as planned. Methodologies used include the literature study, consultation with experts in BAPETEN, discussions in the national seminar including FGD. (author)

  3. Licensing schedule for away-from-reactor (AFR) spent fuel storage facilities

    International Nuclear Information System (INIS)

    Gray, P.L.

    1981-08-01

    The Nuclear Regulatory Commission has authority to issue licenses for Away-From-Reactor (AFR) installations for the storage of spent nuclear fuel. This report presents a detailed estimate of the time required to prosecute a licensing action. The projected licensing schedule shows that the elapsed time between filing an application and issuance of a license will be about 32 months, assuming intervention. The legal procedural steps will determine the time schedule and will override considerations of technical complexity. A license could be issued in about 14 months in the absence of intervention

  4. Interim licensing criteria for physical protection of certain storage of spent fuel

    International Nuclear Information System (INIS)

    Dwyer, P.A.

    1994-11-01

    This document presents interim criteria to be used in the physical protection licensing of certain spent fuel storage installations. Installations that will be reviewed under this criteria are those that store power reactor spent fuel at decommissioned power reactor sites; independent spent fuel storage installations located outside of the owner controlled area of operating nuclear power reactors; monitored retrievable storage installations owned by the Department of Energy, designed and constructed specifically for the storage, of spent fuel; the proposed geologic repository operations area; or permanently shutdown power reactors still holding a Part 50 license. This criteria applies to both dry cask and pool storage. However, the criteria in this document does not apply to the storage of spent fuel within the owner-controlled area of operating nuclear power reactors

  5. Users manual. Pursuit program of use licenses of radioactive material or generator equipment of ionizing radiations

    International Nuclear Information System (INIS)

    Becerril M, V.M.; Villarreal, J.E.

    1992-05-01

    The objective of the program 'Databases for the pursuit of licenses of use of radioactive material', it consists on the application of a computer system carried out in dbase IV that it allows the control of the all the information related with those licenses for use, possession and storage of radioactive material or generator equipment of ionizing radiations. (Author)

  6. Licensing requirements for initial commissioning programs in Spain: Application to different PWR designs

    International Nuclear Information System (INIS)

    Munuera, A.; Conde, J.M.; Martinez, J.

    1991-01-01

    This paper describes the overall licensing process in Spain, focusing on the initial commissioning requirements. The significance of this part of the regulatory work is evident both from the licensing and the licensee's points of view. Licensing in Spain is ruled by different laws which determine the general requirements and fix the licensing frame. Being a nuclear technology importer country, the base of the regulatory work lies on the rules and regulations of the country of origin of the planet, with the addition of case specific requirements. The application of this methodology to plants designed in different countries produces licensing processes which are similar to the overall, but very different in its development. It also means a special technical effort on the part of the regulatory body to cope with the problems arising from the use of different technologies and safety standards. The start-up programs from fuel loading to full power of a Westinghouse plant (Vandellos 2) and a Siemens-KWU plant (Trillo 1) are compared from the technical point of view, enhancing the differences that can be relevant for the regulatory work. The difficulties arising from the application of both the German and US concepts are discussed. (orig.)

  7. Development and Field Test of Competency Based Instructional Material for a Career Mobility Program for Licensed Practical Nurses. Final Report.

    Science.gov (United States)

    Bergen Community Coll., Paramus, NJ.

    The Associate Degree Nursing Program at Bergen Community College developed and field tested competency-based instructional modules in a program designed to allow licensed practical nurses to qualify to take the certification examination for registered nurses after a year of study. Thirteen licensed practical nurses were enrolled in the first class…

  8. Current emergency programs for nuclear installations in Japan

    International Nuclear Information System (INIS)

    Chino, Masamichi

    2007-01-01

    Large effort has been taken for nuclear emergency programs in Japan especially after the JCO accident. A special law for nuclear emergency was established after the accident. The law extended the scope of emergency preparedness to fuel cycle facilities, research reactors, etc. and clarified the roles and responsibilities of the national government, local governments and license holders. For initial responses, the action levels and action procedures are defined based on environmental doses and specific initial events of NPPs. A senior specialist was dispatched to each site for nuclear emergency and a facility 'Off-site center' to be used as the local emergency headquator was designated at each site. This paper describes the structure of emergency program, responsibility of related organizations and the definition of unusual events for notification and emergency. Emergency preparedness, emergency radiation monitoring and computer-based prediction of on- and off-site situation are also addressed. (author)

  9. Main features of licensing requirements for nuclear installations in several OECD member countries

    International Nuclear Information System (INIS)

    Reyners, P.

    1977-01-01

    The present paper contains a brief description of the main features of the above-mentioned six countries' licensing systems, namely the legal regime applicable, the appropriate licensing bodies, the general frame and scope of the respective national regimes, the involvement of the public and technical safety bodies as well as the inspection procedures. This description is supplemented by some introductory remarks. (orig.) [de

  10. Main features of licensing requirements for nuclear installations in several OECD member countries

    International Nuclear Information System (INIS)

    Reyners, P.

    1975-01-01

    The present paper contains a brief description of the main features of the above-mentioned six countries' licensing systems, namely the legal regime applicable, the appropriate licensing bodies, the general frame and scope of the respective national regimes, the involvement of the public and technical safety bodies as well as the inspection procedures. This description is supplemented by some introductory remarks. (orig.) [de

  11. NUPLEX Licensing Subcommittee

    International Nuclear Information System (INIS)

    Edwards, D.W.; Allen, S.R.

    1988-01-01

    The NUPLEX Licensing Subcommittee was organized to seek a formal license renewal mechanism that institutionalizes the current licensing basis and consequent level of safety of a plant as the legitimate standard for acceptance and approval of an application for extended operation. Along with defining the most workable approach to and scope of review for license renewal, this paper explains the reasons why a regulatory framework is needed by the early 1990s. The initial results of development work on two key issues, licensing criteria and hearing process, are also presented. at this point six potential license renewal criteria have emerged: evaluation of existing monitoring/maintenance programs, revalidation of current licensing basis, conformance to special regulations, evaluation to a safety goal, plant performance history, and environmental assessment. The work on a hearing process has led to the development of two models for future consideration: hybrid legislative and hybrid adjudicatory

  12. 'Culture and memory of the Sto. Antonio do Morro Grande/MG Quilombola community' program - case study: environmental licensing progress for the Rio de Janeiro-Belo Horizonte Gas Pipeline (GASBEL II)

    Energy Technology Data Exchange (ETDEWEB)

    Ismerio, Marcia [Pallos Environmental Consulting, Rio de Janeiro, RJ (United States); Bartolini, Marcia [PETROBRAS, Rio de Janeiro, RJ (Brazil)

    2009-07-01

    The 'Culture and Memory of the Sto. Antonio do Morro Grande Quilombola Community' Program was included in the environmental licensing process of the Rio de Janeiro-Minas Gerais gas pipeline ('GASBEL II'), as requested by the Palmares Cultural Foundation (Fundacao Cultural Palmares), which stipulates the elaboration and implementation of this program as a condition for obtaining the installation license. To develop the program and submit it to this institution, we used methodological procedures in the form of an anthropological social research, such as: interviews with the community's older or most active residents, and a preliminary recognition of the territory and the local culture; all in order to learn more about the community's history and current needs and to identify the remaining 'quilombolas' still living in the community. Analyzing the information raised the need for guided actions designed to rescue the community's cultural memory as an ethnic group and to contribute to its process of affirmation as a Traditional Rural 'Quilombola' Community. This led to the creation of the proposed 'Culture and Memory of the Sto. Antonio do Morro Grande Quilombola Community' Program, currently being developed for the Quilombola Community located in Ressaquinha, in the State of Minas Gerais. (author)

  13. Online driver's license renewal.

    Science.gov (United States)

    2015-09-01

    The Kentucky Department of Vehicle Regulation is exploring the possibility of developing and implementing online : drivers license renewal. The objective of this project was to: 1) evaluate online drivers license and REAL ID renewal : programs ...

  14. An ontology based trust verification of software license agreement

    Science.gov (United States)

    Lu, Wenhuan; Li, Xiaoqing; Gan, Zengqin; Wei, Jianguo

    2017-08-01

    When we install software or download software, there will show up so big mass document to state the rights and obligations, for which lots of person are not patient to read it or understand it. That would may make users feel distrust for the software. In this paper, we propose an ontology based verification for Software License Agreement. First of all, this work proposed an ontology model for domain of Software License Agreement. The domain ontology is constructed by proposed methodology according to copyright laws and 30 software license agreements. The License Ontology can act as a part of generalized copyright law knowledge model, and also can work as visualization of software licenses. Based on this proposed ontology, a software license oriented text summarization approach is proposed which performances showing that it can improve the accuracy of software licenses summarizing. Based on the summarization, the underline purpose of the software license can be explicitly explored for trust verification.

  15. EMPIRICAL STUDY OF CAR LICENSE PLATES RECOGNITION

    Directory of Open Access Journals (Sweden)

    Nasa Zata Dina

    2015-01-01

    Full Text Available The number of vehicles on the road has increased drastically in recent years. The license plate is an identity card for a vehicle. It can map to the owner and further information about vehicle. License plate information is useful to help traffic management systems. For example, traffic management systems can check for vehicles moving at speeds not permitted by law and can also be installed in parking areas to se-cure the entrance or exit way for vehicles. License plate recognition algorithms have been proposed by many researchers. License plate recognition requires license plate detection, segmentation, and charac-ters recognition. The algorithm detects the position of a license plate and extracts the characters. Various license plate recognition algorithms have been implemented, and each algorithm has its strengths and weaknesses. In this research, I implement three algorithms for detecting license plates, three algorithms for segmenting license plates, and two algorithms for recognizing license plate characters. I evaluate each of these algorithms on the same two datasets, one from Greece and one from Thailand. For detecting li-cense plates, the best result is obtained by a Haar cascade algorithm. After the best result of license plate detection is obtained, for the segmentation part a Laplacian based method has the highest accuracy. Last, the license plate recognition experiment shows that a neural network has better accuracy than other algo-rithm. I summarize and analyze the overall performance of each method for comparison.

  16. Importance of the licensing process on the safety culture in the Brazilian nuclear fuel cycle facilities

    International Nuclear Information System (INIS)

    Motta, E.S.; Sousa, A.L.B. de; Paiva, R.L.C. de; Mezrahi, A.

    2013-01-01

    The main objective of the Nuclear Fuel Cycle Facilities licensing processes is to ensure the safety of these installations in their entire life cycle (in the installation site selection, designing, construction, pre-operational tests, operational and decommissioning phases). The Brazilian licensing process requires from the operator, among others, before the operating license: (I) a Site Report and a Final Safety Analysis Report, ensuring that all safety related issues are adequately analyzed and understood; (II) a formal structured Management System focused on the installation safety; and (III) dissemination of safety related information to all involved operator employees and subcontractors. Therefore, these requirements reflect in an adequate operator actions and practices, ensuring a working environment with a high level of safety culture. (author)

  17. Importance of the licensing process on the safety culture in the Brazilian nuclear fuel cycle facilities

    Energy Technology Data Exchange (ETDEWEB)

    Motta, E.S.; Sousa, A.L.B. de; Paiva, R.L.C. de; Mezrahi, A., E-mail: emotta@cnen.gov.br [Comissao Nacional de Energia Nuclear (CNEN-RJ), Rio de Janeiro, RJ (Brazil)

    2013-07-01

    The main objective of the Nuclear Fuel Cycle Facilities licensing processes is to ensure the safety of these installations in their entire life cycle (in the installation site selection, designing, construction, pre-operational tests, operational and decommissioning phases). The Brazilian licensing process requires from the operator, among others, before the operating license: (I) a Site Report and a Final Safety Analysis Report, ensuring that all safety related issues are adequately analyzed and understood; (II) a formal structured Management System focused on the installation safety; and (III) dissemination of safety related information to all involved operator employees and subcontractors. Therefore, these requirements reflect in an adequate operator actions and practices, ensuring a working environment with a high level of safety culture. (author)

  18. Department of Energy licensing strategy

    International Nuclear Information System (INIS)

    Frei, M.W.

    1984-01-01

    The Department of Energy (DOE) is authorized by the Nuclear Waste Policy Act of 1982 (Act) to site, design, construct, and operate mined geologic repositories for high-level radioactive wastes and is required to obtain licenses from the Nuclear Regulatory Commission (NRC) to achieve that mandate. To this end the DOE has developed a licensing approach which defines program strategies and which will facilitate and ease the licensing process. This paper will discuss the regulatory framework within which the repository program is conducted, the DOE licensing strategy, and the interactions between DOE and NRC in implementing the strategy. A licensing strategy is made necessary by the unique technical nature of the repository. Such a facility has never before been licensed; furthermore, the duration of isolation of waste demanded by the proposed EPA standard will require a degree of reliance on probabilistic performance assessment as proof of compliance that is a first of a kind for any industry. The licensing strategy is also made necessary by the complex interrelationships among the many involved governmental agencies and even within DOE itself, and because these relationships will change with time. Program activities which recognize these relationships are essential for implementing the Act. The guiding principle in this strategy is an overriding commitment to safeguarding public health and safety and to protecting the environment

  19. RM - ODP to express nuclear licensing

    International Nuclear Information System (INIS)

    Barbosa, E.A.; Martucci, M. Jr.

    2002-01-01

    The scope of CNEN (Comissao Nacional de Energia Nuclear) is established by standards and procedures, which allow one context where several activities for nuclear licensing are realized by persons, machines and other entities of real world and by software systems. The CNEN objectives for licensing nuclear installations can be specified and they define how the systems are consisted, its nature, and which important elements were considered relevant for its constitution. The behavior, where the software will be operated, was likely defined in this paper through all aspects of its business process, which means from its licensing context. The concepts and definition showed here defined one specifics business domain, through ODP context. The functionalities of nuclear licensing process, the relationship scope and the rules of interaction that contributed for to specify the nuclear licensing process were defined, too. Therefore, the definition of the domain follows the orientation of architecture concepts and allows to implement the reflection model, where, with the auxiliary from IDEF0 (Integration Definition for Function Modeling) diagrams, the interactions between extern domains were mapped

  20. Real-Time Vehicle Speed Estimation Based on License Plate Tracking in Monocular Video Sequences

    Directory of Open Access Journals (Sweden)

    Aleksej MAKAROV

    2016-02-01

    Full Text Available A method of estimating the vehicle speed from images obtained by a fixed over-the-road monocular camera is presented. The method is based on detecting and tracking vehicle license plates. The contrast between the license plate and its surroundings is enhanced using infrared light emitting diodes and infrared camera filters. A range of the license plate height values is assumed a priori. The camera vertical angle of view is measured prior to installation. The camera tilt is continuously measured by a micro-electromechanical sensor. The distance of the license plate from the camera is theoretically derived in terms of its pixel coordinates. Inaccuracies due to the frame rate drift, to the tilt and the angle of view measurement errors, to edge pixel detection and to a coarse assumption of the vehicle license plate height are analyzed and theoretically formulated. The resulting system is computationally efficient, inexpensive and easy to install and maintain along with the existing ALPR cameras.

  1. Operating reactors licensing actions summary

    International Nuclear Information System (INIS)

    1982-04-01

    The operating reactors licensing actions summary is designed to provide the management of the Nuclear Regulatory Commission (NRC) with an overview of licensing actions dealing with operating power and nonpower reactors. These reports utilize data collected from the Division of Licensing in the Office of Nuclear Reactor Regulation and are prepared by the Office of Management and Program Analysis

  2. Improvement suggestions on license extension management for civil nuclear safety equipment activities

    International Nuclear Information System (INIS)

    Sun Xingjian; Liu Hongji; Han Guoli; Jia Fengcai

    2013-01-01

    Based on the concepts of Clear Requirements, Comprehensive Review, Objective Assessment, Dynamic Management, this paper gives improvement suggestions on license extension management for civil nuclear safety equipment design, manufacture, installation and non-destructive examination activities, which include establishing a relatively unified license extension review standard, combining multi-views and close linking license review and supervision, full utilizing the daily supervision and inspection results, as well as further improving motivation and elimination mechanism. (authors)

  3. The SLOWPOKE licensing model

    Energy Technology Data Exchange (ETDEWEB)

    Snell, V. G.; Takats, F.; Szivos, K.

    1989-08-15

    The SLOWPOKE Energy System (SES-10) is a 10 MW heating reactor that has been developed in Canada. It will be capable of running without a licensed operator in continuous attendance, and will be sited in urban areas. It has forgiving safety characteristics, including transient time-scales of the order of hours. A process called `up-front` licensing has been evolved in Canada to identify, and resolve, regulatory concerns early in the process. Because of the potential market in Hungary for nuclear district heating, a licensing plan has been developed that incorporates Canadian licensing experience, identifies specific Hungarian requirements, and reduces the risk of licensing delays by seeking agreement of all parties at an early stage in the program.

  4. Decree No. 77-1133 of 21 September 1977 made in implementation of Act No. 76-663 of 19 July 1976 on installations classified for purposes of environmental protection

    International Nuclear Information System (INIS)

    1977-01-01

    This Decree, amended in 1980 and 1985 implements the 1976 Act and contains provisions applying specifically to installations subject to licensing and others which apply solely to installations subject to declaration; also, certain provisions apply to all classified installations. As regards installations subject to licensing, the Decree details the licensing procedure: information to be contained in the application, accompanying documents, conditions of the hearing for issuance of the licensing decree, etc. In addition, it specifies for installations subject to declaration, the particulars to be contained in the declaration, the accompanying documents, the conditions for publicising it as well as the conditions for modifying the general specifications applicable to the installation declared. The provisions of the Decree common to both types of installation mainly concern inspections, conditions to be observed if there is a change in the operator or cessation of activities, and fines in case of non-compliance with the Decree (NEA) [fr

  5. Current status of the PBMR licensing project

    International Nuclear Information System (INIS)

    Mysen, A.; Clapisson, G.A.; Metcalf, P.E.

    2000-01-01

    The CNS is currently reviewing the PBMR conceptual design from a licensibility point of view. The PBMR concept is based on a High Temperature Gas Cooled Reactor - pebble bed reactor type. It is anticipated that the PBMR design will rely on inherent safety characteristics to contain fission products within fuel over the full range of design basis events. This feature combined with the high temperature integrity of the fuel and structural graphite, allows the safe use of a high coolant temperature, which allows consideration of the future development of this reactor for non-electrical applications of nuclear heat for industrial use. The CNS licensing approach requires that the licensing and design basis of the plant should respect prevailing international norms and practices and that a quantitative risk assessment should demonstrate compliance with the CNS fundamental safety standards. The first stage of the licensing process is now ongoing; this is a pre-application phase, which will result in a statement on licensibility being issued. Identification of the specific documentation requirements and information needed is required across every step of the licensing process. Top level regulatory requirements have been established for the PBMR. They include the CNS fundamental safety standard and basic licensing criteria, which describes requirements on licensees of nuclear installations regarding risk assessment and compliance with the safety criteria and define classification of licensing basis events. (author)

  6. Physical Protection Study of the Radio metallurgy Installation Using SAVIComputer Program

    International Nuclear Information System (INIS)

    Pinitoyo, Andreas

    2000-01-01

    Based on IAEA Recommendation on INFCIR/225/Rev.3 (The Physical Protectionof Nuclear Material), a nuclear installation shall have physical protectionsystem for protection or being secure on sabotage activities in theinstallation and thieve of nuclear materials. The recommendation states therequirements for physical protection of nuclear materials usage, transit andstorage. Radio metallurgy Installation of the Fuel Element and ReprocessingDevelopment Center (BATAN) at Serpong is a nuclear installation for researchon post irradiation of high radioactive spent fuel element, its processingand storage. The installation has risk on threat of a sabotage, which isdominant than thieve. The RMI building was designed and constructed ofphysical protection components and have been integrated with the BATAN Safetyand Security System and the Security Guards functions to be PhysicalProtection System for the RMI. By using the SAVI Computer Program with inputdata from the existing standards, assumptions for detection possibility,delay and response, that will result the probability of interruptions of theworst adversary paths PI = 0.1. These mean that the physical protectionsystems of the RMI shall be upgraded and improved in order to be reliable orbetter if the most of paths to the target PI = 1.0. (author)

  7. PC-based car license plate reader

    Science.gov (United States)

    Hwang, Chung-Mu; Shu, Shyh-Yeong; Chen, Wen-Yu; Chen, Yie-Wern; Wen, Kuang-Pu

    1992-11-01

    A car license plate reader (CLPR) using fuzzy inference and neural network algorithm has been developed in Industrial Technology Research Institute (ITRI) and installed in highway toll stations to identify stolen cars. It takes an average of 0.7 seconds to recognize a car license plate by using a PC with 80486-50 CPU. The recognition rate of the system is about 97%. The techniques of CLPR include vehicle sensing, image grab control, optic pre- processing, lighting, and optic character recognition (OCR). The CLPR can be used in vehicle flow statistics, the checking of stolen vehicles, automatic charging systems in parking lots or garage management, and so on.

  8. The Savannah River Site's Groundwater Monitoring Program 1991 well installation report

    International Nuclear Information System (INIS)

    1992-06-01

    This report is a summary of the well and environmental soil boring information compiled for the groundwater monitoring program of the Environmental Protection Department/Environmental Monitoring Section (EPD/EMS) at the Savannah River Site (SRS) during 1991. It includes discussion of environmental soil borings, surveying, well installations, abandonments, maintenance, and stabilization

  9. Licensing authority's control of radiation sources and nuclear materials in Brazil

    International Nuclear Information System (INIS)

    Binns, D.A.C.

    2002-01-01

    Full text: The Brazilian Nuclear Energy Commission is the national licensing authority and among its responsibilities is the control of nuclear materials and radiation sources. This control is carried out in three different ways: 1) Control of the import and export of nuclear materials and radiation sources. To be able to import or export any nuclear material or radiation source, the user has to have an explicit permission of the licensing authority. This is controlled by electronic means in which the user has to fill a special form found on the licensing authority's home page, where he has to fill in his name, license number, license number of his radiation protection officer and data of the material to be imported or exported. These data are checked with a data base that contains all the information of the licensed users and qualified personnel before authorization is emitted. The airport authorities have already installed x-ray machines to check all baggages entering or leaving the country. 2) Transport and transfer permit for radiation sources. In order to transport and/or transfer radiations sources and nuclear materials within the country, the user(s) have to submit an application to the licensing authority. The user(s) fill out an application form where he fills in his company's name, licensing I.D., radiation protection officer's name and I.D and identification of the sources involved. These information are checked with the licensing operations data before the operations is permitted. 3) Inspections and radiation monitoring systems. Routine and regulatory inspections are continuously carried out where the user's radiation sources and nuclear materials inventory are checked. Also the physical security and protection of these materials are verified. The installation of monitoring systems is an item that is being discussed with the airport authorities so as to increase the possibilities of detecting any illegal transport of these materials. (author)

  10. Stability in licensing requirements: a technical perspective

    International Nuclear Information System (INIS)

    Szalay, R.A.

    1978-01-01

    The serious difficulties encountered in the licensing procedure for nuclear power plants in the United States have resulted in the elaboration of a Bill on the siting and licensing of nuclear installations for the purpose of reforming the present system. The author fears, however, that this Bill will not reduce the complexity of present regulations and will be unable to reach the object sought which is to reduce the length of the procedure; he analyses the technical and political reasons underlying this situation, and in particular the role of the staff of the Nuclear Regulatory Commission. (NEA) [fr

  11. Challenges of SMR licensing practices

    Energy Technology Data Exchange (ETDEWEB)

    Soderholm, K., E-mail: kristiina.soderholm@fortum.com [Fortum Power, Espoo (Finland)

    2012-12-15

    This paper aims to increase the understanding of high level Nuclear Power Plant (NPP) licensing processes in Finland, France, the UK, Canada and the USA. These countries have been selected for this study because of their different licensing processes and recent actions in new NPP construction. After discussing their similarities and differences, suitable features for Small Modular Reactor licensing can be emphasized and suggested. Some of the studied licensing processes have elements that are already quite well suited for application to SMRs, but all of these different national processes can benefit from studying and implementing lessons learned from SMR specific licensing needs. The main SMR features to take into account in licensing are standardization of the design, modularity, mass production and serial construction. Modularity can be divided into two different categories: the first category is simply a single unit facility constructed of independently engineered modules (e.g., construction process for Westinghouse AP-1000 NPP) and the second is a facility structure composed of many reactor modules where modules are manufactured in factories and installed into the facility as needed (e.g., NuScale Power SMR design). Short construction schedules will not be fully benefited from if the long licensing process prolongs the commissioning and approach to full-power operation. The focus area of this study is to better understand the possibility of SMR deployment in small nuclear countries, such as Finland, which currently has four operating NPPs. The licensing process needs to be simple and clear to make SMR deployment feasible from an economical point of view. This paper uses public information and interviews with experts to establish the overview of the different licensing processes and their main steps. A high-level comparison of the licensing steps has been carried out. Certain aspects of the aviation industry licensing process have also been studied and certain

  12. Nuclear plant license renewal

    International Nuclear Information System (INIS)

    Gazda, P.A.; Bhatt, P.C.

    1991-01-01

    During the next 10 years, nuclear plant license renewal is expected to become a significant issue. Recent Electric Power Research Institute (EPRI) studies have shown license renewal to be technically and economically feasible. Filing an application for license renewal with the Nuclear Regulatory Commission (NRC) entails verifying that the systems, structures, and components essential for safety will continue to perform their safety functions throughout the license renewal period. This paper discusses the current proposed requirements for this verification and the current industry knowledge regarding age-related degradation of structures. Elements of a license renewal program incorporating NRC requirements and industry knowledge including a schedule are presented. Degradation mechanisms for structural components, their significance to nuclear plant structures, and industry-suggested age-related degradation management options are also reviewed

  13. General aspects of radiological protection to consider for the licensing a hospital cyclotron

    International Nuclear Information System (INIS)

    Andrada Contardi, F.A.; Fruttero, N.H.; Bozzo, R.H.; Moschella, E.G.

    2010-01-01

    The use of PET/PET-CT studies for a variety of diagnoses has increased significantly on a global scale. Modern medical cyclotrons must be placed in or near hospitals on account of the short radioactive half-life of the pharmaceuticals used in such studies. Many countries in Latin America are now licensing cyclotrons and laboratories for the production of radio-pharmaceuticals for the first time, and most are expected to have installations within the near future. This report outlines the general aspects of radiological protection important to consideration during the licensing of these facilities, and includes the following: general operation of the cyclotron and laboratory for the production of radiopharmaceuticals, safety systems (shielding, interlocks, ventilation, manual safety systems, alarms and monitors), and general aspects for licensing an installation (monitoring, accidental and incidental events, activation of components, etc.) and personnel. (authors) [es

  14. 47 CFR 80.13 - Station license required.

    Science.gov (United States)

    2010-10-01

    ... signals using a marine radio operating in the 156-162 MHz band, any type of AIS, any type of EPIRB, and any type of radar installation. All other transmissions must be authorized under a ship station... paragraph (c) of this section, stations in the maritime service must be licensed by the FCC either...

  15. Python Introduction and Installation

    Directory of Open Access Journals (Sweden)

    William J. Turkel

    2012-07-01

    Full Text Available This first lesson in our section on dealing with Online Sources is designed to get you and your computer set up to start programming. We will focus on installing the relevant software – all free and reputable – and finally we will help you to get your toes wet with some simple programming that provides immediate results. In this opening module you will install the Python programming language, the Beautiful Soup HTML/XML parser, and a text editor. Screencaps provided here come from Komodo Edit, but you can use any text editor capable of working with Python. Here’s a list of other options: Python Editors. Once everything is installed, you will write your first programs, “Hello World” in Python and HTML.

  16. Operating reactors licensing actions summary. Vol. 3, No. 3

    International Nuclear Information System (INIS)

    1983-04-01

    The operating reactors licensing actions summary is designed to provide the management of the Nuclear Regularory Commission (NRC) with an overview of licensing actions dealing with operating power and nonpower reactors. These reports utilize data collected from the Division of Licensing in the Office of Nuclear Reactor Regulation and are prepared by the Office of Management and Program Analysis. This summary report is published primarily for internal NRC use in managing the operating reactors licensing actions program

  17. THTR steam generator licensing experience as seen by the manufacturer

    International Nuclear Information System (INIS)

    Fricker, H.W.

    1981-01-01

    This paper describes the licensing procedures of the manufacture of the 300 MWe THTR steam generator. The following problems are discussed: operating data, design, materials used, manufacture and installation of the generator, and also quality control

  18. Licensing procedure for the construction and operation of nuclear installations within the EEC member states

    International Nuclear Information System (INIS)

    Didier, J.M.

    1976-08-01

    For Belgium and Luxembourg, the authorization procedure varies according to the Class in which the installation concerned falls (assigned according to the degree of hazard involved: Classes I, II or III). Moreover, separate authorizations are needed, one for construction and another for operation of Class I and II installations. With respect to Germany also, two such separate authorization are needed, but there is no specific procedure relating to the potential extent of hazard involved in the installation concerned. In France, the 'basic' nuclear installations are subject to a special procedure. Furthermore, the construction and operation of these installations are also subject to two separate authorizations. While the latter two authorizations are required in Italy for the main nuclear installations, no system of 'classified' installations exists according to extent of hazard involved. Similar legislation is applicable in the Netherlands. Neither does such a system of 'classified' installations exist in the United Kingdom. Moreover, there is only one single authorization (the 'site licence'), which is succesively adapted during construction. On the other hand, in Denmark and Ireland, no detailed legislation has been developed on the subject

  19. International Harmonization of Reactor Licensing Regulations

    International Nuclear Information System (INIS)

    Kuhnt, Dietmar.

    1977-01-01

    The purpose of a harmonization policy for reactor licensing regulations on the basis of already considerable experience is to attain greater rationalisation in this field, in the interest of economic policy and healthy competition, and most important, radiation protection and safety of installations. This paper considers the legal instruments for such harmonization and the conditions for their implementation, in particular within the Communities framework. (NEA) [fr

  20. Utilizing Facebook and Automated Telephone Calls to Increase Adoption of a Local Smoke Alarm Installation Program.

    Science.gov (United States)

    Frattaroli, Shannon; Schulman, Eric; McDonald, Eileen M; Omaki, Elise C; Shields, Wendy C; Jones, Vanya; Brewer, William

    2018-05-17

    Innovative strategies are needed to improve the prevalence of working smoke alarms in homes. To our knowledge, this is the first study to report on the effectiveness of Facebook advertising and automated telephone calls as population-level strategies to encourage an injury prevention behavior. We examine the effectiveness of Facebook advertising and automated telephone calls as strategies to enroll individuals in Baltimore City's Fire Department's free smoke alarm installation program. We directed our advertising efforts toward Facebook users eligible for the Baltimore City Fire Department's free smoke alarm installation program and all homes with a residential phone line included in Baltimore City's automated call system. The Facebook campaign targeted Baltimore City residents 18 years of age and older. In total, an estimated 300 000 Facebook users met the eligibility criteria. Facebook advertisements were delivered to users' desktop and mobile device newsfeeds. A prerecorded message was sent to all residential landlines listed in the city's automated call system. By the end of the campaign, the 3 advertisements generated 456 666 impressions reaching 130 264 Facebook users. Of the users reached, 4367 individuals (1.3%) clicked the advertisement. The automated call system included approximately 90 000 residential phone numbers. Participants attributed 25 smoke alarm installation requests to Facebook and 458 to the automated call. Facebook advertisements are a novel approach to promoting smoke alarms and appear to be effective in exposing individuals to injury prevention messages. However, converting Facebook message recipients to users of a smoke alarm installation program occurred infrequently in this study. Residents who participated in the smoke alarm installation program were more likely to cite the automated call as the impetus for their participation. Additional research is needed to understand the circumstances and strategies to effectively use the social

  1. Usefulness of the DETECT program for assessing the internal structure of dimensionality in simulated data and results of the Korean nursing licensing examination

    Directory of Open Access Journals (Sweden)

    Dong Gi Seo

    2017-12-01

    Full Text Available Purpose The dimensionality of examinations provides empirical evidence of the internal test structure underlying the responses to a set of items. In turn, the internal structure is an important piece of evidence of the validity of an examination. Thus, the aim of this study was to investigate the performance of the DETECT program and to use it to examine the internal structure of the Korean nursing licensing examination. Methods Non-parametric methods of dimensional testing, such as the DETECT program, have been proposed as ways of overcoming the limitations of traditional parametric methods. A non-parametric method (the DETECT program was investigated using simulation data under several conditions and applied to the Korean nursing licensing examination. Results The DETECT program performed well in terms of determining the number of underlying dimensions under several different conditions in the simulated data. Further, the DETECT program correctly revealed the internal structure of the Korean nursing licensing examination, meaning that it detected the proper number of dimensions and appropriately clustered the items within each dimension. Conclusion The DETECT program performed well in detecting the number of dimensions and in assigning items for each dimension. This result implies that the DETECT method can be useful for examining the internal structure of assessments, such as licensing examinations, that possess relatively many domains and content areas.

  2. Operating reactors licensing actions summary. Vol. 3, No. 6

    International Nuclear Information System (INIS)

    1983-07-01

    The operating reactors licensing actions summary is designed to provide the management of the Nuclear Regulatory Commission (NRC) with an overview of licensing actions dealing with operating power and nonpower reactors. These reports utilize data collected from the Division of Licensing in the Office of Nuclear Reactor Regulation and are prepared by the Office of Management and Program Analysis. This summary report is published primarily for internal NRC use in managing the operating reactors licensing actions program. Its content will change based on NRC management informational requirements

  3. Generational differences among newly licensed registered nurses.

    Science.gov (United States)

    Keepnews, David M; Brewer, Carol S; Kovner, Christine T; Shin, Juh Hyun

    2010-01-01

    Responses of 2369 newly licensed registered nurses from 3 generational cohorts-Baby Boomers, Generation X, and Generation Y-were studied to identify differences in their characteristics, work-related experiences, and attitudes. These responses revealed significant differences among generations in: job satisfaction, organizational commitment, work motivation, work-to-family conflict, family-to-work conflict, distributive justice, promotional opportunities, supervisory support, mentor support, procedural justice, and perceptions of local job opportunities. Health organizations and their leaders need to anticipate intergenerational differences among newly licensed nurses and should provide for supportive working environments that recognize those differences. Orientation and residency programs for newly licensed nurses should be tailored to the varying needs of different generations. Future research should focus on evaluating the effectiveness of orientation and residency programs with regard to different generations so that these programs can be tailored to meet the varying needs of newly licensed nurses at the start of their careers. Copyright 2010 Mosby, Inc. All rights reserved.

  4. 76 FR 60937 - Draft License Renewal Interim Staff Guidance LR-ISG-2011-02; Aging Management Program for Steam...

    Science.gov (United States)

    2011-09-30

    ...-2011-02; Aging Management Program for Steam Generators AGENCY: Nuclear Regulatory Commission. ACTION... License Renewal Interim Staff Guidance (LR-ISG), LR-ISG-2011-02, ``Aging Management Program for Steam... using Revision 3 of NEI 97-06 to manage steam generator aging. The Draft LR-ISG revises the NRC staff's...

  5. Python Introduction and Installation

    OpenAIRE

    William J. Turkel; Adam Crymble

    2012-01-01

    This first lesson in our section on dealing with Online Sources is designed to get you and your computer set up to start programming. We will focus on installing the relevant software – all free and reputable – and finally we will help you to get your toes wet with some simple programming that provides immediate results. In this opening module you will install the Python programming language, the Beautiful Soup HTML/XML parser, and a text editor. Screencaps provided here come from Komodo ...

  6. Two Approaches to Reactor Decommissioning: 10 CFR Part 50 License Termination and License Amendment, Lessons Learned from the Regulatory Perspective

    International Nuclear Information System (INIS)

    Watson, B.A.; Buckley, J.T.; Craig, C.M.

    2006-01-01

    Trojan Nuclear Plant (Trojan) and Maine Yankee Nuclear Plant (Maine Yankee) were the first two power reactors to complete decommissioning under the U. S. Nuclear Regulatory Commission's (NRC's) License Termination Rule (LTR), 10 CFR Part 20, Subpart E. The respective owners' decisions to decommission the sites resulted in different approaches to both the physical aspects of the decommissioning, and the approach for obtaining approval for completing the decommissioning in accordance with regulations. Being in different States, the two single-unit pressurized water reactor sites had different State requirements and levels of public interest that impacted the decommissioning approaches. This resulted in significant differences in decommissioning planning, conduct of decommissioning operations, volumes of low- level radioactive waste disposed, and the final status survey (FSS) program. While both licensees have Independent Spent Fuel Storage Installations (ISFSIs), Trojan obtained a separate license for the ISFSI in accordance with the requirements of 10 CFR Part 72 and terminated their 10 CFR Part 50 license. Maine Yankee elected to obtain a general license under 10 CFR Part 50 for the ISFSI and reduce the physical site footprint to the ISFSI through a series of license amendments. While the NRC regulations are flexible and allow different approaches to ISFSI licensing there are separate licensing requirements that must be addressed. In 10 CFR 50.82, the NRC mandates public participation in the decommissioning process. For Maine Yankee, public input resulted in the licensee entering into an agreement with a concerned citizen group and resulted in State legislation that significantly lowered the dose limit below the NRC radiological criteria of 25 mrem (0.25 mSv) per year (yr) in 10 CFR 20.1402 for unrestricted use. The lowering of the radiological criteria resulted in a significant dose modeling effort using site-specific Derived Concentrations Guideline Levels (DCGLs

  7. Licensing decisions and safety research related to LMFBR accidents

    International Nuclear Information System (INIS)

    Denise, R.P.; Speis, T.P.; Kelber, C.N.; Curtis, R.T.

    1977-01-01

    The licensing approach which ensures adequate protection of the public health and safety against serious accidents is described. This paper describes the role of core melt and core disruptive accidents in the design, safety research, and licensing processes, using the Clinch River Breeder Reactor (CRBR) as a focal point. Major design attention is placed on the prevention of these accidents so that the probability of core melt accidents is reduced to a sufficiently low level that they are not treated as design basis accidents. Additional requirements are placed upon the design to further reduce residual risk. This licensing process is supported by a confirmatory research program designed to provide an independent basis for licensing judgements. It has as a goal the resolution of generic safety issues prior to the establishment of a commercial LMFBR industry. The program includes accident analysis, experiments in materials interactions, aerosol transport and system integrity and planning for new safety test facilities. The problems are approached in a multi-disciplinary functional manner that identifies key safety issues and centralizes efforts to resolve them. The near term objectives of the program support the licensing of the Clinch River Breeder Reactor (CRBR) and the proposed Prototype Large Breeder Reactor (PLBR). The long term objectives of the program support the licensing of commercial LMFBRs during the late 1980's and beyond. This safety research is designed to provide an independent basis for the licensing judgements which must be made by the Nuclear Regulatory Commission

  8. Methodology to identify, review, and evaluate components for license renewal

    International Nuclear Information System (INIS)

    Carlson, D.D.; Gregor, F.E.; Walker, R.S.

    1988-01-01

    A methodology has been developed to systematically identify, review, and evaluate plant equipment for license renewal. The method builds upon the existing licensing basis, operating history, and accepted deterministic and probabilistic techniques. Use of these approaches provides a focus for license renewal upon those safety-significant systems and components that are not routinely replaced, refurbished, or subject to detailed inspection as part of the plant's existing test, maintenance, and surveillance programs. Application of the method identified the PWR and BWR systems that should be subjected to detailed license renewal review. Detailed examination of two example systems demonstrates the approach. The review and evaluation of plant equipment for license renewal differ from the initial licensing of the plant. A substantial operating history has been established, the licensing basis has evolved from the original one, and plant equipment has been subject to periodic maintenance and surveillance throughout its life. In consideration of these differences, a basis for license renewal is needed. License renewal should be based upon continuation of the existing licensing basis and recognition of existing programs and operating history

  9. The function of specialized organization in work safety engineering for nuclear installations

    International Nuclear Information System (INIS)

    Salvatore, J.E.L.

    1989-01-01

    The attributions of Brazilian CNEN in the licensing procedures of any nuclear installation are discussed. It is shown that the work safety engineering and industrial safety constitute important functions for nuclear safety. (M.C.K.) [pt

  10. The USNCR license renewal process

    International Nuclear Information System (INIS)

    Kuo, Pao-Tsin

    2002-01-01

    The US Congress promulgated a law in 1954, entitled 'Atomic Energy Act'. This Act states that operating licenses for commercial nuclear power plants are limited to a fixed term of 40 years, but they may be renewed for a period not to exceed 20 years. The terms were established mainly for economic considerations, not based on technical limitations. The U.S. Nuclear Regulatory Commission (USNRC) published the license renewal rule, Title 10 of the Code of Federal Regulations, Part 54 (10 CFR Part 54), in December, 1991. The rule has since been amended in May, 1995. The underlying principle of the rule is that the regulatory process is adequate for ensuring safety of operating plants. The regulatory process includes NRC's issuance of Orders, Bulletins, Generic Letters, and Information Notices, as well as a number of special inspections in addition to the continuous oversight and routine inspection activities performed by on-site inspectors. Because of this comprehensive regulatory process, compilation of the current license basis or re-verification of the current licensing basis is not considered necessary for a license renewal review. The USNRC also determined on the basis of the findings of its research programs that active structures and components are well maintained by the existing programs. Therefore, the focus of the license renewal review is on passive, long-lived structures and components and on time-limited ageing analyses. The time-limited ageing analyses are for those structures and components which were originally designed to a 40 year service life

  11. Decree No 74-945 of 6 November 1974 concerning gaseous radioactive effluent releases from large nuclear installations and nuclear installations located on the same site

    International Nuclear Information System (INIS)

    1974-01-01

    This Decree prescribes the licensing for the release of gaseous wastes from nuclear installations as well as the technical supervision of such operations. It does not apply to the transport of radioactive effluents which is governed by the regulations on the transport of dangerous goods. (NEA) [fr

  12. Safety and licensing requirements in the Republic of South Africa

    International Nuclear Information System (INIS)

    Simpson, D.M.; Langford, E.L.

    1986-01-01

    The principles for licensing of nuclear installations in South Africa are based on the control of mortality risk to the operators of an installation and the population resident in the vicinity of the site. This paper describes the development of this safety philosophy, and the nuclear licensing process used in this country. The structure of the nuclear regulatory function is briefly described, including the respective roles of the Atomic Energy Corporation, Licencing Branch and the Council for Nuclear Safety. The development of risk criteria and quantitative release magnitude-probability criteria for radioactive material is outlined. Tasks that have to be undertaken by a potential waste disposal site licensee before a site licence is issued are described. Once the facility is commissioned periodic monitoring procedures will have to be adopted throughout the lifetime of the facility. The scope of typical monitoring activities is outlined and the ongoing analyses to be performed and the records to be kept are discussed

  13. Assessment of the licensing aspects of HTGR in Yugoslavia

    International Nuclear Information System (INIS)

    Varazdinec, Z.

    1990-01-01

    This paper deals not only with the licensing procedure in Yugoslavia, but also reflects the Utility/Owner approach to the assessment of the licensability of the HTGR during the site selection process and especially during bid evaluation process. Besides the description of the existing procedure which was implemented on licensing of LWR program, the assessment of some licensing aspects of HTGR has been presented to describe possible implementation on licensing procedure. (author)

  14. Assessment of the licensing aspects of HTGR in Yugoslavia

    Energy Technology Data Exchange (ETDEWEB)

    Varazdinec, Z [Institut za Elektroprivredu-Zagreb, Zagreb (Yugoslavia)

    1990-07-01

    This paper deals not only with the licensing procedure in Yugoslavia, but also reflects the Utility/Owner approach to the assessment of the licensability of the HTGR during the site selection process and especially during bid evaluation process. Besides the description of the existing procedure which was implemented on licensing of LWR program, the assessment of some licensing aspects of HTGR has been presented to describe possible implementation on licensing procedure. (author)

  15. Decree 2869/1972 of 21 July approving the Regulations on nuclear and radioactive installations

    International Nuclear Information System (INIS)

    1972-01-01

    This Decree determines nuclear and radioactive installations and establishes their licensing system which is carried out in several stages and differs according to the category concerned. The procedures cover in particular prior authorization, construction licence and operating licence. Provision is also made for inspections. The Annex to the Decree classifies the radionuclides for determining the category of the installation. (NEA) [fr

  16. Sharing of responsibilities between central and local authorities with regard to the licensing of nuclear installations

    International Nuclear Information System (INIS)

    Peltzer, P.

    1986-01-01

    With regard to sharing of responsibility in the field of nuclear licensing between central and local authorities, the Belgian State has entered into a new phase of regionalisation since the enactment of the law of August 8, 1980. This might entail a conflict of competence in case of the licensing of nuclear power plants. A general survey of foreign legislations seems to indicate that a similar risk also exists in other countries. (CW) [de

  17. Licensing of New Nuclear Power Plants in Canada

    International Nuclear Information System (INIS)

    Schwarz, Garry; Miller, Doug

    2011-01-01

    The regulatory process for new power plant licensing in Canada, from receipt of the initial application to commercial operation, can be divided into three phases: - Environmental Assessment (EA) and License to Prepare Site; - License to Construct; and - License to Operate. The Nuclear Safety and Control Act (NSCA) does not have provisions for combined licenses for site preparation, construction, or operation. Separate licenses must, therefore, be granted for each phase, and would be issued in sequence. However, applications to prepare a site, to construct and to operate a new nuclear power plant could be assessed in parallel. The total duration from the application for the License to Prepare Site to the issuance of the License to Operate (which is a prerequisite for first fuel load) has been established as 9 years subject to certain factors. To help facilitate this timeline, the CNSC has undertaken an aggressive program of documenting regulatory practices, requirements and guidance to assist applicants in submitting complete applications. Working level procedures to assist CNSC staff in their review of submissions are also under development. Extensive program and project management has been introduced to ensure that timelines will be achieved. In parallel with the above activities, regulatory oversight measures to be employed during site preparation activities and plant construction and commissioning are also being developed. On the international front, the CNSC is participating in the MDEP program to leverage the resources and knowledge of other national regulatory authorities in reviews the CNSC is undertaking. The CNSC also participates in IAEA and other international activities to utilize/adapt international practices as appropriate in Canada. (authors)

  18. Licensing plan for UMTRA project disposal sites

    International Nuclear Information System (INIS)

    1993-09-01

    The Uranium Mill Tailings Remedial Action (UMTRA) Project Office developed a plan to define UMTRA Project licensing program objectives and establish a process enabling the DOE to document completion of remedial actions in compliance with 40 CFR 1 92 and the requirements of the NRC general license. This document supersedes the January 1987 Project Licensing Plan (DOE, 1987). The plan summarizes the legislative and regulatory basis for licensing, identifies participating agencies and their roles and responsibilities, defines key activities and milestones in the licensing process, and details the coordination of these activities. This plan provides an overview of the UMTRA Project from the end of remedial actions through the NRC's acceptance of a disposal site under the general license. The licensing process integrates large phases of the UMTRA Project. Other programmatic UMTRA Project documents listed in Section 6.0 provide supporting information

  19. Aging management review for license renewal and plant life management

    International Nuclear Information System (INIS)

    Rinckel, M.A.; Young, G.G.

    2002-01-01

    license renewal for 25 nuclear units by 2005. It is anticipated that over 90% of the 103 operating nuclear plants in the United States will pursue license renewal and seek an additional 20 years of operation. Some plants may pursue operation to 80 years or longer since the license renewal rule does not limit the operating life of a nuclear power plant. The estimated cost to prepare and process a license renewal application is approximately $10M to $15M, which includes NRC review fees. The NRC review for license renewal is strictly a safety review and plant economics is not a consideration. However, economics will drive the decision to pursue license renewal for U.S. nuclear power plants. For nuclear units with strong performance records, license renewal is a good business decision when compared to the cost of building new generating capacity. The license renewal rule focuses on ageing of passive long-lived components and ageing management programs that manage those structures and components. Ninety to ninety-five percent of the ageing management programs credited in a plant license renewal application are existing programs (e.g., ASME Section XI, Chemistry Control Program, and Steam Generator Integrity). Typical examples of new programs required to manage ageing include reactor vessel internals, small bore Class 1 piping, Alloy 600, buried piping, and buried high voltage cable exposed to wetted environments. At present, there have been no commitments by any utility to replace components as a result of license renewal. After the NRC has approved a license renewal application, the credited ageing management programs (i.e., existing and new) become commitments for the remaining plant life. These commitments typically form the bases for a comprehensive plant life management program (PLIM). PLIM differs from license renewal in that it considers active and passive components as well as economics of plant operation and maintenance. Plants that have recently received renewed

  20. Safety of nuclear installations

    International Nuclear Information System (INIS)

    1991-01-01

    In accordance with the Nuclear Energy Act, a Licence may only be issued if the precautions required by the state of the art have been taken to prevent damage resulting from the construction and operation of the installation. The maximum admissible body doses in the area around the installation which must be observed in planning constructional and other technical protective measures to counter accidents in or at a nuclear power station (accident planning values, are established). According to the Radiological Protection Ordinance the Licensing Authority can consider these precautions to have been taken if, in designing the installation against accidents, the applicant has assumed the accidents which, according to the Safety Criteria and Guidelines for Nuclear Power Stations published in the Federal Register by the Federal Minister of the Interior after hearing the competent senior state authorities, must determine the design of a nuclear power station. On the basis of previous experience from safety analysis, assessment and operation of nuclear power stations, the accident guidelines published here define which accidents are determinative for the safety-related design of PWR power stations and what verification -particularly with regard to compliance with the accident planning values of the Radiological Protection Ordinance -must be provided by the applicant. (author)

  1. LicenseScript: A Logical Language for Digital Rights Management

    NARCIS (Netherlands)

    Chong, C.N.; Corin, R.J.; Doumen, J.M.; Etalle, Sandro; Hartel, Pieter H.; Law, Y.W.; Tokmakoff, Andrew

    We propose LicenseScript, a language for digital rights management (DRM) based on multiset rewriting and logic programming. LicenseScript enjoys a precise syntax and semantics, and it is rich enough to embed other rights expression languages (REL). We show that LicenseScript is expressive and

  2. ISO and software quality assurance - licensing and certification of software professionals

    Energy Technology Data Exchange (ETDEWEB)

    Hare, J.; Rodin, L.

    1997-11-01

    This report contains viewgraphs on licensing and certifing of software professionals. Discussed in this report are: certification programs; licensing programs; why became certified; certification as a condition of empolyment; certification requirements; and examination structures.

  3. U.S. licensing process and ABWR certification

    International Nuclear Information System (INIS)

    Quirk, J.F.; Williams, W.A.

    1996-01-01

    Part 50 of Title 10 of the Code of Federal Regulation (CFR) establishes a two-step licensing process by which the U.S. Nuclear Regulatory Committee (NRC) authorizes nuclear reactor plant construction through issuance of a construction permit and authorizes operation by issuance of an operating license. At each stage, the NRC Staff conducts technical reviews and there is potential for public hearings. In 1989, the NRC issued a new, simplified licensing process: Part 52. The purpose of the Part 52 licensing process is to provide a regulatory framework that brings about earlier resolution of licensing issues. Because issues are not resolved early in the Part 50 licensing process, approval of an operating license is not assured until after a significant investment has been made in the plant. Part 52 increases the stability and certainty of the licensing process by providing for the early resolution of safety and environmental issues. The Part 52 licensing process features (1) early site permits, (2) design certification, and (3) combined construction permit and operating licenses. As part of the U.S. Advanced Light Water Reactor (ALWR) Program to revitalize the nuclear option through the integration of government/utility/industry efforts, GE undertook the role of applying for certification for its latest product line, the Advanced Boiling Water Reactor (ABWR), under the U.S. ABWR certification program. The ABWR design is an essentially complete plant. Initial application for design certification was in 1987 under Part 50. GE reapplied in late 1991 under the newly promulgated Part 52. Following seven years of intensive interactions with the NRC and ACRS, GE was awarded the first Final Design Approval (FDA) under Part 52. The Commission initiated rulemaking by publishing the proposed ABWR Certification Rule in the Federal Register in early 1995. Certification is anticipated mid-1996. (J.P.N.)

  4. Licensing issues

    International Nuclear Information System (INIS)

    Roberts, J.P.; Desell, L.J.; Birch, M.L.; Berkowitz, L.; Bader, J.F.

    1992-01-01

    To provide guidance for the Department of Energy's (DOE) Civilian Radioactive Waste Management Program, the Nuclear Regulatory Commission (NRC) has issued a draft regulatory guide on the Format and Content for the License Application for the High-Level Waste Repository (FCRG). To facilitate the development of the FCRG, NRC suggested that DOE use the draft guide as the basis for preparing an annotated outline for a license application. DOE is doing so using an iterative process called the Annotated Outline Initiative. DOE;s use of the Initiative will assist in achieving the desired incorporation of actual experience in the FCRG, contribute to the development of shared interpretation and understanding of NRC regulations, and provide other important programmatic benefits described in this paper

  5. Generic aging management programs for license renewal of BWR reactor coolant systems components

    International Nuclear Information System (INIS)

    Shah, V.N.; Liu, Y.Y.

    2002-01-01

    The paper reviews the existing generic aging management programs (AMPs) for the reactor coolant system (RCS) components in boiling water reactors (BWRs), including the reactor pressure vessel and internals, the reactor recirculation system, and the connected piping. These programs have been evaluated in the U.S. Nuclear Regulatory Commission (NRC) report, Generic Aging Lessons Learned (GALL), NUREG-1801, for their use in the license renewal process to manage several aging effects, including loss of material, crack initiation and growth, loss of fracture toughness, loss of preload, wall thinning, and cumulative fatigue damage. The program evaluation includes a review of ten attributes (scope of program, preventive actions, parameters monitored/inspected, detection of aging effects, monitoring and trending, acceptance criteria, corrective actions, confirmative process, administrative control, and operating experience) for their effectiveness in managing a specific aging effect in a given component(s). The generic programs are based on the ASME Section XI inservice inspection requirements; industry guidelines for inspection and evaluation of aging effects in BWR reactor vessel, internals, and recirculation piping; monitoring and control of BWR water chemistry; and operating experience as reported in the USNRC generic communications and industry reports. The review concludes that all generic AMPs are acceptable for managing aging effects in BWR RCS components during an extended period of operation and do not need further evaluation. However, the plant-specific programs for managing aging in certain RCS components during an extended period of operation do require further evaluation. For some plant-specific AMPs, the GALL report recommends an aging management activity to verify their effectiveness. An example of such an activity is a one-time inspection of Class 1 small-bore piping to ensure that service-induced weld cracking is not occurring in the piping. Several of

  6. Generic Aging Management Programs for License Renewal of BWR Reactor Coolant System Components

    International Nuclear Information System (INIS)

    Shah, V.N.; Liu, Y.Y.

    2002-01-01

    The paper reviews the existing generic aging management programs (AMPs) for the reactor coolant system (RCS) components in boiling water reactors (BWRs), including the reactor pressure vessel and internals, the reactor recirculation system, and the connected piping. These programs have been evaluated in the U.S. Nuclear Regulatory Commission (NRC) report, Generic Aging Lessons Learned (GALL), NUREG-1801, for their use in the license renewal process to manage several aging effects, including loss of material, crack initiation and growth, loss of fracture toughness, loss of preload, wall thinning, and cumulative fatigue damage. The program evaluation includes a review of ten attributes (scope of program, preventive actions, parameters monitored/inspected, detection of aging effects, monitoring and trending, acceptance criteria, corrective actions, confirmative process, administrative control, and operating experience) for their effectiveness in managing a specific aging effect in a given component(s). The generic programs are based on the ASME Section XI inservice inspection requirements; industry guidelines for inspection and evaluation of aging effects in BWR reactor vessel, internals, and recirculation piping; monitoring and control of BWR water chemistry; and operating experience as reported in the USNRC generic communications and industry reports. The review concludes that all generic AMPs are acceptable for managing aging effects in BWR RCS components during an extended period of operation and do not need further evaluation. However, the plant-specific programs for managing aging in certain RCS components during an extended period of operation do require further evaluation. For some plant-specific AMPs, the GALL report recommends an aging management activity to verify their effectiveness. An example of such an activity is a one-time inspection of Class 1 small-bore piping to ensure that service-induced weld cracking is not occurring in the piping. Several of

  7. System engineering in the Nuclear Regulatory Commission licensing process: Program architecture process and structure

    International Nuclear Information System (INIS)

    Romine, D.T.

    1989-01-01

    In October 1987, the U.S. Nuclear Regulatory Commission (NRC) established the Center for Nuclear Waste Regulatory Analyses at Southwest Research Institute in San Antonio, Texas. The overall mission of the center is to provide a sustained level of high-quality research and technical assistance in support of NRC regulatory responsibilities under the Nuclear Waste Policy Act (NWPA). A key part of that mission is to assist the NRC in the development of the program architecture - the systems approach to regulatory analysis for the NRC high-level waste repository licensing process - and the development and implementation of the computer-based Program Architecture Support System (PASS). This paper describes the concept of program architecture, summarizes the process and basic structure of the PASS relational data base, and describes the applications of the system

  8. Operator licensing examiner standards

    International Nuclear Information System (INIS)

    1994-06-01

    The Operator Licensing Examiner Standards provide policy and guidance to NRC examiners and establish the procedures and practices for examining licensees and applicants for reactor operator and senior reactor operator licenses at power reactor facilities pursuant to Part 55 of Title 10 of the Code of Federal Regulations (10 CFR 55). The Examiner Standards are intended to assist NRC examiners and facility licensees to better understand the initial and requalification examination processes and to ensure the equitable and consistent administration of examinations to all applicants. These standards are not a substitute for the operator licensing regulations and are subject to revision or other internal operator licensing policy changes. Revision 7 was published in January 1993 and became effective in August 1993. Supplement 1 is being issued primarily to implement administrative changes to the requalification examination program resulting from the amendment to 10 CFR 55 that eliminated the requirement for every licensed operator to pass an NRC-conducted requalification examination as a condition for license renewal. The supplement does not substantially alter either the initial or requalification examination processes and will become effective 30 days after its publication is noticed in the Federal Register. The corporate notification letters issued after the effective date will provide facility licensees with at least 90 days notice that the examinations will be administered in accordance with the revised procedures

  9. NUMARC view of license renewal criteria

    International Nuclear Information System (INIS)

    Edwards, D.W.

    1989-01-01

    The Atomic Energy Act and the implementing regulations of the US Nuclear Regulatory Commission (NRC) permit the renewal of nuclear plant operating licenses upon expiration of their 40-year license term. However, the regulatory process by which license renewal may be accomplished and the requirements for the scope and content of renewal applications are yet to be established. On August 29, 1988, the NRC published an Advanced Notice of Proposed Rulemaking regarding the subject of license renewal. This Advanced Notice and the NUREG which it references, NUREG-1317, Regulatory Options for Nuclear Plant License Renewal, provide the most recent regulatory thought on this issue. The basic issue addressed by NUREG-1317 is the definition of an adequate licensing basis for the renewal of a plant license. The report contemplates three alternatives in this regard. This paper discusses each of these three proposals. The NUMARC NUPLEX Working Group endorses a license renewal process based on a plant's current licensing basis along with an evaluation of the pertinent components, systems, and structures affected by age-related degradation. The NUMARC NUPLEX Working group believes that an appropriate scope for NRC review of the license renewal application should focus on those safety-significant structures systems, and components subject to significant age-related degradation that are not subject to existing recognized effective replacement, refurbishment, or inspection programs. The paper also briefly discusses NUMARC's view of the role of the Backfit Rule in the license renewal process

  10. Impact of New Radiation Safety Standards on Licensing Requirements of Nuclear Power Plant

    International Nuclear Information System (INIS)

    Strohal, P.; Subasic, D.; Valcic, I.

    1996-01-01

    As the outcomes of the newly introduced safety philosophies, new and more strict safety design requirements for nuclear installation are expected to be introduced. New in-depth defence measures should be incorporated into the design and operation procedure for a nuclear installation, to compensate for potential failures in protection or safety measures. The new requirements will also apply to licensing of NPP's operation as well as to licensing of nuclear sites, especially for radioactive waste disposal sites. This paper intends to give an overview of possible impacts of new internationally agreed basic safety standards with respect to NPP and related technologies. Recently issued new basic safety standards for radiation protection are introducing some new safety principles which may have essential impact on future licensing requirements regarding nuclear power plants and radioactive waste installations. These new standards recognize exposures under normal conditions ('practices') and intervention conditions. The term interventions describes the human activities that seek to reduce the existing radiation exposure or existing likelihood of incurring exposure which is not part of a controlled practice. The other new development in safety standards is the introduction of so called potential exposure based on the experience gained from a number of radiation accidents. This exposure is not expected to be delivered with certainty but it may result from an accident at a source or owing to an event or sequence of events of a probabilistic nature, including equipment failures and operating errors. (author)

  11. Collegiate Licensing in Canada and the Statutory Advantage.

    Science.gov (United States)

    Burshtein, Sheldon

    1985-01-01

    Discusses a specific provision in a Canadian statute enabling universities and other educational institutions to obtain protection and financial gain in a collegiate licensing program, an advantage not held in other countries or by other trademark licensers in Canada. (MSE)

  12. 45 CFR 1321.75 - Licenses and safety.

    Science.gov (United States)

    2010-10-01

    ... 45 Public Welfare 4 2010-10-01 2010-10-01 false Licenses and safety. 1321.75 Section 1321.75... AND COMMUNITY PROGRAMS ON AGING Service Requirements § 1321.75 Licenses and safety. The State shall... that the facility complies with all applicable State and local health, fire, safety, building, zoning...

  13. Operating reactors licensing actions summary. Volume 5, No. 2

    International Nuclear Information System (INIS)

    1985-04-01

    The Operating Reactors Licensing Actions Summary is designed to provide the management of the Nuclear Regulatory Commission (NRC) with an overview of licensing actions dealing with operating power and nonpower reactors. These reports utilize data collected from the Division of Licensing in the Office of Nuclear Reactor Regulation and are prepared by the Office of Resource Management. This summary report is published primarily for internal NRC use in managing the Operating Reactors Licensing Actions Program

  14. Graduated driver licensing and differential deterrence: The effect of license type on intentions to violate road rules.

    Science.gov (United States)

    Poirier, Brigitte; Blais, Etienne; Faubert, Camille

    2018-01-01

    In keeping with the differential deterrence theory, this article assesses the moderating effect of license type on the relationship between social control and intention to violate road rules. More precisely, the article has two objectives: (1) to assess the effect of license type on intentions to infringe road rules; and (2) to pinpoint mechanisms of social control affecting intentions to violate road rules based on one's type of driver license (a restricted license or a full license). This effect is examined among a sample of 392 young drivers in the province of Quebec, Canada. Drivers taking part in the Graduated Driver Licensing (GDL) program have limited demerit points and there is zero tolerance for drinking-and-driving. Propensity score matching techniques were used to assess the effect of the license type on intentions to violate road rules and on various mechanisms of social control. Regression analyses were then conducted to estimate the moderating effect of license type. Average treatment effects from propensity score matching analyses indicate that respondents with a restricted license have lower levels of intention to infringe road rules. While moral commitment and, to a lesser extent, the perceived risk of arrest are both negatively associated with intentions to violate road rules, the license type moderates the relationship between delinquent peers and intentions to violate road rules. The effect of delinquent peers is reduced among respondents with a restricted driver license. Finally, a diminished capability to resist peer pressure could explain the increased crash risk in months following full licensing. Copyright © 2017 Elsevier Ltd. All rights reserved.

  15. 77 FR 34093 - License Renewal for Calvert Cliffs Nuclear Power Plant, LLC's

    Science.gov (United States)

    2012-06-08

    ... Nuclear Power Plant, LLC's AGENCY: Nuclear Regulatory Commission. ACTION: Environmental assessment and... Spent Fuel Storage Installation (ISFSI) at the Calvert Cliffs Nuclear Power Plant site near Lusby... Cliffs Nuclear Power Plant, LLC (CCNPP) submitted an application to the NRC to renew NRC License SNM-2505...

  16. Accident consequence analysis models applied to licensing process of nuclear installations, radioactive and conventional industries

    International Nuclear Information System (INIS)

    Senne Junior, Murillo; Vasconcelos, Vanderley de; Jordao, Elizabete

    2002-01-01

    The industrial accidents happened in the last years, particularly in the eighty's decade, had contributed in a significant way to call the attention to government authorities, industry and society as a whole, demanding mechanisms for preventing episodes that could affect people's safety and environment quality. Techniques and methods already thoroughly used in the nuclear, aeronautic and war industries were then adapted for performing analysis and evaluation of the risks associated to other industrial activities, especially in the petroleum, chemistry and petrochemical areas. Some models for analyzing the consequences of accidents involving fire and explosion, used in the licensing processes of nuclear and radioactive facilities, are presented in this paper. These models have also application in the licensing of conventional industrial facilities. (author)

  17. Installing Python Modules with pip

    OpenAIRE

    Fred Gibbs

    2013-01-01

    This lesson shows you how to download and install Python modules. There are many ways to install external modules, but for the purposes of this lesson, we’re going to use a program called pip. As of Python 2.7.9 and newer, pip is installed by default. This tutorial will be helpful for anyone using older versions of Python (which are still quite common).

  18. Open licenses and their compliance with the new private law (new civil code)

    OpenAIRE

    Kráľ, Štefan

    2013-01-01

    Computer programs are widely licensed under open (public, open source, free) licenses. This thesis examines whether the open license (especially GNU GPL) is in compliance with the Czech law and which business models are used to generate profit distributing open computer programs. On the basis of analysis of legislation, case law and doctrinal literature the author assesses whether open licenses are admissible under the new Civil Code. The thesis also provides an overview of commonly used busi...

  19. Information handbook on independent spent fuel storage installations

    International Nuclear Information System (INIS)

    Raddatz, M.G.; Waters, M.D.

    1996-12-01

    In this information handbook, the staff of the U.S. Nuclear Regulatory Commission describes (1) background information regarding the licensing and history of independent spent fuel storage installations (ISFSIs), (2) a discussion of the licensing process, (3) a description of all currently approved or certified models of dry cask storage systems (DCSSs), and (4) a description of sites currently storing spent fuel in an ISFSI. Storage of spent fuel at ISFSIs must be in accordance with the provisions of 10 CFR Part 72. The staff has provided this handbook for information purposes only. The accuracy of any information herein is not guaranteed. For verification or for more details, the reader should refer to the respective docket files for each DCSS and ISFSI site. The information in this handbook is current as of September 1, 1996

  20. The "Clubs against Drugs" program in Stockholm, Sweden: two cross-sectional surveys examining drug use among staff at licensed premises

    Directory of Open Access Journals (Sweden)

    Gripenberg Abdon Johanna

    2011-02-01

    Full Text Available Abstract Background The objective of this study is to examine self-reported drug use among staff at licensed premises, types of drugs used, attitudes towards drugs, and observed drug use among guests. Results are presented from two measurement points (in 2001 and 2007/08. This study was carried out within the framework of the "Clubs against Drugs" program, which is a community-based multi-component intervention targeting licensed premises in Stockholm, Sweden. Methods Two cross-sectional surveys were conducted, the first in 2001 and the second in 2007/08. Staff at licensed premises attending server training were asked to participate in the anonymous survey. A survey was administered in a classroom setting and consisted of four sections: 1 demographics, 2 respondents' own drug use experience, 3 respondents' attitudes towards drug use, and 4 observed drug use among guests at licensed premises. Results Data were collected from 446 staff in 2001 and 677 staff in 2007/08. The four most commonly used drugs among staff were cannabis, cocaine, amphetamine, and ecstasy. The highest rates of drug use were reported by staff in the two youngest age groups, i.e., those younger than 25 and those between the ages of 25 and 29. In 2007/08 staff reported significantly lower rates of drug use than staff in 2001. Last year drug use for the sample in 2007/08 was 19% compared to 27% for the 2001 sample. While drug-using staff compared to non drug-using staff reported more observations of drug use among guests, they were less inclined to intervene. Overall, staff reported restrictive attitudes towards drugs. Conclusions The prevalence of life-time and last year drug use among staff at licensed premises is high compared to the general population in Sweden. Lower rates of self-reported drug use among staff were reported in 2007/08. The results of this study highlight that staff at licensed premises represent an important target population in club drug prevention

  1. Standard format and content for a license application to store spent fuel and high-level radioactive waste

    International Nuclear Information System (INIS)

    1989-09-01

    Subpart B, ''License Application, Form, and Contents,'' of 10 CFR Part 72, ''Licensing Requirements for the Independent Storage of Spent Nuclear Fuel and High-Level Radioactive Waste,'' specifies the information to be covered in an application for a license to store spent fuel in an independent spent fuel storage installation (ISFSI) or to store spent fuel and high-level radioactive waste in a monitored retrievable storage facility (MRS). However, Part 72 does not specify the format to be followed in the license application. This regulatory guide suggests a format acceptable to the NRC staff for submitting the information specified in Part 72 for license application to store spent fuel in an ISFSI or to store spent fuel and high-level radioactive waste in an MRS

  2. Licensed bases management for advanced nuclear plants

    International Nuclear Information System (INIS)

    O'Connell, J.; Rumble, E.; Rodwell, E.

    2001-01-01

    Prospective Advanced Nuclear Plant (ANP) owners must have high confidence that the integrity of the licensed bases (LB) of a plant will be effectively maintained over its life cycle. Currently, licensing engineers use text retrieval systems, database managers, and checklists to access, update, and maintain vast and disparate licensing information libraries. This paper describes the demonstration of a ''twin-engine'' approach that integrates a program from the emerging class of concept searching tools with a modern Product Data Management System (PDMS) to enhance the management of LB information for an example ANP design. (author)

  3. Licensed bases management for advanced nuclear plants

    Energy Technology Data Exchange (ETDEWEB)

    O' Connell, J [Duke Engineering and Services, Marlborough, MA (United States); Rumble, E; Rodwell, E [EPRI, Palo Alto, CA (United States)

    2001-07-01

    Prospective Advanced Nuclear Plant (ANP) owners must have high confidence that the integrity of the licensed bases (LB) of a plant will be effectively maintained over its life cycle. Currently, licensing engineers use text retrieval systems, database managers, and checklists to access, update, and maintain vast and disparate licensing information libraries. This paper describes the demonstration of a ''twin-engine'' approach that integrates a program from the emerging class of concept searching tools with a modern Product Data Management System (PDMS) to enhance the management of LB information for an example ANP design. (author)

  4. Regulatory requirements and administrative practice in safety of nuclear installations

    International Nuclear Information System (INIS)

    Servant, J.

    1977-01-01

    This paper reviews the current situation of the France regulatory rules and procedures dealing with the safety of the main nuclear facilities and, more broadly, the nuclear security. First, the author outlines the policy of the French administration which requires that the licensee responsible for an installation has to demonstrate that all possible measures are taken to ensure a sufficient level of safety, from the early stage of the project to the end of the operation of the plant. Thus, the administration performs the assessment on a case-by-case basis, of the safety of each installation before granting a nuclear license. On the other hand, the administration settles overall safety requirements for specific categories of installations or components, which determine the ultimate safety performances, but avoid, as far as possible, to detail the technical specifications to be applied in order to comply with these goals. This approach, which allows the designers and the licensees to rely upon sound codes and standards, gains the advantage of a great flexibility without imparing the nuclear safety. The author outlines the licensing progress for the main categories of installations: nuclear power plants of the PWR type, fast breeders, uranium isotope separation plants, and irradiated fuel processing plants. Emphasis is placed on the most noteworthy points: standardization of projects, specific risks of each site, problems of advanced type reactors, etc... The development of the technical regulations is presented with emphasis on the importance of an internationally concerned action within the nuclear international community. The second part of this paper describes the France operating experience of nuclear installations from the safety point of view. Especially, the author examines the technical and administrative utilization of data from safety significant incidents in reactors and plants, and the results of the control performed by the nuclear installations

  5. Operating reactors licensing actions summary. Volume 5, No. 6

    International Nuclear Information System (INIS)

    1985-08-01

    The operating reactors licensing actions summary is designed to provide the management of the Nuclear Regulatory Commission (NRC) with an overview of licensing actions dealing with operating power and nonpower reactors. These reports utilize data collected from the Division of Licensing in the Office of Nuclear Reactor Regulation and are prepared by the Office of Resource Management. This summary report is published for internal NRC use in managing the Operating Reactors Licensing Actions Program. Its content will change based on NRC management informational requirements

  6. Technical and legal aspects of the decommissioning of nuclear installations

    International Nuclear Information System (INIS)

    Rowden, M.A.; Fowler, S.E.

    1983-01-01

    Many of the plants licensed at the start of nuclear power programmes will require decommissioning in the 1990's and this issue should now be confronted by the nuclear industry, its regulators and governments. This paper deals with the United States programme and experience in the decommissioning of nuclear installations and describes alternative decommissioning methods including safety and financial aspects. (NEA) [fr

  7. Safety culture in nuclear installations - The role of the regulator

    International Nuclear Information System (INIS)

    Karigi, Alice W.

    2002-01-01

    Safety culture is an amalgamation of values, standards, morals and norms of acceptable behavior by the licensees, Radiation workers and the Regulator. The role played by a Regulator in establishing safety culture in a nuclear installation is that related to Authorization, review, assessment, inspection and enforcement. The regulator is to follow the development of a facility or activity from initial selection of the site through design, construction, commissioning, radioactive waste management through to decommissioning and closure. He is to ensure safety measures are followed through out the operation of the facility by laying down in the license conditions of controlling construction of nuclear installations and ensuring competence of the operators. (author)

  8. Management of the licensing of users of radioactive materials should be improved

    International Nuclear Information System (INIS)

    1976-01-01

    Radioactive material licenses are required for manufacturing nuclear fuel for reactors and for industrial, commercial, medical, and educational uses of radioactive materials. This type of license is not for constructing or operating nuclear power reactors and facilities for processing used nuclear fuels. This report discusses the need for better management improvements in the NRC's program for licensing the users. As of December 31, 1974, there were 8,253 active NRC-issued material licenses held by 6,310 licensees. The study reviewed NRC's policies, procedures, and practices, and examined recent evaluations of state programs to identify problems encountered by the states

  9. Installing QGIS 2.0 and Adding Layers

    Directory of Open Access Journals (Sweden)

    Jim Clifford

    2013-12-01

    Full Text Available In this lesson you will install QGIS software, download geospatial files like shapefiles and GeoTIFFs, and create a map out of a number of vector and raster layers. Quantum or QGIS is an open source alternative to the industry leader, ArcGIS from ESRI. QGIS is multiplatform, which means it runs on Windows, Macs, and Linux and it has many of the functions most commonly used by historians. ArcGIS is prohibitively expensive and only runs on Windows (though software can be purchased to allow it to run on Mac. However, many universities have site licenses, meaning students and employees have access to free copies of the software (try contacting your map librarian, computer services, or the geography department. QGIS is ideal for those without access to a free copy of Arc and it is also a good option for learning basic GIS skills and deciding if you want to install a copy of ArcGIS on your machine. Moreover, any work you do in QGIS can be exported to ArcGIS at a later date if you decide to upgrade. The authors tend to use both and are happy to run QGIS on Mac and Linux computers for basic tasks, but still return to ArcGIS for more advanced work. In many cases it is not lack of functions, but stability issues that bring us back to ArcGIS. For those who are learning Python with the Programming Historian, you will be glad to know that both QGIS and ArcGIS use Python as their main scripting language.

  10. Operating reactors licensing actions summary. Volume 5, Number 1

    International Nuclear Information System (INIS)

    1985-03-01

    This document is designed to provide the management of the Nuclear Regulatory Commission (NRC) with an overview of licensing actions dealing with operating power and nonpower reactors. These reports utilize data collected from the Division of Licensing in the Office of Nuclear Reactor Regulation and are prepared by the Office of Resource Management. This summary report is published primarily for internal NRC use in managing the operating reactors licensing actions program

  11. Licensed bases management for advanced nuclear plants

    Energy Technology Data Exchange (ETDEWEB)

    O' Connell, J. [Duke Engineering and Services, Marlborough, MA (United States); Rumble, E.; Rodwell, E. [EPRI, Palo Alto, CA (United States)

    2001-07-01

    Prospective Advanced Nuclear Plant (ANP) owners must have high confidence that the integrity of the licensed bases (LB) of a plant will be effectively maintained over its life cycle. Currently, licensing engineers use text retrieval systems, database managers, and checklists to access, update, and maintain vast and disparate licensing information libraries. This paper describes the demonstration of a ''twin-engine'' approach that integrates a program from the emerging class of concept searching tools with a modern Product Data Management System (PDMS) to enhance the management of LB information for an example ANP design. (author)

  12. Groundwater quality monitoring well installation for Waste Area Grouping at Oak Ridge National Laboratory, Oak Ridge, Tennessee. Environmental Restoration Program

    International Nuclear Information System (INIS)

    Mortimore, J.A.; Lee, T.A.

    1994-09-01

    This report documents the drilling and installation of 18 groundwater quality monitoring (GQM) wells on the perimeter of Waste Area Grouping (WAG) 11. WAG 11 (White Wing Scrap Yard) is located on the west end of East Fork Ridge between White Wing Road and the Oak Ridge Turnpike. The scrap yard is approximately 25 acres in size. The wells at WAG 11 were drilled and developed between January 1990 and October 1990. These wells were installed to characterize and assess the WAG in accordance with applicable Department of Energy, state, and Environmental Protection Agency regulatory requirements. The wells at WAG 11 were drilled with auger or air rotary rigs. Depending on the hydrogeologic conditions present at each proposed well location, one of four basic installation methods was utilized. Detailed procedures for well construction were specified by the Engineering Division to ensure that the wells would provide water samples representative of the aquifer. To ensure conformance with the specifications, Energy Systems Construction Engineering and ERCE provided continuous oversight of field activities. The purpose of the well installation program was to install GQM wells for groundwater characterization at WAG 11. Data packages produced during installation activities by the ERCE hydrogeologists are an important product of the program. These packages document the well drilling, installation, and development activities and provide valuable data for well sampling and WAG characterization. The forms contained in the packages include predrilling and postdrilling checklists, drilling and construction logs, development and hydraulic conductivity records, and quality control-related documents

  13. Technology of geographical information systems applied to the licensing of nuclear sector installations

    International Nuclear Information System (INIS)

    Oliveira, Aline F.G. De; Barreto, Alberto A.; Carvalho Filho, Carlos A. de; Rodrigues, Paulo Cezar Horta; Moura, Igor Felipe Silva

    2017-01-01

    The nuclear licensing process involves the preparation of documents such as Local's Report (LR), Preliminary Safety Analysis Report (PSAR), Final Safety Analysis Report (FSAR), Physical Protection Plans, Radiation Protection Plans and Emergency plans that must be submit to the National Nuclear Energy Commission (DRS / CNEN) for approval. This work presents an analysis and a guide for the use of Geoprocessing tools in the updating of environmental studies necessary to update the Local's Report (LR) of the Center for the Development of Nuclear Technology (CDTN). The main purpose is to contribute to streamline the execution of steps involved in the nuclear licensing process, such as structuring and executing environmental studies, planning environmental monitoring activities, etc. To achieve the objective, we search for and obtained available data of high reliability in various organs using a methodological flowchart for data acquisition and treatment. The study was develop using the ArcMap 10.2 application from ArcGis, especially the Model Builder analytic tool. This tool allowed the (macro) schematization of the methodology from the applied GIS tools, which presents as advantages to the efficiency and optimization of the execution time of the procedures in situations where it is necessary to apply the same routine of tasks, besides the fact of being editable, which offers possibilities for adaptations and improvements. (author)

  14. Technology of geographical information systems applied to the licensing of nuclear sector installations

    Energy Technology Data Exchange (ETDEWEB)

    Oliveira, Aline F.G. De; Barreto, Alberto A.; Carvalho Filho, Carlos A. de; Rodrigues, Paulo Cezar Horta [Centro de Desenvolvimento da Tecnologia Nuclear (CDTN/CNEN-MG), Belo Horizonte, MG (Brazil); Moura, Igor Felipe Silva, E-mail: afgo@cdtn.br, E-mail: aab@cdtn.br, E-mail: cacf@cdtn.br, E-mail: igorfelipedx@ufmg.br [Universidade Federal de Minas Gerais (UFMG), Belo Horizonte, MG (Brazil)

    2017-07-01

    The nuclear licensing process involves the preparation of documents such as Local's Report (LR), Preliminary Safety Analysis Report (PSAR), Final Safety Analysis Report (FSAR), Physical Protection Plans, Radiation Protection Plans and Emergency plans that must be submit to the National Nuclear Energy Commission (DRS / CNEN) for approval. This work presents an analysis and a guide for the use of Geoprocessing tools in the updating of environmental studies necessary to update the Local's Report (LR) of the Center for the Development of Nuclear Technology (CDTN). The main purpose is to contribute to streamline the execution of steps involved in the nuclear licensing process, such as structuring and executing environmental studies, planning environmental monitoring activities, etc. To achieve the objective, we search for and obtained available data of high reliability in various organs using a methodological flowchart for data acquisition and treatment. The study was develop using the ArcMap 10.2 application from ArcGis, especially the Model Builder analytic tool. This tool allowed the (macro) schematization of the methodology from the applied GIS tools, which presents as advantages to the efficiency and optimization of the execution time of the procedures in situations where it is necessary to apply the same routine of tasks, besides the fact of being editable, which offers possibilities for adaptations and improvements. (author)

  15. Guide to request license for industrial X-rays practices

    International Nuclear Information System (INIS)

    2000-05-01

    In this work the instructions it plows described to request license for practices it of industrial x-ray it continued. The instructions but important: they plows license type, purpose of the application, source and equipment, location of local the, program of radiological protection and security

  16. Software licenses: Stay honest!

    CERN Multimedia

    Computer Security Team

    2012-01-01

    Do you recall our article about copyright violation in the last issue of the CERN Bulletin, “Music, videos and the risk for CERN”? Now let’s be more precise. “Violating copyright” not only means the illegal download of music and videos, it also applies to software packages and applications.   Users must respect proprietary rights in compliance with the CERN Computing Rules (OC5). Not having legitimately obtained a program or the required licenses to run that software is not a minor offense. It violates CERN rules and puts the Organization at risk! Vendors deserve credit and compensation. Therefore, make sure that you have the right to use their software. In other words, you have bought the software via legitimate channels and use a valid and honestly obtained license. This also applies to “Shareware” and software under open licenses, which might also come with a cost. Usually, only “Freeware” is complete...

  17. Assuring the Quality of Licensing and Certification Programs.

    Science.gov (United States)

    Shimberg, Benjamin

    When one considers the importance and social significance of licensing and certification examinations, it is amazing that the enterprise operates with virtually no societal oversight. The "Standards for Educational and Psychological Testing" and the "Code of Fair Testing Practices in Education" of the American Psychological…

  18. Installing Omeka

    Directory of Open Access Journals (Sweden)

    Jonathan Reeve

    2016-07-01

    Full Text Available Omeka.net is a useful service for Omeka beginners, but there are a few reasons why you might want to install your own copy of Omeka. Reasons include: * Upgrades. By installing Omeka yourself, you can use the latest versions of Omeka as soon as they’re released, without having to wait for Omeka.net to upgrade their system. * Plugins and themes. You can install any plugin or theme you want, without being restricted to those provided by Omeka.net. * Customizations. You can buy a custom domain name, and customize your code to achieve your desired functionality. * Control. You have control over your own backups, and you can update the server yourself so that its security is always up-to-date. * Price. There are many low-cost Virtual Private Servers (VPSs now, some of which cost only $5 per month. * Storage. Many shared hosting providers now offer unlimited storage. This is useful if you have a large media library. In this tutorial, we’ll be entering a few commands on the command line. This tutorial assumes no prior knowledge of the command line, but if you want a concise primer, consult the Programming Historian introduction to BASH. There are other ways of installing Omeka, of course, some using exclusively GUI tools. Some hosting providers even offer “one-click installs” via their control panels. Many of those methods, however, will install older versions of Omeka which are then harder to upgrade and maintain. The method outlined below may not be the easiest way to install Omeka, but it will give you some good practice with using the command line, which is a skill that will be useful if you want to manually upgrade your install, or manually install other web frameworks. (For example, this installation method is very similar to WordPress’s “Five-Minute Install”. There are four steps to this process, and it should take about an hour.

  19. Protection of third parties by collateral clauses of plan approvals or licenses

    International Nuclear Information System (INIS)

    Badura, P.

    1989-01-01

    This contribution discusses the regulatory functions of collateral clauses of plan approvals or licences, the legal protection of the constitutional and other rights of third parties in connection with the licensing of installations or similar projects, infringements of such rights and means of defence, and protection of neighbours under public law against noise. (RST) [de

  20. Practical issues in structuring seismic licensing and acquisition agreements

    International Nuclear Information System (INIS)

    Lawrence, M.A.

    1999-01-01

    Some issues facing the geophysical industry in the area of licensing and acquisition agreements are discussed, focusing on a very large business segment of the industry called 'non-exclusive' seismic data (commonly referred to as SPEC data). A historical perspective of the industry in the Gulf of Mexico is presented, highlighting some important aspects of data licenses. The benefits of licensing three-dimensional data to the exploration industry include: (1) economy of scale, (2) 3-D is more affordable, (3) reduced barriers to entry by independents, and (4) improved success rates and reduced risk. A list of 'SPEC' companies in the Gulf of Mexico is provided and the data licensing process is outlined. There are two basic types of seismic data use licenses. The first is for a single, one-time transaction, and the other (which is more prevalent), covers multiple use licenses contemplated over a period of time. This paper briefly outlined the meaning of some important terms usually found in a license agreement, among them ownership, rights of licensee, term, disclosure to third parties, and transfer. International 'SPEC' programs and the requirements for a successful 'SPEC' program are described. The requirements include: a stable host government, reliable, competitive system of concession offerings, long term scheduled offerings, clear, consistent, and acceptable concession terms to oil and gas companies, and consistent, fair and timely method of evaluating bids and awarding concessions. 001CA9901758

  1. Essays on the economics of licensing nuclear power plants

    International Nuclear Information System (INIS)

    Cohen, L.R.

    1979-01-01

    Regulation and licensing of nuclear power plants by the United States Atomic Energy Commission and the United States Nuclear Regulatory Commission are discussed. Chapter 1 overviews the licensing process and issues raised in licensing cases. Based on a sample of plants licensed between 1967 and 1978, a statistical study of the impact of public participation in licensing is performed. The study concludes that public participation has had a major impact on licensing and power-plant costs. The impact is due to a fundamental weakness of the Commissions: their inability to resolve certain issues related to acceptable social risk. The study has important policy implications for reforming the Federal licensing process. Chapter 2 contains an analysis of the Price-Anderson Act, a Federal program for compensating victims of large nuclear accidents. The Price-Anderson Act is placed within the context of generalized federal disaster relief. A model is developed that allows an evaluation programs on the basis of moral hazard and equity principles. Chapter 3 analyzes the Nuclear Regulatory Commission's treatment of its mandatory antitrust review of applicants for nuclear power plants. The main conclusion of the chapter is that the reviews have not addressed the central economic issues of antitrust that are relevant to nuclear power. Instead, the reviews contribute to further cartelization of the electric utility industry. While politically expedient, the reviews are counter-productive to the development of an optimal industry structure

  2. Are we done yet? An assessment of the remaining barriers to increasing compact fluorescent lamp installations and recommended program strategies for reducing them

    Energy Technology Data Exchange (ETDEWEB)

    Rasmussen, Tami; Canseco, Jennifer [KEMA Inc., Sustainable Market Strategies Group (United States); Rubin, Rob [San Diego Gas and Electric Company (United States); Teja, Anu [Northwest Energy Efficiency Alliance (United States)

    2007-07-01

    Residential energy efficiency lighting programs in active regions of the United States have been successful in dramatically increasing compact fluorescent lamp (CFL) purchases over the last decade - where currently a majority of households have one or more CFLs installed. However, in these regions CFLs are used in less than 10 percent of residential lamp sockets, and much untapped energy savings potential remains. Consumers in these active regions with CFLs already installed could expand their existing CFL installations by a factor of five. The reasons that they are not doing so include waiting for incandescent bulbs to burn out, issues with CFL performance, the need for specialty CFLs (which are expensive and not widely available) and the higher cost of CFLs.Programs in these active regions should consider the following recommendations for increasing CFL installations: encourage consumers to retrofit more CFLs and not to wait for incandescent bulbs to burn out; track and address CFL performance issues for the range of CFL products; broaden program strategies to address specialty CFLs; expand incentives to year-round and to more stores and products; and track market barriers at both the household and lamp socket level.In regions of the United States or countries with emerging residential CFL programs, program planners should consider the following recommendations: research the lighting market and introduce program strategies within existing market channels; focus first on the most basic style of CFLs that are designed to replace standard incandescent bulbs and move to specialty CFLs later; and track and monitor product quality from program inception.

  3. USNRC licensing process as related to nuclear criticality safety

    International Nuclear Information System (INIS)

    Ketzlach, N.

    1987-01-01

    The U.S. Code of Federal Regulations establishes procedures and criteria for the issuance of licenses to receive title to, own, acquire, deliver, receive, possess, use, and initially transfer special nuclear material; and establishes and provides for the terms and conditions upon which the Nuclear Regulatory Commission (NRC) will issue such licenses. Section 70.22 of the regulations, ''Contents of Applications'', requires that applications for licenses contain proposed procedures to avoid accidental conditions of criticality. These procedures are elements of a nuclear criticality safety program for operations with fissionable materials at fuels and materials facilities (i.e., fuel cycle facilities other than nuclear reactors) in which there exists a potential for criticality accidents. To assist the applicant in providing specific information needed for a nuclear criticality safety program in a license application, the NRC has issued regulatory guides. The NRC requirements for nuclear criticality safety include organizational, administrative, and technical requirements. For purely technical matters on nuclear criticality safety these guides endorse national standards. Others provide guidance on the standard format and content of license applications, guidance on evaluating radiological consequences of criticality accidents, or guidance for dealing with other radiation safety issues. (author)

  4. Environmental qualification design for NPP refurbishment to comply with revised licensing requirements

    International Nuclear Information System (INIS)

    MacBeth, M. J.; Hemmings, R. L.

    2002-01-01

    Recent Canadian Nuclear Regulatory decisions have imposed Environmental Qualification (EQ) requirements for twenty-four Reactor Building (RB) airlocks at the four-unit Pickering Nuclear Generating Station-B (PNGS-B) facility. This paper describes the EQ modification design work completed by CANATOM-NPM for the problematic aspects for such projects. The airlocks allow RB access while providing a containment boundary and are designed to prevent a potential breach of containment for all analysed station conditions. Each PNGS-B unit has three large equipment airlocks and three smaller personnel airlocks. The airlocks must function under postulated worst-case design basis accident(DBA) conditions for assigned mission durations. The design must ensure that accident conditions cannot spuriously initiate an un-requested door opening. CANATOM-NPM reviewed site data to specify the necessary EQ modifications required to satisfy licensing requirements while providing a correct and complete as-found record of the existing airlock installation. The design team assessed the installed airlocks configuration against environmental qualification requirements to finalize the list of necessary modifications. A comprehensive, cross-discipline review of proposed design changes was completed to identify any further changes required to satisfy the final EQ licensing goal. The design team also conducted a design review of the EQ modification installation strategy to integrate the design deliverables with the installation team requirements while attempting to minimize necessary outage time for EQ modification installations. This project was completed on schedule and within the cost limitations required by the client with comprehensive, high quality final design packages. Overall improvements were realized for OPG system drawings and the electronic documentation of design data. The EQ modifications designed by CANATOM-NPM will ensure the continued operation of the PNGS-B NPP past December 31

  5. The comparison of license management procedure for nuclear power plant in China and United States

    International Nuclear Information System (INIS)

    Yu Zusheng

    2006-01-01

    'Tow steps' license management procedure for nuclear power plant has been performed bas- ted on the requirement of 10CFR Part50-DOMESTIC LICENSING OF PRODUCTION AND UTILIZATION FACILITIES in United States since last century fifties. In order to ulterior reduce the risk of investment and technical for new construction nuclear power plants, new regulations 'One step' license management procedure-10CFR Part52-EARLY SITE PERMITS; STANDARD DESIGN CERTIFICATIONS; AND COMBINED LICENSES FOR NUCLEAR POWER PLANTS issued in 1989. The new regulations has been adopted by new design of nuclear power plant, for example AP1000. ‘The similar tow steps’ license management procedure for nuclear power plant has been performed basted on the requirement of HAFO01/01 Rules for the Implementation of Regulations on the Safety Regulation for Civilian Nuclear Installations of the People's Re- public of China Part One: Application and Issuance of Safety License for Nuclear Power Plant (December 1993) in China since last century nineties. This article introduces and compares the requirements and characteristics of above license management procedure for nuclear power plant in China and United States. (author)

  6. Nuclear power plants: recent developments in Brazil relating to the legal aspect of installation - erection - operation

    International Nuclear Information System (INIS)

    Lima Moreira, Y.M. de.

    1981-10-01

    A Federal statutory system governs the setting up and operation of nuclear power plants in Brazil. This paper describes the general regulatory framework for electric utilities and in particular analyses the licensing procedure for nuclear installations. (NEA) [fr

  7. Regulatory challenges for independent organization and licensing procedures for Egypt first nuclear power program

    International Nuclear Information System (INIS)

    Elsheikh, B.M.

    2012-01-01

    In March 2010 the Government of Egypt issued an Ordinance creating an independent regulatory body the Egypt Nuclear and Radiological Regulatory Authority (NRRA) reporting directly to the Prime Minister and responsible for matters dealing with protection of the radiation worker, public and environment from the harmful effects of ionizing radiation. A little more than 2 years have elapsed since this date. Some of the challenges faced by NRRA to its regulatory independence are given below. This paper will discuss the major challenges relating to Egyptian nuclear power program and specially the regulatory effectiveness and licensing procedures compared to international comparison.

  8. Establishment of the nuclear regulatory framework for the process of decommissioning of nuclear installations in Mexico

    International Nuclear Information System (INIS)

    Salmeron V, J. A.; Camargo C, R.; Nunez C, A.

    2015-09-01

    Today has not managed any process of decommissioning of nuclear installations in the country; however because of the importance of the subject and the actions to be taken to long term, the Comision Nacional de Seguridad Nuclear y Salvaguardias (CNSNS) in Mexico, accordance with its objectives is developing a National Nuclear Regulatory Framework and defined requirements to ensure the implementation of appropriate safety standards when such activities are performed. In this regard, the national nuclear regulatory framework for nuclear installations and the particular case of nuclear power reactors is presented, as well as a proposed licensing process for the nuclear power plant of Laguna Verde based on international regulations and origin country regulations of the existing reactors in nuclear facilities in accordance with the license conditions of operation to allow to define and incorporate such regulation. (Author)

  9. Public participation in nuclear licensing procedures from the viewpoint of constitutional law

    International Nuclear Information System (INIS)

    Mutschler, Ulrich

    1981-10-01

    This paper reviews public participation in the licensing procedure for nuclear installations, in particular in the Federal Republic of Germany. Examples are given of practical experience acquired to date, also in the field of case-law. Finally, the paper stresses the importance of public information in nuclear procedures in view of the growing concerns for the environment. (NEA) [fr

  10. Future of Nuclear Power: NRC emergency preparedness licensing activities agenda

    International Nuclear Information System (INIS)

    Essig, T.H.

    1995-01-01

    This talk summary addresses the issue of how future policies of the NRC will affect nuclear power in areas such as construction, emergency preparedness, and licensing. Specific topics covered include the following: Emergent EP licensing issues for operating nuclear Power Plants; 10CFR Part 52 and the process for licensing of Advanced Light Water Reactors (ALWRs); and potential revisions to emergency preparedness programs for future nuclear power plants

  11. An economic perspective on software licenses--open source, maintainers and user-developers

    DEFF Research Database (Denmark)

    Edwards, Kasper

    2005-01-01

    This paper presents a model for understanding behaviour of agents using and/or contributing to open source software. The model illustrates behaviour of agents under three licenses regimes: 1) The GPL, The BSD and 3) The Microsoft EULA. The latter license is not an open source license...... licenses induce different incentives and dynamics for maintainer and user-developer and the paper explains, from an economic standpoint, the mechanisms that ensure programs are developed and maintained under the three license regimes....

  12. Conflict management in the planning of nuclear installations

    International Nuclear Information System (INIS)

    Pfeifer, M.

    1989-01-01

    Subsequent to the decision of the Bavarian Higher Administrative Court, which after judicial review declared the development plan for the Wackersdorf site and the reprocessing facility there to be void, the author analyses the situation with regard to the tasks to be accomplished by an installation-specific planning management for coping with arising conflicts - and nuclear hazards in particular -, and for coming to a reconciliation of interests. The author agrees with the decision of the Lueneburg Higher Administrative Court which stated that, in view of the subsequent licensing procedure provided by the law, the development plans need not specify any regulations concerning the specific nuclear hazards or radiological consequences of installations of this type, so that development plans within the meaning of sec. 1, sub-sec. (3) BauGB do not necessarily have to consider nuclear risks or dose limits. (orig./HP) [de

  13. Evaluation of experience and trends in international co-operation in nuclear safety and licensing

    International Nuclear Information System (INIS)

    Stadie, K.B.; Strohl, P.

    1977-01-01

    The paper traces the development of co-operation in nuclear safety technology between the OECD Member countries which began as early as 1965 and is now organised under the auspices of the Committee on the Safety of Nuclear Installations of the OECD Nuclear Energy Agency. The principal objective is to exchange and evaluate information on relevant R and D and hence broaden the technical basis for decision-making by licensing authorities in the different countries. The membership of the Committee on the Safety of Nuclear Installations combines expertise in nuclear safety R and D and in licensing questions so that licensing procedures in the different countries may be exposed continuously to the influence of overall technological progress. The Committee actively seeks to narrow the differences between administrative procedures and traditional legal practices in Member countries as these affect the licensing of nuclear installations, primarily by assessing and comparing the methods employed. The paper shows how the Committee's working arrangements provide for maximum flexibility: the various co-ordinated programmes are selected after in-depth evaluation of potential areas of priority and are implemented through ad hoc Working Groups, specialist meetings or task forces, or in the form of special studies involving all interested countries. The results, conclusions and recommendations emerging from each programme are reviewed by the Committee before dissemination. Hitherto the greater part of the Committee's activities has been concerned with the safety of light water reactors and related subjects, but more attention is now being given to other topics such as LMFBR safety technology and the safety of fuel cycle facilities, particularly those at the end of the process, the so-called ''back-end'' plants. The paper discusses certain problems and constraints encountered in implementing the programme, some of which stem from Member countries' different degrees of penetration

  14. Decay heat removal plan of the SNR-300: a licensed concept

    International Nuclear Information System (INIS)

    Morgenstern, F.H.; Gyr, W.; Stoetzel, H.; Vossebrecker, H.

    1976-01-01

    The report describes how the decay heat removal plan of the SNR-300 has been established in 3 essential licensing steps, thus giving a very significant example for the slow but steady progress in the overall licensing process of the plant. (1) Introduction of an ECCS in addition to the 3 main heat transfer chains as a back-up for rather unlikely and undefined occurrences, 1970; (2) Experimental and computational demonstration of a reliable functioning of the in-vessel natural convection of the fluid flow, 1974; and (3) Proof of fulfilling the general safety and specific reliability criteria for the overall decay heat removal plan; i.e., the 3 main heat transfer chains with specific installations on the steam/water system side and the ECCS, 1976. Some special problem areas, for instance the cavity concept provided for the pipe fracture accident, have still to be licensed, but they do not contribute considerably to the overall risk

  15. Groundwater quality monitoring well installation for Lower Waste Area Grouping 2 at Oak Ridge National Laboratory, Oak Ridge, Tennessee. Environmental Restoration Program

    International Nuclear Information System (INIS)

    Mortimore, J.A.; Lee, T.A.

    1994-09-01

    This report documents the drilling and installation of 11 groundwater quality monitoring (GQM) wells on the perimeter of Lower Waste Area Grouping (WAG) 2. Lower WAG 2 consists of White Oak Lake and the embayment below White Oak Dam above the Clinch River. The wells in Lower WAG 2 were drilled and developed between December 1989 and September 1990. These wells were installed to characterize and assess the WAG in accordance with applicable Department of Energy, state, and Environmental Protection Agency regulatory requirements. The wells at Lower WAG 2 were drilled with auger or air rotary rigs. Depending on the hydrogeologic conditions present at each proposed well location, one of three basic installation methods was utilized. Detailed procedures for well construction were specified by the Engineering Division to ensure that the wells would provide water samples representative of the aquifer. To ensure conformance with the specifications, Energy Systems Construction Engineering and ERCE provided continuous oversight of field activities. The purpose of the well installation program was to install GQM wells for groundwater characterization at Lower WAG 2. Data packages produced during installation activities by the ERCE hydrogeologists are an important product of the program. These packages document the well drilling, installation, and development activities and provide valuable data for well sampling and WAG characterization. The forms contained in the packages include predrilling and postdrilling checklists, drilling and construction logs, development and hydraulic conductivity records, and quality control-related documents

  16. Summary of the Mol electrolysis cell test program in the CRL tritium laboratory

    International Nuclear Information System (INIS)

    Miller, J.M.; Keyes, R.J.

    1996-01-01

    The development of electrolysis technology for highly tritiated water at the Studiecentrum voor Kernenergie/Centre d'Etude de l'Energie Nucleaire (SCK/CEN), Mol, Belgium, focused on A Low Inventory Capillary Electrolyser (ALICE). The key characteristic of ALICE is its low liquid inventory, a key feature for the radio-toxicity of tritiated water. A program to test this electrolytic cell design with highly tritiated water in the Chalk River Tritium Laboratory was initiated in 1988 and extended through to early 1995. The activities conducted at CRL and associated with the experimental program-design, installation, licensing and commissioning activities- are described in this report along with the results of the test program conducted on the experimental system with non-tritiated heavy water. The installation in the CRL Tritium Laboratory consisted of three main sections: the electrolysis section, the tritium storage and supply section, and the recombination section. 16 figs., 2 tabs., 10 refs

  17. IRIS pre-application licensing

    International Nuclear Information System (INIS)

    Carelli, Mario D.; Kling, Charles L.; Ritterbusch, Stanley E.

    2003-01-01

    This paper presents the approach to pre-application licensing by the International Reactor Innovative and Secure (IRIS), and advanced, integral reactor design with a thermal power of 1000 MW. The rationale for the pre-application licensing is discussed. Since IRIS technology is based on proven LWR experience, the project will rely on AP600/AP1000 precedent and will focus during the pre-application on long lead and novel items. A discussion of the evolution of the project to significantly reduce licensing issues is provided, followed by a summary of the IRIS safety-by-design which provides a formidable first step in the Defense in Depth approach. The effects of the safety-by-design, as well as of passive systems, on the IRIS safety will be investigated in a proposed testing program that will be reviewed by NRC during the pre-application. Documentation to be provided to NRC is discussed. Early design analyses indicate that the benefits of the IRIS safety-by-design approach are so significant that the basic premise of current emergency planning regulations (i.e., likelihood of core damage) will be reduced to the extent that special emergency response planning beyond the exclusion area boundary may not be needed. How this very significant outcome can be effected through a highly risk-informed licensing is discussed. (author)

  18. 75 FR 77017 - Nextera Energy Seabrook, LLC Seabrook Station Independent Spent Fuel Storage Installation; Exemption

    Science.gov (United States)

    2010-12-10

    ... NUCLEAR REGULATORY COMMISSION [Docket Nos. 50-443, 72-63; NRC-2010-0381] Nextera Energy Seabrook, LLC Seabrook Station Independent Spent Fuel Storage Installation; Exemption 1.0 Background NextEra Energy Seabrook, LLC (NextEra, the licensee) is the holder of Facility Operating License No. NPF-86...

  19. ITER licensing

    International Nuclear Information System (INIS)

    Gordon, C.W.

    2005-01-01

    ITER was fortunate to have four countries interested in ITER siting to the point where licensing discussions were initiated. This experience uncovered the challenges of licensing a first of a kind, fusion machine under different licensing regimes and helped prepare the way for the site specific licensing process. These initial steps in licensing ITER have allowed for refining the safety case and provide confidence that the design and safety approach will be licensable. With site-specific licensing underway, the necessary regulatory submissions have been defined and are well on the way to being completed. Of course, there is still work to be done and details to be sorted out. However, the informal international discussions to bring both the proponent and regulatory authority up to a common level of understanding have laid the foundation for a licensing process that should proceed smoothly. This paper provides observations from the perspective of the International Team. (author)

  20. The licensing of nuclear plants as an example of conflicts of authority in parallel licensing procedures

    International Nuclear Information System (INIS)

    Henseler, P.

    1982-01-01

    Although the results obtained cannot be translated into installation licences related to the clean air act or to building codes without reservations, they can be generalized as follows: If several authorities have to assess one and the same project in independent procedures, they do not only have to use the metric used for subject-specific licensing prerequisites, but also the one used for the common weal. Then the spheres of responsibility require division. Oriented towards the purpose of the relevant laws, it has to be settled first for the sake of which public interest the authorities involved substantiate of a licensing reservation at all. All the decisions which fall within the sphere of responsibility of a certain authority are reserved and may not be prejudged by other authorities involved by issuing acts of regulation with externally binding effects. Insofar as similar or related public interests are to be considered in several licencing procedures (to be conducted) and insofar as there is no possibility of assigning the safeguarding of these interests to a special field of activity of one of the authorities involved, diverging results have to be accepted. (orig./HP) [de

  1. Experience with HEPA filters at United States nuclear installations

    International Nuclear Information System (INIS)

    Bellamy, R.R.

    1977-01-01

    Part 50 of Title 10 of the United States Code of Federal Regulations requires that a number of atmosphere cleanup systems be included in the design of commercial nuclear power plants to be licensed in the United States. These filtering systems are to contain high efficiency particulate air (HEPA) filters for removal of radioactive particulate matter generated during normal and accident conditions. Recommendations for the design, testing and maintenance of the filtering systems and HEPA filter components are contained in a number of United States Nuclear Regulatory Commission documents and industry standards. This paper will discuss this published guidance available to designers of filtering systems and the plant operators of U.S. commercial nuclear power plants. The paper will also present a survey of published reports of experience with HEPA filters, failures and possible causes for the failures, and other abnormal occurrences pertaining to HEPA filters installed in U.S. nuclear power installations. A discussion will be included of U.S. practices for qualification of HEPA filters before installation, and verification of continued performance capability at scheduled intervals during operation

  2. Gas reactor international cooperative program interim report: United States/Federal Republic of Germany nuclear licensing comparison

    International Nuclear Information System (INIS)

    1978-09-01

    In order to compare US and FRG Nuclear Licensing, a summary description of United States Nuclear Licensing is provided as a basis. This is followed by detailed information on the participants in the Nuclear Licensing process in the Federal Republic of Germany (FRG). FRG licensing procedures are described and the rules and regulations imposed are summarized. The status of gas reactor licensing in both the U.S. and the FRG is outlined and overall conclusions are drawn as to the major licensing differences. An appendix describes the most important technical differences between US and FRG criteria

  3. IRIS Licensing Status

    International Nuclear Information System (INIS)

    Kling, Charles L.; Carelli, Mario D.

    2006-01-01

    The International Reactor Innovative and Secure (IRIS) nuclear power plant is well into the pre-application review process with the US NRC and has accomplished its first near term goal of obtaining US NRC feedback on the long term testing program. To date, the IRIS team has submitted to the US NRC a number of documents patterned after the Evaluation Model Development and Assessment Process (EMDAP) outlined in Regulatory Guide 1,203. They have covered a detailed description of IRIS, initial safety analysis results, PIRT development for limiting transients, scaling analysis and a description of the test program. The IRIS Safety-by-Desing TM intrinsically eliminates and/or significantly reduces the consequences of traditional LWR accidents. In addition, the fewer passive safety systems are similar in principle to those of the US NRC approved AP1000 design. For these reasons, the IRIS testing program only needs to include those features unique to the IRIS design. NRC feedback was that the planned test program appeared to be complete and could generate sufficient information to support a Design Certification (DC) submittal. The US NRC has also stated that a DC application must include complete information regarding the test program. On this basis the IRIS team has initiated an aggressive program to conduct IRIS testing to support a DC submittal by the end of 2008. Subsequent US NRC review should be expeditious because of the AP1000 precedent, allowing IRIS to obtain its Final Design Approval (FDA) in 2012; thereby, maintaining its goal of deployment in the 2015-2017 time frame. The next steps in the pre-application review process will be to provide the US NRC with a road map of the anticipated IRIS licensing process, a review of current licensing requirements showing that IRIS meets or exceeds all current criteria and information to support the long term goal of redefining the Emergency Planning Zone (EPZ)

  4. Suitcase to Audit Solar Installations

    Energy Technology Data Exchange (ETDEWEB)

    Alberdi, J.; Barcala, J.M.; Blas de, J.; Molinero, A.; Navarrete, J.J.; Yuste, C.

    2001-07-01

    The audit suitcase was proposed by BESEL to introduce in the solar energy market a new tool which can make an evaluation of solar installation efficiency. Non-invasive sensors and low power components permit both easy installation of the devices and data storage for a period as long as ten days. This project was funded by the contract JOR3-CT98-7030 of the European Union JOULE III program. (Author)

  5. Suitcase to Audit Solar Installations

    International Nuclear Information System (INIS)

    Alberdi, J.; Barcala, J. M.; Blas, J. de; Molinero, A.; Navarrete, J. J.; Yuste, C.

    2001-01-01

    The audit suitcase was proposed by BESEL to introduce in the solar energy market a new tool which can make an evaluation of solar installation efficiency. Non-invasive sensors and low power components permit both easy installation of the devices and data storage for a period as long as ten days. This project was funded by the contract JOR3-CT98-7030 of the European Union JOULE III program. (Author)

  6. A COMPARATIVE STUDY OF STATE LICENSING BOARDS FOR SCHOOL ADMINISTRATION AND OTHER SELECTED PROFESSIONS.

    Science.gov (United States)

    MOLINARI, RALPH G.; AND OTHERS

    COMPARISON OF THE COMPOSITION, CHARACTERISTICS, AND CURRENT LICENSING PRACTICES OF STATE LICENSING BOARDS FOR EDUCATIONAL ADMINISTRATION WITH LICENSING PROGRAMS FOR SEVEN OTHER PROFESSIONS, (ACCOUNTANCY, ARCHITECTURE, DENTISTRY, ENGINEERING, LAW, MEDICINE, AND NURSING) WAS THE PURPOSE OF THIS NATIONWIDE STUDY. THE RESEARCH PROCEDURES WERE DIVIDED…

  7. Evaluation of Installation Time for SMASHmount by SMASHsolar

    Energy Technology Data Exchange (ETDEWEB)

    2017-04-05

    The Department of Energy SunShot Incubator program provides early-stage assistance to help startup companies cross technological barriers to commercialization while encouraging private sector investment. The SunShot Incubator program aims to shorten the time it takes for a young business or company to develop an innovative product concept and make it commercially available, which includes product prototyping, deployment, and, potentially, manufacturing. SMASHsolar was selected as an Incubator awardee to develop a simple, snap-together, module-integrated photovoltaic (PV) mounting system in attempts to dramatically reduce the time, effort and skill needed to install rooftop solar. In support of this award, the National Renewable Energy Laboratory worked with SMASHsolar to develop a procedure for evaluating the installation time required for the SMASHmount system vs. widely-available rail systems. Amongst several installations, NREL measured the following installation times, subject to the qualifications and conditions described later in this report. NREL found that the SMASHsolar SMASHmount system was installed between 15% and 37% faster than tested competing systems after one or two installations of the system.

  8. Nuclear proliferation and civilian nuclear power. Report of the Nonproliferation Alternative Systems Assessment Program. Volume VI. Safety and environmental considerations for licensing

    International Nuclear Information System (INIS)

    1980-06-01

    This volume of the Nonproliferation Alternative Systems Assessment Program report addresses safety and environmental considerations in licensing the principal alternative nuclear reactors and fuel cycles in the United States for large-scale commercial nuclear power plants. In addition, this volume examines the safety and environmental considerations for licensing fuel service centers. These centers, which have been proposed for controlling sensitive fuel-cycle facilities and special nuclear materials, would contain a combination of such facilities as reprocessing plants, fabrication plants, and reactors. For this analysis, two fuel service center concepts were selected - one with power - generating capability and one without

  9. License renewal in the United States

    International Nuclear Information System (INIS)

    Brons, Jack

    2002-01-01

    Full text: Nuclear plants in the United States are licensed for 40 years, a length specified in the Atomic Energy Act of 1954, which laid out much of the regulatory basis for the commercial nuclear industry. The Act, however, made provision for license renewal. The original 40-year license period was chosen arbitrarily by the U.S. Congress because it was the typical period over which utilities recovered their investment in electricity generating plants. Nuclear plants, however, are subject to a rigorous program of Nuclear Regulatory Commission oversight, maintenance and equipment replacement. In effect, they must be in the same operating condition on the last day of their licenses as they were on the first. As the industry matured, it became apparent that there was no physical limitation on the continued operation of nuclear plants past 40 years. The industry turned its attention toward license renewal. When the issue was first raised, the NRC considered stringent process equivalent to seeking a new operating license for each plant. The complexity, length and cost of the process made it unlikely that many nuclear plants would seek license renewal. The nuclear industry worked successfully with NRC on the application of generic principles to license renewal, however, and in 1995, the NRC issued an efficient, tightly-focused rule that made license renewal a safe, viable option. To extend the operating license for a reactor, a company must demonstrate to the NRC that aging effects will be adequately managed during the renewal terms, thus ensuring equipment functionality. The rule allows licensees to apply for extensions of up to 20 years. The first license renewal application was filed in 1998 by the owner of the two-unit Calvert Cliffs plant. Shortly thereafter, an application was filed for the three-unit Oconee Nuclear Station. The NRC renewed the licenses for all five units in 2000, and since then, five more licenses have been renewed. The NRC has received 37

  10. National Accreditation and Its Role in Early Education: An Analysis of Florida's Gold Seal Quality Child-Care Program and Licensing Standards

    Science.gov (United States)

    Winterbottom, Christian; Jones, Ithel

    2014-01-01

    This article reports on the first Florida statewide assessment of the Gold Seal Quality Care program, accreditation, and the relationship with licensing violations. This study analyzed the differences between the Department of Children and Families Gold Seal-Accredited facilities and nonaccredited facilities by comparing the facilities and the…

  11. Preliminary assessment report for Grubbs/Kyle Training Center, Smyrna/Rutherford County Regional Airport, Installation 47340, Smyrna, Tennessee. Installation Restoration Program

    Energy Technology Data Exchange (ETDEWEB)

    Dennis, C.; Stefano, J.

    1993-07-01

    This report presents the results of the preliminary assessment (PA) conducted by Argonne National Laboratory at the Tennessee Army National Guard (TNARNG) property near Smyrna, Tennessee. Preliminary assessments of federal facilities are being conducted to compile the information necessary for completing preremedial activities and to provide a basis for establishing corrective actions in response to releases of hazardous substances. The principal objective of the PA is to characterize the site accurately and determine the need for further action by examining site activities, quantities of hazardous substances present, and potential pathways by which contamination could affect public health and the environment. This PA satisfies, for the Grubbs/Kyle Training Center property, the requirement of the Department of Defense Installation Restoration Program.

  12. Development model to public hearing for environmental licensing of nuclear facilities

    Energy Technology Data Exchange (ETDEWEB)

    Vasques, Luciana Gomes; Aquino, Afonso Rodrigues de, E-mail: lu_vasques@usp.br, E-mail: araquino@ipen.br [Instituto de Pesquisas Energeticas e Nucleares (IPEN/CNEN-SP), Sao Paulo, SP (Brazil)

    2015-07-01

    The use of nuclear technology has always been a matter of concern from an environmental point of view. Although disputed, the generation of electricity in nuclear reactors was considered a source of clean emission in relation to emission of gases responsible for the greenhouse effect. In Brazil, nuclear activities are regulated and supervised by the Brazilian Commission of Nuclear Energy - CNEN. Environmental issues associated with nuclear activities are described by CONAMA, and the developments in this area are licensed by IBAMA, regardless of obtaining nuclear licenses issued by CNEN. Obtaining environmental licenses (prior, installation and operation) depends initially on preparing the Environmental Impact Study - EIS and the Environmental Impact Report - EIR, consisting of a presentation of EIS in language accessible to all. EIR is forwarded to bodies and entities with some connection to the enterprise, to be manifested with IBAMA about the relevance of its content. This information serves as a resource for Public Hearings, which are meetings organized by entrepreneurs, conducted by IBAMA, and rely on public participation, can be considered as a licensing step. Public Hearings are subject to subjectivity, and the model proposed in this research becomes more objective ill-defined, difficult to understand actions for the entrepreneur. (author)

  13. Development model to public hearing for environmental licensing of nuclear facilities

    International Nuclear Information System (INIS)

    Vasques, Luciana Gomes; Aquino, Afonso Rodrigues de

    2015-01-01

    The use of nuclear technology has always been a matter of concern from an environmental point of view. Although disputed, the generation of electricity in nuclear reactors was considered a source of clean emission in relation to emission of gases responsible for the greenhouse effect. In Brazil, nuclear activities are regulated and supervised by the Brazilian Commission of Nuclear Energy - CNEN. Environmental issues associated with nuclear activities are described by CONAMA, and the developments in this area are licensed by IBAMA, regardless of obtaining nuclear licenses issued by CNEN. Obtaining environmental licenses (prior, installation and operation) depends initially on preparing the Environmental Impact Study - EIS and the Environmental Impact Report - EIR, consisting of a presentation of EIS in language accessible to all. EIR is forwarded to bodies and entities with some connection to the enterprise, to be manifested with IBAMA about the relevance of its content. This information serves as a resource for Public Hearings, which are meetings organized by entrepreneurs, conducted by IBAMA, and rely on public participation, can be considered as a licensing step. Public Hearings are subject to subjectivity, and the model proposed in this research becomes more objective ill-defined, difficult to understand actions for the entrepreneur. (author)

  14. Obstacles to engaging in young driver licensing: Perspectives of parents.

    Science.gov (United States)

    Naz, Sehana; Scott-Parker, Bridie

    2017-02-01

    Young novice drivers remain at greater risk of injury and death despite a wealth of interventions including graduated driver licensing (GDL) programs. The key to implementing safer practices inherent in GDL appears to lie with optimising the role of parents. This qualitative research explored the parent's perspectives of obstacles to engaging in the driver licensing process within a GDL program. Parents also shared advice on what they found helpful, and where relevant, recommended changes in the process to enable safer practices for young drivers. Twenty-three parents (aged 35-60 years, M=49.52, SD=8.01, 11 males) participated in semi-structured interviews regarding licensing experiences with their young driver children. The young drivers included learner (n=11), provisional (restricted/intermediate) (n=9) and open (unrestricted/full) licence drivers (n=3), ranging from 16 to 24 years (M=18.04, SD=2.21, 13 males). Content analysis revealed that most obstacles were encountered at the learner licensing phase, with the parent-reported difficult temperament of the learner driver the most prominent. Unsurprisingly, advice to other parents to be patient and remain calm featured heavily during the same phase. Anxiety from not having control of the vehicle was another obstacle at the learner phase, translating to anxieties for child safety in the early stages of provisional driving. Recommendations for the current GDL included more rigorous road rule testing, with general support for the program, professional driver training at learner and provisional stages facilitated parental engagement through the licensing phases. The findings overwhelmingly suggest a need for parents to be educated regarding their importance in, and of, the driver licensing process, and the efficacy of their instruction, content and practices. Copyright © 2016 Elsevier Ltd. All rights reserved.

  15. The problem of licensing and safety of nuclear power plants

    International Nuclear Information System (INIS)

    Silva, R.A. da.

    1987-01-01

    The historical evolution of licensing process of nuclear power plants is presented. The designs carried out by FURNAS for constructing Angra-1 reactor and its contribution to the Brazilian CNEN in de licensing process, are evaluated. The aims of FURNAS Research Programs are determined and the safety goals are established. (M.C.K.) [pt

  16. Nuclear proliferation and civilian nuclear power: report of the Nonproliferation Alternative Systems Assessment Program. Volume VI. Safety and environmental considerations for licensing

    International Nuclear Information System (INIS)

    1979-12-01

    Volume 6 of the Nonproliferation Alternative Systems Assessment Program report addresses safety and environmental considerations in licensing the principal alternative nuclear reactors and fuel cycles in the United States for large-scale commercial nuclear power plants. In addition, this volume examines the safety and environmental considerations for licensing fuel service centers. These centers, which have been proposed for controlling sensitive fuel-cycle facilities and special nuclear materials, would contain a combination of such facilities as reprocessing plants, fabrication plants, and reactors. For this analysis, two fuel service center concepts were selected - one with power-generating capability and one without. This volume also provides estimates of the time required for development of large-scale commercial reactor systems to reach the construction permit application stage and for fuel-cycle facilities to reach the operating license application stage, which is a measure of the relative technical status of alternative nuclear systems

  17. 30 CFR 817.180 - Utility installations.

    Science.gov (United States)

    2010-07-01

    ... PERMANENT PROGRAM PERFORMANCE STANDARDS PERMANENT PROGRAM PERFORMANCE STANDARDS-UNDERGROUND MINING ACTIVITIES § 817.180 Utility installations. All underground mining activities shall be conducted in a manner...; oil, gas, and coal-slurry pipelines, railroads; electric and telephone lines; and water and sewage...

  18. Regulatory licensing, status summary report; Systematic evaluation program

    International Nuclear Information System (INIS)

    1978-01-01

    This document is part of a management information system presenting a logical flow of events that represent the evaluation of 11 of the older operating nuclear reactors. Information collected will be used to determine the degree to which the 11 plants meet current licensing requirements and to develop an overall balanced position concerning any needed backfitting of the facilities and the documentation of the results of such evaluations

  19. AGING MANAGMENT OF REACTOR COOLANT SYSTEM MECHANICAL COMPONENTS FOR LICENSE RENEWAL

    International Nuclear Information System (INIS)

    SUBUDHI, M.; MORANTE, R.; LEE, A.D.

    2002-01-01

    The reactor coolant system (RCS) mechanical components that require an aging management review for license renewal include the primary loop piping and associated connections to other support systems, reactor vessel, reactor vessel internals, pressurizer. steam generators, reactor coolant pumps, and all other inter-connected piping, pipe fittings, valves, and bolting. All major RCS components are located inside the reactor building. Based on the evaluation findings of recently submitted license renewal applications for pressurized water reactors, this paper presents the plant programs and/or activities proposed by the applicants to manage the effects of aging. These programs and/or activities provide reasonable assurance that the intended function(s) of these mechanical components will be maintained for the period of extended operation. The license renewal application includes identification of RCS subcomponents that are within the scope of license renewal and are vulnerable to age-related degradation when exposed to environmental and operational conditions. determination of the effects of aging on their intended safety functions. and implementation of the aging management programs and/or activities including both current and new programs. Industry-wide operating experience, including generic communication by the NRC, is part of the aging management review for the RCS components. In addition, this paper discusses time-limited aging analyses associated with neutron embrittlement of the reactor vessel beltline region and thermal fatigue

  20. 77 FR 20353 - United States Warehouse Act; Export Food Aid Commodities Licensing Agreement

    Science.gov (United States)

    2012-04-04

    ... licensing agreement include, but are not limited to, corn soy blend, vegetable oil, and pulses such as peas, beans, and lentils. USWA licensing is a voluntary program. Warehouse operators that apply for USWA...

  1. Climate Change Planning for Military Installations: Findings and Implications

    Science.gov (United States)

    2010-10-01

    climate change as an emerging issue with potential national security implications. As a result of these concerns, the DoD Strategic Environmental Research and Development Program (SERDP) is establishing a research and development program to address climate change effects on DoD installations and associated missions. To help establish the program, SERDP tasked Noblis to identify potential climate change effects on military installations and their missions and operations. This report presents the findings portion of this study and

  2. Safety and licensing analyses for the Fort St. Vrain HTGR

    International Nuclear Information System (INIS)

    Ball, S.J.; Conklin, J.C.; Harrington, R.M.; Cleveland, J.C.; Clapp, N.E. Jr.

    1982-01-01

    The Oak Ridge National Laboratory (ORNL) safety analysis program for the HTGR includes development and verification of system response simulation codes, and applications of these codes to specific Fort St. Vrain reactor licensing problems. Licensing studies addressed the oscillation problems and the concerns about large thermal stresses in the core support blocks during a postulated accident

  3. Decree No 74-1181 of 31 December 1974 concerning liquid radioactive effluent releases from nuclear installations

    International Nuclear Information System (INIS)

    1975-01-01

    This Decree prescribes the licensing procedure for the release of liquid wastes from nuclear installations as well as the technical supervision of such operations. It does not apply to the transport of radioactive effluents which is governed by the regulations on the transport of dangerous goods. (NEA) [fr

  4. Decree No 70-440 of 22 May 1970 abolishing the licensing system, set up by the Decree of 30 October 1935, in respect of thermal and nuclear electricity-generating plants

    International Nuclear Information System (INIS)

    1970-01-01

    With this Decree, nuclear power plants are subject only to the licensing system established by the 1963 Decree on nuclear installations, as amended subsequently by the Decree of 1973 and regulations specific to nuclear installations. (NEA) [fr

  5. The Planning, Licensing, Modifications, and Use of a Russian Vessel for Shipping Spent Nuclear Fuel by Sea in Support of the DOE RRRFR Program

    International Nuclear Information System (INIS)

    Tyacke, Michael; Bolshinsky, Igor; Tomczak, Wlodzimierz; Naletov, Sergey; Pichugin, Oleg

    2001-01-01

    The Russian Research Reactor Fuel Return (RRRFR) Program, under the U.S. Department of Energy's Global Threat Reduction Initiative, began returning Russian-supplied high-enriched uranium (HEU) spent nuclear fuel (SNF), stored at Russian-designed research reactors throughout the world, to Russia in January 2006. During the first years of making HEU SNF shipments, it became clear that the modes of transportation needed to be expanded from highway and railroad to include sea and air to meet the extremely aggressive commitment of completing the first series of shipments by the end of 2010. The first shipment using sea transport was made in October 2008 and used a non-Russian flagged vessel. The Russian government reluctantly allowed a one-time use of the foreign-owned vessel into their highly secured seaport, with the understanding that any future shipments would be made using a vessel owned and operated by a Russian company. ASPOL-Baltic of St. Petersburg, Russia, owns and operates a small fleet of vessels and has a history of shipping nuclear materials. ASPOL-Baltic's vessels were licensed for shipping nuclear materials; however, they were not licensed to transport SNF materials. After a thorough review of ASPOL Baltic's capabilities and detailed negotiations, it was agreed that a contract would be let with ASPOL-Baltic to license and refit their MCL Trader vessel for hauling SNF in support of the RRRFR Program. This effort was funded through a contract between the RRRFR Program, Idaho National Laboratory, and Radioactive Waste Management Plant of Swierk, Poland. This paper discusses planning, Russian and international maritime regulations and requirements, Russian authorities reviews and approvals, licensing, design, and modifications made to the vessel in preparation for SNF shipments. A brief summary of actual shipments using this vessel, experiences, and lessons learned also are described.

  6. The Planning, Licensing, Modifications, and Use of a Russian Vessel for Shipping Spent Nuclear Fuel by Sea in Support of the DOE RRRFR Program

    Energy Technology Data Exchange (ETDEWEB)

    Michael Tyacke; Dr. Igor Bolshinsky; Wlodzimierz Tomczak; Sergey Naletov; Oleg Pichugin

    2001-10-01

    The Russian Research Reactor Fuel Return (RRRFR) Program, under the U.S. Department of Energy’s Global Threat Reduction Initiative, began returning Russian-supplied high-enriched uranium (HEU) spent nuclear fuel (SNF), stored at Russian-designed research reactors throughout the world, to Russia in January 2006. During the first years of making HEU SNF shipments, it became clear that the modes of transportation needed to be expanded from highway and railroad to include sea and air to meet the extremely aggressive commitment of completing the first series of shipments by the end of 2010. The first shipment using sea transport was made in October 2008 and used a non-Russian flagged vessel. The Russian government reluctantly allowed a one-time use of the foreign-owned vessel into their highly secured seaport, with the understanding that any future shipments would be made using a vessel owned and operated by a Russian company. ASPOL-Baltic of St. Petersburg, Russia, owns and operates a small fleet of vessels and has a history of shipping nuclear materials. ASPOL-Baltic’s vessels were licensed for shipping nuclear materials; however, they were not licensed to transport SNF materials. After a thorough review of ASPOL Baltic’s capabilities and detailed negotiations, it was agreed that a contract would be let with ASPOL-Baltic to license and refit their MCL Trader vessel for hauling SNF in support of the RRRFR Program. This effort was funded through a contract between the RRRFR Program, Idaho National Laboratory, and Radioactive Waste Management Plant of Swierk, Poland. This paper discusses planning, Russian and international maritime regulations and requirements, Russian authorities’ reviews and approvals, licensing, design, and modifications made to the vessel in preparation for SNF shipments. A brief summary of actual shipments using this vessel, experiences, and lessons learned also are described.

  7. License renewal

    International Nuclear Information System (INIS)

    Newberry, S.

    1993-01-01

    This article gives an overview of the process of license renewal for nuclear power plants. It explains what is meant by license renewal, the significance of license renewal, and goes over key elements involved in the process of license renewal. Those key elements are NRC requirements embodied in 10 CFR Part 54 (Reactor Safety) and 10 CFR Part 51 (Environmental Issues). In addition Industry Reports must be developed and reviewed. License renewal is essentially the process of applying for a 20 year extension to the original 40 year operating license granted for the plant. This is a very long term process, which involves a lot of preparation, and compliance with regulatory rules and guidelines. In general it is a process which is expected to begin when plants reach an operating lifetime of 20 years. It has provisions for allowing the public to become involved in the review process

  8. Reconstruction efficiency and precision for the events detected by the BIS-2 installation using the Perun pattern recognition program

    International Nuclear Information System (INIS)

    Burilkov, D.T.; Genchev, V.I.; Markov, P.K.; Likhachev, M.F.; Takhtamyshev, G.G.; Todorov, P.T.; Trayanov, P.K.

    1982-01-01

    Results of studying the efficiency and accuracy of the track and event reconstruction with the Perun pattern recognition program used in the experiments carried out at the BIS-2 installation are presented. The Monte Carlo method is used for simulating the processes of neutron interactions with matter. The con-- clusion is made that the Perun program correctly, with good accuracy and high efficiency reconstructs complex multiparticle events [ru

  9. Nuclear safety requirements for operation licensing of Egyptian research reactors

    International Nuclear Information System (INIS)

    Ahmed, E.E.M.; Rahman, F.A.

    2000-01-01

    From the view of responsibility for health and nuclear safety, this work creates a framework for the application of nuclear regulatory rules to ensure safe operation for the sake of obtaining or maintaining operation licensing for nuclear research reactors. It has been performed according to the recommendations of the IAEA for research reactor safety regulations which clearly states that the scope of the application should include all research reactors being designed, constructed, commissioned, operated, modified or decommissioned. From that concept, the present work establishes a model structure and a computer logic program for a regulatory licensing system (RLS code). It applies both the regulatory inspection and enforcement regulatory rules on the different licensing process stages. The present established RLS code is then applied to the Egyptian Research Reactors, namely; the first ET-RR-1, which was constructed and still operating since 1961, and the second MPR research reactor (ET-RR-2) which is now in the preliminary operation stage. The results showed that for the ET-RR-1 reactor, all operational activities, including maintenance, in-service inspection, renewal, modification and experiments should meet the appropriate regulatory compliance action program. Also, the results showed that for the new MPR research reactor (ET-RR-2), all commissioning and operational stages should also meet the regulatory inspection and enforcement action program of the operational licensing safety requirements. (author)

  10. Licensing procedure for nuclear power in Sweden. An international look with lessons for Sweden

    International Nuclear Information System (INIS)

    Gaahlin, Emil; Nilsson, Isabelle; Pettersson, Maria; Soederholm, Patrik

    2011-02-01

    In this study we present an in-depth analysis of the existing licensing procedure for nuclear power in Sweden, and the related processes towards different public authorities. In order to put the existing legislation into context we also analyze the legal and political prerequisites for the establishment of nuclear reactors during the 1970s. The purpose of this report is thus to: (a) analyze the legal and political conditions under which the existing nuclear power plants in Sweden were built; and (b) review and analyze the existing licensing procedure for nuclear power in the country. Four main statutes (and several subordinated regulations) apply in connection with the establishment of a new nuclear plant in Sweden, including the adoption of physical plans, a principal governmental decision on the permissibility of the plant and at least five major licenses. Physical planning according to the Planning and Building Act is primarily a municipal responsibility. A plan has to meet certain environmental requirements; not least the 'provisions on efficient management of natural resources' in the Environmental Code, indicating how different kinds of land and water areas should be used and thereby direct the location of different installations. The Swedish rules are complex and vague in many respects, and may therefore imply major uncertainties for a prospective investor. The legal protection is less unclear if an area is of national interest for a specific purpose, such as nature conservation, where it normally would not be possible to locate, say, a nuclear power plant. An area may also be of national interest for nuclear plants, which of course significantly alters the preconditions in favour of the plant project. The physical planning procedure comprises an 'environmental consideration' of the plan, including an 'environmental impact assessment' (EIA), provided the plan is likely to have significant effects on the environment. This 'programmatic EIA' does however not

  11. Normative questions connected with the procedure for approval and operation of nuclear installations

    International Nuclear Information System (INIS)

    Nocera, F.

    1980-03-01

    Recent regulatory developments in the licensing procedure for nuclear installations in Italy are discussed in the light of technical and scientific developments and international rules. The author then discusses the questions likely to be further defined and regulated, i.e. requirements for possession of fuels and fuel storage facilities, nuclear plant decommissioning, protection of the population with reference to the directives of the European Communities. (NEA) [fr

  12. Annual Radiological Environmental Monitoring Program Report for the Three Mile Island, Unit 2, Independent Spent Fuel Storage Installation

    International Nuclear Information System (INIS)

    Hall, Gregory Graham

    2002-01-01

    This report presents the results of the 2001 Radiological Environmental Monitoring Program conducted in accordance with 10 CFR 72.44 for the Three Mile Island, Unit 2, Independent Spent Fuel Storage Installation. A description of the facility and the monitoring program is provided. The results of monitoring the two predominant radiation exposure pathways, potential airborne radioactivity releases and direct radiation exposure, indicate the facility operation has not contributed to any increase in the estimated maximum potential dose commitment to the general public.

  13. Department of Energy interest and involvement in nuclear plant license renewal activities

    International Nuclear Information System (INIS)

    Bustard, Larry D.; Harrison, Dennis L.

    1991-01-01

    Recognizing the importance of nuclear license renewal to the nation's energy strategy, the Department of Energy (DOE) initiated a plant lifetime improvement program during 1985 to determine the feasibility of the license renewal option for US nuclear plants. Initial activities of the DOE program focused on determining whether there were technical and economic obstacles that might preclude or limit the successful implementation of the license renewal option. To make this determination, DOE co-sponsored with the Electric Power Research Institute (EPRI) 'pilot-plant' efforts by Virginia Electric Power and Northern States Power. Both pilot-plant efforts concluded that life extension is technically and economically feasible. In parallel with the pilot plant activities, DOE performed national economic studies that demonstrated the economic desirability of life extension. Having demonstrated the feasibility of life extension, DOE, in conjunction with EPRI, selected two lead plants to demonstrate the license renewal process. These lead plants are Yankees Atomic's Yankee Rowe facility and Northern States Power's Monticello facility. DOE also initiated activities to develop the technical and regulatory bases to support the license renewal process in the United States. These include (1) development of a methodology for identifying systems, structures, and components important to license renewal, (2) development of industry reports that describe industry-accepted approaches for license renewal of ten important classes of equipment, (3) development of technical basis to support license renewal, and (4) interaction/negotiation with the NRC through the Nuclear Management Resources Council (NUMARC) regarding appropriate regulatory requirements for license renewal. DOE has recently identified nuclear plant license renewal to be an important element of its National Energy Strategy. This paper summarizes the significant results, conclusions and ongoing activities of the DOE effort

  14. The United States nuclear regulatory commission license renewal process

    International Nuclear Information System (INIS)

    Holian, B.E.

    2009-01-01

    The United States (U.S.) Nuclear Regulatory Commission (NRC) license renewal process establishes the technical and administrative requirements for the renewal of operating power plant licenses. Reactor ope-rating licenses were originally issued for 40 years and are allowed to be renewed. The review process for license renewal applications (L.R.A.) provides continued assurance that the level of safety provided by an applicant's current licensing basis is maintained for the period of extended operation. The license renewal review focuses on passive, long-lived structures and components of the plant that are subject to the effects of aging. The applicant must demonstrate that programs are in place to manage those aging effects. The review also verifies that analyses based on the current operating term have been evaluated and shown to be valid for the period of extended operation. The NRC has renewed the licenses for 52 reactors at 30 plant sites. Each applicant requested, and was granted, an extension of 20 years. Applications to renew the licenses of 20 additional reactors at 13 plant sites are under review. As license renewal is voluntary, the decision to seek license renewal and the timing of the application is made by the licensee. However, the NRC expects that, over time, essentially all U.S. operating reactors will request license renewal. In 2009, the U.S. has 4 plants that enter their 41. year of ope-ration. The U.S. Nuclear Industry has expressed interest in 'life beyond 60', that is, requesting approval of a second renewal period. U.S. regulations allow for subsequent license renewals. The NRC is working with the U.S. Department of Energy (DOE) on research related to light water reactor sustainability. (author)

  15. Final report on the waste area grouping perimeter groundwater quality monitoring well installation program at Oak Ridge National Laboratory, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    Greene, J.A.

    1991-06-01

    A groundwater quality monitoring well installation program was conducted at Oak Ridge National Laboratory (ORNL) to meet the requirements of environmental regulations, including the Resource Conservation and Recovery Act (RCRA) and the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA). A total of 173 wells were installed and developed at 11 different waste area groupings (WAGs) between June 1986 and November 1990. A location map of the wells is included

  16. Licensing process characteristics of Small Modular Reactors and spent nuclear fuel repository

    Energy Technology Data Exchange (ETDEWEB)

    Söderholm, Kristiina, E-mail: kristiina.soderholm@fortum.com [Fortum Power (Finland); Tuunanen, Jari, E-mail: jari.tuunanen@fortum.com [Fortum Power (Finland); Amaba, Ben, E-mail: baamaba@us.ibm.com [IBM Complex Systems (United States); Bergqvist, Sofia, E-mail: sofia.bergqvist@se.ibm.com [IBM Rational Software (Sweden); Lusardi, Paul, E-mail: plusardi@nuscalepower.com [NuScale Power (United States)

    2014-09-15

    Highlights: • We examine the licensing process challenges of modular nuclear facilities. • We compare the features of Small Modular Reactors and spent nuclear fuel repository. • We present the need of nuclear licensing simplification. • Part of the licensing is proposed to be internationally applicable. • Systems engineering and requirements engineering benefits are presented. - Abstract: This paper aims to increase the understanding of the licensing processes characteristics of Small Modular Reactors (SMR) compared with licensing of spent nuclear fuel repository. The basis of the SMR licensing process development lies in licensing processes used in Finland, France, the UK, Canada and the USA. These countries have been selected for this study because of their various licensing processes and recent actions in the new NPP construction. Certain aspects of the aviation industry licensing process have also been studied and selected practices have been investigated as possibly suitable for use in nuclear licensing. Suitable features for SMR licensing are emphasized and suggested. The licensing features of the spent nuclear fuel deep repository along with similar features of SMR licensing are discussed. Since there are similar types of challenges of lengthy licensing time frames, as well as modular features to be taken into account in licensing, these two different nuclear industry fields can be compared. The main SMR features to take into account in licensing are: • Standardization of the design. • Modularity. • Mass production. • Serial construction. Modularity can be divided into two different categories: the first category is simply a single power plant unit constructed of independently engineered modules (e.g. construction process for Westinghouse AP-1000 NPP) and the second one a power plant composed of many reactor modules, which are manufactured in factories and installed as needed (e.g. NuScale Power SMR design). The deep underground repository

  17. 47 CFR 74.787 - Digital licensing.

    Science.gov (United States)

    2010-10-01

    ..., AUXILIARY, SPECIAL BROADCAST AND OTHER PROGRAM DISTRIBUTIONAL SERVICES Low Power TV, TV Translator, and TV Booster Stations § 74.787 Digital licensing. (a) Applications for digital low power television and... channels may be filed at any time. Such applications shall be filed on FCC Form 346 and will be treated as...

  18. National waste terminal storage repository in a bedded salt formation for spent unreprocessed fuel. Quality assurance program for licensing

    International Nuclear Information System (INIS)

    1978-12-01

    A National Waste Terminal Storage Repository, in bedded salt, for spent unreprocessed fuel is the subject of a conceptual design project which began in January 1977. This volume presents a preliminary quality assurance program to guide the license applicant in developing a detailed program that will be compatible with anticipated National Waste Terminal Storage (NWTSR2) contracting arrangements and provide the documentation required by regulatory bodies. This QA program is designed to provide confidence that the quality-related activities pertaining to safety-related structures, systems, and components will be identified and controlled. Specific responsibilities for quality-related activities are documented and assigned to personnel and organizations for the major phases of facility design and construction. These responsibilities encompass a broad range of activities and are addressed in this preliminary program. The quality assurance program elements are organized and discussed herein as follows: (1) quality assurance during design and construction; (2) the applicant (DOE); (3) siting contractor; (4) architect/engineer; (5) project field management; and (6) operations contractor

  19. Legal action initiated by a municipality in order to prevent installation of a nuclear power station

    International Nuclear Information System (INIS)

    Anon.

    1986-01-01

    A municipality is authorized to appeal against the licensing of a nuclear power plant which is about to be installed in the neighbourhood of the municipality in order to protect its water treatment plant. (Non-official headnotes) OVG Rheinland-Pfalz, interlocutary decree of June 3, 1986 - 7 A II 2/85 - (appealable). (orig./HSCH) [de

  20. Licensing of the OPAL reactor during construction and commissioning

    International Nuclear Information System (INIS)

    Summerfield, M.

    2007-01-01

    This paper presents a description of the licensing activities associated with the construction and commissioning of the Australian Nuclear Science and Technology Organisation's (ANSTO) OPAL reactor. It addresses the Construction Licence, the interface between ANSTO, INVAP (the contractor with responsibility for design and construction of the facility) and the Australian Radiation Protection and Nuclear Safety Agency (ARPANSA, the Australian nuclear regulator) during the construction of OPAL, specific licensing issues that have arisen during the construction and commissioning process, and the Operating Licence Application. Particular emphasis will be given to the way in which the licensing process is integrated into the overall project program and the lessons learnt that may be of benefit to other licensees and regulators

  1. License renewal process

    International Nuclear Information System (INIS)

    Fable, D.; Prah, M.; Vrankic, K.; Lebegner, J.

    2004-01-01

    The purpose of this paper is to provide information about license renewal process, as defined by Nuclear Regulatory Commission (NRC). The Atomic Energy Act and NRC regulations limit commercial power reactor licenses to an initial 40 years but also permit such licenses to be renewed. This original 40-year term for reactor licenses was based on economic and antitrust considerations not on limitations of nuclear technology. Due to this selected time period; however, some structures and components may have been engineered on the basis of an expected 40-year service life. The NRC has established a timely license renewal process and clear requirements codified in 10 CFR Part 51 and 10 CFR Part 54, that are needed to assure safe plant operation for extended plant life. The timely renewal of licenses for an additional 20 years, where appropriate to renew them, may be important to ensuring an adequate energy supply during the first half of the 21st Century. License renewal rests on the determination that currently operating plants continue to maintain adequate levels of safety, and over the plant's life, this level has been enhanced through maintenance of the licensing bases, with appropriate adjustments to address new information from industry operating experience. Additionally, NRC activities have provided ongoing assurance that the licensing bases will continue to provide an acceptable level of safety. This paper provides additional discussion of license renewal costs, as one of key elements in evaluation of license renewal justifiability. Including structure of costs, approximately value and two different approaches, conservative and typical. Current status and position of Nuclear Power Plant Krsko, related to license renewal process, will be briefly presented in this paper. NPP Krsko is designed based on NRC Regulations, so requirements from 10 CFR 51, and 10 CFR 54, are applicable to NPP Krsko, as well. Finally, this paper will give an overview of current status of

  2. Uranium-mill appraisal program

    International Nuclear Information System (INIS)

    Everett, R.J.; Cain, C.L.

    1982-08-01

    The results of special team appraisals at NRC-licensed uranium mills in the period May to November 1981 are reported. Since the Three Mile Island accident, NRC management has instituted a program of special team appraisals of radiation protection programs at certain NRC-licensed facilities. These appraisals were designed to identify weaknesses and strengths in NRC-licensed programs, including those areas not covered by explicit regulatory requirements. The regulatory requirements related to occupational radiation protection and environmental monitoring at uranium mills have been extensively upgraded in the past few years. In addition, there was some NRC staff concern with respect to the effectiveness of NRC licensing and inspection programs. In response to this concern and to changes in mill requirements, the NRC staff recommended that team appraisals be conducted at mills to determine the adequacy of mill programs, the effectiveness of the new requirements, and mill management implementation of programs and requirements. This report describes the appraisal scope and methodology as well as summary findings and conclusions. Significant weaknesses identified during the mill appraisals are discussed as well as recommendations for improvements in uranium mill programs and mill licensing and inspection

  3. Department of Energy interest and involvement in nuclear plant license renewal activities

    International Nuclear Information System (INIS)

    Bustard, L.D.; Harrison, D.L.

    1991-01-01

    Recognizing the importance of nuclear license renewal to the nation's energy strategy, the Department of Energy (DOE) initiated a plant lifetime improvement program during 1985 to determine the feasibility of the license renewal option for US nuclear plants. Initial activities of the DOE program focused on determining whether there were technical and economic obstacles that might preclude or limit the successful implementation of the license renewal option. To make this determination, DOE cosponsored with the Electric Power Research Institute (EPRI) pilot-plant efforts by Virginia Electric Power and Northern States Power. Both pilot-plant efforts concluded that life extension is technically and economically feasible. In parallel with the pilot-plant activities, DOE performed national economic studies that demonstrated the economic desirability of life extension. Having demonstrated the feasibility of life extension, DOE, in conjunction with EPRI, selected two lead plants to demonstrate the license renewal process. These lead plants are Yankee Atomic's Yankee Rowe facility and Northern States Power's Monticello facility. DOE also initiated activities to develop the technical and regulatory bases to support the license renewal process in the United States. DOE has recently identified nuclear plant license renewal to be an important element of its National Energy Strategy. This paper summarizes the significant results, conclusions, and ongoing activities of the DOE effort. 18 refs

  4. Ship and Installation Program: Optimal Stationing of Naval Ships

    National Research Council Canada - National Science Library

    Colgary, Katherine A; Willett, Devon K

    2006-01-01

    .... Using constraints that maintain adequate pier capacity and unique capability installation, Configuration Analysis seeks to maximize a measure of military value while penalizing excess capacity...

  5. Experience in Cuba in the licensing during import, commissioning and operation of an Irradiator LLCo ISOGAMMA

    International Nuclear Information System (INIS)

    Forteza, Yamil Lopez; Reyes, Yolanda Perez; Garcia, Jose R. Quevedo; Molina, Igor I. Sarabia; Gonzalez, Leonel Omarovich; Zubiaur, Omar Cruz

    2013-01-01

    This work presented the experiences during the process of licensing an irradiator ISOGAMMA LLCo model according to the recommendations of the International Atomic Energy (IAEA). Aspects of the safety assessment are detailed, as well as control and verification requirements for radiation safety and security at different stages of the process (import, transportation, installation irradiator loading 60Co sources, commissioning and operation) of irradiator recently installed in Cuba. The results of the evaluation carried a source of reference and consultation necessary for the work of the regulator to consider for similar processes that lie ahead in other facilities irradiation

  6. Criteria of classification applied to licensing of particle accelerators

    International Nuclear Information System (INIS)

    Costa, Evaldo L.C.; Melo, Paulo F.F.

    2013-01-01

    This work aims to bring to discussion the proposal of a new classification model toward to generating ionizing radiation, specifically particle accelerators, considering two parameters: the size of these facilities and the level of energy they operate, emphasizing large accelerators, which typically operate at higher levels of energy. Also motivated by the fact that the Brazilian rules do not provide an adequate standard of licensing for this size of installation, this work will seek to revise the existing classification, where generators of ionizing radiation (including particle accelerators) are considered up to the level of energy of 50 MeV

  7. Evaluating the effectiveness of a post-license education program for young novice drivers in Belgium.

    Science.gov (United States)

    Brijs, Kris; Cuenen, Ariane; Brijs, Tom; Ruiter, Robert A C; Wets, Geert

    2014-05-01

    The disproportionately large number of traffic accidents of young novice drivers highlights the need for an effective driver education program. The Goals for Driving Education (GDE) matrix shows that driver education must target both lower and higher levels of driver competences. Research has indicated that current education programs do not emphasize enough the higher levels, for example awareness and insight. This has raised the importance of insight programs. On the Road (OtR), a Flemish post-license driver education program, is such an insight program that aims to target these higher levels. The program focus is on risky driving behavior like speeding and drink driving. In addition, the program addresses risk detection and risk-related knowledge. The goal of the study was to do an effect evaluation of this insight program at immediate post-test and 2 months follow-up. In addition, the study aimed to generalize the results of this program to comparable programs in order to make usable policy recommendations. A questionnaire based on the Theory of Planned Behavior (TPB) was used in order to measure participants' safety consciousness of speeding and drink driving. Moreover, we focused on risk detection and risk-related knowledge. Participants (N=366) were randomly assigned to a baseline-follow-up group or a post-test-follow-up group. Regarding speeding and driving, we found OtR to have little effect on the TPB variables. Regarding risk detection, we found no significant effect, even though participants clearly needed substantial improvement when stepping into the program. Regarding risk-related knowledge, the program did result in a significant improvement at post-test and follow-up. It is concluded that the current program format is a good starting point, but that it requires further attention to enhance high level driving skills. Program developers are encouraged to work in a more evidence-based manner when they select target variables and methods to influence

  8. 50 CFR 660.336 - Pacific whiting vessel licenses.

    Science.gov (United States)

    2010-10-01

    ... groundfish fishing capacity reduction program. NMFS will also make license applications available online at... by that vessel's United States Coast Guard documentation number. (b) [Reserved] [74 FR 10193, Mar. 10, 2009; 74 FR 11881, Mar. 20, 2009] ...

  9. Exploring the Gap between a Pre- and Post-Installation of a Corporate E-Learning Program in an Accounting Workplace

    Science.gov (United States)

    Cheng, Kai-Wen

    2013-01-01

    Although earlier concentration has addressed the use of corporate e-learning programs (CELP), the dissimilitude between pre and post installation reaction to CELP is less explored. This study adopted a two-phase investigation to survey learner intention to use CELP and actual behavior within an international accounting firm. In the…

  10. Installation of the Ion Accelerator for the Surface Analysis

    Energy Technology Data Exchange (ETDEWEB)

    Kwon, Hyeok-Jung; Kim, Han-Sung; Chung, Bo-Hyun; Ahn, Tae-Sung; Kim, Dae-Il; Kim, Cho-Rong; Cho, Yong-Sub [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2015-10-15

    In this paper, an introduction to the accelerator, an installation status at KOMAC and the operation plan of the accelerator are discussed. A pelletron, which has been used over 25 years at KIGAM, is moved and installed at KOMAC in order to supply a qualified service to ion beam users. The system will be installed in September and component tests will be carried. The operation of the system starts in 2016 after it gets operation license from Nuclear Safety and Security Commission. Korea Multi-purpose Accelerator Complex (KOMAC) is operating several ion beam accelerators to provide various ion beams to users. Those are a 100 MeV proton linear accelerator, a 220 keV ion implanter for gaseous ion beams, a 150 keV metal ion implanter and a 20 keV high-current ion implanter. All of those are the machine for user service and it is important to qualify the results of the irradiation conditions for user service. For this reason, an electrostatic tandem accelerator, which has been operating over 25 years at Korea Institute of Geoscience and Mineral Resources (KIGAM), is moved to KOMAC in order to supply the qualified and quantified data on the irradiation species.

  11. NRC antitrust licensing actions, 1978--1996

    International Nuclear Information System (INIS)

    Mayer, S.J.; Simpson, J.J.

    1997-09-01

    NUREG-0447, Antitrust Review of Nuclear Power Plants, was published in May 1978 and includes a compilation and discussion of U.S. Nuclear Regulatory Commission (NRC) proceedings and activity involving the NRC's competitive review program through February 1978, NUREG-0447 is an update of an earlier discussion of the NRC's antitrust review of nuclear power plants, NR-AIG-001, The US Nuclear Regulatory Commission's Antitrust Review of Nuclear Power Plants: The Conditioning of Licenses, which reviewed the Commission's antitrust review function from its inception in December 1970 through April 1976. This report summarizes the support provided to NRC staff in updating the compilation of the NRC's antitrust licensing review activities for commercial nuclear power plants that have occurred since February 1978. 4 refs., 4 tabs

  12. NRC analysis of the environmental impacts and licensing policies for expanded spent fuel storage in the United States

    International Nuclear Information System (INIS)

    Smith, C.V. Jr.

    1978-01-01

    This paper reviews the findings of the U.S. environmental impact studies on spent fuel storage to the year 2000, addresses design criteria for independent spent fuel storage installations and expresses the position of the NRC for licensing expanded spent fuel storage capabilities until such time as final solutions are established

  13. To License or Not to License Remanufacturing Business?

    Directory of Open Access Journals (Sweden)

    Zu-Jun Ma

    2018-01-01

    Full Text Available Many original equipment manufacturers (OEMs face the choice of whether to license an independent remanufacturer (IR to remanufacture their used products. In this paper, we develop closed-loop supply chain models with licensed and unlicensed remanufacturing operations to analyze the competition and cooperation between an OEM and an IR. The OEM sells new products and collects used products through trade-ins, while the IR intercepts the OEM’s cores to produce remanufactured products and sell them in the same market. We derive optimal decisions for each of the two types of firms in licensed and unlicensed remanufacturing scenarios and identify conditions under which the OEM and the IR would be most likely to cooperate with each other in implementing remanufacturing. The results show although it is beneficial for an OEM to license an IR to remanufacture its cores, it is not always necessary for an IR to accept OEM’s authorization. Moreover, we contrast the result for licensed remanufacturing scenario in the decentralized system with that in the centrally coordinated system to quantify potential inefficiency resulting from decentralization of decision making.

  14. Technology licensing in China

    DEFF Research Database (Denmark)

    Wang, Yuandi; Li-Ying, Jason; Chen, Jin

    2015-01-01

    We explore the landscape of technology licensing among Chinese entities in the period 2000–12, using a unique database on technological licensing from the State Intellectual Property Office of China. We find that: first, among Chinese licensee organizations, firms have dominated in terms...... of the number of licensed technologies; second, the geographical distribution of licensed technologies among the provinces has gradually reached a new quantitative balance; third, utility models are the most popular technologies to be licensed and the majority of technology licensing in China has been between...... Chinese entities, and most transactions have been local within provinces; and finally, Chinese firms have gradually in-licensed newer and newer technologies, but the technologies in-licensed from foreign sources are by no means state-of-the-art. We make several suggestions for innovation policy...

  15. Outline for embedded topical license renewal industry perspective

    International Nuclear Information System (INIS)

    Gilchrist, Jacqueline

    1991-01-01

    This presentation describes the history of the project, selection of the Lead plant; project management, and project implementation, License renewal application contains: implementation plan; technical specifications and program changes; updated safety analysis report supplement; plant specific exemptions; environmental report update

  16. Safety of nuclear installations. An international comparison

    International Nuclear Information System (INIS)

    Renner, Andrea; Diwes, Andreas; Reingardt, Martin

    2010-01-01

    Safeguarding of nuclear power plants against disruptive actions or other external hazards is part of the plant design and presumption of an operation license. The general principle is defense in depth involving different security zones with separate barriers. The safeguards for nuclear installations are organized in three areas of responsibility: governmental measures (police, military), technical (detectors, scanners, illuminations, camera tracking, concrete barriers) and personnel measures (access control, security personnel, alarm) of the operating company. International responsibilities results from the treaty on the non-proliferation of nuclear weapons and several IAEA documents. The authors discuss the national regulations in Germany, Switzerland, United Kingdom and USA. Older NPPs that are not in compliance with actual safety standards will be a topic of increasing importance.

  17. Performance assessment and licensing issues for United States commercial near-surface low-level radioactive waste disposal facilities

    International Nuclear Information System (INIS)

    Birk, S. M.

    1997-01-01

    This paper covers the performance assessment and licensing issues, the performance the objectives, the performance assessment phases, the scenario selection, the mathematical modeling and computer programs, the final results of performance assessments submitted for license applications, the institutional control period, and the licensing issues. 38 refs

  18. Establishment of regulatory framework for the development reactor licensing

    International Nuclear Information System (INIS)

    Jo, Jong C.; Yune, Young G.; Kim, Woong S.; Ahn, Sang K.; Kim, In G.; Kim, Hho J.

    2003-01-01

    With a trend that various types of advanced reactor designs are currently under development worldwide, the Korea Atomic Energy Research Institute has been developing an advanced reactor called ' System-integrated Modular Advanced Reactor (SMART)', which is a small sized integral type pressurized water reactor with a rated thermal power of 330 MW. To demonstrate the safety and the performance of the SMART reactor design, the SMART Research and Development Center has embarked to build a scaled-down pilot plant of SMART, called 'SMART-P' with a rated thermal power of 65 MW. In preparation for the forthcoming applications for both construction permit and operating license of SMART-P in the near future, the Korea Institute of Nuclear Safety is developing a new regulatory framework for licensing review of such a development reactor, which covers establishment of licensing process, identification and resolution of technical and safety issues, development of regulatory evaluation or verification-purpose computer codes and analytical methods, and establishment of design-specific, general design and operating criteria, regulations, and associated regulatory guides. This paper presents the current activities for establishing a regulatory framework for the licensing of a research and development reactor. Discussions are made on the SMART-P development program, the current Korean regulatory framework for reactor licensing, the SMART-P licensing-related issues, and the approach and strategy for developing an effective regulatory framework for the SMART-P licensing

  19. Data bank usage in reload design and licensing

    International Nuclear Information System (INIS)

    Goudey, J.L.; Hansen, E.C.; Scigliano, S.M.; Williams, R.D.

    1986-01-01

    In 1977 the Nuclear Energy Business Operations of General Electric Company (GE) began a major project to automate sequential execution of the data transfer between the various computer programs used in performing calculations to support design, release, licensing, and core management of fuel used in boiling water reactors (BWRs). A centralized and controlled data bank was designed and implemented to complement the data management system and to achieve the following objectives: (1) enhance the quality and reliability of engineering data used for design and licensing of BWR fuel; (2) provide for traceability and long-term retrievability of engineering data as required by 10CFR50, Appendix B; (3) standardize the location and minimize the redundancy of engineering data; and (4) make engineering data readily available to all individuals and computer programs with a need for it. The structure of this data bank, which has become known as the BWR Engineering Data Bank or BWR/EDB, was purposefully left flexible and expandable with the ability to accommodate numerical, logical, and textual data. The BWR/EDB has been used by GE during fuel release, fuel and core design, reload licensing, and core management activities for 30 to 40 commercial power reactors over the past several years

  20. Decree No 63-1228 of 11 December 1963 concerning nuclear installations as amended by Decree No 73-405 of 27 March 1973

    International Nuclear Information System (INIS)

    1973-01-01

    This text, which incorporates the amendments made by the 1973 Decree, regulates large nuclear installations in France and defines them. It lays down in detail their licensing procedure and also designates the competent authorities in that respect. (NEA) [fr

  1. Analysis of normative requirements for the development and implementation of a quality management system in Brazilian nuclear installations and activities

    International Nuclear Information System (INIS)

    Kibrit, Eduardo

    2008-01-01

    The present work identifies, characterizes and analyses the normative requirements for the development and implementation of quality management systems in Brazilian nuclear installations and activities. The requirements established in standards IAEA GS-R-3, IAEA GS-G-3.1, IAEA DS 349, NBR ISO 9001:2000 e CNEN-NN-1.16 are critically analyzed. A correlation matrix of the applicable standards is presented and the related topics among them are identified. The standards IAEA GS-R-3, IAEA GS-G-3.1 and IAEA DS 349 define general requirements for establishing, implementing, assessing and continually improving an integrated management system in nuclear installations and activities, in IAEA member countries. The standard NBR ISO 9001:2000 establishes general requirements for the implementation of a quality management system in all kinds of organizations. The standard CNEN NN-1.16 establishes the regulating requirements for the quality assurance systems and programs of nuclear installations, for licensing and authorization for operation of these installations in Brazil. The standard IAEA GS-R-3 that replaces the code IAEA 50-C-Q introduces the concept of 'Integrated Management System' for the nuclear area, in preference to the concepts of 'Quality Assurance' and 'Quality Management'. This new approach is aligned with the current tendency incorporating requirements of quality, safety, health, environment, security, economics and other in a unique management system. Examples of quality management systems implemented by Brazilian nuclear organizations and by nuclear organizations outside Brazil are analyzed and considered in the discussion of results. (author)

  2. 75 FR 43118 - Fisheries of the Exclusive Economic Zone Off Alaska; Gulf of Alaska License Limitation Program

    Science.gov (United States)

    2010-07-23

    ...: The Bering Sea (BS), Aleutian Islands (AI); Southeast Outside District (SEO); Central Gulf of Alaska... holders of latent fixed-gear endorsed LLP licenses could resume fishing under the licenses in the future... how fishery effort may shift in the future, but a large number of latent LLP licenses do exist, and...

  3. Licensing process in Finland

    International Nuclear Information System (INIS)

    Tiippana, Petteri

    2011-01-01

    In accordance with the Nuclear Energy Act, the use of nuclear energy constitutes operations subject to license. The licensing process and conditions for granting a license is defined in the legislation. The licenses are applied from and granted by the Government. This paper discusses briefly the licensing process in Finland and also the roles and responsibilities of main stakeholders in licensing. Licensing of a nuclear power plant in Finland has three steps. The first step is the Decision in Principle (DiP). Goal of DiP is to decide whether using nuclear power is for the overall good for the Finnish society. The second step is Construction License (CL) and the goal of CL phase is to determine whether the design of the proposed plant is safe and that the participating organisations are capable of constructing the plant to meet safety goals. The third step is the Operating License (OL) and the goal of the OL phase is to determine whether the plant operates safely and licensee is capable to operate the plant safely. Main stakeholders in the licensing process in Finland are the utility (licensee) interested in using nuclear power in Finland, Ministry of Employment and the Economy (MEE), Government, Parliament, STUK, the municipality siting the plant and the general public. Government grants all licenses, and Parliament has to ratify Government's Decision in Principle. STUK has to assess the safety of the license applications in each step and give statement to the Ministry. Municipality has to agree to site the plant. Both STUK and the municipality have a veto right in the licensing process

  4. NPP long term operation in Spain - First application for license renewal

    International Nuclear Information System (INIS)

    Francia, L.; Gorrochategui, I.; Marcos, R.

    2007-01-01

    Full text: In the operation of the Spanish nuclear power plants (NPP), safety is always the prime consideration. Plant Life Management Programmes have been set up with the strategic objective to operate the NPPs as long as they are considered safe and reliable. The safety of each NPP is reviewed by the Spanish nuclear regulatory authority (CSN) under a continuous process. In addition, experience is gained from operating the plants and from exchanges with operators of similar units. Current Spanish regulatory framework for renewing NPP operating licenses requires performing a Periodic Safety Review (PSR) to be performed every 10 years and submitted when applying for a new renewal of the NPP operating license. A few years ago, CSN issued a document regarding the licensing requirements that nuclear power plants should meet in order to be granted with an operating license for long term operation (i.e, operation beyond the original plant design life, typically 40 years). Besides the traditional PSR requirements, specific requirements regarding to long term operation (LTO) include: - An Aging Management and Evaluation Program, including the identification and evaluation of Time Limited Aging Analysis (TLAA). - An updated Radiological Impact Study. - A review and assessment of regulation/standard applicability. Garona NPP (GE, BWR/3 design) operated by Spanish utility Nuclenor from 1971 has a current operating license up to 2009. A decision was made to apply for a new operating license, being Garona plant the first one in Spain to face with the new long term operation requirements. The paper will provide an overview of the methodology used in Spain to address and perform the required analyses to support the LTO application for the operating license renewal. In particular, focus will be paid on the project developed in Garona (2002-2006) whose result has been the first Spanish application for License Renewal for LTO. Also it will be reported the ongoing work necessary to

  5. Automation of the DoD Export License Application Review Process

    National Research Council Canada - National Science Library

    Young, Shelton

    2002-01-01

    .... The overall audit objective was to determine whether Federal automation programs supporting the export license and review process could be used to establish a common electronic interface creating...

  6. 78 FR 59065 - Interview Room Recording System Standard and License Plate Reader Standard Workshops

    Science.gov (United States)

    2013-09-25

    ... DEPARTMENT OF JUSTICE Office of Justice Programs [OJP (NIJ) Docket No. 1632] Interview Room..., Department of Justice. ACTION: Notice of the Interview Room Recording System Standard and License Plate... performance standards for Interview Room Recording Systems and License Plate Readers used by criminal justice...

  7. Certification for Small Wind Turbine Installers: What's the Hang Up?; Preprint

    Energy Technology Data Exchange (ETDEWEB)

    Oteri, F.; Sinclair, K.

    2012-03-01

    Several programs have been implemented to support the advancement of a professional, mature small wind industry and to ensure that this industry moves forward in a sustainable direction. The development of a standard for small wind turbine systems and the creation of the Small Wind Certification Council support small wind technology that is reliable and safe. Consumers and incentive programs will ultimately rely on certification to differentiate among systems sold in the U.S. market. Certification of small wind installers is yet another component deemed necessary for this industry to expand. The National Renewable Energy Laboratory, under the guidance and funding support of the U.S. Department of Energy, supported the development of small wind system installer certification provided via the North American Board of Certified Energy Practitioners. However, the small wind community is not supportive of the installer certification. There are currently only nine certified installers in the U.S. pool. This paper provides an overview of the installer certification program and why more small wind turbine installers are not pursuing this certification.

  8. 1990 No. 1918. The Nuclear Installations Act 1965 (Repeal and Modifications) Regulations 1990

    International Nuclear Information System (INIS)

    1990-01-01

    These Regulations entered into force on 31 October 1990. They repeal part of Section (1) of the Nuclear Installations Act 1965 to remove the exemption of the United Kingdom Atomic Energy Authority (UKAEA) from licensing under the Act. The Regulations also amend the 1965 Act to ensure that the UKAEA's duties in respect of the safety of premises it occupies will continue to apply whether or not a nuclear site licence has been granted. (NEA) [fr

  9. A quantitative integrated assessment of pollution prevention achieved by integrated pollution prevention control licensing.

    Science.gov (United States)

    Styles, David; O'Brien, Kieran; Jones, Michael B

    2009-11-01

    This paper presents an innovative, quantitative assessment of pollution avoidance attributable to environmental regulation enforced through integrated licensing, using Ireland's pharmaceutical-manufacturing sector as a case study. Emissions data reported by pharmaceutical installations were aggregated into a pollution trend using an Environmental Emissions Index (EEI) based on Lifecycle Assessment methodologies. Complete sectoral emissions data from 2001 to 2007 were extrapolated back to 1995, based on available data. Production volume data were used to derive a sectoral production index, and determine 'no-improvement' emission trends, whilst questionnaire responses from 20 industry representatives were used to quantify the contribution of integrated licensing to emission avoidance relative to these trends. Between 2001 and 2007, there was a 40% absolute reduction in direct pollution from 27 core installations, and 45% pollution avoidance relative to hypothetical 'no-improvement' pollution. It was estimated that environmental regulation avoided 20% of 'no-improvement' pollution, in addition to 25% avoidance under business-as-usual. For specific emissions, avoidance ranged from 14% and 30 kt a(-1) for CO(2) to 88% and 598 t a(-1) for SO(x). Between 1995 and 2007, there was a 59% absolute reduction in direct pollution, and 76% pollution avoidance. Pollution avoidance was dominated by reductions in emissions of VOCs, SO(x) and NO(x) to air, and emissions of heavy metals to water. Pollution avoidance of 35% was attributed to integrated licensing, ranging from between 8% and 2.9 t a(-1) for phosphorus emissions to water to 49% and 3143 t a(-1) for SO(x) emissions to air. Environmental regulation enforced through integrated licensing has been the major driver of substantial pollution avoidance achieved by Ireland's pharmaceutical sector - through emission limit values associated with Best Available Techniques, emissions monitoring and reporting requirements, and

  10. NRC antitrust licensing actions, 1978--1996

    Energy Technology Data Exchange (ETDEWEB)

    Mayer, S.J.; Simpson, J.J.

    1997-09-01

    NUREG-0447, Antitrust Review of Nuclear Power Plants, was published in May 1978 and includes a compilation and discussion of U.S. Nuclear Regulatory Commission (NRC) proceedings and activity involving the NRC`s competitive review program through February 1978, NUREG-0447 is an update of an earlier discussion of the NRC`s antitrust review of nuclear power plants, NR-AIG-001, The US Nuclear Regulatory Commission`s Antitrust Review of Nuclear Power Plants: The Conditioning of Licenses, which reviewed the Commission`s antitrust review function from its inception in December 1970 through April 1976. This report summarizes the support provided to NRC staff in updating the compilation of the NRC`s antitrust licensing review activities for commercial nuclear power plants that have occurred since February 1978. 4 refs., 4 tabs.

  11. NRC Analysis of the environmental impacts and licensing policies for expanded spent fuel storage in the United States

    International Nuclear Information System (INIS)

    Clifford, V.S.

    1978-01-01

    The findings of the U.S. environmental impact studies on spent fuel storage to the year 2000 are reviewed, the design criteria for independent spent fuel storage installations are addressed and the position of the NRC for licensing expanded spent fuel storage capabilities, until such time as final solutions are established, is expressed. (author)

  12. Libraries and licensing

    Directory of Open Access Journals (Sweden)

    Maja Žumer

    2001-01-01

    Full Text Available In the mid 90s, the abundance of various electronic publications exposed libraries to the problems of licensing electronic content. Various licensing principles have been prepared recently to help libraries in the process; it can be said that in general, the knowledge of licensing issues has improved in libraries of all types. Libraries form consortia in order to gain stronger negotiating positions and obtain better conditions.In the article, new licensing principles are presented in more detail, as well as some domestic and foreign experiences with consortia forming.

  13. A materials engineering view of license renewal at the US Nuclear Regulatory Commission

    International Nuclear Information System (INIS)

    Banic, M.

    1999-01-01

    This paper discusses the treatment of license renewal at the US Nuclear Regulatory Commission (NRC) with emphasis on the review process by the staff of the Materials and Chemical Engineering Branch (EMCB). The paper covers the rules governing license renewal, the applications received, the schedule, the approach, and the technical issues. The NRC has a tight schedule of 30-36 months to renew a license. To date, Baltimore Gas and Electric (BG and E) and Duke Power have applied for license renewal. Expecting more applicants, the staff has taken steps to address the public's concern that the effects of aging will be adequately managed and the industry's concern that the reviews will be timely, efficient, and uniform. These steps include identifying aging effects and making the results available in a report and computerized database, approving topical reports and aging management programs for generic use, and reviewing aging management programs according to specific criteria. Materials Engineering staff have a major role because many of the aging issues are materials related. (author)

  14. Report of the Task Force on bonding and perpetual care of nuclear licensed activities

    International Nuclear Information System (INIS)

    Snellings, D.D. Jr.

    1975-01-01

    The primary concern was to consider the bonding and perpetual care requirements of state-licensed shallow land burial sites used for the disposal of radioactive wastes. The specific charge of the task force was to examine in detail the requirements for establishing bonding and perpetual care programs for all types of licensed nuclear activities and to report the findings of the task force as guidance to assist states in program development. Goals and recommendations of the task force are discussed

  15. The current role of simulators for performance evaluations and licensing (case of Mexico)

    International Nuclear Information System (INIS)

    Maldonado A, H.

    1997-01-01

    The main purpose of this paper is to share the experience acquired by the National Commission of Nuclear Safety and Safeguards (CNSNS) during the administration of both certification and licensing operational exams applied to Senior Reactor Operators (SRO) and Reactor OPerators (RO) by using a full-scope simulator. The licensing operational exams are administered to examinate candidates for a SRO or RO license while the certification operational exams are administered to all personnel that possess a SRO or RO license in order to renew their licenses within a six years period. A general description with the most important simulator antecedents from the initial authorization for its usage to provide the ''Initial Simulator Training Course'' until currently in which it has been started the installation and testing performance of a new computer equipment that will improve and increase the simulation capacity of the Laguna Verde Nuclear Power Plant (LVNPP) simulator. In other hand, it is showed the process that the CNSNS will apply during the next verification of the simulator certification which should be performed due to the old computer equipment is being replaced with a more modern computer equipment so that the simulation capability will be improved. The verification process was discussed with the utility personnel and as result of this an agreement has been established to carry into effect this hard task. Finally, the conclusions and recommendations from regulators point of view are presented regarding to the importance of perform a well both evaluation and verification of simulators performance. (author)

  16. The law governing the nuclear licensing procedure in Brazil and in the Federal Republic of Germany

    International Nuclear Information System (INIS)

    Andrade Da Costa Lima, W.

    1984-01-01

    The two first parts of this thesis separately describe the framework of the legal system of the two countries in the field of nuclear energy, whereas the third part goes into details which are explained in order to prepare the subsequent comparative analysis. The comparison covers the structural set-up of the bodies of the national atomic energy provisions, the structure of the various nuclear licensing procedures, the role and competences of experts and their opinions, and the role and competence of jurisdiction. The most profound difference is found in the fact that Brazilian administrative law does not include jurisdiction of an administrative court, and this for constitutional reasons. The civil courts only have competence to examine acts of administration with regard to their legality. The procedure for licensing nuclear installations or equipment is determined by the central licensing authority within the framework of its competency. So far, there have been no attempts in Brazil to seek judicial remedy or to start an action to set aside decisions taken in the nuclear licensing procedure. Furthermore, there are no means in Brazilian law to stop licensing whenever the requirements of Art. 7, section 1, no. I-IV of Lei 6189 are met. The licensing authority has no scope of discretion. Applicants for a licence in Brazil will have no problems in finding out which regulations are applicable to their particular case. The concrete definition of details, however, always is a time-consuming and expensive process. (orig./HSCH) [de

  17. Comparative assessment of licensing processes of uranium mines in Brazil

    International Nuclear Information System (INIS)

    Silva, K.M.; Menezes, R.M.; Mezrahi, A.

    2002-01-01

    Commercial operation of uranium mining and milling started in Brazil, at the Pocos de Caldas Unit, State of Minas Gerais, in 1982. The Pocos de Caldas Unit was licensed by the Brazilian Regulatory Body (CNEN) and its is now in the decommissioning process. In 2000, a new mining and milling installation, the Caetite Unit, located in State of Bahia, started operation. This paper will discuss how Brazilian Nuclear Energy Commission is licensing the Caetite Unit based on the lessons learned from the Pocos de Caldas Unit. The objective is to draw attention to the importance of the safety assessment for a new unit, specially considering that some wrong decisions were taken for the Pocos de Caldas unit. These decisions lead to less effective long term solutions to protect the environment. Notwithstanding the differences between the two units, it is of great value to use the acquired experience to avoid or minimize the short, medium and long term impacts to the environment and population in the new operation. (author)

  18. Safety philosophy and licensing practice in different member states of IAEA: Spain

    International Nuclear Information System (INIS)

    Alonso, A.

    1981-01-01

    With the aim of presenting the licensing experience in Spain, the countries with nuclear activities are divided into three main groups: exporters, qualified importers and importers, being Spain in the second group. The licensing problems, and therefore the licensing experience, are different in the different groups of countries. Moreover, the experience in Spain is enriched by the following facts: an early start, a substantial program and a diversity of types, pressurized and boiling water reactors, and suppliers, American and German plants. Reference is made to the basic legal documents governing licensing in Spain, together with the difficulties in adopting and applying detailed regulations. Within this framework, the licensing experience in Spain is described with reference to the reference plant concept, later enlarged to include the reference-site reference plant concept, ending in the most practical approach of the reference problem concept. Finally specific licensing problems are introduced with reference to the Spanish operating nuclear power plants, the ones under commissioning and in an advanced state of construction and the ones just staring construction. (orig./RW)

  19. Reactor licensing

    International Nuclear Information System (INIS)

    Harvie, J.D.

    2002-01-01

    This presentation discusses reactor licensing and includes the legislative basis for licensing, other relevant legislation , the purpose of the Nuclear Safety and Control Act, important regulations, regulatory document, policies, and standards. It also discusses the role of the CNSC, its mandate and safety philosophy

  20. An independent spent-fuel storage installation at Surry Station: Design and operation

    International Nuclear Information System (INIS)

    McKay, H.S.; Wakeman, B.H.; Pickworth, J.M.; Routh, S.D.; Hopkins, W.C.

    1989-07-01

    Design and licensing of the Surry Power Station Independent Spent Fuel Storage Installation (ISFSI) was initiated in 1982 by Virginia Power as part of a comprehensive strategy to increase spent fuel storage capacity at the Station. Designed to use large, metal dry storage casks, the Surry ISFSI will accommodate 84 such casks with a total storage capacity of 811 MTU of spent PWR fuel assemblies. The ISFSI is located at the Surry Station in a wooded area approximately 1000 meters (3300 feet) east of the reactor facilities. Construction of the first of three reinforced concrete storage pads and its associated support systems was completed in March 1986. The operating license and Technical Specifications were issued by the US NRC on July 2, 1986. Initial loading operations of a General Nuclear Systems, Inc., CASTOR V/21 storage cask began in September 1986. The first two CASTOR V/21 casks were placed in storage at the ISFSI in December 1986. 16 refs., 33 figs., 16 tabs

  1. Nuclear reactor operator licensing

    International Nuclear Information System (INIS)

    Bursey, R.J.

    1978-01-01

    The Atomic Energy Act of 1954, which was amended in 1974 by the Energy Reorganization Act, established the requirement that individuals who had the responsibility of operating the reactors in nuclear power plants must be licensed. Section 107 of the act states ''the Commission shall (1) prescribe uniform conditions for licensing individuals; (2) determine the qualifications of such individuals; and (3) issue licenses to such individuals in such form as the Commission may prescribe.'' The article discusses the types of licenses, the selection and training of individuals, and the administration of the Nuclear Regulatory Commission licensing examinations

  2. Operator licensing examiner standards

    International Nuclear Information System (INIS)

    1987-05-01

    The Operator Licensing Examiner Standards provide policy and guidance to NRC examiners and establish the procedures and practices for examining and licensing of applicants for NRC operator licenses pursuant to Part 55 of Title 10 of the Code of Federal Regulations (10 CFR 55). They are intended to assist NRC examiners and facility licensees to understand the examination process better and to provide for equitable and consistent administration of examinations to all applicants by NRC examiners. These standards are not a substitute for the operator licensing regulations and are subject to revision or other internal operator examination licensing policy changes

  3. Licensing in an international triopoly

    Science.gov (United States)

    Ferreira, Fernanda A.; Ferreira, Flávio

    2011-12-01

    We study the effects of entry of two foreign firms on domestic welfare in the presence of licensing, when the incumbent is technologically superior to the entrants. We consider two different situations: (i) the cost-reducing innovation is licensed to both entrants; (ii) the cost-reducing innovation is licensed to just one of the entrants. We analyse three kind of license: (lump-sum) fixed-fee; (per-unit) royalty; and two-part tariff, that is a combination of a fixed-fee and a royalty. We prove that a two part tariff is never an optimal licensing scheme for the incumbent. Moreover, (i) when the technology is licensed to the two entrants, the optimal contract consists of a licensing with only output royalty; and (ii) when the technology is licensed to just one of the entrants, the optimal contract consists of a licensing with only a fixed-fee.

  4. 14 CFR 431.73 - Continuing accuracy of license application; application for modification of license.

    Science.gov (United States)

    2010-01-01

    ... 14 Aeronautics and Space 4 2010-01-01 2010-01-01 false Continuing accuracy of license application; application for modification of license. 431.73 Section 431.73 Aeronautics and Space COMMERCIAL SPACE... Conditions § 431.73 Continuing accuracy of license application; application for modification of license. (a...

  5. Licensing and Other Controls of the Drinking Driver.

    Science.gov (United States)

    Waller, Patricia F.

    Driver licensing, the only state program with the opportunity for routine personal contact with every driver, has unmatched potential for both general and specific countermeasures to the problem of drunk driving. General countermeasures apply to large groups of drivers prior to the occurrence of any infraction. They may be considered basically…

  6. Quality guarantee of images as a way for obtained lower levels of radiation doses in diagnostic x-ray rooms: criteria for licensing

    International Nuclear Information System (INIS)

    Castellanos, C.A.

    1996-01-01

    This work constitutes a criticism to the present system for licensing in diagnostic x-ray installations in Guatemala. A series of recommendations are made with the aim of obtaining the best diagnostic imaging. This procedure leads to obtain lower doses of radiation for patients and workers

  7. NRC's license renewal regulations

    International Nuclear Information System (INIS)

    Akstulewicz, Francis

    1991-01-01

    In order to provide for the continuity of the current generation of nuclear power plant operating licenses and at the same time ensure the health and safety of the public, and the quality of the environment, the US Nuclear Regulatory Commission (NRC) established a goal of developing and issuing regulations and regulatory guidance for license renewal in the early 1990s. This paper will discuss some of those activities underway to achieve this goal. More specifically, this paper will discuss the Commission's regulatory philosophy for license renewal and the two major license renewal rule makings currently underway. The first is the development of a new Part 54 to address procedural and technical requirements for license renewal; the second is a revision to existing Part 51 to exclude environmental issues and impacts from consideration during the license renewal process. (author)

  8. External radiation levels in installations of nuclear technology center

    International Nuclear Information System (INIS)

    Maletta, Paulo Guilherme M.; Filipetto, Joao; Wakabayashi, Tetsuaki; Silva, Teogenes A. da

    2005-01-01

    The radiological protection is a basic activity of nuclear technology center so that can carry through its activities with security, having to be planned and executed with total effectiveness. One of the basic tools of the radiological protection is the adoption of monitoring programs, that have as objective generality to evaluate the radiological conditions of the workstation and to assure that these conditions are acceptable safe for the displayed individuals, either workers or members of the public, as established in the basic norms of radiological protection. The Centro de Desenvolvimento da Tecnologia Nuclear - CDTN, first institution in Brazil, created in 1952 to entirely dedicate the related works to the nuclear area, to own 39 building, of which they are kept the Triga Reactor, Irradiation Gamma Laboratory, Reject Laboratory, Calibration Dosemeters Laboratory and others. In such installations, radioactive materials are produced, handled, processed and stored, being necessary the levels of external radiation ambient monitoring. As part of the radioprotection plan, monitoring 63 points on strategically located in the external areas to the building of CDTN, using characterized and calibrated thermoluminescence dosemeters. This work describes the dose distribution of the points, the doses evaluation procedure and the 4 results carried through between 2001 and 2004. The data demonstrate the attendance to the level of security established in the basic norm, what it contributed for the operation licensing of to the IBAMA. (author)

  9. Participation of the public in licensing procedures under the Atomic Energy Act and the Federal Emission Control Act

    International Nuclear Information System (INIS)

    Hett, F.T.

    1994-01-01

    Section 7 of the Atomic Energy Act (AtG), section 4 of the Federal Emission Control Act (BImSchG), the Nuclear Installations Licensing Ordinance (AtVfV), and the Ninth Ordinance on the Implementation of the BImSchG (Principles of the licensing procedure) require participation of the public in the procedure before administrative provisions or decisions are issued. The book presents the legally prescribed steps at which participation of the public is mandatory, for the simple case (only one license on the agenda), and for the multi-stage licensing procedure: preliminary negotiations / filling of applications for a license and filing of documents / public announcement of projects / access to files / objections / preclusion of delayed objections / public hearing and other expert discussions / termination of procedure, decision-making by the authorities / decisions on subdivision of procedure into defined stages / modification of the procedure. The analysis of the functions of participation of the public examines the following goals: information / representation of interests / reconciliation of interests / legitimation / control / protection of rights / support. Finally, the book explains the principles of the Constitution demanding participation of the public: human dignity / democracy / rule of law / anticipated effects of the right to have recourse to the courts / civil rights. (orig./HP) [de

  10. Licensed Healthcare Facilities

    Data.gov (United States)

    California Natural Resource Agency — The Licensed Healthcare Facilities point layer represents the locations of all healthcare facilities licensed by the State of California, Department of Health...

  11. Computer systems for nuclear installation data control

    International Nuclear Information System (INIS)

    1987-09-01

    The computer programs developed by Divisao de Instalacoes Nucleares (DIN) from Brazilian CNEN for data control on nuclear installations in Brazil are presented. The following computer programs are described: control of registered companies, control of industrial sources, irradiators and monitors; control of liable person; control of industry irregularities; for elaborating credence tests; for shielding analysis; control of waste refuge [pt

  12. Specification of requirements to get a license for an Independent Spent Fuel Dry Storage Installation (ISFSI) at the site of the NPP-LV; Especificacion de los requerimientos para tramitar una licencia de una instalacion independiente de almacenamiento temporal en seco de combustible gastado (ISFSI) en el sitio de la CNLV

    Energy Technology Data Exchange (ETDEWEB)

    Serrano R, M. L., E-mail: mlserrano@cnsns.gob.mx [Comision Nacional de Seguridad Nuclear y Salvaguardias, Dr. Barragan 779, Col. Narvarte, 03020 Ciudad de Mexico (Mexico)

    2015-09-15

    This article describes some of the work done in the Comision Nacional de Seguridad Nuclear y Salvaguardias (CNSNS) to define specifically the requirements that the Federal Electricity Commission (CFE) shall meet to submit for consideration of CNSNS an operation request of an Independent Spent Fuel Dry Storage Installation (ISFSI). The project of a facility of this type arose from the need to provide storage capacity for spent nuclear fuel in the nuclear power plant of Laguna Verde (NPP-LV) and to continue the operation at the same facility in a safe manner. The licensing of these facilities in the United States of America has two modes: specific license or general license. The characteristics of these licenses are described in this article. However, in Mexico the existing national legislation is not designed for such license types, in fact there is a lack of standards or regulations in this regard. The regulatory law of Article 27 of the Constitution in the nuclear matter, only generally establishes that this type of facility requires an authorization from the Ministry of Energy. For this reason and because there is not a national legislation, was necessary to use the legislation that provides the Nuclear Regulatory Commission of USA, the US NRC. However, it cannot be applied as is established, so was necessary that the CNSNS analyze one by one the requirements of both types of license and determine what would be required to NPP-LV to submit its operating license of ISFSI. The American regulatory applicable to an ISFSI, the 10-Cfr-72 of the US NRC, establishes the requirements for both types of licenses. Chapter 10-Cfr was analyzed in all its clauses and coupled to the laws, regulations and standards as well as to the requirements established by CNSNS, all associated with a store spent fuel on site; the respective certification of containers for spent fuel dry storage was not included in this article, even though the CNSNS also performed that activity under the

  13. 2015 Business Licenses

    Data.gov (United States)

    City of Jackson, Mississippi — This data displays all business license information for the year of 2015. This information details license classifications and status. This information will updated...

  14. Teenagers' licensing decisions and their views of licensing policies: a national survey.

    Science.gov (United States)

    Williams, Allan F

    2011-08-01

    One objective was to determine teenage licensing rates on a national basis, interest in early licensure, and reasons for delay. A second objective was to learn teenagers' opinions about licensing policies, important in states considering ways to upgrade their current licensing systems. One thousand three hundred eighty-three 15- to 18-year-olds completed an online survey in November 2010. They were drawn from a nationally representative panel of US households recruited using probability-based sampling. The panel included cell phone-only households, and Internet access was provided to those without it. Weighting procedures were applied so that the study population represented the national US population of 15- to 18-year-olds. Most teens said that they were interested in getting a license as soon as legally possible, but many had not started the process. At 16, teens were about equally divided among those who had not started, those in the learner stage, and those with a restricted or full license. At 18, 62 percent had full licenses; 22 percent had not started. For those old enough to start, lack of a car, costs, parent availability, ability to get around without a car, and being busy with other activities were leading reasons for delay. The majority of teens were not in favor of higher licensing ages. Forty-six percent thought the minimum learner age should be 16; 30 percent thought the full license age should be 18 or older. The majority approved of night (78%) and passenger (57%) restrictions, and 85 and 93 percent endorsed cell phone and texting bans, respectively. When these policies were packaged together in a single law that included an age 16 start, night, passenger, cell phone and texting bans, and a full license at age 18, 74 percent of teens were in favor. Teenagers are not as supportive of strong licensing policies as parents of teens, but there is evidence that they will support comprehensive policies likely to lead to further reductions in teen crash

  15. Radiopharmaceutical licensing

    International Nuclear Information System (INIS)

    Mather, S.J.

    1992-01-01

    Recent health service legislation, and especially the loss of crown immunity has once again focussed attention on the arrangements for licensing of radiopharmaceuticals. The aim of the article is to describe in general terms the UK licensing system and in particular to provide guidance to those responsible for the supply of radiopharmaceuticals in hospitals. (author)

  16. 7 CFR 4290.390 - Licensing as a RBIC.

    Science.gov (United States)

    2010-01-01

    ... financial information concerning the RBIC in order to qualify for a Leverage commitment; and (4) Enter into... a participant or potential participant in the RBIC program. (d) Effect of a RBIC license. The... following: (1) Approval to operate as a RBIC under the Act; (2) A commitment of Leverage; and (3) An...

  17. An examination of the perceived teaching competencies of novice alternatively licensed and traditionally licensed high school science teachers

    Science.gov (United States)

    Shea, Kathleen A.

    In most states, there are two routes to teacher licensure; traditional and alternative. The alternative route provides an accelerated entry into the classroom, often without the individual engaging in education coursework or a practicum. No matter the route, teaching skills continue to be learned by novice teachers while in the classroom with the guidance of a school-based mentor. In this study, the perceptions of mentor teachers of traditionally and alternatively licensed high school science teachers were compared with respect to mentees' science teaching competency. Further, the study explored the novice teachers' self-perception of their teaching competency. A survey, consisting of 56 Likert-type questions, was completed by mentors (N = 79) and novice high school science teachers (N = 83) in six northeastern states. The results revealed a statistically significant difference in the perceptions of the mentors of traditionally and alternatively licensed novice high school science teachers in the areas of general pedagogical knowledge, pedagogical content knowledge and professional growth, with more favorable perceptions recorded by mentors of traditionally licensed science teachers. There were no differences in the perceptions of the mentors with respect to novice high school teachers' content knowledge. There was no statistical difference in the self-perceptions of competency of the novice teachers. While alternative routes to licensure in science may be a necessity, the results of this study indicate that the lack of professional preparation may need to be addressed at the school level through the agency of the mentor. This study indicates that mentors must be prepared to provide alternatively licensed novice teachers with different assistance to that given to traditionally licensed novice teachers. School districts are urged to develop mentoring programs designed to develop the teaching competency of all novice teachers regardless of the route that led them

  18. State Licenses & Permits

    Data.gov (United States)

    Small Business Administration — Starting a business? Confused about whether you need a business license or permit? Virtually every business needs some form of license or permit to operate legally....

  19. Operator licensing examiner standards

    International Nuclear Information System (INIS)

    1983-10-01

    The Operator Licensing Examiner Standards provide policy and guidance to NRC examiners and establish the procedures and practices for examining and licensing of applicants for NRC operator licenses pursuant to Part 55 of Title 10 of the Code of Federal Regulations (10 CFR 55). They are intended to assist NRC examiners and facility licensees to understand the examination process better and to provide for equitable and consistent administration of examinations to all applicants by NRC examiners. These standards are not a substitute for the operator licensing regulations and are subject to revision or other internal operator examination licensing policy changes. As appropriate, these standards will be revised periodically to accommodate comments and reflect new information or experience

  20. License to build

    International Nuclear Information System (INIS)

    Huntelaar, Mark; Vos, Renate de; Roobol, Lars

    2007-01-01

    Full text: A new license under the nuclear power act is applied for at the Dutch Government for the building of a High Active Repackaging Unit (HAVA-VU in Dutch) at NRG in Petten, The Netherlands. This new building is necessary to comply with our nuclear license to dispose of high active nuclear waste at Petten to the intermediate storage facility (COVRA). In the first part of this paper attention is given to the formal procedure followed by the Government, what type of documents are to be submitted, what time frames are followed, how citizen participation is organized, and as final result a new license. In the second part more detailed information is given about the present license renewal needed for the High Active Repackaging Unit

  1. M5TM alloy high burnup behavior and worldwide licensing

    International Nuclear Information System (INIS)

    Mardon, J.P.; Hoffmann, P.B.; Garner, G.L.

    2005-01-01

    The in-reactor behavior of advanced PWR Zirconium alloys at burnups equal to or below licensing limits has been widely reported. Specifically, the advanced alloy M5 has demonstrated impressive improvements over Zircaloy-4 for fuel rod cladding and fuel assembly structural components. To demonstrate superiority of the alloy at burnups beyond current licensing limits, M5 has been operated in PWR at burnups exceeding 71 GWd/tU in the United States and 78 GWd/tU in Europe. Two extensive irradiation programs have been performed in the United States to demonstrate alloy M5 performance beyond current licensing limits. Four M5 TM fuel rods were exposed to four 24-month cycles in a 15x15 reactor beginning in 1995. Additionally, one 17x17 lead assembly containing M5 fuel rods and guide tubes was operated for four 18-month cycles beginning from 1997. Post-irradiation examinations (PIE) performed after all four cycles in the 15x15 demonstration program revealed excellent performance in the licensed burnup and in the high burnup stages of the experience. Examination of the 4th cycle 17x17 assembly will be accomplished in two stages the first of which is scheduled for June 2005. Moreover, several irradiation campaigns have been performed in Europe in order to confirm the excellent M5 in-pile behavior in demanding PWRs irradiation conditions with regard to void fraction, heat flux, lithium content and temperature. Results from the high burnup fuel examinations verify that the excellent performance achieved up to 62 GWd/tU was continued into higher burnup. The results of high burnup PIE campaigns for European and American PWR's are presented in this paper. Measured performance indicators include fuel assembly dimensional stability parameters (assembly length, fuel rod length, assembly bow, fuel rod bow, fuel rod radial creep and spacer grid width), oxidation measurements (fuel rod and guide tube) and hydrogen pick-up data (fuel rod). In the framework of PCI studies, power ramp

  2. Evaluation of Terminated Nuclear Material Licenses

    International Nuclear Information System (INIS)

    Spencer, K.M.; Zeighami, E.A.

    1999-01-01

    This report presents the results of a six-year project that reviewed material licenses that had been terminated during the period from inception of licensing until approximately late-1994. The material licenses covered in the review project were Part 30, byproduct material licenses; Part 40, source material licenses; and Part 70, special nuclear material licenses. This report describes the methodology developed for the project, summarizes the findings of the license file inventory process, and describes the findings of the reviews or evaluations of the license files. The evaluation identified nuclear material use sites that need review of the licensing material or more direct follow-up of some type. The review process also identified licenses authorized to possess sealed sources for which there was incomplete or missing documentation of the fate of the sources

  3. Preparing as an organization, to submit or to review a construction license application for a DGR of ILW and HLW in France. French National Case - Andra - Preparing to Submit Cigeo's Creation License Application

    International Nuclear Information System (INIS)

    Boissier, Fabrice; Labalette, T.; Leverd, Pascal C.; Voinis, Sylvie

    2014-01-01

    The reversible repository in a deep geological formation is the French reference solution for the long-term management of high-level and intermediate-level long-lived radioactive waste. Since the first French Act on nuclear waste management research (1991), Andra has carried out twenty years of conceptual and basic studies on the subject, leading in particular to the feasibility demonstration in 2005 and to the choice of the detailed reconnaissance zone (ZIRA) in 2010. Taking advantage from this work, Andra has now reached a new phase where the project is engaging in the design of the industrial installation named Cigeo. At this stage, the further development of the project implies that Andra undertakes a multiplicity of actions in order to successfully reach various external and internal key milestones. Of paramount importance is the careful articulation between the regulatory authorization and decision processes and the outcome of the industrial installation design phases. In 2006 was built a regulatory framework that plans a succession of step by step decisions stages: 2013: Public debate on reversibility, memory keeping, environmental and health survey modalities, dialogue with the local stakeholders to harmoniously define and plan the external infrastructures that have to be developed to support the construction and the operation of Cigeo (roads, railway tracks and terminal, power and water supplies, etc.). 2015: Creation license application and start of the regulatory review process (notably various plans of the installation, the description of the solution envisaged for the closure of the facility, the preliminary safety case (operational safety, long-term safety, protection against malevolent actions, management of incidental situations, preliminary acceptance criteria), environmental impact studies (health, salubrity, transports, human activities, nature, patrimonial aspects). 2016-2017: new parliamentary Act on the reversibility conditions of the

  4. Decree No 90-78 of 19 January 1990 amending Decree No 63-1228 of 11 December 1963 on nuclear installations

    International Nuclear Information System (INIS)

    1990-01-01

    This Decree amends Decree No. 63-1228 of 11 December 1963 laying down a prior licensing procedure for large nuclear installations. The amendments aim to harmonize the 1963 Decree with the Act of 1987 on the prevention of major risks. Henceforth decommissioning is taken into account, both in the application and in the licence itself [fr

  5. Pharmaceutical new product development: the increasing role of in-licensing.

    Science.gov (United States)

    Edwards, Nancy V

    2008-12-01

    Many pharmaceutical companies are facing a pipeline gap because of the increasing economic burden and uncertainty associated with internal research and development programs designed to develop new pharmaceutical products. To fill this pipeline gap, pharmaceutical companies are increasingly relying on in-licensing opportunities. New business development identifies new pharmaceuticals that satisfy unmet needs and are a good strategic fit for the company, completes valuation models and forecasts, evaluates the ability of the company to develop and launch products, and pursues in-licensing agreements for pharmaceuticals that cannot be developed internally on a timely basis. These agreements involve the transfer of access rights for patents, trademarks, or similar intellectual property from an outside company in exchange for payments. Despite the risks, in-licensing is increasingly becoming the preferred method for pharmaceutical companies with pipeline gaps to bring new pharmaceuticals to the clinician.

  6. Contestable Licensing

    OpenAIRE

    Zvika Neeman; Gerhard O. Orosel

    2000-01-01

    We analyze a model of repeated franchise bidding for natural monopoly with contestable licensing - a franchisee halds an (exclusive) license to operate a franchise until another rm offers to pay more for it. In a world where quality is observable but not veri able, the simple regulatory scheme we describe combines market-like incentives with regulatory oversight to generate efficient outcomes.

  7. The licensing practice on nuclear power plants in Korea

    International Nuclear Information System (INIS)

    Moon, S. P.

    1994-01-01

    The evolution of Korean regulatory system has tightly coupled with development ot Korean nuclear power program. The nuclear power plant licensing has become a major regulatory function of the government when the construction of the Kori NPP Unit 1 started in early 1970s. During this period, domestic laws and regulations applicable to the licensing of NPP were not yet fully developed. Therefore the vendor countries' laws and regulations were applied as mandatory requirement. Beginning in the early 19808, component approach was used and contracts were awarded separately for major components of the plants, thus enabling more domestic industries to participate in the projects. The two-step licensing system was incorporated into the law. In the third phase from 1987, major efforts have been concentrated on the maximum participation of local industries. The overriding priority for selecting suppliers was the condition of higher nuclear technology transfer to Korea. The Korea Institute of Nuclear Safety (KINS) was established in 1990 as an independent regulatory expert organization

  8. Tast Force report on bonding and perpetual care of nuclear licensed activities

    International Nuclear Information System (INIS)

    Anon.

    1975-01-01

    Potential issues which should be considered prior to the adoption and implementation of a bonding or perpetual care program are examined. The following topics are discussed: problem definition; major processors; factors in setting the amount of a bond; waste handling licensees; ore refineries and mills; former AEC licensed facilities; other specific licenses; authority; states where it is deemed that amendment of existing statutes is necessary to authorize imposition of a bonding requirement for licenses; administration; and recommendations. The following appendices are included: summary of cost estimate to decontaminate the American Nuclear Company; report on 1974 national conference on radiation control workshop no. 3; suggested changes to state regulations; and suggested legislation for licensee bonding and perpetual care trust funds

  9. Cask development, testing, and licensing

    International Nuclear Information System (INIS)

    Quinn, G.J.; Haelsig, R.T.; Warrant, M.M.

    1986-01-01

    The NuPac 125-B Rail Cask was developed to provide a safe means of transporting the damaged core of Three Mile Island Unit 2 from the TMI site at Middletown, PA, to the Idaho National Engineering laboratory (INEL) at Idaho Falls, ID. The development of the NuPac 125-B Rail Cask posed two engineering and technical management challenges; Licensing Strategy - The NuPac 125-B Rail Cask represented the first irradiated fuel rail cask developed within the United States in the past decade, a decade characterized by changing nuclear regulations, and Accelerated Schedule - The TMI-2 defueling schedule demanded a cask development schedule one-third as long as normally required. These challenges governed the overall development and licensing process for the cask. First, a high degree of conservation was incorporated into the design to allow quick, simplified demonstrations of adequacy to regulatory staff. Second, redundant design techniques were employed in all areas of uncertainty. The testing program eliminated performance uncertainties and validated predictions and predictive models. Drop tests of a quarter-scale model of the cask were conducted, and results were correlated with analytic predictions to verify structural and mechanical performance of the cask. Full-scale tests of the canisters were conducted to verify structural behavior of canister internals which provide criticality control. This paper describes the testing program for the NuPac 125-B Rail Cask, presents results therefrom, and correlates findings with Regulation 10 CFR 71 of the U.S. Nuclear Regulatory Commission

  10. NRC licensing of uranium enrichment plants

    International Nuclear Information System (INIS)

    Moran, B.W.

    1991-01-01

    The US Nuclear Regulatory Commission (NRC) is preparing a rule making that establishes the licensing requirements for low-enriched uranium enrichment plants. Although implementation of this rule making is timed to correspond with receipt of a license application for the Louisiana Energy Services centrifuge enrichment plant, the rule making is applicable to all uranium enrichment technologies. If ownership of the US gaseous diffusion plants and/or atomic vapor laser isotope separation is transferred to a private or government corporation, these plants also would be licensable under the new rule making. The Safeguards Studies Department was tasked by the NRC to provide technical assistance in support of the rule making and guidance preparation process. The initial and primary effort of this task involved the characterization of the potential safeguards concerns associated with a commercial enrichment plant, and the licensing issues associated with these concerns. The primary safeguards considerations were identified as detection of the loss of special nuclear material, detection of unauthorized production of material of low strategic significance, and detection of production of uranium enriched to >10% 235 U. The primary safeguards concerns identified were (1) large absolute limit of error associated with the material balance closing, (2) the inability to shutdown some technologies to perform a cleanout inventory of the process system, and (3) the flexibility of some technologies to produce higher enrichments. Unauthorized production scenarios were identified for some technologies that could prevent conventional material control and accounting programs from detecting the production and removal of 5 kg 235 U as highly enriched uranium. Safeguards techniques were identified to mitigate these concerns

  11. Population genetics analysis using R and the Geneland program

    DEFF Research Database (Denmark)

    Guillot, Gilles; Santos, Filipe; Estoup, Arnaud

    2011-01-01

    Geneland program documentation 2011 Program distributed under GNU license as an R package on the Comprehensive R Archive Network.......Geneland program documentation 2011 Program distributed under GNU license as an R package on the Comprehensive R Archive Network....

  12. Regulation of the life cycle of nuclear installations. Peer discussions on regulatory practices

    International Nuclear Information System (INIS)

    1999-06-01

    This report arises from the sixth series of peer discussions on regulatory practices entitled 'Regulation of Life Cycle of Nuclear Installations'. Senior regulators from 18 Member States participated in three peer group discussions during 1997-1998. This report presents the outcome of these meetings and recommendations of good practices identified by senior regulators, which do not necessarily reflect those of the governments of the nominating Member States, the nominating organizations, or the IAEA. The purpose of this report is to disseminate the views which the senior regulators presented at the meetings relating to the policies, principles and requirements imposed by regulatory bodies for the safe management of the life cycle of a nuclear installation. The intention of doing this is to assist Member States in the formulation and enhancement of their regulatory control over PLCM by identifying commonly accepted good practices. This report is structured to cover the subject matter under the following main headings: Policies and Principles for the Life Cycle Management of Nuclear Installations; Responsibilities of the Regulatory Body and the Operating Organization; Requirements and Criteria Imposed by the Regulatory Body; Licensing and Regulatory Assessment for Plant Life Cycle Management; and Good Practices

  13. Arrangements for dealing with emergencies at civil nuclear installations

    International Nuclear Information System (INIS)

    Turner, M.J.; Robinson, I.F.

    1989-01-01

    This paper covers arrangements for dealing with nuclear emergencies at sites licensed by the Health and Safety Executive/Nuclear Installations Inspectorate. Such arrangements are over and above the contingency plans required for radiation incidents as required by the Ionising Radiations Regulations. The statutory position of the NII is described and, although the NII is limited to regulating the activities of the operator, the functions of the other organisations that could be involved in dealing with an emergency are briefly covered in order to give as complete a picture as possible. The basis for emergency planning is given together with the consequences and countermeasures for mitigation of a nuclear emergency, including the use of ERLs. The requirements for emergency exercises are explained. (author)

  14. USNRC severe core damage assessment program

    Energy Technology Data Exchange (ETDEWEB)

    Hanson, J E [EG and G Idaho, Inc., Idaho Falls (USA); Johnston, W V; Kelber, C N [Nuclear Regulatory Commission, Washington, DC (USA)

    1981-01-01

    The accident at the Three Mile Island nuclear power station has significantly altered the perception of the importance of beyond-design-basis accidents in licensing and safety reviews of light-water reactors in the USA. Increased consideration will be given by the United States Nuclear Regulatory Commission to low-probability, high-risk core melt accidents in future licensing proceedings. To this end, the USNRC is mounting experimental and analytic methods development programs to provide the technical basis for future LWR design and licensing criteria related to class-9 accidents. The scope, objectives, and content of five major new programs addressing safety and licensing issues for beyond-design-basis accidents are reviewed and the rationale and logic for formulation of the programs is discussed.

  15. Safety Assessment of the New Very Low-Level Waste Disposal Installation at El Cabril, Spain

    International Nuclear Information System (INIS)

    Lopez, I.; Navarro, M.; Zuloaga, P.

    2009-01-01

    The sixth General Radioactive Waste Plan approved by the Spanish government in 2006, foresees important volumes of wastes with a very low content of radioactivity mainly coming from the dismantling of nuclear power plants, along with the occurrence of some radiological industrial incidents in the past. This fact has boosted the construction of a new disposal installation, specifically designed for this category of waste. This new installation is part of the existing low and intermediate level waste (LILW) disposal facility at El Cabril, and includes four cells with a total capacity of around 130,000 m 3 . The design of the cells is consistent with the European Directive for the disposal of hazardous waste and fulfils the same basic safety criteria as the present facility for LILW. The safety assessment methodology applied for the very low level waste (VLLW) installation is fully coherent with the approach adopted for the existing disposal facility for low and intermediate level waste (concrete vaults disposal system) and takes into account the potential impact of the new installation during both the operational and long-term periods. The license for the VLLW installation was granted by the Spanish Ministry of Industry, Tourism and Commerce (MITYC) in July 2008, following technical approval by the Nuclear Safety Council (CSN), and the first disposal operation occurred in October 2008. (authors)

  16. Evaluation guideline for the study of the radiological impact of based nuclear installations (INB) presented in support of releases authorization demands; Guide d'examen pour l'etude de l'impact radiologique d'une installation nucleaire de base (INB) fournie a l'appui des demandes d'autorisation de rejets

    Energy Technology Data Exchange (ETDEWEB)

    Chartier, M; Despres, A; Supervil, S; Conte, D; Hubert, P; Oudiz, A; Champion, D

    2002-10-01

    In the case of a license demand for the effluents release and water taking for a nuclear installation, the operating must realize a study of the nuclear effluents radiological impact on the environment and the public health. In this context, the study presents technical and methodological specifications which led the Direction of the Nuclear Installations Safety (DSIN) and the General Direction of the Health (DGS) to ask the IPSN the elaboration of a guideline to help these studies evaluation. The guideline presents the regulatory context, the description of the installations, the treatment and the control processes, the rules of management, the description of the environment, the estimation of the radiological impacts and the environment control system definition. (A.L.B.)

  17. 31 CFR 596.306 - License.

    Science.gov (United States)

    2010-07-01

    ... ASSETS CONTROL, DEPARTMENT OF THE TREASURY TERRORISM LIST GOVERNMENTS SANCTIONS REGULATIONS General Definitions § 596.306 License. Except as otherwise specified, the term license means any license or...

  18. Safety aspects of nuclear plant licensing in Canada

    International Nuclear Information System (INIS)

    Jennekens, J.H.F.

    1975-01-01

    The legislative authority is laid down in the Atomic Energy Control Act, 1946, declaring atomic energy a matter of national interest and establishing the Atomic Energy Control Board (AECB) as the competent body for regulating all aspects of atomic energy. The Act also vests a Minister designated by the Government with research and exploitation functions; thus, by Ministerial order, Atomic Energy of Canada Limited was established in 1952 as a State-owned company. The Nuclear Liability Act, 1970, channels all liability for nuclear damage to the operator of a nuclear installation and requires him to obtain insurance in the amount of $75 million, part of which may be re-insured by the Government. The licensing requirements comprise the issuance of a site approval, a construction licence and an operating licence. The AECB is assisted in its licensing functions by its Nuclear Plant Licensing Directorate and by the Reactor Safety Advisory Committee co-operating with each other in making extensive safety assessments of a licence application. A site evaluation report, a preliminary safety report and a final safety report are required in relation to the siting, construction and operation of a nuclear power plant. The Canadian reactor safety philosophy is based on the concept of defence in depth, implemented through a multi-step approach, which includes avoidance of malfunctions, provision of special safety systems, periodic inspection and testing, and avoidance of human errors. Specific criteria and principles have evolved in applying this basic safety philosophy and radiation protection standards are derived from international recommendations. Stringent control is exercised over the management of radioactive waste and management facilities must meet the engineering and procedural requirements of AECB before they can be placed in operation. (author)

  19. Understanding Licensing Behavior

    DEFF Research Database (Denmark)

    Cabaleiro, Goretti; Moreira, Solon; Reichstein, Toke

    The potential for rent dissipation has been argued to be the main cause of firms? licensing out behavior being stifled.However, this aspect has been scarcely studied empirically. We draw on rent dissipation arguments, and hypothesize that firms suffering from the not-invented-here (NIH) syndrome......, firms in competitive product markets, and firms that have incurred substantial sunk cost are associated with lower rates of technology out-licensing. We also posit that sunk costs negatively moderate the relationship between competition in the licensor?s product market, and licensing rate. We test our...

  20. Nuclear power stations licensing

    International Nuclear Information System (INIS)

    Solito, J.

    1978-04-01

    The judicial aspects of nuclear stations licensing are presented. The licensing systems of the United States, Spain, France and Federal Republic of Germany are focused. The decree n 0 60.824 from July 7 sup(th), 1967 and the following legislation which define the systematic and area of competence in nuclear stations licensing are analysed [pt

  1. Licensing and safety of nuclear power plants in Canada

    International Nuclear Information System (INIS)

    Boyd, F.C.

    1981-09-01

    An overview of the regulatory framework and licensing process for nuclear power plants in Canada is given along with an outline of the evolution of the safety philosophy followed and some comments on how this philosophy and process could be applied by a country embarking on a nuclear power program

  2. An overview of Class I Structures license renewal Industry Report

    International Nuclear Information System (INIS)

    Statton, J.A.; Renfro, L.J.; Peeifer, B.W.; Deng, D.Z.; Byron, J.

    1991-01-01

    The results of this evaluation indicate that license renewal of Class I Structures is technically achievable and that most age-related degradation can be managed by existing effective programs such that the continued safe operation of the plant is assured. Existing effective programs are satisfactory as long as plant-unique verification of design and operating features is performed. Thus, the conclusions of this IR can be applied to individual plants. (author)

  3. 76 FR 15826 - Fisheries of the Exclusive Economic Zone Off Alaska; Gulf of Alaska License Limitation Program

    Science.gov (United States)

    2011-03-22

    ... Islands (AI); Southeast Outside District (SEO); Central Gulf of Alaska (CG), which includes the West... LLP licenses could resume fishing under the licenses in the future and thereby adversely affect active... BS or AI regulatory areas because a Pacific cod endorsement requirement has already been established...

  4. Piezometer installation and monitoring procedure: Revision 1

    International Nuclear Information System (INIS)

    1987-04-01

    The Deaf Smith County (Texas) site has been selected by the US Department of Energy as one of three candidate sites for characterization to determine its suitability as a geologic repository for high-level nuclear waste. The installation and monitoring of piezometers has been identified as one of the tasks required during the development of an underground Exploratory Shaft Facility to satisfy specific information needs through a program of in situ testing, instrumentation and monitoring. The scope of piezometer installation and monitoring encompasses the installation of fluid pressure measuring equipment and the subsequent collection, presentation and interpretation of piezometric data from strata surrounding the Exploratory Shaft Facility (ESF) prior to, during and following construction of the ESF, and as part of geohydrologic testing within the ESF. This procedure describes the required instrumentation, equipment, and sequence of activities for piezometer installation in the ESF. The procedure also includes details on the data recording and presentation requirements, personnel responsibilities, test management and quality assurance. 16 refs., 12 figs., 2 tabs

  5. FOSS License Selection and Code Management

    OpenAIRE

    Vescuso, Peter

    2011-01-01

    With nearly 2,000 free and open source software (FLOSS) licenses, software license proliferation¿ can be a major headache for software development organizations trying to speed development through software component reuse, as well as companies redistributing software packages as components of their products. Scope is one problem: from the Free Beer license to the GPL family of licenses to platform-specific licenses such as Apache and Eclipse, the number and variety of licenses make it difficu...

  6. PWR reactor pressure vessel internals license renewal industry report; revision 1. Final report

    International Nuclear Information System (INIS)

    Schwirian, R.; Robison, G.

    1994-07-01

    The U.S. nuclear power industry, through coordination by the Nuclear Management and Resources Council (NUMARC), and sponsorship by the U.S. Department of Energy (DOE) and the Electric Power Research Institute (EPRI), has evaluated age-related degradation effects for a number of major plant systems, structures and components, in the license renewal technical Industry Reports (IRs). License renewal applicants may choose to reference these IRs in support of their plant-specific license renewal applications, as an equivalent to the integrated plant assessment provisions of the license renewal rule (10 CFR Part 54). Pressurized water reactor (PWR) reactor pressure vessel (RPV) internals designed by all three U.S. PWR nuclear steam supply system vendors have been evaluated relative to the effects of age-related degradation mechanisms; the capability of current design limits; inservice examination, testing, repair, refurbishment, and other programs to manage these effects; and the assurance that these internals can continue to perform their intended safety functions in the license renewal term. This industry report (IR), one of a series of ten, provides a generic technical basis for evaluation of PWR reactor pressure vessel internals for license renewal

  7. Installation tests for BERSAFE 88

    International Nuclear Information System (INIS)

    Bamfield, R.D.; Haigh, R.

    1989-02-01

    A set of ten test problems for each of the four BERSAFE stress analysis programs is provided. These problems along with this report, which forms part of the BERSAFE 88 documentation, constitute a test of the customers' BERSAFE installation. On running the problems and attaining results identical to those presented here, the customer should have some confidence that his system is operating correctly. (author)

  8. Learning-by-Licensing: How Chinese Firms Benefit From Licensing-In Technologies

    DEFF Research Database (Denmark)

    Wang, Yuandi; Roijakkers, N.; Vanhaverbeke, W.

    2012-01-01

    This paper explores how interfirm variations in their in-licensed technology portfolios influence subsequent innovation performance. Existing studies mainly assume licensed technologies are homogeneously accessible to firms, and a prevailing explanation as to why firms vary in their innovation pe...

  9. Long Term Operation R and D to Investigate the Technical Basis for Life Extension and License Renewal Decisions

    International Nuclear Information System (INIS)

    Gaertner, John

    2012-01-01

    Establishing an improved technical basis for long term operation of existing plants is a nuclear industry priority. The Electric Power Research Institute (EPRI) has responded with a comprehensive Long Term Operation (LTO) Program addressing this need for existing nuclear power plants world-wide. The program supports both the business decisions necessary to achieve high performance operation and the licensing requirements for operation beyond 60 years. The program selects its R and D priorities in a structured and objective way with much industry input to provide useful results for decisions in the 2014 to 2019 time frame. The program is highly collaborative with U.S. Department of Energy (DOE) and with EPRI-member utilities. The R and D portfolio includes materials aging (metals, concrete, and cables), modernization of information and control technology, enhanced safety analysis, advanced fuel design, demonstration plant activities, life cycle management, and identification of aging management program need for subsequent license renewal. The program has focussed stakeholders world-wide on the technical issues of long term operation, and it is on-track to provide practical results for life extension and license renewal decisions. (author)

  10. Installing and Testing a Server Operating System

    Directory of Open Access Journals (Sweden)

    Lorentz JÄNTSCHI

    2003-08-01

    Full Text Available The paper is based on the experience of the author with the FreeBSD server operating system administration on three servers in use under academicdirect.ro domain.The paper describes a set of installation, preparation, and administration aspects of a FreeBSD server.First issue of the paper is the installation procedure of FreeBSD operating system on i386 computer architecture. Discussed problems are boot disks preparation and using, hard disk partitioning and operating system installation using a existent network topology and a internet connection.Second issue is the optimization procedure of operating system, server services installation, and configuration. Discussed problems are kernel and services configuration, system and services optimization.The third issue is about client-server applications. Using operating system utilities calls we present an original application, which allows displaying the system information in a friendly web interface. An original program designed for molecular structure analysis was adapted for systems performance comparisons and it serves for a discussion of Pentium, Pentium II and Pentium III processors computation speed.The last issue of the paper discusses the installation and configuration aspects of dial-in service on a UNIX-based operating system. The discussion includes serial ports, ppp and pppd services configuration, ppp and tun devices using.

  11. Operator licensing examiner standards

    International Nuclear Information System (INIS)

    1993-01-01

    The Operator Licensing Examiner Standards provide policy and guidance to NRC examiners and establish the procedures and practices for examining licensees and applicants for reactor operator and senior reactor operator licenses at power reactor facilities pursuant to Part 55 of Title 10 of the Code of Federal Regulations (10 CFR 55). The Examiner Standards are intended to assist NRC examiners and facility licensees to better understand the initial and requalification examination processes and to ensure the equitable and consistent administration of examinations to all applicants. These standards are not a substitute for the operator licensing regulations and are subject to revision or other internal operator licensing policy changes

  12. Flexible licensing

    Directory of Open Access Journals (Sweden)

    Martyn Jansen

    2012-07-01

    Full Text Available The case is presented for a more flexible approach to licensing online library resources. Today's distributed education environment creates pressure for UK higher and further education institutions (HEI/FEIs to form partnerships and to develop educational products and roll them out across the globe. Online library resources are a key component of distributed education and yet existing licensing agreements struggle to keep pace with the increasing range of users and purposes for which they are required. This article describes the process of developing a flexible approach to licensing and proposes a new model licence for online library resources which has the adaptability needed in this new global educational landscape. These ideas have been presented and discussed at various workshops across Eduserv's and JISC Collections' higher education and publisher communities, and further consultation is ongoing.

  13. Fuel Receiving and Storage Station. License application, amendment 4

    International Nuclear Information System (INIS)

    1975-04-01

    Amendment No. 4 of the application for licensing the Barnwell Fuel Processing Plant is presented. Information is included on: the quantity and characteristics of nuclear fuel assemblies which can be received and stored; specifications limiting the outside washdown of contaminated casks received for unloading; and definition of environmental monitoring program. (U.S.)

  14. Trends in nuclear licensing

    Energy Technology Data Exchange (ETDEWEB)

    Dalton, N W [Council for Nuclear Safety, Hennopsmeer, Pretoria (South Africa)

    1990-06-01

    The development of nuclear safety and licensing is briefly reviewed in four stages namely: The Formative Period (1946-1959), The Expansive Period (1960-1969), The Mature Period (1970-1979) and the Apprehensive Period (1980-1989). Particular safety issues in the respective periods are highlighted to indicate the changing emphasis of nuclear licensing over the past thirty years or so. Against this background, nuclear licensing. (author)

  15. Trends in nuclear licensing

    International Nuclear Information System (INIS)

    Dalton, N.W.

    1990-01-01

    The development of nuclear safety and licensing is briefly reviewed in four stages namely: The Formative Period (1946-1959), The Expansive Period (1960-1969), The Mature Period (1970-1979) and the Apprehensive Period (1980-1989). Particular safety issues in the respective periods are highlighted to indicate the changing emphasis of nuclear licensing over the past thirty years or so. Against this background, nuclear licensing. (author)

  16. IRIS. Progress in licensing and toward deployment

    International Nuclear Information System (INIS)

    Petrovic, B.; Carelli, M.D.; Kling, C.L.; Cavlina, N.; Grgic, D.

    2006-01-01

    The International Reactor Innovative and Secure (IRIS) is an advanced, integral, light water cooled, pressurized reactor of smaller generating capacity (1000 MWt, or 335 MWe). It is being developed through a strong international partnership by a team lead by Westinghouse and including organizations from 10 countries. The main objective of the project is to offer a simple nuclear power plant with outstanding safety, attractive economics and enhanced proliferation resistance characteristics ready for deployment within the next decade. IRIS embodies the requirements set forth by the recently announced US DOE Global Nuclear Energy Partnership (GNEP) program for worldwide deployment of a smaller-scale reactors and provides a viable bridge to Generation IV reactors. IRIS is designed to address the needs of both developed and emerging markets. Its smaller power level provides deployment flexibility in larger developed markets, and makes it in particular well suited for markets with limited grids or where the annual energy demand growth is moderate. Due to its short construction time and the staggered build option, IRIS significantly reduces the required financing, improves cash flow, and provides a viable solution for economies with limited resources. While based on proven and worldwide accepted LWR technology, IRIS introduces a number of innovative solutions to simplify its design and improve safety and operational characteristics, including the integral primary system and its components, as well as the safety-by-design approach. These features will be tested and demonstrated in a testing program that has been initiated. As its centerpiece, the program will include the integral test facility. Results of this program will support licensing with the US NRC. A multinational licensing is considered to facilitate worldwide deployment. (author)

  17. The characteristic features of the German and the U.S. American law governing the licensing of nuclear installations

    International Nuclear Information System (INIS)

    Heitsch, C.

    1993-01-01

    The author's comparative analysis of the German and the U.S. American legislation is intended to exhibit the specific structures of the two regulatory systems, and their performance regarding the intended purpose of providing the best possible protection against the risks posed by nuclear energy. It is further analysed whether instruments or structures of the U.S. American law can be adopted by the German law and applied to solving problems arising in Germany. In the selfcontained review of the German Atomic Energy Act and the nuclear licensing provisions, emphasis is placed on the development of judicial control in Germany, as the court decisions have a major impact on accepted practice in Germany. This is followed by a self-contained review of the licensing procedure in the U.S.A., with a focus on the right to be heard of the general public, and on the system of rulemaking powers by the state commissions and agencies. The author finally explains the most significant differences of the two regulatory systems and draws some conclusions as to the underlying legal policy. A concluding analysis examines the question of whether the recent judgments by the Federal Administrative Court, relating to judicial control and the binding effect of substantiating administrative regulations, are justifiable from the dogmative point of views. (orig.) [de

  18. RECOGNITION DESIGN OF LICENSE PLATE AND CAR TYPE USING TESSERACT OCR AND EmguCV

    Directory of Open Access Journals (Sweden)

    Antonius Herusutopo

    2012-10-01

    Full Text Available The goal of the research is to design and implement software that can recognize license plates and car types from images. The method used for the research is soft computing using library of EmguCV. There are four phases in creating the software, i.e., input image process, pre-processing, training processing and recognition. Firstly, user enters the car image. Then, the program reads and does pre-processing the image from bitmap form into vector. The next process is training process, which is learning phase in order the system to be able recognize an object (in this case license plate and car type, and in the end is the recognition process itself. The result is data about the car types and the license plates that have been entered. Using simulation, this software successfully recognized license plate by 80.223% accurate and car type 75% accurate.Keywords: Image; Pre-Processing; License plate and Car Type Recognition, Training

  19. Mock Site Licensing Demonstration Project. Final report

    International Nuclear Information System (INIS)

    Roop, R.D.

    1986-06-01

    The Mock Site Licensing Demonstration Project developed the Low-Level Radioactive Waste Siting Simulation, a role-playing exercise designed to facilitate the process of siting and licensing disposal facilities for low-level waste (LLW). This report describes the development, contant, and usefulness of the siting simulation. The simulation was designed by Harvard University's Program on Negotiation; it can be conducted at a workshop or conference, involves 14 or more participants, and requires about eight hours to complete. The simulation consists of two sessions. In the first, participants negotiate the selection of siting criteria, and in the second, a preferred site for a facility is chosen from three candidate sites. The project sponsored two workshops (in Boston, Massachusetts and Richmond, Virginia) in which the simulation was conducted for persons involved in planning for LLW. It is concluded that the siting simulation can be useful in three ways: (1) as a tool for information dissemination, (2) as a vehicle that can foste communication among parties in conflict, and (3) as a step toward consensus building and conflict resolution. The DOE National Low-Level Waste Management Program is now making the siting simulation available for use by states, regional compacts, and other organizations involved in development of LLW disposal facilities

  20. The Monticello license renewal project

    International Nuclear Information System (INIS)

    Clauss, J.M.; Harrison, D.L.; Pickens, T.A.

    1993-01-01

    Today, 111 nuclear power plants provide over 20 percent of the electrical energy generated in the United States. The operating license of the oldest operating plant will expire in 2003, one-third of the existing operating licenses will expire by 2010 and the newest plant's operating license will expire in 2033. The National Energy Strategy (NES) prepared by the Department of Energy (DOE) assumes that 70 percent of the current operating plants will continue to operate beyond their current license expiration. Power from current operating plants can assist in ensuring an adequate, diverse, and environmentally acceptable energy supply for economic growth and improved U.S. competitiveness. In order to preserve this energy resource, three major tasks must be successfully completed: (1) establishment of regulations, technical standards, and procedures for the preparation and review of License Renewal Applications (LRAs); (2) development of technical criteria and bases for monitoring, refurbishing or replacing plant equipment; and (3) demonstration of the regulatory process by a plant obtaining a renewed license. Since 1986, the DOE has been working with the nuclear industry and the Nuclear Regulatory Commission (NRC) to establish and demonstrate the option to extend the life of a nuclear power plant by renewing the operating license. The Monticello Lead Plant demonstration project was initiated in September 1988, following the Pilot Plant studies. This paper is primarily focused on the status and insights gained from the Northern States Power Company (NSP) Monticello Lead Plant demonstration project. The following information is included: (1) Current Status - Monticello License Renewal Application; (2) Economic Analysis; (3) License Renewal Regulatory Uncertainty Issues; (4) Key Decisions; (5) Management Structure; (6) Technical and Licensing Perspective; (7) NRC Interactions; (8) Summary

  1. Agricultural biogas. Intermediate assessment - Biogas Mission. The Energivie Program - Projects of development of farm-based methanization. Site selection, Visits of installations, Consultation of installers

    International Nuclear Information System (INIS)

    Maurer, Michel

    2005-06-01

    A first document presents Alsace pilot projects: technical and economic recalls, site pre-selection, project leader, description of the mobilisation of lipid co-substrates (interest of fats, modalities), regulatory context (for biogas production, electric energy supply and digestate use). It also presents installer companies which have been consulted for these projects. Another document proposes technical and economical analyses of proposals made by installers, and an analysis of deadlocking points for these pilot projects. Technical, economic, and environmental elements, as well as those dealing with installation management, costs and construction delays to be provided by the consulted company are indicated and commented

  2. Solar, Install, Mount, Production, Labor, Equipment Balance of Systems

    Energy Technology Data Exchange (ETDEWEB)

    Gentry, Russell [Georgia Tech Applied Research Corporation, Atlanta, GA (United States); Al-Haddad, Tristan [Georgia Tech Applied Research Corporation, Atlanta, GA (United States); Valdes, Francisco [Georgia Tech Applied Research Corporation, Atlanta, GA (United States); Caravati, Kevin [Georgia Tech Applied Research Corporation, Atlanta, GA (United States); Goodman, Joseph [Georgia Tech Applied Research Corporation, Atlanta, GA (United States)

    2015-08-27

    The GTRI led project team in partnership with the DOE, universities, and numerous industry leaders, have advanced the mission of the DOE EERE, the Solar Energy Technologies Program, and the SunShot Initiative by accelerating the research, development, and demonstration of solar PV technologies that provide Extreme Balance of Systems Cost Reductions (BOS-X). The research produced 132 design concepts, resulting in 19 invention disclosures, five patent applications, four 90% pre-commercial designs, and three licensed technologies. Technology practice rights were obtained by an industry partner, and a new solar commercial start-up company was launched in Atlanta as a result of this project. Innovations in residential, commercial, and utility scale balance of systems technologies were realized through an unprecedented multi-disciplinary university/industry partnership with over 50 students and 24 faculty members that produced 18 technical publications, a PhD thesis, and two commercially deployed operating prototypes. The technical effectiveness and economic feasibility of the multidisciplinary systems based approach executed by the project team was realized through 1) a comprehensive evaluation of industry, regulatory, and public stakeholder requirements; 2) numerous industry/student/faculty engagements in design studios, technical conferences, and at solar PV installation sites; 3) time and motion studies with domain experts that provided technical data and costs for each phase and component of the solar PV installation processes; 4) extensive wind tunnel and systems engineering modeling; and 5) design, construction, and demonstration of the selected technologies in the field at high profile sites in Atlanta. The SIMPLE BOS project has benefitted the public in the following ways: • Workforce development: The launch of a start-up company to commercialize the DOE funded SIMPLE BoS designs has directly created 9 new jobs in the State of Georgia. As of November 2014, the

  3. 7 CFR 1436.13 - Loan installments, delinquency, and acceleration of maturity date.

    Science.gov (United States)

    2010-01-01

    ... 7 Agriculture 10 2010-01-01 2010-01-01 false Loan installments, delinquency, and acceleration of... FACILITY LOAN PROGRAM REGULATIONS § 1436.13 Loan installments, delinquency, and acceleration of maturity... delinquency, CCC may permit a rescheduling of the debt or other measures consistent with the collection of...

  4. Design and installation of a system of quality for the specialized services of irradiation

    International Nuclear Information System (INIS)

    Rodriguez, Y.; Romero, M.; Castillo, E.; Villoch, A.; Cruz, S.

    1999-01-01

    This study is traced as objective the the design and installation of a System of Quality of agreement to the norm ISO 9002 and the NC-ISO/IEC Guide 25. For this a program was elaborated that it embraced the following phases: organization, installation and maintenance of the system. The elements that would conform the whole program of quality of the irradiation services they would be given from the qualification of the material to process until the certification of the dose imparted to the product; as well as the internal and external control of the quality in the own one installation

  5. Radioactive waste from non-licensed activities - identification of waste, compilation of principles and guidance, and proposed system for final management

    International Nuclear Information System (INIS)

    Jones, C.; Pers, K.

    2001-07-01

    Presently national guidelines for the handling of radioactive waste from non-licensed activities are lacking in Sweden. Results and information presented in this report are intended to form a part of the basis for decisions on further work within the Swedish Radiation Protection Institute on regulations or other guidelines on final management and final disposal of this type of waste. An inventory of radioactive waste from non-licensed activities is presented in the report. In addition, existing rules and principles used in Sweden - and internationally - on the handling of radioactive and toxic waste and non-radioactive material are summarized. Based on these rules and principles a system is suggested for the final management of radioactive material from non-licensed activities. A model is shown for the estimation of dose as a consequence of leaching of radio-nuclides from different deposits. The model is applied on different types of waste, e.g. peat ashes, light concrete and low-level waste from a nuclear installation

  6. The licensing practice on nuclear power plants in Korea

    Energy Technology Data Exchange (ETDEWEB)

    Moon, S P

    1994-12-31

    The evolution of Korean regulatory system has tightly coupled with development ot Korean nuclear power program. The nuclear power plant licensing has become a major regulatory function of the government when the construction of the Kori NPP Unit 1 started in early 1970s. During this period, domestic laws and regulations applicable to the licensing of NPP were not yet fully developed. Therefore the vendor countries` laws and regulations were applied as mandatory requirement. Beginning in the early 19808, component approach was used and contracts were awarded separately for major components of the plants, thus enabling more domestic industries to participate in the projects. The two-step licensing system was incorporated into the law. In the third phase from 1987, major efforts have been concentrated on the maximum participation of local industries. The overriding priority for selecting suppliers was the condition of higher nuclear technology transfer to Korea. The Korea Institute of Nuclear Safety (KINS) was established in 1990 as an independent regulatory expert organization. 1 tab., 4 figs.

  7. 76 FR 13972 - United States Warehouse Act; Export Food Aid Commodities Licensing Agreement

    Science.gov (United States)

    2011-03-15

    ..., nuts, cottonseed, and dry beans. Warehouse operators that apply voluntarily agree to be licensed... program for port and transload facility operators storing EFAC. This proposal is in response to the...

  8. Licensing of ANSTO's Replacement Research Reactor

    International Nuclear Information System (INIS)

    Summerfield, M.W.; Garea, V.

    2003-01-01

    This paper presents a general description of the licensing of the 20 MW Pool-type Replacement Research Reactor (RRR) currently being built by the Australian Nuclear Science and Technology Organisation (ANSTO) at their Lucas Heights site. The following aspects will be addressed: 1) The influence of ARPANSA's (the Australian regulator) Regulatory Assessment Principles and Design Criteria on the design of the RRR. 2) The Site Licence Application, including the EIS and the supporting siting documentation. 3) The Construction Licence Application, including the PSAR and associated documentation. 4) The review process, including the IAEA Peer Review and the Public Submissions as well as ARPANSA's own review. 5) The interface between ANSTO, INVAP and ARPANSA in relation to the ongoing compliance with ARPANS Regulation 51 and 54. 6) The future Operating Licence Application, including the draft FSAR and associated documentation. These aspects are all addressed from the point of view of the licensee ANSTO and the RRR Project. Particular emphasis will be given to the way in which the licensing process is integrated into the overall project program and how the licensing and regulatory regime within Australia influenced the design of the RRR. In particular, the safety design features that have been incorporated as a result of the specific requirements of ANSTO and the Australian regulator will be briefly described. The paper will close with a description of how the RRR meets, and in many aspects exceeds the requirements of ANSTO and the Australian regulator. (author)

  9. How should a legal system of approval adequate to democracy look like. Nuclear power station licensing for example

    International Nuclear Information System (INIS)

    Rossnagel, A.

    1986-01-01

    The concept of an administrative referendum is explained as a possibility of reshaping the current system of approval so as to make it commensurate with democratic principles. Introduction of such a concept would require only few modifications of the valid legal provisions: The licensing procedure would remain as it is, but in addition, a referendum would be made possible, on the initiative of the population, which would give the population of a Federal Land a right of decision on the political level, deciding whether a given, licensed installation is conductive to the public good. Through such an administrative referendum, the political sovereign would be given political power of control of administrative decisions, and assume responsibility, which would be legally based on Art. 20, para. II GG (Basic Law). (HSCH) [de

  10. Establishing a safety and licensing basis for generation IV advanced reactors. License by test

    International Nuclear Information System (INIS)

    Kadak, Andrew C.

    2001-01-01

    The license by test approach to licensing is a novel method of licensing reactors. It provides an opportunity to deal with innovative non-water reactors in a direct way on a time scale that could permit early certification based on tests of a demonstration reactor. The uncertainties in the design and significant contributors to risk would be identified in the PRA during the design. Deterministic analysis computer codes could be tested on a real reactor. Scaling effects and associated uncertainties would be minimized. License by test is an approach that has sufficient merit to be developed and tested

  11. 22 CFR 96.30 - State licensing.

    Science.gov (United States)

    2010-04-01

    ... Licensing and Corporate Governance § 96.30 State licensing. (a) The agency or person is properly licensed or... person follows applicable State licensing and regulatory requirements in all jurisdictions in which it provides adoption services. (c) If it provides adoption services in a State in which it is not itself...

  12. Selection, training, qualification and licensing of Three Mile Island reactor operating personnel

    International Nuclear Information System (INIS)

    Eytchison, R.M.

    1980-01-01

    The various programs which were intended to staff Three Mile Island with competent, trained operators and supervisors are reviewed. The analysis includes a review of the regulations concerning operator training and licensing, and describes how the requirements were implemented by the NRC, Metropolitan Edison Company, and Babcock and Wilcox Company. Finally the programs conducted by these three organisations are evaluated. (U.K.)

  13. Licensing assessment of the CANDU pressurized heavy water reactor. Volume I. Preliminary safety information document

    International Nuclear Information System (INIS)

    1977-06-01

    The PHWR design contains certain features that will require significant modifications to comply with USNRC siting and safety requirements. The most significant of these features are the reactor vessel; control systems; quality assurance program requirements; seismic design of structures, systems and components; and providing an inservice inspection program capability. None of these areas appear insolvable with current state-of-the-art engineering or with upgrading of the quality assurance program for components constructed outside of the USA. In order to be licensed in the U. S., the entire reactor assembly would have to be redesigned to comply with ASME Boiler and Pressure Vessel Code, Section III, Division 1 and Division 2. A summary matrix at the end of this volume identifies compliance of the systems and structures of the PHWR plant with the USNRC General Design Criteria. The matrix further identifies the estimated incremental cost to a 600 MWe PHWR that would be required to license the plant in the U. S. Further, the matrix identifies whether or not the incremental licensing cost is size dependent and the relative percentage of the base direct cost of a Canadian sited plant

  14. Licensing in an International Market

    Science.gov (United States)

    Ferreira, Fernanda A.

    2008-09-01

    We study the effects of entry of a foreign firm on domestic welfare in the presence of licensing, when the entrant is technologically superior to the incumbent. We show that foreign entry increases domestic welfare for sufficiently large technological differences between the firms under both fixed-fee licensing and royalty licensing.

  15. 22 CFR 120.20 - License.

    Science.gov (United States)

    2010-04-01

    ... 22 Foreign Relations 1 2010-04-01 2010-04-01 false License. 120.20 Section 120.20 Foreign Relations DEPARTMENT OF STATE INTERNATIONAL TRAFFIC IN ARMS REGULATIONS PURPOSE AND DEFINITIONS § 120.20 License. License means a document bearing the word “license” issued by the Directorate of Defense Trade...

  16. License renewal of the HFR research reactor - A regulatory view

    International Nuclear Information System (INIS)

    Van der Plas, Y.

    2006-01-01

    Full text: Regulatory policy in The Netherlands is having safety evaluations of a nuclear installation each ten year. Recently a periodic safety evaluation has been finished on the 45 MW High Flux Reactor (HFR) in Petten divided over the following main topics: Risk Scoping Study; HEU-LEU fuel conversion; Evaluation against a pre-defined Reference Licensing Basis; Ageing study. The Risk Scoping Study is a limited probabilistic safety assessment showing scenarios towards serious core degradation and their probabilities. Individual risks for members of the public induced by the incidents analyzed in the first phase are compared with the mortality limits and probabilistic doses limits of the national BKSE decree. For non- proliferation reasons the fuel is converted from high to low enriched uranium. Before starting the project a reference licensing basis (RLB) was defined. A list of postulated initiating events (PIEs), re-establishing a design basis has been approved. An ageing management system shall provide information on the actual status and the residual life time of the plant. The evaluation results into a list of deficiencies, recommendations and suggestions from which modifications are to be proposed. Examples are: more redundancy and separation within the reactor protection system; renewal of the emergency and decay heat cooling; addition of a secundary reactor shut down system; more redundancy in the electric power supply; addition of injection valves introducing efficient use of passive cooling inventor) under LOCA conditions; damping of the impact from loads accidentally falling into the pool. A new nuclear license was issued begin 2004, covering all modifications which are to be implemented ultimate end 2007

  17. 48 CFR 227.7203-4 - License rights.

    Science.gov (United States)

    2010-10-01

    ... Software and Computer Software Documentation 227.7203-4 License rights. (a) Grant of license. The... license, under an irrevocable license granted or obtained by the contractor which developed the software... granted to the Government. The scope of a computer software license is generally determined by the source...

  18. Current status of construction license of PEFP

    International Nuclear Information System (INIS)

    Kim, J. Y.; Cho, J. S.; Min, Y. S.; Nam, J. M.; Jeon, G. P.; Park, S. S.; Jo, J. H.; Song, I. T.

    2012-01-01

    Since 2010 August, PEFP(Proton Engineering Frontier Project)'s Proton Accelerator Research Center has been under construction so far. Generally, in advance of construction startup, many kinds of licenses should be acquired along with the types of construction works. To acquire a license in time, each item should meet the standard by the related regulation, including not only procedural but also content aspect. In the advent of internet era, electronic government system has been adopted in many governmental functions: So is the national construction license acquisition system. Owing to the system, both approval and documentation functions in licensing are integrated in online computer network which provide us simplification in process and easy accessibility to license data. However, aside from these construction licenses, other types of licenses still remain separately managed: Machinery, electric facilities, and so on. Moreover, all the licenses have the priority order and take legal term in processing. So, to avoid any time delay in license acquisition, we organized license hierarchy and found out the priority among them. Thereafter, according to their legal term in approval and acquisition, whole license acquisition schedule was arranged and we completed all the necessary licenses acquisition in time In this study, we summarize the current status of license acquisition on Proton Accelerator Research Center Construction, and manifest how they have been and will be managed systematically

  19. Current status of construction license of PEFP

    Energy Technology Data Exchange (ETDEWEB)

    Kim, J. Y.; Cho, J. S.; Min, Y. S.; Nam, J. M.; Jeon, G. P.; Park, S. S.; Jo, J. H.; Song, I. T. [KAERI, Daejeon (Korea, Republic of)

    2012-10-15

    Since 2010 August, PEFP(Proton Engineering Frontier Project)'s Proton Accelerator Research Center has been under construction so far. Generally, in advance of construction startup, many kinds of licenses should be acquired along with the types of construction works. To acquire a license in time, each item should meet the standard by the related regulation, including not only procedural but also content aspect. In the advent of internet era, electronic government system has been adopted in many governmental functions: So is the national construction license acquisition system. Owing to the system, both approval and documentation functions in licensing are integrated in online computer network which provide us simplification in process and easy accessibility to license data. However, aside from these construction licenses, other types of licenses still remain separately managed: Machinery, electric facilities, and so on. Moreover, all the licenses have the priority order and take legal term in processing. So, to avoid any time delay in license acquisition, we organized license hierarchy and found out the priority among them. Thereafter, according to their legal term in approval and acquisition, whole license acquisition schedule was arranged and we completed all the necessary licenses acquisition in time In this study, we summarize the current status of license acquisition on Proton Accelerator Research Center Construction, and manifest how they have been and will be managed systematically.

  20. Technology Licensing and Firm Innovation

    DEFF Research Database (Denmark)

    Moreira, Solon

    acquisition. The findings indicate that technology licensing is positively related to the number of inventions produced by the licensee in the years subsequent to the licensing deal. Subsequently, I investigate the moderating effect that organizational slack and myopia have on this main relationship....... The findings also suggest that high levels of Organizational Slack (available financial resources) strengthen the positive effect of licensing on innovation. However, higher levels of Organizational Myopia (the extent to which a firm draws on its own knowledge) can decrease the main effect of licensing....

  1. 31 CFR 596.309 - Specific license.

    Science.gov (United States)

    2010-07-01

    ... FOREIGN ASSETS CONTROL, DEPARTMENT OF THE TREASURY TERRORISM LIST GOVERNMENTS SANCTIONS REGULATIONS General Definitions § 596.309 Specific license. The term specific license means any license or...

  2. Environmental assessment for final rule on nuclear power plant license renewal

    International Nuclear Information System (INIS)

    1991-12-01

    The Atomic Energy Act and Nuclear Regulatory Commission (NRC) regulations provide for the renewal of nuclear power plant operating licenses beyond their initial 40-year term. The Act and NRC regulations, however, do not specify the procedures, criteria, and standards that must be satisfied in order to renew a license. The NRC is promulgating a rule (10 CFR Part 54) to codify such requirements prior to the receipt of applications for license renewal. The NRC has assessed the possible environmental effects of promulgating requirements in 10 CFR Part 54 now rather than employing such requirements in an ad hoc manner in individual licensing actions. The final part 54 rule requires the development of information and analyses to identify aging problems of systems, structures, and components unique to license renewal that will be of concern during the period of extended operation and will not be controlled by existing effective programs. In general, licensee activities for license renewal may involve replacement, refurbishment, inspection, testing, or monitoring. Such actions will be generally be within the range of similar actions taken for plants during the initial operating term. These actions would be primarily confined within the plants with potential for only minor disruption to the environment. It is unlikely that these actions would change the operating conditions of plants in ways that would change the environmental effects already being experienced. Relicensing under existing regulations would also be primarily focused on aging degradation and would likely result in requirements similar to those that will result from relicensing under the final rule

  3. 31 CFR 596.305 - General license.

    Science.gov (United States)

    2010-07-01

    ... FOREIGN ASSETS CONTROL, DEPARTMENT OF THE TREASURY TERRORISM LIST GOVERNMENTS SANCTIONS REGULATIONS General Definitions § 596.305 General license. The term general license means any license or authorization...

  4. Establishment of the nuclear regulatory framework for the process of decommissioning of nuclear installations in Mexico; Establecimiento del marco regulador nuclear para el proceso de cierre de instalaciones nucleares en Mexico

    Energy Technology Data Exchange (ETDEWEB)

    Salmeron V, J. A.; Camargo C, R.; Nunez C, A., E-mail: juan.salmeron@cnsns.gob.mx [Comision Nacional de Seguridad Nuclear y Salvaguardias, Dr. Barragan 779, Col. Narvarte, 03020 Ciudad de Mexico (Mexico)

    2015-09-15

    Today has not managed any process of decommissioning of nuclear installations in the country; however because of the importance of the subject and the actions to be taken to long term, the Comision Nacional de Seguridad Nuclear y Salvaguardias (CNSNS) in Mexico, accordance with its objectives is developing a National Nuclear Regulatory Framework and defined requirements to ensure the implementation of appropriate safety standards when such activities are performed. In this regard, the national nuclear regulatory framework for nuclear installations and the particular case of nuclear power reactors is presented, as well as a proposed licensing process for the nuclear power plant of Laguna Verde based on international regulations and origin country regulations of the existing reactors in nuclear facilities in accordance with the license conditions of operation to allow to define and incorporate such regulation. (Author)

  5. Evaluation guideline for the study of the radiological impact of based nuclear installations (INB) presented in support of releases authorization demands; Guide d'examen pour l'etude de l'impact radiologique d'une installation nucleaire de base (INB) fournie a l'appui des demandes d'autorisation de rejets

    Energy Technology Data Exchange (ETDEWEB)

    Chartier, M.; Despres, A.; Supervil, S.; Conte, D.; Hubert, P.; Oudiz, A.; Champion, D

    2002-10-01

    In the case of a license demand for the effluents release and water taking for a nuclear installation, the operating must realize a study of the nuclear effluents radiological impact on the environment and the public health. In this context, the study presents technical and methodological specifications which led the Direction of the Nuclear Installations Safety (DSIN) and the General Direction of the Health (DGS) to ask the IPSN the elaboration of a guideline to help these studies evaluation. The guideline presents the regulatory context, the description of the installations, the treatment and the control processes, the rules of management, the description of the environment, the estimation of the radiological impacts and the environment control system definition. (A.L.B.)

  6. Problems raised by participation of foreign citizens in national licensing procedures - aspects of public international law

    International Nuclear Information System (INIS)

    Pelzer, N.

    1983-01-01

    In western Europe persons living in border areas increasingly ask for participation in national licensing procedures for nuclear installations to be erected close to the border in neighbouring countries. National practices vary in this matter. Whilst many countries concede rights of participation to foreign citizens in the border areas, the Federal Republic of Germany, e.g., denies foreign citizens direct participation. The paper enquires into the connected problems of public international law and pertinent international treaties and international customary low are examined. (NEA) [fr

  7. Licensing an assured isolation facility for low-level radioactive waste. Volume 1: Licensing strategy and issues

    International Nuclear Information System (INIS)

    Silverman, D.J.; Bauser, M.A.; Baird, R.D.

    1998-07-01

    This report provides a detailed set of proposed criteria and guidance for the preparation of a license application for an assured isolation facility (AIF). The report is intended to provide a detailed planning basis upon which a prospective applicant may begin pre-licensing discussions with the Nuclear Regulatory Commission and initiate development of a license application. The report may also be useful to the NRC or to state regulatory agencies that may be asked to review such an application. Volume 1 of this report provides background information, and describes the licensing approach and methodology. Volume 2 identifies specific information that is recommended for inclusion in a license application

  8. The role of effective communications in Nuclear Regulatory Commission licensing

    International Nuclear Information System (INIS)

    Counsil, W.G.

    1991-01-01

    Communications are essential to the licensing and general regulatory program of the Nuclear Regulatory Commission. This paper attempts to identify and address certain aspects of, and approaches to, maintaining effective and efficient communications. It considers, from the perspective of the high-level radioactive waste repository program, both internal communication within the DOE itself and external communication with the Nuclear Regulatory Commission and interested parties. Many of the points presented are based on lessons learned from electric utility experience with nuclear plants

  9. Analysis of corrective action data from trial program on programmatic performance indicators

    International Nuclear Information System (INIS)

    Mays, G.T.; Poore, W.P.

    1989-01-01

    The Nuclear Regulatory Commission (NRC) is considering the use of cause codes as performance indicators (PIs) to monitor licensee performance. In conjunction with the cause codes, corrective action codes are also under consideration to describe licensee corrective actions for problems as represented by the cause codes. The set of cause codes and corrective actions employed in a trial program to assess their usefulness included: (1) administrative error -- training; (2) design/installation -- procedure modification; (3) fabrication error -- discipline; (4) random equipment failure -- management change; (5) licensed operator error -- design modification; and (6) other personal error -- equipment replacement/adjustment. These causes were selected to represent a broad range of licensee programs, hence the designation of programmatic PIs, that could be monitored in a systematic manner to identify trends in performance. They should establish a basis and focus for further investigation of a particular programmatic area if undesirable trends are evidence. 2 figs

  10. Licensing aspects regarding the RBMN project

    International Nuclear Information System (INIS)

    Cuccia, Valeria; Sacramento, Arivaldo M.; Aleixo, Bruna L.; Ferreira, Vinicius V.M.

    2013-01-01

    The licensing process of a waste disposal facility is a complex and demanding undertaking. It proceeds in phases, starting with the site selection and ending many decades later, when the radionuclides decayed and no longer offer possible hazard. That is one of the reasons why the licensing process for the Brazilian repository for low and intermediate level radioactive waste (RBMN Project) is a challenge for all the technicians involved. Besides that, the only national experience associated to this subject arose after a radiological accident in the State of Goias, in 1987. Two different institutions are involved in this licensing process: IBAMA, for environmental licensing, and CNEN, for nuclear licensing. Both of them will evaluate the possible impacts caused by the waste disposal, so it is essential to avoid conflicts and duplications of activities. The RBMN project has different teams for each main activity, and one of them is the Licensing group. This team has been planning the licensing activities for the repository, studying the legal framework and estimating costs and execution time for each step. This paper presents the status of the licensing activities regarding to the RBMN project done by the CNEN staff. (author)

  11. Managing Licensing in a Market for Technology

    DEFF Research Database (Denmark)

    Arora, Ashish; Rønde, Thomas; Fosfuri, Andrea

    the technology makes licensing decisions—to centralized licensing. The business unit has superior information about licensing opportunities but may not have the appropriate incentives because its rewards depend upon product market performance. If licensing is decentralized, the business unit forgoes valuable...... licensing opportunities since the rewards for licensing are (optimally) weaker than those for product market profits. This distortion is stronger when production-based incentives are more powerful, making centralization more attractive. Growth of technology markets favors centralization and drives higher...

  12. Installation and validation of MCNP-4A

    International Nuclear Information System (INIS)

    Marks, N.A.

    1997-01-01

    MCNP-4A is a multi-purpose Monte Carlo program suitable for the modelling of neutron, photon, and electron transport problems. It is a particularly useful technique when studying systems containing irregular shapes. MCNP has been developed over the last 25 years by Los Alamos, and is distributed internationally via RSIC at Oak Ridge. This document describes the installation of MCNP-4A (henceforth referred to as MCNP) on the Silicon Graphics workstation (bluey.ansto.gov.au). A limited number of benchmarks pertaining to fast and thermal systems were performed to check the installation and validate the code. The results are compared to deterministic calculations performed using the AUS neutronics code system developed at ANSTO. (author)

  13. Idaho National Engineering Laboratory installation roadmap document

    International Nuclear Information System (INIS)

    1993-01-01

    The roadmapping process was initiated by the US Department of Energy's office of Environmental Restoration and Waste Management (EM) to improve its Five-Year Plan and budget allocation process. Roadmap documents will provide the technical baseline for this planning process and help EM develop more effective strategies and program plans for achieving its long-term goals. This document is a composite of roadmap assumptions and issues developed for the Idaho National Engineering Laboratory (INEL) by US Department of Energy Idaho Field Office and subcontractor personnel. The installation roadmap discusses activities, issues, and installation commitments that affect waste management and environmental restoration activities at the INEL. The High-Level Waste, Land Disposal Restriction, and Environmental Restoration Roadmaps are also included

  14. MEX04/058 supporting the license renewal of the LVNPP

    International Nuclear Information System (INIS)

    Diaz, A.; Arganis, C.; Viais, J.; Mendoza, G.; Lucatero, M. A.; Contreras, A.

    2010-10-01

    Nuclear power plants in the United States are authorized to operate for 40 years. However, this 40-year period was chosen based on economic considerations and not on technological restrictions or safety aspects. In general, the operation of equipment, systems and components in a nuclear power plant is subject to rigorous maintenance and inspection monitoring under strict surveillance programs throughout their life. In fact, according to the Nuclear Energy Institute, in December 2009, 59 nuclear power plants in the United States had already reached the 40 years of the original operating license and carried out their renewal process, extending their operation for up to 20 more years. These 59 nuclear power plants carried out their renewal process, basing their operation mainly on safety reviews that validated the good working order of systems, structures and components, meeting the technical specifications required, as well as complying with the specific safety provisions for prolonging the use of a operating license. The owner is responsible for showing the Regulatory Agency that it is capable of effectively managing the aging of the systems, structures and components,guaranteeing their good working order during the renewal period. In the specific case of Mexico, Unit 1 of the Laguna Verde Nuclear Power Plant (LVNPP) has an original 30-year license, with almost 20 years of proper operation, for which, in order to request a license extension, it is necessary to begin management activities, which allow for constituting and submitting the license renewal application to the Regulatory Agency in order to continue its commercial operation. This paper presents some of most important activities carried out by Instituto Nacional de Investigaciones Nucleares and LVNPP in the international project MEX04/058, related to Plant Life Management as a support of the beginning of plant license renewal process. (Author)

  15. Status of environmental response efforts at radioactively contaminated sites in the united states air force installation restoration program

    International Nuclear Information System (INIS)

    Rowe, W.D. Jr.; McEntee, T.E. Jr.; Johnson, B.; Manning, L.

    1995-01-01

    The United States Air Force has identified approximately 170 radioactively contaminated sites at its domestic installations. These sites contain a variety of low level radioactive and mixed wastes and are classified as burial sites, landfills, buildings, and other disposal sites. Of these 170, approximately 70 are presently being evaluated under the Air Force Installation Restoration Program (IRP) in accordance with applicable laws and regulations. Removal and/or remedial actions have been taken at specific sites using site-specific residual radioactivity criteria. The remaining sites are either under investigation to determine the need for possible action or have been classified as response complete based on restricted or unrestricted future use. This paper describes past Air Force operations that generated radioactive waste materials; examines the current inventory of resulting radioactively contaminated sites in the Air Force IRP; reviews criteria used to evaluate sites for removal and/or remedial actions; provides summary information on actions taken at sites; and focuses on response actions and cleanup levels at two completed sites. The paper concludes with an assessment of outstanding issues relevant to the remediation of radioactively contaminated sites. (author)

  16. The Texas A&M Radioisotope Production and Radiochemistry Program

    International Nuclear Information System (INIS)

    Akabani, Gamal

    2016-01-01

    The main motivation of the project at Texas A&M University was to carry out the production of critically needed radioisotopes used in medicine for diagnostics and therapy, and to establish an academic program in radionuclide production and separation methods. After a lengthy battle with the Texas A&M University Radiation Safety Office, the Texas Department of State Health Services granted us a license for the production of radionuclides in July 2015, allowing us to work in earnest in our project objectives. Experiments began immediately after licensing, and we started the assembly and testing of our target systems. There were four analytical/theoretical projects and two experimental target systems. These were for At-211 production and for Zn-62/Cu-62 production. The theoretical projects were related to the production of Mo-99/Tc-99m using a) a subcritical aqueous target system and b) production of Tc-99m from accelerator-generated Mo-99 utilizing a photon-neutron interaction with enriched Mo-100 targets. The two experimental projects were the development of targetry systems and production of At-211 and Zn-62/Cu-62 generator. The targetry system for At-211 has been tested and production of At-211 is chronic depending of availability of beam time at the cyclotron. The installation and testing of the targetry system for the production of Zn-62/Cu-62 has not been finalized. A description of the systems is described. The academic program in radionuclide production and separation methods was initiated in the fall of 2011 and, due to the lack of a radiochemistry laboratory, it was suspended. We expect to re-start the academic program at the Texas A&M Institute for Preclinical Studies under the Molecular Imaging Program.

  17. The Texas A&M Radioisotope Production and Radiochemistry Program

    Energy Technology Data Exchange (ETDEWEB)

    Akabani, Gamal [Texas A & M Univ., College Station, TX (United States)

    2016-08-31

    The main motivation of the project at Texas A&M University was to carry out the production of critically needed radioisotopes used in medicine for diagnostic and therapy, and to establish an academic program in radionuclide production and separation methods. After a lengthy battle with the Texas A&M University Radiation Safety Office, the Texas Department of State Health Services granted us a license for the production of radionuclides in July 2015, allowing us to work in earnest in our project objectives. Experiments began immediately after licensing, and we started the assembly and testing of our target systems. There were four analytical/theoretical projects and two experimental target systems. These were for At-211 production and for Zn- 62/Cu-62 production. The theoretical projects were related to the production of Mo-99/Tc-99m using (a) a subcritical aqueous target system and (b) production of Tc-99m from accelerator-generated Mo-99 utilizing a photon-neutron interaction with enriched Mo-100 targets. The two experimental projects were the development of targetry systems and production of At-211 and Zn-62/Cu-62 generator. The targetry system for At-211 has been tested and production of At-211 is chronic depending of availability of beam time at the cyclotron. The installation and testing of the targetry system for the production of Zn-62/Cu-62 has not been finalized. A description of the systems is described. The academic program in radionuclide production and separation methods was initiated in the fall of 2011; due to the lack of a radiochemistry laboratory, it was suspended. We expect to re-start the academic program at the Texas A&M Institute for Preclinical Studies under the Molecular Imaging Program.

  18. The Texas A&M Radioisotope Production and Radiochemistry Program

    International Nuclear Information System (INIS)

    Akabani, Gamal

    2016-01-01

    The main motivation of the project at Texas A&M University was to carry out the production of critically needed radioisotopes used in medicine for diagnostic and therapy, and to establish an academic program in radionuclide production and separation methods. After a lengthy battle with the Texas A&M University Radiation Safety Office, the Texas Department of State Health Services granted us a license for the production of radionuclides in July 2015, allowing us to work in earnest in our project objectives. Experiments began immediately after licensing, and we started the assembly and testing of our target systems. There were four analytical/theoretical projects and two experimental target systems. These were for At-211 production and for Zn- 62/Cu-62 production. The theoretical projects were related to the production of Mo-99/Tc-99m using (a) a subcritical aqueous target system and (b) production of Tc-99m from accelerator-generated Mo-99 utilizing a photon-neutron interaction with enriched Mo-100 targets. The two experimental projects were the development of targetry systems and production of At-211 and Zn-62/Cu-62 generator. The targetry system for At-211 has been tested and production of At-211 is chronic depending of availability of beam time at the cyclotron. The installation and testing of the targetry system for the production of Zn-62/Cu-62 has not been finalized. A description of the systems is described. The academic program in radionuclide production and separation methods was initiated in the fall of 2011; due to the lack of a radiochemistry laboratory, it was suspended. We expect to re-start the academic program at the Texas A&M Institute for Preclinical Studies under the Molecular Imaging Program.

  19. The Texas A&M Radioisotope Production and Radiochemistry Program

    Energy Technology Data Exchange (ETDEWEB)

    Akabani, Gamal [Texas A & M Univ., College Station, TX (United States). Dept. of Nuclear Engineering. Dept. of Veterinary Integrative Biosciences

    2016-10-28

    The main motivation of the project at Texas A&M University was to carry out the production of critically needed radioisotopes used in medicine for diagnostics and therapy, and to establish an academic program in radionuclide production and separation methods. After a lengthy battle with the Texas A&M University Radiation Safety Office, the Texas Department of State Health Services granted us a license for the production of radionuclides in July 2015, allowing us to work in earnest in our project objectives. Experiments began immediately after licensing, and we started the assembly and testing of our target systems. There were four analytical/theoretical projects and two experimental target systems. These were for At-211 production and for Zn-62/Cu-62 production. The theoretical projects were related to the production of Mo-99/Tc-99m using a) a subcritical aqueous target system and b) production of Tc-99m from accelerator-generated Mo-99 utilizing a photon-neutron interaction with enriched Mo-100 targets. The two experimental projects were the development of targetry systems and production of At-211 and Zn-62/Cu-62 generator. The targetry system for At-211 has been tested and production of At-211 is chronic depending of availability of beam time at the cyclotron. The installation and testing of the targetry system for the production of Zn-62/Cu-62 has not been finalized. A description of the systems is described. The academic program in radionuclide production and separation methods was initiated in the fall of 2011 and, due to the lack of a radiochemistry laboratory, it was suspended. We expect to re-start the academic program at the Texas A&M Institute for Preclinical Studies under the Molecular Imaging Program.

  20. Application of up-front licensing

    Energy Technology Data Exchange (ETDEWEB)

    Grant, S D [Atomic Energy of Canada Ltd., Saskatoon, SK (Canada); Snell, V G [Atomic Energy of Canada Ltd., Mississauga, ON (Canada)

    1996-12-31

    AECL has been pioneering `up-front` licensing of new reactor designs. The CANDU 3 design has been formally reviewed by AECB staff for a number of years. The CANDU 9 design has just started the up-front licensing process. The process gives designers, regulators and potential customers early confidence in the licensability of future plants. (author). 4 refs., 2 tabs.

  1. Application of up-front licensing

    International Nuclear Information System (INIS)

    Grant, S.D.; Snell, V.G.

    1995-01-01

    AECL has been pioneering 'up-front' licensing of new reactor designs. The CANDU 3 design has been formally reviewed by AECB staff for a number of years. The CANDU 9 design has just started the up-front licensing process. The process gives designers, regulators and potential customers early confidence in the licensability of future plants. (author). 4 refs., 2 tabs

  2. Regulatory systems-based licensing guidance documentation

    International Nuclear Information System (INIS)

    Delligatti, M.S.

    1991-01-01

    The US Nuclear Regulatory Commission (NRC) has developed a series of licensing guidance documents based on the regulatory requirements in Part 60 of Title 10 of the Code of Federal Regulations (10 CFR Part 60). This regulatory systems-based approach to licensing guidance documentation relies on the definition of the high-level waste repository in 10 CFR Part 60. A document which is important for the frame-work it gives to other programmatic licensing guidance is the Draft Regulatory Guide open-quotes Format and Content for the License Application for the High-Level Waste Repositoryclose quotes (FCRG). The FCRG describes a format and content acceptable to NRC for a high-level waste repository license application pursuant to the requirements of 10 CFR Part 60. Other licensing guidance documents will be compatible with the FCRG

  3. Installation report - Lidar

    DEFF Research Database (Denmark)

    Georgieva Yankova, Ginka; Villanueva, Héctor

    The report describes the installation, configuration and data transfer for the ground-based lidar. The unit is provided by a customer but is installed and operated by DTU while in this project.......The report describes the installation, configuration and data transfer for the ground-based lidar. The unit is provided by a customer but is installed and operated by DTU while in this project....

  4. Risk-assessment techniques and the reactor licensing process

    International Nuclear Information System (INIS)

    Levine, S.

    1979-01-01

    A brief description of the Reactor Safety Study (WASH-1400), concentrating on the engineering aspects of the contribution to reactor accident risks is followed by some comments on how we have applied the insights and techniques developed in this study to prepare a program to improve the safety of nuclear power plants. Some new work we are just beginning on the application of risk-assessment techniques to stablize the reactor licensing process is also discussed

  5. Preliminary assessment report for Army Aviation Support Facility No. 3, Installation 13307, Hunter Army Airfield, Savannah, Georgia. Installation Restoration Program

    Energy Technology Data Exchange (ETDEWEB)

    Kolpa, R.; Smith, K.

    1993-07-01

    This report presents the results of the preliminary assessment (PA) conducted by Argonne National Laboratory at the Georgia Army National Guard property located on Hunter Army Airfield (HAA) near Savannah, Georgia, known as Army Aviation Support Facility (AASF) No. 3. Preliminary assessments of federal facilities are being conducted to compile the information necessary for completing preremedial activities and to provide a basis for establishing corrective actions in response to releases of hazardous substances. The principal objective of the PA is to characterize the site accurately and determine the need for further action by examining site activities, types and quantities of hazardous substances utilized, the nature and amounts of wastes generated or stored at the facility, and potential pathways by which contamination could affect public health and the environment. This PA satisfies, for the AASF No. 3 property, requirements of the Department of Defense Installation Restoration Program (IRP). The scope of this assessment is limited to the facilities and past activities contained within the area now occupied by AASF No. 3. However, this assessment report is intended to be read in conjunction with a previous IRP assessment of HAA completed in 1992 (USATHAMA 1992) and to provide comprehensive information on AASF No. 3 for incorporation with information contained in that previous assessment for the entirety of HAA.

  6. Function and set up of public participation in the nuclear licensing procedure

    International Nuclear Information System (INIS)

    Wiedemann, H.

    1977-01-01

    From the point of view of the public utilities, the participation of the public in the nuclear licensing procedure, in the site provision procedure, in constructional planning, and as a joint action brought pursuant to the new 'Nuclear Installations Ordinance' (AtVfO) is discussed. In this context, it is emphasized, that a change, via possibilities existing de lege lator, is not necessary if government and administration are willing to achieve the objectives given by the legislator on the basis of the existing instrumentarium. The target they have to achieve is the enforcing 'general public interest', which has been declared as binding in law and in programmes of the government based on these laws. (HP) [de

  7. The intelligent customer: considerations around build-own-operate business and licensing models for small modular reactors in Canada

    International Nuclear Information System (INIS)

    Jones, K.

    2014-01-01

    An organization planning a proposal for a build-own-operate business model needs to address expanded licensee responsibilities under this model, associated regulatory impacts and how this affects their role as an 'intelligent customer'. This is particularly important for cases where builder-owner-operators plan to manufacture factory-fuelled designs and ship them to a site for installation and operation. The primary responsibility for safe conduct of licensed activities rests with the licensee. A build-own-operate model expands the scope of licensed activities to include design, manufacturing, transport, construction, and operation. The licensee must be able to demonstrate they are qualified to conduct all licensed activities including sufficient competent resources within the licensee's organization to oversee('Intelligent Customer') any work it commissions externally and the subsequent flow down through of the supply chain. This paper examines aspects that organizations need to assess the suitability of approaches that it may take to maintain in-house expertise for the control and oversight of licensed activities at all times. It considers the approach to identification of: core capabilities the licensee would need to understand its safety case under a build-own-operate model to manage licensed activities in accordance with requirements under the Nuclear Safety and Control Acta licensee's 'intelligent customer' capabilities in particular around understanding, specifying, overseeing and accepting work undertaken on its behalf by contractors. While this paper is focused on small modular reactors, being an intelligent customer applies to large commercial or research reactors equally; the size of reactor is immaterial.

  8. The intelligent customer: considerations around build-own-operate business and licensing models for small modular reactors in Canada

    Energy Technology Data Exchange (ETDEWEB)

    Jones, K., E-mail: kenneth.jones@cnsc-ccsn.gc.ca [Canadian Nuclear Safety Commission, Ottawa, Ontario (Canada)

    2014-07-01

    An organization planning a proposal for a build-own-operate business model needs to address expanded licensee responsibilities under this model, associated regulatory impacts and how this affects their role as an 'intelligent customer'. This is particularly important for cases where builder-owner-operators plan to manufacture factory-fuelled designs and ship them to a site for installation and operation. The primary responsibility for safe conduct of licensed activities rests with the licensee. A build-own-operate model expands the scope of licensed activities to include design, manufacturing, transport, construction, and operation. The licensee must be able to demonstrate they are qualified to conduct all licensed activities including sufficient competent resources within the licensee's organization to oversee('Intelligent Customer') any work it commissions externally and the subsequent flow down through of the supply chain. This paper examines aspects that organizations need to assess the suitability of approaches that it may take to maintain in-house expertise for the control and oversight of licensed activities at all times. It considers the approach to identification of: core capabilities the licensee would need to understand its safety case under a build-own-operate model to manage licensed activities in accordance with requirements under the Nuclear Safety and Control Acta licensee's 'intelligent customer' capabilities in particular around understanding, specifying, overseeing and accepting work undertaken on its behalf by contractors. While this paper is focused on small modular reactors, being an intelligent customer applies to large commercial or research reactors equally; the size of reactor is immaterial.

  9. Free Software Licenses and Other Free Licenses: Genetic Code of Digital Common Goods

    OpenAIRE

    Marco Ciurcina

    2017-01-01

    This article explores the history and describes the main features of free software licenses and other free licenses in an attempt to shed light on the reasons for their success in promoting individual behaviors converging towards the collective construction of digital commons.

  10. Managing Licensing in a Market for Technology

    DEFF Research Database (Denmark)

    Arora, Ashish; Fosfuri, Andrea; Rønde, Thomas

    2013-01-01

    , we find that interdependency across business units may result in more, not less, decentralization. Furthermore, even though centralization results in less information, centralized licensing deals are larger. Our model conforms to the existing evidence that reports heterogeneity across firms in both......Technology licensing is an important means for companies to extract more value from their intellectual assets. We build a model that helps understand how licensing activity should be organized within large corporations. More specifically, we compare decentralization—where the business unit using...... the technology makes licensing decisions—to centralized licensing. The business unit has superior information about licensing opportunities but may not have the appropriate incentives because its rewards depend on product market performance. If licensing is decentralized, the business unit forgoes valuable...

  11. Information Management: Military Affiliate Radio System (MARS)

    National Research Council Canada - National Science Library

    1986-01-01

    .... It describes a program sponsored by the Department of Defense and supported by the Department of the Army in which military installations, military units, clubs, and volunteer licensed amateur radio...

  12. Nuclear power plant attempts in Turkey and the first licensed site

    International Nuclear Information System (INIS)

    Bektur, Y.; Bezdegumeli, U.

    2004-01-01

    Turkey is currently in a rapid industrialization process with a young population of 71 million. Electricity is an inevitable need for Turkey as a fast developing country. Turkey's average annual growth rates of electricity consumption have been 8% in the last two decades. The installed electricity generating capacity of Turkey reached 36 GW; the annual gross power generation was 140 TWh (23% lignite and coal, 44% natural gas, 25% hydro and 8% others); and the annual gross per capita consumption of electricity was around 2.000 kWh as of end-2003. According to forecasts prepared by the Ministry of Energy and Natural Resources (MENR), Turkey will need about 60 GW of capacity by 2010, and about 100 GW by 2020. This implies power demand growth rates of at least 8% per annum for the coming decade and at least 6% per annum for the following decade. This means that there is a need for rapid build-up of 3 GW new capacities per year for at least several years. Turkey's experience with nuclear power dates back to the 1960s - a research reactor has been operating in Istanbul since 1962 - and successive governments have had plans to introduce commercial nuclear power to the country for three decades or more. Since 1965, four attempts were made for the construction of an NPP in Turkey, but all failed. Turkish Electricity Authority (TEK, reorganized as Electricity Generation Corporation in 2002) was granted a site license for the Akkuyu site in 1976. According to the current long-term energy planning studies made by MENR, nuclear power is an important option to enhance the national energy security and reliability. In the light of this study, the Turkish Government has an intention for commencement of a nuclear power program that envisages the construction of 4500 M We nuclear power installed capacity in the next decade if the private energy sector do not make an attempt

  13. Cleansing and dismantling of CEA-Saclay nuclear licensed facilities

    International Nuclear Information System (INIS)

    Jeanjacques, Michel; Delaire, Isabelle; Glevarec, Rebecca; Mandard, Lionel; Martin, Jean-Louis; Serrano, Roger

    2013-01-01

    This summary presents the cleansing and dismantling operations currently realized on the CEA center of Saclay (CEA-Saclay). It was initiated at the beginning of the 2000 years a cleansing and dismantling program of the old Nuclear Licensed Facilities (NLF). Currently this program relates the dismantling operations to the Hot Laboratories (Laboratoires de Haute Activite: LHA) and the old workshops of the Liquid Waste Treatment Plant (Station des Effluents Liquides: STEL), the dismantling preparation of Ulysse reactor and the dismantling studies to the Solid Waste Management Plant (SWMP; Zone de Gestion des Dechets Solides) and the Osiris reactor. (authors)

  14. Gas Reactor International Cooperative Program. Interim report. Safety and licensing evaluaion of German Pebble Bed Reactor concepts

    International Nuclear Information System (INIS)

    1978-09-01

    The Pebble Bed Gas Cooled Reactor, as developed in the Federal Republic of Germany, was reviewed from a United States Safety and Licensing perspective. The primary concepts considered were the steam cycle electric generating pebble bed (HTR-K) and the process heat pebble bed (PNP), although generic consideration of the direct cycle gas turbine pebble bed (HHT) was included. The study examines potential U.S. licensing issues and offers some suggestions as to required development areas

  15. 7 CFR 6.28 - Transfer of license.

    Science.gov (United States)

    2010-01-01

    ... Licensing Authority will transfer to such other person the historical, nonhistorical or designated license... escrow with the sole condition for return of escrow being that the Licensing Authority determines that... to whom the historical licenses were issued during the quota year in which the sale or conveyance...

  16. Free Software Licenses and Other Free Licenses: Genetic Code of Digital Common Goods

    Directory of Open Access Journals (Sweden)

    Marco Ciurcina

    2017-06-01

    Full Text Available This article explores the history and describes the main features of free software licenses and other free licenses in an attempt to shed light on the reasons for their success in promoting individual behaviors converging towards the collective construction of digital commons.

  17. Licensing Teachers: Lessons from Other Professions.

    Science.gov (United States)

    Haberman, Martin

    1986-01-01

    The licensing of teachers should be modeled against professions similar to teaching rather than professions like medicine and architecture that are vastly different. Applying similar licensing practices can raise the status of teaching. Ignoring these licensing practices will prevent teachers from functioning as professionals. (MD)

  18. Expertise concerning the request by the ZWILAG Intermediate Storage Wuerenlingen AG for delivery of the operation licence for the conditioning installation as well as for the burning and melting installation of the central intermediate storage facility for radioactive wastes in Wuerenlingen; Gutachten zum Gesuch der ZWILAG Zwischenlager Wuerenlingen AG um Erteilung der Betriebsbewilligung fuer die Konditionierungsanlage sowie fuer die Verbrennungs- und Schmelzanlage des Zentralen Zwischenlagers fuer radioaktive Abfaelle in Wuerenlingen

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1999-08-15

    On December 15, 1997, the Central Intermediate Storage Facility for radioactive materials (ZWILAG) delivered a request to the Swiss Federal Council for an operational licence for the conditioning installation and the incineration and melting installation at the Central Intermediate Storage Facility (ZZL). For the whole project, the general licence was granted on June 23, 1993. The construction of the whole installation as well as the operation in the storage halls with reception, hot cell and transhipment station were licensed on August 12, 1999. The Federal Agency for the Safety of Nuclear Installations (HSK) examined the request documentation of ZWILAG from the point of view of nuclear safety and radiation protection. The results of the examination are contained in this report. In general, the examination leads to a positive decision. During the realisation process many project adaptations have brought improvements to the installation as far as radiation protection and the treatment of wastes are concerned. HSK requests from a former licensing process were taken into account by ZWILAG. The present examination contains many remarks and requests that the HSK considers necessary. The most important remarks are issued as special references as far as they do not appear as proposals in the licence obligations. In general, the reference form was chosen when the fulfilment of the request can be guarantied by HSK within the framework of a release process. Several references inform ZWILAG of problems for which HSK wishes to receive the results of extended inquiries or where HSK will assist in testing or demonstrations. Other references concern requests for plant documentation. Further, calculations of radioactive material release during normal operation is considered as being necessary. Based on its examination, HSK concludes that the conditions are fulfilled for the safe operation of the conditioning installation and of the incineration and melting installation as long as

  19. ONR Licensing and Regulation of a Geological Disposal Facility in the UK

    International Nuclear Information System (INIS)

    Boydon, Frans; Glazbrook, David

    2014-01-01

    Document available in abstract form only. Full text follows: The UK has substantial quantities of waste which has arisen from operation and decommissioning of legacy nuclear plant. While a disposal route for Low Level Waste (LLW) has been in operation in the UK for many years, there is as yet no such route for Higher Activity Waste. The government invited local communities to express an interest in hosting a Geological Disposal Facility (GDF). However, the Scottish government is opposed to deep disposal and proposes long-term interim storage in Scotland. This paper describes the work underway and current progress in developing a GDF for the UK. In particular it describes the current legal system in the UK that enables nuclear facilities to be licensed and the background underpinning licensing of existing disposal facilities. It identifies changes which will be necessary to legislation to enable a GDF to be licensed and work which it is performing in close co-operation with the Environment Agency which operate a permitting regime for environmental aspects. The Office of Nuclear Regulation (ONR) regulates safety, security and transport associated with nuclear sites. This paper focuses on the regulation of safety and radioactive waste. The UK licensing regime is non-prescriptive and proportionate, allowing for a flexible approach to licensing. The licence is not time-limited but is designed to be used from construction, through commissioning for the lifetime of the facility. Under the Nuclear Installations Act 1965 (as amended) ONR may attach licence conditions: - In the interests of safety; or - with respect to the handling, treatment and disposal of nuclear matter. ONR has developed a suite of 36 Licence conditions, which typically require the operator to made 'adequate arrangements' to ensure safety. These arrangements would involve the use of 'hold points' beyond which the operator must not proceed without ONR's agreement. In determining

  20. The licensing processes influence on nuclear market

    International Nuclear Information System (INIS)

    Locatelli, Giorgio; Mancini, Mauro; Sainati, Tristano; Sallinen, Liisa

    2011-01-01

    The paper deals with the licensing nuclear power plants; it focuses primarily on the licensing process implications into the international nuclear market. Nowadays there are twenty-six countries that are planning to build new nuclear facilities, and thirty-seven where nuclear reactors are proposed; on the other hand, there are mainly ten international reactor vendors. At international level, there are few vendors that have sufficient resources, capabilities and experience to carry out the design and delivering of a nuclear power plant in the international market; On the other hand, the licensing processes are strictly dependent on national law frameworks, and on the nuclear policies. The paper proposes a comparison of six licensing processes (the ones established in Finland, France, Italy, South Korea, USA and UK), and analyzes its main features and implications; the IAEA licensing process is taken as reference point. The objective of the paper is to propose a systemic approach for considering the licensing procedures. The framework proposed enables facilitating the licensing management and inferring the main features of licensing contexts. The paper concludes with a forecast of the nuclear licensing context, especially with respect to the fourth generation of nuclear reactors. (author)

  1. Research and development associated with licensing of MHTGR [Modular High Temperature Gas-Cooled Reactor

    International Nuclear Information System (INIS)

    Jones, H.

    1990-01-01

    The Modular High Temperature Gas-Cooled Reactor (MHTGR) currently under development by the US Department of Energy (US-DOE) for commercial applications has top-level goals of producing safe, economical power for the US utility industry. The utility industry has been represented in formulating design and licensing requirements through both a ''Utility User Requirements Document'' and by participating in the DOE system engineering process known as the ''Integrated Approach.'' The result of this collaboration has been to set stringent goals for both the safety and operational reliability of the MHTGR. To achieve these goals, the designer must have access to a more comprehensive data base of properties in several fields of technology than is currently available. A technology development program has been planned to provide this data to the designer in time to support both his design activities and the submittal of formal licensing application documents. The US-DOE has chosen the Oak Ridge National Laboratory (ORNL) to take the lead in planning and executing these technology programs. When completed these will augment the designer's current data base and provide the necessary depth to meet the stringent goals which have been set for the MHTGR. It is worth noting that the goals of safety and operational reliability are complementary, and the data required from the technology development program will be similar. Therefore, the program to support the licensing of the MHTGR is not separate from that required for design, but is a subset of that which meets all the requirements that result from implementing the US-DOE's integrated approach. 38 figs

  2. Installation of the Light-Water Breeder Reactor at the Shippingport Atomic Power Station (LWBR Development Program)

    International Nuclear Information System (INIS)

    Massimino, R.J.; Williams, D.A.

    1983-05-01

    This report summarizes the refueling operations performed to install a Light Water Breeder Reactor (LWBR) core into the existing pressurized water reactor vessel at the Shippingport Atomic Power Station. Detailed descriptions of the major installation operations (e.g., primary system preconditioning, fuel installation, pressure boundary seal welding) are included as appendices to this report; these operations are of technical interest to any reactor servicing operation, whether the reactor is a breeder or a conventional light water non-breeder core

  3. Installation of the Light-Water Breeder Reactor at the Shippingport Atomic Power Station (LWBR Development Program)

    Energy Technology Data Exchange (ETDEWEB)

    Massimino, R.J.; Williams, D.A.

    1983-05-01

    This report summarizes the refueling operations performed to install a Light Water Breeder Reactor (LWBR) core into the existing pressurized water reactor vessel at the Shippingport Atomic Power Station. Detailed descriptions of the major installation operations (e.g., primary system preconditioning, fuel installation, pressure boundary seal welding) are included as appendices to this report; these operations are of technical interest to any reactor servicing operation, whether the reactor is a breeder or a conventional light water non-breeder core.

  4. Whom to Choose as License Partner?

    DEFF Research Database (Denmark)

    Laursen, Keld; Reichstein, Toke; Trombini, Giulia

    2013-01-01

    between technology and market forces: if partners are market distant, the likelihood of technology license contractual partnership decreases with partners’ technological distance. Using data on the formation of license partnerships in the global biopharmaceutical industry over the period 1994......This paper investigates the matching of firms on the market for technology. The paper forwards two dimensions along which license formation occurs: technology and product-market. Both sides of the market search for a partner representing potential for high technology synergies to maximize licensing...

  5. 7 CFR 6.32 - Globalization of licenses.

    Science.gov (United States)

    2010-01-01

    ... 7 Agriculture 1 2010-01-01 2010-01-01 false Globalization of licenses. 6.32 Section 6.32 Agriculture Office of the Secretary of Agriculture IMPORT QUOTAS AND FEES Dairy Tariff-Rate Import Quota Licensing § 6.32 Globalization of licenses. If the Licensing Authority determines that entries of an article...

  6. 42 CFR 431.710 - Provisional licenses.

    Science.gov (United States)

    2010-10-01

    ... Licensing Nursing Home Administrators § 431.710 Provisional licenses. To fill a position of nursing home... 42 Public Health 4 2010-10-01 2010-10-01 false Provisional licenses. 431.710 Section 431.710 Public Health CENTERS FOR MEDICARE & MEDICAID SERVICES, DEPARTMENT OF HEALTH AND HUMAN SERVICES...

  7. Product Licenses Database Application

    CERN Document Server

    Tonkovikj, Petar

    2016-01-01

    The goal of this project is to organize and centralize the data about software tools available to CERN employees, as well as provide a system that would simplify the license management process by providing information about the available licenses and their expiry dates. The project development process is consisted of two steps: modeling the products (software tools), product licenses, legal agreements and other data related to these entities in a relational database and developing the front-end user interface so that the user can interact with the database. The result is an ASP.NET MVC web application with interactive views for displaying and managing the data in the underlying database.

  8. LHC installation planning

    CERN Document Server

    Weisz, S

    2005-01-01

    installation of the general services, the installation of the cryogenic line (QRL), the installation of the machine elements and the hardware commissioning. While the installation of the general services is now almost finished (see presentation by Katy Foraz and Serge Grillot), several problems and delays with the QRL made it unavoidable to revise the installation strategy and to schedule a number tasks in parallel. A new compressed installation planning has been issued, that fulfils the strategic objectives and allows starting new activities with minimal delays in sectors 7-8 and 8-1. However, the shortcuts that are introduced increase the level of risk that we will have to face and the coordination of such a large and complex variety of simultaneous activities makes the project even more challenging. The document will describe how the input from the different equipment groups is taken into account by the master schedule planning team with respect to equipment availability and production as well as logistics...

  9. Broad Overview of Energy Efficiency and Renewable Energy Opportunities for Department of Defense Installations

    Energy Technology Data Exchange (ETDEWEB)

    Anderson, E.; Antkowiak, M.; Butt, R.; Davis, J.; Dean, J.; Hillesheim, M.; Hotchkiss, E.; Hunsberger, R.; Kandt, A.; Lund, J.; Massey, K.; Robichaud, R.; Stafford, B.; Visser, C.

    2011-08-01

    The Strategic Environmental Research and Developmental Program (SERDP)/Environmental Security Technology Certification Program (ESTCP) is the Department of Defense?s (DOD) environmental science and technology program focusing on issues related to environment and energy for the military services. The SERDP/ESTCP Office requested that the National Renewable Energy Laboratory (NREL) provide technical assistance with strategic planning by evaluating the potential for several types of renewable energy technologies at DOD installations. NREL was tasked to provide technical expertise and strategic advice for the feasibility of geothermal resources, waste-to-energy technology, photovoltaics (PV), wind, microgrids, and building system technologies on military installations. This technical report is the deliverable for these tasks.

  10. Reactor coolant pump service life evaluation for current life cycle optimization and license renewal

    International Nuclear Information System (INIS)

    Doroshuk, B.W.; Berto, D.S.; Robles, M.

    1990-01-01

    This paper reports that as part of the plant life cycle management and license renewal program, Baltimore Gas and Electric Company (BG and E) has completed a service life evaluation of their reactor coolant pumps, funded jointly by EPRI and performed by ABB Combustion Engineering Nuclear Power. Two of the goals of the BG and E plant life cycle management and license renewal program, and of this current evaluation, are to identify actions which would optimize current plant operation, and ensure that license renewal remains a viable option. The reactor coolant pumps (RCPs) at BG and E's Calvert Cliffs Units 1 and 2 are Byron Jackson pumps with a diffuser and a single suction. This pump design is also used in many other nuclear plants. The RCP service life evaluation assessed the effect of all plausible age-related degradation mechanisms (ARDMs) on the RCP components. Cyclic fatigue and thermal embrittlement were two ARDMs identified as having a high potential to limit the service life of the pump case. The pump case is a primary pressure boundary component. Hence, ensuring its continued structural integrity is important

  11. Second session: operating European facilities and their programs; Session 2: Les installations Europeennes actuelles et leurs programmes

    Energy Technology Data Exchange (ETDEWEB)

    Iracane, D. [CEA Saclay, Dir. de l' Energie Nucleaire (DEN), 91 - Gif sur Yvette (France); Porracchia, A.; Fougeras, P.; Morey, J.M. [CEA Cadarache, 13 - Saint-Paul-lez-Durance (France). Dept. d' Etudes des Reacteurs; Loubiere, S.; Durande-Ayme, P. [CEA Saclay, Nuclear Energy Div., Reactors and Nuclear Services Deptment, 91 - Gif-sur-Yvette (France); Guidez, J.; Goux, D. [CEA Valrho, Dir. de l' Energie Nucleaire, DEN, 30 - Marcoule (France); Dupraz, R.; Brand, B. [FRAMATOME, AREVA-FANP, 69 - Lyon (France); Blanc, J.Y. [CEA Saclay, 91 - Gif sur Yvette (France); Perthuis, S. de [FRAMATOME ANP, 92 - Paris-La-Defence (France); Le Rouzic, J.F. [Electricite de France (EDF), 92 - Clamart (France)

    2005-07-01

    Most European nuclear post-irradiation examination facilities are ageing and the optimization of the remaining infrastructures may lead to connect them through a network implying consistent staff competence between countries and efficient nuclear material transport means. The second article describes the 3 very-low power research reactors operating in France: Minerve, Masurca and Eole. The Osiris reactor is presented in the third article, the author focuses on the devices available in Osiris to perform irradiation in light water reactor conditions and in high temperature reactor conditions and on the associated programs. Phenix reactor located on the Marcoule site had been performing from 1974 to 1990 the necessary technological qualifications required by the fast reactor system. An important upgrading program, led from 1994 to 2003, has allowed the reactor to begin a second life. Its investigation program encompasses research work on the transmutation of actinides and fission products and on new nuclear fuels and materials required for the future fourth generation of reactors. In Europe about 20 hot laboratories offer services to perform examination and qualification required by their national civil nuclear programs. Most are state-owned and show a large range of activities: nuclear fuels, materials, reprocessing, radio-nuclides, and radio-active sources. The last article reviews the main test loops operating in France and in neighboring countries. About 30 installations are reported and classified according to their activity fields : critical heat flux, hydro-mechanics, device testing, accidental situations, helium and severe reactor accidents. (A.C.)

  12. Environmental Impact Appraisal for renewal of special nuclear material license No. SNM-42 (Docket No. 70-27)

    International Nuclear Information System (INIS)

    1984-03-01

    The Babcock and Wilcox Company (B and W) Naval Nuclear Fuel Division (NNFD) facility near Lynchburg, Virginia, produces fuel assemblies and complete fuel modules for reactors used in the US Navy nuclear propulsion program and fuel components for university and other research reactors; and processes scrap material to recover the enriched uranium content. No significant modifications of the production procedures for the US Navy nuclear fuel fabrication have been made since the previous environmental assessment, and none are anticipated during the five-year license renewal period being considered. In 1982 the fabrication of fuel assemblies for university and other research reactors was begun. This environmental assessment provides a review of the past five years of operation and an analysis of future impacts, including the effect of plant changes. The proposed action is the renewal of the license necessary for B and W to continue the existing fuel fabrication operations. Principal operations in the fabrication facility include the processing of highly enriched uranium (> 90% 235 U) into fuel elements and assembling the elements into complete reactor cores for shipment and eventual installation in US Navy facilities. The principal environmental impacts of current operation of the NNFD result from release of radioactive gases to the atmosphere and of radioactively contaminated liquids to the adjacent James River. The actual gaseous and liquid pollutants released during normal operation of the plant have been monitored and documented. The principal subjects addressed in this environmental assessment include water use, pollutant controls, environmental monitoring, and environmental impact of operation and accidents. Other site factors and plant operations necessary for this assessment are described, and aspects of insignificant impacts are identified. 10 figures, 36 tables

  13. Nuclear facilities licensing

    International Nuclear Information System (INIS)

    Carvalho, A.J.M. de.

    1978-01-01

    The need for the adoption of a legal and normative system, defining objectives, pescriptions and the process of nuclear licensing and building of nuclear power plants in Brazil is enphasized. General rules for the development of this system are presented. The Brazilian rules on the matter are discussed. A general view of the German legal system for nuclear power plant licensing and the IAEA recommendations on the subject are finally presented. (A.L.S.L.) [pt

  14. 76 FR 13973 - United States Warehouse Act; Processed Agricultural Products Licensing Agreement

    Science.gov (United States)

    2011-03-15

    ... security of goods in the care and custody of the licensee. The personnel conducting the examinations will..., Warehouse Operations Program Manager, FSA, United States Department of Agriculture, Mail Stop 0553, 1400... continuing compliance with the standards of approval and operation. FSA will conduct examinations of licensed...

  15. Independent Spent Fuel Storage Installations (ISFSI). Annual report, FY 1978

    International Nuclear Information System (INIS)

    Zima, G.E.

    1979-03-01

    The prime objective of the subject program is the identification of technical aspects of the design, operation and maintenance of independent spent fuel storage installations which could contribute to technical bases for Regulations and Regulatory Guides issued by NRC for these facilities. Activities on the various tasks of the program for the FY 1978 period are discussed in this report

  16. To License or Not to License: An Examination of State Statutes Regarding Private Investigators and Digital Examiners

    Directory of Open Access Journals (Sweden)

    Thomas Lonardo

    2008-09-01

    Full Text Available In this paper the authors examine statutes that regulate, license, and enforce investigative functions in each US state. After identification and review of Private Investigator licensing requirements, the authors find that very few state statutes explicitly differentiate between Private Investigators and Digital Examiners. After contacting all state agencies the authors present a distinct grouping organizing state approaches to professional Digital Examiner licensing. The authors conclude that states must differentiate between Private Investigator and Digital Examiner licensing requirements and oversight.

  17. The Upgraded Plasma Focus Installation > - The Installation >

    International Nuclear Information System (INIS)

    Krokhin, O.N.; Nikulin, V.Ya.; Babenko, B.A.; Gorbunov, D.N.; Gurei, A.E.; Kalachev, N.V.; Kozlova, T.A.; Malafeev, Yu.S.; Polukhin, S.N.; Sychev, A.A.; Tikhomirov, A.A.; Tsybenko, S.P.; Volobuev, I.V.

    1999-01-01

    The paper presents the upgraded plasma focus installation > - the installation > and some preliminary experimental results. The total energy stored in capacity bank is now 400 kJ, current - 5 MA with the rise time 3.5 μs. The investigation is targeted on the study of near electrode processes and its influence on plasma dynamics in a special operating regime of Filippov type PF - Hard X-ray regime. (author)

  18. Operating reactors licensing actions summary

    International Nuclear Information System (INIS)

    1981-08-01

    The Operating Reactors Licensing Actions Summary is designed to provide the management of the Nuclear Regulatory Commission (NRC) with an overview of licensing actions dealing with operating power and nonpower reactors

  19. 77 FR 71404 - Notice of Intent to License Government-Owned Inventions; Intent to License on a Partially...

    Science.gov (United States)

    2012-11-30

    ... DEPARTMENT OF DEFENSE Department of the Army Notice of Intent to License Government-Owned Inventions; Intent to License on a Partially-Exclusive Basis AGENCY: Department of the Army, DoD. ACTION... by the Secretary of the Army. The US Army Edgewood Chemical Biological Center intends to license...

  20. Licensing of ''grandfather's'' facilities: Ukrainian experience

    International Nuclear Information System (INIS)

    Mikolaitchouk, H.; Bogdan, L.; Steinberg, N.

    1995-01-01

    In the former USSR, unlike most countries, radioactive waste management activities including waste disposal needed no license. But after the USSR breakdown the Ukrainian Parliament -- Verkhovna Rada -- invoked the revised Law on Business activities. According to Article 4 of the Law, in order to treat or to dispose radioactive waste every enterprise has to get a special permission or license. In compliance with the Law, the Cabinet of Ministers by its Ordinance of January 13, 1993, authorized the Ukrainian State Committee for Nuclear and Radiation Safety (UkrSCNRS) to issue special permissions or licenses for waste treatment and disposal. And that requirement was valid not only for future activities but also for existing facilities in operation. Taking into account the undergoing legislative process, SCNRS began to develop its licensing process without waiting for the special nuclear laws to be passed. On the basis of the legislation already in effect, first of all the Law on Enterprises (full responsibility of enterprises for their activities) and Law on Business activities (requirement to have a license for special types of activities), the newly formed national regulatory body had to identify all the enterprises that needed to be licensed, to establish relevant procedures, to develop related regulatory documents, to implement these procedures and documents at operating enterprises, and for each case to make a decision concerning feasibility of issuing a license, period of validity and license conditions

  1. Survey of the authorities competent for licensing and supervision in the field of radiation protection under the terms of the Atomic Energy Act (As of January 1980)

    International Nuclear Information System (INIS)

    1980-01-01

    Contents: 1. Portfolio of the Federal Minister of Defence. 2. Handling of other radioactive substances, equipment for the generation of ionizing radiation and activities in installations owned by third parties: 2.1 Licensing authorities; 2.2 competent authorities for the acception and documentation of notifications required under sections 4, sub-section 1, 17 sub-section 1, of the Radiation Protection Ordinance; 2.3 authorities competent for the registration of radiation records; 2.4 supervisory authorities. 3. Carriage of radioactive substances: 3.1 Federal authorities responsible for licensing and supervisions; 3.2 Land authorities responsible for licensing; 3.3 Land authorities responsible for supervision. 4. Permits concerning the design of equipment. 5. Import and export of radioactive substances: 5.1 Licensing authorities; 5.2 supervisory authorities. 6. Competent authorities in accordance with section 63 sub-section 3 paragraph 1 of the Radiation Protection Ordinance (monitoring stations) and according to the provisions of Land legislation. 7. Licensing and supervisory authorities for the treatment, processing or any other use of nuclear fuels under section 9 of the Atomic Energy Act. 8. Competences of the Laender in the implementation of the Atomic Energy Act and the Radiation Protection Ordinance. (orig.) [de

  2. Review process for license renewal applications

    International Nuclear Information System (INIS)

    Craig, John W.; Kuo, P.T.

    1991-01-01

    In preparation for license renewal reviews, the Nuclear Regulatory Commission has recently published for public review and comment a proposed rule for license renewal and a draft Standard Review Plan as well as a draft Regulatory Guide relating to the implementation of the proposed rule. In support of future license renewal applications, the nuclear industry has also submitted 11 industry reports for NRC review and approval. This paper briefly describe how these parallel regulatory and industry activities will be factored into the NRC review process for license renewal. (author)

  3. 10 CFR 781.51 - Nonexclusive licenses.

    Science.gov (United States)

    2010-01-01

    ... corporate structure of which licensee is a part, if any. However, the license shall not be assignable or... license upon the policies of the United States Government; (3) The effect of the license upon domestic and... extent of U.S. Government contribution to the development of the invention; (iv) The degree of...

  4. 7 CFR 6.33 - License fee.

    Science.gov (United States)

    2010-01-01

    ... certified mail, return receipt requested, advising the licensee that if payment is not mailed in accordance.... Where the license at issue is a historical license, this will result, pursuant to § 6.23(b), in the person's loss of historical eligibility for such license. (d) Licensees may elect not to accept certain...

  5. Intervention in independent spent fuel storage facility license application proceedings for storage on the power plant site

    International Nuclear Information System (INIS)

    Jordan, J.

    1992-01-01

    This presentation summarizes the intervention in the Nuclear Regulatory Commission (NRC) licensing process for currently operating Independent Spent fuel Storage Installation (ISFSI) projects at Carolina Power and Light's Company's H.B. Robinson, Duke Power Company's Oconee, and Virginia Power Company's Surry. In addition, intervention at dry storage facilities that are currently under development are also described. The utilities and reactors include Baltimore Gas and Electric Company's Calvert Cliffs, Public Service Company of Colorado's Fort St. Vrain plant, Northern States Power Company's Prairie Island, Wisconsin Electric Power Company's Point Beach, and Consumers Power Company's Palisades

  6. Licensing of ANSTO'S OPAL reactor during construction and commissioning

    International Nuclear Information System (INIS)

    Summerfield, M.W.; Ordonez, J.P.

    2006-01-01

    Full text: This paper presents a general description of the ongoing licensing activities associated with the construction and commissioning of the Australian Nuclear Science and Technology Organisation's (ANSTO) Open Pool Australian Light-water (OPAL) Reactor at their Lucas Heights site. It addresses the following aspects: The Construction Licence - what it is and what impact it had on the construction of the OPAL Reactor, specifically the various Construction Licence Conditions; The interface between ANSTO, INVAP and ARPANSA during the construction of the OPAL Reactor, particularly in relation to ARPANS Regulation 54; Specific licensing issues that have arisen during the construction and commissioning process and how they have been resolved; The Operating Licence Application - what it is and how it interfaces with the construction and commissioning of the OPAL Reactor. These aspects are all addressed from the point of view of the licensee ANSTO and the RRR Project. Particular emphasis will be given to the way in which the licensing process is integrated into the overall project program and the lessons learnt that may be of benefit to other licensees and regulators. Note that this paper is an update of a presentation given at IGORR10 and follows on from a paper previously presented at PNBC12 in October 2002

  7. 25 CFR 11.601 - Marriage licenses.

    Science.gov (United States)

    2010-04-01

    ... 25 Indians 1 2010-04-01 2010-04-01 false Marriage licenses. 11.601 Section 11.601 Indians BUREAU... ORDER CODE Domestic Relations § 11.601 Marriage licenses. A marriage license shall be issued by the clerk of the court in the absence of any showing that the proposed marriage would be invalid under any...

  8. Groundwater quality monitoring well installation for Waste Area Grouping 5 at Oak Ridge National Laboratory, Oak Ridge, Tennessee

    International Nuclear Information System (INIS)

    Mortimore, J.A.; Ebers, M.L.

    1994-09-01

    This report documents the drilling and installation of 22 groundwater quality monitoring (GQM) wells on the perimeter of Waste Area Grouping (WAG) 5. WAG 5 is located south of the Oak Ridge National Laboratory main plant area in Melton Valley and includes 33 solid waste management units. The wells at WAG 5 were drilled and developed between July 1987 and March 1990. These wells were installed to characterize and assess the WAG in accordance with applicable Department of Energy, state, and Environmental Protection Agency regulatory requirements. The purpose of the well installation program was to install GQM wells for groundwater characterization at WAG 5. Data packages produced during installation activities by the ERCE hydrogeologists are an important product of the program. These packages document the well drilling, installation, and development activities and provide valuable data for well sampling and WAG characterization. The forms contained in the packages include predrilling and postdrilling checklists, drilling and construction logs, development and hydraulic conductivity records, and quality control-related documents

  9. The optimal licensing contract in a differentiated Stackelberg model.

    Science.gov (United States)

    Hong, Xianpei; Yang, Lijun; Zhang, Huaige; Zhao, Dan

    2014-01-01

    This paper extends the work of Wang (2002) by considering a differentiated Stackelberg model, when the leader firm is an inside innovator and licenses its new technology by three options, that is, fixed-fee licensing, royalty licensing, and two-part tariff licensing. The main contributions and conclusions of this paper are threefold. First of all, this paper derives a very different result from Wang (2002). We show that, with a nondrastic innovation, royalty licensing is always better than fixed-fee licensing for the innovator; with a drastic innovation, royalty licensing is superior to fixed-fee licensing for small values of substitution coefficient d; however when d becomes closer to 1, neither fee nor royalty licensing will occur. Secondly, this paper shows that the innovator is always better off in case of two-part tariff licensing than fixed-fee licensing no matter what the innovation size is. Thirdly, the innovator always prefers to license its nondrastic innovation by means of a two-part tariff instead of licensing by means of a royalty; however, with a drastic innovation, the optimal licensing strategy can be either a two-part tariff or a royalty, depending upon the differentiation of the goods.

  10. Decommissioning of the Nuclear Licensed Facilities at the Fontenay aux Roses CEA Center

    International Nuclear Information System (INIS)

    Jeanjacques, Michel; Piketty, Laurence; Mandard, Lionel; Pedron, Guy; Boissonneau, Jean Francois; Fouquereau, Alain; Pichereau, Eric; Lethuaire, Nathalie; Estivie, David; Binet, Cedric; Meden, Igor

    2008-01-01

    This is a summary of the program for the decommissioning of all the CEA's facilities in Fontenay aux Roses. The particularity of this center is that it is located in a built-up area. Taking into account the particularities of the various buildings and the levels of radioactivity in them, it was possible to devise a coherent, optimized program for the CEA-FAR licensed nuclear facility decommissioning operations

  11. Solar lease grant program. Technical progress report

    Energy Technology Data Exchange (ETDEWEB)

    1981-04-01

    Progress on a lease program for the installation of a solar water heater with no installation charge is reported. Information on the announcement of the program, the selection of participants, the contractural agreement, progress on installation of equipment, monitoring, and evaluation is summarized. The status of the budget concerned with the program is announced. Forms used for applications for the program and an announcement from Resource Alternatives for Cilco customers are presented.

  12. Specificity in the licensing process of reduced enrichment in the Bulgarian research reactor

    International Nuclear Information System (INIS)

    Vitkova, Marietta; Gorinov, Ivan

    2005-01-01

    The presented paper considers some specific questions of the licensing process regarding the reconstruction of the Bulgarian IRT-2000 research reactor, which includes conversion to the low enriched fuel. This specificity has risen as a result of two facts. The design of the reactor reconstruction was made on the basis of the existing fresh 36% highly enriched fuel. But after finishing of the design process, this fresh highly enriched fuel was shipped back to Russia in the framework of the RERTR program. These facts have involved some changes in both - in the licensing and the design processes. Re-analysis of the neutronic and thermal-hydraulic calculations is required to be made on the base of the technical specifications of the new LEU fuel. To facilitate the licensing process the NRA has adopted regulatory acceptance criteria for approval of the reactor core design with LEU fuel. (author)

  13. Process computers automate CERN power supply installations

    CERN Document Server

    Ullrich, H

    1974-01-01

    Computerized automation systems are being used at CERN, Geneva, to improve the capacity, operational reliability and flexibility of the power supply installations for main ring magnets in the experimental zones of particle accelerators. A detailed account of the technological problem involved is followed in the article by a description of the system configuration, the program system and field experience already gathered in similar schemes. (1 refs).

  14. Delivering Regulatory Consents for Decommissioning and Restoration of the Dounreay Nuclear Licensed Site

    International Nuclear Information System (INIS)

    Crawford, R.W.; Zyda, P.W.

    2006-01-01

    On behalf of the Nuclear Decommissioning Authority (NDA) the United Kingdom Atomic Energy Authority (UKAEA) has implemented a strategy to translate the near-term Dounreay restoration plan into a suite of land use documents designed to deliver the necessary planning consents to decommission and restore the Dounreay Nuclear Licensed Site. The legal consents and authorizations required to enable UKAEA to commence major projects and progress the decommissioning of the site are highlighted along with the measures taken to secure political, public and regulatory acceptance at the earliest opportunity. The approach taken by UKAEA is explained, focusing particularly on the critical need to secure planning permission and stakeholder approval well before the onset of construction works. The intention is to realize the benefits of forging a close working relationship with the land use regulator, The Highland Council. UKAEA has taken an approach to suitably inform the planning authority, in particular, the production of the Dounreay Planning Framework (DPF) document. This paper describes the role and need for the DPF, focusing on the key purpose of amending the local development plan to secure supportive planning policies and to set a land use context for the subsequent site decommissioning and restoration. This also has the advantage of securing public acceptance through an established legal process. Strategic milestones subsequent to the Highland Council's adoption of the DPF are highlighted, including the submission of phased planning applications and compliance with environmental legislation generally. The paper describes and underscores the need for early engagement of other regulators in the planning process such as the Scottish Environment Protection Agency (SEPA), and the safety regulator, the Nuclear Installations Inspectorate (NII). It describes the linkages amongst land use consents, Best Practicable Environmental Options (BPEO), radioactive substances

  15. AVC/H.264 patent portfolio license

    Science.gov (United States)

    Skandalis, Dean A.

    2006-08-01

    MPEG LA, LLC offers a joint patent license for the AVC (a/k/a H.264) Standard (ISO/IEC IS 14496-10:2004). Like MPEG LA's other licenses, the AVC Patent Portfolio License is offered for the convenience of the marketplace as an alternative enabling users to access essential intellectual property owned by many patent holders under a single license rather than negotiating licenses with each of them individually. The AVC Patent Portfolio License includes essential patents owned by DAEWOO Electronics Corporation; Electronics and Telecommunications Research Institute (ETRI); France Telecom, societe anonyme; Fujitsu Limited; Hitachi, Ltd.; Koninklijke Philips Electronics N.V.; LG Electronics Inc.; Matsushita Electric Industrial Co., Ltd.; Microsoft Corporation; Mitsubishi Electric Corporation; Robert Bosch GmbH; Samsung Electronics Co., Ltd.; Sedna Patent Services, LLC; Sharp Kabushiki Kaisha; Siemens AG; Sony Corporation; The Trustees of Columbia University in the City of New York; Toshiba Corporation; UB Video Inc.; and Victor Company of Japan, Limited. Another is expected also to join as of August 1, 2006. MPEG LA's objective is to provide worldwide access to as much AVC essential intellectual property as possible for the benefit of AVC users. Therefore, any party that believes it has essential patents is welcome to submit them for evaluation of their essentiality and inclusion in the License if found essential.

  16. The Optimal Licensing Contract in a Differentiated Stackelberg Model

    Directory of Open Access Journals (Sweden)

    Xianpei Hong

    2014-01-01

    Full Text Available This paper extends the work of Wang (2002 by considering a differentiated Stackelberg model, when the leader firm is an inside innovator and licenses its new technology by three options, that is, fixed-fee licensing, royalty licensing, and two-part tariff licensing. The main contributions and conclusions of this paper are threefold. First of all, this paper derives a very different result from Wang (2002. We show that, with a nondrastic innovation, royalty licensing is always better than fixed-fee licensing for the innovator; with a drastic innovation, royalty licensing is superior to fixed-fee licensing for small values of substitution coefficient d; however when d becomes closer to 1, neither fee nor royalty licensing will occur. Secondly, this paper shows that the innovator is always better off in case of two-part tariff licensing than fixed-fee licensing no matter what the innovation size is. Thirdly, the innovator always prefers to license its nondrastic innovation by means of a two-part tariff instead of licensing by means of a royalty; however, with a drastic innovation, the optimal licensing strategy can be either a two-part tariff or a royalty, depending upon the differentiation of the goods.

  17. Licensing and advanced fuel designs

    International Nuclear Information System (INIS)

    Davidson, S.L.; Novendstern, E.H.

    1991-01-01

    For the past 15 years, Westinghouse has been actively involved in the development and licensing of fuel designs that contain major advanced features. These designs include the optimized fuel assembly, The VANTAGE 5 fuel assembly, the VANTAGE 5H, and most recently the VANTAGE+ fuel assembly. Each of these designs was supported by extensive experimental data, safety evaluations, and design efforts and required intensive interaction with the US Nuclear Regulatory Commission (NRC) during the review and approval process. This paper presents a description of the licensing approach and how it was utilized by the utilities to facilitate the licensing applications of the advanced fuel designs for their plants. The licensing approach described in this paper has been successfully applied to four major advanced fuel design changes ∼40 plant-specific applications, and >350 cycle-specific reloads in the past 15 years

  18. Nuclear licensing in Slovenia

    International Nuclear Information System (INIS)

    Prah, M.; Spiler, J.; Vojnovic, D.; Pristavec, M.

    1998-01-01

    The article presents the approach to nuclear licensing in Slovenia. The paper describes, the initialization, internal authorization and review process in the Krsko NPP. The overall process includes preparation, internal independent evaluation, the Krsko Operating Committee and the Krsko Safety Committee review and internal approval. In addition, the continuation of the licensing process is discussed which includes independent evaluation by an authorized institution and a regulatory body approval process. This regulatory body approval process includes official hearing of the licensee, communication with the licensee, and final issuance of a license amendment. The internal evaluation, which follows the methodology of US NRC (defined in 10 CFR 50.59 and NUMARC 125) is described. This concept is partially implemented in domestic legislation.(author)

  19. Fire protection and fire fighting in nuclear installations

    International Nuclear Information System (INIS)

    1989-01-01

    Fires are a threat to all technical installations. While fire protection has long been a well established conventional discipline, its application to nuclear facilities requires special considerations. Nevertheless, for a long time fire engineering has been somewhat neglected in the design and operation of nuclear installations. In the nuclear industry, the Browns Ferry fire in 1975 brought about an essential change in the attention paid to fire problems. Designers and plant operators, as well as insurance companies and regulators, increased their efforts to develop concepts and methods for reducing fire risks, not only to protect the capital investment in nuclear plants but also to consider the potential secondary effects which could lead to nuclear accidents. Although the number of fires in nuclear installations is still relatively large, their overall importance to the safety of nuclear power plants was not considered to be very high. Only more recently have probabilistic analyses changed this picture. The results may well have to be taken into account more carefully. Various aspects of fire fighting and fire protection were discussed during the Symposium, the first of its kind to be organized by the IAEA. It was convened in co-operation with several organizations working in the nuclear or fire protection fields. The intention was to gather experts from nuclear engineering areas and the conventional fire protection field at one meeting with a view to enhancing the exchange of information and experience and to presenting current knowledge on the various disciplines involved. The presentations at the meeting were subdivided into eight sessions: standards and licensing (6 papers); national fire safety practices (7 papers); fire safety by design (11 papers); fire fighting (2 papers); computer fire modeling (7 papers); fire safety in fuel center facilities (7 papers); fire testing of materials (3 papers); fire risk assessment (5 papers). A separate abstract was

  20. Regulatory guidance for license renewal

    International Nuclear Information System (INIS)

    Thoma, John A.

    1991-01-01

    The proposed 10 CFR Part 54 rule proceduralizes the process for license renewal by identifying both the administrative and technical requirements for a renewal application. To amplify and support this regulation, written guidance has been provided in the form of a draft Regulatory Guide (DG 1009) and a draft Standard Review Plan for License Renewal (NUREG 1299). This guidance is scheduled to be finalized in 1992. Similar guidance will be provided for the proposed revisions to 10 CFR Part 51 concerning the environmental aspects of license renewal. (author)

  1. In-situ thermal testing program strategy

    International Nuclear Information System (INIS)

    1995-06-01

    In the past year the Yucca Mountain Site Characterization Project has implemented a new Program Approach to the licensing process. The Program Approach suggests a step-wise approach to licensing in which the early phases will require less site information than previously planned and necessitate a lesser degree of confidence in the longer-term performance of the repository. Under the Program Approach, the thermal test program is divided into two principal phases: (1) short-term in situ tests (in the 1996 to 2000 time period) and laboratory thermal tests to obtain preclosure information, parameters, and data along with bounding information for postclosure performance; and (2) longer-term in situ tests to obtain additional data regarding postclosure performance. This effort necessitates a rethinking of the testing program because the amount of information needed for the initial licensing phase is less than previously planned. This document proposes a revised and consolidated in situ thermal test program (including supporting laboratory tests) that is structured to meet the needs of the Program Approach. A customer-supplier model is used to define the Project data needs. These data needs, along with other requirements, were then used to define a set of conceptual experiments that will provide the required data within the constraints of the Program Approach schedule. The conceptual thermal tests presented in this document represent a consolidation and update of previously defined tests that should result in a more efficient use of Project resources. This document focuses on defining the requirements and tests needed to satisfy the goal of a successful license application in 2001, should the site be found suitable

  2. Authorization procedure for the construction and operation of nuclear installations within certain non-member states of the European Communities. Canada, Spain, Sweden, Switzerland, the United States and Yugoslavia 1975

    International Nuclear Information System (INIS)

    Amaducci, Sandro; Dider, J.M.

    1976-01-01

    In all the countries considered except Switzerland, a formal site approval for a future nuclear installation is necessary before any request for construction can be placed with the licensing authority. Moreover, two separate authorizations - one for construction and the other for operation - are needed before full operations can begin. It is only in Sweden that no express application is required for a full operating authorization. Between the respective authorizations for construction and full operation, there are, in Canada, Spain and Sweden, one or more intermediate formal authorizations to be delivered by the licensing authority, and this alongside the progressive full loading of the nuclear installation concerned. As regards the decision-making level, the relevant authorizations are generally issued at centralized level, except in Yugoslavia, and to a certain extent, in Switzerland - this being because of the federal structure of these countries. Furthermore, public hearings are organized during the authorization procedure, except in Switzerland and Yugoslavia. Finally, there are steps which are very particular to the country concerned. In Canada, there is an informal 'application' and discussion between the 'applicant' and the licensing authority before the real procedure begins, whereas in the United States, the Attorney General carried out an anti-trust review at a pre-procedural stage. Further it is only in the latter country that time requirements are fixed by regulations for certain steps of the procedure

  3. Solar PV Manufacturing Cost Model Group: Installed Solar PV System Prices (Presentation)

    Energy Technology Data Exchange (ETDEWEB)

    Goodrich, A. C.; Woodhouse, M.; James, T.

    2011-02-01

    EERE's Solar Energy Technologies Program is charged with leading the Secretary's SunShot Initiative to reduce the cost of electricity from solar by 75% to be cost competitive with conventional energy sources without subsidy by the end of the decade. As part of this Initiative, the program has funded the National Renewable Energy Laboratory (NREL) to develop module manufacturing and solar PV system installation cost models to ensure that the program's cost reduction targets are carefully aligned with current and near term industry costs. The NREL cost analysis team has leveraged the laboratories' extensive experience in the areas of project finance and deployment, as well as industry partnerships, to develop cost models that mirror the project cost analysis tools used by project managers at leading U.S. installers. The cost models are constructed through a "bottoms-up" assessment of each major cost element, beginning with the system's bill of materials, labor requirements (type and hours) by component, site-specific charges, and soft costs. In addition to the relevant engineering, procurement, and construction costs, the models also consider all relevant costs to an installer, including labor burdens and overhead rates, supply chain costs, and overhead and materials inventory costs, and assume market-specific profits.

  4. Westinghouse AP1000 licensing maturity

    International Nuclear Information System (INIS)

    Schulz, T.; Vijuk, R.P.

    2005-01-01

    The Westinghouse AP1000 Program is aimed at making available a nuclear power plant that is economical in the U.S deregulated electrical power industry in the near-term. The AP1000 is two-loop 1000 MWe pressurizer water reactor (PWR). It is an up rated version of the AP600. The AP1000 uses passive safety systems to provide significant and measurable improvements in plant simplification, safety, reliability, investment protection and plant costs. The AP1000 uses proven technology, which builds on over 35 years of operating PWR experience. The AP1000 received Final Design Approval by the United States Nuclear Regulatory Commission (U.S. NRC) in September 2004. The AP1000 meets the US utility requirements. The AP1000 and its sister plant the AP600 have gone through a very through and complete licensing review. This paper describes the U.S. NRC review efforts of both the AP600 and the AP1000. The detail of the review and the independent calculations, evaluations and testing is discussed. The AP600 licensing documentation was submitted in 1992. The U.S. NRC granted Final Design Approval in 1999. During the intervening 7 years, the U.S. NRC asked thousands of questions, performed independent safety analysis, audited Westinghouse calculations and analysis, and performed independent testing. The more significant areas of discussion will be described. For the AP1000 Westinghouse first engaged the U.S. NRC in pre-certification discussions to define the extent of the review required, since the design is so similar to the AP600. The AP1000 licensing documentation was submitted in March 2002. The U.S. NRC granted Final Design Approval in September 2004. During the intervening 2 1/2 years, the U.S. NRC asked hundreds of questions, performed independent safety analysis, audited Westinghouse calculations and analysis, and performed independent testing. The more significant areas of discussion will be described. The implications of this review and approval on AP1000 applications in

  5. The latest electrical installation (I)

    International Nuclear Information System (INIS)

    Won, Jong Su

    1976-04-01

    This book deals with the latest electrical installation. The contents of this book are construction electrical installation, regulations related electrical installation, foundation and principle of wiring, main line feeder, lighting installation, power of wiring, main line feeder, lighting installation, power installation, method to read structure drawing for electrical construct drawing electric lamp wiring diagram, working drawing, material and tools and method of construction of electrical installation on types of wiring construction, metallic conduit, rigid poly-vinyl conduit wiring, bus duct work, cable work and insulation out of metal lathed.

  6. Structural considerations for solar installers : an approach for small, simplified solar installations or retrofits.

    Energy Technology Data Exchange (ETDEWEB)

    Richards, Elizabeth H.; Schindel, Kay (City of Madison, WI); Bosiljevac, Tom; Dwyer, Stephen F.; Lindau, William (Lindau Companies, Inc., Hudson, WI); Harper, Alan (City of Madison, WI)

    2011-12-01

    Structural Considerations for Solar Installers provides a comprehensive outline of structural considerations associated with simplified solar installations and recommends a set of best practices installers can follow when assessing such considerations. Information in the manual comes from engineering and solar experts as well as case studies. The objectives of the manual are to ensure safety and structural durability for rooftop solar installations and to potentially accelerate the permitting process by identifying and remedying structural issues prior to installation. The purpose of this document is to provide tools and guidelines for installers to help ensure that residential photovoltaic (PV) power systems are properly specified and installed with respect to the continuing structural integrity of the building.

  7. Development, assessment, licensing, and application of RELAP5YA at Yankee Atomic Electric Company

    International Nuclear Information System (INIS)

    Husain, A.

    1984-01-01

    Since 1975, Yankee Atomic Electric Company (YAEC) has been licensed to perform LOCA analyses (large and small breaks) for PWRs. The methods are based upon the WREM package, comprised of RELAP4-MOD 3, RELAP4-FLOOD, and TOODEE-2EM. Significant efforts were expended to compare WREM models against Appendix K criteria, and to incorporate changes for compliance with the criteria and for improved representation of LOCA phenomena. /SUP 2,3,4/ This internalized capability has been used extensively for licensing the Yankee and Maine Yankee plants, and for timely resolution of LOCA issues which frequently arose. The value of this internalized analysis capability was well recognized by the Yankee management. In 1979, Yankee embarked upon another LOCA Methods Development Program. One objective was to remove extra conservatisms inherent in older codes to provide additional operational flexibility for our plants. Also, we needed a code which could be used in a production mode to provide realistic response for off-normal conditions to be used in operator training and emergency guideline assessment. This program resulted in the development of RELAP5YA. The development, assessment, licensing, and application of RELAP5YA at YAEC is briefly described in this paper

  8. Guide to the selection, training, and licensing or certification of reprocessing plant operators. Volume I

    International Nuclear Information System (INIS)

    1976-06-01

    The Code of Federal Regulations, Title 10, Part 55, establishes procedures and criteria for the licensing of operators, including senior operators, in ''Production and Utilization Facilities'', which includes plants for reprocessing irradiated fuel. A training guide is presented which will facilitate the licensing of operators for nuclear reprocessing plants by offering generalized descriptions of the basic principles (theory) and the unit operations (mechanics) employed in reprocessing spent fuels. In the present volume, details about the portions of a training program that are of major interest to management are presented

  9. Guide to the selection, training, and licensing or certification of reprocessing plant operators. Volume I

    Energy Technology Data Exchange (ETDEWEB)

    None

    1976-06-01

    The Code of Federal Regulations, Title 10, Part 55, establishes procedures and criteria for the licensing of operators, including senior operators, in ''Production and Utilization Facilities'', which includes plants for reprocessing irradiated fuel. A training guide is presented which will facilitate the licensing of operators for nuclear reprocessing plants by offering generalized descriptions of the basic principles (theory) and the unit operations (mechanics) employed in reprocessing spent fuels. In the present volume, details about the portions of a training program that are of major interest to management are presented. (JSR)

  10. Changing mobility patterns and road mortality among pre-license teens in a late licensing country : an epidemiological study.

    NARCIS (Netherlands)

    Twisk, D.A.M. Bos, N.M. Shope, J.T. & Kok, G.

    2013-01-01

    Whereas the safety of teens in early licensing countries has been extensively studied, little is known about the safety of pre-license teens in late licensing countries, where these teens also may be at risk. This risk exists because of the combination of a) increasing use of travel modes with a

  11. 78 FR 17450 - Notice of Issuance of Materials License Renewal, Operating License SUA-1341, Uranium One USA, Inc...

    Science.gov (United States)

    2013-03-21

    ... License Renewal, Operating License SUA-1341, Uranium One USA, Inc., Willow Creek Uranium In Situ Recovery.... SUA- 1341 to Uranium One USA, Inc. (Uranium One) for its Willow Creek Uranium In Situ Recovery (ISR... Commission License No. SUA-1341 For Uranium One USA, Inc., Irigaray and Christensen Ranch Projects (Willow...

  12. 78 FR 5840 - Notice of License Termination for University of Illinois Advanced TRIGA Reactor, License No. R-115

    Science.gov (United States)

    2013-01-28

    ... University of Illinois Advanced TRIGA Reactor, License No. R-115 The U.S. Nuclear Regulatory Commission (NRC) is noticing the termination of Facility Operating License No. R-115, for the University of Illinois... Operating License No. R-115 is terminated. The above referenced documents may be examined, and/or copied for...

  13. A meta-analytic review of moral licensing.

    Science.gov (United States)

    Blanken, Irene; van de Ven, Niels; Zeelenberg, Marcel

    2015-04-01

    Moral licensing refers to the effect that when people initially behave in a moral way, they are later more likely to display behaviors that are immoral, unethical, or otherwise problematic. We provide a state-of-the-art overview of moral licensing by conducting a meta-analysis of 91 studies (7,397 participants) that compare a licensing condition with a control condition. Based on this analysis, the magnitude of the moral licensing effect is estimated to be a Cohen's d of 0.31. We tested potential moderators and found that published studies tend to have larger moral licensing effects than unpublished studies. We found no empirical evidence for other moderators that were theorized to be of importance. The effect size estimate implies that studies require many more participants to draw solid conclusions about moral licensing and its possible moderators. © 2015 by the Society for Personality and Social Psychology, Inc.

  14. Instruction of 27 March 1973 concerning implementation of Decree No 73-278 of 13 March 1973 setting up a Higher Council for Nuclear Safety and a Central Service for the Safety of Nuclear Installations

    International Nuclear Information System (INIS)

    1973-01-01

    This Instruction specifies, on the basis of the 1973 Decree, the duties, in particular regarding licensing, of the Central Service for the Safety of Nuclear Installations. The Service is assisted in its work by the Atomic Energy Commission (CEA) and advisory groups.(NEA) [fr

  15. PBMR-SA licensing project organization

    International Nuclear Information System (INIS)

    Clapisson, G.A.; Metcalf, P.E.; Mysen, A.

    2001-01-01

    The South African nuclear regulatory authority, the Council for Nuclear Safety (CNS), is beginning the safety review of the Pebble Bed Modular Reactor (PBMR) design under development by the South African National Electrical Utility, Eskom. This paper describes the CNS licensing process, including the establishment of basic licensing criteria, general design criteria, and specific design rules, as well the safety assessment to be conducted in accordance with the established structure. It also summarises the CNS PBMR review project activities, including the overall organisational arrangements, licensing basis, safety and risk assessment, general operating rules and plant design engineering, and pre-operational testing. (author)

  16. Residential Central Air Conditioning and Heat Pump Installation – Workshop Outcomes

    Energy Technology Data Exchange (ETDEWEB)

    Goetzler, William [Navigant Consulting, Burlington, MA (United States); Zogg, Robert [Navigant Consulting, Burlington, MA (United States); Young, Jim [Navigant Consulting, Burlington, MA (United States); Bargach, Youssef [Navigant Consulting, Burlington, MA (United States)

    2016-11-01

    DOE's Building Technologies Office works with researchers and industry partners to develop and deploy technologies that can substantially reduce energy consumption in residential and commercial buildings. This report aims to advance BTO’s energy savings, emissions reduction, and other program goals by identifying research and development (R&D), demonstration and deployment, and other non-regulatory initiatives for improving the design and installation of residential central air conditioners (CAC) and central heat pumps (CHP). Improving the adoption of CAC/CHP design and installation best practices has significant potential to reduce equipment costs, improve indoor air quality and comfort, improve system performance, and most importantly, reduce household energy consumption and costs for heating and cooling by addressing a variety of common installation issues.

  17. Licensing reform in the USA

    International Nuclear Information System (INIS)

    1991-01-01

    The licensing process for nuclear power plants in the USA is currently in two distinct stages: the issuance of a construction permit followed later by the issuance of an operation license. The ''two-step'' process has come under heavy criticism from the U.S. nuclear industry on the grounds that it causes uncertainty and delays and therefore inhibits new commitments to nuclear power plants. In 1989 the NRC published new regulations for the licensing of nuclear power plants which provide for the issuance of early site permits, safety certifications of standard designs, and combined construction permits and operating licences. The new rule was challenged by intervenors representing antinuclear groups who filed a legal challenge seeking to have the rule set aside on the grounds that it violates the Atomic Energy Act which they allege makes two-step licensing mandatory. In November 1990 the US Court of Appeals upheld the NRC's authority to issue combined licenses. An appeal for a rehearing has been filed. The paper analyses the events and the possible consequences of an adverse court decision. It reviews the options open to the NRC and industry if the court decision is upheld. The possibility of congressional action to amend the Atomic Energy Act is discussed. (author)

  18. An introduction to intellectual property licensing for technology companies

    Science.gov (United States)

    Meier, Lawrence H.

    2001-05-01

    Intellectual property licensing is an important issue facing all technology companies. Before entering into license agreements a number of issues need to be addressed, including invention ownership, obtaining and identifying licensable subject matter, and developing a licensing strategy. There are a number of important provisions that are included in most intellectual property license agreements. These provisions include definitions, the license grant, consideration, audit rights confidentiality, warranties, indemnification, and limitation of liability. Special licensing considerations exist relative to each type of intellectual property, and when the other party is a foreign company or a university.

  19. 75 FR 55799 - Government-Owned Inventions; Availability for Licensing

    Science.gov (United States)

    2010-09-14

    ... licensing. Licensing Contact: Patrick P. McCue, PhD, (301) 435-5560; [email protected] . Collaborative... Reference No. E-051-2010/0-US-01). Licensing Status: Available for licensing. Licensing Contact: Patrick P... for the brain tumors or brain cancers indentified as gliomas, glioblastomas, or astrocytomas. This...

  20. Installation Of A Training Center With Nuclear Instruments In The I.N.E.A

    International Nuclear Information System (INIS)

    Camargo B, Ana C.; Periaza C, A.

    1993-01-01

    In the framework of the regional technical cooperation of the countries in development, at present, the IAEA executes some investigation projects such as the program of Regional Arrangements of Technical Cooperation for Latin America and Caribbean (ARCAL), from which the program of nuclear instrumentation ARCAL II is derived and by agreement the INEA should install a reference center in Electronic and Nuclear Instrumentation. To complete this objective it has assigned the development of different sub projects, among which is the installation of a training center for operation, cares and quality control of nuclear instruments of medical applications

  1. 77 FR 47393 - Ocean Transportation Intermediary License Revocations

    Science.gov (United States)

    2012-08-08

    ...: Voluntary surrender of license. License No.: 12454N. Name: Federation Exports-Imports Inc. Address: 747...: Natco International Transports USA, L.L.C. Address: 12415 SW 136th Avenue, Bay 4, Miami, FL 33186 Date...: Voluntary surrender of license. License No.: 022773F. Name: WLI (USA) Inc. Address: 175-01 Rockaway Blvd...

  2. Experience of Developing Cloud Service for accounting Sales in installments

    Science.gov (United States)

    Barankov, V. V.; Barankova, I. I.; Mikhailova, U. V.; Kalugina, O. B.

    2018-05-01

    The paper presents the developed and implemented system of accounting sales in installments using tables as a cloud variant of Google services. The main system requirements and the special features of the program implementation such as the multi user data cleaning, the volume and speed of converting the tables, the mechanisms of conditional formatting of cells, the protection of cells and ranges and the data input check are provided. The paper also discusses the functionality of the system of accounting sales in installments, which is implemented by the formulae in the cells, the formulae in the extra options of Google tables and by programming in Google Apps Script, as a cloud variant of Java Script. The safety and security of the customers’ data, as well as staff members’ accountability and responsibility for the input of data in the system, are provided by a number of information security measures

  3. Status of safety issues at licensed power plants

    International Nuclear Information System (INIS)

    1991-03-01

    As part of ongoing US Nuclear Regulatory Commission (NRC) efforts to ensure the quality and accountability of safety issue information, a program has been established whereby an annual NUREG series report will be published on the status of licensee implementation and NRC verification of safety issues in major NRC requirement areas. The data contained in this report are a product of the NRC's Safety Issues Management System database, which is maintained by the Project Management Staff in the Office of Nuclear Reactor Regulation and by personnel in the NRC regions. This report has been prepared in order to provide a comprehensive description of the implementation and verification status of all the TMI Action Plan requirements at licensed reactors, and to make this information available to other interested parties, including the public. A corollary purpose of this report is for it to serve as a follow-on to NUREG-0933, ''A Prioritization of Safety Issues,'' which tracks safety issues up until requirements are approved for imposition at licensed facilities

  4. Evaluation of the contribution of license renewal of nuclear power plants to fault reduction in the U.S

    International Nuclear Information System (INIS)

    Chiba, Goro

    2008-01-01

    Although nuclear power plants in the U.S. were originally permitted to operate for 40 years, operating periods of many plants have been extended by license renewal for another 20 years. On the other hand, plant life management of nuclear power plants in Japan is carried out assuming long-term operation, and the licensee submits aging technology assessment reports before the plant has been operating commercially for 30 years, and then every ten years thereafter, and receives an evaluation by the authorities. In this paper, trend analysis using the INSS database on faults at nuclear power plants overseas, state of implementation of relevant aging management programs, and the effects of license renewal on preservation activities are examined. It is shown that the aging management program identified that many of the cases of fatigue, FAC, and a closed cycle cooling system have been addressed. As a result of analyzing the fault number for each unit, the number of aging faults trends to decrease after applying for license renewal. Therefore, the U.S. license renewal system is considered to be effective for plant life management, and hence the plant life management in Japan, which is substantially equivalent to the U.S. system, is valid. (author)

  5. 14 CFR 1245.108 - License to contractor.

    Science.gov (United States)

    2010-01-01

    ... 14 Aeronautics and Space 5 2010-01-01 2010-01-01 false License to contractor. 1245.108 Section... INTELLECTUAL PROPERTY RIGHTS Patent Waiver Regulations § 1245.108 License to contractor. (a) Each contractor.... The license extends to the contractor's domestic subsidiaries and affiliates, if any, within the...

  6. License protection with a tamper-resistant token

    NARCIS (Netherlands)

    Chong, C.N.; Ren, Bin; Doumen, J.M.; Etalle, Sandro; Hartel, Pieter H.; Corin, R.J.; Lim, Chae Hoon; Yung, Moti

    Content protection mechanisms are intended to enforce the usage rights on the content. These usage rights are carried by a license. Sometimes, a license even carries the key that is used to unlock the protected content. Unfortunately, license protection is difficult, yet it is important for digital

  7. Trends in CANDU licensing

    International Nuclear Information System (INIS)

    Snell, V.G.; Grant, S.D.

    1997-01-01

    Modern utilities view nuclear power more and more as a commodity - it must compete 'today' with current alternatives to attract their investment. With its long construction times and large capital investment, nuclear plants are vulnerable to delays once they have been committed. There are two related issues. Where the purchaser and the regulator are experienced in CANDU, the thrust is a very practical one: to identify and resolve major licensing risks at a very early stage in the project. Thus for a Canadian project, the designer (AECL) and the prospective purchaser would deal directly with the AECB. However CANDU has also been successfully licensed in other countries, including Korea, Romania, Argentina, India and Pakistan. Each of these countries has its own regulatory agency responsible for licensing the plant. In addition, however, the foreign customer and regulator may seek input from the AECB, up to and including a statement of licensability in Canada; this is not normally needed for a ''repeat'' plant and/or if the customer is experienced in CANDU, but can be requested if the plant configuration has been modified significantly from an already-operating CANDU. It is thus the responsibility of the designer to initiate early discussions with the AECB so the foreign CANDU meets the expectations of its customers

  8. 47 CFR 97.5 - Station license required.

    Science.gov (United States)

    2010-10-01

    .... (3) A military recreation station license grant. A military recreation station license grant may be... States military recreational premises where the station is situated. The person must not be a... the balance of the license term and the suspension is still in effect, suspended for the balance of...

  9. Capping off installation

    CERN Multimedia

    2006-01-01

    Installation of the cathode strip chambers for the muon system on the CMS positive endcap has been completed. Technicians install one of the last muon system cathode strip chambers on the CMS positive endcap. Like successfully putting together the pieces of a giant puzzle, installation of the muon system cathode strip chambers on one of the CMS endcaps has been completed. Total installation of the cathode strip chambers (CSC) is now 91 percent complete; only one ring of chambers needs to be mounted on the remaining endcap to finish installation of the entire system. To guarantee a good fit for the 468 total endcap muon system CSCs, physicists and engineers from the collaboration spent about 10 years carefully planning the design. The endcap muon system's cables, boxes, pipes and other parts were designed and integrated using a 3D computerized model. 'It took a long time to do all the computer modelling, but in the long run it saved us an enormous amount of time because it meant that everything fit together,...

  10. Non-Power Reactor Operator Licensing Examiner Standards

    International Nuclear Information System (INIS)

    1994-06-01

    The Non-Power Reactor Operator Licensing Examiner Standards provide policy and guidance to NRC examiners and establish the procedures and practices for examining and licensing of applicants for NRC operator licenses pursuant to Part 55 of Title 10 of the Code of Federal Regulations (10 CFR Part 55). They are intended to assist NRC examiners and facility licensees to understand the examination process better and to provide for equitable and consistent administration of examinations to all applicants by NRC examiners. These standards are not a substitute for the operator licensing regulations and are subject to revision or other internal operator examination licensing policy changes. As appropriate, this standard will be revised periodically to accommodate comments and reflect new information or experience

  11. IRIS project update: status of the design and licensing activities

    International Nuclear Information System (INIS)

    Petrovic, B.; Carelli, M.

    2004-01-01

    This paper presents an overview of the current status of the IRIS (International Reactor Innovative and Secure) project, focusing on the design and licensing activities. An update relative to the previous presentation at the 4th HND Conference is provided, highlighting some of the main accomplishments over the past two years. After successfully completing the conceptual design phase, IRIS is now finalizing the preliminary design as well. The pre-application licensing review with the U.S. NRC has been initiated in October of 2002. The safety-by-design approach and PRA-guided design open the possibility to aim for licensing not requiring off-site emergency response planning. Multiple single-unit and twin-unit site layouts have been developed within the ESP (Early Site Permit) program currently pursued by three U.S. power utilities. Desalination and district heating options have recently been added to the base design. Staggered construction schedules of multiple units may be applied to optimize cash-flow and minimize the required investment, making IRIS a financially attractive option, even for economies with limited investment capabilities. Because of its modularity, compatibility with smaller/medium grids, and enabling gradual build of new generating capacity matching the needs, IRIS has a large potential in the worldwide market.(author)

  12. Correlations between radiological technology graduates academic achievement and their obtainment of a license

    International Nuclear Information System (INIS)

    Park, Myeong Hwan; Kwon, Deok Moon; Seo, Soo Kyo

    2006-01-01

    The study analyzed the correlations between variables like characteristics related to admission, academic achievement, obtainment of a radiological technology license. A majority of participants were from Daegu and academic high schools. Many participants were accepted by general admission selection, and their reason to apply to Daegu Health College was high graduate employment. Their selection for the academic program was made by their parents and themselves. Those who took the same course twice held 35.1%, and those who got an academic warning took 8.5%. The degree of participants' academic achievement showed somewhat low, and they had difficulty in taking their major courses. The average grade for admission was lower in a following selection order: college graduates, general, special, and rural areas. The admission selections and taking science courses in high school showed little significant correlations with obtainment of a radiological technology license. However, the obtainment of the license had significant correlations with retaking the same course, getting an academic warning, and the degree of academic achievement. The results also revealed that the obtainment of the license had little significant correlations with a part-time job experience, having a boy/girlfriend, and student club participation, but it had significant correlations with accommodations and study club participation. In conclusion, it is important to point out that radiological technology graduates' obtainment of a license is closely related with the degree of their academic achievement and their college life

  13. NPP License Renewal and Aging Management: Revised Guidance

    International Nuclear Information System (INIS)

    Hull, A.B.; Hiser, A.L.; Lindo-Talin, S.E.

    2012-01-01

    Based on the Atomic Energy Act, the NRC issues licenses for commercial power reactors to operate for up to 40 years and allows these licenses to be renewed for up to another 20 years. NRC has approved license renewal for well over 50% of U.S. located reactors originally licensed to operate for 40 years. Of these 104 reactors (69 PWRs, 35 BWRs), the NRC has issued renewed licenses for 71 units and is currently reviewing applications for another 15 units. As of May 1, 2012, ten plants at nine sites had entered their 41st year of operation and thus are in their first period of extended operation (PEO). Five more plants will enter the PEO by the end of 2012. One foundation of the license renewal process has been license renewal guidance documents (LRGDs). The U.S. Nuclear Regulatory Commission (NRC) revised key guidance documents used for nuclear power license renewal in 2010 and 2011. These include NUREG-1800, 'Standard Review Plan for Review of License Renewal Applications,' revision 2 (SRP-LR), and NUREG-1801, 'Generic Aging Lessons Learned (GALL) Report,' revision 2 (GALL Report). The guidance documents were updated to reflect lessons learned and operating experience gained since the guidance documents were last issued in 2005. (author)

  14. 76 FR 31307 - Notice of Intent To License Government-Owned Inventions; Intent To License Exclusively

    Science.gov (United States)

    2011-05-31

    ... DEPARTMENT OF DEFENSE Department of the Army Notice of Intent To License Government-Owned Inventions; Intent To License Exclusively AGENCY: Department of the Army, DoD. ACTION: Notice. SUMMARY: The... Army. The US Army Edgewood Chemical Biological Center and the US Army Research Laboratory intend to...

  15. Hydroelectric power in Switzerland: large growth potential by increasing the installed power

    International Nuclear Information System (INIS)

    Schleiss, A.

    2007-01-01

    Due to its important hydroelectric power generation facilities (about 525 plants with a total power of 13,314 MW producing about 35.3 TWh annually) Switzerland plays an important role in the interconnected European power system. Large artificial storage lakes in the Swiss Alps can generate peak power during hours of highest demand: 9700 MW are available from accumulated energy and the total power of pumped-storage facilities amounts to 1700 MW. The latter allow refilling the reservoirs at periods of low power demand and generating power at periods of peak demand. In the case of favorable conditions, the yearly average power production could be increased by 6% and the production during the winter period (October to March) by 20% by the year 2020. However, looking forward to the year 2050, the annual production is expected to decrease by 3% despite a possible extension of hydropower. This decrease is due to the enforcement of the minimum residual water flow rates required by a new legislation to protect the rivers. The enforcement is due at latest when the present licenses for water utilization expire. On the other hand, the installed (peak) power might be further increased by 50% by retrofitting the existing installations and constructing the pumped-storage plants currently at the planning stage

  16. 9 CFR 2.6 - Annual license fees.

    Science.gov (United States)

    2010-01-01

    ... method used to calculate the license fee. All initial license and changed class of license fees must be... research facilities, dealers, exhibitors, retail pet stores, and persons for use as pets, directly or through an auction sale, by the dealer or applicant during his or her preceding business year (calendar or...

  17. May compact storage facilities be licensed

    International Nuclear Information System (INIS)

    Gleim, A.; Winter, G.

    1980-01-01

    The authors examine as potential statements fo fact for licensing so-called compact storage facilities for spent fuel elements Sec. 6 to 9c of the German Atomic Energy Act and Sec. 4 of the German Radiation Protection Ordinance. They find that none of these provisions were applicable to compact stroage facilities. In particular, the storage of spent fuel elements was no storage of nuclear fuels licensable under Sec. 6 of the Atomic Energy Act, because Sec. 6 did not cover spent fuel elements. Also in the other wording of the Atomic Energy Act there was no provision, which could be used as a statement of fact for licensing compact storage facilities. Such facilities could not be licensed and, for that reason, were not permitted. (IVR) [de

  18. How a regulator is preparing for reviewing a license application file: The case of ASN

    International Nuclear Information System (INIS)

    Tanguy, Loic

    2014-01-01

    The French Nuclear Safety Authority (ASN) is an independent administrative authority. It prepares regulation pertaining to the management of radioactive waste, monitors the control of safety of basic nuclear installations that produce or treat waste or are involved in their disposal and performs inspections of waste producers (EDF, AREVA, CEA, hospitals, research centres, etc.) and Andra, the French National Radioactive Waste Management Agency. It regulates the overall system set up by Andra for accepting waste from producers and assesses waste management policy and the practices of radioactive waste producers. It reviews license applications and authorises commissioning of nuclear installations. In order to review technical documents, ASN benefits from the expertise of technical support organisations. The French Institute for Radiation Protection and Nuclear Safety (IRSN) is the main such organisation. ASN has been making efforts to diversify its experts for several years. In preparing its decisions, ASN also calls on the opinions and recommendations of seven Advisory Committees of Experts (GPE), with expert knowledge in the areas of waste, nuclear pressure equipment, medical exposure, non-medical radiation protection, reactors, transport, and laboratories and nuclear plants. ASN consults the GPEs in preparing its main decisions. In particular, they review the preliminary, provisional and final safety analysis reports for each nuclear installation. They can also be consulted about changes in regulations or doctrine. (authors)

  19. Illicit operation of industrial plant subject to licensing, or of other installations within the purview of the German Federal Emission Control Act (BImSchG), which have been shut down for protection against hazards (section 327, subsection 2, No. 1 Penal Code (StGB)); Das unerlaubte Betreiben von genehmigungsbeduerftigen Anlagen oder sonstigen Anlagen im Sinne des Bundes-Immissionsschutzgesetzes, deren Betrieb zum Schutz vor Gefahren untersagt worden ist (Paragraph 327 Abs.2 Nr.1 StGB)

    Energy Technology Data Exchange (ETDEWEB)

    Ocker, A.

    1995-12-31

    The 18th act of 28 March 1980 for amendment of the German Criminal Code (StGB) incorporated the provisions governing the criminal offence of illicit operation of installations subject to licensing into the StGB. These provisions have until then been forming part of the BImSchG (Federal Act on Emission Control). The study in hand presents a discussion of section 327, subsection 2, No. 1 StGB, because this provision represents a fundamental type of an administration accessory criminal offence and thus is suitable to be taken as a basis for an analysis of the scope of problems covered by the StGB, but having an effect on and being interlaced with offences governed by other acts and legal provisions. The study addresses inter alia items such as the object of legal protection defined by this section of the StGB, the provisions defining the licensability of a non-licensed installation in operation, and the consequences of defective decisions under administrative law on the applicability of criminal law provisions. The specific aspects of section 327 StGB, which are of a dominantly administrative nature, are discussed, in particular those referring to the definition of the term ``industrial installation`` as defined by the BImSchG. [Deutsch] Durch das 18. Strafrechtsaenderungsgesetz vom 28.3.1980 wurde der Straftatbestand des unerlaubten Betreibens von Anlagen, die einer Genehmigung nach dem Bundesimmissionsschutzgesetz beduerfen, aus dem BImSchG in das Kernstrafrecht ueberfuehrt. Die vorliegende Untersuchung versucht eine eingehendere Auseinandersetzung mit Para. 327 Abs. 2 Nr. 1 StGB, weil diese Vorschrift als ein Grundtypus der verwaltungsakzessorischen Straftatbestaende die Gelegenheiit zur vertieften Diskussion von umfassenderen strafrechtlichen Problemkreisen gibt. Angesprochen sind insoweit vor allem die Frage des geschuetzten Rechtsgutes der Norm, der Behandlung der materiellen Genehmigungsfaehigkeit eines ungenehmigten Anlagenbetriebs sowie der Auswirkungen von

  20. Solar installer training: Home Builders Institute Job Corps

    Energy Technology Data Exchange (ETDEWEB)

    Hansen, K.; Mann, R. [San Diego Job Corps Center, Imperial Beach, CA (United States). Home Builders Inst.

    1996-10-01

    The instructors describe the solar installation training program operated since 1979 by the Home Builders Institute, the Educational Arm of the National Association of Home Builders for the US Department of Labor, Job Corps in San Diego, CA. The authors are the original instructors and have developed the program since its inception by a co-operative effort between the Solar Energy Industries Association, NAHB and US DOL. Case studies of a few of the 605 students who have gone to work over the years after the training are included. It is one of the most successful programs under the elaborate Student Performance Monitoring Information System used by all Job Corps programs. Job Corps is a federally funded residential job training program for low income persons 16--24 years of age. Discussion details the curriculum and methods used in the program including classroom, shop and community service projects. Solar technologies including all types of hot water heating, swimming pool and spa as well as photovoltaics are included.