WorldWideScience

Sample records for plant pfp project

  1. Project plan remove special nuclear material from PFP project plutonium finishing plant

    International Nuclear Information System (INIS)

    BARTLETT, W.D.

    1999-01-01

    This plan presents the overall objectives, description, justification and planning for the Plutonium Finishing Plant (PFP) Remove Special Nuclear Material (SNM) Materials. The intent of this plan is to describe how this project will be managed and integrated with other facility stabilization and deactivation activities. This plan supplements the overall integrated plan presented in the Plutonium Finishing Plant Integrated Project Management Plan (IPMP), HNF-3617, Rev. 0. This project plan is the top-level definitive project management document for PFP Remove SNM Materials project. It specifies the technical, schedule, requirements and the cost baselines to manage the execution of the Remove SNM Materials project. Any deviations to the document must be authorized through the appropriate change control process

  2. Project plan remove special nuclear material from PFP project plutonium finishing plant; TOPICAL

    International Nuclear Information System (INIS)

    BARTLETT, W.D.

    1999-01-01

    This plan presents the overall objectives, description, justification and planning for the Plutonium Finishing Plant (PFP) Remove Special Nuclear Material (SNM) Materials. The intent of this plan is to describe how this project will be managed and integrated with other facility stabilization and deactivation activities. This plan supplements the overall integrated plan presented in the Plutonium Finishing Plant Integrated Project Management Plan (IPMP), HNF-3617,Rev. 0. This project plan is the top-level definitive project management document for PFP Remove SNM Materials project. It specifies the technical, schedule, requirements and the cost baselines to manage the execution of the Remove SNM Materials project. Any deviations to the document must be authorized through the appropriate change control process

  3. Project Plan For Remove Special Nuclear Material (SNM) from Plutonium Finishing Plant (PFP) Project

    International Nuclear Information System (INIS)

    BARTLETT, W.D.

    1999-01-01

    This plan presents the overall objectives, description, justification and planning for the Plutonium Finishing Plant (PFP) Remove SNM Materials. The intent of this plan is to describe how this project will be managed and integrated with other facility stabilization and deactivation activities. This plan supplements the overall integrated plan presented in the Plutonium Finishing Plant Integrated Project Management Plan (IPMP), HNF-3617. This project plan is the top-level definitive project management document for the PFP Remove SNM Materials project. It specifies the technical, schedule, requirements and the cost baseline to manage the execution of the Remove SNM Materials project. Any deviation to the document must be authorized through the appropriate change control process. The Remove SNM Materials project provides the necessary support and controls required for DOE-HQ, DOE-RL, BWHC, and other DOE Complex Contractors the path forward to negotiate shipped/receiver agreements, schedule shipments, and transfer material out of PFP to enable final deactivation

  4. Plutonium Finishing Plant (PFP) hazards assessment

    International Nuclear Information System (INIS)

    Campbell, L.R.

    1998-01-01

    This report documents the hazards assessment for the Plutonium Finishing Plant (PFP) located on the US Department of Energy (DOE) Hanford Site. This hazards assessment was conducted to provide the emergency planning technical basis for the PFP. DOE Orders require an emergency planning hazards assessment for each facility that has the potential to reach or exceed the lowest level emergency classification

  5. PFP deactivation project management plan

    International Nuclear Information System (INIS)

    Bogen, D.M.

    1997-01-01

    This document identifies the overall approach for deactivation of the Plutonium Finishing Plant (PFP) Complex, excluding the vaults, and includes a draft set of End Point Criteria for all buildings being deactivated

  6. Anticipated Radiological Dose to Worker for Plutonium Stabilization and Handling at PFP - Project W-460

    International Nuclear Information System (INIS)

    WEISS, E.V.

    2000-01-01

    This report provides estimates of the expected whole body and extremity radiological dose, expressed as dose equivalent (DE), to workers conducting planned plutonium (Pu) stabilization processes at the Hanford Site Plutonium Finishing Plant (PFP). The report is based on a time and motion dose study commissioned for Project W-460, Plutonium Stabilization and Handling, to provide personnel exposure estimates for construction work in the PFP storage vault area plus operation of stabilization and packaging equipment at PFP

  7. Anticipated Radiological Dose to Worker for Plutonium Stabilization and Handling at PFP - Project W-460

    CERN Document Server

    Weiss, E V

    2000-01-01

    This report provides estimates of the expected whole body and extremity radiological dose, expressed as dose equivalent (DE), to workers conducting planned plutonium (Pu) stabilization processes at the Hanford Site Plutonium Finishing Plant (PFP). The report is based on a time and motion dose study commissioned for Project W-460, Plutonium Stabilization and Handling, to provide personnel exposure estimates for construction work in the PFP storage vault area plus operation of stabilization and packaging equipment at PFP.

  8. PFP requirements development planning guide

    International Nuclear Information System (INIS)

    SINCLAIR, J.C.

    1999-01-01

    The PFP Requirements Development Planning Guide presents the strategy and process used for the identification, allocation, and maintenance of requirements within the Plutonium Finishing Plant (PFP) integrated project baseline. Future revisions to this document will be included as attachments (e.g., results of the PFP Requirements Analysis attributable to this approach). This document is intended be a Project-owned management tool. As such, this document will periodically require revisions resulting from improvements of the information, processes, and techniques as now described. Future updates may be made to this document by PFP management and final approval of the content will be accomplished in a Baseline Change Request as it impacts the Multi-Year Work Plan, or baseline information managed in the Hanford Site Systems Engineering Baseline

  9. PFP functional development planning guide

    International Nuclear Information System (INIS)

    SINCLAIR, J.C.

    1999-01-01

    The PFP Functional Development Planning Guide presents the strategy and process used for the identification, development, and analysis of functions (activities) necessary to satisfy the requirements within the Plutonium Finishing Plant (PFP) integrated project baseline. The functional analysis will provide the basis for the development of a function driven work breakdown structure. Future revisions to this document will include as attachments the results of the PFP Functional Analysis resulting from this approach. This document is intended be a Project-owned management tool. As such, the guide will periodically require revisions resulting from improvements of the information, processes, and techniques as now described

  10. PFP total operating efficiency calculation and basis of estimate

    International Nuclear Information System (INIS)

    SINCLAIR, J.C.

    1999-01-01

    The purpose of the Plutonium Finishing Plant (PFP) Total Operating Efficiency Calculation and Basis of Estimate document is to provide the calculated value and basis of estimate for the Total Operating Efficiency (TOE) for the material stabilization operations to be conducted in 234-52 Building. This information will be used to support both the planning and execution of the Plutonium Finishing Plant (PFP) Stabilization and Deactivation Project's (hereafter called the Project) resource-loaded, integrated schedule

  11. PFP issues/assumptions development and management planning guide

    International Nuclear Information System (INIS)

    SINCLAIR, J.C.

    1999-01-01

    The PFP Issues/Assumptions Development and Management Planning Guide presents the strategy and process used for the identification, allocation, and maintenance of an Issues/Assumptions Management List for the Plutonium Finishing Plant (PFP) integrated project baseline. Revisions to this document will include, as attachments, the most recent version of the Issues/Assumptions Management List, both open and current issues/assumptions (Appendix A), and closed or historical issues/assumptions (Appendix B). This document is intended be a Project-owned management tool. As such, this document will periodically require revisions resulting from improvements of the information, processes, and techniques as now described. Revisions that suggest improved processes will only require PFP management approval

  12. Plutonium Finishing Plant (PFP) Treatment and Storage Unit Waste Analysis Plan

    International Nuclear Information System (INIS)

    PRIGNANO, A.L.

    2000-01-01

    The purpose of this waste analysis plan (WAP) is to document waste analysis activities associated with the Plutonium Finishing Plant Treatment and Storage Unit (PFP Treatment and Storage Unit) to comply with Washington Administrative Code (WAC) 173-303-300(1), (2), (4)(a) and (5). The PFP Treatment and Storage Unit is an interim status container management unit for plutonium bearing mixed waste radiologically managed as transuranic (TRU) waste. TRU mixed (TRUM) waste managed at the PFP Treatment and Storage Unit is destined for the Waste Isolation Pilot Plant (WIPP) and therefore is not subject to land disposal restrictions [WAC 173-303-140 and 40 CFR 268]. The PFP Treatment and Storage Unit is located in the 200 West Area of the Hanford Facility, Richland Washington (Figure 1). Because dangerous waste does not include source, special nuclear, and by-product material components of mixed waste, radionuclides are not within the scope of this documentation. The information on radionuclides is provided only for general knowledge

  13. System Design Description PFP Thermal Stabilization

    International Nuclear Information System (INIS)

    RISENMAY, H.R.

    2000-01-01

    The purpose of this document is to provide a system design description (SDD) and design basis for the Plutonium Finishing Plant (PFP) Thermal Stabilization project. The chief objective of the SDD is to document the Structures, Systems, and Components (SSCs) that establish and maintain the facility Safety Envelope necessary for normal safe operation of the facility; as identified in the FSAR, the OSRs, and Safety Assessment Documents (SADs). This safety equipment documentation should satisfy guidelines for the SDD given in WHC-SD-CP-TI-18 1, Criteria for Identification and Control of Equipment Necessary for Preservation of the Safety Envelope and Safe Operation of PFP. The basis for operational, alarm response, maintenance, and surveillance procedures are also identified and justified in this document. This document and its appendices address the following elements of the PFP Thermal Stabilization project: Functional and design requirements; Design description; Safety Envelope Analysis; Safety Equipment Class; and Operational, maintenance and surveillance procedures

  14. Plutonium Finishing Plant (PFP) Final Safety Analysis Report (FSAR) [SEC 1 THRU 11

    Energy Technology Data Exchange (ETDEWEB)

    ULLAH, M K

    2001-02-26

    The Plutonium Finishing Plant (PFP) is located on the US Department of Energy (DOE) Hanford Site in south central Washington State. The DOE Richland Operations (DOE-RL) Project Hanford Management Contract (PHMC) is with Fluor Hanford Inc. (FH). Westinghouse Safety Management Systems (WSMS) provides management support to the PFP facility. Since 1991, the mission of the PFP has changed from plutonium material processing to preparation for decontamination and decommissioning (D and D). The PFP is in transition between its previous mission and the proposed D and D mission. The objective of the transition is to place the facility into a stable state for long-term storage of plutonium materials before final disposition of the facility. Accordingly, this update of the Final Safety Analysis Report (FSAR) reflects the current status of the buildings, equipment, and operations during this transition. The primary product of the PFP was plutonium metal in the form of 2.2-kg, cylindrical ingots called buttoms. Plutonium nitrate was one of several chemical compounds containing plutonium that were produced as an intermediate processing product. Plutonium recovery was performed at the Plutonium Reclamation Facility (PRF) and plutonium conversion (from a nitrate form to a metal form) was performed at the Remote Mechanical C (RMC) Line as the primary processes. Plutonium oxide was also produced at the Remote Mechanical A (RMA) Line. Plutonium processed at the PFP contained both weapons-grade and fuels-grade plutonium materials. The capability existed to process both weapons-grade and fuels-grade material through the PRF and only weapons-grade material through the RMC Line although fuels-grade material was processed through the line before 1984. Amounts of these materials exist in storage throughout the facility in various residual forms left from previous years of operations.

  15. Project Management Plan to Maintain Safe and Compliant Conditions at the Plutonium Finishing Plant

    International Nuclear Information System (INIS)

    COX, G.J.

    1999-01-01

    This Project Management Plan presents the overall plan, description, mission, and workscope for the Plutonium Finishing Plant (PFP) maintain safe and compliant conditions project at PFP. This plan presents the overall description, mission, work scope, and planning for the Plutonium Finishing Plant (PFP) Maintain Safe and Compliant Conditions Project at PFP. This project includes all tasks required to maintain the safety boundary for the PFP Complex, except for the 2736-2 Vault Complex and the 234-52 vaults and vault-type rooms. The intent of this plan is to describe how this project will be managed and integrated with the stabilization, and deactivation activities. This plan supplements the overall integrated plan presented in the Plutonium Finishing Plant Integrated Project Management Plan (IPMP), HNF-3617, Rev. 0. This is the top-level definitive project management document that specifies the technical (work scope), schedule, and cost baselines that will manage the execution of this project. It describes the organizational approach and roles/responsibilities implemented to execute the project. This plan is under configuration management and any deviations must be authorized by appropriate change control action

  16. Plutonium Finishing Plant (PFP) Waste Composition and High Efficiency Particulate Air Filter Loading

    Energy Technology Data Exchange (ETDEWEB)

    ZIMMERMAN, B.D.

    2000-12-11

    This analysis evaluates the effect of the Plutonium Finishing Plant (PFP) waste isotopic composition on Tank Farms Final Safety Analysis Report (FSAR) accidents involving high-efficiency particulate air (HEPA) filter failure in Double-Contained Receiver Tanks (DCRTs). The HEPA Filter Failure--Exposure to High Temperature or Pressure, and Steam Intrusion From Interfacing Systems accidents are considered. The analysis concludes that dose consequences based on the PFP waste isotopic composition are bounded by previous FSAR analyses. This supports USQD TF-00-0768.

  17. Plutonium Finishing Plant (PFP) Standards/Requirements Identification Document (S/RID)

    Energy Technology Data Exchange (ETDEWEB)

    Maddox, B.S.

    1996-01-01

    This Standards/Requirements Identification Document (S/RID) sets forth the Environmental Safety and Health (ESH) standards/requirements for the Plutonium Finishing Plant (PFP). This S/RID is applicable to the appropriate life cycle phases of design, construction, operation, and preparation for decommissioning. These standards/requirements are adequate to ensure the protection of the health and safety of workers, the public, and the environment.

  18. Plutonium Finishing Plant (PFP) Standards/Requirements Identification Document (S/RID)

    International Nuclear Information System (INIS)

    Maddox, B.S.

    1996-01-01

    This Standards/Requirements Identification Document (S/RID) sets forth the Environmental Safety and Health (ESH) standards/requirements for the Plutonium Finishing Plant (PFP). This S/RID is applicable to the appropriate life cycle phases of design, construction, operation, and preparation for decommissioning. These standards/requirements are adequate to ensure the protection of the health and safety of workers, the public, and the environment

  19. PFP supply fan motor starters

    International Nuclear Information System (INIS)

    Keck, R.D.

    1995-01-01

    The Plutonium Finishing Plant (PFP) is currently stabilizing about 25 kg of Pu sludge; upon completion of this task, PFP will be maintained in a safe standby condition to await decision from the PFP NEPA review. It can take about 10 years to initiate and complete terminal cleanout after this; the facility will then be decommissioned and decontaminated. The 234-5Z ventilation system must continue to operate until terminal cleanout. Part of the ventilation system is the seismic fan shutdown system which shuts down the ventilation supply fans in case of strong earthquake. This document presents criteria for installing solid state, reduced voltage motor starters and isolation contactors for the 8 main ventilation supply fans. The isolation contactors will shutdown the supply fans in event of earthquake

  20. PFP dangerous waste training plan

    International Nuclear Information System (INIS)

    Khojandi, J.

    1996-01-01

    This document establishes the minimum training requirements for the Plutonium Finishing Plant (PFP) personnel who are responsible for management of dangerous waste. The training plan outlines training requirements for handling of solid dangerous waste during generator accumulation and liquid dangerous waste during treatment and storage operations. The implementation of this training plan will ensure the PFP facility compliance with the training plan requirements of Dangerous Waste Regulation. Chapter 173-303-330. Washington Administrative Code (WAC). The requirements for such compliance is described in Section 11.0 of WHC-CM-7-5 Environmental Compliance Manual

  1. PLUTONIUM FINISHING PLANT (PFP) 241-Z LIQUID WASTE TREATMENT FACILITY DEACTIVATION AND DEMOLITION

    International Nuclear Information System (INIS)

    JOHNSTON GA

    2008-01-01

    Fluor Hanford, Inc. (FH) is proud to submit the Plutonium Finishing Plant (PFP) 241-Z liquid Waste Treatment Facility Deactivation and Demolition (D and D) Project for consideration by the Project Management Institute as Project of the Year for 2008. The decommissioning of the 241-Z Facility presented numerous challenges, many of which were unique with in the Department of Energy (DOE) Complex. The majority of the project budget and schedule was allocated for cleaning out five below-grade tank vaults. These highly contaminated, confined spaces also presented significant industrial safety hazards that presented some of the most hazardous work environments on the Hanford Site. The 241-Z D and D Project encompassed diverse tasks: cleaning out and stabilizing five below-grade tank vaults (also called cells), manually size-reducing and removing over three tons of process piping from the vaults, permanently isolating service utilities, removing a large contaminated chemical supply tank, stabilizing and removing plutonium-contaminated ventilation ducts, demolishing three structures to grade, and installing an environmental barrier on the demolition site . All of this work was performed safely, on schedule, and under budget. During the deactivation phase of the project between November 2005 and February 2007, workers entered the highly contaminated confined-space tank vaults 428 times. Each entry (or 'dive') involved an average of three workers, thus equaling approximately 1,300 individual confined -space entries. Over the course of the entire deactivation and demolition period, there were no recordable injuries and only one minor reportable skin contamination. The 241-Z D and D Project was decommissioned under the provisions of the 'Hanford Federal Facility Agreement and Consent Order' (the Tri-Party Agreement or TPA), the 'Resource Conservation and Recovery Act of 1976' (RCRA), and the 'Comprehensive Environmental Response, Compensation, and Liability Act of 1980

  2. PFP Interface identification and management planning guide

    International Nuclear Information System (INIS)

    SINCLAIR, J.C.

    1999-01-01

    The purpose of-this planning guide is to present the process used to identify, document, and control PFP Stabilization and Deactivation Project interfaces. Revisions to this document will include, as attachments, the most recent version of the Project Interface Management List. A preliminary Interface Management List is included in Appendix A. This document is intended be a Project owned management tool. As such, this document will periodically require revisions resulting from improvements of the information, processes, and techniques as now described. For most revisions that suggest improved processes, PFP management approval is all that will be required

  3. HANFORD PLUTONIUM FINISHG PLAN (PFP) COMPLETES PLUTONIUM STABILIZATION KEY SAFETY ISSUES CLOSED

    International Nuclear Information System (INIS)

    GERBER, M.S.

    2004-01-01

    A long and intense effort to stabilize and repackage nearly 18 metric tons (MT) of plutonium-bearing leftovers from defense production and nuclear experiments concluded successfully in February, bringing universal congratulations to the Department of Energy's Hanford Site in southeast Washington State. The victorious stabilization and packaging endeavor at the Plutonium Finishing Plant (PFP), managed and operated by prime contractor Fluor Hanford, Inc., finished ahead of all milestones in Hanford's cleanup agreement with regulators, and before deadlines set by the Defense Nuclear Facilities Safety Board (DNFSB), a part of the federal Executive Branch that oversees special nuclear materials. The PFP stabilization and packaging project also completed under budget for its four-year tenure, and has been nominated for a DOE Secretarial Award. It won the Project of the Year Award in the local chapter competition of the Project Management Institute, and is being considered for awards at the regional and national level

  4. PFP Interface identification and management planning guide; TOPICAL

    International Nuclear Information System (INIS)

    SINCLAIR, J.C.

    1999-01-01

    The purpose of-this planning guide is to present the process used to identify, document, and control PFP Stabilization and Deactivation Project interfaces. Revisions to this document will include, as attachments, the most recent version of the Project Interface Management List. A preliminary Interface Management List is included in Appendix A. This document is intended be a Project owned management tool. As such, this document will periodically require revisions resulting from improvements of the information, processes, and techniques as now described. For most revisions that suggest improved processes, PFP management approval is all that will be required

  5. PLUTONIUM FINISHING PLANT (PFP) 241-Z LIQUID WASTE TREATMENT FACILITY DEACTIVATION AND DEMOLITION

    Energy Technology Data Exchange (ETDEWEB)

    JOHNSTON GA

    2008-01-15

    Fluor Hanford, Inc. (FH) is proud to submit the Plutonium Finishing Plant (PFP) 241-Z liquid Waste Treatment Facility Deactivation and Demolition (D&D) Project for consideration by the Project Management Institute as Project of the Year for 2008. The decommissioning of the 241-Z Facility presented numerous challenges, many of which were unique with in the Department of Energy (DOE) Complex. The majority of the project budget and schedule was allocated for cleaning out five below-grade tank vaults. These highly contaminated, confined spaces also presented significant industrial safety hazards that presented some of the most hazardous work environments on the Hanford Site. The 241-Z D&D Project encompassed diverse tasks: cleaning out and stabilizing five below-grade tank vaults (also called cells), manually size-reducing and removing over three tons of process piping from the vaults, permanently isolating service utilities, removing a large contaminated chemical supply tank, stabilizing and removing plutonium-contaminated ventilation ducts, demolishing three structures to grade, and installing an environmental barrier on the demolition site . All of this work was performed safely, on schedule, and under budget. During the deactivation phase of the project between November 2005 and February 2007, workers entered the highly contaminated confined-space tank vaults 428 times. Each entry (or 'dive') involved an average of three workers, thus equaling approximately 1,300 individual confined -space entries. Over the course of the entire deactivation and demolition period, there were no recordable injuries and only one minor reportable skin contamination. The 241-Z D&D Project was decommissioned under the provisions of the 'Hanford Federal Facility Agreement and Consent Order' (the Tri-Party Agreement or TPA), the 'Resource Conservation and Recovery Act of 1976' (RCRA), and the 'Comprehensive Environmental Response, Compensation, and

  6. PFP solution stabilization

    International Nuclear Information System (INIS)

    Aftanas, B.L.

    1996-01-01

    This Functional Design Criteria (FDC) addresses remediation of the plutonium-bearing solutions currently in inventory at the Plutonium Finishing Plant (PFP). The recommendation from the Environmental Impact Statement (EIS) is that the solutions be treated thermally and stabilized as a solid for long term storage. For solutions which are not discardable, the baseline plan is to utilize a denitration process to stabilize the solutions prior to packaging for storage

  7. Technical Basis Document for PFP Area Monitoring Dosimetry Program

    CERN Document Server

    Cooper, J R

    2000-01-01

    This document describes the phantom dosimetry used for the PFP Area Monitoring program and establishes the basis for the Plutonium Finishing Plant's (PFP) area monitoring dosimetry program in accordance with the following requirements: Title 10, Code of Federal Regulations (CFR), part 835, ''Occupational Radiation Protection'' Part 835.403; Hanford Site Radiological Control Manual (HSRCM-1), Part 514; HNF-PRO-382, Area Dosimetry Program; and PNL-MA-842, Hanford External Dosimetry Technical Basis Manual.

  8. Technical Basis Document for PFP Area Monitoring Dosimetry Program

    International Nuclear Information System (INIS)

    COOPER, J.R.

    2000-01-01

    This document describes the phantom dosimetry used for the PFP Area Monitoring program and establishes the basis for the Plutonium Finishing Plant's (PFP) area monitoring dosimetry program in accordance with the following requirements: Title 10, Code of Federal Regulations (CFR), part 835, ''Occupational Radiation Protection'' Part 835.403; Hanford Site Radiological Control Manual (HSRCM-1), Part 514; HNF-PRO-382, Area Dosimetry Program; and PNL-MA-842, Hanford External Dosimetry Technical Basis Manual

  9. Technical Basis Document for PFP Area Monitoring Dosimetry Program

    Energy Technology Data Exchange (ETDEWEB)

    COOPER, J.R.

    2000-04-17

    This document describes the phantom dosimetry used for the PFP Area Monitoring program and establishes the basis for the Plutonium Finishing Plant's (PFP) area monitoring dosimetry program in accordance with the following requirements: Title 10, Code of Federal Regulations (CFR), part 835, ''Occupational Radiation Protection'' Part 835.403; Hanford Site Radiological Control Manual (HSRCM-1), Part 514; HNF-PRO-382, Area Dosimetry Program; and PNL-MA-842, Hanford External Dosimetry Technical Basis Manual.

  10. PFP total process throughput calculation and basis of estimate

    International Nuclear Information System (INIS)

    SINCLAIR, J.C.

    1999-01-01

    The PFP Process Throughput Calculation and Basis of Estimate document provides the calculated value and basis of estimate for process throughput associated with material stabilization operations conducted in 234-52 Building. The process throughput data provided reflects the best estimates of material processing rates consistent with experience at the Plutonium Finishing Plant (PFP) and other U.S. Department of Energy (DOE) sites. The rates shown reflect demonstrated capacity during ''full'' operation. They do not reflect impacts of building down time. Therefore, these throughput rates need to have a Total Operating Efficiency (TOE) factor applied

  11. Integrated project management plan for the Plutonium Finishing Plant stabilization and deactivation project

    International Nuclear Information System (INIS)

    SINCLAIR, J.C.

    1999-01-01

    This document sets forth the plans, organization, and control systems for managing the PFP Stabilization and Deactivation Project, and includes the top level cost and schedule baselines. The project includes the stabilization of Pu-bearing materials, storage, packaging, and transport of these and other nuclear materials, surveillance and maintenance of facilities and systems relied upon for storage of the materials, and transition of the facilities in the PFP Complex

  12. Plutonium Finishing Plant (PFP) Criticality Alarm System Commercial Grade Item (CGI) Critical Characteristics

    International Nuclear Information System (INIS)

    WHITE, W.F.

    1999-01-01

    This document specifies the critical characteristics for Commercial Grade Items (CGI) procured for PFP's criticality alarm system as required by HNF-PRO-268 and HNF-PRO-1819. These are the minimum specifications that the equipment must meet in order to properly perform its safety function. There may be several manufacturers or models that meet the critical characteristics for any one item. PFP's Criticality Alarm System includes the nine criticality alarm system panels and their associated hardware. This includes all parts up to the first breaker in the electrical distribution system. Specific system boundaries and justifications are contained in HNF-SD-CP-SDD-003, ''Definition and Means of Maintaining the Criticality Detectors and Alarms Portion of the PFP Safety Envelope.'' The procurement requirements associated with the system necessitates procurement of some system equipment as Commercial Grade Items in accordance with HNF-PRO-268, ''Control of Purchased Items and Services.''

  13. The Integrated Safety Management System Verification Enhancement Review of the Plutonium Finishing Plant (PFP)

    International Nuclear Information System (INIS)

    BRIGGS, C.R.

    2000-01-01

    The primary purpose of the verification enhancement review was for the DOE Richland Operations Office (RL) to verify contractor readiness for the independent DOE Integrated Safety Management System Verification (ISMSV) on the Plutonium Finishing Plant (PFP). Secondary objectives included: (1) to reinforce the engagement of management and to gauge management commitment and accountability; (2) to evaluate the ''value added'' benefit of direct public involvement; (3) to evaluate the ''value added'' benefit of direct worker involvement; (4) to evaluate the ''value added'' benefit of the panel-to-panel review approach; and, (5) to evaluate the utility of the review's methodology/adaptability to periodic assessments of ISM status. The review was conducted on December 6-8, 1999, and involved the conduct of two-hour interviews with five separate panels of individuals with various management and operations responsibilities related to PFP. A semi-structured interview process was employed by a team of five ''reviewers'' who directed open-ended questions to the panels which focused on: (1) evidence of management commitment, accountability, and involvement; and, (2) consideration and demonstration of stakeholder (including worker) information and involvement opportunities. The purpose of a panel-to-panel dialogue approach was to better spotlight: (1) areas of mutual reinforcement and alignment that could serve as good examples of the management commitment and accountability aspects of ISMS implementation, and, (2) areas of potential discrepancy that could provide opportunities for improvement. In summary, the Review Team found major strengths to include: (1) the use of multi-disciplinary project work teams to plan and do work; (2) the availability and broad usage of multiple tools to help with planning and integrating work; (3) senior management presence and accessibility; (4) the institutionalization of worker involvement; (5) encouragement of self-reporting and self

  14. PFP Wastewater Sampling Facility

    International Nuclear Information System (INIS)

    Hirzel, D.R.

    1995-01-01

    This test report documents the results obtained while conducting operational testing of the sampling equipment in the 225-WC building, the PFP Wastewater Sampling Facility. The Wastewater Sampling Facility houses equipment to sample and monitor the PFP's liquid effluents before discharging the stream to the 200 Area Treated Effluent Disposal Facility (TEDF). The majority of the streams are not radioactive and discharges from the PFP Heating, Ventilation, and Air Conditioning (HVAC). The streams that might be contaminated are processed through the Low Level Waste Treatment Facility (LLWTF) before discharging to TEDF. The sampling equipment consists of two flow-proportional composite samplers, an ultrasonic flowmeter, pH and conductivity monitors, chart recorder, and associated relays and current isolators to interconnect the equipment to allow proper operation. Data signals from the monitors are received in the 234-5Z Shift Office which contains a chart recorder and alarm annunciator panel. The data signals are also duplicated and sent to the TEDF control room through the Local Control Unit (LCU). Performing the OTP has verified the operability of the PFP wastewater sampling system. This Operability Test Report documents the acceptance of the sampling system for use

  15. Project Management Plan Solution Stabilization

    International Nuclear Information System (INIS)

    SATO, P.K.

    1999-01-01

    This plan presents the overall objectives, description, justification and planning for the Plutonium Finishing Plant (PFP) Solutions Stabilization subproject. The intent of this plan is to describe how this project will be managed and integrated with other facility stabilization and deactivation activities. This plan supplements the overall integrated plan presented in the Integrated Project Management Plan (IPMP) for the Plutonium Finishing Plant Stabilization and Deactivation Project, HNF-3617. This project plan is the top-level definitive project management document for the PFP Solution Stabilization subproject. It specifies the technical, schedule, requirements and the cost baselines to manage the execution of the Solution Stabilization subproject. Any deviations to the document must be authorized through the appropriate change control process

  16. Project Management Plan Solution Stabilization

    Energy Technology Data Exchange (ETDEWEB)

    SATO, P.K.

    1999-08-31

    This plan presents the overall objectives, description, justification and planning for the Plutonium Finishing Plant (PFP) Solutions Stabilization subproject. The intent of this plan is to describe how this project will be managed and integrated with other facility stabilization and deactivation activities. This plan supplements the overall integrated plan presented in the Integrated Project Management Plan (IPMP) for the Plutonium Finishing Plant Stabilization and Deactivation Project, HNF-3617. This project plan is the top-level definitive project management document for the PFP Solution Stabilization subproject. It specifies the technical, schedule, requirements and the cost baselines to manage the execution of the Solution Stabilization subproject. Any deviations to the document must be authorized through the appropriate change control process.

  17. System design description PFP thermal stabilization

    International Nuclear Information System (INIS)

    RISENMAY, H.R.

    1998-01-01

    The purpose of this document is to provide a system design description and design basis for the Plutonium Finishing P1ant (PFP) Thermal Stabilization project. The sources of material for this project are residues scraped from glovebox floors and materials already stored in vault storage that need further stabilizing to meet the 3013 storage requirements. Stabilizing this material will promote long term storage and reduced worker exposure. This document addresses: function design, equipment, and safety requirements for thermal stabilization of plutonium residues and oxides

  18. SLIGHTLY IRRADIATED FUEL (SIF) INTERIM DISPOSITION PROJECT

    International Nuclear Information System (INIS)

    Norton, S.H.

    2010-01-01

    CH2M HILL Plateau Remediation Company (CH2M HILL PRC) is proud to submit the Slightly Irradiated Fuel (SIF) Interim Disposition Project for consideration by the Project Management Institute as Project of the Year for 2010. The SIF Project was a set of six interrelated sub-projects that delivered unique stand-alone outcomes, which, when integrated, provided a comprehensive and compliant system for storing high risk special nuclear materials. The scope of the six sub-projects included the design, construction, testing, and turnover of the facilities and equipment, which would provide safe, secure, and compliant Special Nuclear Material (SNM) storage capabilities for the SIF material. The project encompassed a broad range of activities, including the following: Five buildings/structures removed, relocated, or built; Two buildings renovated; Structural barriers, fencing, and heavy gates installed; New roadways and parking lots built; Multiple detection and assessment systems installed; New and expanded communication systems developed; Multimedia recording devices added; and A new control room to monitor all materials and systems built. Project challenges were numerous and included the following: An aggressive 17-month schedule to support the high-profile Plutonium Finishing Plant (PFP) decommissioning; Company/contractor changeovers that affected each and every project team member; Project requirements that continually evolved during design and construction due to the performance- and outcome-based nature ofthe security objectives; and Restrictions imposed on all communications due to the sensitive nature of the projects In spite of the significant challenges, the project was delivered on schedule and $2 million under budget, which became a special source of pride that bonded the team. For years, the SIF had been stored at the central Hanford PFP. Because of the weapons-grade piutonium produced and stored there, the PFP had some of the tightest security on the Hanford

  19. SLIGHTLY IRRADIATED FUEL (SIF) INTERIM DISPOSITION PROJECT

    Energy Technology Data Exchange (ETDEWEB)

    NORTON SH

    2010-02-23

    CH2M HILL Plateau Remediation Company (CH2M HILL PRC) is proud to submit the Slightly Irradiated Fuel (SIF) Interim Disposition Project for consideration by the Project Management Institute as Project of the Year for 2010. The SIF Project was a set of six interrelated sub-projects that delivered unique stand-alone outcomes, which, when integrated, provided a comprehensive and compliant system for storing high risk special nuclear materials. The scope of the six sub-projects included the design, construction, testing, and turnover of the facilities and equipment, which would provide safe, secure, and compliant Special Nuclear Material (SNM) storage capabilities for the SIF material. The project encompassed a broad range of activities, including the following: Five buildings/structures removed, relocated, or built; Two buildings renovated; Structural barriers, fencing, and heavy gates installed; New roadways and parking lots built; Multiple detection and assessment systems installed; New and expanded communication systems developed; Multimedia recording devices added; and A new control room to monitor all materials and systems built. Project challenges were numerous and included the following: An aggressive 17-month schedule to support the high-profile Plutonium Finishing Plant (PFP) decommissioning; Company/contractor changeovers that affected each and every project team member; Project requirements that continually evolved during design and construction due to the performance- and outcome-based nature ofthe security objectives; and Restrictions imposed on all communications due to the sensitive nature of the projects In spite of the significant challenges, the project was delivered on schedule and $2 million under budget, which became a special source of pride that bonded the team. For years, the SIF had been stored at the central Hanford PFP. Because of the weapons-grade piutonium produced and stored there, the PFP had some of the tightest security on the Hanford

  20. CSER 99-001: PFP LAB Dentirating calciner

    International Nuclear Information System (INIS)

    MILLER, E.M.; DOBBIN, K.D.

    1999-01-01

    A criticality safety evaluation report was prepared for the Plutonium Finishing Plant (PFP) laboratory denigrating calciner, located in Glovebox 188-1, that converts Pu(NO 3 ) 4 solutions to the high fired stable oxide PuO 2 . Fissile mass limits and volume limits are set for the glovebox for testing operations and training operators using only nitric acid feed to a plutonium oxide bed in the calciner

  1. Water bath and air bath calorimeter qualification for measuring 3013 containers of plutonium oxide at the Hanford Plutonium Finishing Plant (PFP)

    International Nuclear Information System (INIS)

    WELSH, T.L.

    2003-01-01

    The purpose of this paper is to present qualification data generated from water and air-bath calorimeters measuring radioactive decay heat from plutonium oxide in DOE STD-3013-2000 (3013) containers at the Hanford Plutonium Finishing Plant (PFP). Published data concerning air and water bath calorimeters and especially 3013-qualified calorimeters is minimal at best. This paper will address the data from the measurement/qualification test plan, the heat standards used, and the calorimeter precision and accuracy results. The 3013 package is physically larger than earlier plutonium oxide storage containers, thereby necessitating a larger measurement chamber. To accommodate the measurements of the 3013 containers at PFP, Los Alamos National Laboratory (LANL) supplied a water bath dual-chambered unit and the Savannah River Technology Center (SRTC) provided two air-bath calorimeters. Both types of Calorimeters were installed in the analytical laboratory at PFP. The larger 3013 containers presented a new set of potential measurement problems: longer counting times, heat conductivity through a much larger container mass and wall thickness, and larger amounts of copper shot to assist sample thermal conductivity. These potential problems were addressed and included in the measurement/qualification test plan

  2. Engineering report (conceptual design) PFP solution stabilization

    Energy Technology Data Exchange (ETDEWEB)

    Witt, J.B.

    1997-07-17

    This Engineering Report (Conceptual Design) addresses remediation of the plutonium-bearing solutions currently in inventory at the Plutonium Finishing Plant (PFP). The recommendation from the Environmental Impact Statement (EIS) is that the solutions be treated thermally and stabilized as a solid for long term storage. For solutions which are not discardable, the baseline plan is to utilize a denitration process to stabilize the solutions prior to packaging for storage.

  3. Engineering report (conceptual design) PFP solution stabilization

    International Nuclear Information System (INIS)

    Witt, J.B.

    1997-01-01

    This Engineering Report (Conceptual Design) addresses remediation of the plutonium-bearing solutions currently in inventory at the Plutonium Finishing Plant (PFP). The recommendation from the Environmental Impact Statement (EIS) is that the solutions be treated thermally and stabilized as a solid for long term storage. For solutions which are not discardable, the baseline plan is to utilize a denitration process to stabilize the solutions prior to packaging for storage

  4. PLUTONIUM FINISHING PLANT (PFP) SUB-GRADE EE/CA EVALUATION OF ALTERNATIVES: A NEW MODEL

    International Nuclear Information System (INIS)

    HOPKINS, A.M.

    2007-01-01

    An engineering evaluation/cost analysis (EE/CA) was performed at the Hanford Site's Plutonium Finishing Plant (PFP). The purpose of the EVCA was to identify the sub-grade items to be evaluated; determine the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA) hazardous substances through process history and available data; evaluate these hazards; and as necessary, identify the available alternatives to reduce the risk associated with the contaminants. The sub-grade EWCA considered four alternatives for an interim removal action: (1) No Action; (2) Surveillance and Maintenance (S and M); (3) Stabilize and Leave in Place (Stabilization); and (4) Remove, Treat and Dispose (RTD). Each alternative was evaluated against the CERCLA criteria for effectiveness, implementability, and cost

  5. Interface Control Document Between the Double Shell Tanks (DST) System and the Plutonium Finishing Plan (PFP)

    International Nuclear Information System (INIS)

    MAY, T.H.

    1999-01-01

    This document identifies the requirements and responsibilities for all parties to support waste transfer from the Plutonium Finishing Plant (PFP) facility to the Double-Shell Tank (DST) System of the River Protection Project (RPP). This Interface Control Document (ICD) will not attempt to control the physical portion of this interface because the physical equipment making up this interface, and any associated interface requirements, are already in place, operational and governed by existing operating specifications and other documentation. The PFP and DST Systems have a direct physical interface (the waste transfer pipeline) that travels between the 241-2 Building (TK-D5) and DST SY-102 via 244-TX double-contained receiver tank (DCRT). The purpose of the ICD process is to formalize working agreements between the RPP DST System and organization/companies internal and external to RPP. This ICD has been developed as part of the requirements basis for design of the DST System to support the Phase I Privatization effort

  6. PFP vault operations containers for Plutonium Handling and Storage Critical Characteristics

    International Nuclear Information System (INIS)

    BONADIE, E.P.

    2000-01-01

    This document specifies the critical characteristics for containers procured for Plutonium Finishing Plant's (PFP's) Vault Operations system as required by HNF-PRO-268 and HNF-PRO-1819. These are the minimum specifications that the equipment must meet in order to perform its safety function

  7. History and stabilization of the Plutonium Finishing Plant (PFP) complex, Hanford Site

    Energy Technology Data Exchange (ETDEWEB)

    Gerber, M.S., Fluor Daniel Hanford

    1997-02-18

    The 231-Z Isolation Building or Plutonium Metallurgy Building is located in the Hanford Site`s 200 West Area, approximately 300 yards north of the Plutonium Finishing Plant (PFP) (234-5 Building). When the Hanford Engineer Works (HEW) built it in 1944 to contain the final step for processing plutonium, it was called the Isolation Building. At that time, HEW used a bismuth phosphate radiochemical separations process to make `AT solution,` which was then dried and shipped to Los Alamos, New Mexico. (AT solution is a code name used during World War II for the final HEW product.) The process was carried out first in T Plant and the 224-T Bulk Reduction Building and B Plant and the 224-B Bulk Reduction Building. The 224-T and -B processes produced a concentrated plutonium nitrate stream, which then was sent in 8-gallon batches to the 231-Z Building for final purification. In the 231-Z Building, the plutonium nitrate solution underwent peroxide `strikes` (additions of hydrogen peroxide to further separate the plutonium from its carrier solutions), to form the AT solution. The AT solution was dried and shipped to the Los Alamos Site, where it was made into metallic plutonium and then into weapons hemispheres.` The 231-Z Building began `hot` operations (operations using radioactive materials) with regular runs of plutonium nitrate on January 16, 1945.

  8. Plutonium Finishing Plant Transition Project mission analysis report

    International Nuclear Information System (INIS)

    Courson, D.B.

    1994-01-01

    This report defines the mission for the Plutonium Finishing Plant Transition Project (PFPTP) using a systems engineering approach. This mission analysis will be the basis for the functional analysis which will further define and break down the mission statement into all of the detailed functions required to accomplish the mission. The functional analysis is then used to develop requirements, allocate those requirements to functions, and eventually be used to design the system. This report: presents the problem which will be addressed, defines PFP Transition Project, defines the overall mission statement, describes the existing, initial conditions, defines the desired, final conditions, identifies the mission boundaries and external interfaces, identifies the resources required to carry out the mission, describes the uncertainties and risks, and discusses the measures which will be used to determine success

  9. PFP Emergency Lighting Study

    International Nuclear Information System (INIS)

    BUSCH, M.S.

    2000-01-01

    NFPA 101, section 5-9 mandates that, where required by building classification, all designated emergency egress routes be provided with adequate emergency lighting in the event of a normal lighting outage. Emergency lighting is to be arranged so that egress routes are illuminated to an average of 1.0 footcandle with a minimum at any point of 0.1 footcandle, as measured at floor level. These levels are permitted to drop to 60% of their original value over the required 90 minute emergency lighting duration after a power outage. The Plutonium Finishing Plant (PFP) has two designations for battery powered egress lights ''Emergency Lights'' are those battery powered lights required by NFPA 101 to provide lighting along officially designated egress routes in those buildings meeting the correct occupancy requirements. Emergency Lights are maintained on a monthly basis by procedure ZSR-12N-001. ''Backup Lights'' are battery powered lights not required by NFPA, but installed in areas where additional light may be needed. The Backup Light locations were identified by PFP Safety and Engineering based on several factors. (1) General occupancy and type of work in the area. Areas occupied briefly during a shiftly surveillance do not require backup lighting while a room occupied fairly frequently or for significant lengths of time will need one or two Backup lights to provide general illumination of the egress points. (2) Complexity of the egress routes. Office spaces with a standard hallway/room configuration will not require Backup Lights while a large room with several subdivisions or irregularly placed rooms, doors, and equipment will require Backup Lights to make egress safer. (3) Reasonable balance between the safety benefits of additional lighting and the man-hours/exposure required for periodic light maintenance. In some plant areas such as building 236-Z, the additional maintenance time and risk of contamination do not warrant having Backup Lights installed in all rooms

  10. Project Execution Plan Project 98L-EWW-460 Plutonium Stabilization and Handling DOE 98-D-453

    International Nuclear Information System (INIS)

    MCGRATH, G.M.

    2000-01-01

    This Project Execution Plan (PEP) describes the management methods and responsibilities of the project participants. Project W-460 is sufficiently large to warrant a stand alone PEP. This project specific PEP describes the relationships and responsibilities of the project team and identifies the technical, schedule, and cost baselines that have been established for the project. The Department of Energy (DOE), Hanford Works (Hanford), at Richland, Wa. currently does not have a system capable of stabilizing or packaging large quantities of plutonium-bearing solids to meet DOE technical standard DOE-STD-3013-99. This project will allow Hanford to meet this standard by installing stabilization and packaging equipment (SPE). The SPE is capable of stabilizing and packaging the current inventory of greater than 30 percent plutonium-bearing materials currently stored in the Plutonium Finishing Plant's (PFP) vaults into 3013 storage containers. The scope of this project is to procure and install the SPE via a Hanford contract and coordination with the Savannah River Site. In addition, the project will modify PFP vaults and upgrade the PFP Laboratory measurement systems. The Facility infrastructure will be modified to support the new SPE system and the new standardized storage container configuration

  11. Project Execution Plan Project 98L-EWW-460 Plutonium Stabilization and Handling DOE 98-D-453

    Energy Technology Data Exchange (ETDEWEB)

    HOLSTEIN, W.A.

    1999-08-01

    This Project Execution Plan (PEP) describes the management methods and responsibilities of the project participants. Project W-460 is sufficiently large to warrant a stand alone PEP. This project specific PEP describes the relationships and responsibilities of the project team and identifies the technical, schedule, and cost baselines that have been established for the project. The Department of Energy (DOE), Hanford Works (Hanford), at Richland Wa. currently does not have a system capable of stabilizing or packaging large quantities of plutonium-bearing solids to meet DOE technical standard DOE-STD-3013-96. This project will allow Hanford to meet this standard by installing stabilization and packaging equipment (SPE). The SPE is capable of stabilizing and packaging the current inventory of greater than 50 percent plutonium-bearing materials currently stored in the Plutonium Finishing Plant's (PFP) vaults into 3013 storage containers. The scope of this project is to procure and install the SPE via a Hanford contract and coordination with the Savannah River Site. In addition, the project will modify PFP vaults and upgrade the PFP Laboratory measurement systems. The Facility infrastructure will be modified to support the new SPE system and the new standardized storage container configuration.

  12. Project Execution Plan Project 98L-EWW-460 Plutonium Stabilization and Handling DOE 98-D-453

    Energy Technology Data Exchange (ETDEWEB)

    MCGRATH, G.M.

    2000-06-21

    This Project Execution Plan (PEP) describes the management methods and responsibilities of the project participants. Project W-460 is sufficiently large to warrant a stand alone PEP. This project specific PEP describes the relationships and responsibilities of the project team and identifies the technical, schedule, and cost baselines that have been established for the project. The Department of Energy (DOE), Hanford Works (Hanford), at Richland, Wa. currently does not have a system capable of stabilizing or packaging large quantities of plutonium-bearing solids to meet DOE technical standard DOE-STD-3013-99. This project will allow Hanford to meet this standard by installing stabilization and packaging equipment (SPE). The SPE is capable of stabilizing and packaging the current inventory of greater than 30 percent plutonium-bearing materials currently stored in the Plutonium Finishing Plant's (PFP) vaults into 3013 storage containers. The scope of this project is to procure and install the SPE via a Hanford contract and coordination with the Savannah River Site. In addition, the project will modify PFP vaults and upgrade the PFP Laboratory measurement systems. The Facility infrastructure will be modified to support the new SPE system and the new standardized storage container configuration.

  13. Operability test procedure for PFP wastewater sampling facility

    International Nuclear Information System (INIS)

    Hirzel, D.R.

    1995-01-01

    Document provides instructions for performing the Operability Test of the 225-WC Wastewater Sampling Station which monitors the discharge to the Treated Effluent Disposal Facility from the Plutonium Finishing Plant. This Operability Test Procedure (OTP) has been prepared to verify correct configuration and performance of the PFP Wastewater sampling system installed in Building 225-WC located outside the perimeter fence southeast of the Plutonium Finishing Plant (PFP). The objective of this test is to ensure the equipment in the sampling facility operates in a safe and reliable manner. The sampler consists of two Manning Model S-5000 units which are rate controlled by the Milltronics Ultrasonic flowmeter at manhole No.C4 and from a pH measuring system with the sensor in the stream adjacent to the sample point. The intent of the dual sampling system is to utilize one unit to sample continuously at a rate proportional to the wastewater flow rate so that the aggregate tests are related to the overall flow and thereby eliminate isolated analyses. The second unit will only operate during a high or low pH excursion of the stream (hence the need for a pH control). The major items in this OTP include testing of the Manning Sampler System and associated equipment including the pH measuring and control system, the conductivity monitor, and the flow meter

  14. Plutonium Finishing Plan (PFP) Treatment and Storage Unit Interim Status Closure Plan

    International Nuclear Information System (INIS)

    PRIGNANO, A.L.

    2000-01-01

    This document describes the planned activities and performance standards for closing the Plutonium Finishing Plant (PFP) Treatment and Storage Unit. The PFP Treatment and Storage Unit is located within the 234-52 Building in the 200 West Area of the Hanford Facility. Although this document is prepared based upon Title 40 Code of Federal Regulations (CFR), Part 265, Subpart G requirements, closure of the unit will comply with Washington Administrative Code (WAC) 173-303-610 regulations pursuant to Section 5.3 of the Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) Action Plan (Ecology et al. 1996). Because the PFP Treatment and Storage Unit manages transuranic mixed (TRUM) waste, there are many controls placed on management of the waste. Based on the many controls placed on management of TRUM waste, releases of TRUM waste are not anticipated to occur in the PFP Treatment and Storage Unit. Because the intention is to clean close the PFP Treatment and Storage Unit, postclosure activities are not applicable to this closure plan. To clean close the unit, it will be demonstrated that dangerous waste has not been left onsite at levels above the closure performance standard for removal and decontamination. If it is determined that clean closure is not possible or is environmentally impractical, the closure plan will be modified to address required postclosure activities. The PFP Treatment and Storage Unit will be operated to immobilize and/or repackage plutonium-bearing waste in a glovebox process. The waste to be processed is in a solid physical state (chunks and coarse powder) and will be sealed into and out of the glovebox in closed containers. The containers of immobilized waste will be stored in the glovebox and in additional permitted storage locations at PFP. The waste will be managed to minimize the potential for spills outside the glovebox, and to preclude spills from reaching soil. Containment surfaces will be maintained to ensure

  15. ALARA Design Review for the Resumption of the Plutonium Finishing Plant (PFP) Cementation Process Project Activities

    CERN Document Server

    Dayley, L

    2000-01-01

    The requirements for the performance of radiological design reviews are codified in 10CFR835, Occupational Radiation Protection. The basic requirements for the performance of ALARA design reviews are presented in the Hanford Site Radiological Control Manual (HSRCM). The HSRCM has established trigger levels requiring radiological reviews of non-routine or complex work activities. These requirements are implemented in site procedures HNF-PRO-1622 and 1623. HNF-PRO-1622 Radiological Design Review Process requires that ''radiological design reviews [be performed] of new facilities and equipment and modifications of existing facilities and equipment''. In addition, HNF-PRO-1623 Radiological Work Planning Process requires a formal ALARA Review for planned activities that are estimated to exceed 1 person-rem total Dose Equivalent (DE). The purpose of this review is to validate that the original design for the PFP Cementation Process ensures that the principles of ALARA (As Low As Reasonably Achievable) were included...

  16. Total Measurement Uncertainty for the Plutonium Finishing Plant (PFP) Segmented Gamma Scan Assay System

    CERN Document Server

    Fazzari, D M

    2001-01-01

    This report presents the results of an evaluation of the Total Measurement Uncertainty (TMU) for the Canberra manufactured Segmented Gamma Scanner Assay System (SGSAS) as employed at the Hanford Plutonium Finishing Plant (PFP). In this document, TMU embodies the combined uncertainties due to all of the individual random and systematic sources of measurement uncertainty. It includes uncertainties arising from corrections and factors applied to the analysis of transuranic waste to compensate for inhomogeneities and interferences from the waste matrix and radioactive components. These include uncertainty components for any assumptions contained in the calibration of the system or computation of the data. Uncertainties are propagated at 1 sigma. The final total measurement uncertainty value is reported at the 95% confidence level. The SGSAS is a gamma assay system that is used to assay plutonium and uranium waste. The SGSAS system can be used in a stand-alone mode to perform the NDA characterization of a containe...

  17. Collaborative Negotiations: A Successful Approach for Negotiation Compliance Milestones for the transition of the PFP Hanford Nuclear Reservation

    International Nuclear Information System (INIS)

    HOPKINS, A.M.

    2003-01-01

    The new approach to negotiations was termed collaborative (win-win) rather than positional (win-lose). Collaborative negotiations were conducted to establish milestones for the decommissioning of the Plutonium Finishing Plant, PFP

  18. Walkdown procedure: Seismic adequacy review of safety class 3 ampersand 4 commodities in 2736-Z ampersand ZB buildings at PFP facility

    International Nuclear Information System (INIS)

    Ocoma, E.C.

    1995-01-01

    Seismic evaluation of existing safety class (SC) 3 and non-SC 4 commodities at the Plutonium Finishing Plant (PFP) is integrated into an area walkdown program. Field walkdowns of potential PFP seismic deficiencies associated with structural failure and falling will be performed using the DOE SQUG/EPRI methodology. Potential proximity interactions are also addressed. Objective of the walkdown is to qualify as much of the equipment as practical and to identify candidates for further evaluation

  19. High knee abduction moments are common risk factors for patellofemoral pain (PFP) and anterior cruciate ligament (ACL) injury in girls: is PFP itself a predictor for subsequent ACL injury?

    Science.gov (United States)

    Myer, Gregory D; Ford, Kevin R; Di Stasi, Stephanie L; Foss, Kim D Barber; Micheli, Lyle J; Hewett, Timothy E

    2015-01-01

    Identifying risk factors for knee pain and anterior cruciate ligament (ACL) injury can be an important step in the injury prevention cycle. We evaluated two unique prospective cohorts with similar populations and methodologies to compare the incidence rates and risk factors associated with patellofemoral pain (PFP) and ACL injury. The 'PFP cohort' consisted of 240 middle and high school female athletes. They were evaluated by a physician and underwent anthropometric assessment, strength testing and three-dimensional landing biomechanical analyses prior to their basketball season. 145 of these athletes met inclusion for surveillance of incident (new) PFP by certified athletic trainers during their competitive season. The 'ACL cohort' included 205 high school female volleyball, soccer and basketball athletes who underwent the same anthropometric, strength and biomechanical assessment prior to their competitive season and were subsequently followed up for incidence of ACL injury. A one-way analysis of variance was used to evaluate potential group (incident PFP vs ACL injured) differences in anthropometrics, strength and landing biomechanics. Knee abduction moment (KAM) cut-scores that provided the maximal sensitivity and specificity for prediction of PFP or ACL injury risk were also compared between the cohorts. KAM during landing above 15.4 Nm was associated with a 6.8% risk to develop PFP compared to a 2.9% risk if below the PFP risk threshold in our sample. Likewise, a KAM above 25.3 Nm was associated with a 6.8% risk for subsequent ACL injury compared to a 0.4% risk if below the established ACL risk threshold. The ACL-injured athletes initiated landing with a greater knee abduction angle and a reduced hamstrings-to-quadriceps strength ratio relative to the incident PFP group. Also, when comparing across cohorts, the athletes who suffered ACL injury also had lower hamstring/quadriceps ratio than the players in the PFP sample (p15 Nm of knee abduction load

  20. Project Execution Plan Project 98L-EWW-460 Plutonium Stabilization and Handling DOE No. 98-D-453

    International Nuclear Information System (INIS)

    HOLSTEIN, W.A.

    1999-01-01

    This Project Execution Plan (PEP) describes the management methods and responsibilities of the project participants. Project W-460 is sufficiently large to warrant a stand alone PEP. This project specific PEP describes the relationships and responsibilities of the project team and identifies the technical, schedule, and cost baselines that have been established for the project. The Department of Energy (DOE), Hanford Works (Hanford), at Richland, WA., currently does not have a system capable of stabilizing or packaging large quantities of plutonium-bearing solids to meet DOE technical standard DOE-STD-3013-96. This project will allow Hanford to meet this standard by installing stabilization and packaging equipment (SPE). The SPE is capable of stabilizing and packaging the current inventory of greater than 50 percent plutonium-bearing materials currently stored in the Plutonium Finishing Plant's (PFP) vaults into 3013 storage containers. The scope of this project is to procure and install the SPE via a Hanford contract and coordination with the Savannah River Site. In addition, the project will modify PFP vaults and upgrade the PFP Laboratory measurement systems. The Facility infrastructure will be modified to support the new SPE system and the new standardized storage container configuration. Use of this document is described in the Project Hanford Policy and Procedure System under HNF-PRO-1999, Construction Program Conceptual Phase

  1. Plutonium Finishing Plant

    Data.gov (United States)

    Federal Laboratory Consortium — The Plutonium Finishing Plant, also known as PFP, represented the end of the line (the final procedure) associated with plutonium production at Hanford.PFP was also...

  2. PFP: Automated prediction of gene ontology functional annotations with confidence scores using protein sequence data.

    Science.gov (United States)

    Hawkins, Troy; Chitale, Meghana; Luban, Stanislav; Kihara, Daisuke

    2009-02-15

    Protein function prediction is a central problem in bioinformatics, increasing in importance recently due to the rapid accumulation of biological data awaiting interpretation. Sequence data represents the bulk of this new stock and is the obvious target for consideration as input, as newly sequenced organisms often lack any other type of biological characterization. We have previously introduced PFP (Protein Function Prediction) as our sequence-based predictor of Gene Ontology (GO) functional terms. PFP interprets the results of a PSI-BLAST search by extracting and scoring individual functional attributes, searching a wide range of E-value sequence matches, and utilizing conventional data mining techniques to fill in missing information. We have shown it to be effective in predicting both specific and low-resolution functional attributes when sufficient data is unavailable. Here we describe (1) significant improvements to the PFP infrastructure, including the addition of prediction significance and confidence scores, (2) a thorough benchmark of performance and comparisons to other related prediction methods, and (3) applications of PFP predictions to genome-scale data. We applied PFP predictions to uncharacterized protein sequences from 15 organisms. Among these sequences, 60-90% could be annotated with a GO molecular function term at high confidence (>or=80%). We also applied our predictions to the protein-protein interaction network of the Malaria plasmodium (Plasmodium falciparum). High confidence GO biological process predictions (>or=90%) from PFP increased the number of fully enriched interactions in this dataset from 23% of interactions to 94%. Our benchmark comparison shows significant performance improvement of PFP relative to GOtcha, InterProScan, and PSI-BLAST predictions. This is consistent with the performance of PFP as the overall best predictor in both the AFP-SIG '05 and CASP7 function (FN) assessments. PFP is available as a web service at http://dragon.bio.purdue.edu/pfp

  3. ASSESSING CHEMICAL HAZARDS AT THE PLUTONIUM FINISHING PLANT FOR PLANNING FUTURE DECONTAMINATION AND DECOMMISSIONING

    International Nuclear Information System (INIS)

    HOPKINS, A.M.; KLOS, D.B.; MINETT, M.J.

    2007-01-01

    This paper documents the fiscal year (FY) 2006 assessment to evaluate potential chemical and radiological hazards associated with vessels and piping in the former plutonium process areas at Hanford's Plutonium Finishing Plant (PFP). Evaluations by PFP engineers as design authorities for specific systems and other subject-matter experts were conducted to identify the chemical hazards associated with transitioning the process areas for the long-term layup of PFP before its eventual final decontamination and decommissioning (D and D). D and D activities in the main process facilities were suspended in September 2005 for a period of between 5 and 10 years. A previous assessment conducted in FY 2003 found that certain activities to mitigate chemical hazards could be deferred safely until the D and D of PFP, which had been scheduled to result in a slab-on-grade condition by 2009. As a result of necessary planning changes, however, D and D activities at PFP will be delayed until after the 2009 time frame. Given the extended project and plant life, it was determined that a review of the plant chemical hazards should be conducted. This review to determine the extended life impact of chemicals is called the ''Plutonium Finishing Plant Chemical Hazards Assessment, FY 2006''. This FY 2006 assessment addresses potential chemical and radiological hazard areas identified by facility personnel and subject-matter experts who reevaluated all the chemical systems (items) from the FY 2003 assessment. This paper provides the results of the FY 2006 chemical hazards assessment and describes the methodology used to assign a hazard ranking to the items reviewed

  4. Plutonium Finishing Plant safety evaluation report

    International Nuclear Information System (INIS)

    1995-01-01

    The Plutonium Finishing Plant (PFP) previously known as the Plutonium Process and Storage Facility, or Z-Plant, was built and put into operation in 1949. Since 1949 PFP has been used for various processing missions, including plutonium purification, oxide production, metal production, parts fabrication, plutonium recovery, and the recovery of americium (Am-241). The PFP has also been used for receipt and large scale storage of plutonium scrap and product materials. The PFP Final Safety Analysis Report (FSAR) was prepared by WHC to document the hazards associated with the facility, present safety analyses of potential accident scenarios, and demonstrate the adequacy of safety class structures, systems, and components (SSCs) and operational safety requirements (OSRs) necessary to eliminate, control, or mitigate the identified hazards. Documented in this Safety Evaluation Report (SER) is DOE's independent review and evaluation of the PFP FSAR and the basis for approval of the PFP FSAR. The evaluation is presented in a format that parallels the format of the PFP FSAR. As an aid to the reactor, a list of acronyms has been included at the beginning of this report. The DOE review concluded that the risks associated with conducting plutonium handling, processing, and storage operations within PFP facilities, as described in the PFP FSAR, are acceptable, since the accident safety analyses associated with these activities meet the WHC risk acceptance guidelines and DOE safety goals in SEN-35-91

  5. DEACTIVATION AND DECOMMISSIONING ENVIRONMENTAL STRATEGY FOR THE PLUTONIUM FINISHING PLANT COMPLEX, HANFORD NUCLEAR RESERVATION

    International Nuclear Information System (INIS)

    Hopkins, A.M.; Heineman, R.; Norton, S.; Miller, M.; Oates, L.

    2003-01-01

    Maintaining compliance with environmental regulatory requirements is a significant priority in successful completion of the Plutonium Finishing Plant (PFP) Nuclear Material Stabilization (NMS) Project. To ensure regulatory compliance throughout the deactivation and decommissioning of the PFP complex, an environmental regulatory strategy was developed. The overall goal of this strategy is to comply with all applicable environmental laws and regulations and/or compliance agreements during PFP stabilization, deactivation, and eventual dismantlement. Significant environmental drivers for the PFP Nuclear Material Stabilization Project include the Tri-Party Agreement; the Resource Conservation and Recovery Act of 1976 (RCRA); the Comprehensive Environmental Response, Compensation and Liability Act of 1980 (CERCLA); the National Environmental Policy Act of 1969 (NEPA); the National Historic Preservation Act (NHPA); the Clean Air Act (CAA), and the Clean Water Act (CWA). Recent TPA negotiation s with Ecology and EPA have resulted in milestones that support the use of CERCLA as the primary statutory framework for decommissioning PFP. Milestones have been negotiated to support the preparation of Engineering Evaluations/Cost Analyses for decommissioning major PFP buildings. Specifically, CERCLA EE/CA(s) are anticipated for the following scopes of work: Settling Tank 241-Z-361, the 232-Z Incinerator, , the process facilities (eg, 234-5Z, 242, 236) and the process facility support buildings. These CERCLA EE/CA(s) are for the purpose of analyzing the appropriateness of the slab-on-grade endpoint Additionally, agreement was reached on performing an evaluation of actions necessary to address below-grade structures or other structures remaining after completion of the decommissioning of PFP. Remaining CERCLA actions will be integrated with other Central Plateau activities at the Hanford site

  6. Plan for the Startup of HA-21I Furnace Operations at the Plutonium Finishing Plant (PFP)

    International Nuclear Information System (INIS)

    WILLIS, H.T.

    2000-01-01

    Achievement of Thermal Stabilization mission elements require the installation and startup of three additional muffle furnaces for the thermal stabilization of plutonium and plutonium bearing materials at the Plutonium Finishing Plant (PFP). The release to operate these additional furnaces will require an Activity Based Startup Review. The conduct of the Activity Based Startup Review (ABSR) was approved by Fluor Daniel Hanford on October 15, 1999. This plan has been developed with the objective of identifying those activities needed to guide the controlled startup of five furnaces from authorization to unrestricted operations by adding the HA-211 furnaces in an orderly and safe manner after the approval to Startup has been given. The Startup Plan provides a phased approach that bridges the activities between the completion of the Activity Based Startup Review authorizing the use of the three additional furnaces and the unrestricted operation of the five thermal stabilization muffle furnaces. The four phases are: (1) the initiation of five furnace operations using three empty (simulated full) boat charges from HA-211 and two full charges from HC-21C; (2) three furnace operations (one full charge from HA-211 and two full charges from HC-21C); (3) four furnace operations (two full charges from HA-211 and two full charges from HC-21C); and (4) integrated five furnace operations and unrestricted operations. Phase 1 of the Plan will be considered as the cold runs. This Plan also provides management oversight and administrative controls that are to be implemented until unrestricted operations are authorized. It also provides a formal review process for ensuring that all preparations needed for full five furnace operations are completed and formally reviewed prior to proceeding to the increased activity levels associated with five furnace operations. Specific objectives include: (1) To ensure that activities are conducted in a safe manner. (2) To provide supplemental

  7. Genotypic and phenotypic diversity in populations of plant-probiotic Pseudomonas spp. colonizing roots

    Science.gov (United States)

    Picard, Christine; Bosco, Marco

    2008-01-01

    Several soil microorganisms colonizing roots are known to naturally promote the health of plants by controlling a range of plant pathogens, including bacteria, fungi, and nematodes. The use of theses antagonistic microorganisms, recently named plant-probiotics, to control plant-pathogenic fungi is receiving increasing attention, as they may represent a sustainable alternative to chemical pesticides. Many years of research on plant-probiotic microorganisms (PPM) have indicated that fluorescent pseudomonads producing antimicrobial compounds are largely involved in the suppression of the most widespread soilborne pathogens. Phenotype and genotype analysis of plant-probiotic fluorescent pseudomonads (PFP) have shown considerable genetic variation among these types of strains. Such variability plays an important role in the rhizosphere competence and the biocontrol ability of PFP strains. Understanding the mechanisms by which genotypic and phenotypic diversity occurs in natural populations of PFP could be exploited to choose those agricultural practices which best exploit the indigenous PFP populations, or to isolate new plant-probiotic strains for using them as inoculants. A number of different methods have been used to study diversity within PFP populations. Because different resolutions of the existing microbial diversity can be revealed depending on the approach used, this review first describes the most important methods used for the assessment of fluorescent Pseudomonas diversity. Then, we focus on recent data relating how differences in genotypic and phenotypic diversity within PFP communities can be attributed to geographic location, climate, soil type, soil management regime, and interactions with other soil microorganisms and host plants. It becomes evident that plant-related parameters exert the strongest influence on the genotypic and phenotypic variations in PFP populations.

  8. THE DEACTIVATION, DECONTAMINATION AND DECOMMISSIONING OF THE PLUTONIUM FINISHING PLANT, A FORMER PLUTONIUM PROCESSING FACILITY AT DOE'S HANFORD SITE

    International Nuclear Information System (INIS)

    CHARBONEAU, S.L.

    2006-01-01

    The Plutonium Finishing Plant (PFP) was constructed as part of the Manhattan Project during World War II. The Manhattan Project was developed to usher in the use of nuclear weapons to end the war. The primary mission of the PFP was to provide plutonium used as special nuclear material (SNM) for fabrication of nuclear devices for the war effort. Subsequent to the end of World War II, the PFP's mission expanded to support the Cold War effort through plutonium production during the nuclear arms race and later the processing of fuel grade mixed plutonium-uranium oxide to support DOE's breeder reactor program. In October 1990, at the close of the production mission for PFP, a shutdown order was prepared by the Department of Energy (DOE) in Washington,; DC--and issued to the Richland DOE field office. Subsequent to the shutdown order, a team from the Defense Nuclear Facilities Safety Board (DNFSB) analyzed the hazards at PFP associated with the continued storage of certain forms of plutonium solutions and solids. The assessment identified many discrete actions that were required to stabilize the different plutonium forms into stable form and repackage the material in high integrity containers. These actions were technically complicated and completed as part of the PFP nuclear material stabilization project between 1995 and early 2005. The completion of the stabilization project was a necessary first step in deactivating PFP. During stabilization, DOE entered into negotiations with the U.S. Environmental Protection Agency (EPA) and the State of Washington and established milestones for the Deactivation and Decommissioning (DandD) of the PFP. The DOE and its contractor, Fluor Hanford (Fluor), have made great progress in deactivating, decontaminating and decommissioning the PFP at the Hanford Site as detailed in this paper. Background information covering the PFP DandD effort includes descriptions of negotiations with the State of Washington concerning consent

  9. Evaluation of Need and Location for a Thermogravimetric Analyzer in the Plutonium Finishing Plant (PFP) Materials Stabilization

    International Nuclear Information System (INIS)

    WILLIS, H.T.

    2000-01-01

    This plan provides an analysis for locating a TGA to support PFP Thermal Stabilization processes. The scope of this document is to evaluate the need for, and location for, installation of a TGA system as a supplement to the SFE equipment for moisture measurement in pure oxides. A location assessment for the SFE equipment was previously performed (HNF 1999). Based on that assessment, co-location of the TGA system with the SFE system is the preferred option. This would enable thermally stabilized material to be analyzed for residual moisture by either the TGA system or SFE system or both This evaluation considers glovebox locations in the PFP 234-52 Building Analytical Laboratory or operating areas for the installation of the TGA system and it's supporting equipment. This evaluation considers using existing gloveboxes along with an alternative of adding a new glovebox to existing process lines. The location evaluation criteria focuses mainly on glovebox size, with qualitative consideration of relative cost and schedule impacts associated with system implementation, radiological control, and interaction with other laboratory operations and processes. In addition, the possible co-location of a TGA furnace system with the SFE system was considered

  10. Time and Temperature Test Results for PFP Thermal Stabilization Furnaces

    International Nuclear Information System (INIS)

    COMPTON, J.A.

    2000-01-01

    The national standard for plutonium storage acceptability (standard DOE-STD-3013-99, generally known as ''the 3013 standard'') has been revised to clarify the requirement for processes that will produce acceptable storage materials. The 3013 standard (Reference 1) now states that ''Oxides shall be stabilized by heating the material in an oxidizing atmosphere to a Material Temperature of at least 950 C (1742 F) for not less than 2 hours.'' The process currently in use for producing stable oxides for storage at the Plutonium Finishing Plant (PFP) heats a furnace atmosphere to 1000 C and holds it there for 2 hours. The temperature of the material being stabilized is not measured directly during this process. The Plutonium Process Support Laboratories (PPSL) were requested to demonstrate that the process currently in use at PFP is an acceptable method of producing stable plutonium dioxide consistently. A spare furnace identical to the production furnaces was set up and tested under varying conditions with non-radioactive surrogate materials. Reference 2 was issued to guide the testing program. The process currently in use at the PFP for stabilizing plutonium-bearing powders was shown to heat all the material in the furnace to at least 950 C for at least 2 hours. The current process will work for (1) relatively pure plutonium dioxide, (2) dioxide powders mixed with up to 20 weight percent magnesium oxide, and (3) dioxide powders with up to 11 weight percent magnesium oxide and 20 weight percent magnesium nitrate hexahydrate. Time and temperature data were also consistent with a successful demonstration for a mixture containing 10 weight percent each of sodium and potassium chloride; however, the molten chloride salts destroyed the thermocouples in the powder and temperature data were unavailable for part of that run. These results assume that the current operating limits of no more than 2500 grams per furnace charge and a powder height of no more than 1.5 inches remain

  11. Preliminary safety analysis report for project 89-GEB-610 Plutonium Finishing Plant instrumentation upgrade. Revision 1

    International Nuclear Information System (INIS)

    Huber, T.E.

    1995-01-01

    This document consists of an analysis of the MICON system upgrade. This project shall install a Micon Co. distributed process monitor and control system with Sparc Sun workstation operator interfaces. The Sparc workstations are housed in consoles custom designed to human factors specifications. The distributed control system (DCS) shall have the installed capacity to monitor and control all related instruments and equipment presently connected to the panels in the PFP Power Control Room 321A as listed in the input/output list. This also includes all devices monitored and controlled by the 2736-ZB Allen Bradley programmable logic controller. The system has since assumed the control and monitoring responsibilities for Projects B- 680H ''Low Level Waste Treatment Facility'' and C-031H ''PFP Liquid Effluent Facilities''. Part of the new en's change area in Building 234-5ZA, Room 712, has been remodeled to house two consoles and one supervisor console. Local control units containing the microprocontrollers and the input/output interface circuit boards shall be wired to the instrumentation and controlled equipment. These units communicate with the Sparc workstations via a redundant data communications highway and shall be strategic, throughout the PFP facility. The DCS has already been purchased from Micon Co., located in Houston Texas, presently on site

  12. Definition and means of maintaining the criticality detectors and alarms portion of the PFP safety envelope

    International Nuclear Information System (INIS)

    White, W.F.

    1997-01-01

    The Criticality Alarm System (CAS) provides continuous detection for high radiation (criticality) events and automatically initiates an evacuation signal to affected personnel. The Safety Envelope (SE) for PFP includes the necessary equipment and the required procedures to ensure the CAS is capable of performing its intended function. This document provides the definition and means of maintaining the SE for PFP related to the CAS. This document also identifies and provides a justification for those portions of the CAS excluded from the PFP Safety Envelope

  13. In-depth performance evaluation of PFP and ESG sequence-based function prediction methods in CAFA 2011 experiment

    Directory of Open Access Journals (Sweden)

    Chitale Meghana

    2013-02-01

    Full Text Available Abstract Background Many Automatic Function Prediction (AFP methods were developed to cope with an increasing growth of the number of gene sequences that are available from high throughput sequencing experiments. To support the development of AFP methods, it is essential to have community wide experiments for evaluating performance of existing AFP methods. Critical Assessment of Function Annotation (CAFA is one such community experiment. The meeting of CAFA was held as a Special Interest Group (SIG meeting at the Intelligent Systems in Molecular Biology (ISMB conference in 2011. Here, we perform a detailed analysis of two sequence-based function prediction methods, PFP and ESG, which were developed in our lab, using the predictions submitted to CAFA. Results We evaluate PFP and ESG using four different measures in comparison with BLAST, Prior, and GOtcha. In addition to the predictions submitted to CAFA, we further investigate performance of a different scoring function to rank order predictions by PFP as well as PFP/ESG predictions enriched with Priors that simply adds frequently occurring Gene Ontology terms as a part of predictions. Prediction accuracies of each method were also evaluated separately for different functional categories. Successful and unsuccessful predictions by PFP and ESG are also discussed in comparison with BLAST. Conclusion The in-depth analysis discussed here will complement the overall assessment by the CAFA organizers. Since PFP and ESG are based on sequence database search results, our analyses are not only useful for PFP and ESG users but will also shed light on the relationship of the sequence similarity space and functions that can be inferred from the sequences.

  14. Plutonium Finishing Plant Treatment and Storage Unit Dangerous Waste Training Plan

    International Nuclear Information System (INIS)

    ENTROP, G.E.

    2000-01-01

    The training program for personnel performing waste management duties pertaining to the Plutonium Finishing Plant (PFP) Treatment and Storage Unit is governed by the general requirements established in the Plutonium Finishing Plant Dangerous Waste Training Plan (PFP DWTP). The PFP Treatment and Storage Unit DWTP presented below incorporates all of the components of the PFP DWTP by reference. The discussion presented in this document identifies aspects of the training program specific to the PFP Treatment and Storage Unit. The training program includes specifications for personnel instruction through both classroom and on-the-job training. Training is developed specific to waste management duties. Hanford Facility personnel directly involved with the PFP Treatment and Storage Unit will receive training to container management practices, spill response, and emergency response. These will include, for example, training in the cementation process and training pertaining to applicable elements of WAC 173-303-330(1)(d). Applicable elements from WAC 173-303-330(1)(d) for the PFP Treatment and Storage Unit include: procedures for inspecting, repairing, and replacing facility emergency and monitoring equipment; communications and alarm systems; response to fires or explosions; and shutdown of operations

  15. Maintenance implementation plan for the Plutonium Finishing Plant. Revision 3

    International Nuclear Information System (INIS)

    Meldrom, C.A.

    1996-03-01

    This document outlines the Maintenance Implementation Plan (MIP) for the Plutonium Finishing Plant (PFP) located at the Hanford site at Richland, Washington. This MIP describes the PFP maintenance program relative to DOE order 4330.4B. The MIP defines the key actions needed to meet the guidelines of the Order to produce a cost-effective and efficient maintenance program. A previous report identified the presence of significant quantities of Pu-bearing materials within PFP that pose risks to workers. PFP's current mission is to develop, install and operate processes which will mitigate these risks. The PFP Maintenance strategy is to equip the facility with systems and equipment able to sustain scheduled PFP operations. The current operating run is scheduled to last seven years. Activities following the stabilization operation will involve an Environmental Impact Statement (EIS) to determine future plant activities. This strategy includes long-term maintenance of the facility for safe occupancy and material storage. The PFP maintenance staff used the graded approach to dictate the priorities of the improvement and upgrade actions identified in Chapter 2 of this document. The MIP documents PFP compliance to the DOE 4330.4B Order. Chapter 2 of the MIP follows the format of the Order in addressing the eighteen elements. As this revision is a total rewrite, no sidebars are included to highlight changes

  16. Project B-610 instrument data base. Revision 6

    International Nuclear Information System (INIS)

    Silvan, G.R.

    1994-01-01

    The following technical information document contains the published data base listing for the instrumentation to be connected into the new MICON distributed control computer. Project B-610 PFP Instrument Upgrade (PFP HVAC Control Room Upgrade) will install the MICON system in PFP and provide for a new control room at the present site of the new SWP change room EDT-150750 1/11/93

  17. Engineering work plan for PFP criticality alarm panel first unit re-build

    International Nuclear Information System (INIS)

    Clem, W.E.

    1994-01-01

    This document describes the first step in increasing the quality, reliability, and ease of maintenance of the nine Criticality Alarm Panels (CAP) at PFP. Development control practices and guidelines of WHC-CM-6-1, EP-2.4 and WHC-IP-1026, EPG-2.4 are applied to develop a prototype of a replacement Criticality Alarm Panel (CAP) with facility-use potential. During the development of the prototype CAP, the design requirements of all of PFP's nine CAPs are considered to develop standardized hardware and detailed design drawings that are tailored to PFP maintenance needs. Increased quality and reliability is achieved through quality hardware, proven technology and design techniques, and the use of the Class 1E workmanship standards of WHC-CM-8-1. The end result of the work described by this work plan is a verified/read-to-install replacement for CAP Z4 and verified/released H-2 drawings that are formatted such that they can easily be replicated when producing design drawings for the other eight CAPs

  18. Definition and means of maintaining the process vacuum liquid detection interlock systems portion of the PFP safety envelope

    International Nuclear Information System (INIS)

    LINTHO, J.E.

    2003-01-01

    The purpose of this document is to record the technical evaluation of the Technical Safety Requirements described in the Plutonium Finishing Plant (PFP) Safety Technical Requirements, HNF-SD-CP-OSR-010/Rev.1, Section 3.1.1, ''Criticality Prevention System.'' This document also defines the Safety Envelope (SE) for the liquid detection interlock system in the Process Vacuum System. The SE is derived FR-om information in the Plutonium Finishing Plant Final Safety Analysis Report (PFP FSAR), HNF-SD-CP-SAR-021, Rev 4, and the Criticality Safety Analysis Report (CSAR) for the 26-inch Hg Vacuum System, WHC-SD-SQA-CSA-20159, Rev 0-A. This document, with its appendices, provides the following: (1) The system functional requirements for determining system operability (Section 3). (2) Evaluations of equipment to determine the safety envelope boundary for the system (Section 4 list of SE boundary drawings). (3) A list of the safety envelope equipment (Appendix B). (4) Functional requirements for the individual safety envelope equipment, including appropriate set points and process parameters (Section 4). (5) A list of the operational and surveillance procedures necessary to operate and maintain the system equipment within the safety envelope (Sections 5 and 6 and Appendix A)

  19. A New Property of Conjugated Polymer PFP: Catalytic Degradation of Methylene Blue Aqueous Solution

    Institute of Scientific and Technical Information of China (English)

    2005-01-01

    A new property of conjugated polymer poly(furancarbinol-co-phenol)(PFP) was studied.The target copolymer was used as a catalyst after proper heating treatment. And dye methylene blue (MB) could be fully degraded and largely mineralized on PFP, under natural light or even in dark, in a few minutes. Furthermore, the catalytic activity could be preserved after several runs and the catalyst was readily separated. The effect of calcination temperature was also observed.

  20. Test plan for N2 HEPA filters assembly shop stock used on PFP E4 exhaust system

    International Nuclear Information System (INIS)

    DICK, J.D.

    1999-01-01

    At Plutonium Finishing Plant (PFP) and Plutonium Reclamation Facility (PRF) Self-contained HEPA filters, encased in wooden frames and boxes, are installed in the E4 Exhaust Ventilation System to provide confinement of radioactive releases to the environment and confinement of radioactive contamination within designated zones inside the facility. Recently during the routine testing in-leakage was discovered downstream of the Self-contained HEPA filters boxes. This Test Plan describes the approach to conduct investigation of the root causes for the in-leakage of HEPA filters

  1. Plutonium vulnerability issues at Hanford's Plutonium Finishing Plant

    International Nuclear Information System (INIS)

    Feldt, E.; Templeton, D.W.; Tholen, E.

    1995-01-01

    The Plutonium Finishing Plant (PFP) at the Hanford, Washington Site was operated to produce plutonium (Pu) metal and oxide for national defense purposes. Due to the production requirements and methods utilized to meet national needs and the abrupt shutdown of the plant in the late 1980s, the plant was left in a condition that poses a risk of radiation exposure to plant workers, of accidental radioactive material release to the environment, and of radiation exposure to the public. In early 1994, an Environmental Impact Statement (EIS) to determine the best methods for cleaning out and stabilizing Pu materials in the PFP was started. While the EIS is being prepared, a number of immediate actions have been completed or are underway to significantly reduce the greatest hazards in the PFP. Recently, increased attention his been paid to Pu risks at Department of Energy (DOE) facilities resulting in the Department-wide Plutonium Vulnerability Assessment and a recommendation by the Defense Nuclear Facilities Safety Board (DNFSB) for DOE to develop integrated plans for managing its nuclear materials

  2. 1999 Annual Cathodic Protection Survey Report for PFP

    International Nuclear Information System (INIS)

    BOWMAN, T.J.

    2000-01-01

    This cathodic protection (CP) report documents the results of the 1999 annual CP survey of the underground piping within PFP property. An annual survey of CP systems is required by Washington Administrative Code (WAC). A spreadsheet to document the 1999 annual survey polarization data is included in this report. Graphs are included to trend the cathodic voltages and the polarization voltages at each test station on PFP property. The trending spans from 1994 to 1999. Graphs are also included to trend voltage and amperage outputs of each rectifier during the annual surveys. During the annual survey, resistance testing between the underground piping was conducted at each test station. The testing showed that all piping (with test leads into the test stations) was continuous with every pipe represented in the test stations. The resistance data is not documented in this report but can be accessed in work package 22-99-01003. During the annual survey, the wiring configurations of anode junction boxes AJB(R45-1) and AJB(45-1) were documented. The sketches can be accessed from the JCS work record of work package 22-99-01003. Analysis, conclusions, and recommendations of the 1999 annual CP survey results are included in this report

  3. Disposal of TRU Waste from the PFP in pipe overpack containers to WIPP Including New Security Requirements

    International Nuclear Information System (INIS)

    HOPKINS, A.M.

    2003-01-01

    The Department of Energy is responsible for the safe management and cleanup of the DOE complex. As part of the cleanup and closure of the Plutonium Finishing Plant (PFP) located on the Hanford site, the nuclear material inventory was reviewed to determine the appropriate disposition path. Based on the nuclear material characteristics, the material was designated for stabilization and packaging for long term storage and transfer to the Savannah River Site, or a decision for discard was made. The discarded material was designated as waste material and slated for disposal to the Waste Isolation Pilot Plant (WIPP). Prior to preparing any residue wastes for disposal at the WIPP, several major activities need to be completed. As detailed a processing history as possible of the material including origin of the waste must be researched and documented. A technical basis for termination of safeguards on the material must be prepared and approved. Utilizing process knowledge and processing history, the material must be characterized, sampling requirements determined, acceptable knowledge package and waste designation completed prior to disposal. All of these activities involve several organizations including the contractor, DOE, state representatives and other regulators such as EPA. At PFP, a process has been developed for meeting the many, varied requirements and successfully used to prepare several residue waste streams including Rocky Flats incinerator ash, hanford incinerator ash and Sand, Slag and Crucible (SS and C) material for disposal. These waste residues are packed into Pipe Overpack Containers for shipment to the WIPP

  4. Characterization of past and present solid waste streams from the plutonium finishing plant

    Energy Technology Data Exchange (ETDEWEB)

    Duncan, D.R.; Mayancsik, B.A. [Westinghouse Hanford Co., Richland, WA (United States); Pottmeyer, J.A.; Vejvoda, E.J.; Reddick, J.A.; Sheldon, K.M.; Weyns, M.I. [Los Alamos Technical Associates, Kennewick, WA (United States)

    1993-02-01

    During the next two decades the transuranic (TRU) wastes now stored in the burial trenches and storage facilities at the Hanford Site are to be retrieved, processed at the Waste Receiving and Processing (WRAP) Facility, and shipped to the Waste Isolation Pilot Plant (WIPP) near Carlsbad, New Mexico for final disposal. Over 50% of the TRU waste to be retrieved for shipment to the WIPP has been generated at the Plutonium Finishing Plant (PFP), also known as the Plutonium Processing and Storage Facility and Z Plant. The purpose of this report is to characterize the radioactive solid wastes generated by the PFP since its construction in 1947 using process knowledge, existing records, and history-obtained from interviews. The PFP is currently operated by Westinghouse Hanford Company (WHC) for the US Department of Energy (DOE).

  5. Characterization of past and present solid waste streams from the plutonium finishing plant

    International Nuclear Information System (INIS)

    Duncan, D.R.; Mayancsik, B.A.; Pottmeyer, J.A.; Vejvoda, E.J.; Reddick, J.A.; Sheldon, K.M.; Weyns, M.I.

    1993-02-01

    During the next two decades the transuranic (TRU) wastes now stored in the burial trenches and storage facilities at the Hanford Site are to be retrieved, processed at the Waste Receiving and Processing (WRAP) Facility, and shipped to the Waste Isolation Pilot Plant (WIPP) near Carlsbad, New Mexico for final disposal. Over 50% of the TRU waste to be retrieved for shipment to the WIPP has been generated at the Plutonium Finishing Plant (PFP), also known as the Plutonium Processing and Storage Facility and Z Plant. The purpose of this report is to characterize the radioactive solid wastes generated by the PFP since its construction in 1947 using process knowledge, existing records, and history-obtained from interviews. The PFP is currently operated by Westinghouse Hanford Company (WHC) for the US Department of Energy (DOE)

  6. Evaluation of the Magnesium Hydroxide Treatment Process for Stabilizing PFP Plutonium/Nitric Acid Solutions

    Energy Technology Data Exchange (ETDEWEB)

    Gerber, Mark A.; Schmidt, Andrew J.; Delegard, Calvin H.; Silvers, Kurt L.; Baker, Aaron B.; Gano, Susan R.; Thornton, Brenda M.

    2000-09-28

    This document summarizes an evaluation of the magnesium hydroxide [Mg(OH)2] process to be used at the Hanford Plutonium Finishing Plant (PFP) for stabilizing plutonium/nitric acid solutions to meet the goal of stabilizing the plutonium in an oxide form suitable for storage under DOE-STD-3013-99. During the treatment process, nitric acid solutions bearing plutonium nitrate are neutralized with Mg(OH)2 in an air sparge reactor. The resulting slurry, containing plutonium hydroxide, is filtered and calcined. The process evaluation included a literature review and extensive laboratory- and bench-scale testing. The testing was conducted using cerium as a surrogate for plutonium to identify and quantify the effects of key processing variables on processing time (primarily neutralization and filtration time) and calcined product properties.

  7. COLLABORATIVE NEGOTIATIONS A SUCCESSFUL APPROACH FOR NEGOTIATING COMPLIANCE MILESTONES FOR THE TRANSITION OF THE PLUTONIUM FINISHING PLANT (PFP), HANFORD NUCLEAR RESERVATION, AND HANFORD, WASHINGTON

    International Nuclear Information System (INIS)

    Hebdon, J.; Yerxa, J.; Romine, L.; Hopkins, AM; Piippo, R.; Cusack, L.; Bond, R.; Wang, Oliver; Willis, D.

    2003-01-01

    The Hanford Nuclear Reservation is a former U. S. Department of Energy Defense Production Site. The site is currently listed on the National Priorities List of the Comprehensive Environmental Response Compensation and Liability Act of 1980 (CERCLA) and is undergoing cleanup and environmental restoration. The PFP is a former Plutonium metal production facility. The operating mission of the PFP ended with a DOE Headquarters shutdown letter in October of 1996. Generally, the receipt of a shutdown letter initiates the start of Transition (as the first step of Decommissioning) of a facility. The Hanford site is subject to the Hanford Federal Facilities Compliance Act and Consent Order (HFFCCO), an order on consent signed by the DOE, the U. S. Environmental Protection Agency, (EPA) and the Washington Department of Ecology (WDOE). Under the HFFCCO, negotiations for transition milestones begin within six months after the issuance of a shutdown order. In the case of the PFP, the Nuclear Materials disposition and stabilization activities, a DOE responsibility, were necessary as precursor activities to Transition. This situation precipitated a crisis in the negotiations between the agencies, and formal negotiations initiated in 1997 ended in failure. The negotiations reached impasse on several key regulatory and operational issues. The 1997 negotiation was characterized by a strongly positional style. DOE and the regulatory personnel took hard lines early in the negotiations and were unable to move to resolution of key issues after a year and a half. This resulted in unhappy stakeholders, poor publicity and work delays as well as wounded relationships between DOE and the regulatory community. In the 2000-2001 PFP negotiations, a completely different approach was suggested and eventually initiated: Collaborative Negotiations. The collaborative negotiation style resulted in agreement between the agencies on all key issues within 6 months of initiation. All parties were very

  8. COLLABORATIVE NEGOTIATIONS A SUCCESSFUL APPROACH FOR NEGOTIATING COMPLIANCE MILESTONES FOR THE TRANSITION OF THE PLUTONIUM FINISHING PLANT (PFP), HANFORD NUCLEAR RESERVATION, AND HANFORD, WASHINGTON

    Energy Technology Data Exchange (ETDEWEB)

    Hebdon, J.; Yerxa, J.; Romine, L.; Hopkins, AM; Piippo, R.; Cusack, L.; Bond, R.; Wang, Oliver; Willis, D.

    2003-02-27

    The Hanford Nuclear Reservation is a former U. S. Department of Energy Defense Production Site. The site is currently listed on the National Priorities List of the Comprehensive Environmental Response Compensation and Liability Act of 1980 (CERCLA) and is undergoing cleanup and environmental restoration. The PFP is a former Plutonium metal production facility. The operating mission of the PFP ended with a DOE Headquarters shutdown letter in October of 1996. Generally, the receipt of a shutdown letter initiates the start of Transition (as the first step of Decommissioning) of a facility. The Hanford site is subject to the Hanford Federal Facilities Compliance Act and Consent Order (HFFCCO), an order on consent signed by the DOE, the U. S. Environmental Protection Agency, (EPA) and the Washington Department of Ecology (WDOE). Under the HFFCCO, negotiations for transition milestones begin within six months after the issuance of a shutdown order. In the case of the PFP, the Nuclear Materials disposition and stabilization activities, a DOE responsibility, were necessary as precursor activities to Transition. This situation precipitated a crisis in the negotiations between the agencies, and formal negotiations initiated in 1997 ended in failure. The negotiations reached impasse on several key regulatory and operational issues. The 1997 negotiation was characterized by a strongly positional style. DOE and the regulatory personnel took hard lines early in the negotiations and were unable to move to resolution of key issues after a year and a half. This resulted in unhappy stakeholders, poor publicity and work delays as well as wounded relationships between DOE and the regulatory community. In the 2000-2001 PFP negotiations, a completely different approach was suggested and eventually initiated: Collaborative Negotiations. The collaborative negotiation style resulted in agreement between the agencies on all key issues within 6 months of initiation. All parties were very

  9. Conceptual design report, plutonium stabilization and handling,project W-460

    Energy Technology Data Exchange (ETDEWEB)

    Weiss, E.V.

    1997-03-06

    Project W-460, Plutonium Stabilization and Handling, encompasses procurement and installation of a Stabilization and Packaging System (SPS) to oxidize and package for long term storage remaining plutonium-bearing special nuclear materials currently in inventory at the Plutonium Finishing Plant (PFP), and modification of vault equipment to allow storage of resulting packages of stabilized SNM for up to fifty years. This Conceptual Design Report (CDR) provides conceptual design details for the vault modification, site preparation and site interface with the purchased SPS. Two concepts are described for vault configuration; acceleration of this phase of the project did not allow completion of analysis which would clearly identify a preferred approach.

  10. Plan for the Initiation of HA-211 Furnace Operations at the Plutonium Finishing Plan (PFP)

    International Nuclear Information System (INIS)

    WILLIS, H.T.

    2000-01-01

    This plan provides a phased approach authorizing the use of three additional muffle furnaces for thermal stabilization. Achievement of Thermal Stabilization mission elements require the installation and startup of three additional muffle furnaces for the thermal stabilization of plutonium and plutonium bearing materials at the Plutonium Finishing Plant (PFP). The release to operate these additional furnaces will require an Activity Based Startup Review. The conduct of the Activity Based Startup Review (ABSR) was approved by Fluor Daniel Hanford on October 15, 1999. This plan has been developed with the objective of identifying those activities needed to guide the controlled startup of five furnaces from authorization to unrestricted operations by adding the HA-211 furnaces in an orderly and safe manner after the approval to Startup has been given

  11. PFP Commercial Grade Food Pack Cans for Plutonium Handling and Storage Critical Characteristics

    International Nuclear Information System (INIS)

    BONADIE, E.P.

    1999-01-01

    This document specifies the critical characteristics for Commercial Grade Items (CGI) procured for PFP's Vault Operations system as required by HNF-PRO-268 and HNF-PRO-1819. These are the minimum specifications that the equipment must meet in order to perform its safety function

  12. Project Management Plan for Material Stabilization

    International Nuclear Information System (INIS)

    SPEER, D.R.

    1999-01-01

    This plan presents the overall objectives, description, justification and planning for the plutonium Finishing Plant (PFP) Materials Stabilization project. The intent of this plan is to describe how this project will be managed and integrated with other facility stabilization and deactivation activities. This plan supplements the overall integrated plan presented in the Plutonium Finishing Plant Integrated Project Management Plan (IPMP), HNF-3617/Rev. 0. This is the top-level definitive project management document that specifies the technical (work scope), schedule, and cost baselines to manager the execution of this project. It describes the organizational approach and roles/responsibilities to be implemented to execute the project. This plan is under configuration management and any deviations must be authorized by appropriate change control action. Materials stabilization is designated the responsibility to open and stabilize containers of plutonium metal, oxides, alloys, compounds, and sources. Each of these items is at least 30 weight percent plutonium/uranium. The output of this project will be containers of materials in a safe and stable form suitable for storage pending final packaging and/or transportation offsite. The corrosion products along with oxides and compounds will be stabilized via muffle furnaces to reduce the materials to high fired oxides

  13. Plutonium Finishing Plant transition project function analysis report

    International Nuclear Information System (INIS)

    Lund, D.P.

    1995-09-01

    The document contains the functions, function definitions, function interfaces, function interface definitions, Input Computer Automated Manufacturing Definition (IDEFO) diagrams, and function hierarchy charts that describe what needs to be performed to deactivate PFP and to continue safe storage, treatment and disposition of Plutonium and High Enriched Uranium

  14. Plant Biology Science Projects.

    Science.gov (United States)

    Hershey, David R.

    This book contains science projects about seed plants that deal with plant physiology, plant ecology, and plant agriculture. Each of the projects includes a step-by-step experiment followed by suggestions for further investigations. Chapters include: (1) "Bean Seed Imbibition"; (2) "Germination Percentages of Different Types of Seeds"; (3)…

  15. Plutonium finishing plant dangerous waste training plan

    International Nuclear Information System (INIS)

    ENTROP, G.E.

    1999-01-01

    This training plan describes general requirements, worker categories, and provides course descriptions for operation of the Plutonium Finish Plant (PFP) waste generation facilities, permitted treatment, storage and disposal (TSD) units, and the 90-Day Accumulation Areas

  16. CSER 00-006 Storage of Plutonium Residue Containers in 55 Gallon Drums at the PFP

    Energy Technology Data Exchange (ETDEWEB)

    DOBBIN, K.D.

    2000-05-24

    This criticality safety evaluation report (CSER) provides the required limit set and controls for safe transit and storage of these drums in the 234-5Z Building at the PFP. A mass limit of 200 g of plutonium or fissile equivalent per drum is acceptable

  17. Radioactive Air Emissions Notice of Construction for the Magnesium Hydroxide Precipitation Process at the Plutonium Finishing Plant (PFP)

    International Nuclear Information System (INIS)

    JANSKY, M.T.

    1999-01-01

    The following description and any attachments and references are provided to the Washington State Department of Health (WDOH), Division of Radiation Protection, Air Emissions and Defense Waste (WAC) 246-247, Radiation Protection-Air Emissions. The WAC 246-247-060, ''Applications, registration, and licensing'', states ''This section describes the information requirements for approval to construct, modify, and operate an emission unit. Any NOC requires the submittal of information listed in Appendix A.'' Appendix A (WAC 246-247-1 10) lists the requirements that must be addressed. Additionally, the following description, attachments and references are provided to the US Environmental Protection Agency (EPA) as an NOC, in accordance with Title 40, Code of Federal Regulations (CFR), Part 61, ''National Emission Standards for Hazardous Air Pollutants.'' The information required for submittal to the EPA is specified in 40 CFR 61.07. The potential emissions from this activity are estimated to provide greater than 0.1 millirem per year total effective dose equivalent (TEDE) to the hypothetical offsite maximally exposed individual (MEI), and commencement is needed within a short time. Therefore, this application also is intended to provide notification of the anticipated date of initial startup in accordance with the requirement listed in 40 CFR 61.09(a)(1), and it is requested that approval of this application also will constitute EPA acceptance of this initial startup notification. Written notification of the actual date of initial startup, in accordance with the requirement listed in 40 CFR 61.09(a)(2) will be provided at a later date. This NOC covers the activities associated with the Construction and operation activities involving the magnesium hydroxide precipitation process of plutonium solutions within the Plutonium Finishing Plant (PFP)

  18. Sludge stabilization at the Plutonium Finishing Plant, Hanford Site, Richland, Washington

    International Nuclear Information System (INIS)

    1994-10-01

    This Environmental Assessment evaluates the proposed action to operate two laboratory-size muffle furnaces in glovebox HC-21C, located in the Plutonium Finishing Plant (PFP), Hanford Site, Richland, Washington. The muffle furnaces would be used to stabilize chemically reactive sludges that contain approximately 25 kilograms (55 pounds) of plutonium by heating to approximately 500 to 1000 degrees C (900 to 1800 degrees F). The resulting stable powder, mostly plutonium oxide with impurities, would be stored in the PFP vaults. The presence of chemically reactive plutonium-bearing sludges in the process gloveboxes poses a risk to workers from radiation exposure and limits the availability of storage space for future plant cleanup. Therefore, there is a need to stabilize the material into a form suitable for long-term storage. This proposed action would be an interim action, which would take place prior to completion of an Environmental Impact Statement for the PFP which would evaluate stabilization of all plutonium-bearing materials and cleanout of the facility. However, only 10 percent of the total quantity of plutonium in reactive materials is in the sludges, so this action will not limit the choice of reasonable alternatives or prejudice the Record of Decision of the Plutonium Finishing Plant Environmental Impact Statement

  19. Transition projects, Fiscal Year 1996: Multi-Year Program Plan (MYPP) for WBS 1.31, 7.1, and 6.13. Revision 1, Volume 1

    Energy Technology Data Exchange (ETDEWEB)

    Cartmell, D.B.

    1995-09-01

    Based on US Department of Energy (DOE), Richland Operations Office (RL) review, specific areas of Westinghouse Hanford Company (WHC), Transition Projects ``Draft`` Multi-Year Program Plan (MYPP) were revised in preparation for the RL approval ceremony on September 26, 1995. These changes were reviewed with the appropriate RL Project Manager. The changes have been incorporated to the MYPP electronic file, and hard copies replacing the ``Draft`` MYPP will be distributed after the formal signing. In addition to the comments received, a summary level schedule and outyear estimates for the K Basin deactivation beginning in FY 2001 have been included. The K Basin outyear waste data is nearing completion this week and will be incorporated. This exclusion was discussed with Mr. N.D. Moorer, RL, Facility Transition Program Support/Integration. The attached MYPP scope/schedule reflects the Integrated Target Case submitted in the April 1995 Activity Data Sheets (ADS) with the exception of B Plant and the Plutonium Finishing Plant (PFP). The 8 Plant assumption in FY 1997 reflects the planning case in the FY 1997 ADS with a shortfall of $5 million. PFP assumptions have been revised from the FY 1997 ADS based on the direction provided this past summer by DOE-Headquarters. This includes the acceleration of the polycube stabilization back to its originally planned completion date. Although the overall program repricing in FY 1996 allowed the scheduled acceleration to fall with the funding allocation, the FY 1997 total reflects a shortfall of $6 million.

  20. Transition projects, Fiscal Year 1996: Multi-Year Program Plan (MYPP) for WBS 1.31, 7.1, and 6.13. Revision 1, Volume 1

    International Nuclear Information System (INIS)

    Cartmell, D.B.

    1995-09-01

    Based on US Department of Energy (DOE), Richland Operations Office (RL) review, specific areas of Westinghouse Hanford Company (WHC), Transition Projects ''Draft'' Multi-Year Program Plan (MYPP) were revised in preparation for the RL approval ceremony on September 26, 1995. These changes were reviewed with the appropriate RL Project Manager. The changes have been incorporated to the MYPP electronic file, and hard copies replacing the ''Draft'' MYPP will be distributed after the formal signing. In addition to the comments received, a summary level schedule and outyear estimates for the K Basin deactivation beginning in FY 2001 have been included. The K Basin outyear waste data is nearing completion this week and will be incorporated. This exclusion was discussed with Mr. N.D. Moorer, RL, Facility Transition Program Support/Integration. The attached MYPP scope/schedule reflects the Integrated Target Case submitted in the April 1995 Activity Data Sheets (ADS) with the exception of B Plant and the Plutonium Finishing Plant (PFP). The 8 Plant assumption in FY 1997 reflects the planning case in the FY 1997 ADS with a shortfall of $5 million. PFP assumptions have been revised from the FY 1997 ADS based on the direction provided this past summer by DOE-Headquarters. This includes the acceleration of the polycube stabilization back to its originally planned completion date. Although the overall program repricing in FY 1996 allowed the scheduled acceleration to fall with the funding allocation, the FY 1997 total reflects a shortfall of $6 million

  1. Artificial intelligence and distance learning philosophy in support of PfP mandate

    OpenAIRE

    Antoliš, Krunoslav

    2003-01-01

    Computers have long been utilised in the legal environment. The main use of computers however, has merely been to automate office tasks. More exciting is the prospect of using artificial intelligence (AI) technology to create computers that can emulate the substantive legal jobs performed by lawyers, to create computers that can autonomously reason with the law to determine legal solutions, for example: structuring and support of Partnership for Peace (PfP) mandate. Such attempts have not bee...

  2. Properties of the malarial proteins Pf2, Pf9 and PfP0, which support ...

    Indian Academy of Sciences (India)

    Properties of the malarial proteins Pf2, Pf9 and PfP0, which support their roles as immune targets. Antibodies raised to each of these proteins (or purified from immune adults) inhibit the growth of Plasmodium falciparum at the red cell invasion step. The proteins are localized on the parasite cell surface. Each protein is ...

  3. Addendum 2 to CSER 79-002: Extension of the 150 gram fissile limit used in room 187 of PFP

    International Nuclear Information System (INIS)

    Friar, D.E.

    1994-01-01

    The PFP operating organization requests that the limit set permitting 150 grams fissile be extended to the Hoods 4 and 5 of Room 187. The request for the limit change is explained in the attached request for analysis

  4. AVLIS Production Plant Project Management Plan

    International Nuclear Information System (INIS)

    1984-01-01

    The AVLIS Production Plant is designated as a Major System Acquisition (in accordance with DOE Order 4240.IC) to deploy Atomic Vapor Laser Isotope Separation (AVLIS) technology at the Oak Ridge, Tennessee site, in support of the US Uranium Enrichment Program. The AVLIS Production Plant Project will deploy AVLIS technology by performing the design, construction, and startup of a production plant that will meet capacity production requirements of the Uranium Enrichment Program. The AVLIS Production Plant Project Management Plan has been developed to outline plans, baselines, and control systems to be employed in managing the AVLIS Production Plant Project and to define the roles and responsibilities of project participants. Participants will develop and maintain detailed procedures for implementing the management and control systems in agreement with this plan. This baseline document defines the system that measures work performed and costs incurred. This plan was developed by the AVLIS Production Plant Project staff of Martin Marietta Energy Systems, Inc. and Lawrence Livermore National Laboratory in accordance with applicable DOE directives, orders and notices. 38 figures, 19 tables

  5. Definition and means of maintaining the criticality detectors and alarms portion of the PFP safety envelope

    Energy Technology Data Exchange (ETDEWEB)

    White, W.F.

    1997-05-13

    The purpose of this document is to provide the definition and means of maintaining the Safety Envelope (SE) related to the Criticality Alarm System (CAS). This document provides amplification of the Limiting Condition for Operation (LCO) described in the Plutonium Finishing Plant (PFP) Operational Safety Requirements (OSR), WHC-SD-CP-OSR-010, Rev. 0, 1994, Section 3.1.2, Criticality Detectors and Alarms. This document, with its appendices, provides the following: (1) System functional requirements for determining system operability (Section 3); (2) A list of annotated system block diagrams which indicate the safety envelope boundaries (Appendix C); (3) A list of the Safety Class 1 and 2 Safety Envelope (SC-1/2 SE) equipment for input into the Master Component Index (Appendix B); (4) Functional requirements for individual SC-1/2 SE components, including appropriate setpoints and process parameters (Section 6 and Appendix A); (5) A list of the operational, maintenance and surveillance procedures necessary to operate and maintain the SC-1/2 SE components as required by the LCO (Section 6 and Appendix A).

  6. Definition and Means of Maintaining the Criticality Prevention Design Features Portion of the PFP Safety Envelope

    International Nuclear Information System (INIS)

    RAMBLE, A.L.

    2000-01-01

    The purpose of this document is to record the technical evaluation of the Operational Safety Requirements described in the Plutonium Finishing Plant Final (PFP) Operational Safety Requirements, WHC-SD-CP-OSR-010. Rev. 0-N , Section 3.1.1, ''Criticality Prevention System.'' This document, with its appendices, provides the following: (1) The results of a review of Criticality Safety Analysis Reports (CSAR), later called Criticality Safety Evaluation Reports (CSER), and Criticality Prevention Specifications (CPS) to determine which equipment or components analyzed in the CSER or CPS are considered as one of the two unlikely, independent, and concurrent changes before a criticality accident is possible. (2) Evaluations of equipment or components to determine the safety boundary for the system (Section 4). (3) A list of essential drawings that show the safety system or component (Appendix A). (4) A list of the safety envelope (SE) equipment (Appendix B). (5) Functional requirements for the individual safety envelope equipment (Sections 3 and 4). (6) A list of the operational and surveillance procedures necessary to maintain the system equipment within the safety envelope (Section 5)

  7. Definition and means of maintaining the criticality detectors and alarms portion of the PFP safety envelope

    International Nuclear Information System (INIS)

    White, W.F.

    1997-01-01

    The purpose of this document is to provide the definition and means of maintaining the Safety Envelope (SE) related to the Criticality Alarm System (CAS). This document provides amplification of the Limiting Condition for Operation (LCO) described in the Plutonium Finishing Plant (PFP) Operational Safety Requirements (OSR), WHC-SD-CP-OSR-010, Rev. 0, 1994, Section 3.1.2, Criticality Detectors and Alarms. This document, with its appendices, provides the following: (1) System functional requirements for determining system operability (Section 3); (2) A list of annotated system block diagrams which indicate the safety envelope boundaries (Appendix C); (3) A list of the Safety Class 1 and 2 Safety Envelope (SC-1/2 SE) equipment for input into the Master Component Index (Appendix B); (4) Functional requirements for individual SC-1/2 SE components, including appropriate setpoints and process parameters (Section 6 and Appendix A); (5) A list of the operational, maintenance and surveillance procedures necessary to operate and maintain the SC-1/2 SE components as required by the LCO (Section 6 and Appendix A)

  8. Fire hazard analysis for Plutonium Finishing Plant complex

    International Nuclear Information System (INIS)

    MCKINNIS, D.L.

    1999-01-01

    A fire hazards analysis (FHA) was performed for the Plutonium Finishing Plant (PFP) Complex at the Department of Energy (DOE) Hanford site. The scope of the FHA focuses on the nuclear facilities/structures in the Complex. The analysis was conducted in accordance with RLID 5480.7, [DOE Directive RLID 5480.7, 1/17/94] and DOE Order 5480.7A, ''Fire Protection'' [DOE Order 5480.7A, 2/17/93] and addresses each of the sixteen principle elements outlined in paragraph 9.a(3) of the Order. The elements are addressed in terms of the fire protection objectives stated in paragraph 4 of DOE 5480.7A. In addition, the FHA also complies with WHC-CM-4-41, Fire Protection Program Manual, Section 3.4 [1994] and WHC-SD-GN-FHA-30001, Rev. 0 [WHC, 1994]. Objectives of the FHA are to determine: (1) the fire hazards that expose the PFP facilities, or that are inherent in the building operations, (2) the adequacy of the fire safety features currently located in the PFP Complex, and (3) the degree of compliance of the facility with specific fire safety provisions in DOE orders, related engineering codes, and standards

  9. Radioactive waste management plan for the PBMR (Pty) Ltd fuel plant

    International Nuclear Information System (INIS)

    Makgae, Mosidi E.

    2009-01-01

    The Pebble Bed Modular Reactor (Pty) Ltd Fuel Plant (PFP) radioactive waste management plan caters for waste from generation, processing through storage and possible disposal. Generally, the amount of waste that will be generated from the PFP is Low and Intermediate Level Waste. The waste management plan outlines all waste streams and the management options for each stream. It also discusses how the Plant has been designed to ensure radioactive waste minimisation through recycling, recovery, reuse, treatment before considering disposal. Compliance to the proposed plan will ensure compliance with national legislative requirements and international good practice. The national and the overall waste management objective is to ensure that all PFP wastes are managed appropriately by utilising processes that minimize, reduce, recover and recycle without exposing employees, the public and the environment to unacceptable impacts. Both International Atomic Energy Agency (IAEA) and Department of Minerals and Energy (DME) principles act as a guide in the development of the strategy in order to ensure international best practice, legal compliance and ensuring that the impact of waste on employees, environment and the public is as low as reasonably achievable. The radioactive waste classification system stipulated in the Radioactive Waste Management Policy and Strategy 2005 will play an important role in classifying radioactive waste and ensuring that effective management is implemented for all waste streams, for example gaseous, liquid or solid wastes.

  10. Peak pressures from hydrogen deflagrations in the PFP thermal stabilization glovebox

    International Nuclear Information System (INIS)

    Van Keuren, J.C.

    1998-01-01

    This document describes the calculations of the peak pressures due to hydrogen deflagrations in the glovebox used for thermal stabilization (glovebox HC-21A) in PFP. Two calculations were performed. The first considered the burning of hydrogen released from a 7 inch Pu can in the Inert Atmosphere Confinement (IAC) section of the glovebox. The peak pressure increase was 12400 Pa (1.8 psi). The second calculation considered burning of the hydrogen from 25 g of plutonium hydride in the airlock leading to the main portion of the glovebox. Since the glovebox door exposes most of the airlock when open, the deflagration was assumed to pressurize the entire glovebox. The peak pressure increase was 3860 Pa (0.56 psi)

  11. The PBMR fuel plant: Proven technology in an advanced safety environment

    International Nuclear Information System (INIS)

    Braehler, G.; Froschauer, K.; Welbers, P.; Boyes, D.

    2008-01-01

    The PBMR Fuel Plant (PFP), to be constructed at the Pelindaba site near Johannesburg will fuel the first South African Pebble Bed Modular Reactor. The qualification of the PBMR fuel shall be based on past experience with fuel which was produced in the German NUKEM/HOBEG plant and irradiated in the German AVR reactor. Accordingly, the PFP must produce the same fuel as the German plant did, and consequently, the design of the PFP has in essence to be a copy of the NUKEM/HOBEG plant. As a reminder this plant had been operated in accordance with the German regulatory rules which were defined in the years 1970/80. Since then, the requirements with regard to radiological protection, criticality safety and emission control have been significantly tightened, and of course the PFP must be designed in accordance with the most advanced international norms and standards. The implications which follow from these two potentially conflicting requirements, as defined above, are highlighted, and technical solutions are presented. Hence, the change from administrative criticality safety control to technical control, i.e. the application of safe geometry as far as possible. and the introduction of technical solutions for the remaining safe mass regime will be described. A lot of equipment in the Kernel area and in the recycling areas needed to be redesigned in safe geometry. The sensitive processes for Kernel Calcining, for the Coating and the Over-coating remain under safe mass regime, but the safety against criticality is completely independent from staff activities and based on technical measures. A new concept for safe storage of large volumes of Uranium-containing liquids has been developed. Also, the change from relatively open handling of Uranium to the application of containment enclosures wherever release of radioactivity into the room atmosphere is possible, will be addressed. This change required redesign of all process steps requiring the handling of dry Uranium oxides

  12. Functional enrichment analyses and construction of functional similarity networks with high confidence function prediction by PFP

    Directory of Open Access Journals (Sweden)

    Kihara Daisuke

    2010-05-01

    Full Text Available Abstract Background A new paradigm of biological investigation takes advantage of technologies that produce large high throughput datasets, including genome sequences, interactions of proteins, and gene expression. The ability of biologists to analyze and interpret such data relies on functional annotation of the included proteins, but even in highly characterized organisms many proteins can lack the functional evidence necessary to infer their biological relevance. Results Here we have applied high confidence function predictions from our automated prediction system, PFP, to three genome sequences, Escherichia coli, Saccharomyces cerevisiae, and Plasmodium falciparum (malaria. The number of annotated genes is increased by PFP to over 90% for all of the genomes. Using the large coverage of the function annotation, we introduced the functional similarity networks which represent the functional space of the proteomes. Four different functional similarity networks are constructed for each proteome, one each by considering similarity in a single Gene Ontology (GO category, i.e. Biological Process, Cellular Component, and Molecular Function, and another one by considering overall similarity with the funSim score. The functional similarity networks are shown to have higher modularity than the protein-protein interaction network. Moreover, the funSim score network is distinct from the single GO-score networks by showing a higher clustering degree exponent value and thus has a higher tendency to be hierarchical. In addition, examining function assignments to the protein-protein interaction network and local regions of genomes has identified numerous cases where subnetworks or local regions have functionally coherent proteins. These results will help interpreting interactions of proteins and gene orders in a genome. Several examples of both analyses are highlighted. Conclusion The analyses demonstrate that applying high confidence predictions from PFP

  13. PFP Commercial Grade Food Pack Cans for Plutonium Handling and Storage Critical Characteristics

    International Nuclear Information System (INIS)

    BONADIE, E.P.

    1999-01-01

    This document specifies the critical characteristics for Commercial Grade Items (CGI) procured for PFP's Vault Operations system as required by HNF-PRO-268 and HNF-PRO-1819. These are the minimum specifications that the equipment must meet in order to perform its safety function. The changes in these specifications have no detrimental effect on the descriptions and parameters related to handling plutonium solids in the authorization basis. Because no parameters or sequences exceed the limits described in the authorization bases, no accident or abnormal conditions are affected. The specifications prescribed in this critical characteristics document do not represent an unreviewed safety question

  14. Fire hazard analysis for Plutonium Finishing Plant complex

    Energy Technology Data Exchange (ETDEWEB)

    MCKINNIS, D.L.

    1999-02-23

    A fire hazards analysis (FHA) was performed for the Plutonium Finishing Plant (PFP) Complex at the Department of Energy (DOE) Hanford site. The scope of the FHA focuses on the nuclear facilities/structures in the Complex. The analysis was conducted in accordance with RLID 5480.7, [DOE Directive RLID 5480.7, 1/17/94] and DOE Order 5480.7A, ''Fire Protection'' [DOE Order 5480.7A, 2/17/93] and addresses each of the sixteen principle elements outlined in paragraph 9.a(3) of the Order. The elements are addressed in terms of the fire protection objectives stated in paragraph 4 of DOE 5480.7A. In addition, the FHA also complies with WHC-CM-4-41, Fire Protection Program Manual, Section 3.4 [1994] and WHC-SD-GN-FHA-30001, Rev. 0 [WHC, 1994]. Objectives of the FHA are to determine: (1) the fire hazards that expose the PFP facilities, or that are inherent in the building operations, (2) the adequacy of the fire safety features currently located in the PFP Complex, and (3) the degree of compliance of the facility with specific fire safety provisions in DOE orders, related engineering codes, and standards.

  15. 7 CFR 1412.48 - Planting Transferability Pilot Project.

    Science.gov (United States)

    2010-01-01

    ... 7 Agriculture 10 2010-01-01 2010-01-01 false Planting Transferability Pilot Project. 1412.48... and Peanuts 2008 through 2012 § 1412.48 Planting Transferability Pilot Project. (a) Notwithstanding § 1412.47, for each of the 2009 and subsequent crop years, the Planting Transferability Pilot Project...

  16. Dispatchable Solar Power Plant Project

    Energy Technology Data Exchange (ETDEWEB)

    Price, Henry [Solar Dynamics LLC, Broomfield, CO (United States)

    2018-01-31

    As penetration of intermittent renewable power increases, grid operators must manage greater variability in the supply and demand on the grid. One result is that utilities are planning to build many new natural gas peaking power plants that provide added flexibility needed for grid management. This report discusses the development of a dispatchable solar power (DSP) plant that can be used in place of natural gas peakers. Specifically, a new molten-salt tower (MST) plant has been developed that is designed to allow much more flexible operation than typically considered in concentrating solar power plants. As a result, this plant can provide most of the capacity and ancillary benefits of a conventional natural gas peaker plant but without the carbon emissions. The DSP system presented was designed to meet the specific needs of the Arizona Public Service (APS) utility 2017 peaking capacity request for proposals (RFP). The goal of the effort was to design a MST peaker plant that had the operational capabilities required to meet the peaking requirements of the utility and be cost competitive with the natural gas alternative. The effort also addresses many perceived barriers facing the commercial deployment of MST technology in the US today. These include MST project development issues such as permitting, avian impacts, visual impacts of tower CSP projects, project schedule, and water consumption. The DSP plant design is based on considerable analyses using sophisticated solar system design tools and in-depth preliminary engineering design. The resulting DSP plant design uses a 250 MW steam power cycle, with solar field designed to fit on a square mile plot of land that has a design point thermal rating of 400 MWt. The DSP plant has an annual capacity factor of about 16% tailored to deliver greater than 90% capacity during the critical Arizona summer afternoon peak. The table below compares the All-In energy cost and capacity payment of conventional combustion turbines

  17. Forecast Inaccuracies in Power Plant Projects From Project Managers' Perspectives

    Science.gov (United States)

    Sanabria, Orlando

    Guided by organizational theory, this phenomenological study explored the factors affecting forecast preparation and inaccuracies during the construction of fossil fuel-fired power plants in the United States. Forecast inaccuracies can create financial stress and uncertain profits during the project construction phase. A combination of purposeful and snowball sampling supported the selection of participants. Twenty project managers with over 15 years of experience in power generation and project experience across the United States were interviewed within a 2-month period. From the inductive codification and descriptive analysis, 5 themes emerged: (a) project monitoring, (b) cost control, (c) management review frequency, (d) factors to achieve a precise forecast, and (e) factors causing forecast inaccuracies. The findings of the study showed the factors necessary to achieve a precise forecast includes a detailed project schedule, accurate labor cost estimates, monthly project reviews and risk assessment, and proper utilization of accounting systems to monitor costs. The primary factors reported as causing forecast inaccuracies were cost overruns by subcontractors, scope gaps, labor cost and availability of labor, and equipment and material cost. Results of this study could improve planning accuracy and the effective use of resources during construction of power plants. The study results could contribute to social change by providing a framework to project managers to lessen forecast inaccuracies, and promote construction of power plants that will generate employment opportunities and economic development.

  18. Functional Design Criteria - plutonium stabilization and handling (PUSH) project W-460

    International Nuclear Information System (INIS)

    NELSON, D.W.

    1999-01-01

    This Functional Design Criteria (FDC) contains information to guide the design of the Stabilization and Packaging Equipment necessary to oxidize and package the remaining plutonium-bearing Special Nuclear Materials (SNM) currently in the Plutonium Finishing Plant (PFP) inventory. The FDC also guides the design of vault modifications to allow storage of 3013 packages of stabilized SNM for up to 50 years

  19. Functional Design Criteria plutonium stabilization and handling (PUSH) project W-460

    Energy Technology Data Exchange (ETDEWEB)

    NELSON, D.W.

    1999-09-02

    This Functional Design Criteria (FDC) contains information to guide the design of the Stabilization and Packaging Equipment necessary to oxidize and package the remaining plutonium-bearing Special Nuclear Materials (SNM) currently in the Plutonium Finishing Plant (PFP) inventory. The FDC also guides the design of vault modifications to allow storage of 3013 packages of stabilized SNM for up to 50 years.

  20. Female PFP patients present alterations in eccentric muscle activity but not the temporal order of activation of the vastus lateralis muscle during the single leg triple hop test.

    Science.gov (United States)

    Kalytczak, Marcelo Martins; Lucareli, Paulo Roberto Garcia; Dos Reis, Amir Curcio; Bley, André Serra; Biasotto-Gonzalez, Daniela Aparecida; Correa, João Carlos Ferrari; Politti, Fabiano

    2018-04-07

    This study aimed to compare the concentric and eccentric activity and the temporal order of peak activity of the hip and knee muscles between women with patellofemoral pain (PFP) and healthy women during the single leg triple hop test (SLTHT). Electromyographic (EMG) and Kinematic data were collected from 14 healthy women (CG) and 14 women diagnosed with PFP (PFG) during a single session of the single leg triple hop test. Integral surface electromyography (iEMG) data of the hip and knee muscles in eccentric and concentric phases and the length of time that each muscle needed to reach the maximal peak of muscle activity were calculated. The iEMG in the eccentric phase was significantly higher (p < 0.05) than the concentric phase, for the gluteus maximus and gluteus medius muscles (CG and PFG) and for the vastus lateralis muscle (PFG). The vastus lateralis muscle was the first muscle to reach the highest peak of activity in the PFG, and the third to reach this peak in the CG. In the present study, the activity of the vastus lateralis muscle during the eccentric phase of the jump was greater than concentric phase, as a temporal anticipation of its peak in activity among women with PFP. Copyright © 2018 Elsevier B.V. All rights reserved.

  1. The Creative Application of Science, Technology and Work Force Innovations to the Decontamination and Decommissioning of the Plutonium Finishing Plant at the Hanford Nuclear Reservation

    International Nuclear Information System (INIS)

    Charboneau, S.; Klos, B.; Heineman, R.; Skeels, B.; Hopkins, A.

    2006-01-01

    The Plutonium Finishing Plant (PFP) consists of a number of process and support buildings for handling plutonium. Building construction began in the late 1940's to meet national priorities and became operational in 1950 producing refined plutonium salts and metal for the United States nuclear weapons program The primary mission of the PFP was to provide plutonium used as special nuclear material for fabrication into a nuclear device for the war effort. Subsequent to the end of World War II, the PFP's mission expanded to support the Cold War effort through plutonium production during the nuclear arms race. PFP has now completed its mission and is fully engaged in deactivation, decontamination and decommissioning (D and D). At this time the PFP buildings are planned to be reduced to ground level (slab-on-grade) and the site remediated to satisfy national, Department of Energy (DOE) and Washington state requirements. The D and D of a highly contaminated plutonium processing facility presents a plethora of challenges. PFP personnel approached the D and D mission with a can-do attitude. They went into D and D knowing they were facing a lot of challenges and unknowns. There were concerns about the configuration control associated with drawings of these old process facilities. There were unknowns regarding the location of electrical lines and the condition and contents of process piping containing chemical residues such as strong acids and caustics. The gloveboxes were highly contaminated with plutonium and chemical residues. Most of the glovebox windows were opaque with splashed process chemicals that coated the windows or etched them, reducing visibility to near zero. Visibility into the glovebox was a serious worker concern. Additionally, all the gloves in the gloveboxes were degraded and unusable. Replacing gloves in gloveboxes was necessary to even begin glovebox clean-out. The sheer volume of breathing air needed was also an issue. These and other challenges and PFP

  2. South Texas Native Plant Restoration Project

    Science.gov (United States)

    2012-10-01

    The South Texas Native Plant Restoration Project was a resounding success in that the primary goal of : developing commercial sources of native seed has been substantially met. By the conclusion of the project : on August 31, 2011, 20 native seed sou...

  3. Successful Training Development and Implementation in Plant Modernization Projects

    International Nuclear Information System (INIS)

    Kuhn, A.; Schoenfelder, C.

    2012-01-01

    In plant modernization projects, for life extension or power update, the competence development (in particular, job and needs oriented training) of the plant staff plays an important role for ensuring the highest standard of nuclear safety, and for facilitating an economic operation of the plant. This paper describes challenges, methodology, activities, and results obtained so far from an on-going project in Sweden. - - As conclusion, critical factors for a successful staff training in plant modernization projects include a systematic approach to training, a dedicated training management team, and good interfaces between supplier's engineering teams, experienced training providers, and equipment suppliers.

  4. Project quality assurance plant: Sodium storage facility, project F-031

    International Nuclear Information System (INIS)

    Shultz, J.W.; Shank, D.R.

    1994-11-01

    The Sodium Storage Facility Project Quality Assurance Plan delineates the quality assurance requirements for construction of a new facility, modifications to the sodium storage tanks, and tie-ins to the FFTF Plant. This plan provides direction for the types of verifications necessary to satisfy the functional requirements within the project scope and applicable regulatory requirements determined in the Project Functional Design Criteria (FDC), WHC-SD-FF-FDC-009

  5. Summary of EPRI projects for improving power plant maintenance and maintainability

    International Nuclear Information System (INIS)

    Shugars, H.G.; Poole, D.N.; Pack, R.W.

    1979-01-01

    The Electric Power Research Institute is sponsoring projects to improve power plant maintenance and maintainability. Areas presently being emphasized are improvements in plant design for maintainability, improvements in performing nuclear plant refuelings, and development of on-line monitoring and diagnostic systems for various plant components. The seven projects are reviewed. They are: (1) human factors review of power plant maintainability; (2) refueling outage improvement; (3) on-line monitoring and diagnostics for power plant machinery; (4) acoustic emission and vibrati1on signature analysis of fossil fuel plant components; (5) acoustic monitoring of power plant valves; (6) on-line monitoring and diagnostics for generators; and (7) detection of water induction in steam turbines. Each project contractor and the project manager are listed for reference. 8 references

  6. Management of delayed nuclear power plant projects

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1999-09-01

    According to the available information at the IAEA PRIS (Power Reactor Information System) at the end of 1998 there were more than 40 nuclear power plant projects with delays of five or more years with respect to the originally scheduled commercial operation. The degree of conformance with original construction schedules showed large variations due to several issues, including financial, economic and public opinion factors. Taking into account the number of projects with several years delay in their original schedules, it was considered useful to identify the subject areas where exchange of experience among Member States would be mutually beneficial in identification of problems and development of guidance for successful management of the completion of these delayed projects. A joint programme of the IAEA Departments of Nuclear Energy (Nuclear Power Engineering Section) and Technical Co-operation (Europe Section, with additional support from the Latin America and West Asia Sections) was set up during the period 1997-1998. The specific aim of the programme was to provide assistance in the management of delayed nuclear power plants regarding measures to maintain readiness for resuming the project implementation schedule when the conditions permit. The integration of IAEA interdepartmental resources enabled the participation of 53 experts from 14 Member States resulting in a wider exchange of experience and dissemination of guidance. Under the framework of the joint programme, senior managers directly responsible for delayed nuclear power plant projects identified several issues or problem areas that needed to be addressed and guidance on management be provided. A work plan for the development of several working documents, addressing the different issues, was established. Subsequently these documents were merged into a single one to produce the present publication. This publication provides information and practical examples on necessary management actions to preserve

  7. Management of delayed nuclear power plant projects

    International Nuclear Information System (INIS)

    1999-09-01

    According to the available information at the IAEA PRIS (Power Reactor Information System) at the end of 1998 there were more than 40 nuclear power plant projects with delays of five or more years with respect to the originally scheduled commercial operation. The degree of conformance with original construction schedules showed large variations due to several issues, including financial, economic and public opinion factors. Taking into account the number of projects with several years delay in their original schedules, it was considered useful to identify the subject areas where exchange of experience among Member States would be mutually beneficial in identification of problems and development of guidance for successful management of the completion of these delayed projects. A joint programme of the IAEA Departments of Nuclear Energy (Nuclear Power Engineering Section) and Technical Co-operation (Europe Section, with additional support from the Latin America and West Asia Sections) was set up during the period 1997-1998. The specific aim of the programme was to provide assistance in the management of delayed nuclear power plants regarding measures to maintain readiness for resuming the project implementation schedule when the conditions permit. The integration of IAEA interdepartmental resources enabled the participation of 53 experts from 14 Member States resulting in a wider exchange of experience and dissemination of guidance. Under the framework of the joint programme, senior managers directly responsible for delayed nuclear power plant projects identified several issues or problem areas that needed to be addressed and guidance on management be provided. A work plan for the development of several working documents, addressing the different issues, was established. Subsequently these documents were merged into a single one to produce the present publication. This publication provides information and practical examples on necessary management actions to preserve

  8. CSER 94-014: Storage of metal-fuel loaded EBR-II casks in concrete vault on PFP grounds

    International Nuclear Information System (INIS)

    Hess, A.L.

    1994-01-01

    A criticality safety evaluation is presented to permit EBR-2 spent fuel casks loaded with metallic fuel rods to be stored in an 8-ft diameter, cylindrical concrete vault inside the PFP security perimeter. The specific transfer of three casks with Pu alloy fuel from the Los Alamos Molten Plutonium Reactor Experiment from the burial grounds to the vault is thus covered. Up to seven casks may be emplaced in the casing with 30 inches center to center spacing. Criticality safety is assured by definitive packaging rules which keep the fissile medium dry and at a low effective volumetric density

  9. Cancellation of the Kaiseraugst nuclear power plant project

    International Nuclear Information System (INIS)

    Blocher, C.; Schoenenberger, J.; Stucky, G.

    1988-01-01

    The nuclear power plant project at Kaiseraugst has been worked on for over 20 years. In 1985 the Swiss Parliament decided to license the plant. The cost of the work to date is about 1.2 x10 6 Swiss Franks. Continuation of the project is only sensible if it can be realized within a foreseeable space of time. It is probable that the discussions concerning future energy, environment and safety will continue for a long time. If this is clear that the Kaiseraugst project will not be realized during the next five to ten years for social, civic and political reasons. A continuation of the project is not justifiable. Kernkraftwerk Kaiseraugst AG must be adequately compensated. A motion has been presented to Parliament which charges the Government to negotiate with Kernkraftwerk Kaiseraugst AG for cancellation of the project

  10. Project organization for automating an industrial power plant

    International Nuclear Information System (INIS)

    Williams, D.R.; McCowen, R.R.

    1988-01-01

    This paper reports on the controls for three boilers and three turbine generators at the power plant at the John Deere Waterloo Works that have been retrofit with a microprocessor based monitoring, control, and optimization system. The factors driving the project in the 15 mW, 500,000 lb/hr, 35 year old plant were reduced electricity costs due to peak shaving, energy conservation, labor savings, reduced maintenance costs and improved reliability. A turnkey design/build arrangement was sought after a preliminary study indicated an attractive return on investment Control system vendors and design/build contractors were evaluated using a group decision making method. A design/build contractor was chosen to do an in-depth study and write specifications for the control system were negotiated with the contractor The project was managed by the Power Plant and Energy Management Department, rather than by the staff department normally responsible for capital projects

  11. Management of delayed nuclear power plant projects

    International Nuclear Information System (INIS)

    2005-01-01

    The IAEA assists the management of organizations responsible for Nuclear Power Plant Projects with significant delays with respect to the originally scheduled commercial operation. Several Member States have Nuclear Power Plant Projects with delays of five or more years with respect to the originally scheduled commercial operation. The degree of conformance with original construction schedules shows large variations due to several issues, including financial, economic and public opinion factors. Solving the special difficulties related with a delayed NPP project is problematic and dependent on the particular country situation. However it is not regarded as an isolated national problem but as a significant issue with a number of difficulties shared by several Member States. The IAEA collects information and supports the management of delayed NPP projects by identifying main common issues, gathering available experience and addressing specific needs. On this background the IAEA is in the position to provide unique impartial assistance based upon best international practices. This enables Member States to maintain readiness for resuming the project construction when the conditions permit and to strengthen management's abilities for the completion of the project. The IAEA's service is tailored to the needs and requirements of the requesting organization, implemented on-site by international experts and addresses areas such as project control measures, human resources, updating to technological and regulatory requirements, project data, nuclear safety review, physical protection and nuclear security and preparation to resume project construction and operation

  12. 1-MWp electrical photovoltaic plant (EPHOP - project)

    International Nuclear Information System (INIS)

    Vitanov, P.; Toneva, A.; Petkanchin, L.; Ivancheva, J.; Neshev, S.

    2000-01-01

    The presented project concerns the realization of a grid connected 1-MW p pilot photovoltaic plant on the territory of Bulgaria.The purpose of the project is to demonstrate and prove solar energy advantages. A special attention will be paid to the possibility the generated electricity to join the national electric network. The site selection according to the meteorological conditions as well as general aspects of the project are discussed

  13. Strategically oriented project management of the decommissioning of nuclear power plants

    International Nuclear Information System (INIS)

    Kemmeter, Sascha; Woempener, Andreas

    2013-01-01

    Due to the politically induced change of the energy sector in Germany, the operators of nuclear power plants had to react and to deal with completely new conditions concerning the decommissioning of their plants on short notice. Therefore the operators have to devise new strategies for controlling their decommissioning and dismantling projects in a short amount of time and most often similarly for several plants. Two fundamental procedures are possible for the successful controlling of these dismantling projects: a centralized or a decentralized management organization. How these project control processes can be realized in an optimal way, is, next to other economic specifications of the dismantling of nuclear power plants, the topic of a new research project of the Chair of Management Accounting at the University Duisburg-Essen. In that process, results and experiences from other research and practical projects concerning general large-scale projects are being used. Selected findings have been compiled and are being discussed in this paper. (orig.)

  14. Plant life management in Belgium: an integrated project

    International Nuclear Information System (INIS)

    Wacquier, W.; Smet, M. de; Hennart, J.C.; Greer, J.L.; Breesch, Ch.; Havard, P.

    2001-01-01

    In Belgium, a specific plant life management project, named ''Continuous Operation of Belgian NPPs'' is currently developing. Its final objective is to centralize all safety and economic aspects of plant life management in order to determine, for each NPP unit, the optimal actions required to maintain their safe and reliable operation. As the lifetime of safety-related active components is permanently controlled by the current maintenance programs, the project focuses only on passive safety-related components and on non-safety components important for the availability of the plants. These structures and components were evaluated and compared on the basis of a set of weighted criteria in order to measure their criticality and to identify those which must be considered in the project. The selection and the ranking of those components is based on the KBM TM methodology (Knowledge Based Maintenance). This methodology facilitates the collection, formalization and exchange of know-how and gives immediate results thanks to a sequential and systematic step by step analysis. (author)

  15. Methodology for cost estimate in projects for nuclear power plants decommissioning

    International Nuclear Information System (INIS)

    Salij, L.M.

    2008-01-01

    The conceptual approaches to cost estimating of nuclear power plants units decommissioning projects were determined. The international experience and national legislative and regulatory basis were analyzed. The possible decommissioning project cost classification was given. It was shown the role of project costs of nuclear power plant units decommissioning as the most important criterion for the main project decisions. The technical and economic estimation of deductions to common-branch fund of decommissioning projects financing was substantiated

  16. Control room modernization at Finnish nuclear power plants - Two projects compared

    International Nuclear Information System (INIS)

    Laarni, J.; Norros, L.

    2006-01-01

    The modernization of automation systems and human-machine interfaces is a current issue at both of the two nuclear power plants (i.e., Fortum's Loviisa plant and TVO's Olkiluoto plant) in Finland. Since the plants have been launched in the 1970's or 1980's, technology is in part old-fashioned and needs to be renewed. At Olkiluoto upgrades of the turbine operator systems have already been conducted; at Loviisa the first phase of the modernization project has just started. Basically, there is a question of the complete digitalization of the information streams at the two plants, and transition from a conventional hard-wired or hybrid control room to a screen-based one. The new human-machine interfaces will comprise new technology, such as PC workstations, soft control, touch screens and large-screen overall displays. The modernization of human-system interfaces is carried out in a stepwise manner at both plants. At both plants the main driver has not been the need to renew the user interfaces of the control room, but the need to upgrade the automation systems. In part because of this, there is a lack of a systematic top-down approach in which different aspects of human factors (HF) engineering are considered in relationship to higher level goals. Our aim here is to give an overview description of the control room modernization projects at the two plants and provide a preliminary evaluation of their progress to date. The projects are also compared, for example, in terms of duration, scope and phasing, and who is responsible for the realization of the project. In addition, we also compare experiences from the Finnish projects to experiences from similar projects abroad. The main part of the data used in this study is based on designers' and project members' interviews. (authors)

  17. Feasibility study of Pridneprovskaya Thermal Power Plant reconstruction project

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2001-03-01

    With objectives of saving energy and reducing greenhouse gas emission at the Pridneprovskaya power plant in Ukraine, a scrap and build project has been discussed. This project will abolish the unit No.12 among the eight units in the existing coal burning power generation facilities, and install a natural gas burning combined cycle plant comprising of three units each with an output of 100 MW. The new plant facilities will consist of gas turbines, steam turbines, HRSG and auxiliary devices, and an air-cooled synchronous power generator with a capacity of 119 MVA. Use of natural gas as fuel reduces generation of soot, sulfur oxides, nitrogen oxides, and CO. In addition, the hot effluent and waste liquor effluent will decrease from those at the present plant. The required fund will be 30,107 million yen. The energy saving effect of this project is reduction of about 7.5 million tons of crude oil equivalent as a total in 40 years. The greenhouse effect gas will decrease by about 39 million tons as a total in 40 years. The profitability estimation calls for the number of investment recovery year of 16 years, and internal profit rate of 7.32%, wherein the implementation of the project cannot be expected as a project to be carried out by private funds. (NEDO)

  18. Feasibility study on Bobovdol thermal power plant upgrading project

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2001-03-01

    A survey has been made in relation with the improvement project intended of energy conservation, and reduction of global warming gas emission at the Bobovdol thermal power plant located in the suburb of Sofia, the capital of the Republic of Bulgaria. The existing Bobovdol power plant having a total capacity of 630 MW with three generators is a coal burning thermal power plant having been used already for 23 to 27 years, hence over-aged. The survey has discussed an improvement project of scrap-and-build type to make the plant a high-efficiency gas combined cycle power plant using gas turbines. The project calls for building 210-MW gas combined power generation facilities having 70-MW gas turbines, one each in three stages in 2007, 2012 and 2017. As a result of the discussions, the fuel consumption reducing rate was found to reach 37.99%, whereas the cumulative energy saving quantity in 41 years will reach 16.37 million tons of fuel oil equivalent. In addition, the reduction rate of global warming gas emission is 57.75%, and the cumulative reduction quantity in 41 years is 105.18 million tons. (NEDO)

  19. Study on nuclear power plant project construction and management mode in China

    International Nuclear Information System (INIS)

    Wang Kai; Chen Lian

    2009-01-01

    Project management mode plays a key role in project construction, especially in nuclear power field. From the aspects of right, responsibility and benefit, this paper discussed the differences among the common used project management modes. Also the main kinds of the construction management modes used in China's nuclear power plants were summarized. At last, considering the experience of Ningde nuclear power plant, this paper put forward several perspectives about the selection of project management mode in nuclear power plant construction. (authors)

  20. Definition and means of maintaining the emergency notification and evacuation system portion of the plutonium finishing plant safety envelope

    International Nuclear Information System (INIS)

    WHITE, W.F.

    1999-01-01

    The Emergency Evacuation and Notification System provides information to the Plutonium Finishing Plant (PFP) Building Emergency Director to assist in determining appropriate emergency response, notifies personnel of the required response, and assists in their response. The report identifies the equipment in the Safety Envelope (SE) for this System and the Administrative, Maintenance, and Surveillance Procedures used to maintain the SE Equipment

  1. Managing the first nuclear power plant project

    International Nuclear Information System (INIS)

    2007-05-01

    Energy is essential for national development. Nearly every aspect of development - from reducing poverty and raising living standards to improving health care, industrial and agricultural productivity - requires reliable access to modern energy resources. States may have different reasons for considering starting a nuclear power project to achieve their national energy needs, such as: lack of available indigenous energy resources, the desire to reduce dependence upon imported energy, the need to increase the diversity of energy resources and/or mitigation of carbon emission increases. The start of a nuclear power plant project involves several complex and interrelated activities with long duration. Experience shows that the time between the initial policy decision by a State to consider nuclear power up to the start of operation of its first nuclear power plant is about 10 to 15 years and that before specific project management can proceed, several key infrastructure issues have to be in place. The proper management of the wide scope of activities to be planned and implemented during this period represents a major challenge for the involved governmental, utility, regulatory, supplier and other supportive organizations. The main focus is to ensure that the project is implemented successfully from a commercial point of view while remaining in accordance with the appropriate engineering and quality requirements, safety standards and security guides. This publication is aimed at providing guidance on the practical management of a first nuclear power project in a country. There are many other issues, related to ensuring that the infrastructure in the country has been prepared adequately to ensure that the project will be able to be completed, that are only briefly addressed in this publication. The construction of the first nuclear power plant is a major undertaking for any country developing a nuclear power programme. Worldwide experience gained in the last 50 years

  2. Demonstration project: Oxy-fuel combustion at Callide-A plant

    Energy Technology Data Exchange (ETDEWEB)

    Makino, Keiji; Misawa, Nobuhiro; Kiga, Takashi; Spero, Chris

    2007-07-01

    Oxy-fuel combustion is expected to be one of the promising systems on CO2 recovery from pulverized-coal power plant, and enable the CO2 to be captured in a more cost-effective manner compared to other CO2 recover process. An Australia-Japan consortium was established in 2004 specifically for the purpose of conducting a feasibility study on the application of oxy-fuel combustion to an existing pulverized-coal power plant that is Callide-A power plant No.4 unit at 30MWe owned by CS Energy in Australia. One of the important components in this study has been the recent comparative testing of three Australian coals under both oxy-fuel and air combustion conditions using the IHI combustion test facilities. The tests have yielded a number of important outcomes including a good comparison of normal air with oxy-fuel combustion, significant reduction in NOx mass emission rates under oxy-fuel combustion. On the basis of the feasibility study, the project under Australia-Japan consortium is now under way for applying oxy-fuel combustion to an existing plant by way of demonstration. In this project, a demonstration plant of oxy-fuel combustion will be completed by the end of 2008. This project aims at recovering CO2 from an actual power plant for storage. (auth)

  3. Fluor Hanford Nuclear Material Stabilization Project Welding Manual

    International Nuclear Information System (INIS)

    BERKEY, J.R.

    2000-01-01

    The purpose of this section of the welding manual is to: (1) Provide a general description of the major responsibilities of the organizations involved with welding. (2) Provide general guidance concerning the application of codes related to welding. This manual contains requirements for welding for all Fluor Hanford (FH) welding operators working on the W460 Project, in the Plutonium Finishing Plant (PFP) at the U. S. Department of Energy (DOE) Hanford facilities. These procedures and any additional requirements for these joining processes can be used by all FH welding operators that are qualified. The Welding Procedure Specifications (WPS) found in this document were established from Procedure Qualification Records (PQR) qualified by FH specifically for the W460 Project. PQRs are permanent records of the initial testing and qualification program and are used to backup, and support, the WPS. The identification numbers of the supporting PQR(s) are recorded on each WPS. All PQRs are permanently stored under the supervision of the Fluor Hanford Welding Engineer (FHWE). New PQRs and WPSs will continue to be developed as necessary. The qualification of welders, welding operators and welding procedures will be performed for FH under supervision and concurrent of the FHWE. All new welding procedures to be entered in this manual or welder personnel to be added to the welder qualification database, shall be approved by the FHWE

  4. Extractive metalurgical pilot plant. Project and installation

    International Nuclear Information System (INIS)

    Paula, H.C.B.; Rolim, T.L.; Santana, A.O. de; Santos, F.S.M. dos; Dantas, C.C.

    1986-01-01

    An extractive metalurgical pilot plant with a flow capacity of 200l/h of phosphoric leach, recovering 80% of the uranium content has been designed and installed. Starting from the diagrams of the chemical process in the laboratory scale, the equipment worksheet of the basic project were developed. The procedure for dimensioning and positioning of each component is described. An isometric figure and the pilot plant lay-out are included. The pilot plant occupying 41 m 2 has been tested and operates at its nominal capacity. (author) [pt

  5. Conservation and restoration of indigenous plants to improve community livelihoods: the Useful Plants Project

    Science.gov (United States)

    Ulian, Tiziana; Sacandé, Moctar; Mattana, Efisio

    2014-05-01

    Kew's Millennium Seed Bank partnership (MSBP) is one of the largest ex situ plant conservation initiatives, which is focused on saving plants in and from regions most at risk, particularly in drylands. Seeds are collected and stored in seed banks in the country of origin and duplicated in the Millennium Seed Bank in the UK. The MSBP also strengthens the capacity of local communities to successfully conserve and sustainably use indigenous plants, which are important for their wellbeing. Since 2007, high quality seed collections and research information have been gathered on ca. 700 useful indigenous plant species that were selected by communities in Botswana, Kenya, Mali, Mexico and South Africa through Project MGU - The Useful Plants Project. These communities range from various farmer's groups and organisations to traditional healers, organic cotton/crop producers and primary schools. The information on seed conservation and plant propagation was used to train communities and to propagate ca. 200 species that were then planted in local gardens, and as species reintroduced for reforestation programmes and enriching village forests. Experimental plots have also been established to further investigate the field performance (plant survival and growth rate) of indigenous species, using low cost procedures. In addition, the activities support revenue generation for local communities directly through the sustainable use of plant products or indirectly through wider environmental and cultural services. This project has confirmed the potential of biodiversity conservation to improve food security and human health, enhance community livelihoods and strengthen the resilience of land and people to the changing climate. This approach of using indigenous species and having local communities play a central role from the selection of species to their planting and establishment, supported by complementary research, may represent a model for other regions of the world, where

  6. Definition and means of maintaining the emergency notification and evacuation system portion of the plutonium finishing plant safety envelope; TOPICAL

    International Nuclear Information System (INIS)

    WHITE, W.F.

    1999-01-01

    The Emergency Evacuation and Notification System provides information to the Plutonium Finishing Plant (PFP) Building Emergency Director to assist in determining appropriate emergency response, notifies personnel of the required response, and assists in their response. The report identifies the equipment in the Safety Envelope (SE) for this System and the Administrative, Maintenance, and Surveillance Procedures used to maintain the SE Equipment

  7. Compilation of PRF Canyon Floor Pan Sample Analysis Results

    Energy Technology Data Exchange (ETDEWEB)

    Pool, Karl N. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Minette, Michael J. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Wahl, Jon H. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Greenwood, Lawrence R. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Coffey, Deborah S. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); McNamara, Bruce K. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Bryan, Samuel A. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Scheele, Randall D. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Delegard, Calvin H. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Sinkov, Sergey I. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Soderquist, Chuck Z. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Fiskum, Sandra K. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Brown, Garrett N. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Clark, Richard A. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States)

    2016-06-30

    common anions, gamma spectrometry, metals, corrosivity, organics and alpha spectrometry (note: alpha spectrometry was cancelled during the performance of this work with concurrence from CHPRC). Results may help elucidate the components that led to the unexpected reaction in the canyon as well as inform the radiological and hazardous characteristics. The specific anions, gamma emitters, organics and metals requested by CHPRC are provided in the analytical reports sections. The individual analyses were conducted under the Plutonium Finishing Plant (PFP) Floor Pan Evaluation Project Quality Assurance Project Plan (PFP Floor Pan Evaluation QAPP, Revision 0.) developed by PNNL specifically for this project. The final reports for each analysis set are included in this compilation of the results. Each package was reviewed under the PFP Floor Pan Evaluation Project Quality Assurance Project Plan so no additional reviews were conducted in this compilation task. The Gas Generation Rates in Appendix G were conducted under the PNNL “How Do I…” quality assurance program and were NOT conducted under the Plutonium Finishing Plant (PFP) Floor Pan Evaluation Project Quality Assurance Project Plan (PFP Floor Pan Evaluation QAPP, Revision 0.).

  8. Plutonium stabilization and handling quality assurance program plan

    International Nuclear Information System (INIS)

    Weiss, E.V.

    1998-01-01

    This Quality Assurance Program Plan (QAPP) identifies project quality assurance requirements for all contractors involved in the planning and execution of Hanford Site activities for design, procurement, construction, testing and inspection for Project W-460, Plutonium Stabilization and Handling. The project encompasses procurement and installation of a Stabilization and Packaging System (SPS) to oxidize and package for long term storage remaining plutonium-bearing special nuclear materials currently in inventory at the Plutonium Finishing Plant (PFP), and modification of vault equipment to allow storage of resulting packages of stabilized SNM

  9. Simulation-based valuation of project finance investments. Crucial aspects of power plant projects

    Energy Technology Data Exchange (ETDEWEB)

    Pietz, Matthaeus

    2010-12-15

    The liberalization of electricity markets transformed a regulated and stable market to a market with former unknown price volatility. This results in a high uncertainty which is mainly due to the, from an economic point of view, lack of storability of the commodity electricity. Thus investments in power plants are highly risky. This dissertation analyzes crucial aspects within the valuation of a power plant financed via project finance, a popular financing method for projects with high capital requirements. Starting with the development of a valuation model based on stochastic modelling of the future cash flows the focus of the analysis is on the impact of model complexity and electricity prices. (orig.)

  10. CSER 01-008 Canning of Thermally Stabilized Plutonium Oxide Powder in PFP Glovebox HC-21A

    International Nuclear Information System (INIS)

    ERICKSON, D.G.

    2001-01-01

    This document presents the analysis performed to support the canning operation in HC-21A. Most of the actual analysis was performed for the operation in HC-18M and HA-20MB, and is documented in HNF-2707 Rev I a (Erickson 2001a). This document will reference Erickson (2001a) as necessary to support the operation in HC-21A. The plutonium stabilization program at the Plutonium Finishing Plant (PFP) uses heat to convert plutonium-bearing materials into dry powder that is chemically stable for long term storage. The stabilized plutonium is transferred into one of several gloveboxes for the canning process, Gloveboxes HC-18M in Room 228'2, HA-20MB in Room 235B, and HC-21A in Room 230B are to be used for this process. This document presents the analysis performed to support the canning operation in HC-21A. Most of the actual analysis was performed for the operation in HC-I8M and HA-20MB, and is documented in HNF-2707 Rev l a (Erickson 2001a). This document will reference Erickson (2001a) as necessary to support the operation in HC-21A. Evaluation of this operation included normal, base cases, and contingencies. The base cases took the normal operations for each type of feed material and added the likely off-normal events. Each contingency is evaluated assuming the unlikely event happens to the conservative base case. Each contingency was shown to meet the double contingency requirement. That is, at least two unlikely, independent, and concurrent changes in process conditions are required before a criticality is possible

  11. Belene Nuclear Power Plant project status

    International Nuclear Information System (INIS)

    Nikolov

    2008-01-01

    The status of the Belene project with the following main features is described: Reactor type - PWR, Russian Design Plant supplier - ASE, AREVA NP/Siemens Reactor thermal power - 2 x 3012 MW Electric output -2 x 1060 MW Net efficiency - 35 % Capacity factor - 90 % Design Life Time - 60 years

  12. Economic-financial analysis of 'Angra 3 Nuclear Power Plant' project

    International Nuclear Information System (INIS)

    Andrade, Ronaldo Barata de

    2005-01-01

    This paper presents an economic-financial evaluation of 'Angra 3 Nuclear Power Plant' project and estimates the lowest power tariff value at which power potentially made available may be commercialized and yet ensure the project a profitability level agreeable to the interests of economic agents and shareholders. According to the 'project evaluation' practice, Angra 3 power generation was considered separately from ELETRONUCLEAR's operating plants (Angra 1 and Angra 2), thus preventing result distortions bound to occur if the economic-financial variables of the new project were analyzed associated with financial commitments and commercialization conditions resulting from the project implementation process and the generated power commercialization conditions, respectively. For this evaluation different technical and economic scenarios were devised, and the theory of Capital Asset Pricing Model for Own Capital cost and that of Weighted Average Cost of Capital were used in addition to the forecast of the Statement of Results and Free Cash flow of Shareholders throughout the power plant life, which is the estimate basis for the lowest power tariff value and the Internal Return Rate of the project. The evaluation conclusion is that Angra 3 project is technically and economically feasible and competitive as compared to the new large power generation projects planned for power supply in Brazil in the next decade, mainly in the Southeast. (author)

  13. Financing Nuclear Power Plant Projects. A New Paradigm?

    International Nuclear Information System (INIS)

    Pehuet Lucet, Fabienne

    2015-05-01

    There are currently 435 operable nuclear power reactors around the world, with a further 71 under construction. Two main proven financing models were applied to nuclear plants in the past: the national model, and the corporate model. The historical model of financing is the national model. It allowed for the most efficient risk allocation model in then-regulated national electricity markets: government or state-owned utilities with government guarantee assumed the risks of building nuclear power plants locally. The national model has proven to be efficient in France, Russia and the USA where it was modified to support private business initiatives. It was then replicated in Japan, Korea and China where significant nuclear programs were developed. In the corporate business model, the owner of the plant assumes most of the risk, but various schemes are used to mitigate the owner's risk by transmitting large areas of risks to others: vendors for construction risk as in Finland, government through loans guarantees etc. As projects became international, a set of common principles were approved by OECD countries concerning financing and the role of Export Credit Agencies. The objective was to provide competition rules whereby exporters compete on the basis of the price and quality of their products rather than the financial terms provided. Various combinations of these models were and still are implemented. Pure Project Finance was not implemented for nuclear power plants, but the model nurtures reflections about new financing models. The context in which nuclear power projects are now decided and financed changed drastically: it is a new paradigm. Risk allocation and financial conditions are at the forefront of competition to win new nuclear projects' tenders insofar as reducing uncertainties is a decisive competition edge. In a context of electricity market deregulation and high construction risks, investors and lenders require more and more securities to

  14. Tecnatom support to new nuclear power plant projects

    International Nuclear Information System (INIS)

    Manrique, A. B.

    2009-10-01

    Tecnatom is a Spanish engineering company with more than 50 years of experience working for the nuclear industry all over the world. It has worked in over 30 countries in activities related to the operation and maintenance of nuclear power plants. Along this half century of history. Tecnatom has been providing its services to nuclear utilities, regulators, NPP vendors, NPP owners / operators and nuclear fuel manufacturers not only in Spain but also abroad. It started to work in the design of new nuclear power plants in the early 90 s and since then has continued collaborating with different suppliers in the design and licensing of new reactors especially in the areas of plant systems design, man-machine interface design, main control room simulators building, training, qualification of equipment and PSI/ISI engineering services. Some challenges to the reactivation of nuclear power plants construction are common worldwide, including: regulatory processes, workforce availability, construction project management, etc. Being some keys to success the following: apply qualified resources, enough resources for early planning, project leadership, organization and integration, establish a strong integrated management team. The goal of this paper is to inform regarding the capabilities of Tecnatom in the construction of new power plants. (Author)

  15. Long Frontal Projections Help Battus philenor (Lepidoptera: Papilionidae) Larvae Find Host Plants.

    Science.gov (United States)

    Kandori, Ikuo; Tsuchihara, Kazuko; Suzuki, Taichi A; Yokoi, Tomoyuki; Papaj, Daniel R

    2015-01-01

    Animals sometimes develop conspicuous projections on or near their heads as, e.g., weaponry, burrowing or digging tools, and probes to search for resources. The frontal projections that insects generally use to locate and assess resources are segmented appendages, including antennae, maxillary palps, and labial palps. There is no evidence to date that arthropods, including insects, use projections other than true segmental appendages to locate food. In this regard, it is noteworthy that some butterfly larvae possess a pair of long antenna-like projections on or near their heads. To date, the function of these projections has not been established. Larvae of pipevine swallowtail butterflies Battus philenor (Papilionidae) have a pair of long frontal fleshy projections that, like insect antennae generally, can be actively moved. In this study, we evaluated the possible function of this pair of long moveable frontal projections. In laboratory assays, both frontal projections and lateral ocelli were shown to increase the frequency with which search larvae found plants. The frontal projections increased finding of host and non-host plants equally, suggesting that frontal projections do not detect host-specific chemical cues. Detailed SEM study showed that putative mechanosensillae are distributed all around the frontal as well as other projections. Taken together, our findings suggest that the frontal projections and associated mechanosensillae act as vertical object detectors to obtain tactile information that, together with visual information from lateral ocelli and presumably chemical information from antennae and mouthparts, help larvae to find host plants. Field observations indicate that host plants are small and scattered in southern Arizona locations. Larvae must therefore find multiple host plants to complete development and face significant challenges in doing so. The frontal projections may thus be an adaptation for finding a scarce resource before starving to

  16. CSER 00-003: Criticality Safety Evaluation report for PFP Magnesium Hydroxide Precipitation Process for Plutonium Stabilization Glovebox 3

    International Nuclear Information System (INIS)

    LAN, J.S.

    2000-01-01

    This Criticality Safety Evaluation Report analyzes the stabilization of plutonium/uranium solutions in Glovebox 3 using the magnesium hydroxide precipitation process at PFP. The process covered are the receipt of diluted plutonium solutions into three precipitation tanks, the precipitation of plutonium from the solution, the filtering of the plutonium precipitate from the solution, the scraping of the precipitate from the filter into boats, and the initial drying of the precipitated slurry on a hot plate. A batch (up to 2.5 kg) is brought into the glovebox as plutonium nitrate, processed, and is then removed in boats for further processing. This CSER establishes limits for the magnesium hydroxide precipitation process in Glovebox 3 to maintain criticality safety while handling fissionable material

  17. Nuclear criticality safety: general. 6. Application of Fixed Neutron Absorbers in the New Hanford PFP Horizontal Rack Design

    International Nuclear Information System (INIS)

    Lan, J.S.; Miller, E.M.; Toffer, H.; Mo, B.S.

    2001-01-01

    The Hanford Plutonium Finishing Plant (PFP) is currently in a waste cleanup and plutonium stabilization mode. Plutonium-bearing materials are processed through thermal treatment, creating forms of oxides suitable for long-term storage. Stabilized materials at PFP are stored in a variety of cans such as the bag-less transfer cans (BTCs), which are ultimately contained in the U.S. Department of Energy (DOE) 3013 can; both cans are larger than previously used plutonium storage containers and hold more plutonium. To compensate for the increased plutonium loadings, added engineered safety features were considered in the storage facilities. The vaults in PFP, subdivided into concrete-walled cubicles, will contain both new and older cans. The DOE 3013 and BTC cans may be loaded with up to 4.4 kg of plutonium as a compound (mostly oxide). New racks that store cans horizontally are being constructed to hold both new and older containers. The loading objective is to accommodate 70 kg of plutonium per cubicle. Two design analysis approaches for the new racks were considered. The first approach incorporated neutron absorption provided by the structural materials of the rack and the cans in determining a safe configuration. A rack loading arrangement was determined as shown in Fig. 1 and specified in Table I. This approach provides compliance with criticality control requirements; however, added administrative controls were needed to accommodate a sufficient number of cans in specific locations to achieve 70 kg of plutonium per cubicle. The 4.4-kg plutonium container can be placed only in predetermined locations. The second approach evaluated the addition of a fixed neutron absorber plate along the back wall of the cubicle (Fig. 1). The location of the special plate facilitates installation of the racks and provides additional criticality safety margin beyond the first approach. Its presence permits loading of racks with up to 4.4-kg plutonium cans in any storage locations

  18. Wind Plant Performance Prediction (WP3) Project

    Energy Technology Data Exchange (ETDEWEB)

    Craig, Anna [National Renewable Energy Laboratory (NREL), Golden, CO (United States)

    2018-01-26

    The methods for analysis of operational wind plant data are highly variable across the wind industry, leading to high uncertainties in the validation and bias-correction of preconstruction energy estimation methods. Lack of credibility in the preconstruction energy estimates leads to significant impacts on project financing and therefore the final levelized cost of energy for the plant. In this work, the variation in the evaluation of a wind plant's operational energy production as a result of variations in the processing methods applied to the operational data is examined. Preliminary results indicate that selection of the filters applied to the data and the filter parameters can have significant impacts in the final computed assessment metrics.

  19. Next Generation Nuclear Plant Project Evaluation of Siting a HTGR Co-generation Plant on an Operating Commercial Nuclear Power Plant Site

    International Nuclear Information System (INIS)

    Demick, L.E.

    2011-01-01

    This paper summarizes an evaluation by the Idaho National Laboratory (INL) Next Generation Nuclear Plant (NGNP) Project of siting a High Temperature Gas-cooled Reactor (HTGR) plant on an existing nuclear plant site that is located in an area of significant industrial activity. This is a co-generation application in which the HTGR Plant will be supplying steam and electricity to one or more of the nearby industrial plants.

  20. Next Generation Nuclear Plant Project Evaluation of Siting a HTGR Co-generation Plant on an Operating Commercial Nuclear Power Plant Site

    Energy Technology Data Exchange (ETDEWEB)

    L.E. Demick

    2011-10-01

    This paper summarizes an evaluation by the Idaho National Laboratory (INL) Next Generation Nuclear Plant (NGNP) Project of siting a High Temperature Gas-cooled Reactor (HTGR) plant on an existing nuclear plant site that is located in an area of significant industrial activity. This is a co-generation application in which the HTGR Plant will be supplying steam and electricity to one or more of the nearby industrial plants.

  1. Inventory of cassava plant protection and development projects in ...

    African Journals Online (AJOL)

    A total of 303 cassava protection and development projects were identified of which about half are plant protection-oriented. Most activities on cassava protection have been centred on biological control and host plant resistance. The least activity has been on chemical control. The applicability of the collected database is ...

  2. Assessment of the Plutonium Finishing Plant Criticality Alarm System U.S. Department of Energy Richland Operations Office

    International Nuclear Information System (INIS)

    NIRIDER, L.T.

    2002-01-01

    At the request of the Assistant Manager for Safety and Engineering, the U.S. Department of Energy Richland Operations Office (RL) Engineering Support Division, performed an oversight review of the Plutonium Finishing Plant (PFP) nuclear Criticality Alarm System (CAS). The review was conducted to satisfy requirements and agreements associated with Defense Nuclear Facility Safety Board (DNFSB) Recommendation 2000-2, ''Vital Safety Systems.'' The PFP is managed by Fluor Hanford, Inc. for RL. The field assessment and staff interviews were conducted August 12 through August 19,2002. This was a limited scope assessment that consisted of a review of the nuclear CAS operations, maintenance, and compliance with National Consensus Standards Requirements. The main purpose of the assessment was to determine the adequacy of the existing alarm system and its associated infrastructure to support the PFP facility mission through the remaining facility lifetime. The Review Plan was modeled upon Criteria and Review Approach Documents (CRAD) developed for DNFSB Recommendation 2000-2 reviews conducted across the Hanford Site. Concerns regarding component degradation and failure, increasing numbers of occurrence reports associated with the alarm system, and reliability issues were addressed. Additionally, RL performed a review of the engineering aspects of the CAS including the functions of design authorities and aspects of systems engineering. However, the focus of the assessment was on operations, maintenance, and reliability of the CAS, associated procurement practices, adequacy of safety and engineering policies and procedures, safety documentation, and fundamental engineering practices including training, qualification, and systems engineering. This assessment revealed that the PFP CAS and its associated infrastructure, administrative procedures, and conduct of operations are generally effective. There are no imminent criticality safety issues associated with the operation of the

  3. Engineering for new-built nuclear power plant projects

    International Nuclear Information System (INIS)

    Gonzalez Lopez, A.

    2012-01-01

    This article reviews the opportunities existing in the market (electrical utilities and reactor vendors) for an engineering company with the profile of Empresarios Agrupados (EA) in new-built nuclear power plant projects. To do this, reference is made to some representative examples of projects in which EA has been participating recently. the article concludes sharing with the reader some lessons learned from this participation. (Author)

  4. Instrumentation project of 3rd desalination plant at Tuas (Singapore)

    OpenAIRE

    Charco Iniesta, Sara

    2016-01-01

    This project consists on the description of instrumentation used in Tuas III desalination plant at Singapore and its flow process description. The project has been developed as part of the work of the instrumentation department of the responsible company of the engineering design of Tuas III desalination plant. First of all is important to know the water problems which suffer all the people who live in Singapore. Singapore is a city-state and is home to 5.5 million residents. The coun...

  5. Purification and Structural and Kinetic Characterization of the Pyrophosphate:Fructose-6-Phosphate 1-Phosphotransferase from the Crassulacean Acid Metabolism Plant, Pineapple.

    Science.gov (United States)

    Tripodi, KEJ.; Podesta, F. E.

    1997-03-01

    Pyrphosphate-dependent phosphofructokinase (PFP) was purified to electrophoretic homogeneity from illuminated pineapple (Ananas comosus) leaves. The purified enzyme consists of a single subunit of 61.5 kD that is immunologically related to the potato tuber PFP [beta] subunit. The native form of PFP likely consists of a homodimer of 97.2 kD, as determined by gel filtration. PFP's glycolytic activity was strongly dependent on pH, displaying a maximum at pH 7.7 to 7.9. Gluconeogenic activity was relatively constant between pH 6.7 and 8.7. Activation by Fru-2,6-bisphosphate (Fru-2,6-P2) was dependent on assay pH. In the glycolytic direction, it activated about 10-fold at pH 6.7, but only 2-fold at pH 7.7. The gluconeogenic reaction was only weakly affected by Fru-2,6-P2. The true substrates for the PFP forward and reverse reactions were Fru-6-phosphate and Mg-pyrophosphate, and Fru-1,6-P2, orthophosphate, and Mg2+, respectively. The results suggest that pineapple PFP displays regulatory properties consistent with a pH-based regulation of its glycolytic activity, in which a decrease in cytosolic pH caused by nocturnal acidification during Crassulacean acid metabolism, which could curtail its activity, is compensated by a parallel increase in its sensitivity to Fru-2,6-P2. It is also evident that the [beta] subunit alone is sufficient to confer PFP with a high catalytic rate and the regulatory properties associated with activation by Fru-2,6-P2.

  6. Project designing of Temelin nuclear power plant

    International Nuclear Information System (INIS)

    Krychtalek, Z.; Linek, V.

    1989-01-01

    The geological and seismic parameters are listed of the Temelin nuclear power plant. The division of the site in building zones is described. The main zones consist of the power generation unit zone with the related auxiliary buildings of hot plants and of the auxiliary buildings of the nonactive part with industrial buildings. The important buildings are interconnected with communication and technology bridges. Cooling towers and spray pools and the entrance area are part of the urbanistic design. The architectonic design of the buildings uses standard building elements and materials. The design of the buildings is based on the requirements on their function and on structural load and on the demands of maximal utilization of the type of the reinforced concrete prefab structure system. The structure is made of concrete or steel cells. The project design is based on Soviet projects. The layout is shown of the main power generation units and a section is presented of a 1,000 MW unit. (J.B.). 2 figs

  7. FGD Franchising Pilot Project of Thermal Power Plants

    Institute of Scientific and Technical Information of China (English)

    2009-01-01

    According to the national policy on enhancing environmental protection,the five major power generation companies are required to carry out flue gas desulphurization(FGD) franchising pilot project in thermal power plants.This paper introduces the development of this pilot project,including the foundation,purpose,objects,demands and procedures.It also discusses some main problems encountered during implementation,involving the understanding,legislation,financing,taxation,pricing and management of franchise.At...

  8. The 1.8-Å resolution crystal structure of YDR533Cp from Saccharomyces cerevisiae: A member of the DJ-1/ThiJ/PfpI superfamily

    Science.gov (United States)

    Wilson, Mark A.; Amour, Courtney V. St.; Collins, Jennifer L.; Ringe, Dagmar; Petsko, Gregory A.

    2004-01-01

    The yeast gene YDR533C encodes a protein belonging to the DJ-1/ThiJ/PfpI superfamily. This family includes the human protein DJ-1, which is mutated in autosomal recessive early-onset Parkinson's disease. The function of DJ-1 and its yeast homologue YDR533Cp is unknown. We report here the crystal structure of YDR533Cp at 1.8-Å resolution. The structure indicates that the closest relative to YDR533Cp is the Escherichia coli heat shock protein Hsp31 (YedU), which has both chaperone and protease activity. As expected, the overall fold of the core domain of YDR533Cp is also similar to that of DJ-1 and the bacterial protease PfpI. YDR533Cp contains a possible catalytic triad analogous to that of Hsp31 and an additional domain that is present in Hsp31 but is not seen in DJ-1 and other members of the family. The cysteine in this triad (Cys-138) is oxidized in this crystal structure, similar to modifications seen in the corresponding cysteine in the crystal structure of DJ-1. YDR533Cp appears to be a dimer both in solution and the crystal, but this dimer is formed by a different interface than that found in Hsp31 or other members of the superfamily. PMID:14745011

  9. Honeywell Modular Automation System Computer Software Documentation

    International Nuclear Information System (INIS)

    STUBBS, A.M.

    2000-01-01

    The purpose of this Computer Software Document (CSWD) is to provide configuration control of the Honeywell Modular Automation System (MAS) in use at the Plutonium Finishing Plant (PFP). This CSWD describes hardware and PFP developed software for control of stabilization furnaces. The Honeywell software can generate configuration reports for the developed control software. These reports are described in the following section and are attached as addendum's. This plan applies to PFP Engineering Manager, Thermal Stabilization Cognizant Engineers, and the Shift Technical Advisors responsible for the Honeywell MAS software/hardware and administration of the Honeywell System

  10. Plant Biology and Biogeochemistry Department annual project report 1999

    DEFF Research Database (Denmark)

    Jensen, A.; Gissel Nielsen, G.; Giese, H.

    2000-01-01

    The Department of Plant Biology and Biogeochemistry is engaged in basic and applied research to improve the scientific knowledge of developing new methods and technology for the future, environmentally benign industrial and agricultural production, thusexerting less stress and strain...... of Biomass, 3. DLF-Risø Biotechnology, 4. Plant Genetics and Epidemiology, 5. Biogeochemistry and 6. Plant Ecosystems and Nutrient Cycling. This electronicversion of the annual report from the Plant Biology and Biogeochemistry Department aims to provide information about the progress in our research. Each...... on the environment. This knowledge will lead to a greater prosperity and welfare for agriculture, industry and consumers in Denmark. The research approach in the Department is mainly experimental and the projects areorganized in six research programmes: 1. Plant-Microbe Symbioses, 2. Plant Products and Recycling...

  11. Economical aspects of a nuclear power plant project

    International Nuclear Information System (INIS)

    Meldonian, N.L.; Santos, E.M. dos

    1992-01-01

    This work describes different aspects and parameters that should be regarded as guidelines for economic evaluation of small and medium power plant projects. The main objective of an economic evaluation is to establish the plant's unitary cost and its economic figure of merit. To achieve that, a number of studies must be undertaken to compare the global competitiveness of a nuclear power plant with other energetic alternatives. These studies involve macro economy, energy generation, electricity transmission and global feasibility of the enterprise. It is concluded that the economic evaluation of a nuclear power plant should be considered as the culmination of a long process of planning at a national level. The main reasons are the investments involved, the technological developments required and political implications of the utilization of nuclear power energy. (author)

  12. Next Generation Nuclear Plant Project Preliminary Project Management Plan

    International Nuclear Information System (INIS)

    Dennis J. Harrell

    2006-01-01

    This draft preliminary project management plan presents the conceptual framework for the Next Generation Nuclear Plant (NGNP) Project, consistent with the authorization in the Energy Policy Act of 2005. In developing this plan, the Idaho National Laboratory has considered three fundamental project planning options that are summarized in the following section. Each of these planning options is literally compliant with the Energy Policy Act of 2005, but each emphasizes different approaches to technology development risks, design, licensing and construction risks, and to the extent of commercialization support provided to the industry. The primary focus of this draft preliminary project management plan is to identify those activities important to Critical Decision-1, at which point a decision on proceeding with the NGNP Project can be made. The conceptual project framework described herein is necessary to establish the scope and priorities for the technology development activities. The framework includes: A reference NGNP prototype concept based on what is judged to be the lowest risk technology development that would achieve the needed commercial functional requirements to provide an economically competitive nuclear heat source and hydrogen production capability. A high-level schedule logic for design, construction, licensing, and acceptance testing. This schedule logic also includes an operational shakedown period that provides proof-of-principle to establish the basis for commercialization decisions by end-users. An assessment of current technology development plans to support Critical Decision-1 and overall project progress. The most important technical and programmatic uncertainties (risks) are evaluated, and potential mitigation strategies are identified so that the technology development plans may be modified as required to support ongoing project development. A rough-order-of-magnitude cost evaluation that provides an initial basis for budget planning. This

  13. Conceptual project of waste treatment plant of CDTN

    International Nuclear Information System (INIS)

    Gabriel, J.L.; Astolfi, D.

    1983-01-01

    This paper presents the conceptual project of the waste treatment plant of CDTN. Several areas, such as: process area, material entrance and exit area are studied. The treatment processes are: evaporation, filtration, cementation, cutting and processing of solid wastes. (C.M.)

  14. Guide for prioritizing power plant productivity improvement projects: handbook of availability improvement methodology

    International Nuclear Information System (INIS)

    1981-01-01

    As part of its program to help improve electrical power plant productivity, the Department of Energy (DOE) has developed a methodology for evaluating productivity improvement projects. This handbook presents a simplified version of this methodology called the Availability Improvement Methodology (AIM), which provides a systematic approach for prioritizing plant improvement projects. Also included in this handbook is a description of data taking requirements necessary to support the AIM methodology, benefit/cost analysis, and root cause analysis for tracing persistent power plant problems. In applying the AIM methodology, utility engineers should be mindful that replacement power costs are frequently greater for forced outages than for planned outages. Equivalent availability includes both. A cost-effective ranking of alternative plant improvement projects must discern between those projects which will reduce forced outages and those which might reduce planned outages. As is the case with any analytical procedure, engineering judgement must be exercised with respect to results of purely mathematical calculations

  15. Purposes and related aspects of the nuclear power plant aging Project

    International Nuclear Information System (INIS)

    Garaud, J.; Reynes, L.; Montardy, A. de

    1989-01-01

    The purposes and some aspects of the nuclear power plant Lifetime project is presented. The work is focused on the study of the aging of the PWR type power plant components. The project consists in two phases. The first one involves: the status reports and the analysis of the lifetime data of the most sensitive units, as well as the applied actions and proposals, the influence of the exploitation modes, the safety and the cost prospectives. The second phase includes: the definition, the contracts, the complementary actions and their achievement, the reasons and the surveyance improvements, the development of the decision supporting means, the summary and the conclusions. The selected units for the project first step and the project of actions, are listed. The first conclusions of the project show that most of the 900 MW PWR reactor components will have about 40 years of service life [fr

  16. General criteria for the project of nuclear fuel reprocessing plants

    International Nuclear Information System (INIS)

    1979-01-01

    Recommendations are presented establishing the general criteria for the project of nuclear fuel reprocessing plants to be licensed according to the legislation in effect. They apply to all the plant's systems, components and structures which are important to operation safety and to the public's health and safety. (F.E.) [pt

  17. Project finance and photovoltaic power plants : a theoretical and practical perspective

    OpenAIRE

    Aasgaard, Anne Kristine

    2010-01-01

    Project finance is a defined structure for developing new activity which involves establishing the project as a separate unit. The review of literature exhibits the distinctive characteristics of project finance and provides a rationale of this form of financing. Project finance entails financial modelling, risk management, legal aspects and the creation of a financial structure. The thesis explores practical use of project finance in a case study of a photovoltaic power plant and presents a ...

  18. Update on the Department of Energy's 1994 plutonium vulnerability assessment for the plutonium finishing plant

    International Nuclear Information System (INIS)

    HERZOG, K.R.

    1999-01-01

    A review of the environmental, safety, and health vulnerabilities associated with the continued storage of PFP's inventory of plutonium bearing materials and other SNM. This report re-evaluates the five vulnerabilities identified in 1994 at the PFP that are associated with SNM storage. This new evaluation took a more detailed look and applied a risk ranking process to help focus remediation efforts

  19. Approaches to Teaching Plant Nutrition. Children's Learning in Science Project.

    Science.gov (United States)

    Leeds Univ. (England). Centre for Studies in Science and Mathematics Education.

    During the period 1984-1986, over 30 teachers from the Yorkshire (England) region have worked in collaboration with the Children's Learning in Science Project (CLIS) developing and testing teaching schemes in the areas of energy, particle theory, and plant nutrition. The project is based upon the constructivist approach to teaching. This document…

  20. Project management in fossil plant construction: A perspective for the Nineties

    International Nuclear Information System (INIS)

    Bhatia, N.K.

    1991-01-01

    The continuing growth in demand for electric power, and the reluctance of electric utility management to commit to new capacity additions has created a potential for somewhat hectic activity in the fossil power plant construction market. With the changing matrix of power plant types and ownerships, the project manager is called upon to deliver a complex product with exacting contract requirements: lump sum contracts, competitive pricing, short schedules, and performance guarantees. A shortage of experienced professionals in the ranks of the owners, engineers, contractors, and suppliers magnifies the challenge. Plant replication, automation, creative management of vendors and contractors, and participative management of the work force will be key elements of successful projects. Partnering between the clients and the engineers-constructors will be an interesting new relationship model

  1. Installation and commissioning of operation nuclear power plant reactor protection system modernization project

    International Nuclear Information System (INIS)

    Lu Weiwei

    2010-01-01

    Qinshan Nuclear Power Plant is the first nuclear power plant in mainland China; it is also the first one which realizes the modernization of analog technology based Reactor Protection System in the operation nuclear power plant of China. The implementation schedule is the shortest one which use same digital technology platform (TELEPERM XS of AREVA NP) to modifying the safety class I and C system in the world, the whole project spent 28 months from equipment contract signed to putting system into operation. It open up a era for operation nuclear power plant using mature digital technology to make safety class I and C system modernization in China. The important practical significance of this successful project is very obvious. This article focus on two important project stage--equipment installation and system commissioning, it is based on a large number of engineering implementation fact, it covers the problems and solutions happened during the installation and commission. The purpose of the article is to share the experience and lessons of safety I and C system modernization for other operation nuclear power plant. (authors)

  2. Data processing project management in the construction of plants and power stations

    International Nuclear Information System (INIS)

    Huelsen, H.; Hayen, W.

    1987-01-01

    The requirements of project management in plant construction i.e. basic data, supervision and control became more and more detailed. These requirements can only satisfactorily be met with the help of data processing. Piping design requires up to 50% of the whole amount of engineering in design and management of plant construction. We present data processing project management system which explains the connections of single aspects. Its connections consists of: collection of basic data, plant design and installation, supervision of planning and installation, planning and calculation, collection, use, administration and approval of plan data, procurement material, construction of the model (1:25), and installation. (orig.) [de

  3. MITI project on advanced man-machine system for nuclear power plants

    International Nuclear Information System (INIS)

    Kato, Kanji; Watanabe, Takao; Hayakawa, Hiroyasu; Naito, Norio; Masui, Takao; Ogino, Takamichi.

    1988-01-01

    A computerized operator support system (COSS) against abnormal plant conditions was developed as a five-year project from 1980 to 1984, under the sponsorship of the Ministry of International Trade and Industry. The main purpose of the COSS development was to implement the lessons learned from the Three Mile Island accident. The main nuclear industries in Japan participated in the project. The design concept of the operator support functions and the method to implement it were established, and the prototype systems of the COSS for BWR and PWR plants were developed. After the completion of the COSS development, the above participant group once again joined for the work on an advanced man-machine system for nuclear power plants (MMS-NPP). This eight-year project aims at realizing an advanced operator support system by applying artificial intelligence, especially knowledge engineering, and sophisticated man-machine interface devices. Its main objectives are shown. This system configuration, operating method decision system, man-machine communication system, operation and maintenance support functions and so on are described. (Kako, I.)

  4. Advanced Grid-Friendly Controls Demonstration Project for Utility-Scale PV Power Plants

    Energy Technology Data Exchange (ETDEWEB)

    Gevorgian, Vahan; O' Neill, Barbara

    2016-01-21

    A typical photovoltaic (PV) power plant consists of multiple power electronic inverters and can contribute to grid stability and reliability through sophisticated 'grid-friendly' controls. The availability and dissemination of actual test data showing the viability of advanced utility-scale PV controls among all industry stakeholders can leverage PV's value from being simply an energy resource to providing additional ancillary services that range from variability smoothing and frequency regulation to power quality. Strategically partnering with a selected utility and/or PV power plant operator is a key condition for a successful demonstration project. The U.S. Department of Energy's (DOE's) Solar Energy Technologies Office selected the National Renewable Energy Laboratory (NREL) to be a principal investigator in a two-year project with goals to (1) identify a potential partner(s), (2) develop a detailed scope of work and test plan for a field project to demonstrate the gird-friendly capabilities of utility-scale PV power plants, (3) facilitate conducting actual demonstration tests, and (4) disseminate test results among industry stakeholders via a joint NREL/DOE publication and participation in relevant technical conferences. The project implementation took place in FY 2014 and FY 2015. In FY14, NREL established collaborations with AES and First Solar Electric, LLC, to conduct demonstration testing on their utility-scale PV power plants in Puerto Rico and Texas, respectively, and developed test plans for each partner. Both Puerto Rico Electric Power Authority and the Electric Reliability Council of Texas expressed interest in this project because of the importance of such advanced controls for the reliable operation of their power systems under high penetration levels of variable renewable generation. During FY15, testing was completed on both plants, and a large amount of test data was produced and analyzed that demonstrates the ability of

  5. Hanford Waste Vitrification Plant - the project and process systems

    International Nuclear Information System (INIS)

    Swenson, L.D.; Miller, W.C.; Smith, R.A.

    1990-01-01

    The Hanford Waste Vitrification Plant (HWVP) project is scheduled to start construction on the Hanford reservation in southeastern Washington State in 1991. The project will immobilize the liquid high-level defense waste stored there. The HWVP represents the third phase of the U.S. Department of Energy (DOE) activities that are focused on the permanent disposal of high-level radioactive waste, building on the experience of Defense Waste Processing Facility (DWPF) at the Savannah River site, South Carolina, and of the West Valley Demonstration Plant (WVDP), New York. This sequential approach to disposal of the country's commercial and defense high-level radioactive waste allows HWVP to make extensive use of lessons learned from the experience of its predecessors, using mature designs from the earlier facilities to achieve economies in design and construction costs while enhancing operational effectiveness

  6. Siting and early-stage project management of nuclear power plant

    International Nuclear Information System (INIS)

    Wang Kai; Li Guojin

    2013-01-01

    In this paper, difficulties and challenges facing in siting of nuclear power plant after Fukushima nuclear accident is introduced. The key points for siting are analyzed. The site characteristics related to nuclear safety and the evaluated methods are discussed. From project management perspective, main procedures and key points for the early-stage of a nuclear power project are described. (authors)

  7. Westinghouse Hanford Company FY 1995 Materials Management Plan (MMP)

    International Nuclear Information System (INIS)

    Higginson, M.C.

    1994-10-01

    The safe and sound operation of facilities and storage of nuclear material are top priorities within Hanford's environmental management, site restoration mission. The projected materials estimates, based on the Materials Management Plan (MMP) assumptions outlined below, were prepared for Department of Energy (DOE) use in long-range planning. The Hanford MMP covers the period FY 1995 through FY 2005, as directed by DOE. All DOE Richland Operations (RL) Office facilities are essentially funded by the Office of Transition and Facilities Management, Environmental Restoration and Waste Management (EM). These facilities include PUREX, the UO 3 plant, N-Reactor, T-Plant, K-Basins, FFTF, PFP and the 300 Area Fuel Fabrication facilities. Currently DP provides partial funding for the latter two facilities. Beginning in FY 1996 (in accordance with DOE-HQ MMP assumptions), EM will fund expenses related to the storage, monitoring, and safeguarding of all Special Nuclear Material (SNM) in the PFP. Ownership and costs related to movement and/or stabilization of that material will belong to EM programs (excluding NE material). It is also assumed that IAEA will take over inventory validation and surveillance of EM owned SNM at this time (FY 1996)

  8. The Power Plant Mapping Student Project: Bringing Citizen Science to Schools

    Science.gov (United States)

    Tayne, K.; Oda, T.; Gurney, K. R.; O'Keeffe, D.; Petron, G.; Tans, P. P.; Frost, G. J.

    2014-12-01

    An emission inventory (EI) is a conventional tool to quantify and monitor anthropogenic emissions of greenhouse gases and air pollutants into the atmosphere. Gridded EI can visually show geographical patterns of emissions and their changes over time. These patterns, when available, are often determined using location data collected by regional governments, industries, and researchers. Datasets such as Carbon Monitoring and Action (CARMA, www.carma.org) are particularly useful for mapping emissions from large point sources and have been widely used in the EI community. The EI community is aware of potentially significant errors in the geographical locations of point sources, including power plants. The big challenge, however, is to review tens of thousands of power plant locations around the world and correct them where needed. The Power Plant Mapping Student Project (PPMSP) is a platform designed for students in 4th through 12th grade to improve the geographical location of power plants indicated in existing datasets to benefit international EI research. In PPMSP, we use VENTUS, a web-based platform (http://ventus.project.asu.edu/) that invites citizens to contribute power plant location data. Using VENTUS, students view scenes in the vicinity of reported power plant coordinates on Google Maps. Students either verify the location of a power plant or search for it within a designated radius using various indicators, an e-guide, and a power plant photo gallery for assistance. If the power plant cannot be found, students mark the plant as unverified. To assure quality for research use, the project contains multiple checkpoints and levels of review. While participating in meaningful research that directly benefits the EI research community, students are engaged in relevant science curricula designed to meet each grade level's Next Generation Science Standards. Students study energy, climate change, the atmosphere, and geographical information systems. The curricula is

  9. Identifying Issues in Applying Integrated Project Delivery to Domestic Nuclear Power Plant Construction Projects

    Energy Technology Data Exchange (ETDEWEB)

    Kim, Young Joo [Korean Nuclear Society, Daejeon (Korea, Republic of)

    2016-05-15

    Integrated Project Delivery (IPD) is defined as that people, systems, business structures, and practices of key stakeholders are incorporated into a single-team, with a single process, which executes a project in a way of optimizing the project's outcome, increasing values delivered to the end user, reducing waste, and maximizing efficiency throughout the phases of engineering to construction. The researcher had carried out literature review in terms of IPD to identify major characteristics of IPD which are presented in the following section and had compared such characteristics against peculiarities of nuclear power plant (NPP) construction projects in order to shed light on obstacles in possible application of IPD method to domestic NPP construction projects in the coming days. In this research, three (3) major characteristics of IPD were identified: 1) key stakeholders signing one balanced contract, forming de facto one body, sharing risk and reward 2) an integrated project team being formed in the early stage of a project and providing input to minimize time and cost loss from rework downstream 3) team members co-locating, having open and direct communication, making decisions on time, and pursuing the success of the project itself.

  10. Summary of developments and future projects in nuclear power plant control and instrumentation in the Netherlands

    International Nuclear Information System (INIS)

    Plas, Y. van der

    1990-01-01

    A general view is given on the developments and trends due to instrumentation and control of the two nuclear power plants in the Netherlands around the year 1989. Several projects, under which for classification of systems and components and for emergency operating procedures, are executed in both plants. An OSART mission initiated a project to make possible the periodic test of safety commands during operation. An other large project concerned the replacement of the process presentation system in Nuclear Power Plant Borssele. In the article several other developments due to the application of I and C in existing plants are outlined generally. Since 1974, no new nuclear power plants have been constructed in the Netherlands. (author). 2 figs

  11. Quality assurance in technology development for The Clinch River Breeder Reactor Plant Project

    International Nuclear Information System (INIS)

    Anderson, J.W.

    1980-01-01

    The Clinch River Breeder Reactor Plant Project is the nation's first large-scale demonstration of the Liquid Metal Fast Breeder Reactor (LMFBR) concept. The Project has established an overall program of plans and actions to assure that the plant will perform as required. The program has been established and is being implemented in accordance with Department of Energy Standard RDT F 2-2. It is being applied to all parts of the plant, including the development of technology supporting its design and licensing activity. A discussion of the program as it is applied to development is presented

  12. Next Generation Nuclear Plant (NGNP) Prismatic HTGR Conceptual Design Project - Final Technical Report

    Energy Technology Data Exchange (ETDEWEB)

    Saurwein, John

    2011-07-15

    This report is the Final Technical Report for the Next Generation Nuclear Plant (NGNP) Prismatic HTGR Conceptual Design Project conducted by a team led by General Atomics under DOE Award DE-NE0000245. The primary overall objective of the project was to develop and document a conceptual design for the Steam Cycle Modular Helium Reactor (SC-MHR), which is the reactor concept proposed by General Atomics for the NGNP Demonstration Plant. The report summarizes the project activities over the entire funding period, compares the accomplishments with the goals and objectives of the project, and discusses the benefits of the work. The report provides complete listings of the products developed under the award and the key documents delivered to the DOE.

  13. Next Generation Nuclear Plant (NGNP) Prismatic HTGR Conceptual Design Project - Final Technical Report

    International Nuclear Information System (INIS)

    Saurwein, J.

    2011-01-01

    This report is the Final Technical Report for the Next Generation Nuclear Plant (NGNP) Prismatic HTGR Conceptual Design Project conducted by a team led by General Atomics under DOE Award DE-NE0000245. The primary overall objective of the project was to develop and document a conceptual design for the Steam Cycle Modular Helium Reactor (SC-MHR), which is the reactor concept proposed by General Atomics for the NGNP Demonstration Plant. The report summarizes the project activities over the entire funding period, compares the accomplishments with the goals and objectives of the project, and discusses the benefits of the work. The report provides complete listings of the products developed under the award and the key documents delivered to the DOE.

  14. Fiscal 1998 research report. Research on the possibility of promoting CDM project through technology transfer with plant exports; 1998 nendo chosa hokokusho. Plant yushutsugata gijutsu iten wo tsujita CDM project suishin kanosei ni kansuru chosa hokokusho

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-03-01

    Study was made on promotion of CDM (clean development mechanism) project through technology transfer with plant exports. Although CDM system was provided in COP3 on climate change held in Kyoto in 1997, its detailed rules including project approval are yet undecided, and only the schedule to provide the detailed rules until COP6 in 2000 was decided in COP4 in 1998. The common recognition that the CDM project with plant exports produces various merits for both Japan and the partner country is increasing. However, from the viewpoint of forming concrete CDM projects, most Japanese enterprises are passive in approach to the CDM project because of no detailed design of CDM, uncertain profitability and procedures, and avoidance of additional burdens. Plant export is also difficult because of the fact that assessment of a new project is difficult. Enterprises' deeper recognition on the CDM project, and a governmental integrated support system are desirable. (NEDO)

  15. Probabilistic cost estimating of nuclear power plant construction projects

    International Nuclear Information System (INIS)

    Finch, W.C.; Perry, L.W.; Postula, F.D.

    1978-01-01

    This paper shows how to identify and isolate cost accounts by developing probability trees down to component levels as justified by value and cost uncertainty. Examples are given of the procedure for assessing uncertainty in all areas contributing to cost: design, factory equipment pricing, and field labor and materials. The method of combining these individual uncertainties is presented so that the cost risk can be developed for components, systems and the total plant construction project. Formats which enable management to use the probabilistic cost estimate information for business planning and risk control are illustrated. Topics considered include code estimate performance, cost allocation, uncertainty encoding, probabilistic cost distributions, and interpretation. Effective cost control of nuclear power plant construction projects requires insight into areas of greatest cost uncertainty and a knowledge of the factors which can cause costs to vary from the single value estimates. It is concluded that probabilistic cost estimating can provide the necessary assessment of uncertainties both as to the cause and the consequences

  16. Westinghouse Hanford Company special nuclear material vault storage study

    International Nuclear Information System (INIS)

    Borisch, R.R.

    1996-01-01

    Category 1 and 2 Special Nuclear Materials (SNM) require storage in vault or vault type rooms as specified in DOE orders 5633.3A and 6430.1A. All category 1 and 2 SNM in dry storage on the Hanford site that is managed by Westinghouse Hanford Co (WHC) is located in the 200 West Area at Plutonium Finishing Plant (PFP) facilities. This document provides current and projected SNM vault inventories in terms of storage space filled and forecasts available space for possible future storage needs

  17. 3D digital dynamic management of maintenance projects for nuclear power plant

    International Nuclear Information System (INIS)

    Wang Baizhong; Luo Yalin; Fang Hao; Ma Li; Zhang Jie; Wang Ruobing; Xie Min

    2005-01-01

    The whole process for the application of digital plant technique in the equipment transport in reactor building and the dynamic management of the spatial arrangement in Daya Bay Nuclear Power Station was introduced in the paper. The establishment of 3D digital Daya Bay plant, and the method and procedure to apply it in the nuclear power plant maintenance project have been discussed. This project utilizes the outer database to preserve the maintenance status of equipments, and avoids the damage or changing of the original 3D final model. Based on the maintenance procedure, the spatial arrangement and schedule for the maintenance of nuclear power station have been simulated and optimized for the whole process. This technique can simulate and optimize the arrangement and spatial arrangement for maintenance in limited space. It has been applied successfully in the reactor vessel head replacement for Unit 2 of Daya Bay NPP to shorten the time for key routes and the total time of this project by 16 hours and 92.5 hours, respectively. (author)

  18. Large scale PV plants - also in Denmark. Project report

    Energy Technology Data Exchange (ETDEWEB)

    Ahm, P [PA Energy, Malling (Denmark); Vedde, J [SiCon. Silicon and PV consulting, Birkeroed (Denmark)

    2011-04-15

    Large scale PV (LPV) plants, plants with a capacity of more than 200 kW, has since 2007 constituted an increasing share of the global PV installations. In 2009 large scale PV plants with cumulative power more that 1,3 GWp were connected to the grid. The necessary design data for LPV plants in Denmark are available or can be found, although irradiance data could be improved. There seems to be very few institutional barriers for LPV projects, but as so far no real LPV projects have been processed, these findings have to be regarded as preliminary. The fast growing number of very large scale solar thermal plants for district heating applications supports these findings. It has further been investigated, how to optimize the lay-out of LPV plants. Under the Danish irradiance conditions with several winter months with very low solar height PV installations on flat surfaces will have to balance the requirements of physical space - and cost, and the loss of electricity production due to shadowing effects. The potential for LPV plants in Denmark are found in three main categories: PV installations on flat roof of large commercial buildings, PV installations on other large scale infrastructure such as noise barriers and ground mounted PV installations. The technical potential for all three categories is found to be significant and in the range of 50 - 250 km2. In terms of energy harvest PV plants will under Danish conditions exhibit an overall efficiency of about 10 % in conversion of the energy content of the light compared to about 0,3 % for biomass. The theoretical ground area needed to produce the present annual electricity consumption of Denmark at 33-35 TWh is about 300 km2 The Danish grid codes and the electricity safety regulations mention very little about PV and nothing about LPV plants. It is expected that LPV plants will be treated similarly to big wind turbines. A number of LPV plant scenarios have been investigated in detail based on real commercial offers and

  19. Strategically oriented project management of the decommissioning of nuclear power plants; Strategieorientiertes Projektmanagement der Stilllegung von Kernkraftwerken

    Energy Technology Data Exchange (ETDEWEB)

    Kemmeter, Sascha [Conscore GmbH, Duesseldorf (Germany); Woempener, Andreas [Duisburg-Essen Univ., Duisburg (Germany). Lehrstuhl fuer ABWL und Controlling

    2013-12-15

    Due to the politically induced change of the energy sector in Germany, the operators of nuclear power plants had to react and to deal with completely new conditions concerning the decommissioning of their plants on short notice. Therefore the operators have to devise new strategies for controlling their decommissioning and dismantling projects in a short amount of time and most often similarly for several plants. Two fundamental procedures are possible for the successful controlling of these dismantling projects: a centralized or a decentralized management organization. How these project control processes can be realized in an optimal way, is, next to other economic specifications of the dismantling of nuclear power plants, the topic of a new research project of the Chair of Management Accounting at the University Duisburg-Essen. In that process, results and experiences from other research and practical projects concerning general large-scale projects are being used. Selected findings have been compiled and are being discussed in this paper. (orig.)

  20. Solar Pilot Plant project review No. 9, May 4--5, 1977. CDRL item 10

    Energy Technology Data Exchange (ETDEWEB)

    None

    1977-01-01

    Drawings and illustrations for the project review are presented. These are included for the 10 MW(e) solar pilot plant, the collector subsystem, the receiver subsystem, the electrical power generation system and balance of plant, plant controls and transient analysis, availability and safety, pilot and commercial plant designs, and summary and recommendations. (MHR)

  1. DEPRESIÓN EN VIGOR POR ENDOGAMIA Y HETEROSIS PARA EL RENDIMIENTO Y SUS COMPONENTES EN ZAPALLO Cucurbita moschata Duch. Ex Poir INBREEDING DEPRESSION AND HETEROSIS FOR YIELD AND ITS COMPONENTS IN PUMPKIN Cucurbita moschata Duch. Ex Poir

    Directory of Open Access Journals (Sweden)

    Miguel Mariano Espitia Camacho

    2006-06-01

    Full Text Available El estudio tuvo como objetivos estimar la depresión por endogamia (DE y cuatro tipos de heterosis: promedio general (HP, promedio de progenitores (HM, heterobeltiosis (HB y útil (HU, en dos dialélos [uno entre cinco variedades (V y el otro entre cinco líneas endogamicas S1 (LS1, derivadas de éstas], para el rendimiento por planta (PFP, número de frutos por planta (NFP y peso promedio de fruto (PPF. Los 30 genotipos se evaluaron en el municipio de Candelaria (Valle del Cauca, Colombia, en un diseño de bloques completos al azar con cinco repeticiones. Se presentaron diferencias significativas (p 40 % y HU (>60 % en PFP.With the goal of estimating inbreeding depression (DE and the four types of heterosis: general average (HP, mean (HM, heterobeltiosis (HB and standard (HU, in two diallelic [one among five cross pollinated varieties (VAR and the other among five self-pollinated lines S1(LS1, derived from these], for yield/plant (PFP, number of fruits/plant (NFP and weight/fruit (PPF. The 30 genotypes were evaluated using a complete randomized design with five replicates in Candelaria (Valle del Cauca, Colombia . Significant differences (p 40 % and HU (>60 % in PFP.

  2. Signal validation of SPDS variables for Westinghouse and Combustion Engineering plants - an EPRI project

    International Nuclear Information System (INIS)

    Anon.

    1987-01-01

    Signal validation in the context of this project is the process of combining information from multiple plant sensors to produce highly reliable information about plant conditions. High information reliability is achieved by the use of redundant sources of information and by the inherent detection, identification, and isolation of faulty signals. The signal validation methodology that has been developed in previous EPRI-sponsored projects has been enhanced and applied toward validation of critical safety-related SPDS signals in the Northeast Utilities Millstone 3 Westinghouse PWR plant and the Millstone 2 Combustion Engineering PWR plant. The designs were implemented in FORTRAN software and tested off-line using recorded plant sensor data, RETRAN-generated simulation data, and data to exercise software logic branches and the integration of software modules. Designs and software modules have been developed for 15 variables to support six PWR SPDS critical safety functions as required by a utility advisory group attached to the project. The signal validation process automates a task currently performed by plant operators and does so with consistent, verified logic regardless of operator stress and training level. The methodology uses a simple structure of generic software blocks, a modular implementation, and it performs effectively within the processor and memory constraints of modern plant process computers. The ability to detect and isolate sensor failures with greater sensitivity, robustness, and coverage of common-cause failures should ultimately lead to improved plant availability, efficiency, and productivity

  3. The reliability evaluation of reclaimed water reused in power plant project

    Science.gov (United States)

    Yang, Jie; Jia, Ru-sheng; Gao, Yu-lan; Wang, Wan-fen; Cao, Peng-qiang

    2017-12-01

    The reuse of reclaimed water has become one of the important measures to solve the shortage of water resources in many cities, But there is no unified way to evaluate the engineering. Concerning this issue, it took Wanneng power plant project in Huai city as a example, analyzed the reliability of wastewater reuse from the aspects of quality in reclaimed water, water quality of sewage plant, the present sewage quantity in the city and forecast of reclaimed water yield, in particular, it was necessary to make a correction to the actual operation flow rate of the sewage plant. the results showed that on the context of the fluctuation of inlet water quality, the outlet water quality of sewage treatment plants is basically stable, and it can meet the requirement of circulating cooling water, but suspended solids(SS) and total hardness in boiler water exceed the limit, and some advanced treatment should be carried out. In addition, the total sewage discharge will reach 13.91×104m3/d and 14.21×104m3/d respectively in the two planning level years of the project. They are greater than the normal collection capacity of the sewage system which is 12.0×104 m3/d, and the reclaimed water yield can reach 10.74×104m3/d, which is greater than the actual needed quantity 8.25×104m3/d of the power plant, so the wastewater reuse of this sewage plant are feasible and reliable to the power plant in view of engineering.

  4. Plutonium Finishing Plant (PFP) Safety Class and Safety Significant Commercial Grade Items (CGI) Critical Characteristic

    International Nuclear Information System (INIS)

    THOMAS, R.J.

    2000-01-01

    This document specifies the critical characteristics for Commercial Grade Items (CGI) procured for use in the Plutonium Finishing Plant as required by HNF-PRO-268 and HNF-PRO-1819. These are the minimum specifications that the equipment must meet in order to properly perform its safety function. There may be several manufacturers or models that meet the critical characteristics of any one item

  5. Issues and measures in the design process from the perspective of risk management of construction projects. study of power plant construction projects accident cases

    International Nuclear Information System (INIS)

    Iwahara, Hirohiko; Shiraki, Wataru; Inomo, Hitoshi; Hasegawa, Syuichi

    2015-01-01

    Construction of power plants, foundation work, consisting of a wide variety of construction work, such as plant equipment work. And, civil engineering, technician electrical such as different engineering field, is a comprehensive construction project that works for the design conditions of the structure. However, if the cooperation design conditions is not sufficient, as a construction project, the optimal structures may not be said to have been built. As a result, total cost or increased, including the initial cost of the end construction projects, it is be a cause of the accident. Previous studies, plant equipment construction, is related to safety management and risk of foundation work such as individual construction were many. In this paper, as an example the power plant construction, and performs the following discussion from the point of view of risk management of large-scale construction projects that these individual construction work together with each other. The importance of design conditions cooperation, (1) 'Challenges and countermeasures of ordering method of construction projects', to verify from the (2) 'actually happened substation foundation displacement accident'. And on whether or not the construction project order institutions can be involved in the design from the site preparation stage, we study (3) for 'construction work scope and risk control the construction project ordering institutions to implement' the risk to the natural disaster (earthquake). From these, we describe the challenges and measures in the construction project of the design process. (author)

  6. Decommissioning project of commercial nuclear power plant

    International Nuclear Information System (INIS)

    Karigome, S.

    2008-01-01

    Decommissioning project of commercial nuclear power plant in Japan was outlined. It is expected that the land, after the decommissioning of commercial nuclear power plants, will serve as sites for new plants. Steps will be taken to reduce the amount of wastes generated and to recycle/reuse them. Wastes with a radioactivity concentration below the 'clearance level' need not be dealt with as radioactive material, and may be handled in the same way as conventional wastes. The Tokai-1 power station, a 166 MWe carbon dioxide cooled reactor which closed down in 1998, is being decommissioned and the first ten years as 'safe storage' to allow radioactivity to decay. Non-reactor grade components such as turbines were already removed, heat exchanger dismantling started and the reactor will be dismantled, the buildings demolished and the site left ready for reuse. All radioactive wastes will be classified as low-level wastes in three categories and will be buried under the ground. The total cost will be 88.5 billion yen -34.7 billion for dismantling and 53.8 billion for waste treatment including the graphite moderator. (T. Tanaka)

  7. I and C systems refurbishment projects for plant life extension

    International Nuclear Information System (INIS)

    Andrashov, A.A.; Sklyar, V.V.; Siora, A.A.

    2012-01-01

    This paper describes the approach to implementation of Nuclear Power Plants (NPPs) Instrumentation and Control (I and C) systems refurbishment projects using Field Programmable Gate Array (FPGA)-based platform. The analysis identifying advantages of refurbishment projects for NPPs is performed. The main goals of the utilities with respect to refurbishment of NPPs I and C systems are outlined. The advantages of FPGA technology application for NPP I and C systems are described. Regulatory framework of FPGA technology for NPPs I and C systems is presented. General principles which may be used for implementation of NPPs I and C system refurbishment projects are presented. The experience of Research and Production Corporation (RPC) Radiy in implementation of NPPs I and C system refurbishment projects is considered. (author)

  8. Case study: Proposed application of project management techniques for construction of nuclear power plant in Malaysia

    International Nuclear Information System (INIS)

    Syahirah Abdul Rahman; Phongsakorn Prak Tom; Wan Abd Hadi Wan Abu Bakar; Shaharum Ramli

    2010-01-01

    This study discusses the techniques of project management for the construction of nuclear power plants that can be used in Malaysia. Nuclear power reactors are expected to apply is the categories of Gen III + reactor where it is safer and more modern than the first generation of reactors built in the 1970s. The objective of this study is that the construction of this reactor to be completed by the stipulated time and not exceed the cost estimates. In addition, project management is also able to meet all the specifications and achieve the quality standard. In this study, the techniques used in project management to ensure the success of construction projects of nuclear power plants are a Gantt Chart, CPM/ PERT and Microsoft Project. From the study, found that these techniques can assist in facilitating the management of the project for the construction of nuclear power plants to ensure that the estimated time and cost can be managed more effectively as well as quality of care. (author)

  9. Preliminary safety evaluation for the plutonium stabilization and packaging system

    International Nuclear Information System (INIS)

    Shapley, J.E.

    1997-01-01

    This Preliminary Safety Evaluation (PSE) describes and analyzes the installation and operation of the Plutonium Stabilization and Packaging System (SPS) at the Plutonium Finishing Plant (PFP). The SPS is a combination of components required to expedite the safe and timely storage of Plutonium (Pu) oxide. The SPS program will receive site Pu packages, process the Pu for storage, package the Pu into metallic containers, and safely store the containers in a specially modified storage vault. The location of the SPS will be in the 2736- ZB building and the storage vaults will be in the 2736-Z building of the PFP, as shown in Figure 1-1. The SPS will produce storage canisters that are larger than those currently used for Pu storage at the PFP. Therefore, the existing storage areas within the PFP secure vaults will require modification. Other modifications will be performed on the 2736-ZB building complex to facilitate the installation and operation of the SPS

  10. Angra 1 nuclear power plant full scope simulator development project

    Energy Technology Data Exchange (ETDEWEB)

    Selvatici, Edmundo; Castanheira, Luiz Carlos C.; Silva Junior, Nilo Garcia da, E-mail: edsel@eletronuclear.gov.br, E-mail: lccast@eletronuclear.gov.br, E-mail: nilogar@eletronuclear.gov.br [Eletrobras Termonuclear S.A. (SCO/ELETRONUCLEAR), Angra dos Reis, RJ (Brazil). Superintendencia de Coordenacao da Operacao; Zazo, Francisco Javier Lopez; Ruiz, Jose Antonio, E-mail: jlopez@tecnatom.es, E-mail: jaruiz@tecnatom.es [Tecnatom S.A., San Sebastian de los Reyes, Madrid (Spain)

    2015-07-01

    Specific Full Scope Simulators are an essential tool for training NPP control room operators, in the formation phase as well as for maintaining their qualifications. In the last years availability of a Plant specific simulator has also become a Regulator requirement for Nuclear Power Plant operation. By providing real-time practical training for the operators, the use of a simulator allows improving the operator's performance, reducing the number of unplanned shutdowns and more effective response to abnormal and emergency operating conditions. It can also be used, among other uses, to validate procedures, test proposed plant modifications, perform engineering studies and to provide operation training for the technical support staff of the plant. The NPP site, in Angra dos Reis-RJ, Brazil, comprises the two units in operation, Unit 1, 640 MWe, Westinghouse PWR and Unit 2, 1350 MWe, KWU/Areva PWR and one unit in construction, Unit 3, 1405 MWe, KWU/Areva PWR, of the same design of Angra 2. Angra 2 has had its full scope simulator from the beginning, however this was not the case of Angra 1, that had to train its operators abroad, due to lack of a specific simulator. Eletronuclear participated in all the phases of the project, from data supply to commissioning and validation. The Angra 1 full scope simulator encompasses more than 80 systems of the plant including the Primary system, reactor core and associated auxiliary systems, the secondary system and turbo generator as well as all the Plant operational and safety I and C. The Angra 1 Main Control Room panels were reproduced in the simulator control room as well as the remote shutdown panels that are outside the control room. This paper describes the project for development of the Angra 1 NPP Full Scope Simulator, supplied by Tecnatom S.A., in the period of Feb.2012 to Feb.2015. (author)

  11. Angra 1 nuclear power plant full scope simulator development project

    International Nuclear Information System (INIS)

    Selvatici, Edmundo; Castanheira, Luiz Carlos C.; Silva Junior, Nilo Garcia da

    2015-01-01

    Specific Full Scope Simulators are an essential tool for training NPP control room operators, in the formation phase as well as for maintaining their qualifications. In the last years availability of a Plant specific simulator has also become a Regulator requirement for Nuclear Power Plant operation. By providing real-time practical training for the operators, the use of a simulator allows improving the operator's performance, reducing the number of unplanned shutdowns and more effective response to abnormal and emergency operating conditions. It can also be used, among other uses, to validate procedures, test proposed plant modifications, perform engineering studies and to provide operation training for the technical support staff of the plant. The NPP site, in Angra dos Reis-RJ, Brazil, comprises the two units in operation, Unit 1, 640 MWe, Westinghouse PWR and Unit 2, 1350 MWe, KWU/Areva PWR and one unit in construction, Unit 3, 1405 MWe, KWU/Areva PWR, of the same design of Angra 2. Angra 2 has had its full scope simulator from the beginning, however this was not the case of Angra 1, that had to train its operators abroad, due to lack of a specific simulator. Eletronuclear participated in all the phases of the project, from data supply to commissioning and validation. The Angra 1 full scope simulator encompasses more than 80 systems of the plant including the Primary system, reactor core and associated auxiliary systems, the secondary system and turbo generator as well as all the Plant operational and safety I and C. The Angra 1 Main Control Room panels were reproduced in the simulator control room as well as the remote shutdown panels that are outside the control room. This paper describes the project for development of the Angra 1 NPP Full Scope Simulator, supplied by Tecnatom S.A., in the period of Feb.2012 to Feb.2015. (author)

  12. Hydroelectric power plant project on the Coulonge River: Report of inquiry and public hearing

    International Nuclear Information System (INIS)

    1992-01-01

    A hydroelectric power plant is proposed for the Coulonge River, a tributary of the Ottawa River in Quebec. Water would be taken from the river through a 609 m tunnel to the plant, which would contain two Francis turbines with a total installed power of 16.2 MW operating under a net head of 43 m and a water flow rate of 21.5 m 3 /s. Other works would be necessary upstream for controlling flow and protecting the intake. Total cost for the two-year construction project is estimated at $28 million and annual revenues are forecast at $6 million. An inquiry and public hearing were held to consider the biophysical, social, economic, and cultural impacts of the proposed hydroelectric project. Results of the hearing are summarized in such areas as legal aspects, environmental quality, water rights, land use, job creation, effects on tourism and recreation, effects on wildlife, water level fluctuations, water quality, and safety. The economic justification for the project is discussed with reference to electricity demand, economic viability, utilization factors, and policies that favor construction of small-scale hydroelectric plants. The project was not found to bring sufficient benefits to the region in which it was to be situated and would not be authorized unless Hydro-Quebec tariff policy with respect to small hydro plants was modified and unless the project sponsor compensates the regional municipality. 13 refs., 11 figs., 4 tabs

  13. Emissions from decentralised CHP plants 2007 - Energinet.dk Environmental project no. 07/1882

    DEFF Research Database (Denmark)

    Nielsen, Malene; Nielsen, Ole-Kenneth; Thomsen, Marianne

    Updated emission factors for decentralised combined heat and power (CHP) plants with a capacity project emission measurements as well as emission measurements performed in recent years that were collected. The emission factors valid for 2006/2007 have been...... estimated for the plant technologies: Municipal solid waste (MSW) incineration plants, plants combusting straw or wood, natural gas fuelled reciprocating engines, biogas fuelled engines, natural gas fuelled gas turbines, gas oil fuelled reciprocating engines, gas oil fuelled gas turbines, steam turbines...

  14. Olkiluoto 1 and 2 - Plant efficiency improvement and lifetime extension-project (PELE) implemented during outages 2010 and 2011

    Energy Technology Data Exchange (ETDEWEB)

    Kosonen, M.; Hakola, M. [Teollisuuden Voima Oyj, F- 27160 Eurajoki (Finland)

    2012-07-01

    Teollisuuden Voima Oyj (TVO) is a non-listed public company founded in 1969 to produce electricity for its stakeholders. TVO is the operator of the Olkiluoto nuclear power plant. TVO follows the principle of continuous improvement in the operation and maintenance of the Olkiluoto plant units. The PELE project (Plant Efficiency Improvement and Lifetime Extension), mainly completed during the annual outages in 2010 and 2011, and forms one part of the systematic development of Olkiluoto units. TVO maintains a long-term development program that aims at systematically modernizing the plant unit systems and equipment based on the latest technology. According to the program, the Olkiluoto 1 and Olkiluoto 2 plant units are constantly renovated with the intention of keeping them safe and reliable, The aim of the modernization projects is to improve the safety, reliability, and performance of the plant units. PELE project at Olkiluoto 1 was done in 2010 and at Olkiluoto 2 in 2011. The outage length of Olkiluoto 1 was 26 d 12 h 4 min and Olkiluoto 2 outage length was 28 d 23 h 46 min. (Normal service-outage is about 14 days including refueling and refueling-outage length is about seven days. See figure 1) The PELE project consisted of several single projects collected into one for coordinated project management. Some of the main projects were as follows: - Low pressure turbines: rotor, stator vane, casing and turbine instrumentation replacement. - Replacement of Condenser Cooling Water (later called seawater pumps) pumps - Replacement of inner isolation valves on the main steam lines. - Generator and the generator cooling system replacement. - Low voltage switchgear replacement. This project will continue during future outages. PELE was a success. 100 TVO employees and 1500 subcontractor employees participated in the project. The execution of the PELE projects went extremely well during the outages. The replacement of the low pressure turbines and seawater pumps improved the

  15. Olkiluoto 1 and 2 - Plant efficiency improvement and lifetime extension-project (PELE) implemented during outages 2010 and 2011

    International Nuclear Information System (INIS)

    Kosonen, M.; Hakola, M.

    2012-01-01

    Teollisuuden Voima Oyj (TVO) is a non-listed public company founded in 1969 to produce electricity for its stakeholders. TVO is the operator of the Olkiluoto nuclear power plant. TVO follows the principle of continuous improvement in the operation and maintenance of the Olkiluoto plant units. The PELE project (Plant Efficiency Improvement and Lifetime Extension), mainly completed during the annual outages in 2010 and 2011, and forms one part of the systematic development of Olkiluoto units. TVO maintains a long-term development program that aims at systematically modernizing the plant unit systems and equipment based on the latest technology. According to the program, the Olkiluoto 1 and Olkiluoto 2 plant units are constantly renovated with the intention of keeping them safe and reliable, The aim of the modernization projects is to improve the safety, reliability, and performance of the plant units. PELE project at Olkiluoto 1 was done in 2010 and at Olkiluoto 2 in 2011. The outage length of Olkiluoto 1 was 26 d 12 h 4 min and Olkiluoto 2 outage length was 28 d 23 h 46 min. (Normal service-outage is about 14 days including refueling and refueling-outage length is about seven days. See figure 1) The PELE project consisted of several single projects collected into one for coordinated project management. Some of the main projects were as follows: - Low pressure turbines: rotor, stator vane, casing and turbine instrumentation replacement. - Replacement of Condenser Cooling Water (later called seawater pumps) pumps - Replacement of inner isolation valves on the main steam lines. - Generator and the generator cooling system replacement. - Low voltage switchgear replacement. This project will continue during future outages. PELE was a success. 100 TVO employees and 1500 subcontractor employees participated in the project. The execution of the PELE projects went extremely well during the outages. The replacement of the low pressure turbines and seawater pumps improved the

  16. Beyond ectomycorrhizal bipartite networks: projected networks demonstrate contrasted patterns between early- and late-successional plants in Corsica.

    Directory of Open Access Journals (Sweden)

    Adrien eTaudiere

    2015-10-01

    Full Text Available The ectomycorrhizal (ECM symbiosis connects mutualistic plants and fungal species into bipartite networks. While links between one focal ECM plant and its fungal symbionts have been widely documented, systemic views of ECM networks are lacking, in particular, concerning the ability of fungal species to mediate indirect ecological interactions between ECM plant species (projected-ECM networks. We assembled a large dataset of plant-fungi associations at the species level and at the scale of Corsica using molecular data and unambiguously host-assigned records to: (i examine the correlation between the number of fungal symbionts of a plant species and the average specialization of these fungal species, (ii explore the structure of the plant-plant projected network and (iii compare plant association patterns in regard to their position along the ecological succession. Our analysis reveals no trade-off between specialization of plants and specialization of their partners and a saturation of the plant projected network. Moreover, there is a significantly lower-than-expected sharing of partners between early- and late-successional plant species, with fewer fungal partners for early-successional ones and similar average specialization of symbionts of early- and late-successional plants. Our work paves the way for ecological readings of Mediterranean landscapes that include the astonishing diversity of below-ground interactions.

  17. A basic framework for managing time of nuclear plant projects

    International Nuclear Information System (INIS)

    Beck, J.R.

    1987-01-01

    One of the crucial problems that faces managers of nuclear power plant projects is how to obtain more effective and efficient utilization of their company's resources. Analysis of this problem showed that improvement was necessary in the time management area. Time management is one of the primary functions of project groups. Much has been written about planning and scheduling, and there are many modern techniques (CPM, PERT, etc.) available to a project group to manage time. So, why is time management still a problem? One reason is that nuclear projects are generally very complex and involve many organizations requiring the same resources. It is the intent of this paper to present a comprehensive and basic framework on which to either build a time management system or use as a basis to assess an existing system

  18. Stabilizing plutonium materials at Hanford: systems engineering for PFP transition project effort on DNFSB 94-1

    Energy Technology Data Exchange (ETDEWEB)

    Huber, T.E., Westinghouse Hanford

    1996-07-02

    This report discusses the basic objectives of the stabilization and packaging activities at the Plutonium Finishing Plant that satisfy the Defense Nuclear Facility Safety Board Recommendation 94-1 by transforming the plutonium materials at hanford into forms or conditions which are suitable for safe storage to appropriate storage criteria; or discard that meets appropriate waste acceptance criteria.

  19. North Plant co-generation project for South Davis County Sewer Improvement District

    Energy Technology Data Exchange (ETDEWEB)

    Rogers, L.S. [Aqua Environmental Services, Inc., Bountiful, UT (United States)

    1993-12-31

    In the summer of 1988, the South Davis County Sewer Improvement District (SDCSID) learned of a grant/loan program being administered by the Utah State Department of Energy(DOE) for projects that demonstrate new and innovative ways of conserving energy or utilizing renewable energy sources. The SDCSID applied for and received from the DOE both a grant and a no-interest loan to finance half of the cost of a co-generation project at the North Wastewater Treatment Plant. This co-generation project utilizes methane gas, a by-product of the anaerobic digestion process, to generate both electricity and heat that is used at the plant. The SDCSID calculated that at the current anaerobic gas production rate, a 140 KW engine generator could be run almost 24 hours a day. Approximately 75% of the current electrical needs at the North Plant are supplied by the 140 KW engine generator. Also, all of the heat necessary to raise the temperature of the incoming sludge to 95{degrees}F, and to heat four large buildings is supplied from the heat recovery system of the engine. The system utilizes an induction type generator to supply electricity, which is somewhat simpler to design and less expensive to install than a synchronous type system. An induction system utilizes the Electrical Utility`s incoming power to excite the generator to correct the phase so that is can be used by the loads in the plant. In addition, the SDCSID installed a second identical engine generator as a back-up and to peak shave. Plant effluent is used to cool the engines instead of air-cooling through radiators.

  20. Compost plant of Medellin - An economically viable project

    International Nuclear Information System (INIS)

    Bedoya V, Julian; Arango M, Carlos Andres

    1999-01-01

    The solid waste treatment facility of Empresas Varias de Medellln started operation of the 70's. The total investment in equipment and construction by 1971 was of about $ 36'000. 000 Colombian pesos, that by 1997 was valued at more than seven thousand million pesos $7.000'000. 000). The solid waste treatment facility was able to process 180 t/day, generating compost and recyclable by products (textile fibbers. paper, cardboard, glass, plastics, scrap metals) with commercial value. Operating expenses for the facility in 1972 were $2'187.742 to process 53.300 t/year in 296 working days. Revenues from compost and recyclable by products were $ 8 '791.280, with a positive balance of $ 6 '603.538. For those years debt annual payments were $ 3'919.372, giving a yearly profit of $ 2'684.165. Instead of debt payments a yearly charge of $ 7 '315. 240 can be made to account for equipment and construction costs; in addition land rent of $ 500000 per year should be charged to the plant. in this case the operational loss is of $ 1' 397.663 ($ 26/ t) that has to be covered by solid waste service charges. Under these conditions the project is not economically feasible, especially if taking solid wastes to Moravia has not cost at all. Twenty-five years later situation is different: transportation and final disposal costs in Curva de Rodas amount to more than $ 19. 000/t. expected total revenues for a similar project in 1997 could be $2.778' 000.000 and operational expenses for 365 days are estimated at $ 506' 000.000; yearly annual cost for construction and equipment amounts to $1. 411' 000.000 and land rental of $96'000.000 give a profit of close to $765 '000.000. Under these conditions the project is economically feasible and generates a profit: it may be even more attractive if the solid waste company pays a disposal fee, since it is saving room in Curva de Rodas. In order to obtain fully feasibility of the project requires: compost must be improved and positioned in the market

  1. Data base on dose reduction research projects for nuclear power plants

    International Nuclear Information System (INIS)

    Khan, T.A.; Yu, C.K.; Roecklein, A.K.

    1994-05-01

    This is the fifth volume in a series of reports that provide information on dose reduction research and health physics technology or nuclear power plants. The information is taken from two of several databases maintained by Brookhaven National Laboratory's ALARA Center for the Nuclear Regulatory Commission. The research section of the report covers dose reduction projects that are in the experimental or developmental phase. It includes topics such as steam generator degradation, decontamination, robotics, improvements in reactor materials, and inspection techniques. The section on health physics technology discusses dose reduction efforts that are in place or in the process of being implemented at nuclear power plants. A total of 105 new or updated projects are described. All project abstracts from this report are available to nuclear industry professionals with access to a fax machine through the ACEFAX system or a computer with a modem and the proper communications software through the ACE system. Detailed descriptions of how to access all the databases electronically are in the appendices of the report

  2. Baseline survey for rare plant species and native plant communities within the Kamehameha Schools 'Lupea Safe Harbor Planning Project Area, North Kona District, Island of Hawai'i

    Science.gov (United States)

    Jacobi, James; Warshauer, F. R.; Price, Jonathan

    2010-01-01

    Kamehameha Schools, in conjunction with several federal, state, and private organizations, has proposed to conduct conservation management on approximately 5,340 ha (~13,200 acres) of land they own in the vicinity of Kīpukalupea in the North Kona District on the island of Hawai'i. The goal of this program is to restore and enhance the habitat to benefit native plant and animal populations that are currently, or were formerly, found in this site. The initial phase of this project has been focused on various activities including conducting baseline surveys for bird and plant species so Kamehameha Schools could develop a Safe Harbor Agreement (SHA) for the proposed project lands relative to the habitat management and species reintroduction efforts they would like to conduct in the Lupea Project area. This report summarizes methods that were used to collect field data on plant species and communities within the project area, and the results of that initial survey. The information was used to calculate baseline values for all listed threatened or endangered plant species found, or expected to be found, within the project area, and to design a monitoring program to assess changes in plant communities and rare plant species relative to management activities over the duration of the SHA.

  3. Bid Preparation and Evaluation for Nuclear Power Plant Project Management

    International Nuclear Information System (INIS)

    Mohd Idris Taib, Mohd Khairulezwan Abdul Manan and Nur Farizan Amadzun

    2011-01-01

    Bid preparation and evaluation is one of the main activities in Nuclear Power Plant Project management. International Atomic Energy Agency guide and Korean experience was studied for Malaysian requirement in realization of first Nuclear Power Plant. Several aspects shall be taken into consideration such as political scenario, financial capabilities, sitting, human resource, technologies, fuel supplies and decommissioning for long term exceeded hundred years. Bidding process and activities is proposed for our country requirement. The main activities included but unlimited to Bid Invitation Specification, Bid Evaluation Process, Technical Evaluation, Economic Bid Evaluation and Contracting. On the end of day, Malaysia need safe and reliable Nuclear Power Plant. Malaysian Economic Transformation Programme also get benefit from spin-off localization products and services as well as Technology Transfer Programme. (author)

  4. Auxiliary feedwater system risk-based inspection guide for the South Texas Project nuclear power plant

    International Nuclear Information System (INIS)

    Bumgardner, J.D.; Nickolaus, J.R.; Moffitt, N.E.; Gore, B.F.; Vo, T.V.

    1993-12-01

    In a study sponsored by the US Nuclear Regulatory Commission (NRC), Pacific Northwest Laboratory has developed and applied a methodology for deriving plant-specific risk-based inspection guidance for the auxiliary feedwater (AFW) system at pressurized water reactors that have not undergone probabilistic risk assessment (PRA). This methodology uses existing PRA results and plant operating experience information. Existing PRA-based inspection guidance information recently developed for the NRC for various plants was used to identify generic component failure modes. This information was then combined with plant-specific and industry-wide component information and failure data to identify failure modes and failure mechanisms for the AFW system at the selected plants. South Texas Project was selected as a plant for study. The product of this effort is a prioritized listing of AFW failures which have occurred at the plant and at other PWRs. This listing is intended for use by the NRC inspectors in preparation of inspection plans addressing AFW risk important components at the South Texas Project plant

  5. Dustfall design of open coal yard in the power plant-a case study on the closed reconstruction project of coal storage yard in shengli power plant

    Science.gov (United States)

    Wang, Kunpeng; Ji, Weidong; Zhang, Feifei; Yu, Wei; Zheng, Runqing

    2018-02-01

    This thesis, based on the closed reconstruction project of the coal storage yard of Shengli Power Plant which is affiliated to Sinopec Shengli Petroleum Administration, first makes an analysis on the significance of current dustfall reconstruction of open coal yard, then summarizes the methods widely adopted in the dustfall of large-scale open coal storage yard of current thermal power plant as well as their advantages and disadvantages, and finally focuses on this project, aiming at providing some reference and assistance to the future closed reconstruction project of open coal storage yard in thermal power plant.

  6. Status of Pantex Plant Waste Management Project/program control system

    International Nuclear Information System (INIS)

    Price, Wesley J.; Matthews, William L.

    1992-01-01

    During a December 1990 Waste Management Program Review held in Albuquerque, New Mexico, the Waste Management and Operational Surety Division (WMOSD) introduced the project control system to be used for the Waste Management (WM) Operations Program. The system was entitled 'TRAC-WM' (Tracking and Control for Waste Management). The stated objective for this system was to establish a frame work for planning, managing, and controlling work within the WM program. As a result Mason and Hanger (the operating contractor at the Pantex Plant) initiated the development of a computerized waste management project tracking system. (author)

  7. Project quality management under EPC mode by the owner of nuclear power plant

    International Nuclear Information System (INIS)

    Xu Hui; Hu Miao

    2014-01-01

    As the first completely independent nuclear power project in China, Fangjiashan nuclear power project is constructed under EPC mode of general project contracting. This paper, taking the project as an example, aims to explore how the project owners carry out quality management for the installation project during the construction of the nuclear power plant based on EPC mode. It has certain reference value for the management of following nuclear power projects which adopting the EPC construction mode. It will play a positive role in improving China's overall self-management abilities in the nuclear power construction, and lay a solid foundation for follow-up nuclear power construction in China. (authors)

  8. Quality management in an international nuclear power plant project

    International Nuclear Information System (INIS)

    Brion, J.; Crustin, J.

    1975-01-01

    SNR (Schneller Natriumgekuehlter Reaktor) is the fast reactor power plant being erected at Kalkar, Federal German Republic. Quality management in this project is a contractual obligation. Quality management is subdivided into quality engineering, set of actions performed before manufacturing, and quality control, set of material controls performed during fabrication. The two successive phases of the quality management are presented. The difficulties and improvment possibilities are discussed [fr

  9. Tank 241-Z-361 Sludge Retrieval and Treatment Alternatives

    International Nuclear Information System (INIS)

    HAMPTON, B.K.

    2000-01-01

    The Plutonium Finishing Plant (PFP) Tank 241-Z-361 (Z-361) contains legacy sludge resulting from waste discharges from past missions at PFP. A sketch of the tank is shown in Figure 1. In this view various risers and penetrations are shown along with the sludge level depicted by the horizontal line halfway up the tank, and the ground level depicted by the horizontal line above the tank. The HEPA filter installed for breathing is also shown on one of the risers

  10. Status of project design work for a German reprocessing plant

    International Nuclear Information System (INIS)

    Lang, K.; Zuehlke, P.

    1976-01-01

    A reprocessing plant will be built within the framework of a comprehensive waste management center planned by the Federal Government to treat the fuel elements unloaded from German nuclear power stations. On the basis of an annual throughput of 1,400 te of uranium averaged over the life of the plant, the center will be able to serve between 45,000 and 50,000 MWe of installed nuclear generating capacity. A comprehensive conceptual design study of the reprocessing plant to be built has been completed on the basis of the operating experience accumulated at the Karlsruhe reprocessing plant and the development work carried out by the Karlsruhe Nuclear Research Center and in the light also of an intensive exchange of experience with British and French reprocessing companies within the framework of United Reprocessors GmbH. This conceptual design study is the foundation for the preliminary project to be carried out on a collaborative basis by KEWA and PWK. (orig.) [de

  11. A desk evaluation review of project POL/5/006 plant breeding using induced mutations. Project desk evaluation

    International Nuclear Information System (INIS)

    1993-01-01

    Projects POL/5/006 was initiated in 1985 to assist the Government of Poland in improving the mutation breeding efforts in the country to promote the development of new and higher yielding crop varieties. The difficult economic situation in the country at this time restricted the procurement of special equipment, spare parts and supplies from abroad and, therefore, impeded research and development work in this field. The project was implemented using a distinctive approach and design characterized by having six recipient institutions and the establishment of one central gamma-irradiation facility to be made available to all participating institutions for mutation induction. The project was formally closed in 1989. The review of project POL/5/006 was undertaken in accord with the expressed wishes of the Board of Governors for selected ex-post evaluations of completed projects. The main purpose of the review was to ascertain if the project objectives were achieved, and to determine what impact the technical assistance provided may have had on continued post-project and current plant breeding programmes in Poland

  12. A desk evaluation review of project POL/5/006 plant breeding using induced mutations. Project desk evaluation

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1993-09-14

    Projects POL/5/006 was initiated in 1985 to assist the Government of Poland in improving the mutation breeding efforts in the country to promote the development of new and higher yielding crop varieties. The difficult economic situation in the country at this time restricted the procurement of special equipment, spare parts and supplies from abroad and, therefore, impeded research and development work in this field. The project was implemented using a distinctive approach and design characterized by having six recipient institutions and the establishment of one central gamma-irradiation facility to be made available to all participating institutions for mutation induction. The project was formally closed in 1989. The review of project POL/5/006 was undertaken in accord with the expressed wishes of the Board of Governors for selected ex-post evaluations of completed projects. The main purpose of the review was to ascertain if the project objectives were achieved, and to determine what impact the technical assistance provided may have had on continued post-project and current plant breeding programmes in Poland.

  13. Project plan for the background soils project for the Paducah Gaseous Diffusion Plant, Paducah, Kentucky

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-09-01

    The Background Soils Project for the Paducah Gaseous Diffusion Plant (BSPP) will determine the background concentration levels of selected naturally occurring metals, other inorganics, and radionuclides in soils from uncontaminated areas in proximity to the Paducah Gaseous Diffusion Plant (PGDP) in Paducah, Kentucky. The data will be used for comparison with characterization and compliance data for soils, with significant differences being indicative of contamination. All data collected as part of this project will be in addition to other background databases established for the PGDP. The BSPP will address the variability of surface and near-surface concentration levels with respect to (1) soil taxonomical types (series) and (2) soil sampling depths within a specific soil profile. The BSPP will also address the variability of concentration levels in deeper geologic formations by collecting samples of geologic materials. The BSPP will establish a database, with recommendations on how to use the data for contaminated site assessment, and provide data to estimate the potential human and health and ecological risk associated with background level concentrations of potentially hazardous constituents. BSPP data will be used or applied as follows.

  14. Project plan for the background soils project for the Paducah Gaseous Diffusion Plant, Paducah, Kentucky

    International Nuclear Information System (INIS)

    1995-09-01

    The Background Soils Project for the Paducah Gaseous Diffusion Plant (BSPP) will determine the background concentration levels of selected naturally occurring metals, other inorganics, and radionuclides in soils from uncontaminated areas in proximity to the Paducah Gaseous Diffusion Plant (PGDP) in Paducah, Kentucky. The data will be used for comparison with characterization and compliance data for soils, with significant differences being indicative of contamination. All data collected as part of this project will be in addition to other background databases established for the PGDP. The BSPP will address the variability of surface and near-surface concentration levels with respect to (1) soil taxonomical types (series) and (2) soil sampling depths within a specific soil profile. The BSPP will also address the variability of concentration levels in deeper geologic formations by collecting samples of geologic materials. The BSPP will establish a database, with recommendations on how to use the data for contaminated site assessment, and provide data to estimate the potential human and health and ecological risk associated with background level concentrations of potentially hazardous constituents. BSPP data will be used or applied as follows

  15. RIBA Project - Risk-Informed approach for In-Service Inspection of Nuclear Power Plant Components. Project summary

    International Nuclear Information System (INIS)

    Lidbury, D.; Smith, G.

    2001-12-01

    The need for a European review of a Risk-Informed Approach for In-Service Inspection of Nuclear Power Plant Components (RIBA) was identified in 1998. This was as a priority item in the programme of activities conducted in the framework of the Council Resolutions of 22 July 1975 and of 18 June 1992 on the Technological Problems of Nuclear Safety. The RIBA Project was established in November 1999 as a 24-month Study Contract funded by the European Commission within the frame of the former DG XI WGCS (Working Group on Codes and Standards). The Study Contract was subsequently managed for the EC by DG TREN. The participants in RIBA were Serco Assurance (project coordinator), Ringhals AB, EDF, Tecnatom SA and Westinghouse Electric Europe. The work is presented in a summary report with the detailed results contained in three companion reports as follows: main conclusions and recommendations, Review of Existing Risk-Informed Methodologies, A Comparative Study of Risk-Informed In-Service Inspection Applications, Conclusions and Recommendations for Risk-Informed in-service inspection methodology applied to Nuclear Power Plants in Europe. (author)

  16. Literature review supporting assessment of potential radionuclides in the 291-Z exhaust ventilation

    International Nuclear Information System (INIS)

    Mahoney, L.A.; Ballinger, M.Y.; Jette, S.J.; Thomas, L.M. Glissmeyer, J.A.; Davis, W.E.

    1994-08-01

    This literature review was prepared to support a study conducted by Pacific Northwest Laboratory to assess the potential deposition and resuspension of radionuclides in the 291-Z ventilation exhaust building located in the 200 West Area of the US Department of Energy's Hanford Project near Richland, Washington. The filtered ventilation air from three of the facilities at the Plutonium Finishing Plant (PFP) complex are combined together in the 291-Z building before discharge through a common stack. These three facilities contributing filtered exhaust air to the discharge stream are (1) the PFP, also known as the Z-Plant or 234-5Z, (2) the Plutonium Reclamation Facility (PRF or 236-Z), and (3), the Waste Incinerator Building (WIB or 232-Z). The 291-Z building houses the exhaust fans that pull air from the 291-Z central collection plenum and exhausts the air to the stack. Section 2.0 of this report is a description of the physical characteristic of the ventilation system from the High Efficiency Particulate Air (HEPA) filters to the exhaust stack. A description of the processes performed in the facilities that are vented through 291-Z is given in Section 3.0. The description focuses on the chemical and physical forms of potential aerosols given off from the unit operations. A timeline of the operations and events that may have affected the deposition of material in the ventilation system is shown. Aerosol and radiation measurements taken in previous studies are also discussed. Section 4.0 discusses the factors that influence particle deposition and adhesion. Mechanisms of attachment and resuspension are covered with specific attention to the PFP ducts. Conclusions and recommendations are given in Section 5.0

  17. Completion of Belene Nuclear Power Plant: Project perspectives

    International Nuclear Information System (INIS)

    Bogdanov, D.

    2006-01-01

    The development of Belene NPP began with site selection in the 1970s, site characterisation in 1980-1981, and a decision to proceed in 1981. Construction was suspended for financial reasons in 1991. Now the state authorities have taken steps to continue the project. Despite the lengthy study period and the subsequent legislative changes, the evaluations indicate that Belene is a suitable NPP site. Studies of the Belene site have been completed and the conclusion is that the site is suitable and eligible for licensing for the construction of a NPP. In order to estimate the different options for completion of the project, different aspects of the plant were estimated. The information for different reactors was analysed, and quantitative assessment was performed by ranking the proposed facilities in different aspects of rated power, technology, safety, operation, licenseability (compliance to local regulations), etc. (author)

  18. Completion of Belene Nuclear Power Plant: Project perspectives

    Energy Technology Data Exchange (ETDEWEB)

    Bogdanov, D. [Risk Engineering Ltd., CREFID, 34 Totleben Blvd., Sofia 1606 (Bulgaria)]. E-mail: bogdanov@riskeng.bg

    2006-07-01

    The development of Belene NPP began with site selection in the 1970s, site characterisation in 1980-1981, and a decision to proceed in 1981. Construction was suspended for financial reasons in 1991. Now the state authorities have taken steps to continue the project. Despite the lengthy study period and the subsequent legislative changes, the evaluations indicate that Belene is a suitable NPP site. Studies of the Belene site have been completed and the conclusion is that the site is suitable and eligible for licensing for the construction of a NPP. In order to estimate the different options for completion of the project, different aspects of the plant were estimated. The information for different reactors was analysed, and quantitative assessment was performed by ranking the proposed facilities in different aspects of rated power, technology, safety, operation, licenseability (compliance to local regulations), etc. (author)

  19. National project : advanced robot for nuclear power plant

    International Nuclear Information System (INIS)

    Tsunemi, T.; Takehara, K.; Hayashi, T.; Okano, H.; Sugiyama, S.

    1993-01-01

    The national project 'Advanced Robot' has been promoted by the Agency of Industrial science and Technology, MITI for eight years since 1983. The robot for a nuclear plant is one of the projects, and is a prototype intelligent one that also has a three dimensional vision system to generate an environmental model, a quadrupedal walking mechanism to work on stairs and four fingered manipulators to disassemble a valve with a hand tool. Many basic technologies such as an actuator, a tactile sensor, autonomous control and so on progress to high level. The prototype robot succeeded functionally in official demonstration in 1990. More refining such as downsizing and higher intelligence is necessary to realize a commercial robot, while basic technologies are useful to improve conventional robots and systems. This paper presents application studies on the advanced robot technologies. (author)

  20. Current situation of the project of 3. and 4. block of nuclear power plant Mochovce

    International Nuclear Information System (INIS)

    Suchy, L.

    2006-01-01

    The contribution shows the basic information about the crucial milestone of 3. building and the current situation of the project of 3. and 4. block of the nuclear power plant Mochovce. Contribution also shows what activities were realized and what material in area of designation of the technical and safety standard of the project was elaborated in the past, the main activities planned for 2006 have been described, support for Feasibility Study elaborated by ENEL and description of the integrated management system. The basic thesis crucial for the next steps on the project of 3. and 4. block of Nuclear Power Plant Mochovce is presented in the conclusion

  1. Status of projects using reject heat for aquaculture and horticulture at power plants in the EEC

    International Nuclear Information System (INIS)

    Aston, R.J.

    1988-08-01

    Data collected mainly from an inventory of waste heat projects in the EEC prepared by Potentiel Energie of Paris covers 46 projects approximately half of which are fish farms and half horticultural projects mainly in the form of greenhouses. About a half of the projects are run on a commercial basis while the other half are Research and Development (R and D) or demonstrations. At least 18 species of fish and 18 species of plant are produced at the various projects but eels and potted plants are grown at more of the commercially orientated projects than any other produce. There has been a significant increase in the number of commercially run projects during the past 10-15 years and this trend is likely to continue in view of the considerable savings that can be made on fuel. The size and number of commercial projects in the UK compares favourably with those in other EEC countries. (author)

  2. RIMAP demonstration project. Pat. 1: Risk based life management of piping system in power plant Heilbronn

    International Nuclear Information System (INIS)

    Bareiss, J.; Puck, P.; Matschecko, B.; Jovanovic, A.; Balos, D.; Perunicic

    2003-01-01

    In the framework of EU project RIMAP [1] a new European Guideline for optimized risk based maintenance and inspection planning of industrial plants (RBLM - Risk Based Life Management) is being developed. The RIMAP project consists of the three clustered projects: development (RTD), demonstration (DEMO) and thematic network (TN). Current work and future, planned work in RIMAP demonstration project on applications of the RIMAP methodology in power plants are presented briefly in the first part of the paper. Also presented in the paper are the results of a preliminary analysis of piping system in power plant Heilbronn using the concept of risk-based monitoring as part of overall concept of risk-based life management. Shortly the following issues are discussed in the paper: identification of critical components, application of a multilevel risk analysis (..from ''screening'' to ''detailed analysis''), determination of PoF - Probability of Failure, determination of COF - Consequence of Failure and optimation of inspection and maintenance plan. (orig.)

  3. PFP MICON DCS computer software documentation

    Energy Technology Data Exchange (ETDEWEB)

    Silvan, G.R.

    1996-03-26

    This document contains the complete printout of the MICON A/S system configuration used in the Plutonium Finishing Plant. The document is divided into several volumes. Volume 1 covers the workstation display and configuration. All other volumes contain the controller configurations, or programs.

  4. PFP MICON DCS computer software documentation

    International Nuclear Information System (INIS)

    Silvan, G.R.

    1996-01-01

    This document contains the complete printout of the MICON A/S system configuration used in the Plutonium Finishing Plant. The document is divided into several volumes. Volume 1 covers the workstation display and configuration. All other volumes contain the controller configurations, or programs

  5. 77 FR 12002 - Mount Baker-Snoqualmie National Forest Site-Specific Invasive Plant Treatment Project and Forest...

    Science.gov (United States)

    2012-02-28

    ... Invasive Plant Treatment Project and Forest Plan Amendment Number 28 AGENCY: Forest Service, USDA. ACTION... Forest. The current Forest-wide treatment approach pre-dates the Pacific Northwest Region Invasive Plant... interdisciplinary analysis: (1) Whether or not to authorize site- specific invasive plant treatments using...

  6. RIMAP demonstration project. Risk-based life management of piping system in power plant Heilbronn

    International Nuclear Information System (INIS)

    Bareiss, J.; Buck, P.; Matschecko, B.; Jovanovic, A.; Balos, D.; Perunicic, M.

    2004-01-01

    In the framework of EU project RIMAP [Risk Based Inspection and Maintenance Procedures for European Industry (2000)] a new European Guideline for optimized risk based maintenance and inspection planning of industrial plants (RBLM, Risk Based Life Management) is being developed. The RIMAP project consists of the three clustered projects: - development (RTD); - demonstration (DEMO): - thematic network (TN). Current work and future, planned work in RIMAP demonstration project on applications of the RIMAP methodology in power plants are presented briefly in the first part of the paper. Also presented in the paper are the results of a preliminary analysis of piping system in power plant Heilbronn using the concept of risk-based monitoring as part of overall concept of risk-based life management. Shortly the following issues are discussed in the paper: - identification of critical components; - application of a multilevel risk analysis (...from 'screening' to 'detailed analysis'); - determination of PoF (Probability of Failure); - determination of CoF (Consequence of Failure); - optimation of inspection and maintenance plan. From our experience with the application of the RIMAP methodology the following conclusions can be drawn: The use of risk-based methods in inspection and maintenance of piping systems in power plants gives transparency to the decision making process and gives an optimized maintenance policy based on current state of the components. The results of the work clearly show the power of the proposed method for concentration on critical items: out of 64 monitored components 5 were selected for intermediate analysis and only 1 for the detailed analysis (probabilistic high temperature fracture mechanics)

  7. The Challenges of Preserving Historic Resources During the Deactivation and Decommissioning of Highly Contaminated Historically Significant Plutonium Process Facilities

    International Nuclear Information System (INIS)

    Hopkins, A.; Minette, M.; Sorenson, D.; Heineman, R.; Gerber, M.; Charboneau, S.; Bond, F.

    2006-01-01

    The Manhattan Project was initiated to develop nuclear weapons for use in World War II. The Hanford Engineer Works (HEW) was established in eastern Washington State as a production complex for the Manhattan Project. A major product of the HEW was plutonium. The buildings and process equipment used in the early phases of nuclear weapons development are historically significant because of the new and unique work that was performed. When environmental cleanup became Hanford's central mission in 1991, the Department of Energy (DOE) prepared for the deactivation and decommissioning of many of the old process facilities. In many cases, the process facilities were so contaminated, they faced demolition. The National Historic Preservation Act (NHPA) requires federal agencies to evaluate the historic significance of properties under their jurisdiction for eligibility for inclusion in the National Register of Historic Places before altering or demolishing them so that mitigation through documentation of the properties can occur. Specifically, federal agencies are required to evaluate their proposed actions against the effect the actions may have on districts, sites, buildings or structures that are included or eligible for inclusion in the National Register. In an agreement between the DOE's Richland Operations Office (RL), the Washington State Historic Preservation Office (SHPO) and the Advisory Council on Historic Preservation (ACHP), the agencies concurred that the Hanford Site Historic District is eligible for listing on the National Register of Historic Places and that a Site-wide Treatment Plan would streamline compliance with the NHPA while allowing RL to manage the cleanup of the Hanford Site. Currently, many of the old processing buildings at the Plutonium Finishing Plant (PFP) are undergoing deactivation and decommissioning. RL and Fluor Hanford project managers at the PFP are committed to preserving historical artifacts of the plutonium production process. They

  8. Compiling Utility Requirements For New Nuclear Power Plant Project

    International Nuclear Information System (INIS)

    Patrakka, Eero

    2002-01-01

    Teollisuuden Voima Oy (TVO) submitted in November 2000 to the Finnish Government an application for a Decision-in-Principle concerning the construction of a new nuclear power plant in Finland. The actual investment decision can be made first after a positive decision has been made by the Government and the Parliament. Parallel to the licensing process, technical preparedness has been upheld so that the procurement process can be commenced without delay, when needed. This includes the definition of requirements for the plant and preliminary preparation of bid inquiry specifications. The core of the technical requirements corresponds to the specifications presented in the European Utility Requirement (EUR) document, compiled by major European electricity producers. Quite naturally, an amount of modifications to the EUR document are needed that take into account the country- and site-specific conditions as well as the experiences gained in the operation of the existing NPP units. Along with the EUR-related requirements concerning the nuclear island and power generation plant, requirements are specified for scope of supply as well as for a variety of issues related to project implementation. (author)

  9. Project C-018H, 242-A Evaporator/PUREX Plant Process Condensate Treatment Facility, functional design criteria. Revision 3

    International Nuclear Information System (INIS)

    Sullivan, N.

    1995-01-01

    This document provides the Functional Design Criteria (FDC) for Project C-018H, the 242-A Evaporator and Plutonium-Uranium Extraction (PUREX) Plant Condensate Treatment Facility (Also referred to as the 200 Area Effluent Treatment Facility [ETF]). The project will provide the facilities to treat and dispose of the 242-A Evaporator process condensate (PC), the Plutonium-Uranium Extraction (PUREX) Plant process condensate (PDD), and the PUREX Plant ammonia scrubber distillate (ASD)

  10. Data base on dose reduction research projects for nuclear power plants: Volume 3

    Energy Technology Data Exchange (ETDEWEB)

    Khan, T.A.; Baum, J.W.

    1989-05-01

    This is the third volume in a series of reports that provide information on dose-reduction research and health physics technology for nuclear power plants. The information is taken from data base maintained by Brookhaven National Laboratory's ALARA Center for the Nuclear Regulatory Commission. This report presents information on 80 new projects, covering a wide area of activities. Projects on steam generator degradation, decontamination, robotics, improvement in reactor materials, and inspection techniques, among others, are described in the research section. The section on health physics technology includes some simple and very cost-effective projects to reduce radiation exposures. Collective dose data from the United States and other countries are also presented. In the conclusion, we suggest that although new advanced reactor design technology will eventually reduce radiation exposures at nuclear power plants to levels below serious concern, in the interim an aggressive approach to dose reduction remains necessary. 20 refs.

  11. Suitable Days for Plant Growth Disappear under Projected Climate Change: Potential Human and Biotic Vulnerability.

    Directory of Open Access Journals (Sweden)

    Camilo Mora

    2015-06-01

    Full Text Available Ongoing climate change can alter conditions for plant growth, in turn affecting ecological and social systems. While there have been considerable advances in understanding the physical aspects of climate change, comprehensive analyses integrating climate, biological, and social sciences are less common. Here we use climate projections under alternative mitigation scenarios to show how changes in environmental variables that limit plant growth could impact ecosystems and people. We show that although the global mean number of days above freezing will increase by up to 7% by 2100 under "business as usual" (representative concentration pathway [RCP] 8.5, suitable growing days will actually decrease globally by up to 11% when other climatic variables that limit plant growth are considered (i.e., temperature, water availability, and solar radiation. Areas in Russia, China, and Canada are projected to gain suitable plant growing days, but the rest of the world will experience losses. Notably, tropical areas could lose up to 200 suitable plant growing days per year. These changes will impact most of the world's terrestrial ecosystems, potentially triggering climate feedbacks. Human populations will also be affected, with up to ~2,100 million of the poorest people in the world (~30% of the world's population highly vulnerable to changes in the supply of plant-related goods and services. These impacts will be spatially variable, indicating regions where adaptations will be necessary. Changes in suitable plant growing days are projected to be less severe under strong and moderate mitigation scenarios (i.e., RCP 2.6 and RCP 4.5, underscoring the importance of reducing emissions to avoid such disproportionate impacts on ecosystems and people.

  12. New power plants in Europe? A challenge for project and quality management

    Energy Technology Data Exchange (ETDEWEB)

    Hartung, M. [RWE Technology GmbH, Essen (Germany)

    2010-07-01

    Against the backdrop of the age structure of the European power plant fleet and the EU's climate protection targets, a significant need for new-build and replacement power plant capacity is becoming apparent. RWE has thus founded RWE Technology in order to achieve its growth targets, but also to implement its ongoing power plant new-build programme in the order of no fewer than 12,000 MW in capacity. This company combines the project management and engineering capacity of the Group in order to meet the challenges posed by the fast-changing energy market. The following article explains the specific steps taken to achieve these objectives. (orig.)

  13. [New materia medica project: synthetic biology based bioactive metabolites research in medicinal plant].

    Science.gov (United States)

    Wang, Yong

    2017-03-25

    In the last decade, synthetic biology research has been gradually transited from monocellular parts or devices toward more complex multicellular systems. The emerging plant synthetic biology is regarded as the "next chapter" of synthetic biology. The complex and diverse plant metabolism as the entry point, plant synthetic biology research not only helps us understand how real life is working, but also facilitates us to learn how to design and construct more complex artificial life. Bioactive compounds innovation and large-scale production are expected to be breakthrough with the redesigned plant metabolism as well. In this review, we discuss the research progress in plant synthetic biology and propose the new materia medica project to lift the level of traditional Chinese herbal medicine research.

  14. The Waste Isolation Pilot Plant (WIPP) integrated project management system

    International Nuclear Information System (INIS)

    Olona, D.; Sala, D.

    1993-01-01

    The Waste Isolation Pilot Plant (WIPP), located 26 miles east of Carlsbad, New Mexico, is a research and development project of the Department of Energy (DOE), tasked with the mission of demonstrating the safe disposal of transuranic (TRU) radioactive wastes. This unique project was authorized by Congress in 1979 in response to the national need for long-term, safe methods for disposing of radioactive by-products from our national defense programs. The WIPP was originally established in December of 1979, by Public Law 96-164, DOE National Security and Military Applications of Nuclear Energy Authorization Act of 1980. Since the inception of the WIPP Project, work has continued to prepare the facility to receive TRU wastes. Studies continue to be conducted to demonstrate the safety of the WIPP facility in accordance with federal and state laws, state agreements, environmental regulations, and DOE Orders. The objectives of implementing an integrated project management system are to assure compliance with all regulatory and federal regulations, identify areas of concern, provide justification for funding, provide a management tool for control of program workscope, and establish a project baseline from which accountability and performance will be assessed. Program management and project controls are essential for the success of the WIPP Project. The WIPP has developed an integrated project management system to establish the process for the control of the program which has an expected total dollar value of $2B over the ten-year period from 1990-2000. The implementation of this project management system was motivated by the regulatory requirements of the project, the highly public environment in which the project takes place, limited funding and resources, and the dynamic nature of the project. Specific areas to be addressed in this paper include strategic planning, project organization, planning and scheduling, fiscal planning, and project monitoring and reporting

  15. Chemical and Radiochemical Composition of Thermally Stabilized Plutonium Oxide from the Plutonium Finishing Plant Considered as Alternate Feedstock for the Mixed Oxide Fuel Fabrication Facility

    International Nuclear Information System (INIS)

    Tingey, Joel M.; Jones, Susan A.

    2005-01-01

    Eighteen plutonium oxide samples originating from the Plutonium Finishing Plant (PFP) on the Hanford Site were analyzed to provide additional data on the suitability of PFP thermally stabilized plutonium oxides and Rocky Flats oxides as alternate feedstock to the Mixed Oxide Fuel Fabrication Facility (MFFF). Radiochemical and chemical analyses were performed on fusions, acid leaches, and water leaches of these 18 samples. The results from these destructive analyses were compared with nondestructive analyses (NDA) performed at PFP and the acceptance criteria for the alternate feedstock. The plutonium oxide materials considered as alternate feedstock at Hanford originated from several different sources including Rocky Flats oxide, scrap from the Remote Mechanical C-Line (RMC) and the Plutonium Reclamation Facility (PRF), and materials from other plutonium conversion processes at Hanford. These materials were received at PFP as metals, oxides, and solutions. All of the material considered as alternate feedstock was converted to PuO2 and thermally stabilized by heating the PuO2 powder at 950 C in an oxidizing environment. The two samples from solutions were converted to PuO2 by precipitation with Mg(OH)2. The 18 plutonium oxide samples were grouped into four categories based on their origin. The Rocky Flats oxide was divided into two categories, low- and high-chloride Rocky Flats oxides. The other two categories were PRF/RMC scrap oxides, which included scrap from both process lines and oxides produced from solutions. The two solution samples came from samples that were being tested at Pacific Northwest National Laboratory because all of the plutonium oxide from solutions at PFP had already been processed and placed in 3013 containers. These samples originated at the PFP and are from plutonium nitrate product and double-pass filtrate solutions after they had been thermally stabilized. The other 16 samples originated from thermal stabilization batches before canning at

  16. Acceptance test report for project C-157 ''T-Plant electrical upgrade''

    International Nuclear Information System (INIS)

    Jeppson, L.A.

    1997-01-01

    This Acceptance Test Report (ATR) documents for record purposes the field results, acceptance, and approvals of the completed acceptance test per WHC-SD-Cl57-ATP-001, Rev. 0, ''Acceptance Test Proceedure for Project C-157 'T Plant Electrical Upgrade''' The test was completed and approved without any problems or exceptions

  17. Acceptance test report for project C-157 ``T-Plant electrical upgrade``

    Energy Technology Data Exchange (ETDEWEB)

    Jeppson, L.A.

    1997-08-05

    This Acceptance Test Report (ATR) documents for record purposes the field results, acceptance, and approvals of the completed acceptance test per WHC-SD-Cl57-ATP-001, Rev. 0, ``Acceptance Test Proceedure for Project C-157 `T Plant Electrical Upgrade``` The test was completed and approved without any problems or exceptions.

  18. Southeast Regional Wastewater Treatment Plant Facilities Improvements Project and Geysers Effluent Pipeline Project. Draft EIR/EIS: Executive summary

    International Nuclear Information System (INIS)

    1994-01-01

    The Southeast Regional Wastewater Treatment Plant (SERWTP) Facilities Improvement Plan and Geysers Effluent Pipeline and Effluent Injection Project are proposed as a plan to provide expanded wastewater treatment capabilities and to dispose of the effluent by injection in The Geysers geothermal field for purposes of power production. The project is located predominantly in the County of Lake, California, and also in part of Sonoma County. The plan includes various conventional facilities improvements in wastewater treatment to a secondary level of treatment at the SWERWTP. The plan includes facilities to convey the treated effluent in a 26-mile, 24-inch inside diameter pipeline to the Southeast Geysers. The wastewater from the SERWTP would be supplemented by raw lake water diverted from nearby Clear Lake. At The Geysers, the effluent would be directed into a system of distribution lines to wells. In the geothermal reservoir, the water will be converted to steam and collected in production wells that will direct the steam to six existing power plants. This document is a summary of a combined full Environmental Impact Report (EIR) and Environmental Impact Statement (EIS). The EIR/EIS describes the environmental impacts of the various components of the project. Mitigation measures are suggested for reducing impacts to a less than significant level

  19. Completion of Mochovce 1 and 2 nuclear power plant project

    International Nuclear Information System (INIS)

    Valach, J.

    2000-01-01

    Commissioning of the Mochovce Nuclear Power Plant unit 2 fully completed the Mochovce unit 1 and 2 project. The power plant construction passed through a complicated evolution since early 80's. The genesis started with the change of the plant location due to a seismic resistance requirement raised by the former Czechoslovak Atomic Energy Commission, change of the design and contractor of the Instrumentation and Control system in early 90's, halt of construction in 1993 till 1996 due to a lack of funding, as well as a series of international reviews of safety aspects. All the obstacles had been overcome in the end, and completion works were re-started in 1996. Looking back to the unit 1 and 2 completion project, I would like to highlight some aspects of the project, particularly the level of safety, technical and organisational conditions, and terms of funding. The most important argument for completion of the plant was that VVER 440/213 reactor units were distinguished with very high level of passive safety, even overcoming Western-type PWR's in some aspects. The replacement of the original I and C system was another important contribution to the initial level of safety. International safety reviews performed at Mochovce NPP between 1990 and 1995 (Siemens, EdF, IAEA, RlSKAUDIT) confirmed the high level of safety of VVER 440/213 reactors, however, pointed out at some safety issues which had not been dealt with in the design. Those included e.g. the 'external risks', primary-to-secondary leaks, qualification of pressurizer safety valves, and others. It is necessary to stress that the Safety Improvement Programme defined for Mochovce NPP to comply with international standards did not become the most important part of the completion project due to external pressures, but based on natural requirements on nuclear power plant safety level generally accepted in 90's. The good example could be the seismic resistance of the plant which, though designed as seismic resistant

  20. Projecting labor demand and worker immigration at nuclear power plant construction sites: an evaluation of methodology

    International Nuclear Information System (INIS)

    Herzog, H.W. Jr; Schlottmann, A.M.; Schriver, W.R.

    1981-12-01

    The study evaluates methodology employed for the projection of labor demand at, and worker migration to, nuclear power plant construction sites. In addition, suggestions are offered as to how this projection methodology might be improved. The study focuses on projection methodologies which forecast either construction worker migration or labor requirements of alternative types of construction activity. Suggested methodological improvements relate both to institutional factors within the nuclear power plant construction industry, and to a better use of craft-specific data on construction worker demand/supply. In addition, the timeliness and availability of the regional occupational data required to support, or implement these suggestions are examined

  1. New concept for condition management of plants as a result of the KUNTO project. New operations approach reduces costs

    Energy Technology Data Exchange (ETDEWEB)

    McNiven, U.; Tamminen, L.

    1998-07-01

    IVO Generation Services Ltd. has carried out a project at the IVO Naantali power plant to develop the plants condition management. The project defines critical and monitored components for each system. In addition, recommendations for further action, investment proposals and suggestions for changes in maintenance and operations practices were supplied for the various systems in the plant. The systematic approach which was the result of the projects integrated into maintenance and operations practices where data collection and analysis is part of the routine. Up-to-date data is utilized in focusing maintenance and investments, in planning and reporting functions

  2. Solution and implementation of project ''Simulator of WWER-440 nuclear power plant''

    International Nuclear Information System (INIS)

    Koukal, V.

    1985-01-01

    The time data are given of the development and construction of the simulator of a WWER-440 nuclear power plant unit. The individual tasks are summed up which are related to the project implementation, and cooperating institutions and enterprises are listed. (J.C.)

  3. Projected impacts of climate change on regional capacities for global plant species richness.

    Science.gov (United States)

    Sommer, Jan Henning; Kreft, Holger; Kier, Gerold; Jetz, Walter; Mutke, Jens; Barthlott, Wilhelm

    2010-08-07

    Climate change represents a major challenge to the maintenance of global biodiversity. To date, the direction and magnitude of net changes in the global distribution of plant diversity remain elusive. We use the empirical multi-variate relationships between contemporary water-energy dynamics and other non-climatic predictor variables to model the regional capacity for plant species richness (CSR) and its projected future changes. We find that across all analysed Intergovernmental Panel on Climate Change emission scenarios, relative changes in CSR increase with increased projected temperature rise. Between now and 2100, global average CSR is projected to remain similar to today (+0.3%) under the optimistic B1/+1.8 degrees C scenario, but to decrease significantly (-9.4%) under the 'business as usual' A1FI/+4.0 degrees C scenario. Across all modelled scenarios, the magnitude and direction of CSR change are geographically highly non-uniform. While in most temperate and arctic regions, a CSR increase is expected, the projections indicate a strong decline in most tropical and subtropical regions. Countries least responsible for past and present greenhouse gas emissions are likely to incur disproportionately large future losses in CSR, whereas industrialized countries have projected moderate increases. Independent of direction, we infer that all changes in regional CSR will probably induce on-site species turnover and thereby be a threat to native floras.

  4. South Ukraine Nuclear Power Plant. Advanced Computer Information System Project

    International Nuclear Information System (INIS)

    Hord, J.; Afanasiev, N.; Smith, C.; Kudinov, Yu.

    1997-01-01

    The South Ukraine upgrade is the first of many that will take place in the former eastern bloc countries over the next several years. Westron is currently developing a similar system for the Zaporozhe nuclear power plant. In addition, there are eleven other WWER type units in operation in the Ukraine, as well as twenty seven others in operation throughout Eastern and Central Europe and Russia - all potential upgrade projects. (author)

  5. Data base on dose reduction research projects for nuclear power plants. Volume 5

    Energy Technology Data Exchange (ETDEWEB)

    Khan, T.A.; Yu, C.K.; Roecklein, A.K. [Brookhaven National Lab., Upton, NY (United States)

    1994-05-01

    This is the fifth volume in a series of reports that provide information on dose reduction research and health physics technology or nuclear power plants. The information is taken from two of several databases maintained by Brookhaven National Laboratory`s ALARA Center for the Nuclear Regulatory Commission. The research section of the report covers dose reduction projects that are in the experimental or developmental phase. It includes topics such as steam generator degradation, decontamination, robotics, improvements in reactor materials, and inspection techniques. The section on health physics technology discusses dose reduction efforts that are in place or in the process of being implemented at nuclear power plants. A total of 105 new or updated projects are described. All project abstracts from this report are available to nuclear industry professionals with access to a fax machine through the ACEFAX system or a computer with a modem and the proper communications software through the ACE system. Detailed descriptions of how to access all the databases electronically are in the appendices of the report.

  6. An ANP-based approach for the selection of photovoltaic solar power plant investment projects

    International Nuclear Information System (INIS)

    Aragones-Beltran, P.; Pastor-Ferrando, J.P.; Rodriguez-Pozo, F.; Chaparro-Gonzalez, F.

    2010-01-01

    In this paper the Analytic Network Process (ANP) is applied to the selection of photovoltaic (PV) solar power projects. These projects follow a long management and execution process from plant site selection to plant start-up. As a consequence, there are many risks of time delays and even of project stoppage. In the case study presented in this paper a top manager of an important Spanish company that operates in the power market has to decide on the best PV project (from four alternative projects) to invest based on risk minimization. The manager identified 50 project execution delay and/or stoppage risks. The influences between the elements of the network (groups of risks and alternatives) were identified and analyzed using the ANP multicriteria decision analysis method. Two different ANP models were used: one hierarchy model (that considers AHP as a particular case of ANP) and one network-based model. The results obtained in each model were compared and analyzed. The main conclusion is that unlike the other models used in the study, the single network model can manage all the information of the real-world problem and thus it is the decision analysis model recommended by the authors. The strengths and weaknesses of ANP as a multicriteria decision analysis tool are also described in the paper. (author)

  7. Establishing the quality assurance programme for a nuclear power plant project

    International Nuclear Information System (INIS)

    1984-01-01

    This Safety Guide provides requirements, recommendations and illustrative examples for establishing the overall quality assurance programme, and its constituent programmes, for a nuclear power plant project. It also provides guidance on the planning and documenting of programme plans and actions that are intended to ensure the achievement of the appropriate quality throughout the design, procurement, manufacture, construction, commissioning, operation and decommissioning of the nuclear power plant. The provisions of this Safety Guide are applicable to all organizations performing activities affecting the quality of items important to safety, such as designing, purchasing, fabricating, manufacturing, handling, shipping, storing, cleaning, erecting, installing, testing, commissioning, operating, inspecting, maintaining, repairing, refuelling, modifying and decommissioning

  8. A high-level dynamic analysis approach for studying global process plant availability and production time in the early stages of mining projects

    Directory of Open Access Journals (Sweden)

    Dennis Travagini Cremonese

    Full Text Available Abstract In the early stage of front-end studies of a Mining Project, the global availability (i.e. number of hours a plant is available for production and production (number of hours a plant is actually operated with material time of the process plant are normally assumed based on the experience of the study team. Understanding and defining the availability hours at the early stages of the project are important for the future stages of the project, as drastic changes in work hours will impact the economics of the project at that stage. An innovative high-level dynamic modeling approach has been developed to assist in the rapid evaluation of assumptions made by the study team. This model incorporates systems or equipment that are commonly used in mining projects from mine to product stockyard discharge after the processing plant. It includes subsystems that will simulate all the component handling, and major process plant systems required for a mining project. The output data provided by this high-level dynamic simulation approach will enhance the confidence level of engineering carried out during the early stage of the project. This study discusses the capabilities of the approach, and a test case compared with standard techniques used in mining project front-end studies.

  9. Technical data for concentrated solar power plants in operation, under construction and in project

    Directory of Open Access Journals (Sweden)

    Ugo Pelay

    2017-08-01

    Full Text Available This article presents technical data for concentrated solar power (CSP plants in operation, under construction and in project all over the world in the form of tables. These tables provide information about plants (e.g., name of the CSP plant, country of construction, owner of the plant, aim of the plant and their technical characteristics (e.g., CSP technology, solar power, area of the plant, presence and type of hybridization system, electricity cost, presence and type of TES, power cycle fluid, heat transfer fluid, operating temperature, operating pressure, type of turbine, type and duration of storage, etc.. Further interpretation of the data and discussions on the current state-of-the-art and future trends of CSP can be found in the associated research article (Pelay et al., 2017 [1].

  10. PFP MICON maintenance manual. Revision 1

    International Nuclear Information System (INIS)

    Silvan, G.R.

    1995-01-01

    This manual covers the use of maintenance displays, maintenance procedures, system alarms and common system failures. This manual is intended to supplement the MICON maintenance training not replace it. It also assumes that the user is familiar with the normal operation of the MICON A/S system. The MICON system is a distributed control computer and, among other things, controls the HVAC system for the Plutonium Finishing Plant

  11. Technical Description Lillgrund Wind Power Plant. Lillgrund Pilot Project

    Energy Technology Data Exchange (ETDEWEB)

    Jeppsson, Joakim; Larsen, Poul Erik; Larsson, Aake [Vattenfall Vindkraft AB, Stockholm (Sweden)

    2008-09-15

    Lillgrund offshore wind power plant comprises 48 wind turbines, each rated at 2.3 MW, bringing the total wind farm capacity to 110 MW. The Lillgrund offshore wind power plant is located in a shallow area of Oeresund, 7 km off the coast of Sweden and 7 km south from the Oeresund Bridge connecting Sweden and Denmark. An average wind speed of around 8,5 m/s at hub height, combined with a relatively low water depth of 4 to 8 meters makes it economically feasible to build here. Vattenfall Vindkraft AB is the owner and operator of Lillgrund offshore wind power plant. Lillgrund is a Swedish pilot project supported by the Swedish Energy Agency. The bidding process was completed during 2005 and the offshore power plant was constructed in the period 2006 to 2007. The wind farm was constructed on time and has now been successfully operational since December 2007. There is, however, always potential for improvement and the aim of this report has been to determine and highlight these areas. It is worth noting out that only the electrical system and the foundations are tailor made at offshore wind power plants. The wind turbines are more or less standard products with none or very limited possibilities for project specific design changes. Geotechnical investigations are expensive and it can be difficult to balance the risks as well as the benefits of this expense in the early phases of a large infrastructure project. As a whole, the geotechnical surveys at Lillgrund proved to be useful. They identified potential issues, such as the fact that extra excavation was required for two of the foundations. It also revealed the location of a small number of boulders that would have to be removed. Vattenfall requested a complete study of the electrical system for Lillgrund to be delivered with the bids. That request was not met. Instead Siemens Wind Power began a complete electrical system study after being awarded the Contract. The electrical system study was completed during the

  12. Feasibility study for Tashkent Heat and Power Plant Modernizing Project

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2001-03-01

    An investigational study was carried out of the project for energy conservation and greenhouse effect gas emission reduction by introducing the newest and most powerful gas turbine cogeneration facilities to the Tashkent cogeneration plant in Uzbekistan. At the Tashkent cogeneration plant, each of the facilities is being superannuated, which leads to lowering of operational reliability and increase in cost of repairs. In the project, studied was the introduction of the newest and most powerful gas turbine cogeneration facilities with heat output of 100 Gcal/h equivalent to that of one can of the existing hot water boiler and with generated output of 80MW. As a result of the study, obtained were the energy conservation amount of 83.9 ktoe/y and the greenhouse effect gas reduction amount of 179.7 kt-CO2/y. The initial investment amount was 10.003 billion yen. Expenses vs. effects were 8.39 toe/y-million yen in energy conservation amount and 18.0 t-CO2/y-million yen in greenhouse effect gas reduction amount. In the study of profitability, the internal earning rate was 9.24% after tax, the return yield of capital was 41.26%, and the period of ROI was 16.9 years. (NEDO)

  13. Seismic safety margins research program. Phase I final report - Plant/site selection and data collection (Project I)

    International Nuclear Information System (INIS)

    Chuang, T.Y.

    1981-07-01

    Project I of Phase I of the Seismic Safety Margins Research Program (SSMRP) comprised two parts: the selection of a representative nuclear power plant/site for study in Phase I and the collection of data needed by the other SSMRP projects. Unit 1 of the Zion Nuclear Power Plant in Zion, Illinois, was selected for the SSMRP Phase I studies. Unit 1 of the Zion plant has been validated as a good choice for the Phase I study plant. Although no single nuclear power plant can represent all such plants equally well, selection criteria were developed to maximize the generic implications of Phase I of the SSMRP. On the basis of the selection criteria, the Zion plant and its site were found to be reasonably representative of operating and future plants with regard to its nuclear steam supply system; the type of containment structure (prestressed concrete); its electrical capacity (1100 MWe); its location (the Midwest); the peak seismic acceleration used for design (0.17g); and the properties of the underlying soil (the low-strain shear-wave velocity is 1650 ft/s in a 50- to 100-ft-thick layer of soil overlying sedimentary bedrock). (author)

  14. CORR Guidelines. Preparing and Conducting Review Missions of Construction Project Readiness for Nuclear Power Plants

    International Nuclear Information System (INIS)

    2013-01-01

    The construction readiness review (CORR) mission for nuclear power plant projects has been established with the aim of conducting peer reviews of construction projects related to nuclear power plants. Such a mission provides a detailed assessment of readiness for construction, construction progress, readiness for turnover, as well as recommendations for improvement. Organizations in Member States, such as nuclear utilities, owners, regulators and technical support organizations, can benefit from such reviews. A team of international experts with complementing specialities will conduct the CORR mission. The review is based on appropriate IAEA publications, such as IAEA Safety Standards Series Guides and IAEA Nuclear Energy Series publications, as well as on internationally recognized project and construction management guides. Mission findings are summarized in a mission report, which includes a list of recommendations, suggestions and identified good practices. The review is not intended to be a regulatory inspection or an audit against international codes and standards. Rather, it is a peer review aimed at improving implementation processes and procedures through an exchange of technical experiences and practices at the working level. The mission is applicable at any stage of a nuclear power plant construction project, although two specific phases are targeted: (1) start of construction mission (Phase 1 mission) and (2) an in-progress mission (Phase 2 mission). Missions are initiated when official requests are submitted by Member States through the appropriate IAEA channels

  15. Fuel Cell Balance-of-Plant Reliability Testbed Project

    Energy Technology Data Exchange (ETDEWEB)

    Sproat, Vern [Stark State College of Technology, North Canton, OH (United States); LaHurd, Debbie [Lockheed Martin Corp., Oak Ridge, TN (United States)

    2016-10-29

    Reliability of the fuel cell system balance-of-plant (BoP) components is a critical factor that needs to be addressed prior to fuel cells becoming fully commercialized. Failure or performance degradation of BoP components has been identified as a life-limiting factor in fuel cell systems.1 The goal of this project is to develop a series of test beds that will test system components such as pumps, valves, sensors, fittings, etc., under operating conditions anticipated in real Polymer Electrolyte Membrane (PEM) fuel cell systems. Results will be made generally available to begin removing reliability as a roadblock to the growth of the PEM fuel cell industry. Stark State College students participating in the project, in conjunction with their coursework, have been exposed to technical knowledge and training in the handling and maintenance of hydrogen, fuel cells and system components as well as component failure modes and mechanisms. Three test beds were constructed. Testing was completed on gas flow pumps, tubing, and pressure and temperature sensors and valves.

  16. The permissibility of power plants and other large-scale projects outside densely populated areas from the point of view of planning legislation

    International Nuclear Information System (INIS)

    Hoppe, W.

    1978-01-01

    For the licensing of power plants, nuclear power plants and other industrial large projects, the question of the building law admissibility gains more and more importance in the licensing procedure. According to paragraph 6 of the Fed. Immission Protection, it is not only necessary that immission protection duties of the operator of plants which are subject to licensing are fulfilled, but other public law regulations must be in correspondance with the construction and operation of the plant. In this connection, the planning law admissibility of the project must also be examined. This is also valid for nuclear power plants. In the practical application of licensing such plants are treated in different ways, as far as terms of building planning are concerned. Some licensing authorities regard them as priviledged outskirts projects, others demand a zoning plan of the community. The author pleads for such large projects to be licensed only on the basis of a zoning plan set up by the community. (orig.) [de

  17. Dose-projection considerations for emergency conditions at nuclear power plants

    International Nuclear Information System (INIS)

    Stoetzel, G.A.; Ramsdell, J.V.; Poeton, R.W.; Powell, D.C.; Desrosiers, A.E.

    1983-05-01

    The purpose of this report is to review the problems and issues associated with making environmental radiation-dose projections during emergencies at nuclear power plants. The review is divided into three areas: source-term development, characterization of atmospheric dispersion and selection of appropriate dispersion models, and development of dosimetry calculations for determining thyroid dose and whole-body dose for ground-level and elevated releases. A discussion of uncertainties associated with these areas is also provided

  18. Dose-projection considerations for emergency conditions at nuclear power plants

    Energy Technology Data Exchange (ETDEWEB)

    Stoetzel, G.A.; Ramsdell, J.V.; Poeton, R.W.; Powell, D.C.; Desrosiers, A.E.

    1983-05-01

    The purpose of this report is to review the problems and issues associated with making environmental radiation-dose projections during emergencies at nuclear power plants. The review is divided into three areas: source-term development, characterization of atmospheric dispersion and selection of appropriate dispersion models, and development of dosimetry calculations for determining thyroid dose and whole-body dose for ground-level and elevated releases. A discussion of uncertainties associated with these areas is also provided.

  19. DSM energy saving pilot project report. Furniture Plant Teika, Riga, Latvia

    International Nuclear Information System (INIS)

    Ananevski, V.; Kalejs, M.; Hercogs, J.; Blumbergs, U.

    1995-07-01

    The purpose of this pilot project was to carry out energy audit into the furniture plant TEIKA and energy saving measures. Another aim was to transfer the Danish know how and experience obtained through the Danish effort in Latvian industries consumers. Therefore great attention is paid to energy mapping in order to show possibilities of the Danish methodisms. This report is a part of the Joint Latvian - Danish Project Demand Side Management and Energy Saving. It is a results of collaborative efforts between a Latvian team, consisting of the specialists from Latvenergo and on the other hand a Danish team, which was represented by the Danish Power Consult company NESA. (EG)

  20. INERT Atmosphere confinement operability test procedure

    International Nuclear Information System (INIS)

    RISENMAY, H.R.

    1999-01-01

    This Operability Test Procedure (OTP) provides instructions for testing operability of the Inert Atmosphere Confinement (IAC). The Inert Atmosphere Confinement was designed and built for opening cans of metal items that might have hydrided surfaces. Unreviewed Safety Question (USQ) PFP-97-005 addresses the discovery of suspected plutonium hydride forming on plutonium metal currently stored in the Plutonium Finishing Plant vaults. Plutonium hydride reacts quickly with air, liberating energy. The Inert Atmosphere Confinement was designed to prevent this sudden liberation of energy by opening the material in an inert argon atmosphere instead of the normal glovebox atmosphere. The IAC is located in glovebox HC-21A, room 230B of the 234-5Z Building at the Plutonium Finishing Plant (PFP) in the 200-West Area of the Hanford Site

  1. Study and Proposal of the Nuclear Power Plant Technology for the Ninh Thuan 2 Project

    International Nuclear Information System (INIS)

    Tran Chi Thanh; Le Van Hong; Hoang Sy Than; Nguyen Van De; Mai Dinh Trung; Nguyen Nhi Dien; Nguyen Minh Tuan; Pham Van Lam; Phan Ngoc Tuyen; Do Chi Dung; Hoang Minh Giang; Le Dai Dien

    2015-01-01

    The Ninh Thuan 1&2 Nuclear Power Plant Projects were approved on November 25th, 2009. At present, the task of NPP technology selection of these projects is an important and complex task. This report will show the acceptable method to create a set of criterion for selecting technology for Ninh Thuan 2 NPP project. The result of evaluation of three NPP technologies, such as ATMEA1, AP1000 and MPWR+ introduced in the Feasibility Study Reports of this project, will be discussed. In conclusion, the AP1000 technology is the first candidate for the Ninh Thuan 2 NPP Project. (author)

  2. Southeast Regional Wastewater Treatment Plant Facilities Improvements Project and Geysers Effluent Pipeline Project. Final EIR/EIS

    International Nuclear Information System (INIS)

    1994-01-01

    On May 26, 1994, the Lake County Sanitation District and the US Bureau of Land Management released for public review a Draft Environmental Impact Report/Environmental Impact Statement (EIR/EIS) on the proposed Southeast Regional Wastewater Treatment Plant Facilities Improvements Project and Geysers Effluent Pipeline Project. A minimum 45-day review and comment period began on that date and notices were published in the Federal Register. The public review and comment period closed on July 26, 1994. Public hearings on the Draft EIMIS were held in Lakeport, CA, on June 30 and July 14, 1994. The first part of this document contains copies of the written comments submitted on the Draft EIR/EIS. It also contains summary paraphrased comments of the public hearings. The second part of this document contains responses to the comments

  3. Influencing factors of public support for modern coal-fired power plant projects: An empirical study from China

    International Nuclear Information System (INIS)

    Liu, Feng; Lyu, Tao; Pan, Li; Wang, Fei

    2017-01-01

    With the development of clean coal technology, modern coal-fired power plants have achieved the similar emission standards as gas power plants. However, due to the impressions of high pollution and high emission in traditional coal-fired power plants, such projects are often opposed by local residents, which hinder the promotion of this technology. This manuscript aims to investigate public attitudes toward these projects and to analyze the influencing mechanisms of the factors of public support. The conceptual model was built with sense of place, trust and environmental attitude as the independent variables, benefit and cost perceptions as the mediating variables and public support as the dependent variable. The model was tested and modified by structural equation modelling. The results revealed that sense of place had a slight indirect impact (−0.043) on public support through benefit perception, whereas trust had a direct impact (0.332) on public support and indirect impacts (0.298) through benefit and cost perceptions. Environmental attitude had indirect impacts on public support through benefit perception (0.180) and cost perception (−0.115). In addition, policy suggestions on decision-making, project publicity and compensation strategy are proposed to enhance public support for similar projects. - Highlights: • This manuscript aims at eliminating the NIMBY effects on modern coal-fired power plant project. • A SEM model is proposed to explore how potential factors affect public support. • Trust is the dominant influencing factor to improve public support with both direct and indirect impacts. • Environmental attitude can also have positive effect on public support through rational compensation plans.

  4. Sludge Stabilization Campaign blend plan

    International Nuclear Information System (INIS)

    De Vries, M.L.

    1994-01-01

    This sludge stabilization blend plan documents the material to be processed and the order of processing for the FY95 Sludge Stabilization Campaign. The primary mission of this process is to reduce the inventory of unstable plutonium bearing sludge. The source of the sludge is residual and glovebox floor sweepings from the production of material at the Plutonium Finishing Plant (PFP). The reactive sludge is currently being stored in various gloveboxes at PFP. There are two types of the plutonium bearing material that will be thermally stabilized in the muffle furnace: Plutonium Reclamation Facility (PRF) sludge and Remote Mechanical C (RMC) Line material

  5. Nevada Renewable Energy Training Project: Geothermal Power Plant Operators

    Energy Technology Data Exchange (ETDEWEB)

    Jim, Nichols [Truckee Meadows Community College, Reno, NV (United States)

    2014-04-29

    The purpose of this project was to develop and institute a training program for certified geothermal power plant operators (GPO). An advisory board consisting of subject matter experts from the geothermal energy industry and academia identified the critical skill sets required for this profession. A 34-credit Certificate of Achievement (COA), Geothermal Power Plant Operator, was developed using eight existing courses and developing five new courses. Approval from the Nevada System of Higher Education Board of Regents was obtained. A 2,400 sq. ft. geothermal/fluid mechanics laboratory and a 3,000 sq. ft. outdoor demonstration laboratory were constructed for hands-on training. Students also participated in field trips to geothermal power plants in the region. The majority of students were able to complete the program in 2-3 semesters, depending on their level of math proficiency. Additionally the COA allowed students to continue to an Associate of Applied Science (AAS), Energy Technologies with an emphasis in Geothermal Energy (26 additional credits), if they desired. The COA and AAS are stackable degrees, which provide students with an ongoing career pathway. Articulation agreements with other NSHE institutions provide students with additional opportunities to pursue a Bachelor of Applied Science in Management or Instrumentation. Job placement for COA graduates has been excellent.

  6. Contribution of research and development and engineering to a large reprocessing plant project. Extension of the La Hague plant

    International Nuclear Information System (INIS)

    Boutaud de la Combe, P.; Courouble, J.M.; Sauteron, J.; Redon, A.

    1983-01-01

    Two reprocessing plants are operated by Cogema: Marcoule (since 1958) and La Hague (since 1967). Since 1976 the latter has been reprocessing LWR assemblies in its 'HAO' workshop, operation of which has provided industrial experience in the reprocessing of this type of fuel. This experience will be drawn upon in the construction of extensions to the La Hague plant, namely the UP3 plant, which will have a capacity of 800 t/a, and UP2-800, which will expand the present plant likewise to a capacity of 800 t/a. These extensions will contain a number of improvements, particularly in the areas of safety and waste treatment, and of procedure and equipment. A considerable R and D contribution is provided by the French Atomic Energy Commission (CEA), which is the licence holder, with its laboratories at Fontenay and the pilot workshop and industrial prototypes service at Marcoule. This activity supports all phases of the project, from the establishment of basic principles to the definition of essential characteristics of equipment, covering also the testing of full-scale prototypes (mock-ups) for the principal components: rotating continuous dissolver, swinging decanter, subcritical pulsed columns, used-solvent distilling apparatus, fission-product vitrification furnace, etc. Engineering work for the new facilities is performed by the Societe generale pour les techniques nouvelles in four phases: (1) establishment of basic data; (2) preparation of preliminary plans (including an estimate and a preliminary schedule) and of the preliminary safety reports; (3) drafting of the 'project' file, giving definitive costs and deadlines; (4) implementation, up to and including the operational testing stage. All phases of design and implementation are subject to a quality assurance programme. Extension of the La Hague plant represents an investment of 23,500 million French francs (in July 1981). Construction is expected to be completed in 1989. (author)

  7. Development project HTR-electricity-generating plant, concept design of an advanced high-temperature reactor steam cycle plant with spherical fuel elements (HTR-K)

    International Nuclear Information System (INIS)

    1978-07-01

    The report gives a survey of the principal work which was necessary to define the design criteria, to determine the main design data, and to design the principal reactor components for a large steam cycle plant. It is the objective of the development project to establish a concept design of an edvanced steam cycle plant with a pebble bed reactor to permit a comparison with the direct-cycle-plant and to reach a decision on the concept of a future high-temperature nuclear power plant. It is tried to establish a largerly uniform basic concept of the nuclear heat-generating systems for the electricity-generating and the process heat plant. (orig.) [de

  8. Mutational synergism between p-fluorophenylalaline and UV in Coprinus lagopus

    International Nuclear Information System (INIS)

    Talmud, P.J.

    1977-01-01

    The amino acid analogue p-fluorophenylalanine (PFP) is mutagenic to Coprinus lagopus due to its incorporation into proteins. Spontaneous mutations, PFP and UV mutagenesis and PFP/UV synergism have been studied in a UV resistant strain and in two complementing UV sensitive mutant strains. By comparison to the UV resistant strain, one UV sensitive strain shows normal spontaneous mutations, 1.4% PFP-induced mutations and 50-fold UV mutagenesis. The second UV sensitive strain has 19-fold spontaneous mutation frequency and slightly elevated UV mutagenesis. In all 3 strains the PFP/UV synergism is comparable (4-5 times the arithmetic expected). The results indicate that PFP mutagenesis is due to the incorporation of PFP into enzymes normally functioning in the organism but which also participate in UV repair mechanisms. A model is proposed for UV repair which is based on a PFP sensitive excision repair system of at least two enzymes, an alternative 'error-proof' pathway which is not susceptible to PFP and an 'error-prone' pathway which is responsible for UV mutagenesis and is susceptible to PFP as shown by the PFP/UV synergism. Because PFP is given before UV treatment, this implies a UV inducible cofactor and a PFP sensitive enzyme which only functions after UV activation

  9. System requirement specifications for the Z-plant materials information tracking system (ZMITS)

    International Nuclear Information System (INIS)

    NEGIN, C.A.

    1999-01-01

    This is a system requirement specification for a database which will be developed to track classified information related to nuclear materials stored at PFP. The system will supplement existing databases to support both processing and disposition information needs

  10. Environmental assessment for Mound Plant decontamination and decommissioning projects, Mound Plant, Miamisburg, Ohio

    International Nuclear Information System (INIS)

    1995-05-01

    The U.S. Department of Energy (DOE) has prepared an Environmental Assessment (EA) for seven decontamination and decommissioning (D ampersand D) projects at the Mound Plant in Miamisburg, Ohio, that have not been previously addressed in the Final Environmental Impact Statement for the Mound Facility (June 1979). Based on the information presented in the EA, the DOE has determined that the proposed action is not a major Federal action significantly affecting the quality of the human environment within the meaning of the National Environmental Policy Act (NEPA) of 1969. Therefore, the preparation of an Environmental Impact Statement (EIS) is not required and the Department is issuing this Finding of No Significant Impact (FONSI)

  11. Rehabilitation and modernization project of units 1 and 2 of Laguna Verde Nuclear Power Plant. A strengthening project to 120%. (2nd phase)

    International Nuclear Information System (INIS)

    Liebana, B.; Merino, A.; Garcia, J. L.; Gomez, M.; Martinez, I.; Ruiz, L.

    2010-01-01

    The power increase of the Laguna Verde Nuclear Power Plant is a project for the rehabilitation and modernization of the turbo and associated equipment to get an increase of its power and of its service life. The project scope includes the design, the engineering, the equipment supply, the installation, the testing and the commissioning. This article presents the work of the second phase.

  12. Advanced conceptual design report: T Plant secondary containment and leak detection upgrades. Project W-259

    International Nuclear Information System (INIS)

    Hookfin, J.D.

    1995-01-01

    The T Plant facilities in the 200-West Area of the Hanford site were constructed in the early 1940s to produce nuclear materials in support of national defense activities. T Plant includes the 271-T facility, the 221-T facility, and several support facilities (eg, 2706-T), utilities, and tanks/piping systems. T Plant has been recommended as the primary interim decontamination facility for the Hanford site. Project W-259 will provide capital upgrades to the T Plant facilities to comply with Federal and State of Washington environmental regulations for secondary containment and leak detection. This document provides an advanced conceptual design concept that complies with functional requirements for the T Plant Secondary Containment and Leak Detection upgrades

  13. Defense waste processing facility project at the Savannah River Plant

    International Nuclear Information System (INIS)

    Baxter, R.G.; Maher, R.; Mellen, J.B.; Shafranek, L.F.; Stevens, W.R. III.

    1984-01-01

    The Du Pont Company is building for the Department of Energy a facility to vitrify high-level waste at the Savannah River Plant near Aiken, South Carolina. The Defense Waste Processing Facility (DWPF) will solidify existing and future radioactive wastes produced by defense activities at the site. At the present time engineering and design are 45% complete, the site has been cleared, and startup is expected in 1989. This paper will describe project status as well as features of the design. 9 figures

  14. Equipment sizing in a coal-fired municipal heating plant modernisation project with support for renewable energy and cogeneration technologies

    International Nuclear Information System (INIS)

    Kalina, Jacek

    2014-01-01

    Highlights: • Sizing of biomass fired cogeneration block is performed for existing heating plant. • Mathematical model for cogeneration block optimisation is presented. • Impact of financial support mechanisms on optimal solution is discussed. • Influence of short term variations of prices and support intensity is presented. • Different design parameters are suggested by economic and technical quality indices. - Abstract: The paper presents results of design parameters optimisation of a wood chips fired steam boiler based heat and power block in a sample project of coal fired municipal heating plant modernisation. The project assumes the conversion of the heating plant into a dual fuel heat and power plant. The problem that is presented is selection of cogeneration block structure and thermodynamic parameters taking into account financial support mechanisms for cogeneration and renewable energy technologies. There are examined energy conversion and financial performances of the project. The results show that without the financial support the project is not profitable although it generates savings of primary energy of fossil fuels. If an administrative incentives are applied the optimal technical solution is different than suggested by energy conversion efficiency or fossil fuel savings. Financial calculations were performed for Polish marked conditions in the years 2011 and 2014 showing the impact of relatively short term variations of prices and support intensity on optimal plant design parameters

  15. Study of the binary mixtures of {monoglyme + (hexane, cyclohexane, octane, dodecane)} by ECM-average and PFP models

    International Nuclear Information System (INIS)

    Rivas, M.A.; Buep, A.H.; Iglesias, T.P.

    2015-01-01

    Highlights: • Polarization of the real mixture is less than that of the ideal mixture. • Molar excess volume does not exert the dominant effect on the polarization of the mixture. • Similar influence of molecular interactions on the behaviour of excess permittivity. • Excess molar volume is more influenced by the interactions than excess permittivity. - Abstract: Excess molar volumes and excess permittivity of binary mixtures involving monoglyme and alkanes, such as n-hexane, cyclohexane, n-octane and n-dodecane, were calculated from density and relative permittivity measurements for the entire composition range at several temperatures (288.15, 298.15 and 308.15) K and atmospheric pressure. The excess permittivity was calculated on the basis of a recent definition considering the ideal volume fraction. Empirical equations for describing the experimental data in terms of temperature and concentration are given. The experimental values of permittivity have been compared with those estimated by well-known models from literature. The results have indicated that better predictions are obtained when the volume change on mixing is incorporated in these calculations. The contribution of interactions to the excess permittivity was analysed by means of the ECM-average model. The Prigogine–Flory–Patterson (PFP) theory of the thermodynamics of solutions was used to shed light on the contribution of interactions to the excess molar volume. The work concludes with an interpretation of the information given by the theoretical models and the behaviour of both excess magnitudes

  16. Experiences of success in industrial plants projects Experiencias exitosas en proyectos de plantas industriales

    Directory of Open Access Journals (Sweden)

    Nuria Forcada

    2008-08-01

    Full Text Available Success has always been the ultimate goal of construction projects, and different researchers have tried to evaluate it using different factors. Although specialized industrial construction usually involves very large scale projects with a high degree of technological complexity, research has mostly focused on civil and residential success factors. Experiences in Industrial Plants projects can help to improve project management and productivity in such a specialized sector. In this kind of projects, the contractual arrangement is one of the core differences on Project management and thus project success. This research seeks to develop a schema for classifying critical success factors as well as a methodology for evaluating projects. This methodology was adopted to evaluate critical success factors in Industrial Plants projects with different contractual arrangements. Findings suggest that although the construction stage has been the focus of many studies, the first stages are decisive for the success of projects; contract construction projects consider project planning to be more important; lump sum contract construction projects give greater importance to monitoring the benefits; bidding competition projects consider the available technology with greater rigor, etc. The results indicate that different Industrial Plants projects involve different success factors and management characteristics to achieve project objectives.En cualquier proyecto de construcción el principal objetivo es que sea exitoso y por lo tanto a lo largo del tiempo diferentes investigadores han tratado de evaluar los factores que influyen en el éxito de proyectos. En el ámbito de la construcción estas investigaciones se han enfocado principalmente a obras civiles y residenciales. Este artículo muestra resultados que provienen de proyectos de construcción industrial especializada que incluyen proyectos de gran escala con un alto grado de complejidad tecnol

  17. Review of the Norwegian-Russian Cooperation on Safety Projects at Kola and Leningrad Nuclear Power Plants 2005 - 2009

    International Nuclear Information System (INIS)

    Mattsson, H.; Tishakov, P.

    2010-11-01

    In this report, Norwegian Radiation Protection Authority (NRPA) has reviewed the Norwegian funded projects on nuclear safety performed in the period 2005-2009 under the Norwegian Action Plan. NRPA has evaluated the progress of eight projects implemented by the Institute for Energy Technology (IFE) at Kola Nuclear Power Plant (KNPP) and Leningrad Nuclear Power Plant (LNPP). NRPA has visited the plants, inspected delivered equipment and discussed the projects implementation with relevant personnel at the plants. One of NRPA findings is that the equipment has been delivered to KNPP and LNPP, it is in regular use by competent personnel, and the equipment contributes to safety of both plants. Furthermore, the cooperation between three main project partners - IFE, LNPP and KNPP, seems to be very productive. NRPA's main conclusion is therefore that the projects have been implemented as described in IFE's project reports and that the goals are met. Furthermore, this report reviews safety levels at the KNPP and LNPP. Safety parameters at the plants indicate that the safety level has been significantly improved since early 1990s when the cooperation between Norway and Russia was initiated. Probabilistic safety assessment (PSA) values and number of INES (International Nuclear Event Scale) events, two internationally acknowledged safety parameters, indicate that the safety level has been much improved since the early 1990s when the cooperation between Norway and Russia started. Although it is clear that the Norwegian-funded projects have contributed positively to this development it is difficult to quantify the contribution. Moreover, the report also reviews the planned life-time of and the decommissioning plans for the reactors at KNPP and LNPP. Construction of new LNPP reactors has started and it is estimated that they will be operational in 2013- 2015. The license of the oldest reactor at LNPP expires in 2018 and if the new reactors are in operation by that time, it is

  18. Savannah River Plant engineering, design, and construction history of ``S`` projects and other work, January 1961--December 1964. Volume 2

    Energy Technology Data Exchange (ETDEWEB)

    1970-03-01

    The work described in this volume of ``S`` Projects History is an extension of the type of work described in Volume I. E.I. du Pont de flemours & Company had entered into Contract AT (07-2)-l with the United States Atomic Energy Commission to develop, design, construct, install, and operate facilities to produce heavy water, fissionable materials, and related products. Under this contract,, Du Pont constructed and operated the Savannah River Plant. The engineering, design, and construction for most of the larger ``S`` projects was performed by the Engineering DeDartment. For some of the large and many of the smaller projects the Engineering Department was responsible only for the construction because the Atomic Energy Division (AED) of the Explosives Department handled the other phases. The Engineering Department Costruction Division also performed the physical work for many of the plant work orders. This volume includes a general description of the Du Pont Engineering Department activities pertaining to the engineering, design, and construction of the ``S`` projects at the Savannah River Plant; brief summaries of the projects and principal work requests; and supplementary informaticn on a few subjects in Volume I for which final data was not available at the closing date. Projects and other plant engineering work which were handled entirely by the Explosives Department -- AED are not included in this history.

  19. Tight integration of computerized procedures with plant information at the South Texas Project

    International Nuclear Information System (INIS)

    Brtis, J.S.; Green, T.

    1996-01-01

    This paper describes a unique undertaking that is underway at Houston Lighting and Power's South Texas Project (STP). The paper presents an information upgrade project that uses expert system technologies to computerize design change procedures and to tightly integrate the resulting on-line, interactive procedures with the on-line information that design change activities use and generate. This effort will show how procedure computerization can leverage the large investments in plant data. The expected benefits include reduced costs and improved quality of design change work, plus a significant reduction in the burden of configuration management that comes from design changes. Both process computerization and the integration of process with data are being implemented at STP. This work is part of a major migration of information from a mainframe to a LAN platform. This paper will be of greatest interest to those involved in: (1) configuration management, (2) coordinating information to support design change procedures, (3) plant information management, and (4) business process reengineering

  20. Decommissioning the Belgonucleaire Dessel MOX plant: presentation of the project and situation end august 2013

    Energy Technology Data Exchange (ETDEWEB)

    Cuchet, J.M. [TRACTEBEL ENGINEERING, Avenue Ariane, 7, B1200 Brussels (Belgium); Libon, H.; Verheyen, C. [BELGONUCLEAIRE S.A. / N.V. Europalaan, 20, B2480 Dessel (Belgium); Bily, J. [STUDSVIK GmbH, Karlsruher Strasse, 20, D75179 Pforzheim,(Germany); Boden, S. [SCK-CEN, Boeretang, 200, B2400 Mol (Belgium); Joffroy, F. [TECNUBEL N.V., Zandbergen, 1, B2480 Dessel (Belgium); Walthery, R. [BELGOPROCESS, Gravenstraat, 73, B2480 Dessel (Belgium)

    2013-07-01

    Belgonucleaire has been operating the Dessel MOX plant at an industrial scale between 1986 and 2006. During this period, 40 metric tons of plutonium (HM) have been processed into 90 reloads of MOX fuel for commercial light water reactors. The decision to stop the production in 2006 and to decommission the MOX plant was the result of the shrinkage of the MOX fuel market due to political and commercial factors. As a significant part of the decommissioning project of the Dessel MOX plant, about 170 medium-sized glove-boxes and about 1.200 metric tons of structure and equipment outside the glove-boxes are planned for dismantling. The license for the dismantling of the MOX plant was granted by Royal Decree in 2008 and the dismantling started in March 2009. The dismantling works are carried out by an integrated organization under leadership and responsibility of Belgonucleaire; this organization includes 3 main contractors, namely Tecnubel N.V., the THV ('Tijdelijke HandelsVereniging') Belgoprocess / SCK-CEN and Studsvik GmbH and Tractebel Engineering as project manager. In this paper, after having described the main characteristics of the project, the authors review the different organizational and technical options considered for the decommissioning of the glove-boxes; thereafter the main decision criteria (qualification of personnel and of processes, confinement, cutting techniques and radiation protection, safety aspects, alpha-bearing waste management) are analyzed as well. Finally the progress, the feedback and the lessons learned at the end of August 2013 are presented, giving the principal's and contractors point of view. (authors)

  1. Honeywell modular automation system computer software documentation

    International Nuclear Information System (INIS)

    Cunningham, L.T.

    1997-01-01

    This document provides a Computer Software Documentation for a new Honeywell Modular Automation System (MAS) being installed in the Plutonium Finishing Plant (PFP). This system will be used to control new thermal stabilization furnaces in HA-21I

  2. Low-Level Waste Vitrification Plant Project contracting strategy decision analysis report

    International Nuclear Information System (INIS)

    Felise, P.; Phillips, J.D.

    1994-01-01

    Ten basic contracting strategies were developed after a review of past strategies that had been used at the Hanford Site, other US Department of Energy (DOE) sites, other US government agencies, and in the private sector. As applicable to the Low-Level Waste Vitrification Plant (LLWVP) Project, each strategy was described and depicted in a schedule format to assess compatibility with the Hanford Federal Facility Agreement and Consent Order, al so known as the Tri-Party Agreement (Ecology et al. 1994) milestones, key decision points, and other project requirements. The-pro and con aspects of each strategy also were tabulated. Using this information as a basis, the LLWVP Project team members, along with representatives of Tank Waste Remediation System (TWRS) Engineering, TWRS Programs, and Procurement Materials Management, formed a Westinghouse Hanford Company (WHC) evaluation team to select the best strategy. Kepner-Tregoe decision analysis techniques were used in facilitated meetings to arrive at the best balanced choice

  3. Low-Level Waste Vitrification Plant Project contracting strategy decision analysis report

    Energy Technology Data Exchange (ETDEWEB)

    Felise, P.; Phillips, J.D.

    1994-10-17

    Ten basic contracting strategies were developed after a review of past strategies that had been used at the Hanford Site, other US Department of Energy (DOE) sites, other US government agencies, and in the private sector. As applicable to the Low-Level Waste Vitrification Plant (LLWVP) Project, each strategy was described and depicted in a schedule format to assess compatibility with the Hanford Federal Facility Agreement and Consent Order, al so known as the Tri-Party Agreement (Ecology et al. 1994) milestones, key decision points, and other project requirements. The-pro and con aspects of each strategy also were tabulated. Using this information as a basis, the LLWVP Project team members, along with representatives of Tank Waste Remediation System (TWRS) Engineering, TWRS Programs, and Procurement Materials Management, formed a Westinghouse Hanford Company (WHC) evaluation team to select the best strategy. Kepner-Tregoe decision analysis techniques were used in facilitated meetings to arrive at the best balanced choice.

  4. Providing more informative projections of climate change impact on plant distribution in a mountain environment

    Science.gov (United States)

    Randin, C.; Engler, R.; Pearman, P.; Vittoz, P.; Guisan, A.

    2007-12-01

    Due to their conic shape and the reduction of area with increasing elevation, mountain ecosystems were early identified as potentially very sensitive to global warming. Moreover, mountain systems may experience unprecedented rates of warming during the next century, two or three times higher than that records of the 20th century. In this context, species distribution models (SDM) have become important tools for rapid assessment of the impact of accelerated land use and climate change on the distribution plant species. In this study, we developed and tested new predictor variables for species distribution models (SDM), specific to current and future geographic projections of plant species in a mountain system, using the Western Swiss Alps as model region. Since meso- and micro-topography are relevant to explain geographic patterns of plant species in mountain environments, we assessed the effect of scale on predictor variables and geographic projections of SDM. We also developed a methodological framework of space-for-time evaluation to test the robustness of SDM when projected in a future changing climate. Finally, we used a cellular automaton to run dynamic simulations of plant migration under climate change in a mountain landscape, including realistic distance of seed dispersal. Results of future projections for the 21st century were also discussed in perspective of vegetation changes monitored during the 20th century. Overall, we showed in this study that, based on the most severe A1 climate change scenario and realistic dispersal simulations of plant dispersal, species extinctions in the Western Swiss Alps could affect nearly one third (28.5%) of the 284 species modeled by 2100. With the less severe B1 scenario, only 4.6% of species are predicted to become extinct. However, even with B1, 54% (153 species) may still loose more than 80% of their initial surface. Results of monitoring of past vegetation changes suggested that plant species can react quickly to the

  5. Projected uranium measurement uncertainties for the Gas Centrifuge Enrichment Plant

    International Nuclear Information System (INIS)

    Younkin, J.M.

    1979-02-01

    An analysis was made of the uncertainties associated with the measurements of the declared uranium streams in the Portsmouth Gas Centrifuge Enrichment Plant (GCEP). The total uncertainty for the GCEP is projected to be from 54 to 108 kg 235 U/year out of a measured total of 200,000 kg 235 U/year. The systematic component of uncertainty of the UF 6 streams is the largest and the dominant contributor to the total uncertainty. A possible scheme for reducing the total uncertainty is given

  6. The evolution of the Waste Isolation Pilot Plant (WIPP) project's public affairs program

    International Nuclear Information System (INIS)

    Walter, L.H.

    1988-01-01

    As a first-of-a-kind facility, the Waste Isolation Pilot Plant (WIPP) presents a unique perspective on the value of designing a public affairs program that grown with and complements a project's evolution from construction to operations. Like the project itself, the public affairs programs progressed through several stages to its present scope. During the construction phase, foundations were laid in the community. Then, in this past year as the project entered a preoperational status, emphasis shifted to broaden the positive image that had been created locally. In this stage, public affairs presented the project's positive elements to the various state agencies, government officials, and federal organizations involved in our country's radioactive waste management program. Most recently, and continuing until receipt of the first shipment of waste in October 1988, an even broader, more aggressive public affairs program is planned

  7. Engineering for new-built nuclear power plant projects; Ingenieria para proyectos de nuevas centrales nucleares

    Energy Technology Data Exchange (ETDEWEB)

    Gonzalez Lopez, A.

    2012-11-01

    This article reviews the opportunities existing in the market (electrical utilities and reactor vendors) for an engineering company with the profile of Empresarios Agrupados (EA) in new-built nuclear power plant projects. To do this, reference is made to some representative examples of projects in which EA has been participating recently. the article concludes sharing with the reader some lessons learned from this participation. (Author)

  8. The role of instrumentation and control systems in power uprating projects for nuclear power plants

    International Nuclear Information System (INIS)

    2008-01-01

    The IAEA's activities in nuclear power plant operating performance and life cycle management are aimed at increasing Member State capabilities in utilizing good engineering and management practices developed and transferred by the IAEA. In particular, the IAEA supports activities focusing on the improvement of nuclear power plant (NPP) performance, plant life management, training, power uprating, operational licence renewal, and the modernization of instrumentation and control (I and C) systems of NPPs in Member States. The subject of the I and C systems' role in power uprating projects in NPPs was suggested by the Technical Working Group on Nuclear Power Plant Control and Instrumentation in 2003. The subject was then approved by the IAEA and included in the programmes for 2004-2007. The increasing importance of power uprating projects can be attributed to the general worldwide tendency to the deregulation of the electricity market. The greater demand for electricity and the available capacity and safety margins, as well as the pressure from several operating NPPs resulted in requests for licence modification to enable operation at a higher power level, beyond the original licence provisions. A number of nuclear utilities have already gone through the uprating process for their nuclear reactors, and many more are planning to go through this modification process. In addition to mechanical and process equipment changes, parts of the electrical and I and C systems and components may also need to be altered to accommodate the new operating conditions and safety limits. This report addresses the role of I and C systems in NPP power uprating projects. The objective of the report is to provide guidance to utilities, safety analysts, regulators and others involved in the preparation, implementation and licensing of power uprating projects, with particular emphasis on the I and C aspects of these projects. As the average age of NPPs is increasing, it is becoming common for

  9. Data base on dose reduction research projects for nuclear power plants

    Energy Technology Data Exchange (ETDEWEB)

    Khan, T.A.; Vulin, D.S.; Liang, H.; Baum, J.W. (Brookhaven National Lab., Upton, NY (United States))

    1992-08-01

    This is the fourth volume in a series of reports that provide information on dose reduction research and health physics technology for nuclear power plants. The information is taken from a data base maintained by Brookhaven National Laboratory's ALARA Center for the Nuclear Regulatory Commission. This report presents information on 118 new or updated projects, covering a wide range of activities. Projects including steam generator degradation, decontamination, robotics, improvement in reactor materials, and inspection techniques, among others, are described in the research section of the report. The section on health physics technology includes some simple and very cost-effective projects to reduce radiation exposures. Included in this volume is a detailed description of how to access the BNL data bases which store this information. All project abstracts from this report, as well as many other useful documents, can be accessed, with permission, through our on-line system, ACE. A computer equipped with a modem, or a fax machine is all that is required to connect to ACE. Many features of ACE, including software, hardware, and communications specifics, are explained in this report.

  10. Plutonium Finishing Plant (PFP) HVAC System Component Index; FINAL

    International Nuclear Information System (INIS)

    DICK, J.D.

    1999-01-01

    This document identities the components, design media, procedures and defines the critical characteristics of Commercial Grade Items necessary to ensure the HVAC system provides these functions. This document lists safety class (SC) and safety significant (SS) components for the Heating Ventilation Air Conditioning (HVAC) and specifies the critical characteristics for Commercial Grade Items (CGI), as required by HNF-PRO-268 and HNF-PRO-1819. These are the minimum specifications that the equipment must meet in order to properly perform its safety function. There may be several manufacturers or models that meet the critical characteristics for any one item

  11. Honeywell Modular Automation System Computer Software Documentation for the Magnesium Hydroxide Precipitation Process

    International Nuclear Information System (INIS)

    STUBBS, A.M.

    2001-01-01

    The purpose of this Computer Software Document (CSWD) is to provide configuration control of the Honeywell Modular Automation System (MAS) in use at the Plutonium Finishing Plant (PFP) for the Magnesium Hydroxide Precipitation Process in Rm 230C/234-5Z. The magnesium hydroxide process control software Rev 0 is being updated to include control programming for a second hot plate. The process control programming was performed by the system administrator. Software testing for the additional hot plate was performed per PFP Job Control Work Package 2Z-00-1703. The software testing was verified by Quality Control to comply with OSD-Z-184-00044, Magnesium Hydroxide Precipitation Process

  12. Pre-project study on a demonstration plant for seawater desalination using a nuclear heating reactor in Morocco

    International Nuclear Information System (INIS)

    Achour, M.

    2000-01-01

    This paper gives in the first part detailed information on the pre-project study on a demonstration plant for seawater desalination using heating reactor implemented by both Moroccan and Chinese sides. The main findings of the pre-project study are given in the second part. (author)

  13. Implementation of the project of equipment reliability in the nuclear power plant of Laguna Verde

    International Nuclear Information System (INIS)

    Rios O, J. E.; Martinez L, A. G.

    2008-01-01

    A equipment is reliable if it fulfills the function for which was designed and when it is required. To implement a project of reliability in a nuclear power plant this associate to a process of continuous analysis of the operation, of the conditions and faults of the equipment. The analysis of the operation of a system, of the equipment of the same faults and the parts that integrate to equipment take to identify the potential causes of faults. The predictive analysis on components and equipment allow to rectify and to establish guides to optimize the maintenance and to guarantee the reliability and function of the same ones. The reliability in the equipment is without place to doubts a wide project that embraces from the more small component of the equipment going by the proof of the parts of reserve, the operation conditions until the operative techniques of analysis. Without place of doubt for a nuclear power plant the taking of decisions based on the reliability of their systems and equipment will be the appropriate for to assure the operation and reliability of the same one. In this work would appear the project of reliability its processes, criteria, indicators action of improvement and the interaction of the different disciplines from the Nuclear Power Plant of Laguna Verde like a fundamental point for it put in operation. (Author)

  14. Project approach study for nuclear power plants in the Netherlands

    International Nuclear Information System (INIS)

    1985-11-01

    The new nuclear program in the Netherlands comprises the construction of two to four nuclear power plants up to the year 2000. The main objective pursued with the implementation of the nuclear program is the supply of low-cost electricity in the future. In order to prepare the program and to provide a basis for further decisions, the Ministry of Economic Affairs has entrusted Motor-Columbus Consulting Engineers Inc., Baden, Switzerland, with a study to determine the most suitable project approach option(s) for the implementation of the future nuclear program in the Netherlands. In carrying out this study, Motor-Columbus investigated the following main project approach options: 1. turnkey contract approach; 2. split-package contract approach; 3. multi-contract approach. It is concluded that if applied in the appropriate way, the normal turnkey contract approach represents the most suitable approach under the prevailing situation in the Netherlands. (orig.)

  15. Finance structure and public enlightenment program of the first Turkish nuclear power plant project (a case study)

    International Nuclear Information System (INIS)

    Lutfi Sarici, E.

    2000-01-01

    This paper deals with four closely related subjects. These are: the positioning of nuclear energy in Turkey's energy planning by presenting supply and demand figures of electricity, giving emphasis to resource availability, pointing out the necessity of diversification of resources; the ongoing situation for realization of the Akkuyu Project with its updated milestones, alternative offers requested for the Akkuyu Nuclear Power Plant and member companies of the consortiums who already have submitted the three bids; the financing of big-scale energy investment projects in developing countries by giving special emphasis to the Akkuyu Nuclear Power Plant Project including the financing requirements in the Bid Specifications, OECD rules for financing, the requirements of financial agents, and financing means of domestic participation; public enlightenment during establishment of nuclear power in Turkey. (author)

  16. Hanford Waste Vitrification Plant Project Waste Form Qualification Program Plan

    International Nuclear Information System (INIS)

    Randklev, E.H.

    1993-06-01

    The US Department of Energy has created a waste acceptance process to help guide the overall program for the disposal of high-level nuclear waste in a federal repository. This Waste Form Qualification Program Plan describes the hierarchy of strategies used by the Hanford Waste Vitrification Plant Project to satisfy the waste form qualification obligations of that waste acceptance process. A description of the functional relationship of the participants contributing to completing this objective is provided. The major activities, products, providers, and associated scheduling for implementing the strategies also are presented

  17. Addendum 1 to CSER 96-025: PFP storage of 9.25/9.5 inch tall, 4.4 kg Pu cans on existing Vault 4 pedestals

    International Nuclear Information System (INIS)

    Hillesland, K.E.

    1997-01-01

    A nuclear criticality safety analysis has been performed to increase the approved plutonium mass limit for cans stored in Vault number-sign 4 cubicles at PFP. The original CSER 96-025 accommodated the storage of 4.4 kg of plutonium in PuO, (5.0 kg PuO,) in Vault number-sign 4 by requiring that half the cubicles be left vacant. This addendum allows for all the cubicles to be used, but with a fissile plutonium mass limit of 58 kg per cubicle. A mass limit for each cubical allows for storage of a larger number of cans if some have less than the 4.4 kg Pu limit per can. The highest k., calculated is 0.932 + 0.003 when an overbatched can is present in every fourth cubicle. This is below the criticality safety limit of kff 0.935, and consequently, an increase of plutonium mass to 4.4 kg per can is within acceptable safety limits for the given mass limit

  18. An assessment of plant biointrusion at the Uranium Mill Tailings Remedial Action Project rock-covered disposal cells

    International Nuclear Information System (INIS)

    1990-10-01

    This study is one of a number of special studies that have been conducted regarding various aspects of the Uranium Mill Tailings Remedial Action (UMTRA) Project. This special study was proposed following routine surveillance and maintenance surveys and observations reported in a special study of vegetative covers (DOE, 1988), in which plants were observed growing up through the rock erosion layer at recently completed disposal cells. Some of the plants observed were deep-rooted woody species, and questions concerning root intrusion into disposal cells and the need to control plant growth were raised. The special study discussed in this report was designed to address some of the ramifications of plant growth on disposal cells that have rock covers. The NRC has chosen rock covers over vegetative covers in the arid western United States because licenses cannot substantiate that the vegetative covers ''will be significantly greater than 30 percent and preferably 70 percent,'' which is the amount of ''vegetation required to reduce flow to a point of stability.'' The potential impacts of vegetation growing in rock covers are not addressed by the NRC (1990). The objectives, then, of this study were to determine the species of plants growing on two rock-covered disposal cells, study the rooting pattern of plants on these cells, and identify possible impacts of plant root penetration on these and other UMTRA Project rock-covered cells

  19. Development of absolute radiometric response functions for HyPlant & G-LiHT using SIRCUS Project

    Data.gov (United States)

    National Aeronautics and Space Administration — The goal of this project is to provide absolute radiometric and cross-calibrated spectral characterizations for G-LiHT and HyPlant.  The objectives are: (i) to...

  20. Engineering and training simulators: A combined approach for nuclear plant construction projects

    International Nuclear Information System (INIS)

    Harnois, Olivier; Gain, Pascal; Bartak, Jan; Gathmann, Ralf

    2007-01-01

    Full text: Simulation technologies have always been widely used on nuclear applications, but with a clear division between engineering application, using highly validated code run in batch mode, and training purpose where real time computation is a mandatory requirement. Thanks to the flexibility of modern simulation technology and the increased performance of computers, it becomes now possible to develop Nuclear Power plant simulators that can be used both for engineering and training purposes. In the last years, the revival of nuclear industry raised a number of new construction or plant finishing projects in which the application of this combined approach would result in decisive improvement on plant construction lead times, better project control and cost optimizations. The simulator development is to be executed in a step-wise approach, scheduled in parallel with the plant design and construction phases. During a first step, the simulator will model the plant nuclear island systems plus the corresponding instrumentation and control, specific malfunctions and local commands. It can then be used for engineering activities defining and validating the plant operating strategies in case of incidents or accidents. The Simulator executive Station and Operator Station will be in prototype version with an interface imagery enabling monitoring and control of the simulator. Availability of such simulation platform leads to a significant increase in efficiency of the engineering works, the possibility to validate basic design hypotheses and detect defects and conflicts early. The second phase will consist in the fully detailed simulation of Main Control Room plant supervision and control MMI, taking into account I and C control loops detailed design improvement, while having sufficient fidelity in order to be suitable for the future operator training. Its use will enable the engineering units not only to specify and validate normal, incident and accident detailed plant

  1. Pilot project concerning the establishment of a collective biomass conversion plant on the island of Mors

    International Nuclear Information System (INIS)

    1993-06-01

    This pilot project comprises a feasibility study in connection with plans to establish a biomass conversion plant, on the Danish island of Mors, which would provide methane to be used as fuel, in combination with natural gas, for a cogeneration plant serving six villages. The subjects of location, organization, the transportation of biomass, the design of the biomass conversion plant, economical aspects and conditions of the use of the methane are discussed as a basis for decisions in this respect. Environmental considerations are also dealt with. (AB)

  2. Controlling engineering project changes for multi-unit, multi-site standardized nuclear power plants

    International Nuclear Information System (INIS)

    Randall, E.; Boddeker, G.; McGugin, H.; Strother, E.; Waggoner, G.

    1978-01-01

    Multibillioin dollar multiple nuclear power plant projects have numerous potential sources of engineering changes. The majority of these are internally generated changes, client generated changes, and changes from construction, procurement, other engineering organizations, and regulatory organizations. For multiunit, multisite projects, the use of a standardized design is cost effective. Engineering changes can then be controlled for a single standardized design, and the unit or site unique changes can be treated as deviations. Once an effective change procedure is established for change control of the standardized design, the same procedures can be used for control of unit or site unique changes

  3. Tri-State Synfuels Project Review: Volume 12. Fluor project status. [Proposed Henderson, Kentucky coal to gasoline plant; engineering

    Energy Technology Data Exchange (ETDEWEB)

    1982-06-01

    The purpose of this report is to document and summarize activities associated with Fluor's efforts on the Tri-State Synfuels Project. The proposed facility was to be coal-to-transport fuels facility located in Henderson, Kentucky. Tri-State Synfuels Company was participating in the project as a partner of the US Department of Energy per terms of a Cooperative Agreement resulting from DOE's synfuel's program solicitation. Fluor's initial work plan called for preliminary engineering and procurement services to the point of commitment for construction for a Sasol Fischer-Tropsch plant. Work proceeded as planned until October 1981 when results of alternative coal-to-methanol studies revealed the economic disadvantage of the Synthol design for US markets. A number of alternative process studies followed to determine the best process configuration. In January 1982 Tri-State officially announced a change from Synthol to a Methanol to Gasoline (MTG) design basis. Further evaluation and cost estimates for the MTG facility eventually led to the conclusion that, given the depressed economic outlook for alternative fuels development, the project should be terminated. Official announcement of cancellation was made on April 13, 1982. At the time of project cancellation, Fluor had completed significant portions of the preliminary engineering effort. Included in this report are descriptions and summaries of Fluor's work during this project. In addition location of key project data and materials is identified and status reports for each operation are presented.

  4. Project structure plan requirements for the deconstruction projects

    International Nuclear Information System (INIS)

    Petrasch, Peter; Schmitt, Christian; Stapf, Meike

    2011-01-01

    The deconstruction of nuclear facilities requires due to the particular conditions and the size of the project a special project planning. The authors analyze the possible requirements to be fulfilled by a project structure plan for nuclear facilities, including personnel resources, organization structure, budget questions, operation and project oriented measures, possibility of modifications and supplements. Further topics include controlling and project realization procedures, documentation, third party activities (authorities, consultants, surveyors), logistics and transport, and radiation protection issues. Several questions remain for plants-specific planning, including the integration of the plant personnel, administrative work, project management, economic and financial issues, radioactive waste management issues.

  5. Plant Responses to Increased UV-B Radiation: A Research Project

    Science.gov (United States)

    DAntoni, H. L.; Skiles, J. W.; Armstrong, R.; Coughlan, J.; Daleo, G.; Mayoral, A.; Lawless, James G. (Technical Monitor)

    1994-01-01

    Ozone decrease implies more ultraviolet-B (UV-B) radiation reaching the surface of the Earth. Increased UV-B radiation triggers responses by living organisms. Despite the large potential impacts on vegetation, little is known about UV-B effects on terrestrial ecosystems. Long-term ecological studies are needed to quantify the effects of increased UV radiation on terrestrial ecosystems, asses the risks, and produce reliable data for prediction. Screening pigments are part of one of the protective mechanism in plants. Higher concentrations of screening pigments in leaves may be interpreted as a response to increased UV radiation. If the screening effect is not sufficient, important molecules will be disturbed by incoming radiation. Thus, genetics, photosynthesis, growth, plant and leaf shape and size, and pollen grains may be affected. This will have an impact on ecosystem dynamics, structure and productivity. It is necessary to monitor selected terrestrial ecosystems to permit detection and interpretation of changes attributable to global climate change and depleted ozone shield. The objectives of this project are: (1) To identify and measure indicators of the effects of increased solar UV-B radiation on terrestrial plants; (2) to select indicators with the greatest responses to UV-B exposure; (3) to test, adapt or create ecosystem models that use the information gathered by this project for prediction and to enhance our understanding of the effects of increased UV-B radiation on terrestrial ecosystems. As a first step to achieve these objectives we propose a three-year study of forest and steppe vegetation on the North slope of the Brooks Range (within the Arctic circle, in Alaska), in the Saguaro National Monument (near Tucson, Arizona) and in the forests and steppes of Patagonia (Argentina). We selected (1) vegetation north of the Polar Circle because at 70N there is 8% risk of plant damage due to increased UV-B radiation; (2) the foothills of Catalina Mountains

  6. S.A.P. Students Adopt Plants: A Curriculum Guide for Independent Research Projects in High School Biology.

    Science.gov (United States)

    Wilkinson, Gayle A.

    This curriculum guide begins with classroom and text study of plants and develops into an individual research project that continues throughout the school year outside the regular biology or botany teaching plan and text. The project uses about one class period every 2 weeks for group discussions, evaluations, and suggestions for the individual…

  7. Projecting the success of plant restoration with population viability analysis

    Science.gov (United States)

    Bell, T.J.; Bowles, M.L.; McEachern, A.K.; Brigham, C.A.; Schwartz, M.W.

    2003-01-01

    Conserving viable populations of plant species requires that they have high probabilities of long-term persistence within natural habitats, such as a chance of extinction in 100 years of less than 5% (Menges 1991, 1998; Brown 1994; Pavlik 1994; Chap. 1, this Vol.). For endangered and threatened species that have been severely reduces in range and whose habitats have been fragmented, important species conservation strategies may include augmenting existing populations or restoring new viable populations (Bowles and Whelan 1994; Chap. 2, this Vol.). Restoration objectives may include increasing population numbers to reduce extinction probability, deterministic manipulations to develop a staged cohort structure, or more complex restoration of a desired genetic structure to allow outcrossing or increase effective population size (DeMauro 1993, 1994; Bowles et al. 1993, 1998; Pavlik 1994; Knapp and Dyer 1998; Chap. 2, this Vol.). These efforts may require translocation of propagules from existing (in situ) populations, or from ex situ botanic gardens or seed storage facilities (Falk et al. 1996; Guerrant and Pavlik 1998; Chap. 2, this Vol.). Population viability analysis (PVA) can provide a critical foundation for plant restoration, as it models demographic projections used to evaluate the probability of population persistence and links plant life history with restoration strategies. It is unknown how well artificially created populations will meet demographic modeling requirements (e.g., due to artificial cohort transitions) and few, if any, PVAs have been applied to restorations. To guide application of PVA to restored populations and to illustrate potential difficulties, we examine effects of planting different life stages, model initial population sizes needed to achieve population viability, and compare demographic characteristics between natural and restored populations. We develop and compare plant population restoration viability analysis (PRVA) case studies of

  8. One System Integrated Project Team Progress in Coordinating Hanford Tank Farms and the Waste Treatment Plant

    International Nuclear Information System (INIS)

    Skwarek, Raymond J.; Harp, Ben J.; Duncan, Garth M.

    2013-01-01

    The One System Integrated Project Team (IPT) was formed at the Hanford Site in late 2011 as a way to improve coordination and itegration between the Hanford Tank Waste Treatment and Immobilization Plant (WTP) and the Tank Operations Contractor (TOC) on interfaces between the two projects, and to eliminate duplication and exploit opportunities for synergy. The IPT is composed of jointly staffed groups that work on technical issues of mutal interest, front-end design and project definition, nuclear safety, plant engineering system integration, commissioning, planning and scheduling, and environmental, safety, health and quality (ESH&Q) areas. In the past year important progress has been made in a number of areas as the organization has matured and additional opportunities have been identified. Areas covered in this paper include: Support for development of the Office of Envirnmental Management (EM) framework document to progress the Office of River Protection's (ORP) River Protection Project (RPP) mission; Stewardship of the RPP flowsheet; Collaboration with Savannah River Site (SRS), Savannah River National Laboratory (SRNL), and Pacific Northwest National Laboratory (PNNL); Operations programs integration; and, Further development of the waste acceptance criteria

  9. SLUDGE TREATMENT PROJECT PHASE 1 SLUDGE STORAGE OPTIONS. ASSESSMENT OF T PLANT VERSUS ALTERNATE STORAGE FACILITY

    International Nuclear Information System (INIS)

    Rutherford, W.W.; Geuther, W.J.; Strankman, M.R.; Conrad, E.A.; Rhoadarmer, D.D.; Black, D.M.; Pottmeyer, J.A.

    2009-01-01

    The CH2M HILL Plateau Remediation Company (CHPRC) has recommended to the U.S. Department of Energy (DOE) a two phase approach for removal and storage (Phase 1) and treatment and packaging for offsite shipment (Phase 2) of the sludge currently stored within the 105-K West Basin. This two phased strategy enables early removal of sludge from the 105-K West Basin by 2015, allowing remediation of historical unplanned releases of waste and closure of the 100-K Area. In Phase 1, the sludge currently stored in the Engineered Containers and Settler Tanks within the 105-K West Basin will be transferred into sludge transport and storage containers (STSCs). The STSCs will be transported to an interim storage facility. In Phase 2, sludge will be processed (treated) to meet shipping and disposal requirements and the sludge will be packaged for final disposal at a geologic repository. The purpose of this study is to evaluate two alternatives for interim Phase 1 storage of K Basin sludge. The cost, schedule, and risks for sludge storage at a newly-constructed Alternate Storage Facility (ASF) are compared to those at T Plant, which has been used previously for sludge storage. Based on the results of the assessment, T Plant is recommended for Phase 1 interim storage of sludge. Key elements that support this recommendation are the following: (1) T Plant has a proven process for storing sludge; (2) T Plant storage can be implemented at a lower incremental cost than the ASF; and (3) T Plant storage has a more favorable schedule profile, which provides more float, than the ASF. Underpinning the recommendation of T Plant for sludge storage is the assumption that T Plant has a durable, extended mission independent of the K Basin sludge interim storage mission. If this assumption cannot be validated and the operating costs of T Plant are borne by the Sludge Treatment Project, the conclusions and recommendations of this study would change. The following decision-making strategy, which is

  10. SLUDGE TREATMENT PROJECT PHASE 1 SLUDGE STORAGE OPTIONS ASSESSMENT OF T PLANT VERSUS ALTERNATE STORAGE FACILITY

    Energy Technology Data Exchange (ETDEWEB)

    RUTHERFORD WW; GEUTHER WJ; STRANKMAN MR; CONRAD EA; RHOADARMER DD; BLACK DM; POTTMEYER JA

    2009-04-29

    The CH2M HILL Plateau Remediation Company (CHPRC) has recommended to the U.S. Department of Energy (DOE) a two phase approach for removal and storage (Phase 1) and treatment and packaging for offsite shipment (Phase 2) of the sludge currently stored within the 105-K West Basin. This two phased strategy enables early removal of sludge from the 105-K West Basin by 2015, allowing remediation of historical unplanned releases of waste and closure of the 100-K Area. In Phase 1, the sludge currently stored in the Engineered Containers and Settler Tanks within the 105-K West Basin will be transferred into sludge transport and storage containers (STSCs). The STSCs will be transported to an interim storage facility. In Phase 2, sludge will be processed (treated) to meet shipping and disposal requirements and the sludge will be packaged for final disposal at a geologic repository. The purpose of this study is to evaluate two alternatives for interim Phase 1 storage of K Basin sludge. The cost, schedule, and risks for sludge storage at a newly-constructed Alternate Storage Facility (ASF) are compared to those at T Plant, which has been used previously for sludge storage. Based on the results of the assessment, T Plant is recommended for Phase 1 interim storage of sludge. Key elements that support this recommendation are the following: (1) T Plant has a proven process for storing sludge; (2) T Plant storage can be implemented at a lower incremental cost than the ASF; and (3) T Plant storage has a more favorable schedule profile, which provides more float, than the ASF. Underpinning the recommendation of T Plant for sludge storage is the assumption that T Plant has a durable, extended mission independent of the K Basin sludge interim storage mission. If this assumption cannot be validated and the operating costs of T Plant are borne by the Sludge Treatment Project, the conclusions and recommendations of this study would change. The following decision-making strategy, which is

  11. GRIN-Global: An International Project to Develop a Global Plant Genebank Information Management System

    Science.gov (United States)

    The mission of the GRIN-Global Project is to create a new, scalable version of the Germplasm Resource Information System (GRIN) to provide the world’s crop genebanks with a powerful, flexible, easy-to-use plant genetic resource (PGR) information management system. The system will help safeguard PGR ...

  12. PROJECT MANAGEMENT MATURITY: AN ASSESSMENT OF MATURITY FOR DEVELOPING PILOT PLANTS

    Directory of Open Access Journals (Sweden)

    H.K. Mittermaier

    2012-01-01

    Full Text Available

    ENGLISH ABSTRACT: Despite the current economic climate, the South African mining and engineering industry is experiencing a very promising future, with a large number of capital projects in the offing. It is inevitable that pilot plant development will form part of this future as a risk mitigation technique. This study found that, even though the terms ‘pilot plant’ and ‘project management maturity’ are familiar within the industry, no link between these two could be found in the literature. A number of maturity models exist; and one developed by PMSolutions was selected to perform an assessment of the current level of project management maturity within the South African mining and engineering industry pertaining to the development of pilot plants. The Delphi technique was used to determine the views of experts in the South African mining, mineral processing, petrochemical, nuclear, and mechanical sectors regarding this maturity. A significant difference was observed between the current level of maturity and the required level of maturity in all but one of the nine knowledge areas defined by the Project Management Institute. The two knowledge areas of project time and risk management showed significant differences between current and required maturity levels, and were identified as key areas for improvement.

    AFRIKAANSE OPSOMMING: Ten spyte van die huidige ekonomiese klimaat ondervind die Suid-Afrikaanse mynbou- en ingenieursbedryf ’n baie bemoedigende toekoms, met ’n groot aantal kapitaalprojekte in die vooruitsig. Ten einde risiko’s te verlaag, sal die ontwikkeling van loodsaanlegte noodwendig deel van hierdie toekoms uitmaak. Daar is gevind dat, alhoewel die terme ‘loodsaanleg’ en ‘projekbestuur volwassenheid’ in die nywerheid bekend is, geen skakeling van hierdie twee terme in die literatuur opgespoor kon word nie. ’n Aantal volwassenheid modelle bestaan; en een wat deur PMSolutions ontwikkel is, is gekies om

  13. Economic Analysis of Cikaso Mini Hydro Power Plant as a CDM Project for Increasing IRR

    OpenAIRE

    Febijanto, Irhan

    2013-01-01

    Renewable energy fueled power generations are few developed by private sector in Indonesia. High-cost investment and low electricity selling price to PT PLN as a single buyer is main barriers for private sector to involve in the development of renewable energy fueled power generations. In this project, the economic feasibility of Mini Hydro Power Plant of Cikaso with capacity of 5.3 MW, located at Sukabumi Regency, West Java province was assessed. This project utilized revenue generated from ...

  14. The biggest rooftop PV plant in Latin America. An example of a pioneering project for the whole region

    International Nuclear Information System (INIS)

    2016-01-01

    About a year ago, the largest rooftop PV installation in Latin America came online in Honduras. Inaugurated by the country’s president, Juan Orlando Hernández, in March 2015, the plant is situated on the roof of the region’s PepsiCo bottling plant, EMSULA (Embotelladora de Sula S.A.) in the town of San Pedro Sula. The project, which has become a reference in the region, has been developed over two phases, the first of which corresponds to a 259 kWp pilot project, commissioned in November 2013, to which the second phase was added last year. (Author)

  15. Study of system safety evaluation on LTO of national project. NISA safety research project on system safety of nuclear power plants

    International Nuclear Information System (INIS)

    Takizawa, Masayuki; Sekimura, Naoto; Miyano, Hiroshi; Aoyama, Katsunobu

    2012-01-01

    Japanese safety regulatory body, that is, Nuclear and Industrial Safety Agency (NISA) started a 5-year national safety research project as 'the first stage' from 2006 FY to 2010 FY whose objective is 'Improve the technical information basis in order to utilize knowledge as well as information related to ageing management and maintenance of NPPs. Fukushima disaster happened in March 2011, and the priority of research needs for ageing management dramatically changed in Japan. The second-stage national project started in October 2011 with the concept of 'system safety' of NNPs where not only ageing management on degradation phenomena of important components but also safety management on total plant systems are paid attention to. The second-stage project is so called 'Japanese Ageing Management Program for System Safety (JAMPSS)'. (author)

  16. Software and man-machine interface considerations for a nuclear plant computer replacement and upgrade project

    International Nuclear Information System (INIS)

    Diamond, G.; Robinson, E.

    1984-01-01

    Some of the key software functions and Man-Machine Interface considerations in a computer replacement and upgrade project for a nuclear power plant are described. The project involves the installation of two separate computer systems: an Emergency Response Facilities Computer System (ERFCS) and a Plant Process Computer System (PPCS). These systems employ state-of-the-art computer hardware and software. The ERFCS is a new system intended to provide enhanced functions to meet NRC post-TMI guidelines. The PPCS is intended to replace and upgrade an existing obsolete plant computer system. A general overview of the hardware and software aspects of the replacement and upgrade is presented. The work done to develop the upgraded Man-Machine Interface is described. For the ERFCS, a detailed discussion is presented of the work done to develop logic to evaluate the readiness and performance of safety systems and their supporting functions. The Man-Machine Interface considerations of reporting readiness and performance to the operator are discussed. Finally, the considerations involved in the implementation of this logic in real-time software are discussed.. For the PPCS, a detailed discussion is presented of some new features

  17. Application of ABWR construction database to nuclear power plant project

    International Nuclear Information System (INIS)

    Takashima, Atsushi; Katsube, Yasuhiko

    1999-01-01

    Tokyo Electric Power Company (TEPCO) completed the construction of Kashiwazaki-Kariwa Nuclear Power Station Unit No. 6 and No. 7 (K-6/7) as the first advanced boiling water reactors (ABWR) in the world successfully. K-6 and K-7 started their commercial operations in November, 1996 and in July, 1997 respectively. We consider ABWR as a standard BWR in the world as well as in Japan because ABWR is highly reputed. However, because the interval of our nuclear power plant construction is going to be longer, our engineering level on plant construction will be declining. Hence it is necessary for us to maintain our engineering level. In addition to this circumstance, we are planning to wide application of separated purchase orders for further cost reduction. Also there is an expectation for our contribution to ABWR plant constructions overseas. As facing these circumstances, we have developed a construction database based on our experience for ABWR construction. As the first step of developing the database for these use, we analyzed our own activities in the previous ABWR construction. Through this analysis, we could define activity units of which the project consists. As the second step, we clarified the data which are treated in each activity unit and the interface among them. By taking these steps, we could develop our database efficiently. (author)

  18. Data base on nuclear power plant dose reduction research projects

    Energy Technology Data Exchange (ETDEWEB)

    Khan, T.A.; Baum, J.W.

    1986-10-01

    Staff at the ALARA Center of Brookhaven National Laboratory have established a data base of information about current research that is likely to result in lower radiation doses to workers. The data base, concerned primarily with nuclear power generation, is part of a project that the ALARA Center is carrying out for the Nuclear Regulatory Commission. This report describes its current status. A substantial amount of research on reducing occupational exposure is being done in the US and abroad. This research is beginning to have an impact on the collective dose expenditures at nuclear power plants. The collective radiation doses in Europe, Japan, and North America all show downward trends. A large part of the research in the US is either sponsored by the nuclear industry through joint industry organizations such as EPRI and ESEERCO or is done by individual corporations. There is also significant participation by smaller companies. The main emphasis of the research on dose reduction is on engineering approaches aimed at reducing radiation fields or keeping people out of high-exposure areas by using robotics. Effective ALARA programs are also underway at a large number of nuclear plants. Additional attention should be given to non-engineering approaches to dose reduction, which are potentially very useful and cost effective but require quantitative study and analysis based on data from nuclear power plants. 9 refs., 1 fig.

  19. Challenges associated with the design of underground grinding plant at McArthur River project

    International Nuclear Information System (INIS)

    Jamrozek, J.S.

    2000-01-01

    McArthur River is an unique high grade uranium underground mine. Ore grinding and thickening are part of the underground operation. The grinding circuit is designed to operate in conditions different from conventional plant environments. Design of the grinding plant was a collective effort of a multi-disciplinary engineering team closely cooperating with project operating personnel. The equipment had to be selected to reflect widely varying ore properties. A user-friendly plant layout provides access to equipment inspections, services, and the delivery of necessary components. The size of the grinding chamber was limited in order to keep the rock stress levels within allowable values. All underground equipment brought to the construction site was restricted in size and weight. Plant construction faced limited storage space underground, tight erection sequencing, and schedule. Plant ventilation is a critical design feature. It efficiently removes radioactive dust from work areas, eliminates stagnant air pockets, and separates clean air from contaminated air areas. Radiation shielding on the equipment is designed to correspond with operational and maintenance functions. Plant operation is remotely controlled and requires little attendance. Video cameras are used on critical equipment and in controlled access areas. An extensive program of preventive and predictive maintenance allows highly reliable plant operation. (author)

  20. Computer software configuration management plan for the Honeywell modular automation system

    International Nuclear Information System (INIS)

    Cunningham, L.T.

    1997-01-01

    This document provides a Computer Software management plan for a new Honeywell Modular Automation System (MAS) being installed in the Plutonium Finishing Plant (PFP). This type of system will be used to control new thermal stabilization furnaces, a vertical denitrator calciner, and a pyrolysis furnace

  1. Project 2019 of Garona Nuclear power plant. First project to licensing renew more than 40 years in Spain

    International Nuclear Information System (INIS)

    Fernandez, R. A.; Torralbo, J. R.

    2004-01-01

    NUCLENOR has been developing lifetime management and modernisation activities at Santa Maria de Garona NPP since the end of the 80's and the plant is now in optimum technical conditions to continue in operation beyond its original lifetime planned in the design (40 years). In the USA, the country of origin of the project, a good number of power plants with a similar design, age and history to SMG are in the process of obtaining or have already obtained, a licensing extension of up to 60 years from the NRC. In Spain, the activities required for requesting a long-term operating licensing extension include the Ageing Assessment and Management of the plant systems, structures and components, in accordance with the american regulation 10CFR54, a Radiological Impact Study for the new operating period, and an Analysis of New Legislation, not included in the licensing bases and considered to be important to safety by the CSN. With a view to obtaining a renewal of the current operating permit for the period 2009-2019, NUCLENOR has launched the Proyecto 2019, which extends to technical and licensing aspects, as it involves all the company's personnel. (Author)

  2. A survey of research projects in maintenance optimization for Electricite de France power plants

    International Nuclear Information System (INIS)

    Jacquot, J.P.

    1996-01-01

    Six years ago, Electricite de France launched a Reliability Centered Maintenance (RCM) pilot project to optimize preventive maintenance for its nuclear power plants. After a feasibility study, a Reliability Centered Maintenance (RCM) method was standardized. It is now applied on a large scale to the 50 EDF nuclear units. A RCM workstation based on this standardized method has been developed and is now used in each plant. In the next step, the author will consider whether a risk based approach can be included in this RCM process in order to analyze critical passive components such as pipes and supports. Considering the potential advantages of these optimization techniques, a dedicated process has been also developed for maintenance of future plants, gas turbines, or nuclear units. For these future plants, a Logistic Support Analysis (LSA) will be added to the RCM process to globally evaluate availability, safety and maintenance costs. This paper will present a survey of these different developments of methods and tools

  3. Outfall 51 air stripping feasibility study for the Reduction of Mercury in Plant Effluent (RMPE) Project. Revision 1

    International Nuclear Information System (INIS)

    1997-01-01

    Within the US Department of Energy's Oak Ridge Y-12 Plant there are a number of industrial wastewater discharge points or outfalls that empty into East Fork Poplar Creek (EFPC). EFPC originates within and runs continuously throughout the plant site and subsequently flows out the east end of the Y-12 Plant into the City of Oak Ridge. Mercury is present in outfall discharges due to contact of water with the soils surrounding past mercury-use buildings. As a result, the Reduction of Mercury in Plant Effluent (RMPE) Project was developed to achieve and maintain environmental compliance with regards to mercury, and, in particular with the National Pollutant Discharge Elimination System permit for the Y-12 Plant. To achieve a reduction in mercury loading to EFPC, a number of options have already been studied and implemented as part of the RMPE project. With the successful implementation of these options, Outfall 51 remains as a significant contributor to mercury load to EFPC. The primary purpose of this project is to determine the feasibility of removing mercury from contaminated spring water using air stripping. In order to accomplish this goal, a number of different areas were addressed. A pilot-scale unit was tested in the field using actual mercury-contaminated source water. Properties which impact the mercury removal via air stripping were reviewed to determine their effect. Also, enhanced testing was performed to improve removal efficiencies. Finally, the variable outfall flow was studied to size appropriate processing equipment for full-scale treatment

  4. Preliminary project concerning the straw-fueled combined power-heat plant to be constructed at Glamsbjerg

    International Nuclear Information System (INIS)

    Gabriel, S.; Koch, T.

    1994-06-01

    Power and heat generation based on biomass gasification is of great importance due to its beneficial environmental effects and good economy. This report concerns a preliminary project on feasibility and problems of implementing a dual-purpose power plant, supplying both power and district heating to several schools, swimming pools and other public facilities at Glamsbjerg (Funen). The plant is to be based on thermal gasification (pyrolysis) of straw and use of the gas in a diesel engine. The diesels operate the power generator, and their waste heat should be utilized in the local district heating network. In order to establish a stable and flexible straw supply to the plant an evaluation of resources in the area has been carried out. Apart from straw-derived fuel the plant is planned to use natural gas for start and maintenance of the process. The prices of the combined plant and of the fuel processing are estimated in the report. (EG)

  5. Outlining the project of the new RADAG hydro power plant; Projektueberblick ueber den Neubau des RADAG-Wehrkraftwerkes

    Energy Technology Data Exchange (ETDEWEB)

    Rost, Manfred; Schlageter, Guenter [Rheinkraftwerk Albbruck-Dogern AG, Laufenburg-Rhina (Germany)

    2010-07-01

    After expiration of the license in 2003 the Swiss Federal Council and the Freiburg District Government issued a new operating license for another 70 years. This new license first of all allows RADAG to continue operation of the existing power plant, situated at the end of a 3,8 km long channel. At the same time, however, it requires the company to commission a new plant besides the existing barrage by the end of 2012, which will increase the present day output from 528 GWh up to 650 GWh per year. RADAG immediately got down working on the project of what would be one of the largest run-of-river power stations in Germany. The new license provides and increase of the total turbine water flow from originally 1 100 m{sup 3}/s up to 1 400 m{sup 3}/s. The new power plant contains one large Kaplan turbine with an installed total wattage of 28 MW, thus increasing the overall wattage up to 108 MW. The total project costs of the new plant amount to about 68 Mio Euro (price level as per 2007), including 4 Mio Euro for environmental measures. (orig.)

  6. Projected range contractions of European protected oceanic montane plant communities: focus on climate change impacts is essential for their future conservation.

    Science.gov (United States)

    Hodd, Rory L; Bourke, David; Skeffington, Micheline Sheehy

    2014-01-01

    Global climate is rapidly changing and while many studies have investigated the potential impacts of this on the distribution of montane plant species and communities, few have focused on those with oceanic montane affinities. In Europe, highly sensitive bryophyte species reach their optimum occurrence, highest diversity and abundance in the north-west hyperoceanic regions, while a number of montane vascular plant species occur here at the edge of their range. This study evaluates the potential impact of climate change on the distribution of these species and assesses the implications for EU Habitats Directive-protected oceanic montane plant communities. We applied an ensemble of species distribution modelling techniques, using atlas data of 30 vascular plant and bryophyte species, to calculate range changes under projected future climate change. The future effectiveness of the protected area network to conserve these species was evaluated using gap analysis. We found that the majority of these montane species are projected to lose suitable climate space, primarily at lower altitudes, or that areas of suitable climate will principally shift northwards. In particular, rare oceanic montane bryophytes have poor dispersal capacity and are likely to be especially vulnerable to contractions in their current climate space. Significantly different projected range change responses were found between 1) oceanic montane bryophytes and vascular plants; 2) species belonging to different montane plant communities; 3) species categorised according to different biomes and eastern limit classifications. The inclusion of topographical variables in addition to climate, significantly improved the statistical and spatial performance of models. The current protected area network is projected to become less effective, especially for specialised arctic-montane species, posing a challenge to conserving oceanic montane plant communities. Conservation management plans need significantly

  7. Projected range contractions of European protected oceanic montane plant communities: focus on climate change impacts is essential for their future conservation.

    Directory of Open Access Journals (Sweden)

    Rory L Hodd

    Full Text Available Global climate is rapidly changing and while many studies have investigated the potential impacts of this on the distribution of montane plant species and communities, few have focused on those with oceanic montane affinities. In Europe, highly sensitive bryophyte species reach their optimum occurrence, highest diversity and abundance in the north-west hyperoceanic regions, while a number of montane vascular plant species occur here at the edge of their range. This study evaluates the potential impact of climate change on the distribution of these species and assesses the implications for EU Habitats Directive-protected oceanic montane plant communities. We applied an ensemble of species distribution modelling techniques, using atlas data of 30 vascular plant and bryophyte species, to calculate range changes under projected future climate change. The future effectiveness of the protected area network to conserve these species was evaluated using gap analysis. We found that the majority of these montane species are projected to lose suitable climate space, primarily at lower altitudes, or that areas of suitable climate will principally shift northwards. In particular, rare oceanic montane bryophytes have poor dispersal capacity and are likely to be especially vulnerable to contractions in their current climate space. Significantly different projected range change responses were found between 1 oceanic montane bryophytes and vascular plants; 2 species belonging to different montane plant communities; 3 species categorised according to different biomes and eastern limit classifications. The inclusion of topographical variables in addition to climate, significantly improved the statistical and spatial performance of models. The current protected area network is projected to become less effective, especially for specialised arctic-montane species, posing a challenge to conserving oceanic montane plant communities. Conservation management plans need

  8. Human errors in test and maintenance of nuclear power plants. Nordic project work

    International Nuclear Information System (INIS)

    Andersson, H.; Liwaang, B.

    1985-08-01

    The present report is a summary of the NKA/LIT-1 project performed for the period 1981-1985. The report summarizes work on human error influence in test and calibration activities in nuclear power plants, reviews problems regarding optimization of the test intervals, organization of test and maintenance activities, and the analysis of human error contribution to the overall risk in test and mainenace tasks. (author)

  9. Southeast Regional Wastewater Treatment Plant Facilities Improvements Project and Geysers Effluent Pipeline Project. Draft EIR/EIS, Volume 2 of 2: Appendices

    International Nuclear Information System (INIS)

    1994-01-01

    The Southeast Regional Wastewater Treatment Plant (SERWTP) Facilities Improvement Plan and Geysers Effluent Pipeline and Effluent Injection Project are proposed as a plan to provide expanded wastewater treatment capabilities and to dispose of the effluent by injection in The Geysers geothermal field for purposes of power production. The project is located predominantly in the County of Lake, California, and also in part of Sonoma County. The plan includes various conventional facilities improvements in wastewater treatment to a secondary level of treatment at the SWERWTP. The plan includes facilities to convey the treated effluent in a 26-mile, 24-inch inside diameter pipeline to the Southeast Geysers. The wastewater from the SERWTP would be supplemented by raw lake water diverted from nearby Clear Lake. At The Geysers, the effluent would be directed into a system of distribution lines to wells. In the geothermal reservoir, the water will be converted to steam and collected in production wells that will direct the steam to six existing power plants. This document is a summary of a combined full Environmental Impact Report (EIR) and Environmental Impact Statement (EIS). The EIR/EIS describes the environmental impacts of the various components of the project. Mitigation measures are suggested for reducing impacts to a less than significant level. This report contains appendices A and B. Appendix A contains notices of preparation/notices of intent and EIR/EIS scoping comments. Appendix B contains GeothermEx, Inc., analysis of Geothermal Reservoir Effects and Induced Seismicity

  10. Data base on dose reduction research projects for nuclear power plants. Volume 4

    Energy Technology Data Exchange (ETDEWEB)

    Khan, T.A.; Vulin, D.S.; Liang, H.; Baum, J.W. [Brookhaven National Lab., Upton, NY (United States)

    1992-08-01

    This is the fourth volume in a series of reports that provide information on dose reduction research and health physics technology for nuclear power plants. The information is taken from a data base maintained by Brookhaven National Laboratory`s ALARA Center for the Nuclear Regulatory Commission. This report presents information on 118 new or updated projects, covering a wide range of activities. Projects including steam generator degradation, decontamination, robotics, improvement in reactor materials, and inspection techniques, among others, are described in the research section of the report. The section on health physics technology includes some simple and very cost-effective projects to reduce radiation exposures. Included in this volume is a detailed description of how to access the BNL data bases which store this information. All project abstracts from this report, as well as many other useful documents, can be accessed, with permission, through our on-line system, ACE. A computer equipped with a modem, or a fax machine is all that is required to connect to ACE. Many features of ACE, including software, hardware, and communications specifics, are explained in this report.

  11. Honeywell Modular Automation System Computer Software Documentation

    International Nuclear Information System (INIS)

    CUNNINGHAM, L.T.

    1999-01-01

    This document provides a Computer Software Documentation for a new Honeywell Modular Automation System (MAS) being installed in the Plutonium Finishing Plant (PFP). This system will be used to control new thermal stabilization furnaces in HA-211 and vertical denitration calciner in HC-230C-2

  12. The development of a wood fuel gasification plant utilising short rotation coppice and forestry residues: project ARBRE

    International Nuclear Information System (INIS)

    Pitcher, K.F.; Lundbergt, H.

    1997-01-01

    This paper will discuss the development of ARBRE Energy, a joint venture company that includes Yorkshire Environmental of the United Kingdom and Tenniska Processer AB of Sweden. The project will establish 2000 hectares of short rotation coppices, some of which will be organically fertilized with digested sewage sludges, to provide 80% of the fuel requirements of a biomass integrated gasification combined cycle (BIGCC) electricity generation plant. The remaining 20% of the fuel requirements will come from forestry waste, although in the first 5 years all the fuel will come from the forestry sources until the coppices are mature. The project will construct a gasification plant at Eggborough, North Yorkshire, England, which will provide gas to a gas turbine and steam turbine generation system, producing 10 MW and exporting 8 MW of electricity. It has been included in the 1993 tranche of the UK's Non Fossil Fuel Obligation (NFFO) and has gained financial support from the European Commission's THERMIE programme as a targeted BIGCC project. The project's technical and environmental effects and benefits will be examined in detail, together with the award of its planning permit and agreement on its operating license. (author)

  13. Feasibility improvement project for the gas turbine power plant in Iran

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2001-03-01

    Investigations and discussions have been given on measures to improve energy conservation and efficiency at a power plant of Kish Water and Power Company (KWPC) in Iran. The site has high ambient temperature throughout a year, making the gas turbine power plant capable of generating power only at about 70% of the rated output, with the power generation efficiency decreasing. The project has analyzed the current situation at the plant, and evaluated different means that appear effective in improving the efficiency, including the gas turbine absorbed air cooling system, the steam injection system, and the combined cycle. As a result of the discussions, it was revealed that energy saving effect can be obtained at 145 TJ with the gas turbine absorbed air cooling system, 224 TJ with the steam injection system, and 1017 TJ with the combined cycle. The annual reduction of greenhouse gas emission due to the above energy conservation would be about 11 thousand tons, 16.5 thousand tons, and 75 thousand tons, respectively. However, the investment payback period would be about 2.45 years, 8.31 years, and 14.21 years, respectively. Therefore, the profitability does not appear very attractive because of low fuel unit cost. (NEDO)

  14. Future-oriented computerized information system for power plant process control in a pilot project at Philippsburg nuclear power plant

    International Nuclear Information System (INIS)

    Woehrle, G.; Kraft, M.

    1988-01-01

    The motivation for the pilot project at Philippsburg nuclear power plant resulted from the Three Mile Island accident in 1979. The primary task embraces an efficient computer-aided reduction of information when a fault occurs based on a process engineering analysis of the information accrued. Accompanying this are a consolidation and evaluation of the information available in the control room. In this pilot project the new tasks of status monitoring, information reduction and operationalcontrol have been realized for the first time using a computer-aided process information system. In addition to the existing control computer, an information computer with approximately 1200 analogue and about 10000 binary signals has been installed. The installation of the system was completed in 1984 and in the meantime initial operational experience has become available. (orig.) [de

  15. Reactivation of nuclear power plant construction projects. Plant status, policy issues and regulatory options

    International Nuclear Information System (INIS)

    Spangler, M.B.

    1986-07-01

    Prior to the TMI-2 accident on March 28, 1979, four nuclear power plant units that had previously been issued a construction permit were cancelled, principally because of reduced projections of regional power demand. Since that time, an additional 31 units with CPs have been cancelled and eight units deferred. On December 23, 1985 one of the deferred units (Limerick-2) was reactivated and construction resumed. The primary objective of this policy study is to identify the principal issues requiring office-level consideration in the event of reactivation of the construction of one or more of the nuclear power plants falling into two categories: (1) LWR units issued a construction permit whose construction has been cancelled, and (2) LWR units whose construction has been deferred. The study scope is limited to identifying regulatory issues or questions deserving analysis rather than providing, at this time, answers or recommended actions. Five tasks are addressed: a tabulation and discussion of the status of all cancelled and deferred LWR units; and identification of potential safety and environmental issues; an identification of regulatory or policy issues and needed information to determine the desirability of revising certain rules and policies; and identification of regulatory options and decision criteria; and an identification of decision considerations in determining staff requirements and organizational coordination of LWR reactivation policy and implementation efforts. 41 refs

  16. Passive Nuclear Plants Program (UPDATE)

    International Nuclear Information System (INIS)

    Chimeno, M. A.

    1998-01-01

    The light water passive plants program (PCNP), today Advanced Nuclear Power Plants Program (PCNA), was constituted in order to reach the goals of the Spanish Electrical Sector in the field of advanced nuclear power plants, optimize the efforts of all Spanish initiatives, and increase joint presence in international projects. The last update of this program, featured in revision 5th of the Program Report, reflects the consolidation of the Spanish sector's presence in International programs of the advanced power plants on the basis of the practically concluded American ALWR program. Since the beginning of the program , the PCNP relies on financing from the Electrical sector, Ocide, SEPI-Endesa, Westinghouse, General Electric, as well as from the industrial cooperators, Initec, UTE (Initec- Empresarios Agrupados), Ciemat, Enusa, Ensa and Tecnatom. The program is made up of the following projects, already concluded: - EPRI's Advanced Light Water Plants Certification Project - Westinghouse's AP600 Project - General Electric's SBWR Project (presently paralyzed) and ABWR project Currently, the following project are under development, at different degrees of advance: - EPP project (European Passive Plant) - EBWR project (European Advanced Boiling Water Reactor)

  17. Macro optical projection tomography for large scale 3D imaging of plant structures and gene activity.

    Science.gov (United States)

    Lee, Karen J I; Calder, Grant M; Hindle, Christopher R; Newman, Jacob L; Robinson, Simon N; Avondo, Jerome J H Y; Coen, Enrico S

    2017-01-01

    Optical projection tomography (OPT) is a well-established method for visualising gene activity in plants and animals. However, a limitation of conventional OPT is that the specimen upper size limit precludes its application to larger structures. To address this problem we constructed a macro version called Macro OPT (M-OPT). We apply M-OPT to 3D live imaging of gene activity in growing whole plants and to visualise structural morphology in large optically cleared plant and insect specimens up to 60 mm tall and 45 mm deep. We also show how M-OPT can be used to image gene expression domains in 3D within fixed tissue and to visualise gene activity in 3D in clones of growing young whole Arabidopsis plants. A further application of M-OPT is to visualise plant-insect interactions. Thus M-OPT provides an effective 3D imaging platform that allows the study of gene activity, internal plant structures and plant-insect interactions at a macroscopic scale. © The Author 2016. Published by Oxford University Press on behalf of the Society for Experimental Biology.

  18. Projected role of nuclear power in Egypt and problems encountered in implementing the first nuclear plant

    International Nuclear Information System (INIS)

    Effat, K.E.A.; Sirry, H.; El-Fouly, M.F.; El-Sharkawy, E.; El-Saiedi, A.F.

    1977-01-01

    This paper reviews the present and projected power demands in Egypt and the factors behind the decision to introduce a nuclear power generation program. Different problems encountered and anticipated in introducing the first nuclear power plant are also discussed

  19. Nuclear power plants. The market for services, retrofitting, construction of new plants and dismantling of older plants in Europe through 2030

    International Nuclear Information System (INIS)

    Briese, Dirk; Hoemske, Tom

    2010-01-01

    The power plant scene in Europe is characterized by new power plant projects and retrofitting projects everywhere. This is due to the ageing of existing power plants and to increasing energy demand. Currently, there are projects for 48 power plant units with an installed capacity of 70 GW. According to a study of the nuclear power plant sector, about 16 GW will probably be constructed prior to 2030. The reference scenario presented in this article assumes a dynamic increase of 15 thousand million Euros per annum through 2016/2018. (orig.)

  20. Radioactive Air Emission Notice of Construction for (NOC) Plutonium Finishing Plant (PFP) Project W-460 Plutonium Stabilization and Handling

    International Nuclear Information System (INIS)

    JANSKY, M.T.

    2000-01-01

    The following description and any attachments and references are provided to the Washington State Department of Health (WDOH), Division of Radiation Protection, Air Emissions and Defense Waste Section as a notice of construction (NOC) in accordance with Washington Administrative Code (WAC) 246-247, Radiation Protection-Air Emissions. The WAC 246-247-060, ''Applications, registration, and licensing'', states ''This section describes the information requirements for approval to construct, modify, and operate an emission unit. Any NOC requires the submittal of information listed in Appendix A,'' Appendix A (WAC 246-247-1 IO) lists the requirements that must be addressed. Additionally, the following description, attachments, and references are provided to the U.S. Environmental Protection Agency (EPA) as an NOC, in accordance with Title 40 Code of Federal Regulations (CFR), Part 61, ''National Emission Standards for Hazardous Air Pollutants.'' The information required for submittal to the EPA is specified in 40 CFR 61.07. The potential emissions from this activity are estimated to provide greater than 0.1 millirem year total effective dose equivalent (TEDE) to the hypothetical offsite maximally exposed individual (MEI) and commencement is needed within a short time. Therefore, this application also is intended to provide notification of the anticipated date of initial startup in accordance with the requirement listed in 40 CFR 61.09(a)(1), and it is requested that approval of this application also constitutes EPA acceptance of this initial startup notification. Written notification of the actual date of initial startup, in accordance with the requirement listed in 40 CFR 61.09(a)(2), will be provided later. This NOC covers the activities associated with the construction and operation activities involving stabilization and/or repackaging of plutonium in the 2736-ZB Building. An operations support trailer will be installed in the proximity of the 2736-ZB Building. A new exhaust stack will be built and operated at the 2736-ZB Building to handle the effluents associated with the operation of the stabilization and repackaging process. Figures provided are based on preliminary design

  1. Facility Operations 1993 fiscal year work plan: WBS 1.3.1

    Energy Technology Data Exchange (ETDEWEB)

    1992-11-01

    The Facility Operations program is responsible for the safe, secure, and environmentally sound management of several former defense nuclear production facilities, and for the nuclear materials in those facilities. As the mission for Facility Operations plants has shifted from production to support of environmental restoration, each plant is making a transition to support the new mission. The facilities include: K Basins (N Reactor fuel storage); N Reactor; Plutonium-Uranium Reduction Extraction (PUREX) Plant; Uranium Oxide (UO{sub 3}) Plant; 300 Area Fuels Supply (N Reactor fuel supply); Plutonium Finishing Plant (PFP).

  2. Facility Operations 1993 fiscal year work plan: WBS 1.3.1

    International Nuclear Information System (INIS)

    1992-11-01

    The Facility Operations program is responsible for the safe, secure, and environmentally sound management of several former defense nuclear production facilities, and for the nuclear materials in those facilities. As the mission for Facility Operations plants has shifted from production to support of environmental restoration, each plant is making a transition to support the new mission. The facilities include: K Basins (N Reactor fuel storage); N Reactor; Plutonium-Uranium Reduction Extraction (PUREX) Plant; Uranium Oxide (UO 3 ) Plant; 300 Area Fuels Supply (N Reactor fuel supply); Plutonium Finishing Plant (PFP)

  3. Foaming in Hanford River Protection Project Waste Treatment Plant LAW Evaporation Processes - FY01 Summary Report

    International Nuclear Information System (INIS)

    Calloway, T.B.

    2002-01-01

    The LAW evaporation processes currently being designed for the Hanford River Protection Project Waste Treatment Plant are subject to foaming. Experimental simulant studies have been conducted in an effort to achieve an effective antifoam agent suitable to mitigate such foaming

  4. AN APPROACH TO CHARACTERIZING and EVALUATING ALTERNATIVES FOR THE DECOMMISSIONING OF SUB-GRADE STRUCTURES AT THE PLUTONIUM FINISHING PLANT

    International Nuclear Information System (INIS)

    HOPKINS, A.M.; KLOS, D.B.

    2007-01-01

    In 2002, the Richland Operations Office (RL) of the US Department of Energy (DOE), the US Environmental Protection Agency (EPA), and the Washington State Department of Ecology (Ecology) developed milestones for transitioning the Plutonium Finishing Plant (PFP) facility to a clean slab-on-grade configuration. These milestones required developing an engineering evaluation/cost analysis (EF/CA) for the facility's sub-grade structures and installations as part of a series of evaluations intended to provide for the transition of the facility to a clean slab-on-grade configuration. In addition to supporting decisions for interim actions, the analyses of sub-grade structures and installations performed through this EE/CA will contribute to the remedial investigation feasibility study(ies) and subsequently to the final records of decision for the relevant operable units responsible for site closure in the 200 West Area of the Hanford Site

  5. The development of the Waste Isolation Pilot Plant (WIPP) project's public affairs program

    International Nuclear Information System (INIS)

    Walter, L.H.

    1988-01-01

    The Waste Isolation Pilot Plant (WIPP) offers a perspective on the value of designing flexibility into a public affairs program to enable it to grow with and complement a project's evolution from construction through to operations. This paper discusses how the WIPP public affairs program progressed through several stages to its present scope. During the WIPP construction phase, the public affairs program laid a foundation for Project acceptance in the community. A speaker's bureau, a visitors program, and various community outreach and support programs emphasized the educational and socioeconomic benefits of having this controversial project in Carlsbad. Then, in this past year as the project entered a preoperational status, the public affairs program emphasis shifted to broaden the positive image that had been created locally. In this stage, the program promoted the project's positive elements with the various state agencies, government officials, and federal organizations involved in our country's radioactive waste management and transportation program. Currently, an even broader, more aggressive public affairs program is planned. During this stage public affairs will be engaged in a comprehensive institutional and outreach program, explaining and supporting WIPP's mission in each of the communities and agencies affected by the operation of the country's first geologic repository

  6. Geothermal project will predetermine future of the Kosice heating plant

    International Nuclear Information System (INIS)

    Hirman, K.

    2003-01-01

    Geoterm, a.s. manager O. Halas describes economic and technical parameters of geothermal energy source by village Durkov near Kosice. It is planned to exploitate geothermal energy source for Kosicka heating plant (TEKO). Three basic variants of technical connecting to geothermal source are developed. Temperature at TEKO entrance should reach 125 degrees, annual heating energy supply will reach 2100 TJ and source output will reach 100 MWt, while admissible deviation at all indicators reaches 10%. The first geothermal energy should by supplied to TEKO in 2007. The investments overlapping 3 billions Slovak crowns are necessary to realize whole project. According to O. Halas a credit from World Bank guaranteed by state is crucial

  7. Projecting trends in plant invasions in Europe under different scenarios of future land-use change

    Czech Academy of Sciences Publication Activity Database

    Chytrý, M.; Wild, Jan; Pyšek, Petr; Jarošík, Vojtěch; Dendoncker, N.; Reginster, I.; Pino, J.; Maskell, L. C.; Vila, M.; Pergl, Jan; Kühn, I.; Spangenberg, J.H.; Settele, J.

    2012-01-01

    Roč. 21, č. 1 (2012), s. 75-87 ISSN 1466-822X R&D Projects: GA MŠk LC06073 Institutional research plan: CEZ:AV0Z60050516 Institutional support: RVO:67985939 Keywords : plant invasions * land-use change * prediction Subject RIV: EF - Botanics Impact factor: 7.223, year: 2012

  8. CHALLENGES AND OPPORTUNITIES--INTEGRATED LIFE-CYCLE OPTIMIZATION INITIATIVES FOR THE HANFORD RIVER PROTECTION PROJECT--WASTE TREATMENT PLANT

    International Nuclear Information System (INIS)

    Auclair, K. D.

    2002-01-01

    This paper describes the ongoing integrated life-cycle optimization efforts to achieve both design flexibility and design stability for activities associated with the Waste Treatment Plant at Hanford. Design flexibility is required to support the Department of Energy Office of River Protection Balance of Mission objectives, and design stability to meet the Waste Treatment Plant construction and commissioning requirements in order to produce first glass in 2007. The Waste Treatment Plant is a large complex project that is driven by both technology and contractual requirements. It is also part of a larger overall mission, as a component of the River Protection Project, which is driven by programmatic requirements and regulatory, legal, and fiscal constraints. These issues are further complicated by the fact that both of the major contractors involved have a different contract type with DOE, and neither has a contract with the other. This combination of technical and programmatic drivers, constraints, and requirements will continue to provide challenges and opportunities for improvement and optimization. The Bechtel National, Inc. team is under contract to engineer, procure, construct, commission and test the Waste Treatment Plant on or ahead of schedule, at or under cost, and with a throughput capacity equal to or better than specified. The Department of Energy is tasked with the long term mission of waste retrieval, treatment, and disposal. While each mission is a compliment and inextricably linked to one another, they are also at opposite ends of the spectrum, in terms of expectations of one another. These mission requirements, that are seemingly in opposition to one another, pose the single largest challenge and opportunity for optimization: one of balance. While it is recognized that design maturation and optimization are the normal responsibility of any engineering firm responsible for any given project, the aspects of integrating requirements and the management

  9. NEOLITHIC PLANT USE IN THE WESTERN MEDITERRANEAN REGION: PRELIMINARY RESULTS FROM THE AGRIWESTMED PROJECT

    Directory of Open Access Journals (Sweden)

    L. Peña-Chocarro

    2013-04-01

    Full Text Available This contribution focuses on the preliminary results of the AGRIWESTMED project which focuses on the archaeobotanical analyses of early Neolithic sites in the western Mediterranean region (both in Iberia and in northern Morocco. A large number of sites has been studied producing an interesting dataset of plant remains which places the earliest examples of domesticated plants in the second half of the 6th millennium cal BC. Plant diversity is high as it is shown by the large number of species represented: hulled and naked wheats, barley, peas, fava beans, vetches, lentils and grass peas. To more crops, poppy and flax, are also part of the first agricultural crops of the area. Although agriculture seems to occupy a first place in the production of food, gathering is well represented in the Moroccan sites where a large number of species has been identified. 

  10. The iPlant Collaborative: Cyberinfrastructure for Plant Biology

    Science.gov (United States)

    Goff, Stephen A.; Vaughn, Matthew; McKay, Sheldon; Lyons, Eric; Stapleton, Ann E.; Gessler, Damian; Matasci, Naim; Wang, Liya; Hanlon, Matthew; Lenards, Andrew; Muir, Andy; Merchant, Nirav; Lowry, Sonya; Mock, Stephen; Helmke, Matthew; Kubach, Adam; Narro, Martha; Hopkins, Nicole; Micklos, David; Hilgert, Uwe; Gonzales, Michael; Jordan, Chris; Skidmore, Edwin; Dooley, Rion; Cazes, John; McLay, Robert; Lu, Zhenyuan; Pasternak, Shiran; Koesterke, Lars; Piel, William H.; Grene, Ruth; Noutsos, Christos; Gendler, Karla; Feng, Xin; Tang, Chunlao; Lent, Monica; Kim, Seung-Jin; Kvilekval, Kristian; Manjunath, B. S.; Tannen, Val; Stamatakis, Alexandros; Sanderson, Michael; Welch, Stephen M.; Cranston, Karen A.; Soltis, Pamela; Soltis, Doug; O'Meara, Brian; Ane, Cecile; Brutnell, Tom; Kleibenstein, Daniel J.; White, Jeffery W.; Leebens-Mack, James; Donoghue, Michael J.; Spalding, Edgar P.; Vision, Todd J.; Myers, Christopher R.; Lowenthal, David; Enquist, Brian J.; Boyle, Brad; Akoglu, Ali; Andrews, Greg; Ram, Sudha; Ware, Doreen; Stein, Lincoln; Stanzione, Dan

    2011-01-01

    The iPlant Collaborative (iPlant) is a United States National Science Foundation (NSF) funded project that aims to create an innovative, comprehensive, and foundational cyberinfrastructure in support of plant biology research (PSCIC, 2006). iPlant is developing cyberinfrastructure that uniquely enables scientists throughout the diverse fields that comprise plant biology to address Grand Challenges in new ways, to stimulate and facilitate cross-disciplinary research, to promote biology and computer science research interactions, and to train the next generation of scientists on the use of cyberinfrastructure in research and education. Meeting humanity's projected demands for agricultural and forest products and the expectation that natural ecosystems be managed sustainably will require synergies from the application of information technologies. The iPlant cyberinfrastructure design is based on an unprecedented period of research community input, and leverages developments in high-performance computing, data storage, and cyberinfrastructure for the physical sciences. iPlant is an open-source project with application programming interfaces that allow the community to extend the infrastructure to meet its needs. iPlant is sponsoring community-driven workshops addressing specific scientific questions via analysis tool integration and hypothesis testing. These workshops teach researchers how to add bioinformatics tools and/or datasets into the iPlant cyberinfrastructure enabling plant scientists to perform complex analyses on large datasets without the need to master the command-line or high-performance computational services. PMID:22645531

  11. The iPlant Collaborative: Cyberinfrastructure for Plant Biology.

    Science.gov (United States)

    Goff, Stephen A; Vaughn, Matthew; McKay, Sheldon; Lyons, Eric; Stapleton, Ann E; Gessler, Damian; Matasci, Naim; Wang, Liya; Hanlon, Matthew; Lenards, Andrew; Muir, Andy; Merchant, Nirav; Lowry, Sonya; Mock, Stephen; Helmke, Matthew; Kubach, Adam; Narro, Martha; Hopkins, Nicole; Micklos, David; Hilgert, Uwe; Gonzales, Michael; Jordan, Chris; Skidmore, Edwin; Dooley, Rion; Cazes, John; McLay, Robert; Lu, Zhenyuan; Pasternak, Shiran; Koesterke, Lars; Piel, William H; Grene, Ruth; Noutsos, Christos; Gendler, Karla; Feng, Xin; Tang, Chunlao; Lent, Monica; Kim, Seung-Jin; Kvilekval, Kristian; Manjunath, B S; Tannen, Val; Stamatakis, Alexandros; Sanderson, Michael; Welch, Stephen M; Cranston, Karen A; Soltis, Pamela; Soltis, Doug; O'Meara, Brian; Ane, Cecile; Brutnell, Tom; Kleibenstein, Daniel J; White, Jeffery W; Leebens-Mack, James; Donoghue, Michael J; Spalding, Edgar P; Vision, Todd J; Myers, Christopher R; Lowenthal, David; Enquist, Brian J; Boyle, Brad; Akoglu, Ali; Andrews, Greg; Ram, Sudha; Ware, Doreen; Stein, Lincoln; Stanzione, Dan

    2011-01-01

    The iPlant Collaborative (iPlant) is a United States National Science Foundation (NSF) funded project that aims to create an innovative, comprehensive, and foundational cyberinfrastructure in support of plant biology research (PSCIC, 2006). iPlant is developing cyberinfrastructure that uniquely enables scientists throughout the diverse fields that comprise plant biology to address Grand Challenges in new ways, to stimulate and facilitate cross-disciplinary research, to promote biology and computer science research interactions, and to train the next generation of scientists on the use of cyberinfrastructure in research and education. Meeting humanity's projected demands for agricultural and forest products and the expectation that natural ecosystems be managed sustainably will require synergies from the application of information technologies. The iPlant cyberinfrastructure design is based on an unprecedented period of research community input, and leverages developments in high-performance computing, data storage, and cyberinfrastructure for the physical sciences. iPlant is an open-source project with application programming interfaces that allow the community to extend the infrastructure to meet its needs. iPlant is sponsoring community-driven workshops addressing specific scientific questions via analysis tool integration and hypothesis testing. These workshops teach researchers how to add bioinformatics tools and/or datasets into the iPlant cyberinfrastructure enabling plant scientists to perform complex analyses on large datasets without the need to master the command-line or high-performance computational services.

  12. The iPlant Collaborative: Cyberinfrastructure for Plant Biology

    Directory of Open Access Journals (Sweden)

    Stephen A Goff

    2011-07-01

    Full Text Available The iPlant Collaborative (iPlant is a United States National Science Foundation (NSF funded project that aims to create an innovative, comprehensive, and foundational cyberinfrastructure in support of plant biology research (PSCIC, 2006. iPlant is developing cyberinfrastructure that uniquely enables scientists throughout the diverse fields that comprise plant biology to address Grand Challenges in new ways, to stimulate and facilitate cross-disciplinary research, to promote biology and computer science research interactions, and to train the next generation of scientists on the use of cyberinfrastructure in research and education. Meeting humanity's projected demands for agricultural and forest products and the expectation that natural ecosystems be managed sustainably will require synergies from the application of information technologies. The iPlant cyberinfrastructure design is based on an unprecedented period of research community input, and leverages developments in high-performance computing, data storage, and cyberinfrastructure for the physical sciences. iPlant is an open-source project with application programming interfaces that allow the community to extend the infrastructure to meet its needs. iPlant is sponsoring community-driven workshops addressing specific scientific questions via analysis tool integration and hypothesis testing. These workshops teach researchers how to add bioinformatics tools and/or datasets into the iPlant cyberinfrastructure enabling plant scientists to perform complex analyses on large datasets without the need to master the command-line or high-performance computational services.

  13. Economic-financial analysis of 'Angra 3 Nuclear Power Plant' project; Analise economico-financeira do empreendimento 'Usina Nuclear Angra 3'

    Energy Technology Data Exchange (ETDEWEB)

    Andrade, Ronaldo Barata de [ELETROBRAS Termonuclear S.A. (ELETRONUCLEAR), Rio de Janeiro, RJ (Brazil)]. E-mail: rbarata@eletronuclear.gov.br

    2005-07-01

    This paper presents an economic-financial evaluation of 'Angra 3 Nuclear Power Plant' project and estimates the lowest power tariff value at which power potentially made available may be commercialized and yet ensure the project a profitability level agreeable to the interests of economic agents and shareholders. According to the 'project evaluation' practice, Angra 3 power generation was considered separately from ELETRONUCLEAR's operating plants (Angra 1 and Angra 2), thus preventing result distortions bound to occur if the economic-financial variables of the new project were analyzed associated with financial commitments and commercialization conditions resulting from the project implementation process and the generated power commercialization conditions, respectively. For this evaluation different technical and economic scenarios were devised, and the theory of Capital Asset Pricing Model for Own Capital cost and that of Weighted Average Cost of Capital were used in addition to the forecast of the Statement of Results and Free Cash flow of Shareholders throughout the power plant life, which is the estimate basis for the lowest power tariff value and the Internal Return Rate of the project. The evaluation conclusion is that Angra 3 project is technically and economically feasible and competitive as compared to the new large power generation projects planned for power supply in Brazil in the next decade, mainly in the Southeast. (author)

  14. Advance: research project on aging electrical wiring in nuclear power plants; Advance: proyecto de investigacion de envejecimiento en cableado electrico en centrales nucleares

    Energy Technology Data Exchange (ETDEWEB)

    Cano, J. C.; Ruiz, S.

    2013-07-01

    As Nuclear Power Plants get older it is more important to know the real condition of low voltage, instrumentation, power and control cables. Additionally, as new plants are being built, the election of cables and the use of in-situ monitoring techniques to get reliable aging indicators, can be very useful during the plant life. The goal of this Project is to adapt, optimize and asses Condition Monitoring techniques for Nuclear Power Plants cables. These techniques, together with the appropriate acceptance criteria, would allow specialists to know the state of the cable over its entire length and estimate its residual life. In the Project, accelerated ageing is used in cables installed in European NPPs in order to evaluate different techniques to detect local and global ageing. Results are compared with accepted tests to validate its use for the estimation of cables residual life. This paper describes the main stages of the Project and some results. (Author)

  15. Novel Natural Products for Healthy Ageing from the Mediterranean Diet and Food Plants of Other Global Sources-The MediHealth Project.

    Science.gov (United States)

    Waltenberger, Birgit; Halabalaki, Maria; Schwaiger, Stefan; Adamopoulos, Nicolas; Allouche, Noureddine; Fiebich, Bernd L; Hermans, Nina; Jansen-Dürr, Pidder; Kesternich, Victor; Pieters, Luc; Schönbichler, Stefan; Skaltsounis, Alexios-Leandros; Tran, Hung; Trougakos, Ioannis P; Viljoen, Alvaro; Wolfender, Jean-Luc; Wolfrum, Christian; Xynos, Nikos; Stuppner, Hermann

    2018-05-06

    There is a rapid increase in the percentage of elderly people in Europe. Consequently, the prevalence of age-related diseases will also significantly increase. Therefore, the main goal of MediHealth, an international research project, is to introduce a novel approach for the discovery of active agents of food plants from the Mediterranean diet and other global sources that promote healthy ageing. To achieve this goal, a series of plants from the Mediterranean diet and food plants from other origins are carefully selected and subjected to in silico, cell-based, in vivo (fly and mouse models), and metabolism analyses. Advanced analytical techniques complement the bio-evaluation process for the efficient isolation and identification of the bioactive plant constituents. Furthermore, pharmacological profiling of bioactive natural products, as well as the identification and synthesis of their metabolites, is carried out. Finally, optimization studies are performed in order to proceed to the development of innovative nutraceuticals, dietary supplements or herbal medicinal products. The project is based on an exchange of researchers between nine universities and four companies from European and non-European countries, exploiting the existing complementary multidisciplinary expertise. Herein, the unique and novel approach of this interdisciplinary project is presented.

  16. Agronomic Characteristics Related to Grain Yield and Nutrient Use Efficiency for Wheat Production in China.

    Directory of Open Access Journals (Sweden)

    Limin Chuan

    Full Text Available In order to make clear the recent status and trend of wheat (Triticum aestivum L. production in China, datasets from multiple field experiments and published literature were collected to study the agronomic characteristics related to grain yield, fertilizer application and nutrient use efficiency from the year 2000 to 2011. The results showed that the mean grain yield of wheat in 2000-2011 was 5950 kg/ha, while the N, P2O5 and K2O application rates were 172, 102 and 91 kg/ha on average, respectively. The decrease in N and P2O5 and increase in K2O balanced the nutrient supply and was the main reason for yield increase. The partial factor productivity (PFP, kg grain yield produced per unit of N, P2O5 or K2O applied values of N (PFP-N, P (PFP-P and K (PFP-K were in the ranges of 29.5~39.6, 43.4~74.9 and 44.1~76.5 kg/kg, respectively. While PFP-N showed no significant changes from 2000 to 2010, both PFP-P and PFP-K showed an increased trend over this period. The mean agronomic efficiency (AE, kg grain yield increased per unit of N, P2O5 or K2O applied values of N (AEN, P (AEP and K (AEK were 9.4, 10.2 and 6.5 kg/kg, respectively. The AE values demonstrated marked inter-annual fluctuations, with the amplitude of fluctuation for AEN greater than those for AEP and AEK. The mean fertilizer recovery efficiency (RE, the fraction of nutrient uptake in aboveground plant dry matter to the nutrient of fertilizer application values of N, P and K in the aboveground biomass were 33.1%, 24.3% and 28.4%, respectively. It was also revealed that different wheat ecological regions differ greatly in wheat productivity, fertilizer application and nutrient use efficiency. In summary, it was suggested that best nutrient management practices, i.e. fertilizer recommendation applied based on soil testing or yield response, with strategies to match the nutrient input with realistic yield and demand, or provided with the 4R's nutrient management (right time, right rate, right

  17. Risk management of energy efficiency projects in the industry - sample plant for injecting pulverized coal into the blast furnaces

    OpenAIRE

    Jovanović Filip P.; Berić Ivana M.; Jovanović Petar M.; Jovanović Aca D.

    2016-01-01

    This paper analyses the applicability of well-known risk management methodologies in energy efficiency projects in the industry. The possibilities of application of the selected risk management methodology are demonstrated within the project of the plants for injecting pulverized coal into blast furnaces nos. 1 and 2, implemented by the company US STEEL SERBIA d.o.o. in Smederevo. The aim of the project was to increase energy efficiency through the reductio...

  18. Baltic nuclear projects

    International Nuclear Information System (INIS)

    Adlys, Gediminas; Adliene, Diana

    2009-01-01

    The Authors discuss the Baltic energy policy with respect to new nuclear power plants for Lithuania, Belarus and the Kaliningrad region. The construction of a new nuclear power plant in Lithuania would threaten Russian interests in the region. Therefore Lithuania is looking to Russian plans to build a new nuclear power plant in the Kaliningrad region as an attempt to subvert Lithuania's foreign partners and potential investors from participating in the Visaginas NPP project. However, the authors conclude, that the Visaginas NPP project is and must be the preferential project for the EU and NATO member states.

  19. Impact of an Educational Hands-on Project on the Antimicrobial, Antitumor and Anti-Inflammatory Properties of Plants on Portuguese Students’ Awareness, Knowledge, and Competences

    Directory of Open Access Journals (Sweden)

    Maria-Manuel Azevedo

    2015-02-01

    Full Text Available Promoting environmental and health education is crucial to allow students to make conscious decisions based on scientific criteria. The study is based on the outcomes of an Educational Project implemented with Portuguese students and consisted of several activities, exploring pre-existent Scientific Gardens at the School, aiming to investigate the antibacterial, antitumor and anti-inflammatory properties of plant extracts, with posterior incorporation in soaps and creams. A logo and a webpage were also created. The effectiveness of the project was assessed via the application of a questionnaire (pre- and post-test and observations of the participants in terms of engagement and interaction with all individuals involved in the project. This project increased the knowledge about autochthonous plants and the potential medical properties of the corresponding plant extracts and increased the awareness about the correct design of scientific experiments and the importance of the use of experimental models of disease. The students regarded their experiences as exciting and valuable and believed that the project helped to improve their understanding and increase their interest in these subjects and in science in general. This study emphasizes the importance of raising students’ awareness on the valorization of autochthonous plants and exploitation of their medicinal properties.

  20. An approach to nuclear plant design and modification support for Russian-designed plants in Eastern Europe

    International Nuclear Information System (INIS)

    Ioannidi, J.; Akins, M.J.

    2002-01-01

    The Western nuclear countries have embarked on numerous programs to improve the safety of the Russian-designed nuclear power plants. In Russian-designed plants in Eastern Europe, plant management is being asked for the first time to decide which safety projects to implement and is finding itself lacking in nuclear safety analytical tools and practices, funds, and experience with project management and project engineering skills and tools. Some of the major areas where assistance is needed are: 1) Defining plant weaknesses toward nuclear safety. 2) Evaluating and grading the importance to safety of proposed modification. 3) Project Planning and Scheduling using computer based scheduling software. 4) Project Finance Development and Management using well defined cash flow management techniques. 5) Contract Management and Change Control. 6) Interface Management. Each of these areas requires a significant amount of discussion to understand the issues and problems associated with them. However, this paper is limited to the Project Management areas. This paper encourages the use of a design engineering firm experienced in safety practices and associated management and technical skills to serve as the Owner's Engineer/Project Management Consultant for the program period for a Russian-designed plants located outside Russia. This approach would allow for the availability and transfer of knowledge of safety practices to plant personnel and owners engineers at nuclear plants outside Russia, improving their nuclear safety culture. The plant personnel would control plant modernizations and upgrades based upon a proven and well-defined process for detailed project definition, configuration change control, and project management. This offers the opportunity to enhance the long-term safety culture by developing plant personnel knowledgeable of the safety practices, plant design basis, developing a modification control process enabling them to control the design basis through future

  1. The role of insurance and risk management in new power plant projects

    International Nuclear Information System (INIS)

    Ryan, R.

    1988-01-01

    Insurance, and other risk management techniques, can be used to facilitate the financing and construction of power plant projects. This paper describes certain techniques, then it concentrates on insurance based solutions. The objective of this paper is to point out how the insurance industry can help small power producers. First, the standard insurance coverages will be reviewed. Then coverages that have been specifically designed for the alternative energy, cogeneration and small power producing industries will be explained. Some real life examples will be discussed to show how the coverages really work

  2. Methods of projecting operations and maintenance costs for nuclear power plants

    International Nuclear Information System (INIS)

    1995-01-01

    Operations and maintenance cost (OMC) had increased its relative importance to the total generation cost for future nuclear power stations, according to the latest update of the OECD Nuclear Energy Agency (NEA) study on Projected Costs of Generating Electricity (EGC studies). OMC is some 20 to 30% of total generation cost for future nuclear power stations in most NEA member countries. However, nuclear OMC that countries projected in the latest EGC study are spread over a wide range, from 5 to 16 US mills/kWh. In order to understand better the reasons for this wide diversity in nuclear OMC projections, the NEA set up an Expert Group. The focus of this study was on projected OMC that were reported in the past EGC studies, but the Group studied actual OMC experienced from existing units, because knowledge or experience concerning actual OMC certainly influences the choice of assumptions or calculation procedure for estimating OMC for future plants. Cost informations from 14 NEA countries have been analysed on the basis of a standardized framework of detailed components of OMC costs. The rationale for different OMC cost projections reported in previous NEA studies on generation cost is discussed and suggestions are made for future studies on both generation cost and OMC cost. Despite the methodological approach and the reduced extent of differences when excluding exceptional figures, it was not possible fully to clarify the origins and to understand the remaining differences in OMC figures. Several countries which have a long and a good experience of operating nuclear units did not provide sufficient detailed data or did not provide any quantitative data at all. (J.S.). 14 refs., 5 figs., 19 tabs., 4 annexes

  3. Cesium Ion Exchange Program at the Hanford River Protection Project Waste Treatment Plant

    International Nuclear Information System (INIS)

    CHARLES, NASH

    2004-01-01

    The River Protection Project - Hanford Tank Waste Treatment and Immobilization Plant will use cesium ion exchange to remove 137Cs from Low Activity Waste down to 0.3 Ci/m3 in the Immobilized LAW, ILAW product. The project baseline for cesium ion exchange is the elutable SuperLig, R, 644, SL-644, resin registered trademark of IBC Advanced Technologies, Inc., American Fork, UT or the Department of Energy approved equivalent. SL-644 is solely available through IBC Advanced Technologies. To provide an alternative to this sole-source resin supply, the RPP--WTP initiated a three-stage process for selection and qualification of an alternative ion exchange resin for cesium removal in the RPPWTP. It was recommended that resorcinol formaldehyde RF be pursued as a potential alternative to SL-644

  4. IAEA TC Project 'Strengthening safety and reliability of fuel and materials in nuclear power plants'

    International Nuclear Information System (INIS)

    Makihara, Y.

    2008-01-01

    The Regional TC Project in Europe RER9076 'Strengthening Safety and Reliability of Fuel and Materials in Nuclear Power Plants' was launched in 2003 as a four-year project and was subsequently extended in 2006 to run through 2008. The purpose of the Project is to support the Central and Eastern European countries with the necessary tools to fulfill their own fuel and material licensing needs. The main objective will be to provide quality data on fuel and materials irradiated in power reactors and in dedicated experiments carried out in material test reactors (MTRs). Within the framework of the Project, ten tasks were implemented. These included experiments performed at the test facilities in the region, training courses and workshops related to fuel safety. While several tasks are expected to be completed by the end of RER9076, some remain. It would be desirable to initiate a new RER Project from the next TC cycle (2009-2011) in order to take over RER9076 and to implement new tasks required for enhancing fuel safety in the region. (author)

  5. The Sydvaerme project: District heating from the Barsebeck nuclear power plant

    International Nuclear Information System (INIS)

    Josefsson, L.

    1977-01-01

    The paper presents a summary report of a study on district heating from Barsebeck Nuclear Power Plant in Sweden, prepared cooperatively by the cities of Malmoe, Lund, Helsingborg, Landskrona and the electric power company Sydkraft. A future number 3 generating set at the Barsebeck nuclear power station could be designed for combined production of heat and electric power. The generating set could be completed after 1983, and could then supply about 65% of total district heating requirements. The first stage of the investigation includes a proposal for a technically feasible solution, sufficiently detailed to permit both technical and economic evaluation of the project. (author)

  6. Economic Analysis of Cikaso Mini Hydro Power Plant as a CDM Project for Increasing IRR

    Directory of Open Access Journals (Sweden)

    Irhan Febijanto

    2013-12-01

    Full Text Available Renewable energy fueled power generations are few developed by private sector in Indonesia. High-cost investment and low electricity selling price to PT PLN as a single buyer is main barriers for private sector to involve in the development of renewable energy fueled power generations. In this project, the economic feasibility of Mini Hydro Power Plant of Cikaso with capacity of 5.3 MW, located at Sukabumi Regency, West Java province was assessed. This project utilized revenue generated from carbon market to increase the economic feasibility. Procedure to register the project to United Nation for Climate Change Convention (UNFCCC as a Clean Development Mechanism project was explained in detail. Approved Consolidation Methodology (ACM 0002 Version 12.3.0 was used to calculate grid emission factor in Jawa-Bali-Madura the grid electricity system. It was calculated that the grid emission factor is 0.833 (t-CO2/MWh, and the carbon emission reduction generated for this project is 21,982 ton/year. From the analysis result, it can be proven that the additional revenue from carbon credit could increase the project IRR from 10.28% to 13.52%.

  7. Managing the development of plant subsystems for a large international project

    International Nuclear Information System (INIS)

    Gurd, D.

    2012-01-01

    ITER is an international collaborative project under development by nations representing over one half of the world's population. Major components will be supplied by 'Domestic Agencies' representing the various participating countries. While the supervisory control system, known as CODAC, will be developed 'in fund' by the International Organization at the project site in the south of France, the EPICS and PLC-based plant control subsystems are to be developed and tested locally, where the subsystems themselves are being built. This is similar to the model used for the development of the Spallation Neutron Source, which was a US national collaboration. However the much more complex constraints of an international collaboration preclude the use of many specifics of the SNS collaboration approach. Moreover, procedures for final system integration and commissioning at ITER are not yet well defined. This paper will outline the particular issues either inherent in an international collaboration or specific to ITER, and will suggest approaches to mitigate those problems with the goal of assuring a successful and timely integration and commissioning phase. (author)

  8. Kvanefjeld uranium project

    International Nuclear Information System (INIS)

    Erlendsson, G.; Jensen, J.; Kofoed, S.; Paulsen, J.L.

    1983-11-01

    The draft uranium project ''Kvanefjeld'' describes the establishment and operation of an industrial plant for exploiting the uranium deposit at Kvanefjeld. The draft project is part of the overall pre-feasibility project and is based on its results. The draft project includes two alternative locations for the processing plant and the tailings deposit plant. The ore reserve is estimated at 56 million tons with an average content of 365 PPM. The mine will be established as an open pit, with a slope angle of 55deg. Conventional techniques are used in drilling, blasting and handling the ore. Waste rock with no uranium content will be disposed of in two ponds near the mine. The waste rock volume is estimated at 80 million tons. A processing plant for extracting uranium from the ore will be established. The technical layout of the plant is based on the extraction experiments performed at Risoe from 1981-83. Yearly capacity is 4.2 million tons of ore. Electrical energy will be supplied from a hydroelectric station to be built at Johan Dahl Land. Thermal energy (steam/heat) will be supplied from a coal-fired district heating plant to be built in connection with the processing plant. Expected power consumption is estimated at 225 GWh/year. Heat consumption is of the same order. In the third year the plant is expected to operate at full capacity. Operating costs will be Dkr. 121/ton of ore from years 1 through 7. Consumption of chemicals will be reduced from the 7th year, and operating costs will consequently drop to Dkr. 115/ton of ore. Calculations show that industrial extraction of the uranium deposit in Kvanefjeld is economically advantageous. In addition, the economy of the project is expected to improve by extracting byproducts from the ore. (EG)

  9. Program change management during nuclear power plant decommissioning

    International Nuclear Information System (INIS)

    Bushart, Sean; Kim, Karen; Naughton, Michael

    2011-01-01

    Decommissioning a nuclear power plant is a complex project. The project involves the coordination of several different departments and the management of changing plant conditions, programs, and regulations. As certain project Milestones are met, the evolution of such plant programs and regulations can help optimize project execution and cost. This paper will provide information about these Milestones and the plant departments and programs that change throughout a decommissioning project. The initial challenge in the decommissioning of a nuclear plant is the development of a definitive plan for such a complex project. EPRI has published several reports related to decommissioning planning. These earlier reports provided general guidance in formulating a Decommissioning Plan. This Change Management paper will draw from the experience gained in the last decade in decommissioning of nuclear plants. The paper discusses decommissioning in terms of a sequence of major Milestones. The plant programs, associated plans and actions, and staffing are discussed based upon experiences from the following power reactor facilities: Maine Yankee Atomic Power Plant, Yankee Nuclear Power Station, and the Haddam Neck Plant. Significant lessons learned from other sites are also discussed as appropriate. Planning is a crucial ingredient of successful decommissioning projects. The development of a definitive Decommissioning Plan can result in considerable project savings. The decommissioning plants in the U.S. have planned and executed their projects using different strategies based on their unique plant circumstances. However, experience has shown that similar project milestones and actions applied through all of these projects. This allows each plant to learn from the experiences of the preceding projects. As the plant transitions from an operating plant through decommissioning, the reduction and termination of defunct programs and regulations can help optimize all facets of

  10. Research and Development Technology Development Roadmaps for the Next Generation Nuclear Plant Project

    Energy Technology Data Exchange (ETDEWEB)

    Ian McKirdy

    2011-07-01

    The U.S. Department of Energy (DOE) has selected the high temperature gas-cooled reactor (HTGR) design for the Next Generation Nuclear Plant (NGNP) Project. The NGNP will demonstrate the use of nuclear power for process heat, hydrogen and electricity production. The reactor will be graphite moderated with helium as the primary coolant and may be either prismatic or pebble-bed. Although, final design features have not yet been determined. Research and Development (R&D) activities are proceeding on those known plant systems to mature the technology, codify the materials for specific applications, and demonstrate the component and system viability in NGNP relevant and integrated environments. Collectively these R&D activities serve to reduce the project risk and enhance the probability of on-budget, on-schedule completion and NRC licensing. As the design progresses, in more detail, toward final design and approval for construction, selected components, which have not been used in a similar application, in a relevant environment nor integrated with other components and systems, must be tested to demonstrate viability at reduced scales and simulations prior to full scale operation. This report and its R&D TDRMs present the path forward and its significance in assuring technical readiness to perform the desired function by: Choreographing the integration between design and R&D activities; and proving selected design components in relevant applications.

  11. Environmental management project of the Patache power plant project and associated transmission line; Gestion ambiental proyecto central termoelectrica Patache y linea de transmision asociada

    Energy Technology Data Exchange (ETDEWEB)

    Carreno Paredes, Cristian [Compania Electrica Tapaca (CELTA, S. A.), (Chile)

    1997-12-31

    This report makes a brief description of the services developed by INGENDESA of the projects executed in the area of engineering as well as in the area of environmental matters. In a second instance a relatively detailed presentation is made of the most important background of the Chilean project: {sup E}nvironmental Management of the Patache Power Plant and the Associated Transmission Line-Compania Electrica Tarapaca (CELTA, S.A.) Region I{sup .} The justification for the construction of the power plant and the environmental problems associated with the same are described [Espanol] En el presente informe se hace una breve presentacion de los servicios desarrollados por INGENDESA, de los proyectos elaborados tanto en el area de la ingenieria como en la tematica ambiental. En segunda instancia, se hace una presentacion relativamente detallada de los antecedentes mas importantes del proyecto chileno {sup G}estion Ambiental Central Patache y Linea de Transmision Asociada - Compania Electrica Tarapaca (CELTA, S.A.) I Region{sup .} Se describe la justificacion de la construccion de esta central termoelectrica y los problemas ambientales asociados a la misma

  12. Environmental management project of the Patache power plant project and associated transmission line; Gestion ambiental proyecto central termoelectrica Patache y linea de transmision asociada

    Energy Technology Data Exchange (ETDEWEB)

    Carreno Paredes, Cristian [Compania Electrica Tapaca (CELTA, S. A.), (Chile)

    1996-12-31

    This report makes a brief description of the services developed by INGENDESA of the projects executed in the area of engineering as well as in the area of environmental matters. In a second instance a relatively detailed presentation is made of the most important background of the Chilean project: {sup E}nvironmental Management of the Patache Power Plant and the Associated Transmission Line-Compania Electrica Tarapaca (CELTA, S.A.) Region I{sup .} The justification for the construction of the power plant and the environmental problems associated with the same are described [Espanol] En el presente informe se hace una breve presentacion de los servicios desarrollados por INGENDESA, de los proyectos elaborados tanto en el area de la ingenieria como en la tematica ambiental. En segunda instancia, se hace una presentacion relativamente detallada de los antecedentes mas importantes del proyecto chileno {sup G}estion Ambiental Central Patache y Linea de Transmision Asociada - Compania Electrica Tarapaca (CELTA, S.A.) I Region{sup .} Se describe la justificacion de la construccion de esta central termoelectrica y los problemas ambientales asociados a la misma

  13. Pulsed-field profile diversities of Salmonella Enteritidis, S. Infantis, and S. Corvallis in Japan.

    Science.gov (United States)

    Murakami, Koichi; Noda, Tamie; Onozuka, Daisuke; Kimura, Hirokazu; Fujimoto, Shuji

    2017-08-16

    The diversity of pulsed-field profiles (PFPs) within non-typhoidal Salmonella subtypes influences epidemiological analyses of Salmonella outbreaks. Therefore, determining the PFP diversity of each Salmonella serovar is important when evaluating current circulating strains. This study examined the PFP diversity of three important public health Salmonella enterica subspecies enterica serovars, S . Enteritidis (n=177), S . Infantis (n=205), and S . Corvallis (n=90), using pulsed-field gel electrophoresis. Isolates were collected from several sources, primarily from chicken-derived samples, in the Kyushu-Okinawa region of Japan between 1989 and 2005. S . Enteritidis isolates displayed 51 distinct PFPs (E-PFPs), with 92 (52.0%) and 32 (18.1%) isolates displaying types E-PFP1 and E-PFP10, respectively. The 205 S . Infantis isolates showed 54 distinct PFPs (I-PFPs), with 87 (42.4%) and 36 (17.6%) isolates being I-PFP4 and I-PFP2, respectively. I-PFP18 was the dominant I-PFP of layer chicken isolates across a 5-year period. Fourteen distinct S . Corvallis PFPs were detected. Simpson's index results for the genetic diversities of S . Enteritidis, S . Infantis, and S . Corvallis isolates were 0.70, 0.79, and 0.78, respectively. None of the E-PFPs or I-PFPs of layer chicken isolates overlapped with those of broiler chicken isolates, and the dominant clonal lines existed for >10 years. In conclusion, limited PFP diversities were detected amongst S . Enteritidis, S. Infantis, and S. Corvallis isolates of primarily chicken-derived origins in the Kyushu-Okinawa region of Japan. Therefore, it is important to take into account these limitations in PFP diversities in epidemiological analyses of Salmonella outbreaks.

  14. Investment appraisal of heat and power plants within an emissions trading scheme. Final Report of the INVIS Project

    International Nuclear Information System (INIS)

    Laurikka, H.; Pirilae, P.

    2005-04-01

    The opportunity cost for carbon dioxide (CO 2 ) emissions has become a new factor influencing investments in heat and power production capacity globally, and in particular in countries with a greenhouse gas emissions trading system, such as the European Union Emissions Trading Scheme (EU ETS). There is a considerable power capacity investment need in the coming decades in Finland, in Europe and globally. As the economic lifetime of an investment in heat and power capacity typically ranges from 20-40 years, 'carbon finance' and the EU ETS therefore introduce a considerable and fundamental price risk to the investment problem. In Europe, the price risk is present in all investments and divestments of power production licences or capacity, be it a green-field plant, a retrofit of an existing plant or an acquisition. The objective of the INVIS research project was to extend the knowledge on strategic implications of emissions trading in investments into heat and power generation. This report gives an overview on the main findings of the project. The focus of INVIS project was on (1) quantitative investment appraisal and (2) methods rather than tools or parameter values. Particular attention in the INVIS project was paid to the incorporation of emissions trading in new methods of investment appraisal, which aim at taking into account the value of real options, rights to postpone or revise decisions. The EU ETS modifies the quantitative investment appraisal of heat and power plants directly through the emission allowance price and the number of free allowances and indirectly through impacts on output prices, input prices, taxation, and subsidies. From the risk perspective, the most problematic impact seems to be the regulatory uncertainty in the number of free allowances, which can turn out to be a barrier for investment in fossil-fuel-fired thermal power plants - even combined-cycle gas turbines. The emission allowance price is a stochastic variable, which implies it is

  15. Comparative risk analysis for the Rocky Flats Plant integrated project planning

    International Nuclear Information System (INIS)

    Jones, M.E.; Shain, D.I.

    1994-01-01

    The Rocky Flats Plant is developing, with active stakeholder participation, a comprehensive planning strategy that will support transition of the Rocky Flats Plant from a nuclear weapons production facility to site cleanup and final disposition. Consideration of the interrelated nature of sitewide problems, such as material movement and disposition, facility and land use endstates, costs, relative risks to workers and the public, and waste disposition are all needed. Comparative Risk Analysis employs both incremental risk and cumulative risk evaluations to compare risks from postulated options or endstates and is an analytical tool for the Rocky Flats Plant Integrated Project Planning which can assist a decision-maker in evaluating relative risks among proposed remediation activity. However, risks from all of the remediation activities, decontamination and decommissioning activities, and normal ongoing operations are imposed upon the Rocky Flats workers, the surrounding public, and the environment. Comparative Risk Analysis will provide risk information, both human health and ecological, to aid in reducing unnecessary resource and monetary expenditures by focusing these resources on the largest risks first. Comparative Risk Analysis has been developed to aggregate various incremental risk estimates to develop a site cumulative risk estimate. The Comparative Risk Analysis methodology Group, consisting of community stakeholders, was established. Early stakeholder involvement in the risk analysis methodology development provides an opportunity for stakeholders to influence the risk information delivered to a decision-maker. This paper discusses development of the Comparative Risk Analysis methodology, stakeholder participation and lessons learned from these challenges

  16. Intelligent and interactive computer image of a nuclear power plant: The ImagIn project

    International Nuclear Information System (INIS)

    Haubensack, D.; Malvache, P.; Valleix, P.

    1998-01-01

    The ImagIn project consists in a method and a set of computer tools apt to bring perceptible and assessable improvements in the operational safety of a nuclear plant. Its aim is to design an information system that would maintain a highly detailed computerized representation of a nuclear plant in its initial state and throughout its in-service life. It is not a tool to drive or help driving the nuclear plant, but a tool that manages concurrent operations that modify the plant configuration in a very general was (maintenance for example). The configuration of the plant, as well as rules and constraints about it, are described in a object-oriented knowledge database, which is built using a generic ImagIn meta-model based on the semantical network theory. An inference engine works on this database and is connected to reality through interfaces to operators and captors on the installation; it verifies constantly in real-time the consistency of the database according to its inner rules, and reports eventual problems to concerned operators. A special effort is made on interfaces to provide natural and intuitive tools (using virtual reality, natural language, voice recognition and synthesis). A laboratory application on a fictive but realistic installation already exists and is used to simulate various tests and scenarii. A real application is being constructed on Siloe, an experimental reactor of the CEA. (author)

  17. Considerations on safety against seismic excitations in the project of reactor auxiliary building and control building in nuclear power plants

    International Nuclear Information System (INIS)

    Santos, S.H.C.; Castro Monteiro, I. de

    1986-01-01

    The seismic requests to be considered in the project of main buildings of a nuclear power plant are discussed. The models for global seismic analysis of nuclear power plant structures, as well as models for global strength distribution are presented. The models for analysing reactor auxiliary building and control building, which together with the reactor building and turbine building form the main energy generation complex in a nuclear power plant, are described. (M.C.K.) [pt

  18. Estimativas de repetibilidade de alguns caracteres de produção em mangueira Estimate of repeatability of some traits of production in mango tree

    Directory of Open Access Journals (Sweden)

    João Gomes da Costa

    2003-04-01

    Full Text Available O presente trabalho objetivou estimar o coeficiente de repetibilidade para os caracteres número total de frutos por planta (NTF, produção de frutos por planta (PFP e peso médio de fruto (PMF, e determinar o número mínimo de avaliações que devem ser feitas para uma predição acurada do valor real dos indivíduos. As estimativas de repetibilidade foram realizadas pelo método dos componentes principais a partir da matriz de correlação. Os coeficientes de repetibilidade estimados foram de: 0,51; 0,53 e 0,81, associados aos coeficientes de determinação (R² de 80,44%, 81,60% e 94,41% respectivamente, para NTF, PFP e PMF. A estimativa do coeficiente de repetibilidade da característica peso médio do fruto demonstrou alta regularidade na superioridade dos indivíduos de um ciclo para outro, sendo necessários três ciclos de avaliações para predizer o valor real dos indivíduos com nível de certeza acima de 90%. Apesar de as características número de frutos por planta e produção de frutos por planta terem influência ambiental, quatro medições permitem obter coeficientes de determinação próximos de 80%.The objective of this papers was to estimate the repeatability coefficient of the total number of fruit per plant (TNF, production of fruit per plant (PFP and average fruit weight (AWF, while the number of measures that should be performed for an efficient selection of the genotypes under evaluation were determined. Analysis were made using principal components. The estimates of the repeatability were of: 0.51; 0.53 and 0.81, associated to the determination coefficients (R² of 80.44%, 81.60% and 94.41, respectively, for TNF, PFP and WMF. The estimate of the repeatability coefficient of the WMF demonstrated high regularity at the superiority of the individuals from one cycle to another, so the evaluation of three cycles was enough to predict the individual real value with R² above 90%. In spite of the traits TNF and PFP have

  19. Waste Treatment & Immobilization Plant Project

    Data.gov (United States)

    Federal Laboratory Consortium — In southeastern Washington State, Bechtel National, Inc. is designing, constructing and commissioning the world's largest radioactive waste treatment plant for the...

  20. Energy analysis and projecting of power plants

    International Nuclear Information System (INIS)

    Jirlow, K.

    1975-01-01

    Energy analysis aims at a better explanation of energy flow and energy exchange at different production processes. In this report the energy budget is analysed for separate nuclear power plants and for expanding systems of power plants. A mathematical model is developed for linear and exponential expanding of nuclear power. The profitableness for nuclear power plants in Sweden is considered to be good. (K.K.)

  1. Plant automation-application to SBWR project

    International Nuclear Information System (INIS)

    Rodriguez Rodriguez, C.

    1995-01-01

    In accordance with the requirements set out in the URD (Utility Requirements Document) issued by the EPRI (Electrical Power Research Institute), the design of new reactors, whether evolutionary or passive, shall taken into account the systematic automation of functions relating to normal plant operation. The objectives established are to: =2E Simplify operator-performed tasks =2E Reduce the risk of operator-error by considering human factors in the allocation of tasks =2E Improve man-machine reliability =2E Increase the availability of the plant In previous designs, automation has only been considered from the point of view of compliance with regulatory requirements for safety-related systems, or in isolated cases, as a method of protecting the investment where there is a risk of damage to main equipment. The use of digital technology has prevented the systematic pursuit of such objectives in the design of automated systems for processes associated with normal plant operation (startup, load follow, normal shutdown, etc) from being excessively complex and therefore costly to undertake. This paper describes how the automation of the aforementioned normal plant operation activities has been approached in General Electric's SBWR (Simplified Boiling Water Reactor) design. (Author)

  2. Basic survey project for Joint Implementation, etc. Feasibility study on the modernization of cement plant in Republic of Kazakhstan

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2000-03-01

    For the purpose of reducing greenhouse effect gas emissions, a project was studied for the modernization of a cement plant in the Republic of Kazakhstan. In the Semipalatinsk cement plant, an old wet type kiln is being used which is much consuming in energy and low in productivity. By replacing this kiln with the NSP dry type kiln, expected were the enhancement of efficiency, energy conservation, and reduction in greenhouse effect gas emissions. Further, it was planned that four lines for raw material production and four lines for clinker combustion are tied together to make it one, and the ball mill is replaced with the low power-consuming type roller mill. By this project, the energy consumption will decrease by 96,000 t/y in coal and 2,095,500 kWh/y in electric power, which is a decrease of approximately 39% from the energy consumption before the project being worked out. Moreover, as to greenhouse effect gases, there are no changes in CO2 gas emissions from limestone, but CO2 gas emissions from coal decrease by 216.960 t/y, which is a decrease of 28.5% from that before the project being worked out. (NEDO)

  3. Modernization projects in Santa Maria e Garona

    International Nuclear Information System (INIS)

    Marcos, R.; Alutiz, J. I.; Garcia Sanchez, M.

    2011-01-01

    This article shows a vision of the Santa Maria de Garona power Plant modernization guidelines and it also presents the most significant projects deployed in the last decade at the power plant grouped in mechanics projects, electrical projects, instrumentations projects and IT projects. At the same time three projects are explained in more detail: the change of one of the main transformers, the evolution from paper recorders to paperless video graphic recorders and the new plant data information system. (Author)

  4. Data management for the Clinch River Breeder Reactor Plant Project by use of document status and hold systems

    International Nuclear Information System (INIS)

    Hunt, C.S.; Beck, A.E.; Akhtar, M.S.

    1982-01-01

    This paper describes the development, framework, and scope of the Document Status System and the Document Hold System for the Clinch River Breeder Reactor Plant Project. It shows how data are generated at five locations and transmitted to a central computer for processing and storage. The resulting computerized data bank provides reports needed to perform day-to-day management and engineering planning. Those reports also partially satisfy the requirements of the Project's Quality Assurance Program

  5. Improving niche projections of plant species under climate change: Silene acaulis on the British Isles as a case study

    Science.gov (United States)

    Ferrarini, Alessandro; Alsafran, Mohammed H. S. A.; Dai, Junhu; Alatalo, Juha M.

    2018-04-01

    Empirical works to assist in choosing climatically relevant variables in the attempt to predict climate change impacts on plant species are limited. Further uncertainties arise in choice of an appropriate niche model. In this study we devised and tested a sharp methodological framework, based on stringent variable ranking and filtering and flexible model selection, to minimize uncertainty in both niche modelling and successive projection of plant species distributions. We used our approach to develop an accurate, parsimonious model of Silene acaulis (L.) presence/absence on the British Isles and to project its presence/absence under climate change. The approach suggests the importance of (a) defining a reduced set of climate variables, actually relevant to species presence/absence, from an extensive list of climate predictors, and (b) considering climate extremes instead of, or together with, climate averages in projections of plant species presence/absence under future climate scenarios. Our methodological approach reduced the number of relevant climate predictors by 95.23% (from 84 to only 4), while simultaneously achieving high cross-validated accuracy (97.84%) confirming enhanced model performance. Projections produced under different climate scenarios suggest that S. acaulis will likely face climate-driven fast decline in suitable areas on the British Isles, and that upward and northward shifts to occupy new climatically suitable areas are improbable in the future. Our results also imply that conservation measures for S. acaulis based upon assisted colonization are unlikely to succeed on the British Isles due to the absence of climatically suitable habitat, so different conservation actions (seed banks and/or botanical gardens) are needed.

  6. Development of antibiotic resistance and up-regulation of the antimutator gene pfpI in mutator Pseudomonas aeruginosa due to inactivation of two DNA oxidative repair genes (mutY, mutM)

    DEFF Research Database (Denmark)

    Mandsberg, Lotte Frigaard; Macia, Maria D.; Bergmann, Kirsten R.

    2011-01-01

    showed only a fivefold increase, whereas the single mutant PAOMMgm (mutM) showed a nonsignificant increase in MR compared with PAO1 and the single mutants. Mutations in the regulator nfxB leading to hyperexpression of MexCD-OprJ efflux pump were found as the mechanism of resistance to ciprofloxacin....... In this study, we constructed a double mutant in mutY and mutM (PAOMY-Mgm) and characterized the phenotype and the gene expression profile using microarray and RT-PCR. PAOMY-Mgm presented 28-fold increases in MR compared with wild-type reference strain PAO1. In comparison, the PAOMYgm (mutY) single mutant...... in the double mutant. A better fitness of the mutator compared with PAO1 was found in growth competition experiments in the presence of ciprofloxacin at concentrations just below minimal inhibitory concentration. Up-regulation of the antimutator gene pfpI, that has been shown to provide protection to oxidative...

  7. Achievement report for fiscal 1981 on Sunshine Program-assisted project. Survey of Australian industrial capability and construction capability relative to Australian brown coal liquefaction plant construction project; 1981 nendo Goshu kattan ekika plant no kensetsu ni kakawaru kogyoryoku, kensetsu kojiryoku ni kansuru chosa seika hokokusho

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1982-03-01

    The industrial capability and construction capability of Australia are surveyed in relation with the project of constructing a brown coal liquefaction plant there. Australian heavy industry is conspicuously advanced in the field of mining machinery involving coal, iron ore, and other mineral resources. On the other hand, in the fields of general-purpose machinery for plants and of civil engineering machinery, it is behind other countries in terms of technology and cost because of the small market. When an industrial project is implemented in Australia, consulting firms, engineering contractors, etc., operate independently from each other, and the project is propelled forward under a perfect specialization system. Labor-related problems in the civil engineering and construction industry are the recruitment of laborers which is difficult and the delay in and suspension of construction due to labor disputes that take place very frequently. In Victoria State where a brown coal liquefaction plant is under construction, the availability of laborers specializing in construction is rather higher than in other states, and there is no important problem in this respect. One cannot be too prudent in Victoria State, however, since it includes a region which is the most notorious in Australia in terms of labor-management dispute. (NEDO)

  8. The decommissioning of WWER type nuclear power plants. Final report on an IAEA regional technical co-operation project

    International Nuclear Information System (INIS)

    2000-01-01

    Numerous WWER-440 nuclear power plants are in operation in central and eastern Europe and a small number have already been shut down. In addition to reactors already shut down, many other reactors will reach the end of their design lifetime in a few years and become candidates for decommissioning. It is unfortunate that little consideration was devoted to decommissioning of WWER-440 reactors at the plant design and construction stage, and little emphasis was placed on planning for decommissioning. It is within this context that the IAEA launched a regional technical co-operation project in 1994 with the aim of providing guidance on planning and management of decommissioning for WWERs. The project, which had a duration of four years (1995-1998), included the organization of workshops and scientific visits to countries having WWERs and other countries where active decommissioning projects were under way. Eventually, participants suggested the consolidation of expert guidance and collective opinions into a TECDOC, which was drafted by both designated participants from project recipient countries and invited experts. The TECDOC has the aim of serving as a stimulus for all concerned parties in central and eastern European countries to initiate concrete decommissioning planning, including assessment of existing and required resources for the eventual implementation of decommissioning plans. In addition, the regional technical co-operation project has managed to bring together in this TECDOC a number of good practices that could be useful in WWER-440 decommissioning

  9. Gait-related intrinsic risk factors for patellofemoral pain in novice recreational runners.

    Science.gov (United States)

    Thijs, Y; De Clercq, D; Roosen, P; Witvrouw, E

    2008-06-01

    To determine prospectively gait-related intrinsic risk factors for patellofemoral pain (PFP) in a population of novice recreational runners. Prospective cohort study. 102 novice recreational runners (89 women) with no history of knee or lower leg complaints. The standing foot posture of the subjects was examined and plantar pressure measurements during running were collected. The subjects then participated in a 10-week "start to run" programme. During this period all sports injuries were registered by a sports medicine physician. The relationship between the standing foot posture and PFP was investigated and gait-related intrinsic risk factors for PFP were determined. The 17 runners who developed PFP exerted a significantly higher vertical peak force underneath the lateral heel and metatarsals 2 and 3. Logistic regression analysis showed that a significantly higher vertical peak force underneath the second metatarsal and shorter time to the vertical peak force underneath the lateral heel were predictors for PFP. No significant evidence was found for an association between an excessively pronated or supinated foot posture and the development of PFP. The findings suggest that an excessive impact shock during heel strike and at the propulsion phase of running may contribute to an increased risk of developing PFP. The hypothesis that persons at risk for PFP show an altered static foot posture in comparison with non-afflicted persons is not supported by the results of this study.

  10. Financial feasibility analysis on small medium reactor nuclear power plant (SMR NPP) project in Indonesia under uncertainty

    International Nuclear Information System (INIS)

    Nuryanti; Suparman; Mochamad Nasrullah; Elok Satiti Amitayani; Wiku Lulus Widodo

    2015-01-01

    NPP SMR is one alternative to overcome the Outside Java Bali region's dependence on diesel power plant. One crucial issue in the NPP project (including SMR) would be financing, associated with the capital-intensive nature of the project. In addition, the SMR NPP project also be vulnerable in occurrence of some uncertainties. Therefore, this study aimed to analyze the financial feasibility of SMR NPP project by accommodating the possibility of the uncertainties. The methodology used is probabilistic analysis which was performed by Monte Carlo technique. This technique simulates the relationship between the uncertainty variables with financial feasibility indicators. The results showed that in probabilistic approach, SMR NPP project is considered feasible on the 'most probable value' of electricity selling price of 15 cents/kWh, indicated by positive average value of NPV (US$ 135,324,004) and the average value of both of IRRs are bigger than MARR (IRR project = 10.65 %, IRR Equity = 14.29 %, while MARR = 10 %). The probability of rejection of the SMR project was about 20 %. The three main variables that are most influential in the project were: selling price of electricity, investment cost and inflation rate. (author)

  11. The projected effect on insects, vertebrates, and plants of limiting global warming to 1.5°C rather than 2°C.

    Science.gov (United States)

    Warren, R; Price, J; Graham, E; Forstenhaeusler, N; VanDerWal, J

    2018-05-18

    In the Paris Agreement on Climate Change, the United Nations is pursuing efforts to limit global warming to 1.5°C, whereas earlier aspirations focused on a 2°C limit. With current pledges, corresponding to ~3.2°C warming, climatically determined geographic range losses of >50% are projected in ~49% of insects, 44% of plants, and 26% of vertebrates. At 2°C, this falls to 18% of insects, 16% of plants, and 8% of vertebrates and at 1.5°C, to 6% of insects, 8% of plants, and 4% of vertebrates. When warming is limited to 1.5°C as compared with 2°C, numbers of species projected to lose >50% of their range are reduced by ~66% in insects and by ~50% in plants and vertebrates. Copyright © 2018 The Authors, some rights reserved; exclusive licensee American Association for the Advancement of Science. No claim to original U.S. Government Works.

  12. Canberra Alpha Sentry Installation Functional Design Criteria (FDC)

    International Nuclear Information System (INIS)

    WHITE, W.F.

    1999-01-01

    This document provides the functional design criteria for the installation of the Canberra Alpha Sentry System at selected locations within the Plutonium Finishing Plant (PFP). The equipment being installed is identified by part number in Section 3 and the locations are given in Section 5. The design, procurement and installation are assigned to Fluor Federal Services

  13. Material stabilization characterization management plan

    International Nuclear Information System (INIS)

    GIBSON, M.W.

    1999-01-01

    This document presents overall direction for characterization needs during stabilization of SNM at the Plutonium Finishing Plant (PFP). Technical issues for needed data and equipment are identified. Information on material categories and links to vulnerabilities are given. Comparison data on the material categories is discussed to assist in assessing the relative risks and desired processing priority

  14. A parametric study on the use of passive fire protection in FPSO topside module

    Directory of Open Access Journals (Sweden)

    Martin Friebe

    2014-12-01

    Full Text Available Fire is a continuous threat to FPSO topside modules as large amounts of oil and gas are passing through the modules. As a conventional measure to mitigate structural failure under fire, passive fire protection (PFP coatings are widely used on main structural members. However, an excessive use of PFP coatings can cause considerable cost for material purchase, installation, inspection and maintenance. Long installation time can be a risk since the work should be done nearly at the last fabrication stage. Thus, the minimal use of PFP can be beneficial to the reduction of construction cost and the avoidance of schedule delay. This paper presents a few case studies on how different applications of PFP have influence on collapse time of a FPSO module structure. A series of heat analysis and thermal elasto-plastic FE analysis are performed for different PFP coatings and the resultant collapse time and the amount of PFP coatings are compared with each other.

  15. Project management skills for nuclear power plants

    International Nuclear Information System (INIS)

    Bhatikar, R.J.

    2002-01-01

    Full text: The E and C Division of L and T has executed several power projects in India and abroad and thus possesses the requisite wherewithal to execute nuclear power projects on a fast track basis. To achieve this L and T has set up a separate Strategic Business Unit (SBU) to have a focused attention to the nuclear power industry in the country. All the four important and necessary hallmarks for successful implementation of any project namely (i) engineering capabilities, (ii) sophisticated project management tools, (iii) ability to mobilize resources, and (iv) skilled personnel to execute the project have been adequately addressed. These could be realized either by establishing fruitful collaborations with other specialist Companies and/or creating powerful and multitasking software tools for effective implementation. The execution of nuclear power projects on a fast track basis could be implemented by following the EPC route and by minimizing the number of packages. Details of this scheme for project implementation will be highlighted during the talk

  16. The CIDEM project for integrating availability, operating experience and maintenance in the design of future nuclear power plants

    International Nuclear Information System (INIS)

    Degrave, C.; Martin-Onraet, M.

    1998-01-01

    To minimize the kWh cost of future nuclear plants EDF has decided to implement the CIDEM project (French acronym for Design Integrating Availability, Operating Experience and Maintenance), an analytic and systematic process for studying new projects. The first CIDEM application is centered on the future French nuclear unit construction program, known as the REP 2000 Program but the approach could be applied to other Reactor type. The CIDEM studies at the beginning, were oriented to the issues strongly impacting the availability. They have concerned: planned outages, forced outages and preventive maintenance. The studies were carried out by a team grouping engineers from the 3 EDF's Divisions (Engineering-Generation-Research), and working together in a Concurrent Engineering-Mode. This team works in close collaboration with the vendors and the German Utilities involved in the REP 2000 EPR program. The implementation of the CIDEM process constitutes for EDF a new approach to the study of the new Nuclear Power Plant projects. The studies conducted in the availability field have already highlighted a number of critical points and have made it possible to establish a series of specifications for the REP 2000/EPR project. The integration in the design process of Preventive Maintenance and Logistic Support studies will allow a better control of the maintenance cost. The competitiveness of nuclear energy greatly depends on the success of such an approach. (author)

  17. Port Menier thermal power plant: Pre-project report

    International Nuclear Information System (INIS)

    1992-02-01

    Port Menier, the town on Anticosti Island in the St Lawrence River estuary, is supplied with electricity from a diesel power plant having a firm capacity of 1,080 kW. Since 1987, power demand has increased at an average annual rate of 5.7%, raising the winter peak demand from 670 kW to 987 kW. The power plant is located in the center of town and is obsolete, presenting a number of architectural, environmental, and operational deficiencies. It is proposed to construct a new power plant having an initial firm capacity of 1,490 kW and storage capacity for 75,000 liters of fuel. The plant site will have an area of ca 6,265 m 2 to allow for an eventual expansion to over 3,000 kW capacity, sufficient for satisfying forecast demand over the next 20 years. Estimated cost of the new plant is ca $9.5 million. The old plant will be decommissioned and the new plant will be built at a site outside of town. The natural and human environments characteristic of the Port Menier area are detailed and the two selected sites for the new plant are described and compared. A site in the industrial zone of Port-Menier is favored. The environmental impacts of the new plant are analyzed and mitigation measures during the preconstruction, construction, and operational phases are proposed. Local economic impacts are estimated at around $990,000. 20 refs., 12 figs., 12 tabs

  18. Balance of plant improvements for future reactor projects

    International Nuclear Information System (INIS)

    Hollingshaus, H.

    1987-01-01

    Many studies have shown that improvements in portions of the plant other than the reactor systems can yield large cost savings during the design, construction, and operation of future reactor power plants. This portion is defined as the Balance of Plant which includes virtually everything except the equipment furnished by the Nuclear Steam Supply System manufacturer. It normally includes the erection of the entire plant including the NSSS. Cost of BOP equipment, engineering and construction work is therefore most of the cost of the plant. Improvements in the BOP have been identified that will substantially reduce nuclear plant cost and construction time while at the same time increasing availability and operability and improving safety. Improvements achieved through standardizatoin, simplification, three-dimensional (3D) computer-aided design, modular construction, innovative construction techniques, and applications for Artificial Intelligence Systems are described. (author)

  19. Pulsed-field profile diversities of Salmonella Enteritidis, S. Infantis, and S. Corvallis in Japan

    Directory of Open Access Journals (Sweden)

    Koichi Murakami

    2017-10-01

    Full Text Available The diversity of pulsed-field profiles (PFPs within non-typhoidal Salmonella subtypes influences epidemiological analyses of Salmonella outbreaks. Therefore, determining the PFP diversity of each Salmonella serovar is important when evaluating current circulating strains. This study examined the PFP diversity of three important public health Salmonella enterica subspecies enterica serovars, S. Enteritidis (n=177, S. Infantis (n=205, and S. Corvallis (n=90, using pulsed-field gel electrophoresis. Isolates were collected from several sources, primarily from chicken-derived samples, in the Kyushu-Okinawa region of Japan between 1989 and 2005. S. Enteritidis isolates displayed 51 distinct PFPs (E-PFPs, with 92 (52.0% and 32 (18.1% isolates displaying types EPFP1 and E-PFP10, respectively. The 205 S. Infantis isolates showed 54 distinct PFPs (I-PFPs, with 87 (42.4% and 36 (17.6% isolates being I-PFP4 and I-PFP2, respectively. I-PFP18 was the dominant I-PFP of layer chicken isolates across a 5-year period. Fourteen distinct S. Corvallis PFPs were detected. Simpson’s index results for the genetic diversities of S. Enteritidis, S. Infantis, and S. Corvallis isolates were 0.70, 0.79, and 0.78, respectively. None of the EPFPs or I-PFPs of layer chicken isolates overlapped with those of broiler chicken isolates, and the dominant clonal lines existed for >10 years. In conclusion, limited PFP diversities were detected amongst S. Enteritidis, S. Infantis, and S. Corvallis isolates of primarily chicken-derived origins in the Kyushu-Okinawa region of Japan. Therefore, it is important to take into account these limitations in PFP diversities in epidemiological analyses of Salmonella outbreaks.

  20. International outage coding system for nuclear power plants. Results of a co-ordinated research project

    International Nuclear Information System (INIS)

    2004-05-01

    The experience obtained in each individual plant constitutes the most relevant source of information for improving its performance. However, experience of the level of the utility, country and worldwide is also extremely valuable, because there are limitations to what can be learned from in-house experience. But learning from the experience of others is admittedly difficult, if the information is not harmonized. Therefore, such systems should be standardized and applicable to all types of reactors satisfying the needs of the broad set of nuclear power plant operators worldwide and allowing experience to be shared internationally. To cope with the considerable amount of information gathered from nuclear power plants worldwide, it is necessary to codify the information facilitating the identification of causes of outages, systems or component failures. Therefore, the IAEA established a sponsored Co-ordinated Research Project (CRP) on the International Outage Coding System to develop a general, internationally applicable system of coding nuclear power plant outages, providing worldwide nuclear utilities with a standardized tool for reporting outage information. This TECDOC summarizes the results of this CRP and provides information for transformation of the historical outage data into the new coding system, taking into consideration the existing systems for coding nuclear power plant events (WANO, IAEA-IRS and IAEA PRIS) but avoiding duplication of efforts to the maximum possible extent

  1. WSSRAP chemical plant geotechnical investigations for the Weldon Spring Site Remedial Action Project, Weldon Spring, Missouri

    International Nuclear Information System (INIS)

    1990-12-01

    This document has been prepared for the United states Department of Energy (DOE) Weldon Spring Site Remedial Action Project (WSSRAP) by the Project Management Contractor (PMC), which consists of MK-Ferguson Company (MKF) and Morrison Knudsen Corporation Environmental Services Group (MKES) with Jacobs Engineering Group (JEG) as MKF's predesignated subcontractor. This report presents the results of site geotechnical investigations conducted by the PMC in the vicinity of the Weldon Spring chemical plant and raffinate pits (WSCP/RP) and in potential on-site and off-site clayey material borrow sources. The WSCP/RP is the proposed disposal cell (DC) site. 39 refs., 24 figs., 12 tabs

  2. Fuel Gas Demonstration Plant Program: Small-Scale Industrial Project. Environmental assessment statement

    Energy Technology Data Exchange (ETDEWEB)

    1979-02-01

    Solid, liquid, and gaseous by-products and wastes are generated during coal storage and processing, gasification, and gas cleanup. Recovery systems have been designed to collect and utilize by-products. Wastes will be placed in storage areas designed to prevent release of the materials to the environment. The coal gasification plant along with the solid waste disposal area will occupy approximately 115 acres. To prevent, to the fullest extent possible, degradation of groundwater and surface water resources, the coal stockpile, landfill, collection pond, settling basin, and drainage ditches will be constructed to prevent the seepage of potential contaminants into groundwater or the drainage of runoff into surface waters. Cooling water is the primary water requirement of the project. None of the water utilized in the gasification plant will be released into the area surface water system, but will be either recycled or directed into the settling basin. The gasification facility has the potential of emitting a broad spectrum of pollutants into the atmosphere. However, effective emission control procedures such as off-gas recycling, hydrogen sulfide removal, particulate removal, and flaring will be applied to minimize the plant's emissions. The necessity of monitoring the more exotic pollutants such as acid gases, trace elements, metal carbonyls, and a multitude of organic compounds, will be determined as the gasification facility becomes more of a reality and the latest literature and research developments can be surveyed to evaluate the emission rates, biological significance, and monitoring techniques for these pollutants.

  3. Can we talk? Communications management for the Waste Isolation Pilot Plant, a complex nuclear waste management project

    International Nuclear Information System (INIS)

    Goldstein, S.A.; Pullen, G.M.; Brewer, D.R.

    1995-01-01

    Sandia Nuclear Waste Management Program is pursuing for DOE an option for permanently disposing radioactive waste in deep geologic repositories. Included in the Program are the Waste Isolation Pilot Plant (WIPP) Project for US defense program mixed waste the Yucca Mountain Project (YMP) for spent power reactor fuel and vitrified high-level waste, projects for other waste types, and development efforts in environmental decision support technologies. WIPP and YMP are in the public arena, of a controversial nature, and provide significant management challenges. Both projects have large project teams, multiple organization participants, large budgets, long durations, are very complex, have a high degree of programmatic risk, and operate in an extremely regulated environment requiring legal defensibility. For environmental projects like these to succeed, SNL's Program is utilizing nearly all areas in PMI's Project Management Body of Knowledge (PMBOK) to manage along multiple project dimensions such as the physical sciences (e.g., geophysics and geochemistry; performance assessment; decision analysis) management sciences (controlling the triple constraint of performance, cost and schedule), and social sciences (belief systems; public participation; institutional politics). This discussion focuses primarily on communication challenges active on WIPP. How is the WIPP team meeting the challenges of managing communications?'' and ''How are you approaching similar challenges?'' will be questions for a dialog with the audience

  4. SRT project: tele-robotics maintenance of nuclear power plants

    International Nuclear Information System (INIS)

    Gomez-Santamaria, J.; Calleja, J.M.; Carmena, P.; Avello, A.; Rubio, Y.A.

    2001-01-01

    The main aim of the SRT project was to develop a family of robots to help in the operation of nuclear power plants. Four robotic systems were developed and this paper focuses on three of them: ANAES -a steam leak detector through noise analysis-, MALIBA -a master-slave tele-operation system with force feedback- and ROBICEN -a compact pneumatic wall climbing robot-. ANAES (the Spanish acronym of spectrum analysis) consists of a set of sensor heads attached to a computer. Each head has two microphones and a video camera installed on it, and a DC motor that rotates the head. The heads are shielded with lead and boron steel, especially near the video camera. The noise generated by the plant is recorded every day at the same time and the software compares the recorded noise with the mean values of past records. The system can discern whether the noise has remarkably changed and, through phase analysis of the sound recorded by both microphones, identifies the direction of arrival (DOA) of the new noise, probably a steam leak. Using several heads, the new noise source can be identified. The video camera can be used to ease the location of the steam leaks. The stationariness of the measured noise has been tested in C.N. Cofrentes -a Spanish BWR-6 reactor-. A finished system with six heads has recently been installed in the MSR (moisture separator reheater) of the same plant. MALIBA is a master-slave tele-operated system with force feedback. It consists of two robots: a Stewart platform used as master robot and an open chain robot used as slave. The slave robot follows faithfully the movements of the master, and the master robot can reflect a force proportional to the force exerted by the slave on the environment. Three tools have been developed for the slave robot: a robot hand that includes a small video camera, a pneumatic drill and a rectifier. The results obtained have shown its effectiveness for the designed operations. ROBICEN is a lightweight pneumatic robot

  5. SRT project: tele-robotics maintenance of nuclear power plants

    Energy Technology Data Exchange (ETDEWEB)

    Gomez-Santamaria, J. [Iberdrola SA, Madrid (Spain); Calleja, J.M.; Carmena, P. [Endesa, Madrid (Spain); Avello, A.; Rubio, Y.A. [CEIT-Centro de Estudias e Investigaciones Tecnicas de Guipuzcoa, San Sebastian (Spain)

    2001-07-01

    The main aim of the SRT project was to develop a family of robots to help in the operation of nuclear power plants. Four robotic systems were developed and this paper focuses on three of them: ANAES -a steam leak detector through noise analysis-, MALIBA -a master-slave tele-operation system with force feedback- and ROBICEN -a compact pneumatic wall climbing robot-. ANAES (the Spanish acronym of spectrum analysis) consists of a set of sensor heads attached to a computer. Each head has two microphones and a video camera installed on it, and a DC motor that rotates the head. The heads are shielded with lead and boron steel, especially near the video camera. The noise generated by the plant is recorded every day at the same time and the software compares the recorded noise with the mean values of past records. The system can discern whether the noise has remarkably changed and, through phase analysis of the sound recorded by both microphones, identifies the direction of arrival (DOA) of the new noise, probably a steam leak. Using several heads, the new noise source can be identified. The video camera can be used to ease the location of the steam leaks. The stationariness of the measured noise has been tested in C.N. Cofrentes -a Spanish BWR-6 reactor-. A finished system with six heads has recently been installed in the MSR (moisture separator reheater) of the same plant. MALIBA is a master-slave tele-operated system with force feedback. It consists of two robots: a Stewart platform used as master robot and an open chain robot used as slave. The slave robot follows faithfully the movements of the master, and the master robot can reflect a force proportional to the force exerted by the slave on the environment. Three tools have been developed for the slave robot: a robot hand that includes a small video camera, a pneumatic drill and a rectifier. The results obtained have shown its effectiveness for the designed operations. ROBICEN is a lightweight pneumatic robot

  6. SAFETY STUDIES TO MEASURE EXOTHERMIC REACTIONS OF SPENT PLUTONIUM DECONTAMINATION CHEMICALS USING WET AND DRY DECONTAMINATION METHODS

    International Nuclear Information System (INIS)

    HOPKINS, A.M.; JACKSON, G.W.; MINETTE, M.; EWALT, J.; COOPER, T.; SCOTT, P.; JONES, S.; SCHEELEY, R.

    2005-01-01

    The Plutonium Finishing Plant (PFP) at the Hanford site in Eastern Washington is currently being decommissioned by Fluor Hanford. Chemicals being considered for dccontamination of gloveboxes in PFP include cerium (IV) nitrate in a nitric acid solution, and proprietary commercial solutions that include acids and sequestering agents. Aggressive chemicals are commonly used to remove transuranic contaminants from process equipment to allow disposal of the equipment as low level waste. Fluor's decontamination procedure involves application of chemical solutions as a spray on the contaminated surfaces, followed by a wipe-down with rags. Alternatively, a process of applying oxidizing Ce IV ions contained in a gel matrix and vacuuming a dry gel material is being evaluated. These processes effectively transfer the transuranic materials to rags or a gel matrix which is then packaged as TRU waste and disposed

  7. The Ranger project - a case study

    International Nuclear Information System (INIS)

    Young, R.I.

    1983-01-01

    Ranger Uranium Mines Pty. Ltd. operates an open pit mine and ore treatment plant in the Northern Territory designed to produce 3000 tonne/yr of U 3 O 8 from 3500 tonne/day of mill feed. The construction of the project was completed in 1981. Wright-Davy were the project managers and designers of the $270 million ore treatment plant and associated infrastructure. Details of project cost, staffing, project design and project systems are given

  8. Trojan technical specification verification project

    International Nuclear Information System (INIS)

    Bates, L.; Rickenback, M.

    1991-01-01

    The Trojan Technical Specification Verification (TTSV) project at the Trojan plant of Portland General Electric Company was motivated by the recognition that many numbers in the Trojan technical specifications (TTS) potentially lacked the consideration of instrument- and/or process-related errors. The plant setpoints were known to consider such errors, but many of the values associated with the limiting conditions for operation (LCO) did not. In addition, the existing plant instrument error analyses were based on industry values that do not reflect the Trojan plant-specific experience. The purpose of this project is to ensure that the Trojan plant setpoint and LCO values include plant-specific instrument error

  9. Inquiry Based Projects Using Student Ozone Measurements and the Status of Using Plants as Bio-Indicators

    Science.gov (United States)

    Ladd, I. H.; Fishman, J.; Pippin, M.; Sachs, S.; Skelly, J.; Chappelka, A.; Neufeld, H.; Burkey, K.

    2006-05-01

    Students around the world work cooperatively with their teachers and the scientific research community measuring local surface ozone levels using a hand-held optical scanner and ozone sensitive chemical strips. Through the GLOBE (Global Learning and Observations to Benefit the Environment) Program, students measuring local ozone levels are connected with the chemistry of the air they breathe and how human activity impacts air quality. Educational tools have been developed and correlated with the National Science and Mathematics Standards to facilitate integrating the study of surface ozone with core curriculum. Ozone air pollution has been identified as the major pollutant causing foliar injury to plants when they are exposed to concentrations of surface ozone. The inclusion of native and agricultural plants with measuring surface ozone provides an Earth system approach to understanding surface ozone. An implementation guide for investigating ozone induced foliar injury has been developed and field tested. The guide, Using Sensitive Plants as Bio-Indicators of Ozone Pollution, provides: the background information and protocol for implementing an "Ozone Garden" with native and agricultural plants; and, a unique opportunity to involve students in a project that will develop and increase their awareness of surface ozone air pollution and its impact on plants.

  10. Hanford Waste Simulants Created to Support the Research and Development on the River Protection Project - Waste Treatment Plant

    Energy Technology Data Exchange (ETDEWEB)

    Eibling, R.E.

    2001-07-26

    The development of nonradioactive waste simulants to support the River Protection Project - Waste Treatment Plant bench and pilot-scale testing is crucial to the design of the facility. The report documents the simulants development to support the SRTC programs and the strategies used to produce the simulants.

  11. The waste isolation pilot plant project: a changing paradigm

    International Nuclear Information System (INIS)

    Sheppard, L.E.; McFadden, M.H.

    1996-01-01

    The Waste Isolation Pilot Plant (WIPP) is a US Department of Energy (DOE) repository that has been developed to demonstrate the safe and permanent isolation of transuranic radioactive wastes in a deep geologic site. It is located in 650 m below the surface in a bedded salt formation, and is designed to hold approximately 175,500 cubic meters of waste. Compliance with the regulations has become the principal focus for the Project. The scientific baseline is an important and integral part of the CCA, as it provides the foundation for conducting total system performance assessment calculations for comparison with applicable standards. The activities required to support the scientific baseline are being pursued in parallel to minimize the time required to collect, analyze, interpret and fully incorporate the results into the CCA. The DOE has shifted its approach to demonstrating compliance with the applicable regulations from a paradigm of a series of broad investigations to a new paradigm of highly focused activities conducted in parallel. The success of this approach will be assessed by the EPA when the application is critically reviewed

  12. Patellofemoral pain in athletes: clinical perspectives

    Science.gov (United States)

    Halabchi, Farzin; Abolhasani, Maryam; Mirshahi, Maryam; Alizadeh, Zahra

    2017-01-01

    Patellofemoral pain (PFP) is a very common problem in athletes who participate in jumping, cutting and pivoting sports. Several risk factors may play a part in the pathogenesis of PFP. Overuse, trauma and intrinsic risk factors are particularly important among athletes. Physical examination has a key role in PFP diagnosis. Furthermore, common risk factors should be investigated, such as hip muscle dysfunction, poor core muscle endurance, muscular tightness, excessive foot pronation and patellar malalignment. Imaging is seldom needed in special cases. Many possible interventions are recommended for PFP management. Due to the multifactorial nature of PFP, the clinical approach should be individualized, and the contribution of different factors should be considered and managed accordingly. In most cases, activity modification and rehabilitation should be tried before any surgical interventions. PMID:29070955

  13. Rates of change in climatic niches in plant and animal populations are much slower than projected climate change

    Science.gov (United States)

    Jezkova, Tereza

    2016-01-01

    Climate change may soon threaten much of global biodiversity. A critical question is: can species undergo niche shifts of sufficient speed and magnitude to persist within their current geographic ranges? Here, we analyse niche shifts among populations within 56 plant and animal species using time-calibrated trees from phylogeographic studies. Across 266 phylogeographic groups analysed, rates of niche change were much slower than rates of projected climate change (mean difference > 200 000-fold for temperature variables). Furthermore, the absolute niche divergence among populations was typically lower than the magnitude of projected climate change over the next approximately 55 years for relevant variables, suggesting the amount of change needed to persist may often be too great, even if these niche shifts were instantaneous. Rates were broadly similar between plants and animals, but especially rapid in some arthropods, birds and mammals. Rates for temperature variables were lower at lower latitudes, further suggesting that tropical species may be especially vulnerable to climate change. PMID:27881748

  14. Facility Effluent Monitoring Plan for the Plutonium Finishing Plant (PFP); FINAL

    International Nuclear Information System (INIS)

    FRAZIER, T.P.

    1999-01-01

    A facility effluent monitoring plan is required by the U. S. Department of Energy in DOE Order 5400.1 for any operations that involve hazardous materials and radioactive substances that could impact employee or public safety or the environment. This facility effluent monitoring plan assesses effluent monitoring systems and evaluates whether these systems are adequate to ensure the public health and safety as specified in applicable federal, state, and local requirements. To ensure the long-range integrity of the effluent monitoring systems, an update to this facility effluent monitoring plan is required whenever a new process or operation introduces new hazardous materials or significant radioactive materials. This document is reviewed annually even if there are no operational changes, and is updated, at a minimum, every 3 years

  15. Validity of Combining History Elements and Physical Examination Tests to Diagnose Patellofemoral Pain.

    Science.gov (United States)

    Décary, Simon; Frémont, Pierre; Pelletier, Bruno; Fallaha, Michel; Belzile, Sylvain; Martel-Pelletier, Johanne; Pelletier, Jean-Pierre; Feldman, Debbie; Sylvestre, Marie-Pierre; Vendittoli, Pascal-André; Desmeules, François

    2018-04-01

    To assess the validity of diagnostic clusters combining history elements and physical examination tests to diagnose or exclude patellofemoral pain (PFP). Prospective diagnostic study. Orthopedic outpatient clinics, family medicine clinics, and community-dwelling. Consecutive patients (N=279) consulting one of the participating orthopedic surgeons (n=3) or sport medicine physicians (n=2) for any knee complaint. Not applicable. History elements and physical examination tests were obtained by a trained physiotherapist blinded to the reference standard: a composite diagnosis including both physical examination tests and imaging results interpretation performed by an expert physician. Penalized logistic regression (least absolute shrinkage and selection operator) was used to identify history elements and physical examination tests associated with the diagnosis of PFP, and recursive partitioning was used to develop diagnostic clusters. Diagnostic accuracy measures including sensitivity, specificity, positive and negative predictive values, and positive and negative likelihood ratios with associated 95% confidence intervals (CIs) were calculated. Two hundred seventy-nine participants were evaluated, and 75 had a diagnosis of PFP (26.9%). Different combinations of history elements and physical examination tests including the age of participants, knee pain location, difficulty descending stairs, patellar facet palpation, and passive knee extension range of motion were associated with a diagnosis of PFP and used in clusters to accurately discriminate between individuals with PFP and individuals without PFP. Two diagnostic clusters developed to confirm the presence of PFP yielded a positive likelihood ratio of 8.7 (95% CI, 5.2-14.6) and 3 clusters to exclude PFP yielded a negative likelihood ratio of .12 (95% CI, .06-.27). Diagnostic clusters combining common history elements and physical examination tests that can accurately diagnose or exclude PFP compared to various knee

  16. Environmental Regulation of Plant Gene Expression: An Rt-qPCR Laboratory Project for an Upper-Level Undergraduate Biochemistry or Molecular Biology Course

    Science.gov (United States)

    Eickelberg, Garrett J.; Fisher, Alison J.

    2013-01-01

    We present a novel laboratory project employing "real-time" RT-qPCR to measure the effect of environment on the expression of the "FLOWERING LOCUS C" gene, a key regulator of floral timing in "Arabidopsis thaliana" plants. The project requires four 3-hr laboratory sessions and is aimed at upper-level undergraduate…

  17. PlantCV v2: Image analysis software for high-throughput plant phenotyping

    Directory of Open Access Journals (Sweden)

    Malia A. Gehan

    2017-12-01

    Full Text Available Systems for collecting image data in conjunction with computer vision techniques are a powerful tool for increasing the temporal resolution at which plant phenotypes can be measured non-destructively. Computational tools that are flexible and extendable are needed to address the diversity of plant phenotyping problems. We previously described the Plant Computer Vision (PlantCV software package, which is an image processing toolkit for plant phenotyping analysis. The goal of the PlantCV project is to develop a set of modular, reusable, and repurposable tools for plant image analysis that are open-source and community-developed. Here we present the details and rationale for major developments in the second major release of PlantCV. In addition to overall improvements in the organization of the PlantCV project, new functionality includes a set of new image processing and normalization tools, support for analyzing images that include multiple plants, leaf segmentation, landmark identification tools for morphometrics, and modules for machine learning.

  18. Soil-plant water status and wine quality: the case study of Aglianico wine (the ZOViSA project)

    Science.gov (United States)

    Bonfante, Antonello; Manna, Piero; Albrizio, Rossella; Basile, Angelo; Agrillo, Antonietta; De Mascellis, Roberto; Caputo, Pellegrina; Delle Cave, Aniello; Gambuti, Angelita; Giorio, Pasquale; Guida, Gianpiero; Minieri, Luciana; Moio, Luigi; Orefice, Nadia; Terribile, Fabio

    2014-05-01

    The terroir analysis, aiming to achieve a better use of environmental features with respect to plant requirement and wine production, needs to be strongly rooted on hydropedology. In fact, the relations between wine quality and soil moisture regime during the cropping season is well established. The ZOViSA Project (Viticultural zoning at farm scale) tests a new physically oriented approach to terroir analysis based on the relations between the soil-plant water status and wine quality. The project is conducted in southern Italy in the farm Quintodecimo of Mirabella Eclano (AV) located in the Campania region, devoted to quality Aglianico red wine production (DOC). The soil spatial distribution of study area (about 3 ha) was recognized by classical soil survey and geophysics scan by EM38DD; then the soil-plant water status was monitored for three years in two experimental plots from two different soils (Cambisol and Calcisol). Daily climate variables (temperature, solar radiation, rainfall, wind), daily soil water variables (through TDR probes and tensiometers), crop development (biometric and physiological parameters), and grape must and wine quality were monitored. The agro-hydrological model SWAP was calibrated and applied in the two experimental plots to estimate soil-plant water status in different crop phenological stages. The effects of crop water status on crop response and wine quality was evaluated in two different pedo-systems, comparing the crop water stress index with both: crop physiological measurements (leaf gas exchange, leaf water potential, chlorophyll content, LAI measurement), grape bunches measurements (berry weight, sugar content, titratable acidity, etc.) and wine quality (aromatic response). Finally a "spatial application" of the model was carried out and different terroirs defined.

  19. Compost plant of Medellin - An interesting project

    International Nuclear Information System (INIS)

    Bedoya V, Julian; Arango M, Carlos Andres

    1998-01-01

    Empresas varias de Medellin acquired a composting plant (solid waste treatment plant) in the beginning of the 70's. This plant, manufactured in Spain, using French technology, started operation in 1972. It was bought from the machinery Pascua Hermanos y Compania ltda. Spanish consortium. The total investment cost by 1971 was of about $ 20' 000, 000 Colombian pesos. The composting plant was designed as a partial solution (180t/day) to the disposal of about 400 t/days of solid waste disposal in Medellin city. The operation steps of the plant were: collection cars into one of the three hoppers dumped solid waste. Then recyclable material was picked up by hand in a flat conveyor. Hammer mills, where non-crushable material was separated and collected in a reject conveyor, crushed organic material. Afterwards, organic material was screened and was taken by another conveyor into a rotary trommel where manure and organic wastes from the cattle market Plaza de Ferias, and from the municipal slaughterhouse, was planned to be added (this operation was never implemented). The organic portion was separated magnetically from ferrous materials and then conducted to the fermenting aisle, where it stayed for nine days; oxidation was increased by aeration by Archimedes screws. Product coming from the fermenting aisle was discharged in a screening system to classify the compost by granulometry. Again strange elements where taken away from the compost using collision with a ballistic separator. Finally, weight and size, and using belt conveyors and a rotary distributor classified compost, it was disposed in a open field, where it would stay for about thirty days. Social, technical, marketing, economic and administrative problems made difficult the operation of the plant that was closed down in 1985 and fully dismantled in 1988

  20. Human factors in nuclear power plants

    International Nuclear Information System (INIS)

    Pack, R.W.

    1978-01-01

    The Electric Power Research Institute has started research in human factors in nuclear power plants. One project, completed in March 1977, reviewed human factors problems in operating power plants and produced a report evaluating those problems. A second project developed computer programs for evaluating operator performance on training simulators. A third project is developing and evaluating control-room design approaches. A fourth project is reviewing human factors problems associated with power-plant maintainability and instrumentation and control technician activities. Human factors engineering is an interdisciplinary specialty concerned with influencing the design of equipment systems, facilities, and operational environments to promote safe, efficient, and reliable operator performance. The Electric Power Research Institute (EPRI) has undertaken four projects studying the application of human factors engineering principles to nuclear power plants. (author)

  1. Programme and activities on nuclear desalination in Morocco. Pre-project study on demonstration plant for seawater desalination using nuclear heating reactor in Morocco

    International Nuclear Information System (INIS)

    Righi, M.

    1998-01-01

    The first part of this paper gives the general information on the pre-project study of a demonstration plant for seawater desalination using a heating reactor being assessed jointly by Morocco and China. The progress of the pre-project study is elaborated in the second part. (author)

  2. Results of dilution studies with waste from tank 241-AN-104

    International Nuclear Information System (INIS)

    HERTING, D.L.

    1999-01-01

    This report documents the completion of the B and W Hanford Company functional and Safety Review Board reviews and the Fluor Daniel Hanford review for the Plutonium Finishing Plant (PFP) Final Safety Analysis Report (FSAR), HNF-SD-CP-SAR-021, Revision 1. The reviews for the FSAR were conducted during the period from December 9, 1998 to January 14, 1999

  3. Integrated Nuclear Recycle Plant

    International Nuclear Information System (INIS)

    Patodi, Anuj; Parashar, Abhishek; Samadhiya, Akshay K.; Ray, Saheli; Dey, Mitun; Singh, K.K.

    2017-01-01

    Nuclear Recycle Board (NRB), Tarapur proposes to set up an 'Integrated Nuclear Recycle Plant' at Tarapur. This will be located in the premises of BARC facilities. The project location is at coastal town of Tarapur, 130 Km north of Mumbai. Project area cover of INRP is around 80 hectares. The plant will be designed to process spent fuel received from Pressurized Heavy Water Reactors (PHWRs). This is the first large scale integrated plant of the country. INRP will process spent fuel obtained from indigenous nuclear power plants and perform left over nuclear waste disposal

  4. Department of Energy Operation Quality Assurance Program for the Waste Isolation Pilot Plant (WIPP) Project (Carlsbad, New Mexico)

    International Nuclear Information System (INIS)

    1987-12-01

    The purpose of this plan is to describe the Quality Assurance (QA)reverse arrow Program to be established and implemented by the US Department of Energy (DOE) Waste Isolation Pilot Plant (WIPP) Project Office (WPO) and by the Project Participants: the Scientific Advisor (Sandia National Laboratory) and the Management and Operating Contractor (Westinghouse Electric Corporation). This plan addresses the Pre-Operational and Operational phases of the WIPP Project not addressed under the construction phase. This plan also requires the QA Programs for DOE and Project Participants to be structured so as to comply with this plan and ANSI-ASME NQA-1. The prime responsibility for Operational Quality Assurance rests with the DOE WIPP Project Office and is implemented through the combined efforts of the Scientific Advisor and the Management and Operating Contractor. Overviews of selected operational and testing activities will be are conducted in accordance with prescribed requirements and that adequate documentation of these activities is maintained. 4 figs

  5. Proximal mechanics during stair ascent are more discriminate of females with patellofemoral pain than distal mechanics.

    Science.gov (United States)

    de Oliveira Silva, Danilo; Barton, Christian John; Pazzinatto, Marcella Ferraz; Briani, Ronaldo Valdir; de Azevedo, Fábio Mícolis

    2016-06-01

    Several hypotheses have been proposed to explain the pathomechanisms underlying patellofemoral pain (PFP). Concurrent evaluation of lower limb mechanics in the same PFP population is needed to determine which may be more important to target during rehabilitation. This study aimed to investigate possible differences in rearfoot eversion, hip adduction, and knee flexion during stair ascent; the relationship between these variables; and the discriminatory capability of each in identifying females with PFP. Thirty-six females with PFP and 31 asymptomatic controls underwent three-dimensional kinematic analyses during stair ascent. Between-group comparisons were made for peak rearfoot eversion, hip adduction, and knee flexion. Pearson's correlation coefficients were calculated to evaluate relationships among these parameters. Receiver operating characteristic curves were applied to identify the discriminatory capability of each. Females with PFP ascended stairs with reduced peak knee flexion, greater peak hip adduction and peak rearfoot eversion. Peak hip adduction (>10.6°; sensitivity=67%, specificity=77%) discriminated females with PFP more effectively than rearfoot eversion (>5.0°; sensitivity=58%, specificity=67%). Reduced peak hip adduction was found to be associated with reduced peak knee flexion (r=0.54, p=0.002) in females with PFP. These findings indicate that proximal, local, and distal kinematics should be considered in PFP management, but proximally targeted interventions may be most important. The relationship of reduced knee flexion with reduced hip adduction also indicates a possible compensatory strategy to reduce patellofemoral joint stress, and this may need to be addressed during rehabilitation. Copyright © 2016 Elsevier Ltd. All rights reserved.

  6. Tidd PFBC demonstration project

    Energy Technology Data Exchange (ETDEWEB)

    Marrocco, M. [American Electric Power, Columbus, OH (United States)

    1997-12-31

    The Tidd project was one of the first joint government-industry ventures to be approved by the US Department of Energy (DOE) in its Clean Coal Technology Program. In March 1987, DOE signed an agreement with the Ohio Power Company, a subsidiary of American Electric Power, to refurbish the then-idle Tidd plant on the banks of the Ohio River with advanced pressurized fluidized bed technology. Testing ended after 49 months of operation, 100 individual tests, and the generation of more than 500,000 megawatt-hours of electricity. The demonstration plant has met its objectives. The project showed that more than 95 percent of sulfur dioxide pollutants could be removed inside the advanced boiler using the advanced combustion technology, giving future power plants an attractive alternative to expensive, add-on scrubber technology. In addition to its sulfur removal effectiveness, the plant`s sustained periods of steady-state operation boosted its availability significantly above design projections, heightening confidence that pressurized fluidized bed technology will be a reliable, baseload technology for future power plants. The technology also controlled the release of nitrogen oxides to levels well below the allowable limits set by federal air quality standards. It also produced a dry waste product that is much easier to handle than wastes from conventional power plants and will likely have commercial value when produced by future power plants.

  7. Study on modular construction management in AP1000 nuclear plant project

    International Nuclear Information System (INIS)

    Fang Xiaopeng; Shen Wenrong; Sun Kebin; Wei Zhong

    2010-01-01

    The construction of AP1000 Nuclear Power Plant (NPP) has commenced in China. The AP1000 NPP features a passive design concept and modular construction technology. Based on the management of the construction of current AP1000 NNP, this paper describes the effects on Nuclear Island (NI) construction project management resulting from modular construction technology, as well as new construction techniques and methods. This paper puts forward new requirements for construction schedule management of the nuclear island construction at different levels. The AP1000 NI construction logic features the parallel construction of civil and structural erection as the main approach, with the integrated schedule of module fabrication, assembly and installation as support. The structural modules of AP1000 project are prefabricated in shop, delivered to site as sub-modules and assembled to integrated structural module. The assembled module is transported to the construction site, hoisted and finally set in NI. This paper illustrates how to ensure the construction quality of structural modules by analyzing the interface process and key links in the quality control program, and introduces how to ensure the safety of heavy structural components during various construction phases by evaluating and analyzing the construction safety process. This paper also makes an analysis of the safe environment for the assembly and installation of Containment Vessel, the management of product protection and personnel safety inside the Containment Building during 'Open Top' construction, raises to implement effective protection for the numerous pre-set mechanical modules and equipments, as well as personnel safety protection programs and measures. The modular construction feature of AP1000 NPP design requires technique improvement and management innovation during the NI construction. This paper makes a study and research on the control management of schedule, quality and safety of AP1000 NPP NI

  8. Phenix Power Plant Decommissioning Project. Treatment of the Primary Cold Trap

    International Nuclear Information System (INIS)

    Deluge, M.

    2008-01-01

    Phenix is a sodium-cooled fast neutron reactor located at the CEA's Rhone Valley Center where it was commissioned in 1974. It has an electric power rating of 250 MW and is operated jointly by the CEA and EDF. Its primary role today is to investigate the transmutation of long-lived radioactive waste into shorter-lived wasteform. Its final shutdown is scheduled for the beginning of 2009. In this context the Phenix Power Plant Decommissioning Project was initiated in 2003. It covers the definitive cessation of plant operation and the dismantling (D and D) operations together with the final shutdown preparatory phase. The final shutdown phase includes the operations authorized within the standard operating methodological framework. The dismantling phase also comprises treatment of sodium-bearing waste and dismantling of the nuclear facilities (reactor block, shielded cells, etc.). Treatment of the Phenix primary cold trap is scheduled to begin in 2016. The analysis program includes the following steps: - Accurately determine the contamination in the trap by carrying out gamma spectrometry measurement campaigns from 2007 to 2013 (the remaining difficulty will be to accurately determine the distribution of the contamination). - Validate the safety studies for the ELA facility. This work is currently in progress; ELA will be commissioned following inactive qualification testing. - Proceed with cutting tests on the knit mesh filter, which are scheduled to begin in 2008

  9. Modern methods of project handling - lean management during the deconstruction of nuclear facilities as illustrated by the vitrification plant VEK

    International Nuclear Information System (INIS)

    Freund, Christina; Gentes, Sascha; Dux, Joachim; Reinelt, Joachim

    2011-01-01

    The authors describe the positive experiences from the project handling during the WAK deconstruction process including the implementation of the so called lean management that is supposed to optimize the timing and cost specific approaches. The practical application includes the planning, the licensing application and in case of licensing the realization of the project. Enhancement of transparency and information flow are reached by periodic last planner sessions. Time management and exact scheduling are central parts of the project handling. The contract partners, authorities and consultants are involved at an early state of the project. After shutdown of the vitrification plant VEK the planning for the deconstruction licensing application according to the atomic law have been started.

  10. Can we talk? Communications management for the Waste Isolation Pilot Plant, a complex nuclear waste management project

    Energy Technology Data Exchange (ETDEWEB)

    Goldstein, S.A.; Pullen, G.M.; Brewer, D.R.

    1995-07-01

    Sandia Nuclear Waste Management Program is pursuing for DOE an option for permanently disposing radioactive waste in deep geologic repositories. Included in the Program are the Waste Isolation Pilot Plant (WIPP) Project for US defense program mixed waste the Yucca Mountain Project (YMP) for spent power reactor fuel and vitrified high-level waste, projects for other waste types, and development efforts in environmental decision support technologies. WIPP and YMP are in the public arena, of a controversial nature, and provide significant management challenges. Both projects have large project teams, multiple organization participants, large budgets, long durations, are very complex, have a high degree of programmatic risk, and operate in an extremely regulated environment requiring legal defensibility. For environmental projects like these to succeed, SNL`s Program is utilizing nearly all areas in PMI`s Project Management Body of Knowledge (PMBOK) to manage along multiple project dimensions such as the physical sciences (e.g., geophysics and geochemistry; performance assessment; decision analysis) management sciences (controlling the triple constraint of performance, cost and schedule), and social sciences (belief systems; public participation; institutional politics). This discussion focuses primarily on communication challenges active on WIPP. How is the WIPP team meeting the challenges of managing communications?`` and ``How are you approaching similar challenges?`` will be questions for a dialog with the audience.

  11. Projected role of nuclear power in Egypt and problems encountered in implementing the first nuclear power plant

    International Nuclear Information System (INIS)

    Effat, K.E.A.; Sirry, H.; El-Sharkawy, E.

    1977-01-01

    The increasing rise in fossil-fuel prices has favourably affected the economics of nuclear power generation bringing down the economically competitive size of nuclear units closer to small sizes compatible with grid capacities in developing countries. This encouraged Egypt to turn to nuclear power to fulfil its future power needs. In implementing its first nuclear power plant, Egypt is facing various problems. The capacity of the national electric power system and its inherent characteristics pose certain restrictions on the size and design of the nuclear plant required. The availability of sufficient local qualified management, engineering and technical personnel to participate in both precontractual and construction phases of the plant is quite a major problem. Lack of local developed industry to back up the construction phase implies the dependence to a large extent on imported equipment, materials and technology. The paper reviews the present and projected power demands in Egypt and the factors behind the decision to introduce a nuclear power generation programme. Various problems encountered and anticipated in introducing the first nuclear power plant are also discussed. (author)

  12. Neutron Measurements At Hanford's Plutonium Finishing Plant

    International Nuclear Information System (INIS)

    Conrady, Matthew M.; Berg, Randal K.; Scherpelz, Robert I.; Rathbone, Bruce A.

    2009-01-01

    The Pacific Northwest National Laboratory (PNNL) conducted neutron measurements at Hanford's Plutonium Finishing Plant (PFP). The measurements were performed to evaluate the performance of the Hanford Standard Dosimeter (HSD) and the 8816 TLD component of the Hanford Combination Neutron Dosimeter (HCND) in the neutron fields responsible for worker neutron exposures. For this study, TEPC detectors and multisphere spectrometers were used to measure neutron dose equivalent rate, and multispheres were used to measure average neutron energy. Water-filled phantoms holding Hanford dosimeters were positioned at each measurement location. The phantoms were positioned in the same location where a multisphere measurement was taken and TEPCs were also positioned there. Plant survey meters were also used to measure neutron dose rates at all locations. Three measurement locations were chose near the HC-9B glovebox in room 228A of Building 234-5. The multisphere spectrometers measured average neutron energies in the range of 337 to 555 keV at these locations. Personal dose equivalent, Hp(10)n, as measured by the multisphere and TEPC, ranged from 2.7 to 9.7 mrem/h in the three locations. Effective dose assuming a rotational geometry (EROT) was substantially lower than Hp(10), ranging from 1.3 to 3.6 mrem/h. These values were lower than the reported values from dosimeters exposed on a rotating phantom. Effective dose assuming an AP geometry (EAP) was also substantially lower than Hp(10), ranging from 2.3 to 6.5 mrem/h. These values were lower than the reported values from the dosimeters on slab phantoms. Since the effective dose values were lower than reported values from dosimeters, the dosimeters were shown to be conservative estimates of the protection quantities.

  13. Advanced plant design recommendations from Cook Nuclear Plant experience

    International Nuclear Information System (INIS)

    Zimmerman, W.L.

    1993-01-01

    A project in the American Electric Power Service Corporation to review operating and maintenance experience at Cook Nuclear Plant to identify recommendations for advanced nuclear plant design is described. Recommendations so gathered in the areas of plant fluid systems, instrument and control, testing and surveillance provisions, plant layout of equipment, provisions to enhance effective maintenance, ventilation systems, radiological protection, and construction, are presented accordingly. An example for a design review checklist for effective plant operations and maintenance is suggested

  14. Country Report Summary: Japan [Project Management in Nuclear Power Plant Construction: Guidelines and Experience

    International Nuclear Information System (INIS)

    2012-01-01

    The Hokkaido Electric Power Company (HEPCO) is the owner of the Tomari NPP comprising three operating PWR units. The latest unit to be connected to the grid, Tomari Unit 3, is a 3-loop PWR power plant with an electric output of 912 MW(e) supplied by Mitsubishi Heavy Industries (MHI). This is the newest unit in HEPCO and it is the newest PWR unit in Japan as well. The first concrete at Tomari Unit 3 was poured at the end of summer in 2004. The unit entered into commercial operation in December 2009. The Tomari site is located on a northern Japanese island. It is battered by strong winds and receives much snow in the winter. Therefore, civil works and building construction were temporarily suspended every year from the beginning of December until the end of March. This increased construction duration by one year compared to other sites. Consequently from first concrete to the start of commercial operation construction at Tomari lasted 64 months. There are specific factors in the approach to construction of nuclear power plants in Japan. (1) Japanese legislation defines that the sole licensee must be the electric power company. This implies that the electric power company is responsible for the safety of the plant and in that capacity it must submit for approval the Safety Analysis Report (SAR) but it is also responsible for the design and reliability of the plant; hence it must also submit for approval the Construction Plan (CP), containing all necessary detailed design information. Consequently, the electric power company becomes the sole counterpart to the regulatory body on all aspects of the project. (2) All Japanese electric power companies are considerably large and have the tradition to do the engineering of their power plant themselves, and this not only for nuclear but also for conventional power plant. Therefore, the owner/utilities in Japan carry themselves the burden of major portions of the engineering, procurement and construction (EPC) of their NPPs

  15. The Contribution of Josip Bakić’s Research to the Study of Wild Edible Plants of the Adriatic Coast: a Military Project with Ethnobiological and Anthropological Implications

    Directory of Open Access Journals (Sweden)

    Marija Jug-Dujaković

    2016-06-01

    Full Text Available Between 1962-1986 the Yugoslav Army carried out a project in which Josip Bakić from the Institute for Naval Medicine of the Yugoslav Navy in Split took the main professional role. In the project, amongst other activities, Bakić and his team explored the possibility of soldiers’ survival on the Adriatic islands based on wild plants and marine animals. As a part of this project, wild food plants and animals from the coast that had been used by the population during World War I and II were surveyed. Some phytochemical properties of the plants were also studied. Educa- tion of soldiers and the wider public was provided based on the results of the research and experiments. The project is a unique example of combining a scientific study with a practical military experiment. Apart from scientific papers the results were also popularized as a survival handbook, a book about nutrition from nature, film documentaries, and workshops. In this paper we summarize the achievements of this project based on the review of published data and interviews with Josip Bakić.

  16. VT Biodiversity Project - Plant and Animal Species Atlas

    Data.gov (United States)

    Vermont Center for Geographic Information — (Link to Metadata) This database contains town-level totals of documented species records for several plant and animal taxa including vascular plants, trees,...

  17. Project Phaseolus

    International Nuclear Information System (INIS)

    Anon.

    Research carried out through the Phaseolus Project of the 'Centro de Energia Nuclear na Agricultura' (CENA) Piracicaba, Sao Paulo State, Brazil, is described. It comprises the following subject s: plant breeding; nitrogen fixation; tissue cultures; proteins; photosynthetic efficiency; soil-plant interactions; electron microscopy of the golden mosaic virus; pest control; production of 15 N-enriched ammonium sulfate, and determination of elements in the beans plant. (M.A.) [pt

  18. Atmospheric release advisory capability pilot project at two nuclear power plants and associated state offices of emergency preparedness. Final report

    International Nuclear Information System (INIS)

    Rosen, L.C.

    1983-01-01

    A project to demonstrate the feasibility of utilizing Atmospheric Release Advisory Capability (ARAC) limited service with commercial nuclear power plants and their associated state offices of emergency preparedness is discussed. Preliminary planning, installation and testing of the ARAC site facilities at Indian Point Nucler Power Station, New York State; at New York State Office of Emergency Preparedness, Albany, New York; at Rancho Seco Nuclear Generating Station, California; and at the State of California Office of Emergency Services, Sacramento, California, are summarized. ARAC participation in the Robert E. Ginna nuclear generating plant accident in New York on January 25, 1982, is discussed. The ARAC system is evaluated with emphasis on communications, the suite of models contained within the ARAC system, and the staff. The implications of this project in designing the next-generation ARAC system to service federal and state needs are assessed

  19. Materials in flue gas condensation plants; Materialval vid roekgaskondensering

    Energy Technology Data Exchange (ETDEWEB)

    Goldschmidt, Barbara; Nordling Magnus

    2003-02-01

    This project is the first part of a larger project. In the part reported here, materials for flue gas condensers have been investigated by contact with plant owners and suppliers and by a literature review of reported failures. If it is decided to continue with another part of the project, a number of materials will be long term tested on site. The project is complementary to an earlier project, which investigated the operating experiences from flue gas condensers in biomass fired cogeneration plants. In the project materials (steel and polymeric) suitable for long term testing in existing plants are discussed. It is proposed that testing in the second part of the project is made with material coupons in one plant fired with only biomass and one plant where biomass is co fired with other fuels. In the biomass fired plant a number of steel materials should be tested. In the co fired plant, with its harsher operating conditions, the same steel materials plus a number of polymeric materials should be tested. Materials suitable for testing are summarised in the report.

  20. Detergent zeolite filtration plant

    OpenAIRE

    Stanković Mirjana S.; Pezo Lato L.

    2003-01-01

    The IGPC Engineering Department designed basic projects for detergent zeolite filtration plant, using technology developed in the IGPC laboratories. Several projects were completed: technological, machine, electrical, automation. On the basis of these projects, a production plant with a capacity of 75,000 t/y was manufactured, at "Zeolite Mira", Mira (VE), Italy, in 1997, for increasing detergent zeolite production, from 50,000 to 100,000 t/y. The main goal was to increase the detergent zeoli...

  1. Emissions from decentralised CHP plants 2007 - Energinet.dk Environmental project no. 07/1882. Project report 5 - Emission factors and emission inventory for decentralised CHP production

    Energy Technology Data Exchange (ETDEWEB)

    Nielsen, Malene; Nielsen, Ole-Kenneth; Thomsen, M.

    2010-06-15

    Updated emission factors for decentralised combined heat and power (CHP) plants with a capacity < 25MWe have been estimated based on project emission measurements as well as emission measurements performed in recent years that were collected. The emission factors valid for 2006/2007 have been estimated for the plant technologies: Municipal solid waste (MSW) incineration plants, plants combusting straw or wood, natural gas fuelled reciprocating engines, biogas fuelled engines, natural gas fuelled gas turbines, gas oil fuelled reciprocating engines, gas oil fuelled gas turbines, steam turbines combusting residual oil and reciprocating engines combusting biomass producer gas based on wood. The emission factors for MSW incineration plants are much lower than the emission factors that were estimated for year 2000. The considerable reduction in the emission factors is a result of lower emission limit values in Danish legislation since 2006 that has lead to installation of new and improved flue gas cleaning systems in most MSW incineration plants. For CHP plants combusting wood or straw no major technical improvements have been implemented. The emission factors for natural gas fuelled reciprocating engines have been reduced since year 2000 as a result of technical improvements that have been carried out due to lower emission limit values in Danish legislation. The NO{sub x} emission factor for natural gas fuelled gas turbines has decreased 62 % since year 2000. This is a result of installation of low-NO{sub x} burners in almost all gas turbines that has been necessary to meet new emission limits in Danish legislation. The emission measurements programme included screening of the emissions of HCB, PCB, PCDD/-F and PBDD/-F. Compared to the Danish national emission decentralized CHP plants are major emission sources for CH{sub 4}, NO{sub x}, SO{sub 2}, heavy metals and HCB. (author)

  2. Transmission avoided cost: a new parameter to evaluate the economic competitiveness of generations plants projects

    Energy Technology Data Exchange (ETDEWEB)

    Ramos, D S [Companhia Energetica de Sao Paulo, SP (Brazil); Albuquerque, J C.R.; Rosenblat, J [ELETROBRAS, Rio de Janeiro, RJ (Brazil)

    1994-12-31

    The paper presents a new formulation that makes feasible a composition of long run production marginal costs with the long run transmission marginal costs, including the costs related to the interconnection EHV networks and that related to the voltage levels below. The goal top be attained is to have available a more adequate parameter in order to compare production cost related to a plant, that will be connected to a certain voltage level network, to the cost related supplying the sam,e amount of energy from the bulk power system which will be represented by the marginal costs up to the voltage level under consideration. This procedure brings to light the Transmission Avoided Costs concepts, that are stressed throughout the text. The proposed methodology is now being used, in the brazilian Power Sector, as a rule of thumb in order to guide planning decisions about the schedule of new plants that have installed capacity below 30 MW. For plants with higher capacity, the transmission avoided costs are evaluated for each specific case, simulating the system behavior without the quoted hydroelectric plant. This paper focuses, an an application example, the case of the Canoas Hydroelectric Project, recently included in the Generation Expansion Reference Plan after a detailed analysis supported by the methodology described here. (author) 7 refs., 3 tabs.

  3. Bioenergy guide. Projecting, operation and economic efficiency of biomass power plants; Leitfaden Bioenergie. Planung, Betrieb und Wirtschaftlichkeit von Bioenergieanlagen

    Energy Technology Data Exchange (ETDEWEB)

    Deimling, S. [Stuttgart Univ. (DE). Inst. fuer Energiewirtschaft und Rationelle Energieanwendung (IER); Kaltschmitt, M; Schneider, B. [and others

    2000-07-01

    This guide gives an survey over planning, operation and economics of biomass conversion plants. Main topics are: production and supply of biomass fuels, combustion properties, licensing, cost and financing. It shows planning and management of projects and the legal background for Germany and the European Union.

  4. Evaluation of the integrity and duration of the Laguna Verde nuclear power plant life- Plant Life Management program (PLIM). TC MEX 04/53 Technical Cooperation Project

    International Nuclear Information System (INIS)

    Arganis J, C.R.; Diaz S, A.; Aguilar T, J.A.

    2006-01-01

    As part of the IAEA TC MEX 04/53 Project 'Evaluation of the integrity and extension of life of the Laguna Verde nuclear power plant Handling Program of plant' whose objective is the one of beginning the actions to apply the methodology of Handling of plant life in the Unit 1 of the Laguna Verde Nucleo electric Central for to obtain the Renovation of License in 2020 the ININ, through the Department of Synthesis and Characterization of materials has carried out more of 20 analysis of susceptibility to the intergranular cracking for corrosion under effort in interns so much of the reactor of the unit 1 like of the unit 2 documenting the current state of components based on the type or types of materials that conform them, to it thermomechanical history, operational and of production, as well as of the particularities associated to its use and operation. For the application of the methodology of life handling of plant 5 structure systems or pilot components were selected, to carry out the programs of handling of the aging and handling of plant life: The encircling of the reactor core (Core Shroud), the reactor pressure vessel (Reactor Pressure Vessel), the primary container (Primary Containment), the recirculation system of feeding water (Reactor Feed Water) and cables. (Author)

  5. Development of a strategic plan for an international R and D project on innovative nuclear fuel cycles and power plants

    International Nuclear Information System (INIS)

    Kendall, J.; Choi, J.S.

    2002-01-01

    The long-term outlook for nuclear energy should be considered in a broader perspective of future energy needs, operational safety, proliferation and environmental impacts. An Advisory Group Meeting (AGM) on Development of a Strategic Plan for an International R and D Project on Innovative Nuclear Fuel Cycles and Power Plants was convened in Vienna in October 1999 to assess the criteria, the needs for international cooperation, and to formulate a strategic plan for project integration. (author)

  6. Development of a General-Purpose Analysis System Based on a Programmable Fluid Processor Final Report CRADA No. TC-2027-01

    Energy Technology Data Exchange (ETDEWEB)

    McConaghy, C. F. [Lawrence Livermore National Lab. (LLNL), Livermore, CA (United States); Gascoyne, P. R. [Lawrence Livermore National Lab. (LLNL), Livermore, CA (United States)

    2017-09-28

    The purpose ofthis project was to develop a general-purpose analysis system based on a programmable fluid processor (PFP). The PFP is an array of electrodes surrounded by fluid reservoirs and injectors. Injected droplets of various reagents are manjpulated and combined on the array by Dielectrophoretic (DEP) forces. The goal was to create a small handheld device that could accomplish the tasks currently undertaken by much larger, time consuming, manual manipulation in the lab. The entire effo1t was funded by DARPA under the Bio-Flips program. MD Anderson Cancer Center was the PI for the DARPA effort. The Bio-Flips program was a 3- year program that ran from September 2000 to September 2003. The CRADA was somewhat behind the Bi-Flips program running from June 2001 to June 2004 with a no cost extension to September 2004.

  7. Deformation and Heat Transfer on Three Sides Protected Beams under Fire Accident

    Science.gov (United States)

    Imran, M.; Liew, M. S.; Garcia, E. M.; Nasif, M. S.; Yassin, A. Y. M.; Niazi, U. M.

    2018-04-01

    Fire accidents are common in oil and gas industry. The application of passive fire protection (PFP) is a costly solution. The PFP is applied only on critical structural members to optimise project cost. In some cases, beams cannot be protected from the top flange in order to accommodate for the placement of pipe supports and grating. It is important to understand the thermal and mechanical response of beam under such condition. This paper discusses the response of steel beam under ISO 834 fire protected, unprotected and three sides protected beams. The model validated against an experimental study. The experimental study has shown good agreement with FE model. The study revealed that the beams protected from three sides heat-up faster compare to fully protected beam showing different temperature gradient. However, the affects load carrying capacity are insignificant under ISO 834 fire.

  8. The Ellweiler uranium plant - a demolition and recycling project

    International Nuclear Information System (INIS)

    Mika, S.; Rohr, T.; Seehars, R.; Feser, A.

    1999-01-01

    The uranium plant at Ellweiler, district of Birkenfeld, was used for the production and storage of uranium concentrates. The owner of the Ellweiler uranium plant (UAE), Gewerkschaft Brunhilde GmbH, ceased processing uranium ore and recycling in 1989 and has been in liquidation since September 1991. The State of Rhineland-Palatinate, had safety measures adopted in a first step, getting the plant into a safe state by former plant personnel. The entire plant was demolished in a second step. The contract for demolishing the former uranium plant was awarded to ABB Reaktor as the general contractor in August 1996. Demolition work was carried out between April 1997 and May 1999. A total of approx. 7900 Mg of material was disposed of. At present, recultivation measures are being carried out. (orig.) [de

  9. Projections of cost and on-site manual-labor requirements for constructing electric-generating plants, 1980-1990

    International Nuclear Information System (INIS)

    1982-02-01

    This report represents part of a continuing effort by the Federal Government to forecast the capital and labor required for constructing electric generating capacity additions necessary to accommodate projected economic and population growth in the US and its regions. Information is included on anticipated additions to electric generating capacity, labor requirements for these additions, capital cost requirements, and forecasting models. Coal-fired, nuclear, hydro, and pumped storage power plants are considered in these forecasts

  10. A study of toxic emissions from a coal-fired power plant utilizing an ESP while demonstrating the ICCT CT-121 FGD Project. Final report

    Energy Technology Data Exchange (ETDEWEB)

    1994-06-16

    The US Department of Energy is performing comprehensive assessments of toxic emissions from eight selected coal-fired electric utility units. This program responds to the Clean Air Act Amendments of 1990, which require the US Environmental Protection Agency (EPA) to evaluate emissions of hazardous air pollutants (HAPs) from electric utility power plants for Potential health risks. The resulting data will be furnished to EPA utility power plants and health risk determinations. The assessment of emissions involves the collection and analysis of samples from the major input, process, and output streams of each of the eight power plants for selected hazardous Pollutants identified in Title III of the Clean Air Act. Additional goals are to determine the removal efficiencies of pollution control subsystems for these selected pollutants and the Concentrations associated with the particulate fraction of the flue gas stream as a function of particle size. Material balances are being performed for selected pollutants around the entire power plant and several subsystems to identify the fate of hazardous substances in each utility system. Radian Corporation was selected to perform a toxics assessment at a plant demonstrating an Innovative Clean Coal Technology (ICCT) Project. The site selected is Plant Yates Unit No. 1 of Georgia Power Company, which includes a Chiyoda Thoroughbred-121 demonstration project.

  11. Basic investigation on promotion of joint implementation in fiscal 2000. Efficiency improvement project for district heat supplying plants in Dailian City in China; 2000 nendo kyodo jisshi nado suishin kiso chosa hokokusho. Chugoku/Dailian shi chiiki netsu kyokyu plant kokoritsu kaizen project

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2001-03-01

    Investigations and discussions have been given on energy saving possibilities at two medium-sized heat and power supplying plants in the city of Dailian in China. The project will improve the operation methods of the heat and power plants so that the energy cost can be minimized, and attempt to improve the boiler heat efficiency and save the energy by means of heat recovery and utilization. The draft modification plan for energy conservation has planned operation optimization for energy conservation, control of boiler operation under variable pressure, modification of the external boiler heat converter, use of inverters for the large capacity motors for boilers, and recovery of heat from the boiler blow-down water. In the analysis, models were structured from the operation data, and the effects of applying the energy saving measures were derived from simulation. As a result, the energy saving effect was found to be about 13,000 tons at the Chunhai plant and about 7,000 tons at the Pulandian plant annually (converted to oil). The reduction in greenhouse gas emission was found to be about 40,000 tons at the Chunhai plant and about 20,000 tons at the Pulandian plant annually. The number of years for investment payback is about 4.1 years at the Chunhai plant, and about 4.9 years at the Pulandian plant, wherein good profitability can be estimated. (NEDO)

  12. Literature Review: Crud Formation at the Liquid/Liquid Interface of TBP-Based Solvent-Extraction Processes

    Energy Technology Data Exchange (ETDEWEB)

    Delegard, Calvin H.; Casella, Amanda J.

    2016-09-30

    This report summarizes the literature reviewed on crud formation at the liquid:liquid interface of solvent extraction processes. The review is focused both on classic PUREX extraction for industrial reprocessing, especially as practiced at the Hanford Site, and for those steps specific to plutonium purification that were used at the Plutonium Reclamation Facility (PRF) within the Plutonium Finishing Plant (PFP) at the Hanford Site.

  13. Optimization of advanced plants operation: The Escrime project

    International Nuclear Information System (INIS)

    Fiche, C.; Papin, B.

    1994-01-01

    The Escrime program aims at defining the optimal share of tasks between humans and computers under normal or accidental plant operation. Basic principles we keep in mind are the following: human operators are likely to be necessary in the operation of future plants because we cannot demonstrate that plant design is error free, so unexpected situation can still happen; automation must not release the operators from their decisional role but only help them avoiding situations of cognitive overload which can lead to increase the risk of errors; the optimum share of tasks between human and automatic systems must be based on a critical analysis of the tasks and of the way they are handled. The last point appeared to be of major importance. The corresponding analysis of the French PWR's operating procedures enabled us to define a unified scheme for plant operation under the form of a hierarchy of goals and means. Beyond this analysis, development of a specific testing facility is under way to check the relevance of the proposed plant operation organization and to test the human-machine cooperation in different situations for various levels of automation. 7 refs, 4 figs

  14. Project management for economical nuclear energy

    International Nuclear Information System (INIS)

    Majerle, P.P.

    2005-01-01

    The price of electricity is significantly influenced by the cost of the initial generation asset. The cost of the initial nuclear generation asset is significantly influenced by the design and construction duration. Negative variations in the cost and duration of actual design and construction have historically impacted the early relative economics of nuclear power generation. Successful management of plant design information will mitigate the risks of the design and construction of future nuclear plants. Information management tools that can model the integrated delivery of large complex projects enable the project owners to accurately evaluate project progress, as well as the economic impact of regulatory, political, or market activities not anticipated in the project execution plan. Significant differences exist in the electrical energy markets, project delivery models, and fuel availability between continents and countries. However, each market and project delivery model is challenged by the need to produce economical electrical energy. The information management system presented in this paper provides a means to capture in a single integrated computerized database the design information developed during plant design, procurement, and construction and to allow this information to be updated and retrieved in real time by all project participants. Utilization of the information management system described herein will enable diverse project teams to rapidly and reliably input, share, and retrieve power plant information, thereby supporting project management's goal to make good on its commitment to the economic promise of tomorrow's nuclear electrical power generation by achieving cost-effective construction. (authors)

  15. Hip and knee strength is not affected in 12-16 year old adolescents with patellofemoral pain--a cross-sectional population-based study.

    Directory of Open Access Journals (Sweden)

    Camilla Rams Rathleff

    Full Text Available BACKGROUND: One of the rationales behind using strength training in the treatment of adolescents with Patellofemoral Pain (PFP is that reduced strength of the lower extremity is a risk factor for PFP and a common deficit. This rationale is based on research conducted on adolescents >15 years of age but has never been investigated among young adolescents with PFP. OBJECTIVES: To compare isometric muscle strength of the lower extremity among adolescents with PFP compared to age- and gender-matched pain-free adolescents. METHODS: In 2011 a population-based cohort (APA2011-cohort consisting of 768 adolescents aged 12-15 years from 8 local schools was formed. In September 2012, all adolescents who reported knee pain in September 2011 were offered a clinical examination if they still had knee pain. From these, 20 adolescents (16 females were diagnosed with PFP. Pain-free adolescents from the APA2011-cohort (n = 20 were recruited on random basis as age- and gender-matched pairs. Primary outcome was isometric knee extension strength normalized to body weight (%BW and blinded towards subject information. Secondary outcomes included knee flexion, hip abduction/adduction and hip internal/external rotation strength. Demographic data included Knee Injury and Osteoarthritis Outcome Score (KOOS and symptom duration. RESULTS: Adolescents with PFP reported long symptom duration and significantly worse KOOS scores compared to pain-free adolescents. There were no significant differences in isometric knee extension strength (Δ0.3% BW, p = 0.97, isometric knee flexion strength (Δ0.4% BW, p = 0.84 or different measures of hip strength (Δ0.4 to 1.1% BW, p>0.35. CONCLUSION: Young symptomatic adolescents with PFP between 12 and 16 years of age did not have decreased isometric muscle strength of the knee and hip. These results question the rationale of targeting strength deficits in the treatment of adolescents with PFP. However, strength training may

  16. Definition and means of maintaining the emergency notification and evacuation system portion of the Plutonium Finishing Plant safety envelope

    International Nuclear Information System (INIS)

    White, W.F.

    1997-01-01

    The Emergency Evacuation and Notification System provides information to the PFP Building Emergency Director to assist in determining appropriate emergency response, notifies personnel of the required response, and assists in their response. The report identifies the equipment in the Safety Envelope (SE) for this System and the Administrative, Maintenance, and Surveillance Procedures used to maintain the SE Equipment

  17. Long-distance transport of mRNA via parenchyma cells and phloem across the host-parasite junction in Cuscuta.

    Science.gov (United States)

    David-Schwartz, Rakefet; Runo, Steven; Townsley, Brad; Machuka, Jesse; Sinha, Neelima

    2008-01-01

    It has been shown that the parasitic plant dodder (Cuscuta pentagona) establishes a continuous vascular system through which water and nutrients are drawn. Along with solutes, viruses and proteins, mRNA transcripts are transported from the host to the parasite. The path of the transcripts and their stability in the parasite have yet to be revealed. To discover the route of mRNA transportation, the in situ reverse transcriptase-polymerase chain reaction (RT-PCR) technique was used to locally amplify host transcript within parasitic tissue. The stability of host mRNA molecules was also checked by monitoring specific transcripts along the growing dodder thread. Four mRNAs, alpha and beta subunits of PYROPHOSPHATE (PPi)-DEPENDENT PHOSPHOFRUCTOKINASE (LePFP), the small subunit of ribulose-1,5-bisphosphate carboxylase/oxygenase (RuBisCO), and GIBBERELLIC ACID INSENSITIVE (LeGAI), were found to move from host (tomato (Solanum lycopersicum)) to dodder. LePFP mRNA was localized to the dodder parenchyma cells and to the phloem. LePFP transcripts were found in the growing dodder stem up to 30 cm from the tomato-dodder connection. These results suggest that mRNA molecules are transferred from host to parasite via symplastic connections between parenchyma cells, move towards the phloem, and are stable for a long distance in the parasite. This may allow developmental coordination between the parasite and its host.

  18. Small-scale hydro-power plant in Quinto - Preliminary project; Progetto minicentrale idroelettrica, Ri Secco - Quinto. Programma piccole centrali idrauliche. Progetto di massima

    Energy Technology Data Exchange (ETDEWEB)

    Dotti, R. [Reali e Guscetti SA, Ambri (Switzerland); Rosselli, P. [Celio Engineering SA, Ambri (Switzerland)

    2009-06-15

    This report for the Swiss Federal Office of Energy (SFOE) takes a look at a project for the realisation of a small hydro-power plant on the alpine stream 'Ri Secco' in the municipality of Quinto, southern Switzerland. The Ri Secco partly flows in a steep canyon. The elevation difference of 810 or 620 m (depending on the location of the water deviation from the stream) is favorable to the installation of a small-scale high-head power plant. The report presents details on the hydrological data and the dimensioning of the installation. Several variants are considered, which also include two possible penstock diameters for each weir location. The electricity production expected is discussed, as is the economic viability of the project.

  19. Safety analysis report for packaging (onsite) transuranic performance demonstration program sample packaging

    International Nuclear Information System (INIS)

    Mccoy, J.C.

    1997-01-01

    The Transuranic Performance Demonstration Program (TPDP) sample packaging is used to transport highway route controlled quantities of weapons grade (WG) plutonium samples from the Plutonium Finishing Plant (PFP) to the Waste Receiving and Processing (WRAP) facility and back. The purpose of these shipments is to test the nondestructive assay equipment in the WRAP facility as part of the Nondestructive Waste Assay PDP. The PDP is part of the U. S. Department of Energy (DOE) National TRU Program managed by the U. S. Department of Energy, Carlsbad Area Office, Carlsbad, New Mexico. Details of this program are found in CAO-94-1045, Performance Demonstration Program Plan for Nondestructive Assay for the TRU Waste Characterization Program (CAO 1994); INEL-96/0129, Design of Benign Matrix Drums for the Non-Destructive Assay Performance Demonstration Program for the National TRU Program (INEL 1996a); and INEL-96/0245, Design of Phase 1 Radioactive Working Reference Materials for the Nondestructive Assay Performance Demonstration Program for the National TRU Program (INEL 1996b). Other program documentation is maintained by the national TRU program and each DOE site participating in the program. This safety analysis report for packaging (SARP) provides the analyses and evaluations necessary to demonstrate that the TRU PDP sample packaging meets the onsite transportation safety requirements of WHC-CM-2-14, Hazardous Material Packaging and Shipping, for an onsite Transportation Hazard Indicator (THI) 2 packaging. This SARP, however, does not include evaluation of any operations within the PFP or WRAP facilities, including handling, maintenance, storage, or operating requirements, except as they apply directly to transportation between the gate of PFP and the gate of the WRAP facility. All other activities are subject to the requirements of the facility safety analysis reports (FSAR) of the PFP or WRAP facility and requirements of the PDP

  20. Remote-Reading Safety and Safeguards Surveillance System for 3013 Containers

    International Nuclear Information System (INIS)

    Lechelt, W. M.; Skorpik, J. R.; Silvers, K. L.; Szempruch, R. W.; Douglas, D. G.; Fein, K. O.

    2002-01-01

    At Hanford's Plutonium Finishing Plant (PFP), plutonium oxide is being loaded into stainless steel containers for long-term storage on the Hanford Site. These containers consist of two weld-sealed stainless steel cylinders nested one within the other. A third container holds the plutonium within the inner cylinder. This design meets the U.S. Department of Energy (DOE) storage standard, DOE-STD- 3013-2000, which anticipates a 50-year storage lifetime. The 3013 standard also requires a container surveillance program to continuously monitor pressure and to assure safeguards are adequate. However, the configuration of the container system makes using conventional measurement and monitoring methods difficult. To better meet the 3013 monitoring requirements, a team from Fluor Hanford (who manages the PFP), Pacific Northwest National Laboratory (PNNL), and Vista Engineering Technologies, LLC, developed a safer, cost-efficient, remote PFP 3013 container surveillance system. This new surveillance system is a combination of two successfully deployed technologies: (1) a magnetically coupled pressure gauge developed by Vista Engineering and (2) a radio frequency (RF) tagging device developed by PNNL. This system provides continuous, 100% monitoring of critical parameters with the containers in place, as well as inventory controls. The 3013 container surveillance system consists of three main elements: (1) an internal magnetic pressure sensor package, (2) an instrument pod (external electronics package), and (3) a data acquisition storage and display computer. The surveillance system described in this paper has many benefits for PFP and DOE in terms of cost savings and reduced personnel exposure. In addition, continuous safety monitoring (i.e., internal container pressure and temperature) of every container is responsible nuclear material stewardship and fully meets and exceeds DOE's Integrated Surveillance Program requirements

  1. Risk management of energy efficiency projects in the industry - sample plant for injecting pulverized coal into the blast furnaces

    Directory of Open Access Journals (Sweden)

    Jovanović Filip P.

    2016-01-01

    Full Text Available This paper analyses the applicability of well-known risk management methodologies in energy efficiency projects in the industry. The possibilities of application of the selected risk management methodology are demonstrated within the project of the plants for injecting pulverized coal into blast furnaces nos. 1 and 2, implemented by the company US STEEL SERBIA d.o.o. in Smederevo. The aim of the project was to increase energy efficiency through the reduction of the quantity of coke, whose production requires large amounts of energy, reduction of harmful exhaust emission and increase productivity of blast furnaces through the reduction of production costs. The project was complex and had high costs, so that it was necessary to predict risk events and plan responses to identified risks at an early stage of implementation, in the course of the project design, in order to minimise losses and implement the project in accordance with the defined time and cost limitations. [Projekat Ministarstva nauke Republike Srbije, br. 179081: Researching contemporary tendencies of strategic management using specialized management disciplines in function of competitiveness of Serbian economy

  2. Outline of nuclear power plant project of fast breeder reactor (FBR) 'Monju'

    International Nuclear Information System (INIS)

    Suzuki, Fumio; Higashide, Noboru

    1982-01-01

    The first step of the construction of the fast breeder prototype reactor ''Monju'' in Japan was taken by the declaration of agreement of Fukui Prefecture governor in May, 1982, and the succeeding approval by the cabinet council. In this paper, the outline of the project is described. The paper first introduces the development status of FBRs in the world, and next, describes the progress of planning the ''Monju'' project. Initially, ''Monju'' was invited by Shiraki region of Tsuruga City, but the move of village was not agreed. Thus, the center of the site was moved to ''Haseda'' about 1 km north-east. In addition, there were some limitations, and the layout of the facility and the design of public work structures including harbour construction were done under many limiting conditions. However, the site is rather in good conditions, and the design rationalization was attempted as far as possible within a range which does not affect the safety of the nuclear power plant. The outline of the examination related to public works and the siting conditions are reported, dividing them into topographic features, geology, meteorology, sea conditions, and natural environment. As the public works plan, site preparation, roads, harbour installations and water intake and discharge facility are also described. (Wakatsuki, Y.)

  3. Report on the basic survey on promotion of joint project implementation in fiscal 1998. 'Repowering of three gas-based thermal power plants'; 1998 nendo kyodo jisshi nado suishin kiso chosa. Gas base karyoku hatsudensho no repowering (3 plant)

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1999-03-01

    With an objective of reactivating and reduction of emission of greenhouse effect gases, investigations and discussions were given on repowering three thermal power plants in the Federal Republic of Russia. The project on Kirishi Power Station calls for withdrawal of 1800-MW capacity out of the existing generation capacity of 2100 MW, and installation of a combined cycle power plant having an output capacity of 1950 MW. The existing 300-MW capacity will be used mainly for heat supply. At Puskovskaya Power Plant, a combined cycle power plant with a capacity of 1170 MW will be built newly. Iriklinskaya Power Station will have the existing plant removed, where a new combined cycle power plant with a capacity of 2340 MW will be constructed. As a result of the discussions, the cumulative reduction amount of CO2 emission will reach 44.67 million tons, 10.53 million tons, and 89.94 million tons respectively, and the investment return rate before tax will be 11.35%, 11.85% and 11.18% respectively. This project is expected to contribute largely to reduction of CO2 emission, and at the same time strengthen the foundation of the power plant management. (NEDO)

  4. Intelligent distributed control for nuclear power plants

    International Nuclear Information System (INIS)

    Klevans, E.H.

    1993-01-01

    This project was initiated in September 1989 as a three year project to develop and demonstrate Intelligent Distributed Control (IDC) for Nuclear Power Plants. There were two primary goals of this research project. The first goal was to combine diagnostics and control to achieve a highly automated power plant as described by M.A. Schultz. The second goal was to apply this research to develop a prototype demonstration on an actual power plant system, the EBR-2 steam plant. Described in this Final (Third Annual) Technical Progress Report is the accomplishment of the project's final milestone, an in-plant intelligent control experiment conducted on April 1, 1993. The development of the experiment included: simulation validation, experiment formulation and final programming, procedure development and approval, and experimental results. Other third year developments summarized in this report are: (1) a theoretical foundation for Reconfigurable Hybrid Supervisory Control, (2) a steam plant diagnostic system, (3) control console design tools and (4) other advanced and intelligent control

  5. Spanish program of advanced Nuclear Power Plants

    International Nuclear Information System (INIS)

    Marco, M.; Redon, R.

    1993-01-01

    The energy Spanish Plan is promoting some actions within the area of advanced reactors. Efforts are focussed onto the European Program of Advanced Reactors, the Program of Passive Plants (EPRI), European Fast Reactor Project and the APWR-1000 Program of INI. Electrical sector utilities and industrial partners supported by the Administration have organized an steering committee. The program of Passive Plants includes activities on Qualification, design and detailed engineering (Qualification project, SBWR project of G.E. and AP600 Project of Westinghouse. The european project on advanced plants has the following Spanish contribution: Analysis of alternative Dossier on European requisites (EUR) and Design of an European Reactor (EPR)

  6. Towards a Plant Bio-Machine

    DEFF Research Database (Denmark)

    Nichele, Stefano; Risi, Sebastian; Tufte, Gunnar

    2018-01-01

    as a proof of concept that sensing capabilities of plants are a viable option for the development of plant bio-machines. Different future scenarios (some speculative) are discussed. The work herein is carried out as a collaboration between the EU project Flora Robotica and the EU project NASCENCE....

  7. Trojan Decommissioning Project Cost Performance

    International Nuclear Information System (INIS)

    Michael B. Lackey

    2000-01-01

    The Trojan nuclear plant (Trojan) was an 1160-MW(electric) four-loop pressurized water reactor located in Rainier, Oregon. The plant was permanently shut down in 1993 after ∼17 yr of commercial operation. The early plant closure was an economic decision. The key factors in the closure analysis were escalation of inspection and repair costs associated with steam generator tube cracking and the projected availability of inexpensive replacement power in the Pacific Northwest region of the United States. Since the plant closure, Portland General Electric (PGE) has been actively engaged in decommissioning. The Trojan Decommissioning Project currently has a forecast at completion of $429.7 million (all costs are in millions of 1997 dollars, unless otherwise noted). The cost performance of the Trojan Decommissioning Project to date is addressed, as well as the tools that are in place to provide cost control through completion of decommissioning

  8. The small-scale hydroelectric power plant project 'Les Esserts' in Boudry, Switzerland - Feasibility study and preliminary planning; Centrale des Esserts a Boudry. Etude de faisabilite et avant-projet detaille

    Energy Technology Data Exchange (ETDEWEB)

    Roelli, P; Croci, S; Ernst, J -R

    2004-07-01

    This report describes in details the project of the installation of a small-scale hydroelectric power plant on the river Areuse in Switzerland. Located on a 4 m high waterfall the plant includes a 10-13 m{sup 3}/s Kaplan turbine, which should deliver roughly 1.6 GWh/year for an installed power of about 500 kVA. The authors insist on the ecological aspect of the project. The plant will be built underground; the river track will be practically unchanged and the existing fish ladder maintained. The report includes maps and pictures of the site as well as technical drawings of the installation. An economic analysis of the project is presented and its viability is discussed. Finally, the authors state that the energy produced by this plant will certainly be certified under one of the Swiss labels 'naturemade star' or 'naturemade basic', in the framework of the federal government's promotion of renewable energy sources.

  9. Innovative Project Activities in Science [From the NSTA Study of Innovative Project Activities

    Science.gov (United States)

    Science Teacher, 1975

    1975-01-01

    Describes four projects chosen as innovative project activities in science which exhibited identification of unique or novel problems and creative approaches to their solutions. Projects included a study of fish in Lake Erie, a goat raising project, an analysis of terrestrial plant ecology and soil composition, and a study of marine and wetlands…

  10. Shippingport: A relevant decommissioning project

    International Nuclear Information System (INIS)

    Crimi, F.P.

    1988-01-01

    Because of Shippingport's low electrical power rating (72 MWe), there has been some misunderstanding on the relevancy of the Shippingport Station Decommissioning Project (SSDP) to a modern 1175 MWe commercial pressurized water reactor (PWR) power station. This paper provides a comparison of the major components of the reactor plant of the 72 MWe Shippingport Atomic Power Station and an 1175 MWe nuclear plant and the relevancy of the Shippingport decommissioning as a demonstration project for the nuclear industry. For the purpose of this comparison, Portland General Electric Company's 1175 MWe Trojan Nuclear Plant at Rainier, Oregon, has been used as the reference nuclear power plant. 2 refs., 2 figs., 1 tab

  11. Support services for new nuclear power plant projects

    International Nuclear Information System (INIS)

    Manrique, Alberto B.; Cazorla, Francisco

    2009-01-01

    TECNATOM is a spanish engineering company with more than 50 years of experience working for the nuclear industry all over the world. TECNATOM has worked in over 30 countries in activities related to the Operation and Maintenance of Nuclear Power Plants. It started to work in the design of new Nuclear Power Plants in the early 90s and since then has continued collaborating with different suppliers in the design and licensing of new reactors specially in the areas of plant systems design, Man-Machine Interface design, Main Control Room simulators building, training, qualification of equipment and PSI/ISI engineering services. (author)

  12. The Effect of an 8-Week Tai Chi Exercise Program on Physical Functional Performance in Middle-Aged Women.

    Science.gov (United States)

    Zacharia, Susan; Taylor, E Laurette; Hofford, Craig W; Brittain, Danielle R; Branscum, Paul W

    2015-08-01

    The purpose of this study was to determine the effectiveness of an 8-week Tai Chi Chih exercise program on physical functional performance (PFP) among women aged 45 to 65 years. A quasi-experimental design with a nonequivalent comparison group was used. Forty-one healthy inactive women were assigned to either an intervention group (n = 19) or a comparison group (n = 19). A 60-min Tai Chi Chih exercise class was conducted twice a week for 8 weeks. PFP was measured at baseline and postintervention using the Continuous Scale Physical Functional Performance-10 (CS-PFP 10). Between-group differences were analyzed using one-way analysis of covariance (ANCOVA). After participating in the 8-week program, intervention group participants showed greater improvement in the CS-PFP measures (p .06). However, the comparison group had little changes. The findings from this study suggest that participation in an 8-week Tai Chi Chih exercise program can improve PFP in healthy, community-dwelling middle-aged women. © The Author(s) 2013.

  13. Organic p-n heterostructures and superlattices

    Energy Technology Data Exchange (ETDEWEB)

    Kowarik, Stefan [Lawrence Berkeley National Laboratory, Berkeley, CA (United States); Hinderhofer, Alexander; Gerlach, Alexander; Schreiber, Frank [Institut fuer Angewandte Physik, Tuebingen (Germany); Osso, Oriol [MATGAS 2000 A.I.E., Esfera UAB, Barcelona (Spain); Wang, Cheng; Hexemer, Alexander [Advanced Light Source, Berkeley, CA (United States)

    2009-07-01

    For many applications of organic semiconductors two components such as e.g. n and p-type layers are required, and the morphology of such heterostructures is crucial for their performance. Pentacene (PEN) is one of the most promising p-type molecular semiconductors and recently perfluoro-pentacene (PFP) has been identified as a good electron conducting material for complementary circuits with PEN. We use soft and hard X-ray reflectivity measurements, scanning transmission X-ray microscopy (STXM) and atomic force microscopy for structural investigations of PFP-PEN heterostructures. The chemical contrast between PEN and PFP in STXM allows us to determine the lateral length scales of p and n domains in a bilayer. For a superlattice of alternating PFP and PEN layers grown by organic molecular beam deposition, X-ray reflectivity measurements demonstrate good structural order. We find a superlattice reflection that varies strongly when tuning the X-ray energy around the fluorine edge, demonstrating that there are indeed alternating PFP and PEN layers.

  14. Intelligent distributed control for nuclear power plants

    International Nuclear Information System (INIS)

    Klevans, E.H.

    1992-01-01

    This project was initiated in September 1989 as a three year project to develop and demonstrate Intelligent Distributed Control (IDC) for Nuclear Power Plants. The body of this Third Annual Technical Progress report summarizes the period from September 1991 to October 1992. There were two primary goals of this research project. The first goal was to combine diagnostics and control to achieve a highly automated power plant as described by M.A. Schultz. His philosophy, is to improve public perception of the safety of nuclear power plants by incorporating a high degree of automation where a greatly simplified operator control console minimizes the possibility of human error in power plant operations. To achieve this goal, a hierarchically distributed control system with automated responses to plant upset conditions was pursued in this research. The second goal was to apply this research to develop a prototype demonstration on an actual power plant system, the EBR-2 stem plant. Emphasized in this Third Annual Technical Progress Report is the continuing development of the in-plant intelligent control demonstration for the final project milestone and includes: simulation validation and the initial approach to experiment formulation

  15. Process engineering considerations in the design of the water treatment plant for the Rum Jungle rehabilitation project

    International Nuclear Information System (INIS)

    Ackland, M.C.

    1983-01-01

    The Rum Jungle rehabilitation programme includes the treatment of around 4 million cubic metres of water that has been polluted by previous treatment operations and acidic seepage containing heavy metal salts from slowly oxidising overburden dumps. The water to be treated is of low pH and contains high sulphate levels. Project rehabilitation criteria and the basic chemistry of metal salts in solution were considered in arriving at the final process design. In order to achieve a cost effective plant design, the process was translated into a flow sheet that used unit operations that are more typical of the extractive metallurgical than the traditional water treatment industry. Consideration of the unit operations and the operating aspects of the plant are discussed

  16. Planning your first wind power project. A primer for utilities: Everything you need to know to bring your first wind power plant on-line

    International Nuclear Information System (INIS)

    Conover, K.; Davis, E.

    1994-12-01

    This primer has been prepared to help utility personnel become familiar with some or the details relative to wind power technology and project development. It is written as a series of relatively independent chapters to address specific topics or phases of wind power evaluation and development as they might occur within a utility. The topics include: wind prospecting and the first pass analysis, resource validation, project feasibility, resource planning and evaluation, resource acquisition, project development, equipment selection, project design and construction, and plant operation and maintenance

  17. Nuclear plant life - A business decision

    International Nuclear Information System (INIS)

    Joosten, J.K.

    1995-01-01

    Regarding the future of the nuclear power option, many scenarios have been put forth over the years. The most commonly accepted projections for installed nuclear capacity show it growing at a rate of about 2% per year throughout the next few decades. These projections appear modes on the surface. However, underlying the projections are critical assumptions and sometimes misconceptions about the lifetimes of existing reactors and how they are determined. The notion of a 40 year plant life is very common. Consequently, many projections start either with the assumption that no plants will be retired in the near terms or with the assumption that each retired plant will be replaced by another nuclear plant after 40 years. Effectively, these assumptions yield future projections for installed capacity that might be characterized as low growth, medium growth and high growth scenarios - or grow, grow, grow. The question remains as to whether or not these assumptions accurately model the driving forces and constraints to nuclear development. After all, there is no scientific basis for believing that all plants, PWRs BWRs, RBMKs, etc., should have the same 40 year life. Most power plant owners purchase the plant for the main reason of supplying electrical power to their consumer. For these owners, electricity production is a day to day commercial activity with various alternatives on how to achieve the prime objective. The decision of which electricity generation alternative to select (gas, coal, nuclear or renewable energy) and how long to operate the plant before replacing it with a new one is essentially a business decision. The paper discusses ageing, the nuclear plant life decision process, the factors which influence the decision and their ramifications regarding the near term growth of nuclear power capacity. The modelling of nuclear plant lifetimes is also discussed. (author). 5 refs, 10 figs, 1 tab

  18. Project finance in Eastern Europe

    International Nuclear Information System (INIS)

    Hart, R.C.

    1993-01-01

    A dysfunctional system of commercial, legal, and financial institutions is the primary problem facing the energy sectors in Eastern Europe. Generally, a major systemic transformation is well underway in the area and is already showing signs of success. The empty promise of export credit financing exerts a significant negative influence on this reform process. The discipline of project finance provides the best, if not the only, basis for financing the modernization of the Eastern European energy sector. An example is given of the Cracow Environmental Project, a modernization project. The power plant is a combined heat and power facility with 460 MW of electric capacity and 1450 MW of thermal energy capacity. Located near the center of Cracow, the plant burns hard coal and provides more than seventy percent of the central district heat consumed in the city. The scope of proposed improvements has changed from the addition of capacity to a combination of modernization and environmental retrofit of the existing plant. The total estimated cost of the improvements program is 150 million dollars. The project consists of three major elements. First, it has proposed and is in the process of restructuring the ownership of the power plant. Second, it is engaged in a major restructuring of the commercial arrangements that govern the operation of the plant. Finally, it is in the late stages of selecting an engineering, procurement, and construction consortium with which it will contract to design and make major improvements to the existing plant

  19. Maryland Power Plant Siting Project: an application of the ORNL-Land Use Screening Procedure

    International Nuclear Information System (INIS)

    Dobson, J.E.

    1975-01-01

    Since 1974 the Resource Analysis Group in the Regional and Urban Studies Section of the Oak Ridge National Laboratory (ORNL) has been engaged in developing a procedure for regional and local siting analysis known as the ORNL Land Use Screening Procedure (LUSP). This document is the final report of the Maryland Power Plant Siting Project (MPPSP) in which the ORNL LUSP was used to identify candidate areas for power plant sites in northern Maryland. Numerous candidate areas are identified on the basis of four different siting objectives: the minimization of adverse ecologic impact, the minimization of adverse socioeconomic impact, the minimization of construction and operating costs, and a composite of all siting objectives. Siting criteria have been defined for each of these objectives through group processing techniques administered to four different groups of siting specialists. The siting priorities and opinions of each group have been expressed quantitatively and applied to a geographic information system containing 52 variables for each 91.8-acre cell in the northern eight counties of Maryland

  20. Maryland Power Plant Siting Project: an application of the ORNL-Land Use Screening Procedure

    Energy Technology Data Exchange (ETDEWEB)

    Dobson, J.E.

    1975-01-01

    Since 1974 the Resource Analysis Group in the Regional and Urban Studies Section of the Oak Ridge National Laboratory (ORNL) has been engaged in developing a procedure for regional and local siting analysis known as the ORNL Land Use Screening Procedure (LUSP). This document is the final report of the Maryland Power Plant Siting Project (MPPSP) in which the ORNL LUSP was used to identify candidate areas for power plant sites in northern Maryland. Numerous candidate areas are identified on the basis of four different siting objectives: the minimization of adverse ecologic impact, the minimization of adverse socioeconomic impact, the minimization of construction and operating costs, and a composite of all siting objectives. Siting criteria have been defined for each of these objectives through group processing techniques administered to four different groups of siting specialists. The siting priorities and opinions of each group have been expressed quantitatively and applied to a geographic information system containing 52 variables for each 91.8-acre cell in the northern eight counties of Maryland.