  1. Metrological control of the gas flow and analysis of mass conservation in Bolivia-Brasil gas pipeline; Controle metrologico da vazao de gas e analise da conservacao de massa no gasoduto Bolivia-Brazil

    Energy Technology Data Exchange (ETDEWEB)

    Palhares, Julio Cesar [TBG - Transportadora Brasileira Gasoduto Bolivia-Brasil, S.A., Rio de Janeiro, RJ (Brazil); Orlando, Alcir de Faro; Frota, Mauricio Nogueira [Pontificia Univ. Catolica do Rio de Janeiro, RJ (Brazil). Curso de Pos-graduacao em Metrologia para Qualidade Industrial

    2005-07-01

    International gas pipelines reflect a integrated commerce and impose a metrological challenge for the custody transferences that indistinctly imply in significant economic impact. This work argues the complex analysis of the mass balance and expression of uncertainties of the Gasoduto Bolivia-Brasil (3.150 Km of length, 557 Km in Bolivian territory and 2.593 Km that cross Brazil of West for East), today carrying approximately 60% from its maximum capacity (30 million of cubic meters daily), operating for the Transportadora Brasileira Gasoduto Bolivia Brasil S.A., a enterprise controlled by PETROBRAS Gas S/A (GASPETRO). The TBG measuring methods always taking care of the necessities of the customers as well as being lined up with the changes of the natural gas market. In six years of existence, the TBG came along with the legislation created for regulating agency in formation and adjusted to the establishment of the contract inspector, important landmarks of the evolution of the market. This work presents the definitions that guide the metrological subjects of the TBG, making use of efficient tools in answers for each demand and searching to satisfy its proper necessities, the necessities of its customers and the new demands of the regulating agency. (author)

  2. Metrological control of instruments, equipment and measurement system for ultrasonic meters of flow; Controle metrologico de instrumentos, equipamentos e sistema de medicao para medidores ultra-sonicos de vazao

    Energy Technology Data Exchange (ETDEWEB)

    Palacios, Oscar de

    2004-07-01

    Following the actual tendency to obtaining greater precision in Natural Gas measurement, in the past few years the use of Ultrasonic Flow Meters as Custody Transfer applications has grown significantly. There are several units currently operating in Brazil. The legislation for model approval, measure system certification and periodical metrological control of the above mentioned equipment, is currently under elaboration final stage. It was placed under public inquire through the 'Portaria 037' of 2004 of INMETRO, which proposes the authorization to perform the Metrological control by the Operator, once it has a quality system implemented according NBR ISO 9001-2000 and/or ISO 17025. This paper describes the verification procedure adopted by most of ultrasonic meters manufacturers. It also describes the application of the procedure for create the 'Metrological Control System of the Measurement System' of a 12'' Ultrasonic Meter installed and operating, with 3 years operation's data. (author)

  3. Internal corrosion control of northern pipelines

    Energy Technology Data Exchange (ETDEWEB)

    Papavinasam, S.

    2005-02-01

    The general causes of internal corrosion in pipelines were discussed along with the methods to control them. Efficient methods are needed to determine chemical efficiency for mitigating internal corrosion in transmission pipelines, particularly those used in environmentally sensitive regions in the Arctic where harsh environmental conditions prevail. According to the Office of Pipeline Safety, 15 per cent of pipeline failures in the United States from 1994 to 2000 were caused by internal corrosion. Since pipelines in the United States are slightly older than Canadian pipelines, internal corrosion is a significant issue from a Canadian perspective. There are 306,618 km of energy-related pipelines in western Canada. Between April 2001 and March 2002 there were 808 failures, of which 425 failures resulted from internal corrosion. The approach to control internal corrosion comprises of dehydrating the gases at production facilities; controlling the quality of corrosive gases such as carbon dioxide and hydrogen sulphide; and, using internal coatings. The approaches to control internal corrosion are appropriate, when supplemented by adequate integrity management program to ensure that corrosive liquids do not collect, over the operational lifetime of the pipelines, at localized areas. It was suggested that modeling of pipeline operations may need improvement. This paper described the causes, prediction and control of internal pitting corrosion. It was concluded that carbon steel equipment can continue to be used reliably and safely as pipeline materials for northern pipelines if the causes that lead to internal corrosion are scientifically and accurately predicted, and if corrosion inhibitors are properly evaluated and applied. 5 figs.

  4. Optimizing pipeline transportation using a fuzzy controller

    Energy Technology Data Exchange (ETDEWEB)

    Aramaki, Thiago L.; Correa, Joao L. L.; Montalvoa, Antonio F. F. [National Control and Operation Center Tranpetro, Rio de Janeiro, (Brazil)

    2010-07-01

    The optimization of pipeline transportation is a big concern for the transporter companies. This paper is the third of a series of three articles which investigated the application of a system to simulate the human ability to operate a pipeline in an optimized way. The present paper presents the development of a proportional integral (PI) fuzzy controller, in order to optimize pipeline transportation capacity. The fuzzy adaptive PI controller system was developed and tested with a hydraulic simulator. On-field data were used from the OSBRA pipeline. The preliminary tests showed that the performance of the software simulation was satisfactory. It varied the set-point of the conventional controller within the limits of flow meters. The transport capacity of the pipe was maximize without compromising the integrity of the commodities transported. The system developed proved that it can be easily deployed as a specialist optimizing system to be added to SCADA systems.

  5. 75 FR 67450 - Pipeline Safety: Control Room Management Implementation Workshop

    Science.gov (United States)

    2010-11-02

    ... regulations to address human factors and other aspects of control room management for certain pipelines where controllers use supervisory control and data acquisition (SCADA) systems. Under the final rule, pipeline... Washington, DC on October 22, 2010. Jeffrey D. Wiese, Associate Administrator for Pipeline Safety. [FR Doc...

  6. PIPELINE CORROSION CONTROL IN OIL AND GAS INDUSTRY: A ...

    African Journals Online (AJOL)

    Corrosion in pipelines is one of the major challenges faced by oil and gas industries all over the world. This has made corrosion control or management a major factor to consider before setting up any industry that will transport products via pipelines. In this study the types of corrosion found on system 2A pipeline were; ...

  7. Pipeline leak detection method and control device therefor

    International Nuclear Information System (INIS)

    Bell, D.A.

    1983-01-01

    Leaks may be located in a pipeline by introducing into the pipeline an assembly that includes a pipe-sealing packer unit, a control unit, and a radioactive source shielded from the control unit. The control unit includes a gamma ray detector that controls the sealing and unsealing of the pipe by the packer in response to the detection of radiation exceeding a preset threshold - a detection event. The assembly is pushed through the pipeline by a relatively low fluid pressure behind it. The progress of the assembly through the pipeline may be monitored externally by a gamma ray detector

  8. Virtual Instrumentation Corrosion Controller for Natural Gas Pipelines

    Science.gov (United States)

    Gopalakrishnan, J.; Agnihotri, G.; Deshpande, D. M.

    2012-12-01

    Corrosion is an electrochemical process. Corrosion in natural gas (methane) pipelines leads to leakages. Corrosion occurs when anode and cathode are connected through electrolyte. Rate of corrosion in metallic pipeline can be controlled by impressing current to it and thereby making it to act as cathode of corrosion cell. Technologically advanced and energy efficient corrosion controller is required to protect natural gas pipelines. Proposed virtual instrumentation (VI) based corrosion controller precisely controls the external corrosion in underground metallic pipelines, enhances its life and ensures safety. Designing and development of proportional-integral-differential (PID) corrosion controller using VI (LabVIEW) is carried out. When the designed controller is deployed at field, it maintains the pipe to soil potential (PSP) within safe operating limit and not entering into over/under protection zone. Horizontal deployment of this technique can be done to protect all metallic structure, oil pipelines, which need corrosion protection.

  9. 75 FR 56972 - Pipeline Safety: Control Room Management/Human Factors

    Science.gov (United States)

    2010-09-17

    ... for certain pipelines where controllers use supervisory control and data acquisition (SCADA) systems..., for all substantive provisions in the rule. Justification PHMSA periodically reviews its pipeline... expediting the implementation deadlines for the selected paragraphs will have significant impact to pipeline...

  10. PIPELINE CORROSION CONTROL IN OIL AND GAS INDUSTRY: A ...

    African Journals Online (AJOL)

    user

    protection technique as a method of controlling corrosion in oil and gas pipelines is effective and efficient when compared to ... In the field of crude oil production and associated engineering .... Industrial/Mechanical Systems, Joen Printing and.

  11. 75 FR 5536 - Pipeline Safety: Control Room Management/Human Factors, Correction

    Science.gov (United States)

    2010-02-03

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration 49 CFR Parts...: Control Room Management/Human Factors, Correction AGENCY: Pipeline and Hazardous Materials Safety... following correcting amendments: PART 192--TRANSPORTATION OF NATURAL AND OTHER GAS BY PIPELINE: MINIMUM...

  12. Method of cleaning pipeline in control rod drive

    International Nuclear Information System (INIS)

    Baba, Mikiya.

    1993-01-01

    A step of filtering cleaning water by a provisional filter unit and a step of returning filtered cleaning water to a provisional tank are disposed. That is, purified water is stored in the provisional tank and it is sucked by a driving pump under pressure by way of a suction filter into the pipelines in a control rod drive system to clean them. Purified water after the cleaning is filtered by the provisional filter unit and returned to the provisional tank by way of provisional pipelines to form a closed loop. A great amount of purified water to be used is no more necessary by thus changing the water passing cleaning method to the recycling cleaning method, which moderate influences on other steps using purified water and ensure a cleaning step for pipelines in a CRD system, in addition, save the steps for plant construction greatly. (N.H.)

  13. Reconfigurable pipelined sensing for image-based control

    NARCIS (Netherlands)

    Medina, R.; Stuijk, S.; Goswami, D.; Basten, T.

    2016-01-01

    Image-based control systems are becoming common in domains such as robotics, healthcare and industrial automation. Coping with a long sample period because of the latency of the image processing algorithm is an open challenge. Modern multi-core platforms allow to address this challenge by pipelining

  14. Pipeline heating method based on optimal control and state estimation

    Energy Technology Data Exchange (ETDEWEB)

    Vianna, F.L.V. [Dept. of Subsea Technology. Petrobras Research and Development Center - CENPES, Rio de Janeiro, RJ (Brazil)], e-mail: fvianna@petrobras.com.br; Orlande, H.R.B. [Dept. of Mechanical Engineering. POLI/COPPE, Federal University of Rio de Janeiro - UFRJ, Rio de Janeiro, RJ (Brazil)], e-mail: helcio@mecanica.ufrj.br; Dulikravich, G.S. [Dept. of Mechanical and Materials Engineering. Florida International University - FIU, Miami, FL (United States)], e-mail: dulikrav@fiu.edu

    2010-07-01

    In production of oil and gas wells in deep waters the flowing of hydrocarbon through pipeline is a challenging problem. This environment presents high hydrostatic pressures and low sea bed temperatures, which can favor the formation of solid deposits that in critical operating conditions, as unplanned shutdown conditions, may result in a pipeline blockage and consequently incur in large financial losses. There are different methods to protect the system, but nowadays thermal insulation and chemical injection are the standard solutions normally used. An alternative method of flow assurance is to heat the pipeline. This concept, which is known as active heating system, aims at heating the produced fluid temperature above a safe reference level in order to avoid the formation of solid deposits. The objective of this paper is to introduce a Bayesian statistical approach for the state estimation problem, in which the state variables are considered as the transient temperatures within a pipeline cross-section, and to use the optimal control theory as a design tool for a typical heating system during a simulated shutdown condition. An application example is presented to illustrate how Bayesian filters can be used to reconstruct the temperature field from temperature measurements supposedly available on the external surface of the pipeline. The temperatures predicted with the Bayesian filter are then utilized in a control approach for a heating system used to maintain the temperature within the pipeline above the critical temperature of formation of solid deposits. The physical problem consists of a pipeline cross section represented by a circular domain with four points over the pipe wall representing heating cables. The fluid is considered stagnant, homogeneous, isotropic and with constant thermo-physical properties. The mathematical formulation governing the direct problem was solved with the finite volume method and for the solution of the state estimation problem

  15. Research on the Numerical Simulation of Sleeper in the Pipeline Global Buckling Controlling Practice

    Directory of Open Access Journals (Sweden)

    Liu Wen-Bin

    2017-01-01

    Full Text Available This paper analyzed the lateral buckling of pipelines located in Western Africa with ABAQUS software. The application of sleepers in practice is explored to guide the pipeline buckling controlling design.

  16. Human Factors Analysis of Pipeline Monitoring and Control Operations: Final Technical Report

    Science.gov (United States)

    2008-11-26

    The purpose of the Human Factors Analysis of Pipeline Monitoring and Control Operations project was to develop procedures that could be used by liquid pipeline operators to assess and manage the human factors risks in their control rooms that may adv...

  17. Crystallographic texture control helps improve pipeline steel resistance to hydrogen-induced cracking

    Energy Technology Data Exchange (ETDEWEB)

    Caleyo, F; Hallen, J M; Herrera, O; Venegas, V [ESIQIE, Instituto Politecnico Nacional, Mexico, (Mexico); Baudin, T [Universite de Paris Sud, Orsay, (France)

    2010-07-01

    The resistance to HIC of sour service pipeline steels has been improved through several strategies but none have proven to be totally efficient in the preservation of HIC in difficult operating conditions. The crystallographic texture plays a significant role in determining the behavior of HIC in pipeline steels. The present study tried to prove that crystallographic texture control, through warm rolling schedules, helps improve pipeline steel resistance to HIC. Several samples of an API 5L X52 grade pipeline steel were produced using different thermomechanical processes (austenization, controlled rolling and recrystallization). These samples were subjected to cathodic charging. Scanning electron microscopy and automated FEG/EBSD were used to perform metallographic inspections and to collect microstructure data. The results showed that the strong y fiber texture significantly reduces or even prevents the HIC damage. It is possible to improve the HIC resistance of pipeline steels using crystallography texture control and grain boundary engineering.

  18. Drive Control System for Pipeline Crawl Robot Based on CAN Bus

    Energy Technology Data Exchange (ETDEWEB)

    Chen, H J [Department of Electrical Engineering, Harbin Institute of Technology Harbin, Heilongjiang, 150001 (China); Gao, B T [Department of Electrical Engineering, Harbin Institute of Technology Harbin, Heilongjiang, 150001 (China); Zhang, X H [Department of Electrical Engineering, Harbin Institute of Technology Harbin, Heilongjiang, 150001 (China); Deng, Z Q [School of Mechanical Engineering, Harbin Institute of Technology Harbin, Heilongjiang, 150001 (China)

    2006-10-15

    Drive control system plays important roles in pipeline robot. In order to inspect the flaw and corrosion of seabed crude oil pipeline, an original mobile pipeline robot with crawler drive unit, power and monitor unit, central control unit, and ultrasonic wave inspection device is developed. The CAN bus connects these different function units and presents a reliable information channel. Considering the limited space, a compact hardware system is designed based on an ARM processor with two CAN controllers. With made-to-order CAN protocol for the crawl robot, an intelligent drive control system is developed. The implementation of the crawl robot demonstrates that the presented drive control scheme can meet the motion control requirements of the underwater pipeline crawl robot.

  19. Drive Control System for Pipeline Crawl Robot Based on CAN Bus

    International Nuclear Information System (INIS)

    Chen, H J; Gao, B T; Zhang, X H; Deng, Z Q

    2006-01-01

    Drive control system plays important roles in pipeline robot. In order to inspect the flaw and corrosion of seabed crude oil pipeline, an original mobile pipeline robot with crawler drive unit, power and monitor unit, central control unit, and ultrasonic wave inspection device is developed. The CAN bus connects these different function units and presents a reliable information channel. Considering the limited space, a compact hardware system is designed based on an ARM processor with two CAN controllers. With made-to-order CAN protocol for the crawl robot, an intelligent drive control system is developed. The implementation of the crawl robot demonstrates that the presented drive control scheme can meet the motion control requirements of the underwater pipeline crawl robot

  20. Transient flow assurance for determination of operational control of heavy oil pipelines

    Energy Technology Data Exchange (ETDEWEB)

    Cabrejo, Victor [TransCanada Pipelines Ltd, (Canada); Mohitpour, Mo [Tempsys Pipeline Solutions Inc., (Canada)

    2010-07-01

    Pipeline transmission systems have been designed traditionally using steady state simulations. Steady state simulation provided sufficient values for simple systems, but is limited in dealing with surges in flow rates, loss of facilities and facility operation. A dynamic approach is required to test the capacity of a system for various fluids. This paper investigated the use of transient analysis of liquid pipelines in order to improve the design of these pipelines and to achieve operational benefits. The transient method and its use are discussed. Dynamic analysis was applied to the Keystone Pipeline Project. The purpose of the study was first to determine the system capacity and data for transportation of Heavy DilBit, and then to implement batch transportation of a volume of synthetic crude oil. It was found that the use of transient modeling in design and operational assessment of a liquid pipeline ensures system capability, control, safety and integrity.

  1. Real Time Implementation of Incremental Fuzzy Logic Controller for Gas Pipeline Corrosion Control

    Directory of Open Access Journals (Sweden)

    Gopalakrishnan Jayapalan

    2014-01-01

    Full Text Available A robust virtual instrumentation based fuzzy incremental corrosion controller is presented to protect metallic gas pipelines. Controller output depends on error and change in error of the controlled variable. For corrosion control purpose pipe to soil potential is considered as process variable. The proposed fuzzy incremental controller is designed using a very simple control rule base and the most natural and unbiased membership functions. The proposed scheme is tested for a wide range of pipe to soil potential control. Performance comparison between the conventional proportional integral type and proposed fuzzy incremental controller is made in terms of several performance criteria such as peak overshoot, settling time, and rise time. Result shows that the proposed controller outperforms its conventional counterpart in each case. Designed controller can be taken in automode without waiting for initial polarization to stabilize. Initial startup curve of proportional integral controller and fuzzy incremental controller is reported. This controller can be used to protect any metallic structures such as pipelines, tanks, concrete structures, ship, and offshore structures.

  2. Using the direct current voltage gradient technology as a quality control tool during construction of new pipelines

    CSIR Research Space (South Africa)

    Masilela, Z

    1998-06-01

    Full Text Available pipelines. This technique is now increasingly gaining popularity as a good quality control tool when used on newly laid pipelines to detect coating damage, most of which could be attributed to construction work. On a recently built 50 km long gas pipeline...

  3. A new design approach for control circuits of pipelined single-flux-quantum microprocessors

    International Nuclear Information System (INIS)

    Yamanashi, Y; Akimoto, A; Yoshikawa, N; Tanaka, M; Kawamoto, T; Kamiya, Y; Fujimaki, A; Terai, H; Yorozu, S

    2006-01-01

    A novel method of design for controllers of pipelined microprocessors using single-flux-quantum (SFQ) logic has been proposed. The proposed design approach is based on one hot encoding and is very suitable for designing a finite state machine using SFQ logic circuits, where each internal state of the microprocessor is represented by a flip-flop. In this approach, decoding of the internal state can be performed instantaneously, in contrast to the case in the conventional method using a binary state register. Moreover, pipelining is effectively implemented without increasing the circuit size because no pipeline registers are required in the one hot encoding. By using this method, we have designed a controller for our new SFQ microprocessors, which employs pipelining. The number of Josephson junctions of the newly designed controller is 1067, while the previous version without pipelining contains 1721 Josephson junctions. These results indicate that the proposed design approach is very effective for pipelined SFQ microprocessors. We have implemented a new controller using the NEC 2.5 kA cm -2 Nb standard process and confirmed its correct operation experimentally

  4. Testing device for pipeline groups and control method for testing device

    International Nuclear Information System (INIS)

    Naito, Shinji; Kajiyama, Shigeru; Takahashi, Fuminobu; Tsuchida, Kenji; Tachibana, Yukio; Shigehiro, Katsuya; Mahara, Yoichi.

    1995-01-01

    The device of the present invention comprises a testing device main body disposed to a rail, a movable mechanism positioning from a reference point, a circumferential direction scanning mechanism, an axial direction scanning mechanism, a posture control mechanism, and a testing probe. Upon testing of pipelines, the detection device main body and auxiliary members are moved from a reference point previously set on a rail for numerical control toward pipelines to be tested in a state where the axial direction scanning mechanism and the testing probe are suspended in the axial direction. The testing is conducted by controlling the position of the testing probe in the axial direction of the pipeline by means of the axial direction scanning mechanism, and scanning the testing probe to the outer circumference of the pipeline along the circumferential track by way of the circumferential direction scanning mechanism. The device can be extremely reduced in the thickness, and can be moved with no interference with pipelines and other obstacles by remote operation even under such undesired condition as the pipelines being crowded, so that non-destructive testing can be conducted accurately. (N.H.)

  5. Coordinated Formation Control of Multiple Autonomous Underwater Vehicles for Pipeline Inspection

    Directory of Open Access Journals (Sweden)

    Xianbo Xiang

    2010-02-01

    Full Text Available This paper addresses the control problem of inspecting underwater pipeline on the seabed, with coordinated multiple autonomous underwater vehicles in a formation. Based on the leader-follower strategy, the dedicated nonlinear path following controller is rigorously built on Lyapunov-based design, driving a fleet of vehicles onto assigned parallel paths elevated and offset from the underwater pipeline, while keeping a triangle formation to capture complete 3D images for inspection. Due to the spatial-temporal decoupling characteristics of individual path following controller, the velocities of the followers can be adapted in the coordinated control level, only relying on the information of generalized along-path length from the leader, in order to build the desired formation. Thus, the communication variable broadcast from the leader is kept to a minimum, which is feasible under the severely constraints of acoustic communication bandwidth. Simulation results illustrate the efficiency of coordinated formation controller proposed for underwater pipeline inspection.

  6. 76 FR 35130 - Pipeline Safety: Control Room Management/Human Factors

    Science.gov (United States)

    2011-06-16

    ...: Control Room Management/Human Factors AGENCY: Pipeline and Hazardous Materials Safety Administration... the Control Room Management/Human Factors regulations in order to realize the safety benefits sooner... FR 5536). By this amendment to the Control Room Management/Human Factors (CRM) rule, an operator must...

  7. 75 FR 69912 - Pipeline Safety: Control Room Management/Human Factors

    Science.gov (United States)

    2010-11-16

    ... 192 and 195 [Docket ID PHMSA-2007-27954] RIN 2137-AE64 Pipeline Safety: Control Room Management/Human... Control Room Management/Human Factors rule at 49 CFR 192.631 and 195.446. The NPRM proposes to expedite... rule and to engage in open discussions with the agency at PHMSA's Control Room Management...

  8. A nuclear on-line sensor for continuous control of vanadium content in oil pipelines

    International Nuclear Information System (INIS)

    Rizk, R.A.M.

    1989-01-01

    Trace amounts of vanadium in crude oil and in heavy distillate fuels are very harmful due to their corrosive action. Thus the necessity arises for continuous control of the vanadium content in oil pipelines. Moreover, the development of a nuclear on-line sensor that can continuously analyze the vanadium content in oil pipelines may lead to a better control of processing operations. In this paper a feasibility study for on-line analysis of vanadium in crude oil by means of neutron activation analysis is presented. (author)

  9. Pipeline integrity management

    Energy Technology Data Exchange (ETDEWEB)

    Guyt, J.; Macara, C.

    1997-12-31

    This paper focuses on some of the issues necessary for pipeline operators to consider when addressing the challenge of managing the integrity of their systems. Topics are: Definition; business justification; creation and safeguarding of technical integrity; control and deviation from technical integrity; pipelines; pipeline failure assessment; pipeline integrity assessment; leak detection; emergency response. 6 figs., 3 tabs.

  10. Multi-level access control in the data pipeline of the international supply chain system

    NARCIS (Netherlands)

    Pruksasri, P.; Berg, J. van den; Hofman, W.; Daskapan, S.

    2013-01-01

    The Seamless Integrated Data Pipeline system was proposed to the European Union in order to overcome the information quality shortcomings of the current international supply chain information exchange systems. Next to identification and authorization of stakeholders, secure access control needs to

  11. Ballasting pipeline moving in horizontal well as method of control sticking phenomenon

    Science.gov (United States)

    Toropov, V. S.; Toropov, E. S.

    2018-05-01

    The mechanism of the phenomenon of sticking a pipeline moving in a well while pulled by the facility horizontal directional drilling is investigated. A quantitative evaluation of the force arising from sticking is given. At the same time, the working hypothesis takes a view of the combined effect of adhesion and friction interactions as the reasons that cause this phenomenon. As a measure to control the occurrence of sticking and to reduce the resistance force to movement of the pipeline in the well, several methods of ballasting the working pipeline are proposed, depending on the profile of the well and the ratio of the length of the curved sections of the inlet and outlet and the straight horizontal sections of the profile. It is shown that for crossings, which profile contains an extended horizontal section, it is possible to partially fill the pipeline with water to achieve zero buoyancy, and for crossings with curvature along the entire profile, the ballasting efficiency will be minimal.

  12. Pipeline integrity management: integration of geotechnical and mechanical assessment to control potential risks due to external forces

    Energy Technology Data Exchange (ETDEWEB)

    Malpartida Moya, John E.; Sota, Giancarlo Massucco de la; Seri, Walter [Compania Operadora de Gas del Amazonas, Lima (Peru)

    2009-07-01

    Every pipeline integrity management system evaluates and controls various threats. On pipelines which have particular characteristics as it is the case of the Andean pipelines and pipelines crossing jungles, one of the main threats are the external forces. Even, this threat causes a greater number of failures than other threats like corrosion or the third part damage. Facing this situation, the pipeline integrity management system of TgP has achieved an important development in the use and suitable handling of the information provided by diverse techniques of pipeline mechanical inspection and geotechnical inspection of the right-of-way (ROW). This document presents our methodology, which interrelate information of the in-line inspection, information of geotechnical inspections of the ROW, instrumentation (Strain Gages), topographic monitoring, among others. All this information is supported in a Geographic Information System (GIS) which allows us to integrate the information. By means of the pipeline integrity management system we control potential risks due to external forces, we have been able to act before events become critical, with no occurrence of failures. This system allows us simultaneously to optimize efforts and preserve the mechanical integrity of our pipelines, not producing neither personal nor environmental nor economical affectation. (author)

  13. The Corrosion control in the Bolivia-Brazil Gas Pipeline; O controle da corrosao no Gasoduto Bolivia-Brasil

    Energy Technology Data Exchange (ETDEWEB)

    Coelho, Jorge Fernando Pereira [TBG - Transportadora Brasileira Gasoduto Bolivia Brasil S.A., Rio de Janeiro, RJ (Brazil)

    2003-07-01

    This paper presents the techniques and procedures adopted for the corrosion control of the Bolivia-Brazil Gas Pipeline. In buried pipes, the corrosion process may occur on the external surface in contact with the surrounding soil as well on the internal surface in contact with the conveyed fluid, being necessary the simultaneous mitigation of the both processes. (author)

  14. Microstructural changes after control rolling and interrupted accelerated cooling simulations in pipeline steel

    Energy Technology Data Exchange (ETDEWEB)

    Sanchez-Mourino, Nuria; Petrov, Roumen [Department of Materials Science and Engineering, Ghent University, Technologiepark Zwijnaarde 903, B-9052 Ghent (Belgium); Bae, Jin-Ho; Kim, Kisoo [Sheet Products and Process Research Group, POSCO, Jeonnam, 545-090 (Korea, Republic of); Kestens, Leo A.I. [Department of Materials Science and Engineering, Ghent University, Technologiepark Zwijnaarde 903, B-9052 Ghent (Belgium); Department of Materials Science and Engineering, Delft University of Technology, Mekelweg 2, 2628 CD, Delft (Netherlands)

    2011-04-15

    The {gamma}-{alpha} transformation and final microstructure in pipeline steel was studied by carrying out a number of physical simulations of industrial hot rolling schedules. Particularly, the effect of the reheating temperature, deformation and cooling parameters on the transformation temperatures and final grain size were considered with a goal to obtain an appropriate thermo-mechanical processing route which will generate appropriate microstructures for pipeline applications. The CCT diagram of the steel was derived experimentally by means of dilatometric tests. Hot torsion experiments were applied in a multi-deformation cycle at various temperatures in the austenite region to simulate industrial rolling schedules. By variation of the reheating temperature, equivalent strain, and accelerated cooling, different types of microstructures were obtained. It was found that the deformation increases the transformation temperatures whereas the higher cooling rates after deformation decrease them. Post-deformation microstructure consists of fine bainitic-ferrite grains with dispersed carbides and small amount of dispersed martensite/austenite islands which can be controlled by varying the reheating temperature, deformation and post-deformation cooling. The detailed microstructure characteristics obtained from the present work could be used to optimize the mechanical properties, strength and toughness of pipeline steel grades by an appropriate control of the thermo-mechanical processing. (Copyright copyright 2011 WILEY-VCH Verlag GmbH and Co. KGaA, Weinheim)

  15. Research of fuel temperature control in fuel pipeline of diesel engine using positive temperature coefficient material

    Directory of Open Access Journals (Sweden)

    Xiaolu Li

    2016-01-01

    Full Text Available As fuel temperature increases, both its viscosity and surface tension decrease, and this is helpful to improve fuel atomization and then better combustion and emission performances of engine. Based on the self-regulated temperature property of positive temperature coefficient material, this article used a positive temperature coefficient material as electric heating element to heat diesel fuel in fuel pipeline of diesel engine. A kind of BaTiO3-based positive temperature coefficient material, with the Curie temperature of 230°C and rated voltage of 24 V, was developed, and its micrograph and element compositions were also analyzed. By the fuel pipeline wrapped in six positive temperature coefficient ceramics, its resistivity–temperature and heating characteristics were tested on a fuel pump bench. The experiments showed that in this installation, the surface temperature of six positive temperature coefficient ceramics rose to the equilibrium temperature only for 100 s at rated voltage. In rated power supply for six positive temperature coefficient ceramics, the temperature of injection fuel improved for 21°C–27°C within 100 s, and then could keep constant. Using positive temperature coefficient material to heat diesel in fuel pipeline of diesel engine, the injection mass per cycle had little change, approximately 0.3%/°C. This study provides a beneficial reference for improving atomization of high-viscosity liquids by employing positive temperature coefficient material without any control methods.

  16. Treatment screening for internal corrosion control of PETROBRAS oil pipelines; Selecao de tratamento para controle da corrosao interna de oleodutos da PETROBRAS

    Energy Technology Data Exchange (ETDEWEB)

    Andrade, Cynthia de Azevedo; Muller, Eduardo Gullo [PETROBRAS, Rio de Janeiro, RJ (Brazil). Centro de Pesquisas; Antunes, Warlley Ligorio; Shioya, Nilce Hiromi; Salvador, Angelica Dias [PETROBRAS, RJ (Brazil). Unidade de Negocios da Bacia de Campos

    2005-07-01

    The use of corrosion inhibitors is spread out in oil and gas industry and is the most common methodology to control pipeline internal corrosion. However, their effectiveness depends on the pipeline material, inhibitor composition, flow type and scale characteristics. When a pipeline has heavy scale deposits, thick bacterial biofilm, or oxygen contamination, the corrosion control via filmic inhibitors is not effective. So, the only way to control internal corrosion of an oil pipeline is to primary identifies the corrosive agent and the main corrosion mechanism. The monitoring of the inhibitor efficiency and the determination of minimal residual concentration to prevent corrosion, are also fundamental. In this paper, is presented the criteria used to identify the main corrosion mechanism of oil pipelines, the treatment proposed in each case and the techniques employed in real time corrosion monitoring. (author)

  17. Pipeline Analyzer using the Fractional Fourier Transform for Engine Control and Satellites Data

    Directory of Open Access Journals (Sweden)

    Darian M. Onchiș

    2011-09-01

    Full Text Available The aim of this paper is to present an algorithm for computing the fractional Fourier transform integrated into the pipeline of processing multi-variate and distributed data recorded by the engine control unit (ECU of a car and its satellites. The role of this transform is vital in establishing a time-variant filter and therefore it must be computed in a fast way. But for large scale time series, the application of the discrete fractional Fourier transform involves the computations of a large number of Hermite polynomials of increasingly order. The parallel algorithm presented will optimally compute the discrete Fourier-type transform for any given angle.

  18. Pipeline engineering

    CERN Document Server

    Liu, Henry

    2003-01-01

    PART I: PIPE FLOWSINTRODUCTIONDefinition and Scope Brief History of PipelinesExisting Major PipelinesImportance of PipelinesFreight (Solids) Transport by PipelinesTypes of PipelinesComponents of PipelinesAdvantages of PipelinesReferencesSINGLE-PHASE INCOMPRESSIBLE NEWTONIAN FLUIDIntroductionFlow RegimesLocal Mean Velocity and Its Distribution (Velocity Profile)Flow Equations for One-Dimensional AnalysisHydraulic and Energy Grade LinesCavitation in Pipeline SystemsPipe in Series and ParallelInterconnected ReservoirsPipe NetworkUnsteady Flow in PipeSINGLE-PHASE COMPRESSIBLE FLOW IN PIPEFlow Ana

  19. Corrosion Prevention And Control In High Pressure Oil And Gas Transmission Pipelines

    International Nuclear Information System (INIS)

    Hafez, M.T.; Radwan, M.H.; Jones, D.G.

    2004-01-01

    At the start of the 1990s there were concerns over the increasing threat of corrosion to the integrity of high-pressure oil and gas transmission pipelines. For example: corrosion was the major cause of reportable incidents in North America (1]. Corrosion was the major cause of pipeline failure in the Gulf of Mexico [2]. Corrosion in a North American onshore oil pipeline had required over $1 billion in repairs(3]. Internal corrosion along the complete length of pipelines had resulted in replacement[4] . However, the worldwide published failure statistics indicate that the incidents of corrosion are not increasing year on year(5-9]. Indeed, CONCA WE[8,9] statistics (for pipelines In Western Europe) show that the failure rate from corrosion (the most likely failure mode with increasing age) has not increased with pipeline age (Figure 1). In fact the statistics for gas pipelines in Europe

  20. Pipeline control support system, 'pipe navigation'; Kanro kanri shien system 'kannabi'

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2000-01-10

    'Pipe navigation' is a pipeline control support system which employs GIS/GPS (geographic information system/global positioning system) technology in controlling information of water pipeline and incidental facilities, using a pen note/personal computer as the operating base. These pen computers can be carried to the spot and used in displaying pipeline/incidental equipment and retrieving related information. The main features as follows:(1) Memo preparation is possible at an arbitrary place with handwriting ease. The memo data so prepared can be taken in other terminals and shared.(2) Communication with remote places is possible by transmitting drawings, prepared memo data, etc., as in facsimile (3) Confirmation of the present position and navigation are possible (GPS function), demonstrating power in a restoration work at the time of earthquake for example.(4) Inputting and maintenance of each facility information are possible through the data input support function even by general users easily. (translated by NEDO)

  1. The Vulnerability Formation Mechanism and Control Strategy of the Oil and Gas Pipeline City

    Science.gov (United States)

    Chen, Y. L.; Han, L.

    2017-12-01

    Most of the pipelines of oil and gas pipelines in our country have been for more than 25 years. These pipes are buried underground and was difficult to daily test. In addition, it was vulnerable to environmental, corrosion and natural disasters, So there is a hidden nature of accidents. The rapid development of urbanization, population accumulation, dense building and insufficient safety range are all the reasons for the frequent accidents of oil and gas pipelines. Therefore, to appraise and know the safe condition of the city various regions oil and gas pipelines is vital significant. In order to ensure the safety of oil and gas pipeline city, this paper defines the connotation of oil and gas pipeline city vulnerability according to the previous research on vulnerability. Then from three perspectives of environment, structure and behavior, based on the analytical paradigm of “structure—vulnerability conduct—performance” about oil and gas, the influential indicators of vulnerable oil and gas pipelines were analysed, the vulnerability mechanism framework of Oil and gas pipeline city was also constructed. Finally, the paper proposed the regulating strategy of the vulnerability of the oil and gas pipeline city to decrease its vulnerability index, which can be realize the city’s vulnerability evaluation and provides new ideas for the sustainable development of the city.

  2. 77 FR 74275 - Pipeline Safety: Information Collection Activities

    Science.gov (United States)

    2012-12-13

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No.... These regulations require operators of hazardous liquid pipelines and gas pipelines to develop and... control room. Affected Public: Operators of both natural gas and hazardous liquid pipeline systems. Annual...

  3. 77 FR 27279 - Pipeline Safety: Information Collection Activities

    Science.gov (United States)

    2012-05-09

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No... collections relate to the pipeline integrity management requirements for gas transmission pipeline operators... Management in High Consequence Areas Gas Transmission Pipeline Operators. OMB Control Number: 2137-0610...

  4. 77 FR 46155 - Pipeline Safety: Information Collection Activities

    Science.gov (United States)

    2012-08-02

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No... collections relate to the pipeline integrity management requirements for gas transmission pipeline operators... Management in High Consequence Areas Gas Transmission Pipeline Operators. OMB Control Number: 2137-0610...

  5. Bridging ImmunoGenomic Data Analysis Workflow Gaps (BIGDAWG): An integrated case-control analysis pipeline.

    Science.gov (United States)

    Pappas, Derek J; Marin, Wesley; Hollenbach, Jill A; Mack, Steven J

    2016-03-01

    Bridging ImmunoGenomic Data-Analysis Workflow Gaps (BIGDAWG) is an integrated data-analysis pipeline designed for the standardized analysis of highly-polymorphic genetic data, specifically for the HLA and KIR genetic systems. Most modern genetic analysis programs are designed for the analysis of single nucleotide polymorphisms, but the highly polymorphic nature of HLA and KIR data require specialized methods of data analysis. BIGDAWG performs case-control data analyses of highly polymorphic genotype data characteristic of the HLA and KIR loci. BIGDAWG performs tests for Hardy-Weinberg equilibrium, calculates allele frequencies and bins low-frequency alleles for k×2 and 2×2 chi-squared tests, and calculates odds ratios, confidence intervals and p-values for each allele. When multi-locus genotype data are available, BIGDAWG estimates user-specified haplotypes and performs the same binning and statistical calculations for each haplotype. For the HLA loci, BIGDAWG performs the same analyses at the individual amino-acid level. Finally, BIGDAWG generates figures and tables for each of these comparisons. BIGDAWG obviates the error-prone reformatting needed to traffic data between multiple programs, and streamlines and standardizes the data-analysis process for case-control studies of highly polymorphic data. BIGDAWG has been implemented as the bigdawg R package and as a free web application at bigdawg.immunogenomics.org. Copyright © 2015 American Society for Histocompatibility and Immunogenetics. Published by Elsevier Inc. All rights reserved.

  6. Liquid Pipeline Operator's Control Room Human Factors Risk Assessment and Management Guide

    Science.gov (United States)

    2008-11-26

    The purpose of this guide is to document methodologies, tools, procedures, guidance, and instructions that have been developed to provide liquid pipeline operators with an efficient and effective means of managing the human factors risks in their con...

  7. EVELOPMENT OF AN ENVIRONMENTALLY BENIGN MICROBIAL INHIBITOR TO CONTROL INTERNAL PIPELINE CORROSION

    Energy Technology Data Exchange (ETDEWEB)

    Bill W. Bogan; Wendy R. Sullivan; Kristine M. H. Cruz; Kristine L. Lowe; John J. Kilbane II

    2004-04-30

    The overall program objective is to develop and evaluate environmentally benign agents or products that are effective in the prevention, inhibition, and mitigation of microbially influenced corrosion (MIC) in the internal surfaces of metallic natural gas pipelines. The goal is to develop one or more environmentally benign (a.k.a. ''green'') products that can be applied to maintain the structure and dependability of the natural gas infrastructure. Previous testing of pepper extracts resulted in preliminary data indicating that some pepper extracts inhibit the growth of some corrosion-associated microorganisms. This quarter additional tests were performed to more specifically investigate the ability of three pepper extracts to inhibit the growth, and to influence the metal corrosion caused by two microbial species: Desulfovibrio vulgaris, and Comomonas denitrificans. All three pepper extracts rapidly killed Desulfovibrio vulgaris, but did not appear to inhibit Comomonas denitrificans. While corrosion rates were at control levels in experiments with Desulfovibrio vulgaris that received pepper extract, corrosion rates were increased in the presence of Comomonas denitrificans plus pepper extract. Further testing with a wider range of pure bacterial cultures, and more importantly, with mixed bacterial cultures should be performed to determine the potential effectiveness of pepper extracts to inhibit MIC.

  8. DEVELOPMENT OF AN ENVIRONMENTALLY BENIGN MICROBIAL INHIBITOR TO CONTROL INTERNAL PIPELINE CORROSION

    Energy Technology Data Exchange (ETDEWEB)

    Bill W. Bogan; Brigid M. Lamb; John J. Kilbane II

    2004-10-30

    The overall program objective is to develop and evaluate environmentally benign agents or products that are effective in the prevention, inhibition, and mitigation of microbially influenced corrosion (MIC) in the internal surfaces of metallic natural gas pipelines. The goal is to develop one or more environmentally benign (a.k.a. ''green'') products that can be applied to maintain the structure and dependability of the natural gas infrastructure. Previous testing indicated that the growth, and the metal corrosion caused by pure cultures of sulfate reducing bacteria were inhibited by hexane extracts of some pepper plants. This quarter tests were performed to determine if chemical compounds other than pepper extracts could inhibit the growth of corrosion-associated microbes and to determine if pepper extracts and other compounds can inhibit corrosion when mature biofilms are present. Several chemical compounds were shown to be capable of inhibiting the growth of corrosion-associated microorganisms, and all of these compounds limited the amount of corrosion caused by mature biofilms to a similar extent. It is difficult to control corrosion caused by mature biofilms, but any compound that disrupts the metabolism of any of the major microbial groups present in corrosion-associated biofilms shows promise in limiting the amount/rate of corrosion.

  9. Recent developments in pipeline welding practice

    Energy Technology Data Exchange (ETDEWEB)

    1979-01-01

    Fourteen chapters are included: overview of pipeline welding systems and quality assurance, CRC automatic welding system, H.C. Price Co. automatic welding system, semi-automatic MIG-welding process, partial penetration welding of steel pipes for gas distribution, construction procedures and quality control in offshore pipeline construction, welding in repair and maintenance of gas transmission pipelines, British Gas studies of welding on pressurized gas transmission pipelines, hot tapping pipelines, underwater welding for offshore pipelines and associated equipment, radial friction welding, material composition vs weld properties, review of NDT of pipeline welds, and safety assurance in pipeline construction. A bibliography of approximately 150 references is included, arranged according to subject and year.

  10. On-line, real-time monitoring for petrochemical and pipeline process control applications

    Energy Technology Data Exchange (ETDEWEB)

    Kane, Russell D.; Eden, D.C.; Cayard, M.S.; Eden, D.A.; Mclean, D.T. [InterCorr International, Inc., 14503 Bammel N. Houston, Suite 300, Houston Texas 77014 (United States); Kintz, J. [BASF Corporation, 602 Copper Rd., Freeport, Texas 77541 (United States)

    2004-07-01

    Corrosion problems in petroleum and petrochemical plants and pipeline may be inherent to the processes, but costly and damaging equipment losses are not. With the continual drive to increase productivity, while protecting both product quality, safety and the environment, corrosion must become a variable that can be continuously monitored and assessed. This millennium has seen the introduction of new 'real-time', online measurement technologies and vast improvements in methods of electronic data handling. The 'replace when it fails' approach is receding into a distant memory; facilities management today is embracing new technology, and rapidly appreciating the value it has to offer. It has offered the capabilities to increase system run time between major inspections, reduce the time and expense associated with turnaround or in-line inspections, and reduce major upsets which cause unplanned shut downs. The end result is the ability to know on a practical basis of how 'hard' facilities can be pushed before excessive corrosion damage will result, so that process engineers can understand the impact of their process control actions and implement true asset management. This paper makes reference to use of a online, real-time electrochemical corrosion monitoring system - SmartCET 1- in a plant running a mostly organic process media. It also highlights other pertinent examples where similar systems have been used to provide useful real-time information to detect system upsets, which would not have been possible otherwise. This monitoring/process control approach has operators and engineers to see, for the first time, changes in corrosion behavior caused by specific variations in process parameters. Process adjustments have been identified that reduce corrosion rates while maintaining acceptable yields and quality. The monitoring system has provided a new window into the chemistry of the process, helping chemical engineers improve their process

  11. DEVELOPMENT OF AN ENVIRONMENTALLY BENIGN MICROBIAL INHIBITOR TO CONTROL INTERNAL PIPELINE CORROSION

    Energy Technology Data Exchange (ETDEWEB)

    Bill W. Bogan; Brigid M. Lamb; Gemma Husmillo; Kristine Lowe; J. Robert Paterek; John J. Kilbane II

    2004-12-01

    The overall program objective is to develop and evaluate environmentally benign agents or products that are effective in the prevention, inhibition, and mitigation of microbially influenced corrosion (MIC) in the internal surfaces of metallic natural gas pipelines. The goal is to develop one or more environmentally benign (a.k.a. ''green'') products that can be applied to maintain the structure and dependability of the natural gas infrastructure. Various chemicals that inhibit the growth and/or the metabolism of corrosion-associated microbes such as sulfate reducing bacteria, denitrifying bacteria, and methanogenic bacteria were evaluated to determine their ability to inhibit corrosion in experiments utilizing pure and mixed bacterial cultures, and planktonic cultures as well as mature biofilms. Planktonic cultures are easier to inhibit than mature biofilms but several compounds were shown to be effective in decreasing the amount of metal corrosion. Of the compounds tested hexane extracts of Capsicum pepper plants and molybdate were the most effective inhibitors of sulfate reducing bacteria, bismuth nitrate was the most effective inhibitor of nitrate reducing bacteria, and 4-((pyridine-2-yl)methylamino)benzoic acid (PMBA) was the most effective inhibitor of methanogenic bacteria. All of these compounds were demonstrated to minimize corrosion due to MIC, at least in some circumstances. The results obtained in this project are consistent with the hypothesis that any compound that disrupts the metabolism of any of the major microbial groups present in corrosion-associated biofilms shows promise in limiting the amount/rate of corrosion. This approach of controlling MIC by controlling the metabolism of biofilms is more environmentally benign than the current approach involving the use of potent biocides, and warrants further investigation.

  12. Assessing the efficiency of automatically controlled valves (ACV) for pipeline sectioning

    Energy Technology Data Exchange (ETDEWEB)

    Veiga, Leandro S. da; Silva, Marcos J.M. da; Leite, Joao Paulo de B.; Santos, Renata N.R. dos; Jardim, Rodrigo B.O.; Quinto, Thiago C. do [Petrobras Transporte S.A. (TRANSPETRO), Rio de Janeiro, RJ (Brazil)

    2009-07-01

    In order to mitigate the effects caused by the rupture of a gas pipeline and following ASME B 31.8 recommendations, block valves are installed in these structures. However, many transportation companies also install devices capable of infer the occurrence of an accident in a gas pipeline. The most common devices are the ones that actuate when pressure in gas pipeline reaches a low value early established (PSL) and those which close valves due to high rate of pressure drop (line-break). Line-break has the function of identifying as fast as possible the occurrence of a rupture in a gas pipeline by high rate of pressure drop in that line. Although PSL presents a later actuation when compared to the line break, it represents redundancy to the line-break system, since it is able to isolate the segment where the accident happened even if other devices or the operator had not done it before. The growing of gas pipelines transport capacity has been generated transients capable of causing an erroneous shut down of the shut down valves (SDV). The aim of this paper, therefore, is to present how the operational limits of SDV can be overcome with remote operation using SCADA System. (author)

  13. Modeling and Controlling Flow Transient in Pipeline Systems: Applied for Reservoir and Pump Systems Combined with Simple Surge Tank

    Directory of Open Access Journals (Sweden)

    Itissam ABUIZIAH

    2014-03-01

    Full Text Available When transient conditions (water hammer exist, the life expectancy of the system can be adversely impacted, resulting in pump and valve failures and catastrophic pipe rupture. Hence, transient control has become an essential requirement for ensuring safe operation of water pipeline systems. To protect the pipeline systems from transient effects, an accurate analysis and suitable protection devices should be used. This paper presents the problem of modeling and simulation of transient phenomena in hydraulic systems based on the characteristics method. Also, it provides the influence of using the protection devices to control the adverse effects due to excessive and low pressure occuring in the transient. We applied this model for two main pipeline systems: Valve and pump combined with a simple surge tank connected to reservoir. The results obtained by using this model indicate that the model is an efficient tool for water hammer analysis. Moreover, using a simple surge tank reduces the unfavorable effects of transients by reducing pressure fluctuations.

  14. Buoyed by geophysics : geophysics, just-in-time procurement help save millions on Ekwan pipeline buoyancy control

    Energy Technology Data Exchange (ETDEWEB)

    Roche, P.

    2005-09-01

    Large-diameter natural gas pipelines buried in wet muskeg have the potential to rise to the surface due to buoyancy. Until recently, the most reliable method to prevent this was to attach specially manufactured bolt-on concrete weights at closely spaced intervals. However, these weights significantly increase capital budgets by millions of dollars because each weight weighs 2,540 kg and costs $1,000. A less costly alternative for buoyancy control in shallow muskeg is for the contractor to simply dig a deeper ditch. Another option is to hold down the pipeline by polyester straps attached to screw anchors. The challenge of applying these less costly options is that heavy equipment cannot be brought to the site to determine ground conditions until after all procurement, assessment and design is completed. Engineers must therefore select a buoyancy control measure based only on air photos and possibly a few drill holes. However, air photos do not indicate the depth of muskeg. Although some muskeg areas may turn out to be thick enough to avoid buoyancy control altogether, once construction is underway, it is too late to opt for cheaper alternatives. EnCana Corporation's 24-inch Ekwan pipeline was recently constructed through a remote area of British Columbia to connect the Greater Sierra natural gas discovery to a tie-in point on Nova Gas Transmission's northwest mainline. Air photos indicated that half of the route was through muskeg. AMEC E and C Services Inc. was responsible for the engineering and management of the project. The company used a combination of geophysical techniques to learn about the ground conditions. Toboggan mounted portable equipment was hauled by snowmobiles along trails made earlier by the survey crews. Ground penetrating radar assessed the muskeg thickness. Fixed frequency electromagnetic surveys also enhanced the results of the ground penetrating radar. The number of bolt-on weights was reduced from 9,000 to 3,700, a savings of $3

  15. Component-based control of oil-gas-water mixture composition in pipelines

    Science.gov (United States)

    Voytyuk, I. N.

    2018-03-01

    The article theoretically proves the method for measuring the changes in content of oil, gas and water in pipelines; also the measurement system design for implementation thereof is discussed. An assessment is presented in connection with random and systemic errors for the future system, and recommendations for optimization thereof are presented.

  16. Studies for the requirements of automatic and remotely controlled shutoff valves on hazardous liquids and natural gas pipelines with respect to public and environmental safety

    Energy Technology Data Exchange (ETDEWEB)

    Oland, C. Barry [XCEL Engineering, Inc. (United States); Rose, Simon D. [Oak Ridge National Lab. (ORNL), Oak Ridge, TN (United States). Engineering Science and Technology Div.; Grant, Herb L. [Oak Ridge National Lab. (ORNL), Oak Ridge, TN (United States). Fabrication, Hoisting and Rigging Div.; Lower, Mark D. [Oak Ridge National Lab. (ORNL), Oak Ridge, TN (United States). Fabrication, Hoisting and Rigging Div.; Spann, Mark A. [Oak Ridge National Lab. (ORNL), Oak Ridge, TN (United States). Facility Management Div.; Kirkpatrick, John R. [Oak Ridge National Lab. (ORNL), Oak Ridge, TN (United States). Computational Sciences and Engineering Div.; Sulfredge, C. David [Oak Ridge National Lab. (ORNL), Oak Ridge, TN (United States). Computational Sciences and Engineering Div.

    2012-12-01

    This study assesses the effectiveness of block valve closure swiftness in mitigating the consequences of natural gas and hazardous liquid pipeline releases on public and environmental safety. It also evaluates the technical, operational, and economic feasibility and potential cost benefits of installing automatic shutoff valves (ASVs) and remote control valves (RCVs) in newly constructed and fully replaced transmission lines. Risk analyses of hypothetical pipeline release scenarios are used as the basis for assessing: (1) fire damage to buildings and property in Class 1, Class 2, Class 3, and Class 4 high consequence areas (HCAs) caused by natural gas pipeline releases and subsequent ignition of the released natural gas; (2) fire damage to buildings and property in HCAs designated as high population areas and other populated areas caused by hazardous liquid pipeline releases and subsequent ignition of the released propane; and (3) socioeconomic and environmental damage in HCAs caused by hazardous liquid pipeline releases of crude oil. These risk analyses use engineering principles and fire science practices to characterize thermal radiation effects on buildings and humans and to quantify the total damage cost of socioeconomic and environmental impacts. The risk analysis approach used for natural gas pipelines is consistent with risk assessment standards developed by industry and incorporated into Federal pipeline safety regulations. Feasibility evaluations for the hypothetical pipeline release scenarios considered in this study show that installation of ASVs and RCVs in newly constructed and fully replaced natural gas and hazardous liquid pipelines is technically, operationally, and economically feasible with a positive cost benefit. However, these results may not apply to all newly constructed and fully replaced pipelines because site-specific parameters that influence risk analyses and feasibility evaluations often vary significantly from one pipeline segment to

  17. Leadership Pipeline

    DEFF Research Database (Denmark)

    Elmholdt, Claus Westergård

    2012-01-01

    Artiklen analyserer grundlaget for Leadership Pipeline modellen med henblik på en vurdering af substansen bag modellen, og perspektiverne for generalisering af modellen til en dansk organisatorisk kontekst.......Artiklen analyserer grundlaget for Leadership Pipeline modellen med henblik på en vurdering af substansen bag modellen, og perspektiverne for generalisering af modellen til en dansk organisatorisk kontekst....

  18. A pipeline to determine RT-QPCR control genes for evolutionary studies: application to primate gene expression across multiple tissues.

    Directory of Open Access Journals (Sweden)

    Olivier Fedrigo

    Full Text Available Because many species-specific phenotypic differences are assumed to be caused by differential regulation of gene expression, many recent investigations have focused on measuring transcript abundance. Despite the availability of high-throughput platforms, quantitative real-time polymerase chain reaction (RT-QPCR is often the method of choice because of its low cost and wider dynamic range. However, the accuracy of this technique heavily relies on the use of multiple valid control genes for normalization. We created a pipeline for choosing genes potentially useful as RT-QPCR control genes for measuring expression between human and chimpanzee samples across multiple tissues, using published microarrays and a measure of tissue-specificity. We identified 13 genes from the pipeline and from commonly used control genes: ACTB, USP49, ARGHGEF2, GSK3A, TBP, SDHA, EIF2B2, GPDH, YWHAZ, HPTR1, RPL13A, HMBS, and EEF2. We then tested these candidate genes and validated their expression stability across species. We established the rank order of the most preferable set of genes for single and combined tissues. Our results suggest that for at least three tissues (cerebral cortex, liver, and skeletal muscle, EIF2B2, EEF2, HMBS, and SDHA are useful genes for normalizing human and chimpanzee expression using RT-QPCR. Interestingly, other commonly used control genes, including TBP, GAPDH, and, especially ACTB do not perform as well. This pipeline could be easily adapted to other species for which expression data exist, providing taxonomically appropriate control genes for comparisons of gene expression among species.

  19. Pipeline integrity handbook risk management and evaluation

    CERN Document Server

    Singh, Ramesh

    2013-01-01

    Based on over 40 years of experience in the field, Ramesh Singh goes beyond corrosion control, providing techniques for addressing present and future integrity issues. Pipeline Integrity Handbook provides pipeline engineers with the tools to evaluate and inspect pipelines, safeguard the life cycle of their pipeline asset and ensure that they are optimizing delivery and capability. Presented in easy-to-use, step-by-step order, Pipeline Integrity Handbook is a quick reference for day-to-day use in identifying key pipeline degradation mechanisms and threats to pipeline integrity. The book begins

  20. Pipeline grounding condition: A control of pipe-to-soil potential for AC interference induced corrosion reduction

    CSIR Research Space (South Africa)

    Adedeji, KB

    2017-02-01

    Full Text Available The interference effect from high voltage overhead lines on nearby metallic pipelines is a major challenge for utility owners due to the induced AC potentials on metallic pipelines. Nevertheless, numerous mitigation techniques have been proposed...

  1. DEVELOPMENT OF AN ENVIRONMENTALLY BENIGN MICROBIAL INHIBITOR TO CONTROL INTERNAL PIPELINE CORROSION

    Energy Technology Data Exchange (ETDEWEB)

    J. Robert Paterek; Gemma Husmillo

    2002-07-01

    The overall program objective is to develop and evaluate environmental benign agents or products that are effective in the prevention, inhibition, and mitigation of microbially influenced corrosion (MIC) in the internal surfaces of metallic natural gas pipelines. The goal is one or more environmental benign, a.k.a. ''green'' products that can be applied to maintain the structure and dependability of the natural gas infrastructure. Capsicum sp. extracts and pure compounds were screened for their antimicrobial activity against MIC causing bacteria. Studies on the ability of these compounds to dissociate biofilm from the substratum were conducted using microtiter plate assays. Tests using laboratory scale pipeline simulators continued. Preliminary results showed that the natural extracts possess strong antimicrobial activity being comparable to or even better than the pure compounds tested against strains of sulfate reducers. Their minimum inhibitory concentrations had been determined. It was also found that they possess bactericidal properties at minimal concentrations. Biofilm dissociation activity as assessed by microtiter plate assays demonstrated varying degrees of differences between the treated and untreated group with the superior performance of the extracts over pure compounds. Such is an indication of the possible benefits that could be obtained from these natural products. Confirmatory experiments are underway.

  2. DEVELOPMENT OF AN ENVIRONMENTALLY BENIGN MICROBIAL INHIBITOR TO CONTROL INTERNAL PIPELINE CORROSION

    Energy Technology Data Exchange (ETDEWEB)

    Kristine L. Lowe; Bill W. Bogan; Wendy R. Sullivan; Kristine Mila H. Cruz; Brigid M. Lamb; John J. Kilbane II

    2004-07-30

    The overall program objective is to develop and evaluate environmentally benign agents or products that are effective in the prevention, inhibition, and mitigation of microbially influenced corrosion (MIC) in the internal surfaces of metallic natural gas pipelines. The goal is to develop one or more environmentally benign (a.k.a. ''green'') products that can be applied to maintain the structure and dependability of the natural gas infrastructure. Previous testing indicated that the growth, and the metal corrosion caused by pure cultures of sulfate reducing bacteria were inhibited by hexane extracts of some pepper plants. This quarter tests were performed with mixed bacterial cultures obtained from natural gas pipelines. Treatment with the pepper extracts affected the growth and metabolic activity of the microbial consortia. Specifically, the growth and metabolism of sulfate reducing bacteria was inhibited. The demonstration that pepper extracts can inhibit the growth and metabolism of sulfate reducing bacteria in mixed cultures is a significant observation validating a key hypothesis of the project. Future tests to determine the effects of pepper extracts on mature/established biofilms will be performed next.

  3. Integrated natural gas pipeline control and customer service system of Gasum; Le systeme integre de controle des canalisations de gaz et de service au consommateur chez Gasum

    Energy Technology Data Exchange (ETDEWEB)

    Aho, J.; Manty, O.; Ahlnas, B. [Gasul Oy (Finland)

    2000-07-01

    Due to the rapid development of the information technology, ageing is not the only driving force for replacing old computer systems with more sophisticated ones. The Finnish natural Gas company, Gasum Oy, has recently taken into use a new control and monitoring system for natural gas pipeline. A special customer service system, developed by Gasum Oy, is closely connected to monitoring system. It provides up-to-date information to all customers of Gasum Oy. The information is layered in three confidential levels: general information, operational data and invoicing information. The system is operating interactively in confidential Extranet. Inside Gasum Oy to meet the needs of departments outside the control room, a new GID system is developed. GID is a way to present pipeline process data and its further modifications with a very user-friendly interface based on geographical map. The system is based on data warehouse architecture and it is working on company's Intranet. This makes it possible to present various secrecy level information based on user ID. Gasum's new SCADA is not only the base for operating the pipeline, but it also provides lot of vital information to other systems serving different user groups within natural gas business in Finland. (authors)

  4. 78 FR 38803 - Pipeline Safety: Information Collection Activities, Revisions to Incident and Annual Reports for...

    Science.gov (United States)

    2013-06-27

    ... Reports for Gas Pipeline Operators AGENCY: Pipeline and Hazardous Materials Safety Administration (PHMSA... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No... (OMB) Control No. 2137-0522, titled ``Incident and Annual Reports for Gas Pipeline Operators.'' PHMSA...

  5. The Role of the Bainitic Packet in Control of Impact Toughness in a Simulated CGHAZ of X90 Pipeline Steel

    Directory of Open Access Journals (Sweden)

    Bin Guo

    2016-10-01

    Full Text Available X90 pipeline steel was processed with the simulated coarse grain heat affect zone (CGHAZ thermal cycle with heat input varying from 30 kJ/cm to 60 kJ/cm, the microstructures were investigated by means of optical microscope (OM, scanning electron microscope (SEM, electron backscattering diffraction (EBSD, and transmission electron microscope (TEM, and the impact properties were evaluated from the welding thermal cycle treated samples. The results indicate that the microstructure is primarily composed of lath bainite. When decreasing the heat input, both bainite packet and block are significantly refined, and the toughness has an increased tendency due to the grain refinement. The fracture surfaces all present cleavage fracture for the samples with different heat inputs. Moreover, the average cleavage facet size for the CGHAZ is nearly equal to the average bainite packet size, and the bainitic packet boundary can strongly impede the crack propagation, indicating that the bainitic packet is the most effective unit in control of impact toughness in the simulated CGHAZ of X90 pipeline steel.

  6. Development of systems for detection, early warning, and control of pipeline leakage in drinking water distribution: a case study.

    Science.gov (United States)

    Li, Weifeng; Ling, Wencui; Liu, Suoxiang; Zhao, Jing; Liu, Ruiping; Chen, Qiuwen; Qiang, Zhimin; Qu, Jiuhui

    2011-01-01

    Water leakage in drinking water distribution systems is a serious problem for many cities and a huge challenge for water utilities. An integrated system for the detection, early warning, and control of pipeline leakage has been developed and successfully used to manage the pipeline networks in selected areas of Beijing. A method based on the geographic information system has been proposed to quickly and automatically optimize the layout of the instruments which detect leaks. Methods are also proposed to estimate the probability of each pipe segment leaking (on the basis of historic leakage data), and to assist in locating the leakage points (based on leakage signals). The district metering area (DMA) strategy is used. Guidelines and a flowchart for establishing a DMA to manage the large-scale looped networks in Beijing are proposed. These different functions have been implemented into a central software system to simplify the day-to-day use of the system. In 2007 the system detected 102 non-obvious leakages (i.e., 14.2% of the total detected in Beijing) in the selected areas, which was estimated to save a total volume of 2,385,000 m3 of water. These results indicate the feasibility, efficiency and wider applicability of this system.

  7. Inhibitor selection for internal corrosion control of pipelines: experience with field monitoring and measurement

    Energy Technology Data Exchange (ETDEWEB)

    Demoz, A.; Michaelian, K.H.; Donini, J. [Natural Resources Canada, CANMET Western Research Centre, Devon, AB (Canada); Papavinasam, S.; Revie, R.W. [Natural Resources Canada, CANMET Materials Technology Laboratory, Ottawa, ON (Canada)

    1999-07-01

    A loop of pipe consisting of pipe segments of 3 inches, 6 inches and 10 inches that could take the full flow of a production well was designed, constructed and put in-line close to a wellhead. The loop was able to simulate multiphase pipelines and had ports for coupons, some of which were used for electrochemical monitoring. Various techniques including electrochemical impedance spectroscopy (EIS), electrochemical noise (ECN), and linear polarization resistance (LPR) were employed, all of which gave corrosion rates that depended on the position of the coupons inside the loop (increasing from top to bottom, reflecting the media and flow to which coupons were exposed in a multiphase producing well). Results indicated that the general corrosion rates obtained were dependent on the method used for measurement, but following the relative trend of LPR>weight loss>EIS>ECN. 20 refs., 8 figs.

  8. Leadership Pipeline

    DEFF Research Database (Denmark)

    Elmholdt, Claus Westergård

    2013-01-01

    I artiklen undersøges det empiriske grundlag for Leader- ship Pipeline. Først beskrives Leadership Pipeline modellen om le- delsesbaner og skilleveje i opadgående transitioner mellem orga- nisatoriske ledelsesniveauer (Freedman, 1998; Charan, Drotter and Noel, 2001). Dernæst sættes fokus på det...... forholdet mellem kontinuitet- og diskontinuitet i ledel- seskompetencer på tværs af organisatoriske niveauer præsenteres og diskuteres. Afslutningsvis diskuteres begrænsningerne i en kompetencebaseret tilgang til Leadership Pipeline, og det foreslås, at succesfuld ledelse i ligeså høj grad afhænger af...

  9. Real-time monitoring and control of the oil pipeline networks; Monitoramento e controle inteligentes e em tempo real de redes de escoamento de petroleo

    Energy Technology Data Exchange (ETDEWEB)

    Brasileiro, F.; Galvao, C.; Brasileiro, E.; Catao, B.; Souto, C.; Machado, E.; Muniz, M.; Souza, A.; Gomes, A. [Universidade Federal de Campina Grande, PB (Brazil)]. E-mail: fubica@dsc.ufcg.edu.br; Aloise, D. [Universidade Federal do Rio Grande do Norte, Natal, RN (Brazil); Oliveira, A.; Gomes, C.; Rolim, T.; Boquimpani, C. [PETROBRAS S.A. (Brazil)

    2003-07-01

    Real-time monitoring and control of complex and large-scale oil pipeline networks is complicated by several requirements, among them: reliability of data acquisition and communication systems; strict time limits between data acquisition and decision of control action; operational constraints of a large number of pipeline devices and multi-objective control, involving economic, operational, environmental and institutional objectives and constraints. The MDTP system was designed for meeting such requirements. A simulation-optimization approach is the strategy adopted for the network state prediction and control. The simulation module is based on the quasi-steady state hydraulics of oil-water flow. The control is centered on the pumping systems, respecting operational constraints of tanks and pipes, without reducing the oil production targets. For real-time control, an optimization scheme generates multiple operational scenarios, the optimum of them being selected by means of a meta-heuristics approach. To meet the strict time limits for deciding the control strategy, a grid computing architecture was adopted, instead of conventional dedicated high-performance computers. (author)

  10. Integrated Proteomic Pipeline Using Multiple Search Engines for a Proteogenomic Study with a Controlled Protein False Discovery Rate.

    Science.gov (United States)

    Park, Gun Wook; Hwang, Heeyoun; Kim, Kwang Hoe; Lee, Ju Yeon; Lee, Hyun Kyoung; Park, Ji Yeong; Ji, Eun Sun; Park, Sung-Kyu Robin; Yates, John R; Kwon, Kyung-Hoon; Park, Young Mok; Lee, Hyoung-Joo; Paik, Young-Ki; Kim, Jin Young; Yoo, Jong Shin

    2016-11-04

    In the Chromosome-Centric Human Proteome Project (C-HPP), false-positive identification by peptide spectrum matches (PSMs) after database searches is a major issue for proteogenomic studies using liquid-chromatography and mass-spectrometry-based large proteomic profiling. Here we developed a simple strategy for protein identification, with a controlled false discovery rate (FDR) at the protein level, using an integrated proteomic pipeline (IPP) that consists of four engrailed steps as follows. First, using three different search engines, SEQUEST, MASCOT, and MS-GF+, individual proteomic searches were performed against the neXtProt database. Second, the search results from the PSMs were combined using statistical evaluation tools including DTASelect and Percolator. Third, the peptide search scores were converted into E-scores normalized using an in-house program. Last, ProteinInferencer was used to filter the proteins containing two or more peptides with a controlled FDR of 1.0% at the protein level. Finally, we compared the performance of the IPP to a conventional proteomic pipeline (CPP) for protein identification using a controlled FDR of <1% at the protein level. Using the IPP, a total of 5756 proteins (vs 4453 using the CPP) including 477 alternative splicing variants (vs 182 using the CPP) were identified from human hippocampal tissue. In addition, a total of 10 missing proteins (vs 7 using the CPP) were identified with two or more unique peptides, and their tryptic peptides were validated using MS/MS spectral pattern from a repository database or their corresponding synthetic peptides. This study shows that the IPP effectively improved the identification of proteins, including alternative splicing variants and missing proteins, in human hippocampal tissues for the C-HPP. All RAW files used in this study were deposited in ProteomeXchange (PXD000395).

  11. The global pipeline of new medicines for the control and elimination of malaria

    Science.gov (United States)

    2012-01-01

    Over the past decade, there has been a transformation in the portfolio of medicines to combat malaria. New fixed-dose artemisinin combination therapy is available, with four different types having received approval from Stringent Regulatory Authorities or the World Health Organization (WHO). However, there is still scope for improvement. The Malaria Eradication Research agenda identified several gaps in the current portfolio. Simpler regimens, such as a single-dose cure are needed, compared with the current three-day treatment. In addition, new medicines that prevent transmission and also relapse are needed, but with better safety profiles than current medicines. There is also a big opportunity for new medicines to prevent reinfection and to provide chemoprotection. This study reviews the global portfolio of new medicines in development against malaria, as of the summer of 2012. Cell-based phenotypic screening, and ‘fast followers’ of clinically validated classes, mean that there are now many new classes of molecules starting in clinical development, especially for the blood stages of malaria. There remain significant gaps for medicines blocking transmission, preventing relapse, and long-duration molecules for chemoprotection. The nascent pipeline of new medicines is significantly stronger than five years ago. However, there are still risks ahead in clinical development and sustainable funding of clinical studies is vital if this early promise is going to be delivered. PMID:22958514

  12. Intelligent Control of Welding Gun Pose for Pipeline Welding Robot Based on Improved Radial Basis Function Network and Expert System

    Directory of Open Access Journals (Sweden)

    Jingwen Tian

    2013-02-01

    Full Text Available Since the control system of the welding gun pose in whole-position welding is complicated and nonlinear, an intelligent control system of welding gun pose for a pipeline welding robot based on an improved radial basis function neural network (IRBFNN and expert system (ES is presented in this paper. The structure of the IRBFNN is constructed and the improved genetic algorithm is adopted to optimize the network structure. This control system makes full use of the characteristics of the IRBFNN and the ES. The ADXRS300 micro-mechanical gyro is used as the welding gun position sensor in this system. When the welding gun position is obtained, an appropriate pitch angle can be obtained through expert knowledge and the numeric reasoning capacity of the IRBFNN. ARM is used as the controller to drive the welding gun pitch angle step motor in order to adjust the pitch angle of the welding gun in real-time. The experiment results show that the intelligent control system of the welding gun pose using the IRBFNN and expert system is feasible and it enhances the welding quality. This system has wide prospects for application.

  13. Requirements for implementing real-time control functional modules on a hierarchical parallel pipelined system

    Science.gov (United States)

    Wheatley, Thomas E.; Michaloski, John L.; Lumia, Ronald

    1989-01-01

    Analysis of a robot control system leads to a broad range of processing requirements. One fundamental requirement of a robot control system is the necessity of a microcomputer system in order to provide sufficient processing capability.The use of multiple processors in a parallel architecture is beneficial for a number of reasons, including better cost performance, modular growth, increased reliability through replication, and flexibility for testing alternate control strategies via different partitioning. A survey of the progression from low level control synchronizing primitives to higher level communication tools is presented. The system communication and control mechanisms of existing robot control systems are compared to the hierarchical control model. The impact of this design methodology on the current robot control systems is explored.

  14. The dengue vaccine pipeline: Implications for the future of dengue control

    OpenAIRE

    Schwartz, Lauren M.; Halloran, M. Elizabeth; Durbin, Anna P.; Longini Jr., Ira M.

    2015-01-01

    Dengue has become the most rapidly expanding mosquito-borne infectious disease on the planet, surpassing malaria and infecting at least 390 million people per year. There is no effective treatment for dengue illness other than supportive care, especially for severe cases. Symptoms can be mild or life-threatening as in dengue hemorrhagic fever and dengue shock syndrome. Vector control has been only partially successful in decreasing dengue transmission. The potential use of safe and effective ...

  15. Development and Applications of Pipeline Steel in Long-Distance Gas Pipeline of China

    Science.gov (United States)

    Chunyong, Huo; Yang, Li; Lingkang, Ji

    In past decades, with widely utilizing of Microalloying and Thermal Mechanical Control Processing (TMCP) technology, the good matching of strength, toughness, plasticity and weldability on pipeline steel has been reached so that oil and gas pipeline has been greatly developed in China to meet the demand of strong domestic consumption of energy. In this paper, development history of pipeline steel and gas pipeline in china is briefly reviewed. The microstructure characteristic and mechanical performance of pipeline steel used in some representative gas pipelines of china built in different stage are summarized. Through the analysis on the evolution of pipeline service environment, some prospective development trend of application of pipeline steel in China is also presented.

  16. Oil pipeline valve automation for spill reduction

    Energy Technology Data Exchange (ETDEWEB)

    Mohitpour, Mo; Trefanenko, Bill [Enbridge Technology Inc, Calgary (Canada); Tolmasquim, Sueli Tiomno; Kossatz, Helmut [TRANSPETRO - PETROBRAS Transporte S.A., Rio de Janeiro, RJ (Brazil)

    2003-07-01

    Liquid pipeline codes generally stipulate placement of block valves along liquid transmission pipelines such as on each side of major river crossings where environmental hazards could cause or are foreseen to potentially cause serious consequences. Codes, however, do not stipulate any requirement for block valve spacing for low vapour pressure petroleum transportation, nor for remote pipeline valve operations to reduce spills. A review of pipeline codes for valve requirement and spill limitation in high consequence areas is thus presented along with a criteria for an acceptable spill volume that could be caused by pipeline leak/full rupture. A technique for deciding economically and technically effective pipeline block valve automation for remote operation to reduce oil spilled and control of hazards is also provided. In this review, industry practice is highlighted and application of the criteria for maximum permissible oil spill and the technique for deciding valve automation thus developed, as applied to ORSUB pipeline is presented. ORSUB is one of the three initially selected pipelines that have been studied. These pipelines represent about 14% of the total length of petroleum transmission lines operated by PETROBRAS Transporte S.A. (TRANSPETRO) in Brazil. Based on the implementation of valve motorization on these three pipeline, motorization of block valves for remote operation on the remaining pipelines is intended, depending on the success of these implementations, on historical records of failure and appropriate ranking. (author)

  17. Pipeline technology. Petroleum oil - long-distance pipelines. Pipelinetechnik. Mineraloelfernleitungen

    Energy Technology Data Exchange (ETDEWEB)

    Krass, W; Kittel, A; Uhde, A

    1979-01-01

    All questions and concerns of pipeline technique are dealt with in detail. Some chapters can be applied for petroleum pipelines only or partly, for example the importance of petroleum pipelines, projecting, calculation, and operation. The sections of pipes and formings, laying, rights of way, and corrosion protection, accessories and remote effect technique, however, are of general interest, for example also for gas pipelines. In the chapter on working material, a very good summary of today's pipe working material including the thermomechanically treated steels is given. Besides methods of improving the toughness, the problems of the corrosion caused by strain cracking and the ways of avoiding it are pointed out. The pipe producing methods and, in the end of the chapter, the tests in the factory are explained. The section of laying deals with the laying methods being applied for years in pipeline construction, a big part referring to welding methods and tests. Active and passive corrosion protection are explained with all details. In addition to the solidity calculation presented with special regard to concerns of petroleum pipelines, theoretical fundaments and calculation methods for pressure are dealt with. Beside general questions of pumps, accessories, and drives, there is a section dealing with measurement and control techniques. Furthermore, remote effect and transmission techniques and news systems are explained in detail. Here, problems are referred to which are applicable not only to the operation of mineral oil pipelines. The book is completed by indications as to pipeline operation emphasizing general operation control, maintenance, repair methods and damage and their elimination. The last chapter contains a collection of the legal fundaments and the technical rules.

  18. Application of heat-resistant non invasive acoustic transducers for coolant control in the NPP pipelines

    International Nuclear Information System (INIS)

    Melnikov, V.; Nigmatulin, B.

    1997-01-01

    The use of ultrasonic waves enables remote testing of the coolant flow, detection of solid and gaseous occlusions and measuring of the water velocity and level. Analysis of the acoustic noise makes it possible to detect coolant leaks and diagnose the state and operation of the rotating mechanisms and bearings. Results are given of the research in the development of highly reliable waveguide-type non-invasive acoustic transducers with a long service life. Examples are given of the use of transducers in various fields of nuclear technology: detection of gas in coolant, indication of the coolant level, control of pipe filling and drainage, measurement of liquid film velocity at the pipe inner surface. (M.D.)

  19. Flow accelerated corrosion and its control measures for the secondary circuit pipelines in Indian nuclear power plants

    International Nuclear Information System (INIS)

    Kain, Vivekanand; Roychowdhury, S.; Mathew, Thomas; Bhandakkar, Atul

    2008-01-01

    A plain carbon steel feeder pipeline in the secondary circuit failed downstream of a flow measurement device (orifice meter) during operation at nuclear power plant. A detailed failure analysis done on the failed pipeline is described in this paper. The results established the fine surface pattern of 'Horseshoe pits' at the affected regions. X-ray diffraction analysis on the samples far from the failed regions showed presence of magnetite but on the sample from the failed region showed peaks due to base metal only, indicating dissolution of the oxide. Thickness profiling of the pipeline indicated reduction of thickness from the design 7.62 mm to a minimum of 0.4-1.4 mm at the location of the failure. These observations are characteristic of single phase flow accelerated corrosion. This paper details the extent of flow accelerated corrosion in various Indian power plants and the remedial measures for replacement and possible design and water chemistry changes to combat it

  20. Instrumented Pipeline Initiative

    Energy Technology Data Exchange (ETDEWEB)

    Thomas Piro; Michael Ream

    2010-07-31

    This report summarizes technical progress achieved during the cooperative agreement between Concurrent Technologies Corporation (CTC) and U.S. Department of Energy to address the need for a for low-cost monitoring and inspection sensor system as identified in the Department of Energy (DOE) National Gas Infrastructure Research & Development (R&D) Delivery Reliability Program Roadmap.. The Instrumented Pipeline Initiative (IPI) achieved the objective by researching technologies for the monitoring of pipeline delivery integrity, through a ubiquitous network of sensors and controllers to detect and diagnose incipient defects, leaks, and failures. This report is organized by tasks as detailed in the Statement of Project Objectives (SOPO). The sections all state the objective and approach before detailing results of work.

  1. Removable pipeline plug

    International Nuclear Information System (INIS)

    Vassalotti, M.; Anastasi, F.

    1984-01-01

    A removable plugging device for a pipeline, and particularly for pressure testing a steam pipeline in a boiling water reactor, wherein an inflatable annular sealing member seals off the pipeline and characterized by radially movable shoes for holding the plug in place, each shoe being pivotally mounted for self-adjusting engagement with even an out-of-round pipeline interior

  2. Underground pipeline corrosion

    CERN Document Server

    Orazem, Mark

    2014-01-01

    Underground pipelines transporting liquid petroleum products and natural gas are critical components of civil infrastructure, making corrosion prevention an essential part of asset-protection strategy. Underground Pipeline Corrosion provides a basic understanding of the problems associated with corrosion detection and mitigation, and of the state of the art in corrosion prevention. The topics covered in part one include: basic principles for corrosion in underground pipelines, AC-induced corrosion of underground pipelines, significance of corrosion in onshore oil and gas pipelines, n

  3. Pipelines, inexpensive and safe mode of transport

    Energy Technology Data Exchange (ETDEWEB)

    Grover, D D

    1979-01-01

    Pipelines are the leading bulk commodity transporter and should play an even more important role in the future of energy transportation and distribution. As fossil fuel and low-cost uranium resources become depleted, it will be economical to produce hydrogen by electrolysis and transport it through underground pipelines to points of consumption. The cost would be only two to three times that of transporting natural gas per unit of heat energy and substantially less than the cost of transporting electric energy in overhead, extra-high-voltage transmission lines. Pipeline design, including economic pipe diameter; pipe material; operation by remote control and automation; cathodic protection; pipeline construction; and pipeline maintenance, particularly as regards the 1157 km long Oil India Pipeline, are discussed.

  4. Sea water pipeline for nuclear power plant

    International Nuclear Information System (INIS)

    Ueno, Ken-ichi.

    1992-01-01

    Heating coils, for example, are wound around sea water pipelines as a heater. The outer wall surface of the sea water pipelines is heated by the heating coils. The inner wall surfaces of the sea water pipelines can be warmed to higher than a predetermined temperature by heating the outer wall surfaces to die out marine organisms deposited at the inner surfaces. Further, thermocouples for the external wall and the internal wall are disposed so that the temperature at the inner wall surface of the sea water pipelines can be controlled. Further, a temperature keeping material is disposed at the external surface of the sea water system pipelines. With such a constitution, the marine organisms deposited on the internal wall surface of the sea water system pipelines are died out to suppress the deposition amount of the marine organisms. Accordingly, the maintenance and the operation reliability is improved after maintenance. (I.N.)

  5. The research of qualitative indicators of gas pipelines during the ...

    African Journals Online (AJOL)

    The research of qualitative indicators of gas pipelines during the operation. ... Journal of Fundamental and Applied Sciences ... The quality control study of the inter-settlement gas pipeline section was conducted, and graphs of dependence of ...

  6. Tools and techniques for schedule's controlling: tracking system and control of Urucu-Manaus gas-pipeline construction, stretch B1

    Energy Technology Data Exchange (ETDEWEB)

    Zuany, Valdenise Marques; Dias, Jose Luiz Gomes [CONCREMAT Engenharia e Tecnologia S/A, Rio de Janeiro, RJ (Brazil)

    2009-07-01

    The goal is to show the monitoring systems and deadline control, using the PMBOK{sup R} project management tools, in the Construction and Assembly of the Coari-Manaus Gas-pipeline, stretch B1, which includes the cities of Coari, Codajas, Anori and Anama, in the state of Amazon, in the Northern Undertaking Implementation (IENOR), an Engineering division of the PETROBRAS System. This report presents the practical effects of the usage of three schedule control tools of the project: Performance Measurement, using the technique of the Earned Value Management (EVM), which integrates cost, schedule and physical progress of the enterprise to determine the variations of schedule and performance; Project Management Software, MSProject, which allows schedule's elaboration and makes the tracking of the planned dates possible (baseline) in relation to real dates and forecasts the trend level, the effects of changes in the project's schedule, demonstrating its utility as a schedule control tool; and Schedule Variance Analysis, which adopts practical data to reach the pessimistic, most likely and optimistic expectations. The implantation of these tools was based in the Work Breakdown Structure of the enterprise. The application of these three tools in the tracking and control of the enterprise demonstrates that, the use of information and techniques deriving from the planning and control can be an important support for project management and decision taking, comparing the results gotten in the implantation of the plan with its actual realization, defining, thus, the necessary corrective actions, generating learned lessons to use in future projects. (author)

  7. Environmental audit guidelines for pipelines

    International Nuclear Information System (INIS)

    1991-01-01

    Environmental auditing is a form of management control which provides an objective basis by which a company can measure the degree of compliance with environmental regulations. Other benefits of this type of auditing include improved environmental management, furthering communication on environmental issues of concern within the company, and provision of documentation on environmental diligence. A series of environmental audit guidelines for pipelines is presented in the form of lists of questions to be asked during an environmental audit followed by recommended actions in response to those questions. The questions are organized into seven main categories: environmental management and planning; operating procedures; spill prevention; management of wastes and hazardous materials; environmental monitoring; construction of pipelines; and pipeline abandonment, decommissioning and site reclamation

  8. 76 FR 45904 - Pipeline Safety: Information Collection Activities

    Science.gov (United States)

    2011-08-01

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No... at U.S. Department of Transportation, Pipeline and Hazardous Materials Safety Administration, 1200...: On Occasion. Title: Record Keeping for Natural Gas Pipeline Operators. OMB Control Number: 2137-0049...

  9. Sensor and transmitter system for communication in pipelines

    Science.gov (United States)

    Cooper, John F.; Burnham, Alan K.

    2013-01-29

    A system for sensing and communicating in a pipeline that contains a fluid. An acoustic signal containing information about a property of the fluid is produced in the pipeline. The signal is transmitted through the pipeline. The signal is received with the information and used by a control.

  10. North America pipeline map

    International Nuclear Information System (INIS)

    Anon.

    2005-01-01

    This map presents details of pipelines currently in place throughout North America. Fifty-nine natural gas pipelines are presented, as well as 16 oil pipelines. The map also identifies six proposed natural gas pipelines. Major cities, roads and highways are included as well as state and provincial boundaries. The National Petroleum Reserve is identified, as well as the Arctic National Wildlife Refuge. The following companies placed advertisements on the map with details of the services they provide relating to pipeline management and construction: Ferus Gas Industries Trust; Proline; SulfaTreat Direct Oxidation; and TransGas. 1 map

  11. Volume totalizers analysis of pipelines operated by TRANSPETRO National Operational Control Center; Analise de totalizadores de volume em oleodutos operados pelo Centro Nacional de Controle e Operacao da TRANSPETRO

    Energy Technology Data Exchange (ETDEWEB)

    Aramaki, Thiago Lessa; Montalvao, Antonio Filipe Falcao [Petrobras Transporte S.A. (TRANSPETRO), Rio de Janeiro, RJ (Brazil); Marques, Thais Carrijo [Universidade do Estado do Rio de Janeiro (UERJ), RJ (Brazil)

    2012-07-01

    This paper aims to present the results and methodology in the analysis of differences in volume totals used in systems such as batch tracking and leak detection of pipelines operated by the National Center for Operational Control (CNCO) at TRANSPETRO. In order to optimize this type of analysis, software was developed to acquisition and processing of historical data using the methodology developed. The methodology developed takes into account the particularities encountered in systems operated by TRANSPETRO, more specifically, by CNCO. (author)

  12. Knotted pipeline

    International Nuclear Information System (INIS)

    Beer, G.; Slovak, K.

    2006-01-01

    It is too early to speculate on where the Transpetrol shares will end up. The bankruptcy trustee of Yukos, Eduard Rebgun, has so far received three offers from Gazprom, the Rusneft oil company and the Penta private equity group via its Cyprian company. All three would like to gain control over the Slovak oil transporting company. As yet, no formal request from the Slovak Republic has been delivered to Moscow. By Trend's deadline, President Ivan Gasparovic and the Minister of Economy, Lubomir Jahnatek, were still negotiating in Moscow with the Russian President, Vladimir Putin. One of the topics on the agenda was the future of the company which transports Russian oil to Europe. Both Slovakia and Russia aim to gain control over the stock and the situation is locked in stalemate The stock in question is owned by the Dutch company, Yukos Finance. And although this company is owned by the bankrupt Yukos, the property rights are in the hands of foundation, Stichting Administratiekantoor Yukos International. Yukos Finance is not in bankruptcy and it is therefore difficult to detach the Yukos shares from the company assets. (authors)

  13. Pipelines 'R' us

    International Nuclear Information System (INIS)

    Thomas, P.

    1997-01-01

    The geopolitical background to the export of oil and gas from Kazakhstan by pipeline is explored with particular reference to the sensitivities of the USA. There are now a number of pipeline proposals which would enable Kazakhstan to get its hydrocarbons to world markets. The construction of two of these formed part of a major oil deal signed recently with China in the face of stiff competition from major US companies. The most convenient and cost effective route, connecting up with Iran's existing pipeline network to the Gulf, is unlikely to be developed given continuing US sanctions against Iran. Equally unlikely seems to be the Turkmenistan to Pakistan pipeline in the light of the political volatility of Afghanistan. US companies continue to face limits on export capacity via the existing Russian pipelines from Kazakhstan. A temporary solution could be to carry some oil in the existing pipeline from Azerbaijan to Georgia which has been upgraded and is due to become operational soon, and later in a second proposed pipeline on this route. The Caspian Pipeline Consortium, consisting of three countries and eleven international companies, is building a 1500 km pipeline from the Tergiz field to Novorossiysk on the Black Sea with a view to completion in 2000. An undersea pipeline crossing the Caspian from Azerbaijan is being promoted by Turkey. There is an international perception that within the next five years Kazakhstan could be in a position to export its oil via as many as half a dozen different routes. (UK)

  14. Best practices for the abandonment of pipelines

    Energy Technology Data Exchange (ETDEWEB)

    Mackean, M; Reed, R; Snow, B [Nabors Canada, Calgary, AB (Canada). Abandonrite Service

    2006-07-01

    Pipeline regulations implemented in 2006 require that licensees register all pipelines. Training must also be provided for ground disturbance supervisors. In addition, signage must be maintained on abandoned pipelines, and discontinued pipelines must be properly isolated. Corrosion control and internal inhibition is required for discontinued lines. However, pipelines are often neglected during the well abandonment process. This presentation provided recommendations for coordinating well and pipeline abandonment processes. Pipeline ends can be located, depressurized, flushed and purged while wells are being abandoned. Contaminated soils around the wells can also be identified prior to reclamation activities. Administrative reviews must be conducted in order to provide accurate information on pipeline location, reclamation certification, and line break history. Field operation files must be reviewed before preliminary field work is conducted. Site inspections should be used to determine if all ends of the line are accessible. Landowners and occupants near the line must also be notified, and relevant documentation must be obtained. Skilled technicians must be used to assess the lines for obstructions as well as to cut and cap the lines after removing risers. The presentation also examined issues related to pressure change, movement, cold tapping, and live dead legs. tabs., figs.

  15. Decontamination device for pipeline

    International Nuclear Information System (INIS)

    Harashina, Heihachi.

    1994-01-01

    Pipelines to be decontaminated are parts of pipelines contaminated with radioactive materials, and they are connected to a fluid transfer means (for example, a bladeless pump) and a ball collector by way of a connector. The fluid of a mixture of chemical decontaminating liquid and spheres is sent into pipelines to be decontaminated. The spheres are, for example, heat resistant porous hard or soft rubber spheres. The fluid discharged from the pipelines to be decontaminated are circulated by way of bypassing means. The inner surface of the pipelines is decontaminated by the circulation of the fluid. When the bypass means is closed, the fluid discharged from the pipelines to be decontaminated is sent to the ball collector, and the spheres are captured by a hopper. Further, the liquid is sent to the filtrating means to filter the chemical contaminating liquid, and sludges contained in the liquid are captured. (I.N.)

  16. Overview of slurry pipelines

    Energy Technology Data Exchange (ETDEWEB)

    Gandhi, R L

    1982-01-01

    Slurry pipelines have proven to be a technically feasible, environmentally attractive and economic method of transporting finely divided particles over long distances. A pipeline system normally consists of preparation, pipeline and utilization facilities and requires optimization of all three components taken together. A considerable amount of research work has been done to develop hydraulic design of a slurry pipeline. Equipment selection and estimation of corrosion-erosion are considered to be as important as the hydraulic design. Future applications are expected to be for the large-scale transport of coal and for the exploitation of remotely located mineral deposits such as iron ore and copper. Application of slurry pipelines for the exploitation of remotely located mineral deposits is illustrated by the Kudremukh iron concentrate slurry pipeline in India.

  17. 75 FR 4134 - Pipeline Safety: Leak Detection on Hazardous Liquid Pipelines

    Science.gov (United States)

    2010-01-26

    ... safety study on pipeline Supervisory Control and Data Acquisition (SCADA) systems (NTSB/SS-05/02). The... indications of a leak on the SCADA interface was the impetus for this study. The NTSB examined 13 hazardous... pipelines, the line balance technique for leak detection can often be performed with manual calculations...

  18. 75 FR 13342 - Pipeline Safety: Workshop on Distribution Pipeline Construction

    Science.gov (United States)

    2010-03-19

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket ID... natural gas distribution construction. Natural gas distribution pipelines are subject to a unique subset... distribution pipeline construction practices. This workshop will focus solely on natural gas distribution...

  19. Leakproof control of technological installations and underground pipelines using radioactive tracers as a contribution to the protection of the natural environment

    International Nuclear Information System (INIS)

    Kras, J.; Walis, L.; Myczkowski, S.; Panczyk, E.

    2004-01-01

    The radioisotope method of leakproof control and leak localization has the following advantages: simplicity, short time of duration of experiment, low cost, short time need for adaptation of the object for the control, high sensitivity of measurements. Owing the application of the isotope technique is possible to carry out the expertise at low pressure, which permits to avoid strength effort of the construction materials. Through the radioisotope method is not a strength test it is complementary to pressure test (hydraulic or pneumatic). It should be noted that the hydraulic test cannot be applied to some technological objects despite the need of their leakproof control. The presentation deals with principles of application of the radioactive tracer - methyl bromide with Br-82, its preparation and ways of injecting the tracer and carrying out radiometric measurements in dependence on the kind of the object examined. The radioisotope tracer method for leakproof control of technological objects and underground pipelines as well as the apparatus used for this control have been developed in the Institute of Nuclear Chemistry and Technology and have been routinely used. (author)

  20. Pipeline system operability review

    Energy Technology Data Exchange (ETDEWEB)

    Eriksson, Kjell [Det Norske Veritas (Norway); Davies, Ray [CC Technologies, Dublin, OH (United States)

    2005-07-01

    Pipeline operators are continuously working to improve the safety of their systems and operations. In the US both liquid and gas pipeline operators have worked with the regulators over many years to develop more systematic approaches to pipeline integrity management. To successfully manage pipeline integrity, vast amounts of data from different sources needs to be collected, overlaid and analyzed in order to assess the current condition and predict future degradation. The efforts undertaken by the operators has had a significant impact on pipeline safety, nevertheless, during recent years we have seen a number of major high profile accidents. One can therefore ask how effective the pipeline integrity management systems and processes are. This paper will present one methodology 'The Pipeline System Operability Review' that can evaluate and rate the effectiveness of both the management systems and procedures, as well as the technical condition of the hardware. The result from the review can be used to compare the performance of different pipelines within one operating company, as well as benchmark with international best practices. (author)

  1. Pipeline system operability review

    Energy Technology Data Exchange (ETDEWEB)

    Eriksson, Kjell [Det Norske Veritas (Norway); Davies, Ray [CC Technologies, Dublin, OH (United States)

    2005-07-01

    Pipeline operators are continuously working to improve the safety of their systems and operations. In the US both liquid and gas pipeline operators have worked with the regulators over many years to develop more systematic approaches to pipeline integrity management. To successfully manage pipeline integrity, vast amounts of data from different sources needs to be collected, overlaid and analyzed in order to assess the current condition and predict future degradation. The efforts undertaken by the operators has had a significant impact on pipeline safety, nevertheless, during recent years we have seen a number of major high profile accidents. One can therefore ask how effective the pipeline integrity management systems and processes are. This paper will present one methodology 'The Pipeline System Operability Review' that can evaluate and rate the effectiveness of both the management systems and procedures, as well as the technical condition of the hardware. The result from the review can be used to compare the performance of different pipelines within one operating company, as well as benchmark with international best practices. (author)

  2. Slurry pipeline design approach

    Energy Technology Data Exchange (ETDEWEB)

    Betinol, Roy; Navarro R, Luis [Brass Chile S.A., Santiago (Chile)

    2009-12-19

    Compared to other engineering technologies, the design of a commercial long distance Slurry Pipeline design is a relatively new engineering concept which gained more recognition in the mid 1960 's. Slurry pipeline was first introduced to reduce cost in transporting coal to power generating units. Since then this technology has caught-up worldwide to transport other minerals such as limestone, copper, zinc and iron. In South America, the use of pipeline is commonly practiced in the transport of Copper (Chile, Peru and Argentina), Iron (Chile and Brazil), Zinc (Peru) and Bauxite (Brazil). As more mining operations expand and new mine facilities are opened, the design of the long distance slurry pipeline will continuously present a commercially viable option. The intent of this paper is to present the design process and discuss any new techniques and approach used today to ensure a better, safer and economical slurry pipeline. (author)

  3. 78 FR 70623 - Pipeline Safety: Meeting of the Gas Pipeline Advisory Committee and the Liquid Pipeline Advisory...

    Science.gov (United States)

    2013-11-26

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No. PHMSA-2009-0203] Pipeline Safety: Meeting of the Gas Pipeline Advisory Committee and the Liquid Pipeline Advisory Committee AGENCY: Pipeline and Hazardous Materials Safety Administration (PHMSA), DOT. [[Page...

  4. Pipeline operators training and certification using thermohydraulic simulators

    Energy Technology Data Exchange (ETDEWEB)

    Barreto, Claudio V.; Plasencia C, Jose [Pontificia Universidade Catolica (PUC-Rio), Rio de Janeiro, RJ (Brazil). Nucleo de Simulacao Termohidraulica de Dutos (SIMDUT); Montalvao, Filipe; Costa, Luciano [TRANSPETRO - PETROBRAS Transporte S.A., Rio de Janeiro, RJ (Brazil)

    2009-07-01

    The continuous pipeline operators training and certification of the TRANSPETRO's Pipeline National Operations Control Center (CNCO) is an essential task aiming the efficiency and safety of the oil and derivatives transport operations through the Brazilian pipeline network. For this objective, a hydraulic simulator is considered an excellent tool that allows the creation of different operational scenarios for training the pipeline hydraulic behavior as well as for testing the operator's responses to normal and abnormal real time operational conditions. The hydraulic simulator is developed based on a pipeline simulation software that supplies the hydraulic responses normally acquired from the pipeline remote units in the field. The pipeline simulation software has a communication interface system that sends and receives data to the SCADA supervisory system database. Using the SCADA graphical interface to create and to customize human machine interfaces (HMI) from which the operator/instructor has total control of the pipeline/system and instrumentation by sending commands. Therefore, it is possible to have realistic training outside of the real production systems, while acquiring experience during training hours with the operation of a real pipeline. A pilot Project was initiated at TRANSPETRO - CNCO targeting to evaluate the hydraulic simulators advantages in pipeline operators training and certification programs. The first part of the project was the development of three simulators for different pipelines. The excellent results permitted the project expansion for a total of twenty different pipelines, being implemented in training programs for pipelines presently operated by CNCO as well as for the new ones that are being migrated. The main objective of this paper is to present an overview of the implementation process and the development of a training environment through a pipe simulation environment using commercial software. This paper also presents

  5. Bulletin 2005-12 : revised Alberta pipeline regulation issued

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2005-05-31

    A revised Pipeline Regulation has been issued and is currently available on the Alberta Energy and Utilities Board (EUB) website. Changes to the regulation reflect bothchanges in EUB regulatory policy and processes and technological improvements. Goals of the revision include improvements in overall pipeline performance, and the implementation of recommendations derived from the Public Safety and Sour Gas Committee concerning sour gas pipeline safety. The regulation was re-organized for greater clarity, and structured into 11 parts. Issues concerning the transition to the revised regulation were presented. The summary of notable administrative changes included clarifications of when a pipeline application is not required; when ABSA approval is required for steam lines; situations for which low-pressure natural gas lines must be licensed; and emergency response requirements. Technical clarifications include requirements for pipeline operations and maintenance manuals; composite materials; limitations on amounts of H{sub 2}S in polymeric pipe; pressure mismatches; approval for testing with gaseous media; venting of small volumes of raw gas; right-of-way surveillance; inspection of surface construction activities; annual corrosion evaluations; registering of pipelines and excavators in controlled areas with Alberta One-Call; ground disturbance training; restoration and signage maintenance on abandoned pipelines; sour service steel pipelines; unused pipelines and abandoned pipelines; and remediation of stub ends in operating pipelines.

  6. 76 FR 53086 - Pipeline Safety: Safety of Gas Transmission Pipelines

    Science.gov (United States)

    2011-08-25

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration 49 CFR Part 192 [Docket No. PHMSA-2011-0023] RIN 2137-AE72 Pipeline Safety: Safety of Gas Transmission Pipelines AGENCY: Pipeline and Hazardous Materials Safety Administration (PHMSA), Department of Transportation (DOT...

  7. 76 FR 70953 - Pipeline Safety: Safety of Gas Transmission Pipelines

    Science.gov (United States)

    2011-11-16

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration 49 CFR Part 192 [Docket ID PHMSA-2011-0023] RIN 2137-AE72 Pipeline Safety: Safety of Gas Transmission Pipelines AGENCY: Pipeline and Hazardous Materials Safety Administration (PHMSA); DOT. ACTION: Advance notice of...

  8. Pipeline Drag Reducers

    International Nuclear Information System (INIS)

    Marawan, H.

    2004-01-01

    Pipeline drag reducers have proven to be an extremely powerful tool in fluid transportation. High molecular weight polymers are used to reduce the frictional pressure loss ratio in crude oil pipelines, refined fuel and aqueous pipelines. Chemical structure of the main used pipeline drag reducers is one of the following polymers and copolymers classified according to the type of fluid to ; low density polyethylene, copolymer of I-hexane cross linked with divinyl benzene, polyacrylamide, polyalkylene oxide polymers and their copolymers, fluorocarbons, polyalkyl methacrylates and terpolymer of styrene, alkyl acrylate and acrylic acid. Drag reduction is the increase in pump ability of a fluid caused by the addition of small amounts of an additive to the fluid. The effectiveness of a drag reducer is normally expressed in terms of percent drag reduction. Frictional pressure loss in a pipeline system is a waste of energy and it costly. The drag reducing additive minimizes the flow turbulence, increases throughput and reduces the energy costs. The Flow can be increased by more than 80 % with existing assets. The effectiveness of the injected drag reducer in Mostorod to Tanta crude oil pipeline achieved 35.4 % drag reduction and 23.2 % flow increase of the actual performance The experimental application of DRA on Arab Petroleum Pipeline Company (Summed) achieved a flow increase ranging from 9-32 %

  9. Pollution from pipelines

    International Nuclear Information System (INIS)

    1991-01-01

    During the 1980s, over 3,900 spills from land-based pipelines released nearly 20 million gallons of oil into U.S. waters-almost twice as much as was released by the March 1989 Exxon Valdez oil spill. Although the Department of Transportation is responsible for preventing water pollution from petroleum pipelines, GAO found that it has not established a program to prevent such pollution. DOT has instead delegated this responsibility to the Coast Guard, which has a program to stop water pollution from ships, but not from pipelines. This paper reports that, in the absence of any federal program to prevent water pollution from pipelines, both the Coast Guard and the Environmental Protection Agency have taken steps to plan for and respond to oil spills, including those from pipelines, as required by the Clean Water Act. The Coast Guard cannot, however, adequately plan for or ensure a timely response to pipeline spills because it generally is unaware of specific locations and operators of pipelines

  10. High temperature pipeline design

    Energy Technology Data Exchange (ETDEWEB)

    Greenslade, J.G. [Colt Engineering, Calgary, AB (Canada). Pipelines Dept.; Nixon, J.F. [Nixon Geotech Ltd., Calgary, AB (Canada); Dyck, D.W. [Stress Tech Engineering Inc., Calgary, AB (Canada)

    2004-07-01

    It is impractical to transport bitumen and heavy oil by pipelines at ambient temperature unless diluents are added to reduce the viscosity. A diluted bitumen pipeline is commonly referred to as a dilbit pipeline. The diluent routinely used is natural gas condensate. Since natural gas condensate is limited in supply, it must be recovered and reused at high cost. This paper presented an alternative to the use of diluent to reduce the viscosity of heavy oil or bitumen. The following two basic design issues for a hot bitumen (hotbit) pipeline were presented: (1) modelling the restart problem, and, (2) establishing the maximum practical operating temperature. The transient behaviour during restart of a high temperature pipeline carrying viscous fluids was modelled using the concept of flow capacity. Although the design conditions were hypothetical, they could be encountered in the Athabasca oilsands. It was shown that environmental disturbances occur when the fluid is cooled during shut down because the ground temperature near the pipeline rises. This can change growing conditions, even near deeply buried insulated pipelines. Axial thermal loads also constrain the design and operation of a buried pipeline as higher operating temperatures are considered. As such, strain based design provides the opportunity to design for higher operating temperature than allowable stress based design methods. Expansion loops can partially relieve the thermal stress at a given temperature. As the design temperature increase, there is a point at which above grade pipelines become attractive options, although the materials and welding procedures must be suitable for low temperature service. 3 refs., 1 tab., 10 figs.

  11. Pipeline four-dimension management is the trend of pipeline integrity management in the future

    Energy Technology Data Exchange (ETDEWEB)

    Shaohua, Dong; Feifan; Zhongchen, Han [China National Petroleum Corporation (CNPC), Beijing (China)

    2009-07-01

    Pipeline integrity management is essential for today's operators to operate their pipelines safety and cost effectively. The latest developments of pipeline integrity management around the world are involved with change of regulation, industry standard and innovation of technology. And who know the trend of PIM in the future, which can be answered in the paper. As a result, the concept of P4DM was set up firstly in the world. The paper analyzed the pipeline HSE management, pipeline integrity management (PIM) and asset integrity management (AIM), the problem of management was produced, and also the Pipeline 4-dimension Management (P4DM) theory was brought forward. According to P4DM, from the hierarchy of P4DM, the management elements, fields, space and time was analyzed. The main content is P4DM integrate the space geography location and time, control and manage the pipeline system in whole process, anywhere and anytime. It includes the pipeline integrity, pipeline operation and emergency, which is integrated by IT system. It come true that the idea, solution, technology, organization, manager alternately intelligently control the process of management. What the paper talks about included the definition of pipeline 4D management, the research develop of P4DM, the theory of P4DM, the relationship between P4DM and PIM, the technology basis of P4DM, how to perform the P4DM and conclusion. The P4DM was produced, which provide the development direction of PIM in the future, and also provide the new ideas for PetroChina in the field of technology and management. (author)

  12. Trouble in the pipeline?

    Energy Technology Data Exchange (ETDEWEB)

    Snieckus, Darius

    2002-10-01

    The author provides a commentary on the political, economic, environmental and social problems facing the proposed 3 billion US dollars Baku-Ceyhan-Tbilisi export pipeline. The 1760 km long pipeline has been designed to carry 1 million b/d of crude oil from the Caspian Sea to Turkey's Mediterranean coast. The pipeline is being constructed by a BP-led consortium made up of Socar, Statoil, Unocal, TPAO, Eni, Itochu, Amerada Hess, TotalFinaElf and BP. (UK)

  13. Oil pipeline performance review, 1990

    International Nuclear Information System (INIS)

    1990-01-01

    This paper reviews the environmental performance of Canadian oil pipelines in spill prevention and control in 1990 and compares it with that in 1989. In 1990, in-service length of the systems reporting increased to 34,907 km. Traffic volume was 235 million m 3 . Failures dropped 16% from 1989 to 36. Equipment failures accounted for 47%, corrosion for 22% and operational error for 19% of the failures. Repair, damage and clean-up costs were considerably higher at $5,302,000, of which one external corrosion failure contributed $4,500,000. The average spill size was 130 m 3 with 72 m 3 recovered for a 55.4% recovery rate. No injuries resulted from the failures. An 11 year statistical summary of oil pipeline performance data is included. 3 figs., 5 tabs

  14. SPIRE, a modular pipeline for eQTL analysis of RNA-Seq data, reveals a regulatory hotspot controlling miRNA expression in C. elegans.

    Science.gov (United States)

    Kel, Ivan; Chang, Zisong; Galluccio, Nadia; Romeo, Margherita; Beretta, Stefano; Diomede, Luisa; Mezzelani, Alessandra; Milanesi, Luciano; Dieterich, Christoph; Merelli, Ivan

    2016-10-18

    The interpretation of genome-wide association study is difficult, as it is hard to understand how polymorphisms can affect gene regulation, in particular for trans-regulatory elements located far from their controlling gene. Using RNA or protein expression data as phenotypes, it is possible to correlate their variations with specific genotypes. This technique is usually referred to as expression Quantitative Trait Loci (eQTLs) analysis and only few packages exist for the integration of genotype patterns and expression profiles. In particular, tools are needed for the analysis of next-generation sequencing (NGS) data on a genome-wide scale, which is essential to identify eQTLs able to control a large number of genes (hotspots). Here we present SPIRE (Software for Polymorphism Identification Regulating Expression), a generic, modular and functionally highly flexible pipeline for eQTL processing. SPIRE integrates different univariate and multivariate approaches for eQTL analysis, paying particular attention to the scalability of the procedure in order to support cis- as well as trans-mapping, thus allowing the identification of hotspots in NGS data. In particular, we demonstrated how SPIRE can handle big association study datasets, reproducing published results and improving the identification of trans-eQTLs. Furthermore, we employed the pipeline to analyse novel data concerning the genotypes of two different C. elegans strains (N2 and Hawaii) and related miRNA expression data, obtained using RNA-Seq. A miRNA regulatory hotspot was identified in chromosome 1, overlapping the transcription factor grh-1, known to be involved in the early phases of embryonic development of C. elegans. In a follow-up qPCR experiment we were able to verify most of the predicted eQTLs, as well as to show, for a novel miRNA, a significant difference in the sequences of the two analysed strains of C. elegans. SPIRE is publicly available as open source software at , together with some example

  15. Chechnya: the pipeline front

    Energy Technology Data Exchange (ETDEWEB)

    Anon,

    1999-11-01

    This article examines the impact of the Russian campaign against Chechnya on projects for oil and gas pipelines from the new Caspian republics, which are seeking financial support. Topics discussed include the pipeline transport of oil from Azerbaijan through Chechnya to the Black Sea, the use of oil money to finance the war, the push for non-Russian export routes, the financing of pipelines, the impact of the war on the supply of Russian and Turkmenistan gas to Turkey, the proposed construction of the Trans Caspian pipeline, the weakening of trust between Russia and its neighbours, and the potential for trans Caucasus republics to look to western backers due to the instability of the North Caucasus. (UK)

  16. National Pipeline Mapping System

    Data.gov (United States)

    Department of Transportation — The NPMS Public Map Viewer allows the general public to view maps of transmission pipelines, LNG plants, and breakout tanks in one selected county. Distribution and...

  17. The Winfrith effluent pipeline

    International Nuclear Information System (INIS)

    Palmer, G.H.

    1959-11-01

    The paper describes the preparatory work leading up to the design of the Winfrith pipeline. Details of the existing system are given and some information on the predicted safe levels of radio-active discharge. (author)

  18. Pipelines in power plants

    International Nuclear Information System (INIS)

    Oude-Hengel, H.H.

    1978-01-01

    Since the end of the Sixties, steam-transporting pipelines are given great attention, as pipeline components often fail, partially even long before their designed operation time is over. Thus, experts must increasingly deal with questions of pipelines and their components. Design and calculation, production and operation of pipelines are included in the discussion. Within the frame of this discussion, planners, producers, operators, and technical surveillance personnel must be able to offer a homogenous 'plan for assuring the quality of pipelines' in fossil and nuclear power plants. This book tries to make a contribution to this topic. 'Quality assuring' means efforts made for meeting the demands of quality (reliability). The book does not intend to complete with well-known manuals, as for as a complete covering of the topic is concerned. A substantial part of its sections serves to show how quality assurance of pipelines can be at least partially obtained by surveillance measures beginning with the planning, covering the production, and finally accompanying the operation. There is hardly need to mention that the sort of planning, production, and operation has an important influence on the quality. This is why another part of the sections contain process aspects from the view of the planners, producers, and operators. (orig.) [de

  19. Pipelines to eastern Canada

    International Nuclear Information System (INIS)

    Otsason, J.

    1998-01-01

    This presentation focused on four main topics: (1) the existing path of pipelines to eastern Canada, (2) the Chicago hub, (3) transport alternatives, and (4) the Vector Pipeline' expansion plans. In the eastern Canadian market, TransCanada Pipelines dominates 96 per cent of the market share and is effectively immune to expansion costs. Issues regarding the attractiveness of the Chicago hub were addressed. One attractive feature is that the Chicago hub has access to multiple supply basins including western Canada, the Gulf Coast, the mid-continent, and the Rockies. Regarding Vector Pipelines' future plans, the company proposes to construct 343 miles of pipeline from Joliet, Illinois to Dawn, Ontario. Project description included discussion of some of the perceived advantages of this route, namely, extensive storage in Michigan and south-western Ontario, the fact that the proposed pipeline traverses major markets which would mitigate excess capacity concerns, arbitrage opportunities, cost effective expansion capability reducing tolls, and likely lower landed costs in Ontario. Project schedule, costs, rates and tariffs are also discussed. tabs., figs

  20. Pipeline for Contraceptive Development

    Science.gov (United States)

    Blithe, Diana L.

    2016-01-01

    The high rates of unplanned pregnancy reflect unmet need for effective contraceptive methods for women, especially for individuals with health risks such as obesity, diabetes, hypertension, and other conditions that may contraindicate use of an estrogen-containing product. Improvements in safety, user convenience, acceptability and availability of products remain important goals of the contraceptive development program. Another important goal is to minimize the impact of the products on the environment. Development of new methods for male contraception has the potential to address many of these issues with regard to safety for women who have contraindications to effective contraceptive methods but want to protect against pregnancy. It also will address a huge unmet need for men who want to control their fertility. Products under development for men would not introduce eco-toxic hormones in the waste water. Investment in contraceptive research to identify new products for women has been limited in the pharmaceutical industry relative to investment in drug development for other indications. Pharmaceutical R&D for male contraception was active in the 1990’s but was abandoned over a decade ago. The Eunice Kennedy Shriver National Institute of Child Health and Human Development (NICHD) has supported a contraceptive development program since 1969. Through a variety of programs including research grants and contracts, NICHD has developed a pipeline of new targets/products for male and female contraception. A number of lead candidates are under evaluation in the NICHD Contraceptive Clinical Trials Network (CCTN) (1–3). PMID:27523300

  1. Condition Monitoring Of Operating Pipelines With Operational Modal Analysis Application

    OpenAIRE

    Mironov Aleksey; Doronkin Pavel; Priklonsky Aleksander; Kabashkin Igor

    2015-01-01

    In the petroleum, natural gas and petrochemical industries, great attention is being paid to safety, reliability and maintainability of equipment. There are a number of technologies to monitor, control, and maintain gas, oil, water, and sewer pipelines. The paper focuses on operational modal analysis (OMA) application for condition monitoring of operating pipelines. Special focus is on the topicality of OMA for definition of the dynamic features of the pipeline (frequencies and mode shapes) i...

  2. Transient leak detection in crude oil pipelines

    Energy Technology Data Exchange (ETDEWEB)

    Beushausen, R.; Tornow, S.; Borchers, H. [Nord-West Oelleitung, Wilhelmshaven (Germany); Murphy, K.; Zhang, J. [Atmos International Ltd., Manchester (United Kingdom)

    2004-07-01

    Nord-West Oelleitung (NWO) operates 2 crude oil pipelines from Wilhemshaven to Koln and Hamburg respectively. German regulations for transporting flammable substances stipulate that 2 independent continuously working procedures be used to detect leaks. Leak detection pigs are used routinely to complement the surveillance system. This paper described the specific issues of transient leak detection in crude oil pipelines. It was noted that traditional methods have failed to detect leaks that occur immediately after pumps are turned on or off because the pressure wave generated by the transient dominates the pressure wave that results from the leak. Frequent operational changes in a pipeline are often accompanied by an increased number of false alarms and failure to detect leaks due to unsteady operations. NWO therefore decided to have the Atmos statistical pipeline leak detection (SPLD) system installed on their pipelines. The key to the SPLD system is the sequential probability ratio test. Comprehensive data validation is performed following reception of pipeline data from the supervisory control and data acquisition (SCADA) system. The validated data is then used to calculate the corrected flow imbalance, which is fed into the SPRT to determine if there is an increase in the flow imbalance. Pattern recognition is then used to distinguish a leak from operational changes. The SPLD is unique because it uses 3 computational pipeline monitoring methods simultaneously, namely modified volume balance, statistical analysis, and pressure and flow monitoring. The successful installation and testing of the SPLD in 2 crude oil pipelines was described along with the main difficulties associated with transient leaks. Field results were presented for both steady-state and transient conditions. 5 refs., 2 tabs., 16 figs.

  3. Market Brief : Turkey oil and gas pipelines

    International Nuclear Information System (INIS)

    2001-08-01

    This report presented some quick facts about oil and gas pipelines in Turkey and presented opportunities for trade. The key players and customers in the oil and gas sector were described along with an export check list. Turkey is looking into becoming an energy bridge between oil and gas producing countries in the Middle East, Central Asia and Europe. The oil and gas sectors are dominated by the Turkish Petroleum Corporation, a public enterprise dealing with exploration and production, and the State Pipeline Corporation which deals with energy transmission. They are also the key buyers of oil and gas equipment in Turkey. There are several pipelines connecting countries bordering the Caspian Sea. Opportunities exist in the areas of engineering consulting as well as contracting services for oil and gas pipeline transmission and distribution. Other opportunities lie in the area of pipeline construction, rehabilitation, materials, equipment, installation, and supervisory control and data acquisition (SCADA) systems. Currently, the major players are suppliers from Italy, Germany, France, United States and Japan. Turkey has no trade barriers and imported equipment and materials are not subjected to any restriction. The oil and gas market in Turkey expected in increase by an average annual growth rate of 15 per cent from 2001 to 2003. A brief description of pipeline projects in Turkey was presented in this report along with a list of key contacts and support services. 25 refs., 1 append

  4. 77 FR 19414 - Pipeline Safety: Public Comment on Leak and Valve Studies Mandated by the Pipeline Safety...

    Science.gov (United States)

    2012-03-30

    ... Safety, Regulatory Certainty, and Job Creation Act of 2011 AGENCY: Pipeline and Hazardous Materials.... Background: The recent passage of the Pipeline Safety, Regulatory Certainty, and Job Creation Act of 2011 has... consider upstream and downstream controls, automation, supervisory control and data acquisition systems...

  5. Modeling and monitoring of pipelines and networks advanced tools for automatic monitoring and supervision of pipelines

    CERN Document Server

    Torres, Lizeth

    2017-01-01

    This book focuses on the analysis and design of advanced techniques for on-line automatic computational monitoring of pipelines and pipe networks. It discusses how to improve the systems’ security considering mathematical models of the flow, historical flow rate and pressure data, with the main goal of reducing the number of sensors installed along a pipeline. The techniques presented in the book have been implemented in digital systems to enhance the abilities of the pipeline network’s operators in recognizing anomalies. A real leak scenario in a Mexican water pipeline is used to illustrate the benefits of these techniques in locating the position of a leak. Intended for an interdisciplinary audience, the book addresses researchers and professionals in the areas of mechanical, civil and control engineering. It covers topics on fluid mechanics, instrumentation, automatic control, signal processing, computing, construction and diagnostic technologies.

  6. Influence of remanent magnetization on pitting corrosion in pipeline steel

    Energy Technology Data Exchange (ETDEWEB)

    Espina-Hernandez, J. H. [ESIME Zacatenco, SEPI Electronica Instituto Politecnico Nacional Mexico, D. F. (Mexico); Caleyo, F.; Hallen, J. M. [DIM-ESIQIE, Instituto Politecnico Nacional Mexico D. F. (Mexico); Lopez-Montenegro, A.; Perez-Baruch, E. [Pemex Exploracion y Produccion, Region Sur Villahermosa, Tabasco (Mexico)

    2010-07-01

    Statistical studies performed in Mexico indicate that leakage due to external pitting corrosion is the most likely cause of failure of buried pipelines. When pipelines are inspected with the magnetic flux leakage (MFL) technology, which is routinely used, the magnetization level of every part of the pipeline changes as the MFL tool travels through it. Remanent magnetization stays in the pipeline wall after inspection, at levels that may differ from a point to the next. This paper studies the influence of the magnetic field on pitting corrosion. Experiments were carried out on grade 52 steel under a level of remanent magnetization and other laboratory conditions that imitated the conditions of a pipeline after an MLF inspection. Non-magnetized control samples and magnetized samples were subjected to pitting by immersion in a solution containing chlorine and sulfide ions for seven days, and then inspected with optical microscopy. Results show that the magnetic field in the pipeline wall significantly increases pitting corrosion.

  7. Security of pipeline facilities

    Energy Technology Data Exchange (ETDEWEB)

    Lee, S.C. [Alberta Energy and Utilities Board, Calgary, AB (Canada); Van Egmond, C.; Duquette, L. [National Energy Board, Calgary, AB (Canada); Revie, W. [Canada Centre for Mineral and Energy Technology, Ottawa, ON (Canada)

    2005-07-01

    This working group provided an update on provincial, federal and industry directions regarding the security of pipeline facilities. The decision to include security issues in the NEB Act was discussed as well as the Pipeline Security Management Assessment Project, which was created to establish a better understanding of existing security management programs as well as to assist the NEB in the development and implementation of security management regulations and initiatives. Amendments to the NEB were also discussed. Areas of pipeline security management assessment include physical safety management; cyber and information security management; and personnel security. Security management regulations were discussed, as well as implementation policies. Details of the Enbridge Liquids Pipelines Security Plan were examined. It was noted that the plan incorporates flexibility for operations and is integrated with Emergency Response and Crisis Management. Asset characterization and vulnerability assessments were discussed, as well as security and terrorist threats. It was noted that corporate security threat assessment and auditing are based on threat information from the United States intelligence community. It was concluded that the oil and gas industry is a leader in security in North America. The Trans Alaska Pipeline Incident was discussed as a reminder of how costly accidents can be. Issues of concern for the future included geographic and climate issues. It was concluded that limited resources are an ongoing concern, and that the regulatory environment is becoming increasingly prescriptive. Other concerns included the threat of not taking international terrorism seriously, and open media reporting of vulnerability of critical assets, including maps. tabs., figs.

  8. LNG transport through pipelines

    Energy Technology Data Exchange (ETDEWEB)

    Pfund, P; Philipps, A

    1975-01-01

    LNG pipelines could help solve some peakshaving problems if operated in conjunction with other facilities that could use the LNG cold recovered during regasification. In some areas at present, LNG is delivered by tanker and regasified near the terminal for transmission through conventional gas pipelines. In other places, utilities liquefy natural gas for easy storage for later peakshaving use. The only chance to avoid the second expensive liquefaction step would be to convey imported LNG through a suitable designed LNG pipeline. The technical problems involved in LNG pipeline construction have basically been solved in recent years, but those pipelines actually constructed have been only short ones. To be economically justified, long-distance LNG lines require additional credit, which could be obtained by selling the LNG cold recovered during regasification to industrial users located in or near the points of gas consumption. Technical details presented cover the pipe material, stress relief, steel composition, pressure enthalpy, bellows-type expansion joints, and mechanical and thermal insulation.

  9. Water level detection pipeline

    International Nuclear Information System (INIS)

    Koshikawa, Yukinobu; Imanishi, Masatoshi; Niizato, Masaru; Takagi, Masahiro

    1998-01-01

    In the present invention, water levels of a feedwater heater and a drain tank in a nuclear power plant are detected at high accuracy. Detection pipeline headers connected to the upper and lower portions of a feedwater heater or a drain tank are connected with each other. The connection line is branched at appropriate two positions and an upper detection pipeline and a lower detection pipeline are connected thereto, and a gauge entrance valve is disposed to each of the detection pipelines. A diaphragm of a pressure difference generator is connected to a flange formed to the end portion. When detecting the change of water level in the feedwater heater or the drain tank as a change of pressure difference, gauge entrance valves on the exit side of the upper and lower detection pipelines are connected by a connection pipe. The gauge entrance valve is closed, a tube is connected to the lower detection pipe to inject water to the diaphragm of the pressure difference generator passing through the connection pipe thereby enabling to calibrate the pressure difference generator. The accuracy of the calibration of instruments is improved and workability thereof upon flange maintenance is also improved. (I.S.)

  10. Pipelines. Economy's veins; Pipelines. Adern der Wirtschaft

    Energy Technology Data Exchange (ETDEWEB)

    Feizlmayr, Adolf; Goestl, Stefan [ILF Beratende Ingenieure, Muenchen (Germany)

    2011-02-15

    According to the existing prognoses more than 1 million km of gas pipelines, oil pipelines and water pipelines are built up to the year 2030. The predominant portion is from gas pipelines. The safe continued utilization of the aging pipelines is a large challenge. In addition, the diagnostic technology, the evaluation and risk assessment have to be developed further. With the design of new oil pipelines and gas pipelines, aspects of environmental protection, the energy efficiency of transport and thus the emission reduction of carbon dioxide, the public acceptance and the market strategy of the exporters gain in importance. With the offshore pipelines one soon will exceed the present border of 2,000 m depth of water and penetrate into larger sea depths.

  11. 77 FR 34123 - Pipeline Safety: Public Meeting on Integrity Management of Gas Distribution Pipelines

    Science.gov (United States)

    2012-06-08

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No. PHMSA-2012-0100] Pipeline Safety: Public Meeting on Integrity Management of Gas Distribution Pipelines AGENCY: Office of Pipeline Safety, Pipeline and Hazardous Materials Safety Administration, DOT. ACTION...

  12. 76 FR 29333 - Pipeline Safety: Meetings of the Technical Pipeline Safety Standards Committee and the Technical...

    Science.gov (United States)

    2011-05-20

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No... Technical Hazardous Liquid Pipeline Safety Standards Committee AGENCY: Pipeline and Hazardous Materials... for natural gas pipelines and for hazardous liquid pipelines. Both committees were established under...

  13. Pipeline rehabilitation planning

    Energy Technology Data Exchange (ETDEWEB)

    Palmer-Jones, Roland; Hopkins, Phil; Eyre, David [PENSPEN (United Kingdom)

    2005-07-01

    An operator faced with an onshore pipeline that has extensive damage must consider the need for rehabilitation, the sort of rehabilitation to be used, and the rehabilitation schedule. This paper will consider pipeline rehabilitation based on the authors' experiences from recent projects, and recommend a simple strategy for planning pipeline rehabilitation. It will also consider rehabilitation options: external re-coating; internal lining; internal painting; programmed repairs. The main focus will be external re-coating. Consideration will be given to rehabilitation coating types, including tape wraps, epoxy, and polyurethane. Finally it will discuss different options for scheduling the rehabilitation of corrosion damage including: the statistical comparison of signals from inspection pigs; statistical comparison of selected measurements from inspection pigs and other inspections; the use of corrosion rates estimated for the mechanisms and conditions; expert judgement. (author)

  14. Beyond the pipeline

    Energy Technology Data Exchange (ETDEWEB)

    Barnsley, J.; Ellis, D.; McIntosh, J.

    1979-12-01

    A study was conducted on the lives of women and their families in Fort Nelson, British Columbia, and Whitehorse, Yukon Territory, two communities which are to be affected by the proposed construction of the Alaska Highway gas pipeline. The womens' socio-economic concerns resulting from the proposed construction were examined by means of interviews with samples of women living in the two communities. Results from the study include descriptions of the communities and their basic services, community planning and housing, women's work in the home and for wages, and the perceived impact of the pipeline on such matters as employment, social services, living costs, business, housing, crime, and the overall community. Recommendations are made to improve the planning process for the pipeline to include the taking into account of womens' needs in such areas as training, health care, housing, and community services. 213 refs., 4 figs., 2 tabs.

  15. CPL: Common Pipeline Library

    Science.gov (United States)

    ESO CPL Development Team

    2014-02-01

    The Common Pipeline Library (CPL) is a set of ISO-C libraries that provide a comprehensive, efficient and robust software toolkit to create automated astronomical data reduction pipelines. Though initially developed as a standardized way to build VLT instrument pipelines, the CPL may be more generally applied to any similar application. The code also provides a variety of general purpose image- and signal-processing functions, making it an excellent framework for the creation of more generic data handling packages. The CPL handles low-level data types (images, tables, matrices, strings, property lists, etc.) and medium-level data access methods (a simple data abstraction layer for FITS files). It also provides table organization and manipulation, keyword/value handling and management, and support for dynamic loading of recipe modules using programs such as EsoRex (ascl:1504.003).

  16. Northern pipelines : backgrounder

    International Nuclear Information System (INIS)

    2002-04-01

    Most analysts agree that demand for natural gas in North America will continue to grow. Favourable market conditions created by rising demand and declining production have sparked renewed interest in northern natural gas development. The 2002 Annual Energy Outlook forecasted U.S. consumption to increase at an annual average rate of 2 per cent from 22.8 trillion cubic feet to 33.8 TCF by 2020, mostly due to rapid growth in demand for electric power generation. Natural gas prices are also expected to increase at an annual average rate of 1.6 per cent, reaching $3.26 per thousand cubic feet in 2020. There are currently 3 proposals for pipelines to move northern gas to US markets. They include a stand-alone Mackenzie Delta Project, the Alaska Highway Pipeline Project, and an offshore route that would combine Alaskan and Canadian gas in a pipeline across the floor of the Beaufort Sea. Current market conditions and demand suggest that the projects are not mutually exclusive, but complimentary. The factors that differentiate northern pipeline proposals are reserves, preparedness for market, costs, engineering, and environmental differences. Canada has affirmed its role to provide the regulatory and fiscal certainty needed by industry to make investment decisions. The Government of the Yukon does not believe that the Alaska Highway Project will shut in Mackenzie Delta gas, but will instead pave the way for development of a new northern natural gas industry. The Alaska Highway Pipeline Project will bring significant benefits for the Yukon, the Northwest Territories and the rest of Canada. Unresolved land claims are one of the challenges that has to be addressed for both Yukon and the Northwest Territories, as the proposed Alaska Highway Pipeline will travel through traditional territories of several Yukon first Nations. 1 tab., 4 figs

  17. Addressing the workforce pipeline challenge

    Energy Technology Data Exchange (ETDEWEB)

    Leonard Bond; Kevin Kostelnik; Richard Holman

    2006-11-01

    A secure and affordable energy supply is essential for achieving U.S. national security, in continuing U.S. prosperity and in laying the foundations to enable future economic growth. To meet this goal the next generation energy workforce in the U.S., in particular those needed to support instrumentation, controls and advanced operations and maintenance, is a critical element. The workforce is aging and a new workforce pipeline, to support both current generation and new build has yet to be established. The paper reviews the challenges and some actions being taken to address this need.

  18. Validation of pig operations through pipelines

    Energy Technology Data Exchange (ETDEWEB)

    Tolmasquim, Sueli Tiomno [TRANSPETRO - PETROBRAS Transporte S.A., Rio de Janeiro, RJ (Brazil); Nieckele, Angela O. [Pontificia Univ. Catolica do Rio de Janeiro, RJ (Brazil). Dept. de Engenharia Mecanica

    2005-07-01

    In the oil industry, pigging operations in pipelines have been largely applied for different purposes: pipe cleaning, inspection, liquid removal and product separation, among others. An efficient and safe pigging operation requires that a number of operational parameters, such as maximum and minimum pressures in the pipeline and pig velocity, to be well evaluated during the planning stage and maintained within stipulated limits while the operation is accomplished. With the objective of providing an efficient tool to assist in the control and design of pig operations through pipelines, a numerical code was developed, based on a finite difference scheme, which allows the simulation of two fluid transient flow, like liquid-liquid, gas-gas or liquid-gas products in the pipeline. Modules to automatically control process variables were included to employ different strategies to reach an efficient operation. Different test cases were investigated, to corroborate the robustness of the methodology. To validate the methodology, the results obtained with the code were compared with a real liquid displacement operation of a section of the OSPAR oil pipeline, belonging to PETROBRAS, with 30'' diameter and 60 km length, presenting good agreement. (author)

  19. A novel approach to pipeline tensioner modeling

    Energy Technology Data Exchange (ETDEWEB)

    O' Grady, Robert; Ilie, Daniel; Lane, Michael [MCS Software Division, Galway (Ireland)

    2009-07-01

    As subsea pipeline developments continue to move into deep and ultra-deep water locations, there is an increasing need for the accurate prediction of expected pipeline fatigue life. A significant factor that must be considered as part of this process is the fatigue damage sustained by the pipeline during installation. The magnitude of this installation-related damage is governed by a number of different agents, one of which is the dynamic behavior of the tensioner systems during pipe-laying operations. There are a variety of traditional finite element methods for representing dynamic tensioner behavior. These existing methods, while basic in nature, have been proven to provide adequate forecasts in terms of the dynamic variation in typical installation parameters such as top tension and sagbend/overbend strain. However due to the simplicity of these current approaches, some of them tend to over-estimate the frequency of tensioner pay out/in under dynamic loading. This excessive level of pay out/in motion results in the prediction of additional stress cycles at certain roller beds, which in turn leads to the prediction of unrealistic fatigue damage to the pipeline. This unwarranted fatigue damage then equates to an over-conservative value for the accumulated damage experienced by a pipeline weld during installation, and so leads to a reduction in the estimated fatigue life for the pipeline. This paper describes a novel approach to tensioner modeling which allows for greater control over the velocity of dynamic tensioner pay out/in and so provides a more accurate estimation of fatigue damage experienced by the pipeline during installation. The paper reports on a case study, as outlined in the proceeding section, in which a comparison is made between results from this new tensioner model and from a more conventional approach. The comparison considers typical installation parameters as well as an in-depth look at the predicted fatigue damage for the two methods

  20. A fully-automated software pipeline for integrating breast density and parenchymal texture analysis for digital mammograms: parameter optimization in a case-control breast cancer risk assessment study

    Science.gov (United States)

    Zheng, Yuanjie; Wang, Yan; Keller, Brad M.; Conant, Emily; Gee, James C.; Kontos, Despina

    2013-02-01

    Estimating a woman's risk of breast cancer is becoming increasingly important in clinical practice. Mammographic density, estimated as the percent of dense (PD) tissue area within the breast, has been shown to be a strong risk factor. Studies also support a relationship between mammographic texture and breast cancer risk. We have developed a fullyautomated software pipeline for computerized analysis of digital mammography parenchymal patterns by quantitatively measuring both breast density and texture properties. Our pipeline combines advanced computer algorithms of pattern recognition, computer vision, and machine learning and offers a standardized tool for breast cancer risk assessment studies. Different from many existing methods performing parenchymal texture analysis within specific breast subregions, our pipeline extracts texture descriptors for points on a spatial regular lattice and from a surrounding window of each lattice point, to characterize the local mammographic appearance throughout the whole breast. To demonstrate the utility of our pipeline, and optimize its parameters, we perform a case-control study by retrospectively analyzing a total of 472 digital mammography studies. Specifically, we investigate the window size, which is a lattice related parameter, and compare the performance of texture features to that of breast PD in classifying case-control status. Our results suggest that different window sizes may be optimal for raw (12.7mm2) versus vendor post-processed images (6.3mm2). We also show that the combination of PD and texture features outperforms PD alone. The improvement is significant (p=0.03) when raw images and window size of 12.7mm2 are used, having an ROC AUC of 0.66. The combination of PD and our texture features computed from post-processed images with a window size of 6.3 mm2 achieves an ROC AUC of 0.75.

  1. Diagnosing in building main pipelines

    Energy Technology Data Exchange (ETDEWEB)

    Telegin, L.G.; Gorelov, A.S.; Kurepin, B.N.; Orekhov, V.I.; Vasil' yev, G.G.; Yakovlev, Ye. I.

    1984-01-01

    General principles are examined for technical diagnosis in building main pipelines. A technique is presented for diagnosis during construction, as well as diagnosis of the technical state of the pipeline-construction machines and mechanisms. The survey materials could be used to set up construction of main pipelines.

  2. Richards Bay effluent pipeline

    CSIR Research Space (South Africa)

    Lord, DA

    1986-07-01

    Full Text Available of major concern identified in the effluent are the large volume of byproduct calcium sulphate (phosphogypsum) which would smother marine life, high concentrations of fluoride highly toxic to marine life, heavy metals, chlorinated organic material... ........................ 9 THE RICHARDS BAY PIPELINE ........................................ 16 Environmental considerations ................................... 16 - Phosphogypsum disposal ................................... 16 - Effects of fluoride on locally occurring...

  3. Central oxygen pipeline failure

    African Journals Online (AJOL)

    surgical intensive care unit (ICU), with two patients on full ventilation and ... uncertainty around the cause of the failure and the restoration, .... soon as its level also falls below three tons. Should ... (properly checked and closed prior to each anaesthetic). ... in use at the time of the central oxygen pipeline failure at Tygerberg.

  4. Characteristics of operating pipelines

    Energy Technology Data Exchange (ETDEWEB)

    Gallyamov, A K; Armenskii, E A; Gimaev, R G; Mastobaev, B N; Shammazov, A M

    1977-04-01

    The interval in pressure changes according to operational data for the Kamennyi Log--Perm oil pipeline was determined with the aid of the pattern identification method. This has made it possible to determine pressure changes in the operational process. 2 references, 1 table.

  5. Transient cavitation in pipelines

    NARCIS (Netherlands)

    Kranenburg, C.

    1974-01-01

    The aim of the present study is to set up a one-dimensional mathematical model, which describes the transient flow in pipelines, taking into account the influence of cavitation and free gas. The flow will be conceived of as a three-phase flow of the liquid, its vapour and non-condensible gas. The

  6. Overview of interstate hydrogen pipeline systems

    International Nuclear Information System (INIS)

    Gillette, J.L.; Kolpa, R.L.

    2008-01-01

    The use of hydrogen in the energy sector of the United States is projected to increase significantly in the future. Current uses are predominantly in the petroleum refining sector, with hydrogen also being used in the manufacture of chemicals and other specialized products. Growth in hydrogen consumption is likely to appear in the refining sector, where greater quantities of hydrogen will be required as the quality of the raw crude decreases, and in the mining and processing of tar sands and other energy resources that are not currently used at a significant level. Furthermore, the use of hydrogen as a transportation fuel has been proposed both by automobile manufacturers and the federal government. Assuming that the use of hydrogen will significantly increase in the future, there would be a corresponding need to transport this material. A variety of production technologies are available for making hydrogen, and there are equally varied raw materials. Potential raw materials include natural gas, coal, nuclear fuel, and renewables such as solar, wind, or wave energy. As these raw materials are not uniformly distributed throughout the United States, it would be necessary to transport either the raw materials or the hydrogen long distances to the appropriate markets. While hydrogen may be transported in a number of possible forms, pipelines currently appear to be the most economical means of moving it in large quantities over great distances. One means of controlling hydrogen pipeline costs is to use common rights-of-way (ROWs) whenever feasible. For that reason, information on hydrogen pipelines is the focus of this document. Many of the features of hydrogen pipelines are similar to those of natural gas pipelines. Furthermore, as hydrogen pipeline networks expand, many of the same construction and operating features of natural gas networks would be replicated. As a result, the description of hydrogen pipelines will be very similar to that of natural gas pipelines

  7. Overview of interstate hydrogen pipeline systems.

    Energy Technology Data Exchange (ETDEWEB)

    Gillette, J .L.; Kolpa, R. L

    2008-02-01

    The use of hydrogen in the energy sector of the United States is projected to increase significantly in the future. Current uses are predominantly in the petroleum refining sector, with hydrogen also being used in the manufacture of chemicals and other specialized products. Growth in hydrogen consumption is likely to appear in the refining sector, where greater quantities of hydrogen will be required as the quality of the raw crude decreases, and in the mining and processing of tar sands and other energy resources that are not currently used at a significant level. Furthermore, the use of hydrogen as a transportation fuel has been proposed both by automobile manufacturers and the federal government. Assuming that the use of hydrogen will significantly increase in the future, there would be a corresponding need to transport this material. A variety of production technologies are available for making hydrogen, and there are equally varied raw materials. Potential raw materials include natural gas, coal, nuclear fuel, and renewables such as solar, wind, or wave energy. As these raw materials are not uniformly distributed throughout the United States, it would be necessary to transport either the raw materials or the hydrogen long distances to the appropriate markets. While hydrogen may be transported in a number of possible forms, pipelines currently appear to be the most economical means of moving it in large quantities over great distances. One means of controlling hydrogen pipeline costs is to use common rights-of-way (ROWs) whenever feasible. For that reason, information on hydrogen pipelines is the focus of this document. Many of the features of hydrogen pipelines are similar to those of natural gas pipelines. Furthermore, as hydrogen pipeline networks expand, many of the same construction and operating features of natural gas networks would be replicated. As a result, the description of hydrogen pipelines will be very similar to that of natural gas pipelines

  8. A management systems approach to pipeline integrity

    Energy Technology Data Exchange (ETDEWEB)

    Abes, J. [CC Technologies Canada, Calgary, AB (Canada)

    2008-07-01

    A management systems approach to pipeline integrity was discussed in terms of accident causation models, lessons from accidents, and management systems. Accident causation models include the Heinrich domino theory; epidemiological models; event chain models; and system-based models. A review of the Bellingham pipeline accident showed that if the pipeline had not been weakened by external damage, it likely would have been able to withstand the pressure that occurred on the day of the rupture, and the accident would not have happened. It was also determined that there was inadequate inspection of excavation work during the water treatment plant project and consequently, there was a failure to identify and repair the damage done to the pipeline. The presentation also addressed other findings, such as inaccurate evaluation of in-line pipeline inspection data; failure to manage and protect the supervisory control and data acquisition system (SCADA); and ineffective management oversight of construction and activation of products terminal. The Carlsbad pipeline explosion was also presented as another example of an accident. Several violations by El Paso were cited, including failure to ensure that qualified personnel performed internal corrosion control procedures; failure to perform necessary tests for corrosion; and failure to follow procedures for continuing surveillance of its facilities. Last, the presentation provided a definition of management systems and discussed the characteristics and elements of a management system. These elements included policy and leadership commitment; organizational structure and responsibilities; management of resources; communication plan; document and records management; operational controls; management of change; and continual improvement. 1 fig.

  9. Bauxite slurry pipeline: start up operation

    Energy Technology Data Exchange (ETDEWEB)

    Othon, Otilio; Babosa, Eder; Edvan, Francisco; Brittes, Geraldo; Melo, Gerson; Janir, Joao; Favacho, Orlando; Leao, Marcos; Farias, Obadias [Vale, Rio de Janeiro, RJ (Brazil); Goncalves, Nilton [Anglo Ferrous Brazil S.A., Rio de Janeiro, RJ (Brazil)

    2009-07-01

    The mine of Miltonia is located in Paragominas-PA, in the north of Brazil. Bauxite slurry pipeline starts at the Mine of Miltonia and finishes in the draining installation of Alunorte refinery at the port of Barcarena-PA, located approximately 244km away from the mine. The pipeline runs over seven cities and passes below four great rivers stream beds. The system was designed for an underground 24 inches OD steel pipe to carry 9.9 million dry metric tonnes per annum (dMTAs) of 50.5% solid concentration bauxite slurry, using only one pumping station. The system is composed by four storage tanks and six piston diaphragm pumps, supplying a flow of 1680 m3/h. There is a cathodic protection system along the pipeline extension to prevent external corrosion and five pressure monitoring stations to control hydraulic conditions, there is also a fiber optic cable interconnection between pump station and terminal station. Pipeline Systems Incorporated (PSI) was the designer and followed the commissioning program of the start up operations. This paper will describe the beginning of the pipeline operations, technical aspects of the project, the operational experiences acquired in these two years, the faced problems and also the future planning. (author)

  10. Corrosion induced failure analysis of subsea pipelines

    International Nuclear Information System (INIS)

    Yang, Yongsheng; Khan, Faisal; Thodi, Premkumar; Abbassi, Rouzbeh

    2017-01-01

    Pipeline corrosion is one of the main causes of subsea pipeline failure. It is necessary to monitor and analyze pipeline condition to effectively predict likely failure. This paper presents an approach to analyze the observed abnormal events to assess the condition of subsea pipelines. First, it focuses on establishing a systematic corrosion failure model by Bow-Tie (BT) analysis, and subsequently the BT model is mapped into a Bayesian Network (BN) model. The BN model facilitates the modelling of interdependency of identified corrosion causes, as well as the updating of failure probabilities depending on the arrival of new information. Furthermore, an Object-Oriented Bayesian Network (OOBN) has been developed to better structure the network and to provide an efficient updating algorithm. Based on this OOBN model, probability updating and probability adaptation are performed at regular intervals to estimate the failure probabilities due to corrosion and potential consequences. This results in an interval-based condition assessment of subsea pipeline subjected to corrosion. The estimated failure probabilities would help prioritize action to prevent and control failures. Practical application of the developed model is demonstrated using a case study. - Highlights: • A Bow-Tie (BT) based corrosion failure model linking causation with the potential losses. • A novel Object-Oriented Bayesian Network (OOBN) based corrosion failure risk model. • Probability of failure updating and adaptation with respect to time using OOBN model. • Application of the proposed model to develop and test strategies to minimize failure risk.

  11. Safety installation for preventing pollution by pipelines

    Energy Technology Data Exchange (ETDEWEB)

    Wittgenstein, G F

    1972-10-25

    A safety installation for preventing pollution by pipelines, particularly those used for transporting liquid hydrocarbons, is described. It is applicable to any pipeline, but particularly to underground or submarine pipelines, whether made of steel, plastics, or any other material. The 4 essential objects of the invention are to insure reliable prevention of pollution of the environment due to leakage of a hydrocarbon through cracks in the pipe; to evacuate the leakage flow without delay to a vessel; to signal almost instantaneously the existence of a leak; and to effect remote control of operations by which the dynamic pressure in the pipe is cancelled. Each equipped section consists of a fluid-type jacket of plastic material which surrounds the pipe, which at its ends is sealed off. It is these seals which delimit the sections. (7 claims)

  12. V-GAP: Viral genome assembly pipeline

    KAUST Repository

    Nakamura, Yoji

    2015-10-22

    Next-generation sequencing technologies have allowed the rapid determination of the complete genomes of many organisms. Although shotgun sequences from large genome organisms are still difficult to reconstruct perfect contigs each of which represents a full chromosome, those from small genomes have been assembled successfully into a very small number of contigs. In this study, we show that shotgun reads from phage genomes can be reconstructed into a single contig by controlling the number of read sequences used in de novo assembly. We have developed a pipeline to assemble small viral genomes with good reliability using a resampling method from shotgun data. This pipeline, named V-GAP (Viral Genome Assembly Pipeline), will contribute to the rapid genome typing of viruses, which are highly divergent, and thus will meet the increasing need for viral genome comparisons in metagenomic studies.

  13. V-GAP: Viral genome assembly pipeline

    KAUST Repository

    Nakamura, Yoji; Yasuike, Motoshige; Nishiki, Issei; Iwasaki, Yuki; Fujiwara, Atushi; Kawato, Yasuhiko; Nakai, Toshihiro; Nagai, Satoshi; Kobayashi, Takanori; Gojobori, Takashi; Ototake, Mitsuru

    2015-01-01

    Next-generation sequencing technologies have allowed the rapid determination of the complete genomes of many organisms. Although shotgun sequences from large genome organisms are still difficult to reconstruct perfect contigs each of which represents a full chromosome, those from small genomes have been assembled successfully into a very small number of contigs. In this study, we show that shotgun reads from phage genomes can be reconstructed into a single contig by controlling the number of read sequences used in de novo assembly. We have developed a pipeline to assemble small viral genomes with good reliability using a resampling method from shotgun data. This pipeline, named V-GAP (Viral Genome Assembly Pipeline), will contribute to the rapid genome typing of viruses, which are highly divergent, and thus will meet the increasing need for viral genome comparisons in metagenomic studies.

  14. Speed Control of Pipeline Pig Using the QFT Method Contrôle de la vitesse d’un racleur grâce à la méthode de synthèse QFT

    Directory of Open Access Journals (Sweden)

    Mirshamsi M.

    2012-08-01

    Full Text Available To provide an efficient inspection of pipeline, pigging operations must be executed at a constant speed. This paper presents an efficient and simple method based on Quantitative Feedback Theory (QFT, which is a well-known robust controller scheme, for speed control of a pig with bypass flow in a liquid pipeline. This classical-type controller commands the valve installed in the body of the pig to open or close. Then, the pig is controlled using the amount of bypass flow across its body. For this purpose, the nonlinear dynamic equation of motion of the pig is converted to a family of linear uncertain equivalent plants using Sobhani-Rafeeyan’s method (SR method. Then, for this family of uncertain equivalent plants, a QFT-type controller is synthesized. The presented method is developed for two-dimensional pipelines in two cases. The designed controllers are simulated numerically using the Simulink toolbox of the MATLAB software. The simulation results show that the designed controller can be used for speed control of the pig with good performance when it runs in the liquid pipelines. Pour qu’une inspection de pipeline soit efficace, l’opération de raclage doit être réalisée à vitesse constante. Cet article présente une méthode simple et efficace fondée sur la théorie QFT (Quantitative Feedback Theory, système de régulation robuste bien connu, permettant de contrôler la vitesse d’un racleur avec bypass dans un oléoduc. Ce régulateur classique commande l’ouverture ou la fermeture d’une soupape installée sur le racleur. Le racleur est ensuite contrôlé grâce au volume de fluide qui le traverse. Pour cela, l’équation dynamique non linéaire du mouvement du racleur est convertie en un ensemble de structures linéaires instables équivalentes via la méthode Sobhani-Rafeeyan (méthode SR. Puis, un régulateur de type QFT est synthétisé. La méthode présentée est conçue pour des pipelines bidimensionnels dans deux

  15. Energy geopolitics and Iran-Pakistan-India gas pipeline

    International Nuclear Information System (INIS)

    Verma, Shiv Kumar

    2007-01-01

    With the growing energy demands in India and its neighboring countries, Iran-Pakistan-India (IPI) gas pipeline assumes special significance. Energy-deficient countries such as India, China, and Pakistan are vying to acquire gas fields in different parts of the world. This has led to two conspicuous developments: first, they are competing against each other and secondly, a situation is emerging where they might have to confront the US and the western countries in the near future in their attempt to control energy bases. The proposed IPI pipeline is an attempt to acquire such base. However, Pakistan is playing its own game to maximize its leverages. Pakistan, which refuses to establish even normal trading ties with India, craves to earn hundreds of millions of dollars in transit fees and other annual royalties from a gas pipeline which runs from Iran's South Pars fields to Barmer in western India. Pakistan promises to subsidize its gas imports from Iran and thus also become a major forex earner. It is willing to give pipeline related 'international guarantees' notwithstanding its record of covert actions in breach of international law (such as the export of terrorism) and its reluctance to reciprocally provide India what World Trade Organization (WTO) rules obligate it to do-Most Favored Nation (MFN) status. India is looking at the possibility of using some set of norms for securing gas supply through pipeline as the European Union has already initiated a discussion on the issue. The key point that is relevant to India's plan to build a pipeline to source gas from Iran relates to national treatment for pipeline. Under the principle of national treatment which also figures in relation to foreign direct investment (FDI), the country through which a pipeline transits should provide some level of security to the transiting pipeline as it would have provided to its domestic pipelines. This paper will endeavor to analyze, first, the significance of this pipeline for India

  16. Energy geopolitics and Iran-Pakistan-India gas pipeline

    Energy Technology Data Exchange (ETDEWEB)

    Verma, Shiv Kumar [Political Geography Division, Center for International Politics, Organization and Disarmament, School of International Studies, Jawaharlal Nehru University, New Delhi 110067 (India)

    2007-06-15

    With the growing energy demands in India and its neighboring countries, Iran-Pakistan-India (IPI) gas pipeline assumes special significance. Energy-deficient countries such as India, China, and Pakistan are vying to acquire gas fields in different parts of the world. This has led to two conspicuous developments: first, they are competing against each other and secondly, a situation is emerging where they might have to confront the US and the western countries in the near future in their attempt to control energy bases. The proposed IPI pipeline is an attempt to acquire such base. However, Pakistan is playing its own game to maximize its leverages. Pakistan, which refuses to establish even normal trading ties with India, craves to earn hundreds of millions of dollars in transit fees and other annual royalties from a gas pipeline which runs from Iran's South Pars fields to Barmer in western India. Pakistan promises to subsidize its gas imports from Iran and thus also become a major forex earner. It is willing to give pipeline related 'international guarantees' notwithstanding its record of covert actions in breach of international law (such as the export of terrorism) and its reluctance to reciprocally provide India what World Trade Organization (WTO) rules obligate it to do-Most Favored Nation (MFN) status. India is looking at the possibility of using some set of norms for securing gas supply through pipeline as the European Union has already initiated a discussion on the issue. The key point that is relevant to India's plan to build a pipeline to source gas from Iran relates to national treatment for pipeline. Under the principle of national treatment which also figures in relation to foreign direct investment (FDI), the country through which a pipeline transits should provide some level of security to the transiting pipeline as it would have provided to its domestic pipelines. This paper will endeavor to analyze, first, the significance of this pipeline for India

  17. Pipeline corridors through wetlands

    International Nuclear Information System (INIS)

    Zimmerman, R.E.; Wilkey, P.L.; Isaacson, H.R.

    1992-01-01

    This paper presents preliminary findings from six vegetational surveys of gas pipeline rights-of-way (ROW) through wetlands and quantifies the impacts of a 20-year-old pipeline ROW through a boreal forest wetland. Six sites of various ages were surveyed in ecosystems ranging from coastal marsh to forested wetland. At all sites except one, both the number and the percentage of wetland species on the Row approximated or exceeded those in the adjacent natural area. The boreal forest study showed that (1) adjacent natural wetland areas were not altered in type; (2) water sheet flow restriction had been reversed by nature; (3) no nonnative plant species invaded the natural area; (4) three-quarters of the ROW area was a wetland, and (5) the ROW increased diversity

  18. Global offshore pipeline markets

    International Nuclear Information System (INIS)

    Knight, R.; Parsons, B.

    2001-01-01

    In this article, two experts forecast a recovery in the offshore pipeline market followed by accelerating growth. A number of clearly definable macro trends are affecting the world offshore oil and gas industry and will be of considerable significance to the offshore pipelines industry. The authors' view is of markets that show every chance of enjoying long-term growth prospects driven by the fundamentals of a continuing increase in demand for offshore oil and gas. The offshore industry however has a highly cyclical nature, due to the impact of variations in oil and gas prices and the differing state of maturity of individual regions. Therefore those companies that are able to offer the widest range of pipe types and diameters and methods of installation across the greatest range of geographic markets are likely to prosper most. Thus, this continues to be a market best suited to those able to operate on a global scale and make a corporate commitment measured in decades

  19. Russia: the pipeline diplomacy

    International Nuclear Information System (INIS)

    Bourdillon, Y.

    2005-01-01

    First world producer of oil and gas, Russia wishes to use its mastery of energy distribution to recover its great power status. The oil and gas pipelines network is the basement used by Russia to build up its hegemony in Europe. The Russian oil and gas companies are also carrying out a long-term strategy of international expansion, in particular thanks to investments in the neighboring countries for the building of new infrastructures or the purchase of oil refineries. (J.S.)

  20. Pipeline Optimization Program (PLOP)

    Science.gov (United States)

    2006-08-01

    the framework of the Dredging Operations Decision Support System (DODSS, https://dodss.wes.army.mil/wiki/0). PLOP compiles industry standards and...efficiency point ( BEP ). In the interest of acceptable wear rate on the pump, industrial standards dictate that the flow Figure 2. Pump class as a function of...percentage of the flow rate corresponding to the BEP . Pump Acceptability Rules. The facts for pump performance, industrial standards and pipeline and

  1. Pipeline network and environment

    International Nuclear Information System (INIS)

    Oliveira Nascimento, I.; Wagner, J.; Silveira, T.

    2012-01-01

    The Rio de Janeiro is one of 27 units of Brazil. It is located in the eastern portion of the Southeast and occupies an area of 43 696.054 km², being effectively the 3rd smallest state in Brazil. This state in recent years has suffered from erosion problems caused by the deployment of the network pipeline. The deployment pipeline is part of the activities related to the oil industry has caused a more intense conflict between the environment and economic activities, modifying the soil structure and distribution of surface and subsurface flows. This study aimed to analyze the erosion caused by the removal of soil for the deployment of pipeline transportation, with the consequences of the emergence of numerous gullies, landslides and silting of rivers. For the development of this study were performed bibliographic research, field work, mapping and digital preparation of the initial diagnosis of active processes and what the consequent environmental impacts. For these reasons, we conclude that the problems could be avoided or mitigated if there was a prior geological risk management. (author)

  2. A study on an autonomous pipeline maintenance robot, 8

    International Nuclear Information System (INIS)

    Fukuda, Toshio; Hosokai, Hidemi; Niitsu, Shunichi; Kaneshige, Masanori; Iwasaki, Shinnosuke.

    1990-01-01

    This paper deals with the path planning and sensing planning expert system with learning functions for the pipeline inspection and maintenance robot, Mark IV. The robot can carry out inspection tasks to autonomously detect malfunctions in a plant pipeline system. Furthermore, the robot becomes more intelligent by adding the following functions: (1) the robot, Mark IV, is capable of inspecting surfaces of storage tanks as well as pipeline outer surfaces; (2) in path planning, the robot has a learning function using information generated in the past such as a moving path, task level and control commands of the robot; (3) in inspecting a pipeline system with plant equipment such as valves, franges, T- and L-joints, the robot is capable of inspecting continuous surfaces in pipeline. Thus, together with the improved path planning expert system (PPES) and the sensing planning expert system (SPES), the Mark IV robot becomes intelligent enough to automatically carry out given inspection tasks. (author)

  3. United States petroleum pipelines: An empirical analysis of pipeline sizing

    Science.gov (United States)

    Coburn, L. L.

    1980-12-01

    The undersizing theory hypothesizes that integrated oil companies have a strong economic incentive to size the petroleum pipelines they own and ship over in a way that means that some of the demand must utilize higher cost alternatives. The DOJ theory posits that excess or monopoly profits are earned due to the natural monopoly characteristics of petroleum pipelines and the existence of market power in some pipelines at either the upstream or downstream market. The theory holds that independent petroleum pipelines owned by companies not otherwise affiliated with the petroleum industry (independent pipelines) do not have these incentives and all the efficiencies of pipeline transportation are passed to the ultimate consumer. Integrated oil companies on the other hand, keep these cost efficiencies for themselves in the form of excess profits.

  4. Pipelines : moving biomass and energy

    Energy Technology Data Exchange (ETDEWEB)

    Kumar, A. [Alberta Univ., Edmonton, AB (Canada). Dept. of Mechanical Engineering

    2006-07-01

    Moving biomass and energy through pipelines was presented. Field sourced biomass utilization for fuel was discussed in terms of competing cost factors; economies of scale; and differing fuel plant sizes. The cost versus scale in a bioenergy facility was illustrated in chart format. The transportation cost of biomass was presented as it is a major component of total biomass processing cost and is in the typical range of 25-45 per cent of total processing costs for truck transport of biomass. Issues in large scale biomass utilization, scale effects in transportation, and components of transport cost were identified. Other topics related to transportation issues included approaches to pipeline transport; cost of wood chips in pipeline transport; and distance variable cost of transporting wood chips by pipeline. Practical applications were also offered. In addition, the presentation provided and illustrated a model for an ethanol plant supplied by truck transport as well as a sample configuration for 19 truck based ethanol plants versus one large facility supplied by truck plus 18 pipelines. Last, pipeline transport of bio-oil and pipeline transport of syngas was discussed. It was concluded that pipeline transport can help in reducing congestion issues in large scale biomass utilization and that it can offer a means to achieve large plant size. Some current research at the University of Alberta on pipeline transport of raw biomass, bio-oil and hydrogen production from biomass for oil sands and pipeline transport was also presented. tabs., figs.

  5. A computational genomics pipeline for prokaryotic sequencing projects.

    Science.gov (United States)

    Kislyuk, Andrey O; Katz, Lee S; Agrawal, Sonia; Hagen, Matthew S; Conley, Andrew B; Jayaraman, Pushkala; Nelakuditi, Viswateja; Humphrey, Jay C; Sammons, Scott A; Govil, Dhwani; Mair, Raydel D; Tatti, Kathleen M; Tondella, Maria L; Harcourt, Brian H; Mayer, Leonard W; Jordan, I King

    2010-08-01

    New sequencing technologies have accelerated research on prokaryotic genomes and have made genome sequencing operations outside major genome sequencing centers routine. However, no off-the-shelf solution exists for the combined assembly, gene prediction, genome annotation and data presentation necessary to interpret sequencing data. The resulting requirement to invest significant resources into custom informatics support for genome sequencing projects remains a major impediment to the accessibility of high-throughput sequence data. We present a self-contained, automated high-throughput open source genome sequencing and computational genomics pipeline suitable for prokaryotic sequencing projects. The pipeline has been used at the Georgia Institute of Technology and the Centers for Disease Control and Prevention for the analysis of Neisseria meningitidis and Bordetella bronchiseptica genomes. The pipeline is capable of enhanced or manually assisted reference-based assembly using multiple assemblers and modes; gene predictor combining; and functional annotation of genes and gene products. Because every component of the pipeline is executed on a local machine with no need to access resources over the Internet, the pipeline is suitable for projects of a sensitive nature. Annotation of virulence-related features makes the pipeline particularly useful for projects working with pathogenic prokaryotes. The pipeline is licensed under the open-source GNU General Public License and available at the Georgia Tech Neisseria Base (http://nbase.biology.gatech.edu/). The pipeline is implemented with a combination of Perl, Bourne Shell and MySQL and is compatible with Linux and other Unix systems.

  6. Environmental impact assessment in the pipeline industry. Experiences with the UK north western ethylene pipeline

    Energy Technology Data Exchange (ETDEWEB)

    Ryde, A.

    1997-12-31

    The north western ethylene pipeline is the final link between Shell`s oil and gas fields in the North Sea and its petrochemical complexes in Cheshire. The natural gas from which ethylene is obtained comes from the Brent and central fields in the North Sea. Environmental impacts are discussed in this paper covering topics as follow: Regulatory and legal aspects; environmental assessment during planning and design; environmental control during construction; environmental management during operation; environmental controls at sensitive sites on the north western ethylene pipeline: some examples. 11 refs., 2 figs.

  7. Environmental impact assessment in the pipeline industry. Experiences with the UK north western ethylene pipeline

    International Nuclear Information System (INIS)

    Ryder, A.

    1997-01-01

    The north western ethylene pipeline is the final link between Shell's oil and gas fields in the North Sea and its petrochemical complexes in Cheshire. The natural gas from which ethylene is obtained comes from the Brent and central fields in the North Sea. Environmental impacts are discussed in this paper covering topics as follow: Regulatory and legal aspects; environmental assessment during planning and design; environmental control during construction; environmental management during operation; environmental controls at sensitive sites on the north western ethylene pipeline: some examples. 11 refs., 2 figs

  8. software for natural gas pipeline design and simulation

    African Journals Online (AJOL)

    Global Journal

    2017-01-17

    Jan 17, 2017 ... investment and operating cost required for natural gas pipeline transmission ... In the early development of the natural gas transmission industry, pressures were low and ..... The software has an error control capability in.

  9. Planned and proposed pipeline regulations

    International Nuclear Information System (INIS)

    De Leon, C.

    1992-01-01

    The Research and Special Programs Administration administers the Natural Gas Pipeline Safety Act of 1968 (NGPSA) and the Hazardous Liquid Pipeline Safety Act of 1979 (HLPSA). The RSPA issues and enforces design, construction, operation and maintenance regulations for natural gas pipelines and hazardous liquid pipelines. This paper discusses a number of proposed and pending safety regulations and legislative initiatives currently being considered by the RSPA and the US Congress. Some new regulations have been enacted. The next few years will see a great deal of regulatory activity regarding natural gas and hazardous liquid pipelines, much of it resulting from legislative requirements. The office of Pipeline Safety is currently conducting a study to streamline its operations. This study is analyzing the office's business, social and technical operations with the goal of improving overall efficiency, effectiveness, productivity and job satisfaction to meet the challenges of the future

  10. Incidental electric heating of pipelines

    Energy Technology Data Exchange (ETDEWEB)

    Sonninskii, A V; Sirotin, A M; Vasiliev, Y N

    1981-04-01

    VNIIgaz has improved the conventional Japanese SECT pipeline-heating system, which uses a small steel tube that contains an insulated heater/conductor and is welded to the top of the pipeline. The improved version has two insulated electric heaters - one on the top and the other on the bottom of the pipeline - located inside steel angle irons that are welded to the pipeline. A comparison of experimental results from heating a 200-ft pipeline with both systems at currents of up to 470 A clearly demonstrated the better heating efficiency of the VNIIgaz unit. The improved SECT system would be suitable for various types of pipelines, including gas lines, in the USSR's far north regions.

  11. Hydrocarbons pipeline transportation risk assessment

    Science.gov (United States)

    Zanin, A. V.; Milke, A. A.; Kvasov, I. N.

    2018-04-01

    The pipeline transportation applying risks assessment issue in the arctic conditions is addressed in the paper. Pipeline quality characteristics in the given environment has been assessed. To achieve the stated objective, the pipelines mathematical model was designed and visualized by using the software product SOLIDWORKS. When developing the mathematical model the obtained results made possible to define the pipeline optimal characteristics for designing on the Arctic sea bottom. In the course of conducting the research the pipe avalanche collapse risks were examined, internal longitudinal and circular loads acting on the pipeline were analyzed, as well as the water impact hydrodynamic force was taken into consideration. The conducted calculation can contribute to the pipeline transport further development under the harsh climate conditions of the Russian Federation Arctic shelf territory.

  12. 75 FR 5244 - Pipeline Safety: Integrity Management Program for Gas Distribution Pipelines; Correction

    Science.gov (United States)

    2010-02-02

    ... Management Program for Gas Distribution Pipelines; Correction AGENCY: Pipeline and Hazardous Materials Safety... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration 49 CFR Part... Regulations to require operators of gas distribution pipelines to develop and implement integrity management...

  13. 77 FR 2126 - Pipeline Safety: Implementation of the National Registry of Pipeline and Liquefied Natural Gas...

    Science.gov (United States)

    2012-01-13

    ... Natural Gas Operators AGENCY: Pipeline and Hazardous Materials Safety Administration (PHMSA), DOT. ACTION... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No...: ``Pipeline Safety: Updates to Pipeline and Liquefied Natural Gas Reporting Requirements.'' The final rule...

  14. 78 FR 41991 - Pipeline Safety: Potential for Damage to Pipeline Facilities Caused by Flooding

    Science.gov (United States)

    2013-07-12

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No...: Pipeline and Hazardous Materials Safety Administration (PHMSA); DOT. ACTION: Notice; Issuance of Advisory... Gas and Hazardous Liquid Pipeline Systems. Subject: Potential for Damage to Pipeline Facilities Caused...

  15. 78 FR 41496 - Pipeline Safety: Meetings of the Gas and Liquid Pipeline Advisory Committees

    Science.gov (United States)

    2013-07-10

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No. PHMSA-2013-0156] Pipeline Safety: Meetings of the Gas and Liquid Pipeline Advisory Committees AGENCY: Pipeline and Hazardous Materials Safety Administration (PHMSA), DOT. ACTION: Notice of advisory committee...

  16. Gas pipeline crossings over water bodies: analysis of environmental impact mitigation coming from controls adopted; Implantacao de travessias de gasodutos em corpos d'agua: analise da mitigacao dos impactos ambientais decorrente das medidas de controle adotadas

    Energy Technology Data Exchange (ETDEWEB)

    Serricchio, Claudio; Caldas, Flaviana V. [PETROBRAS, Rio de Janeiro, RJ (Brazil); Souza, Izabel C. de [TELSAN Engenharia e Servicos Ltda, Vitoria, ES (Brazil); Paz, Claudio [IMC Saste - Construcoes, Servicos e Comercio Ltda., Sao Paulo, SP (Brazil); Veronez, Fernanda A. [Centro Federal de Educacao Tecnologica do Espirito Santo (CEFET-ES), Vitoria, ES (Brazil)

    2008-07-01

    Among the implemented measures to control environmental impacts during the crossings of water courses, can be mentioned: the laying of pipe under provisional passages, the execution of physical barriers, the provisional and definitive drainage systems, the riverbank water bodies revegetation after the completion of works and the monitoring of water quality in the previous phases and after the execution of works for the implementation of the crossing. This study examined the effectiveness of these measures using as a case study the works of gas pipelines: Cacimbas (ES) - Vitoria (ES) and Cabiunas (RJ) - Vitoria (ES). In general it was observed that the measures taken were effective. In the case of implemented crossings with the conventional method of monitoring, the results confirmed an expected temporary increase in turbidity, resulting from the removal of sediment of the river bed in order to open the ditch. This impact was shown to be well tolerated by the body water, after crossing back to normal conditions. Regarding the Monitoring of Water Quality, which usually increases the cost of the venture, this was not an effective instrument for the control of impacts due to the time needed to obtain the results of samples taken compared to the time of execution of the crossing. (author)

  17. 49 CFR 195.210 - Pipeline location.

    Science.gov (United States)

    2010-10-01

    ... 49 Transportation 3 2010-10-01 2010-10-01 false Pipeline location. 195.210 Section 195.210 Transportation Other Regulations Relating to Transportation (Continued) PIPELINE AND HAZARDOUS MATERIALS SAFETY... PIPELINE Construction § 195.210 Pipeline location. (a) Pipeline right-of-way must be selected to avoid, as...

  18. Slurry pipeline technology: an overview

    Energy Technology Data Exchange (ETDEWEB)

    Chapman, Jay P. [Pipeline Systems Incorporated (PSI), Belo Horizonte, MG (Brazil); Lima, Rafael; Pinto, Daniel; Vidal, Alisson [Ausenco do Brasil Engenharia Ltda., Nova Lima, MG (Brazil). PSI Div.

    2009-12-19

    Slurry pipelines represent an economical and environmentally friendly transportation means for many solid materials. This paper provides an over-view of the technology, its evolution and current Brazilian activity. Mineral resources are increasingly moving farther away from ports, processing plants and end use points, and slurry pipelines are an important mode of solids transport. Application guidelines are discussed. State-of-the-Art technical solutions such as pipeline system simulation, pipe materials, pumps, valves, automation, telecommunications, and construction techniques that have made the technology successful are presented. A discussion of where long distant slurry pipelines fit in a picture that also includes thickened and paste materials pipe lining is included. (author)

  19. Pipeline, utilities to spend $127 million on scada systems

    International Nuclear Information System (INIS)

    Anon.

    1993-01-01

    Spending for new or upgraded supervisory control and data acquisition (scada) systems and for additional remote-terminal units (RTUs) by North American pipelines and utilities will exceed $165 million through February 1996. New and updated scada systems will total 122 at a cost of more than $127 million; 143 RTU add-on projects will cost more than $38 million. Pipelines and combined utilities/pipelines will spend $89.5 million for 58 scada-system projects and $30.2 million for RTU add-on projects. Scada systems are computerized hardware and software systems that perform monitoring and control functions. In gas utilities, these systems perform functions normally associated with gas transmission and distribution as well as production-plant process control. In gas and oil pipelines, the systems perform these functions as well as such specialized functions as batch tracking, leak detection, and gas load flow

  20. 76 FR 44985 - Pipeline Safety: Potential for Damage to Pipeline Facilities Caused by Flooding

    Science.gov (United States)

    2011-07-27

    .... PHMSA-2011-0177] Pipeline Safety: Potential for Damage to Pipeline Facilities Caused by Flooding AGENCY... liquid pipelines to communicate the potential for damage to pipeline facilities caused by severe flooding... pipelines in case of flooding. ADDRESSES: This document can be viewed on the Office of Pipeline Safety home...

  1. Bears and pipeline construction in Alaska

    Energy Technology Data Exchange (ETDEWEB)

    Follmann, E.H.; Hechtel, J.L. (Univ. of Alaska Fairbanks, AK (USA))

    1990-06-01

    Serious problems were encountered with bears during construction of the 1274-km trans-Alaska oil pipeline between Prudhoe Bay and Valdez. This multi-billion-dollar project traversed both black bear (Ursus americanus Pallas) and grizzly bear (U. arctos L.) habitat throughtout its entire length. Plans for dealing with anticipated problems with bears were often inadequate. Most (71%) problems occurred north of the Yukon River in a previously roadless wilderness where inadequate refuse disposal and widespread animal feeding created dangerous situations. Of the 192 officially reported bear problems associated with the Trans-Alaska Pipeline System (TAPS) (1971-1979), about 65% involved the presence of bears in camps or dumps, 13% the feeding of bears on garbage or handouts, 10% property damage or economic loss, 7% bears under and in buildings, and only 5% charges by bears. Remarkably, no bear-related injuries were reported, suggesting that bears became accustomed to people and did not regard them as a threat. Following construction of the TAPS there have been proposals for pipelines to transport natural gas from Prudhoe Bay to southern and Pacific-rim markets. Based on past experience, some animal control measures were developed during the planning phase for the authorized gas pipeline route in Alaska. Fences installed around 100-person survey camps were found to be effective in deterring bears in two traditionally troublesome areas. 16 refs., 7 figs., 1 tab.

  2. Pipelines, utilities plan over 150 scada systems

    International Nuclear Information System (INIS)

    Anon.

    1992-01-01

    This paper reports that North American pipelines and utilities will spend more than $170 million on new or upgraded supervisory control and data acquisition (scada) systems during the 30-month period that commenced Sept. 1. Another $12.5 million will be spent on peripherals and consulting. Among the 699 various projects to be implemented during the period, companies will install 151 scada systems, add 154 remote-terminal units (RTUs) to existing scada units, and install 196 communications systems. Scada systems are computerized hardware and software systems that perform a set of monitoring and control functions. In gas utilities, these systems perform functions normally associated with gas transmission and distribution as well as production plant process control. In gas and oil pipelines, the systems perform these functions as well as such specialized functions as batch tracking, leak detection, and gas load flow

  3. Automatic pipeline operation using Petri Nets

    Energy Technology Data Exchange (ETDEWEB)

    Moreira, Guilherme O. [PETROBRAS TRANSPORTE S.A., Rio de Janeiro, RJ (Brazil)

    2009-07-01

    A pipeline operation requires several actions, attention and time from the control room operator in each of its operating phases. This article proposition is to use automation as something more than a remote control, drastically reducing the number of repetitive and routine actions needed from the operator to start and stop the system, granting more time for system supervision, decision making during critical conditions and avoiding errors caused due to the need of several actions being executed in a short period of time. To achieve these objectives the pipeline operation will be modeled as a Petri Net consisting of states, event and actions. A methodology for converting this Petri Net into a Ladder controller code will also be proposed. (author)

  4. 77 FR 19799 - Pipeline Safety: Pipeline Damage Prevention Programs

    Science.gov (United States)

    2012-04-02

    ... noted ``when the oil pipeline industry developed the survey for its voluntary spill reporting system...) [cir] The American Public Gas Association (APGA) [cir] The Association of Oil Pipelines (AOPL) [cir... the contrary, all 50 states in the United States have a law designed to prevent excavation damage to...

  5. Hydrogeological considerations in northern pipeline development. [Permafrost affected by hot or chilled pipeline

    Energy Technology Data Exchange (ETDEWEB)

    Harlan, R L

    1974-11-01

    Some of the hydrogeological implications of construction and operation of oil and gas pipelines in northern regions of Canada are considered in relation to their potential environmental impacts and those factors affecting the security of the pipeline itself. Although the extent to which water in permafrost participates in the subsurface flow regime has not been fully demonstrated, the role of liquid as well as vapor transport in frozen earth materials can be shown from theory to be highly significant; water movement rates in frozen soil are on the same order as those in unsaturated, unfrozen soil. Below 0/sup 0/C, the unfrozen water content in a fine-grained porous medium is dependent on temperature but independent of the total water content. The thermal gradient controls the rate and direction of water movement in permafrost. The groundwater stabilizes the streamflow and in the absence of large lakes provides the main source of flow during the winter. As groundwater is frequently confined by the permafrost, degradation of the permafrost can have significant consequences. The thaw bulb formed around a hot oil pipeline can induce liquefactioned flow of the thawed material. A chilled pipeline could restrict groundwater movement, resulting in buildup of artesian conditions and icings. The liberation and absorption of latent heat on freezing and thawing affects the thermal regime in the ground surface. Recommendations are given for pipeline construction and areas for further study pointed out. (DLC)

  6. Lay Pipeline Abandonment Head during Some

    African Journals Online (AJOL)

    2016-12-01

    Dec 1, 2016 ... is very cruel to the structural integrity of the pipeline structure after ... and properties may be jeopardized should the pipeline structure be used for oil or gas transport when such ... pipelines under bending may alter the material.

  7. Health, safety and environment risk assessment in gas pipelines by indexing method:case of Kermanshah Sanandaj oil pipeline

    Directory of Open Access Journals (Sweden)

    Y. Hamidi

    2009-10-01

    Full Text Available Background and AimsUsing pipelines for oil products transportation involves ranges of safety, health and environmental risks, this option however, is dominant with numerous  advantages. The purpose of this study was; relative risk assessment of abovementioned risk in Kermanshah-Sanandaj Oil Pipeline.MethodsThe method used in this study was Kent Muhlbauer method in which relative risk was assessed using third-party damage, corrosion, design, incorrect operations and leak impact  factor.ResultsOnce applying this method, collection of required data and performing needed experiments, scoring results showed 96 risk segments along the pipeline length in which lengths 100+860, 101+384 and 103+670 had relative risk scores 9.74, 9.82 and 9.91 respectively and therefore these segments were identified as focal risk points and priority for improvement actions.ConclusionRegarding importance of pipeline failure, inspection and regular patrol along the pipeline route, precise control of cathodic protection of pipeline and using communication technologies such as SCADA or optical fibers along the pipeline route were amongst the mostimportant control action suggested by the study.

  8. Pipeline Processing for VISTA

    Science.gov (United States)

    Lewis, J. R.; Irwin, M.; Bunclark, P.

    2010-12-01

    The VISTA telescope is a 4 metre instrument which has recently been commissioned at Paranal, Chile. Equipped with an infrared camera, 16 2Kx2K Raytheon detectors and a 1.7 square degree field of view, VISTA represents a huge leap in infrared survey capability in the southern hemisphere. Pipeline processing of IR data is far more technically challenging than for optical data. IR detectors are inherently more unstable, while the sky emission is over 100 times brighter than most objects of interest, and varies in a complex spatial and temporal manner. To compensate for this, exposure times are kept short, leading to high nightly data rates. VISTA is expected to generate an average of 250 GB of data per night over the next 5-10 years, which far exceeds the current total data rate of all 8m-class telescopes. In this presentation we discuss the pipelines that have been developed to deal with IR imaging data from VISTA and discuss the primary issues involved in an end-to-end system capable of: robustly removing instrument and night sky signatures; monitoring data quality and system integrity; providing astrometric and photometric calibration; and generating photon noise-limited images and science-ready astronomical catalogues.

  9. Accuracy Limitations of Pipelined ADCs

    NARCIS (Netherlands)

    Quinn, P.J.; Roermund, van A.H.M.

    2005-01-01

    In this paper, the key characteristics of the main errors which affect the performance of a switched capacitor pipelined ADC are presented and their effects on the ADC transfer characteristics demonstrated. Clear and concise relationships are developed to aid optimized design of the pipeline ADC and

  10. Kepler Science Operations Center Pipeline Framework

    Science.gov (United States)

    Klaus, Todd C.; McCauliff, Sean; Cote, Miles T.; Girouard, Forrest R.; Wohler, Bill; Allen, Christopher; Middour, Christopher; Caldwell, Douglas A.; Jenkins, Jon M.

    2010-01-01

    The Kepler mission is designed to continuously monitor up to 170,000 stars at a 30 minute cadence for 3.5 years searching for Earth-size planets. The data are processed at the Science Operations Center (SOC) at NASA Ames Research Center. Because of the large volume of data and the memory and CPU-intensive nature of the analysis, significant computing hardware is required. We have developed generic pipeline framework software that is used to distribute and synchronize the processing across a cluster of CPUs and to manage the resulting products. The framework is written in Java and is therefore platform-independent, and scales from a single, standalone workstation (for development and research on small data sets) to a full cluster of homogeneous or heterogeneous hardware with minimal configuration changes. A plug-in architecture provides customized control of the unit of work without the need to modify the framework itself. Distributed transaction services provide for atomic storage of pipeline products for a unit of work across a relational database and the custom Kepler DB. Generic parameter management and data accountability services are provided to record the parameter values, software versions, and other meta-data used for each pipeline execution. A graphical console allows for the configuration, execution, and monitoring of pipelines. An alert and metrics subsystem is used to monitor the health and performance of the pipeline. The framework was developed for the Kepler project based on Kepler requirements, but the framework itself is generic and could be used for a variety of applications where these features are needed.

  11. Condition Monitoring Of Operating Pipelines With Operational Modal Analysis Application

    Directory of Open Access Journals (Sweden)

    Mironov Aleksey

    2015-12-01

    Full Text Available In the petroleum, natural gas and petrochemical industries, great attention is being paid to safety, reliability and maintainability of equipment. There are a number of technologies to monitor, control, and maintain gas, oil, water, and sewer pipelines. The paper focuses on operational modal analysis (OMA application for condition monitoring of operating pipelines. Special focus is on the topicality of OMA for definition of the dynamic features of the pipeline (frequencies and mode shapes in operation. The research was conducted using two operating laboratory models imitated a part of the operating pipeline. The results of finite-element modeling, identification of pipe natural modes and its modification under the influence of virtual failure are discussed. The work considers the results of experimental research of dynamic behavior of the operating pipe models using one of OMA techniques and comparing dynamic properties with the modeled data. The study results demonstrate sensitivity of modal shape parameters to modification of operating pipeline technical state. Two strategies of pipeline repair – with continuously condition-based monitoring with proposed technology and without such monitoring, was discussed. Markov chain reliability models for each strategy were analyzed and reliability improvement factor for proposed technology of monitoring in compare with traditional one was evaluated. It is resumed about ability of operating pipeline condition monitoring by measuring dynamic deformations of the operating pipe and OMA techniques application for dynamic properties extraction.

  12. Security Support in Continuous Deployment Pipeline

    DEFF Research Database (Denmark)

    Ullah, Faheem; Raft, Adam Johannes; Shahin, Mojtaba

    2017-01-01

    Continuous Deployment (CD) has emerged as a new practice in the software industry to continuously and automatically deploy software changes into production. Continuous Deployment Pipeline (CDP) supports CD practice by transferring the changes from the repository to production. Since most of the CDP...... penetration tools. Our findings indicate that the applied tactics improve the security of the major components (i.e., repository, continuous integration server, main server) of a CDP by controlling access to the components and establishing secure connections....

  13. Simulation of high consequence areas for gas pipelines

    OpenAIRE

    Orlando Díaz-Parra; Enrique Vera-López

    2018-01-01

    The gas pipeline is used for the transport of natural gas at a great distance. Risks derived from the handling of a combustible material transported under high pressure, by pipelines that pass close to where people live, makes it necessary to adopt prevention, mitigation and control measures to reduce the effect in case of ignition of a gas leak. This work shows the development of a new mathematical model to determine areas of high consequence and their application, using widely available and...

  14. Maglev crude oil pipeline

    Science.gov (United States)

    Knolle, Ernst G.

    1994-01-01

    This maglev crude oil pipeline consists of two conduits guiding an endless stream of long containers. One conduit carries loaded containers and the other empty returns. The containers are levitated by permanent magnets in repulsion and propelled by stationary linear induction motors. The containers are linked to each other in a manner that allows them, while in continuous motion, to be folded into side by side position at loading and unloading points. This folding causes a speed reduction in proportion to the ratio of container diameter to container length. While in side by side position, containers are opened at their ends to be filled or emptied. Container size and speed are elected to produce a desired carrying capacity.

  15. Shipping Information Pipeline

    DEFF Research Database (Denmark)

    Jensen, Thomas

    to creating a more efficient shipping industry, and a number of critical issues are identified. These include that shipments depend on shipping information, that shipments often are delayed due to issues with documentation, that EDI messages account for only a minor part of the needed information......This thesis applies theoretical perspectives from the Information Systems (IS) research field to propose how Information Technology (IT) can improve containerized shipping. This question is addressed by developing a set of design principles for an information infrastructure for sharing shipping...... information named the Shipping Information Pipeline (SIP). Review of the literature revealed that IS research prescribed a set of meta-design principles, including digitalization and digital collaboration by implementation of Inter-Organizational Systems based on Electronic Data Interchange (EDI) messages...

  16. The Leaking Pipeline

    DEFF Research Database (Denmark)

    Henningsen, Inge; Højgaard, Lis

    2002-01-01

    negotiations of cultural prescriptions of gendered subjectivity and identities, organizational understandings and procedures embedded in specific university cultures, traditional of different science disciplines, and the systemic logic and political rationale of the education and research system....... these positions, and one that maintains that a closer look at the statistics does not support this optimism because women’s percentage in recruitment positions is not increasing as the pool of potential female researchers increases, or to put it metaphorically, “the pipeline is leaking women all along” (Alper...... it identifies and describes a Danish verion of ‘the leaky pipeline’ from analyses of the ratios of women in science from high school through tenured positions. Finally it illustrates the cultural mechanisms at play in this process, based on the results of three studies. The first two analyze the educational...

  17. Northern pipelines : challenges and needs

    Energy Technology Data Exchange (ETDEWEB)

    Dean, D.; Brownie, D. [ProLog Canada Inc., Calgary, AB (Canada); Fafara, R. [TransCanada PipeLines Ltd., Calgary, AB (Canada)

    2007-07-01

    Working Group 10 presented experiences acquired from the operation of pipeline systems in a northern environment. There are currently 3 pipelines operating north of 60, notably the Shiha gas pipeline near Fort Liard, the Ikhil gas pipeline in Inuvik and the Norman Wells oil pipeline. Each has its unique commissioning, operating and maintenance challenges, as well as specific training and logistical support requirements for the use of in-line inspection tools and other forms of integrity assessment. The effectiveness of cathodic protection systems in a permafrost northern environment was also discussed. It was noted that the delay of the Mackenzie Gas Pipeline Project by two to three years due to joint regulatory review may lead to resource constraints for the project as well as competition for already scarce human resources. The issue of a potential timing conflict with the Alaskan Pipeline Project was also addressed as well as land use issues for routing of supply roads. Integrity monitoring and assessment issues were outlined with reference to pipe soil interaction monitoring in discontinuous permafrost; south facing denuded slope stability; base lining projects; and reclamation issues. It was noted that automatic welding and inspection will increase productivity, while reducing the need for manual labour. In response to anticipated training needs, companies are planning to involve and train Aboriginal labour and will provide camp living conditions that will attract labour. tabs., figs.

  18. Natural gas pipeline technology overview.

    Energy Technology Data Exchange (ETDEWEB)

    Folga, S. M.; Decision and Information Sciences

    2007-11-01

    The United States relies on natural gas for one-quarter of its energy needs. In 2001 alone, the nation consumed 21.5 trillion cubic feet of natural gas. A large portion of natural gas pipeline capacity within the United States is directed from major production areas in Texas and Louisiana, Wyoming, and other states to markets in the western, eastern, and midwestern regions of the country. In the past 10 years, increasing levels of gas from Canada have also been brought into these markets (EIA 2007). The United States has several major natural gas production basins and an extensive natural gas pipeline network, with almost 95% of U.S. natural gas imports coming from Canada. At present, the gas pipeline infrastructure is more developed between Canada and the United States than between Mexico and the United States. Gas flows from Canada to the United States through several major pipelines feeding U.S. markets in the Midwest, Northeast, Pacific Northwest, and California. Some key examples are the Alliance Pipeline, the Northern Border Pipeline, the Maritimes & Northeast Pipeline, the TransCanada Pipeline System, and Westcoast Energy pipelines. Major connections join Texas and northeastern Mexico, with additional connections to Arizona and between California and Baja California, Mexico (INGAA 2007). Of the natural gas consumed in the United States, 85% is produced domestically. Figure 1.1-1 shows the complex North American natural gas network. The pipeline transmission system--the 'interstate highway' for natural gas--consists of 180,000 miles of high-strength steel pipe varying in diameter, normally between 30 and 36 inches in diameter. The primary function of the transmission pipeline company is to move huge amounts of natural gas thousands of miles from producing regions to local natural gas utility delivery points. These delivery points, called 'city gate stations', are usually owned by distribution companies, although some are owned by

  19. Effort problem of chemical pipelines

    Energy Technology Data Exchange (ETDEWEB)

    Okrajni, J.; Ciesla, M.; Mutwil, K. [Silesian Technical University, Katowice (Poland)

    1998-12-31

    The problem of the technical state assessment of the chemical pipelines working under mechanical and thermal loading has been shown in the paper. The pipelines effort after the long time operating period has been analysed. Material geometrical and loading conditions of the crack initiation and crack growth process in the chosen object has been discussed. Areas of the maximal effort have been determined. The material structure charges after the long time operating period have been described. Mechanisms of the crack initiation and crack growth in the pipeline elements have been analysed and mutual relations between the chemical and mechanical influences have been shown. (orig.) 16 refs.

  20. Transient evaluation for LPG and oil pipelines

    Energy Technology Data Exchange (ETDEWEB)

    Meliande, Patricia; Do Nascimento, Elson Antonio; Fernandes Lacerda, Rogerio [Federal Fluminense University, Niteroi, RJ (Brazil)

    2010-07-01

    In the last decades, the offshore industry has expanded thanks to the development of equipment for subsea operation. In such installations, protection equipment can be adapted to the installation's design in order to avoid surge pressure effects and ensure safety and integrity of the system, predicting transient effect is therefore very important. The purpose of this study is to predict the surge pressure on refrigerated LPG and gasoline pipelines during unpredicted closure of valves. Flowmaster software was used to carry out the simulations and its results were then validated with a methodology that applied the characteristics method based on Wylie and Streeter assumptions. Results showed that surge pressures during transient effect for both refrigerated LPG and Gasoline pipeline systems were less than the maximum allowable operating pressure and therefore no control dispositive installations are geeded. This study showed that the use of these computer models can ensure the optimization of the system and provide cost effective solutions.

  1. Fishing intensity around the BBL pipeline

    NARCIS (Netherlands)

    Hintzen, Niels

    2016-01-01

    Wageningen Marine Research was requested by ACRB B.V. to investigate the fishing activities around the BBL pipeline. This gas pipeline crosses the southern North Sea from Balgzand (near Den Helder) in the Netherlands to Bacton in the UK (230km). This pipeline is abbreviated as the BBL pipeline. Part

  2. 77 FR 16471 - Pipeline Safety: Implementation of the National Registry of Pipeline and Liquefied Natural Gas...

    Science.gov (United States)

    2012-03-21

    ... Registry of Pipeline and Liquefied Natural Gas Operators AGENCY: Pipeline and Hazardous Materials Safety... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration 49 CFR Parts... Register (75 FR 72878) titled: ``Pipeline Safety: Updates to Pipeline and Liquefied Natural Gas Reporting...

  3. Logistics aspects of petroleum pipeline operations

    Directory of Open Access Journals (Sweden)

    W. J. Pienaar

    2010-11-01

    Full Text Available The paper identifies, assesses and describes the logistics aspects of the commercial operation of petroleum pipelines. The nature of petroleum-product supply chains, in which pipelines play a role, is outlined and the types of petroleum pipeline systems are described. An outline is presented of the nature of the logistics activities of petroleum pipeline operations. The reasons for the cost efficiency of petroleum pipeline operations are given. The relative modal service effectiveness of petroleum pipeline transport, based on the most pertinent service performance measures, is offered. The segments in the petroleum-products supply chain where pipelines can play an efficient and effective role are identified.

  4. Pipelines programming paradigms: Prefab plumbing

    International Nuclear Information System (INIS)

    Boeheim, C.

    1991-08-01

    Mastery of CMS Pipelines is a process of learning increasingly sophisticated tools and techniques that can be applied to your problem. This paper presents a compilation of techniques that can be used as a reference for solving similar problems

  5. Economic evaluation: wood stave pipelines

    Energy Technology Data Exchange (ETDEWEB)

    Rook, M.E.

    The spray of leakage from the wood stave water supply pipeline serving the New England Power Company's (NEPCO) Searsburg hydroelectric development had caused this facility to be dubbed ''The Searsburg Car Wash.'' In July, 1982, excessive leakage from this pipeline prompted NEPCO to perform a technical inspection which would inform the company's decision to replace, repair, or abandon the pipeline. The inspection indicated that a combination of interrelated factors has led to rapid deterioration. The feasibility study, which included a benefit -cost analysis of a times replacement with a continued repair program weighed annually by a risk factor representing the probability of pipeline failure during the replacement period, determined that direct replacement was most advantageous. 4 figures, 1 figures.

  6. Pipeline robots with elastic elements

    Directory of Open Access Journals (Sweden)

    A. Matuliauskas

    2002-10-01

    Full Text Available In the article constructions of the pipeline robots with elastic elements are reviewed and the scheme of new original construction is presented. The mathematical models of a robot with one-dimensional vibration exciter with two degrees of freedom were developed and the equations of movement were formed and written. The mathematical model of the pipeline robot with circular elements is formed and its motion equations are presented.

  7. Optimal valve location in long oil pipelines

    OpenAIRE

    Grigoriev, A.; Grigorieva, N.V.

    2007-01-01

    We address the valve location problem, one of the basic problems in design of long oil pipelines. Whenever a pipeline is depressurized, the shutoff valves block the oil flow and seal the damaged part of the pipeline. Thus, the quantity of oil possibly contaminating the area around the pipeline is determined by the volume of the damaged section of the pipeline between two consecutive valves. Then, ecologic damage can be quantified by the amount of leaked oil and the environmental characteristi...

  8. Crude oil pipeline expansion summary

    International Nuclear Information System (INIS)

    2005-02-01

    The Canadian Association of Petroleum Producers has been working with producers to address issues associated with the development of new pipeline capacity from western Canada. This document presents an assessment of the need for additional oil pipeline capacity given the changing mix of crude oil types and forecasted supply growth. It is of particular interest to crude oil producers and contributes to current available information for market participants. While detailed, the underlying analysis does not account for all the factors that may come into play when individual market participants make choices about which expansions they may support. The key focus is on the importance of timely expansion. It was emphasized that if pipeline expansions lags the crude supply growth, then the consequences would be both significant and unacceptable. Obstacles to timely expansion are also discussed. The report reviews the production and supply forecasts, the existing crude oil pipeline infrastructure, opportunities for new market development, requirements for new pipeline capacity and tolling options for pipeline development. tabs., figs., 1 appendix

  9. Solving an unpiggable pipeline challenge

    Energy Technology Data Exchange (ETDEWEB)

    Walker, James R. [GE Oil and Gas, PII Pipeline Solutions, Cramlington Northumberland (United Kingdom); Kern, Michael [National Grid, New Hampshire (United Kingdom)

    2009-07-01

    Technically, any pipeline can be retrofitted to enable in line inspection. Sensibly however, the expense of excavations and construction of permanent facilities have been, in many cases, exceedingly prohibitive. Even where traditional modifications are feasible from engineering perspectives, flow interruption may not be an option - either because they are critical supply lines or because the associated lost revenues could be nearly insurmountable. Savvy pipeline integrity managers know the safety issue that is at stake over the long term. They are also well aware of the accuracy benefits that high-quality in-line inspection data offer over potentially supply disruptive alternatives such as hydrostatic testing. To complicate matters further, many operators, particularly in the US, now face regulatory pressure to assess the integrity of their yet-uninspected pipelines located in highly populated areas. This paper describes an important project National Grid undertook that made use of a unique pipeline access method that did not require permanent installation of expensive facilities required for in line inspection of a pipeline previously considered 'unpiggable'. Since the pipeline was located in an urban area, flow disruption had to be minimized. This paper will define the project background, its challenges, outcomes and lessons learned for the future. (author)

  10. Putting the coal slurry pipelines to the test

    Energy Technology Data Exchange (ETDEWEB)

    Sauermann, H B

    1978-03-01

    This paper deals with the advantages and disadvantages of coal slurry pipelines and describes coal slurry tests undertaken in three test circuits with 100, 200 and 250 mm diameter pipes. The test results from the test circuits were used to scale-up pressure gradients to larger pipe diameters. The construction and installation of hydraulic transport pipelines is simple and requires a minimum of space. The crossing of rivers, roads, railways or any other obstacles is comparatively easy. The operation, supervision and maintenance of a pipeline is simple since any pipeline can be easily adapted for fully automatic control. For this reason manpower requirements are small resulting in only small increases in operating costs during the life of a pipeline. This is an attractive feature in any economy troubled by inflationary trends. In transporting a commodity such as coal the quantities handled are usually large and the distances are long. The profitability of hydraulic transportation systems benefits from such operating conditions. Even though the various components of a slurry transport system, such as the slurrying facilities at the mine end and the dewatering facilities at the utilization end, are complex, their reliability is high. Against the advantages, the following limitations can be visualized: It is practically impossible to transport solids other than those for which the pipeline was designed; in this regard, road and rail transportation is more versatile. The solids throughput through a pipeline cannot be economically increased beyond its design throughput. Pipelining involves the use of fluids, in most cases water, which in some instances may not be readily available.

  11. Simulation of high consequence areas for gas pipelines

    Directory of Open Access Journals (Sweden)

    Orlando Díaz-Parra

    2018-01-01

    Full Text Available The gas pipeline is used for the transport of natural gas at a great distance. Risks derived from the handling of a combustible material transported under high pressure, by pipelines that pass close to where people live, makes it necessary to adopt prevention, mitigation and control measures to reduce the effect in case of ignition of a gas leak. This work shows the development of a new mathematical model to determine areas of high consequence and their application, using widely available and easy to use software, such as Google Earth and Excel, to determine and visualize the area up to which the level of radiation can affect the integrity of people and buildings. The model takes into account the pressure drop into the gas pipeline from the compression station, the gas leakage rate and possible forms of gas ignition. This development is an alternative to the use of specialized software and highly trained personnel. The simulation is applied to a traced of the Miraflores-Tunja gas pipeline, using a macro developed in Excel to determine the impact area and compare it with the coordinates of the vulnerable areas. The zones where these areas intersect are constituted in high consequence areas and are identified along with the sections of the pipeline that affect them, to provide the operator with a risk analysis tool for the determination and visualization of the gas pipeline and its environment.

  12. 76 FR 28326 - Pipeline Safety: National Pipeline Mapping System Data Submissions and Submission Dates for Gas...

    Science.gov (United States)

    2011-05-17

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration 49 CFR 191... Reports AGENCY: Pipeline and Hazardous Materials Safety Administration (PHMSA), DOT. ACTION: Issuance of... Pipeline and Hazardous Materials Safety Administration (PHMSA) published a final rule on November 26, 2010...

  13. 75 FR 45591 - Pipeline Safety: Notice of Technical Pipeline Safety Advisory Committee Meetings

    Science.gov (United States)

    2010-08-03

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration 49 CFR Part... Committee Meetings AGENCY: Pipeline and Hazardous Materials Safety Administration (PHMSA); DOT. ACTION... safety standards, risk assessments, and safety policies for natural gas pipelines and for hazardous...

  14. 77 FR 36606 - Pipeline Safety: Government/Industry Pipeline Research and Development Forum, Public Meeting

    Science.gov (United States)

    2012-06-19

    ...: Threat Prevention --Working Group 2: Leak Detection/Mitigation & Storage --Working Group 3: Anomaly... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket ID PHMSA-2012-0146] Pipeline Safety: Government/Industry Pipeline Research and Development Forum, Public...

  15. Gathering pipeline methane emissions in Fayetteville shale pipelines and scoping guidelines for future pipeline measurement campaigns

    Directory of Open Access Journals (Sweden)

    Daniel J. Zimmerle

    2017-11-01

    Full Text Available Gathering pipelines, which transport gas from well pads to downstream processing, are a sector of the natural gas supply chain for which little measured methane emissions data are available. This study performed leak detection and measurement on 96 km of gathering pipeline and the associated 56 pigging facilities and 39 block valves. The study found one underground leak accounting for 83% (4.0 kg CH4/hr of total measured emissions. Methane emissions for the 4684 km of gathering pipeline in the study area were estimated at 402 kg CH4/hr [95 to 1065 kg CH4/hr, 95% CI], or 1% [0.2% to 2.6%] of all methane emissions measured during a prior aircraft study of the same area. Emissions estimated by this study fall within the uncertainty range of emissions estimated using emission factors from EPA’s 2015 Greenhouse Inventory and study activity estimates. While EPA’s current inventory is based upon emission factors from distribution mains measured in the 1990s, this study indicates that using emission factors from more recent distribution studies could significantly underestimate emissions from gathering pipelines. To guide broader studies of pipeline emissions, we also estimate the fraction of the pipeline length within a basin that must be measured to constrain uncertainty of pipeline emissions estimates to within 1% of total basin emissions. The study provides both substantial insight into the mix of emission sources and guidance for future gathering pipeline studies, but since measurements were made in a single basin, the results are not sufficiently representative to provide methane emission factors at the regional or national level.

  16. Energy geopolitics and Iran-Pakistan-India gas pipeline

    Energy Technology Data Exchange (ETDEWEB)

    Verma, Shiv Kumar [Political Geography Division, Center for International Politics, Organization and Disarmament, School of International Studies, Jawaharlal Nehru University, New Delhi 110067 (India)]. E-mail: vermajnu@gmail.com

    2007-06-15

    With the growing energy demands in India and its neighboring countries, Iran-Pakistan-India (IPI) gas pipeline assumes special significance. Energy-deficient countries such as India, China, and Pakistan are vying to acquire gas fields in different parts of the world. This has led to two conspicuous developments: first, they are competing against each other and secondly, a situation is emerging where they might have to confront the US and the western countries in the near future in their attempt to control energy bases. The proposed IPI pipeline is an attempt to acquire such base. However, Pakistan is playing its own game to maximize its leverages. Pakistan, which refuses to establish even normal trading ties with India, craves to earn hundreds of millions of dollars in transit fees and other annual royalties from a gas pipeline which runs from Iran's South Pars fields to Barmer in western India. Pakistan promises to subsidize its gas imports from Iran and thus also become a major forex earner. It is willing to give pipeline related 'international guarantees' notwithstanding its record of covert actions in breach of international law (such as the export of terrorism) and its reluctance to reciprocally provide India what World Trade Organization (WTO) rules obligate it to do-Most Favored Nation (MFN) status. India is looking at the possibility of using some set of norms for securing gas supply through pipeline as the European Union has already initiated a discussion on the issue. The key point that is relevant to India's plan to build a pipeline to source gas from Iran relates to national treatment for pipeline. Under the principle of national treatment which also figures in relation to foreign direct investment (FDI), the country through which a pipeline transits should provide some level of security to the transiting pipeline as it would have provided to its domestic pipelines. This paper will endeavor to analyze, first, the significance of this

  17. 77 FR 45417 - Pipeline Safety: Inspection and Protection of Pipeline Facilities After Railway Accidents

    Science.gov (United States)

    2012-07-31

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No... Accidents AGENCY: Pipeline and Hazardous Materials Safety Administration (PHMSA); DOT. [[Page 45418

  18. New territory for NGL pipelines

    International Nuclear Information System (INIS)

    Turner, C.L.; Billings, F.E.

    1994-01-01

    Even though the NGL pipeline industry appears mature, new geographic territory exists for expansion of NGL pipelines. However, the most fertile territory that must be pursued is the collective opportunities to better link the existing NGL industry. Associations like the Gas Processors Association can not perform the role demanded by a need to share information between the links of the chain on a more real time basis. The Association can not substitute for picking up the phone or calling a meeting of industry participants to discuss proposed changes in policies and procedures. All stakeholders must participate in squeezing out the inefficiencies of the industry. Some expansion and extension of NGL pipelines will occur in the future without ownership participation or commitments from the supply and demand businesses. However, significant expansions linking new supply sources and demand markets will only be made as the supply and demand businesses share long-term strategies and help define the pipeline opportunity. The successful industries of the twenty-first century will not be dominated by a single profitable sector, but rather by those industries which foster cooperation as well as competition. A healthy NGL industry will be comprised of profitable supply businesses and profitable demand businesses, linked together by profitable pipeline businesses

  19. Emergency preparedness of OSBRA Pipeline

    Energy Technology Data Exchange (ETDEWEB)

    Magalhaes, Milton P.; Torres, Carlos A.R.; Almeida, Francisco J.C. [TRANSPETRO, Rio de Janeiro, RJ (Brazil)

    2009-07-01

    This paper presents the experience of PETROBRAS Transporte S. A. - TRANSPETRO in the preparation for emergencies in the OSBRA pipeline, showing specific aspects and solutions developed. The company has a standardized approach for the emergency management, based on risk analysis studies, risk management plan and contingency plans. To cover almost 1,000 km of pipeline, the Company avails of Emergency Response Centers and Environmental Defense Center, located at strategic points. In order to achieve preparation, fire fighting training and oil leakage elimination training are provided. Additionally, simulation exercises are performed, following a schedule worked out according to specific criteria and guidelines. As a conclusion, a picture is presented of the evolution of the preparation for emergencies in the OSBRA System which bears the enormous responsibility of transporting flammable products for almost 1,000 km of pipeline, crossing 40 municipalities, 3 states and the Federal District. (author)

  20. Caspian Pipeline Consortium, Bellwether of Russia's Investment climate?

    International Nuclear Information System (INIS)

    Dellecker, A.

    2008-01-01

    The Caspian Pipeline Consortium (CPC), a shipper-owned oil pipeline carrying Caspian oil to Russia's Black Sea port of Novorossyisk, remains to this day the only oil export pipeline on Russian territory that is not under the control of the state company Transneft. Completed in 2001, the CPC was, from the start, the product of a fragile balance of power between states eager to maintain control of hydrocarbon flows and private companies able to finance the necessary infrastructure. Despite its economic success, the future of the CPC currently hinges on a share-holding dispute pitting Russia against private shareholders. This essay places the CPC dossier in the broader context of Russia's investment climate and argues that the dispute's dynamic is an important bellwether of the Russian energy policy. (author)

  1. 77 FR 51848 - Pipeline Safety: Information Collection Activities

    Science.gov (United States)

    2012-08-27

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No... Program for Gas Distribution Pipelines. DATES: Interested persons are invited to submit comments on or.... These regulations require operators of hazardous liquid pipelines and gas pipelines to develop and...

  2. 78 FR 5866 - Pipeline Safety: Annual Reports and Validation

    Science.gov (United States)

    2013-01-28

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket ID PHMSA-2012-0319] Pipeline Safety: Annual Reports and Validation AGENCY: Pipeline and Hazardous Materials... 2012 gas transmission and gathering annual reports, remind pipeline owners and operators to validate...

  3. 78 FR 46560 - Pipeline Safety: Class Location Requirements

    Science.gov (United States)

    2013-08-01

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration 49 CFR Part... class location requirements for gas transmission pipelines. Section 5 of the Pipeline Safety, Regulatory... and, with respect to gas transmission pipeline facilities, whether applying IMP requirements to...

  4. 75 FR 53733 - Pipeline Safety: Information Collection Activities

    Science.gov (United States)

    2010-09-01

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No. PHMSA-2010-0246] Pipeline Safety: Information Collection Activities AGENCY: Pipeline and Hazardous... liquefied natural gas, hazardous liquid, and gas transmission pipeline systems operated by a company. The...

  5. 77 FR 15453 - Pipeline Safety: Information Collection Activities

    Science.gov (United States)

    2012-03-15

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No... information collection titled, ``Gas Pipeline Safety Program Certification and Hazardous Liquid Pipeline... collection request that PHMSA will be submitting to OMB for renewal titled, ``Gas Pipeline Safety Program...

  6. pipelines cathodic protection design methodologies for impressed

    African Journals Online (AJOL)

    HOD

    oil and gas pipelines corrosion in the United State of. American alone ... or preventing external corrosion of pipeline steels and other metallic .... 2.1 Materials and Impressed Current Design. Carbon steel ..... Research Analysis, Vol. 2, pp 2277 ...

  7. Natural disasters and the gas pipeline system.

    Science.gov (United States)

    1996-11-01

    Episodic descriptions are provided of the effects of the Loma Prieta earthquake (1989) on the gas pipeline systems of Pacific Gas & Electric Company and the Cit of Palo Alto and of the Northridge earthquake (1994) on Southern California Gas' pipeline...

  8. 75 FR 63774 - Pipeline Safety: Safety of On-Shore Hazardous Liquid Pipelines

    Science.gov (United States)

    2010-10-18

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration 49 CFR Part... Pipelines AGENCY: Pipeline and Hazardous Materials Safety Administration (PHMSA), Department of... Gas Pipeline Safety Act of 1968, Public Law 90-481, delegated to DOT the authority to develop...

  9. 77 FR 61825 - Pipeline Safety: Notice of Public Meeting on Pipeline Data

    Science.gov (United States)

    2012-10-11

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket ID... program performance measures for gas distribution, gas transmission, and hazardous liquids pipelines. The... distribution pipelines (49 CFR 192.1007(e)), gas transmission pipelines (49 CFR 192.945) and hazardous liquids...

  10. GASVOL 18'' gas pipeline - risk based inspection study

    Energy Technology Data Exchange (ETDEWEB)

    Bjoernoey, Ola H.; Etterdal, Birger A. [Det Norske Veritas (DNV), Oslo (Norway); Guarize, Rosimar; Oliveira, Luiz F.S. [Det Norske Veritas (DNV) (Brazil); Faertes, Denise; Dias, Ricardo [TRANSPETRO - PETROBRAS Transporte S.A., Rio de Janeiro, RJ (Brazil)

    2003-07-01

    This paper describes a risk based approach and inspection planning as part of the Pipeline Integrity Management (PIM) system for the 95.5 km long 18'' GASVOL gas pipeline in the South eastern region of Brazil transporting circa 5 000 000 m3 dry gas per day. Pipeline systems can be subject to several degradation mechanisms and inspection and monitoring are used to ensure system integrity. Modern pipeline regulations and codes are normally based on a core safety or risk philosophy. The detailed design requirements presented in design codes are practical interpretations established so as to fulfill these core objectives. A given pipeline, designed, constructed and installed according to a pipeline code is therefore the realization of a structure, which, along its whole length, meets the applicable safety objectives of that code. The main objective of Pipeline Integrity Management (PIM) is to control and document the integrity of the pipeline for its whole service life, and to do this in a cost-effective manner. DNV has a specific approach to RBI planning, starting with an initial qualitative assessment where pipelines and damage type are ranked according to risk and potential risk reduction by an inspection and then carried forward to a quantitative detailed assessment where the level of complexity and accuracy can vary based on availability of information and owner needs. Detailed assessment requires significant effort in data gathering. The findings are dependent upon the accuracy of the inspection data, and on DNV's interpretation of the pipeline reference system and simplifications in the inspection data reported. The following specific failure mechanisms were investigated: internal corrosion, external corrosion, third party interference, landslides and black powder. RBI planning, in general words, is a 'living process'. In order to optimize future inspections, it is essential that the analyses utilize the most recent information regarding

  11. California Natural Gas Pipelines: A Brief Guide

    Energy Technology Data Exchange (ETDEWEB)

    Neuscamman, Stephanie [Lawrence Livermore National Lab. (LLNL), Livermore, CA (United States); Price, Don [Lawrence Livermore National Lab. (LLNL), Livermore, CA (United States); Pezzola, Genny [Lawrence Livermore National Lab. (LLNL), Livermore, CA (United States); Glascoe, Lee [Lawrence Livermore National Lab. (LLNL), Livermore, CA (United States)

    2013-01-22

    The purpose of this document is to familiarize the reader with the general configuration and operation of the natural gas pipelines in California and to discuss potential LLNL contributions that would support the Partnership for the 21st Century collaboration. First, pipeline infrastructure will be reviewed. Then, recent pipeline events will be examined. Selected current pipeline industry research will be summarized. Finally, industry acronyms are listed for reference.

  12. Proceedings of the 5. biennial international pipeline conference, IPC 2004 : the power of technology

    International Nuclear Information System (INIS)

    Paulson, K.; Kraft, H.; Hopkins, P.

    2004-01-01

    The fifth international pipeline conference provided a forum for experts in the pipeline industry, academia and governments to discuss new technologies and approaches to pipeline transport. Presentations focused on a wide range of issues related to pipeline engineering. The conference was divided into 16 main sessions: (1) compression and pump technologies, (2) corrosion protection and analysis techniques, (3) pipeline design and construction, (4) environmental issues, (5) database development, (6) emerging issues and innovative projects, (7) inspection techniques, (8) integrity management, (9) joining, (10) materials, (11) offshore issues, (12) operations and maintenance, (13) pipeline automation and measurement, (14) pipelining in northern environments, (15) risk and reliability, (16) standards and regulations. The presentations provided up-to-date information related to future technology trends as well as recent innovations and practices. Pipeline design standards and new pipeline materials using high strength steels and reinforced composite plastic coatings were also reviewed. Other sessions discussed emerging technologies for inspection, quality control, ultrasonic testing, and the use of remote sensors. The conference also included a student paper competition. A total of 339 peer reviewed presentations were given at the conference, all of which were indexed separately for inclusion in this database. refs., tabs., fig.

  13. Bio-Docklets: virtualization containers for single-step execution of NGS pipelines.

    Science.gov (United States)

    Kim, Baekdoo; Ali, Thahmina; Lijeron, Carlos; Afgan, Enis; Krampis, Konstantinos

    2017-08-01

    Processing of next-generation sequencing (NGS) data requires significant technical skills, involving installation, configuration, and execution of bioinformatics data pipelines, in addition to specialized postanalysis visualization and data mining software. In order to address some of these challenges, developers have leveraged virtualization containers toward seamless deployment of preconfigured bioinformatics software and pipelines on any computational platform. We present an approach for abstracting the complex data operations of multistep, bioinformatics pipelines for NGS data analysis. As examples, we have deployed 2 pipelines for RNA sequencing and chromatin immunoprecipitation sequencing, preconfigured within Docker virtualization containers we call Bio-Docklets. Each Bio-Docklet exposes a single data input and output endpoint and from a user perspective, running the pipelines as simply as running a single bioinformatics tool. This is achieved using a "meta-script" that automatically starts the Bio-Docklets and controls the pipeline execution through the BioBlend software library and the Galaxy Application Programming Interface. The pipeline output is postprocessed by integration with the Visual Omics Explorer framework, providing interactive data visualizations that users can access through a web browser. Our goal is to enable easy access to NGS data analysis pipelines for nonbioinformatics experts on any computing environment, whether a laboratory workstation, university computer cluster, or a cloud service provider. Beyond end users, the Bio-Docklets also enables developers to programmatically deploy and run a large number of pipeline instances for concurrent analysis of multiple datasets. © The Authors 2017. Published by Oxford University Press.

  14. Fishing activity near offshore pipelines, 2017

    NARCIS (Netherlands)

    Machiels, Marcel

    2018-01-01

    On the North Sea bottom lie numerous pipelines to link oil- or gas offshore drilling units, - platforms and processing stations on land. Although pipeline tubes are coated and covered with protective layers, the pipelines risk being damaged through man-made hazards like anchor dropping and fishing

  15. Elasticplastic dynamic analysis of pipelines

    International Nuclear Information System (INIS)

    Veloso Filho, D.; Loula, A.F.D.; Guerreiro, J.N.C.

    1982-01-01

    A model for structural analysis of spatial pipelines constituted by material with perfect elastoplastic behavior and submmited to time dependence stress is presented. The spatial discretization is done using the Finite Element method, and for the time integration of movement equations an stable finite difference algorithm is used. (E.G.) [pt

  16. Alternate seismic support for pipeline systems in nuclear power plants

    International Nuclear Information System (INIS)

    Muthumani, K.; Gopalakrishnan, N.; Sathish Kumar, K.; Sreekala, R.; Rama Rao, G.V.; Reddy, G.R.; Parulekar, Y.M.

    2008-01-01

    Failure free design of supporting systems for pipe lines carrying highly toxic or radioactive liquids at very high temperature is an important issue in the safety aspect for a nuclear power plant installation which is a key topic for researchers all around the world. Generally, these pipeline systems are designed to be held rigid by conventional snubber supports for protection from earthquakes. The piping design must balance seismic deformations and other deformations due to thermal effect. A rigid pipeline system using conventional snubber supports always leads to an increase in thermal stresses; hence a rational seismic design for pipeline supporting systems becomes essential. Contrary to this rigid design, it is possible to design a flexible pipeline system and to decrease the seismic response by increasing the damping through the use of passive energy absorbing elements, which dissipate vibration energy. This paper presents the experimental and analytical studies carried out on modeling yielding type elasto-plastic passive energy-absorbing elements to be used in a passive energy-dissipating device for the control of large seismic deformations of pipelines subjected to earthquake loading. (author)

  17. Optimal Energy Consumption Analysis of Natural Gas Pipeline

    Science.gov (United States)

    Liu, Enbin; Li, Changjun; Yang, Yi

    2014-01-01

    There are many compressor stations along long-distance natural gas pipelines. Natural gas can be transported using different boot programs and import pressures, combined with temperature control parameters. Moreover, different transport methods have correspondingly different energy consumptions. At present, the operating parameters of many pipelines are determined empirically by dispatchers, resulting in high energy consumption. This practice does not abide by energy reduction policies. Therefore, based on a full understanding of the actual needs of pipeline companies, we introduce production unit consumption indicators to establish an objective function for achieving the goal of lowering energy consumption. By using a dynamic programming method for solving the model and preparing calculation software, we can ensure that the solution process is quick and efficient. Using established optimization methods, we analyzed the energy savings for the XQ gas pipeline. By optimizing the boot program, the import station pressure, and the temperature parameters, we achieved the optimal energy consumption. By comparison with the measured energy consumption, the pipeline now has the potential to reduce energy consumption by 11 to 16 percent. PMID:24955410

  18. Customer service drives pipelines' reorganization

    International Nuclear Information System (INIS)

    Share, J.

    1997-01-01

    The concept behind formation of Enron Transportation and Storage tells plenty about this new gas industry. When executives at the Enron Gas Pipeline Group considered plans last year to streamline operations by merging the support functions of Transwestern Pipeline and their other wholly owned pipeline company, Northern Natural Gas, seamless customer service was foremost on their agenda. Instead of worrying about whether employees would favor one pipeline over the other, perhaps to the detriment of customers, they simply created a new organization that everyone would swear the same allegiance to. The 17,000-mile, 4.1 Bcf/d Northern system serves the upper Midwest market and two major expansion projects were completed there last year. Transwestern is a 2,700-mile system with an eastward capacity of 1 Bcf/d and westward of 1.5 Bcf/, that traditionally served California markets. It also ties into Texas intrastate markets and, thanks to expansion of the San Juan lateral, to southern Rocky Mountain supplies. Although Enron Corp. continues to position itself as a full-service energy company, the Gas Pipeline Group continues to fuel much of corporate's net income, which was $584 million last year. With ET and S comprising a significant portion of GPG's income, it was vital that the merger of Northern's 950 employees with Transwestern's 250 indeed be a seamless one. It was not easy either psychologically or geographically with main offices in Omaha, NE and Houston as well as operations centers in Minneapolis, MN; Amarillo, TX; W. Des Moines, IA; and Albuquerque, NM. But the results have been gratifying, according to William R. Cordes, President of ET and S and Nancy L. Gardner, Executive Vice President of Strategic Initiatives

  19. Test-system for the control and selection of tests applicable to a weldment and its documentation for assembling the Angra - 2 pipelines

    International Nuclear Information System (INIS)

    Carvalho Nunez, J.I. de; Spiegelberg, N.; Souza Rosa, M. de; Soares Filho, J.C.T.

    1988-01-01

    Due to quality assurance characteristics applicable to the construction of a Nuclear Power Plant, the welding inspection for the piping erection becomes a very well controlled and documented activity. By means of informatic support, a system was developed for the control and selection of testes applicable to a weldment according to the suitable specification. As a result, it is obtained: cost reduction during the project phase, expedition of modifications due to isometric revision, better control and follow-up of inspections activities and piping erection, and the guarantee of the correct interpretation for the applicable specification. (author) [pt

  20. Selection of pipeline steels with an engineering fracture mechanical analysis

    Energy Technology Data Exchange (ETDEWEB)

    Stenbacka, N [Swedish State Power Board, Vaellingby

    1985-01-01

    Selection of pipeline steels is discussed on the basis of two mutually independent failure mechanisms: elastic fracture and plastic collapse. The presentation is restricted to axial flaws. A formal analysis shows that brittle fracture in modern pipelines has no high priority in design, since steels used today have a high fracture toughness. Instead, a case of practical concern is tha plastic collapse mode, where failure is flow stress controlled. Conditions governing this design case are specified. In conjunction with this, criterions for material selection with regard to fracture toughness is presented.

  1. The Kepler Science Operations Center Pipeline Framework Extensions

    Science.gov (United States)

    Klaus, Todd C.; Cote, Miles T.; McCauliff, Sean; Girouard, Forrest R.; Wohler, Bill; Allen, Christopher; Chandrasekaran, Hema; Bryson, Stephen T.; Middour, Christopher; Caldwell, Douglas A.; hide

    2010-01-01

    The Kepler Science Operations Center (SOC) is responsible for several aspects of the Kepler Mission, including managing targets, generating on-board data compression tables, monitoring photometer health and status, processing the science data, and exporting the pipeline products to the mission archive. We describe how the generic pipeline framework software developed for Kepler is extended to achieve these goals, including pipeline configurations for processing science data and other support roles, and custom unit of work generators that control how the Kepler data are partitioned and distributed across the computing cluster. We describe the interface between the Java software that manages the retrieval and storage of the data for a given unit of work and the MATLAB algorithms that process these data. The data for each unit of work are packaged into a single file that contains everything needed by the science algorithms, allowing these files to be used to debug and evolve the algorithms offline.

  2. Calculation of NPP pipeline seismic stability

    International Nuclear Information System (INIS)

    Kirillov, A.P.; Ambriashvili, Yu.K.; Kaliberda, I.V.

    1982-01-01

    A simplified design procedure of seismic pipeline stability of NPP at WWER reactor is described. The simplified design procedure envisages during the selection and arrangement of pipeline saddle and hydraulic shock absorbers use of method of introduction of resilient mountings of very high rigidity into the calculated scheme of the pipeline and performance of calculations with step-by-step method. It is concluded that the application of the design procedure considered permits to determine strains due to seismic loads, to analyze stressed state in pipeline elements and supporting power of pipe-line saddle with provision for seismic loads to plan measures on seismic protection

  3. Radio-frequency slurry-density measurement for dredging pipelines

    NARCIS (Netherlands)

    van Eeten, M.J.C.

    2011-01-01

    Hydraulic dredgers make use of a density meter to measure the instantaneous density in the slurry transport pipeline, primarily for process control and production calculation. the current ‘golden’ standard for slurry density measurement is the radioactive density meter. It is based on a slurry

  4. 78 FR 55775 - Pipeline Safety: Information Collection Activities

    Science.gov (United States)

    2013-09-11

    ... important tool for identifying safety trends in the hazardous liquid pipeline industry. In a Federal... reference of American Petroleum Institute (API) API 1130 (the industry standard on leak detection) which... requests that volume exiting a system during a controlled event not be reported. PHMSA Response: PHMSA does...

  5. Online estimation of wax deposition thickness in single-phase sub-sea pipelines based on acoustic chemometrics: A feasibility study

    OpenAIRE

    Halstensen, Maths; Arvoh, Benjamin Kaku; Amundsen, Lene; Hoffmann, Rainer

    2012-01-01

    Wax deposition in sub-sea oil producing pipelines is a concern to the oil producing companies. The deposition of wax in pipelines can cause serious economic implications if not monitored and controlled. Several researchers have developed models and investigated the deposition of wax in crude oil pipelines. As of today, there is no off the shelf instrument available for reliable online estimation of the wax depo- sition thickness in sub-sea pipelines. Acoustic chemometrics was applied to inves...

  6. Relationship between Pipeline Wall Thickness (Gr. X60) and Water Depth towards Avoiding Failure during Installation

    Science.gov (United States)

    Razak, K. Abdul; Othman, M. I. H.; Mat Yusuf, S.; Fuad, M. F. I. Ahmad; yahaya, Effah

    2018-05-01

    Oil and gas today being developed at different water depth characterized as shallow, deep and ultra-deep waters. Among the major components involved during the offshore installation is pipelines. Pipelines are a transportation method of material through a pipe. In oil and gas industry, pipeline come from a bunch of line pipe that welded together to become a long pipeline and can be divided into two which is gas pipeline and oil pipeline. In order to perform pipeline installation, we need pipe laying barge or pipe laying vessel. However, pipe laying vessel can be divided into two types: S-lay vessel and J-lay vessel. The function of pipe lay vessel is not only to perform pipeline installation. It also performed installation of umbilical or electrical cables. In the simple words, pipe lay vessel is performing the installation of subsea in all the connecting infrastructures. Besides that, the installation processes of pipelines require special focus to make the installation succeed. For instance, the heavy pipelines may exceed the lay vessel’s tension capacities in certain kind of water depth. Pipeline have their own characteristic and we can group it or differentiate it by certain parameters such as grade of material, type of material, size of diameter, size of wall thickness and the strength. For instances, wall thickness parameter studies indicate that if use the higher steel grade of the pipelines will have a significant contribution in pipeline wall thickness reduction. When running the process of pipe lay, water depth is the most critical thing that we need to monitor and concern about because of course we cannot control the water depth but we can control the characteristic of the pipe like apply line pipe that have wall thickness suitable with current water depth in order to avoid failure during the installation. This research will analyse whether the pipeline parameter meet the requirements limit and minimum yield stress. It will overlook to simulate pipe

  7. Russia: the pipeline diplomacy; Russie: la diplomatie du pipeline

    Energy Technology Data Exchange (ETDEWEB)

    Bourdillon, Y

    2005-01-15

    First world producer of oil and gas, Russia wishes to use its mastery of energy distribution to recover its great power status. The oil and gas pipelines network is the basement used by Russia to build up its hegemony in Europe. The Russian oil and gas companies are also carrying out a long-term strategy of international expansion, in particular thanks to investments in the neighboring countries for the building of new infrastructures or the purchase of oil refineries. (J.S.)

  8. Arctic pipeline planning design, construction, and equipment

    CERN Document Server

    Singh, Ramesh

    2013-01-01

    Utilize the most recent developments to combat challenges such as ice mechanics. The perfect companion for engineers wishing to learn state-of-the-art methods or further develop their knowledge of best practice techniques, Arctic Pipeline Planning provides a working knowledge of the technology and techniques for laying pipelines in the coldest regions of the world. Arctic Pipeline Planning provides must-have elements that can be utilized through all phases of arctic pipeline planning and construction. This includes information on how to: Solve challenges in designing arctic pipelines Protect pipelines from everyday threats such as ice gouging and permafrost Maintain safety and communication for construction workers while supporting typical codes and standards Covers such issues as land survey, trenching or above ground, environmental impact of construction Provides on-site problem-solving techniques utilized through all phases of arctic pipeline planning and construction Is packed with easy-to-read and under...

  9. Canadian pipeline contractors in holding pattern

    Energy Technology Data Exchange (ETDEWEB)

    Caron, G [Pe Ben Pipelines Ltd.; Osadchuk, V; Sharp, M; Stabback, J G

    1979-05-21

    A discussion of papers presented at a Pipe Line Contractors Association of Canada convention includes comments by G. Caron (Pe Ben Pipelines Ltd.) on the continued slack in big-inch pipeline construction into 1980 owing mainly to delayed U.S. and Canadian decisions on outstanding Alaska Highway gas pipeline issues and associated gas export bids and on the use of automatic welding for expeditious construction of the northern sections of the Alaska Highway pipeline; by V. Osadchuk (Majestic Wiley Contract. Ltd.) on the liquidation of surplus construction equipment because of these delays; by M. Sharp (Can. North. Pipeline Agency) on the need for close U.S. and Canadian governmental and industrial cooperation to permit an early 1980 start for construction of the prebuild sections of the Alaska pipeline; and by J. G. Stabback (Can. Natl. Energy Board) on the Alaska oil pipeline applications by Foothills Pipe Lines Ltd., Trans Mountain Pipe Line Co. Ltd., and Kitimat Pipe Line Ltd.

  10. Which future for conventional pipeline laying barges?; Quel avenir pour les barges de pose de pipelines conventionnelles ?

    Energy Technology Data Exchange (ETDEWEB)

    Borelli, A.; Perinet, D. [ETPM International (International organizations without location)

    1997-05-01

    The aim of this paper is to study the evolution of conventional pipeline laying barges. The past and todays capacities of some barges are presented in order to follow the evolution of their equipments with time to answer the market needs. The second part outlines the main characteristics of todays market needs. Different analyses are made according to the different means of pipeline laying: conventional, flexible pipes and rigid pipes using unrolling technique. Market trends in these 3 domains show a sensible growth from 1996 to 1997 and are assumed to keep a sustained level during the following years. However, the tendency shows an evolution towards smaller diameter pipes and greater depths. The last part concerns the evolution of laying barges. The most important improvements in pipeline laying industry concern the dynamic positioning, the laying techniques (`S` laying technique), and the rate of laying using real-time control techniques. (J.S.)

  11. A new approach to e-commerce customs control in China: Integrated supply chain - A practical application towards large-scale data pipeline implementation

    NARCIS (Netherlands)

    R. Hu (Rong); Y.H. Tan (Yao Hua); F. Heijmann (Frank)

    2016-01-01

    textabstractDevelopments in e-commerce are presenting new challenges in customs control and China's customs agency is developing a new approach to how it addresses these challenges. China Customs has adopted an integrated supply chain approach to secure international trade lanes and to facilitate

  12. A new approach to e-commerce customs control in China: Integrated supply chain : A practical application towards large-scale data pipeline implementation

    NARCIS (Netherlands)

    Hu, R.; Tan, Y.; Heijmann, F.

    2016-01-01

    Developments in e-commerce are presenting new challenges in customs control and China's customs agency is developing a new approach to how it addresses these challenges. China Customs has adopted an integrated supply chain approach to secure international trade lanes and to facilitate legitimate

  13. New method for control of biological fouling in pipelines based on elevated partial pressures of carbon dioxide or combustion exhaust gases.

    Energy Technology Data Exchange (ETDEWEB)

    B.J. Watten; R.E. Sears; R.F. Bumgardner [U.S. Geological Survey - Leetown Science Center, Kearneysville, WV (United States)

    2005-07-01

    Zebra mussels (Dreissena polymorpha) and Asian clams (Corbicula fluminea) are major macro fouling species of water conduits used in industrial and power station raw water/condensor systems. Control typically involves manual scraping and use of thermal treatment, deoxygenation or biocides. The costs of control and system damage resulting from fouling in the United States alone have been estimated at $1 billion/year. There is a pressing need for new economical and safe control strategies. Aquatic species in general are intolerant to increases in PCO{sub 2} given its effect on water, blood and hemolymph pH. These species are also sensitive to increases in elevated total dissolved gas pressure. The gas bubble disease that develops following exposure can, as with CO{sub 2} exposure, lead to mortality. We are exploiting this sensitivity by developing a control method based on manipulation of PCO{sub 2} or power plant exhaust gas (CO{sub 2}, 14%; SO{sub 2}, 0.3%), i.e., the supersaturation of hemolymph and tissues with gas followed by an induced (short term) pressure release designed to induce formation of gas emboli. SO{sub 2} present in stack gas acts with CO{sub 2} to reduce water and hemolymph pH so as to reduce required exposure periods. System effluents are degassed, CO{sub 2} recovered and pH adjusted if needed with alkaline reagents. Test results indicate the new process is effective at controlling C. fluminea as well as other target species, including crustaceans and fish. Required exposure periods (LT50) are short and decrease with increasing gas supersaturation levels. Gas recovery and reuse methods developed have reduced gas requirements by 85% making the method attractive economically and environmentally. 40 refs., 8 figs., 1 tab.

  14. Use of pipe saks on pipeline construction

    Energy Technology Data Exchange (ETDEWEB)

    Ghio, Alberto F.M.; Caciatori, Angelo [Galvao Engenharia S.A., Sao Paulo, SP (Brazil); Ruschi, Allan A.; Santos, Felipe A. dos; Barros, Horacio B. de; Loureiro, Regis R. [PETROBRAS S.A., Rio de Janeiro, RJ (Brazil)

    2009-07-01

    The use of new technologies applied to pipeline construction and assembling, aimed at enhancing productivity has been searched by PETROBRAS, throughout its subcontractors, assemblers, by transference in the mentioned constructions. Along the construction of Cacimbas Catu Pipeline, Spread 1 A, placed between the Cacimbas Gas Treatment Station (Linhares, ES) and the future Compression Station of Sao Mateus (ES), one, by means of surveys, noticed that the length of flooded or prone to flooding areas was way superior to the ones foreseen in the basic design. One of the broadly used methods for assuring buoyancy control is concreting the pipes. Such method deeply impacts work's logistics in for instance, the pipe stringing work; in this one, a maximum load of two pipes can be transported until the area to applied, what leads to lower productivity and higher risk due to the increase of trips by heavy load trucks. As an alternative to regular concrete, the Pipe Sak System was adopted and such method improved productivity and decreased discontinuities. (author)

  15. Pipeline system for gas centrifuge

    International Nuclear Information System (INIS)

    Masumoto, Tsutomu; Umezawa, Sadao.

    1977-01-01

    Purpose: To enable effective operation for the gas centrifuge cascade system upon failures in the system not by interrupting the operation of all of the centrifuges in the system but by excluding only the failed centrifuges. Constitution: A plurality of gas centrifuges are connected by way of a pipeline and an abnormal detector for the automatic detection of abnormality such as destruction in a vacuum barrel and loss of vacuum is provided to each of the centrifuges. Bypass lines for short-circuitting adjacent centrifuges are provided in the pipelines connecting the centrifuges. Upon generation of abnormality in a centrifuge, a valve disposed in the corresponding bypass is automatically closed or opened by a signal from the abnormal detector to change the gas flow to thereby exclude the centrifuge in abnormality out of the system. This enables to effectively operate the system without interrupting the operation for the entire system. (Moriyama, K.)

  16. Nova Gas's pipeline to Asia

    International Nuclear Information System (INIS)

    Lea, N.

    1996-01-01

    The involvement of the Calgary-based company NOVA Gas International (NGI) in Malaysia's peninsular gas utilization (PGU) project, was described. Phase I and II of the project involved linking onshore gas processing plants with a natural gas transmission system. Phase III of the PGU project was a gas transmission pipeline that began midway up the west coast of peninsular Malaysia to the Malaysia-Thailand border. The complex 549 km pipeline included route selection, survey and soil investigation, archaeological study, environmental impact assessment, land acquisition, meter-station construction, telecommunication systems and office buildings. NGI was the prime contractor on the project through a joint venture with OGP Technical Services, jointly owned by NGI and Petronas, the Thai state oil company. Much of NGI's success was attributed to excellent interpersonal skills, particularly NGI's ability to build confidence and credibility with its Thai partners

  17. Shore approach of Camarupim pipeline

    Energy Technology Data Exchange (ETDEWEB)

    Bernardi, Tiaraju P.; Oliveira Neto, Vasco A. de; Siqueira, Jakson [Petroleo Brasileiro S.A. (PETROBRAS), Rio de Janeiro, RJ (Brazil)

    2009-07-01

    Camarupim Field is located in the northern portion of Espirito Santo Basin and was discovered from the drilling of the well 1-ESS-164 in 2006. It is a gas field which start of the production is in mid of 2009. The production unit will be a FPSO (Floating Production, Storage and Offloading) and the gas will flow through a pipeline with diameter ranging from 12 inches and 24 inches with approximately 60 km long, from the FPSO Cidade de Sao Mateus to UTGC (Unit for Treatment of Gas Cacimbas-Linhares-ES). The FPSO will have processing capacity of 10MMm3/day of gas. Due to the approach of the pipeline in the continental portion, located in an environmental protection area and place of spawning of sea turtles, the connection between the stretch of sea and land pipeline running through a shore approach, known and proven technique of horizontal directional drilling about 950m in length. This paper will be shown the assumptions adopted, the technique employed, the challenges faced by the team and the lessons learned to build the directional hole. (author)

  18. Some technological aspects of the functioning of the Thessalonica-OKTA oil pipeline

    International Nuclear Information System (INIS)

    Zikovski, Toni

    2004-01-01

    Crude oil pipeline Solun-Okta was built according to international technical, ecological and safety standards and enables quick, optimal and continuity supply of OKTA Refinery with crude oil. The building of the pipeline began in 1999, and finished in 2002 with official start-up operation by pumping of first quantity crude oil. After the activation, human environment protection has an important place. A lot of instructions and procedures are prepared especial for this purpose. With a total length about 212 km, pipeline enables transport of crude oil from ECO Refinery to OKTA with a capacity of 2.5 million tons per year. Pipeline is designed for a transport of few types crude oil and their mixtures. Pipeline system has been equipped with sophistic and modern equipment, which will enable quality of the work by controlling and monitoring of the system. (Author)

  19. Some technological aspects for functioning of crude oil pipeline Solun-OKTA

    International Nuclear Information System (INIS)

    Zikovski, Toni

    2005-01-01

    Crude oil pipeline Solun-Okta was built according to international technical, ecological and safety standards and enables quick, optimal and continuity supply of OKTA Refinery with crude oil. The building of the pipeline began in 1999 and finished in 2002 with official start-up operation by pumping of first quantity crude oil. After the activation, human environment protection has an important place. A lot of instructions and procedures are prepared specially for this purpose. With a total length about 212 km, pipeline enables transport of crude oil from ECO Refinery to OKTA with a capacity of 2.5 million tons per year. The pipeline is designed for transport of few types crude oil and their mixtures. The pipeline system has been equipped with sophisticated and modern equipment, which will enable quality of the work by controlling and monitoring of the system. (Author)

  20. Some technological aspects for functioning of crude oil pipeline Solun-Okta

    International Nuclear Information System (INIS)

    Zikovski, Toni

    2005-01-01

    Crude oil pipeline Solun-Okta was built according to international technical, ecological and safety standards and enables quick, optimal and continuity supply of OKTA Refinery with crude oil. The building of the pipeline began in 1999 and finished in 2002 with official start-up operation by pumping of first quantity crude oil. After the activation, human environment protection has an important place. A lot of instructions and procedures are prepared specially for this purpose. With a total length about 212 km, pipeline enables transport of crude oil from ECO Refinery to OKTA with a capacity of 2.5 million tons per year. The pipeline is designed for transport of few types crude oil and their mixtures. The pipeline system has been equipped with sophisticated and modern equipment, which will enable quality of the work by controlling and monitoring of the system. (Author)

  1. Evaluation of satellite technology for pipeline route surveillance and the prevention of third party interference damage

    Energy Technology Data Exchange (ETDEWEB)

    Palmer-Jones, Roland; Hopkins, Phil [Penspen Integrity, Newcastle upon Tyne (United Kingdom)]. E-mail: r.palmer-jones@penspen.com; p.hopkins@penspen.com; Fraser, Andy [Integrated Statistical Solutions (United States)]. E-mail: andy@issquared.co.uk; Dezobry, Jerome [Gas de France, Paris (France)]. E-mail: jerome.dezobry@gazdefrance.com; Merrienboer, Hugo Van [Gasunie, Groningen (Netherlands)]. E-mail: H.A.M.van.Merrienboer@gasunie.nl

    2003-07-01

    The damage caused by Third Party Interference (TPI) is one of the major causes of pipeline failures. Consequently, new technologies for identifying activities that may cause damage to our pipelines are constantly being developed. A recently completed project sponsored by a number of pipeline operators has investigated the use of high-resolution satellites for the integrity management of onshore transmission pipelines. The sponsors were BG Technology (on behalf of Transco), Dansk Olie NatureGas, Gasunie, BP, Gaz de France, Distrigas, and the Health and Safety Executive. The project started with a general review of the satellite technologies available and their potential. The study was then focussed on the identification of activities that might result in damage to the pipeline and the potential of high-resolution optical satellites in identifying hazardous activities. A key element of the study was a comparison with existing surveillance systems, which generally involve regular aerial patrols of the pipeline route. To achieve this a survey was carried out to try and evaluate the costs and benefits of existing systems. In addition a simple model for analysing the cost benefit of pipeline surveillance was constructed, and a functional specification for a surveillance system drafted. Finally the performance of the IKONOS 2 high-resolution satellite system was tested in a controlled experiment using targets placed along a pipeline route. The results of this test were compared with a similar test of helicopter-based surveillance carried out by one of the sponsors. (author)

  2. Analysis of integrity and risk for onshore pipelines; Analise de integridade e risco para dutos onshore

    Energy Technology Data Exchange (ETDEWEB)

    Lima, Marco Aurelio [Det Norske Veritas (DNV), Rio de Janeiro, RJ (Brazil)

    2008-07-01

    The increasing expansion of the oil and gas industry in Brazil, the current legal requirements relating to security, health and environment in the industrial installations, is necessary that the companies, responsible by the operation of pipelines for oil and gas transport, adopt efficient techniques to assure the operational continuity of these of trustworthy form and insurance. To fulfill this important function it is important that the companies implement a management program to control and register the integrity of the pipelines during the all operational life cycle. Inside of this context of management of the integrity of pipelines, the DNV developed the software ORBIT Pipeline with the intention to serve as an important tool to monitor the technique and security condition of the pipeline, to define the frequency and content technician of the inspection program and to recommend the work of intervention or repair in pipeline when necessary. Additionally to these activities that are carried through directly in the ORBIT Pipeline, also an evaluation of the activity of third part and the land/soil movement is made inside of the systematic for analysis of integrity and risk for onshore pipelines performed by DNV. (author)

  3. Risk assessment in gas and oil pipelines based on the fuzzy Bow-tie technique

    Directory of Open Access Journals (Sweden)

    P. Heyrani

    2016-04-01

      Conclusion: Considering the recognized factors leading to destruction of pipelines and their most notable outcomes, instructions on how to control and reduce the potential consequences were suggested, with emphasis on the removal of the most probable causes.

  4. 75 FR 49943 - New Agency Information Collection Activity Under OMB Review: Pipeline System Operator Security...

    Science.gov (United States)

    2010-08-16

    ... INFORMATION CONTACT: Joanna Johnson, Office of Information Technology, TSA-11, Transportation Security... Collection Activity Under OMB Review: Pipeline System Operator Security Information AGENCY: Transportation... System Operator Security Information. Type of Request: New collection. OMB Control Number: Not yet...

  5. Development of high productivity pipeline girth welding

    International Nuclear Information System (INIS)

    Yapp, David; Liratzis, Theocharis

    2010-01-01

    The trend for increased oil and gas consumption implies a growth of long-distance pipeline installations. Welding is a critical factor in the installation of pipelines, both onshore and offshore, and the rate at which the pipeline can be laid is generally determined by the speed of welding. This has resulted in substantial developments in pipeline welding techniques. Arc welding is still the dominant process used in practice, and forge welding processes have had limited successful application to date, in spite of large investments in process development. Power beam processes have also been investigated in detail and the latest laser systems now show promise for practical application. In recent years the use of high strength steels has substantially reduced the cost of pipeline installation, with X70 and X80 being commonly used. This use of high strength pipeline produced by thermomechanical processing has also been researched. They must all meet three requirments, high productivity, satisfactory weld properties, and weld quality

  6. Submarine pipelines and the North Sea environment

    International Nuclear Information System (INIS)

    Haldane, D.; Paul, M.A.; Reuben, R.L.; Side, J.C.

    1992-01-01

    The function and design of pipelines for use on the United Kingdom continental shelf are described. Environmental influences which can threaten the integrity of seabed pipelines in the North Sea include hydrodynamic forces due to residual, tidal and wave currents, the nature of seabed sediments and corrosion by seawater. Damage may be caused to pipelines by interaction with vessel anchors and with fishing gear. Special care has to be taken over the selection of the general area for the landfall of a pipeline and the engineering of the installation where the pipeline comes ashore. Trenching and other protection techniques for pipelines are discussed together with hydrostatic testing and commissioning and subsequent inspection, maintenance and repair. (UK)

  7. Measures for security and supervision of pipelines; Massnahmen zur Pipeline-Sicherheit und -Ueberwachung

    Energy Technology Data Exchange (ETDEWEB)

    Horlacher, Hans-Burkhard [TU Dresden (Germany). Inst. fuer Wasserbau und Technische Hydromechanik; Giesecke, Juergen [Stuttgart Univ. (Germany). Inst. fuer Wasserbau

    2010-07-01

    In a previous publication, the two authors dealt with the hydraulic problems as regards mineral oil pipelines. The present report describes the measures mainly used to guarantee the safety of such pipelines. (orig.)

  8. Lessons Learned from Developing and Operating the Kepler Science Pipeline and Building the TESS Science Pipeline

    Science.gov (United States)

    Jenkins, Jon M.

    2017-01-01

    The experience acquired through development, implementation and operation of the KeplerK2 science pipelines can provide lessons learned for the development of science pipelines for other missions such as NASA's Transiting Exoplanet Survey Satellite, and ESA's PLATO mission.

  9. Strength analysis of copper gas pipeline span

    OpenAIRE

    Ianevski, Philipp

    2016-01-01

    The purpose of the study was to analyze the stresses in a gas pipeline. While analyzing piping systems located inside building were used. Calculation of the strength of a gas pipeline is done by using information of the thickness of pipe walls, by choosing the suitable material, inner and outer diameter for the pipeline. Data for this thesis was collected through various internet sources and different books. From the study and research, the final results were reached and calculations were ...

  10. Preliminary results from the hierarchical glitch pipeline

    International Nuclear Information System (INIS)

    Mukherjee, Soma

    2007-01-01

    This paper reports on the preliminary results obtained from the hierarchical glitch classification pipeline on LIGO data. The pipeline that has been under construction for the past year is now complete and end-to-end tested. It is ready to generate analysis results on a daily basis. The details of the pipeline, the classification algorithms employed and the results obtained with one days analysis on the gravitational wave and several auxiliary and environmental channels from all three LIGO detectors are discussed

  11. Pipeline dreams face up to reality

    International Nuclear Information System (INIS)

    Ryan, Orla

    1999-01-01

    This article gives details of two gas pipelines which are expected to be built in Turkey to meet the estimated demand for gas. The Bluestream joint ENI/Gasprom project pipeline will convey Russian gas across the Black Sea to Turkey, and the PSG joint Bechtel/General Electric venture will bring gas from Turkmenistan to Turkey across the Caspian Sea. Construction of the pipelines and financing aspects are discussed. (uk)

  12. Chile's pipelines - who's out in the cold?

    International Nuclear Information System (INIS)

    Bellhouse, G.

    1998-01-01

    There is a battle on in Northern Chile to supply the region with gas and electricity. Two pipelines and a transmission line are being built, but there is insufficient demand to merit the construction of all of these projects. It is widely believed that the first pipeline to be finished will be the overall winner, but the situation is not that simple. A more sensible conclusion could be the merger of the two pipeline projects, rationalising supply of gas to the region. (Author)

  13. On researching erosion-corrosion wear in pipelines: the rate and residual lifetime estimation

    International Nuclear Information System (INIS)

    Baranenko, V.I.; Yanchenko, Yu.A.; Gulina, O.M.; Dokukin, D.A.

    2010-01-01

    To base the normative document on calculation of pipelines erosive-corrosive wear (ECW) rate and residual lifetime this research of ECW regularities for pearlitic steel NPP pipelines was performed. The estimates of control data treatment statistical procedures efficiency were presented. The influence of the scheme of piping control on the ECW rate and residual lifetime estimation results was demonstrated. The simplified scheme is valid only in case of complete information. It's usage under data uncertainties leads to essential residual lifetime overstating [ru

  14. Thermal expansion absorbing structure for pipeline

    International Nuclear Information System (INIS)

    Nagata, Takashi; Yamashita, Takuya.

    1995-01-01

    A thermal expansion absorbing structure for a pipeline is disposed to the end of pipelines to form a U-shaped cross section connecting a semi-circular torus shell and a short double-walled cylindrical tube. The U-shaped longitudinal cross-section is deformed in accordance with the shrinking deformation of the pipeline and absorbs thermal expansion. Namely, since the central lines of the outer and inner tubes of the double-walled cylindrical tube deform so as to incline, when the pipeline is deformed by thermal expansion, thermal expansion can be absorbed by a simple configuration thereby enabling to contribute to ensure the safety. Then, the entire length of the pipeline can greatly be shortened by applying it to the pipeline disposed in a high temperature state compared with a method of laying around a pipeline using only elbows, which has been conducted so far. Especially, when it is applied to a pipeline for an FBR-type reactor, the cost for the construction of a facility of a primary systems can greater be reduced. In addition, it can be applied to a pipeline for usual chemical plants and any other structures requiring absorption of deformation. (N.H.)

  15. Transmission pipeline calculations and simulations manual

    CERN Document Server

    Menon, E Shashi

    2014-01-01

    Transmission Pipeline Calculations and Simulations Manual is a valuable time- and money-saving tool to quickly pinpoint the essential formulae, equations, and calculations needed for transmission pipeline routing and construction decisions. The manual's three-part treatment starts with gas and petroleum data tables, followed by self-contained chapters concerning applications. Case studies at the end of each chapter provide practical experience for problem solving. Topics in this book include pressure and temperature profile of natural gas pipelines, how to size pipelines for specified f

  16. Acoustic system for communication in pipelines

    Science.gov (United States)

    Martin, II, Louis Peter; Cooper, John F [Oakland, CA

    2008-09-09

    A system for communication in a pipe, or pipeline, or network of pipes containing a fluid. The system includes an encoding and transmitting sub-system connected to the pipe, or pipeline, or network of pipes that transmits a signal in the frequency range of 3-100 kHz into the pipe, or pipeline, or network of pipes containing a fluid, and a receiver and processor sub-system connected to the pipe, or pipeline, or network of pipes containing a fluid that receives said signal and uses said signal for a desired application.

  17. Tubular lining material for pipelines having bends

    Energy Technology Data Exchange (ETDEWEB)

    Moringa, A.; Sakaguchi, Y.; Hyodo, M.; Yagi, I.

    1987-03-24

    A tubular lining material for pipelines having bends or curved portions comprises a tubular textile jacket made of warps and wefts woven in a tubular form overlaid with a coating of a flexible synthetic resin. It is applicable onto the inner surface of a pipeline having bends or curved portions in such manner that the tubular lining material with a binder onto the inner surface thereof is inserted into the pipeline and allowed to advance within the pipeline, with or without the aid of a leading rope-like elongated element, while turning the tubular lining material inside out under fluid pressure. In this manner the tubular lining material is applied onto the inner surface of the pipeline with the binder being interposed between the pipeline and the tubular lining material. The lining material is characterized in that a part of all of the warps are comprised of an elastic yarn around which, over the full length thereof, a synthetic fiber yarn or yarns have been left-and/or right-handedly coiled. This tubular lining material is particularly suitable for lining a pipeline having an inner diameter of 25-200 mm and a plurality of bends, such as gas service pipelines or house pipelines, without occurrence of wrinkles in the lining material in a bend.

  18. A quick guide to pipeline engineering

    CERN Document Server

    Alkazraji, D

    2008-01-01

    Pipeline engineering requires an understanding of a wide range of topics. Operators must take into account numerous pipeline codes and standards, calculation approaches, and reference materials in order to make accurate and informed decisions.A Quick Guide to Pipeline Engineering provides concise, easy-to-use, and accessible information on onshore and offshore pipeline engineering. Topics covered include: design; construction; testing; operation and maintenance; and decommissioning.Basic principles are discussed and clear guidance on regulations is provided, in a way that will

  19. East, West German gas pipeline grids linked

    International Nuclear Information System (INIS)

    Anon.

    1992-01-01

    This paper reports that Ruhrgas AG, Essen, has started up the first large diameter gas pipeline linking the gas grids of former East and West Germany. Ruhrgas last month placed in service a 40 in., 70 km line at Vitzeroda, near Eisenach, linking a new Ruhrgas pipeline in Hesse state with a 330 km gas pipeline built last year in Thuringia and Saxony states by Erdgasversorgungs GmbH (EVG), Leipzig. The new link enables pipeline operator EVG to receive 70 bcf/year of western European gas via Ruhrgas, complementing the 35 bcf/year of gas coming from the Commonwealth of Independent States via Verbundnetz Gas AG (VNG), Leipzig

  20. Better US energy policy in pipeline

    Energy Technology Data Exchange (ETDEWEB)

    1979-11-01

    The article points out that criticism from fellow industrialized nations as well as criticism from oil-producing nations is leading America to a steady rationalization of its energy policy. The Carter Administration's decontrol programs which will alter the prices for domestic oil are applauded. Another good sign is the pipeline to transport gas from Alaskan fields, through Canada, directly to major US market areas. Gas is mentioned as the major alternative to oil available to the US and Canada, but there are many environmental issues and pressure groups to contend with before the project can be begun. Carter appointments to the Federal Reserve and the Treasury are viewed as the sound money brigade taking control - namely those who believe that a major stimulant to the growth of inflation is the growth of money stock without an equivalent growth in goods or services. Finally, the symbiotic relationship between America's inflation troubles and its trade deficit is analyzed.

  1. Alternate current interference in pipeline; Interferencia por corrente alternada em dutos

    Energy Technology Data Exchange (ETDEWEB)

    Oliver, Joao Hipolito de Lima [TRANSPETRO - PETROBRAS Transporte S.A., Rio de Janeiro, RJ (Brazil)

    2003-07-01

    This paper regards to the concerning that the pipeline operators should take in to account to better understand and control the alternate current interference (AC- interference). Pipelines sharing rights-of-way with AC high voltage power lines are subjected to AC interference that can cause risk for personnel, operational safety and environment. The AC-interference shall be evaluated, in such way that mitigating action can be applied in order to assure the pipeline is operated in a safety way. The AC-interference evaluation should take in to account the pipeline and the electrical generation/transmission design data. Three approaches are considered: the coating integrity, the personnel chock hazards and the pipeline integrity. The coating integrity is affected by the possibility of high-voltage be induced on the pipeline during power line current fault. The operation and maintenance personnel can be prone to chock hazards (touch voltage and step voltage), depending upon the level of the induced voltage on the pipeline and the ground current. An induced voltage evaluation is then necessary to identify AC potentials in pipeline higher than the safe criteria. The pipeline integrity is concerning to the possibility of occurring alternate current corrosion (AC-corrosion) on the pipe wall. This kind of corrosion is still been investigated, and although it is less critical than the direct current corrosion, it can happen in specific situation. Parameters that affect AC-corrosion are discussed in this paper. Finely it is presented a brief guide to evaluate the possibility of occurring AC- interference in a pipeline and a mitigation measures summary. (author)

  2. 77 FR 6857 - Pipeline Safety: Notice of Public Meetings on Improving Pipeline Leak Detection System...

    Science.gov (United States)

    2012-02-09

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket ID... installed to lessen the volume of natural gas and hazardous liquid released during catastrophic pipeline... p.m. Panel 3: Considerations for Natural Gas Pipeline Leak Detection Systems 3:30 p.m. Break 3:45 p...

  3. Contemporary methods of emergency repair works on transit pipelines. Repair works on in-service pipelines

    International Nuclear Information System (INIS)

    Olma, T.; Winckowski, J.

    2007-01-01

    The paper presents modern methods and relevant technologies of pipeline failure repairs, basing on TD Williamson technique for hermetic plugging of gas pipelines without interrupting service. Rules for management of emergency situations on the Polish Section of Yamal - Europe Transit Gas Pipeline are being discussed as well. (author)

  4. PipelineDog: a simple and flexible graphic pipeline construction and maintenance tool.

    Science.gov (United States)

    Zhou, Anbo; Zhang, Yeting; Sun, Yazhou; Xing, Jinchuan

    2018-05-01

    Analysis pipelines are an essential part of bioinformatics research, and ad hoc pipelines are frequently created by researchers for prototyping and proof-of-concept purposes. However, most existing pipeline management system or workflow engines are too complex for rapid prototyping or learning the pipeline concept. A lightweight, user-friendly and flexible solution is thus desirable. In this study, we developed a new pipeline construction and maintenance tool, PipelineDog. This is a web-based integrated development environment with a modern web graphical user interface. It offers cross-platform compatibility, project management capabilities, code formatting and error checking functions and an online repository. It uses an easy-to-read/write script system that encourages code reuse. With the online repository, it also encourages sharing of pipelines, which enhances analysis reproducibility and accountability. For most users, PipelineDog requires no software installation. Overall, this web application provides a way to rapidly create and easily manage pipelines. PipelineDog web app is freely available at http://web.pipeline.dog. The command line version is available at http://www.npmjs.com/package/pipelinedog and online repository at http://repo.pipeline.dog. ysun@kean.edu or xing@biology.rutgers.edu or ysun@diagnoa.com. Supplementary data are available at Bioinformatics online.

  5. 76 FR 303 - Pipeline Safety: Safety of On-Shore Hazardous Liquid Pipelines

    Science.gov (United States)

    2011-01-04

    ... leak detection requirements for all pipelines; whether to require the installation of emergency flow... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration 49 CFR Part 195 [Docket ID PHMSA-2010-0229] RIN 2137-AE66 Pipeline Safety: Safety of On-Shore Hazardous Liquid...

  6. Maritimes and northeast pipeline update

    International Nuclear Information System (INIS)

    Langan, P.

    1998-01-01

    Efforts made by Maritimes and Northeast Pipelines to bring the benefits of natural gas to the Maritime's economy was discussed. Some background on the developments that have brought the company to where they are today and an update on all their activities were presented. These activities and operations are expected to impact and affect the region's economy in a positive way. Particular attention was paid to the company's policy on laterals and the positive effects of that policy on the development of natural gas service and future natural gas distribution business in the Maritimes

  7. Integrity management of Brazil-Bolivia gas pipeline to reduce risks due third party damage

    Energy Technology Data Exchange (ETDEWEB)

    Vasconcellos, Carlos Renato Aragonez de; Monte, Oswaldo [PETROBRAS, Rio de Janeiro, RJ (Brazil); Colen, Eustaquio; Cunha, Roberto de Souza; Oliveira, Hudson Regis de [Transportadora Brasileira Gasoduto Bolivia-Brasil, S.A., Rio de Janeiro, RJ (Brazil); Lima, Rogerio de Souza [RSL Consultoria Geoprojetos (Brazil); Schultz Neto, Walter [Milton Braga Assessoria Tecnica (Brazil)

    2005-07-01

    The Bolivia-Brazil Natural Gas Pipeline has 2.600 kilometers from Rio Grande City in Bolivia to Canoas City, in the south of Brazil. The right-of-way crosses a lot of types of topography and areas subjected to various kinds of anthropological actions, like areas in class locations 3, locals under agricultural activities, forests and minerals explorations, and near constructions of highway and railway, industrial constructions, new pipelines in the same right-of -way, channels, dams, that requires special projects to avoid that the gas pipeline could be subject to strengths that were not consider in the original design. The aim of this paper is to present the jobs developed by TBG during seven years of gas pipeline operations, as public awareness program, procedures to design, construct and inspect specials constructions along and near the right-of -way, control of mineral and forest explorations, monitoring and controlling of excavations on the right-of-way to install new pipelines and optical cables, to reduce risks of gas pipeline damage due third party, as a component of TBG' Managing Integrity Gas Pipeline Program. (author)

  8. Field sludge characterization obtained from inner of pipelines

    Energy Technology Data Exchange (ETDEWEB)

    Nava, N.; Sosa, E.; Alamilla, J.L. [Instituto Mexicano del Petroleo, Programa de Integridad de Ductos, Eje Central Lazaro Cardenas Norte 152, San Bartolo Atepehuacan, C.P. 07730 (Mexico); Knigth, C. [PEMEX Refinacion, Avenida Marina Nacional 329, Edificio B-2, Piso 11, C.P. 11311 (Mexico); Contreras, A. [Instituto Mexicano del Petroleo, Programa de Integridad de Ductos, Eje Central Lazaro Cardenas Norte 152, San Bartolo Atepehuacan, C.P. 07730 (Mexico)], E-mail: acontrer@imp.mx

    2009-11-15

    Physicochemical characterization of sludge obtained from refined hydrocarbons transmission pipeline was carried out through Moessbauer spectroscopy and X-ray diffraction. The Moessbauer and X-ray patterns indicate the presence of corrosion products composed of different iron oxide and sulfide phases. Hematite ({alpha}-Fe{sub 2}O{sub 3}), magnetite (Fe{sub 3}O{sub 4}), maghemite ({gamma}-Fe{sub 2}O{sub 3}), magnetic and superparamagnetic goethite ({alpha}-FeOOH), pyrrhotite (Fe{sub 1-x}S), akaganeite ({beta}-FeOOH), and lepidocrocite ({gamma}-FeOOH) were identified as corrosion products in samples obtained from pipeline transporting Magna and Premium gasoline. For diesel transmission pipeline, hematite, magnetite, and magnetic goethite were identified. Corrosion products follow a simple reaction mechanism of steel dissolution in aerated aqueous media at a near-neutral pH. Chemical composition of the corrosion products depends on H{sub 2}O and sulfur inherent in fluids (traces). These results can be useful for decision-making with regard to pipeline corrosion control.

  9. Optimal inspection planning for onshore pipelines subject to external corrosion

    International Nuclear Information System (INIS)

    Gomes, Wellison J.S.; Beck, André T.; Haukaas, Terje

    2013-01-01

    Continuous operation of pipeline systems involves significant expenditures in inspection and maintenance activities. The cost-effective safety management of such systems involves allocating the optimal amount of resources to inspection and maintenance activities, in order to control risks (expected costs of failure). In this context, this article addresses the optimal inspection planning for onshore pipelines subject to external corrosion. The investigation addresses a challenging problem of practical relevance, and strives for using the best available models to describe random corrosion growth and the relevant limit state functions. A single pipeline segment is considered in this paper. Expected numbers of failures and repairs are evaluated by Monte Carlo sampling, and a novel procedure is employed to evaluate sensitivities of the objective function with respect to design parameters. This procedure is shown to be accurate and more efficient than finite differences. The optimum inspection interval is found for an example problem, and the robustness of this optimum to the assumed inspection and failure costs is investigated. It is shown that optimum total expected costs found herein are not highly sensitive to the assumed costs of inspection and failure. -- Highlights: • Inspection, repair and failure costs of pipeline systems considered. • Optimum inspection schedule (OIS) obtained by minimizing total expected life-cycle costs. • Robustness of OIS evaluated w.r.t. estimated costs of inspection and failure. • Accurate non-conservative models of corrosion growth employed

  10. Environmental impact of oil transportation by tankers, pipelines, railway

    International Nuclear Information System (INIS)

    Tsitskishvili, M.S.; Chelidze, M.A.; Kaviladze, I.; Chkhartishvili, A.G.; Tsitskishvili, L.B.; Ninua, T.L.; Kordzaxia, G.I.; Gavasheli, L.; Petriashvili, E.T.; Alania, M.L.; Gigolashvili, Sh.Z.; Kordzakhia, M.O.; Chankotadze, P.

    2005-01-01

    vulnerable. Several cases of railway incidents have occurred during last ten years in Georgia and several tanks with oil have been released in the rivers causing significant contamination. The railway infrastructure needs significant improvement and strict control. The railway tanks for oil transportation should be also technically improved to minimize emissions and risks of leakage. Yet we can not avoid the fact that the railways are very often crossing the populated areas and the risks for the human life in case of collision (e.g. third party intentional actions or operational faults) are high. Very important fact is that the National Plan for Oil Spill Contingency in Georgia is almost 95% focused on off-shore spills and in fact no plan exists for the on-shore spills except the corporative oil spill plans provided by BP for the BTC and WREP pipelines. The Government has in fact no capacity to react on railway related oil spills or leakages from other pipeline systems. The government has no capacity for being involved in oil spill response actions organized by BP in case of spills from the BTC or WREP pipelines. There is no organized governmental system for emergency situations. Even BP has not introduced yet the oil spill related fire response plans (and the fires are highly probable in the cases of oil spills cause by terrorist attacks). The general system for emergency response and particularly system of fire response should be organized in the countries of the Region

  11. Logistics aspects of pipeline transport in the supply of petroleum products

    Directory of Open Access Journals (Sweden)

    Wessel Pienaar

    2008-09-01

    activities are involved in the flow of goods between place of origin and place of consumption or application:Demand forecasting, Facility site selection, Procurement,Materials handling, Packaging, Warehouse management, Inventory management,Order processing, Logistics communications, Transport, Reverse logistics. Because cost is incurred without adding value each time goods are handled (activity 4 at a terminal or storage facility, a primary logistics objective is to eliminate handling wherever possible. With the carriage of crude oil and petroleum products by pipeline this objective is fully met. Commodity intake, haulage, and discharge are combined in one process, usually a remote-controlled operation. Pipeline transport is a non-containerised bulk mode of transport thereby obviating the need for packaging (activity 5 and returning empty containers. Pipelines provide a direct and long-term link between these origins and destinations. If necessary a continuous service can be provided with no need for a return trip or a reverse pumping process (activity 11.The elimination of handling, packaging and reverse logistics activities contribute substantially to the high measure of economies of scale that pipeline transport enjoys. The article provides adscription of each of the eleven logistics activities in the context of pipeline transport. Effective logistics service is a prerequisite to help ensure that customers receive the required products at the desired quality and quantity, where and when needed. The most pertinent determinants of logistics service performance aresuitability, accessibility, goods security, transit time, reliability and flexibility. The article offers a discussion of the extent to which pipeline transport conforms to each of these measures of effectiveness.

  12. Assessing fugitive emissions of CH4 from high-pressure gas pipelines in the UK

    Science.gov (United States)

    Clancy, S.; Worrall, F.; Davies, R. J.; Almond, S.; Boothroyd, I.

    2016-12-01

    Concern over the greenhouse gas impact of the exploitation of unconventional natural gas from shale deposits has caused a spotlight to be shone on to the entire hydrocarbon industry. Numerous studies have developed life-cycle emissions inventories to assess the impact that hydraulic fracturing has upon greenhouse gas emissions. Incorporated within life-cycle assessments are transmission and distribution losses, including infrastructure such as pipelines and compressor stations that pressurise natural gas for transport along pipelines. Estimates of fugitive emissions from transmission, storage and distribution have been criticized for reliance on old data from inappropriate sources (1970s Russian gas pipelines). In this study, we investigate fugitive emissions of CH4 from the UK high pressure national transmission system. The study took two approaches. Firstly, CH4 concentration is detected by driving along roads bisecting high pressure gas pipelines and also along an equivalent distance along a route where no high pressure gas pipeline was nearby. Five pipelines and five equivalent control routes were driven and the test was that CH4 measurements, when adjusted for distance and wind speed, should be greater on any route with a pipe than any route without a pipe. Secondly, 5 km of a high pressure gas pipeline and 5 km of equivalent farmland, were walked and soil gas (above the pipeline where present) was analysed every 7 m using a tunable diode laser. When wind adjusted 92 km of high pressure pipeline and 72 km of control route were drive over a 10 day period. When wind and distance adjusted CH4 fluxes were significantly greater on routes with a pipeline than those without. The smallest leak detectable was 3% above ambient (1.03 relative concentration) with any leaks below 3% above ambient assumed ambient. The number of leaks detected along the pipelines correlate to the estimated length of pipe joints, inferring that there are constant fugitive CH4 emissions from

  13. Numerical Leak Detection in a Pipeline Network of Complex Structure with Unsteady Flow

    Science.gov (United States)

    Aida-zade, K. R.; Ashrafova, E. R.

    2017-12-01

    An inverse problem for a pipeline network of complex loopback structure is solved numerically. The problem is to determine the locations and amounts of leaks from unsteady flow characteristics measured at some pipeline points. The features of the problem include impulse functions involved in a system of hyperbolic differential equations, the absence of classical initial conditions, and boundary conditions specified as nonseparated relations between the states at the endpoints of adjacent pipeline segments. The problem is reduced to a parametric optimal control problem without initial conditions, but with nonseparated boundary conditions. The latter problem is solved by applying first-order optimization methods. Results of numerical experiments are presented.

  14. 78 FR 24309 - Pipeline and Hazardous Materials Safety Administration

    Science.gov (United States)

    2013-04-24

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration List of Special Permit Applications Delayed AGENCY: Pipeline and Hazardous Materials Safety Administration (PHMSA..., Pipeline and Hazardous Materials Safety Administration, U.S. Department of Transportation, East Building...

  15. Oil and Natural Gas Pipelines, North America, 2010, Platts

    Data.gov (United States)

    U.S. Environmental Protection Agency — The Oil and Natural Gas Pipeline geospatial data layer contains gathering, interstate, and intrastate natural gas pipelines, crude and product oil pipelines, and...

  16. 75 FR 32836 - Pipeline Safety: Workshop on Public Awareness Programs

    Science.gov (United States)

    2010-06-09

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket ID... American Public Gas Association Association of Oil Pipelines American Petroleum Institute Interstate... the pipeline industry). Hazardous Liquid Gas Transmission/Gathering Natural Gas Distribution (10...

  17. 75 FR 67807 - Pipeline Safety: Emergency Preparedness Communications

    Science.gov (United States)

    2010-11-03

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No... is issuing an Advisory Bulletin to remind operators of gas and hazardous liquid pipeline facilities... Gas Pipeline Systems. Subject: Emergency Preparedness Communications. Advisory: To further enhance the...

  18. 76 FR 65778 - Pipeline Safety: Information Collection Activities

    Science.gov (United States)

    2011-10-24

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No...: 12,120. Frequency of Collection: On occasion. 2. Title: Recordkeeping for Natural Gas Pipeline... investigating incidents. Affected Public: Operators of natural gas pipeline systems. Annual Reporting and...

  19. 75 FR 13807 - Pipeline Safety: Information Collection Activities

    Science.gov (United States)

    2010-03-23

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No... of Transportation, Pipeline and Hazardous Materials Safety Administration, 1200 New Jersey Avenue, SE...: Updates to Pipeline and Liquefied Natural Gas Reporting Requirements (One Rule). The Notice of Proposed...

  20. 77 FR 61826 - Pipeline Safety: Communication During Emergency Situations

    Science.gov (United States)

    2012-10-11

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No... liquefied natural gas pipeline facilities that operators should immediately and directly notify the Public.... Background Federal regulations for gas, liquefied natural gas (LNG), and hazardous liquid pipeline facilities...

  1. 77 FR 34457 - Pipeline Safety: Mechanical Fitting Failure Reports

    Science.gov (United States)

    2012-06-11

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No... notice provides clarification to owners and operators of gas distribution pipeline facilities when... of a gas distribution pipeline facility to file a written report for any mechanical fitting failure...

  2. Software for pipeline integrity administration

    Energy Technology Data Exchange (ETDEWEB)

    Soula, Gerardo; Perona, Lucas Fernandez [Gie SA., Buenos Aires (Argentina); Martinich, Carlos [Refinaria do Norte S. A. (REFINOR), Tartagal, Provincia de Salta (Argentina)

    2009-07-01

    A Software for 'pipeline integrity management' was developed. It allows to deal with Geographical Information and a PODS database (Pipeline Open database Standard) simultaneously, in a simple and reliable way. The premises for the design were the following: didactic, geo referenced, multiple reference systems. Program skills: 1.PODS+GIS: the PODS database in which the software is based on is completely integrated with the GIS module. 2 Management of different kinds of information: it allows to manage information on facilities, repairs, interventions, physical inspections, geographical characteristics, compliance with regulations, training, offline events, operation measures, O and M information treatment and importing specific data and studies in a massive way. It also assures the integrity of the loaded information. 3 Right of way survey: it allows to verify the class location, ROW occupation, sensitive areas identification and to manage landowners. 4 Risk analysis: it is done in a qualitative way, depending on the entered data, allowing the user to identify the riskiest stretches of the system. Either results from risk analysis, data and consultations made about the database, can be exported to standard formats. (author)

  3. Electrical fingerprint of pipeline defects

    International Nuclear Information System (INIS)

    Mica, Isabella; Polignano, Maria Luisa; Marco, Cinzia De

    2004-01-01

    Pipeline defects are dislocations that connect the source region of the transistor with the drain region. They were widely reported to occur in CMOS, BiCMOS devices and recently in SOI technologies. They can reduce device yield either by affecting the devices functionality or by increasing the current consumption under stand-by conditions. In this work the electrical fingerprint of these dislocations is studied, its purpose is to enable us to identify these defects as the ones responsible for device failure. It is shown that the pipeline defects are responsible for a leakage current from source to drain in the transistors. This leakage has a resistive characteristic and it is lightly modulated by the body bias. It is not sensitive to temperature; vice versa the off-current of a good transistor exhibits the well-known exponential dependence on 1/T. The emission spectrum of these defects was studied and compared with the spectrum of a good transistor. The paper aims to show that the spectrum of a defective transistor is quite peculiar; it shows well defined peaks, whereas the spectrum of a good transistor under saturation conditions is characterized by a broad spectral light emission distribution. Finally the deep-level transient spectroscopy (DLTS) is tried on defective diodes

  4. System reliability of corroding pipelines

    International Nuclear Information System (INIS)

    Zhou Wenxing

    2010-01-01

    A methodology is presented in this paper to evaluate the time-dependent system reliability of a pipeline segment that contains multiple active corrosion defects and is subjected to stochastic internal pressure loading. The pipeline segment is modeled as a series system with three distinctive failure modes due to corrosion, namely small leak, large leak and rupture. The internal pressure is characterized as a simple discrete stochastic process that consists of a sequence of independent and identically distributed random variables each acting over a period of one year. The magnitude of a given sequence follows the annual maximum pressure distribution. The methodology is illustrated through a hypothetical example. Furthermore, the impact of the spatial variability of the pressure loading and pipe resistances associated with different defects on the system reliability is investigated. The analysis results suggest that the spatial variability of pipe properties has a negligible impact on the system reliability. On the other hand, the spatial variability of the internal pressure, initial defect sizes and defect growth rates can have a significant impact on the system reliability.

  5. Increase of ecological safety of the pipeline

    International Nuclear Information System (INIS)

    Dr Movsumov, Sh.N.; Prof Aliyev, F.G.

    2005-01-01

    Full text : For increase of ecological safety of the pipeline, necessary decrease of damage (risk) rendered by the pipeline on surrounding natural environment which depends: on the frequency of damage of the pipeline; on the volume poured oil; on the factor of sensitivity of an environment where flood of oil was. Frequency of damage of the pipeline depends on physico-chemical properties of a material of the pipeline, from its technical characteristics (thickness of a wall, length of a pipe, working pressure), on the seismic area of the district where the pipeline passed and also on the way of lining of the pipeline (underground or overground). The volume poured oil depends on diameter of the received damage, from stability of the pipeline mechanical and other external actions, from an ambient temperature, from capacity of the pipeline, from distance between the latches established in the pipeline, and also from time, necessary for their full closing. The factor of sensitivity of environment depends on geological structure and landscapes of district (mountain, the river, settlements) where passed the pipeline. At designing the pipeline, in report is shown questions of increase of ecological safety of the pipeline are considered at his construction and exploitation. For improvement of ecological safety of the pipeline is necessary to hold the following actions: Ecological education of the public, living near along a line of the oil pipeline; carrying out ecological monitoring; working of the public plan of response to oil spills; For ecological education of the public is necessary: carrying out informing of the public for all (technical, ecological, social and economic and legal) questions connected to an oil pipeline, and also on methods of protection of the rights at participation in acceptance of ecological significant decisions; Creation of public groups for realization of activity on observance of the legislation and to prevention of risks; Exposure of hot

  6. Dynamic pressure measures for long pipeline leak detection

    Energy Technology Data Exchange (ETDEWEB)

    Likun Wang; Hongchao Wang; Min Xiong; Bin Xu; Dongjie Tan; Hengzhang Zhou [PetroChina Pipeline Company, Langfang (China). R and D Center

    2009-07-01

    Pipeline leak detection method based on dynamic pressure is studied. The feature of dynamic pressure which is generated by the leakage of pipeline is analyzed. The dynamic pressure method is compared with the static pressure method for the advantages and disadvantages in pipeline leak detection. The dynamic pressure signal is suitable for pipeline leak detection for quick-change of pipeline internal pressure. Field tests show that the dynamic pressure method detects pipeline leak rapidly and precisely. (author)

  7. Assessing fugitive emissions of CH4 from high-pressure gas pipelines

    Science.gov (United States)

    Worrall, Fred; Boothroyd, Ian; Davies, Richard

    2017-04-01

    The impact of unconventional natural gas production using hydraulic fracturing methods from shale gas basins has been assessed using life-cycle emissions inventories, covering areas such as pre-production, production and transmission processes. The transmission of natural gas from well pad to processing plants and its transport to domestic sites is an important source of fugitive CH4, yet emissions factors and fluxes from transmission processes are often based upon ver out of date measurements. It is important to determine accurate measurements of natural gas losses when compressed and transported between production and processing facilities so as to accurately determine life-cycle CH4 emissions. This study considers CH4 emissions from the UK National Transmission System (NTS) of high pressure natural gas pipelines. Mobile surveys of CH4 emissions using a Picarro Surveyor cavity-ring-down spectrometer were conducted across four areas in the UK, with routes bisecting high pressure pipelines and separate control routes away from the pipelines. A manual survey of soil gas measurements was also conducted along one of the high pressure pipelines using a tunable diode laser. When wind adjusted 92 km of high pressure pipeline and 72 km of control route were drive over a 10 day period. When wind and distance adjusted CH4 fluxes were significantly greater on routes with a pipeline than those without. The smallest leak detectable was 3% above ambient (1.03 relative concentration) with any leaks below 3% above ambient assumed ambient. The number of leaks detected along the pipelines correlate to the estimated length of pipe joints, inferring that there are constant fugitive CH4 emissions from these joints. When scaled up to the UK's National Transmission System pipeline length of 7600 km gives a fugitive CH4 flux of 4700 ± 2864 kt CH4/yr - this fugitive emission from high pressure pipelines is 0.016% of the annual gas supply.

  8. Canadian pipeline transportation system : transportation assessment

    International Nuclear Information System (INIS)

    2009-07-01

    In addition to regulating the construction and operation of 70,000 km of oil and natural gas pipelines in Canada, the National Energy Board (NEB) regulates the trade of natural gas, oil and natural gas liquids. This report provided an assessment of the Canadian hydrocarbon transportation system in relation to its ability to provide a robust energy infrastructure. Data was collected from NEB-regulated pipeline companies and a range of publicly available sources to determine if adequate pipeline capacity is in place to transport products to consumers. The NEB also used throughput and capacity information received from pipeline operators as well as members of the investment community. The study examined price differentials compared with firm service tolls for transportation paths, as well as capacity utilization on pipelines and the degree of apportionment on major oil pipelines. This review indicated that in general, the Canadian pipeline transportation system continues to work effectively, with adequate pipeline capacity in place to move products to consumers who need them. 9 tabs., 30 figs., 3 appendices.

  9. The MIRI Medium Resolution Spectrometer calibration pipeline

    NARCIS (Netherlands)

    Labiano, A.; Azzollini, R.; Bailey, J.; Beard, S.; Dicken, D.; García-Marín, M.; Geers, V.; Glasse, A.; Glauser, A.; Gordon, K.; Justtanont, K.; Klaassen, P.; Lahuis, F.; Law, D.; Morrison, J.; Müller, M.; Rieke, G.; Vandenbussche, B.; Wright, G.

    2016-01-01

    The Mid-Infrared Instrument (MIRI) Medium Resolution Spectrometer (MRS) is the only mid-IR Integral Field Spectrometer on board James Webb Space Telescope. The complexity of the MRS requires a very specialized pipeline, with some specific steps not present in other pipelines of JWST instruments,

  10. Oil pipeline energy consumption and efficiency

    Energy Technology Data Exchange (ETDEWEB)

    Hooker, J.N.

    1981-01-01

    This report describes an investigation of energy consumption and efficiency of oil pipelines in the US in 1978. It is based on a simulation of the actual movement of oil on a very detailed representation of the pipeline network, and it uses engineering equations to calculate the energy that pipeline pumps must have exerted on the oil to move it in this manner. The efficiencies of pumps and drivers are estimated so as to arrive at the amount of energy consumed at pumping stations. The throughput in each pipeline segment is estimated by distributing each pipeline company's reported oil movements over its segments in proportions predicted by regression equations that show typical throughput and throughput capacity as functions of pipe diameter. The form of the equations is justified by a generalized cost-engineering study of pipelining, and their parameters are estimated using new techniques developed for the purpose. A simplified model of flow scheduling is chosen on the basis of actual energy use data obtained from a few companies. The study yields energy consumption and intensiveness estimates for crude oil trunk lines, crude oil gathering lines and oil products lines, for the nation as well as by state and by pipe diameter. It characterizes the efficiency of typical pipelines of various diameters operating at capacity. Ancillary results include estimates of oil movements by state and by diameter and approximate pipeline capacity utilization nationwide.

  11. Testing the School-to-Prison Pipeline

    Science.gov (United States)

    Owens, Emily G.

    2017-01-01

    The School-to-Prison Pipeline is a social phenomenon where students become formally involved with the criminal justice system as a result of school policies that use law enforcement, rather than discipline, to address behavioral problems. A potentially important part of the School-to-Prison Pipeline is the use of sworn School Resource Officers…

  12. Generating pipeline networks for corrosion assessment

    Energy Technology Data Exchange (ETDEWEB)

    Ferguson, J. [Cimarron Engineering Ltd., Calgary, AB (Canada)

    2008-07-01

    Production characteristics and gas-fluid compositions of fluids must be known in order to assess pipelines for internal corrosion risk. In this study, a gathering system pipeline network was built in order to determine corrosion risk for gathering system pipelines. Connections were established between feeder and collector lines in order measure upstream production and the weighted average of the upstream composition of each pipeline in the system. A Norsok M-506 carbon dioxide (CO{sub 2}) corrosion rate model was used to calculate corrosion rates. A spreadsheet was then used to tabulate the obtained data. The analysis used straight lines drawn between the 'from' and 'to' legal sub-division (LSD) endpoints in order to represent pipelines on an Alberta township system (ATS) and identify connections between pipelines. Well connections were established based on matching surface hole location and 'from' LSDs. Well production, composition, pressure, and temperature data were sourced and recorded as well attributes. XSL hierarchical computations were used to determine the production and composition properties of the commingled inflows. It was concluded that the corrosion assessment process can identify locations within the pipeline network where potential deadlegs branched off from flowing pipelines. 4 refs., 2 tabs., 2 figs.

  13. Analysis of buried pipelines at Kozloduy

    International Nuclear Information System (INIS)

    Asfura, A.

    1999-01-01

    This paper describes the analysis of the buried pipelines at Kozloduy NPP. It involves the description of the studied pipelines, their properties, a detailed description of the methodology applied, and the evaluation of the soil strain field as well as the graphical representation of the results obtained

  14. The LOFAR Known Pulsar Data Pipeline

    NARCIS (Netherlands)

    Alexov, A.; Hessels, J.W.T.; Mol, J.D.; Stappers, B.; van Leeuwen, J.

    2010-01-01

    Abstract: Transient radio phenomena and pulsars are one of six LOFAR Key Science Projects (KSPs). As part of the Transients KSP, the Pulsar Working Group (PWG) has been developing the LOFAR Pulsar Data Pipelines to both study known pulsars as well as search for new ones. The pipelines are being

  15. Repairing method for reactor primary system pipeline

    International Nuclear Information System (INIS)

    Hosokawa, Hideyuki; Uetake, Naoto; Hara, Teruo.

    1997-01-01

    Pipelines after decontamination of radioactive nuclides deposited on the pipelines in a nuclear power plant during operation or pipelines to replace pipelines deposited with radioactive nuclide are connected to each system of the nuclear power plant. They are heated in a gas phase containing oxygen to form an oxide film on the surface of the pipelines. The thickness of the oxide film formed in the gas phase is 1nm or greater, preferably 100nm. The concentration of oxygen in the gas phase containing oxygen must be 0.1% or greater. The heating is conducted by circulating a heated gas to the inside of the pipelines or disposing a movable heater such as a high frequency induction heater inside of the pipelines to form the oxide film. Then, redeposition of radioactive nuclide can be suppressed and since the oxide film is formed in the gas phase, a large scaled facilities are not necessary, thereby enabling to repair pipelines of reactor primary system at low cost. (N.H.)

  16. Protection of pipelines affected by surface subsidence

    International Nuclear Information System (INIS)

    Luo, Y.; Peng, S.S.; Chen, H.J.

    1998-01-01

    Surface subsidence resulting from underground coal mining can cause problems for buried pipelines. A technique for assessing the level of stress on a subsidence-affected pipeline is introduced. The main contributors to the stress are identified, and mitigation techniques for reducing the stress are proposed. The proposed mitigation techniques were then successfully tested. 13 refs., 8 figs., 2 tabs

  17. 49 CFR 195.581 - Which pipelines must I protect against atmospheric corrosion and what coating material may I use?

    Science.gov (United States)

    2010-10-01

    ... corrosion and what coating material may I use? 195.581 Section 195.581 Transportation Other Regulations... Corrosion Control § 195.581 Which pipelines must I protect against atmospheric corrosion and what coating... atmosphere, except pipelines under paragraph (c) of this section. (b) Coating material must be suitable for...

  18. STRESS AND STRAIN STATE OF REPAIRING SECTION OF PIPELINE

    Directory of Open Access Journals (Sweden)

    V. V. Nikolaev

    2015-01-01

    Full Text Available Reliability of continuous operation of pipelines is an actual problem. For this reason should be developed an effective warning system of the main pipelines‘  failures and accidents not only in design and operation but also in selected repair. Changing of linear, unloaded by bending position leads to the change of stress and strain state of pipelines. And besides this, the stress and strain state should be determined and controlled in the process of carrying out the repair works. The article presents mathematical model of pipeline’s section straining in viscoelastic setting taking into account soils creep and high-speed stress state of pipeline with the purpose of stresses evaluation and load-supporting capacity of repairing section of pipeline, depending on time.  Stress and strain state analysis of pipeline includes longitudinal and circular stresses calculation  with  account of axis-asymmetrical straining and  was  fulfilled  on  the base of momentless theory of shells. To prove the consistency of data there were compared the calcu- lation results and the solution results by analytical methods for different cases (long pipeline’s section strain only under influence of cross-axis action; long pipeline’s section strain under in- fluence of longitudinal stress; long pipeline’s section strain; which is on the elastic foundation, under influence of cross-axis action. Comparison results shows that the calculation error is not more than 3 %.Analysis of stress-strain state change of pipeline’s section was carried out with development  of  this  model,  which  indicates  the  enlargement  of  span  deflection  in  comparison with problem’s solution in elastic approach. It is also proved, that for consistent assessment of pipeline maintenance conditions, it is necessary to consider the areolas of rheological processes of soils. On the base of complex analysis of pipelines there were determined stresses and time

  19. Offshore Pipeline Locations in the Gulf of Mexico, Geographic NAD27, MMS (2007) [pipelines_vectors_mms_2007

    Data.gov (United States)

    Louisiana Geographic Information Center — Offshore Minerals Management Pipeline Locations for the Gulf of Mexico (GOM). Contains the lines of the pipeline in the GOM. All pipelines existing in the databases...

  20. Offshore Pipeline Locations in the Gulf of Mexico, Geographic NAD27, MMS (2007) [pipelines_points_mms_2007

    Data.gov (United States)

    Louisiana Geographic Information Center — Offshore Minerals Management Pipeline Locations for the Gulf of Mexico (GOM). Contains the points of the pipeline in the GOM. All pipelines existing in the databases...

  1. Pipeline monitoring with unmanned aerial vehicles

    Science.gov (United States)

    Kochetkova, L. I.

    2018-05-01

    Pipeline leakage during transportation of combustible substances leads to explosion and fire thus causing death of people and destruction of production and accommodation facilities. Continuous pipeline monitoring allows identifying leaks in due time and quickly taking measures for their elimination. The paper describes the solution of identification of pipeline leakage using unmanned aerial vehicles. It is recommended to apply the spectral analysis with input RGB signal to identify pipeline damages. The application of multi-zone digital images allows defining potential spill of oil hydrocarbons as well as possible soil pollution. The method of multi-temporal digital images within the visible region makes it possible to define changes in soil morphology for its subsequent analysis. The given solution is cost efficient and reliable thus allowing reducing timing and labor resources in comparison with other methods of pipeline monitoring.

  2. optimization for trenchless reconstruction of pipelines

    Directory of Open Access Journals (Sweden)

    Zhmakov Gennadiy Nikolaevich

    2015-01-01

    Full Text Available Today the technologies of trenchless reconstruction of pipelines are becoming and more widely used in Russia and abroad. One of the most perspective is methods is shock-free destruction of the old pipeline being replaced with the help of hydraulic installations with working mechanism representing a cutting unit with knife disks and a conic expander. A construction of a working mechanism, which allows making trenchless reconstruction of pipelines of different diameters, is optimized and patented and its developmental prototype is manufactured. The dependence of pipeline cutting force from knifes obtusion of the working mechanisms. The cutting force of old steel pipelines with obtuse knife increases proportional to the value of its obtusion. Two stands for endurance tests of the knifes in laboratory environment are offered and patented.

  3. Crude oil growth impact on pipelines

    International Nuclear Information System (INIS)

    Devries, O.

    2005-01-01

    This paper provided an outline of crude oil production and supply in Canada. Details of oil sands projects in Athabasca, Cold Lake and Peace River were presented. A chart of oil sands growth by major project was provided. A list of new emerging oil sands crude types was also presented along with details of a synthetic bitumen blending synergy. Maps of Western Canadian crude oil markets were provided, along with details of refinery and market demand by crude type. Various pipeline alternatives to new markets were examined, with reference to Enbridge Pipeline's supply and capacity. Details of the Hardisty to U.S Gulf Coast Pipeline and the Edmonton to Prince Rupert Pipeline and its terminal and dock facilities were presented. It was concluded that pipeline capacity and seasonal factors will influence market demand, while linefill, crude types and the quality of the product will influence operational strategies. tabs., figs

  4. Millennium Pipeline Presentation : a new northeast passage

    International Nuclear Information System (INIS)

    Wolnik, J.

    1997-01-01

    Routes of the proposed Millennium Pipeline project were presented. The pipeline is to originate at the Empress gas field in Alberta and link up to eastern markets in the United States. One of the key advantages of the pipeline is that it will have the lowest proposed rates from Empress to Chicago and through links via affiliates to New York and other eastern markets. It will include 380 miles of new 36-inch pipeline and have a capacity of 650 million cubic feet per day. In many instances it will follow existing rights-of-way. The pipeline is expected to be in service for the 1999 winter heating season. The project sponsors are Columbia Gas Transmission, CMS Energy, MCN Energy, and Westcoast Energy. 6 figs

  5. Efficiency improvements in pipeline transportation systems

    Energy Technology Data Exchange (ETDEWEB)

    Banks, W. F.; Horton, J. F.

    1977-09-09

    This report identifies potential energy-conservative pipeline innovations that are most energy- and cost-effective and formulates recommendations for the R, D, and D programs needed to exploit those opportunities. From a candidate field of over twenty classes of efficiency improvements, eight systems are recommended for pursuit. Most of these possess two highly important attributes: large potential energy savings and broad applicability outside the pipeline industry. The R, D, and D program for each improvement and the recommended immediate next step are described. The eight technologies recommended for R, D, and D are gas-fired combined cycle compressor station; internally cooled internal combustion engine; methanol-coal slurry pipeline; methanol-coal slurry-fired and coal-fired engines; indirect-fired coal-burning combined-cycle pump station; fuel-cell pump station; drag-reducing additives in liquid pipelines; and internal coatings in pipelines.

  6. Pipeline modeling and assessment in unstable slopes

    Energy Technology Data Exchange (ETDEWEB)

    Caceres, Carlos Nieves [Oleoducto Central S.A., Bogota, Cundinamarca (Colombia); Ordonez, Mauricio Pereira [SOLSIN S.A.S, Bogota, Cundinamarca (Colombia)

    2010-07-01

    The OCENSA pipeline system is vulnerable to geotechnical problems such as faults, landslides or creeping slopes, which are well-known in the Andes Mountains and tropical countries like Colombia. This paper proposes a methodology to evaluate the pipe behaviour during the soil displacements of slow landslides. Three different cases of analysis are examined, according to site characteristics. The process starts with a simplified analytical model and develops into 3D finite element numerical simulations applied to the on-site geometry of soil and pipe. Case 1 should be used when the unstable site is subject to landslides impacting significant lengths of pipeline, pipeline is straight, and landslide is simple from the geotechnical perspective. Case 2 should be used when pipeline is straight and landslide is complex (creeping slopes and non-conventional stabilization solutions). Case 3 should be used if the pipeline presents vertical or horizontal bends.

  7. Location of leaks in pressurized underground pipelines

    International Nuclear Information System (INIS)

    Eckert, E.G.; Maresca, J.W. Jr.

    1993-01-01

    Millions of underground storage tanks (UST) are used to store petroleum and other chemicals. The pressurized underground pipelines associated with USTs containing petroleum motor fuels are typically 2 in. in diameter and 50 to 200 ft in length. These pipelines typically operate at pressures of 20 to 30 psi. Longer lines, with diameters up to 4 in., are found in some high-volume facilities. There are many systems that can be used to detect leaks in pressurized underground pipelines. When a leak is detected, the first step in the remediation process is to find its location. Passive-acoustic measurements, combined with advanced signal-processing techniques, provide a nondestructive method of leak location that is accurate and relatively simple, and that can be applied to a wide variety of pipelines and pipeline products

  8. Reduce operational cost and extend the life of pipeline infrastructure by automating remote cathodic protection systems

    Energy Technology Data Exchange (ETDEWEB)

    Rosado, Elroy [Freewave Technologies, Inc., Boulder, CO (United States). Latin America

    2009-07-01

    Energy and Pipeline Companies wrestle to control operating costs largely affected by new government regulations, ageing buried metal assets, rising steel prices, expanding pipeline operations, new interference points, HCA encroachment, restrictive land use policies, heightened network security, and an ageing soon-to-retire work force. With operating costs on the rise, seemingly out of control, many CP and Operations Professionals look to past best practices in cost containment through automation. Many companies achieve solid business results through deployment of telemetry and SCADA automation of remote assets and now hope to expand this success to further optimize operations by automating remote cathodic protection systems. This presentation will provide examples of how new remote cathodic protection systems are helping energy and pipeline companies address the growing issue of the aging pipeline infrastructure and reduce their costs while optimizing their operations. (author)

  9. Risk and integrity management system for PETRONAS Gas Berhad's gas and liquid hydrocarbon pipelines

    Energy Technology Data Exchange (ETDEWEB)

    Khalid, Tuan Hj. Ahmad Nadzri bin; Nasir, Osman; Napiah, Mohd Nazmi Mohd Ali [PETRONAS Gas Berhad, Johor (Malaysia); Choong, Evelyn

    2005-07-01

    PETRONAS Gas Berhad (PGB), Malaysia currently operates one of Southeast Asia's largest onshore pipeline systems comprising more than 2,500 km of large diameter high pressure gas and liquid transmission, supply and lateral pipelines. Recognizing the value of a risk based approach to pipeline integrity management program, in 2002 PGB implemented a customized and fully integrated Risk and Integrity Management System (RIMS) which included software modules for: data management; semi-quantitative risk assessment; risk control cost benefit analyses; defect assessment; corrosion growth modeling; and reporting. As part of this project, a benchmarking study performed jointly with the contractor, PGB's pipeline integrity programs were also compared with a broad group of international pipeline operators. This study compared the relative ranking position of PGB pre- and post implementation of RIMS. It demonstrated that implementation of RIMS places PGB in a select group of first quartile international pipeline operators, with respect to the implementation of pipeline integrity management best practice. This paper describes the functionalities of RIMS system and how it has benefited PGB, which have been realized to date from its implementation. (author)

  10. Feasibility study on rehabilitation and optimization of gas pipeline network/system

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2000-03-01

    For the purpose of reducing greenhouse effect gas emissions, a survey was conducted on repairs and optimization of gas pipeline net/system in Bangladesh. In the survey, the measurement of methane gas concentration, wind direction/velocity and temperature was made for 16 stations of BC pipeline and BD pipeline including Ring Line. As a result of the measurement, the amount of methane leakage totaled 5,300 tons/year including 1,300 tons in BD pipeline, 2,500 tons in BC pipeline and 1,500 tons in Ring Line. For repairs/optimization of the pipeline net/system, the necessity of the following was pointed out: exchanges of gaskets, piping and valves; repairs of portions of the pipeline exposure; exchanges of pressure control valves and flowmeters; repair of the corrosion prevention system. In this improvement project, the reduction amount of greenhouse effect gas emissions will be 5,300 tons/year and approximately 106,000 tons in 20 years. The conservation will amount to 0.66 MMUS$/year. (NEDO)

  11. Pipeline integrity: ILI baseline data for QRA

    Energy Technology Data Exchange (ETDEWEB)

    Porter, Todd R. [Tuboscope Pipeline Services, Houston, TX (United States)]. E-mail: tporter@varco.com; Silva, Jose Augusto Pereira da [Pipeway Engenharia, Rio de Janeiro, RJ (Brazil)]. E-mail: guto@pipeway.com; Marr, James [MARR and Associates, Calgary, AB (Canada)]. E-mail: jmarr@marr-associates.com

    2003-07-01

    The initial phase of a pipeline integrity management program (IMP) is conducting a baseline assessment of the pipeline system and segments as part of Quantitative Risk Assessment (QRA). This gives the operator's integrity team the opportunity to identify critical areas and deficiencies in the protection, maintenance, and mitigation strategies. As a part of data gathering and integration of a wide variety of sources, in-line inspection (ILI) data is a key element. In order to move forward in the integrity program development and execution, the baseline geometry of the pipeline must be determined with accuracy and confidence. From this, all subsequent analysis and conclusions will be derived. Tuboscope Pipeline Services (TPS), in conjunction with Pipeway Engenharia of Brazil, operate ILI inertial navigation system (INS) and Caliper geometry tools, to address this integrity requirement. This INS and Caliper ILI tool data provides pipeline trajectory at centimeter level resolution and sub-metre 3D position accuracy along with internal geometry - ovality, dents, misalignment, and wrinkle/buckle characterization. Global strain can be derived from precise INS curvature measurements and departure from the initial pipeline state. Accurate pipeline elevation profile data is essential in the identification of sag/over bend sections for fluid dynamic and hydrostatic calculations. This data, along with pipeline construction, operations, direct assessment and maintenance data is integrated in LinaViewPRO{sup TM}, a pipeline data management system for decision support functions, and subsequent QRA operations. This technology provides the baseline for an informed, accurate and confident integrity management program. This paper/presentation will detail these aspects of an effective IMP, and experience will be presented, showing the benefits for liquid and gas pipeline systems. (author)

  12. A Reliability Assessment of the Hydrostatic Test of Pipeline with 0.8 Design Factor in the West–East China Natural Gas Pipeline III

    Directory of Open Access Journals (Sweden)

    Kai Wen

    2018-05-01

    Full Text Available The use of 0.8 design factor in Chinese pipeline industry is a breakthrough with the success of the test pipe section in the west–east China gas pipeline III. For such a design factor, the traditional P-V (Pressure-Volume curve based pressure test control cannot describe the details of the process, and the 0/1 type failure is not an efficient index to show the safety level of the pipeline. In this paper, a reliability based assessment method is proposed to monitor the real-time failure probability of the pipeline during the hydrostatic test process. The reliability index can be used as the degree of risk. Following the actual hydrostatic testing of a test pipe section with 0.8 design factor in the west–east China gas pipeline III, reliability analysis was performed using Monte Carlo technique. The basic values of input parameters of the limit state equations are based on the data collected from either the tested section or the recommended value in the codes. The analysis of limit states, i.e., the yielding deformation and the excessive plastic deformation of pipeline, proceeded based on these distributions. Finally, it is found that the gradually increased water pressure makes the failure probability increase accordingly. A reliability assessment method was proposed and illustrated with the practical pressure test process.

  13. The Very Large Array Data Processing Pipeline

    Science.gov (United States)

    Kent, Brian R.; Masters, Joseph S.; Chandler, Claire J.; Davis, Lindsey E.; Kern, Jeffrey S.; Ott, Juergen; Schinzel, Frank K.; Medlin, Drew; Muders, Dirk; Williams, Stewart; Geers, Vincent C.; Momjian, Emmanuel; Butler, Bryan J.; Nakazato, Takeshi; Sugimoto, Kanako

    2018-01-01

    We present the VLA Pipeline, software that is part of the larger pipeline processing framework used for the Karl G. Jansky Very Large Array (VLA), and Atacama Large Millimeter/sub-millimeter Array (ALMA) for both interferometric and single dish observations.Through a collection of base code jointly used by the VLA and ALMA, the pipeline builds a hierarchy of classes to execute individual atomic pipeline tasks within the Common Astronomy Software Applications (CASA) package. Each pipeline task contains heuristics designed by the team to actively decide the best processing path and execution parameters for calibration and imaging. The pipeline code is developed and written in Python and uses a "context" structure for tracking the heuristic decisions and processing results. The pipeline "weblog" acts as the user interface in verifying the quality assurance of each calibration and imaging stage. The majority of VLA scheduling blocks above 1 GHz are now processed with the standard continuum recipe of the pipeline and offer a calibrated measurement set as a basic data product to observatory users. In addition, the pipeline is used for processing data from the VLA Sky Survey (VLASS), a seven year community-driven endeavor started in September 2017 to survey the entire sky down to a declination of -40 degrees at S-band (2-4 GHz). This 5500 hour next-generation large radio survey will explore the time and spectral domains, relying on pipeline processing to generate calibrated measurement sets, polarimetry, and imaging data products that are available to the astronomical community with no proprietary period. Here we present an overview of the pipeline design philosophy, heuristics, and calibration and imaging results produced by the pipeline. Future development will include the testing of spectral line recipes, low signal-to-noise heuristics, and serving as a testing platform for science ready data products.The pipeline is developed as part of the CASA software package by an

  14. Pipeline Decommissioning Trial AWE Berkshire UK - 13619

    Energy Technology Data Exchange (ETDEWEB)

    Agnew, Kieran [AWE, Aldermaston, Reading, RG7 4PR (United Kingdom)

    2013-07-01

    This Paper details the implementation of a 'Decommissioning Trial' to assess the feasibility of decommissioning the redundant pipeline operated by AWE located in Berkshire UK. The paper also presents the tool box of decommissioning techniques that were developed during the decommissioning trial. Constructed in the 1950's and operated until 2005, AWE used a pipeline for the authorised discharge of treated effluent. Now redundant, the pipeline is under a care and surveillance regime awaiting decommissioning. The pipeline is some 18.5 km in length and extends from AWE site to the River Thames. Along its route the pipeline passes along and under several major roads, railway lines and rivers as well as travelling through woodland, agricultural land and residential areas. Currently under care and surveillance AWE is considering a number of options for decommissioning the pipeline. One option is to remove the pipeline. In order to assist option evaluation and assess the feasibility of removing the pipeline a decommissioning trial was undertaken and sections of the pipeline were removed within the AWE site. The objectives of the decommissioning trial were to: - Demonstrate to stakeholders that the pipeline can be removed safely, securely and cleanly - Develop a 'tool box' of methods that could be deployed to remove the pipeline - Replicate the conditions and environments encountered along the route of the pipeline The onsite trial was also designed to replicate the physical prevailing conditions and constraints encountered along the remainder of its route i.e. working along a narrow corridor, working in close proximity to roads, working in proximity to above ground and underground services (e.g. Gas, Water, Electricity). By undertaking the decommissioning trial AWE have successfully demonstrated the pipeline can be decommissioned in a safe, secure and clean manor and have developed a tool box of decommissioning techniques. The tool box of includes

  15. Calibration pipeline for VIR data

    Science.gov (United States)

    Carraro, F.; Fonte, S.; Coradini, A.; Filacchione, G.; de Sanctis, M. C.; Ammannito, E.; Capria, M. T.; Cartacci, M.; Noschese, R.; Tosi, F.; Capaccioni, F.

    2011-10-01

    During the second quarter of 2011 VIR-MS (VIS and IR Mapping Spectrometer) [1] aboard Dawn mission [2] has approached Vesta in order to start a long period of acquisitions that will end at the beginning of 2012. Data acquired by each instrument always require a calibration process in order to remove all the instrument effects that could affect the scientific evaluations and analysis. VIR-MS instrument team has realized a calibration pipeline which has the goal of producing calibrated (1b level) data starting from the raw (1a level) ones. The other goal of the tool has been the check of the goodness of acquired data by means of the evaluation of a series of minimum requisites of each data file, such as the percentage of the saturated pixels, the presence of spikes or the mean S/N ratio of each qube.

  16. Northeast market view : Millennium Pipeline

    International Nuclear Information System (INIS)

    Pentzien, D.C.

    1998-01-01

    The potential for growth in the U.S. northeast natural gas markets was discussed. In presenting a forecast for natural gas consumption, the growth in demand was attributed primarily to the planned conversion of coal and oil-fired electric generation plants to gas-fired ones, combined with nuclear plant shutdowns, and more stringent environmental policies. An overview of the development of the Millennium Pipeline bringing natural gas from the Alberta border all the way to New York City was also provided, with an update on the current status of the project. Assuming no unreasonable delays in the present schedule, the line should be in service sometime in the year 2000. figs

  17. U.S. interstate pipelines ran more efficiently in 1994

    International Nuclear Information System (INIS)

    True, W.R.

    1995-01-01

    Regulated US interstate pipelines began 1995 under the momentum of impressive efficiency improvements in 1994. Annual reports filed with the US Federal Energy Regulatory Commission (FERC) show that both natural-gas and petroleum liquids pipeline companies increased their net incomes last year despite declining operating revenues. This article discusses trends in the pipeline industry and gives data on the following: pipeline revenues, incomes--1994; current pipeline costs; pipeline costs--estimated vs. actual; current compressor construction costs; compressor costs--estimated vs. actual; US interstate mileage; investment in liquids pipelines; 10-years of land construction costs; top 10 interstate liquids pipelines; top 10 interstate gas pipelines; liquids pipeline companies; and gas pipeline companies

  18. Current pipelines for neglected diseases.

    Science.gov (United States)

    di Procolo, Paolo; Jommi, Claudio

    2014-09-01

    This paper scrutinises pipelines for Neglected Diseases (NDs), through freely accessible and at-least-weekly updated trials databases. It updates to 2012 data provided by recent publications, and integrates these analyses with information on location of trials coordinators and patients recruitment status. Additionally, it provides (i) disease-specific information to better understand the rational of investments in NDs, (ii) yearly data, to understand the investment trends. The search identified 650 clinical studies. Leishmaniasis, Arbovirus infection, and Dengue are the top three diseases by number of clinical studies. Disease diffusion risk seems to be the most important driver of the clinical trials target choice, whereas the role played by disease prevalence and unmet need is controversial. Number of trials is stable between 2005 and 2010, with an increase in the last two years. Patient recruitment was completed for most studies (57.6%), and Phases II and III account for 35% and 28% of trials, respectively. The primary purpose of clinical investigations is prevention (49.3%), especially for infectious diseases with mosquitoes and sand flies as the vector, and treatment (43.2%), which is the primary target for parasitic diseases Research centres and public organisations are the most important clinical studies sponsors (58.9%), followed by the pharmaceutical industry (24.1%), foundations and non-governmental organisations (9.3%). Many coordinator centres are located in less affluent countries (43.7%), whereas OECD countries and BRICS account for 34.7% and 17.5% of trials, respectively. Information was partially missing for some parameters. Notwithstanding, and despite its descriptive nature, this research has enhanced the evidence of the literature on pipelines for NDs. Future contributions may further investigate whether trials metrics are consistent with the characteristics of the interested countries and the explicative variables of trials location, target

  19. Flooding simulation of hilly pipeline commisionning process

    Energy Technology Data Exchange (ETDEWEB)

    Nan, Zhang [China National Oil and Gas Exploration and Development Corporation and China University of Petroleum, Beijing (China); Jing, Gong [China University of Petroleum, Beijing (China); Baoli, Zhu [China National Oil and Gas Exploration and Development Corporation, Beijing (China); Lin, Zheng [CNPC Oil and Gas Control Center, Beijing (China)

    2010-07-01

    When the construction of a pipeline has been completed, the pipeline flooding is done as part of the pipeline commissioning process. This method consists of filling the empty pipe with water or oil. In a pipeline situated in hilly terrain, air entrapped in the fluid causes problems with the flooding process and it is necessary to discharge the accumulated air to address this issue. The aim of this paper is to provide a model for predicting the location and volume of air pockets in a pipeline. This model was developed based on the fundamentals of mass balance and momentum transfer in multiphase flow and was then applied to a pipeline in China and compared with the SCADA data. Results showed a good match between the model's predictions of hydraulic movement and the real data from SCADA. The two flow model developed can predict hydraulic movement during pipeline flooding in a hilly area and thus it can be used to predict water front location and air pocket movement in the pipe.

  20. Optimal hub location in pipeline networks

    Energy Technology Data Exchange (ETDEWEB)

    Dott, D.R.; Wirasinghe, S.C.; Chakma, A. [Univ. of Calgary, Alberta (Canada)

    1996-12-31

    This paper discusses optimization strategies and techniques for the location of natural gas marketing hubs in the North American gas pipeline network. A hub is a facility at which inbound and outbound network links meet and freight is redirected towards their destinations. Common examples of hubs used in the gas pipeline industry include gas plants, interconnects and market centers. Characteristics of the gas pipeline industry which are relevant to the optimization of transportation costs using hubs are presented. Allocation techniques for solving location-allocation problems are discussed. An outline of the research in process by the authors in the field of optimal gas hub location concludes the paper.

  1. Prospects for coal slurry pipelines in California

    Science.gov (United States)

    Lynch, J. F.

    1978-01-01

    The coal slurry pipeline segment of the transport industry is emerging in the United States. If accepted it will play a vital role in meeting America's urgent energy requirements without public subsidy, tax relief, or federal grants. It is proven technology, ideally suited for transport of an abundant energy resource over thousands of miles to energy short industrial centers and at more than competitive costs. Briefly discussed are the following: (1) history of pipelines; (2) California market potential; (3) slurry technology; (4) environmental benefits; (5) market competition; and (6) a proposed pipeline.

  2. Integrating sustainable growth into export pipeline projects

    International Nuclear Information System (INIS)

    Jeniffer, Barringer; William, Lukens; Patricia, Wild

    2002-01-01

    Full text: Sustainable growth in the energy industry is rapidly expanding beyond the conceptual stage. Policies addressing the three principles of Sustainable Development are being established and strategies to execute these policies are being developed and implemented in the field. Conoco is developing a strong corporate culture around sustainable growth; and, pipeline systems play a vital role in delivering the triple bottom line results for our stake holders. This paper will highlight some of the key focal points by Conoco Inc., in each phase of pipeline project development, execution, and operation to make pipeline projects a contributor to Conoco's sustainable growth success, and shares some lessons learned

  3. ARTIP: Automated Radio Telescope Image Processing Pipeline

    Science.gov (United States)

    Sharma, Ravi; Gyanchandani, Dolly; Kulkarni, Sarang; Gupta, Neeraj; Pathak, Vineet; Pande, Arti; Joshi, Unmesh

    2018-02-01

    The Automated Radio Telescope Image Processing Pipeline (ARTIP) automates the entire process of flagging, calibrating, and imaging for radio-interferometric data. ARTIP starts with raw data, i.e. a measurement set and goes through multiple stages, such as flux calibration, bandpass calibration, phase calibration, and imaging to generate continuum and spectral line images. Each stage can also be run independently. The pipeline provides continuous feedback to the user through various messages, charts and logs. It is written using standard python libraries and the CASA package. The pipeline can deal with datasets with multiple spectral windows and also multiple target sources which may have arbitrary combinations of flux/bandpass/phase calibrators.

  4. Basic Block of Pipelined ADC Design Requirements

    Directory of Open Access Journals (Sweden)

    V. Kledrowetz

    2011-04-01

    Full Text Available The paper describes design requirements of a basic stage (called MDAC - Multiplying Digital-to- Analog Converter of a pipelined ADC. There exist error sources such as finite DC gain of opamp, capacitor mismatch, thermal noise, etc., arising when the switched capacitor (SC technique and CMOS technology are used. These non-idealities are explained and their influences on overall parameters of a pipelined ADC are studied. The pipelined ADC including non-idealities was modeled in MATLAB - Simulink simulation environment.

  5. Integrity assessment of pipelines - additional remarks; Avaliacao da integridade de dutos - observacoes adicionais

    Energy Technology Data Exchange (ETDEWEB)

    Alves, Luis F.C. [PETROBRAS S.A., Salvador, BA (Brazil). Unidade de Negocios. Exploracao e Producao

    2005-07-01

    Integrity assessment of pipelines is part of a process that aims to enhance the operating safety of pipelines. During this task, questions related to the interpretation of inspection reports and the way of regarding the impact of several parameters on the pipeline integrity normally come up. In order to satisfactorily answer such questions, the integrity assessment team must be able to suitably approach different subjects such as corrosion control and monitoring, assessment of metal loss and geometric anomalies, and third party activities. This paper presents additional remarks on some of these questions based on the integrity assessment of almost fifty pipelines that has been done at PETROBRAS/E and P Bahia over the past eight years. (author)

  6. Ultrasonic testing standard of fusion joint for polythylene(PE) pipeline

    International Nuclear Information System (INIS)

    Lee, Euy Jong; Hur, Sam Suk; Chae, Gug Byeong

    2006-01-01

    The polyethylene(PE) pipes are widely used to transport city gas worldwide with steel pipes. Generally, Steel pipe are used for high pressure line and PE pipe for low pressure line whose pressure is less than 4 kg/m 2 . The steel pipe line are subject to 100 percent Radiographic Testing(RT) during installation stage, on the contrary, there has been no the established testing method for the welding fusion joint of polyethylene pipes, so all quality control is limited only Visual Testing(VT) or management of Fusion welding equipment. Even though PE pipeline is exposed to lower pressure than steel pipeline, the gas leakage from PE pipe may result in almost the same serious consequence from steel pipeline. So, it is necessary to develop the reliable testing standard for PE pipeline from the point of view of NDT engineers.

  7. Simulation of non-isothermal transient flow in gas pipeline

    Energy Technology Data Exchange (ETDEWEB)

    Ferreira Junior, Luis Carlos; Soares, Matheus; Lima, Enrique Luis; Pinto, Jose Carlos [Coordenacao dos Programas de Pos-graduacao de Engenharia (COPPE/UFRJ), Rio de Janeiro, RJ (Brazil). Programa de Engenharia Quimica; Muniz, Cyro; Pires, Clarissa Cortes; Rochocz, Geraldo [ChemTech, Rio de Janeiro, RJ (Brazil)

    2009-07-01

    Modeling of gas pipeline usually considers that the gas flow is isothermal (or adiabatic) and that pressure changes occur instantaneously (quasi steady state approach). However, these assumptions are not valid in many important transient applications (changes of inlet and outlet flows/pressures, starting and stopping of compressors, changes of controller set points, among others). Besides, the gas properties are likely to depend simultaneously on the pipe position and on the operation time. For this reason, a mathematical model is presented and implemented in this paper in order to describe the gas flow in pipeline when pressure and temperature transients cannot be neglected. The model is used afterwards as a tool for reconciliation of available measured data. (author)

  8. Pipeline cost reduction through effective project management and applied technology

    Energy Technology Data Exchange (ETDEWEB)

    Jenkins, A. [TransCanada Pipeline Ltd., Alberta (Canada); Babuk, T. [Empress International Inc., Westwood, NJ (United States); Mohitpour, M. [Tempsys Pipeline Solutions Inc., Vancouver, BC (Canada); Murray, M.A. [National Energy Board of Canada (Canada)

    2005-07-01

    Pipelines are regarded by many as passive structures with the technology involved in their construction and operation being viewed as relatively simple and stable. If such is the case how can there be much room for cost improvement? In reality, there have been many technological and regulatory innovations required within the pipeline industry to meet the challenges posed by ever increasing consumer demand for hydrocarbons, the effects of aging infrastructure and a need to control operating and maintenance expenditures. The importance of technology management, as a subset of overall project management, is a key element of life cycle cost control. Assurance of public safety and the integrity of the system are other key elements in ensuring a successful pipeline project. The essentials of best practise project management from an owner/ operator's perspective are set out in the paper. Particular attention is paid to the appropriate introduction of new technology, strategic procurement practice and material selection, indicating that capital cost savings of up to 15% are achievable without harming life cycle cost. The value of partnering leading to technical innovation, cost savings and improved profitability for all the participants is described. Partnering also helps avoid duplicated effort through the use of common tools for design, planning schedule tracking and reporting. Investing in appropriate technology development has been a major source of cost reduction in recent years and the impact of a number of these recently introduced technologies in the areas of materials, construction processes and operation and maintenance are discussed in the paper. (author)

  9. Dynamic modelling and real-time leak detection for NGL pipelines

    Energy Technology Data Exchange (ETDEWEB)

    Young, B.R.; Svrcek, W.Y. [Calgary Univ., AB (Canada). Dept. of Chemical and Petroleum Engineering; Cooke, J.G.; Daye, R.E. [Rangeland Engineering Ltd., Calgary, AB (Canada)

    2004-07-01

    This paper presented newly developed steady-state and dynamic models commissioned for natural gas liquids (NGL) pipelines near Empress, Alberta. The work demonstrates a unique university-industry collaboration for solving the challenge of reliable pipeline leak detection. The flexible, custom real-time leak detection system was tested on the dynamic simulation. It was successfully used to replace a volume balance system for NGL pipelines at Empress in March 2003. A custom pipeline monitoring system was also developed to integrate with the existing pipeline supervisory control and data acquisition (SCADA) system. Simulation results enabled a change in the control scheme of the pipelines that resulted in less transient operation. The premise of the leak detection system is a rigorous thermodynamics and dynamic mass balance calculation based on real-time information from field flow, pressure and temperature sensors. The application of the system makes it possible to minimize or eliminate false or nuisance alarms, which is critical to the confidence of the monitoring system. The volumetric and mass imbalance formulae permit the system to cross check the calculation and then make important decisions regarding the sounding of alarms. The custom solution offers flexibility for use in a wide variety of conditions and applications. In addition, it is cost effective and locally supported. 8 refs., 4 tabs., 5 figs.

  10. Knowledge Pipeline: A Task Oriented Way to Implement Knowledge Management

    International Nuclear Information System (INIS)

    Pan Jiajie

    2014-01-01

    Concept of knowledge pipeline: There are many pipelines named by tasks or business processes in an organization. Knowledge contributors put knowledge to its corresponding pipelines. A maintenance team could keep the knowledge in pipelines clear and valid. Users could get knowledge just like opening a faucet in terms of their tasks or business processes

  11. 49 CFR 192.627 - Tapping pipelines under pressure.

    Science.gov (United States)

    2010-10-01

    ... 49 Transportation 3 2010-10-01 2010-10-01 false Tapping pipelines under pressure. 192.627 Section... NATURAL AND OTHER GAS BY PIPELINE: MINIMUM FEDERAL SAFETY STANDARDS Operations § 192.627 Tapping pipelines under pressure. Each tap made on a pipeline under pressure must be performed by a crew qualified to make...

  12. 76 FR 21423 - Pipeline Safety: Request for Special Permit

    Science.gov (United States)

    2011-04-15

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No. PHMSA-2011-0063] Pipeline Safety: Request for Special Permit AGENCY: Pipeline and Hazardous Materials... application is for two 30-inch segments, segments 3 and 4, of the TPL 330 natural gas pipeline located in St...

  13. 77 FR 2606 - Pipeline Safety: Random Drug Testing Rate

    Science.gov (United States)

    2012-01-18

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket ID PHMSA-2012-0004] Pipeline Safety: Random Drug Testing Rate AGENCY: Pipeline and Hazardous Materials... pipelines and operators of liquefied natural gas facilities must select and test a percentage of covered...

  14. 75 FR 35516 - Pipeline Safety: Request for Special Permit

    Science.gov (United States)

    2010-06-22

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No. PHMSA-2010-0147] Pipeline Safety: Request for Special Permit AGENCY: Pipeline and Hazardous Materials... with the Class 1 location portion of a 7.4 mile natural gas pipeline to be constructed in Alaska. This...

  15. 77 FR 26822 - Pipeline Safety: Verification of Records

    Science.gov (United States)

    2012-05-07

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No. PHMSA-2012-0068] Pipeline Safety: Verification of Records AGENCY: Pipeline and Hazardous Materials... issuing an Advisory Bulletin to remind operators of gas and hazardous liquid pipeline facilities to verify...

  16. 75 FR 73160 - Pipeline Safety: Information Collection Activities

    Science.gov (United States)

    2010-11-29

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No...-Related Conditions on Gas, Hazardous Liquid, and Carbon Dioxide Pipelines and Liquefied Natural Gas... Pipelines and Liquefied Natural Gas Facilities.'' The Pipeline Safety Laws (49 U.S.C. 60132) require each...

  17. 75 FR 9018 - Pipeline Safety: Random Drug Testing Rate

    Science.gov (United States)

    2010-02-26

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket ID PHMSA-2010-0034] Pipeline Safety: Random Drug Testing Rate AGENCY: Pipeline and Hazardous Materials... pipelines and operators of liquefied natural gas facilities must select and test a percentage of covered...

  18. 75 FR 4136 - Pipeline Safety: Request To Modify Special Permit

    Science.gov (United States)

    2010-01-26

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No. PHMSA-2009-0377] Pipeline Safety: Request To Modify Special Permit AGENCY: Pipeline and Hazardous... coating on its gas pipeline. DATES: Submit any comments regarding this special permit modification request...

  19. 76 FR 11853 - Pipeline Safety: Request for Special Permit

    Science.gov (United States)

    2011-03-03

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No. PHMSA-2011-0027] Pipeline Safety: Request for Special Permit AGENCY: Pipeline and Hazardous Materials... a 24-inch mainline natural gas pipeline, 595 feet in length. The first segment of the special permit...

  20. 77 FR 34458 - Pipeline Safety: Requests for Special Permit

    Science.gov (United States)

    2012-06-11

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No. PHMSA-2012-0112] Pipeline Safety: Requests for Special Permit AGENCY: Pipeline and Hazardous Materials... BreitBurn Energy Company LP, two natural gas pipeline operators, seeking relief from compliance with...

  1. 78 FR 14877 - Pipeline Safety: Incident and Accident Reports

    Science.gov (United States)

    2013-03-07

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket ID PHMSA-2013-0028] Pipeline Safety: Incident and Accident Reports AGENCY: Pipeline and Hazardous Materials... PHMSA F 7100.2--Incident Report--Natural and Other Gas Transmission and Gathering Pipeline Systems and...

  2. 78 FR 65429 - Pipeline Safety: Request for Special Permit

    Science.gov (United States)

    2013-10-31

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No. PHMSA-2010-0041] Pipeline Safety: Request for Special Permit AGENCY: Pipeline and Hazardous Materials...-0041 Williams Gas Pipeline 49 CFR 192.150........ To authorize the extension Company, LLC (WGP). of a...

  3. 49 CFR 192.513 - Test requirements for plastic pipelines.

    Science.gov (United States)

    2010-10-01

    ... 49 Transportation 3 2010-10-01 2010-10-01 false Test requirements for plastic pipelines. 192.513 Section 192.513 Transportation Other Regulations Relating to Transportation (Continued) PIPELINE AND... Test requirements for plastic pipelines. (a) Each segment of a plastic pipeline must be tested in...

  4. Pipelines in Louisiana, Geographic NAD83, USGS (1999) [pipelines_la_usgs_1999

    Data.gov (United States)

    Louisiana Geographic Information Center — This dataset contains vector line map information of various pipelines throughout the State of Louisiana. The vector data contain selected base categories of...

  5. Regular pipeline maintenance of gas pipeline using technical operational diagnostics methods

    Energy Technology Data Exchange (ETDEWEB)

    Volentic, J [Gas Transportation Department, Slovensky plynarensky priemysel, Slovak Gas Industry, Bratislava (Slovakia)

    1998-12-31

    Slovensky plynarensky priemysel (SPP) has operated 17 487 km of gas pipelines in 1995. The length of the long-line pipelines reached 5 191 km, distribution network was 12 296 km. The international transit system of long-line gas pipelines ranged 1 939 km of pipelines of various dimensions. The described scale of transport and distribution system represents a multibillion investments stored in the ground, which are exposed to the environmental influences and to pipeline operational stresses. In spite of all technical and maintenance arrangements, which have to be performed upon operating gas pipelines, the gradual ageing takes place anyway, expressed in degradation process both in steel tube, as well as in the anti-corrosion coating. Within a certain time horizon, a consistent and regular application of methods and means of in-service technical diagnostics and rehabilitation of existing pipeline systems make it possible to save substantial investment funds, postponing the need in funds for a complex or partial reconstruction or a new construction of a specific gas section. The purpose of this presentation is to report on the implementation of the programme of in-service technical diagnostics of gas pipelines within the framework of regular maintenance of SPP s.p. Bratislava high pressure gas pipelines. (orig.) 6 refs.

  6. Regular pipeline maintenance of gas pipeline using technical operational diagnostics methods

    Energy Technology Data Exchange (ETDEWEB)

    Volentic, J. [Gas Transportation Department, Slovensky plynarensky priemysel, Slovak Gas Industry, Bratislava (Slovakia)

    1997-12-31

    Slovensky plynarensky priemysel (SPP) has operated 17 487 km of gas pipelines in 1995. The length of the long-line pipelines reached 5 191 km, distribution network was 12 296 km. The international transit system of long-line gas pipelines ranged 1 939 km of pipelines of various dimensions. The described scale of transport and distribution system represents a multibillion investments stored in the ground, which are exposed to the environmental influences and to pipeline operational stresses. In spite of all technical and maintenance arrangements, which have to be performed upon operating gas pipelines, the gradual ageing takes place anyway, expressed in degradation process both in steel tube, as well as in the anti-corrosion coating. Within a certain time horizon, a consistent and regular application of methods and means of in-service technical diagnostics and rehabilitation of existing pipeline systems make it possible to save substantial investment funds, postponing the need in funds for a complex or partial reconstruction or a new construction of a specific gas section. The purpose of this presentation is to report on the implementation of the programme of in-service technical diagnostics of gas pipelines within the framework of regular maintenance of SPP s.p. Bratislava high pressure gas pipelines. (orig.) 6 refs.

  7. A Novel Method to Enhance Pipeline Trajectory Determination Using Pipeline Junctions.

    Science.gov (United States)

    Sahli, Hussein; El-Sheimy, Naser

    2016-04-21

    Pipeline inspection gauges (pigs) have been used for many years to perform various maintenance operations in oil and gas pipelines. Different pipeline parameters can be inspected during the pig journey. Although pigs use many sensors to detect the required pipeline parameters, matching these data with the corresponding pipeline location is considered a very important parameter. High-end, tactical-grade inertial measurement units (IMUs) are used in pigging applications to locate the detected problems of pipeline using other sensors, and to reconstruct the trajectories of the pig. These IMUs are accurate; however, their high cost and large sizes limit their use in small diameter pipelines (8″ or less). This paper describes a new methodology for the use of MEMS-based IMUs using an extended Kalman filter (EKF) and the pipeline junctions to increase the position parameters' accuracy and to reduce the total RMS errors even during the unavailability of above ground markers (AGMs). The results of this new proposed method using a micro-electro-mechanical systems (MEMS)-based IMU revealed that the position RMS errors were reduced by approximately 85% compared to the standard EKF solution. Therefore, this approach will enable the mapping of small diameter pipelines, which was not possible before.

  8. Worldwide natural gas pipeline situation. Sekai no tennen gas pipeline jokyo

    Energy Technology Data Exchange (ETDEWEB)

    Arimoto, T [Osaka Gas Co. Ltd., Osaka (Japan)

    1993-03-01

    Constructing natural gas pipelines in wide areas requires investments of a huge amount. Many countries are building natural gas supply infrastructures under public support as nations' basic policy of promoting use of natural gas. This paper describes the present conditions of building pipelines in Western Europe, the U.S.A., Korea and Taiwan. In Western Europe, transporting companies established in line with the national policy own trunk pipelines and storage facilities, and import and distribute natural gas. The U.S.A. has 2300 small and large pipeline companies bearing transportation business. Pipelines extend about 1.9 million kilometers in total, with trunk pipelines accounting for about 440,000 kilometers. The companies are given eminent domain for the right of way. Korea has a plan to build a pipeline network with a distance of 1600 kilometers in around 2000. Taiwan has completed trunk pipelines extending 330 kilometers in two years. In Japan, the industry is preparing draft plans for wide area pipeline construction. 5 figs., 1 tab.

  9. Pipeline engineering. 8. rev. and enl. ed.

    International Nuclear Information System (INIS)

    Wagner, W.

    2000-01-01

    Apart from calculating the strength of pipeline components planning and design are the most important tasks on the areas of apparatus manufacturing, fluid engineering, process engineering and thermal engineering. It is therefore necessary that the flow diagrams of a plant are clearly understandable and in accordance with the technical rules even in the early stages of planning. This book concentrates on steel pipeline which are not laid underground but of the type used mostly in industrial applications. The pictures and equations provided can be used for the design of pipelines, tables and diagrams are given to facilitate estimation of elasticity, pipeline pressure losses and insulating thicknesses. An overview of the equations is given at the end of the book. Many examples facilitate learning. (orig.) [de

  10. Australia's changing natural gas and pipeline industry

    International Nuclear Information System (INIS)

    Kimber, M.J.

    1998-01-01

    The future is bright for continued development of Australia's natural gas pipeline infrastructure, as well as for privatization and private energy infrastructure growth. Gas demands are growing and the development of open access principles for all natural gas transmission and distribution pipelines heralds a much more market focused industry. Within the next few years gas-on-gas competition will apply to supply, pipelines, and retail marketing. No longer will operators be able to pass on high costs resulting from inefficiencies to their customers. This article describes the changing Australian gas industry, evaluates the drivers for change and looks at ways the industry is responding to new regulatory regimes and the development and use of new pipeline technology

  11. Citizenship program in near communities of pipelines

    Energy Technology Data Exchange (ETDEWEB)

    Mascarenhas, Carina R.; Vilas Boas, Ianne P. [TELSAN Engenharia, Belo Horizonte, MG (Brazil); Bourscheid, Pitagoras [PETROBRAS S.A., Rio de Janeiro, RJ (Brazil)

    2009-12-19

    During the construction of a pipeline, the IENE - Engineering Unit of PETROBRAS, responsible for the construction and erection of pipelines and related plants in northeastern Brazil, crossed more than 7 states and 250 counties, had implemented a social responsibility program, in special a citizenship program. This action was the result of community studies located near of the pipelines AID - Direct Influence Area (438 yards right and left of the pipeline) and through the evidence that those locations were poor and have no personal documents and citizen position in society. This paper intents to share the experience of IENE about its citizen program that worked in three big lines: community mobilization; citizenship qualification; and citizenship board. This last one, turns possible to people obtains theirs personal documents and exercise the plenitude of citizenship. (author)

  12. 78 FR 53190 - Pipeline Safety: Notice to Operators of Hazardous Liquid and Natural Gas Pipelines of a Recall on...

    Science.gov (United States)

    2013-08-28

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No. PHMSA-2013-0185] Pipeline Safety: Notice to Operators of Hazardous Liquid and Natural Gas Pipelines of a Recall on Leak Repair Clamps Due to Defective Seal AGENCY: Pipeline and Hazardous Materials Safety...

  13. 78 FR 42889 - Pipeline Safety: Reminder of Requirements for Utility LP-Gas and LPG Pipeline Systems

    Science.gov (United States)

    2013-07-18

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration 49 CFR Part 192 [Docket No. PHMSA-2013-0097] Pipeline Safety: Reminder of Requirements for Utility LP-Gas and LPG Pipeline Systems AGENCY: Pipeline and Hazardous Materials Safety Administration (PHMSA), DOT. ACTION...

  14. Black powder in gas pipelines

    Energy Technology Data Exchange (ETDEWEB)

    Sherik, Abdelmounam [Saudi Aramco, Dhahran (Saudi Arabia)

    2009-07-01

    Despite its common occurrence in the gas industry, black powder is a problem that is not well understood across the industry, in terms of its chemical and physical properties, source, formation, prevention or management of its impacts. In order to prevent or effectively manage the impacts of black powder, it is essential to have knowledge of its chemical and physical properties, formation mechanisms and sources. The present paper is divided into three parts. The first part of this paper is a synopsis of published literature. The second part reviews the recent laboratory and field work conducted at Saudi Aramco Research and Development Center to determine the compositions, properties, sources and formation mechanisms of black powder in gas transmission systems. Microhardness, nano-indentation, X-ray Diffraction (XRD), X-ray Fluorescence (XRF) and Scanning Electron Microscopy (SEM) techniques were used to analyze a large number of black powder samples collected from the field. Our findings showed that black powder is generated inside pipelines due to internal corrosion and that the composition of black powder is dependent on the composition of transported gas. The final part presents a summary and brief discussion of various black powder management methods. (author)

  15. Simplified Technique for Predicting Offshore Pipeline Expansion

    Science.gov (United States)

    Seo, J. H.; Kim, D. K.; Choi, H. S.; Yu, S. Y.; Park, K. S.

    2018-06-01

    In this study, we propose a method for estimating the amount of expansion that occurs in subsea pipelines, which could be applied in the design of robust structures that transport oil and gas from offshore wells. We begin with a literature review and general discussion of existing estimation methods and terminologies with respect to subsea pipelines. Due to the effects of high pressure and high temperature, the production of fluid from offshore wells is typically caused by physical deformation of subsea structures, e.g., expansion and contraction during the transportation process. In severe cases, vertical and lateral buckling occurs, which causes a significant negative impact on structural safety, and which is related to on-bottom stability, free-span, structural collapse, and many other factors. In addition, these factors may affect the production rate with respect to flow assurance, wax, and hydration, to name a few. In this study, we developed a simple and efficient method for generating a reliable pipe expansion design in the early stage, which can lead to savings in both cost and computation time. As such, in this paper, we propose an applicable diagram, which we call the standard dimensionless ratio (SDR) versus virtual anchor length (L A ) diagram, that utilizes an efficient procedure for estimating subsea pipeline expansion based on applied reliable scenarios. With this user guideline, offshore pipeline structural designers can reliably determine the amount of subsea pipeline expansion and the obtained results will also be useful for the installation, design, and maintenance of the subsea pipeline.

  16. Outlook '98 - Gas and oil pipelines

    International Nuclear Information System (INIS)

    Curtis, B.

    1998-01-01

    Due to rising North American demand, especially by the United States, by the end of 1997 there were plans to build 15 new pipelines over the next three years, at an estimated cost of $17 billion. Canada''s proximity to the United States, combined with huge Canadian reserves, and the fact that Canada already supplies some 15 per cent of U.S. requirements, makes Canada the obvious choice for filling future demand. This explains why most, if not all, current pipeline expansion projects are targeting markets in the U.S. Market forces will determine which of the projects will actually go forward. From the point of view of the Canadian Energy Pipeline Association pipeline regulatory reform, pipeline safety, integrity and climate change will be the Association''s key concerns during 1998. To that end, the Association is cooperating with the National Energy Board in a multi-million dollar study of stress corrosion cracking. The Association has also developed a Manual of Recommended Practices for the use of member companies to assist them to tailor stress corrosion cracking practices to their own operations. Meeting Canada''s commitment at the Kyoto Conference for greenhouse gas emissions of six per cent below 1990 levels by the year 2008 to 2012 (in effect a 25 per cent reduction from the level anticipated in the year 2000), a very difficult task according to industry experts, is also among the high priority items on the pipeline industry''s agenda for 1998

  17. World pipeline work set for rapid growth

    International Nuclear Information System (INIS)

    Anon.

    1992-01-01

    This paper reports on international pipeline construction which has entered a fast-growth period, accelerated by the new political and economic realities around the world and increasing demand for natural gas, crude oil and refined petroleum products. Many projects are under way or in planning for completion in the mid- to late 1990s in Europe, South America, Asia and the Middle East. Pipeline And Gas Journal's projection calls for construction or other work on 30,700 miles of new natural gas, crude oil and refined products pipelines in the 1992-93 period outside Canada and the U.S. These projects will cost an estimated $30 billion-plus. Natural gas pipelines will comprise most of the mileage, accounting for almost 23,000 miles at an estimated cost of $26.3 billion. Products pipelines, planned or under construction, will add another 5,800 miles at a cost of $2.8 billion. Crude oil pipelines, at a minimum, will total 1,900 new miles at a cost of slightly under $1 billion

  18. Seismic vulnerability of natural gas pipelines

    International Nuclear Information System (INIS)

    Lanzano, Giovanni; Salzano, Ernesto; Santucci de Magistris, Filippo; Fabbrocino, Giovanni

    2013-01-01

    This work deals with the analysis of the interaction of earthquakes with pipelines transporting and distributing natural gas for industrial and civil use. To this aim, a new large data-set of seismic information classified on the basis of selected seismological, geotechnical and structural parameters is presented and analyzed. Particular attention is devoted to continuous pipelines under strong ground shaking, which is the geotechnical effect due to passage of waves in soil. Results are provided in terms of the likelihood of the loss of containment with respect to Peak Ground Velocity (PGV), a seismic intensity parameter which may be easily retrieved either from local authorities and public databases or from site dependent hazard analysis. Fragility functions and seismic intensity threshold values for the failure and for the loss of containment of gas from pipeline systems are also given. The obtained functions can be easily implemented in existing codes and guidelines for industrial risk assessment, land-use planning, and for the design of public distribution network, with specific reference to Natural—Technological interaction (Na-Tech). -- Highlights: • The seismic vulnerability of natural gas pipelines is analyzed. • A collection of data for pipelines damaged by earthquake is given. • Damage states and risk states for pipelines are defined. • Consequence-based fragility formulations for the loss of containment are given • Seismic threshold values for public authority, risk assessment and gas distribution are shown

  19. Rupture detection device for pipeline in reactor

    International Nuclear Information System (INIS)

    Murakoshi, Toshinori; Kanamori, Shigeru; Shirasawa, Hirofumi.

    1991-01-01

    A difference between each of the pressures in a plurality of pipelines disposed in a shroud a reactor container and a pressure outside of the shroud is detected, thereby enabling safety and reliable detection even for simultaneous rapture and leakage of the pipelines. That is, a difference between the pressure of a steam phase outside of the shroud and a pressure in each of a plurality of low pressure injection pipelines in an emergency core cooling system opened to the inside of the shroud in the reactor container is detected by a difference pressure detector for each of them. Then, an average value for each of the pressure difference is determined, which is compared with the difference pressure obtained from each of the detectors in a comparator. Then, if openings should be caused by rupture, leakage or the like in any of the pipelines, the pressure in that pipeline is lowered to a vicinity of an atmospheric pressure and at the vapor phase pressure at the lowest. If the pressure is compared with the average value by the comparator, a negative difference is caused. Accordingly, an alarming unit generates an alarm based on the pressure difference signal, thereby enabling to specify the failed pipeline and provide an announce of the failure. (I.S.)

  20. GRAVITY PIPELINE TRANSPORT FOR HARDENING FILLING MIXTURES

    Directory of Open Access Journals (Sweden)

    Leonid KROUPNIK

    2015-12-01

    Full Text Available In underground mining of solid minerals becoming increasingly common development system with stowing hardening mixtures. In this case the natural ore array after it is replaced by an artificial excavation of solidified filling mixture consisting of binder, aggregates and water. Such a mixture is prepared on the surface on special stowing complexes and transported underground at special stowing pipelines. However, it is transported to the horizons of a few kilometers, which requires a sustainable mode of motion of such a mixture in the pipeline. Hardening stowing mixture changes its rheological characteristics over time, which complicates the calculation of the parameters of pipeline transportation. The article suggests a method of determining the initial parameters of such mixtures: the status coefficient, indicator of transportability, coefficient of hydrodynamic resistance to motion of the mixture. These indicators characterize the mixture in terms of the possibility to transport it through pipes. On the basis of these indicators is proposed methodology for calculating the parameters of pipeline transport hardening filling mixtures in drift mode when traffic on the horizontal part of the mixture under pressure column of the mixture in the vertical part of the backfill of the pipeline. This technique allows stable operation is guaranteed to provide pipeline transportation.

  1. Remote operation for pipelines; Operacao remota para gasodutos

    Energy Technology Data Exchange (ETDEWEB)

    Teixeira, Paulo Lyra Borgerth [TBG - Transportadora Brasileira Gasoduto Bolivia Brasil S.A., Rio de Janeiro, RJ (Brazil)

    2003-07-01

    This paper describes pipeline GASBOL which are remotely monitored, operated and controlled from a central control station in Rio de Janeiro, Brazil. This is a result of TBG's experience in design, construction and operation of compressor stations and city gates that are built for unattended operation. Only a small maintenance crew is necessary for routine tasks. In this connection, a complete set of resources has been implemented in order to ensure the required reliability level. This includes monitoring instruments, redundant systems and protections, together with automatic control system for each of the relevant components. Equipment status signals, process variables as well as alarm and trip signals are exchanged via a SCADA system with the Control and Supervision Center, CSC, in Rio de Janeiro. In addition, the CSC is capable of performing all relevant control actions such as start / stop compressor units and station auxiliaries, also remotely setting the station pressure and flow control points. The paper describes also the architecture and configuration of the supervisory and control functions which are performed by means of a SCADA system, along with the pipeline telecommunications system. (author)

  2. A fast-track preliminary thermo-mechanical design of oil export pipelines from P-56 platform

    Energy Technology Data Exchange (ETDEWEB)

    Solano, Rafael F.; Mendonca, Salete M. de [PETROBRAS S.A., Rio de Janeiro, RJ (Brazil); Franco, Luciano D.; Walker, Alastair; El-Gebaly, Sherif H. [INTECSEA, Rio de Janeiro, RJ (Brazil)

    2009-12-19

    The oil export pipelines of Marlim Sul field Module 3, Campus Basin, offshore Brazil, will operate in high pressure and temperature conditions, and will be laid on seabed crossing ten previously laid pipelines along the routes. In terms of thermo-mechanical design, these conditions turn out to be great challenges. In order to obtain initial results and recommendations for detail design, a preliminary thermo-mechanical design of pipelines was carried out as a fast-track design before the bid. This way, PETROBRAS can assess and emphasize the susceptibility of these lines to lateral buckling and pipeline walking behavior. Therefore, PETROBRAS can present a preliminary mitigation strategy for lateral buckling showing solutions based on displacement controlled criteria and by introducing buckle initiation along the pipeline using distribution buoyancy. Besides that, axial displacements and loads at the pipeline ends can be furnished also in order to provide a basis for the detailed design. The work reported in this paper follows the SAFEBUCK JIP methodology and recommendation, which were used to determine the allowable strain and maximum allowable VAS (Virtual Anchor Spacing) considered in the buckling mitigation strategy. The paper presents also the formation of uncontrolled buckles on the seabed and the propensity for pipeline walking in its sections between buckles. The buckling mitigation strategy established in this preliminary design confirms that the oil pipeline specifications are adequate to maintain integrity during design life. (author)

  3. Report of study group 4.3 ''pipeline integrity management and safety''

    Energy Technology Data Exchange (ETDEWEB)

    Clavel, P.

    2000-07-01

    This report highlights the Pipeline integrity Management methods being implemented by gas companies. These aim at maintaining the current high safety level, prevent major hazards, ensure the integrity of the pipeline and protect people and environment in the vicinity of the pipeline in the most cost effective way. It should be noticed that Pipeline Integrity Management aspects, technical and organisational, are included in the more general framework of the Safety Management System. Currently, more and more gas companies implement such a system on the basis of standards like ISO 9000 and so on. In this way, the report shows how practices of Pipeline Integrity Management are continually developing in order to adapt to their environment, and to improve performance. Past experience and imminent developments show that Pipeline Integrity Management is a flexible and efficient approach to improve safety in the long term. Consequently, Pipeline Integrity Management Systems are, under the control of authorities, the best alternative to additional safety regulations. Within the context of deregulation of the European markets and globalization Pipeline Integrity Management appears to be a tool to promote the gas industry in the eyes of the authorities, the market regulators and the customers (industrialists,...). (author)

  4. Analytical solutions for peak and residual uplift resistance of pipelines

    Energy Technology Data Exchange (ETDEWEB)

    Nixon, J.F. [Nixon Geotech Ltd., Calgary, AB (Canada); Oswell, J.M. [Naviq Consulting Inc., Calgary, AB (Canada)

    2010-07-01

    Frost heave can occur on cold pipelines that traverse unfrozen, non permafrost terrain. The stresses experienced by the pipeline are partly a function of the strength of the soil on the non heaving side of the frozen-unfrozen interface. This paper proposed three analytical solutions to estimate the soil uplift resistance by considering the pipeline and soil to act similar to a strip footing, a punching shear failure, and by considering the formation of horizontal crack emanating from the spring line of the pipe. Peak uplift resistance and residual uplift resistance were discussed. Results for full scale pipe and for laboratory scale model pipes were presented, with particular reference to cover depth, temperature and crack width; and limits to residual uplift resistance. It was concluded that the peak uplift resistance and the residual uplift resistance are generally independent and controlled by different factors. The peak resistance is related directly to pipe diameter, and less strongly dependent on springline depth. It is also strongly dependent on soil temperature. However, the residual uplift resistance is strongly dependent on burial depth, weakly dependent on pipe displacement rate and also on soil temperature. 15 refs., 19 figs.

  5. A study on an autonomous pipeline maintenance robot, 5

    International Nuclear Information System (INIS)

    Fukuda, Toshio; Hosokai, Hidemi; Otsuka, Masashi.

    1989-01-01

    The path planning is very important for the pipeline maintenance robot because there are many obstacles on pipeline such as flanges and T-joints and others, and because pipelines are constructed as a connected network in a very complicated way. Furthermore the maintenance robot Mark III previously reported has the ability to transit from one pipe to another the path planner should consider. The expert system especially aimed for path planning, named PPES (Path Planning Expert System), is described in this paper. A human-operator has only to give some tasks to this system. This system automatically replies with the optimal path, which is based on the calculation of the task levels and list of some control commands. Task level is a criterion to determine one optimal path. It consists of the difference of potential energies, the static joint torques, velocity of the robot, step numbers of the grippers' or body's movement, which the robot requires. This system also has graphic illustrations, so that the operator can easily check and understand the plant map and the result of the path planning. (author)

  6. Case histories of pipeline exposure at stream crossings in Alberta

    Energy Technology Data Exchange (ETDEWEB)

    Malcovish, C.D. [Malaron Engineering Ltd., St. Albert, AB (Canada); Janz, A. [ATCO Pipelines, Edmonton, AB (Canada); Gray, D.M. [Gulf Midstream Services, Edmonton, AB (Canada)

    2000-07-01

    Five case histories of river channel changes and associated pipeline exposure problems at river and stream crossings in Alberta were discussed with emphasis on the need for proactive inspection. For each case, the different hydrologic and geomorphic factors that resulted in erosion problems were reviewed and the mitigative actions that were taken to solve the problems were described. It was shown that in some cases, there are inherent difficulties in identifying potential erosion problems at the project design stage. It was also demonstrated that systematic monitoring and inspection procedures are useful for planning and implementing remedial measures before problems occur. There are many natural and anthropogenic causes of channel degradation. Upstream progressing degradation is usually the most common problem encountered at pipeline crossings in Alberta. The two main causes are both flood related. They include channel shortening by cutoffs across long meandering loops, and washout of downstream slope controls such as large beaver dams. The five case studies presented in this paper were: (1) North Saskatchewan River crossing near Drayton Valley, (2) Smoky River crossing near Grande Cache, (3) Hells Creek crossing near Grande Cache, (4) Modeste Creek crossing near Breton, and (5) Freeman River crossing near Swan Hills. It was emphasized that pipeline operators must consider past channel changes and geomorphic analysis to predict future channel instability. 15 figs.

  7. New and Pipeline Drugs for Gout.

    Science.gov (United States)

    Keenan, Robert T; Schlesinger, Naomi

    2016-06-01

    Gout is the most common inflammatory arthropathy in the western world. Affecting millions and accounting for lost wages, increased health care costs, and significant disability, it remains a burden for those afflicted, their families, and the health care system. Despite the availability of a number of effective therapies, gout is often inadequately treated, and its impact on the patients overall health and well-being is underestimated by physicians and patients alike. For many decades, controlling acute flares was the priority in the management of gout. More recently, however, a deeper understanding of gout pathophysiology has resulted in a new appreciation that gout impacts the patient with consequences well beyond the episodes of acute inflammatory arthritis. Reflecting the chronic nature of the disease, gout treatment needs to be chronic as well, and aimed at reducing the underlying cause of gout-hyperuricemia-as well as the symptom of acute attacks. Therapy therefore requires both urate lowering and anti-inflammatory strategies. Unfortunately, the most commonly used urate lowering and anti-inflammatory treatments may be problematic in some gout patients, who often have multiple comorbidities that establish relative contraindications. Novel urate lowering therapies, and new medications to treat and prevent acute gouty flares, can not only improve care of the individual; they can also lead to a better discourse for the edification of those who manage and are managed for this underestimated disease. In this paper, we discuss new and pipeline drugs for acute gout, prophylactic anti-inflammatory therapies as well as urate lowering therapies.

  8. APPLIED OF IMPRESSED CURRENT CATHODIC PROTECTION DESIGN FOR FUEL PIPELINE NETWORK AT NAVAL BASE

    Directory of Open Access Journals (Sweden)

    k. Susilo

    2017-06-01

    Full Text Available Indonesian Navy (TNI AL is the main component for Maritime Security and Defence. Because of that, TNI AL needs Indonesian Warship (KRI to covered Maritime area. The main requirement from KRI is fulfilled by demand. To pock of fuel demand from KRI at Naval Base, it needs a new pipeline of fuel distribution network system. The pipeline network system used for maximum lifetime must be protected from corrosion. Basically, there are five methods of corrosion control such as change to a more suitable material, modification to the environment, use of protective coating, design modification to the system or component, and the application of cathodic or anodic protection. Cathodic protection for pipeline available in two kinds, namely Sacrifice Anode and Impressed Current Cathodic Protection (ICCP. This paper makes analysis from design of Impressed Current Cathodic Protection and total current requirement in the method. This paper showed both experimental from speciment test and theoritical calculation. The result showed that design of Impressed Current Cathodic Protection on fuel distribution pipeline network system requires voltage 33,759 V(DC, protection current 6,6035 A(DC by theoritical calculation and 6,544 A(DC from pipeline specimen test, with 0,25 mpy for corrosion rate. Transformer Rectifier design needs requirements 45 V with 10 A for current. This research result can be made as literature and standardization for Indonesian Navy in designing the Impressed Current Cathodic Protection for fuel distribution pipeline network system.

  9. Turning Noise into Signal: Utilizing Impressed Pipeline Currents for EM Exploration

    Science.gov (United States)

    Lindau, Tobias; Becken, Michael

    2017-04-01

    Impressed Current Cathodic Protection (ICCP) systems are extensively used for the protection of central Europe's dense network of oil-, gas- and water pipelines against destruction by electrochemical corrosion. While ICCP systems usually provide protection by injecting a DC current into the pipeline, mandatory pipeline integrity surveys demand a periodical switching of the current. Consequently, the resulting time varying pipe currents induce secondary electric- and magnetic fields in the surrounding earth. While these fields are usually considered to be unwanted cultural noise in electromagnetic exploration, this work aims at utilizing the fields generated by the ICCP system for determining the electrical resistivity of the subsurface. The fundamental period of the switching cycles typically amounts to 15 seconds in Germany and thereby roughly corresponds to periods used in controlled source EM applications (CSEM). For detailed studies we chose an approximately 30km long pipeline segment near Herford, Germany as a test site. The segment is located close to the southern margin of the Lower Saxony Basin (LSB) and part of a larger gas pipeline composed of multiple segments. The current injected into the pipeline segment originates in a rectified 50Hz AC signal which is periodically switched on and off. In contrast to the usual dipole sources used in CSEM surveys, the current distribution along the pipeline is unknown and expected to be non-uniform due to coating defects that cause current to leak into the surrounding soil. However, an accurate current distribution is needed to model the fields generated by the pipeline source. We measured the magnetic fields at several locations above the pipeline and used Biot-Savarts-Law to estimate the currents decay function. The resulting frequency dependent current distribution shows a current decay away from the injection point as well as a frequency dependent phase shift which is increasing with distance from the injection

  10. Automatic process control for pipeline: an ally in the quest for excellence in quality; Controle automatizado do processo de revestimento de dutos: um aliado na busca da excelencia em qualidade

    Energy Technology Data Exchange (ETDEWEB)

    Silva, Christian E.; Santos, Paulo T.; Nunes, Matheus; Sartori, Marcio [Soco Ril do Brasil S.A., Pindamonhangaba, SP (Brazil); Populin, German [Soco-Ril da Argentina S.A. (Argentina); Ferreira, Joaquim C. [Tenaris Confab, Pindamonhangaba, SP (Brazil)

    2004-07-01

    Process is any specific combination of machines, methods, tools and people which aim to obtain products or services with high quality. Any changing in one of these elements may result in another process. The concern in assuring its control totally owe to the necessity of having quickly answers related to the standards deviation. Herewith, it is possible to get as much uniformity as possible from that quality characteristic. Through a thickness automatic controlled system it may be possible to evaluate in real time the process itself, identifying tendencies of sequential or temporal performance. Therefore it is possible to act instantaneously adjusting the process, complying with client's specification. The present paper describes the applicability of a automatic controlled system and shows the advantages of its using. (author)

  11. Integrated surface management for pipeline construction: The Mid-America Pipeline Company Four Corners Project

    Science.gov (United States)

    Maria L. Sonett

    1999-01-01

    Integrated surface management techniques for pipeline construction through arid and semi-arid rangeland ecosystems are presented in a case history of a 412-mile pipeline construction project in New Mexico. Planning, implementation and monitoring for restoration of surface hydrology, soil stabilization, soil cover, and plant species succession are discussed. Planning...

  12. 77 FR 32631 - Lion Oil Trading & Transportation, Inc., Magnolia Pipeline Company, and El Dorado Pipeline...

    Science.gov (United States)

    2012-06-01

    ... DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. OR12-13-000] Lion Oil... of the Commission's Rules of Practice and Procedure, 18 CFR 385.202 (2011), Lion Oil Trading & Transportation, Inc., Magnolia Pipeline Company, and El Dorado Pipeline Company, collectively, Lion Companies...

  13. The Dangers of Pipeline Thinking: How the School-to-Prison Pipeline Metaphor Squeezes out Complexity

    Science.gov (United States)

    McGrew, Ken

    2016-01-01

    In this essay Ken McGrew critically examines the "school-to-prison pipeline" metaphor and associated literature. The origins and influence of the metaphor are compared with the origins and influence of the competing "prison industrial complex" concept. Specific weaknesses in the "pipeline literature" are examined.…

  14. Skaha Lake crossing, innovations in pipeline installation

    International Nuclear Information System (INIS)

    Fernandez, M.L.; Bryce, P.W.; Smith, J.D.

    1995-01-01

    This paper describes the construction of a 10.8 km long NPS16 (406 mm, 16 inch diameter) pipeline, across Skaha Lake, in the south Okanagan valley, British Columbia, Canada. The water crossing is part of the 32 km South Okanagan Natural Gas Pipeline Project (SONG) operated by BC Gas. The pipeline is located in a region dependent on year-round tourism. Therefore, the design and construction was influenced by sensitive environmental and land use concerns. From earlier studies, BC Gas identified surface tow or lay as preferred installation methods. The contractor, Fraser River Pile and Dredge departed from a conventional laybarge methodology after evaluating environmental data and assessing locally available equipment. The contractor proposed a surface tow with multiple surface tie-ins. This approach modification to the ''Surface Tow and Buoy Release Method'' (STBRM) used previously with success on relatively short underwater pipelines. A total of 10 pipe strings, up to 1 km long, were towed into position on the lake and tied-in using a floating platform. The joined pipeline was lowered to the lakebed by divers releasing buoys while tension was maintained from a winch barge at the free end of the pipeline. From analysis and field verified measurement the installation stresses were well below the allowable limits during all phases of construction. The entire construction, including mobilization and demobilization, lasted less than three months, and actual pipelaying less than three weeks. Installation was completed within budget and on schedule, without any environmental or safety related incidents. The SONG pipeline became operational in December 1994

  15. Pipeline capacity and heavy oil markets

    International Nuclear Information System (INIS)

    Scott, G.R.

    1993-01-01

    Aspects of transporting heavy crude to markets from Canadian sources are discussed, with reference to pipeline expansion, western Canadian crude supply, and exports to various Petroleum Administration for Defense Districts (PADDs) in the USA. Pipeline expansions have been proposed by Interprovincial Pipeline, Trans Mountain Pipeline, Rangeland, and Wascana, and some of these proposals are in the review stage. Western Canadian crude supply is expected to peak at 1.9 million bbl/d in 1996. An increase in heavy crude supply is expected but this increase will not be sufficient to offset a decline in light crude supply. Adequate pipeline capacity should exist with the Interprovincial expansion volume of 170,000 bbl/d and the Trans Mountain expansion of 38,000 bbl/d forecast to be in place by 1995. Canadian crude exports to the USA have steadily increased since 1989, and heavy crude exports have grown an average of 20,000 bbl/d each year. In PADD Region IV, oil production is declining and ca 20,000 bbl/d of heavy crude will be needed by the year 2000; additional pipeline capacity will be required. In PADD Region II, Canadian heavy crude imports are ca 390,000 bbl/d and further market opportunities exist, after the Interprovincial expansion is complete. When the various combinations of possible pipeline expansions or reversals are considered, a range of heavy crude near-term growth potentials is obtained in which Canadian heavy oil would displace offshore heavy oil supplied to USA refineries. This potential is seen to range from 35,000 bbl/d to 200,000 bbl/d. 7 refs., 20 figs., 3 tabs

  16. System of maintenance of sustainability of oil pipelines

    International Nuclear Information System (INIS)

    Aleskerov, R.

    2005-01-01

    Full text : Development of the ecological science defining interrelation and interaction of system of an alive and lifeless matter, opens new opportunities and decisions of a problem of system maintenance of stability of oil pipelines and other engineering constructions and devices of strategic purpose. In work the methodology of system maintenance of stability of oil pipelines is resulted. It is known, that at transport of oil and gas a plenty of automatic and electronic devices, devices are applied to the control and the signal system of parameters of dangerous and harmful factors, a condition of the technological and test equipment, diagnostics and the control of pipelines. The control of parameters of safety of an oil pipeline over the operation, considering influence of heavy climatic conditions during all line, etc. (1, 2, 3) is carried out. Therefore stability of work of various parts of system of an oil pipeline depends on reliability and accuracy of work of devices and devices. However, thus influence of variations of geomagnetic fields and the geodynamic processes breaking the indications of devices and devices which lead to infringement reliability of all design of system of an oil pipeline is not considered. In turn, specified leads to failure, lost of human and natural resources. Now, according to the accepted methodology of a safety of working conditions, potential dangers of any activity, only person, with the subsequent development of measures of protection (4) are considered. Proceeding from it all surrounding material world shares on the following objects forming in aggregate working conditions: subjects of work.; means of production; products of work; the industrial environment; technology process; an environmental-climatic complex; fauna and flora; people (work of the person). Apparently from above resulted, in the accepted methodology potential dangers of any activity of the person and corresponding environmental -climatic conditions of the

  17. JGI Plant Genomics Gene Annotation Pipeline

    Energy Technology Data Exchange (ETDEWEB)

    Shu, Shengqiang; Rokhsar, Dan; Goodstein, David; Hayes, David; Mitros, Therese

    2014-07-14

    Plant genomes vary in size and are highly complex with a high amount of repeats, genome duplication and tandem duplication. Gene encodes a wealth of information useful in studying organism and it is critical to have high quality and stable gene annotation. Thanks to advancement of sequencing technology, many plant species genomes have been sequenced and transcriptomes are also sequenced. To use these vastly large amounts of sequence data to make gene annotation or re-annotation in a timely fashion, an automatic pipeline is needed. JGI plant genomics gene annotation pipeline, called integrated gene call (IGC), is our effort toward this aim with aid of a RNA-seq transcriptome assembly pipeline. It utilizes several gene predictors based on homolog peptides and transcript ORFs. See Methods for detail. Here we present genome annotation of JGI flagship green plants produced by this pipeline plus Arabidopsis and rice except for chlamy which is done by a third party. The genome annotations of these species and others are used in our gene family build pipeline and accessible via JGI Phytozome portal whose URL and front page snapshot are shown below.

  18. Monitoring device for the reactor pipelines

    International Nuclear Information System (INIS)

    Fukumoto, Akira.

    1983-01-01

    Purpose: To enable rapid and accurate operator's monitoring for the state of pipelines in a BWR type reactor. Constitution: Specific symbols are attached respectively to a fluid supply source constituting the pipelines of a nuclear reactor facility, a plurality of fluid passing points and equipments to be supplied with the fluid, and a symmetrical matrix comprising these symbols in rows and columns is constituted. Then, a matrix is prepared based on detection signals for the states of the liquid supply source, equipments to be supplied with fluid and pipeline equipments by rendering the matrix elements between the signals expressing the state capable of passing the fluid as 1 and the matrix elements between the signals expressing the state incapable of passing the fluid as 0 . The matrix thus prepared in a signal procession circuit and a matrix in a memory circuit previously storing the matrix expressing the normal state of the pipelines are compared to judge the state of the pipelines in a short time and with no misjudging. (Moriyama, K.)

  19. Color correction pipeline optimization for digital cameras

    Science.gov (United States)

    Bianco, Simone; Bruna, Arcangelo R.; Naccari, Filippo; Schettini, Raimondo

    2013-04-01

    The processing pipeline of a digital camera converts the RAW image acquired by the sensor to a representation of the original scene that should be as faithful as possible. There are mainly two modules responsible for the color-rendering accuracy of a digital camera: the former is the illuminant estimation and correction module, and the latter is the color matrix transformation aimed to adapt the color response of the sensor to a standard color space. These two modules together form what may be called the color correction pipeline. We design and test new color correction pipelines that exploit different illuminant estimation and correction algorithms that are tuned and automatically selected on the basis of the image content. Since the illuminant estimation is an ill-posed problem, illuminant correction is not error-free. An adaptive color matrix transformation module is optimized, taking into account the behavior of the first module in order to alleviate the amplification of color errors. The proposed pipelines are tested on a publicly available dataset of RAW images. Experimental results show that exploiting the cross-talks between the modules of the pipeline can lead to a higher color-rendition accuracy.

  20. Diagnostics and reliability of pipeline systems

    CERN Document Server

    Timashev, Sviatoslav

    2016-01-01

    The book contains solutions to fundamental problems which arise due to the logic of development of specific branches of science, which are related to pipeline safety, but mainly are subordinate to the needs of pipeline transportation.          The book deploys important but not yet solved aspects of reliability and safety assurance of pipeline systems, which are vital aspects not only for the oil and gas industry and, in general, fuel and energy industries , but also to virtually all contemporary industries and technologies. The volume will be useful to specialists and experts in the field of diagnostics/ inspection, monitoring, reliability and safety of critical infrastructures. First and foremost, it will be useful to the decision making persons —operators of different types of pipelines, pipeline diagnostics/inspection vendors, and designers of in-line –inspection (ILI) tools, industrial and ecological safety specialists, as well as to researchers and graduate students.

  1. Hazard identification studies applied to oil pipelines

    Energy Technology Data Exchange (ETDEWEB)

    Savio, Augusto; Alpert, Melina L. [TECNA S.A., Buenos Aires (Argentina)], e-mail: asavio@tecna.com, e-mail: malpert@tecna.com

    2008-07-01

    In order to assess risks inherent to an Oil Pipeline, it is imperative to analyze what happens 'outside the process'. HAZID (HAZard IDentification) studies are mainly carried out for this purpose. HAZID is a formal study which identifies hazards and risks associated to an operation or facility and enable its acceptability assessment. It is a brainstorming exercise guided by a typical 'Checklist', divided into four Sections: External, Facilities and Health Hazards and Issues pertaining to Project Execution, which are further subdivided into Hazard Categories. For each Category, there are 'Guide-words' and 'Prompts'. Even if an Oil Pipeline Risk Assessment can be performed by means of the above referred 'Checklist', carrying out the actual process can become lengthy and annoying due to the lack of specificity. This work aims at presenting the most suitable 'Checklist' for the identification of Oil Pipeline Risk Assessment, although it could be used for Gas Pipeline Risk Assessment too. Prepared ad hoc, this list, is based on the spill causes established by CONCAWE (CONservation of Clean Air Water in Europe). Performing Oil Pipeline Risk Assessment by means of specially formulated Checklist enables the Study Team to easily identify risks, shortens execution time and provides both accuracy and specificity. (author)

  2. Pipesworld : applying planning systems to pipeline transportation

    Energy Technology Data Exchange (ETDEWEB)

    Milidiu, R.L.; Santos Liporace, F. [Pontificia Univ. Catolica, Rio de Janeiro (Brazil). Dept. de Informatica

    2004-07-01

    This paper explored issues facing the complex task of managing pipelines that transport large volumes of petroleum products over long distances. Since oil pipelines are generally a few inches wide and several miles long, reasonable amounts of distinct products can be transported with very small loss due to the mixing at liquid boundaries. Optimizing the transportation through oil pipelines in terms of maintenance and environmental safety is a high priority for pipeline operators. This paper presented the Pipesworld model which takes into account features such as product interface constraints, limited product storage capacities and due dates for product delivery. It has been benchmarked as a start-of-art general purpose artificial planning system. This paper also reported the results derived by general purpose artificial intelligence planning systems when applied to the Pipesworld model. It demonstrated how various modelling techniques can be used to enhance the planners performance. Current work in developing Plumber was also presented. This dedicated solver that addresses operational situations uses both general purpose planning techniques as well as domain specific knowledge. When Plumber was incorporated into Pipesworld, its outperformed Fast-Forward, one of the best available general purpose planning systems, suggesting that improved versions of Plumber have the potential to deal with various problem scenarios in pipeline operations. 11 refs., 2 tabs., 3 figs.

  3. Strategies for the optimization of cathodic protection of pipelines under AC influence; Strategien fuer die Optimierung des kathodischen Korrosionsschutzes von Rohrleitungen unter Wechselspannungsbeeinflussung

    Energy Technology Data Exchange (ETDEWEB)

    Buechler, Markus [SGK Schweizerische Gesellschaft fuer Korrosionsschutz, Zuerich (Switzerland)

    2012-07-01

    The newly determined values for the protection of cathodically protected pipelines against AC corrosion cannot be readily applied to all pipelines. From this perspective, the author of the contribution under consideration reports on strategies for the optimization of cathodic protection of pipelines under AC influence. It is hardly possible to define general strategies. Rather, an examination of the entire pipeline is essential. Is a compliance with the prescribed limits not possible or only possible with unreasonable effort, an active cathodic corrosion protection in combination with remote-controlled monitoring and protection devices can reduce the current corrosion risk.

  4. Stress analysis and mitigation measures for floating pipeline

    Science.gov (United States)

    Wenpeng, Guo; Yuqing, Liu; Chao, Li

    2017-03-01

    Pipeline-floating is a kind of accident with contingency and uncertainty associated to natural gas pipeline occurring during rainy season, which is significantly harmful to the safety of pipeline. Treatment measures against pipeline floating accident are summarized in this paper on the basis of practical project cases. Stress states of pipeline upon floating are analyzed by means of Finite Element Calculation method. The effectiveness of prevention ways and subsequent mitigation measures upon pipeline-floating are verified for giving guidance to the mitigation of such accidents.

  5. Appraisal of the biocide activity of products for the control of microorganisms associated with corrosive processes in the Bacia de Campos pipelines; Avaliacao da acao biocida de produtos para o controle de microrganismos associados a processos corrosivos em oledutos da Bacia de Campos

    Energy Technology Data Exchange (ETDEWEB)

    Penna, Monica de Oliveira [PETROBRAS, Rio de Janeiro, RJ (Brazil). Centro de Pesquisas. Setor de Biotecnologia e Ecossistemas]. E-mail: mpena@cenpes.petrobras.com.br; Andrade, Cynthia de Azevedo [PETROBRAS, Rio de Janeiro, RJ (Brazil). Centro de Pesquisas. Setor de Tecnologia de Materiais, Equipamentos e Corrosao]. E-mail: cynthiaandrade@cenpes.petrobras.com.br; Nascimento, Juliana Rangel do; Silva, Edilson Domingos da; Souza, Leonardo Suhett de [Fundacao GORCEIX, Ouro Preto, MG (Brazil)]. E-mail: julianarn@cenpes.petrobras.com.br; edilson@cenpes.petrobras.com.br; suhett@cenpes.petrobras.com.br

    2001-12-01

    The possible effect of corrosion inhibitors on bacteria has significant interest for the oil and gas industry since, in addition to presenting lower operational costs than biocides due to the low concentrations used, they allow a simultaneous activity on the inhibition of corrosion and adhesion of sulfate reducing-bacteria. In the case of pipes with low BSW oil fluid low, the benefit of using corrosion inhibitors in microorganism combat is even more significant in view of their dispersing characteristics during the oil phase. Herein presented are the laboratorial analysis results of the biocidal effects of six commercial products, four of which having corrosion inhibition function and two with biocidal quality. During this analysis, an oil sample collected from a Petrobras pipeline and a mixed culture of sulfate-reducing mesophilic bacteria (m-BRS) obtained from this sample were used. The study was divided in two phases: the first phase performed in semi-static conditions and, the second phase performed in dynamic conditions (loop). Compositions were analyzed according to their activities regarding the growth control of sulfate-reducing planktonic bacteria, according to their time reducing performance regarding microbial growth (activity) detection and regarding sessile bacteria (pre-adhered bacteria). Results showed that the two biocidal products had the best performance in the presence of oil and that the tetra kishidroximethyl phosphonium sulfate (THPS) at 75% was the most effective. Of the four corrosion inhibitors tested for efficiency regarding BRS growth in solution, three were slightly stimulating and the fourth was intensely stimulating. (author)

  6. Automation of the second iron ore slurry pipeline from Samarco

    Energy Technology Data Exchange (ETDEWEB)

    Aguilar, Juliana M.; Fonseca, Mario L.; Drumond, Pablo P.; Barbosa, Sylvio [IHM Engenharia, Belo Horizonte, MG (Brazil)

    2009-07-01

    The second iron ore slurry pipeline from Samarco was build to attend the Third Pellet Plant Project, which includes a new Concentration Plant at Germano-MG and a third Pellet Plant at Ubu-ES. It has 396km of extension and links the two plants by pulping the iron ore slurry prepared at Germano Unit. This works aims to present the iron ore slurry pipeline with emphasis on the automation architecture for the supervision and control system, interconnect throughout the pipe extension by fiber optics. The control system is composed of ControlLogix CLP's at the pulping and valve station and Micrologix CLP's at the pressure and cathodic protection monitoring points, totalizing 19 PLC's. The supervisory system was developed using the Wonderware IAS 3.0 suite, including the supervisory software InTouch 9.5 and the integrated ArchestrA IDE, and is composed of two data servers in redundancy and nine operation stations. The control and supervision system is interconnect through and Ethernet network using fiber optics and multiplexer modules (GE JungleMux) for voice, data and video. Among the expected results, it can be highlighted the sequence automation, greater process data availability (real and historical) and greater facility for the operation and detection of failures. (author)

  7. Commissioning of long subsea pipelines - environmental aspects

    International Nuclear Information System (INIS)

    Falck, C.; Kleppe, T.; Maribu, J.

    1997-01-01

    Discharges to air and sea are inevitable during precommissioning and commissioning of long subsea pipelines. Large quantities of water is pumped through the pipeline during these operations. This water is normally treated with corrosion inhibiting chemicals to minimise internal corrosion of the pipeline. Chemicals like methanol or glycol may be used to prevent hydrate formation, and will normally be discharged to sea during commissioning. In order to minimise the environmental impact of these operations, while maintaining corrosion protection, the Norwegian Statoil has been working for several years along three main routes such as to develop concepts and methods that minimise the discharged volumes, the use of the most environmentally friendly chemicals available, and to monitor and identify the effects of discharges to various marine species. 3 refs., 4 figs

  8. Digitally assisted pipeline ADCs theory and implementation

    CERN Document Server

    Murmann, Boris

    2007-01-01

    List of Figures. List of Tables. Acknowledgements. Preface. 1: Introduction. 1. Motivation. 2. Overview. 3. Chapter Organization. 2: Performance Trends. 1. Introduction. 2. Digital Performance Trends. 3. ADC Performance Trends. 3: Scaling Analysis. 1. Introduction. 2. Basic Device Scaling from a Digital Perspective. 3. Technology Metrics for Analog Circuits. 4. Scaling Impact on Matching-Limited Circuits. 5. Scaling Impact on Noise-Limited Circuits. 4: Improving Analog Circuit Efficiency. 1. Introduction. 2. Analog Circuit Challenges. 3. The Cost of Feedback. 4. Two-Stage Feedback Amplifier vs. Open-Loop Gain Stage. 5. Discussion. 5: Open-Loop Pipelined ADCs. 1. A Brief Review of Pipelined ADCs. 2. Conventional Stage Implementation. 3. Open-Loop Pipeline Stages. 4. Alternative Transconductor Implementations. 6: Digital Nonlinearity Correction. 1. Overview. 2. Error Model and Digital Correction. 3. Alternative Error Models. 7: Statistics-Based Parameter Estimation. 1. Introduction. 2. Modulation Approach. 3. R...

  9. Design Against Propagating Shear Failure in Pipelines

    Science.gov (United States)

    Leis, B. N.; Gray, J. Malcolm

    Propagating shear failure can occur in gas and certain hazardous liquid transmission pipelines, potentially leading to a large long-burning fire and/or widespread pollution, depending on the transported product. Such consequences require that the design of the pipeline and specification of the steel effectively preclude the chance of propagating shear failure. Because the phenomenology of such failures is complex, design against such occurrences historically has relied on full-scale demonstration experiments coupled with empirically calibrated analytical models. However, as economic drivers have pushed toward larger diameter higher pressure pipelines made of tough higher-strength grades, the design basis to ensure arrest has been severely compromised. Accordingly, for applications where the design basis becomes less certain, as has occurred increasing as steel grade and toughness has increased, it has become necessary to place greater reliance on the use and role of full-scale testing.

  10. The LCOGT Science Archive and Data Pipeline

    Science.gov (United States)

    Lister, Tim; Walker, Z.; Ciardi, D.; Gelino, C. R.; Good, J.; Laity, A.; Swain, M.

    2013-01-01

    Las Cumbres Observatory Global Telescope (LCOGT) is building and deploying a world-wide network of optical telescopes dedicated to time-domain astronomy. In the past year, we have deployed and commissioned four new 1m telescopes at McDonald Observatory, Texas and at CTIO, Chile, with more to come at SAAO, South Africa and Siding Spring Observatory, Australia. To handle these new data sources coming from the growing LCOGT network, and to serve them to end users, we have constructed a new data pipeline and Science Archive. We describe the new LCOGT pipeline, currently under development and testing, which makes use of the ORAC-DR automated recipe-based data reduction pipeline and illustrate some of the new data products. We also present the new Science Archive, which is being developed in partnership with the Infrared Processing and Analysis Center (IPAC) and show some of the new features the Science Archive provides.

  11. Engineering critical assessment of PETROBRAS Camarupim pipeline

    Energy Technology Data Exchange (ETDEWEB)

    Gordon, J.R. [Microalloying International, Houston, TX (United States); Gatlin, R.W. [Global Industries, Rio de Janeiro, RJ (Brazil); Zumpano Junior, P.; Kaspary, T. [PETROBRAS S.A., Rio de Janeiro, RJ (Brazil)

    2009-12-19

    This paper presents details of an Engineering Critical Assessment (ECA) performed to develop girth weld flaw acceptance criteria for the PETROBRAS Camarupim Pipeline which was installed in Espirito Santo Basin, ES, offshore Brazil in May 2008 by Global Industries. The pipeline was constructed using 24-inch diameter API Grade X65 pipe with wall thicknesses of 0.875-inch (22.2 mm) and 1.00 inch (25.4 mm). Although the Camarupim pipeline will initially transport sweet gas there is the potential for mildly sour service operation in mid to late life. To assess the effect of sour service on the material toughness properties a series of slow strain rate fracture toughness tests were performed in a Project representative sour service environment. In addition the results of sour service fatigue crack growth tests were analyzed to develop a conservative sour service fatigue crack growth law for the ECA analysis. (author)

  12. The SWAT approach for pipeline watercourse crossings

    Energy Technology Data Exchange (ETDEWEB)

    Jasper, Steve [WorleyParsons Calgary, Pipeline Systems Business Unit, Calgary, AB (Canada)], email: steve.jasper@worleyparsons.com; Harris, Jason D. [Triton Environmental Consultants Ltd., Terrace, British Columbia (Canada)], email: jharris@triton-env.com; Doering, Raymond [Enbridge Northern Gateway Pipelines, Calgary, AB (Canada)], email: raymond.doering@enbridge.com

    2010-07-01

    In a pipeline project, watercourse crossings are an important environmental and technical challenge. In identifying the best crossing location and method, many factors must be taken into account such as fish habitat, access, geotechnical and hydrological issues. The aim of this paper is to present a program used in a major pipeline project to assess crossings of sensitive watercourses. This program was implemented in the Enbridge Northern Gateway project which extends from Bruderheim, Alberta, to Kitimat, British Columbia, crossing over 750 watercourses. A sensitive watercourse assessment (SWAT) team composed of a fisheries biologist, a pipeline watercourse construction specialist and other personnel carried out assessments on the 200 sensitive watercourses identified. This program led to recommendations to shift the crossing location at 40% of the sensitive sites. This project showed that setting up a SWAT team be helpful in choosing the best location, method and construction timing for a crossing.

  13. The Dark Energy Survey Image Processing Pipeline

    Energy Technology Data Exchange (ETDEWEB)

    Morganson, E.; et al.

    2018-01-09

    The Dark Energy Survey (DES) is a five-year optical imaging campaign with the goal of understanding the origin of cosmic acceleration. DES performs a 5000 square degree survey of the southern sky in five optical bands (g,r,i,z,Y) to a depth of ~24th magnitude. Contemporaneously, DES performs a deep, time-domain survey in four optical bands (g,r,i,z) over 27 square degrees. DES exposures are processed nightly with an evolving data reduction pipeline and evaluated for image quality to determine if they need to be retaken. Difference imaging and transient source detection are also performed in the time domain component nightly. On a bi-annual basis, DES exposures are reprocessed with a refined pipeline and coadded to maximize imaging depth. Here we describe the DES image processing pipeline in support of DES science, as a reference for users of archival DES data, and as a guide for future astronomical surveys.

  14. [Comparison of gut microbiotal compositional analysis of patients with irritable bowel syndrome through different bioinformatics pipelines].

    Science.gov (United States)

    Zhu, S W; Liu, Z J; Li, M; Zhu, H Q; Duan, L P

    2018-04-18

    To assess whether the same biological conclusion, diagnostic or curative effects regarding microbial composition of irritable bowel syndrome (IBS) patients could be reached through different bioinformatics pipelines, we used two common bioinformatics pipelines (Uparse V2.0 and Mothur V1.39.5)to analyze the same fecal microbial 16S rRNA high-throughput sequencing data. The two pipelines were used to analyze the diversity and richness of fecal microbial 16S rRNA high-throughput sequencing data of 27 samples, including 9 healthy controls (HC group), 9 diarrhea IBS patients before (IBS group) and after Rifaximin treatment (IBS-treatment, IBSt group). Analyses such as microbial diversity, principal co-ordinates analysis (PCoA), nonmetric multidimensional scaling (NMDS) and linear discriminant analysis effect size (LEfSe) were used to find out the microbial differences among HC group vs. IBS group and IBS group vs. IBSt group. (1) Microbial composition comparison of the 27 samples in the two pipelines showed significant variations at both family and genera levels while no significant variations at phylum level; (2) There was no significant difference in the comparison of HC vs. IBS or IBS vs. IBSt (Uparse: HC vs. IBS, F=0.98, P=0.445; IBS vs. IBSt, F=0.47,P=0.926; Mothur: HC vs.IBS, F=0.82, P=0.646; IBS vs. IBSt, F=0.37, P=0.961). The Shannon index was significantly decreased in IBSt; (3) Both workshops distinguished the significantly enriched genera between HC and IBS groups. For example, Nitrosomonas and Paraprevotella increased while Pseudoalteromonadaceae and Anaerotruncus decreased in HC group through Uparse pipeline, nevertheless Roseburia 62 increased while Butyricicoccus and Moraxellaceae decreased in HC group through Mothur pipeline.Only Uparse pipeline could pick out significant genera between IBS and IBSt, such as Pseudobutyricibrio, Clostridiaceae 1 and Clostridiumsensustricto 1. There were taxonomic and phylogenetic diversity differences between the two

  15. Applications of the pipeline environment for visual informatics and genomics computations

    Directory of Open Access Journals (Sweden)

    Genco Alex

    2011-07-01

    Full Text Available Abstract Background Contemporary informatics and genomics research require efficient, flexible and robust management of large heterogeneous data, advanced computational tools, powerful visualization, reliable hardware infrastructure, interoperability of computational resources, and detailed data and analysis-protocol provenance. The Pipeline is a client-server distributed computational environment that facilitates the visual graphical construction, execution, monitoring, validation and dissemination of advanced data analysis protocols. Results This paper reports on the applications of the LONI Pipeline environment to address two informatics challenges - graphical management of diverse genomics tools, and the interoperability of informatics software. Specifically, this manuscript presents the concrete details of deploying general informatics suites and individual software tools to new hardware infrastructures, the design, validation and execution of new visual analysis protocols via the Pipeline graphical interface, and integration of diverse informatics tools via the Pipeline eXtensible Markup Language syntax. We demonstrate each of these processes using several established informatics packages (e.g., miBLAST, EMBOSS, mrFAST, GWASS, MAQ, SAMtools, Bowtie for basic local sequence alignment and search, molecular biology data analysis, and genome-wide association studies. These examples demonstrate the power of the Pipeline graphical workflow environment to enable integration of bioinformatics resources which provide a well-defined syntax for dynamic specification of the input/output parameters and the run-time execution controls. Conclusions The LONI Pipeline environment http://pipeline.loni.ucla.edu provides a flexible graphical infrastructure for efficient biomedical computing and distributed informatics research. The interactive Pipeline resource manager enables the utilization and interoperability of diverse types of informatics resources. The

  16. Corral framework: Trustworthy and fully functional data intensive parallel astronomical pipelines

    Science.gov (United States)

    Cabral, J. B.; Sánchez, B.; Beroiz, M.; Domínguez, M.; Lares, M.; Gurovich, S.; Granitto, P.

    2017-07-01

    Data processing pipelines represent an important slice of the astronomical software library that include chains of processes that transform raw data into valuable information via data reduction and analysis. In this work we present Corral, a Python framework for astronomical pipeline generation. Corral features a Model-View-Controller design pattern on top of an SQL Relational Database capable of handling: custom data models; processing stages; and communication alerts, and also provides automatic quality and structural metrics based on unit testing. The Model-View-Controller provides concept separation between the user logic and the data models, delivering at the same time multi-processing and distributed computing capabilities. Corral represents an improvement over commonly found data processing pipelines in astronomysince the design pattern eases the programmer from dealing with processing flow and parallelization issues, allowing them to focus on the specific algorithms needed for the successive data transformations and at the same time provides a broad measure of quality over the created pipeline. Corral and working examples of pipelines that use it are available to the community at https://github.com/toros-astro.

  17. Dynamics stresses in pipelines and components

    International Nuclear Information System (INIS)

    Prates, C.L.M.; Stukart, R.N.L.; Halbritter, A.L.

    1982-01-01

    The procedure to generate the dynamic stresses caused by external events, necessary for the structural calculation of pipelines and components in nuclear power plants is presented. A special attention is given to the stress caused by the action of earthquakes and exterior explosions. In the dynamic analysis of pipeline and components is usually to show the stresses procedured by these events under the response spectra form. The methodology to obtain these response spectra is shown and discussed. Some pratical examples of spectra from nuclear power plant building are still shown. (E.G.) [pt

  18. Preventing erosion at pipeline crossings of watercourses

    International Nuclear Information System (INIS)

    Sawatsky, L.; Arnold, G.

    1997-01-01

    Watercourses are naturally vulnerable to erosion but the risk is particularly acute after sub-soil and armour materials have been disturbed by trenching and backfilling during construction. Various types of erosion (river scour, river bed, river channel bed and river bank ) and the progressive removal of pipeline cover resulting from erosion were discussed. Methods of estimating the risk of progressive erosion, river avulsions and beaver dam scour, and methods of mitigating erosion at pipeline crossings such as deep burial, proper siting, conventional armouring, and a combination of bank toe protection, and upper bank vegetation cover, were described

  19. Vulnerability maps for Druzba crude oil pipeline

    International Nuclear Information System (INIS)

    Hladik, P.; Hosnedl, P.; Buresova, H.; Corbet, J.

    2012-01-01

    Maps of risk for individual environmental aspects within the protection zone of the Czech part of the Druzba crude oil pipeline (505.7 km) were developed based on a modified 'H and V index' method. Risk data were added into a GIS of the Druzba pipeline so that the system could be used as conceptual material in the field of environmental protection (a base for the new SCADA system). Considered environmental aspects were assessed in terms of their vulnerability. The criteria were defined as the vulnerability of the aquatic environment (surface waters and ground waters), the vulnerability of soil environment and the vulnerability of biotic components of the environment. (authors)

  20. Analysis of the Komineft Pipeline oil

    Energy Technology Data Exchange (ETDEWEB)

    Lambert, P.; Wang, Z.; Fieldhouse, B.; Jokuty, P.; Bissonnette, M.; Fingas, M. [Whiticar Scientific, Ottawa, ON (Canada); Whiticar, S. [Whiticar Scientific, Ottawa, ON (Canada); Kyle, D.; Landriault, M.; Sigouin, L.; Goldthorp, M.

    1995-12-31

    A detailed summary of the results of a study by Canadian experts acting as members of a United Nations (UN) team at a pipeline oil spill site in Western Siberia was presented. The purpose of the UN visit was to assess existing damage to the environment and to determine potential future hazards. A Komineft Pipeline oil sample was examined and its composition and characteristics were established. The oil characterization included determination of density, viscosity, pour point, interfacial tension, flash point, water content, dispersant effectiveness, sulphur content, evaporative loss, emulsion viscosity, emulsion water content and hydrocarbon group composition. 11 refs., 20 tabs., 17 figs.

  1. Self lubrication of bitumen froth in pipelines

    International Nuclear Information System (INIS)

    Joseph, D.D.

    1997-01-01

    In this paper I will review the main properties of water lubricated pipelines and explain some new features which have emerged from studies of self-lubrication of Syncrudes' bitumen froth. When heavy oils are lubricated with water, the water and oil are continuously injected into a pipeline and the water is stable when in a lubricating sheath around the oil core. In the case of bitumen froth obtained from the Alberta tar sands, the water is dispersed in the bitumen and it is liberated at the wall under shear; water injection is not necessary because the froth is self-lubricating

  2. 77 FR 22387 - Pipeline Safety: Information Collection Activities, Revision to Gas Transmission and Gathering...

    Science.gov (United States)

    2012-04-13

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No. PHMSA-2012-0024] Pipeline Safety: Information Collection Activities, Revision to Gas Transmission and Gathering Pipeline Systems Annual Report, Gas Transmission and Gathering Pipeline Systems Incident Report...

  3. 75 FR 5640 - Pipeline Safety: Implementation of Revised Incident/Accident Report Forms for Distribution...

    Science.gov (United States)

    2010-02-03

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No... Distribution Systems, Gas Transmission and Gathering Systems, and Hazardous Liquid Systems AGENCY: Pipeline and.... SUMMARY: This notice advises owners and operators of gas pipeline facilities and hazardous liquid pipeline...

  4. 75 FR 2926 - Pipeline Safety: Reporting Drug and Alcohol Test Results for Contractors and Multiple Operator...

    Science.gov (United States)

    2010-01-19

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No... Operator Identification Numbers AGENCY: Pipeline and Hazardous Materials Safety Administration (PHMSA), DOT... liquid, and carbon dioxide pipelines and liquefied natural gas facilities that the Pipeline and Hazardous...

  5. 78 FR 65427 - Pipeline Safety: Reminder of Requirements for Liquefied Petroleum Gas and Utility Liquefied...

    Science.gov (United States)

    2013-10-31

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No. PHMSA-2013-0097] Pipeline Safety: Reminder of Requirements for Liquefied Petroleum Gas and Utility Liquefied Petroleum Gas Pipeline Systems AGENCY: Pipeline and Hazardous Materials Safety Administration...

  6. 77 FR 58616 - Pipeline Safety: Information Collection Activities, Revision to Gas Transmission and Gathering...

    Science.gov (United States)

    2012-09-21

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No. PHMSA-2012-0024] Pipeline Safety: Information Collection Activities, Revision to Gas Transmission and Gathering Pipeline Systems Annual Report, Gas Transmission and Gathering Pipeline Systems Incident Report...

  7. 75 FR 58014 - Pipeline Safety: Information Collection Activity; Request for Comments

    Science.gov (United States)

    2010-09-23

    ..., supports pipeline safety by ensuring the proper functioning of CPM leak detection systems. Affected Public...-phase hazardous liquid pipeline facilities that use computational pipeline monitoring (CPM) leak... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No...

  8. 77 FR 20807 - Northwest Pipeline GP; Notice of Application

    Science.gov (United States)

    2012-04-06

    ... diameter pipelines away from an adjacent surface coal mine west of Kemmerer, Wyoming. Northwest also... directed to Pam Barnes, Manager Certificates and Tariffs, Northwest Pipeline GP, 295 Chipeta Way, Salt Lake...

  9. 76 FR 45332 - Pipeline and Hazardous Materials Safety Administration

    Science.gov (United States)

    2011-07-28

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration Office of... Hazardous Materials Safety Administration (PHMSA), DOT. ACTION: List of Applications for Modification of..., 2011. ADDRESSES: Record Center, Pipeline and Hazardous Materials Safety Administration, U.S. Department...

  10. 76 FR 70217 - Pipeline Safety: Information Collection Activities

    Science.gov (United States)

    2011-11-10

    ... combined comment from American Petroleum Institute (API) and American Oil Pipelines Association (AOPL) on... some rural low-stress hazardous liquid pipelines are not subject to part 195 although they are required...

  11. Software for natural gas pipeline design and simulation (gaspisim ...

    African Journals Online (AJOL)

    Software for natural gas pipeline design and simulation (gaspisim) ... This paper focuses on the development of software for optimum design and simulation of natural gas pipeline. General ... EMAIL FREE FULL TEXT EMAIL FREE FULL TEXT

  12. Diagnosing plant pipeline system performance using radiotracer techniques

    Energy Technology Data Exchange (ETDEWEB)

    Kasban, H.; Ali, Elsayed H.; Arafa, H. [Engineering Department, Nuclear Research Center, Atomic Energy Authority, Inshas (Egypt)

    2017-02-15

    This study presents an experimental work in a petrochemical company for scanning a buried pipeline using Tc{sup 99m} radiotracer based on the measured velocity changes, in order to determine the flow reduction along a pipeline. In this work, Tc{sup 99m} radiotracer was injected into the pipeline and monitored by sodium iodide scintillation detectors located at several positions along the pipeline. The flow velocity has been calculated between every two consecutive detectors along the pipeline. Practically, six experiments have been carried out using two different data acquisition systems, each of them being connected to four detectors. During the fifth experiment, a bypass was discovered between the scanned pipeline and another buried parallel pipeline connected after the injection point. The results indicate that the bypass had a bad effect on the volumetric flow rate in the scanned pipeline.

  13. Investigation of Corrosion of Buried Oil Pipeline by the Electrical ...

    African Journals Online (AJOL)

    MICHAEL

    ABSTRACT: The delineation of possible areas of corrosion along an underground oil pipeline in Ubeji, ... prevention of pipeline failure with its attendant environmental, human and economic consequences. @ JASEM .... Cathodic protection as.

  14. Distributed acoustic sensing for pipeline monitoring

    Energy Technology Data Exchange (ETDEWEB)

    Hill, David; McEwen-King, Magnus [OptaSense, QinetiQ Ltd., London (United Kingdom)

    2009-07-01

    Optical fibre is deployed widely across the oil and gas industry. As well as being deployed regularly to provide high bandwidth telecommunications and infrastructure for SCADA it is increasingly being used to sense pressure, temperature and strain along buried pipelines, on subsea pipelines and downhole. In this paper we present results from the latest sensing capability using standard optical fibre to detect acoustic signals along the entire length of a pipeline. In Distributed Acoustic Sensing (DAS) an optical fibre is used for both sensing and telemetry. In this paper we present results from the OptaSense{sup TM} system which has been used to detect third party intervention (TPI) along buried pipelines. In a typical deployment the system is connected to an existing standard single-mode fibre, up to 50km in length, and was used to independently listen to the acoustic / seismic activity at every 10 meter interval. We will show that through the use of advanced array processing of the independent, simultaneously sampled channels it is possible to detect and locate activity within the vicinity of the pipeline and through sophisticated acoustic signal processing to obtain the acoustic signature to classify the type of activity. By combining spare fibre capacity in existing buried fibre optic cables; processing and display techniques commonly found in sonar; and state-of-the-art in fibre-optic distributed acoustic sensing, we will describe the new monitoring capabilities that are available to the pipeline operator. Without the expense of retrofitting sensors to the pipeline, this technology can provide a high performance, rapidly deployable and cost effective method of providing gapless and persistent monitoring of a pipeline. We will show how this approach can be used to detect, classify and locate activity such as; third party interference (including activity indicative of illegal hot tapping); real time tracking of pigs; and leak detection. We will also show how an

  15. Evaluation of stream crossing methods prior to gas pipeline construction

    International Nuclear Information System (INIS)

    Murphy, M.H.; Rogers, J.S.; Ricca, A.

    1995-01-01

    Stream surveys are conducted along proposed gas pipeline routes prior to construction to assess potential impacts to stream ecosystems and to recommend preferred crossing methods. Recently, there has been a high level of scrutiny from the Public Service Commission (PSC) to conduct these stream crossings with minimal effects to the aquatic community. PSC's main concern is the effect of sediment on aquatic biota. Smaller, low flowing or intermittent streams are generally crossed using a wet crossing technique. This technique involves digging a trench for the pipeline while the stream is flowing. Sediment control measures are used to reduce sediment loads downstream. Wider, faster flowing, or protected streams are typically crossed with a dry crossing technique. A dry crossing involves placing a barrier upstream of the crossing and diverting the water around the crossing location. The pipeline trench is then dug in the dry area. O'Brien and Gere and NYSEG have jointly designed a modified wet crossing for crossing streams that exceed maximum flows for a dry crossing, and are too wide for a typical wet crossing. This method diverts water around the crossing using a pumping system, instead of constructing a dam. The trench is similar to a wet crossing, with sediment control devices in place upstream and downstream. If streams are crossed during low flow periods, the pumping system will be able to reduce the majority of water flow and volume form the crossing area, thereby reducing ecological impacts. Evaluation of effects of this crossing type on the stream biota are currently proposed and may proceed when construction begins

  16. Genome Assembly and Computational Analysis Pipelines for Bacterial Pathogens

    KAUST Repository

    Rangkuti, Farania Gama Ardhina

    2011-06-01

    Pathogens lie behind the deadliest pandemics in history. To date, AIDS pandemic has resulted in more than 25 million fatal cases, while tuberculosis and malaria annually claim more than 2 million lives. Comparative genomic analyses are needed to gain insights into the molecular mechanisms of pathogens, but the abundance of biological data dictates that such studies cannot be performed without the assistance of computational approaches. This explains the significant need for computational pipelines for genome assembly and analyses. The aim of this research is to develop such pipelines. This work utilizes various bioinformatics approaches to analyze the high-­throughput genomic sequence data that has been obtained from several strains of bacterial pathogens. A pipeline has been compiled for quality control for sequencing and assembly, and several protocols have been developed to detect contaminations. Visualization has been generated of genomic data in various formats, in addition to alignment, homology detection and sequence variant detection. We have also implemented a metaheuristic algorithm that significantly improves bacterial genome assemblies compared to other known methods. Experiments on Mycobacterium tuberculosis H37Rv data showed that our method resulted in improvement of N50 value of up to 9697% while consistently maintaining high accuracy, covering around 98% of the published reference genome. Other improvement efforts were also implemented, consisting of iterative local assemblies and iterative correction of contiguated bases. Our result expedites the genomic analysis of virulent genes up to single base pair resolution. It is also applicable to virtually every pathogenic microorganism, propelling further research in the control of and protection from pathogen-­associated diseases.

  17. Risk and integrity management system for PETRONAS Gas Berhad's gas and liquid hydrocarbon pipelines

    Energy Technology Data Exchange (ETDEWEB)

    Khalid, Tuan Hj. Ahmad Nadzri bin; Nasir, Osman; Napiah, Mohd Nazmi Mohd Ali [PETRONAS Gas Berhad, Johor (Malaysia); Choong, Evelyn

    2005-07-01

    PETRONAS Gas Berhad (PGB), Malaysia currently operates one of Southeast Asia's largest onshore pipeline systems comprising more than 2,500 km of large diameter high pressure gas and liquid transmission, supply and lateral pipelines. Recognizing the value of a risk based approach to pipeline integrity management program, in 2002 PGB implemented a customized and fully integrated Risk and Integrity Management System (RIMS) which included software modules for: data management; semi-quantitative risk assessment; risk control cost benefit analyses; defect assessment; corrosion growth modeling; and reporting. As part of this project, a benchmarking study performed jointly with the contractor, PGB's pipeline integrity programs were also compared with a broad group of international pipeline operators. This study compared the relative ranking position of PGB pre- and post implementation of RIMS. It demonstrated that implementation of RIMS places PGB in a select group of first quartile international pipeline operators, with respect to the implementation of pipeline integrity management best practice. This paper describes the functionalities of RIMS system and how it has benefited PGB, which have been realized to date from its implementation. (author)

  18. Repair methods for damaged pipeline beyond diving depth

    OpenAIRE

    Mohammadi, Keramat

    2011-01-01

    Master's thesis in Offshore Technology Mechanical damage of a subsea pipeline is found as one of the most severe concern in management of pipeline integrity. The need to reach and bring the hydrocarbons from the fields located in deep and ultra-deep waters, imposes the need to improve the technologies and techniques in order to repair any unacceptable damage in pipeline. The main objective of this work is to investigate various methods for repairing a subsea pipeline that has been damaged ...

  19. FUZZY INFERENCE BASED LEAK ESTIMATION IN WATER PIPELINES SYSTEM

    OpenAIRE

    N. Lavanya; G. Anand; S. Srinivasan

    2015-01-01

    Pipeline networks are the most widely used mode for transporting fluids and gases around the world. Leakage in this pipeline causes harmful effects when the flowing fluid/gas is hazardous. Hence the detection of leak becomes essential to avoid/minimize such undesirable effects. This paper presents the leak detection by spectral analysis methods in a laboratory pipeline system. Transient in the pressure signal in the pipeline is created by opening and closing the exit valve. These pressure var...

  20. ORAC-DR: A generic data reduction pipeline infrastructure

    Science.gov (United States)

    Jenness, Tim; Economou, Frossie

    2015-03-01

    ORAC-DR is a general purpose data reduction pipeline system designed to be instrument and observatory agnostic. The pipeline works with instruments as varied as infrared integral field units, imaging arrays and spectrographs, and sub-millimeter heterodyne arrays and continuum cameras. This paper describes the architecture of the pipeline system and the implementation of the core infrastructure. We finish by discussing the lessons learned since the initial deployment of the pipeline system in the late 1990s.

  1. Multi-Criteria Decision Making Models for Water Pipelines

    OpenAIRE

    El Chanati, Hisham; El-Abbasy, Mohammed S.; Mosleh, Fadi; Senouci, Ahmed; Abouhamad, Mona; Gkountis, Iason; Zayed, Tarek; Al-Derham, Hassan

    2016-01-01

    The deterioration of water pipelines leads to impaired water quality, increased breakage rate, and reduced hydraulic capacity. The planning of maintenance programs for water pipelines is essential to minimize health and safety concerns and ensure an adequate supply of water in a safe, cost-effective, reliable, and sustainable manner. It is essential to assess the performance of water pipelines to assist municipalities in planning inspection and rehabilitation programs for their pipelines. Sev...

  2. 75 FR 45696 - Pipeline Safety: Personal Electronic Device Related Distractions

    Science.gov (United States)

    2010-08-03

    ... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No... and operators of natural gas and hazardous liquid pipeline facilities are required to have and follow.... Advisory Bulletin (ADB-10-06) To: Owners and Operators of Hazardous Liquid and Natural Gas Pipeline Systems...

  3. Examination of faults active motion on buried pipelines | Parish ...

    African Journals Online (AJOL)

    ... lateral spreading, landslides and slope failures. Since the pipelines are widely spread, and in some areas necessarily cross through the areas with faults, therefore, improvement study of pipelines in areas with faults is very important. This article explores faults active motion on buried pipelines. Keywords: water utilities ...

  4. Stress and Strain State Analysis of Defective Pipeline Portion

    Science.gov (United States)

    Burkov, P. V.; Burkova, S. P.; Knaub, S. A.

    2015-09-01

    The paper presents computer simulation results of the pipeline having defects in a welded joint. Autodesk Inventor software is used for simulation of the stress and strain state of the pipeline. Places of the possible failure and stress concentrators are predicted on the defective portion of the pipeline.

  5. Development of a Free-Swimming Acoustic Tool for Liquid Pipeline Leak Detection Including Evaluation for Natural Gas Pipeline Applications

    Science.gov (United States)

    2010-08-01

    Significant financial and environmental consequences often result from line leakage of oil product pipelines. Product can escape into the surrounding soil as even the smallest leak can lead to rupture of the pipeline. From a health perspective, water...

  6. Annual compensation for pipelines in Alberta

    International Nuclear Information System (INIS)

    2008-11-01

    The Surface Rights Board (SRB) in Alberta held a hearing in November 2007 to address three issues involving a pipeline for Enbridge Pipelines (Athabasca) Inc. as well as several land owner issues in Townships 66-68 and Ranges 17-19, all west of the 4th Meridian. The issues the SRB examined were the appropriate amount (i.e. magnitude) of compensation payable under right of entry orders under consideration; the appropriate structure of the compensation award; and to whom the compensation was payable. This document presented a review by the Farmer's Advocate Office (FAO) of the published decision of the SRB. The verbatim decision and rationale used by the SRB to award annual compensation for loss and/or ongoing nuisance and inconvenience was presented. The document could be useful to landowners as they determine their negotiation strategy when faced with considering future pipeline access agreements. The document included a discussion of the context for the decision and a case review. Specific topics that were covered included the rationale for the decision; long term effects of pipeline arguments and SRB commentary; the award and determination; and what still needs to be done. It was concluded that the SRB requires evidence in order to answer several questions regarding the magnitude of any losses, and to what degree, if any, had the nuisance, inconvenience, and loss of rights already been anticipated and factored into the operator's final offer

  7. The First Steps into a "Leaky Pipeline"

    DEFF Research Database (Denmark)

    Emerek, Ruth; Larsen, Britt Østergaard

    2011-01-01

    Research shows that the higher the level of academic positions at universities the lower the percentage of women among employees also applies at Danish universities. This may be due to a historical backlog or merely to a 'Leaky pipeline', as earlier studies have revealed that an increasing propor...

  8. Pipeline or Personal Preference: Women in Engineering

    Science.gov (United States)

    Schreuders, P. D.; Mannon, S. E.; Rutherford, B.

    2009-01-01

    Although the number of women in the engineering field has increased since the 1960s, those increases have largely stagnated over the last few years. This paper re-examines the pipeline for bringing women into engineering and, based on survey data, examines the attitudes, motivations, and interests of 969 male and female engineering students.…

  9. Women Engineering Faculty: Expanding the Pipeline

    Science.gov (United States)

    Greni, Nadene Deiterman

    2006-01-01

    The purpose for this case study was to explore the features of undergraduate engineering departmental and college support that influenced the persistence of women students. Women engineering faculty members were among the participants at three Land Grant universities in the Midwest. The data revealed the theme, Expanding the Pipeline, and…

  10. Optimal Processor Assignment for Pipeline Computations

    Science.gov (United States)

    1991-10-01

    the use of ratios: initially each task is assigned a procesbuor2 the remaining proceborb are distributed in proportion to the quantities f,(1), 1 < i...algorithmns. IEEE Trans. onl Parallel and Distributed Systemns, 1 (4):470-499, October 1990. [26] P. Al. Kogge. The Architeture of Pipelined Comnputers

  11. Pipeline : Hebrew data from ETCBC to Github

    NARCIS (Netherlands)

    Roorda, Dirk

    2017-01-01

    This pipeline delivers, among other good things, a file bhsa_xx.mql.bz2 which contains all ETCBC data and research additions to it. The form is MQL, compressed, and the size is less than 30 MB. Where ever you have Emdros installed, you can query this data. If you take this file from the continuous

  12. Vibrations in pipelines of nuclear power plants

    International Nuclear Information System (INIS)

    Leal, M.R.L.V.; Bevilacqua, L.

    1984-01-01

    It is presented the main causes of vibrations in nuclear power plants pipelines to allow the identification of critical areas and correct the errors during the specification design. The methods of vibration analysis to give subsidies in the determination of the corrective providences when the problem appears during the commissioning or the generation energy, are also presented. (M.C.K.) [pt

  13. Underwater Adhesives Retrofit Pipelines with Advanced Sensors

    Science.gov (United States)

    2015-01-01

    Houston-based Astro Technology Inc. used a partnership with Johnson Space Center to pioneer an advanced fiber-optic monitoring system for offshore oil pipelines. The company's underwater adhesives allow it to retrofit older deepwater systems in order to measure pressure, temperature, strain, and flow properties, giving energy companies crucial data in real time and significantly decreasing the risk of a catastrophe.

  14. Halifax Lateral Pipeline Project : comprehensive study report

    International Nuclear Information System (INIS)

    1998-12-01

    The National Energy Board has requested the preparation of a comprehensive study report (CSR) for the proposed Halifax Lateral Pipeline Project in support of Maritimes and Northeast Pipeline Company's proposal to construct the lateral pipeline to transport natural gas produced in offshore Nova Scotia to the Tufts Cove electric generating station in the Halifax Regional Municipality. The project will also enhance the access of natural gas to potential markets located along the pipeline route. This CSR was prepared according to guidelines of the Canadian Environmental Assessment Agency. The report presents: (1) an overview of the project, (2) a summary of the regulatory requirements for assessment, (3) a description of the environmental assessment and regulatory process to date, (4) a summary of the predicted residual environmental and socio-economic effects associated with the project, and (5) a summary of the public consultation process. The environmental and socio-economic assessment focused on these eleven issues: groundwater resources, surface water resources, wetlands, soils, air quality, fish habitat, rare herpetiles, mammals, avifauna, rare plants and archaeological heritage resources. The report identified potential interactions between the project and valued socio-economic and environmental components. These were addressed in combination with recommended mitigative measures to reduce potential adverse effects. It was concluded that the overall environmental effects from the proposed project are likely to be minimal and can be effectively managed with good environmental management methods. 14 refs., 5 tabs., 5 figs., 2 appendices

  15. Internal Corrosion Detection in Liquids Pipelines

    Science.gov (United States)

    2012-01-01

    PHMSA project DTRS56-05-T-0005 "Development of ICDA for Liquid Petroleum Pipelines" led to the development of a Direct Assessment (DA) protocol to prioritize locations of possible internal corrosion. The underlying basis LP-ICDA is simple; corrosion ...

  16. Key Design Properties for Shipping Information Pipeline

    DEFF Research Database (Denmark)

    Jensen, Thomas; Tan, Yao-Hua

    2015-01-01

    on paper, e-mail, phone and text message, and far too costly. This paper explores the design properties for a shared information infrastructure to exchange information between all parties in the supply chain, commercial parties as well as authorities, which is called a Shipping Information Pipeline...

  17. The Effect of Landslide on Gas Pipeline

    Directory of Open Access Journals (Sweden)

    Valkovič Vojtech

    2016-11-01

    Full Text Available The present paper deals with the calculation of stresses on the pipeline system embedded on a flexible substrate which is burdened by a landslide. As well as taking into account the probability of the influences acting on the pipe as wall thickness, and others.

  18. Runtime Modifications of Spark Data Processing Pipelines

    NARCIS (Netherlands)

    Lazovik, E.; Medema, M.; Albers, T.; Langius, E.A.F.; Lazovik, A.

    2017-01-01

    Distributed data processing systems are the standard means for large-scale data analysis in the Big Data field. These systems are based on processing pipelines where the processing is done via a composition of multiple elements or steps. In current distributed data processing systems, the code and

  19. Pipelines cathodic protection design methodologies for impressed ...

    African Journals Online (AJOL)

    Several inadequate designs of cathodically polarized offshore and onshore pipelines have been reported in Nigeria owing to design complexity and application of the cathodic protection system. The present study focused on critical and detailed approach in impressed current and sacrificial anode design calculation ...

  20. The Bakou-Ceyhan pipeline: paradoxes and coherence of the USA strategy of pipelines

    International Nuclear Information System (INIS)

    Jafalian, A.

    2004-01-01

    In 2002, the construction of the Bakou-Ceyhan pipeline, from the Caspian Sea to the Mediterranean Sea, is begun, in spite of the the controversies of industrialists against politicians and experts. The diplomatic USA activity in favor this pipeline largely contributes to the problems solution. The author presents the USA policy and strategy in the region, the economic constraints and the negotiations. (A.L.B.)

  1. Remotely operated closure device for a pipeline with a fixed pipeline flange

    International Nuclear Information System (INIS)

    Westendorf, H.

    1987-01-01

    The remotely operated closure is set by suspension centring on the circumference of a blank flange on the fixed pipeline flange to be closed. By operating a central actuating mechanism at the closure, the clamping levers are adjusted so that the blank flange is clamped to the pipeline flange and the two flanges are pressed together. The spring-loaded clamping levers are particularly suitable for actuating the closure with the pliers of a manipulator of a large cell. (DG) [de

  2. Methodology for environmental audit of execution in gas-pipelines and pipelines

    International Nuclear Information System (INIS)

    Hurtado Palomino, Maria Patricia; Vargas Bejarano, Carlos Hernando

    1999-01-01

    In first instance the constructive aspects and the environmental impact related with the gas-pipes and pipelines construction are presented; then a methodology to make the environmental audit of execution in gas-pipes and pipelines, is showed. They contemplate four stages basically: planning, pre-auditory, execution and analysis, and post-auditory with their respective activities. Also, it is given to know, generalities of the practical case, to evaluate the applicability of the proposed methodology

  3. Stabilité des pipelines non ensouillés. Etude bibliographique Stability of Unburied Pipelines. Bibliographic Study

    OpenAIRE

    Alliot J. M.

    2006-01-01

    The integrity of an unburied subsea pipeline depends to a very large extent on its stability on the seabed along its entire length. Hence the determination of this stability is of great importance in the engineering design of pipelines. This article proposes to examine the principal problems raised by the stability of unburied pipelines in the field of soil mechanics. These problems mainly concern the reactions of the soil to pipelines and their assessment, i. e. the forces of soil resistance...

  4. Risk analysis of urban gas pipeline network based on improved bow-tie model

    Science.gov (United States)

    Hao, M. J.; You, Q. J.; Yue, Z.

    2017-11-01

    Gas pipeline network is a major hazard source in urban areas. In the event of an accident, there could be grave consequences. In order to understand more clearly the causes and consequences of gas pipeline network accidents, and to develop prevention and mitigation measures, the author puts forward the application of improved bow-tie model to analyze risks of urban gas pipeline network. The improved bow-tie model analyzes accident causes from four aspects: human, materials, environment and management; it also analyzes the consequences from four aspects: casualty, property loss, environment and society. Then it quantifies the causes and consequences. Risk identification, risk analysis, risk assessment, risk control, and risk management will be clearly shown in the model figures. Then it can suggest prevention and mitigation measures accordingly to help reduce accident rate of gas pipeline network. The results show that the whole process of an accident can be visually investigated using the bow-tie model. It can also provide reasons for and predict consequences of an unfortunate event. It is of great significance in order to analyze leakage failure of gas pipeline network.

  5. An Automated, Adaptive Framework for Optimizing Preprocessing Pipelines in Task-Based Functional MRI.

    Directory of Open Access Journals (Sweden)

    Nathan W Churchill

    Full Text Available BOLD fMRI is sensitive to blood-oxygenation changes correlated with brain function; however, it is limited by relatively weak signal and significant noise confounds. Many preprocessing algorithms have been developed to control noise and improve signal detection in fMRI. Although the chosen set of preprocessing and analysis steps (the "pipeline" significantly affects signal detection, pipelines are rarely quantitatively validated in the neuroimaging literature, due to complex preprocessing interactions. This paper outlines and validates an adaptive resampling framework for evaluating and optimizing preprocessing choices by optimizing data-driven metrics of task prediction and spatial reproducibility. Compared to standard "fixed" preprocessing pipelines, this optimization approach significantly improves independent validation measures of within-subject test-retest, and between-subject activation overlap, and behavioural prediction accuracy. We demonstrate that preprocessing choices function as implicit model regularizers, and that improvements due to pipeline optimization generalize across a range of simple to complex experimental tasks and analysis models. Results are shown for brief scanning sessions (<3 minutes each, demonstrating that with pipeline optimization, it is possible to obtain reliable results and brain-behaviour correlations in relatively small datasets.

  6. A computational platform for modeling and simulation of pipeline georeferencing systems

    Energy Technology Data Exchange (ETDEWEB)

    Guimaraes, A.G.; Pellanda, P.C.; Gois, J.A. [Instituto Militar de Engenharia (IME), Rio de Janeiro, RJ (Brazil); Roquette, P.; Pinto, M.; Durao, R. [Instituto de Pesquisas da Marinha (IPqM), Rio de Janeiro, RJ (Brazil); Silva, M.S.V.; Martins, W.F.; Camillo, L.M.; Sacsa, R.P.; Madeira, B. [Ministerio de Ciencia e Tecnologia (CT-PETRO2006MCT), Brasilia, DF (Brazil). Financiadora de Estudos e Projetos (FINEP). Plano Nacional de Ciencia e Tecnologia do Setor Petroleo e Gas Natural

    2009-07-01

    This work presents a computational platform for modeling and simulation of pipeline geo referencing systems, which was developed based on typical pipeline characteristics, on the dynamical modeling of Pipeline Inspection Gauge (PIG) and on the analysis and implementation of an inertial navigation algorithm. The software environment of PIG trajectory simulation and navigation allows the user, through a friendly interface, to carry-out evaluation tests of the inertial navigation system under different scenarios. Therefore, it is possible to define the required specifications of the pipeline geo referencing system components, such as: required precision of inertial sensors, characteristics of the navigation auxiliary system (GPS surveyed control points, odometers etc.), pipeline construction information to be considered in order to improve the trajectory estimation precision, and the signal processing techniques more suitable for the treatment of inertial sensors data. The simulation results are analyzed through the evaluation of several performance metrics usually considered in inertial navigation applications, and 2D and 3D plots of trajectory estimation error and of recovered trajectory in the three coordinates are made available to the user. This paper presents the simulation platform and its constituting modules and defines their functional characteristics and interrelationships.(author)

  7. Virtual georeferencing : how an 11-eyed video camera helps the pipeline industry

    Energy Technology Data Exchange (ETDEWEB)

    Ball, C.

    2006-08-15

    Designed by Immersive Media Corporation (IMC) the new Telemmersion System is a lightweight camera system capable of generating synchronized high-resolution video streams that represent a full motion spherical world. With 11 cameras configured in a sphere, the system is portable and can be easily mounted on ground and air-borne vehicles for use in surveillance; integration; commanded control of interactive intelligent databases; scenario modelling; and specialized training. The system was recently used to georeference immersive video of existing and proposed pipeline routes. Footage from the system was used to supplement traditional data collection methods for environmental impact assessment; route selection and engineering; regulatory compliance; and public consultation. Traditionally, the medium used to visualize pipeline routes is a map overlaid with aerial photography. Pipeline routes are typically flown throughout the planning stages in order to give environmentalists, engineers and other personnel the opportunity to visually inspect the terrain, identify issues and make decisions. The technology has significantly reduced the costs during the planning stages of pipeline routes, as the remote footage can be stored on DVD, allowing various stakeholders and contractors to view the terrain and zoom in on particular land features. During one recent 3-day trip, 500 km of proposed pipeline was recorded using the technology. Typically, for various regulatory and environmental requirements, a half a dozen trips would have been required. 2 figs.

  8. Surface electromagnetic technology for the external inspection of oil and gas pipelines

    Energy Technology Data Exchange (ETDEWEB)

    Mousatov, A.; Nakamura, E.; Delgado, O.; Flores, A. [Mexican Petroleum Institute, Mexico City (Mexico); Nakamura, E. [Moscow State University, Moscow (Russian Federation); Shevnin, V. [Moscow State University (Russian Federation)

    2009-07-01

    In this paper we present a surface electromagnetic technology for the non-destructive pipeline coating inspection (SEMPI). This technology allows: determination of the depth and plane position of pipelines, quantitative evaluation of the insulation resistance and delimitation of zones with coating damages, estimation of the performance of the cathodic protection system (CPS) and detection of its connections to out-of-service pipes and other grounded constructions, and assessment of the soil aggressively. The SEMPI technology is based on the approximation of pipelines by heterogeneous transmission lines with variable leakage conductance and pipe impedance to represent insulation coating and wall thickness damages. Based on the result of simulations, we have optimized the field measurements and developed the interpretation procedure of experimental data. The field operations include surface measurements of magnetic field, voltage on the control posts of the CPS and soil resistivity. In zones with coating damages the detailed measurements can be performed using magnetic or electric field to increase the resolution in localizing and evaluating the insulation damages. The SEMPI technology has been applied for inspections of pipelines with different technical characteristics in complicated environmental conditions. The examples presented in this work confirm the high efficiency of the developed technology for external integrity evaluation of pipelines. (author)

  9. Diverless pipeline repair system for deep water

    Energy Technology Data Exchange (ETDEWEB)

    Spinelli, Carlo M. [Eni Gas and Power, Milan (Italy); Fabbri, Sergio; Bachetta, Giuseppe [Saipem/SES, Venice (Italy)

    2009-07-01

    SiRCoS (Sistema Riparazione Condotte Sottomarine) is a diverless pipeline repair system composed of a suite of tools to perform a reliable subsea pipeline repair intervention in deep and ultra deep water which has been on the ground of the long lasting experience of Eni and Saipem in designing, laying and operating deep water pipelines. The key element of SiRCoS is a Connection System comprising two end connectors and a repair spool piece to replace a damaged pipeline section. A Repair Clamp with elastomeric seals is also available for pipe local damages. The Connection System is based on pipe cold forging process, consisting in swaging the pipe inside connectors with suitable profile, by using high pressure seawater. Three swaging operations have to be performed to replace the damaged pipe length. This technology has been developed through extensive theoretical work and laboratory testing, ending in a Type Approval by DNV over pipe sizes ranging from 20 inches to 48 inches OD. A complete SiRCoS system has been realised for the Green Stream pipeline, thoroughly tested in workshop as well as in shallow water and is now ready, in the event of an emergency situation.The key functional requirements for the system are: diverless repair intervention and fully piggability after repair. Eni owns this technology and is now available to other operators under Repair Club arrangement providing stand-by repair services carried out by Saipem Energy Services. The paper gives a description of the main features of the Repair System as well as an insight into the technological developments on pipe cold forging reliability and long term duration evaluation. (author)

  10. Advances in riser and pipeline technologies

    Energy Technology Data Exchange (ETDEWEB)

    Kan, Wan C.; Mortazavi, Mehrdad; Weir, Michael S. [ExxonMobil Development Company, Dallas, TX (United States)

    2009-12-19

    As oil and gas production continues to move into new frontier areas, novel applications of the existing riser and pipeline technologies need to be developed to meet the often more stringent requirements encountered in these environments. The challenges include ultra deep water, harsh environments, aggressive fluid conditions, and local content objectives, etc. They will require industry to constantly extend, expand, and enhance the broad range of solution options. Also, the existing design criteria in industry may need to be revised or new criteria may need to be developed to satisfy these needs. Exxon Mobil (Em) employs, and works with others in industry to promote robust design and operating practices. This approach requires in-depth understanding, sound engineering principles, advanced analysis, uncertainty management, and supportive qualification test data. It enables confident selection, extrapolation, and innovation of technologies to address new riser system and pipeline challenges. Focus on fundamental is imperative to ensure integrity of the selected systems during fabrication, installation, and operation phases. Recent and past project experience in deep water Gulf of Mexico and West Africa provides many successful examples of this approach. This paper reviews several examples of the key riser system and pipeline technology enhancements recently achieved by EM to provide confidence in addressing technical and project application challenges. Riser system technology enhancements addressed in this paper include steel catenary riser (SCR) application on turret-moored FPSO with severe motions, pipe-in-pipe (PIP) hybrid production riser to effectively manage gas lift and flow assurance requirements, irregular wave analysis methodology for flexible risers and umbilicals to reduce conservatism, and qualification of riser and pipeline VIV prediction and mitigation methods. Pipeline technology enhancements detailed in this paper include lateral buckling prediction

  11. Data processing pipeline for Herschel HIFI

    Science.gov (United States)

    Shipman, R. F.; Beaulieu, S. F.; Teyssier, D.; Morris, P.; Rengel, M.; McCoey, C.; Edwards, K.; Kester, D.; Lorenzani, A.; Coeur-Joly, O.; Melchior, M.; Xie, J.; Sanchez, E.; Zaal, P.; Avruch, I.; Borys, C.; Braine, J.; Comito, C.; Delforge, B.; Herpin, F.; Hoac, A.; Kwon, W.; Lord, S. D.; Marston, A.; Mueller, M.; Olberg, M.; Ossenkopf, V.; Puga, E.; Akyilmaz-Yabaci, M.

    2017-12-01

    Context. The HIFI instrument on the Herschel Space Observatory performed over 9100 astronomical observations, almost 900 of which were calibration observations in the course of the nearly four-year Herschel mission. The data from each observation had to be converted from raw telemetry into calibrated products and were included in the Herschel Science Archive. Aims: The HIFI pipeline was designed to provide robust conversion from raw telemetry into calibrated data throughout all phases of the HIFI missions. Pre-launch laboratory testing was supported as were routine mission operations. Methods: A modular software design allowed components to be easily added, removed, amended and/or extended as the understanding of the HIFI data developed during and after mission operations. Results: The HIFI pipeline processed data from all HIFI observing modes within the Herschel automated processing environment as well as within an interactive environment. The same software can be used by the general astronomical community to reprocess any standard HIFI observation. The pipeline also recorded the consistency of processing results and provided automated quality reports. Many pipeline modules were in use since the HIFI pre-launch instrument level testing. Conclusions: Processing in steps facilitated data analysis to discover and address instrument artefacts and uncertainties. The availability of the same pipeline components from pre-launch throughout the mission made for well-understood, tested, and stable processing. A smooth transition from one phase to the next significantly enhanced processing reliability and robustness. Herschel was an ESA space observatory with science instruments provided by European-led Principal Investigator consortia and with important participation from NASA.

  12. PLUGGING AND UNPLUGGING OF WASTE TRANSFER PIPELINES

    International Nuclear Information System (INIS)

    Ebadian, M.A.

    1999-01-01

    This project, which began in FY97, involves both the flow loop research on plugging and unplugging of waste transfer pipelines, and the large-scale industrial equipment test of plugging locating and unplugging technologies. In FY98, the related work was performed under the project name ''Mixing, Settling, and Pipe Unplugging of Waste Transfer Lines.'' The mixing, settling, and pipeline plugging and unplugging are critical to the design and maintenance of a waste transfer pipeline system, especially for the High-Level Waste (HLW) pipeline transfer. The major objective of this work is to recreate pipeline plugging conditions for equipment testing of plug locating and removal and to provide systematic operating data for modification of equipment design and enhancement of performance of waste transfer lines used at DOE sites. As the waste tank clean-out and decommissioning program becomes active at the DOE sites, there is an increasing potential that the waste slurry transfer lines will become plugged and unable to transport waste slurry from one tank to another or from the mixing tank to processing facilities. Transfer systems may potentially become plugged if the solids concentration of the material being transferred increases beyond the capability of the prime mover or if upstream mixing is inadequately performed. Plugging can occur due to the solids' settling in either the mixing tank, the pumping system, or the transfer lines. In order to enhance and optimize the slurry's removal and transfer, refined and reliable data on the mixing, sampling, and pipe unplugging systems must be obtained based on both laboratory-scale and simulated in-situ operating conditions

  13. Energy cost reduction in oil pipeline

    Energy Technology Data Exchange (ETDEWEB)

    Limeira, Fabio Machado; Correa, Joao Luiz Lavoura; Costa, Luciano Macedo Josino da; Silva, Jose Luiz da; Henriques, Fausto Metzger Pessanha [Petrobras Transporte S.A. (TRANSPETRO), Rio de Janeiro, RJ (Brazil)

    2012-07-01

    One of the key questions of modern society consists on the rational use of the planet's natural resources and energy. Due to the lack of energy, many companies are forced to reduce their workload, especially during peak hours, because residential demand reaches its top and there is not enough energy to fulfill the needs of all users, which affects major industries. Therefore, using energy more wisely has become a strategic issue for any company, due to the limited supply and also for the excessive cost it represents. With the objective of saving energy and reducing costs for oil pipelines, it has been identified that the increase in energy consumption is primordially related to pumping stations and also by the way many facilities are operated, that is, differently from what was originally designed. Realizing this opportunity, in order to optimize the process, this article intends to examine the possibility of gains evaluating alternatives regarding changes in the pump scheme configuration and non-use of pump stations at peak hours. Initially, an oil pipeline with potential to reduce energy costs was chosen being followed by a history analysis, in order to confirm if there was sufficient room to change the operation mode. After confirming the pipeline choice, the system is briefly described and the literature is reviewed, explaining how the energy cost is calculated and also the main characteristics of a pumping system in series and in parallel. In that sequence, technically feasible alternatives are studied in order to operate and also to negotiate the energy demand contract. Finally, costs are calculated to identify the most economical alternative, that is, for a scenario with no increase in the actual transported volume of the pipeline and for another scenario that considers an increase of about 20%. The conclusion of this study indicates that the chosen pipeline can achieve a reduction on energy costs of up to 25% without the need for investments in new

  14. Neutron backscattered application in investigation for Pipeline Intelligent Gauge (PIG) tracking in RAYMINTEX matrix pipeline

    International Nuclear Information System (INIS)

    Mohd Fakarudin Badul Rahman; Ismail Mustapha; Nor Paiza Mohd Hasan; Pairu Ibrahim; Airwan Affandi Mahmood; Mior Ahmad Khusaini Adnan; Najib Mohammed Zakey

    2012-01-01

    The Radiation Vulcanized Natural Rubber Latex (RVNRL) process plants such RAYMINTEX, pipelines are used extensively to transfer a latex product from storage vessel and being irradiated to produce a high quality of latex. A hydraulically activated Pipeline Intelligent Gauge (PIG) was held back against the latex flow. Consequently, the stuck PIG in pipeline was subjected to interrupt plant operation. The investigation was carried out using the neutron backscattered technique scanner to track the stuck PIG in pipeline of RVNRL plant. The 50 mCi Americium Beryllium (AmBe 241 ) fast neutron emitter source in the range 0.5-11 MeV has been used and thermal neutrons in the 30 eV- 0.5 MeV was detected using Helium-3 (He 3 ) detector. It is observed that there is unambiguous relationship between vapour and RVNRL consequence of diverse hydrogen concentration in pipeline. Thus, neutron backscattered technique was capable to determine the location of stuck PIG in a RVNRL pipeline. (author)

  15. 76 FR 54531 - Pipeline Safety: Potential for Damage to Pipeline Facilities Caused by the Passage of Hurricanes

    Science.gov (United States)

    2011-09-01

    ... prescribed in Sec. 195.452(h).'' Operators of shallow-water gas and hazardous liquid pipelines in the Gulf of... pipeline safety: 1. Identify persons who normally engage in shallow-water commercial fishing, shrimping... DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket No...

  16. Economic evaluation of CO2 pipeline transport in China

    International Nuclear Information System (INIS)

    Zhang Dongjie; Wang Zhe; Sun Jining; Zhang Lili; Li Zheng

    2012-01-01

    Highlights: ► We build a static hydrodynamic model of CO 2 pipeline for CCS application. ► We study the impact on pressure drop of pipeline by viscosity, density and elevation. ► We point out that density has a bigger impact on pressure drop than viscosity. ► We suggest dense phase transport is preferred than supercritical state. ► We present cost-optimal pipeline diameters for different flowrates and distances. - Abstract: Carbon capture and sequestration (CCS) is an important option for CO 2 mitigation and an optimized CO 2 pipeline transport system is necessary for large scale CCS implementation. In the present work, a hydrodynamic model for CO 2 pipeline transport was built up and the hydrodynamic performances of CO 2 pipeline as well as the impacts of multiple factors on pressure drop behavior along the pipeline were studied. Based on the model, an economic model was established to optimize the CO 2 pipeline transport system economically and to evaluate the unit transport cost of CO 2 pipeline in China. The hydrodynamic model results show that pipe diameter, soil temperature, and pipeline elevation change have significant influence on the pressure drop behavior of CO 2 in the pipeline. The design of pipeline system, including pipeline diameter and number of boosters etc., was optimized to achieve a lowest unit CO 2 transport cost. In regarding to the unit cost, when the transport flow rate and distance are between 1–5 MtCO 2 /year and 100–500 km, respectively, the unit CO 2 transport cost mainly lies between 0.1–0.6 RMB/(tCO 2 km) and electricity consumption cost of the pipeline inlet compressor was found to take more than 60% of the total cost. The present work provides reference for CO 2 transport pipeline design and for feasibility evaluation of potential CCS projects in China.

  17. Measurement of flow characteristics of solid particles mixed with gas in pipelines

    Energy Technology Data Exchange (ETDEWEB)

    Siberev, S P; Nazarov, S I; Soldatkin, G I

    1983-01-01

    A mathematical model of the interaction of solid particles in a gas stream flowing through a pipeline comprises equations for the energy and material balances in the system and for force and energy interactions between the solid particles and transducers located within the pipeline. Soviet researchers confirmed that the average value of stress recorded by a transducer is proportional to the average kinetic energy of the particles; for a constant particle speed, the stress is proportional to the mass flow of the particles. The analysis and flow transducer measurements are valuable in measuring and controlling flowline sand and soil in natural gas transport from gas wells and undergound storage facilities.

  18. HiCUP: pipeline for mapping and processing Hi-C data.

    Science.gov (United States)

    Wingett, Steven; Ewels, Philip; Furlan-Magaril, Mayra; Nagano, Takashi; Schoenfelder, Stefan; Fraser, Peter; Andrews, Simon

    2015-01-01

    HiCUP is a pipeline for processing sequence data generated by Hi-C and Capture Hi-C (CHi-C) experiments, which are techniques used to investigate three-dimensional genomic organisation. The pipeline maps data to a specified reference genome and removes artefacts that would otherwise hinder subsequent analysis. HiCUP also produces an easy-to-interpret yet detailed quality control (QC) report that assists in refining experimental protocols for future studies. The software is freely available and has already been used for processing Hi-C and CHi-C data in several recently published peer-reviewed studies.

  19. Vulnerability assessment of critical infrastructure : activity 2 progress report : information of SCADA systems and other security monitoring systems used in oil and gas pipelines

    Energy Technology Data Exchange (ETDEWEB)

    Gu, G.P. [Natural Resources Canada, Ottawa, ON (Canada). CANMET Materials Technology Laboratory

    2007-12-15

    Many pipelines are located in remote regions and subjected to harsh environmental conditions. Damage to pipelines can have significant economic and environmental impacts. This paper discussed the use of supervisory control and data acquisition (SCADA) systems to monitor and control oil and gas pipeline infrastructure. SCADA systems are a real time, distributed computerized system with an intelligent capability for condition identification and fault diagnosis. SCADA systems can be used to capture thousands of miles of pipeline system process data and distribute it to pipeline operators, whose work stations are networked with the SCADA central host computer. SCADA architectures include monolithic, distributed, and networked systems that can be distributed across wide area networks (WANs). SCADA security strategies must be implemented to ensure corporate network security. Case studies of SCADA systems currently used by oil and gas operators in Alberta were also presented. 15 refs., 1 fig.

  20. Laser-based gas sensors keep moisture out of pipelines

    Energy Technology Data Exchange (ETDEWEB)

    Anon.

    2006-07-15

    Natural gas often contains contaminants that cause corrosion, and long-term deterioration, and must be cleaned and brought to pipeline standards before it can be delivered to high-pressure, long-distance pipelines. Many older sensors produce false data that can result in contaminated gas getting through. This article presented details of the SpectraSensor, a new laser-based sensor technology used by the El Paso Natural Gas Company (EPNG). The SpectraSensor is comprised of a tunable diode laser (TDL) based technology developed by the National American Space Agency (NASA). The gas analyzer provides non-contact measurement of moisture, carbon dioxide, and other corrosives in natural gas pipelines, and the tunable laser-based gas sensors are fast, accurate, and flexible. Producers can monitor El Paso's gas analyzer readings by capturing the electronic signal from El Paso's unit via a SCADA system and view the readings from control rooms. While initial purchase price is higher than more problematic surface-based gas sensors, an evaluation of the technology has indicated that maintenance savings alone may provide an almost immediate return on investments. Unlike electrochemical and crystal gas sensors, laser-based gas analyzers do not come into direct contact with any substances, a fact which practically eliminates maintenance and operational costs. Studies have shown that the cost of operating conventional electrochemical sensors can result in a cumulative annual expense exceeding $50,000 per unit including labour; recalibration and rebuilding; back-up sensor heads; and gas dehydration and tariffs. 1 fig.

  1. Probability distribution of pitting corrosion depth and rate in underground pipelines: A Monte Carlo study

    International Nuclear Information System (INIS)

    Caleyo, F.; Velazquez, J.C.; Valor, A.; Hallen, J.M.

    2009-01-01

    The probability distributions of external-corrosion pit depth and pit growth rate were investigated in underground pipelines using Monte Carlo simulations. The study combines a predictive pit growth model developed by the authors with the observed distributions of the model variables in a range of soils. Depending on the pipeline age, any of the three maximal extreme value distributions, i.e. Weibull, Frechet or Gumbel, can arise as the best fit to the pitting depth and rate data. The Frechet distribution best fits the corrosion data for long exposure periods. This can be explained by considering the long-term stabilization of the diffusion-controlled pit growth. The findings of the study provide reliability analysts with accurate information regarding the stochastic characteristics of the pitting damage in underground pipelines.

  2. Probability distribution of pitting corrosion depth and rate in underground pipelines: A Monte Carlo study

    Energy Technology Data Exchange (ETDEWEB)

    Caleyo, F. [Departamento de Ingenieria Metalurgica, ESIQIE, IPN, UPALM Edif. 7, Zacatenco, 07738 Mexico, D.F. (Mexico)], E-mail: fcaleyo@gmail.com; Velazquez, J.C. [Departamento de Ingenieria Metalurgica, ESIQIE, IPN, UPALM Edif. 7, Zacatenco, 07738 Mexico, D.F. (Mexico); Valor, A. [Facultad de Fisica, Universidad de La Habana, San Lazaro y L, Vedado, 10400, La Habana (Cuba); Hallen, J.M. [Departamento de Ingenieria Metalurgica, ESIQIE, IPN, UPALM Edif. 7, Zacatenco, 07738 Mexico, D.F. (Mexico)

    2009-09-15

    The probability distributions of external-corrosion pit depth and pit growth rate were investigated in underground pipelines using Monte Carlo simulations. The study combines a predictive pit growth model developed by the authors with the observed distributions of the model variables in a range of soils. Depending on the pipeline age, any of the three maximal extreme value distributions, i.e. Weibull, Frechet or Gumbel, can arise as the best fit to the pitting depth and rate data. The Frechet distribution best fits the corrosion data for long exposure periods. This can be explained by considering the long-term stabilization of the diffusion-controlled pit growth. The findings of the study provide reliability analysts with accurate information regarding the stochastic characteristics of the pitting damage in underground pipelines.

  3. Effects of cathodic protection on cracking of high-strength pipeline steels

    Energy Technology Data Exchange (ETDEWEB)

    Elboujdaini, M.; Revie, R. W.; Attard, M. [CANMET Materials Technology Laboratory, Ottawa, ON(Canada)], email: melboujd@nrcan.gc.ca

    2010-07-01

    Four strength levels of pipeline steels, ranging from X-70 to X-120, were compared to determine whether higher strength materials are more susceptible to hydrogen embrittlement under cathodic protection. Ductility was measured in a solution at four protection levels, going from no cathodic protection to 500 mV of overprotection. All four steels showed loss of ductility under cathodic protection. Under cathodic polarization, the loss of ductility increased with the strength of the steel and the activity of the potential. After slow-strain-rate experiments conducted in air and examination of fracture surfaces, it is concluded that application of cathodic potentials, cathodic overprotection, higher strength of steel, and exposure to aqueous solution are factors that decrease the ductility of steel. Hydrogen reduction seems to be an important factor in ductility reduction and fractures. Observations suggest that high-strength pipelines need better control of cathodic protection than lower-strength pipelines.

  4. Mechanical Characteristics of Submerged Arc Weldment in API Gas Pipeline Steel of Grade X65

    International Nuclear Information System (INIS)

    Hashemi, S. H.; Mohammadyani, D.

    2011-01-01

    The mechanical properties of submerged arc weldment (SAW) in gas transportation pipeline steel of grade API X65 (65 ksi yield strength) were investigated. This steel is produced by thermo mechanical control rolled (TMC), and is largely used in Iran gas piping systems and networks. The results from laboratory study on three different regions; i.e. base metal (BM), fusion zone (FZ) and heat affected zone (HAZ) were used to compare weldment mechanical characteristics with those specified by API 5L (revision 2004) standard code. Different laboratory experiments were conducted on test specimens taken from 48 inch outside diameter and 14.3 mm wall thickness gas pipeline. The test results showed a gradient of microstructure and Vickers hardness data from the centerline of FZ towards the unaffected MB. Similarly, lower Charpy absorbed energy (compared to BM) was observed in the FZ impact specimens. Despite this, the API specifications were fulfilled in three tested zones, ensuring pipeline structural integrity under working conditions.

  5. Managing the market risk in pipeline capacity positions

    International Nuclear Information System (INIS)

    Simard, T.S.

    1998-01-01

    Managing the risk involved in adding new pipeline capacity was explored in this presentation. Topics discussed included: (1) pipeline capacity positions as basis swaps, (2) physical capacity versus basis transactions, (3) managing the market price risk in a capacity position, and (4) sharing of pipeline market risk. Pipeline owners were advised to recognize that pipeline capacity carries significant market price risk, that basis markets can sometimes be more volatile than outright markets, and to treat physical capacity market risk the same way as one would treat a financial basis position. 2 figs

  6. Pipeline abandonment - a discussion paper on technical and environmental issues

    International Nuclear Information System (INIS)

    1996-11-01

    The technical and environmental issues associated with pipeline abandonment were reviewed to provide a basis for the development of guidelines that companies could follow in order to abandon oil and gas pipelines in an environmentally safe and economic manner. Some of the topics discussed include land use management, ground subsidence, soil and groundwater contamination, erosion and the potential to create water conduits. A major issue still to be resolved, i.e., the legal and financial aspects of pipeline abandonment, was addressed. An industry-financed fund has been created to cover the cost of reclamation and abandonment of orphaned pipelines and certain associated pipeline facilities. 30 refs., 4 tabs., 3 figs

  7. Online slug detection in multi-phase transportation pipelines using electrical tomography

    DEFF Research Database (Denmark)

    Pedersen, Simon; Mai, Christian; Hansen, Leif

    2015-01-01

    in the pipelines is a highly investigated topic. To eliminate the slug in an online manner real-time slug detection methods are often required. Traditionally topside pressure transmitters upstream a 3-phase separator have been used as the controlled variable. In this paper Electrical Resistivity Tomography (ERT...

  8. Online Slug Detection in Multi-phase Transportation Pipelines Using Electrical Tomography

    DEFF Research Database (Denmark)

    Pedersen, Simon; Mai, Christian; Hansen, Leif

    2015-01-01

    in the pipelines is a highly investigated topic. To eliminate the slug in an online manner real-time slug detection methods are often required. Traditionally topside pressure transmitters upstream a 3-phase separator have been used as the controlled variable. In this paper Electrical Resistivity Tomography (ERT...

  9. 49 CFR 192.489 - Remedial measures: Cast iron and ductile iron pipelines.

    Science.gov (United States)

    2010-10-01

    ... 49 Transportation 3 2010-10-01 2010-10-01 false Remedial measures: Cast iron and ductile iron... for Corrosion Control § 192.489 Remedial measures: Cast iron and ductile iron pipelines. (a) General graphitization. Each segment of cast iron or ductile iron pipe on which general graphitization is found to a...

  10. 49 CFR 192.620 - Alternative maximum allowable operating pressure for certain steel pipelines.

    Science.gov (United States)

    2010-10-01

    ... (SCADA) system, other leak detection system, or an alternative method of control. (iii) Remote valve... outs, leakage, or other activities or conditions affecting the safety operation of the pipeline. (ii... requirements of § 192.707(d) except in agricultural areas, large water crossings or swamp, steep terrain, or...

  11. An integrated system for pipeline condition monitoring

    Energy Technology Data Exchange (ETDEWEB)

    Strong, Andrew P.; Lees, Gareth; Hartog, Arthur; Twohig, Richard; Kader, Kamal; Hilton, Graeme; Mullens, Stephen; Khlybov, Artem [Schlumberger, Southampton (United Kingdom); Sanderson, Norman [BP Exploration, Sunbury (United Kingdom)

    2009-07-01

    In this paper we present the unique and innovative 'Integriti' pipeline and flow line integrity monitoring system developed by Schlumberger in collaboration with BP. The system uses optical fiber distributed sensors to provide simultaneous distributed measurements of temperature, strain and vibration for the detection, monitoring, and location of events including: Third Party Interference (TPI), including multiple simultaneous disturbances; geo-hazards and landslides; gas and oil leaks; permafrost protection. The Integriti technology also provides a unique means for tracking the progress of cleaning and instrumented pigs using existing optical telecom and data communications cables buried close to pipelines. The Integriti solution provides a unique and proactive approach to pipeline integrity management. It performs analysis of a combination of measurands to provide the pipeline operator with an event recognition and location capability, in effect providing a hazard warning system, and offering the operator the potential to take early action to prevent loss. Through the use of remote, optically powered amplification, an unprecedented detection range of 100 km is possible without the need for any electronics and therefore remote power in the field. A system can thus monitor 200 km of pipeline when configured to monitor 100 km upstream and downstream from a single location. As well as detecting conditions and events leading to leaks, this fully integrated system provides a means of detecting and locating small leaks in gas pipelines below the threshold of present online leak detection systems based on monitoring flow parameters. Other significant benefits include: potential reductions in construction costs; enhancement of the operator's existing integrity management program; potential reductions in surveillance costs and HSE risks. In addition to onshore pipeline systems this combination of functionality and range is available for practicable

  12. Living and working near pipelines : Landowner guide 2002

    International Nuclear Information System (INIS)

    Anon

    2002-01-01

    The transportation of natural gas, oil and other commodities is effected by pipelines throughout most of the country. Safety in the vicinity of a pipeline is very important because damage to a pipeline could result in adverse conditions to public safety and/or the environment. Before digging, written approval must be obtained from the pipeline company. If a landowner is having difficulty negotiating an agreement with the pipeline company, they should call the National Energy Board. It is illegal to construct or excavate without authorization, and approval or denial of a request must be granted within 10 business days by the pipeline company. Three days are allowed to the pipeline company to locate its pipeline. A section dealing with pipeline right-of-way is included, as well as the safety zone and the restricted area. A 10-step checklist of safety tips assists the landowner in taking the appropriate measures in the vicinity of a pipeline. A brief overview of the responsibilities of the National Energy Board is provided, followed by a list of the main pipelines regulated by the National Energy Board. 2 figs

  13. Induced AC voltages on pipelines may present a serious hazard

    International Nuclear Information System (INIS)

    Kirkpatrick, E.L.

    1997-01-01

    The problem of induced AC voltages on pipelines has always been with us. Early pipeline construction consisted of bare steel or cast iron pipe, which was very well grounded. Bell and spigot, mechanical, or dresser-style joint couplings often were used, creating electrically discontinuous pipelines which are less susceptible to AC induction. Although induced AC affects any pipeline parallel to a high-voltage alternating current (HVAC) power line, the effects were not noticeable on bare pipelines. With the advent of welded steel pipelines, modern cathodic protection (CP) methods and materials, and the vastly improved quality of protective coatings, induced AC effects on pipelines have become a significant consideration on many pipeline rights-of-way. In the last two to three decades, one has been seeing much more joint occupancy of the same right-of-way by one or more pipelines and power lines. As the cost of right-of-way and the difficulty in acquisition, particularly in urban areas, have risen, the concept of joint occupancy rights-of-way has become more attractive to many utility companies. Federal and state regulations usually insist on joint-use right-of-way when a utility proposes crossing regulated or publicly owned lands, wherever there is an existing easement. Such joint use allows the induced AC phenomena to occur and may create electrical hazards and interference to pipeline facilities. Underground pipelines are especially susceptible if they are well-coated and electrically isolated for CP

  14. Modelling of CO2 pipelines in dynamic CCS systems

    Science.gov (United States)

    Nimtz, M.; Klatt, M.; Krautz, H. J.

    2012-04-01

    The growing rate of renewable energies contributing to the power supply in Germany is starting to influence conventional thermal power plants. As a particular example, the state of Brandenburg in the eastern part of Germany has an installed capacity of 4.4 GW wind power [DEWI 2011] and 6.1 GW fossil fueled large-scale power plants (including the site in Boxberg, north-east saxony) [Vattenfall 2011] respectively. This ratio is disadvantageous, as the local thermal power plants have to provide all the balancing power to control the load of the power grid in the region. As long as there are bottlenecks in the grid, preventing the extra load from wind energy to be transported as well as a lack of technologies to store electrical energy, almost all load changes have to be balanced by the large fossil fueled power plants. The ability to provide balancing power will also be an essential criterion for new large-scale CCS (carbon dioxide capture and storage) power plants to be permitted. But this of course will influence the overall performance of the power plant and the connected peripheral systems. It is obvious that the additional equipment to capture, transport and store the CO2 and all related extra process steps will lower the flexibility and the speed of load changes that can be applied to the CCS system if no special measures are applied. All changes in load that are demanded from the power grid will be transferred to the capture and transport system, finally resulting in changes in mass flow and pressure of the CO2. These changes will also influence the performance of the storage reservoir. The presentation at the GeoEn session at the EGU 2012 will cover a look at a CCS system consisting of a coal fired Oxyfuel power plant, a pipeline to transport the CO2 and a saline aquifer as a storage reservoir. It is obvious that all parts of this system will influence each other due to the direct connection via pipeline and the physical limitations in mass flow and pressure

  15. Assessing and preparing a pipeline for in line inspection

    Energy Technology Data Exchange (ETDEWEB)

    Payne, Larry [T.D. Williamson Inc., Tulsa, OK (United States)

    2003-07-01

    In today's pipeline environment, operators around the world face new and emerging state and federal regulations requiring validation of their pipelines' integrity. In line inspection, or smart pigging, is generally the preferred methodology used to investigate metal loss and corrosion in pipelines. Although many pipelines can accommodate smart pigging, there are many pipelines that cannot, for various reasons. Those reasons can vary from not having pig launchers and receivers installed on the line to impassable bends or restrictions and general cleanliness of the pipeline itself. Pipeline cleanliness, more times than not, is one of the main reasons for inaccurate in line inspection data gathering or failed smart pig runs. (author)

  16. Method for keeping equipment and pipeline of nuclear power plant

    International Nuclear Information System (INIS)

    Okubo, Osamu.

    1990-01-01

    The present invention intends to suppress corrosion of equipments and pipelines in condensate, feedwater and feedwater heater drain systems during operation of a nuclear power plant. That is, condensate, feedwater and drain remained in equipments and pipelines just after the stopping of operation are passed through pipelines comprising only conduits, or they are introduced to a condensator passing through the pipelines and condensate pipes. Further, the remaining droplets on the inner surfaces are evaporated by the remaining heat of the equipments and the pipelines themselves. Then, the equipments and pipelines are isolated from other regions and kept. In view of the above, since condensate, feedwater and water feeder drains are introduced directly to the condensator passing through the conduits in which other equipments such as tanks and pumps are not present and are isolated and kept, corrosion of the equipments and the pipelines is suppressed and radioactive contamination is suppressed from prevailing by way of cruds. (I.S.)

  17. Improved, Low-Stress Economical Submerged Pipeline

    Science.gov (United States)

    Jones, Jack A.; Chao, Yi

    2011-01-01

    A preliminary study has shown that the use of a high-strength composite fiber cloth material may greatly reduce fabrication and deployment costs of a subsea offshore pipeline. The problem is to develop an inexpensive submerged pipeline that can safely and economically transport large quantities of fresh water, oil, and natural gas underwater for long distances. Above-water pipelines are often not feasible due to safety, cost, and environmental problems, and present, fixed-wall, submerged pipelines are often very expensive. The solution is to have a submerged, compliant-walled tube that when filled, is lighter than the surrounding medium. Some examples include compliant tubes for transporting fresh water under the ocean, for transporting crude oil underneath salt or fresh water, and for transporting high-pressure natural gas from offshore to onshore. In each case, the fluid transported is lighter than its surrounding fluid, and thus the flexible tube will tend to float. The tube should be ballasted to the ocean floor so as to limit the motion of the tube in the horizontal and vertical directions. The tube should be placed below 100-m depth to minimize biofouling and turbulence from surface storms. The tube may also have periodic pumps to maintain flow without over-pressurizing, or it can have a single pump at the beginning. The tube may have periodic valves that allow sections of the tube to be repaired or maintained. Some examples of tube materials that may be particularly suited for these applications are non-porous composite tubes made of high-performance fibers such as Kevlar, Spectra, PBO, Aramid, carbon fibers, or high-strength glass. Above-ground pipes for transporting water, oil, and natural gas have typically been fabricated from fiber-reinforced plastic or from more costly high-strength steel. Also, previous suggested subsea pipeline designs have only included heavy fixed-wall pipes that can be very expensive initially, and can be difficult and expensive

  18. Pipeline corrosion prevention by pH stabilization or corrosion inhibitors

    Energy Technology Data Exchange (ETDEWEB)

    Nyborg, Rolf [Institute for Energy Technology, Oslo (Norway)

    2009-07-01

    In many offshore oil and gas projects the pipeline costs are a considerable part of the investment and can become prohibitively high if the corrosivity of the fluid necessitates the use of corrosion resistant alloys instead of carbon steel. Development of more robust and reliable methods for internal corrosion control can increase the application range of carbon steel and therefore have a large economic impact. Corrosion control of carbon steel pipelines has traditionally often been managed by the use of corrosion inhibitors. The pH stabilization technique has been successfully used for corrosion control of several large wet gas pipelines in the last years. This method has advantages over film forming corrosion inhibitors when no or little formation water is produced. The use of corrosion inhibitors in multiphase pipelines implies several challenges which are not fully accounted for in traditional corrosion inhibitor testing procedures. Specialized test procedures have been developed to take account for the presence of emulsions dispersions and sand and clay particles in corrosion inhibitor testing. (author)

  19. Digitization of radiographic inspection for pipeline girth welded joints

    International Nuclear Information System (INIS)

    Uemura, Shimpei

    2016-01-01

    In radiographic inspection for the girth welded joints of natural gas pipeline, film radiographic testing (FRT) is applied presently in Japan. However, as of July 2016, the work of establishing JIS standard for radiographic inspection with digital detector is in progress. In order to provide users with the merit of digitization as soon as possible, the authors have developed NSDART (Nittetsu-Sumikin digital detector array technology) as a field X-ray inspection system for the girth welded joints of pipeline. This paper reports the required performances discussed in face of development of NSDART, selection of digital detector, and outline of NSDART, and shows part of the radiographic images acquired with NSDART. As required performances, the following were established: (1) required image quality for radiographic image, (2) identifiable minimum wire diameter of transmission meter, (3) density range of radiographic image and value of gradation meter, (4) spatial resolution via Duplex Wire, (5) X-ray generator, (6) real time performance, and (7) display for observing radiographic image. As for the selection of digital detector, flat panel detector was judged to be the most suitable, and its incorporation to NSDART was determined. NSDART devices are composed of a magnet-wheeled self-propelled imaging device, personal computer, controller, and externally installed display for judgment. (A.O.)

  20. Quality assurance for pipeline installations in nuclear power plants

    International Nuclear Information System (INIS)

    Anon.

    1983-01-01

    Approximately 25% of the cost of a nuclear power plant are caused by the pipeline system, i.e. pipes and fixtures. This is an enourmous portion, demanding of the supplier and fitter of these components a very high safety standard. Against the background of the sociopolitical discussion on the safety of nuclear power plants it was a very useful idea of Mannesmann AG, one of the most important manufacturers in this sector, to lay open its quality assurance concept. On the occasion of the symposium ''Safe components for nuclear energy'' held for the expert press it was pointed out that the share of 17% electric energy coming at present from 15 nuclear power plants will increase in future for economic and ecologic reasons. So, it was maintained, the question is not about the ''pro and the con'', but exclusively about the safety standard for nuclear power plants. Specialists from the various branches of the undertaking informed on how this safety concept for the components pipelines and control equipment is realized. (orig./RW) [de