WorldWideScience

Sample records for improvement project phase iii

  1. Qinshan Phase III (CANDU) nuclear power project quality assurance

    International Nuclear Information System (INIS)

    Wang Lingen; Du Jinxiang

    2001-01-01

    The completion and implementation of quality assurance system of Qinshan Phase III (CANDU) nuclear power project are presented. Some comments and understanding with consideration of the project characteristics are put forward

  2. The Qinshan phase III project-a successful model of sino-canadian cooperation

    International Nuclear Information System (INIS)

    Pang, S.H.H.; Alikhan, S.; Gu Jun

    2005-01-01

    The Qinshan Phase III (CANDU) Project, the largest-scale cooperative project between China and Canada, was completed in 2003 well in advance of the schedule and 10% under budget. The Third Qinshan (Phase III) Nuclear Power Plant (TQNPP) was built in record times: Unit 1 achieved commercial operation on December 31, 2002 and Unit 2 on July 20, 2003, 43 days and 115 days ahead of schedule respectively. Improvements in design and construction methods allowed Unit 1 to be constructed in 51.5 months from First Concrete to Criticality - a record in China for nuclear power plants. The key factors are project management and project management tools, quality assurance, construction methods, electronic documentation with configuration control that provides up-to-date on-line information, CADDS design linked with material management and control. New design and construction techniques were introduced by combining conventional AECL practices with working experiences in China. The most advanced tools and techniques for achieving optimum construction quality, schedule and cost were used. Successful application of advanced project management methods and tools has benefited TQNPC in its subsequent plant operation, and the Chinese contractors in advancing their capabilities in future nuclear projects in China as well as enhancing their opportunities internationally. Excellent co-operation and teamwork within the integrated TQNPC/AECL Commissioning Team with well documented QA program, process and procedures also contributed to the remarkable success of the Project. AECL's initial assessment, based on lessons learned, showed that the project schedule could readily be reduced to 66 months and the capital costs reduced by 25% for a replication project. AECL is building on this experience and successful results of TQNPP in its Advanced CANDU Reactor TM (ACR TM ) ** design. (authors)

  3. Individualized Inservice Teacher Education (Project In-Step). Evaluation Report. Phase III.

    Science.gov (United States)

    Thurber, John C.

    This is a report on the third phase of Project IN-STEP, which was intended to develop a viable model for individualized, multi-media in-service teacher education programs. (Phase I and II are reported in ED 033 905, and ED 042 709). The rationale for Phase III was to see if the model could be successfully transferred to an area other than teaching…

  4. The third phase of the OECD/NEA TDB project: TDB III

    International Nuclear Information System (INIS)

    Mompean, F.J.; Illemassene, M.; Perrone, J.

    2005-01-01

    In 2003 with a foreseen duration of four years. The main objective of this new phase is to extend the existing critically reviewed database for elements of relevance in radioactive waste management, paying attention to the needs of the various national programmes. Following the decision by the Project Management Board (integrated by representatives of 16 organisations with responsibilities in radioactive waste management in 12 OECD member countries) the elements contemplated in this new phase are Th, Sn and Fe, with a higher priority being allocated to inorganic species and compounds. In addition to the corresponding review teams for these elements, an additional expert team has been constituted to prepare guidelines for the evaluation of thermodynamic data for solid solutions. As was the case in TDB Phase II, the basic project review methodology remains unaltered in TDB III. The Figure illustrates the relationship between the various TDB bodies, with an International Organisation, the OECD NEA, acting as Project Coordinator and linking the independent scientific teams and the project governing bodies. This organizational paradigm has proven successful with the recent completion of the five Phase II Reviews (Update, Ni, Se, Zr and Organic Ligands). The review and expert team activities were started in 2004 (except for Fe, being started in 2005) following an initiation stage. This preliminary stage was designed in order to tailor the team compositions to the existing literature for each element. The first reviews stemming from TDB III are scheduled to appear in published form in 2007. The successful completion of these objectives will add three further reports to the current series of nine volumes (dealing with the chemical thermodynamics of U, Np, Pu, Am, Tc, Ni, Se, Zr and compounds and complexes of these elements with oxalate, citrate, EDTA and isa). (authors)

  5. Cyprus natural analogue project (CNAP). Phase III final report

    International Nuclear Information System (INIS)

    Alexander, W.R.; Milodowski, A.E.; Pitty, A.F.

    2012-01-01

    The CNAP Phase III project was carried out following identification of the requirement to support ongoing laboratory and modelling efforts on the potential reaction of the bentonite buffer with cementitious leachates in the repository EBS. Although it is known that the higher pH (12.5 to 13) leachates from OPC cement will degrade bentonite, it is unclear if this will also be the case for the lower pH (10 to 11) leachates typical of low alkali cements. Ongoing laboratory and URL programmes which are currently investigating this face the obstacle of slow kinetics and the production of short-lived metastable phases, meaning obtaining unambiguous results may take decades. This is exacerbated by the limitations of the thermodynamic databases for minerals of interest to models of bentonite/low alkali cement leachate reaction. It was therefore decided to implement a focussed NA study on bentonite/low alkali cement leachate reaction to provide indications of likely long-term reaction products and reaction pathways to provide feedback on the existing short-term investigations noted above and to ascertain if any critical path R and D needs to be instigated now. The results of the analyses presented here suggest that there has been very limited alkaline groundwater reaction with the bentonite. This is generally supported by both the geomorphological evidence and the natural decay series data which imply groundwater groundwater/rock interaction in the last 10 5 a. When integrated with the novel data currently being produced in the BIGRAD project, the CNAP data tend to indicate that any long-term bentonite reaction in low alkali cement leachates is minimal. (orig.)

  6. Cyprus natural analogue project (CNAP). Phase III final report

    Energy Technology Data Exchange (ETDEWEB)

    Alexander, W R [Bedrock Geosciences, Auenstein (Switzerland); Milodowski, A E [British Geological Survey, Keyworth (United Kingdom); Pitty, A F [Pitty (EIA) Consulting, Norwich (United Kingdom)

    2012-01-15

    The CNAP Phase III project was carried out following identification of the requirement to support ongoing laboratory and modelling efforts on the potential reaction of the bentonite buffer with cementitious leachates in the repository EBS. Although it is known that the higher pH (12.5 to 13) leachates from OPC cement will degrade bentonite, it is unclear if this will also be the case for the lower pH (10 to 11) leachates typical of low alkali cements. Ongoing laboratory and URL programmes which are currently investigating this face the obstacle of slow kinetics and the production of short-lived metastable phases, meaning obtaining unambiguous results may take decades. This is exacerbated by the limitations of the thermodynamic databases for minerals of interest to models of bentonite/low alkali cement leachate reaction. It was therefore decided to implement a focussed NA study on bentonite/low alkali cement leachate reaction to provide indications of likely long-term reaction products and reaction pathways to provide feedback on the existing short-term investigations noted above and to ascertain if any critical path R and D needs to be instigated now. The results of the analyses presented here suggest that there has been very limited alkaline groundwater reaction with the bentonite. This is generally supported by both the geomorphological evidence and the natural decay series data which imply groundwater groundwater/rock interaction in the last 10{sup 5} a. When integrated with the novel data currently being produced in the BIGRAD project, the CNAP data tend to indicate that any long-term bentonite reaction in low alkali cement leachates is minimal. (orig.)

  7. Lake Roosevelt Rainbow Trout : Habitat/Passage Improvement Project Annual Report 2000.

    Energy Technology Data Exchange (ETDEWEB)

    Sear, Sheri

    2001-02-01

    Lake Franklin D. Roosevelt was created with the completion of the Grand Coulee Dam in 1942. The lake stretches 151 miles up-stream to the International border between the United States and Canada at the 49th parallel. Increased recreational use, subsistence and sport fishing has resulted in intense interest and possible exploitation of the resources within the lake. Previous studies of the lake and its fishery have been limited. Early studies indicate that natural reproduction within the lake and tributaries are not sufficient to support a rainbow trout (Onchoryhnchus mykiss) fishery (Scholz et. al., 1988). These studies indicate that the rainbow trout population may be limited by lack of suitable habitat for spawning and rearing (Scholz et. al., 1988). The initial phase of this project (Phase I, baseline data collection- 1990-91) was directed at the assessment of limiting factors such as quality and quantity of available spawning gravel, identification of passage barriers, and assessment of other limiting factors. Population estimates were conducted using the Seber/LeCren removal/depletion method. After the initial assessment of stream parameters, several streams were selected for habitat/passage improvement projects (Phase II, implementation-1992-96). At the completion of project habitat improvements, the final phase (Phase III, monitoring) began. This phase will assess changes and gauge the success achieved through the improvements. The objective of the project is to correct passage barriers and improve habitat conditions of selected tributaries to Lake Roosevelt for adfluvial rainbow trout that utilize tributary streams for spawning and rearing. Streams with restorable habitats were selected for improvements. Completion of improvement efforts should increase the adfluvial rainbow trout contribution to the resident fishery in Lake Roosevelt. Three co-operating agencies, the Confederated Tribes of the Colville Reservation (CCT), the Spokane Tribe of Indians (STI

  8. Lake Roosevelt Rainbow Trout : Habitat/Passage Improvement Project Annual Report 1999.

    Energy Technology Data Exchange (ETDEWEB)

    Jones, Charles D.

    2000-02-01

    Lake Franklin D. Roosevelt was created with the completion of the Grand Coulee Dam in 1942. The lake stretches 151 miles up-stream to the International border between the United States and Canada at the 49th parallel. Increased recreational use, subsistence and sport fishing has resulted in intense interest and possible exploitation of the resources within the lake. Previous studies of the lake and its fishery have been limited. Early studies indicate that natural reproduction within the lake and tributaries are not sufficient to support a rainbow trout (Onchoryhnchus mykiss) fishery (Scholz et. al., 1988). These studies indicate that the rainbow trout population may be limited by lack of suitable habitat for spawning and rearing (Scholz et. al., 1988). The initial phase of this project (Phase I, baseline data collection- 1990-91) was directed at the assessment of limiting factors such as quality and quantity of available spawning gravel, identification of passage barriers, and assessment of other limiting factors. Population estimates were conducted using the Seber/LeCren removal/depletion method. After the initial assessment of stream parameters, several streams were selected for habitat/passage improvement projects (Phase II, implementation-1992-96). At the completion of project habitat improvements, the final phase (Phase III, monitoring) began. This phase will assess changes and gauge the success achieved through the improvements. The objective of the project is to correct passage barriers and improve habitat conditions of selected tributaries to Lake Roosevelt for adfluvial rainbow trout that utilize tributary streams for spawning and rearing. Streams with restorable habitats were selected for improvements. Completion of improvement efforts should increase the adfluvial rainbow trout contribution to the resident fishery in Lake Roosevelt. Three co-operating agencies, the Confederated Tribes of the Colville Reservation (CCT), the Spokane Tribe of Indians (STI

  9. Application of project management in technology improvement of Qinshan III

    International Nuclear Information System (INIS)

    Liu Xiaonian

    2008-01-01

    During the operation of Qinshan III, many engineering modifications and renovation projects are being carried out. Advanced international project management methodologies accustomed to the policy and organizational characteristics of TQNPC were applied to the management of these projects. After practical application and development of these methodologies, the company finally sets up its own classification of project management system. The project management system is introduced and discussed for its evolving direction in this paper. (authors)

  10. Failures in Phase III: Causes and Consequences.

    Science.gov (United States)

    Seruga, Bostjan; Ocana, Alberto; Amir, Eitan; Tannock, Ian F

    2015-10-15

    Phase III randomized controlled trials (RCT) in oncology fail to lead to registration of new therapies more often than RCTs in other medical disciplines. Most RCTs are sponsored by the pharmaceutical industry, which reflects industry's increasing responsibility in cancer drug development. Many preclinical models are unreliable for evaluation of new anticancer agents, and stronger evidence of biologic effect should be required before a new agent enters the clinical development pathway. Whenever possible, early-phase clinical trials should include pharmacodynamic studies to demonstrate that new agents inhibit their molecular targets and demonstrate substantial antitumor activity at tolerated doses in an enriched population of patients. Here, we review recent RCTs and found that these conditions were not met for most of the targeted anticancer agents, which failed in recent RCTs. Many recent phase III RCTs were initiated without sufficient evidence of activity from early-phase clinical trials. Because patients treated within such trials can be harmed, they should not be undertaken. The bar should also be raised when making decisions to proceed from phase II to III and from phase III to marketing approval. Many approved agents showed only better progression-free survival than standard treatment in phase III trials and were not shown to improve survival or its quality. Introduction of value-based pricing of new anticancer agents would dissuade the continued development of agents with borderline activity in early-phase clinical trials. When collaborating with industry, oncologists should be more critical and better advocates for cancer patients. ©2015 American Association for Cancer Research.

  11. Project 8, Phase III Design: Placing an eV-Scale Limit on the Neutrino Mass using Cyclotron Radiation Emission Spectroscopy

    Science.gov (United States)

    Oblath, Noah; Project 8 Collaboration

    2016-09-01

    We report on the design concept for Phase III of the Project 8 experiment. In the third phase of Project 8 we aim to place a limit on the neutrino mass that is similar to the current limits set by tritium beta-decay experiments, mν radioastronomy will be employed to search for and track electron signals in the fiducial volume. This talk will present the quantitative design concept for the phased-array receiver, and illustrate how we are progressing towards the Phase IV experiment, which will have sensitivity to the neutrino mass scale allowed by the inverted mass hierarchy. This work is supported by the DOE Office of Science Early Career Research Program, and the Laboratory Directed Research and Development Program at Pacific Northwest National Laboratory.

  12. Final report on the surface-based investigation phase (phase 1) at the Mizunami Underground Research Laboratory project

    International Nuclear Information System (INIS)

    Saegusa, Hiromitsu; Matsuoka, Toshiyuki

    2011-03-01

    The Mizunami Underground Research Laboratory (MIU) Project is a comprehensive research project investigating the deep underground environment within crystalline rock being conducted by Japan Atomic Energy Agency at Mizunami City in Gifu Prefecture, central Japan and its role is defined in 'Framework for Nuclear Energy Policy' by Japan Atomic Energy Commission. The MIU Project has three overlapping phases: Surface-based Investigation phase (Phase I), Construction phase (Phase II), and Operation phase (Phase III), with a total duration of 20 years. The overall project goals of the MIU Project from Phase I through to Phase III are: 1) to establish techniques for investigation, analysis and assessment of the deep geological environment, and 2) to develop a range of engineering for deep underground application. During Phase I, the overall project goals were supported by Phase I goals. For the overall project goals 1), the Phase I goals were set to construct models of the geological environment from all surface-based investigation results that describe the geological environment prior to excavation and predict excavation response. For the overall project goals 2), the Phase I goals were set to formulate detailed design concepts and a construction plan for the underground facilities. This report summarizes the Phase I investigation which was completed in March 2005. The authors believe this report will make an important milestone, since this report clarifies how the Phase I goals are achieved and evaluate the future issues thereby direct the research which will be conducted during Phase II. With regard to the overall project goals 1), 'To establish techniques for investigation, analysis and assessment of the deep geological environment,' a step-wise investigation was conducted by iterating investigation, interpretation, and assessment, thereby understanding of geologic environment was progressively and effectively improved with progress of investigation. An optimal

  13. Improving Climate Projections by Understanding How Cloud Phase affects Radiation

    Science.gov (United States)

    Cesana, Gregory; Storelvmo, Trude

    2017-01-01

    Whether a cloud is predominantly water or ice strongly influences interactions between clouds and radiation coming down from the Sun or up from the Earth. Being able to simulate cloud phase transitions accurately in climate models based on observational data sets is critical in order to improve confidence in climate projections, because this uncertainty contributes greatly to the overall uncertainty associated with cloud-climate feedbacks. Ultimately, it translates into uncertainties in Earth's sensitivity to higher CO2 levels. While a lot of effort has recently been made toward constraining cloud phase in climate models, more remains to be done to document the radiative properties of clouds according to their phase. Here we discuss the added value of a new satellite data set that advances the field by providing estimates of the cloud radiative effect as a function of cloud phase and the implications for climate projections.

  14. Analysis of Reasons for fluctuation in seal oil system on generator and countermeasures in Qinshan phase III project

    International Nuclear Information System (INIS)

    Jin Xiaodong

    2012-01-01

    Reasons for hydraulic differential fluctuations seal hydrogen oil on generator in Qinshan phase III project were analyzed, provide a basis for modifying Run method is to determine the causes and effects of seal oil flow changes and in the relationship between flow changes and hydraulic differential hydrogen oil changes according to reason Results were analyzed to adjust the running test, to verify the feasibility of running adjustment programs

  15. The coupling of thermochemistry and phase diagrams for group III-V semiconductor systems. Final report

    Energy Technology Data Exchange (ETDEWEB)

    Anderson, T.J.

    1998-07-21

    The project was directed at linking the thermochemical properties of III-V compound semiconductors systems with the reported phase diagrams. The solid-liquid phase equilibrium problem was formulated and three approaches to calculating the reduced standard state chemical potential were identified and values were calculated. In addition, thermochemical values for critical properties were measured using solid state electrochemical techniques. These values, along with the standard state chemical potentials and other available thermochemical and phase diagram data, were combined with a critical assessment of selected III-V systems. This work was culminated with a comprehensive assessment of all the III-V binary systems. A novel aspect of the experimental part of this project was the demonstration of the use of a liquid encapsulate to measure component activities by a solid state emf technique in liquid III-V systems that exhibit high vapor pressures at the measurement temperature.

  16. Final report on the surface-based investigation (phase 1) at the Mizunami Underground Laboratory project

    International Nuclear Information System (INIS)

    Saegusa, Hiromitsu; Seno, Yasuhiro; Nakama, Shigeo; Tsuruta, Tadahiko; Amano, Kenji; Takeuchi, Ryuji; Matsuoka, Toshiyuki; Onoe, Hironori; Mizuno, Takashi; Ohyama, Takuya; Hama, Katsuhiro; Sato, Toshinori; Kuji, Masayoshi; Kuroda, Hidetaka; Semba, Takeshi; Uchida, Masahiro; Sugihara, Kozo; Sakamaki, Masanori; Iwatsuki, Teruki

    2007-03-01

    The Mizunami Underground Laboratory (MIU) Project is a comprehensive research project investigating the deep underground environment within crystalline rock being conducted by Japan Atomic Energy Agency at Mizunami City in Gifu Prefecture, central Japan and its role is defined in 'Framework for Nuclear Energy Policy' by Japan Atomic Energy Commission. The MIU Project has three overlapping phases: Surface-based Investigation phase (Phase I), Construction phase (Phase II), and Operation phase (Phase III), with a total duration of 20 years. The overall project goals of the MIU Project from Phase I through to Phase III are: 1) to establish techniques for investigation, analysis and assessment of the deep geological environment, and 2) to develop a range of engineering for deep underground application. During Phase I, the overall project goals were supported by Phase I goals. For the overall project goals 1), the Phase I goals were set to construct models of the geological environment from all surface-based investigation results that describe the geological environment prior to excavation and predict excavation response. For the overall project goals 2), the Phase I goals were set to formulate detailed design concepts and a construction plan for the underground facilities. This report summarizes the Phase I investigation which was completed in March 2005. The authors believe this report will make an important milestone, since this report clarifies how the Phase I goals are achieved and evaluate the future issues thereby direct the research which will be conducted during Phase II. With regard to the overall project goals 1), 'To establish techniques for investigation, analysis and assessment of the deep geological environment,' a step-wise investigation was conducted by iterating investigation, interpretation, and assessment, thereby understanding of geologic environment was progressively and effectively improved with progress of investigation. An optimal procedure from

  17. The OPAL phase III microvertex detector

    International Nuclear Information System (INIS)

    De Jong, S.

    1997-01-01

    A description of the OPAL Phase III microvertex detector is given. Special emphasis is put on problems that have been encountered in the installation and operation of the different phases of the OPAL microvertex detector leading to the present Phase III detector and their cures. A short description of the new OPAL radiation monitoring and beam dump system is also given. (orig.)

  18. Thermal dewatering of lignite: Phase III - final report

    Energy Technology Data Exchange (ETDEWEB)

    Champagne, P J; Szladow, A J; Kybett, B D

    1981-01-01

    Phase III of this project extended the investigation of thermal dewatering on several lignite and peat samples at the temperature range up to 400 degrees C and investigated variables such as retention time, increased rates of heating and cooling, extent of trace element removal, effect of particle size and effect of dewatering under heavy and light oils. Lignites from three areas of Canada (Estevan and Coronach, Saskatchewan, and Onakawana, Ontario) and one peat sample (Garrick, Saskatchewan) were thermally dewatered. The equilibrium moisture values obtained for the dewatered products were as low as, or lower than those obtained in Phases I and II of this project (350 degrees C). However, the measured moisture contents of the thermally dewatered Saskatchewan lignites were somewhat higher than those measured in Phases I and II. The equilibrium moisture values and the moisture contents decreased with increasing temperature. An optimum balance between extent of dewatering and resulting steam pressures is obtained for a dewatering temperature between 300 and 350 degrees C. At these temperatures, residence times in the order of 15 minutes are required. (35 refs.)

  19. The role of technology in reducing health care costs. Phase II and phase III.

    Energy Technology Data Exchange (ETDEWEB)

    Cilke, John F.; Parks, Raymond C.; Funkhouser, Donald Ray; Tebo, Michael A.; Murphy, Martin D.; Hightower, Marion Michael; Gallagher, Linda K.; Craft, Richard Layne, II; Garcia, Rudy John

    2004-04-01

    In Phase I of this project, reported in SAND97-1922, Sandia National Laboratories applied a systems approach to identifying innovative biomedical technologies with the potential to reduce U.S. health care delivery costs while maintaining care quality. The effort provided roadmaps for the development and integration of technology to meet perceived care delivery requirements and an economic analysis model for development of care pathway costs for two conditions: coronary artery disease (CAD) and benign prostatic hypertrophy (BPH). Phases II and III of this project, which are presented in this report, were directed at detailing the parameters of telemedicine that influence care delivery costs and quality. These results were used to identify and field test the communication, interoperability, and security capabilities needed for cost-effective, secure, and reliable health care via telemedicine.

  20. Neutral bidentate N-heterocyclic ligands - phase transfer reagents improving the kinetics of solvent extraction of Am(III) and Eu(III) ions with tetradentate 6,6'-bis-(diethyl-1,2,4-triazin-3-yl)-2,2'-bipyridine

    International Nuclear Information System (INIS)

    Narbutt, J.; Krejzler, J.

    2008-01-01

    Poor kinetics of solvent extraction of Am(III) and Eu(III) ions from 1 M HNO 3 with 6,6'-bis-(diethyl-1,2,4-triazin-3-yl)-2,2'-bipyridine (etBTBP) has been improved by adding an auxiliary bidentate N-heterocyclic ligand to the extraction system. Two such ligands were studied, derivatives of bis-triazine and pyridine-triazine, which alone poorly extract the metal ions, but together with etBTBP they act as phase transfer reagents, improving the extraction kinetics to a different degree. The ability to transfer the metal ions from aqueous to organic phase depends on lipophilicity and acid/base properties of these auxiliary ligands, as well as on the mode of shaking the two liquid phases - gentle or vigorous. (orig.)

  1. Comprehensive Evaluation of the Geothermal Resource Potential within the Pyramid Lake Paiute Reservation Phase III Report

    Energy Technology Data Exchange (ETDEWEB)

    Noel, Donna [Pyramid Lake Paiute Tribe, Nixon, NV (United States)

    2013-12-01

    This project integrated state-of-the-art exploration technologies with a geologic framework and reservoir modeling to ultimately determine the efficacy of future geothermal production within the PLPT reservation. The information gained during this study should help the PLPT to make informed decisions regarding construction of a geothermal power plant. Additional benefits included the transfer of new technologies and geothermal data to the geothermal industry and it created and/or preserved nearly three dozen jobs accordance with the American Recovery and Reinvestment Act of 2009. A variety of tasks were conducted to achieve the above stated objectives. The following are the tasks completed within the project: 1. Permitting 2. Shallow temperature survey 3. Seismic data collection and analysis 4. Fracture stress analysis 5. Phase I reporting Permitting 7. Shallow temperature survey 8. Seismic data collection and analysis 9. Fracture stress analysis 10. Phase I reporting 11. Drilling two new wells 12. Borehole geophysics 13. Phase II reporting 14. Well testing and geochemical analysis 15. Three-dimensional geologic model 16. Three-dimensional reservoir analysis 17. Reservation wide geothermal potential analysis 18. Phase III reporting Phase I consisted of tasks 1 – 5, Phase II tasks 6 – 8, and Phase III tasks 9 – 13. This report details the results of Phase III tasks. Reports are available for Phase I, and II as separate documents.

  2. DECOVALEX - Mathematical models of coupled T-H-M processes for nuclear waste repositories. Report of phase III

    International Nuclear Information System (INIS)

    Jing, L.; Rutqvist, J.; Stephansson, O.

    1995-12-01

    This report presents the methodologies and results of the field/laboratory experiments and mathematical modeling defined for the phase III of the project. Results from test cases 2-6 are given in separate chapters of the report (which have been indexed separately), and the last chapter discusses the lessons learned from the three phases of the DECOVALEX project

  3. Hydrogeological characterization on surface-based investigation phase in the Mizunami underground research laboratory project, in Japan

    International Nuclear Information System (INIS)

    Saegusa, Hiromitsu; Onoe, Hironori; Takeuchi, Shinji; Takeuchi, Ryuji; Ohyama, Takuya

    2007-01-01

    The Mizunami Underground Research Laboratory (MIU) project is being carried out by Japan Atomic Energy Agency in the Cretaceous Toki granite in the Tono area, central Japan. The MIU project is a purpose-built generic underground research laboratory project that is planned for a broad scientific study of the deep geological environment as a basis of research and development for geological disposal of nuclear wastes. One of the main goals of the MIU project is to establish comprehensive techniques for investigation, analysis, and assessment of the deep geological environment. The MIU project has three overlapping phases: Surface-based Investigation (Phase I), Construction (Phase II) and Operation (Phase III). Hydrogeological investigations using a stepwise process in Phase I have been carried out in order to obtain information on important properties such as, location of water conducting features, hydraulic conductivity and so on. Hydrogeological modeling and groundwater flow simulations in Phase I have been carried out in order to synthesize these investigation results, to evaluate the uncertainty of the hydrogeological model and to identify the main issues for further investigations. Using the stepwise hydrogeological characterization approach and combining the investigation with modeling and simulation, understanding of the hydrogeological environment has been progressively improved. (authors)

  4. Breckinridge Project, initial effort. Report III, Volume 2. Specifications

    Energy Technology Data Exchange (ETDEWEB)

    None

    1982-01-01

    Report III, Volume 2 contains those specifications numbered K through Y, as follows: Specifications for Compressors (K); Specifications for Piping (L); Specifications for Structures (M); Specifications for Insulation (N); Specifications for Electrical (P); Specifications for Concrete (Q); Specifications for Civil (S); Specifications for Welding (W); Specifications for Painting (X); and Specifications for Special (Y). The standard specifications of Bechtel Petroleum Incorporated have been amended as necessary to reflect the specific requirements of the Breckinridge Project and the more stringent specifications of Ashland Synthetic Fuels, Inc. These standard specifications are available for the Initial Effort (Phase Zero) work performed by all contractors and subcontractors.

  5. Yakima Basin Fish Passage Project, Phase 2

    International Nuclear Information System (INIS)

    1991-08-01

    Implementation of the Yakima Basin Fish Passage Project -- Phase 2 would significantly improve the production of anadromous fish in the Yakima River system. The project would provide offsite mitigation and help to compensate for lower Columbia River hydroelectric fishery losses. The Phase 2 screens would allow greater numbers of juvenile anadromous fish to survive. As a consequence, there would be higher returns of adult salmon and steelhead to the Yakima River. The proposed action would play an integral part in the overall Yakima River anadromous fish enhancement program (fish passage improvement, habitat enhancement, hatchery production increases, and harvest management). These would be environmental benefits associated with implementation of the Fish Passage and Protective Facilities Phase 2 Project. Based on the evaluation presented in this assessment, there would be no significant adverse environmental impacts if the proposed action was carried forward. No significant adverse environmental effects have been identified from construction and operation of the Yakima Phase 2 fish passage project. Proper design and implementation of the project will ensure no adverse effects will occur. Based on the information in this environmental analysis, BPA's and Reclamation's proposal to construct these facilities does not constitute a major Federal action that could significantly affect the quality of the human environment. 8 refs., 4 figs., 6 tabs

  6. Unraveling the Mystery of the Blue Fog: Structure, Properties, and Applications of Amorphous Blue Phase III.

    Science.gov (United States)

    Gandhi, Sahil Sandesh; Chien, Liang-Chy

    2017-12-01

    The amorphous blue phase III of cholesteric liquid crystals, also known as the "blue fog," are among the rising stars in materials science that can potentially be used to develop next-generation displays with the ability to compete toe-to-toe with disruptive technologies like organic light-emitting diodes. The structure and properties of the practically unobservable blue phase III have eluded scientists for more than a century since it was discovered. This progress report reviews the developments in this field from both fundamental and applied research perspectives. The first part of this progress report gives an overview of the 130-years-long scientific tour-de-force that very recently resulted in the revelation of the mysterious structure of blue phase III. The second part reviews progress made in the past decade in developing electrooptical, optical, and photonic devices based on blue phase III. The strong and weak aspects of the development of these devices are underlined and criticized, respectively. The third- and-final part proposes ideas for further improvement in blue phase III technology to make it feasible for commercialization and widespread use. © 2017 WILEY-VCH Verlag GmbH & Co. KGaA, Weinheim.

  7. PandaX-III: Searching for neutrinoless double beta decay with high pressure 136Xe gas time projection chambers

    Science.gov (United States)

    Chen, Xun; Fu, ChangBo; Galan, Javier; Giboni, Karl; Giuliani, Franco; Gu, LingHui; Han, Ke; Ji, XiangDong; Lin, Heng; Liu, JiangLai; Ni, KaiXiang; Kusano, Hiroki; Ren, XiangXiang; Wang, ShaoBo; Yang, Yong; Zhang, Dan; Zhang, Tao; Zhao, Li; Sun, XiangMing; Hu, ShouYang; Jian, SiYu; Li, XingLong; Li, XiaoMei; Liang, Hao; Zhang, HuanQiao; Zhao, MingRui; Zhou, Jing; Mao, YaJun; Qiao, Hao; Wang, SiGuang; Yuan, Ying; Wang, Meng; Khan, Amir N.; Raper, Neill; Tang, Jian; Wang, Wei; Dong, JiaNing; Feng, ChangQing; Li, Cheng; Liu, JianBei; Liu, ShuBin; Wang, XiaoLian; Zhu, DanYang; Castel, Juan F.; Cebrián, Susana; Dafni, Theopisti; Garza, Javier G.; Irastorza, Igor G.; Iguaz, Francisco J.; Luzón, Gloria; Mirallas, Hector; Aune, Stephan; Berthoumieux, Eric; Bedfer, Yann; Calvet, Denis; d'Hose, Nicole; Delbart, Alain; Diakaki, Maria; Ferrer-Ribas, Esther; Ferrero, Andrea; Kunne, Fabienne; Neyret, Damien; Papaevangelou, Thomas; Sabatié, Franck; Vanderbroucke, Maxence; Tan, AnDi; Haxton, Wick; Mei, Yuan; Kobdaj, Chinorat; Yan, Yu-Peng

    2017-06-01

    Searching for the neutrinoless double beta decay (NLDBD) is now regarded as the topmost promising technique to explore the nature of neutrinos after the discovery of neutrino masses in oscillation experiments. PandaX-III (particle and astrophysical xenon experiment III) will search for the NLDBD of 136Xe at the China Jin Ping Underground Laboratory (CJPL). In the first phase of the experiment, a high pressure gas Time Projection Chamber (TPC) will contain 200 kg, 90% 136Xe enriched gas operated at 10 bar. Fine pitch micro-pattern gas detector (Microbulk Micromegas) will be used at both ends of the TPC for the charge readout with a cathode in the middle. Charge signals can be used to reconstruct the electron tracks of the NLDBD events and provide good energy and spatial resolution. The detector will be immersed in a large water tank to ensure 5 m of water shielding in all directions. The second phase, a ton-scale experiment, will consist of five TPCs in the same water tank, with improved energy resolution and better control over backgrounds.

  8. Managing project complexity : A study into adapting early project phases to improve project performance in large engineering projects

    NARCIS (Netherlands)

    Bosch-Rekveldt, M.G.C.

    2011-01-01

    Engineering projects become increasingly more complex and project complexity is assumed to be one of the causes for projects being delivered late and over budget. However, what this project complexity actually comprised of was unclear. To improve the overall project performance, this study focuses

  9. Los Angeles International Airport Runway Incursion Studies: Phase III--Center-Taxiway Simulation

    Science.gov (United States)

    Madson, Michael D.

    2004-01-01

    Phase III of the Los Angeles International Airport Runway Incursion Studies was conducted, under an agreement with HNTB Corporation, at the NASA Ames FutureFlight Central (FFC) facility in June 2003. The objective of the study was the evaluation of a new center-taxiway concept at LAX. This study is an extension of the Phase I and Phase II studies previously conducted at FFC. This report presents results from Phase III of the study, in which a center-taxiway concept between runways 25L and 25R was simulated and evaluated. Phase III data were compared objectively against the Baseline data. Subjective evaluations by participating LAX controllers were obtained with regard to workload, efficiency, and safety criteria. To facilitate a valid comparison between Baseline and Phase III data, the same scenarios were used for Phase III that were tested during Phases I and II. This required briefing participating controllers on differences in airport and airline operations between 2001 and today.

  10. The Lunar Phases Project: A Mental Model-Based Observational Project for Undergraduate Nonscience Majors

    Science.gov (United States)

    Meyer, Angela Osterman; Mon, Manuel J.; Hibbard, Susan T.

    2011-01-01

    We present our Lunar Phases Project, an ongoing effort utilizing students' actual observations within a mental model building framework to improve student understanding of the causes and process of the lunar phases. We implement this project with a sample of undergraduate, nonscience major students enrolled in a midsized public university located…

  11. Objectives and methodology of BIOBADASER phase iii.

    Science.gov (United States)

    Sanchez-Piedra, Carlos; Hernández Miguel, M Victoria; Manero, Javier; Roselló, Rosa; Sánchez-Costa, Jesús Tomás; Rodríguez-Lozano, Carlos; Campos, Cristina; Cuende, Eduardo; Fernández-Lopez, Jesús Carlos; Bustabad, Sagrario; Martín Domenech, Raquel; Pérez-Pampín, Eva; Del Pino-Montes, Javier; Millan-Arcineas, Ana Milena; Díaz-González, Federico; Gómez-Reino, Juan Jesús

    2017-09-18

    Describe the objectives, methods and results of the first year of the new version of the Spanish registry of adverse events involving biological therapies and synthetic drugs with an identifiable target in rheumatic diseases (BIOBADASER III). Multicenter prospective registry of patients with rheumatic inflammatory diseases being treated with biological drugs or synthetic drugs with an identifiable target in rheumatology departments in Spain. The main objective of BIOBADASER Phase III is the registry and analysis of adverse events; moreover, a secondary objective was added consisting of assessing the effectiveness by means of the registry of activity indexes. Patients in the registry are evaluated at least once every year and whenever they experience an adverse event or a change in treatment. The collection of data for phase iii began on 17 December 2015. During the first year, 35 centers participated. The number of patients included in this new phase in December 2016 was 2,664. The mean age was 53.7 years and the median duration of treatment was 8.1 years. In all, 40.4% of the patients were diagnosed with rheumatoid arthritis. The most frequent adverse events were infections and infestations. BIOBADASER Phase III has been launched to adapt to a changing pharmacological environment, with the introduction of biosimilars and small molecules in the treatment of rheumatic diseases. This new stage is adapted to the changes in the reporting of adverse events and now includes information related to activity scores. Copyright © 2017 Elsevier España, S.L.U. and Sociedad Española de Reumatología y Colegio Mexicano de Reumatología. All rights reserved.

  12. Two-phase titration of cerium(III) by permanganate

    International Nuclear Information System (INIS)

    Lazarev, A.I.; Lazareva, V.I.; Gerko, V.V.

    1987-01-01

    This paper presents a method for the two-phase titrimetric determination of cerium(III) with permanganate which does not require an expenditure of sugar and preliminary removal of chlorides and nitrates. The interaction of cerium(III) with permanganate at room temperature was studied as a function of the pH, the concentration of pyrophosphate, tetraphenylphosphonium (TPP), permanganate, and extraneous compounds, the rate of titration, and the time of stay of the solution in air before titration. The investigations were conducted according to the following methodology: water, solution of cerium(III) pyrophosphate, and TPP were introduced into an Erlenmeyer flask with a side branch near the bottom for clearer observation of the color of the chloroform phase. The authors established the given pH value, poured the water into a volume of 50 ml, and added chloroform. The result was titrated with permanganate solutions of various concentrations until a violet color appeared in the chloroform phase

  13. Sears Point Tidal Marsh Restoration Project: Phase I

    Science.gov (United States)

    Information about the SFBWQP Sears Point Tidal Marsh Restoration Project: Phase I project, part of an EPA competitive grant program to improve SF Bay water quality focused on restoring impaired waters and enhancing aquatic resources.

  14. Methods for improved growth of group III nitride buffer layers

    Science.gov (United States)

    Melnik, Yurity; Chen, Lu; Kojiri, Hidehiro

    2014-07-15

    Methods are disclosed for growing high crystal quality group III-nitride epitaxial layers with advanced multiple buffer layer techniques. In an embodiment, a method includes forming group III-nitride buffer layers that contain aluminum on suitable substrate in a processing chamber of a hydride vapor phase epitaxy processing system. A hydrogen halide or halogen gas is flowing into the growth zone during deposition of buffer layers to suppress homogeneous particle formation. Some combinations of low temperature buffers that contain aluminum (e.g., AlN, AlGaN) and high temperature buffers that contain aluminum (e.g., AlN, AlGaN) may be used to improve crystal quality and morphology of subsequently grown group III-nitride epitaxial layers. The buffer may be deposited on the substrate, or on the surface of another buffer. The additional buffer layers may be added as interlayers in group III-nitride layers (e.g., GaN, AlGaN, AlN).

  15. TA 55 Reinvestment Project II Phase C Update Project Status May 23, 2017

    Energy Technology Data Exchange (ETDEWEB)

    Giordano, Anthony P. [Los Alamos National Lab. (LANL), Los Alamos, NM (United States)

    2017-05-25

    The TA-55 Reinvestment Project (TRP) II Phase C is a critical infrastructure project focused on improving safety and reliability of the Los Alamos National Laboratory (LANL) TA-55 Complex. The Project recapitalizes and revitalizes aging and obsolete facility and safety systems providing a sustainable nuclear facility for National Security Missions.

  16. Improving decision making in the early phases of configuration projects

    DEFF Research Database (Denmark)

    Mortensen, Niels Henrik; Harlou, Ulf; Haug, Anders

    2008-01-01

    During the early phases of configuration projects very important decisions are made which will heavily influence the performance of the company, benefits in different functional areas (production, sales, purchase, product development, service etc), maintenance of the configuration system...

  17. Improving decision making in the early phases of configuration projects

    DEFF Research Database (Denmark)

    Mortensen, Niels Henrik; Hvam, Lars; Harlou, Ulf

    2011-01-01

    During the early phases of configuration projects very important decisions are made which will heavily influence the performance of the company, benefits in different functional areas (production, sales, purchase, product development, service etc), maintenance of the configuration system...

  18. Perceived Benefits of National Fadama Development Project III ...

    African Journals Online (AJOL)

    The study was conducted to appraise the perceived benefits of third national fadama development project III among rural farmers in Kwara state, Nigeria. A multi-stage random sampling technique was employed in selecting 225 Fadama III users as respondents. Data were collected by well trained fadama community ...

  19. Lake Roosevelt Rainbow Trout Habitat/Passage Improvement Project, Annual Report 2002-2003.

    Energy Technology Data Exchange (ETDEWEB)

    Sears, Sheryl

    2004-01-01

    Tribes (CCT), Spokane Tribe of Indians (STI) and Washington Department of Fish and Wildlife (WDFW) to develop and propose a comprehensive fishery management plan for Lake Roosevelt. The Rainbow Trout Habitat/Passage Improvement Project (LRHIP) was designed with goals directed towards increasing natural production while maintaining genetic integrity among current tributary stocks. The initial phase of the Lake Roosevelt Habitat Improvement Project (Phase I, baseline data collection: 1990-91) was focused on the assessment of limiting factors, including the quality and quantity of available spawning gravel, identification of passage barriers, and assessment of other constraints. After the initial assessment of stream parameters, five streams meeting specific criteria were selected for habitat/passage improvement projects (Phase II, implementation -1992-1995). Four of these projects were on the Colville Indian Reservation South Nanamkin, North Nanamkin, Louie and Iron Creeks and one Blue Creek was on the Spokane Indian Reservation. At the completion of project habitat improvements, the final phase (Phase III, monitoring-1996-2000) began. This phase assessed the changes and determined the success achieved through the improvements. Data analysis showed that passage improvements are successful for increasing habitat availability and use. The results of in-stream habitat improvements were inconclusive. Project streams, to the last monitoring date, have shown increases in fish density following implementation of the improvements. In 2000 Bridge Creek, on the Colville Reservation was selected for the next phase of improvements. Data collection, including baseline stream survey and population data collection, was carried out during 2001 in preparation for the design and implementation of stream habitat/passage improvements. Agencies cooperating on the project include the Colville Confederated Tribes (CCT), Natural Resource Conservation Service (NRCS, Ferry County District), Ferry

  20. Lake Roosevelt Rainbow Trout Habitat/Passage Improvement Project, Annual Report 2001-2002.

    Energy Technology Data Exchange (ETDEWEB)

    Sears, Sheryl

    2003-01-01

    Tribes (CCT), Spokane Tribe of Indians (STI) and Washington Department of Fish and Wildlife (WDFW) to develop and propose a comprehensive fishery management plan for Lake Roosevelt. The Rainbow Trout Habitat/Passage Improvement Project (LRHIP) was designed with goals directed towards increasing natural production while maintaining genetic integrity among current tributary stocks. The initial phase of the Lake Roosevelt Habitat Improvement Project (Phase I, baseline data collection: 1990-91) was focused on the assessment of limiting factors, including the quality and quantity of available spawning gravel, identification of passage barriers, and assessment of other constraints. After the initial assessment of stream parameters, five streams meeting specific criteria were selected for habitat/passage improvement projects (Phase II, implementation -1992-1995). Four of these projects were on the Colville Indian Reservation South Nanamkin, North Nanamkin, Louie and Iron Creeks and one Blue Creek was on the Spokane Indian Reservation. At the completion of project habitat improvements, the final phase (Phase III, monitoring-1996-2000) began. This phase assessed the changes and determined the success achieved through the improvements. Data analysis showed that passage improvements are successful for increasing habitat availability and use. The results of in-stream habitat improvements were inconclusive. Project streams, to the last monitoring date, have shown increases in fish density following implementation of the improvements. In 2000 Bridge Creek, on the Colville Reservation was selected for the next phase of improvements. Data collection, including baseline stream survey and population data collection, was carried out during 2001 in preparation for the design and implementation of stream habitat/passage improvements. Agencies cooperating on the project include the Colville Confederated Tribes (CCT), Natural Resource Conservation Service (NRCS, Ferry County District), Ferry

  1. Horonobe Underground Research Laboratory project. Synthesis of phase II (construction phase) investigations to a depth of 350 m

    International Nuclear Information System (INIS)

    Sato, Toshinori; Sasamoto, Hiroshi; Ishii, Eiichi; Matsuoka, Toshiyuki; Hayano, Akira; Miyakawa, Kazuya; Fujita, Tomoo; Tanai, Kenji; Nakayama, Masashi; Takeda, Masaki; Yokota, Hideharu; Aoyagi, Kazuhei; Ohno, Hirokazu; Shigeta, Naotaka; Hanamuro, Takahiro; Ito, Hiroaki

    2017-03-01

    The Horonobe Underground Research Laboratory (URL) Project is being pursued by the Japan Atomic Energy Agency (JAEA) to enhance the reliability of relevant disposal technologies through investigations of the deep geological environment within the host sedimentary formations at Horonobe, northern Hokkaido. The project consists of two major research areas, 'Geoscientific Research' and 'R and D on Geological Disposal', and proceeds in three overlapping phases, 'Phase I: Surface-based investigation', 'Phase II: Construction' and 'Phase III: Operation', over a period of 20 years. This report summarizes the results of the Phase II investigations carried out from April 2005 to June 2014 to a depth of 350 m. Integration of work from different disciplines into a 'geosynthesis' ensures that the Phase II goals have been successfully achieved and identifies key issues that need to be addressed in the Phase II investigations. Efforts are made to summarize as many lessons learnt from the Phase II investigations and other technical achievements as possible to form a 'knowledge base' that will reinforce the technical basis for both implementation and the formulation of safety regulations. (author)

  2. CONVERSION EXTRACTION DESULFURIZATION (CED) PHASE III

    Energy Technology Data Exchange (ETDEWEB)

    James Boltz

    2005-03-01

    This project was undertaken to refine the Conversion Extraction Desulfurization (CED) technology to efficiently and economically remove sulfur from diesel fuel to levels below 15-ppm. CED is considered a generic term covering all desulfurization processes that involve oxidation and extraction. The CED process first extracts a fraction of the sulfur from the diesel, then selectively oxidizes the remaining sulfur compounds, and finally extracts these oxidized materials. The Department of Energy (DOE) awarded Petro Star Inc. a contract to fund Phase III of the CED process development. Phase III consisted of testing a continuous-flow process, optimization of the process steps, design of a pilot plant, and completion of a market study for licensing the process. Petro Star and the Degussa Corporation in coordination with Koch Modular Process Systems (KMPS) tested six key process steps in a 7.6-centimeter (cm) (3.0-inch) inside diameter (ID) column at gas oil feed rates of 7.8 to 93.3 liters per hour (l/h) (2.1 to 24.6 gallons per hour). The team verified the technical feasibility with respect to hydraulics for each unit operation tested and successfully demonstrated pre-extraction and solvent recovery distillation. Test operations conducted at KMPS demonstrated that the oxidation reaction converted a maximum of 97% of the thiophenes. The CED Process Development Team demonstrated that CED technology is capable of reducing the sulfur content of light atmospheric gas oil from 5,000-ppm to less than 15-ppm within the laboratory scale. In continuous flow trials, the CED process consistently produced fuel with approximately 20-ppm of sulfur. The process economics study calculated an estimated process cost of $5.70 per product barrel. The Kline Company performed a marketing study to evaluate the possibility of licensing the CED technology. Kline concluded that only 13 refineries harbored opportunity for the CED process. The Kline study and the research team's discussions

  3. Analysis of gas-liquid metal two-phase flows using a reactor safety analysis code SIMMER-III

    International Nuclear Information System (INIS)

    Suzuki, Tohru; Tobita, Yoshiharu; Kondo, Satoru; Saito, Yasushi; Mishima, Kaichiro

    2003-01-01

    SIMMER-III, a safety analysis code for liquid-metal fast reactors (LMFRs), includes a momentum exchange model based on conventional correlations for ordinary gas-liquid flows, such as an air-water system. From the viewpoint of safety evaluation of core disruptive accidents (CDAs) in LMFRs, we need to confirm that the code can predict the two-phase flow behaviors with high liquid-to-gas density ratios formed during a CDA. In the present study, the momentum exchange model of SIMMER-III was assessed and improved using experimental data of two-phase flows containing liquid metal, on which fundamental information, such as bubble shapes, void fractions and velocity fields, has been lacking. It was found that the original SIMMER-III can suitably represent high liquid-to-gas density ratio flows including ellipsoidal bubbles as seen in lower gas fluxes. In addition, the employment of Kataoka-Ishii's correlation has improved the accuracy of SIMMER-III for gas-liquid metal flows with cap-shape bubbles as identified in higher gas fluxes. Moreover, a new procedure, in which an appropriate drag coefficient can be automatically selected according to bubble shape, was developed. Through this work, the reliability and the precision of SIMMER-III have been much raised with regard to bubbly flows for various liquid-to-gas density ratios

  4. Assessment Of Various Activities Indicators Made Available To Farmers For Participation Through Fadama Iii Agricultural Project Delivery Agency In Bayelsa State Nigeria

    Directory of Open Access Journals (Sweden)

    Ominikari

    2017-09-01

    Full Text Available The study assessed the activities made available to farmers for participation through Fadama III Project in Bayelsa State. Objective of the study was activities made available to farmers through National Fadama III Agricultural project delivery agency. Purposive sampling technique was used to select One-Hundred and fifty 150 farmers that participated and 150 staff from the delivery agency. Data were collected with a structured questionnaire. The data collected was analyzed using frequency count percentage mean X amp773 standard deviation STD while z-test was used to test the null hypotheses at 0.05 level of significance. Farmers in the state truly believe in the existence of various activities in Fadama III project in the state as being made available to them through the delivery agency. The result of the z-test showed that the mean response of the farmers in Fadama III projects was 2.986 while the mean response of the delivery agency was 3.793 there was significant difference z -20.245 in the mean score response of the delivery agency and participants of National Fadama III Agricultural Project on the various activities that were made available to the farmers at P amp8804 0.05. The study therefore recommended that National Fadama III Project activities should be reorganized to be of great benefit to the farmers proper training in all the activities should be made available for effective participation empower the participants to improve their income level and to move them away from poverty by improving their standard of living by reorganizing the Fadama III Project.

  5. Probability of success for phase III after exploratory biomarker analysis in phase II.

    Science.gov (United States)

    Götte, Heiko; Kirchner, Marietta; Sailer, Martin Oliver

    2017-05-01

    The probability of success or average power describes the potential of a future trial by weighting the power with a probability distribution of the treatment effect. The treatment effect estimate from a previous trial can be used to define such a distribution. During the development of targeted therapies, it is common practice to look for predictive biomarkers. The consequence is that the trial population for phase III is often selected on the basis of the most extreme result from phase II biomarker subgroup analyses. In such a case, there is a tendency to overestimate the treatment effect. We investigate whether the overestimation of the treatment effect estimate from phase II is transformed into a positive bias for the probability of success for phase III. We simulate a phase II/III development program for targeted therapies. This simulation allows to investigate selection probabilities and allows to compare the estimated with the true probability of success. We consider the estimated probability of success with and without subgroup selection. Depending on the true treatment effects, there is a negative bias without selection because of the weighting by the phase II distribution. In comparison, selection increases the estimated probability of success. Thus, selection does not lead to a bias in probability of success if underestimation due to the phase II distribution and overestimation due to selection cancel each other out. We recommend to perform similar simulations in practice to get the necessary information about the risk and chances associated with such subgroup selection designs. Copyright © 2017 John Wiley & Sons, Ltd.

  6. FY 1991 project plan for the Hanford Environmental Dose Reconstruction Project, Phase 2

    International Nuclear Information System (INIS)

    1991-02-01

    Phase 1 of the Hanford Environmental Dose Reconstruction Project was designed to develop and demonstrate a method for estimating radiation doses people may have received from Hanford Site operations since 1944. The method researchers developed relied on a variety of measured and reconstructed data as input to a modular computer model that generates dose estimates and their uncertainties. As part of Phase 1, researchers used the reconstructed data and computer model to calculate preliminary dose estimates for populations in a limited geographical area and time period. Phase 2, now under way, is designed to evaluate the Phase 1 data and model and improve them to calculate more accurate and precise dose estimates. Phase 2 will also be used to obtain preliminary estimates of two categories of doses: for Native American tribes and for individuals included in the pilot phase of the Hanford Thyroid Disease Study (HTDS). TSP Directive 90-1 required HEDR staff to develop Phase 2 task plans for TSP approval. Draft task plans for Phase 2 were submitted to the TSP at the October 11--12, 1990 public meeting, and, after discussions of each activity and associated budget needs, the TSP directed HEDR staff to proceed with a slate of specific project activities for FY 1991 of Phase 2. This project plan contains detailed information about those activities. Phase 2 is expected to last 15--18 months. In mid-FY 1991, project activities and budget will be reevaluated to determine whether technical needs or priorities have changed. Separate from, but related to, this project plan, will be an integrated plan for the remainder of the project. HEDR staff will work with the TSP to map out a strategy that clearly describes ''end products'' for the project and the work necessary to complete them. This level of planning will provide a framework within which project decisions in Phases 2, 3, and 4 can be made

  7. Sample exchange/evaluation (SEE) report - Phase III

    International Nuclear Information System (INIS)

    Winters, W.I.

    1996-01-01

    This report describes the results from Phase III of the Sample Exchange Evaluation (SEE) program. The SEE program is used to compare analytical laboratory performance on samples from the Hanford Site's high level waste tanks

  8. Joint probability of statistical success of multiple phase III trials.

    Science.gov (United States)

    Zhang, Jianliang; Zhang, Jenny J

    2013-01-01

    In drug development, after completion of phase II proof-of-concept trials, the sponsor needs to make a go/no-go decision to start expensive phase III trials. The probability of statistical success (PoSS) of the phase III trials based on data from earlier studies is an important factor in that decision-making process. Instead of statistical power, the predictive power of a phase III trial, which takes into account the uncertainty in the estimation of treatment effect from earlier studies, has been proposed to evaluate the PoSS of a single trial. However, regulatory authorities generally require statistical significance in two (or more) trials for marketing licensure. We show that the predictive statistics of two future trials are statistically correlated through use of the common observed data from earlier studies. Thus, the joint predictive power should not be evaluated as a simplistic product of the predictive powers of the individual trials. We develop the relevant formulae for the appropriate evaluation of the joint predictive power and provide numerical examples. Our methodology is further extended to the more complex phase III development scenario comprising more than two (K > 2) trials, that is, the evaluation of the PoSS of at least k₀ (k₀≤ K) trials from a program of K total trials. Copyright © 2013 John Wiley & Sons, Ltd.

  9. A quality assurance audit: phase III trial of maximal androgen deprivation in prostate cancer (TROG 96.01).

    Science.gov (United States)

    Steigler, A; Mameghan, H; Lamb, D; Joseph, D; Matthews, J; Franklin, I; Turner, S; Spry, N; Poulsen, M; North, J; Kovacev, O; Denham, J

    2000-02-01

    In 1997 the Trans-Tasman Radiation Oncology Group (TROG) performed a quality assurance (QA) audit of its phase III randomized clinical trial investigating the effectiveness of different durations of maximal androgen deprivation prior to and during definitive radiation therapy for locally advanced carcinoma of the prostate (TROG 96.01). The audit reviewed a total of 60 cases from 15 centres across Australia and New Zealand. In addition to verification of technical adherence to the protocol, the audit also incorporated a survey of centre planning techniques and a QA time/cost analysis. The present report builds on TROG's first technical audit conducted in 1996 for the phase III accelerated head and neck trial (TROG 91.01) and highlights the significant progress TROG has made in the interim period. The audit provides a strong validation of the results of the 96.01 trial, as well as valuable budgeting and treatment planning information for future trials. Overall improvements were detected in data quality and quantity, and in protocol compliance, with a reduction in the rate of unacceptable protocol violations from 10 to 4%. Audit design, staff education and increased data management resources were identified as the main contributing factors to these improvements. In addition, a budget estimate of $100 per patient has been proposed for conducting similar technical audits. The next major QA project to be undertaken by TROG during the period 1998-1999 is an intercentre dosimetry study. Trial funding and staff education have been targeted as the key major issues essential to the continued success and expansion of TROG's QA programme.

  10. 75 FR 38645 - Standards Improvement Project-Phase III

    Science.gov (United States)

    2010-07-02

    ... every working man and woman in the Nation safe and healthful working conditions and to preserve our... Textile Mfrs. Institute v. OSHA, 452 U.S. 490, 513 (1981) (ATMI); American Iron and Steel Institute v... chemicals. Instead, OSHA required half-mask particulate-filter respirators for the 13 carcinogens, which are...

  11. 76 FR 33589 - Standards Improvement Project-Phase III

    Science.gov (United States)

    2011-06-08

    ... every working man and woman in the Nation safe and healthful working conditions and to preserve our... develop. (See American Textile Mfrs. Institute v. OSHA, 452 U.S. 490, 513 (1981) (ATMI); American Iron and...-air respirators with a requirement to use half-mask particulate-filter respirators for the 13...

  12. Electronic construction collaboration system : phase III.

    Science.gov (United States)

    2011-12-01

    This phase of the electronic collaboration project involved two major efforts: 1) implementation of AEC Sync (formerly known as Attolist), a web-based project management system (WPMS), on the Broadway Viaduct Bridge Project and the Iowa Falls Arch Br...

  13. Improved gas installations and services. Phase 1: Analysis project. Part report

    International Nuclear Information System (INIS)

    Nielsen, K.J.

    1996-05-01

    As Danish gas companies receive a large number of complaints related to the installation and operation of gas installations it was suggested that a course for personnel should be established in order to raise the standard of services and installation requirements. The first phase of the described project was to evaluate the quality of the gas installers' services so as to determine which aspects of installation and services should be emphasized during such a course. Interviews were carried out and questionnaires (illustrated within the document) sent out to installaters etc. Recommendations include that the level of information given to customers should be raised, also in relation to maintenance, and that installation should be improved. Analyses of the degree of customers' satisfaction, of the nature of the quality of services etc. expected, subjects for further training in this area and details of the training system are dealt with

  14. Decontamination and decommissioning project status of the TRIGA Mark II and III in Korea

    International Nuclear Information System (INIS)

    Paik, S.T.; Park, S.K.; Chung, K.W.; Chung, U.S.; Jung, K.J.

    1999-01-01

    TRIGA Mark-II, the first research reactor in Korea, has operated since 1962, and the second one, TRIGA Mark-III since 1972. Both of them had their operation phased out in 1995 due to their lives and operation of the new research reactor, HANARO (High-flux Advanced Neutron Application Reactor) at the Korea Atomic Energy Institute (KAERI) in Taejon. Decontamination and decommissioning (D and D) project of TRIGA Mark-II and Mark-III was started in January 1997 and will be completed in December 2002. The first year of the project, work was performed in preparation of the decommissioning plan, start of the environmental impact assessment and setup licensing procedure and documentation for the project with cooperation of Korea Institute of Nuclear Safety (KINS). Hyundai Engineering Company (HEC) is the main contractor to do design and licensing documentation for the D and D of both reactors. British Nuclear Fuels plc (BNFL) is the technical assisting partner of HEC. The decommissioning plan document was submitted to the Ministry of Since and Technology (MOST) for the decommissioning license in December 1998, and it expecting to be issued a license in mid 1999. The goal of this project is to release the reactor site and buildings as an unrestricted area. This paper summarizes current status and future plan for the D and D project. (author)

  15. SELENIUM TREATMENT/REMOVAL ALTERNATIVES DEMONSTRATION PROJECT - MINE WASTE TECHNOLOGY PROGRAM ACTIVITY III, PROJECT 20

    Science.gov (United States)

    This document is the final report for EPA's Mine WAste Technology Program (MWTP) Activity III, Project 20--Selenium Treatment/Removal Alternatives Demonstration project. Selenium contamination originates from many sources including mining operations, mineral processing, abandoned...

  16. Motivation and participation in a phase III cardiac rehabilitation programme: an application of the health action process approach.

    Science.gov (United States)

    Dohnke, Birte; Nowossadeck, Enno; Müller-Fahrnow, Werner

    2010-10-01

    This longitudinal study extends the previous research on low participation rates and high dropout rates in phase III cardiac rehabilitation (CR) exercise programmes. It examines the correlates of motivation and participation 6 months after inpatient phase II CR (T1) and the predictors of dropout 6 months later (T2) using the health action process approach (HAPA). Risk perception, outcome expectancies, self-efficacy, intention (at T1), and participation (at T1 and T2) in relation to phase III CR programmes was assessed in 456 patients. Based on intention and participation at T1, patients were classified as nonintenders (56%), intenders (13%), or actors (31%). Group differences were confirmed in outcome expectancies and self-efficacy. By T2, 21% of T1 actors had dropped out. Dropouts and maintainers differed in intention and self-efficacy (at T1). Results are in line with the HAPA and suggest a perspective for tailoring motivational counselling to improve participation in phase III CR programmes.

  17. Tier I ecological evaluation for phase III channel improvements to the John. F. Baldwin ship channel

    Energy Technology Data Exchange (ETDEWEB)

    Bienert, R.W.; Shreffler, D.K.; Word, J.Q.; Kohn, N.P. [Battelle/Marine Sciences Lab., Sequim, WA (United States)

    1994-05-01

    To assist the US Army Corps of Engineers (USACE) in determing whether the material from proposed dredging of the John F. Baldwin Ship Channel (JFBSC) is suitable for unrestricted, unconfined open-ocean disposal, Battelle/Marine Sciences Laboratory (MSL) prepared this report. Based on these findings, sediments that would be removed during Phase III improvements to the JFBSC fail to meet the three suitability criteria for open-ocean disposal. Firstly, fine-grained sediments comprise a significant fraction of the bottom material in some areas of the channel, and this material is not exposed to high current or wave energy. Dredged material from the JFBSC is not being proposed for beach nourishment; therefore the second criterion is not met. JFBSC sediments do not meet the third criterion because, although they may be substantially similar to substrates at several of the proposed disposal sites, they are from an area that historically has experienced loading of contaminants, which toxicology studies have shown have the potential to result in acute toxicity or significant bioaccumulation.

  18. All projects related to | Page 101 | IDRC - International Development ...

    International Development Research Centre (IDRC) Digital Library (Canada)

    Financial Services and the Deployment of Agricultural Innovations in the Sahel. Project. Over the past 20 years, numerous innovations to improve food crop yields have ... Areas Network Phase III: Devolution to the American University of Beirut.

  19. Improving Project Portfolio Management (PPM) for Improvement Projects

    DEFF Research Database (Denmark)

    Pries-Heje, Jan; Jakobsen, Peter M.; Korsaa, Morten

    2017-01-01

    Project Portfolio Management (PPM) focus on the integration and alignment of projects with the business operation in order to achieve most value and cost-efficiency for the investment in projects. PPM is often a challenge and especially so for improvement projects where PPM is considerably...... of evaluating a portfolio of improvement projects and combine this evaluation with the effect they have on the CMMI maturity level. Further, the paper demonstrates how the combination of a strong senior management requirement for improved maturity and the focus on getting the most value out of PPM made...

  20. 78 FR 73555 - Deepwater Horizon Oil Spill; Draft Programmatic and Phase III Early Restoration Plan and Draft...

    Science.gov (United States)

    2013-12-06

    ... Environmental Impact Statement (Draft Phase III ERP/PEIS). The Draft Phase III ERP/PEIS considers programmatic... programmatic restoration alternatives. The Draft Phase III ERP/PEIS evaluates these restoration alternatives... the Framework Agreement. The Draft Phase III ERP/PEIS also evaluates the environmental consequences of...

  1. Successful completion of the Qinshan phase III nuclear power plant-a successful model for Chinese-Canadian cooperation

    International Nuclear Information System (INIS)

    Peng Xiaoxing

    2004-01-01

    This report documents Qinshan CANDU project construction and commissioning experience as well as management strategies and approaches that contributed to the successful completion of the project. The Qinshan phase III (CANDU) nuclear power plant was built in record times: Unit 1 achieved commercial operation on December 31, 2002 and Unit 2 on July 24, 2003, 43 days and 112 days ahead of schedule respectively. The reference plant design is the Wolsong 3 and 4 CANDU-6 units in the Republic of Korea. Improvements in design and construction methods allowed Unit 1 to be constructed in 51.5 Months from First Concrete to Criticality-a record in China for nuclear power plants. The key factors are project management and project management tools, quality assurance, construction methods (including open top construction, heavy lifts and modularization), electronic documentation with configuration control that provides up-to-date on-line information, CADDS design linked with material management, specialized material control including bar coding, and planning. The introduction of new design and construction techniques was achieved by combining conventional AECL practices with working experiences in China. The most advanced tools and techniques for achieving optimum construction quality, schedule and cost were used. Successful application of advanced project management methods and tools will benefit TQNPC in operation of the station, and the Chinese contractors in advancing their capabilities in future nuclear projects in China and enhancing their opportunities internationally. TQNPC's participation in Quality surveillance (QS) activities of nuclear steam plant (NSP) and Balance of Plant (BOP) offshore equipment benefited TQNPC in acquiring knowledge of specific equipment manufacturing processes, which can be applied to similar activities in China. China has established the capability of manufacturing CANDU fuel and becoming self-reliant in fuel supply. Excellent co-operation and

  2. Sears Point Tidal Marsh Restoration Project: Phase II

    Science.gov (United States)

    Information about the SFBWQP Sears Point Tidal Marsh Restoration Project: Phase II, part of an EPA competitive grant program to improve SF Bay water quality focused on restoring impaired waters and enhancing aquatic resources.

  3. Policy and procedures for classification of Class III groundwater at UMTRA Project sites

    International Nuclear Information System (INIS)

    1989-03-01

    The US Environmental Protection Agency (EPA) has recently proposed groundwater regulations for the US Department of Energy's )DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project. These regulations allow the application of supplemental standards at UMTRA Project sites in specific situations. The designation of groundwater as Class III permits the application of supplemental standards. This document discusses a final UMTRA Project policy and procedures for identifying Class III groundwater, including identification of a review area, definition of water quality, quantification of aquifer yield, and identification of methods reasonably employed for public water supply systems. These items, either individually or collectively, need to be investigated in order to determine if groundwaters at UMTRA Project sites are Class III. This document provides a framework for the DOE to determine Class III groundwaters

  4. A quality assurance audit: phase iii trial of maximal androgen deprivation in prostate cancer (TROG 96.01)

    International Nuclear Information System (INIS)

    Steigler, A.; Kovacev, O.; Denham, J.; Lamb, D.; North, J.

    2000-01-01

    In 1997 the Trans-Tasman Radiation Oncology Group (TROG) performed a quality assurance (QA) audit of its phase III randomized clinical trial investigating the effectiveness of different durations of maximal androgen deprivation prior to and during definitive radiation therapy for locally advanced carcinoma of the prostate (TROG 96.01). The audit reviewed a total of 60 cases from 15 centres across Australia and New Zealand. In addition to verification of technical adherence to the protocol, the audit also incorporated a survey of centre planning techniques and a QA time/cost analysis. The present report builds on TROG's first technical audit conducted in 1996 for the phase III accelerated head and neck trial (TROG 91.01) and highlights the significant progress TROG has made in the interim period. The audit provides a strong validation of the results of the 96.01 trial, as well as valuable budgeting and treatment planning information for future trials. Overall improvements were detected in data quality and quantity, and in protocol compliance, with a reduction in the rate of unacceptable protocol violations from 10 to 4%. Audit design, staff education and increased data management resources were identified as the main contributing factors to these improvements. In addition, a budget estimate of $100 per patient has been proposed for conducting similar technical audits. The next major QA project to be undertaken by TROG during the period 1998-1999 is an intercentre dosimetry study. Trial funding and staff education have been targeted as the key major issues essential to the continued success and expansion of TROG's QA programme. Copyright (1999) Blackwell Science Pty Ltd

  5. Maqarin natural analogue project: Phase IV. Reconnaissance mission report (April 28 to May 7, 1999)

    International Nuclear Information System (INIS)

    Smellie, J.A.T.

    2000-08-01

    Final planning of the Technical Proposal for Phase IV of the Maqarin Natural Analogue Project was preceded by a ten day Reconnaissance Mission to the Jordan sites. The main objective of this mission was to: i) allow new organisations within the project to become familiar with the geological context of the Maqarin and Central Jordan sites and also to appreciate the prevailing technical and logistical limitations, ii) carry out limited field investigations, and iii) based on the experience from these two points, provide the opportunity to finalise the Maqarin Phase IV Technical Proposal. This report details the results of the mission

  6. Maqarin natural analogue project: Phase IV. Reconnaissance mission report (April 28 to May 7, 1999)

    Energy Technology Data Exchange (ETDEWEB)

    Smellie, J.A.T. [ed.] [Conterra AB, Uppsala (Sweden)

    2000-08-01

    Final planning of the Technical Proposal for Phase IV of the Maqarin Natural Analogue Project was preceded by a ten day Reconnaissance Mission to the Jordan sites. The main objective of this mission was to: i) allow new organisations within the project to become familiar with the geological context of the Maqarin and Central Jordan sites and also to appreciate the prevailing technical and logistical limitations, ii) carry out limited field investigations, and iii) based on the experience from these two points, provide the opportunity to finalise the Maqarin Phase IV Technical Proposal. This report details the results of the mission.

  7. INL Results for Phases I and III of the OECD/NEA MHTGR-350 Benchmark

    Energy Technology Data Exchange (ETDEWEB)

    Gerhard Strydom; Javier Ortensi; Sonat Sen; Hans Hammer

    2013-09-01

    The Idaho National Laboratory (INL) Very High Temperature Reactor (VHTR) Technology Development Office (TDO) Methods Core Simulation group led the construction of the Organization for Economic Cooperation and Development (OECD) Modular High Temperature Reactor (MHTGR) 350 MW benchmark for comparing and evaluating prismatic VHTR analysis codes. The benchmark is sponsored by the OECD's Nuclear Energy Agency (NEA), and the project will yield a set of reference steady-state, transient, and lattice depletion problems that can be used by the Department of Energy (DOE), the Nuclear Regulatory Commission (NRC), and vendors to assess their code suits. The Methods group is responsible for defining the benchmark specifications, leading the data collection and comparison activities, and chairing the annual technical workshops. This report summarizes the latest INL results for Phase I (steady state) and Phase III (lattice depletion) of the benchmark. The INSTANT, Pronghorn and RattleSnake codes were used for the standalone core neutronics modeling of Exercise 1, and the results obtained from these codes are compared in Section 4. Exercise 2 of Phase I requires the standalone steady-state thermal fluids modeling of the MHTGR-350 design, and the results for the systems code RELAP5-3D are discussed in Section 5. The coupled neutronics and thermal fluids steady-state solution for Exercise 3 are reported in Section 6, utilizing the newly developed Parallel and Highly Innovative Simulation for INL Code System (PHISICS)/RELAP5-3D code suit. Finally, the lattice depletion models and results obtained for Phase III are compared in Section 7. The MHTGR-350 benchmark proved to be a challenging simulation set of problems to model accurately, and even with the simplifications introduced in the benchmark specification this activity is an important step in the code-to-code verification of modern prismatic VHTR codes. A final OECD/NEA comparison report will compare the Phase I and III

  8. The magic school bus TV project. Final technical performance report, July 1, 1992--July 31, 1995. Season III

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1997-03-01

    For Season III, our goal has been to produce 13 new episodes that can optimally benefit from our research and experience in developing this unique series. With a total of 39 episodes, MSB`s third season will move the production from a weekly to a daily series, airing Monday to Friday and Sundays on PBS. As we delivered the 13 Season II episodes to PBS during fall of 1995, we also completed 13 more scripts for Season III production. During the remaining portion of Season III, these 13 scripts are being animated and prepared for delivery to PBS for an October 7th, 1996 launch date. Based on staggered phases of production used since the project`s inception, the development of science topics and show scripting for Season IV occurs at the same time that Season III shows are in animation and post-production. Thus, topics for Season IV shows are being selected, and science research and scripting have also begun during this time period. Both the National Science Foundation and PBS have made a commitment to Season IV, and a proposal has been submitted to Microsoft for consideration.

  9. Phase II Water Rental Pilot Project: Snake River Resident Fish and Wildlife Resources and Management Recommendations.

    Energy Technology Data Exchange (ETDEWEB)

    Stovall, Stacey H.

    1994-08-01

    The Idaho Water Rental Pilot Project was implemented in 1991 as part of the Non-Treaty Storage Fish and Wildlife Agreement between Bonneville Power Administration and the Columbia Basin Fish and Wildlife Authority. The goal of the project is to quantify resident fish and wildlife impacts resulting from salmon flow augmentation releases made from the upper Snake River Basin. Phase I summarized existing resource information and provided management recommendations to protect and enhance resident fish and wildlife habitat resulting from storage releases for the I improvement of an adromous fish migration. Phase II includes the following: (1) a summary of recent biological, legal, and political developments within the basin as they relate to water management issues, (2) a biological appraisal of the Snake River between American Falls Reservoir and the city of Blackfoot to examine the effects of flow fluctuation on fish and wildlife habitat, and (3) a preliminary accounting of 1993--1994 flow augmentation releases out of the upper Snake, Boise, and Payette river systems. Phase III will include the development of a model in which annual flow requests and resident fish and wildlife suitability information are interfaced with habitat time series analysis to provide an estimate of resident fish and wildlife resources.

  10. Solar neutrino oscillation parameters after SNO Phase-III and SAGE Part-III

    International Nuclear Information System (INIS)

    Yang Ping; Liu Qiuyu

    2009-01-01

    We analyse the recently published results from solar neutrino experiments SNO Phase-III and SAGE Part-III and show their constraints on solar neutrino oscillation parameters, especially for the mixing angle θ 12 . Through a global analysis using all existing data from SK, SNO, Ga and Cl radiochemical experiments and long base line reactor experiment KamLAND , we obtain the parameters Δm 12 2 =7.684 -0.208 +0.212 x 10 -5 eV 2 , tan 2 θ 12 =0.440 -0.057 +0.059 . We also find that the discrepancy between the KamLAND and solar neutrino results can be reduced by choosing a small non-zero value for the mixing angle θ 13 . (authors)

  11. Health Activities Project (HAP), Trial Edition III.

    Science.gov (United States)

    Buller, Dave; And Others

    Contained within this Health Activities Project (HAP) trial edition (set III) are a teacher information folio and numerous student activity folios which center around the idea that students in grades 5-8 can control their own health and safety. Each student folio is organized into an Overview, Health Background, Materials, Setting Up, and…

  12. ISTC projects devoted to improving laser beam quality

    Science.gov (United States)

    Malakhov, Yu. I.

    2007-05-01

    Short overview is done about the activity of ISTC in a direction concerned with improving powerful laser beam quality by means of nonlinear and linear adaptive optics methods. Completed projects #0591 and #1929 resulted in the development of a stimulated Brillouin scattering (SBS) phase conjugation mirror of superhigh fidelity employing the kinoform optical elements (rasters of small lenses) of new generation designed for pulsed or pulse-periodic lasers with nanosecond scale pulse duration. Project #2631 is devoted to development of an adaptive optical system for phase registration and correction of laser beams with wave front vortices. The principles of operation of conventional adaptive systems are based on the assumption that the phase is a smooth continuous function in space. Therefore the solution of the Project tasks will assume a new step in adaptive optics.

  13. Phase III Simplified Integrated Test (SIT) results - Space Station ECLSS testing

    Science.gov (United States)

    Roberts, Barry C.; Carrasquillo, Robyn L.; Dubiel, Melissa Y.; Ogle, Kathryn Y.; Perry, Jay L.; Whitley, Ken M.

    1990-01-01

    During 1989, phase III testing of Space Station Freedom Environmental Control and Life Support Systems (ECLSS) began at Marshall Space Flight Center (MSFC) with the Simplified Integrated Test. This test, conducted at the MSFC Core Module Integration Facility (CMIF), was the first time the four baseline air revitalization subsystems were integrated together. This paper details the results and lessons learned from the phase III SIT. Future plans for testing at the MSFC CMIF are also discussed.

  14. Twenty-seven years of phase III trials for patients with extensive disease small-cell lung cancer: disappointing results.

    Directory of Open Access Journals (Sweden)

    Isao Oze

    Full Text Available BACKGROUND: Few studies have formally assessed whether treatment outcomes have improved substantially over the years for patients with extensive disease small-cell lung cancer (ED-SCLC enrolled in phase III trials. The objective of the current investigation was to determine the time trends in outcomes for the patients in those trials. METHODS AND FINDINGS: We searched for trials that were reported between January 1981 and August 2008. Phase III randomized controlled trials were eligible if they compared first-line, systemic chemotherapy for ED-SCLC. Data were evaluated by using a linear regression analysis. RESULTS: In total, 52 trials were identified that had been initiated between 1980 and 2006; these studies involved 10,262 patients with 110 chemotherapy arms. The number of randomized patients and the proportion of patients with good performance status (PS increased over time. Cisplatin-based regimens, especially cisplatin and etoposide (PE regimen, have increasingly been studied, whereas cyclophosphamide, doxorubicin, and vincristine-based regimens have been less investigated. Multiple regression analysis showed no significant improvement in survival over the years. Additionally, the use of a PE regimen did not affect survival, whereas the proportion of patients with good PS and the trial design of assigning prophylactic cranial irradiation were significantly associated with favorable outcome. CONCLUSIONS AND SIGNIFICANCE: The survival of patients with ED-SCLC enrolled in phase III trials did not improve significantly over the years, suggesting the need for further development of novel targets, newer agents, and comprehensive patient care.

  15. Aqueous phase complexation of Cm(III) and Cf(III) with ionizable macrocyclic ligands

    International Nuclear Information System (INIS)

    Manchanda, V.K.; Mohapatra, P.K.

    1995-01-01

    Complexation behaviour of Cm(III) and Cf(III) with 1,7-diaza-4,10,13-trioxacyclopentadecane-N,N'-diacetic acid (K21DA), 1,10-diaza-4,7,13,16-tetraoxacyclooctadecane-N,N'-diacetic acid (K22DA) and ethylene diamine N,N'- diacetic acid (EDDA) has been investigated using dinonyl naphthalene sulphonic acid (DNNS), in tetramethyl ammonium form as liquid cation exchanger. The aqueous phase complex formation constants are computed from the distribution data. Though larger complex formation constants are observed with K21DA as well as K22DA compared to those with the acyclic analog EDDA, no size correlation is observed. (author). 5 refs., 1 tab

  16. Superconductivity in the unconventional high pressure phase bismuth-III

    Energy Technology Data Exchange (ETDEWEB)

    Semeniuk, Konstantin; Brown, Philip; Vasiljkovic, Aleksandar; Grosche, Malte [University of Cambridge (United Kingdom)

    2015-07-01

    One of the most surprising developments in high pressure research was the realisation that many elements assume very unexpected high pressure structures, described in terms of extremely large or even infinite unit cells. Elemental bismuth, which has been known to undergo a series of pressure induced structural transitions between 25 kbar and 80 kbar, is an interesting example: the intermediate pressure Bi-III phase has a complex 'host-guest' structure consisting of two incommensurate sublattices. Since the unit cell is infinitely large, the description of electronic and lattice excitations is problematic. Apart from its metallic character and the observation of superconductivity at low temperature, little is known about the electronic structure in this phase. We investigate the electrical resistivity within the metallic Bi-III phase under high hydrostatic pressure and in applied magnetic field using a piston cylinder cell. Superconductivity is observed below 7.1 K, and we extract the temperature dependence of the upper critical field, which exceeds 2 T at low temperature. The normal state resistivity exhibits an approximately linear temperature dependence. This could be attributed to strong scattering from low-lying excitations, as caused by an unusually soft phonon spectrum. The results suggest that strong coupling superconductivity arises within the host-guest structure of Bi-III out of an unusual electronic state.

  17. Whole Brain Radiotherapy and RRx-001: Two Partial Responses in Radioresistant Melanoma Brain Metastases from a Phase I/II Clinical Trial: A TITE-CRM Phase I/II Clinical Trial.

    Science.gov (United States)

    Kim, Michelle M; Parmar, Hemant; Cao, Yue; Pramanik, Priyanka; Schipper, Matthew; Hayman, James; Junck, Larry; Mammoser, Aaron; Heth, Jason; Carter, Corey A; Oronsky, Arnold; Knox, Susan J; Caroen, Scott; Oronsky, Bryan; Scicinski, Jan; Lawrence, Theodore S; Lao, Christopher D

    2016-04-01

    Kim et al. report two patients with melanoma metastases to the brain that responded to treatment with RRx-001 and whole brain radiotherapy (WBRT) without neurologic or systemic toxicity in the context of a phase I/II clinical trial. RRx-001 is an reactive oxygen and reactive nitrogen species (ROS/RNS)-dependent systemically nontoxic hypoxic cell radiosensitizer with vascular normalizing properties under investigation in patients with various solid tumors including those with brain metastases. Metastatic melanoma to the brain is historically associated with poor outcomes and a median survival of 4 to 5 months. WBRT is a mainstay of treatment for patients with multiple brain metastases, but no significant therapeutic advances for these patients have been described in the literature. To date, candidate radiosensitizing agents have failed to demonstrate a survival benefit in patients with brain metastases, and in particular, no agent has demonstrated improved outcome in patients with metastatic melanoma. Kim et al. report two patients with melanoma metastases to the brain that responded to treatment with novel radiosensitizing agent RRx-001 and WBRT without neurologic or systemic toxicity in the context of a phase I/II clinical trial. Published by Elsevier Inc.

  18. Phase III Drilling Operations at the Long Valley Exploratory Well (LVF 51-20)

    Energy Technology Data Exchange (ETDEWEB)

    Finger, J.T.; Jacobson, R.D.

    1999-06-01

    During July-September, 1998, a jointly funded drilling operation deepened the Long Valley Exploratory Well from 7178 feet to 9832 feet. This was the third major drilling phase of a project that began in 1989, but had sporadic progress because of discontinuities in tiding. Support for Phase III came from the California Energy Commission (CEC), the International Continental Drilling Program (ICDP), the US Geological Survey (USGS), and DOE. Each of these agencies had a somewhat different agenda: the CEC wants to evaluate the energy potential (specifically energy extraction from magma) of Long Valley Caldera; the ICDP is studying the evolution and other characteristics of young, silicic calderas; the USGS will use this hole as an observatory in their Volcano Hazards program; and the DOE, through Sandia, has an opportunity to test new geothermal tools and techniques in a realistic field environment. This report gives a description of the equipment used in drilling and testing; a narrative of the drilling operations; compiled daily drilling reports; cost information on the project; and a brief summary of engineering results related to equipment performance and energy potential. Detailed description of the scientific results will appear in publications by the USGS and other researchers.

  19. Palestinian Adolescents Coping with Trauma (PACT) - Phase III ...

    International Development Research Centre (IDRC) Digital Library (Canada)

    Palestinian Adolescents Coping with Trauma (PACT) - Phase III. Violent conflict has been repeatedly shown to result in severe, long-term social and mental health problems for exposed children and adolescents. While in the developed world, it is generally accepted that individuals seek professional one-on-one ...

  20. Military Family Coping Project - Phase II

    Science.gov (United States)

    2015-05-01

    Anxiety, Life Satisfaction , Addiction, Trauma 4 The Military Family Coping Project reflects two phases. The first consisted of a series of focus...need for and guided the work of the Military Family Coping Project Phase II funded by TATRC. The Military Family Coping Project Phase II was...solidarity. For the purposes of family functioning analyses, married and unmarried soldiers were analyzed separately because marital status affects

  1. Horonobe Underground Research Laboratory project. Synthesis of phase I investigation 2001-2005. Volume 'geoscientific research'

    International Nuclear Information System (INIS)

    Ota, Kunio; Abe, Hironobu; Kunimaru, Takanori

    2011-03-01

    The Horonobe Underground Research Laboratory (URL) Project is being pursued by the Japan Atomic Energy Agency (JAEA) to enhance the reliability of relevant disposal technologies through investigations of the deep geological environment within the host sedimentary formations at Horonobe in Hokkaido, northern Japan. The project consists of two major research areas, 'Geoscientific Research' and 'R and D on Geological Disposal', and proceeds in three overlapping phases, 'Phase I: Surface-based investigation', 'Phase II: Construction' and 'Phase III: Operation', over a period of 20 years. The present report summarises the results of the Phase I geoscientific research carried out from March 2001 to March 2005. Integration of the results from different disciplines ensures that the Phase I goals have been successfully achieved and identifies key issues that need to be addressed in Phases II and III. More importantly, efforts are made to summarise as many lessons learnt from the Phase I investigations and other technical achievements as possible to form a 'knowledge base' that will reinforce the technical basis for both implementation and the formulation of safety regulations. Based on experiences of selecting the URL area and site in Horonobe Town, important factors that should be taken into consideration in such selection processes and their rationale are demonstrated. In the course of stepwise surface-based investigations, a number of achievements have been made, which can eventually provide examples of integrated methodologies for characterising the sedimentary formations. The relevant surface-based investigation techniques have thus been further developed. The Horonobe URL has been designed based on geoscientific information accumulated during the surface-based investigations and the plans for safe construction and operation of the URL have been defined in a feasible manner. In addition, a variety of environmental measures taken during Phase I have proved to be

  2. Stakeholder perspectives on the use of positron emission tomography in phase III oncology trials in the UK.

    Science.gov (United States)

    Rojas-Anaya, Hector; Skogen, Karoline; Miles, Kenneth Alan

    2012-06-01

    To identify factors that influence the use of PET in phase III oncology trials in the UK by evaluating stakeholder perspectives. A wide range of UK PET research stakeholders with a potential interest in the use of PET in phase III trials were identified and invited to participate. These UK PET research stakeholders were consulted using a semistructured questionnaire on their personal experience with and involvement in PET research, the role of PET in phase III oncology clinical trials and on the promotion of UK PET research and unmet clinical needs in oncology. Responses were analysed quantitatively and by qualitative content analysis of free-text responses. A total of 118 responses were received from a wide range of stakeholders representing several professional groups and working environments. Of these respondents, 49 (42%) were using PET in their research. There was the general perception that using PET in clinical research is beneficial in oncology. The two major barriers identified were poor availability of PET and perceived difficulties in funding of excess treatment costs (75% of respondents). Other factors included limited coverage of PET in training, uncertainty about developing imaging protocols or the status of tracers other than 18F-fluorodeoxyglucose, and low awareness of the role of PET in patient selection for therapeutic trials. Patient concerns about radiation were not perceived as a research barrier. Interventions that improve the availability and funding pathways for PET research scans and that increase researcher awareness could help promote the use of PET for phase III oncology trials in the UK.

  3. Phase III Advanced Anodes and Cathodes Utilized in Energy Efficient Aluminum Production Cells; FINAL

    International Nuclear Information System (INIS)

    Christini, R.A.; Dawless, R.K.; Ray, S.P.; Weirauch, D.A. Jr.

    2001-01-01

    During Phase I of the present program, Alcoa developed a commercial cell concept that has been estimated to save 30% of the energy required for aluminum smelting. Phase ii involved the construction of a pilot facility and operation of two pilots. Phase iii of the Advanced Anodes and Cathodes Program was aimed at bench experiments to permit the resolution of certain questions to be followed by three pilot cells. All of the milestones related to materials, in particular metal purity, were attained with distinct improvements over work in previous phases of the program. NiO additions to the ceramic phase and Ag additions to the Cu metal phase of the cermet improved corrosion resistance sufficiently that the bench scale pencil anodes met the purity milestones. Some excellent metal purity results have been obtained with anodes of the following composition: Further improvements in anode material composition appear to be dependent on a better understanding of oxide solubilities in molten cryolite. For that reason, work was commissioned with an outside consultant to model the MeO - cryolite systems. That work has led to a better understanding of which oxides can be used to substitute into the NiO-Fe2O3 ceramic phase to stabilize the ferrites and reduce their solubility in molten cryolite. An extensive number of vertical plate bench electrolysis cells were run to try to find conditions where high current efficiencies could be attained. TiB2-G plates were very inconsistent and led to poor wetting and drainage. Pure TiB2 did produce good current efficiencies at small overlaps (shadowing) between the anodes and cathodes. This bench work with vertical plate anodes and cathodes reinforced the importance of good cathode wetting to attain high current efficiencies. Because of those conclusions, new wetting work was commissioned and became a major component of the research during the third year of Phase III. While significant progress was made in several areas, much work needs to be

  4. Assessing local resources and culture before instituting quality improvement projects.

    Science.gov (United States)

    Hawkins, C Matthew

    2014-12-01

    The planning phases of quality improvement projects are commonly overlooked. Disorganized planning and implementation can escalate chaos, intensify resistance to change, and increase the likelihood of failure. Two important steps in the planning phase are (1) assessing local resources available to aid in the quality improvement project and (2) evaluating the culture in which the desired change is to be implemented. Assessing local resources includes identifying and engaging key stakeholders and evaluating if appropriate expertise is available for the scope of the project. This process also involves engaging informaticists and gathering available IT tools to plan and automate (to the extent possible) the data-gathering, analysis, and feedback steps. Culture in a department is influenced by the ability and willingness to manage resistance to change, build consensus, span boundaries between stakeholders, and become a learning organization. Allotting appropriate time to perform these preparatory steps will increase the odds of successfully performing a quality improvement project and implementing change. Copyright © 2014 American College of Radiology. Published by Elsevier Inc. All rights reserved.

  5. Overview of progress on the improvement projects for the LANSCE accelerator and target facilities

    International Nuclear Information System (INIS)

    Macek, R.J.; Browne, J.; Brun, T.; Donahue, J.B.; Fitzgerald, D.H.; Hoffman, E.; Pynn, R.; Schriber, S.; Weinacht, D.

    1997-01-01

    Three projects have been initiated since 1994 to improve the performance of the accelerator and target facilities for the Los Alamos Neutron Science Center (LANSCE). The LANSCE Reliability Improvement Project (LRIP) was separated into two phases. Phase 1, completed in 1995, targeted near-term improvements to beam reliability and availability that could be completed in one-year's time. Phase 2, now underway and scheduled for completion in May 1998, consists of two projects: (a) implementation of direct H-injection for the Proton Storage Ring (PSR) and (b) an upgrade of the target/moderator system for the short pulse spallation neutron (SPSS) source. The latter will reduce the target change-out time from about 10 months to about three weeks. The third project, the SPSS Enhancement Project, is aimed at increasing the PSR output beam current to 200 microA at 30 Hz and providing up to seven new neutron scattering instruments

  6. Heterogeneous FDG-guided dose-escalation for locally advanced NSCLC (the NARLAL2 trial): Design and early dosimetric results of a randomized, multi-centre phase-III study

    DEFF Research Database (Denmark)

    Møller, Ditte Sloth; Nielsen, Tine Bjørn; Brink, Carsten

    2017-01-01

    Background and purpose: Local recurrence is frequent in locally advanced NSCLC and is primarily located in FDG-avid parts of tumour and lymph nodes. Aiming at improving local control without increasing toxicity, we designed a multi-centre phase-III trial delivering inhomogeneous dose-escalation d......Background and purpose: Local recurrence is frequent in locally advanced NSCLC and is primarily located in FDG-avid parts of tumour and lymph nodes. Aiming at improving local control without increasing toxicity, we designed a multi-centre phase-III trial delivering inhomogeneous dose...

  7. Mismanagement Reasons of the Projects Execution Phase

    Directory of Open Access Journals (Sweden)

    Hatem Khaleefah Al-Agele

    2017-10-01

    Full Text Available The execution phase of the project is most dangerous and the most drain on the resources during project life cycle, therefore, its need to monitor and control by specialists to exceeded obstructions and achieve the project goals. The study aims to detect the actual reasons behind mismanagement of the execution phase. The study begins with theoretical part, where it deals with the concepts of project, project selection, project management, and project processes. Field part consists of three techniques: 1- brainstorming, 2- open interviews with experts and 3- designed questionnaire (with 49 reason. These reasons result from brainstorming and interviewing with experts., in order to find the real reasons behind mismanagement of the execution phase. The most important reasons which are negatively impact on management of the execution phase that proven by the study were (Inability of company to meet project requirements because it's specialized and / or large project, Multiple sources of decision and overlap in powers, Inadequate planning, Inaccurate estimation of cost, Delayed cash flows by owners, Poor performance of project manager, inefficient decision making process, and the Negative impact of people in the project area. Finally, submitting a set of recommendations which will contribute to overcome the obstructions of successful management of the execution phase.

  8. Estuary 2100 Project, Phase 2: Building Partnerships for Resilient Watersheds

    Science.gov (United States)

    Information about the SFBWQP Estuary 2100 Project, Phase 2: Building Partnerships for Resilient Watersheds, part of an EPA competitive grant program to improve SF Bay water quality focused on restoring impaired waters and enhancing aquat

  9. CHAOS. III. GAS-PHASE ABUNDANCES IN NGC 5457

    Energy Technology Data Exchange (ETDEWEB)

    Croxall, Kevin V.; Pogge, Richard W. [Department of Astronomy, The Ohio State University, 140 West 18th Avenue, Columbus, OH 43210 (United States); Berg, Danielle A. [Center for Gravitation, Cosmology and Astrophysics, Department of Physics, University of Wisconsin Milwaukee, 1900 East Kenwood Boulevard, Milwaukee, WI 53211 (United States); Skillman, Evan D. [Minnesota Institute for Astrophysics, University of Minnesota, 116 Church Street SE, Minneapolis, MN 55455 (United States); Moustakas, John [Department of Physics and Astronomy, Siena College, 515 Loudon Road, Loudonville, NY 12211 (United States)

    2016-10-10

    We present Large Binocular Telescope observations of 109 H ii regions in NGC 5457 (M101) obtained with the Multi-Object Double Spectrograph. We have robust measurements of one or more temperature-sensitive auroral emission lines for 74 H ii regions, permitting the measurement of “direct” gas-phase abundances. Comparing the temperatures derived from the different ionic species, we find: (1) strong correlations of T [N ii] with T [S iii] and T [O iii], consistent with little or no intrinsic scatter; (2) a correlation of T [S iii] with T [O iii], but with significant intrinsic dispersion; (3) overall agreement between T [N ii], T [S ii], and T [O ii], as expected, but with significant outliers; (4) the correlations of T [N ii] with T [S iii] and T [O iii] match the predictions of photoionization modeling while the correlation of T [S iii] with T [O iii] is offset from the prediction of photoionization modeling. Based on these observations, which include significantly more observations of lower excitation H ii regions, missing in many analyses, we inspect the commonly used ionization correction factors (ICFs) for unobserved ionic species and propose new empirical ICFs for S and Ar. We have discovered an unexpected population of H ii regions with a significant offset to low values in Ne/O, which defies explanation. We derive radial gradients in O/H and N/O which agree with previous studies. Our large observational database allows us to examine the dispersion in abundances, and we find intrinsic dispersions of 0.074 ± 0.009 in O/H and 0.095 ± 0.009 in N/O (at a given radius). We stress that this measurement of the intrinsic dispersion comes exclusively from direct abundance measurements of H ii regions in NGC 5457.

  10. Application of the BISON Fuel Performance Code of the FUMEX-III Coordinated Research Project

    International Nuclear Information System (INIS)

    Williamson, R.L.; Novascone, S.R.

    2013-01-01

    Since 1981, the International Atomic Energy Agency (IAEA) has sponsored a series of Coordinated Research Projects (CRP) in the area of nuclear fuel modeling. These projects have typically lasted 3-5 years and have had broad international participation. The objectives of the projects have been to assess the maturity and predictive capability of fuel performance codes, support interaction and information exchange between countries with code development and application needs, build a database of well- defined experiments suitable for code validation, transfer a mature fuel modeling code to developing countries, and provide guidelines for code quality assurance and code application to fuel licensing. The fourth and latest of these projects, known as FUMEX-III1 (FUel Modeling at EXtended Burnup- III), began in 2008 and ended in December of 2011. FUMEX-III was the first of this series of fuel modeling CRP's in which the INL participated. Participants met at the beginning of the project to discuss and select a set of experiments ('priority cases') for consideration during the project. These priority cases were of broad interest to the participants and included reasonably well-documented and reliable data. A meeting was held midway through the project for participants to present and discuss progress on modeling the priority cases. A final meeting was held at close of the project to present and discuss final results and provide input for a final report. Also in 2008, the INL initiated development of a new multidimensional (2D and 3D) multiphysics nuclear fuel performance code called BISON, with code development progressing steadily during the three-year FUMEX-III project. Interactions with international fuel modeling researchers via FUMEX-III played a significant role in the BISON evolution, particularly influencing the selection of material and behavioral models which are now included in the code. The FUMEX-III cases are generally integral fuel rod experiments occurring

  11. Improving Immunization Rates Using Lean Six Sigma Processes: Alliance of Independent Academic Medical Centers National Initiative III Project.

    Science.gov (United States)

    Hina-Syeda, Hussaini; Kimbrough, Christina; Murdoch, William; Markova, Tsveti

    2013-01-01

    Quality improvement education and work in interdisciplinary teams is a healthcare priority. Healthcare systems are trying to meet core measures and provide excellent patient care, thus improving their Hospital Consumer Assessment of Healthcare Providers & Systems scores. Crittenton Hospital Medical Center in Rochester Hills, MI, aligned educational and clinical objectives, focusing on improving immunization rates against pneumonia and influenza prior to the rates being implemented as core measures. Improving immunization rates prevents infections, minimizes hospitalizations, and results in overall improved patient care. Teaching hospitals offer an effective way to work on clinical projects by bringing together the skill sets of residents, faculty, and hospital staff to achieve superior results. WE DESIGNED AND IMPLEMENTED A STRUCTURED CURRICULUM IN WHICH INTERDISCIPLINARY TEAMS ACQUIRED KNOWLEDGE ON QUALITY IMPROVEMENT AND TEAMWORK, WHILE FOCUSING ON A SPECIFIC CLINICAL PROJECT: improving global immunization rates. We used the Lean Six Sigma process tools to quantify the initial process capability to immunize against pneumococcus and influenza. The hospital's process to vaccinate against pneumonia overall was operating at a Z score of 3.13, and the influenza vaccination Z score was 2.53. However, the process to vaccinate high-risk patients against pneumonia operated at a Z score of 1.96. Improvement in immunization rates of high-risk patients became the focus of the project. After the implementation of solutions, the process to vaccinate high-risk patients against pneumonia operated at a Z score of 3.9 with a defects/million opportunities rate of 9,346 and a yield of 93.5%. Revisions to the adult assessment form fixed 80% of the problems identified. This process improvement project was not only beneficial in terms of improved quality of patient care but was also a positive learning experience for the interdisciplinary team, particularly for the residents. The

  12. Research ICT Africa (RIA!) - phase III | CRDI - Centre de recherches ...

    International Development Research Centre (IDRC) Digital Library (Canada)

    Research ICT Africa (RIA!) - phase III. Depuis la création du réseau RIA! en 2003, ses responsables ont mené avec succès des études portant tant sur l'offre que sur la demande afin de permettre de mieux comprendre l'accès aux TIC et leur utilisation en Afrique. Au cours des deux premières phases du projet (nos 101584 ...

  13. Public Policy and Protection from Exclusion - Phase III | IDRC ...

    International Development Research Centre (IDRC) Digital Library (Canada)

    Public Policy and Protection from Exclusion - Phase III ... and decision-makers active in the promotion of equitable health policies, with a view to promoting the emergence of an observatory of health systems in the ... Policy in Focus publishes a special issue profiling evidence to empower women in the labour market.

  14. W.A. Parish Post-Combustion CO{sub 2} Capture and Sequestration Project Phase 1 Definition

    Energy Technology Data Exchange (ETDEWEB)

    Armpriester, Anthony; Smith, Roger; Scheriffius, Jeff; Smyth, Rebecca; Istre, Michael

    2014-02-01

    For a secure and sustainable energy future, the United States (U.S.) must reduce its dependence on imported oil and reduce its emissions of carbon dioxide (CO{sub 2}) and other greenhouse gases (GHGs). To meet these strategic challenges, the U.S. wiU have to create fundamentally new technologies with performance levels far beyond what is now possible. Developing advanced post-combustion clean coal technologies for capturing CO{sub 2} from existing coal-fired power plants can play a major role in the country's transition to a sustainable energy future, especially when coupled with CO{sub 2}-enhanced oil recovery (CO{sub 2}-EOR). Pursuant to these goals, NRG Energy, Inc. (NRG) submitted an application and entered into a cost-shared collaboration with the U.S. Department of Energy (DOE) under Round 3 of the Clean Coal Power Initiative (CCPI) to advance low-emission coal technologies. The objective of the NRG W A Parish Post-Combustion CO{sub 2} Capture and Sequestration Demonstration Project is to establish the technical feasibility and economic viability of post-combustion CO{sub 2} capture using flue gas from an existing pulverized coal-fired boiler integrated with geologic sequestration via an enhanced oil recovery (EOR) process. To achieve these objectives, the project will be executed in three phases. Each phase represents a distinct aspect of the project execution. The project phases are: • Phase I. Project Definition/Front-End Engineering Design (FEED) • Phase ll. Detailed Engineering, Procurement & Construction • Phase III. Demonstration and Monitoring The purpose of Phase I is to develop the project in sufficient detail to facilitate the decision-making process in progressing to the next stage of project delivery. Phase n. This report provides a complete summary of the FEED study effort, including pertinent project background information, the scope of facilities covered, decisions, challenges, and considerations made regarding configuration and

  15. Brush Day & Night Phase III to Phase IV: ensuring that good oral health habits are sustainable.

    Science.gov (United States)

    Melo, Paulo; Fine, Charlotte; Malone, Sinead; Horn, Virginie

    2018-05-01

    Over the past 10 years, the FDI-Unilever Brush Day & Night partnership has significantly influenced the life of children worldwide through the implementation of school programmes for oral health education and prevention. This article reports the key facts and outcomes of Phase III of the partnership, and announces the launch of Phase IV. During Phase III, the expert advisors of the Brush Day & Night partnership conducted a longitudinal study to evaluate the impact of the '21 Day' programme in almost 8,000 children in 10 countries. Analysis revealed the effectiveness of the 21 Day programme in sustainably educating children to brush their teeth twice a day, with the greatest impact observed in children aged 7-9 years. With the launch of Phase IV, the Brush Day & Night partnership will continue to deliver its oral health school programme for 7-9 year-old children with a strengthened methodology, including randomized sampling and control groups. The scope of the evaluation will be broadened to include oral health-related quality of life indicators, and monitoring of the oral health knowledge of children's parents/carers. © 2018 FDI World Dental Federation.

  16. Exploring the Photoreduction of Au(III) Complexes in the Gas-Phase

    Science.gov (United States)

    Marcum, Jesse C.; Kaufman, Sydney H.; Weber, J. Mathias

    2010-06-01

    We have used photodissociation spectroscopy to probe the electronic structure and photoreduction of Au(III) in gas-phase complexes containing Cl- and OH-. The gas-phase electronic spectrum of [AuCl_4]- closely resembles the aqueous solution spectrum, showing a lack of strong solvatochromic shifts. Substitution of Cl- ligands with OH- results in a strong blue shift, in agreement with ligand-field theory. Upon excitation, [AuCl_4]- can dissociate by loss of either one or two neutral Cl atoms, resulting in the reduction of gold from Au(III) to Au(II) and Au(I) respectively. The hydroxide substituted complex, [AuCl_2(OH)_2]-, demonstrates similar behavior but the only observable fragment channel is the loss of two neutral OH ligands, leading only to Au(I).

  17. Improved sensitivity for W-band Gd(III)-Gd(III) and nitroxide-nitroxide DEER measurements with shaped pulses

    Science.gov (United States)

    Bahrenberg, Thorsten; Rosenski, Yael; Carmieli, Raanan; Zibzener, Koby; Qi, Mian; Frydman, Veronica; Godt, Adelheid; Goldfarb, Daniella; Feintuch, Akiva

    2017-10-01

    Chirp and shaped pulses have been recently shown to be highly advantageous for improving sensitivity in DEER (double electron-electron resonance, also called PELDOR) measurements due to their large excitation bandwidth. The implementation of such pulses for pulse EPR has become feasible due to the availability of arbitrary waveform generators (AWG) with high sampling rates to support pulse shaping for pulses with tens of nanoseconds duration. Here we present a setup for obtaining chirp pulses on our home-built W-band (95 GHz) spectrometer and demonstrate its performance on Gd(III)-Gd(III) and nitroxide-nitroxide DEER measurements. We carried out an extensive optimization procedure on two model systems, Gd(III)-PyMTA-spacer-Gd(III)-PyMTA (Gd-PyMTA ruler; zero-field splitting parameter (ZFS) D ∼ 1150 MHz) as well as nitroxide-spacer-nitroxide (nitroxide ruler) to evaluate the applicability of shaped pulses to Gd(III) complexes and nitroxides, which are two important classes of spin labels used in modern DEER/EPR experiments. We applied our findings to ubiquitin, doubly labeled with Gd-DOTA-monoamide (D ∼ 550 MHz) as a model for a system with a small ZFS. Our experiments were focused on the questions (i) what are the best conditions for positioning of the detection frequency, (ii) which pump pulse parameters (bandwidth, positioning in the spectrum, length) yield the best signal-to-noise ratio (SNR) improvements when compared to classical DEER, and (iii) how do the sample's spectral parameters influence the experiment. For the nitroxide ruler, we report an improvement of up to 1.9 in total SNR, while for the Gd-PyMTA ruler the improvement was 3.1-3.4 and for Gd-DOTA-monoamide labeled ubiquitin it was a factor of 1.8. Whereas for the Gd-PyMTA ruler the two setups pump on maximum and observe on maximum gave about the same improvement, for Gd-DOTA-monoamide a significant difference was found. In general the choice of the best set of parameters depends on the D

  18. The application and design of distributed control system in reactor shutdown system of Qinshan phase III

    International Nuclear Information System (INIS)

    Su Guoquan; Liu Wangtian; Yu Yijun; Xiong Weihua

    2006-03-01

    The design, commissioning and running of the reactor trip parameter monitoring system used in Qinshan Phase III are introduced. The applying technology of Distributed Control System realized trip parameter monitoring and realized the function of trip parameters quick data acquisitioning, transferring, saving, alarm, query. The applying of trip parameters monitoring system improved the abilities of plant status monitoring and event analyzing, and increased the security and economy of nuclear power plant. (authors)

  19. Cold in-place recycling using solventless emulsion - phase IV (emulsion qualification and long-term field performance).

    Science.gov (United States)

    2016-05-01

    This report looks into how a successful Cold In-Place solventless emulsion behaves and how the emulsion : break test developed in Phase III of this project demonstrates that behavior. Modifications to the test have been : made to improve the consiste...

  20. Estuary 2100 Project, Phase 1: Resilient Watersheds for a Changing Climate

    Science.gov (United States)

    Information about the SFBWQP Estuary 2100 Project, Phase 1: Resilient Watersheds for a Changing Climate , part of an EPA competitive grant program to improve SF Bay water quality focused on restoring impaired waters and enhancing aquatic resources.

  1. Phase accuracy evaluation for phase-shifting fringe projection profilometry based on uniform-phase coded image

    Science.gov (United States)

    Zhang, Chunwei; Zhao, Hong; Zhu, Qian; Zhou, Changquan; Qiao, Jiacheng; Zhang, Lu

    2018-06-01

    Phase-shifting fringe projection profilometry (PSFPP) is a three-dimensional (3D) measurement technique widely adopted in industry measurement. It recovers the 3D profile of measured objects with the aid of the fringe phase. The phase accuracy is among the dominant factors that determine the 3D measurement accuracy. Evaluation of the phase accuracy helps refine adjustable measurement parameters, contributes to evaluating the 3D measurement accuracy, and facilitates improvement of the measurement accuracy. Although PSFPP has been deeply researched, an effective, easy-to-use phase accuracy evaluation method remains to be explored. In this paper, methods based on the uniform-phase coded image (UCI) are presented to accomplish phase accuracy evaluation for PSFPP. These methods work on the principle that the phase value of a UCI can be manually set to be any value, and once the phase value of a UCI pixel is the same as that of a pixel of a corresponding sinusoidal fringe pattern, their phase accuracy values are approximate. The proposed methods provide feasible approaches to evaluating the phase accuracy for PSFPP. Furthermore, they can be used to experimentally research the property of the random and gamma phase errors in PSFPP without the aid of a mathematical model to express random phase error or a large-step phase-shifting algorithm. In this paper, some novel and interesting phenomena are experimentally uncovered with the aid of the proposed methods.

  2. Direct disposal of spent fuel. Simulation of shaft transport. Phase III. Final report

    International Nuclear Information System (INIS)

    Filbert, W.; Heda, M.; Khamis, M.; Neydek, J.; Niehues, N.; Rissel, J.; Schrimpf, C.; Weber, W.; Fuchs, D.; Gerlach, A.; Langebrake, F.; Sindern, W.; Gasch, A.; Leicht, R.; Schwab, B.; Hecke, R. van; Kipka, P.; Simmich, K.; Weber, H.

    1994-01-01

    The aim of these demonstration tests was to verify the technical feasibility of a shaft hoisting equipment with a payload of 85 t as well as the safe transport of POLLUX-casks. In phase III of the project the components and the test stand were built, their proper functioning and reliability were tested to demonstrate that they are state-of-the-art. The following additional investigations were carried out: - Tests to fix operational disturbances and simulation tests for the new components to demonstrate their licensibility -Selection and lifetime tests of ropes and investigation of the present state-of-the-art of rope slighting under the conditions of the conceptual design of the shaft hoisting facility - Execution of a probabilistic safety analysis e.g. the determination of the release of radioactive material (result: probability [de

  3. Feedback from D and D projects - Improvement through preparation

    International Nuclear Information System (INIS)

    Sykora, Alexandra; Arnold, Hans-Uwe; Clement, Gilles

    2016-01-01

    This paper describes feedback from AREVA's experience in all stages of decommissioning projects (from end of life to greenfield), focusing on the recommendations for initial actions to be taken early in the project and in the preparation phase. Such initiatives can be summarized in the following four points: (i) Build a strong and specific Decommissioning Team composed of the plant staff together with D and D specialists that shall take the lead and promote the culture change within the remaining staff; (ii) Insist on pre-work as well as real-time Radiological Characterization to optimize waste production; (iii) Develop a tailored Decommissioning Manual streamlined from the legacy Operation Manual (that is no longer appropriate); (iv) Replace the plant's legacy support systems (e.g. ventilation, water treatment, electricity, lighting etc.) with modular and lighter systems better fit for the D and D purpose and allowing to accelerate the cutting and knocking down ('straight backwards') operations. (authors)

  4. MAQARIN natural analogue study: phase III

    International Nuclear Information System (INIS)

    Alexander, W.R.; Mazurek, M.; Waber, H.N.; Arlinger, J.; Erlandson, A.C.; Hallbeck, L.; Pedersen, K.; Chambers, A.V.; Haworth, A.; Ilett, D.; Linklater, C.M.; Tweed, C.J.; Chenery, S.R.N.; Kemp, S.J.; Milodowski, A.E.; Pearce, J.M.; Reeder, S.; Rochelle, C.A.; Smith, B.; Wetton, P.D.; Wragg, J.; Clark, I.D.; Karlsson, F.; Khoury, H.N.; Salameh, E.; Lagerblad, B.; Longworth, G.; Savage, D.; Smellie, J.A.T.

    1998-12-01

    This report represents the conclusion to Phase III of the Maqarin Natural Analogue Study. The main thrust was to establish the origin and chemistry of the Western Springs hyper alkaline groundwaters (Na/K enriched Ca(OH) 2 type) and to study their interaction with rocks of different compositions, as natural analogues to key processes that might occur at an early stage within the 'alkali disturbed zone' of cementitious repositories in different host rocks. Whilst earlier studies at Maqarin were very much site-specific and process-oriented, Phase III provided a regional perspective to the geological evolution of the Maqarin region. This was made possible by greater field access which allowed a more systematic structural and geomorphological study of the area. This has resulted in a greater understanding of the age and spatial relationships concerning formation of the cement zones through spontaneous combustion of the Bituminous Marls, and the subsequent formation of high pH groundwaters at the Eastern and Western Springs locations. At the Western Springs locality, hydrochemical and hydrogeological evaluation of new and published data (plus access to unpublished data), together with detailed mineralogical and geochemical studies, helped to clarify the very earliest stage of cement leachate/host rock interaction. The data were used also to test coupled flow/transport codes developed to assess the long-term evolution of a cementitious repository. Additional objectives addressed include: a) rock matrix diffusion, b) the occurrence and chemical controls on zeolite composition, e) the occurrence and chemical controls on clay stability, and d) the role of microbes, organics and colloids in trace element transport. The Maqarin site now provides a consistent picture explaining the origin of the hyperalkaline groundwaters, and is therefore a unique location for the examination of the mechanisms and processes associated with cementitious repositories. Application of these

  5. Jobs and Self-Sufficiency: Goals of the Project, "Technical Support Services to the Developmentally Disabled, Region III." Final Report, October 1976 to September 1979.

    Science.gov (United States)

    Mallik, Kalisankar; Shaver, Elaine M.

    The final report of a 3 year project to improve the quality of life of mentally retarded, cerebral palsied, and epileptic persons in Region III is presented. The first section details the efforts of the project staff in providing competitive employment opportunities or sheltered employment for 40 severely disabled persons. Equipment modification…

  6. R+D project KEWA. Cooperative development of economically efficient applications for environment, traffic and neighbouring fields in new administrative structures. Phase III 2007/08; F+E-Vorhaben KEWA. Kooperative Entwicklung wirtschafticher Anwendungen fuer Umwelt, Verkehr und benachbarte Bereiche in neuen Verwaltungsstrukturen. Phase III 2007/08

    Energy Technology Data Exchange (ETDEWEB)

    Mayer-Foell, R.; Keitel, A.; Geiger, W. (eds.)

    2008-07-15

    The contribution to the R+D project 'KEWA - Cooperative development of economically efficient applications for environment, traffic and neighbouring fields in new administrative structures. Phase III 2007/08' contains the following contributions: (a) INSPIRE-GeoZG - Realisation of the INSPIRE regulation by means of the planned geo data access law of the Federal Government; (b) RIPS-GDI-AAA - Realisation of the CONCEPTION RIPS 2006 under consideration of the geo data infrastructure Baden-Wuerttemberg and of the AAA concepts of the administration of measurement; (c) RIPS-MDK - Spatial information system and planning system Baden-Wuerttemberg for the IuK group country/municipalities - RIPS metadata profile and further development - MDK; (d) disy Cadenza/GISterm WE - Further development of a platform for reports, evaluations and GIS as well as their applications in the Federal Government and countries; (e) disy Cadenza/GISterm NF - New special applications on the basis of Cadenza and GISterm - scope of special applications; (f) Environmental portals of the country - Networking of information in the environmental portals of Baden-Wuerttemberg, Sachsen-Anhalt and Thuringia under employment of a commercial search machine; (g) Topic park - Extension of the environmental communication platform by multimedial functionalities and contents of the Bodenseeweb; (h) FADO BW - Development of a fundamental version for a new management of special documents in the environmental information system Baden-Wuerttemberg; (i) BodenseeOnline -Interconnected research projects for an information system for the prediction of the hydrodynamics and water quality of lakes by the example of the Bodensee; (j) WaterFrame registered - Modern water information systems by cooperation of Baden-Wuerttemberg, Thuringia and Bavaria at specialized and technical level; (k) TrIS - New development of the drinking water information system Baden-Wueerttemberg; (l) FLIWAS-LE - Country-wide introduction

  7. On the determination of Zr(IV), Ce((III), Th(IV) and U(VI) in organic phase using arsenazo-I and arsenazo-III

    International Nuclear Information System (INIS)

    El-Sweify, F.H.; Kamel, M.M.; Shabana, R.

    1997-01-01

    Some organic extractants of different types, namely tridodecylamine (TDA), tricapryl methyl ammonium chloride (TCMA), di(2-ethylhexyl) phosphoric acid (HDEHP) and 1-[thenoyl-(2)]-3,3,3-trifluoroacetone (HTTA) in xylene have been used to study the extraction behaviour of coloured complexes of Zr(IV), Ce(III), Th(IV) and U(VI) from slightly acidic aqueous solutions of arsenazo-III. Spectrophotometric study for the determination of the aforementioned elements, as well as the colouring agents arsenazo-I and arsenazo-III in the organic phase has been carried out. Some factors affecting the spectrophotometric determination of these elements were studied. These factors were hydrogen ion concentration, concentration of the colouring agents in the aqueous phase and diluent type. Absorption spectra and standard curves are given. The molar extinction coefficients have been calculated. 10 figs

  8. Heliostat Manufacturing for near-term markets. Phase II final report

    International Nuclear Information System (INIS)

    1998-01-01

    This report describes a project by Science Applications International Corporation and its subcontractors Boeing/Rocketdyne and Bechtel Corp. to develop manufacturing technology for production of SAIC stretched membrane heliostats. The project consists of three phases, of which two are complete. This first phase had as its goals to identify and complete a detailed evaluation of manufacturing technology, process changes, and design enhancements to be pursued for near-term heliostat markets. In the second phase, the design of the SAIC stretched membrane heliostat was refined, manufacturing tooling for mirror facet and structural component fabrication was implemented, and four proof-of-concept/test heliostats were produced and installed in three locations. The proposed plan for Phase III calls for improvements in production tooling to enhance product quality and prepare increased production capacity. This project is part of the U.S. Department of Energy's Solar Manufacturing Technology Program (SolMaT)

  9. ISTC Projects from RFNC-VNIIEF Devoted to Improving Laser Beam Quality

    Science.gov (United States)

    Starikov, F.; Kochemasov, G.

    Information is given about the Projects # 1929 and # 2631 supported by ISTC and concerned with improving laser beam quality and interesting for adaptive optics community. One of them, Project # 1929 has been recently finished. It has been devoted to development of an SBS phase conjugation mirror of superhigh conjugation quality employing the kinoform optics for high-power lasers with nanosecond scale pulse duration. With the purpose of reaching ideal PC fidelity, the SBS mirror includes the raster of small lenses that has been traditionally used as the lenslet in Shack-Hartmann wavefront sensor in adaptive optics. The second of them, Project # 2631, is concerned with the development of an adaptive optical system for phase correction of laser beams with wavefront vortex. The principles of operation of modern adaptive systems are based on the assumption that the phase is a smooth continuous function in space. Therefore the solution of the Project tasks will assume a new step in adaptive optics.

  10. SIMMER-III code-verification. Phase 1

    International Nuclear Information System (INIS)

    Maschek, W.

    1996-05-01

    SIMMER-III is a computer code to investigate core disruptive accidents in liquid metal fast reactors but should also be used to investigate safety related problems in other types of advanced reactors. The code is developed by PNC with cooperation of the European partners FZK, CEA and AEA-T. SIMMER-III is a two-dimensional, three-velocity-field, multiphase, multicomponent, Eulerian, fluid-dynamics code coupled with a space-, time-, and energy-dependent neutron dynamics model. In order to model complex flow situations in a postulated disrupting core, mass and energy conservation equations are solved for 27 density components and 16 energy components, respectively. Three velocity fields (two liquid and one vapor) are modeled to simulate the relative motion of different fluid components. An additional static field takes into account the structures available in a reactor (pins, hexans, vessel structures, internal structures etc.). The neutronics is based on the discrete ordinate method (S N method) coupled into a quasistatic dynamic model. The code assessment and verification of the fluid dynamic/thermohydraulic parts of the code is performed in several steps in a joint effort of all partners. The results of the FZK contributions to the first assessment and verification phase is reported. (orig.) [de

  11. Reversed phase partition chromatographic separation of Gd(III) on poly(Crown Ether) column

    International Nuclear Information System (INIS)

    Mahanwar, K.R.; Sabale, S.R.

    2014-01-01

    A simple method has been developed for the separation of Gd(III) in hippuric acid medium by using poly(dibenzo-18-crown-6) as stationary phase. The effect of hippuric acid concentration, different eluting agent, foreign ions etc was studied and the optimum conditions were established. Breakthrough capacity of poly(dibenzo-18-crown-6) for Gd(III) was found to be 0.572 ±0.01 mmolg -1 of crown polymer. The separation of Gd(III) from other elements in multicomponent mixtures has been achieved. The method was extended for determination of Gd(III) in real sample. The method is simple, rapid and selective with good reproducibility (approximately ± 2%). Crown ethers are widely used as complexing agent that can selectively capture metal cation in their cavity. This special feature shown by poly (dibenzo-18-crown-6) has been used in our laboratory for selective cation exchanger by column chromatography. No attempts were made for the separation of Gd(III) using hippuric acid media and column chromatography. The present communication describes a simple and sensitive method for the determination of Gd(III) using poly(dibenzo-18-crown-6) as stationary phase in hippuric acid medium. The proposed method affords an attractive feature as compared to the solvent extraction technique i.e. it is free from any organic diluents as an environmental concern

  12. Participation in the IAEA Coordinated Research Project Fumex III: Final Report of AREVA NP

    International Nuclear Information System (INIS)

    2013-01-01

    After the Coordinated Research Project (CRP) FUMEXII, participants asked for a new exercise within an IAEA CRP. This CRP started in December 2008 in Vienna with the first Research Coordination Meeting (RCM). The CRP is titled ''Improvement of Computer Codes Used for Fuel Behaviour Simulation FUMEX III''. The object of FUMEX III were the improvement of fuel rod performance codes for modeling high burnup phenomena in modern fuel. This includes transient behavior, as well as mechanical interaction between pellet and cladding and, in progression to the FUMEX II exercise, fission gas release during various conditions (steady state, load follow, transient). AREVA NP agreed on participating in this exercise under the IAEA research agreement no. 15369 and expressed interest in the modeling of pelletclad mechanical interactions as well as fission gas release under steady state and transient conditions. In this exercise AREVA NP used its new global fuel rod code GALILEO, which is still under development (formerly known under the project name COPERNIC 3). During a Consultants Meeting potential topics and a proposed selection of cases have been prepared, which were discussed during the 1st Research Coordination Meeting (RCM) in Vienna in December 2008. During the discussions a number of additional cases motivated by the participants have been identified. Finally, a case table has been agreed upon, which included several cases for the different topics. Most of the cases have been based on the International Fuel Performance Experiments (IFPE) database, but additional cases have been provided during the exercise (e.g., the AREVA idealized case

  13. Phase III randomized clinical trial comparing tremelimumab with standard-of-care chemotherapy in patients with advanced melanoma

    NARCIS (Netherlands)

    Ribas, Antoni; Kefford, Richard; Marshall, Margaret A.; Punt, Cornelis J. A.; Haanen, John B.; Marmol, Maribel; Garbe, Claus; Gogas, Helen; Schachter, Jacob; Linette, Gerald; Lorigan, Paul; Kendra, Kari L.; Maio, Michele; Trefzer, Uwe; Smylie, Michael; McArthur, Grant A.; Dreno, Brigitte; Nathan, Paul D.; Mackiewicz, Jacek; Kirkwood, John M.; Gomez-Navarro, Jesus; Huang, Bo; Pavlov, Dmitri; Hauschild, Axel

    2013-01-01

    In phase I/II trials, the cytotoxic T lymphocyte-associated antigen-4-blocking monoclonal antibody tremelimumab induced durable responses in a subset of patients with advanced melanoma. This phase III study evaluated overall survival (OS) and other safety and efficacy end points in patients with

  14. Phase III randomized clinical trial comparing tremelimumab with standard-of-care chemotherapy in patients with advanced melanoma.

    NARCIS (Netherlands)

    Ribas, A.; Kefford, R.; Marshall, Martin; Punt, C.J.A.; Haanen, J.B.; Marmol, M.; Garbe, C.; Gogas, H.; Schachter, J.; Linette, G.; Lorigan, P.; Kendra, K.L.; Maio, M.; Trefzer, U.; Smylie, M.; McArthur, G.A.; Dreno, B.; Nathan, P.D.; Mackiewicz, J.; Kirkwood, J.M.; Gomez-Navarro, J.; Huang, B.; Pavlov, D.; Hauschild, A.

    2013-01-01

    PURPOSE: In phase I/II trials, the cytotoxic T lymphocyte-associated antigen-4-blocking monoclonal antibody tremelimumab induced durable responses in a subset of patients with advanced melanoma. This phase III study evaluated overall survival (OS) and other safety and efficacy end points in patients

  15. DIAGNOSTIC GUIDANCE AND EARLY INTERVENTION IN CLASS III MALOCCLUSION

    Directory of Open Access Journals (Sweden)

    Rinandri Charea Runizar

    2015-06-01

    Full Text Available Timing of orthodontic treatment for Class III malocclusion has always been somewhat controversial. Many orthodontic pioneers like Angle, Tweed, and Graber have advocated early interception of class II malocclusion because this kind of skeletal discrepancy once established, would usually progress rapidly. What kind of early treatment would be appropriate for this malocclusion? Would this approach be effective and promises a stable result? Early orthodontic treatment is defined as a treatment that is initiated during the primary or mixed dentition stage to enhance skeletal and dental development. It is usually done in two phases. The first phase is intended to correct skeletal discrepancy by taking advantage of growth and development period. The second phase followed to improve occlusal relationship. Early treatment of Class III malocclusion is a possible alternative to improve skeletal discrepancy or at the very east may serve to prevent a worsening malocclusion. Principles of Class III early treatment depend on whether it is dental Class III, functional Class III, or skeletal Class III. Practitioners should consider positive and negative factors of a patient before initiating treatment. Likewise, they should understand factors that affect prognosis and stability of the results.

  16. Omalizumab Improves Quality of Life and Asthma Control in Chinese Patients With Moderate to Severe Asthma: A Randomized Phase III Study

    Science.gov (United States)

    Li, Jing; Kang, Jian; Wang, Changzheng; Yang, Jing; Wang, Linda; Kottakis, Ioannis; Humphries, Michael

    2016-01-01

    Purpose Omalizumab is the preferred add-on therapy for patients with moderate-to-severe persistent allergic asthma and has demonstrated efficacy and safety in various ethnicities. This study evaluated the efficacy and safety of omalizumab in Chinese patients with moderate-to-severe allergic asthma. Methods This randomized, double-blind, parallel-group, placebo-controlled, phase III study assessed lung function, quality of life, asthma control, and safety of omalizumab after 24-week therapy in Chinese patients (18-75 years of age). Results A total of 616 patients were randomized (1:1) to omalizumab or placebo. The primary endpoint, least squares mean treatment difference (LSM-TD) in morning peak expiratory flow (PEF) (omalizumab vs placebo), at Weeks >20-24 was 8.85 L/min (Full analysis set; P=0.062). Per-protocol analysis set showed significant improvements with LSM-TD of 11.53 L/min in mean mPEF at Weeks >20-24 (P=0.022). The FEV1 % predicted was significantly improved with omalizumab vs placebo from 8 to 24 weeks (after 24-week treatment: LSM-TD=4.12%; P=0.001). At Week 24, a higher proportion of omalizumab-treated patients achieved clinically relevant improvements in standardized AQLQ (58.2% vs 39.3%; LSM=0.51 vs 0.10; Pquality of life, and asthma control in Chinese patients with moderate-to-severe persistent allergic asthma and has a good safety profile. PMID:27126725

  17. Baseline job satisfaction and stress among pharmacists and pharmacy technicians participating in the Fleetwood Phase III Study.

    Science.gov (United States)

    Lapane, Kate L; Hughes, Carmel M

    2004-11-01

    To provide baseline levels of job satisfaction and stress among members of the long-term care pharmacy team participating in the Fleetwood Phase III evaluation. Cross-sectional design; long-term care pharmacy provider in North Carolina (the implementation site of the large-scale Fleetwood Phase III study). All current pharmacy employees as of May/June 2002. None. Health Professional Stress Inventory and job satisfaction. Ninety-four percent (16/17) of consultant pharmacists were satisfied with their job, with 89% reporting they would definitely choose to be a pharmacist again. Seventy-five percent both of dispensing pharmacists and pharmacy technicians reported overall job satisfaction. Forty-one reported that they would not choose to be a pharmacist (pharmacy technician) again. The most frequently reported sources of stress among the dispensing pharmacists and pharmacy technicians were conflicts with non-work obligations (i.e., family, personal life) and the ability to perform duties with short staffing. In addition, inadequate pay and few opportunities for job advancement were often/frequent sources of stress among pharmacy technicians. More than one third of dispensing pharmacists also reported stress frequently because of fears of mistakes in patient treatment. Overall, consultants are very satisfied with their positions, although dispensing pharmacists and pharmacy technicians are less satisfied with their work. The reasons may be because of the different nature of each job, as well as staffing shortages. The extent to which the Fleetwood Model can improve job satisfaction and impact on stress will be evaluated once we resurvey the pharmacy team after the intervention period of the Fleetwood Phase III study.

  18. Contributions to reversed-phase column selectivity: III. Column hydrogen-bond basicity.

    Science.gov (United States)

    Carr, P W; Dolan, J W; Dorsey, J G; Snyder, L R; Kirkland, J J

    2015-05-22

    Column selectivity in reversed-phase chromatography (RPC) can be described in terms of the hydrophobic-subtraction model, which recognizes five solute-column interactions that together determine solute retention and column selectivity: hydrophobic, steric, hydrogen bonding of an acceptor solute (i.e., a hydrogen-bond base) by a stationary-phase donor group (i.e., a silanol), hydrogen bonding of a donor solute (e.g., a carboxylic acid) by a stationary-phase acceptor group, and ionic. Of these five interactions, hydrogen bonding between donor solutes (acids) and stationary-phase acceptor groups is the least well understood; the present study aims at resolving this uncertainty, so far as possible. Previous work suggests that there are three distinct stationary-phase sites for hydrogen-bond interaction with carboxylic acids, which we will refer to as column basicity I, II, and III. All RPC columns exhibit a selective retention of carboxylic acids (column basicity I) in varying degree. This now appears to involve an interaction of the solute with a pair of vicinal silanols in the stationary phase. For some type-A columns, an additional basic site (column basicity II) is similar to that for column basicity I in primarily affecting the retention of carboxylic acids. The latter site appears to be associated with metal contamination of the silica. Finally, for embedded-polar-group (EPG) columns, the polar group can serve as a proton acceptor (column basicity III) for acids, phenols, and other donor solutes. Copyright © 2015 Elsevier B.V. All rights reserved.

  19. Project Half Double: Current Results of Phase 1 and Phase 2, December 2017

    DEFF Research Database (Denmark)

    Svejvig, Per; Thorp Adland, Karoline; Zippora Klein, Judith Birte

    ’s competitiveness and play an important role in the battle for jobs and future welfare. The overall goal is to deliver “Projects in half the time with double the impact” where projects in half the time should be understood as half the time to impact (benefit realization, effect is achieved) and not as half the time...... of Project Half Double was initiated in June 2015. It is a two-phase project: phase 1 took place from June 2015 to June 2016 with seven pilot projects, and phase 2 is in progress from July 2016 to July 2018 with 10 pilot projects. The Half Double consortium: Implement Consulting Group is the project leader....... 2016, Svejvig et al. 2017). This report’s target group inludes practitioners in Danish industry and society in general. The editorial team from Aarhus University prepared the report from October 2017 to December 2017, which means that data about pilot projects from December 2017 is not included....

  20. The SUSTAIN Project: A European Study on Improving Integrated Care for Older People Living at Home

    Science.gov (United States)

    Stoop, Annerieke; Billings, Jenny; Leichsenring, Kai; Ruppe, Georg; Tram, Nhu; Barbaglia, María Gabriela; Ambugo, Eliva A.; Zonneveld, Nick; Paat-Ahi, Gerli; Hoffmann, Henrik; Khan, Usman; Stein, Viktoria; Wistow, Gerald; Lette, Manon; Jansen, Aaltje P.D.; Nijpels, Giel; Baan, Caroline A.

    2018-01-01

    Introduction: Integrated care programmes are increasingly being put in place to provide care to older people who live at home. Knowledge of how to further develop integrated care and how to transfer successful initiatives to other contexts is still limited. Therefore, a cross-European research project, called Sustainable Tailored Integrated Care for Older People in Europe (SUSTAIN), has been initiated with a twofold objective: 1. to collaborate with local stakeholders to support and monitor improvements to established integrated care initiatives for older people with multiple health and social care needs. Improvements focus on person-centredness, prevention orientation, safety and efficiency; 2. to make these improvements applicable and adaptable to other health and social care systems, and regions in Europe. This paper presents the overall structure and approach of the SUSTAIN project. Methods: SUSTAIN uses a multiple embedded case study design. In three phases, SUSTAIN partners: (i) conduct interviews and workshops with stakeholders from fourteen established integrated care initiatives to understand where they would prefer improvements to existing ways of working; (ii) collaborate with local stakeholders to support the design and implementation of improvement plans, evaluate implementation progress and outcomes per initiative, and carry out overarching analyses to compare the different initiatives, and; (iii) translate knowledge and experience to an online roadmap. Discussion: SUSTAIN aims to generate evidence on how to improve integrated care, and apply and transfer the knowledge gained to other health and social care systems, and regions. Lessons learned will be brought together in practical tools to inform and support policy-makers and decision-makers, as well as other stakeholders involved in integrated care, to manage and improve care for older people living at home. PMID:29632456

  1. Dramatic improvement in photostability of luminescent Eu(III) complexes with tetraphenylimidodiphosphinate ligand

    International Nuclear Information System (INIS)

    Zheng, Wei; Li, Shu-Jing; Li, Cheng-Hui; Zheng, You-Xuan; You, Xiao-Zeng

    2014-01-01

    In this paper, we synthesized and characterized a new Eu(III) tetraphenylimidodiphosphinate complex with dimethyl sulfoxide (DMSO) as co-ligand. Moreover, we compared the photostability of a series of Eu(III) complexes containing tetraphenylimidodiphosphinate ligands, Eu(tpip) 3 , Eu(tpip) 3 Phen, Eu(tpip) 3 DMSO, with their analogs of 1,3-dibenzoylmethanate, Eu(dbm) 3 ∙2H 2 O, Eu(dbm) 3 Phen, Eu(dbm) 3 (DMSO) 2 . We found that the photostability of the luminescent Eu(III) complexes was significantly improved upon substitution of the 1,3-diketones with tetraphenylimidodiphosphinate ligands. -- Highlights: • We synthesized and characterized a new Eu(III) tetraphenylimidodiphosphinate complexes with dimethyl sulfoxide. • We compared the photostability of Eu(III) complex with tetraphenylimidodiphosphinate and 1,3-dibenzoylmethanate ligands. • The photostability is significantly improved in Eu(III) complexes with tetraphenylimidodiphosphinate ligands

  2. Qinshan CANDU project open top construction method

    International Nuclear Information System (INIS)

    Petrunik, K.J.; Wittann, K.; Khan, A.; Ricciuti, R.; Ivanov, A.; Chen, S.

    2003-01-01

    The significant schedule reductions achieved on the Qinshan CANDU Project were due in large part to the incorporation of advanced construction technologies in project design and delivery. For the Qinshan Project, a number of key advantages were realized through the use of the 'Open Top' construction method. This paper discusses the Qinshan Phase III CANDU Project Open Top implementation method. The Open Top method allowed major equipment to be installed simply, via the use of a Very Heavy Lift (VHL) crane and permitted the use of large-scale modularization. The advantages of Open Top construction, such as simplified access, more flexible project scheduling, improved construction safety and quality, and reduced labours are presented. The large-scale modularization of the Reactor Building Dousing System and the Open Top installation method and advantages relative to traditional CANDU 6 construction practices are also presented. Finally, major improvements for future CANDU plant construction using the Open Top method are discussed. (author)

  3. MAQARIN natural analogue study: phase III

    Energy Technology Data Exchange (ETDEWEB)

    Alexander, W R; Mazurek, M; Waber, H N [Univ. of Berne (Switzerland). Institutes of Geology, Mineralogy and Petrology, Rock-Water Interaction Group (GGWW); Arlinger, J; Erlandson, A C; Hallbeck, L; Pedersen, K [Goeteborg University (Sweden). Dept. of General and Marine Microbiology; Boehlmann, W; Fritz, P; Geyer, S; Geyer, W; Hanschman, G; Kopinke, F D; Poerschmann, J [Umweltforschungszentrum Leipzig-Halle (Germany); Chambers, A V; Haworth, A; Ilett, D; Linklater, C M; Tweed, C J [AEA Technology plc, Harwell (United Kingdom); Chenery, S R.N.; Kemp, S J; Milodowski, A E; Pearce, J M; Reeder, S; Rochelle, C A; Smith, B; Wetton, P D; Wragg, J [British Geological Survey, Keyworth (United Kingdom); Clark, I D [Univ. of Ottawa (Canada). Dept. of Geology; Hodginson, E; Hughes, C R [Univ. of Manchester (United Kingdom). Dept. of Earth Sciences; Hyslop, E K [British Geological Survey, Edinburgh (United Kingdom); Karlsson, F [Swedish Nuclear Fuel and Waste Management Co., Stockholm (Sweden); Khoury, H N; Salameh, E [Univ. of Jordan, Amman (Jordan); Lagerblad, B [Cement Institute, Stockholm (Sweden); Longworth, G [Univ. of Manchester (United Kingdom). Dept. of Geology; Pitty, A F [Private consultant, Norwich (United Kingdom); Savage, D [QuantiSci Ltd, Melton Mowbray (United Kingdom); Smellie, J A.T. [ed.; Conterra AB, Uppsala (Sweden)

    1998-12-01

    This report represents the conclusion to Phase III of the Maqarin Natural Analogue Study. The main thrust was to establish the origin and chemistry of the Western Springs hyper alkaline groundwaters (Na/K enriched Ca(OH){sub 2} type) and to study their interaction with rocks of different compositions, as natural analogues to key processes that might occur at an early stage within the `alkali disturbed zone` of cementitious repositories in different host rocks. Whilst earlier studies at Maqarin were very much site-specific and process-oriented, Phase III provided a regional perspective to the geological evolution of the Maqarin region. This was made possible by greater field access which allowed a more systematic structural and geomorphological study of the area. This has resulted in a greater understanding of the age and spatial relationships concerning formation of the cement zones through spontaneous combustion of the Bituminous Marls, and the subsequent formation of high pH groundwaters at the Eastern and Western Springs locations. At the Western Springs locality, hydrochemical and hydrogeological evaluation of new and published data (plus access to unpublished data), together with detailed mineralogical and geochemical studies, helped to clarify the very earliest stage of cement leachate/host rock interaction. The data were used also to test coupled flow/transport codes developed to assess the long-term evolution of a cementitious repository. Additional objectives addressed include: a) rock matrix diffusion, b) the occurrence and chemical controls on zeolite composition, e) the occurrence and chemical controls on clay stability, and d) the role of microbes, organics and colloids in trace element transport. The Maqarin site now provides a consistent picture explaining the origin of the hyperalkaline groundwaters, and is therefore a unique location for the examination of the mechanisms and processes associated with cementitious repositories. Application of these

  4. MAQARIN natural analogue study: phase III

    Energy Technology Data Exchange (ETDEWEB)

    Alexander, W R; Mazurek, M; Waber, H N [Univ. of Berne (Switzerland). Institutes of Geology, Mineralogy and Petrology, Rock-Water Interaction Group (GGWW); Arlinger, J; Erlandson, A C; Hallbeck, L; Pedersen, K [Goeteborg Univ. (Sweden). Dept. of General and Marine Microbiology; Boehlmann, W; Fritz, P; Geyer, S; Geyer, W; Hanschman, G; Kopinke, F D; Poerschmann, J [Umweltforschungszentrum Leipzig-Halle (Germany); Chambers, A V; Haworth, A; Ilett, D; Linklater, C M; Tweed, C J [AEA Technology plc, Harwell (United Kingdom); Chenery, S R.N.; Kemp, S J; Milodowski, A E; Pearce, J M; Reeder, S; Rochelle, C A; Smith, B; Wetton, P D; Wragg, J [British Geological Survey, Keyworth (United Kingdom); Clark, I D [Univ. of Ottawa (Canada). Dept. of Geology; Hodginson, E; Hughes, C R [Univ. of Manchester (United Kingdom). Dept. of Earth Sciences; Hyslop, E K [British Geological Survey, Edinburgh (United Kingdom); Karlsson, F [Swedish Nuclear Fuel and Waste Management Co., Stockholm (Sweden); Khoury, H N; Salameh, E [Univ. of Jordan, Amman (Jordan); Lagerblad, B [Cement Inst., Stockholm (Sweden); Longworth, G [Univ. of Manchester (United Kingdom). Dept. of Geology; Pitty, A F [Private consultant, Norwich (United Kingdom); Savage, D [QuantiSci Ltd, Melton Mowbray (United Kingdom); Smellie, J A.T. [ed.; Conterra AB, Uppsala (Sweden)

    1998-12-01

    This report represents the conclusion to Phase III of the Maqarin Natural Analogue Study. The main thrust was to establish the origin and chemistry of the Western Springs hyper alkaline groundwaters (Na/K enriched Ca(OH){sub 2} type) and to study their interaction with rocks of different compositions, as natural analogues to key processes that might occur at an early stage within the `alkali disturbed zone` of cementitious repositories in different host rocks. Whilst earlier studies at Maqarin were very much site-specific and process-oriented, Phase III provided a regional perspective to the geological evolution of the Maqarin region. This was made possible by greater field access which allowed a more systematic structural and geomorphological study of the area. This has resulted in a greater understanding of the age and spatial relationships concerning formation of the cement zones through spontaneous combustion of the Bituminous Marls, and the subsequent formation of high pH groundwaters at the Eastern and Western Springs locations. At the Western Springs locality, hydrochemical and hydrogeological evaluation of new and published data (plus access to unpublished data), together with detailed mineralogical and geochemical studies, helped to clarify the very earliest stage of cement leachate/host rock interaction. The data were used also to test coupled flow/transport codes developed to assess the long-term evolution of a cementitious repository. Additional objectives addressed include: a) rock matrix diffusion, b) the occurrence and chemical controls on zeolite composition, e) the occurrence and chemical controls on clay stability, and d) the role of microbes, organics and colloids in trace element transport. The Maqarin site now provides a consistent picture explaining the origin of the hyperalkaline groundwaters, and is therefore a unique location for the examination of the mechanisms and processes associated with cementitious repositories. Application of these

  5. Breckinridge Project, initial effort

    Energy Technology Data Exchange (ETDEWEB)

    None, None

    1982-09-01

    Report III, Volume 1 contains those specifications numbered A through J, as follows: General Specifications (A); Specifications for Pressure Vessels (C); Specifications for Tanks (D); Specifications for Exchangers (E); Specifications for Fired Heaters (F); Specifications for Pumps and Drivers (G); and Specifications for Instrumentation (J). The standard specifications of Bechtel Petroleum Incorporated have been amended as necessary to reflect the specific requirements of the Breckinridge Project, and the more stringent specifications of Ashland Synthetic Fuels, Inc. These standard specifications are available to the Initial Effort (Phase Zero) work performed by all contractors and subcontractors. Report III, Volume 1 also contains the unique specifications prepared for Plants 8, 15, and 27. These specifications will be substantially reviewed during Phase I of the project, and modified as necessary for use during the engineering, procurement, and construction of this project.

  6. Field review of fish habitat improvement projects in central Idaho

    International Nuclear Information System (INIS)

    Beschta, R.L.; Griffith, J.; Wesche, T.A.

    1993-05-01

    The goal of this field review was to provide information to the Bonneville Power Administration (BPA) regarding previous and ongoing fish habitat improvement projects in central Idaho. On July 14, 1992, the review team met at the Sawtooth National Recreation Area office near Ketchum, Idaho, for a slide presentation illustrating several habitat projects during their construction phases. Following the slide presentation, the review team inspected fish habitat projects that have been implemented in the last several years in the Stanley Basin and adjacent valleys. At each site the habitat project was described to the field team and a brief period for project inspection followed. The review team visited approximately a dozen sites on the Challis, Sawtooth, and Boise National Forests over a period of approximately two and a half days. There are two objectives of this review namely to summarize observations for specific field sites and to provide overview commentary regarding the BPA habitat improvement program in central Idaho

  7. Microbial Reducibility of Fe(III Phases Associated with the Genesis of Iron Ore Caves in the Iron Quadrangle, Minas Gerais, Brazil

    Directory of Open Access Journals (Sweden)

    Ceth W. Parker

    2013-11-01

    Full Text Available The iron mining regions of Brazil contain thousands of “iron ore caves” (IOCs that form within Fe(III-rich deposits. The mechanisms by which these IOCs form remain unclear, but the reductive dissolution of Fe(III (hydroxides by Fe(III reducing bacteria (FeRB could provide a microbiological mechanism for their formation. We evaluated the susceptibility of Fe(III deposits associated with these caves to reduction by the FeRB Shewanella oneidensis MR-1 to test this hypothesis. Canga, an Fe(III-rich duricrust, contained poorly crystalline Fe(III phases that were more susceptible to reduction than the Fe(III (predominantly hematite associated with banded iron formation (BIF, iron ore, and mine spoil. In all cases, the addition of a humic acid analogue enhanced Fe(III reduction, presumably by shuttling electrons from S. oneidensis to Fe(III phases. The particle size and quartz-Si content of the solids appeared to exert control on the rate and extent of Fe(III reduction by S. oneidensis, with more bioreduction of Fe(III associated with solid phases containing more quartz. Our results provide evidence that IOCs may be formed by the activities of Fe(III reducing bacteria (FeRB, and the rate of this formation is dependent on the physicochemical and mineralogical characteristics of the Fe(III phases of the surrounding rock.

  8. NASA SBIR abstracts of 1990 phase 1 projects

    Science.gov (United States)

    Schwenk, F. C.; Gilman, J. A.; Paige, J. B.

    1991-01-01

    The research objectives of the 280 projects placed under contract in the National Aeronautics and Space Administration (NASA) 1990 Small Business Innovation Research (SBIR) Phase 1 program are described. The basic document consists of edited, non-proprietary abstracts of the winning proposals submitted by small businesses in response to NASA's 1990 SBIR Phase 1 Program Solicitation. The abstracts are presented under the 15 technical topics within which Phase 1 proposals were solicited. Each project was assigned a sequential identifying number from 001 to 280, in order of its appearance in the body of the report. The document also includes Appendixes to provide additional information about the SBIR program and permit cross-reference in the 1990 Phase 1 projects by company name, location by state, principal investigator, NASA field center responsible for management of each project, and NASA contract number.

  9. Randomized phase III study comparing paclitaxel/cisplatin/gemcitabine and gemcitabine/cisplatin in patients with locally advanced or metastatic urothelial cancer without prior systemic therapy

    DEFF Research Database (Denmark)

    Bellmunt, Joaquim; von der Maase, Hans; Mead, Graham M

    2012-01-01

    The combination of gemcitabine plus cisplatin (GC) is a standard regimen in patients with locally advanced or metastatic urothelial cancer. A phase I/II study suggested that a three-drug regimen that included paclitaxel had greater antitumor activity and might improve survival....

  10. Investigation of the separation of americium(III) and europium(III) by high-speed countercurrent chromatography

    International Nuclear Information System (INIS)

    Wu, J.F.; Jin, Y.R.; Xu, Q.C.; Wang, S.L.; Zhang, L.X.

    2005-01-01

    The long-lived actinides are the important elements in the radioactive waste ;disposal. Because the ions semi diameter and chemical properties of trivalent actinides(III) and trivalent lanthanides(III) are very similar, the separation between them is very difficult. Yang Yu-Sheng put forward the actinides(III) are softer acid than the lanthanides(III), so the actinides(III) are more easily extracted by the soft extractant contain sulfur or nitrogen than the lanthanides(III). Some research have been done on the separation between actinides(III) and lanthanides(III) using the extractants contain sulfur or nitrogen. The results show that satisfactory separation efficiency was gained. Countercurrent Chromatography (CCC) have many specific advantages, such as free from solid support, permit large sample volume and high flow rate, which is useful in the preconcentration of inorganic solute and inorganic preparation. Some studies were done on the separation of lanthanides or-other inorganic elements by HSCCC, the high-purity reagents prepared by HSCCC or CPC turned out to be successful. In present paper, the investigation of separation between Americium (III) and Euricium (III) by High-Speed Countercurrent Chromatography (HSCCC) were made. The extractant used in the work was prepared by ourselves, which is of the soft extractant contrain sulfur. The effects of separation condition on the separation efficiency of Am and Eu by HSCCC were investigated using dichlorophenyl dithiophosphinic acid in xylene as the stationary phase and 0.1 mol/L NaClO4 as mobile phase, respectively. The results show that mutual separation between Am and Eu can be accomplished. The separation factor increases with the increasing of the concentration of extractant and the pH value of the mobile phase, further more, minishing the flow rate of the mobile phase can also improves the separation efficiency between Am and Eu. The nearly base separation was gained when the flow rate is 0.35 ml/min, the

  11. Enhanced Cr(VI) reduction and As(III) oxidation in ice phase: Important role of dissolved organic matter from biochar

    Energy Technology Data Exchange (ETDEWEB)

    Dong, Xiaoling [Department of Soil and Water Science, University of Florida, Gainesville, FL 32611 (United States); Ma, Lena Q., E-mail: lqma@ufl.edu [State Key Laboratory of Pollution Control and Resource Reuse, School of the Environment, Nanjing University, Jiangsu 210046 (China); Department of Soil and Water Science, University of Florida, Gainesville, FL 32611 (United States); Gress, Julia; Harris, Willie [Department of Soil and Water Science, University of Florida, Gainesville, FL 32611 (United States); Li, Yuncong [Soil and Water Science Department, Tropical Research and Education Center, University of Florida, Homestead, FL 33031-3314 (United States)

    2014-02-01

    Graphical abstract: - Highlights: • Biochar-derived dissolved organic matter (DOM) effectively reduced Cr(VI) and oxidized As(III). • Cr(VI) and As(III) could serve as a redox couple. • Cr(VI) and As(III) redox conversion was more effective in the ice phase than aqueous phase. • FTIR and ESR showed that biochar DOM served as both electron donor and acceptor. - Abstract: This study evaluated the impact of DOM from two biochars (sugar beet tailing and Brazilian pepper) on Cr(VI) reduction and As(III) oxidation in both ice and aqueous phases with a soil DOM as control. Increasing DOM concentration from 3 to 300 mg C L{sup −1} enhanced Cr(VI) reduction from 20% to 100% and As(III) oxidation from 6.2% to 25%; however, Cr(VI) reduction decreased from 80–86% to negligible while As(III) oxidation increased from negligible to 18–19% with increasing pH from 2 to 10. Electron spin resonance study suggested semiquinone radicals in DOM were involved in As(III) oxidation while Fourier transform infrared analysis suggested that carboxylic groups in DOM participated in both Cr(VI) reduction and As(III) oxidation. During Cr(VI) reduction, part of DOM (∼10%) was oxidized to CO{sub 2}. The enhanced conversion of Cr(VI) and As(III) in the ice phase was due to the freeze concentration effect with elevated concentrations of electron donors and electron acceptors in the grain boundary. Though DOM enhanced both Cr(VI) reduction and As(III)oxidation, Cr(VI) reduction coupled with As(III) oxidation occurred in absence of DOM. The role of DOM, Cr(VI) and/or As(III) in Cr and As transformation may provide new insights into their speciation and toxicity in cold regions.

  12. Remedial Action Report for Operable Units 6-05 and 10-04, Phase III

    Energy Technology Data Exchange (ETDEWEB)

    R. P. Wells

    2007-08-15

    This Phase III remedial action report addresses the remediation of lead-contaminated soils found at the Security Training Facility STF-02 Gun Range at the Idaho National Laboratory Site. Phase I, consisting of developing and implementing institutional controls at Operble Unit 10-04 sites and developing and implementing Idaho National Laboratory Site-wide plans for both institutional controls and ecological monitoring, was addressed in a previous report. Phase II will remediate sites contaminated with trinitrotoluene and Royal Demolition Explosive. Phase IV will remediate hazards from unexploded ordnance.

  13. Horonobe Underground Research Laboratory Project. Plans for surface-based investigations. Phase 1

    International Nuclear Information System (INIS)

    Goto, Junichi; Hama, Katsuhiro

    2003-10-01

    The Horonobe Underground Research Laboratory Project is an investigation project which is planned over 20 years. The investigations are conducted in the three phases: investigations from surface (Phase 1), investigations during construction of the underground facility (Phase 2) and investigations using the facility (Phase 3). Taking into account the results from 'H12: Project of Establish the Scientific and Technical Basis for HLW Disposal in Japan - Second Progress Report on Research and Development for the Geological Disposal of HLW in Japan-' (JNC, 2000), research and development goals for the Horonobe URL project were re-defined as follows; a) Development of investigation technologies for the geological environment, b) Development of monitoring technologies for the geological environment, c) Study on the long-term stability of the geological environment, d) Development of the basis for engineering technologies in deep underground, e) Verification of technologies for engineered barriers, f) Development of detailed designing technologies of the repositories, and g) Improvement of safety assessment methodologies. Investigations for the goals a) to d) and e) to g) are conducted in the 'Geoscientific Research' and 'Research and Development on Geological Disposal', respectively. In Phase 1, a 'laboratory construction area' of a few kilometers square is selected based on the results from early stage investigations. Subsequent investigations are concentrated in the selected area and its periphery. Acquisition of data by surface-based investigations, modeling of the geological environment and predictions of changes in the geological environment caused by the construction of the underground facility, are conducted in a) Development of investigation technologies for the geological environment. Development and installation of monitoring equipments and data acquisition prior to the construction of the underground facility fall under b) Development of monitoring technologies

  14. Savanna ecosystem project: phase I summary and phase II progress

    CSIR Research Space (South Africa)

    Huntely, BJ

    1978-07-01

    Full Text Available A summary of the results of the first phase (mid 1974 to mid 1976) of the South African Savanna Ecosystem Project being undertaken at Nylsvley in the northern Transvaal is presented. Phase I of this ten year study of the structure and functioning...

  15. Gas-phase infrared spectrum of phosphorus (III) oxycyanide, OPCN: experimental and theoretical investigations

    Science.gov (United States)

    Allaf, Abdul. W.; Kassem, M.; Alibrahim, M.; Boustani, Ihsan

    1999-03-01

    An attempt was made to observe the gas-phase infrared spectrum of Phosphorus (III) oxycyanide, OPCN for the first time. This molecule was produced by an on-line process using phosphorus (III) oxychloride, OPCl as precursor passed over heated AgCN. The products were characterised by the infrared spectra of their vapours. The low resolution gas-phase Fourier transform infrared spectrum shows two bands centered at 2165 and 1385 cm -1. These bands are assigned to, ν1 (CN stretch) and ν2 (OP stretch), respectively. Ab initio self-consistent-field (SCF) molecular orbital (MO) and Møller-Plesset second order perturbation theory (MP2) calculations were performed to determine the geometry, total energy and vibrational frequencies of OPCN.

  16. X-ray phase-contrast tomosynthesis for improved breast tissue discrimination

    International Nuclear Information System (INIS)

    Schleede, Simone; Bech, Martin; Grandl, Susanne; Sztrókay, Aniko; Herzen, Julia; Mayr, Doris; Stockmar, Marco; Potdevin, Guillaume

    2014-01-01

    Purpose: Attenuation-based tomosynthesis has proven to successfully resolve the glandular tissue overlap present in mammography. However, the ability of tomosynthesis to differentiate tumorous and glandular tissue remains limited, due to the small differences in X-ray attenuation in breast tissue. One possibility to overcome this limitation and to further increase the diagnostic value of tomosynthesis exams, is the application of recently developed grating-based phase-contrast methods, which provide complementary information on the phase shift and the local scattering power of the sample. In this study, we report on first phase-contrast breast tomosynthesis results of a mastectomy sample slice with an invasive ductal carcinoma. Material and methods: A slice of a mastectomy sample with histologically proven invasive ductal cancer was imaged at the synchrotron radiation source ESRF (Grenoble, France). We used a two-grating interferometer setup at the ninth fractional Talbot distance and with an X-ray energy of 23 keV. In grating interferometry absorption, differential phase, and scattering images are recorded simultaneously. The tomosynthesis scan comprises 61 projections. Multimodal tomosynthesis results were reconstructed using a standard filtered back-projection approach. Our findings are supported by a comparison of tomographic views to histopathology. Results: Phase-contrast tomosynthesis combines the advantage of improved soft-tissue discrimination in phase-contrast imaging with the ability of tomosynthesis to provide a third dimension so that improved feature visibility is not hampered by superposition artifacts. Our results indicate superior diagnostic value due to the depth resolution supplied in tomosynthesis imaging; a region of necrotic tissue that is obscured in a projection image can clearly be depicted in one single tomosynthesis slice. Compared to absorption tomosynthesis alone, soft tissue contrast is significantly enhanced in phase

  17. X-ray phase-contrast tomosynthesis for improved breast tissue discrimination.

    Science.gov (United States)

    Schleede, Simone; Bech, Martin; Grandl, Susanne; Sztrókay, Aniko; Herzen, Julia; Mayr, Doris; Stockmar, Marco; Potdevin, Guillaume; Zanette, Irene; Rack, Alexander; Weitkamp, Timm; Pfeiffer, Franz

    2014-03-01

    Attenuation-based tomosynthesis has proven to successfully resolve the glandular tissue overlap present in mammography. However, the ability of tomosynthesis to differentiate tumorous and glandular tissue remains limited, due to the small differences in X-ray attenuation in breast tissue. One possibility to overcome this limitation and to further increase the diagnostic value of tomosynthesis exams, is the application of recently developed grating-based phase-contrast methods, which provide complementary information on the phase shift and the local scattering power of the sample. In this study, we report on first phase-contrast breast tomosynthesis results of a mastectomy sample slice with an invasive ductal carcinoma. A slice of a mastectomy sample with histologically proven invasive ductal cancer was imaged at the synchrotron radiation source ESRF (Grenoble, France). We used a two-grating interferometer setup at the ninth fractional Talbot distance and with an X-ray energy of 23 keV. In grating interferometry absorption, differential phase, and scattering images are recorded simultaneously. The tomosynthesis scan comprises 61 projections. Multimodal tomosynthesis results were reconstructed using a standard filtered back-projection approach. Our findings are supported by a comparison of tomographic views to histopathology. Phase-contrast tomosynthesis combines the advantage of improved soft-tissue discrimination in phase-contrast imaging with the ability of tomosynthesis to provide a third dimension so that improved feature visibility is not hampered by superposition artifacts. Our results indicate superior diagnostic value due to the depth resolution supplied in tomosynthesis imaging; a region of necrotic tissue that is obscured in a projection image can clearly be depicted in one single tomosynthesis slice. Compared to absorption tomosynthesis alone, soft tissue contrast is significantly enhanced in phase-contrast tomosynthesis views, where fibrous structures

  18. EcoDoses. Improving radiological assessment of doses to man from terrestrial ecosystems. A status report for the NKS-B project 2004

    Energy Technology Data Exchange (ETDEWEB)

    Nielsen, Sven P.; Isaksson, M.; Nilsson, Elisabeth (and others)

    2005-07-01

    The NKS B-programme EcoDoses project started in 2003 as a collaboration between all the Nordic countries. The aim of the project is to improve the radiological assessments of doses to man from terrestrial ecosystems. The present report sums up the work performed in the second phase of the project. The main topics in 2004 have been: (i) A continuation of previous work with a better approach for estimating global fallout on a regional or national scale, based on a correlation between precipitation and deposition rates. (ii) Fur-ther extension of the EcoDoses milk database. Estimation of effective ecological half lives of {sup 137}Cs in cows milk focussing on suitable post-Chernobyl time-series. Modelling integrated transfer of {sup 13}7{sup C}s to cow's milk from Nordic countries. (iii) Determination of effective ecological half lives for fresh water fish from Nordic lakes. (iv) Investigate ra-dioecological sensitivity for Nordic populations. (v) Food-chain modelling using the Eco-sys-model, which is the underlying food- and dose-module in several computerised deci-sion-making systems. (au)

  19. EcoDoses. Improving radiological assessment of doses to man from terrestrial ecosystems. A status report for the NKS-B project 2004

    International Nuclear Information System (INIS)

    Nielsen, Sven P.; Isaksson, M.; Nilsson, Elisabeth

    2005-07-01

    The NKS B-programme EcoDoses project started in 2003 as a collaboration between all the Nordic countries. The aim of the project is to improve the radiological assessments of doses to man from terrestrial ecosystems. The present report sums up the work performed in the second phase of the project. The main topics in 2004 have been: (i) A continuation of previous work with a better approach for estimating global fallout on a regional or national scale, based on a correlation between precipitation and deposition rates. (ii) Fur-ther extension of the EcoDoses milk database. Estimation of effective ecological half lives of 137 Cs in cows milk focussing on suitable post-Chernobyl time-series. Modelling integrated transfer of 13 7 C s to cow's milk from Nordic countries. (iii) Determination of effective ecological half lives for fresh water fish from Nordic lakes. (iv) Investigate ra-dioecological sensitivity for Nordic populations. (v) Food-chain modelling using the Eco-sys-model, which is the underlying food- and dose-module in several computerised deci-sion-making systems. (au)

  20. Improved uranium-utilization program, Phase I. First semiannual report, September 1979-March 1980

    International Nuclear Information System (INIS)

    Hopkins, G.C.

    1980-11-01

    The Improved Uranium Utilization Program includes a Phase I evaluation of BWR design alternatives which have potential to reduce uranium ore requirements in once-through fuel cycles. The Phase I project is evaluating the alternatives in detail, including considerations of reliability, performance, manufacturing, safety and economics; is establishing implementation development requirements, costs and schedules; is selecting the most promising alternatives; and is developing detailed plans for Phase II projects for implementation. Emphasis is being placed on developing practical alternatives which can be demonstrated at the earliest possible date in existing operating BWR nuclear power stations. Priority is being given to alternatives which have the maximum payoff, measured by reduction of the nation's uranium resource requirements, on the shortest schedule. Alternatives included in current evaluations are: improved refueling and control rod pattern optimization, spectral shift, extended burnup, reduction in gadolinia residual, axial blanket optimization, reconstitution, and combinations of these alternatives

  1. Applying the min-projection strategy to improve the transient performance of the three-phase grid-connected inverter.

    Science.gov (United States)

    Baygi, Mahdi Oloumi; Ghazi, Reza; Monfared, Mohammad

    2014-07-01

    Applying the min-projection strategy (MPS) to a three-phase grid-connected inverter to improve its transient performance is the main objective of this paper. For this purpose, the inverter is first modeled as a switched linear system. Then, the feasibility of the MPS technique is investigated and the stability criterion is derived. Hereafter, the fundamental equations of the MPS for the control of the inverter are obtained. The proposed scheme is simulated in PSCAD/EMTDC environment. The validity of the MPS approach is confirmed by comparing the obtained results with those of VOC method. The results demonstrate that the proposed method despite its simplicity provides an excellent transient performance, fully decoupled control of active and reactive powers, acceptable THD level and a reasonable switching frequency. Copyright © 2014 ISA. Published by Elsevier Ltd. All rights reserved.

  2. Horonobe Underground Research Laboratory project. Plans of investigations during shaft and drift excavation (Construction of underground facilities: Phase II)

    International Nuclear Information System (INIS)

    2005-06-01

    Horonobe Underground Research Laboratory Project is planned for over 20 years to establish the scientific and technical basis for the underground disposal of high-level radioactive wastes in Japan. The investigations are conducted by JNC in three phases, from the surface (Phase I), during the construction of the underground facilities (Phase II), and using the facilities (Phase III). This report concerns the investigation plans for Phase II. During excavation of shafts and drifts, detailed geological and borehole investigation will be conducted and the geological model constructed in Phase I is evaluated and revised by newly acquired data of geophysical and geological environment. Detailed in-situ experiments, as well as the effects of shaft excavation, are also done to study long-term changes, rock properties, groundwater flow and chemistry to ensure the reliability of repository technology and establish safety assessment methodology. (S. Ohno)

  3. Tank waste remediation system privatization Phase 1 infrastructure, project W-519, project execution plan

    International Nuclear Information System (INIS)

    Parazin, R.J.

    1998-01-01

    This Project Execution Plan (PEP) defines the overall strategy, objectives, and contractor management requirements for the execution phase of Project W-519 (98-D403), Privatization Phase 1 Infrastructure Support, whose mission is to effect the required Hanford site infrastructure physical changes to accommodate the Privatization Contractor facilities. This plan provides the project scope, project objectives and method of performing the work scope and achieving objectives. The plan establishes the work definitions, the cost goals, schedule constraints and roles and responsibilities for project execution. The plan also defines how the project will be controlled and documented

  4. The majority of patients with metastatic melanoma are not represented in pivotal phase III immunotherapy trials

    DEFF Research Database (Denmark)

    Donia, Marco; Kimper-Karl, Marie Louise; Høyer, Katrine Lundby

    2017-01-01

    BACKGROUND: Recent randomised phase III trials have led to the approval of several immune checkpoint inhibitors for unresectable or metastatic melanoma (MM). These trials all employed strict patient selection criteria, and it is currently unknown how large proportion of 'real-world' patients diag...... a huge knowledge gap regarding the usefulness of new immunotherapies in the 'real-world' patient population, and urge additional testing of known regimens in selected poor prognosis cohorts.......BACKGROUND: Recent randomised phase III trials have led to the approval of several immune checkpoint inhibitors for unresectable or metastatic melanoma (MM). These trials all employed strict patient selection criteria, and it is currently unknown how large proportion of 'real-world' patients...... in 2014, were included in the analysis. Seven pre-defined eligibility criteria, all used to select patients for enrolment in five recent randomised phase III immunotherapy trials, were analysed. RESULTS: Fifty-five percent of the total population with MM did not meet one or more eligibility criteria ('not...

  5. Using implementation tools to design and conduct quality improvement projects for faster and more effective improvement.

    Science.gov (United States)

    Ovretveit, John; Mittman, Brian; Rubenstein, Lisa; Ganz, David A

    2017-10-09

    Purpose The purpose of this paper is to enable improvers to use recent knowledge from implementation science to carry out improvement changes more effectively. It also highlights the importance of converting research findings into practical tools and guidance for improvers so as to make research easier to apply in practice. Design/methodology/approach This study provides an illustration of how a quality improvement (QI) team project can make use of recent findings from implementation research so as to make their improvement changes more effective and sustainable. The guidance is based on a review and synthesis of improvement and implementation methods. Findings The paper illustrates how research can help a quality project team in the phases of problem definition and preparation, in design and planning, in implementation, and in sustaining and spreading a QI. Examples of the use of different ideas and methods are cited where they exist. Research limitations/implications The example is illustrative and there is little limited experimental evidence of whether using all the steps and tools in the one approach proposed do enable a quality team to be more effective. Evidence supporting individual guidance proposals is cited where it exists. Practical implications If the steps proposed and illustrated in the paper were followed, it is possible that quality projects could avoid waste by ensuring the conditions they need for success are in place, and sustain and spread improvement changes more effectively. Social implications More patients could benefit more quickly from more effective implementation of proven interventions. Originality/value The paper is the first to describe how improvement and implementation science can be combined in a tangible way that practical improvers can use in their projects. It shows how QI project teams can take advantage of recent advances in improvement and implementation science to make their work more effective and sustainable.

  6. Best practices of Building Information Modelling (BIM) implementation in design phase for construction project

    Science.gov (United States)

    Kasim, N.; Zainal Abidin, N. A.; Zainal, R.; Sarpin, N.; Rahim, M. H. I. Abd; Saikah, M.

    2017-11-01

    Implementation of Building Information Modelling (BIM) was expected to bring improvement in current practices of Malaysian construction industry. In the design phase, there is a lack of a ready pool of skilled workers who are able to develop BIM strategic plan and effectively utilise it. These create boundaries for BIM nature in Malaysian construction industry specifically in the design phase to achieve its best practices. Therefore, the objectives of this research are to investigate the current practices of BIM implementation in the design phase as well as the best practices factors of BIM implementation in the design phase. The qualitative research approach is carried out through semi-structured interviews with the designers of different organisations which adopt BIM in the design phase. Data collection is analysed by executing content analysis method. From the findings, the best practices factors of BIM implementation in design phase such as the incentive for BIM training, formal approach to monitoring automated Level of Detailing (LOD), run a virtual meeting and improve Industry Foundation Class (IFC). Thus, best practices factors which lead to practices improvements in the design phase of project development which subsequently improves the implementation of BIM in the design phase of Malaysian construction industry.

  7. Scaled Vitrification System III (SVS III) Process Development and Laboratory Tests at the West Valley Demonstration Project

    International Nuclear Information System (INIS)

    Jain, V.; Barnes, S.M.; Bindi, B.G.; Palmer, R.A.

    2000-01-01

    At the West Valley Demonstration Project (WVDP),the Vitrification Facility (VF)is designed to convert the high-level radioactive waste (HLW)stored on the site to a stable glass for disposal at a Department of Energy (DOE)-specified federal repository. The Scaled Vitrification System III (SVS-III)verification tests were conducted between February 1995 and August 1995 as a supplemental means to support the vitrification process flowsheet, but at only one seventh the scale.During these tests,the process flowsheet was refined and optimized. The SVS-III test series was conducted with a focus on confirming the applicability of the Redox Forecasting Model, which was based on the Index of Feed Oxidation (IFO)developed during the Functional and Checkout Testing of Systems (FACTS)and SVS-I tests. Additional goals were to investigate the prototypical feed preparation cycle and test the new target glass composition. Included in this report are the basis and current designs of the major components of the Scale Vitrification System and the results of the SVS-III tests.The major subsystems described are the feed preparation and delivery, melter, and off-gas treatment systems. In addition,the correlation between the melter's operation and its various parameters;which included feed rate,cold cap coverage,oxygen reduction (redox)state of the glass,melter power,plenum temperature,and airlift analysis;were developed

  8. Converging Redundant Sensor Network Information for Improved Building Control

    Energy Technology Data Exchange (ETDEWEB)

    Dale Tiller; D. Phil; Gregor Henze; Xin Guo

    2007-09-30

    This project investigated the development and application of sensor networks to enhance building energy management and security. Commercial, industrial and residential buildings often incorporate systems used to determine occupancy, but current sensor technology and control algorithms limit the effectiveness of these systems. For example, most of these systems rely on single monitoring points to detect occupancy, when more than one monitoring point could improve system performance. Phase I of the project focused on instrumentation and data collection. During the initial project phase, a new occupancy detection system was developed, commissioned and installed in a sample of private offices and open-plan office workstations. Data acquisition systems were developed and deployed to collect data on space occupancy profiles. Phase II of the project demonstrated that a network of several sensors provides a more accurate measure of occupancy than is possible using systems based on single monitoring points. This phase also established that analysis algorithms could be applied to the sensor network data stream to improve the accuracy of system performance in energy management and security applications. In Phase III of the project, the sensor network from Phase I was complemented by a control strategy developed based on the results from the first two project phases: this controller was implemented in a small sample of work areas, and applied to lighting control. Two additional technologies were developed in the course of completing the project. A prototype web-based display that portrays the current status of each detector in a sensor network monitoring building occupancy was designed and implemented. A new capability that enables occupancy sensors in a sensor network to dynamically set the 'time delay' interval based on ongoing occupant behavior in the space was also designed and implemented.

  9. Zwitterion-functionalized polymer microspheres as a sorbent for solid phase extraction of trace levels of V(V), Cr(III), As(III), Sn(IV), Sb(III) and Hg(II) prior to their determination by ICP-MS.

    Science.gov (United States)

    Jia, Xiaoyu; Gong, Dirong; Zhao, Junyi; Ren, Hongyun; Wang, Jiani; Zhang, Xian

    2018-03-19

    This paper describes the preparation of zwitterion-functionalized polymer microspheres (ZPMs) and their application to simultaneous enrichment of V(V), Cr(III), As(III), Sn(IV), Sb(III) and Hg(II) from environmental water samples. The ZPMs were prepared by emulsion copolymerization of ethyl methacrylate, 2-diethylaminoethyl methacrylate and triethylene glycol dimethyl acrylate followed by modification with 1,3-propanesultone. The components were analyzed by elemental analyses as well as Fourier transform infrared spectroscopy, and the structures were characterized by scanning electron microscopy and transmission electron microscopy. The ZPMs were packed into a mini-column for on-line solid-phase extraction (SPE) of the above metal ions. Following extraction with 40 mM NH 4 NO 3 and 0.5 M HNO 3 solution, the ions were quantified by ICP-MS. Under the optimized conditions, the enrichment factors (from a 40 mL sample) are up to 60 for the ions V(V), As(III), Sb(III) and Hg(II), and 55 for Cr(III) and Sn(IV). The detection limits are 1.2, 3.4, 1.0, 3.7, 2.1 and 1.6 ng L -1 for V(V), Cr(III), As(III), Sn(IV), Sb(III) and Hg(II), respectively, and the relative standard deviations (RSDs) are below 5.2%. The feasibility and accuracy of the method were validated by successfully analyzing six certified reference materials as well as lake, well and river waters. Graphical abstract Zwitterion-functionalized polymer microspheres (ZPMs) were prepared and packed into a mini-column for on-line solid-phase extraction (SPE) via pump 1. Then V(V), Cr(III), As(III), Sn(IV), Sb(III) and Hg(II) ions in environmental waters were eluted and submitted to ICP-MS via pump 2.

  10. The UK MK III GCR experimental physics programme at AEE Winfrith

    Energy Technology Data Exchange (ETDEWEB)

    Johnstone, I

    1972-06-15

    The UK programme of reactor physics experiments in support of the Mk III GCR project started in 1968/69 and has now reached its third main phase. The overall programme is broadly summarised in this report.

  11. Water Use Optimization Toolset Project: Development and Demonstration Phase Draft Report

    Energy Technology Data Exchange (ETDEWEB)

    Gasper, John R. [Argonne National Laboratory; Veselka, Thomas D. [Argonne National Laboratory; Mahalik, Matthew R. [Argonne National Laboratory; Hayse, John W. [Argonne National Laboratory; Saha, Samrat [Argonne National Laboratory; Wigmosta, Mark S. [PNNL; Voisin, Nathalie [PNNL; Rakowski, Cynthia [PNNL; Coleman, Andre [PNNL; Lowry, Thomas S. [SNL

    2014-05-19

    This report summarizes the results of the development and demonstration phase of the Water Use Optimization Toolset (WUOT) project. It identifies the objective and goals that guided the project, as well as demonstrating potential benefits that could be obtained by applying the WUOT in different geo-hydrologic systems across the United States. A major challenge facing conventional hydropower plants is to operate more efficiently while dealing with an increasingly uncertain water-constrained environment and complex electricity markets. The goal of this 3-year WUOT project, which is funded by the U.S. Department of Energy (DOE), is to improve water management, resulting in more energy, revenues, and grid services from available water, and to enhance environmental benefits from improved hydropower operations and planning while maintaining institutional water delivery requirements. The long-term goal is for the WUOT to be used by environmental analysts and deployed by hydropower schedulers and operators to assist in market, dispatch, and operational decisions.

  12. Phase 0 and phase III transport in various organs: combined concept of phases in xenobiotic transport and metabolism.

    Science.gov (United States)

    Döring, Barbara; Petzinger, Ernst

    2014-08-01

    The historical phasing concept of drug metabolism and elimination was introduced to comprise the two phases of metabolism: phase I metabolism for oxidations, reductions and hydrolyses, and phase II metabolism for synthesis. With this concept, biological membrane barriers obstructing the accessibility of metabolism sites in the cells for drugs were not considered. The concept of two phases was extended to a concept of four phases when drug transporters were detected that guided drugs and drug metabolites in and out of the cells. In particular, water soluble or charged drugs are virtually not able to overcome the phospholipid membrane barrier. Drug transporters belong to two main clusters of transporter families: the solute carrier (SLC) families and the ATP binding cassette (ABC) carriers. The ABC transporters comprise seven families with about 20 carriers involved in drug transport. All of them operate as pumps at the expense of ATP splitting. Embedded in the former phase concept, the term "phase III" was introduced by Ishikawa in 1992 for drug export by ABC efflux pumps. SLC comprise 52 families, from which many carriers are drug uptake transporters. Later on, this uptake process was referred to as the "phase 0 transport" of drugs. Transporters for xenobiotics in man and animal are most expressed in liver, but they are also present in extra-hepatic tissues such as in the kidney, the adrenal gland and lung. This review deals with the function of drug carriers in various organs and their impact on drug metabolism and elimination.

  13. Talking in Taejon : regional cooperative agreement project formulation meeting

    International Nuclear Information System (INIS)

    McEwan, A. C.

    1997-01-01

    The International Atomic Energy Agency as part of its Regional Cooperative Agreement (RCA) with countries in east Asia and the neighboring Pacific, has had a project on strengthening radiation protection infrastructures operating for some years. This project has arranged training courses, workshops and other activities on a range of topics related to establishing or improving radiation protection measures and safety of radiation sources in member states of the region. A second 5 year phase of planned activities is to be concluded during 1997, and the value of the project is such that member coutntries proposed its continuation for a further 5 year period commencing in 1998. For this purpose a Task Group took the lead in assembling and evaluating proposals for consideration and approval at a meeting of national coordinators for the project held in Taejon Korea, 24-28 February. The RCA project for Phase III will be titled Enhancement and Harmonisation of Radiation Protection. The meeting of national coordinators from the region represents a unique opportunity for information sharing and cooperation in radiation protection betweem countries. (author)

  14. Safety systems and safety analysis of the Qinshan phase III CANDU nuclear power plant

    International Nuclear Information System (INIS)

    Cai Jianping; Shen Sen; Barkman, N.

    1999-01-01

    The author introduces the Canadian nuclear reactor safety philosophy and the Qinshan Phase III CANDU NPP safety systems and safety analysis, which are designed and performed according to this philosophy. The concept of 'defence-in-depth' is a key element of the Canadian nuclear reactor safety philosophy. The design concepts of redundancy, diversity, separation, equipment qualification, quality assurance, and use of appropriate design codes and standards are adopted in the design. Four special safety systems as well as a set of reliable safety support systems are incorporated in the design of Qinshan phase III CANDU for accident mitigation. The assessment results for safety systems performance show that the fundamental safety criteria for public dose, and integrity of fuel, channels and the reactor building, are satisfied

  15. DECOVALEX III PROJECT. Thermal-Hydro-Mechanical Coupled Processes in Safety Assessments. Report of Task 4

    International Nuclear Information System (INIS)

    Andersson, Johan

    2005-02-01

    A part (Task 4) of the International DECOVALEX III project on coupled thermo-hydro-mechanical (T-H-M) processes focuses on T-H-M modelling applications in safety and performance assessment of deep geological nuclear waste repositories. A previous phase, DECOVALEX II, saw a need to improve such modelling. In order to address this need Task 4 of DECOVALEX III has: Analysed two major T-H-M experiments (Task 1 and Task 2) and three different Bench Mark Tests (Task 3) set-up to explore the significance of T-H-M in some potentially important safety assessment applications. Compiled and evaluated the use of T-H-M modelling in safety assessments at the time of the year 2000. Organised a forum a forum of interchange between PA-analysts and THM modelers at each DECOVALEX III workshop. Based on this information the current report discusses the findings and strives for reaching recommendations as regards good practices in addressing coupled T-H-M issues in safety assessments. The full development of T-H-M modelling is still at an early stage and it is not evident whether current codes provide the information that is required. However, although the geosphere is a system of fully coupled processes, this does not directly imply that all existing coupled mechanisms must be represented numerically. Modelling is conducted for specific purposes and the required confidence level should be considered. It is necessary to match the confidence level with the modelling objective. Coupled THM modelling has to incorporate uncertainties. These uncertainties mainly concern uncertainties in the conceptual model and uncertainty in data. Assessing data uncertainty is important when judging the need to model coupled processes. Often data uncertainty is more significant than the coupled effects. The emphasis on the need for THM modelling differs among disciplines. For geological radioactive waste disposal in crystalline and other similar hard rock formations DECOVALEX III shows it is essential to

  16. DECOVALEX III PROJECT. Thermal-Hydro-Mechanical Coupled Processes in Safety Assessments. Report of Task 4

    Energy Technology Data Exchange (ETDEWEB)

    Andersson, Johan [JA Streamflow AB, Aelvsjoe (Sweden)

    2005-02-15

    A part (Task 4) of the International DECOVALEX III project on coupled thermo-hydro-mechanical (T-H-M) processes focuses on T-H-M modelling applications in safety and performance assessment of deep geological nuclear waste repositories. A previous phase, DECOVALEX II, saw a need to improve such modelling. In order to address this need Task 4 of DECOVALEX III has: Analysed two major T-H-M experiments (Task 1 and Task 2) and three different Bench Mark Tests (Task 3) set-up to explore the significance of T-H-M in some potentially important safety assessment applications. Compiled and evaluated the use of T-H-M modelling in safety assessments at the time of the year 2000. Organised a forum a forum of interchange between PA-analysts and THM modelers at each DECOVALEX III workshop. Based on this information the current report discusses the findings and strives for reaching recommendations as regards good practices in addressing coupled T-H-M issues in safety assessments. The full development of T-H-M modelling is still at an early stage and it is not evident whether current codes provide the information that is required. However, although the geosphere is a system of fully coupled processes, this does not directly imply that all existing coupled mechanisms must be represented numerically. Modelling is conducted for specific purposes and the required confidence level should be considered. It is necessary to match the confidence level with the modelling objective. Coupled THM modelling has to incorporate uncertainties. These uncertainties mainly concern uncertainties in the conceptual model and uncertainty in data. Assessing data uncertainty is important when judging the need to model coupled processes. Often data uncertainty is more significant than the coupled effects. The emphasis on the need for THM modelling differs among disciplines. For geological radioactive waste disposal in crystalline and other similar hard rock formations DECOVALEX III shows it is essential to

  17. Steady-state heat and particle removal with the actively cooled Phase III outboard pump limiter in Tore Supra

    International Nuclear Information System (INIS)

    Nygren, R.; Koski, J.; Lutz, T.; McGrath; Miller, J.; Watkins, J.; Guilhem, D.; Chappuis, P.; Cordier, J.; Loarer, T.

    1995-01-01

    Tore Supra's Phase III outboard pump limiter (OPL) is a modular actively-cooled mid-plane limiter, designed for heat and particle removal during long pulse operation. During its initial operation in 1993, the OPL successfully removed about 1 MW of power during ohmicly heated shots of up to 10 s duration and reached (steady state) thermal equilibrium. The particle pumping of the Phase III OPL was found to be about 50% greater than the Phase II OPL which had a radial distance between the last closed flux surface and the entrance of the pumping throat of 3.5 cm compared with only 2.5 cm for the Phase III OPL. This paper gives examples of power distribution over the limiter from IR measurements of surface temperature and from extensively calorimetry (34 thermocouples and 10 flow meters) and compares the distributions with values predicted by a 3D model (HF3D) with a detailed magnetic configuration (e.g., includes field ripple). ((orig.))

  18. Operations planning and analysis handbook for NASA/MSFC phase B development projects

    Science.gov (United States)

    Batson, Robert C.

    1986-01-01

    Current operations planning and analysis practices on NASA/MSFC Phase B projects were investigated with the objectives of (1) formalizing these practices into a handbook and (2) suggesting improvements. The study focused on how Science and Engineering (S&E) Operational Personnel support Program Development (PD) Task Teams. The intimate relationship between systems engineering and operations analysis was examined. Methods identified for use by operations analysts during Phase B include functional analysis, interface analysis methods to calculate/allocate such criteria as reliability, Maintainability, and operations and support cost.

  19. PandaX-III neutrinoless double beta decay experiment

    Science.gov (United States)

    Wang, Shaobo; PandaX-III Collaboration

    2017-09-01

    The PandaX-III experiment uses high pressure Time Projection Chambers (TPCs) to search for neutrinoless double-beta decay of Xe-136 with high energy resolution and sensitivity at the China Jin-Ping underground Laboratory II (CJPL-II). Fine-pitch Microbulk Micromegas will be used for charge amplification and readout in order to reconstruct both the energy and track of the neutrinoless double-beta decay event. In the first phase of the experiment, the detector, which contains 200 kg of 90% Xe-136 enriched gas operated at 10 bar, will be immersed in a large water tank to ensure 5 m of water shielding. For the second phase, a ton-scale experiment with multiple TPCs will be constructed to improve the detection probability and sensitivity. A 20-kg scale prototype TPC with 7 Micromegas modules has been built to optimize the design of Micromegas readout module, study the energy calibration of TPC and develop algorithm of 3D track reconstruction.

  20. Acceptance test procedure, 241-SY-101 Flexible Receiver System, Phase III testing

    International Nuclear Information System (INIS)

    Ritter, G.A.

    1994-01-01

    This Acceptance Test Procedure is for the 241-SY-101 Flexible Receiver System, Phase III Testing. This procedure will test the sealing integrity of the Flexible Receiver System to ensure that release of waste and aerosols will be minimized during the removal of the test mixer pump from tank SY-101

  1. Luminescence studies of Sm(III) and Cm(III) complexes in NaSCN/DHDECMP extraction systems

    CERN Document Server

    Chung, D Y; Kimura, T

    1999-01-01

    Laser-induced fluorescence (LIF) studies of Sm(III) and Cm(III) complexes in the NaSCN/DHDECMP solvent extraction system were carried out. Luminescence lifetimes were measured to determine the number of water molecules coordinated to Sm(III), Tb(III), Dy(III), and Cm(III) in the sodium thiocyanate solution and in the DHDECMP phase. The hydration number of Sm(III), Tb(III), Dy(III), and Cm(III) in the sodium thiocyanate solution decreased linearly with increasing sodium thiocyanate concentration. The hydration numbers of Sm(III), Dy(III), and Cm(III) in the DHDECMP phase decreased with increasing sodium thiocyanate concentration. The water molecules in the inner coordination sphere of Sm(III) and Dy(III) extracted into the DHDECMP were not completely removed at low sodium thiocyanate concentration but decreased with increasing sodium thiocyanate concentration. However, in the case of Cm(III) extracted into the DHDECMP phase from the sodium thiocyanate solution, there was no water in the inner coordination sphe...

  2. Improved Antileishmanial Activity of Dppz through Complexation with Antimony(III and Bismuth(III: Investigation of the Role of the Metal

    Directory of Open Access Journals (Sweden)

    Cynthia Demicheli

    2012-10-01

    Full Text Available Two novel trivalent antimony(III and bismuth(III complexes with the nitrogen-donor heterocyclic ligand dipyrido[3,2-a:2',3'-c]phenazine (dppz were synthesized and characterized as [Sb(dppzCl3]∙H2O∙CH3OH and [Bi(dppzCl3]. The crystal structure of Sb(III complex was determined by X-ray crystallography. These complexes were evaluated for their activity against the promastigote form of Sb(III-sensitive and –resistant Leishmania infantum chagasi and Leishmania amazonensis strains. Both complexes were more effective than dppz alone in inhibiting the growth of Leishmania promastigotes and were at least 77 and 2,400 times more active than potassium antimonyl tartrate in Sb(III-sensitive and -resistant Leishmania, respectively. The cytotoxicity of dppz and its complexes against mouse peritoneal macrophages occurred at dppz concentrations at least 6-fold greater than those found to be active against Leishmania promastigotes.To investigate the role of the metal in the improved antileishmanial activity of dppz, the activity of the Sb(III complex was compared between the Sb-resistant mutants and their respective parental sensitive strains. The lack of cross-resistance to the Sb(III-dppz complex together with the much lower activity of antimonyl tartrate, SbCl3 and BiCl3 strongly support the model that the metal is not active by itself but improves the activity of dppz through complexation.

  3. Laser projection using generalized phase contrast

    DEFF Research Database (Denmark)

    Glückstad, Jesper; Palima, Darwin; Rodrigo, Peter John

    2007-01-01

    is introduced. An arbitrary phase shift filter eliminates the need for high-frequency modulation and conjugate phase encoding. This lowers device performance requirements and allows practical implementation with currently available dynamic spatial light modulators. (c) 2007 Optical Society of America.......We demonstrate experimental laser projection of a gray-level photographic image with 74% light efficiency using the generalized phase contrast (GPC) method. In contrast with a previously proposed technique [Alonzo et al., New J. Phys. 9, 132 (2007)], a new approach to image construction via GPC...

  4. The acknowledge project: toward improved efficiency in the knowledge acquisition process

    International Nuclear Information System (INIS)

    Marty, J.C.; Ramparany, F.

    1990-01-01

    This paper presents a general overview of the ACKnowledge Project (Acquisition of Knowledge). Knowledge Acquisition is a critical and time-consuming phase in the development of expert systems. The ACKnowledge project aims at improving the efficiency of knowledge acquisition by analyzing and evaluating knowledge acquisition techniques, and developing a Knowledge Engineering Workbench that supports the Knowledge Engineer from the early stage of knowledge aquisition up to the implementation of the knowledge base in large and complex application domains such as the diagnosis of dynamic computer networks

  5. Solvent extraction of anionic chelate complexes of lanthanum(III), europium(III), lutetium(III), scandium(III), and indium(III) with 2-thenoyltrifluoroacetone as ion-pairs with tetrabutylammonium ions

    International Nuclear Information System (INIS)

    Noro, Junji; Sekine, Tatsuya.

    1992-01-01

    The solvent extraction of lanthanum(III), europium(III), lutetium(III), scandium(III), and indium(III) in 0.1 mol dm -3 sodium nitrate solutions with 2-thenoyltrifluoroacetone (Htta) in the absence and presence of tetrabutylammonium ions (tba + ) into carbon tetrachloride was measured. The extraction of lanthanum(III), europium(III), and lutetium(III) was greatly enhanced by the addition of tba + ; this could be explained in terms of the extraction of a ternary complex, M(tta) 4 - tba + . However, the extractions of scandium(III) and indium(III) were nearly the same when tba + was added. The data were treated on the basis of the formation equilibrium of the ternary complex from the neutral chelate, M(tta) 3 , with the extracted ion-pairs of the reagents, tta - tba + , in the organic phase. It was concluded that the degree of association of M(tta) 3 with the ion-pair, tta - tba + , is greater in the order La(tta) 3 ≅ Eu(tta) 3 > Lu(tta) 3 , or that the stability of the ternary complex in the organic phase is higher in the order La(tta) 4 - tba + ≅ Eu(tta) 4 - tba + > Lu(tta) 4 - tba + . This is similar to those of adduct metal chelates of Htta with tributylphosphate (TBP) in synergistic extraction systems. (author)

  6. Implementing Effective Mission Systems Engineering Practices During Early Project Formulation Phases

    Science.gov (United States)

    Moton, Tryshanda

    2016-01-01

    Developing and implementing a plan for a NASA space mission can be a complicated process. The needs, goals, and objectives of any proposed mission or technology must be assessed early in the Project Life Cycle. The key to successful development of a space mission or flight project is the inclusion of systems engineering in early project formulation, namely during Pre-phase A, Phase A, and Phase B of the NASA Project Life Cycle. When a space mission or new technology is in pre-development, or "pre-Formulation", feasibility must be determined based on cost, schedule, and risk. Inclusion of system engineering during project formulation is key because in addition to assessing feasibility, design concepts are developed and alternatives to design concepts are evaluated. Lack of systems engineering involvement early in the project formulation can result in increased risks later in the implementation and operations phases of the project. One proven method for effective systems engineering practice during the pre-Formulation Phase is the use of a mission conceptual design or technology development laboratory, such as the Mission Design Lab (MDL) at NASA's Goddard Space Flight Center (GSFC). This paper will review the engineering process practiced routinely in the MDL for successful mission or project development during the pre-Formulation Phase.

  7. Gas-phase infrared spectrum of phosphorus (III) oxycyanide, OPCN: Experimental and theoretical and theoretical investigations

    International Nuclear Information System (INIS)

    Allaf, A.W.; Kassem, M.; Alibrahim, M.

    1999-01-01

    An attempt was made to observe the gas-phase infrared spectrum of phosphorus (III) oxycyanide, OPCN for the first time. This molecule was produced by on-line process using phosphorus (III) oxychloride, OPCI as precursor passed over heated Ag CN. The products were characterised by the infrared spectra of their vapours. The low resolution gas-phase Fourier transform infrared spectrum shows two bands at 2165 and 1385 cm -1 . These bands are assigned to ν 1 (C≡N stretch) and ν 2 (O=P stretch), respectively. Ab initio self-consistent-field (SCF) molecular orbital (MO) and Moeller - Plesset second order perturbation theory (MP2) calculations were performed to determine the geometry, total energy and vibrational frequencies of OPCN. (authors)

  8. SPSP Phase III Recruiting, Selecting, and Developing Secure Power Systems Professionals. Job Profiles

    Energy Technology Data Exchange (ETDEWEB)

    O' Neil, Lori Ross [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Conway, T. J. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Tobey, D. H. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Greitzer, Frank L. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Dalton, Angela C. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Pusey, Portia K. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States)

    2015-03-01

    The Secure Power Systems Professional Phase III final report was released last year which an appendix of Job Profiles. This new report is that appendix broken out as a standalone document to assist utilities in recruiting and developing Secure Power Systems Professionals at their site.

  9. NASA SBIR abstracts of 1991 phase 1 projects

    Science.gov (United States)

    Schwenk, F. Carl; Gilman, J. A.; Paige, J. B.

    1992-01-01

    The objectives of 301 projects placed under contract by the Small Business Innovation Research (SBIR) program of the National Aeronautics and Space Administration (NASA) are described. These projects were selected competitively from among proposals submitted to NASA in response to the 1991 SBIR Program Solicitation. The basic document consists of edited, non-proprietary abstracts of the winning proposals submitted by small businesses. The abstracts are presented under the 15 technical topics within which Phase 1 proposals were solicited. Each project was assigned a sequential identifying number from 001 to 301, in order of its appearance in the body of the report. Appendixes to provide additional information about the SBIR program and permit cross-reference of the 1991 Phase 1 projects by company name, location by state, principal investigator, NASA Field Center responsible for management of each project, and NASA contract number are included.

  10. NASA SBIR abstracts of 1992, phase 1 projects

    Science.gov (United States)

    Schwenk, F. C.; Gilman, J. A.; Paige, J. B.; Sacknoff, S. M.

    1993-01-01

    The objectives of 346 projects placed under contract by the Small Business Innovation Research (SBIR) program of the National Aeronautics and Space Administration (NASA) are described. These projects were selected competitively from among proposals submitted to NASA in response to the 1992 SBIR Program Solicitation. The basic document consists of edited, non-proprietary abstracts of the winning proposals submitted by small businesses. The abstracts are presented under the 15 technical topics within which Phase 1 proposals were solicited. Each project was assigned a sequential identifying number from 001 to 346, in order of its appearance in the body of the report. Appendixes to provide additional information about the SBIR program and permit cross-reference of the 1992 Phase 1 projects by company name, location by state, principal investigator, NASA Field Center responsible for management of each project, and NASA contract number are included.

  11. U.S. LCI Database Project--Final Phase I Report

    Energy Technology Data Exchange (ETDEWEB)

    2003-08-01

    This Phase I final report reviews the process and provides a plan for the execution of subsequent phases of the database project, including recommended data development priorities and a preliminary cost estimate. The ultimate goal of the project is to develop publicly available LCI Data modules for commonly used materials, products, and processes.

  12. Report on the second uranium-series intercomparison project workshop, Harwell, 23 to 24, June 1980

    International Nuclear Information System (INIS)

    Ivanovich, M.; Warchal, R.M.

    1981-03-01

    The second Uranium-series Intercomparison Project Workshop was held on June 23 and 24, 1980 at Harwell. The aim of the Workshop was to analyse the results of Phase III of the Project and to define the future aims of the Project, if any. This report is an account of the matters raised and discussed during the two day workshop. A detailed report of a statistical analysis of USIP results - Phases I, II, and III is included. A final report submitted to USIP by CBNM, Euratom Laboratory, Geel, on the determination of the alpha activity ratio 228 Th/ 232 U in the Harwell spike solution used in USIP Phase III is reproduced in full. An account of an investigation into suitability of a limestone specimen for a geologic standard carried out at Koeln University is also given. (author)

  13. Liquid-liquid extraction of ruthenium(III) thiocyanate with hexamethylphosphoramide: direct spectrophotometric determination in the organic phase

    International Nuclear Information System (INIS)

    Mitra, B.K.; Pal, B.K.; Chowdhury, R.P.

    1982-01-01

    Ru(III) thiocyanate has been extracted with hexamethylphosphoramide(HMPA) in methyl isobutyl ketone (MIBK). Thus the extractability, sensitivity and selectivity are improved over the simple binary Ru(III) thiocyanate system in spectrophotometric determination of ruthenium in the organic phase. The maximum colour develops on the steam bath, at the acidity range of 1.5 - 2.5 M with HCl and ammonium thiocyanate concentration range of 0.25 - O.5 M. The colour is completely extractable in MIBK when 1.5 - 3.0 ml HMPA is used and show maximum absorbance at 570 nm. The colour system obeys Beer's law for 0.7 - 13 μg Ru/ml and the optimum concentration range is 2 - 13 μg/ml. The molar absorptivity and sensitivity are 6940 l . mole -1 cm -1 and 0.0145 μg/cm 2 respectively. The percent relative error is 2.72%. The method is very simple and does not require oxidation and subsequent distillation. The method can be applied in the presence of osmium. (Author)

  14. SCOPE1: a randomised phase II/III multicentre clinical trial of definitive chemoradiation, with or without cetuximab, in carcinoma of the oesophagus

    International Nuclear Information System (INIS)

    Hurt, Christopher N; Nixon, Lisette S; Griffiths, Gareth O; Al-Mokhtar, Ruby; Gollins, Simon; Staffurth, John N; Phillips, Ceri J; Blazeby, Jane M; Crosby, Tom D

    2011-01-01

    Chemoradiotherapy is the standard of care for patients with oesophageal cancer unsuitable for surgery due to the presence of co-morbidity or extent of disease, and is a standard treatment option for patients with squamous cell carcinoma of the oesophagus. Modern regimens of chemoradiotherapy can lead to significant long-term survival. However the majority of patients will die of their disease, most commonly with local progression/recurrence of their tumours. Cetuximab may overcome one of the principal mechanisms of tumour radio-resistance, namely tumour repopulation, in patients treated with chemoradiotherapy. The purpose of this research is first to determine whether the addition of cetuximab to definitive chemoradiotherapy for treatment of patients with non-metastatic carcinoma of the oesophagus is active (in terms of failure-free rate), safe, and feasible within the context of a multi-centre randomised controlled trial in the UK. If the first stage is successful then the trial will continue to accrue sufficient patients to establish whether the addition of cetuximab to the standard treatment improves overall survival. SCOPE1 is a two arm, open, randomised multicentre Phase II/III trial. Eligible patients will have histologically confirmed carcinoma of the oesophagus and have been chosen to receive definitive chemoradiotherapy by an accredited multidisciplinary team including a specialist Upper GI surgeon. 420 patients will be randomised to receive definitive chemoradiotherapy with or without cetuximab using a 1:1 allocation ratio. During Phase II of the study, the trial will assess safety (toxicity), activity (failure-free rate) and feasibility (recruitment rate and protocol dose modifications/delays) in 90 patients in the experimental arm. If the experimental arm is found to be active, safe, and feasible by the Independent Data Monitoring Committee then recruitment will continue into Phase III. This second stage will recruit a further 120 patients into each arm

  15. SCOPE1: a randomised phase II/III multicentre clinical trial of definitive chemoradiation, with or without cetuximab, in carcinoma of the oesophagus

    Directory of Open Access Journals (Sweden)

    Staffurth John N

    2011-10-01

    Full Text Available Abstract Background Chemoradiotherapy is the standard of care for patients with oesophageal cancer unsuitable for surgery due to the presence of co-morbidity or extent of disease, and is a standard treatment option for patients with squamous cell carcinoma of the oesophagus. Modern regimens of chemoradiotherapy can lead to significant long-term survival. However the majority of patients will die of their disease, most commonly with local progression/recurrence of their tumours. Cetuximab may overcome one of the principal mechanisms of tumour radio-resistance, namely tumour repopulation, in patients treated with chemoradiotherapy. The purpose of this research is first to determine whether the addition of cetuximab to definitive chemoradiotherapy for treatment of patients with non-metastatic carcinoma of the oesophagus is active (in terms of failure-free rate, safe, and feasible within the context of a multi-centre randomised controlled trial in the UK. If the first stage is successful then the trial will continue to accrue sufficient patients to establish whether the addition of cetuximab to the standard treatment improves overall survival. Methods/Design SCOPE1 is a two arm, open, randomised multicentre Phase II/III trial. Eligible patients will have histologically confirmed carcinoma of the oesophagus and have been chosen to receive definitive chemoradiotherapy by an accredited multidisciplinary team including a specialist Upper GI surgeon. 420 patients will be randomised to receive definitive chemoradiotherapy with or without cetuximab using a 1:1 allocation ratio. During Phase II of the study, the trial will assess safety (toxicity, activity (failure-free rate and feasibility (recruitment rate and protocol dose modifications/delays in 90 patients in the experimental arm. If the experimental arm is found to be active, safe, and feasible by the Independent Data Monitoring Committee then recruitment will continue into Phase III. This second

  16. TWRS phase 1 infrastructure project (W-519) characterization

    International Nuclear Information System (INIS)

    Mitchell, C.J.

    1998-01-01

    In order to treat the mixed radioactive and hazardous waste stored in 177 underground tanks, the Tank Waste Remediation System (TWRS) program is developing a 'demonstration' site for treatment and immobilization of these wastes by a private contractor. Project W-519 is providing the infrastructure support to this site by developing the designs and emplacing required pipelines, roads, electrical, etc. In support of the TWRS Phase 1 Infrastructure Project (W-519) Characterization, Numatec Hanford Corporation (NHC) contracted with Waste Management Federal Services, Inc., Northwest Operations (WMNW) to investigate a number of locations in and just outside the 200 East Area eastern fenceline boundary. These areas consisted of known or suspected waste lines or waste sites that could potentially impact the construction and emplacement of the proposed facility improvements, including waterlines and roads. These sites were all located subsurface and sugaring would be required to obtain sample material from the desired depth. The soils would then be sampled and submitted to the laboratory for analysis of radioactivity

  17. Study of complex formation of cobalt (II) and cobalt (III) in acrylamide aqueous solutions and in the phase of acrylamide hydrogel

    International Nuclear Information System (INIS)

    Ismailova, M.M.; Egorova, L.A.; Khamidov, B.O.

    1993-01-01

    Present article is devoted to study of complex formation of cobalt (II) and cobalt (III) in acrylamide aqueous solutions and in the phase of acrylamide hydrogel. The condition of cobalt in various rate of oxidation in acrylamide aqueous solutions was studied. The concentration conditions of stability of system Co(II)-Co(III) were defined. The composition of coordination compounds of cobalt (II) and cobalt (III) in acrylamide aqueous solutions and in the phase of acrylamide hydrogel was determined.

  18. Delivery improvements for CANDU projects

    International Nuclear Information System (INIS)

    Stephen Yu; Ken Hedges

    1998-01-01

    Future CANDU design will continue to meet emerging design and performance requirements as expected by the operating utilities, and will integrate new technologies into both the product features and work processes. Elements of this risk reduction strategy include feedback of lessons learned from operating plants, project experiences from previous projects, and replication of successful systems and equipment. Project implementation risk is minimized by up-front engineering and licensing prior to contract start. Enhanced competitiveness of the CANDU products is ensured by incorporating improvements based on updated technology. This paper summarizes the strategy used to enhance competitiveness of the CANDU products and the measures introduced to minimize risk during project implementation. This strategy provides a balance between innovation and proven designs; and between the desire for safety and operational improvements and the cost to achieve the improvements

  19. Encyclopedia of two-phase heat transfer and flow III macro and micro flow boiling and numerical modeling fundamentals

    CERN Document Server

    2018-01-01

    Set III of this encyclopedia is a new addition to the previous Sets I and II. It contains 26 invited chapters from international specialists on the topics of numerical modeling of two-phase flows and evaporation, fundamentals of evaporation and condensation in microchannels and macrochannels, development and testing of micro two-phase cooling systems for electronics, and various special topics (surface wetting effects, microfin tubes, two-phase flow vibration across tube bundles). The chapters are written both by renowned university researchers and by well-known engineers from leading corporate research laboratories. Numerous "must read" chapters cover the fundamentals of research and engineering practice on boiling, condensation and two-phase flows, two-phase heat transfer equipment, electronics cooling systems, case studies and so forth. Set III constitutes a "must have" reference together with Sets I and II for thermal engineering researchers and practitioners.

  20. Engaging Clinical Nurses in Quality Improvement Projects.

    Science.gov (United States)

    Moore, Susan; Stichler, Jaynelle F

    2015-10-01

    Clinical nurses have the knowledge and expertise required to provide efficient and proficient patient care. Time and knowledge deficits can prevent nurses from developing and implementing quality improvement or evidence-based practice projects. This article reviews a process for professional development of clinical nurses that helped them to define, implement, and analyze quality improvement or evidence-based practice projects. The purpose of this project was to educate advanced clinical nurses to manage a change project from inception to completion, using the Six Sigma DMAIC (Define, Measure, Analyze, Improve, Control) Change Acceleration Process as a framework. One-to-one mentoring and didactic in-services advanced the knowledge, appreciation, and practice of advanced practice clinicians who completed multiple change projects. The projects facilitated clinical practice changes, with improved patient outcomes; a unit cultural shift, with appreciation of quality improvement and evidence-based projects; and engagement with colleagues. Project outcomes were displayed in poster presentations at a hospital exposition for knowledge dissemination. Copyright 2015, SLACK Incorporated.

  1. Uncertainty in project phases: A framework for organisational change management

    DEFF Research Database (Denmark)

    Kreye, Melanie; Balangalibun, Sarah

    2015-01-01

    in the early stage of the change project but was delayed until later phases. Furthermore, the sources of uncertainty were found to be predominantly within the organisation that initiated the change project and connected to the project scope. Based on these findings, propositions for future research are defined......Uncertainty is an integral challenge when managing organisational change projects (OCPs). Current literature highlights the importance of uncertainty; however, falls short of giving insights into the nature of uncertainty and suggestions for managing it. Specifically, no insights exist on how...... uncertainty develops over the different phases of OCPs. This paper presents case-based evidence on different sources of uncertainty in OCPs and how these develop over the different project phases. The results showed some surprising findings as the majority of the uncertainty did not manifest itself...

  2. Imprinted magnetic graphene oxide for the mini-solid phase extraction of Eu (III) from coal mine area

    Science.gov (United States)

    Patra, Santanu; Roy, Ekta; Madhuri, Rashmi; Sharma, Prashant K.

    2017-05-01

    The present work represents the preparation of imprinted magnetic reduced graphene oxide and applied it for the selective removal of Eu (III) from local coal mines area. A simple solid phase extraction method was used for this purpose. The material shows a very high adsorption as well as removal efficiency towards Eu (III), which suggest that the material have potential to be used in future for their real time applications in removal of Eu (III) from complex matrices.

  3. Validation and Improvement of the FEMAXI-JNES Code by Using PIE Data at Extended Burnup. Final Report for FUMEX-III

    International Nuclear Information System (INIS)

    Hirose, Tsutomu; Miura, Hiromichi; Kitamura, Toshiya; Kamimura, Katsuichiro

    2013-01-01

    Japan Nuclear Energy Safety Organization (JNES) has participated in the IAEA FUMEX-III Coordinated Research Project (CRP) on the Improvement of Computer Codes Used for Fuel Behaviour Simulation for the following purpose. 1. Cooperate between member states and exchange information and expertise for understanding of fuel modelling and improvement 2. Develop and improve the FEMAXI-JNES code as an audit code for Japanese safety licensing review of fuel rod design, especially, - High burnup fuel - MOX fuel 3. Set the standard models for the FEMAXI-JNES code to provide best-estimate predictions of the thermal and mechanical performance of LWR fuel rod This is the JNES's final report for the FUMEX-III CRP. During the period of the CRP, JNES has modified pellet swelling and fission gas release models, and demonstrated the predictive capability relative to fuel centerline temperature, fission gas release, fuel rod internal gas pressure, cladding diametral deformation and cladding elongation by comparisons of integral code predictions of these parameters to experimental (measured) data from OECD/NEA IFPE database. (author)

  4. A survey of Type III restriction-modification systems reveals numerous, novel epigenetic regulators controlling phase-variable regulons; phasevarions

    Science.gov (United States)

    Atack, John M; Yang, Yuedong; Jennings, Michael P

    2018-01-01

    Abstract Many bacteria utilize simple DNA sequence repeats as a mechanism to randomly switch genes on and off. This process is called phase variation. Several phase-variable N6-adenine DNA-methyltransferases from Type III restriction-modification systems have been reported in bacterial pathogens. Random switching of DNA methyltransferases changes the global DNA methylation pattern, leading to changes in gene expression. These epigenetic regulatory systems are called phasevarions — phase-variable regulons. The extent of these phase-variable genes in the bacterial kingdom is unknown. Here, we interrogated a database of restriction-modification systems, REBASE, by searching for all simple DNA sequence repeats in mod genes that encode Type III N6-adenine DNA-methyltransferases. We report that 17.4% of Type III mod genes (662/3805) contain simple sequence repeats. Of these, only one-fifth have been previously identified. The newly discovered examples are widely distributed and include many examples in opportunistic pathogens as well as in environmental species. In many cases, multiple phasevarions exist in one genome, with examples of up to 4 independent phasevarions in some species. We found several new types of phase-variable mod genes, including the first example of a phase-variable methyltransferase in pathogenic Escherichia coli. Phasevarions are a common epigenetic regulation contingency strategy used by both pathogenic and non-pathogenic bacteria. PMID:29554328

  5. Improved healing of extraperitoneal intestinal anastomoses in the early phase when surrounded by omentum.

    Science.gov (United States)

    Pierie, J P; de Graaf, P W; van Dijk, M; Renooij, W; van Vroonhoven, T J; Obertop, H

    2000-01-01

    The extra-anatomical position of a cervical oesophagogastrostomy is a reason for impaired anastomotic healing, but transposition of the omentum that is covered with mesothelial cells may be a way to improve that. This hypothesis was tested in a rat model. An end-to-end jejuno-jejunostomy was placed subcutaneously in group I (n = 29), subcutaneously surrounded by omentum in group II (n = 29) and intra-abdominally surrounded by omentum in group III (n = 20). After 3, 7 or 14 days, the rats were sacrificed and bursting pressure (BP) of the anastomosis or jejunum was measured and the hydroxyproline (HP) level was determined. In group I 5/29, in group II 2/29 and in group III 0/20 rats died following anastomotic leakage (nonsignificant) and were excluded from other measurements. BP was decreased after 3 days in group I (60+/-9 mm Hg) compared with group II (101+/-8 mm Hg) and group III (107+/-11 mm Hg) (p = 0.002). After 7 days, BP in groups I (122+/-10 mm Hg) and II (132+/-10 mm Hg) were lower as compared with group III (230+/-8 mm Hg) (p<0.001). Differences in HP levels were not statistically significant between the groups after 3, 7 and 14 days. The healing of intestinal anastomoses in an extraperitoneal position is improved in the early phase only when surrounded by omentum. Copyright 2000 S. Karger AG, Basel

  6. Ultracompact electro-optic phase modulator based on III-V-on-silicon microdisk resonator.

    Science.gov (United States)

    Lloret, J; Kumar, R; Sales, S; Ramos, F; Morthier, G; Mechet, P; Spuesens, T; Van Thourhout, D; Olivier, N; Fédéli, J-M; Capmany, J

    2012-06-15

    A novel ultracompact electro-optic phase modulator based on a single 9 μm-diameter III-V microdisk resonator heterogeneously integrated on and coupled to a nanophotonic waveguide is presented. Modulation is enabled by effective index modification through carrier injection. Proof-of-concept implementation involving binary phase shift keying modulation format is assembled. A power imbalance of ∼0.6  dB between both symbols and a modulation rate up to 1.8 Gbps are demonstrated without using any special driving technique.

  7. Phase 1 of the Hanford Environmental Dose Reconstruction Project

    International Nuclear Information System (INIS)

    1991-08-01

    The work described in this report was prompted by the public's concern about potential effect from the radioactive materials released from the Hanford Site. The Hanford Environmental Dose Reconstruction (HEDR) Project was established to estimate radiation dose the public might have received from the Hanford Site since 1944, when facilities began operating. Phase 1 of the HEDR Project is a ''pilot'' or ''demonstration'' phase. The objectives of this initial phase were to determine whether enough historical information could be found or reconstructed to be used for dose estimation and develop and test conceptual and computational models for calculating credible dose estimates. Preliminary estimates of radiation doses were produced in Phase 1 because they are needed to achieve these objectives. The reader is cautioned that the dose estimates provided in this and other Phase 1 HEDR reports are preliminary. As the HEDR Project continues, the dose estimates will change for at least three reasons: more complete input information for models will be developed; the models themselves will be refined; and the size and shape of the geographic study area will change. This is one of three draft reports that summarize the first phase of the four-phased HEDR Project. This, the Summary Report, is directed to readers who want a general understanding of the Phase 1 work and preliminary dose estimates. The two other reports -- the Air Pathway Report and the Columbia River Pathway Report -- are for readers who understand the radiation dose assessment process and want to see more technical detail. Detailed descriptions of the dose reconstruction process are available in more than 20 supporting reports listed in Appendix A. 32 refs., 46 figs

  8. Randomized phase III study comparing paclitaxel/cisplatin/ gemcitabine and gemcitabine/cisplatin in patients with locally advanced or metastatic urothelial cancer without prior systemic therapy: EORTC intergroup study 30987

    NARCIS (Netherlands)

    J. Bellmunt (Joaquim); H. von der Maase (Hans); G.M. Mead (Graham); I. Skoneczna (I.); M. de Santis (Maria); G. Daugaard (Gedske); J. Boehle; C. Chevreau (Christine); L. Paz-Ares (Luis); L.R. Laufman (Leslie); E. Winquist (Eric); R. Raghavan (Raghu); S. Marreaud (Sandrine); S. Collette (Sandra); R. Sylvester (Richard); R. de Wit (Ronald)

    2012-01-01

    textabstractPurpose: The combination of gemcitabine plus cisplatin (GC) is a standard regimen in patients with locally advanced or metastatic urothelial cancer. A phase I/II study suggested that a three-drug regimen that included paclitaxel had greater antitumor activity and might improve survival.

  9. Radiotherapy in carcinoma of the uterine cervix phase III

    Energy Technology Data Exchange (ETDEWEB)

    Alvarez Villa, O; Reinerio, A; Felipe Castillo, A; Alonso Pantiga, R; Roig, M

    1985-01-01

    Between April 1968 and December 1980, 61 patients with phase III cancer of the cervix were treated. Fifty-six of them were squamous-cell carcinomas and five adenocarcinomas. The treatment consisted of a combination of external irradiation at doses varying between 4,000 and 7,000 rads and intracavitary radiotherapy with doses of 4.000 to 6.000 MHz, according to the schemes of the D.M. Anderson of Houston. The results obtained as far as survival is concerned and calculated by the actuarial method were 40% after five and ten years. The local control rate reached was 74%. The severe complications caused by the treatment reached 8.1%.

  10. Single-crystal neutron diffraction study of ammonium nitrate phase III

    International Nuclear Information System (INIS)

    Choi, C.S.; Prask, H.J.

    1982-01-01

    The crystal structure of ammonium nitrate phase III has been studied at room temperature by neutron diffraction using a single crystal containing 5% KNO 3 in solid-solution form. The space group is Pnma, with a = 7.6772 (4), b = 5.8208 (4), c = 7.1396 (5) A, Z = 4. The final residual after full-matrix least-squares refinement was R = 0.042 for 348 observed reflections. The ammonium ions are thermally disordered into two orientations, displaced by an angle of approximately 42 0 about an axis parallel to the c axis. (Auth.)

  11. 49 CFR 268.21 - Down-selection of one or more Maglev projects for further study and selection of one project for...

    Science.gov (United States)

    2010-10-01

    ... 49 Transportation 4 2010-10-01 2010-10-01 false Down-selection of one or more Maglev projects for... Procedures For Financial Assistance § 268.21 Down-selection of one or more Maglev projects for further study... completion of Phase III of the Maglev Deployment Program, FRA will down-select one or more projects to...

  12. DECOVALEX III/BENCHPAR PROJECTS. Implications of Thermal-Hydro-Mechanical Coupling on the Near-Field Safety of a Nuclear Waste Repository. Report of BMT1A/WP2

    Energy Technology Data Exchange (ETDEWEB)

    Jing, L. [Royal Inst. of Technology, Stockholm (Sweden). Engineering Geology; Nguyen, T.S. [Canadian Nuclear Safety Commission, Ottawa, ON (Canada)] (eds.)

    2005-02-15

    This report presents the works performed for the first phase (BMT1A) of BMT1 of the DECOVALEX III project for the period of 1999-2002. The works of BMT1 is divided into three phases: BMT1A, BMT1B and BMT1C. The BMT1A concerns with calibration of the computer codes with a reference T-H-M experiment at Kamaishi Mine, Japan. The objective is to validate the numerical approaches, computer codes and material models, so that the teams simulating tools are at a comparable level of maturity and sophistication in order to perform the scooping calculations defined in BMT1B and BMT1C. Five teams participated in studying BMT1A: CNSC (Canada), JNC (Japan), IRSN/CEA (France), ANDRA/INERIS (France) and SKI/KTH (Sweden), using FEM approach except the INERIS team (Using FDM approach). A simplified calibration test case of the in-situ experiment was proposed and defined as an axisymmetric model. The case focuses on the THM behaviour along a radial line (with a radial distance r as the coordinate) from the centre of the heater. The desired output parameters are: temperature, radial displacement, pore pressure, water content, the total radial stress and the radial and tangential strains, respectively. Time histories of these output parameters were calculated for both the heating and cooling phases. A number of improvements to the modelling of the Kamaishi Mine heater test were suggested and tested in this study. Although the model geometry is much simplified compared to the field test conditions, improved simulation of the general THM responses were obtained, as compared with the Task 2C results of DECOVALEX II. The measures taken for improvement were: i) Parameter changes (reduced rock mass permeability and rock mass thermal expansion by the SKI/KTH team, and increased thermal expansion coefficient and reduced swelling pressure constant of the buffer by JNC team); ii) Inclusion of the sealing of rock fractures by penetrating bentonite by the SKI/KTH team, which can explain the

  13. Sustainability in the AAP Bronchiolitis Quality Improvement Project.

    Science.gov (United States)

    Shadman, Kristin A; Ralston, Shawn L; Garber, Matthew D; Eickhoff, Jens; Mussman, Grant M; Walley, Susan C; Rice-Conboy, Elizabeth; Coller, Ryan J

    2017-11-01

    Adherence to American Academy of Pediatrics (AAP) bronchiolitis clinical practice guideline recommendations improved significantly through the AAP's multiinstitutional collaborative, the Bronchiolitis Quality Improvement Project (BQIP). We assessed sustainability of improvements at participating institutions for 1 year following completion of the collaborative. Twenty-one multidisciplinary hospital-based teams provided monthly data for key inpatient bronchiolitis measures during baseline and intervention bronchiolitis seasons. Nine sites provided data in the season following completion of the collaborative. Encounters included children younger than 24 months who were hospitalized for bronchiolitis without comorbid chronic illness, prematurity, or intensive care. Changes between baseline-, intervention-, and sustainability-season data were assessed using generalized linear mixed-effects models with site-specific random effects. Differences between hospital characteristics, baseline performance, and initial improvement between sites that did and did not participate in the sustainability season were compared. A total of 2275 discharges were reviewed, comprising 995 baseline, 877 intervention, and 403 sustainability- season encounters. Improvements in all key bronchiolitis quality measures achieved during the intervention season were maintained during the sustainability season, and orders for intermittent pulse oximetry increased from 40.6% (95% confidence interval [CI], 22.8-61.1) to 79.2% (95% CI, 58.0- 91.3). Sites that did and did not participate in the sustainability season had similar characteristics. BQIP participating sites maintained improvements in key bronchiolitis quality measures for 1 year following the project's completion. This approach, which provided an evidence-based best-practice toolkit while building the quality-improvement capacity of local interdisciplinary teams, may support performance gains that persist beyond the active phase of the

  14. Klondike III/Biglow Canyon Wind Integration Project; Final Environmental Impact Statement, September 2006.

    Energy Technology Data Exchange (ETDEWEB)

    United States. Bonneville Power Administration

    2006-09-01

    BPA has been asked by PPM Energy, Inc. to interconnect 300 megawatts (MW) of electricity generated from the proposed Klondike III Wind Project to the Federal Columbia River Transmission System. Orion Energy LLC has also asked BPA to interconnect 400 MW of electricity from its proposed Biglow Canyon Wind Farm, located north and east of the proposed Klondike III Wind Project. (Portland General Electric recently bought the rights to develop the proposed Biglow Canyon Wind Farm from Orion Energy, LLC.) Both wind projects received Site Certificates from the Oregon Energy Facility Siting Council on June 30, 2006. To interconnect these projects, BPA would need to build and operate a 230-kV double-circuit transmission line about 12 miles long, expand one substation and build one new substation. The wind projects would require wind turbines, substation(s), access roads, and other facilities. Two routes for the transmission line are being considered. Both begin at PPM's Klondike Schoolhouse Substation then travel north (Proposed Action) or north and westerly (Middle Alternative) to a new BPA 230-kV substation next to BPA's existing John Day 500-kV Substation. BPA is also considering a No Action Alternative in which BPA would not build the transmission line and would not interconnect the wind projects. The proposed BPA and wind projects would be located on private land, mainly used for agriculture. If BPA decides to interconnect the wind projects, construction of the BPA transmission line and substation(s) could commence as early as the winter of 2006-07. Both wind projects would operate for much of each year for at least 20 years. The proposed projects would generally create no or low impacts. Wildlife resources and local visual resources are the only resources to receive an impact rating other than ''none'' or ''low''. The low to moderate impacts to wildlife are from the expected bird and bat mortality and the cumulative

  15. PROJECT GOVERNANCE – PHASES AND LIFE CYCLE

    Directory of Open Access Journals (Sweden)

    Robbert Titus DEENEN

    2007-01-01

    Full Text Available When talking about projects, the barrier is clear: successful and failed. Some fail due to different reasons, but lack of good project and risk management played a large part. Others succeed largely because of the rigorous and disciplined application of good project practices. But both groups illustrate many points that underline and demonstrate important concepts applicable to current projects. Systematic application of good methods leads to successful outcomes in projects of all types. All projects are fundamentally dependent on people, and human beings are not very different today than we were hundreds, or even thousands, of years ago. This paper uncovers main elements in projects area such as the concepts and governance of projects, with an underline of the main characteristics and the projects phases and life cycle that erase the uncertainty that joins all the projects built at any time.

  16. Projected phase-change memory devices.

    Science.gov (United States)

    Koelmans, Wabe W; Sebastian, Abu; Jonnalagadda, Vara Prasad; Krebs, Daniel; Dellmann, Laurent; Eleftheriou, Evangelos

    2015-09-03

    Nanoscale memory devices, whose resistance depends on the history of the electric signals applied, could become critical building blocks in new computing paradigms, such as brain-inspired computing and memcomputing. However, there are key challenges to overcome, such as the high programming power required, noise and resistance drift. Here, to address these, we present the concept of a projected memory device, whose distinguishing feature is that the physical mechanism of resistance storage is decoupled from the information-retrieval process. We designed and fabricated projected memory devices based on the phase-change storage mechanism and convincingly demonstrate the concept through detailed experimentation, supported by extensive modelling and finite-element simulations. The projected memory devices exhibit remarkably low drift and excellent noise performance. We also demonstrate active control and customization of the programming characteristics of the device that reliably realize a multitude of resistance states.

  17. Ultrasonic Communication Project, Phase 1, FY1999

    Energy Technology Data Exchange (ETDEWEB)

    Haynes, H.D.; Akerman, M.A.; Baylor, V.M.

    2000-06-01

    This Phase 1 project has been successful in identifying, exploring, and demonstrating methods for ultrasonic-based communication with an emphasis on the application of digital signal processing techniques. During the project, at the direction of the agency project monitor, particular attention was directed at sending and receiving ultrasonic data through air and through pipes that would be commonly found in buildings. Efforts were also focused on development of a method for transmitting computer files ultrasonically. New methods were identified and evaluated for ultrasonic communication. These methods are based on a technique called DFS. With DFS, individual alphanumeric characters are broken down into a sequence of bits, and each bit is used to generate a discrete ultrasonic frequency. Characters are then transmitted one-bit-at-a-time, and reconstructed by the receiver. This technique was put into practice through the development of LabVIEW{trademark}VIs. These VIs were integrated with specially developed electronic circuits to provide a system for demonstrating the transmission and reception/reconstruction of typed messages and computer files. Tests were performed to determine the envelope for ultrasound transmission through pipes (with and without water) versus through air. The practical aspects of connections, efficient electronics, impedance matching, and the effect of damping mechanisms were all investigated. These tests resulted in a considerable number of reference charts that illustrate the absorption of ultrasound through different pipe materials, both with and without water, as a function of distance. Ultrasound was found to be least attenuated by copper pipe and most attenuated by PVC pipe. Water in the pipe provides additional damping and attenuation of ultrasonic signals. Dramatic improvements are observed, however, in ultrasound signal strength if the transducers are directly coupled to the water, rather than simply attaching them to the outside of

  18. Thermal Modeling Method Improvements for SAGE III on ISS

    Science.gov (United States)

    Liles, Kaitlin; Amundsen, Ruth; Davis, Warren; McLeod, Shawn

    2015-01-01

    The Stratospheric Aerosol and Gas Experiment III (SAGE III) instrument is the fifth in a series of instruments developed for monitoring aerosols and gaseous constituents in the stratosphere and troposphere. SAGE III will be delivered to the International Space Station (ISS) via the SpaceX Dragon vehicle. A detailed thermal model of the SAGE III payload, which consists of multiple subsystems, has been developed in Thermal Desktop (TD). Many innovative analysis methods have been used in developing this model; these will be described in the paper. This paper builds on a paper presented at TFAWS 2013, which described some of the initial developments of efficient methods for SAGE III. The current paper describes additional improvements that have been made since that time. To expedite the correlation of the model to thermal vacuum (TVAC) testing, the chambers and GSE for both TVAC chambers at Langley used to test the payload were incorporated within the thermal model. This allowed the runs of TVAC predictions and correlations to be run within the flight model, thus eliminating the need for separate models for TVAC. In one TVAC test, radiant lamps were used which necessitated shooting rays from the lamps, and running in both solar and IR wavebands. A new Dragon model was incorporated which entailed a change in orientation; that change was made using an assembly, so that any potential additional new Dragon orbits could be added in the future without modification of the model. The Earth orbit parameters such as albedo and Earth infrared flux were incorporated as time-varying values that change over the course of the orbit; despite being required in one of the ISS documents, this had not been done before by any previous payload. All parameters such as initial temperature, heater voltage, and location of the payload are defined based on the case definition. For one component, testing was performed in both air and vacuum; incorporating the air convection in a submodel that was

  19. Improved detection of chronic myocardial infarction with Fourier amplitude and phase imaging in two projections

    International Nuclear Information System (INIS)

    Akins, E.W.; Scott, E.A.; Williams, C.M.

    1987-01-01

    Twenty-seven patients with 33 chronic myocaridal infarctions underwent MR imaging and radionuclide ventriculography at rest. The radionuclide ventriculographs, in left anterior oblique (LAO) and left posterior oblique (LPO) projections, were analyzed by two independent observers by visual inspection and combined Fourier-transformed amplitude and phase imaging. Only 15 (45%) of the 33 infarctions were detected by visual inspection, but 21 (64%) were detected on the LAO Fourier-transformed images along. Thirty (91%) were detected by using both LAO and LPO Fourier-transformed images. On MR imaging, 28 (85%) of the myocardial infarctions appeared as areas of focal wall thinning. Combined Fourier-transformed amplitude and phase imaging in both LAO and LPO views discloses more myocardial infarctions than visual inspection or LAO Fourier-transformed images alone because inferior infarctions, which are frequently missed in the LAO view, are easily seen in the LPO view

  20. Urban Ecosystem Health in Kathmandu (Nepal) - Phase III | CRDI ...

    International Development Research Centre (IDRC) Digital Library (Canada)

    The two earlier phases of this project (003320 and 101277) led to the creation or strengthening of 18 local stakeholder groups and resulted in a new Animal Slaughtering and Meat Inspection Act, modification of the Nepal Food Act, modification of the Garbage Disposal Act, revisions to the Kathmandu Valley Housing Plan ...

  1. Integrated Sensing & Controls for Coal Gasification - Development of Model-Based Controls for GE's Gasifier & Syngas Cooler. Topical Rerport for Phase III

    Energy Technology Data Exchange (ETDEWEB)

    Kumar, Aditya

    2011-02-17

    This Topical Report for the final Phase III of the program summarizes the results from the Task 3 of the program. In this task, the separately designed extended Kalman Filter (EKF) and model predictive controls (MPC) with ideal sensing, developed in Phase II, were integrated to achieve the overall sensing and control system for the gasification section of an IGCC plant. The EKF and MPC algorithms were updated and re-tuned to achieve closed-loop system stability as well as good steady-state and transient control response. In particular, the performance of the integrated EKF and MPC solution was tested extensively through multiple simulation studies to achieve improved steady-state as well as transient performance, with coal as well as coal-petcoke blended fuel, in the presence of unknown modeling errors as well as sensor errors (noise and bias). The simulation studies demonstrated significant improvements in steady state and transient operation performance, similar to that achieved by MPC with ideal sensors in Phase II of the program.

  2. Safety and hemostatic efficacy of fibrin pad in partial nephrectomy: Results of an open-label Phase I and a randomized, standard-of-care-controlled Phase I/II study

    Directory of Open Access Journals (Sweden)

    Nativ Ofer

    2012-11-01

    Full Text Available Abstract Background Bleeding severity, anatomic location, tissue characteristics, and visibility are common challenges encountered while managing intraoperative bleeding, and conventional hemostatic measures (suture, ligature, and cautery may sometimes be ineffective or impractical. While topical absorbable hemostats (TAH are useful hemostatic adjuvants, each TAH has associated disadvantages. Methods We evaluated the safety and hemostatic efficacy of a new advanced biologic combination product―fibrin pad―to potentially address some gaps associated with TAHs. Fibrin pad was assessed as adjunctive hemostat in open partial nephrectomy in single-center, open-label, Phase I study (N = 10, and as primary hemostat in multicenter, single-blind, randomized, standard-of-care (SOC-controlled Phase I/II study (N = 7 in Israel. It was used to control mild-to-moderate bleeding in Phase I and also spurting arterial bleeding in Phase I/II study. Phase I study assessed safety and Phase I/II study, proportion of successes at 10 min following randomization, analyzed by Fisher exact tests at 5% significance level. Results Phase I (N = 10: All patients completed the study. Hemostasis was achieved within 3–4 min (average = 3.1 min of a single application in all patients. Fibrin pad was found to be safe for human use, with no product-related adverse events reported. Phase I/II (N = 7: Hemostatic success at 10 min (primary endpoint was achieved in 3/4 patients treated with fibrin pad versus 0/3 patients treated with SOC. No clinically significant change in laboratory or coagulation parameters was recorded, except a case of post-procedural hemorrhage with fibrin pad, which was considered serious and related to the fibrin pad treatment, and required re-operation. Although Data Safety Monitoring Board authorized trial continuation, the sponsor decided against proceeding toward an indication for primary treatment of severe arterial

  3. Project NOAH: Regulating modern sea-level rise. Phase II: Jerusalem Underground

    Science.gov (United States)

    Newman, Walter S.; Fairbridge, Rhodes W.

    This proposal builds a high-speed inter-urban express between Jerusalem and Tel Aviv, generates 1500 megawatts of hydroelectric energy, curtails littoral erosion, builds a port along the Israeli Mediterranean coast and demands peaceful cooperation on both sides of the Jordan River. Phase II represents a pilot project demonstrating the feasibility of continuing to regulate world sea-level by a new series of water regulation schemes. Phase I previously described all those projects already completed or underway which have inadvertently and/or unintentionally served the purpose of sea-level regulation. These forms of Phase I sea-level regulation include large and small reservoirs, irrigation projects, water infiltration schemes, farm ponds, and swimming and reflecting pools. All these water storage projects have already exercised a very appreciable brake on 20th century sea-level rise. Phase II outlines a high-visibility proposal which will serve to illustrate the viability of “Project NOAH”.

  4. Room temperature ionic liquids enhanced the speciation of Cr(VI) and Cr(III) by hollow fiber liquid phase microextraction combined with flame atomic absorption spectrometry

    Energy Technology Data Exchange (ETDEWEB)

    Zeng, Chujie, E-mail: cjzeng@126.com [Department of Chemistry and Material, Yulin Normal College, Yulin, Guangxi 537000 (China); Lin, Yao; Zhou, Neng; Zheng, Jiaoting; Zhang, Wei [Department of Chemistry and Material, Yulin Normal College, Yulin, Guangxi 537000 (China)

    2012-10-30

    Highlights: Black-Right-Pointing-Pointer First reported enhancement effect of RTILs in HF-LPME for the speciation of chromium. Black-Right-Pointing-Pointer The addition of RTILs led to 3.5 times improvement of the sensitivity of Cr(VI). Black-Right-Pointing-Pointer The proposed method is a simplicity, sensitivity, low cost, green method. - Abstract: A new method for the speciation of Cr(VI) and Cr(III) based on enhancement effect of room temperature ionic liquids (RTILs) for hollow fiber liquid phase microextraction (HF-LPME) combined with flame atomic absorption spectrometry (FAAS) was developed. Room temperature ionic liquids (RTILs) and diethyldithiocarbamate (DDTC) were used enhancement reagents and chelating reagent, respectively. The addition of room temperature ionic liquids led to 3.5 times improvement in the determination of Cr(VI). In this method, Cr(VI) reacts with DDTC yielding a hydrophobic complex, which is subsequently extracted into the lumen of hollow fiber, whereas Cr(III) is remained in aqueous solutions. The extraction organic phase was injected into FAAS for the determination of Cr(VI). Total Cr concentration was determined after oxidizing Cr(III) to Cr(VI) in the presence of KMnO{sub 4} and using the extraction procedure mentioned above. Cr(III) was calculated by subtracting of Cr(VI) from the total Cr. Under optimized conditions, a detection limit of 0.7 ng mL{sup -1} and an enrichment factor of 175 were achieved. The relative standard deviation (RSD) was 4.9% for Cr(VI) (40 ng mL{sup -1}, n = 5). The proposed method was successfully applied to the speciation of chromium in natural water samples with satisfactory results.

  5. Room temperature ionic liquids enhanced the speciation of Cr(VI) and Cr(III) by hollow fiber liquid phase microextraction combined with flame atomic absorption spectrometry

    International Nuclear Information System (INIS)

    Zeng, Chujie; Lin, Yao; Zhou, Neng; Zheng, Jiaoting; Zhang, Wei

    2012-01-01

    Highlights: ► First reported enhancement effect of RTILs in HF-LPME for the speciation of chromium. ► The addition of RTILs led to 3.5 times improvement of the sensitivity of Cr(VI). ► The proposed method is a simplicity, sensitivity, low cost, green method. - Abstract: A new method for the speciation of Cr(VI) and Cr(III) based on enhancement effect of room temperature ionic liquids (RTILs) for hollow fiber liquid phase microextraction (HF-LPME) combined with flame atomic absorption spectrometry (FAAS) was developed. Room temperature ionic liquids (RTILs) and diethyldithiocarbamate (DDTC) were used enhancement reagents and chelating reagent, respectively. The addition of room temperature ionic liquids led to 3.5 times improvement in the determination of Cr(VI). In this method, Cr(VI) reacts with DDTC yielding a hydrophobic complex, which is subsequently extracted into the lumen of hollow fiber, whereas Cr(III) is remained in aqueous solutions. The extraction organic phase was injected into FAAS for the determination of Cr(VI). Total Cr concentration was determined after oxidizing Cr(III) to Cr(VI) in the presence of KMnO 4 and using the extraction procedure mentioned above. Cr(III) was calculated by subtracting of Cr(VI) from the total Cr. Under optimized conditions, a detection limit of 0.7 ng mL −1 and an enrichment factor of 175 were achieved. The relative standard deviation (RSD) was 4.9% for Cr(VI) (40 ng mL −1 , n = 5). The proposed method was successfully applied to the speciation of chromium in natural water samples with satisfactory results.

  6. Prototypical Rod Consolidation Demonstration Project

    International Nuclear Information System (INIS)

    1993-05-01

    The objective of Phase III of the Prototypical Rod Consolidation Demonstration Project (PRCDP) was to procure, fabricate, assemble, and test the Prototypical Rod Consolidation System as described in the NUS Phase II Final Design Report. This effort required providing the materials, components, and fabricated parts which makes up all of the system equipment. In addition, it included the assembly, installation, and setup of this equipment at the Cold Test Facility. During the Phase III effort the system was tested on a component, subsystem, and system level. Volume IV provides the Operating and Maintenance Manual for the Prototypical Rod Consolidation System that was installed at the Cold Test Facility. This document, Book 1 of Volume IV, discusses: Process overview functional descriptions; Control system descriptions; Support system descriptions; Maintenance system descriptions; and Process equipment descriptions

  7. Prototypical Rod Consolidation Demonstration Project

    International Nuclear Information System (INIS)

    1993-05-01

    The objective of Phase III of the Prototypical Rod Consolidation Demonstration Project (PRCDP) was to procure, fabricate, assemble, and test the Prototypical Rod Consolidation System as described in the NUS Phase II Final Design Report. This effort required providing the materials, components, and fabricated parts which makes up all of the system equipment. In addition, it included the assembly, installation, and setup of this equipment at the Cold Test Facility. During the Phase III effort the system was tested on a component, subsystem, and system level. Volume IV provides the Operating and Maintenance Manual for the Prototypical Rod Consolidation System that was installed at the Cold Test Facility. This document, Book 4 of Volume IV, discusses: Off-normal operating and recovery procedures; Emergency response procedures; Troubleshooting procedures; and Preventive maintenance procedures

  8. Clinical effects of Angelica dahurica dressing on patients with I-II phase pressure sores.

    Science.gov (United States)

    Gong, Fen; Niu, Junzhi; Pei, Xing

    2016-11-02

    Angelica dahurica is a well-known traditional Chinese Medicine (TCM), while little information is available about its effects on pressure sores. We aimed to investigate the clinical effect of Angelica dahurica on patients with I-II phase pressure sores, as well as the underlying mechanism. Patients (n = 98) with phase I and phase II pressure sores were enrolled and randomly assigned to control and treated groups. In addition to holistic nursing, patients in the control group received compound clotrimazole cream, while patients in the treated group received continuous 4 weeks of external application of Angelica dahurica dressing. Therapeutic effect was recorded, along with the levels of interleukin-8 (IL-8), epidermal growth factor (EGF), transforming growth factor (TGF)-β, and vascular endothelial growth factor (VEGF). Besides, HaCaT cells were cultured with different concentrations of Angelica dahurica, and then cell viability, clone formation numbers, cell cycle, and levels of cyclin D1 and cyclin-dependent kinase (CDK) 2 were determined. The total effective rate in the treated group was significantly higher than in the control group. Levels of IL-8, EGF, TGF-β, and VEGF were statistically increased by Angelica dahurica. In addition, the cell viability and clone formation numbers were significantly upregulated by Angelica dahurica in a dose-dependent manner. Also, the percentage of cells in G0/G1 phase, and levels of cyclin D1 and CDK2 were significantly elevated. Our results suggest that Angelica dahurica may provide an effective clinical treatment for I-II phase pressure sores.

  9. Waste Management Process Improvement Project

    International Nuclear Information System (INIS)

    Atwood, J.; Borden, G.; Rangel, G. R.

    2002-01-01

    The Bechtel Hanford-led Environmental Restoration Contractor team's Waste Management Process Improvement Project is working diligently with the U.S. Department of Energy's (DOE) Richland Operations Office to improve the waste management process to meet DOE's need for an efficient, cost-effective program for the management of dangerous, low-level and mixed-low-level waste. Additionally the program must meet all applicable regulatory requirements. The need for improvement was highlighted when a change in the Groundwater/Vadose Zone Integration Project's waste management practices resulted in a larger amount of waste being generated than the waste management organization had been set up to handle

  10. Remedial Design/Remedial Action Work Plan for Operable Units 6-05 and 10-04, Phase III

    Energy Technology Data Exchange (ETDEWEB)

    R. P. Wells

    2006-09-19

    The remedial design/remedial action for Operable Unit 6-05 (Waste Area Group 6) and Operable Unit 10-04 (Waste Area Group 10) - collectively called Operable Unit 10-04 has been divided into four phases. Phase I consists of developing and implementing institutional controls at Operable Unit 10-04 sites and developing and implementing Idaho National Laboratory-wide plans for both institutional controls and ecological monitoring. Phase II will remediate sites contaminated with trinitrotoluene and Royal Demolition Explosive. Phase III will remediate lead contamination at a gun range, and Phase IV will remediate hazards from unexploded ordnance. This Phase III remedial Design/Remedial Action Work Plan addresses the remediation of lead-contaminated soils found at the Security Training Facility (STF)-02 Gun Range located at the Idaho National Laboratory. Remediation of the STF-02 Gun Range will include excavating contaminated soils; physically separating copper and lead for recycling; returning separated soils below the remediation goal to the site; stabilizing contaminated soils, as required, and disposing of the separated soils that exceed the remediation goal; encapsulating and disposing of creosote-contaminated railroad ties and power poles; removing and disposing of the wooden building and asphalt pads found at the STF-02 Gun Range; sampling and analyzing soil to determine the excavation requirements; and when the remediation goals have been met, backfilling and contouring excavated areas and revegetating the affected area.

  11. Stratospheric Aerosol and Gas Experiment, SAGE III on ISS, An Earth Science Mission on the International Space Station, Schedule Risk Analysis, A Project Perspective

    Science.gov (United States)

    Bonine, Lauren

    2015-01-01

    The presentation provides insight into the schedule risk analysis process used by the Stratospheric Aerosol and Gas Experiment III on the International Space Station Project. The presentation focuses on the schedule risk analysis process highlighting the methods for identification of risk inputs, the inclusion of generic risks identified outside the traditional continuous risk management process, and the development of tailored analysis products used to improve risk informed decision making.

  12. Unexpected Relationships and Inbreeding in HapMap Phase III Populations

    Science.gov (United States)

    Stevens, Eric L.; Baugher, Joseph D.; Shirley, Matthew D.; Frelin, Laurence P.; Pevsner, Jonathan

    2012-01-01

    Correct annotation of the genetic relationships between samples is essential for population genomic studies, which could be biased by errors or omissions. To this end, we used identity-by-state (IBS) and identity-by-descent (IBD) methods to assess genetic relatedness of individuals within HapMap phase III data. We analyzed data from 1,397 individuals across 11 ethnic populations. Our results support previous studies (Pemberton et al., 2010; Kyriazopoulou-Panagiotopoulou et al., 2011) assessing unknown relatedness present within this population. Additionally, we present evidence for 1,657 novel pairwise relationships across 9 populations. Surprisingly, significant Cotterman's coefficients of relatedness K1 (IBD1) values were detected between pairs of known parents. Furthermore, significant K2 (IBD2) values were detected in 32 previously annotated parent-child relationships. Consistent with a hypothesis of inbreeding, regions of homozygosity (ROH) were identified in the offspring of related parents, of which a subset overlapped those reported in previous studies (Gibson et al. 2010; Johnson et al. 2011). In total, we inferred 28 inbred individuals with ROH that overlapped areas of relatedness between the parents and/or IBD2 sharing at a different genomic locus between a child and a parent. Finally, 8 previously annotated parent-child relationships had unexpected K0 (IBD0) values (resulting from a chromosomal abnormality or genotype error), and 10 previously annotated second-degree relationships along with 38 other novel pairwise relationships had unexpected IBD2 (indicating two separate paths of recent ancestry). These newly described types of relatedness may impact the outcome of previous studies and should inform the design of future studies relying on the HapMap Phase III resource. PMID:23185369

  13. Integrated Monitoring and Surveillance System demonstration project. Phase 2 accomplishments

    International Nuclear Information System (INIS)

    Aumeier, S.E.; Walters, B.G.; Singleterry, R.C.

    1997-01-01

    The paper presents the results of the Integrated Monitoring and Surveillance System (IMSS) demonstration project Phase 2 efforts. the rationale behind IMSS development is reviewed and progress in each of the 5 basic tasks is detailed. Significant results include further development of the data acquisition system and procurement of necessary hardware/software, options and associated costs for plutonium canning systems and gloveboxes, initiation of facility modifications, determination of possibly affected facility documentation, results from sensor system trade study, and preliminary storage configuration designs. Resources invested during Phase 1 and Phase 2 are summarized and budgetary requirements for completion of Phase 3 presented. The results show that the IMSS demonstration project team has met and in many cases exceeded the commitments made for Phase 2 deliverables

  14. Project inspection using mobile technology - phase I : an investigation into existing business processes and areas for improvement using mobile technology.

    Science.gov (United States)

    2013-08-01

    As mobile technology becomes widely available and affordable, transportation agencies can use this technology to : streamline operations involved within project inspection. This research, conducted in two phases, identified : opportunities for proces...

  15. Physical Improvements in Exciter/Igniter Units, Phase II

    Data.gov (United States)

    National Aeronautics and Space Administration — The proposed Phase 2 project consists of the physical integration of our Phase 1 small, compact exciter with a "flight like" igniter or spark plug capable of...

  16. Improvement of Computer Codes Used for Fuel Behaviour Simulation (FUMEX-III). Report of a Coordinated Research Project 2008-2012

    International Nuclear Information System (INIS)

    2013-03-01

    It is fundamental to the future of nuclear power that reactors can be run safely and economically to compete with other forms of power generation. As a consequence, it is essential to develop the understanding of fuel performance and to embody that knowledge in codes to provide best estimate predictions of fuel behaviour. This in turn leads to a better understanding of fuel performance, a reduction in operating margins, flexibility in fuel management and improved operating economics. The IAEA has therefore embarked on a series of programmes addressing different aspects of fuel behaviour modelling with the following objectives: - To assess the maturity and prediction capabilities of fuel performance codes, and to support interaction and information exchange between countries with code development and application needs (FUMEX series); - To build a database of well defined experiments suitable for code validation in association with the OECD Nuclear Energy Agency (OECD/NEA); - To transfer a mature fuel modelling code to developing countries, to support teams in these countries in their efforts to adapt the code to the requirements of particular reactors, and to provide guidance on applying the code to reactor operation and safety assessments; - To provide guidelines for code quality assurance, code licensing and code application to fuel licensing. This report describes the results of the coordinated research project on the ''Improvement of computer codes used for fuel behaviour simulation (FUMEX-III)''. This programme was initiated in 2008 and completed in 2012. It followed previous programmes on fuel modelling: D-COM 1982-1984, FUMEX 1993-1996 and FUMEX-II 2002-2006. The participants used a mixture of data derived from commercial and experimental irradiation histories, in particular data designed to investigate the mechanical interactions occurring in fuel during normal, transient and severe transient operation. All participants carried out calculations on priority

  17. Stability considerations of permanent magnet quadrupoles for CESR phase-III upgrade

    Directory of Open Access Journals (Sweden)

    W. Lou

    1998-06-01

    Full Text Available The Cornell electron storage ring (CESR phase-III upgrade plan includes very strong permanent magnet quadrupoles in front of the cryostat for the superconducting quadrupoles and physically as close as possible to the interaction point. Together with the superconducting quadrupoles, they provide tighter vertical focusing at the interaction point. The quadrupoles are built with neodymium iron boron (NdFeB material and operate inside the 15 kG solenoid field. Requirements on the field quality and stability of these quadrupoles are discussed and test results are presented.

  18. Fuel Rod Consolidation Project: Phase 2, Final report: Volume 5, Operations and maintenance manual

    International Nuclear Information System (INIS)

    1988-01-01

    The purpose of this manual is to describe the function, installation, operation and maintenance of the Fuel Rod Consolidation System. This Document is preliminary and must be updated to incorporate any modifications to the mechanical and electrical systems that are performed during construction. Any changes and specific references related to the software requirements will be provided as the software is developed in Phase III. Setpoints related to equipment positions as a function of resolver and position transducer readings will also be provided in Phase III. References such as vendor supplied Operating and Maintenance Manuals for vendor components and assemblies are not available until a receipt of a purchase order. These references will become an integral part of this manual during the construction phase

  19. Superior outcome of women with stage I/II cutaneous melanoma: Pooled analysis of four European organisation for research and treatment of cancer phase III trials

    NARCIS (Netherlands)

    A. Joosse (Arjen); S. Collette (Sandra); S. Suciu (Stefan); T.E.C. Nijsten (Tamar); F.J. Lejeune (Ferdy); U.R. Kleeberg (Ulrich); J.W.W. Coebergh (Jan Willem); A.M.M. Eggermont (Alexander); E.G.E. de Vries (Elisabeth)

    2012-01-01

    textabstractPurpose: Several studies observed a female advantage in the prognosis of cutaneous melanoma, for which behavioral factors or an underlying biologic mechanism might be responsible. Using complete and reliable follow-up data from four phase III trials of the European Organisation for

  20. Steam generator reliability improvement project

    International Nuclear Information System (INIS)

    Blomgren, J.C.; Green, S.J.

    1987-01-01

    Upon successful completion of its research and development technology transfer program, the Electric Power Research Institute's Steam Generator Owners Group (SGOG II) will disband in December 1986 and be replaced in January 1987 by a successor project, the Steam Generator Reliability Project (SGRP). The new project, funded in the EPRI base program, will continue the emphasis on reliability and life extension that was carried forward by SGOG II. The objectives of SGOG II have been met. Causes and remedies have been identified for tubing corrosion problems, such as stress corrosion cracking and pitting, and steam generator technology has been improved in areas such as tube wear prediction and nondestructive evaluation (NDE). These actions have led to improved reliability of steam generators. Now the owners want to continue with a centrally managed program that builds on what has been learned. The goal is to continue to improve steam generator reliability and solve small problems before they become large problems

  1. Steam generator reliability improvement project

    International Nuclear Information System (INIS)

    Blomgren, J.C.; Green, S.J.

    1987-01-01

    Upon successful completion of its research and development technology transfer program, the Electric Power Research Institute's (EPRI's) Steam Generator Owners Group (SGOG II) will disband in December 1986, and be replaced in January 1987, by a successor project, the Steam Generator Reliability Project (SGRP). The new project, funded in the EPRI base program, will continue to emphasize reliability and life extension, which were carried forward by SGOG II. The objectives of SGOG II have been met. Causes and remedies have been identified for tubing corrosion problems such as stress corrosion cracking and pitting, and steam generator technology has been improved in areas such as tube wear prediction and nondestructive evaluation. These actions have led to improved reliability of steam generators. Now the owners want to continue with a centrally managed program that builds on what has been learned. The goal is to continue to improve steam generator reliability and to solve small problems before they become large problems

  2. Gamma-ray CT from incomplete projections for two-phase pipe flow.

    Science.gov (United States)

    Xin, S; Wang, H X

    2017-02-01

    A low-energy low-dose γ-ray computed tomography (CT) system used in the gas-liquid two-phase pipe flow measurement has been studied at Tianjin University in recent years. The γ-ray CT system, having a third-generation X-ray CT scanning configuration, is comprised of one 300mCi 241 Am source and 17 CdZnTe detector units and achieves a spatial image resolution of about 7 mm. It is primarily intended to measure the two-phase pipe flow and provide improvement suggestions for industrial CT system. Recently we improve the design for image reconstruction from incomplete projection to optimize the scanning parameters and reduce the radiation dose. First, tomographic problem from incomplete projections is briefly described. Next, a system structure and a hardware circuit design are listed and explained, especially on time parameter setting of the pulse shaper. And then a detailed system analysis is provided in Section II, mainly focusing on spatial resolution, temporal resolution, system noise, and imaging algorithm. Finally, we carry on necessary static and dynamic experiments in a full scan (360°) and two sets of partial scan reconstruction tests to determine the feasibility of this γ-ray CT system for reconstructing the images from insufficient projections. And based on an A-variable algebraic reconstruction technique method, a specially designed algorithm, we evaluate the system performance and noise level of this CT system working quantitatively and qualitatively. Results of dynamic test indicate that the acceptable results can be acquired using a multi-source γ-ray CT system with the same parameters when the flow rate is less than 0.04 m/s and the imaging speed is slower than 33 frames/s.

  3. Effect of silodosin on specific urinary symptoms associated with benign prostatic hyperplasia: analysis of international prostate symptom scores in 2 phase III clinical studies

    OpenAIRE

    Gittelman, Marc C; Marks, Leonard S; Hill, Lawrence A; Volinn, Weining; Hoel, Gary

    2010-01-01

    Marc C Gittelman1, Leonard S Marks2, Lawrence A Hill3, Weining Volinn3, Gary Hoel31South Florida Medical Research, Aventura, Florida, USA; 2University of California at Los Angeles and Urological Sciences Research Foundation, Los Angeles, California, USA; 3Watson Laboratories, Salt Lake City, Utah, USAPurpose: Pooled results from 2 randomized, placebo-controlled, US phase III studies (NCT00224107, NCT00224120) showed that silodosin, a uroselective α-blocker, significantly improved In...

  4. An Application of Graphical Approach to Construct Multiple Testing Procedure in a Hypothetical Phase III Design

    Directory of Open Access Journals (Sweden)

    Naitee eTing

    2014-01-01

    Full Text Available Many multiple testing procedures (MTP have been developed in recent years. Among these new procedures, the graphical approach is flexible and easy to communicate with non-statisticians. A hypothetical Phase III clinical trial design is introduced in this manuscript to demonstrate how graphical approach can be applied in clinical product development. In this design, an active comparator is used. It is thought that this test drug under development could potentially be superior to this comparator. For comparison of efficacy, the primary endpoint is well established and widely accepted by regulatory agencies. However, an important secondary endpoint based on Phase II findings looks very promising. The target dose may have a good opportunity to deliver superiority to the comparator. Furthermore, a lower dose is included in case the target dose may demonstrate potential safety concerns. This Phase III study is designed as a non-inferiority trial with two doses, and two endpoints. This manuscript will illustrate how graphical approach is applied to this design in handling multiple testing issues.

  5. Improving Project Manufacturing Coordination

    Directory of Open Access Journals (Sweden)

    Korpivaara Ville

    2014-09-01

    Full Text Available The objective of this research is to develop firms’ project manufacturing coordination. The development will be made by centralizing the manufacturing information flows in one system. To be able to centralize information, a deep user need assessment is required. After user needs have been identified, the existing system will be developed to match these needs. The theoretical background is achieved through exploring the literature of project manufacturing, development project success factors and different frameworks and tools for development project execution. The focus of this research is rather in customer need assessment than in system’s technical expertise. To ensure the deep understanding of customer needs this study is executed by action research method. As a result of this research the information system for project manufacturing coordination was developed to respond revealed needs of the stakeholders. The new system improves the quality of the manufacturing information, eliminates waste in manufacturing coordination processes and offers a better visibility to the project manufacturing. Hence it provides a solid base for the further development of project manufacturing.

  6. Integrated monitoring and surveillance system demonstration project: Phase I accomplishments

    International Nuclear Information System (INIS)

    Aumeier, S.E.; Walters, B.G.; Crawford, D.C.

    1997-01-01

    The authors present the results of the Integrated Monitoring and Surveillance System (IMSS) demonstration project Phase I efforts. The rationale behind IMSS development is reviewed and progress in each of the 5 basic tasks is detailed. Significant results include decisions to use Echelon LonWorks networking protocol and Microsoft Access for the data system needs, a preliminary design for the plutonium canning system glovebox, identification of facilities and materials available for the demonstration, determination of possibly affected facility documentation, and a preliminary list of available sensor technologies. Recently imposed changes in the overall project schedule and scope are also discussed and budgetary requirements for competition of Phase II presented. The results show that the IMSS demonstration project team has met and in many cases exceeded the commitments made for Phase I deliverables

  7. Project Hanford management contract quality improvement project management plan; TOPICAL

    International Nuclear Information System (INIS)

    ADAMS, D.E.

    1999-01-01

    On July 13, 1998, the U.S. Department of Energy, Richland Operations Office (DOE-RL) Manager transmitted a letter to Fluor Daniel Hanford, Inc. (FDH) describing several DOE-RL identified failed opportunities for FDH to improve the Quality Assurance (QA) Program and its implementation. In addition, DOE-RL identified specific Quality Program performance deficiencies. FDH was requested to establish a periodic reporting mechanism for the corrective action program. In a July 17, 1998 response to DOE-RL, FDH agreed with the DOE concerns and committed to perform a comprehensive review of the Project Hanford Management Contract (PHMC) QA Program during July and August, 1998. As a result, the Project Hanford Management Contract Quality Improvement Plan (QIP) (FDH-3508) was issued on October 21, 1998. The plan identified corrective actions based upon the results of an in-depth Quality Program Assessment. Immediately following the scheduled October 22, 1998, DOE Office of Enforcement and Investigation (EH-10) Enforcement Conference, FDH initiated efforts to effectively implement the QIP corrective actions. A Quality Improvement Project (QI Project) leadership team was assembled to prepare a Project Management Plan for this project. The management plan was specifically designed to engage a core team and the support of representatives from FDH and the major subcontractors (MSCs) to implement the QIP initiatives; identify, correct, and provide feedback as to the root cause for deficiency; and close out the corrective actions. The QI Project will manage and communicate progress of the process

  8. High Resolution Air Quality Forecasts in the Western Mediterranean area within the MACC, MACC-II and MACC-III European projects

    Energy Technology Data Exchange (ETDEWEB)

    Cansado, A.; Martinez, I.; Morales, T.

    2015-07-01

    The European Earth observation programme Copernicus, formerly known as GMES (Global Monitoring for Environment and Security) is establishing a core global and regional environmental atmospheric service as a component of the Europes Copernicus/GMES initiative through successive R and D projects led by ECMWF (European Center for Medium-range Weather Forecasting) and funded by the 6th and 7th European Framework Programme for Research and Horizon 2020 Programme: GEMS, MACC, MACC-II and MACC-III. AEMET (Spanish State Meteorological Agency) has participated in the projects MACC and MACC-II and continues participating in MACC-III (http://atmosphere.copernicus.eu). AEMET has contributed to those projects by generating highresolution (0.05 degrees) daily air-quality forecasts for the Western Mediterranean up to 48 hours aiming to analyse the dependence of the quality of forecasts on resolution. We monitor the evolution of different chemical species such as NO{sub 2}, O{sub 3}, CO y SO{sub 2} at surface and different vertical levels using the global model MOCAGE and the MACC Regional Ensemble forecasts as chemical boundary conditions. We will show different case-studies, where the considered chemical species present high values and will show a validation of the air-quality by comparing to some of the available air-quality observations (EMEP/GAW, regional -autonomous communities- and local -city councils- air-quality monitoring networks) over the forecast domain. The aim of our participation in these projects is helping to improve the understanding of the processes involved in the air-quality forecast in the Mediterranean where special factors such as highly populated areas together with an intense solar radiation make air-quality forecasting particularly challenging. (Author)

  9. High Resolution Air Quality Forecasts in the Western Mediterranean area within the MACC, MACC-II and MACC-III European projects

    Energy Technology Data Exchange (ETDEWEB)

    Cansado, A.; Martinez, I.; Morales, T.

    2015-07-01

    The European Earth observation programme Copernicus, formerly known as GMES (Global Monitoring for Environment and Security) is establishing a core global and regional environmental atmospheric service as a component of the Europe’s Copernicus/GMES initiative through successive R&D projects led by ECMWF (European Center for Medium-range Weather Forecasting) and funded by the 6th and 7th European Framework Programme for Research and Horizon 2020 Programme: GEMS, MACC, MACC-II and MACC-III. AEMET (Spanish State Meteorological Agency) has participated in the projects MACC and MACC-II and continues participating in MACC-III (http://atmosphere.copernicus.eu). AEMET has contributed to those projects by generating highresolution (0.05 degrees) daily air-quality forecasts for the Western Mediterranean up to 48 hours aiming to analyse the dependence of the quality of forecasts on resolution. We monitor the evolution of different chemical species such as NO2, O3, CO y SO2 at surface and different vertical levels using the global model MOCAGE and the MACC Regional Ensemble forecasts as chemical boundary conditions. We will show different case-studies, where the considered chemical species present high values and will show a validation of the air-quality by comparing to some of the available air-quality observations (EMEP/GAW, regional -autonomous communities- and local -city councils- air-quality monitoring networks) over the forecast domain. The aim of our participation in these projects is helping to improve the understanding of the processes involved in the air-quality forecast in the Mediterranean where special factors such as highly populated areas together with an intense solar radiation make air-quality forecasting particularly challenging. (Author)

  10. Comprehensive analysis of published phase I/II clinical trials between 1990-2010 in osteosarcoma and Ewing sarcoma confirms limited outcomes and need for translational investment

    Directory of Open Access Journals (Sweden)

    van Maldegem Annemiek M

    2012-01-01

    Full Text Available Abstract Background High grade primary bone sarcomas are rare cancers that affect mostly children and young adults. Osteosarcoma and Ewing sarcoma are the most common histological subtypes in this age group, with current multimodality treatment strategies achieving 55-70% overall survival. As there remains an urgent need to develop new therapeutic interventions, we have reviewed published phase I/II trials that have been reported for osteosarcoma and Ewing sarcoma in the last twenty years. Results We conducted a literature search for clinical trials between 1990 and 2010, either for trials enrolling bone sarcoma patients as part of a general sarcoma indication or trials specifically in osteosarcoma and Ewing sarcoma. We identified 42 clinical trials that fulfilled our search criteria for general sarcoma that enrolled these patient groups, and eight and twenty specific trials for Ewing and osteosarcoma patients, respectively. For the phase I trials which enrolled different tumour types our results were incomplete, because the sarcoma patients were not mentioned in the PubMed abstract. A total of 3,736 sarcoma patients were included in these trials over this period, 1,114 for osteosarcoma and 1,263 for Ewing sarcoma. As a proportion of the worldwide disease burden over this period, these numbers reflect a very small percentage of the potential patient recruitment, approximately 0.6% for Ewing sarcoma and 0.2% for osteosarcoma. However, these data show an increase in recent activity overall and suggest there is still much room for improvement in the current trial development structures. Conclusion Lack of resources and commercial investment will inevitably limit opportunity to develop sufficiently rapid improvements in clinical outcomes. International collaboration exists in many well founded co-operative groups for phase III trials, but progress may be more effective if there were also more investment of molecular and translational research into

  11. Promoting mobility and reducing length of stay in hospitalized general medicine patients: A quality-improvement project.

    Science.gov (United States)

    Hoyer, Erik H; Friedman, Michael; Lavezza, Annette; Wagner-Kosmakos, Kathleen; Lewis-Cherry, Robin; Skolnik, Judy L; Byers, Sherrie P; Atanelov, Levan; Colantuoni, Elizabeth; Brotman, Daniel J; Needham, Dale M

    2016-05-01

    To determine whether a multidisciplinary mobility promotion quality-improvement (QI) project would increase patient mobility and reduce hospital length of stay (LOS). Implemented using a structured QI model, the project took place between March 1, 2013 and March 1, 2014 on 2 general medicine units in a large academic medical center. There were 3352 patients admitted during the QI project period. The Johns Hopkins Highest Level of Mobility (JH-HLM) scale, an 8-point ordinal scale ranging from bed rest (score = 1) to ambulating ≥250 feet (score = 8), was used to quantify mobility. Changes in JH-HLM scores were compared for the first 4 months of the project (ramp-up phase) versus 4 months after project completion (post-QI phase) using generalized estimating equations. We compared the relative change in median LOS for the project months versus 12 months prior among the QI units, using multivariable linear regression analysis adjusting for 7 demographic and clinically relevant variables. Comparing the ramp-up versus post-QI phases, patients reaching JH-HLM's ambulation status increased from 43% to 70% (P mobility scores between admission and discharge increased from 32% to 45% (P 7 days), were associated with a significantly greater adjusted median reduction in LOS of 1.11 (95% CI: -1.53 to -0.65, P mobility was not associated with an increase in injurious falls compared to 12 months prior on the QI units (P = 0.73). Active prevention of a decline in physical function that commonly occurs during hospitalization may be achieved with a structured QI approach. In an adult medicine population, our QI project was associated with improved mobility, and this may have contributed to a reduction in LOS, particularly for more complex patients with longer expected hospital stay. Journal of Hospital Medicine 2016. © 2016 Society of Hospital Medicine. © 2016 Society of Hospital Medicine.

  12. The Barselina Project Phase 4 Summary report. Ignalina Unit 2 Probabilistic Safety Analysis

    Energy Technology Data Exchange (ETDEWEB)

    Johansson, Gunnar [ES-Konsult AB, Stockholm (Sweden); Hellstroem, P. [RELCON AB, Solna (Sweden); Zheltobriuch, G.; Bagdonas, A. [Ignalina Power Plant, Visaginas (Lithuania)

    1996-12-01

    The Barselina Project was initiated in the summer of 1991. The project is a multilateral co-operation between Lithuania, Russia and Sweden. The long range objective is to establish common perspectives and unified bases for assessment of severe accident risks and needs for remedial measures for the RBMK reactors. The Swedish BWR Barsebaeck is used as reference plant and the Lithuanian RBMK Ignalina as application plant. During phase 3, from March, 1993 to June, 1994, a full scope Probabilistic Safety Analysis (PSA) model of the Ignalina Nuclear Power Plant unit 2 (INPP-2) was developed to identify possible safety improvement of risk importance. The probabilistic methodology was applied on a plant specific basis for a channel type reactor of RBMK design. To increase the realism of the risk model a set of deterministic analyses were performed and plant/RBMK-specific data bases were developed and used. A general concept for analysing this type of reactor was developed. During phase 4, July 1994 to September 1996, the PSA was further developed, taking into account plant changes, improved modeling methods and extended plant information concerning dependencies (area events, dynamic effects, electrical and signal dependencies). The updated model is quantified and new results and conclusions are evaluated.

  13. Study Protocol: Phase III single-blinded fast-track pragmatic randomised controlled trial of a complex intervention for breathlessness in advanced disease

    Directory of Open Access Journals (Sweden)

    Brafman-Kennedy Barbara

    2011-05-01

    Full Text Available Abstract Background Breathlessness in advanced disease causes significant distress to patients and carers and presents management challenges to health care professionals. The Breathlessness Intervention Service (BIS seeks to improve the care of breathless patients with advanced disease (regardless of cause through the use of evidence-based practice and working with other healthcare providers. BIS delivers a complex intervention (of non-pharmacological and pharmacological treatments via a multi-professional team. BIS is being continuously developed and its impact evaluated using the MRC's framework for complex interventions (PreClinical, Phase I and Phase II completed. This paper presents the protocol for Phase III. Methods/Design Phase III comprises a pragmatic, fast-track, single-blind randomised controlled trial of BIS versus standard care. Due to differing disease trajectories, the service uses two broad service models: one for patients with malignant disease (intervention delivered over two weeks and one for patients with non-malignant disease (intervention delivered over four weeks. The Phase III trial therefore consists of two sub-protocols: one for patients with malignant conditions (four week protocol and one for patients with non-malignant conditions (eight week protocol. Mixed method interviews are conducted with patients and their lay carers at three to five measurement points depending on randomisation and sub-protocol. Qualitative interviews are conducted with referring and non-referring health care professionals (malignant disease protocol only. The primary outcome measure is 'patient distress due to breathlessness' measured on a numerical rating scale (0-10. The trial includes economic evaluation. Analysis will be on an intention to treat basis. Discussion This is the first evaluation of a breathlessness intervention for advanced disease to have followed the MRC framework and one of the first palliative care trials to use fast

  14. SmartPark Technology Demonstration Project, Phase II: Final Report

    Science.gov (United States)

    2018-05-01

    The purpose of FMCSA's SmartPark project was to determine the feasibility of a technology for providing truck parking space availability information in real time to truckers on the road. SmartPark consisted of two phases. Phase I was a field operatio...

  15. Acoustic Detection of Faults and Degradation in a High-Bypass Turbofan Engine during VIPR Phase III Testing

    Science.gov (United States)

    Boyle, Devin K.

    2017-01-01

    The Vehicle Integrated Propulsion Research (VIPR) Phase III project was executed at Edwards Air Force Base, California, by the National Aeronautics and Space Administration and several industry, academic, and government partners in the summer of 2015. One of the research objectives was to use external radial acoustic microphone arrays to detect changes in the noise characteristics produced by the research engine during volcanic ash ingestion and seeded fault insertion scenarios involving bleed air valves. Preliminary results indicate the successful acoustic detection of suspected degradation as a result of cumulative exposure to volcanic ash. This detection is shown through progressive changes, particularly in the high-frequency content, as a function of exposure to greater cumulative quantities of ash. Additionally, detection of the simulated failure of the 14th stage stability bleed valve and, to a lesser extent, the station 2.5 stability bleed valve, to their fully-open fail-safe positions was achieved by means of spectral comparisons between nominal (normal valve operation) and seeded fault scenarios.

  16. Projecting future expansion of invasive species: comparing and improving methodologies for species distribution modeling.

    Science.gov (United States)

    Mainali, Kumar P; Warren, Dan L; Dhileepan, Kunjithapatham; McConnachie, Andrew; Strathie, Lorraine; Hassan, Gul; Karki, Debendra; Shrestha, Bharat B; Parmesan, Camille

    2015-12-01

    Modeling the distributions of species, especially of invasive species in non-native ranges, involves multiple challenges. Here, we developed some novel approaches to species distribution modeling aimed at reducing the influences of such challenges and improving the realism of projections. We estimated species-environment relationships for Parthenium hysterophorus L. (Asteraceae) with four modeling methods run with multiple scenarios of (i) sources of occurrences and geographically isolated background ranges for absences, (ii) approaches to drawing background (absence) points, and (iii) alternate sets of predictor variables. We further tested various quantitative metrics of model evaluation against biological insight. Model projections were very sensitive to the choice of training dataset. Model accuracy was much improved using a global dataset for model training, rather than restricting data input to the species' native range. AUC score was a poor metric for model evaluation and, if used alone, was not a useful criterion for assessing model performance. Projections away from the sampled space (i.e., into areas of potential future invasion) were very different depending on the modeling methods used, raising questions about the reliability of ensemble projections. Generalized linear models gave very unrealistic projections far away from the training region. Models that efficiently fit the dominant pattern, but exclude highly local patterns in the dataset and capture interactions as they appear in data (e.g., boosted regression trees), improved generalization of the models. Biological knowledge of the species and its distribution was important in refining choices about the best set of projections. A post hoc test conducted on a new Parthenium dataset from Nepal validated excellent predictive performance of our 'best' model. We showed that vast stretches of currently uninvaded geographic areas on multiple continents harbor highly suitable habitats for parthenium

  17. Development of an Improved Process for Installation Projects of High Technology Manufacturing Equipment

    Energy Technology Data Exchange (ETDEWEB)

    Quintana, Sarah V. [Los Alamos National Lab. (LANL), Los Alamos, NM (United States)

    2014-04-30

    High technology manufacturing equipment is utilized at Los Alamos National Laboratory (LANL) to support nuclear missions. This is undertaken from concept initiation where equipment is designed and then taken through several review phases, working closely with system engineers (SEs) responsible for each of the affected systems or involved disciplines (from gasses to HVAC to structural, etc.). After the design is finalized it moves to procurement and custom fabrication of the equipment and equipment installation, including all of the paperwork involved. Not only are the engineering and manufacturing aspects important, but also the scheduling, financial forecasting, and planning portions that take place initially and are sometimes modified as the project progresses should requirements, changes or additions become necessary. The process required to complete a project of this type, including equipment installation, is unique and involves numerous steps to complete. These processes can be improved and recent work on the Direct Current Arc (DC Arc) Glovebox Design, Fabrication and Installation Project provides an opportunity to identify some important lessons learned (LL) that can be implemented in the future for continued project improvement and success.

  18. Conceptual design report for environmental, safety and health phase III FY-91 line item

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1988-09-01

    The Mound Facility (Mound), located in Miamisburg, Ohio, is a Department of Energy (DOE) development and production facility performing support work for DOE`s weapons and energy-related programs. EG&G Mound Applied Technologies (EG&G) is the Operating Contractor (OC) for this Government-Owned, Contractor-Operated (GOCO) facility. The work performed at Mound emphasizes nuclear energy and explosives technology. Mound is currently implementing an Environmental, Safety, and Health (ES&H) Program designed to protect its employees, the public, and the environment from adverse effects caused by the facility`s activities. Design has been completed, and construction is in progress for Phase I of this multiphase program. Phase II has been submitted for fiscal year (FY) 89 funding and Phase IV is being submitted as an FY 92 line item. This Conceptual Design Report (CDR) addresses Phase III of the ES&H program.

  19. Design of the randomized, Phase III, QUAZAR AML Maintenance trial of CC-486 (oral azacitidine) maintenance therapy in acute myeloid leukemia.

    Science.gov (United States)

    Roboz, Gail J; Montesinos, Pau; Selleslag, Dominik; Wei, Andrew; Jang, Jun-Ho; Falantes, Jose; Voso, Maria T; Sayar, Hamid; Porkka, Kimmo; Marlton, Paula; Almeida, Antonio; Mohan, Sanjay; Ravandi, Farhad; Garcia-Manero, Guillermo; Skikne, Barry; Kantarjian, Hagop

    2016-02-01

    Older patients with acute myeloid leukemia (AML) have worse rates of complete remission and shorter overall survival than younger patients. The epigenetic modifier CC-486 is an oral formulation of azacitidine with promising clinical activity in patients with AML in Phase I studies. The Phase III, randomized, double-blind, placebo-controlled QUAZAR AML Maintenance trial (CC-486-AML-001) examines CC-486 maintenance therapy (300 mg/day for 14 days of 28-day treatment cycles) for patients aged ≥55 years with AML in first complete remission. The primary end point is overall survival. Secondary end points include relapse-free survival, safety, health-related quality of life and healthcare resource utilization. This trial will investigate whether CC-486 maintenance can prolong remission and improve survival for older patients with AML.

  20. Mizunami Underground Research Laboratory project. Annual report for fiscal year 2007

    International Nuclear Information System (INIS)

    Nishio, Kazuhisa; Matsuoka, Toshiyuki; Tsuruta, Tadahiko; Amano, Kenji; Ohyama, Takuya; Takeuchi, Ryuji; Saegusa, Hiromitsu; Hama, Katsuhiro; Mizuno, Takashi; Sai, Masataka; Hirano, Toru; Iyatomi, Yosuke; Shimada, Akiomi; Matsui, Hiroya; Ogata, Nobuhisa; Uchida, Masahiro; Sugihara, Kozo; Mikake, Shinichiro; Ikeda, Koki; Yamamoto, Masaru

    2009-03-01

    Japan Atomic Energy Agency (JAEA) at Tono Geoscience Center (TGC) is developing a geoscientific research project named Mizunami Underground Research Laboratory (MIU) Project in crystalline rock environment in order to establish scientific and technological basis for geological disposal of HLW. Geoscientific research at MIU is planned to be carried out in three phases over a period of 20 years; Surface-based Investigation Phase (Phase I), Construction Phase (Phase II) and Operation Phase (Phase III). Currently, the project is under the Construction Phase. This document presents the following results of the research and development performed in fiscal year 2007, as a part of the Construction Phase based on the MIU Master Plan updated in 2002, 1) Investigation at the MIU Construction Site and the Shobasama Site, 2) Construction at the MIU Construction Site, 3) Research Collaboration. (author)

  1. Competitiveness Improvement Project Informational Workshop

    Energy Technology Data Exchange (ETDEWEB)

    Sinclair, Karin C [National Renewable Energy Laboratory (NREL), Golden, CO (United States); Preus, Robert W [National Renewable Energy Laboratory (NREL), Golden, CO (United States); Dana, Scott [National Renewable Energy Laboratory (NREL), Golden, CO (United States); Van Dam, Jeroen J [National Renewable Energy Laboratory (NREL), Golden, CO (United States); Damiani, Rick R [National Renewable Energy Laboratory (NREL), Golden, CO (United States); Jackson, Kyndall R [National Renewable Energy Laboratory (NREL), Golden, CO (United States); Baring-Gould, Edward I [National Renewable Energy Laboratory (NREL), Golden, CO (United States); Jain, Anant [Intertek

    2018-02-27

    This presentation was given at the Competitiveness Improvement Project (CIP) Informational Workshop on December 6, 2017. Topics covered during the workshop include an overview of the CIP, past projects, scoring criteria, technical support opportunities, certification body requirements, standards applicable to distributed wind generators, information on the National Electric Code, certification testing requirements, test site requirements, National Environmental Policy Act, design review, levelized cost of energy, procurement/contracting, project management/deliverables, and outreach materials.

  2. Brachytherapy Improves Survival in Stage III Endometrial Cancer With Cervical Involvement

    Energy Technology Data Exchange (ETDEWEB)

    Bingham, Brian [Department of Radiation Oncology, Vanderbilt University, Nashville, Tennessee (United States); Orton, Andrew; Boothe, Dustin [Department of Radiation Oncology, University of Utah, Salt Lake City, Utah (United States); Stoddard, Greg [Division of Epidemiology, University of Utah, Salt Lake City, Utah (United States); Huang, Y. Jessica; Gaffney, David K. [Department of Radiation Oncology, University of Utah, Salt Lake City, Utah (United States); Poppe, Matthew M., E-mail: Matthew.poppe@hci.utah.edu [Department of Radiation Oncology, University of Utah, Salt Lake City, Utah (United States)

    2017-04-01

    Purpose: To evaluate the survival benefit of adding vaginal brachytherapy (BT) to pelvic external beam radiation therapy (EBRT) in women with stage III endometrial cancer. Methods and Materials: The National Cancer Data Base was used to identify patients with stage III endometrial cancer from 2004 to 2013. Only women who received adjuvant EBRT were analyzed. Women were grouped according to receipt of BT. Logistic regression modeling was used to identify predictors of receiving BT. Log–rank statistics were used to compare survival outcomes. Cox proportional hazards modeling was used to evaluate the effect of BT on survival. A propensity score–matched analysis was also conducted among women with cervical involvement. Results: We evaluated 12,988 patients with stage III endometrial carcinoma, 39% of whom received EBRT plus BT. Women who received BT were more likely to have endocervical or cervical stromal involvement (odds ratios 2.03 and 1.77; P<.01, respectively). For patients receiving EBRT alone, the 5-year survival was 66% versus 69% with the addition of BT at 5 years (P<.01). Brachytherapy remained significantly predictive of decreased risk of death (hazard ratio 0.86; P<.01) on multivariate Cox regression. The addition of BT to EBRT did not affect survival among women without cervical involvement (P=.84). For women with endocervical or cervical stromal invasion, the addition of BT significantly improved survival (log–rank P<.01). Receipt of EBRT plus BT was associated with improved survival in women with positive and negative surgical margins, and receiving chemotherapy did not alter the benefit of BT. Propensity score–matched analysis results confirmed the benefit of BT among women with cervical involvement (hazard ratio 0.80; P=.01). Conclusions: In this population of women with stage III endometrial cancer the addition of BT to EBRT was associated with an improvement in survival for women with endocervical or cervical stromal invasion.

  3. Brachytherapy Improves Survival in Stage III Endometrial Cancer With Cervical Involvement

    International Nuclear Information System (INIS)

    Bingham, Brian; Orton, Andrew; Boothe, Dustin; Stoddard, Greg; Huang, Y. Jessica; Gaffney, David K.; Poppe, Matthew M.

    2017-01-01

    Purpose: To evaluate the survival benefit of adding vaginal brachytherapy (BT) to pelvic external beam radiation therapy (EBRT) in women with stage III endometrial cancer. Methods and Materials: The National Cancer Data Base was used to identify patients with stage III endometrial cancer from 2004 to 2013. Only women who received adjuvant EBRT were analyzed. Women were grouped according to receipt of BT. Logistic regression modeling was used to identify predictors of receiving BT. Log–rank statistics were used to compare survival outcomes. Cox proportional hazards modeling was used to evaluate the effect of BT on survival. A propensity score–matched analysis was also conducted among women with cervical involvement. Results: We evaluated 12,988 patients with stage III endometrial carcinoma, 39% of whom received EBRT plus BT. Women who received BT were more likely to have endocervical or cervical stromal involvement (odds ratios 2.03 and 1.77; P<.01, respectively). For patients receiving EBRT alone, the 5-year survival was 66% versus 69% with the addition of BT at 5 years (P<.01). Brachytherapy remained significantly predictive of decreased risk of death (hazard ratio 0.86; P<.01) on multivariate Cox regression. The addition of BT to EBRT did not affect survival among women without cervical involvement (P=.84). For women with endocervical or cervical stromal invasion, the addition of BT significantly improved survival (log–rank P<.01). Receipt of EBRT plus BT was associated with improved survival in women with positive and negative surgical margins, and receiving chemotherapy did not alter the benefit of BT. Propensity score–matched analysis results confirmed the benefit of BT among women with cervical involvement (hazard ratio 0.80; P=.01). Conclusions: In this population of women with stage III endometrial cancer the addition of BT to EBRT was associated with an improvement in survival for women with endocervical or cervical stromal invasion.

  4. I. Final Report for DOE SBIR Phase I Project DE-SC0013795 Final Report for DOE SBIR Phase I Project DE-SC0013795 Microtron-based Compact, Portable Gamma-Ray Source

    Energy Technology Data Exchange (ETDEWEB)

    Abrams, Robert J. [Muons Inc., Batavia, IL (United States)

    2017-01-09

    Microtron-based Compact, Portable Gamma-Ray Source. The objective of Phase I of this project was to produce a conceptual design of a prototype compact microtron electron accelerator, which could be designed, built, and demonstrated in Phase II of the project. The conceptual design study included an analysis of the parameters of the microtron and its components, and the expected performance of the prototype microtron as a source of x-rays and/or RF neutrons in the MeV energy range. The major components of the microtron are the magnet, the accelerating system, the power system, the vacuum system, the control system, the beam extraction system and the targets to produce x-rays (and/or neutrons). Our objectives for the design of the prototype were for it to be compact, cost-effective, capable of producing high intensity x-ray (an/or neutron) fluxes. In addition, the prototype was to be easily assembled and disassembled so that components could be easily replaced. The main parameters for the prototype are the following: the range of electron kinetic energies, the output power, the RF frequency band (X-band, C-band, or S-Band), the type of injection (Type I or Type II), the magnet type, i.e. permanent magnet, electromagnet, or a hybrid combination of permanent and electromagnet. The results of the Phase I study and analysis for a prototype microtron are the following: The electron energy range can be varied from below 6 MeV to 9 MeV, the optimal frequency range is S-Band (2-4 GHz) RF frequency, Type II injection (described below), and the magnet type is the hybrid version. The prototype version will be capable of producing gamma ray doses of ~1800 R/min-m and neutron fluxes of up to ~6 x 1010 n/s with appropriate targets. The results of the Phase I study and analysis are provided below. The proposed Phase II plan was to demonstrate the prototype at low beam power. In the subsequent Phase III, high power tests would be performed, and the design of commercial

  5. Phase II clinical development of new drugs

    CERN Document Server

    Ting, Naitee; Ho, Shuyen; Cappelleri, Joseph C

    2017-01-01

    This book focuses on how to appropriately plan and develop a Phase II program, and how to design Phase II clinical trials and analyze their data. It provides a comprehensive overview of the entire drug development process and highlights key questions that need to be addressed for the successful execution of Phase II, so as to increase its success in Phase III and for drug approval. Lastly it warns project team members of the common potential pitfalls and offers tips on how to avoid them.

  6. "India Population Projects" in Karnataka.

    Science.gov (United States)

    Reddy, P H; Badari, V S

    1991-12-01

    An overview, objectives, implementation, and research and evaluation studies of 2 India Population Projects in Karnataka are presented. The India Population Project I (IPP-I) was conducted in Karnataka and Uttar Pradesh. India Population Project III (IPP-III) took place between 1984-92 in 6 districts of Karnataka: Belgaum, Bijapur, Dharwad, Bidar, Gulbarga, and Raichur, and 4 districts in Kerala. The 6 districts in Karnataka accounted for 36% (13.2 million) of the total national population. The project cost was Rs. 713.1 million which was shared by the World Bank, and the Indian national and regional government. Due to poor past performance, these projects were undertaken to improve health and family welfare status. Specific project objectives are outlined. IPP-I included an urban component, and optimal Government of India program, and an intensive rural initiative. The urban program aimed to improved pre- and postnatal services and facilities, and the family planning (FP) in Bangalore city. The rural program was primarily to provide auxiliary nurse-midwives and hospitals and clinics, and also supplemental feeding program for pregnant and nursing mothers and children up to 2 years. The government program provided FP staff and facilities. IPP-I had 3 units to oversee building construction, to recruit staff and provide supplies and equipment, and to establish a Population Center. IPP-III was concerned with service delivery; information, education, and communication efforts (IEC) and population education; research and evaluation; and project management. Both projects contributed significantly to improving the infrastructure. A brief account of the types and kinds of studies undertaken is given. Studies were grouped into longitudinal studies of fertility, mortality, and FP; management information and evaluation systems for health and family welfare programs; experimental strategies; and other studies. Research and evaluation studies in IPP-III encompassed studies in

  7. A new ion imprinted polymer based on Ru(III)-thiobarbituric acid complex for solid phase extraction of ruthenium(III) prior to its determination by ETAAS

    International Nuclear Information System (INIS)

    Zambrzycka, Elżbieta; Godlewska-Żyłkiewicz, Beata

    2014-01-01

    A new ruthenium ion imprinted polymer was prepared from the Ru(III) 2-thiobarbituric acid complex (the template), methacrylic acid or acrylamide (the functional monomers), and ethylene glycol dimethacrylate (the cross-linking agent) using 2,2′-azobisisobutyronitrile as the radical initiator. The ion imprinted polymer was characterized and used as a selective sorbent for the solid phase extraction of Ru(III) ions. The effects of type of functional monomer, sample volume, solution pH and flow rate on the extraction efficiency were studied in the dynamic mode. Ru(III) ion was quantitatively retained on the sorbents in the pH range from 3.5 to 10, and can be eluted with 4 mol L−1 aqueous ammonia. The affinity of Ru(III) for the ion imprinted polymer based on the acrylamide monomer is weaker than that for the polymer based on the methacrylic acid monomer, which therefore was used in interference studies and in analytical applications. Following extraction of Ru(III) ions with the imprint and their subsequent elution from the polymer with aqueous ammonia, Ru(III) was detected by electrothermal atomic absorption spectrometry with a detection limit of 0.21 ng mL −1 . The method was successfully applied to the determination of trace amounts of Ru(III) in water, waste, road dust and platinum ore (CRM SARM 76) with a reproducibility (expressed as RSD) below 6.4 %. (author)

  8. Optimal dose selection accounting for patient subpopulations in a randomized Phase II trial to maximize the success probability of a subsequent Phase III trial.

    Science.gov (United States)

    Takahashi, Fumihiro; Morita, Satoshi

    2018-02-08

    Phase II clinical trials are conducted to determine the optimal dose of the study drug for use in Phase III clinical trials while also balancing efficacy and safety. In conducting these trials, it may be important to consider subpopulations of patients grouped by background factors such as drug metabolism and kidney and liver function. Determining the optimal dose, as well as maximizing the effectiveness of the study drug by analyzing patient subpopulations, requires a complex decision-making process. In extreme cases, drug development has to be terminated due to inadequate efficacy or severe toxicity. Such a decision may be based on a particular subpopulation. We propose a Bayesian utility approach (BUART) to randomized Phase II clinical trials which uses a first-order bivariate normal dynamic linear model for efficacy and safety in order to determine the optimal dose and study population in a subsequent Phase III clinical trial. We carried out a simulation study under a wide range of clinical scenarios to evaluate the performance of the proposed method in comparison with a conventional method separately analyzing efficacy and safety in each patient population. The proposed method showed more favorable operating characteristics in determining the optimal population and dose.

  9. Pipe Overpack Container Fire Testing: Phase I II & III.

    Energy Technology Data Exchange (ETDEWEB)

    Figueroa, Victor G. [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States); Ammerman, Douglas J. [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States); Lopez, Carlos [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States); Gill, Walter [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States)

    2018-02-01

    The Pipe Overpack Container (POC) was developed at Rocky Flats to transport plutonium residues with higher levels of plutonium than standard transuranic (TRU) waste to the Waste Isolation Pilot Plant (WIPP) for disposal. In 1996 Sandia National Laboratories (SNL) conducted a series of tests to determine the degree of protection POCs provided during storage accident events. One of these tests exposed four of the POCs to a 30-minute engulfing pool fire, resulting in one of the 7A drum overpacks generating sufficient internal pressure to pop off its lid and expose the top of the pipe container (PC) to the fire environment. The initial contents of the POCs were inert materials, which would not generate large internal pressure within the PC if heated. POCs are now being used to store combustible TRU waste at Department of Energy (DOE) sites. At the request of DOE’s Office of Environmental Management (EM) and National Nuclear Security Administration (NNSA), starting in 2015 SNL conducted a series of fire tests to examine whether PCs with combustibles would reach a temperature that would result in (1) decomposition of inner contents and (2) subsequent generation of sufficient gas to cause the PC to over-pressurize and release its inner content. Tests conducted during 2015 and 2016 were done in three phases. The goal of the first phase was to see if the PC would reach high enough temperatures to decompose typical combustible materials inside the PC. The goal of the second test phase was to determine under what heating loads (i.e., incident heat fluxes) the 7A drum lid pops off from the POC drum. The goal of the third phase was to see if surrogate aerosol gets released from the PC when the drum lid is off. This report will describe the various tests conducted in phase I, II, and III, present preliminary results from these tests, and discuss implications for the POCs.

  10. Managing externally financed projects: the Integrated Primary Health Care Project in Bolivia.

    Science.gov (United States)

    Homedes, N

    2001-12-01

    Bolivia is one of the poorest countries in Latin America. Health indicators are very poor, communicable diseases are prevalent and, coupled with malnutrition, remain the major killers of children under 5 years old. The Integrated Primary Health Care Project (PROISS) was a US$39 million project executed by the Ministry of Health (MOH), 50% financed by the World Bank and aimed at improving primary health care in the four largest Bolivian municipalities. The implementation of the project started in 1990 and ended in 1997. During implementation it went through three distinct phases: Phase 1 (1990-94) was a period characterized by conflict and confusion; Phase 2 (1995-mid-1996) documented major improvements in coverage and service quality; and Phase 3 (mid-1996-97) witnessed the decline of the project. This paper explores the factors that contributed to the success and the decline of the project, draws lessons for project managers and international agencies involved in the definition and implementation of social sector projects, and discusses the unlikelihood that externally financed projects can have a sustainable impact on the development of the health sector of recipient countries.

  11. Use of Geothermal Energy for Aquaculture Purposes - Phase III

    Energy Technology Data Exchange (ETDEWEB)

    Johnson, W C; Smith, K C

    1981-09-01

    This project, financed by the Pacific Northwest Regional Commission (PNRC), was designed to provide information to evaluate the best methods to use for intensive aquaculture of freshwater prawns, Macrobrachium rosenbergii, using geothermal energy. The freshwater prawn is a tropical organism and is native to southeast Asia. Earlier projects at Oregon Institute of Technology have shown the feasibility of culturing this aquatic animal in geothermal water. This phase of the project was designed to investigate intensive culture of this animal as well as the advantages of growing rainbow trout, ornamental tropical fin fish, and mosquito fish, Gambusia affnis, for vector control using geothermal energy. The research data collected on the prawns was obtained from the stocking and sampling of two 0.2- ha (half-acre) ponds constructed as a part of the project. The ponds are equipped with recording monitors for temperature and flow. The geothermal energy used is the geothermal effluent from the Oregon Institute of Technology heating system. This water is of potable quality and ranges in temperature from 50 to 70oC. The geothermal water used in the ponds is controlled at 27oC, ± 2oC, by using thermostats and solenoid valves. A small building next to the ponds contains facilities for hatching larvae prawns and tanks for growing post-larvae prawns. The hatchery facility makes the project self-sustaining. The hatchery was obtained as part of an earlier PNRC project.

  12. Phase Startup Initiative Phases 3 and 4 Test Plan and Test Specification ( OCRWM)

    Energy Technology Data Exchange (ETDEWEB)

    PAJUNEN, A.L.; LANGEVIN, M.J.

    2000-08-07

    Construction for the Spent Nuclear Fuel (SNF) Project facilities is continuing per the Level III Baseline Schedule, and installation of the Fuel Retrieval System (FRS) and Integrated Water Treatment System (IWTS) in K West Basin is now complete. In order to accelerate the project, a phased start up strategy to initiate testing of the FRS and IWTS early in the overall project schedule was proposed (Williams 1999). Wilkinson (1999) expands the definition of the original proposal into four functional testing phases of the Phased Startup Initiative (PSI). Phases 1 and 2 are based on performing functional tests using dummy fuel. This test plan provides overall guidance for Phase 3 and 4 tests, which are performed using actual irradiated N fuel assemblies. The overall objective of the Phase 3 and 4 testing is to verify how the FRS and IWTS respond while processing actual fuel. Conducting these tests early in the project schedule will allow identification and resolution of equipment and process problems before they become activities on the start-up critical path. The specific objectives of this test plan are to: Define the Phase 3 and 4 test scope for the FRS and IWTS; Provide detailed test requirements that can be used to write the specific test procedures; Define data required and measurements to be taken. Where existing methods to obtain these do not exist, enough detail will be provided to define required additional equipment; and Define specific test objectives and acceptance criteria.

  13. Phase Startup Initiative Phases 3 and 4 Test Plan and Test Specification (OCRWM)

    International Nuclear Information System (INIS)

    PAJUNEN, A.L.; LANGEVIN, M.J.

    2000-01-01

    Construction for the Spent Nuclear Fuel (SNF) Project facilities is continuing per the Level III Baseline Schedule, and installation of the Fuel Retrieval System (FRS) and Integrated Water Treatment System (IWTS) in K West Basin is now complete. In order to accelerate the project, a phased start up strategy to initiate testing of the FRS and IWTS early in the overall project schedule was proposed (Williams 1999). Wilkinson (1999) expands the definition of the original proposal into four functional testing phases of the Phased Startup Initiative (PSI). Phases 1 and 2 are based on performing functional tests using dummy fuel. This test plan provides overall guidance for Phase 3 and 4 tests, which are performed using actual irradiated N fuel assemblies. The overall objective of the Phase 3 and 4 testing is to verify how the FRS and IWTS respond while processing actual fuel. Conducting these tests early in the project schedule will allow identification and resolution of equipment and process problems before they become activities on the start-up critical path. The specific objectives of this test plan are to: Define the Phase 3 and 4 test scope for the FRS and IWTS; Provide detailed test requirements that can be used to write the specific test procedures; Define data required and measurements to be taken. Where existing methods to obtain these do not exist, enough detail will be provided to define required additional equipment; and Define specific test objectives and acceptance criteria

  14. Enantiomeric separation of iridium (III) complexes using HPLC chiral stationary phases based on amylose derivatives

    International Nuclear Information System (INIS)

    Kim, Hee Eun; Seo, Na Hyeon; Hyun, Myung Ho

    2016-01-01

    Cyclometalated iridium (III) complexes formed with three identical cyclometalating (C-N) ligands (homoleptic) or formed with two cyclometalating (C-N) ligands and one ancillary (LX) ligand (heteroleptic) have been known as highly phosphorescent materials and, thus, they have been utilized as efficient phosphorescent dopants in organic light emitting diodes (OLEDs) 1–3 or as effective phosphorescent chemosensors. 4–7 Cylometalated iridium (III) complexes are chiral compounds consisting of lambda (Λ, left-handed) and delta (Δ, right-handed) isomers. Racemic cyclometa- lated iridium (III) complexes emit light with no net polarization, but optically active cyclometalated iridium (III) complexes emit circularly polarized light. 8,9 Circularly polarized light can be used in various fields including highly efficient three dimensional electronic devices, photo nic devices for optical data storage, biological assays, and others. 8,9 In order to obtain optically active cylometalated iridium (III) complexes and to determine the enantiomeric composition of optically active cylometalated iridium (III) complexes, liquid chromatogr aphic enantiomer separation method on chiral stationary phases (CSPs) has been used. For example, Okamoto and coworkers first reported the high performance liquid chromatographic (HPLC) direct enantiomeric separation of two homoleptic cylometalated iridium (III) complexes on immobilized amylose tris(3,5- dimethylphenylcarbamate) (Chiralpak IA), coated cellulose tris(3,5-dimethylphenylcarbamate) (Chiralc el OD), and coated cellulose tris(4-methylbenzoate) (Chiralce l OJ). 10 Supercritical fluid chromatography (SFC) was also used by Bernhard and coworkers for the enantiomeric separation of cylometalated iridium (III) complexes on coated amylose tris(3,5-dimethylphenylcarbamate) (Chiralpak AD-H). 8 However, the general use of the HPLC method for the direct enantiomeric separation of homoleptic

  15. Enantiomeric separation of iridium (III) complexes using HPLC chiral stationary phases based on amylose derivatives

    Energy Technology Data Exchange (ETDEWEB)

    Kim, Hee Eun; Seo, Na Hyeon; Hyun, Myung Ho [Dept. of Chemistry and Chemistry Institute for Functional Materials, Pusan National University, Busan (Korea, Republic of)

    2016-12-15

    Cyclometalated iridium (III) complexes formed with three identical cyclometalating (C-N) ligands (homoleptic) or formed with two cyclometalating (C-N) ligands and one ancillary (LX) ligand (heteroleptic) have been known as highly phosphorescent materials and, thus, they have been utilized as efficient phosphorescent dopants in organic light emitting diodes (OLEDs) 1–3 or as effective phosphorescent chemosensors. 4–7 Cylometalated iridium (III) complexes are chiral compounds consisting of lambda (Λ, left-handed) and delta (Δ, right-handed) isomers. Racemic cyclometa- lated iridium (III) complexes emit light with no net polarization, but optically active cyclometalated iridium (III) complexes emit circularly polarized light. 8,9 Circularly polarized light can be used in various fields including highly efficient three dimensional electronic devices, photo nic devices for optical data storage, biological assays, and others. 8,9 In order to obtain optically active cylometalated iridium (III) complexes and to determine the enantiomeric composition of optically active cylometalated iridium (III) complexes, liquid chromatogr aphic enantiomer separation method on chiral stationary phases (CSPs) has been used. For example, Okamoto and coworkers first reported the high performance liquid chromatographic (HPLC) direct enantiomeric separation of two homoleptic cylometalated iridium (III) complexes on immobilized amylose tris(3,5- dimethylphenylcarbamate) (Chiralpak IA), coated cellulose tris(3,5-dimethylphenylcarbamate) (Chiralc el OD), and coated cellulose tris(4-methylbenzoate) (Chiralce l OJ). 10 Supercritical fluid chromatography (SFC) was also used by Bernhard and coworkers for the enantiomeric separation of cylometalated iridium (III) complexes on coated amylose tris(3,5-dimethylphenylcarbamate) (Chiralpak AD-H). 8 However, the general use of the HPLC method for the direct enantiomeric separation of homoleptic.

  16. Explorations of new phases in the Ga(III)/In(III)-Mo(VI)-Se(IV)/Te(IV)-O systems.

    Science.gov (United States)

    Kong, Fang; Hu, Chun-Li; Hu, Ting; Zhou, Yong; Mao, Jiang-Gao

    2009-07-07

    Systematic explorations of new phases in the Ga(III)/In(III)-Mo(VI)-Se(IV)/Te(IV)-O systems by hydrothermal syntheses or solid-state reactions at high-temperature led to four new quaternary compounds, namely, Ga(2)MoQ(2)O(10) (Q = Se, Te), In(2)Mo(2)Se(2)O(13)(H(2)O) and In(2)MoTe(2)O(10). Ga(2)MoQ(2)O(10) (Q = Se, Te) are isostructural and their structures feature a 3D network of gallium selenite/tellurite with 12-member ring tunnels along b-axis, the distorted MoO(6) octahedra are attached on the wall of the above tunnels. The structure of In(2)Mo(2)Se(2)O(13)(H(2)O) features a new pillared-layered architecture composed of 2D indium(III) selenite layers that are interconnected by Mo(2)O(10) dimers, forming 8-membered ring tunnels along the b-axis. The structure of In(2)MoTe(2)O(10) features a 2D indium oxide layer formed by corner- and edge-sharing InO(6) and InO(7) polyhedra with MoO(4) tetrahedra and TeO(n) (n = 4, 5) polyhedra hanging on both sides of the layer, there are weak interlayer Te-O bonds of 2.512 A. Results of optical diffuse reflectance spectrum measurements indicate that all four compounds are insulators, which are in agreement with results of band structure calculations based on DFT methods.

  17. A strategic plan for the second phase (2013-2015) of the Korea biobank project.

    Science.gov (United States)

    Park, Ok; Cho, Sang Yun; Shin, So Youn; Park, Jae-Sun; Kim, Jun Woo; Han, Bok-Ghee

    2013-04-01

    biobanks, and has also carried out various publicity promotions to the public and researchers. During the first phase, biospecimens from more than 300,000 participants through various cohorts and biospecimens from more than 200,000 patients from hospitals were collected, which were distributed to approximately 600 research projects. The planning committee for the second phase evaluated that the first phase of the KBP was successful. However, the first phase of the project was meant to allow autonomy to the individual biobanks. The biobanks were able to choose the kind of specimens they were going to collect and the amount of specimen they would set as a goal, as well as being allowed to choose their own methods to manage their biobanks (autonomy). Therefore, some biobanks collected resources that were easy to collect and the resources needed by researchers were not strategically collected. In addition, there was also a low distribution rate to researchers outside of hospitals, who do not have as much access to specimens and cases as those in hospitals. There were also many cases in which researchers were not aware of the KBP, and the distribution processes were not set up to be convenient to the demands of researchers. Accordingly, the second phase of the KBP will be focused on increasing the integration and cooperation between the biobanks within the network. The KBP plans to set goals for the strategic collection of the needed human bioresources. Although the main principle of the first phase was to establish infrastructure and resource collection, the key objective of the second phase is the efficient utilization of gathered resources. In order to fully utilize the gathered resources in an efficient way, distribution systems and policies must be improved. Vitalization of distribution, securing of high-value resource and related clinical and laboratory information, international standardization of resource management systems, and establishment of a virtuous cycle between

  18. Training improves oxidative capacity, but not function, in spinal muscular atrophy type III

    DEFF Research Database (Denmark)

    Madsen, Karen Lindhardt; Hansen, Regitze Sølling; Preisler, Nicolai

    2015-01-01

    max (17 ± 2 to 21 ± 2 ml/kg/min, P sleep in 3 patients, and led to training modifications in 2 patients. CONCLUSIONS: Cycle exercise improves VO2max in SMA III without causing muscle...... a 12-week training program, performing 42 30-minute sessions exercising at 65-70% of maximal oxygen uptake (VO2max ). VO2max , muscle strength, functional tests, and self-reported activities of daily living were assessed before and after the training. RESULTS: Training induced a 27 ± 3% increase in VO2...... damage, but it also induces significant fatigue. This warrants study into alternative training methods to improve exercise capacity in SMA III patients....

  19. Project SAFE. Update of the SFR-1 safety assessment. Phase 1

    International Nuclear Information System (INIS)

    Andersson, Johan; Riggare, P.; Skagius, K.

    1998-10-01

    SFR-1 is a facility for disposal of low-level radioactive operational waste from the nuclear power plants in Sweden. Low-level radioactive waste from industry, medicine, and research is also disposed in SFR-1. The facility is situated in bedrock beneath the Baltic Sea, 1 km off the coast near the Forsmark nuclear power plant. SFR-1 was built between the years 1983 and 1988. An assessment of the long-term performance of the facility was included in the vast documentation that was a part of the application for an operational license. The assessment was presented in the form of a final safety report. In the operational licence for SFR-1 it is stated that renewed safety assessments should be carried out at least each ten years. In order to meet this demand SKB has launched a special project, SAFE (Safety Assessment of Final Disposal of Operational Radioactive Waste). The aim of the project is to update the safety analysis and to prepare a safety report that will be presented to the Swedish authorities not later than year 2000. Project SAFE is divided into three phases. The first phase is a prestudy, and the results of the prestudy are given in this report. The aim of the prestudy is to identify issues where additional studies would improve the basis for the updated safety analysis as well as to suggest how these studies should be carried out. The work has been divided into six different topics, namely the inventory, the near field, the far field, the biosphere, radionuclide transport calculations and scenarios. For each topic the former safety reports and regulatory reviews are scrutinised and needs for additional work is identified. The evaluations are given in appendices covering the respective topics. The main report is a summary of the appendices with a more stringent description of the repository system and the processes that are of interest and therefore should be addressed in an updated safety assessment. However, it should be pointed out that one of the

  20. Enginnering development of coal-fired high performance power systems phase II and III

    International Nuclear Information System (INIS)

    1998-01-01

    This report presents work carried out under contract DE-AC22-95PC95144 ''Engineering Development of Coal-Fired High Performance Systems Phase II and III.'' The goals of the program are to develop a coal-fired high performance power generation system (HIPPS) that is capable of: thermal efficiency (HHV) >47%; NOx, SOx, and particulates 65% of heat input; all solid wastes benign; cost of electricity <90% of present plants. Phase I, which began in 1992, focused on the analysis of various configurations of indirectly fired cycles and on technical assessments of alternative plant subsystems and components, including performance requirements, developmental status, design options, complexity and reliability, and capital and operating costs. Phase I also included preliminary R ampersand D and the preparation of designs for HIPPS commercial plants approximately 300 MWe in size. This phase, Phase II, involves the development and testing of plant subsystems, refinement and updating of the HIPPS commercial plant design, and the site selection and engineering design of a HIPPS prototype plant. Work reported herein is from: Task 2.2 HITAF Air Heaters; Task 6 HIPPS Commercial Plant Design Update

  1. Phase II and III Clinical Studies of Diphtheria-Tetanus-Acellular Pertussis Vaccine Containing Inactivated Polio Vaccine Derived from Sabin Strains (DTaP-sIPV).

    Science.gov (United States)

    Okada, Kenji; Miyazaki, Chiaki; Kino, Yoichiro; Ozaki, Takao; Hirose, Mizuo; Ueda, Kohji

    2013-07-15

    Phase II and III clinical studies were conducted to evaluate immunogenicity and safety of a novel DTaP-IPV vaccine consisting of Sabin inactivated poliovirus vaccine (sIPV) and diphtheria-tetanus-acellular pertussis vaccine (DTaP). A Phase II study was conducted in 104 healthy infants using Formulation H of the DTaP-sIPV vaccine containing high-dose sIPV (3, 100, and 100 D-antigen units for types 1, 2, and 3, respectively), and Formulations M and L, containing half and one-fourth of the sIPV in Formulation H, respectively. Each formulation was administered 3 times for primary immunization and once for booster immunization. A Phase III study was conducted in 342 healthy infants who received either Formulation M + oral polio vaccine (OPV) placebo or DTaP + OPV. The OPV or OPV placebo was orally administered twice between primary and booster immunizations. Formulation M was selected as the optimum dose. In the Phase III study, the seropositive rate was 100% for all Sabin strains after primary immunization, and the neutralizing antibody titer after booster immunization was higher than in the control group (DTaP + OPV). All adverse reactions were clinically acceptable. DTaP-sIPV was shown to be a safe and immunogenic vaccine. JapicCTI-121902 for Phase II study, JapicCTI-101075 for Phase III study (http://www.clinicaltrials.jp/user/cte_main.jsp).

  2. Effects of PECS Phase III Application Training on Independent Mands in Young Children with Autism

    Science.gov (United States)

    Love, Jessica June

    2013-01-01

    The purpose of this study was to examine the effects of PECS phase III application training on independent mands in young children with autism. Participants were five children with autism ranging from ages 2 to 4 years old. A multiple baseline across participants was used to evaluate acquisition of independent correct mands across baseline and…

  3. Investor Outlook: Focus on Upcoming LCA2 Gene Therapy Phase III Results.

    Science.gov (United States)

    Schimmer, Joshua; Breazzano, Steven

    2015-09-01

    Investor interest in gene therapy has increased substantially over the past few years, and the next major catalyst for the field is likely to be Spark Therapeutics's phase III trial for the treatment of visual impairment caused by RPE65 gene mutations (often referred to as Leber congenital amaurosis type 2, or LCA2, but may include other retinal disorders). Analysis of the approach from the basic genetics, underlying visual mechanisms, clinical data, and commercialization considerations helps frame investor expectations and the potential implications for the broader field.

  4. How to Begin a Quality Improvement Project.

    Science.gov (United States)

    Silver, Samuel A; Harel, Ziv; McQuillan, Rory; Weizman, Adam V; Thomas, Alison; Chertow, Glenn M; Nesrallah, Gihad; Bell, Chaim M; Chan, Christopher T

    2016-05-06

    Quality improvement involves a combined effort among health care staff and stakeholders to diagnose and treat problems in the health care system. However, health care professionals often lack training in quality improvement methods, which makes it challenging to participate in improvement efforts. This article familiarizes health care professionals with how to begin a quality improvement project. The initial steps involve forming an improvement team that possesses expertise in the quality of care problem, leadership, and change management. Stakeholder mapping and analysis are useful tools at this stage, and these are reviewed to help identify individuals who might have a vested interest in the project. Physician engagement is a particularly important component of project success, and the knowledge that patients/caregivers can offer as members of a quality improvement team should not be overlooked. After a team is formed, an improvement framework helps to organize the scientific process of system change. Common quality improvement frameworks include Six Sigma, Lean, and the Model for Improvement. These models are contrasted, with a focus on the Model for Improvement, because it is widely used and applicable to a variety of quality of care problems without advanced training. It involves three steps: setting aims to focus improvement, choosing a balanced set of measures to determine if improvement occurs, and testing new ideas to change the current process. These new ideas are evaluated using Plan-Do-Study-Act cycles, where knowledge is gained by testing changes and reflecting on their effect. To show the real world utility of the quality improvement methods discussed, they are applied to a hypothetical quality improvement initiative that aims to promote home dialysis (home hemodialysis and peritoneal dialysis). This provides an example that kidney health care professionals can use to begin their own quality improvement projects. Copyright © 2016 by the American

  5. Telecentric 3D profilometry based on phase-shifting fringe projection.

    Science.gov (United States)

    Li, Dong; Liu, Chunyang; Tian, Jindong

    2014-12-29

    Three dimensional shape measurement in the microscopic range becomes increasingly important with the development of micro manufacturing technology. Microscopic fringe projection techniques offer a fast, robust, and full-field measurement for field sizes from approximately 1 mm2 to several cm2. However, the depth of field is very small due to the imaging of non-telecentric microscope, which is often not sufficient to measure the complete depth of a 3D-object. And the calibration of phase-to-depth conversion is complicated which need a precision translation stage and a reference plane. In this paper, we propose a novel telecentric phase-shifting projected fringe profilometry for small and thick objects. Telecentric imaging extends the depth of field approximately to millimeter order, which is much larger than that of microscopy. To avoid the complicated phase-to-depth conversion in microscopic fringe projection, we develop a new system calibration method of camera and projector based on telecentric imaging model. Based on these, a 3D reconstruction of telecentric imaging is presented with stereovision aided by fringe phase maps. Experiments demonstrated the feasibility and high measurement accuracy of the proposed system for thick object.

  6. Waste retrieval sluicing system vapor sampling and analysis plan for evaluation of organic emissions, process test phase III

    International Nuclear Information System (INIS)

    SASAKI, L.M.

    1999-01-01

    This sampling and analysis plan identifies characterization objectives pertaining to sample collection, laboratory analytical evaluation, and reporting requirements for vapor samples obtained to address vapor issues related to the sluicing of tank 241-C-106. Sampling will be performed in accordance with Waste Retrieval Sluicing System Emissions Collection Phase III (Jones 1999) and Process Test Plan Phase III, Waste Retrieval Sluicing System Emissions Collection (Powers 1999). Analytical requirements include those specified in Request for Ecology Concurrence on Draft Strategy/Path Forward to Address Concerns Regarding Organic Emissions from C-106 Sluicing Activities (Peterson 1998). The Waste Retrieval Sluicing System was installed to retrieve and transfer high-heat sludge from tank 241-C-106 to tank 241-AY-102, which is designed for high-heat waste storage. During initial sluicing of tank 241-C-106 in November 1998, operations were halted due to detection of unexpected high volatile organic compounds in emissions that exceeded regulatory permit limits. Several workers also reported smelling sharp odors and throat irritation. Vapor grab samples from the 296-C-006 ventilation system were taken as soon as possible after detection; the analyses indicated that volatile and semi-volatile organic compounds were present. In December 1998, a process test (phase I) was conducted in which the pumps in tanks 241-C-106 and 241-AY-102 were operated and vapor samples obtained to determine constituents that may be present during active sluicing of tank 241-C-106. The process test was suspended when a jumper leak was detected. On March 7, 1999, phase I1 of the process test was performed; the sluicing system was operated for approximately 7 hours and was ended using the controlled shutdown method when the allowable amount of solids were transferred to 241-AY-102. The phase II test was successful, however, further testing is required to obtain vapor samples at higher emission levels

  7. Virtual reality exercise on a home-based phase III cardiac rehabilitation program, effect on executive function, quality of life and depression, anxiety and stress: a randomized controlled trial.

    Science.gov (United States)

    Vieira, Ágata; Melo, Cristina; Machado, Jorge; Gabriel, Joaquim

    2018-02-01

    To analyse the effect of a six-month home-based phase III cardiac rehabilitation (CR) specific exercise program, performed in a virtual reality (Kinect) or conventional (booklet) environment, on executive function, quality of life and depression, anxiety and stress of subjects with coronary artery disease. A randomized controlled trial was conducted with subjects, who had completed phase II, randomly assigned to intervention group 1 (IG1), whose program encompassed the use of Kinect (n = 11); or intervention group 2 (IG2), a paper booklet (n = 11); or a control group (CG), only subjected to the usual care (n = 11). The three groups received education on cardiovascular risk factors. The assessed parameters, at baseline (M0), 3 (M1) and 6 months (M2), were executive function, control and integration in the implementation of an adequate behaviour in relation to a certain objective, specifically the ability to switch information (Trail Making Test), working memory (Verbal Digit Span test), and selective attention and conflict resolution ability (Stroop test), quality of life (MacNew questionnaire) and depression, anxiety and stress (Depression, Anxiety and Stress Scale 21). Descriptive and inferential statistical measures were used, significance level was set at .05. The IG1 revealed significant improvements, in the selective attention and conflict resolution ability, in comparison with the CG in the variable difference M0 - M2 (p = .021) and in comparison with the IG2 in the variable difference M1 - M2 and M0 - M2 (p = .001 and p = .002, respectively). No significant differences were found in the quality of life, and depression, anxiety and stress. The virtual reality format had improved selective attention and conflict resolution ability, revealing the potential of CR, specifically with virtual reality exercise, on executive function. Implications for Rehabilitation In cardiac rehabilitation, especially in phase III, it is

  8. Distributed Wind Competitiveness Improvement Project

    Energy Technology Data Exchange (ETDEWEB)

    2018-02-27

    The Competitiveness Improvement Project (CIP) is a periodic solicitation through the U.S. Department of Energy and its National Renewable Energy Laboratory. The Competitiveness Improvement Project (CIP) is a periodic solicitation through the U.S. Department of Energy and its National Renewable Energy Laboratory. Manufacturers of small and medium wind turbines are awarded cost-shared grants via a competitive process to optimize their designs, develop advanced manufacturing processes, and perform turbine testing. The goals of the CIP are to make wind energy cost competitive with other distributed generation technology and increase the number of wind turbine designs certified to national testing standards. This fact sheet describes the CIP and funding awarded as part of the project.ufacturers of small and medium wind turbines are awarded cost-shared grants via a competitive process to optimize their designs, develop advanced manufacturing processes, and perform turbine testing. The goals of the CIP are to make wind energy cost competitive with other distributed generation technology and increase the number of wind turbine designs certified to national testing standards. This fact sheet describes the CIP and funding awarded as part of the project.

  9. SPSP Phase III Recruiting, Selecting, and Developing Secure Power Systems Professionals. Individual and Team Performance Guidelines

    Energy Technology Data Exchange (ETDEWEB)

    O' Neil, Lori Ross [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Conway, T. J. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Tobey, D. H. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Greitzer, Frank L. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Dalton, Angela C. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Pusey, Portia K. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States)

    2015-03-01

    The Secure Power Systems Professional Phase III final report was released last year which an appendix of Individual and Team Performance Guidelines. This new report is that appendix broken out as a standalone document to assist utilities in recruiting and developing Secure Power Systems Professionals at their site.

  10. Assessing the influence of project management on quality during the early phases of construction projects

    Directory of Open Access Journals (Sweden)

    Ljevo Žanesa

    2018-12-01

    Full Text Available Although the quality of a process affects the quality of the end product, there is currently an insignif­icant amount of knowledge about the quality of project management (PM processes that directly affect the quality of the delivered product (constructed building. This study presents a proposal for modeling the impact of the quality of the PM process on the quality of the con­structed building. The quality of the PM process is rep­resented by the main quality factors and product quality indicators. It presents the results of the interviews that were conducted and study cases that were analyzed in Bosnia and Herzegovina with a variety of project partici­pants (with different managerial perspectives in terms of the indicators of quality of the delivered product. All par­ticipants, regardless of managerial perspective, believe that the most important indicator of the quality of prod­ucts for each phase of the project is “customer satisfaction in the end phase”, the measurement of which is different for each project phase that is presented. The results of the factor analysis of the definition and the planning phases show that 11 variables, namely, the quality factors of the PM process, can be grouped into three new factors, which is described as 66.61% (77.046% of the basic set of vari­ables.

  11. Computational advances in transition phase analysis

    International Nuclear Information System (INIS)

    Morita, K.; Kondo, S.; Tobita, Y.; Shirakawa, N.; Brear, D.J.; Fischer, E.A.

    1994-01-01

    In this paper, historical perspective and recent advances are reviewed on computational technologies to evaluate a transition phase of core disruptive accidents in liquid-metal fast reactors. An analysis of the transition phase requires treatment of multi-phase multi-component thermohydraulics coupled with space- and energy-dependent neutron kinetics. Such a comprehensive modeling effort was initiated when the program of SIMMER-series computer code development was initiated in the late 1970s in the USA. Successful application of the latest SIMMER-II in USA, western Europe and Japan have proved its effectiveness, but, at the same time, several areas that require further research have been identified. Based on the experience and lessons learned during the SIMMER-II application through 1980s, a new project of SIMMER-III development is underway at the Power Reactor and Nuclear Fuel Development Corporation (PNC), Japan. The models and methods of SIMMER-III are briefly described with emphasis on recent advances in multi-phase multi-component fluid dynamics technologies and their expected implication on a future reliable transition phase analysis. (author)

  12. A pivotal registration phase III, multicenter, randomized tuberculosis controlled trial: design issues and lessons learnt from the Gatifloxacin for TB (OFLOTUB project

    Directory of Open Access Journals (Sweden)

    Merle Corinne SC

    2012-05-01

    Full Text Available Abstract Background There have been no major advances in tuberculosis (TB drug development since the first East African/British Medical Research Council short course chemotherapy trial 35 years ago. Since then, the landscape for conducting TB clinical trials has profoundly changed with the emergence of HIV infection, the spread of resistant TB bacilli strains, recent advances in mycobacteriological capacity, and drug discovery. As a consequence questions have arisen on the most appropriate approach to design and conduct current TB trials. To highlight key issues discussed: Is a superiority, equivalence, or non-inferiority design most appropriate? What should be the primary efficacy outcome? How to consider re-infections in the definition of the outcome? What is the optimal length of patient follow-up? Is blinding appropriate when treatment duration in test arm is shorter? What are the appropriate assumptions for sample size calculation? Methods Various drugs are currently in the development pipeline. We are presenting in this paper the design of the most recently completed phase III TB trial, the OFLOTUB project, which is the pivotal trial of a registration portfolio for a gatifloxacin-containing TB regimen. It is a randomized, open-label, multicenter, controlled trial aiming to evaluate the efficacy and safety of a gatifloxacin-containing 4-month regimen (trial registration: ClinicalTrial.gov database: NCT00216385. Results In the light of the recent scientific and regulatory discussions, we discuss some of the design issues in TB clinical trials and more specifically the reasons that guided our choices, in order to best answer the trial objectives, while at the same time satisfying regulatory authority requirements. Conclusion When shortening TB treatment, we are advocating for a non-inferiority, non-blinded design, with a composite unfavorable endpoint assessed 12 months post treatment completion, and added trial procedures specifically

  13. EX8000 ramps up preparation phase in Horizon oil sands project

    Energy Technology Data Exchange (ETDEWEB)

    Anon.

    2006-07-15

    This article presented details of Hitachi's EX8000 hydraulic shovel, a key piece of equipment that will be used throughout the extensive mine preparation phase of the Horizon oil sands project. Within 2 years, the project expects to produce over 200,000 barrels of oil per day. However, more than 400 million cubic metres of soil will need to be moved before production can begin. In order to remain on schedule, overburden must be removed in massive volumes. With a 52.3 cubic yard bucket, the Hitachi EX8000 has the capacity to feed a dozen 320 metric tonne haul trucks as well as several smaller 282 metric tonne trucks, and can fill each truck in 4 passes. Material is now being moved by to an area in which dikes are being constructed to house water generated in the refining process. Stockpiling, relocation and reclamation phases will follow as the project progresses. In order to reach the oil, as much as 75 feet of overburden must be removed, including layers of sandstone, limestone, trap rock and other materials. Once the overburden has been removed, oil sand layers are also often intermixed with other materials. The EX8000 can separate the tramp material from the oil sands, improving the overall efficiency of the operation. The Alberta-based North American Construction Group, who have a 10-year contract with Canadian Natural Resources Ltd. for the Horizon project, owns more than 100 Hitachi units in various sizes and has already purchased another EX8000 which is slated for delivery in the Fall of 2006. It was concluded that the company has purchased hundreds of new trucks to handle added volumes of materials being moved as the oil sands industry gains momentum. 3 figs.

  14. Code of Conduct for wind-power projects - Phase 3

    International Nuclear Information System (INIS)

    Strub, P.; Ziegler, Ch.

    2008-11-01

    This paper discusses the results of phase three of a project concerning wind-power projects. Feasibility and strategy aspects are examined and discussed. The current state of the wind power market is discussed on the basis of the results of a survey made on the subject. The social acceptance of wind power installations is discussed, whereby the rejection of particular projects is compared with a general lack of acceptance. Requirements placed on such projects and possible solutions are discussed. Finally, the feasibility of setting up a code of conduct in the area of wind-power projects is discussed and the definition of further instruments is examined

  15. Comparison between publicly accessible publications, registries, and protocols of phase III trials indicated persistence of selective outcome reporting.

    Science.gov (United States)

    Zhang, Sheng; Liang, Fei; Li, Wenfeng

    2017-11-01

    The decision to make protocols of phase III randomized controlled trials (RCTs) publicly accessible by leading journals was a landmark event in clinical trial reporting. Here, we compared primary outcomes defined in protocols with those in publications describing the trials and in trial registration. We identified phase III RCTs published between January 1, 2012, and June 30, 2015, in The New England Journal of Medicine, The Lancet, The Journal of the American Medical Association, and The BMJ with available protocols. Consistency in primary outcomes between protocols and registries (articles) was evaluated. We identified 299 phase III RCTs with available protocols in this analysis. Out of them, 25 trials (8.4%) had some discrepancy for primary outcomes between publications and protocols. Types of discrepancies included protocol-defined primary outcome reported as nonprimary outcome in publication (11 trials, 3.7%), protocol-defined primary outcome omitted in publication (10 trials, 3.3%), new primary outcome introduced in publication (8 trials, 2.7%), protocol-defined nonprimary outcome reported as primary outcome in publication (4 trials, 1.3%), and different timing of assessment of primary outcome (4 trials, 1.3%). Out of trials with discrepancies in primary outcome, 15 trials (60.0%) had discrepancies that favored statistically significant results. Registration could be seen as a valid surrogate of protocol in 237 of 299 trials (79.3%) with regard to primary outcome. Despite unrestricted public access to protocols, selective outcome reporting persists in a small fraction of phase III RCTs. Only studies from four leading journals were included, which may cause selection bias and limit the generalizability of this finding. Copyright © 2017 Elsevier Inc. All rights reserved.

  16. Phase II and III the next generation of CLS beamline control and data acquisition systems

    International Nuclear Information System (INIS)

    Matias, E.; Beauregard, D.; Berg, R.; Black, G.; Boots, M.J.; Dolton, W.; Hunter, D.; Igarashi, R.; Liu, D.; Maxwell, D.; Miller, C.D.; Wilson, T.; Wright, G.

    2012-01-01

    The Canadian Light Source (CLS) is nearing the completion of its suite of Phase II Beamlines and in detailed design of its Phase III Beamlines. The paper presents an overview of the overall approach adopted by CLS in the development of beamline control and data acquisition systems. Building on the experience of our first phase of beamlines the CLS has continued to make extensive use of EPICS with EDM and QT based user interfaces. Increasing interpretive languages such as Python are finding a place in the beamline control systems. Web based environment such as ScienceStudio have also found a prominent place in the control system architecture as we move to tighter integration between data acquisition, visualization and data analysis. (authors)

  17. Novel solid phase extraction procedure for gold(III) on Dowex M 4195 prior to its flame atomic absorption spectrometric determination

    International Nuclear Information System (INIS)

    Tuzen, Mustafa; Saygi, Kadriye O.; Soylak, Mustafa

    2008-01-01

    A method for solid phase extraction (SPE) of gold(III) using Dowex M 4195 chelating resin has been developed. The optimum experimental conditions for the quantitative sorption of gold(III), pH, effect of flow rates, eluent types, sorption capacity and the effect of diverse ions on the sorption of gold(III) have been investigated. The chelating resin can be reused for more than 100 cycles of sorption-desorption without any significant change in sorption of gold(III) ions. The recovery values for gold(III) and detection limit (LOD) of gold were greater than 95% and 1.61 μg L -1 , respectively. The preconcentration factor was 31. The relative standard deviation of the method was -1 . The proposed method has been applied for the determination of gold(III) in some real samples including water, soil and sediment samples

  18. Improving Climate Projections Using "Intelligent" Ensembles

    Science.gov (United States)

    Baker, Noel C.; Taylor, Patrick C.

    2015-01-01

    Recent changes in the climate system have led to growing concern, especially in communities which are highly vulnerable to resource shortages and weather extremes. There is an urgent need for better climate information to develop solutions and strategies for adapting to a changing climate. Climate models provide excellent tools for studying the current state of climate and making future projections. However, these models are subject to biases created by structural uncertainties. Performance metrics-or the systematic determination of model biases-succinctly quantify aspects of climate model behavior. Efforts to standardize climate model experiments and collect simulation data-such as the Coupled Model Intercomparison Project (CMIP)-provide the means to directly compare and assess model performance. Performance metrics have been used to show that some models reproduce present-day climate better than others. Simulation data from multiple models are often used to add value to projections by creating a consensus projection from the model ensemble, in which each model is given an equal weight. It has been shown that the ensemble mean generally outperforms any single model. It is possible to use unequal weights to produce ensemble means, in which models are weighted based on performance (called "intelligent" ensembles). Can performance metrics be used to improve climate projections? Previous work introduced a framework for comparing the utility of model performance metrics, showing that the best metrics are related to the variance of top-of-atmosphere outgoing longwave radiation. These metrics improve present-day climate simulations of Earth's energy budget using the "intelligent" ensemble method. The current project identifies several approaches for testing whether performance metrics can be applied to future simulations to create "intelligent" ensemble-mean climate projections. It is shown that certain performance metrics test key climate processes in the models, and

  19. Evaluation of candidate magnetohydrodynamic materials for the U-02 Phase III test

    International Nuclear Information System (INIS)

    Marchant, D.D.; Bates, J.L.

    1978-06-01

    As part of a cooperative U.S.--U.S.S.R. program, electrode and insulator materials tested at the Westinghouse Electrode Systems Test Facility in Pittsburgh, Pennsylvania, were evaluated. From this evaluation materials will be selected for use in the third phase of tests being conducted in the U-02 magnetohydrodynamics test facility in the Soviet Union. Electrode and insulator materials were examined with both an optical microscope and a scanning electron microscope. The cathodes were found to behave differently from the anodes; most notably, the cathodes showed greater potassium interaction. The lanthanum chromite-based electrodes (excluding those fabricated by plasma-spraying) are recommended for testing in the U-02 Phase III test. Hotpressed, fused-grained MgO and sintered MgAl 2 O 4 are recommended as insulator materials. The electrode attachment techniques used in the Westinghouse Tests were inadequate and need to be modified for the U-02 test

  20. Methodology of quality improvement projects for the Texas Medicare population.

    Science.gov (United States)

    Pendergrass, P W; Abel, R L; Bing, M; Vaughn, R; McCauley, C

    1998-07-01

    The Texas Medical Foundation, the quality improvement organization for the state of Texas, develops local quality improvement projects for the Medicare population. These projects are developed as part of the Health Care Quality Improvement Program undertaken by the Health Care Financing Administration. The goal of a local quality improvement project is to collaborate with providers to identify and reduce the incidence of unintentional variations in the delivery of care that negatively impact outcomes. Two factors are critical to the success of a quality improvement project. First, as opposed to peer review that is based on implicit criteria, quality improvement must be based on explicit criteria. These criteria represent key steps in the delivery of care that have been shown to improve outcomes for a specific disease. Second, quality improvement must be performed in partnership with the health care community. As such, the health care community must play an integral role in the design and evaluation of a quality improvement project and in the design and implementation of the resulting quality improvement plan. Specifically, this article provides a historical perspective for the transition from peer review to quality improvement. It discusses key steps used in developing and implementing local quality improvement projects including topic selection, quality indicator development, collaborator recruitment, and measurement of performance/improvement. Two Texas Medical Foundation projects are described to highlight the current methodology and to illustrate the impact of quality improvement projects.

  1. Improved Design Methods for Robust Single- and Three-Phase ac-dc-ac Power Converters

    DEFF Research Database (Denmark)

    Qin, Zian

    . The approaches for improving their performance, in terms of the voltage stress, efficiency, power density, cost, loss distribution, and temperature, will be studied. The structure of the thesis is as follows, Chapter 1 presents the introduction and motivation of the whole project as well as the background...... becomes a emerging challenge. Accordingly, installation of sustainable power generators like wind turbines and solar panels has experienced a large increase during the last decades. Meanwhile, power electronics converters, as interfaces in electrical system, are delivering approximately 80 % electricity...... back-to-back, and meanwhile improve the harmonics, control flexibility, and thermal distribution between the switches. Afterwards, active power decoupling methods for single-phase inverters or rectifiers that are similar to the single-phase ac-dc-ac converter, are studied in Chapter 4...

  2. Gene expression of transporters and phase I/II metabolic enzymes in murine small intestine during fasting

    Directory of Open Access Journals (Sweden)

    van der Meijde Jolanda

    2007-08-01

    Full Text Available Abstract Background Fasting has dramatic effects on small intestinal transport function. However, little is known on expression of intestinal transport and phase I/II metabolism genes during fasting and the role the fatty acid-activated transcription factor PPARα may play herein. We therefore investigated the effects of fasting on expression of these genes using Affymetrix GeneChip MOE430A arrays and quantitative RT-PCR. Results After 24 hours of fasting, expression levels of 33 of the 253 analyzed transporter and phase I/II metabolism genes were changed. Upregulated genes were involved in transport of energy-yielding molecules in processes such as glycogenolysis (G6pt1 and mitochondrial and peroxisomal oxidation of fatty acids (Cact, Mrs3/4, Fatp2, Cyp4a10, Cyp4b1. Other induced genes were responsible for the inactivation of the neurotransmitter serotonin (Sert, Sult1d1, Dtd, Papst2, formation of eicosanoids (Cyp2j6, Cyp4a10, Cyp4b1, or for secretion of cholesterol (Abca1 and Abcg8. Cyp3a11, typically known because of its drug metabolizing capacity, was also increased. Fasting had no pronounced effect on expression of phase II metabolic enzymes, except for glutathione S-transferases which were down-regulated. Time course studies revealed that some genes were acutely regulated, whereas expression of other genes was only affected after prolonged fasting. Finally, we identified 8 genes that were PPARα-dependently upregulated upon fasting. Conclusion We have characterized the response to fasting on expression of transporters and phase I/II metabolic enzymes in murine small intestine. Differentially expressed genes are involved in a variety of processes, which functionally can be summarized as a increased oxidation of fat and xenobiotics, b increased cholesterol secretion, c increased susceptibility to electrophilic stressors, and d reduced intestinal motility. This knowledge increases our understanding of gut physiology, and may be of relevance

  3. Early orthopedic correction of skeletal Class III malocclusion using combined reverse twin block and face mask therapy

    Directory of Open Access Journals (Sweden)

    Vinay Kumar Chugh

    2015-01-01

    Full Text Available A 6-year 8-month-old girl presented with a moderate Class III malocclusion characterized by mid-face deficiency and an anterior cross bite. In the first phase, the patient was treated with combination of reverse twin block and facemask therapy. In phase two, fixed appliances were placed in the permanent dentition. The post treatment results were good and a favorable growth tendency could be observed. The correction of the Class III malocclusion occurred by a combination of skeletal and dental improvements. This report shows successful correction of skeletal Class III malocclusion in the early transitional dentition using combination therapy.

  4. Development of a central data warehouse for statewide ITS and transportation data in Florida phase III : final report.

    Science.gov (United States)

    2009-12-15

    This report documents Phase III of the development and operation of a prototype for the Statewide Transportation : Engineering Warehouse for Archived Regional Data (STEWARD). It reflects the progress on the development and : operation of STEWARD sinc...

  5. Youth's social network structures and peer influences: study protocol MyMovez project - Phase I.

    Science.gov (United States)

    Bevelander, Kirsten E; Smit, Crystal R; van Woudenberg, Thabo J; Buijs, Laura; Burk, William J; Buijzen, Moniek

    2018-04-16

    Youth are an important target group for social network interventions, because they are particularly susceptible to the adaptation of healthy and unhealthy habits and behaviors of others. They are surrounded by 'social influence agents' (i.e., role models such as family, friends and peers) that co-determine their dietary intake and physical activity. However, there is a lack of systematic and comprehensive research on the implementation of a social network approach in health campaigns. The MyMovez research project aims to fill this gap by developing a method for effective social network campaign implementation. This protocol paper describes the design and methods of Phase I of the MyMovez project, aiming to unravel youth's social network structures in combination with individual, psychosocial, and environmental factors related to energy intake and expenditure. In addition, the Wearable Lab is developed to enable an attractive and state-of-the-art way of collecting data and online campaign implementation via social networks. Phase I of the MyMovez project consists of a large-scale cross-sequential cohort study (N = 953; 8-12 and 12-15 y/o). In five waves during a 3-year period (2016-2018), data are collected about youth's social network exposure, media consumption, socialization experiences, psychological determinants of behavior, physical environment, dietary intake (snacking and drinking behavior) and physical activity using the Wearable Lab. The Wearable Lab exists of a smartphone-based research application (app) connected to an activity tracking bracelet, that is developed throughout the duration of the project. It generates peer- and self-reported (e.g., sociometric data and surveys) and experience sampling data, social network beacon data, real-time physical activity data (i.e., steps and cycling), location information, photos and chat conversation data from the app's social media platform Social Buzz. The MyMovez project - Phase I is an innovative cross

  6. Phase unwrapping algorithm based on multi-frequency fringe projection and fringe background for fringe projection profilometry

    International Nuclear Information System (INIS)

    Zhang, Chunwei; Zhao, Hong; Gu, Feifei; Ma, Yueyang

    2015-01-01

    A phase unwrapping algorithm specially designed for the phase-shifting fringe projection profilometry (FPP) is proposed. It combines a revised dual-frequency fringe projectionalgorithm and a proposed fringe background based quality guided phase unwrapping algorithm (FB-QGPUA). Phase demodulated from the high-frequency fringe patterns is partially unwrapped by that demodulated from the low-frequency ones. Then FB-QGPUA is adopted to further unwrap the partially unwrapped phase. Influences of the phase error on the measurement are researched. Strategy to select the fringe pitch is given. Experiments demonstrate that the proposed method is very robust and efficient. (paper)

  7. Synthesis, characterization and stability of Cr(III) and Fe(III) hydroxides

    International Nuclear Information System (INIS)

    Papassiopi, N.; Vaxevanidou, K.; Christou, C.; Karagianni, E.; Antipas, G.S.E.

    2014-01-01

    Highlights: • Fe(III)–Cr(III) hydroxides enhance groundwater quality better than pure Cr(III) compounds. • Crystalline Cr(OH) 3 ·3H 2 O was unstable, with a solubility higher than 50 μg/l. • Amorphous Cr(OH) 3 (am) was stable with a solubility lower than 50 μg/l in the range 5.7 0.75 Cr 0.25 (OH) 3 , the stability region was extended to 4.8 3 ·xH 2 O whereas in the presence of iron the precipitate is a mixed Fe (1−x) Cr x (OH) 3 phase. In this study, we report on the synthesis, characterisation and stability of mixed (Fe x ,Cr 1−x )(OH) 3 hydroxides as compared to the stability of Cr(OH) 3 . We established that the plain Cr(III) hydroxide, abiding to the approximate molecular formula Cr(OH) 3 ·3H 2 O, was crystalline, highly soluble, i.e. unstable, with a tendency to transform into the stable amorphous hydroxide Cr(OH) 3 (am) phase. Mixed Fe 0.75 Cr 0.25 (OH) 3 hydroxides were found to be of the ferrihydrite structure, Fe(OH) 3 , and we correlated their solubility to that of a solid solution formed by plain ferrihydrite and the amorphous Cr(III) hydroxide. Both our experimental results and thermodynamic calculations indicated that mixed Fe(III)–Cr(III) hydroxides are more effective enhancers of groundwater quality, in comparison to the plain amorphous or crystalline Cr(III) hydroxides, the latter found to have a solubility typically higher than 50 μg/l (maximum EU permitted Cr level in drinking water), while the amorphous Cr(OH) 3 (am) phase was within the drinking water threshold in the range 5.7 0.75 Cr 0.25 (OH) 3 hydroxides studied were of extended stability in the 4.8 < pH < 13.5 range

  8. IDC Reengineering Phase 2 Project Scope.

    Energy Technology Data Exchange (ETDEWEB)

    Harris, James M. [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States)

    2015-02-01

    This report provides a brief description of the scope of the IDC Reengineering Phase 2 project. It describes the goals and objectives of reengineering, the system definition, and the technical scope of the system. REVISIONS Version Date Author/Team Revision Description Authorized by 1.0 9/25/2014 SNL IDC Reengineering Team Unlimited Release for I2 M. Harris 1.1 28/01/2015 IDC Reengineering Team Align with previous IDC scope document E. Tomuta.

  9. The international INTRAVAL project. Phase 2, Summary report

    International Nuclear Information System (INIS)

    Larsson, A.; Pers, K.; Skagius, K.; Dverstorp, B.

    1997-01-01

    The international project INTRAVAL addresses the validation of models of transport of radionuclides through groundwater in the geosphere. Such models are used in the assessment of the long-term safety of radioactive waste disposal systems. The second phase of INTRAVAL, which started in 1990, was concluded at the end of 1993. The objective of Phase 2 was to increase the understanding how various geophysical, geohydrological and geochemical phenomena of importance for radionuclide transport from a repository to the biosphere could be described by mathematical models and to study the model validation process. Summarized results from Phase 2 of the INTRAVAL study are presented in this report. (K.A.)

  10. An improvement project within urological care.

    Science.gov (United States)

    Khatami, Annelie; Rosengren, Kristina

    2015-01-01

    The purpose of this paper is to describe staff experiences in an on-going improvement project regarding patients with ureteral stones. A qualitative descriptive study based on eight group interviews and 48 narratives, was performed. Data were analysed using qualitative content analysis. Trustworthiness was ensured by using a well-documented improvement process method during six months. The results formed three categories: an absent comprehensive view; complexity; and vulnerability within the organisation. A holistic perspective regarding urological care at the micro-, meso- and macro-levels is needed to improve planning and caring processes. This study includes one team (six members, different health professionals) within the same urology department. Results show that staff need information, such as guidelines and support throughout the improvement work to deliver high-quality care. Moreover, there is a need for evidence-based guidelines at national level to support improvement work. Healthcare staff need to pay attention to all team member needs to improve urological care. Organisational and managerial aspect are needed to support clear and common goals regarding healthcare improvement work. Urological improvement projects, generally, are lacking, which is why this study is important to improve nephrolithiasis patient care.

  11. Small car exposure data project. Phase 1 : methodology

    Science.gov (United States)

    1985-10-01

    The Small Car Exposure Data Project represents the first phase of an effort to build a data : base of exposure variables for crash-avoidance studies. Among these are: (1) vehicle make, : model, year, body style, wheel base, weight, and horsepower; (2...

  12. Lapatinib versus hormone therapy in patients with advanced renal cell carcinoma: a randomized phase III clinical trial

    DEFF Research Database (Denmark)

    Ravaud, Alain; Hawkins, Robert; Gardner, Jason P

    2008-01-01

    PURPOSE: Lapatinib is an orally reversible inhibitor of epidermal growth factor receptor (EGFR)/human epidermal growth factor receptor 2 (HER-2) tyrosine kinases with demonstrated activity in patients with HER-2-positive breast cancer. In the current phase III open-label trial, lapatinib was comp...

  13. UMTRA Project-Level Cost Reduction/Productivity Improvement Program manual

    International Nuclear Information System (INIS)

    1995-06-01

    Mission of the Uranium Mill Tailings Remedial Action (UMTRA) Project Cost Reduction/Productivity Improvement Program (CR/PIP) is to contribute to the UMTRA Project's environmental restoration mission by providing the means to achieve and recognize continuous improvements and cost savings. This manual includes program definition, description of UMTRA project organizational responsibilities and interfaces with existing project functions, guidance to contractors, and definition of project-level functions

  14. Fringe-period selection for a multifrequency fringe-projection phase unwrapping method

    International Nuclear Information System (INIS)

    Zhang, Chunwei; Zhao, Hong; Jiang, Kejian

    2016-01-01

    The multi-frequency fringe-projection phase unwrapping method (MFPPUM) is a typical phase unwrapping algorithm for fringe projection profilometry. It has the advantage of being capable of correctly accomplishing phase unwrapping even in the presence of surface discontinuities. If the fringe frequency ratio of the MFPPUM is too large, fringe order error (FOE) may be triggered. FOE will result in phase unwrapping error. It is preferable for the phase unwrapping to be kept correct while the fewest sets of lower frequency fringe patterns are used. To achieve this goal, in this paper a parameter called fringe order inaccuracy (FOI) is defined, dominant factors which may induce FOE are theoretically analyzed, a method to optimally select the fringe periods for the MFPPUM is proposed with the aid of FOI, and experiments are conducted to research the impact of the dominant factors in phase unwrapping and demonstrate the validity of the proposed method. Some novel phenomena are revealed by these experiments. The proposed method helps to optimally select the fringe periods and detect the phase unwrapping error for the MFPPUM. (paper)

  15. Guide for prioritizing power plant productivity improvement projects: handbook of availability improvement methodology

    International Nuclear Information System (INIS)

    1981-01-01

    As part of its program to help improve electrical power plant productivity, the Department of Energy (DOE) has developed a methodology for evaluating productivity improvement projects. This handbook presents a simplified version of this methodology called the Availability Improvement Methodology (AIM), which provides a systematic approach for prioritizing plant improvement projects. Also included in this handbook is a description of data taking requirements necessary to support the AIM methodology, benefit/cost analysis, and root cause analysis for tracing persistent power plant problems. In applying the AIM methodology, utility engineers should be mindful that replacement power costs are frequently greater for forced outages than for planned outages. Equivalent availability includes both. A cost-effective ranking of alternative plant improvement projects must discern between those projects which will reduce forced outages and those which might reduce planned outages. As is the case with any analytical procedure, engineering judgement must be exercised with respect to results of purely mathematical calculations

  16. Search for dark photons using data from CRESST-II Phase 2

    Science.gov (United States)

    Gütlein, A.; Angloher, G.; Bento, A.; Bucci, C.; Canonica, L.; Defay, X.; Erb, A.; Feilitzsch, F. v.; Ferreiro Iachellini, N.; Gorla, P.; Hauff, D.; Jochum, J.; Kiefer, M.; Kluck, H.; Kraus, H.; Lanfranchi, J.-C.; Loebell, J.; Mancuso, M.; Münster, A.; Pagliarone, C.; Petricca, F.; Potzel, W.; Pröbst, F.; Puig, R.; Reindl, F.; Schäffner, K.; Schieck, J.; Schönert, S.; Seidel, W.; Stahlberg, M.; Stodolsky, L.; Strandhagen, C.; Strauss, R.; Tanzke, A.; Trinh Thi, H. H.; Türkoǧlu, C.; Uffinger, M.; Ulrich, A.; Usherov, I.; Wawoczny, S.; Willers, M.; Wüstrich, M.; Zöller, A.

    2017-09-01

    Understanding the nature and origin of dark matter is one of the most important challenges for modern particle physics. During the previous decade the sensitivities of direct dark matter searches have improved by several orders of magnitude. These experiments focus their work mainly on the search for dark-matter particles interacting with nuclei (e.g. Weakly Interacting Massive Particles, WIMPs). However, there exists a large variety of different candidates for dark-matter particles. One of these candidates, the so-called dark photon, is a long-lived vector boson with a kinetic mixing to the standard-model photon. In this work we present the preliminary results of our search for dark photons. Using data from the direct dark matter search CRESST-II Phase 2 we can improve the existing constraints for the kinetic mixing for dark-photon masses between 0.3 and 0.5 keV/c2. In addition, we also present projected sensitivities for the next phases of the CRESST-III experiment showing great potential to improve the sensitivity for dark-photon masses below 1 keV.

  17. SNF project engineering process improvement plan

    International Nuclear Information System (INIS)

    KELMENSON, R.L.

    1999-01-01

    This Engineering Process Improvement Plan documents the activities and plans to be taken by the SNF Project (the Project) to support its engineering process and to produce a consolidated set of engineering procedures that are fully compliant with the requirements of HNF-PRO-1819 (1819). These requirements are imposed on all engineering activities performed for the Project and apply to all life-cycle stages of the Project's systems, structures and components (SSCs). This Plan describes the steps that will be taken by the Project during the transition period to ensure that new procedures are effectively integrated into the Project's work process as these procedures are issued. The consolidated procedures will be issued and implemented by September 30, 1999

  18. Opioid Patient Controlled Analgesia (PCA) use during the Initial Experience with the IMPROVE PCA Trial: A Phase III Analgesic Trial for Hospitalized Sickle Cell Patients with Painful Episodes

    OpenAIRE

    Dampier, Carlton D.; Smith, Wally R.; Kim, Hae-Young; Wager, Carrie Greene; Bell, Margaret C.; Minniti, Caterina P.; Keefer, Jeffrey; Hsu, Lewis; Krishnamurti, Lakshmanan; Mack, A. Kyle; McClish, Donna; McKinlay, Sonja M.; Miller, Scott T.; Osunkwo, Ifeyinwa; Seaman, Phillip

    2011-01-01

    Opioid analgesics administered by patient-controlled analgesia (PCA) are frequently used for pain relief in children and adults with sickle cell disease (SCD) hospitalized for persistent vaso-occlusive pain, but optimum opioid dosing is not known. To better define PCA dosing recommendations, a multi-center phase III clinical trial was conducted comparing two alternative opioid PCA dosing strategies (HDLI-higher demand dose with low constant infusion or LDHI- lower demand dose and higher const...

  19. A service evaluation and improvement project: a three year systematic audit cycle of the physiotherapy treatment for Lateral Epicondylalgia.

    Science.gov (United States)

    Barratt, Paul A; Selfe, James

    2018-06-01

    To improve outcomes of physiotherapy treatment for patients with Lateral Epicondylalgia. A systematic audit and quality improvement project over three phases, each of one year duration. Salford Royal NHS Foundation Trust Teaching Hospital Musculoskeletal Physiotherapy out-patients department. n=182. Phase one - individual discretion; Phase two - strengthening as a core treatment however individual discretion regarding prescription and implementation; Phase three - standardised protocol using high load isometric exercise, progressing on to slow combined concentric & eccentric strengthening. Global Rating of Change Scale, Pain-free grip strength, Patient Rated Tennis Elbow Evaluation, Tampa Scale of Kinesophobia-11. Phase three demonstrated a reduction in the average number of treatments by 42% whilst improving the number of responders to treatment by 8% compared to phase one. Complete cessation of non-evidence based treatments was also observed by phase three. Strengthening should be a core treatment for LE. Load setting needs to be sufficient. In phase three of the audit a standardised tendon loading programme using patient specific high load isometric exercises into discomfort/pain demonstrated a higher percentage of responders compared to previous phases. Copyright © 2017 Chartered Society of Physiotherapy. Published by Elsevier Ltd. All rights reserved.

  20. OECD/NEA Aagesta decontamination project. Phase 1, final report

    International Nuclear Information System (INIS)

    1982-12-01

    The objective of the project is to utilize the four primary loops of the Aagesta reactor to demonstrate decontamination methods for PWR primary systems. The first phase of the project consisted of laboratory scale tests. The methods tested were developed at a) Studsvik Energiteknik AB, Sweden (a soft chemistry). b) Kraftwerk Union AG, Federal Republic of Germany, (two chemistries, one soft and one hard). c) Swiss Federal Institute of Reactor Research (two chemistries, one soft and one hard). d) Berkeley Nuclear Laboratories, United Kingdom, (a soft chemistry). The test programme consisted of decontamination tests on steam generator tubing and other active material from Aagesta and a number of operating reactors as well as material compatibility tests on standardized samples of a representative selection of modern PWR primary system materials. Six countries have participated in Phase I of the project - the four countries named above as well as the United States of America and Italy. Studsvik Energiteknik AB was appointed Project leader. The results show that all six processes in general met the acceptance criteria both regarding decontamination and corrosion. The decontamination results with the hard chemistries were rather uneven. (Author)

  1. Improving the treatment of non-aqueous phase TCE in low permeability zones with permanganate.

    Science.gov (United States)

    Chokejaroenrat, Chanat; Comfort, Steve; Sakulthaew, Chainarong; Dvorak, Bruce

    2014-03-15

    Treating dense non-aqueous phase liquids (DNAPLs) embedded in low permeability zones (LPZs) is a particularly challenging issue for injection-based remedial treatments. Our objective was to improve the sweeping efficiency of permanganate (MnO4(-)) into LPZs to treat high concentrations of TCE. This was accomplished by conducting transport experiments that quantified the penetration of various permanganate flooding solutions into a LPZ that was spiked with non-aqueous phase (14)C-TCE. The treatments we evaluated included permanganate paired with: (i) a shear-thinning polymer (xanthan); (ii) stabilization aids that minimized MnO2 rind formation and (iii) a phase-transfer catalyst. In addition, we quantified the ability of these flooding solutions to improve TCE destruction under batch conditions by developing miniature LPZ cylinders that were spiked with (14)C-TCE. Transport experiments showed that MnO4(-) alone was inefficient in penetrating the LPZ and reacting with non-aqueous phase TCE, due to a distinct and large MnO2 rind that inhibited the TCE from further oxidant contact. By including xanthan with MnO4(-), the sweeping efficiency increased (90%) but rind formation was still evident. By including the stabilization aid, sodium hexametaphosphate (SHMP) with xanthan, permanganate penetrated 100% of the LPZ, no rind was observed, and the percentage of TCE oxidized increased. Batch experiments using LPZ cylinders allowed longer contact times between the flooding solutions and the DNAPL and results showed that SHMP+MnO4(-) improved TCE destruction by ∼16% over MnO4(-) alone (56.5% vs. 40.1%). These results support combining permanganate with SHMP or SHMP and xanthan as a means of treating high concentrations of TCE in low permeable zones. Copyright © 2014 Elsevier B.V. All rights reserved.

  2. Improved design for large wind turbine blades of fibre composites (Phase 3) - Summary report

    Energy Technology Data Exchange (ETDEWEB)

    Soerensen, B.F. (Risoe DTU, Materials Research Div., Roskilde (Denmark)); Branner, K. (Risoe DTU, Wind Energy Div., Roskilde (Denmark)); Lund, E. (Aalborg Univ., Dept. of Mechanical Engineering, Aalborg (Denmark)); Wedel-Heinen, J. (Vestas Wind System, Randers (Denmark)); Garm, J.H. (LM Glasfiber, Kolding (Denmark))

    2009-06-15

    An overview is given of the activities of the project 'Improved design for large wind turbine blades (Phase 3)', partially supported by the Danish Energy Agency under the Ministry of Climate and Energy through the EFP-grant no. 33031-0078. The project was focussed at the development of new design methods for wind turbine blades, so that uncertainties associated with damage and defects can be reduced. The following topics with respect to failure modes were covered: Buckling-driven delamination of load-carrying laminates, cracking along interfaces in material joints, implementation of cohesive laws in finite element programmes and hierarchical finite element models. Methods and major research results of the project are summarised. Some future goals for future research activities are briefly discussed. (author)

  3. Novel concepts for the compression of large volumes of carbon dioxide-phase III

    Energy Technology Data Exchange (ETDEWEB)

    Moore, J. Jeffrey [Southwest Research Inst., San Antonio, TX (United States); Allison, Timothy C. [Southwest Research Inst., San Antonio, TX (United States); Evans, Neal D. [Southwest Research Inst., San Antonio, TX (United States); Moreland, Brian [Southwest Research Inst., San Antonio, TX (United States); Hernandez, Augusto J. [Southwest Research Inst., San Antonio, TX (United States); Day, Meera [Southwest Research Inst., San Antonio, TX (United States); Ridens, Brandon L. [Southwest Research Inst., San Antonio, TX (United States)

    2014-06-30

    In the effort to reduce the release of CO2 greenhouse gases to the atmosphere, sequestration of CO2 from Integrated Gasification Combined Cycle (IGCC) and Oxy-Fuel power plants is being pursued. This approach, however, requires significant compression power to boost the pressure to typical pipeline levels. The penalty can be as high as 8-12% on a typical IGCC plant. The goal of this research is to reduce this penalty through novel compression concepts and integration with existing IGCC processes. The primary objective of the study of novel CO2 compression concepts is to reliably boost the pressure of CO2 to pipeline pressures with the minimal amount of energy required. Fundamental thermodynamics were studied to explore pressure rise in both liquid and gaseous states. For gaseous compression, the project investigated novel methods to compress CO2 while removing the heat of compression internal to the compressor. The highpressure ratio, due to the delivery pressure of the CO2 for enhanced oil recovery, results in significant heat of compression. Since less energy is required to boost the pressure of a cooler gas stream, both upstream and inter-stage cooling is desirable. While isothermal compression has been utilized in some services, it has not been optimized for the IGCC environment. Phase I of this project determined the optimum compressor configuration and developed technology concepts for internal heat removal. Other compression options using liquefied CO2 and cryogenic pumping were explored as well. Preliminary analysis indicated up to a 35% reduction in power is possible with the new concepts being considered. In the Phase II program, two experimental test rigs were developed to investigate the two concepts further. A new pump loop facility was constructed to qualify a cryogenic turbopump for use on liquid CO2 . Also, an internally cooled compressor diaphragm was developed

  4. Improved adaptive genetic algorithm with sparsity constraint applied to thermal neutron CT reconstruction of two-phase flow

    Science.gov (United States)

    Yan, Mingfei; Hu, Huasi; Otake, Yoshie; Taketani, Atsushi; Wakabayashi, Yasuo; Yanagimachi, Shinzo; Wang, Sheng; Pan, Ziheng; Hu, Guang

    2018-05-01

    Thermal neutron computer tomography (CT) is a useful tool for visualizing two-phase flow due to its high imaging contrast and strong penetrability of neutrons for tube walls constructed with metallic material. A novel approach for two-phase flow CT reconstruction based on an improved adaptive genetic algorithm with sparsity constraint (IAGA-SC) is proposed in this paper. In the algorithm, the neighborhood mutation operator is used to ensure the continuity of the reconstructed object. The adaptive crossover probability P c and mutation probability P m are improved to help the adaptive genetic algorithm (AGA) achieve the global optimum. The reconstructed results for projection data, obtained from Monte Carlo simulation, indicate that the comprehensive performance of the IAGA-SC algorithm exceeds the adaptive steepest descent-projection onto convex sets (ASD-POCS) algorithm in restoring typical and complex flow regimes. It especially shows great advantages in restoring the simply connected flow regimes and the shape of object. In addition, the CT experiment for two-phase flow phantoms was conducted on the accelerator-driven neutron source to verify the performance of the developed IAGA-SC algorithm.

  5. Elementary and middle school science improvement project

    Science.gov (United States)

    Mcguire, Saundra Y.

    1989-01-01

    The Alabama A and M University Elementary and Middle School Science Improvement Project (Project SIP) was instituted to improve the science knowledge of elementary and middle school teachers using the experimental or hands-on approach. Summer workshops were conducted during the summers of 1986, 1987, and 1988 in the areas of biology, chemistry, physics, and electricity, and magnetism. Additionally, a manual containing 43 lessons which included background information, experiments and activities for classroom and home use was provided to each teacher. During the course of the project activities, the teachers interacted with various university faculty members, scientists, and NASA staff. The administrative aspects of the program, the delivery of the services to participating teachers, and the project outcome are addressed.

  6. Phased Startup Initiative Phases 3 and 4 Test Plan and Test Specification (OCRWM)

    International Nuclear Information System (INIS)

    PITNER, A.L.

    2000-01-01

    Construction for the Spent Nuclear Fuel (SNF) Project facilities is continuing per the Level III Baseline Schedule, and installation of the Fuel Retrieval System (FRS) and Integrated Water Treatment System (IWTS) in K West Basin is now complete. In order to accelerate the project, a phased start up strategy to initiate testing of the FRS and IWTS early in the overall project schedule was proposed (Williams 1999). Wilkinson (1999) expands the definition of the original proposal into four functional testing phases of the Phased Startup Initiative (PSI). Phases 1 and 2 are based on performing functional tests using dummy fuel. These tests are described in separate planning documents. This test plan provides overall guidance for Phase 3 and 4 tests, which are performed using actual irradiated N fuel assemblies. The overall objective of the Phase 3 and 4 testing is to verify how the FRS and IWTS respond while processing actual fuel. Conducting these tests early in the project schedule will allow identification and resolution of equipment and process problems before they become activities on the start-up critical path. The specific objectives of this test plan are to: (1) Define the test scope for the FRS and IWTS; (2) Provide detailed test requirements that can be used to write the specific test procedures; (3) Define data required and measurements to be taken. Where existing methods to obtain these do not exist, enough detail will be provided to define required additional equipment; and (4) Define specific test objectives and acceptance criteria

  7. 200-ZP-1 phase II and III IRM groundwater pump and treat site safety plan

    International Nuclear Information System (INIS)

    St. John, C.H.

    1996-07-01

    This safety plan covers operations, maintenance, and support activities related to the 200-ZP-1 Phase II and III Ground Water Pump- and-Treat Facility. The purpose of the facility is to extract carbon tetrachloride contaminated groundwater underlying the ZP-1 Operable Unit; separate the contaminant from the groundwater; and reintroduce the treated water to the aquifer. An air stripping methodology is employed to convert volatile organics to a vapor phase for absorption onto granular activated carbon. The automated process incorporates a variety of process and safety features that shut down the process system in the event that process or safety parameters are exceeded or compromised

  8. ELECTRONIC COMPLIANCE AND APPROVAL PROJECT (ECAP)

    Energy Technology Data Exchange (ETDEWEB)

    Hope Morgan; Richard A. Varela; Deborah LaHood; Susan Cisco; Mary Ann Benavides; Donna Burks

    2002-11-01

    The Texas Railroad Commission (RRC), working in partnership with the United States Department of Energy and the oil and gas industry it regulates, is implementing a strategy for improving efficiency in regulations and significantly reducing administrative operating costs through the Electronic Compliance and Approval Process (ECAP). The project will streamline regulatory compliance and reporting by providing the ability to electronically submit, process, and query oil and gas applications and reports through the Internet-based ECAP system. Implementation of an ECAP drilling permit pilot project began September 1999 after funding resources were secured--a $700,000 grant from the U.S. Department of Energy and an appropriation of $1.4 million from the Texas Legislature. The pilot project involves creating the ability to file, review, and approve a well's drilling permit application through a completely electronic process. The pilot project solution will ultimately provide the infrastructure, technology, and electronic modules to enable the filing of all compliance permits and performance reports through the internet from a desktop computer. The pilot project was conducted in three phases. The first phase, implemented May 2000, provided the infrastructure that allows the electronic filing and approval of simple drilling permit applications, associated fees, and attachments. The official ''roll-out'' of ECAP and the first electronically filed drilling permit application occurred on May 11, 2000 in Dallas in conjunction with an Internet Workshop sponsored by the Petroleum Technology Transfer Council. After the completion of Phase I, the ECAP team conducted an extensive review of progress to date and analyzed requirements and opportunities for future steps. The technical team identified core infrastructure modifications that would facilitate and better support future development and expansion of the ECAP system and work began on database structure

  9. Synthesis, characterization and stability of Cr(III) and Fe(III) hydroxides

    Energy Technology Data Exchange (ETDEWEB)

    Papassiopi, N.; Vaxevanidou, K.; Christou, C.; Karagianni, E.; Antipas, G.S.E., E-mail: gantipas@metal.ntua.gr

    2014-01-15

    Highlights: • Fe(III)–Cr(III) hydroxides enhance groundwater quality better than pure Cr(III) compounds. • Crystalline Cr(OH){sub 3}·3H{sub 2}O was unstable, with a solubility higher than 50 μg/l. • Amorphous Cr(OH){sub 3}(am) was stable with a solubility lower than 50 μg/l in the range 5.7 < pH < 11. • For mixed Fe{sub 0.75}Cr{sub 0.25}(OH){sub 3}, the stability region was extended to 4.8 < pH < 13.5. -- Abstract: Chromium is a common contaminant of soils and aquifers and constitutes a major environmental problem. In nature, chromium usually exists in the form of two oxidation states, trivalent, Cr(III), which is relatively innocuous for biota and for the aquatic environment, and hexavalent, Cr(VI) which is toxic, carcinogenic and very soluble. Accordingly, the majority of wastewater and groundwater treatment technologies, include a stage where Cr(VI) is reduced to Cr(III), in order to remove chromium from the aqueous phase and bind the element in the form of environmentally stable solid compounds. In the absence of iron the final product is typically of the form Cr(OH){sub 3}·xH{sub 2}O whereas in the presence of iron the precipitate is a mixed Fe{sub (1−x)}Cr{sub x}(OH){sub 3} phase. In this study, we report on the synthesis, characterisation and stability of mixed (Fe{sub x},Cr{sub 1−x})(OH){sub 3} hydroxides as compared to the stability of Cr(OH){sub 3}. We established that the plain Cr(III) hydroxide, abiding to the approximate molecular formula Cr(OH){sub 3}·3H{sub 2}O, was crystalline, highly soluble, i.e. unstable, with a tendency to transform into the stable amorphous hydroxide Cr(OH){sub 3}(am) phase. Mixed Fe{sub 0.75}Cr{sub 0.25}(OH){sub 3} hydroxides were found to be of the ferrihydrite structure, Fe(OH){sub 3}, and we correlated their solubility to that of a solid solution formed by plain ferrihydrite and the amorphous Cr(III) hydroxide. Both our experimental results and thermodynamic calculations indicated that mixed Fe(III)–Cr(III

  10. Brazilian Decimetric Array (BDA) project - Phase II

    Science.gov (United States)

    Faria, C.; Stephany, S.; Sawant, H. S.; Cecatto, J. R.; Fernandes, F. C. R.

    2010-02-01

    The configuration of the second phase of the Brazilian Decimetric Array (BDA), installed at Cachoeira Paulista, Brazil (Longitude 45° 0‧ 20″ W and Latitude 22° 41‧ 19″ S), is a T-shaped array where 21 antennas are being added to existing 5 antennas of the first phase. In the third phase, in each arm of the T array, four more antennas will be added and baselines will be increased to 2.5 × 1.25 km in east-west and south directions, respectively. The antennas will be equally spaced at the distances of 250 meters from the central antenna of the T-array. Also, the frequency range will be increased to 1.2-1.7, 2.8 and 5.6 GHz. The Second phase of the BDA should be operational by the middle of 2010 and will operate in the frequency range of (1.2-1.7) GHz for solar and non solar observations. Here, we present the characteristics of the second phase of the BDA project, details of the array configuration, the u-v coverage, the synthesized beam obtained for the proposed configuration.

  11. Hanford spent nuclear fuel project recommended path forward, volume III: Alternatives and path forward evaluation supporting documentation

    International Nuclear Information System (INIS)

    Fulton, J.C.

    1994-10-01

    Volume I of the Hanford Spent Nuclear Fuel Project - Recommended Path Forward constitutes an aggressive series of projects to construct and operate systems and facilities to safely retrieve, package, transport, process, and store K Basins fuel and sludge. Volume II provided a comparative evaluation of four Alternatives for the Path Forward and an evaluation for the Recommended Path Forward. Although Volume II contained extensive appendices, six supporting documents have been compiled in Volume III to provide additional background for Volume II

  12. Classification of criticality calculations with correlation coefficient method and its application to OECD/NEA burnup credit benchmarks phase III-A and II-A

    International Nuclear Information System (INIS)

    Okuno, Hiroshi

    2003-01-01

    A method for classifying benchmark results of criticality calculations according to similarity was proposed in this paper. After formulation of the method utilizing correlation coefficients, it was applied to burnup credit criticality benchmarks Phase III-A and II-A, which were conducted by the Expert Group on Burnup Credit Criticality Safety under auspices of the Nuclear Energy Agency of the Organisation for Economic Cooperation and Development (OECD/NEA). Phase III-A benchmark was a series of criticality calculations for irradiated Boiling Water Reactor (BWR) fuel assemblies, whereas Phase II-A benchmark was a suite of criticality calculations for irradiated Pressurized Water Reactor (PWR) fuel pins. These benchmark problems and their results were summarized. The correlation coefficients were calculated and sets of benchmark calculation results were classified according to the criterion that the values of the correlation coefficients were no less than 0.15 for Phase III-A and 0.10 for Phase II-A benchmarks. When a couple of benchmark calculation results belonged to the same group, one calculation result was found predictable from the other. An example was shown for each of the Benchmarks. While the evaluated nuclear data seemed the main factor for the classification, further investigations were required for finding other factors. (author)

  13. Phase 2 Reese River Geothermal Project Slim Well 56-4 Drilling and Testing

    Energy Technology Data Exchange (ETDEWEB)

    Henkle, William R.; Ronne, Joel

    2008-06-15

    This report covers the drilling and testing of the slim well 56-4 at the Reese River Geothermal Project in Lander County, Nevada. This well was partially funded through a GRED III Cooperative Funding Agreement # DE-FC36-04GO14344, from USDOE.

  14. A phase III clinical trial of exercise modalities on treatment side-effects in men receiving therapy for prostate cancer

    International Nuclear Information System (INIS)

    Newton, Robert U; Taaffe, Dennis R; Spry, Nigel; Gardiner, Robert A; Levin, Gregory; Wall, Bradley; Joseph, David; Chambers, Suzanne K; Galvão, Daniel A

    2009-01-01

    targeting bone density, cardiovascular function, lean and fat mass, physical function and falls risk as primary study endpoints. In terms of advancement of prostate cancer care, we expect dissemination of the knowledge gained from this project to reduce fracture risk, improve physical and functional ability, quality of life and ultimately survival rate in this population. A Phase III clinical trial of exercise modalities on treatment side-effects in men receiving therapy for prostate cancer; ACTRN12609000200280

  15. CEC project Mirage - Second phase on migration of radionuclides in the geosphere

    International Nuclear Information System (INIS)

    Come, B.

    1989-01-01

    A second phase of the Community coordinated project Mirage (migration of radionuclides in the geosphere) was launched in 1986. The present report brings together reviews of work done in the four research areas of this phase for 1988, and therefore constitues an update of the previous report, ref. EUR 11589. This project is part of the CEC R and D programme on radioactive waste management (1985-89)

  16. SPSP Phase III Recruiting, Selecting, and Developing Secure Power Systems Professionals: Behavioral Interview Guidelines by Job Roles

    Energy Technology Data Exchange (ETDEWEB)

    O' Neil, Lori Ross [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Conway, T. J. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Tobey, D. H. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Greitzer, Frank L. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Dalton, Angela C. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Pusey, Portia K. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States)

    2015-03-01

    The Secure Power Systems Professional Phase III final report was released last year which an appendix of Behavioral Interview Guidelines by Job Roles. This new report is that appendix broken out as a standalone document to assist utilities in recruiting and developing Secure Power Systems Professionals at their site.

  17. Novel solid phase extraction procedure for gold(III) on Dowex M 4195 prior to its flame atomic absorption spectrometric determination

    Energy Technology Data Exchange (ETDEWEB)

    Tuzen, Mustafa [Gaziosmanpasa University, Faculty of Science and Arts, Chemistry Department, 60250 Tokat (Turkey)], E-mail: mtuzen@gop.edu.tr; Saygi, Kadriye O. [Gaziosmanpasa University, Faculty of Science and Arts, Chemistry Department, 60250 Tokat (Turkey); Soylak, Mustafa [Erciyes University, Faculty of Science and Arts, Chemistry Department, 38039 Kayseri (Turkey)

    2008-08-15

    A method for solid phase extraction (SPE) of gold(III) using Dowex M 4195 chelating resin has been developed. The optimum experimental conditions for the quantitative sorption of gold(III), pH, effect of flow rates, eluent types, sorption capacity and the effect of diverse ions on the sorption of gold(III) have been investigated. The chelating resin can be reused for more than 100 cycles of sorption-desorption without any significant change in sorption of gold(III) ions. The recovery values for gold(III) and detection limit (LOD) of gold were greater than 95% and 1.61 {mu}g L{sup -1}, respectively. The preconcentration factor was 31. The relative standard deviation of the method was <5%. The adsorption capacity of the resin was 8.1 mg g{sup -1}. The proposed method has been applied for the determination of gold(III) in some real samples including water, soil and sediment samples.

  18. ELECTRICAL SAFETY IMPROVEMENT PROJECT A COMPLEX WIDE TEAMING INITIATIVE

    Energy Technology Data Exchange (ETDEWEB)

    GRAY BJ

    2007-11-26

    This paper describes the results of a year-long project, sponsored by the Energy Facility Contractors Group (EFCOG) and designed to improve overall electrical safety performance throughout Department of Energy (DOE)-owned sites and laboratories. As evidenced by focused metrics, the Project was successful primarily due to the joint commitment of contractor and DOE electrical safety experts, as well as significant support from DOE and contractor senior management. The effort was managed by an assigned project manager, using classical project-management principles that included execution of key deliverables and regular status reports to the Project sponsor. At the conclusion of the Project, the DOE not only realized measurable improvement in the safety of their workers, but also had access to valuable resources that will enable them to do the following: evaluate and improve electrical safety programs; analyze and trend electrical safety events; increase electrical safety awareness for both electrical and non-electrical workers; and participate in ongoing processes dedicated to continued improvement.

  19. Improving the treatment of non-aqueous phase TCE in low permeability zones with permanganate

    International Nuclear Information System (INIS)

    Chokejaroenrat, Chanat; Comfort, Steve; Sakulthaew, Chainarong; Dvorak, Bruce

    2014-01-01

    Graphical abstract: - Highlights: • Transport experiments used transmissive and low permeability zones (LPZs). • 14 C-labeled TCE was used to quantify oxidation of DNAPL in LPZs by permanganate. • Stabilization aids prevented MnO 2 rind formation. • DNAPL oxidation improved when xanthan and stabilization aids were used. - Abstract: Treating dense non-aqueous phase liquids (DNAPLs) embedded in low permeability zones (LPZs) is a particularly challenging issue for injection-based remedial treatments. Our objective was to improve the sweeping efficiency of permanganate (MnO 4 − ) into LPZs to treat high concentrations of TCE. This was accomplished by conducting transport experiments that quantified the penetration of various permanganate flooding solutions into a LPZ that was spiked with non-aqueous phase 14 C-TCE. The treatments we evaluated included permanganate paired with: (i) a shear-thinning polymer (xanthan); (ii) stabilization aids that minimized MnO 2 rind formation and (iii) a phase-transfer catalyst. In addition, we quantified the ability of these flooding solutions to improve TCE destruction under batch conditions by developing miniature LPZ cylinders that were spiked with 14 C-TCE. Transport experiments showed that MnO 4 − alone was inefficient in penetrating the LPZ and reacting with non-aqueous phase TCE, due to a distinct and large MnO 2 rind that inhibited the TCE from further oxidant contact. By including xanthan with MnO 4 − , the sweeping efficiency increased (90%) but rind formation was still evident. By including the stabilization aid, sodium hexametaphosphate (SHMP) with xanthan, permanganate penetrated 100% of the LPZ, no rind was observed, and the percentage of TCE oxidized increased. Batch experiments using LPZ cylinders allowed longer contact times between the flooding solutions and the DNAPL and results showed that SHMP + MnO 4 − improved TCE destruction by ∼16% over MnO 4 − alone (56.5% vs. 40.1%). These results support

  20. EXPERIMENTAL RESULTS OF THE NEPHELINE PHASE III STUDY

    Energy Technology Data Exchange (ETDEWEB)

    Fox, K.; Edwards, T.

    2009-11-09

    This study is the third phase in a series of experiments designed to reduce conservatism in the model that predicts the formation of nepheline, a crystalline phase that can reduce the durability of high level waste glass. A Phase I study developed a series of glass compositions that were very durable while their nepheline discriminator values were well below the current nepheline discriminator limit of 0.62, where nepheline is predicted to crystallize upon slow cooling. A Phase II study selected glass compositions to identify any linear effects of composition on nepheline crystallization and that were restricted to regions that fell within the validation ranges of the Defense Waste Processing Facility (DWPF) Product Composition Control System (PCCS) models. However, it was not possible to identify any linear effects of composition on chemical durability performance for this set of study glasses. The results of the Phase II study alone were not sufficient to recommend modification of the current nepheline discriminator. It was recommended that the next series of experiments continue to focus not only on compositional regions where the PCCS models are considered applicable (i.e., the model validation ranges), but also be restricted to compositional regions where the only constraint limiting processing is the current nepheline discriminator. Two methods were used in selecting glasses for this Phase III nepheline study. The first was based on the relationship of the current nepheline discriminator model to the other DWPF PCCS models, and the second was based on theory of crystallization in mineral and glass melts. A series of 29 test glass compositions was selected for this study using a combination of the two approaches. The glasses were fabricated and characterized in the laboratory. After reviewing the data, the study glasses generally met the target compositions with little issue. Product Consistency Test results correlated well with the crystallization analyses in

  1. Improvement of Construction Project Management Processes

    Directory of Open Access Journals (Sweden)

    Nazarko, J.

    2017-07-01

    Full Text Available The common denominator of the five papers published in the current edition of the Journal of Engineering, Project, and Production Management is the improvement of construction project management processes for effective use of resources. Execution of proper project management processes is widely recognized as a key success factor influencing likelihood of project success (Alleman, 2014. It is noticeable that four out of five papers in this issue of the Journal are authored or co-authored by Iranian researchers from the same Institute but their conclusions bear importance that cannot be limited to the authors’ region.

  2. High precision capacitive beam phase probe for KHIMA project

    Energy Technology Data Exchange (ETDEWEB)

    Hwang, Ji-Gwang, E-mail: windy206@hanmail.net [Korea Institute of Radiological and Medical Sciences, 215–4, Gongneung-dong, Nowon-t, Seoul 139–706 (Korea, Republic of); Yang, Tae-Keun [Korea Institute of Radiological and Medical Sciences, 215–4, Gongneung-dong, Nowon-t, Seoul 139–706 (Korea, Republic of); Forck, Peter [GSI Helmholtz Centre for Ion Research, Darmstadt 64291, German (Germany)

    2016-11-21

    In the medium energy beam transport (MEBT) line of KHIMA project, a high precision beam phase probe monitor is required for a precise tuning of RF phase and amplitude of Radio Frequency Quadrupole (RFQ) accelerator and IH-DTL linac. It is also used for measuring a kinetic energy of ion beam by time-of-flight (TOF) method using two phase probes. The capacitive beam phase probe has been developed. The electromagnetic design of the high precision phase probe was performed to satisfy the phase resolution of 1° (@200 MHz). It was confirmed by the test result using a wire test bench. The measured phase accuracy of the fabricated phase probe is 1.19 ps. The pre-amplifier electronics with the 0.125 ∼ 1.61 GHz broad-band was designed and fabricated for amplifying the signal strength. The results of RF frequency and beam energy measurement using a proton beam from the cyclotron in KIRAMS is presented.

  3. Construction Project Performance Improvement through Radio Frequency Identification Technology Application on a Project Supply Chain

    Science.gov (United States)

    Wang, Heng

    2017-01-01

    Construction project productivity typically lags other industries and it has been the focus of numerous studies in order to improve the project performance. This research investigated the application of Radio Frequency Identification (RFID) technology on construction projects' supply chain and determined that RFID technology can improve the…

  4. Orthodontic clockwise rotation of maxillomandibular complex for improving facial profile in late teenagers with Class III malocclusion: A preliminary report

    OpenAIRE

    Eric JW Liou; Yu-Chi Wang

    2018-01-01

    Objective: Orthodontic camouflage treatments improve occlusion but might worsen facial profile in patients with Class III malocclusion. It has been reported that surgical clockwise rotation of maxillomandibular complex (MMc) improves facial profile by reducing chin prominence and chin throat length in patients with Class III malocclusion. The purpose of this report was to illustrate two orthodontic techniques for clockwise rotation of the MMc in late teenagers with Class III malocclusion and ...

  5. A clinical review of treatment outcomes in glioblastoma multiforme - the validation in a non-trial population of the results of a randomised Phase III clinical trial: has a more radical approach improved survival?

    LENUS (Irish Health Repository)

    Rock, K

    2012-01-03

    Objective: Glioblastoma multiforme (GBM) accounts for up to 60% of all malignant primary brain tumours in adults, occurring in 2-3 cases per 100 000 in Europe and North America. In 2005, a Phase III clinical trial demonstrated a significant improvement in survival over 2, and subsequently, 5 years with the addition of concurrent and adjuvant temozolomide (TMZ) to radical radiotherapy (RT) (Stupp R, Hegi M, van den Bent M, et al. Effects of radiotherapy with concomitant and adjuvant temozolomide versus radiotherapy alone on survival in glioblastoma in a randomised phase III study: 5-year analysis of the EORTC-NCIC trial. Lancet Oncol 2009:10:459-66). The aim of this study was to investigate if the demonstrated improved survival in the literature translated to clinical practice.Methods: This was a retrospective study including all patients with histologically proven GBM diagnosed from 1999 to 2008 and treated with adjuvant RT at our institution. A total of 273 patients were identified. Statistical analysis was carried out using SPSS v18.Results: The median survival for the whole group (n = 273) over the 10-year period was 7.6 months (95% confidence interval 6.7-8.4 months). Overall, the cumulative probability of survival at 1 and 2 years was 31.5 and 9.4%, respectively. In total, 146 patients received radical RT. 103 patients were treated with radical RT and TMZ and 43 patients received radical RT alone. The median survival for patients receiving radical RT with TMZ was 13.4 months (95% CI 10.9-15.8 months) vs 8.8 months for radical RT alone (95% CI 6.9 - 10.7 months, p = 0.006). 2-year survival figures were 21.2 vs 4.7%, respectively. On multivariate analysis, independent predictors of survival included KPS, RT dose, TMZ and extent of surgery. The strongest predictors of poorer outcome based on the hazard ratio were palliative RT, followed by not receiving TMZ chemotherapy, then KPS <90 and a biopsy only surgical approach.Conclusion: This paper demonstrates

  6. A clinical review of treatment outcomes in glioblastoma multiforme - the validation in a non-trial population of the results of a randomised Phase III clinical trial: has a more radical approach improved survival?

    LENUS (Irish Health Repository)

    2012-02-01

    Objective: Glioblastoma multiforme (GBM) accounts for up to 60% of all malignant primary brain tumours in adults, occurring in 2-3 cases per 100 000 in Europe and North America. In 2005, a Phase III clinical trial demonstrated a significant improvement in survival over 2, and subsequently, 5 years with the addition of concurrent and adjuvant temozolomide (TMZ) to radical radiotherapy (RT) (Stupp R, Hegi M, van den Bent M, et al. Effects of radiotherapy with concomitant and adjuvant temozolomide versus radiotherapy alone on survival in glioblastoma in a randomised phase III study: 5-year analysis of the EORTC-NCIC trial. Lancet Oncol 2009:10:459-66). The aim of this study was to investigate if the demonstrated improved survival in the literature translated to clinical practice.Methods: This was a retrospective study including all patients with histologically proven GBM diagnosed from 1999 to 2008 and treated with adjuvant RT at our institution. A total of 273 patients were identified. Statistical analysis was carried out using SPSS v18.Results: The median survival for the whole group (n = 273) over the 10-year period was 7.6 months (95% confidence interval 6.7-8.4 months). Overall, the cumulative probability of survival at 1 and 2 years was 31.5 and 9.4%, respectively. In total, 146 patients received radical RT. 103 patients were treated with radical RT and TMZ and 43 patients received radical RT alone. The median survival for patients receiving radical RT with TMZ was 13.4 months (95% CI 10.9-15.8 months) vs 8.8 months for radical RT alone (95% CI 6.9 - 10.7 months, p = 0.006). 2-year survival figures were 21.2 vs 4.7%, respectively. On multivariate analysis, independent predictors of survival included KPS, RT dose, TMZ and extent of surgery. The strongest predictors of poorer outcome based on the hazard ratio were palliative RT, followed by not receiving TMZ chemotherapy, then KPS <90 and a biopsy only surgical approach.Conclusion: This paper demonstrates improved

  7. Fringe order error in multifrequency fringe projection phase unwrapping: reason and correction.

    Science.gov (United States)

    Zhang, Chunwei; Zhao, Hong; Zhang, Lu

    2015-11-10

    A multifrequency fringe projection phase unwrapping algorithm (MFPPUA) is important to fringe projection profilometry, especially when a discontinuous object is measured. However, a fringe order error (FOE) may occur when MFPPUA is adopted. An FOE will result in error to the unwrapped phase. Although this kind of phase error does not spread, it brings error to the eventual 3D measurement results. Therefore, an FOE or its adverse influence should be obviated. In this paper, reasons for the occurrence of an FOE are theoretically analyzed and experimentally explored. Methods to correct the phase error caused by an FOE are proposed. Experimental results demonstrate that the proposed methods are valid in eliminating the adverse influence of an FOE.

  8. A quality improvement project to improve admission temperatures in very low birth weight infants.

    Science.gov (United States)

    Lee, H C; Ho, Q T; Rhine, W D

    2008-11-01

    To review the results of a quality improvement (QI) project to improve admission temperatures of very low birth weight inborn infants. The neonatal intensive care unit at Lucile Packard Children's Hospital underwent a QI project to address hypothermic preterm newborns by staff education and implementing processes such as polyethylene wraps and chemical warming mattresses. We performed retrospective chart review of all inborn infants with birth weight project. The improvement was consistent and persisted over a 15-month period. After risk adjustment, the strongest predictor of hypothermia was being born in the period before implementation of the QI project (odds ratio 8.12, 95% confidence interval 4.63, 14.22). Although cesarean delivery was a strong risk factor for hypothermia prior to the project, it was no longer significant after the project. There was no significant difference in death or intraventricular hemorrhage detected between periods. There was a significant improvement in admission temperatures after a QI project, which persisted beyond the initial implementation period. Although there was no difference in mortality or intraventricular hemorrhage rates, we did not have sufficient power to detect small differences in these outcomes.

  9. Decitabine improves progression-free survival in older high-risk MDS patients with multiple autosomal monosomies: results of a subgroup analysis of the randomized phase III study 06011 of the EORTC Leukemia Cooperative Group and German MDS Study Group.

    Science.gov (United States)

    Lübbert, Michael; Suciu, Stefan; Hagemeijer, Anne; Rüter, Björn; Platzbecker, Uwe; Giagounidis, Aristoteles; Selleslag, Dominik; Labar, Boris; Germing, Ulrich; Salih, Helmut R; Muus, Petra; Pflüger, Karl-Heinz; Schaefer, Hans-Eckart; Bogatyreva, Lioudmila; Aul, Carlo; de Witte, Theo; Ganser, Arnold; Becker, Heiko; Huls, Gerwin; van der Helm, Lieke; Vellenga, Edo; Baron, Frédéric; Marie, Jean-Pierre; Wijermans, Pierre W

    2016-01-01

    In a study of elderly AML patients treated with the hypomethylating agent decitabine (DAC), we noted a surprisingly favorable outcome in the (usually very unfavorable) subgroup with two or more autosomal monosomies (MK2+) within a complex karyotype (Lübbert et al., Haematologica 97:393-401, 2012). We now analyzed 206 myelodysplastic syndrome (MDS) patients (88 % of 233 patients randomized in the EORTC/GMDSSG phase III trial 06011, 61 of them with RAEBt, i.e. AML by WHO) with cytogenetics informative for MK status.. Endpoints are the following: complete/partial (CR/PR) and overall response rate (ORR) and progression-free (PFS) and overall survival (OS). Cytogenetic subgroups are the following: 63 cytogenetically normal (CN) patients, 143 with cytogenetic abnormalities, 73 of them MK-negative (MK-), and 70 MK-positive (MK+). These MK+ patients could be divided into 17 with a single autosomal monosomy (MK1) and 53 with at least two monosomies (MK2+). ORR with DAC in CN patients: 36.1 %, in MK- patients: 16.7 %, in MK+ patients: 43.6 % (MK1: 44.4 %, MK2+ 43.3 %). PFS was prolonged by DAC compared to best supportive care (BSC) in the CN (hazard ratio (HR) 0.55, 99 % confidence interval (CI), 0.26; 1.15, p = 0.03) and MK2+ (HR 0.50; 99 % CI, 0.23; 1.06, p = 0.016) but not in the MK-, MK+, and MK1 subgroups. OS was not improved by DAC in any subgroup. In conclusion, we demonstrate for the first time in a randomized phase III trial that high-risk MDS patients with complex karyotypes harboring two or more autosomal monosomies attain encouraging responses and have improved PFS with DAC treatment compared to BSC.

  10. Tofacitinib improves pruritus and health-related quality of life up to 52 weeks: Results from 2 randomized phase III trials in patients with moderate to severe plaque psoriasis.

    Science.gov (United States)

    Feldman, Steven R; Thaçi, Diamant; Gooderham, Melinda; Augustin, Matthias; de la Cruz, Claudia; Mallbris, Lotus; Buonanno, Marjorie; Tatulych, Svitlana; Kaur, Mandeep; Lan, Shuping; Valdez, Hernan; Mamolo, Carla

    2016-12-01

    Tofacitinib is an oral Janus kinase inhibitor that improves clinical measures of psoriasis. We sought to assess patient-reported outcomes in tofacitinib-treated patients with moderate to severe plaque psoriasis over 52 weeks. In 2 identical, phase III studies (Oral treatment for Psoriasis Trial Pivotal 1 [NCT01276639], n = 901, and Pivotal 2 [NCT01309737], n = 960), patients were randomized 2:2:1 to receive 5 or 10 mg of tofacitinib or placebo, twice daily. At week 16, placebo-treated patients were re-randomized to tofacitinib. Dermatology Life Quality Index score, Itch Severity Item score, Patient Global Assessment score, and patient satisfaction were assessed. Baseline Dermatology Life Quality Index score indicated substantial health-related quality of life impairment. At week 16, a greater proportion of patients achieved Dermatology Life Quality Index score of 1 or less (no effect of psoriasis on health-related quality of life) with tofacitinib 5 and 10 mg twice daily versus placebo (Oral treatment for Psoriasis Trial Pivotal 1/2: 26.7%/28.6% and 40.2%/48.2% vs 4.6%/6.0%, respectively; P tofacitinib doses versus placebo (P tofacitinib versus placebo (P Tofacitinib demonstrated improvement in health-related quality of life and patient-reported symptoms that persisted over 52 weeks. Copyright © 2016 American Academy of Dermatology, Inc. Published by Elsevier Inc. All rights reserved.

  11. Extraction behaviour of Am(III) and Eu(III) from nitric acid medium in TEHDGA-HDEHP impregnated resins

    Energy Technology Data Exchange (ETDEWEB)

    Saipriya, G.; Kumar, T. [Bhabha Atomic Research Centre Facilities, Kalpakkam (India). Kalpakkam Reprocessing Plant; Kumaresan, R.; Nayak, P.K.; Venkatesan, K.A.; Antony, M.P. [Indira Gandhi Center for Atomic Research, Kalpakkam (India). Fuel Chemistry Div.

    2016-07-01

    The extraction behaviour of Am(III) and Eu(III) from nitric acid medium was studied in the solvent impregnated resins containing extractants such as tetra-bis(2-ethylhexyl)diglycolamide (TEHDGA) or bis-(2-ethylhexyl)phosphoric acid (HDEHP) or mixture of TEHDGA+HDEHP. The rate of extraction of Am(III) and Eu(III) from 1 M nitric acid and the effect of various parameters, such as the concentration of nitric acid in aqueous phase and concentration of TEHDGA and HDEHP in resin phase, on the distribution coefficient of Am(III) and Eu(III) was studied. The distribution coefficient of Am(III) and Eu(III) in HDEHP-impregnated resin decreased and that in TEHDGA-impregnated resin increased, with increase in the concentration of nitric acid. However, in (TEHDGA+HDEHP) - impregnated resin, synergic extraction was observed at lower nitric acid concentration and antagonism at higher nitric acid concentration. The mechanism of Am(III) and Eu(III) extraction in the combined resin was investigated by slope analysis method. The extraction of various metal ions present in the fast reactor simulated high-level liquid waste was studied. The separation factor of Am(III) over Eu(III) was studied using citrate-buffered diethylenetriaminepentaacetic acid (DTPA) solution.

  12. Uranium Mill Tailings Remedial Action Project: Cost Reduction and Productivity Improvement Program Project Plan

    International Nuclear Information System (INIS)

    1991-11-01

    The purpose of the Cost Reduction/Productivity Improvement Program Plan is to formalize and improve upon existing efforts to control costs which have been underway since project inception. This program plan has been coordinated with the Department of Energy (DOE) Office of Environmental Management (EM) and the DOE Field Office, Albuquerque (AL). It incorporates prior Uranium Mill Tallings Remedial Action (UMTRA) Project Office guidance issued on the subject. The opportunities for reducing cosh and improving productivity are endless. The CR/PIP has these primary objectives: Improve productivity and quality; heighten the general cost consciousness of project participants, at all levels of their organizations; identify and implement specific innovative employee ideas that extend beyond what is required through existing processes and procedures; emphasize efforts that create additional value for the money spent by maintaining the project Total Estimated Cost (TEC) at the lowest possible level

  13. Improvement of the accuracy of phase observation by modification of phase-shifting electron holography

    International Nuclear Information System (INIS)

    Suzuki, Takahiro; Aizawa, Shinji; Tanigaki, Toshiaki; Ota, Keishin; Matsuda, Tsuyoshi; Tonomura, Akira

    2012-01-01

    We found that the accuracy of the phase observation in phase-shifting electron holography is strongly restricted by time variations of mean intensity and contrast of the holograms. A modified method was developed for correcting these variations. Experimental results demonstrated that the modification enabled us to acquire a large number of holograms, and as a result, the accuracy of the phase observation has been improved by a factor of 5. -- Highlights: ► A modified phase-shifting electron holography was proposed. ► The time variation of mean intensity and contrast of holograms were corrected. ► These corrections lead to a great improvement of the resultant phase accuracy. ► A phase accuracy of about 1/4000 rad was achieved from experimental results.

  14. The use of process mapping in healthcare quality improvement projects.

    Science.gov (United States)

    Antonacci, Grazia; Reed, Julie E; Lennox, Laura; Barlow, James

    2018-05-01

    Introduction Process mapping provides insight into systems and processes in which improvement interventions are introduced and is seen as useful in healthcare quality improvement projects. There is little empirical evidence on the use of process mapping in healthcare practice. This study advances understanding of the benefits and success factors of process mapping within quality improvement projects. Methods Eight quality improvement projects were purposively selected from different healthcare settings within the UK's National Health Service. Data were gathered from multiple data-sources, including interviews exploring participants' experience of using process mapping in their projects and perceptions of benefits and challenges related to its use. These were analysed using inductive analysis. Results Eight key benefits related to process mapping use were reported by participants (gathering a shared understanding of the reality; identifying improvement opportunities; engaging stakeholders in the project; defining project's objectives; monitoring project progress; learning; increased empathy; simplicity of the method) and five factors related to successful process mapping exercises (simple and appropriate visual representation, information gathered from multiple stakeholders, facilitator's experience and soft skills, basic training, iterative use of process mapping throughout the project). Conclusions Findings highlight benefits and versatility of process mapping and provide practical suggestions to improve its use in practice.

  15. Interface control document for tank waste remediation system privatization phase 1 infrastructure support Project W-519

    International Nuclear Information System (INIS)

    Parazin, R.J.

    1998-01-01

    This document describes the functional and physical interfaces between the Tank Waste Remediation System (TWRS) Privatization Phase 1 Infrastructure Project W-519 and the various other projects (i.e., Projects W-314, W-464, W-465, and W-520) supporting Phase 1 that will require the allocation of land in and about the Privatization Phase 1 Site and/or interface with the utilities extended by Project W-519. Project W-519 will identify land use allocations and upgrade/extend several utilities in the 200-East Area into the Privatization Phase 1 Site (formerly the Grout Disposal Compound) in preparation for the Privatization Contractors (PC) to construct treatment facilities. The project will upgrade/extend: Roads, Electrical Power, Raw Water (for process and fire suppression), Potable Water, and Liquid Effluent collection. The replacement of an existing Sanitary Sewage treatment system that may be displaced by Phase 1 site preparation activities may also be included

  16. Broadband microwave photonic fully tunable filter using a single heterogeneously integrated III-V/SOI-microdisk-based phase shifter.

    Science.gov (United States)

    Lloret, Juan; Morthier, Geert; Ramos, Francisco; Sales, Salvador; Van Thourhout, Dries; Spuesens, Thijs; Olivier, Nicolas; Fédéli, Jean-Marc; Capmany, José

    2012-05-07

    A broadband microwave photonic phase shifter based on a single III-V microdisk resonator heterogeneously integrated on and coupled to a nanophotonic silicon-on-insulator waveguide is reported. The phase shift tunability is accomplished by modifying the effective index through carrier injection. A comprehensive semi-analytical model aiming at predicting its behavior is formulated and confirmed by measurements. Quasi-linear and continuously tunable 2π phase shifts at radiofrequencies greater than 18 GHz are experimentally demonstrated. The phase shifter performance is also evaluated when used as a key element in tunable filtering schemes. Distortion-free and wideband filtering responses with a tuning range of ~100% over the free spectral range are obtained.

  17. All projects related to | Page 608 | IDRC - International Development ...

    International Development Research Centre (IDRC) Digital Library (Canada)

    Region: North of Sahara, South of Sahara, Benin, Ivory Coast, Mali, Senegal, Burkina Faso, Switzerland. Program: Maternal and Child Health. Total Funding: CA$ 874,011.00. Public Policy and Protection from Exclusion - Phase III. Project. In November 2001, IDRC supported the establishment of a research network on the ...

  18. RF Phase Reference Distribution System for the TESLA Technology Based Projects

    CERN Document Server

    Czuba, K; Romaniuk, R S

    2013-01-01

    Since many decades physicists have been building particle accelerators and usually new projects became more advanced, more complicated and larger than predecessors. The importance and complexity of the phase reference distribution systems used in these accelerators have grown significantly during recent years. Amongst the most advanced of currently developed accelerators are projects based on the TESLA technology. These projects require synchronization of many RF devices with accuracy reaching femtosecond levels over kilometre distances. Design of a phase reference distribution system fulfilling such requirements is a challenging scientific task. There are many interdisciplinary problems which must be solved during the system design. Many, usually negligible issues, may became very important in such system. Furthermore, the design of a distribution system on a scale required for the TESLA technology based projects is a new challenge and there is almost no literature sufficiently covering this subject. This th...

  19. Extraction and separation studies of Ga(III, In(III and Tl(III using the neutral organophosphorous extractant, Cyanex-923

    Directory of Open Access Journals (Sweden)

    P. M. DHADKE

    2003-07-01

    Full Text Available The neutral extractant, Cyanes-923 has been used for the extraction and separation of gallium(III, indium(III and thallium(III from acidic solution. These metal ions were found to be quantitatively extracted with Cyanex-923 in toluene in the pH range 4.5–5.5, 5.0–6.5 and 1.5–3.0, respectively, and from the organic phase they can be stripped with 2.0 mol dm-3 HNO3, 3.0 mol dm-3 HNO3 and 3.0 mol dm-3 HCl, respectively. The effect of pH equilibration period, diluents, diverse ions and stripping agents on the extraction of Ga(III, In(III and Tl(III has been studied. The stroichiometry of the extracted species of these metal ions was determined on the basis of the slope analysis method. The reaction proceed by solvation and the probable extracted species found were [MCl3. 3Cyanex-923] [where M = Ga(III or In(III ] and [HTlCl4. 3Cyanex-923]. Based on these results a sequential procedure for the separation of Ga(III, In(III and Tl(III from each other was developed.

  20. Direct numerical simulation of incompressible multiphase flow with phase change

    Science.gov (United States)

    Lee, Moon Soo; Riaz, Amir; Aute, Vikrant

    2017-09-01

    Simulation of multiphase flow with phase change is challenging because of the potential for unphysical pressure oscillations, spurious velocity fields and mass flux errors across the interface. The resulting numerical errors may become critical when large density contrasts are present. To address these issues, we present a new approach for multiphase flow with phase change that features, (i) a smooth distribution of sharp velocity jumps and mass flux within a narrow region surrounding the interface, (ii) improved mass flux projection from the implicit interface onto the uniform Cartesian grid and (iii) post-advection velocity correction step to ensure accurate velocity divergence in interfacial cells. These new features are implemented in combination with a sharp treatment of the jumps in pressure and temperature gradient. A series of 1-D, 2-D, axisymmetric and 3-D problems are solved to verify the improvements afforded by the new approach. Axisymmetric film boiling results are also presented, which show good qualitative agreement with heat transfer correlations as well as experimental observations of bubble shapes.

  1. 13. status report of the project HDR safety program of Kernforschungszentrum Karlsruhe. Working report 05.46/89

    International Nuclear Information System (INIS)

    Katzenmeier, G.

    1989-01-01

    The programme phase III, which extends to the end of 1991, is divided into the part projects containment behaviour in extreme accidents, long-term damage and monitoring the components in operation, behaviour of damaged components in dynamic accidents and large fires of actual materials. The main aims, state of the HDR safety programme, main points of the programme for 1990 and 8 technical reports on phase II and III are documented. There is a survey of costs. (DG) [de

  2. Cost-effectiveness of optimizing prevention in patients with coronary heart disease: the EUROASPIRE III health economics project.

    Science.gov (United States)

    De Smedt, Delphine; Kotseva, Kornelia; De Bacquer, Dirk; Wood, David; De Backer, Guy; Dallongeville, Jean; Seppo, Lehto; Pajak, Andrzej; Reiner, Zeljko; Vanuzzo, Diego; Georgiev, Borislav; Gotcheva, Nina; Annemans, Lieven

    2012-11-01

    The EUROASPIRE III survey indicated that the guidelines on cardiovascular disease prevention are poorly implemented in patients with established coronary heart disease (CHD). The purpose of this health economic project was to assess the potential clinical effectiveness and cost-effectiveness of optimizing cardiovascular prevention in eight EUROASPIRE III countries (Belgium, Bulgaria, Croatia, Finland, France, Italy, Poland, and the U.K.). METHODS AND RESULTS The individual risk for subsequent cardiovascular events was estimated, based on published Framingham equations. Based on the EUROASPIRE III data, the type of suboptimal prevention, if any, was identified for each individual, and the effects of optimized tailored prevention (smoking cessation, diet and exercise, better management of elevated blood pressure and/or LDL-cholesterol) were estimated. Costs of prevention and savings of avoided events were based on country-specific data. A willingness to pay threshold of €30,000/quality-adjusted life year (QALY) was used. The robustness of the results was validated by sensitivity analyses. Overall, the cost-effectiveness analyses for the eight countries showed mainly favourable results with an average incremental cost-effectiveness ratio (ICER) of €12,484 per QALY. Only in the minority of patients at the lowest risk for recurrent events, intensifying preventive therapy seems not cost-effective. Also, the single impact of intensified cholesterol control seems less cost-effective, possibly because their initial 2-year risk was already fairly low, hence the room for improvement is rather limited. These results underscore the societal value of optimizing prevention in most patients with established CHD, but also highlight the need for setting priorities towards patients more at risk and the need for more studies comparing intensified prevention with usual care in these patients.

  3. Radiation therapy for ocular choroidal neovascularization (phase I/II study)

    International Nuclear Information System (INIS)

    Sasai, Keisuke; Murata, Rumi; Mandai, Michiko; Takahashi, Masayo; Hiraoka, Masahiro

    1996-01-01

    /2 weeks (last 18 eyes). All eyes were irradiated with a single lateral 6 MV photon beam, angled 10 degree posteriorly to exclude the ipsilateral lens and the contralateral eye from the radiation field. The ipsilateral lens was irradiated with less than 10% of the total reference dose. The field size averaged 3.0 x 2.5 cm. Records of the 17 eyes with CNV referred to our hospital in 1993, which satisfied the eligibility criteria for this study, were retrospectively analyzed for comparison. Results: There was no significant acute morbidity. All patients were followed regularly by both ophthalmologists and radiation oncologists. One patient treated with a dose of 20 Gy died due to intercurrent disease 2 months after irradiation. Median follow up periods for the group of patients receiving 10 Gy and for the group of patients receiving 20 Gy were 18 months, and 9 months, respectively. One patient who received 20 Gy complained of transient dry-eye sensation 2 months after treatment, but this disappeared spontaneously at the 4th month. Subjective symptoms, visual acuity and size of the neovascular membrane were evaluated 6 months after treatment in each group. In the group of patients irradiated with 10 Gy, subjective symptoms improved in 3 eyes, did not change in 10, and deteriorated in 5. In the 20 Gy group, 8 improved, 5 did not change, and 4 deteriorated. Although visual acuity was significantly decreased in the control group, patients of both irradiated groups did not show such a decrease in visual acuity. The size of the neovascular membrane in the control group progressed significantly. However, patients in the 20 Gy group showed significant regression of the membrane, although the 10 Gy group showed no significant change in size. Conclusions: This phase I/II study including a dose escalation study showed that radiation therapy seems to be useful for CNV. The dose of 20 Gy in 10 fractions was more useful in treating neovascular membranes than the dose of 10 Gy in 5

  4. Phase II/III multicentre randomised controlled trial evaluating a strategy of primary surgery and adjuvant chemotherapy versus peri-operative chemotherapy for resectable gastric signet ring cell adenocarcinomas – PRODIGE 19 – FFCD1103 – ADCI002

    International Nuclear Information System (INIS)

    Piessen, Guillaume; Mariette, Christophe; Messager, Mathieu; Le Malicot, Karine; Robb, William B; Di Fiore, Frédéric; Guilbert, Marie; Moreau, Marie; Christophe, Véronique; Adenis, Antoine

    2013-01-01

    A dramatic increase in the incidence of the diffuse form of gastric adenocarcinomas and particularly signet ring cell carcinomas has been observed in Western countries. Evidence is accruing that signet ring cell carcinomas may have inherent chemo resistance leaving many clinicians unsure of the benefits of delaying surgery to pursue a neoadjuvant approach. PRODIGE-19-FFCD1103-ADCI002 is a prospective multicentre controlled randomised phase II/III trial comparing current standard of care of perioperative chemotherapy (2x3 cycles of Epirubicin, cisplatin, 5-fluorouracil) with a strategy of primary surgery followed by adjuvant chemotherapy (6 cycles of Epirubicin, cisplatin, 5-fluorouracil) in patients with a stage IB-III gastric signet ring cell tumour. The principal objective of the phase II study (84 patients) is to determine if the experimental arm (primary surgery followed by adjuvant chemotherapy) has sufficient interest in terms of percentage of living patients at 24 months to be evaluated in a phase III trial. If 7 or less patients in the experimental arm are alive at 24 months, phase III will not be initiated. The primary objective of phase III (230 additional patients) is to demonstrate superiority of the experimental arm in terms of overall survival. Secondary endpoints include overall survival at 36 months, disease free survival at 24 and 36 months, R0 resection rates, treatment tolerance, postoperative mortality and morbidity evaluated by Clavien-Dindo severity index, the prognostic impact of positive peritoneal cytology and the assessment of quality of life. An ancillary study will assess the emotional and cognitive impact of surgery and perioperative chemotherapy for both the patient and their partner. As inherent chemo resistance of signet ring cell tumours and delay in definitive surgery may favour tumour progression we hypothesise that a policy of primary surgery followed by adjuvant chemotherapy will improve overall survival compared to a standard

  5. Statement on current progress of the EPR project. Basic Design phase concluded

    International Nuclear Information System (INIS)

    Lamprecht, F.

    1997-01-01

    Against the background of expected increasing demand for electric power worldwide it is obvious that any existing technology for electricity generation will be required in the future to meet the demand, just as well as technology improvements. Nuclear industry's answer to this challenge are activities for further evolution of the PWR concept as a joint venture of France and Germany for development of the European Pressurized Water Reactor (EPR). The project participants are reactor manufacturers and operators of both countries as well as organisations responsible for reactor safety. The Basic Design phase which started in 1995, after prior definition of the common safety philosophy, has recently been concluded. The results have been presented at a meeting in October 1997 in Cologne, organised by KTG and SFEN, the countries' respective nuclear societies. The broad statement is that project work was successful in achieving two major objectives: A well-balanced safety concept, and a competitive design. (orig./CB) [de

  6. Phase III trial of high- vs. low-dose-rate interstitial radiotherapy for early mobile tongue cancer

    International Nuclear Information System (INIS)

    Inoue, Takehiro; Inoue, Toshihiko; Yoshida, Ken; Yoshioka, Yasuo; Shimamoto, Shigetoshi; Tanaka, Eiichi; Yamazaki, Hideya; Shimizutani, Kimishige; Teshima, Teruki; Furukawa, Souhei

    2001-01-01

    Purpose: Early mobile tongue cancer can be controlled with interstitial radiotherapy (ISRT). We carried out a Phase III trial to compare the treatment results of low-dose-rate (Ld) ISRT and high-dose-rate (HDR) ISRT for early mobile tongue cancer. Methods and Materials: From April 1992 through October 1996, 59 patients with cancer of the early mobile tongue were registered in this Phase III study. Eight patients were excluded from the evaluation because of violations of the requirements for this study. Of 51 eligible patients, 26 patients were treated with LDR-ISRT (70 Gy/4-9 days) and 25 patients with HDR-ISRT (60 Gy/10 fractions/1 week). For the hyperfractionated HDR-ISRT, the time interval between 2 fractions was more than 6 h. Results: Five-year local control rates of the LDR and HDR groups were 84% and 87% respectively. Nodal metastasis occurred in 6 patients in each group. Five-year nodal control rates of the LDR and HDR groups were 77% and 76%, respectively. Conclusion: Hyperfractionated HDR-ISRT for early mobile tongue cancer has the same local control compared with continuous LDR-ISRT. Hyperfractionated HDR-ISRT is an alternative treatment for continuous LDR-ISRT

  7. [Strategies for improving care of oncologic patients: SHARE Project results].

    Science.gov (United States)

    Reñones Crego, María de la Concepción; Fernández Pérez, Dolores; Vena Fernández, Carmen; Zamudio Sánchez, Antonio

    2016-01-01

    Cancer treatment is a major burden for the patient and its family that requires an individualized management by healthcare professionals. Nurses are in charge of coordinating care and are the closest healthcare professionals to patient and family; however, in Spain, there are not standard protocols yet for the management of oncology patients. The Spanish Oncology Nursing Society developed between 2012 and 2014 the SHARE project, with the aim of establishing strategies to improve quality of life and nursing care in oncology patients. It was developed in 3 phases. First, a literature search and review was performed to identify nursing strategies, interventions and tools to improve cancer patients' care. At the second stage, these interventions were agreed within a group of oncology nursing experts; and at the third phase, a different group of experts in oncology care categorized the interventions to identify the ones with highest priority and most feasible to be implemented. As a result, 3 strategic actions were identified to improve nursing care during cancer treatment: To provide a named nurse to carry out the follow up process by attending to the clinic or telephonic consultation, develop therapeutic education with adapted protocols for each tumor type and treatment and ensure specific training for nurses on the management of the cancer patients. Strategic actions proposed in this paper aim to improve cancer patients' healthcare and quality of life through the development of advanced nursing roles based on a higher level of autonomy, situating nurses as care coordinators to assure an holistic care in oncology patients. Copyright © 2016 Elsevier España, S.L.U. All rights reserved.

  8. A portfolio evaluation framework for air transportation improvement projects

    Science.gov (United States)

    Baik, Hyeoncheol

    This thesis explores the application of portfolio theory to the Air Transportation System (ATS) improvement. The ATS relies on complexly related resources and different stakeholder groups. Moreover, demand for air travel is significantly increasing relative to capacity of air transportation. In this environment, improving the ATS is challenging. Many projects, which are defined as technologies or initiatives, for improvement have been proposed and some have been demonstrated in practice. However, there is no clear understanding of how well these projects work in different conditions nor of how they interact with each other or with existing systems. These limitations make it difficult to develop good project combinations, or portfolios that maximize improvement. To help address this gap, a framework for identifying good portfolios is proposed. The framework can be applied to individual projects or portfolios of projects. Projects or portfolios are evaluated using four different groups of factors (effectiveness, time-to-implement, scope of applicability, and stakeholder impacts). Portfolios are also evaluated in terms of interaction-determining factors (prerequisites, co-requisites, limiting factors, and amplifying factors) because, while a given project might work well in isolation, interdependencies between projects or with existing systems could result in lower overall performance in combination. Ways to communicate a portfolio to decision makers are also introduced. The framework is unique because (1) it allows using a variety of available data, and (2) it covers diverse benefit metrics. For demonstrating the framework, an application to ground delay management projects serves as a case study. The portfolio evaluation approach introduced in this thesis can aid decision makers and researchers at universities and aviation agencies such as Federal Aviation Administration (FAA), National Aeronautics and Space Administration (NASA), and Department of Defense (DoD), in

  9. Improvement of the accuracy of phase observation by modification of phase-shifting electron holography

    Energy Technology Data Exchange (ETDEWEB)

    Suzuki, Takahiro; Aizawa, Shinji; Tanigaki, Toshiaki [Advanced Science Institute, RIKEN, Hirosawa 2-1, Wako, Saitama 351-0198 (Japan); Ota, Keishin, E-mail: ota@microphase.co.jp [Microphase Co., Ltd., Onigakubo 1147-9, Tsukuba, Ibaragi 300-2651 (Japan); Matsuda, Tsuyoshi [Japan Science and Technology Agency, Kawaguchi-shi, Saitama 332-0012 (Japan); Tonomura, Akira [Advanced Science Institute, RIKEN, Hirosawa 2-1, Wako, Saitama 351-0198 (Japan); Okinawa Institute of Science and Technology, Graduate University, Kunigami, Okinawa 904-0495 (Japan); Central Research Laboratory, Hitachi, Ltd., Hatoyama, Saitama 350-0395 (Japan)

    2012-07-15

    We found that the accuracy of the phase observation in phase-shifting electron holography is strongly restricted by time variations of mean intensity and contrast of the holograms. A modified method was developed for correcting these variations. Experimental results demonstrated that the modification enabled us to acquire a large number of holograms, and as a result, the accuracy of the phase observation has been improved by a factor of 5. -- Highlights: Black-Right-Pointing-Pointer A modified phase-shifting electron holography was proposed. Black-Right-Pointing-Pointer The time variation of mean intensity and contrast of holograms were corrected. Black-Right-Pointing-Pointer These corrections lead to a great improvement of the resultant phase accuracy. Black-Right-Pointing-Pointer A phase accuracy of about 1/4000 rad was achieved from experimental results.

  10. Status report EFF and EAF projects

    International Nuclear Information System (INIS)

    Gruppelaar, H.; Kopecky, J.

    1990-08-01

    The European Fusion File (EFF) project and the associated European Activation File Project (EAF) are sponsored by the European Community's Fusion Technology Programme. The 1st programme is directed to the short-term needs of the NET team, which designs the Next European Torus, while the 2nd program is directed to long-term needs in the development of a Fusion Demonstration Reactor, in particular in connection with the study of low-activation materials. Various European laboratories participate in this project. The programme of the EFF-project is in its 2nd phase, after the successful completion of the EFF-1 data file. The emphasis on the 1st phase was on the improvement of the tritium breeding and neutron multiplication cross sections, while the 2nd phase emphasizes the improvement of a shielding data base. The progress of this 2nd phase is described. (author). 1 tab

  11. Predicting hypothetical willingness to participate (WTP) in a future phase III HIV vaccine trial among high-risk adolescents.

    Science.gov (United States)

    Giocos, Georgina; Kagee, Ashraf; Swartz, Leslie

    2008-11-01

    The present study sought to determine whether the Theory of Planned Behaviour predicted stated hypothetical willingness to participate (WTP) in future Phase III HIV vaccine trials among South African adolescents. Hierarchical logistic regression analyses showed that The Theory of Planned Behaviour (TPB) significantly predicted WTP. Of all the predictors, Subjective norms significantly predicted WTP (OR = 1.19, 95% C.I. = 1.06-1.34). A stepwise logistic regression analysis revealed that Subjective Norms (OR = 1.19, 95% C.I. = 1.07-1.34) and Attitude towards participation in an HIV vaccine trial (OR = 1.32, 95% C.I. = 1.00-1.74) were significant predictors of WTP. The addition of Knowledge of HIV vaccines and HIV vaccine trials, Perceived self-risk of HIV infection, Health-promoting behaviours and Attitudes towards HIV/AIDS yielded non-significant results. These findings provide support for the Theory of Reasoned Action (TRA) and suggest that psychosocial factors may play an important role in WTP in Phase III HIV vaccine trials among adolescents.

  12. Phase-based Planning for Railway Infrastructure Projects

    DEFF Research Database (Denmark)

    Li, Rui

    2017-01-01

    is important in terms of economy and rail operations. This study presents two types of Phase-based Decision Support System (PDSS), i.e. Functional Phase-Based Planning Approach (F-PBPA) and Process-Oriented Phase-Based Planning Approach (PO-PBPA). They are used for decision support for the planning...... of the railway infrastructure maintenance activities at the strategic planning level. The objective is to achieve better economy, as well as improve cost efficiency. F-PBPA consists of ve main phases: Data Collection, Technical Optimization (TeO), Economic Optimization (EcO), Constrained Optimization (Co...... the costs. Finally, constrained optimization (CoO) includes additional constraints and it allows the railway expert to adjust input parameters, thereby to obtain alternative maintenance plans. PO-PBPA contains another systematic phase based process. With a focus on Life Cycle Cost (LCC), PO-PBPA can guide...

  13. State partnership in environmental health and safety phase of Plowshare projects

    Energy Technology Data Exchange (ETDEWEB)

    Kinsman, S [California State Department of Public Health, Berkeley, CA (United States)

    1969-07-01

    When experiments on projects involving Plowshare devices are conceived, the state chosen for the project should be invited to participate in planning the health and safety aspects and be prepared to actively participate in the D-Day phase as well as the post-detonation activity. In California nuclear science technology and competence have preceded the social acceptance and use of nuclear devices for large scale Plowshare projects. However, the environmental surveillance program of the Bureau of Radiological Health in the State Department of Public Health has established an operative program which will be ready and able to function as an active participant or in a support role in environmental health phases of nuclear projects scheduled in the State. A description of our present program will be included in this paper. This will enable the attendees and readers to realize capabilities which will be activated for participation and/or support roles during Plowshare activities in the State or in a neighboring state if the need arises. (author)

  14. State partnership in environmental health and safety phase of Plowshare projects

    International Nuclear Information System (INIS)

    Kinsman, S.

    1969-01-01

    When experiments on projects involving Plowshare devices are conceived, the state chosen for the project should be invited to participate in planning the health and safety aspects and be prepared to actively participate in the D-Day phase as well as the post-detonation activity. In California nuclear science technology and competence have preceded the social acceptance and use of nuclear devices for large scale Plowshare projects. However, the environmental surveillance program of the Bureau of Radiological Health in the State Department of Public Health has established an operative program which will be ready and able to function as an active participant or in a support role in environmental health phases of nuclear projects scheduled in the State. A description of our present program will be included in this paper. This will enable the attendees and readers to realize capabilities which will be activated for participation and/or support roles during Plowshare activities in the State or in a neighboring state if the need arises. (author)

  15. Self-reliance and innovation of Qinshan phase II NPP project

    International Nuclear Information System (INIS)

    Ye Qizhen; Yang Lanhe

    2007-01-01

    This article mainly describes the self-reliance and innovation of Qinshan nuclear power project of phase II, in-between it contains new reactor core design, as well as related experimental and calculation analysis, especially for new reactor design produced fluid-induced vibration model test, theoretical analysis and testing in-built reactor; aiming at two-loop NSSS a series improvement made for safety systems and related safety analysis to enhance their reliability and redundancy; according to specialty of two-loop NSSS an optimization made for NPP parameters and design of related equipments, for the purpose to make the output of NPP maximal; design of main reactor building and T-G building also improved according to characteristics of two-loop NSSS and site conditions. CRDM and refueling machine are researched and manufactured on base of self-reliance, their performance are better than design requirements, large portion of key equipments are localized through different way. In construction first time realized the integrated erection of containment dome. During the commissioning non-nuclear steam driving of T-G set, as well as 500 kV high voltage rising using emergent diesel generator, etc. are carried out.In period of operation still continuous innovation and improvement are made, so that to keep the good record of operation. (authors)

  16. Performance Evaluation and Parameter Identification on DROID III

    Science.gov (United States)

    Plumb, Julianna J.

    2011-01-01

    The DROID III project consisted of two main parts. The former, performance evaluation, focused on the performance characteristics of the aircraft such as lift to drag ratio, thrust required for level flight, and rate of climb. The latter, parameter identification, focused on finding the aerodynamic coefficients for the aircraft using a system that creates a mathematical model to match the flight data of doublet maneuvers and the aircraft s response. Both portions of the project called for flight testing and that data is now available on account of this project. The conclusion of the project is that the performance evaluation data is well-within desired standards but could be improved with a thrust model, and that parameter identification is still in need of more data processing but seems to produce reasonable results thus far.

  17. Improving Quality of Seal Leak Test Product using Six Sigma

    Science.gov (United States)

    Luthfi Malik, Abdullah; Akbar, Muhammad; Irianto, Dradjad

    2016-02-01

    Seal leak test part is a polyurethane material-based product. Based on past data, defect level of this product was 8%, higher than the target of 5%. Quality improvement effort was done using six sigma method that included phases of define, measure, analyse, improve, and control. In the design phase, a Delphi method was used to identify factors that were critical to quality. In the measure phase, stability and process capability was measured. Fault tree analysis (FTA) and failure mode and effect analysis (FMEA) were used in the next phase to analize the root cause and to determine the priority issues. Improve phase was done by compiling, selecting, and designing alternative repair. Some improvement efforts were identified, i.e. (i) making a checklist for maintenance schedules, (ii) making written reminder form, (iii) modifying the SOP more detail, and (iv) performing a major service to the vacuum machine. To ensure the continuity of improvement efforts, some control activities were executed, i.e. (i) controlling, monitoring, documenting, and setting target frequently, (ii) implementing reward and punishment system, (iii) adding cleaning tool, and (iv) building six sigma organizational structure.

  18. Improving Quality of Seal Leak Test Product using Six Sigma

    International Nuclear Information System (INIS)

    Malik, Abdullah Luthfi; Akbar, Muhammad; Irianto, Dradjad

    2016-01-01

    Seal leak test part is a polyurethane material-based product. Based on past data, defect level of this product was 8%, higher than the target of 5%. Quality improvement effort was done using six sigma method that included phases of define, measure, analyse, improve, and control. In the design phase, a Delphi method was used to identify factors that were critical to quality. In the measure phase, stability and process capability was measured. Fault tree analysis (FTA) and failure mode and effect analysis (FMEA) were used in the next phase to analize the root cause and to determine the priority issues. Improve phase was done by compiling, selecting, and designing alternative repair. Some improvement efforts were identified, i.e. (i) making a checklist for maintenance schedules, (ii) making written reminder form, (iii) modifying the SOP more detail, and (iv) performing a major service to the vacuum machine. To ensure the continuity of improvement efforts, some control activities were executed, i.e. (i) controlling, monitoring, documenting, and setting target frequently, (ii) implementing reward and punishment system, (iii) adding cleaning tool, and (iv) building six sigma organizational structure. (paper)

  19. Project inspection using mobile technology - phase II : assessing the impacts of mobile technology on project inspection.

    Science.gov (United States)

    2015-01-01

    As mobile technology becomes widely available and affordable, transportation agencies can use this : technology to streamline operations involved within project inspection. This research, conducted in two : phases, identified opportunities for proces...

  20. CQI project improves discharge process.

    Science.gov (United States)

    1998-08-01

    At Gibson Rehab Center in Williamsport, PA, a continuous quality improvement project to bolster the institution's discharge planning process has resulted in increased satisfaction and an award for quality. The 15-month project was spearheaded by a multidisciplinary team charged with identifying areas that had a significant impact on customer service and suggesting better ways of delivering that service. Among the changes the group suggested were establishing a weekly discharge planning group for new neuro patients, assigning a discharge coordinator for each treatment team, and creating an interdisciplinary communication sheet for the home health therapy staff.

  1. Approaching the Practice Quality Improvement Project in Interventional Radiology.

    Science.gov (United States)

    Reis, Stephen P; White, Benjamin; Sutphin, Patrick D; Pillai, Anil K; Kalva, Sanjeeva P; Toomay, Seth M

    2015-12-01

    An important component of maintenance of certification and quality improvement in radiology is the practice quality improvement (PQI) project. In this article, the authors describe several methodologies for initiating and completing PQI projects. Furthermore, the authors illustrate several tools that are vital in compiling, analyzing, and presenting data in an easily understandable and reproducible manner. Last, they describe two PQI projects performed in an interventional radiology division that have successfully improved the quality of care for patients. Using the DMAIC (define, measure, analyze, improve, control) quality improvement framework, interventional radiology throughput has been increased, to lessen mediport wait times from 43 to 8 days, and mediport infection rates have decreased from more than 2% to less than 0.4%. Copyright © 2015 American College of Radiology. Published by Elsevier Inc. All rights reserved.

  2. Code of Conduct for wind-power projects - Phases 1 and 2

    International Nuclear Information System (INIS)

    Strub, P.; Ziegler, Ch.

    2008-08-01

    This paper discusses the results of the first two phases of a project concerning wind-power projects. The paper deals with the results of a system analysis, takes a look at lessons learned and presents an appraisal of existing instruments. A system-analysis of wind-power projects is presented with emphasis on social factors and the role of stakeholders. The success factors concerning social acceptance of wind-power projects and their special characteristics are discussed. Lessons learned are examined. Instruments for the sustainable implementation of projects are looked at, in particular with a focus on social acceptance

  3. Japanese contributions to IAEA INTOR workshop, phase two A, part 2, chapter III: impurity control (engineering)

    International Nuclear Information System (INIS)

    Seki, Masahiro; Miki, Nobuharu; Shibutani, Yoji; Fujimura, Kaoru; Adachi, Jun-ichi; Sato, Kosuke; Fujii, Masaharu; Yamazaki, Seiichiro; Itoh, Shin-ichi.

    1985-07-01

    This report corresponds to the second half of Chapter III of Japanese contribution report to IAEA INTOR Workshop, Phase Two A, Part 2. Data base assessment are made on candidate materials for the divertor, limiter, and the first wall. Engineering trade-off studies are made for the high-recycling and low temperature conditions. The studies include material considerations, configuration, thermohydraulic and stress analysis, disruption, lifetime analysis, and tritium permeation. (author)

  4. Individualized In-Service Teacher Education. (Project IN-STEP). Evaluation Report, Phase II.

    Science.gov (United States)

    Thurber, John C.

    Phase 2 of Project IN-STEP was conducted to revise, refine, and conduct further field testing of a new inservice teacher education model. The method developed (in Phase 1--see ED 003 905 for report) is an individualized, multi-media approach. Revision activities, based on feedback provided for Phase 1, include the remaking of six videotape…

  5. Image/patient registration from (partial) projection data by the Fourier phase matching method

    International Nuclear Information System (INIS)

    Weiguo Lu; You, J.

    1999-01-01

    A technique for 2D or 3D image/patient registration, PFPM (projection based Fourier phase matching method), is proposed. This technique provides image/patient registration directly from sequential tomographic projection data. The method can also deal with image files by generating 2D Radon transforms slice by slice. The registration in projection space is done by calculating a Fourier invariant (FI) descriptor for each one-dimensional projection datum, and then registering the FI descriptor by the Fourier phase matching (FPM) method. The algorithm has been tested on both synthetic and experimental data. When dealing with translated, rotated and uniformly scaled 2D image registration, the performance of the PFPM method is comparable to that of the IFPM (image based Fourier phase matching) method in robustness, efficiency, insensitivity to the offset between images, and registration time. The advantages of the former are that subpixel resolution is feasible, and it is more insensitive to image noise due to the averaging effect of the projection acquisition. Furthermore, the PFPM method offers the ability to generalize to 3D image/patient registration and to register partial projection data. By applying patient registration directly from tomographic projection data, image reconstruction is not needed in the therapy set-up verification, thus reducing computational time and artefacts. In addition, real time registration is feasible. Registration from partial projection data meets the geometry and dose requirements in many application cases and makes dynamic set-up verification possible in tomotherapy. (author)

  6. Phase retrieval with the reverse projection method in the presence of object's scattering

    International Nuclear Information System (INIS)

    Wang, Zhili; Gao, Kun; Wang, Dajiang

    2017-01-01

    X-ray grating interferometry can provide substantially increased contrast over traditional attenuation-based techniques in biomedical applications, and therefore novel and complementary information. Recently, special attention has been paid to quantitative phase retrieval in X-ray grating interferometry, which is mandatory to perform phase tomography, to achieve material identification, etc. An innovative approach, dubbed “Reverse Projection” (RP), has been developed for quantitative phase retrieval. The RP method abandons grating scanning completely, and is thus advantageous in terms of higher efficiency and reduced radiation damage. Therefore, it is expected that this novel method would find its potential in preclinical and clinical implementations. Strictly speaking, the reverse projection method is applicable for objects exhibiting only absorption and refraction. In this contribution, we discuss the phase retrieval with the reverse projection method for general objects with absorption, refraction and scattering simultaneously. Especially, we investigate the influence of the object's scattering on the retrieved refraction signal. Both theoretical analysis and numerical experiments are performed. The results show that the retrieved refraction signal is the product of object's refraction and scattering signals for small values. In the case of a strong scattering, the reverse projection method cannot provide reliable phase retrieval. Those presented results will guide the use of the reverse projection method for future practical applications, and help to explain some possible artifacts in the retrieved images and/or reconstructed slices. - Highlights: • Accurate phase retrieval by the reverse projection method without object's scattering. • Retrieved refraction signal contaminated by the object's scattering. • Refraction signal underestimated by the reverse projection method. • Guide the use of the reverse projection method for

  7. Alteration of Occlusal Plane in Orthognathic Surgery: Clinical Features to Help Treatment Planning on Class III Patients

    Directory of Open Access Journals (Sweden)

    Daniel Amaral Alves Marlière

    2018-01-01

    Full Text Available Dentofacial deformities (DFD presenting mainly as Class III malocclusions that require orthognathic surgery as a part of definitive treatment. Class III patients can have obvious signs such as increasing the chin projection and chin throat length, nasolabial folds, reverse overjet, and lack of upper lip support. However, Class III patients can present different facial patterns depending on the angulation of occlusal plane (OP, and only bite correction does not always lead to the improvement of the facial esthetic. We described two Class III patients with different clinical features and inclination of OP and had undergone different treatment planning based on 6 clinical features: (I facial type; (II upper incisor display at rest; (III dental and gingival display on smile; (IV soft tissue support; (V chin projection; and (VI lower lip projection. These patients were submitted to orthognathic surgery with different treatment plannings: a clockwise rotation and counterclockwise rotation of OP according to their facial features. The clinical features and OP inclination helped to define treatment planning by clockwise and counterclockwise rotations of the maxillomandibular complex, and two patients undergone to bimaxillary orthognathic surgery showed harmonic outcomes and stables after 2 years of follow-up.

  8. Improving the treatment of non-aqueous phase TCE in low permeability zones with permanganate

    Energy Technology Data Exchange (ETDEWEB)

    Chokejaroenrat, Chanat, E-mail: chanat@sut.ac.th [Department of Civil Engineering, University of Nebraska, Lincoln, NE 68588-0531 (United States); School of Environmental Engineering, Institute of Engineering, Suranaree University of Technology, Nakhon Ratchasima 30000 (Thailand); Comfort, Steve, E-mail: scomfort1@unl.edu [School of Natural Resources, University of Nebraska, Lincoln, NE 68583-0915 (United States); Sakulthaew, Chainarong, E-mail: cvtcns@ku.ac.th [School of Natural Resources, University of Nebraska, Lincoln, NE 68583-0915 (United States); Department of Veterinary Technology, Kasetsart University, Bangkok 10900 (Thailand); Dvorak, Bruce, E-mail: bdvorak1@unl.edu [Department of Civil Engineering, University of Nebraska, Lincoln, NE 68588-0531 (United States)

    2014-03-01

    Graphical abstract: - Highlights: • Transport experiments used transmissive and low permeability zones (LPZs). • {sup 14}C-labeled TCE was used to quantify oxidation of DNAPL in LPZs by permanganate. • Stabilization aids prevented MnO{sub 2} rind formation. • DNAPL oxidation improved when xanthan and stabilization aids were used. - Abstract: Treating dense non-aqueous phase liquids (DNAPLs) embedded in low permeability zones (LPZs) is a particularly challenging issue for injection-based remedial treatments. Our objective was to improve the sweeping efficiency of permanganate (MnO{sub 4}{sup −}) into LPZs to treat high concentrations of TCE. This was accomplished by conducting transport experiments that quantified the penetration of various permanganate flooding solutions into a LPZ that was spiked with non-aqueous phase {sup 14}C-TCE. The treatments we evaluated included permanganate paired with: (i) a shear-thinning polymer (xanthan); (ii) stabilization aids that minimized MnO{sub 2} rind formation and (iii) a phase-transfer catalyst. In addition, we quantified the ability of these flooding solutions to improve TCE destruction under batch conditions by developing miniature LPZ cylinders that were spiked with {sup 14}C-TCE. Transport experiments showed that MnO{sub 4}{sup −} alone was inefficient in penetrating the LPZ and reacting with non-aqueous phase TCE, due to a distinct and large MnO{sub 2} rind that inhibited the TCE from further oxidant contact. By including xanthan with MnO{sub 4}{sup −}, the sweeping efficiency increased (90%) but rind formation was still evident. By including the stabilization aid, sodium hexametaphosphate (SHMP) with xanthan, permanganate penetrated 100% of the LPZ, no rind was observed, and the percentage of TCE oxidized increased. Batch experiments using LPZ cylinders allowed longer contact times between the flooding solutions and the DNAPL and results showed that SHMP + MnO{sub 4}{sup −} improved TCE destruction by

  9. Final Technical Report. Project Boeing SGS

    Energy Technology Data Exchange (ETDEWEB)

    Bell, Thomas E. [The Boeing Company, Seattle, WA (United States)

    2014-12-31

    Boeing and its partner, PJM Interconnection, teamed to bring advanced “defense-grade” technologies for cyber security to the US regional power grid through demonstration in PJM’s energy management environment. Under this cooperative project with the Department of Energy, Boeing and PJM have developed and demonstrated a host of technologies specifically tailored to the needs of PJM and the electric sector as a whole. The team has demonstrated to the energy industry a combination of processes, techniques and technologies that have been successfully implemented in the commercial, defense, and intelligence communities to identify, mitigate and continuously monitor the cyber security of critical systems. Guided by the results of a Cyber Security Risk-Based Assessment completed in Phase I, the Boeing-PJM team has completed multiple iterations through the Phase II Development and Phase III Deployment phases. Multiple cyber security solutions have been completed across a variety of controls including: Application Security, Enhanced Malware Detection, Security Incident and Event Management (SIEM) Optimization, Continuous Vulnerability Monitoring, SCADA Monitoring/Intrusion Detection, Operational Resiliency, Cyber Range simulations and hands on cyber security personnel training. All of the developed and demonstrated solutions are suitable for replication across the electric sector and/or the energy sector as a whole. Benefits identified include; Improved malware and intrusion detection capability on critical SCADA networks including behavioral-based alerts resulting in improved zero-day threat protection; Improved Security Incident and Event Management system resulting in better threat visibility, thus increasing the likelihood of detecting a serious event; Improved malware detection and zero-day threat response capability; Improved ability to systematically evaluate and secure in house and vendor sourced software applications; Improved ability to continuously monitor

  10. All projects related to | Page 494 | IDRC - International Development ...

    International Development Research Centre (IDRC) Digital Library (Canada)

    Gender and Generational Analysis of Armed Conflict, Peace and Justice Processes (Sudan and Uganda)- Phase III ... Program: Agriculture and Food Security ... and allocate resources more efficiently, thereby improving health service delivery.

  11. SAFOD Phase III Core Sampling and Data Management at the Gulf Coast Repository

    Directory of Open Access Journals (Sweden)

    David Lockner

    2011-03-01

    Full Text Available The San Andreas Fault Observatory at Depth (SAFODproject is yielding new insight into the San Andreas Fault (Zoback et al., 2010; Zoback et al., this issue. SAFOD drilling started in 2002 with a pilot hole, and proceeded with three phrases of drilling and coring during the summers of 2004, 2005, and 2007 (Fig. 1. One key component of theproject is curation, sampling, and documentation of SAFOD core usage at the Integrated Ocean Drilling Program’s (IODP Gulf Coast Repository (GCR at Texas A&M University. We present here the milestones accomplished over the past two years of sampling Phase III core at the GCR.

  12. Collection of URL measurement data in 2006 at the Horonobe Underground Research Laboratory project

    International Nuclear Information System (INIS)

    Kumagai, Yasuhito; Funaki, Hironori; Yamasaki, Masanao; Yamaguchi, Takehiro; Sanada, Hiroyuki; Abe, Hironobu; Orukawa, Go

    2008-07-01

    The Horonobe Underground Research Laboratory (URL) Project is being pursued by the Japan Atomic Energy Agency (JAEA) to enhance the reliability of relevant disposal technologies through investigations of the deep geological environment within the host sedimentary formations at Horonobe, northern Hokkaido. The project consists two major research area, Geoscientific Research' and 'R and D on Geological Disposal', and proceeds in three overlapping phases, 'Phase I: Surface-based investigation', 'Phase II: Construction' and 'Phase III: Operation', over a period of 20 years. The Phase I geoscientific research was carried out from March 2001 to March 2005 in parallel with design and execution scheme on URL facilities. In addition, identifying key issues that need to be addressed in the Phase II/III investigations was carried out. At the inception of the Phase II investigations, an investigation report titled 'Measurement Plan and Observational Construction Program on Shaft Excavation at the Horonobe Underground Research Laboratory Project' (hereinafter referred to as Observational Construction Program') was published. The Observational Construction Program summarizes followings lessons learnt from the Phase I investigations: measurements for safety/reasonable construction, measurements for R and D on enhancement of shaft design/construction technology, and measurements for verification of the deep geological environment estimated before shaft excavation. This report summarizes the measurements data acquired at the Ventilation Shaft (to approx. 50m depth) and the East Shaft (to approx. 40m depth) in 2006 based on the Observational Construction Program. CD-ROM and DVD-ROM are attached as an appendix. (J.P.N.)

  13. TH-E-17A-05: Optimizing Four Dimensional Cone Beam Computed Tomography Projection Allocation to Respiratory Bins

    International Nuclear Information System (INIS)

    OBrien, R; Shieh, C; Kipritidis, J; Keall, P

    2014-01-01

    Purpose: Four dimensional cone beam computed tomography (4DCBCT) is an emerging image guidance strategy but it can suffer from poor image quality. To avoid repeating scans it is beneficial to make the best use of the imaging data obtained. For conventional 4DCBCT the location and size of respiratory bins is fixed and projections are allocated to the respiratory bin within which it falls. Strictly adhering to this rule is unnecessary and can compromise image quality. In this study we optimize the size and location of respiratory bins and allow projections to be sourced from adjacent phases of the respiratory cycle. Methods: A mathematical optimization framework using mixed integer quadratic programming has been developed that determines when to source projections from adjacent respiratory bins and optimizes the size and location of the bins. The method, which we will call projection sharing, runs in under 2 seconds of CPU time. Five 4DCBCT datasets of stage III-IV lung cancer patients were used to test the algorithm. The standard deviation of the angular separation between projections (SD-A) and the standard deviation in the volume of the reconstructed fiducial gold coil (SD-V) were used as proxies to measure streaking artefacts and motion blur respectively. Results: The SD-A using displacement binning and projection sharing was 30%–50% smaller than conventional phase based binning and 59%–76% smaller than conventional displacement binning indicating more uniformly spaced projections and fewer streaking artefacts. The SD-V was 20–90% smaller when using projection sharing than using conventional phase based binning suggesting more uniform marker segmentation and less motion blur. Conclusion: Image quality was visibly and significantly improved with projection sharing. Projection sharing does not require any modifications to existing hardware and offers a more robust replacement to phase based binning, or, an option if phase based reconstruction is not of a

  14. Collection of measurement data in 2014 fiscal year at the Horonobe Underground Research Laboratory Project

    International Nuclear Information System (INIS)

    Sakurai, Akitaka; Aoyagi, Kazuhei

    2016-07-01

    The Horonobe Underground Research Laboratory (URL) Project has being pursued by Japan Atomic Energy Agency (JAEA) to enhance the reliability of relevant disposal technologies through investigations of the deep geological environment within the host sedimentary formations at Horonobe, northern Hokkaido. The URL project consists of two major research areas, 'Geoscientific Research' and 'R and D on Geological Disposal Technologies', and proceeds in three overlapping phases, 'Phase I: Surface-based investigations', 'Phase II: Investigations during tunnel excavation' and 'Phase III: Investigations in the underground facilities', over a period of around 20 years. The Phase I geoscientific research was carried out from March 2001 to March 2006 in parallel with design and execution scheme on URL facilities. In addition, identifying key issues that need to be addressed in the Phase II/III investigations were planned. At the beginning of the Phase II investigations, investigation reports related to measurement plan and observational construction program on shaft and drift excavation were published. The observational construction program summarizes the followings from the results of the Phase I investigations: measurements for safety and reasonable constructions, enhancement of shaft design and construction technologies and evaluation of appropriateness for the deep geological environment model estimated before shaft excavation. Currently, Phase III investigation related to geological disposal in underground facilities has been conducting. Also, measurement for consideration of long-term stability of the tunnel has been continued. This report summarizes the measurements data acquired at the West Shaft in 2014 fiscal year for the purpose of the basic data for carrying out the Observational Construction Program. A DVD-ROM is attached as an appendix. (J.P.N.)

  15. Disposal and solidification of LAW/MAW in underground caverns, phase 4

    International Nuclear Information System (INIS)

    Ganser, B.; Dedegil, Y.

    1989-05-01

    In this report the concluding phase IV of the project for the containerless disposal of LAW/MAW-concentrate is described. This phase IV became necessary because of two pipe pluggings during phase III to demonstrate the technical performability. Compared with phase III the following plant and process modifications were performed: partially filled cross section of the feed pipe ('snifting air'), increased feed pipe diameter (47.4 to 59.4 mm), increased plant throughput (12 t/h to 24 t/h), feed pipe instrumentation (density, flow, pressure). In the pilot scale the modified process was tested in a 100 m-pipe (Asse, Blindschacht 4). The technical demonstration was performed by the 1000 m pipe from the above-day plant to the prototype cavern of the Asse salt mine. Overall more than 1000 t of product have been feeded within several shifts in successful performance. (orig.) [de

  16. Functional improvement of antibody fragments using a novel phage coat protein III fusion system

    DEFF Research Database (Denmark)

    Jensen, Kim Bak; Larsen, Martin; Pedersen, Jesper Søndergaard

    2002-01-01

    Functional expressions of proteins often depend on the presence of host specific factors. Frequently recombinant expression strategies of proteins in foreign hosts, such as bacteria, have been associated with poor yields or significant loss of functionality. Improvements in the performance of het......(s) of the filamentous phage coat protein III. Furthermore, it will be shown that the observed effect is neither due to improved stability nor increased avidity....

  17. BWR radiation exposure--experience and projection

    International Nuclear Information System (INIS)

    Falk, C.F.; Wilkinson, C.D.; Hollander, W.R.

    1979-01-01

    The BWR/6 Mark III radiation exposures are projected to be about half of those of current average operating experience of 725 man-rem. These projections are said to be realistic and based on current achievements and not on promises of future development. The several BWRs operating with low primary system radiation levels are positive evidence that radiation sources can be reduced. Improvements have been made in reducing the maintenance times for the BWR/6, and further improvements can be made by further attention to cost-effective plant arrangement and layout during detail design to improve accessibility and maintainability of each system and component

  18. Effects of induction docetaxel, platinum, and fluorouracil chemotherapy in patients with stage III or IVA/B nasopharyngeal cancer treated with concurrent chemoradiation therapy: Final results of 2 parallel phase 2 clinical trials.

    Science.gov (United States)

    Kong, Lin; Zhang, Youwang; Hu, Chaosu; Guo, Ye; Lu, Jiade J

    2017-06-15

    The effects of docetaxel, platinum, and fluorouracil (TPF) induction chemotherapy plus concurrent chemoradiotherapy (CCRT) on locoregionally advanced nasopharyngeal cancer (NPC) are unclear. This study examined the long-term outcomes of the addition of this regimen to CCRT for stage III and IVA/B NPC. Two parallel, single-arm phase 2 trials were performed synchronously to evaluate the efficacy and toxicity of TPF-based induction chemotherapy in patients with stage III or IVA/B NPC. The induction chemotherapy, which preceded standard intensity-modulated radiation therapy/platinum-based chemoradiation, consisted of 3 cycles of docetaxel (75 mg/m 2 on day 1), cisplatin (75 mg/m 2 on day 1), and a continuous infusion of fluorouracil (500 mg/m 2 /d on days 1-5) every 4 weeks. The primary endpoint for both trials was 5-year overall survival (OS). Between January 2007 and July 2010, 52 eligible patients with stage III NPC and 64 eligible patients with nonmetastatic stage IV NPC were accrued to the 2 trials. With a median follow-up of 67 months, the 5-year OS, progression-free survival, distant metastasis-free survival, and local progression-free survival (LPFS) rates were all improved in comparison with historical benchmarks for patients with stage III or IVA/IVB NPC. Multivariate analyses indicated that T and N classifications (T1/T2 vs T3/T4 and N3 vs N0-N2) were the only significant prognosticators for OS. The number of induction chemotherapy cycles was the only significant prognostic factor for predicting LPFS. TPF-based induction chemotherapy appears to significantly improve outcomes in comparison with historical data when it is administered before CCRT for locoregionally advanced NPC. A phase 3 trial is currently being performed to confirm this benefit. Cancer 2017;123:2258-2267. © 2017 American Cancer Society. © 2017 American Cancer Society.

  19. Can treatment with Cocculine improve the control of chemotherapy-induced emesis in early breast cancer patients? A randomized, multi-centered, double-blind, placebo-controlled Phase III trial

    Directory of Open Access Journals (Sweden)

    Pérol David

    2012-12-01

    to nausea and vomiting before inclusion. In addition, nausea, vomiting and global emesis FLIE scores were not statistically different at any time between the two study arms. The frequencies of severe (Grade ≥ 2 nausea and vomiting were low in our study (nausea: P: 17.6% vs C: 15.7%, p=0.62; vomiting: P: 10.8% vs C: 12.0%, p=0.72 during the first course. Conclusion This double-blinded, placebo-controlled, randomised Phase III study showed that adding a complex homeopathic medicine (Cocculine to standard anti-emetic prophylaxis does not improve the control of CINV in early breast cancer patients.

  20. Improved design for large wind turbine blades of fibre composites (Phase 4) - Summary report

    Energy Technology Data Exchange (ETDEWEB)

    Soerensen, B.F.; Toftegaard, H.; Goutanos, S. (Risoe DTU, Materials Research Div., Roskilde (Denmark)); Branner, K.; Berring, P. (Risoe DTU, Wind Energy Div., Roskilde (Denmark)); Lund, E. (Aalborg Univ., Dept. of Mechanical Engineering, Aalborg (Denmark)); Wedel-Heinen, J. (Vestas Wind System, Randers (Denmark)); Garm, J.H. (LM Wind Power, Kolding (Denmark))

    2010-06-15

    Results are summarised for the project 'Improved design for large wind turbine blades (Phase 4)', partially supported by the Danish Energy Agency under the Ministry of Climate and Energy through the EUDP journal no.: 33033-0267. The aim of the project was to develop new and better design methods for wind turbine blades, so that uncertainties associated with damage and defects can be reduced. The topics that are studied include buckling-driven delamination of flat load-carrying laminates, cracking along interfaces in material joints (fracture mechanical characterisation and modelling), cyclic crack growth with large scale bridging and the use of cohesive laws in finite element programmes for simulating wind turbine blade failure. An overview is given of the methods and the major research results of the project. The implementation of the knowledge in the industry is discussed. Finally, some ideas for future research activities are considered. (author)

  1. Improving Hybrid III injury assessment in steering wheel rim to chest impacts using responses from finite element Hybrid III and human body model.

    Science.gov (United States)

    Holmqvist, Kristian; Davidsson, Johan; Mendoza-Vazquez, Manuel; Rundberget, Peter; Svensson, Mats Y; Thorn, Stefan; Törnvall, Fredrik

    2014-01-01

    The main aim of this study was to improve the quality of injury risk assessments in steering wheel rim to chest impacts when using the Hybrid III crash test dummy in frontal heavy goods vehicle (HGV) collision tests. Correction factors for chest injury criteria were calculated as the model chest injury parameter ratios between finite element (FE) Hybrid III, evaluated in relevant load cases, and the Total Human Model for Safety (THUMS). This is proposed to be used to compensate Hybrid III measurements in crash tests where steering wheel rim to chest impacts occur. The study was conducted in an FE environment using an FE-Hybrid III model and the THUMS. Two impactor shapes were used, a circular hub and a long, thin horizontal bar. Chest impacts at velocities ranging from 3.0 to 6.0 m/s were simulated at 3 impact height levels. A ratio between FE-Hybrid III and THUMS chest injury parameters, maximum chest compression C max, and maximum viscous criterion VC max, were calculated for the different chest impact conditions to form a set of correction factors. The definition of the correction factor is based on the assumption that the response from a circular hub impact to the middle of the chest is well characterized and that injury risk measures are independent of impact height. The current limits for these chest injury criteria were used as a basis to develop correction factors that compensate for the limitations in biofidelity of the Hybrid III in steering wheel rim to chest impacts. The hub and bar impactors produced considerably higher C max and VC max responses in the THUMS compared to the FE-Hybrid III. The correction factor for the responses of the FE-Hybrid III showed that the criteria responses for the bar impactor were consistently overestimated. Ratios based on Hybrid III and THUMS responses provided correction factors for the Hybrid III responses ranging from 0.84 to 0.93. These factors can be used to estimate C max and VC max values when the Hybrid III is

  2. Advanced Petroleum-Based Fuels -- Diesel Emissions Control Project (APBF-DEC): Lubricants Project, Phase 2 Final Report

    Energy Technology Data Exchange (ETDEWEB)

    2006-06-01

    This report summarizes the results of the second phase of a lubricants project, which investigated the impact of engine oil formulation on diesel vehicle emissions and the performance of a nitrogen oxide adsorber catalyst (NAC).

  3. The PISC III programme: 1989 status report

    International Nuclear Information System (INIS)

    Crutzen, S.; Jehenson, P.; McDonald, N.

    1990-01-01

    The PISC Programme has the general objective of assessing procedures and techniques in use for the inspection of pressure components (in particular the vessel and piping). The Series of projects for the Inspection of Steel Components carried out since 1974 under the auspices of the CEC/JRC and the OECD/NEA is a major international effort to better assess the capability and reliability of Non Destructive Inspection procedures on structural components. The programme is now in its third phase (PISC III project); the activities are concentrated on the validation of the PISC II results (e.g. modification of the ASME Inspection Codes) on real structures containing real service defects and the extension of the PISC methodology on most important structural components made of different materials. Most of the PISC test assemblies and structure pieces are representative of (or are coming from) nuclear reactor components. (author)

  4. Contribution of the Politecnico di Milano to the FUMEX-III Project

    International Nuclear Information System (INIS)

    Luzzi, Lelio; Pastore, Giovanni; Van Uffelen, Paul

    2013-01-01

    In nuclear reactors, irradiation continuously alter the thermal, mechanical, and chemical properties of nuclear fuels (Olander 1976). To assure the safe and economic operation of the nuclear fuel rods in all the operation conditions, there is a need for fuel characterization and optimization through an integrated theoretical, experimental, and computational approach. The aim of computational fuel modelling is to predict the changes in properties and evaluate the thermo-mechanical behaviour of the fuel rods during the life in the reactor. For this purpose, increasingly complex fuel performance codes are developed, which include physical models of the processes taking place in the fuel rods during irradiation (Aybar and Ortego 2005). In this framework, international benchmark exercises on fuel modelling are of high importance for the development of fuel performance codes, since they provide the possibility for cross-comparison and complementary validation of a large number of codes involved. Three such exercises were organized during the last 3 decades: D-COM in the mid 80's (Misfeldt 1983), and the Coordinated Research Projects (CRPs) FUMEX-I (1993-1996) (Chantoin et al. 1997) and FUMEX-II (2002- 2006) (Killeen et al. 2007, IAEA 2011). In extending the previous CRPs on the subject of improving the predictive capabilities of fuel performance codes for extended burn-up and transient conditions, the focus of the CRP FUMEX-III (2008-2012) is on the topics of fission gas release, pellet-cladding interaction (PCI) and dimensional changes (Killeen et al. 2009). The TRANSURANUS fuel performance code (Lassmann 1992, Lassmann 2001) is presently available at the Politecnico di Milano (POLIMI). Based on the assumption of axial-symmetric cylindrical rod and the superposition of a one-dimensional radial and axial description (11/2D approach), the mechanical-mathematical framework of TRANSURANUS allows to analyze, at reasonable computer cost, the integral fuel rod during a

  5. Improved Prioritization Criteria for Road Infrastructure Projects

    Directory of Open Access Journals (Sweden)

    Ionescu Heroiu Marcel

    2016-12-01

    Full Text Available This report’s main aim is to propose a methodology for assessing state-budget-funded projects based on a rigorous selection model, including clear and effective prioritization criteria. This report first argues that project prioritization and selection should be optimized against four dimensions: absorption, impact, legitimacy, and capacity. Second, it provides a diagnostic of the National Program for Local Development (PNDL, managed by the Ministry of Regional Development and Public Administration (MRDPA, as the most significant source of state-budget funding for local infrastructure projects. The PNDL’s current design and implementation leaves room for improvement, as reflected by the lack of strategic direction in allocating funds and the continued rise in the number of projects that get started without a feasible timeline for their completion. Further, this report makes recommendations for improvement of project evaluation and selection procedures for local infrastructure development projects, with a special focus on prioritization criteria and viable funding sources for each type of investment. The practical purpose is to enhance the efficiency and effectiveness of proposed investments, maximizing impact in the context of inherently limited available financial resources. A complementary focus is on opportunities for harmonizing and better coordinating investments across various sources of funding, in the context of nearly EUR 40 billion available to Romania from the EU for the 2014-2020 programming period.

  6. Long-Term Management Strategy for Dredged Material Disposal for Naval Facilities at Pearl Harbor, Hawaii Phase III - Analysis of Alternatives and Development of an LTMS

    National Research Council Canada - National Science Library

    Palermo, Michael

    2000-01-01

    This report documents Phase III of a three-phase study to develop a Long-Term Management Study for disposal of dredged material unsuitable for ocean disposal from Pearl Harbor Naval Complex for the next 30 years...

  7. Robust Requirements Tracing via Internet Search Technology: Improving an IV and V Technique. Phase 2

    Science.gov (United States)

    Hayes, Jane; Dekhtyar, Alex

    2004-01-01

    There are three major objectives to this phase of the work. (1) Improvement of Information Retrieval (IR) methods for Independent Verification and Validation (IV&V) requirements tracing. Information Retrieval methods are typically developed for very large (order of millions - tens of millions and more documents) document collections and therefore, most successfully used methods somewhat sacrifice precision and recall in order to achieve efficiency. At the same time typical IR systems treat all user queries as independent of each other and assume that relevance of documents to queries is subjective for each user. The IV&V requirements tracing problem has a much smaller data set to operate on, even for large software development projects; the set of queries is predetermined by the high-level specification document and individual requirements considered as query input to IR methods are not necessarily independent from each other. Namely, knowledge about the links for one requirement may be helpful in determining the links of another requirement. Finally, while the final decision on the exact form of the traceability matrix still belongs to the IV&V analyst, his/her decisions are much less arbitrary than those of an Internet search engine user. All this suggests that the information available to us in the framework of the IV&V tracing problem can be successfully leveraged to enhance standard IR techniques, which in turn would lead to increased recall and precision. We developed several new methods during Phase II; (2) IV&V requirements tracing IR toolkit. Based on the methods developed in Phase I and their improvements developed in Phase II, we built a toolkit of IR methods for IV&V requirements tracing. The toolkit has been integrated, at the data level, with SAIC's SuperTracePlus (STP) tool; (3) Toolkit testing. We tested the methods included in the IV&V requirements tracing IR toolkit on a number of projects.

  8. An assessment of BWR [boiling water reactor] Mark III containment challenges, failure modes, and potential improvements in performance

    International Nuclear Information System (INIS)

    Schroeder, J.A.; Pafford, D.J.; Kelly, D.L.; Jones, K.R.; Dallman, F.J.

    1991-01-01

    This report describes risk-significant challenges posed to Mark III containment systems by severe accidents as identified for Grand Gulf. Design similarities and differences between the Mark III plants that are important to containment performance are summarized. The accident sequences responsible for the challenges and the postulated containment failure modes associated with each challenge are identified and described. Improvements are discussed that have the potential either to prevent or delay containment failure, or to mitigate the offsite consequences of a fission product release. For each of these potential improvements, a qualitative analysis is provided. A limited quantitative risk analysis is provided for selected potential improvements. 21 refs., 5 figs., 46 tabs

  9. Donepezil improves gait performance in older adults with mild Alzheimer's disease: a phase II clinical trial.

    Science.gov (United States)

    Montero-Odasso, Manuel; Muir-Hunter, Susan W; Oteng-Amoako, Afua; Gopaul, Karen; Islam, Anam; Borrie, Michael; Wells, Jennie; Speechley, Mark

    2015-01-01

    Gait deficits are prevalent in people with dementia and increase their fall risk and future disability. Few treatments exist for gait impairment in Alzheimer's disease (AD) but preliminary studies have shown that cognitive enhancers may improve gait in this population. To determine the efficacy of donepezil, a cognitive enhancer that improves cholinergic activity, on gait in older adults newly diagnosed with AD. Phase II clinical trial in 43 seniors with mild AD who received donepezil. Participants had not previously received treatment with cognitive enhancers. Primary outcome variables were gait velocity (GV) and stride time variability (STV) under single and dual-task conditions measured using an electronic walkway. Secondary outcomes included attention and executive function. After four months of treatment, participants with mild AD improved their GV from 108.4 ± 18.6 to 113.3 ± 19.5 cm/s, p = 0.010; dual-task GV from 80.6 ± 23.0 to 85.3 ± 22.3 cm/s, p = 0.028. Changes in STV were in the expected direction although not statistically significant. Participants also showed improvements in Trail Making Tests A (p = 0.030), B (p = 0.001), and B-A (p = 0.042). Donepezil improved gait in participants with mild AD. The enhancement of dual-task gait suggests the positive changes achieved in executive function as a possible causal mechanism. This study yielded a clinically significant estimate of effect size; as well, the findings are relevant to the feasibility and ethics considerations for the design of a Phase III clinical trial.

  10. Interest groups, the Lesotho Highlands Water Project Phase 1

    African Journals Online (AJOL)

    interest groups can bring about changes in the water policy arena. ... Lesotho Highlands Water Project Phase 1 as a case study. ... attempts to influence public policy and their representation ... ties concern the relations between state actors and non-state ..... 'bears responsibility here [LHWP], since it is the sponsor of.

  11. A phased approach to cooperative environmental management R ampersand D projects with Russian institutes

    International Nuclear Information System (INIS)

    Matalucci, R.V.; Albert, T.E.

    1994-01-01

    An important aspect of technology exchange between the US and the Former Society Union (FSU) countries is the identification and implementation of cooperative projects that are mutually beneficial. The US Department of Energy (DOE) and its national laboratories have established a four-phase approach to identify and further develop Russian technologies that could contribute to solving DOE environmental management problems. Following an initial screening and identification of potential technologies, the country-to-country interaction is formally initiated in the first phase through a small-scale pilot project study. This phase consists of an evaluation of the specific technology for DOE applications, and provides an opportunity for both US and Russian scientists and engineers to validate the use of the technology for a specific DOE requirement. The successful completion of this phase establishes the basis for continuing the technology development into the second phase, which includes laboratory testing in Russia. In the third phase, the technology is laboratory tested in the US, most likely at those DOE national laboratories having the capability and greatest interest in the particular technology area. The fourth and final phase consist of a commercialization process that establishes a partnership with a US business to finalize development of the technology and to prepare for implementation within the DOE complex. An example of this phased approach is a current high-level waste separation cooperative project between the Khlopin Radium Institute and the DOE through Sandia National Laboratories (SNL) and Science Applications International Corporation (SAIC). This effort has not only enhanced separations technology for the DOE, but has also provided an example of a working process for future cooperative projects

  12. Electronic monitoring and voice prompts improve hand hygiene and decrease nosocomial infections in an intermediate care unit.

    Science.gov (United States)

    Swoboda, Sandra M; Earsing, Karen; Strauss, Kevin; Lane, Stephen; Lipsett, Pamela A

    2004-02-01

    To determine whether electronic monitoring of hand hygiene and voice prompts can improve hand hygiene and decrease nosocomial infection rates in a surgical intermediate care unit. Three-phase quasi-experimental design. Phase I was electronic monitoring and direct observation; phase II was electronic monitoring and computerized voice prompts for failure to perform hand hygiene on room exit; and phase III was electronic monitoring only. Nine-room, 14-bed intermediate care unit in a university, tertiary-care institution. All patient rooms, utility room, and staff lavatory were monitored electronically. All healthcare personnel including physicians, nurses, nursing support personnel, ancillary staff, all visitors and family members, and any other personnel interacting with patients on the intermediate care unit. All patients with an intermediate care unit length of stay >48 hrs were followed for nosocomial infection. Electronic monitoring during all phases, computerized voice prompts during phase II only. We evaluated a total of 283,488 electronically monitored entries into a patient room with 251,526 exits for 420 days (10,080 hrs and 3,549 patient days). Compared with phase I, hand hygiene compliance in patient rooms improved 37% during phase II (odds ratio, 1.38; 95% confidence interval, 1.04-1.83) and 41% in phase III (odds ratio, 1.41; 95% confidence interval, 1.07-1.84). When adjusting for patient admissions during each phase, point estimates of nosocomial infections decreased by 22% during phase II and 48% during phase III; when adjusting for patient days, the number of infections decreased by 10% during phase II and 40% during phase III. Although the overall rate of nosocomial infections significantly decreased when combining phases II and III, the association between nosocomial infection and individual phase was not significant. Electronic monitoring provided effective ongoing feedback about hand hygiene compliance. During both the voice prompt phase and post

  13. Final Report for the ADMX Phase 2a Project at the University of Washington

    International Nuclear Information System (INIS)

    Rosenberg, Leslie J.

    2015-01-01

    This is a final report of the ADMX (Axion Dark Matter eXperiment) Phase 2a program. This program is a project allowing for a sensitive axion dark-matter search at higher axion masses. The Phase 2a program also prepares the project for lower temperature anticipated in later operations. The Phase 2a program includes sensitive data-taking operations at two cavity modes, TM010 and TM020, allowing for faster data-taking operations and extending the search to higher and plausible dark-matter axion masses.

  14. Improving Minuteman III Maintenance Concepts

    Science.gov (United States)

    2017-03-23

    the ground . Then figure out what your challenges are. We’ll have those” (Pappalardo, 2011). Another challenge facing the maintenance personnel...as assets aged as indicated by the pattern ‘B’ shown in Figure 2. With the increase in the mechanization of processes, more attention has been...concepts could be applied to the sustainment of the MM III as well as benefit its planned replacement, the Ground Based Strategic Deterrent (GBDS

  15. Utilization of modified corn silk as a biosorbent for solid-phase extraction of Cr(III) and chromium speciation.

    Science.gov (United States)

    Yu, Hongmei; Pang, Jing; Wu, Mei; Wu, Qiaoli; Huo, Cuixiu

    2014-01-01

    The ues of corn silk modified with diluted nitric acid (HNO3-MCS) as a novel biosorbent has been established for solid-phase extraction of Cr(III) and chromium speciation in water samples. The functional groups of the HNO3-MCS surface are favorable for the adsorption of Cr(III). Effective extraction conditions were optimized in both batch and column methods. At pH 3.0 - 6.0, a discrimination of Cr(III) and Cr(VI) is achieved on the HNO3-MCS surface. Cr(III) ions are retained onto the HNO3-MCS surface, however, the adsorption of Cr(VI) is negligible under the same conditions. The adsorption isotherm of HNO3-MCS for Cr(III) has been demonstrated in accordance with a linear form of the Langmuir equation, and the maximum adsorption capacity is 35.21 mg g(-1). The well fitted linear regression of the pseudo-second order model showed the indication of a chemisorption mechanism for the entire concentration range. Thermodynamic studies have shown that the adsorption process is spontaneous and endothermic. The adsorbed Cr(III) was quantitatively eluted by a nitric acid solution with detection by flame atomic absorption spectrometry (FAAS). With a sample volume of 30 mL, a detection limit (3σ) of 0.85 μg L(-1) and a precision of 2.0% RSD at the 40 μg L(-1) level were achieved. The concentration of Cr(III) could be accurately quantified within a linear range of 3 - 200 μg L(-1). After Cr(VI) has been reduced to Cr(III) with hydroxylamine hydrochloride, the total amount of chromium was obtained, and the content of Cr(VI) was given by subtraction. The procedure was validated by analyzing chromium in a certified reference material (GBW (E) 080039). It was also successfully applied for the speciation of chromium in wastewater samples.

  16. Improving the luteal phase after ovarian stimulation

    DEFF Research Database (Denmark)

    Andersen, Claus Yding; Vilbour Andersen, K

    2014-01-01

    The human chorionic gonadotrophin (HCG) trigger used for final follicular maturation in connection with assisted reproduction treatment combines ovulation induction and early luteal-phase stimulation of the corpora lutea. The use of a gonadotrophin-releasing hormone agonist (GnRHa) for final...... follicular maturation has, however, for the first time allowed a separation of the ovulatory signal from the early luteal-phase support. This has generated new information that may improve the currently employed luteal-phase support. Thus, combined results from a number of randomized controlled trials using...

  17. Improved Lunar and Martian Regolith Simulant Production, Phase II

    Data.gov (United States)

    National Aeronautics and Space Administration — The technical objective of the Phase II project is to provide a more complete investigation of the long-term needs of the simulant community based on the updated...

  18. Stakeholder Salience in ERP Projects

    OpenAIRE

    Salhotra, Eashan

    2014-01-01

    The aim of this study is to examine stakeholder involvement in an Enterprise Resource Planning (ERP) System project that involves implementation and improvement of the implemented system. The study targets stakeholders, their classification, and their degree of importance during different phases of an ERP project life cycle, i.e. planning, implementation, stabilisation and improvement. The study shows that stakeholder involvement and their salience vary along the ERP project life cycle a...

  19. MDSplus quality improvement project

    Energy Technology Data Exchange (ETDEWEB)

    Fredian, Thomas W., E-mail: twf@psfc.mit.edu [Massachusetts Institute of Technology, 175 Albany Street, Cambridge, MA 02139 (United States); Stillerman, Joshua [Massachusetts Institute of Technology, 175 Albany Street, Cambridge, MA 02139 (United States); Manduchi, Gabriele; Rigoni, Andrea [Consorzio RFX, Euratom-ENEA Association, Corso Stati Uniti 4, Padova 35127 (Italy); Erickson, Keith [Princeton Plasma Physics Laboratory, Princeton, NJ 08543 (United States)

    2016-11-15

    Highlights: • Project to improve the quality of the MDSplus software package. • Use of modern software technology, compiler options, automake. • Refactoring of older code. • Use of testing tools. - Abstract: MDSplus is a data acquisition and analysis system used worldwide predominantly in the fusion research community. Development began 29 years ago on the OpenVMS operating system. Since that time there have been many new features added and the code has been ported to many different operating systems. There have been contributions to the MDSplus development from the fusion community in the way of feature suggestions, feature implementations, documentation and porting to different operating systems. The bulk of the development and support of MDSplus, however, has been provided by a relatively small core developer group of three or four members. Given the size of the development team and the large number of users much more effort was focused on providing new features for the community than on keeping the underlying code and documentation up to date with the evolving software development standards. To ensure that MDSplus will continue to provide the needs of the community in the future, the MDSplus development team along with other members of the MDSplus user community has commenced on a major quality improvement project. The planned improvements include changes to software build scripts to better use GNU Autoconf and Automake tools, refactoring many of the source code modules using new language features available in modern compilers, using GNU MinGW-w64 to create MS Windows distributions, migrating to a more modern source code management system, improvement of source documentation as well as improvements to the (www.mdsplus.org) web site documentation and layout, and the addition of more comprehensive test suites to apply to MDSplus code builds prior to releasing installation kits to the community. This work should lead to a much more robust product and

  20. MDSplus quality improvement project

    International Nuclear Information System (INIS)

    Fredian, Thomas W.; Stillerman, Joshua; Manduchi, Gabriele; Rigoni, Andrea; Erickson, Keith

    2016-01-01

    Highlights: • Project to improve the quality of the MDSplus software package. • Use of modern software technology, compiler options, automake. • Refactoring of older code. • Use of testing tools. - Abstract: MDSplus is a data acquisition and analysis system used worldwide predominantly in the fusion research community. Development began 29 years ago on the OpenVMS operating system. Since that time there have been many new features added and the code has been ported to many different operating systems. There have been contributions to the MDSplus development from the fusion community in the way of feature suggestions, feature implementations, documentation and porting to different operating systems. The bulk of the development and support of MDSplus, however, has been provided by a relatively small core developer group of three or four members. Given the size of the development team and the large number of users much more effort was focused on providing new features for the community than on keeping the underlying code and documentation up to date with the evolving software development standards. To ensure that MDSplus will continue to provide the needs of the community in the future, the MDSplus development team along with other members of the MDSplus user community has commenced on a major quality improvement project. The planned improvements include changes to software build scripts to better use GNU Autoconf and Automake tools, refactoring many of the source code modules using new language features available in modern compilers, using GNU MinGW-w64 to create MS Windows distributions, migrating to a more modern source code management system, improvement of source documentation as well as improvements to the (www.mdsplus.org) web site documentation and layout, and the addition of more comprehensive test suites to apply to MDSplus code builds prior to releasing installation kits to the community. This work should lead to a much more robust product and

  1. Collection of measurement data in 2012 fiscal year at the Horonobe Underground Research Laboratory project

    International Nuclear Information System (INIS)

    Inagaki, Daisuke

    2014-03-01

    The Horonobe Underground Research Laboratory (URL) Project has being pursued by the Japan Atomic Energy Agency (JAEA) to enhance the reliability of relevant disposal technologies through investigations of the deep geological environment within the host sedimentary formations at Horonobe, northern Hokkaido. The URL project consists of two major research areas, 'Geoscientific Research' and 'R and D on Geological Disposal Technologies', and proceeds in three overlapping phases, 'Phase I: Surface-based investigations', 'Phase II: Investigations during tunnel excavation' and 'Phase III: Investigations in the underground facilities', over a period of around 20 years. The Phase I geoscientific research was carried out from March 2001 to March 2006 in parallel with design and execution scheme on URL facilities. In addition, identifying key issues that need to be addressed in the Phase II/III investigations was planned. At the begining of the Phase II investigations, an investigation report titled 'Measurement Plan and Observational Construction Program on Shaft Excavation at the Horonobe Underground Research Laboratory Project' (hereinafter referred to as 'Observational Construction Program') and an investigation report titled 'Measurement Plan and Observational Construction Program on Drift Excavation at the Horonobe Underground Research Laboratory Project' were published. The Observational Construction Program summarizes the followings from the results of the Phase I investigations: measurements for safety and reasonable constructions, enhancement of shaft design and construction technologies and evaluation of appropriateness for the deep geological environment model estimated before shaft excavation. This report summarizes the measurements data acquired at the Ventilation Shaft, the East Shaft and the drifts in 2012 fiscal year based on the Observational Construction Program. The report summarizes the measurements data for the purpose of acquisition of the basic data

  2. Improving access to research outcomes for innovation in agriculture and forestry: the VALERIE project

    Directory of Open Access Journals (Sweden)

    Luca Bechini

    2017-06-01

    Full Text Available Many excellent results are obtained in agricultural and forestry research projects, but their practical adoption is often limited. The aim of the European project VALERIE is to increase the transfer and application of innovations produced by research in agriculture and forestry, by facilitating their integration into management practices. The project is still ongoing and the results illustrated in this paper are still temporary and subject to being improved. Here we present the methodology used in VALERIE to extract and summarise knowledge for innovation from research documents with the aim of making it available to final users through ask-Valerie.eu; we also report on current progress. The tasks associated with extracting and summarising knowledge are centred on: i an ontology; ii a document base; and iii a system (ask-Valerie.eu that allows users to effectively search the document base. An ontology defines a set of concepts and the relations between them. The VALERIE ontology is built by experts in the agricultural and forestry domain and contains 6169 concepts (21st October 2016. The document base is the collection of documents in which the system searches. The VALERIE document base includes scientific and practical documents derived from various sources, written in any of a number of languages. All documents contained in the document base are annotated using the ontology: each term (a word or a short phrase in the document that matches a concept in the VALERIE-ontology is linked to that concept. Annotation is an automated process that takes place whenever a document is added to the document base. The document base contains 4278 documents (October 2016. Among them, there are 201 minifactsheets written by members of the VALERIE project, each describing an innovation with: a short description of the innovation, a list of correlated projects, and some links to scientific and practical documents. ask-Valerie.eu searches documents and fragments of

  3. Improving image quality of parallel phase-shifting digital holography

    International Nuclear Information System (INIS)

    Awatsuji, Yasuhiro; Tahara, Tatsuki; Kaneko, Atsushi; Koyama, Takamasa; Nishio, Kenzo; Ura, Shogo; Kubota, Toshihiro; Matoba, Osamu

    2008-01-01

    The authors propose parallel two-step phase-shifting digital holography to improve the image quality of parallel phase-shifting digital holography. The proposed technique can increase the effective number of pixels of hologram twice in comparison to the conventional parallel four-step technique. The increase of the number of pixels makes it possible to improve the image quality of the reconstructed image of the parallel phase-shifting digital holography. Numerical simulation and preliminary experiment of the proposed technique were conducted and the effectiveness of the technique was confirmed. The proposed technique is more practical than the conventional parallel phase-shifting digital holography, because the composition of the digital holographic system based on the proposed technique is simpler.

  4. DELSY project: status and development Dubna Electron Synchrotron

    CERN Document Server

    Balalykin, N; Bykovsky, V

    2003-01-01

    The DELSY (Dubna Electron Synchrotron) project is under development at the Joint Institute for Nuclear Research. It is based on an acceleration facility donated to the Joint Institute for Nuclear Research by the Institute for Nuclear and High Energy Physics (NIKHEF, Amsterdam). The NIKHEF accelerator facility consists of the linear electron accelerator MEA, which has an electron energy of 700 MeV, and the electron storage ring AmPS, with a maximum energy of 900 MeV and a beam current of 200 mA. There are three phases to the construction of the DELSY facility. Phase I will be accomplished with the construction of a complex of free-electron lasers covering continuously the spectrum from the far infrared down to the ultraviolet (approx 150 nm). Phase II will be accomplished with the commissioning of the storage ring DELSY. Complete commissioning of the DELSY project will take place after finishing Phase III, the construction of an X-ray free-electron laser. This phase is considered as the ultimate goal of the pr...

  5. Phase 2 of the Nea TDB project and some lessons learned from the use of phase 1 data

    International Nuclear Information System (INIS)

    Spahiu, K.

    2002-01-01

    As the five initial reviews of the TDB Project come to their conclusion, the negotiations for an independently funded continuation of the TDB Project through two meetings of an ad hoc group were completed in late 1997. The participating organisations are ANSTO (Australia), NIRAS/ONDRAF (Belgium), RAWRA (Czech Republic), POSIVA (Finland), ANDRA and IPSN (France), FZK (Germany), JNC/PNC (Japan), ENRESA (Spain), SKB and SKI (Sweden), HSK, NAGRA and PSI (Switzerland), BNFL and NIREX (UK) and the DOE (USA). This project is referred to as the TDB Phase II Project, or simply TDB II. The following new reviews will be performed within this project: - an update of the existing U/Am/Tc/Np/Pu reviews (one review team for all elements); - the inorganic chemistry of Ni; - the inorganic chemistry of Se; - the complexation of selected simple organic ligands (ISA, EDTA, citrate and oxalate) with U, Am, Tc, Np, Pu, Ni, Se, Zr and some selected competing cations; the inorganic chemistry of Zr. These review areas have been decided on taking into account the toxicity, mobility, radioactivity and half-lives of the commonly occurring nuclides in radioactive waste, as well as the particular areas of interest of the funding organisations. To avoid the delays that have plagued Phase I, the organisation of the TDB Project has been restructured, and the funding provided has been calculated to cover all necessary expenses for the project. (author)

  6. Treatment-related death in patients with small-cell lung cancer in phase III trials over the last two decades.

    Directory of Open Access Journals (Sweden)

    Nobuaki Ochi

    Full Text Available INTRODUCTION: Treatment-related death (TRD remains a serious problem in small-cell lung cancer (SCLC, despite recent improvements in supportive care. However, few studies have formally assessed time trends in the proportion of TRD over the past two decades. The aim of this study was to determine the frequency and pattern of TRD over time. METHODS: We examined phase 3 trials conducted between 1990 and 2010 to address the role of systemic treatment for SCLC. The time trend was assessed using linear regression analysis. RESULTS: In total, 97 trials including nearly 25,000 enrolled patients were analyzed. The overall TRD proportion was 2.95%. Regarding the time trend, while it was not statistically significant, it tended to decrease, with a 0.138% decrease per year and 2.76% decrease per two decades. The most common cause of death was febrile neutropenia without any significant time trend in its incidence over the years examined (p = 0.139. However, deaths due to febrile neutropenia as well as all causes in patients treated with non-platinum chemotherapy increased significantly (p = 0.033. CONCLUSIONS: The overall TRD rate has been low, but not negligible, in phase III trials for SCLC over the past two decades.

  7. Analysis of a new phase and height algorithm in phase measurement profilometry

    Science.gov (United States)

    Bian, Xintian; Zuo, Fen; Cheng, Ju

    2018-04-01

    Traditional phase measurement profilometry adopts divergent illumination to obtain the height distribution of a measured object accurately. However, the mapping relation between reference plane coordinates and phase distribution must be calculated before measurement. Data are then stored in a computer in the form of a data sheet for standby applications. This study improved the distribution of projected fringes and deducted the phase-height mapping algorithm when the two pupils of the projection and imaging systems are of unequal heights and when the projection and imaging axes are on different planes. With the algorithm, calculating the mapping relation between reference plane coordinates and phase distribution prior to measurement is unnecessary. Thus, the measurement process is simplified, and the construction of an experimental system is made easy. Computer simulation and experimental results confirm the effectiveness of the method.

  8. Collection of URL measurement data in 2007 at the Horonobe Underground Research Laboratory project

    International Nuclear Information System (INIS)

    Yamasaki, Masanao; Funaki, Hironori; Niinuma, Hiroaki; Fujikawa, Daisuke; Sanada, Hiroyuki; Hiraga, Naoto; Tsusaka, Kimikazu; Yamaguchi, Takehiro

    2008-11-01

    The Horonobe Underground Research Laboratory (URL) Project has being pursued by the Japan Atomic Energy Agency (JAEA) to enhance the reliability of relevant disposal technologies through investigations of the deep geological environment within the host sedimentary formations at Horonobe, northern Hokkaido. The project consists of two major research areas, Geoscientific Research' and 'R and D on Geological Disposal', and proceeds in three overlapping phases, 'Phase I: Surface-based investigation', 'Phase II: Construction' and 'Phase III: Operation', over a period of 20 years. The Phase I geoscientific research was planned from March 2001 to March 2006 in parallel with design and execution scheme on URL facilities. In addition, identifying key issues that need to be addressed in the Phase II/III investigations was planned. At the beginning of the Phase II investigations, an investigation report titled 'Measurement Plan and Observational Construction Program on Shaft Excavation at the Horonobe Underground Research Laboratory Project' (hereinafter referred to as 'Observational Construction Program') was published. The Observational Construction Program summarizes the followings from the results of the Phase I investigations: measurements for safety and reasonable constructions, enhancement of shaft design and construction technologies and evaluation of appropriateness for the deep geological environment model estimated before shaft excavation. This report summarizes the measurements data acquired at the Ventilation Shaft, the East Shaft and the drifts in 2007 based on the Observational Construction Program. The report summarizes for the purpose of the following: sharing the investigation and measurements data, preventing the loss of them and acquisition the basic data for carrying out the Observational Construction Program. Two DVD-ROMs are attached as an appendix. (J.P.N.)

  9. Fundamental research of two-phase flows with high liquid/gas density ratios

    International Nuclear Information System (INIS)

    Mishima, Kaichiro; Hibiki, Takashi; Saito, Yasushi; Tobita, Yoshiharu; Konishi, Kensuke; Suzuki, Tohru

    2000-07-01

    In order to analyze the boiling of a fuel-steel mixture pool formed during the core disruptive accident in a fast breeder reactor, it is important to understand the flow characteristics of gas-liquid two-phase pools containing molten reactor materials. Since the liquid/gas density ratio is high, the characteristics of such two-phase flows may differ from those of ordinary flows such as water/air flow. In this study, as a fundamental research of two-phase flows with a high liquid/gas density ratio, the experiments were performed to visualize and measure molten metal (lead-bismuth)/nitrogen gas two-phase flows using a neutron radiography technique. From these experiments, fundamental data such as bubble shapes, void fractions and liquid velocity fields were obtained. In addition, the momentum exchange model of SIMMER-III, which has been developed by JNC, was assessed and improved using the experimental data. In the visualization by neutron radiography, it was found that deformed ellipsoidal bubbles could be seen with smaller gas flux or lower void fractions, and spherical cap bubbles could be seen with larger gas flux or higher void fractions. In addition, a correlation applicable to SIMMER-III was proposed through a comparison between the experimental data and traditional empirical correlations. Furthermore, a visualization experiment using gold-cadmium tracer particles showed that the image processing technique used in the quantification of void fractions is applicable to the measurement of the liquid velocity fields. On the other hand, in the analysis by SIMMER-III, it was confirmed that the original momentum exchange model was appropriate for ellipsoidal bobby flows and that the accuracy of SIMMER-III for cap bubbly flows was much improved with the proposed correlation. Moreover, a new procedure, in which the appropriate drag coefficient could be automatically selected according to bubble shape, was developed. The SIMMER-III code improved through this study can

  10. Improvement of the cost-benefit analysis algorithm for high-rise construction projects

    Directory of Open Access Journals (Sweden)

    Gafurov Andrey

    2018-01-01

    Full Text Available The specific nature of high-rise investment projects entailing long-term construction, high risks, etc. implies a need to improve the standard algorithm of cost-benefit analysis. An improved algorithm is described in the article. For development of the improved algorithm of cost-benefit analysis for high-rise construction projects, the following methods were used: weighted average cost of capital, dynamic cost-benefit analysis of investment projects, risk mapping, scenario analysis, sensitivity analysis of critical ratios, etc. This comprehensive approach helped to adapt the original algorithm to feasibility objectives in high-rise construction. The authors put together the algorithm of cost-benefit analysis for high-rise construction projects on the basis of risk mapping and sensitivity analysis of critical ratios. The suggested project risk management algorithms greatly expand the standard algorithm of cost-benefit analysis in investment projects, namely: the “Project analysis scenario” flowchart, improving quality and reliability of forecasting reports in investment projects; the main stages of cash flow adjustment based on risk mapping for better cost-benefit project analysis provided the broad range of risks in high-rise construction; analysis of dynamic cost-benefit values considering project sensitivity to crucial variables, improving flexibility in implementation of high-rise projects.

  11. Improvement of the cost-benefit analysis algorithm for high-rise construction projects

    Science.gov (United States)

    Gafurov, Andrey; Skotarenko, Oksana; Plotnikov, Vladimir

    2018-03-01

    The specific nature of high-rise investment projects entailing long-term construction, high risks, etc. implies a need to improve the standard algorithm of cost-benefit analysis. An improved algorithm is described in the article. For development of the improved algorithm of cost-benefit analysis for high-rise construction projects, the following methods were used: weighted average cost of capital, dynamic cost-benefit analysis of investment projects, risk mapping, scenario analysis, sensitivity analysis of critical ratios, etc. This comprehensive approach helped to adapt the original algorithm to feasibility objectives in high-rise construction. The authors put together the algorithm of cost-benefit analysis for high-rise construction projects on the basis of risk mapping and sensitivity analysis of critical ratios. The suggested project risk management algorithms greatly expand the standard algorithm of cost-benefit analysis in investment projects, namely: the "Project analysis scenario" flowchart, improving quality and reliability of forecasting reports in investment projects; the main stages of cash flow adjustment based on risk mapping for better cost-benefit project analysis provided the broad range of risks in high-rise construction; analysis of dynamic cost-benefit values considering project sensitivity to crucial variables, improving flexibility in implementation of high-rise projects.

  12. Extraction behaviour of Am(III) and Eu(III) from nitric acid medium in CMPO-HDEHP impregnated resins

    Energy Technology Data Exchange (ETDEWEB)

    Saipriya, K.; Kumar, T. [Bhabha Atomic Research Centre Facilities (India). Kalpakkam Reproscessing Plants; Kumaresan, R.; Nayak, P.K.; Venkatesan, K.A.; Antony, M.P. [Indira Gandhi Center for Atomic Research, Kalpakkam (India). Fuel Chemistry Div.

    2016-05-01

    Chromatographic resin containing extractants such as octyl(phenyl)-N,N-diisobutylcarbamoylmethylphosphine oxide (CMPO) or bis-(2-ethylhexyl)phosphoric acid (HDEHP) or mixture of extractants (CMPO + HDEHP) in an acrylic polymer matrix was prepared and studied for the extraction of Am(III) and Eu(III) over a range of nitric acid concentration. The effect of various parameters such as concentration of nitric acid in aqueous phase and the concentration of CMPO and HDEHP in the resin phase was studied. The distribution coefficient of Am(III) and Eu(III) in the impregnated resin increased with increased in the concentration of nitric acid for CMPO-impregnated resin, whereas a reverse trend was observed in HDEHP impregnated resin. In case of resin containing both the extractants, synergism was observed at low nitric acid concentration and antagonism at high nitric acid concentration. The mechanism of extraction was probed by slope analysis method at 0.01 and 2 M nitric acid concentrations. Citrate-buffered DTPA was used for the selective separation of Am(III), and a separation factor of 3-4 was obtained at pH 3.

  13. Rape embryogenesis. III. Embryo development in time

    Directory of Open Access Journals (Sweden)

    Teresa Tykarska

    2014-01-01

    Full Text Available It was found that the growth curve of the rape embryo axis is of triple sigmoid type. Embryo growth occurs in 3 phases corresponding to 3 different periods of development. Phase I includes growth of the apical cell up to it's division into two layers of octants. Phase II comprises the increase of the spherical proembryo to the change of its symmetry from radial to bilateral. Phase III includes, growth of the embryo from the heart stage up to the end of embryogenesis. In each phase the relative growth rate increases drastically and then diminishes. The differences in growth intensity during the same phase are several-fold. The growth intensity maximum of the embryo axis occurs in phase II. The phasic growth intensity maxima occur: in phase I during apical cell elongation, :before its division, and in phases II and III in the periods of cell division ;growth in globular and torpedo-shaped -shaped embryos.

  14. Improving Mixed-phase Cloud Parameterization in Climate Model with the ACRF Measurements

    Energy Technology Data Exchange (ETDEWEB)

    Wang, Zhien [Univ. of Wyoming, Laramie, WY (United States)

    2016-12-13

    Mixed-phase cloud microphysical and dynamical processes are still poorly understood, and their representation in GCMs is a major source of uncertainties in overall cloud feedback in GCMs. Thus improving mixed-phase cloud parameterizations in climate models is critical to reducing the climate forecast uncertainties. This study aims at providing improved knowledge of mixed-phase cloud properties from the long-term ACRF observations and improving mixed-phase clouds simulations in the NCAR Community Atmosphere Model version 5 (CAM5). The key accomplishments are: 1) An improved retrieval algorithm was developed to provide liquid droplet concentration for drizzling or mixed-phase stratiform clouds. 2) A new ice concentration retrieval algorithm for stratiform mixed-phase clouds was developed. 3) A strong seasonal aerosol impact on ice generation in Arctic mixed-phase clouds was identified, which is mainly attributed to the high dust occurrence during the spring season. 4) A suite of multi-senor algorithms was applied to long-term ARM observations at the Barrow site to provide a complete dataset (LWC and effective radius profile for liquid phase, and IWC, Dge profiles and ice concentration for ice phase) to characterize Arctic stratiform mixed-phase clouds. This multi-year stratiform mixed-phase cloud dataset provides necessary information to study related processes, evaluate model stratiform mixed-phase cloud simulations, and improve model stratiform mixed-phase cloud parameterization. 5). A new in situ data analysis method was developed to quantify liquid mass partition in convective mixed-phase clouds. For the first time, we reliably compared liquid mass partitions in stratiform and convective mixed-phase clouds. Due to the different dynamics in stratiform and convective mixed-phase clouds, the temperature dependencies of liquid mass partitions are significantly different due to much higher ice concentrations in convective mixed phase clouds. 6) Systematic evaluations

  15. Phase matching in quantum searching and the improved Grover algorithm

    International Nuclear Information System (INIS)

    Long Guilu; Li Yansong; Xiao Li; Tu Changcun; Sun Yang

    2004-01-01

    The authors briefly introduced some of our recent work related to the phase matching condition in quantum searching algorithms and the improved Grover algorithm. When one replaces the two phase inversions in the Grover algorithm with arbitrary phase rotations, the modified algorithm usually fails in searching the marked state unless a phase matching condition is satisfied between the two phases. the Grover algorithm is not 100% in success rate, an improved Grover algorithm with zero-failure rate is given by replacing the phase inversions with angles that depends on the size of the database. Other aspects of the Grover algorithm such as the SO(3) picture of quantum searching, the dominant gate imperfections in the Grover algorithm are also mentioned. (author)

  16. DECOVALEX III PROJECT. Mathematical Models of Coupled Thermal-Hydro-Mechanical Processes for Nuclear Waste Repositories. Executive Summary

    Energy Technology Data Exchange (ETDEWEB)

    Jing, L.; Stephansson, O. [Royal Inst. of Technology, Stockholm (Sweden). Engineering Geology; Tsang, C.F. [Lawrence Berkely National Laboratory, Berkeley, CA (United States). Earth Science Div.; Mayor, J.C. [ENRESA, Madrid (Spain); Kautzky, F. [Swedish Nuclear Power Inspectorate, Stockholm (Sweden)] (eds.)

    2005-02-15

    DECOVALEX is an international consortium of governmental agencies associated with the disposal of high-level nuclear waste in a number of countries. The consortium's mission is the DEvelopment of COupled models and their VALidation against EXperiments. Hence the acronym/name DECOVALEX. Currently, agencies from Canada, Finland, France, Germany, Japan, Spain, Switzerland, Sweden, United Kingdom, and the United States are in DECOVALEX. Emplacement of nuclear waste in a repository in geologic media causes a number of physical processes to be intensified in the surrounding rock mass due to the decay heat from the waste. The four main processes of concern are thermal, hydrological, mechanical and chemical. Interactions or coupling between these heat-driven processes must be taken into account in modeling the performance of the repository for such modeling to be meaningful and reliable. DECOVALEX III is organized around four tasks. The FEBEX (Full-scale Engineered Barriers EXperiment) in situ experiment being conducted at the Grimsel site in Switzerland is to be simulated and analyzed in Task 1. Task 2, centered around the Drift Scale Test (DST) at Yucca Mountain in Nevada, USA, has several sub-tasks (Task 2A, Task 2B, Task 2C and Task 2D) to investigate a number of the coupled processes in the DST. Task 3 studies three benchmark problems: a) the effects of thermal-hydrologic-mechanical (THM) coupling on the performance of the near-field of a nuclear waste repository (BMT1); b) the effect of upscaling THM processes on the results of performance assessment (BMT2); and c) the effect of glaciation on rock mass behavior (BMT3). Task 4 is on the direct application of THM coupled process modeling in the performance assessment of nuclear waste repositories in geologic media. This executive summary presents the motivation, structure, objectives, approaches, and the highlights of the main achievements and outstanding issues of the tasks studied in the DECOVALEX III project

  17. DECOVALEX III PROJECT. Mathematical Models of Coupled Thermal-Hydro-Mechanical Processes for Nuclear Waste Repositories. Executive Summary

    International Nuclear Information System (INIS)

    Jing, L.; Stephansson, O.; Kautzky, F.

    2005-02-01

    DECOVALEX is an international consortium of governmental agencies associated with the disposal of high-level nuclear waste in a number of countries. The consortium's mission is the DEvelopment of COupled models and their VALidation against EXperiments. Hence the acronym/name DECOVALEX. Currently, agencies from Canada, Finland, France, Germany, Japan, Spain, Switzerland, Sweden, United Kingdom, and the United States are in DECOVALEX. Emplacement of nuclear waste in a repository in geologic media causes a number of physical processes to be intensified in the surrounding rock mass due to the decay heat from the waste. The four main processes of concern are thermal, hydrological, mechanical and chemical. Interactions or coupling between these heat-driven processes must be taken into account in modeling the performance of the repository for such modeling to be meaningful and reliable. DECOVALEX III is organized around four tasks. The FEBEX (Full-scale Engineered Barriers EXperiment) in situ experiment being conducted at the Grimsel site in Switzerland is to be simulated and analyzed in Task 1. Task 2, centered around the Drift Scale Test (DST) at Yucca Mountain in Nevada, USA, has several sub-tasks (Task 2A, Task 2B, Task 2C and Task 2D) to investigate a number of the coupled processes in the DST. Task 3 studies three benchmark problems: a) the effects of thermal-hydrologic-mechanical (THM) coupling on the performance of the near-field of a nuclear waste repository (BMT1); b) the effect of upscaling THM processes on the results of performance assessment (BMT2); and c) the effect of glaciation on rock mass behavior (BMT3). Task 4 is on the direct application of THM coupled process modeling in the performance assessment of nuclear waste repositories in geologic media. This executive summary presents the motivation, structure, objectives, approaches, and the highlights of the main achievements and outstanding issues of the tasks studied in the DECOVALEX III project. The

  18. Collection of URL measurement data in 2010 fiscal year at the Horonobe Underground Research Laboratory project

    International Nuclear Information System (INIS)

    Inagaki, Daisuke; Sawada, Sumiyuki; Tokiwa, Tetsuya; Tsusaka, Kimikazu; Amano, Yuki; Niinuma, Hiroaki

    2012-09-01

    The Horonobe Underground Research Laboratory (URL) Project has being pursued by the Japan Atomic Energy Agency (JAEA) to enhance the reliability of relevant disposal technologies through investigations of the deep geological environment within the host sedimentary formations at Horonobe, northern Hokkaido. The URL project consists of two major research areas, 'Geoscientific Research' and 'R and D on Geological Disposal Technologies', and proceeds in three overlapping phases, 'Phase I: Surface-based investigations', 'Phase II: Investigations during tunnel excavation' and 'Phase III: Investigations in the underground facilities', over a period of around 20 years. The Phase I geoscientific research was carried out from March 2001 to March 2006 in parallel with design and execution scheme on URL facilities. In addition, identifying key issues that need to be addressed in the Phase II/III investigations was planned. At the begining of the Phase II investigations, an investigation report titled 'Measurement Plan and Observational Construction Program on Shaft Excavation at the Horonobe Underground Research Laboratory Project' (hereinafter referred to as 'Observational Construction Program') and an investigation report titled 'Measurement Plan and Observational Construction Program on Drift Excavation at the Horonobe Underground Research Laboratory Project' were published. The Observational Construction Program summarizes the followings from the results of the Phase I investigations: measurements for safety and reasonable constructions, enhancement of shaft design and construction technologies and evaluation of appropriateness for the deep geological environment model estimated before shaft excavation. This report summarizes the measurements data acquired at the Ventilation Shaft, the East Shaft and the drifts in 2010 fiscal year based on the Observational Construction Program. The report summarizes the measurements data for the purpose of acquisition the basic data for

  19. Collection of URL measurement data in 2011 fiscal year at the Horonobe Underground Research Laboratory project

    International Nuclear Information System (INIS)

    Inagaki, Daisuke; Tokiwa, Tetsuya; Murakami, Hiroaki

    2013-02-01

    The Horonobe Underground Research Laboratory (URL) Project has being pursued by the Japan Atomic Energy Agency (JAEA) to enhance the reliability of relevant disposal technologies through investigations of the deep geological environment within the host sedimentary formations at Horonobe, northern Hokkaido. The URL project consists of two major research areas, 'Geoscientific Research' and 'R and D on Geological Disposal Technologies', and proceeds in three overlapping phases, 'Phase I: Surface-based investigations', 'Phase II: Investigations during tunnel excavation' and 'Phase III: Investigations in the underground facilities', over a period of around 20 years. The Phase I geoscientific research was carried out from March 2001 to March 2006 in parallel with design and execution scheme on URL facilities. In addition, identifying key issues that need to be addressed in the Phase II/III investigations was planned. At the beginning of the Phase II investigations, an investigation report titled 'Measurement Plan and Observational Construction Program on Shaft Excavation at the Horonobe Underground Research Laboratory Project' (hereinafter referred to as 'Observational Construction Program') and an investigation report titled 'Measurement Plan and Observational Construction Program on Drift Excavation at the Horonobe Underground Research Laboratory Project' were published. The Observational Construction Program summarizes the followings from the results of the Phase I investigations: measurements for safety and reasonable constructions, enhancement of shaft design and construction technologies and evaluation of appropriateness for the deep geological environment model estimated before shaft excavation. This report summarizes the measurements data acquired at the Ventilation Shaft, the East Shaft and the drifts in 2011 fiscal year based on the Observational Construction Program. The report summarizes the measurements data for the purpose of acquisition the basic data for

  20. Current and evolving approaches for improving the oral permeability of BCS Class III or analogous molecules.

    Science.gov (United States)

    Dave, Vivek S; Gupta, Deepak; Yu, Monica; Nguyen, Phuong; Varghese Gupta, Sheeba

    2017-02-01

    The Biopharmaceutics Classification System (BCS) classifies pharmaceutical compounds based on their aqueous solubility and intestinal permeability. The BCS Class III compounds are hydrophilic molecules (high aqueous solubility) with low permeability across the biological membranes. While these compounds are pharmacologically effective, poor absorption due to low permeability becomes the rate-limiting step in achieving adequate bioavailability. Several approaches have been explored and utilized for improving the permeability profiles of these compounds. The approaches include traditional methods such as prodrugs, permeation enhancers, ion-pairing, etc., as well as relatively modern approaches such as nanoencapsulation and nanosizing. The most recent approaches include a combination/hybridization of one or more traditional approaches to improve drug permeability. While some of these approaches have been extremely successful, i.e. drug products utilizing the approach have progressed through the USFDA approval for marketing; others require further investigation to be applicable. This article discusses the commonly studied approaches for improving the permeability of BCS Class III compounds.

  1. Establishing a portfolio of quality-improvement projects in pediatric surgery through advanced improvement leadership systems.

    Science.gov (United States)

    Gerrein, Betsy T; Williams, Christina E; Von Allmen, Daniel

    2013-01-01

    Formal quality-improvement (QI) projects require that participants are educated in QI methods to provide them with the capability to carry out successful, meaningful work. However, orchestrating a portfolio of projects that addresses the strategic mission of the institution requires an extension of basic QI training to provide the division or business unit with the capacity to successfully develop and manage the portfolio. Advanced Improvement Leadership Systems is a program to help units create a meaningful portfolio. This program, used by the Division of Pediatric General and Thoracic Surgery at Cincinnati Children's Hospital Medical Center, helped establish a portfolio of targeted QI projects designed to achieve outstanding outcomes at competitive costs in multiple clinical areas aligned with the institution's strategic goals (improve disease-based outcomes, patient safety, flow, and patient and family experience). These objectives are addressed in an institutional strategic plan built around 5 core areas: Safety, Productivity, Care Coordination and Outcomes, Patient and Family Experience, and Value. By combining the portfolio of QI projects with improvements in the divisional infrastructure, effective improvement efforts were realized throughout the division. In the 9 months following the program, divisional capability resulted in a 16.5% increase (5.7% to 22.2%) of formally trained staff working on 10 QI teams. Concurrently, a leadership team, designed to coordinate projects, remove barriers, and provide technical support, provided the capacity to pursue this ongoing effort. The Advanced Improvement Leadership Systems program increased the Division's efficiency and effectiveness in pursing the QI mission that is integral at our hospital.

  2. Establishing a Portfolio of Quality-Improvement Projects in Pediatric Surgery through Advanced Improvement Leadership Systems

    Science.gov (United States)

    Gerrein, Betsy T; Williams, Christina E; von Allmen, Daniel

    2013-01-01

    Formal quality-improvement (QI) projects require that participants are educated in QI methods to provide them with the capability to carry out successful, meaningful work. However, orchestrating a portfolio of projects that addresses the strategic mission of the institution requires an extension of basic QI training to provide the division or business unit with the capacity to successfully develop and manage the portfolio. Advanced Improvement Leadership Systems is a program to help units create a meaningful portfolio. This program, used by the Division of Pediatric General and Thoracic Surgery at Cincinnati Children’s Hospital Medical Center, helped establish a portfolio of targeted QI projects designed to achieve outstanding outcomes at competitive costs in multiple clinical areas aligned with the institution’s strategic goals (improve disease-based outcomes, patient safety, flow, and patient and family experience). These objectives are addressed in an institutional strategic plan built around 5 core areas: Safety, Productivity, Care Coordination and Outcomes, Patient and Family Experience, and Value. By combining the portfolio of QI projects with improvements in the divisional infrastructure, effective improvement efforts were realized throughout the division. In the 9 months following the program, divisional capability resulted in a 16.5% increase (5.7% to 22.2%) of formally trained staff working on 10 QI teams. Concurrently, a leadership team, designed to coordinate projects, remove barriers, and provide technical support, provided the capacity to pursue this ongoing effort. The Advanced Improvement Leadership Systems program increased the Division’s efficiency and effectiveness in pursing the QI mission that is integral at our hospital. PMID:24361020

  3. Enhanced FAA-hybrid III numerical dummy model in Madymo for aircraft occupant safety assessment

    NARCIS (Netherlands)

    Boucher, H.; Waagmeester, C.D.

    2003-01-01

    To improve survivability and to minimize the risk of injury to occupants in helicopter crash events, a complete Cabin Safety System concept including safety features and an enhanced FAA-Hybrid III dummy were developed within the HeliSafe project. A numerical tool was also created and validated to

  4. Phase I/II study of gefitinib (Iressa(®)) and vorinostat (IVORI) in previously treated patients with advanced non-small cell lung cancer.

    Science.gov (United States)

    Han, Ji-Youn; Lee, Soo Hyun; Lee, Geon Kook; Yun, Tak; Lee, Young Joo; Hwang, Kum Hui; Kim, Jin Young; Kim, Heung Tae

    2015-03-01

    Vorinostat has been shown to overcome resistance to gefitinib. We performed a phase I/II study combining gefitinib with vorinostat in previously treated non-small cell lung cancer (NSCLC). A 3 + 3 dose-escalation design was used to determine maximum tolerated dose (MTD) and recommended phase II dose (RP2D). Three dose levels were tested: 250 mg/day gefitinib on days 1-28 and 200, 300 or 400 mg/day vorinostat on days 1-7, and 15-21 out of every 28 days. The primary endpoint was median progression-free survival (PFS). Fifty-two patients were enrolled and treated (43 in phase II). The median age was 59 years, 28 patients were male, 44 had adenocarcinoma, 29 had never smoked, and 36 had undergone one prior treatment. Twenty-two patients exhibited sensitive EGFR mutations. Planned dose escalation was completed without reaching the MTD. The RP2D was 250 mg gefitinib and 400 mg vorinostat. In 43 assessable patients in phase II, the median PFS was 3.2 months; the overall survival (OS) was 19.0 months. There were 16 partial responses and six cases of stable disease. In EGFR-mutant NSCLC, response rate was 77 %, median PFS was 9.1 months, and median OS was 24.1 months. The most common adverse events were anorexia and diarrhea. Treatment with 250 mg gefitinib daily with biweekly 400 mg/day vorinostat was feasible and well tolerated. In an unselected patient population, this combination dose did not improve PFS. However, this combination showed a potential for improving efficacy of gefitinib in EGFR-mutant NSCLC (NCT01027676).

  5. Application of Advanced Reservoir Characterization, Simulation, and Production Optimization Strategies to Maximize Recovery in Slope and Basin Clastic Reservoirs, West Texas (Delaware Basin), Class III

    Energy Technology Data Exchange (ETDEWEB)

    Dutton, Shirley P.; Flanders, William A.

    2001-11-04

    The objective of this Class III project was demonstrate that reservoir characterization and enhanced oil recovery (EOR) by CO2 flood can increase production from slope and basin clastic reservoirs in sandstones of the Delaware Mountain Group in the Delaware Basin of West Texas and New Mexico. Phase 1 of the project, reservoir characterization, focused on Geraldine Ford and East Ford fields, which are Delaware Mountain Group fields that produce from the upper Bell Canyon Formation (Ramsey sandstone). The demonstration phase of the project was a CO2 flood conducted in East Ford field, which is operated by Orla Petco, Inc., as the East Ford unit.

  6. Bragg projection ptychography on niobium phase domains

    Science.gov (United States)

    Burdet, Nicolas; Shi, Xiaowen; Clark, Jesse N.; Huang, Xiaojing; Harder, Ross; Robinson, Ian

    2017-07-01

    Bragg projection ptychography (BPP) is a coherent x-ray diffraction imaging technique which combines the strengths of scanning microscopy with the phase contrast of x-ray ptychography. Here we apply it for high resolution imaging of the phase-shifted crystalline domains associated with epitaxial growth. The advantages of BPP are that the spatial extent of the sample is arbitrary, it is nondestructive, and it gives potentially diffraction limited spatial resolution. Here we demonstrate the application of BPP for revealing the domain structure caused by epitaxial misfit in a nanostructured metallic thin film. Experimental coherent diffraction data were collected from a niobium thin film, epitaxially grown on a sapphire substrate as the beam was scanned across the sample. The data were analyzed by BPP using a carefully selected combination of refinement procedures. The resulting image shows a close packed array of epitaxial domains, shifted with respect to each other due to misfit between the film and its substrate.

  7. Outcome for stage II and III rectal and colon cancer equally good after treatment improvement over three decades.

    Science.gov (United States)

    Fischer, Joern; Joern, Fischer; Hellmich, Gunter; Gunter, Hellmich; Jackisch, Thomas; Thomas, Jackisch; Puffer, Erik; Erik, Puffer; Zimmer, Jörg; Jörg, Zimmer; Bleyl, Dorothea; Dorothea, Bleyl; Kittner, Thomas; Thomas, Kittner; Witzigmann, Helmut; Helmut, Witzigmann; Stelzner, Sigmar; Sigmar, Stelzner

    2015-06-01

    This study aimed to investigate the outcome for stage II and III rectal cancer patients compared to stage II and III colonic cancer patients with regard to 5-year cause-specific survival (CSS), overall survival, and local and combined recurrence rates over time. This prospective cohort study identified 3,355 consecutive patients with adenocarcinoma of the colon or rectum and treated in our colorectal unit between 1981 and 2011, for investigation. The study was restricted to International Union Against Cancer (UICC) stages II and III. Postoperative mortality and histological incomplete resection were excluded, which left 995 patients with colonic cancer and 726 patients with rectal cancer for further analysis. Five-year CSS rates improved for colonic cancer from 65.0% for patients treated between 1981 and 1986 to 88.1% for patients treated between 2007 and 2011. For rectal cancer patients, the respective 5-year CSS rates improved from 53.4% in the first observation period to 89.8% in the second one. The local recurrence rate for rectal cancer dropped from 34.2% in the years 1981-1986 to 2.1% in the years 2007-2011. In the last decade of observation, prognosis for rectal cancer was equal to that for colon cancer (CSS 88.6 vs. 86.7%, p = 0.409). Survival of patients with colon and rectal cancer has continued to improve over the last three decades. After major changes in treatment strategy including introduction of total mesorectal excision and neoadjuvant (radio)chemotherapy, prognosis for stage II and III rectal cancer is at least as good as for stage II and III colonic cancer.

  8. Improved detection of hydrophilic phosphopeptides using graphite powder microcolumns and mass spectrometry: evidence for in vivo doubly phosphorylated dynamin I and dynamin III

    DEFF Research Database (Denmark)

    Larsen, Martin Røssel; Graham, Mark E; Robinson, Phillip J

    2004-01-01

    A common strategy in proteomics to improve the number and quality of peptides detected by mass spectrometry (MS) is to desalt and concentrate proteolytic digests using reversed phase (RP) chromatography prior to analysis. However, this does not allow for detection of small or hydrophilic peptides...... a large improvement in the detection of small amounts of phosphopeptides by MS and the approach has major implications for both small- and large-scale projects in phosphoproteomics.......A common strategy in proteomics to improve the number and quality of peptides detected by mass spectrometry (MS) is to desalt and concentrate proteolytic digests using reversed phase (RP) chromatography prior to analysis. However, this does not allow for detection of small or hydrophilic peptides......, or peptides altered in hydrophilicity such as phosphopeptides. We used microcolumns to compare the ability of RP resin or graphite powder to retain phosphopeptides. A number of standard phosphopeptides and a biologically relevant phosphoprotein, dynamin I, were analyzed. MS revealed that some phosphopeptides...

  9. Functional design criteria for project W-252, phase II liquid effluent treatment and disposal. Revision 2

    International Nuclear Information System (INIS)

    Hatch, C.E.

    1995-05-01

    This document is the Functional Design Criteria for Project W-252. Project W-252 provides the scope to provide BAT/AKART (best available technology...) to 200 Liquid Effluent Phase II streams (B-Plant). This revision (Rev. 2) incorporates a major descoping of the project. The descoping was done to reflect a combination of budget cutting measures allowed by a less stringent regulatory posture toward the Phase II streams

  10. Prospective trial of angiography and embolization for all grade III to V blunt splenic injuries: nonoperative management success rate is significantly improved.

    Science.gov (United States)

    Miller, Preston R; Chang, Michael C; Hoth, J Jason; Mowery, Nathan T; Hildreth, Amy N; Martin, R Shayn; Holmes, James H; Meredith, J Wayne; Requarth, Jay A

    2014-04-01

    Nonoperative management (NOM) of blunt splenic injury is well accepted. Substantial failure rates in higher injury grades remain common, with one large study reporting rates of 19.6%, 33.3%, and 75% for grades III, IV, and V, respectively. Retrospective data show angiography and embolization can increase salvage rates in these severe injuries. We developed a protocol requiring referral of all blunt splenic injuries, grades III to V, without indication for immediate operation for angiography and embolization. We hypothesized that angiography and embolization of high-grade blunt splenic injury would reduce NOM failure rates in this population. This was a prospective study at our Level I trauma center as part of a performance-improvement project. Demographics, injury characteristics, and outcomes were compared with historic controls. The protocol required all stable patients with grade III to V splenic injuries be referred for angiography and embolization. In historic controls, referral was based on surgeon preference. From January 1, 2010 to December 31, 2012, there were 168 patients with grades III to V spleen injuries admitted; NOM was undertaken in 113 (67%) patients. The protocol was followed in 97 patients, with a failure rate of 5%. Failure rate in the 16 protocol deviations was 25% (p = 0.02). Historic controls from January 1, 2007 to December 31, 2009 were compared with the protocol group. One hundred and fifty-three patients with grade III to V injuries were admitted during this period, 80 (52%) patients underwent attempted NOM. Failure rate was significantly higher than for the protocol group (15%, p = 0.04). Use of a protocol requiring angiography and embolization for all high-grade spleen injuries slated for NOM leads to a significantly decreased failure rate. We recommend angiography and embolization as an adjunct to NOM for all grade III to V splenic injuries. Copyright © 2014 American College of Surgeons. Published by Elsevier Inc. All rights reserved.

  11. The modification of main steam safety valves in Qinshan phase Ⅱ expansion project

    International Nuclear Information System (INIS)

    Chen Haiqiao

    2012-01-01

    The main steam safety valves of NPP steam system are second- class nuclear safety component. It used to limit the pressure of SG secondary side and main steam system via emitting steam into the environment. At present, the main steam safety valves have mechanical valves and assisted power valves. According to the experience of power plants at home and abroad, including Qinshan Phase Ⅱ unit 1/2 experience feedback, Qinshan Phase Ⅱ expansion project made modification on valve type, setting value and valve body. This paper introduce the characteristics of different safety valve types, the modification of main steam safety valves and the modification analysis on safety issues.security and impact on the other systems in Qinshan Phase Ⅱ expansion project. (author)

  12. NOVEL CONCEPTS RESEARCH IN GEOLOGIC STORAGE OF CO2 PHASE III

    Energy Technology Data Exchange (ETDEWEB)

    Neeraj Gupta

    2006-01-23

    As part of the Department of Energy's (DOE) initiative on developing new technologies for storage of carbon dioxide in geologic reservoirs, Battelle has been investigating the feasibility of CO{sub 2} sequestration in the deep saline reservoirs in the Ohio River Valley region. In addition to the DOE, the project is being sponsored by American Electric Power (AEP), BP, The Ohio Coal Development Office (OCDO) of the Ohio Air Quality Development Authority, Schlumberger, and Battelle. The main objective of the project is to demonstrate that CO{sub 2} sequestration in deep formations is feasible from engineering and economic perspectives, as well as being an inherently safe practice and one that will be acceptable to the public. In addition, the project is designed to evaluate the geology of deep formations in the Ohio River Valley region in general and in the vicinity of AEP's Mountaineer Power Plant in particular, in order to determine their potential use for conducting a long-term test of CO{sub 2} disposal in deep saline formations. The current technical progress report summarizes activities completed for the October through December 2005 period of the project. As discussed in the following report, the main field activity was reservoir testing in the Copper Ridge ''B-zone'' in the AEP No.1 well. In addition reservoir simulations were completed to assess feasibility of CO{sub 2} injection for the Mountaineer site. These reservoir testing and computer simulation results suggest that injection potential may be substantially more than anticipated for the Mountaineer site. Work also continued on development of injection well design options, engineering assessment of CO{sub 2} capture systems, permitting, and assessment of monitoring technologies as they apply to the project site. Overall, the current design feasibility phase project is proceeding according to plans.

  13. Planning and reporting of Russian transmutation research projects within ISTC. Phase 2

    Energy Technology Data Exchange (ETDEWEB)

    Conde, H. [Uppsala Univ. (Sweden). Dept. of Neutron Research; Gudowski, W. [Royal Inst. of Tech., Stockholm (Sweden). Dept. of Reactor and Neutron Physics; Liljenzin, J.O. [Chalmers Univ. of Technology, Goeteborg (Sweden). Dept. of Nuclear Chemistry; Mileikovsky, C. [Pully (Switzerland)

    1998-11-01

    The present report about phase 2 of the SKI project on Planning and Reporting of Russian Transmutation Research Projects within ISTC is an update of the information given in the SKI report no 97:15 (Feb 1997) about phase 1 of the same project. The background information is partly repeated in the present report to avoid that the reader has to go back to the report of Phase 1 for information about the basis for the project. USA, EU, Japan, Republic of Korea and Norway are at present supporting the International Scientific and Technical Center (ISTC) in Moscow. The Centre gives funds to research projects of civilian interest to former nuclear weapon laboratories to counteract the risk of nuclear weapon proliferation by the emigration of former USSR technical and scientific experts to `border countries` which are aiming towards the development of nuclear weapons. Before Sweden and Finland entered the EU, both countries gave national support to ISTC, in the case of Sweden 4 MUSD. Some of the projects which were funded by the Swedish national support to ISTC are still in progress. Nuclear technical concepts (i.e. Accelerator Transmutation of Nuclear Waste, ATW) have been proposed to incinerate and transmute long-lived radioactive nuclear waste to relax the time needed to store the waste in a geological repository. The named Russian experts are knowledgeable and well equipped of doing research in the different technical fields of relevance for the transmutation concepts. Thus, a number of ISTC projects have been initiated, and further ones have been proposed, to investigate different technical aspects of ATW with a result that a fair number of former weapon specialists have converted from military to peaceful civilian research. A similar centre STCU (The Scientific and Technical Centre of the Ukraine) has been set up in Kiev. Sweden has been active in promoting this Centre, which is supported by USA, Japan, Canada and recently also by EU. The present report describes the

  14. Planning and reporting of Russian transmutation research projects within ISTC. Phase 2

    International Nuclear Information System (INIS)

    Conde, H.

    1998-11-01

    The present report about phase 2 of the SKI project on Planning and Reporting of Russian Transmutation Research Projects within ISTC is an update of the information given in the SKI report no 97:15 (Feb 1997) about phase 1 of the same project. The background information is partly repeated in the present report to avoid that the reader has to go back to the report of Phase 1 for information about the basis for the project. USA, EU, Japan, Republic of Korea and Norway are at present supporting the International Scientific and Technical Center (ISTC) in Moscow. The Centre gives funds to research projects of civilian interest to former nuclear weapon laboratories to counteract the risk of nuclear weapon proliferation by the emigration of former USSR technical and scientific experts to 'border countries' which are aiming towards the development of nuclear weapons. Before Sweden and Finland entered the EU, both countries gave national support to ISTC, in the case of Sweden 4 MUSD. Some of the projects which were funded by the Swedish national support to ISTC are still in progress. Nuclear technical concepts (i.e. Accelerator Transmutation of Nuclear Waste, ATW) have been proposed to incinerate and transmute long-lived radioactive nuclear waste to relax the time needed to store the waste in a geological repository. The named Russian experts are knowledgeable and well equipped of doing research in the different technical fields of relevance for the transmutation concepts. Thus, a number of ISTC projects have been initiated, and further ones have been proposed, to investigate different technical aspects of ATW with a result that a fair number of former weapon specialists have converted from military to peaceful civilian research. A similar centre STCU (The Scientific and Technical Centre of the Ukraine) has been set up in Kiev. Sweden has been active in promoting this Centre, which is supported by USA, Japan, Canada and recently also by EU. The present report describes the

  15. Investor Outlook: Significance of the Positive LCA2 Gene Therapy Phase III Results.

    Science.gov (United States)

    Schimmer, Joshua; Breazzano, Steven

    2015-12-01

    Spark Therapeutics recently reported positive phase III results for SPK-RPE65 targeting the treatment of visual impairment caused by RPE65 gene mutations (often referred to as Leber congenital amaurosis type 2, or LCA2, but may include other retinal disorders), marking an important inflection point for the field of gene therapy. The results highlight the ability to successfully design and execute a randomized trial of a gene therapy and also reinforce the potentially predictive nature of early preclinical and clinical data. The results are expected to pave the way for the first approved gene therapy product in the United States and should sustain investor interest and confidence in gene therapy for many approaches, including retina targeting and beyond.

  16. A randomized placebo-controlled phase III trial of oral laquinimod for multiple sclerosis

    DEFF Research Database (Denmark)

    Vollmer, T L; Sorensen, P S; Selmaj, K

    2014-01-01

    The phase III placebo-controlled BRAVO study assessed laquinimod effects in patients with relapsing-remitting MS (RRMS), and descriptively compared laquinimod with interferon beta (IFNβ)-1a (Avonex(®) reference arm). RRMS patients age 18-55 years with Expanded Disability Status Scale (EDSS) scores...... months. The primary endpoint was annualized relapse rate (ARR); secondary endpoints included percent brain volume change (PBVC) and 3-month confirmed disability worsening. In all, 1,331 patients were randomized: laquinimod (n = 434), placebo (n = 450), and IFNβ-1a (n = 447). ARR was not significantly...... reduced with laquinimod [-18 %, risk ratio (RR) = 0.82, 95 % CI 0.66-1.02; p = 0.075] vs. placebo. Laquinimod significantly reduced PBVC (28 %, p change in confirmed disability worsening with laquinimod measured...

  17. The Effects of PECS Teaching to Phase III on the Communicative Interactions between Children with Autism and Their Teachers

    Science.gov (United States)

    Carr, Deborah; Felce, Janet

    2007-01-01

    The study investigated the impact of mastery of the Picture Exchange Communication System (PECS) to Phase III, on the communications of children with autism. Children aged between 3 and 7 years, formed a PECS intervention group and a non-intervention control group. The intervention group received 15 h of PECS teaching over 5 weeks. Three 2-h…

  18. Interstate Electrification Improvement Project

    Energy Technology Data Exchange (ETDEWEB)

    Puckette, Margaret [Shorepower Technologies, Hillsboro, OR (United States); Kim, Jeff [Shorepower Technologies, Hillsboro, OR (United States)

    2015-07-01

    The Interstate Electrification Improvement Project, publicly known as the Shorepower Truck Electrification Project (STEP), started in May 2011 and ended in March 2015. The project grant was awarded by the Department of Energy’s Vehicles Technology Office in the amount of $22.2 million. It had three overarching missions: 1. Reduce the idling of Class 8 tractors when parked at truck stops, to reduce diesel fuel consumption and thus U.S. dependence on foreign petroleum; 2. Stimulate job creation and economic activity as part of the American Reinvestment and Recovery Act of 2009; 3. Reduce greenhouse gas emissions (GHG) from diesel combustion and the carbon footprint of the truck transportation industry. The project design was straightforward. First, build fifty Truck Stop Electrification (TSE) facilities in truck stop parking lots across the country so trucks could plug-in to 110V, 220V, or 480VAC, and shut down the engine instead of idling. These facilities were strategically located at fifty truck stops along major U.S. Interstates with heavy truck traffic. Approximately 1,350 connection points were installed, including 150 high-voltage electric standby Transport Refrigeration Unit (eTRU) plugs--eTRUs are capable of plugging in to shore power1 to cool the refrigerated trailer for loads such as produce, meats and ice cream. Second, the project provided financial incentives on idle reduction equipment to 5,000 trucks in the form of rebates, to install equipment compatible with shore power. This equipment enables drivers to shut down the main engine when parked, to heat or cool their cab, charge batteries, or use other household appliances without idling—a common practice that uses approximately 1 gallon of diesel per hour. The rebate recipients were intended to be the first fleets to plug into Shorepower to save diesel fuel and ensure there is significant population of shore power capable trucks. This two part project was designed to complement each other by

  19. Phenomenology of Polymorphism, III: p, TDiagram and Stability of Piracetam Polymorphs

    Science.gov (United States)

    Céolin, R.; Agafonov, V.; Louër, D.; Dzyabchenko, V. A.; Toscani, S.; Cense, J. M.

    1996-02-01

    The nootropic drug Piracetam is known to crystallize in three phases. In order to obtain their stability hierarchy from sublimation pressure inequalities, the drawing of a topologicalp,Tdiagram was attempted. For such a purpose and also for quality control, crystallographic and thermodynamic data were required. Powder X-ray diffractometry (XRD) and differential scanning calorimetry (DSC) were used. Molecular energy calculations were performed. Phase I melts at 426 K (ΔfusH(I) = +180 J·g-1). Phase II transforms into Phase I at 399 K (Δ(II→I)H= +24 J·g-1). Phase III transforms into phase I at 392 K (Δ(III→I)H= +28 J·g-1) or melts at 412 K (ΔfusH(III) = +210 J·g-1). Thep,Tdiagram shows that phase I is stable at higher temperature and phase II at lower temperature, like phase III, which is stable under high pressure. At room temperature, phase II is the more stable form, and phase I the less stable one. This agrees with the spontaneous I → II transformation observed at 298 K within a few hours, and with lattice energies, calculated previously. Molecular energy calculations and crystal structure comparison show how intermolecular hydrogen bonds and H-bonded dimers, in phases II and III, may stabilize conformations higher in energy than those of the isolated molecule and of phase I.

  20. A phase III trial of zoladex and flutamide versus orchiectomy in the treatment of patients with advanced carcinoma of the prostate

    DEFF Research Database (Denmark)

    Iversen, P; Christensen, M G; Friis, E

    1990-01-01

    In a multicenter Phase III trial 264 patients with advanced prostatic cancer were randomized to either bilateral orchiectomy or treatment with zoladex supplemented by flutamide. Presently, median follow-up time is 30 months. A small difference in objective response was recorded in favor of the co......In a multicenter Phase III trial 264 patients with advanced prostatic cancer were randomized to either bilateral orchiectomy or treatment with zoladex supplemented by flutamide. Presently, median follow-up time is 30 months. A small difference in objective response was recorded in favor...... of the combination therapy, whereas no statistically significant difference was found in subjective response to therapy, time to progression, and overall survival. Adverse effects were more commonly encountered in the pharmacologically treated patients. It is concluded that the combination of zoladex plus flutamide...... is not clinically superior to orchiectomy in the treatment of patients with advanced carcinoma of the prostate....

  1. Summary of EPRI projects for improving power plant maintenance and maintainability

    International Nuclear Information System (INIS)

    Shugars, H.G.; Poole, D.N.; Pack, R.W.

    1979-01-01

    The Electric Power Research Institute is sponsoring projects to improve power plant maintenance and maintainability. Areas presently being emphasized are improvements in plant design for maintainability, improvements in performing nuclear plant refuelings, and development of on-line monitoring and diagnostic systems for various plant components. The seven projects are reviewed. They are: (1) human factors review of power plant maintainability; (2) refueling outage improvement; (3) on-line monitoring and diagnostics for power plant machinery; (4) acoustic emission and vibrati1on signature analysis of fossil fuel plant components; (5) acoustic monitoring of power plant valves; (6) on-line monitoring and diagnostics for generators; and (7) detection of water induction in steam turbines. Each project contractor and the project manager are listed for reference. 8 references

  2. Improving Project Management Using Formal Models and Architectures

    Science.gov (United States)

    Kahn, Theodore; Sturken, Ian

    2011-01-01

    This talk discusses the advantages formal modeling and architecture brings to project management. These emerging technologies have both great potential and challenges for improving information available for decision-making. The presentation covers standards, tools and cultural issues needing consideration, and includes lessons learned from projects the presenters have worked on.

  3. Improving food and agricultural production. Thailand. Project findings and recommendations

    International Nuclear Information System (INIS)

    1992-01-01

    This document is the terminal report of a United Nations Development Program project to improve food and agricultural production in Thailand by means of nuclear and related technology. The project resulted in improved mutant material to be made available to plant breeders as well as in reports and recommendations on soil-water-plant management practices and livestock management. An additional benefit has been the specialized training that has been provided to many researchers in the country through the project

  4. Code of Conduct for wind-power projects - Phase 3; Code of Conduct fuer windkraftprojekte. Phase 3 Machbarkeit und Strategie

    Energy Technology Data Exchange (ETDEWEB)

    Strub, P. [Pierre Strub, freischaffender Berater, Binningen (Switzerland); Ziegler, Ch. [Inter Act, Basel (Switzerland)

    2008-11-15

    This paper discusses the results of phase three of a project concerning wind-power projects. Feasibility and strategy aspects are examined and discussed. The current state of the wind power market is discussed on the basis of the results of a survey made on the subject. The social acceptance of wind power installations is discussed, whereby the rejection of particular projects is compared with a general lack of acceptance. Requirements placed on such projects and possible solutions are discussed. Finally, the feasibility of setting up a code of conduct in the area of wind-power projects is discussed and the definition of further instruments is examined

  5. Local blur analysis and phase error correction method for fringe projection profilometry systems.

    Science.gov (United States)

    Rao, Li; Da, Feipeng

    2018-05-20

    We introduce a flexible error correction method for fringe projection profilometry (FPP) systems in the presence of local blur phenomenon. Local blur caused by global light transport such as camera defocus, projector defocus, and subsurface scattering will cause significant systematic errors in FPP systems. Previous methods, which adopt high-frequency patterns to separate the direct and global components, fail when the global light phenomenon occurs locally. In this paper, the influence of local blur on phase quality is thoroughly analyzed, and a concise error correction method is proposed to compensate the phase errors. For defocus phenomenon, this method can be directly applied. With the aid of spatially varying point spread functions and local frontal plane assumption, experiments show that the proposed method can effectively alleviate the system errors and improve the final reconstruction accuracy in various scenes. For a subsurface scattering scenario, if the translucent object is dominated by multiple scattering, the proposed method can also be applied to correct systematic errors once the bidirectional scattering-surface reflectance distribution function of the object material is measured.

  6. The Agricultural Model Intercomparison and Improvement Project: Phase I Activities by a Global Community of Science. Chapter 1

    Science.gov (United States)

    Rosenzweig, Cynthia E.; Jones, James W.; Hatfield, Jerry L.; Antle, John M.; Ruane, Alexander C.; Mutter, Carolyn Z.

    2015-01-01

    The Agricultural Model Intercomparison and Improvement Project (AgMIP) was founded in 2010. Its mission is to improve substantially the characterization of world food security as affected by climate variability and change, and to enhance adaptation capacity in both developing and developed countries. The objectives of AgMIP are to: Incorporate state-of-the-art climate, crop/livestock, and agricultural economic model improvements into coordinated multi-model regional and global assessments of future climate impacts and adaptation and other key aspects of the food system. Utilize multiple models, scenarios, locations, crops/livestock, and participants to explore uncertainty and the impact of data and methodological choices. Collaborate with regional experts in agronomy, animal sciences, economics, and climate to build a strong basis for model applications, addressing key climate related questions and sustainable intensification farming systems. Improve scientific and adaptive capacity in modeling for major agricultural regions in the developing and developed world, with a focus on vulnerable regions. Improve agricultural data and enhance data-sharing based on their intercomparison and evaluation using best scientific practices. Develop modeling frameworks to identify and evaluate promising adaptation technologies and policies and to prioritize strategies.

  7. Occlusion therapy improves phase-alignment of the cortical response in amblyopia.

    Science.gov (United States)

    Kelly, John P; Tarczy-Hornoch, Kristina; Herlihy, Erin; Weiss, Avery H

    2015-09-01

    The visual evoked potential (VEP) generated by the amblyopic visual system demonstrates reduced amplitude, prolonged latency, and increased variation in response timing (phase-misalignment). This study examined VEPs before and after occlusion therapy (OT) and whether phase-misalignment can account for the amblyopic VEP deficits. VEPs were recorded to 0.5-4cycles/degree gratings in 10 amblyopic children (2-6years age) before and after OT. Phase-misalignment was measured by Fourier analysis across a limited bandwidth. Signal-to-noise ratios (SNRs) were estimated from amplitude and phase synchrony in the Fourier domain. Responses were compared to VEPs corrected for phase-misalignment (individual epochs shifted in time to correct for the misalignment). Before OT, amblyopic eyes (AE) had significantly more phase-misalignment, latency prolongation, and lower SNR relative to the fellow eye. Phase-misalignment contributed significantly to low SNR but less so to latency delay in the AE. After OT, phase-alignment improved, SNR improved and latency shortened in the AE. Raw averaged waveforms from the AE improved after OT, primarily at higher spatial frequencies. Correcting for phase-misalignment in the AE sharpened VEP peak responses primarily at low spatial frequencies, but could not account for VEP waveform improvements in the AE after OT at higher spatial frequencies. In summary, VEP abnormalities from the AE are associated with phase-misalignment and reduced SNR possibly related to desynchronization of neuronal activity. The effect of OT on VEP responses is greater than that accounted for by phase-misalignment and SNR alone. Copyright © 2014 Elsevier Ltd. All rights reserved.

  8. Phase III Study of Cabozantinib in Previously Treated Metastatic Castration-Resistant Prostate Cancer: COMET-1.

    Science.gov (United States)

    Smith, Matthew; De Bono, Johann; Sternberg, Cora; Le Moulec, Sylvestre; Oudard, Stéphane; De Giorgi, Ugo; Krainer, Michael; Bergman, Andries; Hoelzer, Wolfgang; De Wit, Ronald; Bögemann, Martin; Saad, Fred; Cruciani, Giorgio; Thiery-Vuillemin, Antoine; Feyerabend, Susan; Miller, Kurt; Houédé, Nadine; Hussain, Syed; Lam, Elaine; Polikoff, Jonathan; Stenzl, Arnulf; Mainwaring, Paul; Ramies, David; Hessel, Colin; Weitzman, Aaron; Fizazi, Karim

    2016-09-01

    Cabozantinib is an inhibitor of kinases, including MET and vascular endothelial growth factor receptors, and has shown activity in men with previously treated metastatic castration-resistant prostate cancer (mCRPC). This blinded phase III trial compared cabozantinib with prednisone in patients with mCRPC. Men with progressive mCRPC after docetaxel and abiraterone and/or enzalutamide were randomly assigned at a two-to-one ratio to cabozantinib 60 mg once per day or prednisone 5 mg twice per day. The primary end point was overall survival (OS). Bone scan response (BSR) at week 12 as assessed by independent review committee was the secondary end point; radiographic progression-free survival (rPFS) and effects on circulating tumor cells (CTCs), bone biomarkers, serum prostate-specific antigen (PSA), and symptomatic skeletal events (SSEs) were exploratory assessments. A total of 1,028 patients were randomly assigned to cabozantinib (n = 682) or prednisone (n = 346). Median OS was 11.0 months with cabozantinib and 9.8 months with prednisone (hazard ratio, 0.90; 95% CI, 0.76 to 1.06; stratified log-rank P = .213). BSR at week 12 favored cabozantinib (42% v 3%; stratified Cochran-Mantel-Haenszel P < .001). rPFS was improved in the cabozantinib group (median, 5.6 v 2.8 months; hazard ratio, 0.48; 95% CI, 0.40 to 0.57; stratified log-rank P < .001). Cabozantinib was associated with improvements in CTC conversion, bone biomarkers, and post-random assignment incidence of SSEs but not PSA outcomes. Grade 3 to 4 adverse events and discontinuations because of adverse events were higher with cabozantinib than with prednisone (71% v 56% and 33% v 12%, respectively). Cabozantinib did not significantly improve OS compared with prednisone in heavily treated patients with mCRPC and progressive disease after docetaxel and abiraterone and/or enzalutamide. Cabozantinib had some activity in improving BSR, rPFS, SSEs, CTC conversions, and bone biomarkers but not PSA outcomes. © 2016 by

  9. Experiences of practice facilitators working on the Improved Delivery of Cardiovascular Care project: Retrospective case study.

    Science.gov (United States)

    Liddy, Clare; Rowan, Margo; Valiquette-Tessier, Sophie-Claire; Drosinis, Paul; Crowe, Lois; Hogg, William

    2018-01-01

    To examine the barriers to and facilitators of practice facilitation experienced by participants in the Improving Delivery of Cardiovascular Care (IDOCC) project. Case studies of practice facilitators' narrative reports. Eastern Ontario. Primary care practices that participated in the IDOCC project. Cases were identified by calculating sum scores in order to determine practices' performance relative to their peers. Two case exemplars were selected that scored within ± 1 SD of the total mean score, and a qualitative analysis of practice facilitators' narrative reports was conducted using a 5-factor implementation framework to identify barriers and facilitators. Narratives were divided into 3 phases: planning, implementation, and sustainability. Barriers and facilitators fluctuated over the intervention's 3 phases. Site A reported more barriers (n = 47) than facilitators (n = 38), while site B reported a roughly equal number of barriers (n = 144) and facilitators (n = 136). In both sites, the most common barriers involved organizational and provider factors and the most common facilitators were associated with innovation and structural factors. Both practices encountered various barriers and facilitators throughout the IDOCC's 3 phases. The case studies reveal the complex interactions of these factors over time, and provide insight into the implementation of practice facilitation programs. Copyright© the College of Family Physicians of Canada.

  10. Kinetic of liquid-liquid extraction for uranyl nitrate and actinides (III) and lanthanides (III) nitrates by amide extractants

    International Nuclear Information System (INIS)

    Toulemonde, V.; CEA Centre d'Etudes de la Vallee du Rhone, 30 -Marcoule

    1995-01-01

    The kinetics of liquid-liquid extraction by amide extractants have been investigated for uranyl nitrate (monoamide extractants), actinides (III) and lanthanides (III) nitrates (diamide extractants). The transfer of the metallic species from the aqueous phase to the organic phase was studied using two experimental devices: ARMOLLEX (Argonne Modified Lewis cell for Liquid Liquid Extraction) and RSC (Rotating Stabilized Cell). The main conclusions are: for the extraction of uranyl nitrate by DEHDMBA monoamide, the rate-controlling step is the complexation of the species at the interface of the two liquids. Thus, an absorption-desorption (according to Langmuir theory) reaction mechanism was proposed; for the extraction of actinides (III) and lanthanides (III) nitrates in nitric acid media by DMDBTDMA diamide, the kinetic is also limited by interfacial reactions. The behavior of Americium and Europium is very similar as fare as their reaction kinetics are concerned. (author)

  11. Columbia River pathway report: phase I of the Hanford Environmental Dose Reconstruction Project

    Energy Technology Data Exchange (ETDEWEB)

    1991-07-01

    This report summarizes the river-pathway portion of the first phase of the Hanford Environmental Dose Reconstruction (HEDR) Project. The HEDR Project is estimating radiation doses that could have been received by the public from the Department of Energy's Hanford Site, in southeastern Washington State. Phase 1 of the river-pathway dose reconstruction effort sought to determine whether dose estimates could be calculated for populations in the area from above the Hanford Site at Priest Rapids Dam to below the site at McNary Dam from January 1964 to December 1966. Of the potential sources of radionuclides from the river, fish consumption was the most important. Doses from drinking water were lower at Pasco than at Richland and lower at Kennewick than at Pasco. The median values of preliminary dose estimates calculated by HEDR are similar to independent, previously published estimates of average doses to Richland residents. Later phases of the HEDR Project will address dose estimates for periods other than 1964--1966 and for populations downstream of McNary Dam. 17 refs., 19 figs., 1 tab.

  12. Generic project definitions for improvement of health care delivery: a case-based approach.

    Science.gov (United States)

    Niemeijer, Gerard C; Does, Ronald J M M; de Mast, Jeroen; Trip, Albert; van den Heuvel, Jaap

    2011-01-01

    The purpose of this article is to create actionable knowledge, making the definition of process improvement projects in health care delivery more effective. This study is a retrospective analysis of process improvement projects in hospitals, facilitating a case-based reasoning approach to project definition. Data sources were project documentation and hospital-performance statistics of 271 Lean Six Sigma health care projects from 2002 to 2009 of general, teaching, and academic hospitals in the Netherlands and Belgium. Objectives and operational definitions of improvement projects in the sample, analyzed and structured in a uniform format and terminology. Extraction of reusable elements of earlier project definitions, presented in the form of 9 templates called generic project definitions. These templates function as exemplars for future process improvement projects, making the selection, definition, and operationalization of similar projects more efficient. Each template includes an explicated rationale, an operationalization in the form of metrics, and a prototypical example. Thus, a process of incremental and sustained learning based on case-based reasoning is facilitated. The quality of project definitions is a crucial success factor in pursuits to improve health care delivery. We offer 9 tried and tested improvement themes related to patient safety, patient satisfaction, and business-economic performance of hospitals.

  13. Acute morbidity reduction using 3DCRT for prostate carcinoma; a randomised phase III study

    International Nuclear Information System (INIS)

    Koper, P.; Putten, W. van; Stroom, J.; Korevaar, G.; Heijmen, B.; Wijnmaalen, A.; Jansen, P.; Hanssens, P.; Griep, C.; Krol, A.; Samson, M.; Levendag, P.

    1997-01-01

    Purpose: A randomised phase III toxicity study (conventional vs conformal radiotherapy) was performed for prostatic carcinoma to study the effects on the (acute) morbidity of intestinal/rectosigmoid and bladder. The observed toxicity was compared with Dose Volume Histograms to reveal possible volume (reduction) effects. Methods: In the phase III study 266 T1-4 N0M0 prostate cancer patients were entered. Patients were randomised for conventional and conformal radiotherapy (total dose 66 Gy, minimum PTV dose 95% ICRU and a CTV-PTV margin of 10 mm in both study arms). The GTV was limited to the prostate only in T1 tumors. In all other patients the GTV was defined to be prostate and seminal vesicles for the complete treatment course. The CTV-PTV margin (10mm) was created by a automated program to ensure the minimum prescribed margin. The rectosigmoid was defined to be the rectum including the sigmoid within the Treatment Volume (ICRU). Acute toxicity was evaluated using the EORTC/RTOG morbidity score and weekly quality of life questionnaires. The radiation technique comparison was done by Dose volume Histogram analysis using the Area Under The Curve (AUC) for different dose levels. In this preliminary DVH analysis we present the data for the first 100 patients. Results: Patient and tumor characteristics were evenly distributed between both study groups. The maximum toxicity is reached at 75% of the tumordose (TD) (rectal grade I 59% grade II 26%, bladder grade I 48%, grade II 16% and grade III 1% [catheter for urinary retention]). Comparing both study arms there seems to be a reduction in intestinal morbidity (grade II and higher resp. 32% vs 19% p=0.02). Further analysis revealed a marked reduction in medication for anal symptoms; this accounts for a large part of the significant difference in intestinal toxicity (grade II conventional vs conformal rectosigmoid 18% vs 14% and anal 16% vs 8%). For bladder morbidity no difference for mobidity higher than grade I is

  14. X-ray differential phase-contrast tomographic reconstruction with a phase line integral retrieval filter

    International Nuclear Information System (INIS)

    Fu, Jian; Hu, Xinhua; Li, Chen

    2015-01-01

    We report an alternative reconstruction technique for x-ray differential phase-contrast computed tomography (DPC-CT). This approach is based on a new phase line integral projection retrieval filter, which is rooted in the derivative property of the Fourier transform and counteracts the differential nature of the DPC-CT projections. It first retrieves the phase line integral from the DPC-CT projections. Then the standard filtered back-projection (FBP) algorithms popular in x-ray absorption-contrast CT are directly applied to the retrieved phase line integrals to reconstruct the DPC-CT images. Compared with the conventional DPC-CT reconstruction algorithms, the proposed method removes the Hilbert imaginary filter and allows for the direct use of absorption-contrast FBP algorithms. Consequently, FBP-oriented image processing techniques and reconstruction acceleration softwares that have already been successfully used in absorption-contrast CT can be directly adopted to improve the DPC-CT image quality and speed up the reconstruction

  15. Hysteroscopic Essure Inserts for Permanent Contraception: Extended Follow-Up Results of a Phase III Multicenter International Study.

    Science.gov (United States)

    Chudnoff, Scott G; Nichols, John E; Levie, Mark

    2015-01-01

    To describe safety, tolerability, and effectiveness results through 5 years of follow-up of a Phase III trial with Essure inserts. Multicenter, nonrandomized, single-arm international study (Canadian Task Force classification II-3). Thirteen clinical study centers in the United States, Europe, and Australia. A total of 518 previously fertile women seeking permanent contraception. The objective of the hysteroscopic sterilization procedure was bilateral Essure insert placement (ESS205 model) and tubal occlusion. Women with satisfactory device location and tube occlusion (based on modified hysterosalpingography [HSG]) were instructed to discontinue alternative contraception and to rely on Essure inserts for permanent contraception. The primary endpoint for the Phase III study was the rate of pregnancies occurring during the first year of relying (i.e., HSG-confirmed occlusion) on the Essure inserts for permanent contraception (i.e., 12 months after HSG). For the full 5 years of follow-up (5 years total of relying on the Essure inserts for contraception), the endpoints of interest were safety, prevention of pregnancy, and satisfaction. No pregnancies were reported among women relying on the Essure inserts who completed the full 5 years of follow-up. As of December 5, 2007, 449 women with successful bilateral placement relying on the Essure inserts contributed a total 24 942 woman-months of follow-up for assessing effectiveness. Overall, the Essure inserts were generally well tolerated, with participant comfort rated as "good" to "excellent" by 99% of women (382 of 385) after 5 years of use. Similarly, overall satisfaction was rated as "somewhat" to "very satisfied" by 98% of women (376 of 384) after 5 years of use. The majority of adverse events reported during the 5 years of follow-up were rated as either "mild" or "moderate" in severity. Three severe events (abdominal pain with very heavy periods and irregular menstrual bleeding) were reported in 2 subjects during

  16. Maintenance Decision Support System, Phase III

    Science.gov (United States)

    2017-09-01

    The main goal of the project was to address barriers that limit NDOTs ability to implement MDSS and MMS systems. The four project tasks included: Task 1: Develop system for tracking sand and/or deicing material usage: A system that tracks where and w...

  17. Evaluate fundamental approaches to longwall dust control. Phase III report

    Energy Technology Data Exchange (ETDEWEB)

    Babbitt, C.; Bartlett, P.; Kelly, J.; Ludlow, J.; Mangolds, A.; Rajan, S.; Ruggieri, S.; Varga, E.

    1984-03-31

    The overall objective of the contract is to evaluate the effectiveness of available dust control technology for double-drum shearer longwall sections in a coordinated, systematic program at a few longwall test sections and to make the results available to the entire coal mining industry. This program is investigating nine different dust control techniques. These nine subprograms encompass a broad range of dust control measures ranging from administrative controls to new hardware. They span not only presently employed methods but also those recently adopted in the United States and those proposed for the future. This report documents the Phase III effort on each of the subprograms. For clarity, the report is divided in sections by subprogram as follows: Section 2, Subprogram A - passive barriers/spray air movers for dust control; Section 3, Subprogram B - practical aspects of deep cutting; Section 4, Subprogram C - stage loader dust control; Section 5, Subprogram D - longwall automation technology; Section 6, Subprogram E - longwall application of ventilation curtains; Section 7, Subprogram F - reversed drum rotation; Section 8, Subprogram G - reduction of shield generated dust; Section 9, Subprogram H - air canopies for longwalls; and Section 10, Subprogram I - mining practices. 43 figures, 11 tables.

  18. Improving patient care through student leadership in team quality improvement projects.

    Science.gov (United States)

    Tschannen, Dana; Aebersold, Michelle; Kocan, Mary Jo; Lundy, Francene; Potempa, Kathleen

    2015-01-01

    In partnership with a major medical center, senior-level nursing students completed a root cause analysis and implementation plan to address a unit-specific quality issue. To evaluate the project, unit leaders were asked their perceptions of the value of the projects and impact on patient care, as well as to provide exemplars depicting how the student root cause analysis work resulted in improved patient outcome and/or unit processes. Liaisons noted benefits of having an RCA team, with positive impact on patient outcomes and care processes.

  19. Modified Vivaldi antenna with improved gain and phase center stability

    DEFF Research Database (Denmark)

    Zhang, Shuai

    2016-01-01

    A modified Vivaldi antenna is proposed with improved gain and phase centre stability. By applying a high permittivity dielectric substrate, the realized gain is enlarged while maintaining the compactness of the designed antenna. With a redistributed comb-shape corrugation the phase centre stabili...... of the antenna is significantly improved. The designed modified Vivaldi antenna covers the lower UWB band of 3.1-5 GHz with a realized gain higher than 10 dBi. A stable phase centre and radiation patterns over the operating band are realized....

  20. Can model weighting improve probabilistic projections of climate change?

    Energy Technology Data Exchange (ETDEWEB)

    Raeisaenen, Jouni; Ylhaeisi, Jussi S. [Department of Physics, P.O. Box 48, University of Helsinki (Finland)

    2012-10-15

    Recently, Raeisaenen and co-authors proposed a weighting scheme in which the relationship between observable climate and climate change within a multi-model ensemble determines to what extent agreement with observations affects model weights in climate change projection. Within the Third Coupled Model Intercomparison Project (CMIP3) dataset, this scheme slightly improved the cross-validated accuracy of deterministic projections of temperature change. Here the same scheme is applied to probabilistic temperature change projection, under the strong limiting assumption that the CMIP3 ensemble spans the actual modeling uncertainty. Cross-validation suggests that probabilistic temperature change projections may also be improved by this weighting scheme. However, the improvement relative to uniform weighting is smaller in the tail-sensitive logarithmic score than in the continuous ranked probability score. The impact of the weighting on projection of real-world twenty-first century temperature change is modest in most parts of the world. However, in some areas mainly over the high-latitude oceans, the mean of the distribution is substantially changed and/or the distribution is considerably narrowed. The weights of individual models vary strongly with location, so that a model that receives nearly zero weight in some area may still get a large weight elsewhere. Although the details of this variation are method-specific, it suggests that the relative strengths of different models may be difficult to harness by weighting schemes that use spatially uniform model weights. (orig.)

  1. Bortezomib before and after high-dose therapy in myeloma : Long-term results from the phase III HOVON-65/GMMGHD-4 trial

    NARCIS (Netherlands)

    Goldschmidt, H.; Lokhorst, H. M.; Mai, E. K.; van der Holt, B.; Blau, I. W.; Zweegman, S.; Weisel, K. C.; Vellenga, E.; Pfreundschuh, M.; Kersten, M. J.; Scheid, C.; Croockewit, S.; Raymakers, R.; Hose, D.; Potamianou, A.; Jauch, A.; Hillengass, J.; Stevens-Kroef, M.; Raab, M. S.; Broijl, A.; Lindemann, H. W.; Bos, G. M. J.; Brossart, P.; Kooy, M. van Marwijk; Ypma, P.; Duehrsen, U.; Schaafsma, R. M.; Bertsch, U.; Hielscher, T.; Jarari, Le; Salwender, H. J.; Sonneveld, P.

    The Dutch-Belgian Cooperative Trial Group for Hematology Oncology Group-65/German-speaking Myeloma Multicenter Group-HD4 (HOVON-65/GMMG-HD4) phase III trial compared bortezomib (BTZ) before and after high-dose melphalan and autologous stem cell transplantation (HDM, PAD arm) compared with classical

  2. Bortezomib before and after high-dose therapy in myeloma: long-term results from the phase III HOVON-65/GMMGHD-4 trial

    NARCIS (Netherlands)

    Goldschmidt, H.; Lokhorst, H. M.; Mai, E. K.; van der Holt, B.; Blau, I. W.; Zweegman, S.; Weisel, K. C.; Vellenga, E.; Pfreundschuh, M.; Kersten, M. J.; Scheid, C.; Croockewit, S.; Raymakers, R.; Hose, D.; Potamianou, A.; Jauch, A.; Hillengass, J.; Stevens-Kroef, M.; Raab, M. S.; Broijl, A.; Lindemann, H. W.; Bos, G. M. J.; Brossart, P.; van Marwijk Kooy, M.; Ypma, P.; Duehrsen, U.; Schaafsma, R. M.; Bertsch, U.; Hielscher, T.; Jarari, Le; Salwender, H. J.; Sonneveld, P.

    2018-01-01

    The Dutch-Belgian Cooperative Trial Group for Hematology Oncology Group-65/German-speaking Myeloma Multicenter Group-HD4 (HOVON-65/GMMG-HD4) phase III trial compared bortezomib (BTZ) before and after high-dose melphalan and autologous stem cell transplantation (HDM, PAD arm) compared with classical

  3. Environmental handling in the Japan: Project of improvement of lands

    International Nuclear Information System (INIS)

    Tascon Carvajal, R.

    1993-01-01

    Some administrative aspects, politicians and strategies are described continued by the Japan to protect the environment in the agrarian sector. It is analyzed the project of improvement of lands, their objectives and functions and the operative mark inside which is unwrapped, their procedures for the implementation as sampling and planning, definitive design and construction. Equally the projects of improvement of lands of reduced reach are discussed, in what concerns to irrigation and drainage, consolidation of lands, prevention of disasters and development of the community. The perspectives of the projects of development of lands of long reach are mentioned inside a general strategy of productivity, sustainability, justness and improvement of the level of life

  4. Radiation therapy for ocular choroidal neovascularization (phase I/II study): preliminary report

    International Nuclear Information System (INIS)

    Sasai, Keisuke; Murata, Rumi; Mandai, Michiko; Takahashi, Masayo; Ogura, Yuichiro; Ngata, Yasushi; Nishimura, Yasumasa; Hiraoka, Masahiro

    1997-01-01

    2 months after treatment, but this had disappeared spontaneously by the fourth month. The subjective symptoms, visual acuity, and size of the neovascular membrane were evaluated at 6 and 12 months after treatment in each patient. In the group of patients irradiated with 10 Gy and with 20 Gy, respectively, subjective symptoms improved in five and seven eyes, did not change in seven and four eyes, and deteriorated in six and six eyes at 12 months. Although visual acuity was significantly decreased in the control group, the patients in both irradiated groups did not show such a decrease in visual acuity. The size of the neovascular membrane in the control group progressed significantly. However, the patients in the 20 Gy group showed significant regression of the membrane, although those in the 10 Gy group showed no significant change in size. Conclusion: This Phase I/II study including a dose escalation study showed that radiation therapy seems to be useful for CNV. The dose of 20 Gy in 10 fractions was more useful in treating neovascular membranes than the dose of 10 Gy in five fractions. These results have encouraged us to start a multicenter randomized prospective study of the treatment of CNV with radiation therapy

  5. Production circulator fabrication and testing for core flow test loop. Final report, Phase III

    Energy Technology Data Exchange (ETDEWEB)

    1981-05-01

    The performance testing of two production helium circulators utilizing gas film lubrication is described. These two centrifugal-type circulators plus an identical circulator prototype will be arranged in series to provide the helium flow requirements for the Core Flow Test Loop which is part of the Gas-Cooled Fast Breeder Reactor Program (GCFR) at the Oak Ridge National Laboratory. This report presents the results of the Phase III performance and supplemental tests, which were carried out by MTI during the period of December 18, 1980 through March 19, 1981. Specific test procedures are outlined and described, as are individual tests for measuring the performance of the circulators. Test data and run descriptions are presented.

  6. Production circulator fabrication and testing for core flow test loop. Final report, Phase III

    International Nuclear Information System (INIS)

    1981-05-01

    The performance testing of two production helium circulators utilizing gas film lubrication is described. These two centrifugal-type circulators plus an identical circulator prototype will be arranged in series to provide the helium flow requirements for the Core Flow Test Loop which is part of the Gas-Cooled Fast Breeder Reactor Program (GCFR) at the Oak Ridge National Laboratory. This report presents the results of the Phase III performance and supplemental tests, which were carried out by MTI during the period of December 18, 1980 through March 19, 1981. Specific test procedures are outlined and described, as are individual tests for measuring the performance of the circulators. Test data and run descriptions are presented

  7. Kinetic of liquid-liquid extraction for uranyl nitrate and actinides (III) and lanthanides (III) nitrates by amide extractants; Cinetique d`extraction liquide-liquide du nitrate d`uranyle et des nitrates d`actinides (III) et de lanthanides (III) par des extractants a fonction amide

    Energy Technology Data Exchange (ETDEWEB)

    Toulemonde, V [CEA Centre d` Etudes Nucleaires de Saclay, 91 -Gif-sur-Yvette (France); [CEA Centre d` Etudes de la Vallee du Rhone, 30 -Marcoule (France). Dept. d` Exploitation du Retraitement et de Demantelement

    1995-12-20

    The kinetics of liquid-liquid extraction by amide extractants have been investigated for uranyl nitrate (monoamide extractants), actinides (III) and lanthanides (III) nitrates (diamide extractants). The transfer of the metallic species from the aqueous phase to the organic phase was studied using two experimental devices: ARMOLLEX (Argonne Modified Lewis cell for Liquid Liquid Extraction) and RSC (Rotating Stabilized Cell). The main conclusions are: for the extraction of uranyl nitrate by DEHDMBA monoamide, the rate-controlling step is the complexation of the species at the interface of the two liquids. Thus, an absorption-desorption (according to Langmuir theory) reaction mechanism was proposed; for the extraction of actinides (III) and lanthanides (III) nitrates in nitric acid media by DMDBTDMA diamide, the kinetic is also limited by interfacial reactions. The behavior of Americium and Europium is very similar as fare as their reaction kinetics are concerned. (author). 89 refs.

  8. Bioavailability of Fe(III) in Natural Soils and the Impact on Mobility of Inorganic Contaminants (Final Report)

    Energy Technology Data Exchange (ETDEWEB)

    Kosson, David S. [Vanderbilt Univ., Nashville, TN (United States). Dept. of Civil and Environmental Engineering; Cowan, Robert M. [Rutgers Univ., New Brunswick, NJ (United States). Dept. of Environmental Science; Young, Lily Y. [Rutgers Univ., New Brunswick, NJ (United States). Center for Agriculture and the Environment; Hatcherl, Eric L. [Vanderbilt Univ., Nashville, TN (United States). Dept. of Civil and Environmental Engineering; Scala, David J. [Vanderbilt Univ., Nashville, TN (United States). Dept. of Civil and Environmental Engineering

    2005-08-02

    Inorganic contaminants, such as heavy metals and radionuclides, can adhere to insoluble Fe(III) minerals resulting in decreased mobility of these contaminants through subsurface environments. Dissimilatory Fe(III)-reducing bacteria (DIRB), by reducing insoluble Fe(III) to soluble Fe(II), may enhance contaminant mobility. The Savannah River Site, South Carolina (SRS), has been subjected to both heavy metal and radionuclide contamination. The overall objective of this project is to investigate the release of inorganic contaminants such as heavy metals and radionuclides that are bound to solid phase soil Fe complexes and to elucidate the mechanisms for mobilization of these contaminants that can be associated with microbial Fe(III) reduction. This is being accomplished by (i) using uncontaminated and contaminated soils from SRS as prototype systems, (ii) evaluating the diversity of DIRBs within the samples and isolating cultures for further study, (iii) using batch microcosms to evaluate the bioavailability of Fe(III) from pure minerals and SRS soils, (iv) developing kinetic and mass transfer models that reflect the system dynamics, and (v) carrying out soil column studies to elucidate the dynamics and interactions amongst Fe(III) reduction, remineralization and contaminant mobility.

  9. Adsorption of As(III), As(V) and Cu(II) on zirconium oxide immobilized alginate beads in aqueous phase.

    Science.gov (United States)

    Kwon, Oh-Hun; Kim, Jong-Oh; Cho, Dong-Wan; Kumar, Rahul; Baek, Seung Han; Kurade, Mayur B; Jeon, Byong-Hun

    2016-10-01

    A composite adsorbent to remove arsenite [As(III)], arsenate [As(V)], and copper [Cu(II)] from aqueous phase was synthesized by immobilizing zirconium oxide on alginate beads (ZOAB). The composition (wt%) of ZOAB (Zr-34.0; O-32.7; C-21.3; Ca-1.0) was confirmed by energy dispersive X-ray (EDX) analysis. Sorption studies were conducted on single and binary sorbate systems, and the effects of contact time, initial adsorbate concentration, and pH on the adsorption performance of ZOAB (pHPZC = 4.3) were monitored. The sorption process for As(III)/As(V) and Cu(II) reached an equilibrium state within 240 h and 24 h, respectively, with maximum sorption capacities of 32.3, 28.5, and 69.9 mg g(-1), respectively. The addition of Cu(II) was favorable for As(V) sorption in contrast to As(III). In the presence of 48.6 mg L(-1) Cu(II), the sorption capacity of As(V) increased from 1.5 to 3.8 mg g(-1) after 240 h. The sorption data for As(III)/As(V) and Cu(II) conformed the Freundlich and Langmuir isotherm models, respectively. The adsorption of As(III), As(V), and Cu(II) followed pseudo second order kinetics. The effect of arsenic species on Cu(II) sorption was insignificant. The results of present study demonstrated that the synthesized sorbent could be useful for the simultaneous removal of both anionic and cationic contaminants from wastewaters. Copyright © 2016 Elsevier Ltd. All rights reserved.

  10. Phase I-II study of everolimus and low-dose oral cyclophosphamide in patients with metastatic renal cell cancer

    International Nuclear Information System (INIS)

    Huijts, Charlotte M; Santegoets, Saskia J; Eertwegh, Alfons J van den; Pijpers, Laura S; Haanen, John B; Gruijl, Tanja D de; Verheul, Henk M; Vliet, Hans J van der

    2011-01-01

    For patients with metastatic renal cell cancer (mRCC) who progressed on vascular endothelial growth factor (VEGF) receptor tyrosine kinase inhibitor therapy, the orally administered mammalian target of rapamycin (mTOR) inhibitor everolimus has been shown to prolong progression free survival. Intriguingly, inhibition of mTOR also promotes expansion of immunosuppressive regulatory T cells (Tregs) that can inhibit anti-tumor immune responses in a clinically relevant way in various tumor types including RCC. This study intends to investigate whether the antitumor efficacy of everolimus can be increased by preventing the detrimental everolimus induced expansion of Tregs using a metronomic schedule of cyclophosphamide. This phase I-II trial is a national multi-center study of different doses and schedules of low-dose oral cyclophosphamide in combination with a fixed dose of everolimus in patients with mRCC not amenable to or progressive after a VEGF-receptor tyrosine kinase inhibitor containing treatment regimen. In the phase I part of the study the optimal Treg-depleting dose and schedule of metronomic oral cyclophosphamide when given in combination with everolimus will be determined. In the phase II part of the study we will evaluate whether the percentage of patients progression free at 4 months of everolimus treatment can be increased from 50% to 70% by adding metronomic cyclophosphamide (in the dose and schedule determined in the phase I part). In addition to efficacy, we will perform extensive immune monitoring with a focus on the number, phenotype and function of Tregs, evaluate the safety and feasibility of the combination of everolimus and cyclophosphamide, perform monitoring of selected angiogenesis parameters and analyze everolimus and cyclophosphamide drug levels. This phase I-II study is designed to determine whether metronomic cyclophosphamide can be used to counter the mTOR inhibitor everolimus induced Treg expansion in patients with metastatic renal cell

  11. Phase I-II study of everolimus and low-dose oral cyclophosphamide in patients with metastatic renal cell cancer

    Directory of Open Access Journals (Sweden)

    Huijts Charlotte M

    2011-11-01

    Full Text Available Abstract Background For patients with metastatic renal cell cancer (mRCC who progressed on vascular endothelial growth factor (VEGF receptor tyrosine kinase inhibitor therapy, the orally administered mammalian target of rapamycin (mTOR inhibitor everolimus has been shown to prolong progression free survival. Intriguingly, inhibition of mTOR also promotes expansion of immunosuppressive regulatory T cells (Tregs that can inhibit anti-tumor immune responses in a clinically relevant way in various tumor types including RCC. This study intends to investigate whether the antitumor efficacy of everolimus can be increased by preventing the detrimental everolimus induced expansion of Tregs using a metronomic schedule of cyclophosphamide. Methods/design This phase I-II trial is a national multi-center study of different doses and schedules of low-dose oral cyclophosphamide in combination with a fixed dose of everolimus in patients with mRCC not amenable to or progressive after a VEGF-receptor tyrosine kinase inhibitor containing treatment regimen. In the phase I part of the study the optimal Treg-depleting dose and schedule of metronomic oral cyclophosphamide when given in combination with everolimus will be determined. In the phase II part of the study we will evaluate whether the percentage of patients progression free at 4 months of everolimus treatment can be increased from 50% to 70% by adding metronomic cyclophosphamide (in the dose and schedule determined in the phase I part. In addition to efficacy, we will perform extensive immune monitoring with a focus on the number, phenotype and function of Tregs, evaluate the safety and feasibility of the combination of everolimus and cyclophosphamide, perform monitoring of selected angiogenesis parameters and analyze everolimus and cyclophosphamide drug levels. Discussion This phase I-II study is designed to determine whether metronomic cyclophosphamide can be used to counter the mTOR inhibitor everolimus

  12. Lessons learnt from Volcanoes' Night I-II-III - a Marie Curie Researchers' Night project series dedicated to geosciences

    Science.gov (United States)

    Cseko, Adrienn; Bodo, Balazs; Ortega Rodriguez, Ariadna

    2017-04-01

    European Researchers' Nights (ERNs) are a pan-European series of events funded by the European Commission, organised on the last Friday of every September since 2005. ERNs mobilise scientific, academic and research organisations with the aim of giving the public the opportunity to meet researchers in an informal setting. The overall objective of ERNs is to achieve better awareness among the general public concerning the importance of science in everyday life and to combat stereotypes about researchers. The longer-term strategic objective of ERNs is to encourage young people to embark on a scientific career. Volcanoes' Night I-II-III has been an ERN project series funded by the EC FP7 and H2020 programmes between 2012-2015 (EC contract No. 316558, 610050, 633310, www.nochedevolcanes.es). The concept of Volcanoes' Night was created by researchers from the Canary Islands, Spain, where both the researchers and the public live in the close vicinity of volcanoes. The objective of the project was to use volcanoes as a background against which the role of geoscientists could be explained to the public. The scope of Volcanoes' Night was exclusively dedicated to geoscience, and in this respect it stands out among all other ERN projects, which are always more general in scope. During its four years of EC funding, the geographical coverage of Volcanoes' Night expanded substantially from a single location in 2012 (Fuencaliente de La Palma, Spain) to a dozen locations in 2015, mobilising multiple scientific organisations, researchers, and public authorities for engagement with the public. The last EC-funded project, Volcanoes' Night III, which was organised in 2014 and 2015, engaged approximately 21,000 visitors through its outreach activities, which included experiments, science cafés, volcano movies, My Day presentations, excursions, science workshops and more. The impact of the project was carefully assessed via surveys and social studies during its lifetime, and an Impact

  13. SNF project engineering process improvement plan

    International Nuclear Information System (INIS)

    DESAI, S.P.

    1999-01-01

    This Engineering Process Improvement Plan documents the activities and plans to be taken by the SNF Project to support its engineering process and to produce a consolidated set of engineering procedures that are fully compliant with the requirements of HNF-PRO-1819. All new procedures will be issued and implemented by September 30, 1999

  14. Characterization of unpaved road condition through the use of remote sensing project - phase II, deliverable 8-D: final report.

    Science.gov (United States)

    2016-03-07

    Building on the success of developing a UAV based unpaved road assessment system in Phase I, the project team was awarded a Phase II project by the USDOT to focus on outreach and implementation. The project team added Valerie Lefler of Integrated Glo...

  15. Phase 2 : evaluation of the national crash experience : comparison of CARDfile national motor vehicle accident projections with projections from other data bases

    Science.gov (United States)

    1997-01-01

    The purpose of this Phase 2 Study is to compare national motor vehicle accident projections : made from the Crash Avoidance Research Data base (CARDfile) with national motor : vehicle accident projections made from other data bases. For the most part...

  16. California Food Processing Industry Wastewater Demonstration Project: Phase I Final Report

    Energy Technology Data Exchange (ETDEWEB)

    Lewis, Glen; Atkinson, Barbara; Rhyne, Ivin

    2009-09-09

    Wastewater treatment is an energy-intensive process and electricity demand is especially high during the utilities summer peak electricity demand periods. This makes wastewater treatment facilities prime candidates for demand response programs. However, wastewater treatment is often peripheral to food processing operations and its demand response opportunities have often been overlooked. Phase I of this wastewater demonstration project monitored wastewater energy and environmental data at Bell-Carter Foods, Inc., California's largest olive processing plant. For this monitoring activity the project team used Green Energy Management System (GEMS) automated enterprise energy management (EEM) technologies. This report presents results from data collected by GEMS from September 15, 2008 through November 30, 2008, during the olive harvest season. This project established and tested a methodology for (1) gathering baseline energy and environmental data at an industrial food-processing plant and (2) using the data to analyze energy efficiency, demand response, daily peak load management, and environmental management opportunities at the plant. The Phase I goals were to demonstrate the measurement and interrelationship of electricity demand, electricity usage, and water quality metrics and to estimate the associated CO{sub 2} emissions.

  17. Impact of baseline covariates on the immunogenicity of the 9-valent HPV vaccine - A combined analysis of five phase III clinical trials

    DEFF Research Database (Denmark)

    Petersen, Lone K; Restrepo, Jaime; Moreira, Edson D

    2017-01-01

    BACKGROUND: The immunogenicity profile of the 9-valent HPV (9vHPV) vaccine was evaluated across five phase III clinical studies conducted in girls and boys 9-15 years of age and young women 16-26 years of age. The effect of baseline characteristics of subjects on vaccine-induced HPV antibody...... responses was assessed. METHODS: Immunogenicity data from 11,304 subjects who received ≥1 dose of 9vHPV vaccine in five Phase III studies were analyzed. Vaccine was administered as a 3-dose regimen. HPV antibody titers were assessed 1 month after dose 3 using a competitive Luminex immunoassay and summarized...... as geometric mean titers (GMTs). Covariates examined were age, gender, race, region of residence, and HPV serostatus and PCR status at day 1. RESULTS: GMTs to all 9 vaccine HPV types decreased with age at vaccination initiation, and were otherwise generally similar among the demographic subgroups defined...

  18. Advanced reservoir characterization for improved oil recovery in a New Mexico Delaware basin project

    Energy Technology Data Exchange (ETDEWEB)

    Martin, F.D.; Kendall, R.P.; Whitney, E.M. [Dave Martin and Associates, Inc., Socorro, NM (United States)] [and others

    1997-08-01

    The Nash Draw Brushy Canyon Pool in Eddy County, New Mexico is a field demonstration site in the Department of Energy Class III program. The basic problem at the Nash Draw Pool is the low recovery typically observed in similar Delaware fields. By comparing a control area using standard infill drilling techniques to a pilot area developed using advanced reservoir characterization methods, the goal of the project is to demonstrate that advanced technology can significantly improve oil recovery. During the first year of the project, four new producing wells were drilled, serving as data acquisition wells. Vertical seismic profiles and a 3-D seismic survey were acquired to assist in interwell correlations and facies prediction. Limited surface access at the Nash Draw Pool, caused by proximity of underground potash mining and surface playa lakes, limits development with conventional drilling. Combinations of vertical and horizontal wells combined with selective completions are being evaluated to optimize production performance. Based on the production response of similar Delaware fields, pressure maintenance is a likely requirement at the Nash Draw Pool. A detailed reservoir model of pilot area was developed, and enhanced recovery options, including waterflooding, lean gas, and carbon dioxide injection, are being evaluated.

  19. SPIRIT: A seamless phase I/II randomized design for immunotherapy trials.

    Science.gov (United States)

    Guo, Beibei; Li, Daniel; Yuan, Ying

    2018-06-07

    Immunotherapy-treatments that enlist the immune system to battle tumors-has received widespread attention in cancer research. Due to its unique features and mechanisms for treating cancer, immunotherapy requires novel clinical trial designs. We propose a Bayesian seamless phase I/II randomized design for immunotherapy trials (SPIRIT) to find the optimal biological dose (OBD) defined in terms of the restricted mean survival time. We jointly model progression-free survival and the immune response. Progression-free survival is used as the primary endpoint to determine the OBD, and the immune response is used as an ancillary endpoint to quickly screen out futile doses. Toxicity is monitored throughout the trial. The design consists of two seamlessly connected stages. The first stage identifies a set of safe doses. The second stage adaptively randomizes patients to the safe doses identified and uses their progression-free survival and immune response to find the OBD. The simulation study shows that the SPIRIT has desirable operating characteristics and outperforms the conventional design. Copyright © 2018 John Wiley & Sons, Ltd.

  20. Optimized FFTF Acceptance Test Program covering Phases III, IV, and V

    International Nuclear Information System (INIS)

    Wykoff, W.R.; Jones, D.H.

    1977-03-01

    A detailed review of Phases III, IV, and V of the FFTF Acceptance Test Program has been completed. The purpose of this review was to formulate that test sequence which not only meets requirements for safe, reliable and useful operation of the plant, but also results in the earliest prudent demonstration of full-power performance. A test sequence based on the underlying assumption that sodium flows into the secondary sodium storage tank (T-44) no later than August 31, 1978, is described in detail. A time-scale which allows extra time to put systems and equipment into operation the first time, debugging, and learning how to operate most effectively has been superimposed on the test sequence. Time is not included for major equipment malfunctions. This test plan provides the basis for coordinating the many and varied activities and interfaces necessary for successful and timely execution of the FFTF Acceptance Test Program. In this report, the need dates have been identified for presently scheduled test articles and standard core components

  1. Summary of Research through Phase II/Year 2 of Initially Approved 3 Phase/3 Year Project - Establishing the Relationship between Fracture-Related Dolomite and Primary Rock Fabric on the Distribution of Reservoirs in the Michigan Basin

    Energy Technology Data Exchange (ETDEWEB)

    G. Grammer

    2007-09-30

    This final scientific/technical report covers the first 2 years (Phases I and II of an originally planned 3 Year/3 Phase program). The project was focused on evaluating the relationship between fracture-related dolomite and dolomite constrained by primary rock fabric in the 3 most prolific reservoir intervals in the Michigan Basin. The characterization of select dolomite reservoirs was the major focus of our efforts in Phases I and II of the project. Structural mapping and log analysis in the Dundee (Devonian) and Trenton/Black River (Ordovician) suggest a close spatial relationship among gross dolomite distribution and regional-scale, wrench fault-related NW-SE and NE-SW structural trends. A high temperature origin for much of the dolomite in these 2 studied intervals (based upon fluid inclusion homogenization temperatures and stable isotopic analyses,) coupled with persistent association of this dolomite in reservoirs coincident with wrench fault-related features, is strong evidence for these reservoirs being influenced by hydrothermal dolomitization. In the Niagaran (Silurian), there is a general trend of increasing dolomitization shelfward, with limestone predominant in more basinward positions. A major finding is that facies types, when analyzed at a detailed level, are directly related to reservoir porosity and permeability in these dolomites which increases the predictability of reservoir quality in these units. This pattern is consistent with our original hypothesis of primary facies control on dolomitization and resulting reservoir quality at some level. The identification of distinct and predictable vertical stacking patterns within a hierarchical sequence and cycle framework provides a high degree of confidence at this point that the results should be exportable throughout the basin. Much of the data synthesis and modeling for the project was scheduled to be part of Year 3/Phase III, but the discontinuation of funding after Year 2 precluded those efforts

  2. Lexical Link Analysis Application: Improving Web Service to Acquisition Visibility Portal Phase III

    Science.gov (United States)

    2015-04-30

    ååì~ä=^Åèìáëáíáçå= oÉëÉ~êÅÜ=póãéçëáìã= qÜìêëÇ~ó=pÉëëáçåë= sçäìãÉ=ff= = Lexical Link Analysis Application: Improving Web Service to Acquisition...2015 2. REPORT TYPE 3. DATES COVERED 00-00-2015 to 00-00-2015 4. TITLE AND SUBTITLE Lexical Link Analysis Application: Improving Web Service...processes. Lexical Link Analysis (LLA) can help, by applying automation to reveal and depict???to decisionmakers??? the correlations, associations, and

  3. SF Bay Water Quality Improvement Fund: Projects and Accomplishments

    Science.gov (United States)

    San Francisco Bay Water Quality Improvement Fund (SFBWQIF) projects listed here are part of an EPA competitive grant program to improve SF Bay water quality focused on restoring impaired waters and enhancing aquatic resources.

  4. Improve services project -- Republic of the Marshall Islands.

    Science.gov (United States)

    Langidrik, J

    1995-01-01

    The Republic of the Marshall Islands has 60 dispensary sites, each staffed by 1 health assistant, to cover 80-800 people/site on 34 atolls. Until the spring of 1994, only curative services were available on a regular basis, and preventive services were provided by traveling health teams from the urban centers. In 1994, the health assistants in selected outer islands were trained to administer immunizations from vaccines which are sent regularly by air. Additional project sites are being selected. In 1993, 2 dispensaries initiated a project to 1) increase the number of women with access to prenatal care during the first trimester, 2) increase immunization levels, 3) improve access to preventive services, and 4) improve reporting and record-keeping systems. This project includes an important training component for the health assistant, the wife of the health assistant, the traditional birth attendant, the youth peer educator, community leaders, and a member of the local council. By 1994, this project was expanded to 13 dispensaries on 2 atolls. In 1995, 18 more dispensaries on 4 more atolls will be able to offer these additional services.

  5. Waste incineration models for operation optimization. Phase 1: Advanced measurement equipment for improved operation of waste fired plants; Affaldsforbraendingsmodeller til driftsoptimering. Fase 1: Avanceret maeleudstyr til forbedret drift af affaldsfyrede anlaeg

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2005-06-01

    This report describes results from the PSO projects ELTRA-5294 and ELTRA-5348: Waste incineration models for operation optimization. Phase 1, and Advanced measurement equipment for improved operation of waste fired plants. Phase 1. The two projects form the first step in a project course build on a long-term vision of a fully automatic system using a wide range of advanced measurement data, advanced dynamic models for prediction of operation and advanced regulation methods for optimization of the operation of waste incinerator plants. (BA)

  6. How can innovative project delivery systems improve the overall efficiency of GDOT in transportation project delivery?

    Science.gov (United States)

    2013-04-01

    The USDOT and Federal Highway Administration (FHWA) recommend the smart use of innovative project : delivery systems, such as design-build, to improve efficiency and effectiveness of developing transportation : projects. Although design-build provide...

  7. High-pressure single-crystal elasticity study of CO{sub 2} across phase I-III transition

    Energy Technology Data Exchange (ETDEWEB)

    Zhang, Jin S., E-mail: zhang72@illinois.edu; Bass, Jay D. [Department of Geology, University of Illinois, Urbana-Champaign, Illinois 61801 (United States); Shieh, Sean R. [Departments of Earth Sciences and Physics and Astronomy, University of Western Ontario, London, Ontario N6A 5B7 (Canada); Dera, Przemyslaw [Hawaii Institute of Geophysics and Planetology, University of Hawaii at Manoa, Honolulu, Hawaii 96822 (United States); Prakapenka, Vitali [Center for Advanced Radiation Sources, University of Chicago, Chicago, Illinois 60637 (United States)

    2014-04-07

    Sound velocities and elastic moduli of solid single-crystal CO{sub 2} were measured at pressures up to 11.7(3) GPa by Brillouin spectroscopy. The aggregate adiabatic bulk modulus (K{sub S}), shear modulus (G), and their pressure derivatives for CO{sub 2} Phase I are K{sub S0} = 3.4(6) GPa, G{sub 0} = 1.8(2) GPa, (dK{sub S}/dP){sub 0} = 7.8(3), (dG/dP){sub 0} = 2.5(1), (d{sup 2}K{sub S}/dP{sup 2}){sub 0} = −0.23(3) GPa{sup −1}, and (d{sup 2}G/dP{sup 2}){sub 0} = −0.10(1) GPa{sup −1}. A small increase of elastic properties was observed between 9.8(1) and 10.5(3) GPa, in agreement with the CO{sub 2} I-III transition pressure determined from previous x-ray diffraction experiments. Above the transition pressure P{sub T}, we observed a mixture dominated by CO{sub 2}-I, with minor CO{sub 2}-III. The CO{sub 2}-I + III mixture shows slightly increased sound velocities compared to pure CO{sub 2}-I. Elastic anisotropy calculated from the single-crystal elasticity tensor exhibits a decrease with pressure beginning at 7.9(1) GPa, which is lower than P{sub T}. Our results coincide with recent X-ray Raman observations, suggesting that a pressure-induced electronic transition is related to local structural and optical changes.

  8. 40 CFR 63.176 - Quality improvement program for pumps.

    Science.gov (United States)

    2010-07-01

    ... type (e.g., piston, horizontal or vertical centrifugal, gear, bellows); pump manufacturer; seal type... 40 Protection of Environment 9 2010-07-01 2010-07-01 false Quality improvement program for pumps... improvement program for pumps. (a) In Phase III, if, on a 6-month rolling average, the greater of either 10...

  9. Mid-Term Assessment of the activties of Fadama III development ...

    African Journals Online (AJOL)

    This paper assessed the activities of Fadama III project in Cross River State. It viewed the aim, objectives, achievements, perceptions of beneficiaries and challenges of the project in the state. It was discovered that Fadama III is aimed at increasing the income of rural land and water resource users, reduce rural poverty, ...

  10. Runaway electron damage to the Tore Supra Phase III outboard pump limiter

    International Nuclear Information System (INIS)

    Nygren, R.; Lutz, T.; Walsh, D.; Martin, G.; Chatelier, M.; Loarer, T.; Guilhem, D.

    1996-01-01

    Operation of the Phase III outboard pump limiter (OPL) in Tore Supra in 1994 was terminated prematurely when runaway electrons during the current decay following a disruption pierced leading edge tube on the electron side and caused a water leak. The location, about 20 mm outside the last closed flux surface during normal operation, and the infrared (IR) images of the limiter indicate that the runaways moved in large outward steps, i.e. tens of millimeters, in one toroidal revolution. For plasma (runaway) currents in the range of 155 to 250 kA, the drift orbits open to the outside. Basic trajectory computations suggest that such motion is possible under the conditions present for this experiment. Activation measurements made on sections of the tube to indicate the area of local damage are presented here. An understanding of this event may provide important guidance regarding the potential damage from runaways in future tokamaks

  11. Measures to improve nuclear power project management

    International Nuclear Information System (INIS)

    Ma Xinchao

    2012-01-01

    Focusing on correct application of ability level principle in setting organizational structure, the effective management system has been established, and 8 practical management regimes have been developed. Personnel training and management work shall be well done and enhanced. Experience feedback in construction management shall be well done for all systems. Exchange of construction and management techniques shall be actively carried out. All staff shall participate in safety management. KPI system is adopted for assessing stakeholders' project management method, and PDCA cycle is adopted for continued improved. Management level upgrading measures are proposed to ensure the smooth construction of nuclear power project. Setting forth and popularizing management theory can provide reference for and promote the smooth progress of various nuclear power projects. (author)

  12. Performance data from the ZEPLIN-III second science run

    International Nuclear Information System (INIS)

    Majewski, P; Edwards, B; Kalmus, G E; Lindote, A; Solovov, V N; Chepel, V; DeViveiros, L; Lopes, M I; Akimov, D Yu; Belov, V A; Burenkov, A A; Kobyakin, A S; Kovalenko, A G; Araújo, H M; Currie, A; Horn, M; Lebedenko, V N; Barnes, E J; Ghag, C; Hollingsworth, A

    2012-01-01

    ZEPLIN-III is a two-phase xenon direct dark matter experiment located at the Boulby Mine (U.K.). After its first science run in 2008 it was upgraded with: an array of low background photomultipliers, a new anti-coincidence detector system with plastic scintillator and an improved calibration system. After 319 days of data taking the second science run ended in May 2011. In this paper we describe the instrument performance with emphasis on the position and energy reconstruction algorithm and summarise the final science results.

  13. Improving the attractiveness of CDM projects through allowing and incorporating options

    International Nuclear Information System (INIS)

    Carmichael, David G.; Ballouz, Joseph J.; Balatbat, Maria C.A.

    2015-01-01

    The paper puts forward a proposal that, within Clean Development Mechanism (CDM) projects, investors be allowed to benefit from options; this will require a CDM rule change. Through the presence of options, the downside risk resulting from low carbon prices and/or low achieved emission reductions on projects can be limited, while any upside resulting from high carbon prices and/or high achieved emission reductions can be taken advantage of. It is demonstrated that the presence of options improves the financial attractiveness of CDM projects, and this is at no detriment to any stakeholder. The flow-on from the proposal is that more CDM projects should be realisable if options are available, and this in turn will lead to reduced global emissions and improved sustainability. The proposal is supported by the necessary theory and is demonstrated on two registered CDM projects, one on hydropower and one on wind power. - Highlights: • The paper proposes that options be allowed within CDM projects. • Introducing options will require a CDM rule change. • Options improve the financial attractiveness of CDM projects. • Allowing options comes at no cost or detriment to any party. • Allowing options is a win–win situation to both society and the project proponent.

  14. Ninety to Nothing: a PDSA quality improvement project.

    Science.gov (United States)

    Prybutok, Gayle Linda

    2018-05-14

    Purpose The purpose of this paper is to present a case study of a successful quality improvement project in an acute care hospital focused on reducing the time of the total patient visit in the emergency department. Design/methodology/approach A multidisciplinary quality improvement team, using the PDSA (Plan, Do, Study, Act) Cycle, analyzed the emergency department care delivery process and sequentially made process improvements that contributed to project success. Findings The average turnaround time goal of 90 minutes or less per visit was achieved in four months, and the organization enjoyed significant collateral benefits both internal to the organization and for its customers. Practical implications This successful PDSA process can be duplicated by healthcare organizations of all sizes seeking to improve a process related to timely, high-quality patient care delivery. Originality/value Extended wait time in hospital emergency departments is a universal problem in the USA that reduces the quality of the customer experience and that delays necessary patient care. This case study demonstrates that a structured quality improvement process implemented by a multidisciplinary team with the authority to make necessary process changes can successfully redefine the norm.

  15. Extraction of lanthanide(III) nitrates from water-salt solutions with n.-octanol

    International Nuclear Information System (INIS)

    Keskinov, V.A.; Kudrova, A.V.; Valueva, O.V.; Pyartman, A.K.

    2004-01-01

    Extraction of lanthanide(III) nitrates (Ln=La-Nd, Sm-Gd) from aqueous-salt solutions at 298.15 K was studied using solution of n.-octanol, its concentration 6.31 mol/l. It was ascertained that at Ln(NO 3 ) 3 concentration in aqueous phase below 0.6 mol/l, there is actually no extraction. At higher concentrations of nitrates in aqueous phase the content of lanthanides(III) in organic phase increases in the series La-Gd. Isotherms of extraction were ascertained, its phase equilibria being described mathematically. It is shown that extraction of lanthanide(III) nitrates with n.-octanol should be realized from concentrated aqueous solutions [ru

  16. Avoiding failure: tools for successful and sustainable quality-improvement projects

    International Nuclear Information System (INIS)

    Donnelly, Lane F.

    2017-01-01

    Involvement in successful and sustained quality improvement can be a very rewarding experience. However, it can be very difficult work. Up to 70% of attempted organizational change is not sustained. There are many reasons why quality-improvement projects might not be successful. In this article, the author reviews items associated with an increased or decreased likelihood of success. Such items have been categorized as structural issues, human issues and environmental context. This paper is intended to serve those embarking on quality-improvement projects as a resource to help position them for success. (orig.)

  17. Avoiding failure: tools for successful and sustainable quality-improvement projects

    Energy Technology Data Exchange (ETDEWEB)

    Donnelly, Lane F. [Texas Children' s Hospital, Department of Radiology, Houston, TX (United States)

    2017-06-15

    Involvement in successful and sustained quality improvement can be a very rewarding experience. However, it can be very difficult work. Up to 70% of attempted organizational change is not sustained. There are many reasons why quality-improvement projects might not be successful. In this article, the author reviews items associated with an increased or decreased likelihood of success. Such items have been categorized as structural issues, human issues and environmental context. This paper is intended to serve those embarking on quality-improvement projects as a resource to help position them for success. (orig.)

  18. Avoiding failure: tools for successful and sustainable quality-improvement projects.

    Science.gov (United States)

    Donnelly, Lane F

    2017-06-01

    Involvement in successful and sustained quality improvement can be a very rewarding experience. However, it can be very difficult work. Up to 70% of attempted organizational change is not sustained. There are many reasons why quality-improvement projects might not be successful. In this article, the author reviews items associated with an increased or decreased likelihood of success. Such items have been categorized as structural issues, human issues and environmental context. This paper is intended to serve those embarking on quality-improvement projects as a resource to help position them for success.

  19. The Phase I/II BNCT Trials at the Brookhaven medical research reactor: Critical considerations

    International Nuclear Information System (INIS)

    Diaz, A.Z.

    2001-01-01

    A phase I/II clinical trial of boronophenylalanine-fructose (BPA-F) mediated boron neutron capture therapy (BNCT) for Glioblastoma Multiforme (GBM) was initiated at Brookhaven National Laboratory (BNL) in 1994. Many critical issues were considered during the design of the first of many sequential dose escalation protocols. These critical issues included patient selection criteria, boron delivery agent, dose limits to the normal brain, dose escalation schemes for both neutron exposure and boron dose, and fractionation. As the clinical protocols progressed and evaluation of the tolerance of the central nervous system (CNS) to BPA-mediated BNCT at the BMRR continued new specifications were adopted. Clinical data reflecting the progression of the protocols will be presented to illustrate the steps taken and the reasons behind their adoption. (author)

  20. Phase II Results of RTOG 0537: A Phase II/III Study Comparing Acupuncture-like Transcutaneous Electrical Nerve Stimulation Versus Pilocarpine in Treating Early Radiation-Induced Xerostomia

    Science.gov (United States)

    Wong, Raimond K. W.; James, Jennifer L.; Sagar, Stephen; Wyatt, Gwen; Nguyen-Tân, Phuc Felix; Singh, Anurag K.; Lukaszczyk, Barbara; Cardinale, Francis; Yeh, Alexander M.; Berk, Lawrence

    2011-01-01

    Purpose This phase II component of a multi-institutional phase II/III randomized trial assessed the feasibility and preliminary efficacy of acupuncture-like transcutaneous electrical nerve stimulation (ALTENS) in reducing radiation-induced xerostomia. Methods Head and neck cancer patients who were 3–24 months from completing radiotherapy ± chemotherapy (RT±C) and experiencing xerostomia symptoms with basal whole saliva production ≥0.1 ml/min and without recurrence were eligible. Patients received twice weekly ALTENS sessions (24 over 12 weeks) using a Codetron™ unit. The primary objective assessed the feasibility of ALTENS treatment. A patient was considered compliant if 19/24 ALTENS were delivered, with a targeted 85% compliance rate. Secondary objectives measured treatment-related toxicities and ALTENS effect on overall radiation-induced xerostomia burden using the University of Michigan Xerostomia-Related Quality of Life Scale (XeQOLS). Results Of 48 accrued patients, 47 were evaluable. Median age was 60 years; 84% were male, 70% completed RT±C for > 12 months and 21% had received prior pilocarpine. All ALTENS sessions were completed in 34 patients, but 9 and 1 completed 20–23 and 19 sessions respectively, representing a 94% total compliance rate. 6-month XeQOLS scores were available for 35 patients; 30 (86%) achieved a positive treatment response with a mean reduction of 35.9% (SD 36.1). Five patients developed grade 1–2 gastrointestinal toxicity and one had grade 1 pain event. Conclusions ALTENS treatment for radiation-induced xerostomia can be uniformly delivered in a cooperative multicenter setting and has possible beneficial treatment response. Given these results, the phase III component of this study was initiated. PMID:22252927