WorldWideScience

Sample records for electric station unit

  1. Evaluation of Waterford Steam Electric Station Unit 3 technical specifications

    International Nuclear Information System (INIS)

    Baxter, D.E.; Bruske, S.J.

    1985-09-01

    This document was prepared for the Nuclear Regulatory Commission (NRC) to assist them in determining whether the Waterford Steam Electric Station Unit 3 Technical Specifications (T/S), which govern plant systems configurations and operations, are in conformance with the requirements of the Final Safety Analysis Report (FSAR) as amended, and the requirements of the Safety Evaluation Report (SER) as supplemented. A comparative audit of the FSAR as amended, and the SER as supplemented was performed with the Waterford T/S. Several discrepancies were identified and subsequently resolved by the cognizant NRC reviewer. Pending completion of the resolutions noted in Part 3 of this report, the Waterford Steam Electric Station Unit 3 T/S, to the extent reviewed, are in conformance with the FSAR and SER

  2. Main unit electrical protection at Sizewell 'B' power station

    International Nuclear Information System (INIS)

    Fischer, A.; Keates, T.

    1992-01-01

    For any power station, reliable electrical protection of the main generating units (generators plus generator transformers) has important commercial implications. Spurious trips cause loss of generation and consequent loss of revenue, while failure to rapidly isolate a fault leads to unnecessary damage and again, loss of generation and revenue. While these conditions apply equally to Sizewell B there are additional factors to be taken into consideration. A spurious trip of a main generating unit may lead to a trip of the reactor with an associated challenge to the shutdown and core cooling plant. The generator transformers, besides exporting power from the generators to the 400 kV National Grid, also import power from the Grid to the 11 kV Main Electrical System, which in turn is the preferred source of supply to the Essential Electrical System. The Main Unit Protection is designed to clear generator faults leaving this off-site power route intact. Hence failure to operate correctly could affect the integrity of the Essential Electrical Supplies. (Author)

  3. MINAC radiography performed on susquehanna Steam Electric Station Unit 1

    International Nuclear Information System (INIS)

    Bognet, J.C.

    1986-01-01

    Ten welds were volumetrically examined with a manual and automated ultrasonic (UT) system during a Susquehanna Steam Electric Station (SES) Unit 1 preservice inspection. The automated system had been recently developed and several problems were encountered in this first field application. The ten welds examined had a Sweepolet-to-Risor weld configuration, which further complicated the examination effort. This weld configuration has corrosion-resistant cladding applied to the outside and inside circumference and, as a result of an installation/removal/reinstallation sequence during plant construction, is often referred to as the double weld. After several attempts to obtain interpretable UT data failed (e.g., repeatable data), the examination effort was terminated. PP and L opted to pursue using the Miniature Linear Accelerator (MINAC) to perform radiographic examination. The results were referenced in the Susquehanna SES Unit 1 outage summary report and submitted to the NRC. The total effort was viewed as a complete success with no impact to the overall outage duration. All welds previously attempted by automated and manual UT were successfully examined using the MINAC

  4. Commerical electric power cost studies. Capital cost addendum multi-unit coal and nuclear stations

    International Nuclear Information System (INIS)

    1977-09-01

    This report is the culmination of a study performed to develop designs and associated capital cost estimates for multi-unit nuclear and coal commercial electric power stations, and to determine the distribution of these costs among the individual units. This report addresses six different types of 2400 MWe (nominal) multi-unit stations as follows: Two Unit PWR Station-1139 MWe Each, Two Unit BWR Station-1190 MWe Each, Two Unit High Sulfur Coal-Fired Station-1232 MWe Each, Two Unit Low Sulfur Coal-Fired Station-1243 MWe Each, Three Unit High Sulfur Coal-Fired Station-794 MWe Each, Three Unit Low Sulfur Coal-Fired Station-801 MWe Each. Recent capital cost studies performed for ERDA/NRC of single unit nuclear and coal stations are used as the basis for developing the designs and costs of the multi-unit stations. This report includes the major study groundrules, a summary of single and multi-unit stations total base cost estimates, details of cost estimates at the three digit account level and plot plan drawings for each multi-unit station identified

  5. Technical Specifications, Comanche Peak Steam Electric Station, Unit 1 (Docket No. 50-445)

    International Nuclear Information System (INIS)

    1990-04-01

    The Technical Specifications for Comanche Peak Steam Electric Station, Unit 1 were prepared by the US Nuclear Regulatory Commission. They set forth the limits, operating conditions, and other requirements applicable to a nuclear reactor facility, as set forth in Section 50.36 of Title 10 of the Code of Federal Regulations Part 50, for the protection of the health and safety of the public

  6. Construction of Shika Nuclear Power Station Unit No.2 of the Hokuriku Electric Power Co., Inc

    International Nuclear Information System (INIS)

    Yamanari, Shozo; Miyahara, Ryohei; Umezawa, Takeshi; Teshiba, Ichiro

    2006-01-01

    Construction of the Shika Nuclear Power Station Unit No.2 of the Hokuriku Electric Power Co., Inc. (advanced boiling-water reactor; output: 1.358 mega watts) was begun in August 1999 and it will resume commercial operation in March 2006 as scheduled. Hitachi contributed effectually toward realizing the project with supply of a complete set of the advanced nuclear reactor and turbine-generator system with the latest design and construction technology in harmony. Large-scale modular structures for installation and a computer-aided engineering system for work procedure and schedule management were applied with the utmost priority placed on work efficiency, safety and quality assurance. (T.Tanaka)

  7. Alteration in reactor installation (addition of Unit 2) in Shimane Nuclear Power Station, Chugoku Electric Power Co., Inc. (inquiry)

    International Nuclear Information System (INIS)

    1983-01-01

    An inquiry was made by the Ministry of International Trade and Industry to Nuclear Safety Commission on the addition of Unit 2 in Shimane Nuclear Power Station of The Chugoku Electric Power Co., Inc., concerning the technical capability of Chugoku Electric Power Co., Inc., and the plant safety. The NSC requested the Committee on Examination of Reactor Safety to make a deliberation on this subject. Both the technical capability and the safety of Unit 1 were already confirmed by MITI. Unit 2 to be newly added in the Shimane Nuclear Power Station is a BWR power plant with electric output of 820 MW. The examination made by MITI is described: the technical capability of Chugoku Electric Power Co., Inc., the safety of Unit 2 about its siting, reactor proper, reactor cooling system, radioactive waste management, etc. (J.P.N.)

  8. Space Station Freedom electrical power system hardware commonality with the United States Polar Platform

    Science.gov (United States)

    Rieker, Lorra L.; Haraburda, Francis M.

    1989-01-01

    Information is presented on how the concept of commonality is being implemented with respect to electric power system hardware for the Space Station Freedom and the U.S. Polar Platform. Included is a historical account of the candidate common items which have the potential to serve the same power system functions on both Freedom and the Polar Platform. The Space Station program and objectives are described, focusing on the test and development responsibilities. The program definition and preliminary design phase and the design and development phase are discussed. The goal of this work is to reduce the program cost.

  9. Combined Solar Charging Stations and Energy Storage Units Allocation for Electric Vehicles by Considering Uncertainties

    DEFF Research Database (Denmark)

    Yousefi Khanghah, Babak; Anvari-Moghaddam, Amjad; Guerrero, Josep M.

    2017-01-01

    Electric vehicles (EVs) are becoming a key feature of smart grids. EVs will be embedded in the smart grids as a mobile load-storage with probabilistic behavior. In order to manage EVs as flexible loads, charging stations (CSs) have essential roles. In this paper, a new method for optimal sitting...... are considered based on time-of-use (TOU) demand response programs (DRPs). In order to solve the optimization problem considering uncertainty of load growth, electricity price, initial state of charge of batteries and solar power generation, genetic algorithm method using Monte-Carlo simulation is used...

  10. Safety Evaluation Report related to the operation of Waterford Steam Electric Station, Unit No. 3 (Docket No. 50-382)

    International Nuclear Information System (INIS)

    1985-03-01

    Supplement 10 to the Safety Evaluation Report for the application filed by Louisiana Power and Light Company for a license to operate the Waterford Steam Electric Station, Unit 3 (Docket No. 50-382), located in St. Charles Parish, Louisiana, has been prepared by the Office of Nuclear Reactor Regulation of the US Nuclear Regulatory Commission. The purpose of this supplement is to update the Safety Evaluation Report by providing the staff's evaluation of information submitted by the licensee since the Safety Evaluation Report and its nine previous supplements were issued

  11. Safety Evaluation Report related to the operation of Comanche Peak Steam Electric Station, Unit 2 (Docket No. 50-446)

    International Nuclear Information System (INIS)

    1992-09-01

    This document supplement 25 to the Safety Evaluation Report related to the operation of the Comanche Peak Steam Electric Station (CPSES), Unit 2 (NUREG-0797), has been prepared by the Office of Nuclear Reactor Regulation of the US Nuclear Regulatory Commission (NRC). The facility is located in Somervell County, Texas, approximately 40 miles southwest of Fort Worth, Texas. This supplement reports the status of certain issues that had not been resolved when the Safety Evaluation Report and Supplements 1, 2, 3, 4, 6, 12, 21, 22, 23, and 24 to that report were published. This supplement deals primarily with Unit 2 issues; however, it also references evaluations for several Unit 1 licensing items resolved since Supplement 24 was issued

  12. Safety Evaluation Report related to the operation of Comanche Peak Steam Electric Station, Unit 2 (Docket No. 50-446)

    International Nuclear Information System (INIS)

    1993-02-01

    Supplement 26 to the Safety Evaluation Report related to the operation of the Comanche Peak Steam Electric Station (CPSES), Unit 2, has been prepared by the Office of Nuclear Reactor Regulation of the US Nuclear Regulatory Commission (NRC). The facility is located in Somervell County, Texas, approximately 40 miles southwest of Fort Worth, Texas. This supplement reports the status of certain issues that had not been resolved when the Safety Evaluation Report and Supplements 1, 2, 3, 4, 6, 12, 21, 22, 23, 24, and 25 to that report were published. This supplement deals primarily with Unit 2 issues; however, it also references evaluations for several licensing issues that relate to Unit 1, which have been resolved since Supplement 25 was issued

  13. Technical specifications: Susquehanna Steam Electric Station, Unit No. 2 (Docket No. 50-388). Appendix A to License No. NPF-22

    International Nuclear Information System (INIS)

    1984-03-01

    Susquehanna Steam Electric Station, Unit 2 Technical Specifications were prepared by the US Nuclear Regulatory Commission to set forth the limits, operating conditions, and other requirements applicable to a nuclear reactor facility as set forth in Section 50.36 of 10 CFR Part 50 for the protection of the health and safety of the public

  14. VT Data - Electric Charging Stations

    Data.gov (United States)

    Vermont Center for Geographic Information — Locations of Electric Charging Stations provided by the NREL national laboratory of the U.S. Department of Energy, Office of Energy Efficiency and Renewable Energy....

  15. Safety evaluation report related to the operation of Susquehanna Steam Electric Station, Units 1 and 2 (Docket Nos. 50-387 and 50-388). Suppl.6

    International Nuclear Information System (INIS)

    1984-03-01

    In April 1981, the staff of the Nuclear Regulatory Commission issued its Safety Evaluation Report (NUREG-0776) regarding the application of the Pennsylvania Power and Light Company (the applicant and/or licensee) and the Allegheny Electric Cooperative, Inc. (co-applicant) for licenses to operate the Susquehanna Steam Electric Station, Units 1 and 2, located on a site in Luzerne County, Pennsylvania. This supplement to NUREG-0776 addresses the remaining issues that required resolution before licensing operation of Unit 2 and closes them out

  16. 78 FR 32278 - Vogtle Electric Generating Station, Units 3 and 4; Southern Nuclear Operating Company; Change to...

    Science.gov (United States)

    2013-05-29

    ... Generating Station, Units 3 and 4; Southern Nuclear Operating Company; Change to Information in Tier 1, Table... Nuclear Operating Company, Inc., and Georgia Power Company, Oglethorpe Power Corporation, Municipal... Table 3.3-1, ``Definition of Wall Thicknesses for Nuclear Island Buildings, Turbine Buildings, and Annex...

  17. Autonomous Electrical Vehicles’ Charging Station

    OpenAIRE

    Józef Paska; Mariusz Kłos; Łukasz Rosłaniec; Rafał Bielas; Magdalena Błędzińska

    2016-01-01

    This paper presents a model of an autonomous electrical vehicles’ charging station. It consists of renewable energy sources: wind turbine system, photovoltaic cells, as well as an energy storage, load, and EV charging station. In order to optimise the operating conditions, power electronic converters were added to the system. The model was implemented in the Homer Energy programme. The first part of the paper presents the design assumptions and technological solutions. Further in the paper...

  18. Final environmental statement related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2: (Docket Nos. 50-445 and 50-446)

    International Nuclear Information System (INIS)

    1981-09-01

    The proposed action is the issuance of operating licenses to the Texas Utilities Generating Company for the startup and operation of Units 1 and 2 of the Comanche Peak Steam Electric Station located on Squaw Creek Reservoir in Somervell County, Texas, about 7 km north-northeast of Glen Rose, Texas, and about 65 km southwest of Fort Worth in north-central Texas. The information in this environmental statement represents the second assessment of the environmental impact associated with the Comanche Peak Steam Electric Station pursuant to the guidelines of the National Environmental Policy Act of 1969 (NEPA) and 10 CFR Part 51 of the Commission's Regulations. After receiving an application to construct this station, the staff carried out a review of impact that would occur during its construction and operation. This evaluation was issued as a Final Environmental Statement -- Construction Phase. After this environmental review, a safety review, an evaluation by the Advisory Committee on Reactor Safeguards, and public hearings in Glen Rose, Texas, the US Atomic Energy Commission (now US Nuclear Regulatory Commission) issued construction permits for the construction of Units 1 and 2 of the Comanche Peak Steam Electric Station. 16 figs., 34 tabs

  19. Final Environmental Statement related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445 and 50-446)

    International Nuclear Information System (INIS)

    1989-10-01

    In September 1981, the staff of the Nuclear Regulatory Commission (NRC) issued its Final Environmental Statement (NUREG-0775) related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445 and 50-446), located in Somervell County, Texas, approximately 40 miles southwest of Fort Worth, Texas. The NRC has prepared this supplement to NUREG-0775 to present its evaluation of the alternative of operating Comanche Peak with the installation of further severe-accident-mitigation design features. The NRC has discovered no substantial changes in the proposed action as previously evaluated in the Final Environmental Statement that are relevant to environmental concerns and bearing on the licensing of Comanche Peak Steam Electric Station, Units 1 and 2. 6 refs., 3 tabs

  20. Safety evaluation report related to the operation of Waterford Steam Electric Station, Unit No. 3 (Docket No. 50-382). Supplement No. 7

    International Nuclear Information System (INIS)

    1984-09-01

    Supplement 7 to the Safety Evaluation Report for Louisiana Power and Light's application for a license to operate Waterford Steam Electric Station, Unit 3 (Docket No. 50-382), located in St. Charles Parish, Louisiana, has been jointly prepared by the Office of Nuclear Reactor Regulation and the Region IV Office of the US Nuclear Regulatory Commission. This supplement provides the results to date of the staff's evaluation of approximately 350 allegations and concerns of poor construction practices at the Waterford 3 facility

  1. Technical evaluation report on the adequacy of station electric-distribution-system voltages for the Millstone Nuclear Power Station, Units 1 and 2. Docket Nos. 50-245, 50-336

    International Nuclear Information System (INIS)

    Selan, J.C.

    1983-01-01

    This report documents the technical evaluation of the adequacy of the station electric-distribution-system voltages for the Millstone Nuclear Power Station, Units 1 and 2. The evaluation is to determine if the onsite distribution system, in conjunction with the offsite power sources, has sufficient capacity to automatically start and operate all Class 1E loads within the equipment voltage ratings under certain conditions established by the Nuclear Regulatory Commission. The analyses submitted demonstrate that adequate voltages will be supplied to the Class 1E equipment under the worst-case conditions analyzed

  2. Safety Evaluation Report related to the operation of Waterford Steam Electric Station, Unit No. 3 (Docket No. 50-382). Supplement No. 8

    International Nuclear Information System (INIS)

    1984-12-01

    Supplement 8 to the Safety Evaluation Report for the application filed by Louisiana Power and Light Company for a license to operate the Waterford Steam Electric Station, Unit 3 (Docket No. 50-382), located in St. Charles Parish, Louisiana, has been prepared by the Office of Nuclear Reactor Regulation of the Nuclear Regulatory Commission. The purpose of this supplement is to update the Safety Evaluation Report by providing the staff's evaluation of information submitted by the applicant since the Safety Evaluation Report and its seven previous supplements were issued

  3. Safety-evaluation report related to the operation of Waterford Steam Electric Station, Unit No. 3. Docket No. 50-382

    International Nuclear Information System (INIS)

    1983-06-01

    Supplement 5 to the Safety Evaluation Report for the application filed by Louisiana Power and Light Company for a license to operate the Waterford Steam Electric Station, Unit 3 (Docket No. 50-382), located in St. Charles Parish, Louisiana has been prepared by the Office of Nuclear Reactor Regulation of the Nuclear Regulatory Commission. The purpose of this supplement is to update the Safety Evaluation Report by providing the staff's evaluation of information submitted by the applicant since the Safety Evaluation Report and its four previous Supplements were issued

  4. Safety evaluation report related to the operation of Waterford Steam Electric Station, Unit No. 3 (Docket No. 50-382). Suppl.6

    International Nuclear Information System (INIS)

    1984-06-01

    Supplement 6 to the Safety Evaluation Report for the application filed by Louisiana Power and Light Company for a license to operate the Waterford Steam Electric Station, Unit 3 (Docket No. 50-382), located in St. Charles Parish, Louisiana, has been prepared by the Office of Nuclear Reactor Regulation of the Nuclear Regulatory Commission. The purpose of this supplement is to update the Safety Evaluation Report by providing the staff's evaluation of information submitted by the applicant since the Safety Evaluation Report and its five previous supplements were issued

  5. Technical evaluation report on the monitoring of electric power to the reactor protection system for the Nine Mile Point Nuclear Station, Unit 1 (Docket No. 50-220)

    International Nuclear Information System (INIS)

    Selan, J.C.

    1984-01-01

    This report documents the technical evaluation of the monitoring of electric power to the reactor protection system (RPS) at the Nine Mile Point Nuclear Station, Unit 1. The evaluation is to determine if the proposed design modification will protect the RPS from abnormal voltage and frequency conditions which could be supplied from the power supplies and will meet certain requirements set forth by the Nuclear Regulatory Commission. The proposed design modifications will protect the RPS from sustained abnormal voltage and frequency conditions from the supplying sources

  6. Safety Evaluation Report related to the operation of Waterford Steam Electric Station, Unit No. 3 (Docket No. 50-382). Supplement 9

    International Nuclear Information System (INIS)

    1984-12-01

    Supplement 9 to the Safety Evaluation Report for Louisiana Power and Light's application for a license to operate Waterford Steam Electric Station, Unit 3 (Docket No. 50-382), located in St. Charles Parish, Louisiana, has been jointly prepared by the Office of Nuclear Reactor Regulation and the Region IV Office of the US Nuclear Regulatory Commission. This supplement provides the results of the staff's completion of its evaluation of approximately 350 allegations and concerns of poor construction practices at the Waterford 3 facility

  7. Alteration in reactor installations (Unit 1 and 2 reactor facilities) in the Hamaoka Nuclear Power Station of The Chubu Electric Power Co., Inc. (report)

    International Nuclear Information System (INIS)

    1982-01-01

    A report by the Nuclear Safety Commission to the Ministry of International Trade and Industry concerning the alteration in Unit 1 and 2 reactor facilities in the Hamaoka Nuclear Power Station, Chubu Electric Power Co., Inc., was presented. The technical capabilities for the alteration of reactor facilities in Chubu Electric Power Co., Inc., were confirmed to be adequate. The safety of the reactor facilities after the alteration was confirmed to be adequate. The items of examination made for the confirmation of the safety are as follows: reactor core design (nuclear design, mechanical design, mixed reactor core), the analysis of abnormal transients in operation, the analysis of various accidents, the analysis of credible accidents for site evaluation. (Mori, K.)

  8. Safety Evaluation Report related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2. Docket Nos. 50-445 and 50-446

    International Nuclear Information System (INIS)

    1983-03-01

    Supplement No. 3 to the Safety Evaluation Report (SER) related to the operation of the Comanche Peak Steam electric Station, Units 1 and 2, has been prepared by the Office of Nuclear Reactor Regulation of the US Nuclear Regulatory Commission. the facility is located in Somervell County, Texas. Subject to favorable resolution of the items identified in this supplement, the staff concludes that the facility can be operated by the applicatn without endangering the health and safety of the public. This document provides the NRC staff's evaluation of the outstanding and confirmatory issues that have been resolved since Supplement No. 2 was issued in January 1982, and addresses changes to the SER and its earlier supplements which have resulted from the receipt of additonal information from the applicant during the period of January throught October 1982

  9. Safety evaluation report related to the operation of Susquehanna Steam Electric Station, Units 1 and 2. Docket Nos. 50-387 and 50-388, Pennsylvania Power and Light Company and Allegheny Electric Cooperative, Inc

    International Nuclear Information System (INIS)

    1982-11-01

    In April 1981, the staff of the Nuclear Regulatory Commission issued its Safety Evaluation Report (NUREG-0776) regarding the application of the Pennsylvania Power and Light Company (the licensee) and the Allegheny Electric Cooperative, Inc. (co-licensee) for licenses to operate the Susquehanna Steam Electric Station, Units 1 and 2, located on a site in Luzerne County, Pennsylvania. Supplement 1, issued in June 1981, addressed outstanding issues. Supplement 2, issued in September 1981, contains the ACRS Report and responses. Supplement 3, issued in July 1982, contains the resolution to five items previously identified as open and closes them out. On July 17, 1982, License NPF-14 was issued to allow Unit 1 operation at power levels not to exceed 5% of rated power. This supplement discusses the resolution of several license conditions that have been met

  10. Safety evaluation report related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445 and 50-446)

    International Nuclear Information System (INIS)

    1988-11-01

    Supplement 19 to the Safety Evaluation Report related to the operation of the Comanche Peak Steam Electric Station (CPSES), Units 1 and 2 (NUREG-0797), has been prepared by the Office of Special Projects of the US Nuclear Regulatory Commission (NRC). The facility is located in Somervell County, Texas, approximately 40 miles southwest of Fort Worth, Texas. This supplement presents the staff's evaluation of the Texas Utilities Electric Company's (lead applicant's) corrective action program (CAP) related to equipment qualification. The scope and methodology for the CAP workscope, as summarized in Revision 0 to the Equipment Qualification Project Status Report and as detailed in related documents, were developed to resolve various issues raised by the Comanche Peak Response Team (CPRT) and the NRC staff to ensure that plant equipment is appropriately environmentally and/or seismically and dynamically qualified and documented in accordance with the validated plant design resulting from other CAP scopes of work for Unit 1 and areas common to Units 1 and 2. The staff concludes that the CAP workscope for equipment qualification provides a comprehensive program for resolving the concerns identified by the CPRT and the NRC staff, including issues raised in the Comanche Peak Safety Evaluation Report and its supplements, and its implementation will ensure that the environmental and/or seismic and dynamic qualification of equipment at CPSES satisfies the validated plant design and the applicable requirements of 10 CFR Part 50. As is routine staff practice, the NRC staff will verify the adequacy of implementation of the environmental and seismic and dynamic equipment qualification program at CPSES during inspections that will take place before fuel loading. 97 refs

  11. Safety evaluation report related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2: Docket No. 50-445 and 50-446

    International Nuclear Information System (INIS)

    1988-11-01

    Supplement 20 to the Safety Evaluation Report related to the operation of the Comanche Peak Steam Electric Station (CPSES), Units 1 and 2 (NUREG-0797), has been prepared by the Office of Special Projects of the US Nuclear Regulatory Commission (NRC). The facility is located in Somervell County, Texas, approximately 40 miles southwest of Fort Worth, Texas. This supplement presents the staff's evaluation of CPRT implementation of the Comanche Peak Response Team (CPRT) Program Plan and the issue-specific action plans (ISAPs), as well as the CPRT's investigations to determine the adequacy of various types of programs and hardware at CPSES. The results and conclusions of the CPRT activities are documented in a results report for each ISAP, a Collective Evaluation Report (CER), and a Collective Significance Report (CSR). This supplement also presents the staff's safety evaluation of TU Electric's root cause assessment of past CPSES design deficiencies and weaknesses. The NRC staff concludes that the CPRT has adequately implemented its investigative activities related to the design, construction, construction quality assurance/quality control, and testing at CPSES. The NRC staff further concludes that the CPRT evaluation of the results of its investigation is thorough and complete and its recommendations for corrective actions are sufficient to resolve identified deficiencies

  12. 77 FR 21815 - South Carolina Electric And Gas Company (Virgil C. Summer Nuclear Station Units 2 and 3); Order...

    Science.gov (United States)

    2012-04-11

    ... (or its counsel or representative) to digitally sign documents and access the E-Submittal server for... fuel pool contained the highest heat load of the six units with the full core present in the spent fuel... adequate evidence but on mere suspicion, unfounded allegations, or error. All documents filed in NRC...

  13. Safety Evaluation Report related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445 and 50-446)

    International Nuclear Information System (INIS)

    1990-02-01

    Supplement 23 to the Safety Evaluation Report related to the operation of the Comanche Peak Steam Electric Station (CPSES), Units 1 and 2 (NUREG-0797), has been prepared by the Office of Nuclear Reactor Regulation of the US Nuclear Regulatory Commission (NRC). The facility is located in Somervell County, Texas, approximately 40 miles southwest of Fort Worth, Texas. This supplement reports the status of certain issues that had not been resolved when the Safety Evaluation Report and supplements 1, 2, 3, 4, 6, 12, 21, and 22 to that report were published. This supplement also includes the evaluations for licensing items resolved since Supplement 22 was issued. Supplement 5 has not been issued. Supplements 7, 8, 9, 10, and 11 were limited to the staff evaluation of allegations investigated by the NRC Technical Review Team. Supplement 13 presented the staff's evaluation of the Comanche Peak Response Team (CPRT) Program Plan, which was formulated by the applicant to resolve various construction and design issues raised by sources external to TU Electric. Supplements 14 through 19 presented the staff's evaluation of the CPSES Corrective Action Program: large- and small-bore piping and pipe supports (Supplement 14); cable trays and cable tray hangers (Supplement 15); conduit supports (Supplement 16); mechanical, civil/structural, electrical, instrumentation and controls, and systems portions of the heating, ventilation, and air conditioning (HVAC) system workscopes (Supplement 17); HVAC structural design (Supplement 18); and equipment qualification (Supplement 19). Supplement 20 presented the staff's evaluation of the Comanche Peak Response Team implementation of the CPRT Program

  14. Safety evaluation report related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445 and 50-446)

    International Nuclear Information System (INIS)

    1990-04-01

    Supplement 24 to the Safety Evaluation Report related to the operation of the Comanche Peak Steam Electric Station (CPSES), Units 1 and 2 (NUREG-0797), has been prepared by the Office of Nuclear Reactor Regulation of the US Nuclear Regulatory Commission (NRC). The facility is located in Somervell County, Texas, approximately 40 miles southwest of Fort Worth, Texas. This supplement reports the status of certain issues that had not been resolved when the Safety Evaluation Report and Supplements 1, 2, 3, 4, 6, 12, 21, 22, and 23 to that report were published. This supplement also includes the evaluations for licensing items resolved since Supplement 23 was issued. Supplement 5 has not been issued. Supplements 7, 8, 9, 10, and 11 were limited to the staff evaluation of allegations investigated by the NRC Technical Review Team. Supplement 13 represented the staff's evaluation of the Comanche Peak Response Team (CPRT) Program Plan, which was formulated by the applicant to resolve various construction and design issues raised by sources external to TU Electric. Supplements 14 through 19 presented the staff's evaluation of the CPSES Corrective Action Program: large- and small-bore piping and pipe supports (Supplement 14); cable trays and cable tray hangers (Supplement 15); conduit supports (Supplement 16); mechanical, civil/structural, electrical, instrumentation and controls, and systems portions of the heating, ventilation, and air conditioning (HVAC) system workscopes (Supplement 17); HVAC structural design (Supplement 18); and equipment qualification (Supplement 19). Supplement 20 presented the staff's evaluation of the CPRT implementation of its Program Plan and the issue-specific action plans, as well as the CPRT's investigations to determine the adequacy of various types of programs and hardware at CPSES

  15. Systematic evaluation program review of NRC safety topic VII-2 associated with the electrical, instrumentation and control portions of the ESF system control logic and design for the Dresden Station, Unit II nuclear power plant

    International Nuclear Information System (INIS)

    St Leger-Barter, G.

    1980-11-01

    This report documents the technical evaluation and review of NRC Safety Topic VII-2, associated with the electrical, instrumentation, and control portions of the ESF system control logic and design for the Dresden Station Unit II nuclear power plant, using current licensing criteria

  16. Technical evaluation report on the adequacy of station electric distribution system voltages for the Point Beach Nuclear Plant, Units 1 and 2. (Docket Nos. 50-266, 50-301)

    International Nuclear Information System (INIS)

    White, R.L.

    1983-01-01

    This report documents the technical evaluation of the adequacy of the station electric distribution system voltages for the Point Beach Nuclear Plant, Units 1 and 2. The evaluation is to determine if the onsite distribution system, in conjunction with the offsite power sources, has sufficient capacity to automatically start and operate all Class 1E loads within the equipment voltage ratings under certain conditions established by the Nuclear Regulatory Commission. For the worst case conditions study submitted by the licensee, it was shown that the station electric distribution system voltages would be adequate to start and operate 4160-volt and 480-volt Class 1E loads and their associated low voltage controls

  17. Safety evaluation report related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2: Docket Nos. 50-445 and 50-446

    International Nuclear Information System (INIS)

    1988-07-01

    Supplement 15 to the Safety Evaluation Report related to the operation of the Comanche Peak Steam Electric Station (CPSES), Units 1 and 2 (NUREG-0797), has been prepared by the Office of Special Projects of the US Nuclear Regulatory Commission (NRC). The facility is located in Somervell County, Texas, approximately 40 miles southwest of Fort Worth, Texas. This supplement presents the staff's evaluation of the applicant's Corrective Action Program (CAP) related to the design of cable trays and cable tray hangers. The scope and methodologies for the CAP workscope as summarized in Revision O to the cable tray and cable tray hanger project status report and as detailed in related documents referenced in this evaluation were developed to resolve various design issues raised by the Atomic Safety and Licensing Board (ASLB) the intervenor, Citizens Association for Sound Energy (CASE); the Comanche Peak Response Team (CPRT); CYGNA Energy Services (CYGNA); and the NRC staff. The NRC staff concludes that the CAP workscope for cable trays and cable tray hangers provides a comprehensive program for resolving the associated technical concerns identified by the ASLB, CASE, CPRT, CYGNA, and the NRC staff and its implementation ensures that the design of cable trays and cable tray hangers at CPSES satisfies the applicable requirements of 10 CFR Part 50

  18. Safety evaluation report related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445 and 50-446)

    International Nuclear Information System (INIS)

    1988-11-01

    Supplement 18 to the Safety Evaluation Report related to the operation of the Comanche Peak Steam Electric Station (CPSES), Units 1 and 2 (NUREG-0797), has been prepared by the Office of Special Projects of the US Nuclear Regulatory Commission (NRC). The facility is located in Somervell County, Texas, approximately 40 miles southwest of Fort Worth, Texas. This supplement presents the staff's evaluation of the applicant's Corrective Action Program (CAP) related to the structural design of the heating, ventilation, and air conditioning (HVAC) systems. The scope and methodologies for the CAP workscope as summarized in Revision 0 to the HVAC project status report and as detailed in related documents referenced in this evaluation were developed to resolve the technical concerns identified in the HVAC area. The NRC staff concludes that the CAP workscope for the HVAC structural design provides a comprehensive program for resolving the associated technical concerns and its implementation ensures that the structural design of the HVAC systems at CPSES satisfies the applicable requirements of 10 CFR Part 50. 32 refs

  19. Safety Evaluation Report related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445 and 50-446)

    International Nuclear Information System (INIS)

    1990-01-01

    Supplement 22 to the Safety Evaluation Report related to the operation of the Comanche Peak Steam Electric Station, Units 1 and 2 (NUREG-0797), has been prepared by the Office of Nuclear Reactor Regulation of the US Nuclear Regulatory Commission. The facility is located in Somervell County, Texas, approximately 40 miles southwest of Fort Worth, Texas. This supplement reports the status of certain issues that had not been resolved at the time of publication of the Safety Evaluation Report and Supplements 1, 2, 3, 4, 6, 12, and 21 to that report. This supplement also includes the evaluations for licensing items resolved since Supplement 21 was issued. Supplement 5 has been cancelled. Supplements 7 through 11 were limited to the staff evaluation of allegations investigated by the NRC Technical Review Team. Supplement 13 presented the staff's evaluation of the Comanche Peak Response Team (CPRT) Program Plan, which was formulated by the applicant to resolve various construction and design issues raised by sources external to the applicant. Supplements 14 through 20 presented the staff's evaluation of the applicant's Corrective Action Program and CPRT activities. Items identified in Supplements 7, 8, 9, 10, 11, 13, 14, and 15 through 20 are not included in this supplement, except to the extent that they affect the applicant's Final Safety Analysis Report. 154 refs., 24 figs., 8 tabs

  20. Safety evaluation report related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445 and 50-446)

    International Nuclear Information System (INIS)

    1988-03-01

    Supplement 14 to the Safety Evaluation Report related to the operation of the Comanche Peak Stam Electric Station (CPSES), Units 1 and 2 (NUREG-0797), has been prepared by the Office of Special Projects of the US Nuclear Regulatory Commission (NRC). The facility is located in Somerville County, Texas, approximately 40 miles southwest of Fort Worth, Texas. This supplement presents the staff's evaluation of the applicants' Corrective Action Program (CAP0 related to large ans small bore piping and pipe supports. The scope and methodologies for CAP workshop as summarized in revision O to the large and small bore piping project status reports and as detailed in related documents referenced in this evaluation were developed to resolve various design issues raised by the Atomic Safety and Licensing Board (ASLB);the intervenor, Citizens Association for Sound Energy (CASE);the Camanche Peak Response Team (CPRT);SYGNA Energy Services (CYGNA);and the NRC staff. The NRC staff concludes that the CAP workscopes for large and small bore piping provide a comprehensive program for resolving the associated technical concerns identified by the ASLB, CASE, CPRT, CYGNA, and the NRC staff and their implementation ensures that the design of large and small bore piping and pipe supports at CPSES satisfies the applicable requirements of 10 CFR 50

  1. Final Environmental Statement related to the operation of Wolf Creek Generating Station, Unit No. 1. Docket No. STN 50-482, Kansas Gas and Electric Company, et al

    International Nuclear Information System (INIS)

    1982-06-01

    This final environmental statement contains the second assessment of the environmental impact associated with operation of Wolf Creek Generating Station Unit 1 pursuant to the National Environmental Policy Act of 1969 (NEPA) and 10 CFR Part 51, as amended, of the NRC's regulations. This statement examines: the affected environment, environmental consequences and mitigating actions, and environmental and economic benefits and costs. Land use and terrestrial- and aquatic-ecological impacts will be small. Air-quality impacts will also be small. However, steam fog from the station's cooling lake has the potential for reducing visibility over nearby roads and bridges. A fog-monitoring program for roads and bridges near the lake has been recommended. Impacts to historic and prehistoric sites will be negligible. Chemical discharges to the Neosho River are expected to have no appreciable impacts on water quality under normal conditions and will be required to meet conditions of the station's NPDES permit. The effects of routine operations, energy transmission, and periodic maintenance of rights-of-way and transmission line facilities should not jeopardize any populations of endangered or threatened species. No significant impacts are anticipated from normal operational releases of radioactivity. The risk associated with accidental radiation exposure is very low. The net socioeconomic effects of the project will be beneficial. The action called for is the issuance of an operating license for the Wolf Creek Generating Station Unit 1

  2. Final environmental statement related to the operation of Limerick Generating Station, Units 1 and 2, Docket Nos. 50-352 and 50-353, Philadelphia Electric Company

    International Nuclear Information System (INIS)

    1989-08-01

    In April 1984 the staff of the Nuclear Regulatory Commission issued its Final Environmental Statement (NUREG-0974) related to the operation of Limerick Generating Station, Units 1 and 2, (Docket Nos. 50-352 and 50-353), located on the Schuylkill River, near Pottstown, in Limerick Township, Montgomery and Chester Counties, Pennsylvania. The NRC has prepared this supplement to NUREG-0974 to present its evaluation of the alternative of facility operation with the installation of further severe accident mitigation design features. The NRC staff has discovered no substantial changes in the proposed action as previously evaluated in the Final Environmental Statement that are relevant to environmental concerns nor significant new circumstances or information relevant to environmental concerns and bearing on the licensing of Limerick Generating Station, Units 1 and 2. 15 refs., 10 tabs

  3. FIND: Douglas Point Nuclear Generating Station, Units 1 and 2

    International Nuclear Information System (INIS)

    Moore, M.M.

    1975-12-01

    This index is presented as a guide to microfiche items 1 through 136 in Docket 50448, which was assigned to Potomac Electric Power Company's Application for Licenses to construct and operate Douglas Point Nuclear Generating Station, Units 1 and 2. Information received from August, 1973 through July, 1975 is included

  4. Preoperation of Hamaoka Nuclear Power Station Unit No. 4

    International Nuclear Information System (INIS)

    Fukuyo, Tadashi; Kurata, Satoshi

    1994-01-01

    Chubu Electric Power Co. finished preoperation of Hamaoka Nuclear Power Station Unit No. 4 in September, 1993. Although unit 4 has the same reactor design as unit 3, its rated electrical output (1,137MW) is 37MW more than that of unit 3. This increase was achieved mainly by adopting a Moisture Separater Heater in the turbine system. We started preoperation of unit 4 in November 1992 and performed various tests at electrical outputs of 20%, 50%, 75%, and 100%. We finished preoperation without any scram or other major problems and obtained satisfactory results for the functions and performance of the plant. This paper describes the major results of unit 4 preoperation. (author)

  5. Improving nuclear generating station response for electrical grid islanding

    International Nuclear Information System (INIS)

    Chou, Q.B.; Kundur, P.; Acchione, P.N.; Lautsch, B.

    1989-01-01

    This paper describes problems associated with the performance characteristics of nuclear generating stations which do not have their overall plant control design functions co-ordinated with the other grid controls. The paper presents some design changes to typical nuclear plant controls which result in a significant improvement in both the performance of the grid island and the chances of the nuclear units staying on-line following the disturbance. This paper focuses on four areas of the overall unit controls and turbine governor controls which could be modified to better co-ordinate the control functions of the nuclear units with the electrical grid. Some simulation results are presented to show the performance of a typical electrical grid island containing a nuclear unit with and without the changes

  6. Station black out of Fukushima Daiichi Nuclear Power Station Unit 1 was not caused by tsunamis

    International Nuclear Information System (INIS)

    Ito, Yoshinori

    2013-01-01

    Station black out (SBO) of Fukushima Daiichi Nuclear Power Station Unit 1 would be concluded to be caused before 15:37 on March 11, 2011 because losses of emergency ac power A system was in 15:36 and ac losses of B system in 15:37 according to the data published by Tokyo Electric Power Co. (TEPCO) in May 10, 2013. Tsunami attacked the site of Fukushima Daiichi Nuclear Power Station passed through the position of wave amplitude meter installed at 1.5 km off the coast after 15:35 and it was also recognized tsunami arrived at the coast of Unit 4 sea side area around in 15:37 judging from a series of photographs taken from the south side of the site and general knowledge of wave propagation. From a series of photographs and witness testimony, tsunami didn't attack Fukushima Daiichi Nuclear Power Station uniformly and tsunami's arrival time at the site of Unit 1 would be far later than arrival time at the coast of Unit 4 sea side area, which suggested it would be around in 15:39. TEPCO insisted tsunami passed through 1.5 km off the coast around in 15:33 and clock of wave amplitude meter was incorrect, which might be wrong. Thus SBO of Fukushima Daiichi Nuclear Power Station Unit 1 occurred before tsunami's arrival at the site of Unit 1 and was not caused by tsunami. (T. Tanaka)

  7. Safety Evaluation Report related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445 and 50-446). Supplement No. 7

    International Nuclear Information System (INIS)

    1985-01-01

    Supplement 7 to the Safety Evaluation Report for the Texas Utilities Electric Company application for a license to operate Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445, 50-446), located in Somervell County, Texas, has been jointly prepared by the Office of Nuclear Reactor Regulation and the Comanche Peak Technical Review of the US Nuclera Regulatory Commission. This supplement provides the results of the staff's evaluation and resolution of approximately 80 technical concerns and allegations in the areas of Electric/Instrumentation and Test Programs regarding construction and plant readiness testing practices at the Comanche Peak facility. Issues raised during Atomic Safety and Licensing Board hearings will be dealt with in future supplements to the Safety Evaluation Report

  8. Selection of persons expressing opinions etc. and attendants in the public hearing concerning the alteration in reactor installations (addition of Unit 3 and 4) in the Genkai Nuclear Power Station of Kyushu Electric Power Co., Inc

    International Nuclear Information System (INIS)

    1984-01-01

    The Nuclear Safety Commission has selected 18 persons expressing opinions etc. and 255 (other) attendants for the public hearing on the alteration of reactor installations (addition of Unit 3 and 4) in Kyushu Electric's Genkai Nuclear Power Station to be held on June 18th, 1984. The order of expressing opinions etc., number of reception, names, addresses, ages and occupations are given of the persons expressing opinions etc. For both the groups, against the selected numbers there are given applicants etc. in number by towns and city. (Mori, K.)

  9. Holding of the public hearing concerning the alteration in reactor installations (addition of Unit 3 and 4) in the Genkai Nuclear Power Station of Kyushu Electric Power Co., Inc

    International Nuclear Information System (INIS)

    1984-01-01

    The Nuclear Safety Commission held a public hearing concerning the addition of Unit 3 and 4 in Kyushu Electric's Genkai Nuclear Power Station in Karatsu City, Saga prefecture, on June 18th, 1984. The selected persons (and other attendants) expressed opinions etc. and personnel in the Ministry of International Trade and Industry answered them. Results of the public hearing are to be taken into conservation in NSC's safety examination. The following are described concerning the public hearing held: date and place, participants, hearing program, documents distributed, names of the persons expressing opinions etc. and the respective summary items of opinions etc. (Mori, K.)

  10. Electric motorcycle charging station powered by solar energy

    Science.gov (United States)

    Siriwattanapong, Akarawat; Chantharasenawong, Chawin

    2018-01-01

    This research proposes a design and verification of an off-grid photovoltaic system (PVS) for electric motorcycle charging station to be located in King’s Mongkut’s University of Technology Thonburi, Bangkok, Thailand. The system is designed to work independently (off-grid) and it must be able to fully charge the batteries of a typical passenger electric motorcycle every evening. A 1,000W Toyotron electric motorcycle is chosen for this study. It carries five units of 12.8V 20Ah batteries in series; hence its maximum energy requirement per day is 1,200Wh. An assessment of solar irradiation data and the Generation Factor in Bangkok, Thailand suggests that the charging system consists of one 500W PV panel, an MPPT charge controller, 48V 150Ah battery, a 1,000W DC to AC inverter and other safety devices such as fuses and breakers. An experiment is conducted to verify the viability of the off-grid PVS charging station by collecting the total daily energy generation data in the raining season and winter. The data suggests that the designed off-grid solar power charging station for electric motorcycle is able to supply sufficient energy for daily charging requirements.

  11. Safety Evaluation Report related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445 and 50-446). Supplement No. 8

    International Nuclear Information System (INIS)

    1985-02-01

    Supplement 8 to the Safety Evaluation Report for the Texas Utilities Electric Company application for a license to operate Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445, 50-446), located in Somervell County, Texas, has been jointly prepared by the Office of Nuclear Reactor Regulation and the Comanche Peak Technical Review Team of the US Nuclear Regulatory Commission. This Supplement provides the results of the staff's evaluation and resolution of approximately 80 technical concerns and allegations relating to civil and structural and miscellaneous issues regarding construction and plant readiness testing practices at the Comanche Peak facility. Issues raised during recent Atomic Safety and Licensing Board hearings will be dealt with in future supplements to the Safety Evaluation Report

  12. Antenna unit and radio base station therewith

    Science.gov (United States)

    Kuwahara, Mikio; Doi, Nobukazu; Suzuki, Toshiro; Ishida, Yuji; Inoue, Takashi; Niida, Sumaru

    2007-04-10

    Phase and amplitude deviations, which are generated, for example, by cables connecting an array antenna of a CDMA base station and the base station, are calibrated in the baseband. The base station comprises: an antenna apparatus 1; couplers 2; an RF unit 3 that converts a receive signal to a baseband signal, converts a transmit signal to a radio frequency, and performs power control; an A/D converter 4 for converting a receive signal to a digital signal; a receive beam form unit 6 that multiplies the receive signal by semi-fixed weight; a despreader 7 for this signal input; a time-space demodulator 8 for demodulating user data; a despreader 9 for probe signal; a space modulator 14 for user data; a spreader 13 for user signal; a channel combiner 12; a Tx calibrater 11 for controlling calibration of a signal; a D/A converter 10; a unit 16 for calculation of correlation matrix for generating a probe signal used for controlling an Rx calibration system and a TX calibration system; a spreader 17 for probe signal; a power control unit 18; a D/A converter 19; an RF unit 20 for probe signal; an A/D converter 21 for signal from the couplers 2; and a despreader 22.

  13. Handling of views and opinions by staters and others in a public hearing on alteration in reactor installation (addition of Unit 2) in the Sendai Nuclear Power Station of Kyushu Electric Power Co., Inc

    International Nuclear Information System (INIS)

    1981-01-01

    A public hearing on the addition of Unit 2 in the Sendai Nuclear Power Station, Kyushu Electric Power Co., Inc., was held on July 17, 1980, in Sendai City, Kagoshima Prefecture. The views and opinions by the local staters and those by the notification of statement were expressed concerning its nuclear safety. The handling of these views and opinions by the Nuclear Safety Commission is explained. The most important in this action is the instruction by the NSC to the Committee on Examination of Reactor Safety to reflect the results of the public hearing to the reactor safety examination of the Unit 2 installation by the CERS. The views and opinions expressed in this connection are summarized as follows: the sitting conditions, the safety design of the reactor plant, and the release of radioactive materials, involving such aspects as earthquakes, accidents and radioactive waste management. (J.P.N.)

  14. FIND: Fort Calhoun Station, Unit 2

    International Nuclear Information System (INIS)

    Williams, W.H.

    1976-07-01

    This index is presented for the microfiche material of Docket 50548 which concerns the application of Omaha Public Power District to build and operate Fort Calhoun Station, Unit 2. The information includes both application and review material dated from September 1975 through March 1976. There are five amendments to the PSAR and one supplement to the ER which have been incorporated by reference into the respective reports. Docket RESAR-3 is used as a reference for portions of the PSAR

  15. Treatment of opinions, etc. in the public hearing on the alteration of reactor installation (addition of Unit 2) in the Shimane Nuclear Power Station of The Chugoku Electric Power Company, Inc

    International Nuclear Information System (INIS)

    1983-01-01

    The Nuclear Safety Commission has acknowledged the governmental policy, and further decided on the treatment of the opinions expressed by the local people in the public hearing held in May, 1983, in Shimane Prefecture on the addition of Unit 2 to the Shimane Nuclear Power Station, Chugoku Electric Power Co., Inc. The NSC has directed the Committee on Examination of Reactor Safety to take into consideration the opinions in its later examination. The opinions expressed by the local people in the form of question are given as follows: siting conditions (earthquake, ground, weather, etc.), the safety design for reactor installation (general aspect, aseismatic design, core design, ECCS, the teaching of TMI accident, etc.), radioactive wastes, radiation exposure, site evaluation. (Mori, K.)

  16. Considerations of the opinions and others in the public hearing on the alteration in reactor installation (addition of Unit 3) in the Hamaoka Nuclear Power Station of the Chubu Electric Power Co., Inc

    International Nuclear Information System (INIS)

    1982-01-01

    A public hearing was held in Hamaoka Town, Shizuoka Prefecture, on the alteration in reactor installation, i.e., the addition of Unit 3 in the Hamaoka Nuclear Power Station, Chubu Electric Power Co., Inc., on March 19, 1981, by the Nuclear Safety Commission. The opinions and others stated by the local people were taken into consideration in the governmental examinations on the installation, etc. The considerations of such opinions principally in the examinations by NSC are explained in the form of questions (i.e. opinion, etc.) and answers (i.e. considerations) as follows: site conditions (earthquakes, ground, hydraulic features, etc.), the safety design of the reactor facilities (overall plant, aseismic design, the control of inflammable gas concentration, radioactive waste treatment, the reflection of accident experiences, etc.), radioactive waste management, radiation exposure relation, the technical capabilities of personnel (operation, etc.). (J.P.N.)

  17. Treatment and management of opinions stated in and notified to the public hearing on the alteration in reactor installation (addition of Unit 3) in the Hamaoka Nuclear Power Station of The Chubu Electric Power Co., Ltd

    International Nuclear Information System (INIS)

    1981-01-01

    A public hearing was made in Hamaoka Town, Shizuoka Prefecture, on March 19, 1981, on the addition of Unit 3 in the Hamaoka Nuclear Power Station, Chubu Electric Power Co., Inc. Treatment and management of the opinions and others stated and notified by the local people, which are understood and to be carried out by the Nuclear Safety Commission, are: to publish them as the report of the public hearing, to include them in the safety examination report of NSC and to refer to them in the examination by the Committee on Examination of Reactor Safety, etc. The opinions and others stated and notified in the public hearing, to which CERS should refer in its examination, are summarized in the form of the questions on siting conditions, safety design of reactor installation, release of radioactivities, etc. (J.P.N.)

  18. Safety evaluation report related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445 and 50-446): Supplement No. 21

    International Nuclear Information System (INIS)

    1989-04-01

    Supplement 21 to the Safety Evaluation Report related to the operation of the Comanche Peak Steam Electric Station (CPSES), Units 1 and 2 (NUREG-0797), has been prepared by the Office of Nuclear Reactor Regulation of the US Nuclear Regulatory Commission (NRC). The facility is located in Somervell County, Texas, approximately 40 miles southwest of Fort Worth, Texas. This supplement reports the status of certain issues that had not been resolved when the Safety Evaluation Report and Supplements 1, 2, 3, 4, 6, and 12 to that report were published. This supplement also lists the new issues that have been identified since Supplement 12 was issued and includes the evaluations for licensing items resolved in this interim period. 21 refs

  19. Safety Evaluation Report related to the operation of Wm. H. Zimmer Nuclear Power Station, Unit No. 1. Docket No. 50-358. Cincinnati Gas and Electric Company

    International Nuclear Information System (INIS)

    1982-08-01

    Information is presented concerning site characteristics; design criteria for structures, systems, and components; reactor; reactor coolant system and connected systems; engineered safety features; instrumentation and controls; electric power; auxiliary systems; conduct of operations; and TMI-2 requirements

  20. Electric machinery and drives in thermal power stations

    International Nuclear Information System (INIS)

    1974-01-01

    The following subjects were dealt with during the VDE meeting: 1) Requirements made by the electric network on the generators and their excitation equipment, and the influence thereof on their design; 2) requirements made by the power station process on the electric drives and the influence thereof on type and design; 3) requirements made on protective measures from the point of the electric power station machinery. (TK) [de

  1. Tampa Electric Company Polk Power Station IGCC project: Project status

    Energy Technology Data Exchange (ETDEWEB)

    McDaniel, J.E.; Carlson, M.R.; Hurd, R.; Pless, D.E.; Grant, M.D. [Tampa Electric Co., FL (United States)

    1997-12-31

    The Tampa Electric Company Polk Power Station is a nominal 250 MW (net) Integrated Gasification Combined Cycle (IGCC) power plant located to the southeast of Tampa, Florida in Polk County, Florida. This project is being partially funded under the Department of Energy`s Clean Coal Technology Program pursuant to a Round II award. The Polk Power Station uses oxygen-blown, entrained-flow IGCC technology licensed from Texaco Development Corporation to demonstrate significant reductions of SO{sub 2} and NO{sub x} emissions when compared to existing and future conventional coal-fired power plants. In addition, this project demonstrates the technical feasibility of commercial scale IGCC and Hot Gas Clean Up (HGCU) technology. The Polk Power Station achieved ``first fire`` of the gasification system on schedule in mid-July, 1996. Since that time, significant advances have occurred in the operation of the entire IGCC train. This paper addresses the operating experiences which occurred in the start-up and shakedown phase of the plant. Also, with the plant being declared in commercial operation as of September 30, 1996, the paper discusses the challenges encountered in the early phases of commercial operation. Finally, the future plans for improving the reliability and efficiency of the Unit in the first quarter of 1997 and beyond, as well as plans for future alternate fuel test burns, are detailed. The presentation features an up-to-the-minute update on actual performance parameters achieved by the Polk Power Station. These parameters include overall Unit capacity, heat rate, and availability. In addition, the current status of the start-up activities for the HGCU portion of the plant is discussed.

  2. Poultry litter power station in the United Kingdom

    International Nuclear Information System (INIS)

    Anon.

    1995-01-01

    Poultry litter has presented a waste disposal problem to the poultry industry in many parts of the United Kingdom. The plant at Eye is a small to medium scale power station, fired using poultry litter. The 12.7 MW of electricity generated is supplied, through the local utility, to the National Grid. The spent litter that constitutes the fuel is made up of excrement and animal bedding (usually 90% excrement and 10% straw or wood shavings). It comes from large climate-controlled buildings (broiler houses) where birds, reared for meat production, are allowed to roam freely. (UK)

  3. Electric Vehicle Charging Stations as a Climate Change Mitigation Strategy

    Science.gov (United States)

    Cave, Bridget; DeYoung, Russell J.

    2014-01-01

    In order to facilitate the use of electric vehicles at NASA Langley Research Center (LaRC), charging stations should be made available to LaRC employees. The implementation of charging stations would decrease the need for gasoline thus decreasing CO2 emissions improving local air quality and providing a cost savings for LaRC employees. A charging station pilot program is described that would install stations as the need increased and also presents a business model that pays for the electricity used and installation at no cost to the government.

  4. Safety Evaluation Report related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445 and 50-446). Supplement No. 11

    International Nuclear Information System (INIS)

    1985-05-01

    Supplement 11 to the Safety Evaluation Report for the Texas Utilities Electric Company application for a license to operate Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445, 50-446), located in Somervell County, Texas, has been jointly prepared by the Office of Nuclear Reactor Regulation and the Comanche Peak Technical Review Team (TRT) of the US Nuclear Regulatory Commission (NRC) and is in two parts. Part 1 (Appendix 0) of this supplement provides the results of the TRT's evaluation of approximately 124 concerns and allegations relating specifically to quality assurance and quality control (QA/QC) issues regarding construction proctices at the Comanche Peak facility. Part 2 (Appendix P) contains an overall summary and conclusion of the QA/QC aspects of the NRC Technical Review Team efforts as reported in supplemental Safety Evaluation Report SERs 7, 8, 9, and 10. Since QA/QC issues are also contained in each of the other supplements, the TRT considered that such a summary and conclusion from all supplements was necessary for a complete TRT description of QA/QC activities at Comanche Peak

  5. The System of Fast Charging Station for Electric Vehicles with Minimal Impact on the Electrical Grid

    Directory of Open Access Journals (Sweden)

    Petr Chlebis

    2016-01-01

    Full Text Available The searching and utilization of new energy sources and technologies is a current trend. The effort to increase the share of electricity production from renewable energy sources is characteristic for economically developed countries. The use of accumulation of electrical energy with a large number of decentralized storage units is most preferred, as well as the focus on the production of energy at the point of its consumption. Modern cogeneration units are a good example. This paper describes the accumulation of electrical energy for equalizing the power balance of electric charging stations with high instantaneous power. The possibility of re-utilization of electrical energy from the charged vehicle in the case of lack of electricity in the power grid is solved at the same time. This paper also deals with the selection of appropriate concept of accumulation system and its cooperation with both renewable and distribution networks. Details of the main power components including the results obtained from the system implementation are also described in this paper.

  6. Operation of Grand Gulf Nuclear Station, Units 1 and 2, Dockets Nos. 50-416 and 50-417: Mississippi Power and Light Company, Middle South Energy, Inc., South Mississippi Electric Power Association. Final environmental statement

    International Nuclear Information System (INIS)

    1981-09-01

    The information in this Final Environmental Statement is the second assessment of the environmental impacts associated with the construction and operation of the Grand Gulf Nuclear Station, Units 1 and 2, located on the Mississippi River in Claiborne County, Mississippi. The Draft Environmental Statement was issued in May 1981. The first assessment was the Final Environmental Statement related to construction, which was issued in August 1973 prior to issuance of the Grand Gulf Nuclear Station construction permits. In September 1981 Grand Gulf Unit 1 was 92% complete and Unit 2 was 22% complete. Fuel loading for Unit 1 is scheduled for December 1981. The present assessment is the result of the NRC staff review of the activities associated with the proposed operation of the Station, and includes the staff responses to comments on the Draft Environmental Statement

  7. Space Station Freedom power - A reliability, availability, and maintainability assessment of the proposed Space Station Freedom electric power system

    Science.gov (United States)

    Turnquist, S. R.; Twombly, M.; Hoffman, D.

    1989-01-01

    A preliminary reliability, availability, and maintainability (RAM) analysis of the proposed Space Station Freedom electric power system (EPS) was performed using the unit reliability, availability, and maintainability (UNIRAM) analysis methodology. Orbital replacement units (ORUs) having the most significant impact on EPS availability measures were identified. Also, the sensitivity of the EPS to variations in ORU RAM data was evaluated for each ORU. Estimates were made of average EPS power output levels and availability of power to the core area of the space station. The results of assessments of the availability of EPS power and power to load distribution points in the space stations are given. Some highlights of continuing studies being performed to understand EPS availability considerations are presented.

  8. Safety Evaluation Report related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445 and 50-446). Supplement No. 13

    International Nuclear Information System (INIS)

    1986-05-01

    Supplement 13 to the Safety Evaluation Report related to the operation of Comanche Peak Steam Electric Station (CPSES), Units 1 and 2 (NUREG-0797), has been prepared by the Office of Nuclear Reactor Regulation of the US Nuclear Regulatory Commission (NRC). The facility is located in Somervell County, Texas, approximately 40 miles southwest of Fort Worth, Texas. This supplement presents the staff's evaluation of the Comanche Peak Response Team (CPRT) Program Plan which was formulated by the applicant to resolve various construction and design issues raised by the Atomic Safety and Licensing Board, allegers, intervenor Citizens Association for Sound Energy (CASE), NRC inspections of various types, and Cygna Energy Services while conducting its independent design assessment. The NRC staff concludes that the CPRT Program Plan provides an overall structure for addressing all existing issues and any future issues which may be identified from further evaluations, and if properly implemented will provide important evidence of the design and construction quality of CPSES, and will identify any needed corrective action. The report identifies items to be addressed by the NRC staff during the implementation phase

  9. 76 FR 40754 - Duke Energy Carolinas, LLC Catawba Nuclear Station, Units 1 and 2; McGuire Nuclear Station, Units...

    Science.gov (United States)

    2011-07-11

    ... NUCLEAR REGULATORY COMMISSION [NRC-2011-0100; Docket Nos. 50-413 and 50-414; Docket Nos. 50-369 and 50-370; Docket Nos. 50-269, 50-270, And 50-287] Duke Energy Carolinas, LLC Catawba Nuclear Station, Units 1 and 2; McGuire Nuclear Station, Units 1 and 2; Oconee Nuclear Station, Units 1, 2, and 3; Notice...

  10. Resilient design of recharging station networks for electric transportation vehicles

    Energy Technology Data Exchange (ETDEWEB)

    Kris Villez; Akshya Gupta; Venkat Venkatasubramanian

    2011-08-01

    As societies shift to 'greener' means of transportation using electricity-driven vehicles one critical challenge we face is the creation of a robust and resilient infrastructure of recharging stations. A particular issue here is the optimal location of service stations. In this work, we consider the placement of battery replacing service station in a city network for which the normal traffic flow is known. For such known traffic flow, the service stations are placed such that the expected performance is maximized without changing the traffic flow. This is done for different scenarios in which roads, road junctions and service stations can fail with a given probability. To account for such failure probabilities, the previously developed facility interception model is extended. Results show that service station failures have a minimal impact on the performance following robust placement while road and road junction failures have larger impacts which are not mitigated easily by robust placement.

  11. Reducing lighting electricity use in underground metro stations

    International Nuclear Information System (INIS)

    Casals, Miquel; Gangolells, Marta; Forcada, Núria; Macarulla, Marcel

    2016-01-01

    Highlights: • Lighting systems are big energy consumers in underground metro stations. • An adaptive lighting system strategy is developed for underground stations. • Dimming controls are based on station occupancy levels and maintenance cycles. • The k-means clustering technique is used to identify stations’ occupancy patterns. • Savings were found to amount to 255.47 MW h in 2 years for a case study metro network. - Abstract: Lighting systems are usually one of the largest electrical end-uses in underground metro stations. Taking into account that budget restrictions in publicly owned companies hinder energy efficiency retrofit projects that require high initial investments, affordable energy saving strategies are needed. This paper presents a low-cost approach for reducing lighting electricity use in underground stations, without affecting passengers’ comfort or the metro operator’s service. For this purpose, an adaptive lighting strategy of dimming the illuminance levels of artificial light sources has been developed. Dimming controls are based on the occupancy of the station, and the preventive maintenance and cleaning cycles of the luminaires. The stations’ monthly occupancy patterns are defined through the k-means clustering technique. To illustrate its effectiveness, the method was applied to 115 underground stations of the Barcelona metro network. The results revealed overall electricity savings of 255.47 MW h on a biannual basis, which represents 36.22% of the stations’ baseline lighting consumption. Individual energy savings were found to range from 25 to 87.5 MW h/year in the stations of the Barcelona metro network, depending on the number and profile of station users. The research findings will undoubtedly be useful for the future energy efficiency project plans of worldwide metro operators and managers of other underground spaces.

  12. Evolutionary growth for Space Station Freedom electrical power system

    Science.gov (United States)

    Marshall, Matthew Fisk; Mclallin, Kerry; Zernic, Mike

    1989-01-01

    Over an operational lifetime of at least 30 yr, Space Station Freedom will encounter increased Space Station user requirements and advancing technologies. The Space Station electrical power system is designed with the flexibility to accommodate these emerging technologies and expert systems and is being designed with the necessary software hooks and hardware scars to accommodate increased growth demand. The electrical power system is planned to grow from the initial 75 kW up to 300 kW. The Phase 1 station will utilize photovoltaic arrays to produce the electrical power; however, for growth to 300 kW, solar dynamic power modules will be utilized. Pairs of 25 kW solar dynamic power modules will be added to the station to reach the power growth level. The addition of solar dynamic power in the growth phase places constraints in the initial Space Station systems such as guidance, navigation, and control, external thermal, truss structural stiffness, computational capabilities and storage, which must be planned-in, in order to facilitate the addition of the solar dynamic modules.

  13. Electric vehicle station equipment for grid-integrated vehicles

    Science.gov (United States)

    Kempton, Willett; Kiamilev, Fouad; McGee, Rodney; Waite, Nick

    2017-09-05

    Methods, systems, and apparatus transferring power between the grid and an electric vehicle are disclosed. The apparatus may include at least one vehicle communication port for interfacing with electric vehicle equipment (EVE) and a processor coupled to the at least one vehicle communication port to establish communication with the EVE, receive EVE attributes from the EVE, and transmit electric vehicle station equipment (EVSE) attributes to the EVE. Power may be transferred between the grid and the electric vehicle by maintaining EVSE attributes, establishing communication with the EVE, and transmitting the EVSE maintained attributes to the EVE.

  14. Electrical power systems for Space Station

    Science.gov (United States)

    Simon, W. E.

    1984-01-01

    Major challenges in power system development are described. Evolutionary growth, operational lifetime, and other design requirements are discussed. A pictorial view of weight-optimized power system applications shows which systems are best for missions of various lengths and required power level. Following definition of the major elements of the electrical power system, an overview of element options and a brief technology assessment are presented. Selected trade-study results show end-to-end system efficiencies, required photovoltaic power capability as a function of energy storage system efficiency, and comparisons with other systems such as a solar dynamic power system.

  15. Impact of Electric Vehicle Charging Station Load on Distribution Network

    Directory of Open Access Journals (Sweden)

    Sanchari Deb

    2018-01-01

    Full Text Available Recent concerns about environmental pollution and escalating energy consumption accompanied by the advancements in battery technology have initiated the electrification of the transportation sector. With the universal resurgence of Electric Vehicles (EVs the adverse impact of the EV charging loads on the operating parameters of the power system has been noticed. The detrimental impact of EV charging station loads on the electricity distribution network cannot be neglected. The high charging loads of the fast charging stations results in increased peak load demand, reduced reserve margins, voltage instability, and reliability problems. Further, the penalty paid by the utility for the degrading performance of the power system cannot be neglected. This work aims to investigate the impact of the EV charging station loads on the voltage stability, power losses, reliability indices, as well as economic losses of the distribution network. The entire analysis is performed on the IEEE 33 bus test system representing a standard radial distribution network for six different cases of EV charging station placement. It is observed that the system can withstand placement of fast charging stations at the strong buses up to a certain level, but the placement of fast charging stations at the weak buses of the system hampers the smooth operation of the power system. Further, a strategy for the placement of the EV charging stations on the distribution network is proposed based on a novel Voltage stability, Reliability, and Power loss (VRP index. The results obtained indicate the efficacy of the VRP index.

  16. Clean coal technology project to Polk Power Station, Tampa Electric Company, Florida, Volume 1: Report

    International Nuclear Information System (INIS)

    1994-06-01

    Tampa Electric Company proposes to construct and operate a 1,150-MW power station in southwestern Polk County, Florida. The proposed Polk Power Station would require an EPA NPDES permit for a new source and would include a 260-MW IGCC unit as a DOE Clean Coal Technology demonstration project. This EIS document assesses the proposed project and alternatives with respect to environmental impacts. Mitigative measures are also evaluated for the preferred alternative. Included in this Volume I are the following: alternatives including Tampa Electric Companies proposed project (preferred alternative with DOE financial assistance); affected environment; environmental consequences of the alternatives

  17. Environmental qualification test of electrical penetration for nuclear power stations

    International Nuclear Information System (INIS)

    Kooziro, Tetsuya; Nakagawa, Akitoshi; Toyoda, Shigeru; Uno, Shunpei

    1979-01-01

    Environmental qualification test was conducted according to IEEE Std. 323-1974 in order to evaluate the safety and reliability of electrical penetration of PWR type nuclear power station. Electrical penetration is the assemblies of electric cables attached to the containment vessel and penetrate through the vessel. Since it is a part of the vessel, it is deemed to be one of the primary safety equipments that are important for the safety and reliability of nuclear power stations. Environmental tests were conducted continuously as to heat cycle, vibration and LOCA with the full size specimens of bushing type, pigtail type and triaxial cable type and at the same time thermal life and irradiation tests were conducted on the insulation materials used, in order to obtain the comprehensive evaluation of their electrical and mechanical characteristics. As the result, they all satisfied the requirements for the circuits for actual use during and after various environmental qualification tests according to IEEE Std. 323. (author)

  18. Utilization of waste heat from electricity generating stations

    International Nuclear Information System (INIS)

    Robertson, R.F.S.

    1977-06-01

    Historically the nuclear power station has been designed solely as an electricity producer. But in Canada today only 15 percent of our energy consumption is as electricity. The non-electrical needs today are supplied almost entirely by natural gas and oil. There is an incentive to see whether a nuclear station could supply energy for some of these non-electrical needs, thus freeing gas and oil for uses for which they may be more valuable and suitable, especially in transportation. A group located at the Whiteshell Nuclear Research Establishment undertook a series of studies to examine this problem. These studies were done in sufficient depth to provide technological and economic answers, and as a result several reports have been published on various topics. In this report, the findings from these studies are drawn together in an assessment of the potential in Canada for using waste heat. (author)

  19. ANALYSIS OF SOLAR POWER STATION SCHEMES ON PHOTOELECTRIC MODULES FOR ELECTRIC CARS CHARGING STATIONS

    Directory of Open Access Journals (Sweden)

    A. Hnatov

    2017-12-01

    Full Text Available The analysis of existing schemes for building solar power stations on photoelectric modules with the revealing of their operation principles and functionality has been conducted. The specified technical characteristics of each of the analyzed schemes are given. The structural scheme of the solar charging station for electric cars with determining its functional capabilities and operation features is proposed. The practical application of this scheme will help to reduce the dependence on the general electric power supply network and will create conditions for its total rejection.

  20. Solar-Assisted Electric Vehicle Charging Station Interim Report

    Energy Technology Data Exchange (ETDEWEB)

    Lapsa, Melissa Voss [ORNL; Durfee, Norman [ORNL; Maxey, L Curt [ORNL; Overbey, Randall M [ORNL

    2011-09-01

    Oak Ridge National Laboratory (ORNL) has been awarded $6.8 million in the Department of Energy (DOE) American Recovery and Reinvestment Act (ARRA) funds as part of an overall $114.8 million ECOtality grant with matching funds from regional partners to install 125 solar-assisted Electric Vehicle (EV) charging stations across Knoxville, Nashville, Chattanooga, and Memphis. Significant progress has been made toward completing the scope with the installation of 25 solar-assisted charging stations at ORNL; six stations at Electric Power Research Institute (EPRI); and 27 stations at Nissan's Smyrna and Franklin sites, with three more stations under construction at Nissan's new lithium-ion battery plant. Additionally, the procurement process for contracting the installation of 34 stations at Knoxville, the University of Tennessee Knoxville (UTK), and Nashville sites is underway with completion of installation scheduled for early 2012. Progress is also being made on finalizing sites and beginning installations of 30 stations in Nashville, Chattanooga, and Memphis by EPRI and Tennessee Valley Authority (TVA). The solar-assisted EV charging station project has made great strides in fiscal year 2011. A total of 58 solar-assisted EV parking spaces have been commissioned in East and Middle Tennessee, and progress on installing the remaining 67 spaces is well underway. The contract for the 34 stations planned for Knoxville, UTK, and Nashville should be underway in October with completion scheduled for the end of March 2012; the remaining three Nissan stations are under construction and scheduled to be complete in November; and the EPRI/TVA stations for Chattanooga, Vanderbilt, and Memphis are underway and should be complete by the end of March 2012. As additional Nissan LEAFs are being delivered, usage of the charging stations has increased substantially. The project is on course to complete all 125 solar-assisted EV charging stations in time to collect meaningful data

  1. Electricity supplies in a French nuclear power station

    International Nuclear Information System (INIS)

    2011-01-01

    As the operation of a nuclear power station requires a power supply system enabling this operation as well as the installation safety, this document describes how such systems are designed in the different French nuclear power stations to meet the requirements during a normal operation (when the station produces electricity) or when it is stopped, but also to ensure power supply to equipment ensuring safety functions during an incident or an accident occurring on the installation. More precisely, these safety functions are provided by two independent systems in the French nuclear power stations. Their operation is briefly described. Two different types of nuclear reactors are addressed: pressurised water reactors (PWR) of second generation, EPR (or PWR of third generation)

  2. Electricity pricing model in thermal generating stations under deregulation

    International Nuclear Information System (INIS)

    Reji, P.; Ashok, S.; Moideenkutty, K.M.

    2007-01-01

    In regulated public utilities with competitive power markets, deregulation has replaced the monopoly. Under the deregulated power market, the electricity price primarily depends on market mechanism and power demand. In this market, generators generally follow marginal pricing. Each generator fixes the electricity price based on their pricing strategy and it leads to more price volatility. This paper proposed a model to determine the electricity price considering all operational constraints of the plant and economic variables that influenced the price, for a thermal generating station under deregulation. The purpose of the model was to assist existing stations, investors in the power sector, regulatory authorities, transmission utilities, and new power generators in decision-making. The model could accommodate price volatility in the market and was based on performance incentive/penalty considering plant load factor, availability of the plant and peak/ off peak demand. The model was applied as a case study to a typical thermal utility in India to determine the electricity price. It was concluded that the case study of a thermal generating station in a deregulated environment showed that the electricity price mainly depended on the gross calorific value (GCV) of fuel, mode of operation, price of the fuel, and operating charges. 11 refs., 2 tabs., 1 fig

  3. Safety evaluation report related to the operation of Susquehanna Steam Electric Station, Units 1 and 2. Docket Nos. 50-387 and 50-388, Pennsylvania Power and Light Company, Allegheny Electric Cooperative, Inc

    International Nuclear Information System (INIS)

    1982-07-01

    Information is presented concerning site characteristics; design criteria for systems and components; reactor thermal and hydraulic characteristics; reactor coolant pressure boundary; engineered safety features; instrumentation and control; electrical power systems; auxiliary systems; conduct of operations; quality assurance; and TMI-2 requirements

  4. Space vehicle field unit and ground station system

    Science.gov (United States)

    Judd, Stephen; Dallmann, Nicholas; Delapp, Jerry; Proicou, Michael; Seitz, Daniel; Michel, John; Enemark, Donald

    2017-09-19

    A field unit and ground station may use commercial off-the-shelf (COTS) components and share a common architecture, where differences in functionality are governed by software. The field units and ground stations may be easy to deploy, relatively inexpensive, and be relatively easy to operate. A novel file system may be used where datagrams of a file may be stored across multiple drives and/or devices. The datagrams may be received out of order and reassembled at the receiving device.

  5. United Kingdom electric system privatization

    Energy Technology Data Exchange (ETDEWEB)

    Lolli, A. (Bologna Univ. (Italy))

    1992-03-01

    This paper reviews the mechanics and first results of deregulation in the electric power industry of the United Kingdom. Several aspects are dealt with, namely: 1983 Energy Act impacts on ownership and subsequent changes brought about by the 1989 Energy Act; the Act's stipulations with regard to share acquisition and distribution; the division of the patrimony of the Area Boards; natural monopolistic characteristics of power distribution; vertical integration in Scotland, target investment limits in Government and public participation; the 'golden share' concept to guarantee public participation; current 40% share ownership by the Government; 15% private ownership limit for individual investors; external control by Government of licensing and rate structure setting; the impacts of organizational changes on the overall cost benefits of deregulation; modified Governmental regulatory powers; measures to ensure competition and consumer protection; provisions regarding misbehaviour; second tier suppliers and reserve fuel supply obligations; deregulation impacts on nuclear power marketing; power pooling regulations; installation of new transmission lines; provisions encouraging the use of diverse energy sources; franchising; interconnection with national grid; regulation of technical operations; standby as it affects rate structure; and spot market pricing.

  6. Total life cycle cost model for electric power stations

    International Nuclear Information System (INIS)

    Cardullo, M.W.

    1995-01-01

    The Total Life Cycle Cost (TLCC) model for electric power stations was developed to provide a technology screening model. The TLCC analysis involves normalizing cost estimates with respect to performance standards and financial assumptions and preparing a profile of all costs over the service life of the power station. These costs when levelized present a value in terms of a utility electricity rate. Comparison of cost and the pricing of the electricity for a utility shows if a valid project exists. Cost components include both internal and external costs. Internal costs are direct costs associated with the purchase, and operation of the power station and include initial capital costs, operating and maintenance costs. External costs result from societal and/or environmental impacts that are external to the marketplace and can include air quality impacts due to emissions, infrastructure costs, and other impacts. The cost stream is summed (current dollars) or discounted (constant dollars) to some base year to yield a overall TLCC of each power station technology on a common basis. While minimizing life cycle cost is an important consideration, it may not always be a preferred method for some utilities who may prefer minimizing capital costs. Such consideration does not always result in technology penetration in a marketplace such as the utility sector. Under various regulatory climates, the utility is likely to heavily weigh initial capital costs while giving limited consideration to other costs such as societal costs. Policy makers considering external costs, such as those resulting from environmental impacts, may reach significantly different conclusions about which technologies are most advantageous to society. The TLCC analysis model for power stations was developed to facilitate consideration of all perspectives

  7. Lewis Research Center space station electric power system test facilities

    Science.gov (United States)

    Birchenough, Arthur G.; Martin, Donald F.

    1988-01-01

    NASA Lewis Research Center facilities were developed to support testing of the Space Station Electric Power System. The capabilities and plans for these facilities are described. The three facilities which are required in the Phase C/D testing, the Power Systems Facility, the Space Power Facility, and the EPS Simulation Lab, are described in detail. The responsibilities of NASA Lewis and outside groups in conducting tests are also discussed.

  8. On the possibility of generation of cold and additional electric energy at thermal power stations

    Science.gov (United States)

    Klimenko, A. V.; Agababov, V. S.; Borisova, P. N.

    2017-06-01

    A layout of a cogeneration plant for centralized supply of the users with electricity and cold (ECCG plant) is presented. The basic components of the plant are an expander-generator unit (EGU) and a vapor-compression thermotransformer (VCTT). At the natural-gas-pressure-reducing stations, viz., gas-distribution stations and gas-control units, the plant is connected in parallel to a throttler and replaces the latter completely or partially. The plant operates using only the energy of the natural gas flow without burning the gas; therefore, it can be classified as a fuelless installation. The authors compare the thermodynamic efficiencies of a centralized cold supply system based on the proposed plant integrated into the thermal power station scheme and a decentralized cold supply system in which the cold is generated by electrically driven vapor-compression thermotransformers installed on the user's premises. To perform comparative analysis, the exergy efficiency was taken as the criterion since in one of the systems under investigation the electricity and the cold are generated, which are energies of different kinds. It is shown that the thermodynamic efficiency of the power supply using the proposed plant proves to be higher within the entire range of the parameters under consideration. The article presents the results of investigating the impact of the gas heating temperature upstream from the expander on the electric power of the plant, its total cooling capacity, and the cooling capacities of the heat exchangers installed downstream from the EGU and the evaporator of the VCTT. The results of calculations are discussed that show that the cold generated at the gas-control unit of a powerful thermal power station can be used for the centralized supply of the cold to the ventilation and conditioning systems of both the buildings of the power station and the neighboring dwelling houses, schools, and public facilities during the summer season.

  9. Electrical system design and reliability at Ontario Hydro nuclear generating stations

    Energy Technology Data Exchange (ETDEWEB)

    Royce, C. J. [Ontario Hydro, 700 University Avenue, Toronto, Ontario M5G 1X6 (Canada)

    1986-02-15

    This paper provides an overview of design practice and the predicted and actual reliability of electrical station service Systems at Ontario Nuclear Generating Stations. Operational experience and licensing changes have indicated the desirability of improving reliability in certain instances. For example, the requirement to start large emergency coolant injection pumps resulted in the turbine generator units in a multi-unit station being used as a back-up power supply. Results of reliability analyses are discussed. To mitigate the effects of common mode events Ontario Hydro adopted a 'two group' approach to the design of safety related Systems. This 'two group' approach is reviewed and a single fully environmentally qualified standby power supply is proposed for future use. (author)

  10. Final environmental assessment for vegetation control at VHF stations, microwave stations, electrical substations, and pole yards

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-10-13

    Southwestern Power Adm. operates very high frequency (VHF) and microwave radio stations, electrical substations, and pole yards for electric power transmission throughout AR, MO, and OK. Vegetation growth at the stations must be suppressed for safety of operation and personnel. Southwestern has been using a combination of mechanical/manual and herbicide control for this purpose; Federally- mandated reductions in staff and budgetary resources require Southwestern to evaluate all potentially efficient methods for vegetation control. Three alternatives were examined: no action, mechanical/manual control, and (proposed) a combination of mechanical/manual and herbicide control. Environmental impacts on air and water quality, wetlands, wildlife, endangered species, archaeological and other resources, farmland, human health, transportation, etc. were evaluated.

  11. Electric trade in the United States 1990

    International Nuclear Information System (INIS)

    1992-01-01

    Electric Trade in the United States 1990 (ELECTRA) is the third in a series of reports on wholesale power transactions prepared by the Electric Data Systems Branch, Survey Management Division, Office of Coal, Nuclear, Electric and Alternate Fuels, Energy Information Administration (EIA). The electric trade data are published biennially. The first report presented 1986 data. The second report contained data for 1988. This report provides information on the industry during 1990

  12. Multi-Unit Aspects of the Pickering Generating Station

    Energy Technology Data Exchange (ETDEWEB)

    Morison, W. G. [Atomic Energy of Canada Ltd, Sheridan Park, ON (Canada)

    1968-04-15

    The Pickering nuclear generating station is located on the north shore of Lake Ontario, about 20 miles east of the city of Toronto, Canada. The station has been planned and laid out on an eight-unit station, four units of which have now been authorized for construction. Each of these four units consists of a single heavy-water moderated and cooled CANDU-type reactor and auxiliaries coupled to a single tandem compound turbine generator with a net output of approximately 500 MW(e). The units are identical and are scheduled to come into operation at intervals of one year from 1970 to 1973. The station has been planned with central facilities for: administration maintenance laboratories, stores, change rooms, decontamination and waste management services. A common control centre, cooling water intake and discharge system, and spent fuel storage bay for four units has been arranged. A feature of the multi-unit station is a common containment system. Cost savings in building a number of identical units on the same site result from a single exclusion area, shared engineering costs, equipment purchase contracts for four identical components, and efficient use of construction plant. Operating cost savings are anticipated in the use of a common operating and maintenance staff and spare parts inventory. The plant has been arranged to minimize problems of operating, commissioning and constructing units at the same time on the same site. The layout and construction sequence have been arranged so that the first unit can be commissioned and operated with little or no interference from the construction forces working on succeeding units. During the construction phase barriers will be erected in the common control centre between operating control equipment and that being installed. Operations and construction personnel will enter the plant by separate routes and work in areas separated by physical barriers. (author)

  13. Safety evaluation report related to the operation of Grand Gulf Nuclear Station, Units 1 and 2. Dockets Nos. 50-416 and 50-417, Mississippi Power and Light Company; Middle South Energy, Inc., South Mississippi Electric Power Association

    International Nuclear Information System (INIS)

    1982-06-01

    Supplement 2 to the Safety Evaluation Report for Mississippi Power and Light Company, et. al, joint application for licenses to operate the Grand Gulf Nuclear Station, Units 1 and 2, located on the east bank of the Mississippi River near Port Gibson, in Claiborne County, Mississippi, has been prepared by the Office of Nuclear Reactor Regulation of the US Nuclear Regulatory Commission. This supplement reports the status of certain items that had not been resolved at the time of publication of the Safety Evaluation Report

  14. Surry Power Station, Units 1 and 2. Semiannual operating report, July--December 1974

    International Nuclear Information System (INIS)

    1974-01-01

    Net electric power generated by Surry Unit 1 was 6,930,353 MWH with the generator on line for 10,417.7 hours. Net electric power generated by Unit 2 was 5,699,299 MWH with the generator on line for 8,384.2 hours. Information is presented concerning operation, radioactive effluent releases, solid radioactive wastes, fuel shipments, occurrences in which temperature limitations on the condenser cooling water discharge were exceeded, changes in station organization, occupational personnel radiation exposure, nonradiological monitoring including thermal, physical, and biological programs, and the radiological environmental monitoring program. (U.S.)

  15. Electric trade in the United States 1994

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1998-08-01

    Wholesale trade in electricity plays an important role for the US electric utility industry. Wholesale, or bulk power, transactions allow electric utilities to reduce power costs, increase power supply options, and improve reliability. In 1994, the wholesale trade market totaled 1.9 trillion kilowatthours, about 66% of total sales to ultimate consumers. This publication, Electric Trade in the United States 1994 (ELECTRA), is the fifth in a series of reports on wholesale power transactions prepared by the Office of Coal, Nuclear, Electric and Alternate Fuels, Energy Information Administration (EIA). The electric trade data are published biennially. The first report presented 1986 data, and this report provides information on the electric power industry during 1994.

  16. Electric trade in the United States 1994

    International Nuclear Information System (INIS)

    1998-08-01

    Wholesale trade in electricity plays an important role for the US electric utility industry. Wholesale, or bulk power, transactions allow electric utilities to reduce power costs, increase power supply options, and improve reliability. In 1994, the wholesale trade market totaled 1.9 trillion kilowatthours, about 66% of total sales to ultimate consumers. This publication, Electric Trade in the United States 1994 (ELECTRA), is the fifth in a series of reports on wholesale power transactions prepared by the Office of Coal, Nuclear, Electric and Alternate Fuels, Energy Information Administration (EIA). The electric trade data are published biennially. The first report presented 1986 data, and this report provides information on the electric power industry during 1994

  17. Design and development of electric vehicle charging station equipped with RFID

    Science.gov (United States)

    Panatarani, C.; Murtaddo, D.; Maulana, D. W.; Irawan, S.; Joni, I. M.

    2016-02-01

    This paper reports the development of electric charging station from distributed renewable for electric vehicle (EV). This designed refer to the input voltage standard of IEC 61851, plugs features of IEC 62196 and standard communication of ISO 15118. The developed electric charging station used microcontroller ATMEGA8535 and RFID as controller and identifier of the EV users, respectively. The charging station successfully developed as desired features for electric vehicle from renewable energy resources grid with solar panel, wind power and batteries storage.

  18. Black Fox Station, Units 1 and 2. Application for construction permits and operating licenses

    International Nuclear Information System (INIS)

    1975-01-01

    An application to construct and operate Black Fox Station, Units 1 and 2, is presented. The two BWR type reactors will have a rated core thermal power of 3579 MW(t) and a net electrical power of approximately 1150 MW(e). The facility will be located in Inola Township, 23 miles east of Tulsa on the east side of the Verdigris River in Rogers County, Oklahoma

  19. Application of wire electrodes in electric discharge machining of metal samples of reactor blocks of the operative atomic power station

    International Nuclear Information System (INIS)

    Gozhenko, S.V.

    2007-01-01

    Features of application of electroerosive methods are considered during the process of direct definition of properties of metal of the equipment of power units of the atomic power station. Results of development of a complex of the equipment for wire electric discharge machining of metal templet and its use are presented at the control of the basic metal of the main circulating pipelines over blocks of the atomic power station of Ukraine over long terms of operation

  20. Electric utilities deregulation and its impact on nuclear power generating stations

    International Nuclear Information System (INIS)

    Trehan, N.K.

    1998-01-01

    Under restructuring and deregulation, it is not clear as to who would have the responsibility, and what obligations the market participants would have to ensure that the electrical system reliability (stability) is maintained. Due to the dynamic nature of the electrical grid, especially with the implementation of restructuring and deregulation, vulnerabilities exist which may impact the reliability (stability) of the offsite electrical power system. In a nuclear power generating unit, an offsite electric power system and an onsite electric power system are required to permit the functioning of structures, systems, and components which are important to safety. The safety function for each system is to provide sufficient capacity and capability to assure that the containment integrity is maintained during power operation or in the event of a postulated accident. Analyses performed by the applicants must verify that the electrical grid remains stable in the event of a loss of the nuclear unit generator, the largest other unit on the grid or the most critical transmission line. The stability of the electric grid is assumed in the safety analyses and a change in it would impact those analyses. However, it may impact the availability of a stable electric power to the safety buses because of the limited number of available transmission lines. This paper discusses electrical power generation and demand, reserve margins, power transfer capability, development of new innovative technologies to compensate for lack of the construction of transmission lines, legislation for the formulation of a self regulation organization (SRO), grid disturbances that may lead to a voltage collapse, and the vulnerabilities which may impact the availability of a stable power to the nuclear power generating stations

  1. Electric trade in the United States, 1996

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1998-12-01

    Wholesale trade in electricity plays an important role for the US electric utility industry. Wholesale, or bulk power, transactions allow electric utilities to reduce power costs, increase power supply options, and improve reliability. In 1996, the wholesale trade market totaled 2.3 trillion kilowatthours, over 73% of total sales to ultimate consumers. This publication, Electric Trade in the United States 1996 (ELECTRA), is the sixth in a series of reports on wholesale power transactions prepared by the Office of Coal, Nuclear, Electric and Alternate Fuels, Energy Information Administration (EIA). The electric trade data are published biennially. The first report presented 1986 data, and this report provides information on the electric power industry during 1996. The electric trade data collected and presented in this report furnish important information on the wholesale structure found within the US electric power industry. The patterns of interutility trade in the report support analyses of wholesale power transactions and provide input for a broader understanding of bulk power market issues that define the emerging national electric energy policies. The report includes information on the quantity of power purchased, sold, exchanged, and wheeled; the geographical locations of transactions and ownership classes involved; and the revenues and costs. 1 fig., 43 tabs.

  2. 76 FR 24538 - Duke Energy Carolinas, LLC; Catawba Nuclear Station, Units 1 and 2; McGuire Nuclear Station...

    Science.gov (United States)

    2011-05-02

    ... NUCLEAR REGULATORY COMMISSION [Docket Nos. 50-413 and 50-414; NRC-2011-0100; Docket Nos. 50-369 and 50-370; Docket Nos. 50-269, 50-270, and 50-287] Duke Energy Carolinas, LLC; Catawba Nuclear Station, Units 1 and 2; McGuire Nuclear Station, Units 1 and 2; Oconee Nuclear Station, Units 1, 2, and 3...

  3. Evaluation of River Bend Station Unit 1 Technical Specifications

    International Nuclear Information System (INIS)

    Baxter, D.E.; Bruske, S.J.

    1985-08-01

    This document was prepared for the Nuclear Regulatory Commission (NRC) to assist them in determining whether the River Bend Station Unit 1 Technical Specifications (T/S), which govern plant systems configurations and operations, are in conformance with the requirements of the Final Safety Analysis Report (FSAR) as amended, and the requirements of the Safety Evaluation Report (SER) as supplemented. A comparative audit of the FSAR as amended, and the SER as supplemented was performed with the River Bend T/S. Several discrepancies were identified and subsequently resolved through discussions with the cognizant NRC reviewer, NRC staff reviewers and/or utility representatives. The River Bend Station Unit 1 T/S, to the extent reviewed, are in conformance with the FSAR and SER

  4. Evaluation of Shoreham Nuclear Power Station, Unit 1 technical specifications

    International Nuclear Information System (INIS)

    Baxter, D.E.; Bruske, S.J.

    1985-08-01

    This document was prepared for the Nuclear Regulatory Commission (NRC) to assist them in determining whether the Shoreham Nuclear Power Station Unit 1 Technical Specifications (T/S), which govern plant systems configurations and operations, are in conformance with the assumptions of the Final Safety Analysis Report (FSAR) as amended, and the requirements of the Safety Evaluation Report (SER) as supplemented. A comparative audit of the FSAR as amended, and the SER as supplemented was performed with the Shoreham T/S. Several discrepancies were identified and subsequently resolved through discussions with the cognizant NRC reviewer, NRC staff reviewers and/or utility representatives. The Shoreham Nuclear Power Station Unit 1 T/S, to the extent reviewed, are in conformance with the FSAR and SER

  5. Solid waste processing experience at Susquehanna Steam Electric Station

    International Nuclear Information System (INIS)

    Phillips, J.W.; Granus, M.W.

    1984-01-01

    This paper reviews the first year's operation at the Susquehanna Steam Electric Station (SSES) with respect to the Westinghouse Hittman Nuclear Incorporated (Hittman) mobile solidification system and the dry activated waste generation, handling and processing. Experiences pertinent to the mobile solidification system are reviewed with emphasis on the integration of the system into the plant, problems associated with unexpected waste properties and the myriad of operating procedures that had to be prepared. The processing history for 1983 is reviewed in terms of the volume of waste, including solidified wastes, dewatered wastes an DAW. Factors that must be considered in evaluating processing alternatives, i.e., dewatering vs. solidification; steel liners vs. HICs, are discussed. Actions taken by Hittman and SSES to maximize the processing economics are also discussed. Finally, recommendations are provided to the utility considering implementing mobile solification services to ensure a smooth and timely integration of services into the plant

  6. Radioactive waste management at nuclear electric power stations

    International Nuclear Information System (INIS)

    Gordelier, S.C.

    1993-01-01

    After suitable treatment, gaseous and liquid wastes are routinely discharged from Nuclear Electric's stations and are diluted and dispersed in the environment. The discharges are controlled and authorized under UK legislation and the environmental impact is minimal. Most solid wastes were originally accumulated at the site of origin, but since 1978 low level wastes (LLW) have been send to the UK's main disposal site at Drigg. Recent changes at Drigg have resulted in changed arrangements for the transport and disposal of low-level wastes, including volume reduction by supercompaction. Small amounts of intermediate-level waste (ILW) have been conditioned and disposed of in the sea but this route is now effectively closed and there is currently no disposal route for ILW in the UK. Spent ion exchange resins at one power station have been conditioned and are stored pending the availability of a disposal route. Most ILW will continue to be stored in retrievable form on the site of origin until a mobile waste treatment plant can be brought into use. The timing of this will be subject to agreement with the regulators. In the case of Magnox fuel element debris, a demonstration dissolution plant has been constructed and this will significantly reduce the volume of waste being stored while retaining the bulk of the activity on site for later treatment. A further development has been the construction of a new facility which will hold Magnox fuel element debris in 500 liter drums

  7. A technological review on electric vehicle DC charging stations using photovoltaic sources

    Science.gov (United States)

    Youssef, Cheddadi; Fatima, Errahimi; najia, Es-sbai; Chakib, Alaoui

    2018-05-01

    Within the next few years, Electrified vehicles are destined to become the essential component of the transport field. Consequently, the charging infrastructure should be developed in the same time. Among this substructure, Charging stations photovoltaic-assisted are attracting a substantial interest due to increased environmental awareness, cost reduction and rise in efficiency of the PV modules. The intention of this paper is to review the technological status of Photovoltaic–Electric vehicle (PV-EV) charging stations during the last decade. The PV-EV charging station is divided into two categories, which are PV-grid and PV-standalone charging systems. From a practical point view, the distinction between the two architectures is the bidirectional inverter, which is added to link the station to the smart grid. The technological infrastructure includes the common hardware components of every station, namely: PV array, dc-dc converter provided with MPPT control, energy storage unit, bidirectional dc charger and inverter. We investigate, compare and evaluate many valuable researches that contain the design and control of PV-EV charging system. Additionally, this concise overview reports the studies that include charging standards, the power converters topologies that focus on the adoption of Vehicle-to grid technology and the control for both PV–grid and PV standalone DC charging systems.

  8. 76 FR 19148 - PSEG Nuclear, LLC, Hope Creek Generating Station and Salem Nuclear Generating Station, Units 1...

    Science.gov (United States)

    2011-04-06

    ... NUCLEAR REGULATORY COMMISSION [Docket Nos. 50-272, 50-311, 50-354; NRC-2009-0390 and NRC-2009-0391] PSEG Nuclear, LLC, Hope Creek Generating Station and Salem Nuclear Generating Station, Units 1 and 2..., DPR-70, and DPR-75 for an additional 20 years of operation for the Hope Creek Generating Station (HCGS...

  9. Photovoltaic power stations in Germany and the United States: A comparative study by data envelopment analysis

    International Nuclear Information System (INIS)

    Sueyoshi, Toshiyuki; Goto, Mika

    2014-01-01

    This study compares Photovoltaic (PV) power stations between Germany and the United States to examine which country more efficiently provides renewable energy in their usages. For the comparative analysis, this study utilizes Data Envelopment Analysis (DEA) as a methodology to evaluate the performance of PV power stations from the perspective of both solar and land usages. A total of one hundred sixty PV power stations (eighty in Germany and eighty in the United States) are used for this comparison. The demand for sustainable energy and energy security has been rapidly increasing over the past decade because of concerns about environment and limited resources. PV solutions are one of many renewable technologies that are being developed to satisfy a recent demand of electricity. Germany is the world's top installer and consumer of PV power and the United States is one of the top five nations. Germany leads the way in installed PV capacity even though the nation has less solar resources and land area. Due to limited solar resources, low insolation and sunshine, and land area, the United States should have a clear advantage over Germany. However, the empirical result of this study exhibits that PV power stations in Germany operate more efficiently than those of the United States even if the latter has many solar and land advantages. The surprising result indicates that the United States has room for improvement when it comes to utilizing solar and land resources and needs to reform the solar policy. For such a purpose, Feed-In Tariff (FIT) may be an effective energy policy at the state level in the United States because the FIT provides investors such as utility companies and other types of energy firms with financial incentives to develop large PV power stations and generation facilities for other renewable energy. It may be true that the FIT is a powerful policy tool to promote PV and other renewable installation and support a reduction of an amount of greenhouse

  10. Indoor unit for electric heat pump

    Science.gov (United States)

    Draper, R.; Lackey, R.S.; Fagan, T.J. Jr.; Veyo, S.E.; Humphrey, J.R.

    1984-05-22

    An indoor unit for an electric heat pump is provided in modular form including a refrigeration module, an air mover module, and a resistance heat package module, the refrigeration module including all of the indoor refrigerant circuit components including the compressor in a space adjacent the heat exchanger, the modules being adapted to be connected to air flow communication in several different ways as shown to accommodate placement of the unit in various orientations. 9 figs.

  11. Quality control for the construction of Ikata Nuclear Power Station No. 2 Unit

    International Nuclear Information System (INIS)

    Onishi, Akiyoshi

    1983-01-01

    In the construction of No. 2 unit in Ikata Nuclear Power Station, Shikoku Electric Power Co., the quality control was practiced making effective use of the experience in preceding stations including the Three Mile Island station, U.S., and improving those. The construction works were also performed in consideration of ensuring the safe running of No. 1 unit in commercial operation. In this report, first the outline of No. 2 unit facility and the quality control in the construction processes are described sequentially. For the comprehensive quality control activity over a series of plant design, manufacturing, installation and commissioning processes, the quality control policy was fixed, the system was established, the plan was prepared, and the quality control was promoted as planned and systematically. The outline of the quality control in each stage is described as follows. Design stage: It was implemented for the confirmation of applicable standards and references, the management of drawings submitted for approval, the selection of materials used, the coordination among sub-contractors, design change and the reflection of experience in preceding stations. Manufacturing stage. It was performed for material control, manufacturing management, factory test and control. Installation stage. It was practiced for the management of installation works, the inspection during the installation, and the check-up and control after the installation. Several quality control items were implemented also in the method of construction works and construction management. (Wakatsuki, Y.)

  12. Concrete works in Igata Nuclear Power Station Unit-2

    International Nuclear Information System (INIS)

    Yanase, Hidemasa

    1981-01-01

    The construction of Igata Nuclear Power Station Unit-2 was started in February, 1978, and is scheduled to start the commercial operation in March, 1982. Construction works are to be finished by August, 1981. The buildings of Igata Nuclear Power Station are composed of large cross section concrete for the purpose of shielding and the resistance to earth quakes. In response to this, moderate heat Portland cement has been employed, and in particular, the heat of hydration has been controlled. In this report, also fine and coarse aggregates, admixtures and chemical admixtures, and further, the techniques to improve the quality are described. Concrete preparation plant was installed in the power station site. Fresh concrete was carried with agitator body trucks from the preparation plant to the unloading point, and from there with pump trucks. Placing of concrete was carried out, striving to obtain homogeneous and dense concrete by using rod type vibrators. Further, concrete was placed in low slump (8 - 15 cm) to reduce water per unit volume, and its temperature was also carefully controlled, e.g., cold water (temperature of mixing water was about 10 deg C) was used in summer season (end of June to end of September). As a result, the control target was almost satisfied. As for testing and inspection, visual appearance test was done as well as material testing in compliance with JIS and other standards. (Wakatsuki, Y.)

  13. Insuring unit failures in electricity markets

    International Nuclear Information System (INIS)

    Pineda, S.; Conejo, A.J.; Carrion, M.

    2010-01-01

    An electric energy producer participates in futures markets in the hope of hedging the risk of trading in the pool. However, this producer is required to supply the energy associated with all its signed forward contracts even if some of its units are forced out due to unexpected failures. In this case, the producer must purchase some of the energy needed to meet its futures market commitments in the pool, which may result in high losses if the pool prices happen to be higher than the forward contract prices. To mitigate these losses, the producer can take out insurance against the forced outages of its units. Using a stochastic programming model, this paper analyzes the convenience of signing an insurance against unit failure by an electric energy producer and its impact on forward contracting decisions. Results from a realistic case study are provided and analyzed.

  14. 75 FR 36700 - Exelon Generation Company, LLC; Three Mile Island Nuclear Station, Unit 1; Environmental...

    Science.gov (United States)

    2010-06-28

    ...; Three Mile Island Nuclear Station, Unit 1; Environmental Assessment and Finding of No Significant Impact... Company, LLC (the licensee), for operation of Three Mile Island Nuclear Station, Unit 1 (TMI-1), located... Three Mile Island Nuclear Station, Units 1 and 2, NUREG-0552, dated December 1972, and Generic...

  15. Adaptive Modeling of the International Space Station Electrical Power System

    Science.gov (United States)

    Thomas, Justin Ray

    2007-01-01

    Software simulations provide NASA engineers the ability to experiment with spacecraft systems in a computer-imitated environment. Engineers currently develop software models that encapsulate spacecraft system behavior. These models can be inaccurate due to invalid assumptions, erroneous operation, or system evolution. Increasing accuracy requires manual calibration and domain-specific knowledge. This thesis presents a method for automatically learning system models without any assumptions regarding system behavior. Data stream mining techniques are applied to learn models for critical portions of the International Space Station (ISS) Electrical Power System (EPS). We also explore a knowledge fusion approach that uses traditional engineered EPS models to supplement the learned models. We observed that these engineered EPS models provide useful background knowledge to reduce predictive error spikes when confronted with making predictions in situations that are quite different from the training scenarios used when learning the model. Evaluations using ISS sensor data and existing EPS models demonstrate the success of the adaptive approach. Our experimental results show that adaptive modeling provides reductions in model error anywhere from 80% to 96% over these existing models. Final discussions include impending use of adaptive modeling technology for ISS mission operations and the need for adaptive modeling in future NASA lunar and Martian exploration.

  16. Snubber reduction program at the Byron Station, Unit 1

    International Nuclear Information System (INIS)

    Arterburn, J.; Bakhtiari, S.

    1987-01-01

    Commonwealth Edison Company's (CECo's) Byron Station, unit 1, was originally designed with approximately 1200 snubbers supporting the plant's large- and small-bore piping systems. This relatively large number of snubbers is attributed to excessive conservatism in nuclear piping codes and regulations effective during the original piping design. A recent pilot program at CECo's LaSalle County Station, a boiling water reactor plant, demonstrated that a 50% or greater reduction in total snubber population is achievable in plants of this design vintage. Based on the successful results of the pilot program, CECo initiated a full scale snubber reduction program at Byron, a pressurized water reactor plant of the same vintage at the LaSalle County Station. The benefits from a reduced snubber population are described. To realize the maximum potential benefits, all snubbers in the plant were prioritized in order of desirability for removal. The priority designations are discussed. The major results from phase 1 of the Byron program are summarized. The NRC inspection of the project addressed a variety of issues and is discussed. The conclusions that can be drawn from the phase 1 program are summarized

  17. Optimal Allocation of Changing Station for Electric Vehicle Based on Queuing Theory

    Directory of Open Access Journals (Sweden)

    Yagang Zhang

    2016-11-01

    Full Text Available Electric vehicle as the main development direction of the future automotive industry, has gained attention worldwide. The rationality of the planning and construction of the power station, as the foundation of energy supply, is an important premise for the development of electric vehicles. In full consideration of the electric demand and electricity consumption, this paper proposes a new construction mode in which charging station and centralized charging station are appropriately combined and presents a location optimization model. Not only can this model be applied to determine the appropriate location for the power station, but it can use the queuing theory to determine the optimal number of power equipment, with which we can achieve the minimum costs. Finally, taking a certain city as an example, the optimum plan for power station is calculated by using this model, which provides an important reference for the study of electric vehicle infrastructure planning.

  18. Experimental research of variable rotation speed ICE-based electric power station

    Directory of Open Access Journals (Sweden)

    Dar’enkov Andrey

    2017-01-01

    Full Text Available Developing variable rotation speed ICE-based stand-alone electric power stations which can supply distant regions and autonomous objects with electricity are of scientific interest due to the insufficient study. The relevance of developing such electric power stations is determined by their usage is to provide a significant fuel saving as well as increase ICE motor service life. The article describes the electric station of autonomous objects with improved fuel economy. The article describes multivariate characteristic. Multivariate characteristic shows the optimal frequency of rotation of the internal combustion engine. At this rotational speed there is the greatest fuel economy.

  19. Introduction of construction management system for preparation work of Shimane Nuclear Power Station Unit-3

    International Nuclear Information System (INIS)

    Sasaki, Yutaka; Tsumura, Isamu; Hayashi, Minoru; Nakamoto, Kenji

    2005-01-01

    The construction management system aims to have information on the construction management between the Chugoku Electric Power Co. Inc. and each contractor, and to work efficiently. The system has been operating during about half year. The system manages the manufacturing process, safety and quality. The aims, development process, characteristics, network construction of the system are reported. As outline of the construction management system, functions and construction management of each process, safety and quality and ITV camera are explained. The system will be used at construction of Shimane nuclear power station unit-3. (S.Y.)

  20. Electric machinery and drives in thermal power stations. Elektrische Maschinen und Antriebe in thermischen Kraftwerken

    Energy Technology Data Exchange (ETDEWEB)

    1974-01-01

    The following subjects were dealt with during the VDE meeting: 1) Requirements made by the electric network on the generators and their excitation equipment, and the influence thereof on their design; 2) requirements made by the power station process on the electric drives and the influence thereof on type and design; 3) requirements made on protective measures from the point of the electric power station machinery.

  1. Condensate demineralizer system for Fukushima Daiichi Nuclear Power Station, the Tokyo Electric Power Co., Inc

    International Nuclear Information System (INIS)

    Ariyoshi, Shigeki; Ikeda, Yukio; Kuramoto, Kenji; Omori, Yoshi; Yamamoto, Hiroyoshi

    1975-01-01

    This paper describes the condensate demineralizing equipment recently supplied to the second, third, and fifth power units of the Fukushima Daiichi Nuclear Power Station of the Tokyo Electric Power Company, Inc. The output of this equipment is rated as 4,900 m 3 /h each, which is currently the largest capacity for this type of equipment in Japan. The purpose of this equipment is to remove any ion components and suspended solids contained in condensate to improve its water purity. By doing so, decreasing the corrosion rate of materials used in the plant and, at the same time, decreasing the radioactivity of the condensate, thus easing the whole plant operation can be achieved. The same kind of equipment is also employed at the conventional thermal power stations, but the required functioning and operating mode are quite different. In the case of the nuclear power plant, extremely severe requirements specific with nuclear technology must be met which arise solely from dealing with radioactive substances. Not only the water treatment method, but also layout and arrangement, operation and liquid waste processing methods differ from those for the conventional power plants. The equipment for the sixth unit at Fukushima is now under designing and that for the Tokai No.2 unit of the Japan Atomic Power Company is already under shop fabrication. Both have the rated capacity of 7,300 m 3 /h each, which exceeds far up the capacity of the previously mentioned equipment. (auth.)

  2. Method and device allowing a more rational exploitation of electrical power-stations. [energy storage

    Energy Technology Data Exchange (ETDEWEB)

    Mascarello, J

    1974-04-12

    Description is given of a device permitting a more rational exploitation of electrical power stations characterized by the fact that, while electric power available during slack hours is used for pressurizing air (the pressurized air being stored in tanks), the electric power available during slack days is used for generating hydrogen from water, the hydrogen being stored in other tanks. Combustion of the stored hydrogen by the stored air is used for generating electric power during electric power consumption peak-periods.

  3. 75 FR 6223 - PSEG Nuclear LLC; Hope Creek Generating Station and Salem Nuclear Generating Station, Unit Nos. 1...

    Science.gov (United States)

    2010-02-08

    ... NUCLEAR REGULATORY COMMISSION [Docket Nos. 50-272, 50-311 and 50-354; NRC-2010-0043] PSEG Nuclear LLC; Hope Creek Generating Station and Salem Nuclear Generating Station, Unit Nos. 1 and 2...-70, and DPR-75, issued to PSEG Nuclear LLC (PSEG, the licensee), for operation of the Hope Creek...

  4. 78 FR 77726 - Exelon Generation Company, LLC Three Mile Island Nuclear Station, Unit 1

    Science.gov (United States)

    2013-12-24

    ... Three Mile Island Nuclear Station, Unit 1 AGENCY: Nuclear Regulatory Commission. ACTION: Exemption... License No. DPR-50, which authorizes operation of the Three Mile Island Nuclear Station, Unit 1 (TMI-1... Facility Operating License No. DPR-50, which authorizes operation of the Three Mile Island Nuclear Station...

  5. Mini hydro electric power stations Lukar 1,2,3,4: Public enterprise (JP) Komunalec

    International Nuclear Information System (INIS)

    Stojanova, Blagica

    2004-01-01

    The role of the Public enterprises in improving entire living conditions of the citizens, not only by its services towards the citizenship such as: water supplying and public hygiene but the opportunity to produce the electric power by the Mini hydro electric-power stations built on the main city water supply pipes. The paper presents experiences of building the mini hydro electric power stations Lukar 1,2,3,4. The successful completion of this project should be a motivation for building more electric power stations because there are great water potential in the Republic of Macedonia i.e. there have been recorded more than a hundred places suitable for construction of power electric stations. This will contribute not only for clean ecological energy but will have a direct influence on the total economic development of the Republic of Macedonia. (Author)

  6. Locating replenishment stations for electric vehicles: Application to Danish traffic data

    DEFF Research Database (Denmark)

    Wen, Min; Laporte, Gilbert; Madsen, Oli B.G.

    2012-01-01

    for electric vehicles on a traffic network with flow-based demand. The objective is to optimize the network performance, for example to maximize the flow covered by a prefixed number of stations, or to minimize the number of stations needed to cover traffic flows. Two mixed integer linear programming......Environment-friendly electric vehicles have gained substantial attention in governments, industry and universities. The deployment of a network of recharging stations is essential given their limited travel range. This paper considers the problem of locating electronic replenishment stations...

  7. Centrifugal Compressor Unit-based Heat Energy Recovery at Compressor Stations

    Directory of Open Access Journals (Sweden)

    V. S. Shadrin

    2016-01-01

    Full Text Available About 95% of the electricity consumed by air compressor stations around the world, is transformed into thermal energy, which is making its considerable contribution to global warming. The present article dwells on the re-use (recovery of energy expended for air compression.The article presents the energy analysis of the process of compressing air from the point of view of compressor drive energy conversion into heat energy. The temperature level of excess heat energy has been estimated in terms of a potential to find the ways of recovery of generated heat. It is shown that the temperature level formed by thermal energy depends on the degree of air compression and the number of stages of the compressor.Analysis of technical characteristics of modern equipment from leading manufacturers, as well as projects of the latest air compressor stations have shown that there are two directions for the recovery of heat energy arising from the air compression: Resolving technological problems of compressor units. The use of the excess heat generation to meet the technology objectives of the enterprise. This article examines the schematic diagrams of compressor units to implement the idea of heat recovery compression to solve technological problems: Heating of the air in the suction line during operation of the compressor station in winter conditions. Using compression heat to regenerate the adsorbent in the dryer of compressed air.The article gives an equity assessment of considered solutions in the total amount of heat energy of compressor station. Presented in the present work, the analysis aims to outline the main vectors of technological solutions that reduce negative impacts of heat generation of compressor stations on the environment and creating the potential for reuse of energy, i.e. its recovery.

  8. Water electrolysis plants for hydrogen and oxygen production. Shipped to Tsuruga Power Station Unit No.1, and Tokai No.2 power station, the Japan Atomic Power Co

    International Nuclear Information System (INIS)

    Ueno, Syuichi; Sato, Takao; Ishikawa, Nobuhide

    1997-01-01

    Ebara's water electrolysis plants have been shipped to Tsuruga Power Station Unit No.1, (H 2 generation rate: 11 Nm 3 /h), and Tokai No.2 Power Station (H 2 generation rate: 36 Nm 3 /h), Japan Atomic Power Co. An outcome of a business agreement between Nissho Iwai Corporation and Norsk Hydro Electrolysers (Norway), this was the first time that such water electrolysis plants were equipped in Japanese boiling water reactor power stations. Each plant included an electrolyser (for generating hydrogen and oxygen), an electric power supply, a gas compression system, a dehumidifier system, an instrumentation and control system, and an auxiliary system. The plant has been operating almost continuously, with excellent feedback, since March 1997. (author)

  9. Electric Vehicle Preparedness - Implementation Approach for Electric Vehicles at Naval Air Station Whidbey Island. Task 4

    Energy Technology Data Exchange (ETDEWEB)

    Schey, Stephen [Idaho National Lab. (INL), Idaho Falls, ID (United States); Francfort, Jim [Idaho National Lab. (INL), Idaho Falls, ID (United States)

    2015-06-01

    Several U.S. Department of Defense base studies have been conducted to identify potential U.S. Department of Defense transportation systems that are strong candidates for introduction or expansion of plug-in electric vehicles (PEVs). This study is focused on the Naval Air Station Whidbey Island (NASWI) located in Washington State. Task 1 consisted of a survey of the non-tactical fleet of vehicles at NASWI to begin the review of vehicle mission assignments and types of vehicles in service. In Task 2, daily operational characteristics of vehicles were identified to select vehicles for further monitoring and attachment of data loggers. Task 3 recorded vehicle movements in order to characterize the vehicles’ missions. The results of the data analysis and observations were provided. Individual observations of the selected vehicles provided the basis for recommendations related to PEV adoption, i.e., whether a battery electric vehicle (BEV) or plug-in hybrid electric vehicle (PHEV) (collectively PEVs) can fulfill the mission requirements. It also provided the basis for recommendations related to placement of PEV charging infrastructure. This report focuses on an implementation plan for the near-term adoption of PEVs into the NASWI fleet.

  10. Wind-powered electrical systems : highway rest areas, weigh stations, and team section buildings.

    Science.gov (United States)

    2009-02-01

    This project considered the use of wind for providing electrical power at Illinois Department of Transportation : (IDOT) highway rest areas, weigh stations, and team section buildings. The goal of the project was to determine : the extent to which wi...

  11. Emissions from coal-fired electric stations : environmental health effects and reduction options

    International Nuclear Information System (INIS)

    Love, P.; Lourie, B.; Pengelly, D.; Labatt, S.; Ogilvie, K.; Kelly, B.

    1998-01-01

    Findings of a study on the environmental effects of current emissions from coal-fired electric stations were summarized. Current and projected emissions from coal-fired electric stations for five emission reduction scenarios were estimated for Ontario, Eastern Canada, Ohio Valley/Great Lakes, and the U.S. northeast regions. Coal-fired electric stations generate a wide range of environmentally significant air emissions. The five pollutants selected - sulphur dioxide, nitrogen oxides, particulate matter (less than 10 micrometres in size), mercury, and carbon dioxide - are considered to impact most on environmental health. This report focused on 312 coal-fired electric stations in the regions named above. They were selected based on the likelihood that long-range transport of the emissions from these coal-fired utilities would have an impact on human health and the environment. 55 refs., 10 tabs., 8 figs

  12. Ergonomic implementation and work station design for quilt manufacturing unit.

    Science.gov (United States)

    Vinay, Deepa; Kwatra, Seema; Sharma, Suneeta; Kaur, Nirmal

    2012-05-01

    Awkward, extreme and repetitive postures have been associated with work related musculoskeletal disorders and injury to the lowerback of workers engaged in quilting manufacturing unit. Basically quilt are made manually by hand stitch and embroidery on the quilts which was done in squatting posture on the floor. Mending, stain removal, washing and packaging were some other associated work performed on wooden table. their work demands to maintain a continuous squatting posture which leads to various injuries related to low back and to calf muscles. The present study was undertaken in Tarai Agroclimatic Zone of Udham Singh Nagar District of Uttarakhand State with the objective to study the physical and physiological parameters as well as the work station layout of the respondent engaged on quilt manufacturing unit. A total of 30 subjects were selected to study the drudgery involved in quilt making enterprise and to make the provision of technology option to reduce the drudgery as well as musculoskeletal disorders, thus enhancing the productivity and comfortability. Findings of the investigation show that majority of workers (93.33 per cent) were female and very few (6.66 per cent) were the male with the mean age of 24.53±6.43. The body mass index and aerobic capacity (lit/min) values were found as 21.40±4.13 and 26.02±6.44 respectively. Forty per cent of the respondents were having the physical fitness index of high average whereas 33.33 per cent of the respondents had low average physical fitness. All the assessed activities involved to make the quilt included a number of the steps which were executed using two types of work station i.e squatting posture on floor and standing posture using wooden table. A comparative study of physiological parameters was also done in the existing conditions as well as in improved conditions by introducing low height chair and wooden spreader to hold the load of quilt while working, to improve the work posture of the worker. The

  13. Safety Evaluation Report related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445 and 50-446). Supplement No. 9

    International Nuclear Information System (INIS)

    1985-03-01

    This supplement addresses TUEC's analyses in support of its request to amend the Comanche Peak Final Safety Analysis Report to eliminate the commitment that coatings inside the reactor Containment Building be qualified for Units 1 and 2. In addition, this supplement provides the results of the staff's evaluation and resolution of 62 technical concerns and allegations in the coatings area for Unit 1. Because of the favorable resolution of the items discussed in this report, the staff concludes for the issues considered herein, that there is reasonable assurance that the facility can be operated by TUEC without endangering the health and safety of the public

  14. Case Study of Multi-Unit Risk: Multi-Unit Station Black-Out

    Energy Technology Data Exchange (ETDEWEB)

    Oh, Kyemin; Jang, Seung-cheol [KAERI, Daejeon (Korea, Republic of); Heo, Gyunyoung [Kyung Hee University, Yongin (Korea, Republic of)

    2015-05-15

    After Fukushima Daiichi Accident, importance and public concern for Multi-Unit Risk (MUR) or Probabilistic Safety Assessment (PSA) have been increased. Most of nuclear power plant sites in the world have more than two units. These sites have been facing the problems of MUR or accident such as Fukushima. In case of South Korea, there are generally more than four units on the same site and even more than ten units are also expected. In other words, sites in South Korea also have been facing same problems. Considering number of units on the same site, potential of these problems may be larger than other countries. The purpose of this paper is to perform case study based on another paper submitted in the conference. MUR is depended on various site features such as design, shared systems/structures, layout, environmental condition, and so on. Considering various dependencies, we assessed Multi-Unit Station Black-out (MSBO) accident based on Hanul Unit 3 and 4 model. In this paper, case study for multi-unit risk or PSA had been performed. Our result was incomplete to assess total multi-unit risk because of two challenging issues. First, economic impact had not been evaluated to estimate multi-unit risk. Second, large uncertainties were included in our result because of various assumptions. These issues must be resolved in the future.

  15. Case Study of Multi-Unit Risk: Multi-Unit Station Black-Out

    International Nuclear Information System (INIS)

    Oh, Kyemin; Jang, Seung-cheol; Heo, Gyunyoung

    2015-01-01

    After Fukushima Daiichi Accident, importance and public concern for Multi-Unit Risk (MUR) or Probabilistic Safety Assessment (PSA) have been increased. Most of nuclear power plant sites in the world have more than two units. These sites have been facing the problems of MUR or accident such as Fukushima. In case of South Korea, there are generally more than four units on the same site and even more than ten units are also expected. In other words, sites in South Korea also have been facing same problems. Considering number of units on the same site, potential of these problems may be larger than other countries. The purpose of this paper is to perform case study based on another paper submitted in the conference. MUR is depended on various site features such as design, shared systems/structures, layout, environmental condition, and so on. Considering various dependencies, we assessed Multi-Unit Station Black-out (MSBO) accident based on Hanul Unit 3 and 4 model. In this paper, case study for multi-unit risk or PSA had been performed. Our result was incomplete to assess total multi-unit risk because of two challenging issues. First, economic impact had not been evaluated to estimate multi-unit risk. Second, large uncertainties were included in our result because of various assumptions. These issues must be resolved in the future

  16. Simplified conversions between specific conductance and salinity units for use with data from monitoring stations

    Science.gov (United States)

    Schemel, Laurence E.

    2001-01-01

    The U.S. Geological Survey, Bureau of Reclamation, and the California Department of Water Resources maintain a large number of monitoring stations that record specific conductance, often referred to as “electrical conductivity,” in San Francisco Bay Estuary and the Sacramento-San Joaquin Delta. Specific conductance units that have been normalized to a standard temperature are useful in fresh waters, but conversion to salinity units has some considerable advantages in brackish waters of the estuary and Delta. For example, salinity is linearly related to the mixing ratio of freshwater and seawater, which is not the case for specific conductance, even when values are normalized to a standard temperature. The Practical Salinity Scale 1978 is based on specific conductance, temperature, and pressure measurements of seawater and freshwater mixtures (Lewis 1980 and references therein). Equations and data that define the scale make possible conversions between specific conductance and salinity values.

  17. Assessment of Extremely Low Frequency (ELF Electric and Magnetic Fields in Hamedan High Electrical Power Stations and their Effects on Workers

    Directory of Open Access Journals (Sweden)

    Farshid Ghorbani Shahna

    2011-09-01

    Full Text Available Introduction: Public and occupational exposure to extremely low frequency (ELF electric and magnetic fields induced by electrical equipment is a significant issue in the environment and at the workplace due to their potential health effects on public health. The purpose of this study was assessment of the electric and magnetic fields intensities and determination of mental and psychological effects of occupational exposure in the high voltage electric power stations in the city of Hamadan, Iran. Material and Methods: The intensities of the magnetic and electric fields were measured at eight high voltage electric power stations at three different intervals of sources using an HI-3604 instrument. A two-part questionnaire was used to assess mental and psychological effects of the exposure to these fields. Two groups of control and case workers including 30 samples were selected to determine the exposure effects. Results: The results of field measurements showed the highest average electric field intensity was related to the CVT unit with 3110 V/m at a 2 m distance from the source and the lowest average was related to the control room with 1.35 V/m next to the source. Also, the highest and lowest magnetic field intensities were close to the transformator 2 and the battery room (50.42 and 1.31 mG, respectively. Discussion and Conclusion: The intensities of electric and magnetic fields in the selected stations are lower than the ACGIH and ICNIRP standard levels for occupational exposures. The results obtained indicate that the distribution of these fields was nonlinear around the sources and the effects observed on exposed workers were non-thermal.

  18. North Anna Power Station - Unit 1: Overview of steam generator replacement project activities

    International Nuclear Information System (INIS)

    Gettler, M.W.; Bayer, R.K.; Lippard, D.W.

    1993-01-01

    The original steam generators at Virginia Electric and Power Company's (Virginia Power) North Anna Power Station (NAPS) Unit 1 have experienced corrosion-related degradation that require periodic inspection and plugging of steam generator tubes to ensure their continued safe and reliable operation. Despite improvements in secondary water chemistry, continued tube degradation in the steam generators necessitated the removal from service of approximately 20.3 percent of the tubes by plugging, (18.6, 17.3, and 25.1 for steam generators A, B, and C, respectively). Additionally, the unit power was limited to 95 % during, its last cycle of operation. Projections of industry and Virginia Power experience indicated the possibility of mid-cycle inspections and reductions in unit power. Therefore, economic considerations led to the decision to repair the steam generators (i.e., replace the steam generator lower assemblies). Three new Model 51F Steam Generator lower assembly units were ordered from Westinghouse. Virginia Power contracted Bechtel Power Corporation to provide the engineering and construction support to repair the Unit 1 steam generators. On January 4, 1993, after an extended coastdown period, North Anna Unit 1 was brought off-line and the 110 day (breaker-to-breaker) Steam Generator Replacement Project (SGRP) outage began. As of this paper, the outage is still in progress

  19. Experience and development of on-line BWR surveillance system at Onagawa nuclear power station unit-1

    International Nuclear Information System (INIS)

    Kishi, A.; Chiba, K.; Kato, K.; Ebata, S.; Ando, Y.; Sakamoto, H.

    1986-01-01

    ONAGAWA nuclear power station Unit-1 (Tohoku Electric Power Co.) is a BWR-4 nuclear power station of 524 MW electric power which started commercial operation in June 1984. To attain high reliability and applicability for ONAGAWA-1, Tohoku Electric Power Co. and Toshiba started a Research and Development project on plant surveillance and diagnosis from April 1982. Main purposes of this project are to: (1) Develop an on-line surveillance system and acquire its operating experience at a commercial BWR, (2) Assist in plant operation and maintenance by data acquisition and analysis, (3) Develop a new technique for plant surveillance and diagnosis. An outline of the project, operating experience gained from the on-line surveillance system and an introduction to new diagnosis techniques are reported in this paper. (author)

  20. Report from investigation committee on the accident at the Fukushima Nuclear Power Stations of Tokyo Electric Power Company

    International Nuclear Information System (INIS)

    Koshizuka, Seiichi

    2012-01-01

    Government's Investigation Committee on the Accident at Fukushima Nuclear Power Stations of Tokyo Electric Power Company published its final report on July 23, 2012. Results of investigation combined final report and interim report published on December 26, 2011. The author was head of accident accuse investigation team mostly in charge of site response, prior measure and plant behavior. This article reported author related technical investigation results focusing on site response and prior measures against tsunamis of units 1-3 of Fukushima Nuclear Power Stations. Misunderstanding of working state of isolation condenser of unit 1, unsuitability of alternative water injection at manual stop of high-pressure coolant injection (HPCI) system of unit 3 and improper prior measure against tsunami and severe accident were pointed out in interim report. Improper monitoring of suppression chamber of unit 2 and again unsuitable work for HPCI system of unit 3 were reported in final report. Thorough technical investigation was more encouraged to update safety measures of nuclear power stations. (T. Tanaka)

  1. Draft environmental impact statement. River Bend Nuclear Power Station, Unit 1

    International Nuclear Information System (INIS)

    Anon.

    1980-01-01

    Federal financing of an undivided ownership interest of River Bend Nuclear Power Station Unit 1 on a 3293-acre site near St. Francisville, Louisiana is proposed in a supplement to the final environmental impact statement of September 1974. The facility would consist of a boiling-water reactor that would produce a maximum of 2894 megawatts (MW) of electrical power. A design level of 3015 MW of electric power could be realized at some time in the future. Exhaust steam would be cooled by mechanical cooling towers using makeup water obtained from and discharged to the Mississippi River. Power generated by the unit would be transmitted via three lines totaling 140 circuit miles traversing portions of the parishes of West Feliciana, East Feliciana, East Baton Rouge, West Baton Rouge, Pointe Coupee, and Iberville. The unit would help the applicant meet the power needs of rural electric consumers in the region, and the applicant would contribute significanlty to area tax base and employment rolls during the life of the unit. Construction related activities would disturb 700 forested acres on the site and 1156 acres along the transmission routes. Of the 60 cubic feet per second (cfs) taken from the river, 48 cfs would evaporate during the cooling process and 12 cfs would return to the river with dissolved solids concentrations increased by 500%. The terrace aquifer would be dewatered for 16 months in order to lower the water table at the building site, and Grants Bayou would be transformed from a lentic to a lotic habitat during this period. Fogging and icing due to evaporation and drift from the cooling towers would increase slightly. During the construction period, farming, hunting, and fishing on the site would be suspended, and the social infractructure would be stressed due to the influx of a maximum of 2200 workers

  2. Recruiting, Training, Retaining, and Promoting the Workforce of the Future at Comanche Peak Steam Electric Station

    International Nuclear Information System (INIS)

    Sunseri, M.

    1999-01-01

    TXU Electric expects to encounter a relatively high turnover in the workforce in the coming years. To prepare for this challenge and to maintain a high level of performance, a number of approaches are being implemented. These approaches involve recruiting experienced personnel, recruiting and developing local nonexperienced personnel, and developing current employees. Through these approaches, TXU Electric expects to maintain a high-quality workforce for the continued support of Comanche Peak Steam Electric Station

  3. A method and device allowing a more rational exploitation of electrical power-stations

    International Nuclear Information System (INIS)

    Mascarello, Jean.

    1974-01-01

    Description is given of a device permitting a more rational exploitation of electrical power-stations characterized by the fact that, while electric power available during slack hours is used for pressurizing air (the thus pressurized air being stored in tanks), the electric power available during slack days is used for generating hydrogen from water, said hydrogen being stored in other tanks, combustion of the stored hydrogen by the stored air being used for generating electric power during electric power consumption peak-periods [fr

  4. An Introduction to Retail Electricity Choice in the United States

    Energy Technology Data Exchange (ETDEWEB)

    Zhou, Shengru [National Renewable Energy Laboratory (NREL), Golden, CO (United States)

    2017-10-04

    Retail electricity choice in the United States allows end-use customers (including industrial, commercial, and residential customers) to buy electricity from competitive retail suppliers. This brochure offers an overview of retail electricity choice in the United States, and its impact on prices and renewable energy procurement. It concludes with three lessons learned from the U.S. retail market experience that may serve as a reference for other countries and regions taking steps towards retail electricity market liberalization.

  5. 77 FR 50533 - Dominion Nuclear Connecticut, Inc.; Millstone Power Station, Unit 3

    Science.gov (United States)

    2012-08-21

    ....; Millstone Power Station, Unit 3 AGENCY: Nuclear Regulatory Commission. ACTION: Environmental assessment and... search, select ``ADAMS Public Documents'' and then select ``Begin Web- based ADAMS Search.'' For problems... Optimized ZIRLO\\TM\\ fuel rod cladding in future core reload applications for Millstone Power Station, Unit 3...

  6. Optimal Charging Schedule Planning and Economic Analysis for Electric Bus Charging Stations

    Directory of Open Access Journals (Sweden)

    Rong-Ceng Leou

    2017-04-01

    Full Text Available The battery capacity of electric buses (EB used for public transportation is greater than that of electric cars, and the charging power is also several times greater than that used in electric cars; this can result in high energy consumption and negatively impact power distribution networks. This paper proposes a framework to determine the optimal contracted power capacity and charging schedule of an EB charging station in such a way that energy costs can be reduced. A mathematical model of controlled charging, which includes the capacity and energy charges of the station, was developed to minimize costs. The constraints of the model include the charging characteristics of an EB and the operational guidelines of the bus company. A practical EB charging station was used to verify the proposed model. The financial viability of this EB charging station is also studied in this paper. The economic analysis model for this charging station considers investment and operational costs, and the operational revenue. Sensitivity analyses with respect to some key parameters are also performed in this paper. Based on actual operational routes and EB charging schemes, test results indicate that the EB charging station investment is feasible, and the planning model proposed can be used to determine optimal station power capacity and minimize energy costs.

  7. 75 FR 43915 - Basin Electric Power Cooperative: Deer Creek Station

    Science.gov (United States)

    2010-07-27

    ... factors that could be affected by the proposed Project were evaluated in detail in the EIS. These issues... DEPARTMENT OF AGRICULTURE Rural Utilities Service Basin Electric Power Cooperative: Deer Creek... Energy Facility project (Project) in Brookings and Deuel Counties, South Dakota. The Administrator of RUS...

  8. An Analytical Planning Model to Estimate the Optimal Density of Charging Stations for Electric Vehicles.

    Directory of Open Access Journals (Sweden)

    Yongjun Ahn

    Full Text Available The charging infrastructure location problem is becoming more significant due to the extensive adoption of electric vehicles. Efficient charging station planning can solve deeply rooted problems, such as driving-range anxiety and the stagnation of new electric vehicle consumers. In the initial stage of introducing electric vehicles, the allocation of charging stations is difficult to determine due to the uncertainty of candidate sites and unidentified charging demands, which are determined by diverse variables. This paper introduces the Estimating the Required Density of EV Charging (ERDEC stations model, which is an analytical approach to estimating the optimal density of charging stations for certain urban areas, which are subsequently aggregated to city level planning. The optimal charging station's density is derived to minimize the total cost. A numerical study is conducted to obtain the correlations among the various parameters in the proposed model, such as regional parameters, technological parameters and coefficient factors. To investigate the effect of technological advances, the corresponding changes in the optimal density and total cost are also examined by various combinations of technological parameters. Daejeon city in South Korea is selected for the case study to examine the applicability of the model to real-world problems. With real taxi trajectory data, the optimal density map of charging stations is generated. These results can provide the optimal number of chargers for driving without driving-range anxiety. In the initial planning phase of installing charging infrastructure, the proposed model can be applied to a relatively extensive area to encourage the usage of electric vehicles, especially areas that lack information, such as exact candidate sites for charging stations and other data related with electric vehicles. The methods and results of this paper can serve as a planning guideline to facilitate the extensive

  9. An Analytical Planning Model to Estimate the Optimal Density of Charging Stations for Electric Vehicles.

    Science.gov (United States)

    Ahn, Yongjun; Yeo, Hwasoo

    2015-01-01

    The charging infrastructure location problem is becoming more significant due to the extensive adoption of electric vehicles. Efficient charging station planning can solve deeply rooted problems, such as driving-range anxiety and the stagnation of new electric vehicle consumers. In the initial stage of introducing electric vehicles, the allocation of charging stations is difficult to determine due to the uncertainty of candidate sites and unidentified charging demands, which are determined by diverse variables. This paper introduces the Estimating the Required Density of EV Charging (ERDEC) stations model, which is an analytical approach to estimating the optimal density of charging stations for certain urban areas, which are subsequently aggregated to city level planning. The optimal charging station's density is derived to minimize the total cost. A numerical study is conducted to obtain the correlations among the various parameters in the proposed model, such as regional parameters, technological parameters and coefficient factors. To investigate the effect of technological advances, the corresponding changes in the optimal density and total cost are also examined by various combinations of technological parameters. Daejeon city in South Korea is selected for the case study to examine the applicability of the model to real-world problems. With real taxi trajectory data, the optimal density map of charging stations is generated. These results can provide the optimal number of chargers for driving without driving-range anxiety. In the initial planning phase of installing charging infrastructure, the proposed model can be applied to a relatively extensive area to encourage the usage of electric vehicles, especially areas that lack information, such as exact candidate sites for charging stations and other data related with electric vehicles. The methods and results of this paper can serve as a planning guideline to facilitate the extensive adoption of electric

  10. Intake-to-delivered-energy ratios for central station and distributed electricity generation in California

    International Nuclear Information System (INIS)

    Heath, Garvin A.; Nazaroff, William W.

    2007-01-01

    In previous work, we showed that the intake fraction (iF) for nonreactive primary air pollutants was 20 times higher in central tendency for small-scale, urban-sited distributed electricity generation (DG) sources than for large-scale, central station (CS) power plants in California [Heath, G.A., Granvold, P.W., Hoats, A.S., Nazaroff, W.W., 2006. Intake fraction assessment of the air pollutant exposure implications of a shift toward distributed electricity generation. Atmospheric Environment 40, 7164-7177]. The present paper builds on that study, exploring pollutant- and technology-specific aspects of population inhalation exposure from electricity generation. We compare California's existing CS-based system to one that is more reliant on DG units sited in urban areas. We use Gaussian plume modeling and a GIS-based exposure analysis to assess 25 existing CSs and 11 DG sources hypothetically located in the downtowns of California's most populous cities. We consider population intake of three pollutants - PM 2.5 , NO x and formaldehyde - directly emitted by five DG technologies - natural gas (NG)-fired turbines, NG internal combustion engines (ICE), NG microturbines, diesel ICEs, and fuel cells with on-site NG reformers. We also consider intake of these pollutants from existing CS facilities, most of which use large NG turbines, as well as from hypothetical facilities located at these same sites but meeting California's best-available control technology standards. After systematically exploring the sensitivity of iF to pollutant decay rate, the iFs for each of the three pollutants for all DG and CS cases are estimated. To efficiently compare the pollutant- and technology-specific exposure potential on an appropriate common basis, a new metric is introduced and evaluated: the intake-to-delivered-energy ratio (IDER). The IDER expresses the mass of pollutant inhaled by an exposed population owing to emissions from an electricity generation unit per quantity of electric

  11. Intake-to-delivered-energy ratios for central station and distributed electricity generation in California

    Science.gov (United States)

    Heath, Garvin A.; Nazaroff, William W.

    In previous work, we showed that the intake fraction (iF) for nonreactive primary air pollutants was 20 times higher in central tendency for small-scale, urban-sited distributed electricity generation (DG) sources than for large-scale, central station (CS) power plants in California [Heath, G.A., Granvold, P.W., Hoats, A.S., Nazaroff, W.W., 2006. Intake fraction assessment of the air pollutant exposure implications of a shift toward distributed electricity generation. Atmospheric Environment 40, 7164-7177]. The present paper builds on that study, exploring pollutant- and technology-specific aspects of population inhalation exposure from electricity generation. We compare California's existing CS-based system to one that is more reliant on DG units sited in urban areas. We use Gaussian plume modeling and a GIS-based exposure analysis to assess 25 existing CSs and 11 DG sources hypothetically located in the downtowns of California's most populous cities. We consider population intake of three pollutants—PM 2.5, NO x and formaldehyde—directly emitted by five DG technologies—natural gas (NG)-fired turbines, NG internal combustion engines (ICE), NG microturbines, diesel ICEs, and fuel cells with on-site NG reformers. We also consider intake of these pollutants from existing CS facilities, most of which use large NG turbines, as well as from hypothetical facilities located at these same sites but meeting California's best-available control technology standards. After systematically exploring the sensitivity of iF to pollutant decay rate, the iFs for each of the three pollutants for all DG and CS cases are estimated. To efficiently compare the pollutant- and technology-specific exposure potential on an appropriate common basis, a new metric is introduced and evaluated: the intake-to-delivered-energy ratio (IDER). The IDER expresses the mass of pollutant inhaled by an exposed population owing to emissions from an electricity generation unit per quantity of electric

  12. Enhanced Hourly Wind Station Data for the Contiguous United States

    Data.gov (United States)

    National Oceanic and Atmospheric Administration, Department of Commerce — U.S. Enhanced Hourly Wind Station Data is digital data set DSI-6421, archived at the National Centers for Environmental Information (NCEI; formerly National Climatic...

  13. A modular Space Station/Base electrical power system - Requirements and design study.

    Science.gov (United States)

    Eliason, J. T.; Adkisson, W. B.

    1972-01-01

    The requirements and procedures necessary for definition and specification of an electrical power system (EPS) for the future space station are discussed herein. The considered space station EPS consists of a replaceable main power module with self-contained auxiliary power, guidance, control, and communication subsystems. This independent power source may 'plug into' a space station module which has its own electrical distribution, control, power conditioning, and auxiliary power subsystems. Integration problems are discussed, and a transmission system selected with local floor-by-floor power conditioning and distribution in the station module. This technique eliminates the need for an immediate long range decision on the ultimate space base power sources by providing capability for almost any currently considered option.

  14. Technical descriptions of Hudson River electricity generating stations

    International Nuclear Information System (INIS)

    Hutchison, J.B.

    1988-01-01

    Six fossil-fueled and one nuclear electricity generating plants are sited along the Hudson River estuary between kilometers 8 and 228, measured from the river mouth. Their aggregate rated capacity is 5,798 MW of electricity; operating at that capacity they would withdraw cooling water from the river at the rate of 1.5 x 10 to the 9th power cu m/d and reject heat at the rate of 155 x 10 to the 9th power kcal/d. Three of these plants, the fossil-fueled Roseton and Bowline and the nuclear Indian Point facilities; account for 75% of total rated capacity, 62% of maximum water withdrawal, and 79% of potential heat rejection. These three plants and a proposed pumped-storage facility at Cornwall, all sited between km 60 and 106, were the focus of environmental litigation. The Indian Point plant normally operates at 100% generation capacity; the other plants may experience daily operating load changes that vary from approximately 50% to 100% of total generation capacity, depending on system electrical demand or economic considerations. All plants experience periodic unscheduled outages for repairs. 6 refs., 7 figs

  15. Business Models for Solar Powered Charging Stations to Develop Infrastructure for Electric Vehicles

    Directory of Open Access Journals (Sweden)

    Jessica Robinson

    2014-10-01

    Full Text Available Electric power must become less dependent on fossil fuels and transportation must become more electric to decrease carbon emissions and mitigate climate change. Increasing availability and accessibility of charging stations is predicted to increase purchases of electric vehicles. In order to address the current inadequate charging infrastructure for electric vehicles, major entities must adopt business models for solar powered charging stations (SPCS. These SPCS should be located in parking lots to produce electricity for the grid and provide an integrated infrastructure for charging electric vehicles. Due to the lack of information related to SPCS business models, this manuscript designs several models for major entities including industry, the federal and state government, utilities, universities, and public parking. A literature review of the available relevant business models and case studies of constructed charging stations was completed to support the proposals. In addition, a survey of a university’s students, staff, and faculty was conducted to provide consumer research on people’s opinion of SPCS construction and preference of business model aspects. Results showed that 69% of respondents would be more willing to invest in an electric vehicle if there was sufficient charging station infrastructure at the university. Among many recommendations, the business models suggest installing level 1 charging for the majority of entities, and to match entities’ current pricing structures for station use. The manuscript discusses the impacts of fossil fuel use, and the benefits of electric car and SPCS use, accommodates for the present gap in available literature on SPCS business models, and provides current consumer data for SPCS and the models proposed.

  16. In situ testing of the Shippingport Atomic Power Station electrical circuits

    International Nuclear Information System (INIS)

    Dinsel, M.R.; Donaldson, M.R.; Soberano, F.T.

    1987-04-01

    This report discusses the results of electrical in situ testing of selected circuits and components at the Shippingport Atomic Power Station in Shippingport, Pennsylvania. Testing was performed by EG and G Idaho in support of the United States Nuclear Regulatory Commission (USNRC) Nuclear Plant Aging Research (NPAR) Program. The goal was to determine the extent of aging or degradation of various circuits from the original plant, and the two major coreplant upgrades (representing three distinct age groups), as well as to evaluate previously developed surveillance technology. The electrical testing was performed using the Electrical Circuit Characterization and Diagnostic (ECCAD) system developed by EG and G for the US Department of Energy to use at TMI-2. Testing included measurements of voltage, effective series capacitance, effective series inductance, impedance, effective series resistance, dc resistance, insulation resistance and time domain reflectometry (TDR) parameters. The circuits evaluated included pressurizer heaters, control rod position indicator cables, miscellaneous primary system Resistance Temperature Detectors (RTDs), nuclear instrumentation cables, and safety injection system motor operated valves. It is to be noted that the operability of these circuits was tested after several years had elapsed because plant operations had concluded at Shippingport. There was no need following plant shutdown to retain the circuits in working condition, so no effort was expended for that purpose. The in situ measurements and analysis of the data confirmed the effectiveness of the ECCAD system for detecting degradation of circuit connections and splices because of high resistance paths, with most of the problems caused by corrosion. Results indicate a correlation between the chronological age of circuits and circuit degradation

  17. Electric trade in the United States 1992

    Energy Technology Data Exchange (ETDEWEB)

    1994-09-01

    This publication, Electric Trade in the US 1992 (ELECTRA), is the fourth in a series of reports on wholesale power transactions prepared by the Electric Data Systems Branch, Survey Management Division, Office of Coal, Nuclear, Electric and Alternate Fuels, Energy Information Administration (EIA). The electric trade data are published biennially. The first report presented 1986 data, and this report provides information on the electric power industry during 1992. The electric trade data collected and presented in this report furnish important information on the wholesale structure found within the US electric power industry. The patterns of interutility trade in the report support analyses of wholesale power transactions and provide input for a broader understanding of bulk power market issues that define the emerging national electric energy policies. The report includes information on the quantity of power purchased, sold, exchanged, and wheeled; the geographical locations of transactions and ownership classes involved; and the revenues and costs. Information on the physical transmission system are being included for the first time in this publication. Transmission data covering investor-owned electric utilities were shifted from the Financial Statistics of Selected Investor-Owned Electric Utilities to the ELECTRA publication. Some of the prominent features of this year`s report include information and data not published before on transmission lines for publicly owned utilities and transmission lines added during 1992 by investor-owned electric utilities.

  18. Electric trade in the United States 1992

    International Nuclear Information System (INIS)

    1994-09-01

    This publication, Electric Trade in the US 1992 (ELECTRA), is the fourth in a series of reports on wholesale power transactions prepared by the Electric Data Systems Branch, Survey Management Division, Office of Coal, Nuclear, Electric and Alternate Fuels, Energy Information Administration (EIA). The electric trade data are published biennially. The first report presented 1986 data, and this report provides information on the electric power industry during 1992. The electric trade data collected and presented in this report furnish important information on the wholesale structure found within the US electric power industry. The patterns of interutility trade in the report support analyses of wholesale power transactions and provide input for a broader understanding of bulk power market issues that define the emerging national electric energy policies. The report includes information on the quantity of power purchased, sold, exchanged, and wheeled; the geographical locations of transactions and ownership classes involved; and the revenues and costs. Information on the physical transmission system are being included for the first time in this publication. Transmission data covering investor-owned electric utilities were shifted from the Financial Statistics of Selected Investor-Owned Electric Utilities to the ELECTRA publication. Some of the prominent features of this year's report include information and data not published before on transmission lines for publicly owned utilities and transmission lines added during 1992 by investor-owned electric utilities

  19. US central station nuclear electric generating units: significant milestones

    International Nuclear Information System (INIS)

    1979-09-01

    Listings of US nuclear power plants include significant dates, reactor type, owners, and net generating capacity. Listings are made by state, region, and utility. Tabulations of status, schedules, and orders are also presented

  20. Multiple Charging Station Location-Routing Problem with Time Window of Electric Vehicle

    Directory of Open Access Journals (Sweden)

    Wang Li-ying

    2015-11-01

    Full Text Available This paper presents the electric vehicle (EV multiple charging station location-routing problem with time window to optimize the routing plan of capacitated EVs and the strategy of charging stations. In particular, the strategy of charging stations includes both infrastructure-type selection and station location decisions. The problem accounts for two critical constraints in logistic practice: the vehicle loading capacity and the customer time windows. A hybrid heuristic that incorporates an adaptive variable neighborhood search (AVNS with the tabu search algorithm for intensification was developed to address the problem. The specialized neighborhood structures and the selection methods of charging station used in the shaking step of AVNS were proposed. In contrast to the commercial solver CPLEX, experimental results on small-scale test instances demonstrate that the algorithm can find nearly optimal solutions on small-scale instances. The results on large-scale instances also show the effectiveness of the algorithm.

  1. Probabilistic modeling of nodal electric vehicle load due to fast charging stations

    DEFF Research Database (Denmark)

    Tang, Difei; Wang, Peng; Wu, Qiuwei

    2016-01-01

    In order to reduce greenhouse gas emission and fossil fuel dependence, Electric Vehicle (EV) has drawn increasing attention due to its zero emission and high efficiency. However, new problems such as range anxiety, long charging duration and high charging power may threaten the safe and efficient...... station into consideration. Fuzzy logic inference system is applied to simulate the charging decision of EV drivers at fast charging station. Due to increasing EV loads in power system, the potential traffic congestion in fast charging stations is modeled and evaluated by queuing theory with spatial...

  2. Competitive Electricity Market Regulation in the United States: A Primer

    Energy Technology Data Exchange (ETDEWEB)

    Flores-Espino, Francisco [National Renewable Energy Lab. (NREL), Golden, CO (United States); Tian, Tian [National Renewable Energy Lab. (NREL), Golden, CO (United States); Chernyakhovskiy, Ilya [National Renewable Energy Lab. (NREL), Golden, CO (United States); Chernyakhovskiy, Ilya [National Renewable Energy Lab. (NREL), Golden, CO (United States); Miller, Mackay [National Grid, Warwick (United Kingdom)

    2016-12-01

    The electricity system in the United States is a complex mechanism where different technologies, jurisdictions and regulatory designs interact. Today, two major models for electricity commercialization operate in the United States. One is the regulated monopoly model, in which vertically integrated electricity providers are regulated by state commissions. The other is the competitive model, in which power producers can openly access transmission infrastructure and participate in wholesale electricity markets. This paper describes the origins, evolution, and current status of the regulations that enable competitive markets in the United States.

  3. Green electricity policies in the United States: case study

    International Nuclear Information System (INIS)

    Menz, Fredric C.

    2005-01-01

    While there has been interest in promoting the use of renewable energy in electricity production for a number of years in the United States, the market share of non-hydro renewable energy sources in electricity production has remained at about 2 percent over the past decade. The paper reviews the principal energy resources used for electricity production, considers the changing regulatory environment for the electricity industry, and describes government policies that have been used to promote green electricity in the United States, with an emphasis on measures adopted by state governments. Factors influencing the development of green power markets are also discussed, including underlying economic issues, public policy measures, the regulatory environment, external costs, and subsidies. Without significant increases in fossil fuel prices, much more stringent environmental regulations, or significant changes in electricity customer preferences, green electricity markets are likely to develop slowly in the United States

  4. United States electric industry : restructuring in review

    International Nuclear Information System (INIS)

    Slocum Hollis, S.

    2004-01-01

    This paper provides a detailed review of the United States electric power industry. The aim of the review was to clarify and better define current industry procedures and practices in light of significant and recent restructuring. In addition, recent bankruptcies and the power blackout in 2003 have raised concerns over industry practices. Issues concerning Independent System Operators (ISO) and regional transmission organizations were evaluated, with reference to an evolution and implementation of Regional Transmission Organization (RTO) policy, including a cost-benefit analysis. A background of RTO formations was provided with reference to consolidation, selection process and transfer of assets. Standard market design, network access and pricing issues were reviewed, as well as market and reliability concerns. Issues concerning affiliate treatment, shortages and the effect of sale of securities were presented. Various approaches to congestion management were examined, with examples from California and New England. Market monitoring issues, investigations and hearings were also examined, with examples and orders, including details of refunds. Measures to improve reliability were reviewed, including: management systems, benefit margins, requirements, assurance agreements and reserve markets. Issues concerning information access were presented, including: Open Access Same-time Information System (OASIS) requirements; tagging; standard business practices and protocols; and quarterly report practices and protocols. Interconnection policies were reviewed with reference to applicability, service options and pricing. The issue of variations was examined, with case examples concerning cost allocation, contract rights and treatment of specific costs. Jurisdiction issues concerning corporate realignments and power exchanges were presented, as well as specific services and state-federal relations. Issues concerning mergers and merger policy were also discussed, with reference

  5. The Electric Fleet Size and Mix Vehicle Routing Problem with Time Windows and Recharging Stations

    DEFF Research Database (Denmark)

    Hiermann, Gerhard; Puchinger, Jakob; Røpke, Stefan

    2016-01-01

    Due to new regulations and further technological progress in the field of electric vehicles, the research community faces the new challenge of incorporating the electric energy based restrictions into vehicle routing problems. One of these restrictions is the limited battery capacity which makes...... detours to recharging stations necessary, thus requiring efficient tour planning mechanisms in order to sustain the competitiveness of electric vehicles compared to conventional vehicles. We introduce the Electric Fleet Size and Mix Vehicle Routing Problem with Time Windows and Recharging Stations (E......-FSMFTW) to model decisions to be made with regards to fleet composition and the actual vehicle routes including the choice of recharging times and locations. The available vehicle types differ in their transport capacity, battery size and acquisition cost. Furthermore, we consider time windows at customer...

  6. Analysis and quality of service evaluation of a fast charging station for electric vehicles

    International Nuclear Information System (INIS)

    Zenginis, Ioannis; Vardakas, John S.; Zorba, Nizar; Verikoukis, Christos V.

    2016-01-01

    Electrification of transportation is considered as one of the most promising ways to mitigate climate change and reduce national security risks from oil and gasoline imports. Fast charging stations that provide high quality of service will facilitate the wide market penetration of electric vehicles. In this paper, the operation of a fast charging station is analyzed by employing a novel queuing model. The proposed analysis considers that the various electric vehicle models are classified by their battery size, and computes the customers' mean waiting time in the queue by taking into account the available charging spots, as well as the stochastic arrival process and the stochastic recharging needs of the various electric vehicle classes. Furthermore, a charging strategy is proposed according to which the drivers are motivated to limit their energy demands. The implementation of the proposed strategy allows the charging station to serve more customers without any increase in the queue waiting time. The high precision of the present analytical model is confirmed through simulations. Therefore, it may be utilized by existing fast charging station operators that need to provide high quality of service, or by future investors that need to design an efficient installation. - Highlights: • A fast charging station for multiple classes of electric vehicles is presented and analyzed. • A novel multiclass queuing model is presented for the mean queue waiting time derivation. • The system's arrival rate capacity is derived given a maximum tolerable waiting time limit. • A charging strategy is proposed aiming at increasing the system's arrival rate capacity. • The charging station operator's revenue is calculated based on the energy drawn by the electric vehicles.

  7. Design of electric vehicle charging station based on wind and solar complementary power supply

    Science.gov (United States)

    Wang, Li

    2018-05-01

    Electric vehicles have become a major trend in the development of the automobile industry. Green energy saving is an important feature of their development. At the same time, the related charging facilities construction is also critical. If we improve the charging measures to adapt to its green energy-saving features, it will be to a greater extent to promote its further development. This article will propose a highly efficient green energy-saving charging station designed for the electric vehicles.

  8. Electricity Generation Through the Koeberg Nuclear Power Station of Eskom in South Africa

    International Nuclear Information System (INIS)

    Dladla, G.; Joubert, J.

    2015-01-01

    The poster provides information on the process of nuclear energy generation in a nuclear power plant in order to produce electricity. Nuclear energy currently provides approximately 11% of the world’s electricity needs, with Koeberg Nuclear Power Station situated in the Western Cape providing 4.4% of South Africa’s electricity needs. As Africa’s first nuclear power station, Koeberg has an installed capacity of 1910 MW of power. Koeberg’ s total net output is 1860 MW. While there are significant differences, there are many similarities between nuclear power plants and other electrical generating facilities. Uranium is used for fuel in nuclear power plants to make electricity. With the exception of solar, wind, and hydroelectric plants, all others including nuclear plants convert water to steam that spins the propeller-like blades of a turbine that spins the shaft of a generator. Inside the generator coils of wire and magnetic fields interact to create electricity. The energy needed to boil water into steam is produced in one of two ways: by burning coal, oil, or gas (fossil fuels) in a furnace or by splitting certain atoms of uranium in a nuclear energy plant. The uranium fuel generates heat through a controlled fission process fission, which is described in this poster presentation. The Koeberg Nuclear Power Station is a Pressurised water reactor (PWR). The operating method and the components of the Koeberg Power Station are also described. The nuclear waste generated at a nuclear power station is described under three headings— low-level waste, intermediate-level waste and used or spent fuel, which can be solid, liquid or gaseous. (author)

  9. Energy and exergy analysis of electricity generation from natural gas pressure reducing stations

    International Nuclear Information System (INIS)

    Neseli, Mehmet Alparslan; Ozgener, Onder; Ozgener, Leyla

    2015-01-01

    Highlights: • Forecasting the recoverable energy from natural gas pressure reduction stations. • Electricity generation through pressure reduction stations via turboexpanders. • A thermodynamics analysis of PRS. - Abstract: Electricity generation or power recovery through pressure reduction stations (PRS) for general use has not been realized in Izmir. The main objective of the present study was to do a case study for calculating electricity to be recovered in one natural gas pressure reduction stations in Izmir. It is the first forecasting study to obtain energy from natural gas pressure-reducing stations in Izmir. Energy can be obtained from natural gas PRS with turbo-expanders instead of using throttle valves or regulators from the PRS. The exergy performance of PRS with TE is evaluated in this study. Exergetic efficiencies of the system and components are determined to assess their individual performances. Based upon pressure change and volumetric flow rate, it can be obtained by recovering average estimated installed capacity and annual energy 494.24 kW, 4113.03 MW h, respectively. In terms of estimated installed capacity power and annual energy, the highest level is 764.88 kW, approximately 6365.34 MW h, in Aliaga PRS. Also it can be seen that CO 2 emission factor average value is 295.45 kg/MW h

  10. 75 FR 52045 - Arizona Public Service Company, Palo Verde Nuclear Generating Station, Unit 3; Environmental...

    Science.gov (United States)

    2010-08-24

    ... Company, Palo Verde Nuclear Generating Station, Unit 3; Environmental Assessment and Finding of No.... NPF-74, issued to Arizona Public Service Company (APS, the licensee), for operation of Palo Verde... Statement for the Palo Verde Nuclear Generating Station, NUREG-0841, dated February 1982. Agencies and...

  11. Method of sharing mobile unit state information between base station routers

    NARCIS (Netherlands)

    Bosch, H.G.P.; Mullender, Sape J.; Polakos, Paul Anthony; Rajkumar, Ajay; Sundaram, Ganapathy S.

    2007-01-01

    The present invention provides a method of operating a first base station router. The method may include transmitting state information associated with at least one inactive mobile unit to at least one second base station router. The state information is usable to initiate an active session with the

  12. Method of sharing mobile unit state information between base station routers

    NARCIS (Netherlands)

    Bosch, H.G.P.; Mullender, Sape J.; Polakos, Paul Anthony; Rajkumar, Ajay; Sundaram, Ganapathy S.

    2010-01-01

    The present invention provides a method of operating a first base station router. The method may include transmitting state information associated with at least one inactive mobile unit to at least one second base station router. The state information is usable to initiate an active session with the

  13. Papers of 4. Scientific-Technical Seminar: Material Study for Electric Power Stations and Energetics

    International Nuclear Information System (INIS)

    1997-01-01

    The research on the materials commonly used in electric power stations and energetics have been summarized in the course of the seminar. Especially a different kinds of steels have been investigated from the view point of their desirable mechanical and corrosion properties

  14. A Control Algorithm for Electric Vehicle Fast Charging Stations Equipped with Flywheel Energy Storage Systems

    DEFF Research Database (Denmark)

    Sun, Bo; Dragicevic, Tomislav; Freijedo Fernandez, Francisco Daniel

    2016-01-01

    This paper proposes a control strategy for plugin electric vehicle (PEV) fast charging station (FCS) equipped with a flywheel energy storage system (FESS). The main role of the FESS is not to compromise the predefined charging profile of PEV battery during the provision of a hysteresis-type active...

  15. Two-Level Control for Fast Electrical Vehicle Charging Stations with Multi Flywheel Energy Storage System

    DEFF Research Database (Denmark)

    SUN, BO; Dragicevic, Tomislav; Vasquez, Juan Carlos

    2015-01-01

    This paper applies a hierarchical control for a fast charging station (FCS) composed of paralleled PWM rectifier and dedicated paralleled multiple flywheel energy storage systems (FESSs), in order to mitigate peak power shock on grid caused by sudden connection of electrical vehicle (EV) chargers...

  16. The effects of solar-geomagnetically induced currents on electrical systems in nuclear power stations

    International Nuclear Information System (INIS)

    Subudhi, M.; Carroll, D.P.; Kasturi, S.

    1994-01-01

    This report presents the results of a study to evaluate the potential effects of geomagnetically induced currents (GICs) caused by the solar disturbances on the in-plant electrical distribution system and equipment in nuclear power stations. The plant-specific electrical distribution system for a typical nuclear plant is modeled using the ElectroMagnetic Transient Program (EMTP). The computer model simulates online equipment and loads from the station transformer in the switchyard of the power station to the safety-buses at 120 volts to which all electronic devices are connected for plant monitoring. The analytical model of the plant's electrical distribution system is studied to identify the transient effects caused by the half-cycle saturation of the station transformers due to GIC. This study provides results of the voltage harmonics levels that have been noted at various electrical buses inside the plant. The emergency circuits appear to be more susceptible to high harmonics due to the normally light load conditions. In addition to steady-state analysis, this model was further analyzed simulating various plant transient conditions (e.g., loss of load or large motor start-up) occurring during GIC events. Detail models of the plant's protective relaying system employed in bus transfer application were included in this model to study the effects of the harmonic distortion of the voltage input. Potential harmonic effects on the uniterruptable power system (UPS) are qualitatively discussed as well

  17. Site preparation and excavation works for the foundation of station main building among construction works for No. 1 unit in Kashiwazaki-Kariwa Nuclear Pwer Station

    International Nuclear Information System (INIS)

    Ueyama, Koreyasu

    1982-01-01

    Tokyo Electric Power Co., Inc., is planning the nuclear power station of final capacity 8,000 MW (7 units) in the region spread over Kashiwazaki City and Kariwa Village in Niigata Prefecture. For No. 1 unit (1100 MWe BWR), the reactor installation license was obtained in September, 1977, the site preparation and road construction started in April, 1978, and harbour construction works started in August, 1979. The construction works are now at the peak, and the overall progressing rate as of the end of June, 1982, is about 51 %. The site is a hilly region of dune along the coast of the Sea of Japan, and No. 1 unit is located in the southern part of the site. This paper reports on the outline of the project, site preparation and excavation works for the foundation of the station main building. For the site preparation and the excavation works for the foundation the main building, the shape of slope cutting, the design of landslide-preventing wall for the vertical excavation for the reactor complex building, and the construction plan and the result are reported. For underground water impermeable wall works, its outline, groundwater condition, groundwater simulation analysis, the investigation of wall installation, the wall structure and construction are described in detail. Also the outline of the control of slope face measurement, the control standards and the measured results are reported. (Wakatsuki, Y.)

  18. Site preparation and excavation works for the foundation of station main building among construction works for No. 1 unit in Kashiwazaki-Kariwa Nuclear Power Station

    Energy Technology Data Exchange (ETDEWEB)

    Ueyama, Koreyasu [Tokyo Electric Power Co., Inc. (Japan)

    1982-09-01

    Tokyo Electric Power Co., Inc., is planning the nuclear power station of final capacity 8,000 MW (7 units) in the region spread over Kashiwazaki City and Kariwa Village in Niigata Prefecture. For No. 1 unit (1100 MWe BWR), the reactor installation license was obtained in September, 1977, the site preparation and road construction started in April, 1978, and harbour construction works started in August, 1979. The construction works are now at the peak, and the overall progressing rate as of the end of June, 1982, is about 51 %. The site is a hilly region of dune along the coast of the Sea of Japan, and No. 1 unit is located in the southern part of the site. This paper reports on the outline of the project, site preparation and excavation works for the foundation of the station main building. For the site preparation and the excavation works for the foundation the main building, the shape of slope cutting, the design of landslide-preventing wall for the vertical excavation for the reactor complex building, and the construction plan and the result are reported. For underground water impermeable wall works, its outline, groundwater condition, groundwater simulation analysis, the investigation of wall installation, the wall structure and construction are described in detail. Also the outline of the control of slope face measurement, the control standards and the measured results are reported.

  19. Optimal planning of electric vehicle charging station at the distribution system using hybrid optimization algorithm

    DEFF Research Database (Denmark)

    Awasthi, Abhishek; Venkitusamy, Karthikeyan; Padmanaban, Sanjeevikumar

    2017-01-01

    India's ever increasing population has made it necessary to develop alternative modes of transportation with electric vehicles being the most preferred option. The major obstacle is the deteriorating impact on the utility distribution system brought about by improper setup of these charging...... stations. This paper deals with the optimal planning (siting and sizing) of charging station infrastructure in the city of Allahabad, India. This city is one of the upcoming smart cities, where electric vehicle transportation pilot project is going on under Government of India initiative. In this context......, a hybrid algorithm based on genetic algorithm and improved version of conventional particle swarm optimization is utilized for finding optimal placement of charging station in the Allahabad distribution system. The particle swarm optimization algorithm re-optimizes the received sub-optimal solution (site...

  20. Autonomous power expert fault diagnostic system for Space Station Freedom electrical power system testbed

    Science.gov (United States)

    Truong, Long V.; Walters, Jerry L.; Roth, Mary Ellen; Quinn, Todd M.; Krawczonek, Walter M.

    1990-01-01

    The goal of the Autonomous Power System (APS) program is to develop and apply intelligent problem solving and control to the Space Station Freedom Electrical Power System (SSF/EPS) testbed being developed and demonstrated at NASA Lewis Research Center. The objectives of the program are to establish artificial intelligence technology paths, to craft knowledge-based tools with advanced human-operator interfaces for power systems, and to interface and integrate knowledge-based systems with conventional controllers. The Autonomous Power EXpert (APEX) portion of the APS program will integrate a knowledge-based fault diagnostic system and a power resource planner-scheduler. Then APEX will interface on-line with the SSF/EPS testbed and its Power Management Controller (PMC). The key tasks include establishing knowledge bases for system diagnostics, fault detection and isolation analysis, on-line information accessing through PMC, enhanced data management, and multiple-level, object-oriented operator displays. The first prototype of the diagnostic expert system for fault detection and isolation has been developed. The knowledge bases and the rule-based model that were developed for the Power Distribution Control Unit subsystem of the SSF/EPS testbed are described. A corresponding troubleshooting technique is also described.

  1. Optimal selection of Orbital Replacement Unit on-orbit spares - A Space Station system availability model

    Science.gov (United States)

    Schwaab, Douglas G.

    1991-01-01

    A mathematical programing model is presented to optimize the selection of Orbital Replacement Unit on-orbit spares for the Space Station. The model maximizes system availability under the constraints of logistics resupply-cargo weight and volume allocations.

  2. Evaluation of High-Performance Rooftop HVAC Unit Naval Air Station Key West, Florida

    Energy Technology Data Exchange (ETDEWEB)

    Howett, Daniel H. [ORNL; Desjarlais, Andre Omer [ORNL; Cox, Daryl [ORNL

    2018-01-01

    This report documents performance of a high performance rooftop HVAC unit (RTU) at Naval Air Station Key West, FL. This report was sponsored by the Federal Energy Management Program as part of the "High Performance RTU Campaign".

  3. 75 FR 8757 - Nebraska Public Power District, Cooper Nuclear Station, Unit 1; Notice of Availability of the...

    Science.gov (United States)

    2010-02-25

    ..., Cooper Nuclear Station, Unit 1; Notice of Availability of the Draft Supplement 41 to the Generic... Renewal of Cooper Nuclear Station, Unit 1 Notice is hereby given that the U.S. Nuclear Regulatory... operating license DPR-46 for an additional 20 years of operation for Cooper Nuclear Station, Unit 1 (CNS-1...

  4. Safety Evaluation Report related to the operation of Limerick Generating Station, Units 1 and 2 (Docket Nos. 50-352 and 50-353). Supplement 2

    International Nuclear Information System (INIS)

    1984-10-01

    In August 1983 the staff of the Nuclear Regulatory Commission issued its Safety Evaluation Report (NUREG-0991) regarding the application of the Philadelphia Electric Company (the applicant) for licenses to operate the Limerick Generating Station, Units 1 and 2, located on a site in Montgomery and Chester Counties, Pennsylvania. This supplement addresses further issues that require resolution and closes them out

  5. Electric power and the environment: An analysis of pollutant emissions at Argentine state-owned electric power stations

    Energy Technology Data Exchange (ETDEWEB)

    Carnevali, D; Suarez, C E [Instituto de Economia Energetica, San Carlos de Bariloche (Argentina)

    1991-08-01

    This paper describes the impact on particulate and 'greenhouse gases' emissions of substitution policies implemented by Argentine state-owned electric power stations. Those policies involve the substitution, on the one hand, of hydroelectric and nuclear energy for conventional thermal energy and, on the other hand, of natural gas for fuel oil, diesel oil and coal. As additional investments are required in conventional thermal power stations to prevent environmental pollution, the investment savings generated by substitution policies have been calculated. While the environmental impacts of hydroelectric, nuclear and natural gas facilities is locally significant and is experienced in geographical areas away from cities, there can be no doubt that the substitution policies implemented in the Argentine electricity sector have overall both ecological and economic benefits. (author). 1 ref., 8 figs, 2 tabs.

  6. Probabilistic Harmonic Calculation in Distribution Networks with Electric Vehicle Charging Stations

    Directory of Open Access Journals (Sweden)

    Jianxue Wang

    2014-01-01

    Full Text Available Integrating EV charging station into power grid will bring impacts on power system, among which the most significant one is the harmonic pollution on distribution networks. Due to the uncertainty of the EV charging process, the harmonic currents brought by EV charging stations have a random nature. This paper proposed a mathematical simulation method for studying the working status of charging stations, which considers influencing factors including random leaving factor, electricity price, and waiting time. Based on the proposed simulation method, the probability distribution of the harmonic currents of EV charging stations is obtained and used in the calculation of the probability harmonic power flow. Then the impacts of EVs and EV charging stations on distribution networks can be analyzed. In the case study, the proposed simulation and analysis method is implemented on the IEEE-34 distribution network. The influences of EV arrival rates, the penetration rate, and the accessing location of EV charging station are also investigated. Results show that this research has good potential in guiding the planning and construction of charging station.

  7. Considering the dynamic refueling behavior in locating electric vehicle charging stations

    Science.gov (United States)

    Liu, K.; Sun, X. H.

    2014-11-01

    Electric vehicles (EVs) will certainly play an important role in addressing the energy and environmental challenges at current situation. However, location problem of EV charging stations was realized as one of the key issues of EVs launching strategy. While for the case of locating EV charging stations, more influence factors and constraints need to be considered since the EVs have some special attributes. The minimum requested charging time for EVs is usually more than 30minutes, therefore the possible delay time due to waiting or looking for an available station is one of the most important influence factors. In addition, the intention to purchase and use of EVs that also affects the location of EV charging stations is distributed unevenly among regions and should be considered when modelling. Unfortunately, these kinds of time-spatial constraints were always ignored in previous models. Based on the related research of refuelling behaviours and refuelling demands, this paper developed a new concept with dual objectives of minimum waiting time and maximum service accessibility for locating EV charging stations - named as Time-Spatial Location Model (TSLM). The proposed model and the traditional flow-capturing location model are applied on an example network respectively and the results are compared. Results demonstrate that time constraint has great effects on the location of EV charging stations. The proposed model has some obvious advantages and will help energy providers to make a viable plan for the network of EV charging stations.

  8. A multi-factor GIS method to identify optimal geographic locations for electric vehicle (EV) charging stations

    Science.gov (United States)

    Zhang, Yongqin; Iman, Kory

    2018-05-01

    Fuel-based transportation is one of the major contributors to poor air quality in the United States. Electric Vehicle (EV) is potentially the cleanest transportation technology to our environment. This research developed a spatial suitability model to identify optimal geographic locations for installing EV charging stations for travelling public. The model takes into account a variety of positive and negative factors to identify prime locations for installing EV charging stations in Wasatch Front, Utah, where automobile emission causes severe air pollution due to atmospheric inversion condition near the valley floor. A walkable factor grid was created to store index scores from input factor layers to determine prime locations. 27 input factors including land use, demographics, employment centers etc. were analyzed. Each factor layer was analyzed to produce a summary statistic table to determine the site suitability. Potential locations that exhibit high EV charging usage were identified and scored. A hot spot map was created to demonstrate high, moderate, and low suitability areas for installing EV charging stations. A spatially well distributed EV charging system was then developed, aiming to reduce "range anxiety" from traveling public. This spatial methodology addresses the complex problem of locating and establishing a robust EV charging station infrastructure for decision makers to build a clean transportation infrastructure, and eventually improve environment pollution.

  9. Pilgrim Nuclear Power Station, Unit 1. Annual operating report, 1975

    International Nuclear Information System (INIS)

    1976-01-01

    Net electric power generated in 1975 was 1,074,401 MW(e) with the generator on line 4,680.7 hrs. Information is presented concerning operations, maintenance, radioactive effluents and waste shipments, health physics, shutdowns, and personnel exposures

  10. Pilgrim Nuclear Power Station, Unit 1. Annual operating report, 1975

    International Nuclear Information System (INIS)

    1976-01-01

    Net electrical power generated was 2,587,248 MWH(e) with the reactor on line 6,242.4 hr. Information is presented concerning operations, power generation, shutdowns, corrective maintenance, chemistry and radiochemistry, occupational radiation exposure, release of radioactive materials, and reportable occurrences

  11. On the legal nature of electricity supply contracts concluded by electricity companies and power stations generating electricity from renewable energy sources

    International Nuclear Information System (INIS)

    Herrmann, B.J.

    1998-01-01

    Section 2 of the German Act for enhanced use of electricity from renewable energy sources (StEG) defines the obligation to contract but not the contractual obligations, i.e. the conditions of performance of the contract (supply and purchase of electricity and the legal obligations of contractors). The analysis here shows that characterising this mandatory contract required by the act as an agreement of purchase and sale more appropriately describes the legal nature of the contract and the intent of the legislator than other contracts for supply and purchase of electricity, as for instance those concluded by electric utilities and their customers. One specific aspect elaborated by the author is that the StEG does not constitute an obligation to supply on the part of the renewable energy generating power station, so that the power station operator is not obliged to ensure availability of the electricity at any time or in terms of supplies that can be called off by the purchasing utility, whereas the electric utility is obliged by section 2 of the StEG to purchase the contractual amounts from the generating station. (orig./CB) [de

  12. Accident analysis of Fukushima Daiichi Nuclear Power Station unit 1

    International Nuclear Information System (INIS)

    Kobayashi, Masahide; Narabayashi, Tadashi; Tsuji, Masashi; Chiba, Go; Nagata, Yasunori; Shimoe, Tomohiro

    2015-01-01

    As a result of the Great East Japan Earthquake that occurred on 11 March 2011, all AC and DC power at the Fukushima Daiichi NPP units 1 to 3 were lost soon after the tsunami. The core cooling function was lost, and the cores of units 1 to 3 were damaged. The purpose of this work is to clarify the progress of the accident in unit 1, which was damaged the earliest among the 3 units. Therefore, an original severe accident analysis code was developed, and the progress of the accident was evaluated from the analysis results and the actual data. As a result, the leakage path from a pressure vessel was clarified, and some lessons and knowledge were gained. (author)

  13. AIR POLLUTION: Emissions from Older Electricity Generating Units

    National Research Council Canada - National Science Library

    2002-01-01

    .... While fossil fuels-coal, natural gas, and oil-account for more than two thirds of our electricity, generating units that burn these fuels are major sources of airborne emissions that pose human...

  14. Quad-Cities Station, Units 1 and 2. Semiannual operating report, January--June 1975

    International Nuclear Information System (INIS)

    1975-01-01

    Unit 1 generated 2,024,125 net electrical MWH and the generator was on line 3162.6 hours. Unit 2 generated 746,184 net electrical MWH and was on line 1475.3 hrs. Data is included concerning operations, power generation, shutdowns, maintenance, changes, and tests. (FS)

  15. Counter rotating type hydroelectric unit suitable for tidal power station

    International Nuclear Information System (INIS)

    Kanemoto, T; Suzuki, T

    2010-01-01

    The counter rotating type hydroelectric unit, which is composed of the axial flow type tandem runners and the peculiar generator with double rotational armatures,was proposed to utilize effectively the tidal power. In the unit, the front and the rear runners counter drive the inner and the outer armatures of the generator, respectively. Besides, the flow direction at the rear runner outlet must coincide with the flow direction at the front runner inlet, because the angular momentum through the rear runner must coincides with that through the front runner. That is, the flow runs in the axial direction at the rear runner outlet while the axial inflow at the front runner inlet. Such operations are suitable for working at the seashore with rising and falling tidal flows, and the unit may be able to take place of the traditional bulb type turbines. The tandem runners were operated at the on-cam conditions, in keeping the induced frequency constant. The output and the hydraulic efficiency are affected by the adjustment of the front and the blade setting angles. The both optimum angles giving the maximum output and/or efficiency were presented at the various discharges/heads. To promote more the tidal power generation by this type unit, the runners were also modified so as to be suitable for both rising and falling flows. The hydraulic performances are acceptable while the output is determined mainly by the trailing edge profiles of the runner blades.

  16. Daily snow depth measurements from 195 stations in the United States

    Energy Technology Data Exchange (ETDEWEB)

    Allison, L.J. [ed.] [Oak Ridge National Lab., TN (United States). Carbon Dioxide Information Analysis Center; Easterling, D.R.; Jamason, P.; Bowman, D.P.; Hughes, P.Y.; Mason, E.H. [National Oceanic and Atmospheric Administration, Asheville, NC (United States). National Climatic Data Center

    1997-02-01

    This document describes a database containing daily measurements of snow depth at 195 National Weather Service (NWS) first-order climatological stations in the United States. The data have been assembled and made available by the National Climatic Data Center (NCDC) in Asheville, North Carolina. The 195 stations encompass 388 unique sampling locations in 48 of the 50 states; no observations from Delaware or Hawaii are included in the database. Station selection criteria emphasized the quality and length of station records while seeking to provide a network with good geographic coverage. Snow depth at the 388 locations was measured once per day on ground open to the sky. The daily snow depth is the total depth of the snow on the ground at measurement time. The time period covered by the database is 1893--1992; however, not all station records encompass the complete period. While a station record ideally should contain daily data for at least the seven winter months (January through April and October through December), not all stations have complete records. Each logical record in the snow depth database contains one station`s daily data values for a period of one month, including data source, measurement, and quality flags.

  17. Reactive Power Support of Electrical Vehicle Charging Station Upgraded with Flywheel Energy Storage System

    DEFF Research Database (Denmark)

    SUN, BO; Dragicevic, Tomislav; Savaghebi, Mehdi

    2015-01-01

    Electrical vehicles (EVs) are presenting increasingly potential to replace the conventional fossil fuel based vehicles due to environmental friendly characteristic. Accordingly, Charging Stations (CS), as an intermediate between grid and large numbers of EVs, are supposed to have more critical...... influence on future smart transportation network. This paper explores an off-board charging station upgraded with flywheel energy storage system that could provide a reactive power support to the grid utility. A supervisory control scheme based on distributed bus signaling is proposed to coordinate...... the operation of each component in the system. As a result, the charging station could supply the reactive power support to the utility grid without compromising the charging algorithm and preserve the battery’s lifetime. Finally, the real-time simulation results based on dSPACE1006 verifies the proposed...

  18. Assessment of environmental effects on Space Station Freedom Electrical Power System

    Science.gov (United States)

    Lu, Cheng-Yi; Nahra, Henry K.

    1991-01-01

    Analyses of EPS (electrical power system) interactions with the LEO (low earth orbit) environment are described. The results of these analyses will support EPS design so as to be compatible with the natural and induced environments and to meet power, lifetime, and performance requirements. The environmental impacts to the Space Station Freedom EPS include aerodynamic drag, atomic oxygen erosion, ultraviolet degradation, VXB effect, ionizing radiation dose and single event effects, electromagnetic interference, electrostatic discharge, plasma interactions (ion sputtering, arcing, and leakage current), meteoroid and orbital debris threats, thermal cycling effects, induced current and voltage potential differences in the SSF due to induced electric field, and contamination degradation.

  19. Space station electrical power distribution analysis using a load flow approach

    Science.gov (United States)

    Emanuel, Ervin M.

    1987-01-01

    The space station's electrical power system will evolve and grow in a manner much similar to the present terrestrial electrical power system utilities. The initial baseline reference configuration will contain more than 50 nodes or busses, inverters, transformers, overcurrent protection devices, distribution lines, solar arrays, and/or solar dynamic power generating sources. The system is designed to manage and distribute 75 KW of power single phase or three phase at 20 KHz, and grow to a level of 300 KW steady state, and must be capable of operating at a peak of 450 KW for 5 to 10 min. In order to plan far into the future and keep pace with load growth, a load flow power system analysis approach must be developed and utilized. This method is a well known energy assessment and management tool that is widely used throughout the Electrical Power Utility Industry. The results of a comprehensive evaluation and assessment of an Electrical Distribution System Analysis Program (EDSA) is discussed. Its potential use as an analysis and design tool for the 20 KHz space station electrical power system is addressed.

  20. 76 FR 24064 - Arizona Public Service Company, Palo Verde Nuclear Generating Station, Units 1, 2, and 3, Notice...

    Science.gov (United States)

    2011-04-29

    ... Service Company, Palo Verde Nuclear Generating Station, Units 1, 2, and 3, Notice of Issuance of Renewed... Company (licensee), the operator of the Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (PVNGS... Plants: Supplement 43, Regarding Palo Verde Nuclear Generating Station,'' issued January 2011, discusses...

  1. Orientation of Space Station Freedom electrical power system in environmental effects assessment

    Science.gov (United States)

    Lu, Cheng-Yi

    1990-01-01

    The orientation effects of six Space Station Freedom Electrical Power System (EPS) components are evaluated for three environmental interactions: aerodynamic drag, atomic oxygen erosion, and orbital debris impact. Designers can directly apply these orientation factors to estimate the magnitude of the examined environment and the environmental effects for the EPS component of interest. The six EPS components are the solar array, photovoltaic module radiator, integrated equipment assembly, solar dynamic concentrator, solar dynamic radiator, and beta gimbal.

  2. Electric Vehicle Fast-Charging Station Unified Modeling and Stability Analysis in the dq Frame

    Directory of Open Access Journals (Sweden)

    Xiang Wang

    2018-05-01

    Full Text Available The electric vehicle fast-charging station is an important guarantee for the popularity of electric vehicle. As the fast-charging piles are voltage source converters, stability issues will occur in the grid-connected fast-charging station. Since the dynamic input admittance of the fast-charging pile and the dynamic output impedance play an important role in the interaction system stability, the station and grid interaction system is regarded as load-side and source-side sub-systems to build the dynamic impedance model. The dynamic input admittance in matrix form is derived from the fast-charging pile current control loop considering the influence of the LC filter. Similarly, the dynamic output impedance can be obtained similarly by considering the regional power grid capacity, transformer capacity, and feed line length. On this basis, a modified forbidden region-based stability criterion is used for the fast-charging station stability analysis. The frequency-domain case studies and time-domain simulations are presented next to show the influence of factors from both the power grid side and fast-charging pile side. The simulation results validated the effectiveness of the dq frame impedance model and the stability analysis method.

  3. Introduction of Electric Vehicle Charging Stations to University Campuses: A Case Study for the University of Georgia from 2014 to 2017

    Directory of Open Access Journals (Sweden)

    Sierra Hovet

    2018-06-01

    Full Text Available Electric vehicles (EVs are becoming increasingly popular in the United States of America (USA. EVs attract buyers with benefits including energy efficiency and environmental friendliness. As EV usage grows, more public spaces are installing EV charging stations. This paper presents a comprehensive analysis of EV charging station usage at the University of Georgia (UGA in Athens, Georgia. Three ChargePoint EV charging stations at UGA were used to collect data about each of 3204 charging events that occurred from 10 April 2014 to 20 June 2017. The charging event data included start date, start time, length of parking time, length of charging time, amount of energy delivered, and the postal code entered by the user during ChargePoint account registration. Analytical methods were proposed to obtain information about EV charging behavior, charging station occupancy, and geolocation of charging station users. The methodology presented here was time- and cost-effective, as well as scalable to other organizations that own charging stations. Because this study took place at a university, the results presented here can be used as a reference for EV charging station usage in other college towns in the USA that do not have EV charging stations but are planning to develop EV infrastructure.

  4. Instructor station of full scope simulator for Qinshan 300 MW Nuclear Power Unit

    International Nuclear Information System (INIS)

    Wu Fanghui

    1996-01-01

    The instructor station of Full Scope Simulator for Qinshan 300 MW Nuclear Power Unit is based on SGI graphic workstation. The operation system is real time UNIX, and the development of man-machine interface, mainly depends on standard X window system, special for X TOOLKITS and MOTIF. The instructor station has been designed to increase training effectiveness and provide the most flexible environment possible to enhance its usefulness. Based on experiences in the development of the instructor station, many new features have been added including I/O panel diagrams, simulation diagrams, graphic operation of malfunction, remote function and I/O overrides etc

  5. Data book of examination of the ruptured pipe at the Hamaoka Nuclear Power Station Unit-1

    International Nuclear Information System (INIS)

    2002-03-01

    In order to investigate root cause of the pipe rupture, which took place at the Hamaoka Nuclear Power Station Unit-1 of Chubu Electric Power Company on November 7, 2001, a task force was established within the Nuclear and Industrial Safety Agency (NISA) and initiated a detailed investigation of the ruptured pipe. The Japan Atomic Energy Research Institute (JAERI) was asked from the Ministry of Education, Culture, Sports, Science and Technology (MEXT) in response to the request from NISA to cooperate as an independent neutral organization with NISA and perform an examination of the ruptured pipe independently from Chubu Electric Power Company. JAERI accepted the request by considering the fact that JAERI is an integrated research institution for nuclear research and development, a prime research institution for nuclear safety research, a research institution with experience of root-cause investigation of various nuclear incidents and accidents of domestic as well as overseas, and a research institution provided with advanced examination facilities necessary for examination of the ruptured pipe. The JAERI examination group was formed at the Tokai Research Establishment and conducted detailed and thorough examination of the pieces taken from the ruptured pipe primarily in the Reactor Fuel Examination Facility (RFEF) with the use of tools such as scanning electron microscopes and other equipments. Purpose of examination was to provide technical information in order to identify causes of the pipe rupture through examination of the pieces taken from the ruptured region of the pipe. The result of the present examination has already been reported to NISA and has also been published as the JAERI-Tech report No.2001-94. This report is a data book containing the detailed data obtained by the present examination. (author)

  6. Report of examination of the ruptured pipe at the Hamaoka Nuclear Power Station Unit-1

    International Nuclear Information System (INIS)

    2001-12-01

    In order to investigate root cause of the pipe rupture, which took place at the Hamaoka Nuclear Power Station Unit-1 of Chubu Electric Power Company on November 7, 2001, a task force was established within the Nuclear and Industrial Safety Agency (NISA) and initiated a detailed investigation of the ruptured pipe. The Japan Atomic Energy Research Institute (JAERI) was asked from the Ministry of Education, Culture, Sports, Science and Technology (MEXT) in response to the request from NISA to cooperate as an independent neutral organization with NISA and perform an examination of the ruptured pipe independently from Chubu Electric Power Company. JAERI accepted the request by considering the fact that JAERI is an integrated research institution for nuclear research and development, a prime research institution for nuclear safety research, a research institution with experience of root-cause investigation of various nuclear incidents and accidents of domestic as well as overseas, and a research institution provided with advanced examination facilities necessary for examination of the ruptured pipe. The JAERI examination group was formed at the Tokai Research Establishment and conducted detailed and thorough examination of the pieces taken from the ruptured pipe primarily in the Reactor Fuel Examination Facility (RFEF) with the use of tools such as scanning electron microscopes and other equipments. Purpose of examination was to provide technical information in order to identify causes of the pipe rupture through examination of the pieces taken from the ruptured region of the pipe. The following findings and conclusion were made as the result of the present examination. (1) Wall thickness of the pipe was significantly reduced in the ruptured region. (2) Dimple pattern resulting from ductile fracture by shearing was observed in the fracture surfaces of nearly all of the pieces and no indication of fatigue crack growth was found. (3) Microstructure showed a typical carbon

  7. Diagnostic testing and repair of Hollingsworth Generating Station`s Unit One

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-12-31

    This paper presents a case history of the diagnosis of a hydroelectric generator problem and the corrections implemented. The problem involved an excessive rotor imbalance coupled with a static air gap imbalance that cause severe load-sensitive vibrations. The problem constrained the plant from operating the generator unit throughout the range of its nameplate rating and caused periodic failure of the generator guide and thrust bearing. The paper describes the vibration survey and mechanical survey of the generator rotor, the pre-overhaul diagnosis, the repairs undertaken to the rotor, and the generator performance after the repair, with comparison to the pre-repair condition. The paper concludes with a discussion of the economic, operational, and logistic issues involved in the overhaul.

  8. Diagnostic testing and repair of Hollingsworth Generating Station`s Unit One

    Energy Technology Data Exchange (ETDEWEB)

    Atkins, R.; Epple, W.; Stevenson, D. [Great Lakes Power Ltd., Sault Ste. Marie, ON (Canada); Brotherton, L.; Crahan, M.; Ghate, A.

    1995-12-31

    A case history of the diagnosis and corrections implemented to resolve vibration problems in a 22,222 kVA hydroelectric generator was presented. The problem prevented the utility from operating the unit throughout the range of its nameplate rating and caused periodic failures of the generator`s guide and thrust bearing. Tests identified that the rim assembly was fastened onto the spider in a manner that resulted in tilting of the rim with respect to the axis of rotation, consequently, there was an unbalanced generator static air gap. A unique repair was implemented to fully restore the rim assembly to its proper position. Problems associated with carrying out such major in-situ repairs in a remote environment and within a scheduled maintenance outage were discussed. Economic benefits and costs associated with the repair were also discussed.

  9. Feasibility Study of a Solar-Powered Electric Vehicle Charging Station Model

    Directory of Open Access Journals (Sweden)

    Bin Ye

    2015-11-01

    Full Text Available In China, the power sector is currently the largest carbon emitter and the transportation sector is the fastest-growing carbon emitter. This paper proposes a model of solar-powered charging stations for electric vehicles to mitigate problems encountered in China’s renewable energy utilization processes and to cope with the increasing power demand by electric vehicles for the near future. This study applies the proposed model to Shenzhen City to verify its technical and economic feasibility. Modeling results showed that the total net present value of a photovoltaic power charging station that meets the daily electricity demand of 4500 kWh is $3,579,236 and that the cost of energy of the combined energy system is $0.098/kWh. In addition, the photovoltaic powered electric vehicle model has pollutant reduction potentials of 99.8%, 99.7% and 100% for carbon dioxide, sulfur dioxide, and nitrogen oxides, respectively, compared with a traditional gasoline-fueled car. Sensitivity analysis results indicated that interest rate has a relatively strong influence on COE (Cost of Energy. An increase in the interest rate from 0% to 6% increases COE from $0.027/kWh to $0.097/kWh. This analysis also suggests that carbon pricing promotes renewable energy only when the price of carbon is above $20/t.

  10. Novel wind powered electric vehicle charging station with vehicle-to-grid (V2G) connection capability

    International Nuclear Information System (INIS)

    Fathabadi, Hassan

    2017-01-01

    Highlights: • The only wind powered EV charging station reported in the literature. • The charging station maximally converts wind energy into electric energy. • Novel fast and highly accurate MPPT technique implemented in the EV charging station. • The charging station is grid-connected type with vehicle-to-grid (V2G) technology. • The charging station balances load demand in the grid connected to it. - Abstract: In this study, a novel grid-connected wind powered electric vehicle (EV) charging station with vehicle-to-grid (V2G) technology is designed and constructed. The wind powered EV charging station consists of a wind energy conversion system (WECS), a unidirectional DC/DC converter connected to the WECS, a maximum power point tracking (MPPT) controller, 15 bidirectional DC/DC converters dedicated to 15 charging stations provided for charging EVs, and a three-phase bidirectional DC/AC inverter connected to the grid. The contribution of this work is that the grid-connected wind powered EV charging station presented in this work is the only constructed EV charging station reported in the literature that uses wind energy as a renewable resource to produce electric energy for charging EVs, and moreover, it maximally converts wind energy into electric energy because it uses a novel fast and highly accurate MPPT technique proposed in this study. Other works are only simulated models without any new MPPT consideration. It is demonstrated that the constructed wind powered EV charging station is a perfect charging station that not only produces electric energy to charge EVs but also balances load demand in the grid connected to it.

  11. Retrofitting and operation solid radwaste system Dresden Station, Units 2 and 3

    International Nuclear Information System (INIS)

    Testa, J.; Homer, J.C.

    1982-01-01

    Units 2 and 3 at Dresden Station are twin 794 MW (net) BWR units that became operational in 1970 and 1971. The waste streams are typical of BWR stations, namely, bead resin and filter sludge (powdered resins and diatomaceous earth), evaporator concentrate containing approximately 25% dissolved solids and dry active waste. The original solid radwaste system utilized cement for solidification in open top 55 gallon drums. Remote handling was provided by means of a monorail with moving platforms supporting the drums. A relatively light-weight compactor was used to compact DAW into 55 gallon drums. Difficulties were experienced with this system

  12. Surry Power Station, Units 1 and 2. Semiannual operating report, January--June 1975

    International Nuclear Information System (INIS)

    1975-01-01

    Net electric power generated by Unit 1 was 2,315,124 MWH(e) and Unit 2 generated 2,062,954 MWH(e) with Unit 1 generator on line for 3,157.8 hrs and Unit 2 on line for 2,881.2 hrs. Information is presented concerning power generation, shutdowns, corrective maintenance, chemistry and radiochemistry, occupational radiation exposure, release of radioactive materials, abnormal occurrences, and environmental monitoring. (FS)

  13. Pilgrim Nuclear Power Station, Unit 1. Annual operating report for 1976

    International Nuclear Information System (INIS)

    Net electrical power generated was 2,415,511 MWH with the generator on line 5,333.6 hrs. Information is presented concerning operations, procedure changes, tests, experiments, maintenance, unit shutdowns and power reductions, and radiation doses to personnel

  14. Outdoor unit construction for an electric heat pump

    Science.gov (United States)

    Draper, R.; Lackey, R.S.

    1984-09-11

    The outdoor unit for an electric heat pump is provided with an upper portion containing propeller fan means for drawing air through the lower portion containing refrigerant coil means in the form of four discrete coils connected together in a subassembly forming a W shape, the unit being provided with four adjustable legs which are retracted in shipment, and are adjusted on site to elevate the unit to a particular height suitable for the particular location in which the unit is installed. 4 figs.

  15. Analysis of electrical systems from Cernavoda NPP - Unit 1 based on commissioning activity

    International Nuclear Information System (INIS)

    Goia, M.L.; Manolescu, I.

    1996-01-01

    Several design solutions regarding the electrical part of Cernavoda NPP Unit 1 station auxiliaries are discussed in this paper. The solutions mentioned may have different variants which should be taken into consideration in the design of Units U2 - U5. This work offers an ample debate on such matters as the supply source connection of the station auxiliaries, the use of two different voltages for the mean voltage (MV) supply, the consequence of the lack of breakers on the 24 kV part of station auxiliary transformers T03 - T04, the protection devices non correlated with the breakers to which they react, as well as the consequences of low subtransient reactance of the new stand-by Diesel generators. Besides these design solutions that can influence the station auxiliaries reliability, matters as malfunctioning of the dry type MV/LV transformers and unreliable behaviour of some MV composite insulators are also discussed. For some of the above mentioned problems the authors proposed several solutions. (authors). 1 fig., 1 tab

  16. Upgrading of fire protection arrangements at Magnox power stations in the United Kingdom

    International Nuclear Information System (INIS)

    Zhu, L.H.

    1998-01-01

    The methodology used in conducting fire hazard assessments at Magnox Reactor power stations operated by Magnox Electric plc is described. The assessments use a deterministic approach. This includes the identification of essential plant and the associated supporting systems required for the safe trip, shutdown and post-trip cooling of the reactor, assessment of the location of the essential plant and the vulnerability of these plant in the presence of a fire, assessment of essential functions against the effects of a fire and identification of improvements to the fire protection arrangements. Practical aspects of fire protection engineering on operating power stations are discussed and examples of improvements in protection described. (author)

  17. Unidirectional Magneto-Electric Dipole Antenna for Base Station: A Review

    Science.gov (United States)

    Idayachandran, Govindanarayanan; Nakkeeran, Rangaswamy

    2018-04-01

    Unidirectional base station antenna design using Magneto-Electric Dipole (MED) has created enormous interest among the researchers due to its excellent radiation characteristics like low back radiation, symmetrical radiation at E-plane and H-plane compared to conventional patch antenna. Generally, dual polarized antennas are used to increase channel capacity and reliability of the communication systems. In order to serve the evolving mobile communication standards like long term evolution LTE and beyond, unidirectional dual polarized MED antenna are required to have broad impedance bandwidth, broad half power beamwidth, high port isolation, low cross polarization level, high front to back ratio and high gain. In this paper, the critical electrical requirements of the base station antenna and frequently used frequency bands for modern mobile communication have been presented. It is followed by brief review on broadband patch antenna and discussion on complementary antenna concepts. Finally, the performance of linearly polarized and dual polarized magneto-electric dipole antennas along with their feeding techniques are discussed and summarized. Also, design and modeling of developed MED antenna is presented.

  18. Rate of generation of tritium during the operation of Tsuruga Power Station Unit No. 2

    International Nuclear Information System (INIS)

    Funamoto, Hisao; Yoshinari, Masaharu; Fukuda, Masayuki; Makino, Shinichi; Watari, Tuneo

    1994-01-01

    Total amount of 3 H activity in primary coolant due to the operation of Tsuruga Power Station Unit No. 2 was estimated. The 3 H inventory was measured for samples from the spent fuel pool, primary coolant and miscellaneous tanks. From the result of the measurement and the data of environmental release of 3 H, the rate of generation of 3 H in the reactor was found to be 25 TBq/GWa. Since Tsuruga Power Station Unit No. 2 is a PWR type reactor, we presume that most of the 3 H in primary coolant is formed by 10 B(n, 2α) 3 H reaction. It is necessary to release about 23 TBq/GWa of 3 H to maintain the station inventory at the present level. (author)

  19. Fast Demand Forecast of Electric Vehicle Charging Stations for Cell Phone Application

    Energy Technology Data Exchange (ETDEWEB)

    Majidpour, Mostafa; Qiu, Charlie; Chung, Ching-Yen; Chu, Peter; Gadh, Rajit; Pota, Hemanshu R.

    2014-07-31

    This paper describes the core cellphone application algorithm which has been implemented for the prediction of energy consumption at Electric Vehicle (EV) Charging Stations at UCLA. For this interactive user application, the total time of accessing database, processing the data and making the prediction, needs to be within a few seconds. We analyze four relatively fast Machine Learning based time series prediction algorithms for our prediction engine: Historical Average, kNearest Neighbor, Weighted k-Nearest Neighbor, and Lazy Learning. The Nearest Neighbor algorithm (k Nearest Neighbor with k=1) shows better performance and is selected to be the prediction algorithm implemented for the cellphone application. Two applications have been designed on top of the prediction algorithm: one predicts the expected available energy at the station and the other one predicts the expected charging finishing time. The total time, including accessing the database, data processing, and prediction is about one second for both applications.

  20. Engineering of electrical systems of nuclear power stations for improved reliability

    International Nuclear Information System (INIS)

    Narasinga Rao, S.N.; Ramanathan, K.; Choudhary, N.N.

    1977-01-01

    Operational problems experienced in electrical systems/equipment of the Tarapur Atomic Power Station (TAPS) and the Rajasthan Atomic Power Station (RAPS) and their solutions are dealt in detail. This experience has led to new design concepts which are being introduced for improved reliability in design of the Madras Atomic Power Project (MAPP) and the Narora Atomic Power Project (NAPP). Saline pollution on switchyard equipments was the major problem of the TAPS due to its coastal location. Saline pollution resulted in flash over of insulators and failure of clamps. The problem was solved by suitable changes in insulators, conductors, transformers, switches and arranging portable live line washing of the switchyard equipment. In MAPP which is also located on coast, an indoor switchyard is built. NAPP is located in a seismic zone, therefore, all equipment is specified for appropriate seismic duty. Various other improvements are described. (M.G.B.)

  1. In core reload design for cycle 4 of Daya Bay nuclear power station both units

    International Nuclear Information System (INIS)

    Zhang Zongyao; Liu Xudong; Xian Chunyu; Li Dongsheng; Zhang Hong; Liu Changwen; Rui Min; Wang Yingming; Zhao Ke; Zhang Hong; Xiao Min

    1998-01-01

    The basic principles and the contents of the reload design for Daya Bay nuclear power station are briefly introduced. The in core reload design results, and the comparison between the calculated values and the measured values of both units the fourth cycle are also given. The reload design results of the two units satisfy all the economic requirements and safety criteria. The experimented results shown that the predicated values are tally good with all the measurement values

  2. Levels of electric field strength within the immediate vicinity of FM radio stations in Accra, Ghana.

    Science.gov (United States)

    Azah, C K; Amoako, J K; Fletcher, J J

    2013-10-01

    Heightened awareness of the ever-expanding use of radiofrequency (RF) techniques and technology has led to mounting concerns from the general public and the scientific community regarding the possible health effects that may arise as a consequence of exposure to RF radiations and has drawn the attention of many researchers the world over. A survey of the RF electromagnetic radiation at public access points in the vicinity of 20 frequency-modulated (FM) radio stations has been made in Accra, Ghana. The fundamental object was to determine the levels of RF fields from FM broadcast antennae within 10-200 m radius about the foot of the FM base station and at a height of 1.5 m above the ground at selected locations. A spectrum analyser and a bi-conical antenna element sensitive and effective within the frequency band of 30-300 MHz were used. Results obtained indicated that the levels of electric field strength ranged from 5.4E-04 V m(-1) at FM station 'O' to 7.4E-08 V m(-1) at FM station 'D'. At a transmission frequency range of 88-108 MHz, the variation of power densities is from 2.5E-10 to 1.5E-17 Wm(-2). These values are very low and are far below the reference level set by the International Commission on Non-Ionizing Radiation Protection and therefore do not pose any known hazard to the inhabitants of Accra, Ghana. The electric field levels presented in this work are comparable with those reported from epidemiological studies conducted elsewhere.

  3. Technical specifications: Seabrook Station, Unit 1 (Docket No. 50-443)

    International Nuclear Information System (INIS)

    1990-03-01

    The Seabrook Station, Unit 1 Technical Specifications were prepared by the US Nuclear Regulatory Commission to set forth the limits, operating conditions, and other requirements applicable to a nuclear reactor facility as set forth in Section 50.36 of 10 CFR Part 50 for the protection of the health and safety of the public

  4. Oconee Nuclear Station, Units 1, 2, and 3. Semiannual operating report, January--June 1975

    International Nuclear Information System (INIS)

    1975-01-01

    Information is presented concerning operations, performance characteristics, changes, tests, inspections, containment leak tests, maintenance, primary coolant chemistry, station staff changes, reservoir investigations, plume mapping, and operational environmental radioactivity monitoring data for oconee Units 1, 2, and 3. The non-radiological environmental surveillance program is also described. (FS)

  5. 77 FR 59679 - Central Vermont Public Service Corporation (Millstone Power Station, Unit 3); Order Approving...

    Science.gov (United States)

    2012-09-28

    ... NUCLEAR REGULATORY COMMISSION [NRC-2012-0044; Docket No. 50-423] Central Vermont Public Service Corporation (Millstone Power Station, Unit 3); Order Approving Application Regarding Corporate Restructuring and Conforming Amendment I Dominion Nuclear Connecticut, Inc. (DNC), Central Vermont Public Service...

  6. Envisioning a renewable electricity future for the United States

    International Nuclear Information System (INIS)

    Mai, Trieu; Mulcahy, David; Hand, M. Maureen; Baldwin, Samuel F.

    2014-01-01

    This paper presents high renewable electricity penetration scenarios in the United States using detailed capacity expansion modeling that is designed to properly account for the variability and uncertainty of wind and solar resources. The scenarios focus solely on the electricity system, an important sector within the larger energy sector, and demonstrate long-term visions of a U.S. power system where renewable technologies, including biomass, geothermal, hydropower, solar, and wind, contribute 80% of 2050 annual electricity, including 49–55% from wind and solar photovoltaic generation. We present the integration challenges of achieving this high penetration and characterize the options to increase grid flexibility to manage variability. Four high renewable pathways are modeled and demonstrate the robustness and diversity of renewable options. We estimate 69–82% annual greenhouse gas emission reductions and 3%–30% incremental electricity price increases associated with reaching 80%-by-2050 renewable electricity relative to reference scenarios. This paper affirms and strengthens similar analysis from the Renewable Electricity Futures study by using an improved model and updated data to better reflect investment and dispatch decisions under current outlooks for the U.S. electricity sector. - Highlights: • We model high renewable electricity scenarios for the U.S. electricity sector. • The mix of technologies will depend on future costs and system conditions. • Integration challenges and flexibility options are presented. • We estimate an incremental electricity price increase of 3–30% to achieve 80% RE (renewable electricity). • We estimate 69–82% reduction in annual carbon emissions with 80% RE

  7. Quad-Cities Station, Units 1 and 2. Annual report, 1975

    International Nuclear Information System (INIS)

    1976-01-01

    Net electrical power generated by Unit 1 was 2,246,757 MWh(e) with the generator on line 4,287.5 hrs while Unit 2 generated 1,729,147 MWh(e) with the generator on line 3,056.21 hrs. Information is presented concerning operations, power generation, shutdowns, maintenance, changes, tests, and experiments

  8. Quad-Cities Station, Units 1 and 2. Annual operating report for 1976

    International Nuclear Information System (INIS)

    1976-01-01

    Net electrical power generated by Unit 1 was 3,393,062 MWH with the generator on line 5,703.0 hrs. Unit 2 generated 4,304,684 MWH with the generator on line 7,145.3 hrs. Information is presented concerning modifications, maintenance, power generation, shutdowns, occupational radiation exposures, and organization

  9. Power transmission cable development for the Space Station Freedom electrical power system

    Science.gov (United States)

    Schmitz, Gregory V.; Biess, John J.

    1989-01-01

    Power transmission cable is presently being evaluated under a NASA Lewis Research Center advanced development contract for application in the Space Station Freedom (SSF) electrical power system (EPS). Evaluation testing has been performed by TRW and NASA Lewis Research Center. The results of this development contract are presented. The primary cable design goals are to provide (1) a low characteristic inductance to minimize line voltage drop at 20 kHz, (2) electromagnetic compatibility control of the 20-kHz ac power current, (3) a physical configuration that minimizes ac resistance and (4) release of trapped air for corona-free operation.

  10. CLIMATE CHANGE FUEL CELL PROGRAM UNITED STATES COAST GUARD AIR STATION CAPE COD BOURNE, MASSACHUSETTS

    Energy Technology Data Exchange (ETDEWEB)

    John K. Steckel Jr

    2004-06-30

    This report covers the first year of operation of a fuel cell power plant, installed by PPL Spectrum, Inc. (PPL) under contract with the United States Coast Guard (USCG), Research and Development Center (RDC). The fuel cell was installed at Air Station Cape Cod in Bourne, MA. The project had the support of the Massachusetts Technology Collaborative (MTC), the Department of Energy (DOE), and Keyspan Energy. PPL selected FuelCell Energy, Inc. (FCE) and its fuel cell model DFC{reg_sign}300 for the contract. Grant contributions were finalized and a contract between PPL and the USCG for the manufacture, installation, and first year's maintenance of the fuel cell was executed on September 24, 2001. As the prime contractor, PPL was responsible for all facets of the project. All the work was completed by PPL through various subcontracts, including the primary subcontract with FCE for the manufacture, delivery, and installation of the fuel cell. The manufacturing and design phases proceeded in a relatively timely manner for the first half of the project. However, during latter stages of manufacture and fuel cell testing, a variety of issues were encountered that ultimately resulted in several delivery delays, and a number of contract modifications. Final installation and field testing was completed in April and May 2003. Final acceptance of the fuel cell was completed on May 16, 2003. The fuel cell has operated successfully for more than one year. The unit achieved an availability rate of 96%, which exceeded expectations. The capacity factor was limited because the unit was set at 155 kW (versus a nameplate of 250 kW) due to the interconnection with the electric utility. There were 18 shutdowns during the first year and most were brief. The ability of this plant to operate in the island mode improved availability by 3 to 4%. Events that would normally be shutdowns were simply island mode events. The mean time between failure was calculated at 239 hours, or slightly

  11. Peach Bottom Atomic Power Station, Units 2 and 3. Annual operating report: January--December 1976

    International Nuclear Information System (INIS)

    1977-01-01

    Unit 2 experienced 11 forced outages, 5 power reductions, and one major refueling outage which lasted about 3 months during which time the feedwater spargers were replaced. Net electrical power generated was 5,569,633 MWH with the generator on line 5,998 hrs. Unit 3 experienced 17 forced outages, 11 power reductions and 2 major outages. The first refueling outage began 12/24/77. Net electrical power generated was 6,049,644 MWH with the unit on line 6,829 hrs. Information is presented concerning operations, personnel exposures, radioactive releases, maintenance, and irradiated fuel examination

  12. Inversion of Multi-Station Schumann Resonance Background Records for Global Lightning Activity in Absolute Units

    Science.gov (United States)

    Williams, E. R.; Mushtak, V. C.; Guha, A.; Boldi, R. A.; Bor, J.; Nagy, T.; Satori, G.; Sinha, A. K.; Rawat, R.; Hobara, Y.; Sato, M.; Takahashi, Y.; Price, C. G.; Neska, M.; Alexander, K.; Yampolski, Y.; Moore, R. C.; Mitchell, M. F.; Fraser-Smith, A. C.

    2014-12-01

    Every lightning flash contributes energy to the TEM mode of the natural global waveguide that contains the Earth's Schumann resonances. The modest attenuation at ELF (0.1 dB/Mm) allows for the continuous monitoring of the global lightning with a small number of receiving stations worldwide. In this study, nine ELF receiving sites (in Antarctica (3 sites), Hungary, India, Japan, Poland, Spitsbergen and USA) are used to provide power spectra at 12-minute intervals in two absolutely calibrated magnetic fields and occasionally, one electric field, with up to five resonance modes each. The observables are the extracted modal parameters (peak intensity, peak frequency and Q-factor) for each spectrum. The unknown quantities are the geographical locations of three continental lightning 'chimneys' and their lightning source strengths in absolute units (C2 km2/sec). The unknowns are calculated from the observables by the iterative inversion of an evolving 'sensitivity matrix' whose elements are the partial derivatives of each observable for all receiving sites with respect to each unknown quantity. The propagation model includes the important day-night asymmetry of the natural waveguide. To overcome the problem of multiple minima (common in inversion problems of this kind), location information from the World Wide Lightning Location Network has been used to make initial guess solutions based on centroids of stroke locations in each chimney. Results for five consecutive days in 2009 (Jan 7-11) show UT variations with the African chimney dominating on four of five days, and America dominating on the fifth day. The amplitude variations in absolute source strength exceed that of the 'Carnegie curve' of the DC global circuit by roughly twofold. Day-to-day variations in chimney source strength are of the order of tens of percent. Examination of forward calculations performed with the global inversion solution often show good agreement with the observed diurnal variations at

  13. Heuristic Storage System Sizing for Optimal Operation of Electric Vehicles Powered by Photovoltaic Charging Station

    Directory of Open Access Journals (Sweden)

    Erik Blasius

    2016-01-01

    Full Text Available This paper discusses the utilisation of PV systems for electric vehicles charging for transportation requirements of smart cities. The gap between PV power output and vehicles charging demand is highly variable. Therefore, there is a need for additional support from a public distribution grid or a storage device in order to handle the residual power. Long term measurement data retrieved from a charging station for 15 vehicles equipped with a PV system were used in the research. Low and high irradiation seasons influenced the PV output. The charging demand of electric vehicles varied over the course of a year and was correlated to weather conditions. Therefore, the sizing and performance of a supportive storage device should be evaluated in a statistical manner using long period observations.

  14. Distributed Cooperative Control of Multi Flywheel Energy Storage System for Electrical Vehicle Fast Charging Stations

    DEFF Research Database (Denmark)

    Sun, Bo; Dragicevic, Tomislav; Quintero, Juan Carlos Vasquez

    2015-01-01

    Plug-in electrical vehicles will play a critical role in future smart grid and sudden connection of electrical vehicles chargers may cause huge power-peaks with high slew-rates on grid. In order to cope with this issue, this paper applies a distributed cooperative control for fast charging station...... with dedicated paralleled flywheel-based energy storage system. The distributed DC-bus signaling method is employed in the power coordination of grid and flywheel converters, and a distributed secondary controller generates DC voltage correction term to adjust the local voltage set-point through a dynamic...... consensus based voltage observer by communicating with its neighbors. The control system can realize the power balancing and DC voltage regulation with low reliance on communications. Finally, real-time hardware-in-the-loop results have been reported in order to verify the feasibility of proposed approach....

  15. Reconfigurable Magneto-Electric Dipole Antennas for Base Stations in Modern Wireless Communication Systems

    Directory of Open Access Journals (Sweden)

    Lei Ge

    2018-01-01

    Full Text Available Magneto-electric (ME dipole antennas, with the function of changing the antenna characteristics, such as frequency, polarization, or radiation patterns, are reviewed in this paper. The reconfigurability is achieved by electrically altering the states of diodes or varactors to change the surface currents distributions or reflector size of the antenna. The purpose of the designs is to obtain agile antenna characteristics together with good directive radiation performances, such as low cross-polarization level, high front-to-back ratio, and stable gain. By reconfiguring the antenna capability to support more than one wireless frequency standard, switchable polarizations, or cover tunable areas, the reconfigurable ME dipole antennas are able to switch functionality as the mission changes. Therefore, it can help increase the communication efficiency and reduce the construction cost. This shows very attractive features in base station antennas of modern wireless communication applications.

  16. Dresden Nuclear Power Station, Units 1, 2, and 3. Annual operating report: January thru December 1976

    International Nuclear Information System (INIS)

    1977-01-01

    Net electrical energy generated by Unit 1 was 953,015.5 MWH with the generator on line 7,399.37 hrs. Unit 2 generated 4,371,553.689 MWH with the generator on line 6,664.58 hrs while Unit 3 generated 4,034,251 MWH with the generator on line 7,234.86 hrs. Information is presented concerning operations, maintenance, and shutdowns

  17. Environmental management at the Grand Rapids Generating Station following the Unit No.1 headcover failure

    International Nuclear Information System (INIS)

    Windsor, D.C.

    1993-01-01

    Failure of the headcover of Unit 1 in the Grand Rapids generating station in March, 1992 caused the station to flood, releasing several thousand gallons of oil and removing the station from service for several weeks. Environmental considerations were a considerable part of the station restoration activities, reservoir and flow management programs and responses to public concerns arising from the accident. A major oil spill containment and cleanup program was undertaken, with station cleanup and debris disposal carried out in a manner acceptable to environmental authorities. Reservoir spillage was necessitated by the station shutdown. The spill recreated fish habitat in the spillway and walleye spawning were documented. A compensation program was developed to respond to problems caused by debris flushed from the spillway channel. On spill termination, a fish salvage program removed fish from a scour hole in the spillway channel. A proactive program of public information provided local residents with the facts about the incident and response program, and allayed concerns about public safety. 4 refs., 2 figs

  18. Corrective Action Plan for Corrective Action Unit 490: Station 44 Burn Area, Tonopah Test Range, Nevada

    Energy Technology Data Exchange (ETDEWEB)

    K. B. Campbell

    2002-04-01

    Corrective Action Unit (CAU) 490, Station 44 Burn Area is located on the Tonopah Test Range (TTR). CAU 490 is listed in the Federal Facility Agreement and Consent Order (FFACO, 1996) and includes for Corrective Action Sites (CASs): (1) Fire Training Area (CAS 03-56-001-03BA); (2) Station 44 Burn Area (CAS RG-56-001-RGBA); (3) Sandia Service Yard (CAS 03-58-001-03FN); and (4) Gun Propellant Burn Area (CAS 09-54-001-09L2).

  19. Lessons learned while implementing a safety parameter display system at the Comanche Peak steam electric station

    International Nuclear Information System (INIS)

    Hagar, B.

    1987-01-01

    With the completion of site Verification and Validation tests, the Safety Parameter Display System (SPDS) will be fully operational at the Comanche Peak Steam Electric Station. Implementation of the SPDS, which began in 1982, included: modifying generic Safety Assessment System Software; developing site-specific displays and features; installing and integrating system equipment into the plant; modifying station heating, ventilation, and air conditioning systems to provide necessary cooling; installing an additional uninterruptible power supply system to provide necessary power; and training station personnel in the operation and use of the system. Lessons learned during this project can be discussed in terms of an ideal SPDS implementation project. Such a project would design and implement an SPDS for a plant that is already under construction or operating, and would progress through a sequence of activities that includes: (1) developing and documenting the system design bases, and including all major design influences; (2) developing a database description and system functional specifications to clarify specific system requirements; (3) developing detailed system hardware and software design specifications to fully describe the system, and to enable identification of necessary site design changes early in the project; (4) implementing the system design; (5) configuring and extensively testing the system prior to routine system operation; and (6) tuning the system after the completion of system installation. The ideal project would include future system users in design development and system testing, and would use Verification and Validation techniques throughout the project to ensure that each sequential step is appropriate and correct

  20. Modeling of a Photovoltaic-Powered Electric Vehicle Charging Station with Vehicle-to-Grid Implementation

    Directory of Open Access Journals (Sweden)

    Azhar Ul-Haq

    2016-12-01

    Full Text Available This paper is aimed at modelling of a distinct smart charging station for electric vehicles (EVs that is suitable for DC quick EV charging while ensuring minimum stress on the power grid. Operation of the charging station is managed in such a way that it is either supplied by photovoltaic (PV power or the power grid, and the vehicle-to-grid (V2G is also implemented for improving the stability of the grid during peak load hours. The PV interfaced DC/DC converter and grid interfaced DC/AC bidirectional converter share a DC bus. A smooth transition of one operating mode to another demonstrates the effectiveness of the employed control strategy. Modelling and control of the different components are explained and are implemented in Simulink. Simulations illustrate the feasible behaviour of the charging station under all operating modes in terms of the four-way interaction among PV, EVs and the grid along with V2G operation. Additionally, a business model is discussed with comprehensive analysis of cost estimation for the deployment of charging facilities in a residential area. It has been recognized that EVs bring new opportunities in terms of providing regulation services and consumption flexibility by varying the recharging power at a certain time instant. The paper also discusses the potential financial incentives required to inspire EV owners for active participation in the demand response mechanism.

  1. Optimal recharging strategy for battery-switch stations for electric vehicles in France

    International Nuclear Information System (INIS)

    Armstrong, M.; El Hajj Moussa, C.; Adnot, J.; Galli, A.; Riviere, P.

    2013-01-01

    Most papers that study the recharging of electric vehicles focus on charging the batteries at home and at the work-place. The alternative is for owners to exchange the battery at a specially equipped battery switch station (BSS). This paper studies strategies for the BSS to buy and sell the electricity through the day-ahead market. We determine what the optimal strategies would have been for a large fleet of EVs in 2010 and 2011, for the V2G and the G2V cases. These give the amount that the BSS should offer to buy or sell each hour of the day. Given the size of the fleet, the quantities of electricity bought and sold will displace the market equilibrium. Using the aggregate offers to buy and the bids to sell on the day-ahead market, we compute what the new prices and volumes transacted would be. While buying electricity for the G2V case incurs a cost, it would have been possible to generate revenue in the V2G case, if the arrivals of the EVs had been evenly spaced during the day. Finally, we compare the total cost of implementing the strategies with the cost of buying the same quantity of electricity from EDF. - Highlights: • Optimal strategies for buying/selling electricity through day-ahead auction market. • Given fleet size power bought and sold would change market price and volume. • New prices computed using aggregate offers to buy/sell power in 2010 and 2011. • Timing of arrival of EVs critical in V2G case. If evenly spaced BSS makes money. • Strategies are very robust even when French and German markets were coupled Nov. 2010

  2. Reliability measurement for mixed mode failures of 33/11 kilovolt electric power distribution stations.

    Directory of Open Access Journals (Sweden)

    Faris M Alwan

    Full Text Available The reliability of the electrical distribution system is a contemporary research field due to diverse applications of electricity in everyday life and diverse industries. However a few research papers exist in literature. This paper proposes a methodology for assessing the reliability of 33/11 Kilovolt high-power stations based on average time between failures. The objective of this paper is to find the optimal fit for the failure data via time between failures. We determine the parameter estimation for all components of the station. We also estimate the reliability value of each component and the reliability value of the system as a whole. The best fitting distribution for the time between failures is a three parameter Dagum distribution with a scale parameter [Formula: see text] and shape parameters [Formula: see text] and [Formula: see text]. Our analysis reveals that the reliability value decreased by 38.2% in each 30 days. We believe that the current paper is the first to address this issue and its analysis. Thus, the results obtained in this research reflect its originality. We also suggest the practicality of using these results for power systems for both the maintenance of power systems models and preventive maintenance models.

  3. Motor unit recruitment during neuromuscular electrical stimulation: a critical appraisal.

    Science.gov (United States)

    Bickel, C Scott; Gregory, Chris M; Dean, Jesse C

    2011-10-01

    Neuromuscular electrical stimulation (NMES) is commonly used in clinical settings to activate skeletal muscle in an effort to mimic voluntary contractions and enhance the rehabilitation of human skeletal muscles. It is also used as a tool in research to assess muscle performance and/or neuromuscular activation levels. However, there are fundamental differences between voluntary- and artificial-activation of motor units that need to be appreciated before NMES protocol design can be most effective. The unique effects of NMES have been attributed to several mechanisms, most notably, a reversal of the voluntary recruitment pattern that is known to occur during voluntary muscle contractions. This review outlines the assertion that electrical stimulation recruits motor units in a nonselective, spatially fixed, and temporally synchronous pattern. Additionally, it synthesizes the evidence that supports the contention that this recruitment pattern contributes to increased muscle fatigue when compared with voluntary actions and provides some commentary on the parameters of electrical stimulation as well as emerging technologies being developed to facilitate NMES implementation. A greater understanding of how electrical stimulation recruits motor units, as well as the benefits and limitations of its use, is highly relevant when using this tool for testing and training in rehabilitation, exercise, and/or research.

  4. 76 FR 72007 - ZionSolutions, LLC; Zion Nuclear Power Station, Units 1 and 2; Exemption From Certain Security...

    Science.gov (United States)

    2011-11-21

    ... NUCLEAR REGULATORY COMMISSION [Docket Nos. 50-295 and 50-304; NRC-2011-0244] ZionSolutions, LLC; Zion Nuclear Power Station, Units 1 and 2; Exemption From Certain Security Requirements 1.0 Background Zion Nuclear Power Station (ZNPS or Zion), Unit 1, is a Westinghouse 3250 MWt Pressurized Water Reactor...

  5. 75 FR 15745 - Arizona Public Service Company, et al. Palo Verde Nuclear Generating Station, Units 1, 2, and 3...

    Science.gov (United States)

    2010-03-30

    ...] Arizona Public Service Company, et al. Palo Verde Nuclear Generating Station, Units 1, 2, and 3; Exemption 1.0 Background The Arizona Public Service Company (APS, the licensee) is the holder of Facility... Generating Station (PVNGS), Units 1, 2, and 3, respectively. The licenses provide, among other things, that...

  6. 75 FR 8149 - Arizona Public Service Company, et al. Palo Verde Nuclear Generating Station, Units 1, 2, and 3...

    Science.gov (United States)

    2010-02-23

    ...] Arizona Public Service Company, et al. Palo Verde Nuclear Generating Station, Units 1, 2, and 3... NPF-74, issued to the Arizona Public Service Company (APS, or the licensee), for operation of the Palo Verde Nuclear Generating Station (PVNGS, the facility), Units 1, 2, and 3, respectively, located in...

  7. 75 FR 43572 - Duke Energy Carolinas, LLC, McGuire Nuclear Station, Units 1 and 2; Environmental Assessment and...

    Science.gov (United States)

    2010-07-26

    ... NUCLEAR REGULATORY COMMISSION [Docket Nos. 50-369 and 50-370; NRC-2010-0259] Duke Energy Carolinas, LLC, McGuire Nuclear Station, Units 1 and 2; Environmental Assessment and Finding of No Significant... Energy Carolinas, LLC (the licensee), for operation of the McGuire Nuclear Station, Units 1 and 2...

  8. 75 FR 43571 - Duke Energy Carolinas, LLC; Catawba Nuclear Station, Units 1 and 2; Environmental Assessment And...

    Science.gov (United States)

    2010-07-26

    ... NUCLEAR REGULATORY COMMISSION [Docket Nos. 50-413 and 50-414; NRC-2010-0260] Duke Energy Carolinas, LLC; Catawba Nuclear Station, Units 1 and 2; Environmental Assessment And Finding of No Significant... Energy Carolinas, LLC (the licensee), for operation of the Catawba Nuclear Station, Units 1 and 2...

  9. IEEE Std 317-1972: IEEE standard for electric penetration assemblies in containment structures for nuclear power generating stations

    International Nuclear Information System (INIS)

    Anon.

    1992-01-01

    This standard prescribes the mechanical, electrical, and test requirements for the design, construction, and installation of electric penetration assemblies in containment structures for stationary nuclear power generating stations. The electric conductor and insulation characteristics of external circuits which connect to penetration assemblies are beyond the scope of these criteria. If there should be any conflict between this standard and those documents referenced herein, this standard shall take precedence over the referenced documents

  10. Feasibility assessment of a solar-powered charging station for electric vehicles in the North Central region of Bulgaria

    Directory of Open Access Journals (Sweden)

    Ilieva Liliya Mihaylova

    2016-01-01

    Full Text Available The paper discusses the topical issue related to the prospects of widespread deployment of electric vehicles and their associated infrastructure in Bulgaria. The main problems hindering the development of electric vehicle transport are summarized and the current status of charging infrastructure in the country is discussed. An approach is proposed for analysis and evaluation of the financial feasibility of investment in a solar-powered charging station for electric vehicles in North Central region of Bulgaria.

  11. Marble Hill Nuclear Generating Station, Units 1 and 2. License application, PSAR, general information

    International Nuclear Information System (INIS)

    1975-01-01

    An application is presented for two PWR reactors to be constructed in Salud Township, Jefferson County, Indiana, about six miles northeast of New Washington on the Ohio River. Each unit will have a rated core power level of 3411 MW(t) with a corresponding electrical output of 1130 MW(e). Mechanical draft cooling towers will be provided. The facility, which will replicate the Byron facility will be employed for the generation of electricity for transmission, sale for resale, and distribution

  12. Indian Point Station, Units 1, 2, and 3. Annual operating report for 1976

    International Nuclear Information System (INIS)

    1977-01-01

    Unit 1 remained in a shutdown condition pending a decision by the Company on the installation of an ECCS as required by NRC. Net electrical power generated by Unit 2 was 2,267,654 MWH with the unit on line 3,056.45 hrs. Unit 3 generated 1,872,947 MWH and was on line 2,286.01 hrs. Information is presented concerning operations, reportable events, corrective maintenance, fuel performance, radioactivity releases, shutdowns, primary coolant chemistry, and occupational radiation exposures

  13. Corrective action decision document, Second Gas Station, Tonopah test range, Nevada (Corrective Action Unit No. 403)

    International Nuclear Information System (INIS)

    1997-11-01

    This Corrective Action Decision Document (CADD) for Second Gas Station (Corrective Action Unit [CAU] No. 403) has been developed for the U.S. Department of Energy's (DOE) Nevada Environmental Restoration Project to meet the requirements of the Federal Facility Agreement and Consent Order (FFACO) of 1996 as stated in Appendix VI, open-quotes Corrective Action Strategyclose quotes (FFACO, 1996). The Second Gas Station Corrective Action Site (CAS) No. 03-02-004-0360 is the only CAS in CAU No. 403. The Second Gas Station CAS is located within Area 3 of the Tonopah Test Range (TTR), west of the Main Road at the location of former Underground Storage Tanks (USTs) and their associated fuel dispensary stations. The TTR is approximately 225 kilometers (km) (140 miles [mi]) northwest of Las Vegas, Nevada, by air and approximately 56 km (35 mi) southeast of Tonopah, Nevada, by road. The TTR is bordered on the south, east, and west by the Nellis Air Force Range and on the north by sparsely populated public land administered by the Bureau of Land Management and the U.S. Forest Service. The Second Gas Station CAS was formerly known as the Underground Diesel Tank Site, Sandia Environmental Restoration Site Number 118. The gas station was in use from approximately 1965 to 1980. The USTs were originally thought to be located 11 meters (m) (36 feet [ft]) east of the Old Light Duty Shop, Building 0360, and consisted of one gasoline UST (southern tank) and one diesel UST (northern tank) (DOE/NV, 1996a). The two associated fuel dispensary stations were located northeast (diesel) and southeast (gasoline) of Building 0360 (CAU 423). Presently the site is used as a parking lot, Building 0360 is used for mechanical repairs of vehicles

  14. Outline of construction and facility features of Onagawa nuclear power station Unit No. 2

    International Nuclear Information System (INIS)

    Umimura, Yoshiharu; Tsunoda, Ryohei; Watanabe, Kazunori

    1996-01-01

    Tohoku Electric Power Company promotes development of various power sources to provide a stable supply of electricity in the future, and nuclear power takes a leading part. In August 1989, construction of Onagawa nuclear power plant Unit No. 2 (825MW) was started, following Unit No. 1 (524MW) which went on line in 1984 as Tohoku Electric's first nuclear power plant unit. Unit No. 2 began commercial operation in July 1995 through satisfactory construction work such as RPV hydraulic test in March 1994, fuel loading in October 1994, and various startup tests in each power stage. The design and construction of Unit No. 2 reflect construction and operation experience gained from Unit No. 1, and the latest technology, including that of the LWR Improvement and Standardization Program, was adopted to enhance facility reliability, improve operation and maintenance performance, and reduce worker dosage. Features of the facility, construction techniques, and a description of preoperation of Onagawa nuclear power plant Unit No. 2 are described in this paper. (author)

  15. Indian Point Station, Unit 1 and 2. Semiannual operating report No. 24, July--December 1974

    International Nuclear Information System (INIS)

    1975-01-01

    Net electrical power generated by Unit 1 was 519,130 MWH with the reactor critical for 2,400.39 hours and the generator on line for 2,316.14 hours. Unit 2 generated 2,427,828 MWH electrical power, was critical for 3,590.31 hours and the generator was on line for 3,485.41 hours. Operations and maintenance are summarized. Information is presented concerning radioactive effluent releases, occupational personnel radiation protection, primary coolant chemistry, changes, tests, and experiments. Environmental radioactivity is discussed. (U.S.)

  16. The competitive economics of a middle aged multi unit nuclear generating station

    International Nuclear Information System (INIS)

    Talbot, K.H.

    1994-01-01

    In 1992 Ontario Hydro's 15 year old 4 x 850 MWe Candu, Bruce A Nuclear Generating Station was predicted to need considerable capital investment to replace pressure tubes, steam generators and other prematurely ageing equipment in order to restore the station to high performance. Over the subsequent two years the station has undergone 2 major economic assessment studies which have confirmed the economic viability of continued operation of the plant. Declining demand for electricity in Ontario combined with a excess of generating capacity and a need to stabilise electricity rates have however forced significant operational cost reductions and reduced capital availability for rehabilitation work, it's medium and long term future remains in question. This presentation offers a practical illustration of the need to maintain steady high performance from nuclear generating plant via the appropriate life management techniques. The avoidance of mid life infusion of capital is considered as essential if nuclear generation is to successfully survive major changes in economic conditions. 2 tabs., 7 figs

  17. Status of electricity trading in the United States

    International Nuclear Information System (INIS)

    McMillan, P.H.

    1999-01-01

    The evolution of the energy marketplace in the United States is presented in a series of overhead viewgraphs. The influencing factors of energy trading are described as being supply concentration, rate cross subsidization, price volatility, physics, stranded investment, market structure and value drivers. A map depicting trading hubs and market structures is included, along with an outline of the key characteristics of a successful market hub. Gas-electric interface issues are also discussed. It was stated that contrary to conventional wisdom that as gas and electricity markets converge, traders will routinely cross-hedge gas and power, the practical reality is that volatility of the gas to electricity basis spread actually limits hedging opportunities. A winning strategy should include thorough fundamental and technical analysis; every trade or position should have a well thought-out exit strategy; get closer to physical assets; and be careful across regional hubs and commodities. 2 tabs., 7 figs

  18. Audit of Wolf Creek Generating Station, Unit 1 technical specifications. Final technical evaluation report

    International Nuclear Information System (INIS)

    Stromberg, H.M.

    1985-07-01

    This document was prepared for the Nuclear Regulatory Commission (NRC) to assist them in determining whether the Wolf Creek Generating Station Unit 1 Technical Specifications (T/S), which govern plant systems configurations and operations, are in conformance with the assumptions of the Final Safety Analysis Report (FSAR) as amended, the requirements of the Safety Evaluation Report (SER) as supplemented, and the Comments and Responses to the Wolf Creek Technical Specification Draft Inspection Report. A comparative audit of the FSAR as amended, the SER as supplemented, and the Draft Inspection Report was performed with the Wolf Creek T/S. Several discrepancies were identified and subsequently resolved through discussions with the cognizant NRC reviewer, NRC staff reviewers and/or utility representatives. The Wolf Creek Generating Station Unit 1 T/S, to the extent reviewed, are in conformance with the FSAR, SER, and Draft Inspection Report

  19. Geothermal electric power generation in Iceland for the proposed Iceland/United Kingdom HVDC power link

    International Nuclear Information System (INIS)

    Hammons, T.J.; Palmason, G.; Thorhallsson, S.

    1991-01-01

    The paper reviews geothermal electric power potential in Iceland which could economically be developed to supplement hydro power for the proposed HVDC Power Link to the United Kingdom, and power intensive industries in Iceland, which are envisaged for development at this time. Technically harnessable energy for electricity generation taking account of geothermal resources down to an assumed base depth, temperature distribution in the crust, probable geothermal recovery factor, and accessibility of the field, has been assessed. Nineteen known high-temperature fields and 9 probable fields have been identified. Technically harnessable geo-heat for various areas is indicated. Data on high temperature fields suitable for geothermal electric power generation, and on harnessable energy for electric power generation within volcanic zones, is stated, and overall assessments are made. The paper then reviews how the potential might be developed, discussing preference of possible sites, and cost of the developments at todays prices. Cost of geothermal electric power generation with comparative costs for hydro generation are given. Possible transmission system developments to feed the power to the proposed HVDC Link converter stations are also discussed

  20. Retrofit flue gas desulfurization system at Indianapolis Power and Light Co. Petersburg Station Units 1 and 2

    International Nuclear Information System (INIS)

    Watson, W.K.; Wolsiffer, S.R.; Youmans, J.; Martin, J.E.; Wedig, C.P.

    1992-01-01

    This paper briefly describes the status of the retrofit wet limestone flue gas desulfurization system (FGDS) project at Indianapolis Power and Light Company (IPL), Petersburg Units 1 and 2. This project was initiated by IPL in response to the Clean Air Act of 1990 and is intended to treat the flue gas from two base load units with a combined capacity of approximately 700 MW gross electrical output. IPL is the owner and operator of the Petersburg Station located in southwestern Indiana. Stone and Webster Engineering Corporation (Stone and Webster) is the Engineer and Constructor for the project. Radian Corporation is a subcontractor to Stone and Webster in the area of flue gas desulfurization (FGD) process. General Electric Environmental Systems, Inc. (GEESI) is the supplier of the FGDS. The project is organized as a team with each company providing services. The supplier of the new stack is scheduled to be selected and join the team in early 1992. Other material suppliers and field contractors will be selected in 1992

  1. The expected environmental consequences and hazards of laser-fusion electric generating stations

    International Nuclear Information System (INIS)

    Devaney, J.J.; Pendergrass, J.H.

    The operation of an expected early form of a laser-fusion electric power plant is described and the hazards and the environmental effects of such a station are estimated. Possible environmental impacts and hazards to mankind can occur from nuclear excursions or explosions, nuclear weapon proliferation, loss of coolant accident (LOCA), tritium releases, chemical fires and accompanying releases of radioactivity or chemicals, induced radioactivity releases (other than tritium), radioactive waste disposal, lasers, normal electrical generation and steam plant effects, external intrusions, natural disasters, land use, resource and transportation use, thermal pollution, and air and water pollution. We find the principle environmental effects to be those of a medium size chemical plant. Electric, magnetic, steam, and radioactive hazards are of a lower order. Indeed in the event of extraordinary success in getting high temperatures and densities so that more difficult nuclear species can be reacted, such as protons with boron-11, there will be no radioactivity at all and also enormously lower hazardous chemical inventories. In our plant designs, for any fusion fuels, nuclear explosions (or even excursions beyond design limits) are not possible. (author)

  2. Electrical stimulation of transplanted motoneurons improves motor unit formation

    Science.gov (United States)

    Liu, Yang; Grumbles, Robert M.

    2014-01-01

    Motoneurons die following spinal cord trauma and with neurological disease. Intact axons reinnervate nearby muscle fibers to compensate for the death of motoneurons, but when an entire motoneuron pool dies, there is complete denervation. To reduce denervation atrophy, we have reinnervated muscles in Fisher rats from local transplants of embryonic motoneurons in peripheral nerve. Since growth of axons from embryonic neurons is activity dependent, our aim was to test whether brief electrical stimulation of the neurons immediately after transplantation altered motor unit numbers and muscle properties 10 wk later. All surgical procedures and recordings were done in anesthetized animals. The muscle consequences of motoneuron death were mimicked by unilateral sciatic nerve section. One week later, 200,000 embryonic day 14 and 15 ventral spinal cord cells, purified for motoneurons, were injected into the tibial nerve 10–15 mm from the gastrocnemii muscles as the only neuron source for muscle reinnervation. The cells were stimulated immediately after transplantation for up to 1 h using protocols designed to examine differential effects due to pulse number, stimulation frequency, pattern, and duration. Electrical stimulation that included short rests and lasted for 1 h resulted in higher motor unit counts. Muscles with higher motor unit counts had more reinnervated fibers and were stronger. Denervated muscles had to be stimulated directly to evoke contractions. These results show that brief electrical stimulation of embryonic neurons, in vivo, has long-term effects on motor unit formation and muscle force. This muscle reinnervation provides the opportunity to use patterned electrical stimulation to produce functional movements. PMID:24848463

  3. United States/Mexico electricity exchanges. [History, incentives, and constraints

    Energy Technology Data Exchange (ETDEWEB)

    None,

    1980-05-01

    As a result of the agreement between the respective presidents, a joint study was undertaken to analyze the possibilities of increasing the international electricity exchange between the two countries. Responsibility for this undertaking was assigned to the United States Department of Energy (DOE) and to the Direccion de Energia de Mexico (DEM) through the Comision Federal de Electricidad (CFE). Representatives from Mexico and the US were chosen from the regional utilities along the border between the two countries and made up working groups that particiated in the study. With the support of both governments, and a high degree of cooperation between the two countries, work on the study was completed within fourteen months The completion of the study has been a major step in broadening the base of bilateral energy relations. the study highlights the opportunities for increased electricity exchanges, which could increase cooperation along the common border. Expansion of electricity interchange could offer substantial economic benefit to both countries, both directly and indirectly. Direct benefits include increased reliability of electric power and cost savings through economies of scale and diversity of peak demand patterns. Indirect benefits include improved economic and employment opportunities, especially in the border areas of both countries. This report provides background on the history of past exchanges and the characteristics of the US and Mexico electric systems, a summary of opportunities and incentives, and suggestions for procedures to remove obstacles and constraints.

  4. Technical Specifications, Byron Station, Unit Nos. 1 and 2 (Docket Nos. STN 50-454 and STN 50-455). Appendix A to license No. NPF-37

    International Nuclear Information System (INIS)

    1985-02-01

    The Byron Station, Unit No. 1 and Unit No. 2 Technical Specifications were prepared by the US Nuclear Regulatory Commission to set forth the limits, operating conditions, and other requirements applicable to a nuclear reactor facility as set forth in Section 50.36 of 10 CFR Part 50 for the protection of the health and safety of the public. Specifications are presented for limiting conditions for operation for the reactor control system, power distribution limits, instrumentation, primary coolant circuit, ECCS, containment systems, plant systems, electrical power systems, refueling operations, radioactive effluents, and radiological environmental monitoring

  5. International Space Station (ISS) Plasma Contactor Unit (PCU) Utilization Plan Assessment Update

    Science.gov (United States)

    Hernandez-Pellerano, Amri; Iannello, Christopher J.; Garrett, Henry B.; Ging, Andrew T.; Katz, Ira; Keith, R. Lloyd; Minow, Joseph I.; Willis, Emily M.; Schneider, Todd A.; Whittlesey, Edward J.; hide

    2014-01-01

    The International Space Station (ISS) vehicle undergoes spacecraft charging as it interacts with Earth's ionosphere and magnetic field. The interaction can result in a large potential difference developing between the ISS metal chassis and the local ionosphere plasma environment. If an astronaut conducting extravehicular activities (EVA) is exposed to the potential difference, then a possible electrical shock hazard arises. The control of this hazard was addressed by a number of documents within the ISS Program (ISSP) including Catastrophic Safety Hazard for Astronauts on EVA (ISS-EVA-312-4A_revE). The safety hazard identified the risk for an astronaut to experience an electrical shock in the event an arc was generated on an extravehicular mobility unit (EMU) surface. A catastrophic safety hazard, by the ISS requirements, necessitates mitigation by a two-fault tolerant system of hazard controls. Traditionally, the plasma contactor units (PCUs) on the ISS have been used to limit the charging and serve as a "ground strap" between the ISS structure and the surrounding ionospheric plasma. In 2009, a previous NASA Engineering and Safety Center (NESC) team evaluated the PCU utilization plan (NESC Request #07-054-E) with the objective to assess whether leaving PCUs off during non-EVA time periods presented risk to the ISS through assembly completion. For this study, in situ measurements of ISS charging, covering the installation of three of the four photovoltaic arrays, and laboratory testing results provided key data to underpin the assessment. The conclusion stated, "there appears to be no significant risk of damage to critical equipment nor excessive ISS thermal coating damage as a result of eliminating PCU operations during non- EVA times." In 2013, the ISSP was presented with recommendations from Boeing Space Environments for the "Conditional" Marginalization of Plasma Hazard. These recommendations include a plan that would keep the PCUs off during EVAs when the

  6. S.I. 1987 No. 2182, The Electricity Generating Stations and Overhead Lines (Inquiries Procedure) Rules 1987

    International Nuclear Information System (INIS)

    1987-01-01

    These Rules, which came into force on 14 January 1988, make new provision for the procedure for any public inquiry held pursuant to Section 34 of the Electricity Act 1957 in relation to applications for consent to construct or extend a generating station (including nuclear stations). The Rules were made pursuant to Section 11 of the Tribunals and Inquiries Act 1971. They revoke the previous Electricity Generating Stations and Overhead Line (Inquiries Procedures) Rules 1981. These new Rules cover the same topics as the previous Rules but aim to shorten the potential length and thus cost of inquiries. They will apply to the Inquiry to be held into the application by the Central Electricity Generating Board to build a pressurised water reactor at Hinkley Point in Somerset. (NEA) [fr

  7. Process for improving the load factor of an electricity generating power station

    International Nuclear Information System (INIS)

    Rostaing, Michel.

    1974-01-01

    A description is given of a process for improving the load factor of an electricity generating power station feeding a supply network in which all or part of the power not required by the network during off-peak hours is used for producing hydrogen which is then stored. The stored hydrogen is then burned and the heat generated is employed for superheating the steam generated by the nuclear reactor of the power plant. This combustion is carried out permanently. The hydrogen is produced by water electrolysis. The oxygen also produced in this manner is used as a comburent in the combustion of the hydrogen. The reactor is of the pressurized water type [fr

  8. Risk impact of planned maintenance configuration at South Texas Project Electric Generating Station

    International Nuclear Information System (INIS)

    Loh, W.T.; Fleming, K.N.; Grantom, C.R.

    2004-01-01

    This paper is based on a study done for the Houston Lighting and Power Company. The purpose of this study is to estimate the risk impact of planned maintenance configurations at South Texas Project Electric Generating Station (STPEGS). To date, the focus of the STP probabilistic safety assessment (PSA) program has been to analyze risk in terms of estimates of accident frequencies that are expressed on a time-averaged basis. Thus, estimates of quantities such as severe core damage frequency have been made such that the temporal variations of this frequency with changing plant configurations are averaged out over time. The only condition that has been imposed on these estimates is that the plant is initially operating at full power when potential initiating events might occur. (author)

  9. Elevated-constant pH control assessment at TXU's Comanche peak steam electric station

    International Nuclear Information System (INIS)

    Fellers, B.; Perkins, D.; Bosma, J.; Deshon, J.

    2002-01-01

    Industry experience with axial offset anomaly (AOA) has raised the importance of crud management strategies. Elevated-constant pH control is recognized as one potential solution. Additionally, minimizing radiation fields remains a high industry goal which is supported by this strategy. An investigation of industry experience and experimental data has supported a strategy of constant at-temperature pH of 7.4, requiring as much as 6-ppm lithium at the beginning-of-cycle (BOC). This approach, in a modern high temperature plant with high boron requirements, necessitated a careful assessment of potential risk for increased susceptibility to corrosion for both fuel cladding and RCS structural materials. This paper presents results of the assessment for Comanche peak steam electric station (CPSES) and plans for a demonstration of this practice. (author)

  10. The decommissioning of commercial magnox gas cooled reactor power stations in the United Kingdom

    International Nuclear Information System (INIS)

    Holt, G.

    1998-01-01

    There are nine commercial Magnox gas-cooled reactor power stations in the United Kingdom. Three of these stations have been shutdown and are being decommissioning, and plans have also been prepared for the eventual decommissioning of the remaining operational stations. The preferred strategy for the decommissioning of the Magnox power stations has been identified as 'Safestore' in which the decommissioning activities are carried out in a number of steps separated by quiescent periods of care and maintenance. The final clearance of the site could be deferred for up to 135 years following station shutdown so as to obtain maximum benefit from radioactive decay. The first step in the decommissioning strategy is to defuel the reactors and transport all spent and new fuel off the site. This work has been completed at all three shutdown stations. Decommissioning work is continuing on the three sites and has involved activities such as dismantling, decontamination, recycling and disposal of some plant and structures, and the preparation of others for retention on the site for a period of care and maintenance. Significant experience has been gained in the practical application of decommissioning, with successful technologies and processes being identified for a wide range of activities. For example, large and small metallic and concrete structures, some with complex geometries, have been successfully decontaminated. Also, the reactors have been prepared for a long period of care and maintenance, with instrumentation and sampling systems having been installed to monitor their continuing integrity. All of this work has been done under careful safety, technical, and financial control. (author)

  11. Service hall in Number 1 Fukushima Nuclear Power Station, Tokyo Electric Power Company, Inc

    International Nuclear Information System (INIS)

    Tawara, Shigesuke

    1979-01-01

    There are six BWR type nuclear power plants in the Number 1 Fukushima Nuclear Power Station, Tokyo Electric Power Company, Inc. The service hall of the station is located near the entrance of the station. In the center of this service hall, there is the model of a nuclear reactor of full scale. This mock-up shows the core region in the reactor pressure vessel for the number one plant. The diameter and the thickness of the pressure vessel are about 5 m and 16 cm, respectively. The fuel assemblies and control rods are set just like the actual reactor, and the start-up operation of the reactor is shown colorfully and dynamically by pushing a button. When the control rods are pulled out, the boiling of water is demonstrated. The 1/50 scale model of the sixth plant with the power generating capacity of 1100 MWe is set, and this model is linked to the mock-up of reactor written above. The operations of a recirculating loop, a turbine and a condenser are shown by switching on and off lamps. The other exhibitions are shielding concrete wall, ECCS model, and many kinds of panels and models. This service hall is incorporated in the course of study and observation of civics. The good environmental effects to fishes and shells are explained in this service hall. Official buildings and schools are built near the service hall utilizing the tax and grant concerning power generation. This service hall contributes to give much freedom from anxiety to the public by the tour. (Nakai, Y.)

  12. Interim report on the accident at Fukushima Nuclear Power Stations of Tokyo Electric Power Company

    International Nuclear Information System (INIS)

    2011-12-01

    The Investigation Committee on the Accident at the Fukushima Nuclear Power Stations (the Investigation Committee) of Tokyo Electric Power Company (TEPCO) was established by the Cabinet decision on May 24, 2011. Its objectives are: to conduct investigation for finding out the causes of accidents at the Fukushima Dai-ichi Nuclear Power Station (Fukushima Dai-ichi NPS) and Fukushima Dai-ni Nuclear Power Station (Fukushima Dai-ni NPS) of TEPCO as well as the causes of accident damage; and to make policy recommendations for limiting the expansion of damage and preventing reoccurrence of similar accidents. The Investigation Committee has conducted its investigation and evaluation since its first meeting on June 7, 2011. Its activities included: site visits to the Fukushima Dai-ichi and Dai-ni NPSs, as well as to other facilities; hearing of heads of local governments around the Fukushima Dai-ichi NPS; and hearing of people concerned through interviews mainly arranged by the Secretariat. As of December 16, 2011, the number of interviewees reached 456. The investigation and evaluation by the Investigation Committee are still ongoing and the Interim Report does not cover every item that the Committee aims at investigating and evaluating. Fact-finding of even some of those items discussed in the Interim Report are not yet completed. The Investigation Committee continues to conduct its investigation and evaluation and will issue its Final Report in the summer of 2012. This brief executive summary covers mainly considerations and evaluation of the issues in Chapter VII of the Interim Report, with brief reference to Chapters I to VI. The Investigation Committee recommendations are printed in bold. (author)

  13. On the complex analysis of the reliability, safety, and economic efficiency of atomic electric power stations

    International Nuclear Information System (INIS)

    Emel'yanov, I.Ya.; Klemin, A.I.; Polyakov, E.F.

    1977-01-01

    The problem is posed of effectively increasing the engineering performance of nuclear electric power stations (APS). The principal components of the engineering performance of modern large APS are considered: economic efficiency, radiation safety, reliability, and their interrelationship. A nomenclature is proposed for the quantitative indices which most completely characterize the enumerated properties and are convenient for the analysis of the engineering performance. The urgent problem of developing a methodology for the complex analysis and optimization of the principal performance components is considered; this methodology is designed to increase the efficiency of the work on high-performance competitive APS. The principle of complex optimization of the reliability, safety, and economic-efficiency indices is formulated; specific recommendations are made for the practical realization of this principle. The structure of the complex quantiative analysis of the enumerated performance components is given. The urgency and promise of the complex approach to solving the problem of APS optimization is demonstrated, i.e., the solution of the problem of creating optimally reliable, fairly safe, and maximally economically efficient stations

  14. Wind Energy Based Electric Vehicle Charging Stations Sitting. A GIS/Wind Resource Assessment Approach

    Directory of Open Access Journals (Sweden)

    George Xydis

    2015-11-01

    Full Text Available The transportation sector is severely correlated with major problems in environment, citizens’ health, climate and economy. Issues such as traffic, fuel cost and parking space have make life more difficult, especially in the dense urban environment. Thus, there is a great need for the development of the electric vehicle (EV sector. The number of cars in cities has increased so much that the current transportation system (roads, parking places, traffic lights, etc. cannot accommodate them properly. The increasing number of vehicles does not affect only humans but also the environment, through air and noise pollution. According to EPA, the 39.2% of total gas emissions in 2007 was caused by transportation activities. Studies have shown that the pollutants are not only gathered in the major roads and/or highways but can travel depending on the meteorological conditions leading to generic pollution. The promotion of EVs and the charging stations are both equally required to be further developed in order EVs to move out of the cities and finally confront the range problem. In this work, a wind resource and a GIS analysis optimizes in a wider area the sitting of wind based charging stations and proposes an optimizing methodology.

  15. Commercialization of an electric propulsion unit for ecological ice resurfacers

    Energy Technology Data Exchange (ETDEWEB)

    Giroux, M. [MG Service, L' Assomption, PQ (Canada); Sylvestre, P. [Environment Canada, Montreal, PQ (Canada)

    2000-03-01

    Community health departments (CHD) and the general public are greatly concerned about the air quality at indoor skating rinks. A solution now exists whereby municipalities can convert their internal combustion resurfacers to electricity, using a system proposed by MG Service. This electric propulsion unit was developed and designed by MG Service, in conjunction with the Centre d'experimentation des vehicules electriques du Quebec (CEVEQ) and TPR Inc., an engineering firm. The main advantage of this technology is the ease of integration into the chassis of conventional resurfacers currently in use throughout the various municipalities. The propulsion unit is battery-powered and designed to replace the internal combustion engine. As a result, it eliminates carbon monoxide and nitrogen dioxide emissions, and more than meets the requirements set by health boards with regard to air quality at indoor skating rinks. Recyclable, maintenance-free and manufactured according to the standards set by the Underwriters Laboratories of Canada (ULC), the gel-sealed batteries display great advantages. The cost effectiveness of the electric propulsion unit is more impressive when considering that electricity is clean and costs five times less than conventional fuels currently in use. Regular verifications and calibrations are not required and the maintenance is minimal. The ventilation requirements are also reduced, leading to savings in energy costs required for the aeration of the indoor skating rink. Finally, the elimination of tank rental and fuel costs represent an added benefit. A detailed description of the components is provided. Following a series of trials, the operators were impressed by the surface gripability, traction and manoeuvrability. The resurfacers also gave an impression of greater raw power and were very quiet and easy to use, resulting in better overall operation when compared to conventional resurfacers. 1 fig.

  16. Electric motor drive unit, especially adjustment drive for vehicles

    Energy Technology Data Exchange (ETDEWEB)

    Litterst, P

    1980-05-29

    An electric motor drive unit, particularly an adjustment drive for vehicles with at least two parallel drive shafts is described, which is compact and saves space, and whose manufacturing costs are low compared with those of well-known drive units of this type. The drive unit contains a suitable number of magnet systems, preferably permanent magnet systems, whose pole axes are spaced and run parallel. The two pole magnet systems have diametrically opposite shell-shaped segments, to which the poles are fixed. In at least one magnet system the two segments are connected by diametrically opposite flat walls parallel to the pole axes to form a single magnetic circuit pole housing. The segments of at least one other magnet system are arranged on this pole housing so that one of these flat walls is a magnetically conducting, connecting component of the magnetic circuit of the other magnet system.

  17. Type test of Class 1E electric cables, field splices, and connections for nuclear power generating stations - 1975

    International Nuclear Information System (INIS)

    Anon.

    1976-01-01

    This Standard provides direction for establishing type tests which may be used in qualifying Class 1E electric cables, field splices, and other connections for service in nuclear power generating stations. General guidelines for qualifications are given in IEEE Std 323-1974, Standard for Qualifying Class 1E Electric Equipment for Nuclear Power Generating Stations. Categories of cables covered are those used for power control and instrumentation services. Though intended primarily to pertain to cable for field installation, this guide may also be used for the qualification of internal wiring of manufactured devices

  18. Managing operations of plug-in hybrid electric vehicle (PHEV) exchange stations for use with a smart grid

    International Nuclear Information System (INIS)

    Nurre, Sarah G.; Bent, Russell; Pan, Feng; Sharkey, Thomas C.

    2014-01-01

    We consider a deterministic integer programming model for determining the optimal operations of multiple plug-in hybrid electric vehicle (PHEV) battery exchange stations over time. The operations include the number of batteries to charge, discharge, and exchange at each point in time over a set time horizon. We allow discharging of batteries back to the power grid, through vehicle-to-grid technology. We incorporate the exchange station's dependence on the power network, transportation network, and other exchange stations. The charging and discharging at these exchange stations lead to a greater amount of variability which creates a less predictable and flat power generation curve. We introduce and test three policies to smooth the power generation curve by balancing its load. Further, tests are conducted evaluating these policies while factoring wind energy into the power generation curve. These computational tests use realistic data and analysis of the results suggest general operating procedures for exchange stations and evaluate the effectiveness of these power flattening policies. - Highlights: • Model the operations of plug-in hybrid electric vehicle battery exchange stations. • Determine the optimal and general charging, discharging, and exchange operations. • Conclude that forced customer service levels are unnecessary with proper pricing. • Examine policies to reduce variability in power generation from PHEVs and wind. • Observe that strict constraints on exchange stations best reduce variability

  19. WIND SPEED AND ATMOSPHERIC STABILITY TRENDS FOR SELECTED UNITED STATES SURFACE STATIONS

    Energy Technology Data Exchange (ETDEWEB)

    Buckley, R; Allen H. Weber, A

    2006-11-01

    Recently it has been suggested that global warming and a decrease in mean wind speeds over most land masses are related. Decreases in near surface wind speeds have been reported by previous investigators looking at records with time spans of 15 to 30 years. This study focuses on United States (US) surface stations that have little or no location change since the late 1940s or the 1950s--a time range of up to 58 years. Data were selected from 62 stations (24 of which had not changed location) and separated into ten groups for analysis. The group's annual averages of temperature, wind speed, and percentage of Pasquill-Gifford (PG) stability categories were fitted with linear least squares regression lines. The results showed that the temperatures have increased for eight of the ten groups as expected. Wind speeds have decreased for nine of the ten groups. The mean slope of the wind speed trend lines for stations within the coterminous US was -0.77 m s{sup -1} per century. The percentage frequency of occurrence for the neutral (D) PG stability category decreased, while that for the unstable (B) and the stable (F) categories increased in almost all cases except for the group of stations located in Alaska.

  20. Emergency operating instruction improvements at San Onofre Nuclear Generating Station Units 2 and 3

    International Nuclear Information System (INIS)

    Trillo, M.W.; Smith, B.H.

    1989-01-01

    In late 1987, San Onofre nuclear generating station (SONGS) began an extensive upgrade of the units 2 and 3 emergency operating instructions (EOIs). The original intent of this program was to incorporate revised generic guidance and to correct problems that were identified by operators. While this program was in progress, the US Nuclear Regulatory Commission (NRC) conducted a series of audits of emergency operating procedure (EOP) development and maintenance programs as 16 commercial nuclear facilities in the United States. These audits included four stations with Combustion Engineering-designed nuclear steam supply systems. (One of these audits included a review of preupgrade SONGS units 2 and 3 EOIs.) Significant industrywide comments resulted from these audits. The NRC has stated its intent to continue the review and audit of EOIs and the associated maintenance programs at all US commercial nuclear facilities. The units 2 and 3 EOI upgrade program developed procedural improvements and procedural program maintenance improvements that address many of the existing audit comments that have been received by the industry. Other resulting improvements may be useful in minimizing NRC comments in future such audits. Specific improvements are discussed. The upgrade program resulted in benefits that were not originally anticipated. The results of this program can be of significant use by other utilities in addressing the industrywide concerns that have been raised in recent NRC audits of EOP development and maintenance programs

  1. Optimization and Economic Analysis of Grid-Photovoltaic Electric Boat Charging Station in Kuala Terengganu

    Directory of Open Access Journals (Sweden)

    Salleh N.A. S.

    2016-01-01

    Full Text Available This study evaluates the feasibility of developing grid-photovoltaic electric boat charging station in Kuala Terengganu using simulation-based method. The main focus is on reducing the dependency on subsidy spent by the government in fisheries sector and encouraging green technology in commercial sector. All data such as solar radiation, amount of subsidy received by fishermen, and fishing activities were collected for the selected area. Economic analyses of the proposed system are discussed based on payback period and net present cost (NPC. The comparison between the proposed system and the grid-only system is done based on the production and consumption of electricity per year, the NPC and emission of pollutant. The system also generates high income from selling energy to the grid with tariff rates RM 1.49/kWh. It is concluded that the proposed system is feasible to be developed in the selected area with the payback period and the NPC are 8.2 years and RM 759,098, respectively. The results also show that the performance of the proposed system is better than grid-only system in all the interested parameters.

  2. Identifying future electricity-water tradeoffs in the United States

    International Nuclear Information System (INIS)

    Sovacool, Benjamin K.; Sovacool, Kelly E.

    2009-01-01

    Researchers for the electricity industry, national laboratories, and state and federal agencies have begun to argue that the country could face water shortages resulting from the addition of thermoelectric power plants, but have not attempted to depict more precisely where or how severe those shortages will be. Using county-level data on rates of population growth collected from the US Census Bureau, utility estimates of future planned capacity additions in the contiguous United States reported to the US Energy Information Administration, and scientific estimates of anticipated water shortages provided from the US Geologic Survey and National Oceanic and Atmospheric Administration, this paper highlights the most likely locations of severe shortages in 22 counties brought about by thermoelectric capacity additions. Within these areas are some 20 major metropolitan regions where millions of people live. After exploring the electricity-water nexus and explaining the study's methodology, the article then focuses on four of these metropolitan areas - Houston, Texas; Atlanta, Georgia; Las Vegas, Nevada; New York, New York - to deepen an understanding of the water and electricity challenges they may soon be facing. It concludes by identifying an assortment of technologies and policies that could respond to these electricity-water tradeoffs.

  3. Identifying future electricity-water tradeoffs in the United States

    Energy Technology Data Exchange (ETDEWEB)

    Sovacool, Benjamin K. [Energy Governance Program, Centre on Asia and Globalisation, Lee Kuan Yew School of Public Policy, National University of Singapore (Singapore); Sovacool, Kelly E. [Department of Geography, Virginia Polytechnic Institute and State University, Blacksburg, VA (United States)

    2009-07-15

    Researchers for the electricity industry, national laboratories, and state and federal agencies have begun to argue that the country could face water shortages resulting from the addition of thermoelectric power plants, but have not attempted to depict more precisely where or how severe those shortages will be. Using county-level data on rates of population growth collected from the US Census Bureau, utility estimates of future planned capacity additions in the contiguous United States reported to the US Energy Information Administration, and scientific estimates of anticipated water shortages provided from the US Geologic Survey and National Oceanic and Atmospheric Administration, this paper highlights the most likely locations of severe shortages in 22 counties brought about by thermoelectric capacity additions. Within these areas are some 20 major metropolitan regions where millions of people live. After exploring the electricity-water nexus and explaining the study's methodology, the article then focuses on four of these metropolitan areas - Houston, Texas; Atlanta, Georgia; Las Vegas, Nevada; New York, New York - to deepen an understanding of the water and electricity challenges they may soon be facing. It concludes by identifying an assortment of technologies and policies that could respond to these electricity-water tradeoffs. (author)

  4. Start-up test of Fukushima Daini Nuclear Power Station Unit No.3

    International Nuclear Information System (INIS)

    Inomata, Toshio; Umezu, Akira; Kajikawa, Makoto; Koibuchi, Hiroshi; Netsu, Nobuhiko.

    1986-01-01

    In Unit 3 of the Fukushima Nuclear Power Station II (daini), a BWR power plant of output 1,100 MW, commercial operation was started in June 1985. Its start-up test was finished successfully in about nine months. That is, new equipments introduced were demonstration tested. Though the items of testing are increased, the start-up test took short time, resulting in construction period only 54.7 months of the Unit 3, the shortest in the world. During the test, there was no scramming other than the planned. Described are the following: an outline of the Unit 3, the items of its improvement and standardization, including the new equipments, preparations for the start-up test, the start-up test and its evaluation. (Mori, K.)

  5. Analysis of a station blackout transient at the Kori units 3/4

    International Nuclear Information System (INIS)

    Bang, Young Seok; Kim, Hho Jung

    1992-01-01

    A transient analysis of station blackout accident is performed to evaluate the plant specific capability to cope with the accident at the Kori Units 3/4. The RELAP5/MOD3/5m5 code and full three loop modelling scheme are used in the calculation. The leak flow from reactor coolant system due to a failure of reactor coolant pump seal following the accident is assumed to be 25 gpm and the turbine driven aux feedwater unavailable. As a result, it is found that no core uncovery occurs in the plant until 7100 sec following a station blackout, the steam generator has a decay heat removal capability until 3100 sec, and the natural circulation over the reactor coolant loop until the complete loop seal voiding are observed. And the Nuclear Plant Analyzer is used and found to be effective in improving the phenomenological understanding on the accident

  6. Fulton Generating Station Units 1 and 2 (Docket Nos. 50-463 and 50-464): Final environmental statement

    International Nuclear Information System (INIS)

    1975-04-01

    The proposed action is the issuance of construction permits to the Philadelphia Electric Company for the construction of the Fulton Generating Station, Units 1 and 2, located in Fulton and Drumore Townships, Lancaster County, Pennsylvania. Makeup water for cooling will be withdrawn form Conowingo Pond at a maximum rate of 43,000 gpm. The dissolved solids content of the blowdown water will be increased by a factor of about two. The remainder of the water will be evaporated to the atmosphere by cooling towers. About 10 acres offsite, some 7 acres of which is woodland, will be used for railroad-spur construction. About 0.25 mile of new transmission-line rights-of-way (9 acres) will be needed, although 49 miles of new transmission line, which will require about 3 miles of selective clearing, will be constructed on existing rights-of-way. An unestablished amount of land will be used for access-road construction, but the applicant will use existing roadway corridors where feasible. A small loss of consumer species will result from loss of habitat. Some loss of benthic and pelagic organisms in Conowingo Pond will be caused by intake and discharge construction. The Station's thermal and chemical discharges will meet the State water-quality standards. The duration of additional ground-level fog caused by Station operation is expected to be less than 3 hr/year. (Sect. 5.3.3). No observable effects are expected from salt deposition from cooling-tower drift. (Sect. 5.3.3). Decomposers, primary producers, and zooplankton will be entrained and killed in the cooling-tower system; they, as well as benthic organisms, will be affected by the heated-water discharge. This loss will have little effect on the pond food web. 30 figs., 76 tabs

  7. Integration Assessment of Visiting Vehicle Induced Electrical Charging of the International Space Station Structure

    Science.gov (United States)

    Kramer, Leonard; Kerslake, Thomas W.; Galofaro, Joel T.

    2010-01-01

    The International Space Station (ISS) undergoes electrical charging in low Earth orbit (LEO) due to positively biased, exposed conductors on solar arrays that collect electrical charges from the space plasma. Exposed solar array conductors predominately collect negatively charged electrons and thus drive the metal ISS structure electrical ground to a negative floating potential (FP) relative to plasma. This FP is variable in location and time as a result of local ionospheric conditions. ISS motion through Earth s magnetic field creates an addition inductive voltage up to 20 positive and negative volts across ISS structure depending on its attitude and location in orbit. ISS Visiting Vehicles (VVs), such as the planned Orion crew exploration vehicle, contribute to the ISS plasma charging processes. Upon physical contact with ISS, the current collection properties of VVs combine with ISS. This is an ISS integration concern as FP must be controlled to minimize arcing of ISS surfaces and ensure proper management of extra vehicular activity crewman shock hazards. This report is an assessment of ISS induced charging from docked Orion vehicles employing negatively grounded, 130 volt class, UltraFlex (ATK Space Systems) solar arrays. To assess plasma electron current collection characteristics, Orion solar cell test coupons were constructed and subjected to plasma chamber current collection measurements. During these tests, coupon solar cells were biased between 0 and 120 V while immersed in a simulated LEO plasma. Tests were performed using several different simulated LEO plasma densities and temperatures. These data and associated theoretical scaling of plasma properties, were combined in a numerical model which was integrated into the Boeing Plasma Interaction Model. It was found that the solar array design for Orion will not affect the ISS FP by more than about 2 V during worst case charging conditions. This assessment also motivated a trade study to determine

  8. Integrated base stations and a method of transmitting data units in a communications system for mobile devices

    NARCIS (Netherlands)

    Bosch, H.G.P.; Mullender, Sape J.; Narlikar, G.J.; Samuel, L.G.; Yagati, L.N.

    2006-01-01

    Integrated base stations and a method of transmitting data units in a communications system for mobile devices. In one embodiment, an integrated base station includes a communications processor having a protocol stack configured with a media access control layer and a physical layer.

  9. Effects of pellet yield on electricity cost in laser fusion generating stations

    International Nuclear Information System (INIS)

    Bohachevsky, I.O.; Booth, L.A.; Hafer, J.F.; Pendergrass, J.H.

    1978-01-01

    The dependence of capital and net electricity production costs on fuel pellet yield is investigated for laser fusion reactors based on the magnetically protected and the wetted wall reactor cavity concepts. It is determined that above a certain pellet yield, which depends on the cavity concept, diseconomies of scale occur and the costs per unit output increase with increasing fuel pellet yield. This behavior, determined with the trade-off and analysis computer code TROFAN, is explained through analytical examination of the scaling rules for the laser fusion reactor components

  10. Decentralized energy management strategy based on predictive controllers for a medium voltage direct current photovoltaic electric vehicle charging station

    International Nuclear Information System (INIS)

    Torreglosa, Juan P.; García-Triviño, Pablo; Fernández-Ramirez, Luis M.; Jurado, Francisco

    2016-01-01

    Highlights: • Electric vehicle charging station supplied by photovoltaic, batteries and grid connection is analyzed. • The bus voltage is the key parameter for controlling the system by decentralized approach. • Decentralized control approach facilities the enlargement of the system. • Photovoltaic and battery systems are controlled by model predictive controllers. • Response by model predictive controllers improves that by PI controllers. - Abstract: The use of distributed charging stations based on renewable energy sources for electric vehicles has increased in recent years. Combining photovoltaic solar energy and batteries as energy storage system, directly tied into a medium voltage direct current bus, and with the grid support, results to be an interesting option for improving the operation and efficiency of electric vehicle charging stations. In this paper, an electric vehicle charging station supplied by photovoltaic solar panels, batteries and with grid connection is analysed and evaluated. A decentralized energy management system is developed for regulating the energy flow among the photovoltaic system, the battery and the grid in order to achieve the efficient charging of electric vehicles. The medium voltage direct current bus voltage is the key parameter for controlling the system. The battery is controlled by a model predictive controller in order to keep the bus voltage at its reference value. Depending on the state-of-charge of the battery and the bus voltage, the photovoltaic system can work at maximum power point tracking mode or at bus voltage sustaining mode, or even the grid support can be needed. The results demonstrate the proper operation and energy management of the electric vehicle charging station under study.

  11. The United Kingdom Law on the authorisation of nuclear power stations

    International Nuclear Information System (INIS)

    Savinson, R.

    1977-01-01

    This paper explains the requirements of the law of the United Kingdom as to the authorisations needed to construct and operate nuclear power plants in Great Britain. For simplicity, the texts referred to apply to England and Wales, Scottish law differing in detail but not in principle. Implementation of this legal system is studied in particular from the viewpoint of the Central Electricity Generating Board (CEGB) which is at present the body exclusively responsible for generating and supplying electricity in England and Wales. (NEA) [fr

  12. Technical Specifications, Seabrook Station, Unit 1 (Docket No. 50-443). Appendix ''A'' to License No. NPF-56

    International Nuclear Information System (INIS)

    1986-10-01

    This report provides specifications for the Seabrook Station Unit 1 reactor concerning: safety limits and limiting safety settings; limiting conditions for operation and surveillance requirements; design features; and administrative controls

  13. Technical specifications, Beaver Valley Power Station, Unit 2 (Docket No. 50-412): Appendix ''A'' to License No. NPF-73

    International Nuclear Information System (INIS)

    1987-08-01

    This report presents information concerning the Beaver Valley Power Station Unit 2 Reactor. Topics under discussion include: safety limits and limiting safety system settings; limiting condition for operation and surveillance requirements; design features; and administrative controls

  14. Development of filtered containment venting system and application for Kashiwazaki-Kariwa Nuclear Power Station Unit 6, 7

    International Nuclear Information System (INIS)

    Murai, Soutarou; Hiranuma, Naoki; Kimura, Takeo; Omori, Shuichi; Watanabe, Fumitoshi; Sasa, Daisuke

    2014-01-01

    The Fukushima Dai-ichi Nuclear Power Station (1F) of Tokyo Electric Power Company (TEPCO) had experienced severe radio-active release to the environment in the Tohoku Region Pacific Coast Earthquake (alias: the Great East Japan Earthquake) in 2011. Under the Station Black-Out (SBO) conditions caused by tsunami with the earthquake, the 1F operators had tried to vent the gasses in the Primary Containment Vessels (PCVs) of the unit 1, 2 and 3 to the environment through the water pools in the suppression chambers of the PCVs. Its venting, however, was imperfect and, as a result, major direct radio-active release to the environment was caused. After this disaster, TEPCO launched a project to develop the Filtered Containment Venting System (FCVS), in which our very bitter experiences in the 1F accident as described above are reflected. One of the main purposes of the development of the FCVS is to enhance operability of venting under the severe plant conditions such as the SBO during progressing of severe core damage, and another is to enhance removal performance of radio-nuclides with the newly added filtering equipment, which is installed in the venting line from the PCV to the outer. The Kashiwazaki-Kariwa NPS unit 6 and 7 will be the first reactors applied the FCVSs. In this paper, we show the design concept of the TEPCO's FCVS, the brief overview of the system design and the summary of experiment which has been performed for getting the performance data of the FCVS such as decontamination factor in various conditions. (author)

  15. Study of a New Quick-Charging Strategy for Electric Vehicles in Highway Charging Stations

    Directory of Open Access Journals (Sweden)

    Lixing Chen

    2016-09-01

    Full Text Available To solve the problem, because of which conventional quick-charging strategies (CQCS cannot meet the requirements of quick-charging for multiple types of electric vehicles (EV on highways where vehicle inflow is excessive, this paper proposed a new quick-charging strategy (NQCS for EVs: on the premise of not affecting those EVs being charged, the remaining power of the quick-charging pile with multiple power output interfaces is used to provide a synchronous charging service for EVs waiting in the queue. To verify the effectiveness of this strategy, a power distribution model of charging pile and a queuing model of charging station (CS were constructed. In addition, based on an actual highway service area where vehicle inflow is excessive during the simulation period (0:00–24:00, charging situations of CQCS and NQCS were respectively simulated in a charging station (CS, with different number of chargers, by basic queuing algorithm and an improved queuing algorithm. The simulation results showed that when the relative EV inflow is excessive, compared to CQCS, NQCS not only can reduce user waiting time, charging time, and stay time, but also can improve the utilisation rate of charging infrastructure and service capacity of CS and reduce the queue length of CS. At the same time, NQCS can reduce the impact on the power grid. In addition, in NQCS, the on-demand power distribution method is more efficient than the average power distribution method. Therefore, NQCS is more suitable for quick-charging for multiple types of EVs on highways where vehicle inflow is excessive.

  16. Probabilistic fire risk assessment for Koeberg Nuclear Power Station Unit 1

    International Nuclear Information System (INIS)

    Grobbelaar, J.F.; Foster, N.A.S.; Luesse, L.J.

    1995-01-01

    A probabilistic fire risk assessment was done for Koeberg Nuclear Power Station Unit 1. Areas where fires are likely to start were identified. Equipment important to safety, as well as their power and/or control cable routes were identified in each fire confinement sector. Fire confinement sectors where internal initiating events could be caused by fire were identified. Detection failure and suppression failure fault trees and event trees were constructed. The core damage frequency associated with each fire confinement sector was calculated, and important fire confinement sectors were identified. (author)

  17. Dungeness 'A' Nuclear Power Station. The findings of NII's assessment of Nuclear Electric's long term safety review

    International Nuclear Information System (INIS)

    1994-01-01

    The assessment is reported of Nuclear Electrics' Long Term Safety Reviews (LTSR) of the Dungeness A magnox reactors. The assessment was undertaken by the Health and Safety Executive's Nuclear Installations Inspectorate (NII) which is responsible for regulating the safety of nuclear installations in the United Kingdom. This was one of a programme of LTSRs for all the UK magnox reactors. The LTSR for each plant was proceeded by a Generic Issues programme. The results of both the LTSR and the Generic Issues programme have been used by NII in forming the conclusions of this assessment. Overall the safety case for Dungeness A is satisfactory for continued operation. A programme of additional modifications and inspections has been put in place which further enhances the safety justification. Reactor operations will continue to be monitored and regulated in accordance with the inspections required under the licensing arrangements. Provided these requirements and the agreed further analysis, improvements and inspections give satisfactory results it is expected that the station will be able to operate safely till each reactor is at least 30 years old. Beyond this point a further Periodic Safety Review will be required. (UK)

  18. Final environmental statement for Shoreham Nuclear Power Station, Unit 1: (Docket No. 50-322)

    International Nuclear Information System (INIS)

    1977-10-01

    The proposed action is the issuance of an Operating License to the Long Island Lighting Company (LILCO) for the startup and operation of the Shoreham Nuclear Power Station, Unit 1 (the plant) located on the north shore of Long Island, the State of New York, County of Suffolk, in the town of Brookhaven. The Shoreham station will employ a boiling-water reactor (BWR), which will operate at a thermal output of 2436 MW leading to a gross output of 846 MWe and a net output of about 820 MWe. The unit will be cooled by once-through flow of water from the Long Island Sound. One nuclear unit with a net capacity of 820 MWe will be added to the generating resources of the Long Island Lighting Company. This will have a favorable effect on reserve margins and provide a cost savings of approximately $62.1 million (1980 dollars) in production costs in 1980 if the unit comes on line as scheduled; additional cost savings will be realized in subsequent years. Approximately 100 acres (40 hectares) of the 500-acre (202-hectare) site of rural (mostly wooded) land owned by the applicant have been cleared. Most of this will be unavailable for other uses during at least the 40-year life of the plant. No offsite acreage has been or will be cleared. Land in the vicinity of the site has undergone some residential development that is typical for all of this area of Long Island. The operation of Shoreham Unit 1 will have insignificant impacts on this and other types of land uses in the vicinity of the site. 33 figs., 56 tabs

  19. Ergonomics work stations decreases the health impairment and saves electrical energy at the woodworking workshop in Bali, Indonesia.

    Science.gov (United States)

    Sudiajeng, Lilik; Adiputra, Nyoman; Leibbrandt, Richard

    2012-12-01

    This research was conducted to assess the positive effect of the ergonomics work station on the health impairment and electrical energy usage at the woodworking workshop in Bali, Indonesia. Woodworking workshops are dangerous, particularly when they are used improperly. Workers are exposed to health hazards that cause health impairment and inefficiencies in their work conditions. A preliminary study at a woodworking workshop at the Bali State Polytechnic showed that the work station was not suitable to body size of the participants and caused awkward postures. In addition, there was also an inappropriate physical work environment. Both inappropriate work station and physical work environment caused participants to be less active and motivated. This paper reports on an experimental study into the effects of an ergonomic intervention at this workshop. The participants were 2 groups of male students with 10 participants in each group. The first group performed the task with the original work station as a control group, while the second group performed the task with the new work station. The study found a significant difference between groups (p work station decreased the working heart rate (16.7%), the total score of musculoskeletal disorders (17.3%), and the total score of psychological fatigue (21.5%). Furthermore, it also decreased the electrical energy usage (38.7%). This shows that an ergonomics intervention on work station decreased the health impairment and saved electrical energy usage. It also protected the workers from woodworking hazards and allowed participants to perform their tasks in healthy, safe, convenient and efficient work conditions.

  20. Safety Evaluation Report related to the full-term operating license for Millstone Nuclear Power Station, Unit No. 1 (Docket No. 50-245)

    International Nuclear Information System (INIS)

    1985-10-01

    The Safety Evaluation Report for the full-term operating license application filed by the Connecticut Light and Power Company, the Hartford Electric Light Company, Western Massachusetts Electric Company and the Millstone Point Company [(now known as Connecticut Light and Power Company (CL and P) and Western Massachusetts Electric Company (WMECO) having authority to possess Millstone-1, 2, and 3, and the Northeast Nuclear Energy Company (NNECO) as the responsible entity for operation of the facilities)] for Millstone Nuclear Power Station Unit 1 has been prepared by the Office of Nuclear Reactor Regulation of the US Nuclear Regulatory Commission. The facility is located in the town of Waterford, Connecticut. Subject to favorable resolution of the items discussed in this report, the staff concludes that the facility can continue to be operated without endangering the health and safety of the public

  1. Bulk energy storage increases United States electricity system emissions.

    Science.gov (United States)

    Hittinger, Eric S; Azevedo, Inês M L

    2015-03-03

    Bulk energy storage is generally considered an important contributor for the transition toward a more flexible and sustainable electricity system. Although economically valuable, storage is not fundamentally a "green" technology, leading to reductions in emissions. We model the economic and emissions effects of bulk energy storage providing an energy arbitrage service. We calculate the profits under two scenarios (perfect and imperfect information about future electricity prices), and estimate the effect of bulk storage on net emissions of CO2, SO2, and NOx for 20 eGRID subregions in the United States. We find that net system CO2 emissions resulting from storage operation are nontrivial when compared to the emissions from electricity generation, ranging from 104 to 407 kg/MWh of delivered energy depending on location, storage operation mode, and assumptions regarding carbon intensity. Net NOx emissions range from -0.16 (i.e., producing net savings) to 0.49 kg/MWh, and are generally small when compared to average generation-related emissions. Net SO2 emissions from storage operation range from -0.01 to 1.7 kg/MWh, depending on location and storage operation mode.

  2. The development of on-line thermal performance monitors in Nuclear Electric Company's stations

    International Nuclear Information System (INIS)

    Conner, A.S.

    1992-01-01

    The paper examines the economic benefits of using on-line monitoring techniques in assisting Station Staff with the task of optimising the efficient use of reactor fuel. The role of thermal performance monitoring for detecting changes in plant condition is also examined and the way in which the data can be used by engineers to assist with the preparation of operating and maintenance programmes. To enable genuine gradual changes in plant performance to be detected when operating against a background of changing plant signal accuracy conditions, plant transducers have to be calibrated on a regular basis. This can be both costly and labour intensive. To reduce this requirement for regular calibrations, an automatic software signal verification program has been developed for use in on-line monitoring schemes. It forms part of the total unit performance calculation package and uses a whole plant model to verify plant signals. All plant signals used to calculate unit heat rate are verified typically every 15 minutes with signals going outside predetermined limits being automatically reported to the user. The program is interactive allowing the user to interrogate the condition of the signal, with respect to both its error magnitude and rate of drift outside signal limits. The program runs in real time mode on a Workstation connected directly to the plant

  3. Start-up tests of Kashiwazakikariwa Nuclear Power Station Unit No.2 and No.5

    International Nuclear Information System (INIS)

    Fueki, Kensuke; Aoki, Shiro; Tanaka, Yasuhisa; Yahagi, Kimitoshi

    1991-01-01

    The Kashiwazakikariwa Nuclear Power Station Units No.5 and No.2 started commercial operation on April 10 and September 28 of 1990 respectively. As the result of the application of the First and Second LWR Improvement and Standardization Program, the plants were designed aiming at improvement of reliability, operation, and maintenance while maintaining safety. Construction of the plants took 6.5 to 7 years for completion, during which period the last 10 months were spent for the start up tests program. Start up tests were carried out under deliberate management to assure that the plants can operate safely and steadily at the prescribed operating points, and the schedules and tests item modifications adopted in Unit No.2 and No.5 were verified under the start up tests program. (author)

  4. Efficient erection of a piping unit in a nuclear power station

    International Nuclear Information System (INIS)

    Halstrick, V.; Peters, G.

    1986-01-01

    In consideration of the negative experience gathered in the past extensive project logistics are required for the erection of piping units in a nuclear power station in order to be able to recognize and master the numerous influences and different marginal conditions with reasonable certainty and at an early stage. The utilization of requirements from the analysis of experience for the conception of project management begins with the erection planning and results in check lists for the execution of erection. During production planning these check lists are verified for realization. Because of the extensive data, EDP-aided systems are applied for checking and controlling the flow of information and material. A dialogue-aided system is presented for project planning and controlling which enables a transparent and farsighted execution of a project. By means of comparable piping units it is demonstrated that due to the created controlling system a great success becomes obvious in relation to the past. (orig.) [de

  5. H2USA: Siting Refueling Stations in the Northeast

    Energy Technology Data Exchange (ETDEWEB)

    Melaina, Marc W [National Renewable Energy Laboratory (NREL), Golden, CO (United States); Muratori, Matteo [National Renewable Energy Laboratory (NREL), Golden, CO (United States); Zuboy, Jarett [Consultant; Ellis, Steve [Honda

    2017-11-01

    To achieve cost-effective deployment of both fuel cell electric vehicles (FCEVs) and hydrogen stations, the number of vehicles and public stations must grow together in areas of highest demand. This fact sheet introduces two advanced modeling tools and presents preliminary analysis of the hydrogen refueling station locations needed to support early consumer demand for FCEVs in the Northeast United States. United States.

  6. Papers of 6. Scientific-Technical Seminar Material Study for Electric Power Stations and Energetics

    International Nuclear Information System (INIS)

    1999-01-01

    The report is an assembly of the papers concerning the material problems occurring during the exploitation of power station. The normalization problems in power station and gas pipelines according to the prescription of UE are also discussed. (author)

  7. Stackelberg Game Model of Wind Farm and Electric Vehicle Battery Switch Station

    Science.gov (United States)

    Jiang, Zhe; Li, Zhimin; Li, Wenbo; Wang, Mingqiang; Wang, Mengxia

    2017-05-01

    In this paper, a cooperation method between wind farm and Electric vehicle battery switch station (EVBSS) was proposed. In the pursuit of maximizing their own benefits, the cooperation between wind farm and EVBSS was formulated as a Stackelberg game model by treating them as decision makers in different status. As the leader, wind farm will determine the charging/discharging price to induce the charging and discharging behavior of EVBSS reasonably. Through peak load shifting, wind farm could increase its profits by selling more wind power to the power grid during time interval with a higher purchase price. As the follower, EVBSS will charge or discharge according to the price determined by wind farm. Through optimizing the charging /discharging strategy, EVBSS will try to charge with a lower price and discharge with a higher price in order to increase its profits. Since the possible charging /discharging strategy of EVBSS is known, the wind farm will take the strategy into consideration while deciding the charging /discharging price, and will adjust the price accordingly to increase its profits. The case study proved that the proposed cooperation method and model were feasible and effective.

  8. Dynamic analysis of electric equipment for nuclear power stations under seismic loads

    International Nuclear Information System (INIS)

    Buck, K.E.; Bodisco, U. von; Winkler, K.

    1977-01-01

    The response spectrum method, generally accepted as the most practical method for linear seismic analysis of power station components, is here applied in conjunction with the finite element method to electric components. The fully dynamic analysis based on the superposition of the natural modes as carried out for an electronics cabinet and for transmitter supports is outlined and selected results are presented. Several different methods are in use for the superposition of the contributions of the different modes. Here addition of absolute values, the square-root of the sum of squares, and a mixed method taking account of closely spaced modes is applied. For different structures, the degree of conservativity is thus demonstrated, the largest difference in the stresses computed by the different methods being approximately 30%. For structures whose natural frequencies are in the spectrum range with zero period response, a simplified response analysis using static loads is often carried out. This is demonstrated for the electronics cabinet and transmitter mountings, and the results are compared with the fully dynamic analyses. It is seen that this 'pseudo-dynamic' analysis yields useful approximations for the distributions of stresses. Practical details of the structural models as well as results are presented for several switchgear and electronics cabinets

  9. Occupational exposure to magnetic fields from transformer stations and electric enclosures in Turkey.

    Science.gov (United States)

    Çam, Semra Tepe; Fırlarer, Arzu; Özden, Semih; Canseven, Ayşe G; Seyhan, Nesrin

    2011-06-01

    We aimed to provide a systematic evaluation of magnetic field (MF) exposure of staff working in the offices located above or close to transformer stations (TS) and electric enclosures (EE). Occupational short-term "spot" measurements with Narda EFA-300 and isotropic magnetic field probe were carried out in two National Banks and one Industrial Company having more than 500 employees. Extremely low-frequency (ELF) MFs up to several tens of μT were measured in the mentioned working environments. 25% of the measured MFs were found less than 0.3 μT, the background exposure level that staff receive at home, 75% were above 0.3 μT with the highest value of 6.8 μT. The mean and median personal exposures were calculated to be 1.19 μT and 0.56 μT, respectively. Most of the staff (83%) is under risk based on epidemiological studies that reported a statistically significant association between risk of leukemia and averaged magnetic fields of 0.2 μT or over. Results showed that risk evaluation should be considered to minimize the possibility of the workers being harmed due to exposure to work-related electromagnetic sources.

  10. Electric Vehicle Performance at McMurdo Station (Antarctica) and Comparison with McMurdo Station Conventional Vehicles

    Energy Technology Data Exchange (ETDEWEB)

    Sears, T.; Lammert, M.; Colby, K.; Walter, R.

    2014-09-01

    This report examines the performance of two electric vehicles (EVs) at McMurdo, Antarctica (McMurdo). The study examined the performance of two e-ride Industries EVs initially delivered to McMurdo on February 16, 2011, and compared their performance and fuel use with that of conventional vehicles that have a duty cycle similar to that of the EVs used at McMurdo.

  11. Setting up charging electric stations within residential communities in current China: Gaming of government agencies and property management companies

    International Nuclear Information System (INIS)

    Wu, Tian; Ma, Lin; Mao, Zhonggen; Ou, Xunmin

    2015-01-01

    The difficulty of charging electric vehicles (EVs) is now hindering their further development. Governments generally choose to build stations for home charging (including piles) within residential communities. Given the conflict of interest between various government agencies and property management companies, constructing a charging station within residential communities would result in welfare loss for the property management companies and therefore lead to the principal–agent problem. This paper constructs a two-period imperfect information game theory model to study the moral hazard involved in this issue and government agencies' optimal choice. In the analytic solution of the model, we find that the optimal choice for a farsighted government agency is to constantly improve the incentive mechanism and introduce charging stations only when the conflict of interest is eliminated. Any benefits derived from government regulations by force would prove short-lived. The government should focus on long-term returns in the development of EVs, and its optimal mechanism should be designed to mitigate the principal–agent problem of property management companies, thereby accelerate the progress of EV charging infrastructure and improve overall social welfare. - Highlights: • The charging of electric vehicles (EVs) is hindering their use. • A game theory model is used for analysis of EV charging station construction. • Charging stations are in residential communities in China. • Government agencies are constantly improving incentive mechanisms

  12. High efficiency-large capacity circulating water pump for Hamaoka Nuclear Power Station unit No.3

    International Nuclear Information System (INIS)

    Ito, Akihiko; Sasamuro, Takemi; Takeda, Hirohisa.

    1988-01-01

    No.3 plant in the Hamaoka Nuclear Power Station, Chube Electric Power Co., Inc. is the latest plant of 1100 MW class BWR type, which began the commercial operation in August, 1987. The seawater intake and discharge system of this plant is composed of the channel exceeding 2 km in the total length from the intake tower to the discharge port. The circulating water pump installed in this system has the capacity of 1620 m 3 /min and the total head of 16.5 m, which are the largest in the world. It attained the efficiency as high as more than 90%. Three pumps supply seawater to three-body condensers. The design of the impeller and the casing for obtaining high efficiency, the structural design for facilitating maintenance, the manufacture of a model pump and the performance test using it and so on are reported. The most important item in the manufacture was the form of the onebody impeller weighing 4.5t. The confirmation of the performance of the actual machines was carried out as a part of the synthetic function confirmation test at the power station, and the flow rate was measured with Pitot tubes and ultrasonic flowmeters. (Kako, I.)

  13. Final environmental statement related to the operation of North Anna Power Station, Units 1 and 2: (Docket Nos. 50-338 and 50-339)

    International Nuclear Information System (INIS)

    1980-08-01

    The proposed action is the issuance of Operating Licenses to the Virginia Electric and Power Company for the startup and operation of the North Anna Power Station, Units No. 1 and 2, located on Lake Anna in Louisa County, 40 miles east of Charlottesville, Virginia. The information in this second addendum responds to the Commission's directive that the staff address in narrative form the environmental dose commitments and health effects from fuel cycle releases, fuel cycle socioeconomic impacts, and possible cumulative impacts pending further treatment by rulemaking

  14. Safety evaluation report related to the operation of Limerick Generating Station, Units 1 and 2 (Docket Nos. 50-352-50-353). Supplement 1

    International Nuclear Information System (INIS)

    1983-12-01

    This report supplements the Safety Evaluation Report (NUREG-0991, August 1983) for the application filed by the Philadelphia Electric Company, as applicant and owner, for licenses to operate the Limerick Generating Station Units 1 and 2 (Docket Nos. 50-352 and 50-353). The facility is located near Pottstown, Pennsylvania. Subject to favorable resolution of the items discussed in this report, the NRC staff concludes that the facility can be operated by the applicant without endangering the health and safety of the public

  15. Safety-evaluation report related to the operation of Limerick Generating Station, Units 1 and 2 (Docket Nos. 50-352 and 50-353)

    International Nuclear Information System (INIS)

    1983-08-01

    The Safety Evaluation Report for the application filed by the Philadelphia Electric Company, as applicant and owner, for licenses to operate the Limerick Generating Station Units 1 and 2 (Docket Nos. 50-352 and 50-353), has been prepared by the Office of Nuclear Reactor Regulation of the US Nuclear Regulatory Commission. The facility is located near Pottstown, Pennsylvania. Subject to favorable resolution of the items discussed in this report, the NRC staff concludes that the facility can be operated by the applicant without endangering the health and safety of the public

  16. Safety Evaluation Report related to the operation of Wolf Creek Generating Station, Unit No. 1 (Docket No. STN 50-482). Supplement No. 6

    International Nuclear Information System (INIS)

    1985-06-01

    This report supplements the Safety Evaluation Report (SER) for the application filed by the Kansas Gas and Electric Company, as applicant and agent for the owners, for a license to operate the Wolf Creek Generating Station, Unit 1 (Docket No. STN 50-482). The facility is located in Coffey County, Kansas. This supplement provides recent information regarding resolution of the license conditions identified in the SER. Because of the favorable resolution of the items discussed in this report, the staff concludes that the facility can be operated by the licensee at power levels greater than 5% without endangering the health and safety of the public

  17. NRC Fact-Finding Task Force report on the ATWS event at Salem Nuclear Generating Station, Unit 1, on February 25, 1983

    International Nuclear Information System (INIS)

    1983-03-01

    An NRC Region I Task Force was established on March 1, 1983 to conduct fact finding and data collection with regard to the circumstances which led to an anticipated transient without scram (ATWS) event at the Public Service Electric and Gas Company's Salem Generating Station, Unit 1 on February 25, 1983. The charter of the Task Force was to determine the factual information pertinent to management and administrative controls which should have ensured proper operation of the reactor trip breakers in the solid state protection system. This report documents the findings of the Task Force along with its conclusions

  18. Development of a Power Electronics Unit for the Space Station Plasma Contactor

    Science.gov (United States)

    Hamley, John A.; Hill, Gerald M.; Patterson, Michael J.; Saggio, Joseph, Jr.; Terdan, Fred; Mansell, Justin D.

    1994-01-01

    A hollow cathode plasma contactor has been baselined as a charge control device for the Space Station (SS) to prevent deleterious interactions of coated structural components with the ambient plasma. NASA LeRC Work Package 4 initiated the development of a plasma contactor system comprised of a Power Electronics Unit (PEU), an Expellant Management Unit (EMU), a command and data interface, and a Plasma Contactor Unit (PCU). A breadboard PEU was designed and fabricated. The breadboard PEU contains a cathode heater and discharge power supply, which were required to operate the PCU, a control and auxiliary power converter, an EMU interface, a command and telemetry interface, and a controller. The cathode heater and discharge supplies utilized a push-pull topology with a switching frequency of 20 kHz and pulse-width-modulated (PWM) control. A pulse ignition circuit derived from that used in arcjet power processors was incorporated in the discharge supply for discharge ignition. An 8088 based microcontroller was utilized in the breadboard model to provide a flexible platform for controller development with a simple command/data interface incorporating a direct connection to SS Mulitplexer/Demultiplexer (MDM) analog and digital I/O cards. Incorporating this in the flight model would eliminate the hardware and software overhead associated with a 1553 serial interface. The PEU autonomously operated the plasma contactor based on command inputs and was successfully integrated with a prototype plasma contactor unit demonstrating reliable ignition of the discharge and steady-state operation.

  19. Safety evaluation report related to the operation of Limerick Generating Station, Units 1 and 2 (Docket Nos. 50-352 and 50-353)

    International Nuclear Information System (INIS)

    1989-06-01

    In August 1983 the staff of the Nuclear Regulatory Commission issued its Safety Evaluation Report (NUREG-0991) regarding the application of the Philadelphia Electric Company (the licensee) for licenses to operate the Limerick Generating Station, Units 1 and 2, located on site in Montgomery and Chester Counties, Pennsylvania. Supplement 1 to NUREG-0991 was issued in December 1983. Supplements 2 and 3 were issued in October 1984. License NPF-27 for the low-power operation of Limerick Unit 1 was issued on October 26, 1984. Supplement 4 was issued in May, 1985, Supplement 5 was issued in July 1985, and Supplement 6 was issued in August 1985. These supplements addressed further issues that required resolution before Unit 1 proceeded beyond the 5-percent power level. The full-power operating license for Limerick Unit 1 (NPF-39) was issued August 8, 1985, and the unit has completed two cycles of operation. Supplement 7 was issued April 1989 to address some of the few significant design differences between Units 1 and 2, the resolution of issues that remained open when the Unit 1 full-power license was issued and an assessment of some of the issues that required resolution before issuance of an operating license for Unit 2. This supplement addresses the remaining issues that required resolution before issuance of and operating license for Unit 2

  20. About the Territorial Potential of the Construction of Battery-Charging Stations for Autonomous Electric Motor Vehicles in the Regions

    Directory of Open Access Journals (Sweden)

    Shilova Lyubov

    2016-01-01

    Full Text Available The article describes the main current trends in the development of electric motor vehicles with "zero emission" as well as the battery-charging stations concerned. The study is based on a preliminary comparative analysis of the RF regions with respect to five indices (average per capita income, number of private cars in the region, air pollution level, provision of the region with power supply and the potential use of local renewable energy resources, and it gives some recommendations on the prospects of possible construction of battery-charging stations in the regions.

  1. The costs of generating electricity in nuclear and coal fired power stations

    International Nuclear Information System (INIS)

    Petroll, M.

    1984-01-01

    An ad-hoc group of experts for international comparison of electricity generation cost was established in the OECD more than two years ago. This group of experts submitted their report of results in English at the end of last year. This paper publishes an abbreviated version making use of original quotations exclusively in order to keep true to the content of the study as much as possible. The study arrives at the following conclusion: ''There is no uniform set of input data for nuclear and coalfired power plants and assumptions concerning the base parameters of the reactor differ from country to country. Despite these differences, the outcome is that, nuclear energy is cheaper than coal in all countries concerned with the exception of some parts of the United States and Canada.'' (orig./UA) [de

  2. Floating nuclear power station of APWS-80 type for electricity generation and fresh water production

    International Nuclear Information System (INIS)

    Zverev, K.V.; Polunichev, V.I.; Sergeev, Yu.A.

    1997-01-01

    To solve the problem of seawater desalination and electric energy generation, the designing organizations of Russia have developed two variants of floating nuclear desalination plant. The KLT-40 type reactors, with maximum 160 MW thermal power, is used as the power source for such plant. Depending on the customer requirement one or two power unit could be installed in the floating desalination plant. There are APWS-80 with two reactors, producing 80,000 m 3 desalinated water per day and APWS-40 with one reactor, producing 40,000 m 3 desalinated water per day. The advantages of floating desalination plants are the possibility to build and test them at the ship-build plant of the supplier country and to hand them over on turnkey base. (author). 5 figs

  3. Second periodic safety review of Angra Nuclear Power Station, unit 1

    Energy Technology Data Exchange (ETDEWEB)

    Martins, Carlos F.O.; Crepaldi, Roberto; Freire, Enio M., E-mail: ottoncf@tecnatom.com.br, E-mail: emfreire46@gmail.com, E-mail: robcrepaldi@hotmail.com [Tecnatom do Brasil Engenharia e Servicos Ltda, Rio de Janeiro, RJ (Brazil); Campello, Sergio A., E-mail: sacampe@eletronuclear.gov.br [Eletrobras Termonuclear S.A. (ELETRONUCLEAR), Rio de Janeiro, RJ (Brazil)

    2015-07-01

    This paper describes the second Periodic Safety Review (PSR2-A1) of Angra Nuclear Power Station, Unit 1, prepared by Eletrobras Eletronuclear S.A. and Tecnatom do Brasil Engenharia e Servicos Ltda., during Jul.2013-Aug.2014, covering the period of 2004-2013. The site, in Angra dos Reis-RJ, Brazil, comprises: Unit 1, (640 MWe, Westinghouse PWR, operating), Unit 2 (1300 MWe, KWU/Areva, operating) and Unit 3 (1405 MWe, KWU/Areva, construction). The PSR2-A1 attends the Standards 1.26-Safety in Operation of Nuclear Power Plants, Brazilian Nuclear Regulatory Commission (CNEN), and IAEA.SSG.25-Periodic Safety Review of Nuclear Power Plants. Within 18 months after each 10 years operation, the operating organization shall perform a plant safety review, to investigate the evolution consequences of safety code and standards, regarding: Plant design; structure, systems and components behavior; equipment qualification; plant ageing management; deterministic and probabilistic safety analysis; risk analysis; safety performance; operating experience; organization and administration; procedures; human factors; emergency planning; radiation protection and environmental radiological impacts. The Review included 6 Areas and 14 Safety Parameters, covered by 33 Evaluations.After document evaluations and discussions with plant staff, it was generated one General and 33 Specific Guide Procedures, 33 Specific and one Final Report, including: Description, Strengths, Deficiencies, Areas for Improvement and Conclusions. An Action Plan was prepared by Electronuclear for the recommendations. It was concluded that the Unit was operated within safety standards and will attend its designed operational lifetime, including possible life extensions. The Final Report was submitted to CNEN, as one requisite for renewal of the Unit Permanent Operation License. (author)

  4. Second periodic safety review of Angra Nuclear Power Station, unit 1

    International Nuclear Information System (INIS)

    Martins, Carlos F.O.; Crepaldi, Roberto; Freire, Enio M.; Campello, Sergio A.

    2015-01-01

    This paper describes the second Periodic Safety Review (PSR2-A1) of Angra Nuclear Power Station, Unit 1, prepared by Eletrobras Eletronuclear S.A. and Tecnatom do Brasil Engenharia e Servicos Ltda., during Jul.2013-Aug.2014, covering the period of 2004-2013. The site, in Angra dos Reis-RJ, Brazil, comprises: Unit 1, (640 MWe, Westinghouse PWR, operating), Unit 2 (1300 MWe, KWU/Areva, operating) and Unit 3 (1405 MWe, KWU/Areva, construction). The PSR2-A1 attends the Standards 1.26-Safety in Operation of Nuclear Power Plants, Brazilian Nuclear Regulatory Commission (CNEN), and IAEA.SSG.25-Periodic Safety Review of Nuclear Power Plants. Within 18 months after each 10 years operation, the operating organization shall perform a plant safety review, to investigate the evolution consequences of safety code and standards, regarding: Plant design; structure, systems and components behavior; equipment qualification; plant ageing management; deterministic and probabilistic safety analysis; risk analysis; safety performance; operating experience; organization and administration; procedures; human factors; emergency planning; radiation protection and environmental radiological impacts. The Review included 6 Areas and 14 Safety Parameters, covered by 33 Evaluations.After document evaluations and discussions with plant staff, it was generated one General and 33 Specific Guide Procedures, 33 Specific and one Final Report, including: Description, Strengths, Deficiencies, Areas for Improvement and Conclusions. An Action Plan was prepared by Electronuclear for the recommendations. It was concluded that the Unit was operated within safety standards and will attend its designed operational lifetime, including possible life extensions. The Final Report was submitted to CNEN, as one requisite for renewal of the Unit Permanent Operation License. (author)

  5. Damodar Valley Corporation, Chandrapura Unit 2 Thermal Power Station Residual Life Assessment Summary report

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-02-01

    The BHEL/NTPC/PFC/TVA teams assembled at the DVC`s Chadrapura station on July 19, 1994, to assess the remaining life of Unit 2. The workscope was expanded to include major plant systems that impact the unit`s ability to sustain generation at 140 MW (Units 1-3 have operated at average rating of about 90 MW). Assessment was completed Aug. 19, 1994. Boiler pressure parts are in excellent condition except for damage to primary superheater header/stub tubes and economizer inlet header stub tubes. The turbine steam path is in good condition except for damage to LP blading; the spar rotor steam path is in better condition and is recommended for Unit 2. Nozzle box struts are severely cracked from the flame outs; the cracks should not be repaired. HP/IP rotor has surface cracks at several places along the steam seal areas; these cracks are shallow and should be machined out. Detailed component damage assessments for above damaged components have been done. The turbine auxiliary systems have been evaluated; cooling tower fouling/blockage is the root cause for the high turbine back pressure. The fuel processing system is one of the primary root causes for limiting unit capacity. The main steam and hot reheat piping systems were conservatively designed and have at least 30 years left;deficiencies needing resolution include restoration of insulation, replacement of 6 deformed hanger clamp/bolts, and adjustment of a few hanger settings. The cold reheat piping system is generally in good condition; some areas should be re-insulated and the rigid support clamps/bolts should be examined. The turbine extraction piping system supports all appeared to be functioning normally.

  6. Transmutor demo unit and thermal into electrical energy transformation problems

    International Nuclear Information System (INIS)

    Matal, O.; Fiedler, J.

    1999-01-01

    In the three circuits layout of the transmutor the heat is transferred from the primary through the secondary circuits by a favourable heat carrier into the tertiary circuit where the thermal into electrical energy transformation in turbo-generator comes into force. Properties as well as parameters of the heat carrier in the secondary circuit affect basically both the conceptual layout of the tertiary circuit and consequently investments costs for its realization and the effectiveness of the transformation of thermal into electrical energy. For several heat carriers considered for the transmutor secondary circuit particular tertiary circuit concepts for the demonstration transmutor unit of approx. 15 W thermal power rate are analyzed, layout features and possibilities of turbogenerator selection are commented and investment costs as well as effectiveness of thermal into electrical energy transformation are estimated. Some of the results are as follows: (i) Heat carrier properties influence thermodynamics of the TDU water/steam cycle substantially. One of the dominant parameters is the melting (freezing) temperature of the heat carrier. (ii) Heat carrier properties influence investment costs of components of the TDU tertiary circuit substantially. Dominantly influenced are costs of the steam generator, steam turbine and high pressure regeneration system. (iii) If the heat carrier has to be a molten salt than a salt with a low melting temperature is recommended to be selected, for example KHF2. (iv) Eutectic alloy Pb-Bi as the heat carrier serves changes to design the TDU with efficient thermodynamics, with acceptable low investment costs of the tertiary as well as secondary circuit components and with an acceptable level of the nuclear safety

  7. Safety Evaluation Report related to the operation of Limerick Generating Station, Units 1 and 2 (Docket Nos. 50-352 and 50-353). Supplement No. 6

    International Nuclear Information System (INIS)

    1985-08-01

    In August 1983 the staff of the Nuclear Regulatory Commission issued its Safety Evaluation Report (NUREG-0991) regarding the application of the Philadelphia Electric Company (the licensee) for licenses to operate the Limerick Generating Station, Units 1 and 2, located on a site in Montgomery and Chester Counties, Pennsylvania. A license for the operation of Limerick Unit 1 was issued on October 26, 1984. The license, which was restricted to a five percent power level, contained conditions which required resolution prior to proceeding beyond the five percent power level. Supplement 4, issued in May 1985, addressed some of these issues. Supplement 4 also contained the comments made by the Advisory Committee on Reactor Safeguards in its report dated November 6, 1984, regarding full power operation of Limerick Unit 1. Supplement 5, issued in July 1985, and this Supplement 6 address further issues, principally the status of offsite emergency planning, that require resolution prior to proceeding beyond the five percent power level

  8. Analysis of internal events for the Unit 1 of the Laguna Verde nuclear power station

    International Nuclear Information System (INIS)

    Huerta B, A.; Aguilar T, O.; Nunez C, A.; Lopez M, R.

    1993-01-01

    This volume presents the results of the starter event analysis and the event tree analysis for the Unit 1 of the Laguna Verde nuclear power station. The starter event analysis includes the identification of all those internal events which cause a disturbance to the normal operation of the power station and require mitigation. Those called external events stay beyond the reach of this study. For the analysis of the Laguna Verde power station eight transient categories were identified, three categories of loss of coolant accidents (LOCA) inside the container, a LOCA out of the primary container, as well as the vessel break. The event trees analysis involves the development of the possible accident sequences for each category of starter events. Events trees by systems for the different types of LOCA and for all the transients were constructed. It was constructed the event tree for the total loss of alternating current, which represents an extension of the event tree for the loss of external power transient. Also the event tree by systems for the anticipated transients without scram was developed (ATWS). The events trees for the accident sequences includes the sequences evaluation with vulnerable nucleus, that is to say those sequences in which it is had an adequate cooling of nucleus but the remoting systems of residual heat had failed. In order to model adequately the previous, headings were added to the event tree for developing the sequences until the point where be solved the nucleus state. This process includes: the determination of the failure pressure of the primary container, the evaluation of the environment generated in the reactor building as result of the container failure or cracked of itself, the determination of the localization of the components in the reactor building and the construction of boolean expressions to estimate the failure of the subordinated components to an severe environment. (Author)

  9. Volume reduction of filter media at Susquehanna steam and electric station

    International Nuclear Information System (INIS)

    Boris, G.F.; Hettinger, J.

    1990-01-01

    This paper describes the joint efforts between Pennsylvania Power ampersand Light (PPQL) and Scientific Ecology Group, Inc. (SEG) to reduce the volume of waste shipped to the burial site by the Susquehanna Steam and Electric Station (SSES) and the resulting savings realized as a result. The filter media used at SSES for its radwaste filters is composed of a mix of anion and cation powered resins, powered carbon, diatomaceous earth and a fibrous overlay. Due to the nature of this waste stream, dewatering was difficult using systems previously available in the industry. Thus, processing was accomplished by decanting (to concentrate the waste) and solidification. In the continuing effort to dewater wastes of this nature, SEG developed a new fabric filter dewatering system (RDU). To investigate its potential use in large containers, this dewatering system was installed in drum-size high integrity containers and used to test its dewatering capabilities on actual SSES waste. Promising results from these tests warranted a full-scale test. This proved successful and implementation of this processing scheme was immediate. Cost savings were substantial in transportation, burial and processing costs as well as personnel exposure. Also, additional waste volume reduction was found due to the volume reduction capability of the dewatering system (equivalent volume of new filter media approximately 1.2 times that of dewatered product volume). Additional savings resulted from SSES's continuing effort to minimize radwaste generation. Combined, these have reduced the number of shipments of filter media in 1989 to sixty percent of the number made in 1988 and have reduced costs by approximately fifty percent. 4 figs., 1 tab

  10. Electrical Power System Design and Station Blackout (SBO) Management in Indian Fast Breeder Reactors

    International Nuclear Information System (INIS)

    Vijaya, N. M.; Theivarajan, N.; Madhusoodanan, K.

    2015-01-01

    In the nuclear new builds and projects in design stage SBO management measures have significant role. Depending on the onsite and offsite power supply configurations, deterministic SBO duration is established. Design of systems with adequately sized battery capacities for SBO duration, special SBO Diesel Generator Sets, structured load shedding strategy to conserve battery availability to cope with SBO and to monitor the plant safety beyond SBO duration are considered as part of electrical system design now. In the design of PFBR, SBO is given due importance right from conceptual design stage. Both deterministic SBO duration and probabilistic SBO duration versus frequency were established by detailed analysis. Dedicated DC power supply systems and additional SBO DG back-up systems are in place to cope with normal and extended SBO. After the Fukushima event, there is greater requirement to demonstrate plant safety during SBO for a long duration extended over several days. In light of this accident, thermal hydraulic synthesis of PFBR has been carried out to ascertain the capability of the plant to manage a prolonged station blackout event. This has brought out the robustness of the design. Safety design features of PFBR ensure comfortable management of extended SBO. In the design of future FBR projects, current trends in the new nuclear builds and recommendations of international bodies considering Fukushima are duly considered. SBO measures by means of alternate AC power sources, redundant emergency power supply sources with less dependence on other auxiliary systems and dedicated DC power systems are considered to cope with normal and extended SBO beyond design basis. Right from the conceptual design, the system robustness to manage normal and extended SBO will be taken care with the related thermal hydraulic and associated analysis. The paper highlights these SBO management strategies in PFBR and future FBRs. (author)

  11. Outline of Noto Nuclear Power Station, Hokuriku Electric Power Co., Inc

    International Nuclear Information System (INIS)

    1988-01-01

    The location of the power station is in Shiga-cho, Hakui-gun, Ishikawa-ken. One BWR of about 1,600 MWt (540 MWe) capacity is installed. The area of the site is about 1.6 million m 2 , which is on the gentle slope of hilly land at the elevation of about 50 m, and faces Japan Sea. The nuclear reactor proper is installed at the position about 400 m eastward from the coastline. The height of the exhaust stack is about 100 m above the ground. The shortest distance from the center of the reactor core to the boundary of the site is about 450 m in the direction of south and southwest. The objective of use in commercial electric power generation. The start of operation is scheduled in March, 1993. The total cost of construction is about 235 billion yen, which is equivalent to about 435,000 yen-kW. The fuel assemblies are 8 x 8 type, the fuel material is uranium dioxide sintered pellets, and the average degree of enrichment of the initially charged fuel is about 1.6 wt.% in type 1, 2.4 wt.% in type 2 and 3.0 wt.% in type 3 (about 2.3 wt.% on the average). The highest burnup of fuel assemblies is 40,000 MWd-t. The total amount of fuel charged in the core is about 64 t of uranium. The main steam temperature at the reactor exit is 286 deg C, and the feedwater pressure at the reactor entrance is 72 kg-cm 2 g. The steam turbine is a tandem four-flow exhaust condensing turbine of 540 MW output. (Kako, I.)

  12. CNSS plant concept, capital cost, and multi-unit station economics

    Energy Technology Data Exchange (ETDEWEB)

    1984-07-01

    United Engineers and Constructors (UE and C) and the Babcock and Wilcox Company (B and W) have performed several studies over the last eight years related to small integral pressurized water reactors. These reactors include the 365 MWt (100 MWe) Consolidated Nuclear Steam Generator (CNSG) and the 1200 MWt Consolidated Nuclear Steam System (CNSS). The studies, mostly performed under contract to the Oak Ridge National Laboratory, have led to a 1250 MWt (400 MWe) Consolidated Nuclear Steam System (CNSS) plant concept, with unique design and cost features. This report contains an update of earlier studies of the CNSS reactor and balance-of-plant concept design, capital costs, and multi-unit plant economics incorporating recent design developments, improvements, and post-TMI-2 upgrades. The economic evaluation compares the total system economic impact of a phased, three stage 400 MWe CNSS implementation program, i.e., a three-unit station, to the installation of a single 1200 MWe Pressurized Water Reactor (PWR) into a typical USA utility system.

  13. CNSS plant concept, capital cost, and multi-unit station economics

    International Nuclear Information System (INIS)

    1984-07-01

    United Engineers and Constructors (UE and C) and the Babcock and Wilcox Company (B and W) have performed several studies over the last eight years related to small integral pressurized water reactors. These reactors include the 365 MWt (100 MWe) Consolidated Nuclear Steam Generator (CNSG) and the 1200 MWt Consolidated Nuclear Steam System (CNSS). The studies, mostly performed under contract to the Oak Ridge National Laboratory, have led to a 1250 MWt (400 MWe) Consolidated Nuclear Steam System (CNSS) plant concept, with unique design and cost features. This report contains an update of earlier studies of the CNSS reactor and balance-of-plant concept design, capital costs, and multi-unit plant economics incorporating recent design developments, improvements, and post-TMI-2 upgrades. The economic evaluation compares the total system economic impact of a phased, three stage 400 MWe CNSS implementation program, i.e., a three-unit station, to the installation of a single 1200 MWe Pressurized Water Reactor (PWR) into a typical USA utility system

  14. Socio-economic impacts of nuclear generating stations: Crystal River Unit 3 case study

    International Nuclear Information System (INIS)

    Bergmann, P.A.

    1982-07-01

    This report documents a case study of the socio-economic impacts of the construction and operation of the Crystal River Unit 3 nuclear power station. It is part of a major post-licensing study of the socio-economic impacts at twelve nuclear power stations. The case study covers the period beginning with the announcement of plans to construct the reactor and ending in the period 1980 to 1981. The case study deals with changes in the economy, population, settlement patterns and housing, local government and public services, social structure, and public response in the study area during the construction/operation of the reactor. A regional modeling approach is used to trace the impact of construction/operation on the local economy, labor market, and housing market. Emphasis in the study is on the attribution of socio-economic impacts to the reactor or other causal factors. As part of the study of local public response to the construction/operation of the reactor, the effects of the Three Mile Island accident are examined

  15. Fire Stations

    Data.gov (United States)

    Department of Homeland Security — Fire Stations in the United States Any location where fire fighters are stationed or based out of, or where equipment that such personnel use in carrying out their...

  16. Improved grid operation through power smoothing control strategies utilizing dedicated energy storage at an electric vehicle charging station

    DEFF Research Database (Denmark)

    Martinsen, Thomas; Holjevac, Ninoslav; Bremdal, Bernt A.

    2016-01-01

    project (Flex-ChEV) supported by the ERA-Net Smart Grid FP7 program. The principal asset of the proposed charging station (CS) is a dedicated Energy Storage System (ESS) to compensate for adverse effects on the grid caused by peak charging demand and which could impose severe trials for the local DSO....... Furthermore, CS of this kind could serve multiple business purposes in a smart grid. It can serve as a hub for seamless integration of local renewable and distributed energy resources, it can provide added flexibility for the local grid through different ancillary services and it can act as an efficient......This paper addresses the principal service aspects for electric vehicles (EV), as well as issues related to energy storage design, charging station integration into power system and load management issues. It builds on the research conducted in the Flexible Electric Vehicle Charging Infrastructure...

  17. IEEE standard for type test of class 1E electric cables, field splices, and connections for nuclear power generating stations

    International Nuclear Information System (INIS)

    Anon.

    1974-01-01

    The Institute of Electrical and Electronics Engineers has generated this document to provide guidance for developing a program to type test cables, field splices, and connections and obtain specific type test data. It supplements IEEE Std 323-1974 Standard for Qualifying Class IE Equipment for Nuclear Power Generating Stations, which describes basic requirements for equipment qualification. It is the integrated performance of the structures, fluid systems, the electrical systems, the instrumentation systems of the station, and in particular, the plant protection system, that limits the consequences of accidents. Seismic effects on installed cable systems are not within the scope of this document. Section 2 of this guide is an example of type tests. It is the purpose of this guide to deal with cable and connections; however, at the time of issue, detailed examples of tests for connections were not available

  18. Provision of Flexible Load Control by Multi-Flywheel-Energy-Storage System in Electrical Vehicle Charging Stations

    DEFF Research Database (Denmark)

    Sun, Bo; Dragicevic, Tomislav; Andrade, Fabio

    2015-01-01

    in order to support basic electrical operation. This paper proposes a local implementation of a hysteresis-based aggregation algorithm for coordinated control of multiple stations that can provide functions such as peak shaving, spinning reserves, frequency control, regulation and load following. Local......Electrical vehicle (EV) chargers are going to occupy a considerable portion of total energy consumption in the future smart grid. Fast charging stations (FCS), as the most demanding representatives of charging infrastructure, will be requested to provide some ancillary services to the power system...... stability. Finally, corresponding hardware in the loop results based on dSPACE1006 platform have been reported in order to verify the validity of proposed approach....

  19. Costs of producing electricity from nuclear, coal-fired and oil-fired power stations

    International Nuclear Information System (INIS)

    1980-07-01

    The Board publishes generation costs per kW h incurred at recently commissioned power stations so that the costs and performance of nuclear and conventional stations of roughly the same date of construction can be compared. The term 'conventional power station' is used to describe coal-fired and oil-fired steam power stations. The Board has now decided: (A) to supplement the past method of calculating costs at main stations commissioned between 1965 and 1977 by giving the associated figures for interest during construction, for research, and for training; (B) to give similar figures for the contemporary stations Hinkley Point B and the first half of Drax, (C) to provide estimates of generating costs of stations under construction; (D) to set out explicitly the relationship of this method of calculation to that employed in taking investment decisions on future stations. In this way the figures for stations in commission and under construction are arrived at more in line with the general principles of evaluating investment proposals. The present document provides this information. (author)

  20. Transient Processes in Electric Power Supply System for Oil Terminal with Own Gas-Turbine Power Station

    Directory of Open Access Journals (Sweden)

    A. M. Hаshimov

    2009-01-01

    Full Text Available The paper contains results of the investigations concerning influence of symmetrical and non-symmetrical short circuits at main power network on electric power supply system of a huge oil terminal which is powered by own gas-turbine power station. Calculations have been made in accordance with the IEC and IEEЕ requirements. Estimations for voltage level and distribution of short circuit current in the electric power supply system of the Sangachal oil terminal being operated in parallel with the AzerEnerji grid are presented in the paper

  1. Guide to Federal Funding, Financing, and Technical Assistance for Plug-in Electric Vehicles and Charging Stations

    Energy Technology Data Exchange (ETDEWEB)

    None, None

    2016-07-29

    The U.S. Department of Energy and the U.S. Department of Transportation have published a guide to highlight examples of federal support and technical assistance for plug-in electric vehicles (PEVs) and charging stations. The guide provides a description of each opportunity and a point of contact to assist those interested in advancing PEV technology. The Department of Energy’s Alternative Fuels Data Center provides a comprehensive database of federal and state programs that support plug-in electric vehicles and infrastructure.

  2. Summary of plant life management evaluation for Onagawa Nuclear Power Station Unit-1

    International Nuclear Information System (INIS)

    Nodate, Kazumi

    2014-01-01

    The Onagawa Nuclear Power Station Unit-1 (Onagawa NPS-1) began commercial operation on June 1, 1984, and has reached 30-year from starting of operation on June of 2014. To that end, we implemented the Plant Life Management (PLM) evaluation for Onagawa NPS-1 as our first experience. We decided on a Long-term Maintenance Management Policy from result of the evaluation, and then applied the Safety-Regulations change approval application on November 6, 2013 and its correcting application on April 16, 2014. Our application was approved on May 21, 2014 through investigation by the Nuclear Regulatory Agency. Also at implementation of the PLM evaluation, we considered effects of the Great East Japan Earthquake that occurred on March 11, 2011 against ageing phenomena. In this paper, we introduce summary of PLM evaluation for Onagawa NPS-1 and the evaluation that considered effects of the Great East Japan Earthquake. (author)

  3. Radiological Effluent Technical Specifications (RETS) implementation: Zion Generating Station Units 1 and 2

    International Nuclear Information System (INIS)

    Serrano, W.; Akers, D.W.; Duce, S.W.; Mandler, J.W.; Simpson, F.B.; Young, T.E.

    1985-06-01

    A review of the Radiological Effluent Technical Specifications (RETS) of the Zion Generating Station Units 1 and 2 was performed. The principal review guidelines used were NUREG-0133, ''Preparation of Radiological Effluent Technical Specifications for Nuclear Power Plants,'' and Draft 7 of NUREG-0472, Revision 3, ''Radiological Effluent Technical Specifications for Pressurized Water Reactors.'' Draft submittals were discussed with the Licensee by both EG and G and the NRC staff until all items requiring changes to the Technical Specifications were resolved. The Licensee then submitted final proposed RETS to the NRC which were evaluated and found to be in compliance with the NRC review guidelines. The proposed Offsite Dose Calculation Manual was reviewed and generally found to be consistent with the NRC review guidelines. 35 refs., 2 figs., 1 tab

  4. Summary of commissioning of Hamaoka Nuclear Power Station Unit No.5

    International Nuclear Information System (INIS)

    Wakunaga, T.; Sekine, Y.; Yamada, K.; Nakamura, Y.; Kawahara, M.

    2006-01-01

    The Hamaoka Nuclear Power Station Unit No.5 was put into commercial operation in January 2005, which is the 1380 MWe advanced boiling water reactor (ABWR) incorporating design improvements and latest technologies of safer operation, reliability and maintenance. For example, S-FMCRD (Sealless Fine-Motion Control Rod Drive) was equipped to eliminate the use of seal housing by adopting a magnetic coupling and also ASD (Adjustable Speed Drive- the multiple drive power supply to reactor internal pumps) that can drive two or three Recirculation Internal Pumps with a large-capacity inverter. The reactor start-up tests were performed about for eleven months from February 2004 to confirm the plant's required performance including design change points. (T. Tanaka)

  5. Results of the 5th regular inspection of Unit 1 in the Hamaoka Nuclear Power Station

    International Nuclear Information System (INIS)

    1983-01-01

    The 5th regular inspection of Unit 1 in the Hamaoka Nuclear Power Station was carried out from March 27 to July 27, 1982. Inspection was made on the reactor proper, reactor cooling system, instrumentation/control system, radiation control facility, etc. By the examinations of external appearance, leakage, performance, etc., no abnormality was observed. In the regular inspection, personnel exposure dose was all below the permissible level. The works done during the inspection were the following: the replacement of control rod drives, the replacement of core support-plate plugs, the repair of steam piping, steam extraction pipes and feed water heaters, the repair of a waste-liquid concentrator, the installation of barriers and leak detectors, the installation of drain sump monitors in a containment vessel, the replacement of concentrated liquid waste pumps, the employment of type B fuel. (Mori, K.)

  6. MRP-227 Reactor vessel internals inspection planning and initial results at the Oconee nuclear station unit 2

    International Nuclear Information System (INIS)

    Davidsaver, S.B.; Fyfitch, S.; Whitaker, D.E.; Doss, R.L.

    2015-01-01

    The U.S. PWR industry has pro-actively developed generic inspection requirements and standards for reactor vessel (RV) internals. The Electric Power Research Institute (EPRI) Pressurized Water Reactor (PWR) Materials Reliability Program (MRP) has issued MRP-227-A and MRP-228 with mandatory and needed requirements based on the Nuclear Energy Institute (NEI) document NEI 03-08. The inspection and evaluation guidelines contained in MRP-227-A consider eight age-related degradation mechanisms: stress corrosion cracking (SCC), irradiation-assisted stress corrosion cracking (IASCC), wear, fatigue, thermal aging embrittlement, irradiation embrittlement, void swelling and irradiation growth, and thermal and irradiation-enhanced stress relaxation or irradiation-enhanced creep. This paper will discuss the decision planning efforts required for implementing the MRP-227-A and MRP-228 requirements and the results of these initial inspections at the Oconee Nuclear power station (ONS) units. Duke Energy and AREVA overcame a significant technology and NDE challenge by successfully completing the first-of-a-kind MRP-227-A scope requirements at ONS-1 in one outage below the estimated dose and with zero safety issues or events. This performance was repeated at ONS-2 a year later. The remote NDE tooling and processes developed to examine the MRP-227-A scope for ONS-1 and ONS-2 are transferable to other PWRs

  7. Techno-economic and sensitivity analysis for grid-connected renewable energy electric boat charging station in Terengganu

    OpenAIRE

    Salleh N. A. S.; Muda W. M. W.

    2017-01-01

    In order to encourage the eco-friendly technologies in transportation sector, the reliance on fuel need to be reduced and the use of renewable energy (RE) technology as energy source are widely explored by researchers. Thus, this study focus on the feasibility of developing grid-connected renewable energy electric boat charging station for the fishermen in Terengganu using simulation-based method by HOMER software. Five year solar radiation and wind speed data were collected at Universiti Sul...

  8. Neural network based inspection of voids and karst conduits in hydro-electric power station tunnels using GPR

    Science.gov (United States)

    Kilic, Gokhan; Eren, Levent

    2018-04-01

    This paper reports on the fundamental role played by Ground Penetrating Radar (GPR), alongside advanced processing and presentation methods, during the tunnel boring project at a Dam and Hydro-Electric Power Station. It identifies from collected GPR data such issues as incomplete grouting and the presence of karst conduits and voids and provides full details of the procedures adopted. In particular, the application of collected GPR data to the Neural Network (NN) method is discussed.

  9. The contribution of small hydro power stations to the electricity generation in Greece: Technical and economic considerations

    International Nuclear Information System (INIS)

    Kaldellis, J.K.

    2007-01-01

    Hydropower is the most widely used renewable energy source worldwide, contributing almost with 18.5% to the fulfillment of the planet electricity generation. However, most locations in Europe appropriate for the installation of large hydro power stations have already been exploited. Furthermore, there is a significant local communities' opposition towards new large power stations; hence, small hydro power stations remain one of the most attractive opportunities for further utilization of the available hydro potential. Greece and more precisely the country's mainland possesses a significant hydro-power potential which is up to now only partially exploited. In parallel, a large number of private investors have officially expressed their interest in creating small hydro power stations throughout the country, encouraged by the significant Greek State subsidy opportunities for renewable energy applications. However, up to now a relatively small number of projects have been realized, mainly due to decision-making problems, like the administrative bureaucracy, the absence of a rational national water resources management plan and the over-sizing of the proposed installations. Certainly, if the above problems are suitably treated, small hydro-power plants can be proved considerably profitable investments, contributing also remarkably to the national electricity balance and replacing heavy polluting lignite and imported oil. In the context of the above interesting issues, the present study reviews in detail the existing situation of small hydropower plants in Greece and investigates their future prospects as far as the energy, economic and environmental contribution are concerned

  10. 76 FR 73721 - Nine Mile Point Nuclear Station, LLC, Nine Mile Point Nuclear Station, Unit No. 2, Environmental...

    Science.gov (United States)

    2011-11-29

    .... Solid radioactive waste streams include filter sludge, spent ion exchange resin, and dry active waste... Environmental Impact of Transportation of Fuel and Waste to and from One Light-Water-Cooled Nuclear Power... facilities. NMP2 uses a boiling-water reactor and a nuclear steam supply system designed by General Electric...

  11. Papers of 7. Scientific-Technical Seminar Material Study for Electric Power Stations and Energetics

    International Nuclear Information System (INIS)

    2000-01-01

    The report is the assembly of the papers concerning the material problems occurring during the exploitation of power station and gas pipelines. The normalization problems in the power station and in the gas pipelines according to the prescription of UE are also discussed. (author)

  12. Operation of the Millstone Nuclear Power Station, Unit No. 3 (NRC Docket No. 50-423) Northeast Nuclear Energy Company et. al., Waterford, New London County, Connecticut

    International Nuclear Information System (INIS)

    1984-07-01

    A draft version of the environmental impact statement (EPA No. 840331D) concerns the proposal to issue an operating license for Unit 3 of the Millstone Nuclear Power Station on Connecticut. The plant would use a four-loop pressurized water reactor to produce up to 3579 MW of thermal energy and a calculated maximum electric output of 1209 MW of electric power. A new line would require clearing about 350 acres. Positive impacts include the addition of new capacity, which would benefit the area economically and employment opportunities. Negative impacts include the loss of some winter flounder, which would be minimized by a fish return system, and some increases in the concentration of chemical constituents that would enter Long Island Sound. Policies relating to coastal areas, water pollution, and reactor regulation provide a legal mandate for the impact statement

  13. Nuclear power station siting experience in the United Kingdom: past and present and proposals for the future

    International Nuclear Information System (INIS)

    Haire, T.P.; Usher, E.F.F.W.

    1975-01-01

    Foremost of the many factors in site selection considerations are population distribution, cooling-water availability and amenity. Others are safety of potable water sources, geological stability and the risk of external hazards. Where cooling-water supplies are a limiting factor, the choica of reactor system is of major importance. To determine as early as possible the effect a station might have on its environment, desk studies, visual surveys and wind-tunnel tests are carried out. The Central Electricity Generating Board places great importance on obtaining the fullest degree of acceptance by the public for its nuclear stations and ensures that full consultation is provided with the relevant authorities at all stages of power-station development. It also provides public exhibitions, public meetings and liaison with the local inhabitants. Recruitment of station staff where possible from the immediate area of the station and formation of sports and social clubs are two of the practical steps which help to integrate the station into the local community. Whilst the current energy crisis has reinforced the need for a substantial nuclear programme, possible ways of further reducing the impact of nuclear stations on the environment are being considered. The paper concludes that sufficient nuclear sites can be provided for future needs but that continuing effort will be required to ensure public acceptance. (author)

  14. Design and Testing of a Breadboard Electrical Power Control Unit for the Fluid Combustion Facility Experiment

    Science.gov (United States)

    Kimnach, Greg L.; Lebron, Ramon C.

    1999-01-01

    The Fluid Combustion Facility (FCF) Project and the Power Technology Division at the NASA Glenn Research Center (GRC) at Lewis Field in Cleveland, OH along with the Sundstrand Corporation in Rockford, IL are jointly developing an Electrical Power Converter Unit (EPCU) for the Fluid Combustion Facility to be flown on the International Space Station (ISS). The FCF facility experiment contains three racks: A core rack, a combustion rack, and a fluids rack. The EPCU will be used as the power interface to the ISS 120V(sub dc) power distribution system by each FCF experiment rack which requires 28V(sub dc). The EPCU is a modular design which contains three 120V(sub dc)-to-28V(sub dc) full-bridge, power converters rated at 1 kW(sub e) each bus transferring input relays and solid-state, current-limiting input switches, 48 current-limiting, solid-state, output switches; and control and telemetry hardware. The EPCU has all controls required to autonomously share load demand between the power feeds and--if absolutely necessary--shed loads. The EPCU, which maximizes the usage of allocated ISS power and minimizes loss of power to loads, can be paralleled with other EPCUs. This paper overviews the electrical design and operating characteristics of the EPCU and presents test data from the breadboard design.

  15. Projected costs of generating electricity from power stations for commissioning in the period 1995-2000

    International Nuclear Information System (INIS)

    1989-01-01

    The study reviews the projected electricity generation costs for the base load power generation options expected to be available in the medium term, using an agreed common economic methodology. Cost projections were obtained for nuclear and fossil fuelled plants that could in principle be commissioned in the mid-1990s, or shortly thereafter, although not all countries plan to commission plants at that time. The major changes in expectations compared with earlier studies, apart from those associated with changed perceptions of fossil fuel prices, include significantly lower nuclear investment costs for the United States, associated with an improved design and the expectation of achieving shorter construction periods than projected in the 1985 study, and generally lower nuclear fuel costs. Some countries project higher operation and maintenance costs for either coal-fired or nuclear plant or both. In the case of coal-fired plants these may be associated with the extra costs of operating desulphurisation equipment. The most marked change in nuclear operating and maintenance costs has taken place in the United States, where these costs are now expected to be twice as large as the projected nuclear fuel costs. There remain major differences in investment cost expectations between countries. The reasons for these differences have been examined in previous studies. They arise from differences in factor costs, regulatory approach, design and siting, and exchange rates which do not adequately reflect the differences in the capital investment costs between countries. In brief, most OECD countries continue to expect nuclear power to have a lower levelised generating cost than coal-fired generation when using their own technical and economic assumptions

  16. Montague Nuclear Power Station, Units 1 and 2: Final environmental statement (Docket Nos. 50-496 and 50-497)

    International Nuclear Information System (INIS)

    1977-02-01

    The proposed action is the issuance of construction permits to the Northeast Nuclear Energy Company for the construction of the Montague Nuclear Power Station, Units 1 and 2, located on the Connecticut River in the Town of Montague, Massachusetts. The plant will employ two identical boiling-water reactors to produce up to 3579 megawatts thermal (MWt) each. Two steam turbine-generators will use this heat to provide 1150 MWe (net) of electrical power capacity from each turbine-generator. A design power level of 3759 MWt (1220 Mwe net) for each unit is anticipated at a future date and is considered in the assessments contained in this statement. The waste heat will be rejected through natural-draft cooling towers using makeup water obtained from and discharged to the Connecticut River. The 1900-acre site is about 90% forest, with the remaining acreage in transmission-line corridor and old-field vegetation. The total loss of mixed-age forest will be 1273 acres. Nodesignated scenic areas will be crossed. Sixty acres of public lands, State forests, and parks will be lost to transmission facilities as well as losses associated with crossings of 2.0 miles of water bodies and 11.9 miles of wetlands. The maximum estimated potential loss of salable wood products will be $849,600. A maximum of 85.8 cfs of cooling water will be withdrawn from the Connecticut River. A maximum of 17.2 cfs will be returned to the river with the dissolved solids concentration increased by a factor of about 5. A maximum of 68.6 cfs will be evaporated to the atmosphere by the cooling towers. 143 refs., 58 figs., 69 tabs

  17. Lessons learned from the seismic reevaluation of San Onofre Nuclear Generating Station, Unit 1

    International Nuclear Information System (INIS)

    Russell, M.J.; Shieh, L.C.; Tsai, N.C.; Cheng, T.M.

    1987-01-01

    A seismic reevaluation program was conducted for the San Onofre Nuclear Generating Station, Unit No. 1 (SONGS 1). SEP was created by the NRC to provide (1) an assessment of the significance of differences between current technical positions on safety issues and those that existed when a particular plant was licensed, (2) a basis for deciding on how these differences should be resolved in an integrated plant review, and (3) a documented evaluation of plant safety. The Systematic Evaluation Program (SEP) seismic review for SONGS 1 was exacerbated by the results of an evaluation of an existing capable fault near the site during the design review for Units 2 and 3, which resulted in a design ground acceleration of 0.67g. Southern California Edison Company (SCE), the licensee for SONGS 1, realized that a uniform application of existing seismic criteria and methods would not be feasible for the upgrading of SONGS 1 to such a high seismic requirement. Instead, SCE elected to supplement existing seismic criteria and analysis methods by developing criteria and methods closer to the state of the art in seismic evaluation techniques

  18. Manufacture of steam generator units and components for the AGR power stations at Heysham II and Torness

    Energy Technology Data Exchange (ETDEWEB)

    Glasgow, J R; Parkin, K [N.E.I. Nuclear Systems Ltd., Gateshead, Tyne and Wear (United Kingdom)

    1984-07-01

    The current AGR Steam Generator is a development of the successful once-through units supplied for the Oldbury Magnox and Hinkley B/Hunterston B AGR power stations. In this paper a brief outline of the evolution of the steam generator design from the earlier gas cooled reactor stations is presented. A description of the main items of fabrication development is given. The production facilities for the manufacture of the units are described. Reference is also made to some of the work on associated components. The early experience on the construction site of installation of the steam generators is briefly outlined. (author)

  19. Manufacture of steam generator units and components for the AGR power stations at Heysham II and Torness

    International Nuclear Information System (INIS)

    Glasgow, J.R.; Parkin, K.

    1984-01-01

    The current AGR Steam Generator is a development of the successful once-through units supplied for the Oldbury Magnox and Hinkley B/Hunterston B AGR power stations. In this paper a brief outline of the evolution of the steam generator design from the earlier gas cooled reactor stations is presented. A description of the main items of fabrication development is given. The production facilities for the manufacture of the units are described. Reference is also made to some of the work on associated components. The early experience on the construction site of installation of the steam generators is briefly outlined. (author)

  20. Ring thermal shield piping modification at Pickering Nuclear Generating Station 'A' Unit 1

    International Nuclear Information System (INIS)

    Brown, R.; Cobanoglu, M.M.

    1995-01-01

    Each of the four Pickering Nuclear Generating Station A (PNGSA) CANDU units was constructed with its reactor and dump tank surrounded by a concrete Calandria Vault (CV). The Ring Thermal Shield (RTS) system at PNGSA units is a water cooled structure with internal cooling channels with the purpose of attenuating excessive heat flux from the calandria shell to the end shield rings and adjoining concrete (Figure 1). In newer CANDU units the reactor calandria vessel is surrounded by a large water filled shield tank which eliminates the requirement for the RTS system. The RTS structures are situated in the space between the calandria and the vault walls. Each RTS is assembled from eight flat sided carbon steel segments, tilted towards the calandria and supported from the end shield rings. Cooling water to the RTS is supplied by carbon steel cooling pipes with a portion of the pipe run embedded in the vault walls. Flow through each RTS is divided into two independent circuits, having an inlet and an outlet cooling line. There are four locations of RTS inlet and outlet cooling lines. The inlet lines are located at the bottom and the outlet lines at the top of the RTS. The 'L' shaped section of RTS inlet and outlet cooling lines, from the RTS waterbox to the start of embedded portion at the concrete wall, had become defective due to corrosion induced by excessive Moisture levels in the calandria vaults. An on-line leak sealing capability was developed and placed in service in all four PNGSA units. However, a leak found during the 1994 Unit 1 outage was too large,to seal with the current capability, forcing Ontario Hydro (OH) to develop a method to replace the corroded pipes. The repair project was subject to some lofty performance targets. All tools had to be able to withstand dose rates of up to 3000 Rem/hour. These tools, along with procedures and personnel had to successfully repair the RTS system within 6 months otherwise a costly outage extension would result. This

  1. Reserving Charging Decision-Making Model and Route Plan for Electric Vehicles Considering Information of Traffic and Charging Station

    Directory of Open Access Journals (Sweden)

    Haoming Liu

    2018-04-01

    Full Text Available With the advance of battery energy technology, electric vehicles (EV are catching more and more attention. One of the influencing factors of electric vehicles large-scale application is the availability of charging stations and convenience of charging. It is important to investigate how to make reserving charging strategies and ensure electric vehicles are charged with shorter time and lower charging expense whenever charging request is proposed. This paper proposes a reserving charging decision-making model for electric vehicles that move to certain destinations and need charging services in consideration of traffic conditions and available charging resources at the charging stations. Besides, the interactive mechanism is described to show how the reserving charging system works, as well as the rolling records-based credit mechanism where extra charges from EV is considered to hedge default behavior. With the objectives of minimizing driving time and minimizing charging expenses, an optimization model with two objective functions is formulated. Then the optimizations are solved by a K shortest paths algorithm based on a weighted directed graph, where the time and distance factors are respectively treated as weights of corresponding edges of transportation networks. Case studies show the effectiveness and validity of the proposed route plan and reserving charging decision-making model.

  2. Stationary Charging Station Design for Sustainable Urban Rail Systems: A Case Study at Zhuzhou Electric Locomotive Co., China

    Directory of Open Access Journals (Sweden)

    Heng Li

    2015-01-01

    Full Text Available In 2014, more than 43 cities in China were racing to construct their urban rail systems (including metro and light rail systems, recognizing that an urban rail system will be a good solution to the tough problems that they are faced with, including traffic congestion and PM2.5 air pollution. On 22 August 2012, the first electric double-layer capacitor (EDLC energy storage-type rail vehicle in the world was unveiled at Zhuzhou Electric Locomotive Co., China. The EDLC rail system has been considered a promising sustainable urban rail system, which is expected to further improve the energy efficiency and to reduce environmental pollution. The first commercial EDLC tram produced by Zhuzhou Electric Locomotive Co. has been applied at Guangzhou Metro Corp. recently. From the view point of scientific research, the system design and energy management of EDLC rail systems have been extensively studied in the literature, while the stationary charging station design for the EDLC energy storage-type urban rail vehicles has been rarely reported. Thus, the aim of this paper is to report a stationary charging station that has been successfully applied in the EDLC rail system produced by Zhuzhou Electric Locomotive Co., China.

  3. Interleaved neuromuscular electrical stimulation: Motor unit recruitment overlap.

    Science.gov (United States)

    Wiest, Matheus J; Bergquist, Austin J; Schimidt, Helen L; Jones, Kelvin E; Collins, David F

    2017-04-01

    In this study, we quantified the "overlap" between motor units recruited by single pulses of neuromuscular electrical stimulation (NMES) delivered over the tibialis anterior muscle (mNMES) and the common peroneal nerve (nNMES). We then quantified the torque produced when pulses were alternated between the mNMES and nNMES sites at 40 Hz ("interleaved" NMES; iNMES). Overlap was assessed by comparing torque produced by twitches evoked by mNMES, nNMES, and both delivered together, over a range of stimulus intensities. Trains of iNMES were delivered at the intensity that produced the lowest overlap. Overlap was lowest (5%) when twitches evoked by both mNMES and nNMES produced 10% peak twitch torque. iNMES delivered at this intensity generated 25% of maximal voluntary dorsiflexion torque (11 Nm). Low intensity iNMES leads to low overlap and produces torque that is functionally relevant to evoke dorsiflexion during walking. Muscle Nerve 55: 490-499, 2017. © 2016 Wiley Periodicals, Inc.

  4. Electrical. Teacher's Guide. Building Maintenance Units of Instruction.

    Science.gov (United States)

    East Texas State Univ., Commerce. Occupational Curriculum Lab.

    This teaching guide on electrical building maintenance, one in a series of six publications designed for building maintenance instructors in Texas, is designed to give students an understanding of electricity in order to know how to make basic repairs to the electrical systems in a building. Introductory material provides teachers with information…

  5. Safety Evaluation Report related to the operation of Cartawba Nuclear Station, Units 1 and 2 (Docket Nos. 50-413 and 50-414). Supplement No. 5

    International Nuclear Information System (INIS)

    1986-02-01

    This report supplements the Safety Evaluation Report (NUREG-0954) issued in February 1983 by the Office of Nuclear Reactor Regulation of the US Nuclear Regulatory Commission with respect to the application filed by Duke Power Company, North Carolina Municipal Power Agency Number 1, North Carolina Membership Corporation, Saluda River Electric Cooperative, Inc., and Piedmont Municipal Power Agency, as applicants and owners, for licenses to operate the Catawba Nuclear Station, Units 1 and 2 (Docket Nos. 50-413 and 50-414, respectively). The facility is located in York County, South Carolina, approximately 9.6 km (6 mi) north of Rock Hill and adjacent to Lake Wylie. This supplement provides additional information supporting the license for initial criticality and power ascension to full-power operation for Unit 2

  6. Safety evaluation report related to the operation of Catawba Nuclear Station, Units 1 and 2 (Docket Nos. 50-413 and 50-414)

    International Nuclear Information System (INIS)

    1984-07-01

    The report supplements the Safety Evaluation Report (NUREG-0954) issued in February 1983 by the Office of Nuclear Reactor Regulation of the US Nuclear Regulatory Commission with respect to the application filed by Duke Power Company, North Carolina Municipal Power Agency Number 1, North Carolina Membership Corporation, and Saluda River Electric Cooperative, Inc. as applicants and owners, for licenses to operate the Catawba Nuclear Station, Units 1 and 2 (Docket Nos. 50-413 and 50-414, respectively). The facility is located in York County, South Carolina, approximately 9.6 km (6 mi) north of Rock Hill and adjacent to Lake Wylie. This supplement provides additional information supporting the license for fuel loading and precriticality testing for Unit 1

  7. Safety Evaluation Report related to the operation of Limerick Generating Station, Units 1 and 2 (Docket Nos. 50-352 and 50-353). Supplement 3

    International Nuclear Information System (INIS)

    1984-10-01

    In August 1983 the staff of the Nuclear Regulatory Commission issued its Safety Evaluation Report (NUREG-0991) regarding the application of the Philadelphia Electric Company (the applicant) for licenses to operate the Limerick Generating Station, Units 1 and 2. Supplement 1 was issued in December 1983 and addressed several outstanding issues. Supplement 1 also contains the comments made by the Advisory Committee on Reactor Safeguards in its report dated October 18, 1983. Supplement 2 was issued in October 1984 and addressed fourteen outstanding and fifty-three confirmatory issues and closed them put. This Supplement 3 addresses the remaining issues that require resolution before issuance of the operating license for Unit 1 and closes them out

  8. Safety evaluation report related to the operation of Catawba Nuclear Station, Units 1 and 2 (Docket Nos. 50-413 and 50-414)

    International Nuclear Information System (INIS)

    1984-12-01

    This report supplements the Safety Evaluation Report (NUREG-0954) issued in February 1983 by the Office of Nuclear Reactor Regulation of the US Nuclear Regulatory Commission with respect to the application filed by Duke Power Company, North Carolina Municipal Power Agency Number 1, North Carolina Membership Corporation, and Saluda River Electric Cooperative, Inc., as applicants and owners, for licenses to operate the Catawba Nuclear Station, Units 1 and 2 (Docket Nos. 50-413 and 50-414, respectively). The facility is located in York County, South Carolina, approximately 9.6 km (6 mi) north of Rock Hill and adjacent to Lake Wylie. This supplement provides additional information supporting the license for initial criticality and power ascension to full-power opertion for Unit 1

  9. Safety Evaluation Report related to the operation of Catawba Nuclear Station, Units 1 and 2 (Docket Nos. 50-413 and 50-414). Supplement No. 6

    International Nuclear Information System (INIS)

    1986-05-01

    This report supplements the Safety Evaluation Report (NUREG-0954) issued in February 1983 by the Office of Nuclear Reactor Regulation of the US Nuclear Regulatory Commission with respect to the application filed by Duke Power Company, North Carolina Municipal Power Agency Number 1, North Carolina Membership Corporation, Saluda River Electric Cooperative, Inc., and Piedmont Municipal Power Agency, as applicants and owners, for licenses to operate the Catawba Nuclear Station, Units 1 and 2 (Docket Nos. 50-413 and 50-414, respectively). The facility is located in York County, South Carolina, approximately 9.6 km (6 miles) north of Rock Hill and adjacent to Lake Wylie. This supplement provides additional information supporting the license for operation above 5% power and power ascension to full-power operation for Unit 2

  10. Results of evaluation of periodic safety review for No. 1 plant in Mihama Power Station, Kansai Electric Power Co., Inc

    International Nuclear Information System (INIS)

    1994-01-01

    No. 1 plant in Mihama Power Station started the commercial power generation in November, 1970, and has continued the operation for more than 23 years. During this period, the counter measures to troubles, periodic inspections and the maintenance by the electric power company have been carried out. These states of No. 1 plant in Mihama Power Station for more than 23 years are to be recollected from the view-points of the comprehensive evaluation of operation experiences and the reflection of latest technological knowledge, and the safety and reliability are to be further improved in the periodic safety review. Agency of Natural Resources and Energy evaluated the report of the periodic safety review for No. 1 plant in Mihama Power Station made by Kansai Electric Power Co., and summarized the results. The course of the evaluation of the report is shown. The facility utilization factor is 43.3% on the average of about 23 years, but in the last 10 years, it was improved to 69.4%. In the last five years, the rate of occurrence of unexpected shutoff was 0.6 times/year. These are the results of preventive maintenance and the improvement of the facilities and operation management. Operation management, maintenance management, fuel management, radiation control, and radioactive waste management have been carried out properly. The work plan for preventing disasters was established, and the experience of troubles and the latest technological knowledge were well reflected to improve the safety. (K.I.)

  11. Load demand profile for a large charging station of a fleet of all-electric plug-in buses

    Directory of Open Access Journals (Sweden)

    Mario A. Rios

    2014-08-01

    Full Text Available This study proposes a general procedure to compute the load demand profile from a parking lot where a fleet of buses with electric propulsion mechanisms are charged. Such procedure is divided in three different stages, the first one models the daily energy utilisation of the batteries based on Monte Carlo simulations and route characteristics. The second one models the process in the charging station based on discrete event simulation of queues of buses served by a lot of available chargers. The third step computes the final demand profile in the parking lot because of the charging process based on the power consumption of batteries’ chargers and the utilisation of the available charges. The proposed procedure allows the computation of the number of required batteries’ chargers to be installed in a charging station placed at a parking lot in order to satisfy and ensure the operation of the fleet, the computation of the power demand profile and the peak load and the computation of the general characteristics of electrical infrastructure to supply the power to the station.

  12. Systematic evaluation program review of NRC Safety Topic VI-10.A associated with the electrical, instrumentation and control portions of the testing of reactor trip system and engineered safety features, including response time for the Dresden station, Unit II nuclear power plant

    International Nuclear Information System (INIS)

    St Leger-Barter, G.

    1980-11-01

    This report documents the technical evaluation and review of NRC Safety Topic VI-10.A, associated with the electrical, instrumentation, and control portions of the testing of reactor trip systems and engineered safety features including response time for the Dresden II nuclear power plant, using current licensing criteria

  13. Use of Physio-Hydrological Units for SMOS Validation at the Valencia Anchor Station Study Area

    Science.gov (United States)

    Millán-Scheiding, C.; Antolín, C.; Marco, J.; Soriano, M. P.; Torre, E.; Requena, F.; Carbó, E.; Cano, A.; Lopez-Baeza, E.

    2009-04-01

    The SMOS space mission will soil moisture over the continents and ocean surface salinity with the sufficient resolution to be used in global climate change studies. With the aim of validating SMOS land data and products at the Valencia Anchor Station site (VAS) in a Mediterranean Ecosystem area of Spain, we have designed a sample methodology using a subdivision of the landscape in environmental units related to the spatial variability of soil moisture (Millán-Scheiding, 2006; Lopez-Baeza, et al. 2008). These physio-hydrological units are heterogeneously structured entities which present a certain degree of internal uniformity of hydrological parameters. The units are delimited by integrating areas with the same physio-morphology, soil type, vegetation, geology and topography (Flugel, et al 2003; Millán-Scheiding et al, 2007). Each of these units presented over the same pedological characteristics, vegetation cover, and landscape position should have a certain degree of internal uniformity in its hydrological parameters and therefore similar soil moisture (SM). The main assumption for each unit is that the dynamical variation of the hydrological parameters within one unit should be minimum compared to the dynamics of another unit. This methodology will hopefully provide an effective sampling design consisting of a reduced number of measuring points, sparsely distributed over the area, or alternatively, using SM validation networks where each sampling point is located where it is representative of the mean soil moisture of a complete unit area. The Experimental Plan for the SMOS Validation Rehearsal Campaign at the VAS area of April-May 2008 used this environmental subdivision in the selection and sampling of over 21.000 soil moisture points in a control area of 10 x 10 km2. The ground measurements were carried out during 4 nights corresponding to a drying out period of the soil. The sampling consisted of 700 plots with 4 volumetric SM cylinders and 7 Delta-T Theta

  14. Final Environmental Statement related to the operation of Beaver Valley Power Station, Unit 2 (Docket No. 50-412)

    International Nuclear Information System (INIS)

    1985-09-01

    This Final Environmental Statement contains the second assessment of the environmental impact associated with Beaver Valley Power Station Unit 2 pursuant to the National Environmental Policy Act of 1969 (NEPA) and Title 10 of the Code of Federal Regulations, Part 51, as amended, of the Nuclear Regulatory Commission regulations. This statement examines the environment, environmental consequences and mitigating actions, and environmental benefits and costs, and concludes that the action called for is the issuance of an operating license for Beaver Valley Unit 2

  15. Experimental study of camel powered electricity generation unit

    Science.gov (United States)

    Jakhar, O. P.; Choudhary, Rahul Raj; Budaniya, Mukesh; Kumar, Ashish

    2018-05-01

    Developing nations are facing a huge gap in generation and demand of electricity across the world. In present scenario the demand of electricity is increasing day by day and the shortfall of electricity has become one of the major obstructions in the development of rural areas. There is a big gap between electricity supply and demand. In India it is very difficult that to give twenty four hours electric supply in rural areas. The traditional use of camel as draught animal, for the purpose of transport of goods and agricultural work, has been drastically reduced during last few decades, due to advancements and cheaper availability of mechanical machineries. In this research paper we experimentally studied the camel powered electricity generation system at National Research Centre on Camels (NRCC) Bikaner. Camel Energy in form of high torque low speed can be converted into low torque high speed through motion converting system i.e. gear and pulley mechanism for high RPM output. This high RPM (more than 3000) output is used for electricity generation. The electricity generated can be used directly or stored in the battery and later may be used whenever it is required either for DC light or AC light using inverter. According to experimental study a camel can comfortably generate electricity up to 1KW by rotating shaft. The complete set up for electricity generation using camel power has been designed, developed and physically commissioned at National Research Centre on Camels (NRCC) Bikaner.

  16. 75 FR 13606 - Arizona Public Service Company, Palo Verde Nuclear Generating Station, Units 1, 2, and 3...

    Science.gov (United States)

    2010-03-22

    ... NUCLEAR REGULATORY COMMISSION [Docket Nos. STN 50-528, STN 50-529, and STN 50-530; NRC-2010-0114] Arizona Public Service Company, Palo Verde Nuclear Generating Station, Units 1, 2, and 3; Environmental...-74, issued to Arizona Public Service Company (APS, the licensee), for operation of the Palo Verde...

  17. 75 FR 53985 - Arizona Public Service Company, et al., Palo Verde Nuclear Generating Station, Unit 3; Temporary...

    Science.gov (United States)

    2010-09-02

    ... NUCLEAR REGULATORY COMMISSION [Docket No. STN 50-530; NRC-2010-0281] Arizona Public Service Company, et al., Palo Verde Nuclear Generating Station, Unit 3; Temporary Exemption 1.0 Background Arizona Public Service Company (APS, the licensee) is the holder of Facility Operating License No. NPF-74, which...

  18. 76 FR 79228 - Combined Licenses at William States Lee III Nuclear Station Site, Units 1 and 2; Duke Energy...

    Science.gov (United States)

    2011-12-21

    ... NUCLEAR REGULATORY COMMISSION [Docket Nos. 52-018 and 52-019; NRC-2008-0170] Combined Licenses at William States Lee III Nuclear Station Site, Units 1 and 2; Duke Energy Carolinas, LLC AGENCY: Nuclear.... SUMMARY: Notice is hereby given that the U.S. Nuclear Regulatory Commission (NRC) and the U.S. Army Corps...

  19. 78 FR 77508 - Duke Energy Carolinas, LLC; William States Lee III Nuclear Station, Units 1 and 2; Combined...

    Science.gov (United States)

    2013-12-23

    ... NUCLEAR REGULATORY COMMISSION [Docket Nos. 52-018 and 52-019; NRC-2008-0170] Duke Energy Carolinas, LLC; William States Lee III Nuclear Station, Units 1 and 2; Combined Licenses Application Review AGENCY: Nuclear Regulatory Commission. ACTION: Final environmental impact statement; availability...

  20. 78 FR 40200 - Duke Energy Carolinas, LLC, Oconee Nuclear Station Units 1, 2, and 3; Independent Spent Fuel...

    Science.gov (United States)

    2013-07-03

    ... NUCLEAR REGULATORY COMMISSION [Docket Nos. 72-1004, 72-40, 50-269, 50-270, and 50-287; NRC-2013-0135] Duke Energy Carolinas, LLC, Oconee Nuclear Station Units 1, 2, and 3; Independent Spent Fuel Storage Installation; Environmental Assessment and Finding of No Significant Impact AGENCY: Nuclear...

  1. 78 FR 45575 - Duke Energy Carolinas, LLC; Oconee Nuclear Station Units 1, 2, and 3; Independent Spent Fuel...

    Science.gov (United States)

    2013-07-29

    ... NUCLEAR REGULATORY COMMISSION [Docket Nos.: 72-1004, 72-40, 50-269, 50-270, 50-287; and NRC-2013- 0135] Duke Energy Carolinas, LLC; Oconee Nuclear Station Units 1, 2, and 3; Independent Spent Fuel Storage Installation AGENCY: Nuclear Regulatory Commission. ACTION: Exemption; issuance. SUMMARY: The NRC...

  2. Technical Specifications: Clinton Power Station, Unit No. 1 (Docket No. 50-461): Appendix ''A'' to License No. NPF-62

    International Nuclear Information System (INIS)

    1987-04-01

    The Clinton Power Station, Unit No. 1 Technical Specifications were prepared by the US Nuclear Regulatory Commission to set forth limits, operating conditions, and other requirements applicable to a nuclear reactor facility as set forth in Section 50.36 of 10 CFR 50 for the protection of the health and safety of the public

  3. Technical Specifications, Seabrook Station, Unit 1 (Docket No. 50-443): Appendix ''A'' to License No. NPF-67

    International Nuclear Information System (INIS)

    1989-05-01

    The Seabrook Station, Unit 1 Technical Specifications were prepared by the US Nuclear Regulatory Commission to set forth the limits, operating conditions, and other requirements applicable to a nuclear reactor facility as set forth in Section 50.36 of 10 CFR Part 50 for the protection of the health and safety of the public

  4. Safety evaluation report related to the operation of Shoreham Nuclear Power Station, Unit No. 1. Docket No. 50-322

    International Nuclear Information System (INIS)

    1983-02-01

    Supplement No. 3 to the Safety Evaluation Report of Long Island Lighting Company's application for a license to operate the Shoreham Nuclear Power Station, Unit 1, located in Suffolk County, New York, has been prepared by the Office of Nuclear Reactor Regulation of the US Nuclear Regulatory Commission. This supplement addresses several items that have come to light since the previous supplement was issued

  5. Draft Environmental Statement related to the operation of Beaver Valley Power Station, Unit 2 (Docket No. 50-412)

    International Nuclear Information System (INIS)

    1984-12-01

    This Draft Environmental Statement contains the second assessment of the environmental impact associated with Beaver Valley Power Station Unit 2 pursuant to the National Environmental Policy Act of 1969 (NEPA) and Title 10 of the Code of Federal Regulations, Part 51, as amended, of the Nuclear Regulatory Commission regulations. This statement examines the environment, environmental consequences and mitigating actions, and environmental benefits and costs

  6. Station blackout transient at the Browns Ferry Unit 1 Plant: a severe accident sequence analysis (SASA) program study

    International Nuclear Information System (INIS)

    Schultz, R.R.

    1982-01-01

    Operating plant transients are of great interest for many reasons, not the least of which is the potential for a mild transient to degenerate to a severe transient yielding core damage. Using the Browns Ferry (BF) Unit-1 plant as a basis of study, the station blackout sequence was investigated by the Severe Accident Sequence Analysis (SASA) Program in support of the Nuclear Regulatory Commission's Unresolved Safety Issue A-44: Station Blackout. A station blackout transient occurs when the plant's AC power from a comemrcial power grid is lost and cannot be restored by the diesel generators. Under normal operating conditions, f a loss of offsite power (LOSP) occurs [i.e., a complete severance of the BF plants from the Tennessee Valley Authority (TVA) power grid], the eight diesel generators at the three BF units would quickly start and power the emergency AC buses. Of the eight diesel generators, only six are needed to safely shut down all three units. Examination of BF-specific data show that LOSP frequency is low at Unit 1. The station blackout frequency is even lower (5.7 x 10 - 4 events per year) and hinges on whether the diesel generators start. The frequency of diesel generator failure is dictated in large measure by the emergency equipment cooling water (EECW) system that cools the diesel generators

  7. Conformance to Regulatory Guide 1.97, Beaver Valley Power Station, Unit No. 2 (Docket No. 50-412)

    International Nuclear Information System (INIS)

    Stoffel, J.W.; Udy, A.C.

    1985-11-01

    This EG and G Idaho, Inc., report reviews the submittals for Regulatory Guide 1.97 for Unit No. 2 of the Beaver Valley Power Station and identifies areas of nonconformance to the regulatory guide. Exceptions to Regulatory Guide 1.97 are evaluated and those areas where sufficient basis for acceptability is not provided are identified

  8. 77 FR 35079 - License Renewal Application for Seabrook Station, Unit 1 ; NextEra Energy Seabrook, LLC

    Science.gov (United States)

    2012-06-12

    ... NUCLEAR REGULATORY COMMISSION [Docket No. 50-443; NRC-2010-0206] License Renewal Application for Seabrook Station, Unit 1 ; NextEra Energy Seabrook, LLC AGENCY: Nuclear Regulatory Commission. ACTION: License renewal application; intent to prepare supplement to draft [[Page 35080

  9. 78 FR 29158 - In the Matter of Zion Solutions, LLC; Zion Nuclear Power Station, Units 1 and 2; Order Approving...

    Science.gov (United States)

    2013-05-17

    ... and DPR-48] In the Matter of Zion Solutions, LLC; Zion Nuclear Power Station, Units 1 and 2; Order... formed for the purpose of acquiring ES, Inc. and is held by certain investment fund entities organized by... Environmental Management Programs, in writing, of such receipt no later than one (1) business day prior to the...

  10. 78 FR 22347 - GPU Nuclear Inc., Three Mile Island Nuclear Power Station, Unit 2, Exemption From Certain...

    Science.gov (United States)

    2013-04-15

    ... NUCLEAR REGULATORY COMMISSION [Docket No. 50-320; NRC-2013-0065] GPU Nuclear Inc., Three Mile Island Nuclear Power Station, Unit 2, Exemption From Certain Security Requirements AGENCY: Nuclear... and State Materials and Environmental Management Programs, U.S. Nuclear Regulatory Commission...

  11. Conformance to Regulatory Guide 1.97, River Bend Station, Unit No. 1 (Docket No. 50-458)

    International Nuclear Information System (INIS)

    Udy, A.C.

    1985-08-01

    This EG and G, Inc., report reviews the submittals for Regulatory Guide 1.97, Revision 3, for the River Bend Station, Unit No. 1. Any exception to Regulatory Guide 1.97 is evaluated and those areas where sufficient basis for acceptability is not provided are identified. 8 refs

  12. Effects of the Chernobyl and Fukushima nuclear accidents on atmospheric electricity parameters recorded at Polish observation stations

    Science.gov (United States)

    Kubicki, Marek; Baranski, Piotr; Odzimek, Anna; Michnowski, Stanislaw; Myslek-Laurikainen, Bogna

    2013-04-01

    We analyse the atmospheric electricity parameters, measured at Polish geophysical stations in Swider, Poland, and Hornsund, Spitsbergen, in connection with the radioactive incident in Fukushima, Japan, beginning on 11 March 2011, following the 9.0 earthquake and tsunami. We compare our results with the situation during and after the Chernobyl disaster on April 26, 1986, when the radioactive fallout detected at Swider increased in the last week of April 1986, from 4.111 to 238.7 Bq/m2 and up to 967.0 Bq/m2 in the second week of May 1986 - what was more than 235 times greater than the values measured prior to that accident. Besides the electric field especially the electric conductivity is very sensitive to the radioactive contamination of the air. Thus we postulate that these two measurements should be run at geophysical stations over the world and used as a relatively simple and low-cost tool for continuous monitoring of possible hazard caused by nuclear power plant accidents.

  13. Aseismatic design of electrical equipments and instruments for nuclear power stations

    International Nuclear Information System (INIS)

    Suzuki, Yasuharu; Nishizawa, Kazuo; Miyazaki, Yoshio; Miura, Takumi

    1977-01-01

    The aseismatic design of electrical instruments is carried out according to IEEE Standard 344-1971 in the USA. In Japan also, the method of aseismatic design of electrical instruments has been investigated by the representatives of electric power companies and electric machine makers since 1972. In Hitachi Ltd., the statical method of confirming aseismatic property was established on the basis of the rigid design for electrical instruments. It is convenient to examine the aseismatic property of electrical equipments by classifying them into control and switch boards, electrical appliances, equipments and circuits. It is possible to use the static method treating earthquake force as static load by avoiding resonance with the electrical equipments which have the higher natural frequency than that of buildings. The purposes of the vibration test are to prove the validity of the theoretical analysis, to clarify the vibration characteristics, and to confirm the maintenance of functions and the strength of the equipments. The vibration tests of control boards, the switch boards of enclosed type, motor control centers, the racks for instrumentation, storage batteries and electrical appliances are explained. Moreover, the vibration analysis with a computer according to finite element method is described. (Kako, I.)

  14. Application of ORC power station to increase electric power of gas compression ignition engine

    Directory of Open Access Journals (Sweden)

    Mocarski Szymon

    2017-01-01

    Full Text Available The paper presents the calculation results of efficiency of the subcritical low temperature ORC power station powered by waste heat resulting from the process of cooling a stationary compression ignition engine. The source of heat to supply the ORC power station is the heat in a form of water jet cooling the engine at a temperature of 92°C, and the exhaust gas stream at a temperature of 420°C. The study considers three variants of systems with the ORC power stations with different ways of using heat source. The first variant assumes using just engine cooling water to power the ORC station. In the second variant the ORC system is powered solely by a heat flux from the combustion gases by means of an intermediary medium - thermal oil, while the third variant provides the simultaneous management of both heat fluxes to heat the water stream as a source of power supply to the ORC station. The calculations were made for the eight working media belonging both to groups of so-called dry media (R218, R1234yf, R227ea and wet media (R32, R161, R152a, R134a, R22.

  15. Efforts to perform safe and efficient decommissioning for Tsuruga Power Station Unit 1

    International Nuclear Information System (INIS)

    Saito, Shiro; Yamauchi, Toyoaki; Austin, Colin R.

    2017-01-01

    Tsuruga Power Station Unit-1 (Tsuruga-1) started commercial operation in March 1970, and the decision to terminate operation was made in 2015. In April 2016, JAPC signed an agreement with Energy Solutions (ES) on strategic cooperation for domestic D and D projects for introduction of successful international experiences. As a first step in this cooperation, D and D know-how developed by ES in the US is being applied to Tsuruga-1 with verifying its applicability to domestic D and D projects. One of the efforts is human resource development. JAPC has also started introduction of ES's project management method to the Tsuruga-1 project for solid project management and the base line is currently being prepared. Regarding the waste disposal paths, application document of approval for measurement and evaluation of clearance material was submitted in September 2016. However the disposal paths for waste are not established in Japan. It is necessary to cooperate with the government, utilities and local stakeholders to establish waste disposal paths. Because it is also important to obtain the understanding from local communities, JAPC and ES will try positively to utilize local companies for D and D works. JAPC and ES believe that their relationship will ensure success of the Tsuruga-1 NPP decommissioning project. (author)

  16. Results of the 4th regular inspection in Unit 1 of the Mihama Nuclear Power Station

    International Nuclear Information System (INIS)

    1981-01-01

    The 4th regular inspection of Unit 1 in the Mihama Nuclear Power Station was made from July, 1975, to December, 1980, on its reactor and associated facilities. The respective stages of inspection during the years are described. The inspection by external appearance examination, disassembling leakage inspection and performance tests indicated crackings in piping for fuel-replacement water tank, the container penetration of recirculation pipe for residual-heat removal, and main steam-relief valve, and leakage in one fuel assembly. Radiation exposure of the personnel during the inspection was less than the permissible dose. Radiation exposure data for the personnel are given in tables. The improvements and repairs done accordingly were as follows: reapir of the piping for a fuel-replacement tank and recirculation piping for residual-heat removal, replacement of the main steam-relief valve, plugging of heating tubes for the steam-generator, replacement of pins and covers for control-rod guide pipes, improvement of safety protection system and installation of rare gas monitor. (J.P.N.)

  17. The electric power stations viewed as a source of local and transfrontier pollution

    International Nuclear Information System (INIS)

    Motiu, C.; Sandu, I.

    1994-01-01

    The pollutant emission of the thermal power stations may have an important contribution to the local pollution as well as to regional (transfrontier) and global pollution. Due to the impossibility at present of making continuous monitoring of the emission of pollutants it is necessary to use computational models for obtaining inventories of the pollutant sources and for studying their dispersion into atmosphere. The computational code used to simulate the pollutant diffusion in the atmosphere is a climatologic model giving the annual average concentration and the evaluation of the maximum SO 2 concentration. The paper presents the analyses for the case of 14 thermal power stations of Romania

  18. Alternative central-station electric power generation technologies: a consistent engineering-economic framework of comparison

    International Nuclear Information System (INIS)

    Baughman, M.L.; Gordon, J.B.; Woodson, H.H.

    1983-01-01

    The electric utility sector is an intermediate processing sector of the economy that utilizes the factor inputs of labor, capital, and materials to process and convert chemical, nuclear, and other basic energy forms into electricity. The electricity is then delivered to and consumed by other intermediate or final users for purposes of heating, cooling, lighting, motive power, and materials processing. The economics of electricity supply encompass not only the selection of the basic energy form to be converted but also the selection of possible physical conversion processes to accomplish the conversion. The conversion processes can vary immensely in technical detail, physical configuration, and the basic scientific principle governing their operation. But whatever the design and technical detail, the basic purpose is to process some form of energy and manufacture electricity

  19. Power Processing Unit For Micro Satellite Electric Propulsion System

    Directory of Open Access Journals (Sweden)

    Savvas Spiridon

    2017-01-01

    Full Text Available The Micro Satellite Electric Propulsion System (MEPS program has been originated by the increasing need to provide a low-cost and low-power Electric Propulsion System (EPS for small satellites ( 92%, small size and weight and high reliability. Its functional modules and preliminary results obtained at breadboard level are also presented.

  20. Testing of the Engineering Model Electrical Power Control Unit for the Fluids and Combustion Facility

    Science.gov (United States)

    Kimnach, Greg L.; Lebron, Ramon C.; Fox, David A.

    1999-01-01

    The John H. Glenn Research Center at Lewis Field (GRC) in Cleveland, OH and the Sundstrand Corporation in Rockford, IL have designed and developed an Engineering Model (EM) Electrical Power Control Unit (EPCU) for the Fluids Combustion Facility, (FCF) experiments to be flown on the International Space Station (ISS). The EPCU will be used as the power interface to the ISS power distribution system for the FCF's space experiments'test and telemetry hardware. Furthermore. it is proposed to be the common power interface for all experiments. The EPCU is a three kilowatt 12OVdc-to-28Vdc converter utilizing three independent Power Converter Units (PCUs), each rated at 1kWe (36Adc @ 28Vdc) which are paralleled and synchronized. Each converter may be fed from one of two ISS power channels. The 28Vdc loads are connected to the EPCU output via 48 solid-state and current-limiting switches, rated at 4Adc each. These switches may be paralleled to supply any given load up to the 108Adc normal operational limit of the paralleled converters. The EPCU was designed in this manner to maximize allocated-power utilization. to shed loads autonomously, to provide fault tolerance. and to provide a flexible power converter and control module to meet various ISS load demands. Tests of the EPCU in the Power Systems Facility testbed at GRC reveal that the overall converted-power efficiency, is approximately 89% with a nominal-input voltage of 12OVdc and a total load in the range of 4O% to 110% rated 28Vdc load. (The PCUs alone have an efficiency of approximately 94.5%). Furthermore, the EM unit passed all flight-qualification level (and beyond) vibration tests, passed ISS EMI (conducted, radiated. and susceptibility) requirements. successfully operated for extended periods in a thermal/vacuum chamber, was integrated with a proto-flight experiment and passed all stability and functional requirements.

  1. Operation and management of United Central Piping LPG supply stations in Shenzhen

    Energy Technology Data Exchange (ETDEWEB)

    Lai Yankai

    1997-11-01

    Shenzhen has based its city gas development project on the eventual conversion to natural gas supply by way of central piping LPG supply stations. To fully exploit the potential gas supply capability of every central piping station and cut down the total running cost, we have been connecting the existing supply stations and their piping system into a network, which not only provided a more reliable gas supply performance, but can greatly simplify the evacuation of gas stations from the ever-expanding downtown areas to suburbs. Through this way, the periodic gas stock held by individual stations can be transferred to storage terminal or stations of enough holding capability; the supplying distance has been much lengthened and the gas volume held in the piping system increased; gas supply covered by small stations has been shifted to new and large stations. By linking these stations, we are able to provide pipeline LP gas supply for a large area, and in the same time lay down the pipeline infrastructure for the upcoming LNG supply so that an easy conversion to LNG supply can be secured as soon as the projected LNG terminal is put to service. (au)

  2. Feed-in tariff and market electricity price comparison. The case of cogeneration units in Croatia

    International Nuclear Information System (INIS)

    Uran, Vedran; Krajcar, Slavko

    2009-01-01

    In August 2007, the Government of the Republic of Croatia instituted a feed-in tariff system, requiring the Croatian Electricity Market Operator (HROTE) to off-take the electricity produced from renewable energy sources or cogeneration units fueled by natural gas. Analysis of the off-take electricity price range, which depends on the net electrical output and electricity market trends, indicates that it is more cost effective for cogeneration units greater than 1 MW to sell their electricity on the exchange market. This was confirmed by developing a mathematical model to calculate the cost-effectiveness ratio of a cogeneration unit. This ratio represents the relation between the profit spread, i.e. the difference between the profit generated from selling the electricity on the exchange market and the profit made from dispatching the electricity to HROTE, as well as the total investment costs. The model can be applied for changes in certain parameters, such as the net electrical output, volatility and spot electricity price. The Monte Carlo method is used to obtain the most probable cost-effectiveness ratio and average future electricity price. Together with these two economic parameters and market price analysis, it is possible to calculate and calibrate an acceptable off-take electricity price. (author)

  3. Revised draft environmental statement related to construction of Atlantic Generating Station Units 1 and 2 (Docket Nos. STN 50-477 and STN 50-478)

    International Nuclear Information System (INIS)

    1976-10-01

    The proposed action is the issuance of a construction permit to Public Service Electric and Gas Company (PDE and G) for the construction of the Atlantic Generating Station (AGS), Units 1 and 2. The AGS is the first nuclear power station in the United States proposed for construction in the offshore waters on the continental shelf. The AHS will be located in the Atlantic Ocean 2.8 miles offshore of Atlantic and Ocean countries. New Jersey, 11 miles northeast of Atlantic City, and will consist of two floating nuclear power plants enclosed in a protective rubble-mound breakwater. Both plants will be identical, of standardized design, and will employ pressurized water reactors to produce up to approximately 3425 megawatts thermal (MWt) each. Steam turbine generators will use this heat to produce up to approximately 1150 megawatts of electrical power (MWe) per unit. The main condensers will be cooled by the flow of seawater drawn from within the breakwater and discharged shoreward and external to the breakwater. This statement identifies various environmental aspects and potential adverse effects associated with the construction and operation of the AGS. Based upon an approximate two-year review period which included a multidisciplined assessment of extensive survey and modeling data, these effects are considered by the staff to be of a generally acceptable nature. Breakwater construction will result in the destruction of 100 acres of benthic infauna (burrowing animals) and the development of a reef-type community on the breakwater. The production of new biomass (standing crop) by the reef community is expected to compensate for the infaunal biomass destroyed by dredging and will contribute mainly to the local sport fishery. 93 figs., 110 tabs

  4. Safety evaluation report related to the operation of Limerick Generating Station, Units 1 and 2, Docket nos. 50-352 and 50-353

    International Nuclear Information System (INIS)

    1989-08-01

    In August 1983 the staff of the Nuclear Regulatory commission issued its Safety Evaluation Report (NUREG-0991) regarding the application of the Philadelphia Electric Company (the licensee) for the licenses to operate the Limerick Generating Station, Units 1 and 2, located on a site in Montgomery and Chester Counties, Pennsylvania. Supplement 1 was issued in December 1983. Supplement 2 was issued in October 1984. Supplement 3 was issued in October 1984. Supplement 4 was issued in May 1985. Supplement 5 was issued in July 1985. Supplement 6 was issued in August 1985 and Supplement 7 was issued in April 1989. Supplement 7 addresses the major design differences between Units 1 and 2, the resolution of all issues that remained open when the Unit 1 full-power license was issued, the staff's assessment regarding the application by the licensee to operate Unit 2 and issues that require resolution before issuance of an operating license for Unit 2. Supplements 8 and 9 address further issues that require resolution prior to issuance of an operating license. 1 tab

  5. Investigation of a photo-voltaic pump station with asynchronous electric drive

    International Nuclear Information System (INIS)

    Dzhagarov, N.; Vladimirov, P.

    2000-01-01

    A scheme of a photo-voltaic pump station with constant current drive is presented. The requirements for reliability and minimal maintenance necessitate the use of asynchronous drive which has been studied. The studies of the system's model for various regimes show its adequacy. The model can be used for determination of the optimal conditions providing maximal working efficiency

  6. Draft Environmental Statement related to the operation of Vogtle Electric Generating Plant, Units 1 and 2 (Docket Nos. 50-424 and 50-425)

    International Nuclear Information System (INIS)

    1984-10-01

    This Draft Environmental Statement contains an assessment of the environmental impact associated with the operation of the Vogtle Electric Generating Plant, Units 1 and 2, pursuant to the National Environmental Policy Act of 1969 (NEPA) and Title 10 of the Code of Federal Regulations, part 51 (10 CFR 51), as amended, of the Nuclear Regulatory Commission regulations. This statement examines the environmental impacts, environmental consequences and mitigating actions, and environmental and economic benefits and costs associated with station operation

  7. Flexible Local Load Controller for Fast ElectricVehicle Charging Station Supplemented with Flywheel Energy Storage System

    DEFF Research Database (Denmark)

    Dragicevic, Tomislav; SUN, BO; Schaltz, Erik

    2014-01-01

    Electric vehicle charging infrastructure is hitting the stage where its impact on performance and operation of power systems becomes more and more pronounced. Aiming to utilize the existing power distribution infrastructure and delay its expansion, an approach that includes installation of dedica......Electric vehicle charging infrastructure is hitting the stage where its impact on performance and operation of power systems becomes more and more pronounced. Aiming to utilize the existing power distribution infrastructure and delay its expansion, an approach that includes installation...... of dedicated flywheel energy storage system (FESS) within the charging station and compensating some of the adverse effects of high power charging is explored in this paper. Although sharing some similarities with vehicle to grid (V2G) technology, the principal advantage of this strategy is the fact that many...

  8. Integrated planning of electric vehicles routing and charging stations location considering transportation networks and power distribution systems

    Directory of Open Access Journals (Sweden)

    Andrés Arias

    2018-09-01

    Full Text Available Electric Vehicles (EVs represent a significant option that contributes to improve the mobility and reduce the pollution, leaving a future expectation in the merchandise transportation sector, which has been demonstrated with pilot projects of companies operating EVs for products delivering. In this work a new approach of EVs for merchandise transportation considering the location of Electric Vehicle Charging Stations (EVCSs and the impact on the Power Distribution System (PDS is addressed. This integrated planning is formulated through a mixed integer non-linear mathematical model. Test systems of different sizes are designed to evaluate the model performance, considering the transportation network and PDS. The results show a trade-off between EVs routing, PDS energy losses and EVCSs location.

  9. The metre-kilogram-second system of electrical units

    CERN Document Server

    Sas, R K

    1947-01-01

    Introduction ; electrostatic units, electromagnetic units, and practical units ; magnetic intensity and flux density ; rationalization ; tribulations of the student ; metres and kilograms in general and in mechanics ; pulse and aperture ; magnetostatics ; steady currents ; electrostatics ; resistance ; electromagnetic induction ; determination of Eo. capacity formulae ; field ; electrons and moving charges ; quantum theory ; memory assisted by the M.K.S. system ; short account of M.K.S. units ; list of formulae

  10. Microprocessor control unit of thyristor regulator of microhydroelectric power station ballast load

    International Nuclear Information System (INIS)

    Nomokonova, Yu; Bogdanov, E

    2014-01-01

    The operational principle of microhydroelectric power station ballast load is presented. The comparative overview of the mathematical modeling methods is performed. The ranges of thyristors optimal work are shown as a result of the regulator regimes analysis. Shows the necessity of regulation the ballast load in microhydroelectric power station with help of developed algorithm of the program for microprocessor control

  11. Present state of electric power business in United States and Europe

    International Nuclear Information System (INIS)

    Onishi, Kenichi

    2011-01-01

    This article reported present state of nuclear power and electric power business in United States and Europe after Fukushima Daiichi Accident. As for the trend of demand and supply of electric power and policy, the accident forced Germany possibly to proceed with phase-out of nuclear power, but France and United States to sustain nuclear power with no great change of energy policy at this moment. As for the trend of electric power market, there was not state in United States with liberalized retail market of electric power after rolling blackouts occurred in California State in the early 2000s. In Germany proceeding with renewable energy introduction, renewable electricity fed into the grid was paid for by the network operators at fixed tariffs and the costs passed on to electricity consumers were increasing. Renewable Portfolio Standards (RPS) in United States forced the state to introduction of renewable energy to some ratio, and Feed-in Tariff (FIT) introduced in EU in 1990s lead to introduction of a large amount of renewable electricity targeted in 2020. Huge amount of wind power introduction brought about several problems to solve such that excess electric power above domestic demand had bad effects on grids in neighboring region. Enforcement of power transmission lines was also needed with increase of maximum electric power as well as introduction of a large amount of renewable electricity. (T. Tanaka)

  12. National Account Energy Alliance Final Report for the Basin Electric Project at Northern Border Pipeline Company's Compressor Station #7, North Dakota

    Energy Technology Data Exchange (ETDEWEB)

    Sweetzer, Richard [Exergy Partners Corp.; Leslie, Neil [Gas Technology Institute

    2008-02-01

    A field research test and verification project was conducted at the recovered energy generation plant at Northern Border Pipeline Company Compressor Station #7 (CS#7) near St. Anthony. Recovered energy generation plant equipment was supplied and installed by ORMAT Technologies, Inc. Basin Electric is purchasing the electricity under a purchase power agreement with an ORMAT subsidiary, which owns and operates the plant.

  13. Water Pumping Stations, File name = UTILITIES - PARTIAL Data is incomplete. Contains electric trans lines, electric substations, sewer plants, sewer pumpstations, water plants, water tanks http://www.harfordcountymd.gov/gis/Index.cfm, Published in 2011, 1:1200 (1in=100ft) scale, Harford County Government.

    Data.gov (United States)

    NSGIC Local Govt | GIS Inventory — Water Pumping Stations dataset current as of 2011. File name = UTILITIES - PARTIAL Data is incomplete. Contains electric trans lines, electric substations, sewer...

  14. Sewerage Pumping Stations, File name = UTILITIES - PARTIAL Data is incomplete. Contains electric trans lines, electric substations, sewer plants, sewer pumpstations, water plants, water tanks http://www.harfordcountymd.gov/gis/Index.cfm, Published in 2011, 1:600 (1in=50ft) scale, Harford County Government.

    Data.gov (United States)

    NSGIC Local Govt | GIS Inventory — Sewerage Pumping Stations dataset current as of 2011. File name = UTILITIES - PARTIAL Data is incomplete. Contains electric trans lines, electric substations, sewer...

  15. Capacity Calculation of Shunt Active Power Filters for Electric Vehicle Charging Stations Based on Harmonic Parameter Estimation and Analytical Modeling

    Directory of Open Access Journals (Sweden)

    Niancheng Zhou

    2014-08-01

    Full Text Available The influence of electric vehicle charging stations on power grid harmonics is becoming increasingly significant as their presence continues to grow. This paper studies the operational principles of the charging current in the continuous and discontinuous modes for a three-phase uncontrolled rectification charger with a passive power factor correction link, which is affected by the charging power. A parameter estimation method is proposed for the equivalent circuit of the charger by using the measured characteristic AC (Alternating Current voltage and current data combined with the charging circuit constraints in the conduction process, and this method is verified using an experimental platform. The sensitivity of the current harmonics to the changes in the parameters is analyzed. An analytical harmonic model of the charging station is created by separating the chargers into groups by type. Then, the harmonic current amplification caused by the shunt active power filter is researched, and the analytical formula for the overload factor is derived to further correct the capacity of the shunt active power filter. Finally, this method is validated through a field test of a charging station.

  16. Regulation of unbalanced electromagnetic moment in mutual loading systems of electric machines of traction rolling stock and multiple unit of mainline and industrial transport

    Directory of Open Access Journals (Sweden)

    A. M. Afanasov

    2014-12-01

    the mutual loading systems of electric machines of direct and pulse current. Analytical expressions for the unbalanced moment of mutually loaded electromagnetic electric machines were obtained. The requirements for automatic regulation systems of the mutual loading stands of the traction electric machines of direct and pulse current are formulated. Practical value. Using the results of the theoretical research will significantly simplify the development algorithms of the test stands management of the traction electric machines of rolling stock for mainline and industrial transport. Introduction of the proposed principles of mutual loading for traction electric machines will significantly reduce the costs for creating new stations and modernization of the existing ones for testing of traction electric machines. Automating the process of refit and acceptance tests of traction electric machines will significantly improve the test quality and reliability of the traction rolling stock and multiple unit with electric traction drive.

  17. Optimal Coordinated Management of a Plug-In Electric Vehicle Charging Station under a Flexible Penalty Contract for Voltage Security

    Directory of Open Access Journals (Sweden)

    Jip Kim

    2016-07-01

    Full Text Available The increasing penetration of plug-in electric vehicles (PEVs may cause a low-voltage problem in the distribution network. In particular, the introduction of charging stations where multiple PEVs are simultaneously charged at the same bus can aggravate the low-voltage problem. Unlike a distribution network operator (DNO who has the overall responsibility for stable and reliable network operation, a charging station operator (CSO may schedule PEV charging without consideration for the resulting severe voltage drop. Therefore, there is a need for the DNO to impose a coordination measure to induce the CSO to adjust its charging schedule to help mitigate the voltage problem. Although the current time-of-use (TOU tariff is an indirect coordination measure that can motivate the CSO to shift its charging demand to off-peak time by imposing a high rate at the peak time, it is limited by its rigidity in that the network voltage condition cannot be flexibly reflected in the tariff. Therefore, a flexible penalty contract (FPC for voltage security to be used as a direct coordination measure is proposed. In addition, the optimal coordinated management is formulated. Using the Pacific Gas and Electric Company (PG&E 69-bus test distribution network, the effectiveness of the coordination was verified by comparison with the current TOU tariff.

  18. Studies on the seasonal variation of atmospheric electricity parameters at a tropical station in Kolkata, India

    Science.gov (United States)

    De, S. S.; Paul, Suman; Barui, S.; Pal, Pinaki; Bandyopadhyay, B.; Kala, D.; Ghosh, A.

    2013-12-01

    The paper deals with the analyses of the atmospheric vertical potential gradient (PG) from the ground for 90 fair weather days during 2006-2009 measured at Kolkata (Lat: 22.56°N). The variations of PG have been studied extensively to investigate their values during monsoon and winter seasons. Higher values of PG at Kolkata are observed due to higher abundance of pollutant particles. The observed PG are compared with the results of Potsdam station (Lat: 52°N) and Johannesburg station (Lat: 26°S), with 9 years data and 2 years data respectively. The correlations studies are carried out among PG, PDC (Point Discharge Current) as well as negative and positive carrier conductivities. The corresponding correlation coefficients are obtained as 0.93, -0.842 and -0.844.

  19. Control of Flywheel Energy Storage Systems in Electrical Vehicle Charging Stations

    DEFF Research Database (Denmark)

    Sun, Bo

    energy storage system (FESS). The proposed PhD project supports a corresponding smart control strategy that could be termed “charging station to grid (CS2G)”. It explores the possibility of using a dedicated energy storage system (FESS) within the charging station to alleviate grid and market conditions...... converters is built and analyzed. |Based on modeling analysis, centralized and distributed control methods are both explored to realize the coordination control of each components in the system. Specially, this project proposes a “dc voltage vs speed” droop strategy for FESS control based on distributed bus...... function method when the system switches its operation behavior between two modes. Finally, a downscaled FCS prototype with FESS is built in the intelligent MG lab, and experiments and hardware-in-loop simulation results are conducted to verify the effectiveness and feasibility with the proposed FCS...

  20. A Cryogenic Test Station for the Pre-series 2400 W @ 1.8 K Refrigeration Units for the LHC

    CERN Document Server

    Claudet, S; Gully, P; Jäger, B; Millet, F; Roussel, P; Tavian, L

    2002-01-01

    The cooling capacity below 2 K for the superconducting magnets in the Large Hadron Collider (LHC), at CERN, will be provided by eight refrigeration units at 1.8 K, each of them coupled to a 4.5 K refrigerator. The supply of the series units is linked to successful testing and acceptance of the pre-series delivered by the two selected vendors. To properly assess the performance of specific components such as cold compressors and some process specificities a dedicated test station is necessary. The test station is able to process up to 130 g/s between 4.5 & 20 K and aims at simulating the steady and transient operational modes foreseen for the LHC. After recalling the basic characteristics of the 1.8 K refrigeration units and the content of the acceptance tests of the pre-series, the principle of the test cryostat is detailed. The components of the test station and corresponding layout are described. The first testing experience is presented as well as preliminary results of the pre-series units.

  1. Periodical inspection in nuclear power stations

    International Nuclear Information System (INIS)

    1986-01-01

    Periodical inspection is presently being made of eight nuclear power plants in nuclear power stations. Up to the present time, in three of them, failures as follows have been observed. (1) Unit 3 (PWR) of the Mihama Power Station in The Kansai Electric Power Co., Inc. Nineteen heat-transfer tubes of the steam generators were plugged up due to failure. A fuel assembly with a failed spring fixture and in another the control-rod cluster with a failed control rod fixture were replaced. (2) Unit 2 (PWR) of the Oi Power Station in The Kansai Electric Power Co., Inc. Eight heat-transfer tubes of the heat exchangers were plugged up due to failure. (3) Unit 6 (BWR) of the Fukushima Nuclear Power Station I in The Tokyo Electric Power Co., Inc. A fuel assembly with leakage was replaced. (Mori, K.)

  2. Manufacture and quality control of concrete for Ikata Nuclear Power Station, Shikoku Electric Power Co., Inc

    International Nuclear Information System (INIS)

    Tada, Akiomi; Kitada, Takao

    1989-01-01

    Ikata Nuclear Power Station, only one nuclear power station in Shikoku, is located at the root of Sada Peninsula on Seto Inland sea side. At present, No.1 and No.2 plants of 566 MW each are in commercial operation, and on the east side, No.3 plant is under construction. No.3 plant is a PWR type plant of 890 MWe output, and the start of commercial operation is scheduled in March, 1995. In the construction of No.3 plant, the concrete used for civil engineering and building works is about 430,000 m 3 , and for the improvement of the quality control of concrete, the pursuit of economic efficiency, the fostering of concrete technology of employee and the coprosperity with local industries, the facilities for manufacturing concrete were constructed within the premise of the power station. The amount of use of concrete and respective materials classified by respective fiscal years, and the amount of manufacture of concrete that determines the scale of the concrete plant are shown. As to the construction of the concrete plant, the foundation work was started in March, 1987, and the machine foundation and building works were started in May, 1987. The acceptance was completed on August 17, 1987. The facilities of manufacturing concrete, the manufacture of concrete, and the quality control of materials and concrete are reported. (author)

  3. Radioactivity in coal, ashes and selected wastewaters from Canadian coal-fired steam electric generating stations

    International Nuclear Information System (INIS)

    1985-09-01

    Coal is known to contain naturally occurring radioactive elements and there has been speculation that as a results, coal-fuelled power generation stations may be significant emitters of these substances. In this report, the subject of radioactivity is introduced. The kinds of radioactive substances which occur naturally in coal formations, the nature of their emissions and the existing information on their behaviour and their effects on environmental organisms are also reviewed. The results of an examination of levels of alpha, beta and gamma radiaton levels, and the substances which produce them in coals, fly ashes, bottom ashes and related wastewaters at six Canadian coal-fuelled power stations are presented. Difficulties in studies of this nature and the potential effects of these releases on organisms in the adjacent aquatic environment are discussed. Existing and potential technologies for the removal of these substances from wastewaters are examined. In general the releases in wastewaters from the six stations were found to be lower than those known to cause short-term or acute biological effects. The potential for long-term effects from such low-level releases could not be accurately assessed because of the paucity of information. A number of recommendations for: improvements in further studies of this nature; the further examination of the fate of naturally occurring radionuclides in the environment; and the determination of the long-term effects of low levels of naturally occurring radioactive substances on aquatic organisms, are made

  4. Demands on project management of comprehensive modernization projects in the electrical systems area. Example of modernization of electrical systems of Kozloduy NPP Unit 5 and 6

    International Nuclear Information System (INIS)

    Stinshoff, Helmut; Weber, Patrick

    2006-01-01

    In nuclear power plants, station supply with electric energy must be guaranteed any time. This applies in particular also during the implementation of complex electrical systems modernization projects. Highest demands on the project management, extensive experience and system knowledge are required. In the frame of the Modernization Program for the nuclear power plant Kozloduy unit 5 and 6 in Bulgaria Framatome ANP has approved its ability to implement a large scope of modernization measures during the refueling outages of the years 2003 to 2005. The Contract of the Modernization Program for the European Consortium Kozloduy (Framatome ANP, Atomenergoexport) was signed in July 1999 and became effective in June 2001. The project will be finished by May 2006, with the approval of the Updated Final Safety Analysis Report. The scope of hardware work has been implemented within 6 plant outages during the years 2002 to 2005. The focus of the Modernization Program is mainly oriented to nuclear safety aspects, with the aim of upgrading of the Units to a high safety level in compliance with international practice. A further section of the project is dedicated to upgrading of operational equipment. Framatome ANP personnel have shown that besides the technical challenges which had to be faced, also the intercultural and language barriers were successfully overcome. The good teamwork between the partners of the Consortium ECK, its Bulgarian subcontractors and with Kozloduy plant personnel has been an important success factor. (authors)

  5. Final environmental statement: Related to the operation of Davis-Besse Nuclear Power Station, Unit 1 (Docket No. 50-346)

    International Nuclear Information System (INIS)

    1975-10-01

    The proposed action is the issuance of an operating license to the Toledo Edison Company and the Cleveland Electric Illuminating Company for the startup and operation of the Davis-Besse Nuclear Power Station Unit 1 (the station) located near Port Clinton in Ottawa County, Ohio. The total site area is 954 acres of which 160 acres have been removed from production of grain crops and converted to industrial use. Approximately 600 acres of the area is marshland which will be maintained as a wildlife refuge. The disturbance of the lake shore and lake bottom during construction of the station water intake and discharge pipes resulted in temporary turbidity, silting, and destruction of bottom organisms. Since completion of these activities, evidence of improvement in turbidity and transparency measurements, and the reestablishment of the bottom organism has been obtained. The cooling tower blowdown and service water which the station discharges to Lake Erie, via a submerged jet, will be heated no more than 20/degrees/F above the ambient lake water temperature. Although some small fish and plankton in the discharge water plume will be disabled as a result of thermal shock, exposure to chlorine and buffeting, few adult fish will be affected. The thermal plume resulting from the maximum thermal discharge is calculated to have an area of less than one acre within the 3/degrees/F isotherm (above lake ambient). Approximately 101 miles of transmission lines have been constructed, primarily over existing farmland, requiring about 1800 acres of land for the rights-of-way. Land use will essentially be unchanged since only the land required for the base of the towers is removed from production. Herbicides will not be used to maintain the rights-of-way. 14 figs., 34 refs

  6. Safety evaluation report related to the operation of Catawba Nuclear Station, Units 1 and 2. Docket Nos. 50-413 and 50-414. Suppl. 1

    International Nuclear Information System (INIS)

    1983-04-01

    This reort supplements the Safety Evaluation Report (NUREG-0954) issued in February 1983 by the Office of Nuclear Reactor Regulation of the US Nuclear Regulatory Commission with respect to the application filed by Duke Power Company, North Carolina Municipal Power Agency Number 1, North Carolina Membership Corporation, and Saluda River Electric Cooperative, Inc. as applicants and owners, for licenses to operate the Catawba Nuclear Station, Units 1 and 2 (Docket Nos. 50-413 and 50-414, respectively). The facility is located in York County, South Carolina, approximately 9.6 km (6 mi) north of Rock Hill and adjacent to Lake Wylie. This supplement provides more recent information regarding resolution or updating of some of the open and confirmatory items and license conditions identified in the Safety Evaluation Report, and discusses the recommendations of the Advisory Committee on Reactor Safeguards in its report dated March 15, 1983

  7. Safety Evaluation Report related to the operation of Wolf Creek Generating Station, Unit No. 1 (Docket No. STN 50-482). Supplement No. 5

    International Nuclear Information System (INIS)

    1985-03-01

    This report supplements the Safety Evaluation Report (SER) for the application filed by the Kansas Gas and Electric Company, as applicant and agent for the owners, for a license to operate the Wolf Creek Generating Station, Unit 1 (Docket No. STN 50-482). The facility is located in Coffey County, Kansas. This supplement has been prepared by the Office of Nuclear Reactor Regulation of the US Nuclear Regulatory Commission and provides recent information regarding resolution of the open items identified in the SER. Because of the favorable resolution of the items discussed in this report, the staff concludes that the facility can be operated by the applicant without endangering the health and safety of the public

  8. Safety Evaluation Report related to the operation of Grand Gulf Nuclear Station, Units 1 and 2 (Docket Nos. 50-416 and 50-417)

    International Nuclear Information System (INIS)

    1984-10-01

    This report supplements the Safety Evaluation Report (NUREG-0831) issued in September 1981 by the Office of Nuclear Reactor Regulation of the US Nuclear Regulatory Commission with respect to the application filed by Mississippi Power and Light (MP and L) Company, Middle South Energy, Inc., and South Mississippi Electric Power Association as applicants and owners, for licenses to operate the Grand Gulf Nuclear Station, Units 1 and 2 (Docket Nos. 50-416 and 50-417, respectively). The facility is located on the east bank of the Mississippi River near Port Gibson in Claiborne County, Mississippi. This supplement provides information on the NRC staff's evaluation of requests for exemptions to NRC regulations pursuant to the Commission's direction in CLI-84-19, dated October 25, 1984

  9. Safety evaluation report related to the operation of Catawba Nuclear Station, Units 1 and 2 (Docket Nos. 50-413 and 50-414). Supplement 2

    International Nuclear Information System (INIS)

    1984-06-01

    This report supplements the Safety Evaluation Report (NUREG-0954) and Supplement 1 with respect to the application filed by Duke Power Company, North Carolina Municipal Power Agency Number 1, North Carolina Membership Corporation, and Saluda River Electric Cooperative, Inc., as applicants and owners, for licenses to operate the Catawba Nuclear Station, Units 1 and 2 (Docket Nos., 50-413 and 50-414, respectively). The facility is located in York County, South Carolina, approximately 9.6 km (6 mi) north of Rock Hill and adjacent to Lake Wylie. This supplement provides more recent information regarding resolution or updating of some of the open and confirmatory issues and license conditions identified in the Safety Evaluation Report

  10. 78 FR 46616 - Virginia Electric and Power Company; North Anna Power Station, Units 1 and 2; Surry Power Station...

    Science.gov (United States)

    2013-08-01

    ... Nuclear Energy Institute (NEI) 99-01, Methodology for Development of Emergency Action Levels.'' The... readily accessible means available in the Control Room. Environmental Impacts of the Proposed Action The... that there are no significant environmental impacts associated with the proposed action. Environmental...

  11. Electric power industry deregulation in the United States: impacts on U.S. and Canadian markets

    Energy Technology Data Exchange (ETDEWEB)

    Hall, G.R. [Putnam, Hayes and Bartlett, Inc., Cambridge, MA (United States)

    1996-10-01

    An overview of the restructuring and deregulation of the United States electric power industry and the implications for the North American natural gas industry was presented. Electric power restructuring and its effect on wholesale and retail competition was discussed. It was suggested that although in the short term electric power deregulation impacts negatively on the natural gas industry, the long term impacts are favourable. The short term impact on the natural gas industry will mean increased competition and downward pressure on gas prices. In contrast, the long term impact could mean increased reliance on gas for electric power generation and convergence of the electric power and natural gas industries.

  12. Highway vehicle electric drive in the United States : 2009 status and issues.

    Energy Technology Data Exchange (ETDEWEB)

    Santini, D. J.; Energy Systems

    2011-02-16

    The status of electric drive technology in the United States as of early 2010 is documented. Rapidly evolving electric drive technologies discussed include hybrid electric vehicles, multiple types of plug-in hybrid electric vehicles, and battery electric vehicles. Recent trends for hybrids are quantified. Various plug-in vehicles entering the market in the near term are examined. The technical and economic requirements for electric drive to more broadly succeed in a wider range of highway vehicle applications are described, and implications for the most promising new markets are provided. Federal and selected state government policy measures promoting and preparing for electric drive are discussed. Taking these into account, judgment on areas where increased Clean Cities funds might be most productively focused over the next five years are provided. In closing, the request by Clean Cities for opinion on the broad range of research needs providing near-term support to electric drive is fulfilled.

  13. Planning Future Electric Vehicle Central Charging Stations Connected to Low-Voltage Distribution Networks

    DEFF Research Database (Denmark)

    Marra, Francesco; Træholt, Chresten; Larsen, Esben

    2012-01-01

    A great interest is recently paid to Electric Vehicles (EV) and their integration into electricity grids. EV can potentially play an important role in power system operation, however, the EV charging infrastructures have been only partly defined, considering them as limited to individual charging...... on their investment cost. Investigation on location and size of CCS is conducted, analyzing two LV grids of different capacity. The results enlighten that a public CCS should be preferably located in the range of 100 m from the transformer. The AC charging levels of 11 kW and 22 kW have the highest potential in LV...

  14. Station blackout: Deterministic and probabilistic approach in the field of electrical supply losses by EDF

    International Nuclear Information System (INIS)

    Meslin, T.; Carnino, A.

    1986-01-01

    This example shows the thoroughness of EDF's approach in processing the difficult problems of the loss of electrical power supplies. Efforts are continuing in several directions: continued revision and improvement of operating procedures in the event of loss of electrical power supplies, PWR plant operator training courses devoted to the problems of power supply losses, and continued testing on simulators, and particularly testing under real conditions, including tests lasting several hours made possible by the performance of the new EDF simulators (two-phase code and taking all power losses into account)

  15. AECL's participation in the commissioning of Point Lepreau generating station unit 1

    International Nuclear Information System (INIS)

    Chawla, S.; Singh, K.; Yerramilli, S.

    1983-05-01

    Support from Atomic Energy of Canada Ltd. (AECL) to Point Lepreau during the commissioning program has been in the form of: seconded staff for commissioning program management, preparation of commissioning procedures, and hands-on commissioning of several systems; analysis of test results; engineering service for problem solving and modifications; design engineering for changes and additions; procurement of urgently-needed parts and materials; technological advice; review of operational limits; interpretation of design manuals and assistance with and preparation of submissions to regulatory authorities; and development of equipment and procedures for inspection and repairs. This, together with AECL's experience in the commissioning of other 600 MWe stations, Douglas Point and Ontario Hydro stations, provides AECL with a wide range of expertise for providing operating station support services for CANDU stations

  16. Projected costs of generating electricity from nuclear and coal-fired power stations for commissioning in 1995

    International Nuclear Information System (INIS)

    1986-01-01

    This report updates and extends the previous NEA study, ''The Costs of Generating Electricity in Nuclear and Coal-fired Power Stations'', published by the OECD in late 1983. Despite the changed expectations concerning coal prices and the considerable movements in exchange rates since the first study was completed, the conclusions remain essentially the same. Nuclear Power is projected to be economically superior by a significant margin to coal-fired plants for base load electricity production in Europe, Japan and some regions of North America. In areas of North America in close proximity to supplies of cheap coal, this would be the more economic fuel, unless future nuclear investment costs can be reduced to match the best US and Canadian experience. In all regions considered, the economic advantage of both coal and nuclear over oil and gas-fired plants for commissioning in the mid-1990s is expected to be substantial. These conclusions are based on an analysis of cost projections for 900 MWe to 1400 MWe Light Water Reactors to be commissioned in 1995, operating at a levelised load factor of about 72 per cent over an assumed 25 years economic life and calculated with a 5 per cent (real) discount rate. This parallels the reference reactor selected for the NEA report ''The Economics of the Nuclear Fuel Cycle'', which was published by the OECD in June 1985, though it deviates somewhat from the reference conditions of the previous generation cost study. Contemporary coal-fired stations ranging in capacity from 330 MWe to 700 MWe with the same assumed economic life and load factor provide the basis for comparison. Some data are included on CANDU Pressurised Heavy Water Reactors, and a brief comment is annexed on the relevance of the comparisons for the smaller plants that may be of interest to countries with smaller electricity networks or where special circumstances apply

  17. Application of a hazard and operability study method to hazard evaluation of a chemical unit of the power station.

    Science.gov (United States)

    Habibi, E; Zare, M; Barkhordari, A; Mirmohammadi, Sj; Halvani, Ghh

    2008-12-28

    The aim of this study was to identify the hazards, evaluate their risk factors and determine the measure for promotion of the process and reduction of accidents in the chemical unit of the power station. In this case and qualitative study, HAZOP technique was used to recognize the hazards and problems of operations on the chemical section at power station. Totally, 126 deviations were documented with various causes and consequences. Ranking and evaluation of identified risks indicate that the majority of deviations were categorized as "acceptable" and less than half of that were "unacceptable". The highest calculated risk level (1B) related to both the interruption of acid entry to the discharge pumps and an increased density of the acid. About 27% of the deviations had the lowest risk level (4B). The identification of hazards by HAZOP indicates that it could, systemically, assess and criticize the process of consumption or production of acid and alkali in the chemical unit of power plant.

  18. Final supplement to the final environmental statement related to operation of Three Mile Island Nuclear Station, Unit 2: (Docket No. 50-320)

    International Nuclear Information System (INIS)

    1976-12-01

    The proposed action is the continuation of construction permit CPPR-66 and the issuance of operating license to Metropolitan Edison Company, Jersey Central Power and Light Company, and the Pennsylvania Electric Company (the Applicants) for the operation of the Three Mile Island Nuclear Station, Unit 2, Docket No. 50-320, near Harrisburg in Dauphin County, Pennsylvania. The Three Mile Island Nuclear Station Unit Number 2 has a designed thermal rating of 2772 megawatts with a maximum electrical output of 959 megawatts. Two natural draft cooling towers are utilized for dissipating the waste heat from the closed cycle cooling system. Extension of TMINS-Bechtelsville 500 kV transmission line an additional 7.36 miles from Bechtelsville to Hosensack required acquisition of additional 175 foot wide right-of-way along an existing 150 foot wide 230 kV corridor. Construction of this line segment resulted in clearing of 21 acres of woodland, spanning over 134.5 acres of agricultural land and diverting of 0.4 acres from agriculture to use under tower bases. About 550 curies of radionuclides in liquid effluents (0.24 Ci/yr excluding tritium and 550 Ci/yr of tritium) will be released to the environment annually. Gaseous releases will be approximately 6700 Ci/yr of noble gases, 0.01 Ci/yr of iodine-131, 560 Ci/yr of tritium, 25 Ci/yr of argon-41, and 0.06 Ci/yr of particulates. No significant environmental impacts are anticipated from normal operational releases of radioactive materials. The calculated dose to the estimated year 1990 US population is less than 540 manrem/yr. This value is less than the natural fluctuation in the approximately 28,000,000 manrem/yr dose this population would receive from background radiation

  19. Safety evaluation report related to the operation of Beaver Valley Power Station, Unit 2 (Docket No. 50-412)

    International Nuclear Information System (INIS)

    1987-03-01

    This report, Supplement No. 4 to the Safety Evaluation Report for the application filed by the Duquesne Light Company et al. (the applicant) for a license to operate the Beaver Valley Power Station, Unit 2 (Docket No. 50-412), has been prepared by the Office of Nuclear Reactor Regulation of the US Nuclear Regulatory Commission. This supplement reports the status of certain items that had not been resolved when the Safety Evaluation Report and its Supplements 1, 2, and 3 were published

  20. Safety evaluation report related to the operation of Beaver Valley Power Station, Unit 2 (Docket No. 50-412)

    International Nuclear Information System (INIS)

    1986-05-01

    This report, Supplement No. 1 to the Safety Evaluation Report for the application filed by the Duquesne Light Company et al. (the applicant) for a license to operate the Beaver valley Power Station, Unit 2 (Docket No. 50-412), has been prepared by the Office of Nuclear Reactor Regulation of the US Nuclear Regulatory Commission. This supplement reports the status of certain items that had not been resolved at the time the Safety Evaluation Report was published

  1. Draft environmental statement related to the operation of Millstone Nuclear Power Station, Unit No. 3 (Docket No. 50-423)

    International Nuclear Information System (INIS)

    1984-07-01

    This Draft Environmental Statement contains the second assessment of the environmental impact associated with the operation of Millstone Nuclear Power Station, Unit 3, pursuant to the National Environmental Policy Act of 1969 (NEPA) and Title 10 of the Code of Federal Regulations, Part 51, as amended, of the Nuclear Regulatory Commission regulations. This statement examines the environment, environmental consequences and mitigating actions, and environmental and economic benefits and costs

  2. Safety Evaluation Report related to the operation of Shoreham Nuclear Power Station, Unit No. 1 (Docket No. 50-322)

    International Nuclear Information System (INIS)

    1989-04-01

    Supplement 10 (SSER 10) to the Safety Evaluation Report on Long Island Lighting Company's application for a license to operate the Shoreham Nuclear Power Station, Unit 1, located in Suffolk County, New York, has been prepared by the Office of Nuclear Reactor Regulation of the US Nuclear Regulatory Commission. This supplement addresses several items that have been reviewed by the staff since the previous supplement was issued

  3. On safety 1E qualification of electrical equipment for nuclear power stations

    International Nuclear Information System (INIS)

    Segarceanu, D.; Geambasu, C.; Avramescu, M.

    1995-01-01

    Electrical equipment and systems for the emergency shutdown of a nuclear reactor are qualified according to safety class 1E. Methods of qualification meeting the requirements should be used, either individually or in combination include, type-test qualification, qualification by operating experience, qualification by analysis, combined qualification. These methods qualification principles, procedures and documents are discussed. (N.T.). 1 fig

  4. System design for a solar powered electric vehicle charging station for workplaces

    NARCIS (Netherlands)

    Chandra Mouli, G.R.; Bauer, P.; Zeman, M.

    2016-01-01

    This paper investigates the possibility of charging battery electric vehicles at workplace in Netherlands using solar energy. Data from the Dutch Meteorological Institute is used to determine the optimal orientation of PV panels for maximum energy yield in the Netherlands. The seasonal and diurnal

  5. Coupled heat-electromagnetic simulation of inductive charging stations for electric vehicles

    NARCIS (Netherlands)

    Kaufmann, C.; Günther, M.; Klagges, D.; Richwin, M.; Schöps, S.; Maten, ter E.J.W.

    2012-01-01

    Coupled electromagnetic-heat problems have been studied for induction or inductive heating, for dielectric heating, for testing of corrosion, for detection of cracks, for hardening of steel, and more recently for inductive charging of electric vehicles. In nearly all cases a simple co-simulation is

  6. Coupled heat-electromagnetic simulation of inductive charging stations for electric vehicles

    NARCIS (Netherlands)

    Kaufmann, C.; Günther, M.; Klagges, D.; Richwin, M.; Schöps, S.; Maten, ter E.J.W.; Fontes, M.; Günther, M.; Marheineke, N.

    2014-01-01

    Coupled electromagnetic-heat problems have been studied for induction or inductive heating, for dielectric heating, for testing of corrosion, for detection of cracks, for hardening of steel, and more recently for inductive charging of electric vehicles. In nearly all cases a simple co-simulation is

  7. 78 FR 53483 - Inspections, Tests, Analyses, and Acceptance Criteria; Vogtle Electric Generating Plant, Unit 3

    Science.gov (United States)

    2013-08-29

    ... NUCLEAR REGULATORY COMMISSION [Docket No. 052-00025; NRC-2008-0252] Inspections, Tests, Analyses, and Acceptance Criteria; Vogtle Electric Generating Plant, Unit 3 AGENCY: Nuclear Regulatory Commission. ACTION: Determination of inspections, tests, analyses, and acceptance criteria (ITAAC) completion...

  8. 78 FR 53484 - Inspections, Tests, Analyses, and Acceptance Criteria; Vogtle Electric Generating Plant, Unit 4

    Science.gov (United States)

    2013-08-29

    ... NUCLEAR REGULATORY COMMISSION [Docket No. 052-00026; NRC-2008-0252] Inspections, Tests, Analyses, and Acceptance Criteria; Vogtle Electric Generating Plant, Unit 4 AGENCY: Nuclear Regulatory Commission. ACTION: Determination of inspections, tests, analyses, and acceptance criteria (ITAAC) completion...

  9. 78 FR 65007 - Inspections, Tests, Analyses, and Acceptance Criteria; Vogtle Electric Generating Plant, Unit 3

    Science.gov (United States)

    2013-10-30

    ... NUCLEAR REGULATORY COMMISSION [Docket No. 052-00026; NRC-2008-0252] Inspections, Tests, Analyses, and Acceptance Criteria; Vogtle Electric Generating Plant, Unit 3 AGENCY: Nuclear Regulatory Commission. ACTION: Determination of inspections, tests, analyses, and acceptance criteria completion...

  10. Variable structure unit vector control of electric power generation ...

    African Journals Online (AJOL)

    A variable structure Automatic Generation Control (VSAGC) scheme is proposed in this paper for the control of a single area power system model dominated by steam powered electric generating plants. Unlike existing, VSAGC scheme where the selection of the control function is based on a trial and error procedure, the ...

  11. Smart electric grids in the United Kingdom energy strategy

    International Nuclear Information System (INIS)

    Gloaguen, Olivier; Dreyfus, Charles-Antoine

    2011-09-01

    This study first gives an overview of the current status and limitations of the British power grid. It indicates the British energy mix, describes the network structure and its economic operation (gross and retail market with the bid and offer system, role of the System Operator, ways to increase the electricity production). It presents the energy policy and its regulation framework, outlines the current limitations and challenges (ageing grid, power crunch, de-carbonation challenges). It presents the development of a smart grid as a solution to economy de-carbonation challenges: definition of the 'smart grid concept', smart grid development planning (from 2010 to 2050), technological transition associated with smart electric grid development (a cleaner but more intermittent and random electricity production, better use of fossil fuels, electric energy storage, consequences for the grid, introduction and effects of smart meters). It describes the new associated economic model: evolution of the value chain, financial challenges (required investments, expected benefits, subsidies), new regulation system. It addresses the strategic challenges and the various uncertainties (notably in terms of consumption, privacy issue in relation with the use of smart meters, and project implementation).

  12. Regulation and competition in United Kingdom electricity and gas industries

    International Nuclear Information System (INIS)

    McGowan, F.

    1992-01-01

    Focussing on the role of regulation in developing competition, this paper reviews the development of a regulation system to monitor and control prices, as well as, quality of service, in the UK's recently privatized electricity and gas industries. The review covers: the control mechanisms applied to the natural gas tariff and contract markets in the area of common carriage; performance monitoring and the concept of yardstick competition in the electric power industry; and the management and control, by OFFER (Office of Electricity Regulation), of the total 'pool' of generated electricity. It is noted that whereas Great Britain's particular energy supply situation permits this nation to attempt privatization/competition regulation, the energy balances of other European countries make similar attempts, for them, risky. The UK experience with privatization/competition regulation so far has shown that regulation is indispensable in guaranteeing competition, and that the incorporation of the controlling board within the framework of anti-trust legislation and the granting of full autonomy to this board has greatly favoured its effectiveness

  13. Electric field effects on ionospheric and thermospheric parameters above the EISCAT station for summer conditions

    Directory of Open Access Journals (Sweden)

    V. V. Klimenko

    Full Text Available Numerical calculations of the thermospheric and ionospheric parameters above EISCAT are presented for quiet geomagnetic conditions in summer. The Global Self-consistent Model of the Thermosphere, Ionosphere and Protonosphere (GSM TIP was used. The numerical results were obtained both with a self-consistent calculation of the electric fields of magnetospheric and dynamo-action origin and with the magnetospheric electric fields only. It was found that the dynamo-electric field has some effect on the ionospheric convection pattern during quiet geomagnetic conditions. It has a marked effect mainly on the zonal neutral wind component above EISCAT (±20 m/s at 140 km altitude. We have studied the effects of various field-aligned current (FAC distributions on thermosphere/ionosphere parameters and we show that a qualitative agreement can be obtained with region-I and -II FAC zones at 75° and 65° geomagnetic latitude, respectively. The maximum FAC intensities have been assumed at 03–21 MLT for both regions with peak values of 2.5×10–7 A m–2 (region I and 1.25×10–7 A m–2 (region II. These results are in agreement with statistical potential distribution and FAC models constructed by use of EISCAT data. The lack of decreased electron density in the night-time sector as observed by the EISCAT radar was found to be due to the spatial distribution of ionospheric convection resulting from electric fields of magnetospheric origin.

    Key words. Electric fields and currents · Ionosphere- atmosphere interactions · Modelling and forecasting

  14. Electric field effects on ionospheric and thermospheric parameters above the EISCAT station for summer conditions

    Directory of Open Access Journals (Sweden)

    V. V. Klimenko

    1998-10-01

    Full Text Available Numerical calculations of the thermospheric and ionospheric parameters above EISCAT are presented for quiet geomagnetic conditions in summer. The Global Self-consistent Model of the Thermosphere, Ionosphere and Protonosphere (GSM TIP was used. The numerical results were obtained both with a self-consistent calculation of the electric fields of magnetospheric and dynamo-action origin and with the magnetospheric electric fields only. It was found that the dynamo-electric field has some effect on the ionospheric convection pattern during quiet geomagnetic conditions. It has a marked effect mainly on the zonal neutral wind component above EISCAT (±20 m/s at 140 km altitude. We have studied the effects of various field-aligned current (FAC distributions on thermosphere/ionosphere parameters and we show that a qualitative agreement can be obtained with region-I and -II FAC zones at 75° and 65° geomagnetic latitude, respectively. The maximum FAC intensities have been assumed at 03–21 MLT for both regions with peak values of 2.5×10–7 A m–2 (region I and 1.25×10–7 A m–2 (region II. These results are in agreement with statistical potential distribution and FAC models constructed by use of EISCAT data. The lack of decreased electron density in the night-time sector as observed by the EISCAT radar was found to be due to the spatial distribution of ionospheric convection resulting from electric fields of magnetospheric origin.Key words. Electric fields and currents · Ionosphere- atmosphere interactions · Modelling and forecasting

  15. Dresden Nuclear Power Station, Unit No. 1: Primary cooling system chemical decontamination: Draft environmental statement (Docket No. 50-10)

    International Nuclear Information System (INIS)

    1980-05-01

    The staff has considered the environmental impact and economic costs of the proposed primary cooling system chemical decontamination at Dresden Nuclear Power Station, Unit 1. The staff has focused this statement on the occupational radiation exposure associated with the proposed Unit 1 decontamination program, on alternatives to chemical decontamination, and on the environmental impact of the disposal of the solid radioactive waste generated by this decontamination. The staff has concluded that the proposed decontamination will not significantly affect the quality of the human environment. Furthermore, any impacts from the decontamination program are outweighed by its benefits. 2 figs., 7 tabs

  16. Specific absorption rate and electric field measurements in the near field of six mobile phone base station antennas.

    Science.gov (United States)

    Toivonen, Tommi; Toivo, Tim; Puranen, Lauri; Jokela, Kari

    2009-05-01

    In this article, the exposure to radio frequency electromagnetic fields was studied in close proximity (distances of 10, 100, 300, and 600 mm) to six base station antennas. The specific absorption rate (SAR) in 800 mm x 500 mm x 200 mm box phantom as well as unperturbed electric field (E) in air was measured. The results were used to determine whether the measurement of local maximum of unperturbed electric field can be used as a compliance check for local exposure. Also, the conservativeness of this assessment method compared to the ICNIRP basic restriction was studied. Moreover, the assessment of whole-body exposure was discussed and the distance ranges presented in which the ICNIRP limit for local exposure could be exceeded before the limit for whole-body SAR. These results show that the electric field measurement alone can be used for easy compliance check for the local exposure at all distances and for all antenna types studied. However, in some cases when the local peak value of E was compared directly to the ICNIRP reference level for unperturbed E, the exposure was overestimated only very slightly (by factor 1.1) compared to the basic restriction for localized SAR in a human, and hence these results can not be generalized to all antenna types. Moreover, it was shown that the limit for localized exposure could be exceeded before the limit for the whole-body average SAR, if the distance to the antenna was less than 240 mm. Copyright 2009 Wiley-Liss, Inc.

  17. Impacts of rising air temperatures on electric transmission ampacity and peak electricity load in the United States

    Science.gov (United States)

    Bartos, Matthew; Chester, Mikhail; Johnson, Nathan; Gorman, Brandon; Eisenberg, Daniel; Linkov, Igor; Bates, Matthew

    2016-11-01

    Climate change may constrain future electricity supply adequacy by reducing electric transmission capacity and increasing electricity demand. The carrying capacity of electric power cables decreases as ambient air temperatures rise; similarly, during the summer peak period, electricity loads typically increase with hotter air temperatures due to increased air conditioning usage. As atmospheric carbon concentrations increase, higher ambient air temperatures may strain power infrastructure by simultaneously reducing transmission capacity and increasing peak electricity load. We estimate the impacts of rising ambient air temperatures on electric transmission ampacity and peak per-capita electricity load for 121 planning areas in the United States using downscaled global climate model projections. Together, these planning areas account for roughly 80% of current peak summertime load. We estimate climate-attributable capacity reductions to transmission lines by constructing thermal models of representative conductors, then forcing these models with future temperature projections to determine the percent change in rated ampacity. Next, we assess the impact of climate change on electricity load by using historical relationships between ambient temperature and utility-scale summertime peak load to estimate the extent to which climate change will incur additional peak load increases. We find that by mid-century (2040-2060), increases in ambient air temperature may reduce average summertime transmission capacity by 1.9%-5.8% relative to the 1990-2010 reference period. At the same time, peak per-capita summertime loads may rise by 4.2%-15% on average due to increases in ambient air temperature. In the absence of energy efficiency gains, demand-side management programs and transmission infrastructure upgrades, these load increases have the potential to upset current assumptions about future electricity supply adequacy.

  18. Control of Flywheel Energy Storage Systems in Electrical Vehicle Charging Stations

    OpenAIRE

    Sun, Bo

    2017-01-01

    Growing environmental awareness and strong political impetus have resulted in plug-in electric vehicles (PEV) becoming ever more attractive means of transportation. They are expected to have a significant impact to the overall loading of future distribution networks. Thus, current distribution grids need to be updated in order to accommodate PEV fleets, which are recognized in smart grid (SG) objective. The prevailing concern in that sense is the combined impact of a large number of randomly ...

  19. The supplying of primary energy to electric power stations up to 1985

    International Nuclear Information System (INIS)

    Roux, J.P.

    1975-01-01

    After specifying the role of thermal power plants in supplying France with electric power, the report examines the impact on their activity of recent events affecting energy and, in the light of this analysis, shows how in the near future it is possible to plan their supplies of fossil fuels. In the face of some uncertainty still present in this field, the adaptability of the power plants to the many and uncertain constraints of the demand constitutes a favourable and important factor [fr

  20. Device for underwater use in nuclear power stations with an electrical distributor

    International Nuclear Information System (INIS)

    1988-01-01

    The electrical connections for the different equipments used underwater are taken to a distributor via waterproof connectors. This distributor is situated in the head of a bell open at the bottom. When the bell is lowered into the water, water will penetrate into it, but only to a certain level, so that the water level inside the bell does not reach the distributor. This air cushion therefore protects the connections on the distributor against water entering them. (DG) [de

  1. 1300MVA steam-turbine generators for Kansai Electric Power's Oi Nuclear Power Station

    Energy Technology Data Exchange (ETDEWEB)

    Oishi, N; Amagasa, N; Ito, H; Yagi, K [Mitsubishi Electric Corp., Kobe (Japan). Kobe Works

    1977-06-01

    Mitsubishi Electric has completed two 1300 MVA generators, equipped with 5500kW brushless exciters, that will be the No. 1 and No. 2 generators of the Oi plant. They are among the largest anywhere, and incorporate such technological innovations as water cooling of the stator coil and asymmetrical arrangement of the rotor slots. The article discusses generator specifications and construction, the brushless exciter, and the results of factory tests.

  2. The Issue of Unit Constraints and the Non-Confiscatory Electricity Market

    DEFF Research Database (Denmark)

    Haji Bashi, Mazaher; Rahmati, Iman; Bak, Claus Leth

    2017-01-01

    Security constraint unit commitment is devised to drive the generation unit schedule in a deregulated environment. Generation bids, transmission system constraints and generation unit constraints are thoroughly considered in this optimization problem. It is acceptable that the transmission system...... normal condition constraints may affect the economic opportunities of the generation companies in the electricity market. Transmission system limitations are the inherent limits of the market environment but this is not true for the generation unit constraints. It means that the generation unit...... constraint of a certain player should not affect the economic opportunities of the rivals. If this happen, generation units can claim to the electricity market regulatory board. In this paper the effect of generation unit constraint on the market outcome is discussed. A fair mechanism is introduced in which...

  3. Systems for controlling the electric power of a boiling water reactor power station

    International Nuclear Information System (INIS)

    Fukunishi, Koyu; Kiyokawa, Kazuhiro.

    1975-01-01

    Object: To achieve automatic increase and decrease of electric output in accordance with a predetermined rate of increase or decrease in output when the power output is raised or lowered. Structure: An electric output signal from an atomic power plant is led to a differentiating circuit through a smoothing circuit to produce a signal for rate of change of time, and an error signal between this signal and a preset signal produced from a circuit for a preset rate of change of output with time is supplied to an analog adjuster through a limiter. In this way, the flow rate in the reactor core is adjusted by a speed controller to obtain an output of a predetermined rate of increase. The difference signal between the electric output signal and a desired value signal is passed through an absolute circuit to a comparator circuit for comparison with a predetermined threshold value setting signal. The output signal of the comparator is used to operate a relay to open the contact so as to prevent an increase or decrease in the output beyond the required level. (Kamimura, M.)

  4. Feasibility of free piston generation unit for electrical power provision

    Energy Technology Data Exchange (ETDEWEB)

    Harvey, R.; Roskilly, A.; Shaw, R.; French, C. [Newcastle Univ. (United Kingdom)

    2000-07-01

    Free piston linear engines offer the capability of providing power without the need to convert reciprocating motion into rotary motion. This allows for the utilisation of higher peak pressures during the combustion process and thus improves efficiency. The objective of this paper is to outline the potential benefits of a Free Piston Generator (FPG) and discuss the feasibility of this technology as a potential platform for electrical power provision. (authors)

  5. Electric heating of a unit for uranium trioxide production

    International Nuclear Information System (INIS)

    Faron, R.; Striff, A.

    1985-01-01

    Ammonium diuranate U 2 O 7 (NH 4 ) 2 containing about 50% of water is dried and transformed by calcination in uranium trioxide UO 3 . Drying and calcination was obtained by air heated by two burners using domestic fuel. In 1984 the plant was transformed for utilization of electric heating improving maintenance cost, decreasing heat losses and by energy saving the payback period on investment is of 2.6 years [fr

  6. Water-related constraints to the development of geothermal electric generating stations

    Energy Technology Data Exchange (ETDEWEB)

    Robertson, R.C.; Shepherd, A.D.; Rosemarin, C.S.; Mayfield, M.W.

    1981-06-01

    The water-related constraints, which may be among the most complex and variable of the issues facing commercialization of geothermal energy, are discussed under three headings: (1) water requirements of geothermal power stations, (2) resource characteristics of the most promising hydrothermal areas and regional and local water supply situations, and (3) legal issues confronting potential users of water at geothermal power plants in the states in which the resource areas are located. A total of 25 geothermal resource areas in California, New Mexico, Oregon, Idaho, Utah, Hawaii, and Alaska were studied. Each had a hydrothermal resource temperature in excess of 150/sup 0/C (300/sup 0/F) and an estimated 30-year potential of greater than 100-MW(e) capacity.

  7. Improved approach for electric vehicle rapid charging station placement and sizing using Google maps and binary lightning search algorithm

    Science.gov (United States)

    Shareef, Hussain; Mohamed, Azah

    2017-01-01

    The electric vehicle (EV) is considered a premium solution to global warming and various types of pollution. Nonetheless, a key concern is the recharging of EV batteries. Therefore, this study proposes a novel approach that considers the costs of transportation loss, buildup, and substation energy loss and that incorporates harmonic power loss into optimal rapid charging station (RCS) planning. A novel optimization technique, called binary lightning search algorithm (BLSA), is proposed to solve the optimization problem. BLSA is also applied to a conventional RCS planning method. A comprehensive analysis is conducted to assess the performance of the two RCS planning methods by using the IEEE 34-bus test system as the power grid. The comparative studies show that the proposed BLSA is better than other optimization techniques. The daily total cost in RCS planning of the proposed method, including harmonic power loss, decreases by 10% compared with that of the conventional method. PMID:29220396

  8. Applicability of Long Duration Exposure Facility environmental effects data to the design of Space Station Freedom electrical power system

    Science.gov (United States)

    Christie, Robert J.; Lu, Cheng-Yi; Aronoff, Irene

    1992-01-01

    Data defining space environmental effects on the Long Duration Exposure Facility (LDEF) are examined in terms of the design of the electrical power system (EPS) of the Space Station Freedom (SSF). The significant effects of long-term exposure to space are identified with respect to the performance of the LDEF's materials, components, and systems. A total of 57 experiments were conducted on the LDEF yielding information regarding coatings, thermal systems, electronics, optics, and power systems. The resulting database is analyzed in terms of the specifications of the SSF EPS materials and subsystems and is found to be valuable in the design of control and protection features. Specific applications are listed for findings regarding the thermal environment, atomic oxygen, UV and ionizing radiation, debris, and contamination. The LDEF data are shown to have a considerable number of applications to the design and planning of the SSF and its EPS.

  9. Probabilistic Physics-Based Risk Tools Used to Analyze the International Space Station Electrical Power System Output

    Science.gov (United States)

    Patel, Bhogila M.; Hoge, Peter A.; Nagpal, Vinod K.; Hojnicki, Jeffrey S.; Rusick, Jeffrey J.

    2004-01-01

    This paper describes the methods employed to apply probabilistic modeling techniques to the International Space Station (ISS) power system. These techniques were used to quantify the probabilistic variation in the power output, also called the response variable, due to variations (uncertainties) associated with knowledge of the influencing factors called the random variables. These uncertainties can be due to unknown environmental conditions, variation in the performance of electrical power system components or sensor tolerances. Uncertainties in these variables, cause corresponding variations in the power output, but the magnitude of that effect varies with the ISS operating conditions, e.g. whether or not the solar panels are actively tracking the sun. Therefore, it is important to quantify the influence of these uncertainties on the power output for optimizing the power available for experiments.

  10. An aerial radiological survey of the South Texas Project Electric Generating Station and surrounding area, Bay City, Texas

    International Nuclear Information System (INIS)

    Thompson, J.M.

    1988-12-01

    An aerial radiological survey was conducted over the South Texas Project Electric Generating Station (STPEGS) near Bay City, Texas, during the period 25 March to 4 April 1988. The purpose of the 259-square-kilometer (100-square-mile) survey was to document the terrestrial gamma environment of the plant and surrounding area. An exposure rate contour map at 1 meter above ground level (AGL) was constructed from the gamma data and overlaid on an aerial photograph and map of the area. Exposure rates were observed up to 10μR/h over land. No areas of enhanced exposure rates were observed. Ground-based exposure rate measurements and soil samples were obtained to support the aerial data. Oblique aerial photographs of the plant were also acquired during the survey. 9 refs., 4 figs., 1 tab

  11. Improved approach for electric vehicle rapid charging station placement and sizing using Google maps and binary lightning search algorithm.

    Directory of Open Access Journals (Sweden)

    Md Mainul Islam

    Full Text Available The electric vehicle (EV is considered a premium solution to global warming and various types of pollution. Nonetheless, a key concern is the recharging of EV batteries. Therefore, this study proposes a novel approach that considers the costs of transportation loss, buildup, and substation energy loss and that incorporates harmonic power loss into optimal rapid charging station (RCS planning. A novel optimization technique, called binary lightning search algorithm (BLSA, is proposed to solve the optimization problem. BLSA is also applied to a conventional RCS planning method. A comprehensive analysis is conducted to assess the performance of the two RCS planning methods by using the IEEE 34-bus test system as the power grid. The comparative studies show that the proposed BLSA is better than other optimization techniques. The daily total cost in RCS planning of the proposed method, including harmonic power loss, decreases by 10% compared with that of the conventional method.

  12. Research at United States Antarctic stations during the International Magnetosphere Study

    International Nuclear Information System (INIS)

    Rosenberg, T.J.

    1982-01-01

    During the International Magnetospheric Study (IMS) the U.S. operated programs at McMurdo, Siple, South Pole, and Palmer stations and at the Soviet Vostok station. Details concerning measurement locations are considered, and program summaries are provided. The programs are related to the study of geomagnetic variations, magnetic pulsations in the polar cap, cosmic noise absorption, VLF radio waves, auroral photometry, the morphology and dynamics of visible auroral forms, cosmic ray intensity variations, and auroral infrasonic waves. One program is based on the utilization of VHF Doppler auroral radar

  13. Considerations for increasing unit 1 spent fuel pool capacity at the Laguna Verde station

    International Nuclear Information System (INIS)

    Vera, A.

    1992-01-01

    To increase the spent fuel storage capacity at the Laguna Verde Station in a safe and economical manner and assure a continuous operation of the first Mexican Nuclear Plant, Comision Federal de Electricidad (CFE), the Nation's Utility, seeked alternatives considering the overall world situation, the safety and licensing aspects, as well as the economics and the extent of the nuclear program of Mexico. This paper describes the alternatives considered, their evaluation and how the decision taken by CFE in this field, provides the Laguna Verde Station with a maximum of 37 years storage capacity plus full core reserve

  14. Safety Evaluation Report related to the operation of Limerick Generating Station, Units 1 and 2 (Docket Nos. 50-352 and 50-353). Supplement No. 4

    International Nuclear Information System (INIS)

    1985-05-01

    In August 1983 the staff of the Nuclear Regulatory Commission issued its Safety Evaluation Report (NUREG-0991) regarding the application of the Philadelphia Electric Company (the applicant) for licenses to operate the Limerick Generating Station, Units 1 and 2 located on a site in Montgomery and Chester Counties, Pennsylvania. A license (NPF-27) for the operation of Limerick Unit 1 was issued on October 26, 1984. The license, which was restricted to a five percent power level, contained conditions which required resolution prior to proceeding beyond the five percent power level. This Supplement 4 to the SER addresses some of those technical issues and their associated license conditions which require resolution prior to proceeding beyond the five percent power level. The remaining issues to be addressed prior to proceeding beyond the five percent power level will be addressed in a later supplement to this report. This Supplement 4 to the SER also contains the comments made by the Advisory Committee on Reactor Safeguards in its report dated November 6, 1984, regarding full power operation of Limerick Unit 1

  15. Techno-economic and sensitivity analysis for grid-connected renewable energy electric boat charging station in Terengganu

    Directory of Open Access Journals (Sweden)

    Salleh N. A. S.

    2017-01-01

    Full Text Available In order to encourage the eco-friendly technologies in transportation sector, the reliance on fuel need to be reduced and the use of renewable energy (RE technology as energy source are widely explored by researchers. Thus, this study focus on the feasibility of developing grid-connected renewable energy electric boat charging station for the fishermen in Terengganu using simulation-based method by HOMER software. Five year solar radiation and wind speed data were collected at Universiti Sultan Zainal Abidin (UNISZA weather station. For load profile, the information about fishing activities and the amount of subsidy spent by the government were obtained from the interview session with the fishermen and validated with Lembaga Kemajuan Ikan Malaysia (LKIM. The results acquired are compared between grid-only and grid-connected RE systems in term of net present cost (NPC, operational cost and payback period. A sensitivity analysis is done to find the minimal Feed-in Tariff (FiT rate that can be implemented in order to encourage the use of RE system in this sector. Then, the relationship between FiT and NPC, payback period and emission of pollutants are analyzed. At current FiT rates RM 0.813/kWh, hybrid grid-PV system manages to achieve its optimal in generating high income from selling the power to the grid with convincing amount of electricity production and short payback period. It is concluded at minimum RM 0.56/kWh of FiT, the grid-connected RE system is possible to be developed because its performance shows better outcome compared to the grid-only system.

  16. Assessment of the use of vanadium redox flow batteries for energy storage and fast charging of electric vehicles in gas stations

    International Nuclear Information System (INIS)

    Cunha, Álvaro; Brito, F.P.; Martins, Jorge; Rodrigues, Nuno; Monteiro, Vitor; Afonso, João L.; Ferreira, Paula

    2016-01-01

    A network of conveniently located fast charging stations is one of the possibilities to facilitate the adoption of Electric Vehicles (EVs). This paper assesses the use of fast charging stations for EVs in conjunction with VRFBs (Vanadium Redox Flow Batteries). These batteries are charged during low electricity demand periods and then supply electricity for the fast charging of EVs during day, thus implementing a power peak shaving process. Flow batteries have unique characteristics which make them especially attractive when compared with conventional batteries, such as their ability to decouple rated power from rated capacity, as well as their greater design flexibility and nearly unlimited life. Moreover, their liquid nature allows their installation inside deactivated underground gas tanks located at gas stations, enabling a smooth transition of gas stations' business model towards the emerging electric mobility paradigm. A project of a VRFB system to fast charge EVs taking advantage of existing gas stations infrastructures is presented. An energy and cost analysis of this concept is performed, which shows that, for the conditions tested, the project is technologically and economically viable, although being highly sensitive to the investment costs and to the electricity market conditions. - Highlights: • Assessment of Vanadium Redox Flow Battery use for EV fast charge in gas stations. • This novel system proposal allows power peak shaving and use of deactivated gas tanks. • Philosophy allows seamless business transition towards the Electric Mobility paradigm. • Project is technologically and economically viable, although with long payback times. • Future Cost cuts due to technology maturation will consolidate project attractiveness.

  17. System Definition Document: Reactor Data Necessary for Modeling Plutonium Disposition in Catawba Nuclear Station Units 1 and 2

    International Nuclear Information System (INIS)

    Ellis, R.J.

    2000-01-01

    The US Department of Energy (USDOE) has contracted with Duke Engineering and Services, Cogema, Inc., and Stone and Webster (DCS) to provide mixed-oxide (MOX) fuel fabrication and reactor irradiation services in support of USDOE's mission to dispose of surplus weapons-grade plutonium. The nuclear station units currently identified as mission reactors for this project are Catawba Units 1 and 2 and McGuire Units 1 and 2. This report is specific to Catawba Nuclear Station Units 1 and 2, but the details and materials for the McGuire reactors are very similar. The purpose of this document is to present a complete set of data about the reactor materials and components to be used in modeling the Catawba reactors to predict reactor physics parameters for the Catawba site. Except where noted, Duke Power Company or DCS documents are the sources of these data. These data are being used with the ORNL computer code models of the DCS Catawba (and McGuire) pressurized-water reactors

  18. Unit: Electric Circuits, Inspection Pack, National Trial Print.

    Science.gov (United States)

    Australian Science Education Project, Toorak, Victoria.

    As a part of the unit materials in the series produced by the Australian Science Education Project, this teacher edition is primarily composed of a core relating to simple circuits, a test form, and options. Options are given under the headings: Your Invention; "How Long Does a Call Last?"; One, Two, Three Wires; Parallel Circuits; More…

  19. Dedicated auxiliary power units for Hybrid Electric Vehicles

    NARCIS (Netherlands)

    Mourad, S.; Weijer, C.J.T. van de

    1998-01-01

    The use of a dedicated auxiliary power unit is essential to utilize the potential that hybrid vehicles offer for efficient and ultra-clean transportation. An example of a hybrid project at the TNO Road-Vehicles Research Institute shows the development and the results of a dedicated auxiliary power

  20. Brunswick Steam Electric Plant, Units 1 and 2. Annual operating report for 1976

    International Nuclear Information System (INIS)

    1977-01-01

    Net electrical energy generated by Unit 1 was 30,399 MWH with the generator on line 334.5 hrs. Unit 2 generated 2,481,014 MWH with the generator on line 4,915.53 hrs. Information is presented concerning operations, shutdowns and power reductions, maintenance, power generation, modifications, changes to operational procedures, radiation exposures, and leak rate testing

  1. An integrated DEA-COLS-SFA algorithm for optimization and policy making of electricity distribution units

    International Nuclear Information System (INIS)

    Azadeh, A.; Ghaderi, S.F.; Omrani, H.; Eivazy, H.

    2009-01-01

    This paper presents an integrated data envelopment analysis (DEA)-corrected ordinary least squares (COLS)-stochastic frontier analysis (SFA)-principal component analysis (PCA)-numerical taxonomy (NT) algorithm for performance assessment, optimization and policy making of electricity distribution units. Previous studies have generally used input-output DEA models for benchmarking and evaluation of electricity distribution units. However, this study proposes an integrated flexible approach to measure the rank and choose the best version of the DEA method for optimization and policy making purposes. It covers both static and dynamic aspects of information environment due to involvement of SFA which is finally compared with the best DEA model through the Spearman correlation technique. The integrated approach would yield in improved ranking and optimization of electricity distribution systems. To illustrate the usability and reliability of the proposed algorithm, 38 electricity distribution units in Iran have been considered, ranked and optimized by the proposed algorithm of this study.

  2. Guide to federal regulation of sales of imported electricity in Canada, Mexico and the United States

    International Nuclear Information System (INIS)

    2005-01-01

    This Guide to Federal Regulation of Sales of Imported Electricity in Canada, Mexico, and the United States promotes cross-border electricity trade. It provides information on federal regulation of cross-border electricity trade and is intended to be used together with a companion guide called the North American Regulation of International Electricity Trade which outlines regulations for the construction and operation of cross-border power lines and the permitting requirements for electricity exports and imports between Canada, Mexico and the United States. The guide outlines the basic elements of the general federal regulatory process that applies to a given North American cross-border electricity trade. It offers an improved understanding of the applicable country's federal regulatory regime. Different federal government agencies within each country may regulate different aspects of a particular cross-border electricity trade. This guide does not examine the requirements that may apply at the state or provincial government levels. Rather, it is a collaborative effort of the 3 national energy departments and energy regulators that support the Experts Group on Electricity Regulatory Issues, a specialized unit assembled by the North American Energy Working Group (NAEWG). It was noted that the energy policies and regulations of each nation can change periodically

  3. Geothermal energy in the western United States and Hawaii: Resources and projected electricity generation supplies

    International Nuclear Information System (INIS)

    1991-09-01

    Geothermal energy comes from the internal heat of the Earth, and has been continuously exploited for the production of electricity in the United States since 1960. Currently, geothermal power is one of the ready-to-use baseload electricity generating technologies that is competing in the western United States with fossil fuel, nuclear and hydroelectric generation technologies to provide utilities and their customers with a reliable and economic source of electric power. Furthermore, the development of domestic geothermal resources, as an alternative to fossil fuel combustion technologies, has a number of associated environmental benefits. This report serves two functions. First, it provides a description of geothermal technology and a progress report on the commercial status of geothermal electric power generation. Second, it addresses the question of how much electricity might be competitively produced from the geothermal resource base. 19 figs., 15 tabs

  4. Long-term security of electrical and control engineering equipment in nuclear power stations to withstand a loss of coolant accident

    International Nuclear Information System (INIS)

    Mueller, H.

    1996-01-01

    Electrical and control engineering equipment, which has to function even after many years of operation in the event of a fault in a saturated steam atmosphere of 160 C maximum, is essential in nuclear power stations in order to control a loss of coolant accident. The nuclear power station operators have, for this purpose, developed verification strategies for groups of components, by means of which it is ensured that the electrical and control engineering components are capable of dealing with a loss of coolant accident even at the end of their planned operating life. (orig.) [de

  5. IEEE Std 383-1974: IEEE standard for type test of Class IE electric cables, field splices, and connections for nuclear power generating stations

    International Nuclear Information System (INIS)

    Anon.

    1992-01-01

    This standard provides direction for establishing type tests which may be used in qualifying Class 1E electric cables, field splices, and other connections for service in nuclear power generating stations. General guidelines for qualifications are given in IEEE Std 323-1974, Standard for Qualifying Class IE Electric Equipment for Nuclear Power Generating Stations. Categories of cables covered are those used for power control and instrumentation services. Though intended primarily to pertain to cable for field installation, this guide may also be used for the qualification of internal wiring of manufactured devices. This guide does not cover cables for service within the reactor vessel

  6. POLLUTION PREVENTION OPPORTUNITY ASSESSMENT - UNITED STATES NAVAL BASE NORFOLK NAVAL AIR STATION

    Science.gov (United States)

    This report summarizes work conducted at the U.S. Navy's Naval Base Norfolk, Naval Air Station (NAS) located at Sewells Point in Norfolk, Virginia, under the U.S. Environmental Protection Agency's (EPA) Waste Reduction Evaluations at Federal Sites (WREAFS) Program. This project w...

  7. Multi-station synthesis of early twentieth century surface atmospheric electricity measurements for upper tropospheric properties

    Directory of Open Access Journals (Sweden)

    R. G. Harrison

    2007-07-01

    Full Text Available The vertical columnar current density in the global atmospheric electrical circuit depends on the local columnar resistance. A simple model for the columnar resistance is suggested, which separates the local boundary layer component from the upper troposphere cosmic ray component, and calculates the boundary layer component from a surface measurement of air conductivity. This theory is shown to provide reasonable agreement with observations. One application of the simple columnar model theory is to provide a basis for the synthesis of surface atmospheric electrical measurements made simultaneously at several European sites. Assuming the ionospheric potential to be common above all the sites, the theoretical air-earth current density present in the absence of a boundary layer columnar resistance can be found by extrapolation. This is denoted the free troposphere limit air-earth current density, J0. Using early surface data from 1909 when no ionospheric potential data are available for corroboration, J0 is found to be ~6 pA m−2, although this is subject to uncertainties in the data and limitations in the theory. Later (1966–1971 European balloon and surface data give J0=2.4 pA m−2.

  8. An assessment of the cyber security legislation and its impact on the United States electrical sector

    Science.gov (United States)

    Born, Joshua

    The purpose of this research was to examine the cyber-security posture for the United States' electrical grid, which comprises a major component of critical infrastructure for the country. The United States electrical sector is so vast, that the Department of Homeland Security (DHS) estimates, it contains more than 6,413 power plants (this includes 3,273 traditional electric utilities and 1,738 nonutility power producers) with approximately 1,075 gigawatts of energy produced on a daily basis. A targeted cyber-security attack against the electric grid would likely have catastrophic results and could even serve as a precursor to a physical attack against the United States. A recent report by the consulting firm Black and Veatch found that one of the top five greatest concerns for United States electric utilities is the risk that cybersecurity poses to their industry and yet, only one-third state they are currently prepared to meet the increasingly likely threat. The report goes on to state, "only 32% of electric utilities surveyed had integrated security systems with the proper segmentation, monitoring and redundancies needed for cyber threat protection. Another 48 % said they did not" Recent estimates indicate that a large-scale cyber-attack against this sector could cost the United States economy as much as a trillion dollars within a weeks' time. Legislative efforts in the past have primarily been focused on creating mandates that encourage public and private partnership, which have been not been adopted as quickly as desired. With 85 % of all electric utilities being privately owned, it is key that the public and private sector partner in order to mitigate risks and respond as a cohesive unit in the event of a major attack. Keywords: Cybersecurity, Professor Riddell, cyber security, energy, intelligence, outlook, electrical, compliance, legislation, partnerships, critical infrastructure.

  9. Ecological effects of nuclear steam electric station operations on estuarine systems. Final report

    International Nuclear Information System (INIS)

    Mihursky, J.A.

    1983-01-01

    This report summarizes the findings of studies of the impact of the Calvert Cliffs Nuclear Power Plant on the aquatic biota of Chesapeake Bay. Physical findings show that the typical radial extent of influence of the discharge on the physical and chemical environment of the Bay is rather limited (< 2 km). This suggestion is bolstered by findings of phytoplankton and zooplankton studies: when effects were noted at all, they only appeared at sampling stations nearest (within 2 km of) the discharge. Also, direct entrainment effects on these groups were either small (in the case of phytoplankton) or species-specific (in the case of zooplankton). Benthos showed mixed responses to plant operations - the populations of some species were enhanced, one species was adversely affected, and others were unaffected. The major plant effect on the benthos was due to habitat resource enrichment, and the consequence was higher standing stocks (e.g., more food for fish) in the affected area. Direct plant effects on finfish are dominated by impingement. Mortality as a result of impingement, for many species, tends to be moderate to slight. Effects as a result of entrainment of eggs and larvae are limited because the Calvert Cliffs area is not a major spawning location for any species. In sum, the Calvert Cliffs plant appears to have a limited effect on the Chesapeake Bay ecosystem. 180 references, 6 figures, 18 tables

  10. Electrical Power Generated from Tidal Currents and Delivered to USCG Station Eastport, ME

    Science.gov (United States)

    2011-01-21

    35 Theory of Operation The ORPC Pre-Commercial Beta Turbine Generator Unit (“Beta TGU”) uses a hydrokinetic cross flow turbine based on Darrieus ...development in the wind turbine industry. The power coefficient (a measure of energy extraction effectiveness) is defined as follows: 31 2 turbine ...stream area of the device. Axial flow wind turbines have demonstrated power coefficients to an estimated 48% which approaches the theoretical “Betz

  11. Swarm Intelligence-Based Smart Energy Allocation Strategy for Charging Stations of Plug-In Hybrid Electric Vehicles

    Directory of Open Access Journals (Sweden)

    Imran Rahman

    2015-01-01

    Full Text Available Recent researches towards the use of green technologies to reduce pollution and higher penetration of renewable energy sources in the transportation sector have been gaining popularity. In this wake, extensive participation of plug-in hybrid electric vehicles (PHEVs requires adequate charging allocation strategy using a combination of smart grid systems and smart charging infrastructures. Daytime charging stations will be needed for daily usage of PHEVs due to the limited all-electric range. Intelligent energy management is an important issue which has already drawn much attention of researchers. Most of these works require formulation of mathematical models with extensive use of computational intelligence-based optimization techniques to solve many technical problems. In this paper, gravitational search algorithm (GSA has been applied and compared with another member of swarm family, particle swarm optimization (PSO, considering constraints such as energy price, remaining battery capacity, and remaining charging time. Simulation results obtained for maximizing the highly nonlinear objective function evaluate the performance of both techniques in terms of best fitness.

  12. Commercialization of new energy technologies. Appendix A. Case study 1: central station electric power generation technologies

    International Nuclear Information System (INIS)

    1976-06-01

    The results of a survey on Technologies for Central Power Generation are presented. The central power generation technologies selected for consideration were: fusion; breeder reactors; solar electric (thermal); geothermal; and magnetohydrodynamics. The responses of industry executives who make key investment decisions concerning new energy technologies and who to identify the problems faced in the development and commercialization of new energy systems are presented. Evaluation of these responses led to the following recommendations: increase industry input into the R, D and D planning process; establish and advocate priorities for new technologies based on detailed analysis of a technology's value in terms of overall national goals; create a mechanism for a joint ERDA/industry appraisal of priorities and programs; increase level of federal funding or subsidy of new technology demonstrations; and focus the activities of the national laboratories on basic research and very early product development; and emphasize industry involvement in systems development

  13. Hierarchical control of a photovoltaic/battery based DC microgrid including electric vehicle wireless charging station

    DEFF Research Database (Denmark)

    Xiao, Zhao xia; Fan, Haodong; Guerrero, Josep M.

    2017-01-01

    In this paper, the hierarchical control strategy of a photovoltaic/battery based dc microgrid is presented for electric vehicle (EV) wireless charging. Considering irradiance variations, battery charging/discharging requirements, wireless power transmission characteristics, and onboard battery...... coils, receiving coils and compensation capacitors, the wireless power transmission system is designed to be resonant when it is operating at the rated power, with the aim to achieve the optimum transmission system efficiency. Simulation and experimental results of the hierarchical control...... charging power change and other factors, the possible operation states are obtained. A hierarchical control strategy is established, which includes central and local controllers. The central controller is responsible for the selection and transfer of operation states and the management of the local...

  14. Study of the mechanical properties of the electric power station components: the punch test

    International Nuclear Information System (INIS)

    Isselin, J.

    2003-03-01

    The aging of the electric production park implies an increasing need of knowledge concerning the evolution of the mechanical properties of its components. With regard to this problem, the availability in material is more and more small. This work proposes to characterize these properties through a mechanical test called Punch test. The main characteristic of this test is to use very small volume samples. The development of this test has been carried out by the study of a 15 MDV 4-05 steel coming from a steam drum of a thermal power plant after 145000 hours of service. At first, we have measured the influence of the parameters of this test. Then, the study has dealt more particularly on the transition temperature of the material. With the finite element simulation method, the strain hardening coefficient of the material has been determined. (O.M.)

  15. Electricity consumers' council statement of case to the Sizewell 'B' power station public inquiry

    International Nuclear Information System (INIS)

    Barnes, M.

    1983-01-01

    Of the four arguments used in favour of Sizewell, the ECC considers that the economic benefit case is much the most important. Consumers will need to be convinced above all that Sizewell will help to restrain the growth of electricity prices. Of the other three arguments, plant need is not taken very seriously by the Board, making provision for future investment options hardly appears in the Statement of Case, and fuel diversity - while an important objective - can only be examined properly within the context of long-term investment strategy and relates only marginally to Sizewell as a self-standing project. Because a decision about Sizewell can in any case only be fully evaluated within the context of long-term plant strategy, the ECC has also briefly considered the most important long-term issues - the existence or otherwise of a nuclear programme, the questions surrounding technology acquisition and alternative energy investments - against which the Sizewell decision should be viewed. (author)

  16. 75 FR 15462 - PPL Susquehanna, LLC; Susquehanna Steam Electric Station, Units 1 and 2; Exemption

    Science.gov (United States)

    2010-03-29

    ... section through its Commission-approved Physical Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Cyber Security Plan referred to collectively hereafter as `security plans...

  17. 76 FR 58844 - Virginia Electric and Power Company, Surry Power Station, Units 1 and 2; Exemption

    Science.gov (United States)

    2011-09-22

    ... effectively addressed through staff augmentation that can only be practically achieved through the use of work... quality of the human environment published in the Federal Register on August 31, 2011 (76 FR 54259). This...

  18. 78 FR 28000 - Entergy Louisiana, LLC and Entergy Operations, Inc.; Waterford Stream Electric Station, Unit No...

    Science.gov (United States)

    2013-05-13

    ... Regulation satisfactory documentary evidence that New ELL has obtained the appropriate amount of insurance..., see the initial application dated September 27, 2012 (Agencywide Documents Access and Management...

  19. 76 FR 12137 - Entergy Operations, Inc. Waterford Steam Electric Station, Unit 3 Exemption

    Science.gov (United States)

    2011-03-04

    ... of the plant and personnel safety, would maintain protection of health and safety of the public...-informed evaluation process has shown to be significant to public health and safety; (2) performing health physics or chemistry duties required as a member of the onsite emergency response organization's minimum...

  20. 75 FR 15746 - Entergy Operations, Inc., Waterford Steam Electric Station, Unit 3; Exemption

    Science.gov (United States)

    2010-03-30

    ... Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Cyber Security Plan... necessary changes to its security plans. Pursuant to 10 CFR 51.32, ``Finding of no significant impact,'' the... and implementing comprehensive site security programs. The amendments to 10 CFR 73.55 published on...