  1. HEAVY WATER COMPONENTS TEST REACTOR DECOMMISSIONING

    Energy Technology Data Exchange (ETDEWEB)

    Austin, W.; Brinkley, D.

    2011-10-13

    The Heavy Water Components Test Reactor (HWCTR) Decommissioning Project was initiated in 2009 as a Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) Removal Action with funding from the American Recovery and Reinvestment Act (ARRA). This paper summarizes the history prior to 2009, the major D&D activities, and final end state of the facility at completion of decommissioning in June 2011. The HWCTR facility was built in 1961, operated from 1962 to 1964, and is located in the northwest quadrant of the Savannah River Site (SRS) approximately three miles from the site boundary. The HWCTR was a pressurized heavy water test reactor used to develop candidate fuel designs for heavy water power reactors. In December of 1964, operations were terminated and the facility was placed in a standby condition as a result of the decision by the U.S. Atomic Energy Commission to redirect research and development work on heavy water power reactors to reactors cooled with organic materials. For about one year, site personnel maintained the facility in a standby status, and then retired the reactor in place. In the early 1990s, DOE began planning to decommission HWCTR. Yet, in the face of new budget constraints, DOE deferred dismantlement and placed HWCTR in an extended surveillance and maintenance mode. The doors of the reactor facility were welded shut to protect workers and discourage intruders. In 2009 the $1.6 billion allocation from the ARRA to SRS for site footprint reduction at SRS reopened the doors to HWCTR - this time for final decommissioning. Alternative studies concluded that the most environmentally safe, cost effective option for final decommissioning was to remove the reactor vessel, both steam generators, and all equipment above grade including the dome. The transfer coffin, originally above grade, was to be placed in the cavity vacated by the reactor vessel and the remaining below grade spaces would be grouted. Once all above equipment

  2. Heavy Water Components Test Reactor Decommissioning - Major Component Removal

    Energy Technology Data Exchange (ETDEWEB)

    Austin, W.; Brinkley, D.

    2010-05-05

    The Heavy Water Components Test Reactor (HWCTR) facility (Figure 1) was built in 1961, operated from 1962 to 1964, and is located in the northwest quadrant of the Savannah River Site (SRS) approximately three miles from the site boundary. The HWCTR facility is on high, well-drained ground, about 30 meters above the water table. The HWCTR was a pressurized heavy water test reactor used to develop candidate fuel designs for heavy water power reactors. It was not a defense-related facility like the materials production reactors at SRS. The reactor was moderated with heavy water and was rated at 50 megawatts thermal power. In December of 1964, operations were terminated and the facility was placed in a standby condition as a result of the decision by the U.S. Atomic Energy Commission to redirect research and development work on heavy water power reactors to reactors cooled with organic materials. For about one year, site personnel maintained the facility in a standby status, and then retired the reactor in place. In 1965, fuel assemblies were removed, systems that contained heavy water were drained, fluid piping systems were drained, deenergized and disconnected and the spent fuel basin was drained and dried. The doors of the reactor facility were shut and it wasn't until 10 years later that decommissioning plans were considered and ultimately postponed due to budget constraints. In the early 1990s, DOE began planning to decommission HWCTR again. Yet, in the face of new budget constraints, DOE deferred dismantlement and placed HWCTR in an extended surveillance and maintenance mode. The doors of the reactor facility were welded shut to protect workers and discourage intruders. The $1.6 billion allocation from the American Recovery and Reinvestment Act to SRS for site clean up at SRS has opened the doors to the HWCTR again - this time for final decommissioning. During the lifetime of HWCTR, 36 different fuel assemblies were tested in the facility. Ten of these

  3. Decommissioning of commercial reactor

    Energy Technology Data Exchange (ETDEWEB)

    Yui, Kohei [Japan Atomic Power Co., Tokyo (Japan)

    1997-02-01

    In the case of nuclear reactors, the diversion is often difficult as they are highly purposive, the disassembling is not easy as they are robust, and attention is required to handle the equipment containing radioactive substances. Decommissioning is defined as all the measures taken from the state that facilities become unused to the state of becoming green field. In Japan, already 40 years have elapsed since the effort for nuclear power was begun, and in this paper, the present state and future subjects of the decommissioning of nuclear power stations are summarized at the opportunity that the stop of commercial operation of Tokai Nuclear Power Station was decided recently. In the Tokai Nuclear Power Station, 166 MWe graphite-moderated, carbon dioxide-cooled reactor called improved Calder Hall type is installed, which started the operation in 1966. The circumstances of the decision to stop its operation are explained. The basic policy of the decommissioning of commercial nuclear power stations has been already published by the Advisory Committee for Energy. The state of the decommissioning in various foreign countries is reported. In Japan, the state of green field was realized in 1996 in the decommissioning of the JPDR in Japan Atomic Energy Research institute, and the decommissioning of the atomic powered ship ``Mutsu`` was completed. (K.I.)

  4. Technology, safety and costs of decommissioning a reference boiling water reactor power station. Volume 1. Main report. Technical report, September 1977-October 1979

    Energy Technology Data Exchange (ETDEWEB)

    Oak, H.D.; Holter, G.M.; Kennedy, W.E. Jr.; Konzek, G.J.

    1980-06-01

    Technology, safety and cost information is given for the conceptual decommissioning of a large (1100MWe) boiling water reactor (BWR) power station. Three approaches to decommissioning, immediate dismantlement, safe storage with deferred dismantlement and entombment, were studied to obtain comparisons between costs, occupational radiation doses, potential dose to the public and other safety impacts. It also shows the sensitivity of decommissioning safety and costs to the power rating of a BWR in the range of 200 to 1100 MWE.

  5. A study of implementing In-Cycle-Shuffle strategy to a decommissioning boiling water reactor

    Energy Technology Data Exchange (ETDEWEB)

    Chen, Chung-Yuan, E-mail: tuckjason@iner.gov.tw; Tung, Wu-Hsiung; Yaur, Shyun-Jung

    2017-06-15

    Highlights: • A loading pattern strategy ICS (In-Cycle-Shuffle) was implemented to the last cycle of the boiling water reactor. • The best power sharing distribution and ICS timing was found. • A new parameter “Burnup sharing” is presented to evaluate ICS strategy. - Abstract: In this paper, a loading pattern strategy In-Cycle-Shuffle (ICS) is implemented to the last cycle of the boiling water reactor (BWR) before decommissioning to save the fuel cycle cost. This method needs a core shutdown during the operation of a cycle to change the loading pattern to gain more reactivity. The reactivity model is used to model the ICS strategy in order to find out the best ICS timing and the optimum power sharing distribution before ICS and after ICS. Several parameters of reactivity model are modified and the effect of burnable poison, gadolinium (Gd), is considered in this research. Three cases are presented and it is found that the best ICS timing is at about two-thirds of total cycle length no matter the poisoning effect of Gd is considered or not. According to the optimum power sharing distribution result, it is suggested to decrease the once burnt power and increase the thrice burnt fuel power as much as possible before ICS. After ICS, it is suggested to increase the positive reactivity fuel power and decrease the thrice burnt fuel power as much as possible. A new parameter “Burnup sharing” is presented to evaluate the special case whose EOC power weighting factor and the burnup accumulation factor in the reactivity model are quite different.

  6. Activation calculation for the dismantling and decommissioning of a light water reactor using MCNP™ with ADVANTG and ORIGEN-S

    Science.gov (United States)

    Schlömer, Luc; Phlippen, Peter-W.; Lukas, Bernard

    2017-09-01

    The decommissioning of a light water reactor (LWR), which is licensed under § 7 of the German Atomic Energy Act, following the post-operational phase requires a comprehensive licensing procedure including in particular radiation protection aspects and possible impacts to the environment. Decommissioning includes essential changes in requirements for the systems and components and will mainly lead to the direct dismantling. In this context, neutron induced activation calculations for the structural components have to be carried out to predict activities in structures and to estimate future costs for conditioning and packaging. To avoid an overestimation of the radioactive inventory and to calculate the expenses for decommissioning as accurate as possible, modern state-of-the-art Monte-Carlo-Techniques (MCNP™) are applied and coupled with present-day activation and decay codes (ORIGEN-S). In this context ADVANTG is used as weight window generator for MCNP™ i. e. as variance reduction tool to speed up the calculation in deep penetration problems. In this paper the calculation procedure is described and the obtained results are presented with a validation along with measured activities and photon dose rates measured in the post-operational phase. The validation shows that the applied calculation procedure is suitable for the determination of the radioactive inventory of a nuclear power plant. Even the measured gamma dose rates in the post-operational phase at different positions in the reactor building agree within a factor of 2 to 3 with the calculation results. The obtained results are accurate and suitable to support effectively the decommissioning planning process.

  7. Activation calculation for the dismantling and decommissioning of a light water reactor using MCNP™ with ADVANTG and ORIGEN-S

    Directory of Open Access Journals (Sweden)

    Schlömer Luc

    2017-01-01

    Full Text Available The decommissioning of a light water reactor (LWR, which is licensed under § 7 of the German Atomic Energy Act, following the post-operational phase requires a comprehensive licensing procedure including in particular radiation protection aspects and possible impacts to the environment. Decommissioning includes essential changes in requirements for the systems and components and will mainly lead to the direct dismantling. In this context, neutron induced activation calculations for the structural components have to be carried out to predict activities in structures and to estimate future costs for conditioning and packaging. To avoid an overestimation of the radioactive inventory and to calculate the expenses for decommissioning as accurate as possible, modern state-of-the-art Monte-Carlo-Techniques (MCNP™ are applied and coupled with present-day activation and decay codes (ORIGEN-S. In this context ADVANTG is used as weight window generator for MCNP™ i. e. as variance reduction tool to speed up the calculation in deep penetration problems. In this paper the calculation procedure is described and the obtained results are presented with a validation along with measured activities and photon dose rates measured in the post-operational phase. The validation shows that the applied calculation procedure is suitable for the determination of the radioactive inventory of a nuclear power plant. Even the measured gamma dose rates in the post-operational phase at different positions in the reactor building agree within a factor of 2 to 3 with the calculation results. The obtained results are accurate and suitable to support effectively the decommissioning planning process.

  8. Technology, safety and costs of decommissioning a reference boiling water reactor power station. Volume 2. Appendices. Technical report, September 1977-October 1979

    Energy Technology Data Exchange (ETDEWEB)

    Oak, H.D.; Holter, G.M.; Kennedy, W.E. Jr.; Konzek, G.J.

    1980-06-01

    Technology, safety and cost information is given for the conceptual decommissioning of a large (1100MWe) boiling water reactor (BWR) power station. Three approaches to decommissioning, immediate dismantlement, safe storage with deferred dismantlement and entombment, were studied to obtain comparisons between costs, occupational radiation doses, potential dose to the public and other safety impacts. It also shows the sensitivity of decommissioning safety and costs to the power rating of a BWR in the range of 200 to 1100 MWE. This volume contains the appendices.

  9. Technology, safety and costs of decommissioning a reference boiling water reactor power station. Appendices. Volume 2

    Energy Technology Data Exchange (ETDEWEB)

    Oak, H.D.; Holter, G.M.; Kennedy, W.E. Jr.; Konzek, G.J.

    1980-06-01

    Appendices are presented concerning the evaluations of decommissioning financing alternatives; reference site description; reference BWR facility description; radiation dose rate and concrete surface contamination data; radionuclide inventories; public radiation dose models and calculated maximum annual doses; decommissioning methods; generic decommissioning information; immediate dismantlement details; passive safe storage, continuing care, and deferred dismantlement details; entombment details; demolition and site restoration details; cost estimating bases; public radiological safety assessment details; and details of alternate study bases.

  10. Technology, Safety and Costs of Decommissioning Nuclear Reactors At Multiple-Reactor Stations

    Energy Technology Data Exchange (ETDEWEB)

    Wittenbrock, N. G.

    1982-01-01

    Safety and cost information is developed for the conceptual decommissioning of large (1175-MWe) pressurized water reactors (PWRs) and large (1155-MWe) boiling water reactors {BWRs) at multiple-reactor stations. Three decommissioning alternatives are studied: DECON (immediate decontamination), SAFSTOR (safe storage followed by deferred decontamination), and ENTOMB (entombment). Safety and costs of decommissioning are estimated by determining the impact of probable features of multiple-reactor-station operation that are considered to be unavailable at a single-reactor station, and applying these estimated impacts to the decommissioning costs and radiation doses estimated in previous PWR and BWR decommissioning studies. The multiple-reactor-station features analyzed are: the use of interim onsite nuclear waste storage with later removal to an offsite nuclear waste disposal facility, the use of permanent onsite nuclear waste disposal, the dedication of the site to nuclear power generation, and the provision of centralized services. Five scenarios for decommissioning reactors at a multiple-reactor station are investigated. The number of reactors on a site is assumed to be either four or ten; nuclear waste disposal is varied between immediate offsite disposal, interim onsite storage, and immediate onsite disposal. It is assumed that the decommissioned reactors are not replaced in one scenario but are replaced in the other scenarios. Centralized service facilities are provided in two scenarios but are not provided in the other three. Decommissioning of a PWR or a BWR at a multiple-reactor station probably will be less costly and result in lower radiation doses than decommissioning an identical reactor at a single-reactor station. Regardless of whether the light water reactor being decommissioned is at a single- or multiple-reactor station: • the estimated occupational radiation dose for decommissioning an LWR is lowest for SAFSTOR and highest for DECON • the estimated

  11. Technology, safety, and costs of decommissioning a reference pressurized water reactor power station. Appendices

    Energy Technology Data Exchange (ETDEWEB)

    Smith, R.I.; Konzek, G.J.; Kennedy, W.E. Jr.

    1978-05-01

    Detailed appendices are presented under the following headings: reference PWR facility description, reference PWR site description, estimates of residual radioactivity, alternative methods for financing decommissioning, radiation dose methodology, generic decommissioning activities, intermediate dismantlement activities, safe storage and deferred dismantlement activities, compilation of unit cost factors, and safety assessment details.

  12. 78 FR 64028 - Decommissioning of Nuclear Power Reactors

    Science.gov (United States)

    2013-10-25

    ... COMMISSION Decommissioning of Nuclear Power Reactors AGENCY: Nuclear Regulatory Commission. ACTION... regulatory guide (RG) 1.184 ``Decommissioning of Nuclear Power Reactors.'' This guide describes a method NRC... decommissioning process for nuclear power reactors. The revision takes advantage of the 13 years of...

  13. Decommissioning of the Salaspils Research Reactor

    Directory of Open Access Journals (Sweden)

    Abramenkovs Andris

    2011-01-01

    Full Text Available In May 1995, the Latvian government decided to shut down the Salaspils Research Reactor and to dispense with nuclear energy in the future. The reactor has been out of operation since July 1998. A conceptual study on the decommissioning of the Salaspils Research Reactor was drawn up by Noell-KRC-Energie- und Umwelttechnik GmbH in 1998-1999. On October 26th, 1999, the Latvian government decided to start the direct dismantling to “green-field” in 2001. The upgrading of the decommissioning and dismantling plan was carried out from 2003-2004, resulting in a change of the primary goal of decommissioning. Collecting and conditioning of “historical” radioactive wastes from different storages outside and inside the reactor hall became the primary goal. All radioactive materials (more than 96 tons were conditioned for disposal in concrete containers at the radioactive wastes depository “Radons” at the Baldone site. Protective and radiation measurement equipment of the personnel was upgraded significantly. All non-radioactive equipment and materials outside the reactor buildings were released for clearance and dismantled for reuse or conventional disposal. Contaminated materials from the reactor hall were collected and removed for clearance measurements on a weekly basis.

  14. Proceedings of the US Nuclear Regulatory Commission fifteenth water reactor safety information meeting: Volume 6, Decontamination and decommissioning, accident management, TMI-2

    Energy Technology Data Exchange (ETDEWEB)

    Weiss, A. J. [comp.

    1988-02-01

    This six-volume report contains 140 papers out of the 164 that were presented at the Fifteenth Water Reactor Safety Information Meeting held at the National Bureau of Standards, Gaithersburg, Maryland, during the week of October 26-29, 1987. The papers are printed in the order of their presentation in each session and describe progress and results of programs in nuclear safety research conducted in this country and abroad. This report, Volume 6, discusses decontamination and decommissioning, accident management, and the Three Mile Island-2 reactor accident. Thirteen reports have been cataloged separately.

  15. Decommissioning of the Tokamak Fusion Test Reactor

    Energy Technology Data Exchange (ETDEWEB)

    E. Perry; J. Chrzanowski; C. Gentile; R. Parsells; K. Rule; R. Strykowsky; M. Viola

    2003-10-28

    The Tokamak Fusion Test Reactor (TFTR) at the Princeton Plasma Physics Laboratory was operated from 1982 until 1997. The last several years included operations with mixtures of deuterium and tritium. In September 2002, the three year Decontamination and Decommissioning (D&D) Project for TFTR was successfully completed. The need to deal with tritium contamination as well as activated materials led to the adaptation of many techniques from the maintenance work during TFTR operations to the D&D effort. In addition, techniques from the decommissioning of fission reactors were adapted to the D&D of TFTR and several new technologies, most notably the development of a diamond wire cutting process for complex metal structures, were developed. These techniques, along with a project management system that closely linked the field crews to the engineering staff who developed the techniques and procedures via a Work Control Center, resulted in a project that was completed safely, on time, and well below budget.

  16. Decontamination and decommissioning of Shippingport commercial reactor

    Energy Technology Data Exchange (ETDEWEB)

    Schreiber, J. [Dept. of Energy, Pittsburgh, PA (United States)

    1989-11-01

    To a certain degree, the decontamination and decommissioning (D and D) of the Shippingport reactor was a joint venture with Duquesne Light Company. The structures that were to be decommissioned were to be removed to at least three feet below grade. Since the land had been leased from Duquesne Light, there was an agreement with them to return the land to them in a radiologically safe condition. The total enclosure volume for the steam and nuclear containment systems was about 1.3 million cubic feet, more than 80% of which was below ground. Engineering plans for the project were started in July of 1980 and the final environmental impact statement (EIS) was published in May of 1982. The plant itself was shut down in October of 1982 for end-of-life testing and defueling. The engineering services portion of the decommissioning plans was completed in September of 1983. DOE moved onto the site and took over from the Navy in September of 1984. Actual physical decommissioning began after about a year of preparation and was completed about 44 months later in July of 1989. This paper describes the main parts of D and D.

  17. Initial decommissioning planning for the Budapest research reactor

    Directory of Open Access Journals (Sweden)

    Toth Gabor

    2011-01-01

    Full Text Available The Budapest Research Reactor is the first nuclear research facility in Hungary. The reactor is to remain in operation for at least another 13 years. At the same time, the development of a decommissioning plan is a mandatory requirement under national legislation. The present paper describes the current status of decommissioning planning which is aimed at a timely preparation for the forthcoming decommissioning of the reactor.

  18. SAVANNAH RIVER SITE R REACTOR DISASSEMBLY BASIN IN SITU DECOMMISSIONING

    Energy Technology Data Exchange (ETDEWEB)

    Langton, C.; Blankenship, J.; Griffin, W.; Serrato, M.

    2009-12-03

    The US DOE concept for facility in-situ decommissioning (ISD) is to physically stabilize and isolate in tact, structurally sound facilities that are no longer needed for their original purpose of, i.e., generating (reactor facilities), processing(isotope separation facilities) or storing radioactive materials. The 105-R Disassembly Basin is the first SRS reactor facility to undergo the in-situ decommissioning (ISD) process. This ISD process complies with the105-R Disassembly Basin project strategy as outlined in the Engineering Evaluation/Cost Analysis for the Grouting of the R-Reactor Disassembly Basin at the Savannah River Site and includes: (1) Managing residual water by solidification in-place or evaporation at another facility; (2) Filling the below grade portion of the basin with cementitious materials to physically stabilize the basin and prevent collapse of the final cap - Sludge and debris in the bottom few feet of the basin will be encapsulated between the basin floor and overlying fill material to isolate if from the environment; (3) Demolishing the above grade portion of the structure and relocating the resulting debris to another location or disposing of the debris in-place; and (4) Capping the basin area with a concrete slab which is part of an engineered cap to prevent inadvertent intrusion. The estimated total grout volume to fill the 105-R Reactor Disassembly Basin is 24,424 cubic meters or 31,945 cubic yards. Portland cement-based structural fill materials were design and tested for the reactor ISD project and a placement strategy for stabilizing the basin was developed. Based on structural engineering analyses and work flow considerations, the recommended maximum lift height is 5 feet with 24 hours between lifts. Pertinent data and information related to the SRS 105-R-Reactor Disassembly Basin in-situ decommissioning include: regulatory documentation, residual water management, area preparation activities, technology needs, fill material designs

  19. Revised analyses of decommissioning for the reference pressurized Water Reactor Power Station. Volume 2, Effects of current regulatory and other considerations on the financial assurance requirements of the decommissioning rule and on estimates of occupational radiation exposure: Appendices, Final report

    Energy Technology Data Exchange (ETDEWEB)

    Konzek, G.J.; Smith, R.I.; Bierschbach, M.C.; McDuffie, P.N.

    1995-11-01

    With the issuance of the final Decommissioning Rule (July 27, 1998), owners and operators of licensed nuclear power plants are required to prepare, and submit to the US Nuclear Regulatory Commission (NRC) for review, decommissioning plans and cost estimates. The NRC staff is in need of bases documentation that will assist them in assessing the adequacy of the licensee submittals, from the viewpoint of both the planned actions, including occupational radiation exposure, and the probable costs. The purpose of this reevaluation study is to provide some of the needed bases documentation. This report contains the results of a review and reevaluation of the 1978 PNL decommissioning study of the Trojan nuclear power plant (NUREG/CR-0130), including all identifiable factors and cost assumptions which contribute significantly to the total cost of decommissioning the nuclear power plant for the DECON, SAFSTOR, and ENTOMB decommissioning alternatives. These alternatives now include an initial 5--7 year period during which time the spent fuel is stored in the spent fuel pool, prior to beginning major disassembly or extended safe storage of the plant. Included for information (but not presently part of the license termination cost) is an estimate of the cost to demolish the decontaminated and clean structures on the site and to restore the site to a ``green field`` condition. This report also includes consideration of the NRC requirement that decontamination and decommissioning activities leading to termination of the nuclear license be completed within 60 years of final reactor shutdown, consideration of packaging and disposal requirements for materials whose radionuclide concentrations exceed the limits for Class C low-level waste (i.e., Greater-Than-Class C), and reflects 1993 costs for labor, materials, transport, and disposal activities.

  20. Revised analyses of decommissioning for the reference boiling water reactor power station. Effects of current regulatory and other considerations on the financial assurance requirements of the decommissioning rule and on estimates of occupational radiation exposure - appendices. Final report

    Energy Technology Data Exchange (ETDEWEB)

    Smith, R.I.; Bierschbach, M.C.; Konzek, G.J.; McDuffie, P.N.

    1996-07-01

    The NRC staff is in need of decommissioning bases documentation that will assist them in assessing the adequacy of the licensee submittals, from the viewpoint of both the planned actions, including occupational radiation exposure, and the probable costs. The purpose of this reevaluation study is to update the needed bases documentation. This report presents the results of a review and reevaluation of the PNL 1980 decommissioning study of the Washington Public Power Supply System`s Washington Nuclear Plant Two (WNP-2) located at Richland, Washington, including all identifiable factors and cost assumptions which contribute significantly to the total cost of decommissioning the plant for the DECON, SAFSTOR, and ENTOMB decommissioning alternatives. These alternatives now include an initial 5-7 year period during which time the spent fuel is stored in the spent fuel pool prior to beginning major disassembly or extended safe storage of the plant. Included for information (but not presently part of the license termination cost) is an estimate of the cost to demolish the decontaminated and clear structures on the site and to restore the site to a {open_quotes}green field{close_quotes} condition. This report also includes consideration of the NRC requirement that decontamination and decommissioning activities leading to termination of the nuclear license be completed within 60 years of final reactor shutdown, consideration of packaging and disposal requirements for materials whose radionuclide concentrations exceed the limits for Class C low-level waste (i.e., Greater-Than-Class C), and reflects 1993 costs for labor, materials, transport, and disposal activities. Sensitivity of the total license termination cost to the disposal costs at different low-level radioactive waste disposal sites, to different depths of contaminated concrete surface removal within the facilities, and to different transport distances is also examined.

  1. ADVANTAGES, DISADVANTAGES, AND LESSONS LEARNED FROM MULTI-REACTOR DECOMMISSIONING PROJECTS

    Energy Technology Data Exchange (ETDEWEB)

    Morton, M.R.; Nielson, R.R.; Trevino, R.A.

    2003-02-27

    This paper discusses the Reactor Interim Safe Storage (ISS) Project within the decommissioning projects at the Hanford Site and reviews the lessons learned from performing four large reactor decommissioning projects sequentially. The advantages and disadvantages of this multi-reactor decommissioning project are highlighted.

  2. 77 FR 8902 - Draft Regulatory Guide: Issuance, Availability Decommissioning of Nuclear Power Reactors

    Science.gov (United States)

    2012-02-15

    ... COMMISSION Draft Regulatory Guide: Issuance, Availability Decommissioning of Nuclear Power Reactors AGENCY... ``Decommissioning of Nuclear Power Reactors.'' This guide describes a method NRC considers acceptable for use in... Revision 1 of Regulatory Guide 1.184, ``Decommissioning of Nuclear Power Reactors,'' dated July 2000. This...

  3. Reactor decommissioning at Magnox Electric sites

    Energy Technology Data Exchange (ETDEWEB)

    Joynson, Dennis [Magnox Electric plc (United Kingdom)

    1997-06-01

    There is almost continuous public debate about the cost-effectiveness of reprocessing spent nuclear fuels, and the practicality, cost and ethics of the final disposal of nuclear wastes. These questions may never be fully resolved but, meanwhile, Magnox Electric is pressing ahead with decommissioning its oldest nuclear power stations. Here, the author describes the work carried out so far at Berkeley, Trawsfynydd and Hunterston A. (Author).

  4. Enhanced productivity in reactor decommissioning and waste management

    Energy Technology Data Exchange (ETDEWEB)

    Wasinger, Karl [Areva GmbH, Offenbach (Germany)

    2014-04-15

    As for any industrial facility, the service live of nuclear power plants, fuel cycle facilities, research and test reactors ends. Decision for decommissioning such facilities may be motivated by technical, economical or political reasons or a combination of it. As of today, a considerable number of research reactors, fuel cycle facilities and power reactors have been completely decommissioned. However, the end point of such facilities' lifetime is achieved, when the facility is finally removed from regulatory control and the site becomes available for further economical utilization. This process is commonly known as decommissioning and involves detailed planning of all related activities, radiological characterization, dismantling, decontamination, clean-up of the site including treatment and packaging of radioactive and/or contaminated material not released for unrestricted recycling or industrial disposal. Decommissioning requires adequate funding and suitable measures to ensure safety while addressing stakeholders' requirements on occupational health, environment, economy, human resources management and the socioeconomic effects to the community and the region. One important aspect in successful management of decommissioning projects and dismantling operation relates to the economical impact of the endeavor, primarily depending on the selected strategy and, as from commencement of dismantling, on total duration until the end point is achieved. Experience gained by Areva in executing numerous decommissioning projects during past 2 decades shows that time injury free execution and optimum productivity turns out crucial to project cost. Areva develops and implements specific 'performance improvement plans' for each of its projects which follow the philosophy of operational excellence based on Lean Manufacturing principles. Means and methods applied in implementation of these plans and improvements achieved are described and examples are given on

  5. Integration of improved decontamination and characterization technologies in the decommissioning of the CP-5 research reactor

    Energy Technology Data Exchange (ETDEWEB)

    Bhattacharyya, S. K.; Boing, L. E.

    2000-02-17

    The aging of research reactors worldwide has resulted in a heightened awareness in the international technical decommissioning community of the timeliness to review and address the needs of these research institutes in planning for and eventually performing the decommissioning of these facilities. By using the reactors already undergoing decommissioning as test beds for evaluating enhanced or new/innovative technologies for decommissioning, it is possible that new techniques could be made available for those future research reactor decommissioning projects. Potentially, the new technologies will result in: reduced radiation doses to the work force, larger safety margins in performing decommissioning and cost and schedule savings to the research institutes in performing the decommissioning of these facilities. Testing of these enhanced technologies for decontamination, dismantling, characterization, remote operations and worker protection are critical to furthering advancements in the technical specialty of decommissioning. Furthermore, regulatory acceptance and routine utilization for future research reactor decommissioning will be assured by testing and developing these technologies in realistically contaminated environments prior to use in the research reactors. The decommissioning of the CP-5 Research Reactor is currently in the final phase of dismantlement. In this paper the authors present results of work performed at Argonne National Laboratory (ANL) in the development, testing and deployment of innovative and/or enhanced technologies for the decommissioning of research reactors.

  6. 76 FR 65541 - Assuring the Availability of Funds for Decommissioning Nuclear Reactors

    Science.gov (United States)

    2011-10-21

    ... COMMISSION Assuring the Availability of Funds for Decommissioning Nuclear Reactors AGENCY: Nuclear Regulatory... Decommissioning Nuclear Reactors.'' This guide provides guidance to applicants and licensees of nuclear power, research, and test reactors concerning methods acceptable to the staff of the U.S. Nuclear Regulatory...

  7. Nuclear reactor decommissioning: an analysis of the regulatory environments

    Energy Technology Data Exchange (ETDEWEB)

    Cantor, R.

    1986-08-01

    In the next several decades, the electric utility industry will be faced withthe retirement of 50,000 megawatts (mW) of nuclear capacity. Responsibility for the financial and technical burdens this activity entails has been delegated to the utilities operating the reactors. However, the operators will have to perform the tasks of reactor decommissioning within the regulatory environment dictated by federal, state and local regulations. The purpose of this study was to highlight some of the current and likely trends in regulations and regulatory practices that will significantly affect the costs, technical alternatives and financing schemes encountered by the electric utilities and their customers. To identify significant trends and practices among regulatory bodies and utilities, a reviw of these factors was undertaken at various levels in the regulatory hierarchy. The technical policies were examined in reference to their treatment of allowed technical modes, restoration of the plant site including any specific recognition of the residual radioactivity levels, and planning requirements. The financial policies were examined for specification of acceptable financing arrangements, mechanisms which adjust for changes in the important parameters used to establish the fund, tax and rate-base treatments of the payments to and earnings on the fund, and whether or not escalation and/or discounting were considered in the estimates of decommissioning costs. The attitudes of regulators toward financial risk, the tax treatment of the decommissioning fund, and the time distribution of the technical mode were found to have the greatest effect on the discounted revenue requirements. Under plausible assumptions, the cost of a highly restricted environment is about seven times that of the minimum revenue requirement environment for the plants that must be decommissioned in the next three decades.

  8. Radiochemical analysis of concrete samples for decommission of nuclear reactors

    Energy Technology Data Exchange (ETDEWEB)

    Zapata-Garcia, Daniel; Wershofen, Herbert [Physikalisch-Technische Bundesanstalt (PTB), Bundesallee 100 38116, Braunschweig (Germany); Larijani, Cyrus; Sobrino-Petrirena, Maitane; Garcia-Miranda, Maria; Jerome, Simon M. [National Physical Laboratory (NPL), Hampton Road, Teddington, Middlesex, TW11 0LW (United Kingdom)

    2014-07-01

    Decommissioning of the oldest nuclear power reactors are some of the most challenging technological legacy issues many countries will face in forthcoming years, as many power reactors reach the end of their design lives. Decommissioning of nuclear reactors generates large amounts of waste that need to be classified according to their radioactive content. Approximately 10 % of the contaminated material ends up in different repositories (depending on their level of contamination) while the rest is decontaminated, measured and released into the environment or sent for recycling. Such classification needs to be done accurately in order to ensure that both the personnel involved in decommissioning and the population at large are not needlessly exposed to radiation or radioactive material and to minimise the environmental impact of such work. However, too conservative classification strategies should not be applied, in order to make proper use of radioactive waste repositories since space is limited and the full process must be cost-effective. Implicit in decommissioning and classification of waste is the need to analyse large amounts of material which usually combine a complex matrix with a non-homogeneous distribution of the radionuclides. Because the costs involved are large, it is possible to make great savings by the adoption of best available practices, such as the use of validated methods for on-site measurements and simultaneous determination of more than one radionuclide whenever possible. The work we present deals with the development and the validation of a procedure for the simultaneous determination of {sup 241}Am, plutonium isotopes, uranium isotopes and {sup 90}Sr in concrete samples. Samples are firstly ground and fused with LiBO{sub 2} and Li{sub 2}B{sub 4}O{sub 7}. After dissolution of the fused sample, silicate and alkaline elements are removed followed by radiochemical separation of the target radionuclides using extraction chromatography. Measurement

  9. Role of decommissioning plan and its progress for the PUSPATI TRIGA Reactor

    Science.gov (United States)

    Zakaria, Norasalwa; Mustafa, Muhammad Khairul Ariff; Anuar, Abul Adli; Idris, Hairul Nizam; Ba'an, Rohyiza

    2014-02-01

    Malaysian nuclear research reactor, the PUSPATI TRIGA Reactor, reached its first criticality in 1982, and since then, it has been serving for more than 30 years for training, radioisotope production and research purposes. Realizing the age and the need for its decommissioning sometime in the future, a ground basis of assessment and an elaborative project management need to be established, covering the entire process from termination of reactor operation to the establishment of final status, documented as the Decommissioning Plan. At international level, IAEA recognizes the absence of Decommissioning Plan as one of the factors hampering progress in decommissioning of nuclear facilities in the world. Throughout the years, IAEA has taken initiatives and drawn out projects in promoting progress in decommissioning programmes, like CIDER, DACCORD and R2D2P, for which Malaysia is participating in these projects. This paper highlights the concept of Decommissioning plan and its significances to the Agency. It will also address the progress, way forward and challenges faced in developing the Decommissioning Plan for the PUSPATI TRIGA Reactor. The efforts in the establishment of this plan helps to provide continual national contribution at the international level, as well as meeting the regulatory requirement, if need be. The existing license for the operation of PUSPATI TRIGA Reactor does not impose a requirement for a decommissioning plan; however, the renewal of license may call for a decommissioning plan to be submitted for approval in future.

  10. Role of decommissioning plan and its progress for the PUSPATI TRIGA Reactor

    Energy Technology Data Exchange (ETDEWEB)

    Zakaria, Norasalwa, E-mail: norasalwa@nuclearmalaysia.gov.my; Mustafa, Muhammad Khairul Ariff, E-mail: norasalwa@nuclearmalaysia.gov.my; Anuar, Abul Adli, E-mail: norasalwa@nuclearmalaysia.gov.my; Idris, Hairul Nizam, E-mail: norasalwa@nuclearmalaysia.gov.my; Ba' an, Rohyiza, E-mail: norasalwa@nuclearmalaysia.gov.my [Malaysian Nuclear Agency, 43000 Kajang, Selangor (Malaysia)

    2014-02-12

    Malaysian nuclear research reactor, the PUSPATI TRIGA Reactor, reached its first criticality in 1982, and since then, it has been serving for more than 30 years for training, radioisotope production and research purposes. Realizing the age and the need for its decommissioning sometime in the future, a ground basis of assessment and an elaborative project management need to be established, covering the entire process from termination of reactor operation to the establishment of final status, documented as the Decommissioning Plan. At international level, IAEA recognizes the absence of Decommissioning Plan as one of the factors hampering progress in decommissioning of nuclear facilities in the world. Throughout the years, IAEA has taken initiatives and drawn out projects in promoting progress in decommissioning programmes, like CIDER, DACCORD and R2D2P, for which Malaysia is participating in these projects. This paper highlights the concept of Decommissioning plan and its significances to the Agency. It will also address the progress, way forward and challenges faced in developing the Decommissioning Plan for the PUSPATI TRIGA Reactor. The efforts in the establishment of this plan helps to provide continual national contribution at the international level, as well as meeting the regulatory requirement, if need be. The existing license for the operation of PUSPATI TRIGA Reactor does not impose a requirement for a decommissioning plan; however, the renewal of license may call for a decommissioning plan to be submitted for approval in future.

  11. SAVANNAH RIVER SITE R-REACTOR DISASSEMBLY BASIN IN-SITU DECOMMISSIONING -10499

    Energy Technology Data Exchange (ETDEWEB)

    Langton, C.; Serrato, M.; Blankenship, J.; Griffin, W.

    2010-01-04

    The US DOE concept for facility in-situ decommissioning (ISD) is to physically stabilize and isolate intact, structurally sound facilities that are no longer needed for their original purpose, i.e., generating (reactor facilities), processing(isotope separation facilities) or storing radioactive materials. The 105-R Disassembly Basin is the first SRS reactor facility to undergo the in-situ decommissioning (ISD) process. This ISD process complies with the 105-R Disassembly Basin project strategy as outlined in the Engineering Evaluation/Cost Analysis for the Grouting of the R-Reactor Disassembly Basin at the Savannah River Site and includes: (1) Managing residual water by solidification in-place or evaporation at another facility; (2) Filling the below grade portion of the basin with cementitious materials to physically stabilize the basin and prevent collapse of the final cap - Sludge and debris in the bottom few feet of the basin will be encapsulated between the basin floor and overlying fill material to isolate it from the environment; (3) Demolishing the above grade portion of the structure and relocating the resulting debris to another location or disposing of the debris in-place; and (4) Capping the basin area with a concrete slab which is part of an engineered cap to prevent inadvertent intrusion. The estimated total grout volume to fill the 105-R Reactor Disassembly Basin is 24,384 cubic meters or 31,894 cubic yards. Portland cement-based structural fill materials were designed and tested for the reactor ISD project, and a placement strategy for stabilizing the basin was developed. Based on structural engineering analyses and material flow considerations, maximum lift heights and differential height requirements were determined. Pertinent data and information related to the SRS 105-R Reactor Disassembly Basin in-situ decommissioning include: regulatory documentation, residual water management, area preparation activities, technology needs, fill material

  12. Radiological survey support activities for the decommissioning of the Ames Laboratory Research Reactor Facility, Ames, Iowa

    Energy Technology Data Exchange (ETDEWEB)

    Wynveen, R.A.; Smith, W.H.; Sholeen, C.M.; Justus, A.L.; Flynn, K.F.

    1984-09-01

    At the request of the Engineering Support Division of the US Department of Energy-Chicago Operations Office and in accordance with the programmatic overview/certification responsibilities of the Department of Energy Environmental and Safety Engineering Division, the Argonne National Laboratory Radiological Survey Group conducted a series of radiological measurements and tests at the Ames Laboratory Research Reactor located in Ames, Iowa. These measurements and tests were conducted during 1980 and 1981 while the reactor building was being decontaminated and decommissioned for the purpose of returning the building to general use. The results of these evaluations are included in this report. Although the surface contamination within the reactor building could presumably be reduced to negligible levels, the potential for airborne contamination from tritiated water vapor remains. This vapor emmanates from contamination within the concrete of the building and should be monitored until such time as it is reduced to background levels. 2 references, 8 figures, 6 tables.

  13. Revised cost estimate for the decommissioning of the reactor DR3

    DEFF Research Database (Denmark)

    2001-01-01

    The report describes a revision of the cost estimate for the decommissioning of the research Reactor DR 3 as described in the report Risø-R-1250(EN). Decommissioning of the Nuclear Facilities at Risø National Laboratory. Edited by Kurt Lauridsen. Therevision has been performed by the planning group...... in the Risø Decommissioning Department, and has been carried out as a discussion and evaluation of procedures methods and necessary resources to overcome the different phases of the the decommissioningtask of the Reactor....

  14. Prediction of Decommissioning Cost for Kijang Research Reactor Using Power Data of DACCORD

    Energy Technology Data Exchange (ETDEWEB)

    Hong, Yun Jeong; Jin, Hyung Gon; Park, Hee Seong; Park, Seung Kook [KAERI, Daejeon (Korea, Republic of)

    2016-05-15

    There are 3 types of cost estimate that can be used, and each have a different level of accuracy: (i) Order of magnitude estimate: One without detailed engineering data, where an estimate is prepared using scale-up or -down factors and approximate ratios. It is likely that the overall scope of the project has not been well defined. The level of accuracy expected is -30% to +50%. The cost plans to predict referring to abroad examples as decommissioning cost estimation has still not developed and been commercial method for Kijang research reactor. In Kijang research reactor case, overall scope of business isn't yet decided. Then it is supposed to estimate cost with type (i). The IAEA project, entitled 'DACCORD' (Data Analysis and Collection for Costing of Research Reactor Decommissioning) performs decommissioning costing after collecting and analyzing the information related to research reactors around the world for several years. Also decommissioning costing method development tends to increase in the each country. This paper aims to estimate preliminary decommissioning cost based on total decommissioning cost per thermal power rate of research reactor presented in DACCORD project' data which is collected by member state. In this paper, preliminary decommissioning cost is estimated based on total decommissioning cost per thermal power rate of research reactor presented in DACCORD data which is collected by member state. Although there exists a general tendency for costs to increase with increasing thermal power, the limited data available show that decommissioning costs at any given power level can vary widely, with increased variability at higher power levels. Variations in decommissioning cost for the research reactors of the same or similar thermal power are caused by differences in reactor types and design, decommissioning project scopes, country- specific unit workforce costs, and other reactor or project factors. An important factor for the

  15. Nonlinear Control of Hydraulic Manipulator for Decommissioning Nuclear Reactor

    Energy Technology Data Exchange (ETDEWEB)

    Kim, Myoung-Ho; Lee, Sung-Uk; Kim, Chang-Hoi; Choi, Byung-Seon; Moon, Jei-Kwon [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2016-10-15

    Robot technique is need to decommission nuclear reactor because of high radiation environment. Especially, Manipulator systems are useful for dismantling complex structure in a nuclear facility. In addition, Hydraulic system is applied to handle heavy duty object. Since hydraulic system can demonstrate high power. The manipulator with hydraulic power is already developed. To solve this problem, various nonlinear control method includes acceleration control. But, it is difficult because acceleration value is highly noisy. In this paper, the nonlinear control algorithm without acceleration control is studied. To verify, the hydraulic manipulator model had been developed. Furthermore, the numerical simulation is carried out. The nonlinear control without acceleration parameter method is developed for hydraulic manipulator. To verify control algorithm, the manipulator is modeled by MBD and the hydraulic servo system is also derived. In addition, the numerical simulation is also carried out. Especially, PID gain is determined though TDC algorithm. In the result of numerical simulation, tracking performance is good without acceleration control. Thus, the PID though TDC with SMC is good for hydraulic manipulator control.

  16. Applying and adapting the Swedish regulatory system for decommissioning to nuclear power reactors - The regulator's perspective.

    Science.gov (United States)

    Amft, Martin; Leisvik, Mathias; Carroll, Simon

    2017-03-16

    Half of the original 13 Swedish nuclear power reactors will be shut down by 2020. The decommissioning of these reactors is a challenge for all parties involved, including the licensees, the waste management system, the financing system, and the Swedish Radiation Safety Authority (SSM). This paper presents an overview of the Swedish regulations for decommissioning of nuclear facilities. It describes some of the experiences that SSM has gained from the application of these regulations. The focus of the present paper is on administrative aspects of decommissioning, such as SSM's guidelines, the definition of fundamental concepts in the regulatory framework, and a proposed revision of the licensing process according to the Environmental Act. These improvements will help to streamline the administration of the commercial nuclear power plant decommissioning projects that are anticipated to commence in Sweden in the near future. Copyright © 2017 Elsevier Ltd. All rights reserved.

  17. Technology, safety, and costs of decommissioning reference nuclear research and test reactors. Main report

    Energy Technology Data Exchange (ETDEWEB)

    Konzek, G.J.; Ludwick, J.D.; Kennedy, W.E. Jr.; Smith, R.I.

    1982-03-01

    Safety and Cost Information is developed for the conceptual decommissioning of two representative licensed nuclear research and test reactors. Three decommissioning alternatives are studied to obtain comparisons between costs (in 1981 dollars), occupational radiation doses, potential radiation dose to the public, and other safety impacts. The alternatives considered are: DECON (immediate decontamination), SAFSTOR (safe storage followed by deferred decontamination), and ENTOMB (entombment). The study results are presented in two volumes. Volume 1 (Main Report) contains the results in summary form.

  18. Revised analyses of decommissioning for the reference boiling water reactor power station. Effects of current regulatory and other considerations on the financial assurance requirements of the decommissioning rule and on estimates of occupational radiation exposure: Appendices, draft report for comment. Volume 2

    Energy Technology Data Exchange (ETDEWEB)

    Smith, R.I.; Bierschbach, M.C.; Konzek, G.J. [Pacific Northwest Lab., Richland, WA (United States)] [and others

    1994-09-01

    On June 27, 1988, the U.S. Nuclear Regulatory Commission (NRC) published in the Federal Register (53 FR 24018) the final rule for the General Requirements for Decommissioning Nuclear Facilities. With the issuance of the final rule, owners and operators of licensed nuclear power plants are required to prepare, and submit to the NRC for review, decommissioning plans and cost estimates. The NRC staff is in need of updated bases documentation that will assist them in assessing the adequacy of the licensee submittals, from the viewpoint of both the planned actions, including occupational radiation exposure, and the probable costs. The purpose of this reevaluation study is to update the needed bases documentation. This report presents the results of a review and reevaluation of the PNL 1980 decommissioning study of the Washington Public Power Supply System`s WNP-2, including all identifiable factors and cost assumptions which contribute significantly to the total cost of decommissioning the plant for the DECON, SAFSTOR, and ENTOMB decommissioning alternatives, which now include an initial 5-7 year period during which time the spent fuel is stored in the spent fuel pool prior to beginning major disassembly or extended safe storage of the plant. This report also includes consideration of the NRC requirement that decontamination and decommissioning activities leading to termination of the nuclear license be completed within 60 years of final reactor shutdown, consideration of packaging and disposal requirements for materials whose radionuclide concentrations exceed the limits for Class C low-level waste. Costs for labor, materials, transport, and disposal activities are given in 1993 dollars. Sensitivities of the total license termination cost to the disposal costs at different low-level radioactive waste disposal sites, to different depths of contaminated concrete surface removal within the facilities, and to different transport distances are also examined.

  19. Decommissioning handbook

    Energy Technology Data Exchange (ETDEWEB)

    Manion, W.J.; LaGuardia, T.S.

    1980-11-01

    This document is a compilation of information pertinent to the decommissioning of surplus nuclear facilities. This handbook is intended to describe all stages of the decommissioning process including selection of the end product, estimation of the radioactive inventory, estimation of occupational exposures, description of the state-of-the-art in re decontamination, remote csposition of wastes, and estimation of program costs. Presentation of state-of-the-art technology and data related to decommissioning will aid in consistent and efficient program planning and performance. Particular attention is focused on available technology applicable to those decommissioning activities that have not been accomplished before, such as remote segmenting and handling of highly activated 1100 MW(e) light water reactor vessel internals and thick-walled reactor vessels. A summary of available information associated with the planning and estimating of a decommissioning program is also presented. Summarized in particular are the methodologies associated with the calculation and measurement of activated material inventory, distribution, and surface dose level, system contamination inventory and distribution, and work area dose levels. Cost estimating techniques are also presented and the manner in which to account for variations in labor costs as impacting labor-intensive work activities is explained.

  20. CONSIDERATIONS FOR THE DEVELOPMENT OF A DEVICE FOR THE DECOMMISSIONING OF THE HORIZONTAL FUEL CHANNELS IN THE CANDU 6 NUCLEAR REACTOR. PART 6 - PRESENTATION OF THE DECOMMISSIONING DEVICE

    Directory of Open Access Journals (Sweden)

    Gabi ROSCA FARTAT

    2015-05-01

    Full Text Available The objective of this paper is to present a possible solution for the designing of a device for the decommissioning of the horizontal fuel channels in the CANDU 6 nuclear reactor. The decommissioning activities are dismantling, demolition, controlled removal of equipment, components, conventional or hazardous waste (radioactive, toxic in compliance with the international basic safety standards on radiation protection. One as the most important operation in the final phase of the nuclear reactor dismantling is the decommissioning of fuel channels. For the fuel channels decommissioning should be taken into account the detailed description of the fuel channel and its components, the installation documents history, adequate radiological criteria for decommissioning guidance, safety and environmental impact assessment, including radiological and non-radiological analysis of the risks that can occur for workers, public and environment, the description of the proposed program for decommissioning the fuel channel and its components, the description of the quality assurance program and of the monitoring program, the equipments and methods used to verify the compliance with the decommissioning criteria, the planning of performing the final radiological assessment at the end of the fuel channel decommissioning. These will include also, a description of the proposed radiation protection procedures to be used during decommissioning. The dismantling of the fuel channel is performed by one device which shall provide radiation protection during the stages of decommissioning, ensuring radiation protection of the workers. The device shall be designed according to the radiation protection procedures. The decommissioning device assembly of the fuel channel components is composed of the device itself and moving platform support for coupling of the selected channel to be dismantled. The fuel channel decommissioning device is an autonomous device designed for

  1. Elements of record management system for the RA research reactor decommissioning

    Directory of Open Access Journals (Sweden)

    Stejić Milijana

    2004-01-01

    Full Text Available According to latest recommendations, the record management system of a nuclear facility should operate as a part of the integrated management information system, and is implemented at the very beginning of the facility’s life cycle. The record management becomes particularly important at the end of the operation of a facility and then the operational record management system gradually transforms to a decommissioning one. However there is a significant number of nuclear facilities in the world which have reached the decommissioning stage with out having neither the initial decommissioning plan nor the established record management system. The objective of this paper is to introduce constituted elements of the record management system for the decommissioning of the RA research reactor in the VINČA Institute of Nuclear Sciences, and to discuss future planned actions related to this matter.

  2. Technology, safety, and costs of decommissioning reference nuclear research and test reactors. Appendices

    Energy Technology Data Exchange (ETDEWEB)

    Konzek, G.J.; Ludwick, J.D.; Kennedy, W.E. Jr.; Smith, R.I.

    1982-03-01

    Safety and Cost Information is developed for the conceptual decommissioning of two representative licensed nuclear research and test reactors. Three decommissioning alternatives are studied to obtain comparisons between costs (in 1981 dollars), occupational radiation doses, potential radiation dose to the public, and other safety impacts. The alternatives considered are: DECON (immediate decontamination), SAFSTOR (safe storage followed by deferred decontamination), and EMTOMB (entombment). The study results are presented in two volumes. Volume 2 (Appendices) contains the detailed data that support the results given in Volume 1, including unit-component data.

  3. Decommissioning an Active Historical Reactor Facility at the Savannah River Site - 13453

    Energy Technology Data Exchange (ETDEWEB)

    Bergren, Christopher L.; Long, J. Tony; Blankenship, John K. [Savannah River Nuclear Solutions, LLC, Bldg. 730-4B, Aiken, SC 29808 (United States); Adams, Karen M. [United States Department of Energy, Bldg. 730-B, Aiken, SC 29808 (United States)

    2013-07-01

    -time critical removal action for the In Situ Decommissioning (ISD) of the 105-C Disassembly Basin. ISD consisted of stabilization/isolation of remaining contaminated water, sediment, activated reactor equipment, and scrap metal by filling the DB with underwater non-structural grout to the appropriate (-4.877 meter) grade-level, thence with dry area non-structural grout to the final -10 centimeter level. The roof over the DB was preserved due to its potential historical significance and to prevent the infiltration of precipitation. Forced evaporation was the form of treatment implemented to remove the approximately 9.1 M liters of contaminated basin water. Using specially formulated grouts, irradiated materials and sediment were treated by solidification/isolation thus reducing their mobility, reducing radiation exposure and creating an engineered barrier thereby preventing access to the contaminants. Grouting provided a low permeability barrier to minimize any potential transport of contaminants to the aquifer. Efforts were made to preserve the historical significance of the Reactor in accordance with the National Historic Preservation Act. ISD provides a cost effective means to isolate and contain residual radioactivity from past nuclear operations allowing natural radioactive decay to reduce hazards to manageable levels. This method limits release of radiological contamination to the environment, minimizes radiation exposure to workers, prevents human/animal access to the hazardous substances, and allows for ongoing monitoring of the decommissioned facility. Field construction was initiated in August 2011; evaporator operations commenced January 2012 and ended July 2012 with over 9 M liters of water treated/removed. Over 8,525 cubic meters of grout were placed, completing in August 2012. The project completed with an excellent safety record, on schedule and under budget. (authors)

  4. Decommissioning of Wuergassen NPP - work on the reactor service floor; Rueckbau des Kernkraftwerkes Wuergassen - Arbeiten auf der Reaktorbedienungsebene

    Energy Technology Data Exchange (ETDEWEB)

    Ehlert, A.; Winnefeld, M. [E.ON Kernkraft GmbH, Kernkraftwerk Wuergassen, Beverungen (Germany)

    2003-07-01

    Wuergassen NPP (KWW) is located on the River Weser, some 50 km north of Kassel. It is a single unit boiling water reactor with an installed electrical generation capacity of 670 MW. The plant was constructed by AEG between 1968 and 1971 and went into operation in late 1971. Wuergassen NPP generated a total of 73 billion kWh of electricity during its period of commercial operation. Cracks were discovered in the core shroud of the reactor pressure vessel while carrying out inspection work during the annual scheduled refuelling outage in 1994. As a result of this, the plant was shut down, Various alternatives as to how to proceed further where evaluated within one year. PreussenElektra AG, the operator at the time, ultimately decided to finally shut the plant down in 1995 and to immediately begin with the decommissioning. Several independent of each other phases have been planned for the decommissioning of the nuclear power plant. The plant components are to be dismantled beginning with the non and low contaminated parts up to the more concentrated or activated installations. The whole decommissioning has been divided into a total of six phases. Theses phases are roughly depicted in fig. 1. Now that the Ministry of Economy and Small Business, Energy and Transport for the State of North Rhine Westphalia has granted permission for phases 1 to 5, all work within the framework of the direct decommissioning of Wuergassen Nuclear Power Plant can be carried out. There are at the present time approximately 500 people actively working on site. This number is made up of about 170 staff from E.ON Kernkraft GmbH and some 330 employees from outside contractors. The decommissioning tasks presented here describe the work that has been carried out in the area of the reactor service floor and specifically in the proximity of the reactor vessel. Therefore, particular requirements were necessary for the technology employed, as well as for the importance of practical radiation protection

  5. CONSIDERATIONS FOR THE DEVELOPMENT OF A DEVICE FOR THE DECOMMISSIONING OF THE HORIZONTAL FUEL CHANNELS IN THE CANDU 6 NUCLEAR REACTOR. PART 7 - FUNCTIONING OF THE DECOMMISSIONING DEVICE

    Directory of Open Access Journals (Sweden)

    Gabi ROSCA FARTAT

    2015-05-01

    Full Text Available The scope of this paper is to achieve the device functioning steps for the commissioning of the horizontal fuel channels of calandria vessel. The dismantling of the fuel channel is performed by one device which shall provide radiation protection during the stages of decommissioning, ensuring radiation protection of the workers. For the decommissioning operation design shall be taken to ensure all aspects of security, environmental protection during decommissioning operation steps and creating and implementing work procedures resulting from developed decommissioning plan. The fuel channel decommissioning device is designed for dismantling and extraction of the fuel channel and its components. The decommissioning operation consists of following major steps: platform with device positioning to the fuel channel to be dismantled; coupling and locking the device at the fuel channel; unblock, extract and store the channel closure plug; unblock, extract and store the channel shield plug; block and cut the middle and the end of the pressure tube; block, extract and store the end fitting; block, extract and store the half of pressure tube; mounting of the extended closing plug. The operations steps are performed by the Cutting and Extraction Device and by the extraction actuator from the device handling elements assembly. After each step of dismantling is necessary the confirmation its finalization in order to perform the next operation step. The dismantling operation steps of the fuel channel components are repeated for all the 380 channels of the reactor, from the front of calandria side (plane R as well as the rear side (plane R'.

  6. A study on source term assessment and waste disposal requirement of decontamination and decommissioning for the TRIGA research reactor

    Energy Technology Data Exchange (ETDEWEB)

    Whang, Joo Ho; Lee, Kyung JIn; Lee, Jae Min; Choi, Gyu Seup; Shin, Byoung Sun [Kyunghee Univ., Seoul (Korea, Republic of)

    1999-08-15

    The objective and necessity of the project : TRIGA is the first nuclear facility that decide to decommission and decontamination in our nation. As we estimate the expected life of nuclear power generation at 30 or 40 years, the decommissioning business should be conducted around 2010, and the development of regulatory technique supporting it should be developed previously. From a view of decommissioning and decontamination, the research reactor is just small in scale but it include all decommissioning and decontamination conditions. So, the rules by regulatory authority with decommissioning will be a guide for nuclear power plant in the future. The basis of regulatory technique required when decommissioning the research reactor are the radiological safety security and the data for it. The source term is very important condition not only for security of worker but for evaluating how we dispose the waste is appropriate for conducting the middle store and the procedure after it when the final disposal is considered. The content and the scope in this report contain the procedure of conducting the assessment of the source term which is most important in understanding the general concept of the decommissioning procedure of the decommissioning and decontamination of TRIGA research reactor. That is, the sampling and measuring method is presented as how to measure the volume of the radioactivity of the nuclear facilities. And also, the criterion of classifying the waste occurred in other countries and the site release criteria which is the final step of decommissioning and decontamination presented through MARSSIM. Finally, the program to be applicable through comparing the methods of our nation and other countries ones is presented as plan for disposal of the waste in the decommissioning.

  7. Thermal analysis to support decommissioning of the molten salt reactor experiment

    Energy Technology Data Exchange (ETDEWEB)

    Sulfredge, C.D.; Morris, D.G.; Park, J.E.; Williams, P.T.

    1996-06-01

    As part of the decommissioning process for the Molten Salt Reactor Experiment (MSRE) at Oak Ridge National Laboratory, several thermal-sciences issues were addressed. Apparently a mixture of UF{sub 6} and F{sub 2} had diffused into the upper portion of one charcoal column in the MSRE auxiliary charcoal bed (ACB), leading to radiative decay heating and possible chemical reaction sources. A proposed interim corrective action was planned to remove the water from the ACB cell to reduce criticality and reactivity concerns and then fill the ACB cell with an inert material. This report describes design of a thermocouple probe to obtain temperature measurements for mapping the uranium deposit, as well as development of steady-state and transient numerical models for the heat transfer inside the charcoal column. Additional numerical modeling was done to support filling of the ACB cell. Results from this work were used to develop procedures for meeting the goals of the MSRE Remediation Project without exceeding appropriate thermal limits.

  8. Light water reactor safety

    CERN Document Server

    Pershagen, B

    2013-01-01

    This book describes the principles and practices of reactor safety as applied to the design, regulation and operation of light water reactors, combining a historical approach with an up-to-date account of the safety, technology and operating experience of both pressurized water reactors and boiling water reactors. The introductory chapters set out the basic facts upon which the safety of light water reactors depend. The central section is devoted to the methods and results of safety analysis. The accidents at Three Mile Island and Chernobyl are reviewed and their implications for light wate

  9. 2016 Annual Inspection and Radiological Survey Results for the Piqua, Ohio, Decommissioned Reactor Site, July 2016

    Energy Technology Data Exchange (ETDEWEB)

    Zimmerman, Brian [USDOE Office of Legacy Management, Washington, DC (United States); Miller, Michele [Navarro Research and Engineering, Oak Ridge, TN (United States)

    2016-07-01

    This report presents the findings of the annual inspection and radiological survey of the Piqua, Ohio, Decommissioned Reactor Site (site). The decommissioned nuclear power demonstration facility was inspected and surveyed on April 15, 2016. The site, located on the east bank of the Great Miami River in Piqua, Ohio, was in fair physical condition. There is no requirement for a follow-up inspection, partly because City of Piqua (City) personnel participated in a March 2016 meeting to address reoccurring safety concerns. Radiological survey results from 104 locations revealed no removable contamination. One direct beta activity reading in a floor drain on the 56-foot level (1674 disintegrations per minute [dpm]/100 square centimeters [cm2]) exceeded the minimum detectable activity (MDA). Beta activity has been detected in the past at this floor drain. The reading was well below the action level of 5000 dpm/100 cm2.

  10. Thermal aging of some decommissioned reactor components and methodology for life prediction

    Energy Technology Data Exchange (ETDEWEB)

    Chung, H.M.

    1989-03-01

    Since a realistic aging of cast stainless steel components for end-of-life or life-extension conditions cannot be produced, it is customary to simulate the thermal aging embrittlement by accelerated aging at /approximately/400/degree/C. In this investigation, field components obtained from decommissioned reactors have been examined after service up to 22 yr to provide a benchmark of the laboratory simulation. The primary and secondary aging processes were found to be identical to those of the laboratory-aged specimens, and the kinetic characteristics were also similar. The extent of the aging embrittlement processes and other key factors that are known to influence the embrittlement kinetics have been compared for the decommissioned reactor components and materials aged under accelerated conditions. On the basis of the study, a mechanistic understanding of the causes of the complex behavior in kinetics and activation energy of aging (i.e., the temperature dependence of aging embrittlement between the accelerated and reactor-operating conditions) is presented. A mechanistic correlation developed thereon is compared with a number of available empirical correlations to provide an insight for development of a better methodology of life prediction of the reactor components. 18 refs., 18 figs., 5 tabs.

  11. Decontamination and decommissioning project of the TRIGA Mark-2 and 3 research reactors

    Energy Technology Data Exchange (ETDEWEB)

    Jung, K. J.; Baik, S. T.; Chung, U. S.; Jung, K. H.; Park, S. K.; Lee, B. J.; Kim, J. K.; Yang, S. H

    2000-01-01

    During the review on the decommissioning plan and environmental impact assessment report by the KINS, the number of the inquired items were two hundred and fifty one, and the answers were made and sent until September 10, 1999, as the screened review results were reported to Ministry of Science and Technology(MOST) in December 14, 1999, all the reviews on the licence were over. Radioactive liquid wastes of 400 tons generated during the operation of the research reactors including reactor vessels are stored in the facility of the research reactor 1 and 2. Those liquid wastes have the low-level-radioactivity which can be discharged to the surroundings, but was wholly treated to be vaporized naturally by means of the increased numbers of the natural vaporization disposal facilities with the annual capacity of 200 tons for the purpose of the minimized environmental contamination.

  12. Topsoil radiological characterisation of L-54M reactor surroundings preliminary to decommissioning operations.

    Science.gov (United States)

    Mossini, E; Codispoti, L; Giola, M; Castelli, L; Macerata, E; Porta, A; Campi, F; Mariani, M

    2017-11-27

    The radiological characterization of the topsoil of the L-54M reactor surroundings carried out in this work aims at obtaining the reference blank point for the forthcoming decommissioning operations and ascertain if unexpected radionuclide release occurred during the operational life of the plant. Standardised methods have been employed in order to collect representative samples and reliable results. Suitable sample pre-treatment procedures were applied. Gamma and beta spectrometric analyses were carried out to measure the activity concentrations of 60Co 137Cs, 152Eu, 241Am and 90Sr. These have been considered as representative radionuclides that could have been originated from reactor operations and that could still be present at four decades post reactor shutdown. Copyright © 2017 Elsevier Ltd. All rights reserved.

  13. Industrial Hygiene Concerns during the Decontamination and Decommissioning of the Tokamak Fusion Test Reactor

    CERN Document Server

    Lumia, M E

    2002-01-01

    A significant industrial hygiene concern during the Decontamination and Decommissioning (D and D) of the Tokamak Fusion Test Reactor (TFTR) was the oxidation of the lead bricks' surface, which were utilized for radiation shielding. This presented both airborne exposure and surface contamination issues for the workers in the field removing this material. This paper will detail the various protection and control methods tested and implemented to protect the workers, including those technologies deployed to decontaminate the work surfaces. In addition, those techniques employed to recycle the lead for additional use at the site will be discussed.

  14. Generation of an activation map for decommissioning planning of the Berlin Experimental Reactor-II

    Science.gov (United States)

    Lapins, Janis; Guilliard, Nicole; Bernnat, Wolfgang

    2017-09-01

    The BER-II is an experimental facility with 10 MW that was operated since 1974. Its planned operation will end in 2019. To support the decommissioning planning, a map with the overall distribution of relevant radionuclides has to be created according to the state of the art. In this paper, a procedure to create these 3-d maps using a combination of MCNP and deterministic methods is presented. With this approach, an activation analysis is performed for the whole reactor geometry including the most remote parts of the concrete shielding.

  15. Decontamination and decommissioning project of the TRIGA mark - 2 and 3 research reactors

    Energy Technology Data Exchange (ETDEWEB)

    Jung, K. J.; Baik, S. T.; Chung, U. S.; Jung, K. H.; Park, S. K.; Kim, J. K.; Lee, D. G.; Kim, H. R.; Lee, B. J.; Yang, S. H.

    2001-01-15

    The decommissioning license for KRR (Korea Research Reactor) 1 and 2 was issued Nov. 23, 2000. The atmospheric stability on the KRR site was evaluated using the meteorological data measured at the site. From the results of this evaluation, the population dose was evaluated for the public who lives at the periphery of the site. The Radiation Safety Management Guideline was developed and it will be used as a base line making Radiation Safety Management Procedure. The container was specially designed and manufactured for the storing of low level radioactive solid waste arising from the D and D activities. Firstly, the 50 containers were completely manufactured.

  16. Decommissioning of the ASTRA research reactor: Planning, executing and summarizing the project

    Directory of Open Access Journals (Sweden)

    Meyer Franz

    2010-01-01

    Full Text Available The decommissioning of the ASTRA research reactor at the Austrian Research Centres Seibersdorf was described within three technical papers already released in Nuclear Technology & Radiation Protection throughout the years 2003, 2006, and 2008. Following a suggestion from IAEA the project was investigated well after the files were closed regarding rather administrative than technical matters starting with the project mission, explaining the project structure and identifying the key factors and the key performance indicators. The continuous documentary and reporting system as implemented to fulfil the informational needs of stake-holders, management, and project staff alike is described. Finally the project is summarized in relationship to the performance indicators.

  17. HLRW management during MR reactor decommissioning in NRC 'Kurchatov Institute'

    Energy Technology Data Exchange (ETDEWEB)

    Chesnokov, Alexander; Ivanov, Oleg; Kolyadin, Vyacheslav; Lemus, Alexey; Pavlenko, Vitaly; Semenov, Sergey; Stepanov, Vyacheslav; Smirnov, Sergey; Potapov, Victor; Fadin, Sergey; Volkov, Victor; Shisha, Anatoly [NRC ' Kurchatov institute' , Moscow (Russian Federation)

    2013-07-01

    A program of decommissioning of MR research reactor in the Kurchatov institute started in 2008. The decommissioning work presumed a preliminary stage, which included: removal of spent fuel from near reactor storage; removal of spent fuel assemble of metal liquid loop channel from a core; identification, sorting and disposal of radioactive objects from gateway of the reactor; identification, sorting and disposal of radioactive objects from cells of HLRW storage of the Kurchatov institute for radwaste creating form the decommissioning of MR. All these works were performed by a remote controlled means with use of a remote identification methods of high radioactive objects. A distribution of activity along high radiated objects was measured by a collimated radiometer installed on the robot Brokk-90, a gamma image of the object was registered by gamma-visor. Spectrum of gamma radiation was measured by a gamma locator and semiconductor detector system. For identification of a presence of uranium isotopes in the HLRW a technique, based on the registration of characteristic radiation of U, was developed. For fragmentation of high radiated objects was used a cold cutting technique and dust suppression system was applied for reduction of volume activity of aerosols in air. The management of HLRW was performed by remote controlled robots Brokk-180 and Brokk-330. They executed sorting, cutting and parking of high radiated part of contaminated equipment. The use of these techniques allowed to reduce individual and collective doses of personal performed the decommissioning. The average individual dose of the personnel was 1,9 mSv/year in 2011, and the collective dose is estimated by 0,0605 man x Sv/year. Use of the remote control machines enables reducing the number of working personal (20 men) and doses. X-ray spectrometric methods enable determination of a presence of the U in high radiated objects and special cans and separation of them for further spent fuel inspection. The

  18. A survey of commercially available manipulators, end-effectors, and delivery systems for reactor decommissioning activities

    Energy Technology Data Exchange (ETDEWEB)

    Henley, D.R. [Argonne National Lab., IL (United States); Litka, T.J. [Advanced Consulting Group, Chicago, IL (United States)

    1996-05-01

    Numerous nuclear facilities owned by the U.S. Department of Energy (DOE) are under consideration for decommissioning. Currently, there are no standardized, automated, remote systems designed to dismantle and thereby reduce the size of activated reactor components and vessels so that they can be packaged and shipped to disposal sites. Existing dismantling systems usually consist of customized, facility-specific tooling that has been developed to dismantle a specific reactor system. Such systems have a number of drawbacks. Generally, current systems cannot be disassembled, moved, and reused. Developing and deploying the tooling for current systems is expensive and time-consuming. In addition, the amount of manual work is significant because long-handled tools must be used; as a result, personnel are exposed to excessive radiation. A standardized, automated, remote system is therefore needed to deliver the tooling necessary to dismantle nuclear facilities at different locations. Because this system would be reusable, it would produce less waste. The system would also save money because of its universal design, and it would be more reliable than current systems.

  19. Decommissioning of the ASTRA research reactor: Dismantling the auxiliary systems and clearance and reuse of the buildings

    Directory of Open Access Journals (Sweden)

    Meyer Franz

    2008-01-01

    Full Text Available The paper presents work performed in the last phase of the decommissioning of the ASTRA research reactor at the Austrian Research Centers Seibersdorf. Dismantling the pump room installations and the ventilation system, as well as the clearance of the buildings is described. Some conclusions and summary data regarding the timetable, material management, and the cost of the entire project are also presented.

  20. WATER BOILER REACTOR

    Science.gov (United States)

    King, L.D.P.

    1960-11-22

    As its name implies, this reactor utilizes an aqueous solution of a fissionable element salt, and is also conventional in that it contains a heat exchanger cooling coil immersed in the fuel. Its novelty lies in the utilization of a cylindrical reactor vessel to provide a critical region having a large and constant interface with a supernatant vapor region, and the use of a hollow sleeve coolant member suspended from the cover assembly in coaxial relation with the reactor vessel. Cool water is circulated inside this hollow coolant member, and a gap between its outer wall and the reactor vessel is used to carry off radiolytic gases for recombination in an external catalyst chamber. The central passage of the coolant member defines a reflux condenser passage into which the externally recombined gases are returned and condensed. The large and constant interface between fuel solution and vapor region prevents the formation of large bubbles and minimizes the amount of fuel salt carried off by water vapor, thus making possible higher flux densities, specific powers and power densities.

  1. Nuclide Inventory Calculation Using MCNPX for Wolsung Unit 1 Reactor Decommissioning

    Energy Technology Data Exchange (ETDEWEB)

    Rabir, Mohamad Hairie; Noh, Kyoung Ho; Hah, Chang Joo [KEPCO International Nuclear Graduate School, Daejeon (Korea, Republic of)

    2014-05-15

    The CINDER90 computation process involves utilizing linear Markovian chains to determine the time dependent nuclide densities. The CINDER90 depletion algorithm is implemented the MCNPX code package. The coupled depletion process involves a Monte-Carlo steady-state reaction rate calculation linked to a deterministic depletion calculation. The process is shown in Fig.1. MCNPX runs a steady state calculation to determine the system eigenvalue collision densities, recoverable energies from fission and neutrons per fission events. In order to generate number densities for the next time step, the CINDER90 code takes the MCNPX generated values and performs a depletion calculation. MCNPX then takes the new number densities and caries out a new steady-stated calculation. The process repeats itself until the final time step. This paper describe the preliminary source term and nuclide inventory calculation of Candu single fuel channel using MCNPX, as a part of the activities to support the equilibrium core model development and decommissioning evaluation process of a Candu reactor. The aim of this study was to apply the MCNPX code for source term and nuclide inventory calculation of Candu single fuel channel. Nuclide inventories as a function of burnup will be used to model an equilibrium core for Candu reactor. The core lifetime neutron fluence obtained from the model is used to estimate radioactivity at the stage of decommisioning. In general, as expected, the actinides and fission products build up increase with increasing burnup. Despite the fact that the MCNPX code is still in development we can conclude that the code is capable of obtaining relevant results in burnup and source term calculation. It is recommended that in the future work, the calculation has to be verified on the basis of experimental data or comparison with other codes.

  2. Decommissioning of eight surplus production reactors at the Hanford Site, Richland, Washington. Addendum (Final Environmental Impact Statement)

    Energy Technology Data Exchange (ETDEWEB)

    1992-12-01

    The first section of this volume summarizes the content of the draft environmental impact statement (DEIS) and this Addendum, which together constitute the final environmental impact statement (FEIS) prepared on the decommissioning of eight surplus plutonium production reactors at Hanford. The FEIS consists of two volumes. The first volume is the DEIS as written. The second volume (this Addendum) consists of a summary; Chapter 9, which contains comments on the DEIS and provides DOE`s responses to the comments; Appendix F, which provides additional health effects information; Appendix K, which contains costs of decommissioning in 1990 dollars; Appendix L, which contains additional graphite leaching data; Appendix M, which contains a discussion of accident scenarios; Appendix N, which contains errata; and Appendix 0, which contains reproductions of the letters, transcripts, and exhibits that constitute the record for the public comment period.

  3. Data Validation Package, June 2016 Groundwater Sampling at the Hallam, Nebraska, Decommissioned Reactor Site, August 2016

    Energy Technology Data Exchange (ETDEWEB)

    Surovchak, Scott [USDOE Office of Legacy Management, Washington, DC (United States); Miller, Michele [Navarro Research and Engineering, Oak Ridge, TN (United States)

    2016-08-01

    The 2008 Long-Term Surveillance Plan [LTSP] for the Decommissioned Hallam Nuclear Power Facility, Hallam, Nebraska (http://www.lm.doe.gov/Hallam/Documents.aspx) requires groundwater monitoring once every 2 years. Seventeen monitoring wells at the Hallam site were sampled during this event as specified in the plan. Planned monitoring locations are shown in Attachment 1, Sampling and Analysis Work Order. Water levels were measured at all sampled wells and at two additional wells (6A and 6B) prior to the start of sampling. Additionally, water levels of each sampled well were measured at the beginning of sampling. See Attachment 2, Trip Report, for additional details. Sampling and analysis were conducted as specified in Sampling and Analysis Plan for U.S. Department of Energy Office of Legacy Management Sites (LMS/PRO/S04351, continually updated, http://energy.gov/lm/downloads/sampling-and-analysis-plan-us-department- energy-office-legacy-management-sites). Gross alpha and gross beta are the only parameters that were detected at statistically significant concentrations. Time/concentration graphs of the gross alpha and gross beta data are included in Attachment 3, Data Presentation. The gross alpha and gross beta activity concentrations observed are consistent with values previously observed and are attributed to naturally occurring radionuclides (e.g., uranium and uranium decay chain products) in the groundwater.

  4. Engineering Evaluation/Cost Analysis for Decommissioning of the Engineering Test Reactor Complex

    Energy Technology Data Exchange (ETDEWEB)

    A. B. Culp

    2006-10-01

    Preparation of this Engineering Evaluation/Cost Analysis is consistent with the joint U.S. Department of Energy and U.S. Environmental Protection Agency Policy on Decommissioning of Department of Energy Facilities Under the Comprehensive Environmental Response, Compensation, and Liability Act, which establishes the Comprehensive Environmental Response, Compensation, and Liability Act non-time-critical removal action (NTCRA) process as an approach for decommissioning.

  5. Numeric determination and validation of neutron induced radioactive nuclide inventories for decommissioning and dismantling of light water reactors; Rechnerische Bestimmung und Validierung von Aktivierungsaktivitaeten fuer die Rueckbau- und Entsorgungsplanung von Leichtwasserreaktoren

    Energy Technology Data Exchange (ETDEWEB)

    Phlippen, Peter W.; Schloemer, Luc; Vallentin, Roger [WTI Wissenschaftlich-Technische Ingenieurberatung GmbH, Juelich (Germany); Lukas, Bernard [EnBW Kernkraft GmbH Kernkraftwerk Philippsburg (Germany); Palm, Stefan [EnBW Kernkraft GmbH Kernkraftwerk Neckarwestheim (Germany)

    2017-02-15

    The deconstruction of nuclear power plants requires project planning and budgeting both during the project and in advance, as well as the secured provision of financial and human resources. When a facility is free from irradiated fuel, the reactor pressure vessel with the nuclear components as well as the biological shield determine the activity inventory of the facility, which almost exclusively consists of activated radionuclides located in the respective structures. Knowledge of the activity distribution and nuclide vectors of the involved components is of vital importance for deconstruction planning. In this context, the development of a computation procedure is described coupling the Monte Carlo method for the determination of neutron flux densities with a procedure to perform activation calculations for the determination of nuclide vectors. For this purpose, detailed knowledge of the material composition, particularly the trace-element concentrations of nitrogen and cobalt in steel and additionally of europium and caesium in concrete structures, considerably impacts the accuracy of the calculated activities. Extensive validation using data collected from various reactor facilities, such as nuclide activities, neutron flux densities, and neutron and gamma dose rates, demonstrates the reliability of the computed nuclide distributions showing ratios of computed over measured values of typically between 0.9 and 3. The practicality of the developed method as well as the convenient use of the results have already been demonstrated analysing several German BWR and PWR facilities and developing packaging strategies based on the produced results.

  6. Assessment of derived emission limits for radioactive effluents resulted from the decommissioning activities of the VVR-S nuclear research reactor.

    Science.gov (United States)

    Tuca, C; Stochioiu, A; Sahagia, M; Gurau, D; Dragusin, M

    2015-10-01

    This paper presents complex studies on establishment of derived emission limits for potential radionuclides emitted as gaseous and liquid effluents, during the decommissioning activities (2nd and 3rd phases) of a nuclear research reactor, cooled and moderated with distilled water, type VVR-S, owned by the IFIN-HH. In the present paper there are described: the analysis methods and equipment used, the methodologies for calculating doses and the Derived Emission Limits (DEL), the experimentally measured activities of the representative radionuclides found in gaseous and liquid effluents resulted from decommissioning activities, as well as the effective derived limits of liquid and gaseous effluents, applying the calculation methodologies, specific to critical categories of exposed subjects. A constraint effective dose limit for a person from the critical group of 50 μSv/year was considered in calculations. From the comparison of the two series of values, measured released activities and DELs, there has been concluded that for the gaseous effluents they comply with the DELs, while in the case of liquid effluents they are higher and consequently they must be treated as liquid radioactive wastes. Copyright © 2015 Elsevier Ltd. All rights reserved.

  7. Analysis of Removal Alternatives for the Heavy Water Components Test Reactor at the Savannah River Site

    Energy Technology Data Exchange (ETDEWEB)

    Owen, M.B. [Westinghouse Savannah River Co., Aiken, SC (United States)

    1996-08-01

    This engineering study was developed to evaluate different options for decommissioning of the Heavy Water Components Test Reactor (HWCTR) at the Savannah River Site. This document will be placed in the DOE-SRS Area reading rooms for a period of 30 days in order to obtain public input to plans for the demolition of HWCTR.

  8. ASSESSMENT OF THE POTENTIAL FOR HYDROGEN GENERATION DURING DEACTIVATION AND DECOMMISSIONING OF REACTOR VESSELS AT THE SAVANNAH RIVER SITE

    Energy Technology Data Exchange (ETDEWEB)

    Wiersma, B.; Serrato, M.; Langton, C.

    2010-11-10

    The R- and P-reactor vessels at the Savannah River Site (SRS) are being prepared for deactivation and decommissioning (D&D). D&D activities will consist primarily of physically isolating and stabilizing the reactor vessel by filling it with a grout material. The reactor vessels contain aluminum alloy materials, which pose a concern in that aluminum corrodes rapidly when it comes in contact with the alkaline grout. A product of the corrosion reaction is hydrogen gas and therefore potential flammability issues were assessed. A model was developed to calculate the hydrogen generation rate as the reactor is being filled with the grout material. Three options existed for the type of grout material for D&D of the reactor vessels. The grout formulation options included ceramicrete (pH 6-8), a calcium aluminate sulfate (CAS) based cement (pH 10), or Portland cement grout (pH 12.4). Corrosion data for aluminum in concrete were utilized as input for the model. The calculations considered such factors as the surface area of the aluminum components, the open cross-sectional area of the reactor vessel, the rate at which the grout is added to the reactor vessel, and temperature. Given the hydrogen generation rate, the hydrogen concentration in the vapor space of the reactor vessel above the grout was calculated. This concentration was compared to the lower flammability limit for hydrogen. The assessment concluded that either ceramicrete or the CAS grout may be used to safely grout the P-reactor vessel. The risk of accumulation of a flammable mixture of hydrogen between the grout-air interface and the top of the reactor is very low. Portland cement grout, on the other hand, for the same range of process parameters did not provide a margin of safety against the accumulation of flammable gas in the reactor vessel during grouting operations in the P-reactor vessel. Therefore, it was recommended that this grout not be utilized for this task. On the other hand, the R-reactor vessel

  9. DETAILS OF OPERATIONS PERFORMED BY THE REMOTE CONTROL ROBOT (CONCEPT TO THE HORIZONTAL FUEL CHANNEL DURING DECOMMISSIONING PHASE OF NUCLEAR REACTOR CALANDRIA STRUCTURE. PART I: OUTSIDE OPERATIONS

    Directory of Open Access Journals (Sweden)

    Constantin POPESCU

    2017-05-01

    Full Text Available The authors contribution to this paper is to present a concept solution of a remote control robot (RCR used for the horizontal fuel channels pressure tube decommissioning in the CANDU nuclear reactor. The authors highlight in this paper, few details of geometry, operations, constraints by kinematics and dynamics of the robot movement outside of the reactor fuel channel. Outside operations performed has as the main steps of dismantling process the followings: positioning front of Calandria structure at the fuel channel to be decommissioned, coupling and locking to the End Fitting (EF, sorting and storage extracted items in the safe container. All steps are performed in automatic mode. The remote control robot (RCR represents a safety system controlled by sensors and has the capability to analyze any error registered and decide next activities or abort the outside decommissioning procedure in case of any risk rise in order to ensure the environmental and workers protection.

  10. CONSIDERATIONS FOR THE DEVELOPMENT OF A DEVICE FOR THE DECOMMISSIONING OF THE HORIZONTAL FUEL CHANNELS IN THE CANDU 6 NUCLEAR REACTOR PART 5 - FUEL CHANEL DECOMMISSIONING

    Directory of Open Access Journals (Sweden)

    Gabi ROSCA FARTAT

    2014-05-01

    Full Text Available As many nuclear power plants are reaching their end of lifecycle, the decommissioning of these installations has become one of the 21st century’s great challenges. Each project may be managed differently, depending on the country, development policies, financial considerations, and the availability of qualified engineers or specialized companies to handle such projects. The principle objective of decommissioning is to place a facility into such a condition that there is no unacceptable risk from the decommissioned facility to public health and safety of the environment. In order to ensure that at the end of its life the risk from a facility is within acceptable bounds, action is normally required. The overall decommissioning strategy is to deliver a timely, cost-effective program while maintaining high standards of safety, security and environmental protection. If facilities were not decommissioned, they could degrade and potentially present an environmental radiological hazard in the future. Simply abandoning or leaving a facility after ceasing operations is not considered to be an acceptable alternative to decommissioning. The final aim of decommissioning is to recover the geographic site to its original condition.

  11. An evaluation of cost estimates of nuclear power reactor decommissioning in Sweden, Germany and the United States

    Energy Technology Data Exchange (ETDEWEB)

    Andersson, S.O.; Varley, G.; Heibel, R.; Rusch, C. [NAC International, Zurich (Switzerland)

    1995-11-01

    Nominal base decommissioning cost estimates in Sweden, Germany and the US differ by large amounts. Even after adjustments to normalize the work scopes, significant cost differences remain. Variations in national cost structures, achievable productivity, the extent of preexisting infrastructure and institutional factors all contribute to make up the differences. Exchange rate aberrations are a complication for which appropriate adjustments have to be made in order to achieve a meaningful comparison. Our analyses demonstrate that virtually all these differences between the Swedish, German and US estimates can be explained by these factors. In terms of the overall reasonableness of the Swedish estimate as a basis for making financial provisions, there remain some issues that may warrant further investigation. One is the potential for and financial consequences of a serious interruption to the proposed sea transportation system. Secondly, the limited number of individual system analyses we have performed indicated some significant potential underestimates. For example, dismantling of the reactor pressure vessel costs appear to be underestimated by up to 70 MSEK (about 10 MUSD) per reactor, or up to 900 MSEK for the whole Swedish program of 12 reactors. Overall, the Swedish estimates appear to be built up in a logical and reasonable way. Our analyses indicate that some internal inconsistencies exist and that some specific input data assumptions may not be valid. In summary, the credibility of the estimates would benefit from further refinement of the scenarios and assumptions. 21 refs., 15 figs., 42 tabs.

  12. BLENDED CALCIUM ALUMINATE-CALCIUM SULFATE CEMENT-BASED GROUT FOR P-REACTOR VESSEL IN-SITU DECOMMISSIONING

    Energy Technology Data Exchange (ETDEWEB)

    Langton, C.; Stefanko, D.

    2011-03-10

    The objective of this report is to document laboratory testing of blended calcium aluminate - calcium hemihydrate grouts for P-Reactor vessel in-situ decommissioning. Blended calcium aluminate - calcium hemihydrate cement-based grout was identified as candidate material for filling (physically stabilizing) the 105-P Reactor vessel (RV) because it is less alkaline than portland cement-based grout which has a pH greater than 12.4. In addition, blended calcium aluminate - calcium hemihydrate cement compositions can be formulated such that the primary cementitious phase is a stable crystalline material. A less alkaline material (pH {<=} 10.5) was desired to address a potential materials compatibility issue caused by corrosion of aluminum metal in highly alkaline environments such as that encountered in portland cement grouts [Wiersma, 2009a and b, Wiersma, 2010, and Serrato and Langton, 2010]. Information concerning access points into the P-Reactor vessel and amount of aluminum metal in the vessel is provided elsewhere [Griffin, 2010, Stefanko, 2009 and Wiersma, 2009 and 2010, Bobbitt, 2010, respectively]. Radiolysis calculations are also provided in a separate document [Reyes-Jimenez, 2010].

  13. Fukushima Daiichi Unit 1 Accident Progression Uncertainty Analysis and Implications for Decommissioning of Fukushima Reactors - Volume I.

    Energy Technology Data Exchange (ETDEWEB)

    Gauntt, Randall O. [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States); Mattie, Patrick D. [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States)

    2016-01-01

    Sandia National Laboratories (SNL) has conducted an uncertainty analysis (UA) on the Fukushima Daiichi unit (1F1) accident progression with the MELCOR code. The model used was developed for a previous accident reconstruction investigation jointly sponsored by the US Department of Energy (DOE) and Nuclear Regulatory Commission (NRC). That study focused on reconstructing the accident progressions, as postulated by the limited plant data. This work was focused evaluation of uncertainty in core damage progression behavior and its effect on key figures-of-merit (e.g., hydrogen production, reactor damage state, fraction of intact fuel, vessel lower head failure). The primary intent of this study was to characterize the range of predicted damage states in the 1F1 reactor considering state of knowledge uncertainties associated with MELCOR modeling of core damage progression and to generate information that may be useful in informing the decommissioning activities that will be employed to defuel the damaged reactors at the Fukushima Daiichi Nuclear Power Plant. Additionally, core damage progression variability inherent in MELCOR modeling numerics is investigated.

  14. An evaluation of alternative reactor vessel cutting technologies for the experimental boiling water reactor at Argonne National Laboratory

    Energy Technology Data Exchange (ETDEWEB)

    Boing, L.E.; Henley, D.R. (Argonne National Lab., IL (USA)); Manion, W.J.; Gordon, J.W. (Nuclear Energy Services, Inc., Danbury, CT (USA))

    1989-12-01

    Metal cutting techniques that can be used to segment the reactor pressure vessel of the Experimental Boiling Water Reactor (EBWR) at Argonne National Laboratory (ANL) have been evaluated by Nuclear Energy Services. Twelve cutting technologies are described in terms of their ability to perform the required task, their performance characteristics, environmental and radiological impacts, and cost and schedule considerations. Specific recommendations regarding which technology should ultimately be used by ANL are included. The selection of a cutting method was the responsibility of the decommissioning staff at ANL, who included a relative weighting of the parameters described in this document in their evaluation process. 73 refs., 26 figs., 69 tabs.

  15. Nuclear Research Reactor IEA-R1 - A Study of the Preparing for Decommissioning

    Energy Technology Data Exchange (ETDEWEB)

    Lopes, Valdir Maciel; Filho, Tufic Madi; Ricci, Walter; Martins, Mauro Onofre; Pereira, Maria da Conceicao [Instituto de Pesquisas Energeticas e Nucleares IPEN/CNEN - Sao Paulo, Av. Professor Lineu Prestes n 2242, USP, Sao Paulo (Brazil)

    2015-07-01

    The Institute of Energy and Nuclear Research (IPEN), Sao Paulo, according to the assignments given by the National Commission of Nuclear Energy (CNEN), enabled the development of this study, especially operational reports about refurbishing carried out on 2013, involving the production of radioisotopes and research in the areas of Radiochemistry and Nuclear Physics. These reports are made in accordance with established standard procedures to meet the requirements of CNEN (National Nuclear Energy Commission, the regulator the nuclear area activities in Brazil) and IAEA (International Atomic Energy Agency). This study presents an assessment of the procedures and methods of treatments for decontamination of the refrigeration primary circuit and changes parts, equipment and tubes of the of the IEA-R1 nuclear research reactor, pool type, power between 3,5 and 4,5 MW. In order to have a sequence in the work, the well-known contaminant radioisotopes were evaluated firstly, using Geiger- Muller equipment. In the second phase, the decontamination was done manually together with the ultrasound cleaning and washing equipment. From the several water solutions of citric acid assessment, the concentration with better confidence was obtained; in order to achieve the best results for decontamination. This study intends to define the best process for decontamination with low taxes of waste and without expensive costs. (authors)

  16. Guidelines of Decommissioning Schedule Establishment

    Energy Technology Data Exchange (ETDEWEB)

    Oh, Jae Yong; Yun, Taesik; Kim, Younggook; Kim, Hee-Geun [KHNP CRI, Daejeon (Korea, Republic of)

    2016-10-15

    Decommissioning has recently become an issue highlighted in Korea due to the Permanent Shutdown (PS) of Kori-1 plant. Since Korea Hydro and Nuclear Power (KHNP) Company decided the PS of Kori-1 instead of further continued operation, Kori-1 will be the first decommissioning plant of the commercial reactors in Korea. Korean regulatory authority demands Initial Decommissioning Plan (IDP) for all the plants in operation and under construction. In addition, decommissioning should be considered for the completion of the life cycle of NPPs. To date, Korea has no experience regarding decommissioning of the commercial reactor and a lot of uncertainties will be expected due to its site-specific factors. However, optimized decommissioning process schedule must be indispensable in the safety and economic efficiency of the project. Differed from USA, Korea has no experience and know-hows of the operation and site management for decommissioning. Hence, in Korea, establishment of decommissioning schedule has to give more weight to safety than precedent cases. More economical and rational schedule will be composed by collecting and analyzing the experience data and site-specific data and information as the decommissioning progresses. In a long-range outlook, KHNP having capability of NPP decommissioning will try to decommissioning business in Korea and foreign countries.

  17. CHIMNEY FOR BOILING WATER REACTOR

    Science.gov (United States)

    Petrick, M.

    1961-08-01

    A boiling-water reactor is described which has vertical fuel-containing channels for forming steam from water. Risers above the channels increase the head of water radially outward, whereby water is moved upward through the channels with greater force. The risers are concentric and the radial width of the space between them is somewhat small. There is a relatively low rate of flow of water up through the radially outer fuel-containing channels, with which the space between the risers is in communication. (AE C)

  18. Water chemistry management of research reactor in JAERI

    Energy Technology Data Exchange (ETDEWEB)

    Yoshijima, Tetsuo [Japan Atomic Energy Research Inst., Tokai, Ibaraki (Japan). Tokai Research Establishment

    1998-10-01

    The JRR-3M cooling system consists of four systems, namely; (1) primary cooling system, (2) heavy water cooling system, (3) helium system and (4) secondary cooling system. The heavy water is used for reflector and pressurized with helium gas. Water chemistry management of the JRR-3M cooling systems is one of the important subject for the safety operation. The main objects are to prevent the corrosion of cooling system and fuel elements, to suppress the plant radiation build-up and to minimize the generation of radioactive waste. All measured values were within the limits of specifications and JRR-3M reactor was operated with safety in 1996. Spent fuels of JRR-3M reactor are stored in the spent fuel pool. This pool water has been analyzed to prevent corrosion of aluminum cladding of spent fuels. Water chemistry of spent fuel pool water is applied to the prevention of corrosion of aluminum alloys including fuel cladding. The JRR-2 reactor was eternally stopped in December 1996 and is now under decommissioning. The JRR-2 reactor is composed of heavy water tank, fuel guide tube and horizontal experimental hole. These are constructed of aluminum alloy and biological shield and upper shield are constructed of concrete. Three types of corrosion of aluminum alloy were observed in the JRR-2. The Alkaline corrosion of aluminum tube occurred in 1972 because of the mechanical damage of the aluminum fuel guide tube which is used for fuel handling. Modification of the reactor top shield was started in 1974 and completed in 1975. (author)

  19. Fracture toughness of weld metal samples removed from a decommissioned Magnox reactor pressure vessel

    Energy Technology Data Exchange (ETDEWEB)

    Bolton, C.J.; Bischler, P.J.E.; Wootton, M.R.; Moskovic, R.; Morri, J.R.; Pegg, H.C.; Haines, A.B.; Smith, R.F.; Woodman, R

    2002-08-01

    Submerged-arc welds in Magnox RPVs are expected to show substantial shifts in ductile-to-brittle transition temperature (DBTT), due to their high copper content, and also because of a contribution from intergranular fracture. For structural integrity arguments, the fracture toughness of irradiated welds is predicted by applying an irradiation shift in DBTT to a start-of-life toughness curve. The shift is obtained from a trend curve derived from Charpy impact data. An uncertainty allowance is obtained by combining uncertainty contributions in start-of-life fracture toughness and shifts, including a contribution from uncertainties in neutron dose. Through-thickness samples were removed from four submerged-arc welds in a decommissioned Magnox RPV at Trawsfynydd. Fracture toughness tests were made on pre-cracked Charpy geometry specimens made from the samples, in order to compare the measured toughnesses with those predicted for irradiated material. Specimens were tested from several positions along the welds and also at four different through-thickness locations with dpa doses varying by a factor of more than 2. The paper presents the results of nearly 400 toughness measurements and demonstrates that the prediction methodology is sound.

  20. Decommissioning and environmental remediation scenario development for Fukushima Daiichi

    Energy Technology Data Exchange (ETDEWEB)

    Kawamura, Hideki [mcm japan, Tokyo (Japan); Yashio, Shoko [Obayashi Corporation, Tokyo (Japan); McKinley, Ian G. [McKinley Consulting, Frick (Switzerland)

    2017-07-15

    Although the general approach to reactor decommissioning is well established, there is no direct precedent for managing the 6 units of the Fukushima Daiichi nuclear power plant. Apart from damaged reactors, challenges include extensive contamination of the entire reactor site and a huge tank farm currently storing contaminated cooling water. In order to move forward with planning decommissioning, it is important to decide on the desired end state of the site and understand the impact on such a decision on the costs, hazards and environmental impact of the project. A decommissioning roadmap and reference dismantling concept provide a basis for short-term planning, but the potential for technological optimisation should be carefully considered.

  1. Decommissioning, Dismantling and Disarming: a Unique Information Showroom Inside the G2 Reactor at Marcoule Centre (France) - 12068

    Energy Technology Data Exchange (ETDEWEB)

    Volant, Emmanuelle [CEA DAM, Bruyeres-le-Chatel (France); Garnier, Cedric [CEA DEN, Marcoule (France)

    2012-07-01

    The paper aims at presenting the new information showroom called 'Escom G2' (for 'Espace Communication') inaugurated by the French Atomic Energy and Alternative Energies Commission (CEA) in spring 2011. This showroom is settled directly inside the main building of the G2 nuclear reactor: a facility formerly dedicated to weapon-grade plutonium production since the late 1950's at the Marcoule nuclear centre, in south of France. After its shutdown, and reprocessing of the last spent fuels, a first dismantling step was successfully completed from 1986 to 1996. Unique in France and in Europe, Escom G2 is focused on France dismantling expertise and its action for disarmament. This showroom comprises of a 300-square meters permanent exhibition, organized around four themes: France strategy for disarmament, decommissioning and dismantling technical aspects, uranium and plutonium production cycles. Each of these topics is illustrated with posters, photos, models and technical pieces from the dismantled plants. It is now used to present France's action in disarmament to highly ranked audiences such as: state representatives, diplomats, journalists... The paper explains the background story of this original project. As a matter of fact, in 1996 France was the first nuclear state to decide to shut down and dismantle its fissile material production facilities for nuclear weapons. First, the paper presents the history of the G2 reactor in the early ages of Marcoule site, its operating highlights as well as its main dismantling operations, are presented. In Marcoule, where the three industrial-scale reactors G1, G2 and G3 used to be operated for plutonium production (to be then reprocessed in the nearby UP1 plant), the initial dismantling phase has now been completed (in 1980's for G1 and in 1996 for G2 and G3). The second phase, aimed at completely dismantling these three reactors, will restart in 2020, and is directly linked to the opening of

  2. HEAVY WATER MODERATED NEUTRONIC REACTOR

    Science.gov (United States)

    Szilard, L.

    1958-04-29

    A nuclear reactor of the type which utilizes uranium fuel elements and a liquid coolant is described. The fuel elements are in the form of elongated tubes and are disposed within outer tubes extending through a tank containing heavy water, which acts as a moderator. The ends of the fuel tubes are connected by inlet and discharge headers, and liquid bismuth is circulated between the headers and through the fuel tubes for cooling. Helium is circulated through the annular space between the outer tubes in the tank and the fuel tubes to cool the water moderator to prevent boiling. The fuel tubes are covered with a steel lining, and suitable control means, heat exchange means, and pumping means for the coolants are provided to complete the reactor assembly.

  3. Design guide for category II reactors light and heavy water cooled reactors. [US DOE

    Energy Technology Data Exchange (ETDEWEB)

    Brynda, W J; Lobner, P R; Powell, R W; Straker, E A

    1978-05-01

    The Department of Energy (DOE), in the ERDA Manual, requires that all DOE-owned reactors be sited, designed, constructed, modified, operated, maintained, and decommissioned in a manner that gives adequate consideration to health and safety factors. Specific guidance pertinent to the safety of DOE-owned reactors is found in Chapter 0540 of the ERDA Manual. The purpose of this Design Guide is to provide additional guidance to aid the DOE facility contractor in meeting the requirement that the siting, design, construction, modification operation, maintainance, and decommissioning of DOW-owned reactors be in accordance with generally uniform standards, guide and codes which are comparable to those applied to similar reactors licensed by the Nuclear Regulatory Commission (NRC). This Design Guide deals principally with the design and functional requirements of Category II reactor structure, components, and systems.

  4. CONSIDERATIONS FOR THE DEVELOPMENT OF A DEVICE FORTHE DECOMMISSIONING OF THE FUEL CHANNELS IN THECANDU NUCLEAR REACTOR

    Directory of Open Access Journals (Sweden)

    Gabi ROSCA FARTAT

    2013-05-01

    Full Text Available As many nuclear power plants are reaching their end of lifecycle, the decommissioning of theseinstallations has become one of the 21stcentury’s great challenges. Each project may be managed differently,depending on the country, development policies, financial considerations, and the availability of qualifiedengineers or specialized companies to handle such projects. The principle objective of decommissioning is toplace a facility into such a condition that there is no unacceptable risk from the decommissioned facility topublic health and safety of the environment. In order to ensure that at the end of its life the risk from a facility iswithin acceptable bounds, action is normally required. The overall decommissioning strategy is todeliver a timely, cost-effective program while maintaining high standards of safety, security and environmentalprotection. If facilities were not decommissioned, they could degrade and potentially present an environmentalradiological hazard in the future. Simply abandoning or leaving a facility after ceasing operations is notconsidered to be an acceptable alternative to decommissioning. The final aim of decommissioning is torecover the geographic site to its original condition.

  5. SUPERHEATING IN A BOILING WATER REACTOR

    Science.gov (United States)

    Treshow, M.

    1960-05-31

    A boiling-water reactor is described in which the steam developed in the reactor is superheated in the reactor. This is accomplished by providing means for separating the steam from the water and passing the steam over a surface of the fissionable material which is not in contact with the water. Specifically water is boiled on the outside of tubular fuel elements and the steam is superheated on the inside of the fuel elements.

  6. Blue Ribbon Commission, Yucca Mountain Closure, Court Actions - Future of Decommissioned Reactors, Operating Reactors and Nuclear Power - 13249

    Energy Technology Data Exchange (ETDEWEB)

    Devgun, Jas S. [Nuclear Power Technologies, Sargent and Lundy LLC1, Chicago, IL (United States)

    2013-07-01

    Issues related to back-end of the nuclear fuel cycle continue to be difficult for the commercial nuclear power industry and for the decision makers at the national and international level. In the US, the 1982 NWPA required DOE to develop geological repositories for SNF and HLW but in spite of extensive site characterization efforts and over ten billion dollars spent, a repository opening is nowhere in sight. There has been constant litigation against the DOE by the nuclear utilities for breach of the 'standard contract' they signed with the DOE under the NWPA. The SNF inventory continues to rise both in the US and globally and the nuclear industry has turned to dry storage facilities at reactor locations. In US, the Blue Ribbon Commission on America's Nuclear Future issued its report in January 2012 and among other items, it recommends a new, consent-based approach to siting of facilities, prompt efforts to develop one or more geologic disposal facilities, and prompt efforts to develop one or more consolidated storage facilities. In addition, the March 2011 Fukushima Daiichi accident had a severe impact on the future growth of nuclear power. The nuclear industry is focusing on mitigation strategies for beyond design basis events and in the US, the industry is in the process of implementing the recommendations from NRC's Near Term Task Force. (authors)

  7. Advanced Fuel Cycle Economic Analysis of Symbiotic Light-Water Reactor and Fast Burner Reactor Systems

    Energy Technology Data Exchange (ETDEWEB)

    D. E. Shropshire

    2009-01-01

    The Advanced Fuel Cycle Economic Analysis of Symbiotic Light-Water Reactor and Fast Burner Reactor Systems, prepared to support the U.S. Advanced Fuel Cycle Initiative (AFCI) systems analysis, provides a technology-oriented baseline system cost comparison between the open fuel cycle and closed fuel cycle systems. The intent is to understand their overall cost trends, cost sensitivities, and trade-offs. This analysis also improves the AFCI Program’s understanding of the cost drivers that will determine nuclear power’s cost competitiveness vis-a-vis other baseload generation systems. The common reactor-related costs consist of capital, operating, and decontamination and decommissioning costs. Fuel cycle costs include front-end (pre-irradiation) and back-end (post-iradiation) costs, as well as costs specifically associated with fuel recycling. This analysis reveals that there are large cost uncertainties associated with all the fuel cycle strategies, and that overall systems (reactor plus fuel cycle) using a closed fuel cycle are about 10% more expensive in terms of electricity generation cost than open cycle systems. The study concludes that further U.S. and joint international-based design studies are needed to reduce the cost uncertainties with respect to fast reactor, fuel separation and fabrication, and waste disposition. The results of this work can help provide insight to the cost-related factors and conditions needed to keep nuclear energy (including closed fuel cycles) economically competitive in the U.S. and worldwide. These results may be updated over time based on new cost information, revised assumptions, and feedback received from additional reviews.

  8. Decommissioning of the Nuclear Reactors R2 and R2-0 at Studsvik, Sweden. General Data as called for under Article 37 of the Euratom Treaty

    Energy Technology Data Exchange (ETDEWEB)

    2009-01-15

    This document describes the plans for decommissioning of the nuclear research and material test reactors R2 and R2-0, situated at the Studsvik site close to the city of Nykoeping, Sweden. The purpose of the document is to serve as information for the European Commission, and to fulfil the requirements of Article 37 of the Euratom Treaty. Studsvik is situated on the Baltic coast, about 20 km east of Nykoeping and 80 km southwest of Stockholm. The site comprises the reactors R2 and R2-0 and several facilities for material investigation and radioactive waste treatment and storage. The reactors were used for a number of different purposes from 1960 until June 2005, when they were shut down following a decision by the operator. Decommissioning of the reactor facility is planned to be completed in 2016 after dismantling and conditioning of radioactive parts and demolition of the facility. Solid and liquid radioactive wastes from the dismantling activities will be treated and stored on-site awaiting final disposal. The waste treatment facilities, which are situated in other buildings at the Studsvik site, are planned to continue operation during and after the decommissioning of the reactor facility. All nuclear fuel has been transferred to a separate storage facility and is being shipped to the US according to existing agreements. The objective of the planned dismantling activities is to achieve clearance of the facility to make it possible to either demolish the buildings or use them for other purposes. The operator has divided the planning for dismantling and demolition of the facility into three phases [1]: Dismantling 1, including primary system decontamination, dismantling of the reactors with systems in the reactor pool, draining, cleaning and temporary covering of the reactor pool. This phase has begun and is due to last till approximately December 2009. Dismantling 2, including dismantling of systems in the reactor facility, removal of equipment, radiological

  9. Supercritical-pressure light water cooled reactors

    CERN Document Server

    Oka, Yoshiaki

    2014-01-01

    This book focuses on the latest reactor concepts, single pass core and experimental findings in thermal hydraulics, materials, corrosion, and water chemistry. It highlights research on supercritical-pressure light water cooled reactors (SCWRs), one of the Generation IV reactors that are studied around the world. This book includes cladding material development and experimental findings on heat transfer, corrosion and water chemistry. The work presented here will help readers to understand the fundamental elements of reactor design and analysis methods, thermal hydraulics, materials and water

  10. Cleaning natural water in the clarifier reactor

    Science.gov (United States)

    Skolubovich, Yuriy; Skolubovich, Aleksandr; Voitov, Evgeniy; Soppa, Mikhail; Chirkunov, Yuriy

    2017-10-01

    The problems of cleaning low turbidity high-color surface waters for drinking water supply are considered. A new design of the clarifier reactor is proposed, which increases the efficiency of water purification and at the same time reduces its operating costs. A detailed description of clarifier reactor design and its operation is given. The study results of the clarifier reactor operation in real conditions for the purification of low turbidity high-color waters are shown. Due to the weighted layer of dense loading use in a process of water purification, the structure productivity can be increased by 2-3 times in comparison with conventional clarifiers with suspended sediment. Using reagents for water purification, the clarifier reactor, due to the processes of contact coagulation, allows reducing the consumption of reagents up to 50%. Investigations of the clarifier reactor operation in technological schemes for various waters purification, including sewage, showed their effectiveness and prospects.

  11. 2016 Inspection and Annual Site Status Report for the Site A/Plot M, Illinois, Decommissioned Reactor Site July 2016

    Energy Technology Data Exchange (ETDEWEB)

    Murl, Jeffrey [USDOE Office of Legacy Management, Washington, DC (United States); Miller, Michele [Navarro Research and Engineering, Oak Ridge, TN (United States)

    2016-07-01

    The Site A/Plot M, Illinois, Decommissioned Reactor Site was inspected on May 17, 2016. The site, located within Cook County forest preserve that is open to the public, was found to be in good condition with one exception. Erosion on top of the grass-covered mound at Plot M continues to be a concern as presented in previous inspections. Ruts form in the soil on top of Plot M as a result of bike traffic using the open field as a pass thru between established bike trails within the forest preserve. Argonne National Laboratory (ANL) who is contracted directly from U.S. Department of Energy (DOE) has filled in the ruts with top soil and reseeding remains an ongoing process. Reseeded areas from 2015 are progressing nicely. No cause for a follow-up inspection was identified. In 2015, ANL plugged and abandoned 8 of 25 monitoring wells (BH41, BH51, BH52, BH54, DH9, DH10, DH13, and DH17). The 17 groundwater monitoring wells remaining at the site were inspected to confirm that they were locked and in good condition. Preliminary environmental monitoring results for 2015 are provided in a draft report titled Surveillance of Site A and Plot M, Report for 2015, prepared by ANL. The report also contains results of an independent analysis conducted by the Illinois Emergency Management Agency on some of the samples collected by ANL in 2015. The draft report states that the results of the surveillance program continue to indicate that the impact of radioactivity at Site A/Plot M is very low and does not endanger the health of those living in the area or visiting the site. The ANL monitoring report will be made available to the public on the DOE Office of Legacy Management public website when it is issued as final. A new county forest preserve campsite opened in 2015 at Bull Frog Lake, which is east of Plot M. Hiking trails connect Bull Frog Lake with Site A/Plot M. The site might receive more traffic from forest preserve visitors now that this new campsite is opened.

  12. Decommissioning Handbook

    Energy Technology Data Exchange (ETDEWEB)

    1994-03-01

    The Decommissioning Handbook is a technical guide for the decommissioning of nuclear facilities. The decommissioning of a nuclear facility involves the removal of the radioactive and, for practical reasons, hazardous materials to enable the facility to be released and not represent a further risk to human health and the environment. This handbook identifies and technologies and techniques that will accomplish these objectives. The emphasis in this handbook is on characterization; waste treatment; decontamination; dismantling, segmenting, demolition; and remote technologies. Other aspects that are discussed in some detail include the regulations governing decommissioning, worker and environmental protection, and packaging and transportation of the waste materials. The handbook describes in general terms the overall decommissioning project, including planning, cost estimating, and operating practices that would ease preparation of the Decommissioning Plan and the decommissioning itself. The reader is referred to other documents for more detailed information. This Decommissioning Handbook has been prepared by Enserch Environmental Corporation for the US Department of Energy and is a complete restructuring of the original handbook developed in 1980 by Nuclear Energy Services. The significant changes between the two documents are the addition of current and the deletion of obsolete technologies and the addition of chapters on project planning and the Decommissioning Plan, regulatory requirements, characterization, remote technology, and packaging and transportation of the waste materials.

  13. DETAILS OF OPERATIONS PERFORMED BY THE REMOTE CONTROL ROBOT (CONCEPT TO THE HORIZONTAL FUEL CHANNEL DURING DECOMMISSIONING PHASE OF NUCLEAR REACTOR CALANDRIA STRUCTURE. PART II: INSIDE OPERATIONS

    Directory of Open Access Journals (Sweden)

    Constantin POPESCU

    2017-05-01

    Full Text Available The authors contribution to this paper is to present a concept solution of a remote control robot (RCR used for decommissioning of the horizontal fuel channels pressure tube in the CANDU nuclear reactor. In this paper the authors highlight few details of geometry, operations, constraints by kinematics and dynamics of the robot movement inside of the reactor fuel channel. Inside operations performed has as the main steps of dismantling process the followings: unblock and extract the channel closure plug (from End Fitting - EF, unblock and extract the channel shield plug (from Lattice Tube - LT, cut the ends of the pressure tube, extract the pressure tube and cut it in small parts, sorting and storage extracted items in the safe robot container. All steps are performed in automatic mode. The remote control robot (RCR represents a safety system controlled by sensors and has the capability to analyze any error registered and decide next activities or abort the inside decommissioning procedure in case of any risk rise in order to ensure the environmental and workers protection.

  14. Advances in light water reactor technologies

    CERN Document Server

    Saito, Takehiko; Ishiwatari, Yuki; Oka, Yoshiaki

    2010-01-01

    ""Advances in Light Water Reactor Technologies"" focuses on the design and analysis of advanced nuclear power reactors. This volume provides readers with thorough descriptions of the general characteristics of various advanced light water reactors currently being developed worldwide. Safety, design, development and maintenance of these reactors is the main focus, with key technologies like full MOX core design, next-generation digital I&C systems and seismic design and evaluation described at length. This book is ideal for researchers and engineers working in nuclear power that are interested

  15. The D&D of the Experimental Boiling Water Reactor (EBWR)

    Energy Technology Data Exchange (ETDEWEB)

    Fellhauer, C.R.; Boling, L.E.; Yule, T.J.; Bhattacharyya, S.K.

    1996-03-01

    Argonne National Laboratory has completed the D&D of the Experimental Boiling Water Reactor. The Project consisted of decontaminating and for packaging as radioactive waste the reactor vessel and internals, contaminated piping systems, miscellaneous tanks, pumps, and associated equipment. The D&D work involved dismantling process equipment and associated plumbing, ductwork drain lines, etc., performing size reduction of reactor vessel internals in the fuel pool, packaging and manifesting all radioactive and mixed waste, and performing a thorough survey of the facility after the removal of activated and contaminated material. Non-radioactive waste was disposed of in the ANL-E landfill or recycled. In January 1996 the EBWR facility was formally decommissioned and transferred from EM-40 to EM-30. This paper will discuss the details of this ten year effort.

  16. Decommissioning: a problem or a challenge?

    Directory of Open Access Journals (Sweden)

    Mele Irena

    2004-01-01

    Full Text Available With the ageing of nuclear facilities or the reduced interest in their further operation, a new set of problems, related to the decommissioning of these facilities, has come into forefront. In many cases it turns out that the preparations for decommissioning have come too late, and that financial resources for covering decommissioning activities have not been provided. To avoid such problems, future liailities should be thoroughly estimated in drawing up the decommissioning and waste management programme for each nuclear facility in time, and financial provisions for implementing such programme should be provided. In this paper a presentation of current decommissioning experience in Slovenia is given. The main problems and difficulties in decommissioning of the Žirovski Vrh Uranium Mine are exposed and the lesson learned from this case is presented. The preparation of the decommissioning programme for the Nuclear Power Plant Krško is also described, and the situation at the TRIGA research reactor is briefly discussed.

  17. CONSIDERATIONS FOR THE DEVELOPMENT OF A DEVICE FOR THE DECOMMISSIONING OF THE HORIZONTAL FUEL CHANNELS IN THE CANDU 6 NUCLEAR REACTOR. PART 10 - PRESENTATION OF THE DECOMMISSIONING DEVICE OPERATING

    Directory of Open Access Journals (Sweden)

    Constantin D. STANESCU,

    2015-05-01

    Full Text Available This paper presents a solution proposed by the authors in order to achieve of a cutting and extracting device operating panel for the decommissioning of the horizontal fuel channels in the CANDU 6 nuclear reactor. The Cutting and Extraction Device (CED is fully automated, connected by wires to a Programmable Logic Controller (PLC and controlled from a Human Machine Interface (HMI. The Cutting and Extraction Device (CED performs the dismantling, cutting and extraction of the fuel channel components, moving with variable speed, temperature monitoring and video surveillance inside the pipe, unblock and extract the channel closure plug (from End Fitting - EF, unblock and extract the channel shield plug (from Lattice Tube - LT, block and cut the middle of the pressure tube, block and cut the end of the pressure tube, block and extract the half of pressure tube. All operations can be monitored and controlled from a operating panel. The PLC fully command the device in automatic or manually mode, to control the internal sensors, transducers, electrical motors, video surveillance and pyrometers for monitoring cutting place temperature. The device controller has direct access to the measured values with these sensors, interprets and processes them, preparing the next actionafter confirming the action in progress. The design of the Cutting and Extraction Device (CED shall be achieved according to the particular features of the fuel channel components to be dismantled and to ensure radiation protection of workers.

  18. Considerations about decommissioning of the IEA-R1 research reactor and the future of its installations after shutdown; Consideracoes sobre o descomissionamento do reator de pesquisa IEA-R1 e futuro de suas instalacoes apos o seu desligamento

    Energy Technology Data Exchange (ETDEWEB)

    Frajndlich, Roberto

    2014-07-01

    The IEA-R1 Nuclear Research Reactor, in operation since 1957, in the Instituto de Pesquisas Energeticas e Nucleares (IPEN-CNEN/SP), is one of the oldest research reactors in the world. However at some point in time in the future, as example of the other reactors, it will be shutdown definitively. Before that time actually arrives, the operational organization needs to plan the future of its installations and define the final destination of equipment and radioactive as well as non-radioactive material contained inside the installations. These and other questions should be addressed in the so called Preliminary decommissioning plan of the installation, which is the subject of this work. The work initially presents an over view about the theme and defines the general and specific objectives describing, in succession, the directions that the operating organization should consider for the formulation of a decommissioning plan. The present structure of the Brazilian nuclear sector emphasizing principally the norms utilized in the management of radioactive waste is also presented. A description of principle equipment of the IEA-R1 reactor which constitutes its inventory of radioactive and non-radioactive material is given. The work emphasizes the experience of the reactor technicians, acquired during several reforms and modifications of the reactor installations realized during its useful life time. This experience may be of great help for the decommissioning in the future. An experiment using the high resolution gamma spectrometric method and computer calculation using Monte Carlo theory were performed with the objective of obtaining an estimate of the radioactive waste produced from dismantling of the reactor pool walls. The cost of reactor decommissioning for different choices of strategies was determined using the CERREX code. Finally, a discussion about different strategies is presented. On the basis of these discussions it is concluded that the most advantageous

  19. Rapid Recovery of Chironomidae (Diptera) in Little Mill Creek (Kansas, U.S.A.) After the Decommissioning of a Waste Water Treatment Plant

    Science.gov (United States)

    Bouchard, R. W.; Ferrington, L. C.

    2005-05-01

    In June 1995 the Lenexa Waste Water Treatment Plant was decommissioned, providing an opportunity to study recovery of Chironomidae community structure in Little Mill Creek. Using pupal exuviae, weekly changes in the species richness and composition of Chironomidae emerging upstream and downstream of the effluent outfall was evaluated from two weeks before decommissioning to eight weeks post-decommissioning. Chironomidae emergence was clearly different between upstream and downstream sites both before and shortly after effluent input ceased. Before decommissioning, sites immediately downstream of the effluent had low species richness and were dominated by Chironomus riparius (Meigen) and other tolerant taxa, with some recovery at sites farther downstream. Two weeks after decommissioning, only sites immediately downstream of the former effluent were clearly impacted, but effects were reduced compared to pre-recovery collections. At five weeks post-decommissioning, species richness was only slightly lower at the sites immediately downstream of the former effluent and the composition of common species (i.e., >5% of relative abundance) was similar between upstream and downstream sites. Rapid recovery of chironomid emergence below the sewage effluent likely resulted from both colonization of drifting larvae from upstream sources and adult dispersal and oviposition, indicating rapid responses in emergence as water quality conditions improved.

  20. SELF-REGULATING BOILING-WATER NUCLEAR REACTORS

    Science.gov (United States)

    Ransohoff, J.A.; Plawchan, J.D.

    1960-08-16

    A boiling-water reactor was designed which comprises a pressure vessel containing a mass of water, a reactor core submerged within the water, a reflector tank disposed within the reactor, the reflector tank being open at the top to the interior of the pressure vessel, and a surge tank connected to the reflector tank. In operation the reflector level changes as a function of the pressure witoin the reactor so that the reactivity of the reactor is automatically controlled.

  1. Produced Water Treatment Using Geothermal Energy from Oil and Gas Wells: An Appropriateness of Decommissioned Wells Index (ADWI) Approach

    Science.gov (United States)

    Kiaghadi, A.; Rifai, H. S.

    2016-12-01

    This study investigated the feasibility of harnessing geothermal energy from retrofitted oil and gas decommissioned wells to power desalination units and overcome the produced water treatment energy barrier. Previous studies using heat transfer models have indicated that well depth, geothermal gradient, formation heat conductivity, and produced water salt levels were the most important constraints that affect the achievable volume of treated water. Thus, the challenge of identifying which wells would be best suited for retrofit as geothermal wells was addressed by defining an Appropriateness of Decommissioned Wells Index (ADWI) using a 25 km x 25 km grid over Texas. Heat transfer modeling combined with fuzzy logic methodology were used to estimate the ADWI at each grid cell using the scale of Very Poor, Poor, Average, Good and Excellent. Values for each of the four constraints were extracted from existing databases and were used to select 20 representative values that covered the full range of the data. A heat transfer model was run for all the 160,000 possible combination scenarios and the results were regressed to estimate weighting coefficients that indicate the relative effect of well depth, geothermal gradient, heat conductivity, and produced water salt levels on the volume of treated water in Texas. The results indicated that wells located in cells with ADWI of "Average", "Good" or "Excellent" can potentially deliver 35,000, 106,000, or 240,000 L/day of treated water, respectively. Almost 98% of the cells in the Granite Wash, 97% in Eagle Ford Shale, 90% in Haynesville Shale, 79% in Permian Basin, and 78% in Barnett Shale were identified as better than "Average" locations; whereas, south of the Eagle Ford, southwestern Permian Basin, and the center of Granite Wash were "Excellent". Importantly, most of the locations with better than "Average" ADWI are within drought prone agricultural regions that would benefit from this resilient source of clean water.

  2. Hydrogen and water reactor safety: proceedings

    Energy Technology Data Exchange (ETDEWEB)

    1982-01-01

    Separate abstracts were prepared for papers presented in the following areas of interest: 1) hydrogen research programs; 2) hydrogen behavior during light water reactor accidents; 3) combustible gas generation; 4) hydrogen transport and mixing; 5) combustion modeling and experiments; 6) accelerated flames and detonations; 7) combustion mitigation and control; and 8) equipment survivability.

  3. Light-water reactor accident classification

    Energy Technology Data Exchange (ETDEWEB)

    Washburn, B.W.

    1980-02-01

    The evolution of existing classifications and definitions of light-water reactor accidents is considered. Licensing practice and licensing trends are examined with respect to terms of art such as Class 8 and Class 9 accidents. Interim definitions, consistent with current licensing practice and the regulations, are proposed for these terms of art.

  4. Coolant mixing in pressurized water reactors

    Energy Technology Data Exchange (ETDEWEB)

    Hoehne, T.; Grunwald, G.

    1998-10-01

    The behavior of PWRs during cold water or boron dilution transients is strongly influenced by the distribution of coolant temperature and boron concentration at the core inlet. This distribution is the needed input to 3-dimensional neutron kinetics to calculate the power distribution in the core. It mainly depends on how the plugs of cold or unborated water formed in a single loop are mixed in the downcomer and in the lower plenum. To simulate such mixture phenomena requires the application of 3-dimensional CFD (computational fluid dynamics) codes. The results of the simulation have to be validated against mixture experiments at scaled facilities. Therefore, in the framework of a research project funded by BMBF, the institute creates a 1:5 mixture facility representing first the geometry of a German pressurized water reactor and later the European Pressurized Water Reactor (EPR) geometry. The calculations are based on the CFD Code CFX-4. (orig.)

  5. Rapid analysis of 14C and 3H in graphite and concrete for decommissioning of nuclear reactor

    DEFF Research Database (Denmark)

    Hou, Xiaolin

    2005-01-01

    A rapid oxidizing combustion method using a commercial Sample Oxidizer has been investigated to determine separately the C-14 and H-3 activities in graphite and concrete. By this method the sample preparation time can be reduced to 2-3min. The detection limits for H-3 and C-14 are 0.96 and 0.58Bq...... the Danish Reactors DR-2 and DR-3, in addition to two concrete cores drilled in the Danish reactor DR-2; these were analysed for H-3 and C-14 using the method that has been developed. (c) 2005 Elsevier Ltd. All rights reserved....

  6. Characterization of Decommissioned PWR Vessel Internals Materials Samples: Material Certification, Fluence, and Temperature (Nonproprietary Version)

    Energy Technology Data Exchange (ETDEWEB)

    M. Krug; R. Shogan; A. Fero; M. Snyder

    2004-11-01

    Pressurized water reactor (PWR) cores, operate under extreme environmental conditions due to coolant chemistry, operating temperature, and neutron exposure. Extending the life of PWRs require detailed knowledge of the changes in mechanical and corrosion properties of the structural austenitic stainless steel components adjacent to the fuel. This report contains basic material characterization information of the as-installed samples of reactor internals material which were harvested from a decommissioned PWR.

  7. 75 FR 43158 - Amended Record of Decision for the Decommissioning of Eight Surplus Production Reactors at the...

    Science.gov (United States)

    2010-07-23

    ... were issued. New engineering controls (such as development and deployment of robotics in an array of field applications), data collection and validation, worker safety practices, and real-time lessons... transition regarding its defense production mission at the time of the Surplus Production Reactor EIS, and...

  8. The Tokamak Fusion Test Reactor decontamination and decommissioning project and the Tokamak Physics Experiment at the Princeton Plasma Physics Laboratory. Environmental Assessment

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1994-05-27

    If the US is to meet the energy needs of the future, it is essential that new technologies emerge to compensate for dwindling supplies of fossil fuels and the eventual depletion of fissionable uranium used in present-day nuclear reactors. Fusion energy has the potential to become a major source of energy for the future. Power from fusion energy would provide a substantially reduced environmental impact as compared with other forms of energy generation. Since fusion utilizes no fossil fuels, there would be no release of chemical combustion products to the atmosphere. Additionally, there are no fission products formed to present handling and disposal problems, and runaway fuel reactions are impossible due to the small amounts of deuterium and tritium present. The purpose of the TPX Project is to support the development of the physics and technology to extend tokamak operation into the continuously operating (steady-state) regime, and to demonstrate advances in fundamental tokamak performance. The purpose of TFTR D&D is to ensure compliance with DOE Order 5820.2A ``Radioactive Waste Management`` and to remove environmental and health hazards posed by the TFTR in a non-operational mode. There are two proposed actions evaluated in this environmental assessment (EA). The actions are related because one must take place before the other can proceed. The proposed actions assessed in this EA are: the decontamination and decommissioning (D&D) of the Tokamak Fusion Test Reactor (TFTR); to be followed by the construction and operation of the Tokamak Physics Experiment (TPX). Both of these proposed actions would take place primarily within the TFTR Test Cell Complex at the Princeton Plasma Physics Laboratory (PPPL). The TFTR is located on ``D-site`` at the James Forrestal Campus of Princeton University in Plainsboro Township, Middlesex County, New Jersey, and is operated by PPPL under contract with the United States Department of Energy (DOE).

  9. A Decommissioning Information Management System

    Energy Technology Data Exchange (ETDEWEB)

    Park, S. K.; Hong, S. B.; Chung, U. S.; Park, J. H. [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2007-07-01

    In 1996, it was determined that research reactors, the KRR-1 and the KRR-2, would be shut down and dismantled. A project for the decommissioning of these reactors was launched in January 1997 with the goal of a completion by 2008. The total budget of the project was 19.4 million US dollars, including the cost for the waste disposal and for the technology development. The work scopes during the decommissioning project were the dismantling of all the facilities and the removal of all the radioactive materials from the reactor site. After the removal of the entire radioactivity, the site and buildings will be released for an unconditional use. A separate project for the decommissioning of the uranium conversion plant was initiated in 2001. The plant was constructed for the development of the fuel manufacturing technologies and the localization of nuclear fuels in Korea. It was shut downed in 1993 and finally it was concluded in 2000 that the plant would be decommissioned. The project will be completed by 2008 and the total budget was 9.2 million US dollars. During this project, all vessels and equipment will be dismantled and the building surface will be decontaminated to be utilized as general laboratories.

  10. Electrochemistry of Water-Cooled Nuclear Reactors

    Energy Technology Data Exchange (ETDEWEB)

    Macdonald, Dgiby; Urquidi-Macdonald, Mirna; Pitt, Jonathan

    2006-08-08

    This project developed a comprehensive mathematical and simulation model for calculating thermal hydraulic, electrochemical, and corrosion parameters, viz. temperature, fluid flow velocity, pH, corrosion potential, hydrogen injection, oxygen contamination, stress corrosion cracking, crack growth rate, and other important quantities in the coolant circuits of water-cooled nuclear power plants, including both Boiling Water Reactors (BWRs) and Pressurized Water Reactors (PWRs). The model is being used to assess the three major operational problems in Pressurized Water Reactors (PWR), which include mass transport, activity transport, and the axial offset anomaly, and provide a powerful tool for predicting the accumulation of SCC damage in BWR primary coolant circuits as a function of operating history. Another achievement of the project is the development of a simulation tool to serve both as a training tool for plant operators and as an engineering test-bed to evaluate new equipment and operating strategies (normal operation, cold shut down and others). The development and implementation of the model allows us to estimate the activity transport or "radiation fields" around the primary loop and the vessel, as a function of the operating parameters and the water chemistry.

  11. BOILING WATER REACTOR WITH FEED WATER INJECTION NOZZLES

    Science.gov (United States)

    Treshow, M.

    1963-04-30

    This patent covers the use of injection nozzles for pumping water into the lower ends of reactor fuel tubes in which water is converted directly to steam. Pumping water through fuel tubes of this type of boiling water reactor increases its power. The injection nozzles decrease the size of pump needed, because the pump handles only the water going through the nozzles, additional water being sucked into the tubes by the nozzles independently of the pump from the exterior body of water in which the fuel tubes are immersed. The resulting movement of exterior water along the tubes holds down steam formation, and thus maintains the moderator effectiveness, of the exterior body of water. (AEC)

  12. A study on the application of CRUDTRAN code in primary systems of domestic pressurized heavy-water reactors for prediction of radiation source term

    Energy Technology Data Exchange (ETDEWEB)

    Song, Jong Soon; Cho, Hoon Jo; Jung, Min Young; Lee, Sang Heon [Dept. of Nuclear Engineering, Chosun University, Gwangju (Korea, Republic of)

    2017-04-15

    The importance of developing a source-term assessment technology has been emphasized owing to the decommissioning of Kori nuclear power plant (NPP) Unit 1 and the increase of deteriorated NPPs. We analyzed the behavioral mechanism of corrosion products in the primary system of a pressurized heavy-water reactor-type NPP. In addition, to check the possibility of applying the CRUDTRAN code to a Canadian Deuterium Uranium Reactor (CANDU)-type NPP, the type was assessed using collected domestic onsite data. With the assessment results, it was possible to predict trends according to operating cycles. Values estimated using the code were similar to the measured values. The results of this study are expected to be used to manage the radiation exposures of operators in high-radiation areas and to predict decommissioning processes in the primary system.

  13. CONSIDERATIONS FOR THE DEVELOPMENT OF A DEVICE FOR THE DECOMMISSIONING OF THE HORIZONTAL FUEL CHANNELS IN THE CANDU 6 NUCLEAR REACTOR PART 4 - FUEL CHANNEL ASSEMBLY

    Directory of Open Access Journals (Sweden)

    Gabi ROSCA FARTAT

    2014-05-01

    Full Text Available As many nuclear power plants are reaching their end of lifecycle, the decommissioning of these installations has become one of the 21st century’s great challenges. Each project may be managed differently, depending on the country, development policies, financial considerations, and the availability of qualified engineers or specialized companies to handle such projects. The principle objective of decommissioning is to place a facility into such a condition that there is no unacceptable risk from the decommissioned facility to public health and safety of the environment. In order to ensure that at the end of its life the risk from a facility is within acceptable bounds, action is normally required. The overall decommissioning strategy is to deliver a timely, costeffective program while maintaining high standards of safety, security and environmental protection. If facilities were not decommissioned, they could degrade and potentially present an environmental radiological hazard in the future. Simply abandoning or leaving a facility after ceasing operations is not considered to be an acceptable alternative to decommissioning. The final aim of decommissioning is to recover the geographic site to its original condition.

  14. CONSIDERATIONS FOR THE DEVELOPMENT OF A DEVICE FOR THE DECOMMISSIONING OF THE HORIZONTAL FUEL CHANNELS IN THE CANDU 6 NUCLEAR REACTOR PART 3 - FUEL CHANNEL REFERENCES

    Directory of Open Access Journals (Sweden)

    Gabi ROSCA FARTAT

    2014-05-01

    Full Text Available As many nuclear power plants are reaching their end of lifecycle, the decommissioning of these installations has become one of the 21st century’s great challenges. Each project may be managed differently, depending on the country, development policies, financial considerations, and the availability of qualified engineers or specialized companies to handle such projects. The principle objective of decommissioning is to place a facility into such a condition that there is no unacceptable risk from the decommissioned facility to public health and safety of the environment. In order to ensure that at the end of its life the risk from a facility is within acceptable bounds, action is normally required. The overall decommissioning strategy is to deliver a timely, cost-effective program while maintaining high standards of safety, security and environmental protection. If facilities were not decommissioned, they could degrade and potentially present an environmental radiological hazard in the future. Simply abandoning or leaving a facility after ceasing operations is not considered to be an acceptable alternative to decommissioning. The final aim of decommissioning is to recover the geographic site to its original condition.

  15. CONSIDERATIONS FOR THE DEVELOPMENT OF A DEVICE FOR THE DECOMMISSIONING OF THE HORIZONTAL FUEL CHANNELS IN THE CANDU 6 NUCLEAR REACTOR PART 2 - FUEL CHANNEL PRESENTATION

    Directory of Open Access Journals (Sweden)

    Gabi ROSCA FARTAT

    2014-05-01

    Full Text Available As many nuclear power plants are reaching their end of lifecycle, the decommissioning of these installations has become one of the 21st century’s great challenges. Each project may be managed differently, depending on the country, development policies, financial considerations, and the availability of qualified engineers or specialized companies to handle such projects. The principle objective of decommissioning is to place a facility into such a condition that there is no unacceptable risk from the decommissioned facility to public health and safety of the environment. In order to ensure that at the end of its life the risk from a facility is within acceptable bounds, action is normally required. The overall decommissioning strategy is to deliver a timely, costeffective program while maintaining high standards of safety, security and environmental protection. If facilities were not decommissioned, they could degrade and potentially present an environmental radiological hazard in the future. Simply abandoning or leaving a facility after ceasing operations is not considered to be an acceptable alternative to decommissioning.The final aim of decommissioning is to recover the geographic site to its original condition.

  16. Decommissioning of DR 1, Final report

    Energy Technology Data Exchange (ETDEWEB)

    Lauridsen, Kurt

    2006-01-15

    The report describes the decommissioning activities carried out at the 2kW homogeneous reactor DR 1 at Risoe National Laboratory. The decommissioning work took place from summer 2004 until late autumn 2005. The components with the highest activity, the core vessel the recombiner and the piping and valves connected to these, were dismantled first by Danish Decommissioning's own technicians. Demolition of the control rod house and the biological shield as well as the removal of the floor in the reactor hall was carried out by an external demolition contractor. The building was emptied and left for other use. Clearance measurements of the building showed that radionuclide concentrations were everywhere below the clearance limit set by the Danish nuclear regulatory authorities. Furthermore, measurements on the surrounding area showed that there was no contamination that could be attributed to the operation and decommissioning of DR 1. (au)

  17. CONSIDERATIONS FOR THE DEVELOPMENT OF A DEVICE FOR THE DECOMMISSIONING OF THE HORIZONTAL FUEL CHANNELS IN THE CANDU 6 NUCLEAR REACTOR. PART 9 - CUTTING AND EXTRACTING DEVICE FUNCTIONING

    Directory of Open Access Journals (Sweden)

    Constantin POPESCU

    2015-05-01

    Full Text Available This paper presents a constructive solution proposed by the authors in order to achieve of a cutting and extracting device for the decommissioning of the horizontal fuel channels in the CANDU 6 nuclear reactor. The Cutting and Extraction Device (CED performs the dismantling, cutting and extraction of the fuel channel components. It's a flexible and modular device, which is designed to work inside the fuel channel and has the following functions: moving with variable speed, temperature monitoring and video surveillance inside the pipe, unblock and extract the channel closure plug (from End Fitting - EF, unblock and extract the channel shield plug (from Lattice Tube - LT, block and cut the middle of the pressure tube, block and cut the end of the pressure tube, block and extract the half of pressure tube. The Cutting and Extraction Device (CED consists of following modules: guiding-fixing module, traction modules, cutting module, guiding-extracting module and flexible elements for modules connecting. The guiding-fixing module is equipped with elastic guiding rollers and fixing claws in working position, the traction modules are provided with variable pitch rollers for allowing variable travel speed through the fuel channel. The cutting module is positioned in the middle of the device and it is equipped with three knife rolls for pressure tube cutting, using a system for cutting place video surveillance and pyrometers for monitoring cutting place temperature. The Cutting and Extraction Device (CED is fully automated, connected by wires to a Programmable Logic Controller (PLC and controlled from a Human Machine Interface (HMI. The design of the Cutting and Extraction Device (CED shall be achieved according to the particular features of the fuel channel components to be dismantled and to ensure radiation protection of workers.

  18. Decommissioning of offshore installations

    Energy Technology Data Exchange (ETDEWEB)

    Oeen, Sigrun; Iversen, Per Erik; Stokke, Reidunn; Nielsen, Frantz; Henriksen, Thor; Natvig, Henning; Dretvik, Oeystein; Martinsen, Finn; Bakke, Gunnstein

    2010-07-01

    and requirements that should be considered in the regulation of decommissioning facilities for offshore installations. These facilities need sound expertise to be able to identify and deal with different types of waste, including hazardous waste such as heavy metals, other hazardous substances, low specific activity (LSA) radioactive material and asbestos. Facilities must be designed to allow safe handling of such waste, with no risk of runoff or infiltration into the soil. In addition, a decommissioning facility should have an effective collection system and an on-site treatment plant for contaminated water, including surface water. Each facility must have a sampling and analysis programme to monitor releases of the most relevant pollutants. The need for an environmental monitoring programme to follow developments in the recipient should also be considered. Other factors that must be closely monitored include noise and releases to air in connection with metal cutting and other operations. Moreover, decommissioning contracts must ensure that the costs of handling hazardous waste are met by the offshore operators. When decommissioning facilities for offshore installations are being sited, other interests must also be taken into account; for example, the use of nearby areas for housing, holiday housing or recreation. In addition, the implications for other sectors such as fisheries and agriculture must be taken into consideration. These are important issues that the municipalities must consider when preparing zoning plans and drawing up environmental impact assessments. In many cases, a regional authority is in a better position than a national one to make overall, cross-sectoral assessments of developments within the region. Nevertheless, the report recommends transferring the authority for regulating decommissioning facilities for offshore installations from the County Governors to the Climate and Pollution Agency. Regulating these facilities requires special

  19. Boiling water neutronic reactor incorporating a process inherent safety design

    Science.gov (United States)

    Forsberg, C.W.

    1985-02-19

    A boiling-water reactor core is positioned within a prestressed concrete reactor vessel of a size which will hold a supply of coolant water sufficient to submerge and cool the reactor core by boiling for a period of at least one week after shutdown. Separate volumes of hot, clean (nonborated) water for cooling during normal operation and cool highly borated water for emergency cooling and reactor shutdown are separated by an insulated wall during normal reactor operation with contact between the two water volumes being maintained at interfaces near the top and bottom ends of the reactor vessel. Means are provided for balancing the pressure of the two water volumes at the lower interface zone during normal operation to prevent entry of the cool borated water into the reactor core region, for detecting the onset of excessive power to coolant flow conditions in the reactor core and for detecting low water levels of reactor coolant. Cool borated water is permitted to flow into the reactor core when low reactor coolant levels or excessive power to coolant flow conditions are encountered.

  20. Analysis of removal alternatives for the Heavy Water Components Test Reactor at the Savannah River Site. Revision 1

    Energy Technology Data Exchange (ETDEWEB)

    Owen, M.B.

    1997-04-01

    This engineering study evaluates different alternatives for decontamination and decommissioning of the Heavy Water Components Test Reactor (HWCTR). Cooled and moderated with pressurized heavy water, this uranium-fueled nuclear reactor was designed to test fuel assemblies for heavy water power reactors. It was operated for this purpose from march of 1962 until December of 1964. Four alternatives studied in detail include: (1) dismantlement, in which all radioactive and hazardous contaminants would be removed, the containment dome dismantled and the property restored to a condition similar to its original preconstruction state; (2) partial dismantlement and interim safe storage, where radioactive equipment except for the reactor vessel and steam generators would be removed, along with hazardous materials, and the building sealed with remote monitoring equipment in place to permit limited inspections at five-year intervals; (3) conversion for beneficial reuse, in which most radioactive equipment and hazardous materials would be removed and the containment building converted to another use such as a storage facility for radioactive materials, and (4) entombment, which involves removing hazardous materials, filling the below-ground structure with concrete, removing the containment dome and pouring a concrete cap on the tomb. Also considered was safe storage, but this approach, which has, in effect, been followed for the past 30 years, did not warrant detailed evaluation. The four other alternatives were evaluate, taking into account factors such as potential effects on the environment, risks, effectiveness, ease of implementation and cost. The preferred alternative was determined to be dismantlement. This approach is recommended because it ranks highest in the comparative analysis, would serve as the best prototype for the site reactor decommissioning program and would be most compatible with site property reuse plans for the future.

  1. Fast Breeder Reactor studies

    Energy Technology Data Exchange (ETDEWEB)

    Till, C.E.; Chang, Y.I.; Kittel, J.H.; Fauske, H.K.; Lineberry, M.J.; Stevenson, M.G.; Amundson, P.I.; Dance, K.D.

    1980-07-01

    This report is a compilation of Fast Breeder Reactor (FBR) resource documents prepared to provide the technical basis for the US contribution to the International Nuclear Fuel Cycle Evaluation. The eight separate parts deal with the alternative fast breeder reactor fuel cycles in terms of energy demand, resource base, technical potential and current status, safety, proliferation resistance, deployment, and nuclear safeguards. An Annex compares the cost of decommissioning light-water and fast breeder reactors. Separate abstracts are included for each of the parts.

  2. Reactor core and plant design concepts of the Canadian supercritical water-cooled reactor

    Energy Technology Data Exchange (ETDEWEB)

    Yetisir, M.; Gaudet, M.; Bailey, J.; Rhodes, D.; Guzonas, D.; Hamilton, H.; Haque, Z.; Pencer, J.; Sartipi, A. [Atomic Energy of Canada Limited, Chalk River, ON (Canada)

    2014-07-01

    Canada is developing a 1200 MWe supercritical water-cooled reactor (SCWR), which has evolved from the well-established pressure-tube type CANDU{sup 1} reactor. This SCWR reactor concept, which is often referred to as the Canadian SCWR, uses supercritical water as a coolant, has a low-pressure heavy water moderator and a direct cycle for power production. The reactor concept incorporates advanced safety features, such as passive emergency core cooling, long-term decay heat rejection to the environment and fuel melt prevention via passive moderator cooling. These features significantly reduce the core damage frequency beyond existing nuclear reactors. This paper presents a description of the Canadian SCWR core design concept, the integration of in-core and out-of-core components and the mechanical plant design concept. Supporting systems for reactor safety, reactor control and moderator cooling are also described. (author)

  3. Development of the Decommissioning Project Management System, DECOMMIS

    Energy Technology Data Exchange (ETDEWEB)

    Chung, U. S.; Park, J. H.; Lee, K. W.; Hwang, D. S.; Park, S. K.; Hwang, S. T.; Paik, S. T.; Choi, Y. D.; Chung, K. H.; Lee, K. I.; Hong, S. B

    2007-03-15

    At the Korea Atomic Energy Research Institute(KAERI), two projects for decommissioning of the research reactors and uranium conversion plant are carried out. The management of the projects can be defined as 'the decision of the changes of the decommissioning methodologies for the more efficient achievement of the project at an adequate time and to an improved method'. The correct decision comes from the experiences on the decommissioning project and the systematic experiences can be obtained from the good management of the decommissioning information. For this, a project management tool, DECOMMIS, was developed in the D and D Technology Division, which has the charge of the decommissioning projects at the KAERI, and its purpose was extended to following fields; generation of reports on the dismantling waste for WACID, record keeping for the next decommissioning projects of nuclear facilities, provision of fundamental data for the R and D of the decommissioning technologies.

  4. Is light water reactor technology sustainable?

    Energy Technology Data Exchange (ETDEWEB)

    Rothwell, G. [Stanford Univ., Dept. of Economics, CA (United States); Van der Zwaan, B. [Vrije Univ., Amsterdam, Inst. for Environmental Studies (Netherlands)

    2001-07-01

    This paper proposes criteria for determining ''intermediate sustainability'' over a 500-year horizon. We apply these criteria to Light Water Reactor (LWR) technology and the LWR industry. We conclude that LWR technology does not violate intermediate sustainability criteria for (1) environmental externalities, (2) worker and public health and safety, or (3) accidental radioactive release. However, it does not meet criteria to (1) efficiently use depleted uranium and (2) avoid uranium enrichment technologies that can lead to nuclear weapons proliferation. Finally, current and future global demand for LWR technology might be below the minimum needed to sustain the current global LWR industry. (author)

  5. Instrumentation and control strategies for an integral pressurized water reactor

    Directory of Open Access Journals (Sweden)

    Belle R. Upadhyaya

    2015-03-01

    Full Text Available Several vendors have recently been actively pursuing the development of integral pressurized water reactors (iPWRs that range in power levels from small to large reactors. Integral reactors have the features of minimum vessel penetrations, passive heat removal after reactor shutdown, and modular construction that allow fast plant integration and a secure fuel cycle. The features of an integral reactor limit the options for placing control and safety system instruments. The development of instrumentation and control (I&C strategies for a large 1,000 MWe iPWR is described. Reactor system modeling—which includes reactor core dynamics, primary heat exchanger, and the steam flashing drum—is an important part of I&C development and validation, and thereby consolidates the overall implementation for a large iPWR. The results of simulation models, control development, and instrumentation features illustrate the systematic approach that is applicable to integral light water reactors.

  6. Superheated Water-Cooled Small Modular Underwater Reactor Concept

    OpenAIRE

    Shirvan, Koroush; Kazimi, Mujid

    2016-01-01

    A novel fully passive small modular superheated water reactor (SWR) for underwater deployment is designed to produce 160 MWe with steam at 500ºC to increase the thermodynamic efficiency compared with standard light water reactors. The SWR design is based on a conceptual 400-MWe integral SWR using the internally and externally cooled annular fuel (IXAF). The coolant boils in the external channels throughout the core to approximately the same quality as a conventional boiling water reactor and ...

  7. Decommissioning at Trawsfynydd nuclear power station

    Energy Technology Data Exchange (ETDEWEB)

    Bindon, F.J.L.

    1997-01-01

    The Trawsfynndd nuclear power station in North Wales was formally closed on July 20th 1993 on economic grounds. Radiation effects in the steel pressure vessels of the two Magnox units required high cost modifications if the reactors were to continue operation. Defuelling of the reactors was completed by August 1995. The Deferred Safestore Strategy has been selected as the decommissioning option. This does not involve any significant active dismantling until about 135 years from shutdown. Three main aspects of the decommissioning are discussed. These are: public consultation which focussed on the socio-economic implications of the reduction in the workforce and the visual impact of the safestore building design which was reduced in height in response to public opinion; technical considerations relating to waste management and electrical plant decommissioning; the conversion of the reactor buildings to provide safe storage for activated and contaminated material for a long period yet requiring only minimal maintenance. (UK).

  8. Materials for high performance light water reactors

    Science.gov (United States)

    Ehrlich, K.; Konys, J.; Heikinheimo, L.

    2004-05-01

    A state-of-the-art study was performed to investigate the operational conditions for in-core and out-of-core materials in a high performance light water reactor (HPLWR) and to evaluate the potential of existing structural materials for application in fuel elements, core structures and out-of-core components. In the conventional parts of a HPLWR-plant the approved materials of supercritical fossil power plants (SCFPP) can be used for given temperatures (⩽600 °C) and pressures (≈250 bar). These are either commercial ferritic/martensitic or austenitic stainless steels. Taking the conditions of existing light water reactors (LWR) into account an assessment of potential cladding materials was made, based on existing creep-rupture data, an extensive analysis of the corrosion in conventional steam power plants and available information on material behaviour under irradiation. As a major result it is shown that for an assumed maximum temperature of 650 °C not only Ni-alloys, but also austenitic stainless steels can be used as cladding materials.

  9. Self-Sustaining Thorium Boiling Water Reactors

    Directory of Open Access Journals (Sweden)

    Ehud Greenspan

    2012-10-01

    Full Text Available A thorium-fueled water-cooled reactor core design approach that features a radially uniform composition of fuel rods in stationary fuel assembly and is fuel-self-sustaining is described. This core design concept is similar to the Reduced moderation Boiling Water Reactor (RBWR proposed by Hitachi to fit within an ABWR pressure vessel, with the following exceptions: use of thorium instead of depleted uranium for the fertile fuel; elimination of the internal blanket; and elimination of absorbers from the axial reflectors, while increasing the length of the fissile zone. The preliminary analysis indicates that it is feasible to design such cores to be fuel-self-sustaining and to have a comfortably low peak linear heat generation rate when operating at the nominal ABWR power level of nearly 4000 MWth. However, the void reactivity feedback tends to be too negative, making it difficult to have sufficient shutdown reactivity margin at cold zero power condition. An addition of a small amount of plutonium from LWR used nuclear fuel was found effective in reducing the magnitude of the negative void reactivity effect and enables attaining adequate shutdown reactivity margin; it also flattens the axial power distribution. The resulting design concept offers an efficient incineration of the LWR generated plutonium in addition to effective utilization of thorium. Additional R&D is required in order to arrive at a reliable practical and safe design.

  10. Environmentally assisted cracking in light water reactors

    Energy Technology Data Exchange (ETDEWEB)

    Chopra, O.K.; Chung, H.M.; Gruber, E.E. [and others

    1996-07-01

    This report summarizes work performed by Argonne National Laboratory on fatigue and environmentally assisted cracking (EAC) in light water reactors (LWRs) from April 1995 to December 1995. Topics that have been investigated include fatigue of carbon and low-alloy steel used in reactor piping and pressure vessels, EAC of Alloy 600 and 690, and irradiation-assisted stress corrosion cracking (IASCC) of Type 304 SS. Fatigue tests were conducted on ferritic steels in water that contained various concentrations of dissolved oxygen (DO) to determine whether a slow strain rate applied during different portions of a tensile-loading cycle are equally effective in decreasing fatigue life. Crack-growth-rate tests were conducted on compact-tension specimens from several heats of Alloys 600 and 690 in simulated LWR environments. Effects of fluoride-ion contamination on susceptibility to intergranular cracking of high- and commercial- purity Type 304 SS specimens from control-tensile tests at 288 degrees Centigrade. Microchemical changes in the specimens were studied by Auger electron spectroscopy and scanning electron microscopy to determine whether trace impurity elements may contribute to IASCC of these materials.

  11. NUCLEAR SUPERHEATER FOR BOILING WATER REACTOR

    Science.gov (United States)

    Holl, R.J.; Klecker, R.W.; Graham, C.B.

    1962-05-15

    A description is given of a boiling water reactor having a superheating region integral with the core. The core consists essentially of an annular boiling region surrounding an inner superheating region. Both regions contain fuel elements and are separated by a cylindrical wall, perforations being provided in the lower portion of the cylindrical wall to permit circulation of a common water moderator between the two regions. The superheater region comprises a plurality of tubular fuel assemblies through which the steam emanating from the boiling region passes to the steam outlet. Each superheater fuel assembly has an outer double-walled cylinder, the double walls being concentrically spaced and connected together at their upper ends but open at the bottom to provide for differential thermal expansion of the inner and outer walls. Gas is entrapped in the annulus between the walls which acts as an insulating space between the fissionable material inside and the moderator outside. (AEC)

  12. Undermoderated spectrum MOX core study. Supercritical pressure light water reactor

    Energy Technology Data Exchange (ETDEWEB)

    Oka, Yoshiaki; Kosizuka, Seiichi [Tokyo Univ., Tokai, Ibaraki (Japan). Nuclear Engineering Research Lab.

    1998-09-01

    The supercritical pressure light water cooling reactor is a nuclear reactor concept with the once through type and the direct cycle reactor cooled with supercritical pressure water. The cooling water controlled with the feed pump flows directly to the turbine and a recirculation is never done by the nuclear reactor of this type. Therefore, this system isn`t equipped with the recirculation system and the steam separator, the system becomes simple. As for this system, it is expected that the cost performance improves. Here, the outline of former study is described. (author)

  13. Fiscal years 1993 and 1994 decontamination and decommissioning activities photobriefing book for the Argonne National Laboratory-East Site, Technology Development Division, Decontamination and Decommissioning Projects Department

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-12-31

    This photobriefing book describes the ongoing decontamination and decommissioning projects at the Argonne National Laboratory (ANL)-East Site near Lemont, Illinois. The book is broken down into three sections: introduction, project descriptions, and summary. The introduction elates the history and mission of the Decontamination and Decommissioning (D and D) Projects Department at ANL-East. The second section describes the active ANL-East D and D projects, giving a project history and detailing fiscal year (FY) 1993 and FY 1994 accomplishments and FY 1995 goals. The final section summarizes the goals of the D and D Projects Department and the current program status. The D/D projects include the Experimental Boiling Water Reactor, Chicago Pile-5 Reactor, that cells, and plutonium gloveboxes. 73 figs.

  14. Steady-state leaching of tritiated water from silica gel

    DEFF Research Database (Denmark)

    Das, H.A.; Hou, Xiaolin

    2009-01-01

    Aqueous leaching of tritium from silica gel, loaded by absorption of water vapor, makes part of reactor de-commissioning. It is found to follow the formulation of steady-state diffusion.......Aqueous leaching of tritium from silica gel, loaded by absorption of water vapor, makes part of reactor de-commissioning. It is found to follow the formulation of steady-state diffusion....

  15. Commercial Light Water Reactor Tritium Extraction Facility

    Energy Technology Data Exchange (ETDEWEB)

    McHood, M D

    2000-10-12

    A geotechnical investigation program has been completed for the Commercial Light Water Reactor - Tritium Extraction Facility (CLWR-TEF) at the Savannah River Site (SRS). The program consisted of reviewing previous geotechnical and geologic data and reports, performing subsurface field exploration, field and laboratory testing, and geologic and engineering analyses. The purpose of this investigation was to characterize the subsurface conditions for the CLWR-TEF in terms of subsurface stratigraphy and engineering properties for design and to perform selected engineering analyses. The objectives of the evaluation were to establish site-specific geologic conditions, obtain representative engineering properties of the subsurface and potential fill materials, evaluate the lateral and vertical extent of any soft zones encountered, and perform engineering analyses for slope stability, bearing capacity and settlement, and liquefaction potential. In addition, provide general recommendations for construction and earthwork.

  16. Light water reactor lower head failure analysis

    Energy Technology Data Exchange (ETDEWEB)

    Rempe, J.L.; Chavez, S.A.; Thinnes, G.L. [EG and G Idaho, Inc., Idaho Falls, ID (United States)] [and others

    1993-10-01

    This document presents the results from a US Nuclear Regulatory Commission-sponsored research program to investigate the mode and timing of vessel lower head failure. Major objectives of the analysis were to identify plausible failure mechanisms and to develop a method for determining which failure mode would occur first in different light water reactor designs and accident conditions. Failure mechanisms, such as tube ejection, tube rupture, global vessel failure, and localized vessel creep rupture, were studied. Newly developed models and existing models were applied to predict which failure mechanism would occur first in various severe accident scenarios. So that a broader range of conditions could be considered simultaneously, calculations relied heavily on models with closed-form or simplified numerical solution techniques. Finite element techniques-were employed for analytical model verification and examining more detailed phenomena. High-temperature creep and tensile data were obtained for predicting vessel and penetration structural response.

  17. Radiation Protection at Light Water Reactors

    CERN Document Server

    Prince, Robert

    2012-01-01

    This book is aimed at Health Physicists wishing to gain a better understanding of the principles and practices associated with a light water reactor (LWR) radiation protection program. The role of key program elements is presented in sufficient detail to assist practicing radiation protection professionals in improving and strengthening their current program. Details related to daily operation and discipline areas vital to maintaining an effective LWR radiation protection program are presented. Programmatic areas and functions important in preventing, responding to, and minimizing radiological incidents and the importance of performing effective incident evaluations and investigations are described. Elements that are integral in ensuring continuous program improvements are emphasized throughout the text.

  18. Strategic Targeting of Light Water Reactors.

    Science.gov (United States)

    1982-03-01

    Effects of Nuclear Weapons. U.S. Department of Defense and U.S. Department of Energy, 1977. 15. Glasstone, Samuel and Walter H. Jordan . Nuclear Power and...0 ’Nhi Mi V ni M 10 NN -4 M2 0 M 0-42(N N Mi 𔃺 - i hi V 10M N (N M2𔃾 - 0 0 0’ 1 0 %r N -T0 m - q- 0 It 14 qTm 4T mi hi m’ 10m N m 02 m 0- m 0 m -i...AFIT/GNE/PF/8ZM- 7 4. TITLE (and Subtitle) S.’ T’ PE OF REPORT & PERIOD COVERED STRATEGIC TARGETING MS THESIS OF LIGUfl WATER REACTORS 6. PERFORMING OIG

  19. Decommissioning in western Europe; Kaernkraftsavveckling i Vaesteuropa

    Energy Technology Data Exchange (ETDEWEB)

    Lundqvist, K. [Castor arbetslivskonsulter AB, Stockholm (Sweden)

    1999-12-01

    This report gives an overview of the situation in Western Europe. The original aim was to focus on organisational and human issues with regard to nuclear reactor decommissioning, but very few articles were found. This is in sharp contrast to the substantial literature on technical issues. While most of the reports on decommissioning have a technical focus, several provide information on regulatory issues, strategies and 'state of the art'. The importance of the human and organizational perspective is however discovered, when reading between the lines of the technical publications, and especially when project managers summarize lessons learned. The results are to a large extent based on studies of articles and reports, mainly collected from the INIS database. Decommissioning of nuclear facilities started already in the sixties, but then mainly research and experimental facilities were concerned. Until now about 70 reactors have been shutdown world-wide. Over the years there have been plenty of conferences for exchanging experiences mostly about technical matters. Waste Management is a big issue. In the 2000s there will be a wave of decommissioning when an increasing amount of reactors will reach the end of their calculated lifetime (40 years, a figure now being challenged by both life-extension and pre-shutdown projects). Several reactors have been shut-down for economical reasons. Shutdown and decommissioning is however not identical. A long period of time can sometimes pass before an owner decides to decommission and dismantle a facility. The conditions will also differ depending on the strategy, 'immediate dismantling' or 'safe enclosure'. If immediate dismantling is chosen the site can reach 'green-field status' in less than ten years. 'Safe enclosure', however, seems to be the most common strategy. There are several pathways, but in general a safe store is constructed, enabling the active parts to remain in safe

  20. Radiation protection in connection with the decommissioning of nuclear plants

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1997-04-01

    This document presents the SSI preliminary views and position concerning the decommissioning of nuclear plants. To prevent the exposure of the decommissioning personnel and the general public to unacceptable levels of radiation and to protect the environment and future generations, it is SSI`s task to formulate and issue the necessary terms and regulations with which the reactor licensees must comply during the decommissioning work. The views and principles presented here are the basis of SSI`s continued work on guidelines and regulations for the decommissioning of nuclear plants.

  1. Introduction to reactor internal materials for pressurized water reactor

    Energy Technology Data Exchange (ETDEWEB)

    Ryu, Woo Suk; Hong, Joon Hwa; Jee, Se Hwan; Lee, Bong Sang; Kuk, Il Hyun [Korea Atomic Energy Research Institute, Taejon (Korea, Republic of)

    1994-06-01

    This report reviewed the R and D states of reactor internal materials in order to be a reference for researches and engineers who are concerning on localization of the materials in the field or laboratory. General structure of PWR internals and material specification for YGN 3 and 4 were reviewed. States-of-arts on R and D of stainless steel and Alloy X-750 were reviewed, and degradation mechanisms of the components were analyzed. In order to develop the good domestic materials for reactor internal, following studies would be carried out: microstructure, sensitization behavior, fatigue property, irradiation-induced stress corrosion cracking/radiation-induced segregation, radiation embrittlement. (Author) 7 refs., 14 figs., 5 tabs.,.

  2. Accidental safety analysis methodology development in decommission of the nuclear facility

    Energy Technology Data Exchange (ETDEWEB)

    Park, G. H.; Hwang, J. H.; Jae, M. S.; Seong, J. H.; Shin, S. H.; Cheong, S. J.; Pae, J. H.; Ang, G. R.; Lee, J. U. [Seoul National Univ., Seoul (Korea, Republic of)

    2002-03-15

    Decontamination and Decommissioning (D and D) of a nuclear reactor cost about 20% of construction expense and production of nuclear wastes during decommissioning makes environmental issues. Decommissioning of a nuclear reactor in Korea is in a just beginning stage, lacking clear standards and regulations for decommissioning. This work accident safety analysis in decommissioning of the nuclear facility can be a solid ground for the standards and regulations. For source term analysis for Kori-1 reactor vessel, MCNP/ORIGEN calculation methodology was applied. The activity of each important nuclide in the vessel was estimated at a time after 2008, the year Kori-1 plant is supposed to be decommissioned. And a methodology for risk analysis assessment in decommissioning was developed.

  3. Life cycle environmental impacts of decommissioning Magnox nuclear power plants in the UK

    OpenAIRE

    Wallbridge, Steve; Banford, Anthony; Azapagic, Adisa

    2013-01-01

    Purpose: Full life cycle assessment (LCA) impacts from decommissioning have rarely been assessed, largely because few sites have been decommissioned so that the impacts of decommissioning are currently uncertain. This paper presents the results of an LCA study of the ongoing decommissioning of the Magnox power plant at Trawsfynydd in the UK. These results have been used to estimate the potential environmental impacts for the whole UK Magnox fleet of 11 reactors that will have to be decommissi...

  4. Water inventory management in condenser pool of boiling water reactor

    Science.gov (United States)

    Gluntz, Douglas M.

    1996-01-01

    An improved system for managing the water inventory in the condenser pool of a boiling water reactor has means for raising the level of the upper surface of the condenser pool water without adding water to the isolation pool. A tank filled with water is installed in a chamber of the condenser pool. The water-filled tank contains one or more holes or openings at its lowermost periphery and is connected via piping and a passive-type valve (e.g., squib valve) to a high-pressure gas-charged pneumatic tank of appropriate volume. The valve is normally closed, but can be opened at an appropriate time following a loss-of-coolant accident. When the valve opens, high-pressure gas inside the pneumatic tank is released to flow passively through the piping to pressurize the interior of the water-filled tank. In so doing, the initial water contents of the tank are expelled through the openings, causing the water level in the condenser pool to rise. This increases the volume of water available to be boiled off by heat conducted from the passive containment cooling heat exchangers. 4 figs.

  5. Decontamination and decommissioning project for the nuclear facilities

    Energy Technology Data Exchange (ETDEWEB)

    Park, J. H.; Paik, S. T.; Park, S. W. (and others)

    2007-02-15

    The final goal of this project is to complete the decommissioning of the Korean Research Reactor no.1 and no. 2(KRR-1 and 2) and uranium conversion plant safely and successfully. The goal of this project in 2006 is to complete the decontamination of the inside reactor hall of the KRR-2 which will be operating as a temporary storage for the radioactive waste until the construction and operation of the national repository site. Also the decommissioning work of the KRR-1 and auxiliary facilities is being progress. As the compaction of decommissioning project is near at hand, a computer information system was developed for a systematically control and preserve a technical experience and decommissioning data for the future reuse. The nuclear facility decommissioning, which is the first challenge in Korea, is being closed to the final stages. We completed the decommissioning of all the bio-shielding concrete for KRR-2 in 2005 and carried out the decontamination and waste material grouping of the roof, wall and bottom of the reactor hall of the KRR-2. The decommissioning for nuclear facility were demanded the high technology, remote control equipment and radioactivity analysis. So developed equipment and experience will be applied at the decommissioning for new nuclear facility in the future.

  6. NMSS handbook for decommissioning fuel cycle and materials licensees

    Energy Technology Data Exchange (ETDEWEB)

    Orlando, D.A.; Hogg, R.C.; Ramsey, K.M. [and others

    1997-03-01

    The US Nuclear Regulatory Commission amended its regulations to set forth the technical and financial criteria for decommissioning licensed nuclear facilities. These regulations were further amended to establish additional recordkeeping requirements for decommissioning; to establish timeframes and schedules for the decommissioning; and to clarify that financial assurance requirements must be in place during operations and updated when licensed operations cease. Reviews of the Site Decommissioning Management Plan (SDMP) program found that, while the NRC staff was overseeing the decommissioning program at nuclear facilities in a manner that was protective of public health and safety, progress in decommissioning many sites was slow. As a result NRC determined that formal written procedures should be developed to facilitate the timely decommissioning of licensed nuclear facilities. This handbook was developed to aid NRC staff in achieving this goal. It is intended to be used as a reference document to, and in conjunction with, NRC Inspection Manual Chapter (IMC) 2605, ``Decommissioning Inspection Program for Fuel Cycle and Materials Licensees.`` The policies and procedures discussed in this handbook should be used by NRC staff overseeing the decommissioning program at licensed fuel cycle and materials sites; formerly licensed sites for which the licenses were terminated; sites involving source, special nuclear, or byproduct material subject to NRC regulation for which a license was never issued; and sites in the NRC`s SDMP program. NRC staff overseeing the decommissioning program at nuclear reactor facilities subject to regulation under 10 CFR Part 50 are not required to use the procedures discussed in this handbook.

  7. Environmentally assisted cracking in light water reactors.

    Energy Technology Data Exchange (ETDEWEB)

    Chopra, O. K.; Chung, H. M.; Clark, R. W.; Gruber, E. E.; Shack, W. J.; Soppet, W. K.; Strain, R. V.

    2007-11-06

    This report summarizes work performed by Argonne National Laboratory on fatigue and environmentally assisted cracking (EAC) in light water reactors (LWRs) from January to December 2002. Topics that have been investigated include: (a) environmental effects on fatigue crack initiation in carbon and low-alloy steels and austenitic stainless steels (SSs), (b) irradiation-assisted stress corrosion cracking (IASCC) of austenitic SSs in BWRs, (c) evaluation of causes and mechanisms of irradiation-assisted cracking of austenitic SS in PWRs, and (d) cracking in Ni-alloys and welds. A critical review of the ASME Code fatigue design margins and an assessment of the conservation in the current choice of design margins are presented. The existing fatigue {var_epsilon}-N data have been evaluated to define the effects of key material, loading, and environmental parameters on the fatigue lives of carbon and low-alloy steels and austenitic SSs. Experimental data are presented on the effects of surface roughness on fatigue crack initiation in these materials in air and LWR environments. Crack growth tests were performed in BWR environments on SSs irradiated to 0.9 and 2.0 x 10{sup 21} n x cm{sup -2}. The crack growth rates (CGRs) of the irradiated steels are a factor of {approx}5 higher than the disposition curve proposed in NUREG-0313 for thermally sensitized materials. The CGRs decreased by an order of magnitude in low-dissolved oxygen (DO) environments. Slow-strain-rate tensile (SSRT) tests were conducted in high-purity 289 C water on steels irradiated to {approx}3 dpa. The bulk S content correlated well with the susceptibility to intergranular SCC in 289 C water. The IASCC susceptibility of SSs that contain >0.003 wt. % S increased drastically. bend tests in inert environments at 23 C were conducted on broken pieces of SSRT specimens and on unirradiated specimens of the same materials after hydrogen charging. The results of the tests and a review of other data in the literature

  8. High pressure water abrasive suspension JET cutting - An innovative cutting technology for the dismantling of reactor core components

    Energy Technology Data Exchange (ETDEWEB)

    Kalwa, H. [VAK, Kahl (Germany); Schwarz, T. [RWE NUKEM Limited, B7 Windscale, Seascale, Cumbria CA20 1PF (United Kingdom)

    2003-07-01

    In the frame of decommissioning of nuclear facilities the dismantling of reactor pressure vessels and their internals represent one special challenge. Due to their high activation, associated high dose rate levels, and to some extent the complex geometry and high material thickness of the components, there are particular demands for dismantling techniques. The task is to safely and economically work in every respect and therefore employ techniques with a wide area of application. As a proven technique, RWE NUKEM offers High Pressure Water Abrasive Suspension Jet Cutting. High pressure Water Abrasive Suspension Jet cutting (WASJ), well established in non-nuclear applications, has now been upgraded to meet the demands of decommissioning in the nuclear industry. The application at the Nuclear Power Plant in Kahl (VAK) was one of the first industrial scale applications. Based on several tests and parametric studies, High Water Abrasive Suspension Jet Cutting was tested against other cutting technologies. Because the overall performance in terms of fast and easy cutting operations, ability for remote handling, production of secondary waste WASJ was chosen at VAK Kahl for the dismantling of the lower core shroud and the reactor pressure vessel itself. The dismantling of the core shroud and the reactor vessel took place in-situ (component in its built-in position) using the WASJ technology. As example of application the core shroud of VAK is given. The total mass of the VAK lower shroud was about 3 tons and the wall thickness varied from 30 to 135 mm. The shroud was cut into segments in its in-vessel position, each segment being 500 x 900 mm and having a mass of about 0.25 tons. Cutting was performed in such a way that the separated pieces could be loaded directly into standard waste containers. All secondary waste (abrasives and dross) was collected in two 200 liter drums and, after drying, the drums were sent directly to waste storage. Reactor Pressure Vessel of VAK

  9. Fast reactor cooled by supercritical light water

    Energy Technology Data Exchange (ETDEWEB)

    Ishiwatari, Yuki; Mukouhara, Tami; Koshizuka, Seiichi; Oka, Yoshiaki [Tokyo Univ., Nuclear Engineering Research Lab., Tokai, Ibaraki (Japan)

    2001-09-01

    This report introduces the result of a feasibility study of a fast reactor cooled by supercritical light water (SCFR) with once-through cooling system. It is characterized by (1) no need of steam separator, recirculation system, or steam generator, (2) 1/7 of core flow rate compared with BWR or PWR, (3) high temperature and high pressure permits small turbine and high efficiency exceeding 44%, (4) structure and operation of major components are already experienced by LWRs or thermal power plants. Modification such as reducing blanket fuels and increasing seed fuels are made to achieve highly economic utilization of Pu and high power (2 GWe). The following restrictions were satisfied. (1) Maximum linear heat rate 39 kW/m, (2) Maximum surface temperature of Inconel cladding 620degC, (3) Negative void reactivity coefficient, (4) Fast neutron irradiation rate at the inner surface of pressure vessel less than 2.0x10{sup 19} n/cm{sup 2}. Thus the high power density of 167 MW/m{sup 3} including blanket is thought to contributes economy. The high conversion is attained to be 0.99 Pu fission residual rate by the outer radius of fuel rod of 0.88 mm. The breeding of 1.034 by Pu fission residual rate can be achieved by using briquette (tube-in-shell) type fuel structure. (K. Tsuchihashi)

  10. Capital Cost: Pressurized Water Reactor Plant Volume 1

    Energy Technology Data Exchange (ETDEWEB)

    1977-06-01

    The investment cost study for the 1139-MW(e) pressurized water reactor (PWR) central station power plant consists of two volumes. This volume includes in addition to the foreword and summary, the plant description and the detailed cost estimate.

  11. Process for treating effluent from a supercritical water oxidation reactor

    Science.gov (United States)

    Barnes, Charles M.; Shapiro, Carolyn

    1997-01-01

    A method for treating a gaseous effluent from a supercritical water oxidation reactor containing entrained solids is provided comprising the steps of expanding the gas/solids effluent from a first to a second lower pressure at a temperature at which no liquid condenses; separating the solids from the gas effluent; neutralizing the effluent to remove any acid gases; condensing the effluent; and retaining the purified effluent to the supercritical water oxidation reactor.

  12. Advanced Computational Thermal Fluid Physics (CTFP) and Its Assessment for Light Water Reactors and Supercritical Reactors

    Energy Technology Data Exchange (ETDEWEB)

    D.M. McEligot; K. G. Condie; G. E. McCreery; H. M. McIlroy; R. J. Pink; L.E. Hochreiter; J.D. Jackson; R.H. Pletcher; B.L. Smith; P. Vukoslavcevic; J.M. Wallace; J.Y. Yoo; J.S. Lee; S.T. Ro; S.O. Park

    2005-10-01

    Background: The ultimate goal of the study is the improvement of predictive methods for safety analyses and design of Generation IV reactor systems such as supercritical water reactors (SCWR) for higher efficiency, improved performance and operation, design simplification, enhanced safety and reduced waste and cost. The objective of this Korean / US / laboratory / university collaboration of coupled fundamental computational and experimental studies is to develop the supporting knowledge needed for improved predictive techniques for use in the technology development of Generation IV reactor concepts and their passive safety systems. The present study emphasizes SCWR concepts in the Generation IV program.

  13. Core design analysis of the supercritical water fast reactor

    Energy Technology Data Exchange (ETDEWEB)

    Mori, M.

    2005-10-01

    Light Water Reactor technology is nowadays the most successful commercial application of fission reactors for the production of electricity. However, in the next years, nuclear industry will have to face new and demanding challenges. The need for sustainable and cheap sources of energy, the need for public acceptance, the need for even higher safety standards, the need to minimize waste production are only a few examples. It is for these very reasons that a few next generation nuclear reactor concepts were selected for extensive research and development. Super critical water cooled reactors are one of them. The use of a supercritical coolant would in fact allow for higher thermal efficiencies and a more compact plant design. As a matter of fact, steam generators, or steam separators and driers would not be needed thus, significantly reducing construction costs. Moreover, because of the high heat capacity of supercritical water, comparatively less coolant would be needed to refrigerate the reactor. Consequently, a water-cooled reactor with a fast neutron spectrum could potentially be designed: the SuperCritical water Fast Reactor. This system presents unique features combining well-known fast and light water reactor characteristics in one design (e.g. the tendency to a positive void reactivity coefficient together with Loss Of Coolant Accidents, as design basis). The core is in fact loaded with highly enriched Mixed Oxide fuel (average plutonium content of {approx}23%), and presents a peculiar and significant geometrical and material heterogeneity (use of radial and axial blankets, solid moderator layers, several enrichment zones). The safety analysis of this very complex core layout, the development of suitable tools of investigation, and the optimization of the void reactivity effect through core design, is the main objective of this work. (orig.)

  14. Decommissioning of DR 2. Final report

    Energy Technology Data Exchange (ETDEWEB)

    Strufe, N.

    2009-02-15

    This report describes the work of dismantling and demolishing reactor DR 2, the waste volumes generated, the health physical conditions and the clearance procedures used for removed elements and waste. Since the ultimate goal for the decommissioning project was not clearance of the building, but downgrading the radiological classification of the building with a view to converting it to further nuclear use, this report documents how the lower classification was achieved and the known occurrence of remaining activity. The report emphasises some of the deliberations made and describes the lessons learned through this decommissioning project. The report also intends to contribute towards the technical basis and experience basis for further decommissioning of the nuclear facilities in Denmark. (au)

  15. Pipeline Decommissioning Trial AWE Berkshire UK - 13619

    Energy Technology Data Exchange (ETDEWEB)

    Agnew, Kieran [AWE, Aldermaston, Reading, RG7 4PR (United Kingdom)

    2013-07-01

    This Paper details the implementation of a 'Decommissioning Trial' to assess the feasibility of decommissioning the redundant pipeline operated by AWE located in Berkshire UK. The paper also presents the tool box of decommissioning techniques that were developed during the decommissioning trial. Constructed in the 1950's and operated until 2005, AWE used a pipeline for the authorised discharge of treated effluent. Now redundant, the pipeline is under a care and surveillance regime awaiting decommissioning. The pipeline is some 18.5 km in length and extends from AWE site to the River Thames. Along its route the pipeline passes along and under several major roads, railway lines and rivers as well as travelling through woodland, agricultural land and residential areas. Currently under care and surveillance AWE is considering a number of options for decommissioning the pipeline. One option is to remove the pipeline. In order to assist option evaluation and assess the feasibility of removing the pipeline a decommissioning trial was undertaken and sections of the pipeline were removed within the AWE site. The objectives of the decommissioning trial were to: - Demonstrate to stakeholders that the pipeline can be removed safely, securely and cleanly - Develop a 'tool box' of methods that could be deployed to remove the pipeline - Replicate the conditions and environments encountered along the route of the pipeline The onsite trial was also designed to replicate the physical prevailing conditions and constraints encountered along the remainder of its route i.e. working along a narrow corridor, working in close proximity to roads, working in proximity to above ground and underground services (e.g. Gas, Water, Electricity). By undertaking the decommissioning trial AWE have successfully demonstrated the pipeline can be decommissioned in a safe, secure and clean manor and have developed a tool box of decommissioning techniques. The tool box of includes

  16. Light Water Reactor Sustainability Accomplishments Report

    Energy Technology Data Exchange (ETDEWEB)

    McCarthy, Kathryn A. [Idaho National Lab. (INL), Idaho Falls, ID (United States)

    2015-02-01

    Welcome to the 2014 Light Water Reactor Sustainability (LWRS) Program Accomplishments Report, covering research and development highlights from 2014. The LWRS Program is a U.S. Department of Energy research and development program to inform and support the long-term operation of our nation’s commercial nuclear power plants. The research uses the unique facilities and capabilities at the Department of Energy national laboratories in collaboration with industry, academia, and international partners. Extending the operating lifetimes of current plants is essential to supporting our nation’s base load energy infrastructure, as well as reaching the Administration’s goal of reducing greenhouse gas emissions to 80% below 1990 levels by the year 2050. The purpose of the LWRS Program is to provide technical results for plant owners to make informed decisions on long-term operation and subsequent license renewal, reducing the uncertainty, and therefore the risk, associated with those decisions. In January 2013, 104 nuclear power plants operated in 31 states. However, since then, five plants have been shut down (several due to economic reasons), with additional shutdowns under consideration. The LWRS Program aims to minimize the number of plants that are shut down, with R&D that supports long-term operation both directly (via data that is needed for subsequent license renewal), as well indirectly (with models and technology that provide economic benefits). The LWRS Program continues to work closely with the Electric Power Research Institute (EPRI) to ensure that the body of information needed to support SLR decisions and actions is available in a timely manner. This report covers selected highlights from the three research pathways in the LWRS Program: Materials Aging and Degradation, Risk-Informed Safety Margin Characterization, and Advanced Instrumentation, Information, and Control Systems Technologies, as well as a look-ahead at planned activities for 2015. If you

  17. Superheated Water-Cooled Small Modular Underwater Reactor Concept

    Directory of Open Access Journals (Sweden)

    Koroush Shirvan

    2016-12-01

    Full Text Available A novel fully passive small modular superheated water reactor (SWR for underwater deployment is designed to produce 160 MWe with steam at 500ºC to increase the thermodynamic efficiency compared with standard light water reactors. The SWR design is based on a conceptual 400-MWe integral SWR using the internally and externally cooled annular fuel (IXAF. The coolant boils in the external channels throughout the core to approximately the same quality as a conventional boiling water reactor and then the steam, instead of exiting the reactor pressure vessel, turns around and flows downward in the central channel of some IXAF fuel rods within each assembly and then flows upward through the rest of the IXAF pins in the assembly and exits the reactor pressure vessel as superheated steam. In this study, new cladding material to withstand high temperature steam in addition to the fuel mechanical and safety behavior is investigated. The steam temperature was found to depend on the thermal and mechanical characteristics of the fuel. The SWR showed a very different transient behavior compared with a boiling water reactor. The inter-play between the inner and outer channels of the IXAF was mainly beneficial except in the case of sudden reactivity insertion transients where additional control consideration is required.

  18. Assessment of the high performance light water reactor concept

    Energy Technology Data Exchange (ETDEWEB)

    Starflinger, J. [Univ. of Stuttgart, IKE, (Germany); Schulenberg, T. [Karlsruhe Inst. of Tech., Karlsruhe (Germany); Bittermann, D. [AREVA NP GmbH, Erlangen (Germany); Andreani, M. [Paul Scherrer Inst., Villigen (Switzerland); Maraczy, C. [AEKI-KFKI, Budapest (Hungary)

    2011-07-01

    From 2006-2010, the High Performance Light Water Reactor (HPLWR) was investigated within a European Funded project called HPLWR Phase 2. Operated at 25MPa with a heat-up rate in the core from 280{sup o}C to 500{sup o}C, this reactor concept provides a technological challenge in the fields of design, neutronics, thermal-hydraulics and heat transfer, materials, and safety. The assessment of the concept with respect to the goals of the technology roadmap for Generation IV Nuclear Reactors of the Generation IV International Forum shows that the HPLWR has a potential to fulfil the goals of economics, safety and proliferation resistance and physical protection. In terms of sustainability, the HPLWR with a thermal neutron spectrum investigated within this project, does not differ from existing Light Water Reactors in terms of usage of fuel and waste production. (author)

  19. Advanced reactor design study. Assessing nonbackfittable concepts for improving uranium utilization in light water reactors

    Energy Technology Data Exchange (ETDEWEB)

    Fleischman, R.M.; Goldsmith, S.; Newman, D.F.; Trapp, T.J.; Spinrad, B.I.

    1981-09-01

    The objective of the Advanced Reactor Design Study (ARDS) is to identify and evaluate nonbackfittable concepts for improving uranium utilization in light water reactors (LWRs). The results of this study provide a basis for selecting and demonstrating specific nonbackfittable concepts that have good potential for implementation. Lead responsibility for managing the study was assigned to the Pacific Northwest Laboratory (PNL). Nonbackfittable concepts for improving uranium utilization in LWRs on the once-through fuel cycle were selected separately for PWRs and BWRs due to basic differences in the way specific concepts apply to those plants. Nonbackfittable concepts are those that are too costly to incorporate in existing plants, and thus, could only be economically incorporated in new reactor designs or plants in very early stages of construction. Essential results of the Advanced Reactor Design Study are summarized.

  20. Nuclear safety in light water reactors severe accident phenomenology

    CERN Document Server

    Sehgal, Bal Raj

    2011-01-01

    This vital reference is the only one-stop resource on how to assess, prevent, and manage severe nuclear accidents in the light water reactors (LWRs) that pose the most risk to the public. LWRs are the predominant nuclear reactor in use around the world today, and they will continue to be the most frequently utilized in the near future. Therefore, accurate determination of the safety issues associated with such reactors is central to a consideration of the risks and benefits of nuclear power. This book emphasizes the prevention and management of severe accidents to teach nuclear professionals

  1. Decommissioning ALARA programs Cintichem decommissioning experience

    Energy Technology Data Exchange (ETDEWEB)

    Adler, J.J.; LaGuardia, T.S. [TLG Services, Inc., Bridgewater, CT (United States)

    1995-03-01

    The Cintichem facility, originally the Union Carbide Nuclear Company (UCNC) Research Center, consisted primarily of a 5MW pool type reactor linked via a four-foot-wide by twelve-foot-deep water-filled canal to a bank of five adjacent hot cells. Shortly after going into operations in the early 1960s, the facility`s operations expanded to provide various reactor-based products and services to a multitude of research, production, medical, and education groups. From 1968 through 1972, the facility developed a process of separating isotopes from mixed fission products generated by irradiating enriched Uranium target capsules. By the late 1970s, 20 to 30 capsules were being processed weekly, with about 200,000 curies being produced per week. Several isotopes such as Mo{sup 99}, I{sup 131}, and Xe{sup 133} were being extracted for medical use.

  2. CONSIDERATIONS FOR THE DEVELOPMENT OF A DEVICE FOR THE DECOMMISSIONING OF THE HORIZONTAL FUEL CHANNELS IN THECANDU 6 NUCLEAR REACTOR. PART 8 - PRESENTATION OF THE CUTTING AND EXTRACTING DEVICE

    Directory of Open Access Journals (Sweden)

    Constantin POPESCU

    2015-05-01

    Full Text Available This paper present a constructive solution proposed by the authors in order to achieve of a cutting and extracting device for the decommissioning of the horizontal fuel channels in the CANDU 6 nuclear reactor. One of the most important part of the decommissioning device is the Cutting and Extraction Device (CED which perform the dismantling, cutting and extraction of the fuel channel components. This flexible and modular device is designed to work inside the fuel channel. The main operations performed by the Cutting and Extraction Device (CED are dismantling and extraction of the channel closure plug and shield plug, cutting and extraction of the pressure tube. The Cutting and Extraction Device (CED consists of following modules: guiding-fixing module, traction modules, cutting module, guiding-extracting module and articulated elements for modules connecting. The guiding-fixing module is equipped with elastic guiding rollers and fixing claws in working position, the traction modules are provided with variable pitch rollers for allowing travel speed change through the fuel channel. The cutting module is positioned in the middle of the device and it is equipped with three roll knives for pressure tube cutting, having a system for cutting place video surveillance and pyrometers for cutting place monitoring temperature. The operations performed by the Cutting and Extraction Device (CED of fuel channel are as follows: unblock and extract the channel closure plug, unblock and extract the channel shield plug, block and cut the middle of the pressure tube, block and cut the end of the pressure tube, block and extract the half of pressure tube. The Cutting and Extraction Device (CED is fully automated, connected by wires to a Programmable Logic Controller (PLC and controlled from a Human Machine Interface (HMI. The design of the Cutting and Extraction Device (CED shall be achieved according to the particular features of the fuel channel components to be

  3. DECOMMISSIONING THE PHYSICS LABORATORY, BUILDING 777-10A, AT THE SAVANNAH RIVER SITE (SRS)

    Energy Technology Data Exchange (ETDEWEB)

    Musall, J; Cathy Sizemore, C

    2007-01-17

    SRS recently completed a four-year mission to decommission {approx}250 excess facilities. As part of that effort, SRS decommissioned a 48,000 ft{sup 2} laboratory that housed four low-power test reactors, formerly used by SRS to determine reactor physics. This paper describes and reviews the decommissioning, with a focus on component segmentation and handling (i.e. hazardous material removal, demolition, and waste handling). The paper is intended to be a resource for engineers, planners, and project managers who face similar decommissioning challenges.

  4. Pellet-Cladding Mechanical Interaction Failure Threshold for Reactivity Initiated Accidents for Pressurized Water Reactors and Boiling Water Reactors

    Energy Technology Data Exchange (ETDEWEB)

    Beyer, Carl E. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Geelhood, Kenneth J. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States)

    2013-06-01

    Pacific Northwest National Laboratory (PNNL) has been requested by the U.S. Nuclear Regulatory Commission to evaluate the reactivity initiated accident (RIA) tests that have recently been performed in the Nuclear Safety Research Reactor (NSRR) and CABRI (French research reactor) on uranium dioxide (UO2) and mixed uranium and plutonium dioxide (MOX) fuels, and to propose pellet-cladding mechanical interaction (PCMI) failure thresholds for RIA events. This report discusses how PNNL developed PCMI failure thresholds for RIA based on least squares (LSQ) regression fits to the RIA test data from cold-worked stress relief annealed (CWSRA) and recrystallized annealed (RXA) cladding alloys under pressurized water reactor (PWR) hot zero power (HZP) conditions and boiling water reactor (BWR) cold zero power (CZP) conditions.

  5. Integrity of the reactor coolant boundary of the European pressurized water reactor (EPR)

    Energy Technology Data Exchange (ETDEWEB)

    Goetsch, D.; Bieniussa, K.; Schulz, H.; Jalouneix, J.

    1997-04-01

    This paper is an abstract of the work performed in the frame of the development of the IPSN/GRS approach in view of the EPR conceptual safety features. EPR is a pressurized water reactor which will be based on the experience gained by utilities and designers in France and in Germany. The reactor coolant boundary of a PWR includes the reactor pressure vessel (RPV), those parts of the steam generators (SGs) which contain primary coolant, the pressurizer (PSR), the reactor coolant pumps (RCPs), the main coolant lines (MCLs) with their branches as well as the other connecting pipes and all branching pipes including the second isolation valves. The present work covering the integrity of the reactor coolant boundary is mainly restricted to the integrity of the main coolant lines (MCLs) and reflects the design requirements for the main components of the reactor coolant boundary. In the following the conceptual aspects, i.e. design, manufacture, construction and operation, will be assessed. A main aspect is the definition of break postulates regarding overall safety implications.

  6. Design of virtual SCADA simulation system for pressurized water reactor

    Science.gov (United States)

    Wijaksono, Umar; Abdullah, Ade Gafar; Hakim, Dadang Lukman

    2016-02-01

    The Virtual SCADA system is a software-based Human-Machine Interface that can visualize the process of a plant. This paper described the results of the virtual SCADA system design that aims to recognize the principle of the Nuclear Power Plant type Pressurized Water Reactor. This simulation uses technical data of the Nuclear Power Plant Unit Olkiluoto 3 in Finland. This device was developed using Wonderware Intouch, which is equipped with manual books for each component, animation links, alarm systems, real time and historical trending, and security system. The results showed that in general this device can demonstrate clearly the principles of energy flow and energy conversion processes in Pressurized Water Reactors. This virtual SCADA simulation system can be used as instructional media to recognize the principle of Pressurized Water Reactor.

  7. Design of virtual SCADA simulation system for pressurized water reactor

    Energy Technology Data Exchange (ETDEWEB)

    Wijaksono, Umar, E-mail: umar.wijaksono@student.upi.edu; Abdullah, Ade Gafar; Hakim, Dadang Lukman [Electrical Power System Research Group, Department of Electrical Engineering Education, Jl. Dr. Setiabudi No. 207 Bandung, Indonesia 40154 (Indonesia)

    2016-02-08

    The Virtual SCADA system is a software-based Human-Machine Interface that can visualize the process of a plant. This paper described the results of the virtual SCADA system design that aims to recognize the principle of the Nuclear Power Plant type Pressurized Water Reactor. This simulation uses technical data of the Nuclear Power Plant Unit Olkiluoto 3 in Finland. This device was developed using Wonderware Intouch, which is equipped with manual books for each component, animation links, alarm systems, real time and historical trending, and security system. The results showed that in general this device can demonstrate clearly the principles of energy flow and energy conversion processes in Pressurized Water Reactors. This virtual SCADA simulation system can be used as instructional media to recognize the principle of Pressurized Water Reactor.

  8. Novel Photocatalytic Reactor Development for Removal of Hydrocarbons from Water

    Directory of Open Access Journals (Sweden)

    Morgan Adams

    2008-01-01

    Full Text Available Hydrocarbons contamination of the marine environment generated by the offshore oil and gas industry is generated from a number of sources including oil contaminated drill cuttings and produced waters. The removal of hydrocarbons from both these sources is one of the most significant challenges facing this sector as it moves towards zero emissions. The application of a number of techniques which have been used to successfully destroy hydrocarbons in produced water and waste water effluents has previously been reported. This paper reports the application of semiconductor photocatalysis as a final polishing step for the removal of hydrocarbons from two waste effluent sources. Two reactor concepts were considered: a simple flat plate immobilised film unit, and a new rotating drum photocatalytic reactor. Both units proved to be effective in removing residual hydrocarbons from the effluent with the drum reactor reducing the hydrocarbon content by 90% under 10 minutes.

  9. Greater-than-Class C low-level radioactive waste characterization. Appendix A-3: Basis for greater-than-Class C low-level radioactive waste light water reactor projections

    Energy Technology Data Exchange (ETDEWEB)

    Mancini, A.; Tuite, P.; Tuite, K.; Woodberry, S.

    1994-09-01

    This study characterizes low-level radioactive waste types that may exceed Class C limits at light water reactors, estimates the amounts of waste generated, and estimates radionuclide content and distribution within the waste. Waste types that may exceed Class C limits include metal components that become activated during operations, process wastes such as cartridge filters and decontamination resins, and activated metals from decommissioning activities. Operating parameters and current management practices at operating plants are reviewed and used to estimate the amounts of low-level waste exceeding Class C limits that is generated per fuel cycle, including amounts of routinely generated activated metal components and process waste. Radionuclide content is calculated for specific activated metals components. Empirical data from actual low-level radioactive waste are used to estimate radionuclide content for process wastes. Volumes and activities are also estimated for decommissioning activated metals that exceed Class C limits. To estimate activation levels of decommissioning waste, six typical light water reactors are modeled and analyzed. This study does not consider concentration averaging.

  10. REFLECTOR CONTROL OF A BOILING-WATER REACTOR

    Science.gov (United States)

    Treshow, M.

    1962-05-22

    A line connecting the reactor with a spent steam condenser contains a valve set to open when the pressure in the reactor exceeds a predetermined value and an orifice on the upstream side of the valve. Another line connects the reflector with this line between the orifice and the valve. An excess steam pressure causes the valve to open and the flow of steam through the line draws water out of the reflector. Provision is also made for adding water to the reflector when the steam pressure drops. (AEC)

  11. Self-Sustaining Thorium Boiling Water Reactors

    Energy Technology Data Exchange (ETDEWEB)

    Greenspan, Ehud [Univ. of California, Berkeley, CA (United States); Gorman, Phillip M. [Univ. of California, Berkeley, CA (United States); Bogetic, Sandra [Univ. of California, Berkeley, CA (United States); Seifried, Jeffrey E. [Univ. of California, Berkeley, CA (United States); Zhang, Guanheng [Univ. of California, Berkeley, CA (United States); Varela, Christopher R. [Univ. of California, Berkeley, CA (United States); Fratoni, Massimiliano [Univ. of California, Berkeley, CA (United States); Vijic, Jasmina J. [Univ. of California, Berkeley, CA (United States); Downar, Thomas [Univ. of Michigan, Ann Arbor, MI (United States); Hall, Andrew [Univ. of Michigan, Ann Arbor, MI (United States); Ward, Andrew [Univ. of Michigan, Ann Arbor, MI (United States); Jarrett, Michael [Univ. of Michigan, Ann Arbor, MI (United States); Wysocki, Aaron [Univ. of Michigan, Ann Arbor, MI (United States); Xu, Yunlin [Univ. of Michigan, Ann Arbor, MI (United States); Kazimi, Mujid [Massachusetts Inst. of Technology (MIT), Cambridge, MA (United States); Shirvan, Koroush [Massachusetts Inst. of Technology (MIT), Cambridge, MA (United States); Mieloszyk, Alexander [Massachusetts Inst. of Technology (MIT), Cambridge, MA (United States); Todosow, Michael [Brookhaven National Lab. (BNL), Upton, NY (United States); Brown, Nicolas [Brookhaven National Lab. (BNL), Upton, NY (United States); Cheng, Lap [Brookhaven National Lab. (BNL), Upton, NY (United States)

    2015-03-15

    The primary objectives of this project are to: Perform a pre-conceptual design of a core for an alternative to the Hitachi proposed fuel-self- sustaining RBWR-AC, to be referred to as a RBWR-Th. The use of thorium fuel is expected to assure negative void coefficient of reactivity (versus positive of the RBWR-AC) and improve reactor safety; Perform a pre-conceptual design of an alternative core to the Hitachi proposed LWR TRU transmuting RBWR-TB2, to be referred to as the RBWR-TR. In addition to improved safety, use of thorium for the fertile fuel is expected to improve the TRU transmutation effectiveness; Compare the RBWR-Th and RBWR-TR performance against that of the Hitachi RBWR core designs and sodium cooled fast reactor counterparts - the ARR and ABR; and, Perform a viability assessment of the thorium-based RBWR design concepts to be identified along with their associated fuel cycle, a technology gap analysis, and a technology development roadmap. A description of the work performed and of the results obtained is provided in this Overview Report and, in more detail, in the Attachments. The major findings of the study are summarized.

  12. Longtime radionuclide monitoring in the vicinity of Salaspils nuclear reactor; Dauerhaftes Monitoring der Radionuklide in Umgebung von Salaspils Kernreaktor

    Energy Technology Data Exchange (ETDEWEB)

    Riekstina, D.; Berzins, J.; Krasta, T. [Latvia Univ. (Latvia). Inst. of Solid State Physics; Skrypnik, O.; Alksnis, J. [Latvia Univ. (Latvia). Inst. of Chemical Physics

    2016-07-01

    The research nuclear reactor in Salaspils was decommissioned in 1998. Now reactor is partially dismantled and its territory is used as a temporary storage of radioactivity contaminated materials and water. Environment radioactivity monitoring for presence of artificial radionuclides in the vicinity of Salaspils nuclear reactor is carried out since 1990. Data include Cs-137 concentration in soils, tritium concentration in ground water, as well as H-3, Cs-137, Co-60 concentration and gross beta-activity of reactors sewage and rainwater drainage. The systematic monitoring allowed to detect in December 2014 a leakage from the special wastewater basin and so to prevent a pollution of ground water outside reactors territory.

  13. Fuel Summary Report: Shippingport Light Water Breeder Reactor - Rev. 2

    Energy Technology Data Exchange (ETDEWEB)

    Olson, Gail Lynn; Mc Cardell, Richard Keith; Illum, Douglas Brent

    2002-09-01

    The Shippingport Light Water Breeder Reactor (LWBR) was developed by Bettis Atomic Power Laboratory to demonstrate the potential of a water-cooled, thorium oxide fuel cycle breeder reactor. The LWBR core operated from 1977-82 without major incident. The fuel and fuel components suffered minimal damage during operation, and the reactor testing was deemed successful. Extensive destructive and nondestructive postirradiation examinations confirmed that the fuel was in good condition with minimal amounts of cladding deformities and fuel pellet cracks. Fuel was placed in wet storage upon arrival at the Expended Core Facility, then dried and sent to the Idaho Nuclear Technology and Engineering Center for underground dry storage. It is likely that the fuel remains in good condition at its current underground dry storage location at the Idaho Nuclear Technology and Engineering Center. Reports show no indication of damage to the core associated with shipping, loading, or storage.

  14. Fuel assembly design study for a reactor with supercritical water

    Energy Technology Data Exchange (ETDEWEB)

    Hofmeister, J. [RWE Power AG, Huyssenallee 2, D-45128 Essen (Germany); Waata, C. [ANSYS Germany GmbH, Staudenfeldweg 12, D-83624 Otterfing (Germany); Starflinger, J. [Forschungszentrum Karlsruhe GmbH, Institute for Nuclear and Energy Technologies, P.O. Box 3640, D-76021 Karlsruhe (Germany); Schulenberg, T. [Forschungszentrum Karlsruhe GmbH, Institute for Nuclear and Energy Technologies, P.O. Box 3640, D-76021 Karlsruhe (Germany)]. E-mail: thomas.schulenberg@iket.fzk.de; Laurien, E. [University of Stuttgart, Institute for Nuclear Technology and Energy Systems (IKE), Pfaffenwaldring 31, D-70569 Stuttgart (Germany)

    2007-08-15

    The European concept of the High Performance Light Water Reactor (HPLWR) differs from current light water reactors in a higher system pressure beyond the critical point of water, as well as a higher heat-up of the coolant within the core and thus higher core outlet temperatures, leading to a significant increase in turbine power and thermal efficiency of the power plant. The motivation to develop a novel fuel assembly for the HPLWR is caused by the high variation of coolant density in the core by more than a factor of seven. A systematic design study shows that a square fuel assembly with two rows of fuel rods and a central moderator box is best to minimize the structural material, to optimize the moderator to fuel ratio and to reduce differences of fuel rod power. Using neutronic and thermal-hydraulic analyses, a detailed mechanical design of a fuel assembly of the HPLWR has been worked out. Moreover, concepts for the head piece, the foot piece, the steam plenum and the lower mixing plenum, including the lower core plate, have been developed to account for the individual flow paths of this reactor. These allow a leak-tight counter current flow of moderator water and coolant as well as uniform mixing of different mass flows. The assembly design concept can be used as a general key component for any advanced core design of this reactor.

  15. Light water reactor fuel response during reactivity initiated accident experiments

    Energy Technology Data Exchange (ETDEWEB)

    MacDonald, P. E.; McCardell, R. K.; Martinson, Z. R.; Seiffert, S. L.

    1979-01-01

    Experimental results from six recent Power Burst Facility (PBF) reactivity initiated accident (RIA) tests are compared with data from previous Special Power Excursion Reactor Test (SPERT), and Japanese Nuclear Safety Research Reactor (NSRR) tests. The RIA fuel behavior experimental program recently started in the PBF is being conducted with coolant conditions typical of hot-startup conditions in a commercial boiling water reactor. The SPERT and NSRR test programs investigated the behavior of single or small clusters of light water reactor (LWR) type fuel rods under approximate room temperature and atmospheric pressure conditions in capsules containing stagnant water. As observed in the SPERT and NSRR tests, energy deposition, and consequent enthalpy increase in the PBF test fuel, appears to be the single most important variable. However, the consequences of failure at boiling water hot-startup system conditions appear to be more severe than previously observed in either the stagnant capsule SPERT or NSRR tests. Metallographic examination of both previously unirradiated and irradiated PBF fuel rod cross sections revealed extensive variation in cladding wall thicknesses (involving considerable plastic flow) and fuel shattering along grain boundaries in both restructured and unrestructured fuel regions. Oxidation of the cladding resulted in fracture at the location of cladding thinning and disintegration of the rods during quench. In addition,swelling of the gaseous and potentially volatile fission products in previously irradiated fuel resulted in volume increases of up to 180% and blockage of the coolant channels within the flow shrouds surrounding the fuel rods.

  16. Risk management and decision rules for light water reactor

    Energy Technology Data Exchange (ETDEWEB)

    Griesmeyer, J. M.; Okrent, D.

    1981-01-01

    The process of developing and adopting safety objectives in quantitative terms can provide a basis for focusing societal decision making on the suitability of such objectives and upon questions of compliance with those objectives. A preliminary proposal for a light water reactor (LWR) risk management framework is presented as part of that process.

  17. Plant Control of the High Performance Light Water Reactor

    Energy Technology Data Exchange (ETDEWEB)

    Schlagenhaufer, Marc; Starflinger, J.; Schulenberg, T. [Institute for Nuclear and Energy Technologies, Forschungszentrum Karlsruhe GmbH, Hermann-von-Helmholtz-Platz 1, Eggenstein-Leopoldshafen, Baden-Wuertemberg 76344 (Germany)

    2009-06-15

    The latest design concept of the High Performance Light Water Reactor (HPLWR) includes a thermal core in which supercritical water at 25 MPa inlet pressure is heated up from 280 deg. C reactor inlet temperature to 500 deg. C core exit temperature in three steps with intermediate coolant mixing to minimize peak cladding temperatures of the fuel rods. A direct supercritical steam cycle of the HPLWR has been designed with high, intermediate and low pressure turbines with a single reheat to 441 deg. C at 4.04 MPa pressure. Three low pressure pre-heaters and four high pressure pre-heaters are foreseen to achieve the envisaged reactor inlet temperature of 280 deg. C at full load. A feedwater tank of 603 m{sup 3} at 0.55 MPa pressure serves as an accumulator for normal and accidental conditions. The steam cycle has been modelled with APROS, developed by VTT Finland, to provide thermodynamic data and cycle efficiency values under full load and part load operation conditions as well as the transient response to load changes. A plant control system has been designed in which the reactor inlet pressure is controlled by the turbine valve, the reactor power is controlled by the feedwater pumps while the life steam temperature is controlled by control rods, and the reheat temperature is controlled by the reheater valve. Neglecting the reactivity control, the core power can also be treated as input parameter such that the life steam temperature is directly controlled by the feedwater mass flow. The plant control can handle all loading and de-loading cycles including complete shut down. A constant pressure at reactor inlet is foreseen for all load cases. Peak temperatures of the fuel pins are checked with a simplified core model. Two shut down procedures starting at 50% load are presented. A reactor scram with turbine states the safe shut down of the whole plant. To avoid hard material temperature changes, a controlled shut down procedure is designed. The rotational speed of the

  18. Design of a decommissioning procedure requirement management of a nuclear facility based on requirement engineering

    Energy Technology Data Exchange (ETDEWEB)

    Park, Hee Seong; Park, Seung Kook; Jin, Hyung Gon; Hong, Yun Jeong; Choi, Jong Won [KAERI, Daejeon (Korea, Republic of)

    2016-05-15

    The decommissioning procedure requires management for a research reactor and a nuclear facility classified through a dismantling strategy, design and planning, decontamination and decommissioning activities, and dismantling management. After collecting a variety of documents such as the ordinance, regulatory requirements, technical requirements, and criteria, the requirements between groups are connected. Based on this, an environment allowing the relationship between the upper-most law to lower-most regulation guide and the technical requirements for dismantling activities to be traced was implemented. Legislation that should be complied with at the decommissioning strategy phase of the decommissioning procedure requirements management during the full-life cycle of the decommissioning was defined. To satisfy the defined legislation at the decommissioning strategy phase, technical requirements and criteria related to the design and planning, the decontamination and decommissioning activities, and the dismantling management were defined. After collecting materials such as the ordinance, regulatory requirements, technical requirements, and criteria related to the decommissioning procedure requirements management, the connectivity of the requirements between four groups was established. Because a database can be managed through a variety of regulatory requirements related to the decommissioning of a nuclear facility from the Nuclear Safety Act to Regulation Guide, the system can utilize the decommissioning plan required by the NSSC when dismantling the research reactor and nuclear power plant.

  19. Gas cool reactor operation in the UK. The present position

    Energy Technology Data Exchange (ETDEWEB)

    Marsden, B.J. [AEA Technology, Risley, Warrington, Cheshire (United Kingdom)

    1998-09-01

    During 1996 there was a major reorganisation of the UK Nuclear Industry. The Advanced Gas Cooled Reactors (AGRs) and Pressurised Water reactor (PWR) operated by Nuclear Electric and Scottish Nuclear was privatised under a new company called British Energy. The Magnox reactors are now operated by a public utility named Magnox Electric, which is currently being merged with British Nuclear Fuels (BNFL). The old UKAEA was split into two parts; a public company, which has maintained the name UKAEA that is responsible for managing all their nuclear liabilities and a technical/consultancy company which is privately owned under the name of AEA Technology. Most of the Magnox and AGRs have continued to operate well with high availability factors. Decommissioning programmes have continued to expand and decommissioning costs have reduced below predicted levels. The industry is maintaining its safety research programme on gas cooled reactors under the direction of the HSE

  20. The Consortium for Advanced Simulation of Light Water Reactors

    Energy Technology Data Exchange (ETDEWEB)

    Ronaldo Szilard; Hongbin Zhang; Doug Kothe; Paul Turinsky

    2011-10-01

    The Consortium for Advanced Simulation of Light Water Reactors (CASL) is a DOE Energy Innovation Hub for modeling and simulation of nuclear reactors. It brings together an exceptionally capable team from national labs, industry and academia that will apply existing modeling and simulation capabilities and develop advanced capabilities to create a usable environment for predictive simulation of light water reactors (LWRs). This environment, designated as the Virtual Environment for Reactor Applications (VERA), will incorporate science-based models, state-of-the-art numerical methods, modern computational science and engineering practices, and uncertainty quantification (UQ) and validation against data from operating pressurized water reactors (PWRs). It will couple state-of-the-art fuel performance, neutronics, thermal-hydraulics (T-H), and structural models with existing tools for systems and safety analysis and will be designed for implementation on both today's leadership-class computers and the advanced architecture platforms now under development by the DOE. CASL focuses on a set of challenge problems such as CRUD induced power shift and localized corrosion, grid-to-rod fretting fuel failures, pellet clad interaction, fuel assembly distortion, etc. that encompass the key phenomena limiting the performance of PWRs. It is expected that much of the capability developed will be applicable to other types of reactors. CASL's mission is to develop and apply modeling and simulation capabilities to address three critical areas of performance for nuclear power plants: (1) reduce capital and operating costs per unit energy by enabling power uprates and plant lifetime extension, (2) reduce nuclear waste volume generated by enabling higher fuel burnup, and (3) enhance nuclear safety by enabling high-fidelity predictive capability for component performance.

  1. Fuel Summary Report: Shippingport Light Water Breeder Reactor

    Energy Technology Data Exchange (ETDEWEB)

    Illum, D.B.; Olson, G.L.; McCardell, R.K.

    1999-01-01

    The Shippingport Light Water Breeder Reactor (LWBR) was a small water cooled, U-233/Th-232 cycle breeder reactor developed by the Pittsburgh Naval Reactors to improve utilization of the nation's nuclear fuel resources in light water reactors. The LWBR was operated at Shippingport Atomic Power Station (APS), which was a Department of Energy (DOE) (formerly Atomic Energy Commission)-owned reactor plant. Shippingport APS was the first large-scale, central-station nuclear power plant in the United States and the first plant of such size in the world operated solely to produce electric power. The Shippingport LWBR was operated successfully from 1977 to 1982 at the APS. During the five years of operation, the LWBR generated more than 29,000 effective full power hours (EFPH) of energy. After final shutdown, the 39 core modules of the LWBR were shipped to the Expended Core Facility (ECF) at Naval Reactors Facility at the Idaho National Engineering and Environmental Laboratory (INEEL). At ECF, 12 of the 39 modules were dismantled and about 1000 of more than 17,000 rods were removed from the modules of proof-of-breeding and fuel performance testing. Some of the removed rods were kept at ECF, some were sent to Argonne National Laboratory-West (ANL-W) in Idaho and some to ANL-East in Chicago for a variety of physical, chemical and radiological examinations. All rods and rod sections remaining after the experiments were shipped back to ECF, where modules and loose rods were repackaged in liners for dry storage. In a series of shipments, the liners were transported from ECF to Idaho Nuclear Technology Engineering Center (INTEC), formerly the Idaho Chemical Processing Plant (ICPP). The 47 liners containing the fully-rodded and partially-derodded core modules, the loose rods, and the rod scraps, are now stored in underground dry wells at CPP-749.

  2. 77 FR 3009 - Knowledge and Abilities Catalog for Nuclear Power Plant Operators: Advanced Boiling Water Reactors

    Science.gov (United States)

    2012-01-20

    ... From the Federal Register Online via the Government Publishing Office NUCLEAR REGULATORY COMMISSION Knowledge and Abilities Catalog for Nuclear Power Plant Operators: Advanced Boiling Water Reactors..., ``Knowledge and Abilities Catalog for Nuclear Power Plant Operators: Advanced Boiling Water Reactors.'' DATES...

  3. 76 FR 14437 - Economic Simplified Boiling Water Reactor Standard Design: GE Hitachi Nuclear Energy; Issuance of...

    Science.gov (United States)

    2011-03-16

    ... From the Federal Register Online via the Government Publishing Office ] NUCLEAR REGULATORY COMMISSION Economic Simplified Boiling Water Reactor Standard Design: GE Hitachi Nuclear Energy; Issuance of... GE Hitachi Nuclear Energy (GEH) for the economic simplified boiling water reactor (ESBWR) standard...

  4. Conceptual design of a large heavy water reactor for US siting

    Energy Technology Data Exchange (ETDEWEB)

    Shapiro, N L; Jesick, J F

    1979-09-01

    Information is presented concerning fuel management and safety and licensing assessment of the pressurized heavy water reactor; and commercial introduction of the pressurized heavy water reactor in the United States.

  5. Shippingport station decommissioning project ALARA Program

    Energy Technology Data Exchange (ETDEWEB)

    Crimi, F.P. [Lockheed Environmental Systems and Technology Co., Houston, TX (United States)

    1995-03-01

    Properly planned and implemented ALARA programs help to maintain nuclear worker radiation exposures {open_quotes}As Low As Reasonably Achievable.{close_quotes}. This paper describes the ALARA program developed and implemented for the decontamination and decommissioning (D&D) of the Shippingport Atomic Power Station. The elements required for a successful ALARA program are discussed along with examples of good ALARA practices. The Shippingport Atomic Power Station (SAPS) was the first commercial nuclear power plant to be built in the United States. It was located 35 miles northwest of Pittsburgh, PA on the south bank of the Ohio river. The reactor plant achieved initial criticality in December 1959. During its 25-year life, it produced 7.5 billion kilowatts of electricity. The SAPS was shut down in October 1982 and was the first large-scale U.S. nuclear power plant to be totally decommissioned and the site released for unrestricted use. The Decommission Project was estimated to take 1,007 man-rem of radiation exposure and $.98.3 million to complete. Physical decommissioning commenced in September 1985 and was completed in September 1989. The actual man-rem of exposure was 155. The project was completed 6 months ahead of schedule at a cost of $91.3 million.

  6. Experience Practices on Decontamination Activity in NPP Decommissioning

    Energy Technology Data Exchange (ETDEWEB)

    Yoon, Suk Bon; Kim, Jeongju; Sohn, Wook [Korea Hydro and Nuclear Power Co., Daejeon (Korea, Republic of)

    2016-10-15

    Decommissioning of a nuclear power plant (NPP) involves various technical and administrative activities for a utility to terminate its license, which allows the plant site to be released from the regulatory control (site release). Decontamination activity in NPP decommissioning is one of the main technical activities to be performed during the decommissioning. The decontamination at decommissioning sites is usually performed due to several reasons such as reducing personnel dose and disposal costs, and cleanup to meet license termination requirements by using physical or chemical removal techniques proven through the previous experience practices. This paper introduces the best and worst practices for the decontamination activities collected from the decommissioning operational experiences through the implementation of nuclear decommissioning projects around the world. Review of the experiences of decontamination shows that it is important to conduct an advanced planning for optimized implementation of decontamination taking into considering site specific conditions such as operating time, reactor type, system, and so on. Also, a review of newer decontamination methods is necessary to safely and economically decommission the nuclear facility.

  7. Standard Guide for Benchmark Testing of Light Water Reactor Calculations

    CERN Document Server

    American Society for Testing and Materials. Philadelphia

    2010-01-01

    1.1 This guide covers general approaches for benchmarking neutron transport calculations in light water reactor systems. A companion guide (Guide E2005) covers use of benchmark fields for testing neutron transport calculations and cross sections in well controlled environments. This guide covers experimental benchmarking of neutron fluence calculations (or calculations of other exposure parameters such as dpa) in more complex geometries relevant to reactor surveillance. Particular sections of the guide discuss: the use of well-characterized benchmark neutron fields to provide an indication of the accuracy of the calculational methods and nuclear data when applied to typical cases; and the use of plant specific measurements to indicate bias in individual plant calculations. Use of these two benchmark techniques will serve to limit plant-specific calculational uncertainty, and, when combined with analytical uncertainty estimates for the calculations, will provide uncertainty estimates for reactor fluences with ...

  8. Chooz A, First Pressurized Water Reactor to be Dismantled in France - 13445

    Energy Technology Data Exchange (ETDEWEB)

    Boucau, Joseph [Westinghouse Electric Company, 43 rue de l' Industrie, Nivelles (Belgium); Mirabella, C. [Westinghouse Electric France, Orsay (France); Nilsson, Lennart [Westinghouse Electric Sweden, Vaesteraas (Sweden); Kreitman, Paul J. [Westinghouse Electric Company, Lake Bluff, IL 60048 (United States); Obert, Estelle [EDF - DPI - CIDEN, Lyon (France)

    2013-07-01

    Nine commercial nuclear power plants have been permanently shut down in France to date, of which the Chooz A plant underwent an extensive decommissioning and dismantling program. Chooz Nuclear Power Station is located in the municipality of Chooz, Ardennes region, in the northeast part of France. Chooz B1 and B2 are 1,500 megawatt electric (MWe) pressurized water reactors (PWRs) currently in operation. Chooz A, a 305 MWe PWR implanted in two caves within a hill, began operations in 1967 and closed in 1991, and will now become the first PWR in France to be fully dismantled. EDF CIDEN (Engineering Center for Dismantling and Environment) has awarded Westinghouse a contract for the dismantling of its Chooz A reactor vessel (RV). The project began in January 2010. Westinghouse is leading the project in a consortium with Nuvia France. The project scope includes overall project management, conditioning of the reactor vessel (RV) head, RV and RV internals segmentation, reactor nozzle cutting for lifting the RV out of the pit and seal it afterwards, dismantling of the RV thermal insulation, ALARA (As Low As Reasonably Achievable) forecast to ensure acceptable doses for the personnel, complementary vacuum cleaner to catch the chips during the segmentation work, needs and facilities, waste characterization and packaging, civil work modifications, licensing documentation. The RV and RV internals will be segmented based on the mechanical cutting technology that Westinghouse applied successfully for more than 13 years. The segmentation activities cover the cutting and packaging plan, tooling design and qualification, personnel training and site implementation. Since Chooz A is located inside two caves, the project will involve waste transportation from the reactor cave through long galleries to the waste buffer area. The project will end after the entire dismantling work is completed, and the waste storage is outside the caves and ready to be shipped either to the ANDRA (French

  9. 77 FR 38339 - Dairyland Power Cooperative, La Crosse Boiling Water Reactor Exemption From Certain Security...

    Science.gov (United States)

    2012-06-27

    ... COMMISSION Dairyland Power Cooperative, La Crosse Boiling Water Reactor Exemption From Certain Security Requirements 1.0 Background The La Crosse Boiling Water Reactor (LACBWR) is owned and was operated by the..., which utilized a forced-circulation, direct-cycle boiling water reactor as its heat source. The plant is...

  10. 77 FR 36014 - Initial Test Program of Emergency Core Cooling Systems for Boiling-Water Reactors

    Science.gov (United States)

    2012-06-15

    ... COMMISSION Initial Test Program of Emergency Core Cooling Systems for Boiling-Water Reactors AGENCY: Nuclear...-1277, ``Initial Test Program of Emergency Core Cooling Systems for Boiling- Water Reactors.'' This... testing features of emergency core cooling systems (ECCSs) for boiling-water reactors (BWRs). DATES...

  11. Multi-Applications Small Light Water Reactor - NERI Final Report

    Energy Technology Data Exchange (ETDEWEB)

    S. Michale Modro; James E. Fisher; Kevan D. Weaver; Jose N. Reyes, Jr.; John T. Groome; Pierre Babka; Thomas M. Carlson

    2003-12-01

    The Multi-Application Small Light Water Reactor (MASLWR) project was conducted under the auspices of the Nuclear Energy Research Initiative (NERI) of the U.S. Department of Energy (DOE). The primary project objectives were to develop the conceptual design for a safe and economic small, natural circulation light water reactor, to address the economic and safety attributes of the concept, and to demonstrate the technical feasibility by testing in an integral test facility. This report presents the results of the project. After an initial exploratory and evolutionary process, as documented in the October 2000 report, the project focused on developing a modular reactor design that consists of a self-contained assembly with a reactor vessel, steam generators, and containment. These modular units would be manufactured at a single centralized facility, transported by rail, road, and/or ship, and installed as a series of self-contained units. This approach also allows for staged construction of an NPP and ''pull and replace'' refueling and maintenance during each five-year refueling cycle.

  12. Site decommissioning management plan

    Energy Technology Data Exchange (ETDEWEB)

    Fauver, D.N.; Austin, J.H.; Johnson, T.C.; Weber, M.F.; Cardile, F.P.; Martin, D.E.; Caniano, R.J.; Kinneman, J.D.

    1993-10-01

    The Nuclear Regulatory Commission (NRC) staff has identified 48 sites contaminated with radioactive material that require special attention to ensure timely decommissioning. While none of these sites represent an immediate threat to public health and safety they have contamination that exceeds existing NRC criteria for unrestricted use. All of these sites require some degree of remediation, and several involve regulatory issues that must be addressed by the Commission before they can be released for unrestricted use and the applicable licenses terminated. This report contains the NRC staff`s strategy for addressing the technical, legal, and policy issues affecting the timely decommissioning of the 48 sites and describes the status of decommissioning activities at the sites.

  13. Decontamination and decommissioning activities photobriefing book FY 1999

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2000-03-08

    The Chicago Pile 5 (CP-5) Reactor, the first reactor built on the Argonne National Laboratory-East site, followed a rich history that had begun in 1942 with Enrico Fermi's original pile built under the west stands at the Stagg Field Stadium of The University of Chicago. CP-5 was a 5-megawatt, heavy water-moderated, enriched uranium-fueled reactor used to produce neutrons for scientific research from 1954--79. The reactor was shut down and defueled in 1979, and placed into a lay-up condition pending funding for decontamination and decommissioning (D and D). In 1990, work was initiated on the D and D of the facility in order to alleviate safety and environmental concerns associated with the site due to the deterioration of the building and its associated support systems. A decision was made in early Fiscal Year (FY) 1999 to direct focus and resources to the completion of the CP-5 Reactor D and D Project. An award of contract was made in December 1998 to Duke Engineering and Services (Marlborough, MA), and a D and D crew was on site in March 1999 to begin work, The project is scheduled to be completed in July 2000. The Laboratory has determined that the building housing the CP-5 facility is surplus to the Laboratory's needs and will be a candidate for demolition. In addition to a photographic chronology of FY 1999 activities at the CP-5 Reactor D and D Project, brief descriptions of other FY 1999 activities and of projects planned for the future are provided in this photobriefing book.

  14. Design concept of the high performance light water reactor

    Energy Technology Data Exchange (ETDEWEB)

    Schulenberg, Thomas; Starflinger, Joerg [Forschungszentrum Karlsruhe GmbH Technik und Umwelt (Germany). Inst. for Nuclear and Energy Technologies; Bittermann, Dietmar [AREVA NP GmbH, Erlangen (Germany). NEP-G Process

    2009-04-15

    The 'High Performance Light Water Reactor' (HPLWR) is a Light Water Reactor operating with supercritical water as coolant. At a pressure of 25 MPa in the core, water is heated up from 280 to 500 C. For these conditions, the envisaged net plant efficiency is 43.5%. The core design concept is based on a so-called '3-pass-core' in which the coolant is heated up in three subsequent steps. After each step, the coolant is mixed avoiding hot streaks possibly leading to unacceptable wall temperatures. The design of such a core comprises fuel assemblies containing 40 fuel rods and an inner and outer box for a better neutron moderation. Nine of these are assembled to a cluster with common head- and foot piece. The coolant is mixed inside an upper and inside a lower mixing chamber and leaves the reactor pressure vessel through a co-axial pipe, which protects the vessel wall against too high temperatures. (orig.)

  15. Decommissioning Project of Bohunice A1 NPP

    Energy Technology Data Exchange (ETDEWEB)

    Stubna, M.; Pekar, A.; Moravek, J.; Spirko, M.

    2002-02-26

    The first (pilot) nuclear power plant A1 in the Slovak Republic, situated on Jaslovske Bohunice site (60 km from Bratislava) with the capacity of 143 MWel, was commissioned in 1972 and was running with interruptions till 1977. A KS 150 reactor (HWGCR) with natural uranium as fuel, D2O as moderator and gaseous CO2 as coolant was installed in the A1 plant. Outlet steam from primary reactor coolant system with the temperature of 410 C was led to 6 modules of steam generators and from there to turbine generators. Refueling was carried out on-line at plant full power. The first serious incident associated with refueling occurred in 1976 when a locking mechanism at a fuel assembly failed. The core was not damaged during that incident and following a reconstruction of the damaged technology channel, the plant continued in operation. However, serious problems were occurring with the integrity of steam generators (CO2 gas on primary side, water and steam on secondary side) when the plant had to be shut down frequently due to failures and subsequent repairs. The second serious accident occurred in 1977 when a fuel assembly was overheated with a subsequent release of D2O into gas cooling circuit due to a human failure in the course of replacement of a fuel assembly. Subsequent rapid increase in humidity of the primary system resulted in damages of fuel elements in the core and the primary system was contaminated by fission products. In-reactor structures had been damaged, too. Activity had penetrated also into certain parts of the secondary system via leaking steam generators. Radiation situation in the course of both events on the plant site and around it had been below the level of limits specified. Based on a technical and economical justification of the demanding character of equipment repairs for the restoration of plant operation, and also due to a decision made not to continue with further construction of gas cooled reactors in Czechoslovakia, a decision was made in

  16. Spiral-shaped reactor for water disinfection

    KAUST Repository

    Soukane, Sofiane

    2016-04-20

    Chlorine-based processes are still widely used for water disinfection. The disinfection process for municipal water consumption is usually carried out in large tanks, specifically designed to verify several hydraulic and disinfection criteria. The hydrodynamic behavior of contact tanks of different shapes, each with an approximate total volume of 50,000 m3, was analyzed by solving turbulent momentum transport equations with a computational fluid dynamics code, namely ANSYS fluent. Numerical experiments of a tracer pulse were performed for each design to generate flow through curves and investigate species residence time distribution for different inlet flow rates, ranging from 3 to 12 m3 s−1. A new nature-inspired Conch tank design whose shape follows an Archimedean spiral was then developed. The spiral design is shown to strongly outperform the other tanks’ designs for all the selected plug flow criteria with an enhancement in efficiency, less short circuiting, and an order of magnitude improvement in mixing and dispersion. Moreover, following the intensification philosophy, after 50% reduction in its size, the new design retains its properties and still gives far better results than the classical shapes.

  17. Dense Medium Plasma Water Purification Reactor (DMP WaPR) Project

    Data.gov (United States)

    National Aeronautics and Space Administration — The Dense Medium Plasma Water Purification Reactor offers significant improvements over existing water purification technologies used in Advanced Life Support...

  18. Status of the Decommissioning Project Management Information System Development of KAERI in 2015

    Energy Technology Data Exchange (ETDEWEB)

    Jin, Hyung Gon; Park, Seungkook; Park, Heeseong; Song, Chanho [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2015-10-15

    Various information systems have been developed and used at decommissioning sites for planning a project, record keeping for a post management and cost estimation. KAERI is the only one expert group which has decommissioning experiences and KAERI is trying to develop computer code to converge all the data which has been accumulated during KRR-1 and 2 and UCP (Uranium Conversion Plant) decommission. KRR-1 and KRR-2 are TRIGA MARK type of research reactor which were constructed worldwide. Hence, there are many chance to use decommissioning experiences and data when other TRIGA MARK type of research reactors start to decommission. KAERI DPMIS stands for Decommissioning Project Management Information System, which is aiming to re-use of data effectively. As a responsible leading group of Korean decommissioning research field, KAERI has been developing DPMIS application program, which is going to be an important mile stone of decommission industry in Korea. User friendly graphical interface and lots of actual data let people well understood on decommission planning. It is expected that continuous effort and funds will be delivered to this research.

  19. Fixed-biofilm reactors applied to waste water treatment and aquacultural water recirculating systems

    NARCIS (Netherlands)

    Bovendeur, J.

    1989-01-01

    Fixed-biofilm waste water treatment may be regarded as one of the oldest engineered biological waste water treatment methods. With the recent introduction of modern packing materials, this type of reactor has received a renewed impuls for implementation in a wide field of water treatment.

    In

  20. Advanced Water-Gas Shift Membrane Reactor

    Energy Technology Data Exchange (ETDEWEB)

    Sean Emerson; Thomas Vanderspurt; Susanne Opalka; Rakesh Radhakrishnan; Rhonda Willigan

    2009-01-07

    The overall objectives for this project were: (1) to identify a suitable PdCu tri-metallic alloy membrane with high stability and commercially relevant hydrogen permeation in the presence of trace amounts of carbon monoxide and sulfur; and (2) to identify and synthesize a water gas shift catalyst with a high operating life that is sulfur and chlorine tolerant at low concentrations of these impurities. This work successfully achieved the first project objective to identify a suitable PdCu tri-metallic alloy membrane composition, Pd{sub 0.47}Cu{sub 0.52}G5{sub 0.01}, that was selected based on atomistic and thermodynamic modeling alone. The second objective was partially successful in that catalysts were identified and evaluated that can withstand sulfur in high concentrations and at high pressures, but a long operating life was not achieved at the end of the project. From the limited durability testing it appears that the best catalyst, Pt-Re/Ce{sub 0.333}Zr{sub 0.333}E4{sub 0.333}O{sub 2}, is unable to maintain a long operating life at space velocities of 200,000 h{sup -1}. The reasons for the low durability do not appear to be related to the high concentrations of H{sub 2}S, but rather due to the high operating pressure and the influence the pressure has on the WGS reaction at this space velocity.

  1. Boiling water reactor radiation shielded Control Rod Drive Housing Supports

    Energy Technology Data Exchange (ETDEWEB)

    Baversten, B.; Linden, M.J. [ABB Combustion Engineering Nuclear Operations, Windsor, CT (United States)

    1995-03-01

    The Control Rod Drive (CRD) mechanisms are located in the area below the reactor vessel in a Boiling Water Reactor (BWR). Specifically, these CRDs are located between the bottom of the reactor vessel and above an interlocking structure of steel bars and rods, herein identified as CRD Housing Supports. The CRD Housing Supports are designed to limit the travel of a Control Rod and Control Rod Drive in the event that the CRD vessel attachement went to fail, allowing the CRD to be ejected from the vessel. By limiting the travel of the ejected CRD, the supports prevent a nuclear overpower excursion that could occur as a result of the ejected CRD. The Housing Support structure must be disassembled in order to remove CRDs for replacement or maintenance. The disassembly task can require a significant amount of outage time and personnel radiation exposure dependent on the number and location of the CRDs to be changed out. This paper presents a way to minimize personal radiation exposure through the re-design of the Housing Support structure. The following paragraphs also delineate a method of avoiding the awkward, manual, handling of the structure under the reactor vessel during a CRD change out.

  2. CONSIDERATIONS FOR THE DEVELOPMENT OF A DEVICE FOR THE DECOMMISSIONING OF THE HORIZONTAL FUEL CHANNELS IN THECANDU 6 NUCLEAR REACTOR. PART 11 - PRESENTATION OF THE CUTTING AND EXTRACTING DEVICE OPERATING

    Directory of Open Access Journals (Sweden)

    Constantin D. STANESCU

    2015-05-01

    Full Text Available This paper presents a constructive solution proposed by the authors in order to achieve of a cutting and extracting device for the decommissioning of the horizontal fuel channels in the CANDU 6 nuclear reactor. The Cutting and Extraction Device (CED performs the dismantling, cutting and extraction of the fuel channel components. It's a flexible and modular device, which is designed to work inside the fuel channel and has the following functions: moving with variable speed, temperature monitoring and video surveillance inside the pipe, unblock and extract the channel closure plug (from End Fitting - EF, unblock and extract the channel shield plug (from Lattice Tube - LT, block and cut the middle of the pressure tube, block and cut the end of the pressure tube, block and extract the half of pressure tube. The Cutting and Extraction Device (CED consists of following modules: guiding-fixing module, traction modules, cutting module, guiding-extracting module and flexible elements for modules connecting. The guiding-fixing module is equipped with elastic guiding rollers and fixing claws in working position, the traction modules are provided with variable pitch rollers for allowing variable travel speed through the fuel channel. The cutting module is positioned in the middle of the device and it is equipped with three knife rolls for pressure tube cutting, using a system for cutting place video surveillance and pyrometers for monitoring cutting place temperature. The Cutting and Extraction Device (CED is fully automated, connected by wires to a Programmable Logic Controller (PLC and controlled from a Human Machine Interface (HMI. The design of the Cutting and Extraction Device (CED shall be achieved according to the particular features of the fuel channel components to be dismantled and to ensure radiation protection of workers.

  3. 76 FR 61118 - Meeting of the ACRS Subcommittee on Advanced Boiling Water Reactor; Notice of Meeting

    Science.gov (United States)

    2011-10-03

    ... From the Federal Register Online via the Government Publishing Office NUCLEAR REGULATORY COMMISSION Advisory Committee on Reactor Safeguards (ACRS) Meeting of the ACRS Subcommittee on Advanced Boiling Water Reactor; Notice of Meeting The ACRS Subcommittee on Advanced Boiling Water Reactor (ABWR...

  4. Preliminary decommissioning study reports

    Energy Technology Data Exchange (ETDEWEB)

    Reed, W.R.

    1984-09-01

    The Old Hydrofracture Facility (OHF) is one of approximately 76 facilities currently managed by the Oak Ridge National Laboratory (ORNL) Surplus Facilities Management Program (SFMP). This program, as part of the Department of Energy (DOE) national SFMP, is responsible for the maintenance and surveillance and the final decommissioning of radioactively contaminated surplus ORNL facilities. A long-range planning effort is being conducted that will outline the scope and objectives of the ORNL program and establish decommissioning priorities based on health and safety concerns, budget constraints, and other progammatic constraints. IN support of this SFMP planning activity, preliminary engineering assessments are being conducted for each of the ORNL surplus facilities currently managed under the program. These efforts are designed to: (1) provide an initial assessment of the potential decommissioning alternatives, (2) choose a preferred alternative and provide a justification for that choice, and (3) provide a preliminary description of the decommissioning plan, including cost and schedule estimates. This report presents the results of the preliminary analysis for the OHF.

  5. Current status of decommissioning projects and their strategies in advanced countries

    Energy Technology Data Exchange (ETDEWEB)

    Chung, U. S.; Lee, K. W.; Hwang, D. S.; Park, S. K.; Hwang, S. T.; Paik, S. T.; Park, J. H.; Choi, Y. D.; Chung, K. H.; Lee, K. I.; Hong, S. B

    2007-06-15

    At the Korea Atomic Energy Research Institute(KAERI), two projects for decommissioning of the research reactors and uranium conversion plant are carried out. The number of nuclear facilities to be dismantled will be much increased in future and the decommissioning industries will be enlarged. Keeping pace with this increasing tendency, each country formulated their own strategies and regulation systems, and applied their own technologies. The international organizations such as the IAEA and the OECD/NEA also prepared standards in technologies and regulation upon decommissioning and recommended to adopt them to the decommissioning projects. These strategies and technologies are very different country by country due to the different site dependent conditions and it will not be reasonable to evaluate their merits and weakness. The world wide status of the decommissioning, highlighted on that of 5 countries of USA, UK, France, Germany and Japan because they are advanced counties in nuclear industries, are summarized and their site specific conditions are evaluated. The scopes of the evaluation are decommissioning strategies, licensing procedures and requirements focused on decommissioning plan, waste management, technology development and so on. The detailed decommissioning progresses of several typical example sites were introduced. The activities on decommissioning field of the international organization, increased according to the enlarged decommissioning industries, are also summarized.

  6. Reactor process water (PW) piping inspections, 1984--1990

    Energy Technology Data Exchange (ETDEWEB)

    Ehrhart, W.S.; Elder, J.B.; Sprayberry, R.E.; Vande Kamp, R.W.

    1990-12-31

    In July 1983, the NRC ordered the shutdown of five boiling water reactors (BWR`s) because of concerns about reliability of ultrasonic examination for detecting intergranular stress corrosion cracking (IGSCC). These concerns arose because of leaking piping at Niagara Mohawk`s Nine Mile Point which was attributed to IGSCC. The leaks were detected shortly after completion of ultrasonic examinations of the piping. At that time, the Dupont plant manager at Savannah River (SR) directed that investigations be performed to determine if similar problems could exist in SR reactors. Investigation determined that all conditions believed necessary for the initiation and propagation of IGSCC in austenitic stainless steel exist in SR reactor process water (PW) systems. Sensitized, high carbon, austenitic stainless steel, a high purity water system with high levels of dissolved oxygen, and the residual stresses associated with welding during construction combine to provide the necessary conditions. A periodic UT inspection program is now in place to monitor the condition of the reactor PW piping systems. The program is patterned after NRC NUREG 0313, i.e., welds are placed in categories based on their history. Welds in upgraded or replacement piping are examined on a standard schedule (at least every five years) while welds with evidence of IGSCC, evaluated as acceptable for service, are inspected at every extended outage (15 to 18 months). This includes all welds in PW systems three inches in diameter and above. Welds are replaced when MSCC exceeds the replacement criteria of more than twenty percent of pipe circumference of fifty percent of through-wall depth. In the future, we intend to perform flow sizing with automated UT techniques in addition to manual sizing to provide more information for comparison with future examinations.

  7. Reactor process water (PW) piping inspections, 1984--1990

    Energy Technology Data Exchange (ETDEWEB)

    Ehrhart, W.S.; Elder, J.B.; Sprayberry, R.E.; Vande Kamp, R.W.

    1990-01-01

    In July 1983, the NRC ordered the shutdown of five boiling water reactors (BWR's) because of concerns about reliability of ultrasonic examination for detecting intergranular stress corrosion cracking (IGSCC). These concerns arose because of leaking piping at Niagara Mohawk's Nine Mile Point which was attributed to IGSCC. The leaks were detected shortly after completion of ultrasonic examinations of the piping. At that time, the Dupont plant manager at Savannah River (SR) directed that investigations be performed to determine if similar problems could exist in SR reactors. Investigation determined that all conditions believed necessary for the initiation and propagation of IGSCC in austenitic stainless steel exist in SR reactor process water (PW) systems. Sensitized, high carbon, austenitic stainless steel, a high purity water system with high levels of dissolved oxygen, and the residual stresses associated with welding during construction combine to provide the necessary conditions. A periodic UT inspection program is now in place to monitor the condition of the reactor PW piping systems. The program is patterned after NRC NUREG 0313, i.e., welds are placed in categories based on their history. Welds in upgraded or replacement piping are examined on a standard schedule (at least every five years) while welds with evidence of IGSCC, evaluated as acceptable for service, are inspected at every extended outage (15 to 18 months). This includes all welds in PW systems three inches in diameter and above. Welds are replaced when MSCC exceeds the replacement criteria of more than twenty percent of pipe circumference of fifty percent of through-wall depth. In the future, we intend to perform flow sizing with automated UT techniques in addition to manual sizing to provide more information for comparison with future examinations.

  8. The Wuergassen decommissioning and dismantling project; Das Stillegungs- und Rueckbauprojekt Wuergassen

    Energy Technology Data Exchange (ETDEWEB)

    Schiffer, K.J.

    1996-12-31

    After detection of cracks in the core shroud and bad economic prognoses, the owner/operator of the Wuergassen reactor, PreussenElektra, decided for decommissioning and direct dismantling of the reactor station, also because experience has shown that the decommissioning work poses no problems in terms of technology, safety, and environmental protection. The licensing application documents for the first decommissioning phase describe the remaining operation and dismantling of some components. Detailed documentation is produced and presented to the supervisory authority in line with progressing decommissioning work, so that documentation is reduced to the necessary extent. Planning work for the second phase and decontrolling measurements at the UNS building are underway. The operational and the project organisation were tuned for the decommissioning phases. Evaluation of results of the first phase will show whether the approaches taken fulfill expectations, particularly with respect to economic efficiency. (orig.)

  9. DIRECT-CYCLE, BOILING-WATER NUCLEAR REACTOR

    Science.gov (United States)

    Harrer, J.M.; Fromm, L.W. Jr.; Kolba, V.M.

    1962-08-14

    A direct-cycle boiling-water nuclear reactor is described that employs a closed vessel and a plurality of fuel assemblies, each comprising an outer tube closed at its lower end, an inner tube, fuel rods in the space between the tubes and within the inner tube. A body of water lying within the pressure vessel and outside the fuel assemblies is converted to saturated steam, which enters each fuel assembly at the top and is converted to superheated steam in the fuel assembly while it is passing therethrough first downward through the space between the inner and outer tubes of the fuel assembly and then upward through the inner tube. (AEC)

  10. Water treatment process in the JEN-1 Research Reactors

    Energy Technology Data Exchange (ETDEWEB)

    Urgel, M.; Perez-Bustamante, J. A.; Batuecas, T.

    1965-07-01

    The main characteristics and requirements which must be met with by waters to be used for nuclear reactors were studied paying attention separately both to those used in primary and secondary circuits as well as to the purification systems to be employed in each case. The experiments carried out for the initial pretreatment of water and the ion-exchange de ionization processes including a number of systems consisting of separated and mixed beds loaded with a variety of different commercially available resins are described. (Author) 24 refs.

  11. Simulation of Water Gas Shift Zeolite Membrane Reactor

    Science.gov (United States)

    Makertiharta, I. G. B. N.; Rizki, Z.; Zunita, Megawati; Dharmawijaya, P. T.

    2017-07-01

    The search of alternative energy sources keeps growing from time to time. Various alternatives have been introduced to reduce the use of fossil fuel, including hydrogen. Many pathways can be used to produce hydrogen. Among all of those, the Water Gas Shift (WGS) reaction is the most common pathway to produce high purity hydrogen. The WGS technique faces a downstream processing challenge due to the removal hydrogen from the product stream itself since it contains a mixture of hydrogen, carbon dioxide and also the excess reactants. An integrated process using zeolite membrane reactor has been introduced to improve the performance of the process by selectively separate the hydrogen whilst boosting the conversion. Furthermore, the zeolite membrane reactor can be further improved via optimizing the process condition. This paper discusses the simulation of Zeolite Membrane Water Gas Shift Reactor (ZMWGSR) with variation of process condition to achieve an optimum performance. The simulation can be simulated into two consecutive mechanisms, the reaction prior to the permeation of gases through the zeolite membrane. This paper is focused on the optimization of the process parameters (e.g. temperature, initial concentration) and also membrane properties (e.g. pore size) to achieve an optimum product specification (concentration, purity).

  12. Study of Pu consumption in Advanced Light Water Reactors. Evaluation of GE Advanced Boiling Water Reactor plants

    Energy Technology Data Exchange (ETDEWEB)

    1993-05-13

    Timely disposal of the weapons plutonium is of paramount importance to permanently safeguarding this material. GE`s 1300 MWe Advanced Boiling Water Reactor (ABWR) has been designed to utilize fill] core loading of mixed uranium-plutonium oxide fuel. Because of its large core size, a single ABWR reactor is capable of disposing 100 metric tons of plutonium within 15 years of project inception in the spiking mode. The same amount of material could be disposed of in 25 years after the start of the project as spent fuel, again using a single reactor, while operating at 75 percent capacity factor. In either case, the design permits reuse of the stored spent fuel assemblies for electrical energy generation for the remaining life of the plant for another 40 years. Up to 40 percent of the initial plutonium can also be completely destroyed using ABWRS, without reprocessing, either by utilizing six ABWRs over 25 years or by expanding the disposition time to 60 years, the design life of the plants and using two ABWRS. More complete destruction would require the development and testing of a plutonium-base fuel with a non-fertile matrix for an ABWR or use of an Advanced Liquid Metal Reactor (ALMR). The ABWR, in addition, is fully capable of meeting the tritium target production goals with already developed target technology.

  13. Transactions of the nineteenth water reactor safety information meeting

    Energy Technology Data Exchange (ETDEWEB)

    Weiss, A.J. (comp.)

    1991-10-01

    This report contains summaries of papers on reactor safety research to be presented at the 19th Water Reactor Safety Information Meeting at the Bethesda Marriott Hotel in Bethesda, Maryland, October 28--30, 1991. The summaries briefly describe the programs and results of nuclear safety research sponsored by the Office of Nuclear Regulatory Research, USNRC. Summaries of invited papers concerning nuclear safety issues from US government laboratories, the electric utilities, the Electric Power Research Institute (EPRI), the nuclear industry, and from the governments and industry in Europe and Japan are also included. The summaries have been compiled in one report to provide a basis for meaningful discussion and information exchange during the course of the meeting, and are given in the order of their presentation in each session. The individual summaries have been cataloged separately.

  14. Non-linear analysis in Light Water Reactor design

    Energy Technology Data Exchange (ETDEWEB)

    Rashid, Y.R.; Sharabi, M.N.; Nickell, R.E.; Esztergar, E.P.; Jones, J.W.

    1980-03-01

    The results obtained from a scoping study sponsored by the US Department of Energy (DOE) under the Light Water Reactor (LWR) Safety Technology Program at Sandia National Laboratories are presented. Basically, this project calls for the examination of the hypothesis that the use of nonlinear analysis methods in the design of LWR systems and components of interest include such items as: the reactor vessel, vessel internals, nozzles and penetrations, component support structures, and containment structures. Piping systems are excluded because they are being addressed by a separate study. Essentially, the findings were that nonlinear analysis methods are beneficial to LWR design from a technical point of view. However, the costs needed to implement these methods are the roadblock to readily adopting them. In this sense, a cost-benefit type of analysis must be made on the various topics identified by these studies and priorities must be established. This document is the complete report by ANATECH International Corporation.

  15. Dominant accident sequences in Oconee-1 pressurized water reactor

    Energy Technology Data Exchange (ETDEWEB)

    Dearing, J F; Henninger, R J; Nassersharif, B

    1985-04-01

    A set of dominant accident sequences in the Oconee-1 pressurized water reactor was selected using probabilistic risk analysis methods. Because some accident scenarios were similar, a subset of four accident sequences was selected to be analyzed with the Transient Reactor Analysis Code (TRAC) to further our insights into similar types of accidents. The sequences selected were loss-of-feedwater, small-small break loss-of-coolant, loss-of-feedwater-initiated transient without scram, and interfacing systems loss-of-coolant accidents. The normal plant response and the impact of equipment availability and potential operator actions were also examined. Strategies were developed for operator actions not covered in existing emergency operator guidelines and were tested using TRAC simulations to evaluate their effectiveness in preventing core uncovery and maintaining core cooling.

  16. Steam-Reheat Option for Supercritical-Water-Cooled Reactors

    Science.gov (United States)

    Saltanov, Eugene

    SuperCritical-Water-cooled Reactors (SCWRs) are being developed as one of the Generation-IV nuclear-reactor concepts. Main objectives of the development are to increase thermal efficiency of a Nuclear Power Plant (NPP) and to decrease capital and operational costs. The first objective can be achieved by introducing nuclear steam reheat inside a reactor and utilizing regenerative feedwater heaters. The second objective can be achieved by designing a steam cycle that closely matches that of the mature supercritical fossil-fuelled power plants. The feasibility of these objectives is discussed. As a part of this discussion, heat-transfer calculations have been performed and analyzed for SuperCritical-Water (SCW) and SuperHeated-Steam (SHS) channels of the proposed reactor concept. In the calculations a uniform and three non-uniform Axial Heat Flux Profiles (AHFPs) were considered for six different fuels (UO2, ThO 2, MOX, UC2, UC, and UN) and at average and maximum channel power. Bulk-fluid, sheath, and fuel centerline temperatures as well as the Heat Transfer Coefficient (HTC) profiles were obtained along the fuel-channel length. The HTC values are within a range of 4.7--20 kW/m2·K and 9.7--10 kW/m2·K for the SCW and SHS channels respectively. The main conclusion is that while all the mentioned fuels may be used for the SHS channel, only UC2, UC, or UN are suitable for a SCW channel, because their fuel centerline temperatures are at least 1000°C below melting point, while that of UO2, ThO2 , and MOX may reach melting point.

  17. Materials Inventory Database for the Light Water Reactor Sustainability Program

    Energy Technology Data Exchange (ETDEWEB)

    Kazi Ahmed; Shannon M. Bragg-Sitton

    2013-08-01

    Scientific research involves the purchasing, processing, characterization, and fabrication of many sample materials. The history of such materials can become complicated over their lifetime – materials might be cut into pieces or moved to various storage locations, for example. A database with built-in functions to track these kinds of processes facilitates well-organized research. The Material Inventory Database Accounting System (MIDAS) is an easy-to-use tracking and reference system for such items. The Light Water Reactor Sustainability Program (LWRS), which seeks to advance the long-term reliability and productivity of existing nuclear reactors in the United States through multiple research pathways, proposed MIDAS as an efficient way to organize and track all items used in its research. The database software ensures traceability of all items used in research using built-in functions which can emulate actions on tracked items – fabrication, processing, splitting, and more – by performing operations on the data. MIDAS can recover and display the complete history of any item as a simple report. To ensure the database functions suitably for the organization of research, it was developed alongside a specific experiment to test accident tolerant nuclear fuel cladding under the LWRS Advanced Light Water Reactor Nuclear Fuels Pathway. MIDAS kept track of materials used in this experiment from receipt at the laboratory through all processes, test conduct and, ultimately, post-test analysis. By the end of this process, the database proved to be right tool for this program. The database software will help LWRS more efficiently conduct research experiments, from simple characterization tests to in-reactor experiments. Furthermore, MIDAS is a universal tool that any other research team could use to organize their material inventory.

  18. Candidate materials performance under Supercritical Water Reactor (SCWR) conditions

    Energy Technology Data Exchange (ETDEWEB)

    Toivonen, A.; Penttilae, S.; Rissanen, L. (VTT Technical Research Centre of Finland, Espoo (Finland))

    2010-05-15

    The High Performance Light Water Reactor (HPLWR) is working at super-critical pressure (25 MPa) and a core coolant temperature up to 500 deg C. As an evolutionary step this reactor type follows the development path of modern supercritical coal-fired plants. This paper reviews the results on performance of commercial candidate materials for in-core applications focusing on corrosion, stress corrosion cracking (SCC) and creep issues. General corrosion (oxidation) tests with an inlet oxygen concentration of 125-150 ppb have been performed on several iron and nickel alloys at 300 to 650 deg C and 25 MPa in supercritical water. Stress corrosion cracking (SCC) susceptibility of selected austenitic stainless steels and a high chromium ODS (Oxide Dispersion Strengthened) alloy were also studied in slow strain rate tests (SSRT) in supercritical water at 500 deg C and 650 deg C. Furthermore, constant load creep tests have been performed on selected austenitic steels at 500 deg C and 650 deg C in supercritical water (25 MPa, 1 ppm O{sub 2}) and in an inert atmosphere (He, pressure 1 atm). Based on the materials studies, the current candidate materials for the core internals are austenitic steels with sufficient oxidation and creep resistance up to 500-550 deg C. High chromium austenitic steels and ODS alloys steels are considered for the fuel rod cladding due to their oxidation resistance up to 650 deg C. However, problems with manufacturing and joining of ODS alloys need to be solved. Alloys with high nickel content were not considered for the SCC or creep studies because of the strong effect of Ni on neutronics of the reactor core (orig.)

  19. The Development of the Advanced Light Water Reactor in Korea - The Korean Next Generation Reactor -

    Energy Technology Data Exchange (ETDEWEB)

    Kim, H.G.; Park, Y.S.; Kim, B.S.; Cho, S.J. [Korea Electric Power Research Institute, Taejon (Korea)

    1999-07-01

    Korean next generation reactor (KNGR), which is to be designed as a standard evolutionary advanced light water reactor (ALWR) in Korea, has been developed from 1992 as one of long-term government projects. The major characteristics of the KNGR are as follows; KNGR is 2-loop PWR and its design lift time is 60 years. The CDF and the CFF will be much lower than 10{sup -5}/RY and 10{sup -6}/RY, respectively. For the design improvement, KNGR adopted inconel-690 as a steam generator tube material, four train ECCS, refueling water storage tank inside containment, and double cylindrical concrete containment. For more reliable and easier control, compact workstations have been adopted in the design of main control complex and digital I and C technology is used for protection, control, and monitoring. In addition, KNGR has some passive design features such as fluidic device in safety injection tank, passive secondary condensing system, and passive auto-catalytic hydrogen recombiner to enhance safety. (author). 4 refs., 4 figs.

  20. Decommissioning and dismantling of nuclear facilities. Experiences and perspectives. 3. new rev. ed.; Stilllegung und Rueckbau kerntechnischer Anlagen. Erfahrungen und Perspektiven

    Energy Technology Data Exchange (ETDEWEB)

    Thierfeldt, S.; Schartmann, F.

    2009-11-15

    The report on decommissioning and dismantling of German nuclear facilities includes nuclear power plants (Niederaichbach, Lingen, Greifswald, Rheinsberg, Gundremmingen-A, Kahl, Wuergassen, Stade, Obrigheim, Muehlheim-Kaerlich), test reactors, research reactors, and fuel cycle facilities. The following issues are discussed with respect to experiences and perspectives: waste management, legal frame work for the decommissioning of nuclear facilities, research funding and exchange of experiences, technologies for the dismantling of nuclear facilities, decommissioning challenges in an international context.

  1. Water cooled breeder program summary report (LWBR (Light Water Breeder Reactor) development program)

    Energy Technology Data Exchange (ETDEWEB)

    1987-10-01

    The purpose of the Department of Energy Water Cooled Breeder Program was to demonstrate pratical breeding in a uranium-233/thorium fueled core while producing electrical energy in a commercial water reactor generating station. A demonstration Light Water Breeder Reactor (LWBR) was successfully operated for more than 29,000 effective full power hours in the Shippingport Atomic Power Station. The reactor operated with an availability factor of 76% and had a gross electrical output of 2,128,943,470 kilowatt hours. Following operation, the expended core was examined and no evidence of any fuel element defects was found. Nondestructive assay of 524 fuel rods determined that 1.39 percent more fissile fuel was present at the end of core life than at the beginning, proving that breeding had occurred. This demonstrates the existence of a vast source of electrical energy using plentiful domestic thorium potentially capable of supplying the entire national need for many centuries. To build on the successful design and operation of the Shippingport Breeder Core and to provide the technology to implement this concept, several reactor designs of large breeders and prebreeders were developed for commercial-sized plants of 900--1000 Mw(e) net. This report summarizes the Water Cooled Breeder Program from its inception in 1965 to its completion in 1987. Four hundred thirty-six technical reports are referenced which document the work conducted as part of this program. This work demonstrated that the Light Water Breeder Reactor is a viable alternative as a PWR replacement in the next generation of nuclear reactors. This transition would only require a minimum of change in design and fabrication of the reactor and operation of the plant.

  2. Oak Ridge National Laboratory Support of Non-light Water Reactor Technologies: Capabilities Assessment for NRC Near-term Implementation Action Plans for Non-light Water Reactors

    Energy Technology Data Exchange (ETDEWEB)

    Belles, Randy [Oak Ridge National Lab. (ORNL), Oak Ridge, TN (United States); Jain, Prashant K. [Oak Ridge National Lab. (ORNL), Oak Ridge, TN (United States); Powers, Jeffrey J. [Oak Ridge National Lab. (ORNL), Oak Ridge, TN (United States)

    2017-04-01

    The Oak Ridge National Laboratory (ORNL) has a rich history of support for light water reactor (LWR) and non-LWR technologies. The ORNL history involves operation of 13 reactors at ORNL including the graphite reactor dating back to World War II, two aqueous homogeneous reactors, two molten salt reactors (MSRs), a fast-burst health physics reactor, and seven LWRs. Operation of the High Flux Isotope Reactor (HFIR) has been ongoing since 1965. Expertise exists amongst the ORNL staff to provide non-LWR training; support evaluation of non-LWR licensing and safety issues; perform modeling and simulation using advanced computational tools; run laboratory experiments using equipment such as the liquid salt component test facility; and perform in-depth fuel performance and thermal-hydraulic technology reviews using a vast suite of computer codes and tools. Summaries of this expertise are included in this paper.

  3. High Performance Fuel Desing for Next Generation Pressurized Water Reactors

    Energy Technology Data Exchange (ETDEWEB)

    Mujid S. Kazimi; Pavel Hejzlar

    2006-01-31

    The use of internally and externally cooled annular fule rods for high power density Pressurized Water Reactors is assessed. The assessment included steady state and transient thermal conditions, neutronic and fuel management requirements, mechanical vibration issues, fuel performance issues, fuel fabrication methods and econmic assessment. The investigation was donducted by a team from MIT, Westinghouse, Gamma Engineering, Framatome ANP, and AECL. The analyses led to the conclusion that raising the power density by 50% may be possible with this advanced fuel. Even at the 150% power level, the fuel temperature would be a few hundred degrees lower than the current fuel temperatre. Significant economic and safety advantages can be obtained by using this fuel in new reactors. Switching to this type of fuel for existing reactors would yield safety advantages, but the economic return is dependent on the duration of plant shutdown to accommodate higher power production. The main feasiblity issue for the high power performance appears to be the potential for uneven splitting of heat flux between the inner and outer fuel surfaces due to premature closure of the outer fuel-cladding gap. This could be overcome by using a very narrow gap for the inner fuel surface and/or the spraying of a crushable zirconium oxide film at the fuel pellet outer surface. An alternative fuel manufacturing approach using vobropacking was also investigated but appears to yield lower than desirable fuel density.

  4. Experiences with austenitic steels in boiling water reactors

    Energy Technology Data Exchange (ETDEWEB)

    Wachter, O. [Preussische Elektrizitaets-AG (Preussenelektra), Hannover (Germany); Bruemmer, G. [Hamburgische Electricitaets-Werke AG., Hamburg (Germany)

    1997-05-01

    Stabilized austenitic steels are susceptible to intergranular stress corrosion cracking (IGSCC) under boiling water reactor (BWR) conditions. This important finding for the German nuclear power station industry arises from the detection of cracks during the last 3 years in reactor hot water pipes made from titanium-stabilized steel AISI 321 in six BWRs and in reactor core components made from the niobium-stabilized steel AISI 347 in one BWR. All the observed cracks had a common feature: they had their origin in the chromium carbide precipitates at the grain boundaries and in the associated chromium-depleted region near the grain boundary. These microstructural features in the heat-affected zones of the hot water pipe weldments were caused by the heat input during deposition of the root bead. The TiC partially dissolved in the region near the fusion line and the released carbon reacted to form chromium-rich M{sub 23}C{sub 6}. Regarding the cracks found in the core shroud and the core grid plates, it was shown that a sensitizing heat treatment of rings taken from the same heat of steel could give rise to a microstructure susceptible to IGSCC in the region of a weldment. High carbon contents coupled with low stabilization ratios led to sensitization. Residual stresses developed during welding provided the significant contributions to the tensile stress necessary for IGSCC. With regard to the service medium, the influence of the electrochemical corrosion potential (ECP) was recognized as a dominant factor, together with the conductivity. The corrosion potential was mainly determined by the radiolytic formation of H{sub 2}O{sub 2}; with increasing distance from the core, the H{sub 2}O{sub 2} content decreased owing to catalytic decomposition. For the pipes the problem of IGSCC could be resolved by the use of optimized steel (lower carbon content with maximum allowable stabilization ratio).

  5. Catalytic membrane reactor for water and wastewater treatment

    Science.gov (United States)

    Heng, Samuel

    A double membrane reactor was fabricated and assessed for continuous treatment of water containing organic contaminants by ozonation. This innovative reactor consisted of a zeolite membrane prepared on the inner surface of a porous a-alumina support, which served as water selective extractor and active contactor, and a porous stainless membrane which was the ozone gas diffuser. The coupling of membrane separation and chemical oxidation was found to be highly beneficial to both processes. The total organic carbon (TOC) removal rate at the retentate was enhanced by up to 2.2 times, as compared to membrane ozonation. Simultaneously, clean water (membrane support, was shown to further enhance TOC degradation, permeated TOC concentration, permeate flux, and moreover, ozone yield. The achievements of this project included: (1) The development of a novel low-temperature zeolite membrane activation method that generates consistently high quality membranes (i.e. high reproducibility and fewer defects). (2) The demonstration that gamma-alumina and gamma-alumina supported catalysts do not have significant activity and that the TOC removal enhancement usually observed during catalytic ozonation was due primarily to the contribution of adsorption and metal leaching. Thermogravimetric analysis (TGA) and elemental analysis (EA) of the spent catalyst showed that, during catalytic ozonation, oxygenated by-products of increased adsorbability were concentrated onto the gamma-alumina contactor, and were subsequently degraded. (3) The development of a method for coating high surface area gamma-alumina layers onto the grains of zeolite membrane support used as the active membrane contactor.

  6. Spent fuel data base: commercial light water reactors. [PWR; BWR

    Energy Technology Data Exchange (ETDEWEB)

    Hauf, M.J.; Kniazewycz, B.G.

    1979-12-01

    As a consequence of this country's non-proliferation policy, the reprocessing of spent nuclear fuel has been delayed indefinitely. This has resulted in spent light water reactor (LWR) fuel being considered as a potential waste form for disposal. Since the Nuclear Regulatory Commission (NRC) is currently developing methodologies for use in the regulation of the management and disposal of high-level and transuranic wastes, a comprehensive data base describing LWR fuel technology must be compiled. This document provides that technology baseline and, as such, will support the development of those evaluation standards and criteria applicable to spent nuclear fuel.

  7. The radiochemistry of nuclear power plants with light water reactors

    Energy Technology Data Exchange (ETDEWEB)

    Neeb, K.H.

    1997-12-31

    In this book, radioactivity and the chemical reactions of radionuclides within the different areas of a nucler power plant are discussed. The text concentrates on commercially operated light water reactors which currently represent the greatest fraction by far of the world`s nuclear power capacity. This book is not only intended for experts working in the various fields of radiochemistry in nuclear power plants. It also provides an overview of the topics dealt with for the operators of nuclear power plants, for people working in design and development and safety-related areas, as well as for those working in licensing and supervision. (orig.)

  8. Advanced fuels for plutonium management in pressurized water reactors

    Science.gov (United States)

    Vasile, A.; Dufour, Ph; Golfier, H.; Grouiller, J. P.; Guillet, J. L.; Poinot, Ch; Youinou, G.; Zaetta, A.

    2003-06-01

    Several fuel concepts are under investigation at CEA with the aim of manage plutonium inventories in pressurized water reactors. This options range from the use of mature technologies like MOX adapted in the case of MOX-EUS (enriched uranium support) and COmbustible Recyclage A ILot (CORAIL) assemblies to more innovative technologies using IMF like DUPLEX and advanced plutonium assembly (APA). The plutonium burning performances reported to the electrical production go from 7 to 60 kg (TW h) -1. More detailed analysis covering economic, sustainability, reliability and safety aspects and their integration in the whole fuel cycle would allow identifying the best candidate.

  9. Reactor Physics Behavior of Transuranic-Bearing TRISO-Particle Fuel in a Pressurized Water Reactor

    Energy Technology Data Exchange (ETDEWEB)

    Michael A. Pope; R. Sonat Sen; Abderrafi M. Ougouag; Gilles Youinou; Brian Boer

    2012-04-01

    Calculations have been performed to assess the neutronic behavior of pins of Fully-Ceramic Micro-encapsulated (FCM) fuel in otherwise-conventional Pressurized Water Reactor (PWR) fuel pins. The FCM fuel contains transuranic (TRU)-only oxide fuel in tri-isotropic (TRISO) particles with the TRU loading coming from the spent fuel of a conventional LWR after 5 years of cooling. Use of the TRISO particle fuel would provide an additional barrier to fission product release in the event of cladding failure. Depletion calculations were performed to evaluate reactivity-limited burnup of the TRU-only FCM fuel. These calculations showed that due to relatively little space available for fuel, the achievable burnup with these pins alone is quite small. Various reactivity parameters were also evaluated at each burnup step including moderator temperature coefficient (MTC), Doppler, and soluble boron worth. These were compared to reference UO{sub 2} and MOX unit cells. The TRU-only FCM fuel exhibits degraded MTC and Doppler coefficients relative to UO{sub 2} and MOX. Also, the reactivity effects of coolant voiding suggest that the behavior of this fuel would be similar to a MOX fuel of very high plutonium fraction, which are known to have positive void reactivity. In general, loading of TRU-only FCM fuel into an assembly without significant quantities of uranium presents challenges to the reactor design. However, if such FCM fuel pins are included in a heterogeneous assembly alongside LEU fuel pins, the overall reactivity behavior would be dominated by the uranium pins while attractive TRU destruction performance levels in the TRU-only FCM fuel pins is. From this work, it is concluded that use of heterogeneous assemblies such as these appears feasible from a preliminary reactor physics standpoint.

  10. Experience from the decommissioning projects in Gundremmingen KRB a and VAK KAHL; Experience de declassement a Grundremmingen KRB et VAK KAHL

    Energy Technology Data Exchange (ETDEWEB)

    Eickelpasch, N.; Steiner, H.; Priesmeyer, U. [Kernkraftwerke Gundremmingen Betriebsgesellschaft mbH (Germany); Watzel, G.V.P. [RWE Energie AG, Essen (Germany)

    1996-12-31

    The Gundremmingen Unit A plant (KRB A, 250 MW{sub e} BWR) and the VAK plant represent the first generation of nuclear reactors in Germany. KRB A was the first commercial reactor in Germany and VAK (16 MW{sub e} BWR) was the pilot nuclear power plant, which had to serve mainly scientific purposes. KRB A is under dismantling since 1983, VAK since 1988. Although both plants are boiling water reactors, there are components, which are comparable with pressurised water reactors, too. Meanwhile a wide range of experience with respect to cutting techniques, decontamination procedures and activity measuring techniques is collected. Due to this we are convinced that the decommissioning of nuclear power plants can be performed with reasonable and predictable costs; without long waiting time for `safe enclosure`; with low radiation exposure and no impact on the environment and with low amount of radioactive waste. (authors) 9 refs.

  11. Implementation of multiple measures to improve reactor recirculation pump sealing performance in nuclear boiling water reactor service

    Energy Technology Data Exchange (ETDEWEB)

    Loenhout, Gerard van [Flowserve B.V., Etten-Leur (Netherlands). Nuclear Services and Solutions Engineering; Hurni, Juerg

    2014-07-01

    A modern reactor recirculation pump circulates a large volume of high temperature, very pure water from the reactor pressure vessel back to the core. A crucial technical problem with a recirculation pump, such as a mechanical seal indicating loss of sealing pressure, may result in a power station having to shut down for repair. The paper describes the sudden increase in stray current phenomenon leading to rapid and severe deterioration of the mechanical end face shaft seal in a reactor recirculation pump. This occurred after the installation of a variable frequency converter replacing the original motorgenerator set.

  12. DOE/NNSA perspective safeguard by design: GEN III/III+ light water reactors and beyond

    Energy Technology Data Exchange (ETDEWEB)

    Pan, Paul Y [Los Alamos National Laboratory

    2010-12-10

    An overview of key issues relevant to safeguards by design (SBD) for GEN III/IV nuclear reactors is provided. Lessons learned from construction of typical GEN III+ water reactors with respect to SBD are highlighted. Details of SBD for safeguards guidance development for GEN III/III+ light water reactors are developed and reported. This paper also identifies technical challenges to extend SBD including proliferation resistance methodologies to other GEN III/III+ reactors (except HWRs) and GEN IV reactors because of their immaturity in designs.

  13. Production test IP-750 raw water as a reactor coolant. Final report

    Energy Technology Data Exchange (ETDEWEB)

    Frymier, J.W.; Geier, R.G.

    1966-08-10

    Approximately ten years ago single-tube tests demonstrated the feasibility of using unfiltered river water as a reactor coolant from the standpoint of aluminum corrosion and film formation. However, some effluent activity penalty was indicated. Inasmuch as both current water plant operation and the characteristics of Columbia River water have changed, it was deemed appropriate to reinvestigate the use of partially treated water as a reactor coolant. This report summarizes the results of a half-reactor test carried out at F Reactor.

  14. Sustained Recycle in Light Water and Sodium-Cooled Reactors

    Energy Technology Data Exchange (ETDEWEB)

    Steven J. Piet; Samuel E. Bays; Michael A. Pope; Gilles J. Youinou

    2010-11-01

    From a physics standpoint, it is feasible to sustain recycle of used fuel in either thermal or fast reactors. This paper examines multi-recycle potential performance by considering three recycling approaches and calculating several fuel cycle parameters, including heat, gamma, and neutron emission of fresh fuel; radiotoxicity of waste; and uranium utilization. The first recycle approach is homogeneous mixed oxide (MOX) fuel assemblies in a light water reactor (LWR). The transuranic portion of the MOX was varied among Pu, NpPu, NpPuAm, or all-TRU. (All-TRU means all isotopes through Cf-252.) The Pu case was allowed to go to 10% Pu in fresh fuel, but when the minor actinides were included, the transuranic enrichment was kept below 8% to satisfy the expected void reactivity constraint. The uranium portion of the MOX was enriched uranium. That enrichment was increased (to as much as 6.5%) to keep the fuel critical for a typical LWR irradiation. The second approach uses heterogeneous inert matrix fuel (IMF) assemblies in an LWR - a mix of IMF and traditional UOX pins. The uranium-free IMF fuel pins were Pu, NpPu, NpPuAm, or all-TRU. The UOX pins were limited to 4.95% U-235 enrichment. The number of IMF pins was set so that the amount of TRU in discharged fuel from recycle N (from both IMF and UOX pins) was made into the new IMF pins for recycle N+1. Up to 60 of the 264 pins in a fuel assembly were IMF. The assembly-average TRU content was 1-6%. The third approach uses fast reactor oxide fuel in a sodium-cooled fast reactor with transuranic conversion ratio of 0.50 and 1.00. The transuranic conversion ratio is the production of transuranics divided by destruction of transuranics. The FR at CR=0.50 is similar to the CR for the MOX case. The fast reactor cases had a transuranic content of 33-38%, higher than IMF or MOX.

  15. Thermal Hydraulic Integral Effect Tests for Pressurized Water Reactors

    Energy Technology Data Exchange (ETDEWEB)

    Baek, W. P.; Song, C. H.; Kim, Y. S. and others

    2005-02-15

    The objectives of the project are to construct a thermal-hydraulic integral effect test facility and to perform various integral effect tests for design, operation, and safety regulation of pressurized water reactors. During the first phase of this project (1997.8{approx}2002.3), the basic technology for thermal-hydraulic integral effect tests was established and the basic design of the test facility was accomplished: a full-height, 1/300-volume-scaled full pressure facility for APR1400, an evolutionary pressurized water reactor that was developed by Korean industry. Main objectives of the present phase (2002.4{approx}2005.2), was to optimize the facility design and to construct the experimental facility. We have performed following researches: 1) Optimization of the basic design of the thermal-hydraulic integral effect test facility for PWRs - ATLAS (Advanced Thermal-hydraulic Test Loop for Accident Simulation) - Reduced height design for APR1400 (+ specific design features of KSNP safety injection systems) - Thermal-hydraulic scaling based on three-level scaling methodology by Ishii et al. 2) Construction of the ATLAS facility - Detailed design of the test facility - Manufacturing and procurement of components - Installation of the facility 3) Development of supporting technology for integral effect tests - Development and application of advanced instrumentation technology - Preliminary analysis of test scenarios - Development of experimental procedures - Establishment and implementation of QA system/procedure.

  16. Reactor vessel water level estimation during severe accidents using cascaded fuzzy neural networks

    Energy Technology Data Exchange (ETDEWEB)

    Kim, Dong Yeong; Yoo, Kwae Hwan; Choi, Geon Pil; Back, Ju Hyun; Na, Man Gyun [Dept. of Nuclear Engineering, Chosun University, Gwangju (Korea, Republic of)

    2016-06-15

    Global concern and interest in the safety of nuclear power plants have increased considerably since the Fukushima accident. In the event of a severe accident, the reactor vessel water level cannot be measured. The reactor vessel water level has a direct impact on confirming the safety of reactor core cooling. However, in the event of a severe accident, it may be possible to estimate the reactor vessel water level by employing other information. The cascaded fuzzy neural network (CFNN) model can be used to estimate the reactor vessel water level through the process of repeatedly adding fuzzy neural networks. The developed CFNN model was found to be sufficiently accurate for estimating the reactor vessel water level when the sensor performance had deteriorated. Therefore, the developed CFNN model can help provide effective information to operators in the event of a severe accident.

  17. Decontamination and decommissioning activities photobriefing book FY 1998.

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1999-07-23

    Fiscal Year (FY) 1998 was very successful in terms of Decontamination and Decommissioning (D&D) project completions. This photobriefing book highlights these projects and activities in one ongoing project. Brief descriptions of projects planned for the future are also provided. Two D&D projects funded by the US DOE Office of Environmental Management (EM-40) were completed safely and on schedule in FY 1998: (1) Argonne Thermal Source Reactor (ATSR) was a low-power research reactor that operated from 1950 to 1989; and (2) The Building 594 (a.k.a. 579) Waste Ion-Exchange Facility was an obsolete facility constructed in the 1950s to process waste fluids from a collecting lagoon. Field work at one project was ongoing during FY 1998: (1) Chicago Pile 5 (CP-5) was a 5-megawatt, heavy water-moderated, enriched uranium-fueled reactor used to produce neutrons for scientific research from 1954-79. The reactor was shut down and defueled in 1979. D&D is scheduled to be completed in FY 2000. Project experience has lent itself to developing unique staff capabilities. The D&D group was chosen as lead organization for a project supported with operating funds provided by Argonne's Plant Facilities and Services (PFS) Division. This project was also completed safely and on schedule in FY 1998: (1) The Building 200/205 Pneumatic Transfer Tube was constructed in the late 1960s between Hot Cell M-4 in Building 200 and a glove box in Room F-131, Building 205, and used to transfer irradiated fuel specimens and other samples between the two buildings.

  18. Accident analysis of heavy water cooled thorium breeder reactor

    Science.gov (United States)

    Yulianti, Yanti; Su'ud, Zaki; Takaki, Naoyuki

    2015-04-01

    Thorium has lately attracted considerable attention because it is accumulating as a by-product of large scale rare earth mining. The objective of research is to analyze transient behavior of a heavy water cooled thorium breeder that is designed by Tokai University and Tokyo Institute of Technology. That is oxide fueled, PWR type reactor with heavy water as primary coolant. An example of the optimized core has relatively small moderator to fuel volume ratio (MFR) of 0.6 and the characteristics of the core are burn-up of 67 GWd/t, breeding ratio of 1.08, burn-up reactivity loss during cycles of fuel and claddings during accident are still below limitations which are in secure condition.

  19. The application of noble metals in light-water reactors

    Science.gov (United States)

    Kim, Young-Jin; Niedrach, Leonard W.; Indig, Maurice E.; Andresen, Peter L.

    1992-04-01

    Corrosion potential is a primary determinant of the stress-corrosion cracking susceptibility of structural materials in high-temperature water. Efforts to minimize stress-corrosion cracking in light-water reactors include adding hydrogen. In someplants' out-of-core regions, the hydrogen required to achieve the desired corrosion potential is relatively high. In-core, more hydrogen is needed for an equivalent reduction in corrosion potential. Additionally, sIDe effects of high hydrogen-addition rates, including increased 16N turbine shine and 60CO deposition, have also been observed in some cases. An approach involving noble-metal coatings on and alloying additions to engineering materials dramatically improves the efficiency with which the corrosion potential is decreased as a function of hydrogen addition, such that very low potentials are obtained once a stoichiometric concentration of hydrogen (versus oxygen) is achieved.

  20. New instrumentation of reactor water level for PWR; Nueva Instrumentacion de nivel de agua del reactor para PWR

    Energy Technology Data Exchange (ETDEWEB)

    Kaercher, S.

    2005-07-01

    Today, many PWR reactors are equipped with a reactor water level instrumentation system based on different measurement methods. Due to obsolescence issues, FRAMATOME ANP started to develop and quality a new water level measurement system using heated und unheated thermocouple measurements. the measuring principle is based on the fact that the heat transfer in water is considerably higher than in steam. The electronic cabinet for signal processing is based on a proven technology already developed, qualified and installed by FRAMATOME ANP in several NPPs. It is equipped with and advanced temperature measuring transducer for acquisition and processing of thermocouple signals. (Author)

  1. Light Water Reactor Sustainability Program Integrated Program Plan

    Energy Technology Data Exchange (ETDEWEB)

    Kathryn McCarthy; Jeremy Busby; Bruce Hallbert; Shannon Bragg-Sitton; Curtis Smith; Cathy Barnard

    2013-04-01

    Nuclear power has safely, reliably, and economically contributed almost 20% of electrical generation in the United States over the past two decades. It remains the single largest contributor (more than 70%) of non-greenhouse-gas-emitting electric power generation in the United States. Domestic demand for electrical energy is expected to experience a 31% growth from 2009 to 2035. At the same time, most of the currently operating nuclear power plants will begin reaching the end of their initial 20-year extension to their original 40-year operating license for a total of 60 years of operation. Figure E-1 shows projected nuclear energy contribution to the domestic generating capacity. If current operating nuclear power plants do not operate beyond 60 years, the total fraction of generated electrical energy from nuclear power will begin to decline—even with the expected addition of new nuclear generating capacity. The oldest commercial plants in the United States reached their 40th anniversary in 2009. The U.S. Department of Energy Office of Nuclear Energy’s Research and Development Roadmap (Nuclear Energy Roadmap) organizes its activities around four objectives that ensure nuclear energy remains a compelling and viable energy option for the United States. The four objectives are as follows: (1) develop technologies and other solutions that can improve the reliability, sustain the safety, and extend the life of the current reactors; (2) develop improvements in the affordability of new reactors to enable nuclear energy to help meet the Administration’s energy security and climate change goals; (3) develop sustainable nuclear fuel cycles; and (4) understand and minimize the risks of nuclear proliferation and terrorism. The Light Water Reactor Sustainability (LWRS) Program is the primary programmatic activity that addresses Objective 1. This document summarizes the LWRS Program’s plans.

  2. Light Water Reactor Sustainability Program Integrated Program Plan

    Energy Technology Data Exchange (ETDEWEB)

    McCarthy, Kathryn A. [Idaho National Lab. (INL), Idaho Falls, ID (United States); Busby, Jeremy [Oak Ridge National Lab. (ORNL), Oak Ridge, TN (United States); Hallbert, Bruce [Idaho National Lab. (INL), Idaho Falls, ID (United States); Bragg-Sitton, Shannon [Idaho National Lab. (INL), Idaho Falls, ID (United States); Smith, Curtis [Idaho National Lab. (INL), Idaho Falls, ID (United States); Barnard, Cathy [Idaho National Lab. (INL), Idaho Falls, ID (United States)

    2014-04-01

    Nuclear power has safely, reliably, and economically contributed almost 20% of electrical generation in the United States over the past two decades. It remains the single largest contributor (more than 70%) of non-greenhouse-gas-emitting electric power generation in the United States. Domestic demand for electrical energy is expected to experience a 31% growth from 2009 to 2035. At the same time, most of the currently operating nuclear power plants will begin reaching the end of their initial 20-year extension to their original 40-year operating license for a total of 60 years of operation. Figure E-1 shows projected nuclear energy contribution to the domestic generating capacity. If current operating nuclear power plants do not operate beyond 60 years, the total fraction of generated electrical energy from nuclear power will begin to decline—even with the expected addition of new nuclear generating capacity. The oldest commercial plants in the United States reached their 40th anniversary in 2009. The U.S. Department of Energy Office of Nuclear Energy’s Research and Development Roadmap (Nuclear Energy Roadmap) organizes its activities around four objectives that ensure nuclear energy remains a compelling and viable energy option for the United States. The four objectives are as follows: (1) develop technologies and other solutions that can improve the reliability, sustain the safety, and extend the life of the current reactors; (2) develop improvements in the affordability of new reactors to enable nuclear energy to help meet the Administration’s energy security and climate change goals; (3) develop sustainable nuclear fuel cycles; and (4) understand and minimize the risks of nuclear proliferation and terrorism. The Light Water Reactor Sustainability (LWRS) Program is the primary programmatic activity that addresses Objective 1. This document summarizes the LWRS Program’s plans.

  3. Light Water Reactor Sustainability Program Integrated Program Plan

    Energy Technology Data Exchange (ETDEWEB)

    George Griffith; Robert Youngblood; Jeremy Busby; Bruce Hallbert; Cathy Barnard; Kathryn McCarthy

    2012-01-01

    Nuclear power has safely, reliably, and economically contributed almost 20% of electrical generation in the United States over the past two decades. It remains the single largest contributor (more than 70%) of non-greenhouse-gas-emitting electric power generation in the United States. Domestic demand for electrical energy is expected to experience a 31% growth from 2009 to 2035. At the same time, most of the currently operating nuclear power plants will begin reaching the end of their initial 20-year extension to their original 40-year operating license for a total of 60 years of operation. Figure E-1 shows projected nuclear energy contribution to the domestic generating capacity. If current operating nuclear power plants do not operate beyond 60 years, the total fraction of generated electrical energy from nuclear power will begin to decline - even with the expected addition of new nuclear generating capacity. The oldest commercial plants in the United States reached their 40th anniversary in 2009. The U.S. Department of Energy Office of Nuclear Energy's Research and Development Roadmap (Nuclear Energy Roadmap) organizes its activities around four objectives that ensure nuclear energy remains a compelling and viable energy option for the United States. The four objectives are as follows: (1) develop technologies and other solutions that can improve the reliability, sustain the safety, and extend the life of the current reactors; (2) develop improvements in the affordability of new reactors to enable nuclear energy to help meet the Administration's energy security and climate change goals; (3) develop sustainable nuclear fuel cycles; and (4) understand and minimize the risks of nuclear proliferation and terrorism. The Light Water Reactor Sustainability (LWRS) Program is the primary programmatic activity that addresses Objective 1. This document summarizes the LWRS Program's plans.

  4. Workshop on decommissioning; Seminarium om avveckling

    Energy Technology Data Exchange (ETDEWEB)

    Broden, K. (ed.)

    2005-12-15

    A Nordic workshop on decommissioning of nuclear facilities was held at Risoe in Denmark September 13-15, 2005. The workshop was arranged by NKS in cooperation with the company Danish Decommissioning, DD, responsible for decommissioning of nuclear facilities at Risoe. Oral presentations were made within the following areas: International and national recommendations and requirements concerning decommissioning of nuclear facilities Authority experiences of decommissioning cases Decommissioning of nuclear facilities in Denmark Decommissioning of nuclear facilities in Sweden Plans for decommissioning of nuclear facilities in Norway Plans for decommissioning of nuclear facilities in Finland Decommissioning of nuclear facilities in German and the UK Decommissioning of nuclear facilities in the former Soviet Union Results from research and development A list with proposals for future work within NKS has been prepared based on results from group-work and discussions. The list contains strategic, economical and political issues, technical issues and issues regarding competence and communication. (au)

  5. Light Water Reactor Sustainability Program Reactor Safety Technologies Pathway Technical Program Plan

    Energy Technology Data Exchange (ETDEWEB)

    Corradini, M. L. [Univ. of Wisconsin, Madison, WI (United States); Peko, D. [US Dept. of Energy, Washington, DC (United States); Farmer, M. [Argonne National Lab. (ANL), Argonne, IL (United States); Rempe, J. [Rempe and Associates LLC, Idaho Falls, ID (United States); Humrickhouse, P. [Idaho National Lab. (INL), Idaho Falls, ID (United States); O' Brien, J. [Idaho National Lab. (INL), Idaho Falls, ID (United States); Robb, K. [Oak Ridge National Lab. (ORNL), Oak Ridge, TN (United States); Gauntt, R. [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States); Osborn, D. [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States)

    2016-06-01

    “end user” of the results from this DOE-sponsored work. The response to the Fukushima accident has been global, and there is a continuing multinational interest in collaborations to better quantify accident consequences and to incorporate lessons learned from the accident. DOE will continue to seek opportunities to facilitate collaborations that are of value to the U.S. industry, particularly where the collaboration provides access to vital data from the accident or otherwise supports or leverages other important R&D work. The purpose of the Reactor Safety Technology R&D is to improve understanding of beyond design basis events and reduce uncertainty in severe accident progression, phenomenology, and outcomes using existing analytical codes and information gleaned from severe accidents, in particular the Fukushima Daiichi events. This information will be used to aid in developing mitigating strategies and improving severe accident management guidelines for the current light water reactor fleet.

  6. Light Water Reactor Sustainability Program: Reactor Safety Technologies Pathway Technical Program Plan

    Energy Technology Data Exchange (ETDEWEB)

    Corradini, M. L. [Univ. of Wisconsin, Madison, WI (United States)

    2015-06-01

    “end user” of the results from this DOE-sponsored work. The response to the Fukushima accident has been global, and there is a continuing multinational interest in collaborations to better quantify accident consequences and to incorporate lessons learned from the accident. DOE will continue to seek opportunities to facilitate collaborations that are of value to the U.S. industry, particularly where the collaboration provides access to vital data from the accident or otherwise supports or leverages other important R&D work. The purpose of the Reactor Safety Technology R&D is to improve understanding of beyond design basis events and reduce uncertainty in severe accident progression, phenomenology, and outcomes using existing analytical codes and information gleaned from severe accidents, in particular the Fukushima Daiichi events. This information will be used to aid in developing mitigating strategies and improving severe accident management guidelines for the current light water reactor fleet.

  7. Stress analysis of the reactor pressure vessel of the high performance light water reactors (HPLWR); Festigkeitsanalyse fuer den Reaktordruckbehaelter des High Performance Light Water Reactor (HPLWR)

    Energy Technology Data Exchange (ETDEWEB)

    Guelton, E.; Fischer, K.

    2006-12-15

    The High Performance Light Water Reactor (HPLWR) is one of the concepts of the Generation IV program. The main difference compared to current Light Water Reactors (LWR) results from the supercritical steam condition of the coolant. Due to the supercritical pressure of 25 MPa, water, used as moderator and coolant, flows as a single phase through the core. The temperatures at the outlet are above 500 C. These conditions have a major impact on the design of the Reactor Pressure Vessel (RPV). For the modelling a RPV concept is proposed, which resembles the design of current LWR and allows the use of approved materials on one side and also meets the additional demands on the other side. A first dimensioning of the RPV wall thicknesses and the geometrical proportions has been performed using the german KTA-guidelines. To verify these results, a stress analysis using the finite element method has been performed with the program ANSYS. The combined mechanical and thermal calculations provide the primary, secondary and peak stresses which are evaluated using the KTA-guidelines design loading (Level 0) and service loading level A for the different components. The results confirm the wall thicknesses estimated by Fischer et al. (2006), but there are peak stresses in the vicinity of the inlet and outlet flanges, which are very close to the allowed design limit. For larger diameters of the RPV those regions will become critical and the stresses might exceed the design limits. Design optimizations for those regions are proposed and evaluated. A readjusted geometry of the inlet flange reduces those stresses by 65%. (orig.)

  8. Three core concepts for producing uranium-233 in commercial pressurized light water reactors for possible use in water-cooled breeder reactors

    Energy Technology Data Exchange (ETDEWEB)

    Conley, G.H.; Cowell, G.K.; Detrick, C.A.; Kusenko, J.; Johnson, E.G.; Dunyak, J.; Flanery, B.K.; Shinko, M.S.; Giffen, R.H.; Rampolla, D.S.

    1979-12-01

    Selected prebreeder core concepts are described which could be backfit into a reference light water reactor similar to current commercial reactors, and produce uranium-233 for use in water-cooled breeder reactors. The prebreeder concepts were selected on the basis of minimizing fuel system development and reactor changes required to permit a backfit. The fuel assemblies for the prebreeder core concepts discussed would occupy the same space envelope as those in the reference core but contain a 19 by 19 array of fuel rods instead of the reference 17 by 17 array. An instrument well and 28 guide tubes for control rods have been allocated to each prebreeder fuel assembly in a pattern similar to that for the reference fuel assemblies. Backfit of these prebreeder concepts into the reference reactor would require changes only to the upper core support structure while providing flexibility for alternatives in the type of fuel used.

  9. Benchmarking severe accident computer codes for heavy water reactor applications

    Energy Technology Data Exchange (ETDEWEB)

    Choi, J.H. [International Atomic Energy Agency, Vienna (Austria)

    2010-07-01

    Consideration of severe accidents at a nuclear power plant (NPP) is an essential component of the defence in depth approach used in nuclear safety. Severe accident analysis involves very complex physical phenomena that occur sequentially during various stages of accident progression. Computer codes are essential tools for understanding how the reactor and its containment might respond under severe accident conditions. International cooperative research programmes are established by the IAEA in areas that are of common interest to a number of Member States. These co-operative efforts are carried out through coordinated research projects (CRPs), typically 3 to 6 years in duration, and often involving experimental activities. Such CRPs allow a sharing of efforts on an international basis, foster team-building and benefit from the experience and expertise of researchers from all participating institutes. The IAEA is organizing a CRP on benchmarking severe accident computer codes for heavy water reactor (HWR) applications. The CRP scope includes defining the severe accident sequence and conducting benchmark analyses for HWRs, evaluating the capabilities of existing computer codes to predict important severe accident phenomena, and suggesting necessary code improvements and/or new experiments to reduce uncertainties. The CRP has been planned on the advice and with the support of the IAEA Nuclear Energy Department's Technical Working Groups on Advanced Technologies for HWRs. (author)

  10. Controlling radiation fields in siemans designed light water reactors

    Energy Technology Data Exchange (ETDEWEB)

    Riess, R.; Marchl, T. [Siemens Power Generation Group, Erlangen (Germany)

    1995-03-01

    An essential item for the control of radiation fields is the minimization of the use of satellites in the reactor systems of Light Water Reactors (LWRs). A short description of the qualification of Co-replacement materials will be followed by an illustration of the locations where these materials were implemented in Siemens designed LWRs. Especially experiences in PWRs show the immense influence of reduction of cobalt sources on dose rate buildup. The corrosion and the fatique and wear behavior of the replacement materials has not created concern up to now. A second tool to keep occupational radiation doses at a low level in PWRs is the use of the modified B/Li-chemistry. This is practized in Siemens designed plants by keeping the Li level at a max. value of 2 ppm until it reaches a pH (at 300{degrees}C) of {approximately}7.4. This pH is kept constant until the end of the cycle. The substitution of cobalt base alloys and thus the removal of the Co-59 sources from the system had the largest impact on the radiation levels. Nonetheless, the effectiveness of the coolant chemistry should not be neglected either. Several years of successful operation of PWRs with the replacement materials resulted in an occupational radiation exposure which is below 0.5 man-Sievert/plant and year.

  11. Technologies for Upgrading Light Water Reactor Outlet Temperature

    Energy Technology Data Exchange (ETDEWEB)

    Daniel S. Wendt; Piyush Sabharwall; Vivek Utgikar

    2013-07-01

    Nuclear energy could potentially be utilized in hybrid energy systems to produce synthetic fuels and feedstocks from indigenous carbon sources such as coal and biomass. First generation nuclear hybrid energy system (NHES) technology will most likely be based on conventional light water reactors (LWRs). However, these LWRs provide thermal energy at temperatures of approximately 300°C, while the desired temperatures for many chemical processes are much higher. In order to realize the benefits of nuclear hybrid energy systems with the current LWR reactor fleets, selection and development of a complimentary temperature upgrading technology is necessary. This paper provides an initial assessment of technologies that may be well suited toward LWR outlet temperature upgrading for powering elevated temperature industrial and chemical processes during periods of off-peak power demand. Chemical heat transformers (CHTs) are a technology with the potential to meet LWR temperature upgrading requirements for NHESs. CHTs utilize chemical heat of reaction to change the temperature at which selected heat sources supply or consume thermal energy. CHTs could directly utilize LWR heat output without intermediate mechanical or electrical power conversion operations and the associated thermodynamic losses. CHT thermal characteristics are determined by selection of the chemical working pair and operating conditions. This paper discusses the chemical working pairs applicable to LWR outlet temperature upgrading and the CHT operating conditions required for providing process heat in NHES applications.

  12. Stability analysis on natural circulation boiling water reactors

    Energy Technology Data Exchange (ETDEWEB)

    Metz, Peter

    1999-05-01

    The purpose of the study is a stability analysis of the simplified boiling water reactor concept. A fluid dynamics code, DYNOS, was developed and successfully validated against FRIGG and DESIRE data and a stability benchmark on the Ringhals 1 forced circulation BWR. Three simplified desings were considered in the analysis: The SWRIOOO by Siemens and the SBWR and ESBWR from the General Electric Co. For all three design operational characteristics, i.e. power versus flow rate maps, were calculated. The effects which different geometric and operational parameters, such as the riser height, inlet subcooling etc., have on the characteristics have been investigated. Dynamic simulations on the three simplified design revealed the geysering and the natural circulation oscillations modes only. They were, however, only encountered at pressure below 0.6 MPa. Stability maps for all tree simplified BWRs were calculated and plotted. The study concluded that a fast pressurisation of the reactor vessel is necessary to eliminate the possibility of geysering or natural circulation oscillations mode instability. (au) 26 tabs., 88 ills.

  13. Pressurized-water reactor internals aging degradation study. Phase 1

    Energy Technology Data Exchange (ETDEWEB)

    Luk, K.H. [Oak Ridge National Lab., TN (United States)

    1993-09-01

    This report documents the results of a Phase I study on the effects of aging degradations on pr internals. Primary stressers for internals an generated by the primary coolant flow in the they include unsteady hydrodynamic forces and pump-generated pressure pulsations. Other stressors are applied loads, manufacturing processes, impurities in the coolant and exposures to fast neutron fluxes. A survey of reported aging-related failure information indicates that fatigue, stress corrosion cracking (SCC) and mechanical wear are the three major aging-related degradation mechanisms for PWR internals. Significant reported failures include thermal shield flow-induced vibration problems, SCC in guide tube support pins and core support structure bolts, fatigue-induced core baffle water-jet impingement problems and excess wear in flux thimbles. Many of the reported problems have been resolved by accepted engineering practices. Uncertainties remain in the assessment of long-term neutron irradiation effects and environmental factors in high-cycle fatigue failures. Reactor internals are examined by visual inspections and the technique is access limited. Improved inspection methods, especially one with an early failure detection capability, can enhance the safety and efficiency of reactor operations.

  14. A study on the establishment of component/equipment performance criteria considering Heavy Water Reactor characteristics

    Energy Technology Data Exchange (ETDEWEB)

    Chang, Keun Sun; Kwon, Young Chul; Lee, Min Kyu; Lee, Yun Soo [Sunmoon Univ., Asan (Korea, Republic of); Chang, Seong Hoong; Ryo, Chang Hyun [Korea Advanced Institute of Science and Technology, Taejon (Korea, Republic of); Kim, Soong Pyung; Hwnag, Jung Rye; Chung, Chul Kee [Chosun Univ., Gwangju (Korea, Republic of)

    2002-03-15

    Foreign and domestic technology trends, regulatory requirements, design and researches for heavy water reactors are analyzed. Safety design guides of Canada industry and regulatory documents and consultative documents of Canada regulatory agency are reviewed. Applicability of MOST guidance 16 Revision 'guidance for technical criteria of nuclear reactor facility' is reviewed. Specific performance criteria are established for components and facilities for heavy water reactor.

  15. Application of CERREX software for KRR-1 Decommissioning Cost Estimation

    Energy Technology Data Exchange (ETDEWEB)

    Hong, Yunjeong; Park, Seungkook [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2016-10-15

    Main objectives of cost estimation is to indicate the costs required to complete the decommissioning project and to optimize the dismantling sequence and timing and then minimize the decommissioning total costs. There are three types of cost estimate; (i) Order of magnitude estimate, (ii) Budgetary estimate, (iii) Definitive estimate. Second of the theses types is applied to cost calculation in this paper. This was also applied to cost estimate part of preliminary decommissioning plan for Kijang construction approval. In this paper, the methodology and procedure for decommissioning costing using CERREX software were presented and cost estimation was performed and compared with actual decommissioning cost for KRR- 1(Korea Reactor Research, Unit 1). Cost estimation for KRR-1 was carried out applying to CERREX software. Table 1 shows the result values of the calculation. The currency was calculated as USD. Calculated cost is within the limit of 'Budgetary estimate' and the values is approximately $7,800,000. Labor costs are calculated based on manpower components per involved professions and hour rates per typical professions.

  16. Development of Safety Assessment Code for Decommissioning of Nuclear Facilities

    Science.gov (United States)

    Shimada, Taro; Ohshima, Soichiro; Sukegawa, Takenori

    A safety assessment code, DecDose, for decommissioning of nuclear facilities has been developed, based on the experiences of the decommissioning project of Japan Power Demonstration Reactor (JPDR) at Japan Atomic Energy Research Institute (currently JAEA). DecDose evaluates the annual exposure dose of the public and workers according to the progress of decommissioning, and also evaluates the public dose at accidental situations including fire and explosion. As for the public, both the internal and the external doses are calculated by considering inhalation, ingestion, direct radiation from radioactive aerosols and radioactive depositions, and skyshine radiation from waste containers. For external dose for workers, the dose rate from contaminated components and structures to be dismantled is calculated. Internal dose for workers is calculated by considering dismantling conditions, e.g. cutting speed, cutting length of the components and exhaust velocity. Estimation models for dose rate and staying time were verified by comparison with the actual external dose of workers which were acquired during JPDR decommissioning project. DecDose code is expected to contribute the safety assessment for decommissioning of nuclear facilities.

  17. Construction management of Indian pressurized heavy water reactors

    Energy Technology Data Exchange (ETDEWEB)

    Bohra, S.A. [Nuclear Power Corporation of India Limited, Vikram Sarabhai Bhavan, Anushaktinagar, Mumbai 400094 (India)]. E-mail: sabohra@npcil.co.in; Sharma, P.D. [Nuclear Power Corporation of India Limited, Vikram Sarabhai Bhavan, Anushaktinagar, Mumbai 400094 (India)

    2006-04-15

    Pandit Jawaharlal Nehru and Dr. Homi J. Bhabha, the visionary architects of Science and Technology of modern India foresaw the imperative need to establish a firm base for indigenous research and development in the field of nuclear electricity generation. The initial phase has primarily focused on the technology development in a systematic and structured manner, which has resulted in establishment of strong engineering, manufacturing and construction base. The nuclear power program started with the setting up of two units of boiling light water type reactors in 1969 for speedy establishment of nuclear technology, safety culture, and development of operation and maintenance manpower. The main aim at that stage was to demonstrate (to ourselves, and indeed to the rest of the world) that India, inspite of being a developing country, with limited industrial infrastructure and low capacity power grids, could successfully assimilate the high technology involved in the safe and economical operation of nuclear power reactors. The selection of a BWR was in contrast to the pressurized heavy water reactors (PHWR), which was identified as the flagship for the first stage of India's nuclear power program. The long-term program in three stages utilizes large reserves of thorium in the monazite sands of Kerala beaches in the third stage with first stage comprising of series of PHWR type plants with a base of 10,000 MW. India has at present 14 reactors in operation 12 of these being of PHWR type. The performance of operating units of 2720 MW has improved significantly with an overall capacity factor of about 90% in recent times. The construction work on eight reactor units with installed capacity of 3960 MW (two PHWRs of 540 MW each, four PHWRs of 220 MW each and two VVERs of 1000 MW each) is proceeding on a rapid pace with project schedules of less than 5 years from first pour of concrete. This is being achieved through advanced construction technology and management. Present

  18. Detecting pin diversion from pressurized water reactors spent fuel assemblies

    Energy Technology Data Exchange (ETDEWEB)

    Ham, Young S.; Sitaraman, Shivakumar

    2017-01-10

    Detecting diversion of spent fuel from Pressurized Water Reactors (PWR) by determining possible diversion including the steps of providing a detector cluster containing gamma ray and neutron detectors, inserting the detector cluster containing the gamma ray and neutron detectors into the spent fuel assembly through the guide tube holes in the spent fuel assembly, measuring gamma ray and neutron radiation responses of the gamma ray and neutron detectors in the guide tube holes, processing the gamma ray and neutron radiation responses at the guide tube locations by normalizing them to the maximum value among each set of responses and taking the ratio of the gamma ray and neutron responses at the guide tube locations and normalizing the ratios to the maximum value among them and producing three signatures, gamma, neutron, and gamma-neutron ratio, based on these normalized values, and producing an output that consists of these signatures that can indicate possible diversion of the pins from the spent fuel assembly.

  19. Commercial Light Water Reactor Tritium Extraction Facility Geotechnical Summary Report

    Energy Technology Data Exchange (ETDEWEB)

    Lewis, M R

    2000-01-11

    A geotechnical investigation program has been completed for the Circulating Light Water Reactor - Tritium Extraction Facility (CLWR-TEF) at the Savannah River Site (SRS). The program consisted of reviewing previous geotechnical and geologic data and reports, performing subsurface field exploration, field and laboratory testing and geologic and engineering analyses. The purpose of this investigation was to characterize the subsurface conditions for the CLWR-TEF in terms of subsurface stratigraphy and engineering properties for design and to perform selected engineering analyses. The objectives of the evaluation were to establish site-specific geologic conditions, obtain representative engineering properties of the subsurface and potential fill materials, evaluate the lateral and vertical extent of any soft zones encountered, and perform engineering analyses for slope stability, bearing capacity and settlement, and liquefaction potential. In addition, provide general recommendations for construction and earthwork.

  20. 78 FR 46378 - La Crosse Boiling Water Reactor, Environmental Assessment and Finding of No Significant Impact...

    Science.gov (United States)

    2013-07-31

    ... From the Federal Register Online via the Government Publishing Office NUCLEAR REGULATORY COMMISSION La Crosse Boiling Water Reactor, Environmental Assessment and Finding of No Significant Impact... of Title 10 of the Code of Federal Regulations (10 CFR) for the La Crosse Boiling Water Reactor...

  1. 77 FR 27097 - LaCrosse Boiling Water Reactor, Exemption From Certain Requirements, Vernon County, WI

    Science.gov (United States)

    2012-05-08

    ... From the Federal Register Online via the Government Publishing Office NUCLEAR REGULATORY COMMISSION LaCrosse Boiling Water Reactor, Exemption From Certain Requirements, Vernon County, WI AGENCY...) 73.55, for the LaCrosse Boiling Water Reactor (LACBWR). This Environmental Assessment (EA) has been...

  2. Technology Implementation Plan. Fully Ceramic Microencapsulated Fuel for Commercial Light Water Reactor Application

    Energy Technology Data Exchange (ETDEWEB)

    Snead, Lance Lewis [Oak Ridge National Lab. (ORNL), Oak Ridge, TN (United States); Terrani, Kurt A. [Oak Ridge National Lab. (ORNL), Oak Ridge, TN (United States); Powers, Jeffrey J. [Oak Ridge National Lab. (ORNL), Oak Ridge, TN (United States); Worrall, Andrew [Oak Ridge National Lab. (ORNL), Oak Ridge, TN (United States); Robb, Kevin R. [Oak Ridge National Lab. (ORNL), Oak Ridge, TN (United States); Snead, Mary A. [Oak Ridge National Lab. (ORNL), Oak Ridge, TN (United States)

    2015-04-01

    This report is an overview of the implementation plan for ORNL's fully ceramic microencapsulated (FCM) light water reactor fuel. The fully ceramic microencapsulated fuel consists of tristructural isotropic (TRISO) particles embedded inside a fully dense SiC matrix and is intended for utilization in commercial light water reactor application.

  3. Final Report on Isotope Ratio Techniques for Light Water Reactors

    Energy Technology Data Exchange (ETDEWEB)

    Gerlach, David C.; Gesh, Christopher J.; Hurley, David E.; Mitchell, Mark R.; Meriwether, George H.; Reid, Bruce D.

    2009-07-01

    The Isotope Ratio Method (IRM) is a technique for estimating the energy or plutonium production in a fission reactor by measuring isotope ratios in non-fuel reactor components. The isotope ratios in these components can then be directly related to the cumulative energy production with standard reactor modeling methods.

  4. Annual meeting on nuclear technology '93. Technical session: Procedure and concepts of decommissioning German nuclear power plants. Papers. Jahrestagung Kerntechnik '93. Fachsitzung: Verfahrensweise und Konzepte der Stillegung von deutschen Anlagen. Fachsitzungsreferate

    Energy Technology Data Exchange (ETDEWEB)

    1993-05-01

    Four of the seven papers deal with experience gathered from the decommissioning of NPP in Germany, in particular the Grundremmingen NPP, unit A, the Greifswald NPP, units 1 to 5, the Rheinsberg NPP, and the research reactors SNEAK, MZFR and VAK. The effects of release regulations on decommissioning are examined, and experience gained from expert opinions with regard to decommissionings is outlined. A report is given on the decommissioning procedure of the fuel fabrication plants NUKEM-A and HOBEG. (orig./DG)

  5. Recent performance experience with US light water reactor self-actuating safety and relief valves

    Energy Technology Data Exchange (ETDEWEB)

    Hammer, C.G.

    1996-12-01

    Over the past several years, there have been a number of operating reactor events involving performance of primary and secondary safety and relief valves in U.S. Light Water Reactors. There are several different types of safety and relief valves installed for overpressure protection of various safety systems throughout a typical nuclear power plant. The following discussion is limited to those valves in the reactor coolant systems (RCS) and main steam systems of pressurized water reactors (PWR) and in the RCS of boiling water reactors (BWR), all of which are self-actuating having a setpoint controlled by a spring-loaded disk acting against system fluid pressure. The following discussion relates some of the significant recent experience involving operating reactor events or various testing data. Some of the more unusual and interesting operating events or test data involving some of these designs are included, in addition to some involving a number of similar events and those which have generic applicability.

  6. Decontamination and decommissioning of the Mayaguez (Puerto Rico) facility

    Energy Technology Data Exchange (ETDEWEB)

    Jackson, P.K.; Freemerman, R.L. [Bechtel National, Inc., Oak Ridge, TN (United States)

    1989-11-01

    On February 6, 1987 the US Department of Energy (DOE) awarded the final phase of the decontamination and decommissioning of the nuclear and reactor facilities at the Center for Energy and Environmental Research (CEER), in Mayaguez, Puerto Rico. Bechtel National, Inc., was made the decontamination and decommissioning (D and D) contractor. The goal of the project was to enable DOE to proceed with release of the CEER facility for use by the University of Puerto Rico, who was the operator. This presentation describes that project and lesson learned during its progress. The CEER facility was established in 1957 as the Puerto Rico Nuclear Center, a part of the Atoms for Peace Program. It was a nuclear training and research institution with emphasis on the needs of Latin America. It originally consisted of a 1-megawatt Materials Testing Reactor (MTR), support facilities and research laboratories. After eleven years of operation the MTR was shutdown and defueled. A 2-megawatt TRIGA reactor was installed in 1972 and operated until 1976, when it woo was shutdown. Other radioactive facilities at the center included a 10-watt homogeneous L-77 training reactor, a natural uranium graphite-moderated subcritical assembly, a 200KV particle accelerator, and a 15,000 Ci Co-60 irradiation facility. Support facilities included radiochemistry laboratories, counting rooms and two hot cells. As the emphasis shifted to non-nuclear energy technology a name change resulted in the CEER designation, and plans were started for the decontamination and decommissioning effort.

  7. Three-component U-Pu-Th fuel for plutonium irradiation in heavy water reactors

    Directory of Open Access Journals (Sweden)

    Peel Ross

    2016-01-01

    Full Text Available This paper discusses concepts for three-component fuel bundles containing plutonium, uranium and thorium for use in pressurised heavy water reactors, and cases for and against implementation of such a nuclear energy system in the United Kingdom. Heavy water reactors are used extensively in Canada, and are deploying within India and China, whilst the UK is considering the use of heavy water reactors to manage its plutonium inventory of 140 tonnes. The UK heavy water reactor proposal uses a mixed oxide (MOX fuel of plutonium in depleted uranium, within the enhanced CANDU-6 (EC-6 reactor. This work proposes an alternative heterogeneous fuel concept based on the same reactor and CANFLEX fuel bundle, with eight large-diameter fuel elements loaded with natural thorium oxide and 35 small-diameter fuel elements loaded with a MOX of plutonium and reprocessed uranium stocks from UK MAGNOX and AGR reactors. Indicative neutronic calculations suggest that such a fuel would be neutronically feasible. A similar MOX may alternatively be fabricated from reprocessed <5% enriched light water reactor fuel, such as the fuel of the AREVA EPR reactor, to consume newly produced plutonium from reprocessing, similar to the DUPIC (direct use of PWR fuel in CANDU process.

  8. Cogema experience on decontamination and underwater automatically remote cutting using ultra high pressure water during nuclear decommissioning operations. The Aquarad robot

    Energy Technology Data Exchange (ETDEWEB)

    Bodin, F.; Fournier, Ph. [Cogema, 78 - Velizy Villacoublay (France); Martin, L. [Salvarem, 91 - Saint Aubin (France)

    2002-07-01

    Reprocessing operations on gas cooled French reactor spent fuel included a mechanical operation called decladding, (i.e., stripping the fuel rod from its magnesium metal cladding). After this operation shut down, COGEMA started a D and D project on the decladding building where specific equipment was stored under water. COGEMA then developed and operated a process to decontaminate and cut metallic structures remotely, using ultra-high-pressure water mixed with sand (3600 bar). This paper describes the experience gained, since the start up of this operation in 1994, discusses resulting dosimetry and waste produced, during decontamination and underwater cutting of high active large metallic structures including some with 200 mm thick steel plates. This process results in significantly lower exposures to workers involved in the D and D operations. In addition, the work was carried out in an environmentally safe manner with reasonable financial costs. (author)

  9. Light Water Reactor Sustainability Program: Integrated Program Plan

    Energy Technology Data Exchange (ETDEWEB)

    None, None

    2017-05-01

    proliferation and terrorism. The Light Water Reactor Sustainability (LWRS) Program is the primary programmatic activity that addresses Objective 1. This document summarizes the LWRS Program’s plans. For the LWRS Program, sustainability is defined as the ability to maintain safe and economic operation of the existing fleet of nuclear power plants for a longer-than-initially-licensed lifetime. It has two facets with respect to long-term operations: (1) manage the aging of plant systems, structures, and components so that nuclear power plant lifetimes can be extended and the plants can continue to operate safely, efficiently, and economically; and (2) provide science-based solutions to the industry to implement technology to exceed the performance of the current labor-intensive business model.

  10. Calculating Program for Decommissioning Work Productivity based on Decommissioning Activity Experience Data

    Energy Technology Data Exchange (ETDEWEB)

    Song, Chan-Ho; Park, Seung-Kook; Park, Hee-Seong; Moon, Jei-kwon [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2014-10-15

    KAERI is performing research to calculate a coefficient for decommissioning work unit productivity to calculate the estimated time decommissioning work and estimated cost based on decommissioning activity experience data for KRR-2. KAERI used to calculate the decommissioning cost and manage decommissioning activity experience data through systems such as the decommissioning information management system (DECOMMIS), Decommissioning Facility Characterization DB System (DEFACS), decommissioning work-unit productivity calculation system (DEWOCS). In particular, KAERI used to based data for calculating the decommissioning cost with the form of a code work breakdown structure (WBS) based on decommissioning activity experience data for KRR-2.. Defined WBS code used to each system for calculate decommissioning cost. In this paper, we developed a program that can calculate the decommissioning cost using the decommissioning experience of KRR-2, UCP, and other countries through the mapping of a similar target facility between NPP and KRR-2. This paper is organized as follows. Chapter 2 discusses the decommissioning work productivity calculation method, and the mapping method of the decommissioning target facility will be described in the calculating program for decommissioning work productivity. At KAERI, research on various decommissioning methodologies of domestic NPPs will be conducted in the near future. In particular, It is difficult to determine the cost of decommissioning because such as NPP facility have the number of variables, such as the material of the target facility decommissioning, size, radiographic conditions exist.

  11. Stability analysis of the high performance light water reactor

    Energy Technology Data Exchange (ETDEWEB)

    Ortega Gomez, Tino

    2009-03-15

    In the Generation IV international advanced nuclear reactor development program, the High Performance Light Water Reactor (HPLWR) is one of the most promising candidates. Important features are its inherently high thermodynamic efficiency (of approximately 45 %) and the ability to use existing supercritical water technology which previously has been developed and deployed for fossil fired power plants. Within a HPLWR core, the fluid experiences a drastic change in thermal and transport properties such as density, dynamic viscosity, specific heat and thermal conductivity, as the supercritical water is heated from 280 C to 500 C. The density change substantially exceeds that in a Boiling Water Reactor (i.e., HPLWR: density changes from 780 kg/m{sup 3} to 90 kg/m{sup 3}; BWR: density changes from 750 kg/m{sup 3} to 198 kg/m3). Due to this density change, the HPLWR can be - under certain operation parameters - susceptible to various thermal-hydraulic flow instabilities, which have to be avoided. In this thesis a stability analysis for the HPLWR is presented. This analysis is based on analytical considerations and numerical results, which were obtained by a computer code developed by the author. The heat-up stages of the HPLWR three-pass core are identified in respect to the relevant flow instability phenomena. The modeling approach successfully used for BWR stability analysis is extended to supercritical pressure operation conditions. In particular, a one-dimensional equation set representing the coolant flow of HPLWR fuel assemblies has been implemented in a commercial software named COMSOL to perform steady-state, time-dependent, and modal analyses. An investigation of important static instabilities (i.e., Ledinegg instabilities, flow maldistribution) and Pressure Drop Oscillations (PDO) have been carried out and none were found under operation conditions of the HPLWR. Three types of Density Wave Oscillation (DWO) modes have been studied: the single channel DWO, the

  12. Design and Fluid Dynamic Investigations for a High Performance Light Water Reactor Fuel Assembly

    Science.gov (United States)

    Hofmeister, Jan; Laurin, Eckart; Class, Andreas G.

    2005-11-01

    Within the 5th Framework Program of the European Commission a nuclear light water reactor with supercritical steam conditions has been investigated called High Performance Light Water Reactor (HPLWR). This reactor concept is distinct from conventional light water reactor concepts by the fact, that supercritical water is used to achieve higher core outlet temperatures. The reactor operates with a high system pressure, high heat-up of the coolant within the core, and high outlet temperatures of the coolant resulting in a thermal efficiency of up to 44%. We present the design concept proposed by IKET, and a fluid dynamic problem in the foot piece of the fuel assembly, where unacceptable temperature variations must be omitted.

  13. Power Plant decommissioning

    Directory of Open Access Journals (Sweden)

    Mažeika Jonas

    2014-11-01

    Full Text Available On a first attempt, the determination of 14C and 36Cl activity concentrations in basic operational waste (spent ion-exchange resins and perlite mixture, in decommissioning waste (construction concrete, sand, stainless steel and serpentinite and irradiated graphite from the Ignalina NPP has been performed. The samples for measurement of the specific activity of 14C and 36Cl were obtained from the selected places, where the highest values of the dose rate and the activity concentrations of gamma emitters were found. The performed study of the total 14C and 36Cl activity concentrations was based on estimated chemical forms of 14C (inorganic and organic compounds and 36Cl as Cl- ion. The tested methods used in this study were found to be suitable for estimation of activity concentrations of measured radionuclides.

  14. Decontamination & decommissioning focus area

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-08-01

    In January 1994, the US Department of Energy Office of Environmental Management (DOE EM) formally introduced its new approach to managing DOE`s environmental research and technology development activities. The goal of the new approach is to conduct research and development in critical areas of interest to DOE, utilizing the best talent in the Department and in the national science community. To facilitate this solutions-oriented approach, the Office of Science and Technology (EM-50, formerly the Office of Technology Development) formed five Focus AReas to stimulate the required basic research, development, and demonstration efforts to seek new, innovative cleanup methods. In February 1995, EM-50 selected the DOE Morgantown Energy Technology Center (METC) to lead implementation of one of these Focus Areas: the Decontamination and Decommissioning (D & D) Focus Area.

  15. Activation analysis of dual-purpose metal cask after the end of design lifetime for decommission

    Energy Technology Data Exchange (ETDEWEB)

    Kim, Tae Man; Ku, Ji Young; Dho Ho Seog; Cho, Chun Hyung [Korea Radioactive Waste Agency, Daejeon (Korea, Republic of); Ko, Jae Hun [Korea Nuclear Engineering and Service Co., Daejeon (Korea, Republic of)

    2016-12-15

    The Korea Radioactive Waste Agency (KORAD) has developed a dual-purpose metal cask for the dry storage of spent nuclear fuel that has been generated by domestic light-water reactors. The metal cask was designed in compliance with international and domestic technology standards, and safety was the most important consideration in developing the design. It was designed to maintain its integrity for 50 years in terms of major safety factors. The metal cask ensures the minimization of waste generated by maintenance activities during the storage period as well as the safe management of the waste. An activation evaluation of the main body, which includes internal and external components of metal casks whose design lifetime has expired, provides quantitative data on their radioactive inventory. The radioactive inventory of the main body and the components of the metal cask were calculated by applying the MCNP5·ORIGEN-2 evaluation system and by considering each component's chemical composition, neutron flux distribution, and reaction rate, as well as the duration of neutron irradiation during the storage period. The evaluation results revealed that 10 years after the end of the cask's design life, {sup 60}Co had greater radioactivity than other nuclides among the metal materials. In the case of the neutron shield, nuclides that emit high-energy gamma rays such as {sup 28}Al and {sup 24}Na had greater radioactivity immediately after the design lifetime. However, their radioactivity level became negligible after six months due to their short half-life. The surface exposure dose rates of the canister and the main body of the metal cask from which the spent nuclear fuel had been removed with expiration of the design lifetime were determined to be at very low levels, and the radiation exposure doses to which radiation workers were subjected during the decommissioning process appeared to be at insignificant levels. The evaluations of this study strongly suggest that

  16. Light Water Reactor Sustainability Program, U.S. Efforts in Support of Examinations at Fukushima Daiichi-2017 Evaluations

    Energy Technology Data Exchange (ETDEWEB)

    Farmer, Mitchell T. [Argonne National Lab. (ANL), Argonne, IL (United States)

    2017-08-01

    Although the accident signatures from each unit at the Fukushima Daiichi Nuclear Power Station (NPS) [Daiichi] differ, much is not known about the end-state of core materials within these units. Some of this uncertainty can be attributed to a lack of information related to cooling system operation and cooling water injection. There is also uncertainty in our understanding of phenomena affecting: a) in-vessel core damage progression during severe accidents in boiling water reactors (BWRs), and b) accident progression after vessel failure (ex-vessel progression) for BWRs and Pressurized Water Reactors (PWRs). These uncertainties arise due to limited full scale prototypic data. Similar to what occurred after the accident at Three Mile Island Unit 2, these Daiichi units offer the international community a means to reduce such uncertainties by obtaining prototypic data from multiple full-scale BWR severe accidents. Information obtained from Daiichi is required to inform Decontamination and Decommissioning activities, improving the ability of the Tokyo Electric Power Company Holdings, Incorporated (TEPCO Holdings) to characterize potential hazards and to ensure the safety of workers involved with cleanup activities. This document, which has been updated to include FY2017 information, summarizes results from U.S. efforts to use information obtained by TEPCO Holdings to enhance the safety of existing and future nuclear power plant designs. This effort, which was initiated in 2014 by the Reactor Safety Technologies Pathway of the Department of Energy Office of Nuclear Energy Light Water Reactor (LWR) Sustainability Program, consists of a group of U.S. experts in LWR safety and plant operations that have identified examination needs and are evaluating TEPCO Holdings information from Daiichi that address these needs. Each year, annual reports include examples demonstrating that significant safety insights are being obtained in the areas of component performance, fission

  17. 78 FR 35990 - All Operating Boiling-Water Reactor Licensees With Mark I And Mark II Containments; Docket Nos...

    Science.gov (United States)

    2013-06-14

    ... COMMISSION All Operating Boiling-Water Reactor Licensees With Mark I And Mark II Containments; Docket Nos... Licensees operate boiling-water reactors (BWRs) with Mark I and Mark II containment designs. II. The events... Boiling Water Reactors with Mark I and Mark II Containments'' (November 26, 2012). Option 2 in SECY-12...

  18. 78 FR 63516 - Initial Test Program of Emergency Core Cooling Systems for New Boiling-Water Reactors

    Science.gov (United States)

    2013-10-24

    ... COMMISSION Initial Test Program of Emergency Core Cooling Systems for New Boiling-Water Reactors AGENCY... Cooling Systems for New Boiling-Water Reactors.'' This RG describes testing methods the NRC staff...)-1277, ``Initial Test Program of Emergency Core Cooling Systems for Boiling-Water Reactors.'' DG-1277...

  19. 78 FR 64029 - Cost-Benefit Analysis for Radwaste Systems for Light-Water-Cooled Nuclear Power Reactors

    Science.gov (United States)

    2013-10-25

    ... COMMISSION Cost-Benefit Analysis for Radwaste Systems for Light-Water-Cooled Nuclear Power Reactors AGENCY... Systems for Light-Water-Cooled Nuclear Power Reactors,'' in which the NRC made editorial corrections and... analysis for liquid and gaseous radwaste system components for light water nuclear power reactors...

  20. 10 CFR 50.46 - Acceptance criteria for emergency core cooling systems for light-water nuclear power reactors.

    Science.gov (United States)

    2010-01-01

    ... light-water nuclear power reactors. 50.46 Section 50.46 Energy NUCLEAR REGULATORY COMMISSION DOMESTIC... Approvals § 50.46 Acceptance criteria for emergency core cooling systems for light-water nuclear power reactors. (a)(1)(i) Each boiling or pressurized light-water nuclear power reactor fueled with uranium oxide...

  1. Response of the Gamma TIP Detectorsin a Nuclear Boiling Water Reactor

    OpenAIRE

    Fridström, Richard

    2010-01-01

    In order to monitor a nuclear boiling water reactor fixed and movable detectors are used, such as the neutron sensitive LPRM (Local Power Range Monitors) detectors and the gamma sensitive TIP (Traversing Incore Probe) detectors. These provide a mean to verify the predictions obtained from core simulators, which are used for planning and following up the reactor operation. The core simulators calculate e.g. the neutron flux and power distribution in the reactor core. The simulators can also si...

  2. Architecture for a new age of nuclear waste and decommissioning

    Energy Technology Data Exchange (ETDEWEB)

    Barrie, D. [ed.

    1995-12-31

    Plans to decommission the Trawsfynydd Nuclear Reactor and bury the remaining structure, restoring the site to its previous natural appearance, are set out in this booklet. The ``Poweto Change`` project is a cooperative venture, drawing together architects, engineers, artists and the local communities of Trawsfynydd and Blaenaum Ffestiniog. Plans for reusing parts of the power plants structures to recreate a media centre are discussed and illustrated. (author).

  3. Summary of the 3rd workshop on the reduced-moderation water reactor

    Energy Technology Data Exchange (ETDEWEB)

    Ishikawa, Nobuyuki; Nakatsuka, Tohru; Iwamura, Takamichi [eds.

    2000-06-01

    The research activities of a Reduced-Moderation Water Reactor (RMWR) are being performed for a development of the next generation water-cooled reactor. A workshop on the RMWR was held on March 3rd 2000 aiming to exchange information between JAERI and other organizations such as universities, laboratories, utilities and vendors. This report summarizes the contents of lectures and discussions on the workshop. The 1st workshop was held on March 1998 focusing on the review of the research activities and future research plan. The succeeding 2nd workshop was held on March 1999 focusing on the topics of the plutonium utilization in water-cooled reactors. The 3rd workshop was held on March 3rd 2000, which was attended by 77 participants. The workshop began with a lecture titled 'Recent Situation Related to Reduced-Moderation Water Reactor (RMWR)', followed by 'Program on MOX Fuel Utilization in Light Water Reactors' which is the mainstream scenario of plutonium utilization by utilities, and 'Feasibility Studies on Commercialized Fast Breeder Reactor Cycle System' mainly conducted by Japan Nuclear Cycle Development Institute (JNC). Also, following lectures were given as the recent research activities in JAERI: 'Progress in Design Study on Reduced-Moderation Water Reactors', 'Long-Term Scenarios of Power Reactors and Fuel Cycle Development and the Role of Reduced Moderation Water Reactors', 'Experimental and Analytical Study on Thermal Hydraulics' and Reactor Physics Experiment Plan using TCA'. At the end of the workshop, a general discussion was performed about the research and development of the RMWR. This report includes the original papers presented at the workshop and summaries of the questions and answers for each lecture and general discussion, as well as presentation viewgraphs, program and participant list as appendixes. The 7 of the presented papers are indexed individually. (J.P.N.)

  4. Multi-Application Small Light Water Reactor Final Report

    Energy Technology Data Exchange (ETDEWEB)

    Modro, S.M.; Fisher, J.E.; Weaver, K.D.; Reyes, J.N.; Groome, J.T.; Babka, P.; Carlson, T.M.

    2003-12-01

    The Multi-Application Small Light Water Reactor (MASLWR) project was conducted under the auspices of the Nuclear Energy Research Initiative (NERI) of the U.S. Department of Energy (DOE). The primary project objectives were to develop the conceptual design for a safe and economic small, natural circulation light water reactor, to address the economic and safety attributes of the concept, and to demonstrate the technical feasibility by testing in an integral test facility. This report presents the results of the project. After an initial exploratory and evolutionary process, as documented in the October 2000 report, the project focused on developing a modular reactor design that consists of a self-contained assembly with a reactor vessel, steam generators, and containment. These modular units would be manufactured at a single centralized facility, transported by rail, road, and/or ship, and installed as a series of self-contained units. This approach also allows for staged construction of an NPP and ''pull and replace'' refueling and maintenance during each five-year refueling cycle. Development of the baseline design concept has been sufficiently completed to determine that it complies with the safety requirements and criteria, and satisfies the major goals already noted. The more significant features of the baseline single-unit design concept include: (1) Thermal Power--150 MWt; (2) Net Electrical Output--35 MWe; (3) Steam Generator Type--Vertical, helical tubes; (4) Fuel UO{sub 2}, 8% enriched; (5) Refueling Intervals--5 years; (6) Life-Cycle--60 years. The economic performance was assessed by designing a power plant with an electric generation capacity in the range of current and advanced evolutionary systems. This approach allows for direct comparison of economic performance and forms a basis for further evaluation, economic and technical, of the proposed design and for the design evolution towards a more cost competitive concept

  5. Comparative assessment of nuclear fuel cycles. Light-water reactor once-through, classical fast breeder reactor, and symbiotic fast breeder reactor cycles

    Energy Technology Data Exchange (ETDEWEB)

    Hardie, R.W.; Barrett, R.J.; Freiwald, J.G.

    1980-06-01

    The object of the Alternative Nuclear Fuel Cycle Study is to perform comparative assessments of nuclear power systems. There are two important features of this study. First, this evaluation attempts to encompass the complete, integrated fuel cycle from mining of uranium ore to disposal of waste rather than isolated components. Second, it compares several aspects of each cycle - energy use, economics, technological status, proliferation, public safety, and commercial potential - instead of concentrating on one or two assessment areas. This report presents assessment results for three fuel cycles. These are the light-water reactor once-through cycle, the fast breeder reactor on the classical plutonium cycle, and the fast breeder reactor on a symbiotic cycle using plutonium and /sup 233/U as fissile fuels. The report also contains a description of the methodology used in this assessment. Subsequent reports will present results for additional fuel cycles.

  6. Licensing assessment of the Candu Pressurized Heavy Water Reactor. Preliminary safety information document. Volume II. [USA

    Energy Technology Data Exchange (ETDEWEB)

    1977-06-01

    ERDA has requested United Engineers and Constructors (UE and C) to evaluate the design of the Canadian natural uranium fueled, heavy water moderated (CANDU) nuclear reactor power plant to assess its conformance with the licensing criteria and guidelines of the U.S. Nuclear Regulatory Commission (USNRC) for light water reactors. This assessment was used to identify cost significant items of nonconformance and to provide a basis for developing a detailed cost estimate for a 1140 MWe, 3-loop Pressurized Heavy Water Reactor (PHWR) located at the Middletown, USA Site.

  7. Bacterial Colonization of Pellet Softening Reactors Used during Drinking Water Treatment

    NARCIS (Netherlands)

    Hammes, F.; Boon, N.; Vital, M.; Ross, P.; Magic-Knezev, A.; Dignum, M.

    2010-01-01

    Pellet softening reactors are used in centralized and decentralized drinking water treatment plants for the removal of calcium (hardness) through chemically induced precipitation of calcite. This is accomplished in fluidized pellet reactors, where a strong base is added to the influent to increase

  8. 77 FR 23513 - Updated Aging Management Criteria for Reactor Vessel Internal Components of Pressurized Water...

    Science.gov (United States)

    2012-04-19

    ... COMMISSION Updated Aging Management Criteria for Reactor Vessel Internal Components of Pressurized Water... Management Criteria for PWR Reactor Vessel Internal Components.'' The original notice provided the ADAMS... published a notice requesting public comments on draft LR-ISG-2011-04, ``Updated Aging Management Criteria...

  9. Supercritical water gasification of sewage sludge in continuous reactor.

    Science.gov (United States)

    Amrullah, Apip; Matsumura, Yukihiko

    2017-10-05

    In this study, a process for the continuous recovery of phosphorus and generation of gas from sewage sludge is investigated for the first time using supercritical water gasification (SCWG). A continuous reactor was employed and experiments were conducted by varying the temperature (500-600 °C) and residence time (5-60 s) while fixing the pressure at 25 MPa. The behavior of phosphorus during the SCWG process was studied. The effect of the temperature and time on the composition of the product gas was also investigated. A model of the reaction kinetics for the SCWG of sewage sludge was developed. The organic phosphorus (OP) was rapidly converted into inorganic phosphorus (IP) within a short residence time of 10 s. The gaseous products were mainly composed of H2, CO2, and CH4. The reaction followed first order kinetics, and the model was found to fit the experimental data well. Copyright © 2017 Elsevier Ltd. All rights reserved.

  10. TOBI: A nonlinear model for boiling water reactor stability analysis

    Energy Technology Data Exchange (ETDEWEB)

    Wehle, F. (Siemens/KWU, Offenbach (West Germany)); Pruitt, D.W.

    1990-06-01

    The magnitude and the divergent nature of the oscillations during the LaSalle unit 2 nuclear power plant even on March 9, 1988, renewed concern about the state of knowledge on boiling water reactor (BWR) instabilities and was followed by many activities, e.g., the Idaho Stability Symposium. For appropriate representation of the physical processes, typical BWR time-domain stability calculations with, e.g., TRAC, RETRAN, or THERMIT require a large number of axial nodes and are very costly with regard to computer time. Linear models are inexpensive, but only valid as long as the parameters have no large deviation from the reference operating conditions. The objective of this work is the development of a physical model that is applicable for stability analysis in the nonlinear regime, but without the disadvantage of numerical problems and excessive computing times. The basic concept of the model TOBI is the integral study of the interaction between the time-dependent single- and two-phase regions. A series of calculations for purely thermal-hydraulic systems and BWRs has shown that TOBI is a convenient tool for stability analysis. Because of the simple but physically realistic modeling, it is very helpful in achieving an improved understanding of the mechanisms that affect BWR stability, and it is inexpensive, with regard to computer time, to perform extensive parameter sensitivity studies, even in the nonlinear regime.

  11. Structural analysis of fuel rod applied to pressurized water reactors

    Energy Technology Data Exchange (ETDEWEB)

    Faria, Danilo P.; Pinheiro, Andre Ricardo M.; Lotto, André A., E-mail: danilo.pinheiro@marinha.mil.br [Centro Tecnológico da Marinha em São Paulo (CTMSP), São Paulo, SP (Brazil)

    2017-07-01

    The design of fuel assemblies applied to Pressurized Water Reactors (PWR) has several requirements and acceptance criteria that must be attended for licensing. In the case of PWR fuel rods, an important mechanical structural requirement is to keep the radial stability when submitted to the coolant external pressure. In the framework of the Accident Tolerant Fuel (ATF) program new materials have been studied to replace zirconium based alloys as cladding, including iron-based alloys. In this sense, efforts have been made to evaluate the behavior of these materials under PWR conditions. The present work aims to evaluate the collapse cold pressure of a stainless steel thin-walled tube similar to that used as cladding material of fuel rods by means of the comparison of numeric data, and experimental results. As a result of the simulations, it was observed that the collapse pressure has a value intermediate value between those found by regulatory requirements and analytical calculations. The experiment was carried out for the validation of the computational model using test specimens of thin-walled tubes considering empty tube. The test specimens were sealed at both ends by means of welding. They were subjected to a high pressure device until the collapse of the tubes. Preliminary results obtained from experiments with the empty test specimens indicate that the computational model can be validated for stainless steel cladding, considering the difference between collapse pressure indicated in the regulatory document and the actual limit pressure concerning to radial instability of tubes with the studied characteristics. (author)

  12. Study on unstable fracture characteristics of light water reactor piping

    Energy Technology Data Exchange (ETDEWEB)

    Kurihara, Ryoichi [Japan Atomic Energy Research Inst., Naka, Ibaraki (Japan). Naka Fusion Research Establishment

    1998-08-01

    Many testing studies have been conducted to validate the applicability of the leak before break (LBB) concept for the light water reactor piping in the world. It is especially important among them to clarify the condition that an inside surface crack of the piping wall does not cause an unstable fracture but ends in a stable fracture propagating only in the pipe thickness direction, even if the excessive loading works to the pipe. Pipe unstable fracture tests performed in Japan Atomic Energy Research Institute had been planned under such background, and clarified the condition for the cracked pipe to cause the unstable fracture under monotonous increase loading or cyclic loading by using test pipes with the inside circumferential surface crack. This paper examines the pipe unstable fracture by dividing it into two parts. One is the static unstable fracture that breaks the pipe with the inside circumferential surface crack by increasing load monotonously. Another is the dynamic unstable fracture that breaks the pipe by the cyclic loading. (author). 79 refs.

  13. Installation of the Light-Water Breeder Reactor at the Shippingport Atomic Power Station (LWBR Development Program)

    Energy Technology Data Exchange (ETDEWEB)

    Massimino, R.J.; Williams, D.A.

    1983-05-01

    This report summarizes the refueling operations performed to install a Light Water Breeder Reactor (LWBR) core into the existing pressurized water reactor vessel at the Shippingport Atomic Power Station. Detailed descriptions of the major installation operations (e.g., primary system preconditioning, fuel installation, pressure boundary seal welding) are included as appendices to this report; these operations are of technical interest to any reactor servicing operation, whether the reactor is a breeder or a conventional light water non-breeder core.

  14. Experimental Studies of NGNP Reactor Cavity Cooling System With Water

    Energy Technology Data Exchange (ETDEWEB)

    Corradini, Michael; Anderson, Mark; Hassan, Yassin; Tokuhiro, Akira

    2013-01-16

    This project will investigate the flow behavior that can occur in the reactor cavity cooling system (RCCS) with water coolant under the passive cooling-mode of operation. The team will conduct separate-effects tests and develop associated scaling analyses, and provide system-level phenomenological and computational models that describe key flow phenomena during RCCS operation, from forced to natural circulation, single-phase flow and two-phase flow and flashing. The project consists of the following tasks: Task 1. Conduct separate-effects, single-phase flow experiments and develop scaling analyses for comparison to system-level computational modeling for the RCCS standpipe design. A transition from forced to natural convection cooling occurs in the standpipe under accident conditions. These tests will measure global flow behavior and local flow velocities, as well as develop instrumentation for use in larger scale tests, thereby providing proper flow distribution among standpipes for decay heat removal. Task 2. Conduct separate-effects experiments for the RCCS standpipe design as two-phase flashing occurs and flow develops. As natural circulation cooling continues without an ultimate heat sink, water within the system will heat to temperatures approaching saturation , at which point two-phase flashing and flow will begin. The focus is to develop a phenomenological model from these tests that will describe the flashing and flow stability phenomena. In addition, one could determine the efficiency of phase separation in the RCCS storage tank as the two-phase flashing phenomena ensues and the storage tank vents the steam produced. Task 3. Develop a system-level computational model that will describe the overall RCCS behavior as it transitions from forced flow to natural circulation and eventual two-phase flow in the passive cooling-mode of operation. This modeling can then be used to test the phenomenological models developed as a function of scale.

  15. Models and Stability Analysis of Boiling Water Reactors

    Energy Technology Data Exchange (ETDEWEB)

    John Dorning

    2002-04-15

    We have studied the nuclear-coupled thermal-hydraulic stability of boiling water reactors (BWRs) using a model that includes: space-time modal neutron kinetics based on spatial w-modes; single- and two-phase flow in parallel boiling channels; fuel rod heat conduction dynamics; and a simple model of the recirculation loop. The BR model is represented by a set of time-dependent nonlinear ordinary differential equations, and is studied as a dynamical system using the modern bifurcation theory and nonlinear dynamical systems analysis. We first determine the stability boundary (SB) - or Hopf bifurcation set- in the most relevant parameter plane, the inlet-subcooling-number/external-pressure-drop plane, for a fixed control rod induced external reactivity equal to the 100% rod line value; then we transform the SB to the practical power-flow map used by BWR operating engineers and regulatory agencies. Using this SB, we show that the normal operating point at 100% power is very stable, that stability of points on the 100% rod line decreases as the flow rate is reduced, and that operating points in the low-flow/high-power region are least stable. We also determine the SB that results when the modal kinetics is replaced by simple point reactor kinetics, and we thereby show that the first harmonic mode does not have a significant effect on the SB. However, we later show that it nevertheless has a significant effect on stability because it affects the basin of attraction of stable operating points. Using numerical simulations we show that, in the important low-flow/high-power region, the Hopf bifurcation that occurs as the SB is crossed is subcritical; hence, growing oscillations can result following small finite perturbations of stable steady-states on the 100% rod line at points in the low-flow/high-power region. Numerical simulations are also performed to calculate the decay ratios (DRs) and frequencies of oscillations for various points on the 100% rod line. It is

  16. Thermal-Hydraulics analysis of pressurized water reactor core by using single heated channel model

    Directory of Open Access Journals (Sweden)

    Reza Akbari

    2017-08-01

    Full Text Available Thermal hydraulics of nuclear reactor as a basis of reactor safety has a very important role in reactor design and control. The thermal-hydraulic analysis provides input data to the reactor-physics analysis, whereas the latter gives information about the distribution of heat sources, which is needed to perform the thermal-hydraulic analysis. In this study single heated channel model as a very fast model for predicting thermal hydraulics behavior of pressurized water reactor core has been developed. For verifying the results of this model, we used RELAP5 code as US nuclear regulatory approved thermal hydraulics code. The results of developed single heated channel model have been checked with RELAP5 results for WWER-1000. This comparison shows the capability of single heated channel model for predicting thermal hydraulics behavior of reactor core.

  17. Summary of the 4th workshop on the reduced-moderation water reactor

    Energy Technology Data Exchange (ETDEWEB)

    Nakatsuka, Toru; Ishikawa, Nobuyuki; Iwamura, Takamichi (eds.) [Japan Atomic Energy Research Inst., Tokai, Ibaraki (Japan). Tokai Research Establishment

    2001-09-01

    The research on Reduced-Moderation Water Reactors (RMWRs) has been performed in JAERI for the development of future innovative reactors. The workshop on the RMWRs has been held every year since fiscal 1997 aimed at information exchange between JAERI and other organizations such as universities, laboratories, utilities and vendors. The 4th workshop was held on March 2, 2001 under the joint auspices of JAERI and North Kanto branch of Atomic Energy Society of Japan. The workshop began with three lectures on recent research activities in JAERI entitled 'Recent Situation of Research on Reduced-Moderation Water Reactor', 'Analysis on Electricity Generation Costs of Reduced Moderation Water Reactors' and 'Reprocessing Technology for Spent Mixed-Oxides Fuel from LWR'. Then five lectures followed: 'Micro Reactor Physics of MOX Fueled LWR' which shows the recent results of reactor physics, Fast Reactor Cooled by Supercritical Light Water' which is another type of reduced-moderation reactor, 'Phase 1 of Feasibility Studies on Commercialized Fast Breeder Reactor Cycle System' mainly conducted by Japan Nuclear Cycle Development Institute (JNC), 'Integral Type Small PWR with Stand-alone Safety' which is intended to suit for the future consumers' needs, and Utilization of Plutonium in Reduced-Moderation Water Reactors' which dictates benefits of plutonium utilization with RMWRs. This report includes the original papers presented at the workshop and summaries of the questions and answers for each lecture, as well as presentation handouts, program and participant list as appendixes. The 8 of the presented papers are indexed individually. (J.P.N.)

  18. Pressurized hydrogenotrophic denitrification reactor for small water systems.

    Science.gov (United States)

    Epsztein, Razi; Beliavski, Michael; Tarre, Sheldon; Green, Michal

    2017-03-15

    The implementation of hydrogenotrophic denitrification is limited due to safety concerns, poor H2 utilization and low solubility of H2 gas with the resulting low transfer rate. The current paper presents the main research work conducted on a pressurized hydrogenotrophic reactor for denitrification that was recently developed. The reactor is based on a new concept suggesting that a gas-liquid equilibrium is achieved in the closed headspace of denitrifying reactor, further produced N2 gas is carried out by the effluent and gas purging is not required. The feasibility of the proposed reactor was shown for two effluent concentrations of 10 and 1 mg NO3--N/L. Hydrogen gas utilization efficiencies of 92.8% and 96.9% were measured for the two effluent concentrations, respectively. Reactor modeling predicted high denitrification rates above 4 g NO3--N/(Lreactor·d) at reasonable operational conditions. Hydrogen utilization efficiency was improved up to almost 100% by combining the pressurized reactor with a following open-to-atmosphere polishing unit. Also, the potential of the reactor to remove ClO4- was shown. Copyright © 2017 Elsevier Ltd. All rights reserved.

  19. Decommissioning the Belgonucleaire Dessel MOX plant: presentation of the project and situation end august 2013

    Energy Technology Data Exchange (ETDEWEB)

    Cuchet, J.M. [TRACTEBEL ENGINEERING, Avenue Ariane, 7, B1200 Brussels (Belgium); Libon, H.; Verheyen, C. [BELGONUCLEAIRE S.A. / N.V. Europalaan, 20, B2480 Dessel (Belgium); Bily, J. [STUDSVIK GmbH, Karlsruher Strasse, 20, D75179 Pforzheim,(Germany); Boden, S. [SCK-CEN, Boeretang, 200, B2400 Mol (Belgium); Joffroy, F. [TECNUBEL N.V., Zandbergen, 1, B2480 Dessel (Belgium); Walthery, R. [BELGOPROCESS, Gravenstraat, 73, B2480 Dessel (Belgium)

    2013-07-01

    Belgonucleaire has been operating the Dessel MOX plant at an industrial scale between 1986 and 2006. During this period, 40 metric tons of plutonium (HM) have been processed into 90 reloads of MOX fuel for commercial light water reactors. The decision to stop the production in 2006 and to decommission the MOX plant was the result of the shrinkage of the MOX fuel market due to political and commercial factors. As a significant part of the decommissioning project of the Dessel MOX plant, about 170 medium-sized glove-boxes and about 1.200 metric tons of structure and equipment outside the glove-boxes are planned for dismantling. The license for the dismantling of the MOX plant was granted by Royal Decree in 2008 and the dismantling started in March 2009. The dismantling works are carried out by an integrated organization under leadership and responsibility of Belgonucleaire; this organization includes 3 main contractors, namely Tecnubel N.V., the THV ('Tijdelijke HandelsVereniging') Belgoprocess / SCK-CEN and Studsvik GmbH and Tractebel Engineering as project manager. In this paper, after having described the main characteristics of the project, the authors review the different organizational and technical options considered for the decommissioning of the glove-boxes; thereafter the main decision criteria (qualification of personnel and of processes, confinement, cutting techniques and radiation protection, safety aspects, alpha-bearing waste management) are analyzed as well. Finally the progress, the feedback and the lessons learned at the end of August 2013 are presented, giving the principal's and contractors point of view. (authors)

  20. Light Water Reactor Sustainability Program: Analysis of Pressurized Water Reactor Station Blackout Caused by External Flooding Using the RISMC Toolkit

    Energy Technology Data Exchange (ETDEWEB)

    Smith, Curtis [Idaho National Lab. (INL), Idaho Falls, ID (United States); Mandelli, Diego [Idaho National Lab. (INL), Idaho Falls, ID (United States); Prescott, Steven [Idaho National Lab. (INL), Idaho Falls, ID (United States); Alfonsi, Andrea [Idaho National Lab. (INL), Idaho Falls, ID (United States); Rabiti, Cristian [Idaho National Lab. (INL), Idaho Falls, ID (United States); Cogliati, Joshua [Idaho National Lab. (INL), Idaho Falls, ID (United States); Kinoshita, Robert [Idaho National Lab. (INL), Idaho Falls, ID (United States)

    2014-08-01

    The existing fleet of nuclear power plants is in the process of extending its lifetime and increasing the power generated from these plants via power uprates. In order to evaluate the impact of these factors on the safety of the plant, the Risk Informed Safety Margin Characterization (RISMC) project aims to provide insight to decision makers through a series of simulations of the plant dynamics for different initial conditions (e.g., probabilistic analysis and uncertainty quantification). This report focuses, in particular, on the application of a RISMC detailed demonstration case study for an emergent issue using the RAVEN and RELAP-7 tools. This case study looks at the impact of a couple of challenges to a hypothetical pressurized water reactor, including: (1) a power uprate, (2) a potential loss of off-site power followed by the possible loss of all diesel generators (i.e., a station black-out event), (3) and earthquake induces station-blackout, and (4) a potential earthquake induced tsunami flood. The analysis is performed by using a set of codes: a thermal-hydraulic code (RELAP-7), a flooding simulation tool (NEUTRINO) and a stochastic analysis tool (RAVEN) – these are currently under development at the Idaho National Laboratory.

  1. Capital cost: pressurized water reactor plant. Commercial electric power cost studies

    Energy Technology Data Exchange (ETDEWEB)

    1977-06-01

    The investment cost study for the 1139 MW(e) pressurized water reactor (PWR) central station power plant consists of two volumes. This volume contains the drawings, equipment list and site description.

  2. Establishment and Evaluation of Decommissioning Plant Inventory DB and Waste Quantity

    Energy Technology Data Exchange (ETDEWEB)

    Oh, Jae Yong; Moon, Sang-Rae; Yun, Taesik; Kim, Hee-Geun [KHNP CRI, Daejeon (Korea, Republic of); Sung, Nak-Hoon; Jung, Seung Hyuk [KONES Corp., Seoul (Korea, Republic of)

    2016-10-15

    Korea Hydro and Nuclear Power (KHNP) made a decision for permanent shutdown of Kori-1 and has progressed the strategy determination and R and D for the decommissioning of Kori-1. Decommissioning waste, Structure, System and Components (SSCs) is one of the most important elements. Decommissioning waste quantity is calculated based on Plant Inventory Database (PI DB) with activation and contamination data. Due to the largest portion of waste management and disposal in decommissioning, it is necessary to exactly evaluate waste quantity (applying the regulation, guideline and site-specific characterization) for economic feasibility. In this paper, construction of PI DB and evaluation of waste quantity for Optimized Pressurized Reactor (OPR-1000) are mainly described. Decommissioning waste quantities evaluated are going to be applied to calculation of the project cost. In fact, Ministry of Trade, Industry and Energy (MOTIE) in Korea expected the decommissioning waste quantity in a range of 14,500-18,850 drums, and predicted appropriate liability for decommissioning fund by using waste quantity. The result of this study is also computed by the range of 14,500-18,850 drums. Since there is no site-specific data for the NPP site, this evaluation is the preliminary analysis.

  3. A State of the Art on the Technology for Recycling and Reuse of the Decommissioning Concrete Wastes

    Energy Technology Data Exchange (ETDEWEB)

    Jung, Chung Hun; Choi, Wang Kyu; Min, Byung Youn; Oh, Won Zin; Lee, Kun Woo [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2008-02-15

    This report describes the reduction and recycling technology of decommissioning concrete waste. Decontamination and decommissioning (D and D) becomes one of the most important nuclear markets especially in the developed countries including USA, UK and France where lots of the retired nuclear facilities have been waiting for decommissioning. In our country the KAERI has been carrying out the decommissioning of the retired TRIGA MARK II and III research reactors and an uranium conversion plant as the first national decommissioning project since 1998. One of the most important areas of the decommissioning is a management of a huge amount of a decommissioning waste the cost of which is more than half of the total decommissioning cost. Therefore reduction in decommissioning waste by a reuse or a recycle is an important subject of decommissioning technology development in the world. Recently much countries pay attention to recycle the large amount of concrete dismantling waste resulted from both a nuclear and a non nuclear industries. In our country, much attention was taken in a recycle of concrete dismantling waste as a concrete aggregate, but a little success has been resulted due to the disadvantages such as a weakness of hardness and surface mortar contamination. A recycle in nuclear industry and a self disposal of the radioactively contaminated concrete wastes are main directions of concrete wastes resulted from a nuclear facility decommissioning. In this report it was reviewed the state of art of the related technologies for a reduction and a recycle of concrete wastes from a nuclear decommissioning in the country and abroad. Prior to recycle and reuse in the nuclear sector, however, the regulatory criteria for the recycle and reuse of concrete waste should be established in parallel with the development of the recycling technology.

  4. Feasibility Study of Supercritical Light Water Cooled Reactors for Electric Power Production

    Energy Technology Data Exchange (ETDEWEB)

    Philip MacDonald; Jacopo Buongiorno; James Sterbentz; Cliff Davis; Robert Witt; Gary Was; J. McKinley; S. Teysseyre; Luca Oriani; Vefa Kucukboyaci; Lawrence Conway; N. Jonsson: Bin Liu

    2005-02-13

    The supercritical water reactor (SCWR) has been the object of interest throughout the nuclear Generation IV community because of its high potential: a simple, direct cycle, compact configuration; elimination of many traditional LWR components, operation at coolant temperatures much higher than traditional LWRs and thus high thermal efficiency. It could be said that the SWR was viewed as the water counterpart to the high temperature gas reactor.

  5. Zeolite Membrane Reactor for Water Gas Shift Reaction for Hydrogen Production

    Energy Technology Data Exchange (ETDEWEB)

    Lin, Jerry Y.S. [Arizona State Univ., Mesa, AZ (United States)

    2013-01-29

    Gasification of biomass or heavy feedstock to produce hydrogen fuel gas using current technology is costly and energy-intensive. The technology includes water gas shift reaction in two or more reactor stages with inter-cooling to maximize conversion for a given catalyst volume. This project is focused on developing a membrane reactor for efficient conversion of water gas shift reaction to produce a hydrogen stream as a fuel and a carbon dioxide stream suitable for sequestration. The project was focused on synthesizing stable, hydrogen perm-selective MFI zeolite membranes for high temperature hydrogen separation; fabricating tubular MFI zeolite membrane reactor and stable water gas shift catalyst for membrane reactor applications, and identifying experimental conditions for water gas shift reaction in the zeolite membrane reactor that will produce a high purity hydrogen stream. The project has improved understanding of zeolite membrane synthesis, high temperature gas diffusion and separation mechanisms for zeolite membranes, synthesis and properties of sulfur resistant catalysts, fabrication and structure optimization of membrane supports, and fundamentals of coupling reaction with separation in zeolite membrane reactor for water gas shift reaction. Through the fundamental study, the research teams have developed MFI zeolite membranes with good perm-selectivity for hydrogen over carbon dioxide, carbon monoxide and water vapor, and high stability for operation in syngas mixture containing 500 part per million hydrogen sulfide at high temperatures around 500°C. The research teams also developed a sulfur resistant catalyst for water gas shift reaction. Modeling and experimental studies on the zeolite membrane reactor for water gas shift reaction have demonstrated the effective use of the zeolite membrane reactor for production of high purity hydrogen stream.

  6. Third party liability of nuclear installation decommissioning with Russian nuclear submarines as an example: insurance versus technologies

    Energy Technology Data Exchange (ETDEWEB)

    Gavrilov, S.D. [PREKSAT Ltd., Moscow (Russian Federation); Derevyankin, A.A. [Reseaarch and Development Institute of Nuclear Power Engineering, Moscow (Russian Federation); Khamyanov, L.P. [All-Russian Research Institute on NPP Operation, Moscow (Russian Federation); Kovalenko, V.N. [Ministry for Nuclear Energy Of Russian, Moscow (Russian Federation); Kovalivich, O.M. [Research and Technological Center for Nuclear and Radiation Safety of Supervisory, Nuclear Energy State Commitee of Russia, Moscow (Russian Federation); Smirnov, P.L. [Nuclear Safety Institute of Russian Academy of Sciences, Moscow (Russian Federation)

    2001-07-01

    Third party and environment of civil liability damage caused by incidents at military nuclear installations, for instance at decommissioned NPS (nuclear powered submarines), may be divided into three main trends: -) Liability of NPS without high-enriched irradiated nuclear fuel (SNF) for its self-submersion (radiation incident); -) Liability of NPS with SNF aboard for its self-submersion (radiation incident); and -) Liability of floating NPS for its SNF discharge (nuclear accident). Without step-by-step transition from the Russian Federation guaranties to insurance and making allowance for liability limits according to the Vienna Convention approach, the sizes of the financial guarantee for the civil liability of the NPS owner (Russian state), in US dollars of 2000, are approximately assessed as the following: -) storing decommissioned NPS or a floating module without SNF - from 12 to 25 thousand dollars per year (per one submarine or module); -) storing decommissioned NPS with SNF inside reactors cores - from 25 to 40 thousand dollars per year; -) assembly-by-assembly removing SNF from reactors' core of decommissioned NPS - up to 1.5 million dollars for undamaged reactor per the discharging period; -) SNF removing within reactor using the filled in-space reactor's core by liquid-phased hardened or dispersed solid-phase materials from decommissioned NPS - from 30 to 50 thousand dollars for undamaged reactor per the discharging period. Both rates and sums for NPS with damaged reactors are to be estimated for the each damaged reactor and NPS at all. It is necessary to perform the measures reducing the risk of nuclear accidents of NPS with undamaged SNF and NPS with damaged reactors in possibly short time. It will allow not only to cut risks by ten times and more, but also to accumulate necessary insurance reserves faster. These measures can be partially or completely executed using the preventing measures reserves assigned to all decommissioned Russian NPS

  7. Recent results of research on supercritical water-cooled reactors in Europe

    Energy Technology Data Exchange (ETDEWEB)

    Starflinger, J.; Koehly, C.; Schulenberg, T. [Forschungszentrum Karlsruhe, Karlsruhe (Germany); Maraczy, C. [AEKI-KFKI, Budapest (Hungary); Toivonen, A.; Penttila, S. [VTT Technical Research Centre, Espoo (Finland); Chandra, L.; Lycklama a Nijeholt, J.A. [Nuclear Research and Consultancy Group (NRG), Petten (Netherlands)

    2009-07-01

    In Europe, the research on Supercritical Water-Cooled Reactors is integrated in a project called 'High Performance Light Water Reactor Phase 2' (HPLWR Phase 2), co-funded by the European Commission. Ten partners and three active supporters are working on critical scientific issues to determine the potential of this reactor concept in the electricity market. The recent design of the HPLWR including flow paths is described in this paper. Exemplarily, design analyses are presented addressing neutronics, thermal-hydraulics, thermo-mechanics, materials investigations and heat transfer. (author)

  8. Passive gamma analysis of the boiling-water-reactor assemblies

    Science.gov (United States)

    Vo, D.; Favalli, A.; Grogan, B.; Jansson, P.; Liljenfeldt, H.; Mozin, V.; Schwalbach, P.; Sjöland, A.; Tobin, S.; Trellue, H.; Vaccaro, S.

    2016-09-01

    This research focused on the analysis of a set of stationary passive gamma measurements taken on the spent nuclear fuel assemblies from a boiling water reactor (BWR) using pulse height analysis data acquisition. The measurements were performed on 25 different BWR assemblies in 2014 at Sweden's Central Interim Storage Facility for Spent Nuclear Fuel (Clab). This study was performed as part of the Next Generation of Safeguards Initiative-Spent Fuel project to research the application of nondestructive assay (NDA) to spent fuel assemblies. The NGSI-SF team is working to achieve the following technical goals more easily and efficiently than in the past using nondestructive assay (NDA) measurements of spent fuel assemblies: (1) verify the initial enrichment, burnup, and cooling time of facility declaration; (2) detect the diversion or replacement of pins, (3) estimate the plutonium mass, (4) estimate the decay heat, and (5) determine the reactivity of spent fuel assemblies. The final objective of this project is to quantify the capability of several integrated NDA instruments to meet the aforementioned goals using the combined signatures of neutrons, gamma rays, and heat. This report presents a selection of the measured data and summarizes an analysis of the results. Specifically, trends in the count rates measured for spectral lines from the following isotopes were analyzed as a function of the declared burnup and cooling time: 137Cs, 154Eu, 134Cs, and to a lesser extent, 106Ru and 144Ce. From these measured count rates, predictive algorithms were developed to enable the estimation of the burnup and cooling time. Furthermore, these algorithms were benchmarked on a set of assemblies not included in the standard assemblies set used by this research team.

  9. FMDP Reactor Alternative Summary Report: Volume 2 - CANDU heavy water reactor alternative

    Energy Technology Data Exchange (ETDEWEB)

    Greene, S.R.; Spellman, D.J.; Bevard, B.B. [and others

    1996-09-01

    The Department of Energy Office of Fissile Materials Disposition (DOE/MD) initiated a detailed analysis activity to evaluate each of ten plutonium disposition alternatives that survived an initial screening process. This document, Volume 2 of a four volume report, summarizes the results of these analyses for the CANDU reactor based plutonium disposition alternative.

  10. Roadmap for Nondestructive Evaluation of Reactor Pressure Vessel Research and Development by the Light Water Reactor Sustainability Program

    Energy Technology Data Exchange (ETDEWEB)

    Smith, Cyrus M [ORNL; Nanstad, Randy K [ORNL; Clayton, Dwight A [ORNL; Matlack, Katie [Georgia Institute of Technology; Ramuhalli, Pradeep [Pacific Northwest National Laboratory (PNNL); Light, Glenn [Southwest Research Institute, San Antonio

    2012-09-01

    The Department of Energy s (DOE) Light Water Reactor Sustainability (LWRS) Program is a five year effort which works to develop the fundamental scientific basis to understand, predict, and measure changes in materials and systems, structure, and components as they age in environments associated with continued long-term operations of existing commercial nuclear power reactors. This year, the Materials Aging and Degradation (MAaD) Pathway of this program has placed emphasis on emerging Non-Destructive Evaluation (NDE) methods which support these objectives. DOE funded Research and Development (R&D) on emerging NDE techniques to support commercial nuclear reactor sustainability is expected to begin next year. This summer, the MAaD Pathway invited subject matter experts to participate in a series of workshops which developed the basis for the research plan of these DOE R&D NDE activities. This document presents the results of one of these workshops which are the DOE LWRS NDE R&D Roadmap for Reactor Pressure Vessels (RPV). These workshops made a substantial effort to coordinate the DOE NDE R&D with that already underway or planned by the Electric Power Research Institute (EPRI) and the Nuclear Regulatory Commission (NRC) through their representation at these workshops.

  11. The role of water chemistry for environmentally assisted cracking in low-alloy reactor pressure vessel and piping steels under boiling reactor conditions

    Energy Technology Data Exchange (ETDEWEB)

    Seifert, H.-P.; Ritter, S

    2005-07-01

    The environmentally assisted initiation and propagation of cracks in structural materials is one of the most important degradation and ageing mechanisms in light water reactors (LWR) and may seriously affect plant availability and economics. In the first part of this paper a short general introduction on environmentally assisted cracking (EAC) and its significance for LWR is given. Then the important role of water chemistry control in reducing the EAC risk in LWR is illustrated by current research results about the effect of chloride transients and hydrogen water chemistry on the EAC crack growth behaviour of low-alloy reactor pressure vessel and piping steels under boiling water reactor conditions. (author)

  12. Decommissioning: a problem or a challenge?

    OpenAIRE

    Mele Irena

    2004-01-01

    With the ageing of nuclear facilities or the reduced interest in their further operation, a new set of problems, related to the decommissioning of these facilities, has come into forefront. In many cases it turns out that the preparations for decommissioning have come too late, and that financial resources for covering decommissioning activities have not been provided. To avoid such problems, future liailities should be thoroughly estimated in drawing up the decommissioning and waste manageme...

  13. Decommissioning Plan for European Spallation Source

    Science.gov (United States)

    Ene, Daniela

    2017-09-01

    This paper is a survey of the European Spallation Source initial decommissioning plan developed in compliance with Swedish Regulatory Authority requirements. The report outlines the decommissioning strategy selected and the baseline plan for decommissioning. Types and quantities of radioactive waste estimated to be generated at the final shut-down of the facility are further provided. The paper ends up with the analysis of the key elements of the decommissioning plan and the recommendations to the ESS management team..

  14. Decommissioning Plan for European Spallation Source

    Directory of Open Access Journals (Sweden)

    Ene Daniela

    2017-01-01

    Full Text Available This paper is a survey of the European Spallation Source initial decommissioning plan developed in compliance with Swedish Regulatory Authority requirements. The report outlines the decommissioning strategy selected and the baseline plan for decommissioning. Types and quantities of radioactive waste estimated to be generated at the final shut-down of the facility are further provided. The paper ends up with the analysis of the key elements of the decommissioning plan and the recommendations to the ESS management team..

  15. Design and installation of a hot water layer system at the Tehran research reactor

    Directory of Open Access Journals (Sweden)

    Mirmohammadi Sayedeh Leila

    2013-01-01

    Full Text Available A hot water layer system (HWLS is a novel system for reducing radioactivity under research reactor containment. This system is particularly useful in pool-type research reactors or other light water reactors with an open pool surface. The main purpose of a HWLS is to provide more protection for operators and reactor personnel against undesired doses due to the radio- activity of the primary loop. This radioactivity originates mainly from the induced radioactivity contained within the cooling water or probable minute leaks of fuel elements. More importantly, the bothersome radioactivity is progressively proportional to reactor power and, thus, the HWLS is a partial solution for mitigating such problems when power upgrading is planned. Following a series of tests and checks for different parameters, a HWLS has been built and put into operation at the Tehran research reactor in 2009. It underwent a series of comprehensive tests for a period of 6 months. Within this time-frame, it was realized that the HWLS could provide a better protection for reactor personnel against prevailing radiation under containment. The system is especially suitable in cases of abnormality, e. g. the spread of fission products due to fuel failure, because it prevents the mixing of pollutants developed deep in the pool with the upper layer and thus mitigates widespread leakage of radioactivity.

  16. Study of Pu consumption in advanced light water reactors: Evaluation of GE advanced boiling water reactor plants - compilation of Phase 1B task reports

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1993-09-15

    This report contains an extensive evaluation of GE advanced boiling water reactor plants prepared for United State Department of Energy. The general areas covered in this report are: core and system performance; fuel cycle; infrastructure and deployment; and safety and environmental approval.

  17. 77 FR 41107 - Decommissioning Planning During Operations

    Science.gov (United States)

    2012-07-12

    ...; ] NUCLEAR REGULATORY COMMISSION 10 CFR Parts 20, 30, 40, 50, 70, and 72 Decommissioning Planning During... on revised draft regulatory guide (DG) 4014, ``Decommissioning Planning During Operations.'' This... Decommissioning Planning Rule. The NRC will hold a public meeting and concurrent Webinar to facilitate the public...

  18. Joint US/Russian study on the development of a decommissioning strategy plan for RBMK-1000 unit No. 1 at the Leningrad Nuclear Power Plant

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1997-12-01

    The objective of this joint U.S./Russian study was to develop a safe, technically feasible, economically acceptable strategy for decommissioning Leningrad Nuclear Power Plant (LNPP) Unit No. 1 as a representative first-generation RBMK-1000 reactor. The ultimate goal in developing the decommissioning strategy was to select the most suitable decommissioning alternative and end state, taking into account the socioeconomic conditions, the regulatory environment, and decommissioning experience in Russia. This study was performed by a group of Russian and American experts led by Kurchatov Institute for the Russian efforts and by the Pacific Northwest National Laboratory for the U.S. efforts and for the overall project.

  19. The uncertainty analysis of a liquid metal reactor for burning minor actinides from light water reactors

    Energy Technology Data Exchange (ETDEWEB)

    Choi, Hang Bok [Korea Atomic Energy Research Institute, Taejon (Korea, Republic of)

    1998-12-31

    The neutronics analysis of a liquid metal reactor for burning minor actinides has shown that uncertainties in the nuclear data of several key minor actinide isotopes can introduce large uncertainties in the predicted performance of the core. A comprehensive sensitivity and uncertainty analysis was performed on a 1200 MWth actinide burner designed for a low burnup reactivity swing, negative doppler coefficient, and low sodium void worth. Sensitivities were generated using depletion perturbation methods for the equilibrium cycle of the reactor and covariance data was taken ENDF-B/V and other published sources. The relative uncertainties in the burnup swing, doppler coefficient, and void worth were conservatively estimated to be 180%, 97%, and 46%, respectively. 5 refs., 1 fig., 3 tabs. (Author)

  20. Atmospheric discharges from nuclear facilities during decommissioning: German experiences

    Energy Technology Data Exchange (ETDEWEB)

    Braun, H.; Goertz, R.; Weil, L.

    1997-08-01

    In Germany, a substantial amount of experience is available with planning, licensing and realization of decommissioning projects. In total, a number of 18 nuclear power plants including prototype facilities as well as 6 research reactors and 3 fuel cycle facilities have been shut down finally and are at different stages of decommissioning. Only recently the final {open_quotes}green field{close_quotes} stage of the Niederaichbach Nuclear Power Plant total dismantlement project has been achieved. From the regulatory point of view, a survey of the decommissioning experience in Germany is presented highlighting the aspects of production and retention of airborne radioactivity. Nuclear air cleaning technology, discharge limits prescribed in licences and actual discharges are presented. As compared to operation, the composition of the discharged radioactivity is different as well as the off-gas discharge rate. In practically all cases, there is no significant amount of short-lived radionuclides. The discussion further includes lessons learned, for example inadvertent discharges of radionuclides expected not to be in the plants inventory. It is demonstrated that, as for operation of nuclear power plants, the limits prescribed in the Ordinance on Radiological Protection can be met using existing air cleaning technology, Optimization of protection results in public exposures substantially below the limits. In the frame of the regulatory investigation programme a study has been conducted to assess the airborne radioactivity created during certain decommissioning activities like decontamination, segmentation and handling of contaminated or activated parts. The essential results of this study are presented, which are supposed to support planning for decommissioning, for LWRs, Co-60 and Cs-137 are expected to be the dominant radionuclides in airborne discharges. 18 refs., 2 figs., 1 tab.

  1. 78 FR 78338 - Japan-U.S. Decommissioning and Remediation Fukushima Recovery Forum Tokyo, Japan February 18-19...

    Science.gov (United States)

    2013-12-26

    ... decommissioning, remediation, waste management, and water management. Participate in networking opportunities with... firms and should CS Japan resources be able to accommodate such interest. There may be an opportunity to... company's products or services to the Japanese decommissioning or remediation sector, including water...

  2. High conversion pressurized water reactor with boiling channels

    Energy Technology Data Exchange (ETDEWEB)

    Margulis, M., E-mail: maratm@post.bgu.ac.il [The Unit of Nuclear Engineering, Ben Gurion University of the Negev, POB 653, Beer Sheva 84105 (Israel); Shwageraus, E., E-mail: es607@cam.ac.uk [Department of Engineering, University of Cambridge, CB2 1PZ Cambridge (United Kingdom)

    2015-10-15

    Highlights: • Conceptual design of partially boiling PWR core was proposed and studied. • Self-sustainable Th–{sup 233}U fuel cycle was utilized in this study. • Seed-blanket fuel assembly lattice optimization was performed. • A coupled Monte Carlo, fuel depletion and thermal-hydraulics studies were carried out. • Thermal–hydraulic analysis assured that the design matches imposed safety constraints. - Abstract: Parametric studies have been performed on a seed-blanket Th–{sup 233}U fuel configuration in a pressurized water reactor (PWR) with boiling channels to achieve high conversion ratio. Previous studies on seed-blanket concepts suggested substantial reduction in the core power density is needed in order to operate under nominal PWR system conditions. Boiling flow regime in the seed region allows more heat to be removed for a given coolant mass flow rate, which in turn, may potentially allow increasing the power density of the core. In addition, reduced moderation improves the breeding performance. A two-dimensional design optimization study was carried out with BOXER and SERPENT codes in order to determine the most attractive fuel assembly configuration that would ensure breeding. Effects of various parameters, such as void fraction, blanket fuel form, number of seed pins and their dimensions, on the conversion ratio were examined. The obtained results, for which the power density was set to be 104 W/cm{sup 3}, created a map of potentially feasible designs. It was found that several options have the potential to achieve end of life fissile inventory ratio above unity, which implies potential feasibility of a self-sustainable Thorium fuel cycle in PWRs without significant reduction in the core power density. Finally, a preliminary three-dimensional coupled neutronic and thermal–hydraulic analysis for a single seed-blanket fuel assembly was performed. The results indicate that axial void distribution changes drastically with burnup. Therefore

  3. Light Water Reactor Sustainability Program. Digital Architecture Requirements

    Energy Technology Data Exchange (ETDEWEB)

    Thomas, Kenneth [Idaho National Lab. (INL), Idaho Falls, ID (United States); Oxstrand, Johanna [Idaho National Lab. (INL), Idaho Falls, ID (United States)

    2015-03-01

    The Digital Architecture effort is a part of the Department of Energy (DOE) sponsored Light-Water Reactor Sustainability (LWRS) Program conducted at Idaho National Laboratory (INL). The LWRS program is performed in close collaboration with industry research and development (R&D) programs that provides the technical foundations for licensing and managing the long-term, safe, and economical operation of current nuclear power plants (NPPs). One of the primary missions of the LWRS program is to help the U.S. nuclear industry adopt new technologies and engineering solutions that facilitate the continued safe operation of the plants and extension of the current operating licenses. Therefore, a major objective of the LWRS program is the development of a seamless digital environment for plant operations and support by integrating information from plant systems with plant processes for nuclear workers through an array of interconnected technologies. In order to get the most benefits of the advanced technology suggested by the different research activities in the LWRS program, the nuclear utilities need a digital architecture in place to support the technology. A digital architecture can be defined as a collection of information technology (IT) capabilities needed to support and integrate a wide-spectrum of real-time digital capabilities for nuclear power plant performance improvements. It is not hard to imagine that many processes within the plant can be largely improved from both a system and human performance perspective by utilizing a plant wide (or near plant wide) wireless network. For example, a plant wide wireless network allows for real time plant status information to easily be accessed in the control room, field workers’ computer-based procedures can be updated based on the real time plant status, and status on ongoing procedures can be incorporated into smart schedules in the outage command center to allow for more accurate planning of critical tasks. The goal

  4. Financial and economical aspects for decommissioning of NPP in Germany

    Energy Technology Data Exchange (ETDEWEB)

    Schroeder, A.; Schlingensiepen, D. [RWE Power AG, Corporate Communications, Stuettgenweg 2, 50935 Cologne (Germany)

    2003-07-01

    Commercial use of nuclear power in Germany began with the commissioning of the VAK (Versuchsatomkraftwerk Kahl) in 1961. Since then a total of 32 commercial reactors have been starting production (Former East Germany and West Germany combined). Up to now 13 power-reactors have been permanently shut down. The typical reasons for shut-down can be placed in the following categories: - Commercial: The continued operation of the reactor is no longer economically viable due to its dated technology and/or the necessity of costly re-fitting programmes. A German example of this is the Wuergassen plant where important fixtures of the reactor would have had to be replaced which was considered uneconomic. - Licensing: If the necessary licences for the reactor operation cannot be obtained the operation of the power plant would not be legal and has to be terminated. The Muelheim-Kaerlich plant (RWE) can be quoted as an example of this, where after a long legal struggle the chances for the continuation of plant-operation were estimated to be minuscule. Another example is the shut-down of the Greifswald reactors in the former GDR where legislation decreed that licences issued by the authorities of the former GDR would expire in 1995; - Technical: Technical problems/faults can prohibit the continued operation. This was mainly (in connection with economical factors) the reason for the shut-down of the Niederaichbach plant which occurred in 1974. These reasons can be interconnected: E.g. initially a technical problem occurs, the relevant licensing authority decrees a remedy which would be very costly to implement and subsequently the operator decides that the continued operation of the reactor is commercially no longer viable. In conclusion, decommissioning of Nuclear Power Plants (NPPs) is a reality in Germany. While 19 power reactors are currently operating, 13 have been shut down and are either already completely removed (2), in the process of decommissioning (9), or in safe

  5. Decontamination and Decommissioning activities photobriefing book FY 1997

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1998-04-01

    The Decontamination and Decommissioning (D and D) Program at Argonne National Laboratory-East (ANL-E) is dedicated to the safe and cost effective D{ampersand}D of surplus nuclear facilities. There is currently a backlog of more than 7,000 contaminated US Department of Energy facilities nationwide. Added to this are 110 licensed commercial nuclear power reactors operated by utilities learning to cope with deregulation and an aging infrastructure that supports the commercial nuclear power industry, as well as medical and other uses of radioactive materials. With this volume it becomes easy to understand the importance of addressing the unique issues and objectives associated with the D{ampersand}D of surplus nuclear facilities. This photobriefing book summarizes the decontamination and decommissioning projects and activities either completed or continuing at the ANL-E site during the year.

  6. Graphite-moderated and heavy water-moderated spectral shift controlled reactors; Reactores de moderador solido controlados por desplazamiento espectral

    Energy Technology Data Exchange (ETDEWEB)

    Alcala Ruiz, F.

    1984-07-01

    It has been studied the physical mechanisms related with the spectral shift control method and their general positive effects on economical and non-proliferant aspects (extension of the fuel cycle length and low proliferation index). This methods has been extended to non-hydrogenous fuel cells of high moderator/fuel ratio: heavy water cells have been con- trolled by graphite rods graphite-moderated and gas-cooled cells have been controlled by berylium rods and graphite-moderated and water-cooled cells have been controlled by a changing mixture of heavy and light water. It has been carried out neutron and thermal analysis on a pre design of these types of fuel cells. We have studied its neutron optimization and their fuel cycles, temperature coefficients and proliferation indices. Finally, we have carried out a comparative analysis of the fuel cycles of conventionally controlled PWRs and graphite-moderated, water-cooled and spectral shift controlled reactors. (Author) 71 refs.

  7. European research activities within the project: High Performance Light Water Reactor phase 2 (HPLWR phase 2)

    Energy Technology Data Exchange (ETDEWEB)

    Starflinger, J.; Schulenberg, T. [Forschungszentrum Karlsruhe GmbH, Institute for Nuclear and Energy Technologies, Karlsruhe (Germany); Marsault, P. [CEA Cadarache (DER/SESI), 13 - Saint Paul lez Durance (France). Dept. d' Etudes des Reacteurs; Bittermann, D. [AREVA NP, NEPR-G, Erlangen (Germany); Maraczy, C. [AEKI-KFKI, Budapest (Hungary); Laurien, E. [Stuttgart Univ. IKE (Germany); Lycklama, J.A. [NRG Petten, NL (Netherlands); Anglart, H. [KTH Energy Technology, Stockholm (Sweden); Aksan, N. [Paul Scherrer Institut CH, Villigen PSI (Switzerland); Ruzickova, M. [UJV Rez plc, Husinec-Rez c.p. (Czech Republic); Heikinheimo, L. [VTT, FIN (Finland)

    2007-07-01

    The High Performance Light Water Reactor (HPLWR) is a Light Water Reactor (LWR) operating at supercritical pressure (25 MPa). It belongs to the six reactors currently being investigated under the framework of the Generation IV International Forum. The most visible advantage of the HPLWR shall be the low construction costs in the order of 1000 Euro/kWe, because of size reduction of components and buildings compared to current Light Water Reactors, and the low electricity production costs which are targeted at 3-4 cents/kWh. In Europe, investigations on the HPLWR have been integrated into a joint research project, called High Performance Light Water Reactor Phase 2 (HPLWR Phase 2), which is co-funded by the European Commission. Within 42 months, ten partners from eight European countries working on critical scientific issues shall show the feasibility of the HPLWR concept. This paper reports on 5 points relevant for HPLWR: 1) design and integration, 2) core design, 3) safety, 4) materials, and 5) heat transfer. The final goal is to assess the future potential of this reactor in the electricity market.

  8. Calculation of Radioactivity and Dose Rate of Activated Corrosion Products in Water-Cooled Fusion Reactor

    Directory of Open Access Journals (Sweden)

    Jingyu Zhang

    2016-01-01

    Full Text Available In water-cooled reactor, the dominant radioactive source term under normal operation is activated corrosion products (ACPs, which have an important impact on reactor inspection and maintenance. A three-node transport model of ACPs was introduced into the new version of ACPs source term code CATE in this paper, which makes CATE capable of theoretically simulating the variation and the distribution of ACPs in a water-cooled reactor and suitable for more operating conditions. For code testing, MIT PWR coolant chemistry loop was simulated, and the calculation results from CATE are close to the experimental results from MIT, which means CATE is available and credible on ACPs analysis of water-cooled reactor. Then ACPs in the blanket cooling loop of water-cooled fusion reactor ITER under construction were analyzed using CATE and the results showed that the major contributors are the short-life nuclides, especially Mn-56. At last a point kernel integration code ARShield was coupled with CATE, and the dose rate around ITER blanket cooling loop was calculated. Results showed that after shutting down the reactor only for 8 days, the dose rate decreased nearly one order of magnitude, which was caused by the rapid decay of the short-life ACPs.

  9. Interfacing systems LOCA (loss-of-coolant accidents): Pressurized water reactors

    Energy Technology Data Exchange (ETDEWEB)

    Bozoki, G.; Kohut, P.; Fitzpatrick, R.

    1989-02-01

    This report summarizes a study performed by Brookhaven National Laboratory for the Office of Nuclear Regulatory Research, Reactor and Plant Safety Issues Branch, Division of Reactor and Plant Systems, US Nuclear Regulatory Commission. This study was requested by the NRC in order to provide a technical basis for the resolution of Generic Issue 105 ''Interfacing LOCA at LWRs.'' This report deals with pressurized water reactors (PWRs). A parallel report was also accomplished for boiling water reactors. This study focuses on three representative PWRs and extrapolates the plant-specific findings for their generic applicability. In addition, a generic analysis was performed to investigate the cost-benefit aspects of imposing a testing program that would require some minimum level of leak testing of the pressure isolation valves on plants that presently have no such requirements. 28 refs., 31 figs., 64 tabs.

  10. Probabilistic Structural Integrity Analysis of Boiling Water Reactor Pressure Vessel under Low Temperature Overpressure Event

    Directory of Open Access Journals (Sweden)

    Hsoung-Wei Chou

    2015-01-01

    Full Text Available The probabilistic structural integrity of a Taiwan domestic boiling water reactor pressure vessel has been evaluated by the probabilistic fracture mechanics analysis. First, the analysis model was built for the beltline region of the reactor pressure vessel considering the plant specific data. Meanwhile, the flaw models which comprehensively simulate all kinds of preexisting flaws along the vessel wall were employed here. The low temperature overpressure transient which has been concluded to be the severest accident for a boiling water reactor pressure vessel was considered as the loading condition. It is indicated that the fracture mostly happens near the fusion-line area of axial welds but with negligible failure risk. The calculated results indicate that the domestic reactor pressure vessel has sufficient structural integrity until doubling of the present end-of-license operation.

  11. Searching for full power control rod patterns in a boiling water reactor using genetic algorithms

    Energy Technology Data Exchange (ETDEWEB)

    Montes, Jose Luis [Departamento Sistemas Nucleares, ININ, Carr. Mexico-Toluca Km. 36.5, Ocoyoacac, Edo. de Mexico (Mexico)]. E-mail: jlmt@nuclear.inin.mx; Ortiz, Juan Jose [Departamento Sistemas Nucleares, ININ, Carr. Mexico-Toluca Km. 36.5, Ocoyoacac, Edo. de Mexico (Mexico)]. E-mail: jjortiz@nuclear.inin.mx; Requena, Ignacio [Departamento Ciencias Computacion e I.A. ETSII, Informatica, Universidad de Granada, C. Daniel Saucedo Aranda s/n. 18071 Granada (Spain)]. E-mail: requena@decsai.ugr.es; Perusquia, Raul [Departamento Sistemas Nucleares, ININ, Carr. Mexico-Toluca Km. 36.5, Ocoyoacac, Edo. de Mexico (Mexico)]. E-mail: rpc@nuclear.inin.mx

    2004-11-01

    One of the most important questions related to both safety and economic aspects in a nuclear power reactor operation, is without any doubt its reactivity control. During normal operation of a boiling water reactor, the reactivity control of its core is strongly determined by control rods patterns efficiency. In this paper, GACRP system is proposed based on the concepts of genetic algorithms for full power control rod patterns search. This system was carried out using LVNPP transition cycle characteristics, being applied too to an equilibrium cycle. Several operation scenarios, including core water flow variation throughout the cycle and different target axial power distributions, are considered. Genetic algorithm fitness function includes reactor security parameters, such as MLHGR, MCPR, reactor k{sub eff} and axial power density.

  12. Environmental problems associated with decommissioning the Chernobyl Nuclear Power Plant Cooling Pond.

    Science.gov (United States)

    Oskolkov, B Ya; Bondarkov, M D; Gaschak, S P; Maksymenko, A M; Maksymenko, V M; Martynenko, V I; Farfán, E B; Jannik, G T; Marra, J C

    2010-11-01

    Decommissioning of nuclear power plants and other nuclear fuel cycle facilities associated with residual radioactive contamination of their territories is an imperative issue. Significant problems may result from decommissioning of cooling ponds with residual radioactive contamination. The Chernobyl Nuclear Power Plant (ChNPP) Cooling Pond is one of the largest self-contained water reservoirs in the Chernobyl region and Ukrainian and Belorussian Polesye region. The 1986 ChNPP Reactor Unit Number Four significantly contaminated the ChNPP Cooling Pond. The total radionuclide inventory in the ChNPP Cooling Pond bottom deposits are as follows: ¹³⁷Cs: 16.28 ± 2.59 TBq; ⁹⁰Sr: 2.4 ± 0.48 TBq; and ²³⁹+²⁴⁰Pu: 0.00518 ± 0.00148 TBq. The ChNPP Cooling Pond is inhabited by over 500 algae species and subspecies, over 200 invertebrate species, and 36 fish species. The total mass of the living organisms in the ChNPP Cooling Pond is estimated to range from about 60,000 to 100,000 tons. The territory adjacent to the ChNPP Cooling Pond attracts many birds and mammals (178 bird species and 47 mammal species were recorded in the Chernobyl Exclusion Zone). This article describes several options for the ChNPP Cooling Pond decommissioning and environmental problems associated with its decommissioning. The article also provides assessments of the existing and potential exposure doses for the shoreline biota. For the 2008 conditions, the estimated total dose rate values were 11.4 40 μGy h⁻¹ for amphibians, 6.3 μGy h⁻¹ for birds, 15.1 μGy h⁻¹ for mammals, and 10.3 μGy h⁻¹ for reptiles, with the recommended maximum dose rate being equal to 40 μGy h⁻¹. However, drying the ChNPP Cooling Pond may increase the exposure doses to 94.5 μGy h⁻¹ for amphibians, 95.2 μGy h⁻¹ for birds, 284.0 μGy h⁻¹ for mammals, and 847.0 μGy h⁻¹ for reptiles. All of these anticipated dose rates exceed the recommended values.

  13. Decommissioning Study of Oskarshamn NPP

    Energy Technology Data Exchange (ETDEWEB)

    Larsson, Helena; Anunti, Aake; Edelborg, Mathias [Westinghouse Electric Sweden AB, Vaesteraas (Sweden)

    2013-06-15

    By Swedish law it is the obligation of the nuclear power utilities to satisfactorily demonstrate how a nuclear power plant can be safely decommissioned and dismantled when it is no longer in service as well as calculate the estimated cost of decommissioning of the nuclear power plant. Svensk Kaernbraenslehantering AB (SKB) has been commissioned by the Swedish nuclear power utilities to meet the requirements of current legislation by studying and reporting on suitable technologies and by estimating the costs of decommissioning and dismantling of the Swedish nuclear power plants. The present report is an overview, containing the necessary information to meet the above needs, for Oskarshamn NPP. Information is given for the plant about the inventory of materials and radioactivity at the time for final shutdown. A feasible technique for dismantling is presented and the waste management is described and the resulting waste quantities are estimated. Finally a schedule for the decommissioning phase is given and the costs associated are estimated as a basis for funding.

  14. Decommissioning study of Forsmark NPP

    Energy Technology Data Exchange (ETDEWEB)

    Anunti, Aake; Larsson, Helena; Edelborg, Mathias [Westinghouse Electric Sweden AB, Vaesteraas (Sweden)

    2013-06-15

    By Swedish law it is the obligation of the nuclear power utilities to satisfactorily demonstrate how a nuclear power plant can be safely decommissioned and dismantled when it is no longer in service as well as calculate the estimated cost of decommissioning of the nuclear power plant. Svensk Kaernbraenslehantering AB (SKB) has been commissioned by the Swedish nuclear power utilities to meet the requirements of current legislation by studying and reporting on suitable technologies and by estimating the costs of decommissioning and dismantling of the Swedish nuclear power plants. The present report is an overview, containing the necessary information to meet the above needs, for the Forsmark NPP. Information is given for the plant about the inventory of materials and radioactivity at the time for final shutdown. A feasible technique for dismantling is presented and the waste management is described and the resulting waste quantities are estimated. Finally a schedule for the decommissioning phase is given and the costs associated are estimated as a basis for funding.

  15. Study on the Use of Hydride Fuel in High-Performance Light Water Reactor Concept

    OpenAIRE

    Haileyesus Tsige-Tamirat; Luca Ammirabile

    2015-01-01

    Hydride fuels have features which could make their use attractive in future advanced power reactors. The potential benefit of use of hydride fuel in HPLWR without introducing significant modification in the current core design concept of the high-performance light water reactor (HPLWR) has been evaluated. Neutronics and thermal hydraulic analyses were performed for a single assembly model of HPLWR with oxide and hydride fuels. The hydride assembly shows higher moderation with softer neutron s...

  16. Recommended values for the distribution coefficient (Kd) to be used in dose assessments for decommissioning the Zion Nuclear Power Plant

    Energy Technology Data Exchange (ETDEWEB)

    Sullivan, T. [Brookhaven National Lab. (BNL), Upton, NY (United States)

    2014-09-24

    ZionSolutions is in the process of decommissioning the Zion Nuclear Power Plant. The site contains two reactor Containment Buildings, a Fuel Building, an Auxiliary Building, and a Turbine Building that may be contaminated. The current decommissioning plan involves removing all above grade structures to a depth of 3 feet below grade. The remaining underground structures will be backfilled. The remaining underground structures will contain low amounts of residual licensed radioactive material. An important component of the decommissioning process is the demonstration that any remaining activity will not cause a hypothetical individual to receive a dose in excess of 25 mrem/y as specified in 10CFR20 SubpartE.

  17. Recommended values for the distribution coefficient (Kd) to be used in dose assessments for decommissioning the Zion Nuclear Power Plant

    Energy Technology Data Exchange (ETDEWEB)

    Sullivan T.

    2014-06-09

    ZionSolutions is in the process of decommissioning the Zion Nuclear Power Plant. The site contains two reactor Containment Buildings, a Fuel Building, an Auxiliary Building, and a Turbine Building that may be contaminated. The current decommissioning plan involves removing all above grade structures to a depth of 3 feet below grade. The remaining underground structures will be backfilled. The remaining underground structures will contain low amounts of residual licensed radioactive material. An important component of the decommissioning process is the demonstration that any remaining activity will not cause a hypothetical individual to receive a dose in excess of 25 mrem/y as specified in 10CFR20 SubpartE.

  18. IRIS Reactor a Suitable Option to Provide Energy and Water Desalination for the Mexican Northwest Region

    Energy Technology Data Exchange (ETDEWEB)

    Alonso, G.; Ramirez, R.; Gomez, C.; Viais, J.

    2004-10-03

    The Northwest region of Mexico has a deficit of potable water, along this necessity is the region growth, which requires of additional energy capacity. The IRIS reactor offers a very suitable source of energy given its modular size of 300 MWe and it can be coupled with a desalination plant to provide the potable water for human consumption, agriculture and industry. The present paper assess the water and energy requirements for the Northwest region of Mexico and how the deployment of the IRIS reactor can satisfy those necessities. The possible sites for deployment of Nuclear Reactors are considered given the seismic constraints and the closeness of the sea for external cooling. And in the other hand, the size of the desalination plant and the type of desalination process are assessed accordingly with the water deficit of the region.

  19. Robust observer based control for axial offset in pressurized-water nuclear reactors based on the multipoint reactor model using Lyapunov approach

    Energy Technology Data Exchange (ETDEWEB)

    Zaidabadinejad, Majid; Ansarifar, Gholam Reza [Isfahan Univ. (Iran, Islamic Republic of). Dept. of Nuclear Engineering

    2017-11-15

    In nuclear reactor imbalance of axial power distribution induces xenon oscillations. These fluctuations must be maintained bounded within allowable limits. Otherwise, the nuclear power plant could become unstable. Therefore, bounded these oscillations is considered to be a restriction for the load following operation. Also, in order to design the nuclear reactor control systems, poisons concentrations, especially xenon must be accessible. But, physical measurement of these parameters is impossible. In this paper, for the first time, in order to estimate the axial xenon oscillations and ensures these oscillations are kept bounded within allowable limits during load-following operation, a robust observer based nonlinear control based on multipoint kinetics reactor model for pressurized-water nuclear reactors is presented. The reactor core is simulated based on the multi-point nuclear reactor model (neutronic and thermal-hydraulic). Simulation results are presented to demonstrate the effectiveness of the proposed observer based controller for the load-following operation.

  20. THE INFLUENCE OF MIEX® RESIN FOR WATER TREATMENT EFFICIENCYIN A HYBRID MEMBRANE REACTOR

    Directory of Open Access Journals (Sweden)

    Mariola Rajca

    2014-10-01

    Full Text Available The paper presents the results of studies related to the effectiveness of removal of natural organic matter (NOM from water using hybrid membrane reactor in which ion exchange and ultrafiltration processes were performed. MIEX® resin by Orica Watercare and immersed ultrafiltration polyvinylidene fluoride capillary module ZeeWeed 1 (ZW 1 by GE Power&Water operated at negative pressure were used. The application of multifunctional reactor had a positive effect on the removal of contaminants and enabled the production of high quality water. Additionally, in refer to single stage ultrafiltration it minimalized the occurrence of membrane fouling.

  1. Water distribution in a sorption enhanced methanation reactor by time resolved neutron imaging.

    Science.gov (United States)

    Borgschulte, A; Delmelle, R; Duarte, R B; Heel, A; Boillat, P; Lehmann, E

    2016-06-29

    Water adsorption enhanced catalysis has been recently shown to greatly increase the conversion yield of CO2 methanation. However, the joint catalysis and adsorption process requires new reactor concepts. We measured the spatial water distribution in a model fixed bed reactor using time resolved neutron imaging. Due to the high neutron attenuation coefficient of hydrogen, the absorbed water in the sorption catalyst gives a high contrast allowing us to follow its formation and map its distribution. At the same time, the product gas was analysed by FTIR-gas analysis. The measurements provided crucial insights into the future design of sorption reactors: during the sorption enhanced reaction, a reaction front runs through the reactor. Once the extension of the reaction front reaches the exhaust, the conversion rate of sorption enhanced methanation decreases. The existence of a reaction front running through the reactor is prerequisite for a high conversion rate. We give a simple model of the experimental results, in particular the conditions, under which a reaction front is established. In particular the latter effect must be taken into account for the dimensions of a large scale reactor.

  2. Reconstructing the direction of reactor antineutrinos via electron scattering in Gd-doped water Cherenkov detectors

    Energy Technology Data Exchange (ETDEWEB)

    Hellfeld, D. [Univ. of California, Berkeley, CA (United States). Dept. of Nuclear Engineering; Bernstein, A. [Lawrence Livermore National Lab. (LLNL), Livermore, CA (United States); Dazeley, S. [Lawrence Livermore National Lab. (LLNL), Livermore, CA (United States); Marianno, C. [Texas A & M Univ., College Station, TX (United States). Dept. of Nuclear Engineering

    2017-01-01

    The potential of elastic antineutrino-electron scattering (ν¯e + e → ν¯e + e) in a Gd-doped water Cherenkov detector to determine the direction of a nuclear reactor antineutrino flux was investigated using the recently proposed WATCHMAN antineutrino experiment as a baseline model. The expected scattering rate was determined assuming a 13 km standoff from a 3.758 GWt light water nuclear reactor. Background was estimated via independent simulations and by appropriately scaling published measurements from similar detectors. Many potential backgrounds were considered, including solar neutrinos, misidentified reactor-based inverse beta decay interactions, cosmogenic radionuclide and water-borne radon decays, and gamma rays from the photomultiplier tubes, detector walls, and surrounding rock. The detector response was modeled using a GEANT4-based simulation package. The results indicate that with the use of low radioactivity PMTs and sufficient fiducialization, water-borne radon and cosmogenic radionuclides pose the largest threats to sensitivity. The directional sensitivity was then analyzed as a function of radon contamination, detector depth, and detector size. Lastly, the results provide a list of theoretical conditions that, if satisfied in practice, would enable nuclear reactor antineutrino directionality in a Gd-doped water Cherenkov detector approximately 10 km from a large power reactor.

  3. UV disinfection of indigenous aerobic spores: implications for UV reactor validation in unfiltered waters.

    Science.gov (United States)

    Mamane-Gravetz, Hadas; Linden, Karl G

    2004-07-01

    Conventional validation testing of UV reactors use cultured microorganisms spiked into test water flowing through a reactor. These tests are limited by the microbe titer it is possible to grow, thus limiting the size of the reactor it is possible to validate. The goal of this study was to examine the UV inactivation of indigenous aerobic spores naturally occurring in raw/unfiltered water supplies and to assess their use as an alternative indicator for validation testing of UV reactor performance, specifically for unfiltered water supplies planning large UV reactors. These spores were found in all raw waters tested in concentrations ranging between 20 and 12,000 CFU/100 mL and were very resistant to UV irradiation compared to a range of different microbes in the literature (i.e. adenovirus, MS-2 coliphage, and Cryptosporidium parvum). The inactivation of indigenous natural aerobic spores followed first-order kinetics with an inactivation coefficient ranging between 0.013 and 0.022 cm2/mJ with a high correlation coefficient. It was determined that naturally occurring aerobic spores, well characterized with respect to UV 253.7 nm inactivation, can be a useful tool when validating plant performance, and might also be used as a regular monitor of UV fluence and performance in a water treatment plant.

  4. Nuclear reactor with makeup water assist from residual heat removal system

    Science.gov (United States)

    Corletti, Michael M.; Schulz, Terry L.

    1993-01-01

    A pressurized water nuclear reactor uses its residual heat removal system to make up water in the reactor coolant circuit from an in-containment refueling water supply during staged depressurization leading up to passive emergency cooling by gravity feed from the refueling water storage tank, and flooding of the containment building. When depressurization commences due to inadvertence or a manageable leak, the residual heat removal system is activated manually and prevents flooding of the containment when such action is not necessary. Operation of the passive cooling system is not impaired. A high pressure makeup water storage tank is coupled to the reactor coolant circuit, holding makeup coolant at the operational pressure of the reactor. The staged depressurization system vents the coolant circuit to the containment, thus reducing the supply of makeup coolant. The level of makeup coolant can be sensed to trigger opening of successive depressurization conduits. The residual heat removal pumps move water from the refueling water storage tank into the coolant circuit as the coolant circuit is depressurized, preventing reaching the final depressurization stage unless the makeup coolant level continues to drop. The residual heat removal system can also be coupled in a loop with the refueling water supply tank, for an auxiliary heat removal path.

  5. Removing 17β-estradiol from drinking water in a biologically active carbon (BAC) reactor modified from a granular activated carbon (GAC) reactor.

    Science.gov (United States)

    Li, Zhongtian; Dvorak, Bruce; Li, Xu

    2012-06-01

    Estrogenic compounds in drinking water sources pose potential threats to human health. Treatment technologies are needed to effectively remove these compounds for the production of safe drinking water. In this study, GAC adsorption was first tested for its ability to remove a model estrogenic compound, 17β-estradiol (E2). Although GAC showed a relatively high adsorption capacity for E2 in isotherm experiments, it appeared to have a long mass transfer zone in a GAC column reactor, causing an early leakage of E2 in the effluent. With an influent E2 concentration of 20 μg/L, the GAC reactor was able to bring down effluent E2 to ≈ 200 ng/L. To further enhance E2 removal, the GAC reactor was converted to a biologically active carbon (BAC) reactor by promoting biofilm growth in the reactor. Under optimal operating conditions, the BAC reactor had an effluent E2 concentration of ≈ 50 ng/L. With the empty bed contact times tested, the reactor exhibited more robust E2 removal performance under the BAC operation than under the GAC operation. It is noted that estrone (E1), an E2 biodegradation intermediate, was frequently detected in reactor effluent during the BAC operation. Results from this study suggested that BAC could be an effective drinking water treatment process for E2 removal and in the meantime E1 accumulation needs to be addressed. Published by Elsevier Ltd.

  6. 76 FR 23339 - Notice of Issuance of License Amendment Regarding Decommission Plan Approval; University of...

    Science.gov (United States)

    2011-04-26

    ... Arizona Research Reactor The U.S. Nuclear Regulatory Commission (NRC) has issued the approval of the University of Arizona decommissioning plan (DP) by amendment to the Facility License R-52 for the University... From the Federal Register Online via the Government Publishing Office NUCLEAR REGULATORY...

  7. Guidance for Developing Principal Design Criteria for Advanced (Non-Light Water) Reactors

    Energy Technology Data Exchange (ETDEWEB)

    Holbrook, Mark [Idaho National Lab. (INL), Idaho Falls, ID (United States); Kinsey, Jim [Idaho National Lab. (INL), Idaho Falls, ID (United States)

    2015-03-01

    In July 2013, the US Department of Energy (DOE) and US Nuclear Regulatory Commission (NRC) established a joint initiative to address a key portion of the licensing framework essential to advanced (non-light water) reactor technologies. The initiative addressed the “General Design Criteria for Nuclear Power Plants,” Appendix A to10 Code of Federal Regulations (CFR) 50, which were developed primarily for light water reactors (LWRs), specific to the needs of advanced reactor design and licensing. The need for General Design Criteria (GDC) clarifications in non-LWR applications has been consistently identified as a concern by the industry and varied stakeholders and was acknowledged by the NRC staff in their 2012 Report to Congress1 as an area for enhancement. The initiative to adapt GDC requirements for non-light water advanced reactor applications is being accomplished in two phases. Phase 1, managed by DOE, consisted of reviews, analyses and evaluations resulting in recommendations and deliverables to NRC as input for NRC staff development of regulatory guidance. Idaho National Laboratory (INL) developed this technical report using technical and reactor technology stakeholder inputs coupled with analysis and evaluations provided by a team of knowledgeable DOE national laboratory personnel with input from individual industry licensing consultants. The DOE national laboratory team reviewed six different classes of emerging commercial reactor technologies against 10 CFR 50 Appendix A GDC requirements and proposed guidance for their adapted use in non-LWR applications. The results of the Phase 1 analysis are contained in this report. A set of draft Advanced Reactor Design Criteria (ARDC) has been proposed for consideration by the NRC in the establishment of guidance for use by non-LWR designers and NRC staff. The proposed criteria were developed to preserve the underlying safety bases expressed by the original GDC, and recognizing that advanced reactors may take

  8. Design optimization of metal getter reactors for removing tritium from flowing gas streams

    Energy Technology Data Exchange (ETDEWEB)

    Nobile, A.; Bieniewski, T.; Frame, K.; Little, R.; Fisher, K. [Los Alamos National Lab., NM (United States)

    1995-10-01

    A reaction engineering approach was used to design a SAES St 198 metal getter reactor for a glovebox detritiation system. The detritiation system will be used to decontaminate and decommission an Li(D, T)-contaminated glovebox previously used in the U.S. nuclear weapons program. The approach involved development of a model that calculates reactor breakthrough curves as a function of various reactor physical parameters. Experiments involving flow of deuterium in nitrogen through a small metal getter reactor validated the model. The model was then used to investigate the effects of temperature, getter pellet size, reactor diameter, and reactor volume on the reactor performance. The resulting design was a 7 cm diam. by 40 cm long cylindrical reactor that operates at 250 {degree}C, and is filled with 5 kg of as-received SAES St 198 getter pellets. The reactor handles a flow rate of 100 L/min. An St 909 getter reactor was used upstream of the St 198 reactor for impurity removal and water decomposition. The glovebox cleanup system design and getter reactor mechanical design are discussed. 14 refs., 6 figs.

  9. Physical aspects of the Canadian generation IV supercritical water-cooled pressure tube reactor plant design

    Energy Technology Data Exchange (ETDEWEB)

    Gaudet, M.; Yetisir, M.; Haque, Z. [Atomic Energy of Canada Limited, Chalk River, ON (Canada)

    2014-07-01

    The form of the containment building is a function of the requirements imposed by various systems. In order to provide sufficient driving force for naturally-circulated emergency cooling systems, as well as providing a gravity-driven core flooding pool function, the Canadian SCWR reactor design relies on elevation differences between the reactor and the safety systems. These elevation differences, the required cooling pool volumes and the optimum layout of safety-related piping are major factors influencing the plant design. As a defence-in-depth, the containment building and safety systems also provide successive barriers to the unplanned release of radioactive materials, while providing a path for heat flow to the ultimate heat sink, the atmosphere. Access to the reactor for refuelling is from the top of the reactor, with water used as shielding during the refuelling operations. The accessibility to the reactor and protection of the environment are additional factors influencing the plant design. This paper describes the physical implementation of the major systems of the Canadian SCWR within the reactor building, and the position of major plant services relative to the reactor building. (author)

  10. Prediction of Reactor Vessel Water Level Using Fuzzy Neural Networks in Severe Accidents due to LOCA

    Energy Technology Data Exchange (ETDEWEB)

    Park, Soonho; Kim, Jaehawn; Na, Mangyun [Chosun Univ., Gwangju (Korea, Republic of)

    2013-05-15

    When the initial events that may lead to the severe accident such as Loss Of Coolant Accident (LOCA) and Steam Generator Tube Rupture (SGTR) occurs at a nuclear power plant, it is most important to check the status of the plant conditions by observing the safety-related parameters such as neutron flux, pressurizer pressure, steam generator pressure and water level. In this paper, we propose a method of predicting the water level of coolant in the reactor vessel that directly affect the important events such as the exposure of the reactor core and the damage of reactor vessel by using a Fuzzy Neural Network (FNN) method. In addition, the data for verifying a proposed model was obtained by simulating the severe accident scenarios for the OPR1000 nuclear power plant using the MAAP4 code. In this paper, a prediction model was developed for predicting the reactor vessel water level using the FNN method. The proposed FNN model was verified based on the simulation data of OPR1000 by using MAAP4 code. As a result of simulation, we could see that the performance of the proposed FNN model is quite satisfactory but some large errors are observed occasionally. If the proposed FNN model is optimized by using a variety of data, it is possible to predict the reactor vessel water level exactly.

  11. Experience on decommissioning commercial nuclear power stations in the United Kingdom

    Energy Technology Data Exchange (ETDEWEB)

    Holt, G.; Lee, J.C.; Woollam, P.B. [Magnox Electric plc, Gloucestershire (United Kingdom)

    1996-12-31

    Magnox Electric is the U.K. government-owned utility that is responsible for nine commercial Magnox nuclear power stations. The stations were commissioned between 1962 and 1971, each having twin gas-cooled, graphite-moderated reactors. Three stations (Berkeley, Hunterston A, and Trawsfynydd) were shut down between 1989 and 1993, and they are being decommissioned in accordance with the preferred SAFSTOR strategy. The six reactors have been defueled, and extensive dismantling and decontamination have already been carried out.

  12. Anaerobic Treatment of Concentrated Black Water in a UASB Reactor at a Short HRT

    Directory of Open Access Journals (Sweden)

    Cees J. N. Buisman

    2010-02-01

    Full Text Available This research describes the feasibility of applying a UASB reactor for the treatment of concentrated black (toilet water at 25 °C. On average 78% of the influent load of COD at an HRT of 8.7 days was removed. Produced methane can be converted to 56 MJ/p/y as electricity and 84 MJ/p/y as heat by combined heat and power (CHP. Minimum reactor volume at full scale was calculated to be 63L per person (for black water containing 16 gCOD/L produced at 5 L/p/d and this is more than two times smaller than other type of reactors for anaerobic treatment of concentrated black water.

  13. OECD - HRP Summer School on Light Water Reactor Structural Materials. August 26th - 30th, 2002

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2002-07-01

    In cooperation with the OECD Nuclear Energy Agency (NEA), the Halden Reactor Project organised a Summer School on Light Water Reactor Structural Materials in the period August 26 - 30, 2002. The summer school was primarily intended for people who wanted to become acquainted with materials-related subjects and issues without being experts. It is especially hoped that the summer school served to transfer knowledge to the ''young generation'' in the field of nuclear. Experts from Halden Project member organisations were solicited for the following programme: (1) Overview of The Nuclear Community and Current Issues, (2) Regulatory Framework for Ensuring Structural Integrity, (3) Non-Destructive Testing for Detection of Cracks, (4) Part I - Basics of Radiation and Radiation Damage, (5) Part II - Radiation Effects on Reactor Internal Materials, (6) Water Chemistry and Radiolysis Effects in LWRs, (7) PWR and Fast Breeder Reactor Internals, (8) PWR and Fast Breeder Reactor Internals, (9) Secondary Side Corrosion Cracking of PWR Steam Generator Tubes, (10) BWR Materials and Their Interaction with the Environment, (11) Radiation Damage in Reactor Pressure Vessels.

  14. Decommissioning of the nuclear facilities at Risø National Laboratory. Descriptions and cost assessment

    DEFF Research Database (Denmark)

    Lauridsen, K.

    2001-01-01

    The report is the result of a project initiated by Risø National Laboratory in June 2000 on request from the Minister of Research and Information Technology. It describes the nuclear facilities at Risø National Laboratory to be decommissioned and gives anassessment of the work to be done and the ......The report is the result of a project initiated by Risø National Laboratory in June 2000 on request from the Minister of Research and Information Technology. It describes the nuclear facilities at Risø National Laboratory to be decommissioned and gives anassessment of the work to be done...... and the costs incurred. Three decommissioning scenarios were considered with decay times of 10, 25 and 40 years for the DR 3 reactor. The assessments conclude, however, that there will not be much to gain by allowing forthe longer decay periods; some operations still will need to be performed remotely....... Furthermore, the report describes some of the legal and licensing framework for the decommissioning and gives an assessment of the amounts of radioactive waste to betransferred to a Danish repository. For a revision of the cost estimate for the decommissioning of the research Reactor DR 3 please consult...

  15. Applicability of a multivariable autoregressive method to boiling water reactor core stability estimation

    Energy Technology Data Exchange (ETDEWEB)

    Suzuki, S.; Fukunishi, K.; Kishi, S.; Yoshimoto, Y.; Kishimoto, K.

    1986-08-01

    A multivariable autoregressive (MAR) method is applied to the core stability estimation of a boiling water reactor-5 operation. Noise data measured during steady-state operations at startup tests are used. In this method, the closed loop transfer function from reactor pressure to reactor power is identified from reactor noise data and transformed into an impulse response function. The decay ratio representing stability characteristics is evaluated from this function. The variation range of decay ratio estimates obtained by this method is sufficiently small, if the analyzing conditions are appropriately selected. The value of the decay ratio is 0.23 during natural circulation and decreases with core flow, reaching close to zero at the rated power. A similar power dependence for the decay ratio is seen in results from a core stability analysis code. The MAR method is a useful tool for stability estimation, even if no external disturbance tests are conducted.

  16. An economic optimization of pressurized light water reactor cores

    Science.gov (United States)

    Pfeifer, Holger

    Two reactor cores (1000 MWe and 600 MWe) are optimized with respect to power cost. The power cost is minimized while retaining the thermal-hydraulic margins of the reference core. Constant thermal-hydraulic margins result in similar accident thermal-hydraulic transient behavior of the cores developed during the optimization study. The cost components impacted by the optimization are once-through fuel cycle, capital, and administrative/manpower costs. The variables in the optimization are pin diameter, moderator to fuel (H/U) ratio, core length, and the number of fuel pins in the core. A sequential quadratic programming approach is employed to solve the nonlinear optimization problem with constraints. The fuel cycle costs are evaluated by the use of the linear reactivity model, and capital costs are adjusted by suitable modifications to the nuclear energy cost database reference costs. The results of the analysis shows that for fixed assembly parameters (i.e., pin diameter, H/U ratio, and core length), the optimum core is one that operates at the thermal-hydraulic limits. Cores optimized with unconstrained assembly characteristics contain a larger number of smaller pins at a higher H/U ratio. This follows the trend in current reactor designs. While the lifetime power cost savings for the optimized core are less than 4 million dollars (versus a present day total cost of 6.9 billion dollars), the optimization analysis shows that higher thermal-hydraulic margins can be attained with minimum power cost increases. With increased emphasis on reactor safety, significantly higher safety margins may therefore be achieved without a significant power cost increase. The optimized configurations were found to be relatively insensitive to fuel cycle cost component variations.

  17. Core Flow Distribution from Coupled Supercritical Water Reactor Analysis

    Directory of Open Access Journals (Sweden)

    Po Hu

    2014-01-01

    Full Text Available This paper introduces an extended code package PARCS/RELAP5 to analyze steady state of SCWR US reference design. An 8 × 8 quarter core model in PARCS and a reactor core model in RELAP5 are used to study the core flow distribution under various steady state conditions. The possibility of moderator flow reversal is found in some hot moderator channels. Different moderator flow orifice strategies, both uniform across the core and nonuniform based on the power distribution, are explored with the goal of preventing the reversal.

  18. Franco-German nuclear cooperation: from the `common product` to the first European pressurized water reactor

    Energy Technology Data Exchange (ETDEWEB)

    Vignon, D. [Societe Franco-Americaine de Constructions Atomiques (FRAMATOME), 92 - Paris-la-Defense (France)

    1999-01-01

    It has now been 10 years since Framatome and Siemens decided to collaborate on the design and sales of an advanced nuclear power plant (NPP) model based on pressurized water reactor (PWR) technology. Originally called the `common product`, this model was renamed the European pressurized water reactor when Electricite de France (EDF) and the German electric utilities joined this cooperative development effort in 1992. Since the beginning, this cooperation has been formalized in the framework of an agreement that led to the founding of a joint and equally owned subsidiary, Nucler Power International (NPI), which is reponsible for leading the development of the new model and later handling its export sales.

  19. Local stability tests in Dresden 2 boiling water reactor

    Energy Technology Data Exchange (ETDEWEB)

    March-Leuba, J.; Fry, D.N.; Buchanan, M.E.; McNew, C.O.

    1984-04-01

    This report presents the results of a local stability test performed at Dresden Unit 2 in May 1983 to determine the effect of a new fuel element design on local channel stability. This test was performed because the diameter of the new fuel rods increases the heat transfer coefficient, making the reactor more responsive and, thus, more susceptible to instabilities. After four of the new fuel elements with a 9 x 9 array of fuel rods were loaded into Dresden 2, the test was performed by inserting an adjacent control rod all the way in and then withdrawing it to its original position at maximum speed. At the moment of the test, reactor conditions were 52.7% power and 38.9% flow. Both the new 9 x 9 fuel elements and the standard 8 x 8 ones proved to be locally stable when operating at minimum pump speed at the beginning of cycle in Dresden 2, and no significant difference was found between the behavior of the two fuel types. Finally, Dresden 2 showed a high degree of stability during control rod and normal noise type perturbations.

  20. On the study of catalytic membrane reactor for water detritiation: Modeling approach

    Energy Technology Data Exchange (ETDEWEB)

    Liger, Karine, E-mail: karine.liger@cea.fr [CEA, DEN, DTN/SMTA/LIPC Cadarache, Saint Paul-lez-Durance F-13108 (France); Mascarade, Jérémy [CEA, DEN, DTN/SMTA/LIPC Cadarache, Saint Paul-lez-Durance F-13108 (France); Joulia, Xavier; Meyer, Xuan-Mi [Université de Toulouse, INPT, UPS, Laboratoire de Génie Chimique, 4, Allée Emile Monso, Toulouse F-31030 (France); CNRS, Laboratoire de Génie Chimique, Toulouse F-31030 (France); Troulay, Michèle; Perrais, Christophe [CEA, DEN, DTN/SMTA/LIPC Cadarache, Saint Paul-lez-Durance F-13108 (France)

    2016-11-01

    Highlights: • Experimental results for the conversion of tritiated water (using deuterium as a simulant of tritium) by means of a catalytic membrane reactor in view of tritium recovery. • Phenomenological 2D model to represent catalytic membrane reactor behavior including the determination of the compositions of gaseous effluents. • Good agreement between the simulation results and experimental measurements performed on the dedicated facility. • Explanation of the unexpected behavior of the catalytic membrane reactor by the modeling results and in particular the gas composition estimation. - Abstract: In the framework of tritium recovery from tritiated water, efficiency of packed bed membrane reactors have been successfully demonstrated. Thanks to protium isotope swamping, tritium bonded water can be recovered under the valuable Q{sub 2} form (Q = H, D or T) by means of isotope exchange reactions occurring on catalyst surface. The use of permselective Pd-based membrane allows withdrawal of reactions products all along the reactor, and thus limits reverse reaction rate to the benefit of the direct one (shift effect). The reactions kinetics, which are still little known or unknown, are generally assumed to be largely greater than the permeation ones so that thermodynamic equilibriums of isotope exchange reactions are generally assumed. This paper proposes a new phenomenological 2D model to represent catalytic membrane reactor behavior with the determination of gas effluents compositions. A good agreement was obtained between the simulation results and experimental measurements performed on a dedicated facility. Furthermore, the gas composition estimation permits to interpret unexpected behavior of the catalytic membrane reactor. In the next future, further sensitivity analysis will be performed to determine the limits of the model and a kinetics study will be conducted to assess the thermodynamic equilibrium of reactions.

  1. The global perspective on decommissioning

    Energy Technology Data Exchange (ETDEWEB)

    Griffin, W.S. [Phillips Petroleum Company, Bartlesville (United States)

    1996-12-31

    An analysis of the issues connected to decommissioning of offshore structures for the oil and gas industry is presented. A brief historical note precedes a country by country review of the extent of the problem and plans of action. A personal interpretation is also given of the London Convention concerning a moratorium on sea disposal of platforms. Continued dialogue and a commitment to regulatory decisions based on sound science are urged to facilitate a solution. (UK)

  2. Nuclear decommissioning planning, execution and international experience

    CERN Document Server

    2012-01-01

    A title that critically reviews the decommissioning and decontamination processes and technologies available for rehabilitating sites used for nuclear power generation and civilian nuclear facilities, from fundamental issues and best practices, to procedures and technology, and onto decommissioning and decontamination case studies.$bOnce a nuclear installation has reached the end of its safe and economical operational lifetime, the need for its decommissioning arises. Different strategies can be employed for nuclear decommissioning, based on the evaluation of particular hazards and their attendant risks, as well as on the analysis of costs of clean-up and waste management. This allows for decommissioning either soon after permanent shutdown, or perhaps a long time later, the latter course allowing for radioactivity levels to drop in any activated or contaminated components. It is crucial for clear processes and best practices to be applied in decommissioning such installations and sites, particular where any ...

  3. Severe water ingress accident analysis for a Modular High Temperature Gas Cooled Reactor

    Energy Technology Data Exchange (ETDEWEB)

    Zhang Zuoyi [Inst. of Nuclear Energy Technology Tsinghua Univ., Beijing, BJ (China); Scherer, Winfried

    1997-12-31

    This paper analyzes the severe water ingress accidents in the SIEMENS 200MW Modular High Temperature Gas Cooled Reactor (HTR-Module) under the assumption of no active safety protection systems in order to find the safety margin of the current HTR-Module design. A water, steam and helium multi-phase cavity model is originally developed and implemented in the DSNP simulation system. The developed DSNP system is used to simulate the primary circuit of HTR-Module power plant. The comparisons of the models with the TINTE calculations validate the current simulation. After analyzing the effects of blower separation on water droplets, the wall heat storage, etc., it is found that the maximum H{sub 2}O density increase rate in the reactor core is smaller than 0.3 kg/(m{sup 3}s). The liquid water vaporization in the steam generator and H{sub 2}O transport from the steam generator to the reactor core reduces the impulse of the H{sub 2}O in the reactor core. The nuclear reactivity increase caused by the water ingress leads to a fast power excursion, which, however, is inherently counterbalanced by negative feedback effects. Concerning the integrity of the fuel elements, the safety relevant temperature limit of 1600degC was not reached in any case. (author)

  4. Reconstructing the direction of reactor antineutrinos via electron scattering in Gd-doped water Cherenkov detectors

    Energy Technology Data Exchange (ETDEWEB)

    Hellfeld, D., E-mail: dhellfeld@berkeley.edu [Department of Nuclear Engineering, University of California, Berkeley, Berkeley, CA 94720 (United States); Bernstein, A. [Lawrence Livermore National Laboratory, Livermore, CA 94550 (United States); Dazeley, S., E-mail: dazeley2@llnl.gov [Lawrence Livermore National Laboratory, Livermore, CA 94550 (United States); Marianno, C. [Department of Nuclear Engineering, Texas A& M University, College Station, TX 77843 (United States)

    2017-01-01

    The potential of elastic antineutrino-electron scattering in a Gd-doped water Cherenkov detector to determine the direction of a nuclear reactor antineutrino flux was investigated using the recently proposed WATCHMAN antineutrino experiment as a baseline model. The expected scattering rate was determined assuming a 13-km standoff from a 3.758-GWt light water nuclear reactor and the detector response was modeled using a Geant4-based simulation package. Background was estimated via independent simulations and by scaling published measurements from similar detectors. Background contributions were estimated for solar neutrinos, misidentified reactor-based inverse beta decay interactions, cosmogenic radionuclides, water-borne radon, and gamma rays from the photomultiplier tubes (PMTs), detector walls, and surrounding rock. We show that with the use of low background PMTs and sufficient fiducialization, water-borne radon and cosmogenic radionuclides pose the largest threats to sensitivity. Directional sensitivity was then analyzed as a function of radon contamination, detector depth, and detector size. The results provide a list of experimental conditions that, if satisfied in practice, would enable antineutrino directional reconstruction at 3σ significance in large Gd-doped water Cherenkov detectors with greater than 10-km standoff from a nuclear reactor.

  5. Environmentally assisted cracking in light water reactors. Semiannual report, April 1994--September 1994, Volume 19

    Energy Technology Data Exchange (ETDEWEB)

    Chopra, O.K.; Chung, H.M.; Gavenda, D.J. [and others

    1995-09-01

    This report summarizes work performed by Argonne National Laboratory (ANL) on fatigue and environmentally assisted cracking (EAC) in light water reactors from April to September 1994. Topics that have been investigated include (a) fatigue of carbon and low-alloy steel used in piping and reactor pressure vessels, (b) EAC of austenitic stainless steels (SSs) and Alloy 600, and (c) irradiation-assisted stress corrosion cracking (IASCC) of Type 304 SS. Fatigue tests have been conducted on A106-Gr B and A533-Gr B steels in oxygenated water to determine whether a slow strain rate applied during different portions of a tensile-loading cycle are equally effective in decreasing fatigue life. Crack growth data were obtained on fracture-mechanics specimens of SSs and Alloy 600 to investigate EAC in simulated boiling water reactor (BWR) and pressurized water reactor environments at 289{degrees}C. The data were compared with predictions from crack growth correlations developed at ANL for SSs in water and from rates in air from Section XI of the ASME Code. Microchemical changes in high- and commercial-purity Type 304 SS specimens from control-blade absorber tubes and a control-blade sheath from operating BWRs were studied by Auger electron spectroscopy and scanning electron microscopy to determine whether trace impurity elements may contribute to IASCC of these materials.

  6. Decommissioning: a United Kingdom perspective

    Energy Technology Data Exchange (ETDEWEB)

    Haworth, A.; Reed, D.L.; Bleeze, A. [Health and Safety Executive, London (United Kingdom)

    1995-12-31

    The paper considers the United Kingdom legislative framework relevant to decommissioning of facilities on nuclear licensed sites. It describes the various legislative bodies involved in regulating this activity and the inspectorate concerned. The licensing regime is described in some detail highlighting the UK arrangements whereby a license is granted for the site upon which nuclear facilities are planned or exist. The license remains in place throughout the life of the plant on the site: from initial planning through to the end of decommissioning. A site (of part of) is not de-licensed until it can be stated that there has ceased to be any danger from ionising radiations from anything on the site (or appropriate part of the site). The final part of the paper considers the changes arising from the commercialization of the nuclear power industry in UK and the restatement of the Nuclear Installation Inspectorate`s policy on decommissioning which has arisen as a result of a review made in response to these changes. (author).

  7. Experience of on-site disposal of production uranium-graphite nuclear reactor.

    Science.gov (United States)

    Pavliuk, Alexander O; Kotlyarevskiy, Sergey G; Bespala, Evgeny V; Zakharova, Elena V; Ermolaev, Vyacheslav M; Volkova, Anna G

    2018-04-01

    The paper reported the experience gained in the course of decommissioning EI-2 Production Uranium-Graphite Nuclear Reactor. EI-2 was a production Uranium-Graphite Nuclear Reactor located on the Production and Demonstration Center for Uranium-Graphite Reactors JSC (PDC UGR JSC) site of Seversk City, Tomsk Region, Russia. EI-2 commenced its operation in 1958, and was shut down on December 28, 1990, having operated for the period of 33 years all together. The extra pure grade graphite for the moderator, water for the coolant, and uranium metal for the fuel were used in the reactor. During the operation nitrogen gas was passed through the graphite stack of the reactor. In the process of decommissioning the PDC UGR JSC site the cavities in the reactor space were filled with clay-based materials. A specific composite barrier material based on clays and minerals of Siberian Region was developed for the purpose. Numerical modeling demonstrated the developed clay composite would make efficient geological barriers preventing release of radionuclides into the environment. Copyright © 2018 Elsevier Ltd. All rights reserved.

  8. Using largest Lyapunov exponent to confirm the intrinsic stability of boiling water reactors

    Energy Technology Data Exchange (ETDEWEB)

    Gavilian-Moreno, Carlos [Iberdrola Generacion, S.A., Cofrentes Nuclear Power Plant, Project Engineering Department, Paraje le Plano S/N, Valencia (Spain); Espinosa-Paredes, Gilberto [Area de ingeniera en Recursos Energeticos, Universidad Autonoma Metropolitana-Iztapalapa, Mexico city (Mexico)

    2016-04-15

    The aim of this paper is the study of instability state of boiling water reactors with a method based in largest Lyapunov exponents (LLEs). Detecting the presence of chaos in a dynamical system is an important problem that is solved by measuring the LLE. Lyapunov exponents quantify the exponential divergence of initially close state-space trajectories and estimate the amount of chaos in a system. This method was applied to a set of signals from several nuclear power plant (NPP) reactors under commercial operating conditions that experienced instabilities events, apparently each of a different nature. Laguna Verde and Forsmark NPPs with in-phase instabilities, and Cofrentes NPP with out-of-phases instability. This study presents the results of intrinsic instability in the boiling water reactors of three NPPs. In the analyzed cases the limit cycle was not reached, which implies that the point of equilibrium exerts influence and attraction on system evolution.

  9. Using Largest Lyapunov Exponent to Confirm the Intrinsic Stability of Boiling Water Reactors

    Directory of Open Access Journals (Sweden)

    Carlos J. Gavilán-Moreno

    2016-04-01

    Full Text Available The aim of this paper is the study of instability state of boiling water reactors with a method based in largest Lyapunov exponents (LLEs. Detecting the presence of chaos in a dynamical system is an important problem that is solved by measuring the LLE. Lyapunov exponents quantify the exponential divergence of initially close state-space trajectories and estimate the amount of chaos in a system. This method was applied to a set of signals from several nuclear power plant (NPP reactors under commercial operating conditions that experienced instabilities events, apparently each of a different nature. Laguna Verde and Forsmark NPPs with in-phase instabilities, and Cofrentes NPP with out-of-phases instability. This study presents the results of intrinsic instability in the boiling water reactors of three NPPs. In the analyzed cases the limit cycle was not reached, which implies that the point of equilibrium exerts influence and attraction on system evolution.

  10. TRAC-PF1: an advanced best-estimate computer program for pressurized water reactor analysis

    Energy Technology Data Exchange (ETDEWEB)

    Liles, D.R.; Mahaffy, J.H.

    1984-02-01

    The Transient Reactor Analysis Code (TRAC) is being developed at the Los Alamos National Laboratory to provide advanced best-estimate predictions of postulated accidents in light water reactors. The TRAC-PF1 program provides this capability for pressurized water reactors and for many thermal-hydraulic experimental facilities. The code features either a one-dimensional or a three-dimensional treatment of the pressure vessel and its associated internals; a two-phase, two-fluid nonequilibrium hydrodynamics model with a noncondensable gas field; flow-regime-dependent constitutive equation treatment; optional reflood tracking capability for both bottom flood and falling-film quench fronts; and consistent treatment of entire accident sequences including the generation of consistent initial conditions. This report describes the thermal-hydraulic models and the numerical solution methods used in the code. Detailed programming and user information also are provided.

  11. Decontamination and decommissioning technology tree and the current status of the technologies

    Energy Technology Data Exchange (ETDEWEB)

    Oh, Won Zin; Won, H.J.; Kim, G.N.; Lee, K.W.; Chol, W.K.; Jung, C.H.; Kim, C.J.; Kim, S.H.; Kwon, S.O.; Chung, C.M

    2001-03-01

    A technology tree diagram was developed on the basis of the necessary technologies applicable to the decontamination and decommissioning of nuclear facilities. The technology tree diagram is consist of 6 main areas such as characterization, decontamination, decommissioning and remote technology, radwaste management, site restoration, and decommissioning plan and engineering. Characterization is divided into 4 regions such as sampling and data collection, general characterization, chemical analysis and radiological analysis. Decontamination is also divided into 4 regions such as chemical decontamination, mechanical decontamination, the other decontamination technologies and new decontamination technologies. Decommissioning and remote technology area is divided into 4 regions such as cutting techniques, decommissioning technologies, new developing technologies and remote technologies. Radwaste management area is divided into 5 regions such as solid waste treatment, sludge treatment, liquid waste treatment, gas waste treatment and thermal treatment. Site restoration area is divided into 3 regions such as the evaluation of site contamination, soil decontamination and ground water decontamination. Finally, permission, decommissioning process, cost evaluation, quality assurance and the estimation of radionuclide inventory were mentioned in the decommissioning plan and engineering area. The estimated items for each technology are applicable domestic D and D facilities, D and D problem area and contamination/requirement, classification of D and D technology, similar technology, principle and overview of technology, status, science technology needs, implementation needs, reference and contact point.

  12. The simulation of thermohydraulic phenomena in a pressurized water reactor primary loop

    Energy Technology Data Exchange (ETDEWEB)

    Popp, M

    1987-01-01

    Several important fluid flow and heat transfer phenomena essential to nuclear power reactor safety were investigated. Scaling and modeling laws for pressurized water reactors are reviewed and a new scaling approach focusing on the overall loop behavior is presented. Scaling criteria for one- and two-phase natural circulation are developed, as well as a simplified model describing the first phase of a small break loss of coolant accident. Reactor vessel vent valve effects are included in the analysis of steady one-phase natural circulation flow. Two new dimensionless numbers, which uniquely describe one-phase flow in natural circulation loops, were deduced and are discussed. A scaled model of the primary loop of a typical Babcock and Wilcox reactor was designed, built, and tested. The particular prototype modeled was the TMI unit 2 reactor. The electrically heated, stainless steel model operates at a maximum pressure of 300 psig and has a maximum heat input of 188 kW. The model is about 4 times smaller in height than the prototype reactor, with a nominal volume scale of 1:500. Experiments were conducted establishing subcooled natural circulation in the model loop. Both steady flow and power transients were investigated.

  13. Decommissioning of the nuclear facilities at Risø National Laboratory. Descriptions and cost assessment

    OpenAIRE

    Lauridsen, K.

    2001-01-01

    The report is the result of a project initiated by Risø National Laboratory in June 2000 on request from the Minister of Research and Information Technology. It describes the nuclear facilities at Risø National Laboratory to be decommissioned and gives anassessment of the work to be done and the costs incurred. Three decommissioning scenarios were considered with decay times of 10, 25 and 40 years for the DR 3 reactor. The assessments conclude, however, that there will not be much to gain by ...

  14. Stress analyses for reactor pressure vessels by the example of a product line '69 boiling water reactor

    Energy Technology Data Exchange (ETDEWEB)

    Mkrtchyan, Lilit; Schau, Henry [TUEV SUED Energietechnik GmbH, Mannheim (Germany). Abt. Strukturverhalten; Wolf, Werner; Holzer, Wieland [TUEV SUED Industrie Service GmbH, Muenchen (Germany). Abt. Behaelter und Turbosatz; Wernicke, Robert; Trieglaff, Ralf [TUEV NORD SysTec GmbH und Co. KG, Hamburg (Germany). Abt. Festigkeit und Konstruktion

    2011-08-15

    The reactor pressure vessels (RPV) of boiling water reactors (BWR) belonging to the product line '69 have unusually designed heads. The spherical cap-shaped bottom head of the vessel is welded directly to the support flange of the lower shell course. This unusual construction has led repeatedly to controversial discussions concerning the limits and admissibility of stress intensities arising in the junction of the bottom head to the cylindrical shell. In the present paper, stress analyses for the design conditions are performed with the finite element method in order to determine and categorize the occurring stresses. The procedure of stress classification in accordance with the guidelines of German KTA 3201.2 and Section III of the ASME Code (Subsection NB) is described and subsequently demonstrated by the example of a typical BWR vessel. The accomplished investigations yield allowable stress intensities in the considered area. Additionally, limit load analyses are carried out to verify the obtained results. Complementary studies, performed for a torispherical head, prove that the determined maximum peak stresses in the junction between the bottom head and the cylindrical shell are not unusual also for pressure vessels with regular bottom head constructions. (orig.)

  15. Environmentally assisted cracking in light water reactors. Semiannual report, October 1993--March 1994. Volume 18

    Energy Technology Data Exchange (ETDEWEB)

    Chung, H.M.; Chopra, O.K.; Erck, R.A.; Kassner, T.F.; Michaud, W.F.; Ruther, W.E.; Sanecki, J.E.; Shack, W.J.; Soppet, W.K. [Argonne National Lab., IL (United States)

    1995-03-01

    This report summarizes work performed by Argonne National Laboratory (ANL) on fatigue and environmentally assisted cracking (EAC) in light water reactors (LWRs) during the six months from October 1993 to March 1994. EAC and fatigue of piping, pressure vessels, and core components in LWRs are important concerns in operating plants and as extended reactor lifetimes are envisaged. Topics that have been investigated include (a) fatigue of low-alloy steel used in piping, steam generators, and reactor pressure vessels, (b) EAC of wrought and cast austenitic stainless steels (SSs), and (c) radiation-induced segregation and irradiation-assisted stress corrosion cracking (IASCC) of Type 304 SS after accumulation of relatively high fluence. Fatigue tests have been conducted on A302-Gr B low-alloy steel to verify whether the current predictions of modest decreases of fatigue life in simulated pressurized water reactor water are valid for high-sulfur heats that show environmentally enhanced fatigue crack growth rates. Additional crack growth data were obtained on fracture-mechanics specimens of austenitic SSs to investigate threshold stress intensity factors for EAC in high-purity oxygenated water at 289{degrees}C. The data were compared with predictions based on crack growth correlations for wrought austenitic SS in oxygenated water developed at ANL and rates in air from Section XI of the ASME Code. Microchemical and microstructural changes in high- and commercial-purity Type 304 SS specimens from control-blade absorber tubes and a control-blade sheath from operating boiling water reactors were studied by Auger electron spectroscopy and scanning electron microscopy to determine whether trace impurity elements, which are not specified in the ASTM specifications, may contribute to IASCC of solution-annealed materials.

  16. TMI-2 Reactor Building source term measurements: surfaces and basement water and sediment

    Energy Technology Data Exchange (ETDEWEB)

    McIsaac, C V; Keefer, D G

    1984-10-01

    Presented in this report are the results of radiochemical and elemental analyses performed on samples collected from the Three Mile Island Unit 2 Reactor Building from August 1979 to December 1983. The quantities of fission products and core materials that were measured on the external surfaces in the Reactor Building or in the water and sediment in its basement are summarized. Recent analysis results for access panels removed from the air cooling assembly and for liquid and particulate samples collected from the Reactor Building sump and reactor coolant drain tank are included in the report. Measurements show that 59% of the /sup 3/H, 2.7% of the /sup 90/Sr, 15% of the /sup 129/I, 20% of the /sup 131/I, and 42% of the /sup 137/Cs originally in the core at the time of the accident could be accounted for outside the core in the Reactor Building. With the exceptions of /sup 90/Sr and /sup 144/Ce, the vast majority of each radionuclide released was found dispersed in the water and sediment in the basement.

  17. Simulation of the Lower Head Boiling Water Reactor Vessel in a Severe Accident

    Directory of Open Access Journals (Sweden)

    Alejandro Nuñez-Carrera

    2012-01-01

    Full Text Available The objective of this paper is the simulation and analysis of the BoilingWater Reactor (BWR lower head during a severe accident. The COUPLE computer code was used in this work to model the heatup of the reactor core material that slumps in the lower head of the reactor pressure vessel. The prediction of the lower head failure is an important issue in the severe accidents field, due to the accident progression and the radiological consequences that are completely different with or without the failure of the Reactor Pressure Vessel (RPV. The release of molten material to the primary containment and the possibility of steam explosion may produce the failure of the primary containment with high radiological consequences. Then, it is important to have a detailed model in order to predict the behavior of the reactor vessel lower head in a severe accident. In this paper, a hypothetical simulation of a Loss of Coolant Accident (LOCA with simultaneous loss of off-site power and without injection of cooling water is presented with the proposal to evaluate the temperature distribution and heatup of the lower part of the RPV. The SCDAPSIM/RELAP5 3.2 code was used to build the BWR model and conduct the numerical simulation.

  18. Experimental and numerical stability investigations on natural circulation boiling water reactors

    NARCIS (Netherlands)

    Marcel, C.P.

    2007-01-01

    The stability of natural circulation boiling water reactors is investigated with a strong emphasis on experiments. Two different facilities are used for such a task: the GENESIS facility (to which a void reactivity feedback system is artificially added) and the CIRCUS facility. In addition,

  19. 77 FR 16270 - Updated Aging Management Criteria for Reactor Vessel Internal Components of Pressurized Water...

    Science.gov (United States)

    2012-03-20

    ... COMMISSION Updated Aging Management Criteria for Reactor Vessel Internal Components of Pressurized Water... license renewal interim staff guidance (LR-ISG), LR-ISG-2011-04, ``Updated Aging Management Criteria for... Aging Lessons Learned (GALL) Report for the aging management of stainless steel structures and...

  20. Light-water-reactor safety program. Quarterly progress report, April--June 1977

    Energy Technology Data Exchange (ETDEWEB)

    Sachs, R G; Kyger, J A

    1977-01-01

    The report summarizes work performed on the following water-reactor-safety problems: (1) loss-of-coolant accident research in heat transfer and fluid dynamics; (2) transient fuel response and fission-product release; (3) mechanical properties of zircaloy containing oxygen; and (4) steam-explosion studies.

  1. Local Fission Gas Release and Swelling in Water Reactor Fuel during Slow Power Transients

    DEFF Research Database (Denmark)

    Mogensen, Mogens Bjerg; Walker, C.T.; Ray, I.L.F.

    1985-01-01

    Gas release and fuel swelling caused by a power increase in a water reactor fuel (burn-up 2.7–4.5% FIMA) is described. At a bump terminal level of about 400 W/cm (local value) gas release was 25–40%. The formation of gas bubbles on grain boundaries and their degree of interlinkage are the two...

  2. Nuclear Engineering Computer Modules, Thermal-Hydraulics, TH-1: Pressurized Water Reactors.

    Science.gov (United States)

    Reihman, Thomas C.

    This learning module is concerned with the temperature field, the heat transfer rates, and the coolant pressure drop in typical pressurized water reactor (PWR) fuel assemblies. As in all of the modules of this series, emphasis is placed on developing the theory and demonstrating its use with a simplified model. The heart of the module is the PWR…

  3. Prediction of the reactor vessel water level using fuzzy neural networks in severe accident circumstance of NPPs

    Energy Technology Data Exchange (ETDEWEB)

    Park, Soon Ho; Kim, Dae Seop; Kim, Jae Hwan; Na, Man Gyun [Dept. of Nuclear Engineering, Chosun University, Gwangju (Korea, Republic of)

    2014-06-15

    Safety-related parameters are very important for confirming the status of a nuclear power plant. In particular, the reactor vessel water level has a direct impact on the safety fortress by confirming reactor core cooling. In this study, the reactor vessel water level under the condition of a severe accident, where the water level could not be measured, was predicted using a fuzzy neural network (FNN). The prediction model was developed using training data, and validated using independent test data. The data was generated from simulations of the optimized power reactor 1000 (OPR1000) using MAAP4 code. The informative data for training the FNN model was selected using the subtractive clustering method. The prediction performance of the reactor vessel water level was quite satisfactory, but a few large errors were occasionally observed. To check the effect of instrument errors, the prediction model was verified using data containing artificially added errors. The developed FNN model was sufficiently accurate to be used to predict the reactor vessel water level in severe accident situations where the integrity of the reactor vessel water level sensor is compromised. Furthermore, if the developed FNN model can be optimized using a variety of data, it should be possible to predict the reactor vessel water level precisely.

  4. Mobile workstation for decontamination and decommissioning operations

    Energy Technology Data Exchange (ETDEWEB)

    Whittaker, W.L.; Osborn, J.F.; Thompson, B.R. [Carnegie-Mellon Univ., Pittsburgh, PA (United States). Robotics Inst.

    1993-10-01

    This project is an interdisciplinary effort to develop effective mobile worksystems for decontamination and decommissioning (D&D) of facilities within the DOE Nuclear Weapons Complex. These mobile worksystems will be configured to operate within the environmental and logistical constraints of such facilities and to perform a number of work tasks. Our program is designed to produce a mobile worksystem with capabilities and features that are matched to the particular needs of D&D work by evolving the design through a series of technological developments, performance tests and evaluations. The project has three phases. In this the first phase, an existing teleoperated worksystem, the Remote Work Vehicle (developed for use in the Three Mile Island Unit 2 Reactor Building basement), was enhanced for telerobotic performance of several D&D operations. Its ability to perform these operations was then assessed through a series of tests in a mockup facility that contained generic structures and equipment similar to those that D&D work machines will encounter in DOE facilities. Building upon the knowledge gained through those tests and evaluations, a next generation mobile worksystem, the RWV II, and a more advanced controller will be designed, integrated and tested in the second phase, which is scheduled for completion in January 1995. The third phase of the project will involve testing of the RWV II in the real DOE facility.

  5. Ammonium recovery from reject water combined with hydrogen production in a bioelectrochemical reactor.

    Science.gov (United States)

    Wu, Xue; Modin, Oskar

    2013-10-01

    In this study, a bioelectrochemical reactor was investigated for simultaneous hydrogen production and ammonium recovery from reject water, which is an ammonium-rich side-stream produced from sludge treatment processes at wastewater treatment plants. In the anode chamber of the reactor, microorganisms converted organic material into electrical current. The electrical current was used to generate hydrogen gas at the cathode with 96±6% efficiency. Real or synthetic reject water was fed to the cathode chamber where proton reduction into hydrogen gas resulted in a pH increase which led to ammonium being converted into volatile ammonia. The ammonia could be stripped from the solution and recovered in acid. Overall, ammonium recovery efficiencies reached 94% with synthetic reject water and 79% with real reject water. This process could potentially be used to make wastewater treatment plants more resource-efficient and further research is warranted. Copyright © 2013 Elsevier Ltd. All rights reserved.

  6. Design of a supercritical water-cooled reactor with a three-pass core arrangement

    Energy Technology Data Exchange (ETDEWEB)

    Fischer, K. [EnBW Kernkraft GmbH, Kernkraftwerk Philippsburg, D-76661 Philippsburg (Germany)], E-mail: kai-fischer@gmx.de; Schulenberg, T. [Forschungszentrum Karlsruhe GmbH, Institute for Nuclear and Energy Technologies, P.O. Box 3640, D-76021 Karlsruhe (Germany); Laurien, E. [University of Stuttgart, Institute for Nuclear and Energy Systems (IKE), Pfaffenwaldring 31, D-70569 Stuttgart (Germany)

    2009-04-15

    The Supercritical Water-cooled Reactor (SCWR) is one of the six concepts of the Generation IV International Forum. In Europe, investigations have been integrated into a joint research project, called High Performance Light Water Reactor (HPLWR). Due to the higher heat up within the core and a higher outlet temperature, a significant increase in turbine power and thermal efficiency of the plant can be expected. Besides the higher pressure and higher steam temperature, the design concept of this type of reactor differs significantly from a conventional LWR by a different core concept. In order to achieve the high outlet temperature of over 500 deg. C, a core with a three-step heat up and intermediate mixing is proposed to keep local cladding temperatures within today's material limits. A design for the reactor pressure vessel (RPV) and the internals has been worked out to incorporate a core arrangement with three passes. All components have been dimensioned following the safety standards of the nuclear safety standards commission in Germany. Additionally, a fuel assembly cluster with head and foot piece has been developed to facilitate the complex flow path for the multi-pass concept. The design of the internals and of the RPV is verified using mechanical or, in the case of large thermal deformations, combined mechanical and thermal stress analyses. Furthermore, the reactor design ensures that the total coolant flow path remains closed against leakage of colder moderator water even in case of large thermal expansions of the components. The design of the RPV and internals is now available for detailed analyses of the core and the reactor.

  7. Elimination of water pathogens with solar radiation using an automated sequential batch CPC reactor

    Energy Technology Data Exchange (ETDEWEB)

    Polo-Lopez, M.I., E-mail: mpolo@psa.es [Plataforma Solar de Almeria - CIEMAT, PO Box 22, 04200 Tabernas, Almeria (Spain); Fernandez-Ibanez, P., E-mail: pilar.fernandez@psa.es [Plataforma Solar de Almeria - CIEMAT, PO Box 22, 04200 Tabernas, Almeria (Spain); Ubomba-Jaswa, E., E-mail: euniceubombajaswa@yahoo.com [Natural Resources and the Environment, CSIR, PO Box 395, Pretoria (South Africa); Navntoft, C., E-mail: christian.navntoft@solarmate.com.ar [Instituto de Investigacion e Ingenieria Ambiental, Universidad Nacional de San Martin (3iA-UNSAM), Peatonal Belgrano 3563, B1650ANQ San Martin (Argentina); Universidad Tecnologica Nacional - Facultad Regional Buenos Aires - Departamento de Ingenieria Civil - Laboratorio de Estudios sobre Energia Solar, (UTN-FRBA-LESES), Mozart 2300, (1407) Ciudad Autonoma de Buenos Aires, Republica Argentina (Argentina); Garcia-Fernandez, I., E-mail: irene.garcia@psa.es [Plataforma Solar de Almeria - CIEMAT, PO Box 22, 04200 Tabernas, Almeria (Spain); Dunlop, P.S.M., E-mail: psm.dunlop@ulster.ac.uk [Department of Physiology and Medical Physics, Royal College of Surgeons in Ireland, Dublin 2 (Ireland); Schmid, M. [Department of Physiology and Medical Physics, Royal College of Surgeons in Ireland, Dublin 2 (Ireland); Byrne, J.A., E-mail: j.byrne@ulster.ac.uk [Department of Physiology and Medical Physics, Royal College of Surgeons in Ireland, Dublin 2 (Ireland); and others

    2011-11-30

    Solar disinfection (SODIS) of water is a well-known, effective treatment process which is practiced at household level in many developing countries. However, this process is limited by the small volume treated and there is no indication of treatment efficacy for the user. Low cost glass tube reactors, together with compound parabolic collector (CPC) technology, have been shown to significantly increase the efficiency of solar disinfection. However, these reactors still require user input to control each batch SODIS process and there is no feedback that the process is complete. Automatic operation of the batch SODIS process, controlled by UVA-radiation sensors, can provide information on the status of the process, can ensure the required UVA dose to achieve complete disinfection is received and reduces user work-load through automatic sequential batch processing. In this work, an enhanced CPC photo-reactor with a concentration factor of 1.89 was developed. The apparatus was automated to achieve exposure to a pre-determined UVA dose. Treated water was automatically dispensed into a reservoir tank. The reactor was tested using Escherichia coli as a model pathogen in natural well water. A 6-log inactivation of E. coli was achieved following exposure to the minimum uninterrupted lethal UVA dose. The enhanced reactor decreased the exposure time required to achieve the lethal UVA dose, in comparison to a CPC system with a concentration factor of 1.0. Doubling the lethal UVA dose prevented the need for a period of post-exposure dark inactivation and reduced the overall treatment time. Using this reactor, SODIS can be automatically carried out at an affordable cost, with reduced exposure time and minimal user input.

  8. Elimination of water pathogens with solar radiation using an automated sequential batch CPC reactor.

    Science.gov (United States)

    Polo-López, M I; Fernández-Ibáñez, P; Ubomba-Jaswa, E; Navntoft, C; García-Fernández, I; Dunlop, P S M; Schmid, M; Byrne, J A; McGuigan, K G

    2011-11-30

    Solar disinfection (SODIS) of water is a well-known, effective treatment process which is practiced at household level in many developing countries. However, this process is limited by the small volume treated and there is no indication of treatment efficacy for the user. Low cost glass tube reactors, together with compound parabolic collector (CPC) technology, have been shown to significantly increase the efficiency of solar disinfection. However, these reactors still require user input to control each batch SODIS process and there is no feedback that the process is complete. Automatic operation of the batch SODIS process, controlled by UVA-radiation sensors, can provide information on the status of the process, can ensure the required UVA dose to achieve complete disinfection is received and reduces user work-load through automatic sequential batch processing. In this work, an enhanced CPC photo-reactor with a concentration factor of 1.89 was developed. The apparatus was automated to achieve exposure to a pre-determined UVA dose. Treated water was automatically dispensed into a reservoir tank. The reactor was tested using Escherichia coli as a model pathogen in natural well water. A 6-log inactivation of E. coli was achieved following exposure to the minimum uninterrupted lethal UVA dose. The enhanced reactor decreased the exposure time required to achieve the lethal UVA dose, in comparison to a CPC system with a concentration factor of 1.0. Doubling the lethal UVA dose prevented the need for a period of post-exposure dark inactivation and reduced the overall treatment time. Using this reactor, SODIS can be automatically carried out at an affordable cost, with reduced exposure time and minimal user input. Copyright © 2011 Elsevier B.V. All rights reserved.

  9. Non normal modal analysis of oscillations in boiling water reactors

    Energy Technology Data Exchange (ETDEWEB)

    Suarez-Antola, Roberto, E-mail: roberto.suarez@miem.gub.uy [Ministerio de Industria, Energia y Mineria (MIEM), Montevideo (Uruguay); Flores-Godoy, Jose-Job, E-mail: job.flores@ibero.mx [Universidad Iberoamericana (UIA), Mexico, DF (Mexico). Dept. de Fisica Y Matematicas

    2013-07-01

    The first objective of the present work is to construct a simple reduced order model for BWR stability analysis, combining a two nodes nodal model of the thermal hydraulics with a two modes modal model of the neutronics. Two coupled non-linear integral-differential equations are obtained, in terms of one global (in phase) and one local (out of phase) power amplitude, with direct and cross feedback reactivities given as functions of thermal hydraulics core variables (void fractions and temperatures). The second objective is to apply the effective life time approximation to further simplify the nonlinear equations. Linear approximations for the equations of the amplitudes of the global and regional modes are derived. The linearized equation for the amplitude of the global mode corresponds to a decoupled and damped harmonic oscillator. An analytical closed form formula for the damping coefficient, as a function of the parameters space of the BWR, is obtained. The coefficient changes its sign (with the corresponding modification in the decay ratio) when a stability boundary is crossed. This produces a supercritical Hopf bifurcation, with the steady state power of the reactor as the bifurcation parameter. However, the linearized equation for the amplitude of the regional mode corresponds always to an over-damped and always coupled (with the amplitude of the global mode) harmonic oscillator, for every set of possible values of core parameters (including the steady state power of the reactor) in the framework of the present mathematical model. The equation for the above mentioned over damped linear oscillator is closely connected with a non-normal operator. Due to this connection, there could be a significant transient growth of some solutions of the linear equation. This behavior allows a significant shrinking of the basin of attraction of the equilibrium state. The third objective is to apply the above approach to partially study the stability of the regional mode and

  10. FLUOR HANFORD DECOMMISSIONING UPDATE

    Energy Technology Data Exchange (ETDEWEB)

    GERBER MS

    2008-04-21

    Fluor Hanford is completing D&D of the K East Basin at the U.S. Department of Energy's (DOE's) Hanford Site in southeastern Washington State this spring, with demolition expected to begin in June. Located about 400 yards from the Columbia River, the K East Basin is one of two indoor pools that formerly contained irradiated nuclear fuel, radioactive sludge and tons of contaminated debris. In unique and path-breaking work, workers finished removing the spent fuel from the K Basins in 2004. In May 2007, workers completed vacuuming the sludge into containers in the K East Basin, and transferring it into containers in the K West Basin. In December, they finished vacuuming the remainder of K West Basin sludge into these containers. The K East Basin was emptied of its radioactive inventory first because it was more contaminated than the K West Basin, and had leaked in the past. In October 2007, Fluor Hanford began physical D&D of the 8,400-square foot K East Basin by pouring approximately 14-inches of grout into the bottom of it. Grout is a type of special cement used for encasing waste. Two months later, Fluor Hanford workers completed sluicing contaminated sand from the large filter that had sieved contaminants from the basin water for more than 50 years. Next, they poured grout into the filter housing and the vault that surrounds the filter, as well as into ion exchange columns that also helped filter basin water. For a six-week period in February and March, personnel drained the approximately one million gallons of contaminated water from the K East Basin. The effort required more than 200 tanker truck loads that transported the water to an effluent treatment facility for treatment and then release. A thin fixative was also applied to the basin walls as the water was removed to hold residual contamination in place. As soon as the water was out of the basin, Fluor pumped in approximately 18 feet of 'controlled density fill' material (somewhat

  11. Draft layout, containment and performance of the safety system of the European Supercritical Water-Cooled Reactor

    Energy Technology Data Exchange (ETDEWEB)

    Starflinger, J.; Schlagenhaufer, M.; Kohly, C.; Schulenberg, T. [Karlsruhe Inst. of Tech., Karlsruhe (Germany); Rothschmitt, S.; Bittermann, D. [AREVA NP GmbH, Erlangen (Germany)

    2010-07-01

    In Europe, the research on Supercritical Water-Cooled Reactors is integrated in a project called 'High Performance Light Water Reactor Phase 2' (HPLWR Phase 2), co-funded by the European Commission. Ten partners and three active supporters are working on critical scientific issues to determine the potential of this reactor concept in the electricity market. Close to the end of the project the technical results are translated into a draft layout of the HPLWR. The containment and safety system are being explained. Exemplarily, a depressurization event shows the capabilities of the safety system to sufficiently cool the reactor by means of a low pressure coolant injection system. (author)

  12. Studies on supercritical water reactor fuel assemblies using the sub-channel code COBRA-EN

    Energy Technology Data Exchange (ETDEWEB)

    Ammirabile, Luca, E-mail: luca.ammirabile@ec.europa.e [European Commission, JRC, Institute for Energy, Westerduinweg 3, 1755 LE Petten (Netherlands)

    2010-10-15

    In the Generation IV International Forum (GIF) program, the supercritical water reactor (SCWR) concept is among the six innovative reactor types selected for development in the near future. In principle the higher efficiency and better economics make the SCWR concept competitive with the current reactor design. Due to different technical challenges that, however exist, fuel assembly design represents a crucial aspect for the success of this concept. In particular large density variations, low moderation, heat transfer enhancement and deterioration have a strong effect on the core design parameters. Only a few computational tools are currently able to perform sub-channel thermal-hydraulic analysis under supercritical water conditions. At JRC-IE the existing sub-channel code COBRA-EN has been improved to work above the critical pressure of water. The water properties package of the IAPWS Industrial Formulation 1997 was integrated in COBRA-EN to compute the Thermodynamic Properties of Water and Steam. New heat transfer and pressure drop correlations more indicated for the supercritical region of water have also been incorporated in the code. As part of the efforts to appraise the new code capabilities, a code assessment was carried out on the hexagonal fuel assembly of a fast supercritical water reactor. COBRA-EN was also applied in combination with the neutronic code MCNP to investigate on the use of hydride fuel in the HPLWR supercritical water fuel assembly. The results showed that COBRA-EN was able to reproduce the results of similar studies with acceptable accuracy. Future activities will focus on the validation of the code against experimental data and the implementation of new features (counter-current moderator channel, wall, and wire-wrap models).

  13. Research in decommissioning techniques for nuclear fuel cycle facilities in JNC. 7. JWTF decommissioning techniques

    Energy Technology Data Exchange (ETDEWEB)

    Ogawa, Ryuichiro; Ishijima, Noboru [Japan Nuclear Cycle Development Inst., Oarai, Ibaraki (Japan). Oarai Engineering Center

    1999-02-01

    Decommissioning techniques such as radiation measuring and monitoring, decontamination, dismantling and remote handling in the world were surveyed to upgrading technical know-how database for decommissioning of Joyo Waste Treatment Facility (JWTF). As the result, five literatures for measuring and monitoring techniques, 14 for decontamination and 22 for dismantling feasible for JWTF decommissioning were obtained and were summarized in tables. On the basis of the research, practical applicability of those techniques to decommissioning of JWTF was evaluated. This report contains brief surveyed summaries related to JWTF decommissioning. (H. Itami)

  14. Overview of Prevention for Water Hammer by Check Valve Action in Nuclear Reactor

    Energy Technology Data Exchange (ETDEWEB)

    Kim, Dayong; Yoon, Hyungi; Seo, Kyoungwoo; Kim, Seonhoon [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2016-10-15

    Water hammer can cause serious damage to pumping system and unexpected system pressure rise in the pipeline. In nuclear reactor, water hammer can influence on the integrity of safety related system. Water hammer in nuclear reactor have been caused by voiding in normally water-filled lines, steam condensation line containing both steam and water, as well as by rapid check valve action. Therefore, this study focuses on the water hammer by check valve among the sources of water hammer occurrence and suggests proper methodology for check valve type selection against water hammer. This study focuses on the water hammer by check valve action among the sources of water hammer occurrence and suggests proper methodology for check valve type selection against water hammer. If the inadvertent pump trip or pipe rupture in high velocity and pressure pipe is predicted, the fast response check valve such as tiled disc, dual disc and nozzle check valve should be installed in the system. If the inadvertent pump trip or pipe rupture in very high velocity and pressure pipe and excessively large revered flow velocity are predicted, the very slowly closing check valve such as controlled closure check valve should be installed in the system.

  15. In-Vessel Melt Retention of Pressurized Water Reactors: Historical Review and Future Research Needs

    OpenAIRE

    Ma, Weimin; Yuan, Yidan; Sehgal, Bal Raj

    2016-01-01

    A historical review of in-vessel melt retention (IVR) is given, which is a severe accident mitigation measure extensively applied in Generation III pressurized water reactors (PWRs). The idea of IVR actually originated from the back-fitting of the Generation II reactor Loviisa VVER-440 in order to cope with the core-melt risk. It was then employed in the new deigns such as Westinghouse AP1000, the Korean APR1400 as well as Chinese advanced PWR designs HPR1000 and CAP1400. The most influential...

  16. An organic profile of a pressurised water reactor secondary plant

    Energy Technology Data Exchange (ETDEWEB)

    Eeden, Nestor van; Stwayi, Mandisibuntu; Gericke, Gerhard [Eskom Holdings SOC Ltd., Western Cape (South Africa). Koeberg Power Station

    2012-07-15

    Make-up water addition to the steam/water cycle at Koeberg Nuclear Power Station usually results in a corresponding increase of the chloride concentration in the steam generator blowdown system. During plant transients, when higher than normal make-up is required to the secondary plant, the concentration of chloride occasionally exceeds the limiting value for the station chemistry performance indicator. Irrespective of this, the demineralised water make-up supply tanks, which are routinely analysed for chloride, are within all recognised acceptable standards for secondary water make-up and therefore these tanks do not initially appear to be the source of chloride contamination. Water treatment at the plant relies essentially on ion exchange, which has been proven to be very effective in removing inorganic ionic species such as chloride. Organic compounds are less effectively removed by ion exchange and may pass through the treatment system, and these organics can reside undetected in the make-up water tanks. Historically, the elevated chloride concentration following high system make-up has been attributed to chlorinated organic compounds known as trihalomethanes being present in the make-up water tanks, but no rigorous study had been undertaken. As it has been assumed that the majority of chloride in the secondary system originates from the make-up water organic impurities, it was considered important to confirm this by compiling an organic profile of the secondary plant. The use of organic additives was also taken into account in the profile. This work has confirmed the contribution from trihalomethanes and has also found that other organochlorides contribute even more significantly to the overall chloride inventory of the secondary plant. (orig.)

  17. Heat Transfer Phenomena in Supercritical Water Nuclear Reactors

    Energy Technology Data Exchange (ETDEWEB)

    Mark H. Anderson; MichaelL. Corradini; Riccardo Bonazza; Jeremy R. Licht

    2007-10-03

    A supercritical water heat transfer facility has been built at the University of Wisconsin to study heat transfer in ancircular and square annular flow channel. A series of integral heat transfer measurements has been carried out over a wide range of heat flux, mas velocity and bulk water temperatures at a pressure of 25 MPa. The circular annular test section geometry is a 1.07 cm diameter heater rod within a 4.29 diameter flow channel.

  18. Reactor safeguards

    CERN Document Server

    Russell, Charles R

    1962-01-01

    Reactor Safeguards provides information for all who are interested in the subject of reactor safeguards. Much of the material is descriptive although some sections are written for the engineer or physicist directly concerned with hazards analysis or site selection problems. The book opens with an introductory chapter on radiation hazards, the construction of nuclear reactors, safety issues, and the operation of nuclear reactors. This is followed by separate chapters that discuss radioactive materials, reactor kinetics, control and safety systems, containment, safety features for water reactor

  19. Decommissioning of the nuclear facilities at Risoe National Laboratory. Descriptions and cost assessment[Denmark

    Energy Technology Data Exchange (ETDEWEB)

    Lauridsen, Kurt [ed.

    2001-02-01

    The report is the result of a project initiated by Risoe National Laboratory in June 2000 on request from the Minister of Research and Information Technology. It describes the nuclear facilities at Risoe National Laboratory to be decommissioned and gives an assessment of the work to be done and the costs incurred. Three decommissioning scenarios were considered with decay times of 10, 25 and 40 years for the DR 3 reactor. The assessments conclude, however, that there will not be much to gain by allowing for the longer decay periods; some operations still will need to be performed remotely. Furthermore, the report describes some of the legal and licensing framework for the decommissioning and gives an assessment of the amounts of radioactive waste to be transferred to a Danish repository. (au)

  20. 2. decommissioning colloquium. 2. Stillegungskolloquium; Manuskripte bzw. Kurzfassungen der Vortraege. Tischvorlage

    Energy Technology Data Exchange (ETDEWEB)

    1992-01-01

    In connection with the close-down of nuclear facilities after reaching their designed service life limit, or for safety reasons, decommissioning is gaining in importance for industry and research. One of the priorities in this regard, in addition to the safe containment and qualification of dismantling techniques for the removal of nuclear installations, are the conditioning and ultimate disposal of components and the recycling of materials for industrial purposes. In the Ferderal Republic of Germany there are 27 decommissioned nuclear facilities. In the old federal states those are, among others, the reactor plants HDR, KKN, KRB A, KWL, MZFR, VAK, KNK II, AVR, THTR, and in the new federal states, the 11 units of the Greifswald, Rheinsberg and Stendal sites, but also installations of the nuclear fuel cycle. For more than 20 years, operators and research institutions have been intensively concerned with the various aspects of decommissioning. (orig./HP). 13 figs.

  1. Overview of the US Department of Energy Light Water Reactor Sustainability Program

    Energy Technology Data Exchange (ETDEWEB)

    K. A. McCarthy; D. L. Williams; R. Reister

    2012-05-01

    The US Department of Energy Light Water Reactor Sustainability Program is focused on the long-term operation of US commercial power plants. It encompasses two facets of long-term operation: (1) manage the aging of plant systems, structures, and components so that nuclear power plant lifetimes can be extended and the plants can continue to operate safely, efficiently, and economically; and (2) provide science-based solutions to the nuclear industry that support implementation of performance improvement technologies. An important aspect of the Light Water Reactor Sustainability Program is partnering with industry and the Nuclear Regulatory Commission to support and conduct the long-term research needed to inform major component refurbishment and replacement strategies, performance enhancements, plant license extensions, and age-related regulatory oversight decisions. The Department of Energy research, development, and demonstration role focuses on aging phenomena and issues that require long-term research and/or unique Department of Energy laboratory expertise and facilities and are applicable to all operating reactors. This paper gives an overview of the Department of Energy Light Water Reactor Sustainability Program, including vision, goals, and major deliverables.

  2. Evaluation of integral continuing experimental capability (CEC) concepts for light water reactor research: PWR scaling concepts

    Energy Technology Data Exchange (ETDEWEB)

    Condie, K G; Larson, T K; Davis, C B; McCreery, G E

    1987-02-01

    In this report reactor transients and thermal-hydraulic phenomena of importance (based on probabilistic risk assessment and the International Code Assessment Program) to reactor safety were examined and identified. Established scaling methodologies were used to develop potential concepts for integral thermal-hydraulic testing facilities. Advantages and disadvantages of each concept are evaluated. Analysis is conducted to examine the scaling of various phenomena in each of the selected concepts. Results generally suggest that a facility capable of operating at typical reactor operating conditions will scale most phenomena reasonably well. Although many phenomena in facilities using Freon or water at nontypical pressure will scale reasonably well, those phenomena that are heavily dependent on quality (heat transfer or critical flow for example) can be distorted. Furthermore, relation of data produced in facilities operating with nontypical fluids or at nontypical pressures to large plants will be a difficult and time consuming process.

  3. Standard Guide for In-Service Annealing of Light-Water Moderated Nuclear Reactor Vessels

    CERN Document Server

    American Society for Testing and Materials. Philadelphia

    2003-01-01

    1.1 This guide covers the general procedures to be considered for conducting an in-service thermal anneal of a light-water moderated nuclear reactor vessel and demonstrating the effectiveness of the procedure. The purpose of this in-service annealing (heat treatment) is to improve the mechanical properties, especially fracture toughness, of the reactor vessel materials previously degraded by neutron embrittlement. The improvement in mechanical properties generally is assessed using Charpy V-notch impact test results, or alternatively, fracture toughness test results or inferred toughness property changes from tensile, hardness, indentation, or other miniature specimen testing (1). 1.2 This guide is designed to accommodate the variable response of reactor-vessel materials in post-irradiation annealing at various temperatures and different time periods. Certain inherent limiting factors must be considered in developing an annealing procedure. These factors include system-design limitations; physical constrain...

  4. Resource book: Decommissioning of contaminated facilities at Hanford

    Energy Technology Data Exchange (ETDEWEB)

    1991-09-01

    In 1942 Hanford was commissioned as a site for the production of weapons-grade plutonium. The years since have seen the construction and operation of several generations of plutonium-producing reactors, plants for the chemical processing of irradiated fuel elements, plutonium and uranium processing and fabrication plants, and other facilities. There has also been a diversification of the Hanford site with the building of new laboratories, a fission product encapsulation plant, improved high-level waste management facilities, the Fast Flux test facility, commercial power reactors and commercial solid waste disposal facilities. Obsolescence and changing requirements will result in the deactivation or retirement of buildings, waste storage tanks, waste burial grounds and liquid waste disposal sites which have become contaminated with varying levels of radionuclides. This manual was established as a written repository of information pertinent to decommissioning planning and operations at Hanford. The Resource Book contains, in several volumes, descriptive information of the Hanford Site and general discussions of several classes of contaminated facilities found at Hanford. Supplementing these discussions are appendices containing data sheets on individual contaminated facilities and sites at Hanford. Twelve appendices are provided, corresponding to the twelve classes into which the contaminated facilities at Hanford have been organized. Within each appendix are individual data sheets containing administrative, geographical, physical, radiological, functional and decommissioning information on each facility within the class. 68 refs., 54 figs., 18 tabs.

  5. 76 FR 77431 - Decommissioning Planning During Operations

    Science.gov (United States)

    2011-12-13

    ... Planning During Operations AGENCY: Nuclear Regulatory Commission. ACTION: Draft regulatory guide; request... regulatory guide (DG) DG-4014, ``Decommissioning Planning During Operations.'' This guide describes a method that the NRC staff considers acceptable for use in complying with the NRC's Decommissioning Planning...

  6. Review of Impact Factors on Decommissioning Strategies

    Energy Technology Data Exchange (ETDEWEB)

    Yun, Taesik; Jung, Hyejin; Kim, Younggook [KHNP CRI, Daejeon (Korea, Republic of)

    2016-10-15

    This article is prepared to factor out decommissioning strategies mostly appropriate to the decommissioning Kori-1 nuclear power plant. Terms used to delineate the lifetime of an authorized facility and of the associated licensing process consists of six core stages such as siting, design, construction, commissioning, operation and decommissioning. The term decommissioning implies the administrative and technical actions taken to allow the removal of some or all of the regulatory controls from a facility except for the part of a disposal facility in which the radioactive waste is emplaced. Whole range of each process of decommissioning should be considered throughout the other five stages. The decommissioning process is typically composed of its planning, conducting actions and terminating the authorization. In order to achieve the successful decommissioning, the impact factor on the strategy should be analyzed and evaluated to optimally apply to Kori-1 project. From my perspective, among eight factor, stakeholder’s consideration and spent fuel management are considered the key elements we have to concentrate on to smoothly go ahead for successful decommissioning of Kori-1.

  7. Sustainable Decommissioning of Oil Fields and Mines

    OpenAIRE

    Environmental Resources Management

    2009-01-01

    The overall goal of the decommissioning of oil fields and mines initiative (the 'Initiative') is, in keeping with World Bank policy, to promote sustainable development by assisting governments to undertake and engage in earlier and more systematic, comprehensive, and responsive planning of the decommissioning and closure of mining and oil and gas production operations, as well as more effe...

  8. Radio-toxicity of spent fuel of the advanced heavy water reactor.

    Science.gov (United States)

    Anand, S; Singh, K D S; Sharma, V K

    2010-01-01

    The Advanced Heavy Water Reactor (AHWR) is a new power reactor concept being developed at Bhabha Atomic Research Centre, Mumbai. The reactor retains many desirable features of the existing Pressurised Heavy Water Reactor (PHWR), while incorporating new, advanced safety features. The reactor aims to utilise the vast thorium resources available in India. The reactor core will use plutonium as the make-up fuel, while breeding (233)U in situ. On account of this unique combination of fuel materials, the operational characteristics of the fuel as determined by its radioactivity, decay heat and radio-toxicity are being viewed with great interest. Radio-toxicity of the spent fuel is a measure of potential radiological hazard to the members of the public and also important from the ecological point of view. The radio-toxicity of the AHWR fuel is extremely high to start with, being approximately 10(4) times that of the fresh natural U fuel used in a PHWR, and continues to remain relatively high during operation and subsequent cooling. A unique feature of this fuel is the peak observed in its radio-toxicity at approximately 10(5) y of decay cooling. The delayed increase in fuel toxicity has been traced primarily to a build-up of (229)Th, (230)Th and (226)Ra. This phenomenon has been observed earlier for thorium-based fuels and is confirmed for the AHWR fuel. This paper presents radio-toxicity data for AHWR spent fuel up to a period of 10(6) y and the results are compared with the radio-toxicity of PHWR.

  9. Supercritical Water Gasification of Biomass in a Ceramic Reactor: Long-Time Batch Experiments

    Directory of Open Access Journals (Sweden)

    Daniele Castello

    2017-10-01

    Full Text Available Supercritical water gasification (SCWG is an emerging technology for the valorization of (wet biomass into a valuable fuel gas composed of hydrogen and/or methane. The harsh temperature and pressure conditions involved in SCWG (T > 375 °C, p > 22 MPa are definitely a challenge for the manufacturing of the reactors. Metal surfaces are indeed subject to corrosion under hydrothermal conditions, and expensive special alloys are needed to overcome such drawbacks. A ceramic reactor could be a potential solution to this issue. Finding a suitable material is, however, complex because the catalytic effect of the material can influence the gas yield and composition. In this work, a research reactor featuring an internal alumina inlay was utilized to conduct long-time (16 h batch tests with real biomasses and model compounds. The same experiments were also conducted in batch reactors made of stainless steel and Inconel 625. The results show that the three devices have similar performance patterns in terms of gas production, although in the ceramic reactor higher yields of C2+ hydrocarbons were obtained. The SEM observation of the reacted alumina surface revealed a good resistance of such material to supercritical conditions, even though some intergranular corrosion was observed.

  10. Development of neutron measurement techniques in reactor diagnostics and determination of water content and water flow

    Energy Technology Data Exchange (ETDEWEB)

    Avdic, Senada

    2000-09-01

    The present thesis deals with three comparatively different topics in neutron physics research. These topics are as follows: construction and experimental investigation of a new detector, capable of measuring the neutron current, and investigation of the possibility to use it for the localisation of a neutron source in a simple experimental arrangement; execution of neutron transmission measurements based on a stationary neutron generator, and the study of their suitability for determining the volume porosity of geological samples; study of the possibility for improving the accuracy of water flow measurements based on the pulsed neutron activation technique. The first subject of this thesis concerns the measurement of the neutron current by a newly constructed detector. The motivation for this work stems from a recent suggestion that the performance of core monitoring methods could be enhanced if, in addition to the scalar neutron flux, also the neutron current was measured. To this end, a current detector was based on a scintillator mounted on a fibre and a Cd layer on one side of the detector. The measurements of the 2-D neutron current were performed in an experimental system by using this detector. The efficiency of the detector in reactor diagnostics was illustrated by demonstrating that the position of a neutron source can be determined by measuring the scalar neutron flux and the neutron current in one spatial point. The results of measurement and calculation show both the suitability of the detector construction for the measurement of the neutron current vector and the use of the current in diagnostics and monitoring. The second subject of this thesis concerns fast neutron transmission measurements, based on a stationary neutron generator, for determining the volume porosity of a sample in a model experiment. Such a technique could be used in field measurements with obvious advantages in comparison with thermal neutron transmission techniques, which can

  11. Modeling of water lighting process and calculation of the reactor-clarifier to improve energy efficiency

    Science.gov (United States)

    Skolubovich, Yuriy; Skolubovich, Aleksandr; Voitov, Evgeniy; Soppa, Mikhail; Chirkunov, Yuriy

    2017-10-01

    The article considers the current questions of technological modeling and calculation of the new facility for cleaning natural waters, the clarifier reactor for the optimal operating mode, which was developed in Novosibirsk State University of Architecture and Civil Engineering (SibSTRIN). A calculation technique based on well-known dependences of hydraulics is presented. A calculation example of a structure on experimental data is considered. The maximum possible rate of ascending flow of purified water was determined, based on the 24 hour clarification cycle. The fractional composition of the contact mass was determined with minimal expansion of contact mass layer, which ensured the elimination of stagnant zones. The clarification cycle duration was clarified by the parameters of technological modeling by recalculating maximum possible upward flow rate of clarified water. The thickness of the contact mass layer was determined. Likewise, clarification reactors can be calculated for any other lightening conditions.

  12. Environmentally assisted cracking in light water reactors annual report January - December 2005.

    Energy Technology Data Exchange (ETDEWEB)

    Alexandreanu, B.; Chen, Y.; Chopra, O. K.; Chung, H. M.; Gruber, E. E.; Shack, W. J.; Soppet, W. K.

    2007-08-31

    This report summarizes work performed from January to December 2005 by Argonne National Laboratory on fatigue and environmentally assisted cracking in light water reactors (LWRs). Existing statistical models for estimating the fatigue life of carbon and low-alloy steels and austenitic stainless steels (SSs) as a function of material, loading, and environmental conditions were updated. Also, the ASME Code fatigue adjustment factors of 2 on stress and 20 on life were critically reviewed to assess the possible conservatism in the current choice of the margins. An approach, based on an environmental fatigue correction factor, for incorporating the effects of LWR environments into ASME Section III fatigue evaluations is discussed. The susceptibility of austenitic stainless steels and their welds to irradiation-assisted stress corrosion cracking (IASCC) is being evaluated as a function of the fluence level, water chemistry, material chemistry, and fabrication history. For this task, crack growth rate (CGR) tests and slow strain rate tensile (SSRT) tests are being conducted on various austenitic SSs irradiated in the Halden boiling water reactor. The SSRT tests are currently focused on investigating the effects of the grain boundary engineering process on the IASCC of the austenitic SSs. The CGR tests were conducted on Type 316 SSs irradiated to 0.45-3.0 dpa, and on sensitized Type 304 SS and SS weld heat-affected-zone material irradiated to 2.16 dpa. The CGR tests on materials irradiated to 2.16 dpa were followed by a fracture toughness test in a water environment. The effects of material composition, irradiation, and water chemistry on growth rates are discussed. The susceptibility of austenitic SS core internals to IASCC and void swelling is also being evaluated for pressurized water reactors. Both SSRT tests and microstructural examinations are being conducted on specimens irradiated in the BOR-60 reactor in Russia to doses up to 20 dpa. Crack growth rate data

  13. Experimental Evaluation of a Water Shield for a Surface Power Reactor

    Science.gov (United States)

    Pearson, J. Boise; Reid, Robert S.

    2006-01-01

    As part of the Vision for Space Exploration the end of the next decade will bring man back to the surface of the moon. One of the most critical issues for the establishment of human presence on the moon will be the availability of compact power sources. The establishment of man on the moon will require power from greater than 10's of kWt's in follow on years. Nuclear reactors are extremely we11 suited to meet the needs for power generation on the lunar or Martian surface. reactor system. Several competing concepts exist for lightweight, safe, robust shielding systems such as a water shield, lithium hydride (LiH), Boron Carbide, and others. Water offers several potential advantages, including reduced cost, reduced technical risk, and reduced mass. Water has not typically been considered for space reactor applications because of the need for gravity to remove the potential for radiation streaming paths. The water shield concept relies on predictions of passive circulation of the shield water by natural convection to adequately cool the shield. This prediction needs to be experimentally evaluated, especially for shields with complex geometries. MSFC has developed the experience and fac necessary to do this evaluation in the Early Flight Fission - Test Facility (EFF-TF).

  14. Preliminary Evaluation of Convective Heat Transfer in a Water Shield for a Surface Power Reactor

    Science.gov (United States)

    Pearson J. Boise; Reid, Robert S.

    2007-01-01

    As part of the Vision for Space Exploration, the end of the next decade will bring man back to the surface of the moon. A crucial issue for the establishment of human presence on the moon will be the availability of compact power sources. This presence could require greater than 10's of kWt's in follow on years. Nuclear reactors are well suited to meet the needs for power generation on the lunar or Martian surface. Radiation shielding is a key component of any surface power reactor system. Several competing concepts exist for lightweight, safe, robust shielding systems such as a water shield, lithium hydride (LiH), and boron carbide. Water offers several potential advantages, including reduced cost, reduced technical risk, and reduced mass. Water has not typically been considered for space reactor applications because of the need for gravity to fix the location of any vapor that could form radiation streaming paths. The water shield concept relies on the predictions of passive circulation of the shield water by natural convection to adequately cool the shield. This prediction needs to be experimentally evaluated, especially for shields with complex geometries. NASA Marshall Space Flight Center has developed the experience and facilities necessary to do this evaluation in its Early Flight Fission - Test Facility (EFF-TF).

  15. Biological mine water treatment operating a one stage reactor system

    CSIR Research Space (South Africa)

    Baloyi, MJ

    2006-05-01

    Full Text Available cuttings, the source of cellulose. The total experimental period was 113 days, which was divided over 4 periods resulting from the addition of fresh grass cuttings and the feed water flow rate. It was concluded from this study that the microorganisms from...

  16. Environmentally assisted cracking in Light Water Reactors. Volume 16: Semiannual report, October 1992--March 1993

    Energy Technology Data Exchange (ETDEWEB)

    Chung, H.M.; Chopra, O.K.; Ruther, W.E.; Kassner, T.F.; Michaud, W.F.; Park, J.Y.; Sanecki, J.E.; Shack, W.J.

    1993-09-01

    This report summarizes work performed by Argonne National Laboratory on fatigue and environmentally assisted cracking (EAC) in light water reactors (LWRs) during the six months from October 1992 to March 1993. Fatigue and EAC of piping, pressure vessels, and core components in LWRs are important concerns as extended reactor lifetimes are envisaged. Topics that have been investigated include (1) fatigue of low-alloy steel used in piping, steam generators, and reactor pressure vessels. (2) EAC of cast stainless steels (SSs), (3) radiation-induced segregation and irradiation-assisted stress corrosion cracking of Type 304 SS after accumulation of relatively high fluence, and (4) EAC of low-alloy steels. Fatigue tests were conducted on medium-sulfur-content A106-Gr B piping and A533-Gr B pressure vessel steels in simulated PWR water and in air. Additional crack growth data were obtained on fracture-mechanics specimens of cast austenitic SSs in the as-received and thermally aged conditions and chromium-nickel-plated A533-Gr B steel in simulated boiling-water reactor (BWR) water at 289{degrees}C. The data were compared with predictions based on crack growth correlations for ferritic steels in oxygenated water and correlations for wrought austenitic SS in oxygenated water developed at ANL and rates in air from Section XI of the ASME Code. Microchemical and microstructural changes in high- and commercial-purity Type 304 SS specimens from control-blade absorber tubes and a control-blade sheath from operating BWRs were studied by Auger electron spectroscopy and scanning electron microscopy.

  17. Radiation transport out from the reactor core: to decouple or not to decouple

    Science.gov (United States)

    Burn, Kenneth W.; Console Camprini, Patrizio

    2017-09-01

    In the framework of the extension of the lifetime of currently operating reactors as well as of issues connected to decommissioning, accurate calculations of neutron and gamma responses outside the reactor core are increasingly being sought. Recently Monte Carlo calculations have been extended to provide a deep penetration capability incorporated within the eigenvalue calculation. This allows, in principle, neutron and gamma ray responses quite far outside the fissile region to be calculated within the same source-iteration scheme employed to define the neutronic responses in the fissile zone. In this paper, the new algorithm is compared to the classic decoupled approach - an eigenvalue calculation followed by a fixed source one - with the point of decoupling chosen as the fission sites. Two contrasting sample problems are discussed: a small fast research reactor and a large GEN-III Pressurized Water Reactor. The latter problem highlights the role of superhistories in maintaining the fundamental mode.

  18. Radiation transport out from the reactor core: to decouple or not to decouple

    Directory of Open Access Journals (Sweden)

    Burn Kenneth W.

    2017-01-01

    Full Text Available In the framework of the extension of the lifetime of currently operating reactors as well as of issues connected to decommissioning, accurate calculations of neutron and gamma responses outside the reactor core are increasingly being sought. Recently Monte Carlo calculations have been extended to provide a deep penetration capability incorporated within the eigenvalue calculation. This allows, in principle, neutron and gamma ray responses quite far outside the fissile region to be calculated within the same source-iteration scheme employed to define the neutronic responses in the fissile zone. In this paper, the new algorithm is compared to the classic decoupled approach - an eigenvalue calculation followed by a fixed source one - with the point of decoupling chosen as the fission sites. Two contrasting sample problems are discussed: a small fast research reactor and a large GEN-III Pressurized Water Reactor. The latter problem highlights the role of superhistories in maintaining the fundamental mode.

  19. Assessment of Water Ingress Accidents in a Modular High-Temperature Gas-Cooled Reactor

    OpenAIRE

    Zhang, Z.; Dong, Y; Scherer, W

    2005-01-01

    Severe water ingress accidents in the 200-MW HTR-module were assessed to determine the safety margins of modular pebble-bed high-temperature gas-cooled reactors (HTR-module). The 200-MW HTR-module was designed by Siemens under the criteria that no active safety protection systems were necessary because of its inherent safe nature. For simulating the behavior of the HTR-module during severe water ingress accidents, a water, steam, and helium multiphase cavity model was developed and implemente...

  20. Implications for accident management of adding water to a degrading reactor core

    Energy Technology Data Exchange (ETDEWEB)

    Kuan, P.; Hanson, D.J.; Pafford, D.J.; Quick, K.S.; Witt, R.J. [EG and G Idaho, Inc., Idaho Falls, ID (United States)

    1994-02-01

    This report evaluates both the positive and negative consequences of adding water to a degraded reactor core during a severe accident. The evaluation discusses the earliest possible stage at which an accident can be terminated and how plant personnel can best respond to undesired results. Specifically discussed are (a) the potential for plant personnel to add water for a range of severe accidents, (b) the time available for plant personnel to act, (c) possible plant responses to water added during the various stages of core degradation, (d) plant instrumentation available to understand the core condition and (e) the expected response of the instrumentation during the various stages of severe accidents.

  1. Secondary flows in the cooling channels of the high-performance light-water reactor

    Energy Technology Data Exchange (ETDEWEB)

    Laurien, E.; Wintterle, Th. [Stuttgart Univ., Institute for Nuclear Technolgy and Energy Systems (IKE) (Germany)

    2007-07-01

    The new design of a High-Performance Light-Water Reactor (HPLWR) involves a three-pass core with an evaporator region, where the compressed water is heated above the pseudo-critical temperature, and two superheater regions. Due to the strong dependency of the supercritical water density on the temperature significant mass transfer between neighboring cooling channels is expected if the temperature is unevenly distributed across the fuel element. An inter-channel flow is then superimposed to the secondary flow vortices induced by the non-isotropy of turbulence. In order to gain insight into the resulting flow patterns as well as into temperature and density distributions within the various subchannels of the fuel element CFD (Computational Fluid Dynamics) calculations for the 1/8 fuel element are performed. For simplicity adiabatic boundary conditions at the moderator box and the fuel element box are assumed. Our investigation confirms earlier results obtained by subchannel analysis that the axial mass flux is significantly reduced in the corner subchannel of this fuel element resulting in a net mass flux towards the neighboring subchannels. Our results provide a first estimation of the magnitude of the secondary flows in the pseudo-critical region of a supercritical light-water reactor. Furthermore, it is demonstrated that CFD is an efficient tool for investigations of flow patterns within nuclear reactor fuel elements. (authors)

  2. Model reactor for photocatalytic degradation of persistent chemicals in ponds and waste water.

    Science.gov (United States)

    Franke, R; Franke, C

    1999-12-01

    A laboratory scale flow-through model reactor for the degradation of persistent chemicals using titanium dioxide (TiO2) as photocatalyst immobilized on glass beads is presented. In the test system with a volume of 18 L contaminated water is pumped to the upper part of the floating reactor and flows over the coated beads which are exposed to UV-radiation. The degradation of two dyes of different persistence was investigated. Primary degradation of methylene blue did not fit a first order kinetic due to coincident adsorption onto the photocatalyst and direct photolysis, resulting in a half-life of 6 h. A filtrate of a green algae suspension accelerated the colour removal. In contrast, reactive red 2 was degraded only by photocatalysis; neither adsorption nor direct photolysis led to a colour removal. The course of primary degradation followed a first order kinetic with a half-life of 18 h and a rate constant of 0.04 h-1. Analysis of the degradation products indicated mineralization by detection of NO2- and NO3-, accompanied by a decrease of pH and an increase of conductivity. A successful adaptation of the model reactor (scale 1:10) to dimensions required for surface waters and waste water treatment plants would be a cost-efficient and environmentally sustainable application of photocatalysis for the treatment of industrially polluted water and could be of relevance for third world countries, particularly those favoured by high solar radiation.

  3. Boiling water reactor in a prestressed reinforced concrete vessel for an atomic central heating-and-power plant

    Energy Technology Data Exchange (ETDEWEB)

    Tokarev, Yu.I.; Sokolov, I.N.; Skvortsov, S.A.; Sidorov, A.M.; Krauze, L.V.

    1978-04-01

    The possibility of using a boiling water reactor in a prestressed reinforced concrete vessel for an atomic central heating-and-power plant (CHPP) was considered, with design features of the reactor intended for a two-purpose plant. A prestressed reinforced concrete vessel and integral arrangement of the primary circuit ensured reliability of the atomic CHPP using various CHPP flowsheets.

  4. Comparison of Standard Light Water Reactor Cross-Section Libraries using the United States Nuclear Regulatory Commission Boiling Water Reactor Benchmark Problem

    Directory of Open Access Journals (Sweden)

    Kulesza Joel A.

    2016-01-01

    Full Text Available This paper describes a comparison of contemporary and historical light water reactor shielding and pressure vessel dosimetry cross-section libraries for a boiling water reactor calculational benchmark problem. The calculational benchmark problem was developed at Brookhaven National Laboratory by the request of the U. S. Nuclear Regulatory Commission. The benchmark problem was originally evaluated by Brookhaven National Laboratory using the Oak Ridge National Laboratory discrete ordinates code DORT and the BUGLE-93 cross-section library. In this paper, the Westinghouse RAPTOR-M3G three-dimensional discrete ordinates code was used. A variety of cross-section libraries were used with RAPTOR-M3G including the BUGLE93, BUGLE-96, and BUGLE-B7 cross-section libraries developed at Oak Ridge National Laboratory and ALPAN-VII.0 developed at Westinghouse. In comparing the calculated fast reaction rates using the four aforementioned cross-section libraries in the pressure vessel capsule, for six dosimetry reaction rates, a maximum relative difference of 8% was observed. As such, it is concluded that the results calculated by RAPTOR-M3G are consistent with the benchmark and further that the different vintage BUGLE cross-section libraries investigated are largely self-consistent.

  5. Radioactive Carbon Isotope Monitoring System Based on Cavity Ring-down Laser Spectroscopy for Decommissioning Process of Nuclear Facilities

    Science.gov (United States)

    Tomita, Hideki; Watanabe, Kenichi; Takiguchi, Yu; Kawarabayashi, Jun; Iguchi, Tetsuo

    In decommissioning process of nuclear facilities, large amount of radioactive isotopes are discharged as waste. Radioactive carbon isotope (14C) is one of the key nuclides to determine the upper limit of concentration in the waste disposal. In particular, 14C on the graphite reactor decommissioning should be separated from stable carbon isotopes (12C and 13C) and monitored for the public health and safety. We propose an isotope analysis system based on cavity ring-down laser spectroscopy (CRDS) to monitor the carbon isotopes (12C, 13C and 14C) in the isotope separation process for the graphite reactor decommissioning. This system is compact and suitable for a continuous monitoring, because the concentration of molecules including the carbon isotope is derived from its photo absorbance with ultra high sensitive laser absorption spectroscopy. Here are presented the necessary conditions of CRDS system for 14C isotope analysis through the preliminary experimental results of 13C isotope analysis with a prototype system.

  6. The Study on Domestic and Foreign Cases for Decommissioning of DPRK Nuclear Facilities

    Energy Technology Data Exchange (ETDEWEB)

    Baek, Ye Ji; Hhu, Joo Youn; Lee, Jung Hyun; Hwang, Yong Soo [Korea Institute of Nuclear Non-proliferation and Control, Daejeon (Korea, Republic of)

    2016-05-15

    This study was able to analyze domestic and foreign cases, and collect data on the approximate amount of waste and time required time; however, data on applied technology, input manpower, required cost, and waste disposal method was insufficient. DPRK activities such as nuclear weapon development or nuclear testing not only threaten our country's security but also have an adverse effect on nuclear nonproliferation and security in the international society. Therefore, denuclearization of the DPRK is prior task that is essential to peace on the Korean Peninsula. The fundamental purpose of denuclearization of the DPRK is to safely decommission facilities related to developing nuclear weapons and to depose related radioactive waste and nuclear materials. Understanding descriptive references and physical properties of the facility and its purpose important for decommissioning nuclear facilities. Although it was impossible to collect data on DPRK nuclear facilities to perform complete decommissioning, we were able to understand the process used at DPRK nuclear facilities with open source data. This study has been conducted to establish overall measures for decommissioning DPRK nuclear facilities. DPRK nuclear facilities in this study include a IRT- 2000 type nuclear research reactor, a 5 MWe graphite moderated reactor, nuclear fuel fabrication facility, and a nuclear fuel reprocessing facility, which are considered as facilities that produce or manufacture nuclear materials needed for nuclear weapons or related to such activities.

  7. Removal of natural organic matter and arsenic from water by electrocoagulation/flotation continuous flow reactor

    Energy Technology Data Exchange (ETDEWEB)

    Mohora, Emilijan, E-mail: emohora@ifc.org [University of Novi Sad Faculty of Sciences, Department of Chemistry, Biochemistry and Environmental Protection, Trg D. Obradovica 3, 21000 Novi Sad (Serbia); Roncevic, Srdjan; Dalmacija, Bozo; Agbaba, Jasmina; Watson, Malcolm; Karlovic, Elvira; Dalmacija, Milena [University of Novi Sad Faculty of Sciences, Department of Chemistry, Biochemistry and Environmental Protection, Trg D. Obradovica 3, 21000 Novi Sad (Serbia)

    2012-10-15

    Highlights: Black-Right-Pointing-Pointer A continuous electrocoagulation/flotation reactor was designed built and operated. Black-Right-Pointing-Pointer Highest NOM removal according to UV{sub 254} was 77% relative to raw groundwater. Black-Right-Pointing-Pointer Highest NOM removal accordance to DOC was 71%, relative to raw groundwater. Black-Right-Pointing-Pointer Highest As removal archived was 85% (6.2 {mu}g/l), relative to raw groundwater. Black-Right-Pointing-Pointer Specific reactor energy and electrode consumption was 1.7 kWh/m{sup 3} and 66 g Al/m{sup 3}. - Abstract: The performance of the laboratory scale electrocoagulation/flotation (ECF) reactor in removing high concentrations of natural organic matter (NOM) and arsenic from groundwater was analyzed in this study. An ECF reactor with bipolar plate aluminum electrodes was operated in the horizontal continuous flow mode. Electrochemical and flow variables were optimized to examine ECF reactor contaminants removal efficiency. The optimum conditions for the process were identified as groundwater initial pH 5, flow rate = 4.3 l/h, inter electrode distance = 2.8 cm, current density = 5.78 mA/cm{sup 2}, A/V ratio = 0.248 cm{sup -1}. The NOM removal according to UV{sub 254} absorbance and dissolved organic matter (DOC) reached highest values of 77% and 71% respectively, relative to the raw groundwater. Arsenic removal was 85% (6.2 {mu}g As/l) relative to raw groundwater, satisfying the drinking water standards. The specific reactor electrical energy consumption was 17.5 kWh/kg Al. The specific aluminum electrode consumption was 66 g Al/m{sup 3}. According to the obtained results, ECF in horizontal continuous flow mode is an energy efficient process to remove NOM and arsenic from groundwater.

  8. A Flooding Induced Station Blackout Analysis for a Pressurized Water Reactor Using the RISMC Toolkit

    Directory of Open Access Journals (Sweden)

    Diego Mandelli

    2015-01-01

    Full Text Available In this paper we evaluate the impact of a power uprate on a pressurized water reactor (PWR for a tsunami-induced flooding test case. This analysis is performed using the RISMC toolkit: the RELAP-7 and RAVEN codes. RELAP-7 is the new generation of system analysis codes that is responsible for simulating the thermal-hydraulic dynamics of PWR and boiling water reactor systems. RAVEN has two capabilities: to act as a controller of the RELAP-7 simulation (e.g., component/system activation and to perform statistical analyses. In our case, the simulation of the flooding is performed by using an advanced smooth particle hydrodynamics code called NEUTRINO. The obtained results allow the user to investigate and quantify the impact of timing and sequencing of events on system safety. In addition, the impact of power uprate is determined in terms of both core damage probability and safety margins.

  9. International academic program in technologies of light-water nuclear reactors. Phases of development and implementation

    Science.gov (United States)

    Geraskin, N. I.; Glebov, V. B.

    2017-01-01

    The results of implementation of European educational projects CORONA and CORONA II dedicated to preserving and further developing nuclear knowledge and competencies in the area of technologies of light-water nuclear reactors are analyzed. Present article addresses issues of design and implementation of the program for specialized training in the branch of technologies of light-water nuclear reactors. The systematic approach has been used to construct the program for students of nuclear specialties, which corresponding to IAEA standards and commonly accepted nuclear principles recognized in the European Union. Possibilities of further development of the international cooperation between countries and educational institutions are analyzed. Special attention is paid to e-learning/distance training, nuclear knowledge preservation and interaction with European Nuclear Education Network.

  10. Mixing of cooling water in the mixing chambers of the HPLWR-High Performance Light Water Reactor

    Energy Technology Data Exchange (ETDEWEB)

    Wank, Alexander, E-mail: alexander.wank@siemens.co [Karlsruhe Institute of Technology (KIT), Institute for Nuclear and Energy Technologies, P.O. Box 3640, 76021 Karlsruhe (Germany); Starflinger, Joerg; Schulenberg, Thomas [Karlsruhe Institute of Technology (KIT), Institute for Nuclear and Energy Technologies, P.O. Box 3640, 76021 Karlsruhe (Germany); Laurien, Eckart [University of Stuttgart, Institute for Nuclear Technology and Energy Systems (IKE) Pfaffenwaldring 31, D-70550 Stuttgart (Germany)

    2010-10-15

    The High Performance Light Water Reactor (HPLWR), a supercritical water cooled reactor concept with multiple heat-up steps, requires efficient mixing of the coolant between these steps to minimize hot spots in the core. Analyzing and improving the mixing in the mixing chamber above the core, situated between evaporator and superheater assemblies, and below the core, between the first and second superheater, is one of the challenges in the design process of the HPLWR. Different measures to enhance mixing have been studied with CFD analyses, in which a new design approach has been applied to the upper mixing chamber. It simplifies the complex structures and takes the effects of the disregarded structures into account by introducing source terms into the momentum equations.

  11. Warm Water Oxidation Verification - Scoping and Stirred Reactor Tests

    Energy Technology Data Exchange (ETDEWEB)

    Braley, Jenifer C.; Sinkov, Sergey I.; Delegard, Calvin H.; Schmidt, Andrew J.

    2011-06-15

    Scoping tests to evaluate the effects of agitation and pH adjustment on simulant sludge agglomeration and uranium metal oxidation at {approx}95 C were performed under Test Instructions(a,b) and as per sections 5.1 and 5.2 of this Test Plan prepared by AREVA. (c) The thermal testing occurred during the week of October 4-9, 2010. The results are reported here. For this testing, two uranium-containing simulant sludge types were evaluated: (1) a full uranium-containing K West (KW) container sludge simulant consisting of nine predominant sludge components; (2) a 50:50 uranium-mole basis mixture of uraninite [U(IV)] and metaschoepite [U(VI)]. This scoping study was conducted in support of the Sludge Treatment Project (STP) Phase 2 technology evaluation for the treatment and packaging of K-Basin sludge. The STP is managed by CH2M Hill Plateau Remediation Company (CHPRC) for the U.S. Department of Energy. Warm water ({approx}95 C) oxidation of sludge, followed by immobilization, has been proposed by AREVA and is one of the alternative flowsheets being considered to convert uranium metal to UO{sub 2} and eliminate H{sub 2} generation during final sludge disposition. Preliminary assessments of warm water oxidation have been conducted, and several issues have been identified that can best be evaluated through laboratory testing. The scoping evaluation documented here was specifically focused on the issue of the potential formation of high strength sludge agglomerates at the proposed 95 C process operating temperature. Prior hydrothermal tests conducted at 185 C produced significant physiochemical changes to genuine sludge, including the formation of monolithic concretions/agglomerates that exhibited shear strengths in excess of 100 kPa (Delegard et al. 2007).

  12. Establishment of a Hub for the Light Water Reactor Sustainability Online Monitoring Community

    Energy Technology Data Exchange (ETDEWEB)

    Nancy J. Lybeck; Magdy S. Tawfik; Binh T. Pham

    2011-08-01

    Implementation of online monitoring and prognostics in existing U.S. nuclear power plants will involve coordinating the efforts of national laboratories, utilities, universities, and private companies. Internet-based collaborative work environments provide necessary communication tools to facilitate interaction between geographically diverse participants. Available technologies were considered, and a collaborative workspace was established at INL as a hub for the light water reactor sustainability online monitoring community.

  13. Multi-physical developments for safety related investigations of low moderated boiling water reactors

    Energy Technology Data Exchange (ETDEWEB)

    Schlenker, Markus Thomas

    2014-12-19

    The main objective of this dissertation is the development and optimization of a low moderated boiling water reactor (BWR) core with improved fuel utilization to be incorporated in a Gen II BWR nuclear power plant. The assessment of the new core design is done by comparing it with a full MOX BWR core design regarding neutron physical and thermal-hydraulic design and safety criteria (e.g. inherent reactivity coefficients) and different sustainability parameters (e.g. conversion ratio).

  14. Light-water-reactor safety research program: quarterly progress report, July--September 1977

    Energy Technology Data Exchange (ETDEWEB)

    None

    1978-01-01

    Progress is summarized on the Argonne National Laboratory work performed during July, August, and September 1977 on water-reactor-safety problems. The following research and development areas are covered: (1) loss-of-coolant accident research: heat transfer and fluid dynamics; (2) transient fuel response and fission-product release program; (3) mechanical properties of Zircaloy containing oxygen; and (4) steam-explosion studies.

  15. Literature search on Light Water Reactor (LWR) fuel and absorber rod fabrication, 1960--1976

    Energy Technology Data Exchange (ETDEWEB)

    Sample, C R [comp.

    1977-02-01

    A literature search was conducted to provide information supporting the design of a conceptual Light Water Reactor (LWR) Fuel Fabrication plant. Emphasis was placed on fuel processing and pin bundle fabrication, effects of fuel impurities and microstructure on performance and densification, quality assurance, absorber and poison rod fabrication, and fuel pin welding. All data have been taken from publicly available documents, journals, and books. This work was sponsored by the Finishing Processes-Mixed Oxide (MOX) Fuel Fabrication Studies program at HEDL.

  16. Analysis of a Partial MOX Core Design with Tritium Targets for Light Water Reactors

    Energy Technology Data Exchange (ETDEWEB)

    Anistratov, Dmitriy Y. [Texas A & M Univ., College Station, TX (United States); Adams, Marvin L. [Texas A & M Univ., College Station, TX (United States)

    1998-04-19

    This report constitutes tangible and verifiable deliverable associated with the task To study the effects of using WG MOX fuel in tritium-producing LWR” of the subproject Water Reactor Options for Disposition of Plutonium. The principal investigators of this subproject are Naeem M. Abdurrahman of the University of Texas at Austin and Marvin L. Adams of Texas A&M University. This work was sponsored by the Amarillo National Resource Center for Plutonium.

  17. Defluoridation of drinking water by electrocoagulation/electroflotation in a stirred tank reactor with a comparative performance to an external-loop airlift reactor

    Energy Technology Data Exchange (ETDEWEB)

    Essadki, A.H., E-mail: essadki@hotmail.com [Ecole Superieure de Technologie de Casablanca, BP 8012, Oasis, Casablanca (Morocco); Gourich, B. [Ecole Superieure de Technologie de Casablanca, BP 8012, Oasis, Casablanca (Morocco); Vial, Ch. [Laboratoire de Genie Chimique et Biochimique, LGCB-UBP/ENSCCF, 24 avenue des Landais, BP 206, 63174 Aubiere Cedex (France); Delmas, H. [Laboratoire de Genie Chimique, ENSIACET-INPT, 5 rue Paulin Talabot, 31106 Toulouse (France); Bennajah, M. [Ecole Superieure de Technologie de Casablanca, BP 8012, Oasis, Casablanca (Morocco); Laboratoire de Genie Chimique, ENSIACET-INPT, 5 rue Paulin Talabot, 31106 Toulouse (France)

    2009-09-15

    Defluoridation using batch electrocoagulation/electroflotation (EC/EF) was carried out in two reactors for comparison purpose: a stirred tank reactor (STR) close to a conventional EC cell and an external-loop airlift reactor (ELAR) that was recently described as an innovative reactor for EC. The respective influences of current density, initial concentration and initial pH on the efficiency of defluoridation were investigated. The same trends were observed in both reactors, but the efficiency was higher in the STR at the beginning of the electrolysis, whereas similar values were usually achieved after 15 min operation. The influence of the initial pH was explained using the analyses of sludge composition and residual soluble aluminum species in the effluents, and it was related to the prevailing mechanisms of defluoridation. Fluoride removal and sludge reduction were both favored by an initial pH around 4, but this value required an additional pre-treatment for pH adjustment. Finally, electric energy consumption was similar in both reactors when current density was lower than 12 mA/cm{sup 2}, but mixing and complete flotation of the pollutants were achieved without additional mechanical power in the ELAR, using only the overall liquid recirculation induced by H{sub 2} microbubbles generated by water electrolysis, which makes subsequent treatments easier to carry out.

  18. Defluoridation of drinking water by electrocoagulation/electroflotation in a stirred tank reactor with a comparative performance to an external-loop airlift reactor.

    Science.gov (United States)

    Essadki, A H; Gourich, B; Vial, Ch; Delmas, H; Bennajah, M

    2009-09-15

    Defluoridation using batch electrocoagulation/electroflotation (EC/EF) was carried out in two reactors for comparison purpose: a stirred tank reactor (STR) close to a conventional EC cell and an external-loop airlift reactor (ELAR) that was recently described as an innovative reactor for EC. The respective influences of current density, initial concentration and initial pH on the efficiency of defluoridation were investigated. The same trends were observed in both reactors, but the efficiency was higher in the STR at the beginning of the electrolysis, whereas similar values were usually achieved after 15min operation. The influence of the initial pH was explained using the analyses of sludge composition and residual soluble aluminum species in the effluents, and it was related to the prevailing mechanisms of defluoridation. Fluoride removal and sludge reduction were both favored by an initial pH around 4, but this value required an additional pre-treatment for pH adjustment. Finally, electric energy consumption was similar in both reactors when current density was lower than 12mA/cm(2), but mixing and complete flotation of the pollutants were achieved without additional mechanical power in the ELAR, using only the overall liquid recirculation induced by H(2) microbubbles generated by water electrolysis, which makes subsequent treatments easier to carry out.

  19. 10 CFR Appendix J to Part 50 - Primary Reactor Containment Leakage Testing for Water-Cooled Power Reactors

    Science.gov (United States)

    2010-01-01

    ...-Cooled Power Reactors J Appendix J to Part 50 Energy NUCLEAR REGULATORY COMMISSION DOMESTIC LICENSING OF PRODUCTION AND UTILIZATION FACILITIES Pt. 50, App. J Appendix J to Part 50—Primary Reactor Containment... basis accident and specified either in the technical specification or associated bases. J. Pt (p.s.i.g...

  20. Light Water Reactor Sustainability Program Status of Silicon Carbide Joining Technology Development

    Energy Technology Data Exchange (ETDEWEB)

    Bragg-Sitton, Shannon M. [Idaho National Lab. (INL), Idaho Falls, ID (United States)

    2013-09-01

    Advanced, accident tolerant nuclear fuel systems are currently being investigated for potential application in currently operating light water reactors (LWR) or in reactors that have attained design certification. Evaluation of potential options for accident tolerant nuclear fuel systems point to the potential benefits of silicon carbide (SiC) relative to Zr-based alloys, including increased corrosion resistance, reduced oxidation and heat of oxidation, and reduced hydrogen generation under steam attack (off-normal conditions). If demonstrated to be applicable in the intended LWR environment, SiC could be used in nuclear fuel cladding or other in-core structural components. Achieving a SiC-SiC joint that resists corrosion with hot, flowing water, is stable under irradiation and retains hermeticity is a significant challenge. This report summarizes the current status of SiC-SiC joint development work supported by the Department of Energy Light Water Reactor Sustainability Program. Significant progress has been made toward SiC-SiC joint development for nuclear service, but additional development and testing work (including irradiation testing) is still required to present a candidate joint for use in nuclear fuel cladding.

  1. IAEA coordinated research project on thermal-hydraulics of Supercritical Water-Cooled Reactors (SCWRs)

    Energy Technology Data Exchange (ETDEWEB)

    Yamada, K. [Vienna International Centre, P.O. Box 100, 1400 Vienna (Austria); Aksan, S. N. [International Atomic Energy Agency, 1400 Vienna (Austria)

    2012-07-01

    The Supercritical Water-Cooled Reactor (SCWR) is an innovative water-cooled reactor concept, which uses supercritical pressure water as reactor coolant. It has been attracting interest of many researchers in various countries mainly due to its benefits of high thermal efficiency and simple primary systems, resulting in low capital cost. The IAEA started in 2008 a Coordinated Research Project (CRP) on Thermal-Hydraulics of SCWRs as a forum to foster the exchange of technical information and international collaboration in research and development. This paper summarizes the activities and current status of the CRP, as well as major progress achieved to date. At present, 15 institutions closely collaborate in several tasks. Some organizations have been conducting thermal-hydraulics experiments and analysing the data, and others have been participating in code-to-test and/or code-to-code benchmark exercises. The expected outputs of the CRP are also discussed. Finally, the paper introduces several IAEA activities relating to or arising from the CRP. (authors)

  2. Supercritical Water Reactor (SCWR) - Survey of Materials Research and Development Needs to Assess Viability

    Energy Technology Data Exchange (ETDEWEB)

    Philip E. MacDonald

    2003-09-01

    Supercritical water-cooled reactors (SCWRs) are among the most promising advanced nuclear systems because of their high thermal efficiency [i.e., about 45% vs. 33% of current light water reactors (LWRs)] and considerable plant simplification. SCWRs achieve this with superior thermodynamic conditions (i.e., high operating pressure and temperature), and by reducing the containment volume and eliminating the need for recirculation and jet pumps, pressurizer, steam generators, steam separators and dryers. The reference SCWR design in the U.S. is a direct cycle, thermal spectrum, light-water-cooled and moderated reactor with an operating pressure of 25 MPa and inlet/outlet coolant temperature of 280/500 °C. The inlet flow splits, partly to a down-comer and partly to a plenum at the top of the reactor pressure vessel to flow downward through the core in special water rods to the inlet plenum. This strategy is employed to provide good moderation at the top of the core, where the coolant density is only about 15-20% that of liquid water. The SCWR uses a power conversion cycle similar to that used in supercritical fossil-fired plants: high- intermediate- and low-pressure turbines are employed with one moisture-separator re-heater and up to eight feedwater heaters. The reference power is 3575 MWt, the net electric power is 1600 MWe and the thermal efficiency is 44.8%. The fuel is low-enriched uranium oxide fuel and the plant is designed primarily for base load operation. The purpose of this report is to survey existing materials for fossil, fission and fusion applications and identify the materials research and development needed to establish the SCWR viabilitya with regard to possible materials of construction. The two most significant materials related factors in going from the current LWR designs to the SCWR are the increase in outlet coolant temperature from 300 to 500 °C and the possible compatibility issues associated with the supercritical water environment.

  3. Deactivation, Decontamination and Decommissioning Project Summaries

    Energy Technology Data Exchange (ETDEWEB)

    Peterson, David Shane; Webber, Frank Laverne

    2001-07-01

    This report is a compilation of summary descriptions of Deactivation, Decontamination and Decommissioning, and Surveillance and Maintenance projects planned for inactive facilities and sites at the INEEL from FY-2002 through FY-2010. Deactivations of contaminated facilities will produce safe and stable facilities requiring minimal surveillance and maintenance pending further decontamination and decommissioning. Decontamination and decommissioning actions remove contaminated facilities, thus eliminating long-term surveillance and maintenance. The projects are prioritized based on risk to DOE-ID, the public, and the environment, and the reduction of DOE-ID mortgage costs and liability at the INEEL.

  4. Environmentally-Assisted Cracking of Low-Alloy Reactor Pressure Vessel Steels under Boiling Water Reactor Conditions

    Energy Technology Data Exchange (ETDEWEB)

    Seifert, H.P.; Ritter, S

    2002-02-01

    The present report summarizes the experimental work performed by PSI on the environmentally-assisted cracking (EAC) of low-alloy steels (LAS) in the frame of the RIKORR-project during the period from January 2000 to August 2001. Within this project, the EAC crack growth behaviour of different low-alloy reactor pressure vessel (RPV) steels, weld filler and weld heat-affected zone materials is investigated under simulated transient and steady-state BWR/NWC power operation conditions. The EAC crack growth behaviour of different low-alloy RPV steels was characterized by slow rising load (SRL) / low-frequency corrosion fatigue (LFCF) and constant load tests with pre-cracked fracture mechanics specimens in oxygenated high-temperature water at temperatures of either 288, 250, 200 or 150 C. These tests revealed the following important interim results: Under low-flow and highly oxidizing (ECP >= 100 mV SHE) conditions, the ASME XI 'wet' reference fatigue crack growth curve could be significantly exceeded by cyclic fatigue loading at low frequencies (<0.001 Hz), at high and low load-ratios R, and by ripple loading near to DKth fatigue thresholds. The BWR VIP 60 SCC disposition lines may be significantly or slightly exceeded (even in steels with a low sulphur content) in the case of small load fluctuations at high load ratios (ripple loading) or at intermediate temperatures (200 -250 C) in RPV materials, which show a distinct susceptibility to dynamic strain ageing (DSA). (author)

  5. Measurements Methods for the analysis of Nuclear Reactors Thermal Hydraulic in Water Scaled Facilities

    Science.gov (United States)

    Spaccapaniccia, C.; Planquart, P.; Buchlin, J. M. AB(; ), AC(; )

    2018-01-01

    The Belgian nuclear research institute (SCK•CEN) is developing MYRRHA. MYRRHA is a flexible fast spectrum research reactor, conceived as an accelerator driven system (ADS). The configuration of the primary loop is pool-type: the primary coolant and all the primary system components (core and heat exchangers) are contained within the reactor vessel, while the secondary fluid is circulating in the heat exchangers. The primary coolant is Lead Bismuth Eutectic (LBE). The recent nuclear accident of Fukushima in 2011 changed the requirements for the design of new reactors, which should include the possibility to remove the residual decay heat through passive primary and secondary systems, i.e. natural convection (NC). After the reactor shut down, in the unlucky event of propeller failures, the primary and secondary loops should be able to remove the decay heat in passive way (Natural Convection). The present study analyses the flow and the temperature distribution in the upper plenum by applying laser imaging techniques in a laboratory scaled water model. A parametric study is proposed to study stratification mitigation strategies by varying the geometry of the buffer tank simulating the upper plenum.

  6. Fuel Sustainability And Actinide Production Of Doping Minor Actinide In Water-Cooled Thorium Reactor

    Science.gov (United States)

    Permana, Sidik

    2017-07-01

    Fuel sustainability of nuclear energy is coming from an optimum fuel utilization of the reactor and fuel breeding program. Fuel cycle option becomes more important for fuel cycle utilization as well as fuel sustainability capability of the reactor. One of the important issues for recycle fuel option is nuclear proliferation resistance issue due to production plutonium. To reduce the proliferation resistance level, some barriers were used such as matrial barrier of nuclear fuel based on isotopic composition of even mass number of plutonium isotope. Analysis on nuclear fuel sustainability and actinide production composition based on water-cooled thorium reactor system has been done and all actinide composition are recycled into the reactor as a basic fuel cycle scheme. Some important parameters are evaluated such as doping composition of minor actinide (MA) and volume ratio of moderator to fuel (MFR). Some feasible parameters of breeding gains have been obtained by additional MA doping and some less moderation to fuel ratios (MFR). The system shows that plutonium and MA are obtained low compositions and it obtains some higher productions of even mass plutonium, which is mainly Pu-238 composition, as a control material to protect plutonium to be used as explosive devices.

  7. A study on the irradiation embrittlement and recovery characteristics of light water reactor pressure vessel steels

    Energy Technology Data Exchange (ETDEWEB)

    Chi, Se Hwan; Hong, Jun Hwa; Lee, Bong Sang; Oh, Jong Myung; Song, Sook Hyang; Milan, Brumovsky [NRI Czech (Czech Republic)

    1999-03-01

    The neutron irradiation embrittlement phenomenon of light water RPV steels greatly affects the life span for safe operation of a reactor. Reliable evaluation and prediction of the embrittlement of RPV steels, especially of aged reactors, are of importance to the safe operation of a reactor. In addition, the thermal recovery of embrittled RPV has been recognized as an option for life extension. This study aimed to tracer/refine available technologies for embrittlement characterization and prediction, to prepare relevant materials for several domestic RPV steels of the embrittlement and recovery, and to find out possible remedy for steel property betterment. Small specimen test techniques, magnetic measurement techniques, and the Meechan and Brinkmann's recovery curve analysis method were examined/applied as the evaluation techniques. Results revealed a high irradiation sensitivity in YG 3 RPV steel. Further extended study may be urgently needed. Both the small specimen test technique for the direct determination of fracture toughness, and the magnetic measurement technique for embrittlement evaluation appeared to be continued for the technical improvement and data base preparation. Manufacturing process relevant to the heat treatment appeared to be improved in lowering the irradiation sensitivity of the steel. Further study is needed especially in applying the present techniques to the new structural materials under new irradiation environment of advanced reactors. (author)

  8. Neutron-gamma flux and dose calculations in a Pressurized Water Reactor (PWR

    Directory of Open Access Journals (Sweden)

    Brovchenko Mariya

    2017-01-01

    Full Text Available The present work deals with Monte Carlo simulations, aiming to determine the neutron and gamma responses outside the vessel and in the basemat of a Pressurized Water Reactor (PWR. The model is based on the Tihange-I Belgian nuclear reactor. With a large set of information and measurements available, this reactor has the advantage to be easily modelled and allows validation based on the experimental measurements. Power distribution calculations were therefore performed with the MCNP code at IRSN and compared to the available in-core measurements. Results showed a good agreement between calculated and measured values over the whole core. In this paper, the methods and hypotheses used for the particle transport simulation from the fission distribution in the core to the detectors outside the vessel of the reactor are also summarized. The results of the simulations are presented including the neutron and gamma doses and flux energy spectra. MCNP6 computational results comparing JEFF3.1 and ENDF-B/VII.1 nuclear data evaluations and sensitivity of the results to some model parameters are presented.

  9. Proceedings of the Water Reactor Fuel Performance Meeting - WRFPM / Top Fuel 2009

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2009-06-15

    SFEN, ENS, SNR, ANS, AESJ, CNS KNS, IAEA and NEA are jointly organizing the 2009 International Water Reactor Fuel Performance / TopFuel 2009 Meeting following the 2008 KNS Water Reactor Performance Meeting held during October 19-23, 2008 in Seoul, Korea. This meeting is held annually on a tri-annual rotational basis in Europe, USA and Asia. In 2009, this meeting will be held in Paris, September 6-10, 2009 in coordination with the Global 2009 Conference at the same date and place. That would lead to a common opening session, some common technical presentations, a common exhibition and common social events. The technical scope of the meeting includes all aspects of nuclear fuel from fuel rod to core design as well as manufacturing, performance in commercial and test reactors or on-going and future developments and trends. Emphasis will be placed on fuel reliability in the general context of nuclear 'Renaissance' and recycling perspective. The meeting includes selectively front and/or back end issues that impact fuel designs and performance. In this frame, the conference track devoted to 'Concepts for transportation and interim storage of spent fuels and conditioned waste' will be shared with 'GLOBAL' conference. Technical Tracks: - 1. Fuel Performance, Reliability and Operational Experience: Fuel operating experience and performance; experience with high burn-up fuels; water side corrosion; stress corrosion cracking; MOX fuel performance; post irradiation data on lead fuel assemblies; radiation effects; water chemistry and corrosion counter-measures. - 2. Transient Fuel Behaviour and Safety Related Issues: Transient fuel behavior and criteria (RIA, LOCA, ATWS, Ramp tests..). Fuel safety-related issues such as PCI (pellet cladding interaction), transient fission gas releases and cladding bursting/ballooning during transient events - Advances in fuel performance modeling and core reload methodology, small and large-scale fuel testing

  10. The current status of nuclear research reactor in Thailand

    Energy Technology Data Exchange (ETDEWEB)

    Sittichai, C.; Kanyukt, R.; Pongpat, P. [Office of Atomic Energy for Peace, Bangkok (Thailand)

    1998-10-01

    Since 1962, the Thai Research Reactor has been serving for various kinds of activities i.e. the production of radioisotopes for medical uses and research and development on nuclear science and technology, for more than three decades. The existing reactor site should be abandoned and relocated to the new suitable site, according to Thai cabinet`s resolution on the 27 December 1989. The decommissioning project for the present reactor as well as the establishment of new nuclear research center were planned. This paper discussed the OAEP concept for the decommissioning programme and the general description of the new research reactor and some related information were also reported. (author)

  11. Welding residual stress distributions for dissimilar metal nozzle butt welds in pressurized water reactors

    Energy Technology Data Exchange (ETDEWEB)

    Kim, Ji Soo; Kim, Ju Hee; Bae, Hong Yeol; OH, Chang Young; Kim, Yun Jae [Korea Univ., Seoul (Korea, Republic of); Lee, Kyungsoo [Korea Electric Power Research Institute, Daejeon (Korea, Republic of); Song, Tae Kwang [Korea Institute of Nuclear Safety, Daejeon (Korea, Republic of)

    2012-02-15

    In pressurized water nuclear reactors, dissimilar metal welds are susceptible to primary water stress corrosion cracking. To access this problem, accurate estimation of welding residual stresses is important. This paper provides general welding residual stress profiles in dissimilar metal nozzle butt welds using finite element analysis. By introducing a simplified shape for dissimilar metal nozzle butt welds, changes in the welding residual stress distribution can be seen using a geometry variable. Based on the results, a welding residual stress profile for dissimilar metal nozzle butt welds is proposed that modifies the existing welding residual stress profile for austenitic pipe butt welds.

  12. Radiological performance of hot water layer system in open pool type reactor

    Directory of Open Access Journals (Sweden)

    Amr Abdelhady

    2013-06-01

    Full Text Available The paper presents the calculated dose rate carried out by using MicroShield code to show the importance of hot water layer system (HWL in 22 MW open pool type reactor from the radiation protection safety point of view. The paper presents the dose rate profiles over the pool surface in normal and abnormal operations of HWL system. The results show that, in case of losing the hot water layer effect, the radiation dose rate profiles over the pool surface will increase from values lower than the worker permissible dose limits to values very higher than the permissible dose limits.

  13. Quarterly technical report on water reactor safety programs sponsored by the Nuclear Regulatory Commission's Division of Reactor Safety Research, July--September 1975

    Energy Technology Data Exchange (ETDEWEB)

    1976-02-01

    Light water reactor safety activities performed during July through September 1975 are summarized. The isothermal blowdown test series of the Semiscale Mod-1 test program has provided data for evaluation of break flow phenomena and analyses of piping flow regimes and pump performance. In the LOFT Program, measurement uncertainties were evaluated. The Thermal Fuels Behavior Program completed two power-cooling-mismatch tests on PWR-type fuel rods to investigate critical heat flux characteristics. Model development and verification efforts of the Reactor Behavior Program included development of the SPLEN1 computer code, subroutines for the FRAP-T code, verification of RELAP4, and results of the Halden Recycle Plutonium Experiment.

  14. A modified firefly algorithm applied to the nuclear reload problem of a pressurized water reactor

    Energy Technology Data Exchange (ETDEWEB)

    Oliveira, Iona Maghali Santos de; Schirru, Roberto, E-mail: ioliveira@con.ufrj.b, E-mail: schirru@lmp.ufrj.b [Universidade Federal do Rio de Janeiro (PEN/COPPE/UFRJ), RJ (Brazil). Coordenacao dos Programas de Pos-Graduacao de Engenharia. Programa de Engenharia Nuclear

    2011-07-01

    The Nuclear Reactor Reload Problem (NRRP) is an issue of great importance and concern in nuclear engineering. It is the problem related with the periodic operation of replacing part of the fuel of a nuclear reactor. Traditionally, this procedure occurs after a period of operation called a cycle, or whenever the nuclear power plant is unable to continue operating at its nominal power. Studied for more than 40 years, the NRRP still remains a challenge for many optimization techniques due to its multiple objectives concerning economics, safety and reactor physics calculations. Characteristics such as non-linearity, multimodality and high dimensionality also make the NRRP a very complex optimization problem. In broad terms, it aims at getting the best arrangement of fuel in the nuclear reactor core that leads to a maximization of the operating time. The primary goal is to design fuel loading patterns (LPs) so that the core produces the required energy output in an economical way, without violating safety limits. Since multiple feasible solutions can be obtained to this problem, judicious optimization is required in order to identify the most economical among them. In this sense, this paper presents a new contribution in this area and introduces a modified firefly algorithm (FA) to perform LPs optimization for a pressurized water reactor. Based on the original FA introduced by Xin-She Yang in 2008, the proposed methodology seems to be very promising as an optimizer to the NRRP. The experiments performed and the comparisons with some well known best performing algorithms from the literature, confirm this statement. (author)

  15. Modeling the behavior of a light-water production reactor target rod

    Energy Technology Data Exchange (ETDEWEB)

    Sherwood, D.J.

    1992-03-01

    Pacific Northwest Laboratory has been conducting a series of in-reactor experiments in the Idaho National Engineering Laboratory (INEL) Advanced Test Reactor (ATR) to determine the amount of tritium released by permeation from a target rod under neutron irradiation. The model discussed in this report was developed from first principles to model the behavior of the first target rod irradiated in the ATR. The model can be used to determine predictive relationships for the amount of tritium that permeates through the target rod cladding during irradiation. The model consists of terms and equations for tritium production, gettering, partial pressure, and permeation, all of which are described in this report. The model addressed only the condition of steady state and features only a single adjustable parameter. The target rod design for producing tritium in a light-water reactor was tested first in the WC-1 in-reactor experiment. During irradiation, tritium is generated in the target rod within the ceramic lithium target material. The target rod has been engineered to limit the release of tritium to the reactor coolant during normal operations. The engineered features are a nickel-plated Zircaloy-4 getter and a barrier coating on the cladding surfaces. The ceramic target is wrapped with the getter material and the resulting ``pencils`` are inserted into the barrier coated cladding. These features of the rod are described in the report, along with the release of tritium from the ceramic target. The steady-state model could be useful for the design procedure of target rod components.

  16. Modeling the behavior of a light-water production reactor target rod

    Energy Technology Data Exchange (ETDEWEB)

    Sherwood, D.J.

    1992-03-01

    Pacific Northwest Laboratory has been conducting a series of in-reactor experiments in the Idaho National Engineering Laboratory (INEL) Advanced Test Reactor (ATR) to determine the amount of tritium released by permeation from a target rod under neutron irradiation. The model discussed in this report was developed from first principles to model the behavior of the first target rod irradiated in the ATR. The model can be used to determine predictive relationships for the amount of tritium that permeates through the target rod cladding during irradiation. The model consists of terms and equations for tritium production, gettering, partial pressure, and permeation, all of which are described in this report. The model addressed only the condition of steady state and features only a single adjustable parameter. The target rod design for producing tritium in a light-water reactor was tested first in the WC-1 in-reactor experiment. During irradiation, tritium is generated in the target rod within the ceramic lithium target material. The target rod has been engineered to limit the release of tritium to the reactor coolant during normal operations. The engineered features are a nickel-plated Zircaloy-4 getter and a barrier coating on the cladding surfaces. The ceramic target is wrapped with the getter material and the resulting pencils'' are inserted into the barrier coated cladding. These features of the rod are described in the report, along with the release of tritium from the ceramic target. The steady-state model could be useful for the design procedure of target rod components.

  17. Solar radiation disinfection of drinking water at temperate latitudes: inactivation rates for an optimised reactor configuration.

    Science.gov (United States)

    Davies, C M; Roser, D J; Feitz, A J; Ashbolt, N J

    2009-02-01

    Solar radiation-driven inactivation of bacteria, virus and protozoan pathogen models was quantified in simulated drinking water at a temperate latitude (34 degrees S). The water was seeded with Enterococcus faecalis, Clostridium sporogenes spores, and P22 bacteriophage, each at ca 1x10(5) mL(-1), and exposed to natural sunlight in 30-L reaction vessels. Water temperature ranged from 17 to 39 degrees C during the experiments lasting up to 6h. Dark controls showed little inactivation and so it was concluded that the inactivation observed was primarily driven by non-thermal processes. The optimised reactor design achieved S90 values (cumulative exposure required for 90% reduction) for the test microorganisms in the range 0.63-1.82 MJ m(-2) of Global Solar Exposure (GSX) without the need for TiO2 as a catalyst. High turbidity (840-920 NTU) only reduced the S(90) value by 0.05). However, inactivation was significantly reduced for E. faecalis and P22 when the transmittance of UV wavelengths was attenuated by water with high colour (140 PtCo units) or a suboptimally transparent reactor lid (prob.SODIS type pasteurization were not produced, non-thermal inactivation alone appeared to offer a viable means for reliably disinfecting low colour source waters by greater than 4 orders of magnitude on sunny days at 34 degrees S latitude.

  18. The use of chemical gel for decontamination during decommissioning of nuclear facilities

    Science.gov (United States)

    Gurau, Daniela; Deju, Radu

    2015-01-01

    A technical research study was developed for testing the decontamination using chemical gels. The study was realized for different type of samples, systems often encountered in the VVR-S nuclear research reactor from Magurele-Romania. The results obtained in the study have demonstrated that the decontamination gels could be an efficient way to reduce or to eliminate the surface contamination of buildings or equipment's, minimizing the potential for spreading contamination during decommissioning activities.

  19. Decommissioning strategy for Trawsfynydd power station

    Energy Technology Data Exchange (ETDEWEB)

    Jones, H.M.; Ellis, A.T. [Nuclear Electric plc, Barnwood (United Kingdom)

    1995-12-31

    Following the decision to close Trawsfynydd power station, Nuclear Electric adapted its generic decommissioning plans to suit the particular local circumstances. This resulted in an early reduced height safestore strategy which is described in the paper. (Author).

  20. Neutronic and Thermal-hydraulic Modelling of High Performance Light Water Reactor

    Energy Technology Data Exchange (ETDEWEB)

    Seppaelae, Malla [VTT Technical Research Centre of Finland, P.O.Box 1000, FI02044 VTT (Finland)

    2008-07-01

    High Performance Light Water Reactor (HPLWR), which is studied in EU project 'HPLWR2', uses water at supercritical pressures as coolant and moderator to achieve higher core outlet temperature and thus higher efficiency compared to present reactors. At VTT Technical Research Centre of Finland, functionality of the thermal-hydraulics in the coupled reactor dynamics code TRAB3D/ SMABRE was extended to supercritical pressures for the analyses of HPLWR. Input models for neutronics and thermal-hydraulics were made for TRAB3D/ SMABRE according to the latest HPLWR design. A preliminary analysis was performed in which the capability of SMABRE in the transition from supercritical pressures to subcritical pressures was demonstrated. Parameterized two-group cross sections for TRAB3D neutronics were received from Hungarian Academy of Sciences KFKI Atomic Energy Research Institute together with a subroutine for handling them. PSG, a new Monte Carlo transport code developed at VTT, was also used to generate two-group constants for HPLWR and comparisons were made with the KFKI cross sections and MCNP calculations. (author)

  1. Best estimate approach for the evaluation of critical heat flux phenomenon in the boiling water reactors

    Energy Technology Data Exchange (ETDEWEB)

    Kaliatka, Tadas; Kaliatka, Algirdas; Uspuras, Eudenijus; Vaisnoras, Mindaugas [Lithuanian Energy Institute, Kaunas (Lithuania); Mochizuki, Hiroyasu; Rooijen, W.F.G. van [Fukui Univ. (Japan). Research Inst. of Nuclear Engineering

    2017-05-15

    Because of the uncertainties associated with the definition of Critical Heat Flux (CHF), the best estimate approach should be used. In this paper the application of best-estimate approach for the analysis of CHF phenomenon in the boiling water reactors is presented. At first, the nodalization of RBMK-1500, BWR-5 and ABWR fuel assemblies were developed using RELAP5 code. Using developed models the CHF and Critical Heat Flux Ratio (CHFR) for different types of reactors were evaluated. The calculation results of CHF were compared with the well-known experimental data for light water reactors. The uncertainty and sensitivity analysis of ABWR 8 x 8 fuel assembly CHFR calculation result was performed using the GRS (Germany) methodology with the SUSA tool. Finally, the values of Minimum Critical Power Ratio (MCPR) were calculated for RBMK-1500, BWR-5 and ABWR fuel assemblies. The paper demonstrate how, using the results of sensitivity analysis, to receive the MCPR values, which covers all uncertainties and remains best estimated.

  2. Improving activity transport models for water-cooled nuclear power reactors

    Energy Technology Data Exchange (ETDEWEB)

    Burrill, K.A

    2001-08-01

    Eight current models for describing radioactivity transport and radiation field growth around water-cooled nuclear power reactors have been reviewed and assessed. A frequent failing of the models is the arbitrary nature of the determination of the important processes. Nearly all modelers agree that the kinetics of deposition and release of both dissolved and particulate material must be described. Plant data must be used to guide the selection and development of suitable improved models, with a minimum of empirically-based rate constraints being used. Limiting case modelling based on experimental data is suggested as a way to simplify current models and remove their subjectivity. Improved models must consider the recent change to 'coordinated water chemistry' that appears to produce normal solubility behaviour for dissolved iron throughout the fuel cycle in PWRs, but retrograde solubility remains for dissolved nickel. Profiles are suggested for dissolved iron and nickel concentrations around the heat transport system in CANDU reactors, which operate nominally at constant chemistry, i.e., pH{sub T} constant with time, and which use carbon steel isothermal piping. These diagrams are modified for a CANDU reactor with stainless steel piping, in order to show the changes expected. The significance of these profiles for transport in PWRs is discussed for further model improvement. (author)

  3. Cogeneration of Electricity and Potable Water Using The International Reactor Innovative And Secure (IRIS) Design

    Energy Technology Data Exchange (ETDEWEB)

    Ingersoll, D.T.; Binder, J.L.; Kostin, V.I.; Panov, Y.K.; Polunichev, V.; Ricotti, M.E.; Conti, D.; Alonso, G.

    2004-10-06

    The worldwide demand for potable water has been steadily growing and is projected to accelerate, driven by a continued population growth and industrialization of emerging countries. This growth is reflected in a recent market survey by the World Resources Institute, which shows a doubling in the installed capacity of seawater desalination plants every ten years. The production of desalinated water is energy intensive, requiring approximately 3-6 kWh/m3 of produced desalted water. At current U.S. water use rates, a dedicated 1000 MW power plant for every one million people would be required to meet our water needs with desalted water. Nuclear energy plants are attractive for large scale desalination application. The thermal energy produced in a nuclear plant can provide both electricity and desalted water without the production of greenhouse gases. A particularly attractive option for nuclear desalination is to couple a desalination plant with an advanced, modular, passively safe reactor design. The use of small-to-medium sized nuclear power plants allows for countries with smaller electrical grid needs and infrastructure to add new electrical and water capacity in more appropriate increments and allows countries to consider siting plants at a broader number of distributed locations. To meet these needs, a modified version of the International Reactor Innovative and Secure (IRIS) nuclear power plant design has been developed for the cogeneration of electricity and desalted water. The modular, passively safe features of IRIS make it especially well adapted for this application. Furthermore, several design features of the IRIS reactor will ensure a safe and reliable source of energy and water even for countries with limited nuclear power experience and infrastructure. The IRIS-D design utilizes low-quality steam extracted from the low-pressure turbine to boil seawater in a multi-effect distillation desalination plant. The desalination plant is based on the horizontal

  4. Transactions of the Twenty-First Water Reactor Safety Information Meeting

    Energy Technology Data Exchange (ETDEWEB)

    Monteleone, S. [comp.

    1993-10-01

    This report contains summaries of papers on reactor safety research to be presented at the 21st Water Reactor Safety Information Meeting at the Bethesda Marriott Hotel, Bethesda, Maryland, October 25--27, 1993. The summaries briefly describe the programs and results of nuclear safety research sponsored by the Office of Nuclear Regulatory Research, US NRC. Summaries of invited papers concerning nuclear safety issues from US government laboratories, the electric utilities, the Electric Power Research Institute (EPRI), the nuclear industry, and from foreign governments and industry are also included. The summaries have been compiled in one report to provide a basis for meaningful discussion and information exchange during the course of the meeting and are given in the order of their presentation in each session.

  5. Passive containment cooling system with drywell pressure regulation for boiling water reactor

    Science.gov (United States)

    Hill, Paul R.

    1994-01-01

    A boiling water reactor having a regulating valve for placing the wetwell in flow communication with an intake duct of the passive containment cooling system. This subsystem can be adjusted to maintain the drywell pressure at (or slightly below or above) wetwell pressure after the initial reactor blowdown transient is over. This addition to the PCCS design has the benefit of eliminating or minimizing steam leakage from the drywell to the wetwell in the longer-term post-LOCA time period and also minimizes the temperature difference between drywell and wetwell. This in turn reduces the rate of long-term pressure buildup of the containment, thereby extending the time to reach the design pressure limit.

  6. Integral Inherently Safe Light Water Reactor (I2S-LWR)

    Energy Technology Data Exchange (ETDEWEB)

    Petrovic, Bojan [Georgia Inst. of Technology, Atlanta, GA (United States); Memmott, Matthew [Brigham Young Univ., Provo, UT (United States); Boy, Guy [Florida Inst. of Technology, Melbourne, FL (United States); Charit, Indrajit [Univ. of Idaho, Moscow, ID (United States); Manera, Annalisa [Univ. of Michigan, Ann Arbor, MI (United States); Downar, Thomas [Univ. of Michigan, Ann Arbor, MI (United States); Lee, John [Univ. of Michigan, Ann Arbor, MI (United States); Muldrow, Lycurgus [Morehouse College, Atlanta, GA (United States); Upadhyaya, Belle [Univ. of Tennessee, Knoxville, TN (United States); Hines, Wesley [Univ. of Tennessee, Knoxville, TN (United States); Haghighat, Alierza [Virginia Polytechnic Inst. and State Univ. (Virginia Tech), Blacksburg, VA (United States)

    2017-10-02

    This final report summarizes results of the multi-year effort performed during the period 2/2013- 12/2016 under the DOE NEUP IRP Project “Integral Inherently Safe Light Water Reactors (I2S-LWR)”. The goal of the project was to develop a concept of a 1 GWe PWR with integral configuration and inherent safety features, at the same time accounting for lessons learned from the Fukushima accident, and keeping in mind the economic viability of the new concept. Essentially (see Figure 1-1) the project aimed to implement attractive safety features, typically found only in SMRs, to a larger power (1 GWe) reactor, to address the preference of some utilities in the US power market for unit power level on the order of 1 GWe.

  7. Transactions of the twenty-fifth water reactor safety information meeting

    Energy Technology Data Exchange (ETDEWEB)

    Monteleone, S. [comp.

    1997-09-01

    This report contains summaries of papers on reactor safety research to be presented at the 25th Water Reactor Safety Information Meeting at the Bethesda Marriott Hotel in Bethesda, Maryland, October 20--22, 1997. The summaries briefly describe the programs and results of nuclear safety research sponsored by the Office of Nuclear Regulatory Research, US NRC. Summaries of invited papers concerning nuclear safety issues from US government laboratories, the electric utilities, the nuclear industry, and from foreign governments and industry are also included. The summaries have been compiled in one report to provide a basis for meaningful discussion of information exchanged during the course of the meeting, and are given in order of their presentation in each session.

  8. Transactions of the twenty-second water reactor safety information meeting

    Energy Technology Data Exchange (ETDEWEB)

    None

    1994-10-01

    This report contains summaries of papers on reactor safety research to be presented at the 22nd Water Reactor Safety Information Meeting at the Bethesda Marriott Hotel, Bethesda, Maryland, October 24--26, 1994. The summaries briefly describe the programs and results of nuclear safety research sponsored by the Office of Nuclear Regulatory Research, US NRC. Summaries of invited papers concerning nuclear safety issues from US government laboratories, the electric utilities, the nuclear industry, and from foreign governments and industry are also included. The summaries have been compiled in one report to provide a basis for meaningful discussion and information exchange during the course of the meeting and are given in the order of their presentation in each session. Individual papers have been cataloged separately.

  9. General installation of pressurized water reactors; Installation generale des reacteurs a eau sous pression

    Energy Technology Data Exchange (ETDEWEB)

    Kaercher, M. [Electricite de France (EDF), 75 - Paris (France)

    2002-07-01

    This article describes the criteria considered for the installation of PWR reactors according to the most recent French standard: the N4 - 1450 MWe plant series which benefits of the experience feedback of the previous 900 and 1300 MWe series: 1 - functional organization: nuclear island, classical island; 2 - general principles of installation: safety, functional and operation requirements, grouping of equipments inside buildings, criteria of equipments separation; 3 - location of the main equipments, plot plan: specific site constraints, sitting of facilities, leveling; 4 - general installation of buildings: reactor building, fuel building, electrical and auxiliaries building, nuclear auxiliaries building, machines room, pumping station, standby generators building, water storage tank and pool building, effluents processing building; 5 - the EPR european concept: 4 sub-series concept, prevention of serious accidents, annual collective dose. (J.S.)

  10. Power level effects on thorium-based fuels in pressure-tube heavy water reactors

    Energy Technology Data Exchange (ETDEWEB)

    Bromley, B.P.; Edwards, G.W.R., E-mail: blair.bromley@cnl.ca [Canadian Nuclear Laboratories, Chalk River, Ontario (Canada); Sambavalingam, P. [Univ. of Ontario Inst. of Technology, Oshawa, Ontario (Canada)

    2016-06-15

    Lattice and core physics modeling and calculations have been performed to quantify the impact of power/flux levels on the reactivity and achievable burnup for 35-element fuel bundles made with Pu/Th or U-233/Th. The fissile content in these bundles has been adjusted to produce on the order of 20 MWd/kg burnup in homogeneous cores in a 700 MWe-class pressure-tube heavy water reactor, operating on a once-through thorium cycle. Results demonstrate that the impact of the power/flux level is modest for Pu/Th fuels but significant for U-233/Th fuels. In particular, high power/flux reduces the breeding and burnup potential of U-233/Th fuels. Thus, there may be an incentive to operate reactors with U-233/Th fuels at a lower power density or to develop alternative refueling schemes that will lower the time-average specific power, thereby increasing burnup.(author)

  11. Characteristics and economy of the European reactor of pressurized water (EPR); Caracteristicas y economia del reactor europeo de agua a presion (EPR)

    Energy Technology Data Exchange (ETDEWEB)

    Ortiz V, J.; Ramirez S, J.R.; Palacios H, J.C. [ININ, 52045 Ocoyoacac, Estado de Mexico (Mexico)]. e-mail: jov@nuclear.inin.mx

    2005-07-01

    The high current costs of the fossil fuels, have propitiated that the industries of electric power generation in the world reconsider the nuclear option as medium of generation. In Europe, the more recently contracted nuclear power plant is that of Olkiluoto-III in Finland that waits it enters in operation at the end of 2009. The reactor that will be installed in this power plant will be a prototype of pressurized water reactor of the companies AREVA and EDF. In this work they are described the reactor EPR and the major components of the nuclear power plant as well as the main characteristics of safety and the flexibility of the operation of the EPR. The supposed costs reported in different sources of information are also described and calculated with information provided by the manufacturer company. (Author)

  12. Quarterly technical progress report on water reactor safety programs sponsored by the Nuclear Regulatory Commission's Division of Reactor Safety Research, October--December 1975

    Energy Technology Data Exchange (ETDEWEB)

    1976-05-01

    Light water reactor safety activities performed during October--December 1975 are reported. The blowdown heat transfer tests series of the Semiscale Mod-1 test program was completed. In the LOFT Program, preparations were made for nonnuclear testing. The Thermal Fuels Behavior Program completed a power-cooling-mismatch test and an irradiation effects test on PWR-type fuel rods. Model development and verification efforts of the Reactor Behavior Program included developing new analysis models for the RELAP4 computer code, subroutines for the FRAP-S and FRAP-T codes, and new models for predicting reactor fuel restructuring and zircaloy cladding behavior; an analysis of post-CHF fuel behavior was made using FRAP-T.

  13. Feasibility Study of Supercritical Light Water Cooled Fast Reactors for Actinide Burning and Electric Power Production, 3rd Quarterly Report

    Energy Technology Data Exchange (ETDEWEB)

    Mac Donald, Philip Elsworth

    2002-06-01

    The use of light water at supercritical pressures as the coolant in a nuclear reactor offers the potential for considerable plant simplification and consequent capital and O&M cost reduction compared with current light water reactor (LWR) designs. Also, given the thermodynamic conditions of the coolant at the core outlet (i.e. temperature and pressure beyond the water critical point), very high thermal efficiencies of the power conversion cycle are possible (i.e. up to about 45%). Because no change of phase occurs in the core, the need for steam separators and dryers as well as for BWR-type re-circulation pumps is eliminated, which, for a given reactor power, results in a substantially shorter reactor vessel and smaller containment building than the current BWRs. Furthermore, in a direct cycle the steam generators are not needed.

  14. Application of Genetic Algorithm methodologies in fuel bundle burnup optimization of Pressurized Heavy Water Reactor

    Energy Technology Data Exchange (ETDEWEB)

    Jayalal, M.L., E-mail: jayalal@igcar.gov.in [Electronics, Instrumentation and Radiological Safety Group (EIRSG), Indira Gandhi Centre for Atomic Research (IGCAR), Kalpakkam, Tamil Nadu (India); Ramachandran, Suja [Electronics, Instrumentation and Radiological Safety Group (EIRSG), Indira Gandhi Centre for Atomic Research (IGCAR), Kalpakkam, Tamil Nadu (India); Rathakrishnan, S. [Reactor Physics Section, Madras Atomic Power Station (MAPS), Kalpakkam, Tamil Nadu (India); Satya Murty, S.A.V. [Electronics, Instrumentation and Radiological Safety Group (EIRSG), Indira Gandhi Centre for Atomic Research (IGCAR), Kalpakkam, Tamil Nadu (India); Sai Baba, M. [Resources Management Group (RMG), Indira Gandhi Centre for Atomic Research (IGCAR), Kalpakkam, Tamil Nadu (India)

    2015-01-15

    Highlights: • We study and compare Genetic Algorithms (GA) in the fuel bundle burnup optimization of an Indian Pressurized Heavy Water Reactor (PHWR) of 220 MWe. • Two Genetic Algorithm methodologies namely, Penalty Functions based GA and Multi Objective GA are considered. • For the selected problem, Multi Objective GA performs better than Penalty Functions based GA. • In the present study, Multi Objective GA outperforms Penalty Functions based GA in convergence speed and better diversity in solutions. - Abstract: The work carried out as a part of application and comparison of GA techniques in nuclear reactor environment is presented in the study. The nuclear fuel management optimization problem selected for the study aims at arriving appropriate reference discharge burnup values for the two burnup zones of 220 MWe Pressurized Heavy Water Reactor (PHWR) core. Two Genetic Algorithm methodologies namely, Penalty Functions based GA and Multi Objective GA are applied in this study. The study reveals, for the selected problem of PHWR fuel bundle burnup optimization, Multi Objective GA is more suitable than Penalty Functions based GA in the two aspects considered: by way of producing diverse feasible solutions and the convergence speed being better, i.e. it is capable of generating more number of feasible solutions, from earlier generations. It is observed that for the selected problem, the Multi Objective GA is 25.0% faster than Penalty Functions based GA with respect to CPU time, for generating 80% of the population with feasible solutions. When average computational time of fixed generations are considered, Penalty Functions based GA is 44.5% faster than Multi Objective GA. In the overall performance, the convergence speed of Multi Objective GA surpasses the computational time advantage of Penalty Functions based GA. The ability of Multi Objective GA in producing more diverse feasible solutions is a desired feature of the problem selected, that helps the

  15. Expert assessments of the cost of light water small modular reactors.

    Science.gov (United States)

    Abdulla, Ahmed; Azevedo, Inês Lima; Morgan, M Granger

    2013-06-11

    Analysts and decision makers frequently want estimates of the cost of technologies that have yet to be developed or deployed. Small modular reactors (SMRs), which could become part of a portfolio of carbon-free energy sources, are one such technology. Existing estimates of likely SMR costs rely on problematic top-down approaches or bottom-up assessments that are proprietary. When done properly, expert elicitations can complement these approaches. We developed detailed technical descriptions of two SMR designs and then conduced elicitation interviews in which we obtained probabilistic judgments from 16 experts who are involved in, or have access to, engineering-economic assessments of SMR projects. Here, we report estimates of the overnight cost and construction duration for five reactor-deployment scenarios that involve a large reactor and two light water SMRs. Consistent with the uncertainty introduced by past cost overruns and construction delays, median estimates of the cost of new large plants vary by more than a factor of 2.5. Expert judgments about likely SMR costs display an even wider range. Median estimates for a 45 megawatts-electric (MWe) SMR range from $4,000 to $16,300/kWe and from $3,200 to $7,100/kWe for a 225-MWe SMR. Sources of disagreement are highlighted, exposing the thought processes of experts involved with SMR design. There was consensus that SMRs could be built and brought online about 2 y faster than large reactors. Experts identify more affordable unit cost, factory fabrication, and shorter construction schedules as factors that may make light water SMRs economically viable.

  16. Defluoridation of water via electrically controlled anion exchange by polyaniline modified electrode reactor.

    Science.gov (United States)

    Cui, Hao; Li, Qin; Qian, Yan; Tang, Rong; An, Hao; Zhai, Jianping

    2011-11-01

    A polyaniline (PANI) modified electrode reactor was designed for fluoride removal from aqueous solutions. The innovative concept behind the reactor design is that the uptake and elute of fluoride could be well controlled by modulating the potential of the PANI film. The maximum fluoride removal capacity of PANI is more than 20 mg/g at a positive voltage based on the electrically controlled anion-exchange mechanism. The results of batch tests showed that terminal potential values had a major impact on fluoride removal by this PANI, with optimal removal occurring at 1.5 V. The fluoride removal capacity (q(e)) increased rapidly within 5 min and reached equilibrium within 10 min, which indicated a rapid removal velocity of fluoride by PANI under this condition. The applicability of defluoridation using the PANI reactor to treat fluoride-contaminated tap water was also tested through flow cell breakthrough studies. At initial fluoride concentrations of 5 mg/L and 10 mg/L, the breakthrough capacities were 20.08 mg/g and 19.24 mg/g, respectively. Moreover, during the first half of the period before the breakthrough point, the fluoride concentration of the treated solution was below the WHO's recommended levels (1.5 mg/L). The results of the five consecutive treatment-regeneration studies also showed that the PANI films could be reused. Taken together, these results implied that the electrically controlled anion exchange by the PANI-modified electrode reactor may be an effective technique for the removal of fluoride from water. Copyright © 2011 Elsevier Ltd. All rights reserved.

  17. Measurement and Analysis of Structural Integrity of Reactor Core Support Structure in Pressurized Water Reactor (PWR) Plant

    Science.gov (United States)

    Ansari, Saleem A.; Haroon, Muhammad; Rashid, Atif; Kazmi, Zafar

    2017-02-01

    Extensive calculation and measurements of flow-induced vibrations (FIV) of reactor internals were made in a PWR plant to assess the structural integrity of reactor core support structure against coolant flow. The work was done to meet the requirements of the Fukushima Response Action Plan (FRAP) for enhancement of reactor safety, and the regulatory guide RG-1.20. For the core surveillance measurements the Reactor Internals Vibration Monitoring System (IVMS) has been developed based on detailed neutron noise analysis of the flux signals from the four ex-core neutron detectors. The natural frequencies, displacement and mode shapes of the reactor core barrel (CB) motion were determined with the help of IVMS. The random pressure fluctuations in reactor coolant flow due to turbulence force have been identified as the predominant cause of beam-mode deflection of CB. The dynamic FIV calculations were also made to supplement the core surveillance measurements. The calculational package employed the computational fluid dynamics, mode shape analysis, calculation of power spectral densities of flow & pressure fields and the structural response to random flow excitation forces. The dynamic loads and stiffness of the Hold-Down Spring that keeps the core structure in position against upward coolant thrust were also determined by noise measurements. Also, the boron concentration in primary coolant at any time of the core cycle has been determined with the IVMS.

  18. Formation and deposition of platinum nanoparticles under boiling water reactor conditions

    Science.gov (United States)

    Grundler, Pascal V.; Veleva, Lyubomira; Ritter, Stefan

    2017-10-01

    Stress corrosion cracking (SCC) is a well-known degradation mechanism for components of boiling water reactors (BWRs). Therefore the mitigation of SCC is important for ensuring the integrity of the reactor system. Noble metal chemical application (NMCA) has been developed by General Electric to mitigate SCC and reduce the negative side-effects of hydrogen water chemistry used initially for SCC mitigation. NMCA is now widely applied as an online process (OLNC) during power operation. However, the understanding of the parameters that control the formation and deposition of the noble metal (Pt) particles in a BWR was still incomplete. To fill this knowledge gap, systematic studies on the formation and deposition behaviour of Pt particles in simulated and real BWR environment were performed in the framework of a research project at PSI. The present paper summarizes the most important findings. Experiments in a sophisticated high-temperature water loop revealed that the flow conditions, water chemistry, the Pt injection rate, and the pre-conditioning of the stainless steel surfaces have an impact on the Pt deposition behaviour. Slower Pt injection rates and stoichiometric excess of H2 over O2 produce smaller particles, which may increase the efficiency of the OLNC technique in mitigating SCC. Surfaces with a well-developed oxide layer retain more Pt particles. Furthermore, the pre- and post-OLNC exposure times play an important role for the Pt deposition on specimens exposed at the KKL power plant. Redistribution of Pt in the plant takes place, but most of the Pt apparently does not redeposit on the steel surfaces in the reactor system. Comparison of lab and plant results also demonstrated that plant OLNC applications can be simulated reasonably well on the lab scale.

  19. Characterization of solids in the Three Mile Island Unit 2 reactor defueling water

    Energy Technology Data Exchange (ETDEWEB)

    Campbell, D. O.

    1987-12-01

    Because of the impact of poor water clarity on defueling operations at the Three Mile Island Unit 2 Nuclear Power Station, a study was undertaken to characterize suspended particulates in the reactor defueling water. The examination included cascade filtration through Nuclepore filters of progressively smaller pore sizes, using three water samples obtained at different times and after varying degrees of clarification. The solids collected on the filters were examined with a scanning electron microscope and analyzed with energy-dispersive x-ray fluorescence. A wide variety of solids was observed, and 26 elements were detected. These included all the materials expected from the reactor system (uranium, zirconium, silver, cadmium, indium, iron, chromium, and nickel), chemicals and zeolites used to decontaminate the water (aluminum, silicon, sodium), common impurities (potassium, chlorine, sulfur, magnesium, calcium, and others), as well as some unexpected metals (molybdenum, manganese, bromine, and lead). There was also evidence for the presence of organic material. A diverse assortment of particles with widely varying surface properties was found to be present.

  20. Evaluation of an accident management strategy of emergency water injection using fire engines in a typical pressurized water reactor

    Directory of Open Access Journals (Sweden)

    Soo-Yong Park

    2015-10-01

    Full Text Available Following the Fukushima accident, a special safety inspection was conducted in Korea. The inspection results show that Korean nuclear power plants have no imminent risk for expected maximum potential earthquake or coastal flooding. However long- and short-term safety improvements do need to be implemented. One of the measures to increase the mitigation capability during a prolonged station blackout (SBO accident is installing injection flow paths to provide emergency cooling water of external sources using fire engines to the steam generators or reactor cooling systems. This paper illustrates an evaluation of the effectiveness of external cooling water injection strategies using fire trucks during a potential extended SBO accident in a 1,000 MWe pressurized water reactor. With regard to the effectiveness of external cooling water injection strategies using fire engines, the strategies are judged to be very feasible for a long-term SBO, but are not likely to be effective for a short-term SBO.

  1. Environmental Problems Associated with Decommissioning of Chernobyl Power Plant Cooling Pond

    Science.gov (United States)

    Foley, T. Q.; Oskolkov, B. Y.; Bondarkov, M. D.; Gashchak, S. P.; Maksymenko, A. M.; Maksymenko, V. M.; Martynenko, V. I.; Jannik, G. T.; Farfan, E. B.; Marra, J. C.

    2009-12-01

    Decommissioning of nuclear power plants and other nuclear fuel cycle facilities associated with residual radioactive contamination is a fairly pressing issue. Significant problems may result from decommissioning of cooling ponds. The Chernobyl Nuclear Power Plant (ChNPP) Cooling Pond is one of the largest self-contained bodies of water in the Chernobyl Region and Ukrainian Polesye with a water surface area of 22.9 km2. The major hydrological feature of the ChNPP Cooling Pond is that its water level is 6-7 m higher than the water level in the Pripyat River and water losses due to seepage and evaporation are replenished by pumping water from the Pripyat River. In 1986, the accident at the ChNPP #4 Reactor Unit significantly contaminated the ChNPP Cooling Pond. According to the 2001 data, the total radionuclide inventory in the ChNPP Cooling Pond bottom deposits was as follows: 16.28 ± 2.59 TBq for 137Cs; 2.4 ± 0.48 TBq for 90Sr, and 0.00518 ± 0.00148 TBq for 239+240Pu. Since ChNPP is being decommissioned, the ChNPP Cooling Pond of such a large size will no longer be needed and cost effective to maintain. However, shutdown of the water feed to the Pond would expose the contaminated bottom deposits and change the hydrological features of the area, destabilizing the radiological and environmental situation in the entire region in 2007 - 2008, in order to assess potential consequences of draining the ChNPP Cooling Pond, the authors conducted preliminary radio-ecological studies of its shoreline ecosystems. The radioactive contamination of the ChNPP Cooling Pond shoreline is fairly variable and ranges from 75 to 7,500 kBq/m2. Three areas with different contamination levels were selected to sample soils, vegetation, small mammals, birds, amphibians, and reptilians in order to measure their 137Cs and 90Sr content. Using the ERICA software, their dose exposures were estimated. For the 2008 conditions, the estimated dose rates were found to be as follows: amphibians - 11

  2. ROLE OF PASSIVE SAFETY FEATURES IN PREVENTION AND MITIGATION OF SEVERE PLANT CONDITIONS IN INDIAN ADVANCED HEAVY WATER REACTOR

    Directory of Open Access Journals (Sweden)

    VIKAS JAIN

    2013-10-01

    Full Text Available Pressing demands of economic competitiveness, the need for large-scale deployment, minimizing the need of human intervention, and experience from the past events and incidents at operating reactors have guided the evolution and innovations in reactor technologies. Indian innovative reactor ‘AHWR’ is a pressure-tube type natural circulation based boiling water reactor that is designed to meet such requirements, which essentially reflect the needs of next generation reactors. The reactor employs various passive features to prevent and mitigate accidental conditions, like a slightly negative void reactivity coefficient, passive poison injection to scram the reactor in event of failure of the wired shutdown systems, a large elevated pool of water as a heat sink inside the containment, passive decay heat removal based on natural circulation and passive valves, passive ECC injection, etc. It is designed to meet the fundamental safety requirements of safe shutdown, safe decay heat removal and confinement of activity with no impact in public domain, and hence, no need for emergency planning under all conceivable scenarios. This paper examines the role of the various passive safety systems in prevention and mitigation of severe plant conditions that may arise in event of multiple failures. For the purpose of demonstration of the effectiveness of its passive features, postulated scenarios on the lines of three major severe accidents in the history of nuclear power reactors are considered, namely; the Three Mile Island (TMI, Chernobyl and Fukushima accidents. Severe plant conditions along the lines of these scenarios are postulated to the extent conceivable in the reactor under consideration and analyzed using best estimate system thermal-hydraulics code RELAP5/Mod3.2. It is found that the various passive systems incorporated enable the reactor to tolerate the postulated accident conditions without causing severe plant conditions and core degradation.

  3. Numerical simulation of severe water ingress accidents in a modular high temperature gas cooled reactor

    Energy Technology Data Exchange (ETDEWEB)

    Zhang Zuoyi; Scherer, W.

    1996-01-01

    This report analyzes reverse water ingress accidents in the SIEMENS 200 MW Modular Pebble-Bed High Temperature Gas Cooled Reactor (HTR-MODULE) under the assumption of no active safety protection systems in order to find the safety margins of the current HTR-MODULE design and to realize a catastrophe-free nuclear technology. A water, steam and helium multi-phase cavity model is developed and implemented in the DSNP simulation system. The DSNP system is then used to simulate the primary and secondary circuit of a HTR-MODULE power plant. Comparisons of the model with experiments and with TINTE calculations serve as validation of the simulation. The analysis of the primary circuit tries to answer the question how fast the water enters the reactor core. It was found that the maximum H{sub 2}O concentration increase in the reactor core is smaller than 0.3 kg/(m{sup 3}s). The liquid water vaporization in the steam generator and H{sub 2}O transport from the steam generator to the reactor core reduce the ingress velocity of the H{sub 2}O into the reactor core. In order to answer the question how much water enters the primary circuit, the full cavitation of the feed water pumps is analyzed. It is found that if the secondary circuit is depressurized enough, the feed water pumps will be inherently stopped by the full cavitation. This limits the water to be pumped from the deaerator to the steam generator. A comprehensive simulation of the MODUL-HTR power plant then shows that the H{sub 2}O inventory in the primary circuit can be limited to about 3000 kg. The nuclear reactivity increase caused by the water ingress leads to a fast power excursion, which, however, is inherently counterbalanced by negative feedback effects. Concerning the integrity of the fuel elements, the safety relevant temperature limit of 1600 C was not reached in any case. (orig.) [Deutsch] Dieser Bericht analysiert schwere Wassereinbruch-Stoerfaelle im 200 MW modularen Kugelhaufen-Hochtemperaturreaktor (HTR

  4. Technology and costs for decommissioning Swedish nuclear power plants; Teknik och kostnader foer rivning av svenska kaernkraftverk

    Energy Technology Data Exchange (ETDEWEB)

    Hedin, Gunnar; Gustavsson, Boerje [Westinghouse Electric Sweden AB, Vaesteraas (Sweden); Carlsson, Jan [Swedish Nuclear Fuel and Waste Management Co., Stockholm (Sweden)

    2004-06-01

    SKB has already performed three studies on available technology and approximate costs for decommissioning Swedish NPPs (years 1986, 1994 and 2000). The present report is an update of the year 2000 report with emphasis on areas that have been studied since the publication of that report. The report also gives a review of the technologies that have been chosen for decommissioning the Swedish reactors. The cost-estimation has also been updated and indexed to the present monetary situation. Areas in need for further studies are pointed in the report.

  5. In-Vessel Melt Retention of Pressurized Water Reactors: Historical Review and Future Research Needs

    Directory of Open Access Journals (Sweden)

    Weimin Ma

    2016-03-01

    Full Text Available A historical review of in-vessel melt retention (IVR is given, which is a severe accident mitigation measure extensively applied in Generation III pressurized water reactors (PWRs. The idea of IVR actually originated from the back-fitting of the Generation II reactor Loviisa VVER-440 in order to cope with the core-melt risk. It was then employed in the new deigns such as Westinghouse AP1000, the Korean APR1400 as well as Chinese advanced PWR designs HPR1000 and CAP1400. The most influential phenomena on the IVR strategy are in-vessel core melt evolution, the heat fluxes imposed on the vessel by the molten core, and the external cooling of the reactor pressure vessel (RPV. For in-vessel melt evolution, past focus has only been placed on the melt pool convection in the lower plenum of the RPV; however, through our review and analysis, we believe that other in-vessel phenomena, including core degradation and relocation, debris formation, and coolability and melt pool formation, may all contribute to the final state of the melt pool and its thermal loads on the lower head. By looking into previous research on relevant topics, we aim to identify the missing pieces in the picture. Based on the state of the art, we conclude by proposing future research needs.

  6. Nonlinear control for core power of pressurized water nuclear reactors using constant axial offset strategy

    Directory of Open Access Journals (Sweden)

    Gholam Reza Ansarifar

    2015-12-01

    Full Text Available One of the most important operations in nuclear power plants is load following, in which an imbalance of axial power distribution induces xenon oscillations. These oscillations must be maintained within acceptable limits otherwise the nuclear power plant could become unstable. Therefore, bounded xenon oscillation is considered to be a constraint for the load following operation. In this paper, the design of a sliding mode control (SMC, which is a robust nonlinear controller, is presented. SMC is a means to control pressurized water nuclear reactor (PWR power for the load following operation problem in a way that ensures xenon oscillations are kept bounded within acceptable limits. The proposed controller uses constant axial offset (AO strategy to ensure xenon oscillations remain bounded. The constant AO is a robust state constraint for the load following problem. The reactor core is simulated based on the two-point nuclear reactor model with a three delayed neutron groups. The stability analysis is given by means of the Lyapunov approach, thus the control system is guaranteed to be stable within a large range. The employed method is easy to implement in practical applications and moreover, the SMC exhibits the desired dynamic properties during the entire output-tracking process independent of perturbations. Simulation results are presented to demonstrate the effectiveness of the proposed controller in terms of performance, robustness, and stability. Results show that the proposed controller for the load following operation is so effective that the xenon oscillations are kept bounded in the given region.

  7. Swelling in light water reactor internal components: Insights from computational modeling

    Energy Technology Data Exchange (ETDEWEB)

    Stoller, Roger E. [Oak Ridge National Lab. (ORNL), Oak Ridge, TN (United States); Barashev, Alexander V. [Oak Ridge National Lab. (ORNL), Oak Ridge, TN (United States); Univ. of Tennessee, Knoxville, TN (United States); Golubov, Stanislav I. [Oak Ridge National Lab. (ORNL), Oak Ridge, TN (United States)

    2015-08-01

    A modern cluster dynamics model has been used to investigate the materials and irradiation parameters that control microstructural evolution under the relatively low-temperature exposure conditions that are representative of the operating environment for in-core light water reactor components. The focus is on components fabricated from austenitic stainless steel. The model accounts for the synergistic interaction between radiation-produced vacancies and the helium that is produced by nuclear transmutation reactions. Cavity nucleation rates are shown to be relatively high in this temperature regime (275 to 325°C), but are sensitive to assumptions about the fine scale microstructure produced under low-temperature irradiation. The cavity nucleation rates observed run counter to the expectation that void swelling would not occur under these conditions. This expectation was based on previous research on void swelling in austenitic steels in fast reactors. This misleading impression arose primarily from an absence of relevant data. The results of the computational modeling are generally consistent with recent data obtained by examining ex-service components. However, it has been shown that the sensitivity of the model s predictions of low-temperature swelling behavior to assumptions about the