WorldWideScience

Sample records for unit replacement steam

  1. Primary separator replacement for Bruce Unit 8 steam generators

    International Nuclear Information System (INIS)

    Roy, S.B.; Mewdell, C.G.; Schneider, W.G.

    2000-01-01

    During a scheduled maintenance outage of Bruce Unit 8 in 1998, it was discovered that the majority of the original primary steam separators were damaged in two steam generators. The Bruce B steam generators are equipped with GXP type primary cyclone separators of B and W supply. There were localized perforations in the upper part of the separators and large areas of generalized wall thinning. The degradation was indicative of a flow related erosion corrosion mechanism. Although the unit- restart was justified, it was obvious that corrective actions would be necessary because of the number of separators affected and the extent of the degradation. Repair was not considered to be a practical option and it was decided to replace the separators, as required, in Unit 8 steam generators during an advanced scheduled outage. GXP separators were selected for replacement to minimize the impact on steam generator operating characteristics and analysis. The material of construction was upgraded from the original carbon steel to stainless steel to maximize the assurance of full life. The replacement of the separators was a first of a kind operation not only for Ontario Power Generation and B and W but also for all CANDU plants. The paper describes the degradations observed and the assessments, the operating experience, manufacture and installation of the replacement separators. During routine inspection in 1998, many of the primary steam separators in two of steam generators at Bruce Nuclear Division B Unit 8 were observed to have through wall perforations. This paper describes assessment of this condition. It also discusses the manufacture and testing of replacement primary steam separators and the development and execution of the replacement separator installation program. (author)

  2. Steam generator replacement in Bruce A Unit 1 and Unit 2

    International Nuclear Information System (INIS)

    Hart, R.S.

    2006-01-01

    The Bruce A Generating Station consists of four 900 MW class CANDU units. The reactor and Primary Heat Transport System for each Unit are housed within a reinforced concrete reactor vault. A large duct running below the reactor vaults accommodates the shared fuel handling system, and connects the four reactor vaults to the vacuum building. The reactor vaults, fuelling system duct and the vacuum building constitute the station vacuum containment system. Bruce A Unit 2 was shut down in 1995 and Bruce A Units 1, 3 and 4 were shutdown in 1997. Bruce A Units 3 and 4 were returned to service in late 2003 and are currently operating. Units 1 and 2 remain out of service. Bruce Power is currently undertaking a major rehabilitation of Bruce A Unit 1 and Units 2 that will extend the in-service life of these units by at least 25 years. Replacement of the Steam Generators (eight in each unit) is required; this work was awarded to SNC-Lavalin Nuclear (SLN). The existing steam drums (which house the steam separation and drying equipment) will be retained. Unit 2 is scheduled to be synchronized with the grid in 2009, followed by Unit 1 in 2009. Each Bruce A unit has two steam generating assemblies, one located above and to each end of the reactor. Each steam generating assembly consists of a horizontal cylindrical steam drum and four vertical Steam Generators. The vertical Steam Generators connect to individual nozzles that are located on the underside of the Steam Drum (SD). The steam drums are located in concrete shielding structures (steam drum enclosures). The lower sections of the Steam Generators penetrate the top of the reactor vaults: the containment pressure boundary is established by bellows assemblies that connect between the reactor vault roof slab and the Steam Generators. Each Steam Generators is supported from the bottom by a trapeze that is suspended from the reactor vault top structure. The Steam Generator Replacement (SGR) methodology developed by SLN for Unit 1

  3. Steam generator replacement in Bruce A Unit 1 and Unit 2

    International Nuclear Information System (INIS)

    Hart, R.S.

    2007-01-01

    The Bruce A Generating Station consists of four 900 MW class CANDU units. The reactor and Primary Heat Transport System for each Unit are housed within a reinforced concrete reactor vault. A large duct running below the reactor vaults accommodates the shared fuel handling system, and connects the four reactor vaults to the vacuum building. The reactor vaults, fuelling system duct and the vacuum building constitute the station vacuum containment system. Bruce A Unit 2 was shut down in 1995 and Bruce A Units 1, 3 and 4 were shutdown in 1997. Bruce A Units 3 and 4 were returned to service in late 2003 and are currently operating. Units 1 and 2 remain out of service. Bruce Power is currently undertaking a major rehabilitation of Bruce A Unit 1 and Unit 2 that will extend the in-service tile of these units by at least 25 years. Replacement of the Steam Generators (eight in each unit) is required; this work was awarded to SNC-Lavalin Nuclear (SLN). The existing steam drums (which house the steam separation and drying equipment) will be retained. Unit 2 is scheduled to be synchronized with the grid in 2009, followed by Unit 1 in 2009. Each Bruce A unit has two steam generating assemblies, one located above and to each end of the reactor. Each steam generating assembly consists of a horizontal cylindrical steam drum and four vertical Steam Generators. The vertical Steam Generators connect to individual nozzles that are located on the underside of the Steam Drum (SD). The steam drums are located in concrete shielding structures (steam drum enclosures). The lower sections of the Steam Generators penetrate the top of the reactor vaults: the containment pressure boundary is established by bellows assemblies that connect between the reactor vault roof slab and the Steam Generators. Each Steam Generators is supported from he bottom by a trapeze that is suspended from the reactor vault top structure. The Steam Generator Replacement (SGR) methodology developed by SLN for Unit 1

  4. Acceptance test for 900 MWe PWR unit replacement steam generators

    International Nuclear Information System (INIS)

    Gourguechon, B.

    1993-01-01

    During the first half of 1994, the Gravelines 1 steam generators will be replaced (SG replacement procedure). The new SG's differ from the former components notably by the alloy used for the tube bundle, in this case, the high chromium content Inconel 690. So, from this standpoint, they are to be considered as PWR 900 replacement SG first models and their thermal efficiency has consequently to be assessed. This will provide an opportunity of ensuring that the performance of the components delivered is in compliance with requirements and of making the necessary provisions if significant deviations are observed. The EFMT branch, which has been in charge of the instrumentation and acceptance of the different SG first models since the first PWR plants were commissioned, will be responsible for the acceptance tests and the ultimate validation of a performance assessment procedure applicable to the future replacement steam generators. The methods and tests proposed for SG expert appraisal are based on consideration of the importance of primary measurement quality for satisfactory SG assessment and of the new test facilities with which the 900 and 1 300 PWR plants are gradually being equipped. These facilities provide an on-site computer environment for tests compatible with the tools (PATTERN, etc.) used at EFMT and in other departments. This test is the first of this kind performed by EFMT and the test facility of a nuclear power plant. (author). 6 figs

  5. North Anna Power Station - Unit 1: Overview of steam generator replacement project activities

    International Nuclear Information System (INIS)

    Gettler, M.W.; Bayer, R.K.; Lippard, D.W.

    1993-01-01

    The original steam generators at Virginia Electric and Power Company's (Virginia Power) North Anna Power Station (NAPS) Unit 1 have experienced corrosion-related degradation that require periodic inspection and plugging of steam generator tubes to ensure their continued safe and reliable operation. Despite improvements in secondary water chemistry, continued tube degradation in the steam generators necessitated the removal from service of approximately 20.3 percent of the tubes by plugging, (18.6, 17.3, and 25.1 for steam generators A, B, and C, respectively). Additionally, the unit power was limited to 95 % during, its last cycle of operation. Projections of industry and Virginia Power experience indicated the possibility of mid-cycle inspections and reductions in unit power. Therefore, economic considerations led to the decision to repair the steam generators (i.e., replace the steam generator lower assemblies). Three new Model 51F Steam Generator lower assembly units were ordered from Westinghouse. Virginia Power contracted Bechtel Power Corporation to provide the engineering and construction support to repair the Unit 1 steam generators. On January 4, 1993, after an extended coastdown period, North Anna Unit 1 was brought off-line and the 110 day (breaker-to-breaker) Steam Generator Replacement Project (SGRP) outage began. As of this paper, the outage is still in progress

  6. Replacement of steam generators at arkansas nuclear one, unit-2 (ano-2)

    International Nuclear Information System (INIS)

    Wilson, R.M.; Buford, A.

    2001-01-01

    The Arkansas Nuclear One, Unit-2 steam generators, originally supplied by Combustion Engineering, began commercial operation in 1980 producing a gross electrical output of 958 MW. After several years of successful operation, the owner decided that the tube degradation rates of the original steam generators were too high for the plant to meet the performance requirements for the full 40-year license period. The contract to supply replacement steam generators (RSGs) was awarded to Westinghouse Electric Company in 1996. Installation of these RSGs took place in the last months of 2000. This paper compares the design features of the original and re-placement steam generators with emphasis on design and reliability enhancements achieved. (author)

  7. Use of mock-up training to reduce personnel exposure at the North Anna Unit 1 Steam Generator Replacement Project

    Energy Technology Data Exchange (ETDEWEB)

    Henry, H.G. [Virginia Power, Mineral, VA (United States); Reilly, B.P. [Bechtel Power Corp., Gaithersburg, MD (United States)

    1995-03-01

    The North Anna Power Station is located on the southern shore of Lake Anna in Louisa County, approximately forty miles northwest of Richmond, Virginia. The two 910 Mw nuclear units located on this site are owned by Virginia Electric and Power Company (Virginia Power) and Old Dominion Electric Cooperative and operated by Virginia Power. Fuel was loaded into Unit 1 in December 1977, and it began commercial operation in June 1978. Fuel was loaded into Unit 2 in April 1980 and began commercial operation in December 1980. Each nuclear unit includes a three-coolant-loop pressurized light water reactor nuclear steam supply system that was furnished by Westinghouse Electric Corporation. Included within each system were three Westinghouse Model 51 steam generators with alloy 600, mill-annealed tubing material. Over the years of operation of Unit 1, various corrosion-related phenomena had occurred that affected the steam generators tubing and degraded their ability to fulfill their heat transfer function. Advanced inspection and repair techniques helped extend the useful life of the steam generators, but projections based on the results of the inspections indicated that the existing steam generators tubing and degraded their ability to fullfill their heat transfer function. Advanced inspection and repair techniques helped extend the useful life of the steam generators, but projections based on the results of the inspections indicated that the existing steam generators would not last their design life and must be repaired. To this end Virginia Power determined that a steam generator replacement (SGR) program was necessary to remove the old steam generator tube bundles and lower shell sections, including the channel heads (collectively called the lower assemblies), and replace them with new lower assemblies incorporating design features that will prevent the degradation problems that the old steam generators had experienced.

  8. Restart Testing Program for piping following steam generator replacement at North Anna Unit 1

    International Nuclear Information System (INIS)

    Bain, R.A.; Bayer, R.K.

    1993-01-01

    In order to provide assurance that the effects of performing steam generator replacement (SGR) at North Anna unit 1 had no adverse impact on plant piping systems, a cold functional verification restart testing program was developed. This restart testing program was implemented in lieu of a hot functional testing program normally used during the initial startup of a nuclear plant. A review of North Anna plant-specific and generic U.S. Nuclear Regulatory Commission requirements for restart testing was performed to ensure that no mandatory hot functional testing was required. This was determined to be the case, and the development of a cold functional test program was initiated. The cold functional test had inherent advantages as compared to the hot functional testing, while still providing assurance of piping system adequacy. The advantages of the cold verification program included reducing risk to personnel from hot piping, increasing the accuracy of measurements with the improvement in work conditions, eliminating engineering activities during the heatup process, and being able to record measurements as construction work was completed allowing for rework or repair of components if required. To ensure the effectiveness of the cold verification program, a project procedure was generated to identify the personnel, equipment, and measurement requirements. An engineering calculation was issued to document the scope of the restart test program, and an additional calculation was developed to provide acceptance criteria for the critical commodity measurements

  9. International examples of steam generator replacement

    International Nuclear Information System (INIS)

    Wiechmann, K.

    1993-01-01

    Since 1979-1980 a total of twelve nuclear power plants world-wide have had their steam generators replaced. The replacement of the Combustion steam generators in the Millstone-2 plant in the United States was completed very recently. Steam generator replacement activities are going on at present in four plants. In North Anna, the steam generators have been under replacement since January 1990. In Japan, preparations have been started for Genkai-1. Since January 1992, the two projects in Beznau-1, Switzerland, and Doel-3, Belgium, have bee planned and executed in parallel. Why steam generator replacement? There are a number of defect mechanisms which give rise to the need for early steam generator replacement. One of the main reasons is the use of Inconel-600 as material for the heating tubes. Steam generator heating tubes made of Inconel-600 have been known to exhibit their first defects due to stress corrosion cracking after less than one year of operation. (orig.) [de

  10. Steam generator replacement at Surry Power Station

    International Nuclear Information System (INIS)

    McKay, H.S.

    1982-01-01

    The purposes of the steam generator repair program at Surry Power Station were to repair the tube degradation caused by corrosion-related phenomena and to restore the integrity of the steam generators to a level equivalent to new equipment. The repair program consisted of (1) replacing the existing lower-shell assemblies with new ones and (2) adding new moisture separation equipment to the upper-shell assemblies. These tasks required that several pieces of reactor coolant piping, feedwater piping, main steam piping, and the steam generator be cut and refurbished for reinstallation after the new lower shell was in place. The safety implications and other potential effects of the repair program both during the repair work and after the unit was returned to power were part of the design basis of the repair program. The repair program has been completed on Unit 2 without any adverse effects on the health and safety of the general public or to the personnel engaged in the repair work. Before the Unit 1 repair program began, a review of work procedures and field changes for the Unit 2 repair was conducted. Several major changes were made to avoid recurrence of problems and to streamline procedures. Steam generator replacements was completed on June 1, 1981, and the unit is presently in the startup phase of the outrage

  11. Steam-generator replacement sets new marks

    International Nuclear Information System (INIS)

    Beck, R.L.

    1995-01-01

    This article describes how, in one of the most successful steam-generator replacement experiences at PWRs worldwide, the V C Summer retrofit exceeded plant goals for critical-path duration, radiation, exposure, and radwaste generation. Intensive planning and teamwork, combined with the firm support of station management and the use of mockups to prepare the work crews for activity in a radiological environment, were key factors in the record performance achieved by South Carolina Electric and Gas Co (SCE and G) in replacing three steam generators at V C Summer nuclear station. The 97-day, two-hour breaker-to-breaker replacement outage -- including an eight-day delay for repair of leak in a small-bore seal-injection line of a reactor coolant pump (unrelated to the replacement activities) -- surpassed the project goal by over one day. Moreover, the outage was only 13 hours shy of the world record held by Virginia Power Co's North Anna Unit 1

  12. Surry Power Station secondary water chemistry improvement since steam generator replacement and the unit two feedwater pipe rupture

    International Nuclear Information System (INIS)

    Swindell, E.T.

    1988-01-01

    Surry Power Station has two Westinghouse-designed three-loop PWRs of 811 MWe design rating. The start of commercial operation was in July, 1972 in No.1 plant, and May, 1973 in No.2 plant. Both plants began the operation using controlled phosphate chemistry for the steam generators. In 1975, both plants were converted to all volatile treatment on the secondary side due to the tube wall thinning corrosion in the steam generators, which was associated with the phosphate sludge that was building up on the tube sheets and created acidic condition. Thereafter, condenser and air leakage and steam generator denting occurred, and after the operation of 8 years 2 month of No.1 plant and 5 years 9 months of No.2 plant, the steam generators were replaced. A major plant improvement program was designed and implemented from 1979 to 1980. The improvement in new steam generators, the modification for preventing corrosion, the addition of a steam generator blowdown recovery system, the reconstruction of condensers, the installation of full flow, deep bed condensate polishers, the addition of Dionex 8,000 on-line ion chromatograph, a long term maintenance agreement with Westinghouse and so on are reported. (Kako, I.)

  13. Technical development and its application on steam generator replacement

    International Nuclear Information System (INIS)

    Morita, Sadahiko; Hanzawa, Katsumi; Sato, Hajime; Kannoto, Yasuo.

    1995-01-01

    Twenty-two PWR nuclear power plants are now under commercial operation in Japan. Eight of these plants are scheduled to have their steam generators replaced by up-graded units as a social responsibility for improved reliability, economy and easier maintenance. To carry out steam generator replacement, main coolant pipe cutting and restoration techniques, remote controlled welding machines and other remote controlled equipment, templating techniques with which the new steam generator primary nozzles will fit the existing primary pipes correctly were developed. An adequate training program was carried out to establish these techniques and they were then applied in replacement work on site. The steam generators of the three plants were replaced completely in 1994. These newly developed techniques are to be applied in upcoming plants and replaced plants will be much reliable. (author)

  14. Steam generator replacement at Kansai Electric Power Co., Inc

    International Nuclear Information System (INIS)

    Kimura, S.; Dodo, Takashi; Negishi, Kazuo

    1995-01-01

    Eleven nuclear units are in operation at the Kansai Electric Power Co., Inc.. In seven of them, Mihama-1·2·3, Takahama-1·2, and Ohi-1·2, comparatively long duration for tube inspection and repair have been required during late annual outages. KEPCO decided to replace all steam generators in these 7 units with the latest model which was improved upon the past degradation experiences, as a result of comprehensive considerations including public confidence in nuclear power generation, maintenability, and economic efficiency. This report presents the design improvements in new steam generators, replacement techniques, and so on. (author)

  15. New steam generators slated for nuclear units

    International Nuclear Information System (INIS)

    Anon.

    1992-01-01

    This article is a brief discussion of Duke Power's plans to replace steam generators at its McGuire and Catawba nuclear units. A letter of intent to purchase (from Babcock and Wilcox) the 12 Westinghouse steam generators has been signed, but no constructor has been selected at this time. This action is brought about by the failures of more than 3000 tubes in these units

  16. Three Steam Generator Replacement Projects in 1995

    International Nuclear Information System (INIS)

    Holz, R.; Clavier, G.

    1996-01-01

    Since the companies Siemens AG and Framatome S. A. joined their experience and efforts in the field of steam generator replacements and formed a consortium in 1991, the following projects were performed in 1995: Ringhals 3, Tihange 3 and Asco 1. Further projects will follow in 1996, i. e., Doel 4 and Asco 2. Currently, this European consortium is bidding for the contract to replace the steam generators at the Krsko NPP and hopes to be awarded in 1996. An overview of the way the Consortium Siemens and Framatome approaches SG replacement projects is given based on the projects performed in 1995. Various aspects of project planning, management, licensing, personnel qualification and techniques used on site will be discussed. (author)

  17. Defining line replaceable units

    NARCIS (Netherlands)

    Parada Puig, J. E.; Basten, R. J I

    2015-01-01

    Defective capital assets may be quickly restored to their operational condition by replacing the item that has failed. The item that is replaced is called the Line Replaceable Unit (LRU), and the so-called LRU definition problem is the problem of deciding on which item to replace upon each type of

  18. Structural considerations in steam generator replacement

    International Nuclear Information System (INIS)

    Bertheau, S.R.; Gazda, P.A.

    1991-01-01

    Corrosion of the tubes and tube-support structures inside pressurized water reactor (PWR) steam generators has led many utilities to consider a replacement of the generators. Such a project is a major undertaking for a utility and must be well planned to ensure an efficient and cost-effective effort. This paper discusses various structural aspects of replacement options, such as total or partial generator replacement, along with their associated pipe cuts; major structural aspects associated with removal paths through the equipment hatch or through an opening in the containment wall, along with the related removal processes; onsite movement and storage of the generators; and the advantages and disadvantages of the removal alternatives. This paper addresses the major structural considerations associated with a steam generator replacement project. Other important considerations (e.g., licensing, radiological concerns, electrical requirements, facilities for management and onsite administrative activities, storage and fabrication activities, and offsite transportation) are not discussed in this paper, but should be carefully considered when undertaking a replacement project

  19. Steam generator replacement from ALARA aspects

    International Nuclear Information System (INIS)

    Terry, I.; Breznik, B.

    2003-01-01

    This paper is going to consider radiological related parameters important for steam generator replacement (SGR) implementation. These parameters are identified as ALARA related parameters, owner-contractor relationship, planning, health physics with logistic services, and time required for the replacement. ALARA related parameters such as source or initial dose rate and plant system configuration define the initial conditions for the planning. There is room to optimise work planning. managerial procedures and also the staff during the implementation phase. The overview of these general considerations is based on the following background: using internationally available data and the experience of one of the vendors, i.e. Siemens-Framatome, and management experience of SG replacement which took place at Krsko NPP in the spring of 2000. Generally plant decisions on maintenance or repair procedures under radiation conditions take into account ALARA considerations. But in the main it is difficult to adjudge the results of an ALARA study, usually in the form of a collective dose estimate, because a comparison standard is missing. That is, very often the planned work is of a one-off nature so comparisons are not possible or the scopes are not the same. In such a case the collective doses for other types of work are looked at and a qualitative evaluation is made. In the case of steam generator replacement this is not the case. Over years of steam generator replacements world-wide a standard has been developed gradually. The first part of the following displays an overview of SGR and sets the Krsko SGR in perspective by applying dose analysis. The second part concentrates on the Krsko SGR itself and its ALARA aspects. (authors)

  20. Steam generator replacement at Doel 3 NPP (Belgium)

    International Nuclear Information System (INIS)

    Danhier, B.

    1993-01-01

    The reasons are presented that led to the conclusion that the most cost-effective strategy for the Doel 3 unit was the immediate replacement of the SG. Discussed are the advantages and drawbacks of the replacement techniques, the so-called 2, 3 and 4 cuts methods. The advantages are emphasized of intensive use of computer aided engineering in this kind of backfitting. The methodology applied to combine a power uprating of 10% over the nominal power with the steam generator replacement is presented. (author) 1 fig

  1. Steam generator replacement project in 2000

    International Nuclear Information System (INIS)

    Cerjak, J.; Holz, R.; Haus, J.; Gloaguen, C.

    1999-01-01

    NE Krsko has awarded the contract for the Steam Generator Replacement Project, which is one of the modernization projects in Krsko, to the Consortium of Siemens / Framatome in February 1998. This paper deals with the various aspects of the project: scope planning, engineering, preparation of modification packages for licensing, management, major techniques used, etc., showing also the status of the activities for the project which are scheduled to be performed in April through June 2000. The project is being performed on a turnkey basis, that means the Consortium is performing all engineering, preparation of the modification packages and site activities; NE Krsko is dealing with the licensing of the project.(author)

  2. Turbine steam path replacement at the Grafenrheinfeld Nuclear Power Station

    International Nuclear Information System (INIS)

    Weschenfelder, K.D.; Oeynhausen, H.; Bergmann, D.; Hosbein, P.; Termuehlen, H.

    1994-01-01

    In the last few years, replacement of old vintage steam turbine flow path components has been well established as a valid approach to improve thermal performance of aged turbines. In nuclear power plants, performance improvement is generally achieved only by design improvements since performance deterioration of old units is minor or nonexistent. With fossil units operating over decades loss in performance is an additional factor which can be taken into account. Such loss of performance can be caused by deposits, solid particle erosion, loss of shaft and inter-stage seal strips, etc. Improvement of performance is typically guaranteed as output increases for operation at full load. This value can be evaluated as a direct gain in unit capacity without fuel or steam supply increase. Since fuel intake does not change, the relative improvement of the net plant heat rate or efficiency is equal to the relative increase in output. The heat rate improvement is achieved not only at full load but for the entire load range. Such heat rate improvement not only moves a plant up on the load dispatch list increasing its capacity factor, but also extensive fuel savings can pay off for the investment cost of new steam path components. Another important factor is that quite often older turbine designs show a deterioration of their reliability and need costly repairs. With new flow path components an aged steam turbine starts a new useful life

  3. Optimization of costs for the DOEL 3 steam generator replacement

    International Nuclear Information System (INIS)

    Leblois, C.

    1994-01-01

    Several aspects of steam generator replacement economics are discussed on the basis of the recent replacement carried out in the Doel 3 unit. The choice between repair of replacement policies, as well as the selection of the intervention date were based on a comparison of costs in which various possible scenarios were examined. The contractual approach for the different works to be performed was also an important point, as well as the project organization in which CAD played an important role. This organization allowed to optimize the outage duration and to realize numerous interventions in the reactor building in parallel with the replacement itself. A last aspect of the optimization of costs is the possibility to uprate the plant power. In the case of Doel 3, the plant restarted with a nominal power increased by 10%, of which 5,7% were possible by the increase of the SG heat transfer area. (Author) 6 refs

  4. Steam generator replacement at Bruce A: approach, results, and lessons learned

    International Nuclear Information System (INIS)

    Tomkiewicz, W.; Savage, B.; Smith, J.

    2008-01-01

    Steam Generator Replacement is now complete in Bruce A Units 1 and 2. In each reactor, eight steam generators were replaced; these were the first CANDU steam generator replacements performed anywhere in the world. The plans for replacement were developed in 2004 and 2005, and were summarized in an earlier paper for the CNS Conference held in November, 2006. The present paper briefly summarizes the methodologies and special processes used such as metrology, cutting and welding and heavy lifting. The paper provides an update since the earlier report and focuses on the project achievements to date, such as: - A combination of engineered methodology, laser metrology and precise remote machining led to accurate first time fit-ups of each new replacement steam generator and steam drums - Lessons learned in the first unit led to schedule improvements in the second unit - Dose received was lowest recorded for any steam generator replacement project. The experience gained and lessons learned from Units 1 and 2 will be valuable in planning and executing future replacement steam generator projects. A video was presented

  5. Acceptance test for 900 MWe PWR unit replacement steam generators; Essai de reception des generateurs de vapeur de remplacement des tranches REP 900

    Energy Technology Data Exchange (ETDEWEB)

    Gourguechon, B.

    1993-12-31

    During the first half of 1994, the Gravelines 1 steam generators will be replaced (SG replacement procedure). The new SG`s differ from the former components notably by the alloy used for the tube bundle, in this case, the high chromium content Inconel 690. So, from this standpoint, they are to be considered as PWR 900 replacement SG first models and their thermal efficiency has consequently to be assessed. This will provide an opportunity of ensuring that the performance of the components delivered is in compliance with requirements and of making the necessary provisions if significant deviations are observed. The EFMT branch, which has been in charge of the instrumentation and acceptance of the different SG first models since the first PWR plants were commissioned, will be responsible for the acceptance tests and the ultimate validation of a performance assessment procedure applicable to the future replacement steam generators. The methods and tests proposed for SG expert appraisal are based on consideration of the importance of primary measurement quality for satisfactory SG assessment and of the new test facilities with which the 900 and 1 300 PWR plants are gradually being equipped. These facilities provide an on-site computer environment for tests compatible with the tools (PATTERN, etc.) used at EFMT and in other departments. This test is the first of this kind performed by EFMT and the test facility of a nuclear power plant. (author). 6 figs.

  6. Life extension and replacement management for RAPS type steam generators

    International Nuclear Information System (INIS)

    Arya, R.C.; Rastogi, A.K.

    1996-01-01

    The steam generating equipment in first four units of Indian PHWRs Rajasthan Atomic Power Station (RAPS) 1-2 and Madras Atomic Power Station (MAPS) 1-2 are hairpin type and comprise of eight boiler assemblies. Each assembly consists of identical, single pass, inverted and vertical hairpin heat exchangers (10 for RAPS and 11 for MAPS) containing 195 monel-400 U tubes of 12.7 mm dia x 1.242 mm thick. The hot heavy water flows through these tubes and imparts heat to feed, light demineralized water entering the shell at the bottom of preheat leg. The heat is generated on the outer surface of the tubes. Details of studies carried out for life extension and replacement management for RAPS type steam generators are given. 1 fig., 5 tabs

  7. Steam generator replacement: a story of continuous improvement

    International Nuclear Information System (INIS)

    Sills, M.S.; Wilkerson, R.

    2009-01-01

    This paper provides a review of the history of steam generator replacement in the US focusing on the last five years. From the early replacements in the 1980s, there have been major technology improvements resulting in dramatically shorter outages and reduced radiological exposure for workers. Even though the changes for the last five years have been less dramatic, the improvement trend continues. No two steam generator replacement (SGR) projects are the same and there are some major differences including; the access path for the components to containment (is a construction opening in containment required), type of containment, number of steam generators, one piece or two piece replacement, plant type (Westinghouse, CE or B and W) and plant layout. These differences along with other variables such as delays due to plant operations and other activities not related to the steam generator replacement make analysis of performance data difficult. However, trends in outage performance and owner expectations can be identified. How far this trend will go is also discussed. Along with the trend of improved performance, there is also a significant variation in performance. Some of the contributors to this variation are identified. This paper addresses what is required for a successful outage, meeting the increasing expectations and setting new records. The authors will discuss various factors that contribute to the success of a steam generator replacement. These factors include technical issues and, equally important, organizational interface and the role the customer plays. Recommendations are provided for planning a successful steam generator replacement outage. (author)

  8. A Geothermal Energy Supported Gas-steam Cogeneration Unit as a Possible Replacement for the Old Part of a Municipal CHP Plant (TEKO

    Directory of Open Access Journals (Sweden)

    L. Böszörményi

    2001-01-01

    Full Text Available The need for more intensive utilization of local renewable energy sources is indisputable. Under the current economic circumstances their competitiveness in comparison with fossil fuels is rather low, if we do not take into account environmental considerations. Integrating geothermal sources into combined heat and power production in a municipal CHP plant would be an excellent solution to this problem. This concept could lead to an innovative type of power plant - a gas-steam cycle based, geothermal energy supported cogeneration unit.

  9. Steam generator replacement at the Obrigheim nuclear power station

    International Nuclear Information System (INIS)

    Pickel, E.; Schenk, H.; Huemmler, A.

    1984-01-01

    The Obrigheim Nuclear Power Station (KWO) is equipped with a dual-loop pressurized water reactor of 345 MW electric power; it was built by Siemens in the period 1965 to 1968. By the end of 1983, KWO had produced some 35 billion kWh in 109,000 hours of operation. Repeated leaks in the heater tubes of the two steam generators had occurred since 1971. Both steam generators were replaced in the course of the 1983 annual revision. Kraftwerk Union AG (KWU) was commissioned to plant and carry out the replacement work. Despite the leakages the steam generators had been run safely and reliably over a period of 14 years until their replacement. Replacing the steam generators was completed within twelve weeks. In addition to the KWO staff and the supervising crew of KWU, some 400 external fitters were employed on the job at peak work-load periods. For the revision of the whole plant, work on the emergency systems and replacement of the steam generators a maximum number of approx. 900 external fitters were employed in the plant in addition to some 250 members of the plant crew. The exposure dose of the personnel sustained in the course of the steam generator replacement was 690 man-rem, which was clearly below previous estimates. (orig.) [de

  10. LMFBR steam generators in the United Kingdom

    International Nuclear Information System (INIS)

    Anderson, R.; Hayden, O.

    2002-01-01

    Experience has been gained in the UK on the operation of LMFBR Steam Generator Units (SGU) over a period of 20 years from the Dounreay Fast Reactor (DFR) and the Prototype Fast Reactor (PFR). The DFR steam generator featured a double barrier and therefore did not represent a commercial design. PFR, however, faced the challenge of a single wall design and it is experience from this which is most valuable. The PFR reactor went critical in March 1974 and the plant operating history since then has been dominated by experience with leaks in the tube to tube plate welds of the high performance U-tubes SGU's. Operation at high power using the full complement of three secondary sodium circuits was delayed until July 1976 by the occurrence of leaks in the tube to tube plate welds of the superheater and reheater units which are fabricated in stainless steel. Repairs were carried out to the two superheaters and they were returned to service. The reheater tube bundle was removed from circuit after sodium was found to have entered the steam side. When the sodium had been removed and inspection carried out it was decided not to recover the unit. Since 1976 the remaining five stainless steel units have operated satisfactorily. This year a replacement reheater unit has been installed. This is of a new design in 9-Cr-Mo ferritic steel using a sleeve through which the steam tube passes to eliminate the tube to tube plate weld. Despite a few early leaks in evaporator tube to tube plate welds up to 1979, these failures did not initially present a major problem. However, in 1980 the rate of evaporator weld failures increased and despite the successful application of a shot peening process to eliminate stress corrosion failures from the water side of the weld, failures traced to the sodium side continued. A sleeving process was developed for application to complete evaporator units on a production basis with the objective of bypassing the welds at each end of the 500 tubes. The decision

  11. Optimization of steam generator replacement with virtual reality modeling

    International Nuclear Information System (INIS)

    Kim, Jeong H.; Suh, Kune Y.

    2008-01-01

    Nuclear power plants (NPPs) have to be carefully examined and maintained up to the point of replacing major components during the overhaul period for continued operation. Most understandably the cost of maintenance and upgrading will tend to increase with the NPP power. There is thus an escalating need for developing an optimized process management method to reduce the cost involved. Albeit the steam generators (SGs) may not directly affect the expected lifespan of NPP, thousands of tubes with diameter on the order of 3 cm in the SG operating at 320degC and 16 MPa may well tend to be called Achilles' heel of the pressurized water reactors (PWRs). For instance, the SGs of Kori Nuclear Unit 1 (KNU 1) were replaced in October 1998 after 20 years of service on account of aging and potential threat to operational safety. In the same year the SG tubes of Ulchin Nuclear Units 1 and 2 were ruptured to result in leakage of the primary coolant to the secondary side. As a result their SGs are planned to be replaced in a few years. There is, however, a limit to improving the replacement process by trial and error in practice on account of the size of NPP with the ensuing complexity in process management. This paper proposes an optimization method for the SG replacement process based on the KNU 1 experience in 1998. The whole process was simulated accounting for interactions of each part in virtual reality utilizing the computer aided design solution CATIA, and the digital process management solution DELMIA. (author)

  12. Replacement of steam generators at Dampierre 1 France

    International Nuclear Information System (INIS)

    Bacot, J.; Chorain, M.; Collot, Y.; Dorimini, G.

    1991-01-01

    1990 was the year of the first steam generator replacement operation on EdF's facilities. The site chosen was Dampierre 1 (900 MW PWR unit with 3 primary coolant loops). The project was a thorough success characterized by: (1) A work schedule which was entirely met and even improved on: 70 work days from the end of fuel unloading authorizing start of work in the reactor building up to the end of refitting in readiness for the primary circuit hydraulic tests, i.e. a gain of one week compared with the forecast work schedule, (2) A final dosimetry less than 230 man-rem for a target of 450 man-rem, (3) Safety: no serious accidents during the 300,000 hours worked. It also provided practical proof of French industry's capacity to undertake an SGR operation. (author)

  13. Radiological protection for the ANGRA 1 steam generator replacement outage

    International Nuclear Information System (INIS)

    Oliveira, Magno Jose de; Amaral, Marcos Antonio do; Minelli, Edson; Ferreira, William Alves

    2009-01-01

    The Angra 1 Nuclear Power Plant (NPP) is a Westinghouse two-loop plant with net output before its 1P16 Outage of 632 MWe, with the Old Steam Generators (OSG) type model D3, which were replaced by two new Steam Generators with feed water-ring system. Localized in Angra dos Reis, Rio de Janeiro - Brazil, Angra 1 started in commercial operation in 1985 and, from the beginning problems related to corrosion have appeared in the Inconel 600 alloy of the tubes. The corrosion problems indicated the necessity for a strong control of the tubes thicknesses and, after a time, the ELETRONUCLEAR decided to replace the OSG. In 2009, ELETRONUCLEAR initiated in January 24, the actions for the Steam Generators Replacement - SGR. During the SGR process, several controls were applied in field, which made possible to have no radiological accidents, no dose limits exceeded, and permitted to achieve a very good result in terms of Collective Dose. This paper describes the radiological controls applied for the Angra 1 Steam Generator Replacement Outage, the radiological protection team sizing and distribution and the obtained results. (author)

  14. A drier unit for steam separators

    International Nuclear Information System (INIS)

    Peyrelongue, J.-P.

    1973-01-01

    Description is given of a drier unit adapted to equip a water separator mounted in a unit for treating a wet steam fed from a high pressure enclosure, so as to dry and contingently superheat said steam prior to injecting same into a turbine low pressure stage. This drier unit is constituted by at least a stack of separating sheets maintained in parallel relationship and at a slight angle with respect to the horizontal so as to allow the water provided by wet steam to flow toward a channel communicating with a manifold, and by means for guiding the steam between the sheets and evenly distributing it. This can be applied to steam turbines in nuclear power stations [fr

  15. Design and performance of BWC replacement steam generators for PWR systems

    Energy Technology Data Exchange (ETDEWEB)

    Klarner, R.; Steinmoeller, F.; Millman, J.; Schneider, W. [Babcock and Wilcox Canada, Cambridge, Ontario (Canada)

    1998-07-01

    In recent years, Babcock and Wilcox Canada (BWC) has provided a number of PWR Replacement Steam Generators (RSGS) to replace units that had experienced extensive Alloy 600 tube degradation. BWC RSG units are in operation at Northeast Utilities' Millstone Unit 2, Rochester Gas and Electric's Ginna Station, Duke Energy's Catawba Unit 1, McGuire Unit 1 and 2, Florida Power and Light's St. Lucie Unit 1 and Commonwealth Edison's Byron 1 Station. Extensive start-up performance characteristics have been obtained for Millstone 2, Ginna, McGuire 1, and Catawba 1 RSGS. The Millstone 2, Ginna and Catawba 1 RSGs have also undergone extensive inspections following their first cycle of operation. The design and start-up performance characteristics of these RSGs are presented. The BWC Replacement Steam generators were designed to fit the existing envelope of pressure boundary dimensions to ensure licensability and integration into the Nuclear Steam Supply System. The RSGs were provided with a tube bundle of Alloy 690TT tubing, sized to match or exceed the original steam generator (OSG) thermal performance including provision for the reduced thermal conductivity of Alloy 690 relative to Alloy 600. The RSG tube bundle configurations provide a higher circulation design relative to the OSG, and feature corrosion resistant lattice grid and U-bend tube supports which provide effective anti-vibration support. The tube bundle supports accommodate relatively unobstructed flow and allow unrestrained structural interactions during thermal transients. Efficient steam separators assure low moisture carryover as well as high circulation. Performance measurements obtained during start-up verify that the BWC RSGs meet or exceed the specified thermal and moisture carryover performance requirements. RSG water level stability results at nor-mal operation and during plant transients have been excellent. Visual and ECT inspections have confirmed minimal deposition and 100

  16. Design and performance of BWC replacement steam generators for PWR systems

    International Nuclear Information System (INIS)

    Klarner, R.; Steinmoeller, F.; Millman, J.; Schneider, W.

    1998-01-01

    In recent years, Babcock and Wilcox Canada (BWC) has provided a number of PWR Replacement Steam Generators (RSGS) to replace units that had experienced extensive Alloy 600 tube degradation. BWC RSG units are in operation at Northeast Utilities' Millstone Unit 2, Rochester Gas and Electric's Ginna Station, Duke Energy's Catawba Unit 1, McGuire Unit 1 and 2, Florida Power and Light's St. Lucie Unit 1 and Commonwealth Edison's Byron 1 Station. Extensive start-up performance characteristics have been obtained for Millstone 2, Ginna, McGuire 1, and Catawba 1 RSGS. The Millstone 2, Ginna and Catawba 1 RSGs have also undergone extensive inspections following their first cycle of operation. The design and start-up performance characteristics of these RSGs are presented. The BWC Replacement Steam generators were designed to fit the existing envelope of pressure boundary dimensions to ensure licensability and integration into the Nuclear Steam Supply System. The RSGs were provided with a tube bundle of Alloy 690TT tubing, sized to match or exceed the original steam generator (OSG) thermal performance including provision for the reduced thermal conductivity of Alloy 690 relative to Alloy 600. The RSG tube bundle configurations provide a higher circulation design relative to the OSG, and feature corrosion resistant lattice grid and U-bend tube supports which provide effective anti-vibration support. The tube bundle supports accommodate relatively unobstructed flow and allow unrestrained structural interactions during thermal transients. Efficient steam separators assure low moisture carryover as well as high circulation. Performance measurements obtained during start-up verify that the BWC RSGs meet or exceed the specified thermal and moisture carryover performance requirements. RSG water level stability results at nor-mal operation and during plant transients have been excellent. Visual and ECT inspections have confirmed minimal deposition and 100% tube integrity following

  17. Design and manufacture of steam generators for replacement

    International Nuclear Information System (INIS)

    Hirano, Hiroshi; Kuri, Syuhei

    1995-01-01

    The basic specification of the steam generators for replacement as heat exchangers (the pressure, temperature, flow rate and thermal output on primary and secondary sides) is set same as that of steam generators before replacement, but the latest design reflecting the operation experience obtained so far and taking the countermeasures for preventing heating tube damage in it is adopted, such as the heating tubes made of TT 690 alloy, the tube support plates with four-lobe shape tube holes made of stainless steel, the stainless steel rest fittings of three in one set and so on. After the heating tube break accident in Mihama No. 2 plant, the quality control was further strengthened. The comparison of the specifications of the steam generators of respective plants before and after the replacement is shown. The main objective of improving steam generators is the heightening of the reliability of heating tubes against intergranular attack and primary water stress corrosion cracking. The improvements of heating tube material, tube support plate material, secondary side heat flow, the shape of tube holes of tube support plates, the method of expanding heating tubes, and vibration-controlling fittings are explained. As to the manufacturing procedure and quality control, the manufacture of raw materials, the build-up welding of tube plates, the manufacture of lower half shell plates, the tube hole making of support plates, the insection of outer cylinder, flow rate distribution plate. Support plates and heating tubes, the sealing welding and expanding of heating tubes, the fixing of rest fittings, the manufacture and fixing of water chamber cover, the manufacture of upper half shell, the fixing of parts inside it, the final joint and inspection are described. (K.I.)

  18. Project No. 6 - Replacement of the heating and steam plant

    International Nuclear Information System (INIS)

    2000-01-01

    At present the Ignalina NPP facilities and Visaginas town are supplied with heat and steam from the district heating facility at Ignalina NPP. A back-up system, dating from 1979, supplies heat and steam when the district heating system is under repair or in case of outages of units 1 and 2. The existing back-up system does no longer meet with applicable technical and safety standards. A breakdown of the back-up system might result in the interruption of the supply to Ignalina NPP of heat and steam necessary for a number of processes, including waste management. Reconstruction of the existing boiler houses is not economically viable option, nor recommendable, for safety reasons, as it would mean the temporary closing of the back-up system. Project activities includes the design, construction and commissioning of the proposed facility, including all licensing documentation

  19. Piping hydrodynamic loads for a PWR power up-rate with steam generator replacement

    International Nuclear Information System (INIS)

    Julie M Jarvis; Allen T Vieira; James M Gilmer

    2005-01-01

    Full text of publication follows: Pipe break hydrodynamic loads are calculated for various systems in a PWR for a Power Up-rate (PUR) with a Steam Generator Replacement (SGR). PUR with SGR can change the system pressures, mass flowrates and pipe routing/configuration. These changes can alter the steam generator piping steam/water hammer loads. This paper discusses the need to benchmark against the original design basis, the use of different modeling techniques, and lessons learned. Benchmarking for licensing in the United States is vital in consideration of 10CFR50.59 and other licensing and safety issues. RELAP5 and its force post-processor R5FORCE are used to model the transient loads for various piping systems such as main feedwater and blowdown systems. Other modeling applications, including the Bechtel GAFT program, are used to evaluate loadings in the main steam piping. Forces are calculated for main steam turbine stop valve closure, feedwater pipe breaks and subsequent check valve slam, and blowdown isolation valve closure. These PUR/SGR forces are compared with the original design basis forces. Modeling techniques discussed include proper valve closure modeling, sonic velocity changes due to pipe material changes, and two phase flow effects. Lessons learned based on analyses done for several PWR PUR with SGR are presented. Lessons learned from these analyses include choosing the optimal replacement piping size and routing to improve system performance without resulting in excessive piping loads. (authors)

  20. Some economic aspects of steam generator replacements in nuclear power plants

    International Nuclear Information System (INIS)

    Lebegner, J.

    1995-01-01

    The steam generator replacements performed over last decade (about 25 replacements until now), indicate trends towards improved techniques, shorter schedules and reduced total exposure and total costs. The goal of this paper is to give a worldwide review of SG replacement experience with accent on the economic aspect of the SG replacement. The main information about carried out replacements will be presented: cost, schedules, exposures, SG supplier and type, date of replacement, etc. Furthermore, the paper will contain the list of planned steam generator replacements in Europe, Japan and US future replacement plans. Finally, some of NPPs will be described whose initial nominal power has been increased along with SG replacement. (author)

  1. Cleaning device for steam units in a nuclear power plant

    International Nuclear Information System (INIS)

    Sasamuro, Takemi.

    1978-01-01

    Purpose: To prevent radioactive contamination upon dismantling and inspection of steam units such as a turbine to a building containing such units and the peripheral area. Constitution: A steam generator indirectly heated by steam supplied from steam generating source in a separate system containing no radioactivity is provided to produce cleaning steam. A cleaning steam pipe is connected by way of a stop valve between separation valve of a nuclear power plant steam pipe and a high pressure turbine. Upon cleaning, the separation valve is closed, and steam supplied from the cleaning steam pipe is flown into a condenser. The water thus condensated is returned by way of a feed water heater and a condenser to a water storage tank. (Nakamura, S.)

  2. 24 CFR 970.31 - Replacement units.

    Science.gov (United States)

    2010-04-01

    ... 24 Housing and Urban Development 4 2010-04-01 2010-04-01 false Replacement units. 970.31 Section... PUBLIC HOUSING PROGRAM-DEMOLITION OR DISPOSITION OF PUBLIC HOUSING PROJECTS § 970.31 Replacement units. Notwithstanding any other provision of law, replacement public housing units may be built on the original public...

  3. Anti vibration bars replacement in Vandellos II steam generators

    International Nuclear Information System (INIS)

    Vinyes, R.; Leal, R.

    1994-01-01

    C.N. Vandellos II is equipped with three steam generators Westinghouse model F. The number of tubes is 5626 each SG and the material Inconel 600TT. During the first inservice inspection, in 1989, tube wall thickness reductions were observed due to fretting in zones of contact with the tubes anti vibration bars. In the 2 nd shutdown for refueling (1990) all the tubes subject to this type of degradation were inspected by eddy currents, occurring a significative increase in number of tubes affected as well as the quantity of plugged tubes for that reason. Additionally, Westinghouse performed visual inspection and dimensional control of gaps in the tube bundles. Taking in account the results, the replacement with AVBs of new design was decided. AVBs new design is more complex than the original due to the combination of flexible and expandable bars in order to eliminate gaps between tubes an bars an assure proper bundle support. Given that the installation has to be done under water for shielding, all unions are bolted so that no welding is required. Each one of the bars, 333 per SG, is attached to a support structure consisting in 6 retaining plates and 4 bridge plates. (Author)

  4. 300 Area steam plant replacement, Hanford Site, Richland, Washington: Environmental assessment

    International Nuclear Information System (INIS)

    1997-03-01

    Steam to support process operations and facility heating is currently produced by a centralized oil-fired plant located in the 300 Area and piped to approximately 26 facilities in the 300 Area. This plant was constructed during the 1940s and, because of tis age, is not efficient, requires a relatively large operating and maintenance staff, and is not reliable. The US Department of Energy is proposing an energy conservation measure for a number of buildings in the 300 Area of the Hanford Site. This action includes replacing the centralized heating system with heating units for individual buildings or groups of buildings, constructing new natural gas pipelines to provide a fuel source for many of these units and constructing a central control building to operate and maintain the system. A new steel-sided building would be constructed in the 300 Area in a previously disturbed area at least 400 m (one-quarter mile) from the Columbia River, or an existing 300 Area building would be modified and used. This Environmental Assessment evaluates alternatives to the proposed actions. Alternatives considered are: (1) the no action alternative; (2) use of alternative fuels, such as low-sulfur diesel oil; (3) construction of a new central steam plant, piping and ancillary systems; (4) upgrade of the existing central steam plant and ancillary systems; and (5) alternative routing of the gas distribution pipeline that is a part of the proposed action. A biological survey and culture resource review and survey were also conducted

  5. Environmentally Friendly Replacement of Mature 200 MW Coal-Fired Power Blocks with 2 Boilers Working on One 500 MW Class Steam Turbine Generator (2on1 Unit Concept)

    Science.gov (United States)

    Grzeszczak, Jan; Grela, Łukasz; Achter, Thomas

    2017-12-01

    The paper covers problems of the owners of a fleet of long-operated conventional power plants that are going to be decommissioned soon in result of failing to achieve new admissible emissions levels or exceeding pressure elements design lifetime. Energoprojekt-Katowice SA, Siemens AG and Rafako SA presents their joint concept of the solution which is a 2on1 concept - replacing two unit by two ultra-supercritical boilers feeding one turbine. Polish market has been taken as an example.

  6. Quad Cities Unit 2 Main Steam Line Acoustic Source Identification and Load Reduction

    International Nuclear Information System (INIS)

    DeBoo, Guy; Ramsden, Kevin; Gesior, Roman

    2006-01-01

    The Quad Cities Units 1 and 2 have a history of steam line vibration issues. The implementation of an Extended Power Up-rate resulted in significant increases in steam line vibration as well as acoustic loading of the steam dryers, which led to equipment failures and fatigue cracking of the dryers. This paper discusses the results of extensive data collection on the Quad Cities Unit 2 replacement dryer and the Main Steam Lines. This data was taken with the intent of identifying acoustic sources in the steam system. Review of the data confirmed that vortex shedding coupled column resonance in the relief and safety valve stub pipes were the principal sources of large magnitude acoustic loads in the main steam system. Modifications were developed in sub-scale testing to alter the acoustic properties of the valve standpipes and add acoustic damping to the system. The modifications developed and installed consisted of acoustic side branches that were attached to the Electromatic Relief Valve (ERV) and Main Steam Safety Valve (MSSV) attachment pipes. Subsequent post-modification testing was performed in plant to confirm the effectiveness of the modifications. The modifications have been demonstrated to reduce vibration loads at full Extended Power Up-rate (EPU) conditions to levels below those at Original Licensed Thermal Power (OLTP). (authors)

  7. Steam turbine of WWER-1000 unit

    International Nuclear Information System (INIS)

    Drahy, J.

    1986-01-01

    The manufacture was started by Skoda of a saturated steam, 1,000 MW, 3,000 rpm turbine designed for the Temelin nuclear power plant. The turbine provides steam for heating water for district heating, this either with an output of 893 MW for a three-stage water heating at 150/60 degC, or of 570 MW for a two-stage water heating at 120/60 degC. The turbine features one high-pressure and three identical low-pressure stages. The pressure gradient between the high-pressure and the low-pressure parts was optimized with respect to the thermal efficiency of the cycle and to the thermodynamic efficiency of the low-pressure part. A value of 0.79 MPa was selected corresponding to the maximum through-flow of steam entering the turbine. This makes 5,495 t/h, the admission steam parameters are 273.3 degC and 5.8 MPa. The feed water temperature is 220.9 degC. 300 cold starts, 1,000 starts after shutdowns for 55 to 88 hours and 600 starts after shutdown for 8 hours are envisaged for the entire turbine service life. (Z.M.). 5 figs., 1 tab., 6 refs

  8. The role of the safety analysis organization in steam generators replacement and reactor vessel head replacement evaluations

    International Nuclear Information System (INIS)

    Choe, Whee G.; Boatwright, W.J.

    2004-01-01

    When a major component in a nuclear power plant is replaced, especially the steam generators, the plant operator is presented a rare opportunity to learn from operating experience and significantly improve the performance, reliability and robustness of the plant. In addition to the use of improved materials, improved design margins can be built into the component specification that can later be used to provide meaningful operating margins. A Safety Analysis organization that is well-integrated with other plant organizations and possesses a detailed knowledge of the plant design and licensing bases can effectively balance the wants and needs of each organization to optimize the benefits realized by the plant as a whole. Knowledge of the assumptions, limitations, and available margins, both analytical and operating, can be used to specify a replacement steam generator design that optimizes costs and operating improvements. The work scope required to support the new design can be controlled through carefully selected and evaluated restrictions in operations, development of alternate operating strategies, and imposition of appropriate limitations. The important point is that the effective Safety Analysis organization must possess both the breadth and depth of knowledge of the plant design and operations and proactively use this information to support the replacement steam generator project. (author)

  9. On economic efficiency of nuclear power unit life extension using steam-gas topping plant

    International Nuclear Information System (INIS)

    Kuznetsov, Y.N.; Lisitsa, F.D.; Smirnov, V.G.

    2001-01-01

    The different options for life extension of the operating nuclear power units have been analyzed in the report with regard for their economic efficiency. A particular attention is given to the option envisaging the reduction of reactor power output and its subsequent compensation with a steam-gas topping plant. Steam generated at its heat-recovery boilers is proposed to be used for the additional loading of the nuclear plant turbine so as to reach its nominal output. It would be demonstrated that the implementation of this option allows to reduce total costs in the period of power plant life extension by 24-29% as compared with the alternative use of the replacing steam-gas unit and the saved resources could be directed, for instance, for decommissioning of a reactor facility. (authors)

  10. The steam generator repair project of the Donald C. Cook Nuclear Plant, Unit 2

    International Nuclear Information System (INIS)

    White, J.D.

    1993-01-01

    Donald C. Cook Nuclear Plant Unit 2 is part of a two unit nuclear complex located in southwestern Michigan and owned and operated by the Indiana Michigan Power Company. The Cook Nuclear Plant is a pressurized water reactor (PWR) plant with four Westinghouse Series 51 steam generators housed in an ice condenser containment. This paper describes the program undertaken by Indiana Michigan Power and the American Electric Power Service Corporation (AEPSC) to repair the Unit 2 steam generators. (Both Indiana Michigan Power and AEPSC arc subsidiaries of American Electric Power Company, Incorporated (AEP). AEPSC provides management and technical support services to Indiana Michigan Power and the other AEP operating companies.) Eddy current examinations, in a series of refueling and forced outages between November 1983 and July 1986 resulted in 763 (5.6%) plugged tubes. In order to maintain adequate reactor core cooling, a limit of 10% is placed on the allowable percentage of steam generator tubes that can be removed from service by plugging. Additionally, sections of tubes were removed for metallurgical analysis and confirmed that the degradation was due to intergranular stress corrosion cracking. In developing the decision on how to repair the steam generators, four alternative actions were considered for addressing these problems: retubing in place, sleeving, operating at 80% reactor power to lower temperature and thus reduce the rate of corrosion, replacing steam generator lower assemblies

  11. Electropolishing of replacement steam generator channel heads at Millstone-2 PWR

    International Nuclear Information System (INIS)

    Hudson, M.J.B.; Raney, H.; Raney, D.; Spalaris, C.N.

    1992-07-01

    A field application of EPRI-developed steam generator electropolishing technique was performed at Millstone-2 PWR. The process was qualified under previous programs on a laboratory scale, but it was thought appropriate to scale up application to full size components. Replacement of steam generators at Millstone-2 provided a unique opportunity to demonstrate that electropolishing can be applied safely and at a cost which was judged to be recoverable after a small number of fuel cycles. The project, preparation, electropolishing and cleanup, was completed at the reactor site in 25 working days. An alternate, less costly electrolyte solution was qualified for use in future applications

  12. Steam generator issues in the United States

    International Nuclear Information System (INIS)

    Strosnider, J.R.

    1997-01-01

    Alloy 600 steam generator tubes in the US have exhibited degradation mechanisms similar to those observed in other countries. Effective programs have been implemented to address several degradation mechanisms including: wastage; mechanical wear; pitting; and fatigue. These degradation mechanisms are fairly well understood as indicated by the ability to effectively mitigate/manage them. Stress corrosion cracking (SCC) is the dominant degradation mechanism in the US. SCC poses significant inspection and management challenges to the industry and the regulators. The paper also addresses issues of research into SCC, inspection programs, plugging, repair strategies, water chemistry, and regulatory control. Emerging issues in the US include: parent tube cracking at sleeve joints; detection and repair of circumferential cracks; free span cracking; inspection and cracking of dented regions; and severe accident analysis

  13. MILA Antenna Control Unit Replacement Project

    Science.gov (United States)

    Bresette, Jeremy

    2007-01-01

    The Air to Ground Subsystem (AGS) Antenna Control Units at the MILA Ground Network Tracking Station are at end-of-life and are being replaced. AGS consists of two antennas at MILA (Quad-Helix and Teltrac). Software was taken from the existing Subsystem Controller and modified for the Antenna Control Unit (ACU). The software is capable of receiving and sending commands to and from the ACU. Moving the azimuth clockwise, counterclockwise, moving the elevation up or down, turning servo power on and off, and inputting azimuth and elevation angles are commands that the antenna can receive.

  14. Proposal of organisation and ALARA procedures for maintenance site: application to replacement of steam generator

    International Nuclear Information System (INIS)

    Lochard, J.; Lefaure, C.

    1989-08-01

    This report proposes generic organization and ALARA procedures for preparing a maintenance site at a NPP. After a short description of the ALARA principle, it describes the proposition for French sites. They are grouped according to the following: motivation, organisation, means. They are illustrated by the example of steam generator replacement. Three special points concerning preparation of the site are developed: education; training of operators; review of the project

  15. Replacement of outboard main steam isolation valves in a boiling water reactor plant

    Energy Technology Data Exchange (ETDEWEB)

    Schlereth, J.R.; Pennington, D.

    1996-12-01

    Most Boiling Water Reactor plants utilize wye pattern globe valves for main steam isolation valves for both inboard and outboard isolation. These valves have required a high degree of maintenance attention in order to pass the plant local leakage rate testing (LLRT) requirements at each outage. Northern States Power made a decision in 1993 to replace the outboard valves at it`s Monticello plant with double disc gate valves. The replacement of the outboard valves was completed during the fall outage in 1994. During the spring outage in April of 1996 the first LLRT testing was performed with excellent results. This presentation will address the decision process, time requirements and planning necessary to accomplish the task as well as the performance results and cost effectiveness of replacing these components.

  16. Replacement of outboard main steam isolation valves in a boiling water reactor plant

    International Nuclear Information System (INIS)

    Schlereth, J.R.; Pennington, D.

    1996-01-01

    Most Boiling Water Reactor plants utilize wye pattern globe valves for main steam isolation valves for both inboard and outboard isolation. These valves have required a high degree of maintenance attention in order to pass the plant local leakage rate testing (LLRT) requirements at each outage. Northern States Power made a decision in 1993 to replace the outboard valves at it's Monticello plant with double disc gate valves. The replacement of the outboard valves was completed during the fall outage in 1994. During the spring outage in April of 1996 the first LLRT testing was performed with excellent results. This presentation will address the decision process, time requirements and planning necessary to accomplish the task as well as the performance results and cost effectiveness of replacing these components

  17. NIF Laser Line Replaceable Units (LRUs)

    International Nuclear Information System (INIS)

    Larson, D W

    2003-01-01

    The National Ignition Facility (NIF) is designed with its high value optical systems in cassettes called Line Replaceable Units (LRUs). Virtually all of the NIF's active components are assembled in one of the ∼4000 electrical and optical LRUs that serve between two and eight of NIF's 192 laser beam lines. Many of these LRUs are optomechanical assemblies that are roughly the size of a telephone booth. The primary design challenges for this hardware include meeting stringent mechanical precision, stability and cleanliness requirements. Pre-production units of each LRU type have been fielded on the first bundle of NIF and used to demonstrate that NIF meets its performance objectives. This presentation provides an overview of the NIF LRUs, their design and production plans for building out the remaining NIF bundles

  18. Evaluation of Waterford Steam Electric Station Unit 3 technical specifications

    International Nuclear Information System (INIS)

    Baxter, D.E.; Bruske, S.J.

    1985-09-01

    This document was prepared for the Nuclear Regulatory Commission (NRC) to assist them in determining whether the Waterford Steam Electric Station Unit 3 Technical Specifications (T/S), which govern plant systems configurations and operations, are in conformance with the requirements of the Final Safety Analysis Report (FSAR) as amended, and the requirements of the Safety Evaluation Report (SER) as supplemented. A comparative audit of the FSAR as amended, and the SER as supplemented was performed with the Waterford T/S. Several discrepancies were identified and subsequently resolved by the cognizant NRC reviewer. Pending completion of the resolutions noted in Part 3 of this report, the Waterford Steam Electric Station Unit 3 T/S, to the extent reviewed, are in conformance with the FSAR and SER

  19. Functional characterization of steam jet-cooked buckwheat flour as a fat replacer in cake-baking.

    Science.gov (United States)

    Min, Bockki; Lee, Seung Mi; Yoo, Sang-Ho; Inglett, George E; Lee, Suyong

    2010-10-01

    With rising consumer awareness of obesity, the food industry has a market-driven impetus to develop low-fat or fat-free foods with acceptable taste and texture. Fancy buckwheat flour was thus subjected to steam jet-cooking and the performance of the resulting product in cake-baking was evaluated as a fat replacer. Steam jet-cooking caused structural breakdown and starch gelatinization of buckwheat flour, thus increasing its water hydration properties. In the pasting measurements, steam jet-cooked buckwheat flour exhibited high initial viscosity, while no peak viscosity was observed. Also, the suspensions of steam jet-cooked buckwheat flour exhibited shear-thinning behaviors, which were well characterized by the power law model. When shortening in cakes was replaced with steam jet-cooked buckwheat gels, the specific gravity of cake batters significantly increased, consequently affecting cake volume after baking. However, shortening replacement with steam jet-cooked buckwheat up to 20% by weight appeared to be effective in producing cakes as soft as the control without volume loss. When buckwheat flour was thermomechanically modified by steam jet-cooking, it was successfully incorporated into cake formulations for shortening up to 20% by weight, producing low-fat cakes with comparable volume and textural properties to the control. Copyright © 2010 Society of Chemical Industry.

  20. Units 3 and 4 steam generators new water level control system

    International Nuclear Information System (INIS)

    Dragoev, D.; Genov, St.

    2001-01-01

    The Steam Generator Water Level Control System is one of the most important for the normal operation systems, related to the safety and reliability of the units. The main upgrading objective for the SG level and SGWLC System modernization is to assure an automatic maintaining of the SG level within acceptable limits (below protections and interlocks) from 0% to 100% of the power in normal operation conditions and in case of transients followed by disturbances in the SG controlled parameters - level, steam flow, feedwater flow and/or pressure/temperature. To achieve this objective, the computerized controllers of new SG water level control system follows current computer control technology and is implemented together with replacement of the feedwater control valves and the needed I and C equipment. (author)

  1. Pre-service baseline inspection using x-probe of Oconee replacement steam generators

    International Nuclear Information System (INIS)

    Addario, M.; Shipp, P.; Davis, K.; Fogal, C.

    2003-01-01

    The eddy current method has been the industry standard for inspecting steam generator tubing for many years and the level of sophistication of coil technology has continued to evolve during that time. State of the art array probe systems now employ multiple sensitivity zones in the probe to better detect and characterize defects in an efficient manner. Owners and regulators of nuclear power plants are interested in the most effective and efficient inspection possible. The ultimate goal has been to meet or exceed new and existing regulatory and design requirements by maximizing the quantity and quality of eddy current data collected while minimizing both the time needed to perform the inspection and the radiation exposure. The X-Probe is an example of this new eddy current array technology. Qualified to detect all types of known defects in steam generator tubing, the technology is comprised of a system of probe, data acquisition instrumentation, computer and human interface software. Recently, Duke Power, along with Babcock and Wilcox Canada and the system developer R/D Tech, collaborated to implement this technology in a first of a kind full scale pre-service inspection of replacement steam generators for Duke Power's Oconee nuclear generating station at Babcock and Wilcox Canada's Cambridge plant. The discussion in this paper will briefly describe the X-Probe technology, describe the system required to perform the inspection, present the general results of the inspection and finally draw some comparative benefit conclusions for both pre-service and in-service applications. (author)

  2. Development of radiation protection technology for application of the retired steam generator, Kori Unit no. 1

    Energy Technology Data Exchange (ETDEWEB)

    Kim, J. H.; Jang, D. C.; Song, K. S.; Lee, S. J.; Ahn, C. S.; Kim, D. H.; Im, Y. K.; Kim, H. D. [Hanil Nuclear Co., Ltd., Anyang (Korea, Republic of)

    2005-04-15

    It is a field study to develop and verify maintenance technologies such as verification and technology development of ECT (Eddy current test) using failure, heat tube excavation and field pressure test regarding the utilization of retired steam generator using 2 units of Retired Steam Generator in Kori 1 that was replaced for the first time in Korea in 1998. Since May, 2003, our team has investigated Retired Steam Generator which was stored in Radioactive waste warehouse in Korea Hydro and Nuclear Power Kori unit no.1 Branch, in order to study natural fault ECT signal acquisition, maintenance technology verification, small tubes/samples abstraction. A temporal task zone was made focusing on 'Man Way at the bottom of Chamber 'A'.' The purpose of the study is to establish Radiological Protection and Radioactive Waste Treatment Plan by setting ALARA (As Low As Reasonably Achievable) goal systematically, which is the basic concept of Radiological Protection and reduction in exposure of radiological workers to radioactive materials with proper Radiological Protection countermeasures according to the changes in radioactivity, to prevent expansion from contamination and to manage 'Radioactive Waste Reduction Activities' effectively.

  3. Steam generator leak detection at Bruce A Unit 1

    International Nuclear Information System (INIS)

    Maynard, K.J.; McInnes, D.E.; Singh, V.P.

    1997-01-01

    A new steam generator leak detection system was recently developed and utilized at Bruce A. The equipment is based on standard helium leak detection, with the addition of moisture detection and several other capability improvements. All but 1% of the Unit 1 Boiler 03 tubesheet was inspected, using a sniffer probe which inspected tubes seven at a time and followed by individual tube inspections. The leak search period was completed in approximately 24 hours, following a prerequisite period of several days. No helium leak indications were found anywhere on the boiler. A single water leak indication was found, which was subsequently confirmed as a through-wall defect by eddy current inspection. (author)

  4. Safety analysis program for steam generators replacement and power uprate at Tihange 2 nuclear power plant

    International Nuclear Information System (INIS)

    Delhaye, X.; Charlier, A.; Damas, Ph.; Druenne, H.; Mandy, C.; Parmentier, F.; Pirson, J.; Zhang, J.

    2002-01-01

    The Belgian Tihange 2 nuclear power plant went into commercial operation in 1983 producing a thermal power of 2785 MW. Since the commissioning of the plant the steam generators U-tubes have been affected by primary stress corrosion cracking. In order to avoid further degradation of the performance and an increase in repair costs, Electrabel, the owner of the plant, decided in 1997 to replace the 3 steam generators. This decision was supported by the feasibility study performed by Tractebel Energy Engineering which demonstrated that an increase of 10% of the initial power together with a fuel cycle length of 18 months was achieved. Tractebel Energy Engineering was entrusted by Electrabel as the owner's engineer to manage the project. This paper presents the role of Tractebel Energy Engineering in this project and the safety analysis program necessary to justify the new operation point and the fuel cycle extension to 18 months re-analysis of FSAR chapter 15 accidents and verification of the capacity of the safety and auxiliary systems. The FSAR chapter 15 accidents were reanalyzed jointly by Framatome and Tractebel Energy Engineering while the systems verifications were carried out by Tractebel Energy Engineering. (author)

  5. The impact of steam generator replacement on PWR primary system contamination

    International Nuclear Information System (INIS)

    Dacquait, F.; Marteau, H.; Guinard, L.; Ranchoux, G.; Taunier, S.; Wintergerst, M.; Bretelle, J.L.; Rocher, A.

    2010-01-01

    This paper analyses the impact of Steam Generator Replacement (SGR) on PWR primary circuit contamination. It presents a comparison of the activities deposited inside the primary system and released during refuelling outages after SGR with three different SG tube alloys (600, 690 and 800) and different SG tube manufacturing processes. A SGR has a great impact on the primary system contamination. After SGR, whatever the SG tube material is, the typical variations are the following: The 58 Co contamination increases for 1 to 3 cycles, and then decreases to very low levels in some cases, mainly depending on the manufacturing process of the replacement SG tubes; The 60 Co Co contamination tends to decrease on the primary coolant pipes and increases by a lower rate on the new SG tubes. This analysis highlights the importance on contamination levels after SGR of both the corrosion product deposits on the primary surfaces before SGR and the surface finish of the SG tubes related to their manufacturing process. (author)

  6. Fuqing nuclear power of nuclear steam turbine generating unit No.1 at the implementation and feedback

    International Nuclear Information System (INIS)

    Cao Yuhua; Xiao Bo; He Liu; Huang Min

    2014-01-01

    The article introduces the Fuqing nuclear power of nuclear steam turbine generating unit no.l purpose, range of experience, experiment preparation, implementation, feedback and response. Turn of nuclear steam turbo-generator set flush, using the main reactor coolant pump and regulator of the heat generated by the electric heating element and the total heat capacity in secondary circuit of reactor coolant system (steam generator secondary side) of saturated steam turbine rushed to 1500 RPM, Fuqing nuclear power of nuclear steam turbine generating unit no.1 implementation of the performance of the inspection of steam turbine and its auxiliary system, through the test problems found in the clean up in time, the nuclear steam sweep turn smooth realization has accumulated experience. At the same time, Fuqing nuclear power of nuclear steam turbine generating unit no.1 at turn is half speed steam turbine generator non-nuclear turn at the first, with its smooth realization of other nuclear power steam turbine generator set in the field of non-nuclear turn play a reference role. (authors)

  7. MINAC radiography performed on susquehanna Steam Electric Station Unit 1

    International Nuclear Information System (INIS)

    Bognet, J.C.

    1986-01-01

    Ten welds were volumetrically examined with a manual and automated ultrasonic (UT) system during a Susquehanna Steam Electric Station (SES) Unit 1 preservice inspection. The automated system had been recently developed and several problems were encountered in this first field application. The ten welds examined had a Sweepolet-to-Risor weld configuration, which further complicated the examination effort. This weld configuration has corrosion-resistant cladding applied to the outside and inside circumference and, as a result of an installation/removal/reinstallation sequence during plant construction, is often referred to as the double weld. After several attempts to obtain interpretable UT data failed (e.g., repeatable data), the examination effort was terminated. PP and L opted to pursue using the Miniature Linear Accelerator (MINAC) to perform radiographic examination. The results were referenced in the Susquehanna SES Unit 1 outage summary report and submitted to the NRC. The total effort was viewed as a complete success with no impact to the overall outage duration. All welds previously attempted by automated and manual UT were successfully examined using the MINAC

  8. 15 years steam generator experience in German PWR power plants; part II: replacement of two completely assembled steam generators within ten weeks

    International Nuclear Information System (INIS)

    Scheuktanz, G.; Bouecker, R.; Riess, R.; Soellner, P.; Stieding, L.; Termeuhlen, H.

    1984-01-01

    This paper reports on the replacement of two steam generators at the Obrigheim power plant during a 10-week period, including a description of the methods and equipment used to do so. It is concluded that the method should be used only if transportation conditions within the reactor building preclude a complete system exchange and that one of the main reasons for the success of this operation was the very close relationship established between plant personnel and the equipment supplier and contractor, a relationship which began when the project was in the planning stage

  9. Examination of steam generator alloy 800 NG tube from the Almaraz unit 2 NPP

    International Nuclear Information System (INIS)

    Diego, G. de; Gomez Briceno, D.; Maffiotte, C.; Baladia, M.; Arias, C.J.

    2015-01-01

    The steam generators of Almaraz Unit 2 were replaced in 1997 by the model 61W/D3 (Siemens) with Alloy 800NG steam generator tubes. Denting indications were firstly detected in 2006 in the SG-3. Crack indications were identified in 2009. At the end of 2011, three tubes were recovered from this steam generator to carry out destructive examination in order to identify the root cause of the tubes degradation. Analysis of deposits point out the existence of multiples elements in the removed OD (Outer Diameter) deposits as well as in the deposits at the free tube under sludge and at the transition zone. Deposits are more abundant at the transition zone than at free tube. About 10% Na concentration has been detected, whereas S and Cl appear in small concentrations. Si appears regularly and Cr, Ni concentrations in the deposits are similar. Multiple intergranular cracks have been detected at 3 mm above the last contact point between the tube and the TS (tube support), in a band of around 5 mm, practically in the whole perimeter of the tube. Fracture surface of crack-B was partially covered by a Si rich layer, whereas fracture surface of crack-A seems to be cleaner. However, no significant differences in composition, except higher amount of S in crack-B, were found in the deposits of both cracks. EDX mapping and Auger profiles point out Ni enrichment with slight Cr enrichment or depletion and Fe depletion. The comparison of Auger profiles with available results for Alloy 800 tested in caustic and acid sulfate environments seems to indicate that the environment inside the cracks detected in the tube R67C48 is neutral or moderately caustic

  10. Overview of the United States steam generator development programs

    Energy Technology Data Exchange (ETDEWEB)

    Kaspar, P W; Lowe, P A

    1975-07-01

    The LMFBR steam generator development program of the USA was initiated to support the development of reliable designs and meaningful performance data for these critical components. Since the steam generators include the structural boundary between heated sodium and water, the consequences of small flaws in the materials that form the boundary are significant. Successful development and demonstration of commercial LMFBR power plants requires the consideration of many factors in addition to the design, construction and operation of a particular plant. Additional factors which must be assessed include: economics, reliability, safety, environment, operability, maintainability and conservation of the resources. In terms of the steam generator these items led to the selection of a single wall tube design using a forced recirculating system for the present Clinch River Breeder Reactor. There are strong economic incentives to use a once-through steam generating system in future designs.

  11. Seeking optimal renal replacement therapy delivery in intensive care units.

    Science.gov (United States)

    Kocjan, Marinka; Brunet, Fabrice P

    2010-01-01

    Globally, critical care environments within health care organizations strive to provide optimal quality renal replacement therapy (RRT), an artificial replacement for lost kidney function. Examination of RRT delivery model literature and a case study review of the multidisciplinary-mixed RRT delivery model utilized within a closed medical surgical intensive care unit illustrates the organizational and clinical management of specialized resource and multidisciplinary roles. The successful utilization of a specific RRT delivery model is dependent upon resource availability.

  12. Coupled RELAP5/PANTHER/COBRA steam line break accident analysis in support of licensing DOEL 2 power uprate and steam generator replacement

    International Nuclear Information System (INIS)

    Zhang, J.; Bosso, S.; Henno, X.; Ouliddren, K.; Schneidesch, C.R.; Hove, W. van

    2004-01-01

    The nuclear reactor accident analyses using best estimate codes provide a better understanding and more accurate modeling of the key physical phenomena, which allows a more realistic evaluation of the conservatism and margins in the final safety analysis report (FSAR) accident analysis. The use of the best estimate codes and methods is necessary to meet the increasing technical, licensing and regulatory requirements for major plant changes (e.g. steam generator replacement), power uprate, core design optimization (cycle extension), as well as Periodic Safety Review. Since 1992, Tractebel Engineering (TE) has developed and applied a deterministic bounding approach to FASR accident analysis using the best estimate system thermal hydraulic code RELAP5/MOD2.5 and the subchannel thermal hydraulic code COBRA-3C. This approach has been accepted by the Belgian Safety Authorities, and turned out to be cost effective for most of the non-LOCA transient analyses. Since this approach adapts a decoupled modeling of the core responses, the analysis results often involved too large un-quantified conservatisms, due to either simplistic approximations for asymmetric accidents with strong 3D core neutronics - plant thermal hydraulics interactions, or additional penalties introduced from 'incoherent' initial/boundary conditions for separate plant and core analyses. Therefore, an external dynamic coupling between the RELAP5/MOD2.5 code and the 3-D neutronic code PANTHER was implemented since 1997 via the transient analysis code linkage program TALINK. Furthermore, a static linkage between the PANTHER code and the COBRA-3C code was developed for on-line calculation of (Departure from Nucleate Boiling Ratio (DNBR). TE intends to use the coupled code package for licensing non-symmetric FSAR accident analysis. The TE coupled code package has been applied to develop a main steam line break (MSLB) accident analysis methodology [using the TE deterministic bounding approach. The methodology

  13. Steam generation unit in a simple version of biomass based small cogeneration unit

    Directory of Open Access Journals (Sweden)

    Sornek Krzysztof

    2014-01-01

    Full Text Available The organic Rankine cycle (ORC is a very promising process for the conversion of low or medium temperature heat to electricity in small and micro scale biomass powered systems. Classic ORC is analogous to Clausius–Rankine cycle in a steam power plant, but instead of water it uses low boiling, organic working fluids. Seeking energy and economical optimization of biomass-based ORC systems, we have proposed some modifications e.g. in low boiling fluid circuit construction. Due to the fact that the operation of a micro steam turbine is rather inefficient from the technical and economic point of view, a specially modified air compressor can be used as a steam piston engine. Such engine should be designed to work at low pressure of the working medium. Studies regarding the first version of the prototype installation were focused on the confirmation of applicability of a straw boiler in the prototype ORC power system. The results of the previous studies and the studies described in the paper (on the new cogeneration unit confirmed the high potential of the developed solution. Of course, many further studies have to be carried out.

  14. Recent technology for nuclear steam turbine-generator units

    International Nuclear Information System (INIS)

    Moriya, Shin-ichi; Kuwashima, Hidesumi; Ueno, Takeshi; Ooi, Masao

    1988-01-01

    As the next nuclear power plants subsequent to the present 1,100 MWe plants, the technical development of ABWRs was completed, and the plan for constructing the actual plants is advanced. As for the steam turbine and generator facilities of 1,350 MWe output applied to these plants, the TC6F-52 type steam turbines using 52 in long blades, moisture separation heaters, butterfly type intermediate valves, feed heater drain pumping-up system and other new technologies for increasing the capacity and improving the thermal efficiency were adopted. In this paper, the outline of the main technologies of those and the state of examination when those are applied to the actual plants are described. As to the technical fields of the steam turbine system for ABWRs, the improvement of the total technologies of the plants was promoted, aiming at the good economical efficiency, reliability and thermal efficiency of the whole facilities, not only the main turbines. The basic specification of the steam turbine facilities for 50 Hz ABWR plants and the main new technologies applied to the turbines are shown. The development of 52 in long last stage blades, the development of the analysis program for the coupled vibration of the large rotor system, the development of moisture separation heaters, the turbine control system, condensate and feed water system, and the generators are described. (Kako, I.)

  15. The economic aspect of transition to power units with supercritical steam parameters

    Energy Technology Data Exchange (ETDEWEB)

    V.R. Kotler

    2007-09-15

    Information on the development and use of power units for supercritical and ultrasupercritical steam parameters in the United States, as well as in Europe and Japan, is presented. It is shown that increasing the parameters of steam reduces not only the fuel consumption, but also the specific emissions of toxic and greenhouse gases. Results of a calculation carried out at the EPRI (the United States) are presented, which show that it is advisable to construct power units for supercritical parameters only at certain (sufficiently high) price of the fuel being fired.

  16. Steam generator tube integrity requirements and operating experience in the United States

    International Nuclear Information System (INIS)

    Karwoski, K.J.

    2009-01-01

    Steam generator tube integrity is important to the safe operation of pressurized-water reactors. For ensuring tube integrity, the U.S. Nuclear Regulatory Commission uses a regulatory framework that is largely performance based. This performance-based framework is supplemented with some prescriptive requirements. The framework recognizes that there are three combinations of tube materials and heat treatments currently used in the United States and that the operating experience depends, in part, on the type of material used. This paper summarizes the regulatory framework for ensuring steam generator tube integrity, it highlights the current status of steam generators, and it highlights some of the steam generator issues and challenges that exist in the United States. (author)

  17. Innovation of blow-down system in steam generators of a VVER 440 unit

    International Nuclear Information System (INIS)

    Matal, O.; Simo, T.; Mancev, M.D.

    1997-01-01

    The impurities getting into the steam generator with the feedwater are continually removed by the blowdown and unit sludge system. The mostly non-symmetrical type of pipe branches under steam generators at WWER-440 units causes nonuniform blowdown flow rates at the halves of the steam generator; this often leads to a blocking of the pipe with the lower flow rate. The most simple way of hydraulically equalizing the blowdown pipes is to implement symmetric blowdown pipes and to install efficient throttling elements in the pipe. The proposed innovation will make it possible to re-distribute the blowdown flow rates and to reduce more effectively the concentrations of impurities in steam generators. (M.D.)

  18. Opinion on serviceability of Bugey 3 reactor steam generators until their replacement foreseen in September 2010

    International Nuclear Information System (INIS)

    2010-04-01

    This document briefly reports the damage characterization of tubular bundles in steam generators of the Bugey 3 reactor, discusses the actions which are foreseen to prevent a tube failure risk, and discusses the risk of leakage during operation. Recommendations are formulated about investigation on the corrosion, and about prediction computation to be performed

  19. Review of the data bases for making decisions regarding Trojan steam generator replacement options

    International Nuclear Information System (INIS)

    Johnson, A.B. Jr.; Gilbert, E.R.

    1992-03-01

    The central focus for this assessment has been to compare the corrosion behavior of two steam generator (SG) tube materials: Inconel 600 TT and Inconel 690 TT from (a) SG operating experience, and (b) laboratory data. The scope and results of the comparisons are summarized in this section. They provide the basis for projecting SG longevity

  20. Search and Retrieval of Foreign Objects for the Steam Generator of Wolsung NPP Unit 1

    International Nuclear Information System (INIS)

    Jeong, Woo-Tae; Lee, Kyung-Ho

    2016-01-01

    We developed a foreign object search and retrieval (FOSAR) system for Wolsung NPP unit 1 steam generators. The steam generators of Wolsung NPP unit 1 have one 2.5 inch hand hole and two 4 inch hand holes. The FOSAR system was designed to be installed through 4 inch hand holes. Using permanent magnet, the FOSAR system was firmly attached to the vertical annulus wall of the steam generator. We successfully developed the FOSAR system for Wolsung NPP unit 1. Using the developed FOSAR system, technicians successfully found and removed various foreign objects. Most of the foreign objects, we found, were made of carbon steel sheet, therefore magnet tool was the most useful to remove it. Alligator tool was sometimes used. Based on the experience during the FOSAR activities, we are developing a lancing system for Wolsung NPP unit 1. It will be designed and manufactured until November 2016

  1. Search and Retrieval of Foreign Objects for the Steam Generator of Wolsung NPP Unit 1

    Energy Technology Data Exchange (ETDEWEB)

    Jeong, Woo-Tae; Lee, Kyung-Ho [KHNP CRI, Daejeon (Korea, Republic of)

    2016-10-15

    We developed a foreign object search and retrieval (FOSAR) system for Wolsung NPP unit 1 steam generators. The steam generators of Wolsung NPP unit 1 have one 2.5 inch hand hole and two 4 inch hand holes. The FOSAR system was designed to be installed through 4 inch hand holes. Using permanent magnet, the FOSAR system was firmly attached to the vertical annulus wall of the steam generator. We successfully developed the FOSAR system for Wolsung NPP unit 1. Using the developed FOSAR system, technicians successfully found and removed various foreign objects. Most of the foreign objects, we found, were made of carbon steel sheet, therefore magnet tool was the most useful to remove it. Alligator tool was sometimes used. Based on the experience during the FOSAR activities, we are developing a lancing system for Wolsung NPP unit 1. It will be designed and manufactured until November 2016.

  2. A steam generating unit identification using subspace methods

    International Nuclear Information System (INIS)

    Poshtan, J.; Mojallali, H.

    2002-01-01

    A Valid boiler model is a tool for the improvement of the steam generation control system and hence results boiler efficiency enhancement. However, methods of obtaining such a model are not readily found in the open literature and are often specific to a particular plant. This paper presents boiler model using a new method in system identification called S ubspace methods . This method is shown to provide an accurate state space model for boiler in a few numbers of operations, directly from input-output data without any prior knowledge of the system equations and any requirement to several stages of testing

  3. LMFBR steam generator leak detection development in the United States

    Energy Technology Data Exchange (ETDEWEB)

    Magee, P M; Gerrels, E E; Greene, D A [General Electric Company, Sunnyvale, CA (United States); McKee, J [Argonne National Laboratory, Argonne, IL (United States)

    1978-10-01

    Leak detection for Liquid Metal Fast Breeder Reactor steam generators is an important economic factor in the shutdown, repair and restart of a plant. Development of leak detection systems in the U.S. has concentrated on four areas: (1) chemical (H{sub 2} and O{sub 2}) leak detection meters; (2) acoustic leak detection/location techniques; (3) investigation of leak behavior (enlargement, damage effects, plugging and unplugging); and (4) data management for plant operations. This paper discusses the status, design aspects, and applications of leak detection technology for LMFBR plants. (author)

  4. LMFBR steam generator leak detection development in the United States

    International Nuclear Information System (INIS)

    Magee, P.M.; Gerrels, E.E.; Greene, D.A.; McKee, J.

    1978-01-01

    Leak detection for Liquid Metal Fast Breeder Reactor steam generators is an important economic factor in the shutdown, repair and restart of a plant. Development of leak detection systems in the U.S. has concentrated on four areas: (1) chemical (H 2 and O 2 ) leak detection meters; (2) acoustic leak detection/location techniques; (3) investigation of leak behavior (enlargement, damage effects, plugging and unplugging); and (4) data management for plant operations. This paper discusses the status, design aspects, and applications of leak detection technology for LMFBR plants. (author)

  5. Consolidated nuclear steam generator

    International Nuclear Information System (INIS)

    Jabsen, F.S.; Schluderberg, D.C.; Paulson, A.E.

    1978-01-01

    An improved system of providing power has a unique generating means for nuclear reactors with a number of steam generators in the form of replaceable modular units of the expendable type to attain the optimum in effective and efficient vaporization of fluid during the generating power. The system is most adaptable to undrground power plants and marine usage

  6. Recent technology for BWR nuclear steam turbine unit

    International Nuclear Information System (INIS)

    Moriya, Shin-ichi; Masuda, Toyohiko; Kashiwabara, Katsuto; Oshima, Yoshikuni

    1990-01-01

    As to the ABWR plants which is the third improvement standard boiling water reactor type plants, already the construction of a plant of 1356 MWe class for 50 Hz is planned. Hitachi Ltd. has accumulated the technology for the home manufacture of a whole ABWR plant including a turbine. As the results, the application of a butterfly type combination intermediate valve to No.5 plant in Kashiwazaki Kariwa Nuclear Power Station, Tokyo Electric Power Co., Inc., which began the commercial operation recently and later plants, the application of a moisture separating heater to No.4 plant in Hamaoka Nuclear Power Station, Chubu Electric Power Co., Inc., which is manufactured at present and later plants and so on were carried out. As to the steam turbine facilities for nuclear power generation manufactured by Hitachi Ltd., three turbines of 1100 MWe class for 50 Hz and one turbine for 60 Hz are in operation. As the new technologies for the steam turbines, the development of 52 in long last stage blades, the new design techniques for the rotor system, the moisture separating heater, the butterfly type combination intermediate valve, cross-around pipes and condensate and feedwater system are reported. (K.I.)

  7. 75 FR 82414 - Carolina Power & Light Company; H. B. Robinson Steam Electric Plant, Unit No. 2; Exemption

    Science.gov (United States)

    2010-12-30

    ... NUCLEAR REGULATORY COMMISSION [Docket No. 50-261; NRC-2010-0062] Carolina Power & Light Company; H. B. Robinson Steam Electric Plant, Unit No. 2; Exemption 1.0 Background Carolina Power & Light... authorizes operation of the H.B. Robinson Steam Electric Plant, Unit 2 (HBRSEP). The license provides, among...

  8. 75 FR 11579 - Carolina Power & Light Company H. B. Robinson Steam Electric Plant, Unit No. 2; Exemption

    Science.gov (United States)

    2010-03-11

    ... NUCLEAR REGULATORY COMMISSION [Docket No. 50-261; NRC-2010-0062] Carolina Power & Light Company H. B. Robinson Steam Electric Plant, Unit No. 2; Exemption 1.0 Background Carolina Power & Light... of the H. B. Robinson Steam Electric Plant, Unit 2 (HBRSEP). The license provides, among other things...

  9. Draft environmental statement related to steam generator repair at H.B. Robinson Steam Electric Plant Unit No. 2, (Docket No. 50-261)

    International Nuclear Information System (INIS)

    1983-09-01

    The staff has considered the environmental impacts and economic costs of the proposed steam generator repair at the H.B. Robinson Steam Electric Plant Unit No. 2 along with reasonable alternatives to the proposed action. The staff has concluded that the proposed repair will not significantly affect the quality of the human environment and that there are no preferable alternatives to the proposed action. Furthermore, any impacts from the repair program are outweighted by its benefits

  10. Process and device for the protection of steam-raising units, particularly of nuclear reactors

    International Nuclear Information System (INIS)

    Beyer, W.; Wieling, N.; Stellwag, B.

    1986-01-01

    To protect the housing against corrosion by chemical conditioning of the feedwater, the redox potential of the feedwater and the corrosion potential of at least one pipe of the pipe bundle is continuously determined during operation of the steam raising unit. With potentials indicating the danger of corrosion, the quality of the secondary water can be improved by suitable measures. (orig./HP) [de

  11. 75 FR 8753 - Carolina Power & Light Company, Brunswick Steam Electric Plant, Units 1 and 2; Environmental...

    Science.gov (United States)

    2010-02-25

    ... Dusenbury of the North Carolina Department of Environment and Natural Resources regarding the environmental... & Light Company, Brunswick Steam Electric Plant, Units 1 and 2; Environmental Assessment and Finding of No... identification of licensing and regulatory actions requiring environmental assessments,'' the NRC prepared an...

  12. Reactor Core Internals Replacement of Ikata Units 1 and 2

    International Nuclear Information System (INIS)

    Ikeda, K.; Ishikawa, T.; Miyoshi, T.; Takagi, T.

    2012-01-01

    This paper presents an overview of the reactor core internals replacement project carried out at the Ikata Nuclear Power Station in Japan, which was the first of its kind among PWRs in the world. Failure of baffle former bolts was first reported in 1989 at Bugey 2 in France. Since then, similar incidents have been reported in Belgium and in the U.S., but not in Japan. However, the possibility of these bolts failing in Japanese plants cannot be denied in the future as operating hours increase. Ageing degradation mechanisms for the reactor core internals include irradiation-assisted stress corrosion cracking of baffle former bolts and mechanical wear of control rod guide cards. Two different approaches can be taken to address these ageing issues: to inspect and repair whenever a problem is found; and to replace the entire core internals with those of a new design having advanced features to prevent ageing degradation problems. The choice of our company was the latter. This paper explains the reasons for the choice and summarizes the replacement project activities at Ikata Units 1 and 2 as well as the improvements incorporated in the new design. (author)

  13. Burst protection device for largely cylindrical steam raising units, preferably of pressurized water nuclear power stations

    International Nuclear Information System (INIS)

    Mutzl, J.

    1978-01-01

    This burst protection device controls forces to be expected in an accident by resolving them into axial (vertical) and radial (horizontal) components, which are taken by a large number of elements stressed in tension. The steam raising unit is surrounded by a containment, but remains easily accessible. The containment consists of a steel jacket, lid and floor. Several cylindrical sections above one another form the steel jacket, which surrounds the steam raising unit with an intermediate insulating layer of concrete. The insulating concrete cylinder is of several times the thickness of the steel jacket, and also consists of cylindrical sections. An outer supporting ring for the lid and floor of the containment have outside diameters which project beyond the jacket. Prestressed circumferential vertical tension ropes between the supporting ring and floor take any additional tensional forces. The lid is domed with downward curvature towards the upper boiler dome. Internal bursting forces produce compressive stresses in the lid, which thus pass along its outside diameter into the surrounding ring. The lid, which is devided along one diameter, makes dismantling and access to the boiler easy even with a central steam pipe going upwards. The floor of the burst protection is also the floor of the steam raising unit. It is of several times the thickness of the tube floor, which, with its spacing above the floor forms the usual inlet and outlet space for the reactor cooling water. The main coolant pump installed there is driven by an external motor through a floor penetration. (HP) [de

  14. Review of the research proposal for the steam generator retired from Kori unit 1

    Energy Technology Data Exchange (ETDEWEB)

    Kim, Joung Soo; Han, Joung Ho; Kim, Hong Pyo; Lim, Yun Soo; Lee, Deok Hyun; Hwang, Seong Sik; Hur, Do Haeng [Korea Atomic Energy Research Institute, Taejeon (Korea)

    2002-03-01

    The tubes of the steam generator retired form Kori unit 1 have many different kinds of failures, such as denting pitting, wastage, ODSCC, PWSCC.Korea Electric Power Research Institute (KEPRI) submitted a research proposal for the steam generator to the Korea Institute S and T Evaluation and Planning (KSITEP). The KISTEP requested Korea Atomic Energy Research Institute to review the proposal by organizing a committee which should be composed of the specialists of the related domestic research institutes. Opinions of the committee on the objectives, research fields, economic benefit and validity in the research proposal were reviewed and suggested optimal research fields to be fulfilled successfully for the retired steam generator. Also, the rolls for the participants in the research works were allocated, which is critical in order to do the project effectively. 6 figs., 5 tabs. (Author)

  15. Effects of shutdown chemistry on steam generator radiation levels at Point Beach Unit 2. Interim report

    International Nuclear Information System (INIS)

    Kormuth, J.W.

    1982-05-01

    A refueling shutdown chemistry test was conducted at a PWR, Point Beach Unit 2. The objective was to yield reactor coolant chemistry data during the cooldown/shutdown process which might establish a relationship between shutdown chemistry and its effects on steam generator radiation fields. Of particular concern were the effects of the presence of hydrogen in the coolant as contrasted to an oxygenated coolant. Analysis of reactor coolant samples showed a rapid soluble release (spike) in Co-58, Co-60, and nickel caused by oxygenation of the coolant. The measurement of radioisotope specific activities indicates that the material undergoing dissolution during the shutdown originated from different sources which had varying histories of activation. The test program developed no data which would support theories that oxygenation of the coolant while the steam generators are full of water contributes to increased steam generator radiation levels

  16. Collision detection for the 3D planing of a steam generator replacement

    International Nuclear Information System (INIS)

    Blanc, H.V.

    1998-01-01

    The aim of this study is the design and the realisation of a planning-aided interactive computer system for the steam generators change-out, in the framework of the nuclear devices maintenance. The objective is to obtain an three dimensional simulation ergonomic tool able to detect shocks in the space. A first analysis of the virtual images construction, allows the choice of the more adapted technic to the problem. The choice of a ECSG model and graphic libraries (OPEN GL) and OPEN inventor), is justified. The various methods of the shocks detection are recalled and a fast algorithm, based on a recursive cutting of the space by merged and oriented volumes and on a fast test of these volumes interpenetration, is proposed. Finally the whole application developed by EDF is presented. This application, taking into account the graphic libraries and the more recent three dimensional tools, owns an accurate and efficiency shocks detection module. This software, equipped with an ergonomic graphic interface, allows the interactive visualisation of a three dimensional scene, the fast movement of devices and many measures of angles and distances in this scene. (A.L.B.)

  17. High-temperature steam oxidation testing of select advanced replacement alloys for potential core internals

    Energy Technology Data Exchange (ETDEWEB)

    Tan, Lizhen [Oak Ridge National Lab. (ORNL), Oak Ridge, TN (United States); Pint, Bruce A. [Oak Ridge National Lab. (ORNL), Oak Ridge, TN (United States)

    2017-05-19

    Coupons from a total of fourteen commercial and custom fabricated alloys were exposed to 1 bar full steam with ~10 ppb oxygen content at 600 and 650°C. The coupons were weighed at 500-h intervals with a total exposure time of 5,000 h. The fourteen alloys are candidate alloys selected under the ARRM program, which include three ferritic steels (Grade 92, 439, and 14YWT), three austenitic stainless steels (316L, 310, and 800), seven Ni-base superalloys (X750, 725, C22, 690, 625, 625 direct-aging, and 625- plus), and one Zr-alloy (Zr–2.5Nb). Among the alloys, 316L and X750 are served as reference alloys for low- and high-strength alloys, respectively. The candidate Ni-base superalloy 718 was procured too late to be included in the tests. The corrosion rates of the candidate alloys can be approximately interpreted by their Cr, Ni and Fe content. The corrosion rate was significantly reduced with increasing Cr content and when Ni content is above ~15 wt%, but not much further reduced when Fe content is less than ~55 wt%. Simplified thermodynamics analyses of the alloy oxidation provided reasonable indications for the constituents of oxide scales formed on the alloys and explanations for the porosity and exfoliation phenomena because of the nature of specific types of oxides.

  18. Vibration Spectrum Analysis for Indicating Damage on Turbine and Steam Generator Amurang Unit 1

    Directory of Open Access Journals (Sweden)

    Beny Cahyono

    2017-12-01

    Full Text Available Maintenance on machines is a mandatory asset management activity to maintain asset reliability in order to reduce losses due to failure. 89% of defects have random failure mode, the proper maintenance method is predictive maintenance. Predictive maintenance object in this research is Steam Generator Amurang Unit 1, which is predictive maintenance is done through condition monitoring in the form of vibration analysis. The conducting vibration analysis on Amurang Unit 1 Steam Generator is because vibration analysis is very effective on rotating objects. Vibration analysis is predicting the damage based on the vibration spectrum, where the vibration spectrum is the result of separating time-based vibrations and simplifying them into vibrations based on their frequency domain. The transformation of time-domain-wave into frequency-domain-wave is using the application of FFT, namely AMS Machinery. The measurement of vibration value is done on turbine bearings and steam generator of Unit 1 Amurang using Turbine Supervisory Instrument and CSI 2600 instrument. The result of this research indicates that vibration spectrum from Unit 1 Amurang Power Plant indicating that there is rotating looseness, even though the vibration value does not require the Unit 1 Amurang Power Plant to stop operating (shut down. This rotating looseness, at some point, can produce some indications that similar with the unbalance. In order to avoid more severe vibrations, it is necessary to do inspection on the bearings in the Amurang Unit 1 Power Plant.

  19. Heat balance calculation and feasibility analysis for initial startup of Fuqing nuclear turbine unit with non-nuclear steam

    International Nuclear Information System (INIS)

    He Liu; Xiao Bo; Song Yumeng

    2014-01-01

    Non-nuclear steam run up compared with nuclear steam run up, can verify the design, manufacture, installation quality of the unit, at the same time shorten the follow-up duration of the entire group ready to start debugging time. In this paper, starting from the first law of thermodynamics, Analyzed Heat balance Calculation and Feasibility analysis for Initial startup of Fuqing nuclear Turbine unit with Non-nuclear steam, By the above calculation, to the system requirements and device status on the basis of technical specifications, confirmed the feasibility of Non-nuclear steam running up in theory. After the implementation of the Non-nuclear turn of Fuqing unit, confirmed the results fit with the actual process. In summary, the Initial startup of Fuqing turbine unit with Non-nuclear steam is feasible. (authors)

  20. Device for inspection and/or repair of a pipe of a steam raising unit of a nuclear power station

    International Nuclear Information System (INIS)

    Vermaat, H.P.

    1986-01-01

    Eddy current sensors are introduced into the pipe from the steam raising unit chamber. The two-part device on the supporting pillar is used to support the sensors and to position them, and so is an arm connected to it via a clutch. It is accommodated inside the steam raising chamber, but can be operated remotely from outside the steam raising chamber. This reduces the radiation loading of the operating staff. (DG) [de

  1. Fast-Valving of Large Steam Turbine Units as a Means of Power System Security Enhancement

    Directory of Open Access Journals (Sweden)

    Bogdan Sobczak

    2014-03-01

    Full Text Available Fast-valving assists in maintaining system stability following a severe transmission system fault by reducing the turbine mechanical power. Fast-valving consists in rapid closing and opening of steam valves in an adequate manner to reduce the generator accelerating power following the recognition of a severe fault. FV can be an effective and economical method of meeting the performance requirements of a power system in the presence of an increase in wind and solar generation in the power system, newly connected large thermal units and delaying of building new transmission lines. The principle of fast-valving and advantages of applying this technique in large steam turbine units was presented in the paper. Effectiveness of fast-valving in enhancing the stability of the Polish Power Grid was analyzed. The feasibility study of fast-valving application in the 560 MW unit in Kozienice Power Station (EW SA was discussed.

  2. Three steam generator replacement projects in 1995: Consortium Siemens Framatome is well prepared to contribute its experience to the SGR at the Krsko NPP

    International Nuclear Information System (INIS)

    Holz, R.; Clavier, G.

    1996-01-01

    Since the companies Siemens AG and Framatome S.A. joined their experience and efforts in the field of steam generators replacements and formed a consortium in 1991, the following projects were performed in 1995: Ringhals 3, Tihange 3 and Asco 2. Further projects will follow in 1996, i.e., Doel 4 and Asco 2. Currently, this European consortium is bidding for the contract to replace the steam generators at the Krsko NPP and hopes to be awarded in 1996. An overview of the way the Consortium Siemens and Framatome approaches SG replacement projects is given based on the projects performed in 1995. Various aspects of project planning, management, licensing, personnel qualification and techniques used on site will be discussed. (author)

  3. Safety evaluation report related to steam generator repair at H.B. Robinson Steam Electric Plant, Unit No. 2. Docket No. 50-261

    International Nuclear Information System (INIS)

    1983-11-01

    A Safety Evaluation Report was prepared for the H.B. Robinson Steam Electric Plant Unit No. 2 by the Office of Nuclear Reactor Regulation. This report considers the safety aspects of the proposed steam generator repair at H.B. Robinson Steam Electric Plant Unit No. 2. The report focuses on the occupational radiation exposure associated with the proposed repair program. It concludes that there is reasonable assurance that the health and safety on the public will not be endangered by the conduct of the proposed action, such activities will be conducted in compliance with the Commission's regulations, and the issuance of this amendment will not be inimical to the common defense and security or the health and safety of the public

  4. Technical Specifications, Comanche Peak Steam Electric Station, Unit 1 (Docket No. 50-445)

    International Nuclear Information System (INIS)

    1990-04-01

    The Technical Specifications for Comanche Peak Steam Electric Station, Unit 1 were prepared by the US Nuclear Regulatory Commission. They set forth the limits, operating conditions, and other requirements applicable to a nuclear reactor facility, as set forth in Section 50.36 of Title 10 of the Code of Federal Regulations Part 50, for the protection of the health and safety of the public

  5. The detection, causes and repair of the small steam leaks in the PFR evaporator units

    International Nuclear Information System (INIS)

    Smedley, J.A.; Broomfield, A.M.; Anderson, R.

    1984-01-01

    The occurrence of a number of small steam leaks into the gas space above the sodium in the evaporator units of the UKAEA's Prototype Fast Reactor at Dounreay has had a significant impact on plant availability. The paper describes experience with the leak detection system and the phenomena which have caused the leaks and an outline is given of the measures which have been introduced to remedy the problem. (author)

  6. Manufacture of steam generator units and components for the AGR power stations at Heysham II and Torness

    Energy Technology Data Exchange (ETDEWEB)

    Glasgow, J R; Parkin, K [N.E.I. Nuclear Systems Ltd., Gateshead, Tyne and Wear (United Kingdom)

    1984-07-01

    The current AGR Steam Generator is a development of the successful once-through units supplied for the Oldbury Magnox and Hinkley B/Hunterston B AGR power stations. In this paper a brief outline of the evolution of the steam generator design from the earlier gas cooled reactor stations is presented. A description of the main items of fabrication development is given. The production facilities for the manufacture of the units are described. Reference is also made to some of the work on associated components. The early experience on the construction site of installation of the steam generators is briefly outlined. (author)

  7. Manufacture of steam generator units and components for the AGR power stations at Heysham II and Torness

    International Nuclear Information System (INIS)

    Glasgow, J.R.; Parkin, K.

    1984-01-01

    The current AGR Steam Generator is a development of the successful once-through units supplied for the Oldbury Magnox and Hinkley B/Hunterston B AGR power stations. In this paper a brief outline of the evolution of the steam generator design from the earlier gas cooled reactor stations is presented. A description of the main items of fabrication development is given. The production facilities for the manufacture of the units are described. Reference is also made to some of the work on associated components. The early experience on the construction site of installation of the steam generators is briefly outlined. (author)

  8. MHD repowering of a 250 MWe unit of the TVA Allen Steam Plant

    International Nuclear Information System (INIS)

    Chapman, J.N.; Attig, R.C.

    1992-01-01

    In this paper coal fired MHD repowering is considered for the TVA Allen Steam Plant. The performance of the repowered plant is presented. Cost comparisons are made of the cost of repowering with MHD versus the cost of meeting similar standards by installing scrubbers and selective catalytic NO x reduction (SCNR). For repowering of a single 250 MW e unit, the costs favor scrubbing and SCNR. If one considers a single repowering of all three 250 MW e units by a single MHD topping cycle and boiler, MHD repowering is more economical. Environmental emissions from the repowered plant are estimated

  9. Characterization and dissolution studies of Bruce Unit 3 steam generator secondary side deposits

    International Nuclear Information System (INIS)

    Semmler, J.

    1998-01-01

    The physical and chemical properties of secondary side steam generator deposits in the form of powder and flake obtained from Bruce Nuclear Generating Station A (BNGS A) Unit 3 were studied. The chemical phases present in both types of deposits, collected prior to the 1994 chemical cleaning during the pre-clean water lancing campaign, were magnetite (Fe 3 O 4 ), metallic copper (Cu), hematite (Fe 2 O 3 ) and cuprous oxide (Cu 2 O). The major difference between the chemical composition of the powder and the flake was the presence of zinc silicate (Zn 2 SiO 4 ) and several unidentified silicate phases containing Ca, Al, Mn, and Mg in the flake. The flake deposit had high hardness values, high electrical resistivity, low porosity and a lower dissolution rate in the EPRI-SGOG (Electric Power Research Institute-Steam Generator Owner's Group) chemical cleaning solvents compared to the powder deposit. Differences in the deposit properties after chemical cleaning of the Unit 3 steam generators and after laboratory cleaning were noted. The presence of silicates in the deposit inhibit magnetite dissolution

  10. Corrosion products behavior and source term reduction : guidelines and feedback for EDF PWRs, concerning the B/Li coordinations and steam generators replacement

    International Nuclear Information System (INIS)

    Taunier, S.; Wintergerst, M.; De Bouvier, O.; Pokor, C.; Carrette, F.; Toivonen, A.; Ranchoux, G.; Bretelle, J.L.

    2010-01-01

    The release of corrosion products by the various components of the primary system into the cooling water may induce some issues on reactor control and on radiation dose rates. Heavy crud deposits may occur on the fuel clad surface and lead to axial offset anomalies (AOA) and in extreme cases, to fuel failures. This deposition phenomenon is apparently associated with steam generator (SG) materials, water chemistry, thermal hydraulics, fuel cleaning or reactor operation history. Moreover, under intense neutron flux, these corrosion products are activated and their dissolution and deposition in the primary system may further increase the out-of-core radioactive contamination and result in radiation dose rates. Several ways are available to reduce the amount and transportation of corrosion products in the primary coolant. A first approach is related to the materials used in the primary system. As one of the main contributors to the release of corrosion products, the Ni-alloy used for the steam generators (SG) tubes has to be properly selected, manufactured and 'passivated'. The paper presents the recent feedback regarding the primary coolant chemistry and radiochemistry after Steam Generators Replacements (SGR). The modified startup procedure of the plant after SGR is also described, as well as its potential benefits on the primary coolant behavior. A second approach is to optimize the primary water chemistry to reduce the release and the transport of the corrosion products through the pH control. This kind of control is important, since higher fuel enrichments are currently used in our reactors, in order to get longer production cycles through higher burn-ups. To ensure the core reactivity control in the PWRs, the concentration of boric acid is increased in the primary water at the beginning of cycle (BOC). As a consequence, the resulting lower pH can induce a higher release of corrosion products from the steam generators. That is why, to keep an almost

  11. C30 Support Plate for Replacing Function of Service Pool 1 at Unit 2

    International Nuclear Information System (INIS)

    Zsoldos, F.

    2006-01-01

    Paks NPP had a serious event at Unit 2 in April 2003. This event was connected to Service Pool 1, there was a cleaning tank int he pool to clean the fuel assemblies from sediments. The sediment problem has occurred at three of our four units, the cause of this problem was the decontamination of the steam generators. We have not made any decontamination at Unit 4 only, and there is no any problem at Unit 4 at all. The plant tried out the mentioned cleaning method at Unit 2 first time, and the event happened at that time. Because of the event the function of Service Pool 1 was not available, the damaged fuel and the cleaning tank is in the pool at this moment. We got the permission from the authority body to operate again Unit 2. This operation, the planned campaign was a short one because of the limited possibility to set up a proper core from the fuel assemblies what were available. Because of the short campaign we had to prepare a proper solution to accomplish the refuelling at Unit 2. The main obstacle was the unavailable functionality of Service Pool 1 which used to carry in fresh fuel and carry out the spent fuel with usage of C30 casks (we have two C30 casks, as it shown in their names the casks can contain 30 fuel assemblies, fresh or spent fuel depending on the given activity have to be done). The plant started to find out what would be the proper solution to replace the function of Service Pool 1 and the C30 support plate was found out as the possible solution to this problem. This C30 support plate is ready to launch the C30 casks or containers with the fresh or spent fuel into the reactor. It means that this C30 support plate is adjusted to the reactor main surface and in this way it ready to serve replacing Service Pool 1. Of course the reactor is empty during the preparation phase of the refuelling. First we carry out the spent fuel from the spent fuel pool, after that the fresh fuel is carried in and just after these preparing activities can be started

  12. ANALISIS KEJADIAN STEAM GENERATOR TUBE RUPTURE (SGTR BERDASARKAN SKENARIO MIHAMA UNIT 2

    Directory of Open Access Journals (Sweden)

    Andi Sofrany Ekariansyah

    2015-03-01

    Full Text Available Pada tanggal 9 Februari 1991, terjadi kecelakaan putusnya pipa pemanas pembangkit uap (Steam Generator Tube Rupture/SGTR pada PLTN Mihama Unit 2. Dari kejadian tersebut, diperoleh catatan sekuensi kecelakaan berupa aktuasi sistem proteksi dan fitur keselamatan terekayasa dalam memitigasi kebocoran dari sistem primer ke sistem sekunder. Urutan sekuensi tersebut kemudian diterapkan pada PWR standar Jepang untuk disimulasikan menggunakan program perhitungan RELAP5/SCDAP/Mod3.2. Tujuannya untuk mengevaluasi konsekuensi yang terjadi bila kecelakaan tersebut terjadi pada PWR standar Jepang. Parameter yang dibandingkan adalah laju alir kebocoran, perubahan tekanan primer dan sekunder dan perubahan level di dalam pressurizer. Hasil simulasi menunjukkan perbedaan lama waktu kejadian SGTR hingga berhentinya kebocoran yang berlangsung lebih pendek pada PWR standar Jepang. Selain itu jumlah pendingin primer yang bocor dan jumlah uap yang terlepas dari MSRV tercatat lebih besar daripada PWR Mihama unit 2. Karakter aliran kebocoran, fluktuasi tekanan primer, dan level pressurizer sedikit berbeda pada tahap-tahap awal kejadian, namun relatif sama pada tahap akhir ketika aliran kebocoran dapat dihentikan. Hasil simulasi juga menunjukkan perlunya tindakan operator secara manual yang ditunjukkan dari isolasi sistem air umpan bantu (AFW pada pembangkit uap yang bocor, aktuasi katup pelepas uap (MSRV pada pembangkit uap yang utuh dan aktuasi auxiliary spray dan power operated relief valve (PORV pada pressurizer untuk mengantisipasi kejadian sebagai bagian dari prosedur operasi darurat. Kata kunci: SGTR, PWR Mihama Unit 2, PWR standar Jepang   On February 9,1991, a Steam Generator Tube Rupture (SGTR took place at the Mihama Unit No. 2. From that event, the accident sequence representing the actuation of protection system and engineered safety feature to mitigate the leak from primary system to secondary system is recorded. That sequence is then applied on the

  13. Equipment for inspection and carrying out repairs, if required, for tube bundles of steam raising units

    International Nuclear Information System (INIS)

    Gugel, G.

    1976-01-01

    The equipment solves the problem of being able to inspect and possibly to repair U-tubes of a vertical steam raising unit standing on a tube floor, without draining the primary medium and bringing the test equipment and tools into the inside of the boiler first. This is achieved by leaving a considerable part of the equipment permanently in the hemispherical space under the tube floor and operating it from the outside, on the other side of the concrete shielding. An inspection tube is threaded in turn horizontally through a concrete shield, a tube duct in the heat insulation of the steam raising unit, and through a hole in the hemispherical space under the tube floor into this space. The end of an angle tube can be moved axially from outside the concrete shield and can be rotated in a semicircle above the tube axis. By interposing a, for example, 12 part distributor with 12 short, differently bent tubes 12 adjacent tubes opening into the tube floor can be controlled and tested, by axial movement of the angle tube together with the distributor, e.g. 4 x 12 other U tubes. A turbulent flow sensor, for example, can be introduced through the angle tube and distributor. In the non-operational condition the equipment is moved into a recess via a supporting angle and stopped there. (ORU) [de

  14. Replacement

    Directory of Open Access Journals (Sweden)

    S. Radhakrishnan

    2014-03-01

    Full Text Available The fishmeal replaced with Spirulina platensis, Chlorella vulgaris and Azolla pinnata and the formulated diet fed to Macrobrachium rosenbergii postlarvae to assess the enhancement ability of non-enzymatic antioxidants (vitamin C and E, enzymatic antioxidants (superoxide dismutase (SOD and catalase (CAT and lipid peroxidation (LPx were analysed. In the present study, the S. platensis, C. vulgaris and A. pinnata inclusion diet fed groups had significant (P < 0.05 improvement in the levels of vitamins C and E in the hepatopancreas and muscle tissue. Among all the diets, the replacement materials in 50% incorporated feed fed groups showed better performance when compared with the control group in non-enzymatic antioxidant activity. The 50% fishmeal replacement (best performance diet fed groups taken for enzymatic antioxidant study, in SOD, CAT and LPx showed no significant increases when compared with the control group. Hence, the present results revealed that the formulated feed enhanced the vitamins C and E, the result of decreased level of enzymatic antioxidants (SOD, CAT and LPx revealed that these feeds are non-toxic and do not produce any stress to postlarvae. These ingredients can be used as an alternative protein source for sustainable Macrobrachium culture.

  15. In-core monitor housing replacement at Fukushima Daiichi Unit No.4

    International Nuclear Information System (INIS)

    Arai, Tomoyuki

    1999-01-01

    The in-core monitor (ICM) housing replacement of a Boiling Water Reactor (BWR) has been completed at Fukushima-Daiichi Unit No. 4 (1F4) of the Tokyo Electric Power Company (TEPCO) in Japan. Since cracking of the inside surface of an ICM housing was found in this unit, the ICM housing was replaced with one made of low-carbon stainless steel (SS) to improve Intergranular Stress Corrosion Cracking (IGSCC) resistance. This project is the first application of the replacement procedure for the ICM housing and employs various advanced technologies. The outline of the ICM housing replacement project and applied technologies are discussed in this paper. (author)

  16. Steam Generator Lancing and FOSAR for HANUL Nuclear Power Plant Unit 2

    Energy Technology Data Exchange (ETDEWEB)

    Jeong, Woo-Tae [Korea Hydro and Nuclear Power Co. Ltd. Central Research Institute, Daejeon (Korea, Republic of); Kim, Sang-Tae; Yoon, Sang-Jung; Seo, Hong-Chang [Sae-An Engineering Corporation, Seoul (Korea, Republic of)

    2015-05-15

    Sludge weight removed during the deposit removal operation was 10.68 kg. Annulus, tubelane, and in-bundle area of the steam generators were searched for possible foreign objects. Three foreign objects were found and removed. Mock-up training before the operation was helpful to finish the service as scheduled. Sludge lancing and FOSAR were Sludge lancing and FOSAR were successfully completed for Hanul nuclear power plant unit 2 during the 19''t''h outage. Mock-up training before the service was helpful for the operators to finish the job on time. Inspection, barrel spray, final barrel/flushing, and sludge collector cleaning was completed for the three steam generators 'A', 'B', and 'C.' Six bag filters and 42 cartridge filters were consumed to remove 10.68 kg of sludge. Three foreign objects were found and removed. One foreign object (HU2R19SGB01) was found in SG 'B', and two objects (HU2R19SGC01, HU2R19SGC02) were found in SG 'C.'.

  17. Upgrading the SPP-500-1 moisture separators-steam reheaters used in the Leningrad NPP turbine units

    Science.gov (United States)

    Legkostupova, V. V.; Sudakov, A. V.

    2015-03-01

    The specific features of existing designs of moisture separators-steam reheaters (MSRs) and experience gained with using them at nuclear power plants are considered. Main factors causing damage to and failures of MSRs are described: nonuniform distribution of wet steam flow among the separation modules, breakthrough of moisture through the separator (and sometimes also through the steam reheater), which may lead to the occurrence of additional thermal stresses and, hence, to thermal-fatigue damage to or stress corrosion cracking of metal. MSR failure results in a less efficient operation of the turbine unit as a whole and have an adverse effect on the reliability of the low-pressure cylinder's last-stage blades. By the time the design service life of the SPP-500-1 MSRs had been exhausted in power units equipped with RBMK-1000 reactors, the number of damages inflicted to both the separation part and to the pipework and heating surface tubes was so large, that a considerable drop of MSR effectiveness and turbine unit efficiency as a whole occurred. The design of the upgraded separation part used in the SPP-500-1 MSR at the Leningrad NPP is described and its effectiveness is shown, which was confirmed by tests. First, efforts taken to achieve more uniform distribution of moisture content over the perimeter and height of steam space downstream of the separation modules and to bring it to values close to the design ones were met with success. Second, no noticeable effect of the individual specific features of separation modules on the moisture content was revealed. Recommendations on elaborating advanced designs of moisture separators-steam reheaters are given: an MSR arrangement in which the separator is placed under or on the side from the steam reheater; axial admission of wet steam for ensuring its uniform distribution among the separation modules; inlet chambers with an extended preliminary separation system and devices for uniformly distributing steam flows in the

  18. Optimal selection of Orbital Replacement Unit on-orbit spares - A Space Station system availability model

    Science.gov (United States)

    Schwaab, Douglas G.

    1991-01-01

    A mathematical programing model is presented to optimize the selection of Orbital Replacement Unit on-orbit spares for the Space Station. The model maximizes system availability under the constraints of logistics resupply-cargo weight and volume allocations.

  19. 76 FR 77022 - In the Matter of Carolina Power & Light Company, H.B. Robinson Steam Electric Plant, Unit No. 2...

    Science.gov (United States)

    2011-12-09

    ... and 72-3] In the Matter of Carolina Power & Light Company, H.B. Robinson Steam Electric Plant, Unit No. 2, H. B. Robinson Steam Electric Plant, Unit 2, Independent Spent Fuel Storage Installation; Order Approving Indirect Transfer of Control of Licenses I. Carolina Power & Light Company (CP&L, the licensee) is...

  20. Radiation control in the core shroud replacement project of Fukushima-Daiichi NPS Unit no.2

    International Nuclear Information System (INIS)

    Kokubun, Yasunori; Haraguchi, Kazuyuki; Yoshizawa, Yuji; Yamada, Yasuo

    2000-01-01

    In Fukushima-Daiichi NPS Unit no.2, the core shroud replacement was made following that of Unit no.3. This project involves replacement of wide-ranging equipment, with the project extending over a long period of time. This was expected to increase the dose equivalent of workers. Accordingly, various measures to lower the dose equivalent were planned and implemented. We outline radiation controls implemented during the project period. The shroud replacement project was a preventive maintenance project which consisted of replacing the core shroud and other internals with those less susceptible to stress corrosion cracking. Problems related to radiation control during the replacement project of Unit no.3 the year before last were summarized. We studied, planned, and implemented measures to be reflected in the project for Unit no.2. This was done to lower the dose equivalent as much as possible while paying due attention to safety and economy. For radiation control during the project for Unit no.2, experiments with Unit no.3 were fully exploited and any effective measures taken at that time were adopted in this project. Problems pointed out after that project with Unit no.3 resulted in new or improved measures being taken with Unit no.2. Measures taken over from the project with Unit no.3; a. Daily analysis of difference between expected and actual dose equivalents b. Dose reduction measures, chemical decontamination, temporary shield, flushing, etc.; New or improved measures; a. Dose reduction measures: Mechanical removal of radiation sources, strengthening of shield, etc.; b. Automatic remote control system; c. Use of new protective devices. With measures implemented as described above, the dose equivalent during shroud replacement of Unit no.2 was reduced by about 30% when compared with that (11.5 persons · Sv) in the case of Unit no.3. Implemented radiation controls will be checked and reviewed in future for reflection in projects with other units. (author)

  1. 76 FR 66333 - Carolina Power & Light Company, H.B. Robinson Steam Electric Plant, Unit No. 2; Environmental...

    Science.gov (United States)

    2011-10-26

    ... NUCLEAR REGULATORY COMMISSION [Docket No. 50-261; NRC-2011-0247] Carolina Power & Light Company, H.B. Robinson Steam Electric Plant, Unit No. 2; Environmental Assessment and Finding of No Significant... Facility Operating License No. DPR-23, issued to Carolina Power & Light Company (the licensee), for...

  2. Inducement of IGA/SCC in Inconel 600 steam generator tubing during unit outages

    Energy Technology Data Exchange (ETDEWEB)

    Durance, D.; Sedman, K. [Bruce Power, Tiverton, Ontario (Canada); Roberts, J. [CANTECH Associates Ltd., Burlington, Ontario (Canada); King, P. [Babcock and Wilcox Canada, Cambridge, Ontario (Canada); Gorman, J. [Dominion Engineering, Reston, VA (United States); Allen, R. [Kinectrics, Inc., Toronto, Ontario (Canada)

    2008-07-01

    The degradation of Unit 4 SG tubing by IGA/SCC has limited both the operating period and end of life predictions for Unit 4 since restart in late 2003. The circumferential IGA/SCC has been most significant in SG4 with substantial increases in both initiation and growth rates from 2005 through the spring of 2007. A detailed review of the occurrence of circumferential OD IGA/SCC at the RTZ in the HL TTS region of Bruce 4 steam generator tubes has led a conclusion that it is probable that the IGA/SCC has been the result of attack by partially reduced sulfur species such as tetrathionates and thiosulfates during periods of low temperature exposure. It is believed that attack of this type has mostly likely occurred during startup evolutions following outages as the result the development of aggressive reduced sulfur species in the TTS region during periods when the boilers were fully drained for maintenance activities. The modification of outage practices to limit secondary side oxygen ingress in the spring of 2007 has apparently arrested the degradation and has had significant affects on the allowable operating interval and end of life predictions for the entire unit. (author)

  3. Inducement of IGA/SCC in Inconel 600 steam generator tubing during unit outages

    International Nuclear Information System (INIS)

    Durance, D.; Sedman, K.; Roberts, J.; King, P.; Gorman, J.; Allen, R.

    2008-01-01

    The degradation of Unit 4 SG tubing by IGA/SCC has limited both the operating period and end of life predictions for Unit 4 since restart in late 2003. The circumferential IGA/SCC has been most significant in SG4 with substantial increases in both initiation and growth rates from 2005 through the spring of 2007. A detailed review of the occurrence of circumferential OD IGA/SCC at the RTZ in the HL TTS region of Bruce 4 steam generator tubes has led a conclusion that it is probable that the IGA/SCC has been the result of attack by partially reduced sulfur species such as tetrathionates and thiosulfates during periods of low temperature exposure. It is believed that attack of this type has mostly likely occurred during startup evolutions following outages as the result the development of aggressive reduced sulfur species in the TTS region during periods when the boilers were fully drained for maintenance activities. The modification of outage practices to limit secondary side oxygen ingress in the spring of 2007 has apparently arrested the degradation and has had significant affects on the allowable operating interval and end of life predictions for the entire unit. (author)

  4. Telemedicine Can Replace the Neurologist on a Mobile Stroke Unit.

    Science.gov (United States)

    Wu, Tzu-Ching; Parker, Stephanie A; Jagolino, Amanda; Yamal, Jose-Miguel; Bowry, Ritvij; Thomas, Abraham; Yu, Amy; Grotta, James C

    2017-02-01

    The BEST-MSU study (Benefits of Stroke Treatment Delivered Using a Mobile Stroke Unit) is a comparative effectiveness trial in patients randomized to mobile stroke unit or standard management. A substudy tested interrater agreement for tissue-type plasminogen activator eligibility between a telemedicine vascular neurologist and onboard vascular neurologist. On scene, both the telemedicine vascular neurologist and onboard vascular neurologist independently evaluated the patient, documenting their tissue-type plasminogen activator treatment decision, National Institutes of Health Stroke Scale score, and computed tomographic interpretation. Agreement was determined using Cohen κ statistic. Telemedicine-related technical failures that impeded remote assessment were recorded. Simultaneous and independent telemedicine vascular neurologist and onboard vascular neurologist assessment was attempted in 174 patients. In 4 patients (2%), the telemedicine vascular neurologist could not make a decision because of technical problems. The telemedicine vascular neurologist agreed with the onboard vascular neurologist on 88% of evaluations (κ=0.73). Remote telemedicine vascular neurologist assessment is reliable and accurate, supporting either telemedicine vascular neurologist or onboard vascular neurologist assessment on our mobile stroke unit. URL: http://www.clinicaltrials.gov. Unique identifier: NCT02190500. © 2017 American Heart Association, Inc.

  5. Results of Steam-Water-Oxygen Treatment of the Inside of Heating Surfaces in Heat-Recovery Steam Generators of the PGU-800 Power Unit at the Perm' District Thermal Power Station

    Science.gov (United States)

    Ovechkina, O. V.; Zhuravlev, L. S.; Drozdov, A. A.; Solomeina, S. V.

    2018-05-01

    Prestarting, postinstallation steam-water-oxygen treatment (SWOT) of the natural circulation/steam reheat heat-recovery steam generators (HRSG) manufactured by OAO Krasny Kotelshchik was performed at the PGU-800 power unit of the Perm District Thermal Power Station (GRES). Prior to SWOT, steam-oxygen cleaning, passivation, and preservation of gas condensate heaters (GCH) of HRSGs were performed for 10 h using 1.3MPa/260°C/70 t/h external steam. After that, test specimens were cut out that demonstrated high strength of the passivating film. SWOT of the inside of the heating surfaces was carried out during no-load operation of the gas turbine unit with an exhaust temperature of 280-300°C at the HRSG inlet. The steam turbine was shutdown, and the generated steam was discharged into the atmosphere. Oxygen was metered into the discharge pipeline of the electricity-driven feed pumps and downcomers of the evaporators. The behavior of the concentration by weight of iron compounds and the results of investigation of cutout specimens by the drop or potentiometric method indicate that the steam-water-oxygen process makes it possible to remove corrosion products and reduce the time required to put a boiler into operation. Unlike other processes, SWOT does not require metal-intensive cleaning systems, temporary metering stations, and structures for collection of the waste solution.

  6. Acceptance test procedure for SY Tank Farm replacement exhauster unit

    Energy Technology Data Exchange (ETDEWEB)

    Becken, G.W.

    1994-12-16

    The proper functioning of a new 241-SY Tank Farm replacement exhauster will be acceptance tested, to establish operability and to provide an operational baseline for the equipment. During this test, a verification of all of the alarm and control circuits associated with the exhaust, which provide operating controls and/or signals to local and remote alarm/annunciator panels, shall be performed. Test signals for sensors that provide alarms, warnings, and/or interlocks will be applied to verify that alarm, warning, and interlock setpoints are correct. Alarm and warning lights, controls, and local and remote readouts for the exhauster will be verified to be adequate for proper operation of the exhauster. Testing per this procedure shall be conducted in two phases. The first phase of testing, to verify alarm, warning, and interlock setpoints primarily, will be performed in the MO-566 Fab Shop. The second phase of testing, to verify proper operation and acceptable interface with other tank farm systems, will be conducted after the exhauster and all associated support and monitoring equipment have been installed in the SY Tank Farm. The exhauster, which is mounted on a skid and which will eventually be located in the SY tank farm, receives input signals from a variety of sensors mounted on the skid and associated equipment. These sensors provide information such as: exhauster system inlet vacuum pressure; prefilter and HEPA filter differential pressures; exhaust stack sampler status; exhaust fan status; system status (running/shut down); and radiation monitoring systems status. The output of these sensors is transmitted to the exhauster annunciator panel where the signals are displayed and monitored for out-of-specification conditions.

  7. Impact of flow induced vibration acoustic loads on the design of the Laguna Verde Unit 2 steam dryer

    International Nuclear Information System (INIS)

    Forsyth, D. R.; Wellstein, L. F.; Theuret, R. C.; Han, Y.; Rajakumar, C.; Amador C, C.; Sosa F, W.

    2015-09-01

    Industry experience with Boiling Water Reactors (BWRs) has shown that increasing the steam flow through the main steam lines (MSLs) to implement an extended power up rate (EPU) may lead to amplified acoustic loads on the steam dryer, which may negatively affect the structural integrity of the component. The source of these acoustic loads has been found to be acoustic resonance of the side branches on the MSLs, specifically, coupling of the vortex shedding frequency and natural acoustic frequency of safety relief valves (SRVs). The resonance that results from this coupling can contribute significant acoustic energy into the MSL system, which may propagate upstream into the reactor pressure vessel steam dome and drive structural vibration of steam dryer components. This can lead to high-cycle fatigue issues. Lock-in between the vortex shedding frequency and SRV natural frequency, as well as the ability for acoustic energy to propagate into the MSL system, are a function of many things, including the plant operating conditions, geometry of the MSL/SRV junction, and placement of SRVs with respect to each other on the MSLs. Comision Federal de Electricidad and Westinghouse designed, fabricated, and installed acoustic side branches (ASBs) on the MSLs which effectively act in the system as an energy absorber, where the acoustic standing wave generated in the side-branch is absorbed and dissipated inside the ASB. These ASBs have been very successful in reducing the amount of acoustic energy which propagates into the steam dome. In addition, modifications to the Laguna Verde Nuclear Power Plant Unit 2 steam dryer have been completed to reduce the stress levels in critical locations in the dryer. The objective of this paper is to describe the acoustic side branch concept and the design iterative processes that were undertaken at Laguna Verde Unit 2 to achieve a steam dryer design that meets the guidelines of the American Society of Mechanical Engineers, Boiler and Pressure

  8. Impact of flow induced vibration acoustic loads on the design of the Laguna Verde Unit 2 steam dryer

    Energy Technology Data Exchange (ETDEWEB)

    Forsyth, D. R.; Wellstein, L. F.; Theuret, R. C.; Han, Y.; Rajakumar, C. [Westinghouse Electric Company LLC, Cranberry Township, PA 16066 (United States); Amador C, C.; Sosa F, W., E-mail: forsytdr@westinghouse.com [Comision Federal de Electricidad, Central Nucleoelectrica Laguna Verde, Km 42.5 Carretera Cardel-Nautla, 91680 Alto Lucero, Veracruz (Mexico)

    2015-09-15

    Industry experience with Boiling Water Reactors (BWRs) has shown that increasing the steam flow through the main steam lines (MSLs) to implement an extended power up rate (EPU) may lead to amplified acoustic loads on the steam dryer, which may negatively affect the structural integrity of the component. The source of these acoustic loads has been found to be acoustic resonance of the side branches on the MSLs, specifically, coupling of the vortex shedding frequency and natural acoustic frequency of safety relief valves (SRVs). The resonance that results from this coupling can contribute significant acoustic energy into the MSL system, which may propagate upstream into the reactor pressure vessel steam dome and drive structural vibration of steam dryer components. This can lead to high-cycle fatigue issues. Lock-in between the vortex shedding frequency and SRV natural frequency, as well as the ability for acoustic energy to propagate into the MSL system, are a function of many things, including the plant operating conditions, geometry of the MSL/SRV junction, and placement of SRVs with respect to each other on the MSLs. Comision Federal de Electricidad and Westinghouse designed, fabricated, and installed acoustic side branches (ASBs) on the MSLs which effectively act in the system as an energy absorber, where the acoustic standing wave generated in the side-branch is absorbed and dissipated inside the ASB. These ASBs have been very successful in reducing the amount of acoustic energy which propagates into the steam dome. In addition, modifications to the Laguna Verde Nuclear Power Plant Unit 2 steam dryer have been completed to reduce the stress levels in critical locations in the dryer. The objective of this paper is to describe the acoustic side branch concept and the design iterative processes that were undertaken at Laguna Verde Unit 2 to achieve a steam dryer design that meets the guidelines of the American Society of Mechanical Engineers, Boiler and Pressure

  9. An Isothermal Steam Expander for an Industrial Steam Supplying System

    Directory of Open Access Journals (Sweden)

    Chen-Kuang Lin

    2015-01-01

    Full Text Available Steam is an essential medium used in the industrial process. To ensure steam quality, small and middle scale boilers are often adopted. However, because a higher steam pressure (compared to the necessary steam pressure is generated, the boiler’s steam pressure will be reduced via a pressure regulator before the steam is directed through the process. Unfortunately, pressure is somewhat wasted during the reducing process. Therefore, in order to promote energy efficiency, a pressure regulator is replaced by a steam expander. With this steam expander, the pressure will be transformed into mechanical energy and extracted during the expansion process. A new type of isothermal steam expander for an industrial steam supplying system will be presented in the paper. The isothermal steam expander will improve the energy efficiency of a traditional steam expander by replacing the isentropic process with an isothermal expansion process. With this, steam condensation will decrease, energy will increase, and steam quality will be improved. Moreover, the mathematical model of the isothermal steam expander will be established by using the Schmidt theory, the same principle used to analyze Stirling engines. Consequently, by verifying the correctness of the theoretical model for the isothermal steam expander using experimental data, a prototype of 100 c.c. isothermal steam expander is constructed.

  10. Effectiveness of a steam cleaning unit for disinfection in a veterinary hospital.

    Science.gov (United States)

    Wood, Cheryl L; Tanner, Benjamin D; Higgins, Laura A; Dennis, Jeffrey S; Luempert, Louis G

    2014-12-01

    To evaluate whether the application of steam to a variety of surface types in a veterinary hospital would effectively reduce the number of bacteria. 5 surface types. Steam was applied as a surface treatment for disinfection to 18 test sites of 5 surface types in a veterinary hospital. A pretreatment sample was obtained by collection of a swab specimen from the left side of each defined test surface. Steam disinfection was performed on the right side of each test surface, and a posttreatment sample was then collected in the same manner from the treated (right) side of each test surface. Total bacteria for pretreatment and posttreatment samples were quantified by heterotrophic plate counts and for Staphylococcus aureus, Pseudomonas spp, and total coliforms by counts on selective media. Significant reductions were observed in heterotrophic plate counts after steam application to dog runs and dog kennel floors. A significant reduction in counts of Pseudomonas spp was observed after steam application to tub sinks. Bacterial counts were reduced, but not significantly, on most other test surfaces that had adequate pretreatment counts for quantification. Development of health-care-associated infections is of increasing concern in human and veterinary medicine. The application of steam significantly reduced bacterial numbers on a variety of surfaces within a veterinary facility. Steam disinfection may prove to be an alternative or adjunct to chemical disinfection within veterinary practices.

  11. Pressure tube replacement in Pickering NGS A units 1 and 2

    International Nuclear Information System (INIS)

    Irvine, H.S.; Bennett, E.J.; Talbot, K.H.

    1986-10-01

    Being able to technically and economically replace the most radioactive components (excluding the nuclear fuel) in operating reactors will help to ensure the ongoing acceptance of nuclear power as a viable energy source for the future. Ontario Hydro is well along the path to meeting the above objective for its CANDU-PHW reactors. Following the failure of a Zircaloy-II pressure tube in unit 2 of Pickering NGS A in August, 1983, Ontario Hydro has embarked on a program to replace all Zircaloy-II pressure tubes in units 1 and 2 at Pickering. This program integrates the in-house research, design, construction, and operating skills of a large utility (Ontario Hydro) with the skills of a national nuclear organization (Atomic Energy of Canada Limited) and the private engineering sector of the Canadian nuclear industry. The paper describes the background to the pressure tube failure in Pickering unit 2 and to the efforts incurred in understanding the failure mechanism and how similar failures are not expected for the zirconium-niobium pressure tube material used in all other large CANDU-PHW units after units 1 and 2 of Pickering NGS A. The tooling developed for the pressure tube replacement program is described as well as the organization to undertake the program in an operating nuclear station. The retubing of units 1 and 2 at Pickering NGS A is nearing a successful completion and shows the benefits of being able to integrate the various skills required for this success. Pressure tube replacement in a CANDU-PHW reactor is equivalent to replacement of the reactor vessel in a LWR. The fact that this replacement can be done economically and with acceptable radiation dose to workers augurs well for the continued viability of the use of nuclear energy for the benefit of mankind. (author)

  12. Prevalence of Total Hip and Knee Replacement in the United States.

    Science.gov (United States)

    Maradit Kremers, Hilal; Larson, Dirk R; Crowson, Cynthia S; Kremers, Walter K; Washington, Raynard E; Steiner, Claudia A; Jiranek, William A; Berry, Daniel J

    2015-09-02

    Descriptive epidemiology of total joint replacement procedures is limited to annual procedure volumes (incidence). The prevalence of the growing number of individuals living with a total hip or total knee replacement is currently unknown. Our objective was to estimate the prevalence of total hip and total knee replacement in the United States. Prevalence was estimated using the counting method by combining historical incidence data from the National Hospital Discharge Survey and the Healthcare Cost and Utilization Project (HCUP) State Inpatient Databases from 1969 to 2010 with general population census and mortality counts. We accounted for relative differences in mortality rates between those who have had total hip or knee replacement and the general population. The 2010 prevalence of total hip and total knee replacement in the total U.S. population was 0.83% and 1.52%, respectively. Prevalence was higher among women than among men and increased with age, reaching 5.26% for total hip replacement and 10.38% for total knee replacement at eighty years. These estimates corresponded to 2.5 million individuals (1.4 million women and 1.1 million men) with total hip replacement and 4.7 million individuals (3.0 million women and 1.7 million men) with total knee replacement in 2010. Secular trends indicated a substantial rise in prevalence over time and a shift to younger ages. Around 7 million Americans are living with a hip or knee replacement, and consequently, in most cases, are mobile, despite advanced arthritis. These numbers underscore the substantial public health impact of total hip and knee arthroplasties. Copyright © 2015 by The Journal of Bone and Joint Surgery, Incorporated.

  13. Embedded piezoelectrics for sensing and energy harvesting in total knee replacement units

    Science.gov (United States)

    Wilson, Brooke E.; Meneghini, Michael; Anton, Steven R.

    2015-04-01

    The knee replacement is the second most common orthopedic surgical intervention in the United States, but currently only 1 in 5 knee replacement patients are satisfied with their level of pain reduction one year after surgery. It is imperative to make the process of knee replacement surgery more objective by developing a data driven approach to ligamentous balance, which increases implant life. In this work, piezoelectric materials are considered for both sensing and energy harvesting applications in total knee replacement implants. This work aims to embed piezoelectric material in the polyethylene bearing of a knee replacement unit to act as self-powered sensors that will aid in the alignment and balance of the knee replacement by providing intraoperative feedback to the surgeon. Postoperatively, the piezoelectric sensors can monitor the structural health of the implant in order to perceive potential problems before they become bothersome to the patient. Specifically, this work will present on the use of finite element modeling coupled with uniaxial compression testing to prove that piezoelectric stacks can be utilized to harvest sufficient energy to power sensors needed for this application.

  14. Some engineering aspects of the steam generator system for the United States LMFBR demonstration plant

    International Nuclear Information System (INIS)

    Tippets, F.E.

    1975-01-01

    This paper describes the main design features of the steam generator system for the Clinch River Breeder Reactor Plant and the engineering approach being employed for some of the critical elements of this system, including in particular the sodium-steam/water boundary, the efforts to have this boundary be of highest integrity, and the system features to safely accommodate any failure of the boundary. (author)

  15. Some engineering aspects of the steam generator system for the United States LMFBR demonstration plant

    Energy Technology Data Exchange (ETDEWEB)

    Tippets, F E

    1975-07-01

    This paper describes the main design features of the steam generator system for the Clinch River Breeder Reactor Plant and the engineering approach being employed for some of the critical elements of this system, including in particular the sodium-steam/water boundary, the efforts to have this boundary be of highest integrity, and the system features to safely accommodate any failure of the boundary. (author)

  16. Through wall degradation problem of the turbine extraction steam drain piping due to liquid drop impingement and measures taken for this problem at Fukushima Dai-ichi Nuclear Power Plant Unit 6

    International Nuclear Information System (INIS)

    Inagaki, Takeyuki; Kobayashi, Teruaki; Shimada, Shigeru; Inoue, Ryousuke; Usuba, Satoshi; Kimura, Takeo

    2011-01-01

    Through wall degradation was found on the extraction steam drain piping of Unit 6 of Fukushima Dai-ichi Nuclear Power Plant owned by Tokyo Electric Power Company after replacement of the turbine rotors with those of higher thermal efficiency. The mechanism of this degradation was loss of material due to liquid drop impingement. Since the estimated life time of the piping based on wall thickness measurements before the replacement was at least 9 years, the rapid wall thinning occurred after the replacement. This paper describes a summary of the phenomenon, its degradation mechanism and root cause, a temporary measurement taken for an immediate action and permanent measures taken during the next refueling outage. (author)

  17. Improving the thermodynamic efficiency of steam turbine condensers with partial tube replacement and an advanced tube bundle design

    International Nuclear Information System (INIS)

    Drosdziok, A.; Zorner, W.

    1989-01-01

    Many different problems have been experienced with power plant condensers all over the world. It has become apparent that plant availability and cost-effectiveness are significantly influenced by the thermodynamic design of the condensers and the materials selected. This paper reports that by refitting older condensers in operating plants it has proven possible to improve thermodynamic efficiency by changing the tube bundle design. In conjunction with the replacement of the cooper-bearing tubing in these condensers, which became necessary because of the introduction of high AVT (All Volatile Treatment) conditioning in the secondary circuit, it has generally been possible to fulfil the requirements imposed on the condensers without a deterioration of plant efficiency. By experience, best results have been obtained by replacing the condenser bundle with an advanced tube bundle design. Apart from solving all problems, this further improves the thermodynamic efficiency of the condensers. In nuclear power plants constructed by the Siemens KWU Group the condensers are tailored to present-day requirements

  18. Development and application of the lancing system of delta-60 steam generator-Kori nuclear power plant unit 1

    International Nuclear Information System (INIS)

    Jeong, W. T.; Han, D. Y.; Ahn, N. S.; Jo, B. H.; Hong, Y. W.

    2001-01-01

    A lancing system for removing the deposits on the tube sheet of a nuclear steam generator using high pressure water was developed and applied to Kori Nuclear Power Plant( NPP) Unit 1. As the place where the lancing system is to be installed is relatively high radioactive area, every part consisting the equipment is carefully selected to be radiation resistant. The lancing robot was designed to be water proof to aviod possible malfunction of the lancing robot because of high pressure water. To minimize radiation exposure to operators, the system was designed considering easy installation and maintenance in mind. Water ejection nozzle are designed to have high strength with special material and heat treatment so as to lessen abrasion caused by high pressure ejection. The lancing system showed good performance during the on-site lancing using the system for Delta-60 steam generator of Kori NPP No. 1 in October 2000

  19. A feasibility study on active ultrasonic techniques for water into sodium leak detection on FBR steam generator units

    International Nuclear Information System (INIS)

    Girard, J.P.; Garnaud, P.; Journeau, C.; Demarais, R.

    1990-01-01

    In the framework of the European Fast Breeder Project one of the aims is to provide the ferritic straight tube steam generator with a fast and reliable leak detection system. The first studies of water sodium leaks, based on the passive listening of noise source, are described. Considerable experience has been acquired of this technique and one of the conclusions is that a high level of reliability may require a sophisticated surveillance algorithm. Further works on the subject should lead to demonstration phase in 1993-1995 on a real and representative steam generator unit in order to have the benefit of a long term run of the surveillance method prior to industrial use in a compulsory safety system. 1 ref., 10 figs

  20. Replacement of the moderator cell unit of JRR-3's cold neutron source facility

    International Nuclear Information System (INIS)

    Hazawa, Tomoya; Nagahori, Kazuhisa; Kusunoki, Tsuyoshi

    2006-10-01

    The moderator cell of the JRR-3's cold neutron source (CNS) facility, converts thermal neutrons into cold neutrons by passing through liquid cold hydrogen. The cold neutrons are used for material and life science research such as the neutron scattering. The CNS has been operated since the start of JRR-3's in 1990. The moderator cell containing liquid hydrogen is made of stainless steel. The material irradiation lifetime is limited to 7 years due to irradiation brittleness. The first replacement was done by using a spare part made in France. This replacement work of 2006 was carried out by using the domestic moderator cell unit. The following technologies were developed for the moderator cell unit production. 1) Technical development of black treatment on moderator cell surface to increase radiation heat. 2) Development of bending technology of concentric triple tubes consisting from inside tube, Outside tube and Vacuum insulation tube. 3) Development of manufacturing technique of the moderator cell with complicated shapes. According to detail planed work procedures, replacement work was carried out. As results, the working days were reduced to 80% of old ones. The radiation dose was also reduced due to reduction of working days. It was verified by measurement of neutrons characteristics that the replaced moderator cell has the same performance as that of the old moderator cell. The domestic manufacturing of the moderator cell was succeeded. As results, the replacement cost was reduced by development of domestic production technology. (author)

  1. Study of ex-vessel steam explosion risk of Reactor Pit Flooding System and structural response of containment for CPR1000"+ Unit

    International Nuclear Information System (INIS)

    Zhang Juanhua; Chen Peng

    2015-01-01

    Reactor Pit Flooding System is one of the special mitigation measures for severe accident for CPR1000"+ Unit. If the In-Vessel Relocation function of Reactor Pit Flooding System is failed, there is the steam explosion risk in reactor cavity. This paper firstly adopts MC3D code to build steam explosion model in order to calculate the pressure load and impulses of steam explosion that are as the input data of containment structural response analysis. The next step is to model the containment structure and analyze the structural response by ABAQUS code. The analysis results show that the integral damage induced by steam explosion to the external containment wall is shallow, and the containment structural integrity can be maintained. The risk and damage to the containment integrity reduced by steam explosion of RPF is small, and it does not influence the design and implementation of RPF. (author)

  2. Simulation of main steam and feedwater system of full scope simulator for Qinshan 300 MW Nuclear Power Unit

    International Nuclear Information System (INIS)

    Zhao Xiaoyu

    1996-01-01

    The simulation of main steam and feedwater system is the most important and maximal part in secondary circuit model, including all of main steam and feedwater's thermal-hydraulic properties, except heat-exchange of secondary side of steam generator. It simulates main steam header, steam power in each stage of turbine, moisture separator-reheater, deaerator, condenser, high pressure and low pressure heater, auxiliary feedwater and main steam bypass in full scope

  3. AGE RELATED DEGRADATION OF STEAM GENERATOR INTERNALS BASED ON INDUSTRY RESPONSES TO GENERIC LETTER 97-06

    International Nuclear Information System (INIS)

    SUBUDHI, M.; SULLIVAN, JR. E.J.

    2002-01-01

    THIS PAPER PRESENTS THE RESULTS OF AN AGING ASSESSMENT OF THE NUCLEAR POWER INDUSTRY RESPONSES TO NRC GENERIC LETTER 97-06 ON THE DEGRADATION OF STEAM GENERATOR INTERNALS EXPERIENCED AT ELECTRICITE DE FRANCE (EDF) PLANTS IN FRANCE AND AT A UNITED STATES PRESSURIZED WATER REACTOR (PWR). WESTINGHOUSE (W), COMBUSTION ENGINEERING (CE), AND BABCOCK AND WILCOX (BW) STEAM GENERATOR MODELS, CURRENTLY IN SERVICE AT U.S. NUCLEAR POWER PLANTS, POTENTIALLY COULD EXPERIENCE DEGRADATION SIMILAR TO THATFOUND AT EDF PLANTS AND THE U.S. PLANT. THE STEAM GENERATORS IN MANY OF THE U.S. PWRS HAVE BEEN REPLACED WITH STEAM GENERATORS WITH STEAM GENERATORS WITH IMPROVED DESIGNS AND MATERIALS. THESE REPLACEMENT STEAM GENERATORS HAVE BEEN MANUFACTURED IN THE U.S. AND ABROAD. DURING THIS ASSESSMENT, EACH OF THE THREE OWNERS GROUPS (W,CE, AND BW) IDENTIFIED FOR ITS STEAM GENERATOR, MODELS ALL THE POTENTIAL INTERNAL COMPONENTS THAT ARE VULNERABLE TO DEGRADATION WHILE IN SERVICE. EACH OWNERS GROUPDEVELOPED INSPEC TION AND MONITORING GUIDANCE AND RECOMMENDATIONS FOR ITS PARTICULAR STEAM GENERATOR MODELS. THE NUCLEAR ENERGY INSTITUTE INCORPORATED IN NEI 97-06 STEAM GENERATOR PROGRAM GUIDELINES, A REQUIREMENT TO MONITOR SECONDARY SIDE STEAM GENERATOR COMPONENTS IF THEIR FAILURE COULD PREVENT THE STEAM GENERATOR FROM FULFILLING ITS INTENDED SAFETY-RELATED FUNCTION. LICENSEES INDICATED THAT THEY IMPLEMENTED OR PLANNED TO IMPLEMENT, AS APPROPRIATE FOR THEIR STEAM GENERATORS, THEIR OWNERS GROUPRECOMMENDATIONS TO ADDRESS THE LONG-TERM EFFECTS OF THE POTENTIAL DEGRADATION MECHANISMS ASSOCIATED WITH THE STEAM GENERATOR INTERNALS

  4. Tube structural integrity evaluation of Palo Verde Unit 1 steam generators for axial upper-bundle cracking

    International Nuclear Information System (INIS)

    Woodman, B.W.; Begley, J.A.; Brown, S.D.; Sweeney, K.; Radspinner, M.; Melton, M.

    1995-01-01

    The analysis of the issue of upper bundle axial ODSCC as it apples to steam generator tube structural integrity in Unit 1 at the Palo Verde Nuclear generating Station is presented in this study. Based on past inspection results for Units 2 and 3 at Palo Verde, the detection of secondary side stress corrosion cracks in the upper bundle region of Unit 1 may occur at some future date. The following discussion provides a description and analysis of the probability of axial ODSCC in Unit 1 leading to the exceedance of Regulatory Guide 1.121 structural limits. The probabilities of structural limit exceedance are estimated as function of run time using a conservative approach. The chosen approach models the historical development of cracks, crack growth, detection of cracks and subsequent removal from service and the initiation and growth of new cracks during a given cycle of operation. Past performance of all Palo Verde Units as well as the historical performance of other steam generators was considered in the development of cracking statistics for application to Unit 1. Data in the literature and Unit 2 pulled tube examination results were used to construct probability of detection curves for the detection of axial IGSCC/IGA using an MRPC (multi-frequency rotating panake coil) eddy current probe. Crack growth rates were estimated from Unit 2 eddy current inspection data combined with pulled tube examination results and data in the literature. A Monte-Carlo probabilistic model is developed to provide an overall assessment of the risk of Regulatory Guide exceedance during plant operation

  5. Safety Evaluation Report related to the operation of Waterford Steam Electric Station, Unit No. 3 (Docket No. 50-382)

    International Nuclear Information System (INIS)

    1985-03-01

    Supplement 10 to the Safety Evaluation Report for the application filed by Louisiana Power and Light Company for a license to operate the Waterford Steam Electric Station, Unit 3 (Docket No. 50-382), located in St. Charles Parish, Louisiana, has been prepared by the Office of Nuclear Reactor Regulation of the US Nuclear Regulatory Commission. The purpose of this supplement is to update the Safety Evaluation Report by providing the staff's evaluation of information submitted by the licensee since the Safety Evaluation Report and its nine previous supplements were issued

  6. Investigation of separation and hydrodynamic characteristics of steam generators used at the NPPs running on PWR-1000 reactors

    International Nuclear Information System (INIS)

    Ageev, A.G.; Korolkov, B.M.; Nigmatulin, B.I.; Vasileva, R.V.; Nekrasov, A.V.; Titiv, V.F.; Tarankov, G.A.

    1997-01-01

    The tests were accomplished at the steam generator of unit 5 of the Novovoronezh nuclear power plant. The outbursts of the steam-water mixture from the gap between the steam generator housing and the submerged perforated screen rim at the side of the inlet coolant manifold were investigated. Tests of the steam generator with a modified steam separation system were carried out on the Balakovo nuclear power plant. The gilled separator of the steam generator was replaced with a steam collecting perforated screen, while the gap between the steam generator housing and the heat exchange bundle rim was closed with additional perforated screens at the side of the inlet manifold. This new solution of moisture separation is better. (M.D.)

  7. Safety Evaluation Report related to the operation of Comanche Peak Steam Electric Station, Unit 2 (Docket No. 50-446)

    International Nuclear Information System (INIS)

    1992-09-01

    This document supplement 25 to the Safety Evaluation Report related to the operation of the Comanche Peak Steam Electric Station (CPSES), Unit 2 (NUREG-0797), has been prepared by the Office of Nuclear Reactor Regulation of the US Nuclear Regulatory Commission (NRC). The facility is located in Somervell County, Texas, approximately 40 miles southwest of Fort Worth, Texas. This supplement reports the status of certain issues that had not been resolved when the Safety Evaluation Report and Supplements 1, 2, 3, 4, 6, 12, 21, 22, 23, and 24 to that report were published. This supplement deals primarily with Unit 2 issues; however, it also references evaluations for several Unit 1 licensing items resolved since Supplement 24 was issued

  8. Safety Evaluation Report related to the operation of Comanche Peak Steam Electric Station, Unit 2 (Docket No. 50-446)

    International Nuclear Information System (INIS)

    1993-02-01

    Supplement 26 to the Safety Evaluation Report related to the operation of the Comanche Peak Steam Electric Station (CPSES), Unit 2, has been prepared by the Office of Nuclear Reactor Regulation of the US Nuclear Regulatory Commission (NRC). The facility is located in Somervell County, Texas, approximately 40 miles southwest of Fort Worth, Texas. This supplement reports the status of certain issues that had not been resolved when the Safety Evaluation Report and Supplements 1, 2, 3, 4, 6, 12, 21, 22, 23, 24, and 25 to that report were published. This supplement deals primarily with Unit 2 issues; however, it also references evaluations for several licensing issues that relate to Unit 1, which have been resolved since Supplement 25 was issued

  9. Steam generators - problems and prognosis

    International Nuclear Information System (INIS)

    Tapping, R.L.

    1997-05-01

    Steam-generator problems, largely a consequence of corrosion and fouling, have resulted in increased inspection requirements and more regulatory attention to steam-generator integrity. In addition, utilities have had to develop steam-generator life-management strategies, including cleaning and replacement, to achieve design life. This paper summarizes the pertinent data to 1993/1994, and presents an overview of current steam-generator management practices. (author)

  10. Fast-Valving of Large Steam Turbine Units as a Means of Power System Security Enhancement

    OpenAIRE

    Bogdan Sobczak; Robert Rink; Rafał Kuczyński; Robert Trębski

    2014-01-01

    Fast-valving assists in maintaining system stability following a severe transmission system fault by reducing the turbine mechanical power. Fast-valving consists in rapid closing and opening of steam valves in an adequate manner to reduce the generator accelerating power following the recognition of a severe fault. FV can be an effective and economical method of meeting the performance requirements of a power system in the presence of an increase in wind and solar generation in the power syst...

  11. Maintenance and repair aspects of the steam generator modules for the United States' LMFBR demonstration plant

    Energy Technology Data Exchange (ETDEWEB)

    Devlin, R W

    1975-07-01

    This paper describes the main considerations relating to the field maintenance and repair of the steam generator modules for the Clinch River Breeder Reactor Plant and the development approaches being employed for some of the critical elements of these operations. In particular, the approach to plant chemical cleaning of the waterside of the modules and the approach to recovery from leaks between the water and sodium sides of the modules are discussed. (author)

  12. Maintenance and repair aspects of the steam generator modules for the United States' LMFBR demonstration plant

    International Nuclear Information System (INIS)

    Devlin, R.W.

    1975-01-01

    This paper describes the main considerations relating to the field maintenance and repair of the steam generator modules for the Clinch River Breeder Reactor Plant and the development approaches being employed for some of the critical elements of these operations. In particular, the approach to plant chemical cleaning of the waterside of the modules and the approach to recovery from leaks between the water and sodium sides of the modules are discussed. (author)

  13. Sludge Lancing and Visual Inspection of Steam Generator for KORI Nuclear Power Plant Unit 3

    Energy Technology Data Exchange (ETDEWEB)

    Jeong, Woo-Tae [Korea Hydro and Nuclear Power Co. Ltd. Central Research Institute, Daejeon(Korea, Republic of); Kim, Sang-Tae; Hong, Jae-Yung; Jeong, Yun-Soon [Sae-An Engineering Corporation, Seoul (Korea, Republic of)

    2015-05-15

    Annulus, tube-lane, and in-bundle area of the steam generators were searched for possible foreign objects. No new foreign objects were found. Two foreign objects which were found during previous outage were impossible to remove. Mock-up training before the operation was helpful to finish the service as scheduled. Sludge lancing of the three steam generators was made using FOLAS-I lancing system. FOSAR operations were done using video probe and special tools of Sae-An Engineering Cooperation. The weight of sludge removed from SG 'A', 'B', and 'C' was 177kg, 134kg, 117kg respectively. Bag filters for and cartridge filters consumed for SG 'A', 'B', and 'C' was (53,414), (75,243), and (61,171) respectively. Foreign object search operation for the annulus, the tube lane, and in-bundle area of the steam generators found nothing. Retrieval of the two remaining foreign objects from the previous outage was tried but failed.

  14. Sludge Lancing and Visual Inspection of Steam Generator for KORI Nuclear Power Plant Unit 3

    International Nuclear Information System (INIS)

    Jeong, Woo-Tae; Kim, Sang-Tae; Hong, Jae-Yung; Jeong, Yun-Soon

    2015-01-01

    Annulus, tube-lane, and in-bundle area of the steam generators were searched for possible foreign objects. No new foreign objects were found. Two foreign objects which were found during previous outage were impossible to remove. Mock-up training before the operation was helpful to finish the service as scheduled. Sludge lancing of the three steam generators was made using FOLAS-I lancing system. FOSAR operations were done using video probe and special tools of Sae-An Engineering Cooperation. The weight of sludge removed from SG 'A', 'B', and 'C' was 177kg, 134kg, 117kg respectively. Bag filters for and cartridge filters consumed for SG 'A', 'B', and 'C' was (53,414), (75,243), and (61,171) respectively. Foreign object search operation for the annulus, the tube lane, and in-bundle area of the steam generators found nothing. Retrieval of the two remaining foreign objects from the previous outage was tried but failed

  15. Proposal of organisation and ALARA procedures for maintenance site: application to replacement of steam generator; Propositions d'organisation et procedures ALARA pour la preparation des chantiers de maintenance: application au RGV

    Energy Technology Data Exchange (ETDEWEB)

    Lochard, J; Lefaure, C

    1989-08-01

    This report proposes generic organization and ALARA procedures for preparing a maintenance site at a NPP. After a short description of the ALARA principle, it describes the proposition for French sites. They are grouped according to the following: motivation, organisation, means. They are illustrated by the example of steam generator replacement. Three special points concerning preparation of the site are developed: education; training of operators; review of the project.

  16. Decreasing Postanesthesia Care Unit to Floor Transfer Times to Facilitate Short Stay Total Joint Replacements.

    Science.gov (United States)

    Sibia, Udai S; Grover, Jennifer; Turcotte, Justin J; Seanger, Michelle L; England, Kimberly A; King, Jennifer L; King, Paul J

    2018-04-01

    We describe a process for studying and improving baseline postanesthesia care unit (PACU)-to-floor transfer times after total joint replacements. Quality improvement project using lean methodology. Phase I of the investigational process involved collection of baseline data. Phase II involved developing targeted solutions to improve throughput. Phase III involved measured project sustainability. Phase I investigations revealed that patients spent an additional 62 minutes waiting in the PACU after being designated ready for transfer. Five to 16 telephone calls were needed between the PACU and the unit to facilitate each patient transfer. The most common reason for delay was unavailability of the unit nurse who was attending to another patient (58%). Phase II interventions resulted in transfer times decreasing to 13 minutes (79% reduction, P care at other institutions. Copyright © 2016 American Society of PeriAnesthesia Nurses. Published by Elsevier Inc. All rights reserved.

  17. A study on the evaluation of vibration effect and the development of vibration reduction method for Wolsung unit 1 main steam piping

    Energy Technology Data Exchange (ETDEWEB)

    Lee, Hyun; Kim, Yeon Whan [Korea Electric Power Corp. (KEPCO), Taejon (Korea, Republic of). Research Center; Kim, Tae Ryong; Park, Jin Ho [Korea Atomic Energy Research Inst., Daeduk (Korea, Republic of)

    1996-08-01

    The main steam piping of nuclear power plant which runs between steam generator and high pressure turbine has been experienced to have a severe effect on the safe operation of the plant due to the vibration induced by the steam flowing inside the piping. The imposed cyclic loads by the vibration could result in the degradation of the related structures such as connection parts between main instruments, valves, pipe supports and building. The objective of the study is to reduce the vibration level of Wolsung nuclear power plant unit 1 main steam pipeline by analyzing vibration characteristics of the piping, identifying sources of the vibration and developing a vibration reduction method .The location of the maximum vibration is piping between the main steam header and steam chest .The stress level was found to be within the allowable limit .The main vibration frequency was found to be 4{approx}6 Hz which is the same as the natural frequency from model test .A vibration reduction method using pipe supports of energy absorbing type(WEAR)is selected .The measured vibration level after WEAR installation was reduced about 36{approx}77% in displacement unit (author). 36 refs., 188 figs.

  18. Theoretical-empirical model of the steam-water cycle of the power unit

    Directory of Open Access Journals (Sweden)

    Grzegorz Szapajko

    2010-06-01

    Full Text Available The diagnostics of the energy conversion systems’ operation is realised as a result of collecting, processing, evaluatingand analysing the measurement signals. The result of the analysis is the determination of the process state. It requires a usageof the thermal processes models. Construction of the analytical model with the auxiliary empirical functions built-in brings satisfyingresults. The paper presents theoretical-empirical model of the steam-water cycle. Worked out mathematical simulation model containspartial models of the turbine, the regenerative heat exchangers and the condenser. Statistical verification of the model is presented.

  19. Liquid metals replace water steam

    Energy Technology Data Exchange (ETDEWEB)

    Kozlov, V

    1976-12-01

    The techniques are described of power generation with regard to their effectiveness which depends on the efficiency of the conversion of thermal energy into electric energy. The magnetohydrodynamic conversion of energy is based on the use of induced electromotive force which results from the movement of the conductor in the magnetic field. The use of liquid metal as the working medium makes it possible to increase the initial temperature of the magnetohydrodynamic cycle to the limit of the highest technically attainable temperatures. The total efficiency of energy conversion in magnetohydrodynamic converters is 2 to 6%.

  20. Liquid metals replace water steam

    International Nuclear Information System (INIS)

    Kozlov, V.

    1976-01-01

    The techniques are described of power generation with regard to their effectiveness which depends on the efficiency of the conversion of thermal energy into electric energy. The magnetohydrodynamic conversion of energy is based on the use of induced electromotive force which results from the movement of the conductor in the magnetic field. The use of liquid metal as the working medium makes it possible to increase the initial temperature of the magnetohydrodynamic cycle to the limit of the highest technically attainable temperatures. The total efficiency of energy conversion in magnetohydrodynamic converters is 2 to 6%. (J.B.)

  1. Strategic management of steam generators

    International Nuclear Information System (INIS)

    Hernalsteen, P.; Berthe, J.

    1991-01-01

    This paper addresses the general approach followed in Belgium for managing any kind of generic defect affecting a Steam Generator tubebundle. This involves the successive steps of: problem detection, dedicated sample monitoring, implementation of preventive methods, development of specific plugging criteria, dedicated 100% inspection, implementation of repair methods, adjusted sample monitoring and repair versus replacement strategy. These steps are illustrated by the particular case of Primary Water Stress Corrosion Cracking in tube roll transitions, which is presently the main problem for two Belgian units Doele-3 and Tihange-2. (author)

  2. Replacement energy costs for nuclear electricity-generating units in the United States: 1997--2001. Volume 4

    International Nuclear Information System (INIS)

    VanKuiken, J.C.; Guziel, K.A.; Tompkins, M.M.; Buehring, W.A.

    1997-09-01

    This report updates previous estimates of replacement energy costs for potential short-term shutdowns of 109 US nuclear electricity-generating units. This information was developed to assist the US Nuclear Regulatory Commission (NRC) in its regulatory impact analyses, specifically those that examine the impacts of proposed regulations requiring retrofitting of or safety modifications to nuclear reactors. Such actions might necessitate shutdowns of nuclear power plants while these changes are being implemented. The change in energy cost represents one factor that the NRC must consider when deciding to require a particular modification. Cost estimates were derived from probabilistic production cost simulations of pooled utility system operations. Factors affecting replacement energy costs, such as random unit failures, maintenance and refueling requirements, and load variations, are treated in the analysis. This report describes an abbreviated analytical approach as it was adopted to update the cost estimates published in NUREG/CR-4012, Vol. 3. The updates were made to extend the time frame of cost estimates and to account for recent changes in utility system conditions, such as change in fuel prices, construction and retirement schedules, and system demand projects

  3. Trip report: United States LMFBR Steam Generator Team. IAEA symposium, Bensberg, Germany, October 14--17, 1974

    International Nuclear Information System (INIS)

    1974-01-01

    Information is presented concerning steam generator design characteristics for the AFR reactor, SNR reactor, PHENIX reactor, SUPER PHENIX reactor, MONJU reactor, and BN-350 reactor; steam generator development programs for West Germany, France, Japan, U. K., and the U. S. S. R.; and the fabrication and inspection of steam generator components. Steam generator performance and maintenance requirements for operating LMFBR reactors are reviewed. (U.S.)

  4. Safety measures for the main control board replacement project at Ikata units 1 and 2

    International Nuclear Information System (INIS)

    Hashimoto, Nozomu; Tada, Kenji

    2013-01-01

    When Units 1 and 2 of the Ikata Power Station underwent replacement of their main control boards, control cabinets, and associated equipment, it was necessary to remove all the control boards, cabinets, and cables from the control building including from the main control room. This meant the loss of operation and monitoring functions in the main control room and functions of control cabinets. To maintain the operation and monitoring functions required under plant shutdown conditions, temporary operation and monitoring equipment (i.e., temporary main control board) was installed in the temporary main control room. The advance preparations included a trial switching from the permanent to the temporary main control board to identify and address potential problems in advance. When the replacement work was underway, a work schedule sheet posted in the temporary and the permanent control rooms was used to prevent human errors caused by operators’ recognition errors. Monitoring and control signals were switched from the old boards to the temporary boards and from the temporary boards to the new boards at appropriate timings to ensure plant safety during the replacement operation. (author)

  5. Replacement of a cracked pressure tube in Bruce GS unit 2

    International Nuclear Information System (INIS)

    Dunn, J.T.

    1982-06-01

    In 1982 February, a primary heat transport system leak was detected in the annulus gas system by on-line instrumentation. The source of the leak was found to be a small axial crack in the pressure tube of fuel channel X-14. This fuel channel was removed and replaced by station maintenance staff, and the unit was returned to service five weeks after it had been shut down. The cracked pressure tube was sent to Chalk River Nuclear Laboratories for examination, and the crack was found to be very similar to those found in Pickering GS units 3 and 4 in 1974-75. It was caused by delayed hydride cracking during the period of high residual stress between the time of rolling and the pre-service stress relief

  6. The United States Naval Nuclear Propulsion Program - Over 151 Million Miles Safely Steamed on Nuclear Power

    Energy Technology Data Exchange (ETDEWEB)

    None, None

    2015-03-01

    NNSA’s third mission pillar is supporting the U.S. Navy’s ability to protect and defend American interests across the globe. The Naval Reactors Program remains at the forefront of technological developments in naval nuclear propulsion and ensures a commanding edge in warfighting capabilities by advancing new technologies and improvements in naval reactor performance and reliability. In 2015, the Naval Nuclear Propulsion Program pioneered advances in nuclear reactor and warship design – such as increasing reactor lifetimes, improving submarine operational effectiveness, and reducing propulsion plant crewing. The Naval Reactors Program continued its record of operational excellence by providing the technical expertise required to resolve emergent issues in the Nation’s nuclear-powered fleet, enabling the Fleet to safely steam more than two million miles. Naval Reactors safely maintains, operates, and oversees the reactors on the Navy’s 82 nuclear-powered warships, constituting more than 45 percent of the Navy’s major combatants.

  7. Device for inspection and/or repair of tubes of a steam raising unit for nuclear reactors

    International Nuclear Information System (INIS)

    Wollensack, W.

    1985-01-01

    The device is situated in a chamber bounded by a pipe floor, the hemispherical floor of the steam raising unit and a wall extending between the pipe floor and this hemi-spherical floor. By using lifting gear which can be anchored in the pipe floor, a supporting leg is introduced into the chamber. Pegs of this supporting leg turned towards the pipe floor act to stop the supporting leg in the pipe floor. To make positioning of the pegs in the pipe floor easier, the lifting gear is provided with a guide turned towards the supporting leg. The guide has a spacer, which is fixed to the supporting leg and guides this along a wall of the chamber. (orig./HP) [de

  8. Non-contact control of the working condition of mechanical units of the steam compressor for desalination plant

    Science.gov (United States)

    Danilin, A. I.; Chernyavsky, A. Zh.; Danilin, S. A.; Neverov, V. V.; Voroh, D. A.; Blagin, E. V.

    2018-03-01

    New methods and means for monitoring working condition of the rotating elements of steam compressor unit such as blade ring of the impeller and gears of multiplier are considered. Blade control is carried out by the signalling device of pre-emergency deformation of impeller blades. Control of the gears condition is carried out by apparatus system which allows to analyse change of the signal form caused by the gears wear. Influence of the wear types on the typical information parameters of the analysed signals is described. Technical characteristics of the devices and experimental research results are presented. Described control systems allow to detect deviations equal to 1-2% from initial condition. Application of such systems gives the opportunity to improve fault diagnosis and maintenance in 2-3 times.

  9. Steam-water separator

    International Nuclear Information System (INIS)

    Modrak, T.M.; Curtis, R.W.

    1978-01-01

    A two-stage steam-water separating device is introduced, where the second stage is made as a cyclone separator. The water separated here is collected in the first stage of the inner tube and is returned to the steam raising unit. (TK) [de

  10. Steam supply and power cogeneration at Yanshan Petrochemical Co., Ltd.

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2000-03-01

    For the purpose of reducing greenhouse effect gas emissions, a project was studied for the improvement of cogeneration facilities with steam supply of 600t/h and electric output of 55MW at Beijing Yanshan Petrochemical Co., China. In Plan A, fuel is changed from heavy oil to natural gas, and two heavy oil boilers are replaced with two gas turbines and two exhaust heat recovery steam generators for steam supply of 241t/h per unit and electric output of 136.9MW per unit. In Plan B, the boilers are replaced with three gas turbines and three exhaust heat recovery steam generators for steam supply of 210t/h per unit and electric output of 79.5MW per unit. The initial investment is 700 million yuan {+-} 100 million yuan in Plan A, and 500 million yuan {+-} 100 million yuan in Plan B. The generating cost is 0.403 yuan/kWh in Plan A, and 0.455 yuan/kWh in Plan B. It was concluded that without Plan A, the project will not be economically successful. In Plan A, the energy conservation will be 887,847 toe/y heavy oil equivalent, which increases productivity. Further, the amount of greenhouse effect gas emissions will be 2,747,187 t-CO2/y. (NEDO)

  11. Technical specifications: Susquehanna Steam Electric Station, Unit No. 2 (Docket No. 50-388). Appendix A to License No. NPF-22

    International Nuclear Information System (INIS)

    1984-03-01

    Susquehanna Steam Electric Station, Unit 2 Technical Specifications were prepared by the US Nuclear Regulatory Commission to set forth the limits, operating conditions, and other requirements applicable to a nuclear reactor facility as set forth in Section 50.36 of 10 CFR Part 50 for the protection of the health and safety of the public

  12. A nuclear power unit with a Babcock type steam generating system-analysis of the break-down in the Three Mile Island power plant

    International Nuclear Information System (INIS)

    Werner, A.

    1980-01-01

    Installations of the primary and the secondary circuits and basic automatic control and protection systems for a nuclear power unit with Babcock type vertical, once-through steam generator are described. On this background the course of the break-down in the Three Mile Island power plant at Harrisburg is presented and analysed. (author)

  13. Active acoustic leak detection in steam generator units of fast reactors

    International Nuclear Information System (INIS)

    Oriol, L.; Journeau, Ch.

    1996-01-01

    Steam generators (SG) of Fast Reactors can be subject to water leakage into the sodium secondary circuit, causing an exothermic chemical reaction with potential serious damage to plant. Within the framework of the European Fast Reactor project, the CEA has developed an active acoustic detection technique which, when used in parallel with passive acoustic detection, will lead to effective leak detection results in terms of reliability and false alarm rates. Whilst the passive method is based on the increase in acoustic noise generated by the reaction, the active method takes advantage of the acoustic attenuation by the hydrogen bubbles produced. The method has been validated: in water, during laboratory testing at the Centre d'Etudes de Cadarache; in sodium, at the ASB loop at Bensberg (Germany) and at AEA Dounreay (Scotland). Full analysis of the tests carried out on the SG of the Prototype Fast Reactor in 1994 during end-of-life testing should lead to reactor validation on the method. (authors)

  14. Brunswick Steam Electric Plant, Units 1 and 2. Annual operating report for 1976

    International Nuclear Information System (INIS)

    1977-01-01

    Net electrical energy generated by Unit 1 was 30,399 MWH with the generator on line 334.5 hrs. Unit 2 generated 2,481,014 MWH with the generator on line 4,915.53 hrs. Information is presented concerning operations, shutdowns and power reductions, maintenance, power generation, modifications, changes to operational procedures, radiation exposures, and leak rate testing

  15. Steam generator operation and maintenance

    International Nuclear Information System (INIS)

    Lee, C.K.

    2004-01-01

    Corrosion of steam generator tube has resulted in the need for extensive repair and replacement of steam generators. Over the past two decades, steam generator problems in the United States were viewed to be one of the most significant contributor to lost generation in operating PWR plants. When the SGOG-I (Steam Generator Owners Groups) was formed in early 1977, denting was responsible for almost 90% of the tube plugging. By the end of 1982, this figure was reduced to less than 2%. During the existence of SGOG-II (from 1982 to 1986), IGA/SCC (lntergranular Attack/Stress Corrosion Cracking) in the tube sheet, primary side SCC, pitting, and fretting surfaced as the primary causes of tube degradation. Although significant process has been made with wastage and denting, the utilities experience shows that the percentage of reactors plugging tubes and the percentage of tubes being plugged each year has remained relatively constant. The diversity of the damage mechanisms means that no one solution is likely to resolve all problems. The task of maintaining steam generator integrity continues to be formidable and challenging. As the older problems were brought under control, many new problems emerged. SGOG-II (Steam Generator Owners Group program from 1982 to 1986) has focused on these problem areas such as tube stress corrosion cracking (SCC) and intergranular attack (IGA) in the open tube sheet crevice, primary side tube cracking, pitting in the lower span, and tube fretting in preheated section and anti-vibration bar (AVB) locations. Primary Water Stress Corrosion Cracking (PWSCC) in the tube to tubesheet roll transition has been a wide spread problem in the Recirculation Steam Generators (RSG) during this period. Although significant progress has been made in resolving this problem, considerable work still remains. One typical problem in the Once Through Steam Generator (OTSG) was the tube support plate broached hole fouling which affects the OTSG steam generating

  16. Analysis of steam-generator tube-rupture events combined with auxiliary-feedwater control-system failure for Three Mile Island-Unit 1 and Zion-Unit 1 pressurized water reactors

    International Nuclear Information System (INIS)

    Nassersharif, B.

    1986-01-01

    A steam-generator tube-rupture (SGTR) event combined with loss of all offsite alternating-current power and failure of the auxiliary-feedwater (AFW) control system has been investigated for the Three Mile Island-Unit 1 (TMI-1) and Zion-Unit 1 (Zion-1) pressurized water reactors. The Transient Reactor Analysis Code was used to simulate the accident sequence for each plant. The objectives of the study were to predict the plant transient response with respect to tube-rupture flow termination, extent of steam generator overfill, and thermal-hydraulic conditions in the steam lines. Two transient cases were calculated: (1) a TMI-1 SGTR and runaway-AFW transient, and (2) a Zion-1 SGTR and runaway-AFW transient. Operator actions terminated the tube-rupture flow by 1342 s (22.4 min) and 1440 s (24.0 min) for TMI-1 and Zion-1, respectively, but AFW injection was continued. The damaged steam generator (DSG) overfilled by 1273 s (21.2 min) for the TMI-1 calculation and by 1604 s (26.7 min) for the Zion-1 calculation. The DSG steam lines were completely filled by 1500 s (25 min) and 2000 s (33.3 min) for TMI-1 and Zion-1, respectively. The maximum subcooling in the steam lines was approx.63 K (approx.113 0 F) for TMI-1 and approx.44 K (approx.80 0 F) for Zion-1

  17. Some causes of vibrations recorded by in-service diagnostic systems in steam generators of units 1 and 2 of Dukovany nuclear power plant

    International Nuclear Information System (INIS)

    Sadilek, J.; Matal, O.

    1989-01-01

    A brief description is presented of the design of the steam generators of the first and second units of the Dukovany nuclear power plant. Attention is also given to the feed water systems and the diagnostic systems. The causes are analyzed of the irregularly occurring vibrations in the steam generators in service. It is demonstrated that the source of the vibrations transmitted to the steam generators are the valves in the feeding tract. The vibrations are induced by dynamic forces from the feed water. Reducing the water pressure at the delivery of the electric feed pumps by reducing the size of the rotor, etc., does not remove all vibrations. It is therefore recommended that valves be ins+alled with better regulating characteristics. (Z.M.). 6 figs., 1 tab., 3 refs

  18. Water lancing of Bruce-A Unit 3 and 4 steam generators

    International Nuclear Information System (INIS)

    Puzzuoli, F.V.; Murchie, B.; Allen, S.

    1995-01-01

    During the Bruce-A 1993 Unit 4 and 1994 Unit 3 outages, three water lancing operations were carried out along with chemical cleaning as part of the station boiler refurbishment program. The water lancing activities focused on three boiler areas.. 1) support plates to clean partially or completely blocked broach holes and prevent boiler water level oscillations, 2) hot leg U-bend supports (HLUBS) to remove deposits contributing to boiler tube stress corrosion cracking (SCC) and 3) tube sheets to dislodge sludge piles that potentially threaten boiler tube integrity and to flush out post chemical cleaning insoluble residues. The combination of water lancing and chemical cleaning effectively reduced broach hole blockage from up to 100% to 0-10% or less. As a result, boilers in Units 3 and 4 will operate for some time to come without concerns over water level oscillations. However, deposits remained in most tube support plate land areas. (author)

  19. A study on the optimal replacement periods of digital control computer's components of Wolsung nuclear power plant unit 1

    International Nuclear Information System (INIS)

    Mok, Jin Il; Seong, Poong Hyun

    1993-01-01

    Due to the failure of the instrument and control devices of nuclear power plants caused by aging, nuclear power plants occasionally trip. Even a trip of a single nuclear power plant (NPP) causes an extravagant economical loss and deteriorates public acceptance of nuclear power plants. Therefore, the replacement of the instrument and control devices with proper consideration of the aging effect is necessary in order to prevent the inadvertent trip. In this paper we investigated the optimal replacement periods of the control computer's components of Wolsung nuclear power plant Unit 1. We first derived mathematical models of optimal replacement periods to the digital control computer's components of Wolsung NPP Unit 1 and calculated the optimal replacement periods analytically. We compared the periods with the replacement periods currently used at Wolsung NPP Unit 1. The periods used at Wolsung is not based on mathematical analysis, but on empirical knowledge. As a consequence, the optimal replacement periods analytically obtained and those used in the field show a little difference. (Author)

  20. Mathematical models of power plant units with once-through steam generators

    International Nuclear Information System (INIS)

    Hofmeister, W.; Kantner, A.

    1977-01-01

    An optimization of effective control functions with the current complex control loop structures and control algorithms is practically not possible. Therefore computer models are required which may be optimized with the process and plant data known before start-up of thermal power plants. The application of process computers allows additional predictions on the control-dynamic behavior of a thermal power plant unit. (TK) [de

  1. BWR Steam Dryer Alternating Stress Assessment Procedures

    Energy Technology Data Exchange (ETDEWEB)

    Morante, R. J. [Brookhaven National Lab. (BNL), Upton, NY (United States); Hambric, S. A. [Brookhaven National Lab. (BNL), Upton, NY (United States); Ziada, S. [Brookhaven National Lab. (BNL), Upton, NY (United States)

    2016-12-01

    This report presents an overview of Boiling Water Reactor (BWR) steam dryer design; the fatigue cracking failures that occurred at the Quad Cities (QC) plants and their root causes; a history of BWR Extended Power Uprates (EPUs) in the USA; and a discussion of steam dryer modifications/replacements, alternating stress mechanisms on steam dryers, and structural integrity evaluations (static and alternating stress).

  2. Handling steam generator problems: the strategy for Ringhals 3 and 4

    International Nuclear Information System (INIS)

    Larsen, G.

    1992-01-01

    An examination in Sweden of twelve Pressurized Water Reactor steam generator tubes (six from Ringhals 3 and six from Ringhals 4) revealed that several had cracks in the roll transition zone, all tubes had shallow intergranular attacks at support plate (TSP) intersections, and some from Ringhals 3 had cracks in the TSP position due to intergranular stress corrosion. It was concluded that this could drastically limit the possibility of successfully operating Ringhals 3 (which entered commercial operation in 1981) to 2010, the year when all nuclear power in Sweden will be phased out. Two possible ways to deal with the problem were investigated: replace the steam generators and uprate the plant; operate with the existing steam generators and reduce the rate of degradation by lowering the primary water temperature, with most failed tubes repaired by sleeving. The analysis showed that replacement of the Ringhals 3 steam generators would be a good investment. As there were no attacks in the TSP intersections at Ringhals 4, which started commercial operation in 1983, it was assumed possible to operate this unit until 2010 without any temperature reduction. The economic evaluation for Ringhals 4 nevertheless indicated that it would be cost effective to replace the steam generators and uprate Ringhals 4 to 112%. However, a new economic study showed that it will still be cost effective to replace the steam generators at Ringhals 3, but it is not clear that there is still a case for replacement at Ringhals 4. Ringhals 3 steam generators will be replaced in 1995, while Ringhals 4 will continue to operate with the existing steam generators. (Author)

  3. Future steam generator designs. Single wall designs

    Energy Technology Data Exchange (ETDEWEB)

    Hayden, O [Nuclear Power Company Ltd, Warrington, Cheshire (United Kingdom)

    1978-10-01

    The easily removable 'U' tube design style adopted in the UK for the existing PFR Steam Generators, the Replacement Units now in production and for the future CDFR, gives the operator an extremely valuable option in the event of a water/steam leak occurring inside the Steam Generator. He can choose to shut-down, attempt to find the leak, assess damage, repair, revalidate and return to service in situ, or he can elect to remove the defect unit and replace with a 'proven' spare before returning the circuit to power. With the latter approach the resultant outage time is a known entity of about two weeks. If a repair is attempted in situ, predictions of outage time can become a matter of guesswork since one has no 'guaranteed' method of leak location and the assessment of secondary damage may be very time consuming, depending on the size and type of the original leak together with the particular design style of the Steam Generator. A further significant advantage of the removable 'U' tube design concept is that periodic interchanging of bundles with a spare enables routine chemical cleaning and thorough scheduled tube inspections, with specimen tube sample removal if required for monitoring purposes. If necessary, bundle decontamination can be undertaken to assess engineering deterioration to various degrees of thoroughness ranging from 100% equivalent factory final assembly inspection, to partial decontamination operating via a glovebox type of maintenance bag arrangement, examining local points of both shell and tube areas of the bundle. Many lessons from the last five years' experience of PFR will be incorporated into the design of the CDFR and PFR Steam Generators have two very good examples of how the designer can ease or severely handicap the operator in coping with sodium/water leakages. Good, quick access to tube ends is achieved in the existing PFR Evaporator by simply unbolting the steam/water closure head, but on the superheater and reheater hand-caps have

  4. Future steam generator designs. Single wall designs

    International Nuclear Information System (INIS)

    Hayden, O.

    1978-01-01

    The easily removable 'U' tube design style adopted in the UK for the existing PFR Steam Generators, the Replacement Units now in production and for the future CDFR, gives the operator an extremely valuable option in the event of a water/steam leak occurring inside the Steam Generator. He can choose to shut-down, attempt to find the leak, assess damage, repair, revalidate and return to service in situ, or he can elect to remove the defect unit and replace with a 'proven' spare before returning the circuit to power. With the latter approach the resultant outage time is a known entity of about two weeks. If a repair is attempted in situ, predictions of outage time can become a matter of guesswork since one has no 'guaranteed' method of leak location and the assessment of secondary damage may be very time consuming, depending on the size and type of the original leak together with the particular design style of the Steam Generator. A further significant advantage of the removable 'U' tube design concept is that periodic interchanging of bundles with a spare enables routine chemical cleaning and thorough scheduled tube inspections, with specimen tube sample removal if required for monitoring purposes. If necessary, bundle decontamination can be undertaken to assess engineering deterioration to various degrees of thoroughness ranging from 100% equivalent factory final assembly inspection, to partial decontamination operating via a glovebox type of maintenance bag arrangement, examining local points of both shell and tube areas of the bundle. Many lessons from the last five years' experience of PFR will be incorporated into the design of the CDFR and PFR Steam Generators have two very good examples of how the designer can ease or severely handicap the operator in coping with sodium/water leakages. Good, quick access to tube ends is achieved in the existing PFR Evaporator by simply unbolting the steam/water closure head, but on the superheater and reheater hand-caps have

  5. Development, implementation and operational experience with 900 mm R1T pocket-type bearings at Oskarshamn unit 3 nuclear steam turbine generator

    International Nuclear Information System (INIS)

    Peel, P.; Roos, A.

    2015-01-01

    The Oskarshamn unit 3 nuclear steam turbine generator in Sweden is operated by OKG and, following the extensive PULS upgrade project, delivers an increased rated output of 1450 MW making it the most powerful BWR unit worldwide. Several turbine bearing incidents occurred in 2009 and 2010, which initiated a detailed root cause analysis to determine the reasons and propose appropriate mitigation measures to ensure reliable unit operation. Together with OKG, ALSTOM Power implemented a short-term solution to operate the unit over the winter period of 2010-11. Subsequently, during the annual outage in June 2011, a permanent solution involving a R1T pocket-type bearing design was installed at three shaft-line positions. Since the 1980's, R1T bearings with diameters from 250 to 670 mm have been operating in numerous full-speed (3000/3600 rpm) steam turbine generators. However, this was the first application of a R1T bearing developed at a diameter of 900 mm and for half-speed operation. This paper presents an overview of the bearing development and details the successful operational feedback gathered to date on the three installed bearings. In comparison with the three tilting pad bearing design, which has typically been used on large half-speed ALSTOM Power steam turbine generators to date, it confirms the R1T bearing design as a viable alternative. (authors)

  6. Final Environmental Statement related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445 and 50-446)

    International Nuclear Information System (INIS)

    1989-10-01

    In September 1981, the staff of the Nuclear Regulatory Commission (NRC) issued its Final Environmental Statement (NUREG-0775) related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445 and 50-446), located in Somervell County, Texas, approximately 40 miles southwest of Fort Worth, Texas. The NRC has prepared this supplement to NUREG-0775 to present its evaluation of the alternative of operating Comanche Peak with the installation of further severe-accident-mitigation design features. The NRC has discovered no substantial changes in the proposed action as previously evaluated in the Final Environmental Statement that are relevant to environmental concerns and bearing on the licensing of Comanche Peak Steam Electric Station, Units 1 and 2. 6 refs., 3 tabs

  7. Safety evaluation report related to the operation of Waterford Steam Electric Station, Unit No. 3 (Docket No. 50-382). Supplement No. 7

    International Nuclear Information System (INIS)

    1984-09-01

    Supplement 7 to the Safety Evaluation Report for Louisiana Power and Light's application for a license to operate Waterford Steam Electric Station, Unit 3 (Docket No. 50-382), located in St. Charles Parish, Louisiana, has been jointly prepared by the Office of Nuclear Reactor Regulation and the Region IV Office of the US Nuclear Regulatory Commission. This supplement provides the results to date of the staff's evaluation of approximately 350 allegations and concerns of poor construction practices at the Waterford 3 facility

  8. Draft environmental statement related to steam-generator repair at Point Beach Nuclear Plant, Unit No. 1. Docket No. 50-266

    International Nuclear Information System (INIS)

    1983-07-01

    The staff has considered the environmental impacts and economic costs of the proposed steam generator repair at the Point Beach Nuclear Plant Unit No. 1 along with reasonable alternatives to the proposed action. The staff has concluded that the proposed repair will not significantly affect the quality of the human environment and that there are no preferable alternatives to the proposed action. Furthermore, any impacts from the repair program are outweighed by its benefits

  9. Final environmental statement related to steam-generator repair at Point Beach Nuclear Plant, Unit No. 1 (Docket No. 50-266)

    International Nuclear Information System (INIS)

    1983-09-01

    The staff hhas considered the environental impacts and economic costs of the proposed steam generator repair at the Point Beach Nuclear Plant, Unit No. 1 along with reasonable alternatives to the proposed action. The staff has concluded that the proposed repair will not significantly affect the quality of the human environment and that there are no preferable alternatives to the proposed action. Furthermore, any impacts from the repair program are outweighed by its benefits

  10. Evaluation of Steam Generator Level behavior for Determination of Turbine Runback rate on COPs trip for Yonggwang 1 and 2 Power Uprating Units

    International Nuclear Information System (INIS)

    Lee, Kyung Jin; Hwang, Su Hyun; Yoo, Tae Geun; Chung, Soon Il; An, Byung Chang; Park, Jung Gu

    2010-01-01

    4.5% power uprate project has been progressing for the first time in Yonggwang 1 and 2(YGN1 and 2). Reviews for design change due to the power uprate were accomplished. Steam generator level behavior was one of the most important parameters because it could be cause of reactor trip or turbine trip. As the results of the reviews, YGN1 and 2 had to reassess it for change of turbine runback rate when turbine runback occurs due to the condensate operating pumps (COP) trip. This study has been carried out for evaluating the steam generator level behavior for determination of turbine runback rate on COPs trip for Yonggwang 1 and 2 Power Uprating Units. The steam generator water level evaluation program for YGN1 and 2 (SLEP-Y1) has been developed for it. The program includes models for the steam generator water level response. SLEP-Y1 is programmed with advanced continuous system simulation language (ACSL). The language has been used to simulate physical systems as a commercial tool used to evaluate system designs

  11. Trends in Testosterone Replacement Therapy Use from 2003 to 2013 among Reproductive-Age Men in the United States.

    Science.gov (United States)

    Rao, Pravin Kumar; Boulet, Sheree L; Mehta, Akanksha; Hotaling, James; Eisenberg, Michael L; Honig, Stanton C; Warner, Lee; Kissin, Dmitry M; Nangia, Ajay K; Ross, Lawrence S

    2017-04-01

    Although testosterone replacement therapy use in the United States has increased dramatically in the last decade, to our knowledge trends in testosterone replacement therapy use among reproductive-age men have not been investigated. We assessed changes in testosterone replacement therapy use and practice patterns among 18 to 45-year-old American men from 2003 to 2013 and compared them to older men. This is a retrospective, cross-sectional analysis of men 18 to 45 and 56 to 64 years old who were enrolled in the Truven Health MarketScan® Commercial Claims Databases throughout each given calendar year from 2003 to 2013, including 5,094,868 men in 2013. Trends in the yearly rates of testosterone replacement therapy use were calculated using Poisson regression. Among testosterone replacement therapy users, the Cochran-Armitage test was used to assess temporal trends in age, formulation type, semen analysis and serum testosterone level testing during the 12 months preceding the documented use of testosterone replacement therapy. Between 2003 and 2013, there was a fourfold increase in the rate of testosterone use among 18 to 45-year-old men from 29.2/10,000 person-years to 118.1/10,000 person-years (p replacement therapy users, topical gel formulations were initially most used. Injection use then doubled between 2009 and 2012 (23.5% and 46.2%, respectively) and surpassed topical gel use in 2013. In men 56 to 64 years old there was a statistically significant threefold increase in testosterone replacement therapy use (p replacement therapy use increased fourfold in men 18 to 45 years old compared to threefold in older men. This younger age group should be a focus for future studies due to effects on fertility and unknown long-term sequelae. Copyright © 2017 American Urological Association Education and Research, Inc. Published by Elsevier Inc. All rights reserved.

  12. Design of SMART steam generator cassette

    International Nuclear Information System (INIS)

    Kim, Y. W.; Kim, J. I.; Jang, M. H.

    2001-01-01

    Basic design development for the steam generator to be installed in the integral reactor SMART has been performed. Optimization of the steam generator shape, determination of the basic dimension and confirmation of the structural strength have been carried out. Individual steam generator cassette can be replaced in the optimized design concept of steam generator. Shape design of the steam generator cassette has been done on the computer based on 3-D CAE strategy. The structural integrity of the developed steam generator was investigated by performing the dynamic analysis for the steam generator cassette, flow induced vibration analysis for the tube bundle, and the thermo-mechanical analysis for the module header and tube. As for the manufacturing of steam generator, the numerical and the experimental simulation have been carried to control the amount of spring back and to eliminate residual stress. SMART steam generator cassette was developed by a sequential research of the aforementioned activities

  13. Effects of Chemistry Parameters of Primary Water affecting Leakage of Steam Generator Tube Cracks

    Energy Technology Data Exchange (ETDEWEB)

    Shin, D. M.; Cho, N. C.; Kang, Y. S.; Lee, K. H. [KHNP CRI, Daejeon (Korea, Republic of)

    2016-10-15

    Degradation of steam generator (SG) tubes can affect pressure boundary tightness. As a defense-in-depth measure, primary to secondary leak monitoring program for steam generators is implemented, and operation is allowed under leakage limits in nuclear power plants. Chemistry parameters that affect steam generator tube leakage due to primary water stress corrosion cracking (PWSCC) are investigated in this study. Tube sleeves were installed to inhibit leakage and improve tube integrity as a part of maintenance methods. Steam generators occurred small leak during operation have been replaced with new steam generators according to plant maintenance strategies. The correlations between steam generator leakage and chemistry parameters are presented. Effects of primary water chemistry parameters on leakage from tube cracks were investigated for the steam generators experiencing small leak. Unit A experienced small leakage from steam generator tubes in the end of operation cycle. It was concluded that increased solubility of oxides due to high pHT could make leakage paths, and low boron concentration lead to less blockage in cracks. Increased dissolved hydrogen may retard crack propagations, but it did not reduce leak rate of the leaking steam generator. In order to inhibit and reduce leakage, pH{sub T} was controlled by servicing cation bed operation. The test results of decreasing pHT indicate low pHT can reduce leak rate of PWSCC cracks in the end of cycle.

  14. Effects of Chemistry Parameters of Primary Water affecting Leakage of Steam Generator Tube Cracks

    International Nuclear Information System (INIS)

    Shin, D. M.; Cho, N. C.; Kang, Y. S.; Lee, K. H.

    2016-01-01

    Degradation of steam generator (SG) tubes can affect pressure boundary tightness. As a defense-in-depth measure, primary to secondary leak monitoring program for steam generators is implemented, and operation is allowed under leakage limits in nuclear power plants. Chemistry parameters that affect steam generator tube leakage due to primary water stress corrosion cracking (PWSCC) are investigated in this study. Tube sleeves were installed to inhibit leakage and improve tube integrity as a part of maintenance methods. Steam generators occurred small leak during operation have been replaced with new steam generators according to plant maintenance strategies. The correlations between steam generator leakage and chemistry parameters are presented. Effects of primary water chemistry parameters on leakage from tube cracks were investigated for the steam generators experiencing small leak. Unit A experienced small leakage from steam generator tubes in the end of operation cycle. It was concluded that increased solubility of oxides due to high pHT could make leakage paths, and low boron concentration lead to less blockage in cracks. Increased dissolved hydrogen may retard crack propagations, but it did not reduce leak rate of the leaking steam generator. In order to inhibit and reduce leakage, pH_T was controlled by servicing cation bed operation. The test results of decreasing pHT indicate low pHT can reduce leak rate of PWSCC cracks in the end of cycle

  15. Impact of the economic downturn on total joint replacement demand in the United States: updated projections to 2021.

    Science.gov (United States)

    Kurtz, Steven M; Ong, Kevin L; Lau, Edmund; Bozic, Kevin J

    2014-04-16

    Few studies have explored the role of the National Health Expenditure and macroeconomics on the utilization of total joint replacement. The economic downturn has raised questions about the sustainability of growth for total joint replacement in the future. Previous projections of total joint replacement demand in the United States were based on data up to 2003 using a statistical methodology that neglected macroeconomic factors, such as the National Health Expenditure. Data from the Nationwide Inpatient Sample (1993 to 2010) were used with United States Census and National Health Expenditure data to quantify historical trends in total joint replacement rates, including the two economic downturns in the 2000s. Primary and revision hip and knee arthroplasty were identified using codes from the International Classification of Diseases, Ninth Revision, Clinical Modification. Projections in total joint replacement were estimated using a regression model incorporating the growth in population and rate of arthroplasties from 1993 to 2010 as a function of age, sex, race, and census region using the National Health Expenditure as the independent variable. The regression model was used in conjunction with government projections of National Health Expenditure from 2011 to 2021 to estimate future arthroplasty rates in subpopulations of the United States and to derive national estimates. The growth trend for the incidence of joint arthroplasty, for the overall United States population as well as for the United States workforce, was insensitive to economic downturns. From 2009 to 2010, the total number of procedures increased by 6.0% for primary total hip arthroplasty, 6.1% for primary total knee arthroplasty, 10.8% for revision total hip arthroplasty, and 13.5% for revision total knee arthroplasty. The National Health Expenditure model projections for primary hip replacement in 2020 were higher than a previously projected model, whereas the current model estimates for total

  16. Preliminary design study of removable integral steam generator units of the multiple helically wound tube type for a 1250 MW(th) H.T.G.C. reactor

    International Nuclear Information System (INIS)

    Gilli, P.V.; Fritz, K.; Lippitsch, J.; Sandri, A.H.; Weiss, B.

    1965-11-01

    The possibilities of designing a multiple steam generator for a 1250 MW(th) High Temperature Gas-Cooled Reactor, consisting of 18 units which are able to pass through 5 ft diam. holes in the integral prestressed concrete pressure vessel are investigated. A lay-out and design with bundles of multi-start helical tubes is evolved, particular attention being paid to the questions of tube blanking and removal of the unit, and of selection of materials for superheater and reheater tubes. Thermal and stress calculations have been carried out, using the Waagner-Biro Computer Code ADURHELIX. (author)

  17. Safety evaluation report related to the operation of Susquehanna Steam Electric Station, Units 1 and 2 (Docket Nos. 50-387 and 50-388). Suppl.6

    International Nuclear Information System (INIS)

    1984-03-01

    In April 1981, the staff of the Nuclear Regulatory Commission issued its Safety Evaluation Report (NUREG-0776) regarding the application of the Pennsylvania Power and Light Company (the applicant and/or licensee) and the Allegheny Electric Cooperative, Inc. (co-applicant) for licenses to operate the Susquehanna Steam Electric Station, Units 1 and 2, located on a site in Luzerne County, Pennsylvania. This supplement to NUREG-0776 addresses the remaining issues that required resolution before licensing operation of Unit 2 and closes them out

  18. 24 CFR 42.375 - One-for-one replacement of lower-income dwelling units.

    Science.gov (United States)

    2010-04-01

    ... related to the conversion. (5) The units must be designed to remain lower-income dwelling units for at... result in the demolition of lower-income dwelling units or the conversion of lower-income dwelling units...-income dwelling units. 42.375 Section 42.375 Housing and Urban Development Office of the Secretary...

  19. Final environmental statement related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2: (Docket Nos. 50-445 and 50-446)

    International Nuclear Information System (INIS)

    1981-09-01

    The proposed action is the issuance of operating licenses to the Texas Utilities Generating Company for the startup and operation of Units 1 and 2 of the Comanche Peak Steam Electric Station located on Squaw Creek Reservoir in Somervell County, Texas, about 7 km north-northeast of Glen Rose, Texas, and about 65 km southwest of Fort Worth in north-central Texas. The information in this environmental statement represents the second assessment of the environmental impact associated with the Comanche Peak Steam Electric Station pursuant to the guidelines of the National Environmental Policy Act of 1969 (NEPA) and 10 CFR Part 51 of the Commission's Regulations. After receiving an application to construct this station, the staff carried out a review of impact that would occur during its construction and operation. This evaluation was issued as a Final Environmental Statement -- Construction Phase. After this environmental review, a safety review, an evaluation by the Advisory Committee on Reactor Safeguards, and public hearings in Glen Rose, Texas, the US Atomic Energy Commission (now US Nuclear Regulatory Commission) issued construction permits for the construction of Units 1 and 2 of the Comanche Peak Steam Electric Station. 16 figs., 34 tabs

  20. Steam drums

    International Nuclear Information System (INIS)

    Crowder, R.

    1978-01-01

    Steam drums are described that are suitable for use in steam generating heavy water reactor power stations. They receive a steam/water mixture via riser headers from the reactor core and provide by means of separators and driers steam with typically 0.5% moisture content for driving turbines. The drums are constructed as prestressed concrete pressure vessels in which the failure of one or a few of the prestressing elements does not significantly affect the overall strength of the structure. The concrete also acts as a radiation shield. (U.K.)

  1. Maintenance or replacement of primary equipments

    International Nuclear Information System (INIS)

    Branchu, J.

    1995-01-01

    The principal materials, such as the primary equipments of a PWR type steam generator, have a finite service life. Framatome, builder of steam generators and maintenance contractor of Electricite de France has developed a methodology for the maintenance or the replacement of primary equipments. The paper describes the methodology followed by Framatome to identify and localize the wear mode and to treat or repair the component. Four failure modes have been considered: crack propagation, rubbing/vibration wear, neutron irradiation and corrosion propagation under permanent stress. A kinetic modelling of wear propagation has been computerized and validated using mechanical tests on Inconel 600 mockups. These analyses have allow to determine the strategy of repair or replacement of vessel heads for each unit. The method is evaluated taking into account the risk assessment, cost, dosimetry, efficiency and time delay involved. (J.S.). 1 fig., 3 photos

  2. Description of the attitude control, guidance and navigation space replaceable units for automated space servicing of selected NASA missions

    Science.gov (United States)

    Chobotov, V. A.

    1974-01-01

    Control elements such as sensors, momentum exchange devices, and thrusters are described which can be used to define space replaceable units (SRU), in accordance with attitude control, guidance, and navigation performance requirements selected for NASA space serviceable mission spacecraft. A number of SRU's are developed, and their reliability block diagrams are presented. An SRU assignment is given in order to define a set of feasible space serviceable spacecraft for the missions of interest.

  3. Steam 80 steam generator instrumentation

    International Nuclear Information System (INIS)

    Carson, W.H.; Harris, H.H.

    1980-01-01

    This paper describes two special instrumentation packages in an integral economizer (preheater) steam generator of one of the first System 80 plants scheduled to go into commercial operation. The purpose of the instrumentation is to obtain accurate operating information from regions of the secondary side of the steam generator inaccessible to normal plant instrumentation. In addition to verification of the System 80 steam generator design predictions, the data obtained will assist in verification of steam generator thermal/hydraulic computer codes developed for generic use in the industry

  4. Africanization in the United States: replacement of feral European honeybees (Apis mellifera L.) by an African hybrid swarm.

    Science.gov (United States)

    Pinto, M Alice; Rubink, William L; Patton, John C; Coulson, Robert N; Johnston, J Spencer

    2005-08-01

    The expansion of Africanized honeybees from South America to the southwestern United States in feral population from the southern United States undergoing Africanization. Our microsatellite data showed that (1) the process of Africanization involved both maternal and paternal bidirectional gene flow between European and Africanized honeybees and (2) the panmitic European population was replaced by panmitic mixtures of A. m. scutellata and European genes within 5 years after Africanization. The post-Africanization gene pool (1998-2001) was composed of a diverse array of recombinant classes with a substantial European genetic contribution (mean 25-37%). Therefore, the resulting feral honeybee population of south Texas was best viewed as a hybrid swarm.

  5. Selling steam

    International Nuclear Information System (INIS)

    Zimmer, M.J.; Goodwin, L.M.

    1991-01-01

    This article addresses the importance of steam sales contract is in financing cogeneration facilities. The topics of the article include the Public Utility Regulatory Policies Act provisions and how they affect the marketing of steam from qualifying facilities, the independent power producers market shift, and qualifying facility's benefits

  6. Steam generator

    International Nuclear Information System (INIS)

    Fenet, J.-C.

    1980-01-01

    Steam generator particularly intended for use in the coolant system of a pressurized water reactor for vaporizing a secondary liquid, generally water, by the primary cooling liquid of the reactor and comprising special arrangements for drying the steam before it leaves the generator [fr

  7. Steam condenser

    International Nuclear Information System (INIS)

    Masuda, Fujio

    1980-01-01

    Purpose: To enable safe steam condensation by providing steam condensation blades at the end of a pipe. Constitution: When high temperature high pressure steam flows into a vent pipe having an opening under water in a pool or an exhaust pipe or the like for a main steam eacape safety valve, non-condensable gas filled beforehand in the steam exhaust pipe is compressed, and discharged into the water in the pool. The non-condensable gas thus discharged from the steam exhaust pipe is introduced into the interior of the hollow steam condensing blades, is then suitably expanded, and thereafter exhausted from a number of exhaust holes into the water in the pool. In this manner, the non-condensable gas thus discharged is not directly introduced into the water in the pool, but is suitable expanded in the space of the steam condensing blades to suppress extreme over-compression and over-expansion of the gas so as to prevent unstable pressure vibration. (Yoshihara, H.)

  8. Feed water distribution pipe replacement at Loviisa NPP

    Energy Technology Data Exchange (ETDEWEB)

    Savolainen, S.; Elsing, B. [Imatran Voima Loviisa NPP (Finland)

    1995-12-31

    Imatran Voima Oy operates two WWER-440 reactors. Unit 1 has been operating since 1977 and unit 2 since 1981. First damages of feed water distribution (FWD) pipe were observed in 1989. The FWD-pipe T-connection had suffered from severe erosion corrosion damages. Similar damages have been been found also in other WWER-440 type NPPs. In 1989 the nozzles of the steam generator YB11 were inspected. No signs of the damages or signs of erosion were detected. The first damaged nozzles were found in 1992 in steam generators of both units. In 1992 it was started studying different possibilities to either repair or replace the damaged FWD-pipes. Due to the difficult conditions for repairing the damaged nozzles it was decided to study different FWD-pipe constructions. In 1991 two new feedwater distributors had been implemented at Dukovany NPP designed by Vitckovice company. Additionally OKB Gidropress had presented their design for new collector. In spring 1994 all the six steam generators of Rovno NPP unit 1 were replaced with FWD-pipes designed by OKB Gidropress. After the implementation an experimental program with the new systems was carried out. Due to the successful experiments at Rovno NPP Unit 1 it was decided to implement `Gidropress solution` during 1994 refueling outage into the steam generator YB52 at Loviisa 2. The object of this paper is to discuss the new FWD-pipe and its effects on the plant safety during normal and accident conditions. (orig.).

  9. Feed water distribution pipe replacement at Loviisa NPP

    Energy Technology Data Exchange (ETDEWEB)

    Savolainen, S; Elsing, B [Imatran Voima Loviisa NPP (Finland)

    1996-12-31

    Imatran Voima Oy operates two WWER-440 reactors. Unit 1 has been operating since 1977 and unit 2 since 1981. First damages of feed water distribution (FWD) pipe were observed in 1989. The FWD-pipe T-connection had suffered from severe erosion corrosion damages. Similar damages have been been found also in other WWER-440 type NPPs. In 1989 the nozzles of the steam generator YB11 were inspected. No signs of the damages or signs of erosion were detected. The first damaged nozzles were found in 1992 in steam generators of both units. In 1992 it was started studying different possibilities to either repair or replace the damaged FWD-pipes. Due to the difficult conditions for repairing the damaged nozzles it was decided to study different FWD-pipe constructions. In 1991 two new feedwater distributors had been implemented at Dukovany NPP designed by Vitckovice company. Additionally OKB Gidropress had presented their design for new collector. In spring 1994 all the six steam generators of Rovno NPP unit 1 were replaced with FWD-pipes designed by OKB Gidropress. After the implementation an experimental program with the new systems was carried out. Due to the successful experiments at Rovno NPP Unit 1 it was decided to implement `Gidropress solution` during 1994 refueling outage into the steam generator YB52 at Loviisa 2. The object of this paper is to discuss the new FWD-pipe and its effects on the plant safety during normal and accident conditions. (orig.).

  10. Steam generator reliability improvement project

    International Nuclear Information System (INIS)

    Blomgren, J.C.; Green, S.J.

    1987-01-01

    Upon successful completion of its research and development technology transfer program, the Electric Power Research Institute's Steam Generator Owners Group (SGOG II) will disband in December 1986 and be replaced in January 1987 by a successor project, the Steam Generator Reliability Project (SGRP). The new project, funded in the EPRI base program, will continue the emphasis on reliability and life extension that was carried forward by SGOG II. The objectives of SGOG II have been met. Causes and remedies have been identified for tubing corrosion problems, such as stress corrosion cracking and pitting, and steam generator technology has been improved in areas such as tube wear prediction and nondestructive evaluation (NDE). These actions have led to improved reliability of steam generators. Now the owners want to continue with a centrally managed program that builds on what has been learned. The goal is to continue to improve steam generator reliability and solve small problems before they become large problems

  11. Steam generator reliability improvement project

    International Nuclear Information System (INIS)

    Blomgren, J.C.; Green, S.J.

    1987-01-01

    Upon successful completion of its research and development technology transfer program, the Electric Power Research Institute's (EPRI's) Steam Generator Owners Group (SGOG II) will disband in December 1986, and be replaced in January 1987, by a successor project, the Steam Generator Reliability Project (SGRP). The new project, funded in the EPRI base program, will continue to emphasize reliability and life extension, which were carried forward by SGOG II. The objectives of SGOG II have been met. Causes and remedies have been identified for tubing corrosion problems such as stress corrosion cracking and pitting, and steam generator technology has been improved in areas such as tube wear prediction and nondestructive evaluation. These actions have led to improved reliability of steam generators. Now the owners want to continue with a centrally managed program that builds on what has been learned. The goal is to continue to improve steam generator reliability and to solve small problems before they become large problems

  12. Steam generator tube integrity program

    International Nuclear Information System (INIS)

    Dierks, D.R.; Shack, W.J.; Muscara, J.

    1996-01-01

    A new research program on steam generator tubing degradation is being sponsored by the U.S. Nuclear Regulatory Commission (NRC) at Argonne National Laboratory. This program is intended to support a performance-based steam generator tube integrity rule. Critical areas addressed by the program include evaluation of the processes used for the in-service inspection of steam generator tubes and recommendations for improving the reliability and accuracy of inspections; validation and improvement of correlations for evaluating integrity and leakage of degraded steam generator tubes, and validation and improvement of correlations and models for predicting degradation in steam generator tubes as aging occurs. The studies will focus on mill-annealed Alloy 600 tubing, however, tests will also be performed on replacement materials such as thermally-treated Alloy 600 or 690. An overview of the technical work planned for the program is given

  13. Optimal replacement and inspection periods of safety and control boards in Wolsung nuclear power plant unit 1

    International Nuclear Information System (INIS)

    Mok, Jin Il

    1993-02-01

    In nuclear power plants, the safety and control systems are important for operating and maintaining safety of nuclear power plants. Due to the failure of the instrument and control devices of nuclear power plants caused by aging, nuclear power plants occasionally trip. Since the start of first commercial operation of Kori nuclear power plant (NPP) unit 1, the trips caused by instrument and control systems account for 28% of total trips of NPPs in Korea. Even a single trip of a nuclear power plant causes an extravagant economical loss and deteriorates public acceptance of nuclear power plants. Therefore, the replacement of the instrument and control devices with proper consideration of the aging effect is necessary in order to prevent the inadvertent trip. In this work we investigated the optimal replacement periods of the digital control computer's (DCC) and the programmable digital comparator's (PDC) electronic circuit boards of Wolsung nuclear power plant Unit 1. We first derived mathematical models which calculate optimal replacement periods for electronic circuit boards of digital control computer (DCC) and for those of the programmable digital comparator (PDC) in Wolsung NPP unit 1. And we analytically obtained the optimal replacement periods of electronic circuit boards by using these models. We compared these periods with the replacement periods currently used at Wolsung NPP Unit. The periods used at Wolsung is not based on mathematical analysis, but on empirical knowledge. As a consequence, the optimal replacement periods analytically obtained for the electronic circuit boards of DCC and those used in the field shown small difference : the optimal replacement periods analytically obtained for the electronic circuit boards of PDC are shorter than those used in the field in general. The engineered safeguards of Wolsung nuclear power plant unit 1 contains redundant systems of 2-out-of-3 logic which are not operating under normal conditions but they are called

  14. Passive system with steam-water injector for emergency supply of NPP steam generators

    International Nuclear Information System (INIS)

    Il'chenko, A.G.; Strakhov, A.N.; Magnitskij, D.N.

    2009-01-01

    The calculation results of reliability indicators of emergency power supply system and emergency feed-water supply system of serial WWER-1000 unit are presented. To ensure safe water supply to steam generators during station blackout it was suggested using additional passive emergency feed-water system with a steam-water injector working on steam generators dump steam. Calculated analysis of steam-water injector operating capacity was conducted at variable parameters of steam at the entrance to injector, corresponding to various moments of time from the beginning of steam-and-water damping [ru

  15. Nuclear facilities: repair and replacement technologies

    International Nuclear Information System (INIS)

    2005-01-01

    The oldest operating reactors are more than 35 years old and are now facing major maintenance operations. The first replacement of a pressurizer took place in autumn 2005 at the St-Lucie plant (Usa) while steam generators have been currently replaced since 1983. Nuclear industry has to adapt to this new market by proposing innovative technological solutions in the reactor maintenance field. This document gathers the 9 papers presented at the conference. The main improvements concern repair works on internal components of PWR-type reactors, the replacement of major components of the primary coolant circuit and surface treatments to limit the propagation of damages. The first paper shows that adequate design and feedback experience are good assets to manage the ageing of a nuclear unit. Another paper shows that a new repair method of a relief valve can avoid its replacement. (A.C.)

  16. Safety Evaluation Report related to the operation of Waterford Steam Electric Station, Unit No. 3 (Docket No. 50-382). Supplement No. 8

    International Nuclear Information System (INIS)

    1984-12-01

    Supplement 8 to the Safety Evaluation Report for the application filed by Louisiana Power and Light Company for a license to operate the Waterford Steam Electric Station, Unit 3 (Docket No. 50-382), located in St. Charles Parish, Louisiana, has been prepared by the Office of Nuclear Reactor Regulation of the Nuclear Regulatory Commission. The purpose of this supplement is to update the Safety Evaluation Report by providing the staff's evaluation of information submitted by the applicant since the Safety Evaluation Report and its seven previous supplements were issued

  17. Safety-evaluation report related to the operation of Waterford Steam Electric Station, Unit No. 3. Docket No. 50-382

    International Nuclear Information System (INIS)

    1983-06-01

    Supplement 5 to the Safety Evaluation Report for the application filed by Louisiana Power and Light Company for a license to operate the Waterford Steam Electric Station, Unit 3 (Docket No. 50-382), located in St. Charles Parish, Louisiana has been prepared by the Office of Nuclear Reactor Regulation of the Nuclear Regulatory Commission. The purpose of this supplement is to update the Safety Evaluation Report by providing the staff's evaluation of information submitted by the applicant since the Safety Evaluation Report and its four previous Supplements were issued

  18. Safety evaluation report related to the operation of Waterford Steam Electric Station, Unit No. 3 (Docket No. 50-382). Suppl.6

    International Nuclear Information System (INIS)

    1984-06-01

    Supplement 6 to the Safety Evaluation Report for the application filed by Louisiana Power and Light Company for a license to operate the Waterford Steam Electric Station, Unit 3 (Docket No. 50-382), located in St. Charles Parish, Louisiana, has been prepared by the Office of Nuclear Reactor Regulation of the Nuclear Regulatory Commission. The purpose of this supplement is to update the Safety Evaluation Report by providing the staff's evaluation of information submitted by the applicant since the Safety Evaluation Report and its five previous supplements were issued

  19. Technical evaluation report on the monitoring of electric power to the reactor-protection system for the Brunswick Steam Electric Plant, Units 1 and 2

    International Nuclear Information System (INIS)

    Selan, J.C.

    1982-01-01

    This report documents the technical evaluation of the monitoring of electric power to the reactor protection system (RPS) at the Brunswick Steam Electric Plant, Units 1 and 2. The evaluation is to determine if the proposed design modification will protect the RPS from abnormal voltage and frequency conditions which could be supplied from the power supplies and will meet certain requirements set forth by the Nuclear Regulatory Commission. The proposed design modifications with time delays verified by GE, will protect the RPS from sustained abnormal voltage and frequency conditions from the supplying sources

  20. Safety Evaluation Report related to the operation of Waterford Steam Electric Station, Unit No. 3 (Docket No. 50-382). Supplement 9

    International Nuclear Information System (INIS)

    1984-12-01

    Supplement 9 to the Safety Evaluation Report for Louisiana Power and Light's application for a license to operate Waterford Steam Electric Station, Unit 3 (Docket No. 50-382), located in St. Charles Parish, Louisiana, has been jointly prepared by the Office of Nuclear Reactor Regulation and the Region IV Office of the US Nuclear Regulatory Commission. This supplement provides the results of the staff's completion of its evaluation of approximately 350 allegations and concerns of poor construction practices at the Waterford 3 facility

  1. Steam turbines for the future

    International Nuclear Information System (INIS)

    Trassl, W.

    1988-01-01

    Approximately 75% of the electrical energy produced in the world is generated in power plants with steam turbines (fossil and nuclear). Although gas turbines are increasingly applied in combined cycle power plants, not much will change in this matter in the future. As far as the steam parameters and the maximum unit output are concerned, a certain consolidation was noted during the past decades. The standard of development and mathematical penetration of the various steam turbine components is very high today and is applied in the entire field: For saturated steam turbines in nuclear power plants and for steam turbines without reheat, with reheat and with double reheat in fossil-fired power plants and for steam turbines with and without reheat in combined cycle power plants. (orig.) [de

  2. United States Advanced Ultra-Supercritical Component Test Facility for 760°C Steam Power Plants ComTest Project

    Energy Technology Data Exchange (ETDEWEB)

    Hack, Horst [Electric Power Research Institute (EPRI); Purgert, Robert Michael [Energy Industries of Ohio

    2017-12-13

    Following the successful completion of a 15-year effort to develop and test materials that would allow coal-fired power plants to be operated at advanced ultra-supercritical (A-USC) steam conditions, a United States-based consortium is presently engaged in a project to build an A-USC component test facility (ComTest). A-USC steam cycles have the potential to improve cycle efficiency, reduce fuel costs, and reduce greenhouse gas emissions. Current development and demonstration efforts are focused on enabling the construction of A-USC plants, operating with steam temperatures as high as 1400°F (760°C) and steam pressures up to 5000 psi (35 MPa), which can potentially increase cycle efficiencies to 47% HHV (higher heating value), or approximately 50% LHV (lower heating value), and reduce CO2 emissions by roughly 25%, compared to today’s U.S. fleet. A-USC technology provides a lower-cost method to reduce CO2 emissions, compared to CO2 capture technologies, while retaining a viable coal option for owners of coal generation assets. Among the goals of the ComTest facility are to validate that components made from advanced nickel-based alloys can operate and perform under A-USC conditions, to accelerate the development of a U.S.-based supply chain for the full complement of A-USC components, and to decrease the uncertainty of cost estimates for future A-USC power plants. The configuration of the ComTest facility would include the key A-USC technology components that were identified for expanded operational testing, including a gas-fired superheater, high-temperature steam piping, steam turbine valve, and cycling header component. Membrane walls in the superheater have been designed to operate at the full temperatures expected in a commercial A-USC boiler, but at a lower (intermediate) operating pressure. This superheater has been designed to increase the temperature of the steam supplied by the host utility boiler up to 1400°F (760

  3. Potential nutritional and economic effects of replacing juice with fruit in the diets of children in the United States.

    Science.gov (United States)

    Monsivais, Pablo; Rehm, Colin D

    2012-05-01

    To estimate the nutritional and economic effects of substituting whole fruit for juice in the diets of children in the United States. Secondary analyses using the 2001-2004 National Health and Nutrition Examination Survey and a national food prices database. Energy intakes, nutrient intakes, and diet costs were estimated before and after fruit juices were completely replaced with fruit in 3 models that emphasized fruits that were fresh, inexpensive, and widely consumed and in a fourth model that partially replaced juice with fruit, capping juice at recommended levels. A nationwide, representative sample of children in the United States. A total of 7023 children aged 3 to 18 years. Systematic complete or partial replacement of juice with fruit. Difference in energy intakes, nutrient intakes, and diet costs between observed and modeled diets. For children who consumed juice, replacement of all juice servings with fresh, whole fruit led to a projected reduction in dietary energy of 233 kJ/d (-2.6% difference [95% CI, -5.1% to -0.1%]), an increase in fiber of 4.3 g/d (31.1% difference [95% CI, 26.4%-35.9%]), and an increase in diet cost of $0.54/d (13.3% difference [95% CI, 8.8%-17.8%]). Substitution of juice with fresh fruit has the potential to reduce energy intake and improve the adequacy of fiber intake in children's diets. This would likely increase costs for schools, childcare providers, and families. These cost effects could be minimized by selecting processed fruits, but fewer nutritional gains would be achieved.

  4. Simulation and design of distillation units for treatment of sulfite pulping condensates to recover methanol and furfural. Part I. Incorporation with an evaporation unit and use of secondary steam

    Energy Technology Data Exchange (ETDEWEB)

    Zacchi, G.; Aly, G.

    1979-06-01

    A distillation unit was simulated using DESTLA, a computer program for steady-state calculations of general multicomponent distillation units. Vapor-liquid and liquid-liquid equilibria were both computed by EQUIL, a computer program for computation and plotting of such equilibria. The simulations resulted in a distillation unit consisting of three columns. Energy consumed in the first column dominates the operating costs of the unit. The first of the three different alternatives studied for satisfying the energy requirements of the first column is presented. Incorporating the first column into an evaporation unit yields low steam consumption. However, a decrease in evaporation capacity due to the temperature drop in the first column and complex control design are the disadvantages associated with this alternative.

  5. Electrosleeve process for in-situ nuclear steam generator repair

    International Nuclear Information System (INIS)

    Renaud, E.; Brennenstuhl, A.M.; Stewart, D.R.; Gonzalez, F.

    2000-01-01

    Degradation of steam generator tubing by localized corrosion is a widespread problem in the nuclear industry that can lead to costly forced outages, unit derating, steam generator replacement or even the permanent shutdown of a reactor. In response to the onset of steam generator degradation at Ontario Power Generation's Pickering Nuclear Generating Station (PNGS) Unit 5, and the determined unsuitability of conventional repair methods (mechanically expanded or welded sleeves) for Alloy 400, an alternative repair technology was developed. Electrosleeve is a non-intrusive, low-temperature process that involves the electrodeposition of a nanocrystalline nickel microalloy forming a continuously bonded, structural layer over the internal diameter of the degraded region. This technology is designed to provide a long-term pressure boundary repair, fully restoring the structural integrity of the damaged region to its original state. This paper describes the Electrosleeve process for steam generator tubing repair and the unique properties of the advanced sleeve material. The successful installation of fourteen Electrosleeves that have been in service for more than six years in Alloy 400 tubing at the Pickering-S CANDU unit, and the more recent (Nov. 99) extension of the technology to Alloy 600 by the installation of 57 sleeves in a U.S. pressurized water reactor (PWR) at Callaway, is presented. The Electrosleeve process has been granted a conditional license by the U.S. Nuclear Regulatory Commission (NRC). In Canada, the process of licensing Electrosleeve with the CNSC / TSSA has begun. (author)

  6. Simulation and design of distillation units for treatment of sulfite pulping condensates to recover methanol and furfural. Part II. Applicability of multiple-effect distillation using live steam

    Energy Technology Data Exchange (ETDEWEB)

    Aly, G.; Zacchi, G.

    1979-06-01

    A distillation unit has been designed for a capacity of 73 t/h of condensate and for at least 90% recovery of the contaminating organics. This unit consists of three columns: a primary stripper to remove volatile organics and two upgrading columns to purify the methanol and furfural byproducts. Three different energy-saving alternatives for satisfying the energy requirements have been studied: utilisation of secondary steam from the evaporation plant, and application of the principle of multi-effect distillation in one-stripper and in two-stripper configurations. Investment cost needed in all alternatives amounts to 5.5 to 6.0 MCr (millions of Swedish Crowns) while operating cost varies between 0.8 to 3.1 MCr. The first design alternative has a payoff period of 2.3 years while the two multi-effect distillation alternatives have a payoff period of about 3 years.

  7. A fast prediction of plant behaviour in the steam generator tube rupture accident at Mihama unit 2 using a similar case

    International Nuclear Information System (INIS)

    Gofuku, Akio; Tanaka, Yutaka; Numoto, Atsushi; Yoshikawa, Hidekazu.

    1996-01-01

    It is important to predict fast and accurately future trend of behaviour of a nuclear power plant in an emergency situation. The case-based reasoning is a strong tool for this purpose because it solves a problem by effectively using past similar cases. This study investigates the applicability of the case-based reasoning as a fast prediction technique of plant behaviour. This paper discusses a prediction of initial plant behaviour in the steam generator tube rupture accident happened at the Mihama nuclear power plant unit 2 by using the behaviour data of an accident of the same type happened at Prairie Island nuclear power plant unit 1. The prediction results coincide well with the reported plant behaviour although there are several important differences in the detailed plant specifications and operator actions between the two SGTR accidents. (author)

  8. Third international seminar on horizontal steam generators

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-12-31

    The Third International Seminar on Horizontal Steam Generators held on October 18-20, 1994 in Lappeenranta, consisted of six sessions dealing with the topics: thermal hydraulic experiments and analyses, primary collector integrity, management of primary-to-secondary leakage accidents, feedwater collector replacement and discussion of VVER-440 steam generator safety issues.

  9. Third international seminar on horizontal steam generators

    International Nuclear Information System (INIS)

    1995-01-01

    The Third International Seminar on Horizontal Steam Generators held on October 18-20, 1994 in Lappeenranta, consisted of six sessions dealing with the topics: thermal hydraulic experiments and analyses, primary collector integrity, management of primary-to-secondary leakage accidents, feedwater collector replacement and discussion of VVER-440 steam generator safety issues

  10. Third international seminar on horizontal steam generators

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-12-31

    The Third International Seminar on Horizontal Steam Generators held on October 18-20, 1994 in Lappeenranta, consisted of six sessions dealing with the topics: thermal hydraulic experiments and analyses, primary collector integrity, management of primary-to-secondary leakage accidents, feedwater collector replacement and discussion of VVER-440 steam generator safety issues.

  11. STEAM GENERATOR TUBE INTEGRITY ANALYSIS OF A TOTAL LOSS OF ALL HEAT SINKS ACCIDENT FOR WOLSONG NPP UNIT 1

    Directory of Open Access Journals (Sweden)

    HEOK-SOON LIM

    2014-02-01

    Full Text Available A total loss of all heat sinks is considered a severe accident with a low probability of occurrence. Following a total loss of all heat sinks, the degasser/condenser relief valves (DCRV become the sole means available for the depressurization of the primary heat transport system. If a nuclear power plant has a total loss of heat sinks accident, high-temperature steam and differential pressure between the primary heat transport system (PHTS and the steam generator (SG secondary side can cause a SG tube creep rupture. To protect the PHTS during a total loss of all heat sinks accident, a sufficient depressurization capability of the degasser/condenser relief valve and the SG tube integrity is very important. Therefore, an accurate estimation of the discharge through these valves is necessary to assess the impact of the PHTS overprotection and the SG tube integrity of the primary circuit. This paper describes the analysis of DCRV discharge capacity and the SG tube integrity under a total loss of all heat sink using the CATHENA code. It was found that the DCRV's discharge capacity is enough to protect the overpressure in the PHTS, and the SG tube integrity is maintained in a total loss of all heat accident.

  12. Steam Generator Tube Integrity Analysis of A Total Loss of all Heat Sinks Accident for Wolsong NPP Unit 1

    Energy Technology Data Exchange (ETDEWEB)

    Lim, Heoksoon; Song, Taeyoung; Chi, Moongoo [Korea Htydro and Nuclear Power Co., Ltd., Daejeon (Korea, Republic of); Kim, Seoungrae [Nuclear Engineering Service and Solution, Daejeon (Korea, Republic of)

    2014-02-15

    A total loss of all heat sinks is considered a severe accident with a low probability of occurrence. Following a total loss of all heat sinks, the degasser/condenser relief valves (DCRV) become the sole means available for the depressurization of the primary heat transport system. If a nuclear power plant has a total loss of heat sinks accident, high-temperature steam and differential pressure between the primary heat transport system (PHTS) and the steam generator (SG) secondary side can cause a SG tube creep rupture. To protect the PHTS during a total loss of all heat sinks accident, a sufficient depressurization capability of the degasser/condenser relief valve and the SG tube integrity is very important. Therefore, an accurate estimation of the discharge through these valves is necessary to assess the impact of the PHTS overprotection and the SG tube integrity of the primary circuit. This paper describes the analysis of DCRV discharge capacity and the SG tube integrity under a total loss of all heat sink using the CATHENA code. It was found that the DCRV's discharge capacity is enough to protect the overpressure in the PHTS, and the SG tube integrity is maintained in a total loss of all heat accident.

  13. Steam Generator Tube Integrity Analysis of A Total Loss of all Heat Sinks Accident for Wolsong NPP Unit 1

    International Nuclear Information System (INIS)

    Lim, Heoksoon; Song, Taeyoung; Chi, Moongoo; Kim, Seoungrae

    2014-01-01

    A total loss of all heat sinks is considered a severe accident with a low probability of occurrence. Following a total loss of all heat sinks, the degasser/condenser relief valves (DCRV) become the sole means available for the depressurization of the primary heat transport system. If a nuclear power plant has a total loss of heat sinks accident, high-temperature steam and differential pressure between the primary heat transport system (PHTS) and the steam generator (SG) secondary side can cause a SG tube creep rupture. To protect the PHTS during a total loss of all heat sinks accident, a sufficient depressurization capability of the degasser/condenser relief valve and the SG tube integrity is very important. Therefore, an accurate estimation of the discharge through these valves is necessary to assess the impact of the PHTS overprotection and the SG tube integrity of the primary circuit. This paper describes the analysis of DCRV discharge capacity and the SG tube integrity under a total loss of all heat sink using the CATHENA code. It was found that the DCRV's discharge capacity is enough to protect the overpressure in the PHTS, and the SG tube integrity is maintained in a total loss of all heat accident

  14. Analisis Safety System dan Manajemen Risiko pada Steam Boiler PLTU di Unit 5 Pembangkitan Paiton, PT. YTL

    Directory of Open Access Journals (Sweden)

    Luluk Kristianingsih

    2013-09-01

    Full Text Available Pembangkit listrik tenaga uap (PLTU merupakan pembangkit listrik yang banyak digunakan di Indonesia. Salah satu bagian dari sistem PLTU yang memiliki risiko bahaya tinggi adalah boiler, oleh karena itu diperlukan adanya analisis bahaya dan safety system sebagai langkah pencegahan bahaya pada boiler. Analisis bahaya dalam penelitian ini dilakukan menggunakan metode HAZOP. Node yang dipakai adalah economizer, steam drum, superheater, dan reheater yang merupakan komponen utama penyusun boiler. Guide word dan deviasi ditentukan berdasarkan control chart yang dibentuk oleh data proses masing-masing komponen selama bulan Maret 2013. Estimasi likelihood dilakukan berdasarkan data maintenance dari work order PT YTL selama 5 tahun, sedangkan estimasi consequences dilakukan berdasarkan kriteria risiko yang ditimbulkan serta berdasarkan control chart. Hasil perkalian likelihood dan consequences dengan risk matrix menghasilkan kriteria risiko dari komponen. Berdasarkan hasil analisis, diperoleh hasil bahwa komponen yang memiliki risiko bahaya paling besar adalah level transmitter steam drum dengan deviasi berupa less level, yaitu dengan kriteria likelihood adalah A dan consequences 4, sehingga risiko bernilai extreme. Selain itu, risiko extreme juga terdapat pada pressure transmitter outlet superheater, dengan likelihood B dan consequences 4. Untuk menurunkan risiko, maka dilakukan perawatan dan kalibrasi secara rutin, serta penambahan redundant transmitter. Bahaya paling besar pada seluruh node adalah adanya kebakaran. Oleh karena itu, dilakukan analisis emergency response plan untuk kebakaran yang mencakup peta evakuasi, tugas dan tanggungjawab tiap personel, langkah pencegahan, serta langkah penanganan.

  15. Final environmental statement related to the operation of H.B. Robinson Nuclear Steam-Electric Plant, Unit 2: (Docket No. 50-261)

    International Nuclear Information System (INIS)

    1975-04-01

    The proposed action is the continuation of Facility Operating License DPR-23 to Carolina Power and Light Company for H.B. Robinson Unit 2. Unit 2, located adjacent to Lake Robinson in Darlington County, near Hartsville, South Carolina, employs a pressurized water reactor to produce up to 2200 megawatts thermal (MWt). A steam turbine-generator uses this heat to provide 700 megawatts electric (MWe) of net electrical power capacity. A design power level of 2300 MWt (730 MWe) has been requested and is considered in the assessments contained in this statement. The exhaust steam is cooled by a flow of water obtained from the discharged to a 2250-acre cooling lake, Lake Robinson. Land areas disturbed during construction of the plant, but not used, have been seeded to native grasses, trees, and shrubs. Construction of a cooling water discharge canal extension resulted in alteration of about 100 acres of wildlife habitat. Subsequently, the canal banks were seeded with pines and legumes. Some erosion has taken place in the pine-seeded areas. Some small fish are killed by impingement on the water intake screens. Organisms passing through the screens very likely do not survive their passage through the circulating water system. Operation of the plant will cause an increase in the temperature of Black Creek below Lake Robinson. A small impact exists due to production and, after processing, disposal or release of sanitary and chemical wastes. Unit 2 may discharge up to 500 pounds/day of chemicals (primarily sulfates). Under conditions of low flow into and out of the lake, this increases the sulfate concentration in the lake by less than 1 ppM over the normal 7.7 ppM

  16. Steam saving during maintenance of the 50-MW Unit 7 at Los Azufres geothermal field, Michoacan; Ahorro de vapor durante el mantenimiento de la Unidad 7 de 50 MW en el campo geotermico de Los Azufres, Michoacan

    Energy Technology Data Exchange (ETDEWEB)

    Medina Barajas, Elvia Nohemi; Ruiz Lemus, Alejandro [Comision Federal de Electricidad, Gerencia de Proyectos Geotermoelectricos, Residencia de Los Azufres, Morelia, Michoacan (Mexico)]. E-mail: elvia-medina@cfe.gob.mx

    2011-07-15

    Commercial-steam production in the southern area of Los Azufres, Mich., Mexico, Geothermal Field began in 1982 with the operation of Unit 2, the backpressure 5-MW unit, and continued in 1988 when the 50-MW condensing Unit 7 was commissioned. Today to supply steam to Unit 7, it is necessary to gather steam from 15 production wells, amounting 450 tons per hour (t/h) under operating conditions. During maintenance periods for Unit 7, production wells are removed from the steam-supply system but continue producing steam that is discharged to the atmosphere-a loss affecting the economic life of the geothermal reservoir. Therefore several actions have been proposed and tried to save the steam and preserve the geothermal resource. This paper presents the results of the actions and the technical and economic benefits obtained from them. [Spanish] La produccion de vapor con fines comerciales en la zona sur del campo geotermico de Los Azufres, Mich., Mexico, empezo en 1982 con la puesta en marcha de la Unidad 2 de 5 MW a contrapresion, para continuar en 1988 con la Unidad 7 de 50 MW a condensacion. Para cumplir con el suministro de vapor a la U-7, a la fecha es necesario integrar la produccion de 15 pozos productores, que producen un total de 450 toneladas por hora (t/h) a condiciones de operacion. Durante los periodos de mantenimiento de la U-7 los pozos son desintegrados del sistema de suministro, pero continuan produciendo vapor, el cual es descargado a la atmosfera sin ningun provecho, lo que representa una perdida que afecta la vida util del yacimiento geotermico. Por ello se han propuesto y aplicado diversas acciones operativas en cada uno de esos pozos con el objetivo de ahorrar vapor y preservar el recurso geotermico. En este trabajo se presentan los resultados de esas acciones y los beneficios tecnicos y economicos obtenidos.

  17. Safety evaluation report related to steam generator tube repair and return to operation Three Mile Island Nuclear Station, Unit No. 1 (Docket No. 50-289)

    International Nuclear Information System (INIS)

    Silver, H.

    1983-11-01

    Based on our evaluation of the steam generator tube repair method and of subsequent operation using the repaired steam generators, we conclude that the steam generator tube kinetic expansion process is acceptable, that applicable GDC have been met, and that there is reasonable assurance that the health and safety of the public will not be endangered by subsequent operation of the plant

  18. Requalification of the steam supply systems of Units 3 and 4 of the Kozloduy NPP to a new model WWER-440/B-209M

    International Nuclear Information System (INIS)

    Iordanov, I.; Ourutchev, V.; Stoev, M.; Sabinov, S.

    2001-01-01

    In order to achieve significant advances in operational safety level, the project characteristics, the possibility of safety systems upgrading and operational conditions of Units 1 to 4 of the Kozloduy NPP were an object of very serious and in-depth analysis in the years 1990-2000. This systematic evaluation was initiated under the broad international concern resulted from the conclusions of IAEA missions held during 1990-1991 to assess the safety of the units. As a result of the efforts of the plant staff and many international experts the operational conditions, design safety and plant management were dramatically improved which resulted in bringing the plant to a new safety level. This review also developed such that the design safety features of Units 3 and 4 are significantly different from those units of the so-called V-230 group. The principle difference and advantages of Units 3 and 4 design were clarified and confirmed. A review process of the changed status of Units 3 and 4 safety was conducted in 1999-2000 with the help of IAEA experts and the experts of RISKAUDIT and WENRA. The process led to the conclusion that the significance of advantages of the safety level need to be encapsulated within a new safety case and the corresponding set of steps was combined as a 'Project for upgrading the Nuclear Steam Supply System of Units 3 and 4 of Kozloduy NPP to model WWER-440/B-209M'. The completion of the activities under this project is expected in 2002 following the major implementation phase during 2001/2002 units' outages. (author)

  19. Steam generator design requirements for ACR-1000

    International Nuclear Information System (INIS)

    Subash, S.; Hau, K.

    2006-01-01

    Atomic Energy of Canada Limited (AECL) has developed the ACR-1000 (Advanced CANDU Reactor-1000 ) to meet market expectations for enhanced safety of plant operation, high capacity factor, low operating cost, increased operating life, simple component replacement, reduced capital cost, and shorter construction schedule. The ACR-1000 design is based on the use of horizontal fuel channels surrounded by a heavy water moderator, the same feature as in all CANDU reactors. The major innovation in the ACR-1000 is the use of low enriched uranium fuel, and light water as the coolant, which circulates in the fuel channels. This results in a compact reactor core design and a reduction of heavy water inventory, both contributing to a significant decrease in capital cost per MWe produced. The ACR-1000 plant is a two-unit, integrated plant with each unit having a nominal gross output of about 1165 MWe with a net output of approximately 1085 MWe. The plant design is adaptable to a single unit configuration, if required. This paper focuses on the technical considerations that went into developing some of the important design requirements for the steam generators for the ACR-1000 plant and how these requirements are specified in the Technical Specification, which is the governing document for the steam generator (SG) detail design. Layout of these SGs in the plant is briefly described and their impacts on the SG design. (author)

  20. Corrective Action Decision Document (CADD), Area 12 fleet operations steam cleaning discharge area, Nevada Test Site Corrective Action Unit 339

    Energy Technology Data Exchange (ETDEWEB)

    Bonn, J.F.

    1996-12-01

    This Corrective Action Decision Document (CADD) incorporates the methodology used for evaluating the remedial alternatives completed for a former steam cleaning discharge area at the Nevada Test Site (NTS). The former steam cleaning site is located in Area 12, east of the Fleet Operations Building 12-16. The discharge area has been impacted by Resource Conservation and Recovery Act (RCRA) F Listed volatile organic compounds (VOCs) and petroleum hydrocarbons waste. Based upon these findings, resulting from Phase 1 and Phase 2 site investigations, corrective action is required at the site. To determine the appropriate corrective action to be proposed, an evaluation of remedial alternatives was completed. The evaluation was completed using a Corrective Measures Study (CMS). Based on the results of the CMS, the favored closure alternative for the site is plugging the effluent discharge line, removing the sandbagged barrier, completing excavation of VOC impacted soils, and fencing the soil area impacted by total petroleum hydrocarbons (TPH), east of the discharge line and west of the soil berm. Management of the F Listed VOCs are dictated by RCRA. Due to the small volume of impacted soil, excavation and transportation to a Treatment Storage and Disposal Facility (TSDF) is the most practical method of management. It is anticipated that the TPH (as oil) impacted soils will remain in place based upon; the A through K Analysis, concentrations detected (maximum 8,600 milligrams per kilogram), expected natural degradation of the hydrocarbons over time, and the findings of the Phase 2 Investigation that vertical migration has been minimal.

  1. Corrective Action Decision Document (CADD), Area 12 fleet operations steam cleaning discharge area, Nevada Test Site Corrective Action Unit 339

    International Nuclear Information System (INIS)

    Bonn, J.F.

    1996-12-01

    This Corrective Action Decision Document (CADD) incorporates the methodology used for evaluating the remedial alternatives completed for a former steam cleaning discharge area at the Nevada Test Site (NTS). The former steam cleaning site is located in Area 12, east of the Fleet Operations Building 12-16. The discharge area has been impacted by Resource Conservation and Recovery Act (RCRA) F Listed volatile organic compounds (VOCs) and petroleum hydrocarbons waste. Based upon these findings, resulting from Phase 1 and Phase 2 site investigations, corrective action is required at the site. To determine the appropriate corrective action to be proposed, an evaluation of remedial alternatives was completed. The evaluation was completed using a Corrective Measures Study (CMS). Based on the results of the CMS, the favored closure alternative for the site is plugging the effluent discharge line, removing the sandbagged barrier, completing excavation of VOC impacted soils, and fencing the soil area impacted by total petroleum hydrocarbons (TPH), east of the discharge line and west of the soil berm. Management of the F Listed VOCs are dictated by RCRA. Due to the small volume of impacted soil, excavation and transportation to a Treatment Storage and Disposal Facility (TSDF) is the most practical method of management. It is anticipated that the TPH (as oil) impacted soils will remain in place based upon; the A through K Analysis, concentrations detected (maximum 8,600 milligrams per kilogram), expected natural degradation of the hydrocarbons over time, and the findings of the Phase 2 Investigation that vertical migration has been minimal

  2. Flow-induced vibration analysis of Three Mile Island Unit-2 once-through steam generator tubes. Volume 1. Final report

    International Nuclear Information System (INIS)

    Johnson, J.R.; Brown, J.C.; Harris, C.E.; McGuinn, E.J.; Simonis, J.C.; Thoren, D.E.

    1981-06-01

    Tube responses to flow-induced vibration were measured in the top two spans and the tenth span in the B once-through steam generator at Three Mile Island, Unit 2. This program evaluated the effects of flow-induced biration of OTSG tubes during steady-state and transient operation. Twenty-three tubes were instrumented with accelerometers and strain gages in tubes located along the open lane, in the bundle, and at the tenth span. Tube displacements, frequencies, dynamic strains, and mode shapes were determined during steady-state and transient operation. Pressure sensors were installed in the OTSG to measure pressure fluctuations and plant parameters, which were recorded for correlation with tube response. Data analysis results indicate that the steady-state tube response increases with increasing reactor power, with the maximum response (12 mils peak to peak at midspan) at the outer perimeter of the generator in the 16th span

  3. Environmental Assessment for DOE permission for off-loading activities to support the movement of Millstone Unit 2 steam generator sub-assemblies across the Savannah River Site

    International Nuclear Information System (INIS)

    1992-10-01

    The Department of Energy (DOE) has prepared an Environmental Assessment (EA), for the proposed granting of DOE permission of offloading activities to support the movement Millstone Unit 2 steam generator sub-assemblies (SGSAs) across the Savannah River Site (SRS). Based on the analyses in the EA, DOE has determined that the proposed action is not a major Federal action significantly affecting the quality of the human environment within the meaning of the National Environmental Policy Act (NEPA) of 1969. Therefore, an environmental impact statement is not required, and the Department is issuing this Finding of No Significant Impact. On the basis of the floodplain/wetlands assessment in the EA, DOE has determined that there is no practicable alternative to the proposed activities and that the proposed action has been designed to minimize potential harm to or within the floodplain of the SRS boat ramp. No wetlands on SRS would be affected by the proposed action

  4. Safety Evaluation Report related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2. Docket Nos. 50-445 and 50-446

    International Nuclear Information System (INIS)

    1983-03-01

    Supplement No. 3 to the Safety Evaluation Report (SER) related to the operation of the Comanche Peak Steam electric Station, Units 1 and 2, has been prepared by the Office of Nuclear Reactor Regulation of the US Nuclear Regulatory Commission. the facility is located in Somervell County, Texas. Subject to favorable resolution of the items identified in this supplement, the staff concludes that the facility can be operated by the applicatn without endangering the health and safety of the public. This document provides the NRC staff's evaluation of the outstanding and confirmatory issues that have been resolved since Supplement No. 2 was issued in January 1982, and addresses changes to the SER and its earlier supplements which have resulted from the receipt of additonal information from the applicant during the period of January throught October 1982

  5. Steam generators

    International Nuclear Information System (INIS)

    Hayden, R.L.J.

    1979-01-01

    Steam generators for nuclear reactors are designed so that deposition of solids on the surface of the inlet side of the tubesheet or the inlet header with the consequent danger of corrosion and eventual tube failure is obviated or substantially reduced. (U.K.)

  6. Multistate Outbreak of Salmonella Virchow Infections Linked to a Powdered Meal Replacement Product - United States, 2015-2016.

    Science.gov (United States)

    Gambino-Shirley, Kelly J; Tesfai, Adiam; Schwensohn, Colin A; Burnett, Cindy; Smith, Lori; Wagner, Jennifer M; Eikmeier, Dana; Smith, Kirk; Stone, Jolianne P; Updike, Dawn; Hines, Jonas; Shade, Lauren N; Tolar, Beth; Fu, Tong-Jen; Viazis, Stelios; Seelman, Sharon L; Blackshear, Kathryn; Wise, Matthew E; Neil, Karen P

    2018-03-07

    Nontyphoidal Salmonella is the leading cause of bacterial gastroenteritis in the United States. Meal replacement products containing raw and 'superfood' ingredients have gained increasing popularity among consumers in recent years. In January 2016, we investigated a multistate outbreak of infections with a novel strain of Salmonella Virchow. Cases were defined using molecular subtyping procedures. Commonly reported exposures were compared with responses from healthy people interviewed in the 2006-2007 FoodNet Population Survey. Firm inspections and product traceback and testing were performed. Thirty-five cases from 24 states were identified; 6 hospitalizations and no deaths were reported. Thirty-one (94%) of 33 ill people interviewed reported consuming a powdered supplement in the week before illness; of these, 30 (97%) reported consuming Product A, a raw organic powdered shake product consumed as a meal replacement. Laboratory testing isolated the outbreak strain of Salmonella Virchow from: leftover Product A collected from ill people's homes, organic moringa leaf powder (an ingredient in Product A), and finished product retained by the firm. Firm inspections at three facilities linked to Product A production did not reveal contamination at the facilities. Traceback identified that the contaminated moringa leaf powder was imported from South Africa. This investigation identified a novel outbreak vehicle and highlighted the potential risk with similar products not intended to be cooked by consumers before consuming. The company issued a voluntary recall of all implicated products. As this product has a long shelf-life, the recall likely prevented additional illnesses.

  7. The dramatic increase in total knee replacement utilization rates in the United States cannot be fully explained by growth in population size and the obesity epidemic.

    Science.gov (United States)

    Losina, Elena; Thornhill, Thomas S; Rome, Benjamin N; Wright, John; Katz, Jeffrey N

    2012-02-01

    Total knee replacement utilization in the United States more than doubled from 1999 to 2008. Although the reasons for this increase have not been examined rigorously, some have attributed the increase to population growth and the obesity epidemic. Our goal was to investigate whether the rapid increase in total knee replacement use over the past decade can be sufficiently attributed to changes in these two factors. We used data from the Nationwide Inpatient Sample to estimate changes in total knee replacement utilization rates from 1999 to 2008, stratified by age (eighteen to forty-four years, forty-five to sixty-four years, and sixty-five years or older). We obtained data on obesity prevalence and U.S. population growth from federal sources. We compared the rate of change in total knee replacement utilization with the rates of population growth and change in obesity prevalence from 1999 to 2008. In 2008, 615,050 total knee replacements were performed in the United States adult population, 134% more than in 1999. During the same time period, the overall population size increased by 11%. While the population of forty-five to sixty-four-year-olds grew by 29%, the number of total knee replacements in this age group more than tripled. The number of obese and non-obese individuals in the United States increased by 23% and 4%, respectively. Assuming unchanged indications for total knee replacement among obese and non-obese individuals with knee osteoarthritis over the last decade, these changes fail to account for the 134% growth in total knee replacement use. Population growth and obesity cannot fully explain the rapid expansion of total knee replacements in the last decade, suggesting that other factors must also be involved. The disproportionate increase in total knee replacements among younger patients may be a result of a growing number of knee injuries and expanding indications for the procedure.

  8. Experimental research regarding the corrosion of incoloy-800 and SA 508 cl.2 in the CANDU steam generator

    International Nuclear Information System (INIS)

    Lucan, D.; Fulger, M.; Savu, G.; Velciu, L.

    2004-01-01

    Steam generators (SGs) are crucial components of pressurized water reactors. The failure of the steam generator as a result of tube degradation by corrosion has been a major cause of Pressurized Water Reactor (PWR) plant unavailability. Steam generator problems have caused major economic losses in terms of lost electricity production through forced unit outages and, in cases of extreme damage, as additional direct cost for large-scale repair or replacement of steam generators. Steam generator tubes are susceptible to failure by a variety of mechanisms, the vast majority of which are related a corrosion. The feedwater that enters into the steam generators under normal operating conditions is extremely pure, but nevertheless contains low levels (generally in the μg/l concentration range) of impurities such as iron, chloride, sulphate, silicate, etc. When water is converted to steam and exits the steam generator, the non-volatile impurities are left behind. As a result, their concentration in the bulk steam generator water is considerably higher than those in the feedwater. Nevertheless, the concentrations of corrosive impurities are still generally sufficiently low that the bulk water is not significantly aggressive towards steam generator materials. The excellent performance to date of CANDU steam generators can be attributed, in part, to their design and performance characteristics, which typically involve higher recirculation ratios and lower heat fluxes and temperatures. The purpose of this paper consists in assessment of generalized corrosion behaviour of the tubes materials (Incoloy-800) and tubesheet material (carbon steel SA 508 cl.2) at the normal secondary circuit parameters (temperature-260 deg C, pressure-5.1MPa). The testing environment was the demineralized water without impurities, at pH=9.5 regulated with morpholine and ciclohexilamine (all volatile treatment - AVT). The results are presented like micrographies and graphics representing loss of metal

  9. A device for locating intercircuit leaks in heat transfer components of WWER steam generators during unit outage

    International Nuclear Information System (INIS)

    Matal, O.; Klinga, J.; Holy, F.; Fabian, S.

    1991-01-01

    The device is based on the following principle. The space between the tubes of the cold steam generator is filled with pressurized gas, the spaces of primary collectors in their bottom neck and in the attached tubing are waterproof-closed, and the inner spaces of the heat transfer tubes are gradually filled with modified water. This water is illuminated and its level is monitored. The formation and magnitude of flow and locality of source of gas bubbles leaking into the primary collector space are optically observed and acoustically measured. The device for this includes a module attached to a support, which is slidably located on a column. The module houses a water level indicator, a camera, a light source, and at least one acoustic sensor located under the water level. On the bottom part of the column, along which a water filling hose and a water tubing are led, is suspended an inflatable bag placed into the bottom neck of the primary collector and into the tubing. The water tubing empties in the lowest space, which is formed by the bottom neck of the primary collector and the surface of the inflated bag. On the inflatable bag is located a flange fitted with a light source oriented into the water-filled space of the primary collector, and with safety and attachment valves. (P.A.). 2 figs

  10. System of aid for the starting of the steam generator of a thermoelectric unit; Sistema de ayuda para el arranque del generador de vapor de una unidad termoelectrica

    Energy Technology Data Exchange (ETDEWEB)

    Quintero R, Agustin; Suarez C, Dionisio A; Aquino E, Juan C; Diaz H, Carlos A; Cruz T, Jorge A; Sanchez L, Jose A [Instituto de Investigaciones Electricas, Cuernavaca, Morelos (Mexico)

    2002-07-01

    This article presents the development of an on line aid system, whose objective is to aid the operator of a thermoelectric unit, providing the information that is required to carry out the heating and pressurization of the steam generator in the shortest possible time. The former takes place respecting the operation limits determined by the manufacturer and the conditions of security established to carry out the maneuvers of operation of the equipment. The system incorporates a scheme of predictive control, based on a neuronal model that estimates the optimal position of two final elements of control to fulfill with the curves of reference for the temperature and pressure of the main steam. The system is based on an architecture client-server and uses technology Web for the access of the information through a navigator of the Internet. [Spanish] Este articulo presenta el desarrollo de un sistema de ayuda en linea, cuyo objetivo es asistir al operador de una unidad termoelectrica, proporcionando la informacion que requiere para llevar a cabo el calentamiento y presurizacion del generador de vapor en el menor tiempo posible. Lo anterior se efectua respetando los limites de operacion determinados por el fabricante y las condiciones de seguridad establecidas para efectuar las maniobras de operacion de los equipos. El sistema incorpora un esquema de control predictivo, basado en un modelo neuronal, que estima la posicion optima de dos elementos finales de control para cumplir con las curvas de referencia para la temperatura y presion del vapor principal. El sistema esta basado en una arquitectura cliente-servidor y utiliza tecnologia Web para el acceso a la informacion a traves de un navegador del Internet.

  11. Experience from replacement and check of thermocouples during reconstruction of in-reactor temperature measurements at Bohunice V-1 units 1 and 2

    International Nuclear Information System (INIS)

    Slanina, M.; Stanc, J.

    2001-01-01

    Replacement of thermocouples in the protection tube blocks was a key phase of the reconstruction of in-reactor temperature measurements at Bohunice V-1 with regard to the success, reliability and impact on safety of unit operation. The replacement consisted of reliable and safe withdrawal of 216 old thermocouples, their disposal and installation of new thermocouples into dry channels. In the material presented, this phase of reconstruction is described in details, with focus on the evaluation of replacement quality and check activities carried out at the new installed thermocouples. (Authors)

  12. Collective Training and Fielding Opportunities for the Objective Force Maneuver Systems at the Unit of Action Level in a Unit Manning/Unit Replacement Personnel System

    National Research Council Canada - National Science Library

    Courts, Michael

    2003-01-01

    The introduction of Objective Force formations, beginning with the first Unit of Action, will fundamentally change existing organizational structures, training requirements and operational constructs for the U.S. Army...

  13. Steam turbine cycle

    International Nuclear Information System (INIS)

    Okuzumi, Naoaki.

    1994-01-01

    In a steam turbine cycle, steams exhausted from the turbine are extracted, and they are connected to a steam sucking pipe of a steam injector, and a discharge pipe of the steam injector is connected to an inlet of a water turbine. High pressure discharge water is obtained from low pressure steams by utilizing a pressurizing performance of the steam injector and the water turbine is rotated by the high pressure water to generate electric power. This recover and reutilize discharged heat of the steam turbine effectively, thereby enabling to improve heat efficiency of the steam turbine cycle. (T.M.)

  14. Turbine casing bolts; a life assessment and bolt replacement strategy

    Energy Technology Data Exchange (ETDEWEB)

    Bulloch, J.H. [ESB, Power Generation, Dublin (Ireland)

    1998-12-31

    The present presentation describes a detailed study concerning the life assessment and replacement strategy of large turbine casing bolts in a 120 MW steam raising unit. After 122000 hours service, circa 1991/92, the Cr-Mo-V steel casing bolts, involving a total of 184 bolts, from two identical 120 MW units, termed Units 1 and 2, were examined to establish the extent of Reverse Temper Embrittlement, RTE, and creep damage suffered during service. The bolt replacement plans for the two units were as follows; Unit 1 bolts were completely replaced with new bolts while Unit 2 embrittled bolts were withdrawn from service and replaced with Non- Embrittled bolts from Unit 1; basically Unit 2 bolts were made up from a mixture of Unit 1 and 2 Non- Embrittled bolts which had been in service for 122000 hours. Remnant life assessments, concerning both embrittlement and creep damage aspects, were earned out on this series of easing bolts at service times 122000, 150000 and 200000 hours. These assessments involved the use of general embrittlement and creep damage laws which were empirically derived and concerned such parameters as microstructural grain size, bulk phosphorus content and accumulated service strain. (orig.) 7 refs.

  15. Turbine casing bolts; a life assessment and bolt replacement strategy

    Energy Technology Data Exchange (ETDEWEB)

    Bulloch, J H [ESB, Power Generation, Dublin (Ireland)

    1999-12-31

    The present presentation describes a detailed study concerning the life assessment and replacement strategy of large turbine casing bolts in a 120 MW steam raising unit. After 122000 hours service, circa 1991/92, the Cr-Mo-V steel casing bolts, involving a total of 184 bolts, from two identical 120 MW units, termed Units 1 and 2, were examined to establish the extent of Reverse Temper Embrittlement, RTE, and creep damage suffered during service. The bolt replacement plans for the two units were as follows; Unit 1 bolts were completely replaced with new bolts while Unit 2 embrittled bolts were withdrawn from service and replaced with Non- Embrittled bolts from Unit 1; basically Unit 2 bolts were made up from a mixture of Unit 1 and 2 Non- Embrittled bolts which had been in service for 122000 hours. Remnant life assessments, concerning both embrittlement and creep damage aspects, were earned out on this series of easing bolts at service times 122000, 150000 and 200000 hours. These assessments involved the use of general embrittlement and creep damage laws which were empirically derived and concerned such parameters as microstructural grain size, bulk phosphorus content and accumulated service strain. (orig.) 7 refs.

  16. Report on US-Japan 1983 meetings on steam generators

    International Nuclear Information System (INIS)

    1984-04-01

    This is a report on a trip to Japan by personnel of the US Nuclear Regulatory Commission in 1983 to exchange information on steam generators of nuclear power plants. Steam generators of Japanese pressurized water reactors have experienced nearly all of the forms of degradation that have been experienced in US recirculating-type steam generators, except for denting and pitting. More tubes have been plugged per year of reactor operation in Japanese than in US steam generators, but much of the Japanese tube plugging is preventative rather than the result of leaks experienced. The number of leaks per reactor year is much smaller for Japanese than for US steam generators. No steam generators have been replaced in Japan while several have been replaced in the US. The Japanese experience may be related to their very stringent inspection and maintenance programs for steam generators

  17. Procedure for generating steam and steam generator for operating said procedure

    International Nuclear Information System (INIS)

    Chlique, Bernard.

    1975-01-01

    This invention concerns the generation of steam by bringing the water to be vaporised into indirect thermal exchange relation with the heating steam which condenses when passing in series, along alternate routes, through bundles of tubes immersed in a vaporising chamber. A number of steam generators working on this principle already exist. The purpose of the invention is to modify the operating method of these steam generators by means of a special disposition making it possible to build a compact unit including an additional bundle of tubes heated by the condensates collected at the outlet of each bundle through which the heating steam passes [fr

  18. Steam generator life-management, reliability, maintenance and refurbishment

    International Nuclear Information System (INIS)

    Spekkens, P.

    2012-01-01

    SGC 2012 is a different kind of a conference - it has its own focus, initiatives and objectives and differs from its predecessors. It originated as the Steam Generator and Heat Exchanger Conference in 1990 - a time when premature degradation of steam generators with Alloy 600 tubes was rampant world-wide, and some CANDU steam generators had started to experience significant fouling and corrosion issues. The six previous steam generator conferences were held on a regular cycle, in a very similar format and with a similar theme. We are now in a different era in steam generators. The Alloy 600 tubing has been largely replaced by more robust materials, and the CANDU steam generators have been brought under much more intense and effective life cycle management. Performance of steam generators has improved greatly, and they are no longer considered at risk of limiting the life of the units. Indeed, most Incoloy 800 steam generators in CANDU units are considered to be capable of operating reliably through the 'second life' of the units and are not being replaced during refurbishments. Given this changing environment, the scope of this conference has been expanded from one to three areas: steam generators and heat exchangers as before, but also; controls, valves and pumps, and; reactor components and systems, Programs A, B and C, respectively. The conference is targeting to address the needs and interests of the operating utilities, and to 'focus on what needs attention'. As a means of 'focusing on what needs attention' an 'Issue-Identification and Definition' program was initiated last winter. The Issue-Identification Team operating with COG President Bob Morrison as its Executive Lead, worked to identify issues requiring attention in the three areas of interest. Of the many issues identified by the Team and elaborated on by the Program Developers of this conference, four were recommended for special attention: A. 'Operate Clean - Build Clean - Plant Wide': Despite their

  19. Safety evaluation report related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445 and 50-446)

    International Nuclear Information System (INIS)

    1988-11-01

    Supplement 19 to the Safety Evaluation Report related to the operation of the Comanche Peak Steam Electric Station (CPSES), Units 1 and 2 (NUREG-0797), has been prepared by the Office of Special Projects of the US Nuclear Regulatory Commission (NRC). The facility is located in Somervell County, Texas, approximately 40 miles southwest of Fort Worth, Texas. This supplement presents the staff's evaluation of the Texas Utilities Electric Company's (lead applicant's) corrective action program (CAP) related to equipment qualification. The scope and methodology for the CAP workscope, as summarized in Revision 0 to the Equipment Qualification Project Status Report and as detailed in related documents, were developed to resolve various issues raised by the Comanche Peak Response Team (CPRT) and the NRC staff to ensure that plant equipment is appropriately environmentally and/or seismically and dynamically qualified and documented in accordance with the validated plant design resulting from other CAP scopes of work for Unit 1 and areas common to Units 1 and 2. The staff concludes that the CAP workscope for equipment qualification provides a comprehensive program for resolving the concerns identified by the CPRT and the NRC staff, including issues raised in the Comanche Peak Safety Evaluation Report and its supplements, and its implementation will ensure that the environmental and/or seismic and dynamic qualification of equipment at CPSES satisfies the validated plant design and the applicable requirements of 10 CFR Part 50. As is routine staff practice, the NRC staff will verify the adequacy of implementation of the environmental and seismic and dynamic equipment qualification program at CPSES during inspections that will take place before fuel loading. 97 refs

  20. MATHEMATICAL MODEL AND METHODOLOGY FOR CALCULATION OF MINIMIZATION ON TURNING RADIUS OF TRACTOR UNIT WITH REPLACEABLE SUPPORTING AND MANEUVERING DEVICE

    Directory of Open Access Journals (Sweden)

    P. V. Zeleniy

    2016-01-01

    Full Text Available Smooth plowing with the help of reversible plows has replaced an enclosure method of soil treatment. The method may cause a formation of back ridges or open furrows. Due to this fact turnings of a tractor unit with a minimum radius required in order to ensure shuttle movements each time in the furrow of the preceding operating stroke have become a dominant type of turnings. Non-productive shift time is directly dependent on them and it is on the average 10–12 %, and it is up to 40 % in small contour areas with short run. Large non-productive time is connected with the desire to reduce headland width at field edges, and then a turning is made in several stages while using a complicated maneuvering. Therefore, an increase in efficiency of a plowing unit by means of minimization on its turning radius and execution of turning at one stage in the shortest possible time are considered as relevant objectives. In such a case it is necessary to take into account the fact that potential capabilities of universal tractors having established time-proved designs in respect of reduction of turning radius are practically at the end. So it is expedient to solve the matter at the expense of additional removable devices that ensure transformation of tractor wheel formula at the run end in order to reorient its position. Finally high quality plowing ensured by future-oriented reversible plows will be accompanied not only by output increase per shift, but also by decrease in headland width, their compaction and abrasion due to suspension systems and increase in productivity. The developed design having a novelty which proved by an invention patent and representing an additional supporting and maneuvering device significantly minimizes all the above-mentioned disadvantages and does not require any changes in tractor production design. Investigations have been carried on the following topic: “Minimization of turning radius for universal tractors by transformation

  1. Operational control and maintenance integrity of typical and atypical coil tube steam generating systems

    Energy Technology Data Exchange (ETDEWEB)

    Beardwood, E.S.

    1999-07-01

    Coil tube steam generators are low water volume to boiler horsepower (bhp) rating, rapid steaming units which occupy substantially less space per boiler horsepower than equivalent conventional tire tube and water tube boilers. These units can be retrofitted into existing steam systems with relative ease and are more efficient than the generators they replace. During the early 1970's they became a popular choice for steam generation in commercial, institutional and light to medium industrial applications. Although these boiler designs do not require skilled or certified operators, an appreciation for a number of the operational conditions that result in lower unscheduled maintenance, increased reliability and availability cycles would be beneficial to facility owners, managers, and operators. Conditions which afford lower operating and maintenance costs will be discussed from a practical point of view. An overview of boiler design and operation is also included. Pitfalls are provided for operational and idle conditions. Water treatment application, as well as steam system operations not conducive to maintaining long term system integrity; with resolutions, will be addressed.

  2. Safety evaluation report related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2: Docket Nos. 50-445 and 50-446

    International Nuclear Information System (INIS)

    1988-07-01

    Supplement 15 to the Safety Evaluation Report related to the operation of the Comanche Peak Steam Electric Station (CPSES), Units 1 and 2 (NUREG-0797), has been prepared by the Office of Special Projects of the US Nuclear Regulatory Commission (NRC). The facility is located in Somervell County, Texas, approximately 40 miles southwest of Fort Worth, Texas. This supplement presents the staff's evaluation of the applicant's Corrective Action Program (CAP) related to the design of cable trays and cable tray hangers. The scope and methodologies for the CAP workscope as summarized in Revision O to the cable tray and cable tray hanger project status report and as detailed in related documents referenced in this evaluation were developed to resolve various design issues raised by the Atomic Safety and Licensing Board (ASLB) the intervenor, Citizens Association for Sound Energy (CASE); the Comanche Peak Response Team (CPRT); CYGNA Energy Services (CYGNA); and the NRC staff. The NRC staff concludes that the CAP workscope for cable trays and cable tray hangers provides a comprehensive program for resolving the associated technical concerns identified by the ASLB, CASE, CPRT, CYGNA, and the NRC staff and its implementation ensures that the design of cable trays and cable tray hangers at CPSES satisfies the applicable requirements of 10 CFR Part 50

  3. Safety evaluation report related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445 and 50-446)

    International Nuclear Information System (INIS)

    1988-11-01

    Supplement 18 to the Safety Evaluation Report related to the operation of the Comanche Peak Steam Electric Station (CPSES), Units 1 and 2 (NUREG-0797), has been prepared by the Office of Special Projects of the US Nuclear Regulatory Commission (NRC). The facility is located in Somervell County, Texas, approximately 40 miles southwest of Fort Worth, Texas. This supplement presents the staff's evaluation of the applicant's Corrective Action Program (CAP) related to the structural design of the heating, ventilation, and air conditioning (HVAC) systems. The scope and methodologies for the CAP workscope as summarized in Revision 0 to the HVAC project status report and as detailed in related documents referenced in this evaluation were developed to resolve the technical concerns identified in the HVAC area. The NRC staff concludes that the CAP workscope for the HVAC structural design provides a comprehensive program for resolving the associated technical concerns and its implementation ensures that the structural design of the HVAC systems at CPSES satisfies the applicable requirements of 10 CFR Part 50. 32 refs

  4. Safety Evaluation Report related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445 and 50-446)

    International Nuclear Information System (INIS)

    1990-01-01

    Supplement 22 to the Safety Evaluation Report related to the operation of the Comanche Peak Steam Electric Station, Units 1 and 2 (NUREG-0797), has been prepared by the Office of Nuclear Reactor Regulation of the US Nuclear Regulatory Commission. The facility is located in Somervell County, Texas, approximately 40 miles southwest of Fort Worth, Texas. This supplement reports the status of certain issues that had not been resolved at the time of publication of the Safety Evaluation Report and Supplements 1, 2, 3, 4, 6, 12, and 21 to that report. This supplement also includes the evaluations for licensing items resolved since Supplement 21 was issued. Supplement 5 has been cancelled. Supplements 7 through 11 were limited to the staff evaluation of allegations investigated by the NRC Technical Review Team. Supplement 13 presented the staff's evaluation of the Comanche Peak Response Team (CPRT) Program Plan, which was formulated by the applicant to resolve various construction and design issues raised by sources external to the applicant. Supplements 14 through 20 presented the staff's evaluation of the applicant's Corrective Action Program and CPRT activities. Items identified in Supplements 7, 8, 9, 10, 11, 13, 14, and 15 through 20 are not included in this supplement, except to the extent that they affect the applicant's Final Safety Analysis Report. 154 refs., 24 figs., 8 tabs

  5. Safety evaluation report related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2: Docket No. 50-445 and 50-446

    International Nuclear Information System (INIS)

    1988-11-01

    Supplement 20 to the Safety Evaluation Report related to the operation of the Comanche Peak Steam Electric Station (CPSES), Units 1 and 2 (NUREG-0797), has been prepared by the Office of Special Projects of the US Nuclear Regulatory Commission (NRC). The facility is located in Somervell County, Texas, approximately 40 miles southwest of Fort Worth, Texas. This supplement presents the staff's evaluation of CPRT implementation of the Comanche Peak Response Team (CPRT) Program Plan and the issue-specific action plans (ISAPs), as well as the CPRT's investigations to determine the adequacy of various types of programs and hardware at CPSES. The results and conclusions of the CPRT activities are documented in a results report for each ISAP, a Collective Evaluation Report (CER), and a Collective Significance Report (CSR). This supplement also presents the staff's safety evaluation of TU Electric's root cause assessment of past CPSES design deficiencies and weaknesses. The NRC staff concludes that the CPRT has adequately implemented its investigative activities related to the design, construction, construction quality assurance/quality control, and testing at CPSES. The NRC staff further concludes that the CPRT evaluation of the results of its investigation is thorough and complete and its recommendations for corrective actions are sufficient to resolve identified deficiencies

  6. Application of the visual system analyzer (ViSA): simulation of the steam generator tube rupture event at Ulchin unit 4

    International Nuclear Information System (INIS)

    Lee, S.W.; Kim, K.D.; Hwang, M.K.; Jeong, J.J.

    2004-01-01

    Korea Atomic Energy Research Institute (KAERI) has developed the Visual System Analyzer (ViSA) based on the best-estimate (B-E) codes, MARS and RETRAN-3D. The key features of ViSA are: (1) The use of the same input and the same level of accuracy as the original codes is guaranteed (2) Users can design their own plant mimic by a drag-and-drop from the provided indicators (3) The on-line interactive control enables users to simulate the operator's actions (4) The nodalization window is designed to display the transient temperature and void distributions. ViSA is composed of two parts; the B-E code with plant input and the Graphic User Interface (GUI) that includes the plant mimic and an interactive control function, etc. The calculation results of the B-E code are transferred to a user via the GUI and a user can apply the operator action to the B-E code using an interactive control function. Therefore, it is not necessary to prepare complex control input data to simulate the various manual operations which may occur during the plant transient. In this study, the Steam Generator Tube Rupture (SGTR) Accident, which occurred at Ulchin Unit 4 in April 2002, has been simulated using ViSA and the simulation results are compared with the measured plant data. The RETRAN-3D plant input data used in this simulation is a genetic input deck prepared for the simulation from a normal operation condition to a Small-Break LOCA. From the results of the SGTR simulation, we found that the GUI functions of ViSA and the input data for Ulchin Unit 4 have enough effectiveness and soundness. (author)

  7. Investigation of cracking on a main steam isolation valve shaft from the Farley unit 1 nuclear power plant

    International Nuclear Information System (INIS)

    Czajkowski, C.J.

    1985-01-01

    The chemical analysis of the Farley Unit 1 MSIV shaft (69C) showed that the chemical composition of the material was consistent with that expected of a Type 410 stainless steel. The microstructure observed in the base metal (tempered martensite) is consistent with that expected in a Type 410 stainless steel in the quenched and tempered condition. The hardness measurements (both Rsub(c) and Knoop) show that the hardness observed (Rsub(c) 41.3 with a KN max of 459) is significantly higher than that which was anticipated by the heat treatments performed. The cracking was intergranular in nature, occuring along prior austenite grain boundaries. There was no evidence of fatigue interaction on the fracture observed, and no definitive corrodent species identified. The cracking is considered to be an intergranular stress corrosion cracking phenomenon resulting from a high hardness-susceptible material under pressurized water reactor conditions

  8. Investigation of cracking on a main steam isolation valve shaft from the Farley Unit No. 1 nuclear power plant

    International Nuclear Information System (INIS)

    Czajkowski, C.J.

    1985-01-01

    Chemical analysis of the Farley Unit No. 1 MSIV shaft (No. 69C) showed that the chemical composition of the material was consistent with that expected of a Type 410 stainless steel. The microstructure observed in the base metal (tempered martensite) is consistent with that expected in a Type 410 stainless steel in the quenched and tempered condition. The hardness measurements (both R/sub c/ and Knoop) show that the hardness observed (R/sub c/ 41.3 with a KN max of 459) is significantly higher than that which was anticipated by the heat treatments performed. The cracking was intergranular in nature, occurring along prior austenite grain boundaries. There was not evidence of fatigue interaction on the fracture observed, and no definitive corrodent species identified. The cracking is considered to be an intergranular stress corrosion cracking phenomenon resulting from a high hardness-susceptible material under pressurized water reactor conditions

  9. Steaming ahead

    International Nuclear Information System (INIS)

    Anon.

    1997-01-01

    An example of the development of geothermal power in Indonesia is described. Wells are being drilled into the Salak volcano on Java, about 60km south of Jakarta. These let out high pressure hot water trapped 1 to 3km below the surface which can be flashed into steam for driving turbines. The hot water field has already produced 110MW of power since 1994 and is currently being expanded to 330MW. Some details of the drilling and civil engineering are given. Since Indonesia sits on the edge of giant tectonic boundary known as the ''Pacific ring of fire'', the potential for further development is enormous. Ultimately volcanic activity could release an estimated 27,000MW capacity. More realistically, 2,000MW of crustal power by 2020 is spoken of. (UK)

  10. Simulation based assembly and alignment process ability analysis for line replaceable units of the high power solid state laser facility

    International Nuclear Information System (INIS)

    Wang, Junfeng; Lu, Cong; Li, Shiqi

    2016-01-01

    Highlights: • Discrete event simulation is applied to analyze the assembly and alignment process ability of LRUs in SG-III facility. • The overall assembly and alignment process of LRUs with specific characteristics is described. • An extended-directed graph is proposed to express the assembly and alignment process of LRUs. • Different scenarios have been simulated to evaluate assembling process ability of LRUs and decision making is supported to ensure the construction millstone. - Abstract: Line replaceable units (LRUs) are important components of the very large high power solid state laser facilities. The assembly and alignment process ability of LRUs will impact the construction milestone of facilities. This paper describes the use of discrete event simulation method for assembly and alignment process analysis of LRUs in such facilities. The overall assembly and alignment process for LRUs is presented based on the layout of the optics assembly laboratory and the process characteristics are analyzed. An extended-directed graph is proposed to express the assembly and alignment process of LRUs. Taking the LRUs of disk amplifier system in Shen Guang-III (SG-III) facility as the example, some process simulation models are built based on the Quest simulation platform. The constraints, such as duration, equipment, technician and part supply, are considered in the simulation models. Different simulation scenarios have been carried out to evaluate the assembling process ability of LRUs. The simulation method can provide a valuable decision making and process optimization tool for the optics assembly laboratory layout and the process working out of such facilities.

  11. Acute renal failure requiring renal replacement therapy in the intensive care unit: impact on prognostic assessment for shared decision making.

    Science.gov (United States)

    Johnson, Robert F; Gustin, Jillian

    2011-07-01

    A 69-year-old female was receiving renal replacement therapy (RRT) for acute renal failure (ARF) in an intensive care unit (ICU). Consultation was requested from the palliative medicine service to facilitate a shared decision-making process regarding goals of care. Clinician responsibility in shared decision making includes the formulation and expression of a prognostic assessment providing the necessary perspective for a spokesperson to match patient values with treatment options. For this patient, ARF requiring RRT in the ICU was used as a focal point for preparing a prognostic assessment. A prognostic assessment should include the outcomes of most importance to a discussion of goals of care: mortality risk and survivor functional status, in this case including renal recovery. A systematic review of the literature was conducted to document published data regarding these outcomes for adult patients receiving RRT for ARF in the ICU. Forty-one studies met the inclusion criteria. The combined mean values for short-term mortality, long-term mortality, renal-function recovery of short-term survivors, and renal-function recovery of long-term survivors were 51.7%, 68.6%, 82.0%, and 88.4%, respectively. This case example illustrates a process for formulating and expressing a prognostic assessment for an ICU patient requiring RRT for ARF. Data from the literature review provide baseline information that requires adjustment to reflect specific patient circumstances. The nature of the acute primary process, comorbidities, and severity of illness are key modifiers. Finally, the prognostic assessment is expressed during a family meeting using recommended principles of communication.

  12. Simulation based assembly and alignment process ability analysis for line replaceable units of the high power solid state laser facility

    Energy Technology Data Exchange (ETDEWEB)

    Wang, Junfeng; Lu, Cong; Li, Shiqi, E-mail: sqli@hust.edu.cn

    2016-11-15

    Highlights: • Discrete event simulation is applied to analyze the assembly and alignment process ability of LRUs in SG-III facility. • The overall assembly and alignment process of LRUs with specific characteristics is described. • An extended-directed graph is proposed to express the assembly and alignment process of LRUs. • Different scenarios have been simulated to evaluate assembling process ability of LRUs and decision making is supported to ensure the construction millstone. - Abstract: Line replaceable units (LRUs) are important components of the very large high power solid state laser facilities. The assembly and alignment process ability of LRUs will impact the construction milestone of facilities. This paper describes the use of discrete event simulation method for assembly and alignment process analysis of LRUs in such facilities. The overall assembly and alignment process for LRUs is presented based on the layout of the optics assembly laboratory and the process characteristics are analyzed. An extended-directed graph is proposed to express the assembly and alignment process of LRUs. Taking the LRUs of disk amplifier system in Shen Guang-III (SG-III) facility as the example, some process simulation models are built based on the Quest simulation platform. The constraints, such as duration, equipment, technician and part supply, are considered in the simulation models. Different simulation scenarios have been carried out to evaluate the assembling process ability of LRUs. The simulation method can provide a valuable decision making and process optimization tool for the optics assembly laboratory layout and the process working out of such facilities.

  13. Four-unit fixed dental prostheses replacing the maxillary incisors supported by two narrow-diameter implants - a five-year case series.

    Science.gov (United States)

    Moráguez, Osvaldo; Vailati, Francesca; Grütter, Linda; Sailer, Irena; Belser, Urs C

    2017-07-01

    (1) To determine the survival rate of 10 four-unit fixed dental prostheses (FDPs) replacing the four maxillary incisors, supported by 20 narrow-diameter implants (NDIs), (2) to assess the incidence of mechanical and biological complications, and (3) to evaluate bone level changes longitudinally after final FDP insertion. Ten patients (six women, four men), mean age 49.4 ± 12.6 years, were treated with a four-unit anterior maxillary FDP (six screw-retained; four cemented). Biological parameters, eventual technical complications, radiographic measurements, and study casts were assessed at 1 (baseline), 3, and 5 years after implant placement. A multilevel logistic regression test was performed on clinical parameters and bone level changes (significance level P four-unit FDP to replace the four missing maxillary incisors may be considered a predictable treatment modality. © 2016 John Wiley & Sons A/S. Published by John Wiley & Sons Ltd.

  14. A steam separator-superheater apparatus

    International Nuclear Information System (INIS)

    Androw, Jean; Bessouat, Roger; Peyrelongue, J.-P.

    1973-01-01

    Description is given of a separator-superheater apparatus comprising an outer enclosure containing a separating-unit and a steam superheating unit according to the main patent. The present addition relates to an improvement in that apparatus, characterized in that the separating unit and the superheating unit, mounted in two distinct portions of the outer enclosure, are divided into the same number of sub-units of each unit being identical and operating in parallel, and in that to each separator sub-unit is associated a superheater sub-unit, said sub-units being mounted in series and located in one in the other of the enclosure two portions, respectively. This can be applied to the treatment of the exhaust steam of a turbine high pressure body, prior to re-injecting said steam into the low pressure body [fr

  15. Electricity from geothermal steam

    Energy Technology Data Exchange (ETDEWEB)

    Wheatcroft, E L.E.

    1959-01-01

    The development of the power station at Wairakei geothermal field is described. Wairakei is located at the center of New Zealand's volcanic belt, which lies within a major graben which is still undergoing some degree of downfaulting. A considerable number of wells, some exceeding 610 m, have been drilled. Steam and hot water are produced from both deep and shallow wells, which produce at gauge pressures of 1.5 MPa and 0.6 MPa, respectively. The turbines are fed by low, intermediate, and high pressure mains. The intermediate pressure turbine bank was installed as a replacement for a heavy water production facility which had originally been planned for the development. Stage 1 includes a 69 MW plant, and stage 2 will bring the capacity to 150 MW. A third stage, which would bring the output up to 250 MW had been proposed. The second stage involves the installation of more high pressure steam turbines, while the third stage would be powered primarily by hot water flashing. Generation is at 11 kV fed to a two-section 500 MVA board. Each section of the board feeds through a 40 MVA transformer to a pair of 220 V transmission lines which splice into the North Island grid. Other transformers feed 400 V auxiliaries and provide local supply.

  16. Boxberg III-2 x 500 MW units: Refurbishing and environmental protection measures on the 815 T/H steam generator of works II in Boxberg Power Station

    Energy Technology Data Exchange (ETDEWEB)

    Cossman, R.; Fritz, M.; Bauchmueller, R. [L& C Steinmueller GmbH, Gummersbach (Germany)

    1995-12-01

    The object of the upgrading measures on the steam generators is: (1) To comply with the requirements of the German antipollution law, which imposes a permissible NO{sub x} content in the flue gas of less than 200 Mg/m{sup 3} STP and a CO content of less than 250 Mg/m{sup 3} STP. (2) To increase the boiler efficiency and availability and the efficiency of the water/steam cycle.

  17. Research perspectives on the evaluation of steam generator tube integrity

    International Nuclear Information System (INIS)

    Muscara, J.; Diercks, D. R.; Majumdar, S.; Kupperman, D. S.; Bakhtiari, S.; Shack, W. J.

    2001-01-01

    Industry effects have been largely successful in managing degradation of steam generator tubes due to wastage, pitting, and denting, but fretting, SCC and intergranular attack have proved more difficult to manage. Although steam generator replacements are proceeding there is substantial industry interest in operating with degraded steam generators, and significant numbers of plants will continue to do so. In most cases degradation of steam generator tubing by stress corrosion cracking is still managed by plug or repair on detection, because current NDE techniques for characterization of flaws are not accurate enough to permit continued operation. This paper reviews some of the historical background that underlies current steam generator degradation management strategies and outlines some of the additional research that must be done to provide more effective management of degradation in current generators and provide greater assurance of satisfactory performance in replacement steam generators

  18. An expert system for diagnostics and estimation of steam turbine components condition

    Science.gov (United States)

    Murmansky, B. E.; Aronson, K. E.; Brodov, Yu. M.

    2017-11-01

    The report describes an expert system of probability type for diagnostics and state estimation of steam turbine technological subsystems components. The expert system is based on Bayes’ theorem and permits to troubleshoot the equipment components, using expert experience, when there is a lack of baseline information on the indicators of turbine operation. Within a unified approach the expert system solves the problems of diagnosing the flow steam path of the turbine, bearings, thermal expansion system, regulatory system, condensing unit, the systems of regenerative feed-water and hot water heating. The knowledge base of the expert system for turbine unit rotors and bearings contains a description of 34 defects and of 104 related diagnostic features that cause a change in its vibration state. The knowledge base for the condensing unit contains 12 hypotheses and 15 evidence (indications); the procedures are also designated for 20 state parameters estimation. Similar knowledge base containing the diagnostic features and faults hypotheses are formulated for other technological subsystems of turbine unit. With the necessary initial information available a number of problems can be solved within the expert system for various technological subsystems of steam turbine unit: for steam flow path it is the correlation and regression analysis of multifactor relationship between the vibration parameters variations and the regime parameters; for system of thermal expansions it is the evaluation of force acting on the longitudinal keys depending on the temperature state of the turbine cylinder; for condensing unit it is the evaluation of separate effect of the heat exchange surface contamination and of the presence of air in condenser steam space on condenser thermal efficiency performance, as well as the evaluation of term for condenser cleaning and for tube system replacement and so forth. With a lack of initial information the expert system enables to formulate a diagnosis

  19. Steam Digest 2002

    Energy Technology Data Exchange (ETDEWEB)

    2003-11-01

    Steam Digest 2002 is a collection of articles published in the last year on steam system efficiency. DOE directly or indirectly facilitated the publication of the articles through it's BestPractices Steam effort. Steam Digest 2002 provides a variety of operational, design, marketing, and program and program assessment observations. Plant managers, engineers, and other plant operations personnel can refer to the information to improve industrial steam system management, efficiency, and performance.

  20. Cogeneration steam turbines from Siemens: New solutions

    Science.gov (United States)

    Kasilov, V. F.; Kholodkov, S. V.

    2017-03-01

    The Enhanced Platform system intended for the design and manufacture of Siemens AG turbines is presented. It combines organizational and production measures allowing the production of various types of steam-turbine units with a power of up to 250 MWel from standard components. The Enhanced Platform designs feature higher efficiency, improved reliability, better flexibility, longer overhaul intervals, and lower production costs. The design features of SST-700 and SST-900 steam turbines are outlined. The SST-700 turbine is used in backpressure steam-turbine units (STU) or as a high-pressure cylinder in a two-cylinder condensing turbine with steam reheat. The design of an SST-700 single-cylinder turbine with a casing without horizontal split featuring better flexibility of the turbine unit is presented. An SST-900 turbine can be used as a combined IP and LP cylinder (IPLPC) in steam-turbine or combined-cycle power units with steam reheat. The arrangements of a turbine unit based on a combination of SST-700 and SST-900 turbines or SST-500 and SST-800 turbines are presented. Examples of this combination include, respectively, PGU-410 combinedcycle units (CCU) with a condensing turbine and PGU-420 CCUs with a cogeneration turbine. The main equipment items of a PGU-410 CCU comprise an SGT5-4000F gas-turbine unit (GTU) and STU consisting of SST-700 and SST-900RH steam turbines. The steam-turbine section of a PGU-420 cogeneration power unit has a single-shaft turbine unit with two SST-800 turbines and one SST-500 turbine giving a power output of N el. STU = 150 MW under condensing conditions.

  1. Safety Evaluation Report related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445 and 50-446)

    International Nuclear Information System (INIS)

    1990-02-01

    Supplement 23 to the Safety Evaluation Report related to the operation of the Comanche Peak Steam Electric Station (CPSES), Units 1 and 2 (NUREG-0797), has been prepared by the Office of Nuclear Reactor Regulation of the US Nuclear Regulatory Commission (NRC). The facility is located in Somervell County, Texas, approximately 40 miles southwest of Fort Worth, Texas. This supplement reports the status of certain issues that had not been resolved when the Safety Evaluation Report and supplements 1, 2, 3, 4, 6, 12, 21, and 22 to that report were published. This supplement also includes the evaluations for licensing items resolved since Supplement 22 was issued. Supplement 5 has not been issued. Supplements 7, 8, 9, 10, and 11 were limited to the staff evaluation of allegations investigated by the NRC Technical Review Team. Supplement 13 presented the staff's evaluation of the Comanche Peak Response Team (CPRT) Program Plan, which was formulated by the applicant to resolve various construction and design issues raised by sources external to TU Electric. Supplements 14 through 19 presented the staff's evaluation of the CPSES Corrective Action Program: large- and small-bore piping and pipe supports (Supplement 14); cable trays and cable tray hangers (Supplement 15); conduit supports (Supplement 16); mechanical, civil/structural, electrical, instrumentation and controls, and systems portions of the heating, ventilation, and air conditioning (HVAC) system workscopes (Supplement 17); HVAC structural design (Supplement 18); and equipment qualification (Supplement 19). Supplement 20 presented the staff's evaluation of the Comanche Peak Response Team implementation of the CPRT Program

  2. Three Mile Island Unit 1 Main Steam Line Break Three-Dimensional Neutronics/Thermal-Hydraulics Analysis: Application of Different Coupled Codes

    International Nuclear Information System (INIS)

    D'Auria, Francesco; Moreno, Jose Luis Gago; Galassi, Giorgio Maria; Grgic, Davor; Spadoni, Antonino

    2003-01-01

    A comprehensive analysis of the double ended main steam line break (MSLB) accident assumed to occur in the Babcock and Wilcox Three Mile Island Unit 1 (TMI-1) has been carried out at the Dipartimento di Ingegneria Meccanica, Nucleare e della Produzione of the University of Pisa, Italy, in cooperation with the University of Zagreb, Croatia. The overall activity has been completed within the framework of the participation in the Organization for Economic Cooperation and Development-Committee on the Safety of Nuclear Installations-Nuclear Science Committee pressurized water reactor MSLB benchmark.Thermal-hydraulic system codes (various versions of Relap5), three-dimensional (3-D) neutronics codes (Parcs, Quabbox, and Nestle), and one subchannel code (Cobra) have been adopted for the analysis. Results from the following codes (or code versions) are assumed as reference:1. Relap5/mod3.2.2, beta version, coupled with the 3-D neutron kinetics Parcs code parallel virtual machine (PVM) coupling2. Relap5/mod3.2.2, gamma version, coupled with the 3-D neutron kinetics Quabbox code (direct coupling)3. Relap5/3D code coupled with the 3-D neutron kinetics Nestle code.The influence of PVM and of direct coupling is also discussed.Boundary and initial conditions of the system, including those relevant to the fuel status, have been supplied by Pennsylvania State University in cooperation with GPU Nuclear Corporation (the utility, owner of TMI) and the U.S. Nuclear Regulatory Commission. The comparison among the results obtained by adopting the same thermal-hydraulic nodalization and the coupled code version is discussed in this paper.The capability of the control rods to recover the accident has been demonstrated in all the cases as well as the capability of all the codes to predict the time evolution of the assigned transient. However, one stuck control rod caused some 'recriticality' or 'return to power' whose magnitude is largely affected by boundary and initial conditions

  3. Safety evaluation report related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445 and 50-446)

    International Nuclear Information System (INIS)

    1990-04-01

    Supplement 24 to the Safety Evaluation Report related to the operation of the Comanche Peak Steam Electric Station (CPSES), Units 1 and 2 (NUREG-0797), has been prepared by the Office of Nuclear Reactor Regulation of the US Nuclear Regulatory Commission (NRC). The facility is located in Somervell County, Texas, approximately 40 miles southwest of Fort Worth, Texas. This supplement reports the status of certain issues that had not been resolved when the Safety Evaluation Report and Supplements 1, 2, 3, 4, 6, 12, 21, 22, and 23 to that report were published. This supplement also includes the evaluations for licensing items resolved since Supplement 23 was issued. Supplement 5 has not been issued. Supplements 7, 8, 9, 10, and 11 were limited to the staff evaluation of allegations investigated by the NRC Technical Review Team. Supplement 13 represented the staff's evaluation of the Comanche Peak Response Team (CPRT) Program Plan, which was formulated by the applicant to resolve various construction and design issues raised by sources external to TU Electric. Supplements 14 through 19 presented the staff's evaluation of the CPSES Corrective Action Program: large- and small-bore piping and pipe supports (Supplement 14); cable trays and cable tray hangers (Supplement 15); conduit supports (Supplement 16); mechanical, civil/structural, electrical, instrumentation and controls, and systems portions of the heating, ventilation, and air conditioning (HVAC) system workscopes (Supplement 17); HVAC structural design (Supplement 18); and equipment qualification (Supplement 19). Supplement 20 presented the staff's evaluation of the CPRT implementation of its Program Plan and the issue-specific action plans, as well as the CPRT's investigations to determine the adequacy of various types of programs and hardware at CPSES

  4. Long-Term Survival of Dialysis Patients with Bacterial Endocarditis Undergoing Valvular Replacement Surgery in the United States

    Science.gov (United States)

    Leither, Maxwell D.; Shroff, Gautam R.; Ding, Shu; Gilbertson, David T.; Herzog, Charles A.

    2013-01-01

    Background Bacterial endocarditis in dialysis patients is associated with high mortality rates. The literature is limited regarding long-term outcomes of valvular replacement surgery and choice of prosthesis in dialysis patients with bacterial endocarditis. Methods and Results Dialysis patients hospitalized for bacterial endocarditis, 2004-2007, were studied retrospectively using data from the US Renal Data System. Long-term survival of patients undergoing valve replacement surgery with tissue or non-tissue valves was compared using the Kaplan-Meier method. A Cox proportional hazards model was used to identify independent predictors of mortality in patients undergoing valvular replacement surgery. During the study period, 11,156 dialysis patients were hospitalized for bacterial endocarditis and 1267 (11.4%) underwent valvular replacement surgery (tissue valve 44.3%, non-tissue valve 55.7%). In the valve replacement cohort, 60% were men, 50% white, 54% aged 45-64 years, and 36% diabetic. Estimated survival with tissue and non-tissue valves, respectively, at 0.5, 1, 2, and 3 years was 59% and 60%, 48% and 50%, 35% and 37%, and 25% and 30% (log rank P = 0.42). Staphylococcus was the predominant organism (66% of identified organisms). Independent predictors of mortality in patients undergoing valve replacement surgery included older age, diabetes as cause of end-stage renal disease, surgery during index hospitalization, staphylococcus as the causative organism, and dysrhythmias as a comorbid condition. Conclusions Valve replacement surgery is appropriate for well-selected dialysis patients with bacterial endocarditis, but is associated with high mortality rates. Survival does not differ with tissue or non-tissue prosthesis. PMID:23785002

  5. Analysis of experimental characteristics of multistage steam-jet electors of steam turbines

    Science.gov (United States)

    Aronson, K. E.; Ryabchikov, A. Yu.; Brodov, Yu. M.; Brezgin, D. V.; Zhelonkin, N. V.; Murmanskii, I. B.

    2017-02-01

    A series of questions for specification of physical gas dynamics model in flow range of steam-jet unit and ejector computation methodology, as well as functioning peculiarities of intercoolers, was formulated based on analysis of experimental characteristics of multistage team-jet steam turbines. It was established that coefficient defining position of critical cross-section of injected flow depends on characteristics of the "sound tube" zone. Speed of injected flow within this tube may exceed that of sound, and pressure jumps in work-steam decrease at the same time. Characteristics of the "sound tube" define optimal axial sizes of the ejector. According to measurement results, the part of steam condensing in the first-stage coolant constitutes 70-80% of steam amount supplied into coolant and is almost independent of air content in steam. Coolant efficiency depends on steam pressure defined by operation of steam-jet unit of ejector of the next stage after coolant of steam-jet stage, temperature, and condensing water flow. As a rule, steam entering content of steam-air mixture supplied to coolant is overheated with respect to saturation temperature of steam in the mixture. This should be taken into account during coolant computation. Long-term operation causes changes in roughness of walls of the ejector's mixing chamber. The influence of change of wall roughness on ejector characteristic is similar to the influence of reverse pressure of the steam-jet stage. Until some roughness value, injection coefficient of the ejector stage operating in superlimiting regime hardly changed. After reaching critical roughness, the ejector switches to prelimiting operating regime.

  6. Replacement of sub-systems

    International Nuclear Information System (INIS)

    Rosen, S.E.

    1992-01-01

    This paper describes a number of quality aspects related to replacement of important systems or components in a nuclear power station. Reference is given to the steam generator replacement and power uprating performed at Ringhals 2 in Sweden in 1989. Since quality is a wide concept there has been put special emphasis in this paper to the important aspects that traditionally are not connected to quality. (author) 1 fig

  7. Steam turbine installations

    International Nuclear Information System (INIS)

    Bainbridge, A.

    1976-01-01

    The object of the arrangement described is to enable raising steam for driving steam turbines in a way suited to operating with liquid metals, such as Na, as heat transfer medium. A preheated water feed, in heat transfer relationship with the liquid metals, is passed through evaporator and superheater stages, and the superheated steam is supplied to the highest pressure stage of the steam turbine arrangement. Steam extracted intermediate the evaporator and superheater stages is employed to provide reheat for the lower pressure stage of the steam turbine. Only a major portion of the preheated water feed may be evaporated and this portion separated and supplied to the superheater stage. The feature of 'steam to steam' reheat avoids a second liquid metal heat transfer and hence represents a simplification. It also reduces the hazard associated with possible steam-liquid metal contact. (U.K.)

  8. Disposal and handling of nuclear steam generator chemical cleaning wastes

    International Nuclear Information System (INIS)

    Larrick, A.P.; Schneidmiller, D.

    1978-01-01

    A large number of pressurized water nuclear reactor electrical generating plants have experienced a corrosion-related problem with their steam generators known as denting. Denting is a mechanical deformation of the steam generator tubes that occurs at the tube support plates. Corrosion of the tube support plates occurs within the annuli through which the tubes pass and the resulting corrosion oxides, which are larger in volume than the original metal, compress and deform the tubes. In some cases, the induced stresses have been severe enough to cause tube and/or support cracking. The problem was so severe at the Turkey Point and Surrey plants that the tubing is being replaced. For less severe cases, chemical cleaning of the oxides, and other materials which deposit in the annuli from the water, is being considered. A Department of Energy-sponsored program was conducted by Consolidated Edison Co. of New York which identified several suitable cleaning solvents and led to in-plant chemical cleaning pilot demonstrations in the Indian Point Unit 1 steam generators. Current programs to improve the technology are being conducted by the Electric Power Research Institute, and the three PWR NSSS vendors with the assistance of numerous consultants, vendors, and laboratories. These programs are expected to result in more effective, less corrosive solvents. However, after a chemical cleaning is conducted, a large problem still remains- that of disposing of the spent wastes. The paper summarizes some of the methods currently available for handling and disposal of the wastes

  9. Mathematical modeling of control system for the experimental steam generator

    Science.gov (United States)

    Podlasek, Szymon; Lalik, Krzysztof; Filipowicz, Mariusz; Sornek, Krzysztof; Kupski, Robert; Raś, Anita

    2016-03-01

    A steam generator is an essential unit of each cogeneration system using steam machines. Currently one of the cheapest ways of the steam generation can be application of old steam generators came from army surplus store. They have relatively simple construction and in case of not so exploited units - quite good general conditions, and functionality of mechanical components. By contrast, electrical components and control systems (mostly based on relay automatics) are definitely obsolete. It is not possible to use such units with cooperation of steam bus or with steam engines. In particular, there is no possibility for automatically adjustment of the pressure and the temperature of the generated steam supplying steam engines. Such adjustment is necessary in case of variation of a generator load. The paper is devoted to description of improvement of an exemplary unit together with construction of the measurement-control system based on a PLC. The aim was to enable for communication between the steam generator and controllers of the steam bus and steam engines in order to construction of a complete, fully autonomic and maintenance-free microcogeneration system.

  10. Mathematical modeling of control system for the experimental steam generator

    Directory of Open Access Journals (Sweden)

    Podlasek Szymon

    2016-01-01

    Full Text Available A steam generator is an essential unit of each cogeneration system using steam machines. Currently one of the cheapest ways of the steam generation can be application of old steam generators came from army surplus store. They have relatively simple construction and in case of not so exploited units – quite good general conditions, and functionality of mechanical components. By contrast, electrical components and control systems (mostly based on relay automatics are definitely obsolete. It is not possible to use such units with cooperation of steam bus or with steam engines. In particular, there is no possibility for automatically adjustment of the pressure and the temperature of the generated steam supplying steam engines. Such adjustment is necessary in case of variation of a generator load. The paper is devoted to description of improvement of an exemplary unit together with construction of the measurement-control system based on a PLC. The aim was to enable for communication between the steam generator and controllers of the steam bus and steam engines in order to construction of a complete, fully autonomic and maintenance-free microcogeneration system.

  11. Ankle replacement

    Science.gov (United States)

    Ankle arthroplasty - total; Total ankle arthroplasty; Endoprosthetic ankle replacement; Ankle surgery ... Ankle replacement surgery is most often done while you are under general anesthesia. This means you will ...

  12. Steam generator waterlancing at DNGS

    International Nuclear Information System (INIS)

    Seppala, D.; Malaugh, J.

    1995-01-01

    Darlington Nuclear Generating Station (DNGS) is a four 900 MW Unit nuclear station forming part of the Ontario Hydro East System. There are four identical steam generators(SGs) per reactor unit. The Darlington SGs are vertical heat exchangers with an inverted U-tube bundle in a cylindrical shell. The DNGS Nuclear Plant Life Assurance Group , a department of DNGS Engineering Services have taken a Proactive Approach to ensure long term SG integrity. Instead of waiting until the tubesheets are covered by a substantial and established hard deposit; DNGS plan to clean each steam generator's tubesheet, first half lattice tube support assembly and bottom of the thermal plate every four years. The ten year business plan provides for cleaning and inspection to be conducted on all four SGs in each unit during maintenance outages (currently scheduled for every four years)

  13. Operating experiences with 1 MW steam generator

    Energy Technology Data Exchange (ETDEWEB)

    Sano, A; Kanamori, A; Tsuchiya, T

    1975-07-01

    1 MW steam generator, which was planned as the first stage of steam generator development in Power Reactor and Nuclear Fuel Corp. (PNC) in Japan, is a single-unit, once-through, integrated shell and tube type with multi-helical coil tubes. It was completed in Oarai Engineering Center of PNC in March of 1971, and the various performance tests were carried out up to April, 1972. After the dismantle of the steam generator for structural inspection and material test, it was restored with some improvements. In this second 1 MW steam generator, small leak occurred twice during normal operation. After repairing the failure, the same kind of performance tests as the first steam generator were conducted in order to verify the thermal insulation effect of argon gas in downcomer zone from March to June, 1974. In this paper the above operating experiences were presented including the outline of some performance test results. (author)

  14. Steam generator with perfected dryers

    International Nuclear Information System (INIS)

    Fenet, J.C.

    1987-01-01

    This steam generator has vertically superposed array of steam dryers. These dryers return the steam flow of 180 0 . The return of the water is made by draining channels to the steam production zone [fr

  15. Gentilly 2 divider plate replacement

    International Nuclear Information System (INIS)

    Forest, J.; Klisel, E.; McClellan, G.; Schnelder, W.

    1995-01-01

    The steam generators at the Gentilly 2 Nuclear Plant in operation since 1983 were built with primary divider plates of a bolted panel configuration. During a routine outage inspection, it was noted that two bolts had dislodged from the divider and were located lying in the primary head. Subsequent inspections revealed erosion damage to a substantial number of divider plate bolts and to a lesser extent, to the divider plate itself. After further inspection and repair the units were returned to operation, however, it was determined that a permanent replacement of the primary divider plates was going to be necessary. After evaluation of various options, it was decided that the panel type dividers would be replaced with a single piece floating design. The divider itself was to be of a one piece all-welded arrangement to be constructed from individual panels to be brought in through the manways. In view of the strength limitations of the bolted attachment of the upper seat bar to the tubesheet, a new welded seat bar was provided. To counteract erosion concerns, the new divider is fitted with erosion resistant inserts or weld buildup and with improved sealing features in order to minimize leakage and erosion. At an advanced stage in the design and manufacture of the components, the issue of divider strength during LOCA conditions came into focus. Analysis was performed to determine the strength and/or failure characteristics of the divider to a variety of small and large LOCA conditions. The paper describes the diagnosis of the original divider plates and the design, manufacture, field mobilization, installation and subsequent operation of the replacement divider plates. (author)

  16. HTGR steam generator development

    International Nuclear Information System (INIS)

    Schuetzenduebel, W.G.; Hunt, P.S.; Weber, M.

    1976-01-01

    More than 40 gas-cooled reactor plants have produced in excess of 400 reactor years of operating experience which have proved a reasonably high rate of gas-cooled reactor steam generator availability. The steam generators used in these reactors include single U-tube and straight-tube steam generators as well as meander type and helically wound or involute tube steam generators. It appears that modern reactors are being equipped with helically wound steam generators of the once-through type as the end product of steam generator evolution in gas-cooled reactor plants. This paper provides a general overview of gas-cooled reactor steam generator evolution and operating experience and shows how design criteria and constraints, research and development, and experience data are factored into the design/development of modern helically wound tube steam generators for the present generation of gas-cooled reactors

  17. Steam Digest 2001

    Energy Technology Data Exchange (ETDEWEB)

    2002-01-01

    Steam Digest 2001 chronicles BestPractices Program's contributions to the industrial trade press for 2001, and presents articles that cover technical, financial and managerial aspects of steam optimization.

  18. Steam generator tube extraction

    International Nuclear Information System (INIS)

    Delorme, H.

    1985-05-01

    To enable tube examination on steam generators in service, Framatome has now developed a process for removing sections of steam generator tubes. Tube sections can be removed without being damaged for treating the tube section expanded in the tube sheet

  19. Analisis Bahaya dengan Metode Hazop dan Manajemen Risiko pada Steam Turbine PLTU di Unit 5 Pembangkitan Listrik Paiton (PT. YTL Jawa Timur

    Directory of Open Access Journals (Sweden)

    Erna Zulfiana

    2013-09-01

    Full Text Available Steam turbine beroperasi pada temperatur dan tekanan uap yang tinggi sehingga keamanan proses harus dijaga agar tidak terjadi bahaya yang menimbulkan risiko. Untuk analisis dan identifikasi bahaya digunakan metode HAZOP yang selanjutnya melakukan manajemen resiko berupa emergency respon plan berdasarkan bahaya yang mungkin terjadi pada PLTU. Identifikasi bahaya dengan metode HAZOP dilakukan dengan penentuan 4 node pada steam turbine yaitu HP Turbine, IP Turbine, LP Turbine 1 dan LP Turbine 2, penentuan guideword dan deviasi berdasarkan control chart data proses transmitter di setiap node, dan untuk estimasi likelihood berdasarkan nilai MTTF tiap transmitter. ERP pada steam turbine dibuat untuk kejadian kebakaran karena berisiko tinggi dan kemungkinan besar terjadi serta dapat menyebabkan bahaya lain seperti ledakan dsb. Dari penelitian ini diketahui kondisi yang paling berbahaya pada steam turbine adalah kondisi high pressure yang diketahui dari risk matrix pressure trasnmitter pada 4 node yang bernilai high dan ekstrim yang dapat menyebabkan turbin mengalami overspeed. Rekomendasi untuk menanggulangi bahaya tersebut antara lain pemasangan pressure alarm, simulasi automatic turbine test, pemeriksaan turbine overspeed protection serta kalibrasi maupun pengecekan pada pressure trasnmitter tersebut.

  20. Theoretical and experimental work on steam generator integrity and reliability with particular reference to leak development and detection. United Kingdom status report. October 1983

    International Nuclear Information System (INIS)

    Smedley, J.A.; Edge, D.M.

    1984-01-01

    This paper reviews the experimental and theoretical work in the UK on the characteristics of sodium-water reactions and describes work on the development of leak detection systems. A review of the operating experience with the PFR steam generators and the protection philosophy used on PFR is also given and the design studies for the Commercial Demonstration Fast Reactor (CDFR) are described

  1. Steam sterilization does not require saturated steam

    NARCIS (Netherlands)

    van Doornmalen Gomez Hoyos, J. P.C.M.; Paunovic, A.; Kopinga, K.

    2017-01-01

    The most commonly applied method to sterilize re-usable medical devices in hospitals is steam sterilization. The essential conditions for steam sterilization are derived from sterilization in water. Microbiological experiments in aqueous solutions have been used to calculate various time–temperature

  2. Understanding the continuous renal replacement therapy circuit for acute renal failure support: a quality issue in the intensive care unit.

    Science.gov (United States)

    Boyle, Martin; Baldwin, Ian

    2010-01-01

    Delivery of renal replacement therapy is now a core competency of intensive care nursing. The safe and effective delivery of this form of therapy is a quality issue for intensive care, requiring an understanding of the principles underlying therapy and the functioning of machines used. Continuous hemofiltration, first described in 1977, used a system where blood flowed from arterial to venous cannulas through a small-volume, low-resistance, and high-flux filter. Monitoring of these early systems was limited, and without a machine interface, less nursing expertise was required. Current continuous renal replacement therapy machines offer user-friendly interfaces, cassette-style circuits, and comprehensive circuit diagnostics and monitoring. Although these machines conceal complexity behind a user-friendly interface, it remains important that nurses have sufficient knowledge for their use and the ability to compare and contrast circuit setups and functions for optimal and efficient treatment.

  3. The Invisibility of Steam

    Science.gov (United States)

    Greenslade, Thomas B., Jr.

    2014-01-01

    Almost everyone "knows" that steam is visible. After all, one can see the cloud of white issuing from the spout of a boiling tea kettle. In reality, steam is the gaseous phase of water and is invisible. What you see is light scattered from the tiny droplets of water that are the result of the condensation of the steam as its temperature…

  4. Strategies for steam

    International Nuclear Information System (INIS)

    Hennagir, T.

    1996-01-01

    This article is a review of worldwide developments in the steam turbine and heat recovery steam generator markets. The Far East is driving the market in HRSGs, while China is driving the market in orders placed for steam turbine prime movers. The efforts of several major suppliers are discussed, with brief technical details being provided for several projects

  5. Steam Digest: Volume IV

    Energy Technology Data Exchange (ETDEWEB)

    2004-07-01

    This edition of the Steam Digest is a compendium of 2003 articles on the technical and financial benefits of steam efficiency, presented by the stakeholders of the U.S. Department of Energy's BestPractices Steam effort.

  6. Steam Digest Volume IV

    Energy Technology Data Exchange (ETDEWEB)

    None

    2004-07-01

    This edition of the Steam Digest is a compendium of 2003 articles on the technical and financial benefits of steam efficiency, presented by the stakeholders of the U.S. Department of Energy's BestPractices Steam effort.

  7. Corrosion Product Measurements to ensure integrity of the Steam Generators in Beznau NPP

    International Nuclear Information System (INIS)

    Mailand, Irene; Franz, Patrick; Venz, Hartmut

    2012-09-01

    The Nuclear Power Plant Beznau comprises two identical 380 MWe PWR units with two loops each, commissioned in 1969 and 1971. Westinghouse was responsible for the primary part of the plant and BBC/ABB for the secondary circuit. The original materials used in the secondary systems were made of several copper-based alloys, such as for the Condensers, the Low Pressure Pre-heaters and the Moisture Separator Re-heater. The original Steam Generator Tubes were made of Inconel 600 MA. Regarding its age, the NPP Beznau has to be qualified as an old plant. However, in fact particularly in the last 20 years the plant has undergone an extensive modernisation programme in which about 1.5 billion Swiss Francs have been invested. Important measures were the replacements of the Steam Generators with tubes comprising Inconel 690 TT which was realized at unit 1 in 1993 and at unit 2 in 1999. Copper was completely banished from the secondary system and replaced by stainless and chromium steel. The Condensers were fitted with titanium tubes. The secondary water chemistry had to be changed by these replacements and moved step by step from Low-AVT with a pH of about 9.3 to High-AVT with a pH of 9.8 to 9.9, currently. To ensure the integrity of the new Steam Generators as well as of the whole Secondary System a corrosion product programme was introduced at the end of the Nineties. Several investigations which are performed periodically are represented by analyses of corrosion products, measurements of sludge mass and composition in the Steam Generators, Hide-Out-Return- and mass balance measurements of corrosion products in the whole circuit. Objectives of these investigations are assessments of the efficiency of the water chemistry and trend considerations regarding to the transport of corrosion products and pollutants into the Steam Generator, as well as of the potential danger of deposits and stored or absorbed pollutants. The main target of all measures is to avoid any chemical

  8. Failure analysis of retired steam generator tubings

    Energy Technology Data Exchange (ETDEWEB)

    Kim, Hong Pyo; Kim, J. S.; Hwang, S. S. and others

    2005-04-15

    Degradation of steam generator leads to forced outage and extension of outage, which causes increase in repair cost, cost of purchasing replacement power and radiation exposure of workers. Steam generator tube rupture incident occurred in Uljin 4 in 2002, which made public sensitive to nuclear power plant. To keep nuclear energy as a main energy source, integrity of steam generator should be demonstrated. Quantitative relationship between ECT(eddy current test) signal and crack size is needed in assesment of integrity of steam generator in pressurized water reactor. However, it is not fully established for application in industry. Retired steam generator of Kori 1 has many kinds of crack such as circumferential and axial primary water stress corrosion crack and outer diameter stress corrosion crack(ODSCC). So, it can be used in qualifying and improving ECT technology and in condition monitoring assesment for crack detected in ISI(in service inspection). In addition, examination of pulled tube of Kori 1 retired steam generator will give information about effectiveness of non welded sleeving technology which was employed to repair defect tubes and remedial action which was applied to mitigate ODSCC. In this project, hardware such as semi hot lab. for pulled tube examination and modification transportation cask for pulled tube and software such as procedure of transportation of radioactive steam generator tube and non-destructive and destructive examination of pulled tube were established. Non-destructive and destructive examination of pulled tubes from Kori 1 retired steam generator were performed in semi hot lab. Remedial actions applied to Kori 1 retired steam generator, PWSCC trend and bulk water chemistry and crevice chemistry in Kori 1 were evaluated. Electrochemical decontamination technology for pulled tube was developed to reduce radiation exposure and enhance effectiveness of pulled tube examination. Multiparameter algorithm developed at ANL, USA was

  9. Development of a steam generator lancing system

    International Nuclear Information System (INIS)

    Jeong, Woo-Tae; Kim, Seok-Tae; Hong, Sung-Yull

    2006-01-01

    It is recommended to clean steam generators of nuclear power plants during plant outages. Under normal operations, sludge is created and constantly accumulates in the steam generators. The constituents of this sludge are different depending on each power plant characteristics. The sludge of the Kori Unit 1 steam generator, for example, was found to be composed of 93% ferrous oxide, 3% carbon and 1% of silica oxide and nickel oxide each. The research to develop a lancing system that would remove sludge deposits from the tubesheet of a steam generator was started in 1998 by the Korea Electric Power Research Institute (KEPRI) of the Korea Electric Power Corporation (KEPCO). The first commercial domestic lancing system in Korea, and KALANS-I Lancing System, was completed in 2000 for Kori Unit 1 for cleaning the tubesheet of its Westinghouse Delta-60 steam generator. Thereafter, the success of the development and site implementation of the KALANS-I lancing system for YGN Units 1 and 2 and Ulchin Units 3 and 4 was also realized in 2004 for sludge removal at those sites. The upper bundle cleaning system for Westinghouse model F steam generators is now under development

  10. Potential nutritional and economic effects of replacing juice with fruit in the diets of children in the United States

    Science.gov (United States)

    Monsivais, Pablo; Rehm, Colin D

    2013-01-01

    Context Dietary guidance for children emphasizes fruit over fruit juices but little is known about the potential nutritional and economic impact of substituting fruit for juice. Objective To estimate the nutritional and economic effects of substituting whole fruit for juice in the diets of children in the US. Design Secondary analyses using the 2001-2004 National Health and Nutrition Examination Survey (NHANES) and a national food price database. Energy, nutrient intakes and diet cost were estimated before and after fruit juices were completely replaced with fruit in three models that emphasized fruits that were fresh, low-cost, and widely-consumed and a fourth model that partially replaced juice with fruit, capping juice at recommended levels. Setting A nationwide, representative sample of children in the US. Participants 7,023 children ages 3-18. Main Outcome Measures Difference in energy, nutrient intakes and diet cost between observed and modeled diets. Results For children who consumed juice, replacement of all juice servings with fresh, whole fruit led to a projected reduction in dietary energy of 233 kJ/day (−2.6% [95% CI −5.1, −0.1%]), an increase in fiber of 4.3 grams/day (+31.1% [95% CI 26.4, 35.9%]) and an increase in diet cost of $0.54/day (+13.3% [95% CI 8.8, 17.8%]). Conclusions Substitution of juice with fresh fruit has the potential to reduce energy intake and improve the adequacy of fiber intake in children’s diets. This would likely increase costs for schools, childcare providers and families. Cost impacts could be minimized by selecting processed fruits but fewer nutritional gains would be achieved. PMID:22566547

  11. Optimal inspection and replacement periods of the safety system in Wolsung Nuclear Power Plant Unit 1 with an optimized cost perspective

    International Nuclear Information System (INIS)

    Jinil Mok; Poong Hyun Seong

    1996-01-01

    In this work, a model for determining the optimal inspection and replacement periods of the safety system in Wolsung Nuclear Power Plant Unit 1 is developed, which is to minimize economic loss caused by inadvertent trip and the system failure. This model uses cost benefit analysis method and the part for optimal inspection period considers the human error. The model is based on three factors as follows: (i) The cumulative failure distribution function of the safety system, (ii) The probability that the safety system does not operate due to failure of the system or human error when the safety system is needed at an emergency condition and (iii) The average probability that the reactor is tripped due to the failure of system components or human error. The model then is applied to evaluate the safety system in Wolsung Nuclear Power Plant Unit 1. The optimal replacement periods which are calculated with proposed model differ from those used in Wolsung NPP Unit 1 by about a few days or months, whereas the optimal inspection periods are in about the same range. (author)

  12. Africanization in the United States: Replacement of Feral European Honeybees (Apis mellifera L.) by an African Hybrid Swarm

    OpenAIRE

    Pinto, M. Alice; Rubink, William L.; Patton, John C.; Coulson, Robert N.; Johnston, J. Spencer

    2005-01-01

    The expansion of Africanized honeybees from South America to the southwestern United States in 50 years is considered one of the most spectacular biological invasions yet documented. In the American tropics, it has been shown that during their expansion Africanized honeybees have low levels of introgressed alleles from resident European populations. In the United States, it has been speculated, but not shown, that Africanized honeybees would hybridize extensively with European ho...

  13. Control system for fluid heated steam generator

    Science.gov (United States)

    Boland, J.F.; Koenig, J.F.

    1984-05-29

    A control system for controlling the location of the nucleate-boiling region in a fluid heated steam generator comprises means for measuring the temperature gradient (change in temperature per unit length) of the heating fluid along the steam generator; means for determining a control variable in accordance with a predetermined function of temperature gradients and for generating a control signal in response thereto; and means for adjusting the feedwater flow rate in accordance with the control signal.

  14. Steam atmosphere drying concepts using steam exhaust recompression

    Energy Technology Data Exchange (ETDEWEB)

    DiBella, F.A. (TECOGEN, Inc., Waltham, MA (United States))

    1992-08-01

    In the US industrial drying accounts for approximately 1.5 quads of energy use per year. Annual industrial dryer expenditures are estimated to be in the $500 million range. Industrial drying is a significant energy and monetary expense. For the thermal drying processes in which water is removed via evaporation from the feedstock, attempts have been made to reduce the consumption of energy using exhaust waste heat recovery techniques, improved dryer designs, or even the deployment of advanced mechanical dewatering techniques. Despite these efforts, it is obvious that a large amount of thermal energy is often still lost if the latent heat of evaporation from the evaporated water cannot be recovered and/or in some way be utilized as direct heat input into the dryer. Tecogen Inc. is conducting research and development on an industrial drying concept. That utilizes a directly or indirectly superheated steam cycle atmosphere with exhaust steam recompression to recover the latent heat in the exhaust that would otherwise be lost. This approach has the potential to save 55 percent of the energy required by a conventional air dryer. Other advantages to the industrial dryer user include: A 35-percent reduction in the yearly cost per kg[sub evap] to dry wet feedstock, Reduced airborne emissions, Reduced dry dust fire/explosion risks, Hot product not exposed to oxygen thus, the product quality is enhanced, Constant rate drying in steam atmosphere, Reduced dryer size and cost, Reduced dryer heat losses due to lower dryer inlet temperatures. Tecogen has projected that the steam atmosphere drying system is most suitable as a replacement technology for state-of-the-art spray, flash, and fluidized bed drying systems. Such systems are utilized in the food and kindred products; rubber products; chemical and allied products; stone, clay, and glass; textiles; and pulp and paper industrial sectors.

  15. Steam atmosphere drying concepts using steam exhaust recompression

    Energy Technology Data Exchange (ETDEWEB)

    DiBella, F.A. [TECOGEN, Inc., Waltham, MA (United States)

    1992-08-01

    In the US industrial drying accounts for approximately 1.5 quads of energy use per year. Annual industrial dryer expenditures are estimated to be in the $500 million range. Industrial drying is a significant energy and monetary expense. For the thermal drying processes in which water is removed via evaporation from the feedstock, attempts have been made to reduce the consumption of energy using exhaust waste heat recovery techniques, improved dryer designs, or even the deployment of advanced mechanical dewatering techniques. Despite these efforts, it is obvious that a large amount of thermal energy is often still lost if the latent heat of evaporation from the evaporated water cannot be recovered and/or in some way be utilized as direct heat input into the dryer. Tecogen Inc. is conducting research and development on an industrial drying concept. That utilizes a directly or indirectly superheated steam cycle atmosphere with exhaust steam recompression to recover the latent heat in the exhaust that would otherwise be lost. This approach has the potential to save 55 percent of the energy required by a conventional air dryer. Other advantages to the industrial dryer user include: A 35-percent reduction in the yearly cost per kg{sub evap} to dry wet feedstock, Reduced airborne emissions, Reduced dry dust fire/explosion risks, Hot product not exposed to oxygen thus, the product quality is enhanced, Constant rate drying in steam atmosphere, Reduced dryer size and cost, Reduced dryer heat losses due to lower dryer inlet temperatures. Tecogen has projected that the steam atmosphere drying system is most suitable as a replacement technology for state-of-the-art spray, flash, and fluidized bed drying systems. Such systems are utilized in the food and kindred products; rubber products; chemical and allied products; stone, clay, and glass; textiles; and pulp and paper industrial sectors.

  16. Knee Replacement

    Science.gov (United States)

    Knee replacement is surgery for people with severe knee damage. Knee replacement can relieve pain and allow you to ... Your doctor may recommend it if you have knee pain and medicine and other treatments are not ...

  17. Safety Management of a Clinical Process Using Failure Mode and Effect Analysis: Continuous Renal Replacement Therapies in Intensive Care Unit Patients.

    Science.gov (United States)

    Sanchez-Izquierdo-Riera, Jose Angel; Molano-Alvarez, Esteban; Saez-de la Fuente, Ignacio; Maynar-Moliner, Javier; Marín-Mateos, Helena; Chacón-Alves, Silvia

    2016-01-01

    The failure mode and effect analysis (FMEA) may improve the safety of the continuous renal replacement therapies (CRRT) in the intensive care unit. We use this tool in three phases: 1) Retrospective observational study. 2) A process FMEA, with implementation of the improvement measures identified. 3) Cohort study after FMEA. We included 54 patients in the pre-FMEA group and 72 patients in the post-FMEA group. Comparing the risks frequencies per patient in both groups, we got less cases of under 24 hours of filter survival time in the post-FMEA group (31 patients 57.4% vs. 21 patients 29.6%; p FMEA, there were several improvements in the management of intensive care unit patients receiving CRRT, and we consider it a useful tool for improving the safety of critically ill patients.

  18. Fourth international seminar on horizontal steam generators

    Energy Technology Data Exchange (ETDEWEB)

    Tuomisto, H. [ed.] [IVO Group, Vantaa (Finland); Purhonen, H. [ed.] [VTT, Espoo (Finland); Kouhia, V. [ed.] [Lappeenranta Univ. of Technology (Finland)

    1997-12-31

    The general objective of the International Seminars of Horizontal Steam Generator Modelling has been the improvement in understanding of realistic thermal hydraulic behaviour of the generators when performing safety analyses for VVER reactors. The main topics presented in the fourth seminar were: thermal hydraulic experiments and analyses, primary collector integrity, feedwater distributor replacement, management of primary-to-secondary leakage accidents and new developments in the VVER safety technology. The number of participants, representing designers and manufacturers of the horizontal steam generators, plant operators, engineering companies, research organizations, universities and regulatory authorities, was 70 from 10 countries.

  19. Fourth international seminar on horizontal steam generators

    Energy Technology Data Exchange (ETDEWEB)

    Tuomisto, H [ed.; IVO Group, Vantaa (Finland); Purhonen, H [ed.; VTT, Espoo (Finland); Kouhia, V [ed.; Lappeenranta Univ. of Technology (Finland)

    1998-12-31

    The general objective of the International Seminars of Horizontal Steam Generator Modelling has been the improvement in understanding of realistic thermal hydraulic behaviour of the generators when performing safety analyses for VVER reactors. The main topics presented in the fourth seminar were: thermal hydraulic experiments and analyses, primary collector integrity, feedwater distributor replacement, management of primary-to-secondary leakage accidents and new developments in the VVER safety technology. The number of participants, representing designers and manufacturers of the horizontal steam generators, plant operators, engineering companies, research organizations, universities and regulatory authorities, was 70 from 10 countries.

  20. Fourth international seminar on horizontal steam generators

    International Nuclear Information System (INIS)

    Tuomisto, H.; Purhonen, H.; Kouhia, V.

    1997-01-01

    The general objective of the International Seminars of Horizontal Steam Generator Modelling has been the improvement in understanding of realistic thermal hydraulic behaviour of the generators when performing safety analyses for VVER reactors. The main topics presented in the fourth seminar were: thermal hydraulic experiments and analyses, primary collector integrity, feedwater distributor replacement, management of primary-to-secondary leakage accidents and new developments in the VVER safety technology. The number of participants, representing designers and manufacturers of the horizontal steam generators, plant operators, engineering companies, research organizations, universities and regulatory authorities, was 70 from 10 countries

  1. Steam Turbine Flow Path Seals (a Review)

    Science.gov (United States)

    Neuimin, V. M.

    2018-03-01

    Various types of shroud, diaphragm, and end seals preventing idle leak of working steam are installed in the flow paths of steam turbine cylinders for improving their efficiency. Widely known labyrinth seals are most extensively used in the Russian turbine construction industry. The category of labyrinth seals also includes seals with honeycomb inserts. The developers of seals with honeycomb inserts state that the use of such seals makes it possible to achieve certain gain due to smaller leaks of working fluid and more reliable operation of the system under the conditions in which the rotor rotating parts may rub against the stator elements. However, a positive effect can only be achieved if the optimal design parameters of the honeycomb structure are fulfilled with due regard to the specific features of its manufacturing technology and provided that this structure is applied in a goal-seeking manner in the seals of steam and gas turbines and compressors without degrading their vibration stability. Calculated and preliminary assessments made by experts testify that the replacement of conventional labyrinth seals by seals with honeycomb inserts alone, due to which the radial gaps in the shroud seal can be decreased from 1.5 to 0.5 mm, allows the turbine cylinder efficiency to be increased at the initial stage by approximately 1% with the corresponding gain in the turbine set power output. The use of rectangular-cellular seals may result, according to estimates made by their developers, in a further improvement of turbine efficiency by 0.5-1.0%. The labor input required to fabricate such seals is six to eight times smaller than that to fabricate labyrinth seals with honeycomb inserts. Recent years have seen the turbine construction companies of the United States and Germany advertising the use of abradable (sealing) coatings (borrowed from the gas turbine construction technology) in the turbine designs instead of labyrinth seals. The most efficient performance of

  2. Future development of large steam turbines

    International Nuclear Information System (INIS)

    Chevance, A.

    1975-01-01

    An attempt is made to forecast the future of the large steam turbines till 1985. Three parameters affect the development of large turbines: 1) unit output; and a 2000 to 2500MW output may be scheduled; 2) steam quality: and two steam qualities may be considered: medium pressure saturated or slightly overheated steam (light water, heavy water); light enthalpie drop, high pressure steam, high temperature; high enthalpic drop; and 3) the quality of cooling supply. The largest range to be considered might be: open system cooling for sea-sites; humid tower cooling and dry tower cooling. Bi-fluid cooling cycles should be also mentioned. From the study of these influencing factors, it appears that the constructor, for an output of about 2500MW should have at his disposal the followings: two construction technologies for inlet parts and for high and intermediate pressure parts corresponding to both steam qualities; exhaust sections suitable for the different qualities of cooling supply. The two construction technologies with the two steam qualities already exist and involve no major developments. But, the exhaust section sets the question of rotational speed [fr

  3. The EBR-II steam generating system - operation, maintenance, and inspection

    International Nuclear Information System (INIS)

    Buschman, H.W.; Penney, W.H.; Longua, K.J.

    2002-01-01

    The Experimental Breeder Reactor II (EBR-II) has operated for 20 years at the Idaho National Engineering Laboratory near Idaho Falls. EBR-II is a Liquid Metal Fast Breeder Reactor (LMFBR) with integrated power producing capability. EBR-II has operated at a capacity factor over 70% in the past few years. Superheated steam is produced by eight natural circulation evaporators, two superheaters, and a conventional steam drum. Steam throttle conditions are 438 C and 8.62 MPa. The designs of the evaporators and superheaters are essentially identical; both are counterflow units with low pressure nonradioactive sodium on the shell side. During the 20 years of operation, components of the steam generator have been subjected to a variety of inspections including visual, dimensional, and ultrasonic. One superheater was removed from service because of anomalous performance and was replaced with an evaporator which was removed, examined, and converted into a superheater. Overall operating experience of the system has been excellent and essentially trouble free. Inspections have not revealed any conditions that are performance or life limiting. (author)

  4. Safety evaluation report related to the operation of Susquehanna Steam Electric Station, Units 1 and 2. Docket Nos. 50-387 and 50-388, Pennsylvania Power and Light Company and Allegheny Electric Cooperative, Inc

    International Nuclear Information System (INIS)

    1982-11-01

    In April 1981, the staff of the Nuclear Regulatory Commission issued its Safety Evaluation Report (NUREG-0776) regarding the application of the Pennsylvania Power and Light Company (the licensee) and the Allegheny Electric Cooperative, Inc. (co-licensee) for licenses to operate the Susquehanna Steam Electric Station, Units 1 and 2, located on a site in Luzerne County, Pennsylvania. Supplement 1, issued in June 1981, addressed outstanding issues. Supplement 2, issued in September 1981, contains the ACRS Report and responses. Supplement 3, issued in July 1982, contains the resolution to five items previously identified as open and closes them out. On July 17, 1982, License NPF-14 was issued to allow Unit 1 operation at power levels not to exceed 5% of rated power. This supplement discusses the resolution of several license conditions that have been met

  5. Nuclear facilities: repair and replacement technologies; Installations nucleaires: technologies de reparation et de remplacement

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2005-07-01

    The oldest operating reactors are more than 35 years old and are now facing major maintenance operations. The first replacement of a pressurizer took place in autumn 2005 at the St-Lucie plant (Usa) while steam generators have been currently replaced since 1983. Nuclear industry has to adapt to this new market by proposing innovative technological solutions in the reactor maintenance field. This document gathers the 9 papers presented at the conference. The main improvements concern repair works on internal components of PWR-type reactors, the replacement of major components of the primary coolant circuit and surface treatments to limit the propagation of damages. The first paper shows that adequate design and feedback experience are good assets to manage the ageing of a nuclear unit. Another paper shows that a new repair method of a relief valve can avoid its replacement. (A.C.)

  6. Condensation of steam

    International Nuclear Information System (INIS)

    Prisyazhniuk, V.A.

    2002-01-01

    An equation for nucleation kinetics in steam condensation has been derived, the equation taking into account the concurrent and independent functioning of two nucleation mechanisms: the homogeneous one and the heterogeneous one. The equation is a most general-purpose one and includes all the previously known condensation models as special cases. It is shown how the equation can be used in analyzing the process of steam condensation in the condenser of an industrial steam-turbine plant, and in working out new ways of raising the efficiency of the condenser, as well as of the steam-turbine plant as a whole. (orig.)

  7. EPRI steam generator programs

    International Nuclear Information System (INIS)

    Martel, L.J.; Passell, T.O.; Bryant, P.E.C.; Rentler, R.M.

    1977-01-01

    The paper describes the current overall EPRI steam generator program plan and some of the ongoing projects. Because of the recent occurrence of a corrosion phenomenon called ''denting,'' which has affected a number of operating utilities, an expanded program plan is being developed which addresses the broad and urgent needs required to achieve improved steam generator reliability. The goal of improved steam generator reliability will require advances in various technologies and also a management philosophy that encourages conscientious efforts to apply the improved technologies to the design, procurement, and operation of plant systems and components that affect the full life reliability of steam generators

  8. Future development LMFBR-steam generators SNR2

    International Nuclear Information System (INIS)

    Essebaggers, J.; Pors, J.G.

    1975-01-01

    The development work for steam generators for large LMFBR plants by Neratoom will be reviewed consisting of: 1. Development engineering information. 2. Concept select studies followed by conceptual designs of selected models. 3. Development manufacturing techniques. 4. Detail design of a prototype unit. 5. Testing of sub-constructions for prototype steam generators. In this presentation item 1 and 2 above will be high lighted, identifying the development work for the SNR-2 steam generators on short term basis. (author)

  9. The Creys Malville FBR Super Phenix steam generators

    International Nuclear Information System (INIS)

    Baque, P.; Zuber, T.; Saur, J.M.; Cambillard, E.

    1980-08-01

    After briefly recalling the French experience on sodium steam generators, the authors describe the design concepts of the Superphenix units and give their main characteristics. A short summary of the realized R and D program precedes the description of the four 750-MWt steam generators, the fabrication of which is in progress by Creusot-Loire at Chalon sur Saone (France). The studies started for the next French fast breeder reactors and their steam generators are mentioned

  10. Changing the simualtor's steam generator

    International Nuclear Information System (INIS)

    Ruiz Martin, J.A.; Ortega Pascual, F.

    2006-01-01

    Two Spanish nuclear power plants (two PWR units each one) have planned to change their Westinghouse D-3 steam generators (SGo henceforth) for a new model, 61W/D3 from Siemens/KWU (SGn henceforth), during 1995/1997. This is the reason why TECNATOM has developed during 1994's last term, a new software for the full scope simulator that incorporates the modifications related to the steam generator substiution programme. This allows an anticipated training on the procedures, not only for normal, but for emergency procedures. As it is a component which has not yet been included in these plants, there are not real references or operative experience data. Therefore, the design of the validation strategy was one of the key points in this work. (author)

  11. High-temperature oxidation of Zircaloy in hydrogen-steam mixtures

    International Nuclear Information System (INIS)

    Chung, H.M.; Thomas, G.R.

    1982-09-01

    Oxidation rates of Zircaloy-4 cladding tubes have been measured in hydrogen-steam mixtures at 1200 to 1700 0 C. For a given isothermal oxidation temperature, the oxide layer thicknesses have been measured as a function of time, steam supply rate, and hydrogen overpressure. The oxidation rates in the mixtures were compared with similar data obtained in pure steam and helium-steam environments under otherwise identical conditions. The rates in pure steam and helium-steam mixtures were equivalent and comparable to the parabolic rates obtained under steam-saturated conditions and reported in the literature. However, when the helium was replaced with hydrogen of equivalent partial pressure, a significantly smaller oxidation rate was observed. For high steam-supply rates, the oxidation kinetics in a hydrogen-steam mixture were parabolic, but the rate was smaller than for pure steam or helium-steam mixtures. Under otherwise identical conditions, the ratio of the parabolic rate for hydrogen-steam to that for pure steam decreased with increasing temperature and decreasing steam-supply rate

  12. Shiraz solar power plant operation with steam engine

    International Nuclear Information System (INIS)

    Yaghoubi, M.; Azizian, K.

    2004-01-01

    The present industrial developments and daily growing need of energy, as well as economical and environmental problem caused by fossil fuels consumption, resulted certain constraint for the future demand of energy. During the past two decades great attention has been made to use renewable energy for different sectors. In this regard for the first time in Iran, design and construction of a 250 K W Solar power plant in Shiraz, Iran is being carried out and it will go to operation within next year. The important elements of this power plant is an oil cycle and a steam cycle, and several studies have been done about design and operation of this power plant, both for steady state and transient conditions. For the steam cycle, initially a steam turbine was chosen and due to certain limitation it has been replaced by a steam engine. The steam engine is able to produce electricity with hot or saturated vapor at different pressures and temperatures. In this article, the effects of installing a steam engine and changing its vapor inlet pressure and also the effects of sending hot or saturated vapor to generate electricity are studied. Various cycle performance and daily electricity production are determined. The effects of oil cycle temperature on the collector field efficiency, and daily, monthly and annual amount of electricity production is calculated. Results are compared with the steam cycle output when it contains a steam turbine. It is found that with a steam engine it is possible to produce more annual electricity for certain conditions

  13. STEAM by Design

    Science.gov (United States)

    Keane, Linda; Keane, Mark

    2016-01-01

    We live in a designed world. STEAM by Design presents a transdisciplinary approach to learning that challenges young minds with the task of making a better world. Learning today, like life, is dynamic, connected and engaging. STEAM (Science, Technology, Environment, Engineering, Art, and Math) teaching and learning integrates information in…

  14. Steampunk: Full Steam Ahead

    Science.gov (United States)

    Campbell, Heather M.

    2010-01-01

    Steam-powered machines, anachronistic technology, clockwork automatons, gas-filled airships, tentacled monsters, fob watches, and top hats--these are all elements of steampunk. Steampunk is both speculative fiction that imagines technology evolved from steam-powered cogs and gears--instead of from electricity and computers--and a movement that…

  15. Safety Picks up "STEAM"

    Science.gov (United States)

    Roy, Ken

    2016-01-01

    This column shares safety information for the classroom. STEAM subjects--science, technology, engineering, art, and mathematics--are essential for fostering students' 21st-century skills. STEAM promotes critical-thinking skills, including analysis, assessment, categorization, classification, interpretation, justification, and prediction, and are…

  16. Steam power plant

    International Nuclear Information System (INIS)

    Campbell, J.W.E.

    1981-01-01

    This invention relates to power plant forced flow boilers operating with water letdown. The letdown water is arranged to deliver heat to partly expanded steam passing through a steam reheater connected between two stages of the prime mover. (U.K.)

  17. Steam generator operating experience: Update for 1984-1986

    International Nuclear Information System (INIS)

    Frank, L.; Stokley, J.

    1988-06-01

    This report summarizes operational events and degradation mechanisms affecting pressurized water reactor steam generator integrity, provides updated inspection results reported in 1984, 1985, and 1986, and highlights both prevalent problem areas and advances in improved equipment test practices, preventive measures, repair techniques, and replacement procedures. It describes equipment design features of the three major suppliers and discusses 68 plants in detail. Steam generator degradation mechanisms include intergranular stress corrosion cracking, primary water stress corrosion cracking, pitting, intergranular attack, and vibration wear that effects tube integrity and causes leakage. Plugging, sleeving heat treatment, peening, chemical cleaning, and steam generator replacements are described and regulatory instruments and inspection guidelines for nondestructive evaluations and girth weld cracking are discusses. The report concludes that although degradation mechanisms are generally understood, the elimination of unscheduled plant shutdowns and costly repairs resulting from leaking tubes has not been achieved. Highlights of steam generator research and unresolved safety issues are discussed. 21 refs., 8 tabs

  18. Targeted steam injection using horizontal wells with limited entry perforations

    Energy Technology Data Exchange (ETDEWEB)

    Boone, T. J.; Youck, D. G.; Sun, S. [Imperial Oil Resources, Calgary, AB (Canada)

    1998-12-31

    An experimental horizontal well using limited-entry perforations as a method for distributing steam to different zones was used to replace ten vertical injection wells. The well was located between rows of vertical wells in a reservoir that has been subjected to more than ten years of operation under cyclic steam stimulation. The limited-entry perforations enabled steam to be targeted at the cold regions of the reservoir. This paper presents an assessment of the well based on theoretical calculations, measured injection pressures and rates and 3-D seismic imaging. All the data collected during the experiment support the conclusion that effective steam distribution along the well has been achieved. It was also concluded that this technology has significant potential for SAGD applications as a mechanism for achieving improved steam distribution at a much reduced cost. 5 refs., 8 figs.

  19. Steam generator life management

    International Nuclear Information System (INIS)

    Tapping, R.L.; Nickerson, J.; Spekkens, P.; Maruska, C.

    1998-01-01

    Steam generators are a critical component of a nuclear power reactor, and can contribute significantly to station unavailability, as has been amply demonstrated in Pressurized Water Reactors (PWRs). CANDU steam generators are not immune to steam generator degradation, and the variety of CANDU steam generator designs and tube materials has led to some unexpected challenges. However, aggressive remedial actions, and careful proactive maintenance activities, have led to a decrease in steam generator-related station unavailability of Canadian CANDUs. AECL and the CANDU utilities have defined programs that will enable existing or new steam generators to operate effectively for 40 years. Research and development work covers corrosion and mechanical degradation of tube bundles and internals, chemistry, thermal hydraulics, fouling, inspection and cleaning, as well as provision for specially tool development for specific problem solving. A major driving force is development of CANDU-specific fitness-for-service guidelines, including appropriate inspection and monitoring technology to measure steam generator condition. Longer-range work focuses on development of intelligent on-line monitoring for the feedwater system and steam generator. New designs have reduced risk of corrosion and fouling, are more easily inspected and cleaned, and are less susceptible to mechanical damage. The Canadian CANDU utilities have developed programs for remedial actions to combat degradation of performance (Gentilly-2, Point Lepreau, Bruce A/B, Pickering A/B), and have developed strategic plans to ensure that good future operation is ensured. This report shows how recent advances in cleaning technology are integrated into a life management strategy, discusses downcomer flow measurement as a means of monitoring steam generator condition, and describes recent advances in hideout return as a life management tool. The research and development program, as well as operating experience, has identified

  20. Device to measure level in a steam drum of NPP

    International Nuclear Information System (INIS)

    Vinogradov, Yu.A.

    1988-01-01

    Gravitation-hydrostatic device for measuring coolant level in a steam drum of NPP is described. The device enables to improve the accuracy and sensitivity of measuring coolant level above and below the submerged perforated sheet of the steam drum and decrease the amount of levelling vessels in the unit by 50%. 1 fig

  1. Parametric Optimization of Biomass Steam-and-Gas Plant

    Directory of Open Access Journals (Sweden)

    V. Sednin

    2013-01-01

    Full Text Available The paper contains a parametric analysis of the simplest scheme of a steam-and gas plant for the conditions required for biomass burning. It has been shown that application of gas-turbine and steam-and-gas plants can significantly exceed an efficiency of steam-power supply units which are used at the present moment. Optimum thermo-dynamical conditions for application of steam-and gas plants with the purpose to burn biomass require new technological solutions in the field of heat-exchange equipment designs.

  2. Status of steam generator tubing integrity at Jaslovske Bohunice NPP

    International Nuclear Information System (INIS)

    Cepcek, S.

    1997-01-01

    Steam generator represents one of the most important component of nuclear power plants. Especially, loss of tubing integrity of steam generators can lead to the primary coolant leak to secondary circuit and in worse cases to the unit shut down or to the PTS events occurrence. Therefore, to ensure the steam generator tubing integrity and the current knowledge about tube degradation propagation and development is of the highest importance. In this paper the present status of steam generator tubing integrity in operated NPP in Slovak Republic is presented

  3. Safety Evaluation Report related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445 and 50-446). Supplement No. 7

    International Nuclear Information System (INIS)

    1985-01-01

    Supplement 7 to the Safety Evaluation Report for the Texas Utilities Electric Company application for a license to operate Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445, 50-446), located in Somervell County, Texas, has been jointly prepared by the Office of Nuclear Reactor Regulation and the Comanche Peak Technical Review of the US Nuclera Regulatory Commission. This supplement provides the results of the staff's evaluation and resolution of approximately 80 technical concerns and allegations in the areas of Electric/Instrumentation and Test Programs regarding construction and plant readiness testing practices at the Comanche Peak facility. Issues raised during Atomic Safety and Licensing Board hearings will be dealt with in future supplements to the Safety Evaluation Report

  4. Safety Evaluation Report related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445 and 50-446). Supplement No. 8

    International Nuclear Information System (INIS)

    1985-02-01

    Supplement 8 to the Safety Evaluation Report for the Texas Utilities Electric Company application for a license to operate Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445, 50-446), located in Somervell County, Texas, has been jointly prepared by the Office of Nuclear Reactor Regulation and the Comanche Peak Technical Review Team of the US Nuclear Regulatory Commission. This Supplement provides the results of the staff's evaluation and resolution of approximately 80 technical concerns and allegations relating to civil and structural and miscellaneous issues regarding construction and plant readiness testing practices at the Comanche Peak facility. Issues raised during recent Atomic Safety and Licensing Board hearings will be dealt with in future supplements to the Safety Evaluation Report

  5. Safety evaluation report related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445 and 50-446): Supplement No. 21

    International Nuclear Information System (INIS)

    1989-04-01

    Supplement 21 to the Safety Evaluation Report related to the operation of the Comanche Peak Steam Electric Station (CPSES), Units 1 and 2 (NUREG-0797), has been prepared by the Office of Nuclear Reactor Regulation of the US Nuclear Regulatory Commission (NRC). The facility is located in Somervell County, Texas, approximately 40 miles southwest of Fort Worth, Texas. This supplement reports the status of certain issues that had not been resolved when the Safety Evaluation Report and Supplements 1, 2, 3, 4, 6, and 12 to that report were published. This supplement also lists the new issues that have been identified since Supplement 12 was issued and includes the evaluations for licensing items resolved in this interim period. 21 refs

  6. A reflux capsule steam generator for sodium cooled reactors

    International Nuclear Information System (INIS)

    Lantz, E.

    Pressurized water reactor plants at numerous sites have sustained significant leakage through their steam generators. The consequent shutdowns for repairs and replacements have damaged their economics. This experience suggests that if steam generators for liquid metal fast breeder reactors (LMFBR's) continue to be built as presently designed some of them will have similar problems. Because of their larger capital investment, the consequent damage to the economics of LMFBR's could be more serious. Reflux capsules provide a way to separate sodium from water and to reduce thermal stresses in steam generators for sodium cooled reactors. Their use would also eliminate the need for a primary heat exchanger and a secondary sodium loop pump. (author)

  7. Chemical cleaning of nuclear (PWR) steam generators

    International Nuclear Information System (INIS)

    Welty, C.S. Jr.; Mundis, J.A.

    1982-01-01

    This paper reports on a significant research program sponsored by a group of utilities (the Steam Generator Owners Group), which was undertaken to develop a process to chemically remove corrosion product deposits from the secondary side of pressurized water reactor (PWR) power plant steam generators. Results of this work have defined a process (solvent system and application methods) that is capable of removing sludge and tube-to-tube support plate crevice corrosion products generated during operation with all-volatile treatment (AVT) water chemistry. Considers a plant-specific test program that includes all materials in the steam generator to be cleaned and accounts for the physical locations (proximity and contact) of those materials. Points out that prior to applying the process in an operational unit, the utility, with the participation of the NSSR vendor, must define allowable total corrosion to the materials of construction of the unit

  8. Optimal Operations and Resilient Investments in Steam Networks

    Energy Technology Data Exchange (ETDEWEB)

    Bungener, Stéphane L., E-mail: stephane.bungener@a3.epfl.ch [Industrial Process and Energy Systems Engineering, École Polytechnique Fédérale de Lausanne, Lausanne (Switzerland); Van Eetvelde, Greet [Environmental and Spatial Management, Faculty of Engineering and Architecture, Ghent University, Ghent (Belgium); Maréchal, François [Industrial Process and Energy Systems Engineering, École Polytechnique Fédérale de Lausanne, Lausanne (Switzerland)

    2016-01-20

    Steam is a key energy vector for industrial sites, most commonly used for process heating and cooling, cogeneration of heat and mechanical power as a motive fluid or for stripping. Steam networks are used to carry steam from producers to consumers and between pressure levels through letdowns and steam turbines. The steam producers (boilers, heat and power cogeneration units, heat exchangers, chemical reactors) should be sized to supply the consumers at nominal operating conditions as well as peak demand. First, this paper proposes an Mixed Integer Linear Programing formulation to optimize the operations of steam networks in normal operating conditions and exceptional demand (when operating reserves fall to zero), through the introduction of load shedding. Optimization of investments based on operational and investment costs are included in the formulation. Though rare, boiler failures can have a heavy impact on steam network operations and costs, leading to undercapacity and unit shutdowns. A method is therefore proposed to simulate steam network operations when facing boiler failures. Key performance indicators are introduced to quantify the network’s resilience. The proposed methods are applied and demonstrated in an industrial case study using industrial data. The results indicate the importance of oversizing key steam producing equipments and the value of industrial symbiosis to increase industrial site resilience.

  9. Optimal Operations and Resilient Investments in Steam Networks

    International Nuclear Information System (INIS)

    Bungener, Stéphane L.; Van Eetvelde, Greet; Maréchal, François

    2016-01-01

    Steam is a key energy vector for industrial sites, most commonly used for process heating and cooling, cogeneration of heat and mechanical power as a motive fluid or for stripping. Steam networks are used to carry steam from producers to consumers and between pressure levels through letdowns and steam turbines. The steam producers (boilers, heat and power cogeneration units, heat exchangers, chemical reactors) should be sized to supply the consumers at nominal operating conditions as well as peak demand. First, this paper proposes an Mixed Integer Linear Programing formulation to optimize the operations of steam networks in normal operating conditions and exceptional demand (when operating reserves fall to zero), through the introduction of load shedding. Optimization of investments based on operational and investment costs are included in the formulation. Though rare, boiler failures can have a heavy impact on steam network operations and costs, leading to undercapacity and unit shutdowns. A method is therefore proposed to simulate steam network operations when facing boiler failures. Key performance indicators are introduced to quantify the network’s resilience. The proposed methods are applied and demonstrated in an industrial case study using industrial data. The results indicate the importance of oversizing key steam producing equipments and the value of industrial symbiosis to increase industrial site resilience.

  10. Corrosion by galvanic coupling on the steam generator auxiliary feedwater pumps at the level of the steam-tight boxes

    International Nuclear Information System (INIS)

    Dordonat, M.; Huet, M.

    1994-01-01

    Corrosion by galvanic coupling in steam generator auxiliary pump is coming from electroplated chromium cracks for the rotor steel, and from chemical KANIGEN nickel cracks for the steam-tight boxes black steel. To avoid galvanic coupling between Cr coating and the rotor steel, first an electrolytic Ni coating is done followed by an electrolytic Cr coating. To avoid galvanic coupling between black steel and graphite rings, black steel is replaced by 316L steel. (A.B.). 1 ref., 7 figs

  11. Research perspectives on the evaluation of steam generator tube integrity

    International Nuclear Information System (INIS)

    Muscara, J.; Diercks, D.R.; Majumdar, S.; Kupperman, D.S.; Bakhtiari, S.; Shack, W.J.

    2002-01-01

    Industry efforts have been largely successful in managing degradation of steam generator tubes due to wastage, pitting, and denting, but fretting, stress corrosions cracking (SCC) and intergranular attack have proved more difficult to manage. Although steam generator replacements are proceeding, there is substantial industry interest in operating with degraded steam generators, and significant numbers of plants will continue to do so. In most cases degradation of steam generator tubing by stress corrosion cracking is still managed by 'plug or repair on detection' because current NDE techniques for characterization of flaws and the knowledge of SCC crack growth rates are not accurate enough to permit continued operation. Replacement generators with improved designs and materials have performed well to date, but previous experience with the appearance of some types of SCC in Alloy 600 after 10 years or more of operation and laboratory results suggest additional understanding of corrosion performance of these materials is needed. This paper reviews some of the historical background that underlies current steam generator degradation management strategies and outlines some of the additional research that must be done to provide more effective management of degradation in current generators and provide greater assurance of satisfactory performance in replacement steam generators. (author)

  12. Steam feeding redundancy for turbine-drives of feed pumps at WWER-1000 NPP

    International Nuclear Information System (INIS)

    Nesterov, Yu.V.; Shmukler, B.I.

    1987-01-01

    The system of steam supply for feed pump driving turbines (T) at the South Ukrainian Unit 1 according to the centralized redundancy principle is described. T is feeded through the collector of water auxiliary sytem (CWAS) to which steam from the third steam extraction line of turbine is supplied under thenormal regime. Under the reduction of turbine load, live steam from the steam generator is supplied to CWAS through the pressure regulator, possesing 10 s speed of responce. In this case the level reduction in the steam generator makes up 170 mm

  13. Steam generator tube failures

    International Nuclear Information System (INIS)

    MacDonald, P.E.; Shah, V.N.; Ward, L.W.; Ellison, P.G.

    1996-04-01

    A review and summary of the available information on steam generator tubing failures and the impact of these failures on plant safety is presented. The following topics are covered: pressurized water reactor (PWR), Canadian deuterium uranium (CANDU) reactor, and Russian water moderated, water cooled energy reactor (VVER) steam generator degradation, PWR steam generator tube ruptures, the thermal-hydraulic response of a PWR plant with a faulted steam generator, the risk significance of steam generator tube rupture accidents, tubing inspection requirements and fitness-for-service criteria in various countries, and defect detection reliability and sizing accuracy. A significant number of steam generator tubes are defective and are removed from service or repaired each year. This wide spread damage has been caused by many diverse degradation mechanisms, some of which are difficult to detect and predict. In addition, spontaneous tube ruptures have occurred at the rate of about one every 2 years over the last 20 years, and incipient tube ruptures (tube failures usually identified with leak detection monitors just before rupture) have been occurring at the rate of about one per year. These ruptures have caused complex plant transients which have not always been easy for the reactor operators to control. Our analysis shows that if more than 15 tubes rupture during a main steam line break, the system response could lead to core melting. Although spontaneous and induced steam generator tube ruptures are small contributors to the total core damage frequency calculated in probabilistic risk assessments, they are risk significant because the radionuclides are likely to bypass the reactor containment building. The frequency of steam generator tube ruptures can be significantly reduced through appropriate and timely inspections and repairs or removal from service

  14. Replacing penalties

    Directory of Open Access Journals (Sweden)

    Vitaly Stepashin

    2017-01-01

    Full Text Available УДК 343.24The subject. The article deals with the problem of the use of "substitute" penalties.The purpose of the article is to identify criminal and legal criteria for: selecting the replacement punishment; proportionality replacement leave punishment to others (the formalization of replacement; actually increasing the punishment (worsening of legal situation of the convicted.Methodology.The author uses the method of analysis and synthesis, formal legal method.Results. Replacing the punishment more severe as a result of malicious evasion from serving accused designated penalty requires the optimization of the following areas: 1 the selection of a substitute punishment; 2 replacement of proportionality is serving a sentence other (formalization of replacement; 3 ensuring the actual toughening penalties (deterioration of the legal status of the convict. It is important that the first two requirements pro-vide savings of repression in the implementation of the replacement of one form of punishment to others.Replacement of punishment on their own do not have any specifics. However, it is necessary to compare them with the contents of the punishment, which the convict from serving maliciously evaded. First, substitute the punishment should assume a more significant range of restrictions and deprivation of certain rights of the convict. Second, the perfor-mance characteristics of order substitute the punishment should assume guarantee imple-mentation of the new measures.With regard to replacing all forms of punishment are set significant limitations in the application that, in some cases, eliminates the possibility of replacement of the sentence, from serving where there has been willful evasion, a stricter measure of state coercion. It is important in the context of the topic and the possibility of a sentence of imprisonment as a substitute punishment in cases where the original purpose of the strict measures excluded. It is noteworthy that the

  15. Steam generator thermal sleeve reconstruction

    Energy Technology Data Exchange (ETDEWEB)

    Caton, E.; Askari, A.; Volder, P. [Babcock and Wilcox Canada Ltd., Cambridge, Ontario (Canada)]. E-mail: eecaton@babcock.com

    2003-07-01

    'Full text:' Successful implementation of a physically difficult repair program requires collaboration of the design and construction functions of an organization to ensure that goals are shared and rework or on-the-fly design changes are not required. Furthermore, in a nuclear facility this collaboration results in the optimal safety condition as dose uptake is minimized with a well planned job. The replacement of the degraded thermal sleeves in the Pickering A Steam Generator feedwater nozzles posed this type of problem. The project may be summarized as follows: i) problem analysis, ii) identification of design parameters and limitations, iii) integration of field engineering and design engineering solutions, iv) installation. Integration of the design engineering and field engineering design parameters ensured that the most effective solution was implemented. (author)

  16. Materials choices for the advanced LWR steam generators

    International Nuclear Information System (INIS)

    Paine, J.P.N.; Shoemaker, C.E.; McIlree, A.R.

    1987-01-01

    Current light water reactor (LWR) steam generators have been affected by a variety of corrosion and mechanical damage degradation mechanisms. Included are wear caused by tube vibration, intergranular corrosion, pitting, and thinning or wastage of the steam generator tubing and accelerated corrosion of carbon steel supports (denting). The Electric Power Research Institute (EPRI) and the Steam Generator Owners Groups (I, II) have sponsored laboratory and field studies to provide ameliorative actions for the majority of the damage forms experienced to date. Some of the current corrosion mechanisms are aggravated or caused by unique materials choices or materials interactions. New materials have been proposed and at least partially qualified for use in replacement model steam generators, including an advanced LWR design. In so far as possible, the materials choices for the advanced LWR steam generator avoid the corrosion pitfalls seemingly inherent in the current designs. The EPRI Steam Generator Project staff has recommended materials and design choices for a new steam generator. Based on these recommendations we believe that the advanced LWR steam generators will be much less affected by corrosion and mechanical damage mechanisms than are now experienced

  17. Evaluation of Hybrid Power Plants using Biomass, Photovoltaics and Steam Electrolysis for Hydrogen and Power Generation

    Science.gov (United States)

    Petrakopoulou, F.; Sanz, J.

    2014-12-01

    Steam electrolysis is a promising process of large-scale centralized hydrogen production, while it is also considered an excellent option for the efficient use of renewable solar and geothermal energy resources. This work studies the operation of an intermediate temperature steam electrolyzer (ITSE) and its incorporation into hybrid power plants that include biomass combustion and photovoltaic panels (PV). The plants generate both electricity and hydrogen. The reference -biomass- power plant and four variations of a hybrid biomass-PV incorporating the reference biomass plant and the ITSE are simulated and evaluated using exergetic analysis. The variations of the hybrid power plants are associated with (1) the air recirculation from the electrolyzer to the biomass power plant, (2) the elimination of the sweep gas of the electrolyzer, (3) the replacement of two electric heaters with gas/gas heat exchangers, and (4) the replacement two heat exchangers of the reference electrolyzer unit with one heat exchanger that uses steam from the biomass power plant. In all cases, 60% of the electricity required in the electrolyzer is covered by the biomass plant and 40% by the photovoltaic panels. When comparing the hybrid plants with the reference biomass power plant that has identical operation and structure as that incorporated in the hybrid plants, we observe an efficiency decrease that varies depending on the scenario. The efficiency decrease stems mainly from the low effectiveness of the photovoltaic panels (14.4%). When comparing the hybrid scenarios, we see that the elimination of the sweep gas decreases the power consumption due to the elimination of the compressor used to cover the pressure losses of the filter, the heat exchangers and the electrolyzer. Nevertheless, if the sweep gas is used to preheat the air entering the boiler of the biomass power plant, the efficiency of the plant increases. When replacing the electric heaters with gas-gas heat exchangers, the

  18. Condensers for measuring steam quality at the inlet of back-pressure units of the Los Azufres, Mich., geothermal field; Condensadores para medir la calidad del vapor a la entrada de las turbinas a contrapresion del campo geotermico de Los Azufres, Mich.

    Energy Technology Data Exchange (ETDEWEB)

    Sandoval Medina, Fernando; Gonzalez Gonzalez, Rubi; Reyes Delgado, Lisette; Medina Martinez, Moises [Comision Federal de Electricidad, Gerencia de Proyectos Geotermoelectricos, Residencia de Los Azufres (Mexico)]. E-mail: fernando.sandoval@cfe.gob.mx

    2007-01-15

    Electrical conductivity is an indirect measurement of the quality of the steam supplied to power units. In the Los Azufres, Mich., geothermal field, the electrical conductivity once was measured in a discrete and periodic way by condensing steam samples through a water-cooled condenser. In an attempt to continuously measure conductivity, conductivity meters were installed where the units discharged, but the values proved unstable and unrepresentative. Thereafter, taking into account that steam quality should be measured at the steam delivery-reception point, equipment was designed and tested for continuously condensing steam. Finally it was possible to get an air-cooled condenser able to condense 500 milliliters per minute, enough to collect a representative flow of the steam and to measure its electrical conductivity. The equipment was installed in all seven back-pressure units operating in the field and to date has been operating in an optimal manner. [Spanish] La conductividad electrica es una medida indirecta de la calidad del vapor que se suministra a las unidades turbogeneradoras. En el campo geotermico de Los Azufres, Mich., la conductividad electrica se media en forma puntual y periodica, condensando muestras de vapor por medio de un serpentin enfriado con agua. Despues, ante la necesidad de medirla en forma continua, se instalaron conductivimetros en las descargas de las unidades, pero los valores resultaron muy inestables y poco representativos. Considerando, ademas, que la calidad del vapor debe medirse en el punto de entrega-recepcion, se disenaron y probaron equipos para condensar vapor de manera continua, lograndose construir un condensador enfriado por aire que logra condensar un flujo de 500 mililitros por minuto, cantidad suficiente para tener un flujo representativo del vapor que alimenta a las turbinas y medirle su conductividad electrica. Se instalaron estos equipos en las siete unidades turbogeneradoras a contrapresion que funcionan en el campo

  19. Steam regulation for 5 MW back-pressure units when a failure occurs in the Los Humeros, Pue., field, Mexico; Regulacion del vapor en caso de falla a unidades a contrapresion de 5 MW en el campo de Los Humeros, Pue., Mexico

    Energy Technology Data Exchange (ETDEWEB)

    Rosales Lopez, Cesar [Comision Federal de Electricidad, Puebla (Mexico)]. E-mail: cesar.rosales@cfe.gob.mx

    2006-07-15

    Four out of the seven back-pressure power units of 5 MW operating in the Los Humeros geothermal field, State of Puebla, Mexico, are fed by one steam pipe gathering the steam produced by nine wells. When a failure occurred in any of the units and the excedence valve had to be open to deviate the steam, a decrease in the steam flow for the remaining units was noted, along with lower electrical generation. The cause for that is analyzed and explained in this paper by comparing the interconnected steam supply system to an electric circuit. A way to maintain a uniform and continuous supply of steam in the Los Humeros field has been found. It was implemented several months ago and the problem has not reoccurred. [Spanish] Cuatro de las siete unidades de 5 MW a contrapresion que operan en el campo geotermico de Los Humeros, Puebla, son alimentadas por un solo vaporducto que reune el vapor de nueve pozos productores. Cuando ocurria una falla en alguna de estas unidades y se abria por completo la valvula de excedencia para desviar el vapor, se observaba una reduccion en el flujo de vapor que llegaba a las otras tres unidades, lo que a su vez ocasionaba que la generacion de electricidad se redujera notoriamente. En este trabajo se analiza y explica la causa de ello, mediante la comparacion de este sistema interconectado de suministro de vapor con un circuito electrico, y se explica la solucion que se encontro e implemento en el campo de Los Humeros para regular el suministro continuo y uniforme de vapor, con resultados satisfactorios a varios meses de su implementacion en las cuatro unidades interconectadas.

  20. Some problems raised by the operation of large nuclear turbo-generator sets. Automatic control system for steam turbo-generator units

    International Nuclear Information System (INIS)

    Cecconi, F.

    1976-01-01

    The design of an appropriate automatic system was found to be useful to improve the control of large size turbo-generator units so as to provide easy and efficient control and monitoring. The experience of the manufacturer of these turbo-generator units allowed a system well suited for this function to be designed [fr

  1. French steam generator

    International Nuclear Information System (INIS)

    Remond, A.

    1986-01-01

    After recalling the potential damage mode of tubes of steam generator, the author recalls the safety criteria used in France. The improvements and the process of damage prejudice and reparation for tubular bundle are presented [fr

  2. Steam purity in PWRs

    International Nuclear Information System (INIS)

    Hopkinson, J.

    1982-01-01

    Impurities enter the secondary loop of the PWR through both makeup water from lake or well and cooling-water leaks in the condenser. These impurities can be carried to the steam generator, where they cause corrosion deposits to form. Corrosion products in steam are swept further through the system and become concentrated at the point in the low-pressure turbine where steam begins to condense. Several plants have effectively reduced impurities, and therefore corrosion, by installing a demineralizer for the makeup water, a resin-bed system to clean condensed steam from the condenser, and a deaerator to remove oxygen from the water and so lower the risk of system metal oxidation. 5 references, 1 figure

  3. Liquid metal steam generator

    International Nuclear Information System (INIS)

    Wolowodiuk, W.

    1975-01-01

    A liquid metal heated steam generator is described which in the event of a tube failure quickly exhausts out of the steam generator the products of the reaction between the water and the liquid metal. The steam is generated in a plurality of bayonet tubes which are heated by liquid metal flowing over them between an inner cylinder and an outer cylinder. The inner cylinder extends above the level of liquid metal but below the main tube sheet. A central pipe extends down into the inner cylinder with a centrifugal separator between it and the inner cylinder at its lower end and an involute deflector plate above the separator so that the products of a reaction between the liquid metal and the water will be deflected downwardly by the deflector plate and through the separator so that the liquid metal will flow outwardly and away from the central pipe through which the steam and gaseous reaction products are exhausted. (U.S.)

  4. Steam cleaning device

    International Nuclear Information System (INIS)

    Karaki, Mikio; Muraoka, Shoichi.

    1985-01-01

    Purpose: To clean complicated and long objects to be cleaned having a structure like that of nuclear reactor fuel assembly. Constitution: Steams are blown from the bottom of a fuel assembly and soon condensated initially at the bottom of a vertical water tank due to water filled therein. Then, since water in the tank is warmed nearly to the saturation temperature, purified water is supplied from a injection device below to the injection device above the water tank on every device. In this way, since purified water is sprayed successively from below to above and steams are condensated in each of the places, the entire fuel assembly elongated in the vertical direction can be cleaned completely. Water in the reservoir goes upward like the steam flow and is drained together with the eliminated contaminations through an overflow pipe. After the cleaning has been completed, a main steam valve is closed and the drain valve is opened to drain water. (Kawakami, Y.)

  5. Steam generator water lancing

    International Nuclear Information System (INIS)

    Kamler, F.; Schneider, W.

    1992-01-01

    The tubesheet and tube support plate deposits in CANDU steam generators are notable for their hardness. Also notable is the wide variety of steam generator access situations. Because of the sludge hardness and the difficulty of the access, traditional water lancing processes which directed jets from the central tube free lane or from the periphery of the bundle have proven unsuitable. This has led to the need for some very unique inter tube water lancing devices which could direct powerful water jets directly onto the deposits. This type of process was applied to the upper broached plates of the Bruce A steam generators, which had become severely blocked. It has since been applied to various other steam generator situations. This paper describes the flexlance equipment development, qualification, and performance in the various CANDU applications. 4 refs., 2 tabs., 7 figs

  6. Extending service life of steam generators by sleeving tubes

    International Nuclear Information System (INIS)

    Gutzwiller, J.E.

    1982-01-01

    Steam generator tubes that are failing due to IGA in the tubesheet crevice can be kept in service by using the basic sealable sleeve design developed by BandW. Variations of the present sleeve design could significantly reduce the number of tubes that must be plugged each year. Sleeving had the potential of keeping 28 percent more tubes in service during 1979. Lowering the overall rate at which tubes are removed from service by plugging will reduce the probability of having to derate the plant or replace the steam generator. Considering tomorrow's replacement power costs, sleeving to keep tubes in service is a practical and sound investment

  7. Steam-water separator

    International Nuclear Information System (INIS)

    Modrak, T.M.; Curtis, R.W.

    1978-01-01

    The steam-water separator connected downstream of a steam generator consists of a vertical centrifugal separator with swirl blades between two concentric pipes and a cyclone separator located above. The water separated in the cyclone separator is collected in the inner tube of the centrifugal separator which is closed at the bottom. This design allows the overall height of the separator to be reduced. (DG) [de

  8. Study of tritium permeation through Peach Bottom Steam Generator tubes

    International Nuclear Information System (INIS)

    Yang, L.; Baugh, W.A.; Baldwin, N.L.

    1977-06-01

    The report describes the equipment developed, samples tested, procedures used, and results obtained in the tritium permeation tests conducted on steam generator tubing samples which were removed from the Peach Bottom Unit No. 1 reactor

  9. Tachometric flowmeters for measuring circulation water parameters in steam generators of the NPPs running on pressurized water reactors

    International Nuclear Information System (INIS)

    Ageev, A.G.; Korolkov, B.M.; Nigmatulin, B.I.; Belov, V.I.; Vasileva, R.V.; Trubkin, N.I.

    1997-01-01

    Tachometric flowmeters used in steam generators for determining the velocity and direction of the flow have a limited service life owing to the use of corundum for the bearing assembly components. Various materials were investigated for the feasibility of using them as alternatives for replacing the corundum bearing and guide bushing under conditions close to the conditions in steam generators: 7 MPa, 260 degC. Good results were obtained with bearing assemblies fabricated from corrosion-resistant steel. Testing of the transducer design and optimization of the technique was accomplished in the course of testing steam generators of the WWER-1000 reactor at the Balakovskaya nuclear power plant. The velocity and direction of flow in the steam generator were measured within a wide range of unit power ratings up to the values corresponding to full power output. The service life of the transducers proved to be not less than 720 hours. The transducer parameters remained unchanged over the entire operation period. (M.D.)

  10. Three-Dimensional Modeling of a Steam-Line Break in a Boiling Water Reactor

    International Nuclear Information System (INIS)

    Tinoco, Hernan

    2002-01-01

    Because of weld problems, the core grids of Units 1 and 2 at the Forsmark nuclear power plant have been replaced by grids of a new design, consisting of a single machined piece without welds. The qualifying structural analysis has been carried out considering dynamic loads, which implies that even loss-of-coolant accidents have to be included. Therefore, a detailed time description of the loads acting on the different internal parts of the reactor is needed. To achieve sufficient space and time resolution, a computational fluid dynamics (CFD) analysis was considered to be a viable alternative.A CFD analysis of a steam-line break in the boiling water reactor of Unit 2 is the subject of this work. The study is based on the assumption that the timescale of the transient analysis is smaller than the relaxation time of the water-steam system. Therefore, a simulation of only the upper, steam part of the reactor with no two-phase effects (flashing) is feasible.The results obtained display a rather complex behavior of the decompression process, forcing the analysis of the pressure field to be accomplished through animation. In contrast, the computed instantaneous forces over different internal parts oscillate regularly and are approximately twice the forces estimated in the past by simpler methods, with frequencies of 30 to 40 Hz; top amplitudes of ∼1.64 MN; and relatively low damping, ∼25% after 0.5 s.According to the present results, this type of modeling is physically meaningful for simulation timescales smaller than the water-steam relaxation time, i.e., ∼0.5 s at reactor conditions. At larger times, a two-phase model is necessary to describe the decompression process since two-phase effects are dominant. The results have not yet been validated with experiments, but validation computations will be run in the future for comparison with results of the Marviken tests

  11. Evaluation of acoustic resonance at branch section in main steam line. Part 1. Effects of steam wetness on acoustic resonance

    International Nuclear Information System (INIS)

    Uchiyama, Yuta; Morita, Ryo

    2011-01-01

    The power uprating of the nuclear power plant (NPP) is conducted in United States, EU countries and so on, and also is planned in Japan. However, the degradation phenomena such as flow-induced vibration and wall thinning may increase or expose in the power uprate condition. In U.S. NPP, the dryer had been damaged by high cycle fatigue due to acoustic-induced vibration under a 17% extended power uprating (EPU) condition. This is caused by acoustic resonance at the stub pipes of safety relief valves (SRVs) in the main steam lines (MSL). Increased velocity by uprating excites the pressure fluctuations and makes large amplitude resonance. To evaluate the acoustic resonance at the stub pipes of SRVs in actual BWR, it is necessary to clarify the acoustic characteristics in steam flow. Although there are several previous studies about acoustic resonance, most of them are not steam flow but air flow. Therefore in this study, to investigate the acoustic characteristics in steam flow, we conducted steam flow experiments in each dry and wet steam conditions, and also nearly saturated condition. We measured pressure fluctuation at the top of the single stub pipe and in main steam piping. As a result, acoustic resonance in dry steam flow could be evaluated as same as that in air flow. It is clarified that resonance amplitude of fluctuating pressure at the top of the stub pipe in wet steam was reduced to one-tenth compared with that in dry. (author)

  12. Life extension of MAPS-2 by replacement of boiler hairpin type heat exchangers

    International Nuclear Information System (INIS)

    Tripathi, J.C.; Rastogi, S.K.; Rastogi, A.K.

    2006-01-01

    The steam generating equipment in MAPS-1 and 2 are Hairpin type comprises of eight boiler assemblies arranged in two banks of four boilers each. Each hairpin type heat exchangers consist of 195 Monel-400 tubes of 12.7 mm OD x 1.24 mm WT. One boiler assembly consists of eleven inverted U type heat exchangers (called hairpin type heat exchangers) mounted in parallel on inlet and outlet heavy water manifolds and connected to steam drum through individual short riser. Heavy water flows through these tubes where as feed water enters the shell at the bottom of one leg called pre-heat leg. After commissioning of MAPS-2 in 1985, five hairpins of MAPS-2 developed leak during the course of operation by the year 1999. Absence of physical access for health assessment of steam generator tube and lack of provision for tube sheet cleaning to remove the deposits on feed water side had caused pile and resulted in tube failures by under deposit pitting corrosion. All the 88 hairpins of MAPS-2 were replaced to extend the plant life when MAPS-2 was taken out of grid for En-masse Coolant Channel Replacement job (EMCCR) in the year 2001 - 03. The long shutdown of MAPS units for EMCCR was considered to be cost effective since unscheduled plant shut downs on account of tube leaks could be avoided. (author)

  13. Darlington steam generator life assurance program

    International Nuclear Information System (INIS)

    Jelinski, E.; Dymarski, M.; Maruska, C.; Cartar, E.

    1995-01-01

    The Darlington Nuclear Generating Station belonging to Ontario Hydro is one of the most modern and advanced nuclear generating stations in the world. Four reactor units each generate 881 net MW, enough to provide power to a major city, and representing approximately 20% of the Ontario grid. The nuclear generating capacity in Ontario represents approximately 60% of the grid. In order to look after this major asset, many proactive preventative and predictive maintenance programs are being put in place. The steam generators are a major component in any power plant. World wide experience shows that nuclear steam generators require specialized attention to ensure reliable operation over the station life. This paper describes the Darlington steam generator life assurance program in terms of degradation identification, monitoring and management. The requirements for chemistry control, surveillance of process parameters, surveillance of inspection parameters, and the integration of preventative and predictive maintenance programs such as water lancing, chemical cleaning, RIHT monitoring, and other diagnostics to enhance our understanding of life management issues are identified and discussed. We conclude that we have advanced proactive activities to avoid and to minimize many of the problems affecting other steam generators. An effective steam generator maintenance program must expand the knowledge horizon to understand life limiting processes and to analyze and synthesize observations with theory. (author)

  14. Spanish approach to research and development applied to steam generator tubes structural integrity and life management

    International Nuclear Information System (INIS)

    Lozano, J.; Bollini, G.J.

    1997-01-01

    The operating experience acquired from certain Spanish Nuclear Power Plant steam generators shows that the tubes, which constitute the second barrier to release of fission products, are susceptible to mechanical damage and corrosion as a result of a variety of mechanisms, among them wastage, pitting, intergranular attack (IGA), stress-corrosion cracking (SCC), fatigue-induced cracking, fretting, erosion/corrosion, support plate denting, etc. These problems, which are common in many plants throughout the world, have required numerous investments by the plants (water treatment plants, replacement of secondary side materials such as condensers and heaters, etc.), have meant costs (operation, inspection and maintenance) and have led to the unavailability of the affected units. In identifying and implementing all these preventive and corrective measures, the Spanish utilities have moved through three successive stages: in the initial stage, the main source of information and of proposals for solutions was the Plant Vendor, whose participation in this respect was based on his own Research and Development programs; subsequently, the Spanish utilities participated jointly in the EPRI Steam Generator Owners Group, collaborating in financing; finally, the Spanish utilities set up their own Steam Generator Research and Development program, while maintaining relations with EPRI programs and those of other countries through information interchange

  15. Fifth CNS international steam generator conference

    International Nuclear Information System (INIS)

    2006-01-01

    The Fifth CNS International Steam Generator Conference was held on November 26-29, 2006 in Toronto, Ontario, Canada. In contrast with other conferences which focus on specific aspects, this conference provided a wide ranging forum on nuclear steam generator technology from life-cycle management to inspection and maintenance, functional and structural performance characteristics to design architecture. The 5th conference has adopted the theme: 'Management of Real-Life Equipment Conditions and Solutions for the Future'. This theme is appropriate at a time of transition in the industry when plants are looking to optimize the performance of existing assets, prevent costly degradation and unavailability, while looking ahead for new steam generator investments in life-extension, replacements and new-build. More than 50 technical papers were presented in sessions that gave an insight to the scope: life management strategies; fouling, cleaning and chemistry; replacement strategies and new build design; materials degradation; condition assessment/fitness for service; inspection advancements and experience; and thermal hydraulic performance

  16. Electrosleeve process for in-situ nuclear steam generator repair

    International Nuclear Information System (INIS)

    Barton, R.A.; Moran, T.E.; Renaud, E.

    1997-01-01

    Degradation of steam generator (SG) tubing by localized corrosion is a widespread problem in the nuclear industry that can lead to costly forced out-ages, unit de-rating, SG replacement or even the permanent shutdown of a reactor. In response to the onset of SG tubing degradation at Ontario Hydro's Pickering Nuclear Generating Station (PNGS) Unit 5, and the determined unsuitability of conventional repair methods (mechanically expanded or welded sleeves) for Alloy 400, an alternative repair technology was developed. Electrosleeve is a non-intrusive, low-temperature process that involves the electrodeposition of a nanocrystalline nickel microalloy forming a continuously bonded, structural layer over the internal diameter of the degraded region. This technology is designed to provide a long-term pressure boundary repair, fully restoring the structural integrity of the damaged region to its original state. This paper describes the Electrosleeve process for SG tubing repair and the unique properties of the advanced sleeve material. The successful installation of Electrosleeves that have been in service for more than three years in Alloy 400 SG tubing at the Pickering-5 CANDU unit, the more recent extension of the technology to Alloy 600 and its demonstration in a U.S. pressurized water reactor (PWR), is presented. A number of PWR operators have requested plant operating technical specification changes to permit Electrosleeve SG tube repair. Licensing of the Electrosleeve by the U.S. Nuclear Regulatory Commission (NRC) is expected imminently. (author)

  17. Knee Replacement

    Science.gov (United States)

    ... days. Medications prescribed by your doctor should help control pain. During the hospital stay, you'll be encouraged to move your ... exercise your new knee. After you leave the hospital, you'll continue physical ... mobility and a better quality of life. And most knee replacements can be ...

  18. Power Plant Replacement Study

    Energy Technology Data Exchange (ETDEWEB)

    Reed, Gary

    2010-09-30

    This report represents the final report for the Eastern Illinois University power plant replacement study. It contains all related documentation from consideration of possible solutions to the final recommended option. Included are the economic justifications associated with the chosen solution along with application for environmental permitting for the selected project for construction. This final report will summarize the results of execution of an EPC (energy performance contract) investment grade audit (IGA) which lead to an energy services agreement (ESA). The project includes scope of work to design and install energy conservation measures which are guaranteed by the contractor to be self-funding over its twenty year contract duration. The cost recovery is derived from systems performance improvements leading to energy savings. The prime focus of this EPC effort is to provide a replacement solution for Eastern Illinois University's aging and failing circa 1925 central steam production plant. Twenty-three ECMs were considered viable whose net impact will provide sufficient savings to successfully support the overall project objectives.

  19. Power Plant Replacement Study

    Energy Technology Data Exchange (ETDEWEB)

    Reed, Gary

    2010-09-30

    This report represents the final report for the Eastern Illinois University power plant replacement study. It contains all related documentation from consideration of possible solutions to the final recommended option. Included are the economic justifications associated with the chosen solution along with application for environmental permitting for the selected project for construction. This final report will summarize the results of execution of an EPC (energy performance contract) investment grade audit (IGA) which lead to an energy services agreement (ESA). The project includes scope of work to design and install energy conservation measures which are guaranteed by the contractor to be self-funding over its twenty year contract duration. The cost recovery is derived from systems performance improvements leading to energy savings. The prime focus of this EPC effort is to provide a replacement solution for Eastern Illinois University’s aging and failing circa 1925 central steam production plant. Twenty-three ECMs were considered viable whose net impact will provide sufficient savings to successfully support the overall project objectives.

  20. Steam explosion studies review

    International Nuclear Information System (INIS)

    Hwang, Moon Kyu; Kim, Hee Dong

    1999-03-01

    When a cold liquid is brought into contact with a molten material with a temperature significantly higher than the liquid boiling point, an explosive interaction due to sudden fragmentation of the melt and rapid evaporation of the liquid may take place. This phenomenon is referred to as a steam explosion or vapor explosion. Depending upon the amount of the melt and the liquid involved, the mechanical energy released during a vapor explosion can be large enough to cause serious destruction. In hypothetical severe accidents which involve fuel melt down, subsequent interactions between the molten fuel and coolant may cause steam explosion. This process has been studied by many investigators in an effort to assess the likelihood of containment failure which leads to large scale release of radioactive materials to the environment. In an effort to understand the phenomenology of steam explosion, extensive studies has been performed so far. The report presents both experimental and analytical studies on steam explosion. As for the experimental studies, both small scale tests which involve usually less than 20 g of high temperature melt and medium/large scale tests which more than 1 kg of melt is used are reviewed. For the modelling part of steam explosions, mechanistic modelling as well as thermodynamic modelling is reviewed. (author)

  1. Babcock and Wilcox Canada steam generators past, present and future

    International Nuclear Information System (INIS)

    Smith, J.C.

    1998-01-01

    The steam generators in all of the domestic CANDU Plants, and most of the foreign CANDU plants, were supplied by Babcock and Wilcox Canada, either on their own or in co-operation with local manufacturers. More than 200 steam generators have been supplied. In addition, Babcock and Wilcox Canada has taken the technology which evolved out of the CANDU steam generators and has adapted the technology to supply of replacement steam generators for PWR's. There is enough history and operating experience, plus laboratory experience, to point to the future directions which will be taken in steam generator design. This paper documents the steam generators which have been supplied, the experience in operation and maintenance, what has worked and not worked, and how the design, materials, and operating and maintenance philosophy have evolved. The paper also looks at future requirements in the market, and the continuing research and product development going on at Babcock and Wilcox to address the future steam generator requirements. (author)

  2. Babcock and Wilcox Canada steam generators past, present and future

    Energy Technology Data Exchange (ETDEWEB)

    Smith, J.C. [Babcock and Wilcox Canada, Cambridge, Ontario (Canada)

    1998-07-01

    The steam generators in all of the domestic CANDU Plants, and most of the foreign CANDU plants, were supplied by Babcock and Wilcox Canada, either on their own or in co-operation with local manufacturers. More than 200 steam generators have been supplied. In addition, Babcock and Wilcox Canada has taken the technology which evolved out of the CANDU steam generators and has adapted the technology to supply of replacement steam generators for PWR's. There is enough history and operating experience, plus laboratory experience, to point to the future directions which will be taken in steam generator design. This paper documents the steam generators which have been supplied, the experience in operation and maintenance, what has worked and not worked, and how the design, materials, and operating and maintenance philosophy have evolved. The paper also looks at future requirements in the market, and the continuing research and product development going on at Babcock and Wilcox to address the future steam generator requirements. (author)

  3. How to replace a reactor pressure vessel

    International Nuclear Information System (INIS)

    Huber, R.

    1996-01-01

    A potential life extending procedure for a nuclear reactor after, say, 40 years of service life, might in some circumstances be the replacement of the reactor pressure vessel. Neutron induced degradation of the vessel might make replacement by one of a different material composition desirable, for example. Although the replacement of heavy components, such as steam generators, has been possible for many years, the pressure vessel presents a much more demanding task if only because it is highly irradiated. Some preliminary feasibility studies by Siemens are reported for the two removal strategies that might be considered. These are removal of the entire pressure vessel in one piece and dismantling it into sections. (UK)

  4. Mechanical design of a sodium heated steam generator

    International Nuclear Information System (INIS)

    Chetal, S.C.

    1975-01-01

    FBTR steam generator is a once through type unit consisting of four 12.5 MW thermal modules generating a total of 74 tons per hour of steam at 125 bar and 480 0 C. This paper outlines the mechanical design of such type of steam generator with emphasis on special design problems associated with this type of sodium to water steam heat exchanger, namely, thermal cycling of transition zone where nucleate boiling changes over to film boiling, application of pressure vessel design criteria for transient pressures, thermal stress evaluation resulting from differential expansion between shell and tube in this typical configuration, sodium headers support design, thermal sleeve, design, thermal shock analysis in thick tubes, thermal stress resulting from stratification and stability of expansion bends against vibration. Some of the possible design changes for the future large size steam generator are outlined. (author)

  5. Steam generators under construction for the SNR-300 power plant

    Energy Technology Data Exchange (ETDEWEB)

    Essebaggers, J

    1975-07-01

    The prototype straight tube and the helical coil-steam generator has been designed and fabricated of which the straight tube steam generator has been successfully tested for over 3000 hours at prototypical conditions and is presently being dismantled for detailed examination of critical designed features. The prototype helical coil steam generator is presently under testing in the 50 MWt test facility at TNO-Hengelo with approximately 500 hours of operation at full load conditions. In an earlier presentation the design and fabrication of the prototype steam generators have been presented, while for this presentation the production units for SNR-300 will be discussed. Some preliminary information will be presented at this meeting of the dismantling operations of the prototype straight tube steam generator. (author)

  6. Steam generators under construction for the SNR-300 power plant

    International Nuclear Information System (INIS)

    Essebaggers, J.

    1975-01-01

    The prototype straight tube and the helical coil-steam generator has been designed and fabricated of which the straight tube steam generator has been successfully tested for over 3000 hours at prototypical conditions and is presently being dismantled for detailed examination of critical designed features. The prototype helical coil steam generator is presently under testing in the 50 MWt test facility at TNO-Hengelo with approximately 500 hours of operation at full load conditions. In an earlier presentation the design and fabrication of the prototype steam generators have been presented, while for this presentation the production units for SNR-300 will be discussed. Some preliminary information will be presented at this meeting of the dismantling operations of the prototype straight tube steam generator. (author)

  7. Generic steam generator life cycle management from a utility perspective

    International Nuclear Information System (INIS)

    Baker, R.L.

    1993-01-01

    Steam generator repairs and replacements, which have occurred over the last 10 years, have lead many utilities to evaluate the economics of continued maintenance on existing steam generators against the economics of steam generator replacement. Such an endeavor requires an assessment of the expected rate and types of degradation. In addition, an identification of possible preventative or remedial measures and their potential effectiveness must be made. To arrive at an assessment of the economic impact of various combinations of potential courses of action many utilities have employed in-house developed or customized commercial programs to convert technical assessments into economic impact evaluations. This paper intends to give the reader an introduction to the technical issues and insight into a method of addressing the economic impact of possible management strategies. 52 refs., 17 figs., 2 tabs

  8. Decontamination of Steam Generator tube using Abrasive Blasting Technology

    International Nuclear Information System (INIS)

    Min, B. Y.; Kim, G. N.; Choi, W. K.; Lee, K. W.; Kim, D. H.; Kim, K. H.; Kim, B. T.

    2010-01-01

    As a part of a technology development of volume reduction and self disposal for large metal waste project, We at KAERI and our Sunkwang Atomic Energy Safety (KAES) subcontractor colleagues are demonstrating radioactively contaminated steam generator tube by abrasive blasting technology at Kori-1 NPP. A steam generator is a crucial component in a PWR (pressurized Water Reactor). It is the crossing between the primary, contaminated, circuit and the secondary waste-steam circuit. The heat from the primary reactor coolant loop is transferred to the secondary side in thousands of small tubes. Due to several problems in the material of those tube, like SCC (Stress Corrosion Cracking), insufficient control in water chemistry, which can be cause of tube leakage, more and more steam generators are replaced today. Only in Korea, already 2 of them are replaced and will be replaced in the near future. The retired 300 ton heavy Steam generator was stored at the storage waste building of Kori NPP site. The steam generator waste has a large volume, so that it is necessary to reduce its volume by decontamination. A waste reduction effect can be obtained through decontamination of the inner surface of a steam generator. Therefore, it is necessary to develop an optimum method for decontamination of the inner surface of bundle tubes. The dry abrasive blasting is a very interesting technology for the realization of three-dimensional microstructures in brittle materials like glass or silicon. Dry abrasive blasting is applicable to most surface materials except those that might be shattered by the abrasive. It is most effective on flat surface and because the abrasive is sprayed and can also applicable on 'hard to reach' areas such as inner tube ceilings or behind equipment. Abrasive decontamination techniques have been applied in several countries, including Belgium, the CIS, France, Germany, Japan, the UK and the USA

  9. Conduction Abnormalities and Permanent Pacemaker Implantation After Transcatheter Aortic Valve Replacement Using the Repositionable LOTUS Device: The United Kingdom Experience.

    Science.gov (United States)

    Rampat, Rajiv; Khawaja, M Zeeshan; Hilling-Smith, Roland; Byrne, Jonathan; MacCarthy, Philip; Blackman, Daniel J; Krishnamurthy, Arvindra; Gunarathne, Ashan; Kovac, Jan; Banning, Adrian; Kharbanda, Raj; Firoozi, Sami; Brecker, Stephen; Redwood, Simon; Bapat, Vinayak; Mullen, Michael; Aggarwal, Suneil; Manoharan, Ganesh; Spence, Mark S; Khogali, Saib; Dooley, Maureen; Cockburn, James; de Belder, Adam; Trivedi, Uday; Hildick-Smith, David

    2017-06-26

    The authors report the incidence of pacemaker implantation up to hospital discharge and the factors influencing pacing rate following implantation of the LOTUS bioprosthesis (Boston Scientific, Natick, Massachusetts) in the United Kingdom. Transcatheter aortic valve replacement (TAVR) is associated with a significant need for permanent pacemaker implantation. Pacing rates vary according to the device used. The REPRISE II (Repositionable Percutaneous Replacement of Stenotic Aortic Valve Through Implantation of Lotus Valve System) trial reported a pacing rate of 29% at 30 days after implantation of the LOTUS device. Data were collected retrospectively on 228 patients who had the LOTUS device implanted between March 2013 and February 2015 across 10 centers in the United Kingdom. Twenty-seven patients (12%) had pacemakers implanted pre-procedure and were excluded from the analysis. Patients were aged 81.2 ± 7.7 years; 50.7% were male. The mean pre-procedural QRS duration was 101.7 ± 20.4 ms. More than one-half of the cohort (n = 111, 55%) developed new left bundle branch block (LBBB) following the procedure. Permanent pacemakers were implanted in 64 patients (32%) with a median time to insertion of 3.0 ± 3.4 days. Chief indications for pacing were atrioventricular (AV) block (n = 46, 72%), or LBBB with 1st degree AV block (n = 11, 17%). Amongst those who received a pacemaker following TAVR the pre-procedural electrocardiogram findings included: No conduction disturbance (n = 41, 64%); 1st degree AV block (n = 10, 16%); right bundle branch block (n = 6, 9%) and LBBB (n = 5, 8%). LBBB (but not permanent pacemaker) occurred more frequently in patients who had balloon aortic valvuloplasty before TAVR (odds ratio [OR]: 1.25; p = 0.03). Pre-procedural conduction abnormality (composite of 1st degree AV block, hemiblock, right bundle branch block, LBBB) was independently associated with the need for permanent pacemaker (OR: 2.54; p = 0.048). The absence of

  10. Steam generator arrangement

    International Nuclear Information System (INIS)

    Ssinegurski, E.

    1981-01-01

    A steam flow path arrangement for covering the walls of the rear gas pass of a steam generator is disclosed. The entire flow passes down the sidewalls with a minor portion then passing up through the rear wall to a superheater inlet header at an intermediate elevation. The major portion of the flow passes up the front wall and through hanger tubes to a roof header. From there the major portion passes across the roof and down the rear wall to the superheater inlet header at the intermediate elevation

  11. Physical Function After Total Knee Replacement: An Observational Study Describing Outcomes in a Small Group of Women From China and the United States.

    Science.gov (United States)

    White, Daniel K; Li, Zhichang; Zhang, Yuqing; Marmon, Adam R; Master, Hiral; Zeni, Joseph; Niu, Jingbo; Jiang, Long; Zhang, Shu; Lin, Jianhao

    2018-01-01

    To describe physical function before and six months after Total Knee Replacement (TKR) in a small sample of women from China and the United States. Observational. Community environment. Both groups adhered to the Osteoarthritis Research Society International (OARSI) protocols for the 6-minute walk and 30-second chair stand. We compared physical function prior to TKR and 6 months after using linear regression adjusted for covariates. Women (N=60) after TKR. Not applicable. Age and body mass index in the China group (n=30; 66y and 27.0kg/m 2 ) were similar to those in the U.S. group (n=30; 65y and 29.6kg/m 2 ). Before surgery, the China group walked 263 (95% confidence interval [CI], -309 to -219) less meters and had 10.2 (95% CI, -11.8 to -8.5) fewer chair stands than the U.S. group. At 6 months when compared with the U.S. group, the China group walked 38 more meters, but this difference did not reach statistical significance (95% CI, -1.6 to 77.4), and had 3.1 (95% CI, -4.4 to -1.7) fewer chair stands. The China group had greater improvement in the 6-minute walk test than did the U.S. group (PChina group had greater gains in walking endurance and similar gains in repeated chair stands than did the U.S. group after surgery. Copyright © 2017 American Congress of Rehabilitation Medicine. Published by Elsevier Inc. All rights reserved.

  12. Steam generator sludge removal apparatus

    International Nuclear Information System (INIS)

    Schafer, B.W.; Werner, C.E.; Klahn, F.C.

    1992-01-01

    The present invention relates to equipment for cleaning steam generators and in particular to a high pressure fluid lance for cleaning sludge off the steam generator tubes away from an open tube lane. 6 figs

  13. Status of the CRBRP steam-generator design

    International Nuclear Information System (INIS)

    Schmidt, J.E.; Martinez, R.S.; Murdock, J.F.

    1981-06-01

    Fabrication of the Prototype Unit is near completion and will be delivered to the test site in August, 1981. The Plant Unit design is presently at an advanced stage and will result in steam generator units fully capable of meeting all the requiments of the CRBRP Power Plant

  14. Steam generators regulatory practices and issues in Spain

    International Nuclear Information System (INIS)

    Mendoza, C.; Castelao, C.; Ruiz-Colino, J.; Figueras, J.M.

    1997-01-01

    This paper presents the actual status of Spanish Steam Generator tubes, actions developed by PWR plant owners and submitted to CSN, and regulatory activities related to tube degradation mechanisms analysis; NDT tube inspection techniques; tube, tubesheet and TSPs integrity studies; tube plugging/repair criteria; preventive and corrective measures including whole SGs replacement; tube leak measurement methods and other operational aspects

  15. The temperature control and water quality regulation for steam generator secondary side hydrostatic test

    International Nuclear Information System (INIS)

    Xiao Bo; Liu Dongyong

    2014-01-01

    The secondary side hydrostatic test for the steam generator of M310 unit is to verify the pressure tightness of steam generator secondary side tube sheet and related systems. As for the importance of the steam generator, the water temperature and water quality of hydrostatic test has strict requirements. The discussion on the water temperature control and water quality regulation for the secondary loop hydrostatic test of Fuqing Unit 1 contribute greatly to the guiding work for the preparation of the steam generator pressure test for M310 unit. (authors)

  16. Reliability study: steam generation and distribution system, Portsmouth Gaseous Diffusion Plant

    International Nuclear Information System (INIS)

    Baker, F.E.; Davis, E.L.; Dent, J.T.; Walters, D.E.; West, R.M.

    1982-10-01

    A reliability study for determining the ability of the Steam Generation and Distribution System to provide reliable and adequate service through the year 2000 has been completed. This study includes an evaluation of the X-600 Steam Plant and the steam distribution system. The Steam Generation and Distribution System is in good overall condition, but to maintain this condition, the reliability study team made twelve recommendations. Eight of the recommendations are for repair or replacement of existing equipment and have a total estimated cost of $540,000. The other four recommendations are for additional testing, new procedure implementation, or continued investigations

  17. Safety Evaluation Report related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445 and 50-446). Supplement No. 11

    International Nuclear Information System (INIS)

    1985-05-01

    Supplement 11 to the Safety Evaluation Report for the Texas Utilities Electric Company application for a license to operate Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445, 50-446), located in Somervell County, Texas, has been jointly prepared by the Office of Nuclear Reactor Regulation and the Comanche Peak Technical Review Team (TRT) of the US Nuclear Regulatory Commission (NRC) and is in two parts. Part 1 (Appendix 0) of this supplement provides the results of the TRT's evaluation of approximately 124 concerns and allegations relating specifically to quality assurance and quality control (QA/QC) issues regarding construction proctices at the Comanche Peak facility. Part 2 (Appendix P) contains an overall summary and conclusion of the QA/QC aspects of the NRC Technical Review Team efforts as reported in supplemental Safety Evaluation Report SERs 7, 8, 9, and 10. Since QA/QC issues are also contained in each of the other supplements, the TRT considered that such a summary and conclusion from all supplements was necessary for a complete TRT description of QA/QC activities at Comanche Peak

  18. Control system pre-feedbacked for the super heated steam temperature in heat recovering units; Sistema de control pre-retroalimentado para la temperatura de vapor sobrecalentado en recuperadores de calor

    Energy Technology Data Exchange (ETDEWEB)

    Lopez Alvarez, Hilario; Madrigal Espinosa, Guadalupe [Instituto de Investigaciones Electricas, Cuernavaca (Mexico)

    1996-12-31

    The study that is presented corresponds to the analysis, design and development of a pre-feedbacked control system for the superheated steam temperature regulation in the heat recovery units of a combined cycle thermoelectric power plant. The designs of the feedback controller and the pre-feedback control system were implemented based in a linear model of the tempering zone. This linear model was obtained through the application of parametric identification techniques to the non-linear mathematical model of a combined cycle power plant. [Espanol] El estudio que se presenta corresponde al analisis, diseno y desarrollo de un sistema de control pre-retroalimentado para regular la temperatura de vapor sobrecalentado en los recuperadores de calor de una central termoelectrica de ciclo combinado. Los disenos del controlador retroalimentado y del sistema de control prealimentado se realizaron con base en un modelo lineal de la zona de atemperacion. Este modelo lineal se obtuvo aplicando tecnicas de identificacion parametrica al modelo matematico no-lineal de una central de ciclo combinado.

  19. Operational monitoring of temperature and state of stress of primary collectors, their stud bolts and cover and temperatures of steam generator's pressure vessel at the nuclear power unit WWER 440

    International Nuclear Information System (INIS)

    Matal, O.; Simo, T.; Holy, F.; Vejvoda, S.

    1992-01-01

    Both primary collectors of the WWER 440 steam generator (STGE) are vertically positioned inside the STGE pressure vessel and connected in their lower part to the primary piping and closed at their upper part by primary covers. The primary cover is pushed against the primary collector flange by 20 stud bolts. Two nickel packing rings are fitted between the primary cover and collector. A leakage in the collector-cover junction could cause flow of the radioactive water into the clean secondary water. If the junction is made in accordance with the Soviet standard design the computed stresses exceed the allowable value in the stud bolts by a factor of 1.5. Therefore an improved design of the primary collector - primary cover flange joint was designed and tested on one STGE at a WWER 440 nuclear power unit in Czechoslovakia. The paper describes the system of joint properties measurement, gives some substantial characteristics of the new stud bolts and primary cover design and comments on significant measured results of state of stress and temperatures in comparison with the operational regime of the STGE. (orig.)

  20. Safety Evaluation Report related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445 and 50-446). Supplement No. 13

    International Nuclear Information System (INIS)

    1986-05-01

    Supplement 13 to the Safety Evaluation Report related to the operation of Comanche Peak Steam Electric Station (CPSES), Units 1 and 2 (NUREG-0797), has been prepared by the Office of Nuclear Reactor Regulation of the US Nuclear Regulatory Commission (NRC). The facility is located in Somervell County, Texas, approximately 40 miles southwest of Fort Worth, Texas. This supplement presents the staff's evaluation of the Comanche Peak Response Team (CPRT) Program Plan which was formulated by the applicant to resolve various construction and design issues raised by the Atomic Safety and Licensing Board, allegers, intervenor Citizens Association for Sound Energy (CASE), NRC inspections of various types, and Cygna Energy Services while conducting its independent design assessment. The NRC staff concludes that the CPRT Program Plan provides an overall structure for addressing all existing issues and any future issues which may be identified from further evaluations, and if properly implemented will provide important evidence of the design and construction quality of CPSES, and will identify any needed corrective action. The report identifies items to be addressed by the NRC staff during the implementation phase

  1. Control system pre-feedbacked for the super heated steam temperature in heat recovering units; Sistema de control pre-retroalimentado para la temperatura de vapor sobrecalentado en recuperadores de calor

    Energy Technology Data Exchange (ETDEWEB)

    Lopez Alvarez, Hilario; Madrigal Espinosa, Guadalupe [Instituto de Investigaciones Electricas, Cuernavaca (Mexico)

    1997-12-31

    The study that is presented corresponds to the analysis, design and development of a pre-feedbacked control system for the superheated steam temperature regulation in the heat recovery units of a combined cycle thermoelectric power plant. The designs of the feedback controller and the pre-feedback control system were implemented based in a linear model of the tempering zone. This linear model was obtained through the application of parametric identification techniques to the non-linear mathematical model of a combined cycle power plant. [Espanol] El estudio que se presenta corresponde al analisis, diseno y desarrollo de un sistema de control pre-retroalimentado para regular la temperatura de vapor sobrecalentado en los recuperadores de calor de una central termoelectrica de ciclo combinado. Los disenos del controlador retroalimentado y del sistema de control prealimentado se realizaron con base en un modelo lineal de la zona de atemperacion. Este modelo lineal se obtuvo aplicando tecnicas de identificacion parametrica al modelo matematico no-lineal de una central de ciclo combinado.

  2. Nuclear reactor fuel replacement system

    International Nuclear Information System (INIS)

    Kayano, Hiroyuki; Joge, Toshio.

    1976-01-01

    Object: To permit the direction in which a fuel replacement unit is moving to be monitored by the operator. Structure: When a fuel replacement unit approaches an intermediate goal position preset in the path of movement, renewal of data display on a goal position indicator is made every time the goal position is changed. With this renewal, the prevailing direction of movement of the fuel replacement unit can be monitored by the operator. When the control of movement is initiated, the co-ordinates of the intermediate goal point A are displayed on a goal position indicator. When the replacement unit reaches point A, the co-ordinates of the next intermediate point B are displayed, and upon reaching point B the co-ordinates of the (last) goal point C are displayed. (Nakamura, S.)

  3. Steam reforming of ethanol

    DEFF Research Database (Denmark)

    Trane-Restrup, Rasmus; Dahl, Søren; Jensen, Anker Degn

    2013-01-01

    Steam reforming (SR) of oxygenated species like bio-oil or ethanol can be used to produce hydrogen or synthesis gas from renewable resources. However, deactivation due to carbon deposition is a major challenge for these processes. In this study, different strategies to minimize carbon deposition...

  4. Steam generators and furnaces

    Energy Technology Data Exchange (ETDEWEB)

    Swoboda, E

    1978-04-01

    The documents published in 1977 in the field of steam generators for conventional thermal power plants are classified according to the following subjects: power industry and number of power plants, planning and operation, design and construction, furnaces, environmental effects, dirt accumulation and corrosion, conservation and scouring, control and automation, fundamental research, and materials.

  5. Watt steam governor stability

    Science.gov (United States)

    Denny, Mark

    2002-05-01

    The physics of the fly-ball governor, introduced to regulate the speed of steam engines, is here analysed anew. The original analysis is generalized to arbitrary governor geometry. The well-known stability criterion for the linearized system breaks down for large excursions from equilibrium; we show approximately how this criterion changes.

  6. Steam purity in PWRs

    International Nuclear Information System (INIS)

    Hopkinson, J.; Passell, T.

    1982-01-01

    Reports that 2 EPRI studies of PWRs prove that impure steam triggers decay of turbine metals. Reveals that EPRI is attempting to improve steam monitoring and analysis, which are key steps on the way to deciding the most cost-effective degree of steam purity, and to upgrade demineralizing systems, which can then reliably maintain that degree of purity. Points out that 90% of all cracks in turbine disks have occurred at the dry-to-wet transition zone, dubbed the Wilson line. Explains that because even very clean water contains traces of chemical impurities with concentrations in the parts-per-billion range, Crystal River-3's secondary loop was designed with even more purification capability; a deaerator to remove oxygen and prevent oxidation of system metals, and full-flow resin beds to demineralize 100% of the secondary-loop water from the condenser. Concludes that focusing attention on steam and water chemistry can ward off cracking and sludge problems caused by corrosion

  7. Replacement rod

    International Nuclear Information System (INIS)

    Hatfield, S.C.

    1989-01-01

    This patent describes in an elongated replacement rod for use with fuel assemblies of the type having two end fittings connected by guide tubes with a plurality of rod and guide tube cell defining spacer grids containing rod support features and mixing vanes. The grids secured to the guide tubes in register between the end fittings at spaced intervals. The fuel rod comprising: an asymmetrically beveled tip; a shank portion having a straight centerline; and a permanently diverging portion between the tip and the shank portion

  8. Técnica de monitorado continuo (on – line para la evaluación del estado técnico de los turbogrupos de 64 y 100 MW. // Technique of continuous monitored (on - line for the evaluation of the technical state in steam turbine units of 64 and 100 MW.

    Directory of Open Access Journals (Sweden)

    F. de la Torre. Silva

    2001-04-01

    Full Text Available En este trabajo se presenta el resultado del estudio de factibilidad realizado a los turbogrupos de 64 y 100 MW de dosCentrales Termoeléctricas, sobre el empleo de técnicas de monitorado continuo “on line” para la evaluación del estadotécnico de estos turbogrupos.Palabras claves: Turbinas de vapor,vibraciones, monitorado continuo “on line”, diagnóstico.______________________________________________________________________Abstract:In this work an study of feasibility is presented. This study is carried out in steam turbine units of 64 and 100 MW, and show the use ofcontinuous monitored technique (on line for the evaluation of the technical state of these turbine units.Key Words: Steam turbines, vibrations, continuous monitoring on line, turbines supervision, Diagnosis,technical state evaluation.

  9. Results of the 5th regular inspection of Unit 1 in the Hamaoka Nuclear Power Station

    International Nuclear Information System (INIS)

    1983-01-01

    The 5th regular inspection of Unit 1 in the Hamaoka Nuclear Power Station was carried out from March 27 to July 27, 1982. Inspection was made on the reactor proper, reactor cooling system, instrumentation/control system, radiation control facility, etc. By the examinations of external appearance, leakage, performance, etc., no abnormality was observed. In the regular inspection, personnel exposure dose was all below the permissible level. The works done during the inspection were the following: the replacement of control rod drives, the replacement of core support-plate plugs, the repair of steam piping, steam extraction pipes and feed water heaters, the repair of a waste-liquid concentrator, the installation of barriers and leak detectors, the installation of drain sump monitors in a containment vessel, the replacement of concentrated liquid waste pumps, the employment of type B fuel. (Mori, K.)

  10. Estimating probable flaw distributions in PWR steam generator tubes

    International Nuclear Information System (INIS)

    Gorman, J.A.; Turner, A.P.L.

    1997-01-01

    This paper describes methods for estimating the number and size distributions of flaws of various types in PWR steam generator tubes. These estimates are needed when calculating the probable primary to secondary leakage through steam generator tubes under postulated accidents such as severe core accidents and steam line breaks. The paper describes methods for two types of predictions: (1) the numbers of tubes with detectable flaws of various types as a function of time, and (2) the distributions in size of these flaws. Results are provided for hypothetical severely affected, moderately affected and lightly affected units. Discussion is provided regarding uncertainties and assumptions in the data and analyses

  11. Secondary coolant circuit operation tests: steam generator feedwater supply

    International Nuclear Information System (INIS)

    Beroux, M.

    1985-01-01

    No one important accident occurred during the start-up tests of the 1300MWe P4 series, concerning the feedwater system of steam generators (SG). This communication comments on some incidents, that the tests allowed to detect very soon and which had no consequences on the operation of units: 1) Water hammer in feedwater tubes, and incidents met in the emergency steam generator water supply circuit. The technological differences between SG 900 and 1300 are pointed out, and the measures taken to prevent this problem are presented. 2) Incidents met on the emergency feedwater supply circuit of steam generators; mechanical or functional modifications involved by these incidents [fr

  12. Evaluation of material integrity on electricity generator water steam cycles component (Main Steam Pipe)

    International Nuclear Information System (INIS)

    Sudardjo; Histori; Triyadi, Ari

    1998-01-01

    The evaluation of material integrity on electricity generator component has been done. That component was main steam pipe of Unit II Suralaya Coal Fired Power Plant. evaluation was done by replication technique. The damage was found are two porosity's, from two point samples of six points sample population. Based on cavity evaluation in steels, which proposed by Neubauer and Wedel that porosity's still at class A damage. For class A damage, its means no remedial action would be required until next major scheduled maintenance outage. That porosity's was grouped on isolated cavities and not need ti repair that main steam pipe component less than three year after replication test

  13. Multi-layer casing of a steam turbine for high steam pressures and temperatures

    International Nuclear Information System (INIS)

    Remberg, A.

    1978-01-01

    In previous turbine casings there is no sealing provided between the inner layer and the outer layer, so that the steam pressure acts fully on the casing top and on the shaft seal housing situated there. To reduce the displacement which occurs there due to pressure differences in the various steam spaces, the normal inner casing is made with the shaft sealing housing in an inner layer, which cannot be divided in the axial direction. The inner layer can be inserted from the high pressure side into the unit outer casing. A horizontal section through the turbine in the attached drawing makes the construction and operation of the invention clear. (GL) [de

  14. LMFBR steam generator development: duplex bayonet tube steam generator. Volume II

    International Nuclear Information System (INIS)

    DeFur, D.D.

    1975-04-01

    This report represents the culmination of work performed in fulfillment of ERDA Contract AT(11-1)-2426, Task Agreement 2, in which alternate steam generator designs were developed and studied. The basic bayonet tube generator design previously developed by C-E under AEC Contract AT(11-1)-3031 was expanded by incorporating duplex heat transfer tubes to enhance the unit's overall safety and reliability. The effort consisted of providing and evaluating conceptual designs of the evaporator, superheater and reheater components for a large plant LMFBR steam generator (950 MWt per heat transport loop)

  15. Analysis of fast reactor steam generator performance

    International Nuclear Information System (INIS)

    Hulme, G.; Curzon, A.F.

    1992-01-01

    A computer model for the prediction of flow and temperature fields within a fast reactor steam generator unit is described. The model combines a commercially available computational fluid dynamics (CFD) solver (PHOENICS) with a steam-tube calculation and provides solutions for the fully coupled flow and temperature fields on both the shell side and the tube side. The model includes the inlet and outlet headers and the bottom end stagnant zone. It also accounts for the effects of support grids and edge-gaps. Two and three dimensional and transient calculations have been performed for both straight tube and J-tube units. Examples of the application of the model are presented. (7 figures) (Author)

  16. Urinary Neutrophil Gelatinase-Associated Lipocalin as a Predictor of Acute Kidney Injury, Severe Kidney Injury, and the Need for Renal Replacement Therapy in the Intensive Care Unit

    Directory of Open Access Journals (Sweden)

    Fatma I. Albeladi

    2017-07-01

    Full Text Available Background: Recent attempts were made to identify early indicators of acute kidney injury (AKI in order to accelerate treatment and hopefully improve outcomes. This study aims to assess the value of urinary neutrophil gelatinase-associated lipocalin (uNGAL as a predictor of AKI, severe AKI, and the need for renal replacement therapy (RRT. Methods: We conducted a prospective study and included adults admitted to our intensive care unit (ICU at King Abdulaziz University Hospital (KAUH, between May 2012 and June 2013, who had at least 1 major risk factor for AKI. They were followed up throughout their hospital stay to identify which potential characteristics predicted any of the above 3 outcomes. We collected information on patients’ age and gender, the Acute Physiology And Chronic Health Evaluation, version II (APACHE II score, the Sepsis-Related Organ Failure Assessment (SOFA score, serum creatinine and cystatin C levels, and uNGAL. We compared ICU patients who presented with any of the 3 outcomes with others who did not. Results: We included 75 patients, and among those 21 developed AKI, 18 severe AKI, and 17 required RRT. Bivariate analysis revealed intergroup differences for almost all clinical variables (e.g., patients with AKI vs. patients without AKI; while multivariate analysis identified mean arterial pressure as the only predictor for AKI (p < 0.001 and the SOFA score (p = 0.04 as the only predictor for severe AKI. For RRT, day 1 maximum uNGAL was the stronger predictor (p < 0.001 when compared to admission diagnosis (p = 0.014. Day 1 and day 2 maximum uNGAL levels were good and excellent predictors for future RRT, but only fair to good predictors for AKI and severe AKI. Conclusions: Maximum urine levels of uNGAL measured over the first and second 24 h of an ICU admission were highly accurate predictors of the future need for RRT, however less accurate at detecting early and severe AKI.

  17. Safety evaluation report related to the operation of Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445 and 50-446)

    International Nuclear Information System (INIS)

    1988-03-01

    Supplement 14 to the Safety Evaluation Report related to the operation of the Comanche Peak Stam Electric Station (CPSES), Units 1 and 2 (NUREG-0797), has been prepared by the Office of Special Projects of the US Nuclear Regulatory Commission (NRC). The facility is located in Somerville County, Texas, approximately 40 miles southwest of Fort Worth, Texas. This supplement presents the staff's evaluation of the applicants' Corrective Action Program (CAP0 related to large ans small bore piping and pipe supports. The scope and methodologies for CAP workshop as summarized in revision O to the large and small bore piping project status reports and as detailed in related documents referenced in this evaluation were developed to resolve various design issues raised by the Atomic Safety and Licensing Board (ASLB);the intervenor, Citizens Association for Sound Energy (CASE);the Camanche Peak Response Team (CPRT);SYGNA Energy Services (CYGNA);and the NRC staff. The NRC staff concludes that the CAP workscopes for large and small bore piping provide a comprehensive program for resolving the associated technical concerns identified by the ASLB, CASE, CPRT, CYGNA, and the NRC staff and their implementation ensures that the design of large and small bore piping and pipe supports at CPSES satisfies the applicable requirements of 10 CFR 50

  18. Lifetime analysis of the THTR steam generator and piping system

    International Nuclear Information System (INIS)

    Kemter, F.; Gloeckner, H.J.; Fritz, H.U.; Koenig, H.

    1989-01-01

    For the life monitoring during operation of the water / steam circuit operated in the high temperature area and the steam-raising units in the THTR, the life monitoring program SLAP was developed. For highly loaded components the current components exploitation and the remaining available life can be determined during operation. A survey is given of the procedure in determining the life exploitation and of the program structure of SLAP. (DG) [de

  19. Super titanium blades for advanced steam turbines

    International Nuclear Information System (INIS)

    Coulon, P.A.

    1990-01-01

    In 1986, the Alsthom Steam Turbines Department launched the manufacture of large titanium alloy blades: airfoil length of 1360 mm and overall length of 1520 mm. These blades are designed for the last-stage low pressure blading of advanced steam turbines operating at full speed (3000 rpm) and rating between 300 and 800 MW. Using titanium alloys for steam turbine exhaust stages as substitutes for chrome steels, due to their high strength/density ratio and their almost complete resistance to corrosion, makes it possible to increase the length of blades significantly and correspondingly that steam passage section (by up to 50%) with a still conservative stresses level in the rotor. Alsthom relies on 8 years of experience in the field of titanium, since as early as 1979 large titanium blades (airfoil length of 1240 mm, overall length of 1430 mm) were erected for experimental purposes on the last stage of a 900 MW unit of the Dampierre-sur-Loire power plant and now totals 45,000 operating hours without problems. The paper summarizes the main properties (chemical, mechanical and structural) recorded on very large blades and is based in particular on numerous fatigue corrosion test results to justify the use of the Ti 6 Al 4 V alloy in a specific context of micrographic structure

  20. Monitoring method for steam generator operation

    International Nuclear Information System (INIS)

    Tamaoki, Tetsuo

    1991-01-01

    In an LMFBR plant having an once-through steam generator, reduction of life of a heat transfer pipe caused by heat cycle fatigue is monitored by early finding for the occurrence of abnormality in the inside of the steam generator and by continuous monitoring for the position of departure from nucleate boiling (DNB), which are difficult with existent static characteristic analysis codes. That is, RMS values of fluctuations in temperature signals sent from thermocouples for measuring the fluid temperature in the vicinity of heat transfer pipe disposed along a primary channel of the once-through type steam generator. The abnormality in heat transfer performance is monitored by the distribution change of the RMS values. Subsequently, DNB point on the side of water and steam is determined by the distribution of the RMS value. Then, accumulated values of the product between the time in which the starting point stays in the DNB region and a life consumption amount per unit time given in accordance with the operation condition are monitored. Accordingly, thermal fatigue failure of the heat transfer pipe due to temperature fluctuation in the DNB region is monitored. (I.S.)

  1. Use of reinforced soil wall to support steam generator transfer

    International Nuclear Information System (INIS)

    Davie, J.R.; Wang, J.T.; Gladstone, R.A.

    1991-01-01

    Consumers Power Company had the two steam generators at its Palisades Nuclear Plant in Michigan replaced in November 1990. This replacement was accomplished through a 26-foot wide by 28-foot high opening cut into the wall of the containment building, about 45 feet above the original ground surface. Because this ground surface was at an approximately 3-H:1-V slope, leveling was required before replacement in order to provide access for the steam generators and adequate support for the heavy-duty gantry crane system used to transfer the generators. A 25-foot high reinforced soil wall was constructed to achieve the level surface. This paper describes the design and construction of the heavily loaded reinforced soil wall, including ground improvement measures required to obtain adequate wall stability. The performance of the wall under test loading will also be presented and discussed

  2. Soviet steam generator technology: fossil fuel and nuclear power plants

    International Nuclear Information System (INIS)

    Rosengaus, J.

    1987-01-01

    In the Soviet Union, particular operational requirements, coupled with a centralized planning system adopted in the 1920s, have led to a current technology which differs in significant ways from its counterparts elsewhere in the would and particularly in the United States. However, the monograph has a broader value in that it traces the development of steam generators in response to the industrial requirements of a major nation dealing with the global energy situation. Specifically, it shows how Soviet steam generator technology evolved as a result of changing industrial requirements, fuel availability, and national fuel utilization policy. The monograph begins with a brief technical introduction focusing on steam-turbine power plants, and includes a discussion of the Soviet Union's regional power supply (GRES) networks and heat and power plant (TETs) systems. TETs may be described as large central co-generating stations which, in addition to electricity, provide heat in the form of steam and hot water. Plants of this type are a common feature of the USSR today. The adoption of these cogeneration units as a matter of national policy has had a central influence on Soviet steam generator technology which can be traced throughout the monograph. The six chapters contain: a short history of steam generators in the USSR; steam generator design and manufacture in the USSR; boiler and furnace assemblies for fossil fuel-fired power stations; auxiliary components; steam generators in nuclear power plants; and the current status of the Soviet steam generator industry. Chapters have been abstracted separately. A glossary is included containing abbreviations and acronyms of USSR organizations. 26 references

  3. Upgraded Steam Generator Lancing System for Uljin NPP no.2

    International Nuclear Information System (INIS)

    Kim, Seok Tae; Jeong, Woo Tae; Hong, Sung Yull

    2005-01-01

    KEPRI(Korea Electric Power Research Institute) has developed various types of steam generator lancing systems since 1998. In this paper, we introduce a new lancing system with new improvements from the previous steam generator lancing system for Uljin NPP #2(nuclear power plant) constructed by KEPRI. The previous lancing system is registered as KALANS R -II and was developed for System-80 type steam generators. The previous lancing system was applied to Uljin unit #3 and it lowered radiation exposure of operators in comparison to manually operated lancing systems. And it effectively removed sludge accumulated around kidney bean zone in the Uljin unit #3 steam generators. But the previous lancing system could only clean partially the steam generators of Uljin unit #4. This was because the rail of the previous lancing system interfered with a part of the steam generator. Therefore we developed a new lancing system that can solve the interference problem. This new lancing system was upgraded from the previous lancing system. Also, a new lancing system for System-80 S/G will be introduced in this paper

  4. Method for repairing a steam turbine or generator rotor

    International Nuclear Information System (INIS)

    Clark, R.E.; Amos, D.R.

    1987-01-01

    A method is described for repairing low alloy steel steam turbine or generator rotors, the method comprising: a. machining mating attachments on a replacement end and a remaining portion of the original rotor; b. mating the replacement end and the original rotor; c. welding the replacement end to the original rotor by narrow-gap gas metal arc or submerged arc welding up to a depth of 1/2-2 inches from the rotor surface; d. gas tungsten arc welding the remaining 1/2-2 inches; e. boring out the mating attachment and at least the inside 1/4 inch of the welding; and f. inspecting the bore

  5. Importance of deposit information in the design and execution of steam generator chemical cleaning

    International Nuclear Information System (INIS)

    Flores, O.; Remark, J.

    1997-01-01

    During the planning stages of the chemical cleaning of the San Onofre Nuclear Generating Station (SONGS) units 2 and 3 steam generators, it was determined that an understanding of the steam generator deposit loading and composition was essential to the design and success of the project. It was also determined that qualification testing, preferably with actual deposits from the SONGS steam generators, was also essential. SONGS units 2 and 3 have Combustion Engineering (CE)-designed pressurized water reactors. Each unit has two CE model 3410 steam generators. Each steam generator has 9350 alloy 600 tubes with 1.9-cm (3/4 in.) outside diameter. Unit 2 began commercial operation in 1983, and unit 3, in 1984. The purpose of this technical paper is to explain the effort and methodology for deposit composition, characterization, and quantification. In addition, the deposit qualification testing and design of the cleaning are discussed

  6. Flow Instabilities and Main Steam Line Vibrations in a Pressurized Water Reactor

    International Nuclear Information System (INIS)

    Henriksson, Mats; Westin, Johan; Granhall, Tord; Andersson, Lars; Bjerke, Lars-Erik

    2002-01-01

    Severe vibrational problems occurred in the main steam system of a PWR nuclear power plant, about 18 months after a steam generator replacement had been carried out. The magnitude of the vibrations reached levels at which the operators had to reduce power in order to stay within the operating limits imposed by the nuclear inspectorate. To solve the problem the following analyses methods were employed: - Testing the influence on vibration level from different modes of plant operation; - Analyses of plant measurement data; - Calculations of: hydraulic behaviour of the system, structural dynamic behaviour of the system, flow at the steam generator outlet. Scale model testing of the steam generator outlet region. Hydraulic flow disturbances in the main steam system were measured using pressure and strain gauges, which made it possible to track individual pressure pulses propagating through the main steam system. Analyses showed that the pressure pulses causing the vibration originated from the vicinity of the steam generator outlet. By using computer codes for network fluid flow analyses the pressure pulses found in the measurement traces could be generated in calculations. Careful studies of the flow at the steam generator outlet region, using model testing in a 1:3 scale model as well as transient 3D CFD calculations, gave clear indications that flow separation occurred at the steam generator outlet nozzle and at the first bend. Finally, by substituting the outlet nozzle for a different design with a multi-port nozzle, the steam line vibration problem has been solved. (authors)

  7. Dynamic performances of wet turbine and steam-separator-superheater and their mathematical simulation as objects of temperature control

    International Nuclear Information System (INIS)

    Golovach, E.A.

    1985-01-01

    A mathematical model of a turbine and steam-separator-superheater (SSS) as applied to solution of the tasks of steam temperature regulaton after SSS has been developed. SSS as objects of steam temperature control are considerably less inertial, than intermediate superheaters (IS) of power units in thermal power plants, since for typical SSS and IS considered the duration of transition process according to steam temperature after SSS is 5-10 times loweA than for IS

  8. Steam generators in PWR's

    International Nuclear Information System (INIS)

    Michel, R.

    1974-01-01

    The steam generator of the PWR operates according to the principle of natural circulation. It consists of a U-shaped tube bundle whose free ends are welded to a bottom plate. The tube bundle is surrounded by a cylinder jacket which has slots closely above the bottom or tube plate. The feed water mixed with boiling water enters the tube bundle through these slots. Because of its buoyancy, the steam-water mixture flows upwards. Below the tube plate there are chambers for distributing and collecting pressurized water separated by means of a partition wall. By omitting some tubes, a free alloy is created so that the tubes in the center get sufficient water, too. By asymmetrical arrangement of the partition wall it is further possible to limit the tube alloy only to the inlet side for pressurized water. The flow over the tube plate is thus improved on the inlet side. (DG) [de

  9. Vertical steam generator

    International Nuclear Information System (INIS)

    Cuda, F.; Kondr, M.; Kresta, M.; Kusak, V.; Manek, O.; Turon, S.

    1982-01-01

    A vertical steam generator for nuclear power plants and dual purpose power plants consists of a cylindrical vessel in which are placed heating tubes in the form upside-down U. The heating tubes lead to the jacket of the cylindrical collector placed in the lower part of the steam generator perpendicularly to its vertical axis. The cylindrical collector is divided by a longitudinal partition into the inlet and outlet primary water sections of the heating tubes. One ends of the heating tube leads to the jacket of the collector for primary water feeding and the second ends of the heating tubes into the jacket of the collector which feeds and offtakes primary water from the heating tubes. (B.S.)

  10. Technical and economic feasibility for the application of micronized coal as a replacement for No. 2 oil for start-up and low-load operation at Illinois Power Havana No. 6 Cycling Unit

    International Nuclear Information System (INIS)

    Rosenberger, F.; Guilfoyle, C.J.; Parker, W.O. Jr.

    1991-01-01

    Uncertainty regarding oil availability and long-term price stability make it difficult for a utility to predict annual ignition costs for a cycling unit. Illinois Power Company, Sargent and Lundy Engineering and Micro-fuel Corporation have produced a detailed feasibility study on the application of micronized coal as a replacement fuel for start-up and low-load operation for Havana No. 6. This unit is a B and W opposed-fired boiler which is rated at 410 MWe (summer net). This paper presents technical and economic analysis, including the uncertainties of the application of this technology

  11. Steam generator life management

    International Nuclear Information System (INIS)

    King, P.; McGillivray, R.; Reinhardt, W.; Millman, J.; King, B.; Schneider, W.

    2003-01-01

    'Full-Text:' Steam Generator Life Management responsibility embodies doing whatever is necessary to maintain the steam generation equipment of a nuclear plant in effective, reliable service. All comes together in that most critical deliverable, namely the submission of the documentation which wins approval for return to service after an outage program. Life management must address all aspects of SG reliability over the life of the plant. Nevertheless, the life management activities leading up to return to service approval is where all of it converges. Steam Generator Life Management activities entail four types of work, all equally important in supporting the objective of successful operation. These activities are i) engineering functions; including identification of inspection and maintenance requirements, outage planning and scope definition plus engineering assessment, design and analysis as necessary to support equipment operation, ii) fitness of service work; including the expert evaluation of degradation mechanisms, disposition of defects for return to service or not, and the fitness for service analysis as required to justify ongoing operation with acceptable defects, iii) inspection work; including large scale eddy current inspection of tubing, the definition of defect size and character, code inspections of pressure vessel integrity and visual inspections for integrity and iv) maintenance work; including repairs, retrofits, cleaning and modifications, all as necessary to implement the measures defined during activities i) through iii). The paper discusses the approach and execution of the program for the achievement of the above objectives and particularly of items i) and ii). (author)

  12. What is geothermal steam worth?

    International Nuclear Information System (INIS)

    Thorhallsson, S.; Ragnarsson, A.

    1992-01-01

    Geothermal steam is obtained from high-temperature boreholes, either directly from the reservoir or by flashing. The value of geothermal steam is similar to that of steam produced in boilers and lies in its ability to do work in heat engines such as turbines and to supply heat for a wide range of uses. In isolated cases the steam can be used as a source of chemicals, for example the production of carbon dioxide. Once the saturated steam has been separated from the water, it can be transported without further treatment to the end user. There are several constraints on its use set by the temperature of the reservoir and the chemical composition of the reservoir fluid. These constraints are described (temperature of steam, scaling in water phase, gas content of steam, well output) as are the methods that have been adopted to utilize this source of energy successfully. Steam can only be transported over relatively short distances (a few km) and thus has to be used close to the source. Examples are given of the pressure drop and sizing of steam mains for pipelines. The path of the steam from the reservoir to the end user is traced and typical cost figures given for each part of the system. The production cost of geothermal steam is estimated and its sensitivity to site-specific conditions discussed. Optimum energy recovery and efficiency is important as is optimizing costs. The paper will treat the steam supply system as a whole, from the reservoir to the end user, and give examples of how the site-specific conditions and system design have an influence on what geothermal steam is worth from the technical and economic points of view

  13. Wet steam wetness measurement in a 10 MW steam turbine

    Directory of Open Access Journals (Sweden)

    Kolovratník Michal

    2014-03-01

    Full Text Available The aim of this paper is to introduce a new design of the extinction probes developed for wet steam wetness measurement in steam turbines. This new generation of small sized extinction probes was developed at CTU in Prague. A data processing technique is presented together with yielded examples of the wetness distribution along the last blade of a 10MW steam turbine. The experimental measurement was done in cooperation with Doosan Škoda Power s.r.o.

  14. Steam generator tube rupture effects on a LOCA

    International Nuclear Information System (INIS)

    LaChance, J.L.

    1979-01-01

    A problem currently experienced in commercial operating pressurized water reactors (PWR) in the United States is the degradation of steam generator tubes. Safety questions have arisen concerning the effect of these degraded tubes rupturing during a postulated loss-of-coolant accident (LOCA). To determine the effect of a small number of tube ruptures on the behavior of a large PWR during a postulated LOCA, a series of computer simulations was performed. The primary concern of the study was to determine whether a small number (10 or less of steam generator tubes rupturing at the beginning surface temperatures. Additional reflood analyses were performed to determine the system behavior when from 10 to 60 tubes rupture at the beginning of core reflood. The FLOOD4 code was selected as being the most applicable code for use in this study after an extensive analysis of the capabilities of existing codes to perform simulations of a LOCA with concurrent steam generator tube ruptures. The results of the study indicate that the rupturing of 10 or less steam generator tubes in any of the steam generators during a 200% cold leg break will not result in a significant increase in the peak cladding temperature. However, because of the vaporization of the steam generator secondary water in the primary side of the steam generator, a significant increase in the core pressure occurs which retards the reflooding process

  15. Shoulder replacement - discharge

    Science.gov (United States)

    Total shoulder arthroplasty - discharge; Endoprosthetic shoulder replacement - discharge; Partial shoulder replacement - discharge; Partial shoulder arthroplasty - discharge; Replacement - shoulder - discharge; Arthroplasty - shoulder - discharge

  16. Steam generators, turbines, and condensers. Volume six

    International Nuclear Information System (INIS)

    Anon.

    1986-01-01

    Volume six covers steam generators (How steam is generated, steam generation in a PWR, vertical U-tube steam generators, once-through steam generators, how much steam do steam generators make?), turbines (basic turbine principles, impulse turbines, reaction turbines, turbine stages, turbine arrangements, turbine steam flow, steam admission to turbines, turbine seals and supports, turbine oil system, generators), and condensers (need for condensers, basic condenser principles, condenser arrangements, heat transfer in condensers, air removal from condensers, circulating water system, heat loss to the circulating water system, factors affecting condenser performance, condenser auxiliaries)

  17. Chemical control and design considerations for CANDU-PHW steam generators

    International Nuclear Information System (INIS)

    Frost, C.R.; Churchill, B.R.

    1978-01-01

    Ontario Hydro presently operates eight nuclear power units with a total capacitiy of about 4000 MW(e) net. Operating experience has been with Monel-400 and with Inconel-600 tubed steam generators using sodium phosphate or all volatile control of the boiler steam and water system. With a heavy water Heat Transport System, steam generator tube integrity is an essential ingredient of economical power production. Only three steam generator tube failures have occurred so far in about 40 unit-years operation. None was attributable to corrosion. Factors in the good reliability are, careful engineering design, good quality control at all stages of tubing and steam generator manufacture and close chemical control. The continuing evolution of our steam generator design means that future requirements will be more stringent. (author)

  18. Clean energy for a new generation. Steam generator life cycle management and Bruce restart

    International Nuclear Information System (INIS)

    Newman, G.W.

    2009-01-01

    In the mid to late 1990s, Ontario Hydro decided to lay-up and write-down the Bruce A Nuclear Reactors. Upon transition to Bruce Power L.P., Canada's first and only private nuclear operator, new life and prospects were injected into the site, local economy and the provincial energy portfolio. The first step in this provincial power recovery initiative involved restart of Bruce Units 3 and 4 in the 2003/04 time-frame. Units 3 and 4 have performed beyond expectation during the last five-year operating interval. A combination of steam generator and fuel channel issues precluded a similar restart of Units 1 and 2. Enter the refurbishment of Bruce Units 1 and 2. This first-of-a-kind undertaking within the Canadian nuclear power industry is testament to the demonstrated industry leadership by Bruce Power L.P., their investors and the significant vendor community contribution that is supporting this major power infrastructure enhancement. Initiated as a 'turn-key' project solution separated from the operating units, this major refurbishment project has evolved to a fully managed in-house refurbishment project with the continued support from the broader vendor community. As part of this first-of-kind undertaking, Bruce Power L.P. is in the process of accomplishing such initiatives as a complete fuel channel re-tube (i.e. full core calandria and pressure tube replacement), replacement of all boilers (i.e. 16 in total) and the majority of feeder pipe replacement. Complimentary major upgrades and replacement of the remainder of plant equipment including both nuclear and non-nuclear valves, heat exchangers, electrical infrastructure, service water systems and components, all while meeting a parallel evolving/maturing regulatory environment related to achieving compliance with IAEA derived modern codes and standards. Returning to ground level, boiler replacement is a key part of the refurbishment undertaking and this further reflected a meeting of the 'old' and the 'new'. Pre

  19. Kids Inspire Kids for STEAM

    OpenAIRE

    Fenyvesi, Kristof; Houghton, Tony; Diego-Mantecón, José Manuel; Crilly, Elizabeth; Oldknow, Adrian; Lavicza, Zsolt; Blanco, Teresa F.

    2017-01-01

    Abstract The goal of the Kids Inspiring Kids in STEAM (KIKS) project was to raise students' awareness towards the multi- and transdisciplinary connections between the STEAM subjects (Science, Technology, Engineering, Arts & Mathematics), and make the learning about topics and phenomena from these fields more enjoyable. In order to achieve these goals, KIKS project has popularized the STEAM-concept by projects based on the students inspiring other students-approach and by utilizing new tec...

  20. The Evaluation of Steam Generator Level Measurement Model for OPR1000 Using RETRAN-3D

    International Nuclear Information System (INIS)

    Doo Yong Lee; Soon Joon Hong; Byung Chul Lee; Heok Soon Lim

    2006-01-01

    Steam generator level measurement is important factor for plant transient analyses using best estimate thermal hydraulic computer codes since the value of steam generator level is used for steam generator level control system and plant protection system. Because steam generator is in the saturation condition which includes steam and liquid together and is the place that heat exchange occurs from primary side to secondary side, computer codes are hard to calculate steam generator level realistically without appropriate level measurement model. In this paper, we prepare the steam generator models using RETRAN-3D that include geometry models, full range feedwater control system and five types of steam generator level measurement model. Five types of steam generator level measurement model consist of level measurement model using elevation difference in downcomer, 1D level measurement model using fluid mass, 1D level measurement model using fluid volume, 2D level measurement model using power and fluid mass, and 2D level measurement model using power and fluid volume. And we perform the evaluation of the capability of each steam generator level measurement model by simulating the real plant transient condition, the title is 'Reactor Trip by The Failure of The Deaerator Level Control Card of Ulchin Unit 3'. The comparison results between real plant data and RETRAN-3D analyses for each steam generator level measurement model show that 2D level measurement model using power and fluid mass or fluid volume has more realistic prediction capability compared with other level measurement models. (authors)

  1. Model studies of the vertical steam generator thermal-hydraulic characteristics

    International Nuclear Information System (INIS)

    Desyatun, V.F.; Moskvichev, V.F.; Ulasov, V.M.; Morozov, V.G.; Burkov, V.K.; Grebennikov, V.N.

    1984-01-01

    Results of investigations conducted to clarify the calculation technique and to test the workability of the main elements and units of the PGV-250 vertical steam generator of saturated steam are considered. The steam generating capacity of the plant is 1486 t/h, thermal power is 792 MW. Steam generation follows a multiple circulation scheme. The heat surface comprises 330-shields. The investigations are carried out with a model which reproduces all the main elements of the steam generator xcluding the economizer section. The flow rates of feed water, generated steam and coolant of the first circuit as well as temperature, pressure and humidity of the generated steam past the separator are determined. The average heat transfer factors of the heat surface are calculated on the base of the data obtained and a conclusion is drawn on the correctness of the thermohydraulic calculation technique used in development of the PGV-250 steam generator design. Temperature pulsations and heat surface steaming are not observed. The steam humidity at the outlet and steam capture into sinking tubes are within permissible values

  2. Steam generator life cycle management: Ontario Power Generation (OPG) experience

    International Nuclear Information System (INIS)

    Maruska, C.C.

    2002-01-01

    A systematic managed process for steam generators has been implemented at Ontario Power Generation (OPG) nuclear stations for the past several years. One of the key requirements of this managed process is to have in place long range Steam Generator Life Cycle Management (SG LCM) plans for each unit. The primary goal of these plans is to maximize the value of the nuclear facility through safe and reliable steam generator operation over the expected life of the units. The SG LCM plans integrate and schedule all steam generator actions such as inspection, operation, maintenance, modifications, repairs, assessments, R and D, performance monitoring and feedback. This paper discusses OPG steam generator life cycle management experience to date, including successes, failures and how lessons learned have been re-applied. The discussion includes relevant examples from each of the operating stations: Pickering B and Darlington. It also includes some of the experience and lessons learned from the activities carried out to refurbish the steam generators at Pickering A after several years in long term lay-up. The paper is structured along the various degradation modes that have been observed to date at these sites, including monitoring and mitigating actions taken and future plans. (author)

  3. Steam injection to increase oil recovery

    Energy Technology Data Exchange (ETDEWEB)

    Leutwyler, K; Bigelow, H L

    1966-03-01

    Speculation is made as to the possibility that future reserves can be increased with steam energy from the first day of production. Boilers and auxilary equipment for this operation should be designed especially for free air operations. The appropriate treatment of the water used is critical in controlling certain problems. Since this operation has been planned for working at temperatures of approximately 315$C, one of the best downhole units for such an operation is found to be the Retrievable Thermal Seal Packer. Expansion joints solve the problem of temperature inhibiting movement causing permanent corkscrew deformity. Conventional sealing material on the tubing threads is not suitable at high temperatures. A band of Teflon does the job well but its use is unjustified by cost and personnel untrained in its use. However, an excellent sealing material has been developed that fills all requirements. General suggestions for the use of steam injection include the good cementing jobs; treatment of the entire system as an integral unit; use of asbestos to insulate is of doubtful value because of the subsequent problems it causes; starting of the steam injection conservatively allows the cement and tubing to heat together. It is believed that this procedure helps reduce the possibility of vertical fractures in the cement.

  4. Hip joint replacement

    Science.gov (United States)

    Hip arthroplasty; Total hip replacement; Hip hemiarthroplasty; Arthritis - hip replacement; Osteoarthritis - hip replacement ... Your hip joint is made up of 2 major parts. One or both parts may be replaced during surgery: ...

  5. Process for superheating the steam generated by a light water nuclear reactor

    International Nuclear Information System (INIS)

    Vakil, H.B.; Brown, D.H.

    1976-01-01

    A process is submitted for superheating the pressurised steam generated in a light water nuclear reactor in which the steam is brought to 340 0 C at least. This superheated steam is used to operate a turbo-generator unit. The characteristic of the process is that an exothermal chemical reaction is used to generate the heat utilised during the superheating stage. The chemical reaction is a mechanisation, oxidation-reduction or hydrogenation reaction [fr

  6. Environmental Statement. Oswego Steam Station. Unit 5.

    Science.gov (United States)

    1971-12-27

    of the draft environmental statement was conducted and found to be in accord with the requirements set forth in the Environmental Policy Act of 1969...furnishcd by the Government or through GovernraenT- cncd facilities for the use of the liconse, inclumire the liccnzee’s proportionate share of the cost of...Commerce, Bureau of the Census I4 Osweqo, N.Y.. Greater Oswego Chamber of Commerce, Inc. IJ 15 Land Use and Transportation Plan - Policies for- Action

  7. Environmental Statement, Oswego Steam Station, Unit Six.

    Science.gov (United States)

    1973-03-29

    Tamias striatus) muskrat (Ondatra zibethicus) woodchuck (Marmota monax) Rept ile s eastern painted turtle (Chrysemys pi~cta) Amphibians grass frog (Rana...Terrestrial Ecoloqy The analysis presented on terrestrial ecology is somewhat nebulous due to the fact that the location of the generating facility is in...The analysis presented on terrestrial ecology is somewhat nebulous due to the - fact that the location of the generating facility is in an industrial

  8. Dependence of steam generator vibrations on feedwater pressure

    International Nuclear Information System (INIS)

    Sadilek, J.

    1989-01-01

    Vibration sensors are attached to the bottom of the steam generator jacket between the input and output primary circuit collectors. The effective vibration value is recorded daily. Several times higher vibrations were observed at irregular intervals; their causes were sought, and the relation between the steam generator vibrations measured at the bottom of its vessel and the feedwater pressure was established. The source of the vibrations was found to be in the feedwater tract of the steam generator. The feedwater tract is described and its hydraulic characteristics are given. Vibrations were measured on the S02 valve. It is concluded that vibrations can be eliminated by reducing the water pressure before the control valves and by replacing the control valves with ones with more suitable control characteristics. (E.J.). 3 figs., 1 tab., 3 refs

  9. Bench-to-bedside review: Treating acid–base abnormalities in the intensive care unit – the role of renal replacement therapy

    OpenAIRE

    Naka, Toshio; Bellomo, Rinaldo

    2004-01-01

    Acid–base disorders are common in critically ill patients. Metabolic acid–base disorders are particularly common in patients who require acute renal replacement therapy. In these patients, metabolic acidosis is common and multifactorial in origin. Analysis of acid–base status using the Stewart–Figge methodology shows that these patients have greater acidemia despite the presence of hypoalbuminemic alkalosis. This acidemia is mostly secondary to hyperphosphatemia, hyperlactatemia, and the accu...

  10. Analysis on the Current Status of Chemical Decontamination Technology of Steam Generators in the Oversea Nuclear Power Plants (NPPs)

    Energy Technology Data Exchange (ETDEWEB)

    Yoon, Taebin; Kim, Sukhoon; Kim, Juyoul; Kim, Juyub; Lee, Seunghee [FNC Technology Co. Ltd., Yongin (Korea, Republic of)

    2015-10-15

    The steam generators in Hanbit Unit 3 and 4 are scheduled to be replaced in 2018 and 2019, respectively. Nevertheless, the wastes from the dismantled steam generators are currently just on-site stored in the NPP because there are no disposal measures for the waste and lack of the decontamination techniques for large-sized metallic equipment. In contrast, in the oversea NPPs, there are many practical cases of chemical decontamination not only for oversized components in the NPPs such as reactor pressure vessel and steam generator, but also for major pipes. Chemical decontamination technique is more effective in decontaminating the components with complicated shape compared with mechanical one. Moreover, a high decontamination factor can be obtained by using strong solvent, and thereby most of radionuclides can be removed. Due to these advantages, the chemical decontamination has been used most frequently for operation of decontaminating the large-sized equipment. In this study, an analysis on the current status of chemical decontamination technique used for the steam generators of the foreign commercial NPPs was performed. In this study, the three major chemical decontamination processes were reviewed, which are applied to the decommissioning process of the steam generators in the commercial NPPs of the United States, Germany, and Belgium. The three processes have the different features in aspect of solvent, while those are based in common on the oxidation and reduction between the target metal surface and solvents. In addition, they have the same goals for improving the decontamination efficiency and decreasing the amount of the secondary waste generation. Based on the analysis results on component sub-processes and major advantages and disadvantages of each process, Table 2 shows the key fundamental technologies for decontamination of the steam generator in Korea and the major considerations in the development process of each technology. It is necessary to prepare

  11. Steam generator tube performance

    International Nuclear Information System (INIS)

    Tatone, O.S.; Pathania, R.S.

    1984-10-01

    A review of the performance of steam generator tubes in 116 water-cooled nuclear power reactors showed that tubes were plugged at 54 (46 percent) of the reactors. The number of tubes removed from service decreased from 4 692 (0.30 percent) in 1981 to 3 222 (0.20 percent) in 1982. The leading causes of tube failures were stress corrosion cracking from the primary side, stress corrosion cracking (or intergranular attack) from the secondary side and pitting corrosion. The lowest incidence of corrosion-induced defects from the secondary side occurred in reactors that have used only volatile treatment, with or without condensate demineralization

  12. Steam generator tube performance

    International Nuclear Information System (INIS)

    Tatone, O.S.; Tapping, R.L.; Stipan, L.

    1992-03-01

    A survey of steam generator operating experience for 1986 has been carried out for 184 pressurized water and pressurized heavy-water reactors, and 1 water-cooled, graphite-moderated reactor. Tubes were plugged at 75 of the reactors (40.5%). In 1986, 3737 tubes were plugged (0.14% of those in service) and 3148 tubes were repaired by sleeving. A small number of reactors accounted for the bulk of the plugged tubes, a phenomenon consistent with previous years. For 1986, the available tubesheet sludge data for 38 reactors has been compiled into tabular form, and sludge/deposit data will be incorporated into all future surveys

  13. Steam generator auxiliary systems

    International Nuclear Information System (INIS)

    Heinz, A.

    1982-01-01

    The author deals with damage and defect types obtaining in auxiliary systems of power plants. These concern water/steam auxiliary systems (feed-water tank, injection-control valves, slide valves) and air/fluegas auxiliary systems (blowers, air preheaters, etc.). Operating errors and associated damage are not dealt with; by contrast, weak spots are pointed out which result from planning and design. Damage types and events are collected in statistics in order to facilitate damage evaluation for arriving at improved design solutions. (HAG) [de

  14. DEMONSTRATION BULLETIN STEAM ENHANCED REMEDIATION STEAM TECH ENVIRONMENTAL SERVICES, INC.

    Science.gov (United States)

    Steam Enhanced Remediation is a process in which steam is injected into the subsurface to recover volatile and semivolatile organic contaminants. It has been applied successfully to recover contaminants from soil and aquifers and at a fractured granite site. This SITE demonstra...

  15. Steam generators: critical components in nuclear steam supply systems

    Energy Technology Data Exchange (ETDEWEB)

    Stevens-Guille, P D

    1974-02-28

    Steam generators are critical components in power reactors. Even small internal leaks result in costly shutdowns for repair. Surveys show that leaks have affected one half of all water-cooled reactors in the world with steam generators. CANDU reactors have demonstrated the highest reliability. However, AECL is actively evolving new technology in design, manufacture, inspection and operation to maintain reliability. (auth)

  16. Gentilly-2 and Point Lepreau divider plate replacement

    International Nuclear Information System (INIS)

    Schneider, W.; McClellan, G.; Weston, S.

    1996-01-01

    The steam generators at Hydro Quebec's Gentilly-2 and New Brunswick Power's Point Lepreau Nuclear Plants have been in operation since 1983, and were built with primary divider plates of a bolted panel configuration. During a routine outage inspection at Gentilly-2, it was noted that two bolts had dislodged from the divider plate and were located lying in the primary head. Subsequent inspections revealed erosion damage to a a substantial number of divider plate bolts and to a lesser extent, to the divider plate itself. After further inspection and repair the units were returned to operation, however, it was determined that a permanent replacement of the primary divider plates was going to be necessary. Upon evaluation of various options, it was decided that the panel type divider plates would be replaced with a single piece floating design. The divider plate itself was to be of one piece all-welded arrangement to be constructed from individual panels to be brought in through the manways. In view of the strength limitations of the bolted attachment of the upper seat bar to the tubesheet, a new welded seat was was provided. To counteract erosion concerns, the new divider plate is fitted with erosion resistant inserts of weld buildup and with improved sealing features in order to minimize leakage and erosion. At an advanced stage in the design and manufacture of the components, the issue of divider plate strength during loss of coolant accident (LOCA) conditions came into focus. Analysis was performed to determine the strength and/or failure characteristics of the divider plate to a variety of small and large LOCA conditions. Subsequently, Point Lepreau decided to replace their divider plates to address LOCA concerns. The paper describes the diagnosis of the original divider plates and the design. manufacture, field mobilization, installation and subsequent operation of the replacement divider plates. (author)

  17. The decommissioning of the BR3 steam generator

    International Nuclear Information System (INIS)

    Denissen, L.

    2006-01-01

    A steam generator is a crucial component in a PWR (Pressurized Water Reactor). It is the crossing between the primary, contaminated, circuit and the secondary water-steam circuit. The heat from the primary reactor coolant loop is transferred to the secondary side in thousands of small tubes. Due to several problems in the material of those tubes, like SCC (Stress Corrosion Cracking), insufficient control in water chemistry, which can be the cause of tube leakage, more and more steam generators are replaced today. Only in Belgium, already 17 of them are replaced. The old 300 ton heavy SGs are stored at the 2 nuclear power plants of Doel and Tihange . While it was foreseen in the BR3 strategy to dismantle the steam generator (only 30 ton), we took the opportunity to search for a complete package in the decommissioning of a steam generator. The complete management consists of a decontamination of the primary side followed by the complete dismantling. The first step, the decontamination with MEDOC (water box + tube bundle) has already been achieved in 2002. It has led to an important DF (Decontamination Factor) between 100 and 1000 and an important dose rate reduction. This hard chemical decontamination process has been described earlier in the scientific report 2002 (The BR3 steam generator decontamination with the MEDOC process - M. Ponnet). The second step, the complete dismantling of the SG has been executed in 2005. With the BR3 SG, the main goal was to dismantle it in a safe way and to free release a maximum of material. We've used two cutting tools to perform the job: A HPWJC (High Pressure Water Jet Cutting) tool in combination with a hydraulic robot and a water cooled diamond cable. The last technique was done in close collaboration with the external company Husqvarna. It was important to have an idea of the performance, the efficiency of the cable and the quantity and the type of secondary waste

  18. Nuclear steam generator tube to tubesheet joint optimization

    International Nuclear Information System (INIS)

    McGregor, Rod

    1999-01-01

    Industry-wide problems with Stress Corrosion Cracking in the Nuclear Steam Generator tube-to-tubesheet joint have led to costly repairs, plugging, and replacement of entire vessels. To improve corrosion resistance, new and replacement Steam Generator developments typically employ the hydraulic tube expansion process (full depth) to minimize tensile residual stresses and cold work at the critical transition zone between the expanded and unexpanded tube. These variables have undergone detailed study using specialized X-ray diffraction and analytical techniques. Responding to increased demands from Nuclear Steam Generator operators and manufacturers to credit the leak-tightness and strength contributions of the hydraulic expansion, various experimental tasks with complimentary analytical modelling were applied to improve understanding and control of tube to hole contact pressure. With careful consideration to residual stress impact, design for strength/leak tightness optimization addresses: Experimentally determined minimum contact pressure levels necessary to preclude incipient leakage into the tube/hole interface. The degradation of contact pressure at surrounding expansions caused by the sequential expansion process. The transient and permanent contact pressure variation associated with tubesheet hole dilation during Steam Generator operation. An experimental/analytical simulation has been developed to reproduce cyclic Steam Generator operating strains on the tubesheet and expanded joint. Leak tightness and pullout tests were performed during and following simulated Steam Generator operating transients. The overall development has provided a comprehensive understanding of the fabrication and in-service mechanics of hydraulically expanded joints. Based on this, the hydraulic expansion process can be optimized with respect to critical residual stress/cold work and the strength/leakage barrier criteria. (author)

  19. Steam-Generator Integrity Program/Steam-Generator Group Project

    International Nuclear Information System (INIS)

    1982-10-01

    The Steam Generator Integrity Program (SGIP) is a comprehensive effort addressing issues of nondestructive test (NDT) reliability, inservice inspection (ISI) requirements, and tube plugging criteria for PWR steam generators. In addition, the program has interactive research tasks relating primary side decontamination, secondary side cleaning, and proposed repair techniques to nondestructive inspectability and primary system integrity. The program has acquired a service degraded PWR steam generator for research purposes. This past year a research facility, the Steam Generator Examination Facility (SGEF), specifically designed for nondestructive and destructive examination tasks of the SGIP was completed. The Surry generator previously transported to the Hanford Reservation was then inserted into the SGEF. Nondestructive characterization of the generator from both primary and secondary sides has been initiated. Decontamination of the channelhead cold leg side was conducted. Radioactive field maps were established in the steam generator, at the generator surface and in the SGEF

  20. Embalse steam generators - status in 2009

    International Nuclear Information System (INIS)

    Luna, P.; Yetisir, M.; Roy, S.; MacEacheron, R.

    2009-01-01

    without major intervention led to a decision to replace the steam generators. This paper identifies the active degradation mechanisms affecting the steam generator performance and the actions taken since 2004 with an emphasis on the activities of 2007 to mitigate their impacts. The processes followed the actions taken in 2007 leading to return to service. The results of the root cause analysis along with the recommendations to change the secondary side chemistry are included. The tube inspection data were used in the development of a successful condition assessment tool to characterize the tube support plates. This characterization was the key step in the completion of a successful FFS evaluation. Additional actions implemented by Embalse to ensure safe and continued operation of the steam generators are also included. (author)

  1. Steam generator materials

    International Nuclear Information System (INIS)

    Kim, Joung Soo; Han, J. H.; Kim, H. P.; Lim, Y. S.; Lee, D. H.; Suh, J. H.; Hwang, S. S.; Hur, D. H.; Kim, D. J.; Kim, Y. H.

    2002-05-01

    In order to keep the nuclear power plant(NPP)s safe and increase their operating efficiency, axial stress corrosion cracking(SCC)(IGA/IGSCC, PWSCC, PbSCC) test techniques were developed and SCC property data of the archive steam generator tubing materials having been used in nuclear power plants operating in Korea were produced. The data obtained in this study were data-based, which will be used to clarify the damage mechanisms, to operate the plants safely, and to increase the lifetime of the tubing. In addition, the basic technologies for the improvement of the SCC property of the tubing materials, for new SCC inhibition, for damaged tube repair, and for manufacturing processes of the tubing were developed. In the 1 phase of this long term research, basic SCC test data obtained from the archive steam generator tubing materials used in NPPs operating in Korea were established. These basic technologies developed in the 1 phase will be used in developing process optimization during the 2 phase in order to develop application technologies to the field nuclear power plants

  2. PWR steam generator chemical cleaning. Phase II. Final report

    International Nuclear Information System (INIS)

    1980-01-01

    Two techniques believed capable of chemically dissolving the corrosion products in the annuli between tubes and support plates were developed in laboratory work in Phase I of this project and were pilot tested in Indian Point Unit No. 1 steam generators. In Phase II, one of the techniques was shown to be inadequate on an actual sample taken from an Indian Point Unit No. 2 steam generator. The other technique was modified slightly, and it was demonstrated that the tube/support plate annulus could be chemically cleaned effectively

  3. Steam hydrocarbon cracking and reforming

    NARCIS (Netherlands)

    Golombok, M.

    2004-01-01

    Many industrial chemical processes are taught as distinct contrasting reactions when in fact the unifying comparisons are greater than the contrasts. We examine steam hydrocarbon reforming and steam hydrocarbon cracking as an example of two processes that operate under different chemical reactivity

  4. Predicting tube repair at French nuclear steam generators using statistical modeling

    Energy Technology Data Exchange (ETDEWEB)

    Mathon, C., E-mail: cedric.mathon@edf.fr [EDF Generation, Basic Design Department (SEPTEN), 69628 Villeurbanne (France); Chaudhary, A. [EDF Generation, Basic Design Department (SEPTEN), 69628 Villeurbanne (France); Gay, N.; Pitner, P. [EDF Generation, Nuclear Operation Division (UNIE), Saint-Denis (France)

    2014-04-01

    Electricité de France (EDF) currently operates a total of 58 Nuclear Pressurized Water Reactors (PWR) which are composed of 34 units of 900 MWe, 20 units of 1300 MWe and 4 units of 1450 MWe. This report provides an overall status of SG tube bundles on the 1300 MWe units. These units are 4 loop reactors using the AREVA 68/19 type SG model which are equipped either with Alloy 600 thermally treated (TT) tubes or Alloy 690 TT tubes. As of 2011, the effective full power years of operation (EFPY) ranges from 13 to 20 and during this time, the main degradation mechanisms observed on SG tubes are primary water stress corrosion cracking (PWSCC) and wear at anti-vibration bars (AVB) level. Statistical models have been developed for each type of degradation in order to predict the growth rate and number of affected tubes. Additional plugging is also performed to prevent other degradations such as tube wear due to foreign objects or high-cycle flow-induced fatigue. The contribution of these degradation mechanisms on the rate of tube plugging is described. The results from the statistical models are then used in predicting the long-term life of the steam generators and therefore providing a useful tool toward their effective life management and possible replacement.

  5. Replacement of fine particle purification filter of the PHT purification system - 15083

    International Nuclear Information System (INIS)

    Lee, D.S.

    2015-01-01

    The increase of chalk river unidentified deposit (CRUD), a particulate corrosion product in PHT (primary heat transport) system with increased operating years of a nuclear power plant causes: -) the problems of increased heavy water decomposition and deuterium formation reaction due to catalytic reaction with CRUD, -) damage to PHT pump seal due to a corrosion product, -) damage to fuel channel closure seal, and increased radiation exposure of workers due to elevated dose rate in steam generator water chamber. Wolsung unit 3 and 4 have replaced fine filter media in PHT purification system in phases reducing the pore size of the filter media (5 μm → 2 μm → 1 μm → 0.45 μm) to solve this problem. The phased replacement of fine filter media by the one with a smaller pore size reduced CRUD in PHT system significantly and also radiation dose rate in steam generator water chamber. Accordingly, many problems related to the aging of a plant (including increased radiation exposure of workers during outage, damage to mechanical seal of PHT pump) have been solved. (author)

  6. Direct injection of superheated steam for continuous hydrolysis reaction

    KAUST Repository

    Wang, Weicheng

    2012-09-01

    The primary intent for previous continuous hydrolysis studies was to minimize the reaction temperature and reaction time. In this work, hydrolysis is the first step of a proprietary chemical process to convert lipids to sustainable, drop-in replacements for petroleum based fuels. To improve the economics of the process, attention is now focused on optimizing the energy efficiency of the process, maximizing the reaction rate, and improving the recovery of the glycerol by-product. A laboratory-scale reactor system has been designed and built with this goal in mind.Sweet water (water with glycerol from the hydrolysis reaction) is routed to a distillation column and heated above the boiling point of water at the reaction pressure. The steam pressure allows the steam to return to the reactor without pumping. Direct injection of steam into the hydrolysis reactor is shown to provide favorable equilibrium conditions resulting in a high quality of FFA product and rapid reaction rate, even without preheating the inlet water and oil and with lower reactor temperatures and lower fresh water demand. The high enthalpy of the steam provides energy for the hydrolysis reaction. Steam injection offers enhanced conditions for continuous hydrolysis of triglycerides to high-purity streams of FFA and glycerol. © 2012 Elsevier B.V.

  7. Lifetime management of the nuclear units in France

    International Nuclear Information System (INIS)

    Combes, J-P.; Godin, R.

    1994-01-01

    A systematic design study entitled 'Lifetime Project' has been initiated at Electricite de France, to estimate, plan, and maximize the life span of the French PWR plants. It is estimated that the present units will have a lifetime of 30 to 50 years. The life of a unit will be determined by that of its components, by economic considerations (whether it is cheaper to repair or replace the unit), and by safety considerations, which may be affected by changing safety standards. A 'periodic safety reassessment' takes place about every ten years. A list of 18 critical components can be summarized by saying that the main concerns are: radiation embrittlement of and within the reactor vessel, the steam generators, the concrete containment (which can not be replaced), instrumentation and control. Examination of samples from decommissioned plants, such as Chooz A, will provide valuable evidence of mechanisms of degradation due to aging

  8. Evaluation on mechanical and corrosion properties of steam generator tubing materials

    Energy Technology Data Exchange (ETDEWEB)

    Kim, In Sup; Lee, Byong Whi; Lee, Sang Kyu; Lee, Young Ho; Kim, Jun Whan; Lee, Ju Seok; Kwon, Hyuk Sang; Kim, Su Jung [Korea Advanced Institute of Science and Technology, Taejon (Korea, Republic of)

    1998-06-15

    Steam generator is one of the major components of nuclear reactor pressure boundary. It's main function os transferring heat which generated in the reactor to turbine generator through steam generator tube. In these days, steam generator tubing materials of operating plant are used Inconel 600 alloys. But according to the operation time, there are many degradation phenomena which included mechanical damage due to flow induced vibration and corrosion damage due to PWSCC, IGA/SCC and pitting etc. Recently Inconel 690 alloys are selected as new and replacement steam generator tubes for domestic nuclear power plant. But there are few study about mechanical and corrosion properties of Inconel 600 and 690. The objectives of this study is to evaluate and compare mechanical and corrosion propertied of steam generator tube materials.

  9. Evaluation on mechanical and corrosion properties of steam generator tubing materials

    International Nuclear Information System (INIS)

    Kim, In Sup; Lee, Byong Whi; Lee, Sang Kyu; Lee, Young Ho; Kim, Jun Whan; Lee, Ju Seok; Kwon, Hyuk Sang; Kim, Su Jung

    1998-06-01

    Steam generator is one of the major components of nuclear reactor pressure boundary. It's main function os transferring heat which generated in the reactor to turbine generator through steam generator tube. In these days, steam generator tubing materials of operating plant are used Inconel 600 alloys. But according to the operation time, there are many degradation phenomena which included mechanical damage due to flow induced vibration and corrosion damage due to PWSCC, IGA/SCC and pitting etc. Recently Inconel 690 alloys are selected as new and replacement steam generator tubes for domestic nuclear power plant. But there are few study about mechanical and corrosion properties of Inconel 600 and 690. The objectives of this study is to evaluate and compare mechanical and corrosion propertied of steam generator tube materials

  10. Measure Guideline. Steam System Balancing and Tuning for Multifamily Residential Buildings

    Energy Technology Data Exchange (ETDEWEB)

    Choi, Jayne [Partnership for Advanced Residential Retrofit (PARR), Chicago, IL (United States); Ludwig, Peter [Partnership for Advanced Residential Retrofit (PARR), Chicago, IL (United States); Brand, Larry [Partnership for Advanced Residential Retrofit (PARR), Chicago, IL (United States)

    2013-04-01

    This guideline provides building owners, professionals involved in multifamily audits, and contractors insights for improving the balance and tuning of steam systems. It provides readers an overview of one-pipe steam heating systems, guidelines for evaluating steam systems, typical costs and savings, and guidelines for ensuring quality installations. It also directs readers to additional resources for details not included here. Measures for balancing a distribution system that are covered include replacing main line vents and upgrading radiator vents. Also included is a discussion on upgrading boiler controls and the importance of tuning the settings on new or existing boiler controls. The guideline focuses on one-pipe steam systems, though many of the assessment methods can be generalized to two-pipe steam systems.

  11. Effects of band-steaming on microbial activity and abundance in organic farming soil

    DEFF Research Database (Denmark)

    Elsgaard, Lars; Jørgensen, Martin Heide; Elmholt, Susanne

    2010-01-01

    Band-steaming of arable soil at 80-90 ◦C kill off weed seeds prior to crop establishment which allows an extensive intra-row weed control. Here we evaluated the side-effects of in situ band-steaming on soil respiration, enzyme activities, and numbers of culturable bacteria and fungi in an organic...... insignificant or slightly stimulatory (P recovery during 90 days after band-steaming. Bacterial colony-forming units increased after soil steaming...... whereas the number of fungal propagules was reduced by 50% (P recovery potential...

  12. Thermal circuit and supercritical steam generator of the BGR-300 nuclear power plant

    International Nuclear Information System (INIS)

    Afanas'ev, B.P.; Godik, I.B.; Komarov, N.F.; Kurochnkin, Yu.P.

    1979-01-01

    Secondary coolant circuit and a steam generator for supercritical steam parameters of the BGR-300 reactor plant are described. The BGR-300 plant with a 300 MW(e) high-temperature gas-cooled fast reactor is developed as a pilot commercial plant. It is shown that the use of a supercritical pressure steam increases the thermal efficiency of the plant and descreases thermal releases to the environment, permits to use home-made commercial turbine plants of large unit power. The proposed supercritical pressure steam generator has considerable advantages from the viewpoint of heat transfer and hydrodynamical processes

  13. Integration between direct steam generation in linear solar collectors and supercritical carbon dioxide Brayton power cycles

    OpenAIRE

    Coco Enríquez, Luis; Muñoz Antón, Javier; Martínez-Val Peñalosa, José María

    2015-01-01

    Direct Steam Generation in Parabolic Troughs or Linear Fresnel solar collectors is a technology under development since beginning of nineties (1990's) for replacing thermal oils and molten salts as heat transfer fluids in concentrated solar power plants, avoiding environmental impacts. In parallel to the direct steam generation technology development, supercritical Carbon Dioxide Brayton power cycles are maturing as an alternative to traditional Rankine cycles for increasing net plant efficie...

  14. Proceedings of steam generator sludge deposition in recirculating and once through steam generator upper tube bundle and support plates

    International Nuclear Information System (INIS)

    Baker, R.L.; Harvego, E.A.

    1992-01-01

    The development of remedial measures of shot peening have given nuclear utilities viable measures to address primary water stress corrosion cracking to extend steam generator life. The nuclear utility industry is now faced with potential replacement of steam generators in nuclear power plants due to stress corrosion cracking and intergranular attach in crevice locations on the secondary side of steam generators at tube support plates and at the crevice at the top of the tube sheet. Significant work has been done on developing and understanding of the effects of sludge buildup on the corrosion process at these locations. This session was envisioned to provide a forum for the development of an understanding of the mechanisms which control the transport and deposition of sludge on the secondary side of steam generators. It is hoped that this information will aid utilities in monitoring the progression of fouling of these crevices by further knowledge in where to look for the onset of support plate crevice fouling. An understanding of the progression of fouling from upper tube support plates to those lower in the steam generator where higher temperatures cause the corrosion process to initiate first can aid the nuclear utility industry in developing remedial measures for this condition and in providing a forewarning of when to apply such remedial measures

  15. Evaluation of a dryer in a steam generator

    International Nuclear Information System (INIS)

    Xue Yunkui; Liu Shixun; Guandao, Xie; Chen Junliang

    1998-01-01

    The hooked-vane-type dryer is used in vertical, natural circulation steam generators used in PWR-type nuclear power stations. it separates the fine droplets of water carried by steam so that the steam generator outlet steam moisture is below 0.25%. Such low moisture is demanded to ensure a safe and economic operation of the unit. The dryer is composed of hooked vanes and a draining structure. A series of tests to screen different designs were performed using air-water mixture. The paper presents the results of the investigation of the effect of the number of drainage hooks , the bending angle , distance between two adjacent vanes, and other geometrical parameters on the performance of a hooked-vane-type steam dryer. It indicates that the dryer still works effectively when the moisture of the steam at the dryer inlet changes in a wide range, and that the performance of the dryer is closely related to the geometry of the draining structure . On the basis of the results of this program, a draining structure with an original design was selected and it is presented in the paper. The performance of the selected draining structure is better than that of similar structures in China and abroad. (author)

  16. Results of the 4th regular inspection in Unit 1 of the Mihama Nuclear Power Station

    International Nuclear Information System (INIS)

    1981-01-01

    The 4th regular inspection of Unit 1 in the Mihama Nuclear Power Station was made from July, 1975, to December, 1980, on its reactor and associated facilities. The respective stages of inspection during the years are described. The inspection by external appearance examination, disassembling leakage inspection and performance tests indicated crackings in piping for fuel-replacement water tank, the container penetration of recirculation pipe for residual-heat removal, and main steam-relief valve, and leakage in one fuel assembly. Radiation exposure of the personnel during the inspection was less than the permissible dose. Radiation exposure data for the personnel are given in tables. The improvements and repairs done accordingly were as follows: reapir of the piping for a fuel-replacement tank and recirculation piping for residual-heat removal, replacement of the main steam-relief valve, plugging of heating tubes for the steam-generator, replacement of pins and covers for control-rod guide pipes, improvement of safety protection system and installation of rare gas monitor. (J.P.N.)

  17. An Improved Steam Injection Model with the Consideration of Steam Override

    OpenAIRE

    He , Congge; Mu , Longxin; Fan , Zifei; Xu , Anzhu; Zeng , Baoquan; Ji , Zhongyuan; Han , Haishui

    2017-01-01

    International audience; The great difference in density between steam and liquid during wet steam injection always results in steam override, that is, steam gathers on the top of the pay zone. In this article, the equation for steam override coefficient was firstly established based on van Lookeren’s steam override theory and then radius of steam zone and hot fluid zone were derived according to a more realistic temperature distribution and an energy balance in the pay zone. On this basis, th...

  18. The modification of main steam safety valves in Qinshan phase Ⅱ expansion project

    International Nuclear Information System (INIS)

    Chen Haiqiao

    2012-01-01

    The main steam safety valves of NPP steam system are second- class nuclear safety component. It used to limit the pressure of SG secondary side and main steam system via emitting steam into the environment. At present, the main steam safety valves have mechanical valves and assisted power valves. According to the experience of power plants at home and abroad, including Qinshan Phase Ⅱ unit 1/2 experience feedback, Qinshan Phase Ⅱ expansion project made modification on valve type, setting value and valve body. This paper introduce the characteristics of different safety valve types, the modification of main steam safety valves and the modification analysis on safety issues.security and impact on the other systems in Qinshan Phase Ⅱ expansion project. (author)

  19. Forced circulation type steam generator simulation code: HT4

    International Nuclear Information System (INIS)

    Okamoto, Masaharu; Tadokoro, Yoshihiro

    1982-08-01

    The purpose of this code is a understanding of dynamic characteristics of the steam generator, which is a component of High-temperature Heat Transfer Components Test Unit. This unit is a number 4th test section of Helium Engineering Demonstration Loop (HENDEL). Features of this report are as follows, modeling of the steam generator, a basic relationship for the continuity equation, numerical analysis techniques of a non-linear simultaneous equation and computer graphics output techniques. Forced circulation type steam generator with strait tubes and horizontal cut baffles, applied in this code, have be designed at the Over All System Design of the VHTRex. The code is for use with JAERI's digital computer FACOM M200. About 1.5 sec required for each time step reiteration, then about 40 sec cpu time required for a standard problem. (author)

  20. Steam generator tube performance

    International Nuclear Information System (INIS)

    Tatone, O.S.; Pathania, R.S.

    1982-04-01

    The performance of steam generator tubes in water-cooled nuclear power reactors has been reviewed for 1980. Tube defects occurred at 38% of the 97 reactors surveyed. This is a marginal improvement over 1979 when defects occurred at 41% of the reactors. The number of failed tubes was also lower, 0.14% of the tubes in service in 1980 compared with 0.20% of those in service in 1979. Analysis of the causes of these failures indicates that stress corrosion cracking was the leading failure mechanism. Reactors that used all-volatile treatment of secondary water, with or without full-flow condensate demineralization since start-up showed the lowest incidence of corrosion-related defects

  1. Steam generator tube performance

    International Nuclear Information System (INIS)

    Tatone, O.S.; Pathania, R.S.

    1983-08-01

    A review of the performance of steam generator tubes in 110 water-cooled nuclear power reactors showed that tubes were plugged at 46 (42 percent) of the reactors. The number of tubes removed from service increased from 1900 (0.14 percent) in 1980 to 4692 (0.30 percent) in 1981. The leading causes of tube failures were stress corrosion cracking from the primary side, stress corrosion cracking (or intergranular attack) from the secondary side and pitting corrosion. The lowest incidence of corrosion-induced defects from the secondary side occurred in reactors that used all-volatile treatment since start-up. At one reactor a large number of degraded tubes were repaired by sleeving which is expected to become an important method of tube repair in the future

  2. Design, development and operating experience with wet steam turbines

    International Nuclear Information System (INIS)

    Bolter, J.R.

    1989-01-01

    The paper first describes the special characteristics of wet steam units. It then goes on to discuss the principal features of the units manufactured by the author's company, the considerations on which the designs were based, and the development work carried out to validate them. Some of the design features such as the separator/reheater units and the arrangements for water extraction in the high pressure turbine are unconventional. An important characteristic of all nuclear plant is the combination of high capital cost and low fuel cost, and the consequent emphasis placed on high availability. The paper describes some service problems experienced with wet steam plant and how these were overcome with minimum loss of generation. The paper also describes a number of the developments for future wet steam plant which have evolved from these experiences, and from research and development programmes aimed at increasing the efficiency and reliability of both conventional and wet steam units. Blading, rotor construction and separator/reheater units are considered. (author)

  3. Leak detection of steam or water into sodium in steam generators of liquid-metal fast breeder reactors

    International Nuclear Information System (INIS)

    Hans, R.; Dumm, K.

    1977-01-01

    The leakage of water or steam into sodium in LMFBR steam generators, including a study of how leaks are detected and located as well as the potential damage that could be caused by such leaks, is surveyed. The most interesting steam generator designs evolving in those countries that develop and construct LMFBRs are presented. The relevant protection measures are described. Fault conditions are defined and descriptions given of possible sequences of events leading to abnormal conditions in a steam generator. Taking into account theory, the potential of the hydrogen and oxygen detection systems is discussed. Different hydrogen and oxygen detection systems are fully described. In so far as interesting technical solutions are concerned, previously developed devices have also been taken into account. The way oxygen detection supplements hydrogen detection is described by listing the available oxygen measuring devices and the relevant theory. Only a few sonic and accelerometer measurements have been made on complete steam generator units so there is little system data available. Descriptions, however, have been included to give the state of the art achieved for the sensors and the achieved sensitivities or band widths. The potential of this monitoring method is made evident by adding the technical data of the sensors. Furthermore, the available systems for monitoring medium and large leakages are described. Finally, recommendations are made concerning steam generator development and the application of hydrogen and oxygen detection systems, as well as acoustic measuring methods for small-leakage detection

  4. Erosion corrosion in wet steam

    International Nuclear Information System (INIS)

    Tavast, J.

    1988-03-01

    The effect of different remedies against erosion corrosion in wet steam has been studied in Barsebaeck 1. Accessible steam systems were inspected in 1984, 1985 and 1986. The effect of hydrogen peroxide injection of the transport of corrosion products in the condensate and feed water systems has also been followed through chemical analyses. The most important results of the project are: - Low alloy chromium steels with a chromium content of 1-2% have shown excellent resistance to erosion corrosion in wet steam. - A thermally sprayed coating has shown good resistance to erosion corrosion in wet steam. In a few areas with restricted accessibility minor attacks have been found. A thermally sprayed aluminium oxide coating has given poor results. - Large areas in the moisture separator/reheater and in steam extraction no. 3 have been passivated by injection of 20 ppb hydrogen peroxide to the high pressure steam. In other inspected systems no significant effect was found. Measurements of the wall thickness in steam extraction no. 3 showed a reduced rate of attack. - The injection of 20 ppb hydrogen peroxide has not resulted in any significant reduction of the iron level result is contrary to that of earlier tests. An increase to 40 ppb resulted in a slight decrease of the iron level. - None of the feared disadvantages with hydrogen peroxide injection has been observed. The chromium and cobalt levels did not increase during the injection. Neither did the lifetime of the precoat condensate filters decrease. (author)

  5. Evaluating Steam Generator Tubing Corrosion through Shutdown Nickel and Cobalt Releases

    International Nuclear Information System (INIS)

    Marks, Chuck; Little, Mike; Krull, Peter; Dennis Hussey; Kenny Epperson

    2012-09-01

    During power operation in PWRs, steam generator tubing corrodes. In PWRs with nickel alloy steam generator tubing this leads to the release of nickel into the coolant. While not structurally significant, this process leads to corrosion product deposition on the fuel surfaces that can threaten fuel integrity, provide a site for boron precipitation, and, through activation and subsequent release, lead to increased out-of-core radiation fields. During shutdown, decreases in temperature and pH and an increase in the oxidation potential lead to dissolution of some corrosion products from the core. This work evaluated the masses of corrosion products released during shutdown as a proxy for steam generator tubing corrosion rates. The masses were evaluated for trends with time (e.g., the number of cycles) and for the influence of design and operating features such as tubing manufacturer, plant design (e.g., three loop versus four loop), and operating chemistry program. This project utilized the EPRI PWR Chemistry Monitoring and Assessment database. Data from over 20 units, many over several cycles, were assessed. The focus was on corrosion product release from Alloy 690TT tubing and all data were from units that had replaced steam generators. Data were analyzed using models developed from corrosion rate test data reported in the literature with a heavy reliance on data from the EDF BOREAL testing. The most striking result of this analysis was a clear division between plants that exhibited corrosion with a falling rate (i.e., following an exponential decay as has been observed, for example, in the BOREAL testing) and those that showed a constant corrosion rate, sustained for many outages. This difference appears to be most closely correlated with the manufacturer of the tubing. Within the two distinct plant groups (decaying corrosion rate and constant corrosion rate), details of the trends were evaluated for correlation with zinc addition history, plant type, and operating

  6. CANDU steam generator life management

    International Nuclear Information System (INIS)

    Tapping, R.L.; Nickerson, J.; Spekkens, P.; Maruska, C.

    1998-01-01

    Steam generators are a critical component of a nuclear power reactor, and can contribute significantly to station unavailability, as has been amply demonstrated in Pressurized Water Reactors (PWRs). CANDU steam generators are not immune to steam generator degradation, and the variety of CANDU steam generator designs and tube materials has led to some unexpected challenges. However, aggressive remedial actions, and careful proactive maintenance activities, have led to a decrease in steam generator-related station unavailability of Canadian CANDUs. AECL and the CANDU utilities have defined programs that will enable existing or new steam generators to operate effectively for 40 years. Research and development work covers corrosion and mechanical degradation of tube bundles and internals, chemistry, thermalhydraulics, fouling, inspection and cleaning, as well as provision for specially tool development for specific problem solving. A major driving force is development of CANDU-specific fitness-for-service guidelines, including appropriate inspection and monitoring technology to measure steam generator condition. Longer-range work focuses on development of intelligent on-line monitoring for the feedwater system and steam generator. New designs have reduced risk of corrosion and fouling, are more easily inspected and cleaned, and are less susceptible to mechanical damage. The Canadian CANDU utilities have developed programs for remedial actions to combat degradation of performance (Gentilly-2, Point Lepreau, Bruce A/B, Pickering A/B), and have developed strategic plans to ensure that good future operation is ensured. The research and development program, as well as operating experience, has identified where improvements in operating practices and/or designs can be made in order to ensure steam generator design life at an acceptable capacity factory. (author)

  7. Fatigue cracking on a steam generator tube

    International Nuclear Information System (INIS)

    Boccanfuso, M.; Lothios, J.; Thebault, Y.; Bruyere, B.; Duisabeau, L.; Herms, E.

    2015-01-01

    A circumferential fatigue crack was observed on a steam generator tube of the unit 2 of the Fessenheim plant. The results of destructive testing and the examination of the fracture surface show that the circumferential crack is linked to a large number of cycles with a very low stress intensity factor. Other aggravating factors like inter-granular corrosion have played a role in the initiating phase of fatigue cracking. The damage has been exacerbated by the lack of support of the tube at the level of the anti-vibration bars. (A.C.)

  8. Advanced technologies on steam generators

    Energy Technology Data Exchange (ETDEWEB)

    Sakata, Kaoru; Nakamura, Yuuki [Mitsubishi Heavy Industry Co., Takasago (Japan); Nakamori, Nobuo; Mizutani, Toshiyuki; Uwagawa, Seiichi; Saito, Itaru [Mitsubishi Heavy Industry Co., Kobe (Japan); Matsuoka, Tsuyoshi [Mitsubishi Heavy Industry Co., Yokohama (Japan)

    1997-12-31

    The thermal-hydraulic tests for a horizontal steam generator of a next-generation PWR (New PWR-21) were performed. The purpose of these tests is to understand the thermal-hydraulic behavior in the secondary side of horizontal steam generator during the plant normal operation. A test was carried out with cross section slice model simulated the straight tube region. In this paper, the results of the test is reported, and the effect of the horizontal steam generator internals on the thermalhydraulic behavior of the secondary side and the circulation characteristics of the secondary side are discussed. (orig.). 3 refs.

  9. Steam reformer with catalytic combustor

    Science.gov (United States)

    Voecks, Gerald E. (Inventor)

    1990-01-01

    A steam reformer is disclosed having an annular steam reforming catalyst bed formed by concentric cylinders and having a catalytic combustor located at the center of the innermost cylinder. Fuel is fed into the interior of the catalytic combustor and air is directed at the top of the combustor, creating a catalytic reaction which provides sufficient heat so as to maintain the catalytic reaction in the steam reforming catalyst bed. Alternatively, air is fed into the interior of the catalytic combustor and a fuel mixture is directed at the top. The catalytic combustor provides enhanced radiant and convective heat transfer to the reformer catalyst bed.

  10. Advanced technologies on steam generators

    Energy Technology Data Exchange (ETDEWEB)

    Sakata, Kaoru; Nakamura, Yuuki [Mitsubishi Heavy Industry Co., Takasago (Japan); Nakamori, Nobuo; Mizutani, Toshiyuki; Uwagawa, Seiichi; Saito, Itaru [Mitsubishi Heavy Industry Co., Kobe (Japan); Matsuoka, Tsuyoshi [Mitsubishi Heavy Industry Co., Yokohama (Japan)

    1998-12-31

    The thermal-hydraulic tests for a horizontal steam generator of a next-generation PWR (New PWR-21) were performed. The purpose of these tests is to understand the thermal-hydraulic behavior in the secondary side of horizontal steam generator during the plant normal operation. A test was carried out with cross section slice model simulated the straight tube region. In this paper, the results of the test is reported, and the effect of the horizontal steam generator internals on the thermalhydraulic behavior of the secondary side and the circulation characteristics of the secondary side are discussed. (orig.). 3 refs.

  11. Transcatheter aortic valve replacement

    Science.gov (United States)

    ... gov/ency/article/007684.htm Transcatheter aortic valve replacement To use the sharing features on this page, please enable JavaScript. Transcatheter aortic valve replacement (TAVR) is surgery to replace the aortic valve. ...

  12. Hip Replacement Surgery

    Science.gov (United States)

    ... Outreach Initiative Breadcrumb Home Health Topics English Español Hip Replacement Surgery Basics In-Depth Download Download EPUB ... PDF What is it? Points To Remember About Hip Replacement Surgery Hip replacement surgery removes damaged or ...

  13. Nicotine replacement therapy

    Science.gov (United States)

    Smoking cessation - nicotine replacement; Tobacco - nicotine replacement therapy ... Before you start using a nicotine replacement product, here are some things to know: The more cigarettes you smoke, the higher the dose you may need to ...

  14. Wet-steam erosion of steam turbine disks and shafts

    International Nuclear Information System (INIS)

    Averkina, N. V.; Zheleznyak, I. V.; Kachuriner, Yu. Ya.; Nosovitskii, I. A.; Orlik, V. G.; Shishkin, V. I.

    2011-01-01

    A study of wet-steam erosion of the disks and the rotor bosses or housings of turbines in thermal and nuclear power plants shows that the rate of wear does not depend on the diagrammed degree of moisture, but is determined by moisture condensing on the surfaces of the diaphragms and steam inlet components. Renovating the diaphragm seals as an assembly with condensate removal provides a manifold reduction in the erosion.

  15. Repowering options for steam power plants

    International Nuclear Information System (INIS)

    Wen, H.; Gopalarathinam, R.

    1992-01-01

    Repowering an existing steam power plant with a gas turbine offers an attractive alternative to a new plant or life extension, especially for unit sizes smaller than 300 MWe. Gas turbine repowering improves thermal efficiency and substantially increases the plant output. Based on recent repowering studies and projects, this paper examines gas turbine repowering options for 100 MWe, 200 MWe and 300 MWe units originally designed for coal firing and currently firing either coal or natural gas. Also discussed is the option for a phased future conversion of the repowered unit to fire coal-derived gas, should there be a fluctuation in the price or availability of natural gas. A modular coal gasification plant designed to shorten the conversion time is presented. Repowering options, performance, costs, and availability impacts are discussed for selected cases

  16. Improved servicing equipment for steam generators

    International Nuclear Information System (INIS)

    Hedtke, James C.

    1998-01-01

    To help keep personnel exposure as low as reasonably achievable and reduce critical path outage time, most nuclear plants of PWR design in the USA are now using improved equipment to service their steam generators (SGs) during outages. Because of the success of this equipment in the USA, two Belgian plants and one English plant have purchased this equipment, and other nuclear plants in Europe are also considering procurement. The improved SG servicing equipment discussed in this paper discusses consists of nozzle dams, segmented multi-stud tensioner, primary manway cover handling tool set, shield door and fastener cleaner. This equipment is specifically designed for the individual plant application and can also be specified for replacement SG projects. All of the equipment can be used without modification of the existing SGs. (author)

  17. Mitigation of organically bound sulphate from water treatment plants at Bruce NGS and impact on steam generator secondary side chemistry control

    Energy Technology Data Exchange (ETDEWEB)

    Nashiem, R.; Davloor, R.; Harper, B.; Smith, K. [Bruce Power, Tiverton, Ontario (Canada); Gauthier, C. [CTGIX Services Inc., Burlington, Ontario (Canada); Schexnailder, S. [GE Water and Process Technologies, Dallas, Texas (United States)

    2010-07-01

    Bruce Power is the source of more than 20 per cent of Ontario's electricity and currently operates six reactor units at the Bruce Nuclear Generating Station A (two units) and B (four units) stations located on Lake Huron. This paper discusses the challenges faced and operating experience (OPEX) gained in meeting WANO 1.0 chemistry performance objectives for steam generator secondary side chemistry control, particularly with control of steam generator sulphates. A detailed sampling and analysis program conducted as part of this study concluded that a major contributor to steam generator (SG) elevated sulphates is Organically Bound Sulphate (OBS) in Water Treatment Plants (WTP) effluent. The Bruce A and B WTPs consist of clarification with downstream sand and carbon filtration for Lake Water pre-treatment, which are followed by conventional Ion Exchange (IX) demineralization. Samples taken from various locations in the process stream were analyzed for a variety of parameters including both organic bound and inorganic forms of sulphate. The results are inconclusive with respect to finding the definitive source of OBS. This is primarily due to the condition that the OBS in the samples, which are in relatively low levels, are masked during chemical analysis by the considerably higher inorganic sulphate background. Additionally, it was also determined that on-line Total Organic Carbon (TOC) levels at different WTP locations did not always correlate well with OBS levels in the effluent, such that TOC could not be effectively used as a control parameter to improve OBS performance of the WTP operation. Improvement efforts at both plants focused on a number of areas including optimization of clarifier operation, replacement of IX resins, addition of downstream mobile polishing trailers, testing of new resins and adsorbents, pilot-scale testing with a Reverse Osmosis (RO) rig, review of resin regeneration and backwashing practices, and operating procedure improvements

  18. Mitigation of organically bound sulphate from water treatment plants at Bruce NGS and impact on steam generator secondary side chemistry control

    International Nuclear Information System (INIS)

    Nashiem, R.; Davloor, R.; Harper, B.; Smith, K.; Gauthier, C.; Schexnailder, S.

    2010-01-01

    Bruce Power is the source of more than 20 per cent of Ontario's electricity and currently operates six reactor units at the Bruce Nuclear Generating Station A (two units) and B (four units) stations located on Lake Huron. This paper discusses the challenges faced and operating experience (OPEX) gained in meeting WANO 1.0 chemistry performance objectives for steam generator secondary side chemistry control, particularly with control of steam generator sulphates. A detailed sampling and analysis program conducted as part of this study concluded that a major contributor to steam generator (SG) elevated sulphates is Organically Bound Sulphate (OBS) in Water Treatment Plants (WTP) effluent. The Bruce A and B WTPs consist of clarification with downstream sand and carbon filtration for Lake Water pre-treatment, which are followed by conventional Ion Exchange (IX) demineralization. Samples taken from various locations in the process stream were analyzed for a variety of parameters including both organic bound and inorganic forms of sulphate. The results are inconclusive with respect to finding the definitive source of OBS. This is primarily due to the condition that the OBS in the samples, which are in relatively low levels, are masked during chemical analysis by the considerably higher inorganic sulphate background. Additionally, it was also determined that on-line Total Organic Carbon (TOC) levels at different WTP locations did not always correlate well with OBS levels in the effluent, such that TOC could not be effectively used as a control parameter to improve OBS performance of the WTP operation. Improvement efforts at both plants focused on a number of areas including optimization of clarifier operation, replacement of IX resins, addition of downstream mobile polishing trailers, testing of new resins and adsorbents, pilot-scale testing with a Reverse Osmosis (RO) rig, review of resin regeneration and backwashing practices, and operating procedure improvements

  19. Fluidelastic instability analysis of steam generator U-tubes at antivibration bar-inactive modes

    International Nuclear Information System (INIS)

    Lee, S.K.; Jo, J.C.

    1995-01-01

    This paper presents the results of thermal-hydraulic and fluidelastic U-tube instability analyses performed for the vertical type pressurized water reactor (PWR) steam generator model being employed at Kori units 2, 3 and 4, and Yonggwang units 1 and 2 in Korea. The thermal-hydraulic analysis for providing the detailed three-dimensional two-phase flow field in the secondary side of the steam generator was accomplished using the ATHOS3 steam generator thermal-hydraulic analysis code. The UTVA2 code designed for calculating both the free vibration responses and fluidelastic stability ratio of a specific U-tube under consideration was used to assess the potential for fluidelastic instability of the steam generator U-tubes at various conditions of antivibration bar (AVB)-inactive modes. The results of the fluidelastic instability analysis were discussed in comparison with those obtained for the steam generator U-tubes at AVB-active mode

  20. Steam turbines for nuclear power stations in Czechoslovakia and their use for district heating

    International Nuclear Information System (INIS)

    Drahy, J.

    1989-01-01

    The first generation of nuclear power stations in Czechoslavakia is equipped with 440 MW e pressurized water reactors. Each reactor supplies two 220 MW, 3000 rpm condensing type turbosets operating with saturated steam. After the completion of heating water piping systems, all of the 24 units of 220 MW in Czechoslovak nuclear power stations will be operated as dual purpose units, delivering both electricity and heat. At the present time, second-generation nuclear power stations, with 1000 MW e PWRs, are being built. Each such plant is equipped with one 1000 MW full-speed saturated steam turbine. The turbine is so designed as to permit the extraction of steam corresponding to the following quantities of heat: 893 MJ/s with three-stage water heating (150/60 0 C); and 570 MJ/s with two-stage water heating (120/60 0 C). The steam is taken from uncontrolled steam extraction points. (author)