WorldWideScience

Sample records for total plant costs

  1. Total generating costs: coal and nuclear plants

    International Nuclear Information System (INIS)

    1979-02-01

    The study was confined to single and multi-unit coal- and nuclear-fueled electric-generating stations. The stations are composed of 1200-MWe PWRs; 1200-MWe BWRs; 800-and 1200-MWe High-Sulfur Coal units, and 800- and 1200-MWe Low-Sulfur Coal units. The total generating cost estimates were developed for commercial operation dates of 1985 and 1990; for 5 and 8% escalation rates, for 10 and 12% discount rates; and, for capacity factors of 50, 60, 70, and 80%. The report describes the methodology for obtaining annualized capital costs, levelized coal and nuclear fuel costs, levelized operation and maintenance costs, and the resulting total generating costs for each type of station. The costs are applicable to a hypothetical Middletwon site in the Northeastern United States. Plant descriptions with general design parameters are included. The report also reprints for convenience, summaries of capital cost by account type developed in the previous commercial electric-power cost studies. Appropriate references are given for additional detailed information. Sufficient detail is given to allow the reader to develop total generating costs for other cases or conditions

  2. Feasibility studies to improve plant availability and reduce total installed cost in IGCC plants

    Energy Technology Data Exchange (ETDEWEB)

    Sullivan, Kevin [General Electric Company, Houston, TX (United States); Anasti, William [General Electric Company, Houston, TX (United States); Fang, Yichuan [General Electric Company, Houston, TX (United States); Subramanyan, Karthik [General Electric Company, Houston, TX (United States); Leininger, Tom [General Electric Company, Houston, TX (United States); Zemsky, Christine [General Electric Company, Houston, TX (United States)

    2015-03-30

    The main purpose of this project is to look at technologies and philosophies that would help reduce the costs of an Integrated Gasification Combined Cycle (IGCC) plant, increase its availability or do both. GE’s approach to this problem is to consider options in three different areas: 1) technology evaluations and development; 2) constructability approaches; and 3) design and operation methodologies. Five separate tasks were identified that fall under the three areas: Task 2 – Integrated Operations Philosophy; Task 3 – Slip Forming of IGCC Components; Task 4 – Modularization of IGCC Components; Task 5 – Fouling Removal; and Task 6 – Improved Slag Handling. Overall, this project produced results on many fronts. Some of the ideas could be utilized immediately by those seeking to build an IGCC plant in the near future. These include the considerations from the Integrated Operations Philosophy task and the different construction techniques of Slip Forming and Modularization (especially if the proposed site is in a remote location or has a lack of a skilled workforce). Other results include ideas for promising technologies that require further development and testing to realize their full potential and be available for commercial operation. In both areas GE considers this project to be a success in identifying areas outside the core IGCC plant systems that are ripe for cost reduction and ity improvement opportunities.

  3. Power plant allocation in East Kalimantan considering total cost and emissions

    Science.gov (United States)

    Muslimin; Utomo, D. S.

    2018-04-01

    The fulfillment of electricity need in East Kalimantan is the responsibility of State Electricity Company/Perusahaan Listrik Negara (PLN). But PLN faces constraints in the lack of generating capacity it has. So the allocation of power loads in East Kalimantan has its own challenges. Additional power supplies from other parties are required. In this study, there are four scenarios tested to meet the electricity needs in East Kalimantan with the goal of minimizing costs and emissions. The first scenario is only by using PLN power plant. The second scenario is by combining PLN + Independent Power Producer (IPP) power plants. The third scenario is by using PLN + Rented power plants. The fourth scenario is by using PLN + Excess capacity generation. Numerical experiment using nonlinear programming is conducted with the help of the solver. The result shows that in the peak load condition, the best combination is scenario 2 (PLN + IPP). While at the lowest load condition, the cheapest scenario is PLN + IPP while the lowest emission is PLN + Rent.

  4. Total Logistic Plant Solutions

    Directory of Open Access Journals (Sweden)

    Dusan Dorcak

    2016-02-01

    Full Text Available The Total Logistics Plant Solutions, plant logistics system - TLPS, based on the philosophy of advanced control processes enables complex coordination of business processes and flows and the management and scheduling of production in the appropriate production plans and planning periods. Main attributes of TLPS is to create a comprehensive, multi-level, enterprise logistics information system, with a certain degree of intelligence, which accepts the latest science and research results in the field of production technology and logistics. Logistic model of company understands as a system of mutually transforming flows of materials, energy, information, finance, which is realized by chain activities and operations

  5. Power plant removal costs

    International Nuclear Information System (INIS)

    Ferguson, J.S.

    1998-01-01

    The financial, regulatory and political significance of the estimated high removal costs of nuclear power plants has generated considerable interest in recent years, and the political significance has resulted in the Nuclear Regulatory Commission (NRC) eliminating the use of conventional depreciation accounting for the decontamination portion of the removal (decommissioning). While nuclear plant licensees are not precluded from utilizing conventional depreciation accounting for the demolition of non-radioactive structures and site restoration, state and federal utility regulators have not been favorably inclined to requests for this distinction. The realization that steam-generating units will be more expensive to remove, relative to their original cost, predates the realization that nuclear units will be expensive. However, the nuclear issues have overshadowed this realization, but are unlikely to continue to do so. Numerous utilities have prepared cost estimates for steam generating units, and this presentation discusses the implications of a number of such estimates that are a matter of public record. The estimates cover nearly 400 gas, oil, coal and lignite generating units. The earliest estimate was made in 1978, and for analysis purposes the author has segregated them between gas and oil units, and coal and lignite units

  6. Total Cost of Ownership and Cost-to-Serve

    DEFF Research Database (Denmark)

    Zachariassen, Frederik

    2007-01-01

    Artiklen reviewer den eksisterende litteratur vedrørende økonomistyringsværktøjerne Total Cost of Ownership (TCO) og Cost-to-Serve (CtS). Herefter kortlægges det, hvordan TCO og CtS bidrager til en identificering af direkte omkostninger såvel som indirekte omkostninger henholdsvis up-stream og down...

  7. Procedure for estimating permanent total enclosure costs

    Energy Technology Data Exchange (ETDEWEB)

    Lukey, M E; Prasad, C; Toothman, D A; Kaplan, N

    1999-07-01

    Industries that use add-on control devices must adequately capture emissions before delivering them to the control device. One way to capture emissions is to use permanent total enclosures (PTEs). By definition, an enclosure which meets the US Environmental Protection Agency's five-point criteria is a PTE and has a capture efficiency of 100%. Since costs play an important role in regulatory development, in selection of control equipment, and in control technology evaluations for permitting purposes, EPA has developed a Control Cost Manual for estimating costs of various items of control equipment. EPA's Manual does not contain any methodology for estimating PTE costs. In order to assist environmental regulators and potential users of PTEs, a methodology for estimating PTE costs was developed under contract with EPA, by Pacific Environmental Services, Inc. (PES) and is the subject of this paper. The methodology for estimating PTE costs follows the approach used for other control devices in the Manual. It includes procedures for sizing various components of a PTE and for estimating capital as well as annual costs. It contains verification procedures for demonstrating compliance with EPA's five-point criteria. In addition, procedures are included to determine compliance with Occupational Safety and Health Administration (OSHA) standards. Meeting these standards is an important factor in properly designing PTEs. The methodology is encoded in Microsoft Exel spreadsheets to facilitate cost estimation and PTE verification. Examples are given throughout the methodology development and in the spreadsheets to illustrate the PTE design, verification, and cost estimation procedures.

  8. Nuclear Power Plant Module, NPP-1: Nuclear Power Cost Analysis.

    Science.gov (United States)

    Whitelaw, Robert L.

    The purpose of the Nuclear Power Plant Modules, NPP-1, is to determine the total cost of electricity from a nuclear power plant in terms of all the components contributing to cost. The plan of analysis is in five parts: (1) general formulation of the cost equation; (2) capital cost and fixed charges thereon; (3) operational cost for labor,…

  9. Procedure for estimating permanent total enclosure costs

    Energy Technology Data Exchange (ETDEWEB)

    Lukey, M.E.; Prasad, C.; Toothman, D.A.; Kaplan, N.

    1999-07-01

    Industries that use add-on control devices must adequately capture emissions before delivering them to the control device. One way to capture emissions is to use permanent total enclosures (PTEs). By definition, an enclosure which meets the US Environmental Protection Agency's five-point criteria is a PTE and has a capture efficiency of 100%. Since costs play an important role in regulatory development, in selection of control equipment, and in control technology evaluations for permitting purposes, EPA has developed a Control Cost Manual for estimating costs of various items of control equipment. EPA's Manual does not contain any methodology for estimating PTE costs. In order to assist environmental regulators and potential users of PTEs, a methodology for estimating PTE costs was developed under contract with EPA, by Pacific Environmental Services, Inc. (PES) and is the subject of this paper. The methodology for estimating PTE costs follows the approach used for other control devices in the Manual. It includes procedures for sizing various components of a PTE and for estimating capital as well as annual costs. It contains verification procedures for demonstrating compliance with EPA's five-point criteria. In addition, procedures are included to determine compliance with Occupational Safety and Health Administration (OSHA) standards. Meeting these standards is an important factor in properly designing PTEs. The methodology is encoded in Microsoft Exel spreadsheets to facilitate cost estimation and PTE verification. Examples are given throughout the methodology development and in the spreadsheets to illustrate the PTE design, verification, and cost estimation procedures.

  10. Total cost of ownership: Getting past the 10% solution

    International Nuclear Information System (INIS)

    Anderson, R.F.

    1996-01-01

    As the refining industry strives to succeed in a more-competitive world, some fresh ideas are needed to counter the headlines of plant closings, layoffs, and corporate restructurings. Other industries facing the same pressures have discovered opportunities to reduce cost in a more human and effective manner by using some tools borrowed from the Total Quality process to enhance the procurement process. Experience suggests that the purchase cost is a small fraction of the actual cost of a commodity and is often dwarfed by hidden costs. Discovering and eliminating the hidden costs of variation, nonoptimal operations, and poorly aligned vendor relations is vital to economic survival. The purpose of this paper is to suggest some fresh approaches to vendor-customer relations that can dramatically reduce undesired costs

  11. Historical plant cost and annual production expenses for selected electric plants, 1982

    International Nuclear Information System (INIS)

    1984-01-01

    This publication is a composite of the two prior publications, Hydroelectric Plant Construction Cost and Annual Production Expenses and Thermal-Electric Plant Construction Cost and Annual Production Expenses. Beginning in 1979, Thermal-Electric Plant Construction Cost and Annual Production Expenses contained information on both steam-electric and gas-turbine electric plant construction cost and annual production expenses. The summarized historical plant cost described under Historical Plant Cost in this report is the net cumulative-to-date actual outlays or expenditures for land, structures, and equipment to the utility. Historical plant cost is the initial investment in plant (cumulative to the date of initial commercial operation) plus the costs of all additions to the plant, less the value of retirements. Thus, historical plant cost includes expenditures made over several years, as modifications are made to the plant. Power Production Expenses is the reporting year's plant operation and maintenance expenses, including fuel expenses. These expenses do not include annual fixed charges on plant cost (capital costs) such as interest on debt, depreciation or amortization expenses, and taxes. Consequently, total production expenses and the derived unit costs are not the total cost of producing electric power at the various plants. This publication contains data on installed generating capacity, net generation, net capability, historical plant cost, production expenses, fuel consumption, physical and operating plant characteristics, and other relevant statistical information for selected plants

  12. Power plant cost estimates put to the test

    International Nuclear Information System (INIS)

    Crowley, J.H.

    1978-01-01

    The growth in standards for nuclear applications and the impact of these codes and standards on the cost of nuclear power plants is described. The preparation of cost estimates and reasons for apparent discrepancies are discussed. Consistent estimates of nuclear power plant costs have been prepared in the USA for over a decade. They show that the difference in capital costs between nuclear and coal fired plants is narrowing and that when total generating costs are calculated nuclear power is substantially cheaper. (UK)

  13. Total quality drives nuclear plant improvements

    International Nuclear Information System (INIS)

    Richey, R.B.

    1991-01-01

    Total quality (TQ) at Carolina Power and Light (CP and L) is fulfilling a 1985 vision of Sherwood H. Smith, Jr., CP and L's chairman, president, and chief executive officer. The TQ concept has provided a way for employees to align their creative energies toward meeting the business needs of the company. Throughout CP and L, TQ has been recognized as the vehicle for reducing operating costs and improving customer satisfaction. Within the nuclear organization, application of the TQ process has helped to improve communications, resolve challenges, and provide more consistent work practices among CP and L's three nuclear plants. Total quality was introduced from the top down, with initial benefits coming from team interactions. Senior management at CP and L defined the corporate expectations and outlined the training requirements for implementing TQ. Management staffs at each organizational level became steering committees for TQ team activities within their departments. Teams of employees most knowledgeable about a given work area were empowered to solve problems or overcome obstacles related to that work area. Employees learned to become better team players and to appreciate the quality of decisions reached through group consensus. Now, formalized methods that started TQ are becoming part of the day-to-day work ethic

  14. Total phenolics and total flavonoids in selected Indian medicinal plants.

    Science.gov (United States)

    Sulaiman, C T; Balachandran, Indira

    2012-05-01

    Plant phenolics and flavonoids have a powerful biological activity, which outlines the necessity of their determination. The phenolics and flavonoids content of 20 medicinal plants were determined in the present investigation. The phenolic content was determined by using Folin-Ciocalteu assay. The total flavonoids were measured spectrophotometrically by using the aluminium chloride colorimetric assay. The results showed that the family Mimosaceae is the richest source of phenolics, (Acacia nilotica: 80.63 mg gallic acid equivalents, Acacia catechu 78.12 mg gallic acid equivalents, Albizia lebbeck 66.23 mg gallic acid equivalents). The highest total flavonoid content was revealed in Senna tora which belongs to the family Caesalpiniaceae. The present study also shows the ratio of flavonoids to the phenolics in each sample for their specificity.

  15. Relative costs to nuclear plants: international experience

    International Nuclear Information System (INIS)

    Souza, Jair Albo Marques de

    1992-03-01

    This work approaches the relative costs to nuclear plants in the Brazil. It also presents the calculation methods and its hypothesis to determinate the costs, and the nacional experience in costs of investment, operating and maintenance of the nuclear plants

  16. Nuclear plant life cycle costs

    International Nuclear Information System (INIS)

    Durante, R.W.

    1994-01-01

    Life cycle costs of nuclear power plants in the United States are discussed. The author argues that these costs have been mishandled or neglected. Decommissioning costs have escalated, e.g. from $328 per unit in 1991 to $370 in 1993 for the Sacramento Municipal Utility District, though they still only amount to less than 0.1 cent per kWh. Waste management has been complicated in the U.S. by the decision to abandon civilian reprocessing; by the year 2000, roughly 30 U.S. nuclear power units will have filled their storage pools; dry storage has been delayed, and will be an expense not originally envisaged. Some examples of costs of major component replacement are provided. No single component has caused as much operational disruption and financial penalties as the steam generator. Operation and maintenance costs have increased steadily, and now amount to more than 70% of production costs. A strategic plan by the Nuclear Power Oversight Committee (of U.S. utilities) will ensure that the ability to correctly operate and maintain a nuclear power plant is built into the original design. 6 figs

  17. Insurance cost of Swedish nuclear power plants

    International Nuclear Information System (INIS)

    Kaellstrand, Aasa.

    1992-01-01

    What happens if a reactor accident occurs? Can victims of a nuclear accident be compensated for losses? The rights of a victim of a nuclear accident to be compensated for losses are governed by international conventions. These conventions make the licensee of a nuclear plant strictly liable. However, the maximum amount of compensation is limited. In Sweden the total liability of the plant-owner is maximized to 1.2 million Swedish Crowns, that is 0.02 oere/kWh. After the accidents of Harrisburg (1979) and Chernobyl (1986), it has become clear that the amounts of the various conventions are not at all sufficient to cover the damages caused by such an accident. In spite of these facts, there are a large number of reliable sources, who think that the insurance costs are negligible in the cost of production. A cost-benefit analysis based on a study performed by Ottinger et al. in 'Environmental costs of electricity' is therefore adopted to derive the costs of the external effects of nuclear plant operation and from releases to the environment during operation. The environmental externality costs of Swedish nuclear power plant operations are in this report estimated to 18.3 oere/kWh. This figure can be compared to the insurance cost, which for the present is 0.02 oere/kWh. The 'real' insurance cost including the external effects is calculated to approximately 1.12 billion Swedish Crowns] That is 900 times larger than the insurance premium, which the licensee of a nuclear plant faces] (au)

  18. Cost analysis of light water reactor power plants

    International Nuclear Information System (INIS)

    Mooz, W.E.

    1978-06-01

    A statistical analysis is presented of the capital costs of light water reactor (LWR) electrical power plants. The objective is twofold: to determine what factors are statistically related to capital costs and to produce a methodology for estimating these costs. The analysis in the study is based on the time and cost data that are available on U.S. nuclear power plants. Out of a total of about 60 operating plants, useful capital-cost data were available on only 39 plants. In addition, construction-time data were available on about 65 plants, and data on completed construction permit applications were available for about 132 plants. The cost data were first systematically adjusted to constant dollars. Then multivariate regression analyses were performed by using independent variables consisting of various physical and locational characteristics of the plants. The dependent variables analyzed were the time required to obtain a construction permit, the construction time, and the capital cost

  19. The total lifetime costs of smoking

    DEFF Research Database (Denmark)

    Rasmussen, S.R.; Prescott, E.; Sørensen, T.I.A.

    2004-01-01

    Net costs of smoking in a lifetime perspective and, hence, the economic interests in antismoking policies have been questioned. It has been proposed that the health-related costs of smoking are balanced by smaller expenditure due to shorter life expectancy.......Net costs of smoking in a lifetime perspective and, hence, the economic interests in antismoking policies have been questioned. It has been proposed that the health-related costs of smoking are balanced by smaller expenditure due to shorter life expectancy....

  20. Supplier managed inventory in the OEM supply chain : the impact of relationship types on total costs and cost distribution

    NARCIS (Netherlands)

    Nyen, van P.L.M.; Bertrand, J.W.M.; Ooijen, van H.P.G.; Vandaele, N.J.

    2009-01-01

    We investigate the impact of four variants of supplier managed inventory on total costs and cost distribution in a capital goods supply chain consisting of a parts supplier who delivers parts to an original equipment manufacturer’s assembly plant. The four supplier managed inventory variants differ

  1. Reduction of capital costs of nuclear power plants

    International Nuclear Information System (INIS)

    2000-01-01

    The competitiveness of nuclear power plants depends largely on their capital costs represent some 60 per cent of their total generation costs. Reviewing and analysing ways and means to reduce capital costs of nuclear power plants are essential to enhance the economic viability of the nuclear option. The report is based upon cost information and data provided by experts from NEA Member countries. It investigates the efficiency of alternative methods for reducing capital costs of nuclear units. It will provide stakeholders from the industry and governmental agencies with relevant elements in support of policy making. (author)

  2. External costs of material recycling strategies for fusion power plants

    International Nuclear Information System (INIS)

    Hallberg, B.; Aquilonius, K.; Lechon, Y.; Cabal, H.; Saez, R.M.; Schneider, T.; Lepicard, S.; Ward, D.; Hamacher, T.; Korhonen, R.

    2003-01-01

    This paper is based on studies performed within the framework of the project Socio-Economic Research on Fusion (SERF3). Several fusion power plant designs (SEAFP Models 1-6) were compared focusing on part of the plant's life cycle: environmental impact of recycling the materials. Recycling was considered for materials replaced during normal operation, as well as materials from decommissioning of the plant. Environmental impact was assessed and expressed as external cost normalised with the total electrical energy output during plant operation. The methodology used for this study has been developed by the Commission of the European Union within the frame of the ExternE project. External costs for recycling, normalised with the energy production during plant operation, are very low compared with those for other energy sources. Results indicate that a high degree of recycling is preferable, at least when considering external costs, because external costs of manufacturing of new materials and disposal costs are higher

  3. Direct cost comparison of totally endoscopic versus open ear surgery.

    Science.gov (United States)

    Patel, N; Mohammadi, A; Jufas, N

    2018-02-01

    Totally endoscopic ear surgery is a relatively new method for managing chronic ear disease. This study aimed to test the null hypothesis that open and endoscopic approaches have similar direct costs for the management of attic cholesteatoma, from an Australian private hospital setting. A retrospective direct cost comparison of totally endoscopic ear surgery and traditional canal wall up mastoidectomy for the management of attic cholesteatoma in a private tertiary setting was undertaken. Indirect and future costs were excluded. A direct cost comparison of anaesthetic setup and resources, operative setup and resources, and surgical time was performed between the two techniques. Totally endoscopic ear surgery has a mean direct cost reduction of AUD$2978.89 per operation from the hospital perspective, when compared to canal wall up mastoidectomy. Totally endoscopic ear surgery is more cost-effective, from an Australian private hospital perspective, than canal wall up mastoidectomy for attic cholesteatoma.

  4. Cost Savings of Nuclear Power with Total Fuel Reprocessing

    International Nuclear Information System (INIS)

    Solbrig, Charles W.; Benedict, Robert W.

    2006-01-01

    The cost of fast reactor (FR) generated electricity with pyro-processing is estimated in this article. It compares favorably with other forms of energy and is shown to be less than that produced by light water reactors (LWR's). FR's use all the energy in natural uranium whereas LWR's utilize only 0.7% of it. Because of high radioactivity, pyro-processing is not open to weapon material diversion. This technology is ready now. Nuclear power has the same advantage as coal power in that it is not dependent upon a scarce foreign fuel and has the significant additional advantage of not contributing to global warming or air pollution. A jump start on new nuclear plants could rapidly allow electric furnaces to replace home heating oil furnaces and utilize high capacity batteries for hybrid automobiles: both would reduce US reliance on oil. If these were fast reactors fueled by reprocessed fuel, the spent fuel storage problem could also be solved. Costs are derived from assumptions on the LWR's and FR's five cost components: 1) Capital costs: LWR plants cost $106/MWe. FR's cost 25% more. Forty year amortization is used. 2) The annual O and M costs for both plants are 9% of the Capital Costs. 3) LWR fuel costs about 0.0035 $/kWh. Producing FR fuel from spent fuel by pyro-processing must be done in highly shielded hot cells which is costly. However, the five foot thick concrete walls have the advantage of prohibiting diversion. LWR spent fuel must be used as feedstock for the FR initial core load and first two reloads so this FR fuel costs more than LWR fuel. FR fuel costs much less for subsequent core reloads ( 6 /MWe. The annual cost for a 40 year licensed plant would be 2.5 % of this or less if interest is taken into account. All plants will eventually have to replace those components which become radiation damaged. FR's should be designed to replace parts rather than decommission. The LWR costs are estimated to be 2.65 cents/kWh. FR costs are 2.99 cents/kWh for the first

  5. Classification of nuclear plant cost to energy

    International Nuclear Information System (INIS)

    Long, G.A.

    1983-01-01

    In order to understand why the fixed-cost/variable-cost method of classifying nuclear plant costs can lead to rate discontinuities, the author must examine the factors which lead to the decision to build a nuclear power plant and the interrelationship between demand (KW) and energy (KWH). The problems and inequities associated with the nuclear plants can be avoided by recognizing that fixed costs are related to both demand and energy and by using a costing methodology which closely relates to the functional purpose of the plant. Generally, this leads to classifying fixed costs of nuclear plants primarily to the energy function in an embedded cost-of-service study and through either implicit or explicit recognition of fuel savings in a marginal cost study. The large rate discontinuities which occurred in the scenario can be resolved. Costs associated with demand or energy charges remain relatively stable compared to actual capacity costs and customers would not experience large changes in their bills due solely to a particular costing convention

  6. An analysis of nuclear plant operating costs: A 1991 update

    International Nuclear Information System (INIS)

    1991-05-01

    This report updates a 1988 Energy Information Administration (EIA) report which examined trends in nonfuel operating costs at the Nation's nuclear power plants. Nonfuel operating costs are comprised of operating and maintenance (O ampersand M) costs and capital expenditures incurred after a plant begins operating. Capital expenditures are typically called ''capital additions'' because the costs are added to the utility's rate base and recovered as a depreciation expense over several years, the number of years being regulated by State Public Utility Commissions. These costs consist of large maintenance expenditures needed to keep a plant operational as well as those needed to make plant modifications mandated by the Nuclear Regulatory Commission (NRC) or implemented at the utility's discretion. The 1988 report found that from 1974 through 1984, the last year for which data were available, nuclear power plant nonfuel operating costs escalated by 14 percent annually in real terms. The objective of the present study was to determine whether trends in nonfuel operating costs have changed since 1984, if there was any change in the underlying factors influencing these costs, and if so, how these changes affect the basic conclusions of the 1988 report. The general trends are encouraging: Total nonfuel operating costs peaked in 1984 and have been lower since that time; O ampersand M costs have been rising, but at a much lower rate than seen from 1974 through 1984; capital additions costs have actually been declining. 9 figs., 12 tabs

  7. Cogeneration Power Plants: a Proposed Methodology for Unitary Production Cost

    International Nuclear Information System (INIS)

    Metalli, E.

    2009-01-01

    A new methodology to evaluate unitary energetic production costs in the cogeneration power plants is proposed. This methodology exploits the energy conversion factors fixed by Italian Regulatory Authority for Electricity and Gas. So it allows to settle such unitary costs univocally for a given plant, without assigning them a priori subjective values when there are two or more energy productions at the same time. Moreover the proposed methodology always ensures positive values for these costs, complying with the total generation cost balance equation. [it

  8. Total life cycle cost model for electric power stations

    International Nuclear Information System (INIS)

    Cardullo, M.W.

    1995-01-01

    The Total Life Cycle Cost (TLCC) model for electric power stations was developed to provide a technology screening model. The TLCC analysis involves normalizing cost estimates with respect to performance standards and financial assumptions and preparing a profile of all costs over the service life of the power station. These costs when levelized present a value in terms of a utility electricity rate. Comparison of cost and the pricing of the electricity for a utility shows if a valid project exists. Cost components include both internal and external costs. Internal costs are direct costs associated with the purchase, and operation of the power station and include initial capital costs, operating and maintenance costs. External costs result from societal and/or environmental impacts that are external to the marketplace and can include air quality impacts due to emissions, infrastructure costs, and other impacts. The cost stream is summed (current dollars) or discounted (constant dollars) to some base year to yield a overall TLCC of each power station technology on a common basis. While minimizing life cycle cost is an important consideration, it may not always be a preferred method for some utilities who may prefer minimizing capital costs. Such consideration does not always result in technology penetration in a marketplace such as the utility sector. Under various regulatory climates, the utility is likely to heavily weigh initial capital costs while giving limited consideration to other costs such as societal costs. Policy makers considering external costs, such as those resulting from environmental impacts, may reach significantly different conclusions about which technologies are most advantageous to society. The TLCC analysis model for power stations was developed to facilitate consideration of all perspectives

  9. Cost savings from extended life nuclear plants

    International Nuclear Information System (INIS)

    Forest, L.R. Jr.; Deutsch, T.R.; Schenler, W.W.

    1988-09-01

    This study assesses the costs and benefits of nuclear power plant life extension (NUPLEX) for the overall US under widely varying economic assumptions and compares these with alternative new coal- fired plants (NEWCOAL). It is found that NUPLEX saves future electricity consumers more than 3 cents/-kwh compared with NEWCOAL. The NUPLEX costs and benefits for existing individual US nuclear power plants under base-line, or most likely, assumptions are assessed to determine the effects of the basic plant design and plant age. While benefits vary widely, virtually all units would have a positive benefit from NUPLEX. The study also presents a cost-benefit analysis of the nuclear industry's planned advanced light water reactor (ALWR). It is concluded that ALWR offers electrical power at a substantially lower cost than NEWCOAL. 9 refs., 6 figs

  10. Costs of Decommissioning Nuclear Power Plants

    International Nuclear Information System (INIS)

    Neri, Emilio; French, Amanda; Urso, Maria Elena; Deffrennes, Marc; Rothwell, Geoffrey; ); Rehak, Ivan; Weber, Inge; ); Carroll, Simon; Daniska, Vladislav

    2016-01-01

    While refurbishments for the long-term operation of nuclear power plants and for the lifetime extension of such plants have been widely pursued in recent years, the number of plants to be decommissioned is nonetheless expected to increase in future, particularly in the United States and Europe. It is thus important to understand the costs of decommissioning so as to develop coherent and cost-effective strategies, realistic cost estimates based on decommissioning plans from the outset of operations and mechanisms to ensure that future decommissioning expenses can be adequately covered. This study presents the results of an NEA review of the costs of decommissioning nuclear power plants and of overall funding practices adopted across NEA member countries. The study is based on the results of this NEA questionnaire, on actual decommissioning costs or estimates, and on plans for the establishment and management of decommissioning funds. Case studies are included to provide insight into decommissioning practices in a number of countries. (authors)

  11. New plant construction cost and schedule

    International Nuclear Information System (INIS)

    Akins, M. J.

    2009-01-01

    The presentation covers the following topics: cost structure; capital costs; variation of capital costs; trends in power plant construction; studies of costs completion; periods and risks. Nuclear plant costs have recently risen so rapidly that vendors are not willing to publicly commit to cost estimates: ∼ $2000/Kw overnight costs in 2006 in the US market > $4000/Kw and in 2008 in the US market > $6000/Kw in 2008 in emerging markets. There is vendors pricing uncertainty. Current contract models may not apply. Current construction projects have problems: Olkiluoto-3 is reported to be 50% over budget and two years behind schedule, increasing perceptions that nuclear costs will continue to increase rapidly; Price of materials is a big volatile unknown, which may decrease Labor could become more available due to limited number of new projects; Lack of debt/credit to finance new project may decrease demand of new construction

  12. Economics of human performance and systems total ownership cost.

    Science.gov (United States)

    Onkham, Wilawan; Karwowski, Waldemar; Ahram, Tareq Z

    2012-01-01

    Financial costs of investing in people is associated with training, acquisition, recruiting, and resolving human errors have a significant impact on increased total ownership costs. These costs can also affect the exaggerate budgets and delayed schedules. The study of human performance economical assessment in the system acquisition process enhances the visibility of hidden cost drivers which support program management informed decisions. This paper presents the literature review of human total ownership cost (HTOC) and cost impacts on overall system performance. Economic value assessment models such as cost benefit analysis, risk-cost tradeoff analysis, expected value of utility function analysis (EV), growth readiness matrix, multi-attribute utility technique, and multi-regressions model were introduced to reflect the HTOC and human performance-technology tradeoffs in terms of the dollar value. The human total ownership regression model introduces to address the influencing human performance cost component measurement. Results from this study will increase understanding of relevant cost drivers in the system acquisition process over the long term.

  13. Cost estimation of the decommissioning of nuclear fuel cycle plants

    International Nuclear Information System (INIS)

    Barbe, A.; Pech, R.

    1991-01-01

    Most studies conducted to date on the cost of decommissioning nuclear facilities pertain to reactors. Few such studies have been performed on the cost of decommissioning nuclear fuel cycle plants, particularly spent fuel reprocessing plants. Present operators of these plants nevertheless need to assess such costs, at least in order to include the related expenses in their short-, medium- or long-term projections. They also need to determine now, for example, suitable production costs that the plant owners will have to propose to their customers. Unlike nuclear reactors for which a series effect is involved (PWRs, BWRs, etc.) and where radioactivity is relatively concentrated, industrial-scale reprocessing plants are large, complex installations for which decommissioning is a long and costly operation that requires a special approach. Faced with this problem, Cogema, the owner and operator of the La Hague and Marcoule reprocessing plants in France, called on SGN to assess the total decommissioning costs for its plants. This assessment led SGN to development by SGN engineers of a novel methodology and a computerized calculation model described below. The resulting methodology and model are applicable to other complex nuclear facilities besides reprocessing plants, such as laboratories and nuclear auxiliaries of reactor cores. (author)

  14. evaluation of total annual costs of heat exchanger networks using

    African Journals Online (AJOL)

    user

    after solving the first problem using RPA based heat integration gave a minimum total annual cost (TAC) of $237, ... mathematical programming and non-RPA based Hint software. ... The concept of pinch analysis evolved over the years.

  15. A general approach to total repair cost limit replacement policies

    Directory of Open Access Journals (Sweden)

    F. Beichelt

    2014-01-01

    Full Text Available A common replacement policy for technical systems consists in replacing a system by a new one after its economic lifetime, i.e. at that moment when its long-run maintenance cost rate is minimal. However, the strict application of the economic lifetime does not take into account the individual deviations of maintenance cost rates of single systems from the average cost development. Hence, Beichet proposed the total repair cost limit replacement policy: the system is replaced by a new one as soon as its total repair cost reaches or exceeds a given level. He modelled the repair cost development by functions of the Wiener process with drift. Here the same policy is considered under the assumption that the one-dimensional probability distribution of the process describing the repair cost development is given. In the examples analysed, applying the total repair cost limit replacement policy instead of the economic life-time leads to cost savings of between 4% and 30%. Finally, it is illustrated how to include the reliability aspect into the policy.

  16. Biofuel supply chain considering depreciation cost of installed plants

    Science.gov (United States)

    Rabbani, Masoud; Ramezankhani, Farshad; Giahi, Ramin; Farshbaf-Geranmayeh, Amir

    2016-06-01

    Due to the depletion of the fossil fuels and major concerns about the security of energy in the future to produce fuels, the importance of utilizing the renewable energies is distinguished. Nowadays there has been a growing interest for biofuels. Thus, this paper reveals a general optimization model which enables the selection of preprocessing centers for the biomass, biofuel plants, and warehouses to store the biofuels. The objective of this model is to maximize the total benefits. Costs of the model consist of setup cost of preprocessing centers, plants and warehouses, transportation costs, production costs, emission cost and the depreciation cost. At first, the deprecation cost of the centers is calculated by means of three methods. The model chooses the best depreciation method in each period by switching between them. A numerical example is presented and solved by CPLEX solver in GAMS software and finally, sensitivity analyses are accomplished.

  17. GASIFICATION PLANT COST AND PERFORMANCE OPTIMIZATION

    Energy Technology Data Exchange (ETDEWEB)

    Samuel S. Tam

    2002-05-01

    The goal of this series of design and estimating efforts was to start from the as-built design and actual operating data from the DOE sponsored Wabash River Coal Gasification Repowering Project and to develop optimized designs for several coal and petroleum coke IGCC power and coproduction projects. First, the team developed a design for a grass-roots plant equivalent to the Wabash River Coal Gasification Repowering Project to provide a starting point and a detailed mid-year 2000 cost estimate based on the actual as-built plant design and subsequent modifications (Subtask 1.1). This unoptimized plant has a thermal efficiency of 38.3% (HHV) and a mid-year 2000 EPC cost of 1,681 $/kW. This design was enlarged and modified to become a Petroleum Coke IGCC Coproduction Plant (Subtask 1.2) that produces hydrogen, industrial grade steam, and fuel gas for an adjacent Gulf Coast petroleum refinery in addition to export power. A structured Value Improving Practices (VIP) approach was applied to reduce costs and improve performance. The base case (Subtask 1.3) Optimized Petroleum Coke IGCC Coproduction Plant increased the power output by 16% and reduced the plant cost by 23%. The study looked at several options for gasifier sparing to enhance availability. Subtask 1.9 produced a detailed report on this availability analyses study. The Subtask 1.3 Next Plant, which retains the preferred spare gasification train approach, only reduced the cost by about 21%, but it has the highest availability (94.6%) and produces power at 30 $/MW-hr (at a 12% ROI). Thus, such a coke-fueled IGCC coproduction plant could fill a near term niche market. In all cases, the emissions performance of these plants is superior to the Wabash River project. Subtasks 1.5A and B developed designs for single-train coal and coke-fueled power plants. This side-by-side comparison of these plants, which contain the Subtask 1.3 VIP enhancements, showed their similarity both in design and cost (1,318 $/kW for the

  18. Nuclear plant cancellations: causes, costs, and consequences

    International Nuclear Information System (INIS)

    1983-04-01

    This study was commissioned in order to help quantify the effects of nuclear plant cancellations on the Nation's electricity prices. This report presents a historical overview of nuclear plant cancellations through 1982, the costs associated with those cancellations, and the reasons that the projects were terminated. A survey is presented of the precedents for regulatory treatment of the costs, the specific methods of cost recovery that were adopted, and the impacts of these decisions upon ratepayers, utility stockholders, and taxpayers. Finally, the report identifies a series of other nuclear plants that remain at risk of canellation in the future, principally as a result of similar demand, finance, or regulatory problems cited as causes of cancellation in the past. The costs associated with these potential cancellations are estimated, along with their regional distributions, and likely methods of cost recovery are suggested

  19. Parametric cost analysis of a HYLIFE-II power plant

    International Nuclear Information System (INIS)

    Bieri, R.L.

    1991-01-01

    The SAFIRE (Systems Analysis for ICF Reactor Economics) code was adapted to model a power plant using a HYLIFE-2 reactor chamber. The code was then used to examine the dependence of the plant capital costs and the busbar cost of electricity (COE) on a variety of design parameters (type of driver, chamber repetition rate, and net electric power). The results show the most attractive operating space for each set of driver/target assumptions and quantify the benefits of improvements in key design parameters. The base-case plant was a 1000-MW(e) plant containing a reactor vessel driven by an induction linac heavy-ion accelerator, run at 8 Hz with a driver energy of 6.73 MJ and a target yield of 350 MJ. The total direct cost for this plant was $2.6 billion. (All costs in this paper are given in equivalent 1988 dollars.) The COE was 8.5 cents/(kWh). The COE and total capital costs for a 1000-MW(e) base plant are nearly independent of the chosen combination of repetition rate and driver energy for a driver operating between 4 and 10 Hz. For comparison, the COE for a coal or future fission plant would be 4.5--5.5 cents/(kWh). The COE for a 1000-MW(e) plant could be reduced to 7.5 cents/(kWh) by using advanced targets and could be cut to 6.5 cents/(kWh) with conventional targets, if the driver cost could be cut in half. There is a large economy of scale with heavy-ion-driven inertial confinement fusion (ICF) plants. A 2000-MW(e) plant with a heavy-ion driver and a HYLIFE-2 chamber would have a COE of only 5.8 cents/(kWh)

  20. Capital investment costs of nuclear power plants

    International Nuclear Information System (INIS)

    Woite, G.

    1978-01-01

    The purpose of the article is to summarize capital cost experience and estimates in industrialized and developing Member States of the IAEA, and to provide some guidance for cost extrapolation. The relative merits of different types and sizes of nuclear and conventional power plants for an expanding electricity generation system are compared over an adequate planning period

  1. Capital cost: gas cooled fast reactor plant

    International Nuclear Information System (INIS)

    1977-09-01

    The results of an investment cost study for a 900 MW(e) GCFR central station power plant are presented. The capital cost estimate arrived at is based on 1976 prices and a conceptual design only, not a mature reactor design

  2. Allocating nuclear power plant costs over time

    International Nuclear Information System (INIS)

    Nellis, R.E.

    1983-01-01

    The nuclear generating plants coming into service in the 1980s have book values amounting to several billion dollars, doubling the rate bases of the owner utilities in some instances. The impact that this is producing on electric rates is of concern to consumers, regulators, and utilities alike. A review of the basic nature of a productive asset, the purpose of depreciation accounting, and the composition of interest rates leads to a method of constructing capital-recovery schedules which has come to be termed economic depreciation. This methodology departs from conventional methodology only in that it accepts inflation as a fact of life. This article indicates that application of the procedure to an actual nuclear reactor provides benefits for all classes of ratepayers in that initial capital-recovery costs to ratepayers are substantially lower and, in terms of dollars of constant purchasing power, the total amount paid by customers for return on investment is substantially the same. For the utility, whereas initial capital recovery is lower, total capital recovery is somewhat greater, and the utility is no worse off if it must raise some working capital in the capital markets. 6 references, 4 figures, 2 tables

  3. Production costs: U.S. gas turbine ampersand combined-cycle power plants

    International Nuclear Information System (INIS)

    Anon.

    1992-01-01

    This fourth edition of UDI's gas turbine O ampersand M cost report gives 1991 operation and maintenance expenses for over 450 US gas turbine power plants. Modeled on UDI's popular series of O ampersand M cost reports for US steam-electric plants, this report shows operator and plant name, plant year-in-service, installed capacity, 1991 net generation, total fuel expenses, total non-fuel O ampersand M expenses, total production costs, and current plant capitalization. Coverage includes over 90 percent of the utility-owned gas/combustion turbine and combined-cycle plants installed in the country

  4. [Total knee and hip prosthesis: variables associated with costs].

    Science.gov (United States)

    Herrera-Espiñeira, Carmen; Escobar, Antonio; Navarro-Espigares, José Luis; Castillo, Juan de Dios Lunadel; García-Pérez, Lidia; Godoy-Montijano, Amparo

    2013-01-01

    The elevated prevalence of osteoarthritis in Western countries, the high costs of hip and knee arthroplasty, and the wide variations in the clinical practice have generated considerable interest in comparing the associated costs before and after surgery. To determine the influence of a number of variables on the costs of total knee and hip arthroplasty surgery during the hospital stay and during the one-year post-discharge. A prospective multi-center study was performed in 15 hospitals from three Spanish regions. Relationships between the independent variables and the costs of hospital stay and postdischarge follow-up were analyzed by using multilevel models in which the "hospital" variable was used to group cases. Independent variables were: age, sex, body mass index, preoperative quality of life (SF-12, EQ-5 and Womac questionnaires), surgery (hip/knee), Charlson Index, general and local complications, number of beds and economic-institutional dependency of the hospital, the autonomous region to which it belongs, and the presence of a caregiver. The cost of hospital stay, excluding the cost of the prosthesis, was 4,734 Euros, and the post-discharge cost was 554 Euros. With regard to hospital stay costs, the variance among hospitals explained 44-46% of the total variance among the patients. With regard to the post-discharge costs, the variability among hospitals explained 7-9% of the variance among the patients. There is considerable potential for reducing the hospital stay costs of these patients, given that more than 44% of the observed variability was not determined by the clinical conditions of the patients but rather by the behavior of the hospitals.

  5. Wind farm balance of plant costs

    International Nuclear Information System (INIS)

    Craig, L.; Liebmann, C.

    1992-01-01

    The study consisted of a detailed investigation of the infrastructure required for the construction and operation of a windfarm in the UK. Costing of the equipment and installation was carried out for three UK sites, with different physical characteristics. A literature survey was carried out to determine current practice in the siting of turbines within windfarms in Europe and the USA. Wind turbines were then laid out on the sites selected for study. Requirements and costs for roads, foundations and site buildings, site electrical system and grid connection, the supervisory control and data acquisition system were discussed and evaluated. A comparison between the balance of plant costs for the 33-metre MS-3 400 kW wind turbine and the 50-metre LS-2 1 MW wind turbine was made for each area of study. Overall balance of plant costs was reviewed, with an investigation of the cost components which are most sensitive to variations. The balance of plant costs averaged over the three sites were 13.0 p/kWh/annum for the MS3 windfarms and 10.6 p/kWh/annum for the LS-2 windfarms. Maps of the sites under investigation, design drawings and tables of costs are included to give supporting information to the text. (author)

  6. Production costs: U.S. hydroelectric power plants, 4th Edition

    International Nuclear Information System (INIS)

    Anon.

    1993-01-01

    The book provides 1991 operation and maintenance expenses for over 800 conventional and pumped-storage hydroelectric power plants. Report shows operator and plant name, plant year-in-service, installed capacity, 1991 net generation, O ampersand M expenses, total production costs and current plant capitalization. Fifty eight percent of the utility-owned hydroelectric plants in the US are covered by this report. Data diskette provides additional capital and production cost accounts and number of employees for each plant

  7. evaluation of total annual costs of heat exchanger networks using

    African Journals Online (AJOL)

    This study presents pinch analysis of some heat exchanger networks (HENs) problems using Hint integration (HINT) software. Three examples reported to have been solved using different approaches by various researchers to obtain the least possible total annual cost (TAC) were solved using the Hint software. In this work ...

  8. Nuclear power plant decommissioning costs in perspective

    International Nuclear Information System (INIS)

    Rothwell, Geoffrey; Deffrennes, Marc; Weber, Inge

    2016-01-01

    At the international level, actual experience is limited in the completion of nuclear power plant decommissioning projects. Cost data for decommissioning projects are thus largely unavailable, with few examples of analyses or comparisons between estimates and actual costs at the project level. The Nuclear Energy Agency (NEA) initiated a project to address this knowledge gap and in early 2016 published the outcomes in the report on Costs of Decommissioning Nuclear Power Plants. The study reviews decommissioning costs and funding practices adopted by NEA member countries, based on the collection and analysis of survey data via a questionnaire. The work was carried out in co-operation with the International Atomic Energy Agency (IAEA) and the European Commission (EC). (authors)

  9. Probabilistic cost estimating of nuclear power plant construction projects

    International Nuclear Information System (INIS)

    Finch, W.C.; Perry, L.W.; Postula, F.D.

    1978-01-01

    This paper shows how to identify and isolate cost accounts by developing probability trees down to component levels as justified by value and cost uncertainty. Examples are given of the procedure for assessing uncertainty in all areas contributing to cost: design, factory equipment pricing, and field labor and materials. The method of combining these individual uncertainties is presented so that the cost risk can be developed for components, systems and the total plant construction project. Formats which enable management to use the probabilistic cost estimate information for business planning and risk control are illustrated. Topics considered include code estimate performance, cost allocation, uncertainty encoding, probabilistic cost distributions, and interpretation. Effective cost control of nuclear power plant construction projects requires insight into areas of greatest cost uncertainty and a knowledge of the factors which can cause costs to vary from the single value estimates. It is concluded that probabilistic cost estimating can provide the necessary assessment of uncertainties both as to the cause and the consequences

  10. Cost Savings for Manufacturing Lithium Batteries in a Flexible Plant

    Energy Technology Data Exchange (ETDEWEB)

    Nelson, Paul A.; Ahmed, Shabbir; Gallagher, Kevin G.; Dees, Dennis W.

    2015-06-01

    The flexible plant postulated in this study would produces types of batteries for electric-drive vehicles of the types hybrid (HEV), 10-mile range and 40-mile range plug-in hybrids (PHEV) and a 150-mile range battery-electric (EV). The annual production rate of the plant is 235,000 per year (30,000 EV batteries and 100,000 HEV batteries). The unit cost savings as calculated with the Argonne BatPaC model for this flex plant vs. dedicated plants range from 8% for the EV battery packs to 23% for the HEV packs including the battery management systems (BMS). The investment cost savings are even larger, ranging from 21% for EVs to 43% for HEVs. The costs of the 1.0-kWh HEV batteries are projected to approach $710 per unit and that of the EV batteries $228 per kWh with the most favorable cell chemistries and including the BMS. The best single indicator of the cost of producing lithium-manganate spinel/graphite batteries in a flex plant is the total cell area of the battery. For the four batteries studied, the price range is $20-24 per m2 of cell area including the cost of the BMS, averaging $21 per m2 for the entire flex plant.

  11. Allocating nuclear power plant costs: an extension

    International Nuclear Information System (INIS)

    Bierman, H. Jr.

    1984-01-01

    The author modifies and extends the argument presented in the September 22, 1983 issue by Richard E. Nellis for using economic depreciation to allocate nuclear power plant costs. The two goals of his model are to charge constant real costs to consumers and to provide a fair return of .125 to investors in each period. The addition of other objectives requires further modification of the model since the schedule of revenues that are deemed to be optimum defines the depreciation schedule. 1 table

  12. Evaluation of construction cost of pyro-partitioning plant

    International Nuclear Information System (INIS)

    Kinoshita, Kensuke; Kurata, Masateru; Inoue, Tadashi

    1999-01-01

    This study was conducted to evaluate the construction cost of a pyro-partitioning plant. The plant capacity was chosen to accommodate processing of the HLLW generated by PUREX reprocessing of 800 ton of spent LWR fuel. The block flow diagram and mass balance obtained from our previous experimental data were used to produce a detailed process-flow diagram and to design the plant. In this evaluation, the plant was estimated to cover an area of about 90 m x 70 m, and to cost $576 million for construction. This study shows that the cost of process equipments, such as reaction vessels, accountability tanks and so on, is just about 13% of total construction cost. On the other hand, the cost of process robots and the equipments for key measurement point (KMP) is major part in the cost of in-cell equipment. So it is clear that the construction cost can be reduced by reducing the number of material balance area (MBA) and KMP. (author)

  13. Cost-identification analysis of total laryngectomy: an itemized approach to hospital costs.

    Science.gov (United States)

    Dedhia, Raj C; Smith, Kenneth J; Weissfeld, Joel L; Saul, Melissa I; Lee, Steve C; Myers, Eugene N; Johnson, Jonas T

    2011-02-01

    To understand the contribution of intraoperative and postoperative hospital costs to total hospital costs, examine the costs associated with specific hospital services in the postoperative period, and recognize the impact of patient factors on hospital costs. Case series with chart review. Large tertiary care teaching hospital system. Using the Pittsburgh Head and Neck Organ-Specific Database, 119 patients were identified as having total laryngectomy with bilateral selective neck dissection and primary closure from 1999 to 2009. Cost data were obtained for 112 patients. Costs include fixed and variable costs, adjusted to 2010 US dollars using the Consumer Price Index. Mean total hospital costs were $29,563 (range, $10,915 to $120,345). Operating room costs averaged 24% of total hospital costs, whereas room charges, respiratory therapy, laboratory, pharmacy, and radiology accounted for 38%, 14%, 8%, 7%, and 3%, respectively. Median length of stay was 9 days (range, 6-43), and median Charlson comorbidity index score was 8 (2-16). Patients with ≥1 day in the intensive care unit had significantly higher hospital costs ($46,831 vs $24,601, P cost differences with stratification based on previous radiation therapy ($27,598 vs $29,915 with no prior radiation, P = .62) or hospital readmission within 30 days ($29,483 vs $29,609 without readmission, P = .97). This is one of few studies in surgery and the first in otolaryngology to analyze hospital costs for a relatively standardized procedure. Further work will include cost analysis from multiple centers with investigation of global cost drivers.

  14. Retail clinic utilization associated with lower total cost of care.

    Science.gov (United States)

    Sussman, Andrew; Dunham, Lisette; Snower, Kristen; Hu, Min; Matlin, Olga S; Shrank, William H; Choudhry, Niteesh K; Brennan, Troyen

    2013-04-01

    To better understand the impact of retail clinic use on a patient's annual total cost of care. A propensity score matched-pair, cohort design was used to analyze healthcare spending patterns among CVS Caremark employees in the year following a visit to a MinuteClinic, the retail clinics inside CVS pharmacies. De-identified medical and pharmacy claims for CVS Caremark employees and their dependents who received care at a retail clinic between June 1, 2009, and May 31, 2010, were matched to those of subjects who received care elsewhere. High-dimensional propensity score and greedy matching techniques were used to create a 1-to-1 matched cohort that was analyzed using generalized linear regression models. Individuals using a retail clinic had a lower total cost of care (-$262; 95% confidence interval, -$510 to -$31; P = .025) in the year following their clinic visit than individuals who received care in other settings. This savings was primarily due to lower medical expenses at physicians' offices ($77 savings, P = .008) and hospital inpatient care ($121 savings, P = .049). The 6022 retail clinic users also had 142 (12%) fewer emergency department visits (P = .01), though this was not related to significant cost savings. This study found that retail clinic use was associated with lower overall total cost of care compared with that at alternative sites. Savings may extend beyond the retail clinic visit itself to other types of medical utilization.

  15. Internal Logistics System Selection with Total Cost of Ownership Analysis

    Science.gov (United States)

    Araújo, Inês; Pimentel, Carina; Godina, Radu; Matias, João C. O.

    2017-06-01

    In this paper a methodology was followed in order to support the decision-making of one industrial unit regarding its internal logistics system. The addressed factory was facing issues with their internal logistics approach. Some alternatives were pointed out and a proper total cost of ownership (TCO) analysis was developed. This analysis was taken in order to demonstrate the more cost-effective solution for the internal logistics system. This tool is more and more valued by the companies, due to their willing to reduce the costs that are associated with the way of doing business. Despite the proposal of the best choice for the internal logistics system of the enterprise, this study also intends to present some conclusions about the match between the nature of the industrial unit and the logistics systems that best fit the requirements of those.

  16. Total cost of performing analog-to-digital upgrades

    International Nuclear Information System (INIS)

    Albrigo, T.

    1993-01-01

    The financial well-being of nuclear power plants in the United States is dependent on reducing costs. Rapid advances in industrial technology have created a conundrum for utility executives and their engineering staffs. Digital technology is being touted as beneficial in many ways; however, a number of significant issues have been raised regarding the adequacy and financial viability of digital systems in nuclear power plants. Actual or perceived problems with digital system design, development, and installation have caused significant financial losses for nuclear utilities. This paper provides a list of problems that must be considered in performing an analog-to-digital conversion or for doing a large digital upgrade. It is desirable that the full financial risks associated with these types of upgrades are considered. Specific problems encountered at Palo Verde nuclear generating station are reviewed to emphasize some of the problem areas

  17. En differentieret tilgang til total cost of ownership (TCO)

    DEFF Research Database (Denmark)

    Zachariassen, Frederik

    2010-01-01

    Økonomistyring er en nødvendig brik i forsøget på at kunne styre dele af eller hele forsyningskæden, og til dette bruges diverse økonomistyringsværktøjer. Denne artikel omhandler økonomistyringsværktøjet 'total cost of ownership', og hvordan dette kan bruges til at forbedre samarbejdet med...

  18. Cost of transporting irradiated fuels and maintenance costs of a chemical treatment plant for irradiated fuels

    International Nuclear Information System (INIS)

    Sousselier, Y.

    1964-01-01

    Numerous studies have been made of the cost of a fuel cycle, but many of them are based on a priori studies and are therefore to be treated with reserve. Thus, in the part dealing with the treatment of irradiated fuels, some important factors in the cost have only rarely been given on the basis of practical experience: the cost of transporting the fuels themselves and the plant maintenance costs. Investigations relating to transport costs are generally based on calculations made from somewhat arbitrary data. The studies carried out in France on the transport of irradiated uranium between the EDF reactors at Chinon and the retreatment plant at La Hague of the irradiated uranium from research reactors to foreign retreatment plants, are reported; they show that by a suitable choice of transport containers and details of expedition it has been possible to reduce the costs very considerably. This has been achieved either by combining rail and road transport or by increasing the writ capacities of the transport containers: an example is given of a container for swimming-pool pile elements which can transport a complete pile core at one time, thus substantially reducing the cost. Studies concerning the maintenance costs of retreatment plants are rarer still, although in direct maintenance plants these figures represent an appreciable fraction of the total treatment cost. An attempt has been made, on the basis of operational experience of a plant, to obtain some idea of these costs. Only maintenance proper has been considered, excluding subsidiary operations such as the final decontamination of apparatus, the burial of contaminated material and radioprotection operations Maintenance has been divided into three sections: mechanical maintenance, maintenance of electrical equipment and maintenance of control and adjustment apparatus. In each of these sections the distinction has been made between manpower and the material side. In order to allow comparisons to be made with

  19. Analysis of nuclear power plant construction costs

    International Nuclear Information System (INIS)

    1986-01-01

    The objective of this report is to present the results of a statistical analysis of nuclear power plant construction costs and lead-times (where lead-time is defined as the duration of the construction period), using a sample of units that entered construction during the 1966-1977 period. For more than a decade, analysts have been attempting to understand the reasons for the divergence between predicted and actual construction costs and lead-times. More importantly, it is rapidly being recognized that the future of the nuclear power industry rests precariously on an improvement in the cost and lead-time situation. Thus, it is important to study the historical information on completed plants, not only to understand what has occurred to also to improve the ability to evaluate the economics of future plants. This requires an examination of the factors that have affected both the realized costs and lead-times and the expectations about these factors that have been formed during the construction process. 5 figs., 22 tabs

  20. Analysis of nuclear power plant construction costs

    Energy Technology Data Exchange (ETDEWEB)

    1986-01-01

    The objective of this report is to present the results of a statistical analysis of nuclear power plant construction costs and lead-times (where lead-time is defined as the duration of the construction period), using a sample of units that entered construction during the 1966-1977 period. For more than a decade, analysts have been attempting to understand the reasons for the divergence between predicted and actual construction costs and lead-times. More importantly, it is rapidly being recognized that the future of the nuclear power industry rests precariously on an improvement in the cost and lead-time situation. Thus, it is important to study the historical information on completed plants, not only to understand what has occurred to also to improve the ability to evaluate the economics of future plants. This requires an examination of the factors that have affected both the realized costs and lead-times and the expectations about these factors that have been formed during the construction process. 5 figs., 22 tabs.

  1. Managing the total cost of risk exposures through risk mapping techniques

    International Nuclear Information System (INIS)

    Unione, A.J.; Rode, D.M.

    1998-01-01

    In a competitive power market, power producers are exposed to an increasingly broad spectrum of financial risks. The cumulative impact of these financial risks is known collectively as the Total of Cost of Risk. The concept of Total of Cost of Risk presents the business reality of a company's exposure to potentially devastating financial consequences in an integrated and useful way. In this way, a strategy of managing Total Cost of Risk in the most cost effective way can become a means of ensuring long term business health and security. This paper will examine the use of risk mapping as a tool for visually understanding Total Cost of Risk, thus creating an enhanced situational awareness and an integrated basis for risk management decision. The evaluation process, available through the use of risk maps allows the power producers to pro-actively implement prudent business decisions concerning the design, operation and maintenance of power plants. Risk mapping is thus a means for harmonizing operational objectives, such as improved plant reliability, with corporate strategies and goals in terms of an effective risk management program

  2. Analysis of the total system life cycle cost for the Civilian Radioactive Waste Management Program

    International Nuclear Information System (INIS)

    1989-05-01

    The total-system life-cycle cost (TSLCC) analysis for the Department of Energy's (DOE) Civilian Radioactive Waste Management Program is an ongoing activity that helps determine whether the revenue-producing mechanism established by the Nuclear Waste Policy Act of 1982 -- a fee levied on electricity generated in commercial nuclear power plants -- is sufficient to cover the cost of the program. This report provides cost estimates for the sixth annual evaluation of the adequacy of the fee and is consistent with the program strategy and plans contained in the DOE's Draft 1988 Mission Plan Amendment. The total-system cost for the system with a repository at Yucca Mountain, Nevada, a facility for monitored retrievable storage (MRS), and a transportation system is estimated at $24 billion (expressed in constant 1988 dollars). In the event that a second repository is required and is authorized by the Congress, the total-system cost is estimated at $31 to $33 billion, depending on the quantity of spent fuel to be disposed of. The $7 billion cost savings for the single-repository system in comparison with the two-repository system is due to the elimination of $3 billion for second-repository development and $7 billion for the second-repository facility. These savings are offset by $2 billion in additional costs at the first repository and $1 billion in combined higher costs for the MRS facility and transportation. 55 refs., 2 figs., 24 tabs

  3. Optimizing power plant cycling operations while reducing generating plant damage and costs

    Energy Technology Data Exchange (ETDEWEB)

    Lefton, S.A.; Besuner, P.H.; Grimsrud, P. [Aptech Engineering Services, Inc., Sunnyvale, CA (United States); Bissel, A. [Electric Supply Board, Dublin (Ireland)

    1998-12-31

    This presentation describes a method for analyzing, quantifying, and minimizing the total cost of fossil, combined cycle, and pumped hydro power plant cycling operation. The method has been developed, refined, and applied during engineering studies at some 160 units in the United States and 8 units at the Irish Electric Supply Board (ESB) generating system. The basic premise of these studies was that utilities are underestimating the cost of cycling operation. The studies showed that the cost of cycling conventional boiler/turbine fossil power plants can range from between $2,500 and $500,000 per start-stop cycle. It was found that utilities typically estimate these costs by factors of 3 to 30 below actual costs and, thus, often significantly underestimate their true cycling costs. Knowledge of the actual, or total, cost of cycling will reduce power production costs by enabling utilities to more accurately dispatch their units to manage unit life expectancies, maintenance strategies and reliability. Utility management responses to these costs are presented and utility cost savings have been demonstrated. (orig.) 7 refs.

  4. Optimizing power plant cycling operations while reducing generating plant damage and costs

    Energy Technology Data Exchange (ETDEWEB)

    Lefton, S A; Besuner, P H; Grimsrud, P [Aptech Engineering Services, Inc., Sunnyvale, CA (United States); Bissel, A [Electric Supply Board, Dublin (Ireland)

    1999-12-31

    This presentation describes a method for analyzing, quantifying, and minimizing the total cost of fossil, combined cycle, and pumped hydro power plant cycling operation. The method has been developed, refined, and applied during engineering studies at some 160 units in the United States and 8 units at the Irish Electric Supply Board (ESB) generating system. The basic premise of these studies was that utilities are underestimating the cost of cycling operation. The studies showed that the cost of cycling conventional boiler/turbine fossil power plants can range from between $2,500 and $500,000 per start-stop cycle. It was found that utilities typically estimate these costs by factors of 3 to 30 below actual costs and, thus, often significantly underestimate their true cycling costs. Knowledge of the actual, or total, cost of cycling will reduce power production costs by enabling utilities to more accurately dispatch their units to manage unit life expectancies, maintenance strategies and reliability. Utility management responses to these costs are presented and utility cost savings have been demonstrated. (orig.) 7 refs.

  5. Primary vs Conversion Total Hip Arthroplasty: A Cost Analysis

    Science.gov (United States)

    Chin, Garwin; Wright, David J.; Snir, Nimrod; Schwarzkopf, Ran

    2018-01-01

    Introduction Increasing hip fracture incidence in the United States is leading to higher occurrences of conversion total hip arthroplasty (THA) for failed surgical treatment of the hip. In spite of studies showing higher complication rates in conversion THA, the Centers for Medicare and Medicaid services currently bundles conversion and primary THA under the same diagnosis-related group. We examined the cost of treatment of conversion THA compared with primary THA. Our hypothesis is that conversion THA will have higher cost and resource use than primary THA. Methods Fifty-one consecutive conversion THA patients (Current Procedure Terminology code 27132) and 105 matched primary THA patients (Current Procedure Terminology code 27130) were included in this study. The natural log-transformed costs for conversion and primary THA were compared using regression analysis. Age, gender, body mass index, American Society of Anesthesiologist, Charlson comorbidity score, and smoker status were controlled in the analysis. Conversion THA subgroups formed based on etiology were compared using analysis of variance analysis. Results Conversion and primary THAs were determined to be significantly different (P conversion THA has significantly greater cost and resource use than primary THA. In order to prevent disincentives for treating these complex surgical patients, reclassification of conversion THA is needed, as they do not fit together with primary THA. PMID:26387923

  6. Estimation of small-scale hydroelectric power plant costs

    International Nuclear Information System (INIS)

    Santos, Afonso Henriques Moreira; Silva, Benedito Claudio da; Magalhaes, Ricardo Nogueira

    2010-01-01

    Changes in Brazilian energy scenario through last years such as increase of demand and search for clean and economically feasible renewable energy sources, has stimulated investors to small hydro power plants (SHP) sector. Such characteristics together with several economic incentives, legal and regulatory mechanisms also, have helped and stimulated building of new plants of this kind and have attracted a great number of investors to this sector. Study of costs analysis and feasibility of investments is a study which has been used since long time in SHP business market as several preliminary studies previous to civil project have significant costs which lead us to count with a feasibility analysis from the very beginning of studies, exactly what is suggested in the present methodology. Such feasibility analysis, in the common patterns where basic unit costs of each input remain outstanding, would be very complex due to great difficulty in obtaining information at initial phase of project. In this direction this study brings a contribution for investors as well as for designers of small hydro power plants since it outlines a link between physical and energetic characteristics of small hydro power plant in its total cost. Such link is based in available physical characteristics in initial phase of the project, making possible a previous comparison between arrangements of a central or even the comparison of return of investment between different plants. The resulting benefit being the possibility of choosing centrals with greater economic feasibility disregarding bad undertakings or arrangements with more expressive cost. Final result gives a better delay in return of investment, helps in power, arrangements more optimized and in saving time as well, reducing costs of undertakings. Due to large number of SHP arrangements, we chose for this study the most common in Brazil, plant of medium and large fall, shunting line balance chimney and low pressure conduit. (author)

  7. High cost of nuclear power plants

    International Nuclear Information System (INIS)

    Bassett, C.

    1978-01-01

    Retroactive safety standards were found to account for over half the costs of a nuclear power plant and point up the need for an effective cost-benefit analysis of changes made by the Nuclear Regulatory Commission after construction has started. The author compared the Davis-Besse Unit No. 1 construction-cost estimates with the final-cost increases during a rate-case investigation in Ohio. He presents data furnished for ten of the largest construction contracts to illustrate the cost increases involving fixed hardware and intensive labor. The situation was found to repeat with other utilities across the country even though safeguards against irresponsible low bidding were introduced. Low bidding was found to continue, encouraged by the need for retrofitting to meet regulation changes. The average cost per kilowatt of major light-water reactors is shown to have increased from $171 in 1970 to $555 in 1977, while construction duration increased from 43.4 to 95.6 months during the same period

  8. PPICA, Power Plant Investment Cost Analysis

    International Nuclear Information System (INIS)

    Lefevre, J.C.

    2002-01-01

    1 - Description of program or function: This software package contains two modules: - CAPITAL1 calculates investment costs from overnight costs, based on the capital structure of the utility (debt/equity ratio), return and interest rates according to the type of securities involved, and a standard-shaped curve of capital outlays during construction of a power plant. - FCRATE1 calculates the year-by-year revenue requirements to cover the capital-related charges incurred by the new investment and their economic equivalent: the levelled fixed-charge rate and capital contribution to the levelled unit power generation cost per kWh. They are proposed as an alternative to the corresponding modules CAPITAL and FCRATE, included in the LPGC (Levelled Power Generation Cost) suite of codes developed by ORNL and US-DOE. They perform the same type of analysis and provide the same results. 2 - Methods: Results output from CAPITAL1, in terms of the initial investment at startup and the fraction thereof that is allowable for tax depreciation, can be transferred automatically as data input to FCRATE1. Other user-defined data are: the project life, the time horizon of the economic analysis (which does not necessarily coincide with the project life), the plant load factor (lifetime average), the tax rate applicable to utility's income, the tax depreciation scheme and the tax charge accounting method (normalised or flow- through). The results of CAPITAL1 and FCRATE1 are expressed both in current money and in constant money of a reference year. Inflation rate and escalation rate of construction expenditures during construction period, and of fixed charges during service life are defined by the user. The discount rate is set automatically by the programme, equal to the weighted average tax-adjusted cost of money. 3 - Restrictions on the complexity of the problem: CAPITAL1 and FCRATE1 are 'alternatives', not 'substitutes', to the corresponding programs CAPITAL and FCRATE of the LPGC

  9. Total cost estimates for large-scale wind scenarios in UK

    International Nuclear Information System (INIS)

    Dale, Lewis; Milborrow, David; Slark, Richard; Strbac, Goran

    2004-01-01

    The recent UK Energy White Paper suggested that the Government should aim to secure 20% of electricity from renewable sources by 2020. A number of estimates of the extra cost of such a commitment have been made, but these have not necessarily included all the relevant cost components. This analysis sets out to identify these and to calculate the extra cost to the electricity consumer, assuming all the renewable electricity is sourced from wind energy. This enables one of the more controversial issues--the implications of wind intermittency--to be addressed. The basis of the assumptions associated with generating costs, extra balancing costs and distribution and transmission system reinforcement costs are all clearly identified and the total costs of a '20% wind' scenario are compared with a scenario where a similar amount of energy is generated by gas-fired plant. This enables the extra costs of the renewables scenario to be determined. The central estimate of the extra costs to electricity consumers is just over 0.3 p/kW h in current prices (around 5% extra on average domestic unit prices). Sensitivity analyses examine the implications of differing assumptions. The extra cost would rise if the capital costs of wind generation fall slower than anticipated, but would fall if gas prices rise more rapidly than has been assumed, or if wind plant are more productive. Even if it is assumed that wind has no capacity displacement value, the added cost to the electricity consumer rises by less than 0.1 p/kW h. It is concluded that there does not appear to be any technical reason why a substantial proportion of the country's electricity requirements could not be delivered by wind

  10. Technology and costs for dismantling a Swedish nuclear power plant

    International Nuclear Information System (INIS)

    1979-10-01

    Various estimates concerning the costs of decommissioning a redundant nuclear power reactor to the green fields state are given in the literature. The purpose of this study is to provide background material for the Swedish nuclear power utilities to estimate the costs and time required to dismantle an ASEA-ATOM Boiling Water Reactor. The units Oskarshamn II and Barsebeck 1, both with an installed capacity of approximately 600 MW, serve as reference plants. The time of operation before final shutdown is assumed to be 40 years. Dismantling operations are initiated one year after shutdown. When the dismantling of the plant is finished, the site is to be released for unrestricted use. The costs for dismantling and subsequent final disposal of the radioactive waste are estimated at approximately SEK 500 million (approximately US dollars 120 million) in terms of 1979 prices. The sum includes 25% contingency. The dismantling cost is equivalent to 10-15% of the installation cost of an equivalent new nuclear power plant. The exact percentage is dependent on the interest rate during the construction period. It is shown in the study that a total dismantling can be accomplished in less than five years. This report is a compilation of studies performed by ASEA-ATOM and VBB based on premises given by KBS. The reports from these studies are presented in appendices. (Auth.)

  11. Total medical costs of treating femoral neck fracture patients with hemi- or total hip arthroplasty: a cost analysis of a multicenter prospective study

    NARCIS (Netherlands)

    P.T.P.W. Burgers (Paul); M. Hoogendoorn (Martine); E.A.C. Van Woensel; R.W. Poolman (Rudolf); M. Bhandari (Mohit); P. Patka (Peter); E.M.M. van Lieshout (Esther)

    2016-01-01

    textabstractSummary: The aim of this study was to determine the total medical costs for treating displaced femoral neck fractures with hemi- or total hip arthroplasty in fit elderly patients. The mean total costs per patient at 2 years of follow-up were €26,399. These results contribute to cost

  12. Capital cost: pressurized water reactor plant. Commerical electric power cost studies

    International Nuclear Information System (INIS)

    1977-06-01

    The investment cost study for the 1139-MW(e) pressurized water reactor (PWR) central station power plant consists of two volumes. This volume includes in addition to the foreword and summary, the plant description and the detailed cost estimate

  13. The influence of size of plant upon reprocessing costs

    International Nuclear Information System (INIS)

    1978-10-01

    This paper reviews recent published estimates for capital and operating costs of reprocessing plants in an attempt to establish a relative variation of unit reprocessing costs with plant design capacity and load factor. It is concluded that capital costs follow the well established ''rule of thumb'' for chemical plants in being proportional to (design capacity)sup(2/3). Operating costs vary significantly with variation in labour costs. Unit reprocessing costs are presented as a function of plant design capacity, load factor and method of financing

  14. Cost analysis of small hydroelectric power plants components and preliminary estimation of global cost

    International Nuclear Information System (INIS)

    Basta, C.; Olive, W.J.; Antunes, J.S.

    1990-01-01

    An analysis of cost for each components of Small Hydroelectric Power Plant, taking into account the real costs of these projects is shown. It also presents a global equation which allows a preliminary estimation of cost for each construction. (author)

  15. Gasification Plant Cost and Performance Optimization

    Energy Technology Data Exchange (ETDEWEB)

    Samuel Tam; Alan Nizamoff; Sheldon Kramer; Scott Olson; Francis Lau; Mike Roberts; David Stopek; Robert Zabransky; Jeffrey Hoffmann; Erik Shuster; Nelson Zhan

    2005-05-01

    As part of an ongoing effort of the U.S. Department of Energy (DOE) to investigate the feasibility of gasification on a broader level, Nexant, Inc. was contracted to perform a comprehensive study to provide a set of gasification alternatives for consideration by the DOE. Nexant completed the first two tasks (Tasks 1 and 2) of the ''Gasification Plant Cost and Performance Optimization Study'' for the DOE's National Energy Technology Laboratory (NETL) in 2003. These tasks evaluated the use of the E-GAS{trademark} gasification technology (now owned by ConocoPhillips) for the production of power either alone or with polygeneration of industrial grade steam, fuel gas, hydrocarbon liquids, or hydrogen. NETL expanded this effort in Task 3 to evaluate Gas Technology Institute's (GTI) fluidized bed U-GAS{reg_sign} gasifier. The Task 3 study had three main objectives. The first was to examine the application of the gasifier at an industrial application in upstate New York using a Southeastern Ohio coal. The second was to investigate the GTI gasifier in a stand-alone lignite-fueled IGCC power plant application, sited in North Dakota. The final goal was to train NETL personnel in the methods of process design and systems analysis. These objectives were divided into five subtasks. Subtasks 3.2 through 3.4 covered the technical analyses for the different design cases. Subtask 3.1 covered management activities, and Subtask 3.5 covered reporting. Conceptual designs were developed for several coal gasification facilities based on the fluidized bed U-GAS{reg_sign} gasifier. Subtask 3.2 developed two base case designs for industrial combined heat and power facilities using Southeastern Ohio coal that will be located at an upstate New York location. One base case design used an air-blown gasifier, and the other used an oxygen-blown gasifier in order to evaluate their relative economics. Subtask 3.3 developed an advanced design for an air

  16. Degradation of Total Petroleum Hydrocarbon in Phytoremediation Using Terrestrial Plants

    Directory of Open Access Journals (Sweden)

    Mushrifah Idris

    2014-06-01

    Full Text Available This study focused on the total petroleum hydrocarbon (TPH degradation in phytoremediation of spiked diesel in sand. The diesel was added to the sand that was planted with terrestrial plants. Four selected terrestrial plants used were Paspalum vaginatum Sw, Paspalums crobiculatum L. varbispicatum Hack, Eragrotis atrovirens (Desf. Trin. ex Steud and Cayratia trifolia (L. Domin since all the plants could survive at a hydrocarbon petroleum contaminated site in Malaysia. The samplings were carried out on Day 0, 7, 14, 28, 42 and 72. The analysis of the TPH was conducted by extracting the spiked sand using ultrasonic extraction. The determination of the TPH concentration in the sand was performed using GC-FID. The degradation of TPH depends on the plant species and time of exposure. The highest percentage degradation by P. vaginatum, P. scrobiculatum, E. atrovirens and C. trifolia were 91.9, 74.0, 68.9 and 62.9%, respectively. In conclusion, the ability to degrade TPH by plants were P. vaginatum > P. scrobiculatum > E. atrovirens> C. trifolia.

  17. Total costs and benefits of biomass in selected regions of the European Union - BioCosts

    Energy Technology Data Exchange (ETDEWEB)

    Almeida, A de; Costa, F B [Coimbra Univ. (Portugal). Inst. de Sistemas e Robotica; Bauen, A [London Univ. (United Kingdom). Div. of Life Sciences; and others

    1998-11-01

    In the BioCosts project, representative biomass-to-electricity and biomass-to-transport-service fuel cycles located at different sites within the European Union have been evaluated concerning their environmental and economic performance. Each case study was compared to a fossil-fuel fired reference case. The case studies examined comprise: utilisation of forestry residues in the Naessjoe circulating fluidized bed combustion plant, Sweden, versus the use of Polish coal in the same plant; utilisation of forestry residues and short-rotation coppice for industrial combined heat and power production in Mangualde, Portugal, versus the use of fuel oil in an engine generating heat and power; production of biogas from manure slurry for municipal combined heat and power generation at Hashoej, Denmark, versus the use of Danish natural gas in the same engine; gasification of woody biomass for combined heat and power generation in Vaernamo, Sweden, and Eggborough, UK, versus the use of coal in the Naessjoe plant mentioned above and a UK power plant; production of cold-pressed rape-seed oil and its use in a cogeneration plant at Weissenburg, Germany, versus the use of diesel fuel in a similar engine; production of rape-seed oil methyl ester and its use for goods transport in Germany, versus the use of diesel fuel in the same fleet of trucks; production of ethyl tertiary butyl ether from sugar beets and sweet sorghum for transport applications in France, versus the use of methyl tertiary butyl ether from fossil sources for the same purpose 130 refs, 25 figs, 42 tabs. Research funded in part by the European Commission in the JOULE III programme

  18. Impact of environmental cost on economics of thermal power plant. Paper no. IGEC-1-007

    International Nuclear Information System (INIS)

    Chandra, H.; Kaushik, S.C.; Chandra, A.

    2005-01-01

    Cost analysis per unit of power generation have been performed for coal based thermal power plant situated in Dadri (UP) for Indian and imported coal from Australia and America. In our study it has been found that it is better to use imported coal in Indian thermal power plants with advantages like low environmental, investment and total cost per unit of power generation. The effect of percent excess air and plant load factor on total cost per unit of power generation is also analyzed. (author)

  19. Reverse-total shoulder arthroplasty cost-effectiveness: A quality-adjusted life years comparison with total hip arthroplasty.

    Science.gov (United States)

    Bachman, Daniel; Nyland, John; Krupp, Ryan

    2016-02-18

    To compare reverse-total shoulder arthroplasty (RSA) cost-effectiveness with total hip arthroplasty cost-effectiveness. This study used a stochastic model and decision-making algorithm to compare the cost-effectiveness of RSA and total hip arthroplasty. Fifteen patients underwent pre-operative, and 3, 6, and 12 mo post-operative clinical examinations and Short Form-36 Health Survey completion. Short form-36 Health Survey subscale scores were converted to EuroQual Group Five Dimension Health Outcome scores and compared with historical data from age-matched patients who had undergone total hip arthroplasty. Quality-adjusted life year (QALY) improvements based on life expectancies were calculated. The cost/QALY was $3900 for total hip arthroplasty and $11100 for RSA. After adjusting the model to only include shoulder-specific physical function subscale items, the RSA QALY improved to 2.8 years, and its cost/QALY decreased to $8100. Based on industry accepted standards, cost/QALY estimates supported both RSA and total hip arthroplasty cost-effectiveness. Although total hip arthroplasty remains the quality of life improvement "gold standard" among arthroplasty procedures, cost/QALY estimates identified in this study support the growing use of RSA to improve patient quality of life.

  20. Power plant project success through total productive generation

    Energy Technology Data Exchange (ETDEWEB)

    Kaivola, R.; Tamminen, L.

    1996-11-01

    The Total Productive Generation concept (TPG) defines the lines of action adopted by IVO Generation Services Ltd (IGS) for the operation and maintenance of power plants. The TPG concept is based on procedures tested in practice. The main idea of TPG is continuous development of quality, which is a joint effort of the entire staff. Its objective is to benefit IGS`s own staff and, in particular, the company`s customers. (orig.)

  1. Theoretical and methodological aspects of assessing economic effectiveness of nuclear power plant construction using cost-benefit analysis

    International Nuclear Information System (INIS)

    Moravcik, A.

    1984-01-01

    The cost benefit of investments is devided into social and economic benefits. The postulates are discussed for the assessment of the cost benefit of capital costs of nuclear power plants. The relations are given for total cost benefit of capital costs expressed by the total profit rate of capital costs, and the absolute effectiveness exoressed by the socio-economic benefit of capital costs. The absolute cost benefit of capital costs is characterized by several complex indexes. Comparable capital cost benefit is used for assessing the effectiveness of interchangeable variants of solution. The minimum calculated costs serve as the criterion for selecting the optimal variant. (E.S.)

  2. Nuclear power plant cost underestimation: mechanisms and corrections

    International Nuclear Information System (INIS)

    Meyer, M.B.

    1984-01-01

    Criticisms of inaccurate nuclear power plant cost estimates have commonly focused upon what factors have caused actual costs to increase and not upon the engineering cost estimate methodology itself. This article describes two major sources of cost underestimation and suggests corrections for each which can be applied while retaining the traditional engineering methodology in general

  3. Current production costs in various power plant systems

    Energy Technology Data Exchange (ETDEWEB)

    Weible, H.

    1977-01-01

    The costs of producing electric power were evaluated for flowing water power plants, storage and pumped storage power plants, bituminous coal power plants, heating oil power plants (fired with heavy heating oil), natural gas-fired power plants, gas turbines, pressurized water reactors, and boiling water reactors. The calculational methods used for evaluating costs and the input data for methods used for the KOSKON and KOSKERN computer programs are described. It is emphasized that the calculations are examples to indicate the possible effects of the cost program and are only as valid as the input data. (JSR)

  4. CONCEPT-5 user's manual. [Power plant costs

    Energy Technology Data Exchange (ETDEWEB)

    Hudson, C.R. II

    1979-01-01

    The CONCEPT computer code package was developed to provide conceptual capital cost estimates for nuclear-fueled and fossil-fired power plants. Cost estimates can be made as a function of plant type, size, location, and date of initial operation. The output includes a detailed breakdown of the estimate into direct and indirect costs similar to the accounting system described in document NUS--531. Cost models are currently provided in CONCEPT 5 for single- and multiunit pressurized-water reactors, boiling-water reactors, and cost-fired plants with and without flue gas desulfurization equipment.

  5. Capital and operating costs of irradiated natural uranium reprocessing plants

    International Nuclear Information System (INIS)

    Thiriet, L.; Jouannaud, C.; Couture, J.; Duboz, J.

    1966-01-01

    This paper presents first a method of analysing natural uranium reprocessing plants investment costs (method similar to LANG and BACH well known in the fuel oil industry) and their operating costs (analysed according to their economic type). This method helps establishing standard cost structures for these plants, allowing thus comparisons between existing or planned industrial facilities. It also helps evaluating the foreseeable consequences of technical progress. Some results obtained are given, concerning: the investment costs sensitivity to the various technical parameters defining the fuel and their comparison according to the country or the economic area taken into account. Finally, the influence of the plants size on their investment costs is shown. (author) [fr

  6. Cost and quality of fuels for electric utility plants 1991

    International Nuclear Information System (INIS)

    1992-01-01

    Data for 1991 and 1990 receipts and costs for fossil fuels discussed in the Executive Summary are displayed in Tables ES1 through ES7. These data are for electric generating plants with a total steam-electric and combined-cycle nameplate capacity of 50 or more megawatts. Data presented in the Executive Summary on generation, consumption, and stocks of fossil fuels at electric utilities are based on data collected on the Energy Information Administration, Form EIA-759, ''Monthly Power Plant Report.'' These data cover all electric generating plants. The average delivered cost of coal, petroleum, and gas each decreased in 1991 from 1990 levels. Overall, the average annual cost of fossil fuels delivered to electric utilities in 1991 was $1.60 per million Btu, a decrease of $0.09 per million Btu from 1990. This was the lowest average annual cost since 1978 and was the result of the abundant supply of coal, petroleum, and gas available to electric utilities. US net generation of electricity by all electric utilities in 1991 increased by less than I percent--the smallest increase since the decline that occurred in 1982.3 Coal and gas-fired steam net generation, each, decreased by less than I percent and petroleum-fired steam net generation by nearly 5 percent. Nuclear-powered net generation, however, increased by 6 percent. Fossil fuels accounted for 68 percent of all generation; nuclear, 22 percent; and hydroelectric, 10 percent. Sales of electricity to ultimate consumers in 1991 were 2 percent higher than during 1990

  7. Total phenolics and antioxidant activity of five medicinal plant

    International Nuclear Information System (INIS)

    Sousa, Cleyton Marcos de M.; Silva, Hilris Rocha e; Vieira-Junior, Gerardo Magela; Ayres, Mariane Cruz C.; Costa, Charllyton Luis S. da; Araajo, Delton Servulo; Cavalcante, Luis Carlos D.; Barros, Elcio Daniel S.; Araujo, Paulo Breitner de M.; Brandao, Marcela S.; Chaves, Mariana H.

    2007-01-01

    This paper describes total phenolics content and antioxidant activity in the ethanolic extract of leaves, bark and roots of five medicinal plants: Terminalia brasiliensis Camb., Terminalia fagifolia Mart. and Zucc., Copernicia cerifera (Miller) H.E. Moore, Cenostigma macrophyllum Tul. var. acuminata Teles Freire and Qualea grandiflora Mart. The total phenolics content of the plant extracts, determined by the Folin-Ciocalteu method, varied from 250.0 ±8,2 to 763,63 ±13.03 mg of gallic acid equivalent/g dry EtOH extract. The antioxidant activity of extracts was evaluated using the 2,2-diphenyl-1-picrylhydrazyl (DPPH) assay system. Extract of bark from T. brasiliensis, the most active, with an EC 50 value of 27.59 ± 0.82 μg/mL, was comparable to rutin (EC 50 = 27.80 ± 1.38) and gallic acid (EC 50 = 24.27 ± 0.31), used as positive controls. The relationship between total phenolic content and antioxidant activity was positive and significant for T. brasiliensis, C. macrophyllum and C. cerifera. (author)

  8. Effect of water treatment on the comparative costs of evaporative and dry cooled power plants

    International Nuclear Information System (INIS)

    Gold, H.; Goldstein, D.J.; Yung, D.

    1976-07-01

    The report presents the results of a study on the relative cost of energy from a nominal 1000 Mwe nuclear steam electric generating plant using either dry or evaporative cooling at four sites in the United States: Rochester, New York; Sheridan, Wyoming; Gallup, New Mexico and Dallas, Texas. Previous studies have shown that because of lower efficiencies the total annual evaluated costs for dry cooling systems exceeds the total annual evaluated costs of evaporative cooling systems, not including the cost of water. The cost of water comprises the cost of supplying the makeup water, the cost of treatment of the makeup and/or the circulating water in the tower, and the cost of treatment and disposal of the blowdown in an environmentally acceptable manner. The purpose of the study is to show the effect of water costs on the comparative costs of dry and evaporative cooled towers

  9. The Cost of Joint Replacement: Comparing Two Approaches to Evaluating Costs of Total Hip and Knee Arthroplasty.

    Science.gov (United States)

    Palsis, John A; Brehmer, Thomas S; Pellegrini, Vincent D; Drew, Jacob M; Sachs, Barton L

    2018-02-21

    In an era of mandatory bundled payments for total joint replacement, accurate analysis of the cost of procedures is essential for orthopaedic surgeons and their institutions to maintain viable practices. The purpose of this study was to compare traditional accounting and time-driven activity-based costing (TDABC) methods for estimating the total costs of total hip and knee arthroplasty care cycles. We calculated the overall costs of elective primary total hip and total knee replacement care cycles at our academic medical center using traditional and TDABC accounting methods. We compared the methods with respect to the overall costs of hip and knee replacement and the costs for each major cost category. The traditional accounting method resulted in higher cost estimates. The total cost per hip replacement was $22,076 (2014 USD) using traditional accounting and was $12,957 using TDABC. The total cost per knee replacement was $29,488 using traditional accounting and was $16,981 using TDABC. With respect to cost categories, estimates using traditional accounting were greater for hip and knee replacement, respectively, by $3,432 and $5,486 for personnel, by $3,398 and $3,664 for space and equipment, and by $2,289 and $3,357 for indirect costs. Implants and consumables were derived from the actual hospital purchase price; accordingly, both methods produced equivalent results. Substantial cost differences exist between accounting methods. The focus of TDABC only on resources used directly by the patient contrasts with the allocation of all operating costs, including all indirect costs and unused capacity, with traditional accounting. We expect that the true costs of hip and knee replacement care cycles are likely somewhere between estimates derived from traditional accounting methods and TDABC. TDABC offers patient-level granular cost information that better serves in the redesign of care pathways and may lead to more strategic resource-allocation decisions to optimize

  10. Cost-benefit analysis for environmental impacts and radwaste system for nuclear power plant

    International Nuclear Information System (INIS)

    Mun, K.N.; Yook, C.C.

    1982-01-01

    During operation of nuclear power plant, radioactive material is inevitably formed. This radioactive material must be safely processed by radwaste system so that essentially zero activity is released to the environment. However zero released activity is not really practicable and population doses resulted from released activity are proportional to total annual cost for the radwaste system. In this study, cost-benefit analysis for the radwaste system of the Korean Nuclear Units 5 and 6 is performed to evaluate the optimization between the total annual cost for the radwaste system and population doses within 80 km from the plants. From the analysis, the following results are obtained; 1. the total population dose is estimated 4.04 x 10 3 man-rem/year, 2. total annual cost for the radwaste system is required $ 1.74 x 10 6 , 3. cost-benefit ratio is estimated $ 429/man-rem. (Author)

  11. Impact Of Total Quality Management (TQM), Activity Based Costing ...

    African Journals Online (AJOL)

    Time (JIT), and Total Quality Management (TQM) as strategic initiatives lead to improved financial performance in the Turkish textile industry. Strong evidence emerged that there is a strong positive association between using ABC, JIT or TQM ...

  12. HIGH ECCENTRICITY EOQ TOTAL COST FUNCTION YIELDS JIT RESULTs

    Directory of Open Access Journals (Sweden)

    Willian Roach

    2010-06-01

    Full Text Available No estoque de bens perecíveis, o custo de armazenamento H é muito maior do que o previsto na fórmula clássica do lote econômico do pedido (EOQ. Para bens perecíveis, a função custo total no EOQ é um pico e não uma reta horizontal. Esta forma pontiaguda leva o modelo EOQ a produzir entregas just in time (JIT - resultados semelhantes. O efeito pontiagudo (excentricidade da curva de custo total do lote econômico EOQ depende apenas do custo de armazenamento (H e não da demanda anual (D ou do custo do pedido (S. D e S determinam o nível (altura da curva de custo total do estoque (TC, mas não a forma.

  13. An analysis of nuclear power plant operating costs

    International Nuclear Information System (INIS)

    1988-01-01

    This report presents the results of a statistical analysis of nonfuel operating costs for nuclear power plants. Most studies of the economic costs of nuclear power have focused on the rapid escalation in the cost of constructing a nuclear power plant. The present analysis found that there has also been substantial escalation in real (inflation-adjusted) nonfuel operating costs. It is important to determine the factors contributing to the escalation in operating costs, not only to understand what has occurred but also to gain insights about future trends in operating costs. There are two types of nonfuel operating costs. The first is routine operating and maintenance expenditures (O and M costs), and the second is large postoperational capital expenditures, or what is typically called ''capital additions.'' O and M costs consist mainly of expenditures on labor, and according to one recently completed study, the majoriy of employees at a nuclear power plant perform maintenance activities. It is generally thought that capital additions costs consist of large maintenance expenditures needed to keep the plants operational, and to make plant modifications (backfits) required by the Nuclear Regulatory Commission (NRC). Many discussions of nuclear power plant operating costs have not considered these capital additions costs, and a major finding of the present study is that these costs are substantial. The objective of this study was to determine why nonfuel operating costs have increased over the past decade. The statistical analysis examined a number of factors that have influenced the escalation in real nonfuel operating costs and these are discussed in this report. 4 figs, 19 tabs

  14. Effects of the Length of Stay on the Cost of Total Knee and Total Hip Arthroplasty from 2002 to 2013.

    Science.gov (United States)

    Molloy, Ilda B; Martin, Brook I; Moschetti, Wayne E; Jevsevar, David S

    2017-03-01

    Utilization of total knee and hip arthroplasty has greatly increased in the past decade in the United States; these are among the most expensive procedures in patients with Medicare. Advances in surgical techniques, anesthesia, and care pathways decrease hospital length of stay. We examined how trends in hospital cost were altered by decreases in length of stay. Procedure, demographic, and economic data were collected on 6.4 million admissions for total knee arthroplasty and 2.8 million admissions for total hip arthroplasty from 2002 to 2013 using the National (Nationwide) Inpatient Sample, a component of the Healthcare Cost and Utilization Project. Trends in mean hospital costs and their association with length of stay were estimated using inflation-adjusted, survey-weighted generalized linear regression models, controlling for patient demographic characteristics and comorbidity. From 2002 to 2013, the length of stay decreased from a mean time of 4.06 to 2.97 days for total knee arthroplasty and from 4.06 to 2.75 days for total hip arthroplasty. During the same time period, the mean hospital cost for total knee arthroplasty increased from $14,988 (95% confidence interval [CI], $14,927 to $15,049) in 2002 to $22,837 (95% CI, $22,765 to $22,910) in 2013 (an overall increase of $7,849 or 52.4%). The mean hospital cost for total hip arthroplasty increased from $15,792 (95% CI, $15,706 to $15,878) in 2002 to $23,650 (95% CI, $23,544 to $23,755) in 2013 (an increase of $7,858 or 49.8%). If length of stay were set at the 2002 mean, the growth in cost for total knee arthroplasty would have been 70.8% instead of 52.4% as observed, and the growth in cost for total hip arthroplasty would have been 67.4% instead of 49.8% as observed. Hospital costs for joint replacement increased from 2002 to 2013, but were attenuated by reducing inpatient length of stay. With demographic characteristics showing an upward trend in the utilization of joint arthroplasty, including a shift

  15. Impact of cost escalation on nuclear plant financing

    International Nuclear Information System (INIS)

    Sherman, R.J.

    1979-01-01

    The extreme degree of plant cost increases in the recent years results from a combination of ten years of inflation in the overall economy, the adoption of more stringent statutory and regulatory requirements, and delays resulting from both regulation and intervention. Since different energy forms are competitive, cost and cost changes associated with any form have to be evaluated as - ''compared to what.'' Costs and changes in costs of nuclear and coal fired generation in the United States are reviewed. Reference to specific cost estimates of nuclear and coal plants of equivalent capacity enables separation of the cost effects of the three factors inflation, regulation and delay. In this analysis per kilowatt costs of two 1200 MW nuclear units are compared to those of three 800 MW bituminous coal units. At last various methods to finance new facilities are discussed. (author)

  16. Total data management in the La Hague reprocessing plant

    International Nuclear Information System (INIS)

    Berthion, Y.; Perot, J.P.; Silie, P.

    1993-01-01

    Due to the complexity of a spent fuel reprocessing plant and its nuclear characteristics, the operators must have real-time access to updated information on many subjects. To meet these requirements effectively, Cogema has installed a number of diversified data processing systems linked by a communications network called Haguenet. The whole system forms the La Hague Total Data Management System (TDMS) which performs a full range of functions, namely production data management, maintenance data management, technical documentation and miscellaneous. Some examples of the main process data management applications implemented within the La Hague TDMS are briefly described (nuclear materials and waste follow-up, analytical data management, operating procedures management and site inspection management). Also presented are some examples of the maintenance-related systems implemented within the La Hague TDMS (diagnostic assistance system, software maintenance center, maintenance interventions demand and spare parts data management). (Z.S.)

  17. Cost-effectiveness of positive contrast and nuclear arthrography in patients who underwent total hip arthroplasty

    International Nuclear Information System (INIS)

    Swan, J.S.; Braunstein, E.M.; Capello, W.; Wellman, H.

    1989-01-01

    The authors have compared the cost effectiveness of contrast arthrography (CA) and nuclear arthrography (NA), in which In-111 chloride is injected with the contrast material, of total hip arthroplasties. Their series included 48 cases of surgically proved loose femoral components. The cost per true-positive result was obtained by taking the total cost of the examinations in surgically proved cases and dividing by the number of true-position cases. The cost of CA was $297 and the cost of NA was $335. For CA, the cost per true positive was $1,018, and for the NA the cost per true positive was $946. In spite of higher initial cost, NA is more cost effective than CA on a cost per true-positive case basis. NA is cost effective in evaluating hip arthroplasties in which there is suspicion of a loose femoral component

  18. Electrochromic Windows: Process and Fabrication Improvements for Lower Total Costs

    Energy Technology Data Exchange (ETDEWEB)

    Mark Burdis; Neil Sbar

    2007-03-31

    The overall goal with respect to the U.S. Department of Energy (DOE) is to achieve significant national energy savings through maximized penetration of EC windows into existing markets so that the largest cumulative energy reduction can be realized. The speed with which EC windows can be introduced and replace current IGU's (and current glazings) is clearly a strong function of cost. Therefore, the aim of this project was to investigate possible improvements to the SageGlass{reg_sign} EC glazing products to facilitate both process and fabrication improvements resulting in lower overall costs. The project was split into four major areas dealing with improvements to the electrochromic layer, the capping layer, defect elimination and general product improvements. Significant advancements have been made in each of the four areas. These can be summarized as follows: (1) Plasma assisted deposition for the electrochromic layer was pursued, and several improvements made to the technology for producing a plasma beam were made. Functional EC devices were produced using the new technology, but there are still questions to be answered regarding the intrinsic properties of the electrochromic films produced by this method. (2) The capping layer work was successfully implemented into the existing SageGlass{reg_sign} product, thereby providing a higher level of transparency and somewhat lower reflectivity than the 'standard' product. (3) Defect elimination is an ongoing effort, but this project spurred some major defect reduction programs, which led to significant improvements in yield, with all the implicit benefits afforded. In particular, major advances were made in the development of a new bus bar application process aimed at reducing the numbers of 'shorts' developed in the finished product, as well as making dramatic improvements in the methods used for tempering the glass, which had previously been seen to produce a defect which appeared as a

  19. Total quality management to improve gas plant profits

    International Nuclear Information System (INIS)

    Kovacs, K.; Wood, G.; Thompson, L.

    1992-01-01

    This paper describes the application of total quality management (TQM) techniques to the gas processing industry. It also assesses the profit potential for applying TQM in a typical plant situation. Companies utilizing TQM techniques will enjoy a competitive advantage. It represents a new way of doing business for the gas processing industry and incorporates many of Dr. W. Edwards Deming's methods which are often cited as one of the competitive advantages used by the Japanese. TQM can be described as a collection of systems or techniques that work toward two major objectives: To continuously improve the process or operation; and To view meeting the customer's needs as an important criterion for success. As applied to a typical U.S. gas processing operation, it involves several different techniques which are outlined in the paper. The benefits of TQM are detailed in this paper. All of these benefits go directly to a plant's bottom line profitability. The paper also describes ho to establish a program and identifies the factors necessary for successful implementation

  20. Cost of goods sold and total cost of delivery for oral and parenteral vaccine packaging formats.

    Science.gov (United States)

    Sedita, Jeff; Perrella, Stefanie; Morio, Matt; Berbari, Michael; Hsu, Jui-Shan; Saxon, Eugene; Jarrahian, Courtney; Rein-Weston, Annie; Zehrung, Darin

    2018-03-14

    Despite limitations of glass packaging for vaccines, the industry has been slow to implement alternative formats. Polymer containers may address many of these limitations, such as breakage and delamination. However, the ability of polymer containers to achieve cost of goods sold (COGS) and total cost of delivery (TCOD) competitive with that of glass containers is unclear, especially for cost-sensitive low- and lower-middle-income countries. COGS and TCOD models for oral and parenteral vaccine packaging formats were developed based on information from subject matter experts, published literature, and Kenya's comprehensive multiyear plan for immunization. Rotavirus and inactivated poliovirus vaccines (IPV) were used as representative examples of oral and parenteral vaccines, respectively. Packaging technologies evaluated included glass vials, blow-fill-seal (BFS) containers, preformed polymer containers, and compact prefilled auto-disable (CPAD) devices in both BFS and preformed formats. For oral vaccine packaging, BFS multi-monodose (MMD) ampoules were the least expensive format, with a COGS of $0.12 per dose. In comparison, oral single-dose glass vials had a COGS of $0.40. BFS MMD ampoules had the lowest TCOD of oral vaccine containers at $1.19 per dose delivered, and ten-dose glass vials had a TCOD of $1.61 per dose delivered. For parenteral vaccines, the lowest COGS was achieved with ten-dose glass vials at $0.22 per dose. In contrast, preformed CPAD devices had the highest COGS at $0.60 per dose. Ten-dose glass vials achieved the lowest TCOD of the parenteral vaccine formats at $1.56 per dose delivered. Of the polymer containers for parenteral vaccines, BFS MMD ampoules achieved the lowest TCOD at $1.89 per dose delivered, whereas preformed CPAD devices remained the most expensive format, at $2.25 per dose delivered. Given their potential to address the limitations of glass and reduce COGS and TCOD, polymer containers deserve further consideration as alternative

  1. Validation of generic cost estimates for construction-related activities at nuclear power plants: Final report

    International Nuclear Information System (INIS)

    Simion, G.; Sciacca, F.; Claiborne, E.; Watlington, B.; Riordan, B.; McLaughlin, M.

    1988-05-01

    This report represents a validation study of the cost methodologies and quantitative factors derived in Labor Productivity Adjustment Factors and Generic Methodology for Estimating the Labor Cost Associated with the Removal of Hardware, Materials, and Structures From Nuclear Power Plants. This cost methodology was developed to support NRC analysts in determining generic estimates of removal, installation, and total labor costs for construction-related activities at nuclear generating stations. In addition to the validation discussion, this report reviews the generic cost analysis methodology employed. It also discusses each of the individual cost factors used in estimating the costs of physical modifications at nuclear power plants. The generic estimating approach presented uses the /open quotes/greenfield/close quotes/ or new plant construction installation costs compiled in the Energy Economic Data Base (EEDB) as a baseline. These baseline costs are then adjusted to account for labor productivity, radiation fields, learning curve effects, and impacts on ancillary systems or components. For comparisons of estimated vs actual labor costs, approximately four dozen actual cost data points (as reported by 14 nuclear utilities) were obtained. Detailed background information was collected on each individual data point to give the best understanding possible so that the labor productivity factors, removal factors, etc., could judiciously be chosen. This study concludes that cost estimates that are typically within 40% of the actual values can be generated by prudently using the methodologies and cost factors investigated herein

  2. The total lifetime health cost savings of smoking cessation to society

    DEFF Research Database (Denmark)

    Rasmussen, Gitte Susanne; Prescott, Eva; Sørensen, Thorkild I A

    2005-01-01

    Smoking cessation has major immediate and long-term health benefits. However, ex-smokers' total lifetime health costs and continuing smokers' costs remain uncompared, and hence the economic savings of smoking cessation to society have not been determined.......Smoking cessation has major immediate and long-term health benefits. However, ex-smokers' total lifetime health costs and continuing smokers' costs remain uncompared, and hence the economic savings of smoking cessation to society have not been determined....

  3. Dynamic cost control information system for nuclear power plant construction

    International Nuclear Information System (INIS)

    Wang Yongqing; Liu Wei

    1998-01-01

    The authors first introduce the cost control functions of some overseas popular project management software at present and the specific ways of cost control of nuclear power plant construction in China. Then the authors stress the necessity of cost and schedule control integration and present the concept of dynamic cost control, the design scheme of dynamic cost control information system and the data structure modeling. Based on the above, the authors can develop the system which has the functions of dynamic estimate, cash flow management and cost optimization for nuclear engineering

  4. The costs of completing unfinished US nuclear power plants

    International Nuclear Information System (INIS)

    Feldman, S.L.; Bernstein, M.A.; Noland, R.B.

    1988-01-01

    A cost benefit analysis is performed to assess the costs of completing unfinished nuclear power plants in four regions of the United States of America, (north-east, south-east, mid-west and west). The analysis is in five main sections: the projection of the cost to complete nuclear plants under construction, the forecast of future operations and maintenance costs, the forecast of price of fuels, the evaluation of future electricity demand and capacity growth, and calculation of the financial cost-benefit ratio based on the preceding figures. It was found that in the north-east, mid-west and west, because the demand for the power will not be made before the year 2000, finishing the units is not the least-cost supply option. Therefore, most of the units should not be finished unless over 90% completed already, in which case it may be cost-effective to finish them. (author)

  5. Intensive care unit drug costs in the context of total hospital drug expenditures with suggestions for targeted cost containment efforts.

    Science.gov (United States)

    Altawalbeh, Shoroq M; Saul, Melissa I; Seybert, Amy L; Thorpe, Joshua M; Kane-Gill, Sandra L

    2018-04-01

    To assess costs of intensive care unit (ICU) related pharmacotherapy relative to hospital drug expenditures, and to identify potential targets for cost-effectiveness investigations. We offer the unique advantage of comparing ICU drug costs with previously published data a decade earlier to describe changes over time. Financial transactions for all ICU patients during fiscal years (FY) 2009-2012 were retrieved from the hospital's data repository. ICU drug costs were evaluated for each FY. ICU departments' charges were also retrieved and calculated as percentages of total ICU charges. Albumin, prismasate (dialysate), voriconazole, factor VII and alteplase denoted the highest percentages of ICU drug costs. ICU drug costs contributed to an average of 31% (SD 1.0%) of the hospital's total drug costs. ICU drug costs per patient day increased by 5.8% yearly versus 7.8% yearly for non-ICU drugs. This rate was higher for ICU drugs costs at 12% a decade previous. Pharmacy charges contributed to 17.7% of the total ICU charges. Growth rates of costs per year have declined but still drug expenditures in the ICU are consistently a significant driver in this resource intensive environment with a high impact on hospital drug expenditures. Copyright © 2017 Elsevier Inc. All rights reserved.

  6. How do high cost-sharing policies for physician care affect total care costs among people with chronic disease?

    Science.gov (United States)

    Xin, Haichang; Harman, Jeffrey S; Yang, Zhou

    2014-01-01

    This study examines whether high cost-sharing in physician care is associated with a differential impact on total care costs by health status. Total care includes physician care, emergency room (ER) visits and inpatient care. Since high cost-sharing policies can reduce needed care as well as unneeded care use, it raises the concern whether these policies are a good strategy for controlling costs among chronically ill patients. This study used the 2007 Medical Expenditure Panel Survey data with a cross-sectional study design. Difference in difference (DID), instrumental variable technique, two-part model, and bootstrap technique were employed to analyze cost data. Chronically ill individuals' probability of reducing any overall care costs was significantly less than healthier individuals (beta = 2.18, p = 0.04), while the integrated DID estimator from split results indicated that going from low cost-sharing to high cost-sharing significantly reduced costs by $12,853.23 more for sick people than for healthy people (95% CI: -$17,582.86, -$8,123.60). This greater cost reduction in total care among sick people likely resulted from greater cost reduction in physician care, and may have come at the expense of jeopardizing health outcomes by depriving patients of needed care. Thus, these policies would be inappropriate in the short run, and unlikely in the long run to control health plans costs among chronically ill individuals. A generous benefit design with low cost-sharing policies in physician care or primary care is recommended for both health plans and chronically ill individuals, to save costs and protect these enrollees' health status.

  7. Controlling costs without compromising quality: paying hospitals for total knee replacement.

    Science.gov (United States)

    Pine, Michael; Fry, Donald E; Jones, Barbara L; Meimban, Roger J; Pine, Gregory J

    2010-10-01

    Unit costs of health services are substantially higher in the United States than in any other developed country in the world, without a correspondingly healthier population. An alternative payment structure, especially for high volume, high cost episodes of care (eg, total knee replacement), is needed to reward high quality care and reduce costs. The National Inpatient Sample of administrative claims data was used to measure risk-adjusted mortality, postoperative length-of-stay, costs of routine care, adverse outcome rates, and excess costs of adverse outcomes for total knee replacements performed between 2002 and 2005. Empirically identified inefficient and ineffective hospitals were then removed to create a reference group of high-performance hospitals. Predictive models for outcomes and costs were recalibrated to the reference hospitals and used to compute risk-adjusted outcomes and costs for all hospitals. Per case predicted costs were computed and compared with observed costs. Of the 688 hospitals with acceptable data, 62 failed to meet effectiveness criteria and 210 were identified as inefficient. The remaining 416 high-performance hospitals had 13.4% fewer risk-adjusted adverse outcomes (4.56%-3.95%; P costs ($12,773-$11,512; P costs. A payment system based on the demonstrated performance of effective, efficient hospitals can produce sizable cost savings without jeopardizing quality. In this study, 96% of total excess hospital costs resulted from higher routine costs at inefficient hospitals, whereas only 4% was associated with ineffective care.

  8. Electric utility power plant construction costs, 1st Edition

    International Nuclear Information System (INIS)

    Anon.

    1993-01-01

    New UDI report combines historical construction costs for more than 1,000 coal, oil, gas, nuclear and geothermal units that have entered commercial operation since 1966 and projected power plant construction costs for about 400 utility-owned generating units scheduled to enter commercial operation during the next 20 years. Key design characteristics and equipment suppliers, A/E, constructor and original installed cost data. Direct construction costs without AFUDC are provided where known. Historical construction cost data are also provided for about 130 utility-owned hydroelectric, gas turbine, combined-cycle and diesel units (these data are generally for units entering service after 1980)

  9. Progress report on the investigation of nuclear plant costs

    International Nuclear Information System (INIS)

    Kent, G.F.

    1987-01-01

    Over the past few years, many studies have been performed in an effort to understand, evaluate, and explain the reasons for the substantial increases in nuclear plant costs, as well as for the divergence between predicted and actual costs. Concerns regarding these cost increases is shared by utility owners, engineer/constructors, and public utility commissions. The future use of nuclear power depends on the ability of the industry to control these costs while maintaining safety. Stone and Webster Engineering Corporation (SWEC) has responded to this concern by initiating an internal study to evaluate, quantify, and explain the factors influencing this cost growth. Previously, a conceptual approach was presented in which three explanatory variables or factors were used as surrogates for the many variables that affected plant cost. This paper presents a progress report of that continuing study

  10. Belowground advantages in construction cost facilitate a cryptic plant invasion.

    Science.gov (United States)

    Caplan, Joshua S; Wheaton, Christine N; Mozdzer, Thomas J

    2014-04-30

    The energetic cost of plant organ construction is a functional trait that is useful for understanding carbon investment during growth (e.g. the resource acquisition vs. tissue longevity tradeoff), as well as in response to global change factors like elevated CO2 and N. Despite the enormous importance of roots and rhizomes in acquiring soil resources and responding to global change, construction costs have been studied almost exclusively in leaves. We sought to determine how construction costs of aboveground and belowground organs differed between native and introduced lineages of a geographically widely dispersed wetland plant species (Phragmites australis) under varying levels of CO2 and N. We grew plants under ambient and elevated atmospheric CO2, as well as under two levels of soil nitrogen. We determined construction costs for leaves, stems, rhizomes and roots, as well as for whole plants. Across all treatment conditions, the introduced lineage of Phragmites had a 4.3 % lower mean rhizome construction cost than the native. Whole-plant construction costs were also smaller for the introduced lineage, with the largest difference in sample means (3.3 %) occurring under ambient conditions. In having lower rhizome and plant-scale construction costs, the introduced lineage can recoup its investment in tissue construction more quickly, enabling it to generate additional biomass with the same energetic investment. Our results suggest that introduced Phragmites has had an advantageous tissue investment strategy under historic CO2 and N levels, which has facilitated key rhizome processes, such as clonal spread. We recommend that construction costs for multiple organ types be included in future studies of plant carbon economy, especially those investigating global change. Published by Oxford University Press on behalf of the Annals of Botany Company.

  11. The adoption of total cost of ownership for sourcing decisions - a structural equations analysis

    NARCIS (Netherlands)

    Wouters, Marc; Anderson, James C.; Wynstra, Finn

    2005-01-01

    This study investigates the adoption of total cost of ownership (TCO) analysis to improve sourcing decisions. TCO can be seen as an application of activity based costing (ABC) that quantifies the costs that are involved in acquiring and using purchased goods or services. TCO supports purchasing

  12. Association of Hospital Costs With Complications Following Total Gastrectomy for Gastric Adenocarcinoma.

    Science.gov (United States)

    Selby, Luke V; Gennarelli, Renee L; Schnorr, Geoffrey C; Solomon, Stephen B; Schattner, Mark A; Elkin, Elena B; Bach, Peter B; Strong, Vivian E

    2017-10-01

    Postoperative complications are associated with increased hospital costs following major surgery, but the mechanism by which they increase cost and the categories of care that drive this increase are poorly described. To describe the association of postoperative complications with hospital costs following total gastrectomy for gastric adenocarcinoma. This retrospective analysis of a prospectively collected gastric cancer surgery database at a single National Cancer Institute-designated comprehensive cancer center included all patients undergoing curative-intent total gastrectomy for gastric adenocarcinoma between January 2009 and December 2012 and was conducted in 2015 and 2016. Ninety-day normalized postoperative costs. Hospital accounting system costs were normalized to reflect Medicare reimbursement levels using the ratio of hospital costs to Medicare reimbursement and categorized into major cost categories. Differences between costs in Medicare proportional dollars (MP $) can be interpreted as the amount that would be reimbursed to an average hospital by Medicare if it paid differentially based on types and extent of postoperative complications. In total, 120 patients underwent curative-intent total gastrectomy for stage I through III gastric adenocarcinoma between 2009 and 2012. Of these, 79 patients (65.8%) were men, and the median (interquartile range) age was 64 (52-70) years. The 51 patients (42.5%) who underwent an uncomplicated total gastrectomy had a mean (SD) normalized cost of MP $12 330 (MP $2500), predominantly owing to the cost of surgical care (mean [SD] cost, MP $6830 [MP $1600]). The 34 patients (28.3%) who had a major complication had a mean (SD) normalized cost of MP $37 700 (MP $28 090). Surgical care was more expensive in these patients (mean [SD] cost, MP $8970 [MP $2750]) but was a smaller contributor to total cost (24%) owing to increased costs from room and board (mean [SD] cost, MP $11 940 [MP $8820]), consultations (mean [SD

  13. Cost structure analysis of commercial nuclear power plants in Japan based on corporate financial statements of electric utility companies

    International Nuclear Information System (INIS)

    Kunitake, Norifumi; Nagano, Koji; Suzuki, Tatsujiro

    1998-01-01

    In this paper, we analyze past and current cost structure of commercial nuclear power plants in Japan based on annual corporate financial statements published by the Japanese electric utility companies, instead of employing the conventional methodology of evaluating the generation cost for a newly constructed model plant. The result of our study on existing commercial nuclear plants reveals the increasing significance of O and M and fuel cycle costs in total generation cost. Thus, it is suggested that electric power companies should take more efforts to reduce these costs in order to maintain the competitiveness of nuclear power in Japan. (author)

  14. US nuclear power plant operating cost and experience summaries

    International Nuclear Information System (INIS)

    Kohn, W.E.; Reid, R.L.; White, V.S.

    1998-02-01

    NUREG/CR-6577, U.S. Nuclear Power Plant Operating Cost and Experience Summaries, has been prepared to provide historical operating cost and experience information on U.S. commercial nuclear power plants. Cost incurred after initial construction are characterized as annual production costs, representing fuel and plant operating and maintenance expenses, and capital expenditures related to facility additions/modifications which are included in the plant capital asset base. As discussed in the report, annual data for these two cost categories were obtained from publicly available reports and must be accepted as having different degrees of accuracy and completeness. Treatment of inconclusive and incomplete data is discussed. As an aid to understanding the fluctuations in the cost histories, operating summaries for each nuclear unit are provided. The intent of these summaries is to identify important operating events; refueling, major maintenance, and other significant outages; operating milestones; and significant licensing or enforcement actions. Information used in the summaries is condensed from annual operating reports submitted by the licensees, plant histories contained in Nuclear Power Experience, trade press articles, and the Nuclear Regulatory Commission (NRC) web site (www.nrc.gov)

  15. US nuclear power plant operating cost and experience summaries

    Energy Technology Data Exchange (ETDEWEB)

    Kohn, W.E.; Reid, R.L.; White, V.S.

    1998-02-01

    NUREG/CR-6577, U.S. Nuclear Power Plant Operating Cost and Experience Summaries, has been prepared to provide historical operating cost and experience information on U.S. commercial nuclear power plants. Cost incurred after initial construction are characterized as annual production costs, representing fuel and plant operating and maintenance expenses, and capital expenditures related to facility additions/modifications which are included in the plant capital asset base. As discussed in the report, annual data for these two cost categories were obtained from publicly available reports and must be accepted as having different degrees of accuracy and completeness. Treatment of inconclusive and incomplete data is discussed. As an aid to understanding the fluctuations in the cost histories, operating summaries for each nuclear unit are provided. The intent of these summaries is to identify important operating events; refueling, major maintenance, and other significant outages; operating milestones; and significant licensing or enforcement actions. Information used in the summaries is condensed from annual operating reports submitted by the licensees, plant histories contained in Nuclear Power Experience, trade press articles, and the Nuclear Regulatory Commission (NRC) web site (www.nrc.gov).

  16. Evaluating decommissioning costs for nuclear power plants

    International Nuclear Information System (INIS)

    MacDonald, R.R.

    1980-01-01

    An overview is presented of the economic aspects of decommissioning of large nuclear power plants in an attempt to put the subject in proper perspective. This is accomplished by first surveying the work that has been done to date in evaluating the requirements for decommissioning. A review is presented of the current concepts of decommissioning and a discussion of a few of the uncertainties involved. This study identifies the key factors to be considered in the econmic evaluation of decommissioning alternatives and highlights areas in which further study appears to be desirable. 12 refs

  17. Strategies for reducing implant costs in the revision total knee arthroplasty episode of care.

    Science.gov (United States)

    Elbuluk, Ameer M; Old, Andrew B; Bosco, Joseph A; Schwarzkopf, Ran; Iorio, Richard

    2017-12-01

    Implant price has been identified as a significant contributing factor to high costs associated with revision total knee arthroplasty (rTKA). The goal of this study is to analyze the cost of implants used in rTKAs and to compare this pricing with 2 alternative pricing models. Using our institutional database, we identified 52 patients from January 1, 2014 to December 31, 2014. Average cost of components for each case was calculated and compared to the total hospital cost for that admission. Costs for an all-component revision were then compared to a proposed "direct to hospital" (DTH) standardized pricing model and a fixed price revision option. Potential savings were calculated from these figures. On average, 28% of the total hospital cost was spent on implants for rTKA. The average cost for revision of all components was $13,640 and ranged from $3000 to $28,000. On average, this represented 32.7% of the total hospital cost. Direct to hospital implant pricing could potentially save approximately $7000 per rTKA, and the fixed pricing model could provide a further $1000 reduction per rTKA-potentially saving $8000 per case on implants alone. Alternative implant pricing models could help lower the total cost of rTKA, which would allow hospitals to achieve significant cost containment.

  18. A decision-making framework for total ownership cost management of complex systems: A Delphi study

    Science.gov (United States)

    King, Russel J.

    This qualitative study, using a modified Delphi method, was conducted to develop a decision-making framework for the total ownership cost management of complex systems in the aerospace industry. The primary focus of total ownership cost is to look beyond the purchase price when evaluating complex system life cycle alternatives. A thorough literature review and the opinions of a group of qualified experts resulted in a compilation of total ownership cost best practices, cost drivers, key performance factors, applicable assessment methods, practitioner credentials and potential barriers to effective implementation. The expert panel provided responses to the study questions using a 5-point Likert-type scale. Data were analyzed and provided to the panel members for review and discussion with the intent to achieve group consensus. As a result of the study, the experts agreed that a total ownership cost analysis should (a) be as simple as possible using historical data; (b) establish cost targets, metrics, and penalties early in the program; (c) monitor the targets throughout the product lifecycle and revise them as applicable historical data becomes available; and (d) directly link total ownership cost elements with other success factors during program development. The resultant study framework provides the business leader with incentives and methods to develop and implement strategies for controlling and reducing total ownership cost over the entire product life cycle when balancing cost, schedule, and performance decisions.

  19. On Decommissioning Cost for Nuclear Power Plants

    Energy Technology Data Exchange (ETDEWEB)

    Varley, Geoff (NAC International (United Kingdom)); Rush, Chris (NAC International (United States))

    2011-01-15

    The two biggest changes in NPP DandD over the last 15 years that are applicable across all countries are: a. Equipment and tools used in NPP DandD have evolved to be available on a more industrial basis, although concerning DandD of the main NPP components, such activity typically is very individual and requires one-of equipment to be developed. b. Regulation of DandD has increased. Earlier regulations were adapting to what emerged from evolving DandD projects. Today regulatory requirements have caught up and have been framed based on the feedback of experience over the last 15 years. In general they impose prescriptive requirements on DandD approaches and execution. In the U.S. access to LLW disposal has been opened up to a majority of states, which will ease the development and timely execution of DandD projects. A newly emerging trend in the U.S. is that segregation of some categories of waste, to facilitate the disposal of some volumes in general landfill rather than in radioactive waste disposal facilities, is being sacrificed, on cost grounds, in favour of mixing waste volumes with the consequence of having to dispose of a larger volume of waste in a LLW facility. Regarding access to information that can be meaningful and sufficiently detailed to support an international benchmarking inter-comparison of NPP DandD cost information: - NAC has established good access to detailed information on actual DandD projects at one U.S. PWR (Trojan) and one U.S. BWR (Rancho Seco). Additional information sources probably can be accessed with additional investigation. - Germany has highly relevant cost estimate and actual NPP DandD experience. Accessibility of the information is not yet fully determined. This will need more extensive, face-to-face interaction with the relevant stakeholders. Utilities and cost estimate service providers offer the opportunity to access relevant information. Specific terms and conditions that would apply and the extent of detail that would be

  20. On Decommissioning Cost for Nuclear Power Plants

    International Nuclear Information System (INIS)

    Varley, Geoff; Rush, Chris

    2011-01-01

    The two biggest changes in NPP DandD over the last 15 years that are applicable across all countries are: a. Equipment and tools used in NPP DandD have evolved to be available on a more industrial basis, although concerning DandD of the main NPP components, such activity typically is very individual and requires one-of equipment to be developed. b. Regulation of DandD has increased. Earlier regulations were adapting to what emerged from evolving DandD projects. Today regulatory requirements have caught up and have been framed based on the feedback of experience over the last 15 years. In general they impose prescriptive requirements on DandD approaches and execution. In the U.S. access to LLW disposal has been opened up to a majority of states, which will ease the development and timely execution of DandD projects. A newly emerging trend in the U.S. is that segregation of some categories of waste, to facilitate the disposal of some volumes in general landfill rather than in radioactive waste disposal facilities, is being sacrificed, on cost grounds, in favour of mixing waste volumes with the consequence of having to dispose of a larger volume of waste in a LLW facility. Regarding access to information that can be meaningful and sufficiently detailed to support an international benchmarking inter-comparison of NPP DandD cost information: - NAC has established good access to detailed information on actual DandD projects at one U.S. PWR (Trojan) and one U.S. BWR (Rancho Seco). Additional information sources probably can be accessed with additional investigation. - Germany has highly relevant cost estimate and actual NPP DandD experience. Accessibility of the information is not yet fully determined. This will need more extensive, face-to-face interaction with the relevant stakeholders. Utilities and cost estimate service providers offer the opportunity to access relevant information. Specific terms and conditions that would apply and the extent of detail that would be

  1. Capital cost: pressurized water reactor plant. Commercial electric power cost studies

    Energy Technology Data Exchange (ETDEWEB)

    1977-06-01

    The investment cost study for the 1139 MW(e) pressurized water reactor (PWR) central station power plant consists of two volumes. This volume contains the drawings, equipment list and site description.

  2. Capital cost: pressurized water reactor plant. Commercial electric power cost studies

    International Nuclear Information System (INIS)

    1977-06-01

    The investment cost study for the 1139 MW(e) pressurized water reactor (PWR) central station power plant consists of two volumes. This volume contains the drawings, equipment list and site description

  3. Guidelines for estimating nuclear power plant decommissioning costs

    International Nuclear Information System (INIS)

    LaGuardia, T.S.; Williams, D.H.

    1989-01-01

    The objectives of the study were: (1) To develop guidelines to facilitate estimating the cost of nuclear power plant decommissioning alternatives on a plant-specific basis and to facilitate comparing estimates made by others. The guidelines are expressed in a form that could be readily adapted by technical specialists from individual utilities or by other uses. (2) To enhance the industry's credibility with decision-makes at the state and federal levels during rate/regulatory processes involving decommissioning costs. This is accomplished by providing a detailed, systematic breakdown of how decommissioning cost estimates are prepared. (3) To increase the validity, realism, and accuracy of site-specific decommissioning cost estimates. This is accomplished by pulling together the experiences and practices of several nuclear utilities and consultants in conducting past decommissioning cost estimates

  4. Main influence factors on the final energy generation cost of a nuclear power plant in comparison with other energy sources

    International Nuclear Information System (INIS)

    Souza, J.A.M. de; Glardon, C.; Schmidt, R.M.

    1981-01-01

    The main factors in the construction and in the operation of nuclear power plants that affect the final energy generation cost are presented. The structure of the energy generation cost, of the nuclear fuel cost and the total investment are studied. (E.G.) [pt

  5. Cost estimating relationships for nuclear power plant operationa and maintenance

    International Nuclear Information System (INIS)

    Bowers, H.I.; Fuller, L.C.; Myers, M.L.

    1987-11-01

    Revised cost estimating relationships for 1987 are presented for estimating annual nonfuel operation and maintenance (O and M) costs for light-water reactor (LWR) nuclear power plants, which update guidelines published previously in 1982. The purpose of these cost estimating relationships is for use in long range planning and evaluations of the economics of nuclear energy for electric power generation. A listing of a computer program, LWROM, implementing the cost estimating relationships and written in advanced BASIC for IBM personal computers, is included

  6. Animal board invited review: Dairy cow lameness expenditures, losses and total cost.

    Science.gov (United States)

    Dolecheck, K; Bewley, J

    2018-03-20

    Lameness is one of the most costly dairy cow diseases, yet adoption of lameness prevention strategies remains low. Low lameness prevention adoption might be attributable to a lack of understanding regarding total lameness costs. In this review, we evaluated the contribution of different expenditures and losses to total lameness costs. Evaluated expenditures included labor for treatment, therapeutic supplies, lameness detection and lameness control and prevention. Evaluated losses included non-saleable milk, reduced milk production, reduced reproductive performance, increased animal death, increased animal culling, disease interrelationships, lameness recurrence and reduced animal welfare. The previous literature on total lameness cost estimates was also summarized. The reviewed studies indicated that previous estimates of total lameness costs are variable and inconsistent in the expenditures and losses they include. Many of the identified expenditure and loss categories require further research to accurately include in total lameness cost estimates. Future research should focus on identifying costs associated with specific lameness conditions, differing lameness severity levels, and differing stages of lactation at onset of lameness to provide better total lameness cost estimates that can be useful for decision making at both the herd and individual cow level.

  7. [Preliminary analysis of total cost and life quality for elder patients with femoral neck fracture].

    Science.gov (United States)

    Liu, Haonan; He, Liang; Zhang, Guilin; Gong, Xiaofeng; Li, Ning

    2015-09-01

    To analyze the total cost and life quality of the femoral neck fracture patients who received different surgery and supplement comprehensive data of osteoporotic fracture. One hundred and five patients above 60-year old who were diagnosed femoral neck fracture and received operation in Department of Orthopedics & Traumatology, Beijing Jishuitan Hospital were admitted into our study from August 2013 to December. According to the type of surgery there were 52 and 53 cases in internal fixation (IF) group and hemiarthroplasty (HA) group respectively. At first we collected the medical expense of the patients before and during hospitalization. And then the 1-year medical and non-medical expenses were collected by the cost diary ever 3 months after discharge. At the last follow-up we evaluated the life quality by the EuroQol-5 Dimensions (EQ-5D) and calculated the total cost. Outcome All the patients completed the operation successfully. No nonunion or delayed union cases in IF group, and no cases received revision surgery in both groups. The total average cost was 59 584.9 yuan including 79.1% medical cost and 20.9% non-medical cost. The primary treatment cost accounts for 84.1% of the medical cost. The cost for home care accounts for 90.7% of the non-medical care. The total and medical cost of IF group just account for 40.3% and 38.5% of the HA group and the non-medical showed no significant difference between the 2 groups (P>0.05). In addition the data of life quality and walking capability also showed no significant difference. The main cost for the femoral neck fracture is medical expense in 1-year follow-up. Both surgeries can provide satisfactory outcome, however IF may be more cost-effective compared to the HA because of the less total cost.

  8. Resource use and costs associated with opioid-induced constipation following total hip or total knee replacement surgery

    Directory of Open Access Journals (Sweden)

    Wittbrodt ET

    2018-05-01

    Full Text Available Eric T Wittbrodt,1 Tong J Gan,2 Catherine Datto,1 Charles McLeskey,1 Meenal Sinha3 1US Medical Affairs, AstraZeneca, Wilmington, DE, USA; 2Department of Anesthesiology, Stony Brook Medicine, Stony Brook, NY, USA; 3Premier Applied Sciences, Premier, Inc., Charlotte, NC, USA Purpose: Constipation is a well-known complication of surgery that can be exacerbated by opioid analgesics. This study evaluated resource utilization and costs associated with opioid-induced constipation (OIC. Patients and methods: This retrospective, observational, and propensity-matched cohort study utilized the Premier Healthcare Database. The study included adults ≥18 years of age undergoing total hip or total knee replacement as inpatients who received an opioid analgesic and were discharged between January 1, 2012, and June 30, 2015. Diagnosis codes identified patients with OIC who were then matched 1:1 to patients without OIC. Generalized linear and logistic regression models were used to compare inpatient resource utilization, total hospital costs, inpatient mortality, and 30-day all-cause readmissions and emergency department visits. Results: Of 788,448 eligible patients, 40,891 (5.2% had OIC. Covariates were well balanced between matched patients with and without OIC (n=40,890 each. In adjusted analyses, patients with OIC had longer hospital lengths of stay (3.6 versus 3.3 days; p<0.001, higher total hospital costs (US$17,479 versus US$16,265; p<0.001, greater risk of intensive care unit admission (odds ratio [OR]=1.12, 95% CI: 1.01–1.24, and increased likelihood of 30-day hospital readmissions (OR=1.16, 95% CI: 1.11–1.22 and emergency department visits (OR=1.38, 95% CI: 1.07–1.79 than patients without OIC. No statistically significant difference was found with inpatient mortality (OR=0.89, 95% CI: 0.59–1.35. Conclusion: OIC was associated with greater resource utilization and hospital costs for patients undergoing primarily elective total hip or total knee

  9. Cost update technology, safety, and costs of decommissioning a reference uranium hexafluoride conversion plant

    International Nuclear Information System (INIS)

    Miles, T.L.; Liu, Y.

    1995-08-01

    The purpose of this study is to update the cost estimates developed in a previous report, NUREG/CR-1757 (Elder 1980) for decommissioning a reference uranium hexafluoride conversion plant from the original mid-1981 dollars to values representative of January 1993. The cost updates were performed by using escalation factors derived from cost index trends over the past 11.5 years. Contemporary price quotes wee used for costs that have increased drastically or for which is is difficult to find a cost trend. No changes were made in the decommissioning procedures or cost element requirements assumed in NUREG/CR-1757. This report includes only information that was changed from NUREG/CR-1757. Thus, for those interested in detailed descriptions and associated information for the reference uranium hexafluoride conversion plant, a copy of NUREG/CR-1757 will be needed

  10. Using value-based total cost of ownership (TCO) measures to inform subsystem trade-offs

    Science.gov (United States)

    Radziwill, Nicole M.; DuPlain, Ronald F.

    2010-07-01

    Total Cost of Ownership (TCO) is a metric from management accounting that helps expose both the direct and indirect costs of a business decision. However, TCO can sometimes be too simplistic for "make vs. buy" decisions (or even choosing between competing design alternatives) when value and extensibility are more critical than total cost. A three-dimensional value-based TCO, which was developed to clarify product decisions for an observatory prior to Final Design Review (FDR), will be presented in this session. This value-based approach incorporates priority of requirements, satisfiability of requirements, and cost, and can be easily applied in any environment.

  11. Determining the total cost of reverse supply chain operations for original equipment manufacturers

    DEFF Research Database (Denmark)

    Larsen, Samuel Brüning; Jacobsen, Peter

    2014-01-01

    When original equipment manufacturers (OEM) examine whether or not to invest in a reverse supply chain (RSC), managers need insight into not only the cost savings and new revenue streams the RSC enables, but also the total cost of the RSC itself. Using case study research the study examines what...... cost parameters constitute the total cost (TC) of the RSC. The specific RSC that the study seeks the TC for consists of 1) end-product refurbishing, 2) component refurbishing, and 3) sales of used materials back to original suppliers or independent recyclers for materials recycling....

  12. Exogenous application of plant growth regulators increased the total ...

    African Journals Online (AJOL)

    PRECIOUS

    2009-11-02

    Nov 2, 2009 ... the exogenous application of flavonoids reports plant growth regulation ... method used for extraction and quantification of endogenous gibberellins was ... 365 nm) while separation was done on a C18 reverse-phase HPLC.

  13. Formosa Plastics Corporation: Plant-Wide Assessment of Texas Plant Identifies Opportunities for Improving Process Efficiency and Reducing Energy Costs

    Energy Technology Data Exchange (ETDEWEB)

    None

    2005-01-01

    At Formosa Plastics Corporation's plant in Point Comfort, Texas, a plant-wide assessment team analyzed process energy requirements, reviewed new technologies for applicability, and found ways to improve the plant's energy efficiency. The assessment team identified the energy requirements of each process and compared actual energy consumption with theoretical process requirements. The team estimated that total annual energy savings would be about 115,000 MBtu for natural gas and nearly 14 million kWh for electricity if the plant makes several improvements, which include upgrading the gas compressor impeller, improving the vent blower system, and recovering steam condensate for reuse. Total annual cost savings could be $1.5 million. The U.S. Department of Energy's Industrial Technologies Program cosponsored this assessment.

  14. Evaluation of the Total Cost of Ownership of Fuel Cell-Powered Material Handling Equipment

    Energy Technology Data Exchange (ETDEWEB)

    Ramsden, T.

    2013-04-01

    This report discusses an analysis of the total cost of ownership of fuel cell-powered and traditional battery-powered material handling equipment (MHE, or more typically 'forklifts'). A number of fuel cell MHE deployments have received funding support from the federal government. Using data from these government co-funded deployments, DOE's National Renewable Energy Laboratory (NREL) has been evaluating the performance of fuel cells in material handling applications. NREL has assessed the total cost of ownership of fuel cell MHE and compared it to the cost of ownership of traditional battery-powered MHE. As part of its cost of ownership assessment, NREL looked at a range of costs associated with MHE operation, including the capital costs of battery and fuel cell systems, the cost of supporting infrastructure, maintenance costs, warehouse space costs, and labor costs. Considering all these costs, NREL found that fuel cell MHE can have a lower overall cost of ownership than comparable battery-powered MHE.

  15. Variation in the cost of care for primary total knee arthroplasties.

    Science.gov (United States)

    Haas, Derek A; Kaplan, Robert S

    2017-03-01

    The study examined the cost variation across 29 high-volume US hospitals and their affiliated orthopaedic surgeons for delivering a primary total knee arthroplasty without major complicating conditions. The hospitals had similar patient demographics, and more than 80% of them had statistically-similar Medicare risk-adjusted readmission and complication rates. Hospital and physician personnel costs were calculated using time-driven activity-based costing. Consumable supply costs, such as the prosthetic implant, were calculated using purchase prices, and postacute care costs were measured using either internal costs or external claims as reported by each hospital. Despite having similar patient demographics and readmission and complication rates, the average cost of care for total knee arthroplasty across the hospitals varied by a factor of about 2 to 1. Even after adjusting for differences in internal labor cost rates, the hospital at the 90th percentile of cost spent about twice as much as the one at the 10th percentile of cost. The large variation in costs among sites suggests major and multiple opportunities to transfer knowledge about process and productivity improvements that lower costs while simultaneously maintaining or improving outcomes.

  16. Cost-competitive, inherently safe LFMBR pool plant

    International Nuclear Information System (INIS)

    McDonald, J.S.; Brunings, J.E.; Chang, Y.I.; Hren, R.R.; Seidensticker, R.W.

    1984-01-01

    The Cost-Competitive, Inherently Safe LMFBR Pool Plant design was prepared in GFY 1983 under a DOE-sponsored program. This plant design was developed as a joint effort by Rockwell International and the Argonne National Laboratory with major contributions from the Bechtel Group, Inc.; Combustion engineering, Inc.; the Chicago Bridge and Iron Company; and the General Electric Company. Using current LMFBR technology, many innovative features were developed and incorporated into the design to meet the ultimate objectives of the Breeder Program, i.e., energy costs competitive with LWRs and inherent safety features to maintain the plant in a safe condition following assumed accidents without requiring operator action. This paper provides a description of the principal features that were incorporated into the design to achieve low cost and inherent safety

  17. Assessing the high costs of new nuclear power plants

    International Nuclear Information System (INIS)

    Komanoff, C.

    1984-01-01

    The variation in nuclear plant capital costs, both over time and within the current generation of plants, is considerable and is one of the impressive facts associated with that technology. This article concerns statistical methods for determining relative management efficiency or inefficiency in nuclear plant construction. It emphasizes the need to adjust raw cost data for important variables in order to make fair comparisons among disparate projects. The analysis identifies the costliest and least-costly projects and elucidates trends that helped or harmed several or more projects at the same time. Its findings can form a supplement and guide for engineering and management audits of individual nuclear projects. 5 references, 1 figure, 1 table

  18. Cost update: Technology, safety, and costs of decommissioning a reference uranium fuel fabrication plant

    International Nuclear Information System (INIS)

    Miles, T.L.; Liu, Y.

    1994-06-01

    The cost estimates originally developed in NUREG/CR-1266 for commissioning a reference low-enrichment uranium fuel fabrication plant are updated from 1978 to early 1993 dollars. During this time, the costs for labor and materials increased approximately at the rate of inflation, the cost of energy increased more slowly than the rate of inflation, and the cost of low-level radioactive waste disposal increased much more rapidly than the rate of inflation. The results of the analysis indicate that the estimated costs for the immediate dismantlement and decontamination for unrestricted facility release (DECON) of the reference plant have increased from the mid-1978 value of $3.57 million to $8.08 million in 1993 with in-compact low-level radioactive waste disposal at the US Ecoloay facility near Richland, Washington. The cost estimate rises to $19.62 million with out-of-compact radioactive waste disposal at the Chem-Nuclear facility near Barnwell, South Carolina. A methodology and a formula are presented for estimating the cost of decommissioning the reference uranium fuel fabrication plant at some future time, based on these early 1993 cost estimates. The formula contains essentially the same elements as the formula given in 10 CFR 50.75 for escalating the decommissioning costs for nuclear power reactors to some future time

  19. Development of Advanced Technologies to Reduce Design, Fabrication and Construction Costs for Future Nuclear Power Plants

    International Nuclear Information System (INIS)

    DiNunzio, Camillo A.; Gupta, Abhinav; Golay, Michael; Luk, Vincent; Turk, Rich; Morrow, Charles; Geum-Taek Jin

    2002-01-01

    OAK-B135 This report presents a summation of the third and final year of a three-year investigation into methods and technologies for substantially reducing the capital costs and total schedule for future nuclear plants. In addition, this is the final technical report for the three-year period of studies

  20. Development of Advanced Technologies to Reduce Design, Fabrication and Construction Costs for Future Nuclear Power Plants

    Energy Technology Data Exchange (ETDEWEB)

    DiNunzio, Camillo A. [Framatome ANP DE& S, Marlborough, MA (United States); Gupta, Abhinav [Univ. of North Carolina, Raleigh, NC (United States); Golay, Michael [Massachusetts Inst. of Technology (MIT), Cambridge, MA (United States); Luk, Vincent [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States); Turk, Rich [Westinghouse Electric Company Nuclear Systems, Windsor, CT (United States); Morrow, Charles [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States); Jin, Geum-Taek [Korea Power Engineering Company Inc., Yongin-si, Gyeonggi-do (Korea, Republic of)

    2002-11-30

    This report presents a summation of the third and final year of a three-year investigation into methods and technologies for substantially reducing the capital costs and total schedule for future nuclear plants. In addition, this is the final technical report for the three-year period of studies.

  1. Preliminary estimates of the total-system cost for the restructured program: An addendum to the May 1989 analysis of the total-system life cycle cost for the Civilian Radioactive Waste Management Program

    International Nuclear Information System (INIS)

    1990-12-01

    The total-system life-cycle cost (TSLCC) analysis for the Department of Energy's (DOE) Civilian Radioactive Waste Management Program is an ongoing activity that helps determine whether the revenue-producing mechanism established by the Nuclear Waste Policy Act of 1982 - a fee levied on electricity generated and sold by commercial nuclear power plants - is sufficient to cover the cost of the program. This report provides cost estimates for the sixth annual evaluation of the adequacy of the fee. The costs contained in this report represent a preliminary analysis of the cost impacts associated with the Secretary of Energy's Report to Congress on Reassessment of the Civilian Radioactive Waste Management Program issued in November 1989. The major elements of the restructured program announced in this report which pertain to the program's life-cycle costs are: a prioritization of the scientific investigations program at the Yucca Mountain candidate site to focus on identification of potentially adverse conditions, a delay in the start of repository operations until 2010, the start of limited waste acceptance at the monitored retrievable storage (MRS) facility in 1998, and the start of waste acceptance at the full-capability MRS facility in 2,000. Based on the restructured program, the total-system cost for the system with a repository at the candidate site at Yucca Mountain in Nevada, a facility for monitored retrievable storage (MRS), and a transportation system is estimated at $26 billion (expressed in constant 1988 dollars). In the event that a second repository is required and is authorized by the Congress, the total-system cost is estimated at $34 to $35 billion, depending on the quantity of spent fuel and high-level waste (HLW) requiring disposal. 17 figs., 17 tabs

  2. A Deterministic and Probabilistic Cost Estimate for Nuclear Power Plants

    International Nuclear Information System (INIS)

    Ha, Gag Kyeon; Kwon, Jong Jooh

    2005-01-01

    There are many cost estimate methodologies for some future projects. Revenue Requirement Method (RRM), Cost/Benefit Ratio method, Return on Investment, Pay Back Period Method. etc. This paper uses the RRM method which is the amount of revenue that must be collected from customers to compensate a utility for all expenditures associated with implementing an alternative decision involving money. This RRM can be combined with a random sampling statistical simulation computer program to calculated the Probability Distribution Functions(PDF) of the cost elements for generating cost. EPRI developed this combined statistical techniques into RRM, named Statistical Revenue Requirement Method(SRRM). The statistical technique is a random sampling statistical simulation. The simulation tool is usually Monte Carlo sampling, Latin Latin Hypercube sampling, etc. SRRM is used to estimating for future power plants, apartments, hospital, marketing, etc. In this paper, RRM calculation and SRRM simulation have been practiced for PWR1400MWe nuclear power plants

  3. Electric plant cost and power production expenses 1990

    International Nuclear Information System (INIS)

    1992-06-01

    Electric Plant Cost and Power Production Expenses is prepared by the Survey Management Division; Office of Coal, Nuclear, Electric and Alternate Fuels, Energy Information Administration (EIA); US Department of Energy. This publication presents electric utility statistics on power production expenses and construction costs of electric generating plants. Data presented here are intended to provide information to the electric utility industry, educational institutions, Federal, State, and local governments, and the general public. These data are collected and published to fulfill data collection and dissemination responsibilities of the Energy Information Administration (EIA), as specified in the Federal Energy Administration Act (Public Law 93-275), as amended

  4. Electric plant cost and power production expenses 1991

    International Nuclear Information System (INIS)

    1993-01-01

    Electric Plant Cost and Power Production Expenses is prepared by the Survey Management Division; Office of Coal, Nuclear, Electric and Alternate Fuels (CNEAF); Energy Information Administration (EIA); US Department of Energy. This publication presents electric utility statistics on power production expenses and construction costs of electric generating plants. Data presented here are intended to provide information to the electric utility industry, educational institutions, Federal, State, and local governments, and the general public. These data are collected and published to fulfill data collection and dissemination responsibilities of the Energy Information Administration (EIA), as specified in the Federal Energy Administration Act (Public Law 93-275), as amended

  5. Solid municipal waste processing plants: Cost benefit analysis

    International Nuclear Information System (INIS)

    Gerardi, V.

    1992-01-01

    This paper performs cost benefit analyses on three solid municipal waste processing alternatives with plants of diverse daily outputs. The different processing schemes include: selected wastes incineration with the production of refuse derived fuels; selected wastes incineration with the production of refuse derived fuels and compost; pyrolysis with energy recovery in the form of electric power. The plant daily outputs range from 100 to 300 tonnes for the refuse derived fuel alternatives, and from 200 to 800 tonnes for the pyrolysis/power generation scheme. The cost analyses consider investment periods of fifteen years in duration and interest rates of 5%

  6. Cost effective snubber reduction program for nuclear power plants

    International Nuclear Information System (INIS)

    Adams, T.M.; Antaki, G.A.; Chang, K.C.

    1985-01-01

    Due to the stringent seismic requirements imposed on nuclear power plants, piping engineers have resorted to the extensive use of snubbers to support nuclear piping systems. The advantage of snubbers is that they provide dynamic restraint while allowing free thermal growth of the pipe. Unfortunately, as more plants go into operation, utilities have to face the costs of strict in-service inspection requirements and risks of unscheduled or extended plant outages associated with snubber failures. The snubber inspection requirements, defined in plant Technical Specifications, require periodic visual inspections of all snubbers and functional tests of a percentage of the plant snubbers, during refueling outages. For a typical 1000 Mw unit this represents from 50 to several hundred snubbers to be functionally tested at each refueling outage. Should failures occur during testing, the sample size must be further increased. Very quickly the costs and risks of extended shutdowns have led the industry to consider, and in many cases implement, snubber reduction programs. At the same time several changes in seismic design criteria have greatly facilitated the reduction of snubbers, making snubber elimination economically and technically attractive. In this paper we examine the costs and benefits of snubber reduction programs and propose a method for evaluating their cost benefits

  7. Cost benefit justification of nuclear plant reliability improvement

    International Nuclear Information System (INIS)

    El-Sayed, M.A.H.; Abdelmonem, N.M.

    1985-01-01

    The design of the secondary steam loop of the nuclear power plant has a significant effect on the reliability of the plant. Moreover, the necessity to cool a reactor safely has increased the reliability demanded from the system. The rapidly rising construction costs and fuel prices in recent years have stimulated a great deal in optimizing the productivity of a nuclear power plant through reliability improvement of the secondary steamloop and the reactor cooling system. A method for evaluating the reliability of steam loop and cooling system of a nuclear power plant is presented. The method utilizes the cut-set technique. The developed method can be easily used to show to what extent the overall reliability of the nuclear plant is affected by the possible failures in the steam and cooling subsystem. A model for calculating the increase in the nuclear plant productivity resulting from a proposed improvement in the two subsystems reliability is discussed. The model takes into account the capital cost of spare parts for several components, replacement energy, operating and maintenance costs

  8. Total life-cycle cost analysis of conventional and alternative fueled vehicles

    International Nuclear Information System (INIS)

    Cardullo, M.W.

    1993-01-01

    Total Life-Cycle Cost (TLCC) Analysis can indicate whether paying higher capital costs for advanced technology with low operating and/or environmental costs is advantageous over paying lower capital costs for conventional technology with higher operating and/or environmental costs. While minimizing total life-cycle cost is an important consideration, the consumer often identifies non-cost-related benefits or drawbacks that make more expensive options appear more attractive. The consumer is also likely to heavily weigh initial capital costs while giving limited consideration to operating and/or societal costs, whereas policy-makers considering external costs, such as those resulting from environmental impacts, may reach significantly different conclusions about which technologies are most advantageous to society. This paper summarizes a TLCC model which was developed to facilitate consideration of the various factors involved in both individual and societal policy decision making. The model was developed as part of a US Department of Energy Contract and has been revised to reflect changes necessary to make the model more realistic. The model considers capital, operating, salvage, and environmental costs for cars, vans, and buses using conventional and alternative fuels. The model has been developed to operate on an IBM or compatible personal computer platform using the commercial spreadsheet program MicroSoft Excell reg-sign Version 4 for Windows reg-sign and can be easily kept current because its modular structure allows straightforward access to embedded data sets for review and update

  9. Reduction of Total Ownership Costs (R-TOC) Best Practices Guide

    National Research Council Canada - National Science Library

    Reed, Danny

    2003-01-01

    The purpose of the Reduction of Total Ownership Costs (R-TOC) program is to achieve readiness improvements in weapon systems by improving the reliability of the systems or the efficiency of the processes used to support...

  10. Do illness rating systems predict discharge location, length of stay, and cost after total hip arthroplasty?

    Directory of Open Access Journals (Sweden)

    Sarah E. Rudasill, BA

    2018-06-01

    Conclusions: These findings suggest that although ASA classifications predict discharge location and SOI scores predict length of stay and total costs, other factors beyond illness rating systems remain stronger predictors of discharge for THA patients.

  11. Minimizing total costs of forest roads with computer-aided design ...

    Indian Academy of Sciences (India)

    imum total road costs, while conforming to design specifications, environmental ..... quality, and enhancing fish and wildlife habitat, an appropriate design ..... Soil, Water and Timber Management: Forest Engineering Solutions in Response to.

  12. Managing the Cost of Plant Piping System Leakage

    International Nuclear Information System (INIS)

    Jenco, John M.; Keck, Donna R.; Johnson, Gary L.

    2002-01-01

    Recent studies have shown that the average annual cost impact of external piping system leakage on commercial nuclear plant operations and maintenance can easily range into the millions of dollars for each reactor unit. Evidence suggests that this significant O and M cost reduction opportunity has largely been overlooked, due to the number of diverse line items and budget areas affected. Results released last year from an EPRI pilot study of more than a dozen reactor units at seven plant sites operated by multiple utilities found that the average annual cost impact was indeed around $1.6 million per year per unit. Subsequent field experience has also demonstrated that an effective fluid leak management program can substantially reduce these costs within the first three years of implementation. This paper presents the general cost impact research results from various studies, outlines key elements of an effective plant fluid leak management program, discusses important implementation issues, and presents results from case studies covering different utility approaches to developing and implementing an effective fluid leak management program. Actual cost data will be included where appropriate. (authors)

  13. Use of predefined biochemical admission profiles does not reduce the number of tests or total cost

    DEFF Research Database (Denmark)

    Pareek, Manan; Haidl, Felix; Folkestad, Lars

    2014-01-01

    The objective of this pilot study was to evaluate whether the use of predefined biochemical profiles as an alternative to individually ordered blood tests by the treating physicians resulted in fewer tests or a lower total cost.......The objective of this pilot study was to evaluate whether the use of predefined biochemical profiles as an alternative to individually ordered blood tests by the treating physicians resulted in fewer tests or a lower total cost....

  14. Cost-benefit analysis for combined heat and power plant

    International Nuclear Information System (INIS)

    Sazdovski, Ace; Fushtikj, Vangel

    2004-01-01

    The paper presents a methodology and practical application of Cost-Benefit Analysis for Combined Heat and Power Plant (Cogeneration facility). Methodology include up-to-date and real data for cogeneration plant in accordance with the trends ill development of the CHP technology. As a case study a CHP plant that could be built-up in Republic of Macedonia is analyzed. The main economic parameters for project evaluation, such as NPV and IRR are calculated for a number of possible scenarios. The analyze present the economic outputs that could be used as a decision for CHP project acceptance for investment. (Author)

  15. Comparative cost analyses: total flow vs other power conversion systems for the Salton Sea Geothermal Resource

    Energy Technology Data Exchange (ETDEWEB)

    Wright, G.W.

    1978-09-18

    Cost studies were done for Total Flow, double flash, and multistage flash binary systems for electric Energy production from the Salton Sea Geothermal Resource. The purpose was to provide the Department of energy's Division of Geothermal Energy with information by which to judge whether to continue development of the Total Flow system. Results indicate that the Total Flow and double flash systems have capital costs of $1,135 and $1,026 /kW with energy costs of 40.9 and 39.7 mills/kW h respectively. The Total Flow and double flash systems are not distinguishable on a cost basis alone; the multistage flash binary system, with capital cost of $1,343 /kW and energy cost of 46.9 mills/kW h, is significantly more expensive. If oil savings are considered in the total analysis, the Total Flow system could save 30% more oil than the double flash system, $3.5 billion at 1978 oil prices.

  16. Recognition of the Environmental Costs of Fossil Fuel Plants

    Directory of Open Access Journals (Sweden)

    Hakkı FINDIK

    2015-12-01

    Full Text Available Environment that is the natural residential area of live life is among the interests of the various sciences. Within the scope of accounting science, the concept of social awareness requires a social responsibility based approach and this causes some additional environmental costs emerged when interaction of business with their environment considered. In the Uniform Accounting Plan there exists a special account relating with monitoring, controlling and managing of environmental costs. This study deals with environmental accounting for enterprises and introduces determination and recognition of the environmental costs of fossil fuel plants that use coal as a fuel

  17. Technology and costs for decommissioning of Swedish nuclear power plants

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1994-06-01

    The decommissioning study for the Swedish nuclear power plants has been carried out during 1992 to 1994 and the work has been led by a steering group consisting of people from the nuclear utilities and SKB. The study has been focused on two reference plants, Oskarshamn 3 and Ringhals 2. Oskarshamn 3 is a boiling water reactor (BWR) and Ringhals 2 is a pressurized water reactor (PWR). Subsequently, the result from these plants have been translated to the other Swedish plants. The study gives an account of the procedures, costs, waste quantities and occupational doses associated with decommissioning of the Swedish nuclear power plants. Dismantling is assumed to start immediately after removal of the spent fuel. No attempts at optimization, in terms of technology or costs, have been made. The nuclear power plant site is restored after decommissioning so that it can be released for use without restriction for other industrial activities. The study shows that a reactor can be dismantled in about five years, with an average labour force of about 150 persons. The maximum labour force required for Oskarshamn 3 has been estimated to about 300 persons. This peak load occurred the first years but is reduced to about 50 persons during the demolishing of the buildings. The cost of decommissioning Oskarshamn 3 has been estimated to be about MSEK 940 in January 1994 prices. The decommissioning of Ringhals 2 has been estimated to be MSEK 640. The costs for the other Swedish nuclear power plants lie in the range MSEK 590-960. 17 refs, 21 figs, 15 tabs.

  18. Technology and costs for decommissioning of Swedish nuclear power plants

    International Nuclear Information System (INIS)

    1994-06-01

    The decommissioning study for the Swedish nuclear power plants has been carried out during 1992 to 1994 and the work has been led by a steering group consisting of people from the nuclear utilities and SKB. The study has been focused on two reference plants, Oskarshamn 3 and Ringhals 2. Oskarshamn 3 is a boiling water reactor (BWR) and Ringhals 2 is a pressurized water reactor (PWR). Subsequently, the result from these plants have been translated to the other Swedish plants. The study gives an account of the procedures, costs, waste quantities and occupational doses associated with decommissioning of the Swedish nuclear power plants. Dismantling is assumed to start immediately after removal of the spent fuel. No attempts at optimization, in terms of technology or costs, have been made. The nuclear power plant site is restored after decommissioning so that it can be released for use without restriction for other industrial activities. The study shows that a reactor can be dismantled in about five years, with an average labour force of about 150 persons. The maximum labour force required for Oskarshamn 3 has been estimated to about 300 persons. This peak load occurred the first years but is reduced to about 50 persons during the demolishing of the buildings. The cost of decommissioning Oskarshamn 3 has been estimated to be about MSEK 940 in January 1994 prices. The decommissioning of Ringhals 2 has been estimated to be MSEK 640. The costs for the other Swedish nuclear power plants lie in the range MSEK 590-960. 17 refs, 21 figs, 15 tabs

  19. Estimation of environmental external costs between coal fired power plant and nuclear power plant

    International Nuclear Information System (INIS)

    Moon, G. H.; Kim, S. S.

    2000-01-01

    First of all, this study evaluated the impacts on the health and the environment of air pollutants emitted from coal power plant and nuclear power pant, two major electric power generating options in Korea. Then, the environmental external costs of those two options were estimated by transforming the health and environment impact into monetary values. To do this, AIRPACTS and Impacts of Atmospheric Release model developed by IAEA were used. The environmental external cost of Samcheonpo coal power plant was estimated about 25 times as much as that of Younggwang nuclear power plant. This result implies that nuclear power plant is a clean technology compared with coal power plant. This study suggests that the external cost should be reflected in the electric system expansion plan in order to allocate energy resources efficiently and to reduce economic impact stemming from the environmental regulation emerged recently on a global level

  20. Cost benefit analysis of power plant database integration

    International Nuclear Information System (INIS)

    Wilber, B.E.; Cimento, A.; Stuart, R.

    1988-01-01

    A cost benefit analysis of plant wide data integration allows utility management to evaluate integration and automation benefits from an economic perspective. With this evaluation, the utility can determine both the quantitative and qualitative savings that can be expected from data integration. The cost benefit analysis is then a planning tool which helps the utility to develop a focused long term implementation strategy that will yield significant near term benefits. This paper presents a flexible cost benefit analysis methodology which is both simple to use and yields accurate, verifiable results. Included in this paper is a list of parameters to consider, a procedure for performing the cost savings analysis, and samples of this procedure when applied to a utility. A case study is presented involving a specific utility where this procedure was applied. Their uses of the cost-benefit analysis are also described

  1. Interior West community tree guide: benefits, costs, and strategic planting

    Science.gov (United States)

    Kelaine E. Vargas; Gregory E. McPherson; James R. Simpson; Paula J. Peper; Shelley L. Gardner; Qingfu. Xiao

    2007-01-01

    Even as they increase the beauty of our surroundings, trees provide us with a great many ecosystem services, including air quality improvement, energy conservation, stormwater interception, and atmospheric carbon dioxide reduction. These benefits must be weighed against the costs of maintaining trees, including planting, pruning, irrigation, administration, pest...

  2. Central Florida community tree guide: benefits, costs, and strategic planting

    Science.gov (United States)

    Paula J. Peper; E. Gregory McPherson; James R. Simpson; Shannon N. Albers; Qingfu Xiao

    2010-01-01

    Trees make our cities more attractive and provide many ecosystem services, including air quality improvement, energy conservation, stormwater interception, and atmospheric carbon dioxide reduction. These benefits must be weighed against the costs of maintaining trees, including planting, pruning, irrigation, administration, pest control, liability, cleanup, and removal...

  3. Desert Southwest Community Tree Guide: Benefits, Costs and Strategic Planting

    Science.gov (United States)

    Greg McPherson; J.R. Simpson; P.J. Peper; S.E. Maco; Q. Xiao; E. Mulrean

    2004-01-01

    This report quantifies benefits and costs for typical large-, medium-, small-stature, deciduous trees (Fraxinus uhdei, Prosopis chilensis, Acacia farnesiana), as well as a conifer (Pinus halapensis). The analysis assumed that trees were planted in a residential yard site or a public (street/park) site, a 40-year time frame, and...

  4. Lower Midwest community tree guide: benefits, costs, and strategic planting

    Science.gov (United States)

    Paula J. Peper; E. Gregory McPherson; James R. Simpson; Kelaine E. Vargas; Qingfu Xiao

    2009-01-01

    Even as they increase the beauty of our surroundings, trees provide us with a great many ecosystem services, including air quality improvement, energy conservation, stormwater interception, and atmospheric carbon dioxide reduction. These benefits must be weighed against the costs of maintaining trees, including planting, pruning, irrigation, administration, pest...

  5. Tropical community tree guide: benefits, costs, and strategic planting

    Science.gov (United States)

    Kelaine E. Vargas; Gregory E. McPherson; James R. Simpson; Paula J. Peper; Shelley L. Gardner; Qingfu Xiao

    2008-01-01

    Even as they increase the beauty of our surroundings, trees provide us with a great many ecosystem services, including air quality improvement, energy conservation, stormwater interception, and atmospheric carbon dioxide reduction. These benefits must be weighed against the costs of maintaining trees, including planting, pruning, irrigation, administration, pest...

  6. Midwest community tree guide: benefits, costs, and strategic planting

    Science.gov (United States)

    E. Gregory McPherson; James R. Simpson; Paula J. Peper; Scott E. Maco; Shelley L. Gardner; Shauna K. Cozad; Qingfu Xiao

    2006-01-01

    This report quantifies benefits and costs for typical small, medium, and large deciduous (losing their leaves every autumn) trees: crabapple, red oak, and hackberry (see "Common and Scientific Names" section). The analysis assumed that trees were planted in a residential yard or public site (streetside or park) with a 60 percent survival rate over a 40-year...

  7. Northeast community tree guide: benefits, costs, and strategic planting

    Science.gov (United States)

    E. Gregory McPherson; James R. Simpson; Paula J. Peper; Shelley L. Gardner; Kelaine E. Vargas; Qingfu Xiao

    2007-01-01

    Trees make our cities more attractive and provide many ecosystem services, including air quality improvement, energy conservation, stormwater interception, and atmospheric carbon dioxide reduction. These benefits must be weighed against the costs of maintaining trees, including planting, pruning, irrigation, administration, pest control, liability, cleanup, and removal...

  8. Cost and quality of fuels for electric utility plants, 1994

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-07-14

    This document presents an annual summary of statistics at the national, Census division, State, electric utility, and plant levels regarding the quantity, quality, and cost of fossil fuels used to produce electricity. Purpose of this publication is to provide energy decision-makers with accurate, timely information that may be used in forming various perspectives on issues regarding electric power.

  9. Life Cycle Cost Analysis of Ready Mix Concrete Plant

    Science.gov (United States)

    Topkar, V. M.; Duggar, A. R.; Kumar, A.; Bonde, P. P.; Girwalkar, R. S.; Gade, S. B.

    2013-11-01

    India, being a developing nation is experiencing major growth in its infrastructural sector. Concrete is the major component in construction. The requirement of good quality of concrete in large quantities can be fulfilled by ready mix concrete batching and mixing plants. The paper presents a technique of applying the value engineering tool life cycle cost analysis to a ready mix concrete plant. This will help an investor or an organization to take investment decisions regarding a ready mix concrete facility. No economic alternatives are compared in this study. A cost breakdown structure is prepared for the ready mix concrete plant. A market survey has been conducted to collect realistic costs for the ready mix concrete facility. The study establishes the cash flow for the ready mix concrete facility helpful in investment and capital generation related decisions. Transit mixers form an important component of the facility and are included in the calculations. A fleet size for transit mixers has been assumed for this purpose. The life cycle cost has been calculated for the system of the ready mix concrete plant and transit mixers.

  10. Cost of Radiotherapy Versus NSAID Administration for Prevention of Heterotopic Ossification After Total Hip Arthroplasty

    International Nuclear Information System (INIS)

    Strauss, Jonathan B.; Chen, Sea S.; Shah, Anand P.; Coon, Alan B.; Dickler, Adam

    2008-01-01

    Purpose: Heterotopic ossification (HO), or abnormal bone formation, is a common sequela of total hip arthroplasty. This abnormal bone can impair joint function and must be surgically removed to restore mobility. HO can be prevented by postoperative nonsteroidal anti-inflammatory drug (NSAID) use or radiotherapy (RT). NSAIDs are associated with multiple toxicities, including gastrointestinal bleeding. Although RT has been shown to be more efficacious than NSAIDs at preventing HO, its cost-effectiveness has been questioned. Methods and Materials: We performed an analysis of the cost of postoperative RT to the hip compared with NSAID administration, taking into account the costs of surgery for HO formation, treatment-induced morbidity, and productivity loss from missed work. The costs of RT, surgical revision, and treatment of gastrointestinal bleeding were estimated using the 2007 Medicare Fee Schedule and inpatient diagnosis-related group codes. The cost of lost wages was estimated using the 2006 median salary data from the U.S. Census Bureau. Results: The cost of administering RT was estimated at $899 vs. $20 for NSAID use. After accounting for the additional costs associated with revision total hip arthroplasty and gastrointestinal bleeding, the corresponding estimated costs were $1,208 vs. $930. Conclusion: If the costs associated with treatment failure and treatment-induced morbidity are considered, the cost of NSAIDs approaches that of RT. Other NSAID morbidities and quality-of-life differences that are difficult to quantify add to the cost of NSAIDs. These considerations have led us to recommend RT as the preferred modality for use in prophylaxis against HO after total hip arthroplasty, even when the cost is considered

  11. Time-driven activity based costing of total knee replacement surgery at a London teaching hospital.

    Science.gov (United States)

    Chen, Alvin; Sabharwal, Sanjeeve; Akhtar, Kashif; Makaram, Navnit; Gupte, Chinmay M

    2015-12-01

    The aim of this study was to conduct a time-driven activity based costing (TDABC) analysis of the clinical pathway for total knee replacement (TKR) and to determine where the major cost drivers lay. The in-patient pathway was prospectively mapped utilising a TDABC model, following 20 TKRs. The mean age for these patients was 73.4 years. All patients were ASA grade I or II and their mean BMI was 30.4. The 14 varus knees had a mean deformity of 5.32° and the six valgus knee had a mean deformity of 10.83°. Timings were prospectively collected as each patient was followed through the TKR pathway. Pre-operative costs including pre-assessment and joint school were £ 163. Total staff costs for admission and the operating theatre were £ 658. Consumables cost for the operating theatre were £ 1862. The average length of stay was 5.25 days at a total cost of £ 910. Trust overheads contributed £ 1651. The overall institutional cost of a 'noncomplex' TKR in patients without substantial medical co-morbidities was estimated to be £ 5422, representing a profit of £ 1065 based on a best practice tariff of £ 6487. The major cost drivers in the TKR pathway were determined to be theatre consumables, corporate overheads, overall ward cost and operating theatre staffing costs. Appropriate discounting of implant costs, reduction in length of stay by adopting an enhanced recovery programme and control of corporate overheads through the use of elective orthopaedic treatment centres are proposed approaches for reducing the overall cost of treatment. Copyright © 2015 Elsevier B.V. All rights reserved.

  12. [Fuel Rod Consolidation Project]: The estimated total life cycle cost for the 30-year operation of prototypical consolidation demonstration equipment: Volume 4, Phase 2

    International Nuclear Information System (INIS)

    1987-01-01

    The Total Life Cycle Costs have been developed for the construction, operation and decommissioning of a single line of hot-cell-enclosed production consolidation equipment operating on spent fuel at the rate of 750 MTU/year for 30 years. The cost estimate is for a single production line that is part of an overall facility at either a Monitored Retrievable Storage or a Repository facility. This overall facility would include other capabilities and possibly other consolidation lines. However, no costs were included in the cost estimate for other portions of the plant, except that staff costs include an overhead charge that reflects the overhead support services in an overall facility

  13. Decommissioning nuclear power plants. Policies, strategies and costs

    International Nuclear Information System (INIS)

    2003-01-01

    The decommissioning of nuclear power plants is a topic of increasing interest to governments and the industry as many nuclear units approach retirement. It is important in this context to assess decommissioning costs and to ensure that adequate funds are set aside to meet future financial liabilities arising after nuclear power plants are shut down. Furthermore, understanding how national policies and industrial strategies affect those costs is essential for ensuring the overall economic effectiveness of the nuclear energy sector. This report, based upon data provided by 26 countries and analysed by government and industry experts, covers a variety of reactor types and sizes. The findings on decommissioning cost elements and driving factors in their variance will be of interest to analysts and policy makers in the nuclear energy field. (author)

  14. Reduction of capital costs of nuclear power plants. NEA-report

    International Nuclear Information System (INIS)

    2000-01-01

    Since the the mid-1980s, the declining real prices of fossil fuels and the significant improvements in thermal efficiencies of combined cycle power plants have eroded the economic competitiveness of nuclear power plants in most OECD countries. In order for nuclear power to remain a viable option for the next millennium, the cost of electricity from nuclear power plant must be greatly reduced to be competitive with alternative sources. Of the three major components of nuclear generation cost - capital, O and M and fuel - the capital cost component makes up approximately 60 per cent of the total. Therefore, identification of the means to reduce the capital costs of nuclear power plants is a high priority activity toward keeping nuclear power competitive. Among a number of capital cost reduction measures, the principal ones were agreed by the expert group as follows: Increased plant size, improved construction methods, reduced construction schedule, design improvement, improved procurement, organisation and contractual aspects, standardisation and construction in series, multiple unit construction, regulatory and policy reform. (orig.)

  15. Technology and costs for decommissioning the Swedish nuclear power plants

    International Nuclear Information System (INIS)

    1986-05-01

    The study shows that, from the viewpoint of radiological safety, a nuclear power plant can be dismantled immediately after it has been shut down and the fuel has been removed, which is estimated to take about one year. Most of the equipment that will be used in decommissioning is already available and is used routinely in maintenance and rebuilding work at the nuclear power plants. Special equipment need only be developed for dismantlement of the reactor vessel and for demolishing of heavy concrete structures. The dismantling of a nuclear power plant can be accomplished in about five years, with an average labour force of about 200 men. The maximum labour force required for Ringhals 1 has been estimated at about 500 men during the first years, when active systems are being dismantled in a number of fronts in the plant. During the last years when the buildings are being demolished, approximately 50 men are required. In order to limit the labour requirement and the dose burden to the personnel, the material is taken out in as large pieces as possible. The cost of decommissioning a boiling water reactor (BWR) of the size of Ringhals 1 has been estimated to be about MSEK 540 in January 1986 prices, and for a pressurized water reactor (PWR, Ringhals 2) about MSEK 460. The cost for the other Swedish nuclear power plants lie in the range of MSEK 410-760. These are the direct cost for the decommissioning work, to which must be added the costs of transportation and disposal of the decommissioning waste, about 100 000 m/sup3/. These costs have been estimated to be about MSEK 600 for the 12 Swedish reactors. (author)

  16. The Relation of Design Parameters, Plant Capacity and Processing Costs in Cobalt-60 Sterilization Plants

    International Nuclear Information System (INIS)

    Brown, M.G.

    1967-01-01

    The paper describes the main features of three basic types of cobalt-60 sterilization plants which have been designed to provide a complete range of capacities for radiosterilization of medical products. The smallest plant has a capacity of up to 50 000 cubic feet of medical products a year, the intermediate size plant has a capacity of up to 500 000 cubic feet a year, and the largest plant has a capacity in excess of 1000 000 cubic feet a year. The relations between capital costs, rate of production, efficiency and unit processing costs for each type of plant are discussed. The method of selecting the best type of plant for a particular need will also be outlined. (author)

  17. Pre-fracture individual characteristics associated with high total health care costs after hip fracture.

    Science.gov (United States)

    Schousboe, J T; Paudel, M L; Taylor, B C; Kats, A M; Virnig, B A; Dowd, B E; Langsetmo, L; Ensrud, K E

    2017-03-01

    Older women with pre-fracture slow walk speed, high body mass index, and/or a high level of multimorbidity have significantly higher health care costs after hip fracture compared to those without those characteristics. Studies to investigate if targeted health care interventions for these individuals can reduce hip fracture costs are warranted. The aim of this study is to estimate the associations of individual pre-fracture characteristics with total health care costs after hip fracture, using Study of Osteoporotic Fractures (SOF) cohort data linked to Medicare claims. Our study population was 738 women age 70 and older enrolled in Medicare Fee for Service (FFS) who experienced an incident hip fracture between January 1, 1992 and December 31, 2009. We assessed pre-fracture individual characteristics at SOF study visits and estimated costs of hospitalizations, skilled nursing facility and inpatient rehabilitation stays, home health care visits, and outpatient utilization from Medicare FFS claims. We used generalized linear models to estimate the associations of predictor variables with total health care costs (2010 US dollars) after hip fracture. Median total health care costs for 1 year after hip fracture were $35,536 (inter-quartile range $24,830 to $50,903). Multivariable-adjusted total health care costs for 1 year after hip fracture were 14 % higher ($5256, 95 % CI $156 to $10,356) in those with walk speed total health care costs after hip fracture in older women. Studies to investigate if targeted health care interventions for these individuals can reduce the costs of hip fractures are warranted.

  18. Evaluating Methods for Isolating Total RNA and Predicting the Success of Sequencing Phylogenetically Diverse Plant Transcriptomes

    Science.gov (United States)

    Bruskiewich, Richard; Burris, Jason N.; Carrigan, Charlotte T.; Chase, Mark W.; Clarke, Neil D.; Covshoff, Sarah; dePamphilis, Claude W.; Edger, Patrick P.; Goh, Falicia; Graham, Sean; Greiner, Stephan; Hibberd, Julian M.; Jordon-Thaden, Ingrid; Kutchan, Toni M.; Leebens-Mack, James; Melkonian, Michael; Miles, Nicholas; Myburg, Henrietta; Patterson, Jordan; Pires, J. Chris; Ralph, Paula; Rolf, Megan; Sage, Rowan F.; Soltis, Douglas; Soltis, Pamela; Stevenson, Dennis; Stewart, C. Neal; Surek, Barbara; Thomsen, Christina J. M.; Villarreal, Juan Carlos; Wu, Xiaolei; Zhang, Yong; Deyholos, Michael K.; Wong, Gane Ka-Shu

    2012-01-01

    Next-generation sequencing plays a central role in the characterization and quantification of transcriptomes. Although numerous metrics are purported to quantify the quality of RNA, there have been no large-scale empirical evaluations of the major determinants of sequencing success. We used a combination of existing and newly developed methods to isolate total RNA from 1115 samples from 695 plant species in 324 families, which represents >900 million years of phylogenetic diversity from green algae through flowering plants, including many plants of economic importance. We then sequenced 629 of these samples on Illumina GAIIx and HiSeq platforms and performed a large comparative analysis to identify predictors of RNA quality and the diversity of putative genes (scaffolds) expressed within samples. Tissue types (e.g., leaf vs. flower) varied in RNA quality, sequencing depth and the number of scaffolds. Tissue age also influenced RNA quality but not the number of scaffolds ≥1000 bp. Overall, 36% of the variation in the number of scaffolds was explained by metrics of RNA integrity (RIN score), RNA purity (OD 260/230), sequencing platform (GAIIx vs HiSeq) and the amount of total RNA used for sequencing. However, our results show that the most commonly used measures of RNA quality (e.g., RIN) are weak predictors of the number of scaffolds because Illumina sequencing is robust to variation in RNA quality. These results provide novel insight into the methods that are most important in isolating high quality RNA for sequencing and assembling plant transcriptomes. The methods and recommendations provided here could increase the efficiency and decrease the cost of RNA sequencing for individual labs and genome centers. PMID:23185583

  19. The Relationship between Cost Leadership Strategy, Total Quality Management Applications and Financial Performance

    Directory of Open Access Journals (Sweden)

    Ali KURT

    2016-03-01

    Full Text Available Firms need to implement some competition strategies and total quality management applications to overcome the fierce competition among others. The purpose of this study is to show the relationship between cost leadership strategy, total quality management applications and firms’ financial performance with literature review and empirical analysis. 449 questionnaires were conducted to the managers of 142 big firms. The data gathered was assessed with AMOS. As a result, the relationship between cost leadership strategy, total quality management applications and firms’ financial performance has been gathered. In addition, the relationship between TQM applications and financial performance has also been gathered.

  20. Clinical benefit and cost effectiveness of total knee arthroplasty in the older patient

    Directory of Open Access Journals (Sweden)

    Krummenauer F

    2009-02-01

    Full Text Available Abstract Purpose Total knee arthroplasty (TKA is an effective, but also cost-intensive health care procedure for the elderly. Furthermore, bearing demographic changes in Western Europe in mind, TKA-associated financial investment for health care insurers will increase notably and thereby catalyze discussions on ressource allocation to Orthopedic surgery. To derive a quantitative rationale for such discussions within Western Europe's health care systems, a prospective assessment of both the benefit of TKA from a patient's perspective as well as its cost effectiveness from a health care insurer's perspective was implemented. Methods A prospective cost effectiveness trial recruited a total of 65 patients (60% females, who underwent TKA in 2006; median age of patients was 66 years (interquartile range 61 - 74 years. Before and three months after surgery patients were interviewed by means of the EuroQol-5D and the WOMAC questionnaires to assess their individual benefit due to TKA and the subsequent inpatient rehabilitation. Both questionnaires' benefit estimates were transformed into the number of gained quality adjusted life years [QALYs]. Total direct cost estimates for the overall care were based on German DRG and rehabilitation cost rates [€]. The primary clinical endpoint of the investigation was the individual number of QALYs gained by TKA based on the WOMAC interview; the primary health economic endpoint was the marginal cost effectiveness ratio (MCER relating the costs to the associated gain in quality of life [€/QALY]. Results Total direct costs for the overall procedure were estimed 9549 € in median. The WOMAC based interview revealed an overall gain of 4.59 QALYs (interquartile range 2.39 - 6.21 QALYs, resulting in marginal costs of 1795 €/QALY (1488 - 3288 €/QALY. The corresponding EuroQol based estimates were 2.93 QALYs (1.75 - 5.59 QALYs and 3063 €/QALY (1613 - 5291 €/QALY. Logistic regression modelling identified the

  1. Costs of construction, operation and maintenance of nuclear power plants - determinant factors

    International Nuclear Information System (INIS)

    Silva, R.A. da

    1981-01-01

    A study about the construction costs of the Angra-1 nuclear power plant, including direct costs, equipment costs, installation and indirect costs such as: engineering, job-training and administration is presented. The operation and maintenance costs of the Angra-1 nuclear power plant and costs of energy generation are still studied. (E.G.) [pt

  2. Impact of solar energy cost on water production cost of seawater desalination plants in Egypt

    International Nuclear Information System (INIS)

    Lamei, A.; Zaag, P. van der; Munch, E.

    2008-01-01

    Many countries in North Africa and the Middle East are experiencing localized water shortages and are now using desalination technologies with either reverse osmosis (RO) or thermal desalination to overcome part of this shortage. Desalination is performed using electricity, mostly generated from fossil fuels with associated greenhouse gas emissions. Increased fuel prices and concern over climate change are causing a push to shift to alternative sources of energy, such as solar energy, since solar radiation is abundant in this region all year round. This paper presents unit production costs and energy costs for 21 RO desalination plants in the region. An equation is proposed to estimate the unit production costs of RO desalination plants as a function of plant capacity, price of energy and specific energy consumption. This equation is used to calculate unit production costs for desalinated water using photovoltaic (PV) solar energy based on current and future PV module prices. Multiple PV cells are connected together to form a module or a panel. Unit production costs of desalination plants using solar energy are compared with conventionally generated electricity considering different prices for electricity. The paper presents prices for both PV and solar thermal energy. The paper discusses at which electricity price solar energy can be considered economical to be used for RO desalination; this is independent of RO plant capacity. For countries with electricity prices of 0.09 US$/kWh, solar-generated electricity (using PV) can be competitive starting from 2 US$/W p (W p is the number of Watts output under standard conditions of sunlight). For Egypt (price of 0.06 US$/kWh), solar-generated electricity starts to be competitive from 1 US$/W p . Solar energy is not cost competitive at the moment (at a current module price for PV systems including installation of 8 US$/W p ), but advances in the technology will continue to drive the prices down, whilst penalties on usage

  3. Bearing Procurement Analysis Method by Total Cost of Ownership Analysis and Reliability Prediction

    Science.gov (United States)

    Trusaji, Wildan; Akbar, Muhammad; Sukoyo; Irianto, Dradjad

    2018-03-01

    In making bearing procurement analysis, price and its reliability must be considered as decision criteria, since price determines the direct cost as acquisition cost and reliability of bearing determine the indirect cost such as maintenance cost. Despite the indirect cost is hard to identify and measured, it has high contribution to overall cost that will be incurred. So, the indirect cost of reliability must be considered when making bearing procurement analysis. This paper tries to explain bearing evaluation method with the total cost of ownership analysis to consider price and maintenance cost as decision criteria. Furthermore, since there is a lack of failure data when bearing evaluation phase is conducted, reliability prediction method is used to predict bearing reliability from its dynamic load rating parameter. With this method, bearing with a higher price but has higher reliability is preferable for long-term planning. But for short-term planning the cheaper one but has lower reliability is preferable. This contextuality can give rise to conflict between stakeholders. Thus, the planning horizon needs to be agreed by all stakeholder before making a procurement decision.

  4. WIPP conceptual design report. Addendum C. Cost worksheets for Waste Isolation Pilot Plant (WIPP)

    International Nuclear Information System (INIS)

    1977-04-01

    The cost worksheets for the Waste Isolation Pilot Plant (WIPP) are presented. A summary cost estimate, cost estimate for surface facilities, and cost estimate for shafts and underground facilities are included

  5. Time-based analysis of total cost of patient episodes: a case study of hip replacement.

    Science.gov (United States)

    Peltokorpi, Antti; Kujala, Jaakko

    2006-01-01

    Healthcare in the public and private sectors is facing increasing pressure to become more cost-effective. Time-based competition and work-in-progress have been used successfully to measure and improve the efficiency of industrial manufacturing. Seeks to address this issue. Presents a framework for time based management of the total cost of a patient episode and apply it to the six sigma DMAIC-process development approach. The framework is used to analyse hip replacement patient episodes in Päijät-Häme Hospital District in Finland, which has a catchment area of 210,000 inhabitants and performs an average of 230 hip replacements per year. The work-in-progress concept is applicable to healthcare--notably that the DMAIC-process development approach can be used to analyse the total cost of patient episodes. Concludes that a framework, which combines the patient-in-process and the DMAIC development approach, can be used not only to analyse the total cost of patient episode but also to improve patient process efficiency. Presents a framework that combines patient-in-process and DMAIC-process development approaches, which can be used to analyse the total cost of a patient episode in order to improve patient process efficiency.

  6. Introduction of total productive maintenance in steelworks plants

    Directory of Open Access Journals (Sweden)

    B. Gajdzik

    2009-04-01

    Full Text Available The paper presents the concept of TPM - Total Productive Maintenance and its basic method 5S (sort, systematize, sweep, sanitize, self-discipline. The new management concept is realized in Japanese and USA companies. On the Polish market the methods was adopted in the first years of 21st century by car manufacturers and household equipment producers. Nowadays the concept is tested by steelworks in Polish steel industry. The process of introduction of these methods is long, difficult and requires organizational and technical changes. The companies which realize Awareness Management Project of workers in Health and Safety System use other methods whose primary goal is to ensure objectivity and comparability of results and skill assessment of particular employees (the Current and Periodic Assessment System for worker and supervision positions.

  7. Compendium of cost-effectiveness evaluations of modifications for dose reduction at nuclear power plants

    International Nuclear Information System (INIS)

    Baum, J.W.; Matthews, G.R.

    1985-12-01

    This report summarizes available information on cost effectiveness of engineering modifications potentially valuable for dose reduction at nuclear power plants. Data were gathered from several US utilities, published literature, equipment and service suppliers, and recent technical meetings. Five simplified econometric models were employed to evaluate data and arrive at a value for cost effectiveness expressed in either (a) dollars/rem, or (b) total dollar savings calculated using a nominal value of $1000/rem. Models employed were: a basic model with no consideration given to the time value of money; two models in which discounting was used to evaluate costs and savings in terms of present values; and two models in which income taxes and revenue requirements were considered. Results from different models varied by as much as a factor of 10, and were generally lowest for the basic model and highest for the before-tax revenue requirements model. Results for 151 evaluations employing different assumptions concerning number of plants per site and outage impacts were tabulated in order of decreasing cost effectiveness. Twenty-five evaluations were identified as exceptionally cost effective since both costs and dose were saved. Forty evaluations indicated highly cost-effective changes based on costs below $1000/rem saved using results of the present-worth model that included discounting of future dose savings

  8. Hybrid Cloud Computing Architecture Optimization by Total Cost of Ownership Criterion

    Directory of Open Access Journals (Sweden)

    Elena Valeryevna Makarenko

    2014-12-01

    Full Text Available Achieving the goals of information security is a key factor in the decision to outsource information technology and, in particular, to decide on the migration of organizational data, applications, and other resources to the infrastructure, based on cloud computing. And the key issue in the selection of optimal architecture and the subsequent migration of business applications and data to the cloud organization information environment is the question of the total cost of ownership of IT infrastructure. This paper focuses on solving the problem of minimizing the total cost of ownership cloud.

  9. Cost minimization in a full-scale conventional wastewater treatment plant: associated costs of biological energy consumption versus sludge production.

    Science.gov (United States)

    Sid, S; Volant, A; Lesage, G; Heran, M

    2017-11-01

    Energy consumption and sludge production minimization represent rising challenges for wastewater treatment plants (WWTPs). The goal of this study is to investigate how energy is consumed throughout the whole plant and how operating conditions affect this energy demand. A WWTP based on the activated sludge process was selected as a case study. Simulations were performed using a pre-compiled model implemented in GPS-X simulation software. Model validation was carried out by comparing experimental and modeling data of the dynamic behavior of the mixed liquor suspended solids (MLSS) concentration and nitrogen compounds concentration, energy consumption for aeration, mixing and sludge treatment and annual sludge production over a three year exercise. In this plant, the energy required for bioreactor aeration was calculated at approximately 44% of the total energy demand. A cost optimization strategy was applied by varying the MLSS concentrations (from 1 to 8 gTSS/L) while recording energy consumption, sludge production and effluent quality. An increase of MLSS led to an increase of the oxygen requirement for biomass aeration, but it also reduced total sludge production. Results permit identification of a key MLSS concentration allowing identification of the best compromise between levels of treatment required, biological energy demand and sludge production while minimizing the overall costs.

  10. Cost to deliver sweet sorghum fermentables to a central plant

    International Nuclear Information System (INIS)

    Cundiff, J.S.

    1991-01-01

    The major obstacle to a sweet sorghum-for-ethanol industry in the Piedmont of Virginia is the short harvest season of eight weeks. A Piedmont harvesting system is described that will enable the Piedmont to compete with Louisiana in production of sweet sorghum for ethanol. The cost to supply feedstock (up to the point fermentation begins) for a one million GPY ethanol plant was estimated to be $2.35/gal expected ethanol yield. This amount compared favorably with two other options

  11. Estimation of small-scale hydroelectric power plant costs; Estimacao de custos de PCH

    Energy Technology Data Exchange (ETDEWEB)

    Santos, Afonso Henriques Moreira [MS Consultoria Ltda, Itajuba, MG (Brazil); Universidade Federal de Itajuba (UNIFEI), MG (Brazil); Silva, Benedito Claudio da [IX Consultoria e Representacoes Ltda, Itajuba, MG (Brazil); Universidade Federal de Itajuba (UNIFEI), MG (Brazil); Magalhaes, Ricardo Nogueira [IX Consultoria e Representacoes Ltda, Itajuba, MG (Brazil)

    2010-07-01

    Changes in Brazilian energy scenario through last years such as increase of demand and search for clean and economically feasible renewable energy sources, has stimulated investors to small hydro power plants (SHP) sector. Such characteristics together with several economic incentives, legal and regulatory mechanisms also, have helped and stimulated building of new plants of this kind and have attracted a great number of investors to this sector. Study of costs analysis and feasibility of investments is a study which has been used since long time in SHP business market as several preliminary studies previous to civil project have significant costs which lead us to count with a feasibility analysis from the very beginning of studies, exactly what is suggested in the present methodology. Such feasibility analysis, in the common patterns where basic unit costs of each input remain outstanding, would be very complex due to great difficulty in obtaining information at initial phase of project. In this direction this study brings a contribution for investors as well as for designers of small hydro power plants since it outlines a link between physical and energetic characteristics of small hydro power plant in its total cost. Such link is based in available physical characteristics in initial phase of the project, making possible a previous comparison between arrangements of a central or even the comparison of return of investment between different plants. The resulting benefit being the possibility of choosing centrals with greater economic feasibility disregarding bad undertakings or arrangements with more expressive cost. Final result gives a better delay in return of investment, helps in power, arrangements more optimized and in saving time as well, reducing costs of undertakings. Due to large number of SHP arrangements, we chose for this study the most common in Brazil, plant of medium and large fall, shunting line balance chimney and low pressure conduit. (author)

  12. Cost effective water treatment program in Heavy Water Plant (Manuguru)

    International Nuclear Information System (INIS)

    Mohapatra, C.; Prasada Rao, G.

    2002-01-01

    Water treatment technology is in a state of continuous evolution. The increasing urgency to conserve water and reduce pollution has in recent years produced an enormous demand for new chemical treatment programs and technologies. Heavy water plant (Manuguru) uses water as raw material (about 3000 m 3 /hr) and its treatment and management has benefited the plant in a significant way. It is a fact that if the water treatment is not proper, it can result in deposit formation and corrosion of metals, which can finally leads to production losses. Therefore, before selecting treatment program, complying w.r.t. quality requirements, safety and pollution aspects cost effectiveness shall be examined. The areas where significant benefits are derived, are raw water treatment using polyelectrolyte instead of inorganic coagulant (alum), change over of regenerant of cation exchangers from hydrochloric acid to sulfuric acid and in-house development of cooling water treatment formulation. The advantages and cost effectiveness of these treatments are discussed in detail. Further these treatments has helped the plant in achieving zero discharge and indirectly increased cost reduction of final product (heavy water); the dosage of 3 ppm of polyelectrolyte can replace 90 ppm alum at turbidity level of 300 NTU of raw water which has resulted in cost saving of Rs. 15-20 lakhs in a year beside other advantages; the change over of regenerant from HCl to H 2 SO 4 will result in cost saving of at least Rs.1.4 crore a year besides other advantages; the change over to proprietary formulation to in-house formulation in cooling water treatment has resulted in a saving about Rs.11 lakhs a year. To achieve the above objectives in a sustainable way the performance results are being monitored. (author)

  13. Total inpatient treatment costs in patients with severe burns: towards a more accurate reimbursement model.

    Science.gov (United States)

    Mehra, Tarun; Koljonen, Virve; Seifert, Burkhardt; Volbracht, Jörk; Giovanoli, Pietro; Plock, Jan; Moos, Rudolf Maria

    2015-01-01

    Reimbursement systems have difficulties depicting the actual cost of burn treatment, leaving care providers with a significant financial burden. Our aim was to establish a simple and accurate reimbursement model compatible with prospective payment systems. A total of 370 966 electronic medical records of patients discharged in 2012 to 2013 from Swiss university hospitals were reviewed. A total of 828 cases of burns including 109 cases of severe burns were retained. Costs, revenues and earnings for severe and nonsevere burns were analysed and a linear regression model predicting total inpatient treatment costs was established. The median total costs per case for severe burns was tenfold higher than for nonsevere burns (179 949 CHF [167 353 EUR] vs 11 312 CHF [10 520 EUR], interquartile ranges 96 782-328 618 CHF vs 4 874-27 783 CHF, p <0.001). The median of earnings per case for nonsevere burns was 588 CHF (547 EUR) (interquartile range -6 720 - 5 354 CHF) whereas severe burns incurred a large financial loss to care providers, with median earnings of -33 178 CHF (30 856 EUR) (interquartile range -95 533 - 23 662 CHF). Differences were highly significant (p <0.001). Our linear regression model predicting total costs per case with length of stay (LOS) as independent variable had an adjusted R2 of 0.67 (p <0.001 for LOS). Severe burns are systematically underfunded within the Swiss reimbursement system. Flat-rate DRG-based refunds poorly reflect the actual treatment costs. In conclusion, we suggest a reimbursement model based on a per diem rate for treatment of severe burns.

  14. The Relationship between Cost Leadership Strategy, Total Quality Management Applications and Financial Performance

    OpenAIRE

    Ali KURT; Cemal ZEHİR

    2016-01-01

    Firms need to implement some competition strategies and total quality management applications to overcome the fierce competition among others. The purpose of this study is to show the relationship between cost leadership strategy, total quality management applications and firms’ financial performance with literature review and empirical analysis. 449 questionnaires were conducted to the managers of 142 big firms. The data gathered was assessed with AMOS. As a result, the relationship between ...

  15. Decommissioning of nuclear power plants: policies, strategies and costs

    International Nuclear Information System (INIS)

    Lund, I.

    2004-01-01

    As many nuclear power plants will reach the end of their lifetime during the next 20 years or so, decommissioning is an increasingly important topic for governments, regulators and industries. From a governmental viewpoint, particularly in a deregulated market, one essential aspect is to ensure that money for the decommissioning of nuclear installations will be available at the time it is needed, and that no 'stranded' liabilities will be left to be financed by the taxpayers rather than by the electricity consumers. For this reason, there is governmental interest in understanding decommissioning costs, and in periodically reviewing decommissioning cost estimates from nuclear installation owners. Robust cost estimates are key elements in designing and implementing a coherent and comprehensive national decommissioning policy including the legal and regulatory bases for the collection, saving and use of decommissioning funds. From the industry viewpoint, it is essential to assess and monitor decommissioning costs in order to develop a coherent decommissioning strategy that reflects national policy and assures worker and public safety, whilst also being cost effective. For these reasons, nuclear power plant owners are interested in understanding decommissioning costs as best as possible and in identifying major cost drivers, whether they be policy, strategy or 'physical' in nature. National policy considerations will guide the development of national regulations that are relevant for decommissioning activities. Following these policies and regulations, industrial managers responsible for decommissioning activities will develop strategies which best suit their needs, while appropriately meeting all government requirements. Decommissioning costs will be determined by technical and economic conditions, as well as by the strategy adopted. Against this backdrop, the study analyses the relationships among decommissioning policy as developed by governments, decommissioning

  16. Cost benefit justification of nuclear plant reliability improvement

    International Nuclear Information System (INIS)

    El-Sayed, M.A.H.; Abdelmonem, N.M.

    1986-01-01

    Nuclear power costs are evaluated on the bases of general ground rules (a) vary from time to time (b) vary from country to another (c) even vary from one reactor type to another. The main objective of an electric utility is to provide the electric energy to the different consummers at the lowest possible cost with reasonable reliability level. Rapid increase of the construction costs and fuel prices in recent years have stimulated a great deal of interest in improving the reliability and productivity of new and existing power plants. One of the most important areas is the improvement of the secondary steam loop and the reactor cooling system. The method for evaluating the reliability of steam loop and cooling system utilizes the cut-set technique. The developed method can be easily used to show to what extent the overall reliability of the nuclear plant is affected by the possible failures in the steam and cooling subsystem. The cost reliability trade-off analysis is used to evaluate alternative schemes in the design with a view towards meeting a high reliability goal. Based on historical or estimated failure and repair rate, the reliability of the alternate scheme can be calculated

  17. Environmental cost/benefit analysis for fusion power plants

    International Nuclear Information System (INIS)

    Young, J.R.

    1976-11-01

    This document presents a cost/benefit analysis of use of fusion power plants early in the 21st century. The first section describes the general formulation of the analysis. Included are the selection of the alternatives to the fusion reactor, selection of the power system cases to be compared, and a general comparison of the environmental effects of the selected alternatives. The second section compares the cumulative environmental effects from 2010 to 2040 for the primary cases of the power system with and without fusion reactors. The third section briefly illustrates the potential economic benefits if fusion reactors produce electricity at a lower unit cost than LMFBRs can. The fourth section summarizes the cost/benefit analysis

  18. Linking the spare parts management with the total costs of ownership: An agenda for future research

    International Nuclear Information System (INIS)

    Duran, O.; Roda, I.; Macchi, M.

    2016-01-01

    Purpose: This manuscript explores the link between Spare Parts Management and Total Costs of Ownership or Life Cycle Costs (LCC). Design/methodology/approach: First, this work enumerates the different managerial decisions instances in spare parts management that are present during the life cycle of a physical asset. Second, we analyse how those decision instances could affect the TCO of a physical asset (from the economic point of view). Finally, we propose a conceptual framework for incorporating the spare parts management into a TCO model. Findings: The recent literature lacks discussions on the integration of spare parts management with the Total Costs of Ownership (TCO). Based in an extensive literature revision we can declare that the computation of costs related to spare parts management has been neglected by TCO models. Originality/value: The contribution of this paper is twofold. First, a literature review and identification of a series of spare parts management decision instances and its relationship with TCOs is presented in this paper. Second, a conceptual framework is suggested for linking those decisions instances to a total cost of ownership perspective. Some research questions and future research challenges are presented at the end of this work.

  19. Linking the spare parts management with the total costs of ownership: An agenda for future research

    Energy Technology Data Exchange (ETDEWEB)

    Duran, O.; Roda, I.; Macchi, M.

    2016-07-01

    Purpose: This manuscript explores the link between Spare Parts Management and Total Costs of Ownership or Life Cycle Costs (LCC). Design/methodology/approach: First, this work enumerates the different managerial decisions instances in spare parts management that are present during the life cycle of a physical asset. Second, we analyse how those decision instances could affect the TCO of a physical asset (from the economic point of view). Finally, we propose a conceptual framework for incorporating the spare parts management into a TCO model. Findings: The recent literature lacks discussions on the integration of spare parts management with the Total Costs of Ownership (TCO). Based in an extensive literature revision we can declare that the computation of costs related to spare parts management has been neglected by TCO models. Originality/value: The contribution of this paper is twofold. First, a literature review and identification of a series of spare parts management decision instances and its relationship with TCOs is presented in this paper. Second, a conceptual framework is suggested for linking those decisions instances to a total cost of ownership perspective. Some research questions and future research challenges are presented at the end of this work.

  20. Linking the spare parts management with the total costs of ownership: An agenda for future research

    Directory of Open Access Journals (Sweden)

    Orlando Duran

    2016-12-01

    Full Text Available Purpose: This manuscript explores the link between Spare Parts Management and Total Costs of Ownership or Life Cycle Costs (LCC. Design/methodology/approach: First, this work enumerates the different managerial decisions instances in spare parts management that are present during the life cycle of a physical asset. Second, we analyse how those decision instances could affect the TCO of a physical asset (from the economic point of view. Finally, we propose a conceptual framework for incorporating the spare parts management into a TCO model. Findings: The recent literature lacks discussions on the integration of spare parts management with the Total Costs of Ownership (TCO. Based in an extensive literature revision we can declare that the computation of costs related to spare parts management has been neglected by TCO models. Originality/value: The contribution of this paper is twofold. First, a literature review and identification of a series of spare parts management decision instances and its relationship with TCOs is presented in this paper. Second, a conceptual framework is suggested for linking those decisions instances to a total cost of ownership perspective. Some research questions and future research challenges are presented at the end of this work.

  1. Total hip arthroplasty revision due to infection: a cost analysis approach.

    Science.gov (United States)

    Klouche, S; Sariali, E; Mamoudy, P

    2010-04-01

    The treatment of total hip arthroplasty (THA) infections is long and costly. However,the number of studies in the literature analysing the real cost of THA revision in relation to their etiology, including infection, is limited. The aim of this retrospective study was to determine the cost of revision of infected THA and to compare these costs to those of primary THA and revision of non-infected THA. We performed a retrospective cost analysis for the year 2006 using an identical analytic accounting system in each hospital department (according to internal criteria) based on allotment of direct costs and receipts for each department. From January to December 2006, 424 primary THA, 57 non-infected THA revisions and 40 THA revisions due to infection were performed. The different cost areas of the patient's treatment were identified.This included preoperative medical work-up, medicosurgical management during hospital stay,a second stay in an orthopedic rehabilitation hospital (ORH) and post-hospitalisation antibiotic therapy after revision due to infection, as well as home-based hospitalisation (HH) costs, if this was the selected alternative option. We used the national health insurance fee schedule found in the "Common classification of medical procedures" and the "General nomenclature of professional procedures" applicable in France since September 1, 2005. Hospital costs included direct costs (hospital overhead costs) and indirect costs, (medical, surgical, technical settings and net general service expenses). The calculation of HH costs and ORH costs were based on the average daily charge of these departments. The cost of primary THA was used as the reference.We then compared our surgical costs with those found for the corresponding comparable hospital stay groups (Groupes homogènes de séjour). The average hospital stay (AHS) was 7.5 +/- 1.8 days for primary THA, 8.9 +/- 2.2 days for non-infected revisions and 30.6 +/- 14.9 days for revisions due to infection

  2. A METHOD OF THE MINIMIZING OF THE TOTAL ACQUISITIONS COST WITH THE INCREASING VARIABLE DEMAND

    Directory of Open Access Journals (Sweden)

    ELEONORA IONELA FOCȘAN

    2015-12-01

    Full Text Available Over time, mankind has tried to find different ways of costs reduction. This subject which we are facing more often nowadays, has been detailed studied, without reaching a general model, and also efficient, regarding the costs reduction. Costs reduction entails a number of benefits over the entity, the most important being: increase revenue and default to the profit, increase productivity, a higher level of services / products offered to clients, and last but not least, the risk mitigation of the economic deficit. Therefore, each entity search different modes to obtain most benefits, for the company to succeed in a competitive market. This article supports the companies, trying to make known a new way of minimizing the total cost of acquisitions, by presenting some hypotheses about the increasing variable demand, proving them, and development of formulas for reducing the costs. The hypotheses presented in the model described below, can be maximally exploited to obtain new models of reducing the total cost, according to the modes of the purchase of entities which approach it.

  3. Total cost of ownership in the services sector: A case study

    NARCIS (Netherlands)

    K. Hurkens (Krisje); W. van der Valk (Wendy); J.Y.F. Wynstra (Finn)

    2006-01-01

    textabstractFew detailed studies exist of the trade-offs to be made when developing a comprehensive, strategically focused total cost of ownership (TCO) model. Moreover, most studies of TCO have been conducted in manufacturing firms, with little or no TCO research directed toward service

  4. Multi-Product Total Cost of Function for Higher Education: A Case of Bible Colleges.

    Science.gov (United States)

    Koshal, Rajindar K.; Koshal, Manjulika; Gupta, Ashok

    2001-01-01

    This study empirically estimates a multiproduct total cost function and output relationship for comprehensive U.S. universities. Statistical results for 184 Bible colleges suggest that there are both economies of scale and of scope in higher education. Additionally, product-specific economies of scope exist for all output levels and activities.…

  5. Permanent magnet design for magnetic heat pumps using total cost minimization

    Science.gov (United States)

    Teyber, R.; Trevizoli, P. V.; Christiaanse, T. V.; Govindappa, P.; Niknia, I.; Rowe, A.

    2017-11-01

    The active magnetic regenerator (AMR) is an attractive technology for efficient heat pumps and cooling systems. The costs associated with a permanent magnet for near room temperature applications are a central issue which must be solved for broad market implementation. To address this problem, we present a permanent magnet topology optimization to minimize the total cost of cooling using a thermoeconomic cost-rate balance coupled with an AMR model. A genetic algorithm identifies cost-minimizing magnet topologies. For a fixed temperature span of 15 K and 4.2 kg of gadolinium, the optimal magnet configuration provides 3.3 kW of cooling power with a second law efficiency (ηII) of 0.33 using 16.3 kg of permanent magnet material.

  6. Time-driven Activity-based Cost of Fast-Track Total Hip and Knee Arthroplasty

    DEFF Research Database (Denmark)

    Andreasen, Signe E; Holm, Henriette B; Jørgensen, Mira

    2017-01-01

    this between 2 departments with different logistical set-ups. METHODS: Prospective data collection was analyzed using the time-driven activity-based costing method (TDABC) on time consumed by different staff members involved in patient treatment in the perioperative period of fast-track THA and TKA in 2 Danish...... orthopedic departments with standardized fast-track settings, but different logistical set-ups. RESULTS: Length of stay was median 2 days in both departments. TDABC revealed minor differences in the perioperative settings between departments, but the total cost excluding the prosthesis was similar at USD......-track methodology, the result could be a more cost-effective pathway altogether. As THA and TKA are potentially costly procedures and the numbers are increasing in an economical limited environment, the aim of this study is to present baseline detailed economical calculations of fast-track THA and TKA and compare...

  7. Cost Analysis of Total Joint Arthroplasty Readmissions in a Bundled Payment Care Improvement Initiative.

    Science.gov (United States)

    Clair, Andrew J; Evangelista, Perry J; Lajam, Claudette M; Slover, James D; Bosco, Joseph A; Iorio, Richard

    2016-09-01

    The Bundled Payment for Care Improvement (BPCI) Initiative is a Centers for Medicare and Medicaid Services program designed to promote coordinated and efficient care. This study seeks to report costs of readmissions within a 90-day episode of care for BPCI Initiative patients receiving total knee arthroplasty (TKA) or total hip arthroplasty (THA). From January 2013 through December 2013, 1 urban, tertiary, academic orthopedic hospital admitted 664 patients undergoing either primary TKA or THA through the BPCI Initiative. All patients readmitted to our hospital or an outside hospital within 90-days from the index episode were identified. The diagnosis and cost for each readmission were analyzed. Eighty readmissions in 69 of 664 patients (10%) were identified within 90-days. There were 53 readmissions (45 patients) after THA and 27 readmissions (24 patients) after TKA. Surgical complications accounted for 54% of THA readmissions and 44% of TKA readmissions. These complications had an average cost of $36,038 (range, $6375-$60,137) for THA and $38,953 (range, $4790-$104,794) for TKA. Eliminating the TKA outlier of greater than $100,000 yields an average cost of $27,979. Medical complications of THA and TKA had an average cost of $22,775 (range, $5678-$82,940) for THA and $24,183 (range, $3306-$186,069) for TKA. Eliminating the TKA outlier of greater than $100,000 yields an average cost of $11,682. Hospital readmissions after THA and TKA are common and costly. Identifying the causes for readmission and assessing the cost will guide quality improvement efforts. Copyright © 2016 Elsevier Inc. All rights reserved.

  8. Technology, safety, and costs of decommissioning a reference nuclear fuel reprocessing plant

    International Nuclear Information System (INIS)

    Schneider, K.J.; Jenkins, C.E.; Rhoads, R.E.

    1977-09-01

    Safety and cost information were developed for the conceptual decommissioning of a fuel reprocessing plant with characteristics similar to the Barnwell Nuclear Fuel Plant. The main process building, spent fuel receiving and storage station, liquid radioactive waste storage tank system, and a conceptual high-level waste-solidification facility were postulated to be decommissioned. The plant was conceptually decommissioned to three decommissioning states or modes; layaway, protective storage, and dismantlement. Assuming favorable work performance, the elapsed time required to perform the decommissioning work in each mode following plant shutdown was estimated to be 2.4 years for layaway, 2.7 years for protective storage, and 5.2 years for dismantlement. In addition to these times, approximately 2 years of planning and preparation are required before plant shutdown. Costs, in constant 1975 dollars, for decommissioning were estimated to be $18 million for layaway, $19 million for protective storage and $58 million for dismantlement. Maintenance and surveillance costs were estimated to be $680,000 per year after layaway and $140,000 per year after protective storage. The combination mode of protective storage followed by dismantlement deferred for 10, 30, and 100 years was estimated to cost $64 million, $67 million and $77 million, respectively, in nondiscounted total 1975 dollars. Present values of these costs give reduced costs as dismantlement is deferred. Safety analyses indicate that radiological and nonradiological safety impacts from decommissioning activities should be small. The 50-year radiation dose commitment to the members of the public from airborne releases from normal decommissioning activities were estimated to be less than 11 man-rem

  9. Technology, safety, and costs of decommissioning a reference nuclear fuel reprocessing plant

    Energy Technology Data Exchange (ETDEWEB)

    Schneider, K.J.; Jenkins, C.E.; Rhoads, R.E.

    1977-09-01

    Safety and cost information were developed for the conceptual decommissioning of a fuel reprocessing plant with characteristics similar to the Barnwell Nuclear Fuel Plant. The main process building, spent fuel receiving and storage station, liquid radioactive waste storage tank system, and a conceptual high-level waste-solidification facility were postulated to be decommissioned. The plant was conceptually decommissioned to three decommissioning states or modes; layaway, protective storage, and dismantlement. Assuming favorable work performance, the elapsed time required to perform the decommissioning work in each mode following plant shutdown was estimated to be 2.4 years for layaway, 2.7 years for protective storage, and 5.2 years for dismantlement. In addition to these times, approximately 2 years of planning and preparation are required before plant shutdown. Costs, in constant 1975 dollars, for decommissioning were estimated to be $18 million for layaway, $19 million for protective storage and $58 million for dismantlement. Maintenance and surveillance costs were estimated to be $680,000 per year after layaway and $140,000 per year after protective storage. The combination mode of protective storage followed by dismantlement deferred for 10, 30, and 100 years was estimated to cost $64 million, $67 million and $77 million, respectively, in nondiscounted total 1975 dollars. Present values of these costs give reduced costs as dismantlement is deferred. Safety analyses indicate that radiological and nonradiological safety impacts from decommissioning activities should be small. The 50-year radiation dose commitment to the members of the public from airborne releases from normal decommissioning activities were estimated to be less than 11 man-rem.

  10. Electricity-cost savings obtained by means of nuclear plant life extension

    International Nuclear Information System (INIS)

    Forest, L.; Fletcher, T.; DuCharme, A.; Harrison, D.L.

    1987-01-01

    This study examines savings caused by nuclear-plant life extension (NUPLEX) and describes the effects of changes in assumptions on costs and technology using an approach simpler than the large economic-model simulations used in other reports. Under the simplified approach, we estimate savings at the broad national level by comparing projected costs/kWh for the typical NUPLEX plant with those for new coal-fired plants, which seem the most likely alternative in most regions. While ignoring some complications handled by the large, regionally disaggregated econometric models, the approach used in this study has advantages in sensitivity analyses. It reveals relationships between savings and basic assumptions on costs and technology in a more transparent way than in large-model simulations. We find that, absent major technological breakthroughs for present generating options, NUPLEX saves consumers money on their electric bills under most plausible economic scenarios. Using mid-range assumptions, we find that NUPLEX saves consumers a total of about dollar 180 billion spread over the period 2010-50. Under optimistic assumptions, the savings swell to over dollar 900 billion. Under extremely pessimistic assumptions, the savings actually turn negative. This wide range of estimates largely reflects the uncertainty in cost projections. Within plausible limits, higher- or lower-than-expected load growth does not affect the savings estimates. The NUPLEX construction costs stand out as the most critical unknown. If they turn out to be 50% (dollar 500 billion) above the baseline estimate savings would fall by almost 60% (dollar 105 billion). A 50% rise in nuclear fuel costs would drop baseline savings by almost 22%. A 50% increase in nuclear-plant operations-and-maintenance costs, would cut baseline savings by about 36%. These sensitivities highlight the need for continued monitoring of economic developments

  11. Impact Of Health Care Delivery System Innovations On Total Cost Of Care.

    Science.gov (United States)

    Smith, Kevin W; Bir, Anupa; Freeman, Nikki L B; Koethe, Benjamin C; Cohen, Julia; Day, Timothy J

    2017-03-01

    Using delivery system innovations to advance health care reform continues to be of widespread interest. However, it is difficult to generalize about the success of specific types of innovations, since they have been examined in only a few studies. To gain a broader perspective, we analyzed the results of forty-three ambulatory care programs funded by the first round of the Center for Medicare and Medicaid Innovation's Health Care Innovations Awards. The innovations' impacts on total cost of care were estimated by independent evaluators using multivariable difference-in-differences models. Through the first two years, most of the innovations did not show a significant effect on total cost of care. Using meta-regression, we assessed the effects on costs of five common components of these innovations. Innovations that used health information technology or community health workers achieved the greatest cost savings. Savings were also relatively large in programs that targeted clinically fragile patients-clinically complex populations at risk for disease progression. While the magnitude of these effects was often substantial, none achieved conventional levels of significance in our analyses. Meta-analyses of a larger number of delivery system innovations are needed to more clearly establish their potential for patient care cost savings. Project HOPE—The People-to-People Health Foundation, Inc.

  12. Using Electromagnetic Algorithm for Total Costs of Sub-contractor Optimization in the Cellular Manufacturing Problem

    Directory of Open Access Journals (Sweden)

    Mohammad Reza Shahriari

    2016-12-01

    Full Text Available In this paper, we present a non-linear binary programing for optimizing a specific cost in cellular manufacturing system in a controlled production condition. The system parameters are determined by the continuous distribution functions. The aim of the presented model is to optimize the total cost of imposed sub-contractors to the manufacturing system by determining how to allocate the machines and parts to each seller. In this system, DM could control the occupation level of each machine in the system. For solving the presented model, we used the electromagnetic meta-heuristic algorithm and Taguchi method for determining the optimal algorithm parameters.

  13. Determination of total As in onion plants growing in contaminated substrates by total reflection X-ray fluorescence

    International Nuclear Information System (INIS)

    Lue-Meru Marco Parra

    2011-01-01

    The onion (Allium cepa L.) is one of the most important cultivars in the world and its production level occupies the second place in Venezuela. It becomes important to develop analytical procedures for arsenic determination and to study the effect of this element on the cultures, as well the absorption, transport and translocation processes. A TXRF method for As determination in onions was developed. Two treatments were applied to the onion plants, As contaminated and control. The contaminant was added to the plants to an amount of 100 μg, in a single time 3 weeks after the transplant of plantlets. The green leaves bulbs, and roots together with the stems were separated 45 days after transplant and analyzed by TXRF and HG-AAS for total Arsenic determination. A good agreement was found between these two techniques, demonstrating the accuracy of the TXRF procedure. It was found that the highest concentration corresponded to the root and stems (37 ± 31 μg g -1 ), followed by the bulbs (11 ± 7 μg g -1 ), being the smallest level found in the green leaves (4 ± 3 μg g -1 ). At low As contamination levels of 0.25 μg g -1 , a risk for translocation of the toxic element to the edible parts of the onion plants exists. At this level the normal development of the plant is not affected, being the only exception the root length, which is significantly higher in the contaminated treatment. (author)

  14. Cost-Effective Mobile-Based Healthcare System for Managing Total Joint Arthroplasty Follow-Up.

    Science.gov (United States)

    Bitsaki, Marina; Koutras, George; Heep, Hansjoerg; Koutras, Christos

    2017-01-01

    Long-term follow-up care after total joint arthroplasty is essential to evaluate hip and knee arthroplasty outcomes, to provide information to physicians and improve arthroplasty performance, and to improve patients' health condition. In this paper, we aim to improve the communication between arthroplasty patients and physicians and to reduce the cost of follow-up controls based on mobile application technologies and cloud computing. We propose a mobile-based healthcare system that provides cost-effective follow-up controls for primary arthroplasty patients through questions about symptoms in the replaced joint, questionnaires (WOMAC and SF-36v2) and the radiological examination of knee or hip joint. We also perform a cost analysis for a set of 423 patients that were treated in the University Clinic for Orthopedics in Essen-Werden. The estimation of healthcare costs shows significant cost savings (a reduction of 63.67% for readmission rate 5%) in both the University Clinic for Orthopedics in Essen-Werden and the state of North Rhine-Westphalia when the mobile-based healthcare system is applied. We propose a mHealth system to reduce the cost of follow-up assessments of arthroplasty patients through evaluation of diagnosis, self-monitoring, and regular review of their health status.

  15. The implications of plant design on the life-time costs for nuclear fuel cycle facilities

    International Nuclear Information System (INIS)

    Macphee, D.S.; Hexter, B.C.; Young, M.P.; Wilson, B.J.

    1997-01-01

    Utilising the experience gained during many years of design and project management of nuclear plant, BNFL is now approaching the final stages of the construction and commissioning of the Sellafield MOX Plant (SMP) in the UK. The paper uses the SMP project to highlight the benefits of these experiences, in particular addressing the implications of the approach to plant design on life time costs. In addition to providing BNFL with a state of the art, commercial scale MOX fuel fabrication facility, the construction of this 120 tHM/yr facility, which is currently in the advanced stages of commissioning, represents a significant demonstration of the design and project management skills of BNFL Engineering Ltd. As well as meeting the main process requirements, the plant design incorporates the highest standards of safety, together with input from the future plant operators and potential customers. As befits a commercial scale plutonium handling facility, SMP also incorporates material accountancy and security provisions that will meet all international requirements. Design, construction and commissioning of this complex and highly automated plant, has benefited from a totally integrated approach to design and documentation that considers not only project implementation but also overall lifetime costs. In addition, project management techniques, developed over many years of major project construction at Sellafield, have been utilised in order to ensure successful project implementation against a background of significant technical challenge and 'fast track' timescales. (author)

  16. Cost related to nuclear power plants: the international experience

    International Nuclear Information System (INIS)

    1995-03-01

    This report about the international costs of nuclear electricity generations is divided in two distinct parts: the first one shows the competitiveness of the main sources of electricity generation for base load operation according to studies carried on by OECD and UNIPEDE since 1983; the second one discusses the most recent OECD study about the different types of power plants to be constructed in its number states, based on the experience of each country and the technology evolution of the different fuels used. (F.E.). 4 refs, 2 figs, 27 tab

  17. Cost per case or total cost? The potential of prevention of hand injuries in young children – Retrospective and prospective studies

    Directory of Open Access Journals (Sweden)

    Carlsson Katarina

    2008-07-01

    Full Text Available Abstract Background Health-care costs for hand and forearm injuries in young children are poorly documented. We examined costs in 533 children injured years 1996–2003. Methods Health-care costs and costs for lost productivity were retrospectively calculated in children from three catchment areas in Sweden. Seven case categories corresponding to alternative prevention strategies were constructed. Results Over time, diminishing number of ward days reduced the health-care cost per case. Among children, the cost of lost productivity due to parental leave was 14 percent of total cost. Fingertip injuries had low median costs but high total costs due to their frequency. Complex injuries by machine or rifle had high costs per case, and despite a low number of cases, total cost was high. Type of injury, surgery and physiotherapy sessions were associated with variations in health-care cost. Low age and ethnic background had a significant effect on number of ward days. Conclusion The costs per hand injury for children were lower compared to adults due to both lower health-care costs and to the fact that parents had comparatively short periods of absence from work. Frequent simple fingertip injuries and rare complex injuries induce high costs for society. Such costs should be related to costs for prevention of these injuries.

  18. Cycling of conventional power plants: Technical limits and actual costs

    International Nuclear Information System (INIS)

    Van den Bergh, Kenneth; Delarue, Erik

    2015-01-01

    Highlights: • Literature reports a wide range of cycling parameters (technical and cost-related). • The impact of different cycling parameters is assessed. • The German 2013 system is studied as a case study. • Even for stringent parameters, the dynamic limit of the portfolio is not reached. • Cycling costs can be reduced with 40% when taken into account in the scheduling. - Abstract: Cycling of conventional generation units is an important source of operational flexibility in the electricity generation system. Cycling is changing the power output of conventional units by means of ramping and switching (starting up and shutting down). In the literature, a wide range of technical and cost-related cycling parameters can be found. Different studies allocate different cycling parameters to similar generation units. This paper assesses the impact of different cycling parameters allocated to a conventional generation portfolio. Both the technical limitations of power plants and all costs related to cycling are considered. The results presented in this paper follow from a unit commitment model, used for a case study based on the German 2013 system. The conventional generation portfolio has to deliver different residual load time series, corresponding to different levels of renewables penetration. The study shows, under the assumptions made, that although the dynamic limits of some units are reached, the limits of the conventional generation portfolio as a whole are not reached, even if stringent dynamic parameters are assigned to the generation portfolio and a highly variable residual load is imposed to the system. The study shows also the importance of including full cycling costs in the unit commitment scheduling. The cycling cost can be reduced by up to 40% when fully taken into account

  19. EFFICIENCY AND COST MODELLING OF THERMAL POWER PLANTS

    Directory of Open Access Journals (Sweden)

    Péter Bihari

    2010-01-01

    Full Text Available The proper characterization of energy suppliers is one of the most important components in the modelling of the supply/demand relations of the electricity market. Power generation capacity i. e. power plants constitute the supply side of the relation in the electricity market. The supply of power stations develops as the power stations attempt to achieve the greatest profit possible with the given prices and other limitations. The cost of operation and the cost of load increment are thus the most important characteristics of their behaviour on the market. In most electricity market models, however, it is not taken into account that the efficiency of a power station also depends on the level of the load, on the type and age of the power plant, and on environmental considerations. The trade in electricity on the free market cannot rely on models where these essential parameters are omitted. Such an incomplete model could lead to a situation where a particular power station would be run either only at its full capacity or else be entirely deactivated depending on the prices prevailing on the free market. The reality is rather that the marginal cost of power generation might also be described by a function using the efficiency function. The derived marginal cost function gives the supply curve of the power station. The load level dependent efficiency function can be used not only for market modelling, but also for determining the pollutant and CO2 emissions of the power station, as well as shedding light on the conditions for successfully entering the market. Based on the measurement data our paper presents mathematical models that might be used for the determination of the load dependent efficiency functions of coal, oil, or gas fuelled power stations (steam turbine, gas turbine, combined cycle and IC engine based combined heat and power stations. These efficiency functions could also contribute to modelling market conditions and determining the

  20. 12 CFR Appendix K to Part 226 - Total Annual Loan Cost Rate Computations for Reverse Mortgage Transactions

    Science.gov (United States)

    2010-01-01

    ... Appendix K to Part 226—Total Annual Loan Cost Rate Computations for Reverse Mortgage Transactions (a... loan cost rate for various transactions, as well as instructions, explanations, and examples for.... (2) Term of the transaction. For purposes of total annual loan cost disclosures, the term of a...

  1. Tårs 10000 m2 CSP + Flat Plate Solar Collector Plant - Cost-Performance Optimization of the Design

    DEFF Research Database (Denmark)

    Perers, Bengt; Furbo, Simon; Tian, Zhiyong

    2016-01-01

    , was established. The optimization showed that there was a synergy in combining CSP and FP collectors. Even though the present cost per m² of the CSP collectors is high, the total energy cost is minimized by installing a combination of collectors in such solar heating plant. It was also found that the CSP......A novel solar heating plant with Concentrating Solar Power (CSP) collectors and Flat Plate (FP) collectors has been put into operation in Tårs since July 2015. To investigate economic performance of the plant, a TRNSYS-Genopt model, including a solar collector field and thermal storage tank...

  2. Incorporating a total cost perspective intothe purchasing strategy : A case study of amedium sized retail compan

    OpenAIRE

    EKSTRÖM, MARCUS; FAHNEHJELM, CAROLINA

    2016-01-01

    The retail industry is today characterized by downward price pressure, and the increasedcompetition in the industry has led to pressure on profit margins. Purchasing and supply chainmanagement have become areas of increased strategic importance and play a crucial role inthe business performance. This study aims to extend previous literature in these fields byproviding the existing research with an empirical study on how the purchasing strategy canincorporate a total cost perspective of the su...

  3. Methods of projecting operations and maintenance costs for nuclear power plants

    International Nuclear Information System (INIS)

    1995-01-01

    Operations and maintenance cost (OMC) had increased its relative importance to the total generation cost for future nuclear power stations, according to the latest update of the OECD Nuclear Energy Agency (NEA) study on Projected Costs of Generating Electricity (EGC studies). OMC is some 20 to 30% of total generation cost for future nuclear power stations in most NEA member countries. However, nuclear OMC that countries projected in the latest EGC study are spread over a wide range, from 5 to 16 US mills/kWh. In order to understand better the reasons for this wide diversity in nuclear OMC projections, the NEA set up an Expert Group. The focus of this study was on projected OMC that were reported in the past EGC studies, but the Group studied actual OMC experienced from existing units, because knowledge or experience concerning actual OMC certainly influences the choice of assumptions or calculation procedure for estimating OMC for future plants. Cost informations from 14 NEA countries have been analysed on the basis of a standardized framework of detailed components of OMC costs. The rationale for different OMC cost projections reported in previous NEA studies on generation cost is discussed and suggestions are made for future studies on both generation cost and OMC cost. Despite the methodological approach and the reduced extent of differences when excluding exceptional figures, it was not possible fully to clarify the origins and to understand the remaining differences in OMC figures. Several countries which have a long and a good experience of operating nuclear units did not provide sufficient detailed data or did not provide any quantitative data at all. (J.S.). 14 refs., 5 figs., 19 tabs., 4 annexes

  4. Cost drivers for the assessment of nuclear power plant life extension

    International Nuclear Information System (INIS)

    2002-09-01

    In the period of the nineteen-sixties to eighties, nuclear power had rapidly expanded in many countries of the world. The nuclear power plants built in this period, will reach the end of their planned life in the near future. Statistics drawn from IAEA's Power Reactor Information System (PRIS) indicate that, by the end of 2001, there were 175 nuclear power units (NPPs) with about 122 GWe of net electrical capacity, having 21 to 45 years of operation. This represents about 34% of the total installed nuclear capacity in the world. Since these plants were initially designed for 30-40 years of operation, utilities operating such NPPs will now have to consider whether they will shutdown, decommission, and replace the plants reaching the end of their planned life, or refurbish the plants and extend their original design life. This decision is quite complex, involving a number of political, technical and economic issues. Finally, the utilities involved should manage their assets in a manner that is as close as practicable to the best possible economic optimum scenario. Well before the end of the plant life, NPP operators must evaluate the technical and economic feasibility for PLEX options, seek and obtain regulatory approvals, and implement PLEX schemes that are justified. Often they also have to substantiate the planned life extension, including the economic viability to the relevant governmental bodies, as well as to assure the general public acceptance. Economic feasibility analysis requires cost data that are not readily available. A recent IAEA review of published information on costs of PLEX revealed the scarcity of published information, while the estimated costs of NPP decommissioning are widely available. This is due in part to the reluctance by NPP operators to divulge the cost data that are considered commercial/confidential, as more plant operators are being privatised, and in part to the absence of a common framework and methodology to account for the

  5. Clinical and cost effectiveness-related aspects of retransfusion in total hip and knee arthroplasty.

    Science.gov (United States)

    Dobosz, Bartłomiej; Dutka, Julian; Dutka, Lukasz; Maleta, Paweł

    2012-01-01

    An increasing demand for blood products forces the rationalisation of management and conservation of blood. The aim of the study is to evaluate the possibility of retransfusion of blood conservation and the cost-effectiveness of this procedure when employed in Total Hip Replacement and Total Knee Arthroplasty. This prospective cohort study involved two groups of patients. Group I comprised 50 patients who underwent blood retransfusion and in several cases had supplementary allogeneic transfusion. Group II, a control group, consisted of 50 patients who did not receive retransfusion. The retransfusion in Group I enabled the recovery of a mean amount of 364.5 ml (± 52.7) of blood in THR patients and 403.8 ml (± 110.7) in TKA patients. Demand for allogeneic blood transfusions in Group I versus Group II was 46% lower in THR patients and 42% lower in TKA patients. The blood recovered for retransfusion is biologically valuable with regard to cellular elements and plasma chemistries. In the costs evaluation, the total savings in Group I were 5,000 PLN. Retransfusion of recuperated blood from postoperative drainage tubing is a simple and safe method that provides clinical and cost-effectiveness advantages.

  6. Decommissioning costs of WWER-440 nuclear power plants. Interim report: Data collection and preliminary evaluations

    International Nuclear Information System (INIS)

    2002-11-01

    Based on the interest in decommissioning costs within Member States, especially in WWER- 440 operating countries that face the complex decision about continued operation vs. decommissioning in the near future, the IAEA launched the task to prepare a technical document on decommissioning costs of WWER-440 nuclear power plants. The main objectives of this publication were to present the decommissioning costs of WWER-440 NPPs in a uniform manner, i.e. using the cost item and cost group system of the Interim Technical Document on Nuclear Decommissioning 'A Proposed Standardised List of Items for Costing Purposes' developed jointly by the EC, the IAEA and the OECD Nuclear Energy Agency (NEA), and providing, as such, a basis for understanding decommissioning costs differences. Member States operating WWER-440 NPPs or having such units under shutdown or even under decommissioning conditions have been requested to provide cost estimates and other input data in order to facilitate understanding of their cost figures. Both decommissioning options, i.e. immediate decommissioning and safe enclosure, have been considered. In the aforementioned joint Interim Technical Document, cost items related to activities that are carried out with a similar emphasis, whether or not tied to a similar time schedule for decommissioning, or that are based on overall activities that cannot be categorised in a specific time period, are grouped as follows: pre-decommissioning actions; facility shutdown activities; procurement of general equipment and material; dismantling activities; waste processing, storage and disposal; site security, surveillance and maintenance; site restoration, cleanup and landscaping; project management, engineering and site support; research and development; fuel and nuclear material; other costs. Before starting implementation of the study, agreement was obtained on general financial, technical and social boundary conditions that should be used in order to facilitate

  7. THE BREAKEVEN POINT GIVEN LIMIT COST USING BIOMASS CHP PLANT

    Directory of Open Access Journals (Sweden)

    Paula VOICU

    2015-06-01

    Full Text Available Biomass is a renewable source, non-fossil, from which can be obtained fuels, which can be used in power generation systems. The main difference of fossil fuels is the availability biomass in nature and that it is in continue "reproduction". The use its enable the use of materials that could be destined destruction, as a source of energy "renewable", though result with many ecological values. In this paper we will study, applying a calculation model in view optimal sizing of the cogeneration plant based on biomass, biomass cost limit for the net present value is zero. It will consider that in cogeneration systems and in heating peak systems using biomass. After applying the mathematical model for limit value of biomass cost will determine the nominal optimal coefficient of cogeneration, for which discounted net revenue value is zero. Optimal sizing of CHP plants based on using biomass will be given by optimum coefficient of cogeneration determined following the application of the proposed mathematical model.

  8. Power plant asset market evaluations: Forecasting the costs of power production

    Energy Technology Data Exchange (ETDEWEB)

    Lefton, S.A.; Grunsrud, G.P. [Aptech Engineering Services, Inc., Sunnyvale, CA (United States)

    1998-12-31

    This presentation discusses the process of evaluating and valuing power plants for sale. It describes a method to forecast the future costs at a power plant using a portion of the past fixed costs, variable energy costs, and most importantly the variable cycling-related wear-and-tear costs. The presentation then discusses how to best determine market share, expected revenues, and then to forecast plant future costs based on future expected unit cycling operations. The presentation concludes with a section on recommendations to power plant buyers or sellers on how to manage the power plant asset and how to increase its market value. (orig.) 4 refs.

  9. Power plant asset market evaluations: Forecasting the costs of power production

    Energy Technology Data Exchange (ETDEWEB)

    Lefton, S A; Grunsrud, G P [Aptech Engineering Services, Inc., Sunnyvale, CA (United States)

    1999-12-31

    This presentation discusses the process of evaluating and valuing power plants for sale. It describes a method to forecast the future costs at a power plant using a portion of the past fixed costs, variable energy costs, and most importantly the variable cycling-related wear-and-tear costs. The presentation then discusses how to best determine market share, expected revenues, and then to forecast plant future costs based on future expected unit cycling operations. The presentation concludes with a section on recommendations to power plant buyers or sellers on how to manage the power plant asset and how to increase its market value. (orig.) 4 refs.

  10. Power plant asset market evaluations: Forecasting the costs of power production

    International Nuclear Information System (INIS)

    Lefton, S.A.; Grunsrud, G.P.

    1998-01-01

    This presentation discusses the process of evaluating and valuing power plants for sale. It describes a method to forecast the future costs at a power plant using a portion of the past fixed costs, variable energy costs, and most importantly the variable cycling-related wear-and-tear costs. The presentation then discusses how to best determine market share, expected revenues, and then to forecast plant future costs based on future expected unit cycling operations. The presentation concludes with a section on recommendations to power plant buyers or sellers on how to manage the power plant asset and how to increase its market value. (orig.) 4 refs

  11. Cost effective decommissioning and dismantling of nuclear power plants

    International Nuclear Information System (INIS)

    Wasinger, Karl

    2012-01-01

    As for any large and complex project, the basis for cost effective decommissioning and dismantling of nuclear power plants is established with the development of the project. Just as its construction, dismantling of a nuclear power plant is similarly demanding. Daily changing situations due to the progress of construction - in the present case progress of dismantling - result in significant logistical challenges for project managers and site supervisors. This will be aggravated by the fact that a considerable amount of the removed parts are contaminated or even activated. Hence, not only occupational health, safety and environmental protection is to be assured, employees, public and environment are to be adequately protected against the adverse effect of radioactive radiation as well. Work progress and not least expenses involved with the undertaking depend on adherence to the planned course of actions. Probably the most frequent cause of deviation from originally planned durations and costs of a project are disruptions in the flow of work. For being enabled to counteract in a timely and efficient manner, all required activities are to be comprehensively captured with the initial planning. The effect initial activities may have on subsequent works until completion must particularly be investigated. This is the more important the larger and more complex the project actually are. Comprehensive knowledge of all the matters which may affect the progress of the works is required in order to set up a suitable work break-down structure; such work break-down structure being indispensable for successful control and monitoring of the project. In building the related organizational structure of the project, all such stakeholders not being direct part of the project team but which may potentially affect the progress of the project are to be considered as well. Cost effective and lost time injury free dismantling of decommissioned nuclear power plants is based on implementing

  12. Changes in Energy Cost and Total External Work of Muscles in Elite Race Walkers Walking at Different Speeds

    Directory of Open Access Journals (Sweden)

    Chwała Wiesław

    2014-12-01

    Full Text Available The aim of the study was to assess energy cost and total external work (total energy depending on the speed of race walking. Another objective was to determine the contribution of external work to total energy cost of walking at technical, threshold and racing speed in elite competitive race walkers.

  13. Episode of Care Payments in Total Joint Arthroplasty and Cost Minimization Strategies.

    Science.gov (United States)

    Nwachukwu, Benedict U; O'Donnell, Evan; McLawhorn, Alexander S; Cross, Michael B

    2016-02-01

    Total joint arthroplasty (TJA) is receiving significant attention in the US health care system for cost containment strategies. Specifically, payer organizations have embraced and are implementing bundled payment schemes in TJA. Consequently, hospitals and providers involved in the TJA care cycle have sought to adapt to the new financial pressures imposed by episode of care payment models by analyzing what components of the total "event" of a TJA are most essential to achieve a good outcome after TJA. As part of this review, we analyze and discuss a health economic study by Snow et al. As part of their study, the authors aimed to understand the association between preoperative physical therapy (PT) and post-acute care resource utilization, and its effect on the total cost of care during total joint arthroplasty. The purpose of this current review therefore is to (1) describe and analyze the findings presented by Snow et al. and (2) provide a framework for analyzing and critiquing economic analyses in orthopedic surgery. The study under review, while having important strengths, has several notable limitations that are important to keep in mind when making policy and coverage decisions. We support cautious interpretation and application of study results, and we encourage maintained attention to economic analysis in orthopedics as well as continued care path redesign to maximize value for patients and health care providers.

  14. Removal of two polycyclic musks in sewage treatment plants: Freely dissolved and total concentrations

    NARCIS (Netherlands)

    Artola-Garicano, E.; Borkent, I.; Hermens, J.L.M.; Vaes, W.H.J.

    2003-01-01

    In the current study, the removal of slowly degradable hydrophobic chemicals in sewage treatment plants (STPs) has been evaluated with emphasis on the combination of free and total concentration data. Free and total concentrations of two polycyclic musks were determined in each compartment of four

  15. Methodology of Evaluation of the Impact of Picking Area Location on the Total Costs of Warehouse

    Directory of Open Access Journals (Sweden)

    Apsalons Raitis

    2017-12-01

    Full Text Available The picking system and the layout of the picking area are the key drivers for the evaluation of a warehouse picking cost. There are five variants for organizing the picking process of orders in a warehouse. The choice of a specific variant depends on the total cost of picking. The picking cost is evaluated within an uninterrupted picking process. It means that no stock out occurs in the time period of the picking process. The storing area and the picking area are created as two separate zones for picking quantities of the customer’s orders; the principle of division of orders is observed strictly. Referring to the locations of stock keeping units (SKU, two approaches of the layout of SKU in the picking area can be estimated. The first one is the single picking location for each single SKU, where replenishment is realized in the picking process. The second one - various picking locations for each single SKU, and the replenishment here is realized just only prior to a picking process or after it. The main benefits of the economy of the picking cost as far as these two approaches are concerned are the shortest picking route in the first case and one common replenishment option in the second case.

  16. Handbook for cost estimating. A method for developing estimates of costs for generic actions for nuclear power plants

    International Nuclear Information System (INIS)

    Ball, J.R.; Cohen, S.; Ziegler, E.Z.

    1984-10-01

    This document provides overall guidance to assist the NRC in preparing the types of cost estimates required by the Regulatory Analysis Guidelines and to assist in the assignment of priorities in resolving generic safety issues. The Handbook presents an overall cost model that allows the cost analyst to develop a chronological series of activities needed to implement a specific regulatory requirement throughout all applicable commercial LWR power plants and to identify the significant cost elements for each activity. References to available cost data are provided along with rules of thumb and cost factors to assist in evaluating each cost element. A suitable code-of-accounts data base is presented to assist in organizing and aggregating costs. Rudimentary cost analysis methods are described to allow the analyst to produce a constant-dollar, lifetime cost for the requirement. A step-by-step example cost estimate is included to demonstrate the overall use of the Handbook

  17. Estimation of the Levelised Electricity Generation Cost for a PWR-Power Plant and Preliminary Evaluation of National Participation

    International Nuclear Information System (INIS)

    Saba, G; Hainoun, A

    2008-01-01

    This work deals with the detailed economic evaluation of the Levelised discounted electricity generation costs (LDEGC) for a nuclear power plant with pressurized water reactor (PWR). The total generation costs are splited in base construction costs, supplementary costs, owner's costs, financial costs, fuel cycle costs and operation and maintenance costs. The evaluation covers also the sensitivity of the estimated energy unit cost to various factors (real annual discount rate, escalation rate, interest rate, load factor, ..) including the role of national participation, that depends upon the development of national infrastructure. For performing this study the IAEA's program package for economic bid evaluation (Bideval-3) has been employed. The program is designed to assist the user in the economic evaluation of bids for nuclear power plant (NPP). It follows the recommended method of determining the present worth value of all costs components for generated electricity unit. The performed study aims at developing national expertise in the field of bid evaluation for electric power plants with main emphasis on NPP. Additional goal is to convoying the technical and economic development of NPP technology that can help in supporting the decision maker with adequate information related to the future development of energy supply system and measures required for ensuring national energy supply security. (author)

  18. Cost-effectivness analysis of total thyroidectomy vs radioiodine for Graves disease

    Directory of Open Access Journals (Sweden)

    Prokić Anđelka

    2013-01-01

    Full Text Available Among the patients suffering from hyperthyroidism 60-80% have Graves' disease. The initial therapy of Graves's disease are antithyroid drugs. If the remission is not achieved after 12-18 months, the patients should be directed to surgical treatment or to the therapy with radioactive iodine. The aim of this study was to compare cost/effectiveness ratios for radioactive iodine and total thyroidectomy. The analysis was made using Markov model, from the perspective of Republic Fund for Health Insurance in Serbia. Duration of one cycle in the model is six months, and the time horizon is 30 years. Monte Carlo simulation was performed for 1000 virtual patients as well as the analysis of sensitivity with the variation of parameters ± 50%. For total thyroidectomy the insurance should provide 138.389,72 RSD / 57, 83 QALY i.e. 2.393,04 dinars for one quality-adjusted life year, and for radioactive iodine the insurance should provide 110.043,64 RSD / 57,82 QALY i.e. 1.903,37 dinars for one quality-adjusted life year. This economic analysis showed that radioactive iodine has better ratio of costs to clinical effectiveness as opposed to total thyroidectomy.

  19. Manual of phosphoric acid fuel cell power plant cost model and computer program

    Science.gov (United States)

    Lu, C. Y.; Alkasab, K. A.

    1984-01-01

    Cost analysis of phosphoric acid fuel cell power plant includes two parts: a method for estimation of system capital costs, and an economic analysis which determines the levelized annual cost of operating the system used in the capital cost estimation. A FORTRAN computer has been developed for this cost analysis.

  20. Efficiency and Cost Analysis of Cell Saver Auto Transfusion System in Total Knee Arthroplasty

    Directory of Open Access Journals (Sweden)

    Mustafa Gökhan Bilgili

    2014-06-01

    Full Text Available Background: Blood loss and replacement is still a controversial issue in major orthopaedic surgery. Allogenic blood transfusion may cause legal problems and concerns regarding the transmission of transfusion-related diseases. Cellsaver Systems (CSS were developed as an alternative to allogenic transfusion but CSS transfusion may cause coagulation, infection and haemodynamic instability. Aims: Our aim was to analyse the efficiency and cost analysis of a cell saver auto-transfusion system in the total knee arthroplasty procedure. Study Design: Retrospective comparative study. Methods: Those patients who were operated on by unilateral, cemented total knee arthroplasty (TKA were retrospectively evaluated. Group 1 included 37 patients who were treated using the cell saver system, and Group 2 involved 39 patients who were treated by allogenic blood transfusion. The groups were compared in terms of preoperative haemoglobin and haematocrit levels, blood loss and transfusion amount, whether allogenic transfusion was made, degree of deformity, body mass index and cost. Results: No significant results could be obtained in the statistical comparisons made in terms of the demographic properties, deformity properties, preoperative laboratory values, transfusion amount and length of hospital stay of the groups. Average blood loss was calculated to be less in Group 1 (p<0.05 and cost was higher in Group 1 (p<0.05. Conclusion: Cell saver systems do not decrease the amount of allogenic blood transfusion and costs more. Therefore, the routine usage of the auto-transfusion systems is a controversial issue. Cell saver system usage does not affect allogenic blood transfusion incidence or allogenic blood transfusion volume. It was found that preoperative haemoglobin and body mass index rates may affect allogenic blood transfusion. Therefore, it is foreseen that auto-transfusion systems could be useful in patients with low haemoglobin level and body mass index.

  1. Industrial plant electrical systems: Simplicity, reliability, cost savings, redundancies

    International Nuclear Information System (INIS)

    Silvestri, A.; Tommazzolli, F.; Pavia Univ.

    1992-01-01

    This article represents a compact but complete design and construction manual for industrial plant electrical systems. It is to be used by design engineers having prior knowledge of local power supply routes and voltages and regards principally the optimum choice of internal distribution systems which can be radial or single, double ringed or with various network configurations, and with single or multiple supplies, and many or few redundancies. After giving guidelines on the choosing of these options, the manual deals with problematics relevant to suitable cable sizing. A cost benefit benefit analysis method is suggested for the choice of the number of redundancies. Recommendations are given for the choice of transformers, motorized equipment, switch boards and circuit breakers. Reference is made to Italian electrical safety and building codes

  2. Low-Cost Methane Liquefaction Plant and Vehicle Refueling Station

    International Nuclear Information System (INIS)

    Wilding, B.; Bramwell, D.

    1999-01-01

    The Idaho National Engineering and Environmental Laboratory (INEEL) is currently negotiating a collaborative effort with Pacific Gas and Electric (PG and E) that will advance the use of liquefied natural gas (LNG) as a vehicle fuel. We plan to develop and demonstrate a small-scale methane liquefaction plant (production of 5,000 to 10,000 gallons per day) and a low-cost ($150,000) LNG refueling station to supply fuel to LNG-powered transit buses and other heavy-duty vehicles. INEEL will perform the research and development work. PG and E will deploy the new facilities commercially in two demonstration projects, one in northern California, and one in southern California

  3. Reduction of operations and maintenance costs at geothermal power plants

    Energy Technology Data Exchange (ETDEWEB)

    Bruton, C.J.; Stevens, C.G.; Rard, J.A.; Kasameyer, P.W. [Lawrence Livermore National Lab., CA (United States)

    1997-12-31

    To reduce chemical costs at geothermal power plants, we are investigating: (a) improved chemical processes associated with H{sub 2}S abatement techniques, and (b) the use of cross dispersive infrared spectrometry to monitor accurately, reliably, and continuously H{sub 2}S emissions from cooling towers. The latter is a new type of infrared optical technology developed by LLNL for non-proliferation verification. Initial work is focused at The Geysers in cooperation with Pacific Gas and Electric. Methods for deploying the spectrometer on-site at The Geysers are being developed. Chemical analysis of solutions involved in H{sub 2}S abatement technologies is continuing to isolate the chemical forms of sulfur produced.

  4. Patterns of pharmacotherapy and health care utilization and costs prior to total hip or total knee replacement in patients with osteoarthritis.

    Science.gov (United States)

    Berger, Ariel; Bozic, Kevin; Stacey, Brett; Edelsberg, John; Sadosky, Alesia; Oster, Gerry

    2011-08-01

    To examine patterns of pharmacotherapy and health care utilization and costs prior to total knee replacement (TKR) or total hip replacement (THR) in patients with osteoarthritis (OA). Using a large US health insurance claims database, we identified all patients with OA who were ages ≥40 years and had undergone TKR or THR between January 1, 2006 and December 31, 2007. Patients with care utilization and costs over the 2-year period preceding surgery. A total of 16,527 patients met all study entry criteria. Their mean ± SD age was 56.6 ± 6.1 years, and 56% of them were women. In the 2 years preceding surgery, 55% of patients received prescription nonsteroidal antiinflammatory drugs, 58% received opioids, and 50% received injections of corticosteroids. The numbers of patients receiving these drugs increased steadily during the presurgery period. The mean ± SD total health care costs in the 2 years preceding surgery were $19,466 ± 29,869, of which outpatient care, inpatient care, and pharmacotherapy represented 45%, 20%, and 20%, respectively. Costs increased from $2,094 in the eighth calendar quarter prior to surgery to $3,100 in the final quarter. Patients with OA who undergo THR or TKR have relatively high levels of use of pain-related pharmacotherapy and high total health care costs in the 2-year period preceding surgery. Levels of utilization and cost increase as the date of surgery approaches. Copyright © 2011 by the American College of Rheumatology.

  5. Accumulation of total mercury and methylmercury in rice plants collected from different mining areas in China

    International Nuclear Information System (INIS)

    Meng, Mei; Li, Bing; Shao, Jun-juan; Wang, Thanh; He, Bin; Shi, Jian-bo; Ye, Zhi-hong; Jiang, Gui-bin

    2014-01-01

    A total of 155 rice plants were collected from ten mining areas in three provinces of China (Hunan, Guizhou and Guangdong), where most of mercury (Hg) mining takes place in China. During the harvest season, whole rice plants were sampled and divided into root, stalk and leaf, husk and seed (brown rice), together with soil from root zone. Although the degree of Hg contamination varied significantly among different mining areas, rice seed showed the highest ability for methylmercury (MeHg) accumulation. Both concentrations of total mercury (THg) and MeHg in rice plants were significantly correlated with Hg levels in soil, indicating soil is still an important source for both inorganic mercury (IHg) and MeHg in rice plants. The obvious discrepancy between the distribution patterns of THg and MeHg reflected different pathways of IHg and MeHg accumulation. Water soluble Hg may play more important role in MeHg accumulation in rice plants. -- Highlights: • Distribution patterns indicated different pathways of IHg and MeHg accumulation. • Soil is an important source for both THg and MeHg to rice plants. • Water soluble Hg may play more important role in MeHg accumulation in rice plants. -- The distribution patterns indicate different pathways of IHg and MeHg accumulation in rice plants

  6. Cost and availability of gadolinium for nuclear fuel reprocessing plants

    International Nuclear Information System (INIS)

    Klepper, O.H.

    1985-06-01

    Gadolinium is currently planned for use as a soluble neutron poison in nuclear fuel reprocessing plants to prevent criticality of solutions of spent fuel. Gadolinium is relatively rare and expensive. The present study was undertaken therefore to estimate whether this material is likely to be available in quantities sufficient for fuel reprocessing and at reasonable prices. It was found that gadolinium, one of 16 rare earth elements, appears in the marketplace as a by-product and that its present supply is a function of the production rate of other more prevalent rare earths. The potential demand for gadolinium in a fuel reprocessing facility serving a future fast reactor industry amounts to only a small fraction of the supply. At the present rate of consumption, domestic supplies of rare earths containing gadolinium are adequate to meet national needs (including fuel reprocessing) for over 100 years. With access to foreign sources, US demands can be met well beyond the 21st century. It is concluded therefore that the supply of gadolinium will quite likely be more than adequate for reprocessing spent fuel for the early generation of fast reactors. The current price of 99.99% pure gadolinium oxide lies in the range $50/lb to $65/lb (1984 dollars). By the year 2020, in time for reprocessing spent fuel from an early generation of large fast reactors, the corresponding values are expected to lie in the $60/lb to $75/lb (1984 dollars) price range. This increase is modest and its economic impact on nuclear fuel reprocessing would be minor. The economic potential for recovering gadolinium from the wastes of nuclear fuel reprocessing plants (which use gadolinium neutron poison) was also investigated. The cost of recycled gadolinium was estimated at over twelve times the cost of fresh gadolinium, and thus recycle using current recovery technology is not economical. 15 refs., 4 figs., 11 tabs

  7. Life-cycle cost assessment of seismically base-isolated structures in nuclear power plants

    International Nuclear Information System (INIS)

    Wang, Hao; Weng, Dagen; Lu, Xilin; Lu, Liang

    2013-01-01

    Highlights: • The life-cycle cost of seismic base-isolated nuclear power plants is modeled. • The change law of life-cycle cost with seismic fortification intensity is studied. • The initial cost of laminated lead rubber bearings can be expressed as the function of volume. • The initial cost of a damper can be expressed as the function of its maximum displacement and tonnage. • The use of base-isolation can greatly reduce the expected damage cost, which leads to the reduction of the life-cycle cost. -- Abstract: Evaluation of seismically base-isolated structural life-cycle cost is the key problem in performance based seismic design. A method is being introduced to address the life-cycle cost of base-isolated reinforced concrete structures in nuclear power plants. Each composition of life-cycle cost is analyzed including the initial construction cost, the isolators cost and the excepted damage cost over life-cycle of the structure. The concept of seismic intensity is being used to estimate the expected damage cost, greatly simplifying the calculation. Moreover, French Cruas nuclear power plant is employed as an example to assess its life-cycle cost, compared to the cost of non-isolated plant at the same time. The results show that the proposed method is efficient and the expected damage cost is enormously reduced because of the application of isolators, which leads to the reduction of the life-cycle cost of nuclear power plants

  8. Small, modular, low-cost coal-fired power plants for the international market

    Energy Technology Data Exchange (ETDEWEB)

    Zauderer, B.; Frain, B.; Borck, B. [Coal Tech Corp., Merion Station, PA (United States); Baldwin, A.L. [Dept. of Energy, Pittsburgh, PA (United States). Pittsburgh Energy Technology Center

    1997-12-31

    This paper presents recent operating results of Coal Tech`s second generation, air cooled, slagging coal combustor, and its application to power plants in the 1 to 20 MW range. This 20 MMBtu/hour combustor was installed in a new demonstration plant in Philadelphia, PA in 1995. It contains the combustion components of a 1 MWe coal fired power plant, a 17,500 lb/hour steam boiler, coal storage and feed components, and stack gas cleanup components. The plant`s design incorporates improvements resulting from 2,000 hours of testing between 1987 and 1993 on a first generation, commercial scale, air cooled combustor of equal thermal rating. Since operations began in early 1996, a total of 51 days of testing have been successfully completed. Major results include durability of the combustor`s refractory wall, excellent combustion with high ash concentration in the fuel, removal of 95% to 100% of the slag in the combustor, very little ash deposition in the boiler, major reduction of in-plant parasitic power, and simplified power system control through the use of modular designs of sub-systems and computer control. Rapid fuel switching between oil, gas, and coal and turndown of up to a factor of three was accomplished. All these features have been incorporated in advanced coal fired plant designs in the 1 to 20 MWe range. Incremental capital costs are only $100 to $200/kW higher than comparable rated gas or oil fired steam generating systems. Most of its components and subsystems can be factory assembled for very rapid field installation. The low capital, low operating costs, fuel flexibility, and compatibility with very high ash fuels, make this power system very attractive in regions of the world having domestic supplies of these fuels.

  9. 48 CFR 945.505-11 - Records of transportation and installation costs of plant equipment.

    Science.gov (United States)

    2010-10-01

    ... and installation costs of plant equipment. 945.505-11 Section 945.505-11 Federal Acquisition Regulations System DEPARTMENT OF ENERGY CONTRACT MANAGEMENT GOVERNMENT PROPERTY Management of Government... plant equipment. The requirements of FAR 45.505-11 apply to plant equipment having a unit cost of $1,000...

  10. Cost determination of the electro-mechanical equipment of a small hydro-power plant

    Energy Technology Data Exchange (ETDEWEB)

    Ogayar, B.; Vidal, P.G. [Grupo de Investigacion IDEA, Escuela Politecnica Superior, University of Jaen, Campus de Las Lagunillas, s/n. 23071-Jaen (Spain)

    2009-01-15

    One of the most important elements on the recovery of a small hydro-power plant is the electro-mechanical equipment (turbine-alternator), since the cost of the equipment means a high percentage of the total budget of the plant. The present paper intends to develop a series of equations which determine its cost from basic parameters such as power and net head. These calculations are focused at a level of previous study, so it will be necessary to carry out the engineering project and request a budget to companies specialized on the construction of electro-mechanical equipment to know its cost more accurately. Although there is a great diversity in the typology of turbines and alternators, data from manufacturers which cover all the considered range have been used. The above equations have been developed for the most common of turbines: Pelton, Francis, Kaplan and semiKaplan for a power range below 2 MW. The obtained equations have been validated with data from real installations which have been subject to analysis by engineering companies working on the assembly and design of small plants. (author)

  11. Social profile and cost analysis of deep infection following total hip replacement surgery

    Directory of Open Access Journals (Sweden)

    Vera Lucia Frazão

    Full Text Available ABSTRACT OBJECTIVE: To characterize the socio-economic and demographic profile of patients undergoing surgery for revision total hip arthroplasty regarding the diagnosis of deep prosthetic infection. METHODS: Twenty patients were retrospectively studied, admitted in the period between 2009 and 2010 by the Hip Surgery Group with the diagnosis of deep prosthetic infection, whose proposed treatment was surgical. This study was carried out in the presence of the patient by completing two forms applied by the social worker of the Group. RESULTS: In a 20-patient sample, 40% were male, 45% were working age, 50% of patients originated from the capital, 85% depended on benefits, 70% were retired, 60% of patients were from this hospital, and 40% were from other services. The average cost of patients to the public system was R$ 55,821.62 per patient and the total spent on treatment of patients in the study exceeded one million Brazilian reals, totalling R$ 1,116,432.40. CONCLUSION: Infection from total hip arthroplasty generates a major expense to the social security system and to the public healthcare system. Physicians must always be alert to the possible risk factors and perioperative care, striving to minimize this complication.

  12. DENINT power plant cost benefit analysis code: Analysis of methane fuelled power plant/district heating system

    International Nuclear Information System (INIS)

    Cincotti, V.; D'Andrea, A.

    1989-07-01

    The DENINT power plant cost benefit analysis code takes into consideration, not only power production costs at the generator terminals, but also, in the case of cogeneration, the costs of the fuel supply and heat and power distribution systems which depend greatly on the location of the plant. The code is able to allow comparisons of alternatives with varying annual operation hours, fuel cost increases, and different types of fossil fuels and production systems. For illustrative purposes, this paper examines two methane fired cogeneration plant/district heating alternatives

  13. Blood Transfusion During Total Ankle Arthroplasty Is Associated With Increased In-Hospital Complications and Costs.

    Science.gov (United States)

    Ewing, Michael A; Huntley, Samuel R; Baker, Dustin K; Smith, Kenneth S; Hudson, Parke W; McGwin, Gerald; Ponce, Brent A; Johnson, Michael D

    2018-04-01

    Total ankle arthroplasty (TAA) is an increasingly used, effective treatment for end-stage ankle arthritis. Although numerous studies have associated blood transfusion with complications following hip and knee arthroplasty, its effects following TAA are largely unknown. This study uses data from a large, nationally representative database to estimate the association between blood transfusion and inpatient complications and hospital costs following TAA. Using the Nationwide Inpatient Sample (NIS) database from 2004 to 2014, 25 412 patients who underwent TAA were identified, with 286 (1.1%) receiving a blood transfusion. Univariate analysis assessed patient and hospital factors associated with blood transfusion following TAA. Patients requiring blood transfusion were more likely to be female, African American, Medicare recipients, and treated in nonteaching hospitals. Average length of stay for patients following transfusion was 3.0 days longer, while average inpatient cost was increased by approximately 50%. Patients who received blood transfusion were significantly more likely to suffer from congestive heart failure, peripheral vascular disease, hypothyroidism, coagulation disorder, or anemia. Acute renal failure was significantly more common among patients receiving blood transfusion ( P < .001). Blood transfusions following TAA are infrequent and are associated with multiple medical comorbidities, increased complications, longer hospital stays, and increased overall cost. Level III: Retrospective, comparative study.

  14. Total staff costs to implement a decision support system in nursing

    Directory of Open Access Journals (Sweden)

    Valéria Castilho

    2014-01-01

    Full Text Available OBJECTIVE: to identify the direct labor (DL costs to put in practice a decision support system (DSS in nursing at the University Hospital of the University of São Paulo (HU-USP. METHOD: the development of the DSS was mapped in four sub-processes: Conception, Elaboration, Construction and Transition. To calculate the DL, the baseline salary per professional category was added to the five-year additional remuneration, representation fees and social charges, and then divided by the number of hours contracted, resulting in the hour wage/professional, which was multiplied by the time spend on each activity in the sub-processes. RESULTS: the DL cost corresponded to R$ 752,618.56 (100%, R$ 26,000.00 (3.45% of which were funded by a funding agency, while R$ 726,618.56 (96,55% came from Hospital and University resources. CONCLUSION: considering the total DL cost, 72.1% related to staff wages for the informatics consulting company and 27.9% to the DL of professionals at the HU and the School of Nursing.

  15. Efficiency and cost analysis of cell saver auto transfusion system in total knee arthroplasty.

    Science.gov (United States)

    Bilgili, Mustafa Gökhan; Erçin, Ersin; Peker, Gökhan; Kural, Cemal; Başaran, Serdar Hakan; Duramaz, Altuğ; Avkan, Cevdet

    2014-06-01

    Blood loss and replacement is still a controversial issue in major orthopaedic surgery. Allogenic blood transfusion may cause legal problems and concerns regarding the transmission of transfusion-related diseases. Cellsaver Systems (CSS) were developed as an alternative to allogenic transfusion but CSS transfusion may cause coagulation, infection and haemodynamic instability. Our aim was to analyse the efficiency and cost analysis of a cell saver auto-transfusion system in the total knee arthroplasty procedure. Retrospective comparative study. Those patients who were operated on by unilateral, cemented total knee arthroplasty (TKA) were retrospectively evaluated. Group 1 included 37 patients who were treated using the cell saver system, and Group 2 involved 39 patients who were treated by allogenic blood transfusion. The groups were compared in terms of preoperative haemoglobin and haematocrit levels, blood loss and transfusion amount, whether allogenic transfusion was made, degree of deformity, body mass index and cost. No significant results could be obtained in the statistical comparisons made in terms of the demographic properties, deformity properties, preoperative laboratory values, transfusion amount and length of hospital stay of the groups. Average blood loss was calculated to be less in Group 1 (pblood transfusion and costs more. Therefore, the routine usage of the auto-transfusion systems is a controversial issue. Cell saver system usage does not affect allogenic blood transfusion incidence or allogenic blood transfusion volume. It was found that preoperative haemoglobin and body mass index rates may affect allogenic blood transfusion. Therefore, it is foreseen that auto-transfusion systems could be useful in patients with low haemoglobin level and body mass index.

  16. [A totally implantable venous access device. Implantation in general or local anaesthesia? A retrospective cost analysis].

    Science.gov (United States)

    Schuld, J; Richter, S; Moussavian, M R; Kollmar, O; Schilling, M K

    2009-08-01

    Implantation of venous access port systems can be performed in local or general anesthesia. In spite of the increasing rate of interventionally implanted systems, the surgical cut-down represents a safe alternative. Thus, the question arises whether--in context to the increasing health-economic pressure--open implantation in general anesthesia is still a feasible alternative to implantation in local anesthesia regarding OR efficiency and costs. In a retrospective analysis, 993 patients receiving a totally implantable venous access device between 2001 and 2007 were evaluated regarding OR utilization, turnover times, intraoperative data and costs. Implantations in local (LA) and general anesthesia (GA) were compared. GA was performed in 762 cases (76.6 %), LA was performed in 231 patients (23.3 %). Mean operation time was similar in both groups (LA 47.27 +/- 1.40 min vs. GA 45.41 +/- 0.75 min, p = 0.244). Patients receiving local anesthesia had a significantly shorter stay in the OR unit (LA 95.9 +/- 1.78 min vs. GA 105.92 +/- 0.92 min; p cut (LA 39.57 +/- 0.69 min vs. GA 50.46 +/- 0.52 min; p material costs were significantly lower in the LA group compared with the GA group (LA: 400.72 +/- 8.25 euro vs. GA: 482.86 +/- 6.23 euro; p systems in local anesthesia is superior in comparison to the implantation under general anesthesia regarding procedural times in the OR unit and costs. With the same operation duration, but less personnel and material expenditure, implantation in local anesthesia offers a potential economic advantage by permitting faster changing times. Implantation in GA only should be performed at a special request by the patient or in difficult venous conditions. Georg Thieme Verlag Stuttgart.New York.

  17. Technology, Safety and Costs of Decommissioning a Reference Uranium Hexafluoride Conversion Plant

    Energy Technology Data Exchange (ETDEWEB)

    Elder, H. K.

    1981-10-01

    Safety and cost information is developed for the conceptual decommissioning of a commercial uranium hexafluoride conversion (UF{sub 6}) plant. Two basic decommissioning alternatives are studied to obtain comparisons between cost and safety impacts: DECON, and passive SAFSTOR. A third alternative, DECON of the plant and equipment with stabilization and long-term care of lagoon wastes. is also examined. DECON includes the immediate removal (following plant shutdown) of all radioactivity in excess of unrestricted release levels, with subsequent release of the site for public use. Passive SAFSTOR requires decontamination, preparation, maintenance, and surveillance for a period of time after shutdown, followed by deferred decontamination and unrestricted release. DECON with stabilization and long-term care of lagoon wastes (process wastes generated at the reference plant and stored onsite during plant operation} is also considered as a decommissioning method, although its acceptability has not yet been determined by the NRC. The decommissioning methods assumed for use in each decommissioning alternative are based on state-of-the-art technology. The elapsed time following plant shutdown required to perform the decommissioning work in each alternative is estimated to be: for DECON, 8 months; for passive SAFSTOR, 3 months to prepare the plant for safe storage and 8 months to accomplish deferred decontamination. Planning and preparation for decommissioning prior to plant shutdown is estimated to require about 6 months for either DECON or passive SAFSTOR. Planning and preparation prior to starting deferred decontamination is estimated to require an additional 6 months. OECON with lagoon waste stabilization is estimated to take 6 months for planning and about 8 months to perform the decommissioning work. Decommissioning cost, in 1981 dollars, is estimated to be $5.91 million for OECON. For passive SAFSTOR, preparing the facility for safe storage is estimated to cost $0

  18. Analysis of the total system life cycle cost for the Civilian Radioactive Waste Management Program: executive summary

    International Nuclear Information System (INIS)

    1985-04-01

    The total-system life-cycle cost (TSLCC) analysis for the Department of Energy's Civilian Radioactive Waste Management Progrram is an ongoing activity that helps determine whether the revenue-producing mechanism established by the Nuclear Waste Policy Act of 1982 is sufficient to cover the cost of the program. This report is an input into the third evaluation of the adequacy of the fee. The total-system cost for the reference waste-management program in this analysis is estimated to be 24 to 30 billion (1984) dollars. For the sensitivity cases studied in this report, the costs could be as high as 35 billion dollars and as low as 21 billion dollars. Because factors like repository location, the quantity of waste generated, transportation-cask technology, and repository startup dates exert substantial impacts on total-system costs, there are several tradeoffs between these factors, and these tradeoffs can greatly influence the total cost of the program. The total-system cost for the reference program described in this report is higher by 3 to 5 billion dollars, or 15 to 20%, than the cost for the reference program of the TSLCC analysis of April 1984. More than two-thirds of this increase is in the cost of repository construction and operation. These repository costs have increased because of changing design concepts, different assumptions about the effort required to perform the necessary activities, and a change in the source data on which the earlier analysis was based. Development and evaluation costs have similarly increased because of a net addition to the work content. Transportation costs have increased because of different assumptions about repository locations and several characteristics of the transportation system. It is expected that the estimates of total-system costs will continue to change in response to both an evolving program strategy and better definition of the work required to achieve the program objectives

  19. Analysis of the total system life cycle cost for the Civilian Radioactive Waste Management Program: Volume 2, Supporting information

    International Nuclear Information System (INIS)

    1987-06-01

    This report provides cost estimates for the fifth evaluation of the adequacy of the fee and is consistent with the program strategy and plans. The total-system cost for the reference cases in the improved-performance system is estimated at $32.1 to $38.2 billion (expressed in constant 1986 collars) over the entire life of the system, or $1.5 to $1.6 billion more than that of the authorized system (i.e., the system without an MRS facility). The current estimate of the total-system cost for the reference cases in the improved-performance system is $3.8 to $5.4 billion higher than the estimate for the same system in the 1986 TSLCC analysis. In the case with the maximum increase, nearly all of the higher cost is due to a $5.2-billion increase in the costs of development and evaluation (D and E); all other system costs are essentially unchanged. The cost difference between the improved-performance system and the authorized system is smaller than the difference estimated in last year's TSLCC analysis. Volume 2 presents the detailed results for the 1987 analysis of the total-system life cycle cost (TSLCC). It consists of four sections: Section A presents the yearly flows of waste between waste-management facilities for the 12 aggregate logistics cases that were studied; Section B presents the annual total-system costs for each of the 30 TSLCC cases by major cost category; Section C presents the annual costs for the disposal of 16,000 canisters of defense high-level waste (DHLW) by major cost category for each of the 30 TSLCC cases; and Section D presents a summary of the cost-allocation factors that were calculated to determine the defense waste share of the total-system costs

  20. Nuclear and coal-fired power plant capital costs 1978 -June 1981

    International Nuclear Information System (INIS)

    Harbour, R.T.

    1981-07-01

    This bibliography covers 16 papers dealing with the economics of power generation - mainly comparisons between the capital costs of nuclear and coal fired plants. Some of the papers additionally discuss fuel, operating and maintenance costs, and performance. (U.K.)

  1. Distributed Flexibility Management Targeting Energy Cost and Total Power Limitations in Electricity Distribution Grids

    DEFF Research Database (Denmark)

    Bessler, Sanford; Kemal, Mohammed Seifu; Silva, Nuno

    2018-01-01

    Demand Management uses the interaction and information exchange between multiple control functions in order to achieve goals that can vary in different application contexts. Since there are several stakeholders involved, these may have diverse objectives and even use different architectures...... to actively manage power demand. This paper utilizes an existing distributed demand management architecture in order to provide the following contributions: (1) It develops and evaluates a set of algorithms that combine the optimization of energy costs in scenarios of variable day-ahead prices with the goal...... to improve distribution grid operation reliability, here implemented by a total Power limit. (2) It evaluates the proposed scheme as a distributed system where flexibility information is exchanged with the existing industry standard OpenADR. A Hardware-in-the-Loop testbed realization demonstrates...

  2. Noninvasive Hemoglobin Monitoring: A Rapid, Reliable, and Cost-Effective Method Following Total Joint Replacement.

    Science.gov (United States)

    Martin, J Ryan; Camp, Christopher L; Stitz, Amber; Young, Ernest Y; Abdel, Matthew P; Taunton, Michael J; Trousdale, Robert T

    2016-03-02

    Noninvasive hemoglobin (nHgb) monitoring was initially introduced in the intensive care setting as a means of rapidly assessing Hgb values without performing a blood draw. We conducted a prospective analysis to compare reliability, cost, and patient preference between nHgb monitoring and invasive Hgb (iHgb) monitoring performed via a traditional blood draw. We enrolled 100 consecutive patients undergoing primary or revision total hip or total knee arthroplasty. On postoperative day 1, nHgb and iHgb values were obtained within thirty minutes of one another. iHgb and nHgb values, cost, patient satisfaction, and the duration of time required to obtain each reading were recorded. The concordance correlation coefficient (CCC) was utilized to evaluate the agreement of the two Hgb measurement methods. Paired t tests and Wilcoxon signed-rank tests were utilized to compare mean Hgb values, time, and pain for all readings. The mean Hgb values did not differ significantly between the two measurement methods: the mean iHgb value (and standard deviation) was 11.3 ± 1.4 g/dL (range, 8.2 to 14.3 g/dL), and the mean nHgb value was 11.5 ± 1.8 g/dL (range, 7.0 to 16.0 g/dL) (p = 0.11). The CCC between the two Hgb methods was 0.69. One hundred percent of the patients with an nHgb value of ≥ 10.5 g/dL had an iHgb value of >8.0 g/dL. The mean time to obtain an Hgb value was 0.9 minute for the nHgb method and 51.1 minutes for the iHgb method (p measurement, resulting in a savings of $26 per Hgb assessment when the noninvasive method is used. Noninvasive Hgb monitoring was found to be more efficient, less expensive, and preferred by patients compared with iHgb monitoring. Providers could consider screening total joint arthroplasty patients with nHgb monitoring and only order iHgb measurement if the nHgb value is protocol had been applied to the first blood draw in our 100 patients, approximately $2000 would have been saved. Extrapolated to the U.S. total joint arthroplasty practice

  3. Polysaccharides, total flavonoids content and antioxidant activities in different parts of Silybum marianum L. plants

    Science.gov (United States)

    Sun, Jing; Li, Xinhua; Yu, Xiaolei

    2017-01-01

    Silybum marianum L. is used for the production of silymarin, a flavonoid utilized for regenerating damaged hepatic tissues. Herein, the total flavonoid content (TFC) and polysaccharides content (PC) in the roots, main stems, leaves, fruit receptacles, and pappi of Silybum marianum were determined. The antioxidant activities of plant ethanol extracts were assessed to validate the medicinal potential of the various plant parts. The pappi exhibited the highest TFC (17.10 mg rutin/g of dry plant material), followed by the fruit receptacles (15.34 mg/g). The PC varied from 3.57±0.23 to 11.02±0.35 mg glucose /g dry plant material; the highest PC was obtained from the roots. At 50 ug/mL, the pappi ethanol extract showed the highest 1, 1-Diphenyl-2-picryl-hydrazyl (DPPH) radical scavenging activity (69.68%), followed by the roots (66.02%).

  4. Clinical Outcomes and 90-Day Costs Following Hemiarthroplasty or Total Hip Arthroplasty for Hip Fracture.

    Science.gov (United States)

    Nichols, Christine I; Vose, Joshua G; Nunley, Ryan M

    2017-09-01

    In the era of bundled payments, many hospitals are responsible for costs from admission through 90 days postdischarge. Although bundled episodes for hip fracture will have a separate target price for the bundle, little is known about the 90-day resource use burden for this patient population. Using Medicare 100% Standard Analytic Files (2010-2014), we identified patients undergoing hemiarthroplasty or total hip arthroplasty (THA). Patients were aged 65 and older with admitting diagnosis of closed hip fracture, no concurrent fractures of the lower limb, and no history of hip surgery in the prior 12 months baseline. Continuous Medicare-only enrollment was required. Complications, resource use, and mortality from admission through 90 days following discharge (follow-up) were summarized. Four cohorts met selection criteria for analysis: (1) hemiarthroplasty diagnosis-related group (DRG) 469 (N = 19,634), (2) hemiarthroplasty DRG 470 (N = 77,744), (3) THA DRG 469 (N = 1686), and (4) THA DRG 470 (N = 9314). All-cause mortality during the study period was 51.6%, 29.5%, 48.1%, and 24.9% with mean 90-day costs of $28,952, $19,243, $29,763, and $18,561, respectively. Most of the patients waited 1 day from admission to surgery (41%-51%). Incidence of an all-cause complication was approximately 70% in each DRG 469 cohort and 14%-16% in each DRG 470 cohort. This study confirms patients with hip fracture are a costly subpopulation. Tailored care pathways to minimize post-acute care resource use are warranted for these patients. Copyright © 2017 The Author(s). Published by Elsevier Inc. All rights reserved.

  5. Factors Influencing the Total Inpatient Pharmacy Cost at a Tertiary Hospital in Malaysia: A Retrospective Study

    Science.gov (United States)

    Ali Jadoo, Saad Ahmed

    2018-01-01

    The steady growth of pharmaceutical expenditures is a major concern for health policy makers and health care managers in Malaysia. Our study examined the factors affecting the total inpatient pharmacy cost (TINPC) at the Universiti Kebangsaan Malaysia Medical Centre (UKMMC). In this retrospective study, we used 2011 administration electronic prescriptions records and casemix databases at UKMMC to examine the impact of sociodemographic, diagnostic, and drug variables on the TINPC. Bivariate and multivariate analyses of the factors associated with TINPC were conducted. The mean inpatient pharmacy cost per patient was USD 102.07 (SD = 24.76). In the multivariate analysis, length of stay (LOS; B = 0.349, P < .0005) and severity level III (B = 0.253, P < .0005) were the primary factors affecting the TINPC. For each day increase in the LOS and each increase of a case of severity level III, there was an increase of approximately USD 11.97 and USD 171.53 in the TINPC per year, respectively. Moreover, the number of prescribed items of drugs and supplies was positively associated with the TINPC (B = 0.081, P < .0005). Gender appears to have affected the TINPC; male patients seem to be associated with a higher TINPC than females (mean = 139.55, 95% confidence interval [CI]: 112.97-166.13, P < .001). Surgical procedures were associated with higher cost than medical cases (mean = 87.93, 95% CI: 61.00-114.85, P < .001). Malay (MYR 242.02, SD = 65.37) and Chinese (MYR 214.66, SD = 27.99) ethnicities contributed to a lower TINPC compared with Indian (MYR 613.93, SD = 98.41) and other ethnicities (MYR 578.47, SD = 144.51). A longer hospitalization period accompanied by major complications and comorbidities had the greatest influence on the TINPC. PMID:29436248

  6. A cost-benefit analysis of power generation from commercial reinforced concrete solar chimney power plant

    International Nuclear Information System (INIS)

    Li, Weibing; Wei, Ping; Zhou, Xinping

    2014-01-01

    Highlights: • We develop an economic model different from related models. • We evaluate the initial investment cost of a plant built in northwest China. • We analyze the cost and benefit of a plant built in northwest China. • By the sensitivity analysis, we examine the sensitivity of TNPV to many parameters. - Abstract: This paper develops a model different from existing models to analyze the cost and benefit of a reinforced concrete solar chimney power plant (RCSCPP) built in northwest China. Based on the model and some assumptions for values of parameters, this work calculates total net present value (TNPV) and the minimum electricity price in each phase by dividing the whole service period into four phases. The results show that the minimum electricity price in the first phase is higher than the current market price of electricity, but the minimum prices in the other phases are far less than the current market price. The analysis indicates that huge advantages of the RCSCPP over coal-fired power plants can be embodied in phases 2–4. In addition, the sensitivity analysis performed in this paper discovers TNPV is very sensitive to changes in the solar electricity price and inflation rate, but responds only slightly to changes in carbon credits price, income tax rate and interest rate of loans. Our analysis predicts that RCSCPPs have very good application prospect. To encourage the development of RCSCPPs, the government should provide subsidy by setting higher electricity price in the first phase, then lower electricity price in the other phases

  7. The total antioxidant capacity and fluorescence imaging of selected plant leaves commonly consumed in Brunei Darussalam

    Science.gov (United States)

    Watu, Aswani; Metussin, Nurzaidah; Yasin, Hartini M.; Usman, Anwar

    2018-02-01

    We investigated the total antioxidant capacity and fluorescence imaging of several selected plants, namely Centella asiatica, Aidia borneensis and Anacardium occidentale, which are grown and traditionally consumed in Brunei Darussalam. The total antioxidant capacities of aqueous-methanolic infusions of their leaves were measured by 2,2-diphenyl-1-picrylhydrazyl (DPPH) free radical scavenging activity, and microscopic fluorescence images were measured to identify the fluorescent substances bound in the leaves. We found that the total antioxidant capacity of their infusions is estimated to be 150, 25, 15 folds, respectively, lower compared with that of the standard gallic acid. Accordingly, we demonstrated that the relative antioxidant activity of young and matured leaves agrees with the intensity of red light emission of their fresh leaves upon UV excitation. Thus, this non-invasive spectroscopic method can be potentially utilized to indicate the antioxidants in plant leaves qualitatively.

  8. Marginal costs of water savings from cooling system retrofits: a case study for Texas power plants

    Science.gov (United States)

    Loew, Aviva; Jaramillo, Paulina; Zhai, Haibo

    2016-10-01

    The water demands of power plant cooling systems may strain water supply and make power generation vulnerable to water scarcity. Cooling systems range in their rates of water use, capital investment, and annual costs. Using Texas as a case study, we examined the cost of retrofitting existing coal and natural gas combined-cycle (NGCC) power plants with alternative cooling systems, either wet recirculating towers or air-cooled condensers for dry cooling. We applied a power plant assessment tool to model existing power plants in terms of their key plant attributes and site-specific meteorological conditions and then estimated operation characteristics of retrofitted plants and retrofit costs. We determined the anticipated annual reductions in water withdrawals and the cost-per-gallon of water saved by retrofits in both deterministic and probabilistic forms. The results demonstrate that replacing once-through cooling at coal-fired power plants with wet recirculating towers has the lowest cost per reduced water withdrawals, on average. The average marginal cost of water withdrawal savings for dry-cooling retrofits at coal-fired plants is approximately 0.68 cents per gallon, while the marginal recirculating retrofit cost is 0.008 cents per gallon. For NGCC plants, the average marginal costs of water withdrawal savings for dry-cooling and recirculating towers are 1.78 and 0.037 cents per gallon, respectively.

  9. CNSS plant concept, capital cost, and multi-unit station economics

    Energy Technology Data Exchange (ETDEWEB)

    1984-07-01

    United Engineers and Constructors (UE and C) and the Babcock and Wilcox Company (B and W) have performed several studies over the last eight years related to small integral pressurized water reactors. These reactors include the 365 MWt (100 MWe) Consolidated Nuclear Steam Generator (CNSG) and the 1200 MWt Consolidated Nuclear Steam System (CNSS). The studies, mostly performed under contract to the Oak Ridge National Laboratory, have led to a 1250 MWt (400 MWe) Consolidated Nuclear Steam System (CNSS) plant concept, with unique design and cost features. This report contains an update of earlier studies of the CNSS reactor and balance-of-plant concept design, capital costs, and multi-unit plant economics incorporating recent design developments, improvements, and post-TMI-2 upgrades. The economic evaluation compares the total system economic impact of a phased, three stage 400 MWe CNSS implementation program, i.e., a three-unit station, to the installation of a single 1200 MWe Pressurized Water Reactor (PWR) into a typical USA utility system.

  10. CNSS plant concept, capital cost, and multi-unit station economics

    International Nuclear Information System (INIS)

    1984-07-01

    United Engineers and Constructors (UE and C) and the Babcock and Wilcox Company (B and W) have performed several studies over the last eight years related to small integral pressurized water reactors. These reactors include the 365 MWt (100 MWe) Consolidated Nuclear Steam Generator (CNSG) and the 1200 MWt Consolidated Nuclear Steam System (CNSS). The studies, mostly performed under contract to the Oak Ridge National Laboratory, have led to a 1250 MWt (400 MWe) Consolidated Nuclear Steam System (CNSS) plant concept, with unique design and cost features. This report contains an update of earlier studies of the CNSS reactor and balance-of-plant concept design, capital costs, and multi-unit plant economics incorporating recent design developments, improvements, and post-TMI-2 upgrades. The economic evaluation compares the total system economic impact of a phased, three stage 400 MWe CNSS implementation program, i.e., a three-unit station, to the installation of a single 1200 MWe Pressurized Water Reactor (PWR) into a typical USA utility system

  11. Procedure for estimating nonfuel operation and maintenance costs for large steam-electric power plants

    International Nuclear Information System (INIS)

    Myers, M.L.; Fuller, L.C.

    1979-01-01

    Revised guidelines are presented for estimating annual nonfuel operation and maintenance costs for large steam-electric power plants, specifically light-water-reactor plants and coal-fired plants. Previous guidelines were published in October 1975 in ERDA 76-37, a Procedure for Estimating Nonfuel Operating and Maintenance Costs for Large Steam-Electric Power Plants. Estimates for coal-fired plants include the option of limestone slurry scrubbing for flue gas desulfurization. A computer program, OMCOST, is also presented which covers all plant options

  12. The Antioxidant Capacities and Total Phenolic Contents of Some Medicinal Plants in Iran

    Directory of Open Access Journals (Sweden)

    Ali Mirzaei

    2011-12-01

    Full Text Available Background & Objectives: Free radicals are highly reactive molecules may cause great damage to cell membranes and DNA and Result in inducing oxidation DNA mutations leading to cancer, degenerative, and other diseases. Plant antioxidant derived may be preventive of free radical damages. Methods & Materials: The Stems and flower sample of plants air-dried, finely ground and were extracted by ethanol: water (70:30 for 48 h. Extracts were filtered and dried under vacuum. The antioxidant activity of five ethanolic extract of medicinal plants (Descurainia Sophia, Plantago major, Trachyspermum copticum L, Coriandrum sativum and Trigonella foenum-graecum from Iran were analysed by five different methods [1,1-diphenyl-2-picrylhydrazyl (DPPH radical, 2,2,azinobis-3-ethylbenzthiazoline-6-sulphonic acid (ABTS radical cation, Ferric-reducing antioxidant power assay (FRAP, phosphomolybdenum (PMB and reducing power (RP]. In addition, for determination of antioxidant components total phenolic content was also analyzed. Results: The total phenolic content of medicinal plant ranges from 74 to 154.3 mg Gallic acid/g extract as measured by the Folin–Ciocalteau method. Values of DPPH varied from 15.5 to 19.6 µmol trolex/g. FRAP ranged from 124.2 to 753 µmol of Fe(II/g extract. Antioxidant activity of the Plantago major was always higher compared to the other plants extracts values of total phenols content and antioxidant capacity by DPPH, ABTS, FRAP, (154.33 mg GAE/g, 1856 µmol trolox, 750 µmol trolox and 1169 µmol of Fe(II/g, extract respectively. The range of total antioxidant activity by phosphomolybdenum method was 513.3 to 870 µmol trolox/g. The reducing ability of the tested extracts was between 0.31-1.26. Plantago majorwas also highest activity in both tests. Conclusion: This study clearly demonstrated that Plantago major crude extract exhibit significant antioxidant activity.

  13. Cost reduction and safety design features of new nuclear power plants in India. Annex 13

    International Nuclear Information System (INIS)

    Sharma, V.K.

    2002-01-01

    Indian Nuclear Power Programme is designed to exploit limited reserves of uranium and extensive resource of thorium. Pressurised heavy water reactors are found most suitable and form the main stay of the first stage of the programme. Thorium utilisation is achieved in the second and third stages. Today India has total installed capacity of 2720 MWe of PHWRs which are operating with high plant load factors of over 80%. Rich experience of construction and operation of over 150 reactor years is being utilised in effecting cost reduction and safety improvements. Standardisation and reduction in gestation period by preproject activities, advance procurement and work packages of engineer, procure, construct and commission are some of the techniques being adopted for cost reduction in the new projects. But the cost of safety is rising. Design basis event of double ended guillotine rupture of primary pressure boundary needs a relook based on current knowledge of material behaviour. This event appears improbable. Similarly some of the safety related systems like closed loop cooling water operating at low temperature and pressure, and low usage factors may be designed as per standard codes without invoking special nuclear requirements. The paper will address these issues and highlight the possible areas for cost reduction both in operating and safety systems. Modern construction and project management techniques are being employed. Gestation period of 5 years and cost of less than US $1400 per KWe are the present targets. In Indian environment nuclear power is found to be competitive with thermal power plants at distances of about 800 Kms from the coal mines. (author)

  14. Cost estimation and economical evaluation of three configurations of activated sludge process for a wastewater treatment plant (WWTP) using simulation

    Science.gov (United States)

    Jafarinejad, Shahryar

    2017-09-01

    The activated sludge (AS) process is a type of suspended growth biological wastewater treatment that is used for treating both municipal sewage and a variety of industrial wastewaters. Economical modeling and cost estimation of activated sludge processes are crucial for designing, construction, and forecasting future economical requirements of wastewater treatment plants (WWTPs). In this study, three configurations containing conventional activated sludge (CAS), extended aeration activated sludge (EAAS), and sequencing batch reactor (SBR) processes for a wastewater treatment plant in Tehran city were proposed and the total project construction, operation labor, maintenance, material, chemical, energy and amortization costs of these WWTPs were calculated and compared. Besides, effect of mixed liquor suspended solid (MLSS) amounts on costs of WWTPs was investigated. Results demonstrated that increase of MLSS decreases the total project construction, material and amortization costs of WWTPs containing EAAS and CAS. In addition, increase of this value increases the total operation, maintenance and energy costs, but does not affect chemical cost of WWTPs containing EAAS and CAS.

  15. Total Data Management System for the La Hague spent fuel reprocessing plants

    International Nuclear Information System (INIS)

    Chabert, J.; Coignaud, G.; Perot, J.P.; Fournier, W.; Silvain, B.

    1991-01-01

    Operation of the UP2 and UP3 reprocessing plants at La Hague, France, generates considerable data processing requirements. To meet these requirements, a Total Data Management System (TDMS) has been designed and installed to operate the biggest Ethernet industrial network in Europe. This network, called Haguenet, interconnects a large number of computers and user terminals. The TDMS' main operational functions are plant operation and production data management, maintenance data management, technical documents management and computer-aided design (CAD). Extensive experience was gained through the design and operation of the TDMS at La Hague. (author)

  16. The Cost-Effectiveness of Dual Mobility Implants for Primary Total Hip Arthroplasty: A Computer-Based Cost-Utility Model.

    Science.gov (United States)

    Barlow, Brian T; McLawhorn, Alexander S; Westrich, Geoffrey H

    2017-05-03

    Dislocation remains a clinically important problem following primary total hip arthroplasty, and it is a common reason for revision total hip arthroplasty. Dual mobility (DM) implants decrease the risk of dislocation but can be more expensive than conventional implants and have idiosyncratic failure mechanisms. The purpose of this study was to investigate the cost-effectiveness of DM implants compared with conventional bearings for primary total hip arthroplasty. Markov model analysis was conducted from the societal perspective with use of direct and indirect costs. Costs, expressed in 2013 U.S. dollars, were derived from the literature, the National Inpatient Sample, and the Centers for Medicare & Medicaid Services. Effectiveness was expressed in quality-adjusted life years (QALYs). The model was populated with health state utilities and state transition probabilities derived from previously published literature. The analysis was performed for a patient's lifetime, and costs and effectiveness were discounted at 3% annually. The principal outcome was the incremental cost-effectiveness ratio (ICER), with a willingness-to-pay threshold of $100,000/QALY. Sensitivity analyses were performed to explore relevant uncertainty. In the base case, DM total hip arthroplasty showed absolute dominance over conventional total hip arthroplasty, with lower accrued costs ($39,008 versus $40,031 U.S. dollars) and higher accrued utility (13.18 versus 13.13 QALYs) indicating cost-savings. DM total hip arthroplasty ceased being cost-saving when its implant costs exceeded those of conventional total hip arthroplasty by $1,023, and the cost-effectiveness threshold for DM implants was $5,287 greater than that for conventional implants. DM was not cost-effective when the annualized incremental probability of revision from any unforeseen failure mechanism or mechanisms exceeded 0.29%. The probability of intraprosthetic dislocation exerted the most influence on model results. This model

  17. Economic Evaluation of Decommissioning Cost of Nuclear Power Plant in the National Electricity Plan in Korea

    International Nuclear Information System (INIS)

    Lee, Man Ki; Nam, Ji Hee

    2008-01-01

    Decommissioning cost of a nuclear power plant includes the costs related with dismantling a nuclear power plant, disposal of a spent fuel and of a low/medium radioactive waste. The decommissioning cost is different from the other expenditures in that it is occurred after the reactor finishes its commercial operation. In this respect, the electricity act was enforced to secure provisions for decommissioning a nuclear power plant during its commercial operation. The purpose of this study is to provide economic evaluation and economic cost for a decommissioning when the cost of a decommissioning is provided as one of input to the national electricity plan. Therefore, this study does not deal with whether the estimated amount of a decommissioning cost is just or not. This study focuses how to transfer the estimated decommissioning cost given in the electricity act to the economic cost, which can be used in the national electricity plan

  18. Cost regulation on the inspection of plants requiring supervision

    International Nuclear Information System (INIS)

    Anon.

    1981-01-01

    According to annexes I to VI of this regulation, TUeVs (technical control authorities) (2nd sentence of para. 1 of sect. 24 c of the trade law) collect fees for inspections ordered by the authorities for the following plants and installations: 1. steam boiler plants, 2. pressure vessels, high-pressure gas vessels, feeders, 3. lifts, 4. acetylene plants, 5. plants for the storage, racking and transport of combustile liquids, 6. electrical installations on hazardous location. (orig.) [de

  19. The marginal cost of carbon abatement from planting street trees in New York City

    Science.gov (United States)

    Kent F. Kovacs; Robert G. Haight; Suhyun Jung; Dexter H. Locke; Jarlath. O' Neil-Dunne

    2013-01-01

    Urban trees can store carbon through the growth process and reduce fossil fuel use by lowering cooling and heating energy consumption of buildings through the process of transpiration, shading, and the blocking of wind. However, the planting and maintenance of urban trees come at a cost. We estimate the discounted cost of net carbon reductions associated with planting...

  20. Force Structure: Restructuring and Rebuilding the Army Will Cost Billions of Dollars for Equipment but the Total Cost Is Uncertain

    National Research Council Canada - National Science Library

    St. Laurent, Janet A

    2008-01-01

    .... Several factors are contributing to the uncertainties about future costs. First, the Army's $43.6 funding plan for equipping modular units was based on preliminary modular unit designs and did not fully consider the needs of National Guard units...

  1. O and M costs: how they affect plant economics

    International Nuclear Information System (INIS)

    Meyers, B.L.; Braun, C.

    1994-01-01

    Addressing work practices and cost-effectiveness at high-cost or average US nuclear units will improve the economics of the entire industry. Improvements can be made through benchmarking, better planning, close accounting and empowerment of employees. (Author)

  2. Analysing uncertainty around costs of innovative medical technologies: the case of fibrin sealant (QUIXIL) for total knee replacement.

    NARCIS (Netherlands)

    Steuten, Lotte Maria Gertruda; Vallejo-Torres, Laura; Bastide, Philippe; Buxton, Martin J.

    2009-01-01

    This paper presents a relatively simple cost model comparing the costs of using a commercial fibrin sealant (QUIXIL®) in addition to conventional haemostatic treatment vs. conventional treatment alone in total knee replacement (TKR) surgery, and demonstrates and discusses how one- and two-way

  3. Fuel prices, emission standards, and generation costs for coal vs natural gas power plants.

    Science.gov (United States)

    Pratson, Lincoln F; Haerer, Drew; Patiño-Echeverri, Dalia

    2013-05-07

    Low natural gas prices and stricter, federal emission regulations are promoting a shift away from coal power plants and toward natural gas plants as the lowest-cost means of generating electricity in the United States. By estimating the cost of electricity generation (COE) for 304 coal and 358 natural gas plants, we show that the economic viability of 9% of current coal capacity is challenged by low natural gas prices, while another 56% would be challenged by the stricter emission regulations. Under the current regulations, coal plants would again become the dominant least-cost generation option should the ratio of average natural gas to coal prices (NG2CP) rise to 1.8 (it was 1.42 in February 2012). If the more stringent emission standards are enforced, however, natural gas plants would remain cost competitive with a majority of coal plants for NG2CPs up to 4.3.

  4. Two views of the comparative escalation of nuclear and coal-fired power plant costs

    International Nuclear Information System (INIS)

    Anon.

    1982-01-01

    Doan L. Phung critiques Charles Komanoff's 1981 book Power Plant Cost Escalation, which compares new nuclear plant costs unfavorably with those of new coal plants because of the increase in capital costs. Phung blames prophets of doom who ignore the escalating costs throughout the economy and now focus their anti-nuclear attacks in economic terms. Proposals by Alvin Weinberg and others to concentrate on reactor-safety improvements are used to conclude that these efforts will further expand the capital costs of nuclear plants and make them noncompetitive. Phung questions whether Komanoff's modeling considers enough of the political, regulatory, and technological factors to determine future costs. Komanoff replies by explaining his method of analysis and denying a bias against nuclear power. A postscript by Phung reiterates his criticism of simplistic calculations and extrapolations. 17 references

  5. Total mercury, methyl mercury, and carbon in fresh and burned plants and soil in Northwestern Ontario

    International Nuclear Information System (INIS)

    Mailman, M.; Bodaly, R.A.

    2005-01-01

    Terrestrial plants and soil contain substantial amounts of organic carbon (C) and mercury. Flooding terrestrial areas stimulates microbial methyl mercury (MeHg) production and fish obtain elevated MeHg concentrations. Our purpose was to determine the loss of C, total mercury (THg), and MeHg from boreal plants and soil after burning to assess the potential of burning before flooding to lower MeHg. Fresh plants contained 4 to 52 ng g -1 dry weight (dw) of THg and 0.1 to 1.3 ng g -1 dw of MeHg. Upland soils contained 162±132 ng g -1 dw of THg and 0.6±0.6 ng g -1 dw of MeHg. Complete burning caused plants to lose 96, 98, 97, and 94% of the mass, C, THg, and MeHg, respectively. Upland soil lost 27, 95, 79, and 82% of the mass, C, THg, and MeHg, respectively. Our results demonstrated that a substantial loss of C, THg, and MeHg was caused by burning. - Burning terrestrial vegetation and soil causes substantial losses of organic carbon, total mercury, and methyl mercury

  6. Total mercury, methyl mercury, and carbon in fresh and burned plants and soil in Northwestern Ontario

    Energy Technology Data Exchange (ETDEWEB)

    Mailman, M. [Department of Zoology, University of Manitoba, Winnipeg, Man. R3T 2N2 (Canada); Freshwater Institute, 501 University Crescent, Winnipeg, Man. R3T 2N6 (Canada)]. E-mail: mailmanma@dfo-mpo.gc.ca; Bodaly, R.A. [Department of Zoology, University of Manitoba, Winnipeg, Man. R3T 2N2 (Canada); Freshwater Institute, 501 University Crescent, Winnipeg, Man. R3T 2N6 (Canada)

    2005-11-15

    Terrestrial plants and soil contain substantial amounts of organic carbon (C) and mercury. Flooding terrestrial areas stimulates microbial methyl mercury (MeHg) production and fish obtain elevated MeHg concentrations. Our purpose was to determine the loss of C, total mercury (THg), and MeHg from boreal plants and soil after burning to assess the potential of burning before flooding to lower MeHg. Fresh plants contained 4 to 52 ng g{sup -1} dry weight (dw) of THg and 0.1 to 1.3 ng g{sup -1} dw of MeHg. Upland soils contained 162{+-}132 ng g{sup -1} dw of THg and 0.6{+-}0.6 ng g{sup -1} dw of MeHg. Complete burning caused plants to lose 96, 98, 97, and 94% of the mass, C, THg, and MeHg, respectively. Upland soil lost 27, 95, 79, and 82% of the mass, C, THg, and MeHg, respectively. Our results demonstrated that a substantial loss of C, THg, and MeHg was caused by burning. - Burning terrestrial vegetation and soil causes substantial losses of organic carbon, total mercury, and methyl mercury.

  7. Screening of immunomodulatory activity of total and protein extracts of some Moroccan medicinal plants.

    Science.gov (United States)

    Daoudi, Abdeljlil; Aarab, Lotfi; Abdel-Sattar, Essam

    2013-04-01

    Herbal and traditional medicines are being widely used in practice in many countries for their benefits of treating different ailments. A large number of plants in Morocco were used in folk medicine to treat immune-related disorders. The objective of this study is to evaluate the immunomodulatory activity of protein extracts (PEs) of 14 Moroccan medicinal plants. This activity was tested on the proliferation of immune cells. The prepared total and PEs of the plant samples were tested using MTT (3-(4,5-dimethylthiazol-2yl)-2,5-diphenyltetrazolium bromide) assay on the splenocytes with or without stimulation by concanavalin-A (Con-A), a mitogenic agent used as positive control. The results of this study indicated different activity spectra. Three groups of activities were observed. The first group represented by Citrullus colocynthis, Urtica dioica, Elettaria cardamomum, Capparis spinosa and Piper cubeba showed a significant immunosuppressive activity. The second group that showed a significant immunostimulatory activity was represented by Aristolochia longa, Datura stramonium, Marrubium vulgare, Sinapis nigra, Delphynium staphysagria, Lepidium sativum, Ammi visnaga and Tetraclinis articulata. The rest of the plant extracts did not alter the proliferation induced by Con-A. This result was more important for the PE than for the total extract. In conclusion, this study revealed an interesting immunomodulating action of certain PEs, which could explain their traditional use. The results of this study may also have implications in therapeutic treatment of infections, such as prophylactic and adjuvant with cancer chemotherapy.

  8. Plant residues--a low cost, effective bioremediation treatment for petrogenic hydrocarbon-contaminated soil.

    Science.gov (United States)

    Shahsavari, Esmaeil; Adetutu, Eric M; Anderson, Peter A; Ball, Andrew S

    2013-01-15

    Petrogenic hydrocarbons represent the most commonly reported environmental contaminant in industrialised countries. In terms of remediating petrogenic contaminated hydrocarbons, finding sustainable non-invasive technologies represents an important goal. In this study, the effect of 4 types of plant residues on the bioremediation of aliphatic hydrocarbons was investigated in a 90 day greenhouse experiment. The results showed that contaminated soil amended with different plant residues led to statistically significant increases in the utilisation rate of Total Petroleum Hydrocarbon (TPH) relative to control values. The maximum TPH reduction (up to 83% or 6800 mg kg(-1)) occurred in soil mixed with pea straw, compared to a TPH reduction of 57% (4633 mg kg(-1)) in control soil. A positive correlation (0.75) between TPH reduction rate and the population of hydrocarbon-utilising microorganisms was observed; a weaker correlation (0.68) was seen between TPH degradation and bacterial population, confirming that adding plant materials significantly enhanced both hydrocarbonoclastic and general microbial soil activities. Microbial community analysis using Denaturing Gradient Gel Electrophoresis (DGGE) showed that amending the contaminated soil with plant residues (e.g., pea straw) caused changes in the soil microbial structure, as observed using the Shannon diversity index; the diversity index increased in amended treatments, suggesting that microorganisms present on the dead biomass may become important members of the microbial community. In terms of specific hydrocarbonoclastic activity, the number of alkB gene copies in the soil microbial community increased about 300-fold when plant residues were added to contaminated soil. This study has shown that plant residues stimulate TPH degradation in contaminated soil through stimulation and perhaps addition to the pool of hydrocarbon-utilising microorganisms, resulting in a changed microbial structure and increased alkB gene

  9. Variation in the cost of care for primary total knee arthroplasties

    Directory of Open Access Journals (Sweden)

    Derek A. Haas, MBA

    2017-03-01

    Conclusions: The large variation in costs among sites suggests major and multiple opportunities to transfer knowledge about process and productivity improvements that lower costs while simultaneously maintaining or improving outcomes.

  10. Exergy-based method for analyzing the composition of the electricity cost generated in gas-fired combined cycle plants

    Energy Technology Data Exchange (ETDEWEB)

    Sarraf Borelli, Samuel Jose [Promon Engenharia Ltda., Av. Presidente Juscelino Kubitschek, 1830, Itaim, CEP:04543-900 Sao Paulo/SP (Brazil)], E-mail: sborelli@terra.com.br; Oliveira Junior, Silvio de [Environmental and Thermal Engineering Laboratory, Polytechnic School, University of Sao Paulo, Av. Prof. Luciano Gualberto, 1289, Cidade Universitaria, CEP:05508-900 Sao Paulo/SP (Brazil)], E-mail: silvio.oliveira@poli.usp.br

    2008-02-15

    The proposed method to analyze the composition of the cost of electricity is based on the energy conversion processes and the destruction of the exergy through the several thermodynamic processes that comprise a combined cycle power plant. The method uses thermoeconomics to evaluate and allocate the cost of exergy throughout the processes, considering costs related to inputs and investment in equipment. Although the concept may be applied to any combined cycle or cogeneration plant, this work develops only the mathematical modeling for three-pressure heat recovery steam generator (HRSG) configurations and total condensation of the produced steam. It is possible to study any nx1 plant configuration (n sets of gas turbine and HRSGs associated to one steam turbine generator and condenser) with the developed model, assuming that every train operates identically and in steady state. The presented model was conceived from a complex configuration of a real power plant, over which variations may be applied in order to adapt it to a defined configuration under study [Borelli SJS. Method for the analysis of the composition of electricity costs in combined cycle thermoelectric power plants. Master in Energy Dissertation, Interdisciplinary Program of Energy, Institute of Eletro-technical and Energy, University of Sao Paulo, Sao Paulo, Brazil, 2005 (in Portuguese)]. The variations and adaptations include, for instance, use of reheat, supplementary firing and partial load operation. It is also possible to undertake sensitivity analysis on geometrical equipment parameters.

  11. Exergy-based method for analyzing the composition of the electricity cost generated in gas-fired combined cycle plants

    Energy Technology Data Exchange (ETDEWEB)

    Borelli, Samuel Jose Sarraf [Promon Engenharia Ltda., Av. Presidente Juscelino Kubitschek, 1830, Itaim, CEP:04543-900 Sao Paulo/SP (Brazil); De Oliveira Junior, Silvio [Environmental and Thermal Engineering Laboratory, Polytechnic School, University of Sao Paulo, Av. Prof. Luciano Gualberto, 1289, Cidade Universitaria, CEP:05508-900 Sao Paulo/SP (Brazil)

    2008-02-15

    The proposed method to analyze the composition of the cost of electricity is based on the energy conversion processes and the destruction of the exergy through the several thermodynamic processes that comprise a combined cycle power plant. The method uses thermoeconomics to evaluate and allocate the cost of exergy throughout the processes, considering costs related to inputs and investment in equipment. Although the concept may be applied to any combined cycle or cogeneration plant, this work develops only the mathematical modeling for three-pressure heat recovery steam generator (HRSG) configurations and total condensation of the produced steam. It is possible to study any n x 1 plant configuration (n sets of gas turbine and HRSGs associated to one steam turbine generator and condenser) with the developed model, assuming that every train operates identically and in steady state. The presented model was conceived from a complex configuration of a real power plant, over which variations may be applied in order to adapt it to a defined configuration under study [Borelli SJS. Method for the analysis of the composition of electricity costs in combined cycle thermoelectric power plants. Master in Energy Dissertation, Interdisciplinary Program of Energy, Institute of Eletro-technical and Energy, University of Sao Paulo, Sao Paulo, Brazil, 2005 (in Portuguese)]. The variations and adaptations include, for instance, use of reheat, supplementary firing and partial load operation. It is also possible to undertake sensitivity analysis on geometrical equipment parameters. (author)

  12. Exergy-based method for analyzing the composition of the electricity cost generated in gas-fired combined cycle plants

    International Nuclear Information System (INIS)

    Sarraf Borelli, Samuel Jose; Oliveira Junior, Silvio de

    2008-01-01

    The proposed method to analyze the composition of the cost of electricity is based on the energy conversion processes and the destruction of the exergy through the several thermodynamic processes that comprise a combined cycle power plant. The method uses thermoeconomics to evaluate and allocate the cost of exergy throughout the processes, considering costs related to inputs and investment in equipment. Although the concept may be applied to any combined cycle or cogeneration plant, this work develops only the mathematical modeling for three-pressure heat recovery steam generator (HRSG) configurations and total condensation of the produced steam. It is possible to study any nx1 plant configuration (n sets of gas turbine and HRSGs associated to one steam turbine generator and condenser) with the developed model, assuming that every train operates identically and in steady state. The presented model was conceived from a complex configuration of a real power plant, over which variations may be applied in order to adapt it to a defined configuration under study [Borelli SJS. Method for the analysis of the composition of electricity costs in combined cycle thermoelectric power plants. Master in Energy Dissertation, Interdisciplinary Program of Energy, Institute of Eletro-technical and Energy, University of Sao Paulo, Sao Paulo, Brazil, 2005 (in Portuguese)]. The variations and adaptations include, for instance, use of reheat, supplementary firing and partial load operation. It is also possible to undertake sensitivity analysis on geometrical equipment parameters

  13. Estimation of the cost of electro-mechanical equipment for small hydropower plants – review and comparison of methods

    Directory of Open Access Journals (Sweden)

    Lipiński Seweryn

    2017-01-01

    Full Text Available The estimate of the cost of electro-mechanical equipment for new small hydropower plants most often amounts to about 30-40% of the total budget. In case of modernization of existing installations, this estimation represents the main cost. This matter constitutes a research problem for at least few decades. Many models have been developed for that purpose. The aim of our work was to collect and analyse formulas that allow estimation of the cost of investment in electro-mechanical equipment for small hydropower plants. Over a dozen functions were analysed. To achieve the aim of our work, these functions were converted into the form allowing their comparison. Then the costs were simulated with respect to plants’ powers and net heads; such approach is novel and allows deeper discussion of the problem, as well as drawing broader conclusions. The following conclusions can be drawn: significant differences in results obtained by using various formulas were observed; there is a need for a wide study based on national investments in small hydropower plants that would allow to develop equations based on local data; the obtained formulas would let to determinate the costs of modernization or a new construction of small hydropower plant more precisely; special attention should be payed to formulas considering turbine type.

  14. Listing the investment costs and producing material analyses for given plants for energy supply

    International Nuclear Information System (INIS)

    Wagner, H.J.; Hansen, K.; Schoen, R.; Wassmann, B.

    1989-01-01

    In this comparison, the investment and material cost for the following plants are examined: 1. Solar service water treatment plants, 2. Solar heating plants, 3. Conventional comparative plants, 4. Heat pump heating plants, 5. Nuclear power stations and hardcoal-fired power stations, and 6. Wind energy converters. The technique of energy conversion of each is generally explained. In the appendix, points of the use of energy are given for the manufacture of components of the heating and installation trade. Specific energy costs per product unit are compiled for the different branches. (UA) [de

  15. Methodology for cost estimate in projects for nuclear power plants decommissioning

    International Nuclear Information System (INIS)

    Salij, L.M.

    2008-01-01

    The conceptual approaches to cost estimating of nuclear power plants units decommissioning projects were determined. The international experience and national legislative and regulatory basis were analyzed. The possible decommissioning project cost classification was given. It was shown the role of project costs of nuclear power plant units decommissioning as the most important criterion for the main project decisions. The technical and economic estimation of deductions to common-branch fund of decommissioning projects financing was substantiated

  16. Nonfuel OandM costs for laser and heavy-ion fusion power plants

    International Nuclear Information System (INIS)

    Pendergrass, J.H.

    1986-01-01

    Very simple nonfuel operating and maintenance (OandM) cost models have been used in many inertial confinement fusion (ICF) commercial applications studies. Often, ICF OandM costs have been accounted for by adding a small fraction of plant initial capital cost to other annual power production costs. Lack of definition of ICF technology and/or perceptions that OandM costs would be small relative to capital-related costs are some reasons for such simple treatments. This approach does not permit rational treatment of potentially significant differences in OandM costs for ICF plants with different driver, reactor, target, etc., technologies or rational comparisons with conventional technologies. Improved understanding of ICF makes more accurate estimates for some OandM costs appear feasible. More detailed OandM cost models, even if of modest accuracy in some areas, are useful for comparisons

  17. The direct and ecological costs of an ant-plant symbiosis.

    Science.gov (United States)

    Frederickson, Megan E; Ravenscraft, Alison; Miller, Gabriel A; Arcila Hernández, Lina M; Booth, Gregory; Pierce, Naomi E

    2012-06-01

    How strong is selection for cheating in mutualisms? The answer depends on the type and magnitude of the costs of the mutualism. Here we investigated the direct and ecological costs of plant defense by ants in the association between Cordia nodosa, a myrmecophytic plant, and Allomerus octoarticulatus, a phytoecious ant. Cordia nodosa trees produce food and housing to reward ants that protect them against herbivores. For nearly 1 year, we manipulated the presence of A. octoarticulatus ants and most insect herbivores on C. nodosa in a full-factorial experiment. Ants increased plant growth when herbivores were present but decreased plant growth when herbivores were absent, indicating that hosting ants can be costly to plants. However, we did not detect a cost to ant colonies of defending host plants against herbivores. Although this asymmetry in costs suggests that the plants may be under stronger selection than the ants to cheat by withholding investment in their partner, the costs to C. nodosa are probably at least partly ecological, arising because ants tend scale insects on their host plants. We argue that ecological costs should favor resistance or traits other than cheating and thus that neither partner may face much temptation to cheat.

  18. CONCEPT-5, Cost and Economics Analysis for Nuclear Fuel or Fossil Fuel Power Plant

    International Nuclear Information System (INIS)

    Bowers, H.I.; Gratteau, J.E.; Zielsinki, T.J.

    1992-01-01

    1 - Description of problem or function: The CONCEPT computer code system was developed to provide conceptual capital cost estimates for nuclear and coal-fired power plants. Cost estimates can be made as a function of plant type, size, location, and date of initial operation. The output includes a detailed breakdown of the estimate into direct and indirect costs similar to the accounting system described in document NUS-531. Cost models are provided in CONCEPT5, the fifth generation in the development of the CONCEPT package, for single-unit coal-fired plants, pressurized-water reactors, boiling- water reactors, liquid-metal-cooled reactors, and multi-unit coal- fired plants based on today's average or best operating experience. Costs may be obtained for any of twenty U.S. cities, a hypothetical Middletown site, and two Canadian cities. CONCEPT5 models are updated models of those available in CONCEPT3 and, in addition, this edition contains historical factory equipment cost data for the generation of cost indices and escalation rates; indirect costs are calculated as a function of unit size rather than a function of direct costs; and an indirect cost account for owner's costs and an improved time-dependent escalation feature are included. The CONCEPT3 models and cost data are outdated; the package is being retained in the library since it is the only UNIVAC1108 machine version of CONCEPT available and could prove helpful in converting the latest IBM release. 2 - Method of solution: CONCEPT is based on the premise that any central station power plant involves approximately the same major cost components regardless of location or date of initial operation. The program has detailed cost models for each plant type at a reference condition. Through use of size, time, and location- dependent cost adjustments, a reference cost model is modified to produce a specific capital cost estimate. CONCEPT is supported by two auxiliary programs--CONTAC, which generates and maintains

  19. Trends in nuclear power plant capital-investment cost estimates - 1976 to 1982

    International Nuclear Information System (INIS)

    Bowers, H.I.; Fuller, L.C.; Myers, M.L.

    1983-09-01

    This report describes trends in power plant capital investment cost estimates over the time period from 1976 to 1982. A review of economic parameters, inflation and escalation rates and cost of money, and a review of cost-size scaling relationships are included. Reference cost estimates are provided for light-water reactor and coal-fired electric power plants based on safety and environmental regulations in effect in January 1982. The sensitivity of the reference cost estimates to numerous economic parameters is analyzed

  20. Efforts to Support Consumer Enrollment Decisions Using Total Cost Estimators: Lessons from the Affordable Care Act’s Marketplaces.

    Science.gov (United States)

    Giovannelli, Justin; Curran, Emily

    2017-02-01

    Issue: Policymakers have sought to improve the shopping experience on the Affordable Care Act’s marketplaces by offering decision support tools that help consumers better understand and compare their health plan options. Cost estimators are one such tool. They are designed to provide consumers a personalized estimate of the total cost--premium, minus subsidy, plus cost-sharing--of their coverage options. Cost estimators were available in most states by the start of the fourth open enrollment period. Goal: To understand the experiences of marketplaces that offer a total cost estimator and the interests and concerns of policymakers from states that are not using them. Methods: Structured interviews with marketplace officials, consumer enrollment assisters, technology vendors, and subject matter experts; analysis of the total cost estimators available on the marketplaces as of October 2016. Key findings and conclusions: Informants strongly supported marketplace adoption of a total cost estimator. Marketplaces that offer an estimator faced a range of design choices and varied significantly in their approaches to resolving them. Interviews suggested a clear need for additional consumer testing and data analysis of tool usage and for sustained outreach to enrollment assisters to encourage greater use of the estimators.

  1. The Importance of State and Plant Characteristics in Determining the Environmental Compliance Costs of Chemical Manufacturing Plants: Evidence from the PACE Survey, 1979-1990 Summary (1994)

    Science.gov (United States)

    Summary of the author's dissertation: links the U.S. Census Bureau's Pollution Abatement Costs and Expenditures data on a plant-by-plant basis with the data in their Longitudinal Research Database (LRD) to examine chemical industry compliance costs.

  2. Infrastructure expenditures and costs. Practical guidelines to calculate total infrastructure costs for five modes of transport. Final report

    International Nuclear Information System (INIS)

    2005-11-01

    Transport infrastructures in general, and the Trans European Transport Network (TEN-T) in particular, play an important role in achieving the medium and long-term objectives of the European Union. In view of this, the Commission has recently adopted a revision of the guidelines for the TEN-T. The main consequences of this revision are the need for a better understanding of the investments made by the member states in the TEN-T and the need for ensuring optimal consistency in the reporting by the Members States of such investments. With Regulation number 1108/70 the Council of the European Communities introduced an accounting system for expenditure on infrastructure in respect of transport by rail, road and inland waterways. The purpose of this regulation is to introduce a standard and permanent accounting system for infrastructure expenditures. However maritime and aviation infrastructure were not included. Further, the need for an effective and easy to apply classification for infrastructure investments concerning all five transport modes was still pending. Therefore, DG TREN has commissioned ECORYS Transport and CE Delft to study the expenditures and costs of infrastructure, to propose an adequate classification of expenditures, and to propose a method for translating data on expenditures into data on costs. The objectives of the present study are threefold: To set out a classification of infrastructure expenditures, in order to increase knowledge of expenditures related to transport infrastructures. This classification should support a better understanding of fixed and variable infrastructure costs; To detail the various components of such expenditures for five modes of transportation, which would enable the monitoring of infrastructure expenditures and costs; and to set up a methodology to move from annual series of expenditures to costs, including fixed and variable elements.

  3. Herbivore-mediated ecological costs of reproduction shape the life history of an iteroparous plant.

    Science.gov (United States)

    Miller, Tom E X; Tenhumberg, Brigitte; Louda, Svata M

    2008-02-01

    Plant reproduction yields immediate fitness benefits but can be costly in terms of survival, growth, and future fecundity. Life-history theory posits that reproductive strategies are shaped by trade-offs between current and future fitness that result from these direct costs of reproduction. Plant reproduction may also incur indirect ecological costs if it increases susceptibility to herbivores. Yet ecological costs of reproduction have received little empirical attention and remain poorly integrated into life-history theory. Here, we provide evidence for herbivore-mediated ecological costs of reproduction, and we develop theory to examine how these costs influence plant life-history strategies. Field experiments with an iteroparous cactus (Opuntia imbricata) indicated that greater reproductive effort (proportion of meristems allocated to reproduction) led to greater attack by a cactus-feeding insect (Narnia pallidicornis) and that damage by this herbivore reduced reproductive success. A dynamic programming model predicted strongly divergent optimal reproductive strategies when ecological costs were included, compared with when these costs were ignored. Meristem allocation by cacti in the field matched the optimal strategy expected under ecological costs of reproduction. The results indicate that plant reproductive allocation can strongly influence the intensity of interactions with herbivores and that associated ecological costs can play an important selective role in the evolution of plant life histories.

  4. POWERCO, Nuclear Power Plant Electricity Cost and Economics

    International Nuclear Information System (INIS)

    Tyson, Frank D.

    1982-01-01

    1 - Description of problem or function: POWERCO calculates the cost of electricity produced by nuclear power stations, assuming all cash expenses such as investment and fuel costs, operating expenses, and taxes are known. The power cost is held constant throughout the project life. 2 - Method of solution: The cost calculation is based on the requirement that income received must provide for recovery of investment, return on investment, and all operating expenses. Equations are developed to calculate true fixed charge rates and true average fuel working capital

  5. Cost and performance of fossil fuel power plants with CO2 capture and storage

    International Nuclear Information System (INIS)

    Rubin, Edward S.; Chen, Chao; Rao, Anand B.

    2007-01-01

    CO 2 capture and storage (CCS) is receiving considerable attention as a potential greenhouse gas (GHG) mitigation option for fossil fuel power plants. Cost and performance estimates for CCS are critical factors in energy and policy analysis. CCS cost studies necessarily employ a host of technical and economic assumptions that can dramatically affect results. Thus, particular studies often are of limited value to analysts, researchers, and industry personnel seeking results for alternative cases. In this paper, we use a generalized modeling tool to estimate and compare the emissions, efficiency, resource requirements and current costs of fossil fuel power plants with CCS on a systematic basis. This plant-level analysis explores a broader range of key assumptions than found in recent studies we reviewed for three major plant types: pulverized coal (PC) plants, natural gas combined cycle (NGCC) plants, and integrated gasification combined cycle (IGCC) systems using coal. In particular, we examine the effects of recent increases in capital costs and natural gas prices, as well as effects of differential plant utilization rates, IGCC financing and operating assumptions, variations in plant size, and differences in fuel quality, including bituminous, sub-bituminous and lignite coals. Our results show higher power plant and CCS costs than prior studies as a consequence of recent escalations in capital and operating costs. The broader range of cases also reveals differences not previously reported in the relative costs of PC, NGCC and IGCC plants with and without CCS. While CCS can significantly reduce power plant emissions of CO 2 (typically by 85-90%), the impacts of CCS energy requirements on plant-level resource requirements and multi-media environmental emissions also are found to be significant, with increases of approximately 15-30% for current CCS systems. To characterize such impacts, an alternative definition of the 'energy penalty' is proposed in lieu of the

  6. Cost-effectiveness of power plants in Eastern Europe. An approach for estimating the cost-effectiveness of existing, retrofitted and new power plants

    International Nuclear Information System (INIS)

    Van Harmelen, T.

    1994-08-01

    In many Western European countries, power plants are replaced or retrofitted after 25 or 30 years; just continuing the operation of an old plant hardly occurs, in most cases because it is considered to be uneconomic. This implies that in many cases operating an old plant in the Western situation is more expensive than building a new one. In some cases, retrofitting the old plant is the least-cost option. In Eastern Europe very old (power) plants are kept in operation 'as long as possible'. Thirty to forty years is no exception. In the discussion on explanations of the different Eastern European practice, two arguments are often heard. The first argument concerns limited availability of financial resources in Eastern Europe as an explanation for the current lifetime extension of old, existing power plants. This argument is popular among Western European experts being their view or judgement of the situation. The second argument, advocated mostly by Eastern European experts, is that it is cheaper or more cost-effective to continue operating old, existing power plants instead of building new ones. This paper will shed some light on the validity of both arguments. First, a summary of national cost-effectiveness analysis such as applied by EFOM-ENV/GAMS will be given. Second, potential arguments pro and contra operating old plants will be summarized and discussed in terms of national cost-benefit analysis. Third, a set of modelling assumptions for appliance in EFOM-ENV/GAMS for the programme 'CO 2 reduction strategies for Eastern Europe' will be presented and discussed. Finally, some case results will be shown and preliminary conclusions will be drawn on the topic of lifetime extension of existing power plants. 2 figs., 2 tabs., 2 refs

  7. Risk and Cost of 90-Day Complications in Morbidly and Superobese Patients After Total Knee Arthroplasty.

    Science.gov (United States)

    Meller, Menachem M; Toossi, Nader; Johanson, Norman A; Gonzalez, Mark H; Son, Min-Sun; Lau, Edmund C

    2016-10-01

    This study investigated the risk and cost of postoperative complications associated with morbid and super obesity after total knee arthroplasty (TKA). A retrospective cohort study was conducted of patients who underwent TKA using Medicare hospital claims data. The International Classification of Diseases, Ninth Revision, Clinical Modification diagnosis code V85.4x was used to identify morbidly obese patients (body mass index [BMI] ≥40 kg/m(2)) and superobese patients (BMI ≥50 kg/m(2)) in 2011-2013. Patients without any BMI-related diagnosis codes were used as controls. Twelve complications occurred in the 90-day period after TKA were analyzed using multivariate Cox models, adjusting for patient demographic, morbidity, and institutional factors. In addition, hospital charges and payments were compared from primary surgery through subsequent 90 days. Morbidly obese patients showed a significantly elevated risk in most complications examined, with a 2-fold or higher risk in dislocation and wound dehiscence. In addition, death, periprosthetic joint infection, acute renal failure, and knee revision had significant hazard ratios between 1.5 and 2.0. However, risk of deep vein thrombosis and acute myocardial infarction did not increase for the morbidly obese patients. Superobese patients had significant increase in risk of infection, wound dehiscence, acute renal failures, revisions, death, and readmission compared with patients with BMI 40-49 kg/m(2). Significant dose-response trend was found between the level of BMI and risk for death, dislocation, implant failure, infection, readmission, revision, wound dehiscence, and acute renal failure. Controlling for patient and institutional factors, each TKA had an average total hospital charges of $75,884 among superobese patients, compared to $65,118 for the control group, a difference of $10,767. Medicare payment for the superobese patients was also higher, but only by $2703. Morbidly obese patients pose a significantly

  8. Assessing the Total cost of ownership of ERP systems : Case study analysis on the factors behind customer costs in recent minor implementations

    OpenAIRE

    Rydgård, Göran; Palmberg, Nils

    2010-01-01

    This master’s thesis presents a model for calculating the total cost of ownership (TCO) of relatively small ERP implementations, including two years of running the system. The main factors affecting the cost items in the model are also analyzed, based in part on four case projects that the consultancy company Acando has carried out recently and in part on literature. The case projects were investigated through interviews with key actors in the projects from Acando and the customer, and throug...

  9. Development of an integrated cost model for nuclear plant decommissioning

    International Nuclear Information System (INIS)

    Amos, G.; Roy, R.

    2003-01-01

    A need for an integrated cost estimating tool for nuclear decommissioning and associated waste processing and storage facilities for Intermediate Level Waste (ILW) was defined during the authors recent MSc studies. In order to close the defined gap a prototype tool was developed using logically derived CER's and cost driver variables. The challenge in developing this was to be able to produce a model that could produce realistic cost estimates from the limited levels of historic cost data that was available for analysis. The model is an excel based tool supported by 3 point risk estimating output and is suitable for producing estimates for strategic or optional cost estimates (±30%) early in the conceptual stage of a decommissioning project. The model was validated using minimal numbers of case studies supported by expert opinion discussion. The model provides an enhanced approach for integrated decommissioning estimates which will be produced concurrently with strategic options analysis on a nuclear site

  10. Antioxidant, Cytotoxic Activities and Total Phenolic Content of Four Indonesian Medicinal Plants

    Directory of Open Access Journals (Sweden)

    Waras Nurcholis

    2017-03-01

    Full Text Available The crude ethanol extracts of four Indonesian medicinal plants namely Curcuma xanthorrhiza Roxb.,Phyllanthus niruri Linn., Andrographis paniculata Ness., and Curcuma aeruginosa Roxb. wereexamined for their antioxidant (radical scavenging activity using 2, 2-diphenyl-2-picrylhydrazyl(DPPH free radical and cytotoxicity using brine shrimp lethality test (BSLT. The total phenoliccontent was used the Folin-Ciocalteu method. IC50 values for DPPH radical scavenging activityranged from 14.5 to 178.5 μg/ml, with P. niruri having the lowest value and therefore the mostpotent, and C. aeruginosa having the highest value. LC50 values for BSLT ranged from 210.3 to593.2 μg/ml, with C. xanthorrhiza and A. paniculata having the lowest and highest values,respectively. The total phenolic content of the Indonesian plants ranged from 133.0 ±3.7 to863.3±54.7 mg tannic acid equivalent per 1 g extract, with C. aeruginosa and P. niruri having thelowest and highest values, respectively. A positive correlation between free radical scavengingactivity and the content of phenolic compounds was found in the four of Indonesian medicinal plants.

  11. Effect of Body Mass Index and Psychosocial Traits on Total Knee Replacement Costs in Patients with Osteoarthritis.

    Science.gov (United States)

    Waimann, Christian A; Fernandez-Mazarambroz, Rodrigo J; Cantor, Scott B; Lopez-Olivo, Maria A; Barbo, Andrea G; Landon, Glenn C; Siff, Sherwin J; Lin, Heather; Suarez-Almazor, Maria E

    2016-08-01

    Clinical and psychosocial attributes are associated with clinical outcomes after total knee replacement (TKR) surgery in patients with osteoarthritis (OA), but their relationship with TKR-related costs is less clear. Our objective was to evaluate the effect of clinical and psychosocial attributes on TKR costs. We conducted a 6-month prospective cohort study of patients with knee OA who underwent TKR. We examined baseline demographic, clinical [body mass index (BMI) and comorbidities], and psychosocial attributes (social support, locus of control, coping, depression, anxiety, stress, and self-efficacy); baseline and 6-month OA clinical outcomes [Western Ontario and McMaster Universities Osteoarthritis Index (WOMAC) pain and function]; and 6-month direct and indirect TKR-related costs. Multiple regression was performed to identify determinants of TKR-related costs. We included 212 patients; 66% were women, 71% were white, and the mean age was 65.2 years. The mean baseline WOMAC pain score was 55 (SD 19) and WOMAC function score was 54 (SD 20). Mean total TKR-related costs were US$30,831 (SD $9893). Multivariate regression analyses showed that increasing BMI and anxiety levels and decreasing levels of positive social interactions were associated with increased costs. A lower cost scenario with a lower range of normal BMI (19.5), highest positive social interaction, and no anxiety predicted TKR costs to be $22,247. Predicted costs in obese patients (BMI 36) with lowest positive social interaction and highest anxiety were $58,447. Increased baseline BMI, anxiety, and poor social support lead to higher TKR-related costs in patients with knee OA. Preoperative interventions targeting these factors may reduce TKR-related costs, and therefore be cost-effective.

  12. ORCOST-2, PWR, BWR, HTGR, Fossil Fuel Power Plant Cost and Economics

    International Nuclear Information System (INIS)

    Fuller, L.C.; Myers, M.L.

    1975-01-01

    1 - Description of problem or function: ORCOST2 estimates the cost of electrical energy production from single-unit steam-electric power plants. Capital costs and operating and maintenance costs are calculated using base cost models which are included in the program for each of the following types of plants: PWR, BWR, HTGR, coal, oil, and gas. The user may select one of several input/output options for calculation of capital cost, operating and maintenance cost, levelized energy costs, fixed charge rate, annual cash flows, cumulative cash flows, and cumulative discounted cash flows. Options include the input of capital cost and/or fixed charge rate to override the normal calculations. Transmission and distribution costs are not included. Fuel costs must be input by the user. 2 - Method of solution: The code follows the guidelines of AEC Report NUS-531. A base capital-cost model and a base operating- and maintenance-cost model are selected and adjusted for desired size, location, date, etc. Costs are discounted to the year of first commercial operation and levelized to provide annual cost of electric power generation. 3 - Restrictions on the complexity of the problem: The capital cost models are of doubtful validity outside the 500 to 1500 MW(e) range

  13. Comparison of dwarf bamboos (Indocalamus sp.) leaf parameters to determine relationship between spatial density of plants and total leaf area per plant.

    Science.gov (United States)

    Shi, Pei-Jian; Xu, Qiang; Sandhu, Hardev S; Gielis, Johan; Ding, Yu-Long; Li, Hua-Rong; Dong, Xiao-Bo

    2015-10-01

    The relationship between spatial density and size of plants is an important topic in plant ecology. The self-thinning rule suggests a -3/2 power between average biomass and density or a -1/2 power between stand yield and density. However, the self-thinning rule based on total leaf area per plant and density of plants has been neglected presumably because of the lack of a method that can accurately estimate the total leaf area per plant. We aimed to find the relationship between spatial density of plants and total leaf area per plant. We also attempted to provide a novel model for accurately describing the leaf shape of bamboos. We proposed a simplified Gielis equation with only two parameters to describe the leaf shape of bamboos one model parameter represented the overall ratio of leaf width to leaf length. Using this method, we compared some leaf parameters (leaf shape, number of leaves per plant, ratio of total leaf weight to aboveground weight per plant, and total leaf area per plant) of four bamboo species of genus Indocalamus Nakai (I. pedalis (Keng) P.C. Keng, I. pumilus Q.H. Dai and C.F. Keng, I. barbatus McClure, and I. victorialis P.C. Keng). We also explored the possible correlation between spatial density and total leaf area per plant using log-linear regression. We found that the simplified Gielis equation fit the leaf shape of four bamboo species very well. Although all these four species belonged to the same genus, there were still significant differences in leaf shape. Significant differences also existed in leaf area per plant, ratio of leaf weight to aboveground weight per plant, and leaf length. In addition, we found that the total leaf area per plant decreased with increased spatial density. Therefore, we directly demonstrated the self-thinning rule to improve light interception.

  14. The true costs of participatory sanitation: Evidence from community-led total sanitation studies in Ghana and Ethiopia.

    Science.gov (United States)

    Crocker, Jonny; Saywell, Darren; Shields, Katherine F; Kolsky, Pete; Bartram, Jamie

    2017-12-01

    Evidence on sanitation and hygiene program costs is used for many purposes. The few studies that report costs use top-down costing methods that are inaccurate and inappropriate. Community-led total sanitation (CLTS) is a participatory behavior-change approach that presents difficulties for cost analysis. We used implementation tracking and bottom-up, activity-based costing to assess the process, program costs, and local investments for four CLTS interventions in Ghana and Ethiopia. Data collection included implementation checklists, surveys, and financial records review. Financial costs and value-of-time spent on CLTS by different actors were assessed. Results are disaggregated by intervention, cost category, actor, geographic area, and project month. The average household size was 4.0 people in Ghana, and 5.8 people in Ethiopia. The program cost of CLTS was $30.34-$81.56 per household targeted in Ghana, and $14.15-$19.21 in Ethiopia. Most program costs were from training for three of four interventions. Local investments ranged from $7.93-$22.36 per household targeted in Ghana, and $2.35-$3.41 in Ethiopia. This is the first study to present comprehensive, disaggregated costs of a sanitation and hygiene behavior-change intervention. The findings can be used to inform policy and finance decisions, plan program scale-up, perform cost-effectiveness and benefit studies, and compare different interventions. The costing method is applicable to other public health behavior-change programs. Copyright © 2017 The Authors. Published by Elsevier B.V. All rights reserved.

  15. Hybrid 21 MW wind-solar system to limit energy costs at an industrial plant

    International Nuclear Information System (INIS)

    López, C.

    2016-01-01

    Ereda has undertaken a project that aims to analyse the possibility of limiting the cost of the energy supply to a medium-sized industrial plant, with an installed capacity of over 26 MW, located in the south-west of Kazakhstan. The cost of electricity for its processes accounts for an important part of its production cost, achieving values in excess of 40%. The price of electricity in the country is expected to rise over the coming years. In addition, the plant is now required to reduce CO2 emissions from its industrial activity, which is why a further cost arising from the acquisition of emissions rights is expected in future. (Author)

  16. Capital cost: high and low sulfur coal plants-1200 MWe. [High sulfur coal

    Energy Technology Data Exchange (ETDEWEB)

    1977-01-01

    This Commercial Electric Power Cost Study for 1200 MWe (Nominal) high and low sulfur coal plants consists of three volumes. The high sulfur coal plant is described in Volumes I and II, while Volume III describes the low sulfur coal plant. The design basis and cost estimate for the 1232 MWe high sulfur coal plant is presented in Volume I, and the drawings, equipment list and site description are contained in Volume II. The reference design includes a lime flue gas desulfurization system. A regenerative sulfur dioxide removal system using magnesium oxide is also presented as an alternate in Section 7 Volume II. The design basis, drawings and summary cost estimate for a 1243 MWe low sulfur coal plant are presented in Volume III. This information was developed by redesigning the high sulfur coal plant for burning low sulfur sub-bituminous coal. These coal plants utilize a mechanical draft (wet) cooling tower system for condenser heat removal. Costs of alternate cooling systems are provided in Report No. 7 in this series of studies of costs of commercial electrical power plants.

  17. A capital cost reduction study on the fast breeder reactor plant

    International Nuclear Information System (INIS)

    Taniyama, H.; Kamei, M.; Moriyama, M.

    1991-01-01

    A capital cost reduction study has been performed for large fast breeder reactor designs. The primary objective of this study is to show a trend of capital cost reduction between FBR plants at the prototype stage, the demonstration stage, and the future commercialization stage. For the FBR plant at the demonstration stage a construction cost comparison with a light water reactor has also been performed, and the target cost of FBR of below 1.5 times that of the light water reactor cost was achieved. To extend the capital cost reduction study, a feasibility study was made to achieve a capital cost of an FBR less than that of a light water reactor. The recommended design is shown as a future commercialization FBR design concept. (author)

  18. Total Measurement Uncertainty for the Plutonium Finishing Plant (PFP) Segmented Gamma Scan Assay System

    CERN Document Server

    Fazzari, D M

    2001-01-01

    This report presents the results of an evaluation of the Total Measurement Uncertainty (TMU) for the Canberra manufactured Segmented Gamma Scanner Assay System (SGSAS) as employed at the Hanford Plutonium Finishing Plant (PFP). In this document, TMU embodies the combined uncertainties due to all of the individual random and systematic sources of measurement uncertainty. It includes uncertainties arising from corrections and factors applied to the analysis of transuranic waste to compensate for inhomogeneities and interferences from the waste matrix and radioactive components. These include uncertainty components for any assumptions contained in the calibration of the system or computation of the data. Uncertainties are propagated at 1 sigma. The final total measurement uncertainty value is reported at the 95% confidence level. The SGSAS is a gamma assay system that is used to assay plutonium and uranium waste. The SGSAS system can be used in a stand-alone mode to perform the NDA characterization of a containe...

  19. Evaluation of automated analysis of 15N and total N in plant material and soil

    DEFF Research Database (Denmark)

    Jensen, E.S.

    1991-01-01

    Simultaneous determination of N-15 and total N using an automated nitrogen analyser interfaced to a continuous-flow isotope ratio mass spectrometer (ANA-MS method) was evaluated. The coefficient of variation (CV) of repeated analyses of homogeneous standards and samples at natural abundance...... was lower than 0.1%. The CV of repeated analyses of N-15-labelled plant material and soil samples varied between 0.3% and 1.1%. The reproducibility of repeated total N analyses using the automated method was comparable to results obtained with a semi-micro Kjeldahl procedure. However, the automated method...... analysis showed that the recovery of inorganic N in the NH3 trap was lower when the N was diffused from water than from 2 M KCl. The results also indicated that different proportions of the NO3- and the NH4+ in aqueous solution were recovered in the trap after combined diffusion. The method is most suited...

  20. Calculation of coal power plant cost on agricultural and material building impact of emission

    International Nuclear Information System (INIS)

    Mochamad Nasrullah; Wiku Lulus Widodo

    2016-01-01

    Calculation for externally cost of Coal Power Plant (CPP) is very important. This paper is focus on CPP appear SO 2 impact on agricultural plant and material building. AGRIMAT'S model from International Atomic Energy Agency is model one be used to account environmental damage for air impact because SO 2 emission. Analysis method use Impact Pathways Assessment: Determining characteristic source, Exposure Response Functions (ERF), Impacts and Damage Costs, and Monetary Unit Cost. Result for calculate shows that SO 2 that issued CPP, if value of SO 2 is 19,3 μg/m3, damage cost begins valuably positive. It shows that the land around CPP has decrease prosperity, and it will disadvantage for agricultural plant. On material building, SO 2 resulting damage cost. The increase humidity price therefore damage cost on material building will increase cost. But if concentration SO 2 increase therefore damage cost that is appear on material building decrease. Expected this result can added with external cost on health impact of CPP. External cost was done at developed countries. If it is done at Indonesia, therefore generation cost with fossil as more expensive and will get implication on issue cut back gases greenhouse. On the other side, renewable energy and also alternative energy as nuclear have opportunity at national energy mix system. (author)

  1. Is total pancreatectomy as feasible, safe, efficacious, and cost-effective as pancreaticoduodenectomy? A single center, prospective, observational study.

    Science.gov (United States)

    Casadei, Riccardo; Ricci, Claudio; Taffurelli, Giovanni; Guariniello, Anna; Di Gioia, Anthony; Di Marco, Mariacristina; Pagano, Nico; Serra, Carla; Calculli, Lucia; Santini, Donatella; Minni, Francesco

    2016-09-01

    Total pancreatectomy is actually considered a viable option in selected patients even if large comparative studies between partial versus total pancreatectomy are not currently available. Our aim was to evaluate whether total pancreatectomy can be considered as feasible, safe, efficacious, and cost-effective as pancreaticoduodenectomy. A single center, prospective, observational trial, regarding postoperative outcomes, long-term results, and cost-effectiveness, in a tertiary referral center was conducted, comparing consecutive patients who underwent elective total pancreatectomy and/or pancreaticoduodenectomy. Seventy-three consecutive elective total pancreatectomies and 184 pancreaticoduodenectomies were compared. There were no significant differences regarding postoperative outcomes and overall survival. The quality of life, evaluated in 119 patients according to the EQ-5D-5L questionnaire, showed that there were no significant differences regarding the five items considered. The mean EQ-5D-5L score was similar in the two procedures (total pancreatectomy = 0.872, range 0.345-1.000; pancreaticoduodenectomy = 0.832, range 0.393-1.000; P = 0.320). The impact of diabetes according to the Problem Areas in Diabetes (PAID) questionnaire did not show any significant differences except for question 13 (total pancreatectomy = 0.60; pancreaticoduodenectomy = 0.19; P = 0.022). The cost-effectiveness analysis suggested that the quality-adjusted life year was not significantly different between the two procedures (total pancreatectomy = 0.910, range 0.345-1.000; pancreaticoduodenectomy = 0.910, range -0.393-1.000; P = 0.320). From this study, it seems reasonable to suggest that total pancreatectomy can be considered as safe, feasible, and efficacious as PD and acceptable in terms of cost-effectiveness.

  2. Federal Regulations: Efforts to Estimate Total Costs and Benefits of Rules

    Science.gov (United States)

    2004-04-07

    the Chamber of Commerce , academicians, the media, and others, and is sometimes cited with a high degree of certainty ." For example, some articles...House of Representatives, Feb . 25,2004; and testimony of William P . Kovacs, Vice President, U .S. Chamber of Commerce , before the Subcommittee on Energy...estimated the annual cost to employers of the Family and Medical Leave Act at $825 million, but that the Chamber of Commerce estimated the cost at between $3

  3. Biological invasions: economic and environmental costs of alien plant, animal, and microbe species

    National Research Council Canada - National Science Library

    Pimentel, David

    2011-01-01

    ...: Economic and Environmental Costs of Alien Plant, Animal, and Microbe Species, this reference discusses how non-native species invade new ecosystems and the subsequent economic and environmental effects of these species...

  4. An application of the 'Bayesian cohort model' to nuclear power plant cost analyses

    International Nuclear Information System (INIS)

    Ono, Kenji; Nakamura, Takashi

    2002-01-01

    We have developed a new method for identifying the effects of calendar year, plant age and commercial operation starting year on the costs and performances of nuclear power plants and also developed an analysis system running on personal computers. The method extends the Bayesian cohort model for time series social survey data proposed by one of the authors. The proposed method was shown to be able to separate the above three effects more properly than traditional methods such as taking simple means by time domain. The analyses of US nuclear plant cost and performance data by using the proposed method suggest that many of the US plants spent relatively long time and much capital cost for modification at their age of about 10 to 20 years, but that, after those ages, they performed fairly well with lower and stabilized O and M and additional capital costs. (author)

  5. Determining the Cost-Savings Threshold and Alignment Accuracy of Patient-Specific Instrumentation in Total Ankle Replacements.

    Science.gov (United States)

    Hamid, Kamran S; Matson, Andrew P; Nwachukwu, Benedict U; Scott, Daniel J; Mather, Richard C; DeOrio, James K

    2017-01-01

    Traditional intraoperative referencing for total ankle replacements (TARs) involves multiple steps and fluoroscopic guidance to determine mechanical alignment. Recent adoption of patient-specific instrumentation (PSI) allows for referencing to be determined preoperatively, resulting in less steps and potentially decreased operative time. We hypothesized that usage of PSI would result in decreased operating room time that would offset the additional cost of PSI compared with standard referencing (SR). In addition, we aimed to compare postoperative radiographic alignment between PSI and SR. Between August 2014 and September 2015, 87 patients undergoing TAR were enrolled in a prospectively collected TAR database. Patients were divided into cohorts based on PSI vs SR, and operative times were reviewed. Radiographic alignment parameters were retrospectively measured at 6 weeks postoperatively. Time-driven activity-based costing (TDABC) was used to derive direct costs. Cost vs operative time-savings were examined via 2-way sensitivity analysis to determine cost-saving thresholds for PSI applicable to a range of institution types. Cost-saving thresholds defined the price of PSI below which PSI would be cost-saving. A total of 35 PSI and 52 SR cases were evaluated with no significant differences identified in patient characteristics. Operative time from incision to completion of casting in cases without adjunct procedures was 127 minutes with PSI and 161 minutes with SR ( P cost-savings threshold range at our institution of $863 below which PSI pricing would provide net cost-savings. Two-way sensitivity analysis generated a globally applicable cost-savings threshold model based on institution-specific costs and surgeon-specific time-savings. This study demonstrated equivalent postoperative TAR alignment with PSI and SR referencing systems but with a significant decrease in operative time with PSI. Based on TDABC and associated sensitivity analysis, a cost-savings threshold

  6. Probabilistic Analysis of Electrical Energy Costs: Comparing Production Costs for Gas, Coal and Nuclear Power Plants. Annex III

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2013-12-15

    The increase in electricity demand is linked to the development of the economy and living standards in each country. This is especially true in those developing countries in which electricity consumption is far below the average of industrialized countries. To satisfy the increased demand for electricity, it is necessary to build new electrical power plants that could, in an optimum way, meet the imposed acceptability criteria. The main criteria are the potential to supply the required energy and to supply it with minimum or, at least, acceptable costs and environmental impacts, to satisfy the licensing requirements and be acceptable to the public. The main competitors for electricity production in the next few decades are fossil fuel power plants (coal and gas) and nuclear power plants. Power plants making use of renewables (solar, wind, biomass) are also important, but due to limited energy supply potential and high costs, can only be a supplement to the main generating units. Large hydropower plants would be competitive under the condition that suitable sites for the construction of such plants exist. Unfortunately, both in Croatia and in the rest of central Europe, such sites are scarce.

  7. Long term developments in irradiated natural uranium processing costs. Optimal size and siting of plants

    International Nuclear Information System (INIS)

    Thiriet, L.

    1964-01-01

    The aim of this paper is to help solve the problem of the selection of optimal sizes and sites for spent nuclear fuel processing plants associated with power capacity programmes already installed. Firstly, the structure of capital and running costs of irradiated natural uranium processing plants is studied, as well as the influence of plant sizes on these costs and structures. Shipping costs from the production site to the plant must also be added to processing costs. An attempt to reach a minimum cost for the production of a country or a group of countries must therefore take into account both the size and the location of the plants. The foreseeable shipping costs and their structure (freight, insurance, container cost and depreciation), for spent natural uranium are indicated. Secondly, for various annual spent fuel reprocessing programmes, the optimal sizes and locations of the plants are determined. The sensitivity of the results to the basic assumptions relative to processing costs, shipping costs, the starting up year of the plant programme and the length of period considered, is also tested. - this rather complex problem, of a combinative nature, is solved through dynamic programming methods. - It is shown that these methods can also be applied to the problem of selecting the optimal sizes and locations of processing plants for MTR type fuel elements, related to research reactor programmes, as well as to future plutonium element processing plants related to breeder reactors. Thirdly, the case where yearly extraction of the plutonium contained in the irradiated natural uranium is not compulsory is examined; some stockpiling of the fuel is then allowed some years, entailing delayed processing. The load factor of such plants is thus greatly improved with respect to that of plants where the annual plutonium demand is strictly satisfied. By including spent natural uranium stockpiling costs an optimal rhythm of introduction and optimal sizes for spent fuel

  8. A study of feasibility, design and cost of excavations for underground siting of nuclear power plants

    International Nuclear Information System (INIS)

    1976-02-01

    A study conducted for the State Power Board on underground siting of nuclear power plants is presented. The report is divided into two chapters, both concerning the technical aspects of large underground openings. The first chapter gives a brief general survey of the problems involved, and the second outlines the technical aspects of a PWR project at a specific site. Details are given in 8 appendices and arrangement drawings. The project differs from conventional hydroelectric excavation schemes mainly in the fact that the spherical reactor containment requires a vault of 60m free span, and the turbine hall a cylindrical vault of 45m span, both of which exceed any span hitherto built for similar purposes. This requires a comparatively wide extrapolation of tested and available experience in underground excavations for permanent civil use. To what extent and under what circumstances such extrapolation is tenable must be tested in practice, preferably in a specially controlled prototype test. However the study indicates that conventional nuclear power plants can be sited underground when the topography and rock conditions are suitable. A 1000-2000 MW conventional plant adapted for underground siting will require large span caverns, tunnels and shafts, totalling about 1.0 mill. cubic metres of underground excavation. In addition access and cooling water tunnels, depending on the location, will require 0.2-0.5 mill. cubic metres of tunnel excavations. The excavations and support work can be completed within a construction time of about 2 1/2 years at an estimated total cost of 215 mill. Norwegian kroner (1975 value). (JIW)

  9. Total quality control: the deming management philosophy applied to nuclear power plants

    International Nuclear Information System (INIS)

    Heising, C.D.; Wetherell, D.L.; Melhem, S.A.; Sato, M.

    1987-01-01

    In recent years, a call has come for the development of inherently safe nuclear reactor systems that cannot have large-scale accidents. In the search for the perfect inherently safe reactor system, some are calling for the institution of computerized automated control of reactors eliminating most human operators from the control room. A different approach to the problem of the control of inherently safe reactors is that both future and present nuclear power plants need to institute total quality control (TQC) to plant operations and management. The Deming management philosophy of TQC has been implemented in a wide range of industries - particularly in Japan and the US. Specific attention is given, however, to TQC implementation in the electric power industry as applied to nuclear plants. The Kansai Electric Power Company and Florida Power and Light Company have recently implemented TQC. Statistical quality control methods have been applied to monitor and control reactor variables (for example, to the steam generator water level important to start-up operations of pressurized water reactors)

  10. Effect of construction time, interest rate, and inflation on the capital cost of nuclear power plants

    International Nuclear Information System (INIS)

    Abel, P.S.; Greybeck, E.M.; Omberg, R.P.

    1981-09-01

    Cost estimates for nuclear power plants currently under construction are on the order of four billion dollars. It will be shown, in this paper, that this is a direct consequence of relatively high inflation rates and relatively long construction times. If either inflation rates or construction times, or a combination thereof, should decrease significantly, cost estimates for nuclear power plants could return to approximately two billion dollars

  11. Comparative Study on Electric Generation Cost of HTR with Another Electric Plant Using LEGECOST Program

    International Nuclear Information System (INIS)

    Mochamad-Nasrullah; Soetrisnanto, Arnold Y.; Tosi-Prastiadi; Adiwardojo

    2000-01-01

    Monetary and economic crisis in Indonesia resulted in impact of electricity and demand and supply planning that it has to be reevaluated. One of the reasons is budget limitation of the government as well as private companies. Considering this reason, the economic calculation for all of aspect could be performed, especially the calculation of electric generation cost. This paper will discuss the economic aspect of several power plants using fossil and nuclear fuel including High Temperature Reactor (HTR). Using Levelized Generation Cost (LEGECOST) program developed by IAEA (International Atomic Energy Agency), the electric generation cost of each power plant could be calculated. And then, the sensitivity analysis has to be done using several economic parameters and scenarios, in order to be known the factors that influence the electric generation cost. It could be concluded, that the electric generation cost of HTR is cheapest comparing the other power plants including nuclear conventional. (author)

  12. Total phenol content and antioxidant activity of water solutions of plant extracts

    Directory of Open Access Journals (Sweden)

    Mirela Kopjar

    2009-01-01

    Full Text Available Water solutions of extracts were investigated for total phenol content, flavonoid content and antioxidant activity. Susceptibility to degradation of water solutions of plant extracts, under light and in the dark, during storage at room temperature was investigated in order to determine their stability prior to their application for fortification of food products. Large dispersion of total phenol (TP content in the investigated model solutions of selected extracts (olive leaves, green tea, red grape, red wine, pine bark PE 5:1, pine bark PE 95 %, resveratrol, ranging from 11.10 mg GAE/100 mL to 92.19 mg GAE/100 mL was observed. Consequently, large dispersion of total flavonoids (TF content (8.89 mg to 61.75 mg CTE/100 mL was also observed. Since phenols have been mostly responsible for antioxidant activity of extracts, in most cases, antioxidant activity followed the TP content. That was proven by estimation of correlation coefficient between the total phenol content and antioxidant activity. Correlation coefficients between investigated parameters ranged from 0.5749 to 0.9604. During storage of 5 weeks at room temperature loss of phenols and flavonoids occurred. Antioxidant activity decreased with the decrease of TP and TF content. Degradations of phenols and flavonoids were more pronounced in samples stored at light.

  13. Self-reported Function, Health Resource Use, and Total Health Care Costs Among Medicare Beneficiaries With Glaucoma.

    Science.gov (United States)

    Prager, Alisa J; Liebmann, Jeffrey M; Cioffi, George A; Blumberg, Dana M

    2016-04-01

    The effect of glaucoma on nonglaucomatous medical conditions and resultant secondary health care costs is not well understood. To assess self-reported medical conditions, the use of medical services, and total health care costs among Medicare beneficiaries with glaucoma. Longitudinal observational study of 72,587 Medicare beneficiaries in the general community using the Medicare Current Beneficiary Survey (2004-2009). Coding to extract data started in January 2015, and analyses were performed between May and July 2015. Self-reported health, the use of health care services, adjusted mean annual total health care costs per person, and adjusted mean annual nonoutpatient costs per person. Participants were 72,587 Medicare beneficiaries 65 years or older with (n = 4441) and without (n = 68,146) a glaucoma diagnosis in the year before collection of survey data. Their mean age was 76.9 years, and 43.2% were male. Patients with glaucoma who responded to survey questions on visual disability were stratified into those with (n = 1748) and without (n = 2639) self-reported visual disability. Medicare beneficiaries with glaucoma had higher adjusted odds of inpatient hospitalizations (odds ratio [OR], 1.27; 95% CI, 1.17-1.39; P total health care costs and $2599 (95% CI, $1985-$3212; P total and nonoutpatient medical costs. Perception of vision loss among patients with glaucoma may be associated with depression, falls, and difficulty walking. Reducing the prevalence and severity of glaucoma may result in improvements in associated nonglaucomatous medical conditions and resultant reduction in health care costs.

  14. Optimum Dispatch of Hybrid Solar Thermal (HSTP Electric Power Plant Using Non-Smooth Cost Function and Emission Function for IEEE-30 Bus System

    Directory of Open Access Journals (Sweden)

    Saroj Kumar Dash

    2016-07-01

    Full Text Available The basic objective of economic load dispatch (ELD is to optimize the total fuel cost of hybrid solar thermal electric power plant (HSTP. In ELD problems the cost function for each generator has been approximated by a single quadratic cost equation. As cost of coal increases, it becomes even more important have a good model for the production cost of each generator for the solar thermal hybrid system. A more accurate formulation is obtained for the ELD problem by expressing the generation cost function as a piece wise quadratic cost function. However, the solution methods for ELD problem with piece wise quadratic cost function requires much complicated algorithms such as the hierarchical structure approach along with evolutionary computations (ECs. A test system comprising of 10 units with 29 different fuel [7] cost equations is considered in this paper. The applied genetic algorithm method will provide optimal solution for the given load demand.

  15. Waste Management Strategy for Dismantling Waste to Reduce Costs for Power Plant Decommissioning - 13543

    Energy Technology Data Exchange (ETDEWEB)

    Larsson, Arne; Lidar, Per [Studsvik Nuclear AB, SE-611 82 Nykoeping (Sweden); Bergh, Niklas; Hedin, Gunnar [Westinghouse Electric Sweden AB, Fredholmsgatan 2, SE-721 63, Vaesteraas (Sweden)

    2013-07-01

    Decommissioning of nuclear power plants generates large volumes of radioactive or potentially radioactive waste. The proper management of the dismantling waste plays an important role for the time needed for the dismantling phase and thus is critical to the decommissioning cost. An efficient and thorough process for inventorying, characterization and categorization of the waste provides a sound basis for the planning process. As part of comprehensive decommissioning studies for Nordic NPPs, Westinghouse has developed the decommissioning inventories that have been used for estimations of the duration of specific work packages and the corresponding costs. As part of creating the design basis for a national repository for decommissioning waste, the total production of different categories of waste packages has also been predicted. Studsvik has developed a risk based concept for categorization and handling of the generated waste using six different categories with a span from extremely small risk for radiological contamination to high level waste. The two companies have recently joined their skills in the area of decommissioning on selected market in a consortium named 'ndcon' to further strengthen the proposed process. Depending on the risk for radiological contamination or the radiological properties and other properties of importance for waste management, treatment routes are proposed with well-defined and proven methods for on-site or off-site treatment, activity determination and conditioning. The system is based on a graded approach philosophy aiming for high confidence and sustainability, aiming for re-use and recycling where found applicable. The objective is to establish a process where all dismantled material has a pre-determined treatment route. These routes should through measurements, categorization, treatment, conditioning, intermediate storage and final disposal be designed to provide a steady, un-disturbed flow of material to avoid

  16. Waste Management Strategy for Dismantling Waste to Reduce Costs for Power Plant Decommissioning - 13543

    International Nuclear Information System (INIS)

    Larsson, Arne; Lidar, Per; Bergh, Niklas; Hedin, Gunnar

    2013-01-01

    Decommissioning of nuclear power plants generates large volumes of radioactive or potentially radioactive waste. The proper management of the dismantling waste plays an important role for the time needed for the dismantling phase and thus is critical to the decommissioning cost. An efficient and thorough process for inventorying, characterization and categorization of the waste provides a sound basis for the planning process. As part of comprehensive decommissioning studies for Nordic NPPs, Westinghouse has developed the decommissioning inventories that have been used for estimations of the duration of specific work packages and the corresponding costs. As part of creating the design basis for a national repository for decommissioning waste, the total production of different categories of waste packages has also been predicted. Studsvik has developed a risk based concept for categorization and handling of the generated waste using six different categories with a span from extremely small risk for radiological contamination to high level waste. The two companies have recently joined their skills in the area of decommissioning on selected market in a consortium named 'ndcon' to further strengthen the proposed process. Depending on the risk for radiological contamination or the radiological properties and other properties of importance for waste management, treatment routes are proposed with well-defined and proven methods for on-site or off-site treatment, activity determination and conditioning. The system is based on a graded approach philosophy aiming for high confidence and sustainability, aiming for re-use and recycling where found applicable. The objective is to establish a process where all dismantled material has a pre-determined treatment route. These routes should through measurements, categorization, treatment, conditioning, intermediate storage and final disposal be designed to provide a steady, un-disturbed flow of material to avoid interruptions. Bottle

  17. Costs of Residential Solar PV Plants in Distribution Grid Networks

    DEFF Research Database (Denmark)

    Kjær, Søren Bækhøj; Yang, Guangya; Ipsen, Hans Henrik

    2015-01-01

    In this article we investigate the impact of residential solar PV plants on energy losses in distribution networks and their impact on distribution transformers lifetime. Current guidelines in Denmark states that distribution transformers should not be loaded with more than 67% solar PV power...

  18. Corruption Significantly Increases the Capital Cost of Power Plants in Developing Contexts

    Directory of Open Access Journals (Sweden)

    Kumar Biswajit Debnath

    2018-03-01

    Full Text Available Emerging economies with rapidly growing population and energy demand, own some of the most expensive power plants in the world. We hypothesized that corruption has a relationship with the capital cost of power plants in developing countries such as Bangladesh. For this study, we analyzed the capital cost of 61 operational and planned power plants in Bangladesh. Initial comparison study revealed that the mean capital cost of a power plant in Bangladesh is twice than that of the global average. Then, the statistical analysis revealed a significant correlation between corruption and the cost of power plants, indicating that higher corruption leads to greater capital cost. The high up-front cost can be a significant burden on the economy, at present and in the future, as most are financed through international loans with extended repayment terms. There is, therefore, an urgent need for the review of the procurement and due diligence process of establishing power plants, and for the implementation of a more transparent system to mitigate adverse effects of corruption on megaprojects.

  19. A Total Cost of Ownership Model for Low Temperature PEM Fuel Cells in Combined Heat and Power and Backup Power Applications

    Energy Technology Data Exchange (ETDEWEB)

    University of California, Berkeley; Wei, Max; Lipman, Timothy; Mayyas, Ahmad; Chien, Joshua; Chan, Shuk Han; Gosselin, David; Breunig, Hanna; Stadler, Michael; McKone, Thomas; Beattie, Paul; Chong, Patricia; Colella, Whitney; James, Brian

    2014-06-23

    A total cost of ownership model is described for low temperature proton exchange membrane stationary fuel cell systems for combined heat and power (CHP) applications from 1-250kW and backup power applications from 1-50kW. System designs and functional specifications for these two applications were developed across the range of system power levels. Bottom-up cost estimates were made for balance of plant costs, and detailed direct cost estimates for key fuel cell stack components were derived using design-for-manufacturing-and-assembly techniques. The development of high throughput, automated processes achieving high yield are projected to reduce the cost for fuel cell stacks to the $300/kW level at an annual production volume of 100 MW. Several promising combinations of building types and geographical location in the U.S. were identified for installation of fuel cell CHP systems based on the LBNL modelling tool DER CAM. Life-cycle modelling and externality assessment were done for hotels and hospitals. Reduced electricity demand charges, heating credits and carbon credits can reduce the effective cost of electricity ($/kWhe) by 26-44percent in locations such as Minneapolis, where high carbon intensity electricity from the grid is displaces by a fuel cell system operating on reformate fuel. This project extends the scope of existing cost studies to include externalities and ancillary financial benefits and thus provides a more comprehensive picture of fuel cell system benefits, consistent with a policy and incentive environment that increasingly values these ancillary benefits. The project provides a critical, new modelling capacity and should aid a broad range of policy makers in assessing the integrated costs and benefits of fuel cell systems versus other distributed generation technologies.

  20. Total Costs and Benefits of Biomass in Selected regions of the European Union

    DEFF Research Database (Denmark)

    Almeida, A. de; Bauen, A.; Costa, F.B.

    1998-01-01

    biomass for combined heat and power generation in Vaernamo, Sweden, and Eggborough, UK, versus the use of coal in the Naessjoe plant mentioned above and a UK power plant;- production of cold-pressed rape-seed oil and its use in a cogeneration plant at Weissenburg, Germany, versus the use of diesel fuel...... and power production in Mangualde, Portugal, versus the use of fuel oil in an engine generating heat and power;- production of biogas from animal slurry for municipal combined heat an power generation at Hashoej, Denmark, versus the use fo Danish natural gas in the same engine;- gasification of woody...... in a similar engine;- production of rape-seed oil methyl ester (RME) and its use for goods transport in Germay, versus the use of diesel fuel in the same fleet of trucks;- production of ethyl tertiary butyl ether (ETBE) from sugar beets and sweet sorghum for transport applications in France, versus the use...

  1. Total flavonoids content and biochemical screening of the leaves of tropical endemic medicinal plant Merremia borneensis

    Directory of Open Access Journals (Sweden)

    Muhammad Dawood Shah

    2014-12-01

    Full Text Available The developing and under developed countries mostly rely on traditional medicines. This herbal or traditional medicine involves the use of different types of organic extracts or the bioactive chemical constituents. This type of biochemical investigation provides health care at an affordable cost. This survey such as ethnomedicine keenly represents one of the best avenues in searching new economic plants for medicines. Keeping this view in mind, the present study is carried out in Merremia borneensis leaves of University Malaysia Sabah, Sabah, Malaysia. The plant has several beneficial properties, such as antioxidant activity. The dry powder of the leaves of M. borneensis was extracted with hexane, ethyl acetate, chloroform, butanol and aqueous ethanol. The flavonoids content of the extracts was determined by Willet method. The flavonoids content of the extracts as quercetin equivalents was found to be highest in aqueous ethanol (53.28% followed by chloroform (38.83%, ethyl acetate (24.51%, butanol (12.54% and hexane extract (3.44%. The results suggest the presence of phytochemical properties in the leaves, which are used in curing the ailments.

  2. Piedmont community tree guide: benefits, costs, and strategic planting

    Science.gov (United States)

    E. Gregory McPherson; James R. Simpson; Paula J. Peper; Shelley L. Gardner; Kelaine E. Vargas; Scott E. Maco; Qingfu Xiao

    2006-01-01

    This report quantifies benefits and costs for small, medium, and large broadleaf trees and one coniferous tree in the Piedmont region: the species chosen as representative are dogwood (Cornus florida), Southern magnolia (Magnolia grandiflora), red maple (Acer rubrum), and loblolly pine (Pinus taeda...

  3. Guidelines for producing commercial nuclear power plant decommissioning cost estimates

    International Nuclear Information System (INIS)

    La Guardia, T.S.

    1986-01-01

    The guidelines are not intended to be a ''cookbook'' or a ''standard''. Their purpose is to ensure all decomissioning cost elements are properly included and to provide guidance on the detail required. Other methodologies may be used if they accomplish this objective

  4. New technologies for lower-cost design and construction of new nuclear power plants. Annex 20

    International Nuclear Information System (INIS)

    Ritterbusch, S.E.; Bryan, R.E.; Harmon, D.L.

    2002-01-01

    Electric Power Research Institute studies indicate that in order to be competitive with gas-fired electric power plant capital costs, new nuclear plant capital cost in the USA must be decreased by at least 35% to 40% relative to costs of some Advanced Light Water Reactors designed in the early 1990s. To address this need, the U. S. Department of Energy is sponsoring three separate projects under its Nuclear Energy Research Initiative. These projects are the Risk-Informed Assessment of Regulatory and Design Requirements for Future Nuclear Power Plants, the Smart Equipment Nuclear Power Plant Program, and the Design, Procure, Construct, Install and Test Program. The goal of the Design-Construction program is reduction of the complete nuclear plant design-procure-construct-install-test cycle schedule and cost. A 3D plant model was combined with a construction schedule to produce a 4D visualization of plant construction, which was then used to analyze plant construction methods. Insights include the need for concurrent engineering, a plant-wide central database, and use of the World-Wide WEB. The goal of Smart Equipment program is to design, develop, and evaluate the methods for implementing smart equipment and predictive maintenance technology. 'Smart' equipment means components and systems that are instrumented and monitored to detect incipient failures in order to improve their reliability. The resulting smart equipment methods will be combined with a more risk-informed regulatory approach to allow plant designers to (1) simplify designs without compromising overall reliability and safety and (2) maintain more reliable plants at lower cost. Initial results show that rotating equipment such as charging pumps would benefit most from smart instrumentation and that the technique of Bayesian Belief Networks would be most appropriate for providing input to a health monitoring system. (author)

  5. Metaldyne. Plant-Wide Assessment at Royal Oak Finds Opportunities to Improve Manufacturing Effciency, Reduce Energy Use, and Achieve Sigificant Cost Savings

    Energy Technology Data Exchange (ETDEWEB)

    None, None

    2005-05-01

    This case study prepared for the U.S. Department of Energy's Industrial Technologies Program describes a plant-wide energy assessment conducted at the Metaldyne, Inc., forging plant in Royal Oak, Michigan. The assessment focused on reducing the plant's operating costs, inventory, and energy use. If the company were to implement all the recommendations that came out of the assessment, its total annual energy savings for electricity would be about 11.5 million kWh and annual cost savings would be $12.6 million.

  6. Metaldyne: Plant-Wide Assessment at Royal Oak Finds Opportunities to Improve Manufacturing Efficiency, Reduce Energy Use, and Achieve Significant Cost Savings

    Energy Technology Data Exchange (ETDEWEB)

    2005-05-01

    This case study prepared for the U.S. Department of Energy's Industrial Technologies Program describes a plant-wide energy assessment conducted at the Metaldyne, Inc., forging plant in Royal Oak, Michigan. The assessment focused on reducing the plant's operating costs, inventory, and energy use. If the company were to implement all the recommendations that came out of the assessment, its total annual energy savings for electricity would be about 11.5 million kWh and annual cost savings would be $12.6 million.

  7. The potential of urban tree plantings to be cost effective in carbon credit markets

    Science.gov (United States)

    M.R. McHale; E.G. McPherson; I.C. Burke

    2007-01-01

    Emission trading is considered to be an economically sensitive method for reducing the concentrations of greenhouse gases, particularly carbon dioxide, in the atmosphere. There has been debate about the viability of using urban tree plantings in these markets. The main concern is whether or not urban planting projects can be cost effective options for investors. We...

  8. Cost-Effectiveness of Emission Reduction for the Indonesian Coal-Fired Power Plants

    NARCIS (Netherlands)

    Handayani, Kamia; Krozer, Yoram

    2014-01-01

    This paper presents the result of research on the cost-effectiveness of emission reduction in the selected coal-fired power plants (CFPPs) in Indonesia. The background of this research is the trend of more stringent environmental regulation regarding air emission from coal-fired power plants (CFPPs)

  9. Incidence, risk factors and the healthcare cost of falls postdischarge after elective total hip and total knee replacement surgery: protocol for a prospective observational cohort study

    Science.gov (United States)

    Hill, Anne-Marie; Ross-Adjie, Gail; McPhail, Steven M; Monterosso, Leanne; Bulsara, Max; Etherton-Beer, Christopher; Powell, Sarah-Jayne; Hardisty, Gerard

    2016-01-01

    Introduction The number of major joint replacement procedures continues to increase in Australia. The primary aim of this study is to determine the incidence of falls in the first 12 months after discharge from hospital in a cohort of older patients who undergo elective total hip or total knee replacement. Methods and analyses A prospective longitudinal observational cohort study starting in July 2015, enrolling patients aged ≥60 years who are admitted for elective major joint replacement (n=267 total hip replacement, n=267 total knee replacement) and are to be discharged to the community. Participants are followed up for 12 months after hospital discharge. The primary outcome measure is the rate of falls per thousand patient-days. Falls data will be collected by 2 methods: issuing a falls diary to each participant and telephoning participants monthly after discharge. Secondary outcomes include the rate of injurious falls and health-related quality of life. Patient-rated outcomes will be measured using the Oxford Hip or Oxford Knee score. Generalised linear mixed modelling will be used to examine the falls outcomes in the 12 months after discharge and to examine patient and clinical characteristics predictive of falls. An economic evaluation will be conducted to describe the nature of healthcare costs in the first 12 months after elective joint replacement and estimate costs directly attributable to fall events. Ethics and dissemination The results will be disseminated through local site networks and will inform future services to support older people undergoing hip or knee joint replacement and also through peer-reviewed publications and medical conferences. This study has been approved by The University of Notre Dame Australia and local hospital human research ethics committees. Trial registration number ACTRN12615000653561; Pre-results. PMID:27412102

  10. Quantifying the total cost of infrastructure to enable environmentally preferable decisions: the case of urban roadway design

    International Nuclear Information System (INIS)

    Gosse, Conrad A; Clarens, Andres F

    2013-01-01

    Efforts to reduce the environmental impacts of transportation infrastructure have generally overlooked many of the efficiencies that can be obtained by considering the relevant engineering and economic aspects as a system. Here, we present a framework for quantifying the burdens of ground transportation in urban settings that incorporates travel time, vehicle fuel and pavement maintenance costs. A Pareto set of bi-directional lane configurations for two-lane roadways yields non-dominated combinations of lane width, bicycle lanes and curb parking. Probabilistic analysis and microsimulation both show dramatic mobility reductions on road segments of insufficient width for heavy vehicles to pass bicycles without encroaching on oncoming traffic. This delay is positively correlated with uphill grades and increasing traffic volumes and inversely proportional to total pavement width. The response is nonlinear with grade and yields mixed uphill/downhill optimal lane configurations. Increasing bicycle mode share is negatively correlated with total costs and emissions for lane configurations allowing motor vehicles to safely pass bicycles, while the opposite is true for configurations that fail to facilitate passing. Spatial impacts on mobility also dictate that curb parking exhibits significant spatial opportunity costs related to the total cost Pareto curve. The proposed framework provides a means to evaluate relatively inexpensive lane reconfiguration options in response to changing modal share and priorities. These results provide quantitative evidence that efforts to reallocate limited pavement space to bicycles, like those being adopted in several US cities, could appreciably reduce costs for all users. (letter)

  11. Quantifying the total cost of infrastructure to enable environmentally preferable decisions: the case of urban roadway design

    Science.gov (United States)

    Gosse, Conrad A.; Clarens, Andres F.

    2013-03-01

    Efforts to reduce the environmental impacts of transportation infrastructure have generally overlooked many of the efficiencies that can be obtained by considering the relevant engineering and economic aspects as a system. Here, we present a framework for quantifying the burdens of ground transportation in urban settings that incorporates travel time, vehicle fuel and pavement maintenance costs. A Pareto set of bi-directional lane configurations for two-lane roadways yields non-dominated combinations of lane width, bicycle lanes and curb parking. Probabilistic analysis and microsimulation both show dramatic mobility reductions on road segments of insufficient width for heavy vehicles to pass bicycles without encroaching on oncoming traffic. This delay is positively correlated with uphill grades and increasing traffic volumes and inversely proportional to total pavement width. The response is nonlinear with grade and yields mixed uphill/downhill optimal lane configurations. Increasing bicycle mode share is negatively correlated with total costs and emissions for lane configurations allowing motor vehicles to safely pass bicycles, while the opposite is true for configurations that fail to facilitate passing. Spatial impacts on mobility also dictate that curb parking exhibits significant spatial opportunity costs related to the total cost Pareto curve. The proposed framework provides a means to evaluate relatively inexpensive lane reconfiguration options in response to changing modal share and priorities. These results provide quantitative evidence that efforts to reallocate limited pavement space to bicycles, like those being adopted in several US cities, could appreciably reduce costs for all users.

  12. Nuclear generating station and heavy water plant cost estimates for strategy studies

    International Nuclear Information System (INIS)

    Archinoff, G.H.

    1979-07-01

    Nuclear generating station capital, operating and maintenance costs are basic input data for strategy analyses of alternate nuclear fuel cycles. This report presents estimates of these costs for natural uranium CANDU stations, CANDU stations operating on advanced fuel cycles, and liquid metal fast breeder reactors. Cost estimates for heavy water plants are also presented. The results show that station capital costs for advanced fuel cycles are not expected to be significantly greater than those for natural uranium stations. LMFBR capital costs are expected to be 25-30 percent greater than for CANDU's. (auth)

  13. Transmission avoided cost: a new parameter to evaluate the economic competitiveness of generations plants projects

    Energy Technology Data Exchange (ETDEWEB)

    Ramos, D S [Companhia Energetica de Sao Paulo, SP (Brazil); Albuquerque, J C.R.; Rosenblat, J [ELETROBRAS, Rio de Janeiro, RJ (Brazil)

    1994-12-31

    The paper presents a new formulation that makes feasible a composition of long run production marginal costs with the long run transmission marginal costs, including the costs related to the interconnection EHV networks and that related to the voltage levels below. The goal top be attained is to have available a more adequate parameter in order to compare production cost related to a plant, that will be connected to a certain voltage level network, to the cost related supplying the sam,e amount of energy from the bulk power system which will be represented by the marginal costs up to the voltage level under consideration. This procedure brings to light the Transmission Avoided Costs concepts, that are stressed throughout the text. The proposed methodology is now being used, in the brazilian Power Sector, as a rule of thumb in order to guide planning decisions about the schedule of new plants that have installed capacity below 30 MW. For plants with higher capacity, the transmission avoided costs are evaluated for each specific case, simulating the system behavior without the quoted hydroelectric plant. This paper focuses, an an application example, the case of the Canoas Hydroelectric Project, recently included in the Generation Expansion Reference Plan after a detailed analysis supported by the methodology described here. (author) 7 refs., 3 tabs.

  14. Evaluation of the Influence of the Logistic Operations Reliability on the Total Costs of a Supply Chain

    Directory of Open Access Journals (Sweden)

    Lukinskiy Valery

    2016-12-01

    Full Text Available Nowadays in logistics integral processes between the material and related flows in supply chains are getting developed more and more. However, in spite of increasing volume of statistical data which reflect the integral processes, the influence evaluation issues of the logistic operations reliability indexes on the total logistics costs remain open and require the corresponding researches implementation.

  15. Cost-effectiveness of low-power nuclear power plants

    International Nuclear Information System (INIS)

    Mitenkov, F.M.; Vostokov, V.S.; Drozhkin, V.N.; Samoilov, O.B.

    1994-01-01

    Many potential consumers of electricity and heat, consuming several thousands of kilowatts (up to 10-15 MW), have now been identified. This is significant primarily for regions far from power grids and other centralized sources of energy, such as, for example, Yakutiya, Northeastern Siberia, and elsewhere. These consumers are now supplied with fossil fuel, which is often difficult and expensive to deliver. For this reason it is very important to develop low-power nuclear power plants for remote regions

  16. Integrated approach to optimize operation and maintenance costs for operating nuclear power plants

    International Nuclear Information System (INIS)

    2006-06-01

    In the context of increasingly open electricity markets and the 'unbundling' of generating companies from former utility monopolies, an area of major concern is the economic performance of the existing fleet of nuclear power plants. Nuclear power, inevitably, must compete directly with other electricity generation sources. Coping with this competitive pressure is a challenge that the nuclear industry should meet if the nuclear option is to remain a viable one. This competitive environment has significant implications for nuclear plant operations, including, among others, the need for the more cost effective management of plant activities, and the greater use of analytical tools to balance the costs and benefits of proposed activities, in order to optimize operation and maintenance costs, and thus insure the economic competitiveness of existing nuclear power plants. In the framework of the activities on Nuclear Economic Performance Information System (NEPIS), the IAEA embarked in developing guidance on optimization of operation and maintenance costs for nuclear power plants. The report was prepared building on the fundamental that optimization of operation and maintenance costs of a nuclear power plant is a key component of a broader integrated business strategic planning process, having as overall result achievement of organization's business objectives. It provides advice on optimization of O and M costs in the framework of strategic business planning, with additional details on operational planning and controlling. This TECDOC was elaborated in 2004-2005 in the framework of the IAEA's programme on Nuclear Power Plant Operating Performance and Life Cycle Management, with the support of two consultants meetings and one technical meeting and based on contributions provided by participants. It can serve as a useful reference for the management and operation staff within utilities, nuclear power plant operators and regulators and other organizations involved in

  17. FRESCO, a simplified code for cost analysis of fusion power plants

    International Nuclear Information System (INIS)

    Bustreo, C.; Casini, G.; Zollino, G.; Bolzonella, T.; Piovan, R.

    2013-01-01

    Highlights: • FRESCO is a code for rapid evaluation of the cost of electricity of a fusion power plant. • Parameters of the basic machine and unitary costs of components derived from ITER. • Power production components and plant power balance are extrapolated from PPCS. • A special effort is made in the investigation of the pulsed operation scenarios. • Technical and economical FRESCO results are compared with those of two PPCS models. -- Abstract: FRESCO (Fusion REactor Simplified COsts) is a code based on simplified models of physics, engineering and economical aspects of a TOKAMAK-like pulsed or steady-state fusion power plant. The experience coming from various aspects of ITER design, including selection of materials and operating scenarios, is exploited as much as possible. Energy production and plant power balance, including the recirculation requirements, are derived from two models of the PPCS European study, the helium cooled lithium/lead blanket model reactor (model AB) and the helium cooled ceramic one (model B). A detailed study of the availability of the power plant due, among others, to the replacement of plasma facing components, is also included in the code. The economics of the fusion power plant is evaluated through the levelized cost approach. Costs of the basic components are scaled from the corresponding values of the ITER project, the ARIES studies and SCAN model. The costs of plant auxiliaries, including those of the magnetic and electric systems, tritium plants, instrumentation, buildings and thermal energy storage if any, are recovered from ITER values and from those of other power plants. Finally, the PPCS models AB and B are simulated and the main results are reported in this paper

  18. Reducing Customers’ Total Cost of Ownership Within a Software Supply Network

    NARCIS (Netherlands)

    Slinger, S.R.L.; Rijsemus, W.

    2006-01-01

    This paper describes how the company Cordys avoids the ERP problems from the last 15 years by improving the software release, delivery, deployment, and maintenance processes. These ERP problems, such as costly ERP migrations and highly complex maintenance procedures, are circumvented by the

  19. RANKED SET SAMPLING FOR ECOLOGICAL RESEARCH: ACCOUNTING FOR THE TOTAL COSTS OF SAMPLING

    Science.gov (United States)

    Researchers aim to design environmental studies that optimize precision and allow for generalization of results, while keeping the costs of associated field and laboratory work at a reasonable level. Ranked set sampling is one method to potentially increase precision and reduce ...

  20. Total and Marginal Cost Analysis for a High School Based Bystander Intervention

    Science.gov (United States)

    Bush, Joshua L.; Bush, Heather M.; Coker, Ann L.; Brancato, Candace J.; Clear, Emily R.; Recktenwald, Eileen A.

    2018-01-01

    Costs of providing the Green Dot bystander-based intervention, shown to be effective in the reduction of sexual violence among Kentucky high school students, were estimated based on data from a large cluster-randomized clinical trial. Rape Crisis Center Educators were trained to provide Green Dot curriculum to students. Implementing Green Dot in…

  1. Functional and oncologic outcomes after excision of the total femur in primary bone tumors: Results with a low cost total femur prosthesis

    Directory of Open Access Journals (Sweden)

    Ajay Puri

    2012-01-01

    Full Text Available Background: The extent of tumor may necessitate resection of the complete femur rarely to achieve adequate oncologic clearance in bone sarcomas. We present our experience with reconstruction in such cases using an indigenously manufactured, low-cost, total femoral prosthesis (TFP. We assessed the complications of the procedure, the oncologic and functional outcomes, and implant survival. Materials and Methods: Eight patients (four males and four females with a mean age of 32 years, operated between December 2003 and June 2009, had a TFP implanted. The diagnosis included osteogenic sarcoma (5, Ewing′s sarcoma (1, and chondrosarcoma (2. Mean followup was 33 months (9-72 months for all and 40 months (24-72 months in survivors. They were evaluated by Musculoskeletal Tumor Society score, implant survival as well as patient survival. Results: There was one local recurrence and five of seven patients are currently alive at the time of last followup. The Musculoskeletal Tumor Society score for patients ranged from 21 to 25 with a mean of 24 (80%. The implant survival was 88% at 5 years with only one TFP needing removal because of infection. Conclusions: A TFP in appropriately indicated patients with malignant bone tumors is oncologically safe. A locally manufactured, cost-effective implant provided consistent and predictable results after excision of the total femur with good functional outcomes.

  2. Sono-photo-degradation of carbamazepine in a thin falling film reactor: Operation costs in pilot plant.

    Science.gov (United States)

    Expósito, A J; Patterson, D A; Monteagudo, J M; Durán, A

    2017-01-01

    The photo-Fenton degradation of carbamazepine (CBZ) assisted with ultrasound radiation (US/UV/H 2 O 2 /Fe) was tested in a lab thin film reactor allowing high TOC removals (89% in 35min). The synergism between the UV process and the sonolytic one was quantified as 55.2%. To test the applicability of this reactor for industrial purposes, the sono-photo-degradation of CBZ was also tested in a thin film pilot plant reactor and compared with a 28L UV-C conventional pilot plant and with a solar Collector Parabolic Compound (CPC). At a pilot plant scale, a US/UV/H 2 O 2 /Fe process reaching 60% of mineralization would cost 2.1 and 3.8€/m 3 for the conventional and thin film plant respectively. The use of ultrasound (US) produces an extra generation of hydroxyl radicals, thus increasing the mineralization rate. In the solar process, electric consumption accounts for a maximum of 33% of total costs. Thus, for a TOC removal of 80%, the cost of this treatment is about 1.36€/m 3 . However, the efficiency of the solar installation decreases in cloudy days and cannot be used during night, so that a limited flow rate can be treated. Copyright © 2016 Elsevier B.V. All rights reserved.

  3. Total direct cost, length of hospital stay, institutional discharges and their determinants from rehabilitation settings in stroke patients.

    Science.gov (United States)

    Saxena, S K; Ng, T P; Yong, D; Fong, N P; Gerald, K

    2006-11-01

    Length of hospital stay (LOHS) is the largest determinant of direct cost for stroke care. Institutional discharges (acute care and nursing homes) from rehabilitation settings add to the direct cost. It is important to identify potentially preventable medical and non-medical reasons determining LOHS and institutional discharges to reduce the direct cost of stroke care. The aim of the study was to ascertain the total direct cost, LOHS, frequency of institutional discharges and their determinants from rehabilitation settings. Observational study was conducted on 200 stroke patients in two rehabilitation settings. The patients were examined for various socio-demographic, neurological and clinical variables upon admission to the rehabilitation hospitals. Information on total direct cost and medical complications during hospitalization were also recorded. The outcome variables measured were total direct cost, LOHS and discharges to institutions (acute care and nursing home facility) and their determinants. The mean and median LOHS in our study were 34 days (SD = 18) and 32 days respectively. LOHS and the cost of hospital stay were significantly correlated. The significant variables associated with LOHS on multiple linear regression analysis were: (i) severe functional impairment/functional dependence Barthel Index institutional discharges (22 to acute care and 17 to nursing homes). On multivariate analysis the significant predictors of discharges to institutions from rehabilitation hospitals were medical complications (OR = 4.37; 95% CI 1.01-12.53) and severe functional impairment/functional dependence. (OR = 5.90, 95% CI 2.32-14.98). Length of hospital stay and discharges to institutions from rehabilitation settings are significantly determined by medical complications. Importance of adhering to clinical pathway/protocol for stroke care is further discussed.

  4. Cost of post-operative intravenous iron therapy in total lower limb arthroplasty: a retrospective, matched cohort study

    Science.gov (United States)

    Muñoz, Manuel; Gómez-Ramírez, Susana; Martín-Montañez, Elisa; Naveira, Enrique; Seara, Javier; Pavía, José

    2014-01-01

    Background Requirements for allogeneic red cell transfusion after total lower limb arthroplasty are still high (20–50%), and post-operative intravenous iron has been shown to reduce transfusion requirements for this surgery. We performed a cost analysis to ascertain whether this alternative is also likely to be cost-effective. Materials and methods Data from 182 matched-pairs of total lower limb arthroplasty patients, managed with a restrictive transfusion protocol and without (control group) or with post-operative intravenous iron (iron group), were retrospectively reviewed. Acquisition and administration costs of iron (iron sucrose or ferric carboxymaltose) and allogeneic red cell concentrates, haemoglobin measurements, and prolonged stay in hospital were used for blood management cost analysis. Results Patients in the iron group received 600 mg intravenous iron, without clinically relevant incidents, and had a lower allogeneic transfusion rate (11.5% vs 26.4% for the iron and control groups, respectively; p=0.001). The reduction in transfusion rate was more pronounced in anaemic patients (17% vs 40%; p=0.015) than in non-anaemic ones (9.6% vs 21.2%; p=0.011). There were no differences with respect to post-operative infection rate. Patients receiving allogeneic transfusion stayed in hospital longer (+1.9 days [95% CI: 1.2–2.6]). As intravenous iron reduces the allogeneic transfusion rate, both iron formulations were cost-neutral in the different cost scenarios (−25.5 to 62.1 €/patient for iron sucrose, and −51.1 to 64.4 €/patient for ferric carboxymaltose). Discussion In patients presenting with or without pre-operative anaemia, post-operative intravenous iron after total lower limb arthroplasty seems to be safe and is associated with reduced transfusion rates, without incremental costs. For anaemic patients, its efficacy could be increased by associating some other blood-saving method. PMID:24120595

  5. Deep water tie-back economics capex vs opex and the total costs

    Energy Technology Data Exchange (ETDEWEB)

    Tarlton, Oran D. [Oil States Industries Inc., Arlington, TX (United States)

    2005-07-01

    This paper explores the real cost and time benefits associated with the current, past, and future contracting strategies associated with subsea developments. It looks at the real cost associated with out sourcing engineering development and the impact of engineering, procurement, installation, and construction (EPIC) contracts. Development costs are first and foremost in the minds of operators as a field is analyzed for development potential. The cycle starts with an analysis of the geological information to estimate the potential value in the field. It proceeds to conceptual design where the first development methodology and cost estimates are prepared. If the project is initially viable it will proceed from conceptual design to Front End Engineering and Design (FEED) where a complete development plan is prepared with possible options and recommendations. Engineering companies may as a part of the FEED prepare a Request for Quotation (RFQ) which is sent to potential suppliers. As part of a FEED contract, an engineering company may also review responses to the RFQ and provide recommendations for selected suppliers. Typically large subsea projects are divided into several major categories such as: topsides; subsea production systems; wells; subsea umbilical risers and glow lines (SURF), and commissioning in order to simplify management and procurement. Many times these contracts are awarded as EPIC contracts to further simplify management and internal procurement efforts. A case study is presented which challenges current contracting strategies and presents an option for a lower cost and a better way forward with respect to the short term and a focus on the long term. (author)

  6. Total cost of ownership of CHP SOFC systems: Effect of installation context

    International Nuclear Information System (INIS)

    Arduino, Francesco; Santarelli, Massimo

    2016-01-01

    Solid oxide fuel cells (SOFC) are one of the most interesting between the emerging technologies for energy production. Although some information about the production cost of these devices are already known, their operational cost has not been studied yet with sufficient accuracy. This paper presents a life cycle cost (LCC) analysis of CHP (combined heat and power) SOFC systems performed in hospitals located in various cities of the US and one in Italy. In this study the strong effects of the installation context will be analyzed using a customized use phase model for each location. The cost effectiveness of these devices has been proved without credits in Mondovi (IT), New York (NY) and Minneapolis (MN) where the payback time goes from 10 to 7 years. Considering the credits, it is possible to obtain economic feasibility also in Chicago (IL) and reduce the payback for other cities to values from 4 to 6 years. In other cities like Phoenix (AZ) and Houston (TX) the payback can’t be reached in any case. The life cycle impact assessment analysis has shown how, even in the cities with cleaner electricity grid, there is a reduction in the emissions of both greenhouse gases and pollutants. - Highlights: •Life cycle cost analysis has been performed for CHP SOFC systems. •The strong effects of the installation context have been analyzed. •Economic feasibility has been proven in new york, Minneapolis and Mondovi. •Economic feasibility can’t be reached in phoenix and Houston. •SOFC always provide a reduction in the emissions of greenhouse gases and pollutant.

  7. Increase plant safety and reduce cost by implementing risk-informed in-service inspection programs

    International Nuclear Information System (INIS)

    Billington, A.; Monette, P.

    2001-01-01

    The idea behind the program is that it is possible to 'inspect less, but inspect better'. In other words, the risk-informed In-Service Inspection (ISI) process is used to improve the effectiveness of examination of piping components, i.e. concentrate inspection resources and enhance inspection strategies on high safety significant locations, and reduce inspection requirements on others. The Westinghouse Owners Group (WOG) risk-informed ISI process has already been applied for full scope (Millstone 3, Surry 1) and limited scope (Beznau, Ringhals 4, Asco, Turkey Point 3). By examining the high safety significant piping segments for the different fluid piping systems, the total piping core damage frequency is reduced. In addition, more than 80% of the risk associated with potential pressure boundary failures is addressed with the WOG risk-informed ISI process, while typically less that 50% of this same risk is addressed by the current inspection programs. The risk-informed ISI processes are used to improve the effectiveness of inspecting safety-significant piping components, to reduce inspection requirements on other piping components, to evaluate improvements to plant availability and enhanced safety measures, including reduction of personnel radiation exposure, and to reduce overall Operation and Maintenance (O and M) costs while maintaining regulatory compliance. A description of the process as well as benefits from past projects is presented, since the methodology is applicable for WWER plant design. (author)

  8. Increase plant safety and reduce cost by implementing risk-informed In-Service Inspection programs

    International Nuclear Information System (INIS)

    Billington, A.; Monette, P.; Doumont, C.

    2000-01-01

    The idea behind the program is that it is possible to 'inspect less, but inspect better'. In other words, the risk-informed In-Service Inspection (ISI) process is used to improve the effectiveness of examination of piping components, i.e. concentrate inspection resources and enhance inspection strategies on high safety significant locations, and reduce inspection requirements on others. The Westinghouse Owners Group (WOG) risk-informed ISI process has already been applied for full scope (Millstone 3, Surry 1) and limited scope (Beznau, Ringhals 4, Asco, Turkey Point 3). By examining the high safety significant piping segments for the different fluid piping systems, the total piping core damage frequency is reduced. In addition, more than 80% of the risk associated with potential pressure boundary failures is addressed with the WOG risk-informed ISI process, while typically less than 50% of this same risk is addressed by the current inspection programs. The risk-informed ISI processes are used: to improve the effectiveness of inspecting safety-significant piping components; to reduce inspection requirements on other piping components; to evaluate improvements to plant availability and enhanced safety measures, including reduction of personnel radiation exposure; and to reduce overall Operation and Maintenance (O and M) costs while maintaining regulatory compliance. A description of the process as well as benefits of past projects is presented, since the methodology is applicable for VVER plant design. (author)

  9. The capital investment and electricity cost of 2 x 600 MW PWR nuclear power plant in China

    International Nuclear Information System (INIS)

    Li Zhihua; Xing Leiming

    1990-01-01

    The capital investment and electricity cost of 2 x 600 MW PWR nuclear power plant in China are studied. If the rate of interest R 1 and of escalation R 2 are 7.2% and 10.0% respectively for RMB and the rate of interest R 1 and of escalation R 2 are 6.5% and 2.0% respectively for MK, the total investment is 9270 M RMB Yuan, the Specific investment is 7320 RMB Yuan/kW, the average selling electricity cost is 0.16 RMB Yuan/(kW·h). If the selling electricity price is 0.24 RMB Yuan/(kW·h), the rate of inner return is 7.7%, the dynamic return period is 13 years, the national income is 15800 M RMB Yuan, the profit of nuclear power plant after taxation is 6800 M RMB Yuan

  10. Maintenance of the Photovolatic Plants Using UAV Equipped with Low-cost GNSS RTK Receiver

    DEFF Research Database (Denmark)

    Bilal, Muhammad; Prasad, Ramjee; Nisi, Marco

    2017-01-01

    of low-cost GNSS RTK receiver, is the maintenance of photovoltaic (PV) plants using Unmanned Aerial Vehicle (UAV). This paper proposes a solution that aims at automating the maintenance of PV plant with enhanced reliability in a time and cost effective manner, which otherwise requires intermediate human...... intervention. The paper presents the architectural concept, system design, and end-to-end algorithm that plays a pivotal role in enabling the automatic report generation of PV plant status. Preliminary results of the proof-of-concept shows the feasibility of the proposed solution....

  11. A reactor-level analysis of busbar costs for US nuclear plants, 1970-2005

    International Nuclear Information System (INIS)

    Koomey, Jonathan; Hultman, Nathan E.

    2007-01-01

    We present a reactor-by-reactor analysis of historical busbar costs for 99 nuclear reactors in the United States, and compare those costs with recent projections for next-generation US reactors. We argue that cost projections far different from median historical costs require more justification than estimates that lie close to those medians. Our analysis suggests that some recent projections of capital costs, construction duration, and total operations and maintenance costs are quite low-far enough from the historical medians that additional scrutiny may be required to justify using such estimates in current policy discussions and planning

  12. Total cost of ownership of electric vehicles compared to conventional vehicles: A probabilistic analysis and projection across market segments

    International Nuclear Information System (INIS)

    Wu, Geng; Inderbitzin, Alessandro; Bening, Catharina

    2015-01-01

    While electric vehicles (EV) can perform better than conventional vehicles from an environmental standpoint, consumers perceive them to be more expensive due to their higher capital cost. Recent studies calculated the total cost of ownership (TCO) to evaluate the complete cost for the consumer, focusing on individual vehicle classes, powertrain technologies, or use cases. To provide a comprehensive overview, we built a probabilistic simulation model broad enough to capture most of a national market. Our findings indicate that the comparative cost efficiency of EV increases with the consumer's driving distance and is higher for small than for large vehicles. However, our sensitivity analysis shows that the exact TCO is subject to the development of vehicle and operating costs and thus uncertain. Although the TCO of electric vehicles may become close to or even lower than that of conventional vehicles by 2025, our findings add evidence to past studies showing that the TCO does not reflect how consumers make their purchase decision today. Based on these findings, we discuss policy measures that educate consumers about the TCO of different vehicle types based on their individual preferences. In addition, measures improving the charging infrastructure and further decreasing battery cost are discussed. - Highlights: • Calculates the total cost of ownership across competing vehicle technologies. • Uses Monte Carlo simulation to analyse distributions and probabilities of outcomes. • Contains a comprehensive assessment across the main vehicle classes and use cases. • Indicates that cost efficiency of technology depends on vehicle class and use case. • Derives specific policy measures to facilitate electric vehicle diffusion

  13. Impact of digital information and control system platform selection on nuclear power generating plant operating costs

    International Nuclear Information System (INIS)

    Bogard, T.; Radomski, S.; Sterdis, B.; Marta, H.; Bond, V.; Richardson, J.; Ramon, G.; Edvinsson, H.

    1998-01-01

    Information is presented on the benefits of a well-planned information and control systems (I and CS) replacement approach for aging nuclear power generating plants' I and CS. Replacement of an aging I and CS is accompanied by increases in plant profitability. Implementing a structured I and CS replacement with current technology allows improved plant electrical production in parallel with reduced I and CS operations and maintenance cost. Qualitative, quantitative, and enterprise management methods for cost benefit justification are shown to justify a comprehensive approach to I and CS replacement. In addition to the advantages of standard I and CS technologies, examples of new I and CS technologies are shown to add substantial cost benefit justification for I and CS replacements. Focus is upon I and CS replacements at nuclear power plants, however the information is applicable to other types of power generating facilities. (author)

  14. YAEC's view of the cause and control of escalating nuclear plant O and M costs

    International Nuclear Information System (INIS)

    Haseltine, J.D.; Lessard, L.P.

    1990-01-01

    This paper provides insights on this issue in terms of both the genesis and effective long-term control of O and M costs. Yankee Atomic Electric Company's (YAEC's) insights stem not only from an analysis of certain industry data, but also from its unique position within the nuclear industry in terms of its age, plant size, and organization. First, at 30 yr of age, the YAEC plant has endured the full swing of the regulatory/institutional pendulum and the associated impact on O and M costs. Second, with a size of only 185 MW(electric), YAEC's imperative since start-up has been the strict control of O and M costs while still achieving operational excellence. Finally, YAEC is an organization strictly focused on nuclear power operations and has not been distracted by fossil plant operations or other utility requirements like distribution, retail sales, etc., that may have plagued other plant operators

  15. Construction costs, payback times, and the leaf economics of carnivorous plants.

    Science.gov (United States)

    Karagatzides, Jim D; Ellison, Aaron M

    2009-09-01

    Understanding how different plant species and functional types "invest" carbon and nutrients is a major goal of plant ecologists. Two measures of such investments are "construction costs" (carbon needed to produce each gram of tissue) and associated "payback times" for photosynthesis to recover construction costs. These measurements integrate among traits used to assess leaf-trait scaling relationships. Carnivorous plants are model systems for examining mechanisms of leaf-trait coordination, but no studies have measured simultaneously construction costs of carnivorous traps and their photosynthetic rates to determine payback times of traps. We measured mass-based construction costs (CC(mass)) and photosynthesis (A(mass)) for traps, leaves, roots, and rhizomes of 15 carnivorous plant species grown under greenhouse conditions. There were highly significant differences among species in CC(mass) for each structure. Mean CC(mass) of carnivorous traps (1.14 ± 0.24 g glucose/g dry mass) was significantly lower than CC(mass) of leaves of 267 noncarnivorous plant species (1.47 ± 0.17), but all carnivorous plants examined had very low A(mass) and thus, long payback times (495-1551 h). Our results provide the first clear estimates of the marginal benefits of botanical carnivory and place carnivorous plants at the "slow and tough" end of the universal spectrum of leaf traits.

  16. Ranking periodic ordering models on the basis of minimizing total inventory cost

    Directory of Open Access Journals (Sweden)

    Mohammadali Keramati

    2015-06-01

    Full Text Available This paper aims to provide proper policies for inventory under uncertain conditions by comparing different inventory policies. To review the efficiency of these algorithms it is necessary to specify the area in which each of them is applied. Therefore, each of the models has been reviewed under different forms of retailing and they are ranked in terms of their expenses. According to the high values of inventories and their impacts on the costs of the companies, the ranking of various models using the simulation annealing algorithm are presented, which indicates that the proposed model of this paper could perform better than other alternative ones. The results also indicate that the suggested algorithm could save from 4 to 29 percent on costs of inventories.

  17. Implementation of Distance Support (DS) to Reduce Total Ownership Cost (R-TOC)

    Science.gov (United States)

    2012-02-01

    Policy of 22 Mar 2007, states that DS combines people, processes and technology into a collaborative infrastructure regardless of geographic location...Tech Assist Data for Submarine Enterprise 120 FTA Events Performed 164 MH Via On-Si te Support Average Cost Per Event (Based on $60.00 Per Hour...CFFC/Command Policy) 16% Success Rate Overa l l On Al l FTA Events 37% Success Rate On Out-Of-Area Events Average MHs Per Event 19 MH Via DS

  18. Efficiency and Cost Analysis of Cell Saver Auto Transfusion System in Total Knee Arthroplasty

    OpenAIRE

    Mustafa Gökhan Bilgili; Ersin Erçin; Cemal Kural; Altuğ Duramaz; Cevdet Avkan; Gökhan Peker; Serdar Hakan Başaran

    2014-01-01

    Background: Blood loss and replacement is still a controversial issue in major orthopaedic surgery. Allogenic blood transfusion may cause legal problems and concerns regarding the transmission of transfusion-related diseases. Cellsaver Systems (CSS) were developed as an alternative to allogenic transfusion but CSS transfusion may cause coagulation, infection and haemodynamic instability. Aims: Our aim was to analyse the efficiency and cost analysis of a cell saver auto-transfusion system ...

  19. The total release of xenon-133 from the Fukushima Dai-ichi nuclear power plant accident

    International Nuclear Information System (INIS)

    Stohl, Andreas; Seibert, Petra; Wotawa, Gerhard

    2012-01-01

    The accident at the Fukushima Dai-ichi nuclear power plant (FD-NPP) on 11 March 2011 released large amounts of radioactivity into the atmosphere. We determine the total emission of the noble gas xenon-133 ( 133 Xe) using global atmospheric concentration measurements. For estimating the emissions, we used three different methods: (i) using a purely observation-based multi-box model, (ii) comparisons of dispersion model results driven with GFS meteorological data with the observation data, and (iii) such comparisons with the dispersion model driven by ECMWF data. From these three methods, we have obtained total 133 Xe releases from FD-NPP of (i) 16.7 ± 1.9 EBq, (ii) 14.2 ± 0.8 EBq, and (iii) 19.0 ± 3.4 EBq, respectively. These values are substantially larger than the entire 133 Xe inventory of FD-NPP of about 12.2 EBq derived from calculations of nuclear fuel burn-up. Complete release of the entire 133 Xe inventory of FD-NPP and additional release of 133 Xe due to the decay of iodine-133 ( 133 I), which can add another 2 EBq to the 133 Xe FD-NPP inventory, is required to explain the atmospheric observations. Two of our three methods indicate even higher emissions, but this may not be a robust finding given the differences between our estimates. - Highlights: ► We determine the total release of xenon-133 from the Fukushima nuclear accident. ► We used global measurements and a box model, as well as dispersion model estimates. ► Total 133 Xe release is about 14.2-19 EBq, more than Fukushima 133 Xe inventory. ► Additional release of iodine-133 and decay into 133 Xe needed to explain results.

  20. Sensitive Electrochemical Determination of Gallic Acid: Application in Estimation of Total Polyphenols in Plant Samples

    Directory of Open Access Journals (Sweden)

    Mohammad Ali Sheikh-Mohseni

    2016-12-01

    Full Text Available A modified electrode was prepared by modification of the carbon paste electrode (CPE with graphene nano-sheets. The fabricated modified electrode exhibited an electrocatalytic activity toward gallic acid (GA oxidation because of good conductivity, low electron transfer resistance and catalytic effect. The graphene modified CPE had a lower overvoltage and enhanced electrical current respect to the bare CPE for the oxidation of GA. The oxidation potential of GA decreased more than 210 mV by the modified electrode. The modified electrode responded to the GA in the concentration range of 3.0 × 10-5-1.5 × 10-4 M with high sensitivity by the technique of differential pulse voltammetry. Also, detection limit of 1.1 × 10-7 M was obtained by this modified electrode for GA. This electrode was used for the successful determination of GA in plant samples. Therefore, the content of total polyphenols in plant samples can be determined by the proposed modified electrode based on the concentration of GA in the sample.

  1. The importance of ecological costs for the evolution of plant defense against herbivory.

    Science.gov (United States)

    van Velzen, Ellen; Etienne, Rampal S

    2015-05-07

    Plant defense against herbivory comes at a cost, which can be either direct (reducing resources available for growth and reproduction) or indirect (through reducing ecological performance, for example intraspecific competitiveness). While direct costs have been well studied in theoretical models, ecological costs have received almost no attention. In this study we compare models with a direct trade-off (reduced growth rate) to models with an ecological trade-off (reduced competitive ability), using a combination of adaptive dynamics and simulations. In addition, we study the dependence of the level of defense that can evolve on the type of defense (directly by reducing consumption, or indirectly by inducing herbivore mortality (toxicity)), and on the type of herbivore against which the plant is defending itself (generalists or specialists). We find three major results: First, for both direct and ecological costs, defense only evolves if the benefit to the plant is direct (through reducing consumption). Second, the type of cost has a major effect on the evolutionary dynamics: direct costs always lead to a single optimal strategy against herbivores, but ecological costs can lead to branching and the coexistence of non-defending and defending plants; however, coexistence is only possible when defending against generalist herbivores. Finally, we find that fast-growing plants invest less than slow-growing plants when defending against generalist herbivores, as predicted by the Resource Availability Hypothesis, but invest more than slow-growing plants when defending against specialists. Our results clearly show that assumptions about ecological interactions are crucial for understanding the evolution of defense against herbivores. Copyright © 2015 Elsevier Ltd. All rights reserved.

  2. Canadian nuclear power plant construction cost forecast and analysis

    International Nuclear Information System (INIS)

    Keng, C.W.K.

    1985-01-01

    Because of the huge volume of capital required to construct a modern electric power generating station, investment decisions have to be made with as complete an understanding of the consequence of the decision as possible. This understanding must be provided by the evaluation of the situation to take place in the future. This paper attempts to use an econometric method to forecast the construction costs escalation of a standard Canadian nuclear generating station (NGS). A review of the history of Canadian nuclear electric power is provided. The major components of the construction costs of a Canadian NGS are studied and summarized. A data base is built and indexes are prepared. Based on these indexes an econometric forecasting model is constructed using an apparently new econometric methodology of forecasting modelling. Forecasts for a period of forty years are generated and applications of alternative scenario forecasts and range forecasts to uncertainty assessment are demonstrated. The indexes, the model, and the forecasts and their applications, to the best of the author's knowledge, are the very first ever done for Canadian NGS constructions

  3. Cost-utility analysis comparing radioactive iodine, anti-thyroid drugs and total thyroidectomy for primary treatment of Graves' disease.

    Science.gov (United States)

    Donovan, Peter J; McLeod, Donald S A; Little, Richard; Gordon, Louisa

    2016-12-01

    Little data is in existence about the most cost-effective primary treatment for Graves' disease. We performed a cost-utility analysis comparing radioactive iodine (RAI), anti-thyroid drugs (ATD) and total thyroidectomy (TT) as first-line therapy for Graves' disease in England and Australia. We used a Markov model to compare lifetime costs and benefits (quality-adjusted life-years (QALYs)). The model included efficacy, rates of relapse and major complications associated with each treatment, and alternative second-line therapies. Model parameters were obtained from published literature. One-way sensitivity analyses were conducted. Costs were presented in 2015£ or Australian Dollars (AUD). RAI was the least expensive therapy in both England (£5425; QALYs 34.73) and Australia (AUD5601; 30.97 QALYs). In base case results, in both countries, ATD was a cost-effective alternative to RAI (£16 866; 35.17 QALYs; incremental cost-effectiveness ratio (ICER) £26 279 per QALY gained England; AUD8924; 31.37 QALYs; ICER AUD9687 per QALY gained Australia), while RAI dominated TT (£7115; QALYs 33.93 England; AUD15 668; 30.25 QALYs Australia). In sensitivity analysis, base case results were stable to changes in most cost, transition probabilities and health-relative quality-of-life (HRQoL) weights; however, in England, the results were sensitive to changes in the HRQoL weights of hypothyroidism and euthyroidism on ATD. In this analysis, RAI is the least expensive choice for first-line treatment strategy for Graves' disease. In England and Australia, ATD is likely to be a cost-effective alternative, while TT is unlikely to be cost-effective. Further research into HRQoL in Graves' disease could improve the quality of future studies. © 2016 European Society of Endocrinology.

  4. Acetone enhances the direct analysis of total condensed tannins in plant tissues by the butanol-HCl-iron assay

    Science.gov (United States)

    The butanol-HCl spectrophotometric assay is widely used to quantify extractable and insoluble forms of condensed tannin (CT, syn. proanthocyanidin) in foods, feeds, and foliage of herbaceous and woody plants. However, this method underestimates total CT content when applied directly to plant materia...

  5. Parabolic Trough Reference Plant for Cost Modeling with the Solar Advisor Model (SAM)

    Energy Technology Data Exchange (ETDEWEB)

    Turchi, C.

    2010-07-01

    This report describes a component-based cost model developed for parabolic trough solar power plants. The cost model was developed by the National Renewable Energy Laboratory (NREL), assisted by WorleyParsons Group Inc., for use with NREL's Solar Advisor Model (SAM). This report includes an overview and explanation of the model, two summary contract reports from WorleyParsons, and an Excel spreadsheet for use with SAM. The cost study uses a reference plant with a 100-MWe capacity and six hours of thermal energy storage. Wet-cooling and dry-cooling configurations are considered. The spreadsheet includes capital and operating cost by component to allow users to estimate the impact of changes in component costs.

  6. RO-75, Reverse Osmosis Plant Design Optimization and Cost Optimization

    International Nuclear Information System (INIS)

    Glueckstern, P.; Reed, S.A.; Wilson, J.V.

    1999-01-01

    1 - Description of problem or function: RO75 is a program for the optimization of the design and economics of one- or two-stage seawater reverse osmosis plants. 2 - Method of solution: RO75 evaluates the performance of the applied membrane module (productivity and salt rejection) at assumed operating conditions. These conditions include the site parameters - seawater salinity and temperature, the membrane module operating parameters - pressure and product recovery, and the membrane module predicted long-term performance parameters - lifetime and long flux decline. RO75 calculates the number of first and second stage (if applied) membrane modules needed to obtain the required product capacity and quality and evaluates the required pumping units and the power recovery turbine (if applied). 3 - Restrictions on the complexity of the problem: The program does not optimize or design the membrane properties and the internal structure and flow characteristics of the membrane modules; it assumes operating characteristics defined by the membrane manufacturers

  7. Good practices for cost effective maintenance of nuclear power plants

    International Nuclear Information System (INIS)

    1997-02-01

    This publication is organized around five areas that were identified by the utilities and government organizations who contributed to this report as most important to them. They are: Increasing production through maintenance activities related to improved plant material condition, reduced duration of planned outages, use of on-line maintenance and reduced frequency of forced outages; reducing workload through avoiding unnecessary regulatory burden and using reliability centered maintenance and condition monitoring; improving maintenance processes through better planning and scheduling, use of information management systems, graduated work controls, and appropriate post-maintenance testing; improving productivity through better teamwork, greater sharing of resources, and better radiation management associated with maintenance; measuring performance of maintenance activities through such tools as performance measures and benchmarking. Figs, tabs

  8. Standardization of PWR power plants: Impact of capital investment cost

    International Nuclear Information System (INIS)

    Vincent, C.

    1991-01-01

    The French program is certainly specific to the French context but it is a large and a real experiment of standardized series of units from which we can abstract the main ideas and ranges available in different contexts. It was estimated that the standardized part could reach more than 60% of the capital cost and this percentage does not take into account a regionalized part which also could have been standardized. The main condition is a large program which could be issued from a country or a partnership between different countries. That means, common terms of reference, lists of standardized equipment, same design documents. With a levelized rhythm of erection, beneficial effects of the series could be expected. The scale effect is fairly well known, also we can wonder for instance about the choice between five units of 600 MW and three units of 1000 MW. The answer is depending on the number of units and on the discount rate. (author)

  9. Cost-Effectiveness Analysis of Total Hip Arthroplasty Performed by a Canadian Short-Stay Surgical Team in Ecuador.

    Science.gov (United States)

    Schlegelmilch, Michael; Rashiq, Saifee; Moreau, Barbara; Jarrín, Patricia; Tran, Bach; Chuck, Anderson

    2017-01-01

    Few charitable overseas surgical missions produce cost-effectiveness analyses of their work. We compared the pre- and postoperative health status for 157 total hip arthroplasty (THA) patients operated on from 2007 to 2011 attended by an annual Canadian orthopedic mission to Ecuador to determine the quality-adjusted life years (QALYs) gained. The costs of each mission are known. The cost per surgery was divided by the average lifetime QALYs gained to estimate an incremental cost-effectiveness ratio (ICER) in Canadian dollars per QALY. The average lifetime QALYs (95% CI) gained were 1.46 (1.4-1.5), 2.5 (2.4-2.6), and 2.9 (2.7-3.1) for unilateral, bilateral, and staged (two THAs in different years) operations, respectively. The ICERs were $4,442 for unilateral, $2,939 for bilateral, and $4392 for staged procedures. Seventy percent of the mission budget was spent on the transport and accommodation of volunteers. THA by a Canadian short-stay surgical team was highly cost-effective, according to criteria from the National Institute for Health and Care Excellence and the World Health Organization. We encourage other international missions to provide similar cost-effectiveness data to enable better comparison between mission types and between mission and nonmission care.

  10. Energy Efficiency Improvement and Cost Saving Opportunities for the Glass Industry. An ENERGY STAR Guide for Energy and Plant Managers

    Energy Technology Data Exchange (ETDEWEB)

    Galitsky, Christina; Worrell, Ernst; Galitsky, Christina; Masanet, Eric; Graus, Wina

    2008-03-01

    The U.S. glass industry is comprised of four primary industry segments--flat glass, container glass, specialty glass, and fiberglass--which together consume $1.6 billion in energy annually. On average, energy costs in the U.S. glass industry account for around 14 percent of total glass production costs. Energy efficiency improvement is an important way to reduce these costs and to increase predictable earnings, especially in times of high energy price volatility. There is a variety of opportunities available at individual plants in the U.S. glass industry to reduce energy consumption in a cost-effective manner. This Energy Guide discusses energy efficiency practices and energy-efficient technologies that can be implemented at the component, process, system, and organizational levels. A discussion of the trends, structure, and energy consumption characteristics of the U.S. glass industry is provided along with a description of the major process steps in glass manufacturing. Expected savings in energy and energy-related costs are given for many energy efficiency measures, based on case study data from real-world applications in glass production facilities and related industries worldwide. Typical measure payback periods and references to further information in the technical literature are also provided, when available. The information in this Energy Guide is intended to help energy and plant managers in the U.S. glass industry reduce energy consumption in a cost-effective manner while maintaining the quality of products manufactured. Further research on the economics of the measures--as well on as their applicability to different production practices--is needed to assess potential implementation of selected technologies at individual plants.

  11. Cost structure of coal- and nuclear-fired electric power plants

    International Nuclear Information System (INIS)

    Helmuth, J.A.

    1981-01-01

    This dissertation investigates the cost structure of coal and nuclear electric power generation. The emphasis of the paper is to empirically estimate the direct costs of generating base-load electric power at the plant level. Empirically, the paper first investigates the relative comparative costs of nuclear and coal power generation, based on historical operating data. Consideration of the learning curve and other dynamic elements is incorporated in the analysis. The second empirical thrust is to inestigate economies of scale for both technologies. The results from the empirical studies give an indication as to the future and present cost viability of each technology. Implications toward energy policy are discussed

  12. Determination of leveled costs of electric generation for gas plants, coal and nuclear

    International Nuclear Information System (INIS)

    Alonso V, G.; Palacios H, J.C.; Ramirez S, J.R.; Gomez, A.

    2005-01-01

    The present work analyzes the leveled costs of electric generation for different types of nuclear reactors known as Generation III, these costs are compared with the leveled costs of electric generation of plants with the help of natural gas and coal. In the study several discount rates were used to determine their impact in the initial investment. The obtained results are comparable with similar studies and they show that it has more than enough the base of the leveled cost the nuclear option it is quite competitive in Mexico. Also in this study it is also thinks about the economic viability of a new nuclear power station in Mexico. (Author)

  13. Are Public-Private Partnerships an Appropriate Governance Structure for Power Plants? A Transaction Cost Analysis

    Science.gov (United States)

    Ho, S. Ping; Hsu, Yaowen

    2015-04-01

    In order to meet the requirements of the rapid economic growth, many countries demand an increasing number of power plants to meet the increasing electricity usage. Since high capital requirements of power plants present a big issue for these countries, PPPs have been considered an alternative to provide power plant infrastructure. In particular, in emerging or developing countries, PPPs may be the fastest way to provide the infrastructure needed. However, while PPPs are a promising alternative to providing various types of infrastructure, many failed power plant PPP projects have made it evident that PPPs, under certain situations, can be very costly or even a wrong choice of governance structure. While the higher efficiency due to better pooling of resources is greatly emphasized in Public-Private Partnerships (PPPs), the embedded transaction inefficiencies are often understated or even ignored. Through the lens of Transaction Cost Economics (TCE), this paper aims to answer why and when PPPs may become a costly governance structure for power plants. Specifically, we develop a TCE-based theory of PPPs as a governance structure. This theory suggests that three major opportunism problems embedded in infrastructure PPPs are possible to cause substantial transaction costs and render PPPs a costly governance structure. The three main opportunism problems are principal-principal problem, firm's hold-up problem, and government-led hold-up problem. Moreover, project and institutional characteristics that may lead to opportunism problems are identified. Based on these characteristics, an opportunism-focused transaction cost analysis (OTCA) for PPPs as a governance structure is proposed to supplement the current practice of PPP feasibility analysis. As a part of theory development, a case study of PPP power plants is performed to evaluate the proposed theory and to illustrate how the proposed OTCA can be applied in practice. Policies and administration strategies for power

  14. Leveraging Real-World Evidence in Disease-Management Decision-Making with a Total Cost of Care Estimator.

    Science.gov (United States)

    Nguyen, Thanh-Nghia; Trocio, Jeffrey; Kowal, Stacey; Ferrufino, Cheryl P; Munakata, Julie; South, Dell

    2016-12-01

    Health management is becoming increasingly complex, given a range of care options and the need to balance costs and quality. The ability to measure and understand drivers of costs is critical for healthcare organizations to effectively manage their patient populations. Healthcare decision makers can leverage real-world evidence to explore the value of disease-management interventions in shifting total cost trends. To develop a real-world, evidence-based estimator that examines the impact of disease-management interventions on the total cost of care (TCoC) for a patient population with nonvalvular atrial fibrillation (NVAF). Data were collected from a patient-level real-world evidence data set that uses the IMS PharMetrics Health Plan Claims Database. Pharmacy and medical claims for patients meeting the inclusion or exclusion criteria were combined in longitudinal cohorts with a 180-day preindex and 360-day follow-up period. Descriptive statistics, such as mean and median patient costs and event rates, were derived from a real-world evidence analysis and were used to populate the base-case estimates within the TCoC estimator, an exploratory economic model that was designed to estimate the potential impact of several disease-management activities on the TCoC for a patient population with NVAF. Using Microsoft Excel, the estimator is designed to compare current direct costs of medical care to projected costs by varying assumptions on the impact of disease-management activities and applying the associated changes in cost trends to the affected populations. Disease-management levers are derived from literature-based concepts affecting costs along the NVAF disease continuum. The use of the estimator supports analyses across 4 US geographic regions, age, cost types, and care settings during 1 year. All patients included in the study were continuously enrolled in their health plan (within the IMS PharMetrics Health Plan Claims Database) between July 1, 2010, and June 30

  15. CO2 control technology effects on IGCC plant performance and cost

    International Nuclear Information System (INIS)

    Chen Chao; Rubin, Edward S.

    2009-01-01

    As part of the USDOE's Carbon Sequestration Program, an integrated modeling framework has been developed to evaluate the performance and cost of alternative carbon capture and storage (CCS) technologies for fossil-fueled power plants in the context of multi-pollutant control requirements. This paper uses the newly developed model of an integrated gasification combined cycle (IGCC) plant to analyze the effects of adding CCS to an IGCC system employing a GE quench gasifier with water gas shift reactors and a Selexol system for CO 2 capture. Parameters of interest include the effects on plant performance and cost of varying the CO 2 removal efficiency, the quality and cost of coal, and selected other factors affecting overall plant performance and cost. The stochastic simulation capability of the model is also used to illustrate the effect of uncertainties or variability in key process and cost parameters. The potential for advanced oxygen production and gas turbine technologies to reduce the cost and environmental impacts of IGCC with CCS is also analyzed

  16. U.S. Nuclear Power Plant Operating Cost and Experience Summaries

    International Nuclear Information System (INIS)

    Reid, RL

    2003-01-01

    The ''U.S. Nuclear Power Plant Operating Cost and Experience Summaries'' (NUREG/CR-6577, Supp. 2) report has been prepared to provide historical operating cost and experience information on U.S. commercial nuclear power plants during 2000-2001. Costs incurred after initial construction are characterized as annual production costs, which represent fuel and plant operating and maintenance expenses, and capital expenditures related to facility additions/modifications, which are included in the plant capital asset base. As discussed in the report, annual data for these two cost categories were obtained from publicly available reports and must be accepted as having different degrees of accuracy and completeness. Treatment of inconclusive and incomplete data is discussed. As an aid to understanding the fluctuations in the cost histories, operations summaries for each nuclear unit are provided. The intent of these summaries is to identify important operating events; refueling, major maintenance, and other significant outages; operating milestones; and significant licensing or enforcement actions. Information used in the summaries is condensed from operating reports submitted by the licensees, the Nuclear Regulatory Commission (NRC) database for enforcement actions, and outage reports

  17. Thermoeconomic cost analysis of CO_2 compression and purification unit in oxy-combustion power plants

    International Nuclear Information System (INIS)

    Jin, Bo; Zhao, Haibo; Zheng, Chuguang

    2015-01-01

    Highlights: • Thermoeconomic cost analysis for CO_2 compression and purification unit is conducted. • Exergy cost and thermoeconomic cost occur in flash separation and mixing processes. • Unit exergy costs for flash separator and multi-stream heat exchanger are identical. • Multi-stage CO_2 compressor contributes to the minimum unit exergy cost. • Thermoeconomic performance for optimized CPU is enhanced. - Abstract: High CO_2 purity products can be obtained from oxy-combustion power plants through CO_2 compression and purification unit (CPU) based on phase separation method. To identify cost formation process and potential energy savings for CPU, detailed thermoeconomic cost analysis based on structure theory of thermoeconomics is applied to an optimized CPU (with double flash separators). It is found that the largest unit exergy cost occurs in the first separation process while the multi-stage CO_2 compressor contributes to the minimum unit exergy cost. In two flash separation processes, unit exergy costs for the flash separator and multi-stream heat exchanger are identical but their unit thermoeconomic costs are different once monetary cost for each device is considered. For cost inefficiency occurring in CPU, it mainly derives from large exergy costs and thermoeconomic costs in the flash separation and mixing processes. When compared with an unoptimized CPU, thermoeconomic performance for the optimized CPU is enhanced and the maximum reduction of 5.18% for thermoeconomic cost is attained. To achieve cost effective operation, measures should be taken to improve operations of the flash separation and mixing processes.

  18. Impact of different national biomass policies on investment costs of biomass district heating plants. Final report

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2000-04-01

    The BIO-COST project - co-ordinated by E.V.A. - was funded by the European Commission's THERMIE Type B Programme. The objective of BIO-COST was to analyse the impact of national biomass policies on the investment costs of biomass district heating (DH) plants. The European comparison should help identifying measures to reduce investment costs for biomass DH plants and/or components down to a 'best practice' level. The investigation is based on the comparison of 20 biomass DH plants by country, with Denmark and Sweden having mainly high energy taxes as driver, while Austria and France rely mainly on subsidy systems. The results of BIO-COST show, that governmental policies can have a big impact especially on grid and buildings costs, effecting of course the overall costs of the plant enormously. Emission standards have their effects especially on the costs for technical equipment, however, this fact was not reflected in the BIO-COST data. The results do not show a clear advantage of either the energy tax approach or the subsidy approach: The French subsidy approach leads to fairly low cost levels compared to the Danish tax approach, while the Swedish tax approach seems to yield the lowest cost level. On the other hand the Austrian subsidy approach seems to intercrease investment costs. In principle both the tax as the subsidy approach can lead to the same effect: a project is calculated in such a way, that it just meets economic breakeven. This is typically the case when the project is not carried out by a private enterprise but by an operator aiming at enhanced public welfare (e.g. co-operative, municipality). In this case a subsidy model might yield more possibilities to encourage an economically efficient development, than a tax. Instead of giving subsidies as a fixed percentage of investments they could be adjusted to the actual needs of the project as proven by a standardised calculation. Of course this can create the incentive to expect higher

  19. Handbook for quick cost estimates. A method for developing quick approximate estimates of costs for generic actions for nuclear power plants

    International Nuclear Information System (INIS)

    Ball, J.R.

    1986-04-01

    This document is a supplement to a ''Handbook for Cost Estimating'' (NUREG/CR-3971) and provides specific guidance for developing ''quick'' approximate estimates of the cost of implementing generic regulatory requirements for nuclear power plants. A method is presented for relating the known construction costs for new nuclear power plants (as contained in the Energy Economic Data Base) to the cost of performing similar work, on a back-fit basis, at existing plants. Cost factors are presented to account for variations in such important cost areas as construction labor productivity, engineering and quality assurance, replacement energy, reworking of existing features, and regional variations in the cost of materials and labor. Other cost categories addressed in this handbook include those for changes in plant operating personnel and plant documents, licensee costs, NRC costs, and costs for other government agencies. Data sheets, worksheets, and appropriate cost algorithms are included to guide the user through preparation of rough estimates. A sample estimate is prepared using the method and the estimating tools provided

  20. Handbook for quick cost estimates. A method for developing quick approximate estimates of costs for generic actions for nuclear power plants

    Energy Technology Data Exchange (ETDEWEB)

    Ball, J.R.

    1986-04-01

    This document is a supplement to a ''Handbook for Cost Estimating'' (NUREG/CR-3971) and provides specific guidance for developing ''quick'' approximate estimates of the cost of implementing generic regulatory requirements for nuclear power plants. A method is presented for relating the known construction costs for new nuclear power plants (as contained in the Energy Economic Data Base) to the cost of performing similar work, on a back-fit basis, at existing plants. Cost factors are presented to account for variations in such important cost areas as construction labor productivity, engineering and quality assurance, replacement energy, reworking of existing features, and regional variations in the cost of materials and labor. Other cost categories addressed in this handbook include those for changes in plant operating personnel and plant documents, licensee costs, NRC costs, and costs for other government agencies. Data sheets, worksheets, and appropriate cost algorithms are included to guide the user through preparation of rough estimates. A sample estimate is prepared using the method and the estimating tools provided.

  1. Energy management for cost reduction in the production. TEEM - Total Energy Efficiency Management; Energiemanagement zur Kostensenkung in der Produktion. TEEM - Total Energy Efficiency Management

    Energy Technology Data Exchange (ETDEWEB)

    Westkaemper, Engelbert; Verl, Alexander (eds.)

    2009-07-01

    Within the workshop of the Fraunhofer Institute for Manufacturing Engineering and Automation IPA (Stuttgart, Federal Republic of Germany) at 6th October, 2009, in Stuttgart the following lectures were held: (1) Presentation of Fraunhofer Institute for Manufacturing Engineering and Automation IPA (Engelbert Westkaemper); (2) TEEM - Total Energy Efficiency Management - ''With energy management to an energy efficient production'' (Alexander Schloske); (3) DIN EN 16001 Introduction of an energy management system - utilization and advantages for companies (Sylvia Wahren); (4) Analysis of the energy efficiency with power flow - Support and implementation at factory planning and optimization of production (Klaus Erlach); (5) Total Energy Efficiency Management - Approaches at the company Kaercher in injection moulding for example (Axel Leschtar); (6) Modelling the embodied product energy (Shahin Rahimifard); (7) Acquisition of energy data in the production - Technologies and possibilities (Joachim Neher); (8) Active energy management by means of an ''energy control centre'' - Analysis of the real situation and upgrading measures in the production using coating plants as an example (Wolfgang Klein); (9) Visualisation and simulation of energy values in the digital factory (Carmen Constantinescu, Axel Bruns).

  2. Basic factors to forecast maintenance cost and failure processes for nuclear power plants

    International Nuclear Information System (INIS)

    Popova, Elmira; Yu, Wei; Kee, Ernie; Sun, Alice; Richards, Drew; Grantom, Rick

    2006-01-01

    Two types of maintenance interventions are usually administered at nuclear power plants: planned and corrective. The cost incurred includes the labor (manpower) cost, cost for new parts, or emergency order of expensive items. At the plant management level there is a budgeted amount of money to be spent every year for such operations. It is very important to have a good forecast for this cost since unexpected events can trigger it to a very high level. In this research we present a statistical factor model to forecast the maintenance cost for the incoming month. One of the factors is the expected number of unplanned (due to failure) maintenance interventions. We introduce a Bayesian model for the failure rate of the equipment, which is input to the cost forecasting model. The importance of equipment reliability and prediction in the commercial nuclear power plant is presented along with applicable governmental and industry organization requirements. A detailed statistical analysis is performed on a set of maintenance cost and failure data gathered at the South Texas Project Nuclear Operating Company (STPNOC) in Bay City, Texas, USA

  3. Process Improvement Project Using Tranexamic Acid Is Cost-Effective in Reducing Blood Loss and Transfusions After Total Hip and Total Knee Arthroplasty.

    Science.gov (United States)

    Demos, Harry A; Lin, Zilan X; Barfield, William R; Wilson, Sylvia H; Robertson, Dawn C; Pellegrini, Vincent D

    2017-08-01

    Tranexamic acid (TXA) has been associated with decreased blood loss and transfusion after total hip arthroplasty (THA) and total knee arthroplasty (TKA). The purpose of this study was to examine both transfusion utilization and the economic impact of a Process Improvement Project implementing TXA for THA and TKA. After standardization of TXA administration in THA and TKA patients, retrospective data were compared from 12 consecutive months before (group A, n = 336 procedures) and after (group B, n = 436 procedures) project initiation. TXA administration increased with project implementation (group A = 3.57%, group B = 86.01%) and was associated with reductions in perioperative hemoglobin decrement (20.2%), patients transfused (45%), and number of units transfused per patient (61.9%). Cost savings were notable per patient ($128) and annually program wide ($55,884) with the primary THA subgroup contributing the most to the savings. No increase in adverse effects was observed. Standardized administration of TXA is an effective and economically favorable blood-reduction strategy for patients undergoing elective THA or TKA. Although reduction in transfusions with TXA may be greater after TKA, the economic and clinical impact of transfusion reduction is more substantial in THA patients. Copyright © 2017 Elsevier Inc. All rights reserved.

  4. The System 80+ standard plant design reduces operations and maintenance costs

    International Nuclear Information System (INIS)

    Chari, D.R.; Robertson, J.E.

    1998-01-01

    To be cost-competitive, nuclear power plants must maximize plant availability and minimize operations and maintenance (O and M) costs. A plant whose design supports these goals will generate more power at less cost and thereby have a lower unit generating cost. The ABB Combustion Engineering Nuclear Systems (ABB-CE) System 80+ Standard Nuclear Power Plant, rated at 1400 megawatts electric (MWe), is designed for high availability at reduced cost. To demonstrate that the duration of refueling outages, the major contributor to plant unavailability, can be shortened, ABB-CE developed a detailed plan that shows a System 80+ plant can safely perform a refueling and maintenance outage in 18 days. This is a significant reduction from the average current U.S. plant outages of 45 days, and is possible due to a two-part outage strategy: use System 80+ advanced system design features and relaxed technical specification (TS) time limits to shift some maintenance from outages to operating periods: and, use System 80+ structural, system, and component features, such as the larger operating floor, permanent pool seal, integral reactor head area cable tray system and missile shield, and longer life reactor coolant pump seals, to reduce the scope and duration of outage maintenance activities. Plant staffing level is the major variable, or controllable contributor to operations costs. ABB-CE worked with the Institute of Nuclear Power Operations (INPO) to perform detailed staffing analyses that show a System 80+ plant can be operated reliably with 30 percent less staff than currently operating nuclear plants of similar size. Safety was not sacrificed when ABB-CE developed the System 80+ refueling outage plan and staffing level. The outage plan was developed utilizing a defense-in-depth concept for shutdown safety. The defense in-depth concept is implemented via systematic control of outage risk evaluation (SCORE) cards. The SCORE cards identify primary and alternate means of

  5. What is the Best Strategy to Minimize After-Care Costs for Total Joint Arthroplasty in a Bundled Payment Environment?

    Science.gov (United States)

    Slover, James D; Mullaly, Kathleen A; Payne, Ashley; Iorio, Richard; Bosco, Joseph

    2016-12-01

    The post-acute care strategies after lower extremity total joint arthroplasty including the use of post-acute rehabilitation centers and home therapy services are associated with different costs. Providers in bundled payment programs are incentivized to use the most cost-effective strategies. We used decision analysis to examine the impact of extending the inpatient hospital stay to avoid discharge of patients to a post-acute rehabilitation facility. The results of this decision analysis show that extended acute hospital care for up to 5.2 extra days to allow for home discharge, rather than discharge to a post-acute inpatient facility can be financially preferable, provided quality is not negatively impacted. The data demonstrate that because the cost of additional acute care hospital days is relatively small and because the cost of an extended post-acute inpatient rehabilitation facility is high, keeping patients in the acute facility for a few extra days and then discharging them directly to home may result in an overall lower cost than discharge after a shorter hospital stay to an expensive post-acute facility. However, this approach will have challenges, and future studies are needed to evaluate this change in strategy. Copyright © 2016 Elsevier Inc. All rights reserved.

  6. Investor's experience with keeping fixed costs during the construction of the Temelin nuclear power plant

    International Nuclear Information System (INIS)

    Cecil, P.

    1990-01-01

    The introduction of fixed costs in the construction of the Temelin nuclear power plant should secure stabilization of budget cost and prevent its increase. The differences between the fixed costs method and the procedure used so far are briefly described. The introduction of fixed costs was to be followed by the corresponding legal regulations; however, the legal adjustment has not been carried out in the desired completeness. The reason is the difference in understanding the notion of fixed costs by the investor, the contractor and the designer. Another problem is the difference in the level and the detail of the initial project design and of the Soviet implementation designs. The investor believes that the introduction of fixed costs has not yet met with the desired response by organizations participating in the construction. (J.P.)

  7. Analysis of the cost for the refurbishment of small hydropower plants

    International Nuclear Information System (INIS)

    Ogayar, B.; Vidal, P.G.; Hernandez, J.C.

    2009-01-01

    In view of all the concerns associated with fossil fuels and energy demand it is appropriate to investigate the large number of abandoned small hydropower plants. In order to solve the difficulty implied, by a viability study on the refurbishment of a small hydropower plant, a series of simple equations has been developed based on the economic optimization of the different elements. These equations can also be used for completely new hydropower plants. The result of this study will allow us to obtain quite approximate costs for the refurbishment of old hydropower plants, or the construction of new ones. These data on costs will act as a reference to examine real possibilities of refurbishment through different tools of financial and economic analysis. Although the equations developed have used unitary prices referring to Spain, they will be applicable to other countries just changing those prices for those of the country, required. (author)

  8. Cost evaluation of I and C upgrade approach in nuclear power plants

    International Nuclear Information System (INIS)

    Kang, Hyun-Tae; Lee, Jae-Ki

    2013-01-01

    Highlights: • Cost evaluation process for I and C system upgrade is built. • 4 cost factors affecting I and C system upgrade are described. • Additional cost incurred by a phased upgrade is calculated. • Cost for system upgrade between upgrade implementations is compared. - Abstract: Utilities have recently been debating the respective pros and cons of implementation of a multi-phase upgrade during several normal outages versus a single major upgrade implementation during a prolonged outage. We have studied these approaches and have been developing the basic design of nuclear power plants (NPPs) instrumentation and control (I and C) upgrade since early 2008. As part of this study, analyses of the NPPs I and C systems were conducted and the need for upgrading the systems was raised. One of the primary concerns regarding the system upgrade is a cost-benefit implementation, which will influence the upgrade approach. From this viewpoint, the I and C upgrade must consider economic factors such as I and C vendor cost, architecture engineering cost, installation cost, utility cost, and other transition costs such as training and procedure development. This paper presents a comparison study of economical aspects including cost evaluation between the aforementioned upgrade implementations and suggests a solution for I and C upgrade approach

  9. Energy Efficiency Improvement and Cost Saving Opportunities for Cement Making. An ENERGY STAR Guide for Energy and Plant Managers

    Energy Technology Data Exchange (ETDEWEB)

    Galitsky, Christina; Worrell, Ernst; Galitsky, Christina

    2008-01-01

    The cost of energy as part of the total production costs in the cement industry is significant, warranting attention for energy efficiency to improve the bottom line. Historically, energy intensity has declined, although more recently energy intensity seems to have stabilized with the gains. Coal and coke are currently the primary fuels for the sector, supplanting the dominance of natural gas in the 1970s. Most recently, there is a slight increase in the use of waste fuels, including tires. Between 1970 and 1999, primary physical energy intensity for cement production dropped 1 percent/year from 7.3 MBtu/short ton to 5.3 MBtu/short ton. Carbon dioxide intensity due to fuel consumption and raw material calcination dropped 16 percent, from 609 lb. C/ton of cement (0.31 tC/tonne) to 510 lb. C/ton cement (0.26 tC/tonne). Despite the historic progress, there is ample room for energy efficiency improvement. The relatively high share of wet-process plants (25 percent of clinker production in 1999 in the U.S.) suggests the existence of a considerable potential, when compared to other industrialized countries. We examined over 40 energy efficient technologies and measures and estimated energy savings, carbon dioxide savings, investment costs, and operation and maintenance costs for each of the measures. The report describes the measures and experiences of cement plants around the wold with these practices and technologies. Substantial potential for energy efficiency improvement exists in the cement industry and in individual plants. A portion of this potential will be achieved as part of (natural) modernization and expansion of existing facilities, as well as construction of new plants in particular regions. Still, a relatively large potential for improved energy management practices exists.

  10. Evaluation of depreciation costs in replacement investments of nuclear power plants

    International Nuclear Information System (INIS)

    Nakada, Shoji; Takashima, Ryuta; Nagano, Koji; Kimura, Hiroshi; Madarame, Haruki

    2010-01-01

    Replacement of nuclear power plants has the possibility of affecting the management of electric power suppliers. Therefore, in the nuclear policy, a depreciation method as an equalization method, which means that part of the investment cost is accumulated as an allowance, and after the start of operation, the depreciation cost in the replacement project is equalized, has been introduced in Japan. In this paper, we evaluate the replacement of nuclear power plants by taking into account the uncertainty of operating costs and the depreciation cost in order to examine the effect of the depreciation method on the decision criteria of the replacement.We found that the equalization method is elective for inducing the acceleration of the replacement. Furthermore, we show the relationship between the uncertainty and the depreciation method. It turns out that as uncertainty increases, the difference in investment threshold between the equalization method and the existing depreciation method decreases, and that in option value increases. (author)

  11. Cost benefit analysis of instrumentation, supervision and control systems for nuclear power plants

    International Nuclear Information System (INIS)

    Hagen, P.

    1973-08-01

    A cost benefit analysis is carried out on a BWR type reactor power plant in which an on-line computer performs plant supervision, reporting, logging, calibration and control functions, using display devices and plotters, while an off-line computer is available for bigger jobs such as fuel management calculations. All on-line functions are briefly described and specified. Three types of computer system are considered, a simplex system, a dual computer system and a multi-processor system. These systems are analysed with respect to reliability, back-up instrumentation requirements and costs. While the multiprocessor system gave in all cases the lowest annual failure costs, the margin to the duplex system was so small that hardware, maintenance and software costs would play an important role in making a decision. (JIW)

  12. Comparison of electricity production costs of nuclear and coal-fired power plants

    International Nuclear Information System (INIS)

    Peltzer, M.

    1980-01-01

    Electricity production costs of nuclear and coal-fired power plants their structure and future development are calculated and compared. Assumed beginning of operation is in the mid-1980. The technical and economical data are based on a nuclear power unit of 1 300 MW and on a coal-fired twin plant of 2 x 750 MW. The study describes and discusses the calculational method and the results. The costs for the electricity generation show an economic advantage for nuclear power. A sensitivity analysis shows that these results are valid also for changed input parameters. (orig.) [de

  13. Central Plant Optimization for Waste Energy Reduction (CPOWER). ESTCP Cost and Performance Report

    Science.gov (United States)

    2016-12-01

    meet all demands, and not necessarily for fuel economy or energy efficiency. Plant operators run the equipment according to a pre-set, fixed strategy ...exchanger, based on the site protocol. Thermal Energy Storage Tank Site-specific optimal operating strategies were developed for the chilled water...being served by the central plant Hypothesis The hypothesis tested that the optimized operation reduces wasted energy and energy costs by smart

  14. A total cost perspective on use of polymeric materials in solar collectors – Importance of environmental performance on suitability

    International Nuclear Information System (INIS)

    Carlsson, Bo; Persson, Helena; Meir, Michaela; Rekstad, John

    2014-01-01

    Highlights: • A polymeric solar collector system was compared with two traditional ones. • It was found the best in terms of climatic performance per solar heat collected. • The differences in climatic cost between the systems compared however are small. • The low climatic cost makes solar heating better compared to natural gas heating. • Use of Ecoindicator 99 for environmental cost makes solar heating even better. - Abstract: To assess the suitability of solar collector systems in which polymeric materials are used versus those in which more traditional materials are used, a case study was undertaken. In this case study a solar heating system with polymeric solar collectors was compared with two equivalent but more traditional solar heating systems: one with flat plate solar collectors and one with evacuated tube solar collectors. To make the comparison, a total cost accounting approach was adopted. The life cycle assessment (LCA) results clearly indicated that the polymeric solar collector system is the best as regards climatic and environmental performance when they are expressed in terms of the IPPC 100 a indicator and the Ecoindicator 99, H/A indicator, respectively. In terms of climatic and environmental costs per amount of solar heat collected, the differences between the three kinds of collector systems were small when compared with existing energy prices. With the present tax rates, it seems unlikely that the differences in environmental and climatic costs will have any significant influence on which system is the most favoured, from a total cost point of view. In the choice between a renewable heat source and a heat source based on the use of a fossil fuel, the conclusion was that for climatic performance to be an important economic factor, the tax or trade rate of carbon dioxide emissions must be increased significantly, given the initial EU carbon dioxide emission trade rate. The rate would need to be at least of the same order of magnitude

  15. Costs of decommissioning nuclear power plants as reported to the public to date

    International Nuclear Information System (INIS)

    Strasma, J.D.

    1982-01-01

    This paper attempts to determine what information has been available to the public, in the United States, concerning the cost of decommissioning nuclear power plants. The search was conducted in the Television News Index and Abstracts, in the annual indexes to The Reader's Digest, and in two computer-based bibliographic retrieval systems, Lockheed's DIALOG Magazine Index and the New York Times Information Bank. Fewer than ten articles appeared in widely read places, with none at all in the Reader's Digest and none on the evening TV news, from 1974 to date. The cost of decommissioning nuclear power plants was reported in various ways, with a wide range of estimates and relatively little actual experience. Costs were given in dollars of different years, in percentages of construction costs, in cost per KWH as per month to the consumer, etc., making the range of reported costs seem even wider than it really was. It is not surprising that the public fears that decommissioning costs will be alarmingly high. The public debate on energy policy might be more rational with better information on decommissioning costs. 16 references

  16. Online total organic carbon (TOC) monitoring for water and wastewater treatment plants processes and operations optimization

    Science.gov (United States)

    Assmann, Céline; Scott, Amanda; Biller, Dondra

    2017-08-01

    Organic measurements, such as biological oxygen demand (BOD) and chemical oxygen demand (COD) were developed decades ago in order to measure organics in water. Today, these time-consuming measurements are still used as parameters to check the water treatment quality; however, the time required to generate a result, ranging from hours to days, does not allow COD or BOD to be useful process control parameters - see (1) Standard Method 5210 B; 5-day BOD Test, 1997, and (2) ASTM D1252; COD Test, 2012. Online organic carbon monitoring allows for effective process control because results are generated every few minutes. Though it does not replace BOD or COD measurements still required for compliance reporting, it allows for smart, data-driven and rapid decision-making to improve process control and optimization or meet compliances. Thanks to the smart interpretation of generated data and the capability to now take real-time actions, municipal drinking water and wastewater treatment facility operators can positively impact their OPEX (operational expenditure) efficiencies and their capabilities to meet regulatory requirements. This paper describes how three municipal wastewater and drinking water plants gained process insights, and determined optimization opportunities thanks to the implementation of online total organic carbon (TOC) monitoring.

  17. Integration into plant biology and soil science has provided insights into the total environment.

    Science.gov (United States)

    Shao, Hongbo; Lu, Haiying; Xu, Gang; Marian, Brestic

    2017-02-01

    The total environment includes 5 closely-linking circles, in which biosphere and lithosphere are the active core. As global population increases and urbanization process accelerates, arable land is gradually decreasing under global climate change and the pressure of various types of environmental pollution. This case is especially for China. Land is the most important resources for human beings' survival. How to increase and manage arable land is the key for sustainable agriculture development. China has extensive marshy land that can be reclamated for the better potential land resources under the pre- condition of protecting the environment, which will be a good way for enlarging globally and managing arable land. Related studies have been conducted in China for the past 30years and now many results with obvious practical efficiency have been obtained. For summarizing these results, salt-soil will be the main target and related contents such as nutrient transport, use types, biodiversity and interactions with plants from molecular biology to ecology will be covered, in which the interactions among biosphere, lithosphere, atmosphere and anthroposphere will be focused on. Copyright © 2016 Elsevier B.V. All rights reserved.

  18. Evaluation of the electric power production cost growth due to decommissioning of nuclear power plants

    International Nuclear Information System (INIS)

    Basso, G.

    1982-01-01

    The increase of production cost for electric power generated by nuclear plants, due to their decommissioning and the end of operating life, is analysed in respect to (a) waiting time from indefinite shut-down date to the start of dismantlement, (b) financing method, (c) interest and inflation rates. The analysis shows that the additional cost is always small for those solutions which have higher probability to be adopted

  19. Capital cost evaluation of liquid metal reactor by plant type - comparison of modular type with monolithic type -

    International Nuclear Information System (INIS)

    Mun, K. H.; Seok, S. D.; Song, K. D.; Kim, I. C.

    1999-01-01

    A preliminary economic comparison study was performed for KALIMER(Korea Advanced LIquid MEtal Reactor)between a modular plant type with 8 150MWe modules and a 1200MWe monolithic plant type. In both cases of FOAK (First-Of-A-Kind) Plant and NOAK (Nth-Of-A-Kind) Plant, the result says that the economics of monolithic plant is superior to its modular plant. In case of NOAK plant comparison, however, the cost difference is not significant. It means that modular plant can compete with monolithic plant in capital cost if it makes efforts of cost reduction and technical progress on the assumption that the same type of NOAK plant will be constructed continuously

  20. Industrial cost assessment for ITER tritium plant system (water distillation, VPCE and ISS)

    International Nuclear Information System (INIS)

    Sood, S.K.; Kalyanam, K.M.; Fong, C.

    1995-01-01

    The objective of this Industrial Cost Assessment Task for ITER Tritium Plant System consists of providing and order of magnitude cost estimate for the following major subsystems, as outlined in the Scope of Task Agreement and Work Program: water distillation (WD) system, vapour phase catalytic exchange (VPCE) system and the isotope separation system (ISS). The methodology adopted in preparing the order of magnitude cost estimate for the above three subsystems of the ITER tritium plant system is based on building the estimate from the ground up, starting with equipment cost estimates, and adding labour activities separately for engineering, fabrication, assembly, testing installation commissioning, etc. The estimate has been developed assuming that the systems are to be engineered, fabricated and constructed in Canada, (to comply with the Codes, Standards, QA and Seismic Classification applicable in Canada) since information on ITER siting is not currently available. The estimate is based on Ontario Hydro in house cost data on similar systems and equipment, such as the heavy water upgrading plants. The cost estimates are not based on quotations from suppliers for specific ITER components, since this would require completion of detailed design and specifications. 4 refs., 9 tabs., 7 figs

  1. Direct hospital costs of total laparoscopic hysterectomy compared with fast-track open hysterectomy at a tertiary hospital: a retrospective case-controlled study.

    Science.gov (United States)

    Rhou, Yoon J J; Pather, Selvan; Loadsman, John A; Campbell, Neil; Philp, Shannon; Carter, Jonathan

    2015-12-01

    To assess the direct intraoperative and postoperative costs in women undergoing total laparoscopic hysterectomy and fast-track open hysterectomy. A retrospective review of the direct hospital-related costs in a matched cohort of women undergoing total laparoscopic hysterectomy (TLH) and fast-track open hysterectomy (FTOH) at a tertiary hospital. All costs were calculated, including the cost of advanced high-energy laparoscopic devices. The effect of the learning curve on cost in laparoscopic hysterectomy was also assessed, as was the hospital case-weighted cost, which was compared with the actual cost. Fifty women were included in each arm of the study. TLH had a higher intraoperative cost, but a lower postoperative cost than FTOH (AUD$3877 vs AUD$2776 P funding model in our hospital is inaccurate when compared to directly calculated hospital costs. © 2013 The Authors ANZJOG © 2013 The Royal Australian and New Zealand College of Obstetricians and Gynaecologists.

  2. An introduction to constructed wetlands (reed beds) sustainable low cost wastewater treatment plants

    International Nuclear Information System (INIS)

    Ahmad, M.I.

    2005-01-01

    The use of 'conventional' wastewater treatment technology (trickling filters and activated sludge) in developing countries has often been unsuccessful due to high cost, complex operating requirements and expensive maintenance procedures. Typical examples of such projects are wastewater plants in Islamabad and Karachi. Actually the conventional systems, such as trickling filters and activated sludge plants were developed to address the concerns about organic pollution of natural water bodies in western temperate climates, rather than the reduction of organic matter as well as pathogens which is often a priority in developing countries. Pakistan, being a developing country cannot and should not follow the western technology blindly but needs the use of a ppropriate technology . Appropriate technology is defined as a treatment system which meets the following criteria: Affordable: Total amount costs, including capital, operation, maintenance and depreciation are within the user's ability to pay. Operable: Operation of the system is possible with locally available labor and support. Reliable: Effluent quality requirements can be met consistently. Currently there are a limited number of appropriate technologies for small communities, which should be considered by a community and their designers. These include conventional and non-conventional systems such as stabilization ponds or lagoons, slow sand filters, land treatment systems, and wetlands (natural or constructed). The non-conventional systems often utilize 'ecological' treatment mechanism (such as aquatic systems or wetlands) and do not have the mechanical parts or energy requirements of conventional systems. Waste Stabilization Ponds are one such solution but sometimes are constrained by land availability, topography, and are not environment friendly. In such locations, natural or constructed wetlands (Reed Beds) could provide an alternative technology. It is what we call a LOW technology, rather than HI TECH

  3. Study of the environmental costs to nuclear power plants using the SIMPACTS program

    Energy Technology Data Exchange (ETDEWEB)

    Menzel, Francine; Sabundjian, Gaiane; Mutarelli, Rita de Cassia, E-mail: fmenzel@ipen.b, E-mail: gdjian@ipen.b [Instituto de Pesquisas Energeticas e Nucleares (IPEN/CNEN-SP), Sao Paulo, SP (Brazil)

    2011-07-01

    The nuclear energy presents advantages in comparison with other kinds of energy sources, when their externalities are evaluated. Externality is a term that represents the side effects of production of goods or services on other people not directly involved in the activity. The externalities can be identified and related to the term environmental cost. The environmental cost is a externality that somehow affects the environment, converted into economic terms, to then be compared with other costs of an action or enterprise. The environmental cost can be calculated through programs for that purpose, however for the nuclear area is the most used SIMPACTS, developed by the International Atomic Energy Agency (IAEA). The motivation for this work arose from the need to have a complete assessment of environmental costs from nuclear power reactors, although it is known that this kind of form of energy generation show an advantage over others with regard to externalities. This work is the first step in implementing the program SIMPACTS in plant Angra 2 in order to calculate the environmental cost of their operation. The objective is to develop a methodology for calculating environmental cost for nuclear power reactors. SIMPACTS program will be used to identify the advantages and disadvantages of a cost analysis of environmental and perform the calculation of environmental costs for Angra 2, with the aim of minimizing the environmental impacts of its operation. From an extensive literature search, is presented in this paper the methodology for calculating the environmental cost of the program SIMPACTS and some results of calculations with the environmental cost in international power reactors other power generation plants. (author)

  4. Study of the environmental costs to nuclear power plants using the SIMPACTS program

    International Nuclear Information System (INIS)

    Menzel, Francine; Sabundjian, Gaiane; Mutarelli, Rita de Cassia

    2011-01-01

    The nuclear energy presents advantages in comparison with other kinds of energy sources, when their externalities are evaluated. Externality is a term that represents the side effects of production of goods or services on other people not directly involved in the activity. The externalities can be identified and related to the term environmental cost. The environmental cost is a externality that somehow affects the environment, converted into economic terms, to then be compared with other costs of an action or enterprise. The environmental cost can be calculated through programs for that purpose, however for the nuclear area is the most used SIMPACTS, developed by the International Atomic Energy Agency (IAEA). The motivation for this work arose from the need to have a complete assessment of environmental costs from nuclear power reactors, although it is known that this kind of form of energy generation show an advantage over others with regard to externalities. This work is the first step in implementing the program SIMPACTS in plant Angra 2 in order to calculate the environmental cost of their operation. The objective is to develop a methodology for calculating environmental cost for nuclear power reactors. SIMPACTS program will be used to identify the advantages and disadvantages of a cost analysis of environmental and perform the calculation of environmental costs for Angra 2, with the aim of minimizing the environmental impacts of its operation. From an extensive literature search, is presented in this paper the methodology for calculating the environmental cost of the program SIMPACTS and some results of calculations with the environmental cost in international power reactors other power generation plants. (author)

  5. Increased installation in existing hydro power plants. Potentials and costs; Oekt installasjon i eksisterende kraftverk. Potensial og kostnader

    Energy Technology Data Exchange (ETDEWEB)

    Stensby, Kjell Erik (ed.)

    2011-06-15

    This report seeks to highlight the costs associated with increased installed capacity of existing hydropower plants. Five selected power plant is further studied. Furthermore, given an overview of the technical possibilities of power expansions in Norway. (AG)

  6. Replacement power costs due to nuclear-plant outages: a higher standard of care

    International Nuclear Information System (INIS)

    Gransee, M.F.

    1982-01-01

    This article examines recent state public utility commission cases that deal with the high costs of replacement power that utilities must purchase after a nuclear power plant outage. Although most commissions have approved such expenses, it may be that there is a trend toward splitting the costs of such expenses between ratepayer and stockholder. Commissions are demanding a management prudence test to determine the cause of the outage and whether it meets the reasonable man standard before allowing these costs to be passed along to ratepayers. Unless the standard is applied with flexibility, however, utility companies could invoke the defenses covering traditional common law negligence

  7. Benefits of using customized instrumentation in total knee arthroplasty: results from an activity-based costing model.

    Science.gov (United States)

    Tibesku, Carsten O; Hofer, Pamela; Portegies, Wesley; Ruys, C J M; Fennema, Peter

    2013-03-01

    The growing demand for total knee arthroplasty (TKA) associated with the efforts to contain healthcare expenditure by advanced economies necessitates the use of economically effective technologies in TKA. The present analysis based on activity-based costing (ABC) model was carried out to estimate the economic value of patient-matched instrumentation (PMI) compared to standard surgical instrumentation in TKA. The costs of the two approaches, PMI and standard instrumentation in TKA, were determined by the use of ABC which measures the cost of a particular procedure by determining the activities involved and adding the cost of each activity. Improvement in productivity due to increased operating room (OR) turn-around times was determined and potential additional revenue to the hospital by the efficient utilization of gained OR time was estimated. Increased efficiency in the usage of OR and utilization of surgical trays were noted with patient-specific approach. Potential revenues to the hospital were estimated with the use of PMI by efficient utilization of time saved in OR. Additional revenues of 78,240 per year were estimated considering utilization of gained OR time to perform surgeries other than TKA. The analysis suggests that use of PMI in TKA is economically effective when compared to standard instrumentation.

  8. Plant evaluation activities and O and M cost reduction in U.S

    International Nuclear Information System (INIS)

    Itoh, Takeshi

    1998-01-01

    Although some nuclear power plants face the possibility of premature retirement, most nuclear power plants have achieved substantial reductions in costs, mainly in O and M costs, and appear to be competitive with new gas and coal fired power plants. Improving competitiveness of existing nuclear power plants in the United States has primarily been driven by the electric utility self assessment activities. However, the background of this activity has been provided by the activities of NRC, INPO, NEI, EUCG and other activities being conducted for improvement of the nuclear power industry as a whole. Utility companies that are in the forefront of this activity have already achieved the reductions in staffing and outage time that are generally known to be effective for reducing O and M costs and are moving forward with rationalization and cost reductions in other areas. However, these electric utility companies are also achieving high safety and reliability. The staff of these electric utility companies have a high degree of autonomy, self motivation and self critical attitude and the staffing of these companies is a numerically small elite. This culture is supported by the self evaluation activity established by each company and is nurtured and supported by the management system. This appears to be one of the major elements in cost reduction. As this is based on U.S. information, differences in the system, society and culture in other nations mean that these findings may not be directly applicable. However, from the point of view of the prospects of nuclear power, these findings have an important meaning. This meaning is that the achievements in the United States of cost reduction activities centering on O and M costs are an important experience for other countries including Japan in reestablishing the economic competitiveness of nuclear power. (author)

  9. Cost base for hydropower plants : with a generating capacity of more than 10 000 kw : price level 1 January 2010

    Energy Technology Data Exchange (ETDEWEB)

    Slapgaard, Jan

    2012-07-25

    This manual has been prepared as a tool for calculation of average foreseeable contractor costs (civil works) and supplier costs (mechanical and electrical equipment) for large hydroelectric power plants with an early phase generating capacity of more than 10 000 kw. These costs will depend on a number of conditions which may vary from plant to plant, and this requires that the user to have a sound technical knowledge. This applies in particular to the civil works associated with the hydropower plant. The manual is a supplement to our cost base for smaller hydropower projects (Manual No. 2/2010)(au)

  10. Template-Directed Instrumentation Reduces Cost and Improves Efficiency for Total Knee Arthroplasty: An Economic Decision Analysis and Pilot Study.

    Science.gov (United States)

    McLawhorn, Alexander S; Carroll, Kaitlin M; Blevins, Jason L; DeNegre, Scott T; Mayman, David J; Jerabek, Seth A

    2015-10-01

    Template-directed instrumentation (TDI) for total knee arthroplasty (TKA) may streamline operating room (OR) workflow and reduce costs by preselecting implants and minimizing instrument tray burden. A decision model simulated the economics of TDI. Sensitivity analyses determined thresholds for model variables to ensure TDI success. A clinical pilot was reviewed. The accuracy of preoperative templates was validated, and 20 consecutive primary TKAs were performed using TDI. The model determined that preoperative component size estimation should be accurate to ±1 implant size for 50% of TKAs to implement TDI. The pilot showed that preoperative template accuracy exceeded 97%. There were statistically significant improvements in OR turnover time and in-room time for TDI compared to an historical cohort of TKAs. TDI reduces costs and improves OR efficiency. Copyright © 2015 Elsevier Inc. All rights reserved.

  11. Integrated batch production and maintenance scheduling for multiple items processed on a deteriorating machine to minimize total production and maintenance costs with due date constraint

    Directory of Open Access Journals (Sweden)

    Zahedi Zahedi

    2016-04-01

    Full Text Available This paper discusses an integrated model of batch production and maintenance scheduling on a deteriorating machine producing multiple items to be delivered at a common due date. The model describes the trade-off between total inventory cost and maintenance cost as the increase of production run length. The production run length is a time bucket between two consecutive preventive maintenance activities. The objective function of the model is to minimize total cost consisting of in process and completed part inventory costs, setup cost, preventive and corrective maintenance costs and rework cost. The problem is to determine the optimal production run length and to schedule the batches obtained from determining the production run length in order to minimize total cost.

  12. Temperate Interior West community tree guide: benefits, costs, and strategic planting

    Science.gov (United States)

    Kelaine E. Vargas; E. Gregory McPherson; James R. Simpson; Paula J. Peper; Shelley L. Gardner; Qingfu Xiao

    2007-01-01

    Even as they increase the beauty of our surroundings, trees provide us with a great many ecosystem services, including air quality improvement, energy conservation, stormwater interception, and atmospheric carbon dioxide reduction. These benefits must be weighed against the costs of maintaining trees, including planting, pruning, irrigation, administration, pest...

  13. Northern California coast community tree guide: benefits, costs, and strategic planting

    Science.gov (United States)

    E. Gregory McPherson; James R. Simpson; Paula. J. Peper; Aaron M.N. Crowell; Qingfu Xiao

    2010-01-01

    Trees make our cities more attractive and provide many ecosystem services, including air quality improvement, energy conservation, stormwater interception, and atmospheric carbon dioxide reduction. These benefits must be weighed against the costs of maintaining trees, including planting, pruning, irrigation, administration, pest control, liability, cleanup, and removal...

  14. Effect of increased regulation on capital costs and manual labor requirements of nuclear power plants

    International Nuclear Information System (INIS)

    Paik, S.; Schriver, W.R.

    1981-01-01

    An attempt is made to explain the impact of increasing governmental regulation on capital costs and labor requirements for constructing light water reactor (LWR) electric power plants. The principal factors contributing to these increases are: (1) market conditions and (2) increased regulation. General market conditions include additional costs attributable to price inflation of equipment, material, labor, and the increased cost of money. The central objective of this work is to estimate the impact of increasing regulation on plant costs and, conversely, on output. To do this it is necessary to isolate two opposing sets of forces which have been in operation during the period of major regulatory expansion: learning based upon plant design experience and economies of scale with increasing size (generating capacity) of newer plants. Conceptual models are specified to capture the independent effects of increasing regulation, learning, and economies of scale. Empirical results were obtained by estimating the models on data collected from industry experience during the 1967-1980 period. 23 refs

  15. Cost-effectiveness analysis of risk reduction at nuclear power plants

    International Nuclear Information System (INIS)

    Lochard, J.; Maccia, C.; Pages, P.

    1985-01-01

    Cost-effectiveness analysis of risk reduction is now widely accepted as a rational analytical framework to consistently address the resource allocation problem underlying any risk management process. This paper presents how this technique can be usefully applied to complex systems such as the management of radioactive releases from nuclear power plants into the environment. (orig.) [de

  16. Clearing of invasive alien plants in South Africa: a preliminary assessment of costs and progress

    CSIR Research Space (South Africa)

    Marais, R

    2004-01-01

    Full Text Available This paper provides estimates of the costs of clearing important species of invasive alien plants, as well as of progress made with clearing, based on data from a recently developed GIS-based project information system. Before the deployment...

  17. Application of the discounted value flows method in production cost calculations for Czechoslovak nuclear power plants

    International Nuclear Information System (INIS)

    Majer, P.

    1990-01-01

    The fundamentals are outlined of the discounted value flows method, which is used in industrial countries for calculating the specific electricity production costs. Actual calculations were performed for the first two units of the Temelin nuclear power plant. All costs associated with the construction, operation and decommissioning of this nuclear power plant were taken into account. With a high degree of certainty, the specific production costs of the Temelin nuclear power plant will lie within the range of 0.32 to 0.36 CSK/kWh. Nearly all results of the sensitivity analysis performed for the possible changes in the input values fall within this range. An increase in the interest rate to above 8% is an exception; this, however, can be regarded as rather improbable on a long-term basis. Sensitivity analysis gave evidence that the results of the electricity production cost calculations for the Temelin nuclear power plant can be considered sufficiently stable. (Z.M.). 7 figs., 2 tabs., 14 refs

  18. Cost/risk/benefit analysis report on the decontamination and decommissioning of Z-plant

    International Nuclear Information System (INIS)

    Melvin, J.P.; Sexton, R.A.; Fort, M.L.; Nunn, S.E.

    1979-01-01

    This study was performed to estimate the cost of decontaminating and decommissioning Z-Plant. All of the buildings in the Z-Plant exclusion area except Building 2736-Z, the plutonium storage vault, are included in the study. The study also excludes all underground facilities within the exclusion area which are not contained within a building and all Z-Plant related facilities outside the perimeter fence. The contamination in Z-Plant is primarily 239 Pu which has a half-life of 24,360 years. Because of the long half-life of 239 Pu, it is not practical to consider the isolation of the facility to await reduction of the contamination level by natural decay. Therefore, this study analyzes the costs, risk and benefit of decontaminating Z-Plant to four different levels of residual contamination. The three principle criteria used in the analysis are cost, the risk of offsite dose to the public, and the occupational exposure to onsite personnel

  19. Cost/risk/benefit analysis report on the decontamination and decommissioning of Z-plant

    Energy Technology Data Exchange (ETDEWEB)

    Melvin, J. P.; Sexton, R. A.; Fort, M. L.; Nunn, S. E.

    1979-09-28

    This study was performed to estimate the cost of decontaminating and decommissioning Z-Plant. All of the buildings in the Z-Plant exclusion area except Building 2736-Z, the plutonium storage vault, are included in the study. The study also excludes all underground facilities within the exclusion area which are not contained within a building and all Z-Plant related facilities outside the perimeter fence. The contamination in Z-Plant is primarily /sup 239/Pu which has a half-life of 24,360 years. Because of the long half-life of /sup 239/Pu, it is not practical to consider the isolation of the facility to await reduction of the contamination level by natural decay. Therefore, this study analyzes the costs, risk and benefit of decontaminating Z-Plant to four different levels of residual contamination. The three principle criteria used in the analysis are cost, the risk of offsite dose to the public, and the occupational exposure to onsite personnel.

  20. Probabilistic life-cycle cost analysis for renewable and non-renewable power plants

    International Nuclear Information System (INIS)

    Cartelle Barros, Juan José; Lara Coira, Manuel; Cruz López, María Pilar de la; Caño Gochi, Alfredo del

    2016-01-01

    Two probabilistic models are presented to assess the costs of power plants. One of them uses requirement trees, value functions and the analytic hierarchy process. It is also based on Monte Carlo simulation. The second one is a mathematical model for calculating the levelised cost of electricity (LCOE) based on discounted cash flow techniques, and combined with Monte Carlo simulation. The results obtained with both models are compared and discussed. On the one hand, the LCOE model provides the most reliable results. These results reinforce the idea that conventional or coal, lignite, oil, natural gas and nuclear power plants are still the most competitive options, with the LCOE falling in a range of around 25 to 200 €/MWh and mean values approaching 70 €/MWh. Generally, renewable power plants obtained the worst results, with a LCOE varying from around 30 to more than 450 €/MWh. Nevertheless, this study demonstrates that renewable alternatives can compete with their conventional counterparts under certain conditions. - Highlights: • Two probabilistic models are presented to assess the costs of power plants. • Conventional power plants are still the most competitive options. • Renewable energies can compete with their conventional counterparts under certain conditions. • The model aids the decision making process in the energy policy field.

  1. Effects Total Solar Eclipse to Nasty Behaviour of the Several Legume Plants as a Result Student Research

    Science.gov (United States)

    Anggraeni, S.; Diana, S.; Supriatno, B.

    2017-09-01

    Some group students of plant Physiology course have given task to do free inquiry. They investigated of the nasty behaviour of several legume plants in response to changes in light during the partial solar eclipse that occurred at March 9, 2016. The investigation carried out in UPI Bandung, West Java, Indonesia, which is in the penumbra region of a total solar eclipse with the location coordinates of latitude: -6.86105, longitude: 07.59071, S 6057’ 37.53553 “and E 107035’ 24.29141”. They were measuring the movement of opening leaves every ten minutes at the beginning of the start until the end of the eclipse compared with the behaviour without eclipsing. Influence is expressed by comparing the leaf opening movement (measured in the form of leaf angular) at the time of the eclipse with a normal day. Each group was observed for one plant of the legume, there are: Mimosa pudica, Bauhinia purpurea, Caesalpinia pulcherrima, and Arachis pintoi. The results showed that the changes in leaf angular in plants Mimosa pudica, Caesalpinia pulcherrima, and Arachis pintoi differently significant, except for Bauhinia purpurea. In conclusion, the total solar eclipse in the penumbra area affects the movement of some nasty legume plants. It is recommended to conduct a study of the nasty behaviour of legume plants in the area umbra in the path of a total solar eclipse.

  2. Associations between preoperative physical therapy and post-acute care utilization patterns and cost in total joint replacement.

    Science.gov (United States)

    Snow, Richard; Granata, Jaymes; Ruhil, Anirudh V S; Vogel, Karen; McShane, Michael; Wasielewski, Ray

    2014-10-01

    Health-care costs following acute hospital care have been identified as a major contributor to regional variation in Medicare spending. This study investigated the associations of preoperative physical therapy and post-acute care resource use and its effect on the total cost of care during primary hip or knee arthroplasty. Historical claims data were analyzed using the Centers for Medicare & Medicaid Services Limited Data Set files for Diagnosis Related Group 470. Analysis included descriptive statistics of patient demographic characteristics, comorbidities, procedures, and post-acute care utilization patterns, which included skilled nursing facility, home health agency, or inpatient rehabilitation facility, during the ninety-day period after a surgical hospitalization. To evaluate the associations, we used bivariate and multivariate techniques focused on post-acute care use and total episode-of-care costs. The Limited Data Set provided 4733 index hip or knee replacement cases for analysis within the thirty-nine-county Medicare hospital referral cluster. Post-acute care utilization was a significant variable in the total cost of care for the ninety-day episode. Overall, 77.0% of patients used post-acute care services after surgery. Post-acute care utilization decreased if preoperative physical therapy was used, with only 54.2% of the preoperative physical therapy cohort using post-acute care services. However, 79.7% of the non-preoperative physical therapy cohort used post-acute care services. After adjusting for demographic characteristics and comorbidities, the use of preoperative physical therapy was associated with a significant 29% reduction in post-acute care use, including an $871 reduction of episode payment driven largely by a reduction in payments for skilled nursing facility ($1093), home health agency ($527), and inpatient rehabilitation ($172). The use of preoperative physical therapy was associated with a 29% decrease in the use of any post-acute care

  3. Estimating the cost of delaying a nuclear power plant: methodology and application

    International Nuclear Information System (INIS)

    Hill, L.J.; Tepel, R.C.; Van Dyke, J.W.

    1985-01-01

    This paper presents an analysis of an actual 24-month nuclear power plant licensing delay under alternate assumptions about regulatory practice, sources of replacement power, and the cost of the plant. The analysis focuses on both the delay period and periods subsequent to the delay. The methodology utilized to simulate the impacts involved the recursive interaction of a generation-costing program to estimate fuel-replacement costs and a financial regulatory model to concomitantly determine the impact on the utility, its ratepayers, and security issues. The results indicate that a licensing delay has an adverse impact on the utility's internal generation of funds and financial indicators used to evaluate financial soundness. The direction of impact on electricity rates is contingent on the source of fuel used for replacement power. 5 references, 5 tables

  4. Utilization of municipal wastewater for cooling in thermoelectric power plants: Evaluation of the combined cost of makeup water treatment and increased condenser fouling

    Energy Technology Data Exchange (ETDEWEB)

    Walker, Michael E. [Illinois Inst. of Technology, Chicago, IL (United States). Dept. of Chemical and Biological Engineering; Theregowda, Ranjani B. [Carnegie Mellon Univ., Pittsburgh, PA (United States). Dept of Civil and Mechanical Engineering; Safari, Iman [Illinois Inst. of Technology, Chicago, IL (United States). Dept. of Chemical and Biological Engineering; Abbasian, Javad [Illinois Inst. of Technology, Chicago, IL (United States). Dept. of Chemical and Biological Engineering; Arastoopour, Hamid [Illinois Inst. of Technology, Chicago, IL (United States). Dept. of Chemical and Biological Engineering; Dzombak, David A. [Carnegie Mellon Univ., Pittsburgh, PA (United States). Dept of Civil and Mechanical Engineering; Hsieh, Ming-Kai [Tamkang Univ., Taipei (Taiwan). Waer Resources Management and Policy Research Center; Miller, David C. [National Energy Technology Lab. (NETL), Morgantown, WV (United States)

    2013-10-01

    A methodology is presented to calculate the total combined cost (TCC) of water sourcing, water treatment and condenser fouling in the recirculating cooling systems of thermoelectric power plants. The methodology is employed to evaluate the economic viability of using treated municipal wastewater (MWW) to replace the use of freshwater as makeup water to power plant cooling systems. Cost analyses are presented for a reference power plant and five different tertiary treatment scenarios to reduce the scaling tendencies of MWW. Results indicate that a 550 MW sub-critical coal fired power plant with a makeup water requirement of 29.3 ML/day has a TCC of $3.0 - 3.2 million/yr associated with the use of treated MWW for cooling. (All costs USD 2009). This translates to a freshwater conservation cost of $0.29/kL, which is considerably lower than that of dry air cooling technology, $1.5/kL, as well as the 2020 conservation cost target set by the U.S. Department of Energy, $0.74/kL. Results also show that if the available price of freshwater exceeds that of secondary-treated MWW by more than $0.13-0.14/kL, it can be economically advantageous to purchase secondary MWW and treat it for utilization in the recirculating cooling system of a thermoelectric power plant.

  5. Plant process computer replacements - techniques to limit installation schedules and costs

    International Nuclear Information System (INIS)

    Baker, M.D.; Olson, J.L.

    1992-01-01

    Plant process computer systems, a standard fixture in all nuclear power plants, are used to monitor and display important plant process parameters. Scanning thousands of field sensors and alarming out-of-limit values, these computer systems are heavily relied on by control room operators. The original nuclear steam supply system (NSSS) vendor for the power plant often supplied the plant process computer. Designed using sixties and seventies technology, a plant's original process computer has been obsolete for some time. Driven by increased maintenance costs and new US Nuclear Regulatory Commission regulations such as NUREG-0737, Suppl. 1, many utilities have replaced their process computers with more modern computer systems. Given that computer systems are by their nature prone to rapid obsolescence, this replacement cycle will likely repeat. A process computer replacement project can be a significant capital expenditure and must be performed during a scheduled refueling outage. The object of the installation process is to install a working system on schedule. Experience gained by supervising several computer replacement installations has taught lessons that, if applied, will shorten the schedule and limit the risk of costly delays. Examples illustrating this technique are given. This paper and these examples deal only with the installation process and assume that the replacement computer system has been adequately designed, and development and factory tested

  6. Power-to-heat in adiabatic compressed air energy storage power plants for cost reduction and increased flexibility

    Science.gov (United States)

    Dreißigacker, Volker

    2018-04-01

    The development of new technologies for large-scale electricity storage is a key element in future flexible electricity transmission systems. Electricity storage in adiabatic compressed air energy storage (A-CAES) power plants offers the prospect of making a substantial contribution to reach this goal. This concept allows efficient, local zero-emission electricity storage on the basis of compressed air in underground caverns. The compression and expansion of air in turbomachinery help to balance power generation peaks that are not demand-driven on the one hand and consumption-induced load peaks on the other. For further improvements in cost efficiencies and flexibility, system modifications are necessary. Therefore, a novel concept regarding the integration of an electrical heating component is investigated. This modification allows increased power plant flexibilities and decreasing component sizes due to the generated high temperature heat with simultaneously decreasing total round trip efficiencies. For an exemplarily A-CAES case simulation studies regarding the electrical heating power and thermal energy storage sizes were conducted to identify the potentials in cost reduction of the central power plant components and the loss in round trip efficiency.

  7. Cost-effectiveness of cervical total disc replacement vs fusion for the treatment of 2-level symptomatic degenerative disc disease.

    Science.gov (United States)

    Ament, Jared D; Yang, Zhuo; Nunley, Pierce; Stone, Marcus B; Kim, Kee D

    2014-12-01

    Cervical total disc replacement (CTDR) was developed to treat cervical spondylosis, while preserving motion. While anterior cervical discectomy and fusion (ACDF) has been the standard of care for 2-level disease, a randomized clinical trial (RCT) suggested similar outcomes. Cost-effectiveness of this intervention has never been elucidated. To determine the cost-effectiveness of CTDR compared with ACDF. Data were derived from an RCT that followed up 330 patients over 24 months. The original RCT consisted of multi-institutional data including private and academic institutions. Using linear regression for the current study, health states were constructed based on the stratification of the Neck Disability Index and a visual analog scale. Data from the 12-item Short-Form Health Survey questionnaires were transformed into utilities values using the SF-6D mapping algorithm. Costs were calculated by extracting Diagnosis-Related Group codes from institutional billing data and then applying 2012 Medicare reimbursement rates. The costs of complications and return-to-work data were also calculated. A Markov model was built to evaluate quality-adjusted life-years (QALYs) for both treatment groups. The model adopted a third-party payer perspective and applied a 3% annual discount rate. Patients included in the original RCT had to be diagnosed as having radiculopathy or myeloradiculopathy at 2 contiguous levels from C3-C7 that was unresponsive to conservative treatment for at least 6 weeks or demonstrated progressive symptoms. Incremental cost-effectiveness ratio of CTDR compared with ACDF. A strong correlation (R2 = 0.6864; P sensitivity analysis, the incremental cost-effectiveness ratio value stays below the threshold of $50,000 per QALY in most scenarios (range, -$58,194 to $147,862 per QALY). The incremental cost-effectiveness ratio of CTDR compared with traditional ACDF is lower than the commonly accepted threshold of $50,000 per QALY. This remains true with varying input

  8. CONTEXT MATTERS: THE IMPORTANCE OF MARKET CHARACTERISTICS IN THE VOLATILITY OF FEEDSTOCK COSTS FOR BIOGAS PLANTS.

    Science.gov (United States)

    Mertens, A; Van Meensel, J; Mondelaers, K; Buysse, J

    2015-01-01

    Recently, biogas plant managers in Flanders face increased financial uncertainty. Between 2011 and 2012, 20% of the Flemish biogas plants went bankrupt. Difficulties in obtaining feedstock at stable and affordable prices is one reason why the biogas sector struggles. In literature, contracting is often proposed as a way to decrease the volatility of the feedstock costs. However, these studies generally do not consider the context in which the biogas plant manager needs to buy the feedstock. Yet, this context could be of specific importance when biogas plant managers are in competition with other users of the same biomass type. Silage maize is an example of such a feedstock, as it is both used by dairy farmers and biogas plant managers. Using a combination of qualitative research and agent-based modelling, we investigated the effect of specific characteristics of the silage maize market on the acquisition of local silage maize by biogas plant managers. This paper details the institutional arrangements of the silage maize market in Flanders and the results of a scenario analysis, simulating three different scenarios. As shown by the results, the time of entry into the market, as well as the different institutional arrangements used by the biogas plant managers as opposed to dairy farmers could explain the difficulties in obtaining a stable supply of local silage maize by biogas plants. Our findings can help to develop mitigation strategies addressing these difficulties.

  9. Preconceptual design studies and cost data of depleted uranium hexafluoride conversion plants

    International Nuclear Information System (INIS)

    Jones, E

    1999-01-01

    One of the more important legacies left with the Department of Energy (DOE) after the privatization of the United States Enrichment Corporation is the large inventory of depleted uranium hexafluoride (DUF6). The DOE Office of Nuclear Energy, Science and Technology (NE) is responsible for the long-term management of some 700,000 metric tons of DUF6 stored at the sites of the two gaseous diffusion plants located at Paducah, Kentucky and Portsmouth, Ohio, and at the East Tennessee Technology Park in Oak Ridge, Tennessee. The DUF6 management program resides in NE's Office of Depleted Uranium Hexafluoride Management. The current DUF6 program has largely focused on the ongoing maintenance of the cylinders containing DUF6. However, the long-term management and eventual disposition of DUF6 is the subject of a Programmatic Environmental Impact Statement (PEIS) and Public Law 105-204. The first step for future use or disposition is to convert the material, which requires construction and long-term operation of one or more conversion plants. To help inform the DUF6 program's planning activities, it was necessary to perform design and cost studies of likely DUF6 conversion plants at the preconceptual level, beyond the PEIS considerations but not as detailed as required for conceptual designs of actual plants. This report contains the final results from such a preconceptual design study project. In this fast track, three month effort, Lawrence Livermore National Laboratory and Bechtel National Incorporated developed and evaluated seven different preconceptual design cases for a single plant. The preconceptual design, schedules, costs, and issues associated with specific DUF6 conversion approaches, operating periods, and ownership options were evaluated based on criteria established by DOE. The single-plant conversion options studied were similar to the dry-conversion process alternatives from the PEIS. For each of the seven cases considered, this report contains information on

  10. RECAP, Replacement Energy Cost for Short-Term Reactor Plant Shut-Down

    International Nuclear Information System (INIS)

    VanKuiken, J.C.; Daun, C.J.; Jusko, M.J.

    1995-01-01

    1 - Description of program or function: RECAP (Replacement Energy Cost Analysis Package) determines the replacement energy costs associated with short-term shutdowns or de-ratings of one or more nuclear reactors. Replacement energy cost refers to the change in generating-system production cost that results from shutting down a reactor. The cost calculations are based on the seasonal, unit-specific cost estimates for 1988-1991 for all 117 nuclear electricity-generating units in the U.S. RECAP is menu-driven, allowing the user to define specific case studies in terms of parameters such as the units to be included, the length and timing of the shutdown or de-rating period, the unit capacity factors, and the reference year for reporting cost results. In addition to simultaneous shutdown cases, more complicated situations, such as overlapping shutdown periods or shutdowns that occur in different years, can be examined through use of a present-worth calculation option. 2 - Method of solution: The user selects a set of units for analysis, defines a shutdown (or de-rating) period, and specifies any planned maintenance outages, delays in unit start-ups, or changes in default capacity factors. The program then determines which seasonal cost numbers to apply, estimates total and daily costs, and makes the appropriate adjustments for multiple outages if they are encountered. The change in production cost is determined from the difference between the total variable costs (variable fuel cost, variable operation and maintenance cost, and purchased energy cost) when the reactor is available for generation and when it is not. Changes in reference-year dollars are based on gross national product (GNP) price deflators or on optional use inputs. Once RECAP has completed the initial cost estimates for a case study (or series of case studies), present-worth analysis can be conducted using different reference-year dollars and discount rates, as specified by the user. The program uses

  11. A Flexible Job Shop Scheduling Problem with Controllable Processing Times to Optimize Total Cost of Delay and Processing

    Directory of Open Access Journals (Sweden)

    Hadi Mokhtari

    2015-11-01

    Full Text Available In this paper, the flexible job shop scheduling problem with machine flexibility and controllable process times is studied. The main idea is that the processing times of operations may be controlled by consumptions of additional resources. The purpose of this paper to find the best trade-off between processing cost and delay cost in order to minimize the total costs. The proposed model, flexible job shop scheduling with controllable processing times (FJCPT, is formulated as an integer non-linear programming (INLP model and then it is converted into an integer linear programming (ILP model. Due to NP-hardness of FJCPT, conventional analytic optimization methods are not efficient. Hence, in order to solve the problem, a Scatter Search (SS, as an efficient metaheuristic method, is developed. To show the effectiveness of the proposed method, numerical experiments are conducted. The efficiency of the proposed algorithm is compared with that of a genetic algorithm (GA available in the literature for solving FJSP problem. The results showed that the proposed SS provide better solutions than the existing GA.

  12. Adoption of an activity based costing model in an Indian steel plant

    Directory of Open Access Journals (Sweden)

    Rishi Dwivedi

    2016-10-01

    Full Text Available In the age of relentless global competition, constantly improving technology and better information systems, managers are often compelled to devise new strategies to maintain sustained competitive advantage while adopting new business management approaches. So, in this paper, an activity based costing (ABC model is proposed for a raw material handling section of an Indian steel plant. The results obtained from ABC model application in the said department facilitates quantification of the unit cost of each process, analysis of various activities in order to identify inefficiency, setting-up of better budget allocation, initiation of cost minimization procedure and establishment of an efficient resource requirement plan. Moreover, the cost information derived from ABC model is compared with that extracted from the traditional costing system to demonstrate that ABC model can significantly minimize the product cost distortion resulting from unsystematic allocation of overhead costs. This paper also discusses the practical implication of the implemented ABC model with respect to its critical role in effective resource control, improved strategic and operational decision making, and aid in continuous improvement through internal cost minimization in the department.

  13. Three-Dimensional Modeling of Weed Plants Using Low-Cost Photogrammetry

    Directory of Open Access Journals (Sweden)

    Dionisio Andújar

    2018-04-01

    Full Text Available Sensing advances in plant phenotyping are of vital importance in basic and applied plant research. Plant phenotyping enables the modeling of complex shapes, which is useful, for example, in decision-making for agronomic management. In this sense, 3D processing algorithms for plant modeling is expanding rapidly with the emergence of new sensors and techniques designed to morphologically characterize. However, there are still some technical aspects to be improved, such as an accurate reconstruction of end-details. This study adapted low-cost techniques, Structure from Motion (SfM and MultiView Stereo (MVS, to create 3D models for reconstructing plants of three weed species with contrasting shape and plant structures. Plant reconstruction was developed by applying SfM algorithms to an input set of digital images acquired sequentially following a track that was concentric and equidistant with respect to the plant axis and using three different angles, from a perpendicular to top view, which guaranteed the necessary overlap between images to obtain high precision 3D models. With this information, a dense point cloud was created using MVS, from which a 3D polygon mesh representing every plants’ shape and geometry was generated. These 3D models were validated with ground truth values (e.g., plant height, leaf area (LA and plant dry biomass using regression methods. The results showed, in general, a good consistency in the correlation equations between the estimated values in the models and the actual values measured in the weed plants. Indeed, 3D modeling using SfM algorithms proved to be a valuable methodology for weed phenotyping, since it accurately estimated the actual values of plant height and LA. Additionally, image processing using the SfM method was relatively fast. Consequently, our results indicate the potential of this budget system for plant reconstruction at high detail, which may be usable in several scenarios, including outdoor

  14. Examples for cost reduction in the design of a WWER-1000 nuclear power plant

    International Nuclear Information System (INIS)

    Kukkola, T.

    1991-01-01

    In a design project during recent years, a version for Finnish conditions has been and is being developed based on the Soviet WWER-1000 PWR plant with four horizontal steam generators. The plant will have a double containment. The inner containment will be a dry full pressure prestressed concrete containment with liner and the secondary containment will be made of ordinary concrete. Four train safety approach is adopted. It is supposed that the plant is to be designed according to the present Finnish safety requirements, e.g. severe reactor accidents are considered. When striving at an economic plant no compromises are made as far as safety is concerned. This paper describes possible cost reduction by redesigning the main technical equipment. (author). 1 ref

  15. Energy Efficiency Improvement and Cost Saving Opportunities for the Vehicle Assembly Industry: An ENERGY STAR Guide for Energy and Plant Managers

    Energy Technology Data Exchange (ETDEWEB)

    Galitsky, Christina; Galitsky, Christina; Worrell, Ernst

    2008-01-01

    The motor vehicle industry in the U.S. spends about $3.6 billion on energy annually. In this report, we focus on auto assembly plants. In the U.S., over 70 assembly plants currently produce 13 million cars and trucks each year. In assembly plants, energy expenditures is a relatively small cost factor in the total production process. Still, as manufacturers face an increasingly competitive environment, energy efficiency improvements can provide a means to reduce costs without negatively affecting the yield or the quality of the product. In addition, reducing energy costs reduces the unpredictability associated with variable energy prices in today?s marketplace, which could negatively affect predictable earnings, an important element for publicly-traded companies such as those in the motor vehicle industry. In this report, we first present a summary of the motor vehicle assembly process and energy use. This is followed by a discussion of energy efficiency opportunities available for assembly plants. Where available, we provide specific primary energy savings for each energy efficiency measure based on case studies, as well as references to technical literature. If available, we have listed costs and typical payback periods. We include experiences of assembly plants worldwide with energy efficiency measures reviewed in the report. Our findings suggest that although most motor vehicle companies in the U.S. have energy management teams or programs, there are still opportunities available at individual plants to reduce energy consumption cost effectively. Further research on the economics of the measures for individual assembly plants, as part of an energy management program, is needed to assess the potential impact of selected technologies at these plants.

  16. Life cycle cost of biomass power plant: Monte Carlo simulation of investment

    Directory of Open Access Journals (Sweden)

    Odavić Petrana

    2017-01-01

    Full Text Available Assessment of life cycle cost is considered as an important instrument for designing and evaluating success of every project. The aim of this work is to determine the precise impact of the investment costs and future operating and maintenance costs of CHP biomass plant. By using the Monte Carlo simulation are determined variations in the settings and the possible impact on the investment risk. The results show that the investment is justified, thanks to the positive outcome of the net present value (NPV, internal rate of return (IRR and the payback period. The greatest impact on the variability of annual profits have operating costs, which have the highest coefficient of variation of 6.44% and the largest share. Variability of net present value of 4% is acceptable, and the investment is considered as stable.

  17. Costs of electric power generation in different types of power plants

    International Nuclear Information System (INIS)

    Weible, H.

    1977-01-01

    In the framework of our study 'energy - environment - industry' we need among other things the costs of electric power generation. We register their structure in a sub-model. Recently there was disagreement on effective costs of electric power generation particularly when comparing fossil-fuel power plants to nuclear power plants. For this reason, expertises on the costs of electric power generation in nuclear and fossil-fuel power plants were ordered with the Energy-Economic Institute in Cologne as well as with the Battelle Institute in Frankfurt. In the framwork of our paper on the system 'energy - environment - industry' we do not want to give new data potentially required for our task, before the expertises will be finished. Therefore the results given in part III of this lecture are only meant as an example in order to show possible consequences of the cost programs set up, depending on initial data whose general recognition is to be aimed at. Furthermore, the theoretical approach to investment calculation has to win general recognition when recording calculation methods computer-compatibly. Any new formulations discussed in industrial management have not been taken into account. (orig.) [de

  18. A protocol for sustained reduction of Total Parenteral Nutrition and cost savings by improvement of nutritional care in hospitals.

    Science.gov (United States)

    van Schaik, Rian; Van den Abeele, Kurt; Melsens, Glenn; Schepens, Peter; Lanssens, Truus; Vlaemynck, Bernadette; Devisch, Maria; Niewold, Theo A

    2016-10-01

    Malnutrition and the use of Total Parenteral Nutrition (TPN) contribute considerably to hospital costs. Recently, we reported on the introduction of malnutrition screening and monitoring of TPN use in our hospital, which resulted in a large (40%) reduction in TPN and improved quality of nutritional care in two years (2011/12). Here, we aimed to assure continuation of improved care by developing a detailed malnutrition screening and TPN use protocol involving instruction tools for hospital staff, while monitoring the results in the following two years (2013/14). A TPN decision tree for follow up of TPN in patients and a TP-EN instruction card for caregivers was introduced, showing TPN/EN introduction schedules based on the energy needs of patients according to EB guidelines, also addressing the risk of refeeding syndrome. TPN patients were monitored by dietitians and TPN usage and costs were presented to the (medical) staff. Screening and treatment of malnourished patients by dietitians is simultaneously ongoing. In 2014 48% of patients, hospitalized for at least 48 h, were screened on malnutrition, 17% of them were diagnosed at risk, 7.9% malnourished and treated by dietitians. TPN usage dropped by 53% and cost savings of 51% were obtained due to 50% decrease of TPN users in 2014 versus 2010. TPN over EN ratio dropped from 2.4 in 2010 to 1.2 in 2014. Sustained improvement of nutritional care and reduction of TPN usage and costs is possible by introduction of procedures embedded in the existing structures. Copyright © 2016 European Society for Clinical Nutrition and Metabolism. Published by Elsevier Ltd. All rights reserved.

  19. Multiple account benefit-cost evaluation of the Burrard Thermal Generating Plant

    International Nuclear Information System (INIS)

    2001-04-01

    The government of British Columbia commissioned a multiple account benefit-cost analysis of the Burrard Thermal Generating Plant to ensure that the power production is in the economic and environmental interest of the province. The power plant consists of 6 natural gas-fired generating units with a combined capacity of 950 MW. It has been updated in recent years to reduce local emissions and to increase plant availability and reliability. Burrard has contributed in a major way to BC Hydro's net revenues, but there have been concerns that BC Hydro's purchases of natural gas for the power plant have contributed to the sharp increases in natural gas prices in 2001. There have also been concerns about air emissions from Burrard, including greenhouse gases and nitrous oxides. Historically, the plant has been beneficial, but this report will determine if it is in the provincial interest to continue operation of Burrard or to turn to alternative scenarios. The alternatives include constraining Burrard's output, or shutting it down and replacing it with other resources and repowering the plant with more efficient combined cycle gas turbine technology. In the constrained scenario, Burrard output and net exports are reduced. In the repowering scenario, investment and output at Burrard is increased. The financial consequences of these impacts are measured by their effect on the net system costs of meeting BC Hydro's load. The report demonstrated that it would not be in the overall interest of the province to constrain the operation of Burrard or shut it down. It was recommended that BC Hydro should review in detail the repowering option for Burrard, and that the government should consider imposing an emission charge reflecting the estimated damage costs associated with local pollutants generated at Burrard. The revenues would be used to fund offset measures in the Lower Fraser Valley airshed. 29 refs., 29 tabs., 3 appendices

  20. Cost-effective design of ringwall storage hybrid power plants: A real options analysis

    International Nuclear Information System (INIS)

    Weibel, Sebastian; Madlener, Reinhard

    2015-01-01

    Highlights: • Economic viability, optimal size, and siting of a hybrid ringwall hydro power plant. • Real options analysis for optimal investment timing and stochastic storage volumes. • Stochastic PV and solar power production affects optimal size of the storage device. • Monte Carlo simulation is used for wind/solar power, el. price, and investment cost. • Numerical computations for two different hybrid ringwall storage plant scenarios. - Abstract: We study the economic viability and optimal sizing and siting of a hybrid plant that combines a ringwall hydro storage system with wind and solar power plants (ringwall storage hybrid power plant, RSHPP). A real options model is introduced to analyze the economics of an onshore RSHPP, and in particular of the varying storage volume in light of the stochastic character of wind and solar power, as well as the optimal investment timing under uncertainty. In fact, many uncertainties arise in such a project. Energy production is determined by the stochastic character of wind and solar power, and affects the optimal size of the storage device. Monte Carlo simulation is performed to analyze the following sources of uncertainty: (i) wind intensity and solar irradiation; (ii) future electricity price; and (iii) investment costs. The results yield the optimal size of the storage device; the energy market on which the operator should sell the electricity generated; numerical examples for two different RSHPP scenarios; and a real options model for analyzing the opportunity to defer the project investment and thus to exploit the value of waiting

  1. Transgenic Plants as Low-Cost Platform for Chemotherapeutic Drugs Screening

    Directory of Open Access Journals (Sweden)

    Daniele Vergara

    2015-01-01

    Full Text Available In this work we explored the possibility of using genetically modified Arabidopsis thaliana plants as a rapid and low-cost screening tool for evaluating human anticancer drugs action and efficacy. Here, four different inhibitors with a validated anticancer effect in humans and distinct mechanism of action were screened in the plant model for their ability to interfere with the cytoskeletal and endomembrane networks. We used plants expressing a green fluorescent protein (GFP tagged microtubule-protein (TUA6-GFP, and three soluble GFPs differently sorted to reside in the endoplasmic reticulum (GFPKDEL or to accumulate in the vacuole through a COPII dependent (AleuGFP or independent (GFPChi mechanism. Our results demonstrated that drugs tested alone or in combination differentially influenced the monitored cellular processes including cytoskeletal organization and endomembrane trafficking. In conclusion, we demonstrated that A. thaliana plants are sensitive to the action of human chemotherapeutics and can be used for preliminary screening of drugs efficacy. The cost-effective subcellular imaging in plant cell may contribute to better clarify drugs subcellular targets and their anticancer effects.

  2. Photocatalytic treatment of an industrial effluent using artificial and solar UV radiation: an operational cost study on a pilot plant scale.

    Science.gov (United States)

    Durán, A; Monteagudo, J M; San Martín, I

    2012-05-15

    The aim of this work was to study the operation costs of treating a real effluent from an integrated gasification combined cycle (IGCC) power station located in Spain. The study compares different homogeneous photocatalytic processes on a pilot plant scale using different types of radiation (artificial UV or solar UV with a compound parabolic collector). The efficiency of the processes was evaluated by an analysis of the total organic carbon (TOC) removed. The following processes were considered in the study: (i) a photo-Fenton process at an artificial UV pilot plant (with the initial addition of H(2)O(2)), (ii) a modified photo-Fenton process with continuous addition of H(2)O(2) and O(2) to the system and (iii) a ferrioxalate-assisted solar photo-Fenton process at a compound parabolic collector (CPC) pilot plant. The efficiency of these processes in degrading pollutants has been studied previously, and the results obtained in each of those studies have been published elsewhere. The operational costs due to the consumption of electrical energy, reagents and catalysts were calculated from the optimal conditions of each process. The results showed that the solar photo-Fenton system was economically feasible, being able to achieve up to 75% mineralization with a total cost of 6 €/m(3), which can be reduced to 3.6 €/m(3) by subtracting the electrical costs because the IGCC plant is self-sufficient in terms of energy. Copyright © 2011 Elsevier Ltd. All rights reserved.

  3. Alternatives and costs for the decommissioning of Angra Nuclear Power Plants

    Energy Technology Data Exchange (ETDEWEB)

    Carajilescov, Pedro; Moreira, Joao Manoel Losada; Maiorino, Jose Rubens, E-mail: pedro.carajilescov@ufabc.edu.br [Universidade Federal do ABC (UFABC), Santo Andre, SP (Brazil)

    2013-07-01

    The decommissioning of a nuclear reactor requires several actions involving legal basis, decommissioning strategies, planning, dismantling, packing, transport and storage of a large volume of radioactive materials, qualified personnel and financial resources. The paper discusses the several aspects of these actions for the decommissioning of Angra nuclear Power Plants, based on the international experiences. The main phases of the decommissioning process, the Brazilian regulation and cost estimations are also presented. Finally, two alternatives for the decommissioning of the plants, based on logistic aspects, are discussed. (author)

  4. Alternatives and costs for the decommissioning of Angra Nuclear Power Plants

    International Nuclear Information System (INIS)

    Carajilescov, Pedro; Moreira, Joao Manoel Losada; Maiorino, Jose Rubens

    2013-01-01

    The decommissioning of a nuclear reactor requires several actions involving legal basis, decommissioning strategies, planning, dismantling, packing, transport and storage of a large volume of radioactive materials, qualified personnel and financial resources. The paper discusses the several aspects of these actions for the decommissioning of Angra nuclear Power Plants, based on the international experiences. The main phases of the decommissioning process, the Brazilian regulation and cost estimations are also presented. Finally, two alternatives for the decommissioning of the plants, based on logistic aspects, are discussed. (author)

  5. Methods and technologies for cost reduction in the design of water cooled reactor power plants

    International Nuclear Information System (INIS)

    1991-05-01

    The Specialists Meeting was organized in the framework of the IAEA International Working Group on Advanced Technologies for Water-Cooled Reactors. Its purpose was to provide an international forum for review and discussion on recent results in research and development on different methods and technologies of current and advanced water-cooled reactor power plants, which can lead to reduced investment and operation, maintenance and fuel-cycle costs of the plants. 27 specialists representing 10 countries and the IAEA took part in the meeting. 10 papers were presented. A separate abstract was prepared for each of these papers. Refs, figs and tabs

  6. EVALUATING THE LIFE CYCLE COSTS OF PLANT ASSETS – A MULTIDIMENSIONAL VIEW

    Directory of Open Access Journals (Sweden)

    Markus Gram

    2012-11-01

    Full Text Available This paper shows the results of the task group "Asset life cycle management" of the AustrianScientific Maintenance and Asset Management Association (ÖVIA. One purpose of the researchactivities is to create a generic life cycle model for physical assets which includes all costs in everyphase of the asset life cycle. The first step is a literature review determining the most established lifecycle cost models. This is the input for discussing the completeness of such frameworks with theparticipating industrial companies. A general model is deducted from existing approaches and thedetermined costs are evaluated with respect to priority and practical relevance. The result of theevaluation shows which costs are taken into account for investment decisions. Another outcome ofthe study is the verification of importance of the proposed costs for industrial companies, especiallyfor the process industry. The derived life cycle cost framework is the basis for developing a calculationtool and subsequently, for further research in the flied of uncertainty-based methodologies forlife cycle cost analyzing of physical plant assets.

  7. Power plant economy of scale and cost trends: further analyses and review of empirical studies

    International Nuclear Information System (INIS)

    Fisher, C.F. Jr.; Paik, S.; Schriver, W.R.

    1986-07-01

    Multiple regression analyses were performed on capital cost data for nuclear and coal-fired power plants in an extension of an earlier study which indicated that nuclear units completed prior to the accident at Three-Mile Island (TMI) have no economy of scale, and that units completed after that event have a weak economy of scale (scaling exponent of about 0.81). The earlier study also indicated that the scaling exponent for coal-fired units is about 0.92, compared with conceptual models which project scaling exponents in a range from about 0.5 to 0.9. Other empirical studies have indicated poor economy of scale, but a large range of cost-size scaling exponents has been reported. In the present study, the results for nuclear units indicate a scaling exponent of about 0.94 but with no economy of scale for large units, that a first unit costs 17% more than a second unit, that a unit in the South costs 20% less than others, that a unit completed after TMI costs 33% more than one completed before TMI, and that costs are increasing at 9.3% per year. In the present study, the results for coal-fired units indicate a scaling exponent of 0.93 but with better scaling economy in the larger units, that a first unit costs 38.5% more, a unit in the South costs 10% less, flue-gas desulfurization units cost 23% more, and that costs are increasing at 4% per year

  8. Analysis of the total system life cycle cost for the Civilian Radioactive Waste Management Program: Volume 1, The analysis and its results

    International Nuclear Information System (INIS)

    1987-06-01

    This report provides cost estimates for the fifth evaluation of the adequacy of the fee and is consistent with the program strategy and plans. The total-system cost for the reference cases in the improved-performance system is estimated at $32.1 to $38.2 billion (expressed in constant 1986 dollars) over the entire life of the system...or $1.5 to $1.6 billion more than that of the authorized system (i.e., the system without an MRS facility). The current estimate of the total-system cost for the reference cases in the improved-performance system is $3.8 to $5.4 billion higher than the estimate for the same system in the 1986 TSLCC analysis. In the case with the maximum increase, nearly all of the higher cost is due to a $5.2-billion increase in the costs of development and evaluation (D and E); all other system costs are essentially unchanged. The cost difference between the improved-performance system and the authorized system is smaller than the difference estimated in last year's TSLCC analysis. Volume 2 presents the detailed results for the 1987 analysis of the total-system life cycle cost (TSLCC). It consists of four sections: Section A presents the yearly flows of waste between waste-management facilities for the 12 aggregate logistics cases that were studied; Section B presents the annual total-system costs for each of the 30 TSLCC cases by major cost category; Section C presents the annual costs for the disposal of 16,000 canisters of defense high-level waste (DHLW) by major cost category for each of the 30 TSLCC cases; and Section D presents a summary of the cost-allocation factors that were calculated to determine the defense waste share of the total-system costs

  9. ORSIM, Nuclear Fuel, Fossil Fuel Hydroelectric Power Plant Cost and Economics

    International Nuclear Information System (INIS)

    Prince, B.E.; Turnage, J.C.

    1984-01-01

    1 - Description of problem or function: ORSIM is an electric power generating system integration model which simulates the multi-year operation of a mixed power system consisting of fossil, nuclear, hydroelectric, and pumped-storage units. For any specified refueling schedule for nuclear units and future load forecast, the model determines a plan of operation for the system which attempts to minimize the total discounted operating cost over a specified study period. The analysis considers the effects of forced outages, spinning reserve operating constraints, and scheduled introduction and retirement of generating stations. The model determines a maintenance schedule for the non-nuclear stations (nuclear stations are maintained during refueling outages) and the optimum allocation of energy-fixed nuclear and hydroelectric resources. It calculates the expected energy generated by each station in the system, by period over the planning horizon, based on input or calculated incremental operating cost. It also calculates the expected loss-of- load probability and un-served energy demand for each period in the planning horizon. An optimum operating plan, designed to minimize the discounted total production cost, is then calculated, as are the costs of operating each station in the system and the discounted total production cost for the derived plan of operation. 2 - Method of solution: ORSIM searches for a particular mode of operation which, over a multi-year planning horizon, will minimize the total system operating cost of a particular electric power generation system discounted to the beginning of the planning horizon. It does this by: (a) calculating the planned maintenance outages for all units; (b) estimating the incremental discounted cost of energy produced by each station in the system for every subinterval of the planning horizon; (c) utilizing the incremental discounted costs of energy generation to calculate, via probabilistic simulation, the economic optimum

  10. A new method for distribution of consumed heat in a fuel and costs in power and heating plants

    Energy Technology Data Exchange (ETDEWEB)

    Kadrnozka, J [Technical Univ., Brno (Czech Republic)

    1993-09-01

    There is described a new method for distribution of consumed heat in a fuel and costs in the power and heating plants, which is based on the relatively the same proportion of advantages followed from combine generation of electricity and heat on electricity and heat. The method is physically substantiated, it is very universal and it is applied for new types of power and heating plants and for distribution of investment costs and other costs. (orig./GL)

  11. A geographically resolved method to estimate levelized power plant costs with environmental externalities

    International Nuclear Information System (INIS)

    Rhodes, Joshua D.; King, Carey; Gulen, Gürcan; Olmstead, Sheila M.; Dyer, James S.; Hebner, Robert E.; Beach, Fred C.; Edgar, Thomas F.; Webber, Michael E.

    2017-01-01

    In this analysis we developed and applied a geographically-resolved method to calculate the Levelized Cost of Electricity (LCOE) of new power plants on a county-by-county basis while including estimates of some environmental externalities. We calculated the LCOE for each county of the contiguous United States for 12 power plant technologies. The minimum LCOE option for each county varies based on local conditions, capital and fuel costs, environmental externalities, and resource availability. We considered ten scenarios that vary input assumptions. We present the results in a map format to facilitate comparisons by fuel, technology, and location. For our reference analysis, which includes a cost of $62/tCO_2 for CO_2 emissions natural gas combined cycle, wind, and nuclear are most often the lowest-LCOE option. While the average cost increases when internalizing the environmental externalities (carbon and air pollutants) is small for some technologies, the local cost differences are as high as $0.62/kWh for coal (under our reference analysis). These results display format, and online tools could serve as an educational tool for stakeholders when considering which technologies might or might not be a good fit for a given locality subject to system integration considerations. - Highlights: • We propose a method to add externalities to LCOE. • We present the least cost technology for every county in the US. • The cheapest technology depends on many characteristics of that locale. • We present online tools for users to change our assumptions. • Our tools are useful in discussing the impact of policy on the cost of electricity.

  12. Determination Total Phosphour of Maize Plant Samples by Continuous Flow Analyzer in Comparison with Vanadium Molybdate Yellow Colorimetric Method

    Directory of Open Access Journals (Sweden)

    LIU Yun-xia

    2015-12-01

    Full Text Available The vanadium molybdate yellow colorimetric method(VMYC method is regarded as one of conventional methods for determining total phosphorus(P in plants, but it is time consuming procedure. Continuous flow analyzer(CFA is a fluid stream segmentation technique with air segments. It is used to measure P concentration based on the molybdate-antimony-ascorbic acid method of Murphy and Riley. Sixty nine of maize plant samples were selected and digested with H2SO4-H2O2. P concentrations in the digests were determined by CFA and VMYC method, respectively. The t test found that there was no any significant difference of the plant P contents measured by the CFA and the VMYC method. A linear equation could best describe their relationship: Y(CFA-P=0.927X(VMYC-P-0.002. The Pearson's correlation coefficient was 0.985 with a significance level(n=69, P<0.01. The CFA method for plant P measurement had a high precision with relative standard deviation(RSD less than 1.5%. It is suggested that the CFA based on Murphy and Riley colorimetric detection can be used to determinate total plant P in the digests solutions with H2SO4-H2O2. The CFA method is labor saving and can handle large numbers of samples. The human error in mixing with other operations is reduced to a great extent.

  13. Cost analysis for application of solidified waste fission product canisters in U.S. Army steam plants

    International Nuclear Information System (INIS)

    Sande, W.E.; Bjorklund, W.J.; Brooks, N.A.

    1977-04-01

    The main objectives of the present study are to design steam plants using projected waste fission product canister characteristics, to analyze the overall impact and cost/benefit to the nuclear fuel cycle associated with these plants, and to develop plans for this application if the cost analysis so warrants it. The construction and operation of a steam plant fueled with waste fission product canisters would require the involvement and cooperation of various government agencies and private industry; thus the philosophies of these groups were studied. These philosophies are discussed, followed by a forecast of canister supply, canister characteristics, and strategies for Army canister use. Another section describes the safety and licensing of these steam plants since this affects design and capital costs. The discussion of steam plant design includes boiler concepts, boiler heat transfer, canister temperature distributions, steam plant size, and steam plant operation. Also, canister transportation is discussed since this influences operating costs. Details of economics of Army steam plants are provided including steam plant capital costs, operating costs, fuel reprocessor savings due to Army canister storage, and overall economics. Recommendations are made in the final section

  14. The effects of regional insolation differences upon advanced solar thermal electric power plant performance and energy costs

    Science.gov (United States)

    Latta, A. F.; Bowyer, J. M.; Fujita, T.

    1979-01-01

    This paper presents the performance and cost of four 10-MWe advanced solar thermal electric power plants sited in various regions of the continental United States. Each region has different insolation characteristics which result in varying collector field areas, plant performance, capital costs, and energy costs. The paraboloidal dish, central receiver, cylindrical parabolic trough, and compound parabolic concentrator (CPC) comprise the advanced concepts studied. This paper contains a discussion of the regional insolation data base, a description of the solar systems' performances and costs, and a presentation of a range for the forecast cost of conventional electricity by region and nationally over the next several decades.

  15. ANALISIS PENETAPAN HARGA JUAL BERDASARKAN TARGET COSTING PADA PT VARIA USAHA BETON PLANT BM MAKASSAR

    Directory of Open Access Journals (Sweden)

    ASHAR MUNTA

    2017-05-01

    The Results showed there are differences in the price of Paving Blocks namely (1 in 2012 the difference between the price of Rp 25.70. (2 In 2013 the price difference Rp 3,31. And (3 In 2014 the difference between the price of Rp 1,37. Which means that the Target Costing Method is better than the Conventional Method in PT Varia Usaha Beton Plant BM Makassar.

  16. POPCYCLE: a computer code for calculating nuclear and fossil plant levelized life-cycle power costs

    International Nuclear Information System (INIS)

    Hardie, R.W.

    1982-02-01

    POPCYCLE, a computer code designed to calculate levelized life-cycle power costs for nuclear and fossil electrical generating plants is described. Included are (1) derivations of the equations and a discussion of the methodology used by POPCYCLE, (2) a description of the input required by the code, (3) a listing of the input for a sample case, and (4) the output for a sample case

  17. Universal model for water costs of gas exchange by animals and plants

    OpenAIRE

    Woods, H. Arthur; Smith, Jennifer N.

    2010-01-01

    For terrestrial animals and plants, a fundamental cost of living is water vapor lost to the atmosphere during exchange of metabolic gases. Here, by bringing together previously developed models for specific taxa, we integrate properties common to all terrestrial gas exchangers into a universal model of water loss. The model predicts that water loss scales to gas exchange with an exponent of 1 and that the amount of water lost per unit of gas exchanged depends on several factors: the surface t...

  18. Computed tomography for preoperative planning in minimal-invasive total hip arthroplasty: Radiation exposure and cost analysis

    Energy Technology Data Exchange (ETDEWEB)

    Huppertz, Alexander, E-mail: Alexander.Huppertz@charite.de [Imaging Science Institute Charite Berlin, Robert-Koch-Platz 7, D-10115 Berlin (Germany); Department of Radiology, Medical Physics, Charite-University Hospitals of Berlin, Chariteplatz 1, D-10117 Berlin (Germany); Radmer, Sebastian, E-mail: s.radmer@immanuel.de [Department of Orthopedic Surgery and Rheumatology, Immanuel-Krankenhaus, Koenigstr. 63, D-14109, Berlin (Germany); Asbach, Patrick, E-mail: Patrick.Asbach@charite.de [Department of Radiology, Medical Physics, Charite-University Hospitals of Berlin, Chariteplatz 1, D-10117 Berlin (Germany); Juran, Ralf, E-mail: ralf.juran@charite.de [Department of Radiology, Medical Physics, Charite-University Hospitals of Berlin, Chariteplatz 1, D-10117 Berlin (Germany); Schwenke, Carsten, E-mail: carsten.schwenke@scossis.de [Biostatistician, Scossis Statistical Consulting, Zeltinger Str. 58G, D-13465 Berlin (Germany); Diederichs, Gerd, E-mail: gerd.diederichs@charite.de [Department of Radiology, Medical Physics, Charite-University Hospitals of Berlin, Chariteplatz 1, D-10117 Berlin (Germany); Hamm, Bernd, E-mail: Bernd.Hamm@charite.de [Department of Radiology, Medical Physics, Charite-University Hospitals of Berlin, Chariteplatz 1, D-10117 Berlin (Germany); Sparmann, Martin, E-mail: m.sparmann@immanuel.de [Department of Orthopedic Surgery and Rheumatology, Immanuel-Krankenhaus, Koenigstr. 63, D-14109, Berlin (Germany)

    2011-06-15

    Computed tomography (CT) was used for preoperative planning of minimal-invasive total hip arthroplasty (THA). 92 patients (50 males, 42 females, mean age 59.5 years) with a mean body-mass-index (BMI) of 26.5 kg/m{sup 2} underwent 64-slice CT to depict the pelvis, the knee and the ankle in three independent acquisitions using combined x-, y-, and z-axis tube current modulation. Arthroplasty planning was performed using 3D-Hip Plan (Symbios, Switzerland) and patient radiation dose exposure was determined. The effects of BMI, gender, and contralateral THA on the effective dose were evaluated by an analysis-of-variance. A process-cost-analysis from the hospital perspective was done. All CT examinations were of sufficient image quality for 3D-THA planning. A mean effective dose of 4.0 mSv (SD 0.9 mSv) modeled by the BMI (p < 0.0001) was calculated. The presence of a contralateral THA (9/92 patients; p = 0.15) and the difference between males and females were not significant (p = 0.08). Personnel involved were the radiologist (4 min), the surgeon (16 min), the radiographer (12 min), and administrative personnel (4 min). A CT operation time of 11 min and direct per-patient costs of 52.80 Euro were recorded. Preoperative CT for THA was associated with a slight and justifiable increase of radiation exposure in comparison to conventional radiographs and low per-patient costs.

  19. Extending total parenteral nutrition hang time in the neonatal intensive care unit: is it safe and cost effective?

    Science.gov (United States)

    Balegar V, Kiran Kumar; Azeem, Mohammad Irfan; Spence, Kaye; Badawi, Nadia

    2013-01-01

    To investigate the effects of prolonging hang time of total parenteral nutrition (TPN) fluid on central line-associated blood stream infection (CLABSI), TPN-related cost and nursing workload. A before-after observational study comparing the practice of hanging TPN bags for 48 h (6 February 2009-5 February 2010) versus 24 h (6 February 2008-5 February 2009) in a tertiary neonatal intensive care unit was conducted. The main outcome measures were CLABSI, TPN-related expenses and nursing workload. One hundred thirty-six infants received 24-h TPN bags and 124 received 48-h TPN bags. Median (inter-quartile range) gestation (37 weeks (33,39) vs. 36 weeks (33,39)), mean (±standard deviation) admission weight of 2442 g (±101) versus 2476 g (±104) and TPN duration (9.7 days (±12.7) vs. 9.9 days (±13.4)) were similar (P > 0.05) between the 24- and 48-h TPN groups. There was no increase in CLABSI with longer hang time (0.8 vs. 0.4 per 1000 line days in the 24-h vs. 48-h group; P < 0.05). Annual cost saving using 48-h TPN was AUD 97,603.00. By using 48-h TPN, 68.3% of nurses indicated that their workload decreased and 80.5% indicated that time spent changing TPN reduced. Extending TPN hang time from 24 to 48 h did not alter CLABSI rate and was associated with a reduced TPN-related cost and perceived nursing workload. Larger randomised controlled trials are needed to more clearly delineate these effects. © 2012 The Authors. Journal of Paediatrics and Child Health © 2012 Paediatrics and Child Health Division (Royal Australasian College of Physicians).

  20. Cost-analysis of robotic-assisted laparoscopic hysterectomy versus total abdominal hysterectomy for women with endometrial cancer and atypical complex hyperplasia

    DEFF Research Database (Denmark)

    Herling, Suzanne Forsyth; Palle, Connie; Møller, Ann M.

    2016-01-01

    INTRODUCTION: The aim of this study was to analyse the hospital cost of treatment with robotic-assisted laparoscopic hysterectomy and total abdominal hysterectomy for women with endometrial cancer or atypical complex hyperplasia and to identify differences in resource use and cost. MATERIAL...... AND METHODS: This cost analysis was based on two cohorts: women treated with robotic-assisted laparoscopic hysterectomy (n = 202) or with total abdominal hysterectomy (n = 158) at Copenhagen University Hospital, Herlev, Denmark. We conducted an activity-based cost analysis including consumables and healthcare...... professionals' salaries. As cost-drivers we included severe complications, duration of surgery, anesthesia and stay at the post-anesthetic care unit, as well as number of hospital bed-days. Ordinary least-squares regression was used to explore the cost variation. The primary outcome was cost difference...

  1. Advancements in valve technology and industry lessons lead to improved plant reliability and cost savings

    International Nuclear Information System (INIS)

    Sharma, V.; Kalsi, M.S.

    2005-01-01

    Plant reliability and safety hinges on the proper functioning of several valves. Recent advancements in valve technology have resulted in new analytical and test methods for evaluating and improving valve and actuator reliability. This is especially significant in critical service applications in which the economic impact of a valve failure on production, outage schedules and consequential damages far surpasses the initial equipment purchase price. This paper presents an overview of recent advances in valve technology driven by reliability concerns and cost savings objectives without comprising safety in the Nuclear Power Industry. This overview is based on over 27 years of experience in supporting US and International nuclear power utilities, and contributing to EPRI, and NSSS Owners' Groups in developing generic models/methodologies to address industry wide issues; performing design basis reviews; and implementing plant-wide valve reliability improvement programs. Various analytical prediction software and hardware solutions and training seminars are now available to implement valve programs covering power plants' lifecycle from the construction phase through life extension and power up rate. These tools and methodologies can enhance valve-engineering activities including the selection, sizing, proper application, condition monitoring, failure analysis, and condition based maintenance optimization with a focus on potential bad actors. This paper offers two such examples, the Kalsi Valve and Actuator Program (KVAP) and Check Valve Analysis and Prioritization (CVAP) [1-3, 8, 9, 11-13]. The advanced, validated torque prediction models incorporated into KVAP software for AOVs and MOVs have improved reliability of margin predictions and enabled cost savings through elimination of unwarranted equipment modifications. CVAP models provides a basis to prioritize the population of valves recommended for preventive maintenance, inspection and/or modification, allowing

  2. Quantification of protein and total nitrogen in some plant foods of Iran

    African Journals Online (AJOL)

    are consumed as fruits and vegetables. The study involved the comparison of these plant protein values by selecting them and subjecting them to heat processing and to preparation of canned vegetables. The estimated protein values estimated are 57.0% for Arum, 44.86% for Portulaca, 28.47% for Chlorophytum, 22.69% ...

  3. Total Content of Polyphenols and Antioxidant Activity of Different Melliferous Plants

    Directory of Open Access Journals (Sweden)

    Claudia Pasca

    2016-01-01

    Full Text Available In this study polyphenols content and antioxidant activity of melliferous plants for the following: mint (Mentha pulegium, burdock (Arctium lappa, comfrey (Symphytum officinale, plantain (Pantago lanceolata, thyme (Thymus vulgaris, sage (Salvia officinalis, marigold (Calendula officinalis, small marshmallow (Althaea officinalis, echinacea (Echinaceea angustifolia and black popular (Populus nigra were investigated, using two different extraction methods. High content of polyphenols and flavones were extracted from Populus nigra, with an average of both extractions 23.14 mg GAE/g and 78.07 mg QE/g flavones. Among the studied plants, Arctium lappa registered the highest antioxidant activity (0.129 mmol Trolox/mL in alcoholic extract and Echinaceea angustifolia with a value of 0.122 mmol Trolox/mL in aqueous extract. The lowest values were recorded for the antioxidant activity of Althaea officinalis (alcoholic extract and Arctium lappa (aqueous extract. The results show that Arctium lappa, Echinaceea angustifolia and Populus nigra can be considered melliferous plants for their high biologically active compounds potential and bee products (honey and pollen that having the composition of these plants will have high antioxidant and antibacterial properties.

  4. Total-system expertise in economically efficient operation of nuclear power plants

    International Nuclear Information System (INIS)

    2000-01-01

    Siemens Nuclear Power GmbH can look back on well over 40 years of experience in developing and constructing nuclear power plants. 23 Power plant units of Siemens design are in operation in five countries, and in autumn this year, another one will start commercial operation, while yet another one is under construction. In comparative international power plant surveys, the Siemens-design systems usually rank in top positions when it comes to comparing systems availability and electric power generation, and Siemens have build a reputation in manufacturing power plants up to the highest safety standards worldwide. Our experience as a manufacturer of turnkey PWR and BWR type reactors, as well as our profound knowledge of international nuclear standardisation, engineering codes and safety guides, has been used and processed to the benefit of the services offered by Siemens, resulting in well-devised service packages, and enhancements and optimisation of our machinery and equipment. Siemens has of course obtained the relevant licenses and certification for all its services and products according to DIN ISO 9001, KTA and ASME standards [de

  5. Determination Total Phosphour of Maize Plant Samples by Continuous Flow Analyzer in Comparison with Vanadium Molybdate Yellow Colorimetric Method

    OpenAIRE

    LIU Yun-xia; WEN Yun-jie; HUANG Jin-li; LI Gui-hua; CHAI Xiao; WANG Hong

    2015-01-01

    The vanadium molybdate yellow colorimetric method(VMYC method) is regarded as one of conventional methods for determining total phosphorus(P) in plants, but it is time consuming procedure. Continuous flow analyzer(CFA) is a fluid stream segmentation technique with air segments. It is used to measure P concentration based on the molybdate-antimony-ascorbic acid method of Murphy and Riley. Sixty nine of maize plant samples were selected and digested with H2SO4-H2O2. P concentrations in the dige...

  6. A Low Cost Concept for Data Acquisition Systems Applied to Decentralized Renewable Energy Plants

    Directory of Open Access Journals (Sweden)

    Fábio T. Brito

    2011-01-01

    Full Text Available The present paper describes experiences of the use of monitoring and data acquisition systems (DAS and proposes a new concept of a low cost DAS applied to decentralized renewable energy (RE plants with an USB interface. The use of such systems contributes to disseminate these plants, recognizing in real time local energy resources, monitoring energy conversion efficiency and sending information concerning failures. These aspects are important, mainly for developing countries, where decentralized power plants based on renewable sources are in some cases the best option for supplying electricity to rural areas. Nevertheless, the cost of commercial DAS is still a barrier for a greater dissemination of such systems in developing countries. The proposed USB based DAS presents a new dual clock operation philosophy, in which the acquisition system contains two clock sources for parallel information processing from different communication protocols. To ensure the low cost of the DAS and to promote the dissemination of this technology in developing countries, the proposed data acquisition firmware and the software for USB microcontrollers programming is a free and open source software, executable in the Linux and Windows® operating systems.

  7. Oxyfuel carbonation/calcination cycle for low cost CO2 capture in existing power plants

    International Nuclear Information System (INIS)

    Romeo, Luis M.; Abanades, J. Carlos; Escosa, Jesus M.; Pano, Jara; Gimenez, Antonio; Sanchez-Biezma, Andres; Ballesteros, Juan C.

    2008-01-01

    Postcombustion CO 2 capture is the best suitable capture technology for existing coal power plants. This paper focuses on an emerging technology that involves the separation of CO 2 using the reversible carbonation reaction of CaO to capture CO 2 from the flue gas, and the calcination of CaCO 3 to regenerate the sorbent and produce concentrated CO 2 for storage. We describe the application to this concept to an existing (with today's technology) power plant. The added capture system incorporates a new supercritical steam cycle to take advantage of the large amount of heat coming out from the high temperature capture process (oxyfired combustion of coal is needed in the CaCO 3 calciner). In these conditions, the capture system is able to generate additional power (26.7% efficiency respect to LHV coal input to the calciner after accounting for all the penalties in the overall system), without disturbing the steam cycle of the reference plant (that retains its 44.9 efficiency). A preliminary cost study of the overall system, using well established analogues in the open literature for the main components, yields capture cost around 16 Euro /ton CO 2 avoided and incremental cost of electricity of just over 1 Euro /MW h e

  8. User's manual for levelized power generation cost using a microcomputer

    International Nuclear Information System (INIS)

    Fuller, L.C.

    1984-08-01

    Microcomputer programs for the estimation of levelized electrical power generation costs are described. Procedures for light-water reactor plants and coal-fired plants include capital investment cost, operation and maintenance cost, fuel cycle cost, nuclear decommissioning cost, and levelized total generation cost. Programs are written in Pascal and are run on an Apple II Plus microcomputer

  9. The determinants of cost efficiency of hydroelectric generating plants: A random frontier approach

    International Nuclear Information System (INIS)

    Barros, Carlos P.; Peypoch, Nicolas

    2007-01-01

    This paper analyses the technical efficiency in the hydroelectric generating plants of a main Portuguese electricity enterprise EDP (Electricity of Portugal) between 1994 and 2004, investigating the role played by increase in competition and regulation. A random cost frontier method is adopted. A translog frontier model is used and the maximum likelihood estimation technique is employed to estimate the empirical model. We estimate the efficiency scores and decompose the exogenous variables into homogeneous and heterogeneous. It is concluded that production and capacity are heteroge