  1. Tampa Electric Company Polk Power Station IGCC project: Project status

    Energy Technology Data Exchange (ETDEWEB)

    McDaniel, J.E.; Carlson, M.R.; Hurd, R.; Pless, D.E.; Grant, M.D. [Tampa Electric Co., FL (United States)

    1997-12-31

    The Tampa Electric Company Polk Power Station is a nominal 250 MW (net) Integrated Gasification Combined Cycle (IGCC) power plant located to the southeast of Tampa, Florida in Polk County, Florida. This project is being partially funded under the Department of Energy`s Clean Coal Technology Program pursuant to a Round II award. The Polk Power Station uses oxygen-blown, entrained-flow IGCC technology licensed from Texaco Development Corporation to demonstrate significant reductions of SO{sub 2} and NO{sub x} emissions when compared to existing and future conventional coal-fired power plants. In addition, this project demonstrates the technical feasibility of commercial scale IGCC and Hot Gas Clean Up (HGCU) technology. The Polk Power Station achieved ``first fire`` of the gasification system on schedule in mid-July, 1996. Since that time, significant advances have occurred in the operation of the entire IGCC train. This paper addresses the operating experiences which occurred in the start-up and shakedown phase of the plant. Also, with the plant being declared in commercial operation as of September 30, 1996, the paper discusses the challenges encountered in the early phases of commercial operation. Finally, the future plans for improving the reliability and efficiency of the Unit in the first quarter of 1997 and beyond, as well as plans for future alternate fuel test burns, are detailed. The presentation features an up-to-the-minute update on actual performance parameters achieved by the Polk Power Station. These parameters include overall Unit capacity, heat rate, and availability. In addition, the current status of the start-up activities for the HGCU portion of the plant is discussed.

  2. Pinon Pine IGCC project status

    International Nuclear Information System (INIS)

    Higginbotham, E.B.; Lamarre, L.J.; Glazer, M.

    1993-01-01

    Sierra Pacific Power Company (SPPCo) intends to build the Pinon Pine Power Project, an integrated coal gasification combined cycle (IGCC) plant at its Tracy Power Station near Reno, Nevada. The plant will burn approximately 800 tons of coal per day to generate electricity in a base load application. The Pinon Project was selected by the U.S. Department of Energy (DOE) for funding under Round IV of the Clean Coal Technology Program. The project will demonstrate the use of the KRW agglomerating fluidized bed gasifer operating in the air blown mode. Hot gas cleanup consisting of particulate and sulfur removal will also be demonstrated. The Cooperative Agreement between SPPCo and the DOE was executed in August 1992. Foster Wheeler USA Corporation (FWUSA) will provide engineering and construction management services. The M.W. Kellogg Company (MWK) will provide engineering of the gasifer and hot gas cleanup systems. A discussion of project progress since the 1992 Clean Coal Technology Conference, design and economic considerations, and current project status is presented

  3. IGCC demonstration project status combustion engineering IGCC repowering project

    International Nuclear Information System (INIS)

    Glamuzina, R.W.; Allen, R.J.; Peletz, L.J.

    1993-01-01

    This demonstration project was originally conceived as the repowering of an existing plant facility, the Lakeside Station in Springfield, Illinois. The Owner, City Water, Light and Power (CWL ampersand P), has removed five of the original boilers and three of the original turbines. The buildings have had asbestos insulation removed and the interiors have been prepared for the construction of a single Integrated Gasification Combined Cycle (IGCC) process train that will generate a net output of 60 megawatts. The plant consists of a combined cycle (gas turbine, heat recovery steam generator, steam turbine) power train located in the existing buildings and a coal gasification system in a new building. The gasification system contains ABB CE's air-blown, entrained flow, two stage gasifier, an advanced hot gas desulfurization system by General Electric Environmental Services, Inc. and the necessary auxiliary systems. The plant is designed to produce a nominal 60 MW net output with an ambient air temperature of 95 degrees F and a cooling water temperature of 89 degrees F on either Natural Gas or Illinois No. 5 coal

  4. Sulphur removal in IGCC projects

    Energy Technology Data Exchange (ETDEWEB)

    Cross, F. (Parsons (United Kingdom))

    1998-01-01

    The technology for recovering elemental sulphur from H[sub 2]S bearing gases is well established. The modified Claus Process is the principal work-horse in sulphur recovery and can customarily achieve conversion efficiencies of 95% or better. Nowadays, such a level of recovery is no longer sufficient in most instances and sulphur recovery facility must then include some form of enhanced recovery, usually by treating the Claus tail gas. A number of processes have been introduced to enable the overall recovery to be increased. Recoveries in excess of 99% are both feasible and economic. Use of oxygen in place has become very popular in cases where oxygen is available cheaply or where capacity increases are designed. Most IGCC projects needing an air separation plant would automatically benefit from extending the use of oxygen to the sulphur recovery plant. The most popular route to minimising sulphur emissions in the context of IGCC projects has involved an oxygen based Claus plant followed by tail gas hydrogenation, hydrogen sulphide recovery and its recycle to the Claus section. The recovery of H[sub 2]S from the Claus tail gas can be integrated with the main gas treating system in the gasification plant. The cost advantage of doing so is significant. Parsons has been involved with the technology since 1949 and has been responsible for developments such as the ammonia burning Claus and jointly with Unocal, the BSRP tail gas process and Selectox processes. Recent innovations in response changing environmental and production requirements have included catalytic and tail gas processes which reduce sulphur emissions. 6 figs., 2 tabs.

  5. Sulphur removal in IGCC projects

    Energy Technology Data Exchange (ETDEWEB)

    Cross, F. [Parsons (United Kingdom)

    1998-12-31

    The technology for recovering elemental sulphur from H{sub 2}S bearing gases is well established. The modified Claus Process is the principal work-horse in sulphur recovery and can customarily achieve conversion efficiencies of 95% or better. Nowadays, such a level of recovery is no longer sufficient in most instances and sulphur recovery facility must then include some form of enhanced recovery, usually by treating the Claus tail gas. A number of processes have been introduced to enable the overall recovery to be increased. Recoveries in excess of 99% are both feasible and economic. Use of oxygen in place has become very popular in cases where oxygen is available cheaply or where capacity increases are designed. Most IGCC projects needing an air separation plant would automatically benefit from extending the use of oxygen to the sulphur recovery plant. The most popular route to minimising sulphur emissions in the context of IGCC projects has involved an oxygen based Claus plant followed by tail gas hydrogenation, hydrogen sulphide recovery and its recycle to the Claus section. The recovery of H{sub 2}S from the Claus tail gas can be integrated with the main gas treating system in the gasification plant. The cost advantage of doing so is significant. Parsons has been involved with the technology since 1949 and has been responsible for developments such as the ammonia burning Claus and jointly with Unocal, the BSRP tail gas process and Selectox processes. Recent innovations in response changing environmental and production requirements have included catalytic and tail gas processes which reduce sulphur emissions. 6 figs., 2 tabs.

  6. Comprehensive report to Congress, Clean Coal Technology program: Pinon Pine IGCC Power Project

    International Nuclear Information System (INIS)

    1992-06-01

    The objective of the proposed project is to demonstrate an advanced IGCC system based upon the air-blown, fluidized-bed KRW gasifier with in-bed desulfurization using limestone sorbent and an external fixed- bed zinc ferrite sulfur removal system. Sierra Pacific Power Company (SPPC) requested financial assistance from DOE for the design, construction, and operation of a nominal 800 ton-per-day (86-Megawatt gross), air blown integrated gasification combined-cycle (IGCC) demonstration plant. The project, named the Pinon Pine IGCC Power Project, is to be located at SPPC's Tracy Station, a power generation facility located on a rural 400-acre plot about 17 miles east of Reno. The demonstration plant will produce electrical power for the utility grid. The project, including the demonstration phase, will last 96 months at a total cost of $269,993,100. DOE's share of the project cost will be 50 percent, or $134,996,550

  7. Kemper County IGCC (tm) Project Preliminary Public Design Report

    Energy Technology Data Exchange (ETDEWEB)

    Nelson, Matt; Rush, Randall; Madden, Diane; Pinkston, Tim; Lunsford, Landon

    2012-07-01

    The Kemper County IGCC Project is an advanced coal technology project that is being developed by Mississippi Power Company (MPC). The project is a lignite-fueled 2-on-1 Integrated Gasification Combined-Cycle (IGCC) facility incorporating the air-blown Transport Integrated Gasification (TRIG™) technology jointly developed by Southern Company; Kellogg, Brown, and Root (KBR); and the United States Department of Energy (DOE) at the Power Systems Development Facility (PSDF) in Wilsonville, Alabama. The estimated nameplate capacity of the plant will be 830 MW with a peak net output capability of 582 MW. As a result of advanced emissions control equipment, the facility will produce marketable byproducts of ammonia, sulfuric acid, and carbon dioxide. 65 percent of the carbon dioxide (CO{sub 2}) will be captured and used for enhanced oil recovery (EOR), making the Kemper County facility’s carbon emissions comparable to those of a natural-gas-fired combined cycle power plant. The commercial operation date (COD) of the Kemper County IGCC plant will be May 2014. This report describes the basic design and function of the plant as determined at the end of the Front End Engineering Design (FEED) phase of the project.

  8. ConocoPhillips Sweeny IGCC/CCS Project

    Energy Technology Data Exchange (ETDEWEB)

    Paul Talarico; Charles Sugg; Thomas Hren; Lauri Branch; Joseph Garcia; Alan Rezigh; Michelle Pittenger; Kathleen Bower; Jonathan Philley; Michael Culligan; Jeremy Maslen; Michele Woods; Kevin Elm

    2010-06-16

    Under its Industrial Carbon Capture and Sequestration (ICCS) Program, the United States (U.S.) Department of Energy (DOE) selected ConocoPhillips Company (ConocoPhillips) to receive funding through the American Recovery and Reinvestment Act (ARRA) of 2009 for the proposed Sweeny Integrated Gasification Combined Cycle (IGCC)/Carbon Capture and Storage (CCS) Project (Project) to be located in Brazoria County, Texas. Under the program, the DOE is partnering with industry to demonstrate the commercial viability and operational readiness of technologies that would capture carbon dioxide (CO{sub 2}) emissions from industrial sources and either sequester those emissions, or beneficially reuse them. The primary objective of the proposed Project was to demonstrate the efficacy of advanced technologies that capture CO{sub 2} from a large industrial source and store the CO{sub 2} in underground formations, while achieving a successful business venture for the entity (entities) involved. The Project would capture 85% of the CO{sub 2} produced from a petroleum coke (petcoke) fed, 703 MWnet (1,000 MWgross) IGCC power plant, using the ConocoPhillips (COP) proprietary and commercially proven E-Gas{trademark} gasification technology, at the existing 247,000 barrel per day COP Sweeny Refinery. In addition, a number of other commercially available technologies would be integrated into a conventional IGCC Plant in a unique, efficient, and reliable design that would capture CO{sub 2}. The primary destination for the CO{sub 2} would be a depleted natural gas field suitable for CO{sub 2} storage ('Storage Facility'). COP would also develop commercial options to sell a portion of the IGCC Plant's CO{sub 2} output to the growing Gulf Coast enhanced oil recovery (EOR) market. The IGCC Plant would produce electric power for sale in the Electric Reliability Council of Texas Houston Zone. The existing refinery effluent water would be treated and reused to fulfill all process

  9. Tampa electric company - IGCC project. Quarterly report, January 1, 1996--March 31, 1996

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1998-02-01

    This quarterly report consists of materials presented at a recent review of the project. The project is an IGCC project being conducted by Tampa Electric Company. The report describes the status of the facility construction, components, operations staff training, and discusses aspects of the project which may impact the final scheduled completion.

  10. Kotka ecopower IGCC-project, the attempt to transfer the biocycle project to Finland

    International Nuclear Information System (INIS)

    Salo, K.

    1998-01-01

    The Danish utilities Elsam and Elkraft planned to build a small (7 MW e ) IGCC-plant in Denmark, called Biocycle Project, based on the gasification and gas clean-up technology of Enviropower Inc. EU/THERMIE program committed to finance part of the investment. The project, however, was not feasible due to the difficulty of finding a suitable customer and sufficient amount of reasonably priced biomass. For this reason a new host and site was found for the Biocycle project. The new site was in Kotka, Finland, where Kotka Energy Ltd., the Energy Board of the City of Kotka acted as the main partner. The fuel of the IGCC project would have been sugar mill wood residue from Xyrofin Inc. During the feasibility investigation (project definition phase) Xyrofin Inc. made the decision to change the production process which eliminated the wood waste production. Without no-cost fuel and due to the low electricity price in Finland the small size IGCC power plant proved not to be feasible. (author)

  11. [Tampa Electric Company IGCC project]. 1996 DOE annual technical report, January--December 1996

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1997-12-31

    Tampa Electric Company`s Polk Power Station Unit 1 (PPS-1) Integrated Gasification Combined Cycle (IGCC) demonstration project uses a Texaco pressurized, oxygen-blown, entrained-flow coal gasifier to convert approximately 2,000 tons per day of coal to syngas. The gasification plant is coupled with a combined cycle power block to produce a net 250 MW electrical power output. Coal is slurried in water, combined with 95% pure oxygen from an air separation unit, and sent to the gasifier to produce a high temperature, high pressure, medium-Btu syngas with a heat content of about 250 BTUs/cf (HHV). The syngas then flows through a high temperature heat recovery unit which cools the syngas prior to its entering the cleanup systems. Molten coal ash flows from the bottom of the high temperature heat recovery unit into a water-filled quench chamber where it solidifies into a marketable slag by-product. Approximately 10% of the raw, hot syngas at 900 F is designed to pass through an intermittently moving bed of metal-oxide sorbent which removes sulfur-bearing compounds from the syngas. PPS-1 will be the first unit in the world to demonstrate this advanced metal oxide hot gas desulfurization technology on a commercial unit. The emphasis during 1996 centered around start-up activities.

  12. Technical and economic assessments commercial success for IGCC technology in China

    International Nuclear Information System (INIS)

    Xiong, T.

    1998-01-01

    The experiences gained from several Integrated Gasification Combined Cycle (IGCC) demonstration plants operating in the US and Europe facilitate commercial success of this advanced coal-based power generation technology. However, commercialization of coal-based IGCC technology in the West, particularly in the US, is restricted due to the low price of natural gas. On the contrary, in China--the largest coal producer and consumer in the world--a lack of natural gas supply, strong demand for air pollution control and relatively low costs of manufacturing and construction provide tremendous opportunities for IGCC applications. The first Chinese IGCC demonstration project was initiated in 1994, and other potential IGCC projects are in planning. IGCC applications in re-powering, fuel switching and multi-generation also show a great market potential in China. However, questions for IGCC development in China remain; where are realistic opportunities for IGCC projects and how can these opportunities be converted into commercial success? The answers to these questions should focus on the Chinese market needs and emphasize economic benefits, not just clean, or power. High price of imported equipment, high financing costs, and the technical risk of first-of-a-kind installation barricade IGCC development in China. This paper presents preliminary technical and economic assessments for four typical IGCC applications in the Chinese marketplace: central power station, fuel switching, re-powering, and multi-generation. The major factors affecting project economics--such as plant cost, financing, prices of fuel and electricity and operating capacity factor--are analyzed. The results indicate that well-proven technology for versatile applications, preferred financing, reduction of the plant cost, environmental superiority and appropriate project structure are the key for commercial success of IGCC in China

  13. Biomass IGCC

    Energy Technology Data Exchange (ETDEWEB)

    Salo, K; Keraenen, H [Enviropower Inc., Espoo (Finland)

    1997-12-31

    Enviropower Inc. is developing a modern power plant concept based on pressurised fluidized-bed gasification and gas turbine combined cycle (IGCC). The process is capable of maximising the electricity production with a variety of solid fuels - different biomass and coal types - mixed or separately. The development work is conducted on many levels. These and demonstration efforts are highlighted in this article. The feasibility of a pressurised gasification based processes compared to competing technologies in different applications is discussed. The potential of power production from biomass is also reviewed. (orig.) 4 refs.

  14. Biomass IGCC

    Energy Technology Data Exchange (ETDEWEB)

    Salo, K.; Keraenen, H. [Enviropower Inc., Espoo (Finland)

    1996-12-31

    Enviropower Inc. is developing a modern power plant concept based on pressurised fluidized-bed gasification and gas turbine combined cycle (IGCC). The process is capable of maximising the electricity production with a variety of solid fuels - different biomass and coal types - mixed or separately. The development work is conducted on many levels. These and demonstration efforts are highlighted in this article. The feasibility of a pressurised gasification based processes compared to competing technologies in different applications is discussed. The potential of power production from biomass is also reviewed. (orig.) 4 refs.

  15. Shippingport Station Decommissioning Project

    International Nuclear Information System (INIS)

    McKernan, M.L.

    1989-01-01

    The Shippingport Atomic Power Station was located on the Ohio River in Shippingport Borough (Beaver County), Pennsylvania, USA. The US Atomic Energy Commission (AEC) constructed the plant in the mid-1950s on a seven and half acre parcel of land leased from Duquesne Light Company (DLC). The purposes were to demonstrate and to develop Pressurized Water Recovery technology and to generate electricity. DLC operated the Shippingport plant under supervision of (the successor to AEC) the Department of Energy (DOE)-Naval Reactors (NR) until operations were terminated on October 1, 1982. NR concluded end-of-life testing and defueling in 1984 and transferred the Station's responsibility to DOE Richland Operations Office (RL), Surplus Facility Management Program Office (SFMPO5) on September 5, 1984. SFMPO subsequently established the Shippingport Station Decommissioning Project and selected General Electric (GE) as the Decommissioning Operations Contractor. This report is intended to provide an overview of the Shippingport Station Decommissioning Project

  16. Shippingport Station Decommissioning Project

    International Nuclear Information System (INIS)

    1989-01-01

    This Topical Report is a synopsis of the decontamination of plant components and structures at the Shippingport Station Decommissioning Project (SSDP). The information is provided as a part of the Technology Transfer Program to document the preparation activities in support of the shipment of radioactive wastes and the unconditional release of the site and structural materials. 1 ref., 16 figs., 4 tabs

  17. Clean coal technology project to Polk Power Station, Tampa Electric Company, Florida, Volume 1: Report

    International Nuclear Information System (INIS)

    1994-06-01

    Tampa Electric Company proposes to construct and operate a 1,150-MW power station in southwestern Polk County, Florida. The proposed Polk Power Station would require an EPA NPDES permit for a new source and would include a 260-MW IGCC unit as a DOE Clean Coal Technology demonstration project. This EIS document assesses the proposed project and alternatives with respect to environmental impacts. Mitigative measures are also evaluated for the preferred alternative. Included in this Volume I are the following: alternatives including Tampa Electric Companies proposed project (preferred alternative with DOE financial assistance); affected environment; environmental consequences of the alternatives

  18. Future direction of air separation design for gasification, IGCC and alternative fuel projects

    Energy Technology Data Exchange (ETDEWEB)

    Allam, R.J.; Castel-Smith, H.; Smith, A.R.; Sorensen, J.C. [Air Products and Chemicals, Inc. (United States)

    1998-12-31

    Low pressure and elevated pressure cryogenic air separation units (ASUs) have successfully been applied to support gasification projects worldwide. ASU technology has ranged from traditional, low pressure, standalone facilities supplying products only to the gasification island, to highly integrated, elevated pressure facilities that obtain air feed from and inject excess nitrogen into a gas turbine. The near-term direction of ASUs is increased single unit capacity, process optimizations that will benefit integration with the new generation of higher pressure ratio and increased capacity gas turbines, and overall ASU facility optimization for the specialized requirements of shipboard units for remote gas conversion processes. Longer-term development is proceeding on compression and driver requirements to support cost improvements for 10,000 to 20,000 merit ton per day oxygen facilities for onshore or platform-based gas conversion processes. 8 refs., 4 figs., 1 tab.

  19. Future direction of air separation design for gasification, IGCC and alternative fuel projects

    Energy Technology Data Exchange (ETDEWEB)

    Allam, R.J.; Castel-Smith, H.; Smith, A.R.; Sorensen, J.C. (Air Products and Chemicals, Inc. (United States))

    1998-01-01

    Low pressure and elevated pressure cryogenic air separation units (ASUs) have successfully been applied to support gasification projects worldwide. ASU technology has ranged from traditional, low pressure, standalone facilities supplying products only to the gasification island, to highly integrated, elevated pressure facilities that obtain air feed from and inject excess nitrogen into a gas turbine. The near-term direction of ASUs is increased single unit capacity, process optimizations that will benefit integration with the new generation of higher pressure ratio and increased capacity gas turbines, and overall ASU facility optimization for the specialized requirements of shipboard units for remote gas conversion processes. Longer-term development is proceeding on compression and driver requirements to support cost improvements for 10,000 to 20,000 merit ton per day oxygen facilities for onshore or platform-based gas conversion processes. 8 refs., 4 figs., 1 tab.

  20. Commercialization of IGCC technology looks promising

    International Nuclear Information System (INIS)

    Smith, D.J.

    1992-01-01

    This paper reports that a major focus of the latest round of the U.S. Department of Energy's Clean Coal Technology Program was three large-scale, high-efficiency electricity generating projects which will rely on coal gasification rather than burning the coal directly. The three projects are: Toms Creek integrated gasification combined-cycle (IGCC) demonstration project. The aim of the project is to demonstrate improved coal-to-power efficiencies in an integrated gasification combined-cycle process. According to the DOE, the Toms Creek project will show that significant reductions in SO 2 and NO x emissions can be accomplished through the use of IGCC technology. On completion of the project, 107 MW of electric capacity will be added to the grid. Pinon Pine IGCC power project. The project's aim is to demonstrate that IGCC plants can be constructed at significantly lower capital costs, and with higher thermal efficiencies, than conventional power generation technologies. It will also demonstrate the effectiveness of hot gas cleanup for low-sulfur western coals. Wasbash River coal gasification repowering project

  1. 75 FR 22674 - Moynihan Station Development Project

    Science.gov (United States)

    2010-04-29

    ... DEPARTMENT OF TRANSPORTATION Federal Railroad Administration Moynihan Station Development Project... availability of and public comment period for the Moynihan Station Development Project Environmental Assessment... 22675

  2. Strategic thinking on IGCC development in China

    International Nuclear Information System (INIS)

    Liu Hengwei; Ni Weidou; Li Zheng; Ma Linwei

    2008-01-01

    With electricity demand growing at a torrid pace-about 15% per year, faster than any other country in the world-China is fast-tracking the construction of new generation facilities, about 80% of which are coal-fired. China's total capacity in the reference scenario of World Energy Outlook 2006 (WEO2006) released by the International Energy Agency (IEA) is projected to practically 3.4 times, from 442 GW in 2004 to 1496 GW in 2030, growing at 4.8% per year on average. The vast majority of this huge generation requirement will still be met through the construction of coal power plants. Because new coal power plants built today have a long life cycle and are not easy to upgrade the technologies involved, decisions made now will have a major impact on the coal utilization mode in the coming years. Thus, the future 20 years is the strategic opportunity period of the transition of conventional coal utilization. Because the Integrated Gasification Combined Cycle (IGCC) can supply electricity, liquid fuels, hydrogen and other chemicals if needed at low pollution level, and has the potential to make carbon capture and sequestration much easier and cheaper than traditional pulverized coal boiler power plants, it should be the strategic direction for China to meet the requirements of the energy and environmental challenges. This paper makes an overview of China's energy and environmental challenges and opportunities, and describes the IGCC technology. It discusses why China should develop IGCC. What are the foundations for China to develop IGCC? What are the rational driving forces to develop IGCC in China? What is the reasonable developing path of IGCC in China?

  3. Advanced IGCC/Hydrogen Gas Turbine Development

    Energy Technology Data Exchange (ETDEWEB)

    York, William [General Electric Company, Schenectady, NY (United States); Hughes, Michael [General Electric Company, Schenectady, NY (United States); Berry, Jonathan [General Electric Company, Schenectady, NY (United States); Russell, Tamara [General Electric Company, Schenectady, NY (United States); Lau, Y. C. [General Electric Company, Schenectady, NY (United States); Liu, Shan [General Electric Company, Schenectady, NY (United States); Arnett, Michael [General Electric Company, Schenectady, NY (United States); Peck, Arthur [General Electric Company, Schenectady, NY (United States); Tralshawala, Nilesh [General Electric Company, Schenectady, NY (United States); Weber, Joseph [General Electric Company, Schenectady, NY (United States); Benjamin, Marc [General Electric Company, Schenectady, NY (United States); Iduate, Michelle [General Electric Company, Schenectady, NY (United States); Kittleson, Jacob [General Electric Company, Schenectady, NY (United States); Garcia-Crespo, Andres [General Electric Company, Schenectady, NY (United States); Delvaux, John [General Electric Company, Schenectady, NY (United States); Casanova, Fernando [General Electric Company, Schenectady, NY (United States); Lacy, Ben [General Electric Company, Schenectady, NY (United States); Brzek, Brian [General Electric Company, Schenectady, NY (United States); Wolfe, Chris [General Electric Company, Schenectady, NY (United States); Palafox, Pepe [General Electric Company, Schenectady, NY (United States); Ding, Ben [General Electric Company, Schenectady, NY (United States); Badding, Bruce [General Electric Company, Schenectady, NY (United States); McDuffie, Dwayne [General Electric Company, Schenectady, NY (United States); Zemsky, Christine [General Electric Company, Schenectady, NY (United States)

    2015-07-30

    The objective of this program was to develop the technologies required for a fuel flexible (coal derived hydrogen or syngas) gas turbine for IGCC that met DOE turbine performance goals. The overall DOE Advanced Power System goal was to conduct the research and development (R&D) necessary to produce coal-based IGCC power systems with high efficiency, near-zero emissions, and competitive capital cost. To meet this goal, the DOE Fossil Energy Turbine Program had as an interim objective of 2 to 3 percentage points improvement in combined cycle (CC) efficiency. The final goal is 3 to 5 percentage points improvement in CC efficiency above the state of the art for CC turbines in IGCC applications at the time the program started. The efficiency goals were for NOx emissions of less than 2 ppm NOx (@15 % O2). As a result of the technologies developed under this program, the DOE goals were exceeded with a projected 8 point efficiency improvement. In addition, a new combustion technology was conceived of and developed to overcome the challenges of burning hydrogen and achieving the DOE’s NOx goal. This report also covers the developments under the ARRA-funded portion of the program that include gas turbine technology advancements for improvement in the efficiency, emissions, and cost performance of gas turbines for industrial applications with carbon capture and sequestration. Example applications could be cement plants, chemical plants, refineries, steel and aluminum plants, manufacturing facilities, etc. The DOE’s goal for more than 5 percentage point improvement in efficiency was met with cycle analyses performed for representative IGCC Steel Mill and IGCC Refinery applications. Technologies were developed in this program under the following areas: combustion, larger latter stage buckets, CMC and EBC, advanced materials and coatings, advanced configurations to reduce cooling, sealing and rotor purge flows, turbine aerodynamics, advanced sensors, advancements in first

  4. IGCC technology and demonstration

    Energy Technology Data Exchange (ETDEWEB)

    Palonen, J [A. Ahlstrom Corporation, Karhula (Finland). Hans Ahlstrom Lab.; Lundqvist, R G [A. Ahlstrom Corporation, Helsinki (Finland); Staahl, K [Sydkraft AB, Malmoe (Sweden)

    1997-12-31

    Future energy production will be performed by advanced technologies that are more efficient, more environmentally friendly and less expensive than current technologies. Integrated gasification combined cycle (IGCC) power plants have been proposed as one of these systems. Utilising biofuels in future energy production will also be emphasised since this lowers substantially carbon dioxide emissions into the atmosphere due to the fact that biomass is a renewable form of energy. Combining advanced technology and biomass utilisation is for this reason something that should and will be encouraged. A. Ahlstrom Corporation of Finland and Sydkraft AB of Sweden have as one part of company strategies adopted this approach for the future. The companies have joined their resources in developing a biomass-based IGCC system with the gasification part based on pressurised circulating fluidized-bed technology. With this kind of technology electrical efficiency can be substantially increased compared to conventional power plants. As a first concrete step, a decision has been made to build a demonstration plant. This plant, located in Vaernamo, Sweden, has already been built and is now in commissioning and demonstration stage. The system comprises a fuel drying plant, a pressurised CFB gasifier with gas cooling and cleaning, a gas turbine, a waste heat recovery unit and a steam turbine. The plant is the first in the world where the integration of a pressurised gasifier with a gas turbine will be realised utilising a low calorific gas produced from biomass. The capacity of the Vaernamo plant is 6 MW of electricity and 9 MW of district heating. Technology development is in progress for design of plants of sizes from 20 to 120 MWe. The paper describes the Bioflow IGCC system, the Vaernamo demonstration plant and experiences from the commissioning and demonstration stages. (orig.)

  5. IGCC technology and demonstration

    Energy Technology Data Exchange (ETDEWEB)

    Palonen, J. [A. Ahlstrom Corporation, Karhula (Finland). Hans Ahlstrom Lab.; Lundqvist, R.G. [A. Ahlstrom Corporation, Helsinki (Finland); Staahl, K. [Sydkraft AB, Malmoe (Sweden)

    1996-12-31

    Future energy production will be performed by advanced technologies that are more efficient, more environmentally friendly and less expensive than current technologies. Integrated gasification combined cycle (IGCC) power plants have been proposed as one of these systems. Utilising biofuels in future energy production will also be emphasised since this lowers substantially carbon dioxide emissions into the atmosphere due to the fact that biomass is a renewable form of energy. Combining advanced technology and biomass utilisation is for this reason something that should and will be encouraged. A. Ahlstrom Corporation of Finland and Sydkraft AB of Sweden have as one part of company strategies adopted this approach for the future. The companies have joined their resources in developing a biomass-based IGCC system with the gasification part based on pressurised circulating fluidized-bed technology. With this kind of technology electrical efficiency can be substantially increased compared to conventional power plants. As a first concrete step, a decision has been made to build a demonstration plant. This plant, located in Vaernamo, Sweden, has already been built and is now in commissioning and demonstration stage. The system comprises a fuel drying plant, a pressurised CFB gasifier with gas cooling and cleaning, a gas turbine, a waste heat recovery unit and a steam turbine. The plant is the first in the world where the integration of a pressurised gasifier with a gas turbine will be realised utilising a low calorific gas produced from biomass. The capacity of the Vaernamo plant is 6 MW of electricity and 9 MW of district heating. Technology development is in progress for design of plants of sizes from 20 to 120 MWe. The paper describes the Bioflow IGCC system, the Vaernamo demonstration plant and experiences from the commissioning and demonstration stages. (orig.)

  6. IGCC crosses the threshold

    Energy Technology Data Exchange (ETDEWEB)

    Broderick, J E

    1986-07-01

    This paper describes the development of the Texaco Coal Gasification Process (TCGP), the first of the advanced gasification processes to become commercialized. The utilization of this process in various demonstration and commercial plants is described. The design of the Cool Water integrated gasification combined cycle (IGCC) plant in California is discussed in some detail. This plant has been operating successfully since June 1984, and has demonstrated that the Texaco gasification technology for electric power generation is commercially viable, can use many different feedstocks, has substantial efficiency growth potential, can provide competitively lower cost electric power, and offers vastly superior environmental performance.

  7. Shippingport Station Decommissioning Project: overview and justification

    International Nuclear Information System (INIS)

    Coffman, F.E.

    1984-01-01

    The purpose of this booklet is to brief the reader on the Shippingport Station Decommissioning Project and to summarize the benefits of funding the project in FY 1984. Background information on the station and the decommissioning project is provided in this section of the booklet; the need for a reactor decommissining demonstration is discussed in the next section; and a summary of how the Shippingport Station Decommissioning Project (SSDP) provides the needed demonstration is provided in the final section

  8. RWE clean coal programme - IGCC power plant with CO{sub 2} capture & storage

    Energy Technology Data Exchange (ETDEWEB)

    Wolf, K.-J.; Ewers, J.; Renzenbrink, W. [RWE Power AG, Essen (Germany)

    2007-07-01

    In early 2006, RWE Power announced it was building a 450 MW gross commercial IGCC power plant with carbon capture. This paper sums up the key results of the project development phase concerning the IGCC power plant and shows the basis for the feasibility phase of the project. 10 figs.

  9. Dynamic modeling of IGCC power plants

    International Nuclear Information System (INIS)

    Casella, F.; Colonna, P.

    2012-01-01

    Integrated Gasification Combined Cycle (IGCC) power plants are an effective option to reduce emissions and implement carbon-dioxide sequestration. The combination of a very complex fuel-processing plant and a combined cycle power station leads to challenging problems as far as dynamic operation is concerned. Dynamic performance is extremely relevant because recent developments in the electricity market push toward an ever more flexible and varying operation of power plants. A dynamic model of the entire system and models of its sub-systems are indispensable tools in order to perform computer simulations aimed at process and control design. This paper presents the development of the lumped-parameters dynamic model of an entrained-flow gasifier, with special emphasis on the modeling approach. The model is implemented into software by means of the Modelica language and validated by comparison with one set of data related to the steady operation of the gasifier of the Buggenum power station in the Netherlands. Furthermore, in order to demonstrate the potential of the proposed modeling approach and the use of simulation for control design purposes, a complete model of an exemplary IGCC power plant, including its control system, has been developed, by re-using existing models of combined cycle plant components; the results of a load dispatch ramp simulation are presented and shortly discussed. - Highlights: ► The acausal dynamic model of an entrained gasifier has been developed. ► The model can be used to perform system optimization and control studies. ► The model has been validated using field data. ► Model use is illustrated with an example showing the transient of an IGCC plant.

  10. Shippingport Station decommissioning project overview

    International Nuclear Information System (INIS)

    Schreiber, J.J.

    1985-01-01

    The U.S. Department of Energy is in the process of decommissioning the Shippingport Atomic Power Station located on the Ohio River, 30 miles northwest of Pittsburgh, Pennsylvania. The Shippingport Station is the first commercial size nuclear power plant to undergo decommissioning in the United Staes. The plant is located on approximately 7 acres of land owned by the Duquesne Light Company (DLC) and leased to the U.S. Government. DLC operates two nuclear power plants, Beaver Valley 1 and 2, located immediately adjacent to the site and the Bruce Mansfield coal-fired power plant is also within the immediate area. The Station was shutdown in October, 1982. Defueling operations began in 1983 and were completed by September, 1984. The Shippingport Station consists of a 275' x 60' fuel handling building containing the reactor containment chamber, the service building, the turbine building, the radioactive waste processing building, the administration building and other smaller support buildings. The Station has four coolant loops and most of the containment structures are located below grade. Structures owned by the U.S. Government including the fuel handling building, service building, contaminated equipment room, the boiler chambers, the radioactive waste processing building and the decontamination and laydown buildings will be dismantled and removed to 3 feet below grade. The area will then be filled with clean soil and graded. The turbine building, testing and training building and the administration building are owned by DLC and will remain

  11. Air permitting of IGCC plants

    Energy Technology Data Exchange (ETDEWEB)

    Chitikela, S.R.

    2007-07-01

    The IGCC process is, currently, the preferred choice over conventional thermal power production in regard to cleanup of fuel and significantly reduced contaminant emissions. The air permitting requirements include the review of: feed preparation and PM emissions; feed gasification and contaminant emissions; elemental sulfur recovery and SO{sub 2} emissions; options for carbon-dioxide recovery; syngas characteristics for combustion; CT design and combustion mechanisms; air contaminant emissions of CT; controlled CT emissions of nitrogen-oxides and carbon-monoxide gases using the SCR and oxidation catalysts, respectively; and, emission of volatile organic compounds (VOCs), and hazardous air pollutants (HAPs). However, the IGCC processes are being rigorously reviewed for the system integration and reliability, and significant reduction of air contaminant emissions (including the greenhouse gases). This paper included a review of IGCC air contaminant emission rates, and various applicable regulatory requirements, such as NSR (New Source Review), NSPS (New Source Performance Standards), and MACT (Maximum Achievable Control Technology). The IGCC facility's NOX, CO, SO{sub 2}, PM, VOCs, and HAPs emission rates would be significantly low. Thus, effective, construction and installation, and operation air permits would be necessary for IGCC facilities.

  12. Recent operating experience and improvement of commercial IGCC

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2013-09-01

    IGCC has today reached a status where experience is available from first and second generation plants, built in the 1970s/1980s and in the 1990s respectively, as commercial-scale demonstration plants for coal-based applications. These plants feature variations on gasification technology and subsequent environmental controls and in operating them a number of technical and commercial lessons have been learned that will help to improve the next generation of IGCC projects. The report reviews and summarises the state-of-the-art and operating experience of several commercial IGCC plants worldwide, setting out the lessons learned and plans for future development embracing such issues as the changes or modifications to plant made to overcome the operational problems and to improve the reliability and availability of the plant. Since IGCC is considered a 'capture ready' technology for CO2 abatement, the current status with regard to the incorporation of carbon capture and storage systems (CCS) has been reviewed. Finally, the report outlines the issues associated with assessing the risks in commercialising IGCC plant.

  13. Live from Space Station Learning Technologies Project

    Science.gov (United States)

    2001-01-01

    This is the Final Report for the Live From Space Station (LFSS) project under the Learning Technologies Project FY 2001 of the MSFC Education Programs Department. AZ Technology, Inc. (AZTek) has developed and implemented science education software tools to support tasks under the LTP program. Initial audience consisted of 26 TreK in the Classroom schools and thousands of museum visitors to the International Space Station: The Earth Tour exhibit sponsored by Discovery Place museum.

  14. IGCC based on proven technology developing towards 50% efficiency mark

    Energy Technology Data Exchange (ETDEWEB)

    Goudappel, E.; Berkhout, M. [Jacobs Consultancy, Leiden (Netherlands)

    2006-07-01

    In this paper the achievements made over the last 10 years in terms of reliability, load following and efficiency improvement potential at the Buggenum IGCC plant, are presented. Also the air side heat integration and its pros and cons are discussed. Additionally future business opportunities adjacent to the power production itself and the view on coal gasification in the near future are provided. The results are discussed and it is shown that with 'proven' gasifier and gas treatment technology, overall efficiency exceeding 47% (LHV basis) can be reached. It puts this technical potential in perspective and describes the view on interesting business opportunities around IGCC projects. 5 figs., 3 tabs.

  15. Shippingport station decommissioning project technology transfer program

    International Nuclear Information System (INIS)

    McKernan, M.L.

    1988-01-01

    US Department of Energy (DOE) Shippingport Station Decommissioning Project (SSDP) decommissioned, decontaminated, and dismantled the world's first, nuclear fueled, commercial size, electric power plant. SSDP programmatic goal direction for technology transfer is documentation of project management and operations experience. Objective is to provide future nuclear facility decommissioning projects with pertinent SSDP performance data for project assessment, planning, and operational implementation. This paper presents a working definition for technology transfer. Direction is provided for access and availability for SSDP technology acquisition

  16. Shippingport station decommissioning project technology transfer program

    International Nuclear Information System (INIS)

    McKernan, M.L.

    1989-01-01

    The US Department of Energy (DOE) Shippingport Station Decommissioning Project (SSDP) decontaminated and dismantled the world's first nuclear-fueled, commercial-size electric power plant. The SSDP programmatic goal direction for technology transfer is documentation of project management and operations experience. The objective is to provide future nuclear facility decommissioning projects with pertinent SSDP performance data for project assessment, planning, and operational implementation. This paper sets out access and availability directions for SSDP technology acquisition. Discusses are technology transfer definition; technology transfer products including topical and other project reports, professional-technical society presentations, other project liaison and media relations, visual documentation, and technology transfer data base; and retrieving SSDP information

  17. Shippingport station decommissioning project technology transfer program

    International Nuclear Information System (INIS)

    Pasquini, L.A.

    1986-01-01

    The purpose of the Shippingport Station Decommissioning Project (SSDP) is to place the Shippingport Atomic Power Station in a long-term radiologically safe condition following defueling of the reactor, to perform decommissioning in such a manner as to demonstrate to the nuclear industry the application of decommissioning procedures to a large scale nuclear power plant, and to provide useful planning data for future decommissioning projects. This paper describes the Technology Transfer Program for collecting and archiving the decommissioning data base and its availability to the nuclear industry

  18. Milliken Station Demonstration Project FDG retrofit update

    Energy Technology Data Exchange (ETDEWEB)

    Alder, R.C.; Jackson, C.E.; O`Dea, D.T. [and others

    1994-12-31

    The Milliken Clean Coal Demonstration Project is one of the nine Clean Coal Projects selected for funding in Round 4 of the U.S. DOE`s Clean Coal Demonstration Program. The project`s sponsor is New York State Electric and Gas Corporation (NYSEG). Project team members include CONSOL Inc., Saarberg-Holter-Umwelttechnik (SHU), NALCO/FuelTech, Stebbins Engineering and Manufacturing Co., DHR Technologies, and CE Air Preheater. Gilbert/Commonwealth is the Architect/Engineer and Construction Manager for the flue gas desulfurization (FGD) retrofit. The project will provide full-scale demonstration of a combination of innovative emission-reducing technologies and plant upgraded for the control of sulfur dioxide (SO{sub 2}) and nitrogen oxides (NO{sub x}) emissions from a coal-fired steam generator without a significant loss of station efficiency. The overall project goals are the following: 98% SO{sub 2} removal efficiency using limestone while burning high sulfur coal; up to 70% NO{sub x} reduction using the NOXOUT selective non-catalytic reduction (SNCR) technology in conjunction with combustion modifications; minimization of solid waste by producing marketable by-products including commercial grade gypsum, calcium chloride, and fly ash; zero wastewater discharge; maintenance of station efficiency by using a high efficiency heat-pipe air heater system and a low-power-consuming scrubber system. The demonstration project is being conducted at NYSEG`s Milliken Station, located in Lansing, New York. Milliken Station has two 150-MWe pulverized coal-fired units built in the 1950s by Combustion Engineering. The SHU FGD process and the combustion modifications are being installed on both units, but the NOXOUT process, Plant Economic Optimization Advisor (PEOA), and the high-efficiency air heater system will be installed on only one unit.

  19. Amine-based post-combustion CO2 capture in air-blown IGCC systems with cold and hot gas clean-up

    International Nuclear Information System (INIS)

    Giuffrida, A.; Bonalumi, D.; Lozza, G.

    2013-01-01

    Highlights: • Hot fuel gas clean-up is a very favorable technology for IGCC concepts. • IGCC net efficiency reduces to 41.5% when realizing post-combustion CO 2 capture. • Complex IGCC layouts are necessary if exhaust gas recirculation is realized. • IGCC performance does not significantly vary with exhaust gas recirculation. - Abstract: This paper focuses on the thermodynamic performance of air-blown IGCC systems with post-combustion CO 2 capture by chemical absorption. Two IGCC technologies are investigated in order to evaluate two different strategies of coal-derived gas clean-up. After outlining the layouts of two power plants, the first with conventional cold gas clean-up and the second with hot gas clean-up, attention is paid to the CO 2 capture station and to issues related to exhaust gas recirculation in combined cycles. The results highlight that significant improvements in IGCC performance are possible if hot coal-derived gas clean-up is realized before the syngas fuels the combustion turbine, so the energy cost of CO 2 removal in an amine-based post-combustion mode is less strong. In particular, IGCC net efficiency as high as 41.5% is calculated, showing an interesting potential if compared to the one of IGCC systems with pre-combustion CO 2 capture. Thermodynamic effects of exhaust gas recirculation are investigated as well, even though IGCC performance does not significantly vary against a more complicated plant layout

  20. Advanced IGCC-Hypogen concepts for a developing hydrogen market

    Energy Technology Data Exchange (ETDEWEB)

    Starr, F.; Cormos, C.-C.; Tzimas, E.; Brown, A. [European Commission, Petten (Netherlands). DG Joint Research Centre, Institute for Energy

    2007-07-01

    With FP6 the EU is funding a project called 'Dynamis' which aims to design plants to generate electricity, plus a limited amount of hydrogen from fossil fuels, in which the CO{sub 2} is captured and stored underground. Such plants have been characterised as being of the 'HYPOGEN' type since they generate both hydrogen and electric power. As the hydrogen market develops IGCC-Hypogen based systems will need to produce much greater amounts of hydrogen. It is also desirable that such plants should be able to vary the proportion of hydrogen-to-electricity. This will enable IGCC-Hypogen plants to load follow and two-shift as electricity demand from the grid changes. Such variations in power output are not always practical with existing designs of electricity-only IGCCs. This paper reviews the technical issues involved in providing a high-flexibility IGCC-Hypogen plant. Three such concepts are discussed (1) very limited flexibility in which the changes from a fixed hydrogen-electricity ratio concept are minor, (2) moderate level of flexibility in which the limit is imposed by the CCGT gas turbine turndown (3) complete flexibility, the plant being able produce the energy as all-electricity or all-hydrogen. 9 refs., 2 figs., 1 tab.

  1. Air toxics emissions from an IGCC process

    Energy Technology Data Exchange (ETDEWEB)

    Mojtahedi, W.; Norrbacka, P. [Enviropower Inc., Espoo (Finland); Hinderson, A. [Vattenfall (Sweden); Rosenberg, R.; Zilliacus, R.; Kurkela, E.; Nieminen, M. [VTT Energy, Espoo (Finland); Hoffren, H. [IVO International Oy, Vantaa (Finland)

    1996-12-01

    The so-called simplified coal gasification combined cycle process, incorporating air gasification and hot gas cleanup, promises high power generation efficiency in an environmentally acceptable manner. Increasingly more stringent environmental regulations have focused attention on the emissions of not only SO{sub 2} and NO{sub x} but also on the so-called air toxics which include a number of toxic trace elements. As result of recent amendments to the United States Clean Air Act, IGCC emissions of eleven trace elements: antimony, arsenic, beryllium, cadmium, chromium, cobalt, lead, manganese, mercury, nickel, selenium - as well as the radionuclides uranium and thorium may be regulated. Similarly, air missions standards in Europe include a limit of 0.05 mg Nm{sup 3} for mercury and cadmium and 1.0 3/Nm{sup 3} for other class I trace elements. A suitable sampling/measuring system has been developed in this project (in cooperation with Imatran Voima Oy, Electric Power Research Institute (EPRI) and Radian Cooperation) which will be used in the pressurized gasification tests. This will enable an accurate measurement of the volatilized trace element species, at high temperature and pressure, which may be found in the vapour phase. Models are being developed that can be used to determine not only the chemical equilibrium composition of gaseous, liquid and solid phases, but also possible interactions of the gaseous species with aerosol particles and surfaces, These should be used to more accurately assess the impact of the toxic trace metals emitted from the simplified IGCC system

  2. Shippingport station decommissioning project ALARA Program

    Energy Technology Data Exchange (ETDEWEB)

    Crimi, F.P. [Lockheed Environmental Systems and Technology Co., Houston, TX (United States)

    1995-03-01

    Properly planned and implemented ALARA programs help to maintain nuclear worker radiation exposures {open_quotes}As Low As Reasonably Achievable.{close_quotes}. This paper describes the ALARA program developed and implemented for the decontamination and decommissioning (D&D) of the Shippingport Atomic Power Station. The elements required for a successful ALARA program are discussed along with examples of good ALARA practices. The Shippingport Atomic Power Station (SAPS) was the first commercial nuclear power plant to be built in the United States. It was located 35 miles northwest of Pittsburgh, PA on the south bank of the Ohio river. The reactor plant achieved initial criticality in December 1959. During its 25-year life, it produced 7.5 billion kilowatts of electricity. The SAPS was shut down in October 1982 and was the first large-scale U.S. nuclear power plant to be totally decommissioned and the site released for unrestricted use. The Decommission Project was estimated to take 1,007 man-rem of radiation exposure and $.98.3 million to complete. Physical decommissioning commenced in September 1985 and was completed in September 1989. The actual man-rem of exposure was 155. The project was completed 6 months ahead of schedule at a cost of $91.3 million.

  3. Feasibility studies to improve plant availability and reduce total installed cost in IGCC plants

    Energy Technology Data Exchange (ETDEWEB)

    Sullivan, Kevin [General Electric Company, Houston, TX (United States); Anasti, William [General Electric Company, Houston, TX (United States); Fang, Yichuan [General Electric Company, Houston, TX (United States); Subramanyan, Karthik [General Electric Company, Houston, TX (United States); Leininger, Tom [General Electric Company, Houston, TX (United States); Zemsky, Christine [General Electric Company, Houston, TX (United States)

    2015-03-30

    The main purpose of this project is to look at technologies and philosophies that would help reduce the costs of an Integrated Gasification Combined Cycle (IGCC) plant, increase its availability or do both. GE’s approach to this problem is to consider options in three different areas: 1) technology evaluations and development; 2) constructability approaches; and 3) design and operation methodologies. Five separate tasks were identified that fall under the three areas: Task 2 – Integrated Operations Philosophy; Task 3 – Slip Forming of IGCC Components; Task 4 – Modularization of IGCC Components; Task 5 – Fouling Removal; and Task 6 – Improved Slag Handling. Overall, this project produced results on many fronts. Some of the ideas could be utilized immediately by those seeking to build an IGCC plant in the near future. These include the considerations from the Integrated Operations Philosophy task and the different construction techniques of Slip Forming and Modularization (especially if the proposed site is in a remote location or has a lack of a skilled workforce). Other results include ideas for promising technologies that require further development and testing to realize their full potential and be available for commercial operation. In both areas GE considers this project to be a success in identifying areas outside the core IGCC plant systems that are ripe for cost reduction and ity improvement opportunities.

  4. Efficiency enhancement in IGCC power plants with air-blown gasification and hot gas clean-up

    International Nuclear Information System (INIS)

    Giuffrida, Antonio; Romano, Matteo C.; Lozza, Giovanni

    2013-01-01

    Air-blown IGCC systems with hot fuel gas clean-up are investigated. In detail, the gas clean-up station consists of two reactors: in the first, the raw syngas exiting the gasifier and passed through high-temperature syngas coolers is desulfurized by means of a zinc oxide-based sorbent, whereas in the second the sulfided sorbent is duly regenerated. The hot fuel gas clean-up station releases H 2 S-free syngas, which is ready to fuel the combustion turbine after hot gas filtration, and a SO 2 -laden stream, which is successively treated in a wet scrubber. A thermodynamic analysis of two air-blown IGCC systems, the first with cold fuel gas clean-up and the second with hot fuel gas clean-up, both with a state-of-the-art combustion turbine as topping cycle, shows that it is possible to obtain a really attractive net efficiency (more than 51%) for the second system, with significant improvements in comparison with the first system. Nevertheless, higher efficiency is accomplished with a small reduction in the power output and no sensible efficiency improvements seem to be appreciated when the desulfurization temperature increases. Other IGCC systems, with an advanced 1500 °C-class combustion turbine as the result of technology improvements, are investigated as well, with efficiency as high as 53%. - Highlights: ► Hot fuel gas clean-up is a highly favorable technology for IGCC concepts. ► Significant IGCC efficiency improvements are possible with hot fuel gas clean-up. ► Size reductions of several IGCC components are possible. ► Higher desulfurization temperatures do not sensibly affect IGCC efficiency. ► IGCC efficiency as high as 53% is possible with a 1500°C-class combustion turbine

  5. IGCC - fuel-flexible technology for the future

    Energy Technology Data Exchange (ETDEWEB)

    Karg, J.; Hannemann, F. [Siemens AG Power Generation, Erlangen (Germany)

    2004-07-01

    According to IEA's World Energy Investment Outlook 2003 the electricity sector will dominate with about 60% of the total investment requirements expected until 2030 for worldwide energy-supply infrastructure. Around 45% of the capital needed for the electricity sector will be for power generation. The investment will be needed for capacity additions and to replace existing older facilities. According to the estimates the global primary energy demand is projected to grow by two thirds over the next three decades and electricity demand is expected to double by 2030. The natural gas for power generation is projected to increase significantly, but coal will remain the largest source of electricity generation throughout the projection period. These trends must be seen against the background that environmental regulations, are becoming tighter, and that environmental legislation will increasingly address greenhouse gas emissions. The necessity for more efficient use of primary energies in combination with more stringent environmental regulations for fossil-fuelled power plants therefore pushes concepts with increased efficiencies and reduced CO{sub 2} emissions, respectively. Since significant reduction of CO{sub 2} emissions cannot only be achieved via increased efficiencies or application of fuels with low carbon content, CO{sub 2} removal options also need to be considered for future power plant configurations. Considering this, IGCC is again one of the most promising solutions which are of relevance in this context. However, these new IGCC applications require further overall a plant concept and component development efforts. One essential step for performance improvement of future IGCC applications is to further develop syngas capabilities of advanced gas turbines, thereby considering the experience and lessons learned from operational plants. 11 refs., 7 figs., 5 tabs.

  6. Project authorization process in the thermal power stations vs in the hydroelectric power stations: two weights, two measurements?

    International Nuclear Information System (INIS)

    Comtois, Y.

    2004-01-01

    Key topics include the long tendering process, a comparison of two projects: thermal station vs. hydroelectrical station, and the solutions towards reducing the delay in obtaining authorization. (author)

  7. Evaluation of Service Station Attendant-Auto Care Project.

    Science.gov (United States)

    Cress, Ronald J.

    The project described offers an approach to providing occupational skills to socially and educationally handicapped youth, specifically the skills necessary for a service station attendant in driveway salesmanship and auto care. The 10-page evaluation report presents project goals and objectives with evaluation data (represented graphically) and…

  8. Waste management for the Shippingport Station Decommissioning Project

    International Nuclear Information System (INIS)

    Mullee, G.R.; Schulmeister, A.R.

    1987-01-01

    The Shippingport Station Decommissioning Project (SSDP) is being performed by the US Department of Energy (DOE) with the objectives of placing the station in a radiologically safe condition, demonstrating safe and cost effective dismantlement and providing useful data for future decommissioning projects. This paper describes the development of the Waste Management Plan which is being used for the accomplishment of the SSDP. Significant aspects of the Plan are described, such as the use of a process control and inventory system. The current status of waste management activities is reported. It is concluded that SSDP has some unique aspects which will provide useful information for future decommissioning projects

  9. Commercial gasifier for IGCC applications study report

    Energy Technology Data Exchange (ETDEWEB)

    Notestein, J.E.

    1990-06-01

    This was a scoping-level study to identify and characterize the design features of fixed-bed gasifiers appearing most important for a gasifier that was to be (1) potentially commercially attractive, and (2) specifically intended for us in integrated coal gasification/combined-cycle (IGCC) applications. It also performed comparative analyses on the impact or value of these design features and on performance characteristics options of the whole IGCC system since cost, efficiency, environmental traits, and operability -- on a system basis -- are what is really important. The study also reviewed and evaluated existing gasifier designs, produced a conceptual-level gasifier design, and generated a moderately advanced system configuration that was utilized as the reference framework for the comparative analyses. In addition, technical issues and knowledge gaps were defined. 70 figs., 31 tabs.

  10. Thermal and sintering characterization of IGCC slag

    Energy Technology Data Exchange (ETDEWEB)

    Acosta, A.; Iglesias, I.; Aineto, M.; Romero, M.; Rincon, J.M. [University of Castilla La Mancha, Ciudad Real (Spain)

    2002-07-01

    IGCC slag is a vitreous residual product from the new induction gasification combined cycle gasification thermal power plants. In order to characterize this waste as secondary raw material for the production of glasses and glass-ceramics as construction materials, slag from the Puertollano, Ciudad Real, Spain power plants was thermally investigated. After controlled heating this waste gives rise to hematite, anorthite, and cristobalite crystallized materials.

  11. Heat integration and analysis of decarbonised IGCC sites

    Energy Technology Data Exchange (ETDEWEB)

    Ng, K.S.; Lopez, Y.; Campbell, G.M.; Sadhukhan, J. [University of Manchester, Manchester (United Kingdom). School of Chemical Engineering & Analytical Science

    2010-02-15

    Integrated gasification combined cycle (IGCC) power generation systems have become of interest due to their high combined heat and power (CHP) generation efficiency and flexibility to include carbon capture and storage (CCS) in order to reduce CO{sub 2} emissions. However, IGCC's biggest challenge is its high cost of energy production. In this study, decarbonised coal IGCC sites integrated with CCS have been investigated for heat integration and economic value analyses. It is envisaged that the high energy production cost of an IGCC site can be offset by maximising site-wide heat recovery and thereby improving the cost of electricity (COE) of CHP generation. Strategies for designing high efficiency CHP networks have been proposed based on thermodynamic heuristics and pinch theory. Additionally, a comprehensive methodology to determine the COE from a process site has been developed. In this work, we have established thermodynamic and economic comparisons between IGCC sites with and without CCS and a trade-off between the degree of decarbonisation and the COE from the heat integrated IGCC sites. The results show that the COE from the heat integrated decarbonised IGCC sites is significantly lower compared to IGCC sites without heat integration making application of CCS in IGCC sites economically competitive.

  12. Api Energia IGCC plant is fully integrated with refinery

    Energy Technology Data Exchange (ETDEWEB)

    Del Bravo, R. [api Energia, Rome (Italy); Trifilo, R. [ABB Sadelmi, Milan (Italy); Chiantore, P.V. [api anonima petroli Italiania Spa, Rome (Italy); Starace, F. [ABB Power Generation, Baden (Switzerland); O`Keefe, L.F. [Texico, White Plains (United States)

    1998-06-01

    The api Energia integrated gasification combined cycle (IGCC) plant being built at Falconara Marittima, on Italy`s Adriatic coast, is one of the three IGCC plants under construction in Italy following the liberalization of the electricity production sector. The plant will take 59.2 t/h of high sulphur heavy oil produced by the Falconara refinery, convert it to syngas and use the gas to generate 280 MW of electricity, plus steam and other gases for use in the refinery. The IGCC plant will be highly integrated into the refining process, with a large number of interchanges between the IGCC unit and the rest of the refinery. (author)

  13. The installation IGCC power plans in the petroleum refinement: international experiences and lessons for Mexico; La instalacion de plantas IGCC en la refinacion de petroleo: experiencias internacionales y lecciones para Mexico

    Energy Technology Data Exchange (ETDEWEB)

    Hernandez, Joel [Ecole du Petrole et des Moteurs, Institut Franzais du Petrole, (France)

    2004-06-15

    In this work, are presented the technical and economic elements of the international experience for the installation of IGCC power plants in the petroleum refinement and the lessons for Mexico in the installation of this technology in PEMEX Refinacion are analyzed. The construction of IGCC power plants in the petroleum refinement has grown 14.3 % at worldwide level as of 1996, in which there was already an installed capacity of 160 MW. At the end of 2003 an installed capacity of 2,500 MW was reached. The growth in the installation of IGCC power plants fundamentally appears in Europe, being Italy and Spain leader countries in the construction of this technology in the petroleum refinement. However, countries like Holland, Japan, Singapore and the United States count on IGCC power plants for electricity and hydrogen generation, which take advantage of low value fuels such as vacuum tower residues, petroleum coke, asphalt, liquid fuels, among others. In Mexico, the installation IGCC power plants in the petroleum refinement is null, nevertheless Petroleos Mexicanos counts with the approval of the government for the installation of cogeneration power plants in its facilities. This approval would allow PEMEX to carry out projects for the installation IGCC power plants, specifically in PEMEX Refinacion, for the generation of electricity and hydrogen from the advantage of heavy residues of low economic value. The opportunity that the installation IGCC power plants in the petroleum refinement offers is directed towards the commercialization of the electricity and hydrogen, which would impel PEMEX Refinacion to enter the competition of the electrical market in Mexico. [Spanish] En este trabajo, se presentan los elementos tecnicos y economicos de la experiencia internacional para la instalacion de plantas IGCC en la refinacion de petroleo y se analizan las lecciones para Mexico en la instalacion de esta tecnologia en PEMEX Refinacion. La construccion de plantas IGCC en la

  14. The reliability of integrated gasification combined cycle (IGCC) power generation units

    Energy Technology Data Exchange (ETDEWEB)

    Higman, C.; DellaVilla, S.; Steele, B. [Syngas Consultants Ltd. (United Kingdom)

    2006-07-01

    This paper presents two interlinked projects aimed at supporting the improvement of integrated gasification combined cycle (IGCC) reliability. The one project comprises the extension of SPS's existing ORAP (Operational Reliability Analysis Program) reliability, availability and maintainability (RAM) tracking technology from its existing base in natural gas open and combined cycle operations into IGCC. The other project is using the extended ORAP database to evaluate performance data from existing plants. The initial work has concentrated on evaluating public domain data on the performance of gasification based power and chemical plants. This is being followed up by plant interviews in some 20 plants to verify and expand the database on current performance. 23 refs., 8 figs., 2 tabs.

  15. Shippingport Station Decommissioning Project: Contaminated concrete removal: Topical report

    International Nuclear Information System (INIS)

    1989-01-01

    This Topical Report is a synopsis of the removal of contaminated concrete from the Shippingport Station Decommissioning Project (SSDP). The information is provided as a part of the Technology Transfer Program to document the decontamination activities in support of site release in the decommissioning of a nuclear power reactor. 4 refs., 8 figs., 2 tabs

  16. Shippingport Station Decommissioning Project Start of Physical Decommissioning

    International Nuclear Information System (INIS)

    Crimi, F. P.

    1987-01-01

    The Shippingport Atomic Power Station consists of the nuclear steam supply system and associated radioactive waste processing systems, which are owned by the United States Department of Energy, and the turbine-generator and balance of plant, which is owned by the Duquesne Light Company. The station is located at Shippingport, Pennsylvania on seven acres of land leased by DOE from Duquesne Light Company. The Shippingport Station Decommissioning Project is being performed under contract to the DOE by the General Electric Company and its integrated subcontractor, Morrison-Knudsen Company. as the Decommissioning Operations Contractor. This paper describes the current status of the physical decommissioning work, which started September 1985. The preparations required to start a major decommissioning work effort in a safe and cost effective manner are discussed including the development and implementation of a cost/schedule control system. The detailed plan required to ensure that people, property, and procedures are ready in sufficient time to support the start of physical decommissioning is also discussed. The total estimated cost of the Shippingport Station Decommissioning Project should be $98.3 M, with the Project scheduled for completion in April 1990. As the decommissioning of the first commercial-scale nuclear power plant, the Shippingport Project is expected to set the standard for safe, cost-effective demolition of nuclear plants

  17. Shippingport station decommissioning project irradiated components transfer: Topical report

    International Nuclear Information System (INIS)

    1988-01-01

    This topical report is a synopsis of the transfer of irradiated components into the Shippingport Reactor Pressure Vessel (RPV) performed at the Shippingport Station Decommissioning Project (SSDP). The information is provided as a part of the Technology Transfer Program to document the preparation activities for the decommissioning of a nuclear power reactor to be removed in one piece

  18. A Renewably Powered Hydrogen Generation and Fueling Station Community Project

    Science.gov (United States)

    Lyons, Valerie J.; Sekura, Linda S.; Prokopius, Paul; Theirl, Susan

    2009-01-01

    The proposed project goal is to encourage the use of renewable energy and clean fuel technologies for transportation and other applications while generating economic development. This can be done by creating an incubator for collaborators, and creating a manufacturing hub for the energy economy of the future by training both white- and blue-collar workers for the new energy economy. Hydrogen electrolyzer fueling stations could be mass-produced, shipped and installed in collaboration with renewable energy power stations, or installed connected to the grid with renewable power added later.

  19. Water-gas shift (WGS) Operation of Pre-combustion CO2 Capture Pilot Plant at the Buggenum IGCC

    NARCIS (Netherlands)

    Van Dijk, H.A.J.; Damen, K.; Makkee, M.; Trapp, C.

    2014-01-01

    In the Nuon/Vattenfall CO2 Catch-up project, a pre-combustion CO2 capture pilot plant was built and operated at the Buggenum IGCC power plant, the Netherlands. The pilot consist of sweet water-gas shift, physical CO2 absorption and CO2 compression. The technology performance was verified and

  20. The United States of America and the People`s Republic of China experts report on integrated gasification combined-cycle technology (IGCC)

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-12-01

    A report written by the leading US and Chinese experts in Integrated Gasification Combined Cycle (IGCC) power plants, intended for high level decision makers, may greatly accelerate the development of an IGCC demonstration project in the People`s Republic of China (PRC). The potential market for IGCC systems in China and the competitiveness of IGCC technology with other clean coal options for China have been analyzed in the report. Such information will be useful not only to the Chinese government but also to US vendors and companies. The goal of this report is to analyze the energy supply structure of China, China`s energy and environmental protection demand, and the potential market in China in order to make a justified and reasonable assessment on feasibility of the transfer of US Clean Coal Technologies to China. The Expert Report was developed and written by the joint US/PRC IGCC experts and will be presented to the State Planning Commission (SPC) by the President of the CAS to ensure consideration of the importance of IGCC for future PRC power production.

  1. Shippingport Station Decommissioning Project (SSDP). A progress report

    International Nuclear Information System (INIS)

    Mullee, G.R.; Usher, J.M.

    1986-01-01

    The Shippingport Atomic Power Station was shutdown in October, 1982 by the Plant Operator, Duquesne Light Company, for decommissioning by the US Department of Energy. The planning for decommissioning was completed in September, 1983. In September, 1984 operational responsibility for the station was transferred to the DOE's Decommissioning Operations Contractor - the General Electric Company (assisted by an integrated subcontractor, MK Ferguson Company). Significant accomplishments to date include the completion of all prerequisites for decommissioning, the removal of asbestos from plant systems, loading of irradiated reactor components into the reactor vessel for shipment, the commencement of electrical deactivations and the commencement of piping/component removal. Decontamination and waste processing are progressing in support of the project schedule. The reactor vessel will be shipped as one piece on a barge for burial at Hanford, Washington. The final release of the site is scheduled for April, 1990. A technology transfer program is being utilized to disseminate information about the project

  2. Pinon Pine power project nears start-up

    Energy Technology Data Exchange (ETDEWEB)

    Tatar, G.A. [Sierra Pacific Power Co., Reno, NV (United States); Gonzalez, M. [Foster Wheeler USA Corp., Clinton, NJ (United States); Mathur, G.K. [M.W. Kellogg Co., Houston, TX (United States)

    1997-12-31

    The IGCC facility being built by Sierra Pacific Power Company (SPPCo) at their Tracy Station in Nevada is one of three IGCC facilities being cost-shared by the US Department of Energy (DOE) under their Clean Coal Technology Program. The specific technology to be demonstrated in SPPCo`s Round Four Project, known as the Pinon Pine IGCC Project, includes the KRW air blown pressurized fluidized bed gasification process with hot gas cleanup coupled with a combined cycle facility based on a new GE 6FA gas turbine. Construction of the 100 MW IGCC facility began in February 1995 and the first firing of the gas turbine occurred as scheduled on August 15, 1996 with natural gas. Mechanical completion of the gasifier and other outstanding work is due in January 1997. Following the startup of the plant, the project will enter a 42 month operating and testing period during which low sulfur western and high sulfur eastern or midwestern coals will be processed.

  3. Market potential of IGCC for domestic power production

    International Nuclear Information System (INIS)

    Gray, D.; Tomlinson, G.; Hawk, E.; Maskew, J.

    1999-01-01

    Mitretek Systems and CONSOL Inc. have completed the first phase of a market potential study for Integrated Coal Gasification Combined Cycle (IGCC) domestic power production. The U. S. Department of Energy (DOE) funded this study. The objective of this study is to provide DOE with data to estimate the future domestic market potential of IGCC for electricity generation. Major drivers in this study are the state of technology development, feedstock costs, environmental control costs, demand growth, and dispatchability. This study examines IGCC potential for baseload power production in the Northeast U. S., an important market area by virtue of existing coal infrastructure and proximity to coal producing regions. IGCC market potential was examined for two levels of technology development as a function of natural gas price and carbon tax. This paper discusses the results of this study, including the levels of performance and cost necessary to insure competitiveness with natural gas combined cycle plants

  4. Puertollano IGCC plant. Present position and future competitiveness

    Energy Technology Data Exchange (ETDEWEB)

    Pedro Casero; Francisco Garcia-Pena

    2006-07-01

    This paper discusses the current status of the Puertollano 350 MW IGCC demonstration power plant in Spain. The experience provided by the operation of this plant during the last years is described, focussing on the core systems of the plant (gasifier, gas cleaning and gas turbines). Bottlenecks and weak points related to these systems are identified, along with the improvements. The production of hydrogen from coal at an IGCC plant is also discussed. 9 figs., 2 tabs.

  5. Demonstration of IGCC features - plant integration and syngas combustion

    Energy Technology Data Exchange (ETDEWEB)

    Hannemann, F.; Huth, M.; Karg, J.; Schiffers, U. [Siemens AG Power Generation (KWU), Erlanger/Muelheim (Germany)

    2000-07-01

    Siemens is involved in three IGCC plants in Europe that are currently in operation. Against the background of the Puertollano and Buggenum plants, some of the specific new features of fully integrated IGCC power plants are discussed, including: requirements and design features of the gas turbine syngas supply system; gas turbine operating experience with air extraction for the air separation unit from the gas turbine air compressor; and design requirements and operational features of the combustion system. 7 refs., 17 figs., 1 tab.

  6. Waste management for Shippingport Station Decommissioning Project: Extended summary

    International Nuclear Information System (INIS)

    Mullee, G.R.; Schulmeister, A.R.

    1987-01-01

    The Shippingport Station (SSDP) is demonstrating that the techniques and methodologies of waste management, which are currently employed by the nuclear industry, provide adequate management and control of waste activities for the decommissioning of a large scale nuclear plant. The SSDP has some unique aspects in that as part of the objective to promote technology transfer, multiple subcontractors are being utilized in the project. The interfaces resulting from multiple subcontractors require additional controls. Effective control has been accomplished by the use of a process control and inventory system, coupled with personnel training in waste management activities. This report summarizes the waste management plan and provides a status of waste management activities for SSDP

  7. Contaminated concrete scabbling at the Shippingport station decommissioning project

    International Nuclear Information System (INIS)

    Bauer, R.G.

    1989-01-01

    The Shippingport atomic power station was the first commercial nuclear power plant in the United States, joining the Duquesne Light Company (DLC) grid in December 1957. The Shippingport station was shut down in October 1982 and defueled in preparation for dismantling. On September 6, 1984, the Shippingport Station Decommissioning Project (SSDP) office of the US Department of Energy (DOE) assumed responsibility for the site. At turnover, there were several areas in the plant where radioactive contamination was entrained in concrete surfaces. The removal of contaminated concrete at SSDP was an important part of the decontamination to meet site release criteria, which is a major consideration in the decommissioning of nuclear power reactors. The highlights of this activity include: (1) development and application of remote scabbling tools, which effectively removed the contaminated concrete surfaces, and (2) use of scabblers minimized the removal of noncontaminated concrete by removing shallow layers of the surface and contributed to waste control, since the waste form enabled good packaging efficiency

  8. Air toxics emission from an IGCC process

    Energy Technology Data Exchange (ETDEWEB)

    Mojtahedi, W; Hovath, A [Carbona Inc, Helsinki (Finland); Hinderson, A [Vattenfall Utveckling (Sweden); Nykaenen, J; Hoffren, H [Imatran Voima Oy, Vantaa (Finland); Nieminen, M; Kurkela, E [VTT, Espoo (Finland)

    1997-10-01

    The emissions of 12 toxic trace element from a coal-fired IGCC plant were calculated based on thermodynamic equilibrium in the gas phase and some of the results published. The theoretical calculations were extended to include some other fuels as well as mixture of some of these fuels. The combustion of the product gas in the gas turbine is also considered. These simulations correspond to gasification of the fuel at 850-1050 deg C (depending on the fuel) and 1823 bar pressure. The gas composition was taken from the measured data as far as possible. In the absence of experimental data, a computer code developed for the U-Gas gasifier was used to determine the fuel gas composition. The gas was then cooled to 550 deg C in the gas cooler and filtered at this same temperature and burned in the gas turbine with an air ratio of 3.2. The results of these simulations are compared with the measured data of an experimental program designed to measure the emissions of a few selected trace elements from a 15 MW,h pressurized fluidized bed gasification pilot plant. The pilot plant was equipped with an advanced hot gas cleanup train which includes a two fluidized-bed reactor system for high-temperature, high-pressure external sulfur removal and a filtration unit housing porous, rigid ceramic candle filters. The trace element concentrations in the fuel, bottom ash, and filter ash are determined and the results compared with EPA regulatory levels

  9. H2FIRST Reference Station Design Task: Project Deliverable 2-2

    Energy Technology Data Exchange (ETDEWEB)

    Pratt, Joseph [Sandia National Lab. (SNL-NM), Albuquerque, NM (United States); Terlip, Danny [National Renewable Energy Laboratory (NREL), Golden, CO (United States); Ainscough, Chris [National Renewable Energy Laboratory (NREL), Golden, CO (United States); Kurtz, Jennifer [National Renewable Energy Laboratory (NREL), Golden, CO (United States); Elgowainy, Amgad [Argonne National Lab. (ANL), Argonne, IL (United States)

    2015-04-20

    This report presents near-term station cost results and discusses cost trends of different station types. It compares various vehicle rollout scenarios and projects realistic near-term station utilization values using the station infrastructure rollout in California as an example. It describes near-term market demands and matches those to cost-effective station concepts. Finally, the report contains detailed designs for five selected stations, which include piping and instrumentation diagrams, bills of materials, and several site-specific layout studies that incorporate the setbacks required by NFPA 2, the National Fire Protection Association Hydrogen Technologies Code. This work identified those setbacks as a significant factor affecting the ability to site a hydrogen station, particularly liquid stations at existing gasoline stations. For all station types, utilization has a large influence on the financial viability of the station.

  10. Exergoeconomic evaluation of a KRW-based IGCC power plant

    International Nuclear Information System (INIS)

    Tsatsavonis, G.; Lin, L.; TawFik, T.; Gallaspy, D.T.

    1991-01-01

    This paper reports on a study supported by the US Department of Energy, in which several design configurations of Kellogg-Rust-Westinghouse (KRW)-based Integrated Gasification-Combined-Cycle (IGCC) power plants were developed. One of these configurations was analyzed from the exergoeconomic (thermoeconomic) viewpoint. The detailed exergoeconomic evaluation identified several changes for improving the cost effectiveness of this IGCC design configuration. Based on the cost information supplied by the M.W. Kellogg Company, an attempt was made to calculate the economically optimal exergetic efficiency for some of the most important plant components. This information is currently used in plant optimization studies

  11. International Space Station Medical Projects - Full Services to Mars

    Science.gov (United States)

    Pietrzyk, R. A.; Primeaux, L. L.; Wood, S. J.; Vessay, W. B.; Platts, S. H.

    2018-01-01

    The International Space Station Medical Projects (ISSMP) Element provides planning, integration, and implementation services for HRP research studies for both spaceflight and flight analog research. Through the implementation of these two efforts, ISSMP offers an innovative way of guiding research decisions to meet the unique challenges of understanding the human risks to space exploration. Flight services provided by ISSMP include leading informed consent briefings, developing and validating in-flight crew procedures, providing ISS crew and ground-controller training, real-time experiment monitoring, on-orbit experiment and hardware operations and facilitating data transfer to investigators. For analog studies at the NASA Human Exploration Research Analog (HERA), the ISSMP team provides subject recruitment and screening, science requirements integration, data collection schedules, data sharing agreements, mission scenarios and facilities to support investigators. The ISSMP also serves as the HRP interface to external analog providers including the :envihab bed rest facility (Cologne, Germany), NEK isolation chamber (Moscow, Russia) and the Antarctica research stations. Investigators working in either spaceflight or analog environments requires a coordinated effort between NASA and the investigators. The interdisciplinary nature of both flight and analog research requires investigators to be aware of concurrent research studies and take into account potential confounding factors that may impact their research objectives. Investigators must define clear research requirements, participate in Investigator Working Group meetings, obtain human use approvals, and provide study-specific training, sample and data collection and procedures all while adhering to schedule deadlines. These science requirements define the technical, functional and performance operations to meet the research objectives. The ISSMP maintains an expert team of professionals with the knowledge and

  12. Modeling and assessment of future IGCC plant concepts with CO{sub 2} capture; Simulation und Bewertung zukuenftiger IGCC-Kraftwerkskonzepte mit CO{sub 2}-Abtrennung

    Energy Technology Data Exchange (ETDEWEB)

    Kunze, Christian A.

    2012-07-13

    The thesis focuses on the assessment of efficiency potential of future IGCC plants with CO{sub 2} capture. Starting point is a comprehensive analysis (thermodynamic, economic and exergy) of a state of the art IGCC. Additionally, five future IGCC concepts are proposed and evaluated for their efficiency potential in the mid- and long-term. The concepts showed significantly higher efficiencies up to approximately 60% and enable an almost CO{sub 2}-free operation.

  13. Thermodynamic assessment of IGCC power plants with hot fuel gas desulfurization

    International Nuclear Information System (INIS)

    Giuffrida, Antonio; Romano, Matteo C.; Lozza, Giovanni G.

    2010-01-01

    In IGCC power plants, hot gas desulfurization (HGD) represents an attractive solution to simplify syngas treatments and to improve the efficiency, potentially reducing the final cost of electricity. In the present study, the various consequences of the introduction of a HGD station in the power plant are discussed and evaluated, in comparison with conventional near-ambient temperature clean-up. Attention is paid to the potential improvements of the overall energy balance of the complete power station, along with the requirements of the sorbent regeneration process, to the influence of the desulfurization temperature and to the different solutions needed to control the NO x emissions (altered by the presence of HGD). The net performance of complete IGCC power plants (with HGD or with conventional desulfurization) were predicted, with reference to status-of-the-art solutions based on an entrained flow, dry-feed, oxygen-blown gasifier and on an advanced, FB-class combined cycle. The net efficiency experiences about 2.5% point improvement with HGD, even if a small reduction in the power output was predicted, when using the same combustion turbine. An exhaustive sensitivity analysis was carried out to evaluate the effects of different working conditions at the HGD station, e.g. desulfurization temperature and oxygen content in the gaseous stream for sorbent regeneration. According to the obtained results, these parameters have a weak influence on the efficiency. In particular, a very elevated desulfurization temperature (above 400-500 o C) does not provide decisive thermodynamic advantages. Therefore, the HGD unit optimization can be driven by technical and economical aspects and by emission abatement requirements. For instance, utilization of nitrogen for HGD sorbent regeneration (rather than for syngas dilution) and higher fuel temperature may improve the NO formation. Hence, different strategies to achieve acceptable NO x emissions (e.g. steam dilution) and their

  14. The appliction of project management in operations preparation of nuclear power station

    International Nuclear Information System (INIS)

    Tang Zhengrong; Zhang Zhixiong

    2001-01-01

    Concept, history, characteristics of the project management is introduced. Analysis is performed on the suitability of application of project management approach in nuclear power station operations preparation. Then the application of project management is detailed in order to present the readers our study and practice. Theory and practice indicate that the project management is a useful management tool for operations preparation of nuclear power station to achieve a good performance

  15. The application of project management in operations preparation of nuclear power station

    International Nuclear Information System (INIS)

    Zhang Zhixiong; Tang Zhengrong

    2000-01-01

    The author first presents a brief introduction of the concept, history, characteristics of project management. Analysis is performed on the suitability of application of project management approach in nuclear power station operations preparation. Then the application of project management is detailed in order to present the readers authors' study and practice. Theory and practice indicate that the project management is a useful management tool for operations preparation of nuclear power station to achieve a good performance

  16. Pushing forward IGCC and CO{sub 2}-free power plant technology at Siemens

    Energy Technology Data Exchange (ETDEWEB)

    Hannemann, E.; Vortmeyer, N.; Zimmermann, G. [Siemens AG, Erlangen (Germany). Power Generation

    2004-07-01

    Siemens Power Generation has entered into several R & D projects within the European Commissions' 5th and 6th Framework Programs. One objective of those projects is to develop advanced modular IGCC concepts for in-refinery energy and hydrogen supply. Additional projects are dealing with pre- and post-combustion decarbonisation technologies, which should achieve high carbon dioxide capture at low costs. In parallel, the development of advanced combustion systems including enhanced fuel flexibility and application of low BTU gases in the highly efficient Siemens V94.3A gas turbine are in progress. In further step the technology for burning hydrogen enriched gases resulting from decarbonisation in CO{sub 2} free power plants will be provided. This report documents the current status of these activities. 9 refs., 12 figs.

  17. Proceedings of the coal-fired power systems 94: Advances in IGCC and PFBC review meeting. Volume 1

    Energy Technology Data Exchange (ETDEWEB)

    McDaniel, H.M.; Staubly, R.K.; Venkataraman, V.K. [eds.

    1994-06-01

    The Coal-Fired Power Systems 94 -- Advances in IGCC and PFBC Review Meeting was held June 21--23, 1994, at the Morgantown Energy Center (METC) in Morgantown, West Virginia. This Meeting was sponsored and hosted by METC, the Office of Fossil Energy, and the US Department of Energy (DOE). METC annually sponsors this conference for energy executives, engineers, scientists, and other interested parties to review the results of research and development projects; to discuss the status of advanced coal-fired power systems and future plans with the industrial contractors; and to discuss cooperative industrial-government research opportunities with METC`s in-house engineers and scientists. Presentations included industrial contractor and METC in-house technology developments related to the production of power via coal-fired Integrated Gasification Combined Cycle (IGCC) and Pressurized Fluidized Bed Combustion (PFBC) systems, the summary status of clean coal technologies, and developments and advancements in advanced technology subsystems, such as hot gas cleanup. A keynote speaker and other representatives from the electric power industry also gave their assessment of advanced power systems. This meeting contained 11 formal sessions and one poster session, and included 52 presentations and 24 poster presentations. Volume I contains papers presented at the following sessions: opening commentaries; changes in the market and technology drivers; advanced IGCC systems; advanced PFBC systems; advanced filter systems; desulfurization system; turbine systems; and poster session. Selected papers have been processed separately for inclusion in the Energy Science and Technology Database.

  18. The Heysham 2 and Torness nuclear power station projects

    International Nuclear Information System (INIS)

    Cameron, P.J.

    1989-01-01

    At the beginning of the design of the Heysham 2 and Torness Nuclear Power Stations in the UK, it was agreed that the Hinkley Point B/Hunterston B Advanced Gas Cooled reactor design would be repeated. However, the Hinkley Point B/Hunterston B designs dated from 1964, and inevitably safety requirements had escalated in the intervening years. Furthermore, operating experience gained from Hinkley Point B/Hunterston B showed that it was desirable to make changes to particular features. Design changes were therefore included where it was considered essential to improve performance, to improve safety and to improve engineering. The resulting station designs are described. (author)

  19. Pilot Water Quality Monitoring Station in Dublin Bay : North Bank Station (NBMS), MATSIS Project Part I

    OpenAIRE

    O'Donnell, Garvan; Joyce, Eileen; Silke, Joe; O'Boyle, Shane; McGovern, Evin

    2008-01-01

    This report describes the pilot development of an autonomous monitoring station in Dublin Bay and validation of the system. It presents results from initial deployments. Sensors were deployed for testing, including an optical sensor for measuring nitrate and sensors for measurement of salinity, temperature, fluorescence and dissolved oxygen. Automated water samplers enabled periodic, remote triggered and event triggered sampling for nutrient and phytoplankton samples.

  20. THERMAL AND SINTERING CHARACTERIZATION OF A IGCC SLAG

    OpenAIRE

    Acosta, Anselmo; Iglesias, Isabel; Aineto, Mónica; Romero, Maximina; Rincón López, Jesús María

    2002-01-01

    IGCC slag is a vitreous residual product from the new induction gasification combined cycle gasification thermal power plants. In order to characterize this waste as secondary new material for the production of new glasses and glass-ceramics as construction materials; this slag from the Puertollano, Ciudad Real, Spain power plants has been fully thermally investigated. After controlled heating this waste gives rise to hematite, anorthite, and cristobalite crystallized materials.

  1. Hydrogen fueling stations in Japan hydrogen and fuel cell demonstration project

    International Nuclear Information System (INIS)

    Koseki, K.; Tomuro, J.; Sato, H.; Maruyama, S.

    2004-01-01

    A new national demonstration project of fuel cell vehicles, which is called Japan Hydrogen and Fuel Cell Demonstration Project (JHFC Project), has started in FY2002 on a four-year plan. In this new project, ten hydrogen fueling stations have been constructed in Tokyo and Kanagawa area in FY2002-2003. The ten stations adopt the following different types of fuel and fueling methods: LPG reforming, methanol reforming, naphtha reforming, desulfurized-gasoline reforming, kerosene reforming, natural gas reforming, water electrolysis, liquid hydrogen, by-product hydrogen, and commercially available cylinder hydrogen. Approximately fifty fuel cell passenger cars and a fuel cell bus are running on public roads using these stations. In addition, two hydrogen stations will be constructed in FY2004 in Aichi prefecture where The 2005 World Exposition (EXPO 2005) will be held. The stations will service eight fuel cell buses used as pick-up buses for visitors. We, Engineering Advancement Association of Japan (ENAA), are commissioned to construct and operate a total of twelve stations by Ministry of Economy Trade and Industry (METI). We are executing to demonstrate or identify the energy-saving effect, reduction of the environmental footprint, and issues for facilitating the acceptance of hydrogen stations on the basis of the data obtained from the operation of the stations. (author)

  2. Fuel Retrieval Sub-Project (FRS) Stuck Fuel Station Performance Test Data Report

    International Nuclear Information System (INIS)

    THIELGES, J.R.

    2000-01-01

    This document provides the test data report for Stuck Fuel Station Performance Testing in support of the Fuel Retrieval Sub-Project. The stuck fuel station was designed to provide a means of cutting open a canister barrel to release fuel elements, etc

  3. [Shippingport Station Decommissioning Project]: FY 1987 annual progress report, October 1, 1986-September 30, 1987

    International Nuclear Information System (INIS)

    1988-01-01

    This report presents progress on the Shippingport Station Decommissioning Project for FY 1987. There are two main topics: Project Management and Decommissioning Project Activities. Changes from technical and managerial concepts developed in the original Decommissioning Plan are presented with the related technical, economic, or schedule considerations. 3 refs., 9 figs., 4 tabs

  4. Shippingport Station Decommissioning Project: FY 1986 annual progress report, October 1, 1985 through September 30, 1986

    International Nuclear Information System (INIS)

    1987-01-01

    This report presents progress on the Shippingport Station Decommissioning Project for FY 1986. There are two main topics: Project Management and Decommissioning Project Activities. Changes from technical and managerial concepts developed in the original Decommissioning Plan are presented with the related technical, economic, or schedule considerations. 9 refs., 4 figs., 3 tabs

  5. Shippingport Station Decommissioning Project: FY 1988 annual progress report, October 1, 1987--September 30, 1988

    International Nuclear Information System (INIS)

    1989-01-01

    This report presents progress on the Shippingport Station Decommissioning Project for FY 1988. There are two main topics: Project Management and Decommissioning Project Activities. Changes from technical and managerial concepts developed in the original Decommissioning Plan are presented with the related technical, economic, or schedular considerations. 4 refs., 17 figs., 2 tabs

  6. A case-based reasoning approach for estimating the costs of pump station projects

    Directory of Open Access Journals (Sweden)

    Mohamed M. Marzouk

    2011-10-01

    Full Text Available The effective estimation of costs is crucial to the success of construction projects. Cost estimates are used to evaluate, approve and/or fund projects. Organizations use some form of classification system to identify the various types of estimates that may be prepared during the lifecycle of a project. This research presents a parametric-cost model for pump station projects. Fourteen factors have been identified as important to the influence of the cost of pump station projects. A data set that consists of forty-four pump station projects (fifteen water and twenty-nine waste water are collected to build a Case-Based Reasoning (CBR library and to test its performance. The results obtained from the CBR tool are processed and adopted to improve the accuracy of the results. A numerical example is presented to demonstrate the development of the effectiveness of the tool.

  7. Siemens sees a future for IGCC - and now it has the technology

    Energy Technology Data Exchange (ETDEWEB)

    Schmid, C.; Hannemann, F. [Siemens Fuel Gasification Technology, Freiberg (Germany)

    2007-10-15

    About 18 months ago Siemens became a key player in the gasification business through its acquisition of Freiberg based Future Energy and its GSP entrained flow technology, now called SFG (Siemens Fuel Gasification). Developed at Schwarze Pumpe in Eastern Germany over many years, a particular attraction of the process is its ability to use low rank fuels such as lignite, with a robust gasifier wall concept a 'cooling screen' that avoids the use of troublesome refractories. The article explains the SFG gasifier technology. It is ideally suited for coal-fueled IGCC power plants with integrated CO{sub 2} capture, especially for low-rank fuels. SFG has been ordered or pre-selected for a number of projects in China, North America and elsewhere. 5 figs.

  8. Comparison of Shell, Texaco, BGL and KRW gasifiers as part of IGCC plant computer simulations

    Energy Technology Data Exchange (ETDEWEB)

    Zheng, L.; Furimsky, E. [Natural Resources Canada, Ottawa, ON (Canada). CANMET Energy Technology Centre

    2005-07-01

    The performances of four IGCC plants employing Shell, Texaco, BGL and KRW gasifiers were simulated using ASPEN Plus software for three different feeds. Performance analyses and comparisons of all four IGCC plants were performed based on the established data bank from the simulation. Discussions were focused on gas compositions, gasifier selection and overall performance.

  9. Developments in the pre-combustion CO2 capture pilot plant at the Buggenum IGCC

    NARCIS (Netherlands)

    Damen, K.; Gnutek, R.; Kaptein, J.; Nannan, N.R.; Oyarzun, B.; Trapp, C.; Colonna, P.; Van Dijk, E.; Gross, J.; Bardow, A.

    2011-01-01

    N.V. Nuon (part of the Vattenfall Group) operates an IGCC in Buggenum and is developing a multi-fuel IGCC with CO2 capture and storage (Nuon Magnum) in Eemshaven, the Netherlands. In order to prepare for large-scale application of CO2 capture and storage, a CO2 capture pilot plant is constructed at

  10. Quality improvement process pilot project at Gallagher station

    International Nuclear Information System (INIS)

    Vondielingen, D.E.

    1992-01-01

    A Quality Improvement Process was piloted at Gallagher station in 1990 to address issues of two Electric System Strategy Group (ESSG) goals. Darrell McElravy headed a group to address quality, productivity and prove and Judy Rushing headed a group to address innovation and recognition. These groups combined when a process was identified that could address both issues. The process was designed for PSI Energy by Business Incentives and is an incentive-based quality improvement process that seeks employee involvement to identify inhibitors t performance and to establish a method to eliminate the problem. Performance goals were also established that help focus efforts to improve performance and reward employees for their efforts

  11. PROJECT OF POLLUTANTS SEPARATOR FROM THE GAS STATION

    Directory of Open Access Journals (Sweden)

    Barbara Kościelnik

    2016-06-01

    Full Text Available Oily wastewater are dangerous for the environment, because they can contaminate ground water or surface, which can lead to contamination of the biosystem or poisoning of humans and animals. The treatment plant of this kind may include petroleum products or substances derived from natural gas, crude oil, asphalt or natural wax. Of course, in the wastewater oily you cannot forget about vegetable oils used in catering. Waste water of this type to be cleaned are subjected to the following processes: flotation, sedimentation, filtration, flowing out, thermal methods, biodegradation, adsorption or chemical and thermal methods to destabilize the emulsion. The aim of this study was to design a separator pollution from the gas station. We present the investment and operating costs. In designing the system chosen individual process units based on the requirements of the quality of wastewater specified in PN - EU 858.

  12. Recovery Act Hospital Alteration Project at Naval Air Station Jacksonville

    Science.gov (United States)

    2010-12-07

    QMAD Quantitative Methods and Analysis Division RLF Rogers Lovelock & Fritz, Incorporated SE Southeast SF Square Feet SOW Statement of Work TMA TRICARE...Finally, the contractor, Rogers Lovelock & Fritz, Incorporated, reported the recipient information required by the Recovery Act. What We Recommend...contractor, Rogers Lovelock & Fritz, Incorporated (RLF), reported the recipient information required by the Recovery Act. Planning: Initially, Project

  13. Geopolitical model of investment power station construction project implementation

    Science.gov (United States)

    Malafeyev, Oleg; Farvazov, Konstantin; Zenovich, Olga; Zaitseva, Irina; Kostyukov, Konstantin; Svechinskaya, Tatiana

    2018-04-01

    Two geopolitical actors implement a geopolitical project that involves transportaion and storage of some commodities. They interact with each other through a transport network. The network consists of several interconnected vertices. Some of the vetrices are trading hubs, storage spaces, production hubs and goods buyers. Actors wish to satify the demand of buyers and recieve the highest possible profit subject to compromise solution principle. A numerical example is given.

  14. Information management for nuclear power stations: project description

    International Nuclear Information System (INIS)

    Halpin, D.W.

    1978-03-01

    A study of the information management structure required to support nuclear power plant construction was performed by a joint university-industry group under the sponsorship of the Department of Energy (DOE), formerly the Energy Research and Development Administration (ERDA). The purpose of this study was (1) to study methods for the control of information during the construction and start-up of nuclear power plants, and (2) identify those data elements intrinsic to nuclear power plants which must be maintained in a structured format for quick access and retrieval. Maintenance of the massive amount of data needed for control of a nuclear project during design, procurement, construction, start-up/testing, and operational phases requires a structuring which allows immediate update and retrieval based on a wide variety of access criteria. The objective of the research described has been to identify design concepts which support the development of an information control system responsive to these requirements. A conceptual design of a Management Information Data Base System which can meet the project control and information exchange needs of today's large nuclear power plant construction projects has been completed and an approach recommended for development and implementation of a complete operational system

  15. CERAMIC MEMBRANE ENABLING TECHNOLOGY FOR IMPROVED IGCC EFFICIENCY

    International Nuclear Information System (INIS)

    Ravi Prasad

    2000-01-01

    The objective of this program is to conduct a technology development program to advance the state-of-the-art in ceramic Oxygen Transport Membranes (OTM) to the level required to produce step change improvements in process economics, efficiency, and environmental benefits for commercial IGCC systems and other applications. The IGCC program is focused on addressing key issues in materials, processing, manufacturing, engineering and system development that will make the OTM a commercial reality. The objective of the OTM materials development task is to identify a suitable material that can be formed into a thin film to produce the target oxygen flux. This requires that the material have an adequate permeation rate, and thermo-mechanical and thermo-chemical properties such that the material is able to be supported on the desired substrate and sufficient mechanical strength to survive the stresses involved in operation. The objective of the composite OTM development task is to develop the architecture and fabrication techniques necessary to construct stable, high performance, thin film OTMs supported on suitable porous, load bearing substrates. The objective of the process development task of this program to demonstrate the program objectives on a single OTM tube under test conditions simulating those of the optimum process cycle for the power plant

  16. Pre-Combustion Capture of CO2 in IGCC Plants

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2011-12-15

    Pre-combustion capture involves reacting a fuel with oxygen or air and/or steam to give mainly a 'synthesis gas (syngas)' or 'fuel gas' composed of carbon monoxide and hydrogen. The carbon monoxide is reacted with steam in a catalytic reactor, called a shift converter, to produce CO2 and more hydrogen. CO2 is then separated, usually by a physical or chemical absorption process, resulting in a hydrogen-rich fuel which can be used in many applications, such as boilers, furnaces, gas turbines, engines and fuel cells. Pre-combustion capture is suitable for use in integrated gasification combined cycle (IGCC) plants especially since the CO2 partial pressures in the fuel gas are higher than in the flue gas. After the introduction there follows a short discussion of the water-gas shift (WGS) reaction. This is followed by chapters on the means of CO2 capture by physical and chemical solvents, solid sorbents, and membranes. The results and conclusions of techno-economic studies are introduced followed by a look at some of the pilot and demonstration plants relevant to pre-combustion capture in IGCC plants.

  17. Integrated assessment of IGCC power generation technology with carbon capture and storage (CCS)

    International Nuclear Information System (INIS)

    Cormos, Calin-Cristian

    2012-01-01

    IGCC (Integrated Gasification Combined Cycle) is a power generation technology in which the solid feedstock is partially oxidized with oxygen and steam to produce syngas. In a conventional IGCC design without carbon capture, the syngas is purified for dust and hydrogen sulphide removal and then it is sent to a CCGT (Combined Cycle Gas Turbine) for power generation. CCS (Carbon capture and storage) technologies are expected to play a significant role in the coming decades for reducing the greenhouse gas emissions. IGCC is one of the power generation technologies having the highest potential to capture CO 2 with low penalties in term of plant energy efficiency, capital and operational costs. This paper investigates the most important techno-economic and environmental indicators (e.g. power output, ancillary consumption, energy efficiency, CW consumption, normalised mass and energy balances and plant construction materials, capital and O and M (operational and maintenance) costs, specific CO 2 emissions, cost of electricity, CO 2 removal and avoidance costs etc.) for IGCC with CCS. Coal-based IGCC cases produce around 400–450 MW net electricity with 90% carbon capture rate. Similar IGCC plants without CCS were presented as references. Future IGCC developments for energy vectors poly-generation were also presented. -- Highlights: ► Techno-economical evaluations of coal-based IGCC power generation with CCS. ► Model development for capital, O and M, CO 2 capture costs and cash flow estimations. ► Technical and economic investigations of key plant design characteristics. ► Evaluations of carbon capture options for IGCC power generation technology.

  18. Shippingport Station Decommissioning Project: Removal of piping and equipment and removal of primary system components

    International Nuclear Information System (INIS)

    1989-01-01

    This report is a technical synopsis of the removal of contaminated and non-contaminated piping and equipment from the Shippingport Station Decommissioning Project (SSDP). The information is provided as a part of the Technology Transfer Program to document dismantling activities in support of reactor decommissioning. 5 refs., 29 figs., 4 tabs

  19. Exergetic comparison of two KRW-based IGCC power plants

    International Nuclear Information System (INIS)

    Tsatsaronis, G.; Tawfik, T.; Lin, L.; Gallaspy, D.T.

    1991-01-01

    In studies supported by the U.S. Department of Energy and the Electric Power Research Institute, several design configurations of Kellogg-Rust-Westinghouse (KRW)-based Integrated Gasification-Combined-Cycle (IGCC) power plants were developed. Two of these configurations are compared in this paper, from the exergetic viewpoint. The exergetic comparison identifies the causes of performance differences between the two cases: differences in the exergy destruction of the gasification system, the gas turbine system, and the gas cooling process, as well as differences in the exergy loss accompanying the solids to disposal stream. The potential for using oxygen-blown versus air-blown KRW gasifiers, and hot gas versus cold gas cleanup processes is evaluated

  20. CO{sub 2}-capture in coal based IGCC power plants

    Energy Technology Data Exchange (ETDEWEB)

    Van Aart, F.; Fleuren, W.; Kamphuis, H.; Ploumen, P.; Jelles, S. [KEMA, Arnhem (Netherlands)

    2007-07-01

    The paper discusses IGCC with carbon capture and storage (CCS), both for retrofit and capture ready plants. The penalties for carbon dioxide capture are given, along with its effect on CAPEX and OPEC costs. 3 refs., 9 figs.

  1. Environmental Assessment for Lignite Fuel Enhancement Project, Coal Creek Station, Great River Energy, Underwood, North Dakota

    Energy Technology Data Exchange (ETDEWEB)

    N/A

    2004-01-16

    The US Department of Energy (DOE) has prepared this EA to assess the environmental impacts of the commercial application of lignite fuel enhancement. The proposed demonstration project would be implemented at Great River Energy's Coal Creek Station near Underwood, North Dakota. The proposed project would demonstrate a technology to increase the heating value of lignite and other high-moisture coals by reducing the moisture in the fuels. Waste heat that would normally be sent to the cooling towers would be used to drive off a percentage of the moisture contained within the lignite. Application of this technology would be expected to boost power-generating efficiencies, provide economic cost savings for lignite and sub-bituminous power plants, and reduce air emissions. The proposed project would be constructed on a previously disturbed site within the Coal Creek Station and no negative impacts would occur in any environmental resource area.

  2. Enabling Technology for Monitoring & Predicting Gas Turbine Health & Performance in IGCC Powerplants

    Energy Technology Data Exchange (ETDEWEB)

    Kenneth A. Yackly

    2005-12-01

    The ''Enabling & Information Technology To Increase RAM for Advanced Powerplants'' program, by DOE request, was re-directed, de-scoped to two tasks, shortened to a 2-year period of performance, and refocused to develop, validate and accelerate the commercial use of enabling materials technologies and sensors for coal/IGCC powerplants. The new program was re-titled ''Enabling Technology for Monitoring & Predicting Gas Turbine Health & Performance in IGCC Powerplants''. This final report summarizes the work accomplished from March 1, 2003 to March 31, 2004 on the four original tasks, and the work accomplished from April 1, 2004 to July 30, 2005 on the two re-directed tasks. The program Tasks are summarized below: Task 1--IGCC Environmental Impact on high Temperature Materials: The first task was refocused to address IGCC environmental impacts on high temperature materials used in gas turbines. This task screened material performance and quantified the effects of high temperature erosion and corrosion of hot gas path materials in coal/IGCC applications. The materials of interest included those in current service as well as advanced, high-performance alloys and coatings. Task 2--Material In-Service Health Monitoring: The second task was reduced in scope to demonstrate new technologies to determine the inservice health of advanced technology coal/IGCC powerplants. The task focused on two critical sensing needs for advanced coal/IGCC gas turbines: (1) Fuel Quality Sensor to rapidly determine the fuel heating value for more precise control of the gas turbine, and detection of fuel impurities that could lead to rapid component degradation. (2) Infra-Red Pyrometer to continuously measure the temperature of gas turbine buckets, nozzles, and combustor hardware. Task 3--Advanced Methods for Combustion Monitoring and Control: The third task was originally to develop and validate advanced monitoring and control methods for coal/IGCC gas

  3. Recycling of residual IGCC slags and their benefits as degreasers in ceramics.

    Science.gov (United States)

    Iglesias Martín, I; Acosta Echeverría, A; García-Romero, E

    2013-11-15

    This work studies the evolution of IGCC slag grains within a ceramic matrix fired at different temperatures to investigate the effect of using IGCC slag as a degreaser. Pressed ceramic specimens from two clay mixtures are used in this study. The M1 mixture is composed of standard clays, whereas the M2 mixture is composed of the same clay mixture as M1 mixture but contains 15% by weight IGCC slag. The amount of IGCC slag added coincides with the amount of slag typically used as a degreaser in the ceramic industry. Specimens are fired at 950 °C, 1000 °C, 1050 °C, 1100 °C and 1150 °C. The mineralogical composition and the IGCC slag grain shape within the ceramic matrix are determined by X-ray diffraction, polarized light microscopy and scanning electron microscopy. The results reveal that the surface of the slag grains is welded to the ceramic matrix while the quartz grains are separated, which causes increased water absorption and reduces the mechanical strength. IGCC slag, however, reduces water absorption. This behaviour is due to the softening temperature of the slag. This property is quite important from an industrial viewpoint because IGCC slag can serve as an alternative to traditional degreasing agents in the ceramic building industry. Additionally, using IGCC slag allows for the transformation of waste into a secondary raw material, thereby avoiding disposal at landfills; moreover, these industrial wastes are made inert and improve the properties of ceramics. Copyright © 2013 Elsevier Ltd. All rights reserved.

  4. Dynamic simulation of operating cases and malfunctions of an IGCC power plant system

    Energy Technology Data Exchange (ETDEWEB)

    Koch, I.; Hannemann, F. [Siemens AG, Power Generation (KWU), Erlangen (Germany); Hoffmann, U. [Technische Univ. Clausthal, Clausthal-Zellerfeld (Germany). Inst. fuer Chemische Verfahrenstechnik

    1999-07-01

    Fully integrated IGCC plants consist of several units. This novel integration of various plant systems places stiff new requirements on power plant design, as prediction of operating and faulted behavior is made more difficult by many different interactions. This is especially the case for the gas turbine fuel system in an IGCC power plant, as it affects and is affected by all of the other major plant systems. (orig.)

  5. Shippingport Station Decommissioning Project: FYs 1984-1985 annual progress report, October 1, 1983 through September 30, 1985

    International Nuclear Information System (INIS)

    1987-01-01

    This report presents progress on the Shippingport Station Decommissioning Project for FYs 1984-85. There are three main topics: project management, decommissioning project activities, and issues of concern. The project purpose is demonstration of nuclear plant decommissioning and dismantlement operations in an environment of current industry practices. 8 refs., 8 figs., 2 tabs

  6. Enabling Technology for Monitoring & Predicting Gas Turbine Health & Performance in COAL IGCC Powerplants

    Energy Technology Data Exchange (ETDEWEB)

    Kenneth A. Yackly

    2004-09-30

    The ''Enabling & Information Technology To Increase RAM for Advanced Powerplants'' program, by DOE request, has been re-directed, de-scoped to two tasks, shortened to a 2-year period of performance, and refocused to develop, validate and accelerate the commercial use of enabling materials technologies and sensors for Coal IGCC powerplants. The new program has been re-titled as ''Enabling Technology for Monitoring & Predicting Gas Turbine Health & Performance in IGCC Powerplants'' to better match the new scope. This technical progress report summarizes the work accomplished in the reporting period April 1, 2004 to August 31, 2004 on the revised Re-Directed and De-Scoped program activity. The program Tasks are: Task 1--IGCC Environmental Impact on high Temperature Materials: This first materials task has been refocused to address Coal IGCC environmental impacts on high temperature materials use in gas turbines and remains in the program. This task will screen material performance and quantify the effects of high temperature erosion and corrosion of hot gas path materials in Coal IGCC applications. The materials of interest will include those in current service as well as advanced, high-performance alloys and coatings. Task 2--Material In-Service Health Monitoring: This second task develops and demonstrates new sensor technologies to determine the in-service health of advanced technology Coal IGCC powerplants, and remains in the program with a reduced scope. Its focus is now on only two critical sensor need areas for advanced Coal IGCC gas turbines: (1) Fuel Quality Sensor for detection of fuel impurities that could lead to rapid component degradation, and a Fuel Heating Value Sensor to rapidly determine the fuel heating value for more precise control of the gas turbine, and (2) Infra-Red Pyrometer to continuously measure the temperature of gas turbine buckets, nozzles, and combustor hardware.

  7. NASA Systems Autonomy Demonstration Project - Development of Space Station automation technology

    Science.gov (United States)

    Bull, John S.; Brown, Richard; Friedland, Peter; Wong, Carla M.; Bates, William

    1987-01-01

    A 1984 Congressional expansion of the 1958 National Aeronautics and Space Act mandated that NASA conduct programs, as part of the Space Station program, which will yield the U.S. material benefits, particularly in the areas of advanced automation and robotics systems. Demonstration programs are scheduled for automated systems such as the thermal control, expert system coordination of Station subsystems, and automation of multiple subsystems. The programs focus the R&D efforts and provide a gateway for transfer of technology to industry. The NASA Office of Aeronautics and Space Technology is responsible for directing, funding and evaluating the Systems Autonomy Demonstration Project, which will include simulated interactions between novice personnel and astronauts and several automated, expert subsystems to explore the effectiveness of the man-machine interface being developed. Features and progress on the TEXSYS prototype thermal control system expert system are outlined.

  8. Environmental Assessment for the Warren Station externally fired combined cycle demonstration project

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-04-01

    The proposed Penelec project is one of 5 projects for potential funding under the fifth solicitation under the Clean Coal Technology program. In Penelec, two existing boilers would be replaced at Warren Station, PA; the new unit would produce 73 MW(e) in a combined cycle mode (using both gas-fired and steam turbines). The project would fill the need for a full utility-size demonstration of externally fire combined cycle (EFCC) technology as the next step toward commercialization. This environmental assessment was prepared for compliance with NEPA; its purpose is to provide sufficient basis for determining whether to prepare an environmental impact statement or to issue a finding of no significant impact. It is divided into the sections: purpose and need for proposed action; alternatives; brief description of affected environment; environmental consequences, including discussion of commercial operation beyond the demonstration period.

  9. Gas expanders at M/R Stations in the natural gas distribution network. Pre-project, subreport; Gasexpandere paa distributionsnettets M/R-stationer. Forprojekt, delrapport

    Energy Technology Data Exchange (ETDEWEB)

    Rasmussen, Niels Bjarne

    2010-05-15

    Danish Gas Technology Centre has been carrying out a feasibility project to clarify the possibilities of installing gas expanders at M/R-stations (Measuring and Regulating) in the Distribution system of the natural gas grid. A large number of such expanders are installed around the world. The novelty of this project is to use a heat pump to perform the necessary heating of the gas before the expander, and to ''export'' to the electricity grid the remaining electricity from the generator connected to the expander. The present project includes the small M/R-stations at the gas Distribution grid where pressure is reduced from 40 or 20 bar to 4 bar. The preliminary project (year 1 of project) has investigated whether components for such smaller systems can be found, and it has investigated prices for different quantities. A technical feasibility study has been done. Also, preliminary calculations of payback times has been carried out. A large potential of CO{sub 2}-reduction is present with this technology based on saving of natural gas combustion and on new electricity production displacing existing production without any use of primary energy. The main results and conclusions are: 1) There are component suppliers for expander systems suitable to the size of distribution network M/R stations. 2) Pressure regulators provided at the stations are laid out with significant overcapacity, enabling a simplified installation of the expander systems. 3) If the system is being rolled out across the Danish distribution grid, the realistic saving potential is approx. 2.3 million Nm3 of gas per year and a production of almost 40 million kWh of electricity. 4) If the price is 0.60 DKK/kWh for electricity sold, the simple pay-back is 6-7 years on average, covering a variation from 3 to 16 years at the various stations. The smallest stations are omitted. The best stations covering more than half of the gas flow have a pay-back time between 3 and 6 years. 5) The

  10. Shippingport Station Decommissioning Project (SSDP): configuration control system and project activity controls

    International Nuclear Information System (INIS)

    Mullee, G.R.

    1986-01-01

    The SSDP has been using a Configuration Control system as a significant element in the management plan for the safe and effective performance of the project. The objective of the Configuration Control system is to control the physical plant configuration, system status, work schedules, status tracking, and day-to-day problem resolution. Prior to the Decommissioning Operations Contractor (DOC) assuming operational responsibility for the Shippingport Plant, an assessment was made of the status of the configuration of the systems and related documentation. Action was taken as required to match the operating procedures and system documentation with the actual physical condition of the plant. During the first stage of the project, planning was put in place for subsequent decommissioning activities. This planning included defining organizational responsibilities, completing the necessary project instructions and procedures, and doing the planning and scheduling for the subsequent decommissioning phase activities. Detailed instructions for the performance of the various decommissioning tasks were prepared. Prior to the start of any work on a given Activity Package, a Work Authorization is required. The Work Authorization form provides a complete checklist to ensure that all necessary prerequisites are completed. A computerized Communications Configuration Control Information system monitors status including information on system status, tag-outs, radiological work permits, etc. An ongoing effort is being directed toward maintaining operating instructions and system schematics, etc. current as the Plant configuration changes. The experience with the Configuration Control System to date has been favorable

  11. Recovery of flue gas energy in heat-integrated gasification combined cycle (IGCC) power plants using the contact economizer system

    CSIR Research Space (South Africa)

    Madzivhandila, VA

    2011-03-01

    Full Text Available (flue gas) stream of a heat-integrated gasification combined cycle (IGCC) design of the Elcogas plant adopted from previous studies. The underlying support for this idea was the direct relationship between efficiency of the IGCC and the boiler feedwater...

  12. Briefing Book, Interagency Geothermal Coordinating Council (IGCC) Meeting of April 28, 1988

    Energy Technology Data Exchange (ETDEWEB)

    None

    1988-04-28

    The IGCC of the U.S. government was created under the intent of Public Law 93-410 (1974) to serve as a forum for the discussion of Federal plans, activities, and policies that are related to or impact on geothermal energy. Eight Federal Departments were represented on the IGCC at the time of this meeting. The main presentations in this report were on: Department of Energy Geothermal R&D Program, the Ormat binary power plant at East Mesa, CA, Potential for direct use of geothermal at Defense bases in U.S. and overseas, Department of Defense Geothermal Program at China Lake, and Status of the U.S. Geothermal Industry. The IGCC briefing books and minutes provide a historical snapshot of what development and impact issues were important at various time. (DJE 2005)

  13. A comparison of improved power plant technologies on lignite with (PFBC) and (IGCC) cycles

    International Nuclear Information System (INIS)

    Cherepnalkovski, Ilija

    1997-01-01

    Technologies and process diagrams descriptions for PFBC (Pressurised Fluidized Bed Combustion) and IGCC (Integrated Gasification Combined Cycle) are presented as for improved cycles with modern clean coal technologies, the most popular currently. A special attention is paid to the possibilities for Macedonian lignites use on the power plants with PFBC and IGCC cycles. The comparison of the above mention technologies has been done particularly on the desulfurization, NO x reduction, ash elimination and its use in the building and construction industries. A comparison between the power plants with PFBC and IGCC cycles is made by the following criteria: cycle efficiency, desulfurization and nitrogen oxides reduction, power plant complexity and their cost, as well as plant reliability. (Author)

  14. International remote monitoring project Argentina Nuclear Power Station Spent Fuel Transfer Remote Monitoring System

    International Nuclear Information System (INIS)

    Schneider, S.; Lucero, R.; Glidewell, D.

    1997-01-01

    The Autoridad Regulataria Nuclear (ARN) and the United States Department of Energy (DOE) are cooperating on the development of a Remote Monitoring System for nuclear nonproliferation efforts. A Remote Monitoring System for spent fuel transfer will be installed at the Argentina Nuclear Power Station in Embalse, Argentina. The system has been designed by Sandia National Laboratories (SNL), with Los Alamos National Laboratory (LANL) and Oak Ridge National Laboratory (ORNL) providing gamma and neutron sensors. This project will test and evaluate the fundamental design and implementation of the Remote Monitoring System in its application to regional and international safeguards efficiency. This paper provides a description of the monitoring system and its functions. The Remote Monitoring System consists of gamma and neutron radiation sensors, RF systems, and video systems integrated into a coherent functioning whole. All sensor data communicate over an Echelon LonWorks Network to a single data logger. The Neumann DCM 14 video module is integrated into the Remote Monitoring System. All sensor and image data are stored on a Data Acquisition System (DAS) and archived and reviewed on a Data and Image Review Station (DIRS). Conventional phone lines are used as the telecommunications link to transmit on-site collected data and images to remote locations. The data and images are authenticated before transmission. Data review stations will be installed at ARN in Buenos Aires, Argentina, ABACC in Rio De Janeiro, IAEA Headquarters in Vienna, and Sandia National Laboratories in Albuquerque, New Mexico. 2 refs., 2 figs

  15. Assessment of oxy-fuel, pre- and post-combustion-based carbon capture for future IGCC plants

    International Nuclear Information System (INIS)

    Kunze, Christian; Spliethoff, Hartmut

    2012-01-01

    Highlights: ► Hot gas cleanup is a highly favorable technology for all selected IGCC concepts. ► Proposed high pressure IGCC with membrane reactor enables direct CO 2 condensation. ► IGCC with OTM and carbonate looping enable significant synergy effects. ► Combining IGCC and oxy-fuel is technically challenging but energetically favorable. ► All selected IGCC concepts are able to realize CO 2 capture rates up to 99%. -- Abstract: Environmental damage due to the emission of greenhouse gases from conventional coal-based power plants is a growing concern. Various carbon capture strategies to minimize CO 2 emissions are currently being investigated. Unfortunately, the efficiency drop due to de-carbonization is still significant and the capture rate is limited. Therefore three future hard coal IGCC concepts are assessed here, applying emerging technologies and various carbon capture approaches. The advanced pre-combustion capture concept is based on hot gas clean-up, membrane-enhanced CO conversion and direct CO 2 condensation. The concept reached a net efficiency of 45.1% (LHV), representing an improvement of 6.46% compared to the conventional IGCC base case. The second IGCC concept, based on post-combustion capture via calcination–carbonation loops, hot gas clean-up and oxygen membranes, showed a net efficiency of 45.87% (LHV). The third IGCC concept applies hot gas clean-up and combustion of the unconverted fuel gas using pure oxygen. The oxygen is supplied by an integrated oxygen membrane. The combination of IGCC and oxy-fuel process reached a net efficiency of 45.74% (LHV). In addition to their increased efficiency, all of the concepts showed significantly improved carbon capture rates up to 99%, resulting in virtually carbon-free fossil power plants.

  16. Recovery of flue gas energy in heat integrated IGCC power plants using the contact economizer system

    CSIR Research Space (South Africa)

    Madzivhandila, V

    2010-10-01

    Full Text Available Asia Pacific Confederation of APCChE 2010 Chemical Engineering Congress October 5-8, 2010, Taipei � �� Recovery of flue gas energy in heat integrated IGCC power plants using the contact economizer system Vhutshilo Madzivhandilaa, Thokozani... temperature and the thermal efficiency of the plant. The 13th Asia Pacific Confederation of APCChE 2010 Chemical Engineering Congress October 5-8, 2010, Taipei � �� 1. Introduction The IGCC (Integrated Gasification Combined Cycle) is one...

  17. Development of low head Kaplan turbine for power station rehabilitation project

    Science.gov (United States)

    Lim, S. M.; Ohtake, N.; Kurosawa, S.; Suzuki, T.; Yamasaki, T.; Nishi, H.

    2012-11-01

    This paper presents the latest Kaplan turbine rehabilitation project for Funagira Power Station in Japan completed by J-POWER Group in collaboration with Toshiba Corporation. Area of rehabilitation was restricted to guide vane and runner. The main goal of the rehabilitation project was to expand the operating range of the existing turbine in terms of discharge and power with high operational stability, low noise as well as high cavitation performance. Computational Fluids Dynamics and model test were used to optimize the shape of guide vane and runner in development stage. Finally, field tests and runner inspection were carried out to confirm the performance of the new turbine. It was found that the new turbine has excellent performance in efficiency, power output, operational stability compared with existing turbine. Moreover, no sign of cavitation on the runner blade surface was observed after 5078 hours of operation near 100% load.

  18. Development of low head Kaplan turbine for power station rehabilitation project

    International Nuclear Information System (INIS)

    Lim, S M; Ohtake, N; Kurosawa, S; Suzuki, T; Yamasaki, T; Nishi, H

    2012-01-01

    This paper presents the latest Kaplan turbine rehabilitation project for Funagira Power Station in Japan completed by J-POWER Group in collaboration with Toshiba Corporation. Area of rehabilitation was restricted to guide vane and runner. The main goal of the rehabilitation project was to expand the operating range of the existing turbine in terms of discharge and power with high operational stability, low noise as well as high cavitation performance. Computational Fluids Dynamics and model test were used to optimize the shape of guide vane and runner in development stage. Finally, field tests and runner inspection were carried out to confirm the performance of the new turbine. It was found that the new turbine has excellent performance in efficiency, power output, operational stability compared with existing turbine. Moreover, no sign of cavitation on the runner blade surface was observed after 5078 hours of operation near 100% load.

  19. Project of a Near-Real-Time Sismo-acoustic Submarine Station for offshore monitoring (NRTSSS)

    Science.gov (United States)

    D'Anna, G.; Calore, D.; Mangano, G.; D'Alessandro, A.; Favali, P.

    2011-12-01

    The INGV seismic network ensures reliable and continuous monitoring of the Italian territory. However, the peculiarity of the Italian peninsula, characterised by an intense offshore geodynamic and seismic activity, requires the extension of the seismic monitoring to the sea. The aim of this project is: - to identify bottleneck is related to the construction, installation and use of underwater seismic station; - to define the most appropriate and low-cost architecture to guarantee the minimum functionality required for a seismic station. In order to obtain reliable seafloor seismic signals integrated to land-based network, the requirements to be fulfill are: - an acceptable coupling with the seabed; - the orientation of the components with respect to the magnetic North and to the verticality; - the correct time stamp of the data; - the data transfer to the land for the integration. Currently, the optimal solution for offshore seismic station is a cable connection to power and real-time data transfer, like the case of Western Ionian Sea cabled observatory, one of the operative node of the EMSO research infrastructure (European Multidisciplinary Seafloor and water column Observatory, http://emso-eu.org). But in the Mediterranean many seismic areas are located a few tens-hundreds of miles from the coast and cabled solutions are not feasible essentially for economic reasons. For this kind of installations EMSO research infrastructure foresees no-cabled solution, that requires a surface buoy deployed in the vicinity seafloor modules.This project plans to develop a surface buoy equipped with autonomous power supply system to power also the seafloor platforms and two-way communication system enabling the data transfer through latest generation of broadband radio communication or satellite link (Fig. 1). All the components of the prototype system are described.

  20. Different scenarios to reduce greenhouse gas emissions of thermal power stations in Canada

    International Nuclear Information System (INIS)

    Zabihian, F.; Fung, A.S.

    2009-01-01

    The purpose of this paper is to examine greenhouse gas (GHG) emission reduction potentials in the Canadian electricity generation sector through fuel switching and the adoption of advanced power generation systems. To achieve this purpose, six different scenarios were introduced. In the first scenario existing power stations' fuel was switched to natural gas. Existing power plants were replaced by natural gas combined cycle (NGCC), integrated gasification combined cycle (IGCC), solid oxide fuel cell (SOFC), hybrid SOFC, and SOFC-IGCC hybrid power stations in scenarios number 2 to 6, respectively. (author)

  1. Puertollano IGCC Power Plant; Central de Gasificacion Integrada en Ciclo Combinado de Puertollano

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2000-07-01

    The Puertollano IGCC Power Plant, rated 335 MW and located in Puertollano, Ciudad Real, in the central area of Spain, is a project led by ELCOGAS, a company incorporated by the European utilities ENDESA, ELECTRICITE DE FRANCE, IBERDROLA HIDROCANTABRICO ELECTRICIDADE DE PURTUGAL, ENEL and NATIONAL POWER and the technology and equipment suppliers SIEMENS, KRUPP UHDE and BABCOCK WILCOX ESPANOLA. IGCC technology is based in a process of coal gasification to obtain a clean combustion synthetic gas, integrated with a combined cycle, agas and steam, electricity-generating unit. The energy efficiency which is aimed to achieve at the Plant is 46% in ISO conditions. The Gasification unit uses the process of pressurised entrained flow for coal gasification. The gas is produced by the reaction of coal with oxygen at high temperatures, of up to 1600 degree centigree. This process is capable of gasifying a wide variety of types and qualities of coal for the production of a synthetic fuel gas. In the case of Puertollano, the raw fuel is a 50% mixture by weight of local coal and petroleum coke. The oxygen needed in the process and the nitrogen used for covering the fuel is generated in the Air Separation. The Gas Cleaning and Sulphur Recovery Unit clean the gases from contaminants and solid particles before to send them to the Gas Turbine. The clean gas is burnt in gas turbine of the Combined Cycle Plant, producing electricity. The exhaust gases feed a heat recovery steam generator, which produces steam used to generate additional electricity in a conventional steam turbine. The gas turbine is capable of operating both with synthetic gas and with natural gas, allowing operation flexibility. The net output of the plant up to December 1999 was 3.061 GWh, from them 344 GWh were produced with synthetic gas. This project has an important technological value, being the first power plant which uses coal gasification to feed a combined cycle in Spain and being also the biggest power plant

  2. Spherical Projection Based Straight Line Segment Extraction for Single Station Terrestrial Laser Point Cloud

    Directory of Open Access Journals (Sweden)

    ZHANG Fan

    2015-06-01

    Full Text Available Due to the discrete distribution computing errors and lack of adaptability are ubiquitous in the current straight line extraction for TLS data methods. A 3D straight line segment extraction method is proposed based on spherical projection for single station terrestrial laser point clouds. Firstly, horizontal and vertical angles of each laser point are calculated by means of spherical coordinates, intensity panoramic image according to the two angles is generated. Secondly, edges which include straight line features are detected from intensity panoramic image by using of edge detection algorithm. Thirdly, great circles are detected from edges of panoramic image using spherical Hough transform. According to the axiom that a straight line segment in 3D space is a spherical great circle after spherical projection, detecting great circles from spherical projected data sets is essentially detecting straight line segments from 3D data sets without spherical projection. Finally, a robust 3D straight line fitting method is employed to fitting the straight lines and calculating parameters of the straight line segments. Experiments using different data sets and comparison with other methods show the accuracy and applicability of the proposed method.

  3. GULF OF MEXICO SEAFLOOR STABILITY AND GAS HYDRATE MONITORING STATION PROJECT

    Energy Technology Data Exchange (ETDEWEB)

    J. Robert Woolsey; Thomas M. McGee; Robin C. Buchannon

    2004-11-01

    The gas hydrates research Consortium (HRC), established and administered at the University if Mississippi's Center for Marine Research and Environmental Technology (CMRET) has been active on many fronts in FY 03. Extension of the original contract through March 2004, has allowed completion of many projects that were incomplete at the end of the original project period due, primarily, to severe weather and difficulties in rescheduling test cruises. The primary objective of the Consortium, to design and emplace a remote sea floor station for the monitoring of gas hydrates in the Gulf of Mexico by the year 2005 remains intact. However, the possibility of levering HRC research off of the Joint Industries Program (JIP) became a possibility that has demanded reevaluation of some of the fundamental assumptions of the station format. These provisions are discussed in Appendix A. Landmark achievements of FY03 include: (1) Continuation of Consortium development with new researchers and additional areas of research contribution being incorporated into the project. During this period, NOAA's National Undersea Research Program's (NURP) National Institute for Undersea Science and Technology (NIUST) became a Consortium funding partner, joining DOE and Minerals Management Service (MMS); (2) Very successful annual and semiannual meetings in Oxford Mississippi in February and September, 2003; (3) Collection of piston cores from MC798 in support of the effort to evaluate the site for possible monitoring station installation; (4) Completion of the site evaluation effort including reports of all localities in the northern Gulf of Mexico where hydrates have been documented or are strongly suspected to exist on the sea floor or in the shallow subsurface; (5) Collection and preliminary evaluation of vent gases and core samples of hydrate from sites in Green Canyon and Mississippi Canyon, northern Gulf of Mexico; (6) Monitoring of gas activity on the sea floor, acoustically

  4. Technical comparison between Integrated Gasification Combined Cycle (IGCC) and Natural Gas Combined Cycle (NGCC) power plants

    Energy Technology Data Exchange (ETDEWEB)

    Ortiz, Pablo Andres Silva; Venturini, Osvaldo Jose; Lora, Electo Eduardo Silva [Federal University of Itajuba - UNIFEI, MG (Brazil). Excellence Group in Thermal Power and Distributed Generation - NEST], e-mails: osvaldo@unifei.edu.br, electo@unifei.edu.br

    2010-07-01

    Among the emerging clean coal technologies for power generation, Integrated Gasification Combined Cycle (IGCC) and Natural Gas Combined Cycle (NGCC) systems are receiving considerable attention as a potentially attractive option to reduce the emissions of greenhouse gases (GHG). The main reason is because these systems has high efficiency and low emissions in comparison with traditional power generation plants. Currently in IGCC and NGCC systems at demonstration stage is been considered to implement CCS technology. CO{sub 2} emissions can be avoided in a gasification-based power plant because by transferring almost all carbon compounds to CO{sub 2} through the water gas shift (WGS) reaction, then removing the CO{sub 2} before it is diluted in the combustion stage. The aim of this study is to compare the technical performance of an IGCC system that uses Brazilian coal and petroleum coke as fuel with a NGCC system, with the same fixed output power of 450 MW. The first section of this paper presents the plant configurations of IGCC systems. The following section presents an analysis of NGCC technology. (author)

  5. Wabash River Coal Gasification Repowering Project: A DOE Assessment; FINAL

    International Nuclear Information System (INIS)

    National Energy Technology Laboratory

    2002-01-01

    The goal of the U.S. Department of Energy (DOE) Clean Coal Technology Program (CCT) is to furnish the energy marketplace with a number of advanced, more efficient, and environmentally responsible coal utilization technologies through demonstration projects. These projects seek to establish the commercial feasibility of the most promising advanced coal technologies that have developed beyond the proof-of-concept stage. This document serves as a DOE post-project assessment (PPA) of a project selected in CCT Round IV, the Wabash River Coal Gasification Repowering (WRCGR) Project, as described in a Report to Congress (U.S. Department of Energy 1992). Repowering consists of replacing an existing coal-fired boiler with one or more clean coal technologies to achieve significantly improved environmental performance. The desire to demonstrate utility repowering with a two-stage, pressurized, oxygen-blown, entrained-flow, integrated gasification combined-cycle (IGCC) system prompted Destec Energy, Inc., and PSI Energy, Inc., to form a joint venture and submit a proposal for this project. In July 1992, the Wabash River Coal Gasification Repowering Project Joint Venture (WRCGRPJV, the Participant) entered into a cooperative agreement with DOE to conduct this project. The project was sited at PSI Energy's Wabash River Generating Station, located in West Terre Haute, Indiana. The purpose of this CCT project was to demonstrate IGCC repowering using a Destec gasifier and to assess long-term reliability, availability, and maintainability of the system at a fully commercial scale. DOE provided 50 percent of the total project funding (for capital and operating costs during the demonstration period) of$438 million

  6. The Impact of Climatological Conditions on Low Enriched Uranium Loading Station Operations for the HEU Blend Down Project

    International Nuclear Information System (INIS)

    Chang, R.C.

    2002-01-01

    A computer model was developed using COREsim to perform a time motion study for the Low Enriched Uranium (LEU) Loading Station operations. The project is to blend Highly Enriched Uranium (HEU) with Natural Uranium (NU) to produce LEU to be shipped to Tennessee Valley Authority (TVA) for further processing. To cope with a project cost reduction, the LEU Loading Station concept has changed from an enclosed building with air-conditioning to a partially enclosed building without air conditioning. The LEU Loading Station is within a radiological contaminated area; two pairs of coveralls and negative pressure respirator are required. As a result, inclement weather conditions, especially heat stress, will affect and impact the LEU loading operations. The purposes of the study are to determine the climatological impacts on LEU Loading operations, resources required for committed throughputs, and to find out the optimum process pathways for multi crews working simultaneously in the space-lim ited LEU Loading Station

  7. Decommissioning of nuclear power stations in community countries carried out and projected

    International Nuclear Information System (INIS)

    Cregut, A.; Gregory, A.R.

    1984-01-01

    The decommissioning of large plants such as nuclear power stations merits an approach requiring the introduction of measures and procedures allowing them to be dealt with efficiently; this efficiency would imply concern for optimum economy of operations while respecting the safety and protection rules inherent in nuclear energy. Consequently, plant owners require: the tactical and policy elements to guide them in their decisions and choices; efficient tools, equipment and processes which meet their needs; information gained from experience of decommissioning already carried out which would provide them with a verified background knowledge when dealing with problems. Since decommissioning experience to date has not made it possible to draw up codes and guidelines, it is important to review the work carried out by Community countries in particular on the decommissioning of nuclear power plants. The following paper does not claim to be exhaustive or to make value judgements. Its aim is to list the nuclear power stations shut down in Community countries, to outline the decommissioning levels selected in each case and to underline some interesting aspects of the technical options. In conclusion it will review what appeared to be the difficulties common to the various projects. (author)

  8. Lessons learned in digital upgrade projects digital control system implementation at US nuclear power stations

    International Nuclear Information System (INIS)

    Kelley, S.; Bolian, T. W.

    2006-01-01

    AREVA NP has gained significant experience during the past five years in digital upgrades at operating nuclear power stations in the US. Plants are seeking modernization with digital technology to address obsolescence, spare parts availability, vendor support, increasing age-related failures and diminished reliability. New systems offer improved reliability and functionality, and decreased maintenance requirements. Significant lessons learned have been identified relating to the areas of licensing, equipment qualification, software quality assurance and other topics specific to digital controls. Digital control systems have been installed in non safety-related control applications at many utilities within the last 15 years. There have also been a few replacements of small safety-related systems with digital technology. Digital control systems are proving to be reliable, accurate, and easy to maintain. Digital technology is gaining acceptance and momentum with both utilities and regulatory agencies based upon the successes of these installations. Also, new plants are being designed with integrated digital control systems. To support plant life extension and address obsolescence of critical components, utilities are beginning to install digital technology for primary safety-system replacement. AREVA NP analyzed operating experience and lessons learned from its own digital upgrade projects as well as industry-wide experience to identify key issues that should be considered when implementing digital controls in nuclear power stations

  9. Risk impact of planned maintenance configuration at South Texas Project Electric Generating Station

    International Nuclear Information System (INIS)

    Loh, W.T.; Fleming, K.N.; Grantom, C.R.

    2004-01-01

    This paper is based on a study done for the Houston Lighting and Power Company. The purpose of this study is to estimate the risk impact of planned maintenance configurations at South Texas Project Electric Generating Station (STPEGS). To date, the focus of the STP probabilistic safety assessment (PSA) program has been to analyze risk in terms of estimates of accident frequencies that are expressed on a time-averaged basis. Thus, estimates of quantities such as severe core damage frequency have been made such that the temporal variations of this frequency with changing plant configurations are averaged out over time. The only condition that has been imposed on these estimates is that the plant is initially operating at full power when potential initiating events might occur. (author)

  10. International Remote Monitoring Project Embalse Nuclear Power Station, Argentina Embalse Remote Monitoring System

    International Nuclear Information System (INIS)

    Schneider, Sigfried L.; Glidewell, Donnie D.; Bonino, Anibal; Bosler, Gene; Mercer, David; Maxey, Curt; Vones, Jaromir; Martelle, Guy; Busse, James; Kadner, Steve; White, Mike; Rovere, Luis

    1999-01-01

    The Autoridad Regulatoria Nuclear of Argentina (ARN), the International Atomic Energy Agency (IAEA), ABACC, the US Department of Energy, and the US Support Program POTAS, cooperated in the development of a Remote Monitoring System for nuclear nonproliferation efforts. This system was installed at the Embalse Nuclear Power Station last year to evaluate the feasibility of using radiation sensors in monitoring the transfer of spent fuel from the spent fuel pond to dry storage. The key element in this process is to maintain continuity of knowledge throughout the entire transfer process. This project evaluated the fundamental design and implementation of the Remote Monitoring System in its application to regional and international safeguard efficiency. New technology has been developed to enhance the design of the system to include storage capability on board sensor platforms. This evaluation has led to design enhancements that will assure that no data loss will occur during loss of RF transmission of the sensors

  11. North Anna Power Station - Unit 1: Overview of steam generator replacement project activities

    International Nuclear Information System (INIS)

    Gettler, M.W.; Bayer, R.K.; Lippard, D.W.

    1993-01-01

    The original steam generators at Virginia Electric and Power Company's (Virginia Power) North Anna Power Station (NAPS) Unit 1 have experienced corrosion-related degradation that require periodic inspection and plugging of steam generator tubes to ensure their continued safe and reliable operation. Despite improvements in secondary water chemistry, continued tube degradation in the steam generators necessitated the removal from service of approximately 20.3 percent of the tubes by plugging, (18.6, 17.3, and 25.1 for steam generators A, B, and C, respectively). Additionally, the unit power was limited to 95 % during, its last cycle of operation. Projections of industry and Virginia Power experience indicated the possibility of mid-cycle inspections and reductions in unit power. Therefore, economic considerations led to the decision to repair the steam generators (i.e., replace the steam generator lower assemblies). Three new Model 51F Steam Generator lower assembly units were ordered from Westinghouse. Virginia Power contracted Bechtel Power Corporation to provide the engineering and construction support to repair the Unit 1 steam generators. On January 4, 1993, after an extended coastdown period, North Anna Unit 1 was brought off-line and the 110 day (breaker-to-breaker) Steam Generator Replacement Project (SGRP) outage began. As of this paper, the outage is still in progress

  12. A collaborative network middleware project by Lambda Station, TeraPaths, and Phoebus

    International Nuclear Information System (INIS)

    Bobyshev, A.; Bradley, S.; Crawford, M.; DeMar, P.; Katramatos, D.; Shroff, K.; Swany, M.; Yu, D.

    2010-01-01

    The TeraPaths, Lambda Station, and Phoebus projects, funded by the US Department of Energy, have successfully developed network middleware services that establish on-demand and manage true end-to-end, Quality-of-Service (QoS) aware, virtual network paths across multiple administrative network domains, select network paths and gracefully reroute traffic over these dynamic paths, and streamline traffic between packet and circuit networks using transparent gateways. These services improve network QoS and performance for applications, playing a critical role in the effective use of emerging dynamic circuit network services. They provide interfaces to applications, such as dCache SRM, translate network service requests into network device configurations, and coordinate with each other to setup up end-to-end network paths. The End Site Control Plane Subsystem (ESCPS) builds upon the success of the three projects by combining their individual capabilities into the next generation of network middleware. ESCPS addresses challenges such as cross-domain control plane signalling and interoperability, authentication and authorization in a Grid environment, topology discovery, and dynamic status tracking. The new network middleware will take full advantage of the perfSONAR monitoring infrastructure and the Inter-Domain Control plane efforts and will be deployed and fully vetted in the Large Hadron Collider data movement environment.

  13. Steam Pressure-Reducing Station Safety and Energy Efficiency Improvement Project

    Energy Technology Data Exchange (ETDEWEB)

    Lower, Mark D [ORNL; Christopher, Timothy W [ORNL; Oland, C Barry [ORNL

    2011-06-01

    The Facilities and Operations (F&O) Directorate is sponsoring a continuous process improvement (CPI) program. Its purpose is to stimulate, promote, and sustain a culture of improvement throughout all levels of the organization. The CPI program ensures that a scientific and repeatable process exists for improving the delivery of F&O products and services in support of Oak Ridge National Laboratory (ORNL) Management Systems. Strategic objectives of the CPI program include achieving excellence in laboratory operations in the areas of safety, health, and the environment. Identifying and promoting opportunities for achieving the following critical outcomes are important business goals of the CPI program: improved safety performance; process focused on consumer needs; modern and secure campus; flexibility to respond to changing laboratory needs; bench strength for the future; and elimination of legacy issues. The Steam Pressure-Reducing Station (SPRS) Safety and Energy Efficiency Improvement Project, which is under the CPI program, focuses on maintaining and upgrading SPRSs that are part of the ORNL steam distribution network. This steam pipe network transports steam produced at the ORNL steam plant to many buildings in the main campus site. The SPRS Safety and Energy Efficiency Improvement Project promotes excellence in laboratory operations by (1) improving personnel safety, (2) decreasing fuel consumption through improved steam system energy efficiency, and (3) achieving compliance with applicable worker health and safety requirements. The SPRS Safety and Energy Efficiency Improvement Project being performed by F&O is helping ORNL improve both energy efficiency and worker safety by modifying, maintaining, and repairing SPRSs. Since work began in 2006, numerous energy-wasting steam leaks have been eliminated, heat losses from uninsulated steam pipe surfaces have been reduced, and deficient pressure retaining components have been replaced. These improvements helped ORNL

  14. IGCC and PFBC By-Products: Generation, Characteristics, and Management Practices

    Energy Technology Data Exchange (ETDEWEB)

    Pflughoeft-Hassett, D.F.

    1997-09-01

    The following report is a compilation of data on by-products/wastes from clean coal technologies, specifically integrated gasification combined cycle (IGCC) and pressurized fluidized-bed combustion (PFBC). DOE had two objectives in providing this information to EPA: (1) to familiarize EPA with the DOE CCT program, CCT by-products, and the associated efforts by DOE contractors in the area of CCT by-product management and (2) to provide information that will facilitate EPA's effort by complementing similar reports from industry groups, including CIBO (Council of Industrial Boiler Owners) and EEI USWAG (Edison Electric Institute Utility Solid Waste Activities Group). The EERC cooperated and coordinated with DOE CCT contractors and industry groups to provide the most accurate and complete data on IGCC and PFBC by-products, although these technologies are only now being demonstrated on the commercial scale through the DOE CCT program.

  15. Computer models and simulations of IGCC power plants with Canadian coals

    Energy Technology Data Exchange (ETDEWEB)

    Zheng, L.; Furimsky, E.

    1999-07-01

    In this paper, three steady state computer models for simulation of IGCC power plants with Shell, Texaco and BGL (British Gas Lurgi) gasifiers will be presented. All models were based on a study by Bechtel for Nova Scotia Power Corporation. They were built by using Advanced System for Process Engineering (ASPEN) steady state simulation software together with Fortran programs developed in house. Each model was integrated from several sections which can be simulated independently, such as coal preparation, gasification, gas cooling, acid gas removing, sulfur recovery, gas turbine, heat recovery steam generation, and steam cycle. A general description of each process, model's overall structure, capability, testing results, and background reference will be given. The performance of some Canadian coals on these models will be discussed as well. The authors also built a computer model of IGCC power plant with Kellogg-Rust-Westinghouse gasifier, however, due to limitation of paper length, it is not presented here.

  16. Development of advanced air-blown entrained-flow two-stage bituminous coal IGCC gasifier

    Directory of Open Access Journals (Sweden)

    Abaimov Nikolay A.

    2017-01-01

    Full Text Available Integrated gasification combined cycle (IGCC technology has two main advantages: high efficiency, and low levels of harmful emissions. Key element of IGCC is gasifier, which converts solid fuel into a combustible synthesis gas. One of the most promising gasifiers is air-blown entrained-flow two-stage bituminous coal gasifier developed by Mitsubishi Heavy Industries (MHI. The most obvious way to develop advanced gasifier is improvement of commercial-scale 1700 t/d MHI gasifier using the computational fluid dynamics (CFD method. Modernization of commercial-scale 1700 t/d MHI gasifier is made by changing the regime parameters in order to improve its cold gas efficiency (CGE and environmental performance, namely H2/CO ratio. The first change is supply of high temperature (900°C steam in gasifier second stage. And the second change is additional heating of blast air to 900°C.

  17. Dynamic simulation of a low-temperature rectification Column as part of an IGCC power plant

    Energy Technology Data Exchange (ETDEWEB)

    Hanke, R. [Leipzig University of Applied Sciences, Department of Mechanical and Energy Engineering, P.O. Box 300066, D-04251 Leipzig (Germany); Hannemann, F. [Siemens AG - Power Generation, PG CTET, P.O. Box 3220, D-91050 Erlangen (Germany); Sundmacher, K. [Max Planck Institute of Dynamics of Complex Technical Systems, Sandtorstrasse 1, D-39106 Magdeburg (Germany); Otto-von-Guericke University Magdeburg, Faculty of Process and Systems Engineering, P.O. Box 4120, D-39106 Magdeburg (Germany)

    2003-11-01

    IGCC plants offer the opportunity to utilize fossil energy sources, like coal or heavy refinery residues, to satisfy increasing energy demand while considering strict environmental constraints. Such a plant consists of a combined power cycle, a fuel gasifier with downstream fuel gas conditioning and an air separation unit (ASU), where the oxygen required for gasification is produced. The low-temperature rectification column as the core of the ASU strongly affects the transient behavior of the system. (Abstract Copyright [2003], Wiley Periodicals, Inc.)

  18. Novel findings about management of gastric cancer: A summary from 10th IGCC

    OpenAIRE

    Penon, Danila; Cito, Letizia; Giordano, Antonio

    2014-01-01

    The Tenth International Gastric Cancer Congress (IGCC) was held in Verona, Italy, from June 19 to 22, 2013. The meeting enclosed various aspects of stomach tumor management, including both tightly clinical approaches, and topics more related to basic research. Moreover, an overview on gastrointestinal stromal tumors was provided too, although here not discussed. Here we will discuss some topics related to molecular biology of gastric cancer (GC), inherent to prognostic, diagnostic and therape...

  19. Thermal expansion of slag and fly ash from coal gasification in IGCC power plant

    Energy Technology Data Exchange (ETDEWEB)

    M. Aineto; A. Acosta; J.M.A. Rincon; M. Romero [University of Castilla La Mancha, Ciudad Real (Spain). Laboratory of Applied Mineralogy

    2006-11-15

    Integrated gasification in combined cycle (IGCC) is an electrical power generation system which is characterized to be a clean coal technology different than conventional process in combustible treatment. IGCC process gives rise to inorganic solid wastes in the form of vitreous slag and fly ashes with singular thermal properties. The gasification of the fuel takes place at high temperature and pressure in reducing atmosphere. Under that conditions, gases such as H{sub 2}, N{sub 2} or CO, which are the main components of the gas mixture in the gasifier, show a high solubility in the melt and during the cooling remain enclosed in the vitreous slag. When these wastes are afterward thermal treated in oxidizing conditions, two phenomena occur. The development of a crystalline phase by devitrification of the glassy matrix and the releasing of the enclosed gas, which starts at temperatures nearly to the softening point. At higher temperatures the bubbles with increasing kinetic energy tend to ascend with difficulty through the viscous liquid phase and promotes an expansive reaction, giving rise to a foam glass-ceramic product. This paper has been focused on the study of thermal expansion in slag and fly ash samples from the ELCOGAS IGCC power plant located in Puertollano (Spain). 18 refs., 11 figs., 1 tab.

  20. CO2 control technology effects on IGCC plant performance and cost

    International Nuclear Information System (INIS)

    Chen Chao; Rubin, Edward S.

    2009-01-01

    As part of the USDOE's Carbon Sequestration Program, an integrated modeling framework has been developed to evaluate the performance and cost of alternative carbon capture and storage (CCS) technologies for fossil-fueled power plants in the context of multi-pollutant control requirements. This paper uses the newly developed model of an integrated gasification combined cycle (IGCC) plant to analyze the effects of adding CCS to an IGCC system employing a GE quench gasifier with water gas shift reactors and a Selexol system for CO 2 capture. Parameters of interest include the effects on plant performance and cost of varying the CO 2 removal efficiency, the quality and cost of coal, and selected other factors affecting overall plant performance and cost. The stochastic simulation capability of the model is also used to illustrate the effect of uncertainties or variability in key process and cost parameters. The potential for advanced oxygen production and gas turbine technologies to reduce the cost and environmental impacts of IGCC with CCS is also analyzed

  1. Low Thermal Conductivity, High Durability Thermal Barrier Coatings for IGCC Environments

    Energy Technology Data Exchange (ETDEWEB)

    Jordan, Eric [Univ. of Connecticut, Storrs, CT (United States); Gell, Maurice [Univ. of Connecticut, Storrs, CT (United States)

    2015-01-15

    Advanced thermal barrier coatings (TBC) are crucial to improved energy efficiency in next generation gas turbine engines. The use of traditional topcoat materials, e.g. yttria-stabilized zirconia (YSZ), is limited at elevated temperatures due to (1) the accelerated undesirable phase transformations and (2) corrosive attacks by calcium-magnesium-aluminum-silicate (CMAS) deposits and moisture. The first goal of this project is to use the Solution Precursor Plasma Spray (SPPS) process to further reduce the thermal conductivity of YSZ TBCs by introducing a unique microstructural feature of layered porosity, called inter-pass boundaries (IPBs). Extensive process optimization accompanied with hundreds of spray trials as well as associated SEM cross-section and laser-flash measurements, yielded a thermal conductivity as low as 0.62 Wm⁻¹K⁻¹ in SPPS YSZ TBCs, approximately 50% reduction of APS TBCs; while other engine critical properties, such as cyclic durability, erosion resistance and sintering resistance, were characterized to be equivalent or better than APS baselines. In addition, modifications were introduced to SPPS TBCs so as to enhance their resistance to CMAS under harsh IGCC environments. Several mitigation approaches were explored, including doping the coatings with Al₂O₃ and TiO₂, applying a CMAS infiltration-inhibiting surface layer, and filling topcoat cracks with blocking substances. The efficacy of all these modifications was assessed with a set of novel CMAS-TBC interaction tests, and the moisture resistance was tested in a custom-built high-temperature moisture rig. In the end, the optimal low thermal conductivity TBC system was selected based on all evaluation tests and its processing conditions were documented. The optimal coating consisted on a thick inner layer of YSZ coating made by the SPPS process having a thermal conductivity 50% lower than standard YSZ coatings topped with a high temperature tolerant CMAS resistant gadolinium

  2. Operational radio interferometry observation network (ORION) mobile VLBI station. [for NASA Crustal Dynamics Project

    Science.gov (United States)

    Renzetti, N. A.; Vegos, C. J.; Parks, G. S.; Sniffin, R. W.; Gannon, D. L.; Nishimura, H. G.; Clements, P. A.; Mckinney, R. P.; Menninger, F. J.; Vandenberg, N. R.

    1983-01-01

    The design and current status of the ORION mobile VLBI station is described. The station consists of a five-meter antenna, a receiving and recording system installed in a mobile antenna transporter, and an electronics transporter. The station is designed for field operation by a two-person crew at the rate of two sites per week. The various subsystems are described in detail, including the antenna, housing facilities for electronics and crew, microwave equipment, receiver, data acquisition subsystem, frequency and timing subsystem, phase calibration, monitoring and control, water vapor radiometer, and communications.

  3. The controlled ecological life support system Antarctic analog project: Analysis of wastewater from the South Pole Station, Antarctica, volume 1

    Science.gov (United States)

    Flynn, Michael T.; Bubenheim, David L.; Straight, Christian L.; Belisle, Warren

    1994-01-01

    The Controlled Ecological Life Support system (CELSS) Antarctic Analog Project (CAAP) is a joint National Science Foundation (NSF) and NASA project for the development, deployment and operation of CELSS technologies at the Amundsen-Scott South Pole Station. NASA goals are operational testing of CELSS technologies and the conduct of scientific studies to facilitate technology selection and system design. The NSF goals are that the food production, water purification, and waste treatment capabilities which will be provided by CAAP will improve the quality of life for the South Pole inhabitants, reduce logistics dependence, and minimize environmental impacts associated with human presence on the polar plateau. This report presents an analysis of wastewater samples taken from the Amundsen-Scott South Pole Station, Antarctica. The purpose of the work is to develop a quantitative understanding of the characteristics of domestic sewage streams at the South Pole Station. This information will contribute to the design of a proposed plant growth/waste treatment system which is part of the CELSS Antarctic Analog Project (CAAP).

  4. Shell coal IGCCS with carbon capture: Conventional gas quench vs. innovative configurations

    International Nuclear Information System (INIS)

    Martelli, Emanuele; Kreutz, Thomas; Carbo, Michiel; Consonni, Stefano; Jansen, Daniel

    2011-01-01

    Highlights: → We aim at defining the preferred IGCC design for dry feed gasifiers with CO 2 capture. → Multiple options of syngas cooling, humidification, and WGS are considered. → Plants are designed, modeled, numerically optimized and costs are carefully assessed. → Partial water quench has poor efficiency but low capital cost, then good performance. → Gas quench with the ECN staged WGS design has the best thermo-economic performance. -- Abstract: The Shell coal integrated gasification combined cycle (IGCC) based on the gas quench system is one of the most fuel flexible and energy efficient gasification processes because is dry feed and employs high temperature syngas coolers capable of rising high pressure steam. Indeed the efficiency of a Shell IGCC with the best available technologies is calculated to be 47-48%. However the system looses many percentage points of efficiency (up to 10) when introducing carbon capture. To overcome this penalty, two approaches have been proposed. In the first, the expensive syngas coolers are replaced by a 'partial water quench' where the raw syngas stream is cooled and humidified via direct injection of hot water. This design is less costly, but also less efficient. The second approach retains syngas coolers but instead employs novel water-gas shift (WGS) configurations that requires substantially less steam to obtain the same degree of CO conversion to CO 2 , and thus increases the overall plant efficiency. We simulate and optimize these novel configurations, provide a detailed thermodynamic and economic analysis and investigate how these innovations alter the plant's efficiency, cost and complexity.

  5. The role of IGCC technology in power generation using low-rank coal

    Energy Technology Data Exchange (ETDEWEB)

    Juangjandee, Pipat

    2010-09-15

    Based on basic test results on the gasification rate of Mae Moh lignite coal. It was found that an IDGCC power plant is the most suitable for Mae Moh lignite. In conclusion, the future of an IDGCC power plant using low-rank coal in Mae Moh mine would hinge on the strictness of future air pollution control regulations including green-house gas emission and the constraint of Thailand's foreign currency reserves needed to import fuels, in addition to economic consideration. If and when it is necessary to overcome these obstacles, IGCC is one variable alternative power generation must consider.

  6. Effective utilization of fossil fuels for low carbon world -- IGCC and high performance gas turbine

    Energy Technology Data Exchange (ETDEWEB)

    Ishii, Hiromi; Hashimoto, Takao; Sakamoto, Koichi; Komori, Toyoaki; Kishine, Takashi; Shiozaki, Shigehiro

    2010-09-15

    The reduction of greenhouse-gas emissions is required to minimize the effect of hydrocarbon based power generation on global warming. In pursue of this objective, Mitsubishi Heavy Industries is dedicating considerable efforts on two different ways to reduce the environmental impact. The first one involves gas turbine performance improvement by raising firing temperature for Natural-gas and LNG applications. In this regard, the latest J class gas turbine was designed to operate at 1600 deg C and expected combined cycle efficiency in excess of 60%. The other approach involves the use of Integrated Gasification Combined Cycle (IGCC) plants to burn solid fuel like coal.

  7. Risk management of the North Anna Power Station Service Water System Preservation Project using the IPE model

    International Nuclear Information System (INIS)

    Afzali, A.; Donovan, M.D.; Sartain, M.D.; Bankley, A.V.

    1993-01-01

    This paper discusses the application of the North Anna Power Station Individual Plant Examination (IPE) models in PRA study of the Service Water System Preservation Project (SWSPP). The service water project involves repair and restoration of the Service Water System (SWS) piping and will require excavation of the buried SWS lines in addition to temporarily removing one of the two redundant SWS loops from operation. The SWSPP will be carried out with one or both units in normal operation. The objective of the PRA study was to quantify the risk impact (as measured by the change in Core Damage Frequency (ΔCDF)) of the SWSPP and to identify and evaluate countermeasures to reduce the risk impact of the project activities. The study concluded that the ΔCDF would be acceptable by undertaking preventative measures and by providing additional accident mitigating measures during performance of the SWSPP activities

  8. Different methods of informing the public on projected sites of nuclear generating stations. Results in France

    International Nuclear Information System (INIS)

    Taccoen, L.B.C.

    1977-01-01

    The situation in France of local public opinion concerning nuclear power stations is very different, according to the region in question. It seems that in industrialized regions, where the inhabitants are already familiar with nuclear energy, public opinion is much more open to the installation of new reactors. In regions which are only slightly industrialized, however, the prejudices of the population against nuclear energy can be very strong. This situation is quite serious because it could lead to an even greater widening of the development gap between various regions in France. Electricite de France has thus been led to develop a program of public information concerning the problems of nuclear energy. In practice, this program consists of: a policy of active presence in meeting and debates as well as at the actual site; eventual opening of information centers; and organization of visists of existing nuclear power stations [fr

  9. Factors Causing Delay of Modification Projects at Koeberg Nuclear Power Station

    International Nuclear Information System (INIS)

    Ntoyanto, S.

    2017-01-01

    Modification project delays could lead to: disrupting the maintenance shutdown (outage) projects' schedule, affecting electricity capacity of the national grid., possible load-shedding restricting electricity supply to domestic, commercial, and industrial consumers; and detrimental consequences to the country's economic activities. To address proficiency of a project manager by improving: Understanding of the organizational processes, High-level technical knowledge of a nuclear power plant technology

  10. 18-months fuel cycle engineering and its project management of the Daya Bay Nuclear Power Station

    International Nuclear Information System (INIS)

    Fu Xiangang; Jiao Ping; Liu Yong; Wu Zhiming

    2002-01-01

    The author introduces aspects related to the performing of 18-months fuel cycle engineering evaluation to the Daya Bay nuclear power plant, including the assessment on proposed technical solutions, appointment to the contractors, breaking down and implementation of project, experience on the project management and risk control, and etc. And it also briefs the prompting to the localization of the long fuel cycle engineering technology and AFA 3G fuel manufacturing and design technology via adequate technology transferring of this project

  11. Shell coal IGCCS with carbon capture. Conventional gas quench vs. innovative configurations

    Energy Technology Data Exchange (ETDEWEB)

    Martellia, E.; Consonni, S. [Politecnico di Milano, Via Scalabrini 76, Piacenza (Italy); Kreutz, T. [Princeton University, Guyot Hall, Room 129, Princeton, NJ (United States); Carbo, M.; Jansen, D. [Energy research Centre of the Netherlands ECN, P.O. Box 1, 1755 ZG, Petten (Netherlands)

    2011-11-15

    The Shell coal integrated gasification combined cycle (IGCC) based on the gas quench system is one of the most fuel flexible and energy efficient gasification processes because is dry feed and employs high temperature syngas coolers capable of rising high pressure steam. Indeed the efficiency of a Shell IGCC with the best available technologies is calculated to be 47-48%. However the system looses many percentage points of efficiency (up to 10) when introducing carbon capture. To overcome this penalty, two approaches have been proposed. In the first, the expensive syngas coolers are replaced by a 'partial water quench' where the raw syngas stream is cooled and humidified via direct injection of hot water. This design is less costly, but also less efficient. The second approach retains syngas coolers but instead employs novel water-gas shift (WGS) configurations that requires substantially less steam to obtain the same degree of CO conversion to CO2, and thus increases the overall plant efficiency. We simulate and optimize these novel configurations, provide a detailed thermodynamic and economic analysis and investigate how these innovations alter the plant's efficiency, cost and complexity.

  12. A single IGCC design for variable CO{sub 2} capture

    Energy Technology Data Exchange (ETDEWEB)

    O' Keefe, L.F.; Griffiths, J.; Wainwright, J.M. [Chevron Texaco Worldwide Power and Gasification, Houston, TX (United States)

    2002-07-01

    Global warming and the production of greenhouse gases (GHG) have become an important issue in many countries around the world. While there has been a heightened sense of awareness that the combustion of fossil fuels produces the majority of the controllable carbon dioxide released to the atmosphere, there have been few substantive solutions that produce economically realistic solutions. Moreover, some fossil fuels, like coal, are viewed negatively due to their relatively high carbon content per Btu. Integrated Gasification Combined Cycle (IGCC) offers the option of a realistic, economically viable solution for reducing, by pre-combustion capture, significant amounts of CO{sub 2} while using existing commercially proven technologies. The novel IGCC flowscheme is designed so that the power plant can be built and operated without CO{sub 2} removal and later upgraded to low CO{sub 2} emissions at minimal additional cost. The novel flowscheme is based on commercially proven technology using processes that are in operation today. Overall performance and capital cost estimates are presented and two other possible applications of the novel flowscheme are discussed in this paper. 17 refs., 3 figs., 2 tabs.

  13. Conceptual model and evaluation of generated power and emissions in an IGCC plant

    International Nuclear Information System (INIS)

    Perez-Fortes, M.; Bojarski, A.D.; Velo, E.; Nougues, J.M.; Puigjaner, L.

    2009-01-01

    This work develops a design and operation support tool for an Integrated Gasification Combined Cycle (IGCC) power plant, which allows the efficiency and environmental issues of alternative process designs and feedstock to be assessed. The study is based on a conceptual model of an IGCC plant, validated with data from the ELCOGAS power plant in Spain. The layout of the model includes an Air Separation Unit (ASU), a Pressurized Entrained Flow (PRENFLO) gasifier, a series of purification gas units (venturi scrubber, sour water steam stripper, COS hydrolysis reactor, MDEA absorber columns and a sulphur recovery Claus plant), a Heat Recovery Steam Generator (HRSG) and a Combined Cycle (CC) system. It comprises steady state models. One of the purposes of this work is to analyze the feasibility of coal co-gasification using waste materials; specifically petcoke and olive pomace (orujillo) are considered here. The model has been developed in Aspen Hysys. It uses electrolyte models that have been implemented in Aspen Plus which are connected to Aspen Hysys by means of Artificial Neural Networks (ANNs) models. Results of the model's, gas composition and generated power, are in agreement with the industrial data.

  14. More Energy-Efficient CO2 Capture from IGCC GE Flue Gases

    Directory of Open Access Journals (Sweden)

    Rakpong Peampermpool

    2017-03-01

    Full Text Available Carbon dioxide (CO2 emissions are one of the main reasons for the increase in greenhouse gasses in the earth’s atmosphere and carbon capture and sequestration (CCS is known as an effective method to reduce CO2 emissions on a larger scale, such as for fossil energy utilization systems. In this paper, the feasibility of capturing CO2 using cryogenic liquefaction and improving the capture rate by expansion will be discussed. The main aim was to design an energy-saving scheme for an IGCC (integrated gasification combined cycle power plant with CO2 cryogenic liquefaction capture. The experimental results provided by the authors, using the feed gas specification of a 740 MW IGCC General Electric (GE combustion power plant, demonstrated that using an orifice for further expanding the vent gas after cryogenic capture from 57 bar to 24 bar gave an experimentally observed capture rate up to 65%. The energy-saving scheme can improve the overall CO2 capture rate, and hence save energy. The capture process has also been simulated using Aspen HYSYS simulation software to evaluate its energy penalty. The results show that a 92% overall capture rate can be achieved by using an orifice.

  15. Conceptual model and evaluation of generated power and emissions in an IGCC plant

    Energy Technology Data Exchange (ETDEWEB)

    Perez-Fortes, M.; Bojarski, A. D.; Velo, E.; Nougues, J. M. [Department of Chemical Engineering, Universitat Politecnica de Catalunya, ETSEIB, Avda. Diagonal, 647, E-08028 Barcelona (Spain); Puigjaner, L., E-mail: luis.puigjaner@upc.edu [Department of Chemical Engineering, Universitat Politecnica de Catalunya, ETSEIB, Avda. Diagonal, 647, E-08028 Barcelona (Spain)

    2009-10-15

    This work develops a design and operation support tool for an Integrated Gasification Combined Cycle (IGCC) power plant, which allows the efficiency and environmental issues of alternative process designs and feedstock to be assessed. The study is based on a conceptual model of an IGCC plant, validated with data from the ELCOGAS power plant in Spain. The layout of the model includes an Air Separation Unit (ASU), a Pressurized Entrained Flow (PRENFLO) gasifier, a series of purification gas units (venturi scrubber, sour water steam stripper, COS hydrolysis reactor, MDEA absorber columns and a sulphur recovery Claus plant), a Heat Recovery Steam Generator (HRSG) and a Combined Cycle (CC) system. It comprises steady state models. One of the purposes of this work is to analyze the feasibility of coal co-gasification using waste materials; specifically petcoke and olive pomace (orujillo) are considered here. The model has been developed in Aspen Hysys. It uses electrolyte models that have been implemented in Aspen Plus which are connected to Aspen Hysys by means of Artificial Neural Networks (ANNs) models. Results of the model's, gas composition and generated power, are in agreement with the industrial data.

  16. Conceptual model and evaluation of generated power and emissions in an IGCC plant

    Energy Technology Data Exchange (ETDEWEB)

    Perez-Fortes, M; Bojarski, A D; Velo, E; Nougues, J M; Puigjaner, L [Department of Chemical Engineering, Universitat Politecnica de Catalunya, ETSEIB, Avda. Diagonal, 647, E-08028 Barcelona (Spain)

    2009-10-15

    This work develops a design and operation support tool for an Integrated Gasification Combined Cycle (IGCC) power plant, which allows the efficiency and environmental issues of alternative process designs and feedstock to be assessed. The study is based on a conceptual model of an IGCC plant, validated with data from the ELCOGAS power plant in Spain. The layout of the model includes an Air Separation Unit (ASU), a Pressurized Entrained Flow (PRENFLO) gasifier, a series of purification gas units (venturi scrubber, sour water steam stripper, COS hydrolysis reactor, MDEA absorber columns and a sulphur recovery Claus plant), a Heat Recovery Steam Generator (HRSG) and a Combined Cycle (CC) system. It comprises steady state models. One of the purposes of this work is to analyze the feasibility of coal co-gasification using waste materials; specifically petcoke and olive pomace (orujillo) are considered here. The model has been developed in Aspen Hysys. It uses electrolyte models that have been implemented in Aspen Plus which are connected to Aspen Hysys by means of Artificial Neural Networks (ANNs) models. Results of the model's, gas composition and generated power, are in agreement with the industrial data. (author)

  17. Conceptual model and evaluation of generated power and emissions in an IGCC plant

    Energy Technology Data Exchange (ETDEWEB)

    Perez-Fortes, M.; Bojarski, A.D.; Velo, E.; Nougues, J.M.; Puigjaner, L. [Department of Chemical Engineering, Universitat Politecnica de Catalunya, ETSEIB, Avda. Diagonal, 647, E-08028 Barcelona (Spain)

    2009-10-15

    This work develops a design and operation support tool for an Integrated Gasification Combined Cycle (IGCC) power plant, which allows the efficiency and environmental issues of alternative process designs and feedstock to be assessed. The study is based on a conceptual model of an IGCC plant, validated with data from the ELCOGAS power plant in Spain. The layout of the model includes an Air Separation Unit (ASU), a Pressurized Entrained Flow (PRENFLO) gasifier, a series of purification gas units (venturi scrubber, sour water steam stripper, COS hydrolysis reactor, MDEA absorber columns and a sulphur recovery Claus plant), a Heat Recovery Steam Generator (HRSG) and a Combined Cycle (CC) system. It comprises steady state models. One of the purposes of this work is to analyze the feasibility of coal co-gasification using waste materials; specifically petcoke and olive pomace (orujillo) are considered here. The model has been developed in Aspen Hysys. It uses electrolyte models that have been implemented in Aspen Plus which are connected to Aspen Hysys by means of Artificial Neural Networks (ANNs) models. Results of the model's, gas composition and generated power, are in agreement with the industrial data. (author)

  18. Integration optimisation of elevated pressure air separation unit with gas turbine in an IGCC power plant

    International Nuclear Information System (INIS)

    Han, Long; Deng, Guangyi; Li, Zheng; Wang, Qinhui; Ileleji, Klein E.

    2017-01-01

    Highlights: • IGCC thermodynamic model was setup carefully. • Simulations focus on integration between an elevated pressure ASU with gas turbine. • Different recommended solutions from those of low pressure ASUs are figured out. • Full N 2 injection and 80% air extraction was suggested as the optimum integration. - Abstract: The integration optimisation between an elevated pressure air separation unit (EP-ASU) and gas turbine is beneficial to promote net efficiency of an integrated gasification combined cycle (IGCC) power plant. This study sets up the thermodynamic model for a 400 MW plant specially coupled with an EP-ASU, aiming to examine system performances under different integrations and acquire the optimum solution. Influences of air extraction rate at conditions of without, partial and full N 2 injection, as well as the effects of N 2 injection rate when adopting separate ASU, partial and full integrated ASU were both analysed. Special attention has been paid to performance differences between utilising an EP-ASU and a low pressure unit. Results indicated that integration solution with a separate EP-ASU or without N 2 injection would not be reasonable. Among various recommended solutions for different integration conditions, N 2 injection rate increased with the growth of air extraction rate. The integration with an air extraction rate of 80% and full N 2 injection was suggested as the optimum solution. It is concluded that the optimum integration solution when adopting an EP-ASU is different from that using a low pressure one.

  19. Novel findings about management of gastric cancer: a summary from 10th IGCC.

    Science.gov (United States)

    Penon, Danila; Cito, Letizia; Giordano, Antonio

    2014-07-21

    The Tenth International Gastric Cancer Congress (IGCC) was held in Verona, Italy, from June 19 to 22, 2013. The meeting enclosed various aspects of stomach tumor management, including both tightly clinical approaches, and topics more related to basic research. Moreover, an overview on gastrointestinal stromal tumors was provided too, although here not discussed. Here we will discuss some topics related to molecular biology of gastric cancer (GC), inherent to prognostic, diagnostic and therapeutic tools shown at the conference. Results about well known subjects, such as E-cadherin loss of expression/function, were presented. They revealed that other mutations of the gene were identified, showing a continuous research to improve diagnosis and prognosis of stomach tumor. Simultaneously, new possible molecular markers with an established role for other neoplasms, were discussed, such as mesothelin, stomatin-like protein 2 and Notch-1. Hence, a wide overview including both old and new diagnostic/prognostic tools was offered. Great attention was also dedicated to possible drugs to be used against GC. They included monoclonal antibodies, such as MS57-2.1, drugs used in other pathologies, such as maraviroc, and natural extracts from plants such as biflorin. We would like to contribute to summarize the most impressive studies presented at the IGCC, concerning novel findings about molecular biology of gastric cancer. Although further investigations will be necessary, it can be inferred that more and more tools were developed, so as to better face stomach neoplasms.

  20. Seismic structural fragility investigation for the San Onofre Nuclear Generating Station, Unit 1 (Project I); SONGS-1 AFWS Project

    International Nuclear Information System (INIS)

    Wesley, D.A.; Hashimoto, P.S.

    1982-04-01

    An evaluation of the seismic capacities of several of the San Onofre Nuclear Generating Station, Unit 1 (SONGS-1) structures was conducted to determine input to the overall probabilistic methodology developed by Lawrence Livermore National Laboratory. Seismic structural fragilities to be used as input consist of median seismic capacities and their variabilities due to randomness and uncertainty. Potential failure modes were identified for each of the SONGS-1 structures included in this study by establishing the seismic load-paths and comparing expected load distributions to available capacities for the elements of each load-path. Particular attention was given to possible weak links and details. The more likely failure modes were screened for more detailed investigation

  1. Towards retrofitting integrated gasification combined cycle (IGCC) power plants with solid oxide fuel cells (SOFC) and CO

    NARCIS (Netherlands)

    Thallam Thattai, A.; Oldenbroek, V.D.W.M.; Schoenmakers, L; Woudstra, T.; Purushothaman Vellayani, A.

    2017-01-01

    This article presents a detailed thermodynamic case study based on the Willem-Alexander Centrale (WAC) power plant in the Netherlands towards retrofitting SOFCs in existing IGCC power plants with a focus on near future implementation. Two systems with high percentage (up to 70%) biomass

  2. Palo Verde Nuclear Generating Station: an example of the state role in regional nuclear projects

    International Nuclear Information System (INIS)

    Pasternak, A.

    1980-10-01

    A nuclear power plant siting policy which confines new construction to existing sites will lead to the formation of large regional power centers, each involving many utilities from several states. The Palo Verde Nuclear Project in Arizona has been examined in terms of the role state regulation plays in large regional nuclear projects. State regulatory processes do not reflect the regional nature of large power centers. Decisions and actions by individual state regulatory commissions create risk and uncertainty for all the utility participants in regional projects. A climate and mechanism to encourage and facilitate interstate cooperation are needed to enhance the viability of the confined siting policy and the regional power center concept

  3. Groundwater remediation project at Stockem railway station following a pollution with MIAK (Methyl Isoamyl Ketone)

    Energy Technology Data Exchange (ETDEWEB)

    Daelemans, A.; Boden, A.; Schuyteneer, L.W. de; Achter, L.H. van [Soil Service of Belgium, Leuven-Heverlee (Belgium)

    2003-07-01

    On the 20{sup th} of January 2000, a derailment accident happened near the railway station of Stockem in the vicinity of the city of Arlon. An estimated 20.000 litres of MIAK (methyl isoamyl ketone or 5-methyl-2-hexanone) was spilled and lost into the soil. Immediately after the accident, the Soil Service of Belgium received a request from the Belgian National Railway Company to establish an emergency plan for the remediation of the spill, including the design and the follow-up of the clean up operations. The calamity happened to the West of the railway station at a height of 360 m above sea level and in the vicinity of the Semois river (200 m to the South). From a geological point of view, the Formation of Florenville is outcropping at the site. This formation is characterized by an alternation of sandy sediments and sandstone layers. Locally the rock layer are porous allowing vertical migration of the water. The formation is an important but vulnerable aquifer. Further to the South, water is extracted from the aquifer in large quantities for both public distribution and bottling purposes. The spilled product, 5-methyl-2-hexanone (MIAK), has a typical fruity odour and its density is slightly lower than water. The product is relative mobile and fairly easy degraded biologically in low concentrations. (orig.)

  4. MIT/Draper Technology Development Partnership Project: Systems Analysis and On-Station Propulsion Subsystem Design

    National Research Council Canada - National Science Library

    Conklin, Theodore

    1998-01-01

    The objective of this thesis is to describe the process for, and the overall design that resulted from the MIT/Draper Project from August, 1996 to May, 1997, including the specific design of the on...

  5. Development and application of project management computer system in nuclear power station

    International Nuclear Information System (INIS)

    Chen Junpu

    2000-01-01

    According to the experiences in the construction of Daya Bay and Lingao nuclear power plants presents, the necessity to use the computers for management and their application in the nuclear power engineering project are explained

  6. 75 FR 39926 - Deer Creek Station Energy Facility Project (DOE/EIS-0415)

    Science.gov (United States)

    2010-07-13

    ... when wind energy is not available. Water resources concerns are related to erosion and sedimentation... withdrawal at Project start-up to fill the on-site water storage tank. Monitoring will take place at least...

  7. A summary of lessons learned at the Shippingport Station Decommissioning Project (SSDP)

    International Nuclear Information System (INIS)

    Crimi, F.P.; Mullee, G.R.

    1987-10-01

    This paper describes the lessons learned from a management perspective during decommissioning. The lessons learned are presented in a chronological sequence during the life of the project up to the present time. The careful analysis of the lessons learned and the implementation of corresponding actions have contributed toward improving the effectiveness of decommissioning as time progresses. The lessons learned should be helpful in planning future decommissioning projects

  8. Incorporating IGCC and CaO sorption-enhanced process for power generation with CO2 capture

    International Nuclear Information System (INIS)

    Chen, Shiyi; Xiang, Wenguo; Wang, Dong; Xue, Zhipeng

    2012-01-01

    Highlights: ► CaO sorption-enhanced process is incorporated with IGCC for CO 2 capture. ► IGCC–CCS is simplified using CaO sorption-enhanced process. ► The electricity efficiency is around 31–33% and CO 2 capture efficiency exceeds 95%. ► Parameters such as sorption pressure influence the system performance. -- Abstract: Integrated gasification combined cycle (IGCC) is a power generation technology to convert solid fuels into electricity. IGCC with CCS is regarded as a promising option to mitigate CO 2 emission. In this paper, the CaO sorption-enhanced process is incorporated downstream with coal gasification to produce a hydrogen-rich stream for electricity production and CO 2 separation. A WGS-absorber substitutes the high- and low-temperature water–gas shift reactors and desulfurization units in conventional IGCC–CCS to produce a hydrogen-rich stream, which is sent onto a gas turbine. CaO is used as the sorbent to enhance hydrogen production and for CO 2 capture. Regeneration of CaO is completed via calcination in a regenerator vessel. The IGCC with CaO sorption-enhanced process is modeled and simulated using Aspen Plus software. Two commercial available gasification technologies, Shell and Texaco, are integrated with the sorption-enhanced process. The results showed IGCC with CaO sorption-enhanced process has a satisfactory system performance. Even though the net electricity efficiency is not as high as expected, just around 30–33%, the system has a high CO 2 capture efficiency ∼97% and low pollutant emissions. Moreover, compared with conventional IGCC–CCS, the schematic diagram of the IGCC–CCS process is simplified. Parameters that affect the plant performance are analyzed in the sensitive analysis, including WGS-absorber temperature, H 2 O/CO ratio, pressure, etc. Some challenges to the system are also discussed.

  9. Data processing project management in the construction of plants and power stations

    International Nuclear Information System (INIS)

    Huelsen, H.; Hayen, W.

    1987-01-01

    The requirements of project management in plant construction i.e. basic data, supervision and control became more and more detailed. These requirements can only satisfactorily be met with the help of data processing. Piping design requires up to 50% of the whole amount of engineering in design and management of plant construction. We present data processing project management system which explains the connections of single aspects. Its connections consists of: collection of basic data, plant design and installation, supervision of planning and installation, planning and calculation, collection, use, administration and approval of plan data, procurement material, construction of the model (1:25), and installation. (orig.) [de

  10. Feasibility, Design and Construction of a Small Hydroelectric Power Generation Station as a Student Design Project.

    Science.gov (United States)

    Peterson, James N.; Hess, Herbert L.

    An undergraduate capstone engineering design project now provides hydroelectric power to a remote wilderness location. Students investigated the feasibility of designing, building, and installing a 4kW hydroelectric system to satisfy the need for electric power to support the research and teaching functions of Taylor Ranch, a university facility…

  11. Projected costs of generating electricity from power stations for commissioning in the period 1995-2000

    International Nuclear Information System (INIS)

    1989-01-01

    The study reviews the projected electricity generation costs for the base load power generation options expected to be available in the medium term, using an agreed common economic methodology. Cost projections were obtained for nuclear and fossil fuelled plants that could in principle be commissioned in the mid-1990s, or shortly thereafter, although not all countries plan to commission plants at that time. The major changes in expectations compared with earlier studies, apart from those associated with changed perceptions of fossil fuel prices, include significantly lower nuclear investment costs for the United States, associated with an improved design and the expectation of achieving shorter construction periods than projected in the 1985 study, and generally lower nuclear fuel costs. Some countries project higher operation and maintenance costs for either coal-fired or nuclear plant or both. In the case of coal-fired plants these may be associated with the extra costs of operating desulphurisation equipment. The most marked change in nuclear operating and maintenance costs has taken place in the United States, where these costs are now expected to be twice as large as the projected nuclear fuel costs. There remain major differences in investment cost expectations between countries. The reasons for these differences have been examined in previous studies. They arise from differences in factor costs, regulatory approach, design and siting, and exchange rates which do not adequately reflect the differences in the capital investment costs between countries. In brief, most OECD countries continue to expect nuclear power to have a lower levelised generating cost than coal-fired generation when using their own technical and economic assumptions

  12. Method and system to estimate variables in an integrated gasification combined cycle (IGCC) plant

    Science.gov (United States)

    Kumar, Aditya; Shi, Ruijie; Dokucu, Mustafa

    2013-09-17

    System and method to estimate variables in an integrated gasification combined cycle (IGCC) plant are provided. The system includes a sensor suite to measure respective plant input and output variables. An extended Kalman filter (EKF) receives sensed plant input variables and includes a dynamic model to generate a plurality of plant state estimates and a covariance matrix for the state estimates. A preemptive-constraining processor is configured to preemptively constrain the state estimates and covariance matrix to be free of constraint violations. A measurement-correction processor may be configured to correct constrained state estimates and a constrained covariance matrix based on processing of sensed plant output variables. The measurement-correction processor is coupled to update the dynamic model with corrected state estimates and a corrected covariance matrix. The updated dynamic model may be configured to estimate values for at least one plant variable not originally sensed by the sensor suite.

  13. Speciation of major and selected trace elements in IGCC fly ash

    Energy Technology Data Exchange (ETDEWEB)

    Oriol Font; Xavier Querol; Frank E. Huggins; Jose M. Chimenos; Ana I. Fernandez; Silvia Burgos; Francisco Garcia Pena [Institute of Earth Sciences ' Jaume Almera' , Barcelona (Spain)

    2005-08-01

    The speciation of Ga, Ge, Ni, V, S and Fe in fly ash from IGCC power plant were investigated for possible further extraction process by combining conventional mineral and chemical analysis, leaching tests, wet sequential extraction, Moessbauer and XAFS spectroscopies. The results shown that Ge occurs mainly as water-soluble species, GeS and/or GeS{sub 2} and hexagonal GeO{sub 2}. Ga is present as an oxide, Ni occurs mainly as nickeline (NiAs), with minor proportions of Ni arsenates and vanadium as V(III) with minor amounts of V(IV) in the aluminosilicate glass matrix. Pyrrhotite and wurtzite-sphalerite are sulfide species containing Fe and Zn, but an important fraction of iron is also present in the aluminosilicate glass. These clear differences between the speciation of the above elements in this material and those reported for fly ash from conventional PC combustion. 15 refs., 8 figs., 5 tabs.

  14. Wabash River Coal Gasification Repowering Project: A DOE Assessment; FINAL

    International Nuclear Information System (INIS)

    National Energy Technology Laboratory

    2002-01-01

    The goal of the U.S. Department of Energy (DOE) Clean Coal Technology Program (CCT) is to furnish the energy marketplace with a number of advanced, more efficient, and environmentally responsible coal utilization technologies through demonstration projects. These projects seek to establish the commercial feasibility of the most promising advanced coal technologies that have developed beyond the proof-of-concept stage. This document serves as a DOE post-project assessment (PPA) of a project selected in CCT Round IV, the Wabash River Coal Gasification Repowering (WRCGR) Project, as described in a Report to Congress (U.S. Department of Energy 1992). Repowering consists of replacing an existing coal-fired boiler with one or more clean coal technologies to achieve significantly improved environmental performance. The desire to demonstrate utility repowering with a two-stage, pressurized, oxygen-blown, entrained-flow, integrated gasification combined-cycle (IGCC) system prompted Destec Energy, Inc., and PSI Energy, Inc., to form a joint venture and submit a proposal for this project. In July 1992, the Wabash River Coal Gasification Repowering Project Joint Venture (WRCGRPJV, the Participant) entered into a cooperative agreement with DOE to conduct this project. The project was sited at PSI Energy's Wabash River Generating Station, located in West Terre Haute, Indiana. The purpose of this CCT project was to demonstrate IGCC repowering using a Destec gasifier and to assess long-term reliability, availability, and maintainability of the system at a fully commercial scale. DOE provided 50 percent of the total project funding (for capital and operating costs during the demonstration period) of$438 million. Construction for the demonstration project was started in July 1993. Pre-operational tests were initiated in August 1995, and construction was completed in November 1995. Commercial operation began in November 1995, and the demonstration period was completed in December

  15. Analysis of return on investment for Naval air station fallon energy project Alternatives

    Science.gov (United States)

    2017-06-01

    Manager (Justin Sielsch, personal communication ). Lack of in-house skill related to HVAC retrofits would require substantial effort by Public Works ...bill. An ESPC project is financed by the contractor performing the work . The contractor guarantees a certain annual energy savings because of their... work . The Navy installation uses the annual savings from its energy budget to pay back the contractor. ESPCs include contractor performance

  16. Application of point system in the project control of Ling'ao Nuclear Power Station

    International Nuclear Information System (INIS)

    Xie ahai

    2005-01-01

    Schedule control and cost control are very complicated issues even we set up the detail schedules and engineering measurements requirements for erection of a nuclear power project. In order to solve these problems, a Point System is used in Ling Ao (LA) Nuclear Power Project. This paper introduces the method. The Point System is a measurement system of workload. The measurement unit of any erection works is a Point only. A Point of workload is defined as the equivalent measurement quantities, which could be completed by a relevant skill worker within an hour. A set of procedure manuals for different installations has been set up. The calculation models of equipment installation, piping, cabling are addressed for example in the paper. The application of the Point System in the schedule control is shown in the paper. The following issues are highlighted: to define the duration of a piping activity in the Project Level 2 Schedule, to draught the curves of Point Schedules for different erection fields, to analyze the productive efficiency, to define erection quota of each month for different erection teams, to follow up the erection progress on site. The application of the Point System in the payment of erection contract is outlined. The calculation formula of a monthly payment is given. The advantage of the payment calculation method is discussed, for example, more accurate, very easy and clearly to check the measurement quantities completed on site, to control lump-sum cost. (authors)

  17. An aerial radiological survey of the South Texas Project Electric Generating Station and surrounding area, Bay City, Texas

    International Nuclear Information System (INIS)

    Thompson, J.M.

    1988-12-01

    An aerial radiological survey was conducted over the South Texas Project Electric Generating Station (STPEGS) near Bay City, Texas, during the period 25 March to 4 April 1988. The purpose of the 259-square-kilometer (100-square-mile) survey was to document the terrestrial gamma environment of the plant and surrounding area. An exposure rate contour map at 1 meter above ground level (AGL) was constructed from the gamma data and overlaid on an aerial photograph and map of the area. Exposure rates were observed up to 10μR/h over land. No areas of enhanced exposure rates were observed. Ground-based exposure rate measurements and soil samples were obtained to support the aerial data. Oblique aerial photographs of the plant were also acquired during the survey. 9 refs., 4 figs., 1 tab

  18. Projected costs of generating electricity from nuclear and coal-fired power stations for commissioning in 1995

    International Nuclear Information System (INIS)

    1986-01-01

    This report updates and extends the previous NEA study, ''The Costs of Generating Electricity in Nuclear and Coal-fired Power Stations'', published by the OECD in late 1983. Despite the changed expectations concerning coal prices and the considerable movements in exchange rates since the first study was completed, the conclusions remain essentially the same. Nuclear Power is projected to be economically superior by a significant margin to coal-fired plants for base load electricity production in Europe, Japan and some regions of North America. In areas of North America in close proximity to supplies of cheap coal, this would be the more economic fuel, unless future nuclear investment costs can be reduced to match the best US and Canadian experience. In all regions considered, the economic advantage of both coal and nuclear over oil and gas-fired plants for commissioning in the mid-1990s is expected to be substantial. These conclusions are based on an analysis of cost projections for 900 MWe to 1400 MWe Light Water Reactors to be commissioned in 1995, operating at a levelised load factor of about 72 per cent over an assumed 25 years economic life and calculated with a 5 per cent (real) discount rate. This parallels the reference reactor selected for the NEA report ''The Economics of the Nuclear Fuel Cycle'', which was published by the OECD in June 1985, though it deviates somewhat from the reference conditions of the previous generation cost study. Contemporary coal-fired stations ranging in capacity from 330 MWe to 700 MWe with the same assumed economic life and load factor provide the basis for comparison. Some data are included on CANDU Pressurised Heavy Water Reactors, and a brief comment is annexed on the relevance of the comparisons for the smaller plants that may be of interest to countries with smaller electricity networks or where special circumstances apply

  19. Station, local, and public participation plan, Salt Repository Project Office, Deaf Smith County, Texas: Draft

    International Nuclear Information System (INIS)

    1987-12-01

    The purpose of the SRPO State, Local, and Public Participation Plan is to provide an ''umbrella'' document for the ongoing and planned institutional involvement. One of the major goals is to develop project-specific outreach and participation programs based on input received from interested parties. DOE's commitment to interaction and information programs is to be demonstrated by conducting activities in an open environment, listening to and understanding the concerns of interested parties, actively involving affected parties in the program, executing faithfully the intent of Congress expressed through the NWPA, and providing equitable treatment for all affected parties. 1 fig., 2 tabs

  20. Corrosion of ceramics for slag removal in IGCC-power plants; Korrosion von Keramiken fuer die Fluessigascheabscheidung in IGCC-Kraftwerken

    Energy Technology Data Exchange (ETDEWEB)

    Fuerst, Denny

    2012-06-12

    Coal gasification and the subsequent production of electricity from syngas in combined-cycle powerplants allows plant efficiencies of up to 43% (LHV). Existing technologies allow up to 50% in the short term. Efficiencies beyond 50% however, require concepts and technologies that still need a certain amount of research and development. One such method to raise plant efficiencies would be a high temperature (at temperatures above the melting point of the ash) syngas cleaning. To effectively utilize the heat from the syngas and enable high turbine inlet temperatures, it is necessary to remove slag particles from the hot gas. The feasibility of such a hot syngas cleaning has been successfully demonstrated for the Pressurized Pulverized Coal Combustion (PPCC) by passing the hot gas through a bed of ceramic balls for slag removal. In order to apply this concept to IGCC powerplants the slag resistance of various ceramic materials had to be investigated under gasifying conditions. Therefore, lab-made ceramics and commercially available refractory materials where treated with liquid slag at 1600 C in a number of reducing atmospheres. At first, three synthetic slags with different basicity were used and after evaluating the results, selected materials were treated with a gasifier slag under continuous conditions. It was shown that both slag and ceramic have to be adjusted to ensure a sufficient corrosion resistance of the ceramic bed for slag removal. Furthermore, the impact of the porosity of the utilized ceramic on the corrosion resistance was shown. The composition of the reducing atmosphere (mainly the partial pressure of Oxygen) affected both physical and chemical properties of the slag via slag components that could easily be reduced or oxidized. The materials most suitable for use in slag separation were found to be dense chromium oxide and other ceramics containing a high amount of chromium oxide. [German] Mit Kohlevergasung und der anschliessenden Stromerzeugung in

  1. Assessment of the Professional Training Course under Watershed Project at Fatehjang Field Station, Punjab, Pakistan

    International Nuclear Information System (INIS)

    Khan, M. N.; Hassan, T.; Shah, H.; Abid, S.; Raza, I.; Abbasi, S. S.

    2015-01-01

    Watershed Project organizing different professional trainings to create awareness about water saving technologies as solar powered irrigation system, drip irrigation, sprinkler irrigation, micro catchment, rooftop rainwater harvesting and irrigation scheduling. Therefore, the project activities also include the training of the professionals from the line departments for the demonstrated technologies to foster the process of adoption. For this purpose Climate and Alternate Energy Water Resources Institute, NARC, organized a professional training on Water Rehabilitation and Irrigation Technology Improvements in April, 2014 in collaboration with ICARDA and USDA. Twenty seven professionals from different organizations and departments namely; Al-Mustafa Development Network (ADN), Taleem Foundation, Islamic International University (IIUI) Islamabad, National Agricultural Research Centre (NARC), National Centre for Rural Development (NCRD), National Rural Support Programme (NRSP), On-Farm Water Management (OFWM), Water Management (WM), Potohar Organization for Development Advocacy (PODA), Quaid-i-Azam University (QAU) and Environmental Sciences actively participated in the professional training. The post-training assessment showed that it had positive impact on the awareness of professionals. Majority of the participants were strongly and merely agreed upon the training practicality, technologies adoption probability and its advantages at farmer's field. Overall, most of the training participants were satisfied with the knowledge sharing presentations about the specific technologies discussed during the training. (author)

  2. Techno-economic analysis of lignite fuelled IGCC with CO{sub 2} capture. Comparing fluidized bed and entrained flow gasifiers

    Energy Technology Data Exchange (ETDEWEB)

    Liu, Guangjian; Wu, Zhen; Zhang, Haiying [North China Electric Power Univ., Beijing (China). School of Energy and Power Engineering

    2013-07-01

    Integrated coal gasification combined cycle (IGCC) plants with pre-combustion capture of CO{sub 2} represent one of the most promising options for generating low-cost decarbonized power using bituminous coals. This work systematically quantify the effect of coal rank on the efficiency and economics of IGCC systems with CO2 capture and storage (CCS), with a special focus on comparison of systems using fluidized-bed gasifier (U-GAS) and entrained flow gasifier (Shell). It was found that the Shell IGCCs are little affect by low rank coal after pre-drying in terms of thermal efficiency and the levelized cost of electricity (LCOE) is only increase by 2-6% for lignite cases with and without CCS compared with bituminous coal cases. The specific CO{sub 2} emissions of U-GAS gasifier based lignite fuelled IGCC with CCS is 198 g/kWhe, almost two times of shell gasifier cases, mainly due to lower carbon conversion in the gasifier and the higher methane in the raw gas of gasifier. However, the total capital cost and COE of U-Gas IGCCs are 15-20% less than that of Shell IGCCs because of lower capital cost of gasifier, coal drying units and air separate units per kWe.

  3. 75 FR 51248 - Record of Decision and Floodplain Statement of Findings; Kemper County IGCC Project, Kemper...

    Science.gov (United States)

    2010-08-19

    ... status. As many as 32 miles of perennial stream channels and 24 miles of intermittent stream channels... through the lake should remain within its historical range. The use of sedimentation ponds for water... floodplain from the flow channel. Total storm-event runoff volumes could increase by up to 637 acre-feet (ac...

  4. IGCC power plant integrated to a Finnish pulp and paper mill. IEA Bioenergy. Techno-economic analysis activity

    Energy Technology Data Exchange (ETDEWEB)

    Koljonen, T.; Solantausta, Y. [VTT Energy, Espoo (Finland). New Energy Technologies; Salo, K.; Horvath, A. [Carbona Inc. (Finland)

    1999-11-01

    In Finland, the pulp and paper industry is the largest consumer of energy among the industries and its power demand will increase due to economical and strict environ- mental requirements. The ageing of oil and biomass boilers in Finland also represents a window of opportunity for the introduction of new environmentally sound technology with a high efficiency in power production, e.g., in biomass gasification. This site-specific study describes the technical and economic feasibility of a biomass gasification combined cycle producing heat and power for a typical Finnish pulp and paper mill. The mill produces SC (super calantered) paper 500 000 ADt/a. The paper mill employs sulphate pulp and GW (ground wood) pulp. The capacity of the pulp mill is 400 000 ADt/a (air dry ton/year) of which 120 000 ADt/a is used at the site. The heat demand of the integrate is covered by a recovery boiler and a bark boiler. A condensing steam turbine with two extractions generates electricity for the mill. The aim is to replace an old bark boiler by an IGCC (Integrated Gasification Combined Cycle) to enhance the economy and environmental performance of the power plant. The IGCC feasibility study is conducted for an pulp and paper integrate because of its suitable infrastructure for IGCC and a large amount of wood waste available at the site. For comparison, the feasibility of an IGCC integrated to a pulp mill is also assessed. The IGCC concept described is based on research and development work performed by Carbona, Inc., who acquired the rights for know-how of Enviropower, Inc. The operation and design of the IGCC concept is based on a 20 MWe gas turbine (MW151). The heat of gas turbine exhaust gas is utilised in a HRSG (Heat Recovery Steam Generator) of two pressure levels to generate steam for the pulp and paper mill and the steam turbine. The MCC power plant operates in condensing mode. The total investment cost of the IGCC plant is estimated at FIM 417 million (USD 83.4 million

  5. IGCC power plant integrated to a Finnish pulp and paper mill. IEA Bioenergy. Techno-economic analysis activity

    International Nuclear Information System (INIS)

    Koljonen, T.; Solantausta, Y.

    1999-01-01

    In Finland, the pulp and paper industry is the largest consumer of energy among the industries and its power demand will increase due to economical and strict environ- mental requirements. The ageing of oil and biomass boilers in Finland also represents a window of opportunity for the introduction of new environmentally sound technology with a high efficiency in power production, e.g., in biomass gasification. This site-specific study describes the technical and economic feasibility of a biomass gasification combined cycle producing heat and power for a typical Finnish pulp and paper mill. The mill produces SC (super calantered) paper 500 000 ADt/a. The paper mill employs sulphate pulp and GW (ground wood) pulp. The capacity of the pulp mill is 400 000 ADt/a (air dry ton/year) of which 120 000 ADt/a is used at the site. The heat demand of the integrate is covered by a recovery boiler and a bark boiler. A condensing steam turbine with two extractions generates electricity for the mill. The aim is to replace an old bark boiler by an IGCC (Integrated Gasification Combined Cycle) to enhance the economy and environmental performance of the power plant. The IGCC feasibility study is conducted for an pulp and paper integrate because of its suitable infrastructure for IGCC and a large amount of wood waste available at the site. For comparison, the feasibility of an IGCC integrated to a pulp mill is also assessed. The IGCC concept described is based on research and development work performed by Carbona, Inc., who acquired the rights for know-how of Enviropower, Inc. The operation and design of the IGCC concept is based on a 20 MWe gas turbine (MW151). The heat of gas turbine exhaust gas is utilised in a HRSG (Heat Recovery Steam Generator) of two pressure levels to generate steam for the pulp and paper mill and the steam turbine. The MCC power plant operates in condensing mode. The total investment cost of the IGCC plant is estimated at FIM 417 million (USD 83.4 million

  6. Report of year 2000 version on feasibility study for joint implementation. Repowering project of Ashuganji Thermal Power Station

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2000-03-01

    Discussions were given on the repowering project of Ashuganji Thermal Power Station in the People's Republic of Bangladesh to link the project to the clean development mechanism (CDM). The project calls for adding gas turbines respectively having output of 31 MW to the existing units No. 3, 4 and 5 (each having an output of 150 MW) to make the plant into the waste gas re-combustion type compound cycle system. The construction cost would be 140 billion yen. The annual reduction of fuel per unit would be 28 kt, which can result in reduction of 2.1 million tons from the three units over the period of 25 years. The annual reduction in CO2 emission from a unit would be 77 kt, resulting in reduction of 5.8 million tons from the three units over 25 years. The return on investment effect was evaluated. In the main case (the output increase as a result of the repowering is used to supplement the current power supply shortage), the required period to recover the investment will be ten years on the basis of introducing private sector fund, but the internal profitability would be 8.09%, being far below the discount rate of 15%, and the current discount worth is also negative, hence the project would not be feasible. However, since there are no problems in repaying the loans, application of the low-interest special Yen loan is desired to eliminate the state of chronic power shortage. The discharge right transaction case (550 yen/ton of CO2) was also found unworkable to recover the investment. (NEDO)

  7. Report of year 2000 version on feasibility study for joint implementation. Repowering project of Ashuganji Thermal Power Station

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2000-03-01

    Discussions were given on the repowering project of Ashuganji Thermal Power Station in the People's Republic of Bangladesh to link the project to the clean development mechanism (CDM). The project calls for adding gas turbines respectively having output of 31 MW to the existing units No. 3, 4 and 5 (each having an output of 150 MW) to make the plant into the waste gas re-combustion type compound cycle system. The construction cost would be 140 billion yen. The annual reduction of fuel per unit would be 28 kt, which can result in reduction of 2.1 million tons from the three units over the period of 25 years. The annual reduction in CO2 emission from a unit would be 77 kt, resulting in reduction of 5.8 million tons from the three units over 25 years. The return on investment effect was evaluated. In the main case (the output increase as a result of the repowering is used to supplement the current power supply shortage), the required period to recover the investment will be ten years on the basis of introducing private sector fund, but the internal profitability would be 8.09%, being far below the discount rate of 15%, and the current discount worth is also negative, hence the project would not be feasible. However, since there are no problems in repaying the loans, application of the low-interest special Yen loan is desired to eliminate the state of chronic power shortage. The discharge right transaction case (550 yen/ton of CO2) was also found unworkable to recover the investment. (NEDO)

  8. The 8000 MW project

    Energy Technology Data Exchange (ETDEWEB)

    Ubis, T. [Repsol YPF (Spain); Bressan, L. [Foster Wheeler (Italy); O' Keefe, L. [Texaco Power and Gasification (Netherlands)

    2001-04-01

    The article describes the heavy oil integrated gasification combined cycle (IGCC) complex designed to process the high sulfur by-products from the nearby Petronor Refinery (in Spain) and produce hydrogen and electricity. The process units and their feedstocks are described. The design and operation of the gasification unit and what it achieves are also described. The raw syngas from the scrubbers in the gasification unit is processed so that it can be fed to the combined cycle. How raw gas syngas cooling is carried out is described in outline. In the sulfur recovery units, the MDEA-rich solution (from the absorption tower) is expanded in a hydraulic turbine to recover power to pump the lean MDEA stream to the absorption tower. The Power Island is described under the sub-headings of: (i) quench gasification technology; (ii) IGCC complex performance; (iii) environmental compact; (iv) the site; (v) project implementation program and (vi) investment cost.

  9. Report of space experiment project, 'Rad Gene', performed in the International Space Station Kibo

    International Nuclear Information System (INIS)

    Ohnishi, Takeo; Takahashi, Akihisa; Nagamatsu, Aiko

    2010-01-01

    This report summarizes results of the project in the title adopted by Japan Aerospace Exploration Agency (JAXA) (in 2000) aiming to elucidate the biological effect of space environment, and contains 3 major parts of the process of the experiment, and of findings by analysis after flight and in radioadaptive response. The process for the experiment includes training of the experimenter crew (Dr. S. Magnus) in JAXA, preparation of samples (frozen cells with normal and mutated p53 genes derived from human lymphoblast TK6) and their transfer to the Space Shuttle Endeavour STS-126 launched on Nov. 15, 2008 (Japanese time) for cell culturing in Feb., 2009. Analyses after flight back to the Kennedy Space Center on Mar. 29, 2009, done on the ground in Japan thereafter include the physical evaluation, confirmation of DNA damage, and phenotypic expression with DNA- and protein-arrays (genes induced for expression of p53-related phenotypes in those cells which were stored frozen in the space, thawed on the ground and then cultured, genes induced for expressing the phenotypes and p53-related proteins expressed in cells cultured in space). Physically, total absorbed dose and dose equivalent are found to be respectively 43.5 mGy and 71.2 mSv (0.5 mSv/day). Interestingly, the biologically estimated dose by DNA-double strand breaks detected by γH2AX staining, 94.5 mSv (0.7 mSv/day), in living, frozen cells in space, is close to the above physical dose. Expression experiments of p53-related phenotypes have revealed that expression of 750 or more genes in 41,000 genes in the array is changed: enhanced or suppressed by space radiation, micro-gravity and/or their mixed effects in space environment. In 642 protein antibodies in the array, 2 proteins are found enhanced and 8, suppressed whereas heat-shock protein is unchanged. Radioadaptive response is the acquisition of radio-resistance to acute exposure by previous irradiation of small dose (window width 20-100 mSv) in normal p53

  10. Model Based Optimal Sensor Network Design for Condition Monitoring in an IGCC Plant

    Energy Technology Data Exchange (ETDEWEB)

    Kumar, Rajeeva; Kumar, Aditya; Dai, Dan; Seenumani, Gayathri; Down, John; Lopez, Rodrigo

    2012-12-31

    This report summarizes the achievements and final results of this program. The objective of this program is to develop a general model-based sensor network design methodology and tools to address key issues in the design of an optimal sensor network configuration: the type, location and number of sensors used in a network, for online condition monitoring. In particular, the focus in this work is to develop software tools for optimal sensor placement (OSP) and use these tools to design optimal sensor network configuration for online condition monitoring of gasifier refractory wear and radiant syngas cooler (RSC) fouling. The methodology developed will be applicable to sensing system design for online condition monitoring for broad range of applications. The overall approach consists of (i) defining condition monitoring requirement in terms of OSP and mapping these requirements in mathematical terms for OSP algorithm, (ii) analyzing trade-off of alternate OSP algorithms, down selecting the most relevant ones and developing them for IGCC applications (iii) enhancing the gasifier and RSC models as required by OSP algorithms, (iv) applying the developed OSP algorithm to design the optimal sensor network required for the condition monitoring of an IGCC gasifier refractory and RSC fouling. Two key requirements for OSP for condition monitoring are desired precision for the monitoring variables (e.g. refractory wear) and reliability of the proposed sensor network in the presence of expected sensor failures. The OSP problem is naturally posed within a Kalman filtering approach as an integer programming problem where the key requirements of precision and reliability are imposed as constraints. The optimization is performed over the overall network cost. Based on extensive literature survey two formulations were identified as being relevant to OSP for condition monitoring; one based on LMI formulation and the other being standard INLP formulation. Various algorithms to solve

  11. Characterizing toxic emissions from a coal-fired power plant demonstrating the AFGD ICCT Project and a plant utilizing a dry scrubber/baghouse system: Bailly Station Units 7 and 8 and AFGD ICCT Project. Final report. Final report

    Energy Technology Data Exchange (ETDEWEB)

    Dismukes, E.B.

    1994-10-20

    This report describes results of assessment of the risk of emissions of hazardous air pollutants at one of the electric power stations, Bailly Station, which is also the site of a Clean Coal Technology project demonstrating the Pure Air Advanced Flue Gas Desulfurization process (wet limestone). This station represents the configuration of no NO{sub x} reduction, particulate control with electrostatic precipitators, and SO{sub 2} control with a wet scrubber. The test was conducted September 3--6, 1993. Sixteen trace metals were determined along with 5 major metals. Other inorganic substances and organic compounds were also determined.

  12. SUPPORT OF GULF OF MEXICO HYDRATE RESEARCH CONSORTIUM: ACTIVITIES TO SUPPORT ESTABLISHMENT OF A SEA FLOOR MONITORING STATION PROJECT

    Energy Technology Data Exchange (ETDEWEB)

    Paul Higley; J. Robert Woolsey; Ralph Goodman; Vernon Asper; Boris Mizaikoff; Angela Davis

    2005-08-01

    data logger, (G) Sufficient energy supply and normal functioning of the pressure compensated battery even following recharge after the first deployment, (H) Survival of the acoustic modem following both deployments though it was found to have developed a slow leak through the transducer following the second deployment due, presumably, to deployment in excess of 300m beyond its rating. (2) Progress on the Sea Floor Probe: (A) The Sea Floor Probe and its delivery system, the Multipurpose sled have been completed, (B) The probe has been modified to penetrate the <1m blanket of hemipelagic ooze at the water/sea floor interface to provide the necessary coupling of the accelerometer with the denser underlying sediments, (C) The MPS has been adapted to serve as an energy source for both p- and s-wave studies at the station as well as to deploy the horizontal line arrays and the SFP. (3) Progress on the Electromagnetic Bubble Detector and Counter: (A) Components for the prototype have been assembled, including a dedicated microcomputer to control power, readout and logging of the data, all at an acceptable speed, (B) The prototype has been constructed and preliminary data collected, (C) The construction of the field system is underway. (4) Progress on the Acoustic Systems for Monitoring Gas Hydrates: (A) Video recordings of bubbles emitted from a seep in Mississippi Canyon have been made from a submersible dive and the bubbles analyzed with respect to their size, number, and rise rate. These measurements have been used to determine the parameters to build the system capable of measuring gas escaping at the site of the monitoring station, (B) Laboratory tests performed using the project prototype have produced a conductivity data set that is being used to refine parameters of the field model. (5) Progress on the Mid-Infrared Sensor for Continuous Methane Monitoring: (A) Preliminary designs of mounting pieces for electrical components of ''sphereIR'' have

  13. National Account Energy Alliance Final Report for the Basin Electric Project at Northern Border Pipeline Company's Compressor Station #7, North Dakota

    Energy Technology Data Exchange (ETDEWEB)

    Sweetzer, Richard [Exergy Partners Corp.; Leslie, Neil [Gas Technology Institute

    2008-02-01

    A field research test and verification project was conducted at the recovered energy generation plant at Northern Border Pipeline Company Compressor Station #7 (CS#7) near St. Anthony. Recovered energy generation plant equipment was supplied and installed by ORMAT Technologies, Inc. Basin Electric is purchasing the electricity under a purchase power agreement with an ORMAT subsidiary, which owns and operates the plant.

  14. Economic evaluation of pre-combustion CO2-capture in IGCC power plants by porous ceramic membranes

    International Nuclear Information System (INIS)

    Franz, Johannes; Maas, Pascal; Scherer, Viktor

    2014-01-01

    Highlights: • Process simulations of IGCC with pre-combustion capture via membranes were done. • Most promising technology is the water–gas-shift-membrane-reactor (WGSMR). • Energetic evaluations showed minimum efficiency loss of 5.8%-points for WGSMR. • Economic evaluations identified boundary limits of membrane technology. • Cost of electricity for optimum WGSMR-case is 57 €/MW h under made assumptions. - Abstract: Pre-combustion-carbon-capture is one of the three main routes for the mitigation of CO 2 -emissions by fossil fueled power plants. Based on the data of a detailed technical evaluation of CO 2 -capture by porous ceramic membranes (CM) and ceramic membrane reactors (WGSMR) in an Integrated-Gasification-Combined-Cycle (IGCC) power plant this paper focuses on the economic effects of CO 2 -abatement. First the results of the process simulations are presented briefly. The analysis is based on a comparison with a reference IGCC without CO 2 -capture (dry syngas cooling, bituminous coal, efficiency of 47.4%). In addition, as a second reference, an IGCC process with CO 2 removal based on standard Selexol-scrubbing is taken into account. The most promising technology for CO 2 -capture by membranes in IGCC applications is the combination of a water gas shift reactor and a H 2 -selective membrane into one water gas shift membrane reactor. For the WGSRM-case efficiency losses can be limited to about 6%-points (including losses for CO 2 compression) for a CO 2 separation degree of 90%. This is a severe reduction of the efficiency loss compared to Selexol (10.3% points) or IGCC–CM (8.6% points). The economic evaluation is based on a detailed analysis of investment and operational costs. Parameters like membrane costs and lifetime, costs of CO 2 -certificates and annual operating hours are taken into account. The purpose of these evaluations is to identify the minimum cost of electricity for the different capture cases for the variation of the boundary

  15. Ion Exchange Technology Development in Support of the Urine Processor Assembly Precipitation Prevention Project for the International Space Station

    Science.gov (United States)

    Mitchell, Julie L.; Broyan, James L.; Pickering, Karen D.; Adam, Niklas; Casteel, Michael; Callahan, Michael; Carrier, Chris

    2012-01-01

    In support of the Urine Processor Assembly Precipitation Prevention Project (UPA PPP), multiple technologies were explored to prevent CaSO4 2H2O (gypsum) precipitation during the on-orbit distillation process. Gypsum precipitation currently limits the water recovery rate onboard the International Space Station (ISS) to 70% versus the planned 85% target water recovery rate. Due to its ability to remove calcium cations in pretreated augmented urine (PTAU), ion exchange was selected as one of the technologies for further development by the PPP team. A total of 13 ion exchange resins were evaluated in various equilibrium and dynamic column tests with solutions of dissolved gypsum, urine ersatz, PTAU, and PTAU brine at 85% water recovery. While initial evaluations indicated that the Purolite SST60 resin had the highest calcium capacity in PTAU (0.30 meq/mL average), later tests showed that the Dowex G26 and Amberlite FPC12H resins had the highest capacity (0.5 meq/mL average). Testing at the Marshall Spaceflight Center (MSFC) integrates the ion exchange technology with a UPA ground article under flight-like pulsed flow conditions with PTAU. To date, no gypsum precipitation has taken place in any of the initial evaluations.

  16. An electron beam flue gas treatment plant for a coal fired thermal power station. EBA demonstration plant in Chengdu thermal power station (China EBA Project)

    International Nuclear Information System (INIS)

    Doi, Yoshitaka; Nakanishi, Ikuo; Shi, Jingke

    1999-01-01

    Ebara's electron beam flue gas treatment plant was installed and is being demonstrated in Chengdu Thermal Power Station, Sichuan, China. The demonstration is proving that this plant is fully capable of meeting the target removal of sulfur dioxides from flue gas (flow rate : 300-thousand m 3 /h). Recovered by-products, namely ammonium sulfate and ammonium nitrate, from the treatment were actually tested as fertilizers, the result of which was favorable. The sale and distribution of these by-products are already underway. In May 1995, this plant was presented the certificate of authorization by China's State Power Corporation. It is noted that this was the first time a sulfur dioxide removal plant was certified as such in China. (author)

  17. SUPPORT OF GULF OF MEXICO HYDRATE RESEARCH CONSORTIUM: ACTIVITIES TO SUPPORT ESTABLISHMENT OF A SEA FLOOR MONITORING STATION PROJECT

    Energy Technology Data Exchange (ETDEWEB)

    Paul Higley; J. Robert Woolsey; Ralph Goodman; Vernon Asper; Boris Mizaikoff; Angela Davis

    2005-09-01

    resulting from matrix substances has been developed and will be incorporated into an optimized ''deepSniff'' program upon completion of initial systems tests of the ''sphereIR''; Continuation of spectroscopic investigations of the highly permeable polymer, poly(trimethylsilyl)propyne (PTMSP), as a potential sensing membrane for methane have continued and will continue in the following project period.; High-pressure multireflection ATR measurements simulating deep-sea conditions for evaluating environmental impact on the sensor system and multivariate data analysis continue. (6) Progress on the Seismo-acoustic Characterization of Sea Floor Properties and Processes at the Hydrate Monitoring Station: Work has continued on developing the electronic part of the acoustic logging system designed for investigating fine-scale temporal changes in sea floor acoustic reflection responses at the Gas Hydrate Monitoring Station; The hardware has been built and extensively tested.

  18. Proceedings of the Flat-Plate Solar Array Project Research Forum on the Design of Flat-Plate Photovoltaic Arrays for Central Stations

    Science.gov (United States)

    1983-01-01

    The Flat Plate Solar Array Project, focuses on advancing technologies relevant to the design and construction of megawatt level central station systems. Photovoltaic modules and arrays for flat plate central station or other large scale electric power production facilities require the establishment of a technical base that resolves design issues and results in practical and cost effective configurations. Design, qualification and maintenance issues related to central station arrays derived from the engineering and operating experiences of early applications and parallel laboratory reserch activities are investigated. Technical issues are examined from the viewpoint of the utility engineer, architect/engineer and laboratory researcher. Topics on optimum source circuit designs, module insulation design for high system voltages, array safety, structural interface design, measurements, and array operation and maintenance are discussed.

  19. Unconventional Coal in Wyoming: IGCC and Gasification of Direct Coal Liquefaction Residue

    Science.gov (United States)

    Schaffers, William Clemens

    Two unconventional uses for Wyoming Powder River Basin coal were investigated in this study. The first was the use of coal fired integrated gasification combined cycle (IGCC) plants to generate electricity. Twenty-eight different scenarios were modeled using AspenPlusRTM software. These included slurry, mechanical and dried fed gasifiers; Wyodak and Green River coals, 0%, 70%, and 90% CO2 capture; and conventional evaporative vs air cooling. All of the models were constructed on a feed basis of 6,900 tons of coal per day on an "as received basis". The AspenPlus RTM results were then used to create economic models using Microsoft RTM Excel for each configuration. These models assumed a 3 year construction period and a 30 year plant life. Results for capital and operating costs, yearly income, and internal rates of return (IRR) were compared. In addition, the scenarios were evaluated to compare electricity sales prices required to obtain a 12% IRR and to determine the effects of a carbon emissions tax on the sales price. The second part of the study investigated the gasification potential of residue remaining from solvent extraction or liquefaction of Powder River Basin Coal. Coal samples from the Decker mine on the Wyoming-Montana border were extracted with tetralin at a temperature of 360°C and pressure of 250 psi. Residue from the extraction was gasified with CO2 or steam at 833°C, 900°C and 975°C at pressures of 0.1 and 0.4 MPa. Product gases were analyzed with a mass spectrometer. Results were used to determine activation energies, reaction order, reaction rates and diffusion effects. Surface area and electron microscopic analyses were also performed on char produced from the solvent extraction residue.

  20. Degradation of TBC Systems in Environments Relevant to Advanced Gas Turbines for IGCC Systems

    Energy Technology Data Exchange (ETDEWEB)

    Gleeson, Brian [Univ. of Pittsburgh, PA (United States)

    2014-09-30

    Air plasma sprayed (APS) thermal barrier coatings (TBCs) are used to provide thermal insulation for the hottest components in gas turbines. Zirconia stabilized with 7wt% yttria (7YSZ) is the most common ceramic top coat used for turbine blades. The 7YSZ coating can be degraded from the buildup of fly-ash deposits created in the power-generation process. Fly ash from an integrated gasification combined cycle (IGCC) system can result from coal-based syngas. TBCs are also exposed to harsh gas environments containing CO2, SO2, and steam. Degradation from the combined effects of fly ash and harsh gas atmospheres has the potential to severely limit TBC lifetimes. The main objective of this study was to use lab-scale testing to systematically elucidate the interplay between prototypical deposit chemistries (i.e., ash and its constituents, K2SO4, and FeS) and environmental oxidants (i.e., O2, H2O and CO2) on the degradation behavior of advanced TBC systems. Several mechanisms of early TBC failure were identified, as were the specific fly-ash constituents responsible for degradation. The reactivity of MCrAlY bondcoats used in TBC systems was also investigated. The specific roles of oxide and sulfate components were assessed, together with the complex interplay between gas composition, deposit chemistry and alloy reactivity. Bondcoat composition design strategies to mitigate corrosion were established, particularly with regard to controlling phase constitution and the amount of reactive elements the bondcoat contains in order to achieve optimal corrosion resistance.

  1. Process, background and design criteria of the gas cleaning at Puertollano IGCC

    Energy Technology Data Exchange (ETDEWEB)

    Pisa, J. [Elcogas, Madrid (Spain)

    1998-11-01

    The Puertollano IGCC plant selected cooling by a water-tube boiler with upstream quenching at high velocities that requires a dust-free cooling gas at not less than 250{degree}C in order not to penalise the heat recovery efficiency. A filtration system for gas dedusting in the 250{degree}C temperature range has been installed and will be commissioned at the end of 1997. The gas cleaning concept is completed with a Venturi Scrubber, a COS hydrolysis reactor and a MDEA column to strip the sulphuric acid to yield clean gas. The gasification island is based upon the PRENFLO system which is an entrained-flow system with dry feeding. The selection of the filter system arrangement considered the limited operational experience in comparable operating conditions and acknowledged the flexibility of the filter system versus the cyclone-scrubber as far as easier load variation operation, the reduction of residues needing deposition and increased slag flow, as well as easier maintenance. Additionally to the ceramic test filters in Furstenhausen (PRENFLO) and Deer Park near Houston (SHELL), ceramic candle-type filter were selected in Buggenum and at Wabash River, and for the KoBra plant. The main criteria for the selection of the filter system and the type of candle were: separation efficiency to match clean gas limits; uniform distribution of the dust-laden gas to the filters; wear-resistant routing of the dust-laden gas flow; need for a supporting structure which must cope with sudden pressure fluctuations; optimised pulse gas system; and maintenance and repair. Based upon the above criteria, the PRENFLO concept requirements and the gas turbine specification, an arrangement with two pressure filter vessels with LLB design and filter elements manufactured by Schumacher has been installed in Puertollano. 2 figs., 3 tabs.

  2. Modelling and dynamics of an air separation rectification column as part of an IGCC power plant

    Energy Technology Data Exchange (ETDEWEB)

    Seliger, B.; Hanke-Rauschenbach, R.; Hannemann, F.; Sundmacher, K. [Otto Von Guericke University, Magdeburg (Germany)

    2006-04-15

    An Integrated Gasification Combined Cycle plant (IGCC) opens the well-proven and highly efficient combined cycle process to fossil fuels, like coal or heavy refinery residues. Such a plant thereby possesses a novel linkage of typical energy engineering related units, e.g. a gas turbine and typical process engineering parts, which in the present case is an air separation plant. Different responses from the connected components can cause undesired mass flow fluctuations within the system especially during changing load demands. The cryogenic rectification column, as the core of the air separation plant, strongly affects the system's transient behaviour. The upper part of such a heat-integrated double column, a packed column with structured packing, has therefore been more closely investigated in the present paper. For this purpose, a dynamic model of such a column has been developed which is also able to describe the pressure dynamics supposedly responsible for these mass flow fluctuations. The transient behaviour of the uncontrolled column is analysed and discussed with special regard to pressure dynamics. The column pressure responds to disturbances on two different time scales. The short-term response, which is in the range of 100-200 s, is governed by the transient behaviour of the fluid dynamics and is discussed in detail. The long-term response is dominated by the nonlinear dynamics of the concentration profiles. The time constant of this response depends strongly on the direction and intensity of the disturbance and takes from 10,000 up to several 100,000 s.

  3. Development of ITM oxygen technology for integration in IGCC and other advanced power generation

    Energy Technology Data Exchange (ETDEWEB)

    Armstrong, Phillip A. [Air Products And Chemicals, Inc., Allentown, PA (United States)

    2015-03-31

    -of-the-art cryogenic air separation technology in energy-intensive applications such as IGCC with and without carbon capture.

  4. Analysis of IGCC-based plants with carbon capture for an efficient and flexible electric power generation

    International Nuclear Information System (INIS)

    Sorgenfrei, Max

    2016-01-01

    In this work, systems based on the Integrated gasification combined cycle (IGCC) technology with carbon capture are analyzed regarding an efficient and flexible electric power generation. All analysis are related to a high-efficiency or low-cost IGCC base case with carbon capture which are both commercially available. In the high-efficiency base case, thermodynamic inefficiencies are determined based on a conventional exergy analysis. The gasifier followed by the combustion chamber of the gas turbine running on syngas are rated to the largest inefficiencies. Based on an advanced exergy analysis, the inefficiencies are split into an avoidable and unavoidable part as well as an endogenous and exogenous part. For example, it was found that about half of the inefficiencies within the gasifier are caused by other components of the overall system(exogenous part). Further investigations on the combination of both splitting types are presented. The gas turbine system is identified to be a major component and therefore a detailed model was developed using state-of-the-art technologies. Based on this model, 12 types of characteristic inefficiencies were determined and rated by their exergy destruction. Chemical-Looping Combustion (CLC) is one of the most promising technologies to enhance the available IGCC design. CLC uses composite metal particles acting as an oxygen carrier to transport oxygen from the air to the fuel gas through a redox-cycle. Thus, the inefficiencies associated with the combustion process decrease and the application of physical absorption for capturing CO 2 is replaced by an inherent CO 2 -capture. In this work, the most suitable oxygen carriers for CLC using syngas (nickel oxide and iron oxide) are analyzed at different temperatures. Moreover, different types of gasifier as well as CLC reactor designs are analyzed. Regenerating the oxygen carrier by steam and air, produces additional hydrogen from the reduction of steam which is further combusted

  5. Computer software design description for the Treated Effluent Disposal Facility (TEDF), Project L-045H, Operator Training Station (OTS)

    International Nuclear Information System (INIS)

    Carter, R.L. Jr.

    1994-01-01

    The Treated Effluent Disposal Facility (TEDF) Operator Training Station (OTS) is a computer-based training tool designed to aid plant operations and engineering staff in familiarizing themselves with the TEDF Central Control System (CCS)

  6. Stratospheric Aerosol and Gas Experiment, SAGE III on ISS, An Earth Science Mission on the International Space Station, Schedule Risk Analysis, A Project Perspective

    Science.gov (United States)

    Bonine, Lauren

    2015-01-01

    The presentation provides insight into the schedule risk analysis process used by the Stratospheric Aerosol and Gas Experiment III on the International Space Station Project. The presentation focuses on the schedule risk analysis process highlighting the methods for identification of risk inputs, the inclusion of generic risks identified outside the traditional continuous risk management process, and the development of tailored analysis products used to improve risk informed decision making.

  7. Thermodynamic simulation of CO{sub 2} capture for an IGCC power plant using the calcium looping cycle

    Energy Technology Data Exchange (ETDEWEB)

    Li, Y. [National Engineering Laboratory for Coal-Burning Pollutant Emission Reduction, Shandong University, Jinan (China); Zhao, C.; Ren, Q. [School of Energy and Environment, Southeast University, Nanjing (China)

    2011-06-15

    A CO{sub 2} capture process for an integrated gasification combined cycle (IGCC) power plant using the calcium looping cycle was proposed. The CO{sub 2} capture process using natural and modified limestone was simulated and investigated with the software package Aspen Plus. It incorporated a fresh feed of sorbent to compensate for the decay in CO{sub 2} capture activity during long-term cycles. The sorbent flow ratios have significant effect on the CO{sub 2} capture efficiency and net efficiency of the CO{sub 2} capture system. The IGCC power plant, using the modified limestone, exhibits higher CO{sub 2} capture efficiency than that using the natural limestone at the same sorbent flow ratios. The system net efficiency using the natural and modified limestones achieves 41.7% and 43.1%, respectively, at the CO{sub 2} capture efficiency of 90% without the effect of sulfation. (Copyright copyright 2011 WILEY-VCH Verlag GmbH and Co. KGaA, Weinheim)

  8. Feasibility analysis of gas turbine inlet air cooling by means of liquid nitrogen evaporation for IGCC power augmentation

    International Nuclear Information System (INIS)

    Morini, Mirko; Pinelli, Michele; Spina, Pier Ruggero; Vaccari, Anna; Venturini, Mauro

    2015-01-01

    Integrated Gasification Combined Cycles (IGCC) are energy systems mainly composed of a gasifier and a combined cycle power plant. Since the gasification process usually requires oxygen as the oxidant, an Air Separation Unit (ASU) is also part of the plant. In this paper, a system for power augmentation in IGCC is evaluated. The system is based on gas turbine inlet air cooling by means of liquid nitrogen spray. In fact, nitrogen is a product of the ASU, but is not always exploited. In the proposed plant, the nitrogen is first liquefied to be used for inlet air cooling or stored for later use. This system is not characterized by the limits of water evaporative cooling systems (the lower temperature is limited by air saturation) and refrigeration cooling (the effectiveness is limited by the pressure drop in the heat exchanger). A thermodynamic model of the system is built by using a commercial code for energy conversion system simulation. A sensitivity analysis on the main parameters is presented. Finally the model is used to study the capabilities of the system by imposing the real temperature profiles of different sites for a whole year and by comparing to traditional inlet air cooling strategies. - Highlights: • Gas turbine inlet air cooling by means of liquid nitrogen spray. • Humidity condensation may form a fog which provides further power augmentation. • High peak and off peak electric energy price ratios make the system profitable

  9. Ground-based multi-station spectroscopic imaging with ALIS. - Scientific highlights, project status and future prospects

    Science.gov (United States)

    Brändström; Gustavsson, Björn; Pellinen-Wannberg, Asta; Sandahl, Ingrid; Sergienko, Tima; Steen, Ake

    2005-08-01

    The Auroral Large Imaging System (ALIS) was first proposed at the ESA-PAC meeting in Lahnstein 1989. The first spectroscopic imaging station was operational in 1994, and since then up to six stations have been in simultaneous operation. Each station has a scientific-grade CCD-detector and a filter-wheel for narrow-band interference-filters with six positions. The field-of-view is around 70°. Each imager is mounted in a positioning system, enabling imaging of a common volume from several sites. This enables triangulation and tomography. Raw data from ALIS is freely available at ("http://alis.irf.se") and ALIS is open for scientific colaboration. ALIS made the first unambiguous observations of Radio-induced optical emissions at high latitudes, and the detection of water in a Leonid meteor-trail. Both rockets and satellite coordination are considered for future observations with ALIS.

  10. Future technological and economic performance of IGCC and FT production facilities with and without CO2 capture: Combining component based learning curve and bottom-up analysis

    NARCIS (Netherlands)

    Knoope, M.M.J.; Meerman, J.C.; Ramirez, C.A.; Faaij, A.P.C.

    2013-01-01

    This study aims to investigate the technological and economic prospects of integrated gasification facilities for power (IGCC) and Fischer–Tropsch (FT) liquid production with and without CCS over time. For this purpose, a component based experience curve was constructed and applied to identify the

  11. Support of Gulf of Mexico Hydrate Research Consortium: Activities of Support Establishment of a Sea Floor Monitoring Station Project

    Energy Technology Data Exchange (ETDEWEB)

    J. Robert Woolsey; Thomas McGee; Carol Lutken

    2008-05-31

    agency documents including the Final Technical Report to DOE covering Cooperative Agreement DEFC26-00NT40920 and Semiannual Progress Reports for this award, DE-FC26-02NT41628. Initial components of the observatory, a probe that collects pore-fluid samples and another that records sea floor temperatures, were deployed in MC118 in May of 2005. Follow-up deployments, planned for fall 2005, had to be postponed due to the catastrophic effects of Hurricane Katrina (and later, Rita) on the Gulf Coast. SFO completion, now anticipated for 2009-10, has, therefore, been delayed. Although delays caused scheduling and deployment difficulties, many sensors and instruments were completed during this period. Software has been written that will accommodate the data that the station retrieves, when it begins to be delivered. In addition, new seismic data processing software has been written to treat the peculiar data to be received by the vertical line array (VLA) and additional software has been developed that will address the horizontal line array (HLA) data. These packages have been tested on data from the test deployments of the VLA and on data from other, similar, areas of the Gulf (in the case of the HLA software). During the life of this Cooperative Agreement (CA), the CMRET conducted many cruises. Early in the program these were executed primarily to survey potential sites and test sensors and equipment being developed for the SFO. When MC118 was established as the observatory site, subsequent cruises focused on this location. Beginning in 2005 and continuing to the present, 13 research cruises to MC118 have been conducted by the Consortium. During September, 2006, the Consortium was able to secure 8 days aboard the R/V Seward Johnson with submersible Johnson SeaLink, a critical chapter in the life of the Observatory project as important documentation, tests, recoveries and deployments were accomplished during this trip (log appended). Consortium members have participated

  12. Optimal Site Selection of Wind-Solar Complementary Power Generation Project for a Large-Scale Plug-In Charging Station

    Directory of Open Access Journals (Sweden)

    Wenjun Chen

    2017-10-01

    Full Text Available The wind-solar hybrid power generation project combined with electric vehicle charging stations can effectively reduce the impact on the power system caused by the random charging of electric cars, contribute to the in-situ wind-solar complementary system and reduce the harm arising from its output volatility. In this paper, the site selection index system of a landscape complementary power generation project is established by using the statistical methods and statistical analysis in the literature. Subsequently, using the Analytic Network Process to calculate the index weight, a cloud model was used in combination with preference ranking organization method for enrichment evaluations to transform and sort uncertain language information. Finally, using the results of the decision-making for the location of the Shanghai wind-solar complementary project and by carrying out contrast analysis and sensitivity analysis, the superiority and stability of the decision model constructed in this study was demonstrated.

  13. SUPPORT OF GULF OF MEXICO HYDRATE RESEARCH CONSORTIUM: ACTIVITIES TO SUPPORT ESTABLISHMENT OF A SEA FLOOR MONITORING STATION PROJECT

    Energy Technology Data Exchange (ETDEWEB)

    Paul Higley; J. Robert Woolsey; Ralph Goodman; Vernon Asper; Boris Mizaikoff; Angela Davis; Bob A. Hardage; Jeffrey Chanton; Rudy Rogers

    2006-03-01

    The Gulf of Mexico Hydrates Research Consortium was established in 1999 to assemble leaders in gas hydrates research. The group is administered by the Center for Marine Resources and Environmental Technology, CMRET, at the University of Mississippi. The primary objective of the group is to design and emplace a remote monitoring station or sea floor observatory on the sea floor in the northern Gulf of Mexico by the year 2005, in an area where gas hydrates are known to be present at, or just below, the sea floor. This mission necessitates assembling a station that will monitor physical and chemical parameters of the sea water and sea floor sediments on a more-or-less continuous basis over an extended period of time. Development of the station has always included the possibility of expanding its capabilities to include biological monitoring, as a means of assessing environmental health. This possibility has recently received increased attention and the group of researchers working on the station has expanded to include several microbial biologists. Establishment of the Consortium has succeeded in fulfilling the critical need to coordinate activities, avoid redundancies and communicate effectively among researchers in this relatively new research arena. Complementary expertise, both scientific and technical, has been assembled to promote innovative research methods and construct necessary instrumentation. Initial components of the observatory, a probe that collects pore-fluid samples and another that records sea floor temperatures, were deployed in Mississippi Canyon 118 in May of 2005. Follow-up deployments are planned for fall 2005 and center about the use of the vessel M/V Ocean Quest and its two manned submersibles. The subs will be used to effect bottom surveys, emplace sensors and sea floor experiments and make connections between sensor data loggers and the integrated data power unit (IDP). Station/observatory completion is anticipated for 2007 following the

  14. The slag from ELCOGAS IGCC thermal power plant as raw material for the synthesis of glass-ceramic materials. Part I: Thermal behavior of the IGCC slag and synthesis of the parent glass.

    Energy Technology Data Exchange (ETDEWEB)

    Aineto, M.; Acosta, A. [University of Castilla La Mancha, Ciudad Real (Spain)

    2005-12-01

    We report here the results of the first phase of investigation on the melting behavior of the IGCC slag, and the use of this slag as raw component to produce glass ceramics. The vitrifying mixture named ECSCP, is composed of 40% slag, 30% glass cullet and 30% precipitated calcium carbonate obtained as a by-product in a sugar refining plant. This mixture was melted at 1450{sup o}C to obtain the ECSCP parent glass, that was then characterized and its crystallization kinetics studied by thermal analysis. The ECSCP glass exhibit a surface mechanism of crystallization, and will be used to produce anorthite/wollastonite glass ceramics in the second part of the investigation.

  15. The Forest Service, Rocky Mountain Research Station's Southwestern Borderlands Ecosystem Management Project: building on ten years of success [Abstract

    Science.gov (United States)

    Gerald J. Gottfried; Carleton B. Edminster

    2005-01-01

    The USDA Forest Service initiated the Southwestern Borderlands Ecosystem Management Project in 1994. The Project concentrates on the unique, relatively unfragmented landscape of exceptional biological diversity in southeastern Arizona and southwestern New Mexico. Its mission is to: "Contribute to the scientific basis for developing and implementing a comprehensive...

  16. Secure base stations

    NARCIS (Netherlands)

    Bosch, Peter; Brusilovsky, Alec; McLellan, Rae; Mullender, Sape J.; Polakos, Paul

    2009-01-01

    With the introduction of the third generation (3G) Universal Mobile Telecommunications System (UMTS) base station router (BSR) and fourth generation (4G) base stations, such as the 3rd Generation Partnership Project (3GPP) Long Term Evolution (LTE) Evolved Node B (eNB), it has become important to

  17. Degradation of TBC Systems in Environments Relevant to Advanced Gas Turbines for IGCC Systems

    Science.gov (United States)

    Bohna, Nathaniel Allan

    Plasma sprayed (PS) thermal barrier coatings (TBCs) are used to provide thermal insulation for the hottest components in gas turbines. Zirconia stabilized with 7wt% yttria (7YSZ) is the most common ceramic top coat used for turbine blades. The 7YSZ coating can be degraded by the buildup of fly-ash deposits which can arise from the fuel source (coal/biomass) used in the combustion process in gas turbines. Fly-ash from the integrated gasification combined cycle (IGCC) process can result from coal-based syngas and also from ambient air which passes through the system. TBCs are also exposed to harsh gas environments containing CO2, SO2, and steam. As presented in this thesis, degradation from the combined effects of fly-ash and harsh gas atmosphere can severely limit TBC lifetimes. It is well established that degradation at very high temperatures (≥1250°C) from deposits consisting of the oxides CaO-MgO-Al2O3-SiO 2 results from extensive liquid silicate infiltration into the porous top coat of the YSZ. This infiltration causes early failure resulting from chemical and/or mechanical damage to the ceramic layer. Damage resulting from liquid infiltration, however, is not typically considered at relatively lower temperatures around 1100°C because liquid silicates would not be expected to form from the oxides in the deposit. A key focus of this study is to assess the mode and extent of TBC degradation at 1100°C in cases when some amount of liquid forms owing to the presence of K2SO4 as a minor ash constituent. Two types of liquid infiltrations are observed depending on the principal oxide (i.e., CaO or SiO2) in the deposit. The degradation is primarily the result of mechanical damage, which results from infiltration caused by the interaction of liquid K2SO4 with either the CaO or SiO2. The TBCs used in this work are representative of commonly used coatings used in the hottest sections of land-based gas turbines. The specimens consist of 7YSZ top coats deposited on

  18. SUPPORT OF GULF OF MEXICO HYDRATE RESEARCH CONSORTIUM: ACTIVITIES TO SUPPORT ESTABLISHMENT OF A SEA FLOOR MONITORING STATION PROJECT

    Energy Technology Data Exchange (ETDEWEB)

    J. Robert Woolsey; Tom McGee; Carol Lutken; Elizabeth Stidham

    2006-06-01

    The Gulf of Mexico Hydrates Research Consortium (GOM-HRC) was established in 1999 to assemble leaders in gas hydrates research. The Consortium is administered by the Center for Marine Resources and Environmental Technology, CMRET, at the University of Mississippi. The primary objective of the group is to design and emplace a remote monitoring station or sea floor observatory (MS/SFO) on the sea floor in the northern Gulf of Mexico by the year 2007, in an area where gas hydrates are known to be present at, or just below, the sea floor. This mission, although unavoidably delayed by hurricanes and other disturbances, necessitates assembling a station that will monitor physical and chemical parameters of the marine environment, including sea water and sea-floor sediments, on a more-or-less continuous basis over an extended period of time. In 2005, biological monitoring, as a means of assessing environmental health was added to the mission of the MS/SFO. Establishment of the Consortium has succeeded in fulfilling the critical need to coordinate activities, avoid redundancies and communicate effectively among researchers in the arena of gas hydrates research. Complementary expertise, both scientific and technical, has been assembled to promote innovative research methods and construct necessary instrumentation. The observatory has now achieved a microbial dimension in addition to the geophysical and geochemical components it had already included. Initial components of the observatory, a probe that collects pore-fluid samples and another that records sea floor temperatures, were deployed in Mississippi Canyon 118 in May of 2005. Follow-up deployments, planned for fall 2005, had to be postponed due to the catastrophic effects of Hurricane Katrina (and later, Rita) on the Gulf Coast. Every effort was made to locate and retain the services of a suitable vessel and submersibles or Remotely Operated Vehicles (ROVs) following the storms and the loss of the contracted vessel

  19. USRCRN Station Information

    Data.gov (United States)

    National Oceanic and Atmospheric Administration, Department of Commerce — Documentation of United States Regional Climate Reference Network (USRCRN) installations in 2009. Installations documented are for USRCRN pilot project stations in...

  20. Questionnaire regarding the international Freiberg conference on IGCC and XtL technologies. Analysis of 75 questionnaires

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2005-07-01

    The Puertollano IGCC Plant, owned by ELCOGAS, uses a mixture (50/50% weight) of local coal with high content of ash (approximately 45%) and pet-coke to be fed into its pressurised entrained flow gasifier. Ash is removed from the bottom of the gasifier as vitrified slag although a fraction is converted into fly ash (2.5-3 t/h) and entrained by the syngas. In order to remove this fly ash, it is filtered in two candle filter vessels with more than 1,000 candles each, using nitrogen for on-line cleaning. The filtering system suffers some malfunctions resulting in blinding of the internal candle surface and increasing of the candle DP. The model of candle filter was changed and modifications were performed without the desired results. Therefore, the identification of suitable hot gas filtration technologies capable of overcoming current and future severe operational constraints experienced is of the utmost importance for IGCC units. In this sense, a pilot plant which allows the performance of alternative filtering elements tests, pulse cleaning strategies, on-line particulate monitoring and off-cleaning procedures has come into operation at the ESI-University of Seville facilities. The design has been conceived as a versatile pilot unit, in order to hold both bags and ceramic candles which are to be tested in a wide range of operating conditions. The pilot is processing air laden with real fly ash provided by ELCOGAS, and high pressure nitrogen for the cleaning operation. This paper describes the design and operation of the pilot as well as the testing plan currently being carried out. (orig.)

  1. Multi-fuel multi-product operation of IGCC power plants with carbon capture and storage (CCS)

    International Nuclear Information System (INIS)

    Cormos, Ana-Maria; Dinca, Cristian; Cormos, Calin-Cristian

    2015-01-01

    This paper investigates multi-fuel multi-product operation of IGCC plants with carbon capture and storage (CCS). The investigated plant designs co-process coal with different sorts of biomass (e.g. sawdust) and solid wastes, through gasification, leading to different decarbonised energy vectors (power, hydrogen, heat, substitute natural gas etc.) simultaneous with carbon capture. Co-gasification of coal with different renewable energy sources coupled with carbon capture will pave the way towards zero emissions power plants. The energy conversions investigated in the paper were simulated using commercial process flow modelling package (ChemCAD) in order to produce mass and energy balances necessary for the proposed evaluation. As illustrative cases, hydrogen and power co-generation and Fischer–Tropsch fuel synthesis (both with carbon capture), were presented. The case studies investigated in the paper produce a flexible ratio between power and hydrogen (in the range of 400–600 MW net electricity and 0–200 MW th hydrogen considering the lower heating value) with at least 90% carbon capture rate. Special emphasis were given to fuel selection criteria for optimisation of gasification performances (fuel blending), to the selection criteria for gasification reactor in a multi-fuel multi-product operation scenario, modelling and simulation of whole process, to thermal and power integration of processes, flexibility analysis of the energy conversion processes, in-depth techno-economic and environmental assessment etc. - Highlights: • Assessment of IGCC-based energy vectors poly-generation systems with CCS. • Optimisation of gasification performances and CO 2 emissions by fuel blending. • Multi-fuel multi-product operation of gasification plants

  2. The Ongoing Addition of Infrasound Sensors and the Flexette Wind-Noise Reducing System to Global Seismic Network Stations Operated by Project IDA

    Science.gov (United States)

    Ebeling, C. W.; Coon, C.

    2017-12-01

    Infrasound sensors are now being installed at Global Seismic Network (GSN) stations meeting certain infrastructure criteria. Manufactured by Hyperion Technology Group, Inc., these instruments (model IFS-3312) have a nominal sensitivity of 140 mV/Pa (at 1 Hz), a full-scale range of ±100 Pa, and a dynamic range of 120 dB. Low power consumption (750 mW at 12 VDC) and small size (153 mm x 178 mm) ease incorporation into the mix of existing GSN instrumentation. The accompanying flexible rosette ("Flexette") acoustic wind-noise reducing system, designed by Project IDA (International Deployment of Accelerometers-IDA), optimally includes 24 inlets, 4 secondary manifolds, and a single primary manifold. Each secondary manifold is connected to 6 inlets and to the primary manifold by 10-ft air hoses, thus eliminating stresses and the greater potential for leaks associated with the use of pipe. While the main design goal was to maximize the reduction of acoustic wind-noise over the widest range of wind speeds possible, consideration of additional criteria resulted in a Flexette base design easily tailored to meet individual station constraints and restrictions, made up of inexpensive (total cost Marshall Islands), in August 2017. During the next 6 months infrasound capability will be extended to IDA GSN stations BORG (Borganes, Iceland), EFI (Mount Kent, East Falkland Islands), and SACV (Santiago Island, Cape Verde).As with other data from GSN stations, real-time infrasound data are freely available from the Incorporated Research Institutions for Seismology-Data Management Center (IRIS-DMC).

  3. Massachusetts Institute of Technology School of Chemical Engineering Practice, Brookhaven station: Summary of projects, 1983-1986

    International Nuclear Information System (INIS)

    1987-11-01

    The MIT Graduate School of Chemical Engineering Practice stresses engineering problem solving. The Practice School program, as it is commonly called, develops in a unique and particularly effective way the student's ability to apply fundamentals to problems in the chemical industry and thus accelerates one's professional development. The themes of atomization, emthanol production and utilization, hydrogen production and compression, localized electrochemical corrosion and biochemical engineering reflect some of the major programs at the Laboratory. The titles of all the projects are listed in chronological order in the index at the end of this document. Brief summaries are presented for each project with related projects grouped together

  4. Support of Gulf of Mexico Hydrate Research Consortium: Activities to Support Establishment of a Sea Floor Monitoring Station Project

    Energy Technology Data Exchange (ETDEWEB)

    J. Robert Woolsey; Thomas M. McGee; Carol Blanton Lutken; Elizabeth Stidham

    2007-03-31

    The Gulf of Mexico Hydrates Research Consortium (GOM-HRC) was established in 1999 to assemble leaders in gas hydrates research. The Consortium is administered by the Center for Marine Resources and Environmental Technology, CMRET, at the University of Mississippi. The primary objective of the group is to design and emplace a remote monitoring station or sea floor observatory (MS/SFO) on the sea floor in the northern Gulf of Mexico by the year 2007, in an area where gas hydrates are known to be present at, or just below, the sea floor. This mission, although unavoidably delayed by hurricanes and other disturbances, necessitates assembling a station that will monitor physical and chemical parameters of the marine environment, including sea water and sea-floor sediments, on a more-or-less continuous basis over an extended period of time. In 2005, biological monitoring, as a means of assessing environmental health, was added to the mission of the MS/SFO. Establishment of the Consortium has succeeded in fulfilling the critical need to coordinate activities, avoid redundancies and communicate effectively among researchers in the arena of gas hydrates research. Complementary expertise, both scientific and technical, has been assembled to promote innovative research methods and construct necessary instrumentation. The observatory has now achieved a microbial dimension in addition to the geophysical, geological, and geochemical components it had already included. Initial components of the observatory, a probe that collects pore-fluid samples and another that records sea floor temperatures, were deployed in Mississippi Canyon 118 (MC118) in May of 2005. Follow-up deployments, planned for fall 2005, had to be postponed due to the catastrophic effects of Hurricane Katrina (and later, Rita) on the Gulf Coast. Station/observatory completion, anticipated for 2007, will likely be delayed by at least one year. These delays caused scheduling and deployments difficulties but many

  5. Support of Gulf of Mexico Hydrate Research Consortium: Activities to Support Establishment of a Sea Floor Monitoring Station Project

    Energy Technology Data Exchange (ETDEWEB)

    Carol Lutken

    2006-09-30

    The Gulf of Mexico Hydrates Research Consortium (GOM-HRC) was established in 1999 to assemble leaders in gas hydrates research. The Consortium is administered by the Center for Marine Resources and Environmental Technology, CMRET, at the University of Mississippi. The primary objective of the group is to design and emplace a remote monitoring station or sea floor observatory (MS/SFO) on the sea floor in the northern Gulf of Mexico by the year 2007, in an area where gas hydrates are known to be present at, or just below, the sea floor. This mission, although unavoidably delayed by hurricanes and other disturbances, necessitates assembling a station that will monitor physical and chemical parameters of the marine environment, including sea water and sea-floor sediments, on a more-or-less continuous basis over an extended period of time. In 2005, biological monitoring, as a means of assessing environmental health, was added to the mission of the MS/SFO. Establishment of the Consortium has succeeded in fulfilling the critical need to coordinate activities, avoid redundancies and communicate effectively among researchers in the arena of gas hydrates research. Complementary expertise, both scientific and technical, has been assembled to promote innovative research methods and construct necessary instrumentation. The observatory has now achieved a microbial dimension in addition to the geophysical, geological, and geochemical components it had already included. Initial components of the observatory, a probe that collects pore-fluid samples and another that records sea floor temperatures, were deployed in Mississippi Canyon 118 in May of 2005. Follow-up deployments, planned for fall 2005, had to be postponed due to the catastrophic effects of Hurricane Katrina (and later, Rita) on the Gulf Coast. Station/observatory completion, anticipated for 2007, will likely be delayed by at least one year. The CMRET has conducted several research cruises during this reporting period

  6. FutureGen Project Report

    Energy Technology Data Exchange (ETDEWEB)

    Cabe, Jim; Elliott, Mike

    2010-09-30

    This report summarizes the comprehensive siting, permitting, engineering, design, and costing activities completed by the FutureGen Industrial Alliance, the Department of Energy, and associated supporting subcontractors to develop a first of a kind near zero emissions integrated gasification combined cycle power plant and carbon capture and storage project (IGCC-CCS). With the goal to design, build, and reliably operate the first IGCC-CCS facility, FutureGen would have been the lowest emitting pulverized coal power plant in the world, while providing a timely and relevant basis for coal combustion power plants deploying carbon capture in the future. The content of this report summarizes key findings and results of applicable project evaluations; modeling, design, and engineering assessments; cost estimate reports; and schedule and risk mitigation from initiation of the FutureGen project through final flow sheet analyses including capital and operating reports completed under DOE award DE-FE0000587. This project report necessarily builds upon previously completed siting, design, and development work executed under DOE award DE-FC26- 06NT4207 which included the siting process; environmental permitting, compliance, and mitigation under the National Environmental Policy Act; and development of conceptual and design basis documentation for the FutureGen plant. For completeness, the report includes as attachments the siting and design basis documents, as well as the source documentation for the following: • Site evaluation and selection process and environmental characterization • Underground Injection Control (UIC) Permit Application including well design and subsurface modeling • FutureGen IGCC-CCS Design Basis Document • Process evaluations and technology selection via Illinois Clean Coal Review Board Technical Report • Process flow diagrams and heat/material balance for slurry-fed gasifier configuration • Process flow diagrams and heat/material balance

  7. The TACIS Nuclear Programme: Assistance in Upgrading Russian Nuclear Power Stations - An Overview of the Individual Projects in the Internet

    International Nuclear Information System (INIS)

    Bieth, Michel; Schoels, Hubert

    2006-01-01

    The European Union' TACIS1 programme has been established for the New Independent States (NIS), among them in the Russian Federation since 1991. One priority of TACIS funding is Nuclear Safety. The European Commission has made available a total of 944 Million Euros for nuclear safety programmes covering the period 1991-2003. The TACIS nuclear safety programme is devoted to the improvement of the safety of Soviet designed nuclear installations in providing technology and safety culture transfer. JRC is carrying out works in the following areas: On-Site Assistance for TACIS operating Nuclear Power Plants; Design Safety and Dissemination of TACIS results; Reactor Pressure Vessel Embrittlement for VVER; Regulatory Assistance; Industrial Waste Management; Nuclear Safeguards; All TACIS projects, dealing with these areas of activity are now available in so called Project Description Sheets (PDS) or Project Results Sheets (PRS) in the Internet for everybody. JRC has created in the Internet an easy to open and to browse database which contains the result of works in relation to the above mentioned nuclear activities. This presentation gives an on-line overview of the app. 430 projects which have been implemented so far since the outset of the TACIS Nuclear Programme in the Russian Federation, which is representative to the other CIS countries, benefiting from the TACIS. The presentation will mainly consist of an on-line-demonstration of the TACIS Nuclear WEB Page, created by JRC. (authors)

  8. SUPPORT OF GULF OF MEXICO HYDRATE RESEARCH CONSORTIUM: ACTIVITIES TO SUPPORT ESTABLISHMENT OF A SEA FLOOR MONITORING STATION PROJECT

    Energy Technology Data Exchange (ETDEWEB)

    Paul Higley; J. Robert Woolsey; Ralph Goodman; Vernon Asper; Boris Mizaikoff; Angela Davis

    2005-11-01

    A Consortium, designed to assemble leaders in gas hydrates research, has been established at the University of Mississippi's Center for Marine Resources and Environmental Technology, CMRET. The primary objective of the group is to design and emplace a remote monitoring station on the sea floor in the northern Gulf of Mexico by the year 2005, in an area where gas hydrates are known to be present at, or just below, the sea floor. This mission necessitates assembling a station that will monitor physical and chemical parameters of the sea water and sea floor sediments on a more-or-less continuous basis over an extended period of time. Development of the station allows for the possibility of expanding its capabilities to include biological monitoring, as a means of assessing environmental health. Establishment of the Consortium has succeeded in fulfilling the critical need to coordinate activities, avoid redundancies and communicate effectively among researchers in this relatively new research arena. Complementary expertise, both scientific and technical, has been assembled to promote innovative research methods and construct necessary instrumentation. Noteworthy achievements one year into the extended life of this cooperative agreement include: (1) Progress on the vertical line array (VLA) of sensors: (1a) Repair attempts of the VLA cable damaged in the October >1000m water depth deployment failed; a new design has been tested successfully. (1b) The acoustic modem damaged in the October deployment was repaired successfully. (1c) Additional acoustic modems with greater depth rating and the appropriate surface communications units have been purchased. (1d) The VLA computer system is being modified for real time communications to the surface vessel using radio telemetry and fiber optic cable. (1e) Positioning sensors--including compass and tilt sensors--were completed and tested. (1f) One of the VLAs has been redesigned to collect near sea floor geochemical data. (2

  9. Field pilot testing for chemical oxidation at the former Nitchequon meteorological station : decontamination project in isolated areas

    Energy Technology Data Exchange (ETDEWEB)

    Peisajovich, A. [Transport Canada, Montreal, PQ (Canada); Bergeron, E. [Golder Associates Ltd., Montreal, PQ (Canada); Barbeau, M. [Golder Associates Innovative Applications, Montreal, PQ (Canada); Lajoie, G. [Cree Regional Authority, Montreal, PQ (Canada)

    2006-07-01

    Field pilot testing for chemical oxidation at the former Nitchequon meteorological station was discussed. This presentation described the site location and provided an aerial view and cross section of the site. The historical background and condition of the site were then identified. Photographs and illustrations of the site and the source of the problem were provided. Photographs were also provided of the logistics, temporary camp, dismantling of tanks, equipment, pipeline dismantling, residues, methodology as well as a graphical representation of how to solve the problem. Other topics included technologies tested on site, full-scale remediation plans, remediation goals, step by step process, and costs distribution. Among the steps discussed was: vegetation removal; excavation of the first two feet of soil; transfer of contaminated soil on high-density polyethylene (HDPE) lining prior to treatment; cell construction; cell lining insulation; transfer of treated soil from the mixers to the curing cells; installation of HDPE top cover lining over the treated soil; and the addition of 12 inches of clean soil over the top cover lining. tabs., figs.

  10. The CELSS Antarctic Analog Project: An Advanced Life Support Testbed at the Amundsen-Scott South Pole Station, Antarctica

    Science.gov (United States)

    Straight, Christian L.; Bubenheim, David L.; Bates, Maynard E.; Flynn, Michael T.

    1994-01-01

    CELSS Antarctic Analog Project (CAAP) represents a logical solution to the multiple objectives of both the NASA and the National Science Foundation (NSF). CAAP will result in direct transfer of proven technologies and systems, proven under the most rigorous of conditions, to the NSF and to society at large. This project goes beyond, as it must, the generally accepted scope of CELSS and life support systems including the issues of power generation, human dynamics, community systems, and training. CAAP provides a vivid and starkly realistic testbed of Controlled Ecological Life Support System (CELSS) and life support systems and methods. CAAP will also be critical in the development and validation of performance parameters for future advanced life support systems.

  11. Study of the Cherokee Nuclear Station: projected impacts, monitoring plan, and mitigation options for Cherokee County, South Carolina

    International Nuclear Information System (INIS)

    Peelle, E.; Schweitzer, M.; Scharre, P.; Pressman, B.

    1979-07-01

    This report inventories Cherokee County's capabilities and CNS project characteristics, projects expected impacts from the interaction of the two defines four options for Cherokee County decision makers, and presents a range of possible mitigation and monitoring plans for dealing with the problems identified. The four options and general implementation guidelines for each are presented after reviewing pertinent features of other mitigation and monitoring plans. The four options include (1) no action, (2) preventing impacts by preventing growth, (3) selective growth in designated areas as services can be supplied, and (4) maximum growth designed to attract as many in-movers as possible through a major program of capital investiments in public and private services. With the exception of the no action option, all plans deal with impacts according to some strategy determined by how the County wishes to manage growth. Solutions for impact problems depend on which growth strategy is selected and what additional resources are secured during the impact period. A monitoring program deals with the problems of data and projections uncertainty, while direct action is proposed to deal with the institutional problems of delay of the needed access road, timeing and location problems from the tax base mismatch, and lack of local planning capability

  12. Study of the Cherokee Nuclear Station: projected impacts, monitoring plan, and mitigation options for Cherokee County, South Carolina

    Energy Technology Data Exchange (ETDEWEB)

    Peelle, E.; Schweitzer, M.; Scharre, P.; Pressman, B.

    1979-07-01

    This report inventories Cherokee County's capabilities and CNS project characteristics, projects expected impacts from the interaction of the two defines four options for Cherokee County decision makers, and presents a range of possible mitigation and monitoring plans for dealing with the problems identified. The four options and general implementation guidelines for each are presented after reviewing pertinent features of other mitigation and monitoring plans. The four options include (1) no action, (2) preventing impacts by preventing growth, (3) selective growth in designated areas as services can be supplied, and (4) maximum growth designed to attract as many in-movers as possible through a major program of capital investiments in public and private services. With the exception of the no action option, all plans deal with impacts according to some strategy determined by how the County wishes to manage growth. Solutions for impact problems depend on which growth strategy is selected and what additional resources are secured during the impact period. A monitoring program deals with the problems of data and projections uncertainty, while direct action is proposed to deal with the institutional problems of delay of the needed access road, timeing and location problems from the tax base mismatch, and lack of local planning capability.

  13. Solar electricity power station building. A preliminary project investigation for “PIRIN TEX LTD.” – Gotze Delchgev using

    International Nuclear Information System (INIS)

    Kolev, Boyko; Todorieva, Vanja

    2009-01-01

    The total solar energy absorbed by Earth's atmosphere, oceans and land masses is approximately 3,850,000 exa joules (EJ=1018 J) per year. In 2005, this was more energy in one hour than the world used in one year. Photosynthesis captures approximately 3,000 EJ per year in biomass. The amount of solar energy reaching the surface of the planet is so vast that in one year it is about twice as much as will ever be obtained from all of the Earth's non-renewable resources of coal, oil, natural gas, and mined uranium combined. Natural gas crisis such as this from January 2009 in Bulgaria turn into the best investments the development of technology for renewable energy sources using especially solar energy using for electricity production and water heating. The aims of this article are: To develop a preliminary project for solar electricity power station build-ing; To estimate the profits of solar energy used for electricity production and water heating. Keywords: renewable energy sources, solar energy accumulation, solar electricity power station, natural gas crisis

  14. The Current Status of the Space Station Biological Research Project: a Core Facility Enabling Multi-Generational Studies under Slectable Gravity Levels

    Science.gov (United States)

    Santos, O.

    2002-01-01

    The Space Station Biological Research Project (SSBRP) has developed a new plan which greatly reduces the development costs required to complete the facility. This new plan retains core capabilities while allowing for future growth. The most important piece of equipment required for quality biological research, the 2.5 meter diameter centrifuge capable of accommodating research specimen habitats at simulated gravity levels ranging from microgravity to 2.0 g, is being developed by NASDA, the Japanese space agency, for the SSBRP. This is scheduled for flight to the ISS in 2007. The project is also developing a multi-purpose incubator, an automated cell culture unit, and two microgravity habitat holding racks, currently scheduled for launch in 2005. In addition the Canadian Space Agency is developing for the project an insect habitat, which houses Drosophila melanogaster, and provides an internal centrifuge for 1 g controls. NASDA is also developing for the project a glovebox for the contained manipulation and analysis of biological specimens, scheduled for launch in 2006. This core facility will allow for experimentation on small plants (Arabidopsis species), nematode worms (C. elegans), fruit flies (Drosophila melanogaster), and a variety of microorganisms, bacteria, yeast, and mammalian cells. We propose a plan for early utilization which focuses on surveys of changes in gene expression and protein structure due to the space flight environment. In the future, the project is looking to continue development of a rodent habitat and a plant habitat that can be accommodated on the 2.5 meter centrifuge. By utilizing the early phases of the ISS to broadly answer what changes occur at the genetic and protein level of cells and organisms exposed to the ISS low earth orbit environment, we can generate interest for future experiments when the ISS capabilities allow for direct manipulation and intervention of experiments. The ISS continues to hold promise for high quality, long

  15. Fire Stations

    Data.gov (United States)

    Department of Homeland Security — Fire Stations in the United States Any location where fire fighters are stationed or based out of, or where equipment that such personnel use in carrying out their...

  16. Design and evaluation of an IGCC power plant using iron-based syngas chemical-looping (SCL) combustion

    International Nuclear Information System (INIS)

    Sorgenfrei, Max; Tsatsaronis, George

    2014-01-01

    Highlights: • A new concept for power generation including carbon capture was found. • The air reactor temperature significantly influences the net efficiency. • The use of a CO 2 turbine decreases the net efficiency. • Compared to a conventional IGCC with 90% CO 2 capture the net efficiency increases. - Abstract: Chemical-looping combustion (CLC) is a novel and promising combustion technology with inherent separation of the greenhouse gas CO 2 . This paper focuses on the design and thermodynamic evaluation of an integrated gasification combined-cycle (IGCC) process using syngas chemical looping (SCL) combustion for generating electricity. The syngas is provided by coal gasification; the gas from the gasifier is cleaned using high-temperature gas desulfurization (HGD). In this study, the oxygen carrier iron oxide (Fe 2 O 3 ) is selected to oxidize the syngas in a multistage moving-bed reactor. The resulting reduced iron particles then consist of FeO and Fe 3 O 4 . To create a closed-cycle operation, these particles are partially re-oxidized with steam in a fluidized-bed regenerator to pure Fe 3 O 4 and then fully re-oxidized in a fluidized-bed air combustor to Fe 2 O 3 . One advantage of this process is the co-production of hydrogen diluted with water vapor within the steam regenerator. Both the HGD and CLC systems are not under commercial operation so far. This mixture is fed to a gas turbine for the purpose of generating electricity. The gas turbine is expected to exhibit low NO x emissions due to the high ratio of water in the combustion chamber. Cooling the flue gas in the HRSG condenses the water vapor to yield high-purity CO 2 for subsequent compression and disposal. To evaluate the net efficiency, two conventional syngas gasifiers are considered, namely the BGL slagging gasifier and the Shell entrained-flow gasifier. The option of using a CO 2 turbine after the SCL-fuel reactor is also investigated. A sensitivity analysis is performed on the SCL

  17. The decision on the application to carry out a decommissioning project at Hinkley Point A Power Station under the Nuclear Reactors (Environmental Impact Assessment for Decommissioning) Regulations 1999

    International Nuclear Information System (INIS)

    2003-01-01

    European Council Directive 85/337/EEC, as amended by Council Directive 97/1 I/EC, sets out a framework on the assessment of the effects of certain public and private projects on the environment. The Directive is implemented in Great Britain for decommissioning nuclear reactor projects by the Nuclear Reactors (Environmental Impact Assessment for Decommissioning) Regulations 1999. The intention of the Directive and Regulations is to involve the public through consultation in considering the potential environmental impacts of a decommissioning project, and to make the decision-making process on granting consent open and transparent. The Regulations require the licensee to undertake an environmental impact assessment, prepare an environmental statement that summarises the environmental effects of the project, and apply to the Health and Safety Executive (HSE) for consent to carry out a decommissioning project. There is an optional stage where the licensee may request from HSE an opinion on what the environmental statement should contain (called a pre-application opinion). The licensee of Hinkley Point A Power Station, Magnox Electric pie, requested a pre-application opinion and provided information in a scoping report in December 2000. HSE undertook a public consultation on the scoping report and provided its pre- application opinion in April 2001. The licensee applied to HSE for consent to carry out a decommissioning project and provided an environmental statement in December 2001. Following a public consultation on the environmental statement, HSE requested further information that was subsequently provided by the licensee. A further public consultation was undertaken on the further information that ended in March 2003. All these public consultations involved around 60 organisations. HSE granted consent to carry out a decommissioning project at Hinkley Point A Power Station under the Regulations in July 2003, and attached conditions to the Consent. HSE took relevant

  18. [STEM on Station Education

    Science.gov (United States)

    Lundebjerg, Kristen

    2016-01-01

    The STEM on Station team is part of Education which is part of the External Relations organization (ERO). ERO has traditional goals based around BHAG (Big Hairy Audacious Goal). The BHAG model is simplified to a saying: Everything we do stimulates actions by others to advance human space exploration. The STEM on Station education initiate is a project focused on bringing off the earth research and learning into classrooms. Educational resources such as lesson plans, activities to connect with the space station and STEM related contests are available and hosted by the STEM on Station team along with their partners such as Texas Instruments. These educational activities engage teachers and students in the current happenings aboard the international space station, inspiring the next generation of space explorers.

  19. Heat Integration of the Water-Gas Shift Reaction System for Carbon Sequestration Ready IGCC Process with Chemical Looping

    Energy Technology Data Exchange (ETDEWEB)

    Juan M. Salazara; Stephen E. Zitney; Urmila M. Diwekara

    2010-01-01

    Integrated gasification combined cycle (IGCC) technology has been considered as an important alternative for efficient power systems that can reduce fuel consumption and CO2 emissions. One of the technological schemes combines water-gas shift reaction and chemical-looping combustion as post gasification techniques in order to produce sequestration-ready CO2 and potentially reduce the size of the gas turbine. However, these schemes have not been energetically integrated and process synthesis techniques can be applied to obtain an optimal flowsheet. This work studies the heat exchange network synthesis (HENS) for the water-gas shift reaction train employing a set of alternative designs provided by Aspen energy analyzer (AEA) and combined in a process superstructure that was simulated in Aspen Plus (AP). This approach allows a rigorous evaluation of the alternative designs and their combinations avoiding all the AEA simplifications (linearized models of heat exchangers). A CAPE-OPEN compliant capability which makes use of a MINLP algorithm for sequential modular simulators was employed to obtain a heat exchange network that provided a cost of energy that was 27% lower than the base case. Highly influential parameters for the pos gasification technologies (i.e. CO/steam ratio, gasifier temperature and pressure) were calculated to obtain the minimum cost of energy while chemical looping parameters (oxidation and reduction temperature) were ensured to be satisfied.

  20. Using renewables and the co-production of hydrogen and electricity from CCS-equipped IGCC facilities, as a stepping stone towards the early development of a hydrogen economy

    International Nuclear Information System (INIS)

    Haeseldonckx, Dries; D'haeseleer, William

    2010-01-01

    In this paper, specific cases for the interaction between the future electricity-generation mix and a newly-developing hydrogen-production infrastructure is modelled with the model E-simulate. Namely, flexible integrated-gasification combined-cycle units (IGCC) are capable of producing both electricity and hydrogen in different ratios. When these units are part of the electricity-generation mix and when they are not operating at full load, they could be used to produce a certain amount of hydrogen, avoiding the costly installation of new IGCC units for hydrogen production. The same goes for the massive introduction of renewable energies (especially wind), possibly generating excess electricity from time to time, which could then perhaps be used to produce hydrogen electrolytically. However, although contra-intuitive, the interaction between both 'systems' turns out to be almost negligible. Firstly, it is shown that it is more beneficial to use IGCC facilities to produce hydrogen with, rather than (excess) wind-generated electricity due to the necessary electrolyser investment costs. But even flexible IGCC facilities do not seem to contribute substantially to the early development of a hydrogen economy. Namely, in most scenarios - which are combinations of a wide range of fuel prices and carbon taxes - one primary-energy carrier (natural gas or coal) seems to be dominant, pushing the other, and the corresponding technologies such as reformers or IGCCs, out of the market. (author)

  1. Amtrak Stations

    Data.gov (United States)

    Department of Homeland Security — Updated database of the Federal Railroad Administration's (FRA) Amtrak Station database. This database is a geographic data set containing Amtrak intercity railroad...

  2. High temperature gasification and gas cleaning – phase II of the HotVegas project

    OpenAIRE

    Meysel, P.; Halama, S.; Botteghi, F.; Steibel, M.; Nakonz, M.; Rück, R.; Kurowski, P.; Buttler, A.; Spliethoff, H.

    2016-01-01

    The primary objective of the research project HotVeGas is to lay the necessary foundations for the long-term development of future, highly efficient high-temperature gasification processes. This includes integrated hot gas cleaning and optional CO2 capture and storage for next generation IGCC power plants and processes for the development of synthetic fuels. The joint research project is funded by the German Federal Ministry of Economics and Technology and five industry partners. It is coordi...

  3. WVU Hydrogen Fuel Dispensing Station

    Energy Technology Data Exchange (ETDEWEB)

    Davis, William [West Virginia University Research Corporation, Morgantown, WV (United States)

    2015-09-01

    The scope of this project was changed during the course of the project. Phase I of the project was to construct a site similar to the site at Central West Virginia Regional Airport in Charleston, WV to show that duplication of the site was a feasible method of conducting hydrogen stations. Phase II of the project was necessitated due to a lack of funding that was planned for the development of the station in Morgantown. The US Department of Energy determined that the station in Charleston would be dismantled and moved to Morgantown and reassembled at the Morgantown site. This necessitated storage of the components of the station for almost a year at the NAFTC Headquarters which caused a number of issues with the equipment that will be discussed in later portions of this report. This report will consist of PHASE I and PHASE II with discussions on each of the tasks scheduled for each phase of the project.

  4. Point Lepreau generating station

    International Nuclear Information System (INIS)

    Ganong, G.H.D.; Strang, A.E.; Gunter, G.E.; Thompson, T.S.

    Point Lepreau-1 reactor is a 600 MWe generating station expected to be in service by October 1979. New Brunswick is suffering a 'catch up' phenomenon in load growth and needs to decrease dependence on foreign oil. The site is on salt water and extensive study has gone into corrosion control. Project management, financing and scheduling have unique aspects. (E.C.B.)

  5. Mojave Base Station Implementation

    Science.gov (United States)

    Koscielski, C. G.

    1984-01-01

    A 12.2 meter diameter X-Y mount antenna was reconditioned for use by the crustal dynamic project as a fixed base station. System capabilities and characteristics and key performance parameters for subsystems are presented. The implementation is completed.

  6. CO2 capture from IGCC gas streams using the AC-ABC process

    Energy Technology Data Exchange (ETDEWEB)

    Nagar, Anoop [SRI International, Menlo Park, CA (United States); McLaughlin, Elisabeth [SRI International, Menlo Park, CA (United States); Hornbostel, Marc [SRI International, Menlo Park, CA (United States); Krishnan, Gopala [SRI International, Menlo Park, CA (United States); Jayaweera, Indira [SRI International, Menlo Park, CA (United States)

    2017-02-16

    The objective of this project was to develop a novel, low-cost CO2 capture process from pre-combustion gas streams. The bench-scale work was conducted at the SRI International. A 0.15-MWe integrated pilot plant was constructed and operated for over 700 hours at the National Carbon Capture Center, Wilsonville, AL. The AC-ABC (ammonium carbonate-ammonium bicarbonate) process for capture of CO2 and H2S from the pre-combustion gas stream offers many advantages over Selexol-based technology. The process relies on the simple chemistry of the NH3-CO2-H2O-H2S system and on the ability of the aqueous ammoniated solution to absorb CO2 at near ambient temperatures and to release it as a high-purity, high-pressure gas at a moderately elevated regeneration temperature. It is estimated the increase in cost of electricity (COE) with the AC-ABC process will be ~ 30%, and the cost of CO2 captured is projected to be less than $27/metric ton of CO2 while meeting 90% CO2 capture goal. The Bechtel Pressure Swing Claus (BPSC) is a complementary technology offered by Bechtel Hydrocarbon Technology Solutions, Inc. BPSC is a high-pressure, sub-dew-point Claus process that allows for nearly complete removal of H2S from a gas stream. It operates at gasifier pressures and moderate temperatures and does not affect CO2 content. When coupled with AC-ABC, the combined technologies allow a nearly pure CO2 stream to be captured at high pressure, something which Selexol and other solvent-based technologies cannot achieve.

  7. Merchant funding for power stations

    International Nuclear Information System (INIS)

    Johnston, B.; Bartlam, M.

    1997-01-01

    The next frontier for project finance is merchant generation: the financing of IPPs without long-term offtake contracts. Banks are just beginning to finance merchant generation power stations. One of the first was Destec's Indian Queens project in Cornwall, UK. Bruce Johnston and Martin Bartlam of Wilde Sapte discuss the project. (UK)

  8. The Princess Elisabeth Station

    Science.gov (United States)

    Berte, Johan

    2012-01-01

    Aware of the increasing impact of human activities on the Earth system, Belgian Science Policy Office (Belspo) launched in 1997 a research programme in support of a sustainable development policy. This umbrella programme included the Belgian Scientific Programme on Antarctic Research. The International Polar Foundation, an organization led by the civil engineer and explorer Alain Hubert, was commissioned by the Belgian Federal government in 2004 to design, construct and operate a new Belgian Antarctic Research Station as an element under this umbrella programme. The station was to be designed as a central location for investigating the characteristic sequence of Antarctic geographical regions (polynia, coast, ice shelf, ice sheet, marginal mountain area and dry valleys, inland plateau) within a radius of 200 kilometers (approx.124 miles) of a selected site. The station was also to be designed as "state of the art" with respect to sustainable development, energy consumption, and waste disposal, with a minimum lifetime of 25 years. The goal of the project was to build a station and enable science. So first we needed some basic requirements, which I have listed here; plus we had to finance the station ourselves. Our most important requirement was that we decided to make it a zero emissions station. This was both a philosophical choice as we thought it more consistent with Antarctic Treaty obligations and it was also a logistical advantage. If you are using renewable energy sources, you do not have to bring in all the fuel.

  9. Aerodynamics and Heat Transfer Studies of Parameters Specific to the IGCC-Requirements: Endwall Contouring, Leading Edge and Blade Tip Ejection under Rotating Turbine Conditions

    Energy Technology Data Exchange (ETDEWEB)

    Schobeiri, Meinhard; Han, Je-Chin

    2014-09-30

    This report deals with the specific aerodynamics and heat transfer problematic inherent to high pressure (HP) turbine sections of IGCC-gas turbines. Issues of primary relevance to a turbine stage operating in an IGCC-environment are: (1) decreasing the strength of the secondary flow vortices at the hub and tip regions to reduce (a), the secondary flow losses and (b), the potential for end wall deposition, erosion and corrosion due to secondary flow driven migration of gas flow particles to the hub and tip regions, (2) providing a robust film cooling technology at the hub and that sustains high cooling effectiveness less sensitive to deposition, (3) investigating the impact of blade tip geometry on film cooling effectiveness. The document includes numerical and experimental investigations of above issues. The experimental investigations were performed in the three-stage multi-purpose turbine research facility at the Turbomachinery Performance and Flow Research Laboratory (TPFL), Texas A&M University. For the numerical investigations a commercial Navier-Stokes solver was utilized.

  10. Evaluation of NVE's snow station network; Subreport in R et D project 302H15 Good snow data; Evaluering av NVE sitt snoestasjonsnettverk

    Energy Technology Data Exchange (ETDEWEB)

    Ree, Bjoerg Lirhus; Landroe, Hilde; Trondsen, Elise; Moeen, Knut M.

    2011-03-15

    NVE has measured snow water equivalent of snow pillow in forty years. Our snow station network has risen since 1997 from 6 to 25 stations. It was therefore absolutely necessary to do a review and quality assurance of NVE's snow data. This report discusses the snow data measured continuously - snow water equivalent and snow depth. Each station and the parameters it measures are described and evaluated. It is concluded in relation to whether stations should be continued or not. Stations technical solutions are well described, both of NVE's standard stations and the two test stations, Filefjell and Svarttjoernbekken. It has been o importance to bring out what problems the instruments have or may have and provide suggestions for solutions to them. Problems related to measure the water equivalent under Norwegian conditions, with the challenges and winter rain and re-freezing provides, is also reviewed. Alternatives to water equivalent measurements with a snow pillow, which is the traditional way in this country, are presented. Some of the alternative methods NVE tests out, for the others only description and our opinion is given. (Author)

  11. Coproduction of transportation fuels in advanced IGCCs via coal and biomass mixtures

    International Nuclear Information System (INIS)

    Chen, Qin; Rao, Ashok; Samuelsen, Scott

    2015-01-01

    Highlights: • Coproduction of electricity and transportation fuels with carbon capture. • Switchgrass biomass is cofed with bituminous coal or lignite. • Cost of Fischer–Tropsch liquids is comparable to longer term price projections of crude oil. • Ethanol costs more than gasoline but greenhouse gas emissions will be lower. • Cost of hydrogen is lower than the DoE announced goal of $3/kg. - Abstract: Converting abundant fossil resources of coal to alternative transportation fuels is a promising option for countries heavily dependent on petroleum imports if plants are equipped with carbon capture for sequestration and cofed with biomass (30% by weight of the total feed on a dry basis), an essentially carbon neutral fuel, without penalizing the process economics excessively. A potential exists to improve both thermal efficiency and economics of such plants by taking advantage of the synergies of coproducing electricity using advanced technologies under development. Three types of transportation fuels are considered. Fischer–Tropsch (F–T) liquids consisting predominantly of waxes could be processed in existing refineries while displacing petroleum and the refined products introduced into the market place at the present time or in the near term without requiring changes to the existing infrastructure. Ethanol could potentially serve in the not so distant future (or phased in by blending with conventional liquid fuels). Hydrogen which could play a dominant role in the more distant future being especially suitable to the fuel cell hybrid vehicle (FCHV). Two types of coal along with biomass cofeed are evaluated; bituminous coal at $42.0/dry tonne, lignite at $12.0/dry tonne, and switchgrass at $99.0/dry tonne. The calculated cost for F–T liquids ranged from $77.8/bbl to $86.6/bbl (or $0.0177 to 0.0197/MJ LHV) depending on the feedstock, which is comparable to the projected longer term market price of crude oil at ∼$80/bbl when supply and demand reach a

  12. Station Capacity

    DEFF Research Database (Denmark)

    Landex, Alex

    2011-01-01

    the probability of conflicts and the minimum headway times into account. The last method analyzes how optimal platform tracks are used by examining the arrival and departure pattern of the trains. The developed methods can either be used separately to analyze specific characteristics of the capacity of a station......Stations are often limiting the capacity of railway networks. This is due to extra need of tracks when trains stand still, trains turning around, and conflicting train routes. Although stations are often the capacity bottlenecks, most capacity analysis methods focus on open line capacity. Therefore...... for platform tracks and the probability that arriving trains will not get a platform track immediately at arrival. The third method is a scalable method that analyzes the conflicts in the switch zone(s). In its simplest stage, the method just analyzes the track layout while the more advanced stages also take...

  13. Application for the Tape Station

    CERN Document Server

    Solero, A

    2003-01-01

    The Tape Station is used as an Isolde facility to observe the variations of intensity and the lifespan of certain isotopes. A Siemens Simatic FM-352-5 module controls the Tape Station in a PLC system then a DSC controls the PLC, which will be controlled the Tape station program. During the Isolde consolidation project, the Tape Station has been rebuilt, and the control system has been fully integrated in the PS control. Finally, a new application has been written in JAVA Development kit 1.4 and the PS Java environment. The main purpose of this note is to explain how to use this program.

  14. Hydrogen Filling Station

    Energy Technology Data Exchange (ETDEWEB)

    Boehm, Robert F; Sabacky, Bruce; Anderson II, Everett B; Haberman, David; Al-Hassin, Mowafak; He, Xiaoming; Morriseau, Brian

    2010-02-24

    Hydrogen is an environmentally attractive transportation fuel that has the potential to displace fossil fuels. The Freedom CAR and Freedom FUEL initiatives emphasize the importance of hydrogen as a future transportation fuel. Presently, Las Vegas has one hydrogen fueling station powered by natural gas. However, the use of traditional sources of energy to produce hydrogen does not maximize the benefit. The hydrogen fueling station developed under this grant used electrolysis units and solar energy to produce hydrogen fuel. Water and electricity are furnished to the unit and the output is hydrogen and oxygen. Three vehicles were converted to utilize the hydrogen produced at the station. The vehicles were all equipped with different types of technologies. The vehicles were used in the day-to-day operation of the Las Vegas Valley Water District and monitoring was performed on efficiency, reliability and maintenance requirements. The research and demonstration utilized for the reconfiguration of these vehicles could lead to new technologies in vehicle development that could make hydrogen-fueled vehicles more cost effective, economical, efficient and more widely used. In order to advance the development of a hydrogen future in Southern Nevada, project partners recognized a need to bring various entities involved in hydrogen development and deployment together as a means of sharing knowledge and eliminating duplication of efforts. A road-mapping session was held in Las Vegas in June 2006. The Nevada State Energy Office, representatives from DOE, DOE contractors and LANL, NETL, NREL were present. Leadership from the National hydrogen Association Board of Directors also attended. As a result of this session, a roadmap for hydrogen development was created. This roadmap has the ability to become a tool for use by other road-mapping efforts in the hydrogen community. It could also become a standard template for other states or even countries to approach planning for a hydrogen

  15. International Space Station exhibit

    Science.gov (United States)

    2000-01-01

    The International Space Station (ISS) exhibit in StenniSphere at John C. Stennis Space Center in Hancock County, Miss., gives visitors an up-close look at the largest international peacetime project in history. Step inside a module of the ISS and glimpse how astronauts will live and work in space. Currently, 16 countries contribute resources and hardware to the ISS. When complete, the orbiting research facility will be larger than a football field.

  16. Power stations

    International Nuclear Information System (INIS)

    Cawte, H.; Philpott, E.F.

    1980-01-01

    The object is to provide a method of operating a dual purpose power station so that the steam supply system is operated at a high load factor. The available steam not required for electricity generation is used to provide process heat and the new feature is that the process plant capacity is determined to make the most economic use of the steam supply system, and not to match the passout capacity of the turbine of the turbogenerator. The product of the process plant should, therefore, be capable of being stored. A dual-purpose power station with a nuclear-powered steam source, turbogenerating means connected to the steam source and steam-powered process plant susceptible to wide variation in its rate of operation is described. (U.K.)

  17. UMTS Network Stations

    Science.gov (United States)

    Hernandez, C.

    2010-09-01

    The weakness of small island electrical grids implies a handicap for the electrical generation with renewable energy sources. With the intention of maximizing the installation of photovoltaic generators in the Canary Islands, arises the need to develop a solar forecasting system that allows knowing in advance the amount of PV generated electricity that will be going into the grid, from the installed PV power plants installed in the island. The forecasting tools need to get feedback from real weather data in "real time" from remote weather stations. Nevertheless, the transference of this data to the calculation computer servers is very complicated with the old point to point telecommunication systems that, neither allow the transfer of data from several remote weather stations simultaneously nor high frequency of sampling of weather parameters due to slowness of the connection. This one project has developed a telecommunications infrastructure that allows sensorizadas remote stations, to send data of its sensors, once every minute and simultaneously, to the calculation server running the solar forecasting numerical models. For it, the Canary Islands Institute of Technology has added a sophisticated communications network to its 30 weather stations measuring irradiation at strategic sites, areas with high penetration of photovoltaic generation or that have potential to host in the future photovoltaic power plants connected to the grid. In each one of the stations, irradiance and temperature measurement instruments have been installed, over inclined silicon cell, global radiation on horizontal surface and room temperature. Mobile telephone devices have been installed and programmed in each one of the weather stations, which allow the transfer of their data taking advantage of the UMTS service offered by the local telephone operator. Every minute the computer server running the numerical weather forecasting models receives data inputs from 120 instruments distributed

  18. Green power production by co-gasification of biomass in coal-fired oxygen-blown entrained-flow based IGCC processes

    Energy Technology Data Exchange (ETDEWEB)

    Van Ree, R; Korbee, R; De Smidt, R P; Jansen, D [ECN Fuels Conversion and Environment, Petten (Netherlands); Baumann, H R; Ullrich, N [Krupp Uhde, Dortmund (Germany); Haupt, G; Zimmerman, [Siemens, Erlangen (Germany)

    1998-11-01

    The use of coal for large scale power production meets a growing environmental concern. In spite of the fact that clean coal conversion technologies integrated with high-efficiency power production facilities, such as IGCC, are developed, the aim for sustainable development strives for a power production system based on renewable energy sources. One of the most promising renewable energy sources that can be used in the Netherlands is biomass, i.e. organic waste materials and/or energy crops. To accelerate the introduction of this material, in a technical and economically acceptable way, co-gasification with fossil fuels, in particular coal, in large scale IGCC processes is considered. In this paper the technical feasibility, economic profitability, and environmental acceptability of co-gasification of biomass in coal-fired oxygen-blown entrained-flow based IGM is discussed. Both a base-case coal-fired oxygen-blown entrained-flow based IGCC process - showing strong resemblance to the Puertollano IGCC plant in Spain - and three co-gasification concepts, viz.: (1) a concept with separate dry coal and biomass feeding systems, (2) a concept with a combined dry coal/biomass-derived pyrolysis char feeding system, and (3) a concept with parallel biomass pre-treatment/gasification and combined fuel gas clean-up/power production, were defined for further consideration. The base-case system and the co-gasification concepts as well are modelled in the flowsheet simulation package ASPEN{sup +}. Steady-state integral system calculations resulted in an overall net electrical plant efficiency for the base-case system of 50. 1 %LHV (48.3 %HHV). Replacing about 10 % of the total thermal plant input (coal) by biomass (willow) resulted in a decrease of the overall net electrical plant efficiency of 1.4 to 2.1 %-points LHV, avoided specific CO2 emissions of 40-49 g/kWh{sub e}, and total avoided CO2 emissions of about 129 to 159 kt/a, all depending on the co-gasification concept

  19. Projectables

    DEFF Research Database (Denmark)

    Rasmussen, Troels A.; Merritt, Timothy R.

    2017-01-01

    CNC cutting machines have become essential tools for designers and architects enabling rapid prototyping, model-building and production of high quality components. Designers often cut from new materials, discarding the irregularly shaped remains. We introduce ProjecTables, a visual augmented...... reality system for interactive packing of model parts onto sheet materials. ProjecTables enables designers to (re)use scrap materials for CNC cutting that would have been previously thrown away, at the same time supporting aesthetic choices related to wood grain, avoiding surface blemishes, and other...... relevant material properties. We conducted evaluations of ProjecTables with design students from Aarhus School of Architecture, demonstrating that participants could quickly and easily place and orient model parts reducing material waste. Contextual interviews and ideation sessions led to a deeper...

  20. Advances in power station construction

    International Nuclear Information System (INIS)

    Anon.

    1986-01-01

    This book is about power stations - specifically about the construction of modern power stations by the Central Electricity Generating Board in England and Wales over the past decade. It describes the work of the CEGB's Generation Development and Construction Division, perhaps better known throughout the world as simply 'Barnwood' where it has its Headquarters in Gloucester, UK. Barnwood was formed in the early 1970s to concentrate the CEGB's then dispersed engineering construction resources to cope with the smaller number but greatly increased size and complexity of modern power station projects. Perhaps uniquely over the ten years since its formation Barnwood has managed the construction of all types of station; coal-fired, oil-fired, nuclear, pumped storage and hydro. This book tells the story of these various projects and gives detailed descriptions of the respective stations. However, it is not intended as a comprehensive description of power station technology. Rather it is intended to convey the scale of such projects and the many decisions and compromises which have to be made in the course of managing their construction

  1. Hydrogen Station Cost Estimates: Comparing Hydrogen Station Cost Calculator Results with other Recent Estimates

    Energy Technology Data Exchange (ETDEWEB)

    Melaina, M. [National Renewable Energy Lab. (NREL), Golden, CO (United States); Penev, M. [National Renewable Energy Lab. (NREL), Golden, CO (United States)

    2013-09-01

    This report compares hydrogen station cost estimates conveyed by expert stakeholders through the Hydrogen Station Cost Calculation (HSCC) to a select number of other cost estimates. These other cost estimates include projections based upon cost models and costs associated with recently funded stations.

  2. The ESA SMOS Validation Rehearsal Campaign at the Valencia Anchor Station Area in the Framework of the SMOS Cal/Val AO Project no. 3252

    Science.gov (United States)

    Lopez-Baeza, E.

    2009-04-01

    Since 2001, the Valencia Anchor Station is currently being prepared for the validation of SMOS land products. The site has recently been selected by the Mission as a core validation site, mainly due to the reasonable homogeneous characteristics of the area which make it appropriate to undertake the validation of SMOS Level 2 land products during the Mission Commissioning Phase, before attempting more complex areas. Close to SMOS launch, ESA defined and designed the SMOS Validation Rehearsal Campaign Plan with the purpose of repeating the Commissioning Phase execution with all centers, all tools, all participants, all structures, all data available, assuming that all tools and structures are ready and trying to produce as close as possible the post-launch conditions. The aim was to test the readiness, the ensemble coordination and the speed of operations to be able to avoid as far as possible any unexpected deficiencies of the plan and procedure during the real Commissioning Phase campaigns. For the rehearsal activity which successfully took place in April 2008, a control area of 10 x 10 km2 was chosen at the Valencia Anchor Station study area where a network of ground soil moisture measuring stations is being set up based on the definition of homogeneous physio-hydrological units, attending to climatic, soil type, lithology, geology, elevation, slope and vegetation cover conditions. These stations are linked via a wireless communication system to a master post accessible via internet. Complementary to the ground measurements, flight operations were performed over the control area using the Helsinki University of Technology TKK Short Skyvan research aircraft. The payload for the campaign consisted of the following instruments: (i) L-band radiometer EMIRAD (Technical University of Denmark, TUD), (ii) HUT-2D L-band imaging interferometric radiometer (TKK), (iii) PARIS GPS reflectrometry system (Institute for Space Studies of Catalonia, IEEC), (iv) IR sensor (Finnish

  3. Quality assurance grading criteria for plant systems and components: Results from a pilot plant project at Grand Gulf Nuclear Station. Final report

    International Nuclear Information System (INIS)

    Parkinson, W.J.

    1995-12-01

    As part of the original design of a nuclear power plant, the NSSS vendor, architect/engineer and utility identified structures, systems and components (SSCs) as safety related and assigned them to a Q-list. A Q-list is usually very large, e.g. 75,000 components, which creates large ongoing annual operating costs for the utility. Operating experience and the greater knowledge of plant systems safety accumulated during the past 20 years have suggested that many components are not truly important to safety and do not warrant the Q-classification and the associated costs. The completion of Probabilistic Safety Analyses (PSAs) for many nuclear power plants has contributed to this greater knowledge. This report describes a practical application of PSA technology to modify the existing QA program at the Grand Gulf Nuclear Station. Section 1 introduces the term, QA Safety Significant (QASS), and relates it to the existing term, ''safety related''. Section 2 describes six deterministic criteria as a basis for classifying systems as QASS or non-QASS. An expert panel reviewed 421 systems at Grand Gulf Nuclear Station and identified 42 of them as QASS. All components in non-QASS systems are classified as non-QASS. For QASS systems, Section 3 describes five deterministic criteria for classifying components as QASS or non-QASS. By using these two sets of criteria, the expert panel found that the number of components requiring full QA compliance could be reduced by 24%. These results are summarized in Section 4

  4. Report of fiscal 1999 basic survey for promoting joint implementation, etc. Combined cycle power generation project for Surgut No.1 power station in the Russian Federation

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2000-03-01

    This paper explains fiscal 1999 survey on a combined cycle power generation project for Surgut power plant in the Russian Federation for the purpose of making the project tied to the COP3 joint implementation. This power plant consists of 16 units with the total capacity of 3,300 MW. This project is to replace the existing superannuated No.1 through No.6 units with a new high-efficiency gas combined cycle power plant. The project plant is planned to comprise of three units, having the capacity of 417 MW, each consisting of one gas turbine and one steam turbine. The average generation efficiency will be improved tremendously from the present 37.2% to 55.2%. The initial investment will be 615 million in US dollars (at 109.2 yen/dollar). Energy saving will be 634,800 toe/year, with cost to effect 9,452 toe-y/million yen. Greenhouse effect gas reduction will be 1,509,000 t-CO2/year, with cost to effect 22.5 t-CO2-y/million yen. The investment recovery period is estimated to be 24 years. The Russian side strongly wishes to be granted a finance on a favorable terms and conditions to realize this project. It is possible that the Russian government requests Japan for grant of the Yen credit. Accordingly, an early start is necessary in order to deal with such request. (NEDO)

  5. Fiscal 1998 research report. Feasibility study on the CO{sub 2} reduction project by residue power generation at the oil refinery in China; 1998 nendo chosa hokokusho. Chugoku no seiyusho ni okeru zansa hatsuden ni yoru CO{sub 2} sakugen project ni kansuru F/S chosa

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1999-03-01

    As a part of the basic research on joint project promotion, this feasibility study supposed introduction of IGCC (integrated gasification combined cycle) to Nanjing oil refinery of Jinling Petrochemical Corp. (JPC) in China, estimated the CO{sub 2} emission reduction effect by in-refinery efficient power generation using petroleum coke residue as fuel, and assessed the feasibility of the project together with a cost benefit. The feasibility study result showed the effectiveness of IGCC introduction to the oil refinery for reducing CO{sub 2} emissions, occupying the interest of JPC. However, Nanjing oil refinery already making a decision to adopt another system (BTG) answered that early adoption of this project is difficult. The feasibility study result also showed that efficient operation of IGCC is difficult because of lower generation efficiency of petroleum coke residue, and achievement of the supposed CO{sub 2} emission reduction effect and profitability is difficult. The project based on this feasibility study result is probably difficult to be realized. (NEDO)

  6. Severe accident analysis of a steam generator tube rupture accident using MAAP-CANDU to support level 2 PSA for the Point Lepreau Generating Station Refurbishment Project

    Energy Technology Data Exchange (ETDEWEB)

    Petoukhov, S.M.; Brown, M.J. [Canadian Nuclear Laboratories, Chalk River, ON (Canada)

    2015-07-01

    A Level 2 Probabilistic Safety Assessment was performed for the Point Lepreau Generating Station. The MAAP-CANDU code was used to simulate the progression of postulated severe core damage accidents and fission product releases. This paper discusses the results for the reference case of the Steam Generator Tube Rupture initiating event. The reference case, dictated by the Level 2 Probabilistic Safety Assessment, was extreme and assumed most safety-related plant systems were not available: all steam generator feedwater; the emergency water supply; the moderator, shield and shutdown cooling systems; and all stages of emergency core cooling. The reference case also did not credit any post Fukushima lessons or any emergency mitigating equipment. The reference simulation predicted severe core damage beginning at 3.7 h, containment failure at 6.4 h, moderator boil off by 8.2 h, and calandria vessel failure at 42 h. A total release of 5.3% of the initial inventory of radioactive isotopes of Cs, Rb and I was predicted by the end of the simulation (139 h). Almost all noble gas fission products were released to the environment, primarily after the containment failure. No hydrogen/carbon monoxide burning was predicted. (author)

  7. Research and Activities of OECD/NEA Benchmark Study of the Accident at the Fukushima Daiichi Nuclear Power Station (BSAF) Project

    Energy Technology Data Exchange (ETDEWEB)

    Kim, Sung Il; Ha, Kwang Soon; Song, JinHo [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2016-10-15

    The severe accident codes were used to analysis the Fukushima Daiichi accident and give valuable information. In addition, the insufficient part of the code could be revised by comparing the calculation result with the measured data. In this circumstance, working plans have been set up to conduct a Benchmark Study of the Accident progression for the Fukushima Daiichi nuclear power plant(BSAF) units 1-3 with the members of the OECD/NEA. The BSAF project was launched in November 2012 with the fifteen organizations of eight countries (France, Germany, Korea, Russia, Spain, Switzerland, the United States, and Japan). The objectives of the project are: - to analyze the Fukushima accident progression. - to raise the understanding of severe accident(SA) phenomena. - to contribute the improvement of methods and models of SA code. - to contribute the status of debris distribution to a future debris removal plan. BSAF phase 2 also has been implemented from April, 2015 and it will be continued to March, 2018. It is more focused on the fission product behavior and source term estimation in phase 2. The phase 2 project implementation period is 3 years from April 2015 to March 2018. The main topic of the BSAF 2 is the fission product behavior in the Fukushima nuclear power plant. In the process of calculation, it is important to know the insufficient models in the code. Furthermore, the model would be applied to the KAERI's severe accident code after making up for the insufficient part.

  8. The Sewer Research Station in Frejlev

    DEFF Research Database (Denmark)

    Schaarup-Jensen, Kjeld; Hvitved-Jacobsen, T.

    This report for the 2000 activities at the sewer research station in Frejlev. Only few - if any - sewer monitoring stations like the one in Frejlev exist. Without no doubt the field data produced - especially the time series - in the course of time will serve as a unique basis for projects dealin...

  9. The Sewer Research Station in Frejlev

    DEFF Research Database (Denmark)

    Hvitved-Jacobsen, Thorkild; Schaarup-Jensen, Kjeld

    This report for the 1999 activities at the sewer research station in Frejlev. Only few - if any - sewer monitoring stations like the one in Frejlev exist. Without no doubt the field data produced - especially the time series - in the course of time will serve as a unigue basis for projects dealin...

  10. Guidelines for Learning Stations.

    Science.gov (United States)

    Fehrle, Carl C.; Schulz, Jolene

    Guidelines for designing and planning learning stations for pupils at the elementary grade level include suggestions on how to develop a station that will be successful in meeting the learners' needs. Instructions for the use of tapes at a station and matching pupils with stations are given, as are guidelines on classroom arrangement and record…

  11. Swedish encapsulation station review

    International Nuclear Information System (INIS)

    Andersson, Sven Olof; Brunzell, P.; Heibel, R.; McCarthy, J.; Pennington, C.; Rusch, C.; Varley, G.

    1998-06-01

    In the Encapsulation Station (ES) Review performed by NAC International, a number of different areas have been studied. The main objectives with the review have been to: Perform an independent review of the cost estimates for the ES presented in SKB's document 'Plan 1996'. This has been made through comparisons between the ES and BNFL's Waste Encapsulation Plant (WEP) at Sellafield as well as with the CLAB facility. Review the location of the ES (at the CLAB site or at the final repository) and its interaction with other parts of the Swedish system for spent fuel management. Review the logistics and plant capacity of the ES. Identify important safety aspects of the ES as a basis for future licensing activities. Based on NAC International's experience of casks for transport and storage of spent fuel, review the basic design of the copper/steel canister and the transport cask. This review insides design, manufacturing, handling and licensing aspects. Perform an overall comparison between the ES project and the CLAB project with the objective to identify major project risks and discuss their mitigation

  12. Swedish encapsulation station review

    Energy Technology Data Exchange (ETDEWEB)

    Andersson, Sven Olof; Brunzell, P.; Heibel, R.; McCarthy, J.; Pennington, C.; Rusch, C.; Varley, G. [NAC International, Zuerich (Switzerland)

    1998-06-01

    In the Encapsulation Station (ES) Review performed by NAC International, a number of different areas have been studied. The main objectives with the review have been to: Perform an independent review of the cost estimates for the ES presented in SKB`s document `Plan 1996`. This has been made through comparisons between the ES and BNFL`s Waste Encapsulation Plant (WEP) at Sellafield as well as with the CLAB facility. Review the location of the ES (at the CLAB site or at the final repository) and its interaction with other parts of the Swedish system for spent fuel management. Review the logistics and plant capacity of the ES. Identify important safety aspects of the ES as a basis for future licensing activities. Based on NAC International`s experience of casks for transport and storage of spent fuel, review the basic design of the copper/steel canister and the transport cask. This review insides design, manufacturing, handling and licensing aspects. Perform an overall comparison between the ES project and the CLAB project with the objective to identify major project risks and discuss their mitigation 19 refs, 9 figs, 35 tabs

  13. Remediation of contaminated areas in the aftermath of the accident at the Fukushima Daiichi Nuclear Power Station. Overview, analysis and lessons learned. Part 1. A report on the ''decontamination pilot project''

    International Nuclear Information System (INIS)

    Nakayama, Shinichi; Kawase, Keiichi; Iijima, Kazuki; Miyahara, Kaname; Hardie, Susan; McKinley, Ian; Klein, Liza; Yashio, Shoko

    2015-03-01

    In the wake of the Great Tohoku earthquake and tsunami, which resulted in significant damage to the Fukushima Daiichi nuclear power station, considerable radioactive discharge and deposition occurred. Populations were evacuated from the zones that received the most deposition and overarching 'Special Measures' laws established the Ministry of the Environment (MOE) as the department responsible for decontamination to remediate the environment. Major challenges to implementing full-scale environmental decontamination were the absence of real-world examples and also lack of experience in planning and implementing decontamination technology appropriate to the physical and social boundary conditions in both Japan and Fukushima. The Japan Atomic Energy Agency (JAEA) was thus charged with conducting a range of 'Decontamination Pilot Project' to examine the applicability of decontamination technologies, with a special focus on reducing dose rates and thus allowing evacuees to return to re-establish their normal lifestyles as quickly as possible, whilst simultaneously maintaining worker safety. The Decontamination Pilot Project was implemented at 16 sites in 11 municipalities within the evacuated zone, including locations that received the highest deposition. Despite tight boundary conditions in terms of timescale and resources, the Decontamination Pilot Project provides a good basis for developing recommendations on how to assure decontamination efficiency and worker safety whilst additionally constraining costs, subsequent waste management and environmental impacts. The Decontamination Pilot Project has thus played a key role in the drafting of guidelines and manuals that are currently being used as a source of reference by the national government, local municipalities and the contractors performing regional decontamination. Part 1 of this report summarises the Decontamination Pilot Project, providing the background required to put this work in context for an

  14. Two-Column Aerosol Project (TCAP): Ground-Based Radiation and Aerosol Validation Using the NOAA Mobile SURFRAD Station Field Campaign Report

    Energy Technology Data Exchange (ETDEWEB)

    Michalsky, Joseph [National Oceanic and Atmospheric Administration (NOAA), Boulder, CO (United States); Lantz, Kathy [Univ. of Colorado, Boulder, CO (United States)

    2016-05-01

    The National Oceanic and Atmospheric Administration (NOAA) is preparing for the launch of the Geostationary Operational Environmental Satellite R-Series (GOES-R) satellite in 2015. This satellite will feature higher time (5-minute versus 30-minute sampling) and spatial resolution (0.5 km vs 1 km in the visible channel) than current GOES instruments provide. NOAA’s National Environmental Satellite Data and Information Service has funded the Global Monitoring Division at the Earth System Research Laboratory to provide ground-based validation data for many of the new and old products the new GOES instruments will retrieve specifically related to radiation at the surface and aerosol and its extensive and intensive properties in the column. The Two-Column Aerosol Project (TCAP) had an emphasis on aerosol; therefore, we asked to be involved in this campaign to de-bug our new instrumentation and to provide a new capability that the U.S. Department of Energy (DOE) Atmospheric Radiation Measurement (ARM) Climate Research Facility’s Mobile Facilities (AMF) did not possess, namely surface albedo measurement out to 1625 nm. This gave us a chance to test remote operation of our new multi-filter rotating shadowband radiometer/multi-filter radiometer (MFRSR/MFR) combination. We did not deploy standard broadband shortwave and longwave radiation instrumentation because ARM does this as part of every AMF deployment. As it turned out, the ARM standard MFRSR had issues, and we were able to provide the aerosol column data for the first 2 months of the campaign covering the summer flight phase of the deployment. Using these data, we were able to work with personnel at Pacific Northwest National Laboratory (PNNL) to retrieve not only aerosol optical depth (AOD), but single scattering albedo and asymmetry parameter, as well.

  15. Hot gas cleaning, a targeted project

    Energy Technology Data Exchange (ETDEWEB)

    Romey, I. [University of Essen, Essen (Germany)

    1998-11-01

    Advanced hot gas cleaning systems will play a key role in future integrated combined cycle technologies. IGCC demonstration plants in operation or under construction are at present equipped with conventional wet gas scrubbing and cleaning systems. Feasibility studies for those IGCC plants have shown that the total efficiency of the processes can be improved using hot gas cleaning systems. However, this technology has not been developed and tested at a technical scale. Six well-known European industrial companies and research centres jointly worked together since January 1996 on a Targeted Project `Hot Gas Cleaning` to investigate and develop new hot gas cleaning systems for advanced clean coal power generation processes. In addition project work on chemical analysis and modelling was carried out in universities in England and Germany. The latest main findings were presented at the workshop. The main project aims are summarised as follows: to increase efficiency of advanced power generation processes; to obtain a reduction of alkalis and environmental emissions e.g. SO{sub 2}, NO{sub x}, CO{sub 2} and dust; and to develop the design basis for future industrial plants based on long-term operation of laboratory, pilot and demo-plants. To cover a range of possible process routes for future hot gas cleaning systems the following research programme is under investigation: removal of trace elements by different commercial and self developed sorbents; gas separation by membranes; separation of gas turbine relevant pollutants by hot filter dust and; H{sub 2}S removal and gas dedusting at high temperatures. 13 figs.

  16. Development and testing of a high temperature (673-1273K), high pressure regenerative desulphurization process for IGCC concepts

    Energy Technology Data Exchange (ETDEWEB)

    Janssen, F.J.J.G.; Meijer, R. (KEMA Fossil Power Plants, Arnhem (Netherlands))

    1994-01-01

    In the period 1990-1993 a European Community (EC) subsidized international project on the subject of high-temperature and high-pressure desulfurization of coal gas has been carried out within the framework of the JOULE 1 program. This report is a summary of the final report, in which an overview is given of the developed and tested absorbents and the results of a feasibility study for a 100 MWe Integrated Coal Gasification Combined Cycle (ICGCC) in combination with a high-temperature desulfurization process. The Utrecht University in Utrecht, Netherlands, developed absorbents in cooperation with The Dutch Centre for Gas Technology GASTEC in Apeldoorn, Netherlands. The absorbents are tested by KEMA and the Netherlands Energy Research Foundation in Petten, Netherlands. Foster Wheeler in Livingston, New Jersey, USA, executed the feasibility study. The combination of iron oxide/molybdenum oxide on aluminium phosphate appears to be the most promising absorbent. The preparation method has been patented. From the feasibility study it appeared that by means of a high-temperature desulfurization process the investment and operational costs can be reduced considerably. Further development of the absorbent and the accompanying reactor concept already has started in a new EC project within the framework of the JOULE 1 program

  17. Co-benefits of including CCS projects in the CDM in India's power sector

    International Nuclear Information System (INIS)

    Eto, R.; Murata, A.; Uchiyama, Y.; Okajima, K.

    2013-01-01

    This study examines the effects of the inclusion of the co-benefits on the potential installed capacity of carbon dioxide capture and storage (CCS) projects with a linear programming model by the clean development mechanism (CDM) in India's power sector. It is investigated how different marginal damage costs of air pollutants affect the potential installed capacity of CCS projects in the CDM with a scenario analysis. Three results are found from this analysis. First, large quantity of IGCC with CCS becomes realizable when the certified emission reduction (CER) prices are above US$56/tCO 2 in the integrated Northern, Eastern, Western, and North-Eastern regional grids (NEWNE) and above US $49/tCO 2 in the Southern grid. Second, including co-benefits contributes to decrease CO 2 emissions and air pollutants with introduction of IGCC with CCS in the CDM at lower CER prices. Third, the effects of the co-benefits are limited in the case of CCS because CCS reduces larger amount of CO 2 emissions than that of air pollutants. Total marginal damage costs of air pollutants of US$250/t and US$200/t lead to CER prices of US$1/tCO 2 reduction in the NEWNE grid and the Southern grid. - Highlights: • We estimate effects of co-benefits on installed capacity of CCS projects in the CDM. • We develop a linear programming (LP) model of two grids of India. • Including co-benefits contributes to introduce IGCC with CCS in the CDM at lower CER prices

  18. The Miksova water power station

    International Nuclear Information System (INIS)

    2005-01-01

    This leaflet describes the Miksova water power station. The Miksova water power station is part of the second derived cascade of hydro power stations on the river Vah. It was built at the end of a huge development in Slovak hydro-energy in the late 1950's and the beginning of the 1960's. It is the second water power station on this derived cascade, which is situated downstream the Hricov reservoir and water power station. At the power station, three turbine sets with vertical Kaplan turbines are installed with a total power output of 3 x 31.2 = 93.6 MW. With this power output the Miksova water power station (Miksova I) was the biggest water power station in the Slovak Republic until the construction of Pumping water power station Liptovska Mara. And it is still the biggest channel water power station on the Vah so far. It was put into operation during the period 1963 to 1965. There are three turbine sets with Kaplan turbines from CKD Blansko, with a synchronous hydro-alternator installed in the power station. Their installed capacity is 93.6 MW in total and the projected annual production of electrical energy is 207 GWh. The turbines are fi ve-bladed (on the Hricov and Povazska Bystrica water power stations they are four-bladed) and the impeller wheel has a diameter of 4800 mm. They are designed for extension of the head from 24.1 to 22.21 m and each of them has an absorption capacity of 134 m 3 .s -1 nd a nominal operating speed of 2.08 m 3 .s -1 , runaway speed 4.9 m 3 .s -1 . Each synchronous hydro-alternator has a maximum power output of 31.2 MW, a nominal voltage of 10.5 kV and power factor cos φ of 0.8. Power from the power station is led out through 110 kV switchgear. The water power station operates under automatic turbine mode of operation with remote indication and control from the Dispatch Centre at Vodne elektrarne, in Trencin. From start of operation until the end of 2003 all three turbine sets operated for a total of 450,500 running hours and the

  19. Controversial power station

    International Nuclear Information System (INIS)

    Marcan, P.

    2008-01-01

    When information on plans to build a power station in Trebisov first appeared reactions differed. A 40-billion investment in a town with more than 20% unemployment seemed attractive. But some people did not like the idea of having a power plant located in the town. Around one year after the investment was officially announced TREND returned to Trebisov. In the meantime the investor has managed to overcome one of the biggest obstacles on its way to building a new power plant. The ministry responsible gave the environmental study a positive rating. But objectors are still not sure that everything is fine. They claim that the study misinterprets data and that the ministry did not show expertise when evaluating it. 'Is it possible that a coal power plant located in a town would have twice as many positive effects on peoples' health than negative ones? Why don't we build them everywhere?'asked the chairman of the civic society, Trebisov nahlas, Gejza Gore. The developer of the project, Ceskoslovenska energeticka spolocnost (CES), Kosice is fighting back and claims that their counterpart lacks professional arguments. In the meantime it is preparing for area management proceedings. Trebisov is also involved in the discussion and claims that the town planning scheme does not include such a project. The Ministry of Construction has a different opinion. In the opinion of the Ministry the town planning scheme allows a 885-megawatt power plant to be built only a few hundred meters away from housing estates. (author)

  20. Reference Climatological Stations

    Data.gov (United States)

    National Oceanic and Atmospheric Administration, Department of Commerce — The Reference Climatological Stations (RCS) network represents the first effort by NOAA to create and maintain a nationwide network of stations located only in areas...

  1. Streamflow Gaging Stations

    Data.gov (United States)

    Department of Homeland Security — This map layer shows selected streamflow gaging stations of the United States, Puerto Rico, and the U.S. Virgin Islands, in 2013. Gaging stations, or gages, measure...

  2. Fire Stations - 2007

    Data.gov (United States)

    Kansas Data Access and Support Center — Fire Station Locations in Kansas Any location where fire fighters are stationed at or based out of, or where equipment that such personnel use in carrying out their...

  3. Hammond Bay Biological Station

    Data.gov (United States)

    Federal Laboratory Consortium — Hammond Bay Biological Station (HBBS), located near Millersburg, Michigan, is a field station of the USGS Great Lakes Science Center (GLSC). HBBS was established by...

  4. Water Level Station History

    Data.gov (United States)

    National Oceanic and Atmospheric Administration, Department of Commerce — Images contain station history information for 175 stations in the National Water Level Observation Network (NWLON). The NWLON is a network of long-term,...

  5. Weather Radar Stations

    Data.gov (United States)

    Department of Homeland Security — These data represent Next-Generation Radar (NEXRAD) and Terminal Doppler Weather Radar (TDWR) weather radar stations within the US. The NEXRAD radar stations are...

  6. Big Game Reporting Stations

    Data.gov (United States)

    Vermont Center for Geographic Information — Point locations of big game reporting stations. Big game reporting stations are places where hunters can legally report harvested deer, bear, or turkey. These are...

  7. Ocean Station Vessel

    Data.gov (United States)

    National Oceanic and Atmospheric Administration, Department of Commerce — Ocean Station Vessels (OSV) or Weather Ships captured atmospheric conditions while being stationed continuously in a single location. While While most of the...

  8. Fire Stations - 2009

    Data.gov (United States)

    Kansas Data Access and Support Center — Fire Stations in Kansas Any location where fire fighters are stationed or based out of, or where equipment that such personnel use in carrying out their jobs is...

  9. Newport Research Station

    Data.gov (United States)

    Federal Laboratory Consortium — The Newport Research Station is the Center's only ocean-port research facility. This station is located at Oregon State University's Hatfield Marine Science Center,...

  10. The Grossmatt hydro-power station

    International Nuclear Information System (INIS)

    Hintermann, M.

    2006-01-01

    This final report for the Swiss Federal Office of Energy (SFOE) presents the project for a small hydropower station on the Birs river in north-western Switzerland. The report reviews the history of the project, in which a new 385 kW-hydro-power station at the site of an earlier installation is foreseen. Details are presented on the investigations made and on the co-ordination with the owners of the hydro-power station situated up-river, the local power utility and the local authorities. Also, the requirements placed on the project by the fishing authorities are quoted and the solution foreseen is described. Also discussed are the requirements placed on the project by legislation on environmental impact and flood protection. Figures on electrical energy production and building costs are presented

  11. UPS Project for GSM base stations with a fuel cell (PEM fuel cell back-up system) - Final report; Projekt USV fuer GSM-Basisstationen mit BZ (PEM fuel cell back-up system) - Abschlussbericht

    Energy Technology Data Exchange (ETDEWEB)

    Trachte, U.

    2007-07-01

    The University of applied sciences HTA Lucerne designed a prototype of an uninterruptible power supply (UPS) with Fuel Cell technology instead of lead-acid batteries and put it into operation. The delayed start-up of the Fuel Cell was bridged with ultra capacitor technology. In a first project stage the system was designed, assembled and tested in laboratory. In a second stage the installation was connected to a real base station of a telecommunication antenna and put to field tests for one year. The field test included monthly simulations of power failure with antenna load of about 2.4 kW as well as tests with external load up to 8.5 kW to establish the characteristic diagram. Hydrogen was provided by two 50 l pressure tanks. The full quantity of hydrogen secured a stand-alone operation of the Fuel Cell system for about 6 hours under antenna load. The results of the 101 grid-failure simulations demonstrate a very reliable start-up behaviour of the Fuel Cell System. Also during a real power failure due to a thunderstorm the installation provided the demanded power without any problem. The total duration of operation of the Fuel Cell during the field tests was 39 hours. No degradation could be noticed. The project takes place in collaboration with the industrial partners APC Industrial Systems, as a producer and market leader of UPS-Systems, and Swisscom Mobile AG, as a user of UPS-systems in telecommunications. Following the good results and in order to get more experience in long-term operation of the Fuel Cell system the tests will go on for two more years. (author)

  12. NASA space station automation: AI-based technology review

    Science.gov (United States)

    Firschein, O.; Georgeff, M. P.; Park, W.; Neumann, P.; Kautz, W. H.; Levitt, K. N.; Rom, R. J.; Poggio, A. A.

    1985-01-01

    Research and Development projects in automation for the Space Station are discussed. Artificial Intelligence (AI) based automation technologies are planned to enhance crew safety through reduced need for EVA, increase crew productivity through the reduction of routine operations, increase space station autonomy, and augment space station capability through the use of teleoperation and robotics. AI technology will also be developed for the servicing of satellites at the Space Station, system monitoring and diagnosis, space manufacturing, and the assembly of large space structures.

  13. Small wind power plants : results of the Nordic wind diesel projects for large telecommunications companies; Implantation d'une centrale eolienne comme source d'energie d'appoint pour des stations de telecommunications

    Energy Technology Data Exchange (ETDEWEB)

    Ilinca, A.; Chaumel, J.L. [ATI Eolien, Rimouski, PQ (Canada); Thibault, G. [Entreprises MB, PQ (Canada)

    2005-07-01

    Two wind-diesel generating stations have been installed at telecommunication towers in the remote communities of Kuujjuarapik and Lac Julien in northern Quebec. The use of wind power contributes to the sustainable development in these remote areas by lowering the reliance on costly helicopter-transported diesel fuel and by reducing the release of greenhouse gases to the atmosphere. The technical characteristics of the Bergey 100 kW turbine with battery charger were presented along with the technical characteristics of the EolDie control panel that controls the supply of electricity from either the wind or diesel power generators. For the first time, the ATI-Wind technology system that was installed can supply the needs of the large telecommunication towers of Bell Canada and Telebec from either the wind or the diesel generators. The system is also capable of shutting down the diesel generators when wind energy is sufficient to take over. Early results from June 2005 showed that the diesel generators could be turned off for 55 per cent of the time. Preliminary results of these 2 projects were discussed by the firms in charge of the diesel and wind aspects and recommendations for improvements to the control systems were presented. 11 figs.

  14. CDIP Station Data Collection - All Stations

    Data.gov (United States)

    Scripps Institution of Oceanography, UC San Diego — The Coastal Data Information Program's station data collection consists of all publicly-released coastal environment measurements taken over the program's history, a...

  15. Shippingport Station Decommissioning Project site release protocol

    International Nuclear Information System (INIS)

    Handy, J.W.

    1988-01-01

    The Richland, Washington field office of the DOE and its Remedial Actions Contractor, GE, took possession of the SSDP site in September 1984. In February of the following year, DOE-HQ issued generic, site independent guidelines taken from existing radiation protection standards. Basic generic dose limits were English equivalents of 1 mSv (100 mrem) per year averaged over the lifetime of any individual member of the general public. Hot spot limits were given. Occupied or habitable structures were limited to 5.2 x 10 -9 C/Kg h (20mR/h). Surface contamination was limited to standards plus average and maximum contact dose rates of 2 microGy (0.2 mrad) per hour and 10 microGy (1 mrad) per hour respectively. In addition, ''all exposures ... were to be limited to levels that (were) as low as reasonably achievable (ALARA).'' Authorized limits higher than these guidelines were allowed under given exceptional circumstances. GE determined the allowable radionuclide concentrations that could remain in soil and included rubble, and not dose the resident farmer to more than 1 mSv (100 mrem) per year. Under more conservative scenarios, however, exposures were controlled for buried, potentially occupationally occupiable, concrete substructures, to souvenir items, or to buried, but potentially exposed, concrete slabs. GE incorporated the scenario's pathways into a document implementing specific site release criteria which cannot be exceeded if the site is to be released unconditionally. 3 refs., 1 fig

  16. California Hydrogen Infrastructure Project

    Energy Technology Data Exchange (ETDEWEB)

    Heydorn, Edward C

    2013-03-12

    Air Products and Chemicals, Inc. has completed a comprehensive, multiyear project to demonstrate a hydrogen infrastructure in California. The specific primary objective of the project was to demonstrate a model of a real-world retail hydrogen infrastructure and acquire sufficient data within the project to assess the feasibility of achieving the nation's hydrogen infrastructure goals. The project helped to advance hydrogen station technology, including the vehicle-to-station fueling interface, through consumer experiences and feedback. By encompassing a variety of fuel cell vehicles, customer profiles and fueling experiences, this project was able to obtain a complete portrait of real market needs. The project also opened its stations to other qualified vehicle providers at the appropriate time to promote widespread use and gain even broader public understanding of a hydrogen infrastructure. The project engaged major energy companies to provide a fueling experience similar to traditional gasoline station sites to foster public acceptance of hydrogen. Work over the course of the project was focused in multiple areas. With respect to the equipment needed, technical design specifications (including both safety and operational considerations) were written, reviewed, and finalized. After finalizing individual equipment designs, complete station designs were started including process flow diagrams and systems safety reviews. Material quotes were obtained, and in some cases, depending on the project status and the lead time, equipment was placed on order and fabrication began. Consideration was given for expected vehicle usage and station capacity, standard features needed, and the ability to upgrade the station at a later date. In parallel with work on the equipment, discussions were started with various vehicle manufacturers to identify vehicle demand (short- and long-term needs). Discussions included identifying potential areas most suited for hydrogen fueling

  17. Solidifying power station resins and sludges

    International Nuclear Information System (INIS)

    Willis, A.S.D.; Haigh, C.P.

    1984-01-01

    Radioactive ion exchange resins and sludges arise at nuclear power stations from various operations associated with effluent treatment and liquid waste management. As the result of an intensive development programme, the Central Electricity Generating Board (CEGB) has designed a process to convert power station resins and sludges into a shielded, packaged solid monolithic form suitable for final disposal. Research and development, the generic CEGB sludge/resin conditioning plant and the CEGB Active Waste Project are described. (U.K.)

  18. Non-Coop Station History

    Data.gov (United States)

    National Oceanic and Atmospheric Administration, Department of Commerce — Station history documentation for stations outside the US Cooperative Observer network. Primarily National Weather Service stations assigned WBAN station IDs. Other...

  19. Shippingport station communications program

    International Nuclear Information System (INIS)

    Stote, J.J.

    1988-01-01

    At the Shippingport Station Decommissioning Project, the central idea of the communications program that was developed for use was purposely designed to be as uncomplicated as possible. The central theme, that was developed and communicated, is that all nuclear plants will someday need to be retired and also decommissioned. The Shippingport Plant, originally constructed as a demonstration nuclear power plant, was now being decommissioned as a demonstration to the world-wide nuclear industry that this evolution can be done in a safe and cost-effective manner. Furthermore, the technology currently exists to complete this process. The new phase of the communications program was initiated even before the responsibility for the plant was transferred from Duquesne Light to GE. With such a change forthcoming, it was necessary to inform local officials of these plans, and the reasons for them. Equally important was the need to inform a variety of agencies and offices in the three-state area of the changes, and the continuing need to involve them in the Site Emergency Plan. This document was also revised in recognition of changing site conditions, as well as the changes in responsibility. 1 ref

  20. Space Station automation and robotics

    Science.gov (United States)

    1987-01-01

    A group of fifteen students in the Electrical Engineering Department at the University of Maryland, College Park, has been involved in a design project under the sponsorship of NASA Headquarters, NASA Goddard Space Flight Center and the Systems Research Center (SRC) at UMCP. The goal of the NASA/USRA project was to first obtain a refinement of the design work done in Spring 1986 on the proposed Mobile Remote Manipulator System (MRMS) for the Space Station. This was followed by design exercises involving the OMV and two armed service vehicle. Three students worked on projects suggested by NASA Goddard scientists for ten weeks this past summer. The knowledge gained from the summer design exercise has been used to improve our current design of the MRMS. To this end, the following program was undertaken for the Fall semester 1986: (1) refinement of the MRMS design; and (2) addition of vision capability to our design.

  1. Base Station Performance Model

    OpenAIRE

    Walsh, Barbara; Farrell, Ronan

    2005-01-01

    At present the testing of power amplifiers within base station transmitters is limited to testing at component level as opposed to testing at the system level. While the detection of catastrophic failure is possible, that of performance degradation is not. This paper proposes a base station model with respect to transmitter output power with the aim of introducing system level monitoring of the power amplifier behaviour within the base station. Our model reflects the expe...

  2. Amtrak Rail Stations (National)

    Data.gov (United States)

    Department of Transportation — Updated database of the Federal Railroad Administration's (FRA) Amtrak Station database. This database is a geographic data set containing Amtrak intercity railroad...

  3. Cooperative Station History Forms

    Data.gov (United States)

    National Oceanic and Atmospheric Administration, Department of Commerce — Various forms, photographs and correspondence documenting the history of Cooperative station instrumentation, location changes, inspections, and...

  4. Nuclear Station Facilities Improvement Planning

    International Nuclear Information System (INIS)

    Hooks, R. W.; Lunardini, A. L.; Zaben, O.

    1991-01-01

    An effective facilities improvement program will include a plan for the temporary relocation of personnel during the construction of an adjoining service building addition. Since the smooth continuation of plant operation is of paramount importance, the phasing plan is established to minimize the disruptions in day-to-day station operation and administration. This plan should consider the final occupancy arrangements and the transition to the new structure; for example, computer hookup and phase-in should be considered. The nuclear industry is placing more emphasis on safety and reliability of nuclear power plants. In order to do this, more emphasis is placed on operations and maintenance. This results in increased size of managerial, technical and maintenance staffs. This in turn requires improved office and service facilities. The facilities that require improvement may include training areas, rad waste processing and storage facilities, and maintenance facilities. This paper discusses an approach for developing an effective program to plan and implement these projects. These improvement projects can range in magnitude from modifying a simple system to building a new structure to allocating space for a future project. This paper addresses the planning required for the new structures with emphasis on site location, space allocation, and internal layout. Since facility planning has recently been completed by Sargent and Leyden at six U. S. nuclear stations, specific examples from some of those plants are presented. Site planning and the establishment of long-range goals are of the utmost importance when undertaking a facilities improvement program for a nuclear station. A plan that considers the total site usage will enhance the value of both the new and existing facilities. Proper planning at the beginning of the program can minimize costs and maximize the benefits of the program

  5. INTERACT Station Catalogue - 2015

    DEFF Research Database (Denmark)

    INTERACT stations are located in all major environmental envelopes of the Arctic providing an ideal platform for studying climate change and its impact on the environment and local communities. Since alpine environments face similar changes and challenges as the Arctic, the INTERACT network also ...... catalogue includes descriptions of 73 research stations included in the network at the time of printing....

  6. Meyrin Petrol Station

    CERN Multimedia

    2006-01-01

    Please note that the Meyrin petrol station will be closed for maintenance work on Tuesday 19 and Wednesday 20 December 2006. If you require petrol during this period we invite you to use the Prévessin petrol station, which will remain open. TS-IC-LO Section Tel.: 77039 - 73793

  7. Nuclear power stations licensing

    International Nuclear Information System (INIS)

    Solito, J.

    1978-04-01

    The judicial aspects of nuclear stations licensing are presented. The licensing systems of the United States, Spain, France and Federal Republic of Germany are focused. The decree n 0 60.824 from July 7 sup(th), 1967 and the following legislation which define the systematic and area of competence in nuclear stations licensing are analysed [pt

  8. SPS rectifier stations

    CERN Multimedia

    CERN PhotoLab

    1974-01-01

    The first of the twelves SPS rectifier stations for the bending magnets arrived at CERN at the end of the year. The photograph shows a station with the rectifiers on the left and in the other three cubicles the chokes, capacitors and resistor of the passive filter.

  9. Ondergronds Station Blijdorp, Rotterdam

    NARCIS (Netherlands)

    Hijma, M.P.|info:eu-repo/dai/nl/266562426; Cohen, K.M.|info:eu-repo/dai/nl/185633374

    2014-01-01

    Het is in de herfst van 2005. Een lief meisje, Marieke, rijdt op haar vouwfiets door Rotterdam. Bij het Centraal Station is het al tijden een grote bouwplaats. Onder de nieuwe hal komt een veel groter metrostation en ook onder de Statenweg in Blijdorp is een grote bouwput voor een nieuw station.

  10. Discussion of the design of satellite-laser measurement stations in the eastern Mediterranean under the geological aspect. Contribution to the earthquake prediction research by the Wegener Group and to NASA's Crustal Dynamics Project

    Science.gov (United States)

    Paluska, A.; Pavoni, N.

    1983-01-01

    Research conducted for determining the location of stations for measuring crustal dynamics and predicting earthquakes is discussed. Procedural aspects, the extraregional kinematic tendencies, and regional tectonic deformation mechanisms are described.

  11. Oceanographic station, temperature profiles, meteorological, and other data from bottle and XBT from the DOLPHIN as part of the Marine Resources Monitoring, Assessment and Prediction (MARMAP) project from 1974-01-09 to 1974-01-12 (NODC Accession 7400287)

    Data.gov (United States)

    National Oceanic and Atmospheric Administration, Department of Commerce — Oceanographic station, temperature profiles, meteorological, and other data were collected from bottle and XBT casts from the DOLPHIN from 09 January 1974 to 12...

  12. Central Station Design Options

    DEFF Research Database (Denmark)

    2011-01-01

    . The work identifies the architecture, sizing and siting of prospective Central Stations in Denmark, which can be located at shopping centers, large car parking lots or gas stations. Central Stations are planned to be integrated in the Danish distribution grid. The Danish island of Bornholm, where a high...... overloading, more reference points might be necessary to represent various transformer loading levels. The subject of safety in Central Station is also addressed. A number of safety rules based on European standards apply to AC charging equipment up to 44 kW. The connection interlock and the automatic de......-energization are identified as fundamental requirements for safety in such a charging station. The connection interlock is a solution which ensures that no power is applied to the DC cable when the EV connector is not connected. The automatic de-energization device ensures that whenever a strain on the cable is detected, e...

  13. Accommodating life sciences on the Space Station

    Science.gov (United States)

    Arno, Roger D.

    1987-01-01

    The NASA Ames Research Center Biological Research Project (BRP) is responsible for identifying and accommodating high priority life science activities, utilizing nonhuman specimens, on the Space Station and is charged to bridge the gap between the science community and the Space Station Program. This paper discusses the approaches taken by the BRP in accomodating these research objectives to constraints imposed by the Space Station System, while maintaining a user-friendly environment. Consideration is given to the particular research disciplines which are given priority, the science objectives in each of these disciplines, the functions and activities required by these objectives, the research equipment, and the equipment suits. Life sciences programs planned by the Space Station participating partners (USA, Europe, Japan, and Canada) are compared.

  14. Developmental state and perspectives of USSR power stations, espec. nuclear power stations

    International Nuclear Information System (INIS)

    1983-01-01

    According to the resolutions of the 25th and 26th party congresses of the CPSU, the Soviet electric and thermal energy economy envisages as the mainstreams in development: Energy projects based on nuclear fuel, i.e. nuclear power stations (NPS), nuclear heat- and -power stations (NHPS) and nuclear heat stations (NHS); fuel-energy complexes: Ekibastuz, Kansk-Achinsk, West-Siberian complex (Tyumen); power stations utilizing non-conventional regenerative energy sources, i.e. solar, geothermal, MHD power stations. Further down, an overview is given on the developmental perspectives of nuclear-heat and nuclear-power economy and on the development of energy management based on fossil fuels. (orig./UA) [de

  15. Space station operations management

    Science.gov (United States)

    Cannon, Kathleen V.

    1989-01-01

    Space Station Freedom operations management concepts must be responsive to the unique challenges presented by the permanently manned international laboratory. Space Station Freedom will be assembled over a three year period where the operational environment will change as significant capability plateaus are reached. First Element Launch, Man-Tended Capability, and Permanent Manned Capability, represent milestones in operational capability that is increasing toward mature operations capability. Operations management concepts are being developed to accomodate the varying operational capabilities during assembly, as well as the mature operational environment. This paper describes operations management concepts designed to accomodate the uniqueness of Space Station Freedoom, utilizing tools and processes that seek to control operations costs.

  16. Waste Transfer Stations

    DEFF Research Database (Denmark)

    Christensen, Thomas Højlund

    2011-01-01

    tion and transport is usually the most costly part of any waste management system; and when waste is transported over a considerable distance or for a long time, transferring the waste from the collection vehicles to more efficient transportation may be economically beneficial. This involves...... a transfer station where the transfer takes place. These stations may also be accessible by private people, offering flexibility to the waste system, including facilities for bulky waste, household hazardous waste and recyclables. Waste transfer may also take place on the collection route from small...... describes the main features of waste transfer stations, including some considerations about the economical aspects on when transfer is advisable....

  17. Environmental radioactivity in the antarctic station

    International Nuclear Information System (INIS)

    Gonzalez, S.; Osores, J.; Martinez, J.; Lopez, E.; Jara, R.

    1998-01-01

    Study about environmental radioactivity in the Peruvian antarctic station Machu Pichu they were carried out during the last three periods to the southern summer. The objective of the project it is to evaluate environmental component in order to elaborate a study it base on the levels background radioactivity and artificial in the antarctic region

  18. Adaptive downtilt for cellular base stations

    NARCIS (Netherlands)

    Mestrom, R.M.C.; Coenen, T.J.; Smolders, A.B.

    2012-01-01

    Efficiency, reconfigurability, and power consumption are paramount for future communication systems in applications such as cellular handsets, base stations and home networking systems. We present our work in the European PANAMA project which addresses the associated challenges. Our work focuses on

  19. National FCEV and Hydrogen Fueling Station Scenarios

    Energy Technology Data Exchange (ETDEWEB)

    Bush, Brian; Melaina, Marc

    2016-06-09

    This presentation provides a summary of the FY16 activities and accomplishments for NREL's national fuel cell electric vehicle (FCEV) and hydrogen fueling station scenarios project. It was presented at the U.S. Department of Energy Hydrogen and Fuel Cells Program 2016 Annual Merit Review and Peer Evaluation Meeting on June 9, 2016, in Washington, D.C.

  20. Impact studies and nuclear power stations

    International Nuclear Information System (INIS)

    Chambolle, Thierry

    1981-01-01

    Impact studies form an essential part of environmental protection. The impact study discipline has enabled the EDF to have a better understanding of the effects of nuclear power stations on the environment and to remedy them at the project design stage [fr

  1. Establishment of Karadeniz Technical University Permanent GNSS Station as Reactivated of TRAB IGS Station

    Directory of Open Access Journals (Sweden)

    Kazancı Selma Zengin

    2017-12-01

    Full Text Available In recent years, Global Navigation Satellite Systems (GNSS have gained great importance in terms of the benefi ts it provides such as precise geodetic point positioning, determining crustal deformations, navigation, vehicle monitoring systems and meteorological applications etc. As in Turkey, for this purpose, each country has set up its own GNSS station networks like Turkish National Permanent RTK Network analyzed precise station coordinates and velocities together with the International GNSS Service, Turkish National Fundamental GPS Network and Turkish National Permanent GNSS Network (TNPGN stations not only are utilized as precise positioning but also GNSS meteorology studies so total number of stations are increased. This work is related to the reactivated of the TRAB IGS station which was established in Karadeniz Technical University, Department of Geomatics Engineering. Within the COST ES1206 Action (GNSS4SWEC KTU analysis center was established and Trop-NET system developed by Geodetic Observatory Pecny (GOP, RIGTC in order to troposphere monitoring. The project titled “Using Regional GNSS Networks to Strengthen Severe Weather Prediction” was accepted to the scientifi c and technological research council of Turkey (TUBITAK. With this project, we will design 2 new constructed GNSS reference station network. Using observation data of network, we will compare water vapor distribution derived by GNSS Meteorology and GNSS Tomography. At this time, KTU AC was accepted as E-GVAP Analysis Centre in December 2016. KTU reference station is aimed to be a member of the EUREF network with these studies.

  2. Establishment of Karadeniz Technical University Permanent GNSS Station as Reactivated of TRAB IGS Station

    Science.gov (United States)

    Kazancı, Selma Zengin; Kayıkçı, Emine Tanır

    2017-12-01

    In recent years, Global Navigation Satellite Systems (GNSS) have gained great importance in terms of the benefi ts it provides such as precise geodetic point positioning, determining crustal deformations, navigation, vehicle monitoring systems and meteorological applications etc. As in Turkey, for this purpose, each country has set up its own GNSS station networks like Turkish National Permanent RTK Network analyzed precise station coordinates and velocities together with the International GNSS Service, Turkish National Fundamental GPS Network and Turkish National Permanent GNSS Network (TNPGN) stations not only are utilized as precise positioning but also GNSS meteorology studies so total number of stations are increased. This work is related to the reactivated of the TRAB IGS station which was established in Karadeniz Technical University, Department of Geomatics Engineering. Within the COST ES1206 Action (GNSS4SWEC) KTU analysis center was established and Trop-NET system developed by Geodetic Observatory Pecny (GOP, RIGTC) in order to troposphere monitoring. The project titled "Using Regional GNSS Networks to Strengthen Severe Weather Prediction" was accepted to the scientifi c and technological research council of Turkey (TUBITAK). With this project, we will design 2 new constructed GNSS reference station network. Using observation data of network, we will compare water vapor distribution derived by GNSS Meteorology and GNSS Tomography. At this time, KTU AC was accepted as E-GVAP Analysis Centre in December 2016. KTU reference station is aimed to be a member of the EUREF network with these studies.

  3. A10 – UAS Control Station Ergo-nomics Considerations : Tasks CS-6 through CS-8

    Science.gov (United States)

    2017-08-01

    The overall objective of the control station tasks within Project A-10 is to provide the Federal Aviation Administration (FAA) with information on an ergonomic design of unmanned aircraft system (UAS) control stations which will allow safe piloting o...

  4. "Central Station" Londonis

    Index Scriptorium Estoniae

    2000-01-01

    Londoni galeriis Milch seitsme läti, leedu ja eesti kunstniku projekt "Central Station". Kuraatorid Lisa Panting, Sally Tallant. Eestist osalevad Hanno Soans (Catarina Campinoga koostöös valminud video), Kiwa, Kai Kaljo

  5. Materials Test Station

    Data.gov (United States)

    Federal Laboratory Consortium — When completed, the Materials Test Station at the Los Alamos Neutron Science Center will meet mission need. MTS will provide the only fast-reactor-like irradiation...

  6. Active Marine Station Metadata

    Data.gov (United States)

    National Oceanic and Atmospheric Administration, Department of Commerce — The Active Marine Station Metadata is a daily metadata report for active marine bouy and C-MAN (Coastal Marine Automated Network) platforms from the National Data...

  7. Electrostatic pickup station

    CERN Multimedia

    CERN PhotoLab

    1982-01-01

    Electrostatic pickup station, with 4 interleaved electrodes, to measure beam position in the horizontal and vertical plane. This type is used in the transfer lines leaving the PS (TT2, TT70, TTL2). See also 7904075.

  8. Public Transit Stations

    Data.gov (United States)

    Department of Homeland Security — fixed rail transit stations within the Continental United States, Alaska, Hawaii, the District of Columbia, and Puerto Rico. The modes of transit that are serviced...

  9. Mukilteo Research Station

    Data.gov (United States)

    Federal Laboratory Consortium — Research at the Mukilteo Research Station focuses on understanding the life cycle of marine species and the impacts of ecosystem stressors on anadromous and marine...

  10. Maine Field Station

    Data.gov (United States)

    Federal Laboratory Consortium — In 2000 NOAA's National Marine Fisheries Service established the Maine Field Station in Orono, ME to have more direct involvement in the conservation of the living...

  11. FEMA DFIRM Station Start

    Data.gov (United States)

    Minnesota Department of Natural Resources — This table contains information about station starting locations. These locations indicate the reference point that was used as the origin for distance measurements...

  12. Natural Weathering Exposure Station

    Data.gov (United States)

    Federal Laboratory Consortium — The Corps of Engineers' Treat Island Natural Weathering Exposure Station is a long-term natural weathering facility used to study concrete durability. Located on the...

  13. Routes and Stations

    Data.gov (United States)

    Department of Homeland Security — he Routes_Stations table is composed of fixed rail transit systems within the Continental United States, Alaska, Hawaii, the District of Columbia, and Puerto Rico....

  14. Gas Stations, US, 2010, NAVTEQ

    Data.gov (United States)

    U.S. Environmental Protection Agency — The Gas_Stations dataset is derived from the Navteq 'AUTOSVC' SDC layer (FAC_TYPE=5540) and contains gas stations and petrol stations. This NAVTEQ dataset is...

  15. Enhanced Master Station History Report

    Data.gov (United States)

    National Oceanic and Atmospheric Administration, Department of Commerce — The Enhanced Master Station History Report (EMSHR) is a compiled list of basic, historical information for every station in the station history database, beginning...

  16. Tobruk power station

    Energy Technology Data Exchange (ETDEWEB)

    Boergardts, B

    1978-01-01

    In February of 1975, the Electricity Corporation Benghazi (ECB) awarded a contract for the construction of a turnkey power station and seawater desalination plant in Tobruk, Libya to a consortium under the leadership of BBC Mannheim. This power station has an output of 129 MW and supplies about 24,000 m/sup 3/ of drinking water daily. It went into operation in 1977, two and a half years after the contract was awarded.

  17. Space Station galley design

    Science.gov (United States)

    Trabanino, Rudy; Murphy, George L.; Yakut, M. M.

    1986-01-01

    An Advanced Food Hardware System galley for the initial operating capability (IOC) Space Station is discussed. Space Station will employ food hardware items that have never been flown in space, such as a dishwasher, microwave oven, blender/mixer, bulk food and beverage dispensers, automated food inventory management, a trash compactor, and an advanced technology refrigerator/freezer. These new technologies and designs are described and the trades, design, development, and testing associated with each are summarized.

  18. Leadership at Antarctic Stations.

    Science.gov (United States)

    1987-03-01

    Claseification 6. No. Pegees LEADERSHIP AT ANTARTIC STATIONS hxIs i4 5, C =r~eta(C), 17 Rfs~W (R, Udusiied U)J 7. No Refs 8. Author(s) Edocumesnt I...whether there is a "best" approach to leadership at an Antartic Station and what leadership style may have the most to offer. 3~~ __ ___ Tipesis to be

  19. National Seismic Station

    International Nuclear Information System (INIS)

    Stokes, P.A.

    1982-06-01

    The National Seismic Station was developed to meet the needs of regional or worldwide seismic monitoring of underground nuclear explosions to verify compliance with a nuclear test ban treaty. The Station acquires broadband seismic data and transmits it via satellite to a data center. It is capable of unattended operation for periods of at least a year, and will detect any tampering that could result in the transmission of unauthentic seismic data

  20. STRUVE arc and EUPOS® stations

    Science.gov (United States)

    Lasmane, Ieva; Kaminskis, Janis; Balodis, Janis; Haritonova, Diana

    2013-04-01

    The Struve Geodetic Arc was developed in Years 1816 to 1855, 200 years ago. Historic information on the points of the Struve Geodetic Arc are included in the UNESCO World Heritage list in 2005. Nevertheless, the sites of many points are still not identified nor included in the data bases nowadays. Originally STRUVE arc consisted of 258 main triangles with 265 triangulation points. Currently 34 of the original station points are identified and included in the in the UNESCO World Heritage list. identified original measurement points of the Meridian Arc are located in Sweden (7 points), Norway (15), Finland (83), Russia (1), Estonia (22), Latvia (16), Lithuania (18), Belorussia (28), Ukraine (59) and Moldova (27). In Year 2002 was initiated another large coverage project - European Position Determination System "EUPOS®". Currently there are about 400 continuously operating GNSS (Global Navigation Satellite Systems) stations covering EU countries Estonia, Latvia, Lithuania, Poland, Czech Republic, Slovakia, Hungary, Bulgaria, Romania and East European countries Ukraine and Moldavia. EUPOS® network is a ground based GNSS augmentation system widely used for geodesy, land surveying, geophysics and navigation. It gives the opportunity for fast and accurate position determination never available before. It is an honorable task to use the EUPOS® system for research of the Struve triangulation former sites. Projects with Struve arc can popularize geodesy, geo-information and its meaning in nowadays GIS and GNSS systems. Struve Arc and its points is unique cooperation cross-border object which deserve special attention because of their natural beauty and historical value for mankind. GNSS in geodesy discovers a powerful tool for the verification and validation of the height values of geodetic leveling benchmarks established historically almost 200 years ago. The differential GNSS and RTK methods appear very useful to identify vertical displacement of landscape by means of

  1. Gravitational biology on the space station

    Science.gov (United States)

    Keefe, J. R.; Krikorian, A. D.

    1983-01-01

    The current status of gravitational biology is summarized, future areas of required basic research in earth-based and spaceflight projects are presented, and potential applications of gravitational biology on a space station are demonstrated. Topics covered include vertebrate reproduction, prenatal/postnatal development, a review of plant space experiments, the facilities needed for growing plants, gravimorphogenesis, thigmomorphogenesis, centrifuges, maintaining a vivarium, tissue culture, and artificial human organ generation. It is proposed that space stations carrying out these types of long-term research be called the National Space Research Facility.

  2. Nova isolates noise to quieten stations

    International Nuclear Information System (INIS)

    Milner, G.J.; Frank, L.D.

    1993-01-01

    This paper reviews a technique developed by Nova Corp., to help isolate and measure the acoustic power of individual components in a pipeline compressor and pumping station. The procedure calculates the sound pressure levels of each piece of equipment independently. Based on these measurements, a prediction can be made of the effect of various types of noise treatment techniques on the overall sound levels currently generated or proposed in a future project. This paper describes the equipment to measure the sound levels, techniques for actually measuring the compressor station or equipment area, and techniques used to generate a remediation plan

  3. Upgrade and extension of the climate station at DTU Byg

    DEFF Research Database (Denmark)

    Andersen, Elsa; Dragsted, Janne; Kristensen, Troels V.

    In the period 2013-2014 the project “Upgrade and Extension of the Climate Station at DTU Byg” is carried out at DTU Byg. The aim of the project is to renew the hardware and the software for data acquisition and monitoring, exchange cables and cable connections in order to avoid interference...... of electrical noise from the surroundings and exchange worn out equipment. Further, the aim is to make measured data from the climate station easily available for the users....

  4. Hydrogen Fuelling Stations

    DEFF Research Database (Denmark)

    Rothuizen, Erasmus Damgaard

    . A system consisting of one high pressure storage tank is used to investigate the thermodynamics of fuelling a hydrogen vehicle. The results show that the decisive parameter for how the fuelling proceeds is the pressure loss in the vehicle. The single tank fuelling system is compared to a cascade fuelling......This thesis concerns hydrogen fuelling stations from an overall system perspective. The study investigates thermodynamics and energy consumption of hydrogen fuelling stations for fuelling vehicles for personal transportation. For the study a library concerning the components in a hydrogen fuelling...... station has been developed in Dymola. The models include the fuelling protocol (J2601) for hydrogen vehicles made by Society of Automotive Engineers (SAE) and the thermodynamic property library CoolProp is used for retrieving state point. The components in the hydrogen fuelling library are building up...

  5. Present status and future of the sophisticated work station

    Science.gov (United States)

    Ishida, Haruhisa

    The excellency of the work station is explained, by comparing the functions of software and hardware of work station with those of personal computer. As one of the examples utilizing the functions of work station, desk top publishing is explained. By describing the competition between the Group of ATT · Sun Microsystems which intends to have the leadership by integrating Berkeley version which is most popular at this moment and System V version, and the group led by IBM, future of UNIX as OS of work station is predicted. Development of RISC processor, TRON Plan and Sigma Projects by MITI are also mentioned as its background.

  6. Hydrogen vehicle fueling station

    Energy Technology Data Exchange (ETDEWEB)

    Daney, D.E.; Edeskuty, F.J.; Daugherty, M.A. [Los Alamos National Lab., NM (United States)] [and others

    1995-09-01

    Hydrogen fueling stations are an essential element in the practical application of hydrogen as a vehicle fuel, and a number of issues such as safety, efficiency, design, and operating procedures can only be accurately addressed by a practical demonstration. Regardless of whether the vehicle is powered by an internal combustion engine or fuel cell, or whether the vehicle has a liquid or gaseous fuel tank, the fueling station is a critical technology which is the link between the local storage facility and the vehicle. Because most merchant hydrogen delivered in the US today (and in the near future) is in liquid form due to the overall economics of production and delivery, we believe a practical refueling station should be designed to receive liquid. Systems studies confirm this assumption for stations fueling up to about 300 vehicles. Our fueling station, aimed at refueling fleet vehicles, will receive hydrogen as a liquid and dispense it as either liquid, high pressure gas, or low pressure gas. Thus, it can refuel any of the three types of tanks proposed for hydrogen-powered vehicles -- liquid, gaseous, or hydride. The paper discusses the fueling station design. Results of a numerical model of liquid hydrogen vehicle tank filling, with emphasis on no vent filling, are presented to illustrate the usefulness of the model as a design tool. Results of our vehicle performance model illustrate our thesis that it is too early to judge what the preferred method of on-board vehicle fuel storage will be in practice -- thus our decision to accommodate all three methods.

  7. Space Station Habitability Research

    Science.gov (United States)

    Clearwater, Yvonne A.

    1988-01-01

    The purpose and scope of the Habitability Research Group within the Space Human Factors Office at the NASA/Ames Research Center is described. Both near-term and long-term research objectives in the space human factors program pertaining to the U.S. manned Space Station are introduced. The concept of habitability and its relevancy to the U.S. space program is defined within a historical context. The relationship of habitability research to the optimization of environmental and operational determinants of productivity is discussed. Ongoing habitability research efforts pertaining to living and working on the Space Station are described.

  8. Implementation of Biogas Stations into Smart Heating and Cooling Network

    Science.gov (United States)

    Milčák, P.; Konvička, J.; Jasenská, M.

    2016-10-01

    The paper is aimed at the description of implementation of a biogas station into software environment for the "Smart Heating and Cooling Networks". The aim of this project is creation of a software tool for preparation of operation and optimization of treatment of heat/cool in small regions. In this case, the biogas station represents a kind of renewable energy source, which, however, has its own operational specifics which need to be taken into account at the creation of an implementation project. For a specific biogas station, a detailed computational model was elaborated, which is parameterized in particular for an optimization of the total computational time.

  9. The local impacts of nuclear stations

    International Nuclear Information System (INIS)

    Gammon, K.M.

    1981-01-01

    The paper looks at the various non-radiological impacts of nuclear power stations on the environment which are grouped as ecological, amenity and socio-economic effects. The study and assessment of environment impacts are explained and comparisons made between those from nuclear and coal fired power stations. The prediction of future effects and judgement of their significance is difficult but is helped by the procedures evolved and by knowledge from the construction and operation of a large number of projects in physically different locations. Research is also needed into new issues and this must be recognised early. From experience of a number of nuclear stations it appears that the local impacts are acceptable provided care is taken. (author)

  10. Cloud Compute for Global Climate Station Summaries

    Science.gov (United States)

    Baldwin, R.; May, B.; Cogbill, P.

    2017-12-01

    Global Climate Station Summaries are simple indicators of observational normals which include climatic data summarizations and frequency distributions. These typically are statistical analyses of station data over 5-, 10-, 20-, 30-year or longer time periods. The summaries are computed from the global surface hourly dataset. This dataset totaling over 500 gigabytes is comprised of 40 different types of weather observations with 20,000 stations worldwide. NCEI and the U.S. Navy developed these value added products in the form of hourly summaries from many of these observations. Enabling this compute functionality in the cloud is the focus of the project. An overview of approach and challenges associated with application transition to the cloud will be presented.

  11. The Dwarf Project: Vidojevica

    Science.gov (United States)

    Vince, O.

    2013-05-01

    The DWARF project is an important international project for observing eclipsing binary stars and searching for third companion which orbit around both stars. Recently, a group of researchers at the Astronomical Observatory of Belgrade joined this project using the 60 cm telescope at the Astronomical Station Vidojevica for observations. All the equipment and the human potential involved with this project from Serbia will be described in this paper.

  12. Power station instrumentation

    International Nuclear Information System (INIS)

    Jervis, M.W.

    1993-01-01

    Power stations are characterized by a wide variety of mechanical and electrical plant operating with structures, liquids and gases working at high pressures and temperatures and with large mass flows. The voltages and currents are also the highest that occur in most industries. In order to achieve maximum economy, the plant is operated with relatively small margins from conditions that can cause rapid plant damage, safety implications, and very high financial penalties. In common with other process industries, power stations depend heavily on control and instrumentation. These systems have become particularly significant, in the cost-conscious privatized environment, for providing the means to implement the automation implicit in maintaining safety standards, improving generation efficiency and reducing operating manpower costs. This book is for professional instrumentation engineers who need to known about their use in power stations and power station engineers requiring information about the principles and choice of instrumentation available. There are 8 chapters; chapter 4 on instrumentation for nuclear steam supply systems is indexed separately. (Author)

  13. Galileo Station Keeping Strategy

    Science.gov (United States)

    Perez-Cambriles, Antonio; Bejar-Romero, Juan Antonio; Aguilar-Taboada, Daniel; Perez-Lopez, Fernando; Navarro, Daniel

    2007-01-01

    This paper presents analyses done for the design and implementation of the Maneuver Planning software of the Galileo Flight Dynamics Facility. The station keeping requirements of the constellation have been analyzed in order to identify the key parameters to be taken into account in the design and implementation of the software.

  14. Designing a Weather Station

    Science.gov (United States)

    Roman, Harry T.

    2012-01-01

    The collection and analysis of weather data is crucial to the location of alternate energy systems like solar and wind. This article presents a design challenge that gives students a chance to design a weather station to collect data in advance of a large wind turbine installation. Data analysis is a crucial part of any science or engineering…

  15. Avoiding Service Station Fraud.

    Science.gov (United States)

    Burton, Grace M.; Burton, John R.

    1982-01-01

    High school students are warned against service station fraud. A problem-solving section is designed to help students calculate consumer costs for various fraudulent transactions. Several ways of reducing fraud or of lessening the chances of problems are noted. (MP)

  16. The Service Station.

    Science.gov (United States)

    Ohio State Univ., Columbus. Center for Vocational and Technical Education.

    The purpose of the teacher's guide is to encourage the primary student to expand his or her awareness of jobs within the community. The role of the service station worker is examined, with emphasis on the goods and services provided. Subject areas for which the materials in this guide have potential are social studies, art, and language. Each set…

  17. Electrostatic pickup station

    CERN Multimedia

    CERN PhotoLab

    1979-01-01

    Electrostatic pickup station, with 4 electrodes, to measure beam position in the horizontal and vertical plane. This type is used in the transfer lines leaving the PS (TT2, TTL2, TT70). See also 8206063, where the electrode shapes are clearly visible.

  18. Tedese Project

    Science.gov (United States)

    Buforn, E.; Davila, J. Martin; Bock, G.; Pazos, A.; Udias, A.; Hanka, W.

    The TEDESE (Terremotos y Deformacion Cortical en el Sur de España) project is a joint project of the Universidad Complutense de Madrid (UCM) and Real Instituto y Observatorio de la Armada de San Fernando, Cadiz (ROA) supported by the Spanish Ministerio de Ciencia y Tecnologia with the participation of the GeoforschungZen- trum, Potsdam (GFZ). The aim is to carry out a study of the characteristics of the oc- currence and mechanism of earthquakes together with measurements of crustal struc- ture and deformations in order to obtain an integrated evaluation of seismic risk in southern Spain from. As part of this project a temporal network of 10 broad-band seismological stations, which will complete those already existing in the zone, have been installed in southern Spain and northern Africa for one year beginning in October 2001. The objectives of the project are the study in detail of the focal mechanisms of earthquakes in this area, of structural in crust and upper mantle, of seismic anisotropy in crust and mantle as indicator for tectonic deformation processed and the measure- ments of crustal deformations using techniques with permanent GPS and SLR stations and temporary GPS surveys. From these studies, seismotectonic models and maps will be elaborated and seismic risk in the zone will be evaluated.

  19. TEPCO plans to construct Higashidori Nuclear Power Station

    International Nuclear Information System (INIS)

    Tsuruta, Atsushi

    2008-01-01

    In 2006, TEPCO submitted to the government plans for the construction of Higashidori Nuclear Power Station. The application was filed 41 years after the project approved by the Higashidori Village Assembly. This nuclear power station will be the first new nuclear power plant constructed by TEPCO since the construction of Units No.6 and 7 at the Kashiwazaki Kariwa Nuclear Power Station 18 years ago. Higashidori Nuclear Power Station is to be constructed at a completely new site, which will become the fourth TEPCO nuclear power station. Higashidori Nuclear Power Station Unit No.1 will be TEPCO's 18th nuclear reactor. Unit No.1 will be an advanced boiling water reactor (ABWR), a reactor-type with a proven track record. It will be TEPCO's third ABWR. Alongside incorporating the latest technology, in Higashidori Nuclear Power Station Unit No.1, the most important requirement is for TEPCO to reflect in the new unit information and experience acquired from the operation of other reactors (information and experience acquired through the experience of operating TEPCO's 17 units at Fukushima Daiichi Nuclear Power Station, Fukushima Daini Nuclear Power Station and Kashiwazaki Kashiwa Nuclear Power Station in addition to information on non-conformities at nuclear power stations in Japan and around the world). Higashidori Nuclear Power Station is located in Higashidori-Village (Aomori Prefecture) and the selected site includes a rich natural environment. From an environmental perspective, we will implement the construction with due consideration for the land and sea environment, aiming to ensure that the plant can co-exist with its natural surroundings. The construction plans are currently being reviewed by the Nuclear and Industrial Safety Agency. We are committed to making progress in the project for the start of construction and subsequent commercial operation. (author)

  20. Physical decommissioning of the Shippingport Atomic Power Station

    International Nuclear Information System (INIS)

    Crimi, F.P.

    1988-01-01

    The Shippingport Atomic Power Station consists of the nuclear steam supply system and associated radioactive waste processing systems, which are owned by the United States Department of Energy (USDOE), and the turbine-generator and balance of plant which is owned by the Duquesne Light Company. The station is located at Shippingport, Pennsylvania on seven acres of land leased by USDOE from the Duquesne Light Company. The Shippingport Station Decommissioning Project (SSDP) is being managed for the USDOE by the General Electric Company and its integated subcontractor, Morrison Knudsen-Ferguson (MK-F) Company. The objectives of the Shippingport Station Decommissioning Project (SSDP) are to: Demonstrate the safe and cost effective dismantlement of a large scale nuclear power plant; Provide useful data for future decommissioning projects

  1. Mobile environmental radiation monitoring station

    International Nuclear Information System (INIS)

    Assido, H.; Shemesh, Y.; Mazor, T.; Tal, N.; Barak, D.

    1997-01-01

    A mobile environmental radiation monitoring station has been developed and established for the Israeli Ministry of Environment. The radiation monitoring station is ready for immediate placing in any required location, or can be operated from a vehicle. The station collects data Tom the detector and transfers it via cellular communication network to a Computerized Control Center for data storage, processing, and display . The mobile station is fully controlled from the. Routinely, the mobile station responses to the data request accumulated since the last communication session. In case of fault or alarm condition in the mobile station, a local claim is activated and immediately initiates communication with the via cellular communication network. (authors)

  2. NASA space station automation: AI-based technology review. Executive summary

    Science.gov (United States)

    Firschein, O.; Georgeff, M. P.; Park, W.; Cheeseman, P. C.; Goldberg, J.; Neumann, P.; Kautz, W. H.; Levitt, K. N.; Rom, R. J.; Poggio, A. A.

    1985-01-01

    Research and Development projects in automation technology for the Space Station are described. Artificial Intelligence (AI) based technologies are planned to enhance crew safety through reduced need for EVA, increase crew productivity through the reduction of routine operations, increase space station autonomy, and augment space station capability through the use of teleoperation and robotics.

  3. Wolf Creek Generating Station containment model

    International Nuclear Information System (INIS)

    Nguyen, D.H.; Neises, G.J.; Howard, M.L.

    1995-01-01

    This paper presents a CONTEMPT-LT/28 containment model that has been developed by Wolf Creek Nuclear Operating Corporation (WCNOC) to predict containment pressure and temperature behavior during the postulated events at Wolf Creek Generating Station (WCGS). The model has been validated using data provided in the WCGS Updated Safety Analysis Report (USAR). CONTEMPT-LT/28 model has been used extensively at WCGS to support plant operations, and recently, to support its 4.5% thermal power uprate project

  4. The future of integrated coal gasification combined cycle power plants

    International Nuclear Information System (INIS)

    Mueller, R.; Termuehlen, H.

    1991-01-01

    This paper examines the future of integrated coal gasification combined cycle (IGCC) power plants as affected by various technical, economical and environmental trends in power generation. The topics of the paper include a description of natural gas-fired combined cycle power plants, IGCC plants, coal gasifier concepts, integration of gasifiers into combined cycle power plants, efficiency, environmental impacts, co-products of IGCC power plants, economics of IGCC power plants, and a review of IGCC power plant projects

  5. Battery charging stations

    Energy Technology Data Exchange (ETDEWEB)

    Bergey, M.

    1997-12-01

    This paper discusses the concept of battery charging stations (BCSs), designed to service rural owners of battery power sources. Many such power sources now are transported to urban areas for recharging. A BCS provides the opportunity to locate these facilities closer to the user, is often powered by renewable sources, or hybrid systems, takes advantage of economies of scale, and has the potential to provide lower cost of service, better service, and better cost recovery than other rural electrification programs. Typical systems discussed can service 200 to 1200 people, and consist of stations powered by photovoltaics, wind/PV, wind/diesel, or diesel only. Examples of installed systems are presented, followed by cost figures, economic analysis, and typical system design and performance numbers.

  6. The nuclear power station

    International Nuclear Information System (INIS)

    Plettner, B.

    1987-04-01

    The processes taking place in a nuclear power plant and the dangers arising from a nuclear power station are described. The means and methods of controlling, monitoring, and protecting the plant and things that can go wrong are presented. There is also a short discourse on the research carried out in the USA and Germany, aimed at assessing the risks of utilising nuclear energy by means of the incident tree analysis and probability calculations. (DG) [de

  7. Shippingport station communications program

    International Nuclear Information System (INIS)

    Stote, J.J.

    1988-01-01

    The author discusses how the communications program for the Shippingport Atomic Power Station has a long history. It can be traced as far back as 1953, when the U.S. Atomic Energy Commission (AEC) awarded a contract to Westinghouse Electric to design the nuclear portion of a power plant for electric utility use. During May of the next year, President Eisenhower initiated groundbreaking ceremonies for the construction of the commercial atomic power plant at Shippingport, Pennsylvania

  8. Refurbishment of Point Lepreau Generating Station

    International Nuclear Information System (INIS)

    Thompson, P.D.; Jaitly, R.; Ichiyen, N.; Petrilli, M.A.

    2004-01-01

    NB Power is planning to conduct an 18-month maintenance outage of the Point Lepreau Generating Station (PLGS) beginning in April 2008. The major activity would be the replacement of all 380 Fuel Channel and Calandria Tube Assemblies and the connecting feeder pipes. This activity is referred to as Retube. NB Power would also take advantage of this outage to conduct a number of repairs, replacements, inspections and upgrades (such as rewinding or replacing the generator, replacement of shutdown system trip computers, replacement of certain valves and expansion joints, inspection of systems not normally accessible, etc). These collective activities are referred to as Refurbishment. This would allow the station to operate for an additional 25 to 30 years. The scope of the project was determined from the outcome of a two-year study involving a detailed condition assessment of the station that examined issues relating to ageing and obsolescence. The majority of the plant components were found to be capable of supporting extended operation without needing replacement or changes. In addition to the condition assessment, a detailed review of Safety and Licensing issues associated with extended operation was performed. This included a review of known regulatory and safety issues, comparison of the station against current codes and standards, and comparison of the station against safety related modifications made to more recent CANDU 6 units. Benefit cost analyses (BCA) were performed to assist the utility in determining which changes were appropriate to include in the project scope. As a Probabilistic Safety Assessment (PSA) for PLGS did not exist at the time, a risk baseline for the station had to be determined for use in the BCA. Extensive dialogue with the Canadian Nuclear Safety Commission staff was also undertaken during this phase. A comprehensive Licensing Framework was produced upon which the CNSC provided feedback to NB Power. This feedback was important in terms of

  9. Emergency Medical Service (EMS) Stations

    Data.gov (United States)

    Kansas Data Access and Support Center — EMS Locations in Kansas The EMS stations dataset consists of any location where emergency medical services (EMS) personnel are stationed or based out of, or where...

  10. Weigh-in-Motion Stations

    Data.gov (United States)

    Department of Homeland Security — The data included in the GIS Traffic Stations Version database have been assimilated from station description files provided by FHWA for Weigh-in-Motion (WIM), and...

  11. Automatic Traffic Recorder (ATR) Stations

    Data.gov (United States)

    Department of Homeland Security — The data included in the GIS Traffic Stations Version database have been assimilated from station description files provided by FHWA for Weigh-in-Motion (WIM), and...

  12. Space Station fluid management logistics

    Science.gov (United States)

    Dominick, Sam M.

    1990-01-01

    Viewgraphs and discussion on space station fluid management logistics are presented. Topics covered include: fluid management logistics - issues for Space Station Freedom evolution; current fluid logistics approach; evolution of Space Station Freedom fluid resupply; launch vehicle evolution; ELV logistics system approach; logistics carrier configuration; expendable fluid/propellant carrier description; fluid carrier design concept; logistics carrier orbital operations; carrier operations at space station; summary/status of orbital fluid transfer techniques; Soviet progress tanker system; and Soviet propellant resupply system observations.

  13. Hyapproval : final handbook for approval of hydrogen refuelling stations

    NARCIS (Netherlands)

    Wurster, R.; Landinger, H.; Machens, C.; Allidières, L.; Molag, M.; Barron, J.; Reijalt, M.; Hill, H.J.

    2006-01-01

    HyApproval is an EC co-financed Specific Targeted Research Project (STREP) to develop a Handbook facilitating the approval of Hydrogen Refuelling Stations (HRS). The project, started in October 2005, will be performed over 24 months by a balanced partnership including 25 partners from industry, SMEs

  14. From city’s station to station city. An integrative spatial approach to the (redevelopment of station areas

    Directory of Open Access Journals (Sweden)

    Ana Luísa Martins da Conceição

    2014-12-01

    Full Text Available Since its origin, the railway station has had a complicated relationship with the city, demanding periodical updates, particularly regarding spatial issues. With the aim of improving the liveability of station areas, current redevelopment projects are reconceptualising them as balanced transport ‘nodes’ and ‘places’ in the city. However, the proposed spatial solutions do not fully support the sought after economic, social and environmental performances. These intentions continue to be predominantly bounded with the (abstract planological level, not finding appropriate translation at the (concrete spatial design level. Further, the interdisciplinary nature of the highly complex planning and design processes of station areas, which should contribute to enhance the performance of their spaces, reinforces constraints and relegates architecture to a marginal role in this quest. It is thus necessary to understand how architecture can contribute to the improvement of the spatial performance of contemporary stations areas, supporting their current reconceptualization. To gain this understanding, the research explored the factors which influence the spatial definition and performance of European High Speed Train station areas, using “design research” and “research by design”. Via a theoretical integrative framework, synthesized from knowledge developed by architecture and other sciences, case studies of ‘through’ stations were analysed and compared. Six cases, encapsulating the most recurrent relative positions of the railway (infrastructure and the station building towards the(ir direct built environment, were chosen out of a large sample. For each category (cases with railway tracks at (a ground level, (b elevated level and (c underground level, two cases, featuring an adapted station building and a newly built one, were studied. Their physical and functional characteristics were mapped at several scales and moments (in history, as

  15. Thermal management of space stations

    Institute of Scientific and Technical Information of China (English)

    2001-01-01

    Thermal management aims at making full use of energy resources available in the space station to reduce energy consumption, waste heat rejection and the weight of the station. It is an extension of the thermal control. This discussion introduces the concept and development of thermal management, presents the aspects of thermal management and further extends its application to subsystems of the space station.

  16. Air and radiation monitoring stations

    CERN Multimedia

    AUTHOR|(SzGeCERN)582709

    2015-01-01

    CERN has around 100 monitoring stations on and around its sites. New radiation measuring stations, capable of detecting even lower levels of radiation, were installed in 2014. Two members of HE-SEE group (Safety Engineering and Environment group) in front of one of the new monitoring stations.

  17. Wind-powered electrical systems : highway rest areas, weigh stations, and team section buildings.

    Science.gov (United States)

    2009-02-01

    This project considered the use of wind for providing electrical power at Illinois Department of Transportation : (IDOT) highway rest areas, weigh stations, and team section buildings. The goal of the project was to determine : the extent to which wi...

  18. The local economic and social effects of power station siting: anticipated, demonstrated and perceived

    International Nuclear Information System (INIS)

    Glasson, J.

    1980-01-01

    The paper discusses the economic and social effects of power station siting at a local level using material based on the interim research findings from a project commissioned by the Central Electricity Generating Board. The cases for and against power station development are outlined and a review of the actual economic and social effects is presented, drawn from a study of a conventional power station at Drax and a nuclear power station at Sizewell. (U.K.)

  19. Defense Base Realignment and Closure Budget Data for Naval Air Technical Training Center, Naval Air Station Pensacola, Florida

    National Research Council Canada - National Science Library

    Granetto, Paul

    1994-01-01

    .... This report provides the results of the audit of 19 projects, valued at $288.9 million, for the realignment of the Naval Air Technical Training Center from Naval Air Station Memphis, Tennessee, to Naval Air Station Pensacola, Florida...

  20. Performance Assessment of a Solar powered Air Quality and Weather Station Placed on a School Rooftop in Hong Kong

    Science.gov (United States)

    Summary of compact, roof version of a Village Green Project station installed on a secondary school rooftop in Hong Kong. Preliminary comparison of the station's data against nearby regulatory monitors are summarized.

  1. Safety Distances for hydrogen filling stations

    Energy Technology Data Exchange (ETDEWEB)

    Matthijsen, A. J. C. M.; Kooi, E. S.

    2005-07-01

    In the Netherlands there is a growing interest in using natural gas as a transport fuel. The most important drivers behind this development are formed by poor inner city air quality and the decision to close several LPG filling stations. Dwellings are not allowed within the safety distances of 45 or 110 meters from the tanker filling point of these LPG stations, depending on the capacity of the station. Another driver is global warming. We are carrying out a study on station supply, compression, storage and filling for natural gas stations, and a similar, simultaneous study on hydrogen as a followup to our risk analysis for the hydrogen filling station in Amsterdam. Here, three buses drive on hydrogen as part of the European CUTE project. Driving on natural gas is an important step in the transition to cars on hydrogen. This study was commissioned by the Dutch Ministry of Spatial Planning, Housing and the Environment to advise on external safety aspects of future hydrogen filling stations. According to Dutch law homes may not be built within an individual risk contour of 10-6 per year of a dangerous object, such as a plant with hazardous materials or a filling station. An individual risk contour of 10-6 is represented by a line around a dangerous object that connects locations with an individual risk level of 10-6 per year. An individual 'located' within this contour line has a chance of one per million per year or more to be killed as a result of an accident caused by this object. The longest distance between the object and such a contour is called a 'safety distance'. A study on safety distances is now in progress for different kinds of hydrogen filling stations (e. g. gaseous and liquid hydrogen) and for different capacities, such as big, medium and small stations. The focus is on different kinds of hydrogen production and the hydrogen supply of the filling station. To decide on the design and supply of the hydrogen station, we examined the

  2. Space station orbit maintenance

    Science.gov (United States)

    Kaplan, D. I.; Jones, R. M.

    1983-01-01

    The orbit maintenance problem is examined for two low-earth-orbiting space station concepts - the large, manned Space Operations Center (SOC) and the smaller, unmanned Science and Applications Space Platform (SASP). Atmospheric drag forces are calculated, and circular orbit altitudes are selected to assure a 90 day decay period in the event of catastrophic propulsion system failure. Several thrusting strategies for orbit maintenance are discussed. Various chemical and electric propulsion systems for orbit maintenance are compared on the basis of propellant resupply requirements, power requirements, Shuttle launch costs, and technology readiness.

  3. Capacity at Railway Stations

    DEFF Research Database (Denmark)

    Landex, Alex

    2011-01-01

    zone(s) the possible conflicts with other trains (also in the opposite direction) are taken into account leading to more trustworthy results. Although the UIC 406 methodology proposes that the railway network should be divided into line sections when trains turn around and when the train order...... is changed, this paper recommends that the railway lines are not always be divided. In case trains turn around on open (single track) line, the capacity consumption may be too low if a railway line is divided. The same can be the case if only few trains are overtaken at an overtaking station. For dead end...

  4. Submerged AUV Charging Station

    Science.gov (United States)

    Jones, Jack A.; Chao, Yi; Curtin, Thomas

    2014-01-01

    Autonomous Underwater Vehicles (AUVs) are becoming increasingly important for military surveillance and mine detection. Most AUVs are battery powered and have limited lifetimes of a few days to a few weeks. This greatly limits the distance that AUVs can travel underwater. Using a series of submerged AUV charging stations, AUVs could travel a limited distance to the next charging station, recharge its batteries, and continue to the next charging station, thus traveling great distances in a relatively short time, similar to the Old West “Pony Express.” One solution is to use temperature differences at various depths in the ocean to produce electricity, which is then stored in a submerged battery. It is preferred to have the upper buoy submerged a reasonable distance below the surface, so as not to be seen from above and not to be inadvertently destroyed by storms or ocean going vessels. In a previous invention, a phase change material (PCM) is melted (expanded) at warm temperatures, for example, 15 °C, and frozen (contracted) at cooler temperatures, for example, 8 °C. Tubes containing the PCM, which could be paraffin such as pentadecane, would be inserted into a container filled with hydraulic oil. When the PCM is melted (expanded), it pushes the oil out into a container that is pressurized to about 3,000 psi (approx equals 20.7 MPa). When a valve is opened, the high-pressure oil passes through a hydraulic motor, which turns a generator and charges a battery. The low-pressure oil is finally reabsorbed into the PCM canister when the PCM tubes are frozen (contracted). Some of the electricity produced could be used to control an external bladder or a motor to the tether line, such that depth cycling is continued for a very long period of time. Alternatively, after the electricity is generated by the hydraulic motor, the exiting low-pressure oil from the hydraulic motor could be vented directly to an external bladder on the AUV, such that filling of the bladder

  5. PlayStation purpura.

    Science.gov (United States)

    Robertson, Susan J; Leonard, Jane; Chamberlain, Alex J

    2010-08-01

    A 16-year-old boy presented with a number of asymptomatic pigmented macules on the volar aspect of his index fingers. Dermoscopy of each macule revealed a parallel ridge pattern of homogenous reddish-brown pigment. We propose that these lesions were induced by repetitive trauma from a Sony PlayStation 3 (Sony Corporation, Tokyo, Japan) vibration feedback controller. The lesions completely resolved following abstinence from gaming over a number of weeks. Although the parallel ridge pattern is typically the hallmark for early acral lentiginous melanoma, it may be observed in a limited number of benign entities, including subcorneal haematoma.

  6. Tether applications for space station

    Science.gov (United States)

    Nobles, W.

    1986-01-01

    A wide variety of space station applications for tethers were reviewed. Many will affect the operation of the station itself while others are in the category of research or scientific platforms. One of the most expensive aspects of operating the space station will be the continuing shuttle traffic to transport logistic supplies and payloads to the space station. If a means can be found to use tethers to improve the efficiency of that transportation operation, it will increase the operating efficiency of the system and reduce the overall cost of the space station. The concept studied consists of using a tether to lower the shuttle from the space station. This results in a transfer of angular momentum and energy from the orbiter to the space station. The consequences of this transfer is studied and how beneficial use can be made of it.

  7. Draper Station Analysis Tool

    Science.gov (United States)

    Bedrossian, Nazareth; Jang, Jiann-Woei; McCants, Edward; Omohundro, Zachary; Ring, Tom; Templeton, Jeremy; Zoss, Jeremy; Wallace, Jonathan; Ziegler, Philip

    2011-01-01

    Draper Station Analysis Tool (DSAT) is a computer program, built on commercially available software, for simulating and analyzing complex dynamic systems. Heretofore used in designing and verifying guidance, navigation, and control systems of the International Space Station, DSAT has a modular architecture that lends itself to modification for application to spacecraft or terrestrial systems. DSAT consists of user-interface, data-structures, simulation-generation, analysis, plotting, documentation, and help components. DSAT automates the construction of simulations and the process of analysis. DSAT provides a graphical user interface (GUI), plus a Web-enabled interface, similar to the GUI, that enables a remotely located user to gain access to the full capabilities of DSAT via the Internet and Webbrowser software. Data structures are used to define the GUI, the Web-enabled interface, simulations, and analyses. Three data structures define the type of analysis to be performed: closed-loop simulation, frequency response, and/or stability margins. DSAT can be executed on almost any workstation, desktop, or laptop computer. DSAT provides better than an order of magnitude improvement in cost, schedule, and risk assessment for simulation based design and verification of complex dynamic systems.

  8. Wind turbine power stations

    International Nuclear Information System (INIS)

    Anon.

    1992-11-01

    The Countryside Council for Wales (CCW's) policy on wind turbine power stations needs to be read in the context of CCW's document Energy:Policy and perspectives for the Welsh countryside. This identifies four levels of action aimed at reducing emission of gases which contribute towards the risk of global warming and gases which cause acid deposition. These are: the need for investment in energy efficiency; the need for investment in conventional power generation in order to meet the highest environmental standards; the need for investment in renewable energy; and the need to use land use transportation policies and decisions to ensure energy efficiency and energy conservation. CCW views wind turbine power stations, along with other renewable energy systems, within this framework. CCW's policy is to welcome the exploitation of renewable energy sources as an element in a complete and environmentally sensitive energy policy, subject to the Environmental Assessment of individual schemes and monitoring of the long-term impact of the various technologies involved. (Author)

  9. WABASH RIVER COAL GASIFICATION REPOWERING PROJECT

    Energy Technology Data Exchange (ETDEWEB)

    Unknown

    2000-09-01

    The close of 1999 marked the completion of the Demonstration Period of the Wabash River Coal Gasification Repowering Project. This Final Report summarizes the engineering and construction phases and details the learning experiences from the first four years of commercial operation that made up the Demonstration Period under Department of Energy (DOE) Cooperative Agreement DE-FC21-92MC29310. This 262 MWe project is a joint venture of Global Energy Inc. (Global acquired Destec Energy's gasification assets from Dynegy in 1999) and PSI Energy, a part of Cinergy Corp. The Joint Venture was formed to participate in the Department of Energy's Clean Coal Technology (CCT) program and to demonstrate coal gasification repowering of an existing generating unit impacted by the Clean Air Act Amendments. The participants jointly developed, separately designed, constructed, own, and are now operating an integrated coal gasification combined-cycle power plant, using Global Energy's E-Gas{trademark} technology (E-Gas{trademark} is the name given to the former Destec technology developed by Dow, Destec, and Dynegy). The E-Gas{trademark} process is integrated with a new General Electric 7FA combustion turbine generator and a heat recovery steam generator in the repowering of a 1950's-vintage Westinghouse steam turbine generator using some pre-existing coal handling facilities, interconnections, and other auxiliaries. The gasification facility utilizes local high sulfur coals (up to 5.9% sulfur) and produces synthetic gas (syngas), sulfur and slag by-products. The Project has the distinction of being the largest single train coal gasification combined-cycle plant in the Western Hemisphere and is the cleanest coal-fired plant of any type in the world. The Project was the first of the CCT integrated gasification combined-cycle (IGCC) projects to achieve commercial operation.

  10. Reload Startup Physics Tests for Tianwan Nuclear Power station

    International Nuclear Information System (INIS)

    Yang Xiaoqiang; Li Wenshuang; Li Youyi; Yao Jinguo; Li Zaipeng Jiangsu

    2010-01-01

    This paper briefly describes the test purposes, test items, test schedules and test equipment's for reload startup physics test's on Unit 1 and 2 of Tianwan Nuclear Power station. Then, an overview of the previous thrice tests and evaluations on the tests results are presented. In the end, the paper shows the development and work direction of optimization project for reload startup physics tests on Unit 1 and 2 of Tianwan Nuclear Power station. (Authors)

  11. Principle simulator for a PWR nuclear power station

    International Nuclear Information System (INIS)

    Wahlstroem, B.

    1975-05-01

    A report is given on a simulator developed for the training of operational and planning staff for the Lovisa nuclear power station in Finland. All main components of the power station are illustrated and trainees can operate the simulator in the power range 3-100 %. The model was originally developed for planning the control system of Lovisa I, for which reason the simulator project could be carried out on a relatively limited budget. (author)

  12. Station planning and design incorporating modern power system practice

    CERN Document Server

    Martin, PC

    1991-01-01

    The planning and design of new power stations can involve complex interaction between the many engineering disciplines involved as well as environmental, planning, economical, political and social pressures. This volume aims to provide a logical review of the procedures involved in power station development. The engineering aspects are outlined in detail, with examples, showing the basis of the relationships involved together with ""non-engineering"" factors so that the engineer can draw on the information provided for specific projects. The civil engineering and building of power stations are

  13. Buried waste integrated demonstration human engineered control station. Final report

    Energy Technology Data Exchange (ETDEWEB)

    1994-09-01

    This document describes the Human Engineered Control Station (HECS) project activities including the conceptual designs. The purpose of the HECS is to enhance the effectiveness and efficiency of remote retrieval by providing an integrated remote control station. The HECS integrates human capabilities, limitations, and expectations into the design to reduce the potential for human error, provides an easy system to learn and operate, provides an increased productivity, and reduces the ultimate investment in training. The overall HECS consists of the technology interface stations, supporting engineering aids, platform (trailer), communications network (broadband system), and collision avoidance system.

  14. Buried waste integrated demonstration human engineered control station. Final report

    International Nuclear Information System (INIS)

    1994-09-01

    This document describes the Human Engineered Control Station (HECS) project activities including the conceptual designs. The purpose of the HECS is to enhance the effectiveness and efficiency of remote retrieval by providing an integrated remote control station. The HECS integrates human capabilities, limitations, and expectations into the design to reduce the potential for human error, provides an easy system to learn and operate, provides an increased productivity, and reduces the ultimate investment in training. The overall HECS consists of the technology interface stations, supporting engineering aids, platform (trailer), communications network (broadband system), and collision avoidance system

  15. 1100 MW BWR power station

    International Nuclear Information System (INIS)

    Anon.

    1983-01-01

    Now, the start-up test of No. 2 plant in Fukushima No. 2 Nuclear Power Station is smoothly in progress, and the start of its commercial operation is scheduled at the beginning of 1984. Here, the main features of No. 2 plant including piping design are explained. For No. 2 plant, many improving measures were adopted as the base plant of the improvement and standardization project of the Ministry of International Trade and Industry, such as the adoption of Mark-2 improved PCV, the adoption of an intermediate loop in the auxiliary cooling system, one-body forging of the lower end cover of the reactor pressure vessel, the adoption of many curved pipes, the adoption of large one-body structural components in reactor recirculation system piping and so on, which are related to the reduction of radiation exposure and the improvement of plant reliability in operation and regular inspection. Also, in order to do general adjustment in the arrangement of equipment and piping and in route design, and to establish the rational construction work plan, model engineering was adopted. In No. 2 plant, a remote-controlled automatic and semiautomatic ultrasonic flaw detection system was adopted to reduce radiation exposure in in-service inspection. Automatic welding was adopted to improve the quality. (Kako, I.)

  16. Prefeasibility of the project for repowering the Nachi Cocom thermal station in Merida, Yucatan state; Prefactibilidad del proyecto de repotenciacion de la central termoelectrica de Nachi- Cocom, en Merida estado de Yucatan

    Energy Technology Data Exchange (ETDEWEB)

    Sanchez Perez, J.L. [Comision Federal de Electricidad (CFE) (Mexico)

    1995-12-31

    This paper presents an alternative to the solution of the more efficient use of energy and for the solution on environmental pollution at a reduced cost, satisfying the electric energy demand with additional capacity three times as much greater than the installed capacity and utilizing evaluation of projects techniques for the prefeasibility analysis of the project. The investment for this type of projects results are feasible and attractive because of the short amortization term. The summary of results is given in Table 4. [Espanol] El presenta trabajo da una alternativa de solucion al uso mas eficiente de la energia y solucion a los problemas de contaminacion ambiental a un costo reducido, satisfaciendo la demanda de energia electrica con capacidad adicional de tres veces mayor a la capacidad instalada. Empleando tecnicas de evaluacion de proyectos para analisis de la prefactibilidad del proyecto. La inversion para este tipo de proyectos resulta factible y atractiva por el corto tiempo de amortizacion. El resumen de los resultados se muestra en la tabla 4.

  17. Prefeasibility of the project for repowering the Nachi Cocom thermal station in Merida, Yucatan state; Prefactibilidad del proyecto de repotenciacion de la central termoelectrica de Nachi- Cocom, en Merida estado de Yucatan

    Energy Technology Data Exchange (ETDEWEB)

    Sanchez Perez, J L [Comision Federal de Electricidad (CFE) (Mexico)

    1996-12-31

    This paper presents an alternative to the solution of the more efficient use of energy and for the solution on environmental pollution at a reduced cost, satisfying the electric energy demand with additional capacity three times as much greater than the installed capacity and utilizing evaluation of projects techniques for the prefeasibility analysis of the project. The investment for this type of projects results are feasible and attractive because of the short amortization term. The summary of results is given in Table 4. [Espanol] El presenta trabajo da una alternativa de solucion al uso mas eficiente de la energia y solucion a los problemas de contaminacion ambiental a un costo reducido, satisfaciendo la demanda de energia electrica con capacidad adicional de tres veces mayor a la capacidad instalada. Empleando tecnicas de evaluacion de proyectos para analisis de la prefactibilidad del proyecto. La inversion para este tipo de proyectos resulta factible y atractiva por el corto tiempo de amortizacion. El resumen de los resultados se muestra en la tabla 4.

  18. Local control stations

    International Nuclear Information System (INIS)

    Brown, W.S.; Higgins, J.C.; Wachtel, J.A.

    1993-01-01

    This paper describes research concerning the effects of human engineering design at local control stations (i.e., operator interfaces located outside the control room) on human performance and plant safety. The research considered both multifunction panels (e.g. remote shutdown panels) as well as single-function interfaces (e.g., valves, breakers, gauges, etc.). Changes in performance shaping factors associated with variations in human engineering at LCSs were estimated based on expert opinion. By means of a scaling procedure, these estimates were used to modify the human error probabilities in a PRA model, which was then employed to generate estimates of plant risk and scoping-level value/impact ratios for various human engineering upgrades. Recent documentation of human engineering deficiencies at single-function LCSs was also reviewed, and an assessment of the current status of LCSs with respect to human engineering was conducted

  19. Innovative Railway Stations

    Science.gov (United States)

    Rzepnicka, Sylwia; Załuski, Daniel

    2017-10-01

    In relation to modern demographic trends, evolving technologies and environment-friendly solutions increases the potential of rail considered as sustainable form of public transport. Contemporary tendencies of designing railway stations in Europe are focused on lowering energy consumption and reducing carbon emission. The main goal of the designers is to create a friendly and intuitive space for its users and at the same time a building that uses renewable energy sources and minimizes negative impact on the environment by the increase of biologically active areas, reuse of rainwater and greywater, innovative heating and cooling solutions and reduction of energy losses. The optimisation of a life circle in railway architecture introduces new approach to passenger service. Examples mentioned in the content of this article help to synthesize changes in approach to the design within the context of sustainability.

  20. Bradwell Nuclear Power Station

    International Nuclear Information System (INIS)

    1987-01-01

    When built, the Magnox reactors were expected to have operating lifetimes of 20-25 years. In order to satisfy the licensing authorities of their continued safety, long term safety reviews (LTSRs) are being carried out as the reactors reach 20 years of operation. This is the Nuclear Installations Inspectorate's (NII) summary report on Bradwell nuclear power station. The objectives of the LTSR are stated. A description of the plant is followed by an explanation of the statutory position on licensing. The responsibilities of the Central Electricity Generating Board (CEGB) and the NII are defined. From the examination of the CEGB's LTSR it is concluded that this generally confirms the validity of the existing safety case for present operation. However, some recommendations are made as to work required for reactor operation up to 1992. A summary of the NII findings is presented. This includes the reactor pressure circuit integrity, effects of ageing and in-service wear and radiation doses. (U.K.)

  1. Practical design considerations for photovoltaic power station

    Science.gov (United States)

    Swanson, T. D.

    Aspects of photovoltaic (PV) technology are discussed along with generic PV design considerations, taking into account the resource sunlight, PV modules and their reliability, questions of PV system design, the support structure subsystem, and a power conditioning unit subsystem. A description is presented of two recent projects which demonstrate the translation of an idea into actual working PV systems. A privately financed project in Denton, Maryland, went on line in early December, 1982, and began providing power to the local utility grid. It represents the first intermediate size, grid-connected, privately financed power station in the U.S. Based on firm quotes, the actual cost of this system is about $13/W peak. The other project, called the PV Breeder, is an energy independent facility which utilizes solar power to make new solar cells. It is also the first large industrial structure completely powered by the sun.

  2. Integrated microfluidic probe station.

    Science.gov (United States)

    Perrault, C M; Qasaimeh, M A; Brastaviceanu, T; Anderson, K; Kabakibo, Y; Juncker, D

    2010-11-01

    The microfluidic probe (MFP) consists of a flat, blunt tip with two apertures for the injection and reaspiration of a microjet into a solution--thus hydrodynamically confining the microjet--and is operated atop an inverted microscope that enables live imaging. By scanning across a surface, the microjet can be used for surface processing with the capability of both depositing and removing material; as it operates under immersed conditions, sensitive biological materials and living cells can be processed. During scanning, the MFP is kept immobile and centered over the objective of the inverted microscope, a few micrometers above a substrate that is displaced by moving the microscope stage and that is flushed continuously with the microjet. For consistent and reproducible surface processing, the gap between the MFP and the substrate, the MFP's alignment, the scanning speed, the injection and aspiration flow rates, and the image capture need all to be controlled and synchronized. Here, we present an automated MFP station that integrates all of these functionalities and automates the key operational parameters. A custom software program is used to control an independent motorized Z stage for adjusting the gap, a motorized microscope stage for scanning the substrate, up to 16 syringe pumps for injecting and aspirating fluids, and an inverted fluorescence microscope equipped with a charge-coupled device camera. The parallelism between the MFP and the substrate is adjusted using manual goniometer at the beginning of the experiment. The alignment of the injection and aspiration apertures along the scanning axis is performed using a newly designed MFP screw holder. We illustrate the integrated MFP station by the programmed, automated patterning of fluorescently labeled biotin on a streptavidin-coated surface.

  3. Lunar base thermoelectric power station study

    Science.gov (United States)

    Determan, William; Frye, Patrick; Mondt, Jack; Fleurial, Jean-Pierre; Johnson, Ken; Stapfer, G.; Brooks, Michael D.; Heshmatpour, Ben

    2006-01-01

    Under NASA's Project Prometheus, the Nuclear Systems Program, the Jet Propulsion Laboratory, Pratt & Whitney Rocketdyne, and Teledyne Energy Systems have teamed with a number of universities, under the Segmented Thermoelectric Multicouple Converter (STMC) program, to develop the next generation of advanced thermoelectric converters for space reactor power systems. Work on the STMC converter assembly has progressed to the point where the lower temperature stage of the segmented multicouple converter assembly is ready for laboratory testing and the upper stage materials have been identified and their properties are being characterized. One aspect of the program involves mission application studies to help define the potential benefits from the use of these STMC technologies for designated NASA missions such as the lunar base power station where kilowatts of power are required to maintain a permanent manned presence on the surface of the moon. A modular 50 kWe thermoelectric power station concept was developed to address a specific set of requirements developed for this mission. Previous lunar lander concepts had proposed the use of lunar regolith as in-situ radiation shielding material for a reactor power station with a one kilometer exclusion zone radius to minimize astronaut radiation dose rate levels. In the present concept, we will examine the benefits and requirements for a hermetically-sealed reactor thermoelectric power station module suspended within a man-made lunar surface cavity. The concept appears to maximize the shielding capabilities of the lunar regolith while minimizing its handling requirements. Both thermal and nuclear radiation levels from operation of the station, at its 100-m exclusion zone radius, were evaluated and found to be acceptable. Site preparation activities are reviewed and well as transport issues for this concept. The goal of the study was to review the entire life cycle of the unit to assess its technical problems and technology

  4. Discharges from nuclear power stations

    International Nuclear Information System (INIS)

    1991-02-01

    HM Inspectorate of Pollution commissioned, with authorising responsibilities in England and Wales, a study into the discharges of radioactive effluents from Nuclear Power Stations. The study considered arisings from nuclear power stations in Europe and the USA and the technologies to treat and control the radioactive discharges. This report contains details of the technologies used at many nuclear power stations to treat and control radioactive discharges and gives, where information was available, details of discharges and authorised discharge limits. (author)

  5. Space Station Engineering Design Issues

    Science.gov (United States)

    Mcruer, Duane T.; Boehm, Barry W.; Debra, Daniel B.; Green, C. Cordell; Henry, Richard C.; Maycock, Paul D.; Mcelroy, John H.; Pierce, Chester M.; Stafford, Thomas P.; Young, Laurence R.

    1989-01-01

    Space Station Freedom topics addressed include: general design issues; issues related to utilization and operations; issues related to systems requirements and design; and management issues relevant to design.

  6. Photochemical Assessment Monitoring Stations (PAMS)

    Data.gov (United States)

    U.S. Environmental Protection Agency — Photochemical Assessment Monitoring Stations (PAMS). This file provides information on the numbers and distribution (latitude/longitude) of air monitoring sites...

  7. Proposed Darlington generating station

    International Nuclear Information System (INIS)

    1975-05-01

    The proposed Darlington GS A project, consisting of four 850 MW CANDU-type reactors, is described. Construction and operation will cause environmental changes with regard to air, water, aquatic life, the site area, safety and noise, and the predicted changes are described. (E.C.B.)

  8. Station History Of The Seismic Station In Ahmadu Bello University ...

    African Journals Online (AJOL)

    Dominants in the selected events are events from Meditterranian, East Kazakhstan, India/Burma/China, South and Central America and North Ascension island regions. The limited number of events reporting at the station was due to low operational gain at the station which permitted only events whose magnitudes are ...

  9. Reducing lighting electricity use in underground metro stations

    International Nuclear Information System (INIS)

    Casals, Miquel; Gangolells, Marta; Forcada, Núria; Macarulla, Marcel

    2016-01-01

    Highlights: • Lighting systems are big energy consumers in underground metro stations. • An adaptive lighting system strategy is developed for underground stations. • Dimming controls are based on station occupancy levels and maintenance cycles. • The k-means clustering technique is used to identify stations’ occupancy patterns. • Savings were found to amount to 255.47 MW h in 2 years for a case study metro network. - Abstract: Lighting systems are usually one of the largest electrical end-uses in underground metro stations. Taking into account that budget restrictions in publicly owned companies hinder energy efficiency retrofit projects that require high initial investments, affordable energy saving strategies are needed. This paper presents a low-cost approach for reducing lighting electricity use in underground stations, without affecting passengers’ comfort or the metro operator’s service. For this purpose, an adaptive lighting strategy of dimming the illuminance levels of artificial light sources has been developed. Dimming controls are based on the occupancy of the station, and the preventive maintenance and cleaning cycles of the luminaires. The stations’ monthly occupancy patterns are defined through the k-means clustering technique. To illustrate its effectiveness, the method was applied to 115 underground stations of the Barcelona metro network. The results revealed overall electricity savings of 255.47 MW h on a biannual basis, which represents 36.22% of the stations’ baseline lighting consumption. Individual energy savings were found to range from 25 to 87.5 MW h/year in the stations of the Barcelona metro network, depending on the number and profile of station users. The research findings will undoubtedly be useful for the future energy efficiency project plans of worldwide metro operators and managers of other underground spaces.

  10. Solar-Assisted Electric Vehicle Charging Station Interim Report

    Energy Technology Data Exchange (ETDEWEB)

    Lapsa, Melissa Voss [ORNL; Durfee, Norman [ORNL; Maxey, L Curt [ORNL; Overbey, Randall M [ORNL

    2011-09-01

    Oak Ridge National Laboratory (ORNL) has been awarded $6.8 million in the Department of Energy (DOE) American Recovery and Reinvestment Act (ARRA) funds as part of an overall $114.8 million ECOtality grant with matching funds from regional partners to install 125 solar-assisted Electric Vehicle (EV) charging stations across Knoxville, Nashville, Chattanooga, and Memphis. Significant progress has been made toward completing the scope with the installation of 25 solar-assisted charging stations at ORNL; six stations at Electric Power Research Institute (EPRI); and 27 stations at Nissan's Smyrna and Franklin sites, with three more stations under construction at Nissan's new lithium-ion battery plant. Additionally, the procurement process for contracting the installation of 34 stations at Knoxville, the University of Tennessee Knoxville (UTK), and Nashville sites is underway with completion of installation scheduled for early 2012. Progress is also being made on finalizing sites and beginning installations of 30 stations in Nashville, Chattanooga, and Memphis by EPRI and Tennessee Valley Authority (TVA). The solar-assisted EV charging station project has made great strides in fiscal year 2011. A total of 58 solar-assisted EV parking spaces have been commissioned in East and Middle Tennessee, and progress on installing the remaining 67 spaces is well underway. The contract for the 34 stations planned for Knoxville, UTK, and Nashville should be underway in October with completion scheduled for the end of March 2012; the remaining three Nissan stations are under construction and scheduled to be complete in November; and the EPRI/TVA stations for Chattanooga, Vanderbilt, and Memphis are underway and should be complete by the end of March 2012. As additional Nissan LEAFs are being delivered, usage of the charging stations has increased substantially. The project is on course to complete all 125 solar-assisted EV charging stations in time to collect meaningful data

  11. High Temperature Syngas Cleanup Technology Scale-up and Demonstration Project

    Energy Technology Data Exchange (ETDEWEB)

    Gardner, Ben [Research Triangle Inst. (RTI), Research Triangle Park, NC (United States); Turk, Brian [Research Triangle Inst. (RTI), Research Triangle Park, NC (United States); Denton, David [Research Triangle Inst. (RTI), Research Triangle Park, NC (United States); Gupta, Raghubir [Research Triangle Inst. (RTI), Research Triangle Park, NC (United States)

    2015-09-30

    Gasification is a technology for clean energy conversion of diverse feedstocks into a wide variety of useful products such as chemicals, fertilizers, fuels, electric power, and hydrogen. Existing technologies can be employed to clean the syngas from gasification processes to meet the demands of such applications, but they are expensive to build and operate and consume a significant fraction of overall parasitic energy requirements, thus lowering overall process efficiency. RTI International has developed a warm syngas desulfurization process (WDP) utilizing a transport-bed reactor design and a proprietary attrition-resistant, high-capacity solid sorbent with excellent performance replicated at lab, bench, and pilot scales. Results indicated that WDP technology can improve both efficiency and cost of gasification plants. The WDP technology achieved ~99.9% removal of total sulfur (as either H2S or COS) from coal-derived syngas at temperatures as high as 600°C and over a wide range of pressures (20-80 bar, pressure independent performance) and sulfur concentrations. Based on the success of these tests, RTI negotiated a cooperative agreement with the U.S. Department of Energy for precommercial testing of this technology at Tampa Electric Company’s Polk Power Station IGCC facility in Tampa, Florida. The project scope also included a sweet water-gas-shift process for hydrogen enrichment and an activated amine process for 90+% total carbon capture. Because the activated amine process provides some additional non-selective sulfur removal, the integration of these processes was expected to reduce overall sulfur in the syngas to sub-ppmv concentrations, suitable for most syngas applications. The overall objective of this project was to mitigate the technical risks associated with the scale up and integration of the WDP and carbon dioxide capture technologies, enabling subsequent commercial-scale demonstration. The warm syngas cleanup pre-commercial test unit

  12. International Space Station Configuration Analysis and Integration

    Science.gov (United States)

    Anchondo, Rebekah

    2016-01-01

    Ambitious engineering projects, such as NASA's International Space Station (ISS), require dependable modeling, analysis, visualization, and robotics to ensure that complex mission strategies are carried out cost effectively, sustainably, and safely. Learn how Booz Allen Hamilton's Modeling, Analysis, Visualization, and Robotics Integration Center (MAVRIC) team performs engineering analysis of the ISS Configuration based primarily on the use of 3D CAD models. To support mission planning and execution, the team tracks the configuration of ISS and maintains configuration requirements to ensure operational goals are met. The MAVRIC team performs multi-disciplinary integration and trade studies to ensure future configurations meet stakeholder needs.

  13. Thermal battery automated assembly station conceptual design

    Energy Technology Data Exchange (ETDEWEB)

    Jacobs, D

    1988-08-01

    Thermal battery assembly involves many operations which are labor- intense. In August 1986, a project team was formed at GE Neutron Devices to investigate and evaluate more efficient and productive battery assembly techniques through the use of automation. The result of this study was the acceptance of a plan to automate the piece part pellet fabrication and battery stacking operations by using computerized pellet presses and robots which would be integrated by a main computer. This report details the conceptual design and development plan to be followed in the fabrication, development, and implementation of a thermal battery automated assembly station. 4 figs., 8 tabs.

  14. Shippingport: A relevant decommissioning project

    International Nuclear Information System (INIS)

    Crimi, F.P.

    1988-01-01

    Because of Shippingport's low electrical power rating (72 MWe), there has been some misunderstanding on the relevancy of the Shippingport Station Decommissioning Project (SSDP) to a modern 1175 MWe commercial pressurized water reactor (PWR) power station. This paper provides a comparison of the major components of the reactor plant of the 72 MWe Shippingport Atomic Power Station and an 1175 MWe nuclear plant and the relevancy of the Shippingport decommissioning as a demonstration project for the nuclear industry. For the purpose of this comparison, Portland General Electric Company's 1175 MWe Trojan Nuclear Plant at Rainier, Oregon, has been used as the reference nuclear power plant. 2 refs., 2 figs., 1 tab

  15. Islands for nuclear power stations

    International Nuclear Information System (INIS)

    Usher, E.F.F.W.; Fraser, A.P.

    1981-01-01

    The safety principles, design criteria and types of artificial island for an offshore nuclear power station are discussed with particular reference to siting adjacent to an industrial island. The paper concludes that the engineering problems are soluble and that offshore nuclear power stations will eventually be built but that much fundamental work is still required. (author)

  16. RF-Station control crate

    International Nuclear Information System (INIS)

    Beuzekom, M.G. van; Es, J.T. van.

    1992-01-01

    This report gives a description of the electronic control-system for the RF-station of AmPS. The electronics form the connection between the computer-system and the hardware of the RF-station. Only the elements of the systems which are not described in the other NIKHEF-reports are here discussed in detail. (author). 7 figs

  17. Balloon launching station, Mildura, Victoria

    International Nuclear Information System (INIS)

    The Mildura Balloon Launching Station was established in 1960 by the Department of Supply (now the Department of Manufacturing Industry) on behalf of the United States Atomic Energy Commission (USAEC) to determine the content of radioactive material in the upper atmosphere over Australia. The Station location and layout, staffing, balloon launching equipment, launching, tracking and recovery are described. (R.L.)

  18. The SNS target station preliminary Title I shielding analyses

    International Nuclear Information System (INIS)

    Johnson, J.O.; Santoro, R.T.; Lillie, R.A.; Barnes, J.M.; McNeilly, G.S.

    2000-01-01

    The Department of Energy (DOE) has given the Spallation Neutron Source (SNS) project approval to begin Title I design of the proposed facility to be built at Oak Ridge National Laboratory (ORNL). During the conceptual design phase of the SNS project, the target station bulk-biological shield was characterized and the activation of the major targets station components was calculated. Shielding requirements were assessed with respect to weight, space, and dose-rate constraints for operating, shut-down, and accident conditions utilizing the SNS shield design criteria, DOE Order 5480.25, and requirements specified in 10 CFR 835. Since completion of the conceptual design phase, there have been major design changes to the target station as a result of the initial shielding and activation analyses, modifications brought about due to engineering concerns, and feedback from numerous external review committees. These design changes have impacted the results of the conceptual design analyses, and consequently, have required a re-investigation of the new design. Furthermore, the conceptual design shielding analysis did not address many of the details associated with the engineering design of the target station. In this paper, some of the proposed SNS target station preliminary Title I shielding design analyses will be presented. The SNS facility (with emphasis on the target station), shielding design requirements, calculational strategy, and source terms used in the analyses will be described. Preliminary results and conclusions, along with recommendations for additional analyses, will also be presented. (author)

  19. Shippingport: Overall project progress

    International Nuclear Information System (INIS)

    Crimi, F.P.

    1989-01-01

    The Shippingport atomic power station (SAPS) consisted of the nuclear steam supply system and associated radioactive waste processing systems, which were owned by the US Department of Energy (DOE), and the balance of plant, owned by the Duquesne Light Company. The station is located at Shippingport, Pennsylvania, on 7 acres of land leased by DOE from Duquesne Light Company. The Shippingport Station Decommissioning Project (SSDP) is being performed under contract to the DOE by the General Electric Company (GE) and its preselected subcontractor, MK-Ferguson Company, as the decommissioning operations contractor (DOC). This paper describes the decommissioning work that has been accomplished since July 1988, and the project's cost and schedule status. As the first decommissioning of a commercial, full-scale nuclear power plant, the SSDP is expected to set the standards for the demolition of future nuclear power plants

  20. Seismometer array station processors

    International Nuclear Information System (INIS)

    Key, F.A.; Lea, T.G.; Douglas, A.

    1977-01-01

    A description is given of the design, construction and initial testing of two types of Seismometer Array Station Processor (SASP), one to work with data stored on magnetic tape in analogue form, the other with data in digital form. The purpose of a SASP is to detect the short period P waves recorded by a UK-type array of 20 seismometers and to edit these on to a a digital library tape or disc. The edited data are then processed to obtain a rough location for the source and to produce seismograms (after optimum processing) for analysis by a seismologist. SASPs are an important component in the scheme for monitoring underground explosions advocated by the UK in the Conference of the Committee on Disarmament. With digital input a SASP can operate at 30 times real time using a linear detection process and at 20 times real time using the log detector of Weichert. Although the log detector is slower, it has the advantage over the linear detector that signals with lower signal-to-noise ratio can be detected and spurious large amplitudes are less likely to produce a detection. It is recommended, therefore, that where possible array data should be recorded in digital form for input to a SASP and that the log detector of Weichert be used. Trial runs show that a SASP is capable of detecting signals down to signal-to-noise ratios of about two with very few false detections, and at mid-continental array sites it should be capable of detecting most, if not all, the signals with magnitude above msub(b) 4.5; the UK argues that, given a suitable network, it is realistic to hope that sources of this magnitude and above can be detected and identified by seismological means alone. (author)

  1. A Management Tool for Improvement (Improving) IMS Stations Performance

    International Nuclear Information System (INIS)

    Mohammad, D.; Pantin, A.; Quintana, E.

    2011-01-01

    IMS-Maintenance is a software under development by the personnel of ARN-CTBT office, intended for the technical management of IMS stations under ARN's responsibility. This software integrates the whole control of the equipment in an IMS station, including the management of consumables used in daily or periodic operation. It permits an easy retrieval (access) of the technical features, suppliers, etc. of each item of the equipment, as well as its maintenance history and scheduled task. Although this project is still in a starting phase, a preliminary version of this software is being used in radionuclide station RN01 (Buenos Aires), having already demonstrated its usefulness and potential for the improvement of IMS station management. (authors)

  2. Space Station Environmental Health System water quality monitoring

    Science.gov (United States)

    Vincze, Johanna E.; Sauer, Richard L.

    1990-01-01

    One of the unique aspects of the Space Station is that it will be a totally encapsulated environment and the air and water supplies will be reclaimed for reuse. The Environmental Health System, a subsystem of CHeCS (Crew Health Care System), must monitor the air and water on board the Space Station Freedom to verify that the quality is adequate for crew safety. Specifically, the Water Quality Subsystem will analyze the potable and hygiene water supplies regularly for organic, inorganic, particulate, and microbial contamination. The equipment selected to perform these analyses will be commercially available instruments which will be converted for use on board the Space Station Freedom. Therefore, the commercial hardware will be analyzed to identify the gravity dependent functions and modified to eliminate them. The selection, analysis, and conversion of the off-the-shelf equipment for monitoring the Space Station reclaimed water creates a challenging project for the Water Quality engineers and scientists.

  3. Project LASER

    Science.gov (United States)

    1990-01-01

    NASA formally launched Project LASER (Learning About Science, Engineering and Research) in March 1990, a program designed to help teachers improve science and mathematics education and to provide 'hands on' experiences. It featured the first LASER Mobile Teacher Resource Center (MTRC), is designed to reach educators all over the nation. NASA hopes to operate several MTRCs with funds provided by private industry. The mobile unit is a 22-ton tractor-trailer stocked with NASA educational publications and outfitted with six work stations. Each work station, which can accommodate two teachers at a time, has a computer providing access to NASA Spacelink. Each also has video recorders and photocopy/photographic equipment for the teacher's use. MTRC is only one of the five major elements within LASER. The others are: a Space Technology Course, to promote integration of space science studies with traditional courses; the Volunteer Databank, in which NASA employees are encouraged to volunteer as tutors, instructors, etc; Mobile Discovery Laboratories that will carry simple laboratory equipment and computers to provide hands-on activities for students and demonstrations of classroom activities for teachers; and the Public Library Science Program which will present library based science and math programs.

  4. Ensuring effective project management

    International Nuclear Information System (INIS)

    Ward, J.N.

    1980-01-01

    A brief description is given of the organisation methods employed by the Bechtel Power Corporation, in their contract with Mississippi Power and Light Company for the design, construction and procurement activities for the Grand Gulf Nuclear Station. The aim is to ensure effective management, and good communications at all stages of construction, between the project team and the client. (U.K.)

  5. The Trencin water power station

    International Nuclear Information System (INIS)

    2005-01-01

    This leaflet describes the Trencin water power station. The Trencin water power station was built seven years after the Dubnica nad Vahom water power station started its operation and was the last stage of the first and the oldest derived cascade of water power stations on the Vah River. After completing water power stations at Ladce (1936), Ilava (1946) and Dubnica nad Vahom (1949) and before constructing the Trencin water power station, the whole second derived cascade of water power stations including water power stations at Kostolna, Nove Mesto nad Vahom and Horna Streda was built as soon as possible mainly because the need to get compensation for discontinued electricity supplies as well as energetic coal from the Czech Republic. Hereby, experiences from the construction of previous grades were used, mainly as far as the dimensioning was concerned, as the fi rst installed power stations had, in comparison with the growing requirements on the electricity supplies, very low absorption capacity - only 150 m 3 .s -1 . Thus the Trencin power station (original name was the Skalka power station) was already dimensioned for the same absorption capacity as the cascade located downstream the river, that is 180 m 3 .s -1 . That was related also to growing demands on electricity supplies during the peaks in the daily electric system load diagram, and thus to the transfer from continuous operation of the water power station to semi-peak or even peak performance. According to the standards of power station classification, the Trencin water power station is a medium size, low pressure, channel power station with two units equipped by Kaplan turbines and synchronous hydro-alternators. The water power station installed capacity is 16.1 MW in total and its designed annual production of electrical energy for medium water year is 85,000 MWh, while the average annual production during the last 30 years is 86,252 MWh. Installed unit has a four-blade Kaplan turbine with the diameter

  6. Space station propulsion requirements study

    Science.gov (United States)

    Wilkinson, C. L.; Brennan, S. M.

    1985-01-01

    Propulsion system requirements to support Low Earth Orbit (LEO) manned space station development and evolution over a wide range of potential capabilities and for a variety of STS servicing and space station operating strategies are described. The term space station and the overall space station configuration refers, for the purpose of this report, to a group of potential LEO spacecraft that support the overall space station mission. The group consisted of the central space station at 28.5 deg or 90 deg inclinations, unmanned free-flying spacecraft that are both tethered and untethered, a short-range servicing vehicle, and a longer range servicing vehicle capable of GEO payload transfer. The time phasing for preferred propulsion technology approaches is also investigated, as well as the high-leverage, state-of-the-art advancements needed, and the qualitative and quantitative benefits of these advancements on STS/space station operations. The time frame of propulsion technologies applicable to this study is the early 1990's to approximately the year 2000.

  7. Scheduling for decommissioning projects

    International Nuclear Information System (INIS)

    Podmajersky, O.E.

    1987-01-01

    This paper describes the Project Scheduling system being employed by the Decommissioning Operations Contractor at the Shippingport Station Decommissioning Project (SSDP). Results from the planning system show that the project continues to achieve its cost and schedule goals. An integrated cost and schedule control system (C/SCS) which uses the concept of earned value for measurement of performance was instituted in accordance with DOE orders. The schedule and cost variances generated by the C/SCS system are used to confirm management's assessment of project status. This paper describes the types of schedules and tools used on the SSDP project to plan and monitor the work, and identifies factors that are unique to a decommissioning project that make scheduling critical to the achievement of the project's goals. 1 fig

  8. 47 CFR 97.109 - Station control.

    Science.gov (United States)

    2010-10-01

    ... 47 Telecommunication 5 2010-10-01 2010-10-01 false Station control. 97.109 Section 97.109... SERVICE Station Operation Standards § 97.109 Station control. (a) Each amateur station must have at least one control point. (b) When a station is being locally controlled, the control operator must be at the...

  9. EUROTRAC projects

    International Nuclear Information System (INIS)

    Slanina, J.; Arends, B.G.; Wyers, G.P.

    1992-07-01

    The projects discussed are BIATEX (BIosphere-ATmosphere EXchange of pollutants), ACE (Acidity in Clouds Experiment) and GCE (Ground-based Cloud Experiment). ECN also coordinates BIATEX and contributes to the coordination of EUROTRAC. Research in BIATEX is aimed at the development of equipment, by which atmosphere-surface interactions of air pollution can be quantified. A ion chromatograph, connected to a rotating denuder, is developed to be applicated in the field for on-line analysis of denuder extracts and other samples. To investigate dry deposition of ammonia a continuous-flow denuder has been developed. A thermodenuder system to measure the concentrations of HNO 3 and NH 4 NO 3 in the ambient air is optimized to determine depositions and is part of the ECN monitoring station in Zegveld, Netherlands. An aerosol separation technique, based on a cyclone separator, has also been developed. All this equipment has been used in field experiments above wheat and heather. An automated monitoring station for long-term investigations of NH 3 , HNO 3 and SO 2 dry deposition on grassland and the impact of the deposition on the presence and composition of water films has been set up and fully tested. Research in GCE concerns the uptake and conversion of air pollution in clouds (cloud chemistry). Measuring equipment from several collaborative institutes has been specified and calibrated in a cloud chamber at ECN. The ECN contribution is the determination of the gas phase composition and the micro-physical characterization of the clouds. Measurement campaigns were carried out in the Po area (Italy) in fog, and in Kleiner Feldberg near Frankfurt, Germany, in orographic clouds. Estimations are given of the deposition of fog water and cloud water on forests in the Netherlands and the low mountain range in Germany. The project ACE was not started because of financial reasons and will be reconsidered. 26 figs., 1 tab., 3 apps., 34 refs

  10. Biotechnology opportunities on Space Station

    Science.gov (United States)

    Deming, Jess; Henderson, Keith; Phillips, Robert W.; Dickey, Bernistine; Grounds, Phyllis

    1987-01-01

    Biotechnology applications which could be implemented on the Space Station are examined. The advances possible in biotechnology due to the favorable microgravity environment are discussed. The objectives of the Space Station Life Sciences Program are: (1) the study of human diseases, (2) biopolymer processing, and (3) the development of cryoprocessing and cryopreservation methods. The use of the microgravity environment for crystal growth, cell culturing, and the separation of biological materials is considered. The proposed Space Station research could provide benefits to the fields of medicine, pharmaceuticals, genetics, agriculture, and industrial waste management.

  11. Space Station Freedom food management

    Science.gov (United States)

    Whitehurst, Troy N., Jr.; Bourland, Charles T.

    1992-01-01

    This paper summarizes the specification requirements for the Space Station Food System, and describes the system that is being designed and developed to meet those requirements. Space Station Freedom will provide a mix of frozen, refrigerated, rehydratable, and shelf stable foods. The crew will pre-select preferred foods from an approved list, to the extent that proper nutrition balance is maintained. A galley with freezers, refrigerators, trash compactor, and combination microwave and convection ovens will improve crew efficiency and productivity during the long Space Station Freedom (SSF) missions.

  12. Torness: proposed nuclear power station

    International Nuclear Information System (INIS)

    Anon.

    1979-01-01

    The need for and desirability of nuclear power, and in particular the proposed nuclear power station at Torness in Scotland, are questioned. Questions are asked, and answered, on the following topics: position, appearance and cost of the proposed Torness plant, and whether necessary; present availability of electricity, and forecast of future needs, in Scotland; energy conservation and alternative energy sources; radiation hazards from nuclear power stations (outside, inside, and in case of an accident); transport of spent fuel from Torness to Windscale; radioactive waste management; possibility of terrorists making a bomb with radioactive fuel from a nuclear power station; cost of electricity from nuclear power; how to stop Torness. (U.K.)

  13. Fuel efficiency, availability and compressor station configuration

    Energy Technology Data Exchange (ETDEWEB)

    Lubomirsky, Matt; Kurz, Rainer [Solar Turbines Inc., San Diego, CA (United States); Klimov, Pavel [Intergas Central Asia, Astana (Kazakhstan)

    2009-12-19

    Compressor stations play a very important role in the success of a gas pipeline design and a careful selection of centrifugal compressors and drivers are key aspects for the success of the project. The state of the art design available today for this equipment provides overall high thermodynamic performance and consequently minimizes installed power requirements and energy usage with significant savings on operating expenses during the economic life of the project For any application of machinery in a pipeline compression station, one of the key questions to answer is the number of units to install to meet the flow requirements of the pipeline. Depending on the load profile of the pipeline, the answers may look different. Other factors to consider include the fact that gas turbines can produce a significant amount of additional power at lower ambient temperatures. So, even for constant load of the pipeline, the relative load of the driver changes. In this paper, a typical transcontinental pipeline with multiple compressor stations is evaluated. The determination of the exact hydraulic behavior of the pipeline is part of the modeling effort. The site ambient conditions, with a significant swing in ambient temperatures are considered. The issue discussed in this paper evolves around the availability that can be achieved with various configurations, based on actually achieved reliability and availability numbers. The other large impact on operating costs, fuel consumption will be discussed. Here, the choice of the number of installed units has a distinct impact on annual fuel consumption, as well as the capacity of the pipeline during various scenarios. (author)

  14. Aseismic design of the Heysham II Nuclear Power Station

    International Nuclear Information System (INIS)

    Day, J.W.

    1983-01-01

    A brief description of the seismic criteria established for use with the Steam Generating Heavy Water Reactor (SCHWR) and taken for the Heysham II Project is given. The qualification strategy adopted for Heysham II is described, and a brief overview is given of some of the more important design changes required for seismic purposes on that station

  15. Sizewell 'B' power station public inquiry: CEGB proof of evidence

    International Nuclear Information System (INIS)

    McFarlane, J.D.

    1982-11-01

    The NNC construction programme for the Sizewell B nuclear power station is outlined. The following topics are considered: constructability aspects of the Sizewell B design; overall project programme and organization; NNC target construction programme; construction planning; material quantities and installation rates; site construction manpowers; construction contracting policy; site industrial relations and productivity; site management. (U.K.)

  16. Double-Station Automatic Video Observation of the Meteors

    Czech Academy of Sciences Publication Activity Database

    Vítek, S.; Koten, Pavel; Páta, P.; Fliegel, K.

    2010-01-01

    Roč. 2010, - (2010), 943145/1-943145/4 ISSN 1687-7969 R&D Projects: GA ČR GA205/09/1302 Grant - others:GA ČR(CZ) GA102/09/0997 Institutional research plan: CEZ:AV0Z10030501 Keywords : double station observation * video technique Subject RIV: BN - Astronomy, Celestial Mechanics, Astrophysics

  17. Inauguration of the ANDRA atmospheric station in Houdelaincourt; Inauguration de la station atmospherique de l'Andra a Houdelaincourt

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2011-07-01

    This document briefly presents the atmospheric monitoring station inaugurated in Houdelaincourt (Meuse) and installed by the ANDRA within the frame of the ICOS (Integrated Carbon Observing System) European infrastructure project which aims at developing air and greenhouse gas monitoring over Europe. It also recalls that this station is part of a set of means of monitoring, experimentation and protection of the environment within the frame of high and medium level nuclear waste storage project in Meuse and Haute-Marne. The document also proposes brief presentations of the different actors involved in the creation of this station: the LSCE (laboratory of sciences of climate and environment), Meteo-France, Air Lorraine, the IRSN, and the LGGE (laboratory of glaciology and geophysics of the environment)

  18. VT Data - Electric Charging Stations

    Data.gov (United States)

    Vermont Center for Geographic Information — Locations of Electric Charging Stations provided by the NREL national laboratory of the U.S. Department of Energy, Office of Energy Efficiency and Renewable Energy....

  19. NOAA Weather Radio - Station Listing

    Science.gov (United States)

    Non-Zero All Hazards Logo Emergency Alert Description Event Codes Fact Sheet FAQ Organization Search COVERAGE County Coverage Listings State Coverage Listings NWR Station Search Maps SAME SAME Coding Using

  20. Services for nuclear power stations

    International Nuclear Information System (INIS)

    Fremann, M.; Ryckelynck

    1987-01-01

    This article gives an information as complete as possible about the activities of the french nuclear industry on the export-market. It describes the equipment and services available in the field of services for nuclear power stations [fr

  1. Interior Alaska Gravity Station Data

    Data.gov (United States)

    National Oceanic and Atmospheric Administration, Department of Commerce — The gravity station data total 9416 records. This data base was received in March 1997. Principal gravity parameters include Free-air Anomalies which have been...

  2. Gravity Station Data for Spain

    Data.gov (United States)

    National Oceanic and Atmospheric Administration, Department of Commerce — The gravity station data total 28493 records. This data base was received in April 1997. Principal gravity parameters include Free-air Anomalies which have been...

  3. Gravity Station Data for Portugal

    Data.gov (United States)

    National Oceanic and Atmospheric Administration, Department of Commerce — The gravity station data total 3064 records. This data base was received in April 1997. Principal gravity parameters include Free-air Anomalies which have been...

  4. Alternative Fuels Data Center: Ethanol Fueling Stations

    Science.gov (United States)

    ... More in this section... Ethanol Basics Benefits & Considerations Stations Locations Infrastructure fueling stations by location or along a route. Infrastructure Development Learn about ethanol fueling infrastructure; codes, standards, and safety; and ethanol equipment options. Maps & Data E85 Fueling Station

  5. Non-Coop Station History (Unindexed)

    Data.gov (United States)

    National Oceanic and Atmospheric Administration, Department of Commerce — Station history documentation for stations outside the US Cooperative Observer network. Documents should be compared with those in the Non-Coop Station History...

  6. Autonomous Electrical Vehicles’ Charging Station

    OpenAIRE

    Józef Paska; Mariusz Kłos; Łukasz Rosłaniec; Rafał Bielas; Magdalena Błędzińska

    2016-01-01

    This paper presents a model of an autonomous electrical vehicles’ charging station. It consists of renewable energy sources: wind turbine system, photovoltaic cells, as well as an energy storage, load, and EV charging station. In order to optimise the operating conditions, power electronic converters were added to the system. The model was implemented in the Homer Energy programme. The first part of the paper presents the design assumptions and technological solutions. Further in the paper...

  7. Space stations systems and utilization

    CERN Document Server

    Messerschmid, Ernst

    1999-01-01

    The design of space stations like the recently launched ISS is a highly complex and interdisciplinary task. This book describes component technologies, system integration, and the potential usage of space stations in general and of the ISS in particular. It so adresses students and engineers in space technology. Ernst Messerschmid holds the chair of space systems at the University of Stuttgart and was one of the first German astronauts.

  8. Space Station Freedom operations costs

    Science.gov (United States)

    Accola, Anne L.; Williams, Gregory J.

    1988-01-01

    Measures to reduce the operation costs of the Space Station which can be implemented in the design and development stages are discussed. Operational functions are described in the context of an overall operations concept. The provisions for operations cost responsibilities among the partners in the Space Station program are presented. Cost estimating methodologies and the way in which operations costs affect the design and development process are examined.

  9. 47 CFR 73.6016 - Digital Class A TV station protection of TV broadcast stations.

    Science.gov (United States)

    2010-10-01

    ... 47 Telecommunication 4 2010-10-01 2010-10-01 false Digital Class A TV station protection of TV... Class A TV station protection of TV broadcast stations. Digital Class A TV stations must protect authorized TV broadcast stations, applications for minor changes in authorized TV broadcast stations filed on...

  10. Electricite de France: Lifetime Project

    International Nuclear Information System (INIS)

    Combes, Jean-Pierre

    1991-01-01

    Electricite de France produces almost 80% of its electricity by means of standardized PWR nuclear power stations. Starting in 1986, therefore, a project known as the 'Lifetime Project' was developed, whose aim was initially to ensure that the lifetime defined at design stage (40 years in general) could be attained without major difficulty (follow up of the aging process). It then became apparent that it would be useful to know just how far it would be technically and economically possible to go. As a result, the project is now working towards increasing the lifetime of power stations. (author)

  11. Empirical approach for real-time estimation of air flow rates in a subway station

    OpenAIRE

    Di Perna, Costanzo; Carbonari, Alessandro; Ansuini, Roberta; Casals Casanova, Miquel

    2014-01-01

    The EU-funded project called SEAM4US (Sustainable Energy mAnageMent for Underground Stations) is targeted to define advanced control systems for cost-effective management of subway stations, which will be applied to the pilot Peer Reviewed

  12. SALCER´s Project

    Directory of Open Access Journals (Sweden)

    Carlos Pérez

    2009-12-01

    Full Text Available SALCER (in Spanish: Sistema de Asesoramiento y Localización de Centrales de EnergíaRenovables could be translated as Counseling and Location of Renewable Energy Power Station´s System. Its objective is to develop a system capable of finding the most suitable place for the construction of renewable power stations, taking into account such things as: budget, topography, amount of energy needed, among others. The most relevant aims of the project are: study of a certain variety of renewable energy technologies, designing an accurate topology system, restraining decisions to demand forecasts and finally performance of an energy plan for a specific region

  13. Brentwood Lessons Learned Project Report

    Energy Technology Data Exchange (ETDEWEB)

    Rivkin, Carl H. [National Renewable Energy Lab. (NREL), Golden, CO (United States); Caton, Melanie C. [National Renewable Energy Lab. (NREL), Golden, CO (United States); Ainscough, Christopher D. [National Renewable Energy Lab. (NREL), Golden, CO (United States); Marcinkoski, Jason [Dept. of Energy (DOE), Washington DC (United States)

    2017-09-26

    The purpose of this report is to document lessons learned in the installation of the hydrogen fueling station at the National Park Service Brentwood site in Washington, D.C., to help further the deployment of hydrogen infrastructure required to support hydrogen and other fuel cell technologies. Hydrogen fueling is the most difficult infrastructure component to build and permit. Hydrogen fueling can include augmenting hydrogen fueling capability to existing conventional fuel fueling stations as well as building brand new hydrogen fueling stations. This report was produced as part of the Brentwood Lessons Learned project. The project consisted of transplanting an existing modular hydrogen fueling station from Connecticut to the National Park Service Brentwood site. This relocation required design and construction at the Brentwood site to accommodate the existing station design as well as installation and validation of the updated station. One of the most important lessons learned was that simply moving an existing modular station to an operating site was not necessarily straight-forward - performing the relocation required significant effort and cost. The station has to function at the selected operating site and this functionality requires a power supply, building supports connecting to an existing alarm system, electrical grounding and lighting, providing nitrogen for purging, and providing deionized water if an electrolyzer is part of the station package. Most importantly, the station has to fit into the existing site both spatially and operationally and not disrupt existing operations at the site. All of this coordination and integration requires logistical planning and project management. The idea that a hydrogen fueling station can be simply dropped onto a site and made immediately operational is generally not realistic. Other important lessons learned include that delineating the boundaries of the multiple jurisdictions that have authority over a project for

  14. Pumped energy transfer stations (STEP)

    International Nuclear Information System (INIS)

    Tournery, Jean-Francois

    2015-12-01

    As objectives of development are high for renewable energies (they are supposed to cover 50 per cent of new energy needs by 2035), pumped energy transfer stations are to play an important role in this respect. The author first discusses the consequences of the development of renewable energies on the exploitation of electric grids: issue of intermittency for some of them, envisaged solutions. Then, he addresses one of the solutions: the storage of electric power. He notices that increasing the potential energy of a volume of water is presently the most mature solution to face massive needs of the power system. Dams and pumped energy transfer stations represent now almost the whole installed storage power in the world. The author then presents these pumped energy transfer stations: principle, brief history (the first appeared in Italy and Switzerland at the end of the 1890's). He indicates the various parameters of assessment of such stations: maximum stored energy, installed power in pumping mode and turbine mode, time constant, efficiency, level of flexibility. He discusses economic issues. He describes and comments the operation of turbine-pump groups: ternary groups, reversible binary groups. He discusses barriers to be overcome and technical advances to be made for varying speed groups and for marine stations. He finally gives an overview (table with number of stations belonging to different power ranges, remarkable installations) of existing stations in China, USA, Japan, Germany, Austria, Spain, Portugal, Italy, Switzerland, France and UK, and indicate predictions regarding storage needs at the world level. Some data are finally indicated for the six existing French installations

  15. Eco-technology service station: the future of gas station; Posto eco-tecnologico: o posto do futuro

    Energy Technology Data Exchange (ETDEWEB)

    Moura, Newton R. [PETROBRAS, Rio de Janeiro, RJ (Brazil); Daher, Humberto Antonio S. [PETROBRAS Distribuidora, Rio de Janeiro, RJ (Brazil)

    2004-07-01

    PETROBRAS Distribuidora and CENPES have a project to build an eco-technology service station at Ilha do Fundao, to know new technologies for vehicle fuelling, test of new vehicle natural gas compression system, and start projects with new fuels that are not available at Brazilian market. This service station concept shall be aligned with sustainability premise that are being established for both companies, that means, besides a technology focus, it shall have a social focus without any environment damage. PETROBRAS 'Board of Directors approved the expansion of PETROBRAS' Research and Development Center (CENPES) installations, including this service station construction. Some activities that will be developed at the service station are pointed out here: available of new natural gas compression system; micro-generation with micro turbine, fuel cell; and photo-voltaic cell technologies; hydrogen fuelling; oil-water system treatment; biodiesel fuelling. This station will have a show room opened to the public, with panels, videos and a CNG compressor in cut. (author)

  16. Challenges with the largest commercial hydrogen station in the world

    Energy Technology Data Exchange (ETDEWEB)

    Charbonneau, Thomas; Gauthier, Pierre [Air Liquide Canada (Canada)

    2010-07-01

    This abstract's objective is to share with the participants the story of the largest hydrogen fueling station made to this date and to kick-start the story, we will cover the challenges; first the technical ones; the operational ones; the distribution ones and; the financial ones. We will then move on to review the logistic (geographic) issues raised by the project and conclude our presentation by sharing the output values of the largest fueling station built so far in the world. (orig.)

  17. Transwaal - economic district heat from the Beznau nuclear power station

    International Nuclear Information System (INIS)

    Schatzmann, G.

    1986-01-01

    Initial study phases of the Transwaal project for distribution of heat from the Beznau nuclear power station via pipe lines to Aare and Limmat valley regions in Switzerland are presented. 500 MW heat availability through heat exchangers providing forward flow water temperature of 120 0 C, pipe line network and pumping station aspects, and the system energy flow diagram, are described. Considerations based on specific energy requirements in the year 2000 including alternative schemes showed economic viability. Investment and consumer costs and savings compared with oil and gas heating are discussed. Heat supply is guaranteed well into the 21st century and avoids environmental disadvantages. (H.V.H.)

  18. Research report of FY 1997 on the environmentally acceptable coal utilization system introduction support project. Follow-up project on circulating fluidized bed boiler introduction (Calaca Batangas Thermal Power Station); 1997 nendo chosa hokokusho. Kankyo chowagata sekitan riyo system donyu shien jigyo (junkan ryudosho boiler ni kakawaru follow up jigyo (Calaca Batangas karyoku hatsudensho))

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1998-03-01

    For the follow-up project, to promote the diffusion of results of the clean coal technology (CCT) model projects, experts of circulating fluidized bed boilers were dispatched, to guide and advise for the operation of facilities introduced in these projects. The purpose of these projects is to diffuse the CCTs, and to support the promotion of environmental measures. Some guidance and advice about operation processes, data processing, operation regulation, maintenance, and boiler maintenance works were provided to the Ministry of Energy and Electric Power Corporation of the Philippines. Semirara, Malangas, and Samar coals in the Philippines were used for the tests. The boiler facilities could be operated by Philippine operators themselves. Based on the guidance and advice about operation processes, combustion tests using various Philippine coals were also planned and conducted by themselves. The maintenance techniques were transferred to Philippine operators through the inspection, repair and advice. The Philippine side understood the technologies well, and the circulating fluidized bed boiler technology was independently educated in the Philippines. 23 figs., 16 tabs.

  19. The Paks Nuclear Power Station

    International Nuclear Information System (INIS)

    Erdosi, N.; Szabo, L.

    1978-01-01

    As the first stage in the construction of the Paks Nuclear Power Station, two units of 440 MW(e) each will be built. They are operated with two coolant loops each. The reactor units are VVER 440 type water-moderated PWR type heterogeneous power reactors designed in the Soviet Union and manufactured in Czechoslovakia. Each unit operates two Soviet-made K-220-44 steam turbines and Hungarian-made generators of an effective output of 220 MW. The output of the transformer units - also of Hungarian made - is 270 MVA. The radiation protection system of the nuclear power station is described. Protection against system failures is accomplished by specially designed equipment and security measures especially within the primary circuit. Some data on the power station under construction are given. (R.P.)

  20. Hungarian repeat station survey, 2010

    Directory of Open Access Journals (Sweden)

    Péter Kovács

    2013-03-01

    Full Text Available The last Hungarian repeat station survey was completed between October 2010 and February 2011. Declination, inclination and the total field were observed using one-axial DMI fluxgate magnetometer mounted on Zeiss20A theodolite and GSM 19 Overhauser magnetometer. The magnetic elements of the sites were reduced to the epoch of 2010.5 on the basis of the continuous recordings of Tihany Geophysical Observatory. In stations located far from the reference observatory, the observations were carried out in the morning and afternoon in order to decrease the effect of the distant temporal correction. To further increase the accuracy, on-site dIdD variometer has also been installed near the Aggtelek station, in the Baradla cave, during the survey of the easternmost sites. The paper presents the technical details and the results of our last campaign. The improvement of the accuracy of the temporal reduction by the use of the local variometer is also reported.

  1. Monitoring of nuclear power stations

    International Nuclear Information System (INIS)

    Ull, E.; Labudda, H.J.

    1987-01-01

    The purpose of the invention is to create a process for undelayed automated detection and monitoring of accidents in the operation of nuclear power stations. According to the invention, this problem is solved by the relevant local measurements, such as radiation dose, components and type of radiation and additional relevant meteorological parameters being collected by means of wellknown data collection platforms, these being transmitted via transmission channels by means of satellites to suitable worldwide situated receiving stations on the ground, being processed there and being evaluated to recognise accidents. The local data collection platforms are used in the immediate vicinity of the nuclear power station. The use of aircraft, ships and balloons as data collection systems is also intended. (HWJ)

  2. Reviewing nuclear power station achievement

    International Nuclear Information System (INIS)

    Howles, L.R.

    1976-01-01

    For measurement of nuclear power station achievement against original purchase the usual gross output figures are of little value since the term loosely covers many different definitions. An authentically designed output figure has been established which relates to net design output plus house load at full load. Based on these figures both cumulative and moving annual load factors are measured, the latter measuring the achievement over the last year, thus showing trends with time. Calculations have been carried out for all nuclear stations in the Western World with 150 MW(e) gross design output and above. From these are shown: moving annual load factor indicating relative station achievements for all the plants; cumulative load factors from which return of investment can be calculated; average moving annual load factors for the four types of system Magnox, PWR, HWR, and BWR; and a relative comparison of achievement by country in a few cases. (U.K.)

  3. 47 CFR 73.1120 - Station location.

    Science.gov (United States)

    2010-10-01

    ... 47 Telecommunication 4 2010-10-01 2010-10-01 false Station location. 73.1120 Section 73.1120... Rules Applicable to All Broadcast Stations § 73.1120 Station location. Each AM, FM, TV and Class A TV... be the geographical station location. [65 FR 30003, May 10, 2000] ...

  4. Developments of space station; Uchu station no kaihatsu

    Energy Technology Data Exchange (ETDEWEB)

    Hashimoto, H. [National Space Development Agency of Japan, Tokyo (Japan)

    1996-03-05

    This paper introduces the Japanese experiment module (JEM) in developing a space station. The JEM consists of systems of a pressurizing section, an exposure section, a pressurizing portion of a supply section, a manipulator and an exposure portion of the supply section. The pressurizing section circulates and controls air so that crews can perform experiments under pressurized environment. The exposure section is a part in which experiments are carried out under exposure environment. The supply section runs between a station and the ground, with required devices loaded on it. The manipulator performs attaching a payload for the exposure section and replaces experimental samples. The JEM undergoes a schedule of fabricating an engineering model, testing for a certification a prototype flight model, and putting the model on a flight. The pressurizing section, exposure section and manipulator are at the stage of system tests. Surveillance of the JEM and control of the experiments are carried out at the Tsukuba Space Center. The Center is composed of a space experiment building, a zero-gravity environment testing building, an astronaut training building, a space station operating building, and a space station testing building. 7 figs., 2 tabs.

  5. Space Station personal hygiene study

    Science.gov (United States)

    Prejean, Stephen E.; Booher, Cletis R.

    1986-01-01

    A personal hygiene system is currently under development for Space Station application that will provide capabilities equivalent to those found on earth. This paper addresses the study approach for specifying both primary and contingency personal hygiene systems and provisions for specified growth. Topics covered are system definition and subsystem descriptions. Subsystem interfaces are explored to determine which concurrent NASA study efforts must be monitored during future design phases to stay up-to-date on critical Space Station parameters. A design concept for a three (3) compartment personal hygiene facility is included as a baseline for planned test and verification activities.

  6. Space Station - Risks and vision

    Science.gov (United States)

    Pedersen, K.

    1986-01-01

    In assessing the prospects of the NASA Space Station program, it is important to take account of the long term perspective embodied in the proposal; its international participants are seen as entering a complex web of developmental and operational interdependence of indefinite duration. It is noted to be rather unclear, however, to what extent this is contemplated by such potential partners as the ESA, which has its own program goals. These competing hopes for eventual autonomy in space station operations will have considerable economic, technological, and political consequences extending well into the next century.

  7. International Space Station Lithium-Ion Battery

    Science.gov (United States)

    Dalton, Penni J.; Schwanbeck, Eugene; North, Tim; Balcer, Sonia

    2016-01-01

    The International Space Station (ISS) primary Electric Power System (EPS) currently uses Nickel-Hydrogen (Ni-H2) batteries to store electrical energy. The electricity for the space station is generated by its solar arrays, which charge batteries during insolation for subsequent discharge during eclipse. The Ni-H2 batteries are designed to operate at a 35 depth of discharge (DOD) maximum during normal operation in a Low Earth Orbit. Since the oldest of the 48 Ni-H2 battery Orbital Replacement Units (ORUs) has been cycling since September 2006, these batteries are now approaching their end of useful life. In 2010, the ISS Program began the development of Lithium-Ion (Li-Ion) batteries to replace the Ni-H2 batteries and concurrently funded a Li-Ion ORU and cell life testing project. When deployed, they will be the largest Li-Ion batteries ever utilized for a human-rated spacecraft. This paper will include an overview of the ISS Li-Ion battery system architecture, the Li-Ion battery design and development, controls to limit potential hazards from the batteries, and the status of the Li-Ion cell and ORU life cycle testing.

  8. Risk Management for the International Space Station

    Science.gov (United States)

    Sebastian, J.; Brezovic, Philip

    2002-01-01

    The International Space Station (ISS) is an extremely complex system, both technically and programmatically. The Space Station must support a wide range of payloads and missions. It must be launched in numerous launch packages and be safely assembled and operated in the harsh environment of space. It is being designed and manufactured by many organizations, including the prime contractor, Boeing, the NASA institutions, and international partners and their contractors. Finally, the ISS has multiple customers, (e.g., the Administration, Congress, users, public, international partners, etc.) with contrasting needs and constraints. It is the ISS Risk Management Office strategy to proactively and systematically manages risks to help ensure ISS Program success. ISS program follows integrated risk management process (both quantitative and qualitative) and is integrated into ISS project management. The process and tools are simple and seamless and permeate to the lowest levels (at a level where effective management can be realized) and follows the continuous risk management methodology. The risk process assesses continually what could go wrong (risks), determine which risks need to be managed, implement strategies to deal with those risks, and measure effectiveness of the implemented strategies. The process integrates all facets of risk including cost, schedule and technical aspects. Support analysis risk tools like PRA are used to support programatic decisions and assist in analyzing risks.

  9. Design of the LBNF Beamline Target Station

    Energy Technology Data Exchange (ETDEWEB)

    Tariq, S. [Fermilab; Ammigan, K. [Fermilab; Anderson, K.; ; Buccellato, S. A. [Fermilab; Crowley, C. F. [Fermilab; Hartsell, B. D. [Fermilab; Hurh, P. [Fermilab; Hylen, J. [Fermilab; Kasper, P. [Fermilab; Krafczyk, G. E. [Fermilab; Lee, A. [Fermilab; Lundberg, B. [Fermilab; Reitzner, S. D. [Fermilab; Sidorov, V. [Fermilab; Stefanik, A. M. [Fermilab; Tropin, I. S. [Fermilab; Vaziri, K. [Fermilab; Williams, K. [Fermilab; Zwaska, R. M. [Fermilab; Densham, C. [RAL, Didcot

    2016-10-01

    The Long Baseline Neutrino Facility (LBNF) project will build a beamline located at Fermilab to create and aim an intense neutrino beam of appropriate energy range toward the DUNE detectors at the SURF facility in Lead, South Dakota. Neutrino production starts in the Target Station, which consists of a solid target, magnetic focusing horns, and the associated sub-systems and shielding infrastructure. Protons hit the target producing mesons which are then focused by the horns into a helium-filled decay pipe where they decay into muons and neutrinos. The target and horns are encased in actively cooled steel and concrete shielding in a chamber called the target chase. The reference design chase is filled with air, but nitrogen and helium are being evaluated as alternatives. A replaceable beam window separates the decay pipe from the target chase. The facility is designed for initial operation at 1.2 MW, with the ability to upgrade to 2.4 MW, and is taking advantage of the experience gained by operating Fermilab’s NuMI facility. We discuss here the design status, associated challenges, and ongoing R&D and physics-driven component optimization of the Target Station.

  10. Project managing your simulator DCS upgrade

    International Nuclear Information System (INIS)

    Carr, S.

    2006-01-01

    The intention of this paper is to provide helpful information and tips for the purchaser with regard to the project management of a DCS upgrade for an existing nuclear power station operator-training simulator. This paper was written shortly after STS Powergen completed two nuclear power station simulator DCS projects in the USA. Areas covered by this paper are: - Contractual documents and arrangements; - Licence and Escrow agreements; - Liquidated damages; - Project management; - Project schedules and resources; - Monitoring progress; - Defect reporting; - DCS automation code; - Access to proprietary information; - Tips for project meetings; - Testing; - Cultural issues; - Training

  11. Single-Station Sigma for the Iranian Strong Motion Stations

    Science.gov (United States)

    Zafarani, H.; Soghrat, M. R.

    2017-11-01

    In development of ground motion prediction equations (GMPEs), the residuals are assumed to have a log-normal distribution with a zero mean and a standard deviation, designated as sigma. Sigma has significant effect on evaluation of seismic hazard for designing important infrastructures such as nuclear power plants and dams. Both aleatory and epistemic uncertainties are involved in the sigma parameter. However, ground-motion observations over long time periods are not available at specific sites and the GMPEs have been derived using observed data from multiple sites for a small number of well-recorded earthquakes. Therefore, sigma is dominantly related to the statistics of the spatial variability of ground motion instead of temporal variability at a single point (ergodic assumption). The main purpose of this study is to reduce the variability of the residuals so as to handle it as epistemic uncertainty. In this regard, it is tried to partially apply the non-ergodic assumption by removing repeatable site effects from total variability of six GMPEs driven from the local, Europe-Middle East and worldwide data. For this purpose, we used 1837 acceleration time histories from 374 shallow earthquakes with moment magnitudes ranging from M w 4.0 to 7.3 recorded at 370 stations with at least two recordings per station. According to estimated single-station sigma for the Iranian strong motion stations, the ratio of event-corrected single-station standard deviation ( Φ ss) to within-event standard deviation ( Φ) is about 0.75. In other words, removing the ergodic assumption on site response resulted in 25% reduction of the within-event standard deviation that reduced the total standard deviation by about 15%.

  12. Task analysis and structure scheme for center manager station in large container inspection system

    International Nuclear Information System (INIS)

    Li Zheng; Gao Wenhuan; Wang Jingjin; Kang Kejun; Chen Zhiqiang

    1997-01-01

    LCIS works as follows: the accelerator generates beam pulses which are formed into fan shape; the scanning system drags a lorry with a container passing through the beam in constant speed; the detector array detects the beam penetrating the lorry; the projection data acquisition system reads the projections and completes an inspection image of the lorry. All these works are controlled and synchronized by the center manage station. The author will describe the process of the projection data acquisition in scanning mode and the methods of real-time projection data processing. the task analysis and the structure scheme of center manager station is presented

  13. Operation and management of United Central Piping LPG supply stations in Shenzhen

    Energy Technology Data Exchange (ETDEWEB)

    Lai Yankai

    1997-11-01

    Shenzhen has based its city gas development project on the eventual conversion to natural gas supply by way of central piping LPG supply stations. To fully exploit the potential gas supply capability of every central piping station and cut down the total running cost, we have been connecting the existing supply stations and their piping system into a network, which not only provided a more reliable gas supply performance, but can greatly simplify the evacuation of gas stations from the ever-expanding downtown areas to suburbs. Through this way, the periodic gas stock held by individual stations can be transferred to storage terminal or stations of enough holding capability; the supplying distance has been much lengthened and the gas volume held in the piping system increased; gas supply covered by small stations has been shifted to new and large stations. By linking these stations, we are able to provide pipeline LP gas supply for a large area, and in the same time lay down the pipeline infrastructure for the upcoming LNG supply so that an easy conversion to LNG supply can be secured as soon as the projected LNG terminal is put to service. (au)

  14. Simple simulation training system for short-wave radio station

    Science.gov (United States)

    Tan, Xianglin; Shao, Zhichao; Tu, Jianhua; Qu, Fuqi

    2018-04-01

    The short-wave radio station is a most important transmission equipment of our signal corps, but in the actual teaching process, which exist the phenomenon of fewer equipment and more students, making the students' short-wave radio operation and practice time is very limited. In order to solve the above problems, to carry out shortwave radio simple simulation training system development is very necessary. This project is developed by combining hardware and software to simulate the voice communication operation and signal principle of shortwave radio station, and can test the signal flow of shortwave radio station. The test results indicate that this system is simple operation, human-machine interface friendly and can improve teaching more efficiency.

  15. Prospect and problems of gas based power stations of NTPC

    International Nuclear Information System (INIS)

    Suryanarayana, A.

    1993-01-01

    The policy of the Government of India concerning utilisation of natural gas resources of the country has undergone changes over the last few years. The government decided in 1985 to allocate natural gas for power generation and in the year 1986 approved the setting up of the first series of three gas based combined cycle power projects of National Thermal Power Corporation (NTPC). The problems of gas power stations of NTPC are discussed. These are high cost of generation, completion of transmission line works to match with the commissioning of gas power stations, high price of natural gas, and fixation of tariff for sale of power from gas based power stations. (N.B.)

  16. Remote input/output station

    CERN Multimedia

    1972-01-01

    A general view of the remote input/output station installed in building 112 (ISR) and used for submitting jobs to the CDC 6500 and 6600. The card reader on the left and the line printer on the right are operated by programmers on a self-service basis.

  17. The Medicina Station Status Report

    Science.gov (United States)

    Orfei, Alessandro; Orlati, Andrea; Maccaferri, Giuseppe

    2013-01-01

    General information about the Medicina Radio Astronomy Station, the 32-m antenna status, and the staff in charge of the VLBI observations is provided. In 2012, the data from geodetic VLBI observations were acquired using the Mark 5A recording system with good results. Updates of the hardware were performed and are briefly described.

  18. "Artificial intelligence" at streamgaging stations

    Science.gov (United States)

    R. B. Thomas

    1985-01-01

    Two types of problems are related to collecting hydrologic data at stream gaging stations. One includes the technical/logistical questions associated with measuring and transferring data for processing. Effort spent on these problems ranges from improving devices for sensing data to using electronic data loggers.

  19. Automating Space Station operations planning

    Science.gov (United States)

    Ziemer, Kathleen A.

    1989-01-01

    The development and implementation of the operations planning processes for the Space Station are discussed. A three level planning process, consisting of strategic, tactical, and execution level planning, is being developed. The integration of the planning procedures into a tactical planning system is examined and the planning phases are illustrated.

  20. Performance of Existing Hydrogen Stations

    Energy Technology Data Exchange (ETDEWEB)

    Sprik, Samuel [National Renewable Energy Laboratory (NREL), Golden, CO (United States); Kurtz, Jennifer M [National Renewable Energy Laboratory (NREL), Golden, CO (United States); Ainscough, Christopher D [National Renewable Energy Laboratory (NREL), Golden, CO (United States); Saur, Genevieve [National Renewable Energy Laboratory (NREL), Golden, CO (United States); Peters, Michael C [National Renewable Energy Laboratory (NREL), Golden, CO (United States)

    2017-12-01

    In this presentation, the National Renewable Energy Laboratory presented aggregated analysis results on the performance of existing hydrogen stations, including performance, operation, utilization, maintenance, safety, hydrogen quality, and cost. The U.S. Department of Energy funds technology validation work at NREL through its National Fuel Cell Technology Evaluation Center (NFCTEC).

  1. Space Station power system issues

    International Nuclear Information System (INIS)

    Giudici, R.J.

    1985-01-01

    Issues governing the selection of power systems for long-term manned Space Stations intended solely for earth orbital missions are covered briefly, drawing on trade study results from both in-house and contracted studies that have been conducted over nearly two decades. An involvement, from the Program Development Office at MSFC, with current Space Station concepts began in late 1982 with the NASA-wide Systems Definition Working Group and continued throughout 1984 in support of various planning activities. The premise for this discussion is that, within the confines of the current Space Station concept, there is good reason to consider photovoltaic power systems to be a venerable technology option for both the initial 75 kW and 300 kW (or much greater) growth stations. The issue of large physical size required by photovoltaic power systems is presented considering mass, atmospheric drag, launch packaging and power transmission voltage as being possible practicality limitations. The validity of searching for a cross-over point necessitating the introduction of solar thermal or nuclear power system options as enabling technologies is considered with reference to programs ranging from the 4.8 kW Skylab to the 9.5 gW Space Power Satellite

  2. 47 CFR 73.6018 - Digital Class A TV station protection of DTV stations.

    Science.gov (United States)

    2010-10-01

    ... 47 Telecommunication 4 2010-10-01 2010-10-01 false Digital Class A TV station protection of DTV... TV station protection of DTV stations. Digital Class A TV stations must protect the DTV service that... application for digital operation of an existing Class A TV station or to change the facilities of a digital...

  3. 47 CFR 80.107 - Service of private coast stations and marine-utility stations.

    Science.gov (United States)

    2010-10-01

    ... 47 Telecommunication 5 2010-10-01 2010-10-01 false Service of private coast stations and marine...) SAFETY AND SPECIAL RADIO SERVICES STATIONS IN THE MARITIME SERVICES Operating Requirements and Procedures Operating Procedures-Land Stations § 80.107 Service of private coast stations and marine-utility stations. A...

  4. 47 CFR 95.139 - Adding a small base station or a small control station.

    Science.gov (United States)

    2010-10-01

    ... 47 Telecommunication 5 2010-10-01 2010-10-01 false Adding a small base station or a small control... base station or a small control station. (a) Except for a GMRS system licensed to a non-individual, one or more small base stations or a small control station may be added to a GMRS system at any point...

  5. New Porta Susa - Turin Railway Station

    Directory of Open Access Journals (Sweden)

    Silvio d'Ascia

    2011-02-01

    Full Text Available The project of the new station of Torino Porta Susa is the project of a huge urban public space, where the station, conceived as an urban gallery, becomes a real street, a “passage”, a new kind of urbanity shape for the future city. The railway station’s transparent volume - a 385 m (the length of the TGV long steel and glass tunnel, 30 m. width, with a variable height compared to the outdoor street level (between 12 and 3 m at the height of the cover - is proposed as a modern reinterpretation of the nineteenth century’s urban galleries and the great historical station’s halles, as well as a kind of symbolic building. Symbol of movement, of the travel universe and the presence of the transportation universe in the contemporary city, urban simulacrum of the object train disappeared from the urban scene below the future Central Spine. The sinuous movement of the tunnel follows the flows of urban pedestrians from the city towards the different transportation modes presents at various levels (national and international lines AV, regional lines, subways, taxis ... emphasizing with its lowering the presence of the big void inside of the underground subway station, about 20 meters deep. The gallery, oriented north-south, folds with its internal pedestrian paths to bring natural light and the sky of Turin, to the quays of trains (at an altitude of -10 m and the Subway (which share -20, transformed so’ in a sort of urban sidewalks. The fast rhythm of the structure of arches with step 360 cm. is marked by the presence of numerous openings along the longitudinal development of the gallery, which is crossed by three transversal passages inside the gallery and is bounded by two others on the north and south of the lot, connecting the city from east to west at street level in continuity with pre-existing axes. The presence of these transversal passages accentuates the urban value of the Spina which was to re-connect the two sides of the city until

  6. Work/control stations in Space Station weightlessness

    Science.gov (United States)

    Willits, Charles

    1990-01-01

    An ergonomic integration of controls, displays, and associated interfaces with an operator, whose body geometry and dynamics may be altered by the state of weightlessness, is noted to rank in importance with the optimal positioning of controls relative to the layout and architecture of 'body-ported' work/control stations applicable to the NASA Space Station Freedom. A long-term solution to this complex design problem is envisioned to encompass the following features: multiple imaging, virtual optics, screen displays controlled by a keyboard ergonomically designed for weightlessness, cursor control, a CCTV camera, and a hand-controller featuring 'no-grip' vernier/tactile positioning. This controller frees all fingers for multiple-switch actuations, while retaining index/register determination with the hand controller. A single architectural point attachment/restraint may be used which requires no residual muscle tension in either brief or prolonged operation.

  7. 20 years of power station master training

    International Nuclear Information System (INIS)

    Schwarz, O.

    1977-01-01

    In the early fifties, the VGB working group 'Power station master training' elaborated plans for systematic and uniform training of power station operating personnel. In 1957, the first power station master course was held. In the meantime, 1.720 power station masters are in possession of a master's certificate of a chamber of commerce and trade. Furthermore, 53 power station masters have recently obtained in courses of the 'Kraftwerksschule e.V.' the know-how which enables them to also carry out their duty as a master in nuclear power stations. (orig.) [de

  8. Quality assurance grading of conventional equipment at nuclear power station

    International Nuclear Information System (INIS)

    Li Ping; Li Shichang

    2006-01-01

    Equipment QA grading with the systematic and standardized approach will benefit the concerned organizations by effective allocating of limited resources to guarantee the quality of essential equipment. This paper presents a new quality assurance grading system for the convention systems/equipment of nuclear power station, which is operative and at the same time could help the owner to allot resource reasonably through the analysis of the purpose of grading and the experience and lessons of LINGAO Phase I project. (authors)

  9. Training of power station staff

    International Nuclear Information System (INIS)

    Dusserre, J.

    1993-01-01

    ELECTRICITE DE FRANCE currently operates 51 generating stations with 900 and 1300 MW Pressurized Water Reactors while, only 15 years ago, France possessed only a very small number of such stations. It was therefore vital to set up a major training organization to produce staff capable of starting, controlling and maintaining these facilities with a constant eye to improving quality and safety. Operator and maintenance staff training is based on highly-structured training plans designed to match both the post to be filled and the qualifications possessed by the person who is to fill it. It was essential to set up suitable high-performance training resources to handle this fast growth in staff. These resources are constantly being developed and allow EDF to make steady progress in a large number of areas, varying from the effects of human factors to the procedures to be followed during an accident

  10. Le projet de station touristique

    OpenAIRE

    Vlès, Vincent

    1996-01-01

    Cet ouvrage traite du savoir-faire du technicien, de l'ingénieur, du directeur d'office de tourisme qui façonne, depuis maintenant près de trois décennies, le territoire local de la production touristique : la station. Il analyse les stratégies, les mises en œuvre, les pratiques de l'aménagement et du développement touristique. Il propose une construction du projet de station, méthode qui est l'aboutissement d'expériences de terrain. Il présente un guide des interventions. Il décrit des modes...

  11. Manned space stations - A perspective

    Science.gov (United States)

    Disher, J. H.

    1981-09-01

    The findings from the Skylab missions are discussed as they relate to the operations planning of future space stations such as Spacelab and the proposed Space Operations Center. Following a brief description of the Skylab spacecraft, the significance of the mission as a demonstration of the possibility of effecting emergency repairs in space is pointed out. Specific recommendations made by Skylab personnel concerning capabilities for future in-flight maintenance are presented relating to the areas of spacecraft design criteria, tool selection and spares carried. Attention is then given to relevant physiological findings, and to habitability considerations in the areas of sleep arrangements, hygiene, waste management, clothing, and food. The issue of contamination control is examined in detail as a potential major system to be integrated into future design criteria. The importance of the Skylab results to the designers of future space stations is emphasized.

  12. Space Station tethered elevator system

    Science.gov (United States)

    Haddock, Michael H.; Anderson, Loren A.; Hosterman, K.; Decresie, E.; Miranda, P.; Hamilton, R.

    1989-01-01

    The optimized conceptual engineering design of a space station tethered elevator is presented. The tethered elevator is an unmanned, mobile structure which operates on a ten-kilometer tether spanning the distance between Space Station Freedom and a platform. Its capabilities include providing access to residual gravity levels, remote servicing, and transportation to any point along a tether. The report discusses the potential uses, parameters, and evolution of the spacecraft design. Emphasis is placed on the elevator's structural configuration and three major subsystem designs. First, the design of elevator robotics used to aid in elevator operations and tethered experimentation is presented. Second, the design of drive mechanisms used to propel the vehicle is discussed. Third, the design of an onboard self-sufficient power generation and transmission system is addressed.

  13. Space Station solar water heater

    Science.gov (United States)

    Horan, D. C.; Somers, Richard E.; Haynes, R. D.

    1990-01-01

    The feasibility of directly converting solar energy for crew water heating on the Space Station Freedom (SSF) and other human-tended missions such as a geosynchronous space station, lunar base, or Mars spacecraft was investigated. Computer codes were developed to model the systems, and a proof-of-concept thermal vacuum test was conducted to evaluate system performance in an environment simulating the SSF. The results indicate that a solar water heater is feasible. It could provide up to 100 percent of the design heating load without a significant configuration change to the SSF or other missions. The solar heater system requires only 15 percent of the electricity that an all-electric system on the SSF would require. This allows a reduction in the solar array or a surplus of electricity for onboard experiments.

  14. Decommissioning of nuclear power stations

    International Nuclear Information System (INIS)

    Gregory, A.R.

    1988-01-01

    In the United Kingdom the Electricity Boards, the United Kingdom Atomic Energy Authority (UKAEA) and BNFL cooperate on all matters relating to the decommissioning of nuclear plant. The Central Electricity Generating Board's (CEGB) policy endorses the continuing need for nuclear power, the principle of reusing existing sites where possible and the building up of sufficient funds during the operating life of a nuclear power station to meet the cost of its complete clearance in the future. The safety of the plant is the responsibility of the licensee even in the decommissioning phase. The CEGB has carried out decommissioning studies on Magnox stations in general and Bradwell and Berkeley in particular. It has also been involved in the UKAEA Windscale AGR decommissioning programme. The options as to which stage to decommission to are considered. Methods, costs and waste management are also considered. (U.K.)

  15. The ANGSTREM project: present status and development activities

    International Nuclear Information System (INIS)

    Stepanov, V.S.; Legyuenko, S.K.; Grigoriev, O.G.; Gromov, B.F.; Dedul, A.V.; Leonchyk, M.P.; Pashkin, Yu.G.; Pankratov, D.V.; Chekunov, V.V.; Skorikov, D.E.

    1998-01-01

    The project ANGSTREM of a modular-transportable nuclear power-and-heating station with assured safety for remote areas is described. The station is based on fast nuclear reactor cooling by a lead-bismuth eutectic. The possible evolution of the project is mentioned in relation to possible new application - sea water desalination or refrigeration plants. (author)

  16. Stage measurement at gaging stations

    Science.gov (United States)

    Sauer, Vernon B.; Turnipseed, D. Phil

    2010-01-01

    Stream and reservoir stage are critical parameters in the computation of stream discharge and reservoir volume, respectively. In addition, a record of stream stage is useful in the design of structures that may be affected by stream elevation, as well as for the planning for various uses of flood plains. This report describes equipment and methodology for the observation, sensing, and recording of stage in streams and reservoirs. Although the U.S. Geological Survey (USGS) still uses the traditional, basic stilling-well float system as a predominant gaging station, modern electronic stage sensors and water-level recorders are now commonly used. Bubble gages coupled with nonsubmersible pressure transducers eliminate the need for stilling wells. Submersible pressure transducers have become common in use for the measurement of stage in both rivers and lakes. Furthermore, noncontact methods, such as radar, acoustic, and laser methods of sensing water levels, are being developed and tested, and in the case of radar, are commonly used for the measurement of stage. This report describes commonly used gaging-station structures, as well as the design and operation of gaging stations. Almost all of the equipment and instruments described in this report will meet the accuracy standard set by the USGS Office of Surface Water (OSW) for the measurement of stage for most applications, which is ±0.01 foot (ft) or 0.2 percent of the effective stage. Several telemetry systems are used to transmit stage data from the gaging station to the office, although satellite telemetry has become the standard. These telemetry systems provide near real-time stage data, as well as other information that alerts the hydrographer to extreme or abnormal events, and instrument malfunctions.

  17. Fortaleza Station Report for 2012

    Science.gov (United States)

    Kaufmann, Pierre; Pereira de Lucena, A. Macilio; Sombra da Silva, Adeildo

    2013-01-01

    This is a brief report about the activities carried out at the Fortaleza geodetic VLBI station (ROEN: R´adio Observat´orio Espacial do Nordeste), located in Eus´ebio, CE, Brazil, during the period from January until December 2012. The observing activities were resumed in May after the major maintenance that comprised the azimuth bearing replacement. The total observational experiments consisted of 103 VLBI sessions and continuous GPS monitoring recordings.

  18. Do cities deserve more railway stations? The choice of a departure railway station in a multiple-station region

    NARCIS (Netherlands)

    Givoni, M.; Rietveld, P.

    2014-01-01

    Promoting the use of rail is an important element in sustainable transport policy. One of the most important decisions to make in planning the railway network is on the number of stations to provide. Stations are the access points to rail services and while each additional station increases rail's

  19. Pumps for nuclear power stations

    International Nuclear Information System (INIS)

    Ogura, Shiro

    1979-01-01

    16 nuclear power plants are in commercial operation in Japan, and nuclear power generation holds the most important position among various substitute energies. Hereafter also, it is expected that the construction of nuclear power stations will continue because other advantageous energy sources are not found. In this paper, the outline of the pumps used for BWR plants is described. Nuclear power stations tend to be large scale to reduce the construction cost per unit power output, therefore the pumps used are those of large capacity. The conditions to be taken in consideration are high temperature, high pressure, radioactive fluids, high reliability, hydrodynamic performances, aseismatic design, relevant laws and regulations, and quality assurance. Pumps are used for reactor recirculation system, control rod driving hydraulic system, boric acid solution injecting system, reactor coolant purifying system, fuel pool cooling and purifying system, residual heat removing system, low pressure and high pressure core spraying systems, and reactor isolation cooling system, for condensate, feed water, drain and circulating water systems of turbines, for fresh water, sea water, make-up water and fire fighting services, and for radioactive waste treating system. The problems of the pumps used for nuclear power stations are described, for example, the requirement of high reliability, the measures to radioactivity and the aseismatic design. (Kako, I.)

  20. Optimization of station battery replacement

    International Nuclear Information System (INIS)

    Jancauskas, J.R.; Shook, D.A.

    1994-01-01

    During a loss of ac power at a nuclear generating station (including diesel generators), batteries provide the source of power which is required to operate safety-related components. Because traditional lead-acid batteries have a qualified life of 20 years, the batteries must be replaced a minimum of once during a station's lifetime, twice if license extension is pursued, and more often depending on actual in-service dates and the results of surveillance tests. Replacement of batteries often occurs prior to 20 years as a result of systems changes caused by factors such as Station Blackout Regulations, control system upgrades, incremental load growth, and changes in the operating times of existing equipment. Many of these replacement decisions are based on the predictive capabilities of manual design basis calculations. The inherent conservatism of manual calculations may result in battery replacements occurring before actually required. Computerized analysis of batteries can aid in optimizing the timing of replacements as well as in interpreting service test data. Computerized analysis also provides large benefits in maintaining the as-configured load profile and corresponding design margins, while also providing the capability of quickly analyze proposed modifications and response to internal and external audits