WorldWideScience

Sample records for station decommissioning project

  1. Shippingport Station Decommissioning Project Start of Physical Decommissioning

    International Nuclear Information System (INIS)

    Crimi, F. P.

    1987-01-01

    The Shippingport Atomic Power Station consists of the nuclear steam supply system and associated radioactive waste processing systems, which are owned by the United States Department of Energy, and the turbine-generator and balance of plant, which is owned by the Duquesne Light Company. The station is located at Shippingport, Pennsylvania on seven acres of land leased by DOE from Duquesne Light Company. The Shippingport Station Decommissioning Project is being performed under contract to the DOE by the General Electric Company and its integrated subcontractor, Morrison-Knudsen Company. as the Decommissioning Operations Contractor. This paper describes the current status of the physical decommissioning work, which started September 1985. The preparations required to start a major decommissioning work effort in a safe and cost effective manner are discussed including the development and implementation of a cost/schedule control system. The detailed plan required to ensure that people, property, and procedures are ready in sufficient time to support the start of physical decommissioning is also discussed. The total estimated cost of the Shippingport Station Decommissioning Project should be $98.3 M, with the Project scheduled for completion in April 1990. As the decommissioning of the first commercial-scale nuclear power plant, the Shippingport Project is expected to set the standard for safe, cost-effective demolition of nuclear plants

  2. Shippingport Station Decommissioning Project

    International Nuclear Information System (INIS)

    McKernan, M.L.

    1989-01-01

    The Shippingport Atomic Power Station was located on the Ohio River in Shippingport Borough (Beaver County), Pennsylvania, USA. The US Atomic Energy Commission (AEC) constructed the plant in the mid-1950s on a seven and half acre parcel of land leased from Duquesne Light Company (DLC). The purposes were to demonstrate and to develop Pressurized Water Recovery technology and to generate electricity. DLC operated the Shippingport plant under supervision of (the successor to AEC) the Department of Energy (DOE)-Naval Reactors (NR) until operations were terminated on October 1, 1982. NR concluded end-of-life testing and defueling in 1984 and transferred the Station's responsibility to DOE Richland Operations Office (RL), Surplus Facility Management Program Office (SFMPO5) on September 5, 1984. SFMPO subsequently established the Shippingport Station Decommissioning Project and selected General Electric (GE) as the Decommissioning Operations Contractor. This report is intended to provide an overview of the Shippingport Station Decommissioning Project

  3. Shippingport Station Decommissioning Project: overview and justification

    International Nuclear Information System (INIS)

    Coffman, F.E.

    1984-01-01

    The purpose of this booklet is to brief the reader on the Shippingport Station Decommissioning Project and to summarize the benefits of funding the project in FY 1984. Background information on the station and the decommissioning project is provided in this section of the booklet; the need for a reactor decommissining demonstration is discussed in the next section; and a summary of how the Shippingport Station Decommissioning Project (SSDP) provides the needed demonstration is provided in the final section

  4. Shippingport station decommissioning project technology transfer program

    International Nuclear Information System (INIS)

    Pasquini, L.A.

    1986-01-01

    The purpose of the Shippingport Station Decommissioning Project (SSDP) is to place the Shippingport Atomic Power Station in a long-term radiologically safe condition following defueling of the reactor, to perform decommissioning in such a manner as to demonstrate to the nuclear industry the application of decommissioning procedures to a large scale nuclear power plant, and to provide useful planning data for future decommissioning projects. This paper describes the Technology Transfer Program for collecting and archiving the decommissioning data base and its availability to the nuclear industry

  5. Shippingport station decommissioning project technology transfer program

    International Nuclear Information System (INIS)

    McKernan, M.L.

    1988-01-01

    US Department of Energy (DOE) Shippingport Station Decommissioning Project (SSDP) decommissioned, decontaminated, and dismantled the world's first, nuclear fueled, commercial size, electric power plant. SSDP programmatic goal direction for technology transfer is documentation of project management and operations experience. Objective is to provide future nuclear facility decommissioning projects with pertinent SSDP performance data for project assessment, planning, and operational implementation. This paper presents a working definition for technology transfer. Direction is provided for access and availability for SSDP technology acquisition

  6. Waste management for the Shippingport Station Decommissioning Project

    International Nuclear Information System (INIS)

    Mullee, G.R.; Schulmeister, A.R.

    1987-01-01

    The Shippingport Station Decommissioning Project (SSDP) is being performed by the US Department of Energy (DOE) with the objectives of placing the station in a radiologically safe condition, demonstrating safe and cost effective dismantlement and providing useful data for future decommissioning projects. This paper describes the development of the Waste Management Plan which is being used for the accomplishment of the SSDP. Significant aspects of the Plan are described, such as the use of a process control and inventory system. The current status of waste management activities is reported. It is concluded that SSDP has some unique aspects which will provide useful information for future decommissioning projects

  7. Shippingport Station Decommissioning Project

    International Nuclear Information System (INIS)

    1989-01-01

    This Topical Report is a synopsis of the decontamination of plant components and structures at the Shippingport Station Decommissioning Project (SSDP). The information is provided as a part of the Technology Transfer Program to document the preparation activities in support of the shipment of radioactive wastes and the unconditional release of the site and structural materials. 1 ref., 16 figs., 4 tabs

  8. Shippingport station decommissioning project ALARA Program

    Energy Technology Data Exchange (ETDEWEB)

    Crimi, F.P. [Lockheed Environmental Systems and Technology Co., Houston, TX (United States)

    1995-03-01

    Properly planned and implemented ALARA programs help to maintain nuclear worker radiation exposures {open_quotes}As Low As Reasonably Achievable.{close_quotes}. This paper describes the ALARA program developed and implemented for the decontamination and decommissioning (D&D) of the Shippingport Atomic Power Station. The elements required for a successful ALARA program are discussed along with examples of good ALARA practices. The Shippingport Atomic Power Station (SAPS) was the first commercial nuclear power plant to be built in the United States. It was located 35 miles northwest of Pittsburgh, PA on the south bank of the Ohio river. The reactor plant achieved initial criticality in December 1959. During its 25-year life, it produced 7.5 billion kilowatts of electricity. The SAPS was shut down in October 1982 and was the first large-scale U.S. nuclear power plant to be totally decommissioned and the site released for unrestricted use. The Decommission Project was estimated to take 1,007 man-rem of radiation exposure and $.98.3 million to complete. Physical decommissioning commenced in September 1985 and was completed in September 1989. The actual man-rem of exposure was 155. The project was completed 6 months ahead of schedule at a cost of $91.3 million.

  9. Shippingport station decommissioning project technology transfer program

    International Nuclear Information System (INIS)

    McKernan, M.L.

    1989-01-01

    The US Department of Energy (DOE) Shippingport Station Decommissioning Project (SSDP) decontaminated and dismantled the world's first nuclear-fueled, commercial-size electric power plant. The SSDP programmatic goal direction for technology transfer is documentation of project management and operations experience. The objective is to provide future nuclear facility decommissioning projects with pertinent SSDP performance data for project assessment, planning, and operational implementation. This paper sets out access and availability directions for SSDP technology acquisition. Discusses are technology transfer definition; technology transfer products including topical and other project reports, professional-technical society presentations, other project liaison and media relations, visual documentation, and technology transfer data base; and retrieving SSDP information

  10. Shippingport Station Decommissioning Project (SSDP). A progress report

    International Nuclear Information System (INIS)

    Mullee, G.R.; Usher, J.M.

    1986-01-01

    The Shippingport Atomic Power Station was shutdown in October, 1982 by the Plant Operator, Duquesne Light Company, for decommissioning by the US Department of Energy. The planning for decommissioning was completed in September, 1983. In September, 1984 operational responsibility for the station was transferred to the DOE's Decommissioning Operations Contractor - the General Electric Company (assisted by an integrated subcontractor, MK Ferguson Company). Significant accomplishments to date include the completion of all prerequisites for decommissioning, the removal of asbestos from plant systems, loading of irradiated reactor components into the reactor vessel for shipment, the commencement of electrical deactivations and the commencement of piping/component removal. Decontamination and waste processing are progressing in support of the project schedule. The reactor vessel will be shipped as one piece on a barge for burial at Hanford, Washington. The final release of the site is scheduled for April, 1990. A technology transfer program is being utilized to disseminate information about the project

  11. Shippingport Station Decommissioning Project: Contaminated concrete removal: Topical report

    International Nuclear Information System (INIS)

    1989-01-01

    This Topical Report is a synopsis of the removal of contaminated concrete from the Shippingport Station Decommissioning Project (SSDP). The information is provided as a part of the Technology Transfer Program to document the decontamination activities in support of site release in the decommissioning of a nuclear power reactor. 4 refs., 8 figs., 2 tabs

  12. Shippingport station decommissioning project irradiated components transfer: Topical report

    International Nuclear Information System (INIS)

    1988-01-01

    This topical report is a synopsis of the transfer of irradiated components into the Shippingport Reactor Pressure Vessel (RPV) performed at the Shippingport Station Decommissioning Project (SSDP). The information is provided as a part of the Technology Transfer Program to document the preparation activities for the decommissioning of a nuclear power reactor to be removed in one piece

  13. [Shippingport Station Decommissioning Project]: FY 1987 annual progress report, October 1, 1986-September 30, 1987

    International Nuclear Information System (INIS)

    1988-01-01

    This report presents progress on the Shippingport Station Decommissioning Project for FY 1987. There are two main topics: Project Management and Decommissioning Project Activities. Changes from technical and managerial concepts developed in the original Decommissioning Plan are presented with the related technical, economic, or schedule considerations. 3 refs., 9 figs., 4 tabs

  14. Shippingport Station Decommissioning Project: FY 1988 annual progress report, October 1, 1987--September 30, 1988

    International Nuclear Information System (INIS)

    1989-01-01

    This report presents progress on the Shippingport Station Decommissioning Project for FY 1988. There are two main topics: Project Management and Decommissioning Project Activities. Changes from technical and managerial concepts developed in the original Decommissioning Plan are presented with the related technical, economic, or schedular considerations. 4 refs., 17 figs., 2 tabs

  15. Shippingport Station Decommissioning Project: FY 1986 annual progress report, October 1, 1985 through September 30, 1986

    International Nuclear Information System (INIS)

    1987-01-01

    This report presents progress on the Shippingport Station Decommissioning Project for FY 1986. There are two main topics: Project Management and Decommissioning Project Activities. Changes from technical and managerial concepts developed in the original Decommissioning Plan are presented with the related technical, economic, or schedule considerations. 9 refs., 4 figs., 3 tabs

  16. Contaminated concrete scabbling at the Shippingport station decommissioning project

    International Nuclear Information System (INIS)

    Bauer, R.G.

    1989-01-01

    The Shippingport atomic power station was the first commercial nuclear power plant in the United States, joining the Duquesne Light Company (DLC) grid in December 1957. The Shippingport station was shut down in October 1982 and defueled in preparation for dismantling. On September 6, 1984, the Shippingport Station Decommissioning Project (SSDP) office of the US Department of Energy (DOE) assumed responsibility for the site. At turnover, there were several areas in the plant where radioactive contamination was entrained in concrete surfaces. The removal of contaminated concrete at SSDP was an important part of the decontamination to meet site release criteria, which is a major consideration in the decommissioning of nuclear power reactors. The highlights of this activity include: (1) development and application of remote scabbling tools, which effectively removed the contaminated concrete surfaces, and (2) use of scabblers minimized the removal of noncontaminated concrete by removing shallow layers of the surface and contributed to waste control, since the waste form enabled good packaging efficiency

  17. Shippingport Station Decommissioning Project: FYs 1984-1985 annual progress report, October 1, 1983 through September 30, 1985

    International Nuclear Information System (INIS)

    1987-01-01

    This report presents progress on the Shippingport Station Decommissioning Project for FYs 1984-85. There are three main topics: project management, decommissioning project activities, and issues of concern. The project purpose is demonstration of nuclear plant decommissioning and dismantlement operations in an environment of current industry practices. 8 refs., 8 figs., 2 tabs

  18. Shippingport Station decommissioning project overview

    International Nuclear Information System (INIS)

    Schreiber, J.J.

    1985-01-01

    The U.S. Department of Energy is in the process of decommissioning the Shippingport Atomic Power Station located on the Ohio River, 30 miles northwest of Pittsburgh, Pennsylvania. The Shippingport Station is the first commercial size nuclear power plant to undergo decommissioning in the United Staes. The plant is located on approximately 7 acres of land owned by the Duquesne Light Company (DLC) and leased to the U.S. Government. DLC operates two nuclear power plants, Beaver Valley 1 and 2, located immediately adjacent to the site and the Bruce Mansfield coal-fired power plant is also within the immediate area. The Station was shutdown in October, 1982. Defueling operations began in 1983 and were completed by September, 1984. The Shippingport Station consists of a 275' x 60' fuel handling building containing the reactor containment chamber, the service building, the turbine building, the radioactive waste processing building, the administration building and other smaller support buildings. The Station has four coolant loops and most of the containment structures are located below grade. Structures owned by the U.S. Government including the fuel handling building, service building, contaminated equipment room, the boiler chambers, the radioactive waste processing building and the decontamination and laydown buildings will be dismantled and removed to 3 feet below grade. The area will then be filled with clean soil and graded. The turbine building, testing and training building and the administration building are owned by DLC and will remain

  19. Physical decommissioning of the Shippingport Atomic Power Station

    International Nuclear Information System (INIS)

    Crimi, F.P.

    1988-01-01

    The Shippingport Atomic Power Station consists of the nuclear steam supply system and associated radioactive waste processing systems, which are owned by the United States Department of Energy (USDOE), and the turbine-generator and balance of plant which is owned by the Duquesne Light Company. The station is located at Shippingport, Pennsylvania on seven acres of land leased by USDOE from the Duquesne Light Company. The Shippingport Station Decommissioning Project (SSDP) is being managed for the USDOE by the General Electric Company and its integated subcontractor, Morrison Knudsen-Ferguson (MK-F) Company. The objectives of the Shippingport Station Decommissioning Project (SSDP) are to: Demonstrate the safe and cost effective dismantlement of a large scale nuclear power plant; Provide useful data for future decommissioning projects

  20. Decommissioning of nuclear power stations in community countries carried out and projected

    International Nuclear Information System (INIS)

    Cregut, A.; Gregory, A.R.

    1984-01-01

    The decommissioning of large plants such as nuclear power stations merits an approach requiring the introduction of measures and procedures allowing them to be dealt with efficiently; this efficiency would imply concern for optimum economy of operations while respecting the safety and protection rules inherent in nuclear energy. Consequently, plant owners require: the tactical and policy elements to guide them in their decisions and choices; efficient tools, equipment and processes which meet their needs; information gained from experience of decommissioning already carried out which would provide them with a verified background knowledge when dealing with problems. Since decommissioning experience to date has not made it possible to draw up codes and guidelines, it is important to review the work carried out by Community countries in particular on the decommissioning of nuclear power plants. The following paper does not claim to be exhaustive or to make value judgements. Its aim is to list the nuclear power stations shut down in Community countries, to outline the decommissioning levels selected in each case and to underline some interesting aspects of the technical options. In conclusion it will review what appeared to be the difficulties common to the various projects. (author)

  1. Shippingport Atomic Power Station decommissioning program and applied technology

    Energy Technology Data Exchange (ETDEWEB)

    Crimi, F P; Skavdahl, R E

    1985-01-01

    The Shippingport Station decommissioning project is the first decommissioning of a large scale nuclear power plant, and also the first nuclear power plant to be decommissioned which has continued the power operation as long as 25 years. The nuclear facilities which have been decommissioned so far have operated for shorter period and were small as compared with commercial power reactors, but the experience gained by those decommissionings as well as that gained by nuclear plant maintenance and modification has helped to establish the technology and cost basis for Shippingport and future decommissioning projects. In this paper, the current status of the preparation being made by the General Electric Co., its subcontractor and the US Department of Energy for starting the decommissioning phase of the Shippingport Atomic Power Station is described. Also remote metal cutting, decontamination, concrete removal, the volume reduction of liquids and solids and robotics which will be applied to the project are discussed. The Shippingport Station is a 72 MWe PWR plant having started operation in 1957, and permanently shut down in 1982, after having generated over 7.4 billion kWh of electricity.

  2. Shippingport Station Decommissioning Project: Removal of piping and equipment and removal of primary system components

    International Nuclear Information System (INIS)

    1989-01-01

    This report is a technical synopsis of the removal of contaminated and non-contaminated piping and equipment from the Shippingport Station Decommissioning Project (SSDP). The information is provided as a part of the Technology Transfer Program to document dismantling activities in support of reactor decommissioning. 5 refs., 29 figs., 4 tabs

  3. Scheduling for decommissioning projects

    International Nuclear Information System (INIS)

    Podmajersky, O.E.

    1987-01-01

    This paper describes the Project Scheduling system being employed by the Decommissioning Operations Contractor at the Shippingport Station Decommissioning Project (SSDP). Results from the planning system show that the project continues to achieve its cost and schedule goals. An integrated cost and schedule control system (C/SCS) which uses the concept of earned value for measurement of performance was instituted in accordance with DOE orders. The schedule and cost variances generated by the C/SCS system are used to confirm management's assessment of project status. This paper describes the types of schedules and tools used on the SSDP project to plan and monitor the work, and identifies factors that are unique to a decommissioning project that make scheduling critical to the achievement of the project's goals. 1 fig

  4. Shippingport: A relevant decommissioning project

    International Nuclear Information System (INIS)

    Crimi, F.P.

    1988-01-01

    Because of Shippingport's low electrical power rating (72 MWe), there has been some misunderstanding on the relevancy of the Shippingport Station Decommissioning Project (SSDP) to a modern 1175 MWe commercial pressurized water reactor (PWR) power station. This paper provides a comparison of the major components of the reactor plant of the 72 MWe Shippingport Atomic Power Station and an 1175 MWe nuclear plant and the relevancy of the Shippingport decommissioning as a demonstration project for the nuclear industry. For the purpose of this comparison, Portland General Electric Company's 1175 MWe Trojan Nuclear Plant at Rainier, Oregon, has been used as the reference nuclear power plant. 2 refs., 2 figs., 1 tab

  5. Waste management for Shippingport Station Decommissioning Project: Extended summary

    International Nuclear Information System (INIS)

    Mullee, G.R.; Schulmeister, A.R.

    1987-01-01

    The Shippingport Station (SSDP) is demonstrating that the techniques and methodologies of waste management, which are currently employed by the nuclear industry, provide adequate management and control of waste activities for the decommissioning of a large scale nuclear plant. The SSDP has some unique aspects in that as part of the objective to promote technology transfer, multiple subcontractors are being utilized in the project. The interfaces resulting from multiple subcontractors require additional controls. Effective control has been accomplished by the use of a process control and inventory system, coupled with personnel training in waste management activities. This report summarizes the waste management plan and provides a status of waste management activities for SSDP

  6. Decommissioning of nuclear power stations

    International Nuclear Information System (INIS)

    Gregory, A.R.

    1988-01-01

    In the United Kingdom the Electricity Boards, the United Kingdom Atomic Energy Authority (UKAEA) and BNFL cooperate on all matters relating to the decommissioning of nuclear plant. The Central Electricity Generating Board's (CEGB) policy endorses the continuing need for nuclear power, the principle of reusing existing sites where possible and the building up of sufficient funds during the operating life of a nuclear power station to meet the cost of its complete clearance in the future. The safety of the plant is the responsibility of the licensee even in the decommissioning phase. The CEGB has carried out decommissioning studies on Magnox stations in general and Bradwell and Berkeley in particular. It has also been involved in the UKAEA Windscale AGR decommissioning programme. The options as to which stage to decommission to are considered. Methods, costs and waste management are also considered. (U.K.)

  7. Decommissioning of multiple-reactor stations: facilitation by sequential decommissioning

    International Nuclear Information System (INIS)

    Moore, E.B.; Smith, R.I.; Wittenbrock, N.G.

    1982-01-01

    Reductions in cost and radiation dose can be achieved for decommissionings at multiple reactor stations because of factors not necessarily present at a single reactor station: reactors of similar design, the opportunity for sequential decommissioning, a site dedicated to nuclear power generation, and the option of either interim or permanent low-level radioactive waste storage facilities onsite. The cost and radiation dose reductions occur because comprehensive decommissioning planning need only be done once, because the labor force is stable and need only be trained once, because there is less handling of radioactive wastes, and because central stores, equipment, and facilities may be used. The cost and radiation dose reductions are sensitive to the number and types of reactors on the site, and to the alternatives selected for decommissioning. 3 tables

  8. A summary of lessons learned at the Shippingport Station Decommissioning Project (SSDP)

    International Nuclear Information System (INIS)

    Crimi, F.P.; Mullee, G.R.

    1987-10-01

    This paper describes the lessons learned from a management perspective during decommissioning. The lessons learned are presented in a chronological sequence during the life of the project up to the present time. The careful analysis of the lessons learned and the implementation of corresponding actions have contributed toward improving the effectiveness of decommissioning as time progresses. The lessons learned should be helpful in planning future decommissioning projects

  9. Shippingport Station Decommissioning Project (SSDP): configuration control system and project activity controls

    International Nuclear Information System (INIS)

    Mullee, G.R.

    1986-01-01

    The SSDP has been using a Configuration Control system as a significant element in the management plan for the safe and effective performance of the project. The objective of the Configuration Control system is to control the physical plant configuration, system status, work schedules, status tracking, and day-to-day problem resolution. Prior to the Decommissioning Operations Contractor (DOC) assuming operational responsibility for the Shippingport Plant, an assessment was made of the status of the configuration of the systems and related documentation. Action was taken as required to match the operating procedures and system documentation with the actual physical condition of the plant. During the first stage of the project, planning was put in place for subsequent decommissioning activities. This planning included defining organizational responsibilities, completing the necessary project instructions and procedures, and doing the planning and scheduling for the subsequent decommissioning phase activities. Detailed instructions for the performance of the various decommissioning tasks were prepared. Prior to the start of any work on a given Activity Package, a Work Authorization is required. The Work Authorization form provides a complete checklist to ensure that all necessary prerequisites are completed. A computerized Communications Configuration Control Information system monitors status including information on system status, tag-outs, radiological work permits, etc. An ongoing effort is being directed toward maintaining operating instructions and system schematics, etc. current as the Plant configuration changes. The experience with the Configuration Control System to date has been favorable

  10. Decommissioning situation and research and development for the decommissioning of the commercial nuclear power station in Japan

    International Nuclear Information System (INIS)

    Yamamoto, Tatsumi.

    1996-01-01

    There are 48 commercial nuclear power stations in operation in Japan as of January 1, 1995, which supplies about 28% (2.2 x 10 8 MWh) of total annual electricity generation in FY 1992. Accordingly, as the nuclear power contributes so much in electricity generation, there is a growing concern in the public toward the safety on decommissioning nuclear power station. It is gravely important to secure the safety throughout the decommissioning. This paper discusses: the decommissioning situation in Japan; the Japanese national policy for decommissioning of commercial nuclear power stations; R and D for decommissioning of commercial nuclear power stations in Japan; and the present conditions of low-level radioactive wastes disposal in Japan

  11. The decommissioning of nuclear power stations

    International Nuclear Information System (INIS)

    Barker, F.

    1992-01-01

    This report has been commissioned by the National Steering Committee of Nuclear Free Local Authorities to provide: a comprehensive introduction to the technical, social, political, environmental and economic dimensions to nuclear power station decommissioning; an independent analysis of Nuclear Electric's recent change of decommissioning strategy; the case for wider public involvement in decision making about decommissioning; and a preliminary assessment of the potential mechanisms for achieving that essential wider public involvement

  12. Regulatory experience in nuclear power station decommissioning

    International Nuclear Information System (INIS)

    Ross, W.M.; Waters, R.E.; Taylor, F.E.; Burrows, P.I.

    1995-01-01

    In the UK, decommissioning on a licensed nuclear site is regulated and controlled by HM Nuclear Installations Inspectorate on behalf of the Health and Safety Executive. The same legislative framework used for operating nuclear power stations is also applied to decommissioning activities and provides a continuous but flexible safety regime until there is no danger from ionising radiations. The regulatory strategy is discussed, taking into account Government policy and international guidance for decommissioning and the implications of the recent white paper reviewing radioactive waste management policy. Although each site is treated on a case by case basis as regulatory experience is gained from decommissioning commercial nuclear power stations in the UK, generic issues have been identified and current regulatory thinking on them is indicated. Overall it is concluded that decommissioning is an evolving process where dismantling and waste disposal should be carried out as soon as reasonably practicable. Waste stored on site should, where it is practical and cost effective, be in a state of passive safety. (Author)

  13. The decision on the application to carry out a decommissioning project at Hinkley Point A Power Station under the Nuclear Reactors (Environmental Impact Assessment for Decommissioning) Regulations 1999

    International Nuclear Information System (INIS)

    2003-01-01

    European Council Directive 85/337/EEC, as amended by Council Directive 97/1 I/EC, sets out a framework on the assessment of the effects of certain public and private projects on the environment. The Directive is implemented in Great Britain for decommissioning nuclear reactor projects by the Nuclear Reactors (Environmental Impact Assessment for Decommissioning) Regulations 1999. The intention of the Directive and Regulations is to involve the public through consultation in considering the potential environmental impacts of a decommissioning project, and to make the decision-making process on granting consent open and transparent. The Regulations require the licensee to undertake an environmental impact assessment, prepare an environmental statement that summarises the environmental effects of the project, and apply to the Health and Safety Executive (HSE) for consent to carry out a decommissioning project. There is an optional stage where the licensee may request from HSE an opinion on what the environmental statement should contain (called a pre-application opinion). The licensee of Hinkley Point A Power Station, Magnox Electric pie, requested a pre-application opinion and provided information in a scoping report in December 2000. HSE undertook a public consultation on the scoping report and provided its pre- application opinion in April 2001. The licensee applied to HSE for consent to carry out a decommissioning project and provided an environmental statement in December 2001. Following a public consultation on the environmental statement, HSE requested further information that was subsequently provided by the licensee. A further public consultation was undertaken on the further information that ended in March 2003. All these public consultations involved around 60 organisations. HSE granted consent to carry out a decommissioning project at Hinkley Point A Power Station under the Regulations in July 2003, and attached conditions to the Consent. HSE took relevant

  14. Decommissioning plan - decommissioning project for KRR 1 and 2 (revised)

    Energy Technology Data Exchange (ETDEWEB)

    Jung, K. J.; Paik, S. T.; Chung, U. S.; Jung, K. H.; Park, S. K.; Lee, D. G.; Kim, H. R.; Kim, J. K.; Yang, S. H.; Lee, B. J

    2000-10-01

    This report is the revised Decommissioning Plan for the license of TRIGA research reactor decommissioning project according to Atomic Energy Act No. 31 and No. 36. The decommissioning plan includes the TRIGA reactor facilities, project management, decommissioning method, decontamination and dismantling activity, treatment, packaging, transportation and disposal of radioactive wastes. the report also explained the radiation protection plan and radiation safety management during the decommissioning period, and expressed the quality assurance system during the period and the site restoration after decommissioning. The first decommissioning plan was made by Hyundai Engineering Co, who is the design service company, was submitted to the Ministry of Science and Technology, and then was reviewed by the Korea Institute of Nuclear Safety. The first decommissioning plan was revised including answers for the questions arising from review process.

  15. Decommissioning plan - decommissioning project for KRR 1 and 2 (revised)

    International Nuclear Information System (INIS)

    Jung, K. J.; Paik, S. T.; Chung, U. S.; Jung, K. H.; Park, S. K.; Lee, D. G.; Kim, H. R.; Kim, J. K.; Yang, S. H.; Lee, B. J.

    2000-10-01

    This report is the revised Decommissioning Plan for the license of TRIGA research reactor decommissioning project according to Atomic Energy Act No. 31 and No. 36. The decommissioning plan includes the TRIGA reactor facilities, project management, decommissioning method, decontamination and dismantling activity, treatment, packaging, transportation and disposal of radioactive wastes. the report also explained the radiation protection plan and radiation safety management during the decommissioning period, and expressed the quality assurance system during the period and the site restoration after decommissioning. The first decommissioning plan was made by Hyundai Engineering Co, who is the design service company, was submitted to the Ministry of Science and Technology, and then was reviewed by the Korea Institute of Nuclear Safety. The first decommissioning plan was revised including answers for the questions arising from review process

  16. Technology, safety and costs of decommissioning nuclear reactors at multiple-reactor stations

    International Nuclear Information System (INIS)

    Wittenbrock, N.G.

    1982-01-01

    Safety and cost information is developed for the conceptual decommissioning of large (1175-MWe) pressurized water reactors (PWR) and large (1155-MWe) boiling water reactors (BWR) at multiple-reactor stations. Three decommissioning alternatives are studied: DECON (immediate decontamination), SAFSTOR (safe storage followed by deferred decontamination), and ENTOMB (entombment). Safety and costs of decommissioning are estimated by determining the impact of probable features of multiple-reactor-station operation that are considered to be unavailable at a single-reactor station, and applying these estimated impacts to the decommissioning costs and radiation doses estimated in previous PWR and BWR decommissioning studies. The multiple-reactor-station features analyzed are: the use of interim onsite nuclear waste storage with later removal to an offsite waste disposal facility, the use of permanent onsite nuclear waste disposal, the dedication of the site to nuclear power generation, and the provision of centralized services

  17. New projects related to decommissioning

    International Nuclear Information System (INIS)

    Benbow, R.

    2008-01-01

    The PMU has been established in support of the KNPP Decommissioning Department. All of the Infrastructure Projects associated with Decommissioning have been identified and are being managed through the EBRD Procurement Process. The status of the following projects is presented: Evaluation of the Radiological Inventory for Units 1 to 4; Supply of Size Reduction and Decontamination Workshops; Dismantling Tools and Equipment; Heat Generation Plant; Environmental Assessment for Decommissioning; Decay Storage Site for Transitional RAW ; Information Centres for Decommissioning; Storage Site for Conventional Waste from Decommissioning; Inventory, Treatment an Conditioning of Contaminated Soil; Concrete Core Sampling Analysis; Asbestos Removal Equipment; Demolition Equipment

  18. Fort St. Vrain decommissioning project

    International Nuclear Information System (INIS)

    Fisher, M.

    1998-01-01

    Public Service Company of Colorado (PSCo), owner of the Fort St. Vrain nuclear generating station, achieved its final decommissioning goal on August 5, 1997 when the Nuclear Regulatory Commission terminated the Part 50 reactor license. PSCo pioneered and completed the world's first successful decommissioning of a commercial nuclear power plant after many years of operation. In August 1989, PSCo decided to permanently shutdown the reactor and proceed with its decommissioning. The decision to proceed with early dismantlement as the appropriate decommissioning method proved wise for all stake holders - present and future - by mitigating potential environmental impacts and reducing financial risks to company shareholders, customers, employees, neighboring communities and regulators. We believe that PSCo's decommissioning process set an exemplary standard for the world's nuclear industry and provided leadership, innovation, advancement and distinguished contributions to other decommissioning efforts throughout the world. (author)

  19. Decommissioning project feedback experience in the Japan Atomic Energy Research Institut

    International Nuclear Information System (INIS)

    Yanagihara, S.; Tachibana, M.; Miyajima, K.

    2003-01-01

    Since starting the research and development program for peaceful use of nuclear energy in 1950's, various research and demonstration facilities have been constructed in research organizations, universities and commercial sectors in Japan. Some of the nuclear facilities constructed in the early stage of research and development have been retired to be decommissioned because of completion of the initial objectives in the Japan Atomic Energy Research Institute (JAERI). On the other hand, since the first commercial operation of nuclear power plant (1968), the number of nuclear power plants has increased up to 52 plants operating as of August 2003 in Japan. The shear of nuclear energy accounts approximately for 35% of electricity generation in total at present time. However, several nuclear power plants have been operated for more than 25 years and two nuclear power plants are expected to be finally shutdown by 2010 to be eventually decommissioned. The Tokai Power Station, the oldest Japanese nuclear power plant operated by the Japan Atomic Power Company, was permanently shutdown from March 1998 and it is in decommissioning stage at this time. The Fugen, which is advanced thermal reactor operated by the Japan Nuclear Cycle Development Institute (JNC), was finally shutdown on March, 2003 after 25 years operation to be decommissioned. In addition, relating to planned unification between JAERI and JNC in 2005, the studies have been in progress on decommissioning and radioactive waste treatment and disposal; the cost was estimated to be 10 to 30 billion Japanese yens per year during 80 years for decommissioning of nearly 200 nuclear facilities. Decommissioning of nuclear facilities is thus getting to be one of important issues in Japan. Decommissioning of nuclear facilities might be possible using conventional and/or partially improved technology. However, reviewing project feedback experience on decommissioning and decontamination might contribute to solve various issues

  20. The planning of decommissioning activities within nuclear facilities - Generating a Baseline Decommissioning Plan

    International Nuclear Information System (INIS)

    Meek, N.C.; Ingram, S.; Page, J.

    2003-01-01

    BNFL Environmental Services has developed planning tools to meet the emerging need for nuclear liabilities management and decommissioning engineering both in the UK and globally. It can provide a comprehensive baseline planning service primarily aimed at nuclear power stations and nuclear plant. The paper develops the following issues: Decommissioning planning; The baseline decommissioning plan;The process; Work package; Compiling the information; Deliverables summary; Customer Benefits; - Planning tool for nuclear liability life-cycle management; - Robust and reliable plans based upon 'real' experience; - Advanced financial planning; - Ascertaining risk; - Strategy and business planning. The following Deliverables are mentioned:1. Site Work Breakdown Structure; 2. Development of site implementation strategy from the high level decommissioning strategy; 3. An end point definition for the site; 4. Buildings, operational systems and plant surveys; 5. A schedule of condition for the site; 6. Development of technical approach for decommissioning for each work package; 7. Cost estimate to WBS level 5 for each work package; 8. Estimate of decommissioning waste arisings for each work package; 9. Preparation of complete decommissioning programme in planning software to suit client; 10. Risk modelling of work package and overall project levels; 11. Roll up of costs into an overall cost model; 12. Cash flow, waste profiling and resource profiling against the decommissioning programme; 13. Preparation and issue of Final Report. Finally The BDP process is represented by a flowchart listing the following stages: [Power Station project assigned] → [Review project and conduct Characterisation review of power station] → [Identify work packages] → [Set up WBS to level 3] → [Assign work packages] → [Update WBS to level 4] →[Develop cost model] → [Develop logic network] → [Develop risk management procedure] ] → [Develop project strategy document]→ [Work package

  1. Risk Assessment Strategy for Decommissioning of Fukushima Daiichi Nuclear Power Station

    Directory of Open Access Journals (Sweden)

    Akira Yamaguchi

    2017-03-01

    Full Text Available Risk management of the Fukushima Daiichi Nuclear Power Station decommissioning is a great challenge. In the present study, a risk management framework has been developed for the decommissioning work. It is applied to fuel assembly retrieval from Unit 3 spent fuel pool. Whole retrieval work is divided into three phases: preparation, retrieval, and transportation and storage. First of all, the end point has been established and the success path has been developed. Then, possible threats, which are internal/external and technical/societal/management, are identified and selected. “What can go wrong?” is a question about the failure scenario. The likelihoods and consequences for each scenario are roughly estimated. The whole decommissioning project will continue for several decades, i.e., long-term perspective is important. What should be emphasized is that we do not always have enough knowledge and experience of this kind. It is expected that the decommissioning can make steady and good progress in support of the proposed risk management framework. Thus, risk assessment and management are required, and the process needs to be updated in accordance with the most recent information and knowledge on the decommissioning works.

  2. Risk assessment strategy for decommissioning of Fukushima Daiichi Nuclear Power Station

    Energy Technology Data Exchange (ETDEWEB)

    Yamaguchi, Akira; Jang, Sung Hoon [The University of Tokyo, Tokyo (Japan); Hida, Kazuki [Nuclear Damage Compensation and Decommissioning Facilitation Corporation, Tokyo (Japan); Yamanaka, Yasunori [Tokyo Electric Power Company Holdings, Tokyo (Japan); Narumiya, Yoshiyuki [The Kansai Electric Power Co., Inc., Osaka (Japan)

    2017-03-15

    Risk management of the Fukushima Daiichi Nuclear Power Station decommissioning is a great challenge. In the present study, a risk management framework has been developed for the decommissioning work. It is applied to fuel assembly retrieval from Unit 3 spent fuel pool. Whole retrieval work is divided into three phases: preparation, retrieval, and transportation and storage. First of all, the end point has been established and the success path has been developed. Then, possible threats, which are internal/external and technical/societal/management, are identified and selected. “What can go wrong?” is a question about the failure scenario. The likelihoods and consequences for each scenario are roughly estimated. The whole decommissioning project will continue for several decades, i.e., long-term perspective is important. What should be emphasized is that we do not always have enough knowledge and experience of this kind. It is expected that the decommissioning can make steady and good progress in support of the proposed risk management framework. Thus, risk assessment and management are required, and the process needs to be updated in accordance with the most recent information and knowledge on the decommissioning works.

  3. Information management for decommissioning projects

    International Nuclear Information System (INIS)

    LeClair, A.N.; Lemire, D.S.

    2011-01-01

    This paper explores the importance of records and information management for decommissioning projects. Key decommissioning information and elements of a sound information management strategy are identified. Various knowledge management strategies and tools are discussed as opportunities for leveraging decommissioning information. The paper also examines the implementation of Atomic Energy of Canada Limited's (AECL) strategy for the long term preservation of decommissioning information, and its initiatives in leveraging of information with the application of several knowledge management strategies and tools. The implementation of AECL's strategy illustrates common as well as unique information and knowledge management challenges and opportunities for decommissioning projects. (author)

  4. Decommissioning project management unit started its activities

    International Nuclear Information System (INIS)

    Medeliene, D.

    2002-01-01

    The Decommissioning Project Management Unit team comprises western experts as well as experts from INPP Decommissioning Service who all work as a single team. The DPMU will develop the Final Decommissioning Plan and a more detailed Decommissioning Project, which will describe how the plant will be removed from service and safely decommissioned

  5. Virtual reality in decommissioning projects: experiences, lessons learned and future plans

    International Nuclear Information System (INIS)

    Rindahl, G.; Mark, N.K.F.; Meyer, G.

    2006-01-01

    The work on Virtual Reality (VR) tools for decommissioning planning, dose estimation and work management started at the Norwegian Institute for Energy Technology (IFE) in 1999 in the VR dose project with Japan Nuclear Cycle development institute (JNC), now JAEA. The main aim of this effort has been to help minimize workers' radiation exposure, as well as help to achieve more efficient use of human resources. VR dose is now used in the decommissioning of one of JNC's reactors, the Fugen Nuclear Power Station. This VR decommissioning project has later resulted in a series of projects and applications. In addition to decommissioning, IFE also put great focus on two other branches of VR tools, namely tools for knowledge management, training and education in operating facilities and tools for control room design. During the last years, this work, beginning at different ends, has been converging more and more towards VR technology for use through out the life cycle of a facility. A VR training simulator for a refuelling machine of the Leningrad NPP (LNPP) developed in cooperation with the Russian Research Centre Kurchatov Institute (RRC KI) is now planned to be used in connection with the decommissioning of the three intact reactors at Chernobyl in Ukraine. In this paper we describe experiences from use of VR in decommissioning processes, as well as results from bringing the VR technology initially developed for planned or productive facilities into the decommissioning toolbox. (author)

  6. Development of the Decommissioning Project Management System, DECOMMIS

    International Nuclear Information System (INIS)

    Chung, U. S.; Park, J. H.; Lee, K. W.; Hwang, D. S.; Park, S. K.; Hwang, S. T.; Paik, S. T.; Choi, Y. D.; Chung, K. H.; Lee, K. I.; Hong, S. B.

    2007-03-01

    At the Korea Atomic Energy Research Institute(KAERI), two projects for decommissioning of the research reactors and uranium conversion plant are carried out. The management of the projects can be defined as 'the decision of the changes of the decommissioning methodologies for the more efficient achievement of the project at an adequate time and to an improved method'. The correct decision comes from the experiences on the decommissioning project and the systematic experiences can be obtained from the good management of the decommissioning information. For this, a project management tool, DECOMMIS, was developed in the D and D Technology Division, which has the charge of the decommissioning projects at the KAERI, and its purpose was extended to following fields; generation of reports on the dismantling waste for WACID, record keeping for the next decommissioning projects of nuclear facilities, provision of fundamental data for the R and D of the decommissioning technologies

  7. Development of the Decommissioning Project Management System, DECOMMIS

    Energy Technology Data Exchange (ETDEWEB)

    Chung, U. S.; Park, J. H.; Lee, K. W.; Hwang, D. S.; Park, S. K.; Hwang, S. T.; Paik, S. T.; Choi, Y. D.; Chung, K. H.; Lee, K. I.; Hong, S. B

    2007-03-15

    At the Korea Atomic Energy Research Institute(KAERI), two projects for decommissioning of the research reactors and uranium conversion plant are carried out. The management of the projects can be defined as 'the decision of the changes of the decommissioning methodologies for the more efficient achievement of the project at an adequate time and to an improved method'. The correct decision comes from the experiences on the decommissioning project and the systematic experiences can be obtained from the good management of the decommissioning information. For this, a project management tool, DECOMMIS, was developed in the D and D Technology Division, which has the charge of the decommissioning projects at the KAERI, and its purpose was extended to following fields; generation of reports on the dismantling waste for WACID, record keeping for the next decommissioning projects of nuclear facilities, provision of fundamental data for the R and D of the decommissioning technologies.

  8. Trojan Decommissioning Project Cost Performance

    International Nuclear Information System (INIS)

    Michael B. Lackey

    2000-01-01

    The Trojan nuclear plant (Trojan) was an 1160-MW(electric) four-loop pressurized water reactor located in Rainier, Oregon. The plant was permanently shut down in 1993 after ∼17 yr of commercial operation. The early plant closure was an economic decision. The key factors in the closure analysis were escalation of inspection and repair costs associated with steam generator tube cracking and the projected availability of inexpensive replacement power in the Pacific Northwest region of the United States. Since the plant closure, Portland General Electric (PGE) has been actively engaged in decommissioning. The Trojan Decommissioning Project currently has a forecast at completion of $429.7 million (all costs are in millions of 1997 dollars, unless otherwise noted). The cost performance of the Trojan Decommissioning Project to date is addressed, as well as the tools that are in place to provide cost control through completion of decommissioning

  9. The decommissioning of commercial magnox gas cooled reactor power stations in the United Kingdom

    International Nuclear Information System (INIS)

    Holt, G.

    1998-01-01

    There are nine commercial Magnox gas-cooled reactor power stations in the United Kingdom. Three of these stations have been shutdown and are being decommissioning, and plans have also been prepared for the eventual decommissioning of the remaining operational stations. The preferred strategy for the decommissioning of the Magnox power stations has been identified as 'Safestore' in which the decommissioning activities are carried out in a number of steps separated by quiescent periods of care and maintenance. The final clearance of the site could be deferred for up to 135 years following station shutdown so as to obtain maximum benefit from radioactive decay. The first step in the decommissioning strategy is to defuel the reactors and transport all spent and new fuel off the site. This work has been completed at all three shutdown stations. Decommissioning work is continuing on the three sites and has involved activities such as dismantling, decontamination, recycling and disposal of some plant and structures, and the preparation of others for retention on the site for a period of care and maintenance. Significant experience has been gained in the practical application of decommissioning, with successful technologies and processes being identified for a wide range of activities. For example, large and small metallic and concrete structures, some with complex geometries, have been successfully decontaminated. Also, the reactors have been prepared for a long period of care and maintenance, with instrumentation and sampling systems having been installed to monitor their continuing integrity. All of this work has been done under careful safety, technical, and financial control. (author)

  10. Technology, safety and costs of decommissioning a reference boiling water reactor power station: Comparison of two decommissioning cost estimates developed for the same commercial nuclear reactor power station

    International Nuclear Information System (INIS)

    Konzek, G.J.; Smith, R.I.

    1990-12-01

    This study presents the results of a comparison of a previous decommissioning cost study by Pacific Northwest Laboratory (PNL) and a recent decommissioning cost study of TLG Engineering, Inc., for the same commercial nuclear power reactor station. The purpose of this comparative analysis on the same plant is to determine the reasons why subsequent estimates for similar plants by others were significantly higher in cost and external occupational radiation exposure (ORE) than the PNL study. The primary purpose of the original study by PNL (NUREG/CR-0672) was to provide information on the available technology, the safety considerations, and the probable costs and ORE for the decommissioning of a large boiling water reactor (BWR) power station at the end of its operating life. This information was intended for use as background data and bases in the modification of existing regulations and in the development of new regulations pertaining to decommissioning activities. It was also intended for use by utilities in planning for the decommissioning of their nuclear power stations. The TLG study, initiated in 1987 and completed in 1989, was for the same plant, Washington Public Supply System's Unit 2 (WNP-2), that PNL used as its reference plant in its 1980 decommissioning study. Areas of agreement and disagreement are identified, and reasons for the areas of disagreement are discussed. 31 refs., 3 figs., 22 tabs

  11. Decommissioning project of commercial nuclear power plant

    International Nuclear Information System (INIS)

    Karigome, S.

    2008-01-01

    Decommissioning project of commercial nuclear power plant in Japan was outlined. It is expected that the land, after the decommissioning of commercial nuclear power plants, will serve as sites for new plants. Steps will be taken to reduce the amount of wastes generated and to recycle/reuse them. Wastes with a radioactivity concentration below the 'clearance level' need not be dealt with as radioactive material, and may be handled in the same way as conventional wastes. The Tokai-1 power station, a 166 MWe carbon dioxide cooled reactor which closed down in 1998, is being decommissioned and the first ten years as 'safe storage' to allow radioactivity to decay. Non-reactor grade components such as turbines were already removed, heat exchanger dismantling started and the reactor will be dismantled, the buildings demolished and the site left ready for reuse. All radioactive wastes will be classified as low-level wastes in three categories and will be buried under the ground. The total cost will be 88.5 billion yen -34.7 billion for dismantling and 53.8 billion for waste treatment including the graphite moderator. (T. Tanaka)

  12. Progress of JPDR decommissioning project

    International Nuclear Information System (INIS)

    Kiyota, M.; Yanagihara, S.

    1995-01-01

    The Japan Power Demonstration Reactor (JPDR) decommissioning project is progressively achieving its final goal; the project will be finished by March 1996 to release the JPDR's site into unrestricted use in a green field condition. The new techniques which developed or improved in R and D, the first phase of this program, have been successfully applied to the actual dismantling activities. Some decommissioning wastes have been managed as the first case of onsite shallow land burial based on the new regulatory frame of radioactive waste management. The experiences and the data obtained from the JPDR dismantling activities are expected to contribute to future decommissioning of commercial nuclear power plants. (author)

  13. Study on archive management for nuclear facility decommissioning projects

    International Nuclear Information System (INIS)

    Huang Ling; Gong Jing; Luo Ning; Liao Bing; Zhou Hao

    2011-01-01

    This paper introduces the main features and status of the archive management for nuclear facility decommissioning projects, and explores and discusses the countermeasures in its archive management. Taking the practice of the archive management system of a reactor decommissioning project as an example, the paper illustrates the establishment of archive management system for the nuclear facility decommissioning projects. The results show that the development of a systematic archive management principle and system for nuclear decommissioning projects and the construction of project archives for the whole process from the design to the decommissioning by digitalized archive management system are one effective route to improve the complete, accurate and systematic archiving of project documents, to promote the standardization and effectiveness of the archive management and to ensure the traceability of the nuclear facility decommissioning projects. (authors)

  14. Project and feedback experience on nuclear facility decommissioning

    Energy Technology Data Exchange (ETDEWEB)

    Santiago, J.L. [ENRESA (Spain); Benest, T.G. [United Kingdom Atomic Energy Authority, Windscale, Cumbria (United Kingdom); Tardy, F.; Lefevre, Ph. [Electricite de France (EDF/CIDEN), 69 - Villeurbanne (France); Willis, A. [VT Nuclear Services (United Kingdom); Gilis, R.; Lewandowski, P.; Ooms, B.; Reusen, N.; Van Laer, W.; Walthery, R. [Belgoprocess (Belgium); Jeanjacques, M. [CEA Saclay, 91 - Gif sur Yvette (France); Bohar, M.P.; Bremond, M.P.; Poyau, C.; Mandard, L.; Boissonneau, J.F.; Fouquereau, A.; Pichereau, E.; Binet, C. [CEA Fontenay aux Roses, 92 (France); Fontana, Ph.; Fraize, G. [CEA Marcoule 30 (France); Seurat, Ph. [AREVA NC, 75 - Paris (France); Chesnokov, A.V.; Fadin, S.Y.; Ivanov, O.P.; Kolyadin, V.I.; Lemus, A.V.; Pavlenko, V.I.; Semenov, S.G.; Shisha, A.D.; Volkov, V.G.; Zverkov, Y.A. [Russian Research Centre Kurchatov Inst., Moscow (Russian Federation)

    2008-11-15

    This series of 6 short articles presents the feedback experience that has been drawn from various nuclear facility dismantling and presents 3 decommissioning projects: first, the WAGR project that is the UK demonstration project for power reactor decommissioning (a review of the tools used to dismantle the reactor core); secondly, the dismantling project of the Bugey-1 UNGG reactor for which the dismantling works of the reactor internals is planned to be done underwater; and thirdly, the decommissioning project of the MR reactor in the Kurchatov Institute. The feedback experience described concerns nuclear facilities in Spain (Vandellos-1 and the CIEMAT research center), in Belgium (the Eurochemic reprocessing plant), and in France (the decommissioning of nuclear premises inside the Fontenay-aux-roses Cea center and the decommissioning of the UP1 spent fuel reprocessing plant at the Marcoule site). (A.C.)

  15. Project and feedback experience on nuclear facility decommissioning

    International Nuclear Information System (INIS)

    Santiago, J.L.; Benest, T.G.; Tardy, F.; Lefevre, Ph.; Willis, A.; Gilis, R.; Lewandowski, P.; Ooms, B.; Reusen, N.; Van Laer, W.; Walthery, R.; Jeanjacques, M.; Bohar, M.P.; Bremond, M.P.; Poyau, C.; Mandard, L.; Boissonneau, J.F.; Fouquereau, A.; Pichereau, E.; Binet, C.; Fontana, Ph.; Fraize, G.; Seurat, Ph.; Chesnokov, A.V.; Fadin, S.Y.; Ivanov, O.P.; Kolyadin, V.I.; Lemus, A.V.; Pavlenko, V.I.; Semenov, S.G.; Shisha, A.D.; Volkov, V.G.; Zverkov, Y.A.

    2008-01-01

    This series of 6 short articles presents the feedback experience that has been drawn from various nuclear facility dismantling and presents 3 decommissioning projects: first, the WAGR project that is the UK demonstration project for power reactor decommissioning (a review of the tools used to dismantle the reactor core); secondly, the dismantling project of the Bugey-1 UNGG reactor for which the dismantling works of the reactor internals is planned to be done underwater; and thirdly, the decommissioning project of the MR reactor in the Kurchatov Institute. The feedback experience described concerns nuclear facilities in Spain (Vandellos-1 and the CIEMAT research center), in Belgium (the Eurochemic reprocessing plant), and in France (the decommissioning of nuclear premises inside the Fontenay-aux-roses Cea center and the decommissioning of the UP1 spent fuel reprocessing plant at the Marcoule site). (A.C.)

  16. Deactivation, Decontamination and Decommissioning Project Summaries

    Energy Technology Data Exchange (ETDEWEB)

    Peterson, David Shane; Webber, Frank Laverne

    2001-07-01

    This report is a compilation of summary descriptions of Deactivation, Decontamination and Decommissioning, and Surveillance and Maintenance projects planned for inactive facilities and sites at the INEEL from FY-2002 through FY-2010. Deactivations of contaminated facilities will produce safe and stable facilities requiring minimal surveillance and maintenance pending further decontamination and decommissioning. Decontamination and decommissioning actions remove contaminated facilities, thus eliminating long-term surveillance and maintenance. The projects are prioritized based on risk to DOE-ID, the public, and the environment, and the reduction of DOE-ID mortgage costs and liability at the INEEL.

  17. Radiation safety for decommissioning projects

    International Nuclear Information System (INIS)

    Ross, A.C.

    1999-01-01

    Decommissioning of redundant nuclear facilities is a growth area in the UK at the present time. NUKEM Nuclear Limited is a leading-edge nuclear decommissioning and waste management contractor (with its own in-house health physics and safety department), working for a variety of clients throughout the UK nuclear industry. NUKEM Nuclear is part of the prestigious, international NUKEM group, a world-class organization specializing in nuclear engineering and utilities technologies. NUKEM Nuclear is involved in a number of large, complex decommissioning projects, both in its own right and as part of consortia. This paper explores the challenges presented by such projects and the interfaces of contractor, client and subcontractors from the point of view of a radiation protection adviser. (author)

  18. Decommissioning of the Shippingport Atomic Power Station. Draft environmental impact statement

    International Nuclear Information System (INIS)

    1981-10-01

    The US DOE proposes to decommission the Shippingport Atomic Power Station. This environmental impact statement analyzes possible decommissioning alternatives, evaluates potential environmental impacts associated with each alternative, and presents cost estimates for each alternative. The Department's preferred decommissioning alternative is immediate dismantlement. Other alternatives include no action, safe storage followed by deferred dismantlement, and entombment. The environmental impacts that are evaluated include those associated with occupational radiation dose, public radiation dose, handling and transporting of radioactive wastes, resource commitments, and socio-economic effects

  19. Project No. 8 - Final decommissioning plan

    International Nuclear Information System (INIS)

    2000-01-01

    Ignalina NPP should prepare the final Ignalina NPP unit 1 decommissioning plan by march 31, 2002. This plan should include the following : description of Ignalina NPP and the Ignalina NPP boundary that could be influenced by decommissioning process; decommissioning strategy selected and a logical substantiation for this selection; description of the decommissioning actions suggested and a time schedule for the actions to be performed; conceptual safety and environmental impact assessment covering ionizing radiation and other man and environment impact; description of the environmental monitoring program proposed during decommissioning process; description of the waste management proposed; assessment of decommissioning expenses including waste management, accumulated funds and other sources. Estimated project cost - 0.75 M EURO

  20. Evaluation of Nuclear Facility Decommissioning Projects program

    International Nuclear Information System (INIS)

    Baumann, B.L.

    1983-01-01

    The objective of the Evaluation of Nuclear Facility Decommissioning Projects (ENFDP) program is to provide the NRC licensing staff with data which will allow an assessment of radiation exposure during decommissioning and the implementation of ALARA techniques. The data will also provide information to determine the funding level necessary to ensure timely and safe decommissioning operations. Actual decommissioning costs, methods and radiation exposures are compared with those estimated by the Battelle-PNL and ORNL NUREGs on decommissioning. Exposure reduction techniques applied to decommissioning activities to meet ALARA objectives are described. The lessons learned concerning various decommissioning methods are evaluated

  1. ADVANTAGES, DISADVANTAGES, AND LESSONS LEARNED FROM MULTI-REACTOR DECOMMISSIONING PROJECTS

    International Nuclear Information System (INIS)

    Morton, M.R.; Nielson, R.R.; Trevino, R.A.

    2003-01-01

    This paper discusses the Reactor Interim Safe Storage (ISS) Project within the decommissioning projects at the Hanford Site and reviews the lessons learned from performing four large reactor decommissioning projects sequentially. The advantages and disadvantages of this multi-reactor decommissioning project are highlighted

  2. Decommissioning Project Manager's Implementing Instructions (PMII)

    International Nuclear Information System (INIS)

    Mihalic, M.A.

    1998-02-01

    Decommissioning Project personnel are responsible for complying with these PMII. If at any time in the performance of their duties a conflict between these instructions and other written or verbal direction is recognized or perceived, the supervisor or worker shall place his/her work place in a safe condition, stop work, and seek resolution of the conflict from the Decommissioning Project Manager or his designee

  3. The brief introduction to decommissioning of nuclear reactor projects

    International Nuclear Information System (INIS)

    Zhao Shixin

    1991-01-01

    The basic concept and procedure of the decommissioning of nuclear reactor project and the three stages of decommissioning defined by IAEA are introduced. The main work of decommissioning of nuclear reactor are as following: (1) the documentary and technological preparation; (2) the site preparation of decommissioning project; (3) the dismantling of equipment piping system and components; (4) the decontamination of the piping system before and after decomminssioning; (5) the storage and disposal of the operational and decommissioning waste

  4. The brief introduction to decommissioning of nuclear reactor projects

    Energy Technology Data Exchange (ETDEWEB)

    Shixin, Zhao [Beijing Inst. of Nuclear Engineering (China)

    1991-08-01

    The basic concept and procedure of the decommissioning of nuclear reactor project and the three stages of decommissioning defined by IAEA are introduced. The main work of decommissioning of nuclear reactor are as following: (1) the documentary and technological preparation; (2) the site preparation of decommissioning project; (3) the dismantling of equipment piping system and components; (4) the decontamination of the piping system before and after decomminssioning; (5) the storage and disposal of the operational and decommissioning waste.

  5. Canadian decommissioning experience from policy to project

    International Nuclear Information System (INIS)

    Pare, F.E.

    1992-01-01

    The Canadian policy on decommissioning of nuclear facilities as defined in the Atomic Energy Control Act and Regulations is administered by the Atomic Energy Control Board (AECB), a Federal Government agency. It requires that these facilities be decommissioned according to approved plans which are to be developed by the owner of the nuclear facility during its early stages of design and to be refined during its operating life. In this regulatory environment, Atomic Energy of Canada Limited (AECL) has developed a decommissioning strategy for power stations which consists of three distinctive phases. After presenting AECL's decommissioning philosophy, this paper explains its foundations and describes how it has and soon will be applied to various facilities. It terminates by providing a brief summary of the experience gained up to date on the implementation of this strategy

  6. Development of a Preliminary Decommissioning Plan Following the International Structure for Decommissioning Costing (ISDC) of Nuclear Installations - 13361

    International Nuclear Information System (INIS)

    Moshonas Cole, Katherine; Dinner, Julia; Grey, Mike; Daniska, Vladimir

    2013-01-01

    The International Structure for Decommissioning Costing (ISDC) of Nuclear Installations, published by OECD/NEA, IAEA and EC is intended to provide a uniform list of cost items for decommissioning projects and provides a standard format that permits international cost estimates to be compared. Candesco and DECOM have used the ISDC format along with two costing codes, OMEGA and ISDCEX, developed from the ISDC by DECOM, in three projects: the development of a preliminary decommissioning plan for a multi-unit CANDU nuclear power station, updating the preliminary decommissioning cost estimates for a prototype CANDU nuclear power station and benchmarking the cost estimates for CANDU against the cost estimates for other reactor types. It was found that the ISDC format provides a well defined and transparent basis for decommissioning planning and cost estimating that assists in identifying gaps and weaknesses and facilitates the benchmarking against international experience. The use of the ISDC can also help build stakeholder confidence in the reliability of the plans and estimates and the adequacy of decommissioning funding. (authors)

  7. Activities of Knowledge Management for Decommissioning of FUGEN Nuclear Power Station

    International Nuclear Information System (INIS)

    Tezuka, M.; Iguchi, Y.; Koda, Y.; Kato, Y.; Yanagihara, S.

    2016-01-01

    Full text: The Fugen nuclear power station is a heavy–water moderated, light–water cooled, pressure– tube type reactor. After ca. 25 year operation, Fugen started decommissioning activities after the final shutdown in 2003 and the decommissioning project will last at least until 2034. In this situation, as the transfer of knowledge and education to the next generation is a crucial issue, integration and implementation of a system for knowledge management is necessary to solve it. For this purpose, a total of knowledge management system (KMS) for decommissioning was proposed. In this system, we have to arrange, organize and systematize the data and information of the plant design, maintenance history, waste management records etc. The collected data, information and records should be organized by computer support system, e.g., data base system, as well as advanced information technologies such as 3D-CAD (Computer Aided Design), VR (Virtual Reality) and AR (Augmented Reality). It will become a base of the explicit knowledge. Moreover, measures for extracting tacit knowledge from retiring employees are necessary. The experience of the retirees should be documented as much as possible through effective questionnaire or interview process. The integrated knowledge mentioned above should be used for the planning, implementation of dismantlement or education for the future generation. (author

  8. Decontamination and decommissioning project for the nuclear facilities

    Energy Technology Data Exchange (ETDEWEB)

    Park, J. H.; Paik, S. T.; Park, S. W. (and others)

    2007-02-15

    The final goal of this project is to complete the decommissioning of the Korean Research Reactor no.1 and no. 2(KRR-1 and 2) and uranium conversion plant safely and successfully. The goal of this project in 2006 is to complete the decontamination of the inside reactor hall of the KRR-2 which will be operating as a temporary storage for the radioactive waste until the construction and operation of the national repository site. Also the decommissioning work of the KRR-1 and auxiliary facilities is being progress. As the compaction of decommissioning project is near at hand, a computer information system was developed for a systematically control and preserve a technical experience and decommissioning data for the future reuse. The nuclear facility decommissioning, which is the first challenge in Korea, is being closed to the final stages. We completed the decommissioning of all the bio-shielding concrete for KRR-2 in 2005 and carried out the decontamination and waste material grouping of the roof, wall and bottom of the reactor hall of the KRR-2. The decommissioning for nuclear facility were demanded the high technology, remote control equipment and radioactivity analysis. So developed equipment and experience will be applied at the decommissioning for new nuclear facility in the future.

  9. Status of the RA research reactor decommissioning project

    International Nuclear Information System (INIS)

    Ljubenov, V.; Nikolic, D.; Pesic, M.; Milosevic, M.; Kostic, Lj.; Steljic, M.; Sotic, O.; Antic, D. . E-mail address of corresponding author: vladan@vin.bg.ac.yu; Ljubenov, V.)

    2005-01-01

    The 6.5 MW heavy water RA research reactor at the VINCA Institute of Nuclear Sciences operated from 1959 to 1984. After 18 years of extended shutdown in 2002 it was decided that the reactor shutdown should be final. Preliminary decommissioning activities have been initiated by the end of 2002 under the Technical Co-operation Programme of the International Atomic Energy Agency. The objective of the project is to implement safe, timely and cost-effective decommissioning of the RA reactor up to unrestricted use of the site. Decommissioning project is closely related to two other projects: Safe Removal of the RA Reactor Spent Nuclear Fuel and Radioactive Waste Management in VINCA Institute. The main phases of the project include preparation of the detailed decommissioning plan, radiological characterization of the reactor site, dismantling and removal of the reactor components and structures, decontamination, final radiological site survey and the documentation of all the activities in order to obtain the approval for unrestricted use of the facility site. In this paper a review of the activities related to the preparation and realization of the RA reactor decommissioning project is given. Status of the project's organizational and technical aspects as for July 2004 are presented and plans for the forthcoming phases of the project realization are outlined. (author)

  10. A state-of-the art on decommissioning of nuclear facilities in Japan

    International Nuclear Information System (INIS)

    Park, Seung Kook; Kim, Hee Reyoung; Chung, Un Soo; Jung, Ki Jung

    2002-05-01

    While proceeding the KRR-1 and 2 decommissioning project, we are carried out study for the state of the art on decommissioning of nuclear facilities in Japan. Also, we are studied for the research reactors and commercial power plant that has the object of decommissioning, and for the government and the organization related on decommissioning operation. We are investigated for decommissioning activities of nuclear facilities achieved by JAERI, and collected the information and data for decommissioning techniques and computational system through the JPDR(Japan Power Demonstration Reactor) decommissioning activities. Such techniques are applying for Tokai Power Station began the decommissioning project from last year, and for Fugen Nuclear Power Station to be planned the decommissioning from 2003. Recent techniques for decommissioning was acquired by direct contact. The status of the treatment for decommissioning waste and the disposal facility for the very low-level radioactive concrete wastes was grasped

  11. The closure of Trawsfynydd power station - effects on staff and the local community and identifying a strategy for decommissioning

    International Nuclear Information System (INIS)

    Kay, J.M.; Ellis, A.T.; Williams, T.W.

    1995-01-01

    The decision to close Trawsfynydd power station had implications for staff and the local community. It was necessary to take immediate steps to prepare for decommissioning the station and to devise an appropriate staff structure. At the same time, there was also a need for Nuclear Electric to adopt a clear and well defined decommissioning strategy. As the station is located within a National Park, as local employment opportunities are very limited and as the nuclear industry was approaching a Government Review, Nuclear Electric took steps to consult the staff and the local public on the options for decommissioning the station. This consultation influenced the decommissioning strategy chosen for Trawsfynydd. (Author)

  12. Methodology for cost estimate in projects for nuclear power plants decommissioning

    International Nuclear Information System (INIS)

    Salij, L.M.

    2008-01-01

    The conceptual approaches to cost estimating of nuclear power plants units decommissioning projects were determined. The international experience and national legislative and regulatory basis were analyzed. The possible decommissioning project cost classification was given. It was shown the role of project costs of nuclear power plant units decommissioning as the most important criterion for the main project decisions. The technical and economic estimation of deductions to common-branch fund of decommissioning projects financing was substantiated

  13. Evaluation of nuclear facility decommissioning projects. Project summary report, Elk River Reactor

    International Nuclear Information System (INIS)

    Miller, R.L.; Adams, J.A.

    1982-12-01

    This report summarizes information concerning the decommissioning of the Elk River Reactor. Decommissioning data from available documents were input into a computerized data-handling system in a manner that permits specific information to be readily retrieved. The information is in a form that assists the Nuclear Regulatory Commission in its assessment of decommissioning alternatives and ALARA methods for future decommissionings projects. Samples of computer reports are included in the report. Decommissioning of other reactors, including NRC reference decommissioning studies, will be described in similar reports

  14. Decontamination and Decommissioning Project for the Nuclear Facilities

    Energy Technology Data Exchange (ETDEWEB)

    Park, J. H.; Paik, S. T.; Park, S. W. and others

    2006-02-15

    The final goal of this project is to complete safely and successfully the decommissioning of the Korean Research Reactor no.1 (KRR-1) and the Korean Research Reactor no.2 (KRR-2), and uranium conversion plant (UCP). The dismantling of the reactor hall of the KRR-2 was planned to complete till the end of 2004, but it was delayed because of a few unexpected factors such as the development of a remotely operated equipment for dismantling of the highly radioactive parts of the beam port tubes. In 2005, the dismantling of the bio-shielding concrete structure of the KRR-2 was finished and the hall can be used as a temporary storage space for the radioactive waste generated during the decommissioning of the KRR-1 and KRR-2. The cutting experience of the shielding concrete by diamond wire saw and the drilling experience by a core boring machine will be applied to another nuclear facility dismantling. An effective management tool of the decommissioning projects, named DECOMIS, was developed and the data from the decommissioning projects were gathered. This system provided many information on the daily D and D works, waste generation, radiation dose, etc., so an effective management of the decommissioning projects is expected from next year. The operation experience of the uranium conversion plant as a nuclear fuel cycle facility was much contributed to the localization of nuclear fuels for both HWR and PWR. It was shut down in 1993 and a program for its decontamination and dismantling was launched in 2001 to remove all the contaminated equipment and to achieve the environment restoration. The decommissioning project is expected to contribute to the development of the D and D technologies for the other domestic fuel cycle facilities and the settlement of the new criteria for decommissioning of the fuel cycle related facilities.

  15. Applicability of EPRI Decommissioning Pre-Planning Manual to International Decommissioning Projects

    International Nuclear Information System (INIS)

    Lessard, Leo; Kay, Jim; Lefrancois, Donald; Furr, Richard; Lucas, Matthieu; Schauer, Konrad

    2016-01-01

    Industry models for planning the efficient decommissioning of a nuclear power plant continue to evolve. Effective planning is a key to cost control, a critical aspect of decommissioning. In 2001, the Electric Power Research Institute (EPRI) published the 'Decommissioning Pre-Planning Manual', referred to as the 'Manual'. The goal of the Manual was to develop a framework for use in pre-planning the decommissioning of a nuclear power plant. The original research was based on information collected during the active decommissioning of power reactors in New England, and the ongoing decommissioning planning of another reactor still in operation. The research team identified thirty-two (32) major Decommissioning Tasks that support the strategic and tactical planning that can be conducted in advance of plant shutdown. The Decommissioning Tasks were organized in a logical sequence of execution, and sorted in common discipline groupings. Owners of U.S. nuclear plants that have shut down prematurely during the past 5 years have found the EPRI Decommissioning Pre-Planning Manual useful in developing their transition plans from an operating to shutdown facility. Concurrently, during the past 15 years, the IAEA has published numerous technical and safety reports on nuclear reactor decommissioning planning and execution. IAEA's goal is to provide its global members with useful and timely guidance for the planning and execution of nuclear decommissioning projects. This information has been used extensively by international nuclear plant operators. One of the key objectives will be to develop a road-map linking the 32 EPRI Decommissioning Tasks with the comparable (or equivalent) topics covered in the IAEA library of decommissioning knowledge. The logical and convenient structure of the Manual will be cross-referenced to the IAEA topics to aid in organizing the development of decommissioning plans. The road-map will serve to provide a basis for improved

  16. A study of a decommissioning activities classification structure for decommissioning of the project management of a nuclear power plant

    International Nuclear Information System (INIS)

    Park, Hee Seong; Park, Seung Kook; Jin, Hyung Gon; Song, Chan Ho; Ha, Jei Hyun; Moon, Jei kwon

    2015-01-01

    Decommissioning activities and requirements that was established in the planning stage should be organized systematically in the course of dismantling the NPP. The work breakdown structure is essential to ensuring that all the project scope is identified, estimated and executed. The project manager needs to ensure that a WBS is established early in the project and maintained throughout the project life cycle. A project management system is ongoing under the circumstance of having no experience dismantling the NPP. The system related to the NPP decommissioning should have technical criteria as well as regulatory requirements in the full scale of decommissioning stage. In the dismantling stage, decommissioning plan document should include the results of radiation/radioactivity characterization, evaluation of the amount of dismantled waste, calculation of the expose dose rate, evaluation of decommissioning cost and schedule after shutdown

  17. A study of a decommissioning activities classification structure for decommissioning of the project management of a nuclear power plant

    Energy Technology Data Exchange (ETDEWEB)

    Park, Hee Seong; Park, Seung Kook; Jin, Hyung Gon; Song, Chan Ho; Ha, Jei Hyun; Moon, Jei kwon [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2015-05-15

    Decommissioning activities and requirements that was established in the planning stage should be organized systematically in the course of dismantling the NPP. The work breakdown structure is essential to ensuring that all the project scope is identified, estimated and executed. The project manager needs to ensure that a WBS is established early in the project and maintained throughout the project life cycle. A project management system is ongoing under the circumstance of having no experience dismantling the NPP. The system related to the NPP decommissioning should have technical criteria as well as regulatory requirements in the full scale of decommissioning stage. In the dismantling stage, decommissioning plan document should include the results of radiation/radioactivity characterization, evaluation of the amount of dismantled waste, calculation of the expose dose rate, evaluation of decommissioning cost and schedule after shutdown.

  18. From conception to decommissioning-servicing nuclear power

    International Nuclear Information System (INIS)

    Burbridge, R.N.

    1988-01-01

    In any utility, or integrated group of utilities, there is a need for an identified body charged with being the guardians of the design database. This is essential with nuclear stations. Within the CEGB (Central Electricity Generating Board), the Generation Development and Construction Division (GDCD) acts as that guardian and performs the triple role of Client (specifying the requirements and procuring new stations), of Architect-Engineer (defining systems and plant layouts and performing effective project management), and of Consultant (for servicing operating stations). Long-term plant developments are pursued until they can be securely incorporated into station proposals. Planning Inquiries for new stations are supported technically until the proposed station is approved and the proposal becomes a project which is managed to be completed on programme and within budget to the required standards. Once complete and commissioned, the station is handed over to the operators and the designers and constructors take on their role of Independent Assessors of proposed design changes. At the end of its life, the decommissioning of the station becomes another project requiring effective management. Nuclear power requires servicing from conception to decommissioning. 1 fig

  19. Health physics program for the Edgemont Uranium Mill decommissioning project

    International Nuclear Information System (INIS)

    Polehn, J.L.; Wallace, R.G.; Reed, R.P.; Wilson, G.T.

    1986-01-01

    The Tennessee Valley Authority (TVA) is actively involved in decommissioning a uranium mill located near the town of Edgemont, South Dakota. The Edgemont Mill Decommissioning Project, which is unique in many respects, will involve dismantlement of the old inactive mill building and excavation and transportation of several million tons of uranium mill tailings to a permanent disposal site. To ensure that workers are adequately protected from radiation exposure during decommissioning operations, a health physics program appropriate for the decommissioning situation was developed. The Edgemont Mill Decommissioning Project Health Physics Manual (HPM) gives the programmatic requirements for worker radiation protection. The requirements of the HPM are implemented by means of detailed onsite operating procedures. The Edgemont project health physics program was developed using currently available regulations and guidance for an operating uranium mill with appropriate modifications for decommissioning. This paper discusses the development, implementation, and documentation of that program

  20. Windscale advanced gas-cooled reactor (WAGR) decommissioning project overview

    International Nuclear Information System (INIS)

    Pattinson, A.

    2003-01-01

    The current BNFL reactor decommissioning projects are presented. The projects concern power reactor sites at Berkely, Trawsfynydd, Hunterstone, Bradwell, Hinkley Point; UKAEA Windscale Pile 1; Research reactors within UK Scottish Universities at East Kilbride and ICI (both complete); WAGR. The BNFL environmental role include contract management; effective dismantling strategy development; implementation and operation; sentencing, encapsulation and transportation of waste. In addition for the own sites it includes strategy development; baseline decommissioning planning; site management and regulator interface. The project objectives for the Windscale Advanced Gas-Cooled Reactor (WAGR) are 1) Safe and efficient decommissioning; 2) Building of good relationships with customer; 3) Completion of reactor decommissioning in 2005. The completed WAGR decommissioning campaigns are: Operational Waste; Hot Box; Loop Tubes; Neutron Shield; Graphite Core and Restrain System; Thermal Shield. The current campaign is Lower Structures and the remaining are: Pressure vessel and Insulation; Thermal Columns and Outer Vault Membrane. An overview of each campaign is presented

  1. Allowable Residual Contamination Levels in soil for decommissioning the Shippingport Atomic Power Station site

    International Nuclear Information System (INIS)

    Kennedy, W.E. Jr.; Napier, B.A.; Soldat, J.K.

    1983-09-01

    As part of decommissioning the Shippingport Atomic Power Station, a fundamental concern is the determination of Allowable Residual Contamination Levels (ARCL) for radionuclides in the soil at the site. The ARCL method described in this report is based on a scenario/exposure-pathway analysis and compliance with an annual dose limit for unrestricted use of the land after decommissioning. In addition to naturally occurring radionuclides and fallout from weapons testing, soil contamination could potentially come from five other sources. These include operation of the Shippingport Station as a pressurized water reactor, operations of the Shippingport Station as a light-water breeder, operation of the nearby Beaver Valley reactors, releases during decommissioning, and operation of other nearby industries, including the Bruce-Mansfield coal-fired power plants. ARCL values are presented for 29 individual radionculides and a worksheet is provided so that ARCL values can be determined for any mixture of the individual radionuclides for any annual dose limit selected. In addition, a worksheet is provided for calculating present time soil concentration value that will decay to the ARCL values after any selected period of time, such as would occur during a period of restricted access. The ARCL results are presented for both unconfined (surface) and confined (subsurface) soil contamination. The ARCL method and results described in this report provide a flexible means of determining unrestricted-use site release conditions after decommissioning the Shippingport Atomic Power Station

  2. Program change management during nuclear power plant decommissioning

    International Nuclear Information System (INIS)

    Bushart, Sean; Kim, Karen; Naughton, Michael

    2011-01-01

    Decommissioning a nuclear power plant is a complex project. The project involves the coordination of several different departments and the management of changing plant conditions, programs, and regulations. As certain project Milestones are met, the evolution of such plant programs and regulations can help optimize project execution and cost. This paper will provide information about these Milestones and the plant departments and programs that change throughout a decommissioning project. The initial challenge in the decommissioning of a nuclear plant is the development of a definitive plan for such a complex project. EPRI has published several reports related to decommissioning planning. These earlier reports provided general guidance in formulating a Decommissioning Plan. This Change Management paper will draw from the experience gained in the last decade in decommissioning of nuclear plants. The paper discusses decommissioning in terms of a sequence of major Milestones. The plant programs, associated plans and actions, and staffing are discussed based upon experiences from the following power reactor facilities: Maine Yankee Atomic Power Plant, Yankee Nuclear Power Station, and the Haddam Neck Plant. Significant lessons learned from other sites are also discussed as appropriate. Planning is a crucial ingredient of successful decommissioning projects. The development of a definitive Decommissioning Plan can result in considerable project savings. The decommissioning plants in the U.S. have planned and executed their projects using different strategies based on their unique plant circumstances. However, experience has shown that similar project milestones and actions applied through all of these projects. This allows each plant to learn from the experiences of the preceding projects. As the plant transitions from an operating plant through decommissioning, the reduction and termination of defunct programs and regulations can help optimize all facets of

  3. Human resource development for management of decommissioning

    International Nuclear Information System (INIS)

    Tanaka, Kenichi

    2017-01-01

    This paper described the contents of 'Human resource development for the planning and implementation of safe and reasonable nuclear power plant decommissioning' as the nuclear human resource development project by the Ministry of Education, Culture, Sports, Science and Technology. The decommissioning of a nuclear power plant takes 30 to 40 years for its implementation, costing tens of billions of yen. As the period of decommissioning is almost the same as the operation period, it is necessary to provide a systematic and continuous supply of engineers who understand the essence of the decommissioning project. The engineers required here should have project management ability to take charge of preparation, implementation, and termination of decommissioning, and have the ability to perform not only technology, but also factor management, cost management, and the like. As the preconditions of these abilities, it is important to develop human resources who possess qualities that can oversee decommissioning in the future. The contents of human resource education are as follows; (1) desk training (teaching materials: facilities of nuclear power plants, management of nuclear fuels, related laws, decommissioning work, decontamination, dismantling, disposal of waste, etc.), (2) field training (simulators, inspection of power station under decommissioning, etc.), (3) practical training (radiation inventory evaluation, and safety assessment), and (4) inspection of overseas decommissioning, etc. (A.O.)

  4. Decommissioning wind energy projects: An economic and political analysis

    International Nuclear Information System (INIS)

    Ferrell, Shannon L.; DeVuyst, Eric A.

    2013-01-01

    Wind energy is the fastest-growing segment of new electrical power capacity in the United States, with the potential for significant growth in the future. To facilitate such growth, a number of concerns between developers and landowners must be resolved, including assurance of wind turbine decommissioning at the end of their useful lives. Oklahoma legislators enlisted the authors to develop an economically-sound proposal to ensure developers complete their decommissioning obligations. Economic analysis of turbine decommissioning is complicated by a lack of operational experience, as few U.S. projects have been decommissioned. This leads to a lack of data regarding decommissioning costs. Politically, the negotiation leading to the finally-enacted solution juxtaposed economic theory against political pragmatism, leading to a different but hopefully sound solution. This article will provide background for the decommissioning issue, chronicle the development of the decommissioning component of the Oklahoma Wind Energy Act, and frame issues that remain for policymakers in regulating wind power development. - Highlights: ► Wind energy is the fastest-growing component of U.S. power generation. ► Decommissioning wind projects is policy concern for wind development. ► Little public information on wind turbine decommissioning costs exists. ► Oklahoma’s solution attempts to account for both costs and risks. ► Additional research is needed to create a more precise policy solution.

  5. Current status of the KNPP units 1 to 4 decommissioning projects

    International Nuclear Information System (INIS)

    Benbow, R.

    2010-01-01

    The PMU has been established in support of the KNPP Decommissioning Division. All of the Infrastructure Projects associated with Decommissioning have been identified. All the major projects are either in Contract or have the Tender Packages prepared and are being managed/implemented through the EBRD Procurement Process. KNPP Decommissioning is being supported with the necessary documentation, tools and equipment

  6. Project No. 7 - Decommissioning unit at Ignalina NPP. (Engineering and project management)

    International Nuclear Information System (INIS)

    2000-01-01

    In order to manage decommissioning process at Ignalina NPP, a new unit should be established in the framework of the Ignalina NPP organizational structure. The on-site Engineering Project Management Unit (PMU) will adopt an integrated approach to project management , engineering design, planning, procurement, safety and licensing activities at Ignalina NPP site. The PMU will assist the Ignalina NPP management in the development of an integrated decommissioning and waste management strategy

  7. Development of decommissioning engineering support system (DEXUS) of the Fugen Nuclear Power Station

    International Nuclear Information System (INIS)

    Iguchi, Yukihiro; Kanehira, Yoshiki; Tochibana, Mitsuo

    2004-01-01

    The Fugen Nuclear Power Station (NPS) was shut down permanently in March 2003, and preparatory activities are underway to decommission the Fugen NPS. An engineering system to support the decommissioning is being developed to create a dismantling plan using state-of-art software such as 3-dimensional computer aided design (3D-CAD) and virtual reality (VR). In particular, an exposure dose evaluation system using VR has been developed and tested. The total system can be used to quantify radioactive waste, to visualize radioactive inventory, to simulate the dismantling plan, to evaluate workload in radiation environments and to optimize the decommissioning plan. The system will also be useful for educating and training workers and for gaining public acceptance. (author)

  8. Constructing Predictive Estimates for Worker Exposure to Radioactivity During Decommissioning: Analysis of Completed Decommissioning Projects - Master Thesis

    Energy Technology Data Exchange (ETDEWEB)

    Dettmers, Dana Lee; Eide, Steven Arvid

    2002-10-01

    An analysis of completed decommissioning projects is used to construct predictive estimates for worker exposure to radioactivity during decommissioning activities. The preferred organizational method for the completed decommissioning project data is to divide the data by type of facility, whether decommissioning was performed on part of the facility or the complete facility, and the level of radiation within the facility prior to decommissioning (low, medium, or high). Additional data analysis shows that there is not a downward trend in worker exposure data over time. Also, the use of a standard estimate for worker exposure to radioactivity may be a best estimate for low complete storage, high partial storage, and medium reactor facilities; a conservative estimate for some low level of facility radiation facilities (reactor complete, research complete, pits/ponds, other), medium partial process facilities, and high complete research facilities; and an underestimate for the remaining facilities. Limited data are available to compare different decommissioning alternatives, so the available data are reported and no conclusions can been drawn. It is recommended that all DOE sites and the NRC use a similar method to document worker hours, worker exposure to radiation (person-rem), and standard industrial accidents, injuries, and deaths for all completed decommissioning activities.

  9. Fort St. Vrain defueling ampersand decommissioning considerations

    International Nuclear Information System (INIS)

    Warembourg, D.

    1994-01-01

    Fort St. Vrain Nuclear Generating Station (FSV) is one of the first commercial reactors to be decommissioned under NRC's decommissioning rule. The defueling and decommissioning of this 330 MWe High Temperature Gas Cooled Reactor (HTGR) has involved many challenges for Public Service Company of Colorado (PSC) including defueling to an Independent Spent Fuel Storage Installation (ISFSI), establishing decommissioning funding, obtaining regulatory approvals, arranging for waste disposal, and managing a large fixed price decommissioning contract. In 1990, a team comprised of the Westinghouse Corporation and Morrison Knudsen Corporation, with the Scientific Ecology Group as a major subcontractor, was contracted by PSC to perform the decommissioning under a fixed price contract. Physical work activities began in August 1992. Currently, physical dismantlement activities are about 45% complete, the project is on schedule, and is within budget

  10. Current status of decommissioning projects and their strategies in advanced countries

    Energy Technology Data Exchange (ETDEWEB)

    Chung, U. S.; Lee, K. W.; Hwang, D. S.; Park, S. K.; Hwang, S. T.; Paik, S. T.; Park, J. H.; Choi, Y. D.; Chung, K. H.; Lee, K. I.; Hong, S. B

    2007-06-15

    At the Korea Atomic Energy Research Institute(KAERI), two projects for decommissioning of the research reactors and uranium conversion plant are carried out. The number of nuclear facilities to be dismantled will be much increased in future and the decommissioning industries will be enlarged. Keeping pace with this increasing tendency, each country formulated their own strategies and regulation systems, and applied their own technologies. The international organizations such as the IAEA and the OECD/NEA also prepared standards in technologies and regulation upon decommissioning and recommended to adopt them to the decommissioning projects. These strategies and technologies are very different country by country due to the different site dependent conditions and it will not be reasonable to evaluate their merits and weakness. The world wide status of the decommissioning, highlighted on that of 5 countries of USA, UK, France, Germany and Japan because they are advanced counties in nuclear industries, are summarized and their site specific conditions are evaluated. The scopes of the evaluation are decommissioning strategies, licensing procedures and requirements focused on decommissioning plan, waste management, technology development and so on. The detailed decommissioning progresses of several typical example sites were introduced. The activities on decommissioning field of the international organization, increased according to the enlarged decommissioning industries, are also summarized.

  11. Current status of decommissioning projects and their strategies in advanced countries

    International Nuclear Information System (INIS)

    Chung, U. S.; Lee, K. W.; Hwang, D. S.; Park, S. K.; Hwang, S. T.; Paik, S. T.; Park, J. H.; Choi, Y. D.; Chung, K. H.; Lee, K. I.; Hong, S. B.

    2007-06-01

    At the Korea Atomic Energy Research Institute(KAERI), two projects for decommissioning of the research reactors and uranium conversion plant are carried out. The number of nuclear facilities to be dismantled will be much increased in future and the decommissioning industries will be enlarged. Keeping pace with this increasing tendency, each country formulated their own strategies and regulation systems, and applied their own technologies. The international organizations such as the IAEA and the OECD/NEA also prepared standards in technologies and regulation upon decommissioning and recommended to adopt them to the decommissioning projects. These strategies and technologies are very different country by country due to the different site dependent conditions and it will not be reasonable to evaluate their merits and weakness. The world wide status of the decommissioning, highlighted on that of 5 countries of USA, UK, France, Germany and Japan because they are advanced counties in nuclear industries, are summarized and their site specific conditions are evaluated. The scopes of the evaluation are decommissioning strategies, licensing procedures and requirements focused on decommissioning plan, waste management, technology development and so on. The detailed decommissioning progresses of several typical example sites were introduced. The activities on decommissioning field of the international organization, increased according to the enlarged decommissioning industries, are also summarized

  12. Project Management Unit for decommissioning of NPP Bohunice VI (2003-2014)

    International Nuclear Information System (INIS)

    Gonzalez Fernandez-conde, A.; Brochet, I.; Ferreira, A.

    2015-01-01

    From October 2003 until december 2014 the Consortium consisting of Iberdrola Engineering and Construction (leader). Empresarios Agrupados Internacional, and Indra Sistemas has carried out the project Project Management Unit ((PMU) for the decommissioning of Bohunice V1 NPP (units 1 and 2), type VVER-440/V-230 in Slovakia. during the first phase (2003-2007) EdF was also part of the Consortium. The project is funded by the Bohunice International Decommissioning Support Fund (BIDSF) administered by the RBRD. The main objective of the project is to provide the necessary engineering and resources of project management for planning, execution, management, coordination and monitoring of all tasks in support of the decommissioning. (Author)

  13. Impact of metals recycling on a Swedish BWR decommissioning project

    International Nuclear Information System (INIS)

    Larsson, Arne; Lidar, Per; Hedin, Gunnar; Bergh, Niklas

    2014-01-01

    Decommissioning of nuclear power plants generates large volumes of radioactive or potentially contaminated metals. By proper management of the waste streams significant amounts can be free released and recycled either directly or after decontamination and melting. A significant part of the required work should be performed early in the process to make the project run smoothly without costly surprises and delays. A large portion of the clearance activities can be performed on-site. This on-site work should focus on the so called low-risk for contamination material. Other material can be decontaminated and released on site if schedule and the available facility areas so allow. It should be noted that the on-site decontamination and clearance activities can be a significant bottle neck for a decommissioning project. The availability of and access to a specialized metals recycling facility is an asset for a decommissioning project. This paper will describe the forecasted positive impact of a well-structured metals characterisation, categorisation and clearance process for a BWR plant decommissioning project. The paper is based on recent studies, performed projects and recent in-house development. (authors)

  14. Planning and progress of the WAGR decommissioning project

    International Nuclear Information System (INIS)

    Boorman, T.

    1988-01-01

    In the United Kingdom, the earliest production reactors, which will be decommissioned first, are of the Magnox type. The Windscale Advanced Gas-cooled Reactor, is however, sufficiently similar to make it a suitable prototype decommissioning project. The planning and progress so far is described. Special decommissioning equipment, including a remote dismantling machine, has been developed and a waste packaging building built on site. Its function is to enable all intermediate-level and low-level radioactive waste removed from the reactor vault by remote equipment to be packaged remotely into suitable containers. The work done on the WAGR decommissioning has shown that the dismantling of a power-producing reactor is feasible and can be accomplished using existing engineering techniques. (U.K.)

  15. Project management system for the decommissioning of research reactors

    International Nuclear Information System (INIS)

    Park, J. H.

    2006-01-01

    KAERI has developed a computer information system, named DECOMMIS, for the project management with the increased effectiveness of the decommissioning projects and the record keeping for a next decommissioning project. The management system consists of three parts, code management system, data input system (DDIS) and data processing and output system (DDPS). Through the DDIS, the data can be directly inputted at sites and the system can play roles of daily work reports to minimize the time gap between the dismantling activities and the evaluation of the data for project management. The DDPS provides useful information to the staff for more effective project management and this information include several fields, such as project progress management, man power management, waste management, radiation dose of workers and so on. It is expected that the system would enable to maintain the decommissioning data, to prepare the source data for the R and D for development of planning tools and to give information to the staff for the decision on the progress of the projects. In this paper, the overall system will be briefly explained and several examples of the utilization, focused on the waste and manpower control, for the project management will be introduced

  16. Worldwide Overview of Lessons Learned from Decommissioning Projects

    International Nuclear Information System (INIS)

    Laraia, Michele

    2008-01-01

    With an increasing number of radioactive facilities and reactors now reaching the end of their useful life and being taken out of service, there is a growing emphasis worldwide on the safe and efficient decommissioning of such plants. There is a wealth of experience already gained in decommissioning projects for all kinds of nuclear facilities. It is now possible to compare and discuss progress and accomplishments worldwide. In particular, rather than on the factual descriptions of projects, technologies and case histories, it is important to focus on lessons learned: in this way, the return of experience is felt to effectively contribute to progress. Key issues - inevitably based on a subjective ranking - are presented in this paper. Through the exchange of lessons learned, it is possible to achieve full awareness of the need for resources for and constraints of safe and cost-effective decommissioning. What remains now is the identification of specific, remaining issues that may hinder or delay the smooth progress of decommissioning. To this end, lessons learned provide the necessary background information; this paper tries to make extensive use of practical experience gained by the international community

  17. Technology, safety and costs of decommissioning a Reference Boiling Water Reactor Power Station. Main report. Volume 1

    Energy Technology Data Exchange (ETDEWEB)

    Oak, H.D.; Holter, G.M.; Kennedy, W.E. Jr.; Konzek, G.J.

    1980-06-01

    Technology, safety and cost information is given for the conceptual decommissioning of a large (1100MWe) boiling water reactor (BWR) power station. Three approaches to decommissioning, immediate dismantlement, safe storage with deferred dismantlement and entombment, were studied to obtain comparisons between costs, occupational radiation doses, potential dose to the public and other safety impacts. It also shows the sensitivity of decommissioning safety and costs to the power rating of a BWR in the range of 200 to 1100 MWe.

  18. In-house developed methodologies and tools for decommissioning projects

    International Nuclear Information System (INIS)

    Detilleux, Michel; Centner, Baudouin

    2007-01-01

    The paper describes different methodologies and tools developed in-house by Tractebel Engineering to facilitate the engineering works to be carried out especially in the frame of decommissioning projects. Three examples of tools with their corresponding results are presented: - The LLWAA-DECOM code, a software developed for the radiological characterization of contaminated systems and equipment. The code constitutes a specific module of more general software that was originally developed to characterize radioactive waste streams in order to be able to declare the radiological inventory of critical nuclides, in particular difficult-to-measure radionuclides, to the Authorities. In the case of LLWAA-DECOM, deposited activities inside contaminated equipment (piping, tanks, heat exchangers...) and scaling factors between nuclides, at any given time of the decommissioning time schedule, are calculated on the basis of physical characteristics of the systems and of operational parameters of the nuclear power plant. This methodology was applied to assess decommissioning costs of Belgian NPPs, to characterize the primary system of Trino NPP in Italy, to characterize the equipment of miscellaneous circuits of Ignalina NPP and of Kozloduy unit 1 and, to calculate remaining dose rates around equipment in the frame of the preparation of decommissioning activities; - The VISIMODELLER tool, a user friendly CAD interface developed to ease the introduction of lay-out areas in a software named VISIPLAN. VISIPLAN is a 3D dose rate assessment tool for ALARA work planning, developed by the Belgian Nuclear Research Centre SCK.CEN. Both softwares were used for projects such as the steam generators replacements in Belgian NPPs or the preparation of the decommissioning of units 1 and 2 of Kozloduy NPP; - The DBS software, a software developed to manage the different kinds of activities that are part of the general time schedule of a decommissioning project. For each activity, when relevant

  19. 233S Decommissioning Project Environmental Control Plan

    International Nuclear Information System (INIS)

    Zoric, J.P.

    2000-01-01

    This Environmental Control Plan is for the 233S Decommissioning activities conducted under the removal action report for the 233S Decontamination and Demolition Project. The purpose of this ECP is to identify environmental requirements for the 233S project. The ECP is a compilation of existing environmental permit conditions, regulatory requirements, and environmental requirements applicable to the specific project or functional activity

  20. Idea: an integrated set of tools for sustainable nuclear decommissioning projects

    International Nuclear Information System (INIS)

    Detilleux, M.; Centner, B.; Vanderperre, S.; Wacquier, W.

    2008-01-01

    Decommissioning of nuclear installations constitutes an important challenge and shall prove to the public that the whole nuclear life cycle is fully mastered by the nuclear industry. This could lead to an easier public acceptance of the construction of new nuclear power plants. When ceasing operation, nuclear installations owners and operators are looking for solutions in order to assess and keep decommissioning costs at a reasonable level, to fully characterise waste streams (in particular radiological inventories of difficult-to-measure radionuclides) and to reduce personnel exposure during the decommissioning activities taking into account several project, site and country specific constraints. In response to this need, Tractebel Engineering has developed IDEA (Integrated DEcommissioning Application), an integrated set of computer tools, to support the engineering activities to be carried out in the frame of a decommissioning project. IDEA provides optimized solutions from an economical, environmental, social and safety perspective. (authors)

  1. Expansive development of a decommissioning program 'recycle simulator' in nuclear power station

    International Nuclear Information System (INIS)

    Nishiuchi, T.; Ozaki, S.; Hironaga, M.

    2004-01-01

    A decommissioning program 'Recycle Simulator' should be put into practice in careful consideration of both recycle of non-radioactive wastes and reduce of radioactive wastes in the coming circulatory social system. Nevertheless current support systems for decommissioning planning mainly deal with decontamination, safety storage and dismantlement, so-called the prior part of the total decommissioning process. Authors emphasize the necessity of total planning of decommissioning including recycle or reuse of a large amount of demolition materials and are propelling the development of the multi expert system named 'Recycle Simulator'. This paper presents an algorithm of the recycling and reusing scenario of demolition materials and a summarized configuration. 'Recycle Simulator' for the demolished concrete was developed in 2000 and presented at a previous International Conference on Nuclear Engineering. Construction of a supporting multi expert system for the totally planning of decommissioning projects is objected by expansive development of the previous version. 3 main conclusions obtained from this paper are the following. (1) The previously developed expert system was advanced in its estimation function toward the satisfaction of decommissioning planners. (2) The applicability of the system was enlarged to all the radioactive and non-radioactive wastes, demolished metal and concrete products, in a corresponding site of decommissioning. (3) Finally decommissioning recycle simulator was completed in a harmonized unification. (authors)

  2. Status of the Decommissioning Project Management Information System Development of KAERI in 2015

    International Nuclear Information System (INIS)

    Jin, Hyung Gon; Park, Seungkook; Park, Heeseong; Song, Chanho

    2015-01-01

    Various information systems have been developed and used at decommissioning sites for planning a project, record keeping for a post management and cost estimation. KAERI is the only one expert group which has decommissioning experiences and KAERI is trying to develop computer code to converge all the data which has been accumulated during KRR-1 and 2 and UCP (Uranium Conversion Plant) decommission. KRR-1 and KRR-2 are TRIGA MARK type of research reactor which were constructed worldwide. Hence, there are many chance to use decommissioning experiences and data when other TRIGA MARK type of research reactors start to decommission. KAERI DPMIS stands for Decommissioning Project Management Information System, which is aiming to re-use of data effectively. As a responsible leading group of Korean decommissioning research field, KAERI has been developing DPMIS application program, which is going to be an important mile stone of decommission industry in Korea. User friendly graphical interface and lots of actual data let people well understood on decommission planning. It is expected that continuous effort and funds will be delivered to this research

  3. Status of the Decommissioning Project Management Information System Development of KAERI in 2015

    Energy Technology Data Exchange (ETDEWEB)

    Jin, Hyung Gon; Park, Seungkook; Park, Heeseong; Song, Chanho [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2015-10-15

    Various information systems have been developed and used at decommissioning sites for planning a project, record keeping for a post management and cost estimation. KAERI is the only one expert group which has decommissioning experiences and KAERI is trying to develop computer code to converge all the data which has been accumulated during KRR-1 and 2 and UCP (Uranium Conversion Plant) decommission. KRR-1 and KRR-2 are TRIGA MARK type of research reactor which were constructed worldwide. Hence, there are many chance to use decommissioning experiences and data when other TRIGA MARK type of research reactors start to decommission. KAERI DPMIS stands for Decommissioning Project Management Information System, which is aiming to re-use of data effectively. As a responsible leading group of Korean decommissioning research field, KAERI has been developing DPMIS application program, which is going to be an important mile stone of decommission industry in Korea. User friendly graphical interface and lots of actual data let people well understood on decommission planning. It is expected that continuous effort and funds will be delivered to this research.

  4. Evaluation of nuclear facility decommissioning projects. Status report. Humboldt Bay Power Plant Unit 3, SAFSTOR decommissioning

    International Nuclear Information System (INIS)

    Baumann, B.L.; Haffner, D.R.; Miller, R.L.; Scotti, K.S.

    1986-06-01

    This document explains the purpose of the US Nuclear Regulatory Commission's (NRC) Evaluation of Nuclear Facility Decommissioning Projects (ENFDP) program and summarizes information concerning the decommissioning of the Humboldt Bay Power Plant (HBPP) Unit 3 facility. Preparations to put this facility into a custodial safe storage (SAFSTOR) mode are currently scheduled for completion by June 30, 1986. This report gives the status of activities as of June 1985. A final summary report will be issued after completion of this SAFSTOR decommissioning activity. Information included in this status report has been collected from the facility decommissioning plan, environmental report, and other sources made available by the licensee. This data has been placed in a computerized data base system which permits data manipulation and summarization. A description of the computer reports that can be generated by the decommissioning data system (DDS) for Humboldt Bay and samples of those reports are included in this document

  5. Efforts to perform safe and efficient decommissioning for Tsuruga Power Station Unit 1

    International Nuclear Information System (INIS)

    Saito, Shiro; Yamauchi, Toyoaki; Austin, Colin R.

    2017-01-01

    Tsuruga Power Station Unit-1 (Tsuruga-1) started commercial operation in March 1970, and the decision to terminate operation was made in 2015. In April 2016, JAPC signed an agreement with Energy Solutions (ES) on strategic cooperation for domestic D and D projects for introduction of successful international experiences. As a first step in this cooperation, D and D know-how developed by ES in the US is being applied to Tsuruga-1 with verifying its applicability to domestic D and D projects. One of the efforts is human resource development. JAPC has also started introduction of ES's project management method to the Tsuruga-1 project for solid project management and the base line is currently being prepared. Regarding the waste disposal paths, application document of approval for measurement and evaluation of clearance material was submitted in September 2016. However the disposal paths for waste are not established in Japan. It is necessary to cooperate with the government, utilities and local stakeholders to establish waste disposal paths. Because it is also important to obtain the understanding from local communities, JAPC and ES will try positively to utilize local companies for D and D works. JAPC and ES believe that their relationship will ensure success of the Tsuruga-1 NPP decommissioning project. (author)

  6. Hinkley Point 'C' power station public inquiry: proof of evidence on on-site radioactive waste management and decommissioning

    International Nuclear Information System (INIS)

    Passant, F.H.

    1988-09-01

    A public inquiry has been set up to examine the planning application made by the Central Electricity Generating Board (CEGB) for the construction of a 1200 MW Pressurized Water Reactor power station at Hinkley Point (Hinkley Point ''C'') in the United Kingdom. The CEGB evidence to the Inquiry presented here provides information on the on-site management of solid, liquid and gaseous radioactive wastes both during station operation and during decommissioning. Estimates are given of current and projected future discharges of liquid and gaseous wastes from the site and packaging and transport arrangements for solid radioactive wastes are described. The framework of waste management policy, disposal strategy and legislation in the United Kingdom which will determine procedure at Hinkley Point ''C'' is given. (UK)

  7. SGN's Dismantling and Decommissioning engineering, projects experience and capabilities

    International Nuclear Information System (INIS)

    Destrait, L.

    1998-01-01

    Its experience in waste treatment, conditioning, storage and disposal, its cooperation with CEA and COGEMA Group in license agreements give SGN expertise in the decommissioning field. SGN's experience and background in all areas of nuclear facility decommissioning, such as chemical and mechanical cells, nuclear advanced reactors, reprocessing facilities result in fruitful references to the customers. The poster is presenting different achievements and projects with SGN's participation such as: - The decommissioning of Windscale Advanced Gas cooled Reactors (WAGR), in particular providing methodology and equipment to dismantle the Pressure and Insulation Vessel of the reactor. - The decommissioning plan of Ignalina (Lithuania) and Paldiski (Estonia), defining strategies, scenarios, necessary equipments and tools and choosing the best solutions to decommission the site under different influencing parameters such as cost, dose rate exposure, etc... - Th One Site Assistance Team (OSAT) at Chernobyl regarding the preparation works for the waste management and decommissioning of the plant. - The decommissioning of French nuclear facilities such as reprocessing (UP1) and reactor (EL4) plants. The important experience acquired during the facility management and during the first dismantling and decommissioning operations is an important factor for the smooth running of these techniques for the future. The challenge to come is to control all the operations, the choice of strategies, the waste management, the efficiency of tools and equipments, and to provide nuclear operators with a full range of proven techniques to optimise costs and minimize decommissioning personnel exposure. (Author)

  8. Reactor vessel decommissioning project. Final report

    International Nuclear Information System (INIS)

    Schoonen, D.H.

    1984-09-01

    This report describes a reactor vessel decommissioning project; it documents and explains the project objectives, scope, performance results, and sodium removal process. The project was successfully completed in FY-1983, within budget and without significant problems or adverse impact on the environment. Waste generated by the operation included the reactor vessel, drained sodium, and liquid, solid, and gaseous wastes which were significantly less than project estimates. Personnel radiation exposures were minimized, such that the project total was one-half the predicted exposure level. Except for the sodium removed, the material remaining in the reactor vessel is essentially the same as when the vessel arrived for processing

  9. Decommissioning Handbook

    International Nuclear Information System (INIS)

    Cusack, J.G.; Dalfonso, P.H.; Lenyk, R.G.

    1994-01-01

    The Decommissioning Handbook provides technical guidance on conducting decommissioning projects. Information presented ranges from planning logic, regulations affecting decommissioning, technology discussion, health and safety requirements, an developing a cost estimate. The major focus of the handbook are the technologies -- decontamination technologies, waste treatment, dismantling/segmenting/demolition, and remote operations. Over 90 technologies are discussed in the handbook providing descriptions, applications, and advantages/disadvantages. The handbook was prepared to provide a compendium of available or potentially available technologies in order to aid the planner in meeting the specific needs of each decommissioning project. Other subjects presented in the Decommissioning Handbook include the decommissioning plan, characterization, final project configuration based planning, environmental protection, and packaging/transportation. These discussions are presented to complement the technologies presented in the handbook

  10. Technology, safety and costs of decommissioning a reference pressurized water reactor power station. Classification of decommissioning wastes. Addendum 3

    International Nuclear Information System (INIS)

    Murphy, E.S.

    1984-09-01

    The radioactive wastes expected to result from decommissioning of the reference pressurized water reactor power station are reviewed and classified in accordance with 10 CFR 61. The 17,885 cubic meters of waste from DECON are classified as follows: Class A, 98.0%; Class B, 1.2%; Class C, 0.1%. About 0.7% (133 cubic meters) of the waste would be generally unacceptable for disposal using near-surface disposal methods

  11. Regulatory Framework for Controlling the Research Reactor Decommissioning Project

    International Nuclear Information System (INIS)

    Melani, Ai; Chang, Soon Heung

    2009-01-01

    Decommissioning is one of important stages in construction and operation of research reactors. Currently, there are three research reactors operating in Indonesia. These reactors are operated by the National Nuclear Energy Agency (BATAN). The age of the three research reactors varies from 22 to 45 years since the reactors reached their first criticality. Regulatory control of the three reactors is conducted by the Nuclear Energy Regulatory Agency (BAPETEN). Controlling the reactors is carried out based on the Act No. 10/1997 on Nuclear Energy, Government Regulations and BAPETEN Chairman Decrees concerning the nuclear safety, security and safeguards. Nevertheless, BAPETEN still lack of the regulation, especially for controlling the decommissioning project. Therefore, in the near future BAPETEN has to prepare the regulations for decommissioning, particularly to anticipate the decommissioning of the oldest research reactors, which probably will be done in the next ten years. In this papers author give a list of regulations should be prepared by BAPETEN for the decommissioning stage of research reactor in Indonesia based on the international regulatory practice

  12. Shippingport: Overall project progress

    International Nuclear Information System (INIS)

    Crimi, F.P.

    1989-01-01

    The Shippingport atomic power station (SAPS) consisted of the nuclear steam supply system and associated radioactive waste processing systems, which were owned by the US Department of Energy (DOE), and the balance of plant, owned by the Duquesne Light Company. The station is located at Shippingport, Pennsylvania, on 7 acres of land leased by DOE from Duquesne Light Company. The Shippingport Station Decommissioning Project (SSDP) is being performed under contract to the DOE by the General Electric Company (GE) and its preselected subcontractor, MK-Ferguson Company, as the decommissioning operations contractor (DOC). This paper describes the decommissioning work that has been accomplished since July 1988, and the project's cost and schedule status. As the first decommissioning of a commercial, full-scale nuclear power plant, the SSDP is expected to set the standards for the demolition of future nuclear power plants

  13. The waste management implications of decommissioning

    International Nuclear Information System (INIS)

    Passant, F.H.

    1988-01-01

    Decommissioning policy can only be framed in the light of radioactive waste management policy. What can be done with the waste materials, how and when, will determine the overall decommissioning plans and costs. In this paper the waste management options and their costs are reviewed for the decommissioning of the Central Electricity Generating Boards civil nuclear power stations. The paper concentrates on the decommissioning of Magnox stations, although comparative information on waste volumes and costs are given for the AGR programme and a typical PWR. (author)

  14. Development of decommissioning technologies in Sumitomo Mitsui Construction Co., Ltd

    International Nuclear Information System (INIS)

    Maruyama, Shinichiro; Suzuki, Toru; Ogane, Daisuke

    2011-01-01

    The decommissioning program of nuclear reactors in Japan first started in December 2001 on the Japan's first commercial nuclear power station Tokai Power Plant. In February 2008, the decommissioning of 'Fugen' was first approved as the program on a large-scale water reactor in Japan, and was started. From now on, decommissioning programs of LWRs constructed in the early stage of nuclear development will gradually increase. Decommissioning projects are required more than 20 years for completing the entire processes, because of its characteristics to placing the utmost priority to safety. Diverse types of element technologies are fully utilized in decommissioning projects, such as technology of evaluating remaining radioactivity, decontamination, dismantling/remote control, and treatment/disposal/recycling. Also there are a lot of civil engineering or building technologies and its applied technologies in these element technologies. Sumitomo Mitsui Construction Co., Ltd. has been committed to contributing to the promotion of decommissioning projects in Japan, and has carried out investigation/evaluation of applicability of the existing dismantling technologies to dismantling of reactors, seismic evaluation of the buildings for dismantling the reactor zone, development of recycling of concrete, and discussion of rational waste treatment/disposal methods. In this thesis, we present our decommissioning technologies focusing on the element technologies that our company has investigated and developed so far. (author)

  15. Financial aspects of decommissioning (key aspects of decommissioning costing)

    International Nuclear Information System (INIS)

    Danska, V.

    2009-01-01

    In this presentation the following aspects of NPPs decommissioning are discussed: Requirements and purpose of decommissioning costing; Decommissioning costing methodologies; Standardised decommissioning cost structure; Input data for cost estimate process; Waste management in cost estimate process; Grading aspects in cost estimating; Cost control in decommissioning projects; Summary of the cost estimation process; Conclusions and recommendations.

  16. Die Energiewerke Nord GmbH. From operator of a decommissioned Russian nuclear power plant to one of Europe's leading decommissioning companies

    International Nuclear Information System (INIS)

    Philipp, Marlies

    2011-01-01

    EWN GmbH is a state-owned company with these duties: - decommissioning and demolition of the Greifswald and Rheinsberg nuclear power stations; - safe operation of the Zwischenlager Nord interim store; - development of the 'Lubminer Heide' industrial and commercial estate. Other projects for which EWN GmbH uses its know-how: - disposal of 120 decommissioned Russian nuclear submarines in Murmansk; - decommissioning and dismantling of the Juelich, NRW, AVR experimental reactor; - demolition of nuclear plants; running the Central Decontamination Operations Department at Karlsruhe, BW. Since 2008, EWN GmbH has held 25% of the shares of Deutsche Gesellschaft zum Bau- und Betrieb von Endlagern fuer Abfallstoffe mbH (DBE), a firm building and operating nuclear repositories. (orig.)

  17. Decommissioning of nuclear power plants

    International Nuclear Information System (INIS)

    Friske, A.; Thiele, D.

    1988-01-01

    The IAEA classification of decommissioning stages is outlined. The international development hitherto observed in decommissioning of nuclear reactors and nuclear power stations is presented. The dismantling, cutting and decontamination methods used in the decommissioning process are mentioned. The radioactive wastes from decommissioning are characterized, the state of the art of their treatment and disposal is given. The radiation burdens and the decommissioning cost in a decommissioning process are estimated. Finally, some evaluation of the trends in the decommissioning process of nuclear power plants is given. 54 refs. (author)

  18. A Quality Assurance Program for decommissioning

    International Nuclear Information System (INIS)

    Briggs, P.M.

    1986-01-01

    Defining the Quality Assurance Program for the US Department of Energy Shippingport Station Decommissioning Project (SSDP) was a unique opportunity because this is the first full-sized commercial nuclear power plant to be decommissioned. General Electric Company defined a Quality Assurance Program that provided adequate control, yet was stripped down to the essentials. The Program is designed to provide a flexible degree of monitoring of subcontractor work, built around a core of radiation safety monitoring, detailed planning, inspection and auditing, and operated with a minimum of dedicated personnel. This paper will concentrate on the traditional quality assurance activities, leaving radiation and environmental monitoring for other presentations

  19. Decommissioning Work Modeling System for Nuclear Facility Decommissioning Design

    International Nuclear Information System (INIS)

    Park, S. K.; Cho, W. H.; Choi, Y. D.; Moon, J. K.

    2012-01-01

    During the decommissioning activities of the KRR-1 and 2 (Korea Research Reactor 1 and 2) and UCP (Uranium Conversion Plant), all information and data, which generated from the decommissioning project, were record, input and managed at the DECOMMIS (DECOMMissioning Information management System). This system was developed for the inputting and management of the data and information of the man-power consumption, operation time of the dismantling equipment, the activities of the radiation control, dismantled waste management and Q/A activities. When a decommissioning is planed for a nuclear facility, an investigation into the characterization of the nuclear facility is first required. The results of such an investigation are used for calculating the quantities of dismantled waste volume and estimating the cost of the decommissioning project. That is why, the DEFACS (DEcommissioning FAcility Characterization DB System) was established for the management of the facility characterization data. The DEWOCS (DEcommissioning WOrk-unit productivity Calculation System) was developed for the calculation of the workability on the decommissioning activities. The work-unit productivities are calculated through this system using the data from the two systems, DECOMMIS and DEFACS. This result, the factors of the decommissioning work-unit productivities, will be useful for the other nuclear facility decommissioning planning and engineering. For this, to set up the items and plan for the decommissioning of the new objective facility, the DEMOS (DEcommissioning work Modeling System) was developed. This system is for the evaluation the cost, man-power consumption of workers and project staffs and technology application time. The factor of the work-unit productivities from the DEWOCS and governmental labor cost DB and equipment rental fee DB were used for the calculation the result of the DEMOS. And also, for the total system, DES (Decommissioning Engineering System), which is now

  20. Social effects of decommissioning Trawsfynydd Power Station

    International Nuclear Information System (INIS)

    Jones, H.

    2001-01-01

    The decision to close Trawsfynydd in 1993 had significant implications for the staff and local community. The site is situated within a National Park and local employment opportunities are limited. The staff and local communities were consulted regarding the issues arising from closure and decommissioning. This consultation influenced the decommissioning strategy for the site, with emphasis placed on the mitigation of the effects of closure. Subsequent studies have shown that the adopted strategies have served to limit the social and economic effects. The experience at Trawsfynydd has proved to be generally applicable at other decommissioning sites. (author)

  1. Human resource development for decommissioning

    International Nuclear Information System (INIS)

    Yanagihara, Satoshi

    2016-01-01

    This paper summarized the features of decommissioning work and the methods how to develop human resources. The general flow of decommissioning includes the following steps: (1) evaluation of facility characteristics, (2) planning, (3) decontamination and disassembly of equipment and structures contaminated with radioactivity, (4) radioactivity measurement, (5) treatment and disposal of radioactive waste, and (6) release from legal restrictions (termination of decommissioning). For this purpose, techniques in various fields are required. In the evaluation of facility characteristics, radiation measurement and calculation of activation amount in the core part are required. In decontamination and dismantling, cutting technology (mechanical cutting, thermal cutting, etc.), decontamination technology, and remote control technology are required. In the nuclear power education in the past, the fields related to design, construction, operation, and maintenance among the plant life cycle were the main parts. Much attention was not payed to decommissioning and the treatment/disposal of radioactive waste in the second half of life cycle. As university education, Hokkaido University and Fukui University have lectures on decommissioning. Furthermore, the education and research for students are proceeding at seven universities, with a focus on common reactors including those of Fukushima Daiichi Power Station. It is a key for promoting decommissioning, to incorporate project management, risk analysis, cost evaluation, and decision making into education, and to foster human resources heading toward challenging problems including social problems. (A.O.)

  2. Collection and sharing of data and experience from EC-funded decommissioning projects

    International Nuclear Information System (INIS)

    Pflugrad, K.; Colquhoun, A.P.; Schreck, G.; Huske, M.; Petrasch, P.; Tuenckens, L.R.J.

    1999-01-01

    The European Commission's Fourth Framework Programme (1994-1998) on Nuclear Fission Safety includes the funding of projects relevant to the decommissioning of nuclear installations. The objectives of the programme for decommissioning are to continue the development of technology (a) to collect and analyse relevant data (b) to test and evaluate strategies and techniques and to stimulate the exchange of information and experience. Objective (b) involves related projects aimed at collecting and analysing data from past, current and future EC programmes and making them understandable and readily available in databases as well as studying how these and other databases might be integrated in a decommissioning strategic planning tool (SPT). This aims to assist EU organizations in making strategic choices for optimizing decommissioning programmes. This paper gives an update on database work, a progress report on the development of an EU access network and work on the standardization of cost item definitions. Progress on the SPT study is reviewed. (author)

  3. Progress in Decommissioning the Humboldt Bay Power Plant - 13604

    Energy Technology Data Exchange (ETDEWEB)

    Rod, Kerry [PG and E Utility, Humboldt Bay Power Plant, 1000 King Salmon Ave. Eureka, CA 95503 (United States); Shelanskey, Steven K. [Anata Management Solutions, 5180 South Commerce Dr,, Suite F Murray, UT 84107 (United States); Kristofzski, John [CH2MHILL, 295 Bradley Blvd. Suite 300, Richland WA 99353 (United States)

    2013-07-01

    Decommissioning of the Pacific Gas and Electric (PG and E) Company Humboldt Bay Power Plant (HBPP) Unit 3 nuclear facility has now, after more than three decades of SAFSTOR and initial decommissioning work, transitioned to full-scale decommissioning. Decommissioning activities to date have been well orchestrated and executed in spite of an extremely small work site with space constricted even more by other concurrent on-site major construction projects including the demolition of four fossil units, construction of a new generating station and 60 KV switchyard upgrade. Full-scale decommissioning activities - now transitioning from Plant Systems Removal (PG and E self-perform) to Civil Works Projects (contractor performed) - are proceeding in a safe, timely, and cost effective manner. As a result of the successful decommissioning work to date (approximately fifty percent completed) and the intense planning and preparations for the remaining work, there is a high level of confidence for completion of all HBPP Unit 3 decommissions activities in 2018. Strategic planning and preparations to transition into full-scale decommissioning was carried out in 2008 by a small, highly focused project team. This planning was conducted concurrent with other critical planning requirements such as the loading of spent nuclear fuel into dry storage at the Independent Spent Fuel Storage Installation (ISFSI) finishing December 2008. Over the past four years, 2009 through 2012, the majority of decommissioning work has been installation of site infrastructure and removal of systems and components, known as the Plant System Removal Phase, where work scope was dynamic with significant uncertainty, and it was self-performed by PG and E. As HBPP Decommissioning transitions from the Plant System Removal Phase to the Civil Works Projects Phase, where work scope is well defined, a contracting plan similar to that used for Fossil Decommissioning will be implemented. Award of five major work scopes

  4. Progress in Decommissioning the Humboldt Bay Power Plant - 13604

    International Nuclear Information System (INIS)

    Rod, Kerry; Shelanskey, Steven K.; Kristofzski, John

    2013-01-01

    Decommissioning of the Pacific Gas and Electric (PG and E) Company Humboldt Bay Power Plant (HBPP) Unit 3 nuclear facility has now, after more than three decades of SAFSTOR and initial decommissioning work, transitioned to full-scale decommissioning. Decommissioning activities to date have been well orchestrated and executed in spite of an extremely small work site with space constricted even more by other concurrent on-site major construction projects including the demolition of four fossil units, construction of a new generating station and 60 KV switchyard upgrade. Full-scale decommissioning activities - now transitioning from Plant Systems Removal (PG and E self-perform) to Civil Works Projects (contractor performed) - are proceeding in a safe, timely, and cost effective manner. As a result of the successful decommissioning work to date (approximately fifty percent completed) and the intense planning and preparations for the remaining work, there is a high level of confidence for completion of all HBPP Unit 3 decommissions activities in 2018. Strategic planning and preparations to transition into full-scale decommissioning was carried out in 2008 by a small, highly focused project team. This planning was conducted concurrent with other critical planning requirements such as the loading of spent nuclear fuel into dry storage at the Independent Spent Fuel Storage Installation (ISFSI) finishing December 2008. Over the past four years, 2009 through 2012, the majority of decommissioning work has been installation of site infrastructure and removal of systems and components, known as the Plant System Removal Phase, where work scope was dynamic with significant uncertainty, and it was self-performed by PG and E. As HBPP Decommissioning transitions from the Plant System Removal Phase to the Civil Works Projects Phase, where work scope is well defined, a contracting plan similar to that used for Fossil Decommissioning will be implemented. Award of five major work scopes

  5. Proven approaches to organise a large decommissioning project, including the management of local stakeholder interests

    International Nuclear Information System (INIS)

    Rodriguez, A.

    2005-01-01

    Full text: Spanish experience holds a relatively important position in the field of the decommissioning of nuclear and radioactive facilities. Decommissioning projects of uranium concentrate mill facilities are near completion; some old uranium mine sites have already been restored; several projects for the dismantling of various small research nuclear reactors and a few pilot plants are at various phases of the dismantling process, with some already completed. The most notable Spanish project in this field is undoubtedly the decommissioning of the Vandellos 1 nuclear power plant that is currently ready to enter a safe enclosure, or dormancy, period. The management of radioactive wastes in Spain is undertaken by 'Empresa Nacional de Residuos Radioactivos, S.A.' (ENRESA), the Spanish national radioactive waste company, constituted in 1984. ENRESA operates as a management company, whose role is to develop radioactive waste management programmes in accordance with the policy and strategy approved by the Spanish Government. Its responsibilities include the decommissioning and dismantling of nuclear installations. Decommissioning and dismantling nuclear installations is an increasingly important topic for governments, regulators, industries and civil society. There are many aspects that have to be carefully considered, planned and organised in many cases well in advance of when they really need to be implemented. The goal of this paper is describe proven approaches relevant to organizing and managing large decommissioning projects, in particular in the case of Vandellos-1 NPP decommissioning. (author)

  6. The Windscale Advanced Gas Cooled Reactor (WAGR) Decommissioning Project A Close Out Report for WAGR Decommissioning Campaigns 1 to 10 - 12474

    Energy Technology Data Exchange (ETDEWEB)

    Halliwell, Chris [Sellafield Ltd, Sellafield (United Kingdom)

    2012-07-01

    The reactor core of the Windscale Advanced Gas-Cooled Reactor (WAGR) has been dismantled as part of an ongoing decommissioning project. The WAGR operated until 1981 as a development reactor for the British Commercial Advanced Gas cooled Reactor (CAGR) power programme. Decommissioning began in 1982 with the removal of fuel from the reactor core which was completed in 1983. Subsequently, a significant amount of engineering work was carried out, including removal of equipment external to the reactor and initial manual dismantling operations at the top of the reactor, in preparation for the removal of the reactor core itself. Modification of the facility structure and construction of the waste packaging plant served to provide a waste route for the reactor components. The reactor core was dismantled on a 'top-down' basis in a series of 'campaigns' related to discrete reactor components. This report describes the facility, the modifications undertaken to facilitate its decommissioning and the strategies employed to recognise the successful decommissioning of the reactor. Early decommissioning tasks at the top of the reactor were undertaken manually but the main of the decommissioning tasks were carried remotely, with deployment systems comprising of little more than crane like devices, intelligently interfaced into the existing structure. The tooling deployed from the 3 tonne capacity (3te) hoist consisted either purely mechanical devices or those being electrically controlled from a 'push-button' panel positioned at the operator control stations, there was no degree of autonomy in the 3te hoist or any of the tools deployed from it. Whilst the ATC was able to provide some tele-robotic capabilities these were very limited and required a good degree of driver input which due to the operating philosophy at WAGR was not utilised. The WAGR box proved a successful waste package, adaptable through the use of waste box furniture specific to the

  7. Decommissioning of NPP A-1

    International Nuclear Information System (INIS)

    Anon

    2009-01-01

    In this presentation the Operation history of A1 NPP, Project 'Decommissioning of A1 NPP' - I stage, Project 'Decommissioning of A1 NPP ' - II stage and Next stages of Project 'Decommissioning of A1 NPP ' are discussed.

  8. Decommissioning of the research nuclear reactor WWR-S Magurele - Bucharest. General presentation of the project

    International Nuclear Information System (INIS)

    Dragulescu, Emilian; Dragusin, Mitica; Popa, Victor; Boicu, Alin; Tuca, Carmen; Iorga, Ioan; Vrabie, Ionut; Mustata, Carmen

    2003-01-01

    A decommissioning project was worked out concerning the nuclear facility research reactor WWR-S Magurele-Bucharest to remove the radioactive and hazardous materials and so to exclude any risk for human health and environment. The project involves the four phases named assessment, development, operations and closeout. There are two major parts to the assesment phase: preliminary characterisation and the review and decision-making process. Characterisation is needed to develop project baseline data, which should include sufficient chemical, physical, and radiological characterisation to meet planning needs. Based on the conclusions of these studies, possible decommissioning alternative will be analyzed and: the best alternative chosen, final goal identified, risk assessments are evaluated. Also, taken into account are: regulations supporting assessment, land use considerations, financial concerns, disposal availability, public involvement, technology developments. After a decommissioning alternative was chosen, detailed engineering will begin following appropriate regulatory guidance. The plan will include characterisation information, namely: review of decommissioning alternatives; justification for the selected alternative; provision for regulatory compliance; predictions of personnel exposure, radioactive waste volume, and cost. Other activities are: scheduling, preparation for decommissioning operations; coordination, documentation, characterization report, feasibility studies, Decommissioning Plan, project daily report, radiological survey, airborne sampling records, termination survey of the site. The operations imply: identification and sequencing the operations on contaminated materials, storing on site the wastes, awaiting processing or disposal, and packaging of materials for transport to processing or disposal facilities.The key operations are: worker protection, health and safety program, review of planing work, work area assessment, work area controls

  9. The curious accountancy of decommissioning

    International Nuclear Information System (INIS)

    Anon.

    1990-01-01

    Financial provision for the decommissioning and waste management of the United Kingdom Magnox and AGR reactor is discussed. In the last set of accounts prior to privatisation a decommissioning provision of Pound 8.34 bn was indicated whereas previous figures had only shown Pound 2.88. It is suggested that the increase was only achieved on paper, without real financial provision. Estimates of decommissioning costs for the Magnox stations have increased greatly. Cost estimates for AGR decommissioning have still to be released but it is expected that the post-privatisation owners of the nuclear power industry, Nuclear Electric, will have to find Pound 6-7 bn to dismantle its own reactors. Much of this it hopes to put off for over 100 years. The South of Scotland Electicity Board has made much more realistic provision for its own Magnox and two AGR stations. Reprocessing costs for AGR reactor fuel is uncertain and high reprocessing and decommissioning costs will mean increases in the price of nuclear electricity. (UK)

  10. Final project report: TA-35 Los Alamos Power Reactor Experiment No. II (LAPRE II) decommissioning project

    International Nuclear Information System (INIS)

    Montoya, G.M.

    1993-02-01

    This final report addresses the decommissioning of the LAPRE II Reactor, safety enclosure, fuel reservoir tanks, emergency fuel recovery system, primary pump pit, secondary loop, associated piping, and the post-remediation activities. Post-remedial action measurements are also included. The cost of the project including, Phase I assessment and Phase II remediation was approximately $496K. The decommissioning operation produced 533 M 3 of mixed waste

  11. Strategically oriented project management of the decommissioning of nuclear power plants

    International Nuclear Information System (INIS)

    Kemmeter, Sascha; Woempener, Andreas

    2013-01-01

    Due to the politically induced change of the energy sector in Germany, the operators of nuclear power plants had to react and to deal with completely new conditions concerning the decommissioning of their plants on short notice. Therefore the operators have to devise new strategies for controlling their decommissioning and dismantling projects in a short amount of time and most often similarly for several plants. Two fundamental procedures are possible for the successful controlling of these dismantling projects: a centralized or a decentralized management organization. How these project control processes can be realized in an optimal way, is, next to other economic specifications of the dismantling of nuclear power plants, the topic of a new research project of the Chair of Management Accounting at the University Duisburg-Essen. In that process, results and experiences from other research and practical projects concerning general large-scale projects are being used. Selected findings have been compiled and are being discussed in this paper. (orig.)

  12. Decommissioning Handbook

    Energy Technology Data Exchange (ETDEWEB)

    1994-03-01

    The Decommissioning Handbook is a technical guide for the decommissioning of nuclear facilities. The decommissioning of a nuclear facility involves the removal of the radioactive and, for practical reasons, hazardous materials to enable the facility to be released and not represent a further risk to human health and the environment. This handbook identifies and technologies and techniques that will accomplish these objectives. The emphasis in this handbook is on characterization; waste treatment; decontamination; dismantling, segmenting, demolition; and remote technologies. Other aspects that are discussed in some detail include the regulations governing decommissioning, worker and environmental protection, and packaging and transportation of the waste materials. The handbook describes in general terms the overall decommissioning project, including planning, cost estimating, and operating practices that would ease preparation of the Decommissioning Plan and the decommissioning itself. The reader is referred to other documents for more detailed information. This Decommissioning Handbook has been prepared by Enserch Environmental Corporation for the US Department of Energy and is a complete restructuring of the original handbook developed in 1980 by Nuclear Energy Services. The significant changes between the two documents are the addition of current and the deletion of obsolete technologies and the addition of chapters on project planning and the Decommissioning Plan, regulatory requirements, characterization, remote technology, and packaging and transportation of the waste materials.

  13. The decommissioning of WWER type nuclear power plants. Final report on an IAEA regional technical co-operation project

    International Nuclear Information System (INIS)

    2000-01-01

    Numerous WWER-440 nuclear power plants are in operation in central and eastern Europe and a small number have already been shut down. In addition to reactors already shut down, many other reactors will reach the end of their design lifetime in a few years and become candidates for decommissioning. It is unfortunate that little consideration was devoted to decommissioning of WWER-440 reactors at the plant design and construction stage, and little emphasis was placed on planning for decommissioning. It is within this context that the IAEA launched a regional technical co-operation project in 1994 with the aim of providing guidance on planning and management of decommissioning for WWERs. The project, which had a duration of four years (1995-1998), included the organization of workshops and scientific visits to countries having WWERs and other countries where active decommissioning projects were under way. Eventually, participants suggested the consolidation of expert guidance and collective opinions into a TECDOC, which was drafted by both designated participants from project recipient countries and invited experts. The TECDOC has the aim of serving as a stimulus for all concerned parties in central and eastern European countries to initiate concrete decommissioning planning, including assessment of existing and required resources for the eventual implementation of decommissioning plans. In addition, the regional technical co-operation project has managed to bring together in this TECDOC a number of good practices that could be useful in WWER-440 decommissioning

  14. Implementation of the international structure for decommissioning costing; examples and related IAEA projects - 59313

    International Nuclear Information System (INIS)

    Daniska, Vladimir; Laraia, Michele; O'Sullivan, Patrick

    2012-01-01

    In 1999, IAEA, the OECD Nuclear Energy Agency and the European Commission jointly proposed the standardised listing of decommissioning activities [1] to serve as a general basis for presentation of decommissioning costs and for promoting the harmonisation in decommissioning costing. The standardised listing of activities [1] was developed in three hierarchical levels based on analysis of typical decommissioning activities identified in various decommissioning projects. The structure [1] has been currently updated by the same organisations as the International Structure for Decommissioning Costing (ISDC) based on the experience gained over ten years of use of the original standardised listing [2]. First part of the paper presents the revised ISDC. The principle of the three-level original hierarchical structure has been preserved. Re-definition of the content and re-structuring was done to avoid ambiguity and to ensure comprehensiveness. Paper presents two basic approaches for implementation of the ISDC structure in costing - converting the cost data available in specific cost structures, mostly according the work breakdown structures of decommissioning projects into ISDC and implementation of the ISDC as the cost calculation structure. Examples of the second approach are given to show that this approach is feasible and may have several advantages. An ORACLE based costing model with implemented of the extended ISDC for detailed costing and an Excel based costing model for preliminary costing at IAEA for research reactors are given. (authors)

  15. Lessons learnt from Ignalina NPP decommissioning project

    International Nuclear Information System (INIS)

    NAISSE, Jean-Claude

    2007-01-01

    The Ignalina Nuclear Power Plant (INPP) is located in Lithuania, 130 km north of Vilnius, and consists of two 1500 MWe RBMK type units, commissioned respectively in December 1983 and August 1987. On the 1. of May 2004, the Republic of Lithuania became a member of the European Union. With the protocol on the Ignalina Nuclear Power in Lithuania which is annexed to the Accession Treaty, the Contracting Parties have agreed: - On Lithuanian side, to commit closure of unit 1 of INPP before 2005 and of Unit 2 by 31 December 2009; - On European Union side, to provide adequate additional Community assistance to the efforts of Lithuania to decommission INPP. The paper is divided in two parts. The first part describes how, starting from this agreement, the project was launched and organized, what is its present status and which activities are planned to reach the final ambitious objective of a green field. To give a global picture, the content of the different projects that were defined and the licensing process will also be presented. In the second part, the paper will focus on the lessons learnt. It will explain the difficulties encountered to define the decommissioning strategy, considering both immediate or differed dismantling options and why the first option was finally selected. The paper will mention other challenges and problems that the different actors of the project faced and how they were managed and solved. The paper will be written by representatives of the Ignalina NPP and of the Project Management Unit. (author)

  16. The decommissioning information management system

    International Nuclear Information System (INIS)

    Park, Seung-Kook; Moon, Jei-Kwon

    2015-01-01

    At the Korea Atomic Energy Research Institute (KAERI), the Korea Research Reactor (KRR-2) and one uranium conversion plant (UCP) were decommissioned. A project was launched in 1997, for the decommissioning of KRR-2 reactor with the goal of completion by 2008. Another project for the decommissioning of the UCP was launched in 2001. The physical dismantling works were started in August 2003 and the entire project was completed by the end of 2010. KAERI has developed a computer information system, named DECOMMIS, for an information management with an increased effectiveness for decommissioning projects and for record keeping for the future decommissioning projects. This decommissioning information system consists of three sub-systems; code management system, data input system (DDIS) and data processing and output system (DDPS). Through the DDIS, the data can be directly inputted at sites to minimize the time gap between the dismantling activities and the evaluation of the data by the project staff. The DDPS provides useful information to the staff for more effective project management and this information includes several fields, such as project progress management, man power management, waste management, and radiation dose control of workers and so on. The DECOMMIS was applied to the decommissioning projects of the KRR-2 and the UCP, and was utilized to give information to the staff for making decisions regarding the progress of projects. It is also to prepare the reference data for the R and D program which is for the development of the decommissioning engineering system tools and to maintain the decommissioning data for the next projects. In this paper, the overall system will be explained and the several examples of its utilization, focused on waste management and manpower control, will be introduced. (author)

  17. Technology, safety and costs of decommissioning a reference boiling water reactor power station. Volume 2. Appendices. Technical report, September 1977-October 1979

    International Nuclear Information System (INIS)

    Oak, H.D.; Holter, G.M.; Kennedy, W.E. Jr.; Konzek, G.J.

    1980-06-01

    Technology, safety and cost information is given for the conceptual decommissioning of a large (1100MWe) boiling water reactor (BWR) power station. Three approaches to decommissioning, immediate dismantlement, safe storage with deferred dismantlement and entombment, were studied to obtain comparisons between costs, occupational radiation doses, potential dose to the public and other safety impacts. It also shows the sensitivity of decommissioning safety and costs to the power rating of a BWR in the range of 200 to 1100 MWE. This volume contains the appendices

  18. Technology, safety and costs of decommissioning a reference boiling water reactor power station. Volume 2. Appendices. Technical report, September 1977-October 1979

    Energy Technology Data Exchange (ETDEWEB)

    Oak, H.D.; Holter, G.M.; Kennedy, W.E. Jr.; Konzek, G.J.

    1980-06-01

    Technology, safety and cost information is given for the conceptual decommissioning of a large (1100MWe) boiling water reactor (BWR) power station. Three approaches to decommissioning, immediate dismantlement, safe storage with deferred dismantlement and entombment, were studied to obtain comparisons between costs, occupational radiation doses, potential dose to the public and other safety impacts. It also shows the sensitivity of decommissioning safety and costs to the power rating of a BWR in the range of 200 to 1100 MWE. This volume contains the appendices.

  19. Technology, safety and costs of decommissioning a reference boiling water reactor power station. Volume 1. Main report. Technical report, September 1977-October 1979

    International Nuclear Information System (INIS)

    Oak, H.D.; Holter, G.M.; Kennedy, W.E. Jr.; Konzek, G.J.

    1980-06-01

    Technology, safety and cost information is given for the conceptual decommissioning of a large (1100MWe) boiling water reactor (BWR) power station. Three approaches to decommissioning, immediate dismantlement, safe storage with deferred dismantlement and entombment, were studied to obtain comparisons between costs, occupational radiation doses, potential dose to the public and other safety impacts. It also shows the sensitivity of decommissioning safety and costs to the power rating of a BWR in the range of 200 to 1100 MWE

  20. Technology, safety and costs of decommissioning a reference boiling water reactor power station. Volume 1. Main report. Technical report, September 1977-October 1979

    Energy Technology Data Exchange (ETDEWEB)

    Oak, H.D.; Holter, G.M.; Kennedy, W.E. Jr.; Konzek, G.J.

    1980-06-01

    Technology, safety and cost information is given for the conceptual decommissioning of a large (1100MWe) boiling water reactor (BWR) power station. Three approaches to decommissioning, immediate dismantlement, safe storage with deferred dismantlement and entombment, were studied to obtain comparisons between costs, occupational radiation doses, potential dose to the public and other safety impacts. It also shows the sensitivity of decommissioning safety and costs to the power rating of a BWR in the range of 200 to 1100 MWE.

  1. Approaches to estimating decommissioning costs

    International Nuclear Information System (INIS)

    Smith, R.I.

    1990-07-01

    The chronological development of methodology for estimating the cost of nuclear reactor power station decommissioning is traced from the mid-1970s through 1990. Three techniques for developing decommissioning cost estimates are described. The two viable techniques are compared by examining estimates developed for the same nuclear power station using both methods. The comparison shows that the differences between the estimates are due largely to differing assumptions regarding the size of the utility and operating contractor overhead staffs. It is concluded that the two methods provide bounding estimates on a range of manageable costs, and provide reasonable bases for the utility rate adjustments necessary to pay for future decommissioning costs. 6 refs

  2. Guideline to Estimate Decommissioning Costs

    Energy Technology Data Exchange (ETDEWEB)

    Yun, Taesik; Kim, Younggook; Oh, Jaeyoung [KHNP CRI, Daejeon (Korea, Republic of)

    2016-10-15

    The primary objective of this work is to provide guidelines to estimate the decommissioning cost as well as the stakeholders with plausible information to understand the decommissioning activities in a reasonable manner, which eventually contribute to acquiring the public acceptance for the nuclear power industry. Although several cases of the decommissioning cost estimate have been made for a few commercial nuclear power plants, the different technical, site-specific and economic assumptions used make it difficult to interpret those cost estimates and compare them with that of a relevant plant. Trustworthy cost estimates are crucial to plan a safe and economic decommissioning project. The typical approach is to break down the decommissioning project into a series of discrete and measurable work activities. Although plant specific differences derived from the economic and technical assumptions make a licensee difficult to estimate reliable decommissioning costs, estimating decommissioning costs is the most crucial processes since it encompasses all the spectrum of activities from the planning to the final evaluation on whether a decommissioning project has successfully been preceded from the perspective of safety and economic points. Hence, it is clear that tenacious efforts should be needed to successfully perform the decommissioning project.

  3. Economic aspects of decommissioning

    International Nuclear Information System (INIS)

    Jenne, C.

    1988-01-01

    Two viewpoints on decommissioning are quoted; the first suggests that decommissioning can be viewed as a technical detail that is of limited relevance whereas the second suggests that decommissioning is a key financial issue. Both are specifically relevant to United Kingdom nuclear power stations. This paper attempts to reconcile the two views. It suggests that decommissioning does raise some important issues for regulation and financing of a privatised industry but, despite this, the economics of nuclear do remain insensitive. The paper begins by examining the significance of decommissioning costs in a number of contexts, including nuclear unit generating costs and financing requirements. It then addresses the degree of uncertainty in the decommissioning cost estimates. With privatisation on the horizon, the paper considers the significance of decommissioning and the associated uncertainty for the investor; this last section considers regulatory issues raised in relation to funding, accounting policy and electricity pricing. (author)

  4. Basic Research about Calculation of the Decommissioning Unit Cost based on The KRR-2 Decommissioning Project

    Energy Technology Data Exchange (ETDEWEB)

    Song, Chan-Ho; Park, Hee-Seong; Ha, Jea-Hyun; Jin, Hyung-Gon; Park, Seung-Kook [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2015-05-15

    The KAERI be used to calculate the decommissioning cost and manage the data of decommissioning activity experience through systems such as the decommissioning information management system (DECOMMIS), Decommissioning Facility Characterization DB System (DEFACS), decommissioning work-unit productivity calculation system (DEWOCS). Some country such as Japan and The United States have the information for decommissioning experience of the NPP and publish reports on decommissioning cost analysis. These reports as valuable data be used to compare with the decommissioning unit cost. In particular, need a method to estimate the decommissioning cost of the NPP because there is no decommissioning experience of NPP in case of Korea. makes possible to predict the more precise prediction about the decommissioning unit cost. But still, there are many differences on calculation for the decommissioning unit cost in domestic and foreign country. Typically, it is difficult to compare with data because published not detailed reports. Therefore, field of estimation for decommissioning cost have to use a unified framework in order to the decommissioning cost be provided to exact of the decommissioning cost.

  5. Basic Research about Calculation of the Decommissioning Unit Cost based on The KRR-2 Decommissioning Project

    International Nuclear Information System (INIS)

    Song, Chan-Ho; Park, Hee-Seong; Ha, Jea-Hyun; Jin, Hyung-Gon; Park, Seung-Kook

    2015-01-01

    The KAERI be used to calculate the decommissioning cost and manage the data of decommissioning activity experience through systems such as the decommissioning information management system (DECOMMIS), Decommissioning Facility Characterization DB System (DEFACS), decommissioning work-unit productivity calculation system (DEWOCS). Some country such as Japan and The United States have the information for decommissioning experience of the NPP and publish reports on decommissioning cost analysis. These reports as valuable data be used to compare with the decommissioning unit cost. In particular, need a method to estimate the decommissioning cost of the NPP because there is no decommissioning experience of NPP in case of Korea. makes possible to predict the more precise prediction about the decommissioning unit cost. But still, there are many differences on calculation for the decommissioning unit cost in domestic and foreign country. Typically, it is difficult to compare with data because published not detailed reports. Therefore, field of estimation for decommissioning cost have to use a unified framework in order to the decommissioning cost be provided to exact of the decommissioning cost

  6. Decontamination and decommissioning project status of the TRIGA mark-2±3 research reactors

    International Nuclear Information System (INIS)

    Jung, K. J.; Baek, S. T.; Jung, W. S.; Park, S. K.; Jung, K. H.

    1999-01-01

    TRIGA Mark-II, the first research reactor in Korea, has operated since 1962, and the second one, TRIGA Mark-III since 1972. Both of them had their operation phased out in 1995 due to their lives and operation of the new research reactor, HANARO at the Korea Atomic Energy Research Institute (KAERI) in Taejeon. Decontamination and decommissioning (D and D) project of the TRIGA Mark-II and Mark-III was started in January 1997 and will be completed in December 2002. In the first year of the project, work was performed in preparation of the decommissioning plan, start of the environmental impact assessment and setup licensing procedure and documentation for the project with cooperation of Korea Institute of Nuclear Safety (KINS). In 1998, Hyundai Engineering Company (HEC) is the main contractor to do design and licensing documentation for the D and D of both reactors. British Nuclear Fuels plc (BNFL) is technical assisting partner of HEC. The decommissioning plan document was submitted to the Ministry of Science and Technology (MOST) for the decommissioning license in December 1998, and it expecting to be issued a license at the end of September 1999. The goal of this project is to release the reactor site and buildings as an unrestricted area. This paper summarizes current status and future plan for the D and D project

  7. Decontamination and decommissioning project status of the TRIGA Mark II and III in Korea

    International Nuclear Information System (INIS)

    Paik, S.T.; Park, S.K.; Chung, K.W.; Chung, U.S.; Jung, K.J.

    1999-01-01

    TRIGA Mark-II, the first research reactor in Korea, has operated since 1962, and the second one, TRIGA Mark-III since 1972. Both of them had their operation phased out in 1995 due to their lives and operation of the new research reactor, HANARO (High-flux Advanced Neutron Application Reactor) at the Korea Atomic Energy Institute (KAERI) in Taejon. Decontamination and decommissioning (D and D) project of TRIGA Mark-II and Mark-III was started in January 1997 and will be completed in December 2002. The first year of the project, work was performed in preparation of the decommissioning plan, start of the environmental impact assessment and setup licensing procedure and documentation for the project with cooperation of Korea Institute of Nuclear Safety (KINS). Hyundai Engineering Company (HEC) is the main contractor to do design and licensing documentation for the D and D of both reactors. British Nuclear Fuels plc (BNFL) is the technical assisting partner of HEC. The decommissioning plan document was submitted to the Ministry of Since and Technology (MOST) for the decommissioning license in December 1998, and it expecting to be issued a license in mid 1999. The goal of this project is to release the reactor site and buildings as an unrestricted area. This paper summarizes current status and future plan for the D and D project. (author)

  8. Decommissioning Unit Cost Data

    International Nuclear Information System (INIS)

    Sanford, P. C.; Stevens, J. L.; Brandt, R.

    2002-01-01

    The Rocky Flats Closure Site (Site) is in the process of stabilizing residual nuclear materials, decommissioning nuclear facilities, and remediating environmental media. A number of contaminated facilities have been decommissioned, including one building, Building 779, that contained gloveboxes used for plutonium process development but did little actual plutonium processing. The actual costs incurred to decommission this facility formed much of the basis or standards used to estimate the decommissioning of the remaining plutonium-processing buildings. Recent decommissioning activities in the first actual production facility, Building 771, implemented a number of process and procedural improvements. These include methods for handling plutonium contaminated equipment, including size reduction, decontamination, and waste packaging, as well as management improvements to streamline planning and work control. These improvements resulted in a safer working environment and reduced project cost, as demonstrated in the overall project efficiency. The topic of this paper is the analysis of how this improved efficiency is reflected in recent unit costs for activities specific to the decommissioning of plutonium facilities. This analysis will allow the Site to quantify the impacts on future Rocky Flats decommissioning activities, and to develop data for planning and cost estimating the decommissioning of future facilities. The paper discusses the methods used to collect and arrange the project data from the individual work areas within Building 771. Regression and data correlation techniques were used to quantify values for different types of decommissioning activities. The discussion includes the approach to identify and allocate overall project support, waste management, and Site support costs based on the overall Site and project costs to provide a ''burdened'' unit cost. The paper ultimately provides a unit cost basis that can be used to support cost estimates for

  9. Use of project management approach for planning of decommissioning activities of a uranium mining site

    Energy Technology Data Exchange (ETDEWEB)

    Ribeiro, Saulo F.Q.; Lage, Ricardo F.; Gomes, Danielle E.; Ogawa, Iukio, E-mail: quintao.saulo@gmail.com, E-mail: rflage@gmail.com, E-mail: danielle@inb.gov.br, E-mail: iukio@inb.gov.br [Indústrias Nucleares do Brasil (INB), Rio de Janeiro, RJ (Brazil)

    2017-07-01

    The decommissioning of nuclear facilities in the fuel cycle is an extremely important factor for the continuity of nuclear program in any country, especially in that countries such as Brazil, where there are some facilities are in process of being dismantled or must be decommissioned in the medium and long term. Since the decommissioning is a process quite complex and expensive and for this reason, it must be handle with modern management practices for so that the chances of success are increased. This work aims to describe the management plan and the strategy adopted for the execution of the decommissioning and environmental remediation (D and ER) activities for the first uranium mine in Brazil, located in the Minas Gerais State and known as Unidade de Tratamento de Minério (UTM). This facility was operated between 1982 and 1995. All the economically recoverable uranium was extracted and nowadays there is no mining activity is underway and there are only research and laboratory activities are running in the site. The conceptual plans for decommissioning and remediation for this unit have been prepared and emergency activities were recommended. These activities are related to studies about drainage acid, ensure safety of dams, adequacy of CAKE II storage conditions and request for operating licenses for the decommissioning from IBAMA and the authorization from CNEN. The majority of the critical factors for decommissioning had their origin due the characteristics of the project have been implemented and has remained due to uncertainties in the decision-making process over time. This project has a set of variables that need to be analyzed considering different aspects as licensing and regulatory framework, radiological, technical and engineering issues, beyond costs, schedule, risks and human resources. In this sense, it was decided to adopt the good practices of project management, published by the Project Management Institute - PMI and to give a differentiated

  10. Use of project management approach for planning of decommissioning activities of a uranium mining site

    International Nuclear Information System (INIS)

    Ribeiro, Saulo F.Q.; Lage, Ricardo F.; Gomes, Danielle E.; Ogawa, Iukio

    2017-01-01

    The decommissioning of nuclear facilities in the fuel cycle is an extremely important factor for the continuity of nuclear program in any country, especially in that countries such as Brazil, where there are some facilities are in process of being dismantled or must be decommissioned in the medium and long term. Since the decommissioning is a process quite complex and expensive and for this reason, it must be handle with modern management practices for so that the chances of success are increased. This work aims to describe the management plan and the strategy adopted for the execution of the decommissioning and environmental remediation (D and ER) activities for the first uranium mine in Brazil, located in the Minas Gerais State and known as Unidade de Tratamento de Minério (UTM). This facility was operated between 1982 and 1995. All the economically recoverable uranium was extracted and nowadays there is no mining activity is underway and there are only research and laboratory activities are running in the site. The conceptual plans for decommissioning and remediation for this unit have been prepared and emergency activities were recommended. These activities are related to studies about drainage acid, ensure safety of dams, adequacy of CAKE II storage conditions and request for operating licenses for the decommissioning from IBAMA and the authorization from CNEN. The majority of the critical factors for decommissioning had their origin due the characteristics of the project have been implemented and has remained due to uncertainties in the decision-making process over time. This project has a set of variables that need to be analyzed considering different aspects as licensing and regulatory framework, radiological, technical and engineering issues, beyond costs, schedule, risks and human resources. In this sense, it was decided to adopt the good practices of project management, published by the Project Management Institute - PMI and to give a differentiated

  11. The application of modern project management principles and processes in major nuclear decommissioning programmes

    International Nuclear Information System (INIS)

    Bayliss, C. R.

    2003-01-01

    The UKAEA has embarked upon an accelerated programme of decommissioning works. This has resulted in a review of its project management systems and processes. This paper describes these processes and their application to nuclear decommissioning and associated new build construction projects. Efficiencies from these processes are necessary. In addition this paper describes how UKAEA, where appropriate, utilizes modern forms of alliance contract so as to work in partnership with its contractors. (author)

  12. Final project report, TA-35 Los Alamos Power Reactor Experiment No. II (LAPRE II) decommissioning project

    International Nuclear Information System (INIS)

    Montoya, G.M.

    1992-01-01

    This final report addresses the decommissioning of the LAPRE II Reactor, safety enclosure, fuel reservoir tanks, emergency fuel recovery system, primary pump pit, secondary loop, associated piping, and the post-remediation activities. Post-remedial action measurements are also included. The cost of the project, including Phase I assessment and Phase II remediation was approximately $496K. The decommissioning operation produced 533 m 3 of low-level solid radioactive waste and 5 m 3 of mixed waste

  13. Decommissioning and decontamination

    International Nuclear Information System (INIS)

    Dadoumont, J.; Cantrel, E.; Valenduc, P.; Noynaert, L.

    2009-01-01

    The SCK-CEN has built a large know-how in decommissioning and decontamination, thanks to its BR3 decommissioning project. In 2007, the decommissioning activities at BR3 have been continued according to the strategy. This article discusses main realisations the following domains: decommissioning of the neutron shield tank and installation of new ventilation for the controlled area, dismantling of the former one and characterization of the stack

  14. Basic Research on Selecting ISDC Activity for Decommissioning Costing in KRR-2 Decommissioning Project Experience Data

    Energy Technology Data Exchange (ETDEWEB)

    Song, Chan-Ho; Park, Hee-Seong; Jin, Hyung-Gon; Park, Seung-Kook [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2015-10-15

    KAERI is performing research for calculation of expected time of a decommissioning work and evaluation of decommissioning cost and this research calculate a decommissioning work unit productivity based on the experience data of decommissioning activity for KRR-2. The KAERI be used to calculate the decommissioning cost and manage the experience data from the decommissioning activity through the Decommissioning Information Management System (DECOMMIS), Decommissioning Facility Characterization DB System (DEFACS), and Decommissioning Work-unit Productivity Calculation System (DEWOCS). In this paper, the methodology was presented how select the ISDC activities in dismantling work procedures of a 'removal of radioactive concrete'. The reason to select the 'removal of radioactive concrete' is main key activity and generates the amount of radioactive waste. This data will take advantage of the cost estimation after the code for the selected items derived ISDC. There are various efforts for decommissioning costing in each country. In particular, OECD/NEA recommends decommissioning cost estimation using the ISDC and IAEA provides for Cost Estimation for Research Reactors in Excel (CERREX) program that anyone is easy to use the cost evaluation from a limited decommissioning experience in domestic. In the future, for the decommissioning cost evaluation, the ISDC will be used more widely in a strong position. This paper has described a method for selecting the ISDC item from the actual dismantling work procedures.

  15. Decommissioning the Dresden Unit 1 Spent Fuel Pool

    International Nuclear Information System (INIS)

    Demmer, R.L.; Bargelt, R.J.; Panozzo, J.B.; Christensen, R.J.

    2006-01-01

    The Dresden Nuclear Power Station, Unit 1 Spent Fuel Pool (SFP) (Exelon Generation Co.) was decommissioned using a new underwater coating strategy developed in cooperation with the Idaho National Laboratory (INL). This was the first time that a commercial nuclear power plant (NPP) SFP was decommissioned using this underwater coating approach. This approach has advantages in many aspects, particularly in reducing airborne contamination and in safer, more cost effective deactivation. The process was pioneered at the INL and used to decommission three SFPs with a total combined pool volume of over 900,000 gallons. The INL provided engineering support and shared project plans to successfully initiate the Dresden project. This report outlines the steps taken by the INL and Exelon on the pathway for this activity. The rationale used to select the underwater coating option and the advantages and disadvantages are shown. Special circumstances, such as the use of a remotely operated underwater vehicle to map (visually and radiologically) the pool areas that were not readily accessible, are discussed. Several specific areas where special equipment was employed are given and a lessons learned evaluation is included. (authors)

  16. Decommissioning challenges - an industrial reality

    International Nuclear Information System (INIS)

    Moore, H.; Mort, P.; Hutton, E.

    2008-01-01

    Sellafield Limited has undergone many transformations in previous years. The Nuclear Decommissioning Authority (NDA) has managed the site from April 2005, and a new Parent Body Organisation (PBO) is soon to be announced. In addition, it is an exciting time for the nuclear industry following the announcement of the UK government support new reactor builds. Should the site be selected for new build, the impact on Sellafield, its decommissioning program and economic impact on the local area can only be speculated at the current time. Every past, present and future decommissioning project at the Sellafield Limited site offers complex challenges, as each facility is unique. Specialist skills and experience must be engaged at pre-planned phases to result in a safe, efficient and successful decommissioning project. This paper provides an overview of a small selection of decommissioning projects, including examples of stakeholder engagement, plant and equipment dismantling using remote handling equipment and the application of innovative techniques and technologies. In addition, the final section provides a summary upon how future technologies required by the decommissioning projects are being assessed and developed. (authors)

  17. Innovative and adaptive technologies in decommissioning of nuclear facilities. Final report of a coordinated research project 2004-2008

    International Nuclear Information System (INIS)

    2008-10-01

    There are dozens of old reactors and other nuclear facilities worldwide that are either being actively dismantled or are candidates for decommissioning in the near term. A significant proportion of these facilities are situated in Member States or institutions that do not have adequate expertise and technologies for planning and implementing state of the art decommissioning projects. The technology selection process is critical in that regard. The main objective of the IAEA technical activities on decommissioning is to promote the exchange of lessons learned in order to improve the technologies, thereby contributing to successful planning and implementation of decommissioning. This should be achieved through a better understanding of the decision making process in technology comparison and selection and relevant issues affecting the entire decommissioning process. The specific objectives of the Coordinated Research Project (CRP) on Innovative and Adaptive Technologies in Decommissioning of Nuclear Facilities include the following general aspects: (a) To establish methodologies and data needs for developing concepts and approaches relevant to technology comparison and selection in decommissioning; (b) To improve and expand the database on applications and performance of various types of decommissioning technologies; (c) To address specific issues for individual decommissioning technologies and generate data relevant to their comparison and selection. It is also expected that this project, and in particular the papers collected in this TECDOC, will draw Member States' attention to the practicality and achievability of timely planning and implementation of decommissioning, especially for many smaller projects. Concluding reports that summarized the work undertaken under the aegis of the CRP were presented at the third and final research coordination meeting held in Rez, Czech Republic, 3-7 December 2007, and collected in this technical publication. Operating

  18. Accelerating the Whiteshell Laboratories Decommissioning Through the Implementation of a Projectized and Delivery-Focused Organization - 13074

    Energy Technology Data Exchange (ETDEWEB)

    Wilcox, Brian; Mellor, Russ; Michaluk, Craig [Atomic Energy of Canada Limited, Whiteshell Laboratories, Pinawa, Manitoba (Canada)

    2013-07-01

    Whiteshell Laboratories (WL) is a nuclear research site in Canada that was commissioned in 1964 by Atomic Energy of Canada Limited. It covers a total area of approximately 4,375 hectares (10,800 acres) and includes the main campus site, the Waste Management Area (WMA) and outer areas of land identified as not used for or impacted by nuclear development or operations. The WL site employed up to 1100 staff. Site activities included the successful operation of a 60 MW organic liquid-cooled research reactor from 1965 to 1985, and various research programs including reactor safety research, small reactor development, fuel development, biophysics and radiation applications, as well as work under the Canadian Nuclear Fuel Waste Management Program. In 1997, AECL made a business decision to discontinue research programs and operations at WL, and obtained government concurrence in 1998. The Nuclear Legacy Liabilities Program (NLLP) was established in 2006 by the Canadian Government to remediate nuclear legacy liabilities in a safe and cost effective manner, including the WL site. The NLLP is being implemented by AECL under the governance of a Natural Resources Canada (NRCan)/AECL Joint Oversight Committee (JOC). Significant progress has since been made, and the WL site currently holds the only Canadian Nuclear Safety Commission (CNSC) nuclear research site decommissioning license in Canada. The current decommissioning license is in place until the end of 2018. The present schedule planned for main campus decommissioning is 30 years (to 2037), followed by institutional control of the WMA until a National plan is implemented for the long-term management of nuclear waste. There is an impetus to advance work and complete decommissioning sooner. To accomplish this, AECL has added significant resources, reorganized and moved to a projectized environment. This presentation outlines changes made to the organization, the tools implemented to foster projectization, and the benefits

  19. Decommissioning and demolition of the Greifswald nuclear power station

    International Nuclear Information System (INIS)

    Sterner, H.; Leushacke, D.; Rittscher, D.

    1995-01-01

    The unexpected decision to decommission the plants in Greifswald makes the management and disposal of fuels and plant waste a major issue to be solved as a precondition for decommissioning and dismantling. The decisive point in waste management is the existence of an interim store or repository of sufficient capacity to accept both the nuclear fuel and the plant waste and the considerable volumes of radioactive residues arising in dismantling. Current major activities include planning for decommissioning and demolition, and drafting of the licensing documents; removal of the fuel elements from the reactor units; construction of the northern interim store for fuel elements and residues. (orig./HP)

  20. Preliminary nuclear decommissioning cost study

    International Nuclear Information System (INIS)

    Sissingh, R.A.P.

    1981-04-01

    The decommissioning of a nuclear power plant may involve one or more of three possible options: storage with surveillance (SWS), restricted site release (RSR), and unrestricted site use(USU). This preliminary study concentrates on the logistical, technical and cost aspects of decommissioning a multi-unit CANDU generating station using Pickering GS as the reference design. The procedure chosen for evaluation is: i) removal of the fuel and heavy water followed by decontamination prior to placing the station in SWS for thiry years; ii) complete dismantlement to achieve a USU state. The combination of SWS and USU with an interim period of surveillance allows for radioactive decay and hence less occupational exposure in achieving USU. The study excludes the conventional side of the station, assumes waste disposal repositories are available 1600 km away from the station, and uses only presently available technologies. The dismantlement of all systems except the reactor core can be accomplished using Ontario Hydro's current operating, maintenance and construction procedures. The total decommissioning period is spread out over approximately 40 years, with major activities concentrated in the first and last five years. The estimated dose would be approximately 1800 rem. Overall Pickering GS A costs would be $162,000,000 (1980 Canadian dollars)

  1. An analysis of decommissioning costs

    International Nuclear Information System (INIS)

    Teunckens, L.; Loeschhorn, U.; Yanagihara, S.; Wren, G.; Menon, S.

    1992-01-01

    Within the OECD/NEA Cooperative Programme on Decommissioning a Task Group was set up early in 1989 to identify the reasons for the large variations in decommissioning cost estimates. The Task Group gathered cost data from 12 of the 14 projects in the Programme to form the basis of their analysis. They included reactors being decommissioned to various stages as well as fuel cycle facilities. The projects were divided into groups of projects with similar characteristics ('models') to facilitate the analysis of the cost distribution in each group of projects and the cost data was progressively refined by a dialogue between the Task Group and the project managers. A comparative analysis was then performed and project specific discrepancies were identified. The Task Group's report is summarized on the results of the comparative analysis as well as the lessons learnt by the Task Group in the acquisition and analysis of cost data from international decommissioning projects. (author) 5 tabs

  2. Decommissioning Trawsfynydd - How public consultation shaped the strategy

    Energy Technology Data Exchange (ETDEWEB)

    Kay, Martin J [Nuclear Electric plc. (United Kingdom)

    1995-07-01

    This case study discusses the ned of consulting the public when decommissioning a nuclear power plants. When Trawsfynydd power station in North Wales shutdown in July 1993, Nuclear Electric's strategy for decommissioning its stations was not clearly defined. The company had altered its corporate policy on decommissioning fro he strategy referred to as the 'Reference Case' which had been approved by the Government, to the preferred 'Deferred Safestore' strategy, which was waiting Government approval. Deferred Safestore is preferred as it simplifies the engineering work involved by capitalising an the basic strength and integrity of the reactor building. It minimises thd radiation exposure to workers and radioactivity released to the environment, reduces the amount of radioactive waste produced and significantly cuts the total decommissioning cost. The closure and the decommissioning of Trawsfynydd power station was a sensitive issue as: The station lies within a National Park of outstanding beauty. The economic circumstances in the area are such that employment opportunities are very limited. At a crucial time when the company was approaching a Government review which would decide its future, Nuclear Electric could not afford to lose any credibility. A public consultation programme was launched in the vicinity of the power station To gauge the reactions of the public and elected local government bodies to a series of decommissioning options. Nuclear Electric presented three main options with details on the employment opportunities, the costs, and the lorry loads of material involved with each. The people were identified on whom decommissioning Trawsfynydd power station is likely to have an environmental or socioeconomic impact. As a result of the polls the Nuclear Electric received feedback in two ways. Formal feedback from the local councils Independent analysis of the completed questionnaires. The company was wholly committed to a meaningful consultation. Before

  3. Decommissioning Trawsfynydd - How public consultation shaped the strategy

    International Nuclear Information System (INIS)

    Kay, Martin J.

    1995-01-01

    This case study discusses the ned of consulting the public when decommissioning a nuclear power plants. When Trawsfynydd power station in North Wales shutdown in July 1993, Nuclear Electric's strategy for decommissioning its stations was not clearly defined. The company had altered its corporate policy on decommissioning fro he strategy referred to as the 'Reference Case' which had been approved by the Government, to the preferred 'Deferred Safestore' strategy, which was waiting Government approval. Deferred Safestore is preferred as it simplifies the engineering work involved by capitalising an the basic strength and integrity of the reactor building. It minimises thd radiation exposure to workers and radioactivity released to the environment, reduces the amount of radioactive waste produced and significantly cuts the total decommissioning cost. The closure and the decommissioning of Trawsfynydd power station was a sensitive issue as: The station lies within a National Park of outstanding beauty. The economic circumstances in the area are such that employment opportunities are very limited. At a crucial time when the company was approaching a Government review which would decide its future, Nuclear Electric could not afford to lose any credibility. A public consultation programme was launched in the vicinity of the power station To gauge the reactions of the public and elected local government bodies to a series of decommissioning options. Nuclear Electric presented three main options with details on the employment opportunities, the costs, and the lorry loads of material involved with each. The people were identified on whom decommissioning Trawsfynydd power station is likely to have an environmental or socioeconomic impact. As a result of the polls the Nuclear Electric received feedback in two ways. Formal feedback from the local councils Independent analysis of the completed questionnaires. The company was wholly committed to a meaningful consultation. Before

  4. Money Related Decommissioning and Funding Decision Making

    International Nuclear Information System (INIS)

    Goodman, Lynne S.

    2008-01-01

    'Money makes the world go round', as the song says. It definitely influences decommissioning decision-making and financial assurance for future decommissioning. This paper will address two money-related decommissioning topics. The first is the evaluation of whether to continue or to halt decommissioning activities at Fermi 1. The second is maintaining adequacy of financial assurance for future decommissioning of operating plants. Decommissioning costs considerable money and costs are often higher than originally estimated. If costs increase significantly and decommissioning is not well funded, decommissioning activities may be deferred. Several decommissioning projects have been deferred when decision-makers determined future spending is preferable than current spending, or when costs have risen significantly. Decommissioning activity timing is being reevaluated for the Fermi 1 project. Assumptions for waste cost-escalation significantly impact the decision being made this year on the Fermi 1 decommissioning project. They also have a major impact on the estimated costs for decommissioning currently operating plants. Adequately funding full decommissioning during plant operation will ensure that the users who receive the benefit pay the full price of the nuclear-generated electricity. Funding throughout operation also will better ensure that money is available following shutdown to allow decommissioning to be conducted without need for additional funds

  5. Industrial safety in a nuclear decommissioning environment observations and lessons learned

    International Nuclear Information System (INIS)

    Brevig, D.

    2008-01-01

    Decommissioning activities present unusual and unexpected workplace safety challenges that go far beyond the traditional experience of nuclear power plant managers. A blend of state-of-the-art safety program management tools along with new and practical applications are required to ensure high industrial safety performance. The demanding and rigorously applied nuclear safety engineering standards that are accepted as normal and routine in the operation of a nuclear power facility, should transform as an industrial safety standard during the non-operating period of decommissioning. In addition, historical measures of non-nuclear industrial safety injury rates would or should not be acceptable safety behaviors during a nuclear decommissioning project. When complex projects, such as the decommissioning of a nuclear generating facility are undertaken, the workforce brings experience, qualifications, and assumptions to the project. The overall multi-year general schedule is developed, with more schedule details, for example, for the nearest rolling 12-18 months. Methods are established for the selection of contractors to assist in areas that are not normal tasks for the facility workforce, whose normal activity is managing and operating a nuclear generating station. However, it is critical to manage those contractors to the agreed work scope to ensure success is maintained by both parties, e.g. the job gets done, on schedule, on budget, all parties are financially whole when the work is complete, and safely. The purpose of this paper is to provide a perspective of nuclear plant personal safety in the ever changing industrial environment created by the demolition of robust and often radiologically contaminated structures in a nuclear facility decommissioning project. (author)

  6. Industrial safety in a nuclear decommissioning environment observations and lessons learned

    Energy Technology Data Exchange (ETDEWEB)

    Brevig, D. [Independent Consultant, San Clemente (United States)

    2008-07-01

    Decommissioning activities present unusual and unexpected workplace safety challenges that go far beyond the traditional experience of nuclear power plant managers. A blend of state-of-the-art safety program management tools along with new and practical applications are required to ensure high industrial safety performance. The demanding and rigorously applied nuclear safety engineering standards that are accepted as normal and routine in the operation of a nuclear power facility, should transform as an industrial safety standard during the non-operating period of decommissioning. In addition, historical measures of non-nuclear industrial safety injury rates would or should not be acceptable safety behaviors during a nuclear decommissioning project. When complex projects, such as the decommissioning of a nuclear generating facility are undertaken, the workforce brings experience, qualifications, and assumptions to the project. The overall multi-year general schedule is developed, with more schedule details, for example, for the nearest rolling 12-18 months. Methods are established for the selection of contractors to assist in areas that are not normal tasks for the facility workforce, whose normal activity is managing and operating a nuclear generating station. However, it is critical to manage those contractors to the agreed work scope to ensure success is maintained by both parties, e.g. the job gets done, on schedule, on budget, all parties are financially whole when the work is complete, and safely. The purpose of this paper is to provide a perspective of nuclear plant personal safety in the ever changing industrial environment created by the demolition of robust and often radiologically contaminated structures in a nuclear facility decommissioning project. (author)

  7. UK reactor decommissioning strategy

    International Nuclear Information System (INIS)

    Woollam, P.B.

    2004-01-01

    With the cessation of electricity generation, nuclear power stations move into the next stage of the overall life cycle of the facility: decommissioning. Decommissioning is defined as the process whereby a nuclear facility, at the end of its economic life, is taken permanently out of service and its site made available for other purposes. This involves the implementation of a structured and safe programme for dismantling and clearing the site and making it available for alternative use in the future. In practical terms, 'decommissioning' means the systematic and progressive reduction of hazards to the point where the site could eventually be de-licensed. (author)

  8. Utility planning for decommissioning

    International Nuclear Information System (INIS)

    Williams, D.H.

    1982-01-01

    Though the biggest impact on a utility of nuclear power plant decommissioning may occur many years from now, procrastination of efforts to be prepared for that time is unwarranted. Foresight put into action through planning can significantly affect that impact. Financial planning can assure the recovery of decommissioning costs in a manner equitable to customers. Decision-making planning can minimize adverse affects of current decisions on later decommissioning impacts and prepare a utility to be equipped to make later decommissioning decisions. Technological knowledge base planning can support all other planning aspects for decommissioning and prepare a utility for decommissioning decisions. Informed project planning can ward off potentially significant pitfalls during decommissioning and optimize the effectiveness of the actual decommissioning efforts

  9. Technology, safety, and costs of decommissioning a reference pressurized water reactor power station

    International Nuclear Information System (INIS)

    Smith, R.I.; Konzek, G.J.; Kennedy, W.E. Jr.

    1978-05-01

    Safety and cost information was developed for the conceptual decommissioning of a large [1175 MW(e)] pressurized water reactor (PWR) power station. Two approaches to decommissioning, Immediate Dismantlement and Safe Storage with Deferred Dismantlement, were studied to obtain comparisons between costs, occupational radiation doses, potential radiation dose to the public, and other safety impacts. Immediate Dismantlement was estimated to require about six years to complete, including two years of planning and preparation prior to final reactor shutdown, at a cost of $42 million, and accumulated occupational radiation dose, excluding transport operations, of about 1200 man-rem. Preparations for Safe Storage were estimated to require about three years to complete, including 1 1 / 2 years for planning and preparation prior to final reactor shutdown, at a cost of $13 million and an accumulated occupational radiation dose of about 420 man-rem. The cost of continuing care during the Safe Storage period was estimated to be about $80 thousand annually. Accumulated occupational radiation dose during the Safe Storage period was estimated to range from about 10 man-rem for the first 10 years to about 14 man-rem after 30 years or more. The cost of decommissioning by Safe Storage with Deferred Dismantlement was estimated to be slightly higher than Immediate Dismantlement. Cost reductions resulting from reduced volumes of radioactive material for disposal, due to the decay of the radioactive containments during the deferment period, are offset by the accumulated costs of surveillance and maintenance during the Safe Storage period

  10. Release criteria for decommissioning of the Shippingport Atomic Power Station

    International Nuclear Information System (INIS)

    Eger, K.J.; Gardner, D.L.; Giordano, R.J.

    1986-01-01

    The United States Department of Energy (DOE) has established guidelines for allowable levels of residual radioactivity at remote sites in the Surplus Facilities Management Program (SFMP). These guidelines specify that doses to the public from this residual radioactivity must not exceed 500 mrem/year (for up to five years) or 100 mrem/year (for a lifetime), regardless of the use of the land. The guidelines also specify that exposures be further limited, depending on ALARA considerations. The decommissioning of the Shippingport Atomic Power Station, done under the auspices of SFMP, is being performed in accordance with these guidelines. It follows that, at the conclusion of the project, the concentrations of residual radioactivity, identified both by isotope and location (x,y,z), must be low enough so that the guidelines (500,100) are not exceeded. Furthermore, the concentrations must be low enough so that additional action which might be taken to reduce them cannot cost effectively decrease the dose to the public. A cost-benefit analysis, based on actual conditions at Shippingport, is being prepared to identify these ''low-enough'' concentrations. Once identified, these concentrations will comprise the release criteria for the site. The analysis will be developed by (1) performing an initial site characterization, (2) employing pathways analyses to compute the dose to a future occupant, (3) costing of proposed site modifications, and (4) repeating a pathways analysis based on each ''as-modified'' location on the site. The result will be a paired set of data relating the cost of modification to the reduction in the dose to the future occupant

  11. Estimating end of life liabilities for plant licensing and financial planning for similarly configured stations

    International Nuclear Information System (INIS)

    Griffiths, G.; Kennard, J.

    2008-01-01

    Ontario Power Generation (OPG) is required to update estimated waste management and decommissioning costs on a 5-year cycle within the Canadian Nuclear Safety Commission's (CNSC) regulatory framework and provide a decommissioning cost update and provisions funds status to the Province of Ontario on a similar five-year cycle under the terms of the Ontario Nuclear Funds Agreement (ONFA). The following is an overview of the important steps used to develop OPG's nuclear power station decommissioning cost estimates, including a discussion of the responsibilities of both the owner (OPG) and estimating services vendor (TLG Services). This presentation is related to decommissioning estimating for multi-unit stations; therefore the discussion will be focused on identifying those activities that may be particularly impacted by multi-unit configuration or multiple stations. It should be noted that simultaneously developing decommissioning estimates for multiple multi-unit stations creates the opportunity to achieve economies of scale to more efficiently produce the estimates, and enables the owner and vendor to compare results between stations to identify inconsistencies. However, without careful attention to detail at the planning and execution stage, it also creates the potential liability of backtracking and developing the estimate multiple times, should significant assumptions be revised in mid-project. (authors)

  12. Estimating end of life liabilities for plant licensing and financial planning for similarly configured stations

    Energy Technology Data Exchange (ETDEWEB)

    Griffiths, G. [TLG Services, Inc. an Entergy Nuclear Co. (United States); Kennard, J. [Ontario Power Generation Inc. (Canada)

    2008-07-01

    Ontario Power Generation (OPG) is required to update estimated waste management and decommissioning costs on a 5-year cycle within the Canadian Nuclear Safety Commission's (CNSC) regulatory framework and provide a decommissioning cost update and provisions funds status to the Province of Ontario on a similar five-year cycle under the terms of the Ontario Nuclear Funds Agreement (ONFA). The following is an overview of the important steps used to develop OPG's nuclear power station decommissioning cost estimates, including a discussion of the responsibilities of both the owner (OPG) and estimating services vendor (TLG Services). This presentation is related to decommissioning estimating for multi-unit stations; therefore the discussion will be focused on identifying those activities that may be particularly impacted by multi-unit configuration or multiple stations. It should be noted that simultaneously developing decommissioning estimates for multiple multi-unit stations creates the opportunity to achieve economies of scale to more efficiently produce the estimates, and enables the owner and vendor to compare results between stations to identify inconsistencies. However, without careful attention to detail at the planning and execution stage, it also creates the potential liability of backtracking and developing the estimate multiple times, should significant assumptions be revised in mid-project. (authors)

  13. Apollo decommissioning project, Apollo, Pennsylvania. Final technical report

    International Nuclear Information System (INIS)

    1997-01-01

    In November, 1991 Babcock and Wilcox (B and W) received a grant to partially fund the decommissioning of the former Apollo Nuclear Fuel Facility. The decommissioning was performed in accordance with a Nuclear Regulatory Commission (NRC) approved decommissioning plan. This report summarizes the decommissioning of the Apollo Nuclear Fuel Facility and the radiological surveying of the site to demonstrate that these decommissioning activities were effective in reducing residual activity well below NRC's criteria for release for unrestricted use. The Apollo Nuclear Fuel Facility was utilized by the Nuclear Materials and Equipment Corporation (NUMEC) and B and W for nuclear research and production under Atomic Energy Commission and Department of Energy (DOE) contracts during 20 plus years of nuclear fuel manufacturing operations

  14. Waste minimization value engineering workshop for the Los Alamos National Laboratory Omega West Reactor Decommissioning Project

    International Nuclear Information System (INIS)

    Hartnett, S.; Seguin, N.; Burns, M.

    1995-01-01

    The Los Alamos National Laboratory Pollution Prevention Program Office sponsored a Value Engineering (VE) Workshop to evaluate recycling options and other pollution prevention and waste minimization (PP/WMin) practices to incorporate into the decommissioning of the Omega West Reactor (OWR) at the laboratory. The VE process is an organized, systematic approach for evaluating a process or design to identify cost saving opportunities, or in this application, waste reduction opportunities. This VE Workshop was a facilitated process that included a team of specialists in the areas of decontamination, decommissioning, PP/WMin, cost estimating, construction, waste management, recycling, Department of Energy representatives, and others. The uniqueness of this VE Workshop was that it used an interdisciplinary approach to focus on PP/WMin practices that could be included in the OWR Decommissioning Project Plans and specifications to provide waste reduction. This report discusses the VE workshop objectives, summarizes the OWR decommissioning project, and describes the VE workshop activities, results, and lessons learned

  15. Waste minimization value engineering workshop for the Los Alamos National Laboratory Omega West Reactor Decommissioning Project

    Energy Technology Data Exchange (ETDEWEB)

    Hartnett, S.; Seguin, N. [Benchmark Environmental Corp., Albuquerque, NM (United States); Burns, M. [Los Alamos National Lab., NM (United States)

    1995-12-31

    The Los Alamos National Laboratory Pollution Prevention Program Office sponsored a Value Engineering (VE) Workshop to evaluate recycling options and other pollution prevention and waste minimization (PP/WMin) practices to incorporate into the decommissioning of the Omega West Reactor (OWR) at the laboratory. The VE process is an organized, systematic approach for evaluating a process or design to identify cost saving opportunities, or in this application, waste reduction opportunities. This VE Workshop was a facilitated process that included a team of specialists in the areas of decontamination, decommissioning, PP/WMin, cost estimating, construction, waste management, recycling, Department of Energy representatives, and others. The uniqueness of this VE Workshop was that it used an interdisciplinary approach to focus on PP/WMin practices that could be included in the OWR Decommissioning Project Plans and specifications to provide waste reduction. This report discusses the VE workshop objectives, summarizes the OWR decommissioning project, and describes the VE workshop activities, results, and lessons learned.

  16. Project gnome decontamination and decommissioning plan

    International Nuclear Information System (INIS)

    1979-04-01

    The document presents the operational plan for conducting the final decontamination and decommissioning work at the site of the first U.S. nuclear detonation designed specifically for peaceful purposes and the first underground event on the Plowshare Program to take place outside the Nevada Test Site. The plan includes decontamination and decommissioning procedures, radiological guidelines, and the NV concept of operations

  17. Decommissioning planning of Swedish nuclear power plants

    Energy Technology Data Exchange (ETDEWEB)

    Hedin, Gunnar; Bergh, Niklas [Westinghouse Electric Sweden AB, Vaesteraes (Sweden)

    2013-07-01

    The technologies required for the decommissioning work are for the most part readily proven. Taken into account that there will be many more years before the studied reactor units will undergo decommissioning, the techniques could even be called conventional at that time. This will help bring the decommissioning projects to a successful closure. A national waste fund is already established in Sweden to finance amongst others all dismantling and decommissioning work. This will assure that funding for the decommissioning projects is at hand when needed. All necessary plant data are readily available and this will, combined with a reliable management system, expedite the decommissioning projects considerably. Final repositories for both long- and short-lived LILW respectively is planned and will be constructed and dimensioned to receive the decommissioning waste from the Swedish NPP:s. Since the strategy is set and well thought-through, this will help facilitate a smooth disposal of the radioactive decommissioning waste. (orig.)

  18. Optimizing decommissioning strategies

    International Nuclear Information System (INIS)

    Passant, F.H.

    1993-01-01

    Many different approaches can be considered for achieving satisfactory decommissioning of nuclear installations. These can embrace several different engineering actions at several stages, with time variations between the stages. Multi-attribute analysis can be used to help in the decision making process and to establish the optimum strategy. It has been used in the Usa and the UK to help in selecting preferred sites for radioactive waste repositories, and also in UK to help with the choice of preferred sites for locating PWR stations, and in selecting optimum decommissioning strategies

  19. Planning and management for reactor decommissioning

    International Nuclear Information System (INIS)

    Miyasaka, Yasuhiko

    2001-01-01

    This report describes decommissioning strategy, planning process, regulation, management and organization, radiological characterization and safety. Planning is used to identify, define and organize the requirements for decommissioning including decommissioning options, items to be accomplished (objective, scope), to solve problems of how it is to be accomplished (methods, means and procedures), questions of who will execute it (resources, organization and responsibilities, interfacing), and time when it will be executed (schedule for meeting the objectives). A plan is highly dependent on the quality of the management team assembled to carry it out. Radiological characterization involves a survey of existing data, calculation, in situ measurements and/or sampling and analyses. Using this databases decommissioning planner may assess options, considering: decontamination processes, dismantling procedures, tools required, radiological protection of workers and public/environment, waste classification, and resulting costs. Comparison and optimization of these factors will lead to selection of a decommissioning strategy, i.e. typically, immediate or deferred dismantling. The planning and implementation of decommissioning for nuclear reactors should be referred both recent dismantling techniques and many decommissioning experiences. The technical lessons learned from many projects will help in the planning for future decommissioning projects. And systematic planning and management are essential to successful completion of a decommissioning project. (author)

  20. Technology, safety and costs of decommissioning a reference pressurized water reactor power station: Technical support for decommissioning matters related to preparation of the final decommissioning rule

    International Nuclear Information System (INIS)

    Konzek, G.J.; Smith, R.I.

    1988-07-01

    Preparation of the final Decommissioning Rule by the Nuclear Regulatory Commission (NRC) staff has been assisted by Pacific Northwest Laboratory (PNL) staff familiar with decommissioning matters. These efforts have included updating previous cost estimates developed during the series of studies on conceptually decommissioning reference licensed nuclear facilities for inclusion in the Final Generic Environmental Impact Statement (FGEIS) on decommissioning; documenting the cost updates; evaluating the cost and dose impacts of post-TMI-2 backfits on decommissioning; developing a revised scaling formula for estimating decommissioning costs for reactor plants different in size from the reference pressurized water reactor (PWR) described in the earlier study; defining a formula for adjusting current cost estimates to reflect future escalation in labor, materials, and waste disposal costs; and completing a study of recent PWR steam generator replacements to determine realistic estimates for time, costs and doses associated with steam generator removal during decommissioning. This report presents the results of recent PNL studies to provide supporting information in four areas concerning decommissioning of the reference PWR: updating the previous cost estimates to January 1986 dollars; assessing the cost and dose impacts of post-TMI-2 backfits; assessing the cost and dose impacts of recent steam generator replacements; and developing a scaling formula for plants different in size than the reference plant and an escalation formula for adjusting current cost estimates for future escalation

  1. Technology, safety and costs of decommissioning a refernce boiling water reactor power station: Technical support for decommissioning matters related to preparation of the final decommissioning rule

    International Nuclear Information System (INIS)

    Konzek, G.J.; Smith, R.I.

    1988-07-01

    Preparation of the final Decommissioning Rule by the Nuclear Regulatory Commission (NRC) staff has been assisted by Pacific Northwest Laboratory (PNL) staff familiar with decommissioning matters. These efforts have included updating previous cost estimates developed during the series of studies of conceptually decommissioning reference licensed nuclear facilities for inclusion in the Final Generic Environmental Impact Statement (FGEIS) on decommissioning; documenting the cost updates; evaluating the cost and dose impacts of post-TMI-2 backfits on decommissioning; developing a revised scaling formula for estimating decommissioning costs for reactor plants different in size from the reference boiling water reactor (BWR) described in the earlier study; and defining a formula for adjusting current cost estimates to reflect future escalation in labor, materials, and waste disposal costs. This report presents the results of recent PNL studies to provide supporting information in three areas concerning decommissioning of the reference BWR: updating the previous cost estimates to January 1986 dollars; assessing the cost and dose impacts of post-TMI-2 backfits; and developing a scaling formula for plants different in size than the reference plant and an escalation formula for adjusting current cost estimates for future escalation

  2. Safety Assessment for Decommissioning

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2013-06-15

    In the past few decades, international guidance has been developed on methods for assessing the safety of predisposal and disposal facilities for radioactive waste. More recently, it has been recognized that there is also a need for specific guidance on safety assessment in the context of decommissioning nuclear facilities. The importance of safety during decommissioning was highlighted at the International Conference on Safe Decommissioning for Nuclear Activities held in Berlin in 2002 and at the First Review Meeting of the Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management in 2003. At its June 2004 meeting, the Board of Governors of the IAEA approved the International Action Plan on Decommissioning of Nuclear Facilities (GOV/2004/40), which called on the IAEA to: ''establish a forum for the sharing and exchange of national information and experience on the application of safety assessment in the context of decommissioning and provide a means to convey this information to other interested parties, also drawing on the work of other international organizations in this area''. In response, in November 2004, the IAEA launched the international project Evaluation and Demonstration of Safety for Decommissioning of Facilities Using Radioactive Material (DeSa) with the following objectives: -To develop a harmonized approach to safety assessment and to define the elements of safety assessment for decommissioning, including the application of a graded approach; -To investigate the practical applicability of the methodology and performance of safety assessments for the decommissioning of various types of facility through a selected number of test cases; -To investigate approaches for the review of safety assessments for decommissioning activities and the development of a regulatory approach for reviewing safety assessments for decommissioning activities and as a basis for regulatory decision making; -To provide a forum

  3. Decommissioning in British Nuclear Fuels plc

    International Nuclear Information System (INIS)

    Colquhoun, A.

    1988-01-01

    Decommissioning projects at the BNFL Sellafield site have been selected taking the following into account; the need to gain experience in preparation for the decommissioning of the Magnox reactors and for the post Magnox stage; the need to develop larger scale projects; the need to be cost effective and to foster long term safety. The balance between prompt or delayed decommissioning has to consider operator dose uptake and radioactive waste management. The ten year plan for decommissioning at Sellafield is described briefly. Currently decommissioning is of the fuel pond and decanning plant, the Windscale Pile Chimneys, the coprecipitation plant and the uranium recovery plant. (author)

  4. Decommissioning techniques for research reactors. Final report of a co-ordinated research project 1997-2001

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2002-02-01

    In its international role, the IAEA is faced with a wide variety of national situations and different availability of technical, human and financial resources. While it is recognised that nuclear decommissioning is a mature industry in some developed countries, and may soon become a routine activity, the situation is by no means so clear in other countries. In addition, transfer of technologies and know-how from developed to developing countries is not a spontaneous, straightforward process, and will take time and considerable effort. As mandated by its own statute and Member States' requests, the IAEA continues to respond to its Member States by monitoring technological progress, ensuring development of safer and more efficient strategies and fostering international information exchange. Previous co-ordinated research projects (CRP) conducted respectively from 1984 to 1987, and from 1989 to 1993, investigated the overall domain of decommissioning. In those CRPs no distinction was made between decommissioning activities carried out at nuclear power plants, research reactors or nuclear fuel cycle facilities. With technological progress and experience gained, it became clear that decommissioning of research reactors had certain specific characteristics which needed a dedicated approach. In addition, a large number of research reactors reached a state of permanent shutdown in the 1990s and were candidates for prompt decommissioning. With the progressive ageing of research reactors, many more of these units will soon become redundant worldwide and require decommissioning. Within this context, a CRP on Decommissioning Techniques for Research Reactors was launched and conducted by the IAEA from 1997 to 2001 in order to prepare for eventual decommissioning. Concluding reports that summarized the work undertaken under the aegis of the CRP were presented at the third and final Research Co-ordination Meeting held in Kendal, United Kingdom, 14-18 May 2001, and are collected

  5. Decommissioning techniques for research reactors. Final report of a co-ordinated research project 1997-2001

    International Nuclear Information System (INIS)

    2002-02-01

    In its international role, the IAEA is faced with a wide variety of national situations and different availability of technical, human and financial resources. While it is recognised that nuclear decommissioning is a mature industry in some developed countries, and may soon become a routine activity, the situation is by no means so clear in other countries. In addition, transfer of technologies and know-how from developed to developing countries is not a spontaneous, straightforward process, and will take time and considerable effort. As mandated by its own statute and Member States' requests, the IAEA continues to respond to its Member States by monitoring technological progress, ensuring development of safer and more efficient strategies and fostering international information exchange. Previous co-ordinated research projects (CRP) conducted respectively from 1984 to 1987, and from 1989 to 1993, investigated the overall domain of decommissioning. In those CRPs no distinction was made between decommissioning activities carried out at nuclear power plants, research reactors or nuclear fuel cycle facilities. With technological progress and experience gained, it became clear that decommissioning of research reactors had certain specific characteristics which needed a dedicated approach. In addition, a large number of research reactors reached a state of permanent shutdown in the 1990s and were candidates for prompt decommissioning. With the progressive ageing of research reactors, many more of these units will soon become redundant worldwide and require decommissioning. Within this context, a CRP on Decommissioning Techniques for Research Reactors was launched and conducted by the IAEA from 1997 to 2001 in order to prepare for eventual decommissioning. Concluding reports that summarized the work undertaken under the aegis of the CRP were presented at the third and final Research Co-ordination Meeting held in Kendal, United Kingdom, 14-18 May 2001, and are collected

  6. Nuclear decommissioning

    International Nuclear Information System (INIS)

    Anon.

    1987-01-01

    The paper on nuclear decommissioning was presented by Dr H. Lawton to a meeting of the British Nuclear Energy Society and Institution of Nuclear Engineers, 1986. The decommissioning work currently being undertaken on the Windscale advanced gas cooled reactor (WAGR) is briefly described, along with projects in other countries, development work associated with the WAGR operation and costs. (U.K.)

  7. TA-2 Water Boiler Reactor Decommissioning Project

    International Nuclear Information System (INIS)

    Durbin, M.E.; Montoya, G.M.

    1991-06-01

    This final report addresses the Phase 2 decommissioning of the Water Boiler Reactor, biological shield, other components within the biological shield, and piping pits in the floor of the reactor building. External structures and underground piping associated with the gaseous effluent (stack) line from Technical Area 2 (TA-2) Water Boiler Reactor were removed in 1985--1986 as Phase 1 of reactor decommissioning. The cost of Phase 2 was approximately $623K. The decommissioning operation produced 173 m 3 of low-level solid radioactive waste and 35 m 3 of mixed waste. 15 refs., 25 figs., 3 tabs

  8. Summary of case studies presented at the WPDD topical session on stakeholder involvement in decommissioning projects - november 14, 2005

    International Nuclear Information System (INIS)

    Metcalfe, Doug

    2006-01-01

    Full text of publication follows: Two case studies were presented on experiences with stakeholder involvement in decommissioning projects. The first paper described the development of the United Kingdom Atomic Energy Authority's (UKAEA) stakeholder involvement activities for the Dounreay Nuclear Reactor Test Establishment. The second paper presented the US Nuclear Regulatory Commission regulatory process for decommissioning that includes opportunities for public involvement. The presentation contrasted the stakeholder involvement for two commercial US nuclear power plants (NPPs) that completed decommissioning in 2005, the Trojan NPP and the Maine Yankee NPP. The two case studies highlighted the importance of involving stakeholders in decommissioning projects, and provide important lessons learned. The Dounreay case study demonstrated the UKAEA's determination and commitment to continuously improve its stakeholder engagement program. In 2002, the UKAEA set out to broaden its stakeholder program by improving both public understanding and participation. With regard to public understanding, the UKAEA committed to keep the public informed on decommissioning developments, and ensure that communication was in an understandable form. To improve participation, the UKAEA actively worked to identify and engage stakeholders. The UKAEA then made efforts to involve stakeholders in decision-making activities, including the use of stakeholder panels to discuss and consider options for specific aspects of the Dounreay decommissioning and site restoration plan. In 2004, the UKAEA commissioned an independent review of its stakeholder involvement program to assess the program's effectiveness and benchmark it against best practices. The program was found to be useful, and positive feedback was provided on the use of stakeholder panels and the UKAEA's determination to deliver a broad based and effective stakeholder strategy. Recommendations to UKAEA included involving stakeholders

  9. Decommissioning of a mixed oxide fuel fabrication facility

    International Nuclear Information System (INIS)

    Buck, S.; Colquhoun, A.

    1990-01-01

    Decommissioning of the coprecipitation plant, which made plutonium/uranium oxide fuel, is a lead project in the BNFL Sellafield decommissioning programme. The overall programme has the objectives of gaining data and experience in a wide range of decommissioning operations and hence in this specific project to pilot the decommissioning of plant heavily contaminated with plutonium and other actinides. Consequently the operations have been used to test improvements in temporary containment, contamination control and decontamination methods and also to develop in situ plutonium assay, plutonium recovery and size-reduction methods. Finally the project is also yielding data on manpower requirements, personnel radiation uptake and waste arisings to help in the planning of future decommissioning projects

  10. Regulatory aspects of nuclear reactor decommissioning

    International Nuclear Information System (INIS)

    Ross, W.M.

    1990-01-01

    The paper discusses the regulatory aspects of decommissioning commercial nuclear power stations in the UK. The way in which the relevant legislation has been used for the first time in dealing with the early stages of decommissioning commercial nuclear reactor is described. International requirements and how they infit with the UK system are also covered. The discussion focusses on the changes which have been required, under the Nuclear Site Licence, to ensure that the licensee carries out of work of reactor decommissioning in a safe and controlled manner. (Author)

  11. Technical and cost aspects of radioactive wastes from decommissioning

    International Nuclear Information System (INIS)

    Claes, J.; Menon, S.

    2001-01-01

    The OECD Nuclear Energy Agency's Co-operative Programme on Decommissioning was established in 1985 to share the experience and information emerging from on-going decommissioning projects within member countries. The main aim of the programme is to gather and collate such data, which can then provide the basis for planning the future industrial phase of decommissioning of commercial nuclear plants. Starting with 10 decommissioning projects in 1985, today the programme has 35 participating projects from 12 countries. Apart from exchanging valuable information, task groups have been set up for in-depth analysis and studies of areas of common interest, among which are the recycling of material from decommissioning projects and decommissioning costs. This paper will describe the structure and mode of operation of the programme. Some of the results of the work in the task groups will be presented, with particular emphasis on the management of materials from decommissioning and on decommissioning costs. (author)

  12. Nuclear power plant decommissioning costs in perspective

    International Nuclear Information System (INIS)

    Rothwell, Geoffrey; Deffrennes, Marc; Weber, Inge

    2016-01-01

    At the international level, actual experience is limited in the completion of nuclear power plant decommissioning projects. Cost data for decommissioning projects are thus largely unavailable, with few examples of analyses or comparisons between estimates and actual costs at the project level. The Nuclear Energy Agency (NEA) initiated a project to address this knowledge gap and in early 2016 published the outcomes in the report on Costs of Decommissioning Nuclear Power Plants. The study reviews decommissioning costs and funding practices adopted by NEA member countries, based on the collection and analysis of survey data via a questionnaire. The work was carried out in co-operation with the International Atomic Energy Agency (IAEA) and the European Commission (EC). (authors)

  13. Nuclear power plants life extension and decommissioning its economic aspects

    International Nuclear Information System (INIS)

    Watanabe, Yoshiaki

    1994-06-01

    In USA where the development of nuclear power was started early, the life of nuclear power plants expires successively around the turn of century, and the serious hindrance to electric power supply is feared. Therefore, the research for extending 40 year approved period of operation is in progress. By the extension of life of nuclear power plants, huge cost reduction is estimated as compared with the construction of new plants. However, due to the rise of the cost for the life extension, there were the cases of forced decommissioning. In this book, the present state of the life extension of nuclear power stations, the economical assessment and analysis of the life extension by DOE, the economical assessment by MIDAS method of Electric Power Research Institute, the economical assessment by cost-benefit method of Northern States Power Co., the assessment of the long term operation possibility of nuclear power stations, the economical assessment system for the life extension in Japan, the present state of the decommissioning of nuclear power stations and that in USA, Canada and Europe, the assessment of the decommissioning cost by OECD/NEA, and the decommissioning cost for thermal power stations are described. (K.I.)

  14. Decommissioning of nuclear facilities: Feasibility, needs and costs

    International Nuclear Information System (INIS)

    DeLaney, E.G.; Mickelson, J.R.

    1985-01-01

    The Nuclear Energy Agency's Working Group on Decommissioning is preparing a study entitled ''Decommissioning of Nuclear Facilities: Feasibility, Needs and Costs.'' The study addresses the economics, technical feasibility and waste management aspects of decommissioning larger commercial reactors and nuclear support facilities. Experience on decommissioning small reactors and fuel cycle facilities shows that current technology is generally adequate. Several major projects that are either underway or planned will demonstrate decommissioning of the larger and more complex facilities. This experience will provide a framework for planning and engineering the decommissioning of the larger commercial reactors and fuel cycle facilities. Several areas of technology development are desired for worker productivity improvement, occupational exposure reduction, and waste volume reduction. In order to assess and plan for the decommissioning of large commercial nuclear facilities, projections have been made of the capacity of these facilities that may be decommissioned in the future and the radioactive waste that would be produced from the decommissioning of these facilities. These projections through the year 2025 are based on current data and the OECD reactor capacity forecast through the year 2000. A 25-year operating lifetime for electrical power generation was assumed. The possibilities of plant lifetime extension and the deferral of plant dismantlement make this projection very conservative

  15. Financing the Decommissioning of Nuclear Facilities

    International Nuclear Information System (INIS)

    2016-01-01

    Decommissioning of both commercial and R and D nuclear facilities is expected to increase significantly in the coming years, and the largest of such industrial decommissioning projects could command considerable budgets. It is important to understand the costs of decommissioning projects in order to develop realistic cost estimates as early as possible based on preliminary decommissioning plans, but also to develop funding mechanisms to ensure that future decommissioning expenses can be adequately covered. Sound financial provisions need to be accumulated early on to reduce the potential risk for residual, unfunded liabilities and the burden on future generations, while ensuring environmental protection. Decommissioning planning can be subject to considerable uncertainties, particularly in relation to potential changes in financial markets, in energy policies or in the conditions and requirements for decommissioning individual nuclear installations, and such uncertainties need to be reflected in regularly updated cost estimates. This booklet offers a useful overview of the relevant aspects of financing the decommissioning of nuclear facilities. It provides information on cost estimation for decommissioning, as well as details about funding mechanisms and the management of funds based on current practice in NEA member countries. (authors)

  16. Cost Estimating for Decommissioning of a Plutonium Facility--Lessons Learned From The Rocky Flats Building 771 Project

    International Nuclear Information System (INIS)

    Stevens, J. L.; Titus, R.; Sanford, P. C.

    2002-01-01

    The Rocky Flats Closure Site is implementing an aggressive approach in an attempt to complete Site closure by 2006. The replanning effort to meet this goal required that the life-cycle decommissioning effort for the Site and for the major individual facilities be reexamined in detail. As part of the overall effort, the cost estimate for the Building 771 decommissioning project was revised to incorporate both actual cost data from a recently-completed similar project and detailed planning for all activities. This paper provides a brief overview of the replanning process and the original estimate, and then discusses the modifications to that estimate to reflect new data, methods, and planning rigor. It provides the new work breakdown structure and discusses the reasons for the final arrangement chosen. It follows with the process used to assign scope, cost, and schedule elements within the new structure, and development of the new code of accounts. Finally, it describes the project control methodology used to track the project, and provides lessons learned on cost tracking in the decommissioning environment

  17. Several issues of uranium geology exploration facilities decommissioning

    International Nuclear Information System (INIS)

    Zhang Lu; Lu Caixia; Sheng Qing; Zhuang Jingqi; Xie Shujun; Liao Yunxuan

    2013-01-01

    The environmental protection completion acceptance review work of uranium geology exploration facilities 'llth five-year plan' decommissioned and remediation projects is introduced. Some questions related to norms and standards for uranium geology exploration facilities decommissioning and remediation, scheme of decommissioning and remediation, process inspection and acceptance of project and so on are discussed, and corresponding countermeasures and suggestions are put forward, Some references can be provided for the later development of uranium geological exploration facility '12th five-year plan' decommissioning and remediation projects. (authors)

  18. Development of a harmonized approach to safety assessment of decommissioning: Lessons learned from international experience (DeSa project)

    International Nuclear Information System (INIS)

    Percival, K.; Nokhamzon, J.-G.; Ferch, R.; Batandjieva, B.

    2006-01-01

    The number of nuclear facilities being or planned to be shutdown as they reach the end of their design life, due to accidents or other political and social factors has been increasing worldwide. This has led to an increase in the awareness of regulators and operators of the importance of development and implementation of adequate safety requirements and criteria for decommissioning of these facilities. A general requirement at international and national levels, even for new facilities to be commissioned, is the development of a decommissioning plan, which includes evaluation of potential radiological consequences to public and workers during planned and accidental decommissioning activities. Experience has been gained in the safety assessment of decommissioning at various sites with different complexities and hazard potentials. This experience shows that various approaches have been used in conducting safety assessments and that there is a need for harmonisation of these approaches and for transferring the good practice and lessons learned to other countries, in particular developing countries with limited financial and human resources. The IAEA launched an international project on Evaluation and Demonstration of Safety during Decommissioning (DeSa) in 2004 to provide a forum for exchange of lessons learned between site operators, regulators, safety assessors and other specialists in safety assessment of decommissioning of nuclear power plants, research reactors, laboratories, nuclear fuel cycle facilities, etc. This paper presents the lessons learned through the project up to date, i.e.; (i) a common approach to safety assessment is being applied worldwide with the following steps - establishment of assessment framework; description of the facility; definition of decommissioning activities; hazard identification and analysis; calculation of consequences; and analysis of results; (ii) a deterministic approach to safety assessment is most commonly applied; (iii) a

  19. A Decommissioning Information Management System

    Energy Technology Data Exchange (ETDEWEB)

    Park, S. K.; Hong, S. B.; Chung, U. S.; Park, J. H. [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2007-07-01

    In 1996, it was determined that research reactors, the KRR-1 and the KRR-2, would be shut down and dismantled. A project for the decommissioning of these reactors was launched in January 1997 with the goal of a completion by 2008. The total budget of the project was 19.4 million US dollars, including the cost for the waste disposal and for the technology development. The work scopes during the decommissioning project were the dismantling of all the facilities and the removal of all the radioactive materials from the reactor site. After the removal of the entire radioactivity, the site and buildings will be released for an unconditional use. A separate project for the decommissioning of the uranium conversion plant was initiated in 2001. The plant was constructed for the development of the fuel manufacturing technologies and the localization of nuclear fuels in Korea. It was shut downed in 1993 and finally it was concluded in 2000 that the plant would be decommissioned. The project will be completed by 2008 and the total budget was 9.2 million US dollars. During this project, all vessels and equipment will be dismantled and the building surface will be decontaminated to be utilized as general laboratories.

  20. Progress on the decommissioning of Zion nuclear generating station

    International Nuclear Information System (INIS)

    Moloney, B. P.; Hess, J.

    2013-01-01

    The decommissioning of the twin 1040 MWe PWRs at Zion, near Chicago USA is a ground breaking programme. The original owner, Exelon Nuclear Corporation, transferred the full responsibility for reactor dismantling and site license termination to a subsidiary of EnergySolutions. The target end state of the Zion site for return to Exelon will be a green field with the exception of the dry fuel storage pad. In return, ZionSolutions has access to the full value of the decommissioning trust fund. There are two potential attractions of this model: lower overall cost and significant schedule acceleration. The Zion programme which commenced in September 2010 is designed to return the cleared site with an Independent Spent Fuel Storage Installation (ISFSI) pad in 2020, 12 years earlier than planned by Exelon. The overall cost, at $500 M per full size power reactor is significantly below the long run trend of $750 M+ per PWR. Implementation of the accelerated programme has been underway for nearly three years and is making good progress. The programme is characterised by numerous projects proceeding in parallel. The critical path is defined by the inspection and removal of fuel from the pond and transfer into dry fuel storage casks on the ISFSI pad and completion of RPV segmentation. Fuel loading is expected to commence in mid- 2013 with completion in late 2014. In parallel, ZionSolutions is proceeding with the segmentation of the Reactor Vessel (RV) and internals in both Units. Removal of large components from Unit 1 is underway. Numerous other projects are underway or have been completed to date. They include access openings into both containments, installation of heavy lift crane capacity, rail upgrades to support waste removal from the site, radiological characterization of facilities and equipment and numerous related tasks. As at February 2013, the programme is just ahead of schedule and within the latest budget. The paper will provide a fuller update. The first two

  1. Progress on the decommissioning of Zion nuclear generating station

    Energy Technology Data Exchange (ETDEWEB)

    Moloney, B. P. [EnergySolutions EU Ltd, Swindon, Wiltshire (United Kingdom); Hess, J. [EnergySolutions LLC, Oak Ridge, TN (United States)

    2013-07-01

    The decommissioning of the twin 1040 MWe PWRs at Zion, near Chicago USA is a ground breaking programme. The original owner, Exelon Nuclear Corporation, transferred the full responsibility for reactor dismantling and site license termination to a subsidiary of EnergySolutions. The target end state of the Zion site for return to Exelon will be a green field with the exception of the dry fuel storage pad. In return, ZionSolutions has access to the full value of the decommissioning trust fund. There are two potential attractions of this model: lower overall cost and significant schedule acceleration. The Zion programme which commenced in September 2010 is designed to return the cleared site with an Independent Spent Fuel Storage Installation (ISFSI) pad in 2020, 12 years earlier than planned by Exelon. The overall cost, at $500 M per full size power reactor is significantly below the long run trend of $750 M+ per PWR. Implementation of the accelerated programme has been underway for nearly three years and is making good progress. The programme is characterised by numerous projects proceeding in parallel. The critical path is defined by the inspection and removal of fuel from the pond and transfer into dry fuel storage casks on the ISFSI pad and completion of RPV segmentation. Fuel loading is expected to commence in mid- 2013 with completion in late 2014. In parallel, ZionSolutions is proceeding with the segmentation of the Reactor Vessel (RV) and internals in both Units. Removal of large components from Unit 1 is underway. Numerous other projects are underway or have been completed to date. They include access openings into both containments, installation of heavy lift crane capacity, rail upgrades to support waste removal from the site, radiological characterization of facilities and equipment and numerous related tasks. As at February 2013, the programme is just ahead of schedule and within the latest budget. The paper will provide a fuller update. The first two

  2. Structure and function design for nuclear facilities decommissioning information database

    International Nuclear Information System (INIS)

    Liu Yongkuo; Song Yi; Wu Xiaotian; Liu Zhen

    2014-01-01

    The decommissioning of nuclear facilities is a radioactive and high-risk project which has to consider the effect of radiation and nuclear waste disposal, so the information system of nuclear facilities decommissioning project must be established to ensure the safety of the project. In this study, by collecting the decommissioning activity data, the decommissioning database was established, and based on the database, the decommissioning information database (DID) was developed. The DID can perform some basic operations, such as input, delete, modification and query of the decommissioning information data, and in accordance with processing characteristics of various types of information data, it can also perform information management with different function models. On this basis, analysis of the different information data will be done. The system is helpful for enhancing the management capability of the decommissioning process and optimizing the arrangements of the project, it also can reduce radiation dose of the workers, so the system is quite necessary for safe decommissioning of nuclear facilities. (authors)

  3. NPP A-1 decommissioning - Phase I

    International Nuclear Information System (INIS)

    Krstenik, A.; Blazek, J.

    2000-01-01

    Nuclear power plant A-1 with output 150 MW e , with metallic natural uranium fuelled, CO 2 cooled and heavy water moderated reactor had been prematurely finally shut down in 1977. It is necessary to mention that neither operator nor regulatory and other authorities have been prepared for the solution of such situation. During next two consecutive years after shutdown main effort of operator focused on technical and administrative activities which are described in the previous paper together with approach, condition and constraints for NPP A-1 decommissioning as well as the work and research carried out up to the development and approval of the Project for NPP A-1 decommissioning - I. phase. Subject of this paper is description of: (1) An approach to NPP A -1 decommissioning; (2) An approach to development of the project for NPP A-1 decommissioning; (3) Project - tasks, scope, objectives; (4) Mode of the Project realisation; (5) Progress achieved up to the 1999 year. (authors)

  4. Decontamination and decommissioning of the initial engine test facility and the IET two-inch hot-waste line

    International Nuclear Information System (INIS)

    Stoll, F.E.

    1987-04-01

    The Initial Engine Test Decommissioning Project is described in this report. The Initial Engine Test facility was constructed and operated at the National Reactor Testing Station, now known as the Idaho National Engineering Laboratory, to support the Aircraft Nuclear Propulsion Program and the Systems for Nuclear Auxiliary Power Transient test program, circa 1950 through 1960s. Due to the severe nature of these nuclear test programs, a significant amount of radioactive contamination was deposited in various portions of the Initial Engine Test Facility. Characterizations, decision analyses, and plans for decontamination and decommissioning were prepared from 1982 through 1985. Decontamination and decommissioning activities were performed in such a way that no radiological health or safety hazard to the public or to personnel at the Idaho National Engineering Laboratory remains. These decontamination and decommissioning activities began in 1985 and were completed in 1987. 13 figs

  5. Nuclear decommissioning

    Energy Technology Data Exchange (ETDEWEB)

    Lawton, H.

    1987-02-01

    Sufficient work has now been done, on a world-wide basis, to justify confidence that full decommissioning of nuclear installations, both plant and reactors, can be carried out safely and efficiently. Projects in several countries should confirm this in the next few years. In the UK, good progress has been made with the WAGR and supporting development work is finding solutions to resolve uncertainties. Estimates from several sources suggest that decommissioning costs can be kept to an acceptable level.

  6. History of radiological characterisation in Studsvik - History of radiological characterisation in decommissioning projects in Studsvik

    International Nuclear Information System (INIS)

    Hedvall, Robert

    2012-01-01

    AB SVAFO is a nuclear waste technology and decommissioning company based in Sweden in the scenic surroundings of Studsvik on the Baltic coast. SVAFO is owned by the Swedish nuclear power industry. The company was created in 1992 by Sydsvenska Vaermekraft AB, Vattenfall AB, Forsmarks Kraftgrupp AB and Oskarshamns Kraftgrupp AB as a consequence of the Act on the Financing of the Management of Certain Radioactive Waste etc, from 1988. AB SVAFO's main business is to take care of formerly state-owned spent nuclear waste at the site, including small amounts of nuclear fuel. Buildings are also included, mainly nuclear waste storage buildings and a research reactor. Some buildings have already been decommissioned and all the fuel is treated. In the past 30 years, various decommissioning projects have been carried out, encompassing areas such as an underground research reactor, a Van de Graaff accelerator, 15,000 m 2 of nuclear laboratories, two 150 m 3 underground concrete sludge silos and several waste-storage buildings. Up till now only one or two persons did a simple characterisation before the project started to get the level of contamination. With the start of the decommissioning of the former uranium mine in Ranstad and the R2-reactor, more efforts have been put for the characterisation. The change in methods will be described. (author)

  7. The decommissioning of nuclear power stations. France and the American experience

    International Nuclear Information System (INIS)

    Tonnac, Alain de; Perves, Jean-Pierre

    2013-01-01

    After having noticed that many electronuclear reactors have already been stopped, and that some research reactors have just been dismantled in Grenoble by the CEA, and evoked the main involved actors (ASN, IRSN, ANDRA), some characteristics of the French situation are outlined: the strategy adopted by EDF for a fast dismantling process, the long legal delays for stopping, dismantling and downgrading of sites, the absence of waste radioactivity release thresholds, and the responsibility of operators for dismantling operations. The main steps of a station dismantling are indicated and discussed: end of exploitation; steps of deconstruction (evacuation of big components, elimination of building radioactivity, building destruction, site partial or total reconversion). The French authorization process is briefly commented. Then, the American experience and situation is commented in terms of number of concerned sites, of site situation, but also in terms of organisation and selected technologies. Critical steps are outlined as well as improvements obtained in terms of exposure, of waste volumes, of effluent filtration capacities, and of cutting methods. The next part proposes an overview of the situation or steps of decommissioning in France for different sites: the Chooz PWR, the fleet of first generation reactors, graphite gas reactors, the Brennilis power station and Super Phenix in Creys Malville. Costs and delays are briefly evoked for the USA as well as for France

  8. An overview of the U.S. Department of Energy Experimental Boiling Water Reactor Decontamination and Decommissioning Project

    International Nuclear Information System (INIS)

    Murphie, W.E.; Mckernan, M.L.

    1991-01-01

    This paper provides an overview of the U.S. Department of Energy's (DOE) Experimental Boiling Water Reactor (EBWR) Decontamination and Decommissioning (D and D) Project. Physical decommissioning work started in 1986 and is scheduled for completion in 1994. The project total estimated cost is 14.3 million (1990, U.S.) dollars. The reactor pressure vessel will be removed by segmentation. Another notable project feature is that D and D operations were planned for and carried out with a small work force comprised of four to six D and D laborers, one or two health physics technicians, an engineer, and a project manager. When the D and D work is completed the facility will be recycled for other productive uses. (author)

  9. Study on decommissioning

    International Nuclear Information System (INIS)

    2012-01-01

    This project consists of researches on (1) establishment of review plan on application of decommissioning, (2) establishment of specific method to confirm decommissioning completion, of decommissioning and (3) establishment of radioactive waste management guideline during dismantling and (4) development of the regulatory system on decommissioning in response to Fukushima Daiichi NPP accident. About researches on establishment of review plan on application of decommissioning. 'Planning of the Commercial Power Reactor Decommissioning:2001' which was published by Atomic Energy Society of Japan, was evaluated whether it suited the requirement for the decommissioning stipulated in the law, and the draft evaluation report was prepared. About researches on establishment of specific method to confirm decommissioning completion, technical information of practical procedures on the confirmation in U.S.A. were organized based on MARSSIM (Multi-Agency Radiation Survey and Site Investigation Manual, NUREG-1575) and applicability of MARSSIM on the confirmation in Japan was examined. Exposed doses for public during decommissioning period were estimated to study dose criterion of the confirmation. Radioactive concentrations in the soil of Tokai and Hamaoka NPP caused by the Fukushima Daiichi NPP accident were also investigated. About researches on establishment of radioactive waste management guideline during dismantling, one concrete core was sampled in biological shield of the Tokai NPP and radioactive concentrations were investigated. About researches on development of the regulatory system on decommissioning in response to Fukushima Daiichi NPP accident, present status of Three Mile Island Unit 2 and Chernobyl NPP Unit 4 were investigated. Present status of regulatory systems for decommissioning in foreign countries taken in consideration of the accident was also researched. (author)

  10. Decommissioning nuclear facilities

    International Nuclear Information System (INIS)

    Buck, S.

    1996-01-01

    Nuclear facilities present a number of problems at the end of their working lives. They require dismantling and removal but public and environmental protection remain a priority. The principles and strategies are outlined. Experience of decommissioning in France and the U.K. had touched every major stage of the fuel cycle by the early 1990's. Decommissioning projects attempt to restrict waste production and proliferation as waste treatment and disposal are costly. It is concluded that technical means exist to deal with present civil plant and costs are now predictable. Strategies for decommissioning and future financial provisions are important. (UK)

  11. 3D based integrated support concept for improving safety and cost-efficiency of nuclear decommissioning projects

    International Nuclear Information System (INIS)

    Szoeke, Istvan

    2016-01-01

    New concepts enabled by emerging computing technologies based on 3D simulation, virtual (VR) and augmented reality (AR), advanced user interfaces (UI), mobile and wearable computing devices, and geographical information systems have great potential for improving nuclear decommissioning strategies. Such techniques offer very effective new opportunities for improving early characterisation and strategical decision making, knowledge management, on-site management of radiological waste, and regulatory compliance. In addition, such methods allow for an effective training of foreseen decommissioning workers to begin during operation and transition phase without disturbance to normal operation of the plant. Improved plant information systems enabled by 3D simulation, advanced user interface, and mobile computing technologies, offer better ways for acquiring and managing the radiological and other plant information that are required for informed decision making in the early planning phase of decommissioning activities. User friendly, realistic management and visualisation of available radiological information, and results of radiological data analyses, allows decision makers to have a better understanding of the radiological conditions expected when decontamination and dismantling work starts, without high need for physical presence in the environment. Such functionalities, combined with capabilities for easy evaluation of possible decommissioning (decontamination, dismantling) options allow decision makers to make informed decisions, and enable a seamless communication (common language) within a multidisciplinary decommissioning planning team. Support systems, enabled by modern information technologies are expected to improve information and knowledge management in decommissioning projects, especially during transition from the operation phase. Traditionally, inefficient transfer of knowledge from the design and operation phase, results in suboptimal work strategies and

  12. Development of a Decommissioning Certificate Program

    International Nuclear Information System (INIS)

    Morton, M. R.

    1999-01-01

    A Decommissioning Certificate Program has been developed at Washington State University Tri-Cities (WSU TC) in conjunction with Bechtel Hanford, Inc. (BHI), and the U.S. Department of Energy (DOE)to address the increasing need for qualified professionals to direct and manage decommissioning projects. The cooperative effort between academia, industry, and government in the development and delivery of this Program of education and training is described, as well as the Program's design to prepare students to contribute sooner, and at a higher level, to decommissioning projects

  13. Decommissioning of the ASTRA research reactor - planning, executing and summarizing the project

    International Nuclear Information System (INIS)

    Meyer, F.

    2010-01-01

    The decommissioning of the ASTRA research reactor at the Austrian Research Centres Seibersdorf was described within three technical papers already released in Nuclear Technology and Radiation Protection throughout the years 2003, 2006, and 2008. Following a suggestion from IAEA the project was investigated well after the files were closed regarding rather administrative than technical matters starting with the project mission, explaining the project structure and identifying the key factors and the key performance indicators. The continuous documentary and reporting system as implemented to fulfil the informational needs of stakeholders, management, and project staff alike is described. Finally the project is summarized in relationship to the performance indicators. (author)

  14. SGDes project. Decommissioning management system of Enresa

    International Nuclear Information System (INIS)

    Fernandez Lopez, M.; Julian, A. de

    2013-01-01

    ENRESA, the public company responsible for managing radioactive waste produced in spain and nuclear facilities decommissioning work, has developed a management information system (SGDes) for the decommissioning of nuclear power plants, critical for the company. SGDes system is capable of responding to operational needs for efficient, controlled and secure way. Dismantling activities require a rigorous operations control within highly specialized, process systematization and safety framework, both the human and technological point of view. (Author)

  15. Use of data processing tools in decommissioning nuclear facilities

    International Nuclear Information System (INIS)

    Petrasch, P.; Lukacs, G.

    1995-01-01

    With the present level of electronic data processing technology, no project of the scale of nuclear reactor decommissioning could be carried out without the use of data processing systems. On the contrary, a reactor decommissioning project requires essential support not only for the technical but also the economic side through the use of proper data processing programs, and not only general applications in the area of personal computers such as MS-EXCEL or MS Project, but also special data processing systems designed for the reactor decommissioning tasks. Various data processing supports are required depending upon the progress of a reactor decommissioning project. (orig./DG) [de

  16. Nuclear decommissioning

    International Nuclear Information System (INIS)

    Lawton, H.

    1987-01-01

    Sufficient work has now been done, on a world-wide basis, to justify confidence that full decommissioning of nuclear installations, both plant and reactors, can be carried out safely and efficiently. Projects in several countries should confirm this in the next few years. In the UK, good progress has been made with the WAGR and supporting development work is finding solutions to resolve uncertainties. Estimates from several sources suggest that decommissioning costs can be kept to an acceptable level. (author)

  17. Estimating of funding levels for decommissioning

    International Nuclear Information System (INIS)

    Sieving, K.W.

    1985-01-01

    In order to meet its public service obligations, an electric utility must attain the following objectives: Recognize future power requirements early, and take appropriate actions to satisfy them; Construct new generating, transmission and distribution facilities in a timely and economical manner; Operate its facilities safely, and maintain them without decreasing the quality and reliability of service. In the case of a nuclear electric generating station, the third objective includes the obligation to decommission the station following shutdown at the end of its useful life and to dispose of residual radioactivity in accordance with Nuclear Regulatory Commission guidelines, as a part of the process of terminating the NRC license. In the case of an investor-owned electric utility, the third objective includes the additional duty to estimate the cost of decommissioning for ratemaking purposes, since the funds required for this future event must be collected over the life of the generating station from the consumers who enjoy the benefits of its output. This article deals with these issues

  18. Procedures and Practices - Challenges for Decommissioning Management and Teamwork

    Energy Technology Data Exchange (ETDEWEB)

    Rindahl, G., E-mail: grete.rindahl@hrp.no [Institute for Energy Technology, Halden (Norway)

    2013-08-15

    The mental and practical approach to a decommissioning project is often not the same at all levels of an organization. Studies indicate that the early establishment of a decommissioning mindset throughout an organization is an important and frequently overlooked process. It is not enough to establish procedures, if practices and mental approaches are overlooked; and for decommissioning projects that are more often than not dominated by one of a kind problem solving, procedure design is challenging, and new requirements are put on communication. Our research considers stakeholder involvement in these processes in the wider sense of the term; however the main stakeholders in focus are regulators and the work force that will perform or lead the tasks related to decommissioning. Issues here treated include: Decommissioning mindset and the manifestation of mindset issues in decommissioning projects, including challenges and prospective solutions; trust building and trust breaking factors in communication and collaboration relevant to transition and decommissioning; new technologies for collaboration and communication and how these may impair or empower participants - experiences from several domains. This paper is based on work done in collaboration with the OECD NEA Halden Reactor Project. (author)

  19. Decommissioning project readiness reviews at the Department of Energy's Hanford, Washington, Site

    International Nuclear Information System (INIS)

    Speer, D.R.; Holmes, P.A.

    1987-01-01

    Two Hanford Site contractors independently formulated readiness review methods to prepare for decontamination and decommissioning (D and D) projects. One readiness review method provided an independent management review process. The other method provided a review by personnel directly involved in the project and concise documentation procedures. A unified system is now used at Hanford which combines the best aspects of both readiness review methods. The unified method assigns category levels based on certain job characteristics. The category assigned to the project then indicates the required level of management review prior to proceeding with the D and D project. In addition, the concise documentation procedures are now used for all category levels

  20. ECED 2013: Eastern and Central Europe Decommissioning. International Conference on Decommissioning of Nuclear Facilities. Conference Guide and Book of Abstracts

    International Nuclear Information System (INIS)

    2013-01-01

    The Conference included the following sessions: (I) Opening session (2 contributions); (II) Managerial and Funding Aspects of Decommissioning (5 contributions); (III) Technical Aspects of Decommissioning I (6 contributions); (IV) Experience with Present Decommissioning Projects (4 contributions); (V) Poster Session (14 contributions); (VI) Eastern and Central Europe Decommissioning - Panel Discussion; (VII) Release of Materials, Waste Management and Spent Fuel Management (6 contributions); (VIII) Technical Aspects of Decommissioning II (5 contributions).

  1. Guidelines of Decommissioning Schedule Establishment

    Energy Technology Data Exchange (ETDEWEB)

    Oh, Jae Yong; Yun, Taesik; Kim, Younggook; Kim, Hee-Geun [KHNP CRI, Daejeon (Korea, Republic of)

    2016-10-15

    Decommissioning has recently become an issue highlighted in Korea due to the Permanent Shutdown (PS) of Kori-1 plant. Since Korea Hydro and Nuclear Power (KHNP) Company decided the PS of Kori-1 instead of further continued operation, Kori-1 will be the first decommissioning plant of the commercial reactors in Korea. Korean regulatory authority demands Initial Decommissioning Plan (IDP) for all the plants in operation and under construction. In addition, decommissioning should be considered for the completion of the life cycle of NPPs. To date, Korea has no experience regarding decommissioning of the commercial reactor and a lot of uncertainties will be expected due to its site-specific factors. However, optimized decommissioning process schedule must be indispensable in the safety and economic efficiency of the project. Differed from USA, Korea has no experience and know-hows of the operation and site management for decommissioning. Hence, in Korea, establishment of decommissioning schedule has to give more weight to safety than precedent cases. More economical and rational schedule will be composed by collecting and analyzing the experience data and site-specific data and information as the decommissioning progresses. In a long-range outlook, KHNP having capability of NPP decommissioning will try to decommissioning business in Korea and foreign countries.

  2. Nuclear decommissioning

    International Nuclear Information System (INIS)

    Lawton, H.

    1987-01-01

    Sufficient work has now been done, on a world-wide basis, to justify confidence that full decommissioning of nuclear installations, both plant and reactors, can be carried out safely and efficiently. Projects in several countries should confirm this in the next few years. In the United Kingdom, good progress has been made with the Windscale Advanced Gas-cooled Reactor and supporting development work is finding solutions to resolve uncertainties. Estimates from several sources suggest that decommissioning costs can be kept to an acceptable level. (author)

  3. Planning, Management and Organizational Aspects of the Decommissioning of Nuclear Facilities

    International Nuclear Information System (INIS)

    2013-08-01

    Many old reactors and other nuclear facilities worldwide are being actively dismantled or are candidates for decommissioning in the near term. A significant number of these facilities are located in Member States having little experience or expertise in planning and implementing state of the art decommissioning projects. Planning, management and organization are critical for the success of such projects. The main objective of IAEA technical activities related to decommissioning is to promote the exchange of lessons learned, thereby contributing to successful planning and implementation of decommissioning projects. Imperative for success is a better understanding of the decision making process, the comparison and selection of decommissioning plans and organizational provisions, and relevant issues affecting the entire decommissioning process. Topics addressed in this publication include details on development of the decommissioning plan, structuring of key project tasks, organizing the project management team, identifying key staffing positions and determining required workforce skills, and managing the transition from an operational phase to the decommissioning phase. It is expected that this project, and in particular the papers collected in this publication, will draw Member States' attention to the practicality and achievability of timely planning and smooth management of decommissioning projects, especially for smaller projects. Concluding reports summarizing the work undertaken under the aegis of a coordinated research project (CRP) on planning, management and organizational aspects in the decommissioning of nuclear facilities, and presented at the third and final research coordination meeting (RCM) held in Da Lat, Vietnam, 5-9 September 2011, are included in this publication. Operating experience and lessons learned during full scale applications, as well as national programmes and plans, are among the most significant achievements of the CRP and have been

  4. Planning, Management and Organizational Aspects of the Decommissioning of Nuclear Facilities

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2013-08-15

    Many old reactors and other nuclear facilities worldwide are being actively dismantled or are candidates for decommissioning in the near term. A significant number of these facilities are located in Member States having little experience or expertise in planning and implementing state of the art decommissioning projects. Planning, management and organization are critical for the success of such projects. The main objective of IAEA technical activities related to decommissioning is to promote the exchange of lessons learned, thereby contributing to successful planning and implementation of decommissioning projects. Imperative for success is a better understanding of the decision making process, the comparison and selection of decommissioning plans and organizational provisions, and relevant issues affecting the entire decommissioning process. Topics addressed in this publication include details on development of the decommissioning plan, structuring of key project tasks, organizing the project management team, identifying key staffing positions and determining required workforce skills, and managing the transition from an operational phase to the decommissioning phase. It is expected that this project, and in particular the papers collected in this publication, will draw Member States' attention to the practicality and achievability of timely planning and smooth management of decommissioning projects, especially for smaller projects. Concluding reports summarizing the work undertaken under the aegis of a coordinated research project (CRP) on planning, management and organizational aspects in the decommissioning of nuclear facilities, and presented at the third and final research coordination meeting (RCM) held in Da Lat, Vietnam, 5-9 September 2011, are included in this publication. Operating experience and lessons learned during full scale applications, as well as national programmes and plans, are among the most significant achievements of the CRP and have been

  5. Investigations on the decommissioning of nuclear facilities

    International Nuclear Information System (INIS)

    Goertz, R.; Bastek, H.; Doerge, W.; Kruschel, K.P.

    1985-01-01

    The study discusses and evaluates safety and licensing related aspects associated with the decommissioning of nuclear power plants. Important decommissioning projects and experiences with relevance to decommissioning are analyzed. Recent developments in the field of decommissioning techniques with the potential of reducing the occupational dose to decommissioning workers are described and their range of application is discussed. The radiological consequences of the recycling of scrap metal arising during decommissioning are assessed. The results may be used to evaluate present licensing practices and may be useful for future licensing procedures. Finally the environmental impact of radionuclide release via air and water pathways associated with decommissioning activities is estimated. (orig.) [de

  6. Treatment of Decommissioning Combustible Wastes with Incineration Technology

    Energy Technology Data Exchange (ETDEWEB)

    Min, B. Y. Min; Yang, D. S.; Yun, G. S.; Lee, K. W.; Moon, J. K. [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2015-05-15

    The aim of the paper is current status of management for the decommissioning radioactive combustible and metal waste in KAERI. In Korea, two decommissioning projects were carried out for nuclear research facilities (KRR-1 and KRR-2) and a uranium conversion plant (UCP). Through the two decommissioning projects, lots of decommissioning wastes were generated. Decommissioning waste can be divided into radioactive waste and releasable waste. The negative pressure of the incineration chamber remained constant within the specified range. Off-gas flow and temperature were maintained constant or within the desired range. The measures gases and particulate materials in the stack were considerably below the regulatory limits. The achieved average volume reduction ratio during facility operation is about 1/65.

  7. Strategically oriented project management of the decommissioning of nuclear power plants; Strategieorientiertes Projektmanagement der Stilllegung von Kernkraftwerken

    Energy Technology Data Exchange (ETDEWEB)

    Kemmeter, Sascha [Conscore GmbH, Duesseldorf (Germany); Woempener, Andreas [Duisburg-Essen Univ., Duisburg (Germany). Lehrstuhl fuer ABWL und Controlling

    2013-12-15

    Due to the politically induced change of the energy sector in Germany, the operators of nuclear power plants had to react and to deal with completely new conditions concerning the decommissioning of their plants on short notice. Therefore the operators have to devise new strategies for controlling their decommissioning and dismantling projects in a short amount of time and most often similarly for several plants. Two fundamental procedures are possible for the successful controlling of these dismantling projects: a centralized or a decentralized management organization. How these project control processes can be realized in an optimal way, is, next to other economic specifications of the dismantling of nuclear power plants, the topic of a new research project of the Chair of Management Accounting at the University Duisburg-Essen. In that process, results and experiences from other research and practical projects concerning general large-scale projects are being used. Selected findings have been compiled and are being discussed in this paper. (orig.)

  8. Proceedings of the topical session on stakeholder involvement in decommissioning projects

    International Nuclear Information System (INIS)

    Santiago, Juan Luis; Chandler, Steve; Metcalfe, Doug; Le Bars, Yves

    2006-01-01

    Set up by the Radioactive Waste Management Committee (RWMC), the WPDD brings together senior representatives of national organisations who have a broad overview of Decommissioning and Dismantling (D and D) issues through their work as regulators, implementers, R and D experts or policy makers. These include representatives from regulatory authorities, industrial decommissioners from the NEA Co-operative Programme on Exchange of Scientific and Technical Information on Nuclear Installation Decommissioning Projects (CPD), and cross-representation from the other NEA Committees. The EC is a member of the WPDD and the IAEA is participating as an observer. This broad participation provides good possibilities for the co-ordination efforts amongst activities in the international programmes. At its sixth meeting, in Paris, 14-16 November 2005, the WPDD held a topical session on the 'Stakeholder Involvement in Decommissioning Projects'. The topical session was jointly planned and run with members of the NEA Forum on Stakeholder Confidence (FSC). This report documents the topical session. The main text summarises the lessons learnt and includes the rapporteurs reports. Appendix 1 and 2 provide the agenda of the topical session and all contributed papers respectively. The Topical session also provided a stimuli to review all the contributions in the area of stakeholder involvement that the WPDD has received since its inception. A list of references is provided in Appendix 3. The topical session was meant to provide an exchange of information and experience on the following issues: - Views from Stakeholders Regarding Stakeholder Involvement and Their Own Role. - Case Studies on Stakeholders Confidence. At the end of each session time was allotted for a plenary discussion. The Rapporteur reviewed the main points and the lessons learnt at the end of the whole Topical Session. (authors)

  9. An outsider's view of decommissioning

    International Nuclear Information System (INIS)

    Wilkie, T.

    1996-01-01

    The decommissioning of nuclear facilities is not just a technical or even a financial issue. Presenting decommissioning as a technically difficult task overcome by superhuman effort on the part of the industry will not gain much credit amongst sophisticated consumers who now require that any complex technology will work and work safely. Any engineering problems are surmountable given the money to find the solution. Some of the financial aspects of decommissioning are worrying, however, given their open-ended nature. The cost of waste disposal is one of these. Despite a lapse of fifty years since the start-up of its first reactor, the United Kingdom is unlikely to have available a repository for the disposal of intermediate level waste until about 2020. Waste disposal is a large consideration in decommissioning and the industry's forecasts of cost in this area lack credibility in the light of a poor track record in financial prediction. Financial engineering in the form of the segregated fund set up in March 1996 to cover the decommissioning of nuclear power stations in the United Kingdom is likely to provide only short term reassurance in the light of doubts about a credible future for nuclear power. This lack of confidence over the wider problems of nuclear power creates particular problems for decommissioning which go beyond technical difficulties and complicate financial considerations. (UK)

  10. Development of a Decommissioning Certificate Program; TOPICAL

    International Nuclear Information System (INIS)

    M. R. Morton

    1999-01-01

    A Decommissioning Certificate Program has been developed at Washington State University Tri-Cities (WSU TC) in conjunction with Bechtel Hanford, Inc. (BHI), and the U.S. Department of Energy (DOE)to address the increasing need for qualified professionals to direct and manage decommissioning projects. The cooperative effort between academia, industry, and government in the development and delivery of this Program of education and training is described, as well as the Program's design to prepare students to contribute sooner, and at a higher level, to decommissioning projects

  11. Decommissioning of Active Ventilation Systems in a Nuclear R and D Facility to Prepare for Building Demolition (Whiteshell Laboratories Decommissioning Project, Canada) - 13073

    International Nuclear Information System (INIS)

    Wilcox, Brian; May, Doug; Howlett, Don; Bilinsky, Dennis

    2013-01-01

    Whiteshell Laboratories (WL) is a nuclear research establishment owned by the Canadian government and operated by Atomic Energy of Canada Limited (AECL) since the early 1960's. WL is currently under a decommissioning license and the mandate is to remediate the nuclear legacy liabilities in a safe and cost effective manner. The WL Project is the first major nuclear decommissioning project in Canada. A major initiative underway is to decommission and demolish the main R and D Laboratory complex. The Building 300 R and D complex was constructed to accommodate laboratories and offices which were mainly used for research and development associated with organic-cooled reactors, nuclear fuel waste management, reactor safety, advanced fuel cycles and other applications of nuclear energy. Building 300 is a three storey structure of approximately 16,000 m 2 . In order to proceed with building demolition, the contaminated systems inside the building have to be characterized, removed, and the waste managed. There is a significant focus on volume reduction of radioactive waste for the WL project. The active ventilation system is one of the significant contaminated systems in Building 300 that requires decommissioning and removal. The active ventilation system was designed to manage hazardous fumes and radioactivity from ventilation devices (e.g., fume hoods, snorkels and glove boxes) and to prevent the escape of airborne hazardous material outside of the laboratory boundary in the event of an upset condition. The system includes over 200 ventilation devices and 32 active exhaust fan units and high efficiency particulate air (HEPA) filters. The strategy to remove the ventilation system was to work from the laboratory end back to the fan/filter system. Each ventilation duct was radiologically characterized. Fogging was used to minimize loose contamination. Sections of the duct were removed by various cutting methods and bagged for temporary storage prior to disposition

  12. Action Memorandum for Decommissioning the Engineering Test Reactor Complex under the Idaho Cleanup Project

    International Nuclear Information System (INIS)

    A. B. Culp

    2007-01-01

    This Action Memorandum documents the selected alternative for decommissioning of the Engineering Test Reactor at the Idaho National Laboratory under the Idaho Cleanup Project. Since the missions of the Engineering Test Reactor Complex have been completed, an engineering evaluation/cost analysis that evaluated alternatives to accomplish the decommissioning of the Engineering Test Reactor Complex was prepared and released for public comment. The scope of this Action Memorandum is to encompass the final end state of the Complex and disposal of the Engineering Test Reactor vessel. The selected removal action includes removing and disposing of the vessel at the Idaho CERCLA Disposal Facility and demolishing the reactor building to ground surface

  13. Demonstration of safety of decommissioning of facilities using radioactive material

    International Nuclear Information System (INIS)

    Batandjieva, Borislava; O'Donnell, Patricio

    2008-01-01

    Full text:The development of nuclear industry worldwide in the recent years has particular impact on the approach of operators, regulators and interested parties to the implementation of the final phases (decommissioning) of all facilities that use radioactive material (from nuclear power plants, fuel fabrication facilities, research reactors to small research or medical laboratories). Decommissioning is becoming an increasingly important activity for two main reasons - termination of the practice in a safe manner with the view to use the facility or the site for other purposes, or termination of the practice and reuse the facility or site for new built nuclear facilities. The latter is of special relevance to multi-facility sites where for example new nuclear power plants and envisaged. However, limited countries have the adequate legal and regulatory framework, and experience necessary for decommissioning. In order to respond to this challenge of the nuclear industry and assist Member States in the adequate planning, conduct and termination of decommissioning of wide range of facilities, over the last decade the IAEA has implemented and initiated several projects in this field. One of the main focuses of this assistance to operators, regulators and specialists involved in decommissioning is the evaluation and demonstration of safety of decommissioning. This importance of these Agency activities was also highlighted in the International Action Plan on Decommissioning, during the second Joint Convention meeting in 2006 and the International Conference on Lessons Learned from Decommissioning in Athens in 2006. The IAEA has been providing technical support to its Member States in this field through several mechanisms: (1) the establishment of a framework of safety standards on decommissioning and development of a supporting technical documents; (2) the establishment of an international peer review mechanism for decommissioning; (3) the technical cooperation projects

  14. Sizewell 'B' power station public inquiry: CEGB proof of evidence

    International Nuclear Information System (INIS)

    Gregory, A.R.

    1982-11-01

    The procedure for decommissioning a CEGB nuclear power station is described. Regulatory and licensing procedures in the UK are first listed. The principal sources of radioactivity in the station after final shutdown are classified. The three stages of the decommissioning procedure are then described. Finally the following topics are dealt with briefly: the management of decommissioning wastes, radiological protection during the operation, possible faults arising having radiological significance, design for decommissioning and costs. (U.K.)

  15. Decommissioning and demolition 1992

    International Nuclear Information System (INIS)

    Whyte, I.L.

    1992-01-01

    The decommissioning and demolition of structures offshore, onshore and in nuclear works involves new technologies and industries in demolition and removal. The aim of the conference was to provide a forum to keep up to date with technological developments, to publicise new techniques and to share and discuss present and future plans. A particular feature was the multi-disciplinary approach to promote and encourage communication between different sectors of this difficult field of operations. The conference emphasised not only technical issues but also legislative, management and health and safety aspects. Papers were presented by practising engineers, contractors and research workers involved in offshore structures, buildings, power stations, contaminated sites, nuclear plant and includes specialist techniques of cutting, lifting, explosives, ground treatment and decontamination. Many valuable case histories and records based on practical experience were reported. The volume provides a reference source on the state-of-the-art in decommissioning and demolition. The ten papers relevant to the decommissioning and demolition of nuclear facilities are indexed separately. (Author)

  16. The decommissioning of nuclear facilities

    International Nuclear Information System (INIS)

    Niel, J.Ch.; Rieu, J.; Lareynie, O.; Delrive, L.; Vallet, J.; Girard, A.; Duthe, M.; Lecomte, C.; Rozain, J.P.; Nokhamzon, J.G.; Davoust, M.; Eyraud, J.L.; Bernet, Ph.; Velon, M.; Gay, A.; Charles, Th.; Leschaeva, M.; Dutzer, M.; Maocec, Ch.; Gillet, G.; Brut, F.; Dieulot, M.; Thuillier, D.; Tournebize, F.; Fontaine, V.; Goursaud, V.; Birot, M.; Le Bourdonnec, Th.; Batandjieva, B.; Theis, St.; Walker, St.; Rosett, M.; Cameron, C.; Boyd, A.; Aguilar, M.; Brownell, H.; Manson, P.; Walthery, R.; Wan Laer, W.; Lewandowski, P.; Dorms, B.; Reusen, N.; Bardelay, J.; Damette, G.; Francois, P.; Eimer, M.; Tadjeddine, A.; Sene, M.; Sene, R.

    2008-01-01

    This file includes five parts: the first part is devoted to the strategies of the different operators and includes the following files: the decommissioning of nuclear facilities Asn point of view, decommissioning of secret nuclear facilities, decommissioning at the civil Cea strategy and programs, EDF de-construction strategy, Areva strategy for decommissioning of nuclear facilities; the second one concerns the stakes of dismantling and includes the articles as follow: complete cleanup of buildings structures in nuclear facilities, decommissioning of nuclear facilities and safety assessment, decommissioning wastes management issues, securing the financing of long-term decommissioning and waste management costs, organizational and human factors in decommissioning projects, training for the decommissioning professions: the example of the Grenoble University master degree; the third part is devoted to the management of dismantling work sites and includes the different articles as follow: decommissioning progress at S.I.C.N. plant, example of decommissioning work site in Cea Grenoble: Siloette reactor decommissioning, matters related to decommissioning sites, decommissioning of french nuclear installations: the viewpoint of a specialist company, specificities of inspections during decommissioning: the Asn inspector point of view; the fourth part is in relation with the international approach and includes as follow: IAEA role in establishing a global safety regime on decommissioning, towards harmonization of nuclear safety practices in Europe: W.E.N.R.A. and the decommissioning of nuclear facilities, EPA superfund program policy for decontamination and decommissioning, progress with remediation at Sellafield, progress and experiences from the decommissioning of the Eurochemic reprocessing plant in Belgium, activities of I.R.S.N. and its daughter company Risk-audit I.r.s.n./G.r.s. international in the field of decommissioning of nuclear facilities in eastern countries

  17. AECL's strategy for decommissioning Canadian nuclear facilities

    International Nuclear Information System (INIS)

    Joubert, W.M.; Pare, F.E.; Pratapagiri, G.

    1992-01-01

    The Canadian policy on decommissioning of nuclear facilities as defined in the Atomic Energy Control Act and Regulations is administered by the Atomic Energy Control Board (AECB), a Federal Government agency. It requires that these facilities be decommissioned according to approved plans which are to be developed by the owner of the nuclear facility during its early stages of design and to be refined during its operating life. In this regulatory environment, Atomic Energy of Canada (AECL) has developed a decommissioning strategy for power stations which consists of three distinctive phases. After presenting AECL's decommissioning philosophy, its foundations are explained and it is described how it has and soon will be applied to various facilities. A brief summary is provided of the experience gained up to date on the implementation of this strategy. (author) 3 figs.; 1 tab

  18. The Importance of Experience Based Decommissioning Planning

    International Nuclear Information System (INIS)

    Larsson, Arne; Lidar, Per; Hedin, Gunnar; Bergh, Niklas

    2016-01-01

    Decommissioning of a nuclear facility is an extensive and multidisciplinary task, which involves the management and technical actions associated with ceasing operation and thereafter the step-by-step transfer of the facility from an operating plant to an object under decommissioning. The decommissioning phase includes dismantling of systems and components, decontamination and clearance, demolition of buildings, remediation of any contaminated ground and finally a survey of the site. Several of these activities generate radioactive or potentially radioactive waste, which has to be managed properly prior to clearance or disposal. What makes decommissioning of nuclear installations unique is to large extent the radioactive waste management. No other industries have that complex regulatory framework for the waste management. If decommissioning project in the nuclear industry does not consider the waste aspects to the extent required, there is a large risk of failure causing a reduced trust by the regulators and other stakeholders as well as cost and schedule overruns. This paper will give an overview of important aspects and findings gathered during decades of planning and conducting decommissioning and nuclear facility modernization projects. (authors)

  19. Research reactor back-end options - decommissioning: a necessary consideration

    International Nuclear Information System (INIS)

    England, M.R.; Parry, D.R.; Smith, C.

    1998-01-01

    Decommissioning is a challenge, which all radioactive site licensees eventually need to face and research reactors are no exception. BNFL has completed numerous major decommissioning projects at its own operational sites and has undertaken similar works at customers' sites including the decommissioning of the Universities Research Reactor (URR), Risley and the ICI TRIGA 1-Mk I Reactor at Billingham. Based on the execution of such projects BNFL has gained an understanding of the variety of customer requirements and the effectiveness of specific decommissioning techniques for research reactors. This paper addresses factors to be considered when reviewing the way forward following shut down and how these affect the final decisions for fuel management and the extent of decommissioning. Case studies are described from BNFL's recent experience decommissioning both the URR and ICI TRIGA reactors. (author)

  20. Addressing Uncertainties in Cost Estimates for Decommissioning Nuclear Facilities

    International Nuclear Information System (INIS)

    Benjamin, Serge; Descures, Sylvain; Du Pasquier, Louis; Francois, Patrice; Buonarotti, Stefano; Mariotti, Giovanni; Tarakonov, Jurij; Daniska, Vladimir; Bergh, Niklas; Carroll, Simon; AaSTRoeM, Annika; Cato, Anna; De La Gardie, Fredrik; Haenggi, Hannes; Rodriguez, Jose; Laird, Alastair; Ridpath, Andy; La Guardia, Thomas; O'Sullivan, Patrick; ); Weber, Inge; )

    2017-01-01

    The cost estimation process of decommissioning nuclear facilities has continued to evolve in recent years, with a general trend towards demonstrating greater levels of detail in the estimate and more explicit consideration of uncertainties, the latter of which may have an impact on decommissioning project costs. The 2012 report on the International Structure for Decommissioning Costing (ISDC) of Nuclear Installations, a joint recommendation by the Nuclear Energy Agency (NEA), the International Atomic Energy Agency (IAEA) and the European Commission, proposes a standardised structure of cost items for decommissioning projects that can be used either directly for the production of cost estimates or for mapping of cost items for benchmarking purposes. The ISDC, however, provides only limited guidance on the treatment of uncertainty when preparing cost estimates. Addressing Uncertainties in Cost Estimates for Decommissioning Nuclear Facilities, prepared jointly by the NEA and IAEA, is intended to complement the ISDC, assisting cost estimators and reviewers in systematically addressing uncertainties in decommissioning cost estimates. Based on experiences gained in participating countries and projects, the report describes how uncertainty and risks can be analysed and incorporated in decommissioning cost estimates, while presenting the outcomes in a transparent manner

  1. Reactor decommissioning

    International Nuclear Information System (INIS)

    Lawton, H.

    1984-01-01

    A pioneering project on the decommissioning of the Windscale Advanced Gas-cooled Reactor, by the UKAEA, is described. Reactor data; policy; waste management; remote handling equipment; development; and recording and timescales, are all briefly discussed. (U.K.)

  2. Measuring and reporting on decommissioning progress

    International Nuclear Information System (INIS)

    Lange, B.A.

    2006-01-01

    One of the challenges facing AECL, as well as other organizations charged with the responsibility of decommissioning nuclear facilities, is the means by which to measure and report on decommissioning progress to various audiences which, in some cases, may only have a peripheral knowledge or understanding of the complexities associated with the decommissioning process. The reporting and measurement of decommissioning progress is important for a number of reasons, i.e., It provides a vehicle by which to effectively communicate the nature of the decommissioning process; It ensures that stakeholders and shareholders are provided with a transparent and understandable means for assessing value for money; It provides a means by which to integrate the planning, measurement, and operational aspects of decommissioning One underlying reason behind the challenge of reporting decommissioning progress lies in the fact that decommissioning programs are generally executed over periods of time that far exceed those generally associated with typical design and build projects. For example, a decommissioning program could take decades to complete in which case progress on the order of a few percent in any one year might be typical. However, such progress may appear low compared to that seen with more typical projects that can be completed in a matter of years. As a consequence, AECL undertook to develop a system by which to measure decommissioning progress in a straightforward, meaningful, and understandable fashion. The system is not rigorously objective, and there are subjective aspects that are necessitated by the need to keep the system readily understandable. It is also important to note that while the system is simple in concept, there is, nonetheless, significant effort involved in generating and updating the parameters used as input, and in the actual calculations. (author)

  3. BN-350 nuclear power plant. Regulatory aspects of decommissioning

    International Nuclear Information System (INIS)

    Shiganakov, S.; Zhantikin, T.; Kim, A.

    2002-01-01

    'General Provisions on Development of the Project on BN-350 Reactor Plant Decommissioning'; 2. Special Technical Conditions 'For Designing of the BN-350 Reactor Facility Decommissioning Project'; 3. Plan of priority measures for BN-350 reactor decommissioning. The documents 1 and 2 were prepared jointly by BN-350, technical institutes, KAEC and various other Kazakhstan Governmental agencies and departments, and they set out: stages in the development of the specifications for the Plan; applicable laws and regulations, and the procedure to follow if the regulations do not cover particular situations or issues; responsibilities of various organizations in the production, agreement and approval process; a recommended detailed list of contents for the Decommissioning Plan (Project); external factors, existing design and planning works which the Plan must take into account; other basic information which needs to be included into the Plan documentation. As the shutdown reactor continues to remain a source of nuclear and radioactive hazard, one have to take measures on putting the reactor to safe status, and thus 'Plan of priority measures for BN-350 reactor decommissioning' was developed. It includes following activities: measures on BN-350 decommissioning Project development; measures on provision of the reactor safety during transition period; measures on sodium drainage and utilization; measures on spent fuel disposal for a long term storage. KAEC was authorized to provide coordination of BN-350 decommissioning work. For example, some duties of KAEC in the Decommissioning Project are as follows: supervision of Project implementation by licensing and engagement of state licensed institutions only for decommissioning works; consideration, approval and authorization of technical documentation of enterprises and institutions implementing the Project within its competency. During the development and implementation of the Project all participants must act according to the laws and

  4. Decommissioning Facility Characterization DB System

    International Nuclear Information System (INIS)

    Park, S. K.; Ji, Y. H.; Park, J. H.; Chung, U. S.

    2010-01-01

    Basically, when a decommissioning is planed for a nuclear facility, an investigation into the characterization of the nuclear facility is first required. The results of such an investigation are used for calculating the quantities of dismantled waste and estimating the cost of the decommissioning project. In this paper, it is presented a computer system for the characterization of nuclear facilities, called DEFACS (DEcommissioning FAcility Characterization DB System). This system consists of four main parts: a management coding system for grouping items, a data input system, a data processing system and a data output system. All data is processed in a simplified and formatted manner in order to provide useful information to the decommissioning planner. For the hardware, PC grade computers running Oracle software on Microsoft Windows OS were selected. The characterization data results for the nuclear facility under decommissioning will be utilized for the work-unit productivity calculation system and decommissioning engineering system as basic sources of information

  5. Decommissioning Facility Characterization DB System

    Energy Technology Data Exchange (ETDEWEB)

    Park, S. K.; Ji, Y. H.; Park, J. H.; Chung, U. S. [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2010-10-15

    Basically, when a decommissioning is planed for a nuclear facility, an investigation into the characterization of the nuclear facility is first required. The results of such an investigation are used for calculating the quantities of dismantled waste and estimating the cost of the decommissioning project. In this paper, it is presented a computer system for the characterization of nuclear facilities, called DEFACS (DEcommissioning FAcility Characterization DB System). This system consists of four main parts: a management coding system for grouping items, a data input system, a data processing system and a data output system. All data is processed in a simplified and formatted manner in order to provide useful information to the decommissioning planner. For the hardware, PC grade computers running Oracle software on Microsoft Windows OS were selected. The characterization data results for the nuclear facility under decommissioning will be utilized for the work-unit productivity calculation system and decommissioning engineering system as basic sources of information

  6. Vinca nuclear decommissioning program

    International Nuclear Information System (INIS)

    Pesic, M.; Subotic, K.; Sotic, O.; Plecas, I.; Ljubenov, V.; Peric, A.

    2002-01-01

    In this paper a preliminary program for the nuclear decommissioning in The Vinca Institute of Nuclear Sciences is presented. Proposed Projects and Activities, planned to be done in the next 10 years within the frames of the Program, should improve nuclear and radiation safety and should solve the main problems that have arisen in the previous period. Project of removal of irradiated spent nuclear fuel from the RA reactor, as a first step in all possible decommissioning strategies and the main activity in the first two-three years of the Program realization, is considered in more details. (author)

  7. Management of Decommissioning on a Multi-Facility Site

    International Nuclear Information System (INIS)

    Laraia, Michele; McIntyre, Peter; Visagie, Abrie

    2008-01-01

    The management of the decommissioning of multi-facility sites may be inadequate or inappropriate if based on approaches and strategies developed for sites consisting of only a single facility. The varied nature of activities undertaken, their interfaces and their interdependencies are likely to complicate the management of decommissioning. These issues can be exacerbated where some facilities are entering the decommissioning phase while others are still operational or even new facilities are being built. Multi-facility sites are not uncommon worldwide but perhaps insufficient attention has been paid to optimizing the overall site decommissioning in the context of the entire life cycle of facilities. Decommissioning management arrangements need to be established taking a view across the whole site. A site-wide decommissioning management system is required. This should include a project evaluation and approval process and specific arrangements to manage identified interfaces and interdependencies. A group should be created to manage decommissioning across the site, ensuring adequate and consistent practices in accordance with the management system. Decommissioning management should be aimed at the entire life cycle of facilities. In the case of multi facility sites, the process becomes more complex and decommissioning management arrangements need to be established with a view to the whole site. A site decommissioning management system, a group that is responsible for decommissioning on site, a site project evaluation and approval process and specific arrangements to manage the identified interfaces are key areas of a site decommissioning management structure that need to be addressed to ensure adequate and consistent decommissioning practices. A decommissioning strategy based on single facilities in a sequential manner is deemed inadequate

  8. 75 FR 22674 - Moynihan Station Development Project

    Science.gov (United States)

    2010-04-29

    ... DEPARTMENT OF TRANSPORTATION Federal Railroad Administration Moynihan Station Development Project... availability of and public comment period for the Moynihan Station Development Project Environmental Assessment... 22675

  9. Role of Slovakia within the IAEA Decommissioning Related Activities

    International Nuclear Information System (INIS)

    Michal, V.; Stubna, M.

    2009-01-01

    Slovakia has a long-term experience with the IAEA decommissioning related activities as a recipient of Agency assistance and then as a country offering assistance to others. Background, short 'history' and current status of Slovakian national technical cooperation (TC) projects SLR/4/008 'Robotic Technologies for Decontamination and Decommissioning of the Bohunice A1 NPP' and SLR/3/002 'Management of Radioactive Waste from the A1 Nuclear Power Plant Decommissioning' will be described in paper. The first TC project SLR/4/008 was solved by the main Slovakian counterpart, company VUJE, Inc., from 2001 to 2006. Second TC project SLR/3/002 is ongoing with extension to 2011. Thanks to the implementation of a long-term large-scale 'Project of the A1 NPP Decommissioning - Stage I' (1996-2007), financed by Slovak National Nuclear Account (decommissioning fund), as well as implementation of the IAEA TC national projects a comprehensive know-how in the field of D and D and RAW management was obtained. Moreover, technologies and facilities necessary for implementation of decommissioning and RAW management projects were developed. Thanks to this development Slovakia offers donor assistance to other countries in subjected fields through IAEA TC program. The type and scope of assistance for Armenia, Bulgaria, Egypt, Latvia, Lithuania and The Ukraine is described in the paper. The above-mentioned national projects are not only activities of Slovakia within the IAEA TC program. Regional TC project RER/3/005 'Support in Planning the Decommissioning of Nuclear Power Plants and Research Reactors' has been ongoing from 2007 with accepted extension to 2011. About nine countries from Eastern and Central Europe participate in the project (for the NPPs part) and Slovakia plays the role of LCC (Leading Country Coordinator). On the basis of suggestion of Nuclear Regulatory Authority of the Slovak Republic, VUJE is the coordinator of the regional project. Moreover, Slovakia would be the

  10. Cost estimation for decommissioning of research reactors

    International Nuclear Information System (INIS)

    Grossi, Pablo Andrade; Tello, Cledola Cassia Oliveira de; Segabinaze, Roberto de Oliveira; Daniska, Vladimir

    2013-01-01

    In the case of research reactors, the limited data that is available tends to provide only overall decommissioning costs, without any breakdown of the main cost elements. In order to address this subject, it is important to collect and analyse all available data of decommissioning costs for the research reactors. The IAEA has started the DACCORD Project focused on data analysis and costing of research reactors decommissioning. Data collection is organized in accordance with the International Structure for Decommissioning Costing (ISDC), developed jointly by the IAEA, the OECD Nuclear Energy Agency and the European Commission. The specific aims of the project include the development of representative and comparative data and datasets for preliminary costing for decommissioning. This paper will focus on presenting a technique to consider several representative input data in accordance with the ISDC structure and using the CERREX (Cost Estimation for Research Reactors in Excel) software developed by IAEA. (author)

  11. BNFL decommissioning strategy and techniques

    International Nuclear Information System (INIS)

    Taylor, D.

    2002-01-01

    This paper provides an overview of the range of reactor decommissioning projects being managed by BNFL, both on its own sites and for other client organizations in the UK and abroad. It also describes the decommissioning strategies and techniques that have been developed by BNFL and adopted in order to carry out this work

  12. Impact of a decommissioning project on the site area, the federal state, and their economic development

    International Nuclear Information System (INIS)

    Spies, B.G.; Butt, G.M.

    1996-01-01

    Greifswald-Lubmin is a site situated in a border region of Germany, but in the center of eastern Europe and the Baltic countries. The chances of the area are a high vocational qualification of the population and the economic potential opened up by the planned decommissioning of the Greifswald nuclear power plant. A decisive factor for the region's future is to interlace the decommissioning and dismantling activities on site with suitable action taken in support of improvement of the infrastructure and the economic life of the region, as a joint effort of local decision-taking bodies and authorities as well as the Land government. Commitment of private firms from Germany and abroad in the project management and performance of project tasks can contribute valuable stimulation and support. (orig.)

  13. Decommissioning of DR 2. Final report

    Energy Technology Data Exchange (ETDEWEB)

    Strufe, N.

    2009-02-15

    This report describes the work of dismantling and demolishing reactor DR 2, the waste volumes generated, the health physical conditions and the clearance procedures used for removed elements and waste. Since the ultimate goal for the decommissioning project was not clearance of the building, but downgrading the radiological classification of the building with a view to converting it to further nuclear use, this report documents how the lower classification was achieved and the known occurrence of remaining activity. The report emphasises some of the deliberations made and describes the lessons learned through this decommissioning project. The report also intends to contribute towards the technical basis and experience basis for further decommissioning of the nuclear facilities in Denmark. (au)

  14. The SGHWR decommissioning project-waste strategy

    International Nuclear Information System (INIS)

    Graham, G.; Napper, M.

    1999-01-01

    Every facility must reach a stage in the decommissioning process where low-level waste (LLW) becomes the major factor in the decommissioning costs, therefore a cost-effective strategy for dealing with the waste must be sought. This paper describes the waste management strategy process that was carried out at the steam generating heavy water reactor (SGHWR) at Winfrith in Dorset. Obviously, each facility will have its own specific radiological problems, with its own unique fingerprint, which will have to be addressed, and, therefore, the optimum waste management strategy will differ for each facility. However, from the work done at SGHWR, it can be seen that it is possible to formulate a structured approach for dealing with LLW which meets the requirements of all stake holders, is safe, technically acceptable, cost-effective, and, furthermore, is equally applicable to other plants. (author)

  15. A Comparative Perspective on Reactor Decommissioning

    International Nuclear Information System (INIS)

    Devgun, J.S.; Zelmer, R.

    2006-01-01

    A comparative perspective on decommissioning, based on facts and figures as well as the national policies, is useful in identifying mutually beneficial 'lessons learned' from various decommissioning programs. In this paper we provide such a perspective on the US and European approaches based on a review of the programmatic experience and the decommissioning projects. The European countries selected for comparison, UK, France, and Germany, have nuclear power programs comparable in size and vintage to the US program but have distinctly different policies at the federal level. The national decommissioning scene has a lot to do with how national nuclear energy policies are shaped. Substantial experience exists in all decommissioning programs and the technology is in a mature state. Substantial cost savings can result from sharing of decommissioning information, technologies and approaches among various programs. However, the Achilles' heel for the decommissioning industry remains the lack of appropriate disposal facilities for the nuclear wastes. (authors)

  16. Decommissioning in western Europe

    International Nuclear Information System (INIS)

    Lundqvist, K.

    1999-12-01

    This report gives an overview of the situation in Western Europe. The original aim was to focus on organisational and human issues with regard to nuclear reactor decommissioning, but very few articles were found. This is in sharp contrast to the substantial literature on technical issues. While most of the reports on decommissioning have a technical focus, several provide information on regulatory issues, strategies and 'state of the art'. The importance of the human and organizational perspective is however discovered, when reading between the lines of the technical publications, and especially when project managers summarize lessons learned. The results are to a large extent based on studies of articles and reports, mainly collected from the INIS database. Decommissioning of nuclear facilities started already in the sixties, but then mainly research and experimental facilities were concerned. Until now about 70 reactors have been shutdown world-wide. Over the years there have been plenty of conferences for exchanging experiences mostly about technical matters. Waste Management is a big issue. In the 2000s there will be a wave of decommissioning when an increasing amount of reactors will reach the end of their calculated lifetime (40 years, a figure now being challenged by both life-extension and pre-shutdown projects). Several reactors have been shut-down for economical reasons. Shutdown and decommissioning is however not identical. A long period of time can sometimes pass before an owner decides to decommission and dismantle a facility. The conditions will also differ depending on the strategy, 'immediate dismantling' or 'safe enclosure'. If immediate dismantling is chosen the site can reach 'green-field status' in less than ten years. 'Safe enclosure', however, seems to be the most common strategy. There are several pathways, but in general a safe store is constructed, enabling the active parts to remain in safe and waterproof conditions for a longer period of

  17. Meeting the challenge of BNFL's decommissioning programme

    International Nuclear Information System (INIS)

    Sheil, A.E.

    1997-01-01

    The paper reviews the co-ordinated and integrated programme, adopted by BNFL, in the decommissioning of its radioactive plants. It examines BNFL's approach to the challenges posed by the eventual decommissioning of its 120 plants, its overall strategies, the constraints and the progress achieved to date, drawing on real experience from the 22 completed projects and the 24 projects currently underway. (author)

  18. Getting the most D and D ''know how'' before starting to plan your decommissioning project

    International Nuclear Information System (INIS)

    Boing, L. E.

    1999-01-01

    Over the last 20 years, the Decommissioning Program of the ANL-East Site has successfully decommissioned numerous facilities including: three research reactors (a 100 MW BWR, a smaller 250 kW biological irradiation reactor and a 10 kW research reactor), a critical assembly, a suite of 61 plutonium gloveboxes in 9 laboratories, a fuels fabrication facility and several non-reactor (waste management and operations) facilities. In addition, extensive decontamination work was performed on 5 hot cells formerly used in a joint ANL/US Navy R and D program. Currently the D and D of the CP-5 research reactor is underway as is planning for several other future D and D projects. The CP-5 facility was also used as a test bed for the evaluation of select evolving D and D technologies to ascertain their value for use in future D and D projects

  19. Decommissioning in the United States - Past, present and future - 16318

    International Nuclear Information System (INIS)

    Devgun, Jas S.

    2009-01-01

    The experience related to decommissioning of nuclear facilities in the United States is very substantial and covers power reactors, research reactors, and many facilities in the Department of Energy complex. The focus of this paper however is on the commercial power plants. With 104 operating reactors, the U.S. fleet of civilian reactors is still the largest in the world. Nuclear power industry in the United States has undergone a dramatic upturn after decades of stalemate. One effect of this nuclear renaissance has been that the plans have changed for several reactors that were initially destined for decommissioning. Instead, the focus now is on re-licensing of the reactors and on power up-rates. In fact, after the peak period between 1987 and 1998, no additional power reactors have been shutdown. On the contrary, power up-rates in the past twenty years have added a cumulative capacity equivalent to five new reactors. Almost all the operating reactors plan to have license extensions, thus postponing the eventual decommissioning. Nevertheless, in addition to the 9 reactors where licenses have been terminated following decommissioning, 12 power and early demonstration reactors and 14 test and research reactors are permanently shutdown and are in decommissioning phase. Substantial experience and lessons learned are available from the U.S. projects that are of value to the international decommissioning projects, especially where such projects are in early stages. These lessons cover a wide array of areas from decommissioning plans, technology applications, large component removal, regulatory and public interface, decommissioning funding and costs, clean up criteria, surveys of the decommissioned site, and license termination. Additionally, because of the unavailability of a national spent fuel disposition facility, most decommissioning sites are constructing above ground interim storage facilities for the spent nuclear fuel. The U.S. nuclear power projects are also

  20. Decommissioning of fuel PIE caves at Berkeley Nuclear Laboratories

    International Nuclear Information System (INIS)

    Brant, A.W.

    1990-01-01

    This paper describes the first major contract awarded to private industry to carry out decommissioning of a facility with significant radiation levels. The work required operatives to work in pressurised suits, entry times were significantly affected by sources of radiation in the Caves, being as low as thirty minutes per day initially. The Caves at Berkeley Nuclear Laboratories carry out post irradiation examination of fuel elements support units and reactor core components from CEGB power stations. The decommissioning work is part of an overall refurbishment of the facility to allow the receipt of AGR Fuel Stringer Component direct from power stations. The paper describes the decommissioning and decontamination of the facility from the remote removal and clean up work carried out by the client to the hands-on work. It includes reference to entry times, work patterns, interfaces with the client and the operations of the laboratory. Details of a specially adapted size reduction method are given. (Author)

  1. The French decommissioning program: a stakeholder point of view

    International Nuclear Information System (INIS)

    Chatry, Jean-Paul; Grenouillet, Jean-Jacques

    2006-01-01

    In January 2001, EDF owner of 56 plants in operation and 9 plants in decommissioning stage decided to accelerate the decommissioning of its first nine nuclear generation units in order to achieve final decommissioning in 25 years' time. An engineering center dedicated to decommissioning, radwaste management and environment was set up to implement this strategy. Four years after its creation, the first lessons learned in the fields of organization, project and program management can now be described. During the 4 years that have elapsed since the creation of CIDEN in 2001 to implement EDF's new decommissioning strategy, its organization has constantly improved to ensure success of its decommissioning projects. The aim has been to build an efficient organization with clearly defined roles for the key players. Simultaneously, the Program Management activities have received increasing consideration and specific mechanisms have been implemented to bring financing and licensing flexibility to the program. The continuous improvement of its organization and the development of new project or program management methodologies is a constant preoccupation of EDF. Its aim is to successfully implement its decommissioning strategy, one of the key issues for guaranteeing the future of a safe economic and environment friendly nuclear energy in France

  2. Decommissioning the Belgonucleaire Dessel MOX plant: presentation of the project and situation end august 2013

    Energy Technology Data Exchange (ETDEWEB)

    Cuchet, J.M. [TRACTEBEL ENGINEERING, Avenue Ariane, 7, B1200 Brussels (Belgium); Libon, H.; Verheyen, C. [BELGONUCLEAIRE S.A. / N.V. Europalaan, 20, B2480 Dessel (Belgium); Bily, J. [STUDSVIK GmbH, Karlsruher Strasse, 20, D75179 Pforzheim,(Germany); Boden, S. [SCK-CEN, Boeretang, 200, B2400 Mol (Belgium); Joffroy, F. [TECNUBEL N.V., Zandbergen, 1, B2480 Dessel (Belgium); Walthery, R. [BELGOPROCESS, Gravenstraat, 73, B2480 Dessel (Belgium)

    2013-07-01

    Belgonucleaire has been operating the Dessel MOX plant at an industrial scale between 1986 and 2006. During this period, 40 metric tons of plutonium (HM) have been processed into 90 reloads of MOX fuel for commercial light water reactors. The decision to stop the production in 2006 and to decommission the MOX plant was the result of the shrinkage of the MOX fuel market due to political and commercial factors. As a significant part of the decommissioning project of the Dessel MOX plant, about 170 medium-sized glove-boxes and about 1.200 metric tons of structure and equipment outside the glove-boxes are planned for dismantling. The license for the dismantling of the MOX plant was granted by Royal Decree in 2008 and the dismantling started in March 2009. The dismantling works are carried out by an integrated organization under leadership and responsibility of Belgonucleaire; this organization includes 3 main contractors, namely Tecnubel N.V., the THV ('Tijdelijke HandelsVereniging') Belgoprocess / SCK-CEN and Studsvik GmbH and Tractebel Engineering as project manager. In this paper, after having described the main characteristics of the project, the authors review the different organizational and technical options considered for the decommissioning of the glove-boxes; thereafter the main decision criteria (qualification of personnel and of processes, confinement, cutting techniques and radiation protection, safety aspects, alpha-bearing waste management) are analyzed as well. Finally the progress, the feedback and the lessons learned at the end of August 2013 are presented, giving the principal's and contractors point of view. (authors)

  3. Offshore decommissioning issues: Deductibility and transferability

    International Nuclear Information System (INIS)

    Parente, Virginia; Ferreira, Doneivan; Moutinho dos Santos, Edmilson; Luczynski, Estanislau

    2006-01-01

    Dealing with the decommissioning of petroleum installations is a relatively new challenge to most producer countries. It is natural to expect that industry's experience in building platforms is much greater than the one of dismantling them. Even if manifold and varied efforts are underway towards establishing international 'best practices' standards in this sector, countries still enjoy rather extensive discretionary power as they practice a particular national style in the regulation of decommissioning activities in their state's jurisdiction. The present paper offers a broad panorama of this discussion, concentrating mainly on two controversial aspects. The first one analyses the ex-ante deductibility of decommissioning costs as they constitute an ex-post expense. The second discussion refers to the assignment of decommissioning responsibility in the case of transfer of exploration and production rights to new lessees during the project's life. Finally the paper applies concepts commonly used in project financing as well as structures generally used in organising pension funds to develop insights into these discussions

  4. Remote Decommissioning Experiences at Sellafield

    International Nuclear Information System (INIS)

    Brownridge, M.

    2006-01-01

    British Nuclear Group has demonstrated through delivery of significant decommissioning projects the ability to effectively deploy innovative remote decommissioning technologies and deliver cost effective solutions. This has been achieved through deployment and development of off-the-shelf technologies and design of bespoke equipment. For example, the worlds first fully remotely operated Brokk was successfully deployed to enable fully remote dismantling, packaging and export of waste during the decommissioning of a pilot reprocessing facility. British Nuclear Group has also successfully implemented remote decommissioning systems to enable the decommissioning of significant challenges, including dismantling of a Caesium Extraction Facility, Windscale Pile Chimney and retrieval of Plutonium Contaminated Material (PCM) from storage cells. The challenge for the future is to continue to innovate through utilization of the supply chain and deploy off-the-shelf technologies which have been demonstrated in other industry sectors, thus reducing implementation schedules, cost and maintenance. (authors)

  5. Decommissioning of nuclear facilities in Europe and the experience of TUV SUD

    International Nuclear Information System (INIS)

    Hummel, Lothar; Kim, Duill; Ha, Taegun; Yang, Kyunghwa

    2012-01-01

    Many commercial nuclear facilities of the first generation will be taken out of operation in the near future. As of January 2012, total 19 prototype and commercial nuclear reactors have been decommissioned or are under dismantling in Germany. Most of decommissioning projects were successfully performed and a great deal of experience has been accumulated. Selecting a decommissioning strategy is a very important step at the beginning of the decision making process. According to IAEA requirements immediate dismantling is chosen as a preferred option in many countries today. It is associated with less uncertainty, positive political and social effect, and it can make use of existing operational experience and know-how. The availability of funds and final repository is of high importance for a decommissioning strategy selection. The time frame for the dismantling of nuclear facilities depends on the type, size and complexity of the individual project. TUV SUD, which is supervising most of nuclear power plants in Germany, has accumulated lots of experience by taking parts in decommissioning projects. It direct dismantling is chosen, actual light water reactor in Germany decommissioned to green field in approx. 10 years. The activities of TUV SUD cover from establishing the decommissioning concept to the clearance of the sites. This provides an overview of decommissioning projects of nuclear facilities in Europe, including a detail illustration of the German situation. Finally, some recommendations are suggested for the first decommissioning project based on the lessons and experiences derived from many decommissioning works in Europe

  6. IAEA Assistance on Decommissioning of Small Facilities with Limited Resources

    International Nuclear Information System (INIS)

    Batandjieva, B.; Warnecke, E.

    2008-01-01

    The number of facilities reaching their lifetime is increasing and drawing the attention of operators, regulators, public and other interested parties (potential users of the site after decommissioning) on the importance of adequate planning, funding and implementation of decommissioning activities in compliance with regulatory requirements and criteria. Specific attention is required for small facilities that have been used for research purposes and in most cases state owned by and dependent on state funding. With the current tendency for expansion of the nuclear industry such small facilities could become less of importance for the operators which can increase the probability that these facilities become abandoned, hazardous and imposing undue burden to future generations. This concern is more related to countries with limited human and financial resources at the operating organizations and the regulatory body. The International Atomic Energy Agency (IAEA) has been working on the; (i) establishment of internationally recognized safety standards on decommissioning and (ii) providing Member States with assistance on the application of these standards. The recent international conference on Lessons Learned from the Decommissioning of Nuclear Facilities and the Safe Termination of Practices (Athens, Greece, 2006) has demonstrated that the set of IAEA standards is almost complete and that the International Action Plan on Decommissioning (2004), that is addressing decommissioning of small facilities, is being successfully implemented. However the need for further assistance on decommissioning of small facilities in countries with limited resources was also recognized and the Agency is planning its future work in this field. The IAEA also addresses the needs of small nuclear countries that have only a limited number of nuclear facilities, e.g. a research reactor, in its R esearch Reactor Decommissioning Demonstration Project (R 2 D 2 P. The Philippine Research Reactor

  7. Shippingport station communications program

    International Nuclear Information System (INIS)

    Stote, J.J.

    1988-01-01

    At the Shippingport Station Decommissioning Project, the central idea of the communications program that was developed for use was purposely designed to be as uncomplicated as possible. The central theme, that was developed and communicated, is that all nuclear plants will someday need to be retired and also decommissioned. The Shippingport Plant, originally constructed as a demonstration nuclear power plant, was now being decommissioned as a demonstration to the world-wide nuclear industry that this evolution can be done in a safe and cost-effective manner. Furthermore, the technology currently exists to complete this process. The new phase of the communications program was initiated even before the responsibility for the plant was transferred from Duquesne Light to GE. With such a change forthcoming, it was necessary to inform local officials of these plans, and the reasons for them. Equally important was the need to inform a variety of agencies and offices in the three-state area of the changes, and the continuing need to involve them in the Site Emergency Plan. This document was also revised in recognition of changing site conditions, as well as the changes in responsibility. 1 ref

  8. Preparatory activities of the Fugen decommissioning

    International Nuclear Information System (INIS)

    Iguchi, Y.; Tajiri, T.; Kiyota, S.

    2004-01-01

    The Advanced Thermal Reactor Fugen is a 165 MWe, heavy water moderated, light-water cooled, pressure-tube type reactor. In February 1998, the Atomic Energy Commission of Japan introduced a new policy that development and research of decommissioning of Fugen should be promoted in order to carry out the decommissioning smoothly after the shutdown. The Fugen reactor was shut down definitely in March 2003, and Fugen has been preparing for the project, including necessary development of technologies. The development of decommissioning for Fugen is divided into two areas. One area is the development of unique technology for dismantling special components such as the reactor core and the heavy water system. Another area is the improvement and enhancement of existing technologies. Especially the former area requires effort and comprises development of the reactor dismantlement, tritium decontamination of heavy water system and engineering support systems. The activities are as follows: the density and amount of radioactive nuclides in all equipment or concrete including the reactor core need to be evaluated for the decommissioning. To prepare for decommissioning, analysis, measurement and evaluation of the neutron flux density have been executed during reactor operation. Special dismantling process is necessary for the heavy water system and the reactor that are unique to Fugen. Some studies and tests are going on for the safe dismantling based on existing technologies and their combination. Systems engineering approach is necessary in order to optimize the work load, exposure dose, waste mass and cost by selecting appropriate dismantling process at the planning stage of the decommissioning. For this reason, in order to make a decommissioning plan efficiently, we have been developing an Engineering Support System for decommissioning by adopting new information technologies such as three-dimensional computer-aided design system and virtual reality system. Moreover, the

  9. Decommissioning and back working of Greifswald nuclear power plant

    International Nuclear Information System (INIS)

    Rittscher, D.; Leushacke, D.F.; Meyer, R.

    1998-01-01

    At Nuclear Power Plant Greifswald, the Energiewerke Nord are carrying out the presently world's largest decommissioning project. This requires the gathering up of experience from the operation of the nuclear power plants at Greifswald, the decommissioning of other nuclear power plants, waste management, project management and licensing procedures for the decommissioning of nuclear power plants. That confirmed that the back working of nuclear plants is not a technical problem but a challenge for project management and logistics. It shows that the dismantling and disposal of nuclear plants is an ordinary process in our economic life. (orig.) [de

  10. Radiological planning and implementation for nuclear-facility decommissioning

    International Nuclear Information System (INIS)

    Valentine, A.M.

    1982-01-01

    The need and scope of radiological planning required to support nuclear facility decommissioning are issues addressed in this paper. The role of radiation protection engineering and monitoring professionals during project implementation and closeout is also addressed. Most of the discussion focuses on worker protection considerations; however, project support, environmental protection and site release certification considerations are also covered. One objective is to identify radiological safety issues that must be addressed. The importance of the issues will vary depending on the type of facility being decommissioned; however, by giving appropriate attention to these issues difficult decommissioning projects can be accomplished in a safer manner with workers and the public receiving minimal radiation exposures

  11. Progress report on decommissioning activities at the Fernald Environmental Management Project (FEMP) site

    International Nuclear Information System (INIS)

    1998-01-01

    The Fernald Environmental Management Project (FEMP), is located about 18 miles northwest of Cincinnati, Ohio. Between 1953 and 1989, the facility, then called the Feed Material Production Center or FMPC, produced uranium metal products used in the eventual production of weapons grade material for use by other US Department of Energy (DOE) sites. In 1989, FMPC's production was suspended by the federal government in order to focus resources on environmental restoration versus defense production. In 1992, Fluor Daniel Fernald assumed responsibility for managing all cleanup activities at the FEMP under contract to the DOE. In 1990, as part of the remediation effort, the site was divided into five operable units based on physical proximity of contaminated areas, similar amounts of types of contamination, or the potential for a similar technology to be used in cleanup activities. This report continues the outline of the decontamination and decommissioning (D and D) activities at the FEMP site Operable Unit 3 (OU3) and provides an update on the status of the decommissioning activities. OU3, the Facilities Closure and Demolition Project, involves the remediation of more than 200 uranium processing facilities. The mission of the project is to remove nuclear materials stored in these buildings, then perform the clean out of the buildings and equipment, and decontaminate and dismantle the facilities

  12. Radiation protection in decommissioning of the NPP V1

    International Nuclear Information System (INIS)

    Svitek, J.; Kaizer, J.; Siska, J.

    2014-01-01

    What's new in decommissioning of the NPP V1? In 2014 the first stage of the decommissioning should be finished. The program of the first stage was characterized by decommissioning of the non-contaminated facilities and buildings (facilities and buildings out of the control area). However, during the first stage, two key activities were done during which radiation protection had to be especially supervised: BIDSF project - Treatment and Conditioning of Wet Historical Waste - Sludge and Sorbents in the operational tanks NPP V1 (the treatment has been the condition of the regulatory body for the ending of the first stage) and preparation of decontamination of both primary circuits NPP (without reactors). In the year 2015, the second stage of decommissioning should be started. Program for the second stage is broad and it includes fragmentation and treatment of activated parts of the primary circuits (reactors, their internal parts, shielding cassettes). Modification of the radiation protection equipment on the NPP site has been made by BIDSF projects. During the first stage, two basic projects have been done: C12 - Refurbishment of the radiation protection monitoring equipment and C-10 - Free release of decommissioning materials. The present state of monitoring systems, as the result of the aforementioned projects, and the first experiences are main part of this presentation. Another activity, which prepared basic conditions for an execution of radiation protection in the second stage of decommissioning, was the preparation of documents for the procurement of license for the second stage of decommissioning. (authors)

  13. Decontamination and Decommissioning Experience at a Sellafield Uranium Purification Plant

    International Nuclear Information System (INIS)

    Prosser, J.L.

    2006-01-01

    Built in the 1950's, this plant was originally designed to purify depleted uranyl nitrate solution arising from reprocessing operations at the Primary Separation and Head End Plant (Fig. 1). The facility was used for various purposes throughout its life cycle such as research, development and trial based processes. Test rigs were operated in the building from the 1970's until 1984 to support development of the process and equipment now used at Sellafield's Thermal Oxide Reprocessing Plant (THORP). The extensive decommissioning program for this facility began over 15 years ago. Many challenges have been overcome throughout this program such as decommissioning the four main process cells, which were very highly alpha contaminated. The cells contained vessels and pipeline systems that were contaminated to such levels that workers had to use pressurized suits to enter the cells. Since decommissioning at Sellafield was in its infancy, this project has trialed various decontamination/decommissioning methods and techniques in order to progress the project, and this has provided valuable learning for other decommissioning projects. The project has included characterization, decontamination, dismantling, waste handling, and is now ready for demolition during late 2005, early 2006. This will be the first major facility within the historic Separation Area at Sellafield to be demolished down to base slab level. The lessons learnt from this project will directly benefit numerous decommissioning projects as the cleanup at Sellafield continues. (authors)

  14. Feedback experience from the decommissioning of Spanish nuclear facilities

    International Nuclear Information System (INIS)

    Santiago, J.L.

    2008-01-01

    The Spain has accumulated significant experience in the field of decommissioning of nuclear and radioactive facilities. Relevant projects include the remediation of uranium mills and mines, the decommissioning of research reactors and nuclear research facilities and the decommissioning of gas-graphite nuclear power plants. The decommissioning of nuclear facilities in Spain is undertaken by ENRESA, who is also responsible for the management of radioactive wastes. The two most notable projects are the decommissioning of the Vandellos I nuclear power plant and the decommissioning of the CIEMAT nuclear research centre. The Vandellos I power plant was decommissioned in about five years to what is known as level 2. During this period, the reactor vessel was confined, most plant systems and components were dismantled, the facility was prepared for a period of latency and a large part of the site was restored for subsequent release. In 2005 the facility entered into the phase of dormancy, with minimum operating requirements. Only surveillance and maintenance activities are performed, among which special mention should be made to the five-year check of the leak tightness of the reactor vessel. After the dormancy period (25 - 30 years), level 3 of decommissioning will be initiated including the total dismantling of the remaining parts of the plant and the release of the whole site for subsequent uses. The decommissioning of the CIEMAT Research Centre includes the dismantling of obsolete facilities such as the research reactor JEN-1, a pilot reprocessing plant, a fuel fabrication facility, a conditioning plant for liquid and a liquid waste storage facility which were shutdown in the early eighties. Dismantling works have started in 2006 and will be completed by 2009. On the basis of the experience gained in the above mentioned sites, this paper describes the approaches adopted by ENRESA for large decommissioning projects. (author)

  15. Decommissioning Operations at the Cadarache Nuclear Research Center

    International Nuclear Information System (INIS)

    Gouhier, E.

    2008-01-01

    Among the different activities of the CEA research center of Cadarache, located in the south of France, one of the most important involves decommissioning. As old facilities close, decommissioning activity increases. This presentation will give an overview of the existing organization and the different ongoing decommissioning and cleanup operations on the site. We shall also present some of the new facilities under construction the purpose of which is to replace the decommissioned ones. Cadarache research center was created on October 14, 1959. Today, the activities of the research center are shared out among several technological R and D platforms, essentially devoted to nuclear energy (fission and fusion) Acting as a support to these R and D activities, the center of Cadarache has a platform of services which groups the auxiliary services required by the nuclear facilities and those necessary to the management of nuclear materials, waste, nuclear facility releases and decommissioning. Many old facilities have shut down in recent years (replaced by new facilities) and a whole decommissioning program is now underway involving the dismantling of nuclear reactors (Rapsodie, Harmonie), processing facilities (ATUE uranium treatment facility, LECA UO 2 facility) as well as waste treatment and storage facilities (INB37, INB 56. In conclusion: other dismantling and cleanup operations that are now underway in Cadarache include the following: - Waste treatment and storage facilities, - Historical VLLW and HLW storage facility, - Fissile material storage building, - Historical spent fuel storage facility. Thanks to the project organization: - Costs and risks on these projects can be reduced. - Engineers and technicians can easily move from one project to another. In some cases, when a new facility is under construction for the purpose of replacing a decommissioned one, some of the project team can integrate the new facility as members of the operation team. Today

  16. Development of decommissioning system engineering technology

    International Nuclear Information System (INIS)

    Lee, K. W.; Kim, S. K.; Seo, B. K.

    2012-02-01

    In the decommissioning planning stage, it is important to select the optimized decommissioning process considering the cost and safety. Especially the selection of the optimized decommissioning process is necessary because it affects to improve worker's safety and decommissioning work efficiency. The decommissioning process evaluation technology can provide the optimized decommissioning process as constructing various decommissioning scenarios and it can help to prevent the potential accidents as delivering the exact work procedures to workers and to help workers to perform decommissioning work skillfully. It's necessary to measure the radioactive contamination in the highly contaminated facilities such as hot-cells or glove-boxes to be decommissioned for decommissioning planning. These facilities are very high radiation level, so it is difficult to approach. In this case the detector system is preferable to separate the sensor and electronics, which have to locate in the facility outside to avoid the electric noise and worker's radiation exposure. In this project, we developed the remote detection system for radiation measurement and signal transmission in the high radiation area. In order to minimize worker's exposure when decommissioning highly activated nuclear facilities, it is necessary to develop the remote handling tool to perform the dismantling work remotely. Especially, since cutting, measuring, and decontamination works should be performed remotely in the highly activated area, the remote handling tool for conducting these works should be developed. Therefore, the multi-purpose dismantling machine that can measuring dose, facility cutting, and remote handling for maintenance and decommissioning of highly activated facility should be needed

  17. The NEA Co-operative Programme on Decommissioning. A Decade of Progress

    International Nuclear Information System (INIS)

    2006-01-01

    The Co-operative Programme for the Exchange of Scientific and Technical Information Concerning Nuclear Installation Decommissioning (CPD) is a joint undertaking according to Article 5 of the Statute of the NEA. Concluded in 1985, the Agreement of the 23 participating organisations constituting the CPD has been continuously extended with the current programme period lasting until 2009. This report provides information about the participants, structure and achievements of the Co-operative Programme. The objective of the CPD is to acquire information and share operational experience from the conduct of 42 current decommissioning projects, such as project description and design, data resulting from the execution of decommissioning projects, and associated research and development results. The information generated in the project is protected by confidentiality provisions, which allow for a frank and open exchange of experiences, on a 'give and take' basis. The information exchange also ensures that the best internationally available experience is available and that safe, environmentally friendly and cost effective methods are employed in all decommissioning projects. The Co-operative Programme is implemented by a Management Board (MB) representing the participating organisations and a Technical Advisory Group (TAG) for the information exchange between the individual decommissioning projects. The latter benefits from the support of a Programme Co-ordinator financed by the Programme. The projects in the Programme have a broad range of characteristics and cover various types of reactors and fuel facilities. The Programme now covers 26 reactors, 8 reprocessing plants and 8 fuel facility projects, representing a wide selection of facility types in each category. Also, all three stages of decommissioning - from active dismantling to safe-store and to completed decommissioning back to 'green field conditions' - are represented. Over the 20 years of experience of the Co

  18. Remote handling techniques in decommissioning - A report of the NEA Co-operative Programme on Decommissioning (CPD) project

    International Nuclear Information System (INIS)

    Borchardt, Ralf; Denissen, Luc; Desbats, Philippe; Jeanjacques, Michel; Nokhamzon, Jean-Guy; Valentin, Pierre; Slater, Steve; Valencia, Luis; Wittenauer, Stephan; Yamauchi, Toyoaki; Burton, Bob

    2011-01-01

    The NEA Co-operative Programme for the Exchange of Scientific and Technical Information Concerning Nuclear Installation Decommissioning Projects (CPD) is a joint undertaking of a limited number of organisations actively executing on planning the decommissioning of nuclear facilities. The objective of the CPD is to acquire information from operational experience in decommissioning nuclear installations that is useful for future projects. Although part of the information exchanged within CPD is confidential in nature and is restricted to programme participants, experience of general interest gained under the programme's auspices is released for broader use. Such information is brought to the attention of all NEA members through regular reports to the NEA Radioactive Waste Management Committee (RWMC), as well as through published studies. This report describes generic results obtained by a CPD Task Group analysing the needs for remote technologies. The existing technologies able to meet these needs, the lessons learned and showing where improvements or further developments should be made in this domain. During the D and D process, the handling of highly radioactive materials, the deployment of tools and sensors and the dismantling of components built from many different materials can be a long, labor-intensive process that has the potential for high exposure rates, heat stress and injury to personnel. Mobile robotics systems provide solutions to these hazards. Such remote handling systems are required to perform tasks within budget and on schedule while justifying the expense by a saving in cumulative doses received by project personnel. To reach this goal, the following are additional factors that need to be evaluated when preparing a project: - System and peripherals must be operator-friendly. Ideally, the system must be designed to allow personnel currently available for the D and D project to become trained as operators within a reasonable time frame. - The

  19. An overview of U.S. decommissioning experience -- A basic introduction

    International Nuclear Information System (INIS)

    Boing, L.E.

    1998-01-01

    This paper presents an overview of the US experiences in the decommissioning technical area. Sections included are: (1) an overview of the magnitude of the problem, (2) a review of the US decommissioning process, (3) regulation of decommissioning, (4) regulatory and funding requirements for decommissioning, and (5) a general overview of all on-going and completed decommissioning projects to date in the US. The final section presents a review of some issues in the decommissioning area currently being debated in the technical specialists community

  20. Enforcement management system for decommissioning project in Ningyo-toge Environmental Engineering Center. Results of activities in fiscal year 2014

    International Nuclear Information System (INIS)

    Ema, Akira; Miyagawa, Hiroshi; Ishimori, Yuu

    2016-03-01

    The Ningyo-toge Environmental Engineering Center of the Japan Atomic Energy Agency had managed the decommissioning project based on the Quality Management System and the Environmental Management System, but found that these systems were unsuitable for project management from several viewpoints. In order to solve these problems, the Task Team for Enforcement Backend Project temporarily managed the decommissioning project in 2013. To enforce the project management systematically, the Research and Development Promotion Section was organized newly in the Environmental Research and Development Department in April 2014, and started the project management. On the other hand, to establish the primary and secondary documents related to the new system, until April 2015 the section has been developing the Enforcement Management System (EMS) to separate from the Quality Management System or the Environmental Management System. This report summarizes the state of these activities in the FY 2014. Section 1 presents the introduction. Section 2 explains the procedure of the project management and its achievements. Section 3 discusses how to develop the primary and secondary documents. Section 4 concludes the new management system and further views. (author)

  1. Offshore decommissioning issues: deductibility and transferability

    Energy Technology Data Exchange (ETDEWEB)

    Parente, V.; Santos, M. dos [University of Sao Paulo (Brazil). Instituto de Electrotecnica; Ferreira, D. [State University of Campinas (Brazil). Dept. of Geology and Natural Resources; Luczynski, E. [Grupo de Estudos e Pesquisas Economico-Energeticas, Belem (Brazil)

    2006-10-15

    Dealing with the decommissioning of petroleum installations is a relatively new challenge to most producer countries. It is natural to expect that industry's experience in building platforms is much greater than the one of dismantling them. Even if manifold and varied efforts are underway towards establishing international ''best practices'' standards in this sector, countries still enjoy rather extensive discretionary power as they practice a particular national style in the regulation of decommissioning activities in their state's jurisdiction. The present paper offers a broad panorama of this discussion, concentrating mainly on two controversial aspects. The first one analyses the ex-ante deductibility of decommissioning costs as they constitute an ex-post expense. The second discussion refers to the assignment of decommissioning responsibility in the case of transfer of exploration and production rights to new lessees during the project's life. Finally the paper applies concepts commonly used in project financing as well as structures generally used in organising pension funds to develop insights into these discussions. (author)

  2. A Lifecycle Knowledge Management Approach to Support Decommissioning and Environmental Remediation Projects

    International Nuclear Information System (INIS)

    Borrmann, F.; Booth, P.

    2016-01-01

    Full text: KM is a discipline that has a long tradition in nuclear. Nevertheless, the necessity for and the specifics of KM in decommissioning and environmental remediation have come into focus but quite recently. On one hand driven by major decommissioning programs like the NDA approach in UK or the phase-out decision in Germany, on the other hand as a request from decommissioning practitioners. In this paper we would like to emphasize the necessity to develop lifecycle wide KM approaches and specific tools for KM in decommissioning and environmental remediation. Additionally, KM approaches must be adapted to the phases of the facilities lifecycle. Especially decommissioning and environmental remediation require different KM systems to cope with a quickly changing environment. (author

  3. Development of computer systems for planning and management of reactor decommissioning

    International Nuclear Information System (INIS)

    Yanagihara, Satoshi; Sukegawa, Takenori; Shiraishi, Kunio

    2001-01-01

    The computer systems for planning and management of reactor decommissioning were developed for effective implementation of a decommissioning project. The systems are intended to be applied to construction of work breakdown structures and estimation of manpower needs, worker doses, etc. based on the unit productivity and work difficulty factors, which were developed by analyzing the actual data on the JPDR dismantling activities. In addition, information necessary for project planning can be effectively integrated as a graphical form on a computer screen by transferring the data produced by subprograms such as radioactive inventory and dose rate calculation routines among the systems. Expert systems were adopted for modeling a new decommissioning project using production rules by reconstructing work breakdown structures and work specifications. As the results, the systems were characterized by effective modeling of a decommissioning project, project management data estimation based on feedback of past experience, and information integration through the graphical user interface. On the other hands, the systems were validated by comparing the calculated results with the actual manpower needs of the JPDR dismantling activities; it is expected that the systems will be applicable to planning and evaluation of other decommissioning projects. (author)

  4. Cost Control Guide For Decommissioning Of Nuclear Installations

    International Nuclear Information System (INIS)

    2013-01-01

    This cost control guide was prepared in response to the request from the OECD/NEA Working Party on Decommissioning and Dismantling (WPDD) - Decommissioning Cost Estimation Group (DCEG) to offer the industry guidance in preparing and implementing cost and schedule controls during decommissioning. The DCEG sent out a survey questionnaire in 2010 soliciting comments from OECD member states on their use of cost controls during decommissioning. While the response was limited, the consensus was to proceed with the preparation of this guide. Cost and schedule control systems have been in use for more than 30 years, and in the last 10 years or so have evolved into a more formalised earned value management system (EVMS). This guide is based on the internationally recognised standard, Earned Value Management Systems (ANSI, 2007). The EVMS is built on a work breakdown structure (WBS) of decommissioning activities, and a defined process for controlling a project. The EVMS not only provides measurement of project status and future performance, but also builds a structure and culture for accountability on project performance. This guide describes the performance metrics used to determine the value earned based on what was planned to be done, what was actually accomplished and what it actually cost. Variances measured monthly at a minimum indicate where potential problems are arising and raise a flag for the project manager to implement corrective actions for the next reporting period. The success of the EVMS programme depends on management commitment to implement a culture change for its employees, and to impose the EVMS on potential future contractors performing decommissioning work at a facility. Formal training is required to ensure all elements of the process are understood and put into action. It is recommended to begin with a small project, and graduate to larger projects as the staff learns how to use the system. The EVMS process has been used internationally for small

  5. Integrated five station nondestructive assay system for the support of decontamination and decommissioning of a former plutonium mixed oxide fuel fabrication facility

    International Nuclear Information System (INIS)

    Caldwell, J.T.; Bieri, J.M.; Hastings, R.D.; Horton, W.S.; Kuckertz, T.H.; Kunz, W.E.; Plettenberg, K.; Smith, L.D.

    1990-01-01

    The goal of a safe, efficient and economic decontamination and decommissioning of plutonium facilities can be greatly enhanced through the intelligent use of an integrated system of nondestructive assay equipment. We have designed and fabricated such a system utilizing five separate NDA stations integrated through a single data acquisition and management personal computer-based controller. The initial station utilizes a passive neutron measurement to determine item Pu inventory to the 0.1 gm level prior to insertion into the decontamination cell. A large active neutron station integrated into the cell is used to measure decontamination effectiveness at the 10 nci/gm level. Cell Pu buildup at critical points is monitored with passive neutron detectors. An active neutron station having better than 1 mg Pu assay sensitivity is used to quantify final compacted waste pucks outside the cell. Bulk Pu in various forms and isotopic enrichments is quantified in a combined passive neutron coincidence and high resolution gamma ray spectrometer station outside the cell. Item control and Pu inventory are managed with bar code labeling and a station integrating algorithm. Overall economy is achieved by multiple station use of the same expensive hardware such as the neutron generator

  6. Review of Impact Factors on Decommissioning Strategies

    Energy Technology Data Exchange (ETDEWEB)

    Yun, Taesik; Jung, Hyejin; Kim, Younggook [KHNP CRI, Daejeon (Korea, Republic of)

    2016-10-15

    This article is prepared to factor out decommissioning strategies mostly appropriate to the decommissioning Kori-1 nuclear power plant. Terms used to delineate the lifetime of an authorized facility and of the associated licensing process consists of six core stages such as siting, design, construction, commissioning, operation and decommissioning. The term decommissioning implies the administrative and technical actions taken to allow the removal of some or all of the regulatory controls from a facility except for the part of a disposal facility in which the radioactive waste is emplaced. Whole range of each process of decommissioning should be considered throughout the other five stages. The decommissioning process is typically composed of its planning, conducting actions and terminating the authorization. In order to achieve the successful decommissioning, the impact factor on the strategy should be analyzed and evaluated to optimally apply to Kori-1 project. From my perspective, among eight factor, stakeholder’s consideration and spent fuel management are considered the key elements we have to concentrate on to smoothly go ahead for successful decommissioning of Kori-1.

  7. Decommissioning Technology Development for Nuclear Research Facilities

    International Nuclear Information System (INIS)

    Lee, K. W.; Kang, Y. A.; Kim, G. H.

    2007-06-01

    It is predicted that the decommissioning of a nuclear power plant would happen in Korea since 2020 but the need of partial decommissioning and decontamination for periodic inspection and life extension still has been on an increasing trend and its domestic market has gradually been extended. Therefore, in this project we developed following several essential technologies as a decommissioning R and D. The measurement technology for in-pipe radioactive contamination was developed for measuring alpha/beta/gamma emitting nuclides simultaneously inside a in-pipe and it was tested into the liquid waste transfer pipe in KRR-2. And the digital mock-up system for KRR-1 and 2 was developed for choosing the best scenarios among several scenarios on the basis of various decommissioning information(schedule, waste volume, cost, etc.) that are from the DMU and the methodology of decommissioning cost estimation was also developed for estimating a research reactor's decommissioning cost and the DMU and the decommissioning cost estimation system were incorporated into the decommissioning information integrated management system. Finally the treatment and management technology of the irradiated graphites that happened after decommissioning KRR-2 was developed in order to treat and manage the irradiated graphites safely

  8. A study on the decommissioning methods of nuclear facilities of North Korea

    International Nuclear Information System (INIS)

    Chung, U. S.; Park, J. H.; Park, S. K.; Hong, S. B.; Lee, G. W.

    2012-02-01

    For Korea, it is essential to participate in the decommissioning of North Korean nuclear facilities for Pu-based weapon program and to lead the project for the protection of the environments from the possible spread of nuclear contamination. Before, the studies for the verification of the North Korea nuclear facilities and for the technical preparation of the decommissioning of north Korea were conducted but the depth of the studies was not reached to the evaluation of the decommissioning project by the documentation of a decommissioning plan to the provision of the technical information to the policy decision makers. It is very helpful for understanding the characteristics of the decommissioning projects to formulate a possible dismantling scenario and to make a decommissioning plan. The cost and the periods estimated on the base of this scenario is more exact and the analysis for the selection of different policies will be possible

  9. European Nuclear Decommissioning Training Facility II

    International Nuclear Information System (INIS)

    Demeulemeester, Y.

    2005-01-01

    SCK-CEN co-ordinates a project called European Nuclear Decommissioning Training Facility II (EUNDETRAF II) in the Sixth Framework Programme on Community activities in the field of research, technological development and demonstration for the period 2002 to 2006. This was a continuation of the FP5 project EUNDETRAF. EUNDETRAF II is a consortium of main European decommissioners, such as SCK-CEN, EWN (Energie Werke Nord, Greifswald Germany), Belgatom (Belgium), SOGIN Societa Gestione Impiantio Nucleari, Italy), Universitaet Hannover (Germany), RWE NUKEM (United Kingdom), DECOM Slovakia Slovakia), CEA Centre d'Energie Atomique, France), UKAEA (United Kingdom's Atomic Energy Agency, United Kingdom) and NRG (Nuclear Research and consultancy Group, Netherlands). The primary objective of this project is to bring together this vast skill base and experience; to consolidate it for easy assimilation and to transfer to future generations by organising a comprehensive training programme.Each training course has a one-week theoretical and a one-week practical component. The theoretical part is for a broader audience and consists of lectures covering all the main aspects of a decommissioning. The practical part of the course includes site visits and desk top solutions of anticipated decommissioning problems. Due to operational constraints and safety considerations, the number of participants to this part of the course is strictly limited. The partners intend to organise altogether two two-week EUNDETRAF II training courses over a period of three years. Another goal is to disseminate the existing theory as well as the practical know-how to personnel of the third countries. Finally it is important to bring together the principal decommissioning organisations undertaking various decommissioning activities. The project creates a forum for regular contacts to exchange information and experiences for mutual benefit of these organisations as well as to enhance skill base in Europe to

  10. Standard Guide for Radiation Protection Program for Decommissioning Operations

    CERN Document Server

    American Society for Testing and Materials. Philadelphia

    1987-01-01

    1.1 This guide provides instruction to the individual charged with the responsibility for developing and implementing the radiation protection program for decommissioning operations. 1.2 This guide provides a basis for the user to develop radiation protection program documentation that will support both the radiological engineering and radiation safety aspects of the decommissioning project. 1.3 This guide presents a description of those elements that should be addressed in a specific radiation protection plan for each decommissioning project. The plan would, in turn, form the basis for development of the implementation procedures that execute the intent of the plan. 1.4 This guide applies to the development of radiation protection programs established to control exposures to radiation and radioactive materials associated with the decommissioning of nuclear facilities. The intent of this guide is to supplement existing radiation protection programs as they may pertain to decommissioning workers, members of...

  11. Conference on decontamination and decommissioning of nuclear facilities

    International Nuclear Information System (INIS)

    Meservey, R.H.

    1979-01-01

    A brief history of Decontamination and Decommissioning (D and D) experience at the Idaho National Engineering Laboratory is presented as an introduction to the status of current projects. Details are then presented as an introduction to the status of current projects. Details are then presented on a project to remove sodium from some major components of the Hallam reactor and on the Organic Moderated Reactor Experiment (OMRE) decommissioning project. Cost, schedule, waste volume, and other technical data from these projects are presented. In addition, a brief summary of the future INEL D and D program is presented

  12. Challenges of Ignalina NPP Decommissioning - View of Lithuanian Operator

    International Nuclear Information System (INIS)

    Aksionov, P.

    2017-01-01

    The state enterprise Ignalina Nuclear Power Plant (INPP) operates 2 similar design units of RBMK-1500 water-cooled graphite-moderated channel-type power reactors (1500 MW electrical power). INPP is carrying out the decommissioning project of the 2 reactors which includes: -) the retrieval of the spent nuclear fuel from the power units and its transportation into the Interim Spent Fuel Storage Facility; -) equipment and building decontamination and dismantling; -) radioactive waste treatment and storage; and -) the operation of key systems to ensure nuclear, radiation and fire protection. Ignalina NPP decommissioning project is planned to be completed by 2038. The presentation will be focused on the ongoing decommissioning activities at Ignalina NPP. The overview of main aspects and challenges of INPP decommissioning will be provided

  13. Lessons learned from decommissioning projects at Los Alamos National Laboratory

    International Nuclear Information System (INIS)

    Salazar, M.

    1995-01-01

    This paper describes lessons learned over the last 20 years from 12 decommissioning projects at Los Alamos National Laboratory. These lessons relate both to overall program management and to management of specific projects during the planning and operations phases. The issues include waste management; the National Environmental Policy Act (NEPA); the Resource Conservation and Recovery Act (RCRA); the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA); contracting; public involvement; client/customer interface; and funding. Key elements of our approach are to be proactive; follow the observation method; perform field activities concurrently; develop strategies to keep reportable incidents from delaying work; seek and use programs, methods, etc., in existence to shorten learning curves; network to help develop solutions; and avoid overstudying and overcharacterizing. This approach results in preliminary plans that require very little revision before implementation, reasonable costs and schedules, early acquisition of permits and NEPA documents, preliminary characterization reports, and contracting documents. Our track record is good -- the last four projects (uranium and plutonium-processing facility and three research reactors) have been on budget and on schedule

  14. Radiation environmental monitoring and assessment of plant-221 site ten years after decommissioning

    International Nuclear Information System (INIS)

    Li Yang; Gu Zhijie; Pan Wei; Ren Xiaona; Hu Xiaolin; She Haiqiang

    2011-01-01

    More than 10 years have passed since nuclear facility decommissioning practice for Plant-221 finished. Environmental radiation monitoring and post assessment of the decommissioning site of Plant-221 was carried out during 2003-2006, which was organized by Department of Environmental Protection and executed by China Institute for Radiation Protection, Environmental Radiation Monitoring station of Qinghai Province, etc. It shows that the decommissioning practice for Plant-221 complied with relevant limits for decommissioning, and its environmental radiation situation has not had significant change in general after 10 years, and the potential impact to the public and the environmental is acceptable. (authors)

  15. ALARA and decommissioning: The Fort St. Vrain experience

    Energy Technology Data Exchange (ETDEWEB)

    Borst, T.; Niehoff, M. [Public Service Co. of Colorado, Platteville, CO (United States); Zachary, M. [Scientific Ecology Group, Platteville, CO (United States)

    1995-03-01

    The Fort St. Vrain Nuclear Generating Station, the first and only commercial High Temperature Gas Cooled Reactor to operate in the United States, completed initial fuel loading in late 1973 and initial startup in early 1974. Due to a series of non-nuclear technical problems, Fort St. Vrain never operated consistently, attaining a lifetime capacity factor of slightly less than 15%. In August of 1989, the decision was made to permanently shut down the plant due to control rod drive and steam generator ring header failures. Public Service Company of Colorado elected to proceed with early dismantlement (DECON) as opposed to SAFSTOR on the bases of perceived societal benefits, rad waste, and exposure considerations, regulatory uncertainties associated with SAFSTOR, and cost. The decommissioning of Fort St. Vrain began in August of 1992, and is scheduled to be completed in early 1996. Decommissioning is being conducted by a team consisting of Westinghouse, MK-Ferguson, and Scientific Ecology Group. Public Service Company of Colorado as the licensee provides contract management and oversight of contractor functions. An aggressive program to maintain project radiation exposures As Low As Reasonably Achievable (ALARA) has been established, with the following program elements: temporary and permanent shielding contamination control; mockup training; engineering controls; worker awareness; integrated work package reviews communication; special instrumentation; video camera usage; robotics application; and project committees. To date, worker exposures have been less than project estimates. from the start of the project through Februrary of 1994, total exposure has been 98.666 person-rem, compared to the project estimate of 433 person-rem and goal of 347 person-rem. The presentation will discuss the site characterization efforts, the radiological performance indicator program, and the final site release survey plans.

  16. Surface radiological free release program for the Battelle Columbus Laboratory Decommissioning Project

    International Nuclear Information System (INIS)

    Horton, C.N.

    1995-01-01

    This paper was prepared for the Second Residual Radioactivity and Recycling Criteria Workshop and discusses decommissioning and decontamination activities at the Battelle Columbus Laboratories Decommissioning Project (BCLDP). The BCLDP is a joint effort between the Department of Energy (DOE) and Battelle Columbus Operations to decontaminate fifteen Battelle-owned buildings contaminated with DOE radioactive materials. The privately owned buildings located across the street from The Ohio State University campus became contaminated with natural uranium and thorium during nuclear research activities. BCLDP waste management is supported by an extensive radiological free-release program. Miscellaneous materials and building surfaces have been free-released from the BCLDP. The free-release program has substantially reduced radioactive waste volumes and supported waste minimization. Free release for unrestricted use has challenged regulators and NRC licensees since the development of early surface-release criteria. This paper discusses the surface radiological free-release program incorporated by the BCLDP and the historical development of the surface radiological free-release criteria. Concerns regarding radiological free-release criteria are also presented. (author)

  17. Planning, managing and organizing the decommissioning of nuclear facilities: Lessons learned

    International Nuclear Information System (INIS)

    2004-05-01

    This publication is intended to encourage the development and improvement of decommissioning planning and management techniques, with the focus on organizational aspects, reduce the duplication of efforts by different parties by transfer of experience and know-how, and provide useful results for those Member States planning or implementing decommissioning projects. In general it can be stated that any decommissioning project can be completed without any deleterious effects on the safety of the workforce and the public or any identifiable impact on the environment. However, timeliness and cost-effectiveness are not always optimal. It has been noted on several occasions that the major weakness in decommissioning projects (as well as in other industrial projects) is often not the lack of technologies, but rather poor planning and management. This publication intends to stimulate awareness of the need for early and efficient planning and to foster developments in management and organization in association with planned or ongoing decommissioning projects. A companion report on Organization and Management for Decommissioning of Large Nuclear Facilities was published by the IAEA in 2000 (Technical Report Series (TRS) No. 399). That TRS provides generic guidance on organizational and management aspects. This TECDOC is complementary to the existing report in that it highlights practical experience - in particular, typical issues, evidence of poor management, undue delays, and lack of timely funding - and distils lessons learned from this experience

  18. Decommissioning Cost Estimating -The ''Price'' Approach

    International Nuclear Information System (INIS)

    Manning, R.; Gilmour, J.

    2002-01-01

    Over the past 9 years UKAEA has developed a formalized approach to decommissioning cost estimating. The estimating methodology and computer-based application are known collectively as the PRICE system. At the heart of the system is a database (the knowledge base) which holds resource demand data on a comprehensive range of decommissioning activities. This data is used in conjunction with project specific information (the quantities of specific components) to produce decommissioning cost estimates. PRICE is a dynamic cost-estimating tool, which can satisfy both strategic planning and project management needs. With a relatively limited analysis a basic PRICE estimate can be produced and used for the purposes of strategic planning. This same estimate can be enhanced and improved, primarily by the improvement of detail, to support sanction expenditure proposals, and also as a tender assessment and project management tool. The paper will: describe the principles of the PRICE estimating system; report on the experiences of applying the system to a wide range of projects from contaminated car parks to nuclear reactors; provide information on the performance of the system in relation to historic estimates, tender bids, and outturn costs

  19. Interim Storage Facility decommissioning. Final report

    International Nuclear Information System (INIS)

    Johnson, R.P.; Speed, D.L.

    1985-01-01

    Decontamination and decommissioning of the Interim Storage Facility were completed. Activities included performing a detailed radiation survey of the facility, removing surface and imbedded contamination, excavating and removing the fuel storage cells, restoring the site to natural conditions, and shipping waste to Hanford, Washington, for burial. The project was accomplished on schedule and 30% under budget with no measurable exposure to decommissioning personnel

  20. Project WAGR: The UK demonstration project for power reactor decommissioning - removing the core and looking to completion

    International Nuclear Information System (INIS)

    Benest, T. G.

    2003-01-01

    delivered the required performance. In such cases, simple tooling and manual intervention have been adopted to maintain the project ahead of programme and below the dose budget. For campaigns where manual intervention was precluded by high dose rates, the contractor has undertaken a risk assessment of each task and elected to develop a number of different tools to cover the most likely risks. Although this strategy incurs costs for tools that may never be utilised, these costs are dwarfed by the project costs of potential delays. Excellent progress has been maintained throughout the remote dismantling with the reliability of the equipment and the experience of the workforce being major contributors to the success. Management arrangements have also contributed to the current excellent programme position. The close working relationship between UKAEA and their prime contractor, and management of the interfaces with the regulators, has enabled problems to be identified early and then dealt with quickly and effectively. The current phase of operations is now planned for completion in early 2005 over 18 months ahead of programme. Currently the WAGR project has operated for over 6 years without a lost time accident to either UKAEA staff or any of the contractor's operatives. In the last 12 months, the maximum radiation dose to an individual was <1.0 mSv. To date, 270 tonnes of graphite and 206 tonnes of steel have been encapsulated. 38 boxes of low level waste have been sent, or are awaiting transport, to BNFL's Drigg site for disposal, and a further 102 boxes of ILW are now stored on-site pending the availability of a national facility. Thus far the UKAEA WAGR project is well ahead of programme, achieving all its objectives and demonstrating to a world-wide audience that a power reactor can be decommissioned safely and efficiently shortly after shutdown

  1. The decommissioning and redevelopment of NECSA site

    International Nuclear Information System (INIS)

    Visagie, A.L.; Fourie, E.

    2008-01-01

    Full text: The South African nuclear programme started in 1948 and was focussed on research and development in the nuclear field. In the early 70s a uranium conversion plant and a uranium enrichment plant were constructed on the NECSA site. The enriched uranium was used for military purposes, as fuel for the research reactor SAFARI-1 at Necsa. A semi-commercial uranium enrichment plant and a fuel manufacturing plant were commissioned in the 80's to supply fuel for the nuclear power plant at Koeberg near Cape Town. Currently the research reactor is utilized for the generation of radioactive isotopes for industrial and medical applications. Various other research projects were initiated and buildings constructed on the Necsa site to accommodate the different projects. The uranium conversion and enrichment projects were terminated in the early 90's, and many buildings on the Necsa site became redundant. An initial decommissioning strategy was to return the Necsa site to green fields. This endpoint of decommissioning has changed dramatically with the nuclear renaissance to include redevelopment and reuse options. In the case of a multi-facility nuclear site, such as the Necsa site, it is vital to develop a total site redevelopment plan rather than to decommission and allocate individual facilities for isolated reuse demands. A holistic approach should be assured by considering current and projected future redevelopment demands in the development of a redevelopment and reuse plan. It is important not to allow the redevelopment and reuse of a single facility on a multi-facility site based on short- term financial gain. With the recent increase in demand for nuclear facilities the redevelopment and reuse of nuclear facilities for non-nuclear applications should generally not be considered due to the inherent advantages associated with an existing licensed site. The initial decommissioning plan did not consider the Necsa site as a whole. Decommissioning costs, and the

  2. Technology, safety, and costs of decommissioning a reference pressurized water reactor power station. Appendices

    International Nuclear Information System (INIS)

    Smith, R.I.; Konzek, G.J.; Kennedy, W.E. Jr.

    1978-05-01

    Detailed appendices are presented under the following headings: reference PWR facility description, reference PWR site description, estimates of residual radioactivity, alternative methods for financing decommissioning, radiation dose methodology, generic decommissioning activities, intermediate dismantlement activities, safe storage and deferred dismantlement activities, compilation of unit cost factors, and safety assessment details

  3. Decommissioning of TRIGA Mark II type reactor

    Energy Technology Data Exchange (ETDEWEB)

    Hwang, Dooseong; Jeong, Gyeonghwan; Moon, Jeikwon [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2012-10-15

    The first research reactor in Korea, KRR 1, is a TRIGA Mark II type with open pool and fixed core. Its power was 100 kWth at its construction and it was upgraded to 250 kWth. Its construction was started in 1957. The first criticality was reached in 1962 and it had been operated for 36,000 hours. The second reactor, KRR 2, is a TRIGA Mark III type with open pool and movable core. These reactors were shut down in 1995, and the decision was made to decommission both reactors. The aim of the decommissioning activities is to decommission the KRR 2 reactor and decontaminate the residual building structures and site, and to release them as unrestricted areas. The KRR 1 reactor was decided to be preserve as a historical monument. A project was launched for the decommissioning of these reactors in 1997, and approved by the regulatory body in 2000. A total budget for the project was 20.0 million US dollars. It was anticipated that this project would be completed and the site turned over to KEPCO by 2010. However, it was discovered that the pool water of the KRR 1 reactor was leaked into the environment in 2009. As a result, preservation of the KRR 1 reactor as a monument had to be reviewed, and it was decided to fully decommission the KRR 1 reactor. Dismantling of the KRR 1 reactor takes place from 2011 to 2014 with a budget of 3.25 million US dollars. The scope of the work includes licensing of the decommissioning plan change, removal of pool internals including the reactor core, removal of the thermal and thermalizing columns, removal of beam port tubes and the aluminum liner in the reactor tank, removal of the radioactive concrete (the entire concrete structure will not be demolished), sorting the radioactive waste (concrete and soil) and conditioning the radioactive waste for final disposal, and final statuses of the survey and free release of the site and building, and turning over the site to KEPCO. In this paper, the current status of the TRIGA Mark-II type reactor

  4. Decommissioning Technology Development for Nuclear Research Facilities

    Energy Technology Data Exchange (ETDEWEB)

    Lee, K. W.; Kang, Y. A.; Kim, G. H. (and others)

    2007-06-15

    It is predicted that the decommissioning of a nuclear power plant would happen in Korea since 2020 but the need of partial decommissioning and decontamination for periodic inspection and life extension still has been on an increasing trend and its domestic market has gradually been extended. Therefore, in this project we developed following several essential technologies as a decommissioning R and D. The measurement technology for in-pipe radioactive contamination was developed for measuring alpha/beta/gamma emitting nuclides simultaneously inside a in-pipe and it was tested into the liquid waste transfer pipe in KRR-2. And the digital mock-up system for KRR-1 and 2 was developed for choosing the best scenarios among several scenarios on the basis of various decommissioning information(schedule, waste volume, cost, etc.) that are from the DMU and the methodology of decommissioning cost estimation was also developed for estimating a research reactor's decommissioning cost and the DMU and the decommissioning cost estimation system were incorporated into the decommissioning information integrated management system. Finally the treatment and management technology of the irradiated graphites that happened after decommissioning KRR-2 was developed in order to treat and manage the irradiated graphites safely.

  5. Design of a requirements system for decommissioning of a nuclear power plant based on systems engineering

    Energy Technology Data Exchange (ETDEWEB)

    Park, Hee Seong; Park, Seung Kook; Jin, Hyung Gon; Song, Chan Ho; Choi, Jong won [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2015-10-15

    The nuclear industry has required an advanced system that can manage decommissioning information ever since the Korean government decide to decommission the Gori No.1 nuclear power plant. The D and D division at KAERI has been developing a system that can secure the reliability and sustainability of the decommissioning project based on the engineering system of the KRR-2 (Korean Research Reactor-2). To establish a decommissioning information system, a WBS that needs to be managed for the decommissioning of an NPP has been extracted, and requirements management research composed of system engineering technology has progressed. This paper propose a new type of system based on systems engineering technology. Even though a decommissioning engineering system was developed through the KRR-2, we are now developing an advanced decommissioning information system because it is not easy to apply this system to a commercial nuclear power plant. An NPP decommissioning is a project requiring a high degree of safety and economic feasibility. Therefore, we have to use a systematic project management at the initial phase of the decommissioning. An advanced system can manage the decommissioning information from preparation to remediation by applying a previous system to the systems engineering technology that has been widely used in large-scale government projects. The first phase of the system has progressed the requirements needed for a decommissioning project for a full life cycle. The defined requirements will be used in various types of documents during the decommissioning preparation phase.

  6. Full system chemical decontamination used in nuclear decommissioning

    International Nuclear Information System (INIS)

    Elder, George; Rottner, Bernard; Braehler, Georg

    2012-01-01

    The decommissioning of nuclear power stations at the end of the operational period of electricity generation offers technical challenges in the safe dismantling of the facility and the minimization of radioactive waste arising from the decommissioning activities. These challenges have been successfully overcome as demonstrated by decommissioning of the first generation of nuclear power plants. One of the techniques used in decommissioning is that of chemical decontamination which has a number of functions and advantages as given here: 1. Removal of contamination from metal surfaces in the reactors cooling systems. 2. Reduction of radioactive exposure to decommissioning workers 3. Minimization of metal waste by decontamination and recycling of metal components 4. Control of contamination when dismantling reactor and waste systems 5. Reduction in costs due to lower radiation fields, lower contamination levels and minimal metal waste volume for disposal. One such chemical decontamination technology was developed for the Electric Power Research Institute (EPRI) by Bradtec (Bradtec is an ONET Technologies subsidiary) and is known as the EPRI DFD system. This paper gives a description of the EPRI DFD system, and highlights the experience using the system. (orig.)

  7. Enhanced productivity in reactor decommissioning and waste management

    International Nuclear Information System (INIS)

    Wasinger, Karl

    2014-01-01

    As for any industrial facility, the service live of nuclear power plants, fuel cycle facilities, research and test reactors ends. Decision for decommissioning such facilities may be motivated by technical, economical or political reasons or a combination of it. As of today, a considerable number of research reactors, fuel cycle facilities and power reactors have been completely decommissioned. However, the end point of such facilities' lifetime is achieved, when the facility is finally removed from regulatory control and the site becomes available for further economical utilization. This process is commonly known as decommissioning and involves detailed planning of all related activities, radiological characterization, dismantling, decontamination, clean-up of the site including treatment and packaging of radioactive and/or contaminated material not released for unrestricted recycling or industrial disposal. Decommissioning requires adequate funding and suitable measures to ensure safety while addressing stakeholders' requirements on occupational health, environment, economy, human resources management and the socioeconomic effects to the community and the region. One important aspect in successful management of decommissioning projects and dismantling operation relates to the economical impact of the endeavor, primarily depending on the selected strategy and, as from commencement of dismantling, on total duration until the end point is achieved. Experience gained by Areva in executing numerous decommissioning projects during past 2 decades shows that time injury free execution and optimum productivity turns out crucial to project cost. Areva develops and implements specific 'performance improvement plans' for each of its projects which follow the philosophy of operational excellence based on Lean Manufacturing principles. Means and methods applied in implementation of these plans and improvements achieved are described and examples are given on the way Areva

  8. Enhanced productivity in reactor decommissioning and waste management

    Energy Technology Data Exchange (ETDEWEB)

    Wasinger, Karl [Areva GmbH, Offenbach (Germany)

    2014-04-15

    As for any industrial facility, the service live of nuclear power plants, fuel cycle facilities, research and test reactors ends. Decision for decommissioning such facilities may be motivated by technical, economical or political reasons or a combination of it. As of today, a considerable number of research reactors, fuel cycle facilities and power reactors have been completely decommissioned. However, the end point of such facilities' lifetime is achieved, when the facility is finally removed from regulatory control and the site becomes available for further economical utilization. This process is commonly known as decommissioning and involves detailed planning of all related activities, radiological characterization, dismantling, decontamination, clean-up of the site including treatment and packaging of radioactive and/or contaminated material not released for unrestricted recycling or industrial disposal. Decommissioning requires adequate funding and suitable measures to ensure safety while addressing stakeholders' requirements on occupational health, environment, economy, human resources management and the socioeconomic effects to the community and the region. One important aspect in successful management of decommissioning projects and dismantling operation relates to the economical impact of the endeavor, primarily depending on the selected strategy and, as from commencement of dismantling, on total duration until the end point is achieved. Experience gained by Areva in executing numerous decommissioning projects during past 2 decades shows that time injury free execution and optimum productivity turns out crucial to project cost. Areva develops and implements specific 'performance improvement plans' for each of its projects which follow the philosophy of operational excellence based on Lean Manufacturing principles. Means and methods applied in implementation of these plans and improvements achieved are described and examples are given on

  9. Plan for decommissioning the Tokamak Fusion Test Reactor

    International Nuclear Information System (INIS)

    Spampinato, P.T.; Walton, G.R.

    1993-01-01

    The Tokamak Fusion Test Reactor (TFTR) Project is in the planning phase of developing a decommissioning project. A Preliminary Decontamination and Decommissioning (D ampersand D) Plan has been developed which provides a framework for the baseline approach, and the cost and schedule estimates. TFTR will become activated and contaminated with tritium after completion of the deuterium-tritium (D-T) experiments. Hence some of the D ampersand D operations will require remote handling. It is expected that all of the waste generated will be low level radioactive waste (LLW). The objective of the D ampersand D Project is to make TFTR Test Cell available for use by a new fusion experiment. This paper discusses the D ampersand D objectives, the facility to be decommissioned, estimates of activation, the technical (baseline) approach, and the assumptions used to develop cost and schedule estimates

  10. Options for Steam Generator Decommissioning

    International Nuclear Information System (INIS)

    Krause, Gregor; Amcoff, Bjoern; Robinson, Joe

    2016-01-01

    Selecting the best option for decommissioning steam generators is a key consideration in preparing for decommissioning PWR nuclear power plants. Steam Generators represent a discrete waste stream of large, complex items that can lend themselves to a variety of options for handling, treatment, recycling and disposal. Studsvik has significant experience in processing full size Steam Generators at its metal recycling facility in Sweden, and this paper will introduce the Studsvik steam generator treatment concept and the results achieved to date across a number of projects. The paper will outline the important parameters needed at an early stage to assess options and to help consider the balance between off-site and on-site treatment solutions, and the role of prior decontamination techniques. The paper also outlines the use of feasibility studies and demonstration projects that have been used to help customers prepare for decommissioning. The paper discusses physical, radiological and operational history data, Pro and Contra factors for on- and off-site treatment, the role of chemical decontamination prior to treatment, planning for off-site shipments as well as Studsvik experience This paper has an original focus upon the coming challenges of steam generator decommissioning and potential external treatment capacity constraints in the medium term. It also focuses on the potential during operations or initial shut-down to develop robust plans for steam generator management. (authors)

  11. Development of computer program for estimating decommissioning cost - 59037

    International Nuclear Information System (INIS)

    Kim, Hak-Soo; Park, Jong-Kil

    2012-01-01

    The programs for estimating the decommissioning cost have been developed for many different purposes and applications. The estimation of decommissioning cost is required a large amount of data such as unit cost factors, plant area and its inventory, waste treatment, etc. These make it difficult to use manual calculation or typical spreadsheet software such as Microsoft Excel. The cost estimation for eventual decommissioning of nuclear power plants is a prerequisite for safe, timely and cost-effective decommissioning. To estimate the decommissioning cost more accurately and systematically, KHNP, Korea Hydro and Nuclear Power Co. Ltd, developed a decommissioning cost estimating computer program called 'DeCAT-Pro', which is Decommission-ing Cost Assessment Tool - Professional. (Hereinafter called 'DeCAT') This program allows users to easily assess the decommissioning cost with various decommissioning options. Also, this program provides detailed reporting for decommissioning funding requirements as well as providing detail project schedules, cash-flow, staffing plan and levels, and waste volumes by waste classifications and types. KHNP is planning to implement functions for estimating the plant inventory using 3-D technology and for classifying the conditions of radwaste disposal and transportation automatically. (authors)

  12. The decommissioning of the Barnwell nuclear fuel plant

    International Nuclear Information System (INIS)

    McNeil, J.

    1999-01-01

    The decommissioning of the Barnwell Nuclear Fuel Plant is nearing completion. The owner's objective is to terminate the plant radioactive material license associated with natural uranium and transuranic contamination at the plant. The property is being released for commercial-industrial uses, with radiation exposure from residual radioactivity not to exceed 0.15 millisieverts per year. Historical site assessments have been performed and the plant characterized for residual radioactivity. The decommissioning of the uranium hexafluoride building was completed in April, 1999. Most challenging from a radiological control standpoint is the laboratory building that contained sixteen labs with a total of 37 glove boxes, many of which had seen transuranics. Other facilities being decommissioned include the separations building and the 300,000-gallon underground high-level waste tanks. This decommissioning in many ways is the most significant project of this type yet undertaken in South Carolina. Many innovations have been made to reduce the time and costs associated with the project. (author)

  13. Role of decommissioning plan and its progress for the PUSPATI TRIGA Reactor

    International Nuclear Information System (INIS)

    Zakaria, Norasalwa; Mustafa, Muhammad Khairul Ariff; Anuar, Abul Adli; Idris, Hairul Nizam; Ba'an, Rohyiza

    2014-01-01

    Malaysian nuclear research reactor, the PUSPATI TRIGA Reactor, reached its first criticality in 1982, and since then, it has been serving for more than 30 years for training, radioisotope production and research purposes. Realizing the age and the need for its decommissioning sometime in the future, a ground basis of assessment and an elaborative project management need to be established, covering the entire process from termination of reactor operation to the establishment of final status, documented as the Decommissioning Plan. At international level, IAEA recognizes the absence of Decommissioning Plan as one of the factors hampering progress in decommissioning of nuclear facilities in the world. Throughout the years, IAEA has taken initiatives and drawn out projects in promoting progress in decommissioning programmes, like CIDER, DACCORD and R2D2P, for which Malaysia is participating in these projects. This paper highlights the concept of Decommissioning plan and its significances to the Agency. It will also address the progress, way forward and challenges faced in developing the Decommissioning Plan for the PUSPATI TRIGA Reactor. The efforts in the establishment of this plan helps to provide continual national contribution at the international level, as well as meeting the regulatory requirement, if need be. The existing license for the operation of PUSPATI TRIGA Reactor does not impose a requirement for a decommissioning plan; however, the renewal of license may call for a decommissioning plan to be submitted for approval in future

  14. Role of decommissioning plan and its progress for the PUSPATI TRIGA Reactor

    International Nuclear Information System (INIS)

    Norasalwa Zakaria; Muhammad Khairul Ariff Mustafa; Abul Adli Anuar; Hairul Nizam Idris; Rohyiza Baan

    2013-01-01

    Full-text: Malaysian nuclear research reactor, the PUSPATI TRIGA Reactor, reached its first criticality in 1982, and since then, it has been serving for more than 30 years for training, radioisotope production and research purposes. Realizing the age and the need for its decommissioning sometime in the future, a ground basis of assessment and an elaborative project management need to be established, covering the entire process from termination of reactor operation to the establishment of final status, documented as the Decommissioning Plan. At international level, IAEA recognizes the absence of Decommissioning Plan as one of the factors hampering progress in decommissioning of nuclear facilities in the world. Throughout the years, IAEA has taken initiatives and drawn out projects in promoting progress in decommissioning programmes, like CIDER, DACCORD and R2D2P, for which Malaysia is participating in these projects. This paper highlights the concept of Decommissioning plan and its significances to the Agency. It will also address the progress, way forward and challenges faced in developing the Decommissioning Plan for the PUSPATI TRIGA Reactor. The efforts in the establishment of this plan helps to provide continual national contribution at the international level, as well as meeting the regulatory requirement, if need be. The existing license for the operation of PUSPATI TRIGA Reactor does not impose a requirement for a decommissioning plan; however, the renewal of license may call for a decommissioning plan to be submitted for approval in future. (author)

  15. Role of decommissioning plan and its progress for the PUSPATI TRIGA Reactor

    Energy Technology Data Exchange (ETDEWEB)

    Zakaria, Norasalwa, E-mail: norasalwa@nuclearmalaysia.gov.my; Mustafa, Muhammad Khairul Ariff, E-mail: norasalwa@nuclearmalaysia.gov.my; Anuar, Abul Adli, E-mail: norasalwa@nuclearmalaysia.gov.my; Idris, Hairul Nizam, E-mail: norasalwa@nuclearmalaysia.gov.my; Ba' an, Rohyiza, E-mail: norasalwa@nuclearmalaysia.gov.my [Malaysian Nuclear Agency, 43000 Kajang, Selangor (Malaysia)

    2014-02-12

    Malaysian nuclear research reactor, the PUSPATI TRIGA Reactor, reached its first criticality in 1982, and since then, it has been serving for more than 30 years for training, radioisotope production and research purposes. Realizing the age and the need for its decommissioning sometime in the future, a ground basis of assessment and an elaborative project management need to be established, covering the entire process from termination of reactor operation to the establishment of final status, documented as the Decommissioning Plan. At international level, IAEA recognizes the absence of Decommissioning Plan as one of the factors hampering progress in decommissioning of nuclear facilities in the world. Throughout the years, IAEA has taken initiatives and drawn out projects in promoting progress in decommissioning programmes, like CIDER, DACCORD and R2D2P, for which Malaysia is participating in these projects. This paper highlights the concept of Decommissioning plan and its significances to the Agency. It will also address the progress, way forward and challenges faced in developing the Decommissioning Plan for the PUSPATI TRIGA Reactor. The efforts in the establishment of this plan helps to provide continual national contribution at the international level, as well as meeting the regulatory requirement, if need be. The existing license for the operation of PUSPATI TRIGA Reactor does not impose a requirement for a decommissioning plan; however, the renewal of license may call for a decommissioning plan to be submitted for approval in future.

  16. The First Decommissioning of a Fusion Reactor Fueled by Deuterium-Tritium

    International Nuclear Information System (INIS)

    Gentile, Charles A.; Perry, Erik; Rule, Keith; Williams, Michael; Parsells, Robert; Viola, Michael; Chrzanowski, James

    2003-01-01

    The Tokamak Fusion Test Reactor (TFTR) at the Plasma Physics Laboratory of Princeton University (PPPL) was the first fusion reactor fueled by a mixture of deuterium and tritium (D-T) to be decommissioned in the world. The decommissioning was performed over a period of three years and was completed safely, on schedule, and under budget. Provided is an overview of the project and detail of various factors which led to the success of the project. Discussion will cover management of the project, engineering planning before the project started and during the field work as it was being performed, training of workers in the field, the novel adaptation of tools from other industry, and the development of an innovative process for the use of diamond wire to segment the activated/contaminated vacuum vessel. The success of the TFTR decommissioning provides a viable model for the decommissioning of D-T burning fusion devices in the future

  17. Decommissioning: Strategies and programmes at the International Atomic Energy Agency (IAEA)

    International Nuclear Information System (INIS)

    Laraia, M.

    2003-01-01

    The International Atomic Energy Agency (IAEA) has included decommissioning in its regular programmes since 1985. Until a few years ago, attention was focused on the decommissioning of nuclear power plants, and to a lesser extent, research reactors. Some countries, however, are now devoting greater attention to the decommissioning of non-reactor facilities, with implementation of these programmes being seen as a high priority. This demanded equal attention in IAEA's programmes. In recent years, the IAEA has expanded its programmes to include guidance on decommissioning of small medical, industrial and research facilities which are prevailing in most of its over 130 Member States. By 2010-2020, a significant number of nuclear power plants, research reactors, fuel cycle and non-reactor facilities will have exceeded their normal design lifetimes. Many of these facilities are already shutdown and are awaiting decommissioning. In 1996, the IAEA organized the decommissioning programme along two directions. A first direction focuses on the safety of management of radioactive waste including decommissioning. A second direction focuses on the technology and strategies to support waste management and decommissioning activities. This split of activities was instituted in order to keep the regulatory aspects separated from the strategic and technology-related activities. The focus of this paper will be on current and foreseen activities related to strategies and technologies of decommissioning, but other activities will be touched upon as well. All technical divisions of the IAEA provide technical support for Technical Co-operation (TC) projects with developing countries. TC projects in the field of decommissioning are given separate coverage in this paper. The IAEA documents on decommissioning strategies and technologies are presented in Section 2. Technical Co-operation Programme concerning Decommissioning is discussed focusing the objectives, the specific projects and the

  18. Jose Cabrera dismantling and decommissioning project

    International Nuclear Information System (INIS)

    Ondaro, Manuel

    2013-01-01

    The Jose Cabrera Nuclear Power Plant (NPP) was the first commercial power reactor (Westinghouse 1 loop PWR 510 MWth, 160 MWe) commissioned in Spain and provided the base for future development and training. The reactor construction started in 1963 and it was officially on-line by 1969. The NPP operated from 1969 until 2006 when it became the first reactor to be shut down after completing its operational period. The containment is reinforced concrete with a stainless steel head. In 2010 responsibility for D and D was transferred to Enresa to achieve IAEA level 3 (a green field site available for unrestricted re-uses) by 2017. Of the total of more than 104,000 tons of materials that will be generated during dismantling, it is estimated that only ∼4,000 tons will be radioactive waste, some of which, 40 t are considered as intermediate level long-lived wastes and the rest (3,960 t) will be categorized as VLLW and ILLW. The Project is divided into five phases: Phase 0 - Removal of fuel and preliminary work.. Phase 1 - Preparatory Activities for D and D. complete. Phase 2 - Dismantling of Major Components. Phase 3 - Removal of Auxiliary Installations, Decontamination and Demolition. Phase 4 - Environmental Restoration. Phase 2, is currently ongoing (50% completed). To manage the diverse aspects of decommissioning operations, Enresa uses an internally developed computerized project management tool. The tool, based on knowledge gathered from other Enresa projects, can process operations management, maintenance operations, materials, waste, storage areas, procedures, work permits, operator dose management and records. Enresa considers that communication is important for both internal and external stakeholder relations and can be used to inform, to neutralize negative opinions and attitudes, to remove false expectations and for training. Enresa has created a new multi-purpose area (exhibition/visitor centre) and encourages visits from the public, local schools, local and

  19. Jose Cabrera dismantling and decommissioning project

    Energy Technology Data Exchange (ETDEWEB)

    Ondaro, Manuel [ENRESA, Madrid (Spain)

    2013-07-01

    The Jose Cabrera Nuclear Power Plant (NPP) was the first commercial power reactor (Westinghouse 1 loop PWR 510 MWth, 160 MWe) commissioned in Spain and provided the base for future development and training. The reactor construction started in 1963 and it was officially on-line by 1969. The NPP operated from 1969 until 2006 when it became the first reactor to be shut down after completing its operational period. The containment is reinforced concrete with a stainless steel head. In 2010 responsibility for D and D was transferred to Enresa to achieve IAEA level 3 (a green field site available for unrestricted re-uses) by 2017. Of the total of more than 104,000 tons of materials that will be generated during dismantling, it is estimated that only ∼4,000 tons will be radioactive waste, some of which, 40 t are considered as intermediate level long-lived wastes and the rest (3,960 t) will be categorized as VLLW and ILLW. The Project is divided into five phases: Phase 0 - Removal of fuel and preliminary work.. Phase 1 - Preparatory Activities for D and D. complete. Phase 2 - Dismantling of Major Components. Phase 3 - Removal of Auxiliary Installations, Decontamination and Demolition. Phase 4 - Environmental Restoration. Phase 2, is currently ongoing (50% completed). To manage the diverse aspects of decommissioning operations, Enresa uses an internally developed computerized project management tool. The tool, based on knowledge gathered from other Enresa projects, can process operations management, maintenance operations, materials, waste, storage areas, procedures, work permits, operator dose management and records. Enresa considers that communication is important for both internal and external stakeholder relations and can be used to inform, to neutralize negative opinions and attitudes, to remove false expectations and for training. Enresa has created a new multi-purpose area (exhibition/visitor centre) and encourages visits from the public, local schools, local and

  20. A large decommissioning project with added value

    International Nuclear Information System (INIS)

    Clements, D.W.

    1998-01-01

    The East Tennessee Technology Park (ETTP) in Oak Ridge, Tennessee, is a centerpiece for the Department of Energy's Reindustrialization program, which seeks to convert formerly used facilities for broad, industrial purposes. BNFL and its partners have been charged with the decommissioning and decontamination of three large gaseous diffusion buildings. BNFL's prior experience with a similar site, Capenhurst, in the United Kingdom was successful in reducing the quantities and costs of low level wastes for disposal. In that program, over 99% of 160,000 tonnes of surface-contaminated materials were safely and cost-effectively treated. Resulting materials could thus be recycled for complete unrestricted re-use within the UK. Decommissioning and decontamination at the ETTP site will be informed by the prior experience and lessons learned. Specialized technologies and approaches developed at Capenhurst will find expression at ETTP. The result will be safe, cost-effective techniques that permit maximum recycle and further use of presently contaminated buildings for industrial purposes. (author)

  1. Proceedings of the research conference on cementitious composites in decommissioning and waste management (RCWM2017)

    International Nuclear Information System (INIS)

    Sano, Yuichi; Ashida, Takashi

    2017-11-01

    Collaborative Laboratories for Advanced Decommissioning Science (CLADS) is responsible to promote international cooperation in the R and D activities on the decommissioning of Fukushima Daiichi Nuclear Power Station and to develop the necessary human resources. CLADS held the Research Conference on Cementitious Composites in Decommissioning and Waste Management (RCWM2017) on 20th and 21st June, 2017. This report compiles the abstracts and the presentation materials in the above conference. (author)

  2. Technology, safety and costs of decommissioning a reference boiling water reactor power station. Appendices. Volume 2

    Energy Technology Data Exchange (ETDEWEB)

    Oak, H.D.; Holter, G.M.; Kennedy, W.E. Jr.; Konzek, G.J.

    1980-06-01

    Appendices are presented concerning the evaluations of decommissioning financing alternatives; reference site description; reference BWR facility description; radiation dose rate and concrete surface contamination data; radionuclide inventories; public radiation dose models and calculated maximum annual doses; decommissioning methods; generic decommissioning information; immediate dismantlement details; passive safe storage, continuing care, and deferred dismantlement details; entombment details; demolition and site restoration details; cost estimating bases; public radiological safety assessment details; and details of alternate study bases.

  3. Knowledge Management Aspects of Decommissioning. Case Study

    International Nuclear Information System (INIS)

    Pironkov, Lyubomir

    2017-01-01

    Kozloduy NPP: Units 5&6, type VVER-1000 - in operation. SE RAW SD “Decommissioning of units 1-4” (type VVER-440); SD “Radioactive Waste – Kozloduy”; SD “National Repository for Radioactive Waste“; SD “Permanent Repository for Radioactive Waste – Novi Han”. Decommissioning Strategy: Strategy Target: “Brown Field”. Initial Version: Safe enclosure – completing by 2050. Updated Version: Continuous dismantling of equipment; Completing the process of Decommissioning of Units 1-4 by 2030. Major Phases: 1.Pre-decommissioning activities; 2.Facility shutdown activities; 3.Procurement of equipment; 4.Dismantling activities; 5.Treatment of RAM and RAW and delivery for disposal; 6.Site management and support; 7.Project management and engineering; 8.Management of SNF and activated materials

  4. Vandellos 1 NPP decommissioning feedback experience

    International Nuclear Information System (INIS)

    Fernandez, Rodriguez A.

    2003-01-01

    The Vandellos 1 Nuclear Power Plant (CNV1) is located on the Mediterranean coast in the province of Tarragona (Spain). The Plant is of the European Natural Uranium Graphite-Gas type. The thermal power of the plant amounts to 1,670 MWt, its electrical output being 500 Mwe. The Plant started-up commercial service in May 1972; its final shutdown, due to a fire in the turbines, occurred in October 1989, after 17 years of operation with an accumulated energy production of 55,647 GWh. The option of decommissioning accepted by the Ministry of Industry, consists of first removing the spent fuel and conditioning the operating radioactive wastes, and then undertaking dismantling of almost all the structures and components located outside the reactor vessel, except those ensuring confinement of the vessel itself and the safety and surveillance of the facility and site. No action will be taken with respect to the vessel, in which the reactor will remain confined without nuclear fuel and with its internal components intact until completion of the waiting (dormancy) period. The site itself will be kept under surveillance during dormancy phase, following partial clearance, the remaining installations being left within the new site perimeter in a situation of monitored confinement. Following the dormancy period, which will last some 30 years, total dismantling of the remaining installations will be undertaken, this implying subsequent complete clearance of the site. The project was started in November of 1992, and the works on site began in 1998. The safe enclosure consists only in the reactor pressure vessel, which will be left on site. The activity content of the vessel is about 100 000 Ci, mostly Co 60. Part of the Stage 2 concept is the total static isolation of this vessel. The vessel has 1 700 penetrations, the pipes of which were cut, seal-welded and inspected. After five years of works in Vandellos 1 NPP decommissioning, ENRESA has an experience and knowledge, that is

  5. INTERNATIONAL DECOMMISSIONING SYMPOSIUM 2000

    Energy Technology Data Exchange (ETDEWEB)

    M.A. Ebadian, Ph.D.

    2001-01-01

    The purpose of IDS 2000 was to deliver a world-class conference on applicable global environmental issues. The objective of this conference was to publicize environmental progress of individual countries, to provide a forum for technology developer and problem-holder interaction, to facilitate environmental and technology discussions between the commercial and financial communities, and to accommodate information and education exchange between governments, industries, universities, and scientists. The scope of this project included the planning and execution of an international conference on the decommissioning of nuclear facilities, and the providing of a business forum for vendors and participants sufficient to attract service providers, technology developers, and the business and financial communities. These groups, when working together with attendees from regulatory organizations and government decision-maker groups, provide an opportunity to more effectively and efficiently expedite the decommissioning projects.

  6. CONSIDERATIONS FOR THE DEVELOPMENT OF A DEVICE FOR THE DECOMMISSIONING OF THE HORIZONTAL FUEL CHANNELS IN THE CANDU 6 NUCLEAR REACTOR PART 5 - FUEL CHANEL DECOMMISSIONING

    Directory of Open Access Journals (Sweden)

    Gabi ROSCA FARTAT

    2014-05-01

    Full Text Available As many nuclear power plants are reaching their end of lifecycle, the decommissioning of these installations has become one of the 21st century’s great challenges. Each project may be managed differently, depending on the country, development policies, financial considerations, and the availability of qualified engineers or specialized companies to handle such projects. The principle objective of decommissioning is to place a facility into such a condition that there is no unacceptable risk from the decommissioned facility to public health and safety of the environment. In order to ensure that at the end of its life the risk from a facility is within acceptable bounds, action is normally required. The overall decommissioning strategy is to deliver a timely, cost-effective program while maintaining high standards of safety, security and environmental protection. If facilities were not decommissioned, they could degrade and potentially present an environmental radiological hazard in the future. Simply abandoning or leaving a facility after ceasing operations is not considered to be an acceptable alternative to decommissioning. The final aim of decommissioning is to recover the geographic site to its original condition.

  7. Treatment of organic radioactive waste in decommissioning project

    International Nuclear Information System (INIS)

    Dimovic, S.; Plecas, I.

    2003-01-01

    This paper describes methods of treatment of organic radioactive waste in the aspect of its integral part of radioactive waste which will arise during decommissioning process of nuclear power reactor RA (author)

  8. A Radiological Survey Approach to Use Prior to Decommissioning: Results from a Technology Scanning and Assessment Project Focused on the Chornobyl NPP

    Energy Technology Data Exchange (ETDEWEB)

    Milchikov, A.; Hund, G.; Davidko, M.

    1999-10-20

    The primary objectives of this project are to learn how to plan and execute the Technology Scanning and Assessment (TSA) approach by conducting a project and to be able to provide the approach as a capability to the Chernobyl Nuclear Power Plant (ChNPP) and potentially elsewhere. A secondary objective is to learn specifics about decommissioning and in particular about radiological surveying to be performed prior to decommissioning to help ChNPP decision makers. TSA is a multi-faceted capability that monitors and analyzes scientific, technical, regulatory, and business factors and trends for decision makers and company leaders. It is a management tool where information is systematically gathered, analyzed, and used in business planning and decision making. It helps managers by organizing the flow of critical information and provides managers with information they can act upon. The focus of this TSA project is on radiological surveying with the target being ChNPP's Unit 1. This reactor was stopped on November 30, 1996. At this time, Ukraine failed to have a regulatory basis to provide guidelines for nuclear site decommissioning. This situation has not changed as of today. A number of documents have been prepared to become a basis for a combined study of the ChNPP Unit 1 from the engineering and radiological perspectives. The results of such a study are expected to be used when a detailed decommissioning plan is created.

  9. A Radiological Survey Approach to Use Prior to Decommissioning: Results from a Technology Scanning and Assessment Project Focused on the Chernobyl NPP

    International Nuclear Information System (INIS)

    Milchikov, A.; Hund, G.; Davidko, M.

    1999-01-01

    The primary objectives of this project are to learn how to plan and execute the Technology Scanning and Assessment (TSA) approach by conducting a project and to be able to provide the approach as a capability to the Chernobyl Nuclear Power Plant (ChNPP) and potentially elsewhere. A secondary objective is to learn specifics about decommissioning and in particular about radiological surveying to be performed prior to decommissioning to help ChNPP decision makers. TSA is a multi-faceted capability that monitors and analyzes scientific, technical, regulatory, and business factors and trends for decision makers and company leaders. It is a management tool where information is systematically gathered, analyzed, and used in business planning and decision making. It helps managers by organizing the flow of critical information and provides managers with information they can act upon. The focus of this TSA project is on radiological surveying with the target being ChNPP's Unit 1. This reactor was stopped on November 30, 1996. At this time, Ukraine failed to have a regulatory basis to provide guidelines for nuclear site decommissioning. This situation has not changed as of today. A number of documents have been prepared to become a basis for a combined study of the ChNPP Unit 1 from the engineering and radiological perspectives. The results of such a study are expected to be used when a detailed decommissioning plan is created

  10. Establishment the code for prediction of waste volume on NPP decommissioning

    International Nuclear Information System (INIS)

    Cho, W. H.; Park, S. K.; Choi, Y. D.; Kim, I. S.; Moon, J. K.

    2013-01-01

    In practice, decommissioning waste volume can be estimated appropriately by finding the differences between prediction and actual operation and considering the operational problem or supplementary matters. So in the nuclear developed countries such as U.S. or Japan, the decommissioning waste volume is predicted on the basis of the experience in their own decommissioning projects. Because of the contamination caused by radioactive material, decontamination activity and management of radio-active waste should be considered in decommissioning of nuclear facility unlike the usual plant or facility. As the decommissioning activity is performed repeatedly, data for similar activities are accumulated, and optimal strategy can be achieved by comparison with the predicted strategy. Therefore, a variety of decommissioning experiences are the most important. In Korea, there is no data on the decommissioning of commercial nuclear power plants yet. However, KAERI has accumulated the basis decommissioning data of nuclear facility through decommissioning of research reactor (KRR-2) and uranium conversion plant (UCP). And DECOMMIS(DECOMMissioning Information Management System) was developed to provide and manage the whole data of decommissioning project. Two codes, FAC code and WBS code, were established in this process. FAC code is the one which is classified by decommissioning target of nuclear facility, and WBS code is classified by each decommissioning activity. The reason why two codes where created is that the codes used in DEFACS (Decommissioning Facility Characterization management System) and DEWOCS (Decommissioning Work-unit productivity Calculation System) are different from each other, and they were classified each purpose. DEFACS which manages the facility needs the code that categorizes facility characteristics, and DEWOCS which calculates unit productivity needs the code that categorizes decommissioning waste volume. KAERI has accumulated decommissioning data of KRR

  11. Experience Practices on Decontamination Activity in NPP Decommissioning

    Energy Technology Data Exchange (ETDEWEB)

    Yoon, Suk Bon; Kim, Jeongju; Sohn, Wook [Korea Hydro and Nuclear Power Co., Daejeon (Korea, Republic of)

    2016-10-15

    Decommissioning of a nuclear power plant (NPP) involves various technical and administrative activities for a utility to terminate its license, which allows the plant site to be released from the regulatory control (site release). Decontamination activity in NPP decommissioning is one of the main technical activities to be performed during the decommissioning. The decontamination at decommissioning sites is usually performed due to several reasons such as reducing personnel dose and disposal costs, and cleanup to meet license termination requirements by using physical or chemical removal techniques proven through the previous experience practices. This paper introduces the best and worst practices for the decontamination activities collected from the decommissioning operational experiences through the implementation of nuclear decommissioning projects around the world. Review of the experiences of decontamination shows that it is important to conduct an advanced planning for optimized implementation of decontamination taking into considering site specific conditions such as operating time, reactor type, system, and so on. Also, a review of newer decontamination methods is necessary to safely and economically decommission the nuclear facility.

  12. Sixteen Years of International Co-operation. The OECD/NEA Co-operative Programme on Decommissioning

    International Nuclear Information System (INIS)

    Menon, S.; Valencia, L.

    2002-01-01

    The Co-operative Programme on Decommissioning under the administration of the Radioactive Waste Management Committee of the OECD Nuclear Energy Agency (NEA) has recently completed sixteen years of operation. The Programme, which is essentially an information exchange programme between decommissioning projects, came into being in 1985. It has grown from an initial 10 decommissioning projects from 7 countries to 39 projects from 14 countries today. From purely information exchange to start with, the Programme has, in later years, been functioning as a voice for the collective expression of views of the implementers of nuclear decommissioning. During the first sixteen years of the operation of the Co-operative Programme, nuclear decommissioning has grown from local specialist activities within projects to a competitive commercial industry. By the dismantling and release from regulatory control of over a dozen diverse nuclear facilities, the Programme has been able to demonstrate in practice, that nuclear decommissioning can be performed safely both for the workers and the public, and that this can be done at reasonable costs in an environmentally friendly fashion. During the recent years, discussions and work within the Co-operative Programme, specially within some of the Task Groups, have had/are having effects and repercussions not just in the field of nuclear decommissioning, but can possibly affect activities and regulations in other industries. This paper describes how the Programme and its activities and procedures have evolved over the years and indicate the directions of developments in the organization and execution of decommissioning projects. Finally, it gives a brief overview of the achievements of the Cooperative Programme and visualizes future developments in the field of nuclear decommissioning

  13. Vandellos 1 decommissioning project. Safety before, during and after

    International Nuclear Information System (INIS)

    Rodriguez, A.

    2002-01-01

    The Nuclear Power Plant of Vandellos 1, a gas-graphite reactor (GCR), started operation in the 70's after 17 years running the decommissioning process began in 1998, and is expected to finish at the end of 2002 with the level 2 of decommissioning with a practically total scope reached, except the concrete reactor vessel and its internals that will remain for another 25 years in surveillance state (dormancy) until their total dismantling. During the last four years the activities related to decontamination and disassembly of the power plant system as well as the management of all this material have been carried out. One of the last phases of the project that will be performed this year, without doubt, one of the most representative of the operative difficulty of the task is the disassembly of some buildings which are more than 80 meters high and with some structures weighing more than 3.000 t, an operation, which is spectacular in terms of volume and mass involved. However one has to keep in mind that it has been preceded by the of clearance process of all these structures to be disassembled this summer. Hundred of thousands of radiological measures will confirm with guarantee that the destination of the dismantled materials is the correct one, assuring the protection of people and the environment. This is a process which has to integrate the principles of radiological safety and industrial safety. First, it has to be guaranteed that structures and components are below the values authorised by authorities for their free release, and, secondly, that the planned sequence of the process and manoeuvres in the disassembly of these colossal structures assures safety. (author)

  14. Environmental Audit. A vital part of decommissioning nuclear plants

    International Nuclear Information System (INIS)

    Perry, T.E.; Dutton, L.M.

    1998-01-01

    NNC has undertaken an environmental audit of the Hunterston A nuclear power station in Scotland. The station has closed and is now in the process of being decommissioned. The purpose of the environmental audit was to ensure that the environmental risks and potential liabilities, particularly those related to non-radioactive issues, were adequately identified and managed. The background, methodology and principal findings of the audit are described. (author)

  15. A radical approach to decommissioning and nuclear liabilities management

    International Nuclear Information System (INIS)

    Pooley, D.

    1995-01-01

    UKAEA Government Division has been set up primarily to manage and eventually eliminate the nuclear liabilities left from the many national nuclear programmes in which UKAEA has been involved. It is no longer primarily a nuclear plant or decommissioning operator but has developed a radical approach to decommissioning. It targets best value for money, alongside meeting safety and environmental requirements, by major use of contractors for its work, including as managing agents for big projects. In its first year of operation it made considerable progress in setting out the mission, goals, performance measures and operational principles for such an organisation, as well as reducing costs on a wide front from those expected in increasing competition for future projects, and in keeping individual projects under good control. It also made major physical progress with specific decommissioning projects. For the future it has established a programme of continuous performance improvement which will bring further benefits and provide a benchmark for all organisations in the business of liabilities management. (author)

  16. Factors influencing the decommissioning of large-scale nuclear plants

    International Nuclear Information System (INIS)

    Large, J.H.

    1988-01-01

    The decision-making process involving the decommissioning of the UK graphite moderated, gas-cooled nuclear power stations is complex. There are timing, engineering, waste disposal, cost and lost generation capacity factors to consider and the overall decision of when and how to proceed with decommissioning may include political and public tolerance dimensions. For the final stage of decommissioning the nuclear industry could either completely dismantle the reactor island leaving a green-field site or, alternatively, the reactor island could be maintained indefinitely with additional super- and substructure containment. At this time the first of these options, or deferred decommissioning, prevails and with this the nuclear industry has expressed considerable confidence that the technology required will become available with passing time, that acceptable radioactive waste disposal methods and facilities will be available and that the eventual costs of decommissioning will not escalate without restraint. If the deferred decommissioning strategy is wrong and it is not possible to completely dismantle the reactor islands a century into the future, then it may be too late to effect sufficient longer term containment to maintain the reactor hulks in a reliable condition. With respect to the final decommissioning of large-scale nuclear plant, it is concluded that the nuclear industry does not know quite how to do it, when it will be attempted and when it will be completed, and they do not know how much it will eventually cost. (author)

  17. Preliminary decommissioning plan of the reactor IPEN-MB01

    International Nuclear Information System (INIS)

    Vivas, Ary de Souza

    2014-01-01

    Around the world, many nuclear plants were built and need to be turned off at a certain time because they are close to their recommended time of use is approximately 50 years. So the IAEA (International Atomic Energy Agency), seeks to guide and recommend a set of guidelines for the conduct of activities of nuclear facilities, with special attention to countries that do not have a framework regulatory Legal that sustain the activities of decommissioning. Brazil, so far, does not have a specific standard to guide the steps of the guidelines regarding decommissioning research reactors. However, in March 2011 a study committee was formed with the main task facing the issues of decommissioning of nuclear installations in Brazil, culminating in Resolution 133 of November 8, 2012, a standard project that treat about the Decommissioning of nucleoelectric plants. O Instituto de Pesquisas Energeticas e Nucleares (IPEN) has two research reactors one being the reactor IPEN/MB-01. The purpose of this master dissertation is to develop a preliminary plan for decommissioning this research reactor, considering the technical documentation of the facility (RAS-Safety Analysis Report), the existing standards of CNEN (National Nuclear Energy Commission), as well as IAEA recommendations. In terms of procedures for decommissioning research reactors, this work was based on what is most modern in experiences, strategies and lessons learned performed and documented in IAEA publications covering techniques and technologies for decommissioning. Considering these technical knowledge and due to the peculiarities of the facility, was selected to immediate dismantling strategy, which corresponds to the start of decommissioning activities once the installation is switched off, dividing it into work sectors. As a resource for monitoring and project management of reactor decommissioning and maintenance of records, we developed a database using Microsoft Access 2007, which contain all the items and

  18. Prediction of Decommissioning Cost for Kijang Research Reactor Using Power Data of DACCORD

    Energy Technology Data Exchange (ETDEWEB)

    Hong, Yun Jeong; Jin, Hyung Gon; Park, Hee Seong; Park, Seung Kook [KAERI, Daejeon (Korea, Republic of)

    2016-05-15

    There are 3 types of cost estimate that can be used, and each have a different level of accuracy: (i) Order of magnitude estimate: One without detailed engineering data, where an estimate is prepared using scale-up or -down factors and approximate ratios. It is likely that the overall scope of the project has not been well defined. The level of accuracy expected is -30% to +50%. The cost plans to predict referring to abroad examples as decommissioning cost estimation has still not developed and been commercial method for Kijang research reactor. In Kijang research reactor case, overall scope of business isn't yet decided. Then it is supposed to estimate cost with type (i). The IAEA project, entitled 'DACCORD' (Data Analysis and Collection for Costing of Research Reactor Decommissioning) performs decommissioning costing after collecting and analyzing the information related to research reactors around the world for several years. Also decommissioning costing method development tends to increase in the each country. This paper aims to estimate preliminary decommissioning cost based on total decommissioning cost per thermal power rate of research reactor presented in DACCORD project' data which is collected by member state. In this paper, preliminary decommissioning cost is estimated based on total decommissioning cost per thermal power rate of research reactor presented in DACCORD data which is collected by member state. Although there exists a general tendency for costs to increase with increasing thermal power, the limited data available show that decommissioning costs at any given power level can vary widely, with increased variability at higher power levels. Variations in decommissioning cost for the research reactors of the same or similar thermal power are caused by differences in reactor types and design, decommissioning project scopes, country- specific unit workforce costs, and other reactor or project factors. An important factor for the

  19. Live from Space Station Learning Technologies Project

    Science.gov (United States)

    2001-01-01

    This is the Final Report for the Live From Space Station (LFSS) project under the Learning Technologies Project FY 2001 of the MSFC Education Programs Department. AZ Technology, Inc. (AZTek) has developed and implemented science education software tools to support tasks under the LTP program. Initial audience consisted of 26 TreK in the Classroom schools and thousands of museum visitors to the International Space Station: The Earth Tour exhibit sponsored by Discovery Place museum.

  20. Decommissioning a nuclear power plant: the tax effects

    International Nuclear Information System (INIS)

    Foyt, W.W.

    1982-01-01

    The tax treatment of decommissioning costs is as important a consideration as construction costs. The principles also apply to offshore operations and pipeline systems having a negative salvage value. Estimates place the cost at somewhere between 15 and 100% of construction costs, depending on how the decommissioning is done. It is essential to find an accurate way to project decommissioning costs and to decide how they should be reported for tax purposes. The Internal Revenue Service (IRS) does not plan to apply Section 167, which deals with negative net salvage. Utility customers will ultimately provide the funds, but current IRS rulings count these funds as ordinary income and do not allow matching the additional revenue with decommissioning expenses

  1. Radioactive Waste Management and Nuclear Facility Decommissioning Progress in Iraq - 13216

    Energy Technology Data Exchange (ETDEWEB)

    Al-Musawi, Fouad; Shamsaldin, Emad S.; Jasim, Hadi [Ministry of Science and Technology (MoST), Al-Jadraya, P.O. Box 0765, Baghdad (Iraq); Cochran, John R. [Sandia National Laboratories1, New Mexico, Albuquerque New Mexico 87185 (United States)

    2013-07-01

    Iraqi Decommissioning Directorate (IDD) is responsible for decommissioning activities. The IDD and the RWTMD work together on decommissioning projects. The IDD has developed plans and has completed decommissioning of the GeoPilot Facility in Baghdad and the Active Metallurgical Testing Laboratory (LAMA) in Al-Tuwaitha. Given this experience, the IDD has initiated work on more dangerous facilities. Plans are being developed to characterize, decontaminate and decommission the Tamuz II Research Reactor. The Tammuz Reactor was destroyed by an Israeli air-strike in 1981 and the Tammuz II Reactor was destroyed during the First Gulf War in 1991. In addition to being responsible for managing the decommissioning wastes, the RWTMD is responsible for more than 950 disused sealed radioactive sources, contaminated debris from the first Gulf War and (approximately 900 tons) of naturally-occurring radioactive materials wastes from oil production in Iraq. The RWTMD has trained staff, rehabilitated the Building 39 Radioactive Waste Storage building, rehabilitated portions of the French-built Radioactive Waste Treatment Station, organized and secured thousands of drums of radioactive waste organized and secured the stores of disused sealed radioactive sources. Currently, the IDD and the RWTMD are finalizing plans for the decommissioning of the Tammuz II Research Reactor. (authors)

  2. Radioactive Waste Management and Nuclear Facility Decommissioning Progress in Iraq - 13216

    International Nuclear Information System (INIS)

    Al-Musawi, Fouad; Shamsaldin, Emad S.; Jasim, Hadi; Cochran, John R.

    2013-01-01

    Directorate (IDD) is responsible for decommissioning activities. The IDD and the RWTMD work together on decommissioning projects. The IDD has developed plans and has completed decommissioning of the GeoPilot Facility in Baghdad and the Active Metallurgical Testing Laboratory (LAMA) in Al-Tuwaitha. Given this experience, the IDD has initiated work on more dangerous facilities. Plans are being developed to characterize, decontaminate and decommission the Tamuz II Research Reactor. The Tammuz Reactor was destroyed by an Israeli air-strike in 1981 and the Tammuz II Reactor was destroyed during the First Gulf War in 1991. In addition to being responsible for managing the decommissioning wastes, the RWTMD is responsible for more than 950 disused sealed radioactive sources, contaminated debris from the first Gulf War and (approximately 900 tons) of naturally-occurring radioactive materials wastes from oil production in Iraq. The RWTMD has trained staff, rehabilitated the Building 39 Radioactive Waste Storage building, rehabilitated portions of the French-built Radioactive Waste Treatment Station, organized and secured thousands of drums of radioactive waste organized and secured the stores of disused sealed radioactive sources. Currently, the IDD and the RWTMD are finalizing plans for the decommissioning of the Tammuz II Research Reactor. (authors)

  3. Milliken Station Demonstration Project FDG retrofit update

    Energy Technology Data Exchange (ETDEWEB)

    Alder, R.C.; Jackson, C.E.; O`Dea, D.T. [and others

    1994-12-31

    The Milliken Clean Coal Demonstration Project is one of the nine Clean Coal Projects selected for funding in Round 4 of the U.S. DOE`s Clean Coal Demonstration Program. The project`s sponsor is New York State Electric and Gas Corporation (NYSEG). Project team members include CONSOL Inc., Saarberg-Holter-Umwelttechnik (SHU), NALCO/FuelTech, Stebbins Engineering and Manufacturing Co., DHR Technologies, and CE Air Preheater. Gilbert/Commonwealth is the Architect/Engineer and Construction Manager for the flue gas desulfurization (FGD) retrofit. The project will provide full-scale demonstration of a combination of innovative emission-reducing technologies and plant upgraded for the control of sulfur dioxide (SO{sub 2}) and nitrogen oxides (NO{sub x}) emissions from a coal-fired steam generator without a significant loss of station efficiency. The overall project goals are the following: 98% SO{sub 2} removal efficiency using limestone while burning high sulfur coal; up to 70% NO{sub x} reduction using the NOXOUT selective non-catalytic reduction (SNCR) technology in conjunction with combustion modifications; minimization of solid waste by producing marketable by-products including commercial grade gypsum, calcium chloride, and fly ash; zero wastewater discharge; maintenance of station efficiency by using a high efficiency heat-pipe air heater system and a low-power-consuming scrubber system. The demonstration project is being conducted at NYSEG`s Milliken Station, located in Lansing, New York. Milliken Station has two 150-MWe pulverized coal-fired units built in the 1950s by Combustion Engineering. The SHU FGD process and the combustion modifications are being installed on both units, but the NOXOUT process, Plant Economic Optimization Advisor (PEOA), and the high-efficiency air heater system will be installed on only one unit.

  4. The Preliminary Decommissioning Plan of the Dalat Nuclear Research Reactor

    Energy Technology Data Exchange (ETDEWEB)

    Lam, Pham Van; Vien, Luong Ba; Vinh, Le Vinh; Nghiem, Huynh Ton; Tuan, Nguyen Minh; Phuong, Pham Hoai [Nuclear Research Institute, Da Lat (Viet Nam)

    2013-08-15

    Recently, after 25 years of operation, a preliminary decommissioning plan for the Dalat Nuclear Research Reactor (DNRR) has been produced but as yet it has not been implemented due to the continued operations of the reactor. However, from the early phases of facility design and construction and during operation, the aspects that facilitate decommissioning process have been considered. This paper outlines the DNRR general description, the organization that manages the facility, the decommissioning strategy and associated project management, and the expected decommissioning activities. The paper also considers associated cost and funding, safety and environmental issues and waste management aspects amongst other considerations associated with decommissioning a nuclear research reactor. (author)

  5. Germany: Management of decommissioning waste in Germany

    International Nuclear Information System (INIS)

    Borrmann, F.; Brennecke, P.; Koch, W.; Kugel, K.; Steyer, S.

    2007-01-01

    Over the past two decades, Germany has gained a substantial amount of experience in the decommissioning of nuclear facilities of different types and sizes. Many research reactors and all prototype nuclear power plants, as well as a few larger nuclear power plants and fuel cycle facilities, are currently at varying stages of decommissioning. Several facilities have been fully dismantled and the sites have been cleared for reuse. The decommissioning projects comprise 18 power and prototype reactors, 33 research reactors and 11 fuel cycle facilities which are being or have been decommissioned. In the future, further nuclear power plants will be shut down and decommissioned in accordance with Germany?s energy policy to phase out the use of nuclear power for commercial electricity generation as given in the April 2002 amendment of the Atomic Energy Act. Radioactive waste, from operations as well as from decommissioning activities, is to be conditioned in such a way as to comply with the waste acceptance requirements of a repository. In Germany, all types of radioactive waste (i.e., short-lived and long-lived) are to be disposed of in deep geological formations. A distinction is being made for heat generating waste (i.e., high level waste) and waste with negligible heat generation (i.e., low level and intermediate level waste). Radioactive decommissioning waste is waste with negligible heat generation. Waste acceptance requirements of a repository are of particular importance for the conditioning of radioactive waste, including decommissioning waste. The waste acceptance requirements, as they resulted from the Konrad licensing procedure, are being applied by the waste generators for the conditioning of decommissioning waste. Compliance with these requirements must be demonstrated through the waste package quality control, even if the waste will be disposed of in the future. In 2002 the Konrad repository was licensed for the disposal of all types of waste with negligible

  6. Financial aspects of decommissioning

    International Nuclear Information System (INIS)

    Chirica, T.; Havris, A.

    2003-01-01

    European Commission adopted recently two proposals of Directives designed to pave the way for a Community approach to the safety of nuclear power plants and the processing of radioactive waste. Nuclear safety cannot be guaranteed without making available adequate financial resources. With regard, in particular, to the decommissioning of nuclear facilities, the Directive defines the Community rules for the establishment, management and use of decommissioning funds allocated to a body with legal personality separate from that of the nuclear operator. In order to comply with the acquis communautaire, Romanian Government issued the Emergency Ordinance no. 11/2003 which set up the National Agency for Radioactive Waste (ANDRAD) and soon will be established the financial mechanism for raising the necessary funds. Societatea Nationala 'Nuclearelectrica' S.A. operates, through one of its branches, Cernavoda NPP Unit 1 and has to prepare its decommissioning strategy and to analyze the options to assure the financing for covering the future costs. The purpose of this paper is to clarify the financial systems' mechanisms to the satisfaction of the nuclear operator obligations, according to the disbursement schedule foreseen by decommissioning projects . The availability of cash to pay for all the decommissioning expenditure must be foreseen by setting up assets and establishing a suitable financing plan. The different practices of assets management shall be presented in this paper on the basis of the international experience. Some calculation samples shall be given as an illustration. (author)

  7. Decommissioning of the Shippingport Atomic Power Station

    International Nuclear Information System (INIS)

    LaGuardia, T.S.

    1988-01-01

    The Shippingport reactor was originally designed as a pressurized water reactor and operated for approximately 10 years in that mode. Later, in 1967 it was converted to a light water breeder reactor and continued its operation until 1985, when the reactor was shut down. However, the decommissioning planning for Shippingport was begun in 1979. Detailed engineering and planning was undertaken to look at alternatives for disposal of the reactor vessel, the overall detailed estimated costs, the exposure to the workers and the waste volume generated and to prepare activity specifications for performance of the work. The program scope and component removal are detailed. The scarification of contaminated concrete, building demolition, special tools and equipment needed and work performance data are described. The successful removal of the primary system components and piping has been completed. (author)

  8. Lessons learned from the decommissioning of NORM facility in Malaysia

    International Nuclear Information System (INIS)

    Kontol, Khairuddin M.; Omar, Muhamat; Ahmad, Syed H.S.S.

    2008-01-01

    Full text: Malaysia Decommissioning of Naturally Occurring Radioactive Materials (NORM) facility in Malaysia will run into unforeseeable complications and difficulties if there is no proper planning. The Atomic Energy Licensing Board (AELB) plays important role in guiding and assisting the operator/contractor in this NORM decommissioning project. A local Naturally Occurring Radioactive Materials (NORM) processing plant located in the northern region of peninsular Malaysia had ceased its operations and decided to decommission and remediate its site for the final release of the site. The remediated site is earmarked as an industrial site. During its operations, monazites are processed for rare earth elements such as cerium and lanthanum. It's plant capable of processing monazite to produce rare earth chloride and rare earth carbonate. The main by-product of monazite processing is the radioactive cake containing primarily thorium hydroxide. Operation of the monazite processing plant started in early eighties and terminated in early nineties. The decommissioning of the plant site started in late 2003 and completed its decommissioning and remediation works in early 2006. This paper described the lesson learned by Malaysian Nuclear Agency (Nuclear Malaysia) in conducting third party independent audit for the decommissioning of the NORM contaminated facility. By continuously reviewing the lessons learned, mistakes and/or inefficiencies in this plant decommissioning project, hopefully will result in a smoother, less costly and more productive future decommissioning works on NORM facilities in Malaysia. (author)

  9. Safety Oversight of Decommissioning Activities at DOE Nuclear Sites

    International Nuclear Information System (INIS)

    Zull, Lawrence M.; Yeniscavich, William

    2008-01-01

    The Defense Nuclear Facilities Safety Board (Board) is an independent federal agency established by Congress in 1988 to provide nuclear safety oversight of activities at U.S. Department of Energy (DOE) defense nuclear facilities. The activities under the Board's jurisdiction include the design, construction, startup, operation, and decommissioning of defense nuclear facilities at DOE sites. This paper reviews the Board's safety oversight of decommissioning activities at DOE sites, identifies the safety problems observed, and discusses Board initiatives to improve the safety of decommissioning activities at DOE sites. The decommissioning of former defense nuclear facilities has reduced the risk of radioactive material contamination and exposure to the public and site workers. In general, efforts to perform decommissioning work at DOE defense nuclear sites have been successful, and contractors performing decommissioning work have a good safety record. Decommissioning activities have recently been completed at sites identified for closure, including the Rocky Flats Environmental Technology Site, the Fernald Closure Project, and the Miamisburg Closure Project (the Mound site). The Rocky Flats and Fernald sites, which produced plutonium parts and uranium materials for defense needs (respectively), have been turned into wildlife refuges. The Mound site, which performed R and D activities on nuclear materials, has been converted into an industrial and technology park called the Mound Advanced Technology Center. The DOE Office of Legacy Management is responsible for the long term stewardship of these former EM sites. The Board has reviewed many decommissioning activities, and noted that there are valuable lessons learned that can benefit both DOE and the contractor. As part of its ongoing safety oversight responsibilities, the Board and its staff will continue to review the safety of DOE and contractor decommissioning activities at DOE defense nuclear sites

  10. Radiochemistry Lab Decommissioning and Dismantlement. AECL, Chalk River Labs, Ontario, Canada

    International Nuclear Information System (INIS)

    Kenny, Stephen

    2008-01-01

    Atomic Energy of Canada (AECL) was originally founded in the mid 1940's to perform research in radiation and nuclear areas under the Canadian Defense Department. In the mid 50's The Canadian government embarked on several research and development programs for the development of the Candu Reactor. AECL was initially built as a temporary site and is now faced with many redundant buildings. Prior to 2004 small amounts of Decommissioning work was in progress. Many reasons for deferring decommissioning activities were used with the predominant ones being: 1. Reduction in radiation doses to workers during the final dismantlement, 2. Development of a long-term solution for the management of radioactive wastes in Canada, 3. Financial constraints presented by the number of facilities shutdown that would require decommissioning funds and the absence of an approved funding strategy. This has led to the development of a comprehensive decommissioning plan that is all inclusive of AECL's current and legacy liabilities. Canada does not have a long-term disposal site; therefore waste minimization becomes the driving factor behind decontamination for decommissioning before and during dismantlement. This decommissioning job was a great learning experience for decommissioning and the associated contractors who worked on this project. Throughout the life of the project there was a constant focus on waste minimization. This focus was constantly in conflict with regulatory compliance primarily with respect to fire regulations and protecting the facility along with adjacent facilities during the decommissioning activities. Discrepancies in historical documents forced the project to treat every space as a contaminated space until proven differently. Decommissioning and dismantlement within an operating site adds to the complexity of the tasks especially when it is being conducted in the heart of the plant. This project was very successful with no lost time accidents in over one hundred

  11. The Community's research and development programme on decommissioning of nuclear power plants

    International Nuclear Information System (INIS)

    1982-01-01

    The programme, adopted by the Council of the European Communities, seeks to promote a number of research and development projects as well as the identification of guiding principles. The projects concern the following subjects: long-term integrity of buildings and systems; decontaminations for decommissioning purposes; dismantling techniques; treatment of specific waste materials (steel, concrete and graphite); large transport containers for radioactive waste arising from decommissioning of nuclear power plants in the Community; and influence of nuclear power plant design features on decommissioning

  12. Workshop on decommissioning

    International Nuclear Information System (INIS)

    Broden, K.

    2005-12-01

    A Nordic workshop on decommissioning of nuclear facilities was held at Risoe in Denmark September 13-15, 2005. The workshop was arranged by NKS in cooperation with the company Danish Decommissioning, DD, responsible for decommissioning of nuclear facilities at Risoe. Oral presentations were made within the following areas: International and national recommendations and requirements concerning decommissioning of nuclear facilities Authority experiences of decommissioning cases Decommissioning of nuclear facilities in Denmark Decommissioning of nuclear facilities in Sweden Plans for decommissioning of nuclear facilities in Norway Plans for decommissioning of nuclear facilities in Finland Decommissioning of nuclear facilities in German and the UK Decommissioning of nuclear facilities in the former Soviet Union Results from research and development A list with proposals for future work within NKS has been prepared based on results from group-work and discussions. The list contains strategic, economical and political issues, technical issues and issues regarding competence and communication. (au)

  13. Status of the support researches for the regulation of nuclear facilities decommissioning in Japan

    International Nuclear Information System (INIS)

    Masuda, Yusuke; Iguchi, Yukihiro; Kawasaki, Satoru; Kato, Masami

    2011-01-01

    In Japan, 4 nuclear power stations are under decommissioning and some nuclear fuel cycle facilities are expected to be decommissioned in the future. On the other hand, the safety regulation of decommissioning of nuclear facilities was changed by amending act in 2005. An approval system after review process of decommissioning plan was adopted and applied to the power stations above. In this situation, based on the experiences of the new regulatory system, the system should be well established and moreover, it should be improved and enhanced in the future. Nuclear Industry and Safety Agency (NISA) is in charge of regulation of commercial nuclear facilities in Japan and decommissioning of them is included. Japan Nuclear Energy Safety Organization (JNES) is in charge of technical supports for NISA as a TSO (Technical Support Organization) also in this field. As for decommissioning, based on regulatory needs, JNES has been continuing research activities from October 2003, when JNES has been established. Considering the 'Prioritized Nuclear Safety Research Plan (August 2009)' of the Nuclear Safety Commission of Japan and the situation of operators facilities, 'Regulatory Support Research Plan between FY 2010-2014' was established in November 2009, which shows the present regulatory needs and a research program. This program consists of researches for 1. review process of decommissioning plan of power reactors, 2. review process of decommissioning plan of nuclear fuel cycle facilities, 3. termination of license at the end of decommissioning and 4. management of decommissioning waste. For the item 1, JNES studied safety assessment methods of dismantling, e.g. obtaining data and analysis of behavior of dust diffusion and risk assessment during decommissioning, which are useful findings for the review process. For the item 2, safety requirements for the decommissioning of nuclear fuel cycle facilities was compiled, which will be used in the future review. For the item 3

  14. Decommissioning of nuclear facilities

    International Nuclear Information System (INIS)

    Lunning, W.H.

    1977-01-01

    Collaborative studies are in progress in the U.K. between the U.K.A.E.A., the Generating Boards and other outside bodies, to identify the development issues and practical aspects of decommissioning redundant nuclear facilities. The various types of U.K.A.E.A. experimental reactors (D.F.R., W.A.G.R , S.G.H.W.R.) in support of the nuclear power development programme, together with the currently operating commercial 26 Magnox reactors in 11 stations, totalling some 5 GW will be retired before the end of the century and attention is focussed on these. The actual timing of withdrawal from service will be dictated by development programme requirements in the case of experimental reactors and by commercial and technical considerations in the case of electricity production reactors. Decommissioning studies have so far been confined to technical appraisals including the sequence logic of achieving specific objectives and are based on the generally accepted three stage progression. Stage 1, which is essentially a defuelling and coolant removal operation, is an interim phase. Stage 2 is a storage situation, the duration of which will be influenced by environmental pressures or economic factors including the re-use of existing sites. Stage 3, which implies removal of all active and non-active waste material and returning the site to general use, must be the ultimate objective. The engineering features and the radioactive inventory of the system must be assessed in detail to avoid personnel or environmental hazards during Stage 2. These factors will also influence decisions on the degree of Stage 2 decommissioning and its duration, bearing in mind that for Stage 3 activation may govern the waste disposal route and the associated radiation man-rem exposure during dismantling. Ideally, planning for decommissioning should be considered at the design stage of the facility. An objective of present studies is to identify features which would assist decommissioning of future systems

  15. The Community's research and development programme on decommissioning of nuclear installations: First annual progress report (year 1985)

    International Nuclear Information System (INIS)

    1986-01-01

    This is the first Annual Progress Report of the European Community's 1984-88 programme of research on the decommissioning of nuclear installations. It shows the status of implementation reached on 31 December 1985. The 1984-88 programme has the following contents: A. Research and development projects concerning the following subjects: Project No 1: Long-term integrity of building and systems; Project No 2: Decontamination for decommissioning purposes; Project No 3: Dismantling techniques; Project No 4: Treatment of specific waste materials: steel, concrete and graphite; Project No 5: Large containers for radioactive waste produced in the dismantling of nuclear installations; Project No 6: Estimation of the quantities of radioactive wastes arising from the decommissioning of nuclear installations in the Community; Project No 7: Influence of installation design features on decommissioning. B. Identification of guiding principles, namely: - certain guiding principles in the design and operation of nuclear installations with a view to simplifying their subsequent decommissioning, - guiding principles in the decommissioning of nuclear installations which could form the initial elements of a Community policy in this field. C. Testing of new techniques under real conditions, within the framework of large-scale decommissioning operations undertaken in Member States. This first progress report, covering the period of putting the programme into action, describes the work to be carried out under the 27 research contracts concluded, as well as initial work performed and first results obtained

  16. Experimental Boiling Water Reactor decontamination and decommissioning project

    International Nuclear Information System (INIS)

    Fellhauer, C.

    1995-01-01

    The author begins by discussing the problems encountered during decontamination and decommissioning. Next, he discusses waste packaging and recycling. His last topic of lessons learned is subdivided into prevention and early detection, recovery issues, management issues, and noteworthy practices

  17. Proceedings of the Workshop on Current and Emerging methods for Optimising Safety and Efficiency in Nuclear Decommissioning

    International Nuclear Information System (INIS)

    2017-02-01

    The workshop was organised by the Institute for Energy Technology (IFE) on behalf of the OECD Halden Reactor Project (OECD-HRP) and in collaboration with the International Atomic Energy Agency (IAEA) and the Nuclear Energy Agency (NEA). The workshop brought together more than 100 people (operators, regulators, scientists, consultants, and contractors) from 25 countries. Program: Day 1 - Successful application of R and D in decommissioning and future needs (Welcome and Opening Speeches; Session 1: Workshop Introductory Presentations; Session 2: Experience from starting, on-going and completed decommissioning projects). Day 2 - R and D and application of advanced technologies for decommissioning (Session 3: New technologies for decommissioning; Session 4: Advanced information technologies for decommissioning). Day 3 - Improving decommissioning management on project, national and international level (Session 5: Challenges and methods for improving decommissioning; Session 6: Workshop closing)

  18. Radiochemical analysis for nuclear waste management in decommissioning

    International Nuclear Information System (INIS)

    Hou, X.

    2010-07-01

    The NKS-B RadWaste project was launched from June 2009. The on-going decommissioning activities in Nordic countries and current requirements and problems on the radiochemical analysis of decommissioning waste were discussed and overviewed. The radiochemical analytical methods used for determination of various radionuclides in nuclear waste are reviewed, a book was written by the project partners Jukka Lehto and Xiaolin Hou on the chemistry and analysis of radionuclide to be published in 2010. A summary of the methods developed in Nordic laboratories is described in this report. The progresses on the development and optimization of analytical method in the Nordic labs under this project are presented. (author)

  19. Radiochemical analysis for nuclear waste management in decommissioning

    Energy Technology Data Exchange (ETDEWEB)

    Hou, X. (Technical Univ. of Denmark, Risoe National Lab. for Sustainable Energy. Radiation Research Div., Roskilde (Denmark))

    2010-07-15

    The NKS-B RadWaste project was launched from June 2009. The on-going decommissioning activities in Nordic countries and current requirements and problems on the radiochemical analysis of decommissioning waste were discussed and overviewed. The radiochemical analytical methods used for determination of various radionuclides in nuclear waste are reviewed, a book was written by the project partners Jukka Lehto and Xiaolin Hou on the chemistry and analysis of radionuclide to be published in 2010. A summary of the methods developed in Nordic laboratories is described in this report. The progresses on the development and optimization of analytical method in the Nordic labs under this project are presented. (author)

  20. Comparative analysis of the Oskarshamn 3 and Barsebaeck site decommissioning studies

    International Nuclear Information System (INIS)

    Hansson, Bertil; Joensson, Lars-Olof

    2009-01-01

    Several projects concerning the decommissioning of different types of nuclear facilities have shown that technical methods and equipment are available today for safe dismantling of nuclear facilities of any type or size. However, comparison of individual cost estimates for specific facilities exhibit relatively large variations, and several studies have tried to identify the reasons for these variations. Analysis has shown that decommissioning cost estimates vary depending on a number of factors, including: the boundary conditions and strategy chosen; the cost items taken into account; the origin of the cost estimate; the methodology applied; the political-administrative framework; and the way contingencies are included. In this study, a comparison has been made between two decommissioning studies in the same country, with more or less same decommissioning schedule and with similar overall ideas on cost estimates. However, the two studies had from the start a different focus and different objectives. One study is intended as a reference study for all BWRs in Sweden, while the other focuses on a full site decommissioning. Furthermore, one of the studies is based on direct dismantling and the other on deferred dismantling. A great deal of work therefore had to be devoted in the present study to giving the studies comparable structures and boundary conditions using the OECD/NEA cost estimate structure. The boundary conditions in each of the studies have been thoroughly evaluated qualitatively and quantitatively, and the differences have been explained. In the end, values have been set in the quantitative analysis to verify that the studies could be compared, within the accuracy of what is defined in the industry as a 'budgetary estimate'. Differences still exist relating to what has been included in the studies and to the decommissioning plans and the resulting inventory from site characterization. Such differences must be accepted as long as it is clear what is

  1. Comparative analysis of the Oskarshamn 3 and Barsebaeck site decommissioning studies

    Energy Technology Data Exchange (ETDEWEB)

    Hansson, Bertil (Bewon, Loeddekoepinge (Sweden)); Joensson, Lars-Olof (Barsebaeck Kraft AB, Loeddekoepinge (Sweden))

    2009-01-15

    Several projects concerning the decommissioning of different types of nuclear facilities have shown that technical methods and equipment are available today for safe dismantling of nuclear facilities of any type or size. However, comparison of individual cost estimates for specific facilities exhibit relatively large variations, and several studies have tried to identify the reasons for these variations. Analysis has shown that decommissioning cost estimates vary depending on a number of factors, including: the boundary conditions and strategy chosen; the cost items taken into account; the origin of the cost estimate; the methodology applied; the political-administrative framework; and the way contingencies are included. In this study, a comparison has been made between two decommissioning studies in the same country, with more or less same decommissioning schedule and with similar overall ideas on cost estimates. However, the two studies had from the start a different focus and different objectives. One study is intended as a reference study for all BWRs in Sweden, while the other focuses on a full site decommissioning. Furthermore, one of the studies is based on direct dismantling and the other on deferred dismantling. A great deal of work therefore had to be devoted in the present study to giving the studies comparable structures and boundary conditions using the OECD/NEA cost estimate structure. The boundary conditions in each of the studies have been thoroughly evaluated qualitatively and quantitatively, and the differences have been explained. In the end, values have been set in the quantitative analysis to verify that the studies could be compared, within the accuracy of what is defined in the industry as a 'budgetary estimate'. Differences still exist relating to what has been included in the studies and to the decommissioning plans and the resulting inventory from site characterization. Such differences must be accepted as long as it is clear

  2. Decommissioning of nuclear facilities. Feasibility, needs and costs

    International Nuclear Information System (INIS)

    1986-01-01

    Reactor decommissioning activities generally are considered to begin after operations have ceased and the fuel has been removed from the reactor, although in some countries the activities may be started while the fuel is still at the reactor site. The three principal alternatives for decommissioning are described. The factors to be considered in selecting the decommissioning strategy, i.e. a stage or a combination of stages that comprise the total decommissioning programme, are reviewed. One presents a discussion of the feasibility of decommissioning techniques available for use on the larger reactors and fuel cycle facilities. The numbers and types of facilities to be decommissioned and the resultant waste volumes generated for disposal will then be projected. Finally, the costs of decommissioning these facilities, the effect of these costs on electricity generating costs, and alternative methods of financing decommissioning are discussed. The discussion of decommissioning draws on various countries' studies and experience in this area. Specific details about current activities and policies in NEA Member Countries are given in the short country specific Annexes. The nuclear facilities that are addressed in this study include reactors, fuel fabrication facilities, reprocessing facilities, associated radioactive waste storage facilities, enrichment facilities and other directly related fuel cycle support facilities. The present study focuses on the technical feasibility, needs, and costs of decommissioning the larger commercial facilities in the OECD member countries that are coming into service up to the year 2000. It is intended to inform the public and to assist in planning for the decommissioning of these facilities

  3. Calculating Program for Decommissioning Work Productivity based on Decommissioning Activity Experience Data

    Energy Technology Data Exchange (ETDEWEB)

    Song, Chan-Ho; Park, Seung-Kook; Park, Hee-Seong; Moon, Jei-kwon [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2014-10-15

    KAERI is performing research to calculate a coefficient for decommissioning work unit productivity to calculate the estimated time decommissioning work and estimated cost based on decommissioning activity experience data for KRR-2. KAERI used to calculate the decommissioning cost and manage decommissioning activity experience data through systems such as the decommissioning information management system (DECOMMIS), Decommissioning Facility Characterization DB System (DEFACS), decommissioning work-unit productivity calculation system (DEWOCS). In particular, KAERI used to based data for calculating the decommissioning cost with the form of a code work breakdown structure (WBS) based on decommissioning activity experience data for KRR-2.. Defined WBS code used to each system for calculate decommissioning cost. In this paper, we developed a program that can calculate the decommissioning cost using the decommissioning experience of KRR-2, UCP, and other countries through the mapping of a similar target facility between NPP and KRR-2. This paper is organized as follows. Chapter 2 discusses the decommissioning work productivity calculation method, and the mapping method of the decommissioning target facility will be described in the calculating program for decommissioning work productivity. At KAERI, research on various decommissioning methodologies of domestic NPPs will be conducted in the near future. In particular, It is difficult to determine the cost of decommissioning because such as NPP facility have the number of variables, such as the material of the target facility decommissioning, size, radiographic conditions exist.

  4. Calculating Program for Decommissioning Work Productivity based on Decommissioning Activity Experience Data

    International Nuclear Information System (INIS)

    Song, Chan-Ho; Park, Seung-Kook; Park, Hee-Seong; Moon, Jei-kwon

    2014-01-01

    KAERI is performing research to calculate a coefficient for decommissioning work unit productivity to calculate the estimated time decommissioning work and estimated cost based on decommissioning activity experience data for KRR-2. KAERI used to calculate the decommissioning cost and manage decommissioning activity experience data through systems such as the decommissioning information management system (DECOMMIS), Decommissioning Facility Characterization DB System (DEFACS), decommissioning work-unit productivity calculation system (DEWOCS). In particular, KAERI used to based data for calculating the decommissioning cost with the form of a code work breakdown structure (WBS) based on decommissioning activity experience data for KRR-2.. Defined WBS code used to each system for calculate decommissioning cost. In this paper, we developed a program that can calculate the decommissioning cost using the decommissioning experience of KRR-2, UCP, and other countries through the mapping of a similar target facility between NPP and KRR-2. This paper is organized as follows. Chapter 2 discusses the decommissioning work productivity calculation method, and the mapping method of the decommissioning target facility will be described in the calculating program for decommissioning work productivity. At KAERI, research on various decommissioning methodologies of domestic NPPs will be conducted in the near future. In particular, It is difficult to determine the cost of decommissioning because such as NPP facility have the number of variables, such as the material of the target facility decommissioning, size, radiographic conditions exist

  5. Engineering and planning for decommissioning of nuclear power plants

    International Nuclear Information System (INIS)

    Gans, G.M. Jr.

    1982-01-01

    With the publication of NUREG-0586, ''Draft Generic Environmental Impact Statement on Decommissioning of Nuclear Facilities'' in January, 1981 the Nuclear Regulatory Commission staff has put the industry on notice that the termination of operating licenses and the final disposal of physical facilities will require the early consideration of several options and approaches and the preparation of comprehensive engineering and planning documents for the selected option at the end of useful life. This paper opens with a discussion of the options available and the principal aspects of decommissioning. The major emphasis of the composition is the nature of documents, the general approach to be followed, and special considerations to be taken into account when performing the detailed engineering and planning for decommissioning, as the end of life approaches and actual physical disposal is imminent. The author's main point of reference is on-going work by Burns and Roe, with Nuclear Energy Services, under contract to the Department of Energy's Richland Office, to perform the engineering and planning for the decommissioning of the Shippingport Atomic Power Station in Pennsylvania

  6. Methodology to collect data on decommissioning costs and occupational radiation exposure

    International Nuclear Information System (INIS)

    Petrasch, P.; Roger, J.

    1993-01-01

    Decommissioning data collection has been, up to now, almost a national matter. The present joint study performed by NIS Ingenieurgesellschaft mbH, Hanau, and the Commissariat a l'energie atomique, Unite de declassement d'installations nucleaires, and coordinated by the Commission of the European Communities, is intended to identify a methodology allowing the collection of data which are useful to manage a decommissioning project, e.g. data on dismantling costs, occupational radiation exposure and waste arisings. A common structure for decommissioning tasks (called working packages) derived from those already in use at the abovementioned organizations has been established and the corresponding first series of data-collection sheets defined in order to cover data from LWRs, GCRs (UNGGs) and nuclear fuel cycle installations. Work focused on the cost of decommissioning tasks. The study is intended to be a first step towards an EC-wide usable data-base for data generated in the various ongoing and future decommissioning projects

  7. Organization and management for decommissioning of large nuclear facilities

    International Nuclear Information System (INIS)

    2000-01-01

    organizational aspects of decommissioning and describes factors relevant to the planning and management of a decommissioning project. It identifies the general issues to be addressed and provides an overview of organizational activities necessary to manage a decommissioning project in a safe, timely and cost effective manner. There are a number of facilities that present special cases and include those which have undergone a major accident as well as uranium mines and mills and radioactive waste repositories. These facilities are not dealt with in this report. This report is structured as follows. Section 1 contains background information, objectives and scope of the document. In Section 2 considerations important for decommissioning management are discussed which could affect the organization. Section 3 deals with the management for active phases of decommissioning and provides a discussion on the organization of the decommissioning management team. Section 4 gives an overview of the decommissioning planning and approval process. Section 5 provides information on quality assurance issues relevant to decommissioning. Management of decommissioning wastes is briefly discussed in Section 6. Responsibilities and qualifications of the decommissioning management team are dealt with in Section 7. Conclusions and recommendations are given in Section 8. The report is supplemented with references, Appendix I giving details on recent experience on data management, a glossary, and national annexes, some of which indicate how the principles set out in the main report are to be utilized in different countries, and some of which are real examples of arrangements used in decommissioning projects. A list of drafting and reviewing bodies is also included

  8. Mound's decommissioning experience, tooling, and techniques

    International Nuclear Information System (INIS)

    Combs, A.B.; Davis, W.P.; Elswick, T.C.; Garner, J.M.; Geichman, J.R.

    1982-01-01

    Monsanto Research Corporation (MRC), which operates Mound for the Department of Energy (DOE), has been decommissioning radioactively contaminated facilities since 1949. We are currently decommissioning three plutonium-238 contaminated facilities (approximately 50,000 ft 2 ) that contained 1100 linear ft of gloveboxes; 900 linear ft of conveyor housing; 2650 linear ft of dual underground liquid waste lines; and associated contaminated piping, services, equipment, structures, and soil. As of June 1982, over 29,000 Ci of plutonium-238 have been removed in waste and scrap residues. As a result of the current and previous decommissioning projects, valuable experience has been gained in tooling and techniques. Special techniques have been developed in planning, exposure control, contamination control, equipment removal, structural decontamination, and waste packaging

  9. Decommissioning of the BR3 PWR

    International Nuclear Information System (INIS)

    Massaut, V.; Klein, M.

    1998-01-01

    The objectives, programme and main achievements of SCK-CEN's decommissioning programme in 1997 are summarised. Particular emphasis is on the BR3 decommissioning project. In 1997, auxiliary equipment and loops were dismantled; concrete antimissile slabs were decontaminated; the radiology of the primary loop was modelled; the quality assurance procedure for dismantling loops and equipment were implemented; a method for the dismantling of the reactor pressure vessel was selected; and contaminated thermal insulation of the primary loop containing asbestos was removed

  10. Safety analysis for the 233-S decontamination and decommissioning project

    International Nuclear Information System (INIS)

    Thoren, S.

    1996-08-01

    Decommissioning of the 233-S Plutonium Concentration Facility (REDOX) is a proposed expedited response action that is regulated by the Comprehensive Environmental Response Compensation and Liability Act of 1980 and the Hanford Federal Facility Agreement and Consent Order. Due to progressive physical deterioration of this facility, a decontamination and decommissioning plan is being considered for the immediate future. This safety analysis describes the proposed actions involved in this D ampersand D effort; identifies the radioactive material inventories involved; reviews site specific environmental characteristics and postulates an accident scenario that is evaluated to identify resultant effects

  11. Project management for the decommissioning and dismantling of nuclear facilities; Projektmanagement fuer Stilllegung und Rueckbau kerntechnischer Anlagen

    Energy Technology Data Exchange (ETDEWEB)

    Klasen, Joerg; Wilhelm, Oliver [ENBW Kernkraft GmbH, Neckarwestheim (Germany); Seizer, Burkhard; Schuetz, Tobias [Drees und Sommer, Stuttgart (Germany)

    2015-12-15

    The decommissioning of nuclear power plants is executed in a classic project manner as it is known from other construction projects. It is obvious to use the known portfolio of project management tools. The complexity that is created by the large size of the project in combination with safety requirements of the nuclear industry has to be handled. Complexity can only be managed addressing two main drivers: Prioritization and speed (agility) in project execution. Prioritization can be realized by applying tools like Earned Value Management. A high speed of project execution is established by applying Agile Management like SCRUM-methods. This method is adopted in the context of the cooperation ''Complex Projects'' to the needs of nuclear industry.

  12. Systematic Approach for Decommissioning Planning and Estimating

    International Nuclear Information System (INIS)

    Dam, A. S.

    2002-01-01

    Nuclear facility decommissioning, satisfactorily completed at the lowest cost, relies on a systematic approach to the planning, estimating, and documenting the work. High quality information is needed to properly perform the planning and estimating. A systematic approach to collecting and maintaining the needed information is recommended using a knowledgebase system for information management. A systematic approach is also recommended to develop the decommissioning plan, cost estimate and schedule. A probabilistic project cost and schedule risk analysis is included as part of the planning process. The entire effort is performed by a experienced team of decommissioning planners, cost estimators, schedulers, and facility knowledgeable owner representatives. The plant data, work plans, cost and schedule are entered into a knowledgebase. This systematic approach has been used successfully for decommissioning planning and cost estimating for a commercial nuclear power plant. Elements of this approach have been used for numerous cost estimates and estimate reviews. The plan and estimate in the knowledgebase should be a living document, updated periodically, to support decommissioning fund provisioning, with the plan ready for use when the need arises

  13. Nuclear Rocket Facility Decommissioning Project: Controlled Explosive Demolition of Neutron-Activated Shield Wall

    International Nuclear Information System (INIS)

    Michael R. Kruzic

    2007-01-01

    Located in Area 25 of the Nevada Test Site (NTS), the Test Cell A (TCA) Facility was used in the early to mid-1960s for the testing of nuclear rocket engines, as part of the Nuclear Rocket Development Program, to further space travel. Nuclear rocket testing resulted in the activation of materials around the reactors and the release of fission products and fuel particles in the immediate area. Identified as Corrective Action Unit 115, the TCA facility was decontaminated and decommissioned (D and D) from December 2004 to July 2005 using the Streamlined Approach for Environmental Restoration (SAFER) process, under the ''Federal Facility Agreement and Consent Order''. The SAFER process allows environmental remediation and facility closure activities (i.e., decommissioning) to occur simultaneously provided technical decisions are made by an experienced decision maker within the site conceptual site model, identified in the Data Quality Objective process. Facility closure involved a seven-step decommissioning strategy. Key lessons learned from the project included: (1) Targeted preliminary investigation activities provided a more solid technical approach, reduced surprises and scope creep, and made the working environment safer for the D and D worker. (2) Early identification of risks and uncertainties provided opportunities for risk management and mitigation planning to address challenges and unanticipated conditions. (3) Team reviews provided an excellent mechanism to consider all aspects of the task, integrated safety into activity performance, increase team unity and ''buy-in'' and promoted innovative and time saving ideas. (4) Development of CED protocols ensured safety and control. (5) The same proven D and D strategy is now being employed on the larger ''sister'' facility, Test Cell C

  14. A radical approach to decommissioning and nuclear liabilities management

    International Nuclear Information System (INIS)

    Pooley, D.

    1996-01-01

    UKAEA Government Division has been set up primarily to manage and eventually eliminate the nuclear liabilities left from the many national nuclear programmes in which UKAEA has been involved. It is no longer primarily a nuclear plant or decommissioning operator but has developed a radical approach to decommissioning. It targets best value for money, alongside meeting safety and environmental requirements, by major use of contractors for its work, including using them as managing agents for big projects. In its first year of operation it made considerable progress in setting out the mission, goals, performance measures and operational principles for such an organization, as well as in reducing costs on a wide front from those expected, in increasing competition for future projects, and in keeping individual projects under good control. It also made major physical progress with specific decommissioning projects. For the future it has established a programme of continuous performance improvement which will bring further benefits and provide a benchmark for all organizations in the business of liabilities management. (author)

  15. Decommissioning a nuclear reactor

    International Nuclear Information System (INIS)

    Montoya, G.M.

    1991-01-01

    The process of decommissioning a facility such as a nuclear reactor or reprocessing plant presents many waste management options and concerns. Waste minimization is a primary consideration, along with protecting a personnel and the environment. Waste management is complicated in that both radioactive and chemical hazardous wastes must be dealt with. This paper presents the general decommissioning approach of a recent project at Los Alamos. Included are the following technical objectives: site characterization work that provided a thorough physical, chemical, and radiological assessment of the contamination at the site; demonstration of the safe and cost-effective dismantlement of a highly contaminated and activated nuclear-fuelded reactor; and techniques used in minimizing radioactive and hazardous waste. 12 figs

  16. Current status and future planning of Fukushima Daiichi Nuclear Power Station after Great East Japan earthquake

    International Nuclear Information System (INIS)

    Inouer, Y.

    2012-01-01

    Fukushima Daiichi Nuclear Power Station (NPS) clean-up and decommissioning activities require a lot of R and D and careful project management due to its severity of damage. Inability of access inside the reactor and turbine buildings due to harsh environment results in large uncertainties which make the project planning difficult R and R activities will be conducted in parallel with on-site clean-up and maintenance activities. In order to cope with this unprecedented challenge, the government, laboratories, academicians, vendors, manufacturers, and other partners have joined together to support tokyo electric Power Company, Inc (TEPCO). This paper will summarize the current status and mid-and long-term plan for the clean-up and decommissioning of Units 1 to 4 of Fukushima Daiichi NPS as of March, 2012. (Author) 15 refs.

  17. A study on the influence of the regulatory requirements of a nuclear facility during decommissioning activities

    Energy Technology Data Exchange (ETDEWEB)

    Park, Hee Seong; Park, Seung Kook; Park, Kook Nam; Hong, Yun Jeong; Park, Jang Jin; Choi, Jong Won [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2016-10-15

    The preliminary decommissioning plan should be written with various chapters such as a radiological characterization, a decommissioning strategy and methods, a design for decommissioning usability, a safety evaluation, decontamination and dismantling activities, radioactive waste management, an environmental effect evaluation, and fire protection. The process requirements of the decommissioning project and the technical requirements and technical criteria should comply with regulatory requirements when dismantling of a nuclear facility. The requirements related to safety in the dismantling of a nuclear facility refer to the IAEA safety serious. The present paper indicates that a decommissioning design and plan, dismantling activities, and a decommissioning project will be influenced by the decommissioning regulatory requirements when dismantling of a nuclear facility. We hereby paved the way to find the effect of the regulatory requirements on the decommissioning of a whole area from the decommissioning strategy to the radioactive waste treatment when dismantling a nuclear facility. The decommissioning requirements have a unique feature in terms of a horizontal relationship as well as a vertical relationship from the regulation requirements to the decommissioning technical requirements. The decommissioning requirements management will be conducted through research that can recognize a multiple relationship in the next stage.

  18. The Communities' research and development programme on decommissioning of nuclear power plants

    International Nuclear Information System (INIS)

    1981-01-01

    This is the first progress report of the European Community's programme (1979-1983) of research on the decommissioning of nuclear power plants. It shows the status of the programme on 31 December 1980. The programme seeks to promote a number of research and development projects as well as the identification of guiding principles. The projects concern the following subjects: long-term integrity of buildings and systems; decontamination for decommissioning purposes; dismantling techniques; treatment of specific waste materials: steel, concrete and graphite; large transport containers for radioactive was produced in the dismantling of nuclear power plants; estimation of the quantities of radioactive wastes arising from decommissioning of nuclear power plants in the Community; influence of nuclear power plant design features on decommissioning

  19. Sellafield Decommissioning Programme - Update and Lessons Learned

    International Nuclear Information System (INIS)

    Lutwyche, P. R.; Challinor, S. F.

    2003-01-01

    The Sellafield site in North West England has over 240 active facilities covering the full nuclear cycle from fuel manufacture through generation, reprocessing and waste treatment. The Sellafield decommissioning programme was formally initiated in the mid 1980s though several plants had been decommissioned prior to this primarily to create space for other plants. Since the initiation of the programme 7 plants have been completely decommissioned, significant progress has been made in a further 16 and a total of 56 major project phases have been completed. This programme update will explain the decommissioning arrangements and strategies and illustrate the progress made on a number of the plants including the Windscale Pile Chimneys, the first reprocessing plan and plutonium plants. These present a range of different challenges and requiring approaches from fully hands on to fully remote. Some of the key lessons learned will be highlighted

  20. The preliminary planning for decommissioning nuclear facilities in Taiwan

    International Nuclear Information System (INIS)

    Li, K.K.

    1993-01-01

    During the congressional hearing in 1992 for a $7 billion project for approval of the fourth nuclear power plant, the public was concerned about the decommissioning of the operating plants. In order to facilitate the public acceptance of nuclear energy and to secure the local capability for appropriate nuclear backend management, both technologically and financially, it is important to have preliminary planning for decommissioning the nuclear facilities. This paper attempted to investigate the possible scope of decommissioning activities and addressed the important regulatory, financial, and technological aspects. More research and development works regarding the issue of decommissioning are needed to carry out the government's will of decent management of nuclear energy from the cradle to the grave

  1. Roadmap and performance carried out during Ciemat site decommissioning

    International Nuclear Information System (INIS)

    Quinones, Javier; Diaz Diaz, Jose Luis

    2005-01-01

    Ciemat (Research Centre for Energy, Environment and Technology) located in the heart of the Ciudad Universitaria of Madrid, occupies a property of 20 Ha. Since its creation in 1951 as JEN, and in 1986 renowned as Ciemat, it has involved on R and D projects in the field of Energy and Environment, i.e., Nuclear Fission, Nuclear Fusion, Fossils Fuels, Renewable Energy. As a consequence of the R and D projects developed between 1951 - 1986 on Nuclear Fission field (fuel design, fabrication, characterization on irradiated fuels, safety studies, etc) and to the diversification of the goals as well, it is necessary to Decommissioning and Dismantling (D and D) from nuclear facilities (nuclear reactor, Hot Cells, Irradiation facility), buildings and soils. Preparations for D and D included a staged shutdown of operations, planning documentation and licensing for decommissioning. As a prerequisite to Ciemat application for a decommissioning license and nuclear environmental assessment was carried out according to Spanish Nuclear Council (CSN) and approval of the site decommissioning project was obtained in 2000 and valid until December 31, 2006. Since 2001 - 2003 is underway and focussed on the radiological characterization of the site (divided in pieces of ground), when each piece of ground is characterized a planning for D and D is presented to CSN in order to obtain a license for actuation. Nowadays several pieces of ground are decontaminated and modifications have been done in order to achieve a safe state of storage-with-surveillance. Later phases have planned waste management improvements for selected wastes already on temporally storage, eventually followed by final decommissioning of facilities and buildings and cleaning of contaminants from soils and removal of waste from the site. This paper describes the planning, nuclear and environment assessment and descriptions of decommissioning activities currently underway at Ciemat. (Author)

  2. Tokai-1 decommissioning project

    International Nuclear Information System (INIS)

    Hirano, Tomoko

    2002-01-01

    The Tokai Power Station (166 MWh in its electric output) of the first commercial nuclear power station in Japan ended its business operation for more than thirty-one years, on end of March, 1998. Through its construction and operation, it has built foundation of nuclear power generation and grown a number of nuclear energy relating engineers. And, technologies and experiences obtained by its construction and operation built base of technology on nuclear power generation in Japan. After now, to share a new role of proof on safe and rational abolishment measure of the first commercial nuclear power stations in Japan, its abolishment measure was begun since December, 2001. It aims at realization of rational subdivision and processing/disposition of wastes, and construction to future LWR abolishment measure. Here were described history of the Tokai Power Station, its outline and process to beginning of stoppage of generation, conditions from the stoppage to beginning of its abolishment measure, outline on its abolishment plan, performing conditions on its abolishment measure, safety security measures, processing and disposition of wastes, and technical development. (G.K.)

  3. Decommissioning plans and program in the Federal Republic of Germany

    International Nuclear Information System (INIS)

    Loschhorn, U.

    1988-01-01

    Seven reactors of different types are currently being decommissioned or plans are being drawn up to do so. The Niederaichbach reactor will be completely dismantled (stage 3) and returned to a green field site within five years. Other reactors will be decommissioned to stage 2. The progress on these projects is summarized. Research and development of decommissioning techniques and tools for decontamination concrete blasting, pipe cutting, remotely controlled manipulators and melting of steel scrap, are described. (author)

  4. Overview of decommissioning research and development activities in the European Community

    International Nuclear Information System (INIS)

    Huber, B.

    1982-01-01

    The European Community's research program on the decommissioning of nuclear power plants is managed by the Commission of the European Communities and carried out by national laboratories and private firms under cost-sharing contracts. Starting in 1980, about fifty research contracts covering a large variety of topics have been let so far. The paper outlines the content, progress and selected results of the seven projects composing the program. These projects concern the following subjects: maintaining disused plants in a safe condition; decontamination for decommissioning purposes; dismantling techniques; treatment of waste materials; large waste containers; estimation of waste arisings; and plant design features facilitating decommissioning. 4 references

  5. Decommissioning strategies for facilities using radioactive material

    International Nuclear Information System (INIS)

    2007-01-01

    The planning for the decommissioning of facilities that have used radioactive material is similar in many respects to other typical engineering projects. However, decommissioning differs because it involves equipment and materials that are radioactive and therefore have to be handled and controlled appropriately. The project management principles are the same. As with all engineering projects, the desired end state of the project must be known before the work begins and there are a number of strategies that can be used to reach this end state. The selection of the appropriate strategy to be used to decommission a facility can vary depending on a number of factors. No two facilities are exactly the same and their locations and conditions can result in different strategies being considered acceptable. The factors that are considered cover a wide range of topics from purely technical issues to social and economic issues. Each factor alone may not have a substantial impact on which strategy to select, but their combination could lead to the selection of the preferred or best strategy for a particular facility. This Safety Report identifies the factors that are normally considered when deciding on the most appropriate strategy to select for a particular facility. It describes the impact that each factor can have on the strategy selection and also how the factors in combination can be used to select an optimum strategy

  6. Decommissioning of Brennilis NPP

    International Nuclear Information System (INIS)

    Baize, Jean-Marc

    1998-01-01

    This EDF press communique give information related to the decommissioning of the Brennilis NPP. The following five items are developed in this report: 1. the level-2 decommissioning operations at the Brennilis NPP; 2. the Brennilis NPP, a pilot operation from the commissioning up to the decommissioning; 3. history of the Brennilis NPP decommissioning; 4. the types of radioactive wastes generated by the Brennilis NPP decommissioning; 5. the Brennilis NPP - a yard management as a function of the wastes. The document contains also seven appendices addressing the following subjects: 1. the share of decommissioning assigned to EDF and the decommissioning steps; 2. the EDF installations in course of decommissioning; 3. the CEA decommissioned installations or in course of decommissioning; 4. regulations; 5. costs; 6. waste management - principles; 7. data on the decommissioning yard

  7. Decommissioning technology development for research reactors

    International Nuclear Information System (INIS)

    Lee, K. W.; Kim, S. K.; Kim, Y. K.

    2004-03-01

    Although it is expected that the decommissioning of a nuclear power plant will happen since 2020, the need of partial decommissioning and decontamination for periodic inspection and life extension has been on an increasing trend and domestic market has gradually been extended. Therefore, in this project the decommissioning DB system on the KRR-1 and 2 was developed as establishing the information classification system of the research reactor dismantling and the structural design and optimization of the decommissioning DB system. Also in order to secure the reliability and safety about the dismantling process, the main dismantling simulation technology that can verify the dismantling process before their real dismantling work was developed. And also the underwater cutting equipment was developed to remove these stainless steel parts highly activated from the RSR. First, the its key technologies were developed and then the design, making, and capability analysis were performed. Finally the actual proof was achieved for applying the dismantling site. an automatic surface contamination measuring equipment was developed in order to get the sample automatically and measure the radiation/radioactivity

  8. Importance of funding in decommissioning cost estimates

    International Nuclear Information System (INIS)

    Mingst, B.C.

    1987-01-01

    Decommissioning cost estimates have been made by several study groups for the decommissioning of pressurized-water and boiling-water nuclear power stations. The results of these studies are comparable when corrected for inflation and the differences in contingency factors applied by the study groups. The estimated dismantling costs differ far less than a factor of 2 in all cases, despite the design differences found in the plants that were studied. An analysis of the different methods available for funding the dismantling of these facilities shows the much stronger effect that the choice of funding methods has on the net cost of decommissioning. The total cost of dismantling may vary more than a factor of 4 from one funding method to another, assuming current or recent historical inflation rates. The funding methods evaluated include sinking funds, deposits, negative-salvage value depreciation, and insurance. These funding methods are taken from the NRC's Notice of Proposed Rulemaking description of acceptable funding methods. The funding analysis for this study was performed using the DECOST-86 computer code. The evaluation of funding options for a nuclear facility, and the appropriate choice of the funding method best for that facility, are found to be more important than detailed engineering studies in determining the net cost of decommissioning during the early portions of the plant's operating lifetime

  9. IAEA International Peer Review Mission on Mid-and-Long-Term Roadmap Towards the Decommissioning of TEPCO's Fukushima Daiichi Nuclear Power Station Units 1-4, Tokyo and Fukushima Prefecture, Japan, 15-22 April 2013. Mission Report

    International Nuclear Information System (INIS)

    2013-01-01

    Following the accident at TEPCO's Fukushima Daiichi Nuclear Power Station (NPS) on 11 March 2011, the ''Mid-and-Long-Term Roadmap towards the Decommissioning of TEPCO's Fukushima Daiichi Nuclear Power Station Units 1-4'' was adopted by the Government of Japan and TEPCO Council on Mid-to-Long-Term Response for Decommissioning in December 2011 and revised in July 2012. The Roadmap, which is scheduled for an additional update in June 2013, describes the main steps and activities to be implemented for the decommissioning of the Fukushima Daiichi NPS through the combined efforts of the Government of Japan and TEPCO. Within the framework of the IAEA Action Plan on Nuclear Safety, the Government of Japan invited the IAEA to conduct an independent peer review of the Roadmap with two main objectives: - To improve the decommissioning planning and the implementation of pre-decommissioning activities at TEPCO's Fukushima Daiichi NPS; and - To share with the international community the good practices and lessons learned by the review. The review has been organized in two steps, and the IAEA conducted the first part in Japan from 15 to 22 April 2013. The objective of the first mission was to undertake an initial review of the Roadmap, including assessments of decommissioning strategy, planning and timing of decommissioning phases and a review of several specific short-term issues and recent challenges. Specifically, it covered the assessment of current reactor conditions, assessment of management of radioactive releases and associated doses, control of radioactive exposure of employees and decontamination within the site for improvement of working environment, structural integrity of reactor buildings and other constructions. The incidents recently experienced at the site, related with failures of the power supply and leakages of water from the underground reservoirs, were also included in the review of the specific short-term issues. The Government of Japan and TEPCO have

  10. Decommissioning of facilities for mining and milling or radioactive ores and closeout of residues

    International Nuclear Information System (INIS)

    1994-01-01

    The purpose of this report is to provide information to Member States in order to assist in planning and implementing the decommissioning/closeout of uranium mine/mill facilities, mines, tailings impoundments, mining debris piles, leach residues and unprocessed ore stockpiles. The report presents an overview of the factors involved in planning and implementing the decommissioning/closeout of uranium mine/mill facilities. The information applies to mines, mills, tailings piles, mining debris piles and leach residues that are present as operational, mothballed or abandoned projects, as well as to future mining and milling projects. The report identifies the major factors that need to be considered in the decommissioning/closeout activities, including regulatory considerations; decommissioning of the mine/mill buildings, structures and facilities; decommissioning/closeout of open pit and underground mines; decommissioning/closeout of tailings impoundments; decommissioning/closeout of mining debris piles, unprocessed ore and other contaminated material such as heap leach piles, in situe leach facilities and contaminated soils; restoration of the site, vicinity properties and groundwater; radiation protection and health and safety considerations; and an assessment of costs and post-decommissioning or post-closeout maintenance and monitoring needs. 55 refs, figs and tabs

  11. Implementing 'Continuous Improvement' in the U.S. Nuclear Regulatory Commission's Decommissioning Program

    International Nuclear Information System (INIS)

    Orlando, D. A.; Buckley, J. T.; Johnson, R. L.; Gillen, D. M.

    2006-01-01

    The United States Nuclear Regulatory Commission's (US NRC's) comprehensive decommissioning program encompasses the decommissioning of all US NRC licensed facilities, ranging from the termination of routine licenses for sealed sources, to the closure of complex materials sites and nuclear power reactor facilities. Of the approximately 200 materials licenses that are terminated each year, most are routine and require little, if any, remediation to meet the US NRC unrestricted release criteria. However, some present technical and policy challenges that require large expenditures of resources, including a few complex materials sites that have requested license termination under the restricted-use provisions of 10 CFR 20.1403. Fiscal constraints to reduce budgeted resources in the decommissioning program, as well as concerns over the time to complete the decommissioning process have led to actions to improve the program and use resources more efficiently. In addition, the US NRC's Strategic Plan requires efforts to identify and implement improvements to US NRC programs in order to improve efficiency, effectiveness, timeliness, and openness, of the US NRC's activities, while maintaining the necessary focus on safety. Decommissioning regulations, and more recently the analysis of several issues associated with implementing those regulations, also have been significant catalysts for improvements in the decommissioning program. Actions in response to these catalysts have resulted in a program focused on the management of complex sites in a comprehensive, consistent, and risk-informed manner, as opposed to the past practice of focusing on sites deemed to be problematic. This paper describes the current status of the decommissioning of US NRC-licensed nuclear facilities, including an overview of recent decommissioning project completion efforts. It provides a detailed summary of past, current, and future improvements in the US NRC decommissioning program including the

  12. Cost estimation for decommissioning: a review of current practice

    International Nuclear Information System (INIS)

    O'Sullivan, P.; Pescatore, C.

    2009-01-01

    boundary conditions; cost estimation methodologies; and experience gained during the process. Twelve countries provided responses and participated in the analysis: Belgium, Canada, France, Germany, Italy, Japan, the Netherlands, the Slovak Republic, Spain, Sweden, the United Kingdom and the United States. The final report documenting the study is nearing publication. Its main findings are reported in this article. There is no single cost assessment methodology that applies equally at all stages of a decommissioning project. This means that different cost assessment methodologies may need to be used as the project advances. Such methodologies should be continuously updated using cost data from actual decommissioning projects, thus improving the cost assessment, providing better control of uncertainties and contingencies for each major cost category, and facilitating the preparation of an annualized schedule of expenditures for each facility. In the future, risk management may benefit from an approach that uses a deterministic calculation (base case) that feeds into a probabilistic assessment of future costs. Such approaches may be used to gain a better understanding of potential cost and programme requirements. Attention should also be given early on to socio-economic factors, including impacts caused by loss of employment, to help in building public support and acceptance of a decommissioning project. Early meetings with stakeholders may be used to gain agreement on project boundary conditions, strategy, release criteria and measurement protocols, and waste containers used. In view of the very significant impacts that changes and increases in scope may have on cost estimates, it is important that these be identified and controlled immediately, and incorporated into the estimate so that the estimate may continue to provide a viable benchmarking resource. Characterisation is acknowledged to be an important part of cost estimating accuracy, as it affects system and structure

  13. On-site disposal as a decommissioning strategy

    International Nuclear Information System (INIS)

    1999-11-01

    On-site disposal is not a novel decommissioning strategy in the history of the nuclear industry. Several projects based on this strategy have been implemented. Moreover, a number of studies and proposals have explored variations within the strategy, ranging from in situ disposal of entire facilities or portions thereof to disposal within the site boundary of major components such as the reactor pressure vessel or steam generators. Regardless of these initiatives, and despite a significant potential for dose, radioactive waste and cost reduction, on-site disposal has often been disregarded as a viable decommissioning strategy, generally as the result of environmental and other public concerns. Little attention has been given to on-site disposal in previous IAEA publications in the field of decommissioning. The objective of this report is to establish an awareness of technical factors that may or may not favour the adoption of on-site disposal as a decommissioning strategy. In addition, this report presents an overview of relevant national experiences, studies and proposals. The expected end result is to show that, subject to safety and environmental protection assessment, on-site disposal can be a viable decommissioning option and should be taken into consideration in decision making

  14. IAEA/CRP for decommissioning techniques for research reactors

    Energy Technology Data Exchange (ETDEWEB)

    Oh, Won Zin; Won, H. J.; Kim, K. N.; Lee, K. W.; Jung, C. H

    2001-03-01

    The following were studied through the project entitled 'IAEA/CRP for decommissioning techniques for research reactors 1. Decontamination technology development for TRIGA radioactive soil waste - Electrokinetic soil decontamination experimental results and its mathematical simulation 2. The 2nd IAEA/CRP for decommissioning techniques for research reactors - Meeting results and program 3. Hosting the 2001 IAEA/RCA D and D training course for research reactors and small nuclear facilities.

  15. IAEA/CRP for decommissioning techniques for research reactors

    International Nuclear Information System (INIS)

    Oh, Won Zin; Won, H. J.; Kim, K. N.; Lee, K. W.; Jung, C. H.

    2001-03-01

    The following were studied through the project entitled 'IAEA/CRP for decommissioning techniques for research reactors 1. Decontamination technology development for TRIGA radioactive soil waste - Electrokinetic soil decontamination experimental results and its mathematical simulation 2. The 2nd IAEA/CRP for decommissioning techniques for research reactors - Meeting results and program 3. Hosting the 2001 IAEA/RCA D and D training course for research reactors and small nuclear facilities

  16. Reactor decommissioning in a deregulated market

    International Nuclear Information System (INIS)

    Beverridge, George; Cooper, T.

    2002-01-01

    Full text: Deregulation of the electricity markets in North America and Western Europe has had many profound effects on the electric utilities and the nuclear industry. Deregulation has led to cost transparency, increased competition, and a drive by the utilities to reduce costs in order to maintain market share and margins. In the context of this more competitive and dynamic market having a clear picture of decommissioning liabilities and their successful discharge has a material impact on the financial performance of a utility. This paper will summarise BNFL Environmental Services' experience with regard to its experience in both the planning and implementation phases of a reactor decommissioning project. In particular it will demonstrate how commercial projects in crucial areas of strategy development, project implementation and site restoration, can be combined with an approach that is both commercial and innovative to reduce the risks to a utility. This paper sets out to demonstrate this viewpoint. (author)

  17. Decommissioning and environmental remediation: An overview

    International Nuclear Information System (INIS)

    Chatzis, Irena

    2016-01-01

    The objective in both decommissioning and environmental remediation is to lower levels of residual radioactivity enough that the sites may be used for any purpose, without restriction. In some cases, however, this may not be practical and restrictions may be placed on future land use. Following decommissioning, for example, some sites may be reused for non-nuclear industrial activities, but not for habitation. Some former uranium mining sites may be released for reuse as nature reserves or for other leisure activities. Both decommissioning and environmental remediation are major industrial projects in which the safety of the workforce, the local public and the environment must be ensured from both radiological and conventional hazards. Hence, an appropriate legal and regulatory framework, as well as proper training for personnel both in implementation and in regulatory oversight are among the necessary preconditions to ensure safety.

  18. Decommissioning and environmental remediation: An overview

    International Nuclear Information System (INIS)

    Chatzis, Irena

    2016-01-01

    The objective in both decommissioning and environmental remediation is to lower levels of residual radioactivity enough that the sites may be used for any purpose, without restriction. In some cases, however, this may not be practical and restrictions may be placed on future land use. Following decommissioning, for example, some sites may be reused for non-nuclear industrial activities, but not for habitation. Some former uranium mining sites may be released for reuse as nature reserves or for other leisure activities. Both decommissioning and environmental remediation are major industrial projects in which the safety of the workforce, the local public and the environment must be ensured from both radiological and conventional hazards. Hence, an appropriate legal and regulatory framework, as well as proper training for personnel both in implementation and in regulatory oversight are among the necessary preconditions to ensure safety

  19. Volume Reduction of Decommissioning Radioactive Burnable and Metal Wastes

    Energy Technology Data Exchange (ETDEWEB)

    Min, B. Y.; Lee, Y. J.; Yun, G. S.; Lee, K. W.; Moon, J. K. [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of); Choi, Y. K.; Cho, J. H. [SunKwang Atomic Energy Safety Co., Seoul (Korea, Republic of)

    2014-10-15

    A large quantity of radioactive waste was generated during the decommissioning projects. For the purpose of the volume reduction and clearance for decommissioning wastes from decommissioning projects, the incineration and high melting technology has been selected for the decommissioning wastes treatment. The volume reduction of the combustible wastes through the incineration technologies has merits from the view point of a decrease in the amount of waste to be disposed of resulting in a reduction of the disposal cost. Incineration is generally accepted as a method of reducing the volume of radioactive waste. The incineration technology is an effective treatment method that contains hazardous chemicals as well as radioactive contamination. Incinerator burns waste at high temperature. Incineration of a mixture of chemically hazardous and radioactive materials, known as 'mixed waste,' has two principal goals: to reduce the volume and total chemical toxicity of the waste. Incineration itself does not destroy the metals or reduce the radioactivity of the waste. A proven melting technology is currently used for low-level waste (LLW) at several facilities worldwide. These facilities use melting as a means of processing LLW for unrestricted release of the metal or for recycling within the nuclear sector. About 16.4 tons of decommissioning combustible waste has been treated using Oxygen Enriched incineration. The incineration facility operated quite smoothly through the analysis major critical parameters of off-gas.

  20. Volume Reduction of Decommissioning Radioactive Burnable and Metal Wastes

    International Nuclear Information System (INIS)

    Min, B. Y.; Lee, Y. J.; Yun, G. S.; Lee, K. W.; Moon, J. K.; Choi, Y. K.; Cho, J. H.

    2014-01-01

    A large quantity of radioactive waste was generated during the decommissioning projects. For the purpose of the volume reduction and clearance for decommissioning wastes from decommissioning projects, the incineration and high melting technology has been selected for the decommissioning wastes treatment. The volume reduction of the combustible wastes through the incineration technologies has merits from the view point of a decrease in the amount of waste to be disposed of resulting in a reduction of the disposal cost. Incineration is generally accepted as a method of reducing the volume of radioactive waste. The incineration technology is an effective treatment method that contains hazardous chemicals as well as radioactive contamination. Incinerator burns waste at high temperature. Incineration of a mixture of chemically hazardous and radioactive materials, known as 'mixed waste,' has two principal goals: to reduce the volume and total chemical toxicity of the waste. Incineration itself does not destroy the metals or reduce the radioactivity of the waste. A proven melting technology is currently used for low-level waste (LLW) at several facilities worldwide. These facilities use melting as a means of processing LLW for unrestricted release of the metal or for recycling within the nuclear sector. About 16.4 tons of decommissioning combustible waste has been treated using Oxygen Enriched incineration. The incineration facility operated quite smoothly through the analysis major critical parameters of off-gas

  1. Brazilian nuclear power plants decommissioning plan for a multiple reactor site

    Energy Technology Data Exchange (ETDEWEB)

    Monteiro, Deiglys B.; Moreira, Joao M.L.; Maiorino, Jose R., E-mail: deiglys.monteiro@ufabc.edu.br, E-mail: joao.moreira@ufabc.edu.br, E-mail: joserubens.maiorino@ufabc.edu.br [Universidade Federal do ABC (CECS/UFABC), Santo Andre, SP (Brazil). Centro de Engenharia, Modelagem e Ciencias Aplicadas. Programa de Pos-Graduacao em Energia e Engenharia da Energia

    2015-07-01

    Actually, Brazil has two operating Nuclear Power Plants and a third one under construction, all at Central Nuclear Almirante Alvaro Alberto - CNAAA. To comply with regulatory aspects the power plants operator, Eletronuclear, must present to Brazilian Nuclear Regulatory Agency, CNEN, a decommissioning plan. Brazilian experience with decommissioning is limited because none of any nuclear reactor at the country was decommissioned. In literature, decommissioning process is well described despite few nuclear power reactors have been decommissioned around the world. Some different approach is desirable for multiple reactors sites, case of CNAAA site. During the decommissioning, a great amount of wastes will be produced and have to be properly managed. Particularly, the construction of Auxiliary Services on the site could be a good choice due to the possibility of reducing costs. The present work intends to present to the Eletronuclear some aspects of the decommissioning concept and decommissioning management, storage and disposal de wastes, based on the available literature, regulatory standards of CNEN and international experience as well as to suggest some solutions to be implemented at CNAAA site before starts the decommissioning project in order to maximize the benefits. (author)

  2. Brazilian nuclear power plants decommissioning plan for a multiple reactor site

    International Nuclear Information System (INIS)

    Monteiro, Deiglys B.; Moreira, Joao M.L.; Maiorino, Jose R.

    2015-01-01

    Actually, Brazil has two operating Nuclear Power Plants and a third one under construction, all at Central Nuclear Almirante Alvaro Alberto - CNAAA. To comply with regulatory aspects the power plants operator, Eletronuclear, must present to Brazilian Nuclear Regulatory Agency, CNEN, a decommissioning plan. Brazilian experience with decommissioning is limited because none of any nuclear reactor at the country was decommissioned. In literature, decommissioning process is well described despite few nuclear power reactors have been decommissioned around the world. Some different approach is desirable for multiple reactors sites, case of CNAAA site. During the decommissioning, a great amount of wastes will be produced and have to be properly managed. Particularly, the construction of Auxiliary Services on the site could be a good choice due to the possibility of reducing costs. The present work intends to present to the Eletronuclear some aspects of the decommissioning concept and decommissioning management, storage and disposal de wastes, based on the available literature, regulatory standards of CNEN and international experience as well as to suggest some solutions to be implemented at CNAAA site before starts the decommissioning project in order to maximize the benefits. (author)

  3. The NEA co-operative programme on decommissioning decontamination and demolition of concrete structures

    International Nuclear Information System (INIS)

    Berton, Marie-Anne; Estivie, David; Cantrel, Eric; Moeller, Joerg; Ondaro, Manuel; Ooms, Bart; Wittenauer, Stefan; Burton, Bob

    2011-01-01

    In response to growing interest in the decommissioning of nuclear facilities, the OECD Nuclear Energy Agency set up the Co-operative Programme on Decommissioning in 1985. Its basic scope is to facilitate the exchange of scientific and technical information between major decommissioning projects. Participation in the Programme has expanded significantly over the years to include organisations from 13 countries. Currently, about 60 projects participate in the Programme. The Programme is executed under an agreement between the participating organisations and companies. A progress report is issued every five years on the CPD and includes a brief description of each project. The most recent report is entitled A Decade of Progress. The projects are divided into two groups: reactor projects (60%) and fuel facility projects (40%). A complete list of the different projects and their country of residence can be found in Annex 1. Many of the early projects in the Programme focused on experimental or prototype plants, however, a number of projects for the decommissioning of commercial facilities (power generation, fuel and reprocessing plants) have recently joined the Programme. Limited feedback on concrete clean-up operations has been available until now due to the lengthy time frame of decommissioning projects and the fact that building demolition occurs in the very late stages of the project. Some of the early projects in the Programme are now complete or nearing completion, making available significant data and experience. This experience and lessons learnt can be applied to the further development of decommissioning and dismantling (D and D) clean-up processes. This report aims to supplement the previous NEA report dedicated to decontamination techniques and to provide project engineers and/or project leaders involved in concrete infrastructure clean-up with: - Guidelines for setting up appropriate and adequate strategies, taking into consideration the international

  4. A Prediction on the Unit Cost Estimation for Decommissioning Activities Using the Experienced Data from DECOMMIS

    Energy Technology Data Exchange (ETDEWEB)

    Park, Seung Kook; Park, Hee Seong; Choi, Yoon Dong; Song, Chan Ho; Moon, Jei Kwon [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2014-05-15

    The KAERI (Korea Atomic Energy Research Institute) has developed the DECOMMIS (Decommissioning Information Management System) and have been applied for the decommissioning project of the KRR (Korea Research Reactor)-1 and 2 and UCP (Uranium Conversion Plant), as the meaning of the first decommissioning project in Korea. All information and data which are from the decommissioning activities are input, saved, output and managed in the DECOMMIS. This system was consists of the web server and the database server. The users could be access through a web page, depending on the input, processing and output, and be modified the permissions to do such activities can after the decommissioning activities have created the initial system-wide data is stored. When it could be used the experienced data from DECOMMIS, the cost estimation on the new facilities for the decommissioning planning will be established with the basic frame of the WBS structures and its codes. In this paper, the prediction on the cost estimation through using the experienced data which were store in DECOMMIS was studied. For the new decommissioning project on the nuclear facilities in the future, through this paper, the cost estimation for the decommissioning using the experienced data which were WBS codes, unit-work productivity factors and annual governmental unit labor cost is proposed. These data were from the KRR and UCP decommissioning project. The differences on the WBS code sectors and facility characterization between new objected components and experienced dismantled components was reduces as scaling factors. The study on the establishment the scaling factors and cost prediction for the cost estimation is developing with the algorithms from the productivity data, now.

  5. EPRI Guidance for Transition from Operations to Decommissioning

    International Nuclear Information System (INIS)

    McGrath, Richard; Reid, Richard; Snyder, Michael

    2016-01-01

    A wide range of key activities are necessary after permanent shutdown of a nuclear power plant before active dismantlement of the plant can begin. This period is typically referred to as the transition period. In some cases these activities are prescribed by regulation and in others they may be more practically driven or even optional. In either case, planning for transition activities should optimally take place prior to final shutdown. Additionally, execution of some transition period activities, such as filing required regulatory submittals, may be performed prior to plant shut down. In addition to general transition period activities such as defueling, management of operational wastes, fulfilling regulatory requirements and changes to plant technical specifications, there are a number of optional activities that may have a long-range impact on future decommissioning activities. This includes activities such as the timing of staff reductions and performance of chemical decontamination. EPRI is nearing completion of a project to develop guidance for transitioning a nuclear power plant to decommissioning. This project includes the following elements: - A review of required and recommended transition period activities. For countries where a clear regulatory framework exists, this includes country-specific requirements; - A review of pending regulatory activities in the US and other countries where there is currently no clear regulatory framework for transitioning to decommissioning; - A summary of activities that have been performed during the transition period for past and current decommissioning sites, as well as current sites that are actively planning decommissioning activities; and - Guidance for development of a transition plan for changing from an operational to decommissioning status. Informed planning of the transition period activities will provide immediate benefits in reducing costs and minimizing the duration of the transition period, as well as longer

  6. Assessment of foreign decommissioning technology with potential application to US decommissioning needs

    International Nuclear Information System (INIS)

    Allen, R.P.; Konzek, G.J.; Schneider, K.J.; Smith, R.I.

    1987-09-01

    This study was conducted by the Pacific Northwest Laboratory (PNL) for the US Department of Energy (DOE) to identify and technically assess foreign decommissioning technology developments that may represent significant improvements over decommissioning technology currently available or under development in the United States. Technology need areas for nuclear power reactor decommissioning operations were identified and prioritized using the results of past light water reactor (LWR) decommissioning studies to quantitatively evaluate the potential for reducing cost and decommissioning worker radiation dose for each major decommissioning activity. Based on these identified needs, current foreign decommissioning technologies of potential interest to the US were identified through personal contacts and the collection and review of an extensive body of decommissioning literature. These technologies were then assessed qualitatively to evaluate their uniqueness, potential for a significant reduction in decommissioning costs and/or worker radiation dose, development status, and other factors affecting their value and applicability to US needs

  7. Project plan for the decontamination and decommissioning of the Argonne National Laboratory Experimental Boiling Water Reactor

    International Nuclear Information System (INIS)

    Boing, L.E.

    1989-12-01

    In 1956, the Experimental Boiling Water Reactor (EBWR) Facility was first operated at Argonne National Laboratory (ANL) as a test reactor to demonstrate the feasibility of operating an integrated power plant using a direct cycle boiling water reactor as a heat source. In 1967, ANL permanently shut down the EBWR and placed it in dry lay-up. This project plan presents the schedule and organization for the decontamination and decommissioning of the EBWR Facility which will allow it to be reused by other ANL scientific research programs. The project total estimated cost is $14.3M and is projected to generate 22,000 cubic feet of low-level radioactive waste which will be disposed of at an approved DOE burial ground. 18 figs., 3 tabs

  8. Project plan for the decontamination and decommissioning of the Argonne National Laboratory Experimental Boiling Water Reactor

    Energy Technology Data Exchange (ETDEWEB)

    Boing, L.E.

    1989-12-01

    In 1956, the Experimental Boiling Water Reactor (EBWR) Facility was first operated at Argonne National Laboratory (ANL) as a test reactor to demonstrate the feasibility of operating an integrated power plant using a direct cycle boiling water reactor as a heat source. In 1967, ANL permanently shut down the EBWR and placed it in dry lay-up. This project plan presents the schedule and organization for the decontamination and decommissioning of the EBWR Facility which will allow it to be reused by other ANL scientific research programs. The project total estimated cost is $14.3M and is projected to generate 22,000 cubic feet of low-level radioactive waste which will be disposed of at an approved DOE burial ground. 18 figs., 3 tabs.

  9. Strategic aspects on waste management in decommissioning of nuclear facilities

    International Nuclear Information System (INIS)

    Rannemalm, T.; Eliasson, S.; Larsson, A.; Lidar, P.; Bergh, N.; Hedin, G.

    2017-01-01

    A team composed of experts from the facility owner OKG, Westinghouse and Studsvik (today Cyclife Sweden and Studsvik Consulting) was asked to develop a basis for decision on an overall strategy for the management of the material and waste arising from the decommissioning of two BWR NPPs at the Oskarshamn site in Sweden. To be able to provide a good basis for decision the full waste management chain from generation to disposition, i.e. clearance or disposal had to be assessed, categorised, quantified and analysed with regards to costs, environmental impact and risks. A systematic approach was applied taking benefit of the decommissioning studies made previously for the two facilities, the decommissioning concepts developed by Ndcon (the partnership in decommissioning between Studsvik and Westinghouse) and the combined knowledge and experience in the project team. In total 4 different waste management concepts were compared individually and in combinations. The four concepts evaluated were based on: direct disposal in the national geological repository; treatment of the waste for volume reduction and where applicable clearance in an external waste treatment facility; decontamination and clearance in an on-site waste treatment facility; direct disposal in a near surface repository at the NPP site. It was important to be able to compare the different options in a quantifiable way. Therefore the project team set up a matrix with parameters for the different options gained from the utility, the national waste management company, external vendors and the experience of the team. In this way a quantitative analysis could be done with the four different waste management options. In addition to the quantitative analysis the team summarised decades of experience in radioactive waste management and decommissioning recommendations and risk analyses. Special attention was given to risk mitigation and redundancy in the waste management chain. The development of an overall waste

  10. Decommissioning, mothballing and revamping

    International Nuclear Information System (INIS)

    Briggs, M.; Buck, S.; Smith, M.

    1997-01-01

    This guide, written to assist those concerned with the decommissioning of redundant facilities, is applicable to nuclear, chemical and power plants. Legal aspects and risk management is covered in the pre-project stage. Preparation for and execution of renovation, modification or mothballing of various plants is also covered. Dismantling operations and the necessary follow-up conclude the book. (UK)

  11. Global solutions through simulation for better decommissioning

    International Nuclear Information System (INIS)

    Scoto Di Suoccio, Ines; Testard, Vincent

    2016-01-01

    Decommissioning is a new activity in sense that it only exists a limited experience. Moreover, each facility is different due to their own history and there is no rule about choosing a decommissioning strategy. There are three major decommissioning strategies. First, 'immediate dismantling', which means the action of decommissioning begins immediately after the transfer of waste and nuclear material. Second, 'deferred dismantling strategy', which means that the facility is maintained into a containment zone from thirty to one hundred years before being decommissioned. Finally, 'entombment', means the facility is placed into a reinforced containment until the radionuclides decay and reach a level allowing the site release. When a strategy is decided many factors have to be taken into account. Into a major project such as a reactor decommissioning, there are many smaller projects. The decommissioning strategy can be different among these smaller projects. For some reasons, some entry data are not perfectly known. For example, dosimetric activity has not been updated through time or after specific events. Indeed, because of uncertainties and/or hypothesis existing around projects and their high level of interdependency, global solutions are a good way to choose the best decommissioning strategy. Actually, each entry data has consequences on output results whether it is on costs, cumulated dose, waste or delays. These output data are interdependent and cannot be taken apart from each other. Whether the dose, delays or waste management, all have impact on costs. To obtain an optimal scenario into a special environment, it is necessary to deal with all these items together. This global solution can be implemented thanks to simulation in dedicated software which helps to define the global strategy, to optimize the scenario, and to prevent contingencies. As a complete scenario simulation can be done quickly and efficiently, many strategies can

  12. Planning activities for ANPP decommissioning

    International Nuclear Information System (INIS)

    Ghazaryan, K.G.

    2002-01-01

    The Armenian NPP consists of two WWER-440, model 270 pressurized water reactors. After an earthquake in northern Armenia in December 1988 both units were shut down for safety reasons: Unit 1 in February 1988, Unit 2 in March 1989, respectively. Unit 2 was restarted in November 1995 after a number of safety upgrades. Unit 1 remains in a long-term shutdown mode. The design lifetime of Unit 2 expires in 2015. Opportunity to shutdown earlier has been discussed in the last years. In particular a statement has been issued by EC asking for an early shutdown of Unit 2 in exchange for the TACIS support in implementing the safety upgrades in a short term. Currently the safety improvement program is being successfully implemented in the framework of US DOE and TACIS assistance. At the moment the date of the permanent plant shutdown is not specified. As with many older reactors throughout the world, a decommissioning plan has not been developed for Armenian NPP at the design stage. After shutdown of ANPP in 1988-1989 the radiological characterization campaign at Unit 1 had been carried out. Recently two studies in the decommissioning area have been performed for ANPP. The first one has been carried out under the US DOE Assistance Program. The purpose of this study was to identify and evaluate feasible decommissioning options for ANPP. Some critical issues related to the waste management had been specified and the near-term activities within this project will be focused on issues of waste characterization and information data base creation as an important prerequisite to manage waste safely. The model used to calculate many of the decommissioning costs was NRC CECP reprogrammed for WWER NPPs. The second study had been carried out in the framework of TACIS project 'Assistance to Energy Strategic Center'. The purpose of the study was to select the best strategy to phase-out and decommission the ANPP and evaluate conditions, implications and consequence of this decision. A

  13. Decommissioning of a tritium-contaminated laboratory

    International Nuclear Information System (INIS)

    Harper, J.R.; Garde, R.

    1982-01-01

    A tritium laboratory facility at the Los Alamos National Laboratory, Los Alamos, New Mexico, was decommissioned in 1979. The project involved dismantling the laboratory equipment and disposing of the equipment and debris at an on-site waste disposal/storage area. The laboratory, constructed in 1953, was in service for tritium research and fabrication of lithium tritide components until 1974. The major features of the laboratory included 25 meters of gloveboxes and hoods, associated vacuum lines, utility lines, exhaust ducts, electrodryers, blowers, and laboratory benches. This report presents details on the decommissioning, health physics, waste management, environmental surveillance, and costs for the operation

  14. Preservation and Implementation of Decommissioning Lessons Learned in the United States Nuclear Regulatory Commission

    International Nuclear Information System (INIS)

    Rodriguez, Rafael L.

    2008-01-01

    Over the past several years, the United States Nuclear Regulatory Commission (NRC) has actively worked to capture and preserve lessons learned from the decommissioning of nuclear facilities. More recently, NRC has involved industry groups, the Organization of Agreement States (OAS), and the Department of Energy (DOE) in the effort to develop approaches to capture, preserve and disseminate decommissioning lessons learned. This paper discusses the accomplishments of the working group, some lessons learned by the NRC in the recent past, and how NRC will incorporate these lessons learned into its regulatory framework. This should help ensure that the design and operation of current and future nuclear facilities will result in less environmental impact and more efficient decommissioning. In summary, the NRC will continue capturing today's experience in decommissioning so that future facilities can take advantage of lessons learned from today's decommissioning projects. NRC, both individually and collectively with industry groups, OAS, and DOE, is aggressively working on the preservation and implementation of decommissioning lessons learned. The joint effort has helped to ensure the lessons from the whole spectrum of decommissioning facilities (i.e., reactor, fuel cycle, and material facilities) are better understood, thus maximizing the amount of knowledge and best practices obtained from decommissioning activities. Anticipated regulatory activities at the NRC will make sure that the knowledge gained from today's decommissioning projects is preserved and implemented to benefit the nuclear facilities that will decommission in the future

  15. BCD: a wiki-based decommissioning knowledge management tool

    International Nuclear Information System (INIS)

    Fontaine, V.; Coudouneau, L.; Goursaud, V.

    2008-01-01

    Knowledge management allows decommissioning stakeholders to take advantage of past experience (in terms of efficiency, quality, safety, cost, etc.), avoid repeating previous errors, and identify good ideas and practices. It is usually broken down into three processes: collecting information, supplementing and enriching it, and making it available to all decommissioning stakeholders. The CEA has been collecting and centralizing data for many years: the first qualitative assessment of operational experience began in 1991. However, the documents collected were not always relevant for this assessment and, for lack of enrichment and distribution, were generally not used to a significant extent. In order to take advantage of the existing and future body of knowledge and to share this knowledge among decommissioning stakeholders, the CEA decommissioning review unit decided to develop an intranet site known as BCD (from the French acronym for Central Decommissioning Database) using the same wiki technology as the collaborative web encyclopedia, Wikipedia. The objective of BCD is to develop a decommissioning encyclopedia comprising definitions and terminology, the regulatory framework, the lessons of experience with technical or contractual projects, guidelines, statements of results, etc. This article describes BCD and its potential, together with the results observed to date and its prospects for future development. (authors)

  16. Hydrogen fueling stations in Japan hydrogen and fuel cell demonstration project

    International Nuclear Information System (INIS)

    Koseki, K.; Tomuro, J.; Sato, H.; Maruyama, S.

    2004-01-01

    A new national demonstration project of fuel cell vehicles, which is called Japan Hydrogen and Fuel Cell Demonstration Project (JHFC Project), has started in FY2002 on a four-year plan. In this new project, ten hydrogen fueling stations have been constructed in Tokyo and Kanagawa area in FY2002-2003. The ten stations adopt the following different types of fuel and fueling methods: LPG reforming, methanol reforming, naphtha reforming, desulfurized-gasoline reforming, kerosene reforming, natural gas reforming, water electrolysis, liquid hydrogen, by-product hydrogen, and commercially available cylinder hydrogen. Approximately fifty fuel cell passenger cars and a fuel cell bus are running on public roads using these stations. In addition, two hydrogen stations will be constructed in FY2004 in Aichi prefecture where The 2005 World Exposition (EXPO 2005) will be held. The stations will service eight fuel cell buses used as pick-up buses for visitors. We, Engineering Advancement Association of Japan (ENAA), are commissioned to construct and operate a total of twelve stations by Ministry of Economy Trade and Industry (METI). We are executing to demonstrate or identify the energy-saving effect, reduction of the environmental footprint, and issues for facilitating the acceptance of hydrogen stations on the basis of the data obtained from the operation of the stations. (author)

  17. R and D and Innovation Needs for Decommissioning Nuclear Facilities

    International Nuclear Information System (INIS)

    Farr, Harvey; LaGuardia, Thomas S.

    2014-01-01

    Nuclear decommissioning activities can greatly benefit from research and development (R and D) projects. This report examines applicable emergent technologies, current research efforts and innovation needs to build a base of knowledge regarding the status of decommissioning technology and R and D. This base knowledge can be used to obtain consensus on future R and D that is worth funding. It can also assist in deciding how to collaborate and optimise the limited pool of financial resources available among NEA member countries for nuclear decommissioning R and D. (authors)

  18. Training for decommissioning

    International Nuclear Information System (INIS)

    Dietzold, A.

    2009-01-01

    Plants entering decommissioning face many challenges One of the most important is the challenge of training for decommissioning This is important because: The facility operators and management have spent many years successfully operating the facility; The facility management arrangements are geared to operation; Decommissioning will include non-nuclear specialists and other stakeholders; Other skills are needed to decommission successfully. UKAEA has decommissioned many facilities at its sites in Dounreay, Windscale, Harwell and Winfrith in the UK. We have faced all of the challenges previously described and have developed many training methods for ensuring the challenges are met safely and effectively. We have developed courses for specialised skills such as safety cases which can be deployed to support any decommissioning. (author)

  19. CECP, Decommissioning Costs for PWR and BWR

    International Nuclear Information System (INIS)

    Bierschbach, M.C.

    1997-01-01

    1 - Description of program or function: The Cost Estimating Computer Program CECP, designed for use on an IBM personal computer or equivalent, was developed for estimating the cost of decommissioning boiling water reactor (BWR) and light-water reactor (PWR) power stations to the point of license termination. 2 - Method of solution: Cost estimates include component, piping, and equipment removal costs; packaging costs; decontamination costs; transportation costs; burial volume and costs; and manpower staffing costs. Using equipment and consumables costs and inventory data supplied by the user, CECP calculates unit cost factors and then combines these factors with transportation and burial cost algorithms to produce a complete report of decommissioning costs. In addition to costs, CECP also calculates person-hours, crew-hours, and exposure person-hours associated with decommissioning. 3 - Restrictions on the complexity of the problem: The program is designed for a specific waste charge structure. The waste cost data structure cannot handle intermediate waste handlers or changes in the charge rate structures. The decommissioning of a reactor can be divided into 5 periods. 200 different items for special equipment costs are possible. The maximum amount for each special equipment item is 99,999,999$. You can support data for 10 buildings, 100 components each; ESTS1071/01: There are 65 components for 28 systems available to specify the contaminated systems costs (BWR). ESTS1071/02: There are 75 components for 25 systems available to specify the contaminated systems costs (PWR)

  20. The Practice of Cost Estimation for Decommissioning of Nuclear Facilities

    International Nuclear Information System (INIS)

    Davidova, Ivana; Desecures, Sylvain; Lexow, Thomas; Buonarroti, Stefano; Marini, Giuseppe; Pescatore, Claudio; Rehak, Ivan; Weber, Inge; ); Daniska, Vladimir; Linan, Jorge Borque; Caroll, Simon; Hedberg, Bjoern; De La Gardie, Fredrik; Haenggi, Hannes; Laguardia, Thomas S.; Ridpath, Andy

    2015-01-01

    Decommissioning of both commercial and R and D nuclear facilities is expected to increase significantly in the coming years, and the largest of such industrial decommissioning projects could command considerable budgets. Several approaches are currently being used for decommissioning cost estimations, with an international culture developing in the field. The present cost estimation practice guide was prepared in order to offer international actors specific guidance in preparing quality cost and schedule estimates to support detailed budgeting for the preparation of decommissioning plans, for the securing of funds and for decommissioning implementation. This guide is based on current practices and standards in a number of NEA member countries and aims to help consolidate the practice and process of decommissioning cost estimation so as to make it more widely understood. It offers a useful reference for the practitioner and for training programmes. The remainder of report is divided into the following chapters: - Chapter 2 covers the purpose and nature of decommissioning cost estimates, approaches to cost estimation and the major elements of a cost estimate. - Chapter 3 examines the development of the integrated schedule of the activity-dependent work scope and the determination of the project critical path. - Chapter 4 describes the attributes of a quality assurance programme applicable to cost estimation and the use and cautions of benchmarking the estimate from other estimates or actual costs. - Chapter 5 describes the pyramidal structure of the report, and the scope and content that should be included in the cost study report to ensure consistency and transparency in the estimate underpinnings. - Chapter 6 provides some observations, conclusions and recommendations on the use of this guide

  1. Electricite de France Strategy for its nuclear power plants' decommissioning programme

    International Nuclear Information System (INIS)

    Knockaert, J.M.; Gatineau, J.P.

    1992-01-01

    Although final shutdown of the first large PWR Power Stations should not occur before 2015, Electricity of France is nevertheless directly concerned by the decommissioning of its nuclear plants. The shutdown programme of the gas-graphite units is in progress and the medium-power PWR plant (300 MWe) installed at Chooz in the Ardennes will be finally shutdown at the end of 1991. This solution requires EDF to have a policy available which enables it to simultaneously run the double operation 'Plant shutdown-decommissioning' and 'New constructions-increasing available power' from both the technical and financial viewpoints. (author)

  2. Safe decommissioning of the Romanian VVR-S research reactor

    International Nuclear Information System (INIS)

    Garlea, C.; Garlea, I.; Kelerman, C.; Rodna, A.

    2002-01-01

    The VVR-S Romania research reactor was operated between 1957-1997, at 2 MW nominal power, for research and radioisotopical production. The detailed decommissioning plan was developed between 1995-1998, in the frame of the International Atomic Energy Agency Technical assistance project ROM/9/017. The proposed strategy agreed by the counterpart as well as international experts was stage 1. In 1997, an independent analysis performed by European Commission experts, in the frame of PHARE project PH04.1/1994 was dedicated to the 'Study of Soviet Design Research Reactors', had consolidated the development of the project emphasizing technical options of safe management for radioactive wastes and VVR-S spent fuel. The paper presents the main technical aspects as well as those of social impact, which lead to the establishment of strategy for safe management of decommissioning. Technical analysis of the VVR-S reactor and associated radwaste facilities (Radioactive Waste Treatment Plant - Magurele and National Repository Baita-Bihor) proved the possibility of the classical method utilization for dismantling of the facility and treatment-conditioning-disposal of the arrised wastes in safe conditions. The decommissioning plan at stage 2 has been developed based on radiological safety assessment, evaluation of radwaste inventory (removed as well as preserved on site), cost analysis and environmental impact. Technical data were provided by the R and D programme including neutron calculations and experiments, radiological characterizing (for facility and its influence area), seismic analysis and environmental balance during the operation and after shut down of the reactor. A special chapter is dedicated to regulatory issues concerning the development of decommissioning under nuclear safety. Based on the Fundamental Norms of Radiological Safety, the Regulatory Body defined the clearance levels and safety criteria for the process. The development of National Norms for the

  3. Progress and experiences from the decommissioning of the eurochemic reprocessing plant

    International Nuclear Information System (INIS)

    Gillis, R.; Lewandowski, P.; Ooms, B.; Reusen, N.; Van Laer, W.; Walthery, R.

    2008-01-01

    The Eurochemic reprocessing facility at Dessel in Belgium, was constructed from 1960 to 1966. After shutdown, the plant was decontaminated from 1975 to 1979 to keep safe standby conditions at reasonable cost. When it was decided in 1986 not to resume reprocessing in Belgium, the main Belgoprocess activities changed to processing and storage of radioactive waste and to decontamination and decommissioning of obsolete nuclear facilities. The industrial decommissioning was started in 1990. This document presents the project: overview of decommissioning activities and equipment used, automation in decontamination, ensuring health and safety during the operations, release of decontaminated materials, current situation of the decommissioning activities and quality assurance program. (A.L.B.)

  4. Chernobyl NPP decommissioning efforts - Past, Present and Future. Decommissioning Efforts on Chernobyl NPP site - Past, Present

    International Nuclear Information System (INIS)

    Kuchinskiy, V.

    2017-01-01

    Two unique large-scale projects are underway at the moment within the Chernobyl - Exclusion zone - Shelter object transformation into ecologically safe system and the decommissioning of 3 Chernobyl NPP Units. As a result of beyond design accident in 1986 the entire territory of the industrial site and facilities located on it was heavily contaminated. Priority measures were carried out at the damaged Unit under very difficult conditions to reduce the accident consequences and works to ensure nuclear and radiation safety are continuous, and the Unit four in 1986 was transformed into the Shelter object. Currently, works at the Shelter object are in progress. Under assistance of the International Community new protective construction was built above the existing Shelter object - New Safe Confinement, which will ensure the SO Safety for the long term - within up to 100 years. The second major project is the simultaneous decommissioning of Chernobyl NPP Units 1, 2 and 3. Currently existing Chernobyl NPP decommissioning Strategy has been continuously improved starting from the Concept of 1992. Over the years the following was analyzed and taken into account: the results of numerous research and development works, international experience in decommissioning, IAEA recommendations, comments and suggestions from the governmental and regulatory bodies in the fields of nuclear energy use and radioactive waste management. In 2008 the final decommissioning strategy option for Chernobyl NPP was approved, that was deferred gradual dismantling (SAFSTOR). In accordance with this strategy, decommissioning will be carried out in 3 stages (Final Shutdown and Preservation, Safe Enclosure, Dismantling). The SAFSTOR strategy stipulates: -) the preservation of the reactor, the primary circuit and the reactor compartment equipment; -) the dismantling of the equipment external in relation to the reactor; -) the safe enclosure (under the supervision); -) the gradual dismantling of the primary

  5. International co-operation on decommissioning - Achievements of the NEA Co-operative programme 1985-1990

    International Nuclear Information System (INIS)

    1992-01-01

    Decommissioning of nuclear facilities is attracting a growing interest in all countries where an increasing number of plants are reaching the end of their operational life and will have to be decommissioned in the next few years. In response to this interest, the NEA set up in 1985 an international programme of technical co-operation between decommissioning projects in eight OECD countries. This report describes the programme and the participating projects, reviews the experiences accumulated during the first five-year term of this international undertaking, and discusses what remains to be done

  6. Development and application of thermal cutting techniques during Phase 1 decommissioning of WAGR

    International Nuclear Information System (INIS)

    White, S.J.

    1992-01-01

    The Windscale Advanced Gas Cooled Reactor is the UK's lead Stage 3 Decommissioning Project. One of the main objectives of the project is to demonstrate that a nuclear reactor can be safely and effectively decommissioned to a greenfield site using existing technology. Techniques using thermal cutting processes are used widely in industry and have been successfully adapted and applied to the first phase of the dismantling project. Over 1000 operational cuts have been performed using plasma cutting technology. Oxypropane and thermic lancing technique have also been applied to the dismantling the Top Biological Shield and Top Dome of the reactor pressure vessel. This paper describes the development and application of these standard technologies to the task of decommissioning a nuclear reactor. (Author)

  7. Case study for a fit-to-purpose regulatory framework: the history and reasons for the evolution-in the French regulation regarding decommissioning

    International Nuclear Information System (INIS)

    Averous, J.; Chapalain, E.

    2005-01-01

    Full text: This paper exposes the regulatory approach for the safety of decommissioning in France, from an historical perspective. The first regulatory framework concerning decommissioning was introduced in the end of the 1980's and considered decommissioning as successive important modifications of the facility, which lead to multiple successive licenses. The first feedback from actual decommissioning projects lead the nuclear safety authority to reconsider the regulatory approach of decommissioning. The new approach privileges an integrated approach to the decommissioning projects, with an initial decommissioning license authorizing the complete project, and puts more weight on the responsibility of the licensee, fostering the organization of internal safety commissions which are allowed to authorize minor operations that do not put into question the global facility safety demonstration. This new regulatory approach was implemented in 2003 and new corresponding licensing procedures are already under way. It is thought that the new regulatory framework for decommissioning that has been introduced in 2003 will allow to regulate in a far more efficient way the decommissioning projects to come, while guarantying a high safety level, adapting the regulatory burden to the actual hazards, and allowing the licensee for the needed flexibility. Taking advantage of this new framework, licensees have already filed many decommissioning license applications, and decommissioning project licensing is currently one of the main tasks of the nuclear safety authority in France. Many such licenses, for all types of nuclear facilities, will be granted in the next few years. (authors)

  8. Health physics considerations in decontamination and decommissioning

    International Nuclear Information System (INIS)

    1985-12-01

    These proceedings contain papers on legal considerations, environmental aspects, decommissioning equipment and methods, instrumentation, applied health physics, waste classification and disposal, and project experience. Separate abstracts have been prepared for individual papers

  9. Technology, safety, and costs of decommissioning a reference nuclear fuel reprocessing plant

    International Nuclear Information System (INIS)

    Schneider, K.J.; Jenkins, C.E.; Rhoads, R.E.

    1977-09-01

    Safety and cost information were developed for the conceptual decommissioning of a fuel reprocessing plant with characteristics similar to the Barnwell Nuclear Fuel Plant. The main process building, spent fuel receiving and storage station, liquid radioactive waste storage tank system, and a conceptual high-level waste-solidification facility were postulated to be decommissioned. The plant was conceptually decommissioned to three decommissioning states or modes; layaway, protective storage, and dismantlement. Assuming favorable work performance, the elapsed time required to perform the decommissioning work in each mode following plant shutdown was estimated to be 2.4 years for layaway, 2.7 years for protective storage, and 5.2 years for dismantlement. In addition to these times, approximately 2 years of planning and preparation are required before plant shutdown. Costs, in constant 1975 dollars, for decommissioning were estimated to be $18 million for layaway, $19 million for protective storage and $58 million for dismantlement. Maintenance and surveillance costs were estimated to be $680,000 per year after layaway and $140,000 per year after protective storage. The combination mode of protective storage followed by dismantlement deferred for 10, 30, and 100 years was estimated to cost $64 million, $67 million and $77 million, respectively, in nondiscounted total 1975 dollars. Present values of these costs give reduced costs as dismantlement is deferred. Safety analyses indicate that radiological and nonradiological safety impacts from decommissioning activities should be small. The 50-year radiation dose commitment to the members of the public from airborne releases from normal decommissioning activities were estimated to be less than 11 man-rem

  10. Technology, safety, and costs of decommissioning a reference nuclear fuel reprocessing plant

    Energy Technology Data Exchange (ETDEWEB)

    Schneider, K.J.; Jenkins, C.E.; Rhoads, R.E.

    1977-09-01

    Safety and cost information were developed for the conceptual decommissioning of a fuel reprocessing plant with characteristics similar to the Barnwell Nuclear Fuel Plant. The main process building, spent fuel receiving and storage station, liquid radioactive waste storage tank system, and a conceptual high-level waste-solidification facility were postulated to be decommissioned. The plant was conceptually decommissioned to three decommissioning states or modes; layaway, protective storage, and dismantlement. Assuming favorable work performance, the elapsed time required to perform the decommissioning work in each mode following plant shutdown was estimated to be 2.4 years for layaway, 2.7 years for protective storage, and 5.2 years for dismantlement. In addition to these times, approximately 2 years of planning and preparation are required before plant shutdown. Costs, in constant 1975 dollars, for decommissioning were estimated to be $18 million for layaway, $19 million for protective storage and $58 million for dismantlement. Maintenance and surveillance costs were estimated to be $680,000 per year after layaway and $140,000 per year after protective storage. The combination mode of protective storage followed by dismantlement deferred for 10, 30, and 100 years was estimated to cost $64 million, $67 million and $77 million, respectively, in nondiscounted total 1975 dollars. Present values of these costs give reduced costs as dismantlement is deferred. Safety analyses indicate that radiological and nonradiological safety impacts from decommissioning activities should be small. The 50-year radiation dose commitment to the members of the public from airborne releases from normal decommissioning activities were estimated to be less than 11 man-rem.

  11. Management of the decommissioning of the Thetis reactor

    Energy Technology Data Exchange (ETDEWEB)

    Ooms, Luc; Maris, Patrick; Noynaert, Luc [SCK-CEN, Mol (Belgium)

    2013-07-01

    decommissioning job. We gained the decommissioning license in May 2012. We also prepared the software tool allowing managing the decommissioning project by updating the inventory and recording the progress, the characterization measurements and the material and waste production. This software allows also to trace all the material streams and to report to the Authorities. This software is a simplified release of the ones developed by SCK-CEN in the framework of other decommissioning projects like BR3 and Belgonucleaire. The dismantling of the reactor i.e. reactor pool, circuits and rabbit system, will be performed in 2013. In 2014, it is planned to map all the surfaces of the infrastructure to highlight residual contamination of floor, walls and ceiling. The contaminated surfaces will be decontaminated and controlled. The objective is to reach the free release of the reactor building and laboratories by the end of 2014. (authors)

  12. WPDD workshop on: 'safe, efficient, and cost-effective decommissioning'. Workshop Conclusions/Final Stocktaking

    International Nuclear Information System (INIS)

    2005-01-01

    On September 6-10, 2004 a workshop on 'Safe, Efficient, and Cost-Effective Decommissioning' was held in Rome (Italy) to enable international experts on decommissioning to compare and evaluate respective approaches and experiences in decommissioning nuclear power and fuel cycle facilities and to formulate proposals for future international cooperation in the decommissioning arena. The main messages emerging from the workshop are: - Decommissioning is a mature industrial process and many projects have been safely completed with support of local communities. Technical and scientific issues are well-understood and practical experience and associated lessons are being documented to guide future activities. Emphasis is being placed on effective planning with active programmes of community involvement. - Individual countries need to further develop integrated decommissioning and waste management strategies to ensure that long-term solutions will be available for all wastes generated from decommissioning. National systems are evolving to meet national needs, against a framework provided by the international organisations, and these seem increasingly to favour early dismantling regardless of the availability of waste disposal routes. - Realistic and streamlined regulatory programmes are being developed with feed back from industry experience and are placing more responsibility and accountability on licensees. - Accurate decommissioning waste cost calculation methods is needed. Waste volumes may vary from project to project even for similar installations. There though appears to be a strong case for accumulating data and benchmarking costs for similar plants and processes. Further work and experience exchange on cost comparisons between different strategies (for example clearance and recycling/reuse of materials versus direct surface disposal) would be valuable. - International clearance criteria have been established, with individual countries free to adopt them

  13. Proceedings of the International Symposium on Preparation for Decommissioning - PREDEC 2016

    International Nuclear Information System (INIS)

    2016-02-01

    The objective of the PREDEC 2016 symposium is to share current practice, experiences and innovations relating to the preparations for decommissioning of nuclear facilities. The symposium will be a forum to: Learn about current practices, Highlight strategic issues related to radiological characterisation and decommissioning, Exchange experiences, Discuss innovative and new techniques and needs for improvements, Develop and maintain networks in the area of radiological characterisation. Seven sessions in total were scheduled with the following topics: 1. Preparation for decommissioning - strategic issues: Preparation for decommissioning requires several strategic decisions with significant impact on the activities. This session covers a wide span of strategic issues such as: Immediate vs. deferred dismantling, Timing and strategic approach for the decommissioning preparations, Prioritised strategic decisions in case of a non-scheduled final shutdown. 2. Early characterisation challenges: There are significant advantages with an early characterisation of a facility to be decommissioned but an early characterisation is faced with constraints, limitations and challenges. The session is open for all approaches and strategies for early characterisation issues, including facility characterisation using theoretical models. 3. Workforce transition, flexibility and knowledge management: The transition from normal operation to facility dismantling involves several important evaluations, decisions and actions. This session covers project organisation issues like: Dismantling by former operators or by specialised teams, Concepts for how the transition could be structured to secure that the required knowledge is kept within the organisation, Ways to achieve the required workforce flexibility for a cost efficient decommissioning project. 4. Key aspects for efficient and cost effective waste management: This session covers activities in the preparation phase that supports an

  14. The use of managing agencies in decommissioning

    International Nuclear Information System (INIS)

    Nelson, R.L.

    1994-01-01

    On 1 April 1994 UKAEA Government Division was formed and one of its main responsibilities is the safe and cost effective management of the facilities which have already closed and the fuel reprocessing and radioactive waste management plant required to assist in the current programme of decommissioning. UKAEA Government Division, working on behalf of DTI, is intended to be a lean and efficient programme management and procurement organisation. Rather than build up its own project management capability it intends to use external resources for this function, obtained in future by competitive tendering. For each major facility undergoing decommissioning a Managing Agency has been, or will be, appointed to act on behalf of UKAEA Government Division. The responsibilities of each Managing Agency will be to assist in the definition of tasks, the commissioning of option studies and safety studies, the specification of individual contracts, management of the tendering processes and the subsequent management of the Implementation Contractors carrying out the decommissioning work, including the associated safety and training responsibilities. Teams involved in Managing Agency work require skills in project management, relevant technical issues, contract and safety management. (author)

  15. Decommissioning of nuclear facilities in Korea

    International Nuclear Information System (INIS)

    Hahn, Pil Soo

    2003-01-01

    In 1996, it was concluded that the first Korea research reactor (KRR-1) and the second Korea research reactor (KRR-2) would be shut down and decommissioned. The main reason for the decommissioning was that the facilities became old and has become surrounded by the urbanised community. And many difficulties, including the higher cost, were faced according to the enhanced regulations. Another reason was the introduction of a new research reactor 'HANARO' in 1995. A project to decommission the reactors was launched on January of 1997 with a goal of release of the site and buildings for unrestricted use by 2008. All the radioactive wastes generated are to be transported to the national repository, planned by the Korea Hydro and Nuclear Power Company (KHNP), and the final evaluation of the residual radioactivity will be made before the clearance of the site. As a first step of the project, a decommissioning plan, including the assessment of the environmental impact and the quality assurance program, was prepared and submitted to the government in 1998. It was approved, after its safety evaluation, by the Korea Institute of Nuclear Safety (KINS) in November of 2000. After some preparative works such as documentation of procedures, the decontamination and dismantling works for the laboratories and hot cells of KRR-2 were started in September, 2001 and finished in December, 2002. The spent fuels that had been generated from the reactors were transferred to the United States in 1998 and no spent fuel remained at the site. All the liquid waste, both operational and decommissioning, was very low in its radioactivity and was treated in a natural evaporation facility of 200 m3/year capacity, developed by KAERI. Especially the laundry waste was treated in a membrane filtering unit for the removal of surfactants before being introduced to the natural evaporator. The solid wastes were segregated and packed in the container of 4 m3, designed according to the ISO-1496, and also in

  16. Idaho National Engineering Laboratory decontamination and decommissioning summary

    International Nuclear Information System (INIS)

    Chapin, J.A.

    1981-01-01

    Topics covered concern the decontamination and decommissioning (D and D) work performed at the Idaho National Engineering Laboratory (INEL) during FY 1979 and include both operations and development projects. Briefly presented are the different types of D and D projects planned and the D and D projects completed. The problems encountered on these projects and the development program recommended are discussed

  17. Funding Decommissioning - UK Experience

    International Nuclear Information System (INIS)

    MacKerron, Gordon

    2006-01-01

    'Funding' started with CEGB and SSEB (state-owned electric utilities) in 1976 using the internal un-segregated fund route (i.e unfunded). This continued until privatisation of electricity industry (excluding nuclear) in 1990. Assets bought with the internal un-segregated fund were mostly transferred into non-nuclear private utilities. New state-owned Nuclear Electric (England and Wales) was given a 'Fossil Fuel Levy', a consumer charge of 10% on retail bills, amounting to c. BP 1 bn. annually. This allowed Nuclear Electric to trade legally (A reserve of BP 2.5 bn. was available from Government if company ran out of money). By 1996 the newer nuclear stations (AGRS plus PWR) were privatised as British Energy. British Energy started an external segregated fund, the Nuclear Decommissioning Fund, with a starting endowment of c. BP 225 m. - and BE made annual contributions of British Pound 16 m. into the Fund. Assumptions were that BE had 70 to accumulate cash and could get a 3.5% average annual real return. Older stations (Magnox) were left in private sector and went to BNFL in 1997. Magnox inherited the surplus cash in BE - mostly unspent Fossil Fuel Levy receipts - of c. BP 2.6 bn. Government gave an 'Undertaking' to pay BP 3.8 bn. (escalating at 4.5% real annually) for Magnox liabilities, should Magnox Electric run out of cash. BNFL inherited the BP 2.6 bn. and by 2000 had a 'Nuclear Liabilities Investment Portfolio' of c. BP 4 bn. This was a quasi-segregated internal fund for liabilities in general. [Note: overall UK nuclear liabilities in civilian sector were running at c. BP 48 bn. by now]. BE started profitable and paid BP 100 m. annually in dividends to private investors for several years. BE ran into severe financial problems after 2001 and Government organised restructuring aid, now approved by European Commission. Terms include: - BE now to contribute BP 20 m. a year into an expanded Nuclear Liabilities Fund; - A bond issue of BP 275 m. to go to Fund; - 65

  18. Uranium mill decommissioning - an update on the Edgemont experience

    International Nuclear Information System (INIS)

    Donovan, Th.K.; Chart, E.J.; Cummings, G.W.; Tappan, J.T.

    1983-01-01

    This paper describes the Edgemont Uranium Mill Decommissioning Project. An estimated 5.4 million tons of contaminated material including approximately 2.5 million tons of uranium mill tailings will be moved to a disposal site approved by the Nuclear Regulatory Commission (NRC). The decommissioning activities will be carried out by Silver King Mines, Inc., under a management services contract to the Tennessee Valley Authority. The primary advantages of the disposal site chosen are the short distance from the existing site and the approximately 650 feet of relatively dense impermeable shales above the shallowest known aquifer. Three large ore stockpiles containing about 100,000 pounds of uranium have been moved from the mill site to a proposed mine site. The decommissioning project will be carried out by using the existing labor force to the maximum extent possible thus preventing a population influx and the accompanying socioeconomic input to the city of Edgemont, SD

  19. The Role of Stakeholders in the Decommissioning of Salaspils Research Reactor

    International Nuclear Information System (INIS)

    Abramenkovs, A.

    2009-01-01

    The paper describes the role of different stakeholders in the decommissioning of the Salaspils Research Reactor. Decommissioning was a large challenge for the Latvia, since the country in this moment had no decommissioning experience and necessary technologies for the implementation of the defined goals by the Government. In this case for facilitation of the decommissioning of Salaspils Research Reactor (SRR), the significant role plays the local and international stakeholders. The paper deals with information on the basic stages of decommissioning of SRR and the role of the wide spectrum of stakeholders in preparation, upgrade and implementation of the decommissioning plan. The role of governmental institutions in the decommissioning of Salaspils research reactor is discussed. It was shown, that local municipalities are very important stakeholders, which significantly influence the decommissioning of SRR. The Salaspils municipalities positive impact on the decommissioning processes are discussed. Basic problems with the Baldone municipality in context of radioactive wastes management are indicated. The role of international stakeholders in decommissioning of Salaspils research reactor is discussed. It was shown, that the support from International Atomic Energy Agency significantly promotes the decommissioning of SRR. The main issues were expert support for solution of different technical problems in radioactive wastes management, area monitoring, and verification of decommissioning plans, training of staff and technical expertise during whole process of decommissioning. It was shown, that technical and economical support from DOE, USA provides the possibility to solve the fuel problem during decommissioning of SRR, as well as, to increase the physical safety of SRR and repository 'Radons'. It was shown, that a proper coordination of all activities and using the services from stakeholders can significantly reduce the total project expenses. The cooperation between

  20. Radiological Characterisation for Decommissioning of Nuclear Installations - Final Report of the Task Group on Radiological Characterisation and Decommissioning (RCD) of the Working Party on Decommissioning and Dismantling (WPDD) - Final Report, September 2013

    International Nuclear Information System (INIS)

    Andrieu, Caroline; Olivier Dehaye, Catherine; Tardy, Frederic; Boisserie, Thierry; Desnoyers, Yvon; Thierfeldt, Stefan; Martin, Nieves; Henrik Efraimsson; Haakansson, Lars; Larsson, Arne; Dunlop, Alister A.; Jarman, Sean; Orr, Peter; Abu-Eid, Boby

    2013-01-01

    Radiological characterisation plays an important role in the decommissioning of nuclear facilities. It is the basis for radiation protection, identification of contamination, assessment of potential risks, cost estimation, planning and implementation of decommissioning and other matters. At all stages of a decommissioning project, adequate radiological characterisation is of crucial importance. The focus of this report is the task of radiological characterisation. The important role and the significance of radiological characterisation become clear when its various objectives are considered, including in particular: - determination of the type, isotopic composition and extent of contamination in structures, systems, components and environmental media; - identification of the nature and extent of remedial actions and decontamination; - supporting planning of decommissioning; - estimation of decommissioning costs. A large number of measurement techniques are available for successful application of radiological characterisation, allowing rapid and comprehensive determination of the activities of most relevant radionuclides. For other radionuclides that are hard to detect, scaling factors can be established that relate their activities to key nuclides. Radiological characterisation is relevant in all phases of the life cycle of a nuclear installation, albeit with different levels of detail and with differing objectives. Basically, the following characterisation phases can be distinguished: pre-operational characterisation; characterisation during operation; characterisation during the transition phase (after final shutdown before initiation of dismantling); characterisation during dismantling (including remediation and decontamination); and characterisation to support the final status survey for site release. The most comprehensive characterisation campaigns are usually carried out during the transition phase in preparation for implementation of dismantling activities

  1. Research reactor decommissioning experience - concrete removal and disposal -

    International Nuclear Information System (INIS)

    Manning, Mark R.; Gardner, Frederick W.

    1990-01-01

    Removal and disposal of neutron activated concrete from biological shields is the most significant operational task associated with research reactor decommissioning. During the period of 1985 thru 1989 Chem-Nuclear Systems, Inc. was the prime contractor for complete dismantlement and decommissioning of the Northrop TRIGA Mark F, the Virginia Tech Argonaut, and the Michigan State University TRIGA Mark I Reactor Facilities. This paper discusses operational requirements, methods employed, and results of the concrete removal, packaging, transport and disposal operations for these (3) research reactor decommissioning projects. Methods employed for each are compared. Disposal of concrete above and below regulatory release limits for unrestricted use are discussed. This study concludes that activated reactor biological shield concrete can be safely removed and buried under current regulations

  2. Decommissioning of the Tokamak Fusion Test Reactor

    International Nuclear Information System (INIS)

    Perry, E.; Chrzanowski, J.; Gentile, C.; Parsells, R.; Rule, K.; Strykowsky, R.; Viola, M.

    2003-01-01

    The Tokamak Fusion Test Reactor (TFTR) at the Princeton Plasma Physics Laboratory was operated from 1982 until 1997. The last several years included operations with mixtures of deuterium and tritium. In September 2002, the three year Decontamination and Decommissioning (D and D) Project for TFTR was successfully completed. The need to deal with tritium contamination as well as activated materials led to the adaptation of many techniques from the maintenance work during TFTR operations to the D and D effort. In addition, techniques from the decommissioning of fission reactors were adapted to the D and D of TFTR and several new technologies, most notably the development of a diamond wire cutting process for complex metal structures, were developed. These techniques, along with a project management system that closely linked the field crews to the engineering staff who developed the techniques and procedures via a Work Control Center, resulted in a project that was completed safely, on time, and well below budget

  3. Development of decommissioning, decontamination and reuse technology for nuclear facilities

    International Nuclear Information System (INIS)

    Lee, K. W.; Moon, J. K.; Choi, B. S.

    2012-03-01

    In this project, the foundation of decommissioning technology through the development of core technologies applied to maintenance and decommissioning of nuclear facility was established. First of all, we developed the key technology such as safety assessment technology for decommissioning work needed at the preparatory stage of decommissioning of the highly contaminated facilities and simultaneous measurement technology of the high-level alpha/beta contamination applicable to the operation and decommissioning of the nuclear facilities. Second, we developed a remotely controlled laser ablation decontamination system which is useful for a removal of fixed contaminants and developed a chemical gel decontamination technology for a removal of non-fixed contaminants during the maintenance and decommissioning works of high radiation hot cells which have been used for a recycling or treatment of spent fuels. Third, we developed a volume reduction and self-disposal technology for dismantled concrete wastes. Also, the technology for volume reduction and stabilization of the peculiar wastes(HEPA filter and organic mixed wastes), which have been known to be very difficult to treat and manage, generated from the high radioactive facilities in operation, improvement and repair and under decommissioning was developed. Finally, this research project was developed a system for the reduction of radiotoxicity of several uranium mixtures generated in the front- and back-end nuclear fuel cycles with characteristics of highly enhanced proliferation-resistance and more environmental friendliness, which can make the uranium to be recovered or separated from the mixtures with a high purity level enough for the uranium to be reused and to be classified as C-class level for burial near the surface, and then which result in the much reduction in volume of the uranium mixture wastes

  4. Environmental assessment for Mound Plant decontamination and decommissioning projects, Mound Plant, Miamisburg, Ohio

    International Nuclear Information System (INIS)

    1995-05-01

    The U.S. Department of Energy (DOE) has prepared an Environmental Assessment (EA) for seven decontamination and decommissioning (D ampersand D) projects at the Mound Plant in Miamisburg, Ohio, that have not been previously addressed in the Final Environmental Impact Statement for the Mound Facility (June 1979). Based on the information presented in the EA, the DOE has determined that the proposed action is not a major Federal action significantly affecting the quality of the human environment within the meaning of the National Environmental Policy Act (NEPA) of 1969. Therefore, the preparation of an Environmental Impact Statement (EIS) is not required and the Department is issuing this Finding of No Significant Impact (FONSI)

  5. Decommissioning of reactor facilities (2). Required technology

    International Nuclear Information System (INIS)

    Yanagihara, Satoshi

    2014-01-01

    Decommissioning of reactor facilities was planned to perform progressive dismantling, decontamination and radioactive waste disposal with combination of required technology in a safe and economic way. This article outlined required technology for decommissioning as follows: (1) evaluation of kinds and amounts of residual radioactivity of reactor facilities with calculation and measurement, (2) decontamination technology of metal components and concrete structures so as to reduce worker's exposure and production of radioactive wastes during dismantling, (3) dismantling technology of metal components and concrete structures such as plasma arc cutting, band saw cutting and controlled demolition with mostly remote control operation, (3) radioactive waste disposal for volume reduction and reuse, and (4) project management of decommissioning for safe and rational work to secure reduction of worker's exposure and prevent the spreading of contamination. (T. Tanaka)

  6. Development of a digital mock-up system for selecting a decommissioning scenario

    International Nuclear Information System (INIS)

    Kim, Sung-Kyun; Park, Hee-Sung; Lee, Kune-Woo; Jung, Chong-Hun

    2006-01-01

    The evaluation of decommissioning scenarios is critical to the successful development and execution of a decommissioning project. In the past, many experts have used a physical mock-up system to find the exact work processes and the working positions. Nowadays, these jobs are being done by a Digital Mock-Up (DMU) system. The DMU, which is a technology to realize an effective work process by using virtual environments through representing the physical and logical schema and the behavior of a real decommissioning work, can save on the cost and time, reduce the risk of making later changes, and develop various decommissioning scenarios. In this research, a decommissioning DMU system was developed for simulating the relevant dismantling processes. Decommissioning data-computing modules which can calculate a dismantling schedule, quantify a radioactive waste, visualize a radioactive inventory, estimate a decommissioning cost, and estimate a worker's exposure were also developed to qualitatively assess the decommissioning information. And an analytic hierarchy process (AHP) model was developed to evaluate the decommissioning scenarios which reflected the quantitative and qualitative considerations. To establish the proper scenario for the thermal column in KRR-1, the developed decommissioning DMU system was applied to evaluate the two candidate scenarios of it

  7. Decommissioning of surplus facilities at Los Alamos National Laboratory

    International Nuclear Information System (INIS)

    Stout, D.S.

    1995-01-01

    Decommissioning Buildings 3 and 4 South at Technical Area 21, Los Alamos National Laboratory, involves the decontamination, dismantlement, and demolition of two enriched-uranium processing buildings containing process equipment and ductwork holdup. The Laboratory has adopted two successful management strategies to implement this project: Rather than characterize an entire site, upfront, investigators use the ''observational approach,'' in which they collect only enough data to begin decommissioning activities and then determine appropriate procedures for further characterization as the work progresses. Project leaders augment work packages with task hazard analyses to fully define specific tasks and inform workers of hazards; all daily work activities are governed by specific work procedures and hazard analyses

  8. Technology demonstrations in the Decontamination and Decommissioning Focus Area

    International Nuclear Information System (INIS)

    Bossart, S.J.

    1996-01-01

    This paper describes three large-scale demonstration projects sponsored jointly by the Decontamination and Decommissioning Focus Area (DDFA), and the three US Department of Energy (DOE) Operations Offices that successfully offered to deactivate or decommission (D ampersand D) one of its facilities using a combination of innovative and commercial D ampersand D technologies. The paper also includes discussions on recent technology demonstrations for an Advanced Worker Protection System, an Electrohydraulic Scabbling System, and a Pipe Explorer trademark. The references at the conclusion of this paper should be consulted for more detailed information about the large-scale demonstration projects and recent technology demonstrations sponsored by the DDFA

  9. Decommissioning nuclear facilities

    International Nuclear Information System (INIS)

    Harmon, K.M.; Jenkins, C.E.; Waite, D.A.; Brooksbank, R.E.; Lunis, B.C.; Nemec, J.F.

    1976-01-01

    This paper describes the currently accepted alternatives for decommissioning retired light water reactor fuel cycle facilities and the current state of decommissioning technology. Three alternatives are recognized: Protective Storage; Entombment; and Dismantling. Application of these alternatives to the following types of facilities is briefly described: light water reactors; fuel reprocessing plants, and mixed oxide fuel fabrication plants. Brief descriptions are given of decommissioning operations and results at a number of sites, and recent studies of the future decommissioning of prototype fuel cycle facilities are reviewed. An overview is provided of the types of operations performed and tools used in common decontamination and decommissioning techniques and needs for improved technology are suggested. Planning for decommissioning a nuclear facility is dependent upon the maximum permitted levels of residual radioactive contamination. Proposed guides and recently developed methodology for development of site release criteria are reviewed. 21 fig, 32 references

  10. Decommissioning of NPP A1 - HWGCR type

    International Nuclear Information System (INIS)

    Burclova, J.

    1998-01-01

    Prototype nuclear power plant A-1 located at Jaslovske Bohunice, was a HWGCR with channel type reactor KS 150 (refuelling during operation) and capacity of 143 MWe. Single unit has been constructed with reactor hall building containing reactor vessel, heavy water system and equipment for spent fuel handling. Another compartment of main building contents coolant system piping, six steam generators and six turbo compressors, the turbine hall was equipped by three turbines. Unit also shares liquid radwaste treatment and storage buildings and ventilation systems including chimney. It started operation in 1972 and was shutdown in 1977 after primary coolant system integrity accident. In 1979 a final decision was made to decommission this plant. The absence of waste treatment technologies and repository and not sufficient storage capacity affected the planning and realization of decommissioning for NPP A-1. The decommissioning policy for the first stage is for lack of regulations based on 'case by case' strategy. For these reasons and for not existence of Decommissioning Found until 1995 the preferred decommissioning option is based on differed decommissioning with safe enclosure of confinement. Transfer of undamaged spent fuel cooled in organic coolant to Russia was finished in 1990. It was necessary to develop new technology for the damaged fuel preparation for transport. The barriers check-up and dismantling of secondary circuit and cooling towers was performed during 1989/90. The complex plan for the first phase of A-1 decommissioning - the status with treated operational radwaste, removed contamination and restored treated waste and spent fuel (in case of interruption of transfer to Russia) was developed in 1993-1994. Under this project bituminization of all liquid operational radwaste (concentrates) was performed during 1995/96, vitrification of inorganic spent fuel coolant started at 1996, decontamination of spent fuel pool coolant occurs (under AEA Technology

  11. Decommissioning of DR 2. Experiences learnt from the completion

    International Nuclear Information System (INIS)

    Strufe, N.

    2009-10-01

    The report describes experiences gathered from the decommissioning of DR 2. The experiences encompasses planning and management of the project, methods of accomplishment, and various materials categories. Additionally, the report describes the experience with specific tools used in the project

  12. Waste management strategy for cost effective and environmentally friendly NPP decommissioning

    Energy Technology Data Exchange (ETDEWEB)

    Per Lidar; Arne Larsson [Studsvik Nuclear AB (ndcon partner), Nykoping (Sweden); Niklas Bergh; Gunnar Hedin [Westinghouse Electric Sweden AB (ndcon partner), Vasteraas (Sweden)

    2013-07-01

    -necks in the process causes increased space requirements and will have negative impact on the project schedule, which increases not only the cost but also the dose exposure to personnel. For these reasons it is critical to create a process that transfers material into conditioned waste ready for disposal as quickly as possible. To a certain extent the decommissioning program should be led by the waste management process. With the objective to reduce time for handling of dismantled material at site and to efficiently and environmental-friendly use waste management methods (clearance for re-use followed by clearance for recycling), the costs for the plant decommissioning could be reduced as well as time needed for performing the decommissioning project. Also, risks for delays would be reduced with a well-defined handling scheme which limits surprises. Delays are a major cost driver for decommissioning projects. (authors)

  13. Waste management strategy for cost effective and environmentally friendly NPP decommissioning

    International Nuclear Information System (INIS)

    Per Lidar; Arne Larsson; Niklas Bergh; Gunnar Hedin

    2013-01-01

    -necks in the process causes increased space requirements and will have negative impact on the project schedule, which increases not only the cost but also the dose exposure to personnel. For these reasons it is critical to create a process that transfers material into conditioned waste ready for disposal as quickly as possible. To a certain extent the decommissioning program should be led by the waste management process. With the objective to reduce time for handling of dismantled material at site and to efficiently and environmental-friendly use waste management methods (clearance for re-use followed by clearance for recycling), the costs for the plant decommissioning could be reduced as well as time needed for performing the decommissioning project. Also, risks for delays would be reduced with a well-defined handling scheme which limits surprises. Delays are a major cost driver for decommissioning projects. (authors)

  14. DASAO: software tool for the management of safeguards, waste and decommissioning

    International Nuclear Information System (INIS)

    Noynaert, Luc; Verwaest, Isi; Libon, Henri; Cuchet, Jean-Marie

    2013-01-01

    Decommissioning of nuclear facilities is a complex process involving operations such as detailed surveys, decontamination and dismantling of equipment's, demolition of buildings and management of resulting waste and nuclear materials if any. This process takes place in a well-developed legal framework and is controlled and followed-up by stakeholders like the Safety Authority, the Radwaste management Agency and the Safeguards Organism. In the framework of its nuclear waste and decommissioning program and more specifically the decommissioning of the BR3 reactor, SCK-CEN has developed different software tools to secure the waste and material traceability, to support the sound management of the decommissioning project and to facilitate the control and the follow-up by the stakeholders. In the case of Belgium, it concerns the Federal Agency for Nuclear Control, the National Agency for radioactive waste management and fissile material and EURATOM and IAEA. In 2005, Belgonucleaire decided to shutdown her Dessel MOX fuel fabrication plant and the production stopped in 2006. According to the final decommissioning plan ('PDF') approved by NIRAS, the decommissioning works should start in 2008 at the earliest. In 2006, the management of Belgonucleaire identified the need for an integrated database and decided to entrust SCK-CEN with its development, because SCK-CEN relies on previous experience in comparable applications namely already approved by authorities such as NIRAS, FANC and EURATOM. The main objectives of this integrated software tool are: - simplified and updated safeguards; - waste and material traceability; - computerized documentation; - support to project management; - periodic and final reporting to waste and safety authorities. The software called DASAO (Database for Safeguards, Waste and Decommissioning) was successfully commissioned in 2008 and extensively used from 2009 to the satisfaction of Belgonucleaire and the stakeholders. SCK-CEN is

  15. Using virtual reality technology for the planning of decommissioning of Fugen NPS

    International Nuclear Information System (INIS)

    Iguchi, Yukihiro; Sundling, Carl-Victor

    1999-01-01

    Fugen is a 165 MWe, heavy water moderated, light-water cooled, pressure-tube type reactor, which started the commercial operation in 1979. The operation of the plant will end by March 2003 and the tasks of decommissioning will start under the policy of the Japanese government. The basic requirement shows the Fugen Decommissioning Project (FDP) should be transparent with sharing international and domestic experience and knowledge, rational using existing technologies, economical with detailed waste evaluation, environmentally friendly by resource recycling and beneficial for local community. Based on the requirements, we have started the planning of decommissioning and found that the collection of sufficient data concerning the plant such as radioactivity inventory and weight of the material is important and optimization of the plan is necessary for the cost reduction. On the other hand, based on the experience of the decommissioning of Japan Power Demonstration Reactor (JPDR), Japan Atomic Energy Research Institute (JAERI) developed the Code System for Management of Reactor Decommissioning (COSMARD), which evaluates project management data such as costs, manpower needs, radiation exposure to workers and waste mass based on the plant data and experienced data concerning the decommissioning in the past. COSMARD is used commonly in Japan and contributes to the optimization of the decommissioning planning including the commercial reactors. The progress of the Virtual Reality (VR) technology shows new possibility of the planning of decommissioning. For example, the simulation of the dismantling process with special devices in the high radiation area is possible with the VR technique. The estimation of radiation exposure of workers may be another target for the VR system with human behavior (author) (ml)

  16. BNFL nuclear decommissioning liabilities management program

    International Nuclear Information System (INIS)

    Colquhoun, A.P.

    1995-01-01

    The objective of this paper is to describe BNFL's policy and strategy for decommissioning and also to summarize the overall scope of nuclear liabilities in the wider field of waste retrieval and storage, as well as the dismantling and demolition aspects of decommissioning. BNFL's recently established organisational arrangements for discharging all types of these liabilities are explained, together with a review of practical progress in dealing with them. Organisational changes in recent years have amalgamated decommissioning work with operations covering waste storage and retrieval operations. A strategy of minimising residual activity in shutdown plants is pursued, followed by dismantling and demolition on appropriate time scales to minimise risk and cost. Since April 1995, a new BNFL subsidiary, Nuclear Liabilities Management Company Limited has taken responsibility for discharge of BNFL's Waste Retrieval and Decommissioning liabilities on all BNFL sites. NLM has the objectives of optimal and lowest cost management of liabilities and much clearer segregation of physical operations from project specification and planning. The Ministry of Defense (MoD) policy, strategy, work programmes and progress for the Atomic Weapons Establishment (AWE) are also outlined. MoD/AEA has established an equivalent strategy for dealing with its liabilities. (J.S.). 5 refs., 2 figs., 4 appends

  17. Environmental impact assessment of decommissioning treatment about radioactive model plant waste ore storage site

    International Nuclear Information System (INIS)

    Bei Xinyu

    2012-01-01

    Aiming at decommissioning treatment project of radioactive model plant waste ore storage site, based on the detailed investigations of source terms and project description, systematic environmental impacts have been identified. The environmental impacts both during decommissioning treatment, radioactive waste transportation and after treatment are assessed. Some specific environmental protection measures are proposed so as to minimize the adverse environmental impacts. (author)

  18. Fiscal year 1996 decontamination and decommissioning activities photobriefing book for the Argonne National Laboratory-East Site, Technology Development Division, Waste Management Program, Decontamination and Decommissioning Projects Department

    International Nuclear Information System (INIS)

    1996-01-01

    The Photobriefing Book describes the Decontamination and Decommissioning (D and D) Program at the Argonne National Laboratory-East Site (ANL-E) near Lemont, Illinois. This book summarizes current D and D projects, reviews fiscal year (FY) 1996 accomplishments, and outlines FY 1997 goals. A section on D and D Technology Development provides insight on new technologies for D and D developed or demonstrated at ANL-E. Past projects are recapped and upcoming projects are described as Argonne works to accomplish its commitment to, ''Close the Circle on the Splitting of the Atom.'' Finally, a comprehensive review of the status and goals of the D and D Program is provided to give a snap-shot view of the program and the direction it's taking as it moves into FY 1997. The D and D projects completed to date include: Plutonium Fuel Fabrication Facility; East Area Surplus Facilities; Experimental Boiling Water Reactor; M-Wing Hot Cell Facilities; Plutonium Gloveboxes; and Fast Neutron Generator

  19. International intercomparison and harmonization projects for demonstrating the safety of radioactive waste management, decommissioning and radioactive waste disposal

    International Nuclear Information System (INIS)

    Metcalf, Phil; O'Donnell, Patricio; Jova Sed, Luis; Batandjieva, Borislava; Rowat, John; Kinker, Monica

    2008-01-01

    Full text: The Joint Convention on the safety of spent fuel management and the safety of radioactive waste management and the international safety standards on radioactive waste management, decommissioning and radioactive waste disposal call for assessment and demonstration of the safety of facilities and activities; during siting, design and construction prior to operation, periodically during operation and at the end of lifetime or upon closure of a waste disposal facility. In addition, more recent revisions of the international safety standards require the development of a safety case for such facilities and activities, documentation presenting all the arguments supporting the safety of the facilities and activities covering site and engineering features, quantitative safety assessment and management systems. Guidance on meeting these safety requirements also indicates the need for a graded approach to safety assessment, with the extent and complexity of the assessment being proportional to the complexity of the activity or facility, and its propensity for radiation hazard. Safety assessment approaches and methodologies have evolved over several decades and international interest in these developments has been considerable as they can be complex and often subjective, which has led to international projects being established aimed at harmonization. The IAEA has sponsored a number of such initiatives, particularly in the area of disposal facility safety, but more recently in the areas of pre disposal waste management and decommissioning, including projects known as ISAM, ASAM, SADRWMS and DeSa. The projects have a number of common aspects including development of standardized methodological approaches, application on test cases and assessment review; they also have activity and facility specific elements. The paper presents an overview of the projects, the outcomes from the projects to date and their future direction aimed very much at practical application of

  20. Document status for 1 and 2 Kozloduy NPP decommissioning activities -Phase 'Final Shutdown'

    International Nuclear Information System (INIS)

    Vangev, A.; Boyadjiev, Z.

    1997-01-01

    Decommissioning process (D and D) is the final phase of each nuclear reactor life cycle. The first nuclear reactor generation has reached his expiration life date. Decommissioning working documentation had not been taken into account at the project and construction stage. The decommissioning activities, planning and legislation has to develop along their operation. Most of developed nuclear energetic countries have gathered good experience and have create their own decommissioning strategy. This report represents in brief an overview of different country's approaches and the Kozloduy NPP decommissioning activity intention in near future and reviews the D and D working document status for 1 and 2 Kozloduy NPP Units decommissioning. Kozloduy NPP D and D task to the moment is to plan the first stage of the decommissioning process - 'The Final Shutdown' and to prepare the working documents for the phase execution. The Final Shutdown of Kozloduy NPP - 1 is the termination of operation of the Units 1 and 2 and the electricity production cessation after their useful life exhaust. In accordance with the legal legislation in Bulgaria only the normal planned termination of operation on units 1 and 2 should be prescribed. The project results concern the initial condition of the equipment and systems, their preparation and sequence for defueling, decontamination and dismantling. A plan for activities' organization for D and D and Complex Characterization of the Site under consideration will contain the following documents: 1. Time-schedule for the sequence of activities during the stages of the Final Shutdown and Safe Enclosure preparation. Technical project for organization of work related to Final Shutdown; 2. Complex Characterization Programme for a condition investigation of the Units 1 and 2 equipment and systems. 3. Technical project for design modifications and dismantling of equipment and systems which violate the radiation and nuclear safety during the Final Shutdown

  1. RA research reactor in 'Vinca' Institute-approach to the decommissioning

    International Nuclear Information System (INIS)

    Ljubenov, V.Lj.; Pesic, M.P.; Sotic, O.

    2002-01-01

    In this paper short overview of decommissioning process of research reactors according to IAEA standards and world practice is given. Basic technical characteristics and details of operational history of the RA research reactor in Vinca Institute of Nuclear Sciences are present. The main nuclear and radiation safety problems related to the RA reactor facility are defined and the outlines of the future decommissioning project are proposed. (author)

  2. Internationally Standardized Cost Item Definitions for Decommissioning of Nuclear Installations

    International Nuclear Information System (INIS)

    Lucien Teunckens; Kurt Pflugrad; Candace Chan-Sands; Ted Lazo

    2000-01-01

    The European Commission (EC), the International Atomic Energy Agency (IAEA), and the Organization for Economic Cooperation and Development/Nuclear Energy Agency (OECD/NEA) have agreed to jointly prepare and publish a standardized list of cost items and related definitions for decommissioning projects. Such a standardized list would facilitate communication, promote uniformity, and avoid inconsistency or contradiction of results or conclusions of cost evaluations for decommissioning projects carried out for specific purposes by different groups. Additionally, a standardized structure would also be a useful tool for more effective cost management. This paper describes actual work and result thus far

  3. Decommissioning and environmental remediation scenario development for Fukushima Daiichi

    Energy Technology Data Exchange (ETDEWEB)

    Kawamura, Hideki [mcm japan, Tokyo (Japan); Yashio, Shoko [Obayashi Corporation, Tokyo (Japan); McKinley, Ian G. [McKinley Consulting, Frick (Switzerland)

    2017-07-15

    Although the general approach to reactor decommissioning is well established, there is no direct precedent for managing the 6 units of the Fukushima Daiichi nuclear power plant. Apart from damaged reactors, challenges include extensive contamination of the entire reactor site and a huge tank farm currently storing contaminated cooling water. In order to move forward with planning decommissioning, it is important to decide on the desired end state of the site and understand the impact on such a decision on the costs, hazards and environmental impact of the project. A decommissioning roadmap and reference dismantling concept provide a basis for short-term planning, but the potential for technological optimisation should be carefully considered.

  4. Feasibility studies for decommissioning

    International Nuclear Information System (INIS)

    Hladky, E.

    2000-01-01

    In this presentation author deals with planning of decommission of the NPPs A1, V1 and V2 Bohunice and Mochovce. It was concluded that: Used model for decommissioning parameters assessment has been suitable for elaboration of initial decommissioning plans (feasibility studies); Basic assessment of main decommissioning parameters and basic comparison of various decommissioning options have been possible; Improvement of the model and corresponding software is desirable and works on software improvement began one year ago; V1-NPP initial decommissioning plan should be actualized, because initial decommissioning plan does not correspond by its content and structure to requirements of Act No. 130/98 and Nuclear Regulatory Authority Degree No. 246/99; Strategy of radioactive wastes treatment and conditioning together with technical provisions at Jaslovske Bohunice site was changed in comparison with the assumptions in 1991-92; Considered V1 NPP decommissioning options are necessary to be re-evaluated in accordance with latest development of knowledge and approaches to NPP decommissioning in the world; Specific unit costs are substantially and differentially changed in comparison with the assumptions in 1991-92; Necessity to take into account technical changes resulted from V1 NPP reconstruction. (author)

  5. NPP Krsko decommissioning concept

    International Nuclear Information System (INIS)

    Novsak, M.; Fink, K.; Spiler, J.

    1996-01-01

    At the end of the operational lifetime of a nuclear power plant (NPP) it is necessary to take measures for the decommissioning as stated in different international regulations and also in the national Slovenian law. Based on these requirements Slovenian authorities requested the development of a site specific decommissioning plan for the NPP Krsko. In September 1995, the Nuklearna Elektrarna Krsko (NEK) developed a site specific scope and content for a decommissioning plan including the assumptions for determination of the decommissioning costs. The NEK Decommissioning Plan contains sufficient information to fulfill the decommissioning requirements identified by NRC, IAEA and OECD - NEA regulations. In this paper the activities and results of development of NEK Decommissioning Plan consisting of the development of three decommissioning strategies for the NPP Krsko and selection of the most suitable strategy based on site specific, social, technical, radiological and economic aspects, cost estimates for the strategies including the costs for construction of final disposal facilities for fuel/high level waste (fuel/HLW) and low/intermediate level waste (LLW/ILW) and scheduling of all activities necessary for the decommissioning of the NPP Krsko are presented. (author)

  6. NPP Krsko decommissioning concept

    International Nuclear Information System (INIS)

    Novsak, M.; Fink, K.; Spiler, J.

    1996-01-01

    At the end of the operational lifetime of a nuclear power plant (NPP) it is necessary to take measures for the decommissioning as stated in different international regulations and also in the national Slovenian law. Based on these requirements Slovenian authorities requested the development of a site specific decommissioning plan for the NPP KRSKO. In September 1995, the Nuklearna Elektrarna Krsko (NEK) developed a site specific scope and content for decommissioning plan including the assumptions for determination of the decommissioning costs. The NEK Decommissioning Plan contains sufficient information to fulfill decommissioning requirements identified by NRC, IAEA and OECD - NEA regulations. In this paper the activities and the results of development of NEK Decommissioning Plan consisting of the development of three decommissioning strategies for the NPP Krsko and selection of the most suitable strategy based on site specific, social, technical, radiological and economical aspects, cost estimates for the strategies including the costs for construction of final disposal facilities for fuel/high level waste (fuel/HLW) and low/intermediate level waste (LLW/ILW) and scheduling all activities necessary for the decommissioning of the NPP KRSKO are presented. (author)

  7. OECD/NEA Radiological characterisation in decommissioning - Evaluation of questionnaire. Strategies for Radiological Characterisation used by Decommissioning Projects in OECD Countries

    International Nuclear Information System (INIS)

    Thierfeldt, Stefan; Haneke, K.

    2012-01-01

    In the first half of 2011, the Radiological Characterization and Decommissioning Task Group (RCD) of the WPDD of the OECD/NEA has prepared a questionnaire on the characterisation of nuclear facilities that has been circulated among nuclear installations in various OECD countries. The aim of this questionnaire was to gather information on the approaches and methods that are used for radiological characterisation (RC) for systems and components, for buildings and for sites (land), on domestic and international guidance and regulations that govern RC, and on the experience with RC that is already available in the particular country. The number of responses to this questionnaire that were received in the second half of 2011 was very satisfactory, so that a broad overview is now available from the following countries: Belgium, Canada, Denmark, Finland, France, Germany, Japan, Korea, Spain, Sweden, and United Kingdom. The presentation deals with the results that were obtained from the evaluation of these questionnaires and gives overviews of the objectives of characterisation, the input data for planning of characterisation, the measurement techniques that were used for metallic structures and components, for buildings and for sites, the data management and QA measures, the obstacles that were encountered, the experience with availability of as-built plans, the regulatory framework and guidelines, and the costs for RC. All information on RC is further broken down with respect to the operational phase (where RC is used for preliminary decommissioning planning), the transition phase (where RC supports decommissioning planning) and the actual decommissioning phase (where RC is needed for dismantling, decontamination and treatment of systems, components, buildings etc.). The presentation also offers conclusions on these subjects. (authors)

  8. The inherent advantages of delayed dismantling of decommissioning nuclear stations

    International Nuclear Information System (INIS)

    Liederman, J.M.; Saroudis, J.I.

    1985-01-01

    Recent studies in Canada pertaining to the decommissioning of the CANDU 600 MW(e) reactor have led to the development of the option of a ''static state'' condition. This alternative is based on judging risk and benefit to society considering the greatly reduced potential radiation exposure to personnel after 30 to 80 years have elapsed, following the final shutdown of the reactor. After approximately 80 to 120 years have elapsed, the decay in all systems and components (with the exception of the reactor assembly) would be such that radiation fields would be at background levels producing an environment that would be acceptable for Stage 3 decommissiong. This philosophy is based on the current engineering judgement that: - All systems, components, and structures which were associated with the nuclear processes and are radioactive, can be put into a static or storage state, and a containment function maintained at low cost for prolonged periods of between 80 to 120 years. - Between 80 to 120 years after shutdown, most of the radioactivity, except for some long lived radionuclides in the reactor vessel itself and its vault, will have naturally decayed to near releasable limits without any external intervention. - There is a lower overall risk to society in this approach, than dismantling and transporting radioactive materials prematurely. This philosophy is developed taking into consideration radiation protection, financial and risk assessment issues. The Canadian concept of dry storage of spent fuel is part of this philosophy and may be of interest to decommissioned nuclear plants of other types. 4 tables, 5 graphs

  9. The decommissioning of nuclear facilities; Le demantelement des installations nucleaires de base

    Energy Technology Data Exchange (ETDEWEB)

    Niel, J.Ch.; Rieu, J.; Lareynie, O.; Delrive, L.; Vallet, J.; Girard, A.; Duthe, M.; Lecomte, C.; Rozain, J.P.; Nokhamzon, J.G.; Davoust, M.; Eyraud, J.L.; Bernet, Ph.; Velon, M.; Gay, A.; Charles, Th.; Leschaeva, M.; Dutzer, M.; Maocec, Ch.; Gillet, G.; Brut, F.; Dieulot, M.; Thuillier, D.; Tournebize, F.; Fontaine, V.; Goursaud, V.; Birot, M.; Le Bourdonnec, Th.; Batandjieva, B.; Theis, St.; Walker, St.; Rosett, M.; Cameron, C.; Boyd, A.; Aguilar, M.; Brownell, H.; Manson, P.; Walthery, R.; Wan Laer, W.; Lewandowski, P.; Dorms, B.; Reusen, N.; Bardelay, J.; Damette, G.; Francois, P.; Eimer, M.; Tadjeddine, A.; Sene, M.; Sene, R

    2008-11-15

    This file includes five parts: the first part is devoted to the strategies of the different operators and includes the following files: the decommissioning of nuclear facilities Asn point of view, decommissioning of secret nuclear facilities, decommissioning at the civil Cea strategy and programs, EDF de-construction strategy, Areva strategy for decommissioning of nuclear facilities; the second one concerns the stakes of dismantling and includes the articles as follow: complete cleanup of buildings structures in nuclear facilities, decommissioning of nuclear facilities and safety assessment, decommissioning wastes management issues, securing the financing of long-term decommissioning and waste management costs, organizational and human factors in decommissioning projects, training for the decommissioning professions: the example of the Grenoble University master degree; the third part is devoted to the management of dismantling work sites and includes the different articles as follow: decommissioning progress at S.I.C.N. plant, example of decommissioning work site in Cea Grenoble: Siloette reactor decommissioning, matters related to decommissioning sites, decommissioning of french nuclear installations: the viewpoint of a specialist company, specificities of inspections during decommissioning: the Asn inspector point of view; the fourth part is in relation with the international approach and includes as follow: IAEA role in establishing a global safety regime on decommissioning, towards harmonization of nuclear safety practices in Europe: W.E.N.R.A. and the decommissioning of nuclear facilities, EPA superfund program policy for decontamination and decommissioning, progress with remediation at Sellafield, progress and experiences from the decommissioning of the Eurochemic reprocessing plant in Belgium, activities of I.R.S.N. and its daughter company Risk-audit I.r.s.n./G.r.s. international in the field of decommissioning of nuclear facilities in eastern countries

  10. Case Study to Apply Work Difficulty Factors to Decommissioning Cost Estimates

    Energy Technology Data Exchange (ETDEWEB)

    Yun, Taesik; Jung, Hyejin; Oh, Jaeyoung; Kim, Younggook [KHNP CRI, Daejeon (Korea, Republic of)

    2016-10-15

    This article is prepared as a guideline regarding how to apply the work difficult factor (WDF) when it comes to the estimates of the decommissioning costs. Although several cases of the decommissioning cost estimates have been made for a few commercial nuclear power plants, the different technical, site-specific economic assumptions used make it difficult to interpret those cost estimates and compare them with that of Kori-1. In addition, it is clear that we are supposed to experience difficulties being created in the process of the Kori-1 and the virtual inaccessibility to the limited areas at the pre-decommissioning stage. Estimating decommissioning costs is one of the most crucial processes since it encompasses all the spectrum of decommissioning activities from the planning to the last evaluation on whether the decommissioning has successfully been proceeded from the safety and economic perspectives. Here I suggested the activity dependent costs is only related to WDFs of the incumbent plant planning or undergone to be decommissioned since as a matter of fact, estimating WDFs is the core process to articulately scrutinize the practical costs to apply to Kori-1 project.

  11. Establishment and Evaluation of Decommissioning Plant Inventory DB and Waste Quantity

    International Nuclear Information System (INIS)

    Oh, Jae Yong; Moon, Sang-Rae; Yun, Taesik; Kim, Hee-Geun; Sung, Nak-Hoon; Jung, Seung Hyuk

    2016-01-01

    Korea Hydro and Nuclear Power (KHNP) made a decision for permanent shutdown of Kori-1 and has progressed the strategy determination and R and D for the decommissioning of Kori-1. Decommissioning waste, Structure, System and Components (SSCs) is one of the most important elements. Decommissioning waste quantity is calculated based on Plant Inventory Database (PI DB) with activation and contamination data. Due to the largest portion of waste management and disposal in decommissioning, it is necessary to exactly evaluate waste quantity (applying the regulation, guideline and site-specific characterization) for economic feasibility. In this paper, construction of PI DB and evaluation of waste quantity for Optimized Pressurized Reactor (OPR-1000) are mainly described. Decommissioning waste quantities evaluated are going to be applied to calculation of the project cost. In fact, Ministry of Trade, Industry and Energy (MOTIE) in Korea expected the decommissioning waste quantity in a range of 14,500-18,850 drums, and predicted appropriate liability for decommissioning fund by using waste quantity. The result of this study is also computed by the range of 14,500-18,850 drums. Since there is no site-specific data for the NPP site, this evaluation is the preliminary analysis

  12. Establishment and Evaluation of Decommissioning Plant Inventory DB and Waste Quantity

    Energy Technology Data Exchange (ETDEWEB)

    Oh, Jae Yong; Moon, Sang-Rae; Yun, Taesik; Kim, Hee-Geun [KHNP CRI, Daejeon (Korea, Republic of); Sung, Nak-Hoon; Jung, Seung Hyuk [KONES Corp., Seoul (Korea, Republic of)

    2016-10-15

    Korea Hydro and Nuclear Power (KHNP) made a decision for permanent shutdown of Kori-1 and has progressed the strategy determination and R and D for the decommissioning of Kori-1. Decommissioning waste, Structure, System and Components (SSCs) is one of the most important elements. Decommissioning waste quantity is calculated based on Plant Inventory Database (PI DB) with activation and contamination data. Due to the largest portion of waste management and disposal in decommissioning, it is necessary to exactly evaluate waste quantity (applying the regulation, guideline and site-specific characterization) for economic feasibility. In this paper, construction of PI DB and evaluation of waste quantity for Optimized Pressurized Reactor (OPR-1000) are mainly described. Decommissioning waste quantities evaluated are going to be applied to calculation of the project cost. In fact, Ministry of Trade, Industry and Energy (MOTIE) in Korea expected the decommissioning waste quantity in a range of 14,500-18,850 drums, and predicted appropriate liability for decommissioning fund by using waste quantity. The result of this study is also computed by the range of 14,500-18,850 drums. Since there is no site-specific data for the NPP site, this evaluation is the preliminary analysis.

  13. Nuclear power plant decommissioning: an unresolved problem

    International Nuclear Information System (INIS)

    Pollock, C.

    1987-01-01

    In 1984, the Critical Mass Energy Project asserted that at least 11 US reactors had gone through one-third of their operating lives without collecting any decommissioning funds and that nationwide only $600 million had been collected. This lack of financial planning prompted 10 states to require mandatory periodic deposits into external accounts: California, Colorado, Connecticut, Maine, Massachusetts, Mississippi, New Hampshire, Pennsylvania, Vermont, and Wisconsin. Setting aside decommissioning funds is essential in every country that uses nuclear power. Regardless of a nation's future energy plans, existing plants must eventually be scrapped. Just as today's cities would not be habitable without large fleets of garbage trucks and extensive landfills, the international nuclear industry is not viable without a sound decommissioning strategy. Thirty years after the first nuclear plant started producing electricity, such a strategy has yet to be formulated. More than 500 reactors, including those currently under construction, will have to be decommissioned. Preparing to safely retire these plants requires aggressive, well-funded research and development programs, policy makers willing to tackle unpleasant, long-term problems, and robust retirement accounts funded by today's utility customers

  14. Decommissioning Planning during the Operation of the Loviisa NPP. Planning, Management and Organizational Aspects

    Energy Technology Data Exchange (ETDEWEB)

    Tuunanen, J. P.; Eurajoki, T. E.E., [Fortum Power and Heat Ltd, Nuclear Waste Espoo (Finland)

    2013-08-15

    The first decommissioning plan for Loviisa nuclear power plant was written already in 1980's, when the plant had just started operation. The plan has been updated in 5-6 years intervals and this work still continues towards the final decommissioning plan. The decommissioning plan is based on immediate dismantling option and final disposal of decommissioning waste to the extension of the on site final disposal facility for low and intermediate level waste. The decommissioning planning has been organized as an independent project, which is realised in close cooperation with Fortum's research programme on radioactive waste management. The plant personnel are involved in the planning work through providing operating experience on contamination and activation of systems, structures and components. Later in the decommissioning phase the plant personnel will form the main part of the decommissioning organization. (author)

  15. IAEA Global Support of Decommissioning Implementation with a Focus on Advanced Technologies

    International Nuclear Information System (INIS)

    Michal, Vladimir; )

    2017-01-01

    Recently there are about 140 power reactors in decommissioning phase worldwide excluding 17+ that might be considered as decommissioned. In addition, more than 400 other nuclear facilities, such as research reactors or nuclear fuel cycle facilities, have been shutdown for decommissioning, have been undergoing active decommissioning or have already been fully dismantled. The IAEA provides various kind of support for Member States including publication of safety and technical reports providing guidance, recommendations, experiences, good practices and lessons learned covering the preparatory and implementation decommissioning phases. Many training courses, workshops, seminars etc. were organized to support sharing of good practices among specialists and organizations involved. In line with the non-technical aspects, such as decommissioning planning, costing, managerial approaches etc., there are also presented and discussed technical solutions often with a focus on the advanced technologies to be considered. Several completed and ongoing IAEA initiatives partially or fully address the advanced approaches and techniques to support safe and effective implementation of decommissioning projects. The presentation will provide an overview of relevant activities organized so far and perspectives of the IAEA on advanced technologies for decommissioning. (author)

  16. License stewardship and other approaches to commercial nuclear power plant decommissioning

    International Nuclear Information System (INIS)

    Daly, P.T.; Moloney, B.P.

    2011-01-01

    This paper addresses the challenge of how our industry could arrange itself to deliver decommissioning of Nuclear Power Plants (NPPs) safely, in good time and affordably. There is a growing wealth of experience across the world in safe decommissioning techniques. Most - arguably all - of the techniques required to perform the full decommissioning of NPPs have been demonstrated on full-scale projects. Waste processing and disposal challenges remain in many countries, where the major issues are societal acceptance and political will. Interim storage possibilities have been identified in most countries. In decommissioning, the outstanding significant issues lie now in the domain of affordability and risk management. This paper will illustrate approaches to decommissioning with examples from the US and UK, to explore how the industry can achieve configurations to deliver lower risk and improved affordability for utilities. Different configurations, or models, will be used to illustrate the approaches taken. (orig.)

  17. Decommissioning of a brachytherapy facility at the Oncology Hospital in Havana

    International Nuclear Information System (INIS)

    Benitez, J.C.; Salgado, M.; Madrazo, S.; Castillo, R.; Marcos, J.; Flores, J.

    2001-01-01

    In the past the National Institute of Oncology and Radiobiology (INOR) used 226 Ra sealed sources for brachytherapy service. For technical obsolescence and safety considerations the brachytherapy facility was shutdown. Most 226 Ra sources were collected from the hospital in 1996, but for different reasons, not all radium sources could be evacuated by this time. Some of them were leaking which caused contamination of the place. In May 1997 the Direction of the Hospital requested the Center for Radiation Protection and Hygiene (CPHR) to evaluate the radiological situation in the contaminated areas and to carry out the decontamination of the rooms and the decommissioning of the brachytherapy facility for unrestricted use. Contamination surveys conducted during this year confirmed the contamination of the facility. Once all necessary conditions were in place the decontamination of rooms and the decommissioning of this facility took place as in June 1999. In order to perform such a work the Hospital received the authorization from the National Centre for Nuclear Safety (Cuban's Regulatory Body) as a License for Decommissioning. The decommissioning process greatly benefited from early planning. This included an assessment of available documentation and operational history of the brachytherapy facility, the definition of responsibilities for each activity, technical seminars with personnel from the hospital and specialist from CPHR in charge of the decommissioning activities, safety assessment of the radiological and non-radiological hazards, the evaluation of available waste management provisions, the availability of financial resources as well as the review of lessons learned from previous projects. The characterization of the facility was a very important task in the selection of decommissioning alternative. During decommissioning operations, radiation monitoring of workers was carried out. In order to evaluate the radiological situation in the contaminated rooms

  18. Methodologies for and Results of Planning later Decommissioning of Nuclear Facilities

    International Nuclear Information System (INIS)

    Auler, I.; Paul, R.; Petrasch, P.

    1996-01-01

    Cost and success of decommissioning and dismantling nuclear power plants or other nuclear facilities are very much related to the chosen strategy and their implementation in practice. The strategy to be developed depends on the specific boundary conditions in a certain country and plant. Inadequate planning and equipment considered too late cause delays in the project performance and improvisations with financial and radiological consequences. For the development of a decommissioning strategy for a nuclear power plant broad experience from past D and D-projects is very important. That experience is very helpful in assessing the importance of the many factors which determine the success or failure of strategic decisions Tools for the systematic recording and investigation of the needed measures and expenditures are available, eg. the decommissioning cost program STILLKO-2, which has been established as standard tool. (author)

  19. Decommissioning Combustible Waste Treatment using Oxygen-Enriched Incinerator

    Energy Technology Data Exchange (ETDEWEB)

    Min, Byungyoun; Lee, Yoonji; Yun, Gyoungsu; Lee, Kiwon; Moon, Jeikwon [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2014-05-15

    The aim of the paper is current status of treatment for the decommissioning combustible waste in KAERI and for the purpose of the volume reduction and clearance for decommissioning combustible wastes generated by the decommissioning projects. The incineration technology has been selected for the treatment of combustible wastes. About 34 tons of decommissioning combustible waste has been treated using Oxygen Enriched incineration. Temperature, pressure of major components, stack gas concentration, i. e., SOx, NOx, CO, CO{sub 2} and HCl, and the residual oxygen were measured. Measured major parameters during normal operation were sustained on a stable status within a criteria operation condition. Oxygen enriched air, 22vol. % (dry basis) was used for stable incineration. The volume reduction ratio has achieved about 1/117. The incineration with decommissioning radioactive combustible waste is possible with moderate oxygen enrichment of 22 vol.% (dry basis) into the supply air. The incineration facility operated quite smoothly through the analysis major critical parameters of off-gas. The pressure, off-gas flow and temperature of major components remained constant within the range specified. The measures gases and particulate materials in stack were considerably below the regulatory limits. The achieved volume reduction ratio through incineration is about 1/117.

  20. Education and Training in Decommissioning Needs, Opportunities and Challenges

    International Nuclear Information System (INIS)

    Kockerols, Pierre; Schneider, Hans Guenther; ); Freer, Martin

    2016-01-01

    The decommissioning of nuclear facilities is an industrial activity that is growing worldwide, creating job opportunities at all educational levels. Over the last decades, European companies have been involved in decommissioning projects that are targeted at delivering an environmentally friendly end-product, in line with the 'circular economy', as promoted by EU and national policies. European industry has acquired know-how and today Europe can position itself at the top level in the world decommissioning market. However, in view of the preparation of future decommissioning programmes, efforts are necessary to ensure and share the underpinning knowledge, skills and competences. In this perspective, the University of Birmingham in association with the European Commission's Joint Research Centre have organised a joint seminar to address the following questions in relation to education and training in nuclear decommissioning: - What are the competence needs for the future? - What are the education and training opportunities? - How can we stimulate interest and future talent? In answering these questions a report has been published which provides suggestions for helping the development, coordination and promotion of adequate education and training programmes at EU level in nuclear decommissioning. It highlights, in particular, the necessity to improve the long term planning of the resources and competences, addressing the specifics of decommissioning activities, to give more visibility to the career possibilities in the sector, and to enhance the cooperation between the existing education and training programmes, providing also more clarity in the learning outcomes. (authors)

  1. CONSIDERATIONS FOR THE DEVELOPMENT OF A DEVICE FORTHE DECOMMISSIONING OF THE FUEL CHANNELS IN THECANDU NUCLEAR REACTOR

    Directory of Open Access Journals (Sweden)

    Gabi ROSCA FARTAT

    2013-05-01

    Full Text Available As many nuclear power plants are reaching their end of lifecycle, the decommissioning of theseinstallations has become one of the 21stcentury’s great challenges. Each project may be managed differently,depending on the country, development policies, financial considerations, and the availability of qualifiedengineers or specialized companies to handle such projects. The principle objective of decommissioning is toplace a facility into such a condition that there is no unacceptable risk from the decommissioned facility topublic health and safety of the environment. In order to ensure that at the end of its life the risk from a facility iswithin acceptable bounds, action is normally required. The overall decommissioning strategy is todeliver a timely, cost-effective program while maintaining high standards of safety, security and environmentalprotection. If facilities were not decommissioned, they could degrade and potentially present an environmentalradiological hazard in the future. Simply abandoning or leaving a facility after ceasing operations is notconsidered to be an acceptable alternative to decommissioning. The final aim of decommissioning is torecover the geographic site to its original condition.

  2. Rapporteur's Report of the Workshop on Radiological Characterisation for Decommissioning

    International Nuclear Information System (INIS)

    Thierfeldt, Stefan

    2012-01-01

    In April 2012, the Nuclear Energy Agency, in co-operation with Studsvik Nuclear AB, the Swedish Radiation Safety Authority (SSM), Swedish Nuclear Fuel and Waste Management Company (SKB) and AB SVAFO, held a Workshop on Radiological Characterisation in Decommissioning in Studsvik near Nykoeping (Sweden). During three days, a wide range of presentations, posters, discussions and site visits brought together over 120 participants from 23 countries and 4 international organisations, the IAEA, the WNA, the European Commission and the OECD/NEA. Members of the Task Group on Radiological Characterisation for Decommissioning (RCD) of the WPDD were involved in the preparation of the workshop. Many decommissioning projects of all types of nuclear installations have progressed substantially and/or have been completed to brown field or green field conditions, so that it was the right time to bring together operators, regulators, scientists, consultants and contractors to exchange information and views and to evaluate the information on radiological characterisation gained from this multitude of projects. The outcome will be valuable for the large number of decommissioning projects about to start in the near future. The Workshop consisted of 5 topical sessions and a poster session. The topical sessions were complemented by discussions in the plenary and in smaller groups. This report provides a short summary of the various presentations and discussions. It concentrates on the outcome of the presentations, posters and discussions than giving an account of the spoken word

  3. Evaluation of Service Station Attendant-Auto Care Project.

    Science.gov (United States)

    Cress, Ronald J.

    The project described offers an approach to providing occupational skills to socially and educationally handicapped youth, specifically the skills necessary for a service station attendant in driveway salesmanship and auto care. The 10-page evaluation report presents project goals and objectives with evaluation data (represented graphically) and…

  4. Decommissioning engineering systems for nuclear facilities and knowledge inheritance for decommissioning of nuclear facilities

    International Nuclear Information System (INIS)

    Tachibana, Mitsuo

    2016-01-01

    Information on construction, operation and maintenance of a nuclear facility is essential in order to plan and implement the decommissioning of the nuclear facility. A decommissioning engineering system collects these information efficiently, retrieves necessary information rapidly, and support to plan the reasonable decommissioning as well as the systematic implementation of dismantling activities. Then, knowledge of workers involved facility operation and dismantling activities is important because decommissioning of nuclear facility will be carried out for a long period. Knowledge inheritance for decommissioning has been carried out in various organizations. This report describes an outline of and experiences in applying decommissioning engineering systems in JAEA and activities related to knowledge inheritance for decommissioning in some organizations. (author)

  5. Preparing for Decommissioning During Operation and After Final Shutdown

    International Nuclear Information System (INIS)

    Kostova, Milena; Papaz, Dan; Pottelberg, Paul; Clement, Gilles; Falcone, Jean-Luc; Gouhier, Eric; Laurent, Gerard; Rondeau, Jean-Marie; Siefridt, Camille; Brendebach, Boris; Knaack, Michael; Ahn, Sangmyeon; Correa Sainz, Cristina; Carroll, Simon; Larsson, Arne; Norberg, Thomas; Stridsman, Henrik; Minges, Juergen; Boniface, Simon; Dunlop, Alister; Jassal, Raj; Moakes, Joanna; Abu-Eid, Rateb; Watson, Bruce; Devgun, Jas; McGrath, Richard; Glorennec, Christian; ); Weber, Inge; )

    2018-01-01

    The transition from an operating nuclear facility to the decommissioning phase is critical in the life cycle of every facility. A number of organisational and technical modifications are needed in order for the facility to meet new objectives and requirements, and a certain number of activities must be initiated to support the transition and preparation for the dismantling of the facility. Thorough preparation and planning is key for the success of global decommissioning and dismantling projects, both to minimise delays and undue costs and to ensure a safe and efficient decommissioning process. The aim of this report is to inform regulatory bodies, policy makers and planners about the relevant aspects and activities that should begin during the last years of operation and following the end of operation. Compiling lessons learnt from experiences and good practices in NEA member countries, the report supports the further optimisation of transition strategies, activities and measures that will ensure adequate preparation for decommissioning and dismantling

  6. 1982 international decommissioning symposium

    International Nuclear Information System (INIS)

    Mickelson, S.

    1982-01-01

    Sixty-four papers were presented at the following sessions: policy, regulations, and standards; management of decommissioning wastes; decommissioning experience; decommissioning tooling and techniques; radiological concerns; and planning and engineering

  7. Lessons Learned for Decommissioning Planning

    International Nuclear Information System (INIS)

    Sohn, Wook; Kim, Young-gook; Kim, Hee-keun

    2015-01-01

    The purpose of this paper is to introduce the U.S. nuclear industrial's some key lessons learned especially for decommissioning planning based on which well informed decommissioning planning can be carried out. For a successful decommissioning, it is crucial to carry out a well-organized decommissioning planning before the decommissioning starts. This paper discussed four key factors which should be decided or considered carefully during the decommissioning planning period with introduction of related decommissioning lessons learned of U.S. nuclear industry. Those factors which have been discussed in this paper include the end state of a site, the overall decommissioning strategy, the management of the spent fuels, and the spent fuel pool island. Among them, the end state of a site should be decided first as it directs the whole decommissioning processes. Then, decisions on the overall decommissioning strategy (DECON vs. SAFSTOR) and the management of the spent fuels (wet vs. dry) should follow. Finally, the spent fuel pool island should be given due consideration because its implementation will result in much cost saving. Hopefully, the results of this paper would provide useful inputs to performing the decommissioning planing for the Kori unit 1

  8. Vandellos 1 NPP decommissioning feedback experience

    Energy Technology Data Exchange (ETDEWEB)

    Fernandez, Rodriguez A. [Empresa Nacional de Residuos Radioactivos, ENPRESA, Madrid (Spain)

    2003-07-01

    The Vandellos 1 Nuclear Power Plant (CNV1) is located on the Mediterranean coast in the province of Tarragona (Spain). The Plant is of the European Natural Uranium Graphite-Gas type. The thermal power of the plant amounts to 1,670 MWt, its electrical output being 500 Mwe. The Plant started-up commercial service in May 1972; its final shutdown, due to a fire in the turbines, occurred in October 1989, after 17 years of operation with an accumulated energy production of 55,647 GWh. The option of decommissioning accepted by the Ministry of Industry, consists of first removing the spent fuel and conditioning the operating radioactive wastes, and then undertaking dismantling of almost all the structures and components located outside the reactor vessel, except those ensuring confinement of the vessel itself and the safety and surveillance of the facility and site. No action will be taken with respect to the vessel, in which the reactor will remain confined without nuclear fuel and with its internal components intact until completion of the waiting (dormancy) period. The site itself will be kept under surveillance during dormancy phase, following partial clearance, the remaining installations being left within the new site perimeter in a situation of monitored confinement. Following the dormancy period, which will last some 30 years, total dismantling of the remaining installations will be undertaken, this implying subsequent complete clearance of the site. The project was started in November of 1992, and the works on site began in 1998. The safe enclosure consists only in the reactor pressure vessel, which will be left on site. The activity content of the vessel is about 100 000 Ci, mostly Co 60. Part of the Stage 2 concept is the total static isolation of this vessel. The vessel has 1 700 penetrations, the pipes of which were cut, seal-welded and inspected. After five years of works in Vandellos 1 NPP decommissioning, ENRESA has an experience and knowledge, that is

  9. Decommissioning handbook

    Energy Technology Data Exchange (ETDEWEB)

    Manion, W.J.; LaGuardia, T.S.

    1980-11-01

    This document is a compilation of information pertinent to the decommissioning of surplus nuclear facilities. This handbook is intended to describe all stages of the decommissioning process including selection of the end product, estimation of the radioactive inventory, estimation of occupational exposures, description of the state-of-the-art in re decontamination, remote csposition of wastes, and estimation of program costs. Presentation of state-of-the-art technology and data related to decommissioning will aid in consistent and efficient program planning and performance. Particular attention is focused on available technology applicable to those decommissioning activities that have not been accomplished before, such as remote segmenting and handling of highly activated 1100 MW(e) light water reactor vessel internals and thick-walled reactor vessels. A summary of available information associated with the planning and estimating of a decommissioning program is also presented. Summarized in particular are the methodologies associated with the calculation and measurement of activated material inventory, distribution, and surface dose level, system contamination inventory and distribution, and work area dose levels. Cost estimating techniques are also presented and the manner in which to account for variations in labor costs as impacting labor-intensive work activities is explained.

  10. Decommissioning handbook

    International Nuclear Information System (INIS)

    Manion, W.J.; LaGuardia, T.S.

    1980-11-01

    This document is a compilation of information pertinent to the decommissioning of surplus nuclear facilities. This handbook is intended to describe all stages of the decommissioning process including selection of the end product, estimation of the radioactive inventory, estimation of occupational exposures, description of the state-of-the-art in re decontamination, remote csposition of wastes, and estimation of program costs. Presentation of state-of-the-art technology and data related to decommissioning will aid in consistent and efficient program planning and performance. Particular attention is focused on available technology applicable to those decommissioning activities that have not been accomplished before, such as remote segmenting and handling of highly activated 1100 MW(e) light water reactor vessel internals and thick-walled reactor vessels. A summary of available information associated with the planning and estimating of a decommissioning program is also presented. Summarized in particular are the methodologies associated with the calculation and measurement of activated material inventory, distribution, and surface dose level, system contamination inventory and distribution, and work area dose levels. Cost estimating techniques are also presented and the manner in which to account for variations in labor costs as impacting labor-intensive work activities is explained

  11. Decommissioning of Ukrainian NPPs

    International Nuclear Information System (INIS)

    Skripov, A.E.

    2002-01-01

    The decision about the development of 'Decommissioning Concept of Ukrainian NPPs' being on commercial operational stage was approved by NAEK 'Energoatom' Board of Administration by way of the decommissioning activity effective planning. The Concept will be the branch document, containing common approaches formulations on problem decisions according to the units decommissioning with generated resources, and RAW and SNF management strategy during decommissioning

  12. Design Lessons Drawn from the Decommissioning of Nuclear Facilities

    International Nuclear Information System (INIS)

    2011-05-01

    This report provides an updated compilation incorporating the most recent lessons learned from decommissioning and remediation projects. It is intended as a 'road map' to those seeking to apply these lessons. The report presents the issues in a concise and systematic manner, along with practical, thought-provoking examples. The most important lessons learned in recent years are organized and examined to enable the intended audience to gauge the importance of this aspect of the planning for new nuclear facilities. These will be of special interest to those seeking to construct nuclear facilities for the first time. In Sections 1 and 2, the current situation in the field of decommissioning is reviewed and the relevance and importance of beneficial design features is introduced. A more detailed review of previous and current lessons learned from decommissioning is given in Section 3 where different aspects of the decommissioning process are analysed. From this analysis beneficial design features have been extracted and identified in Section 4 which includes two comprehensive tables where brief descriptions of the features are summarized and responsibilities are identified. Conclusions and key design features and key recommendations are given in Section 5. Two Annexes are included to provide lessons from past projects and past experience and to record notes and extracts taken from a comprehensive list of publications listed in the References on page 47.

  13. Research and development activities for reactor decommissioning. Developing technology of Fuji Electric Co., Ltd

    International Nuclear Information System (INIS)

    Shirakawa, Masahiro; Takaya, Jyunichi; Mizukoshi, Seiji; Hosoda, Hiroshi; Tomizuka, Chiaki; Funaguchi, Susumu; Ito, Katsuhito

    1997-01-01

    Fuji Electric Co., Ltd. is conducting decommissioning R and D for commercial reactor, especially for gas cooled reactor since the construction of the Tokai-1 power station of JAPCO, in the field of system engineering, residual radioactivity evaluation, dismantling of core internals, remote handling, treatment and disposal of radioactive waste, and radioactivity measurement. These R and D have been performed mainly under contract of JAPCO and JAERI. This paper gives a summary of the present status and future plan concerning technical development for decommissioning of nuclear reactor by Fuji Electric Co., Ltd. (author)

  14. Approaches of Knowledge Management System for the Decommissioning of Nuclear Facilities

    International Nuclear Information System (INIS)

    Iguchi, Y.; Yanagihara, S.; Kato, Y.; Tezuka, M.; Koda, Y.

    2016-01-01

    Full text: The decommissioning of a nuclear facility is a long term project, handling information beginning with design, construction and operation. Moreover, the decommissioning project is likely to be extended because of the lack of the waste disposal site. In this situation, as the transfer of knowledge to the next generation is a crucial issue, approaches of knowledge management (KM) are necessary. For this purpose, the total system of decommissioning knowledge management system (KMS) is proposed. In this system, we should arrange, organize and systematize the data and information of the plant design, maintenance history, trouble events, waste management records etc. The collected data, information and records should be organized by computer support systems. It becomes a base of the explicit knowledge. Moreover, measures of extracting tacit knowledge from retiring employees are necessary. The experience of the retirees should be documented as much as possible through effective questionnaire or interview process. In this way, various KM approaches become an integrated KMS as a whole. The system should be used for daily accumulation of knowledge thorough the planning, implementation and evaluation of decommissioning activities and it will contribute to the transfer of knowledge. (author

  15. Rancho Seco--Decommissioning Update

    International Nuclear Information System (INIS)

    Newey, J. M.; Ronningen, E. T.; Snyder, M. W.

    2003-01-01

    The Rancho Seco Nuclear Generating Station ceased operation in June of 1989 and entered an extended period of SAFSTOR to allow funds to accumulate for dismantlement. Incremental dismantlement was begun in 1997 of steam systems and based on the successful completion of work, the Sacramento Municipal Utility District (SMUD) board of directors approved full decommissioning in July 1999. A schedule has been developed for completion of decommissioning by 2008, allowing decommissioning funds to accumulate until they are needed. Systems removal began in the Auxiliary Building in October of 1999 and in the Reactor Building in January of 2000. Systems dismantlement continues in the Reactor Building and should be completed by the end of 2003. System removal is near completion in the Auxiliary Building with removal of the final liquid waste tanks in progress. The spent fuel has been moved to dry storage in an onsite ISFSI, with completion on August 21, 2002. The spent fuel racks are currently being removed from the pool, packaged and shipped, and then the pool will be cleaned. Also in the last year the reactor coolant pumps and primary piping were removed and shipped. Characterization and planning work for the reactor vessel and internals is also in progress with various cut-up and/or disposal options being evaluated. In the year ahead the remaining systems in the Reactor Building will be removed, packaged and sent for disposal, including the pressurizer. Work will be started on embedded and underground piping and the large outdoor tanks. Building survey and decontamination will begin. RFP's for removal of the vessel and internals and the steam generators are planned to fix the cost of those components. If the costs are consistent with current estimates the work will go forward. If they are not, hardened SAFSTOR/entombment may be considered

  16. Decommissioning of offshore installations

    Energy Technology Data Exchange (ETDEWEB)

    Oeen, Sigrun; Iversen, Per Erik; Stokke, Reidunn; Nielsen, Frantz; Henriksen, Thor; Natvig, Henning; Dretvik, Oeystein; Martinsen, Finn; Bakke, Gunnstein

    2010-07-01

    New legislation on the handling and storage of radioactive substances came into force 1 January 2011. This version of the report is updated to reflect this new regulation and will therefore in some chapters differ from the Norwegian version (see NEI-NO--1660). The Ministry of the Environment commissioned the Climate and Pollution Agency to examine the environmental impacts associated with the decommissioning of offshore installations (demolition and recycling). This has involved an assessment of the volumes and types of waste material and of decommissioning capacity in Norway now and in the future. This report also presents proposals for measures and instruments to address environmental and other concerns that arise in connection with the decommissioning of offshore installations. At present, Norway has four decommissioning facilities for offshore installations, three of which are currently involved in decommissioning projects. Waste treatment plants of this kind are required to hold permits under the Pollution Control Act. The permit system allows the pollution control authority to tailor the requirements in a specific permit by evaluating conditions and limits for releases of pollutants on a case-to-case basis, and the Act also provides for requirements to be tightened up in line with the development of best available techniques (BAT). The environmental risks posed by decommissioning facilities are much the same as those from process industries and other waste treatment plants that are regulated by means of individual permits. Strict requirements are intended to ensure that environmental and health concerns are taken into account. The review of the four Norwegian decommissioning facilities in connection with this report shows that the degree to which requirements need to be tightened up varies from one facility to another. The permit for the Vats yard is newest and contains the strictest conditions. The Climate and Pollution Agency recommends a number of measures

  17. Research on decommissioning of nuclear facilities (Joint research)

    International Nuclear Information System (INIS)

    Shibahara, Yuji; Morishita, Yoshitsugu; Ishigami, Tsutomu; Yanagihara, Satoshi; Arita, Yuji

    2011-07-01

    To implement a decommissioning project reasonably, it is necessary and important to beforehand evaluate project management data as well as to select an optimum dismantling scenario among various scenarios postulated. Little study on the subject of selecting an optimum scenario has been carried out, and it is one of the most important subjects in terms of decision making. In FY 2009, Japan Atomic Energy Agency and University of Fukui launched the joint research of a decision making method which is important to determine a decommissioning plan. The purpose of the research is to construct a methodology for selecting an optimum dismantling scenario among various scenarios postulated based on calculated results of project management data for FUGEN. Project management data for several dismantling scenarios postulated at FUGEN were evaluated based on actual dismantling work for feed water heater at FUGEN, and an optimum scenario was discussed using the SMART, one of Multi-Criteria Decision Analysis Method. This report describes the results of the joint research in FY 2009. (author)

  18. Safety Assessment for Decommissioning of Nuclear Facilities - From Methodology to the Use of Results in Decision Making

    International Nuclear Information System (INIS)

    Batandjieva, B.; Ferch, R.; Joubert, A.; Kaulard, J.; Manson, P.; Percival, K.; Thierfeldt, St.

    2008-01-01

    The safety assessment of operational facilities in the nuclear industry is well understood and methodologies have been developed and refined over several decades. Similarly safety assessment methodologies for near surface disposal facilities have been harmonized internationally during the last few years. There is however relatively less widespread and documented experience of safety assessment for decommissioning among Member States of the International Atomic Energy Agency (IAEA) and consequently there is less commonalty of approaches internationally. The importance of safety during decommissioning was further emphasized at the first review meeting of the Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management, and the Berlin Conference 'Safe Decommissioning for Nuclear Activities' (14-18 October 2002). As a consequence during its June 2004 meeting the IAEA Board of Governors approved an Action Plan on Decommissioning of nuclear Facilities that requested the Secretariat to 'establish a forum for the sharing and exchange of national information and experience on the application of safety assessment in the context of decommissioning and provide a means to convey this information to other interested parties, also drawing on the work of other international organizations in this area'. In response the IAEA launched the International Project Evaluation and Demonstration of Safety during Decommissioning of Nuclear Facilities (DeSa) in November 2004 with the following objectives: - To develop a harmonized approach to safety assessment and define the elements of safety assessment for decommissioning; - To investigate the practical applicability of the methodology and performance of safety assessments for the decommissioning of various types of facilities through a selected number of test cases; - To investigate approaches for review of safety assessments for decommissioning activities and the development of a regulatory

  19. Atmospheric discharges from nuclear facilities during decommissioning: German experiences

    Energy Technology Data Exchange (ETDEWEB)

    Braun, H.; Goertz, R.; Weil, L.

    1997-08-01

    In Germany, a substantial amount of experience is available with planning, licensing and realization of decommissioning projects. In total, a number of 18 nuclear power plants including prototype facilities as well as 6 research reactors and 3 fuel cycle facilities have been shut down finally and are at different stages of decommissioning. Only recently the final {open_quotes}green field{close_quotes} stage of the Niederaichbach Nuclear Power Plant total dismantlement project has been achieved. From the regulatory point of view, a survey of the decommissioning experience in Germany is presented highlighting the aspects of production and retention of airborne radioactivity. Nuclear air cleaning technology, discharge limits prescribed in licences and actual discharges are presented. As compared to operation, the composition of the discharged radioactivity is different as well as the off-gas discharge rate. In practically all cases, there is no significant amount of short-lived radionuclides. The discussion further includes lessons learned, for example inadvertent discharges of radionuclides expected not to be in the plants inventory. It is demonstrated that, as for operation of nuclear power plants, the limits prescribed in the Ordinance on Radiological Protection can be met using existing air cleaning technology, Optimization of protection results in public exposures substantially below the limits. In the frame of the regulatory investigation programme a study has been conducted to assess the airborne radioactivity created during certain decommissioning activities like decontamination, segmentation and handling of contaminated or activated parts. The essential results of this study are presented, which are supposed to support planning for decommissioning, for LWRs, Co-60 and Cs-137 are expected to be the dominant radionuclides in airborne discharges. 18 refs., 2 figs., 1 tab.

  20. Project authorization process in the thermal power stations vs in the hydroelectric power stations: two weights, two measurements?

    International Nuclear Information System (INIS)

    Comtois, Y.

    2004-01-01

    Key topics include the long tendering process, a comparison of two projects: thermal station vs. hydroelectrical station, and the solutions towards reducing the delay in obtaining authorization. (author)