WorldWideScience

Sample records for siting licensing development

  1. Siting Practices and Site Licensing Process for New Reactors in Canada

    International Nuclear Information System (INIS)

    Vos, Marcel de

    2011-01-01

    'Siting' in Canada is composed of Site Evaluation and Site Selection. As outlined in CNSC Regulatory Document RD-346 Site Evaluation for New Nuclear Power Plants (based on IAEA NS-R-3), prior to the triggering of the Environmental Assessment (EA) and licensing processes, the proponent is expected to use a robust process to characterize proposed sites over the full life cycle of the facility, and then develop a fully documented defense of the site selection case. This case forms the backbone for submissions in support of the EA and the application for a License to Prepare Site which will be reviewed by the CNSC and other applicable federal authorities. The Environmental Assessment process and License to Prepare Site in Canada do not require a proponent to select a specific design; however, CNSC does not accept a 'black box' approach to siting. CNSC balances the level of design information required with the extent of safety assurance desired for any designs being contemplated for the proposed site. Nevertheless, the design information submitted must be sufficient to justify the site as suitable for all future licensing stages. The depth of plant design information contributes significantly to the credibility of the applicant's case for both the EA and application for License to Prepare Site. The review process utilizes an assessment plan with defined review stages and timelines. The outcome of these reviews is a series of recommendations to a federal government appointed Joint Review Panel (which also serves as a panel of the 'Commission') which, following public hearings, renders a decision regarding the EA, and subsequently, the application for a License to Prepare Site. (author)

  2. Mock Site Licensing Demonstration Project. Final report

    International Nuclear Information System (INIS)

    Roop, R.D.

    1986-06-01

    The Mock Site Licensing Demonstration Project developed the Low-Level Radioactive Waste Siting Simulation, a role-playing exercise designed to facilitate the process of siting and licensing disposal facilities for low-level waste (LLW). This report describes the development, contant, and usefulness of the siting simulation. The simulation was designed by Harvard University's Program on Negotiation; it can be conducted at a workshop or conference, involves 14 or more participants, and requires about eight hours to complete. The simulation consists of two sessions. In the first, participants negotiate the selection of siting criteria, and in the second, a preferred site for a facility is chosen from three candidate sites. The project sponsored two workshops (in Boston, Massachusetts and Richmond, Virginia) in which the simulation was conducted for persons involved in planning for LLW. It is concluded that the siting simulation can be useful in three ways: (1) as a tool for information dissemination, (2) as a vehicle that can foste communication among parties in conflict, and (3) as a step toward consensus building and conflict resolution. The DOE National Low-Level Waste Management Program is now making the siting simulation available for use by states, regional compacts, and other organizations involved in development of LLW disposal facilities

  3. Licensing plan for UMTRA project disposal sites

    International Nuclear Information System (INIS)

    1993-09-01

    The Uranium Mill Tailings Remedial Action (UMTRA) Project Office developed a plan to define UMTRA Project licensing program objectives and establish a process enabling the DOE to document completion of remedial actions in compliance with 40 CFR 1 92 and the requirements of the NRC general license. This document supersedes the January 1987 Project Licensing Plan (DOE, 1987). The plan summarizes the legislative and regulatory basis for licensing, identifies participating agencies and their roles and responsibilities, defines key activities and milestones in the licensing process, and details the coordination of these activities. This plan provides an overview of the UMTRA Project from the end of remedial actions through the NRC's acceptance of a disposal site under the general license. The licensing process integrates large phases of the UMTRA Project. Other programmatic UMTRA Project documents listed in Section 6.0 provide supporting information

  4. Post-TMI developments in U.S. nuclear power siting and licensing policies

    International Nuclear Information System (INIS)

    Rowden, M.A.

    1981-10-01

    The regulatory consequences of the Three Mile Island accident continue to exert a dominating influence on the American nuclear power programme, in particular on siting and licensing policies. The major regulatory and legislative measures are discussed and also listed in chronological order and summarized in the Appendices to the paper. These summaries illustrate the shift in focus of the regulatory measures from an initial emphasis on licensing constraints to a change so as to expedite the licensing procedure. (NEA) [fr

  5. Project licensing plan for UMTRA [Uranium Mill Tailings Remedial Action] sites

    International Nuclear Information System (INIS)

    1984-07-01

    The purpose of the Uranium Mill Tailings Remedial Action (UMTRA) Project Licensing Plan is to establish how a disposal site will be licensed, and to provide responsibilities of participatory agencies as legislated by the Uranium Mill Tailings Radiation Control Act (UMTRCA) of 1978 (Public Law 95-604). This Plan has been developed to ensure that the objectives of licensing are met by identifying the necessary institutional controls, participatory agency responsibilities, and key milestones in the licensing process. The Plan contains the legislative basis for and a description of the licensing process (''Process'') for UMTRA sites. This is followed by a discussion of agency responsibilities, and milestones in the Process. The Plan concludes with a generic timeline of this Process. As discussed in Section 2.1, a custodial maintenance and surveillance plan will constitute the basis for a site license. The details of maintenance and surveillance are discussed in the Project Maintenance and Surveillance Plan (AL-350124.0000). 5 refs., 4 figs

  6. Site Specific Vendor's License

    Data.gov (United States)

    Montgomery County of Maryland — This dataset contains information of a site-specific vendor's license which is required if an individual sells or offers to sell goods or services from a stationary...

  7. PROCESS FOR LICENSE APPLICATION DEVELOPMENT FOR THE GEOLOGIC REPOSITORY

    International Nuclear Information System (INIS)

    DOUGLAS M. FRANKS AND NORMAN C. HENDERSON

    1997-01-01

    The Department of Energy (DOE), specifically the Office of Civilian Radioactive Waste Management (OCRWM) has been charged by the U.S. Congress, through the Nuclear Waste Policy Act (NWPA), with the responsibility for obtaining a license to develop a geologic repository. The NRC is the licensing authority for geologic disposal, and its regulations pertinent to construction authorization and license application are specified in 10 CFR Part 60, Disposal of High-Level Radioactive Wastes in Geologic Repositories, (section)60.21ff and (section)60.31ff. This paper discusses the process the Yucca Mountain Site Site Characterization Project (YMP) will use to identify and apply regulatory and industry guidance to development of the license application (LA) for a geologic repository at Yucca Mountain, Nevada. This guidance will be implemented by the ''Technical Guidance Document for Preparation of the License Application'' (TGD), currently in development

  8. The site-characterization plan and its role in resolving siting and licensing issues

    International Nuclear Information System (INIS)

    Hanlon, C.L.

    1986-01-01

    As required by the Nuclear Waste Policy Act and the Nuclear Regulatory Commission (NRC) in 10 CFR Part 60, the Department of Energy is preparing plans for conducting site characterization at three candidate sites. Prepared according to a detailed annotated outline that is based on the NRC's Regulatory Guide 4.17, these plans will present the information collected to date about the geologic, hydrologic, geochemical, geoengineering, and climatic conditions of each site; describe the design of the repository and the waste package; and discuss the site-characterization program. The most important portions of the plan will be the strategy for resolving siting and licensing issues and the description of the testing and analysis program to be followed in resolving these issues. The issues-resolution strategy consists of identifying issues and the associated information needs; allocating performance goals for various components of the repository system; developing a testing plan to gather the necessary information; gathering and analyzing the information; and documenting the results for use in site selection and licensing. The issues-resolution strategy will allow the Department to define all of the issues that must be resolved in order to demonstrate compliance with applicable regulations and to specify the information needed to resolve these issues. It will provide a consistent framework and establish priorities for the Department's site-characterization effort for the next several years

  9. Nebraska withdraws its intent to deny site license

    International Nuclear Information System (INIS)

    Anon.

    1993-01-01

    The state of Nebraska has withdrawn its notice of intent to deny the US Ecology (USE) license application for the proposed low-level radioactive waste disposal site in Boyd County, near Butte, Neb. On October 4, after review of USE's August 27 submittal of a revision to the boundaries of the proposed site, a letter from the state's Department of Health (DOH) and Department of Environmental Quality (DEQ) to John. H. DeOld, the USE project manager for the Central Interstate Compact's proposed LLW site, noted that open-quotes...we are hereby withdrawing the Notice of Intent to Deny License as a moot, and will conduct a substantive review of the reconfigured site for compliance with the applicable regulations.close quotes

  10. The Texas concurrent characterization, licensing, and development process

    Energy Technology Data Exchange (ETDEWEB)

    Avant, R.V. Jr. [Texas Low-Level Radioactive Waste Disposal Authority, Austin, TX (United States)

    1993-03-01

    The 72nd Texas Legislature specifically delineated a 400-square-mile area in southeast Hudspeth County where siting activities would be limited. The Authority was given unprecedented powers of property access and eminent domain and expanded budget authority to conduct site selection, characterization, and licensing. In the summer of 1991, the Authority identified five general siting areas in the prescribed region, and in the fall of 1991, the Authority narrowed the siting area to one large ranch composed of about 16,000 acres--called the Faskin Ranch. Site characterization began in 1991 and will be complete by September 1993. In September 1991, Authority staff began preparing the license application and included all available information on the Faskin Ranch. At its February meeting, the Authority`s board directed staff to submit the license application to the Texas Water Commission (the new Texas radiation control agency). The license application was submitted on March 2, 1992, and on April 15, 1992, the Commission determined that the application was sufficiently complete to begin review. Discrete technical packages such as groundwater hydrology, surface water hydrology, design, etc., will be submitted to the agency for review on the completion of each package. A schedule has been developed to allow the regulators the maximum time possible to review critical technical areas while minimizing the total review period.

  11. Process for license application development for the geologic repository

    International Nuclear Information System (INIS)

    Franks, D.M.; Henderson, N.C.

    1998-01-01

    The Department of Energy (DOE), specifically the Office of Civilian Radioactive Waste Management (OCRWM) has been charged by the US Congress, through the Nuclear Waste Policy Act (NWPA), with the responsibility for obtaining a license to develop a geologic repository. The NRC is the licensing authority for geologic disposal, and its regulations pertinent to construction authorization and license application are specified in 10 CFR Part 60, Disposal of High-Level Radioactive Wastes in Geologic Repositories, section 60.21ff and section 60.31ff. This paper discusses the process the Yucca Mountain Site Characterization Project (YMP) will use to identify and apply regulatory and industry guidance to development of the license application (LA) for a geologic repository at Yucca Mountain, Nevada. This guidance will be implemented by the Technical Guidance Document for Preparation of the License Application (TGD), currently in development

  12. New Reactor Siting, Licensing and Construction Experience. Proceedings of the 2. CNRA International Workshop on 'New Reactor Siting, Licensing and Construction Experience'

    International Nuclear Information System (INIS)

    2013-01-01

    This report documents the proceedings from the 2. Workshop on New Reactor Siting, Licensing and Construction Experience. A total of 45 specialists from 16 countries and international organisations attended. The meeting was sponsored by the OECD Nuclear Energy Agency Committee on Nuclear Regulatory Activities and hosted by the US Nuclear Regulatory Commission (U.S.NRC). The objectives of the workshop were to provide a forum to exchange information on lessons learned from siting, licensing and constructing new nuclear power plants around the world. Key focus areas included siting practices and regulatory positions that have been enhanced as a result of the Fukushima accident; lessons learned from licensing and design review approaches and challenges, construction experience and recommendations for regulatory oversight; and regulatory cooperation on generic and design specific issues through the MDEP specific working groups. The workshop was structured in 4 technical sessions, each followed by ample time for panel discussions. The first technical session was devoted to regulatory cooperation on generic and design specific issues, MDEP working groups (EPR, AP1000), vendor inspection co-operation, digital I and C, and codes and standards. The second technical session was intended to discuss and share regulatory positions on siting practices and enhancements as a result of lessons learned from Fukushima accident. The third technical session addressed the construction experience and regulatory oversight of new reactor construction activities. And the fourth technical session included presentations on the lessons learned from regulatory licensing reviews of new reactor designs

  13. Completion of decommissioning: Monitoring for site release and license termination

    International Nuclear Information System (INIS)

    Boing, L.E.

    1997-01-01

    To request termination of a license upon completion of dismantling or decommissioning activities, documenting any residual radioactivity to show that the levels are environmentally acceptable will be necessary. When the regulators approve the decommissioning plan, they establish what the release criteria for the decommissioned site will be at the time of the site release and license termination. The criteria are numeric guidelines for direct radiation in soils and on surfaces. If the regulatory body finds that the measured on-site values are below the guidelines, the site will be acceptable for unrestricted release (no radiological controls or future use). If areas are found above those values, more decontamination or cleanup of these areas may be required unless the regulatory body grants an exemption

  14. The National Site Licensing of Electronic Resources: An Institutional Perspective

    Directory of Open Access Journals (Sweden)

    Xiaohua Zhu

    2011-06-01

    Full Text Available While academic libraries in most countries are struggling to negotiate with publishers and vendors individually or collaboratively via consortia, a few countries have experimented with a different model, national site licensing (NSL. Because NSL often involves government and large-scale collaboration, it has the potential to solve many problems in the complex licensing world. However, not many nations have adopted it. This study uses historical research approach and the comparative case study research method to explore the seemingly low level of adoption. The cases include the Canadian National Site Licensing Project (CNSLP, the United Kingdom’s National Electronic Site Licensing Initiative (NESLI, and the United States, which has not adopted NSL. The theoretical framework guiding the research design and data collection is W. Richard Scott’s institutional theory, which utilizes three supporting pillars—regulative, normative, and cultural-cognitive—to analyze institutional processes. In this study, the regulative pillar and the normative pillar of NSL adoption— an institutional construction and change—are examined. Data were collected from monographs, research articles, government documents, and relevant websites. Based on the analysis of these cases, a preliminary model is proposed for the adoption of NSL. The factors that support a country’s adoption of NSL include the need for new institutions, a centralized educational policy-making system and funding system, supportive political trends, and the tradition of cooperation. The factors that may prevent a country from adopting NSL include decentralized educational policy and funding, diversity and the large number of institutions, the concern for the “Big Deal,” and the concern for monopoly.

  15. Cask development, testing, and licensing

    International Nuclear Information System (INIS)

    Quinn, G.J.; Haelsig, R.T.; Warrant, M.M.

    1986-01-01

    The NuPac 125-B Rail Cask was developed to provide a safe means of transporting the damaged core of Three Mile Island Unit 2 from the TMI site at Middletown, PA, to the Idaho National Engineering laboratory (INEL) at Idaho Falls, ID. The development of the NuPac 125-B Rail Cask posed two engineering and technical management challenges; Licensing Strategy - The NuPac 125-B Rail Cask represented the first irradiated fuel rail cask developed within the United States in the past decade, a decade characterized by changing nuclear regulations, and Accelerated Schedule - The TMI-2 defueling schedule demanded a cask development schedule one-third as long as normally required. These challenges governed the overall development and licensing process for the cask. First, a high degree of conservation was incorporated into the design to allow quick, simplified demonstrations of adequacy to regulatory staff. Second, redundant design techniques were employed in all areas of uncertainty. The testing program eliminated performance uncertainties and validated predictions and predictive models. Drop tests of a quarter-scale model of the cask were conducted, and results were correlated with analytic predictions to verify structural and mechanical performance of the cask. Full-scale tests of the canisters were conducted to verify structural behavior of canister internals which provide criticality control. This paper describes the testing program for the NuPac 125-B Rail Cask, presents results therefrom, and correlates findings with Regulation 10 CFR 71 of the U.S. Nuclear Regulatory Commission

  16. Off-site preparedness and nuclear-power-plant licensing

    International Nuclear Information System (INIS)

    Perry, S.W.

    1983-01-01

    The first year and a half in which off-site emergency preparedness issues have been litigated before the Atomic Safety and Licensing Boards of the NRC have surfaced unique problems of proof for the applicant as well as the staff. These problems seem to be abating as the boards and the parties become more comfortable with the field and its issues, and as FEMA-NRC emergency management expertise gains credibility. Emergency preparedness presentations have also improved as the parties have become more sensitive to the seasonality of the preparedness case, and have increasingly attempted to raise it at a time when a fully developed set of facts is available for the record. Off-site preparedness issues are only now beginning to be raised on appeal to the NRC appeals board, the full commission, and the courts. Helpful guidance on what constitutes an adequate record in this area will undoubtedly be forthcoming in decisions handed down by these bodies in the months ahead

  17. Nuclear power plant attempts in Turkey and the first licensed site

    International Nuclear Information System (INIS)

    Bektur, Y.; Bezdegumeli, U.

    2004-01-01

    In this paper, detailed information regarding Turkey's past attempts for the construction of a nuclear power plant (NPP) and site survey studies conducted for this plant is given. Also, some important characteristics of the first licensed site, namely Akkuyu, are summarized. There were four attempts made for the construction of an NPP in the past. However, all of them failed due to technical, economical and/or some other reasons. Akkuyu site has been selected among around 25 candidate sites for the reasons that bulky materials can be transported there by sea; it is located near the major electricity demand centers; soil-structure interaction and slab stability are suitable for the construction of an NPP; its surrounding is one of the most sparsely populated areas of Turkey; and it is seismically the most stable region in earthquake-prone Turkey, e.g. Turkish Electricity Authority (TEK) was granted a site license for the Akkuyu in 1976. (author)

  18. Design/licensing of on-site package for core component

    International Nuclear Information System (INIS)

    Ogasawara, K.; Chohzuka, T.; Shimura, T.; Kikuchi, T.; Fujiwara, R.; Karigome, S.; Takani, M.

    1993-01-01

    For storage of used core components which are produced from reactors, Tohoku EPCO decided to construct a site bunker at Onagawa site. It was also decided to develop and fabricate one packaging to transport core components from the reactor buildings to the site bunker. The packaging will be used within the power station; therefore, it shall comply with 'The Law for the Business of Electric Power' and relevant Notification. The main requirements of the packaging are as follows: 1) The number of contents, such as channel boxes and control rods, shall be as large as possible. 2) The weight and the outer dimensions of the packaging shall be within the limitation of the reactor building and the site bunker. 3) Materials shall be selected from those which have been already applied for existing packagings and utilized without any problems. 4) It shall be considered during design of trunnions that handling equipment, such as lifting beam, can be used for not only this packaging but also for existing spent fuel packagings. The design of the packaging is completed and has been licensed. The packaging is scheduled to be utilized from November, 1993. (J.P.N.)

  19. Estimation of expenses for low and intermediate level radioactive waste repository project in Croatia up to site license acquisition

    International Nuclear Information System (INIS)

    Schaller, A.; Lokner, V.; Subasic, D.

    2003-01-01

    The expenses needed for development of low- and intermediate level radioactive waste (LILW) repository project in Croatia include: (a) preliminary activities, (b) preparatory activities, and (c) preparing of environmental impact study. The first group of expenses are referring to the project leading activities, project plan updating, build-up of required infrastructure, preparing of licensing documentation, site investigations, data acquisition programme, pre-operational radio-ecological monitoring, modelling, safety analysis (first iteration) and public related activities. Preparatory activities are referring to purchasing of land for repository and preparatory activities for carrying out of on-site investigations, while third group of expenses are related to preparation and validation of Environmental impact study. It was found out that about 50 % of total expenses refer to build-up of infrastructure. Additional 25 % finances are related to radio-ecological monitoring, site investigations and development of calculations and models, while remaining 25 % of total estimated sum is expected to be spent for repository safety assessment, public relations, purchasing and preparing the on-site terrain for construction, etc. It was calculated 607 EUR per m3 of LILW to be needed up to site license acquisition. According to the world-wide practice, by extrapolating of additional expenses necessary for construction of the repository and acquisition of operational license, it comes out the cost of 1.723 EUR per m3 of LILW for shallow-ground and 2.412 EUR per m3 of LILW for tunnel repository. The estimated expenses for Croatia are within the span of expenses for the same purpose in the countries considered. Expected duration of the project performance up to acquisition of the site license is 4 years and 3 months. (author)

  20. California LLW disposal site development update: Ahead of milestone schedule

    International Nuclear Information System (INIS)

    Romano, S.A.; Gaynor, R.K.

    1987-01-01

    US Ecology has been designated by the State of California to locate, develop and operate a low-level radioactive waste disposal facility. In early 1986, the firm identified eighteen desert basins in southeastern California for siting consideration. Three candidate sites were selected for detailed field characterization work in February, 1987. A preferred site for licensing purposes will be identified in early 1988. California is currently ahead of the siting milestone schedule mandated by the Low-Level Radioactive Waste Policy Amendments Act. It is likely that a license application will be filed before the 1990 milestone date. This paper describes the process undertaken by US Ecology to identify three candidates sites for characterization, and the public involvement program supporting this decision. Future activities leading to final site development are also described

  1. ITER licensing

    International Nuclear Information System (INIS)

    Gordon, C.W.

    2005-01-01

    ITER was fortunate to have four countries interested in ITER siting to the point where licensing discussions were initiated. This experience uncovered the challenges of licensing a first of a kind, fusion machine under different licensing regimes and helped prepare the way for the site specific licensing process. These initial steps in licensing ITER have allowed for refining the safety case and provide confidence that the design and safety approach will be licensable. With site-specific licensing underway, the necessary regulatory submissions have been defined and are well on the way to being completed. Of course, there is still work to be done and details to be sorted out. However, the informal international discussions to bring both the proponent and regulatory authority up to a common level of understanding have laid the foundation for a licensing process that should proceed smoothly. This paper provides observations from the perspective of the International Team. (author)

  2. Proceedings of the CNRA Workshop on New Reactor Siting, Licensing and Construction Experience

    International Nuclear Information System (INIS)

    2011-01-01

    This report documents the proceedings from the 'Workshop on New Reactor Siting, Licensing and Construction Experience', held in Prague, Czech Republic on 15-17 September 2010. A total of 59 specialists from 16 countries and international organisations attended. The Meeting was sponsored by the OECD Nuclear Energy Agency Committee on Nuclear Regulatory Activities and hosted by the State Office for Nuclear Safety (SUJB) in Czech Republic. The objectives of the workshop were to review and discuss recent and past construction experience lessons learned including perspectives from regulatory authorities, as well as vendors, and licensee. The workshop addressed issues associated with project management resources including: a) overall human resources, expertise, experience and organisation available to the licensee, b) capability of each potential vendor (in-house knowledge and skills versus planned subcontracting and subcontractor management). The workshop also discussed the lessons learned in the regulation of site selection, evaluation and site preparation as well as the review of regulatory practices for the licensing of new reactors, including the regulatory body infrastructure, staffing and expertise needed. The workshop provided an excellent opportunity to communicate recent experience on these topics to a wider audience, including participants from OECD member countries as well as New Entrants from non-OECD member countries. The workshop allowed the WGRNR group to introduce and discuss the current programme of work and products under development in order to gain insights from workshop participants on each of the programme of work areas, and get feedback on additional focus areas. The workshop was structured in 4 technical sessions, each followed by ample time for panel discussions. The first technical session was devoted to presentations of the licensing process for new reactors followed by different member countries. The second technical session was

  3. The SLOWPOKE licensing model

    Energy Technology Data Exchange (ETDEWEB)

    Snell, V. G.; Takats, F.; Szivos, K.

    1989-08-15

    The SLOWPOKE Energy System (SES-10) is a 10 MW heating reactor that has been developed in Canada. It will be capable of running without a licensed operator in continuous attendance, and will be sited in urban areas. It has forgiving safety characteristics, including transient time-scales of the order of hours. A process called `up-front` licensing has been evolved in Canada to identify, and resolve, regulatory concerns early in the process. Because of the potential market in Hungary for nuclear district heating, a licensing plan has been developed that incorporates Canadian licensing experience, identifies specific Hungarian requirements, and reduces the risk of licensing delays by seeking agreement of all parties at an early stage in the program.

  4. Development and licensing of a melting plant for Chernobyl scrap

    International Nuclear Information System (INIS)

    Sappok, M.; Zunk, H.; Fashevsky, K.A.

    1998-01-01

    One decade after the accident at unit 4 of the Chernobyl nuclear power station, a melting plant for radioactively contaminated metallic materials, the so-called SURF facility, is being planned and licensed for erection in the direct neighbourhood of the NPP area. Main goal is the recycling of the material largely decontaminated by the melting process, by means of manufacturing of casks and containers for waste disposal and of shielding equipment. The melting plant will be part of the Ukrainian waste handling centre (CPPRO). The technology is based on the long-term experience gained at Siempelkamp's CARLA plant in Krefeld. Within 1995 and 1996 the licensing conditions were defined, the licensing documents prepared and the formal procedure initiated. The complex is scheduled to start operation in 2001, in case the necessary financing is allocated. To this end the proposed site of the facility has undergone the state assessment. The technical documentation for construction is at the stage of development. (author)

  5. Site suitability, selection and characterization: Branch technical position--Low-Level Waste Licensing Branch

    International Nuclear Information System (INIS)

    Siefken, D.; Pangburn, G.; Pennifill, R.; Starmer, R.J.

    1982-04-01

    The staff provides an expanded interpretation of the site suitability requirements in the proposed rule 10 CFR Part 61, a description of the anticipated site selection process, and a detailed discussion of the site characterization program needed to support a license application and environmental report. The paper provides early-on guidance to prospective applicants in these three subject areas

  6. WIPP - Pre-Licensing and Operations: Developer and Regulator Perspectives

    International Nuclear Information System (INIS)

    Peake, Tom; Patterson, R.

    2014-01-01

    The Waste Isolation Pilot Plant (WIPP) is a disposal system for defense-related transuranic (TRU) radioactive waste. Developed by the Department of Energy (DOE), WIPP is located in Southeastern New Mexico: radioactive waste is disposed of 2,150 feet underground in an ancient layer of salt with a total capacity of 6.2 million cubic feet of waste. Congress authorized the development and construction of WIPP in 1980 for the express purpose of providing a research and development facility to demonstrate the safe disposal of radioactive wastes resulting from the defense activities and programs of the United States. This paper makes a historical review of the site development, site operations (waste disposal operations started in 1999), communications between US EPA and DOE, the chronology of pre-licensing and pre-operations, the operational phase and the regulatory challenges, and the lessons learned after 12 years of operations

  7. Licensing and accident reviews for an HNEC

    International Nuclear Information System (INIS)

    Clark, R.G.

    1978-09-01

    The purpose of this review was to identify siting or other concerns that may indicate limitations on the ability to license a nuclear energy center at Hanford. Several studies on nuclear energy centers have been completed and some have included licensing (regulatory) aspects of siting nuclear power centers. This review however, was primarily to identify any limitations that may affect licensing specifically at an HNEC. The scope included examining existing criteria for siting nuclear facilities, including single reactor and multireactor (multi-unit) sites. To fill a void in other analyses and to gain some perspective on another impact of an HNEC, the scope was extended to analyze the consequences within the HNEC, of a class nine accident at a unit at one site. A predictive model utilized in this analysis was developed from meteorological parameters based on thirty years of meteorological records at Hanford. From this analysis, additional perspective was developed on the relative severity of the effects of rare events, both man made and from unstable conditions in nature, on the operation of (and the ability to license) an energy center at Hanford

  8. Licensing of New Nuclear Power Plants in Canada

    International Nuclear Information System (INIS)

    Schwarz, Garry; Miller, Doug

    2011-01-01

    The regulatory process for new power plant licensing in Canada, from receipt of the initial application to commercial operation, can be divided into three phases: - Environmental Assessment (EA) and License to Prepare Site; - License to Construct; and - License to Operate. The Nuclear Safety and Control Act (NSCA) does not have provisions for combined licenses for site preparation, construction, or operation. Separate licenses must, therefore, be granted for each phase, and would be issued in sequence. However, applications to prepare a site, to construct and to operate a new nuclear power plant could be assessed in parallel. The total duration from the application for the License to Prepare Site to the issuance of the License to Operate (which is a prerequisite for first fuel load) has been established as 9 years subject to certain factors. To help facilitate this timeline, the CNSC has undertaken an aggressive program of documenting regulatory practices, requirements and guidance to assist applicants in submitting complete applications. Working level procedures to assist CNSC staff in their review of submissions are also under development. Extensive program and project management has been introduced to ensure that timelines will be achieved. In parallel with the above activities, regulatory oversight measures to be employed during site preparation activities and plant construction and commissioning are also being developed. On the international front, the CNSC is participating in the MDEP program to leverage the resources and knowledge of other national regulatory authorities in reviews the CNSC is undertaking. The CNSC also participates in IAEA and other international activities to utilize/adapt international practices as appropriate in Canada. (authors)

  9. Establishment of regulatory framework for the development reactor licensing

    International Nuclear Information System (INIS)

    Jo, Jong C.; Yune, Young G.; Kim, Woong S.; Ahn, Sang K.; Kim, In G.; Kim, Hho J.

    2003-01-01

    With a trend that various types of advanced reactor designs are currently under development worldwide, the Korea Atomic Energy Research Institute has been developing an advanced reactor called ' System-integrated Modular Advanced Reactor (SMART)', which is a small sized integral type pressurized water reactor with a rated thermal power of 330 MW. To demonstrate the safety and the performance of the SMART reactor design, the SMART Research and Development Center has embarked to build a scaled-down pilot plant of SMART, called 'SMART-P' with a rated thermal power of 65 MW. In preparation for the forthcoming applications for both construction permit and operating license of SMART-P in the near future, the Korea Institute of Nuclear Safety is developing a new regulatory framework for licensing review of such a development reactor, which covers establishment of licensing process, identification and resolution of technical and safety issues, development of regulatory evaluation or verification-purpose computer codes and analytical methods, and establishment of design-specific, general design and operating criteria, regulations, and associated regulatory guides. This paper presents the current activities for establishing a regulatory framework for the licensing of a research and development reactor. Discussions are made on the SMART-P development program, the current Korean regulatory framework for reactor licensing, the SMART-P licensing-related issues, and the approach and strategy for developing an effective regulatory framework for the SMART-P licensing

  10. Evaluation of Terminated Nuclear Material Licenses

    International Nuclear Information System (INIS)

    Spencer, K.M.; Zeighami, E.A.

    1999-01-01

    This report presents the results of a six-year project that reviewed material licenses that had been terminated during the period from inception of licensing until approximately late-1994. The material licenses covered in the review project were Part 30, byproduct material licenses; Part 40, source material licenses; and Part 70, special nuclear material licenses. This report describes the methodology developed for the project, summarizes the findings of the license file inventory process, and describes the findings of the reviews or evaluations of the license files. The evaluation identified nuclear material use sites that need review of the licensing material or more direct follow-up of some type. The review process also identified licenses authorized to possess sealed sources for which there was incomplete or missing documentation of the fate of the sources

  11. A new approach to the nuclear power plant site licensing

    Energy Technology Data Exchange (ETDEWEB)

    Kidron, A A [Israel Electric Corp. Ltd., Haifa (Israel)

    1996-12-01

    The Israel Electric Corporation Ltd.(IEC) conducted a survey to determine the geotechnical suitability of the Shivta Site for the purpose of erecting a Nuclear Power Station and presented the results in a Preliminary Safety Analysis Report (PSAR) to the Licensing Division of the Israel Atomic Energy Commission (LD). The studies for selecting a site in the NW Negev were conducted by multi-disciplinary teams of Israeli and US professionals, beginning in 1982, over a twelve-year period. The investigations involved comprehensive geological, geophysical, geotechnical, hydrological, as well as geomorphic and pedologic evaluations of the region and the then- proposed site locale. The prior studies were completed using highly advanced and modern tools and approaches and provided a significant amount of information related to the tectonic and seismic characteristics of the NW Negev region. (author).

  12. License application approach for the California LLRW disposal facility

    International Nuclear Information System (INIS)

    Gaynor, R.K.; Romano, S.A.; Hanrahan, T.P.

    1990-01-01

    US Ecology, Inc. is the State of California's license designee to site, develop and operate a low-level radioactive waste (LLRW) disposal facility to serve member states of the Southwestern Compact. US Ecology identified a proposed site in the Ward Valley of southeastern California in March 1988. Following proposed site selection, US Ecology undertook studies required to prepare a license application. US Ecology's license application for this desert site was deemed complete for detailed regulatory review by the California Department of Health Services (DHS) in December 1989. By mutual agreement, disposal of mixed waste is not proposed pending the State of California's decision on appropriate management of this small LLRW subset

  13. THE DECISION TO RECOMMEND YUCCA MOUNTAIN AND THE NEXT STEPS TOWARD LICENSED REPOSITORY DEVELOPMENT

    International Nuclear Information System (INIS)

    Barrett, L. H.

    2002-01-01

    After more than 20 years of carefully planned and reviewed scientific field work by the U.S. Department of Energy, the U.S. Geological Survey, and numerous other organizations, Secretary of Energy Abraham concluded in January that the Yucca Mountain site is suitable, within the meaning of the Nuclear Waste Policy Act, for development as a permanent nuclear waste and spent fuel repository. In February, the Secretary recommended to the President that the site be developed for licensed disposal of these wastes, and the President transmitted this recommendation to Congress. This paper summarizes key technical and national interest considerations that provided the basis for the recommendation. It also discusses the program's near-term plans for repository development if Congress designates the site

  14. Licensing procedures for Low-Level Waste disposal facilities

    International Nuclear Information System (INIS)

    Roop, R.D.; Van Dyke, J.W.

    1985-09-01

    This report describes the procedures applicable to siting and licensing of disposal facilities for low-level radioactive wastes. Primary emphasis is placed on those procedures which are required by regulations, but to the extent possible, non-mandatory activities which will facilitate siting and licensing are also considered. The report provides an overview of how the procedural and technical requirements for a low-level waste (LLW) disposal facility (as defined by the Nuclear Regulatory Commission's Rules 10 CFR Parts 2, 51, and 61) may be integrated with activities to reduce and resolve conflict generated by the proposed siting of a facility. General procedures are described for site screening and selection, site characterization, site evaluation, and preparation of the license application; specific procedures for several individual states are discussed. The report also examines the steps involved in the formal licensing process, including docketing and initial processing, preparation of an environmental impact statement, technical review, hearings, and decisions. It is concluded that development of effective communication between parties in conflict and the utilization of techniques to manage and resolve conflicts represent perhaps the most significant challenge for the people involved in LLW disposal in the next decade. 18 refs., 6 figs

  15. Delivering Regulatory Consents for Decommissioning and Restoration of the Dounreay Nuclear Licensed Site

    International Nuclear Information System (INIS)

    Crawford, R.W.; Zyda, P.W.

    2006-01-01

    On behalf of the Nuclear Decommissioning Authority (NDA) the United Kingdom Atomic Energy Authority (UKAEA) has implemented a strategy to translate the near-term Dounreay restoration plan into a suite of land use documents designed to deliver the necessary planning consents to decommission and restore the Dounreay Nuclear Licensed Site. The legal consents and authorizations required to enable UKAEA to commence major projects and progress the decommissioning of the site are highlighted along with the measures taken to secure political, public and regulatory acceptance at the earliest opportunity. The approach taken by UKAEA is explained, focusing particularly on the critical need to secure planning permission and stakeholder approval well before the onset of construction works. The intention is to realize the benefits of forging a close working relationship with the land use regulator, The Highland Council. UKAEA has taken an approach to suitably inform the planning authority, in particular, the production of the Dounreay Planning Framework (DPF) document. This paper describes the role and need for the DPF, focusing on the key purpose of amending the local development plan to secure supportive planning policies and to set a land use context for the subsequent site decommissioning and restoration. This also has the advantage of securing public acceptance through an established legal process. Strategic milestones subsequent to the Highland Council's adoption of the DPF are highlighted, including the submission of phased planning applications and compliance with environmental legislation generally. The paper describes and underscores the need for early engagement of other regulators in the planning process such as the Scottish Environment Protection Agency (SEPA), and the safety regulator, the Nuclear Installations Inspectorate (NII). It describes the linkages amongst land use consents, Best Practicable Environmental Options (BPEO), radioactive substances

  16. Licensing procedures for Low-Level Waste disposal facilities

    Energy Technology Data Exchange (ETDEWEB)

    Roop, R.D.; Van Dyke, J.W.

    1985-09-01

    This report describes the procedures applicable to siting and licensing of disposal facilities for low-level radioactive wastes. Primary emphasis is placed on those procedures which are required by regulations, but to the extent possible, non-mandatory activities which will facilitate siting and licensing are also considered. The report provides an overview of how the procedural and technical requirements for a low-level waste (LLW) disposal facility (as defined by the Nuclear Regulatory Commission's Rules 10 CFR Parts 2, 51, and 61) may be integrated with activities to reduce and resolve conflict generated by the proposed siting of a facility. General procedures are described for site screening and selection, site characterization, site evaluation, and preparation of the license application; specific procedures for several individual states are discussed. The report also examines the steps involved in the formal licensing process, including docketing and initial processing, preparation of an environmental impact statement, technical review, hearings, and decisions. It is concluded that development of effective communication between parties in conflict and the utilization of techniques to manage and resolve conflicts represent perhaps the most significant challenge for the people involved in LLW disposal in the next decade. 18 refs., 6 figs.

  17. Radioactive liquid waste discharged from Nuclear Electric licensed sites during 1991

    International Nuclear Information System (INIS)

    Austin, L.S.; Odell, K.J.

    1993-03-01

    This report presents the detailed isotopic composition of radioactive liquid waste discharged from Nuclear Electric licensed sites in 1991. Liquid discharges from those Magnox stations using pond storage of irradiated fuel contained low levels of activation and fission products, while those from Wylfa and the AGR stations contained lower levels of activation products with only traces of fission products. Discharges were similar to those observed in previous years, with any changes concordant with changes in stations' generation performance. (author)

  18. Development of radioactive waste management licensing review assistant

    International Nuclear Information System (INIS)

    Loa, W.W.; Chen, S.; Yu, W.C.; Peng, C.M.; Huang, C.L.; Lin, C.

    1992-01-01

    Regulations on radioactive waste disposal are now in urgent need due to our increasing consumption of electric power from nuclear origin. It is set forth that actually applying the regulations to evaluate the license application of new repositories for interim storage and final disposal fo High-Level Waste and Low-Level Waste before the year of 2000. In the mean time, it is expected to establish the basis for the decision on issuing the license. The license review procedure can be very complicated because too many factors must be taken into consideration. However, to maintain a more efficient, accurate, and systematic review procedure, and at the same time to reduce costs, the Artificial Intelligence (AI) techniques may be used. An expert system is designed as a radioactive waste management licensing review aid for the staff those are in charge of the license application. Tasks such as completeness checking, functional areas of review distribution, participation confirmation, knowledge acquisition, review comment collection, weighting calculation, and degree of satisfaction are considered. In this paper the authors will discuss the development of the radioactive waste management licensing review assistant

  19. An economic perspective on software licenses--open source, maintainers and user-developers

    DEFF Research Database (Denmark)

    Edwards, Kasper

    2005-01-01

    This paper presents a model for understanding behaviour of agents using and/or contributing to open source software. The model illustrates behaviour of agents under three licenses regimes: 1) The GPL, The BSD and 3) The Microsoft EULA. The latter license is not an open source license...... licenses induce different incentives and dynamics for maintainer and user-developer and the paper explains, from an economic standpoint, the mechanisms that ensure programs are developed and maintained under the three license regimes....

  20. Development of Advanced Non-LOCA Analysis Methodology for Licensing

    International Nuclear Information System (INIS)

    Jang, Chansu; Um, Kilsup; Choi, Jaedon

    2008-01-01

    KNF is developing a new design methodology on the Non-LOCA analysis for the licensing purpose. The code chosen is the best-estimate transient analysis code RETRAN and the OPR1000 is aimed as a target plant. For this purpose, KNF prepared a simple nodal scheme appropriate to the licensing analyses and developed the designer-friendly analysis tool ASSIST (Automatic Steady-State Initialization and Safety analysis Tool). To check the validity of the newly developed methodology, the single CEA withdrawal and the locked rotor accidents are analyzed by using a new methodology and are compared with current design results. Comparison results show a good agreement and it is concluded that the new design methodology can be applied to the licensing calculations for OPR1000 Non-LOCA

  1. MARSSIM guidelines for non-impacted area identification in support of partial site release prior to license termination

    International Nuclear Information System (INIS)

    Parish, D.

    1999-01-01

    Regulations are in place which allow plants undergoing decommissioning to remove obsolete requirements from their licenses. Large buffer areas to the site boundary, needed for emergency planning purposes during power operation, are not required for permanently defueled facilities. It is important that non-impacted areas be removed from license restrictions as soon as possible post shutdown to allow rapid asset recovery and return the large environmental resources these areas represent to beneficial use. License termination surveys are not required for non-impacted areas in accordance with the guidance of US Nuclear Regulatory Commission (NRC) NUREG-1575 (MARSSIM), and NRC Draft Regulatory Guide DG-4006. Thus, such areas do not fall under the license termination requirements of 10CFR50.82 (US Code of Federal Regulations). This report describes methods of classifying areas as non-impacted in accordance with MARRSIM and other NRC guidance, and the licensing options for release of non-impacted areas prior to license termination. The status of Big Rock Point's efforts toward early release of non-impacted areas also is provided. (author)

  2. Dry spent fuel storage licensing

    International Nuclear Information System (INIS)

    Sturz, F.C.

    1995-01-01

    In the US, at-reactor-site dry spent fuel storage in independent spent fuel storage installations (ISFSI) has become the principal option for utilities needing storage capacity outside of the reactor spent fuel pools. Delays in the geologic repository operational date at or beyond 2010, and the increasing uncertainty of the US Department of Energy's (DOE) being able to site and license a Monitored Retrievable Storage (MRS) facility by 1998 make at-reactor-site dry storage of spent nuclear fuel increasingly desirable to utilities and DOE to meet the need for additional spent fuel storage capacity until disposal, in a repository, is available. The past year has been another busy year for dry spent fuel storage licensing. The licensing staff has been reviewing 7 applications and 12 amendment requests, as well as participating in inspection-related activities. The authors have licensed, on a site-specific basis, a variety of dry technologies (cask, module, and vault). By using certified designs, site-specific licensing is no longer required. Another new cask has been certified. They have received one new application for cask certification and two amendments to a certified cask design. As they stand on the brink of receiving multiple applications from DOE for the MPC, they are preparing to meet the needs of this national program. With the range of technical and licensing options available to utilities, the authors believe that utilities can meet their need for additional spent fuel storage capacity for essentially all reactor sites through the next decade

  3. Development of radioactive waste management licensing review assistant

    International Nuclear Information System (INIS)

    Wei-Whua Loa; Suan Chen; Wei-Chu Yu

    1992-01-01

    Regulations on radioactive waste disposal are now in urgent need due to our increasing consumption of electric power from nuclear origin. It is set forth that actually applying the regulations to evaluate the license application of new repositories for interim storage and final disposal of High-Level Waste and Low-Level Waste before the year of 2000. In the mean time, it is expected to establish the basis for the decision on issuing the license. The license review procedure can be very complicated, because too many factors must be taken into consideration. For the time being, licensing review is as much an art as it is a science. The authority usually faces three major problems; (1) the availability of domain expert, (2) maintaining of high quality and consistent reviews, and (3) the documentation of the review process. However, to maintain a more efficient, accurate, and systematic review procedure, and at the same time to reduce costs, the Artificial Intelligence (AI) techniques may be used. An expert system is designed as a radioactive waste management licensing review aid for the staff those are in charge of the license application. Tasks such as completeness checking, functional areas of review distribution, participation confirmation, knowledge acquisition, review comment collection, weighting calculation, and degree of satisfaction are considered. In this paper we will discuss the development of the radioactive waste management licensing review assistant

  4. Licensing process in Finland

    International Nuclear Information System (INIS)

    Tiippana, Petteri

    2011-01-01

    In accordance with the Nuclear Energy Act, the use of nuclear energy constitutes operations subject to license. The licensing process and conditions for granting a license is defined in the legislation. The licenses are applied from and granted by the Government. This paper discusses briefly the licensing process in Finland and also the roles and responsibilities of main stakeholders in licensing. Licensing of a nuclear power plant in Finland has three steps. The first step is the Decision in Principle (DiP). Goal of DiP is to decide whether using nuclear power is for the overall good for the Finnish society. The second step is Construction License (CL) and the goal of CL phase is to determine whether the design of the proposed plant is safe and that the participating organisations are capable of constructing the plant to meet safety goals. The third step is the Operating License (OL) and the goal of the OL phase is to determine whether the plant operates safely and licensee is capable to operate the plant safely. Main stakeholders in the licensing process in Finland are the utility (licensee) interested in using nuclear power in Finland, Ministry of Employment and the Economy (MEE), Government, Parliament, STUK, the municipality siting the plant and the general public. Government grants all licenses, and Parliament has to ratify Government's Decision in Principle. STUK has to assess the safety of the license applications in each step and give statement to the Ministry. Municipality has to agree to site the plant. Both STUK and the municipality have a veto right in the licensing process

  5. Strategic Basis for License Application Planning for a Potential Yucca Mountain Repository

    International Nuclear Information System (INIS)

    Newberry, C. M.; Brocoum, S. J.; Gamble, R. P.; Murray, R. C.; Cline, M.

    2002-01-01

    If Yucca Mountain, Nevada is designated as the site for development of a geologic repository for disposal of spent nuclear fuel and high-level radioactive waste, the Department of Energy (DOE) must obtain Nuclear Regulatory Commission (NRC) approval first for repository construction, then for an operating license, and, eventually, for repository closure and decommissioning. The licensing criteria defined in Code of Federal Regulations, Title 10, Part 63 (10 CFR Part 63) establish the basis for these NRC decisions. Submittal of a license application (LA) to the NRC for authorization to construct a repository at the Yucca Mountain site is, at this point, only a potential future action by the DOE. The policy process defined in the Nuclear Waste Policy Act (NWPA), as amended, for recommendation and designation of Yucca Mountain as a repository site makes it difficult to predict whether or when the site might be designated. The DOE may only submit a LA to the NRC if the site designation takes effect. In spite of this uncertainty, the DOE must take prudent and appropriate action now, and over the next several years, to prepare for development and timely submittal of a LA. This is particularly true given the need for the DOE to develop, load, and certify the operation of its electronic information system to provide access to its relevant records as part of the licensing support network (LSN) in compliance with NRC requirements six months prior to LA submittal. The DOE must also develop a LA, which is a substantially different document from those developed to support a Site Recommendation (SR) decision. The LA must satisfy NRC licensing criteria and content requirements, and address the acceptance criteria defined by the NRC in its forthcoming Yucca Mountain Review Plan (YMRP). The content of the LA must be adequate to facilitate NRC acceptance and docketing for review, and the LA and its supporting documents must provide the documented basis for the NR C findings required

  6. Pharmaceutical new product development: the increasing role of in-licensing.

    Science.gov (United States)

    Edwards, Nancy V

    2008-12-01

    Many pharmaceutical companies are facing a pipeline gap because of the increasing economic burden and uncertainty associated with internal research and development programs designed to develop new pharmaceutical products. To fill this pipeline gap, pharmaceutical companies are increasingly relying on in-licensing opportunities. New business development identifies new pharmaceuticals that satisfy unmet needs and are a good strategic fit for the company, completes valuation models and forecasts, evaluates the ability of the company to develop and launch products, and pursues in-licensing agreements for pharmaceuticals that cannot be developed internally on a timely basis. These agreements involve the transfer of access rights for patents, trademarks, or similar intellectual property from an outside company in exchange for payments. Despite the risks, in-licensing is increasingly becoming the preferred method for pharmaceutical companies with pipeline gaps to bring new pharmaceuticals to the clinician.

  7. Evaluation of the impact of a committed site on fusion reactor development

    International Nuclear Information System (INIS)

    Reid, R.L.; Nagy, A.

    1979-01-01

    The technical and economic merits of a committed fusion site for development of tokamak, mirror, and EBT reactor from ignition through demo phases were evaluated. Schedule compression resulting from evolving several reactor concepts and/or phases on a committed site as opposed to sequential use of independent sites was estimated. Land, water, and electrical power requirements for a committed fusion site were determined. A conceptual plot plan for siting three fusion reactors on a committed site was configured. Reactor support equipment common to the various concepts was identified as candidates for sharing. Licensing issues for fusion plants were briefly addressed

  8. Environmental licensing issues for cogeneration plants

    International Nuclear Information System (INIS)

    Lipka, G.S.; Bibbo, R.V.

    1990-01-01

    The siting and licensing of cogeneration and independent power production (IPP) facilities is a complex process involving a number of interrelated engineering, economic, and environmental impact considerations. Important considerations for the siting and licensing of such facilities include air quality control and air quality impacts, water supply and wastewater disposal, and applicable noise criteria and noise impact considerations. Air quality control and air quality impact considerations for power generation facilities are commonly reviewed in the public forum, and most project developers are generally aware of the key air quality licensing issues. These issues include Best Available Control Technology (BACT) demonstration requirements, and air quality modeling requirements. BACT is a case-by-case determination, which causes uncertainty, in that developers have difficulty in projecting the cost of required control systems. Continuing developments in control technology may cause this problem to continue in the 1990's. Air quality modeling can be a problem in hilly terrain or within or near an urban environment, which could delay or preclude permitting of a new cogeneration or IPP facility in such locations. This paper discusses several environmental issues which are less frequently addressed than air quality issues, namely water/wastewater and noise. The design features of typical cogeneration and IPP facilities that affect water supply requirements, wastewater volumes, and noise emissions are discussed. Then, the site selection and impact review process are examined to identify typical constraints and trade-offs that can develop relative to water, wastewater, and noise issues. Trends in permit review requirements for water, wastewater, and noise are examined. Finally, innovative approaches that can be used to resolve potential development constraints for water, wastewater, and noise issues are discussed

  9. Department of Energy licensing strategy

    International Nuclear Information System (INIS)

    Frei, M.W.

    1984-01-01

    The Department of Energy (DOE) is authorized by the Nuclear Waste Policy Act of 1982 (Act) to site, design, construct, and operate mined geologic repositories for high-level radioactive wastes and is required to obtain licenses from the Nuclear Regulatory Commission (NRC) to achieve that mandate. To this end the DOE has developed a licensing approach which defines program strategies and which will facilitate and ease the licensing process. This paper will discuss the regulatory framework within which the repository program is conducted, the DOE licensing strategy, and the interactions between DOE and NRC in implementing the strategy. A licensing strategy is made necessary by the unique technical nature of the repository. Such a facility has never before been licensed; furthermore, the duration of isolation of waste demanded by the proposed EPA standard will require a degree of reliance on probabilistic performance assessment as proof of compliance that is a first of a kind for any industry. The licensing strategy is also made necessary by the complex interrelationships among the many involved governmental agencies and even within DOE itself, and because these relationships will change with time. Program activities which recognize these relationships are essential for implementing the Act. The guiding principle in this strategy is an overriding commitment to safeguarding public health and safety and to protecting the environment

  10. A comparison of licensed and un-licensed artisanal and small-scale gold miners (ASGM) in terms of socio-demographics, work profiles, and injury rates.

    Science.gov (United States)

    Calys-Tagoe, Benedict N L; Clarke, Edith; Robins, Thomas; Basu, Niladri

    2017-11-06

    Artisanal and small-scale gold mining (ASGM) represents one of the most hazardous work environments. While formalization of this sector has been suggested (e.g., Minamata Convention) as a means to improve working conditions, we are unaware of empirical evidence that supports this notion. This study aimed to compare sociodemographic profiles, work profiles, and injury rates among miners working in licensed versus un-licensed ASGM sites. In the Tarkwa mining region of Ghana, 404 small-scale miners were recruited in 2014 and interviewed regarding their occupational injury experiences over the preceding 10 years. Workers were drawn from 9 mining sites, of which 5 were licensed and 4 were not licensed. Sociodemographic characteristics of miners from the two groups were relatively similar. Those currently working in an un-licensed mine have spent more time in the ASGM sector than those currently working in a licensed mine (94 vs. 70 months). Miners working in an un-licensed site tended to experience more injury episodes (e.g., 26% vs. 8% had 3 or more injury events) and not use personal protective equipment during the time of an injury (92% indicated to not using vs. 73%) when compared to miners working in a licensed site. A total of 121 injury episodes were recorded for 2245 person years of ASGM work. The injury rate for those working in un-licensed mines was 5.9 per 100 person years (59 injuries in 995 person years) versus 5.0 (62 injuries in 1250 person-years) in the licensed mines. When focusing on the male miners, there was a significant difference in injury rates between those working in a licensed mine (4.2 per 100 person years) versus an un-licensed mine (6.1 per 100 person years). These findings advance our understanding of injuries amongst ASGM workers, and help identify important differences in socio-demographics, work profiles, and injury rates between miners working in a licensed versus and un-licensed site. The findings suggest that certain working

  11. Inventory of sites used to develop residual radioactivity criteria

    International Nuclear Information System (INIS)

    Ronca-Battista, M.; Hardeman, J.C. Jr.

    1986-01-01

    The US Environmental Protection Agency (EPA), in conjunction with the National Conference of Radiation Control Program Directors (CRCPD), has compiled an inventory of never licensed or otherwise poorly documented sites that may be contaminated with radioactive materials. This effort is in support of the EPA's development of radiation protection criteria for residual radioactivity at decommissioned sites. The inventory will help to establish the range of circumstances for which criteria are needed, as well as the suitability of candidate criteria for actual situations. The information will also be used to develop model sites and facilities for analyzing technical and economic feasibility of residual radioactivity criteria and to assess costs and benefits of alternate criteria. Relevant information about each site, such as radionuclides, waste forms, and quantities present will be included in the inventory when such information is available. The CRCPD has requested that each State radiation control agency furnish the information for the inventory. The inventory supplements the relatively extensive documentation of sites regulated by Federal or State agencies with information on old or unlicensed sites, such as old waste storage sites or radium ore processing facilities

  12. Technology neutral licensing requirements: have we been successful?

    International Nuclear Information System (INIS)

    Jamieson, T.

    2009-01-01

    The Canadian Nuclear Safety Commission (CNSC) is Canada's nuclear regulator. In preparation for the licensing of the next generation of nuclear reactors in Canada, the CNSC has made major changes in its processes and procedures associated with all aspects of the licensing life cycle. These include: development of key regulatory documents outlining the CNSC expectations for the design and siting of new reactors; creation of applicant guidelines for completing licensing applications; creation of a comprehensive set of review guides, specifying how topics in applications are to be reviewed; performing pre-project design reviews for proposed new reactor technologies; and streamlining processes wherever possible, such as performing the environmental assessment and license to prepare site activities in parallel. The predicted workload associated with the nuclear renaissance in Canada is real. The CNSC is currently performing: 4 pre-project design reviews (for AECL's ACR-1000 and EC-6, Areva's EPR and Westinghouse's AP-1000), has received applications for 4 new builds (at Darlington, Bruce, Nanticoke and in Alberta) and is in the midst of performing the combined environmental assessment and license to prepare site phases for these sites. This is in addition to the work associated with: the licensing of new uranium mines; oversight of the existing reactor fleet; refurbishments at Bruce/Gentilly/Point Lepreau; license renewal for the NRU reactor; and oversight of our general client base of over 5000 licensees. In this presentation, experience to date with these new processes and procedures will be discussed, including: status of the current new build projects; anticipated new activities; lessons learned, especially the technology neutral approach; application to our other licensed activities, including non-power reactors; and work underway to further develop CNSC methods. Qualifications Needed to Design, Construct and Manufacture Nuclear Systems and Equipment, C. Voutsinos

  13. A comparison of licensed and un-licensed artisanal and small-scale gold miners (ASGM in terms of socio-demographics, work profiles, and injury rates

    Directory of Open Access Journals (Sweden)

    Benedict N. L. Calys-Tagoe

    2017-11-01

    Full Text Available Abstract Background Artisanal and small-scale gold mining (ASGM represents one of the most hazardous work environments. While formalization of this sector has been suggested (e.g., Minamata Convention as a means to improve working conditions, we are unaware of empirical evidence that supports this notion. This study aimed to compare sociodemographic profiles, work profiles, and injury rates among miners working in licensed versus un-licensed ASGM sites. Methods In the Tarkwa mining region of Ghana, 404 small-scale miners were recruited in 2014 and interviewed regarding their occupational injury experiences over the preceding 10 years. Workers were drawn from 9 mining sites, of which 5 were licensed and 4 were not licensed. Results Sociodemographic characteristics of miners from the two groups were relatively similar. Those currently working in an un-licensed mine have spent more time in the ASGM sector than those currently working in a licensed mine (94 vs. 70 months. Miners working in an un-licensed site tended to experience more injury episodes (e.g., 26% vs. 8% had 3 or more injury events and not use personal protective equipment during the time of an injury (92% indicated to not using vs. 73% when compared to miners working in a licensed site. A total of 121 injury episodes were recorded for 2245 person years of ASGM work. The injury rate for those working in un-licensed mines was 5.9 per 100 person years (59 injuries in 995 person years versus 5.0 (62 injuries in 1250 person-years in the licensed mines. When focusing on the male miners, there was a significant difference in injury rates between those working in a licensed mine (4.2 per 100 person years versus an un-licensed mine (6.1 per 100 person years. Conclusions These findings advance our understanding of injuries amongst ASGM workers, and help identify important differences in socio-demographics, work profiles, and injury rates between miners working in a licensed versus and un-licensed

  14. Problems of developing remedial strategy for the uranium ore processing legacy site Pridneprovsky Chemical Plant site (Dneprodzerginsk, Ukraine)

    International Nuclear Information System (INIS)

    Riazantsev, V.; Bugai, D.; Skalskyy, A.; Tkachenko, E.

    2014-01-01

    In this paper we present results of works and studies carried out in the frame of ongoing national and international projects aimed at developing the remedial strategy for the Soviet era legacy uranium production site Pridneprovsky Chemical Plant, Dneprodzerginsk, Ukraine. The site includes several uranium mill tailings, contaminated buildings, ore storage grounds and other contaminated facilities. Taking into account the necessity to implement provisions of the new IAEA standards (Radiation Protection and Safety of Radiation Sources: International Basic Safety Standards, No. GSR Part 3 (Interim) and others) as well as the provisions of the ICRP 103 publication, the State Nuclear Regulatory Inspectorate Ukraine developed the draft of the new licensing requirements for activities of uranium ores processing.

  15. Recommendations for the hydrogeologic review and assessment of sites for nuclear power installations within the framework of the radiation protection licensing procedure

    International Nuclear Information System (INIS)

    Adam, C.; Petschel, M.; Koerner, W.

    1985-01-01

    Article 4 of the Nuclear Facility Licensing Ordinance requires the information to be submitted in support of licensing applications for nuclear power installations to include an expertise on the hydrogeologic characteristics of the site environment with main emphasis on the movement of radionuclides through groundwater in the event of accident conditions, and on measures to protect ground and surface waters. Recommendations are given for the conduct of a hydrogeologic review and assessment process and its timing relative to the individual stages in the licensing procedure. (author)

  16. Licensing arrangements and the development of the solar energy industry

    Energy Technology Data Exchange (ETDEWEB)

    Green, M.

    1979-06-01

    The process by which technology and information related to technology are transferred within industry is explored. Property rights in technology are part of the broader field of intellectual property. The general contours of legal protection for knowledge are explored. The four basic forms of intellectual property - patents, trade secrets (or know-how), trademarks, and copyrights - are covered in varying degrees of depth, depending on their relative applicability to the development of the solar industry. Once this background has been established, the legal aspects of licensing are examined. A license is a legal arrangement whereby a party (licensor) who controls the right to use an idea, invention, etc. shares the right to use the particular intellectual property with someone else (licensee). The advantages and disadvantages of licensing are described from the point of view of potential licensees and licensors. Barriers to licensing are discussed.

  17. Licensing procedures and siting problems of nuclear power stations in Japan

    International Nuclear Information System (INIS)

    Saito, Osamu.

    1981-10-01

    This paper describes the legislative and regulatory framework for nuclear power plant licensing in Japan and the different stages in the licensing procedure. The role and responsibilities of the authorities competent for the different types of nuclear facilities (power generation, ship propulsion and research) are also reviewed. The Annexes to the paper contain charts of the administrative structure for nuclear activities, the licensing procedure and nuclear facilities. (NEA) [fr

  18. Improving regulatory effectiveness in Federal/State siting actions: Federal/State regulatory permitting actions in selected nuclear power station licensing cases

    International Nuclear Information System (INIS)

    Baroff, J.

    1977-06-01

    The Federal/State regulatory permitting actions in 12 case histories of nuclear power station licensing in nine different states are documented. General observations regarding Federal/State siting roles in the siting process are included. Eleven of the case histories are illustrated with a logic network that gives the actions of the utilities in addition to the Federal/State permits

  19. Use of modeling in repository licensing

    International Nuclear Information System (INIS)

    McGarry, J.M. III; Echols, F.S.

    1995-01-01

    A review of the regulatory history of the Nuclear Regulatory Commission (NRC) regulations applicable to the licensing of a geologic repository, as well as a review of NRC administrative (licensing) decisions and federal case law, support the NRC's use of simplified models, in appropriate circumstances, which provide well-documented and reasonably conservative bounding assumptions, together with the use of expert judgement, natural analogues, and other aids to supplement available information, in reaching its reasonable assurance determination whether the public health and safety will be adequately protected if the Yucca Mountain, Nevada site should be licensed for development as a geologic repository. Specific examples are provided to assist the reader to better understand how such qualitative concepts as open-quote reasonable assurance close-quote, open-quote reasonably conservative close-quote, and open-quote adequate close-quote protection are used in an administrative context to resolve technical issues

  20. Two Approaches to Reactor Decommissioning: 10 CFR Part 50 License Termination and License Amendment, Lessons Learned from the Regulatory Perspective

    International Nuclear Information System (INIS)

    Watson, B.A.; Buckley, J.T.; Craig, C.M.

    2006-01-01

    Trojan Nuclear Plant (Trojan) and Maine Yankee Nuclear Plant (Maine Yankee) were the first two power reactors to complete decommissioning under the U. S. Nuclear Regulatory Commission's (NRC's) License Termination Rule (LTR), 10 CFR Part 20, Subpart E. The respective owners' decisions to decommission the sites resulted in different approaches to both the physical aspects of the decommissioning, and the approach for obtaining approval for completing the decommissioning in accordance with regulations. Being in different States, the two single-unit pressurized water reactor sites had different State requirements and levels of public interest that impacted the decommissioning approaches. This resulted in significant differences in decommissioning planning, conduct of decommissioning operations, volumes of low- level radioactive waste disposed, and the final status survey (FSS) program. While both licensees have Independent Spent Fuel Storage Installations (ISFSIs), Trojan obtained a separate license for the ISFSI in accordance with the requirements of 10 CFR Part 72 and terminated their 10 CFR Part 50 license. Maine Yankee elected to obtain a general license under 10 CFR Part 50 for the ISFSI and reduce the physical site footprint to the ISFSI through a series of license amendments. While the NRC regulations are flexible and allow different approaches to ISFSI licensing there are separate licensing requirements that must be addressed. In 10 CFR 50.82, the NRC mandates public participation in the decommissioning process. For Maine Yankee, public input resulted in the licensee entering into an agreement with a concerned citizen group and resulted in State legislation that significantly lowered the dose limit below the NRC radiological criteria of 25 mrem (0.25 mSv) per year (yr) in 10 CFR 20.1402 for unrestricted use. The lowering of the radiological criteria resulted in a significant dose modeling effort using site-specific Derived Concentrations Guideline Levels (DCGLs

  1. NUPLEX Licensing Subcommittee

    International Nuclear Information System (INIS)

    Edwards, D.W.; Allen, S.R.

    1988-01-01

    The NUPLEX Licensing Subcommittee was organized to seek a formal license renewal mechanism that institutionalizes the current licensing basis and consequent level of safety of a plant as the legitimate standard for acceptance and approval of an application for extended operation. Along with defining the most workable approach to and scope of review for license renewal, this paper explains the reasons why a regulatory framework is needed by the early 1990s. The initial results of development work on two key issues, licensing criteria and hearing process, are also presented. at this point six potential license renewal criteria have emerged: evaluation of existing monitoring/maintenance programs, revalidation of current licensing basis, conformance to special regulations, evaluation to a safety goal, plant performance history, and environmental assessment. The work on a hearing process has led to the development of two models for future consideration: hybrid legislative and hybrid adjudicatory

  2. Safety and licensing requirements in the Republic of South Africa

    International Nuclear Information System (INIS)

    Simpson, D.M.; Langford, E.L.

    1986-01-01

    The principles for licensing of nuclear installations in South Africa are based on the control of mortality risk to the operators of an installation and the population resident in the vicinity of the site. This paper describes the development of this safety philosophy, and the nuclear licensing process used in this country. The structure of the nuclear regulatory function is briefly described, including the respective roles of the Atomic Energy Corporation, Licencing Branch and the Council for Nuclear Safety. The development of risk criteria and quantitative release magnitude-probability criteria for radioactive material is outlined. Tasks that have to be undertaken by a potential waste disposal site licensee before a site licence is issued are described. Once the facility is commissioned periodic monitoring procedures will have to be adopted throughout the lifetime of the facility. The scope of typical monitoring activities is outlined and the ongoing analyses to be performed and the records to be kept are discussed

  3. Effects of Californian PRC 25500 on nuclear power plant licensing

    International Nuclear Information System (INIS)

    Hahn, F.J.

    1976-01-01

    The California Public Resources Code 25500 established the Energy Resources Conservation and Development Commission on January 7, 1976. This Act mandated that the Commission process applications for new power plants within very specific timeframes. The paper presents the intent and timing of the two-phase licensing procedure and illustrates the effect of this procedure on power plants already into the NRC licensing process and on power plants which are in the beginning of the site selection process

  4. 78 FR 37234 - Prospective Grant of Exclusive License: Start-Up Commercial License for the Development of...

    Science.gov (United States)

    2013-06-20

    ... the Treatment of Brain, Liver, and Pancreatic Cancers and Congestive Heart Failure AGENCY: National..., development, manufacture, distribution, sale, and use in humans for the treatment of brain cancer, liver...: Patrick McCue, Ph.D., Licensing and Patenting Manager, Office of Technology Transfer, National Institutes...

  5. Development of a low level radioactive waste disposal site in Texas - 1994 status

    International Nuclear Information System (INIS)

    Jacobi, L.R. Jr.

    1995-01-01

    The Texas Low Level Radioactive Waste Disposal Authority, an agency of the State of Texas, has been trying to develop a site for the disposal of low level radioactive waste in Texas for over ten years. Since 1991, the agency has been evaluating a site near Sierra Blanca, in far west Texas. Site characterization has been completed and a license application has been filed with the Texas Natural Resource Conservation Commission. Construction plans were completed in 1993, and the agency is prepared to begin construction and operations as soon as a license can be issued. Development costs for the site are borne by the utility companies and other major generators in Texas through the assessment of a planning and implementation fee. Total costs to date are approximately $26 million. As the project moves toward completion, state and national anti-nuclear activist groups have become more involved in attempts to thwart the Texas government's effort to solve the radioactive waste problem. To counter this increased opposition, the Texas utility companies and medical radioactive waste generators have also become more active in responding to these groups. This has been very helpful and is in keeping with the elements of building block 12 of the Nuclear Power Oversight Committee's Strategic Plan for Building New Nuclear Power Plants. This paper and poster session look at the schedule, design, and long term prospects for ultimate success of the project

  6. License renewal demonstration program: NRC observations and lessons learned

    International Nuclear Information System (INIS)

    Prato, R.J.; Kuo, P.T.; Newberry, S.F.

    1996-12-01

    This report summarizes the Nuclear Regulatory Commission staff's observations and lessons learned from the five License Renewal Demonstration Program (LRDP) site visits performed by the staff from March 25, 1996, through August 16, 1996. The LRDP was a Nuclear Energy Institute (NEI) program intended to assess the effectiveness of the guidance provided by NEI 95-10, Revision 0, open-quotes Industry Guideline for Implementing the Requirements of 10 CFR Part 54 - The License Renewal Rule,close quotes to implement the requirements of Title 10 of the Code of Federal Regulations, Part 54 (10 CFR Part 54), open-quotes Requirements for Renewal of Operating Licenses for Nuclear Power Plants.close quotes In general, NEI 95-10 appeared to contain the basic guidance needed for scoping, screening, identifying aging effects, developing aging management programs, and performing time-limited aging analyses. However, inconsistent implementation of this guidance in some areas was an indication that clarification of existing guidance and/or the inclusion-of some new guidance may be needed for applicants to develop a license renewal program that is consistent with the intent of the rule

  7. The need for legislative framework (licensing)

    International Nuclear Information System (INIS)

    Krech, H.

    1977-01-01

    For reasons of public acceptance the basis of a licensing system should be laid down in a law, details can be fixed in regulations below the law-level. The competence for licensing nuclear installations should be attributed to one body, which is not a the same time charged with the promotion of nuclear energy. The licensing authority has to be provided with sufficient technical advice, given by experts organized in advisory bodies. Normally a licensing procedure is split into several steps (site approval, construction permit, operation licence), each step can be subdivided. Some general aspects of licensing conditions (personal, technical and financial) as well as of the licensing procedure are outlined. The participation of the public is of particular importance but also involves most intricate problems. The paper concludes with some critical remarks on the role of administrative courts with respect to the licensing of nuclear power plants. (orig.) [de

  8. Recycling and disposal of FUSRAP materials from the Ashland 2 site at a licensed uranium mill

    International Nuclear Information System (INIS)

    Howard, B.; Conboy, D.; Rehmann, M.; Roberts, H.

    1999-01-01

    During World War II the Manhattan Engineering District (MED) used facilities near Buffalo, N.Y. to extract natural uranium from ores. Some of the byproduct material left from the ores (MED byproduct), containing low levels of uranium, thorium, and radium, was deposited on a disposal site known as Ashland 2, located in Tonawanda, NY. On behalf of the United States Army Corps of Engineers (USACE, or the Corps), ICF Kaiser Engineers (ICFKE) was tasked to provide the best value clean-up results that meet all of the criteria established in the Record of Decision for the site. International Uranium (USA) Corporation (IUC), the operator of the White Mesa Uranium Mill, a Nuclear Regulatory Commission (NRC)-licensed mill near Blanding, Utah, was selected to perform uranium extraction on the excavated materials, therefore giving the best value as it provided beneficial use of the material consistent with the Resource Conservation and Recovery Act (RCRA) intent to encourage recycling and recovery, while also providing the most cost-effective means of disposal. Challenges overcome to complete this project included (1) identifying the best-value location to accept the material; (2) meeting regulatory requirements with IUC obtaining an NRC license amendment to accept and process the material as an alternate feed; (3) excavating and preparing the material for shipment, then shipping the material to the Mill for uranium recovery; and (4) processing the material, followed by disposal of tailings from the process in the Mill's licensed uranium tailings facility. Excavation from Ashland 2 and processing of the Ashland 2 material at the White Mesa Mill resulted in a cleaner environment at Tonawanda, a cost avoidance of up to $16 million, beneficial recovery of source material, and environmentally protective disposal of byproduct material. (author)

  9. Long-term surveillance plan for the Gunnison, Colorado, disposal site

    International Nuclear Information System (INIS)

    1996-05-01

    This long-term surveillance plan (LTSP) describes the US Department of Energy's (DOE) long-term care program for the Uranium Mill Tailings Remedial Action (UMTRA) Project Gunnison disposal site in Gunnison County, Colorado. The US Nuclear Regulatory Commission (NRC) has developed regulations for the issuance of a general license for the custody and long-term care of UMTRA Project disposal sites in 10 CFR Part 40. The purpose of this general license is to ensure that the UMTRA Project disposal sites will be cared for in a manner that protects the public health and safety and the environment.For each disposal site to be licensed, the NRC requires the DOE to submit a site-specific LTSP. The DOE prepared this LTSP to meet this requirement for the Gunnison disposal site. The general license becomes effective when the NRC concurs with the DOE's determination of completion of remedial action for the Gunnison site and the NRC formally accepts this LTSP

  10. Assessment of the licensing aspects of HTGR in Yugoslavia

    International Nuclear Information System (INIS)

    Varazdinec, Z.

    1990-01-01

    This paper deals not only with the licensing procedure in Yugoslavia, but also reflects the Utility/Owner approach to the assessment of the licensability of the HTGR during the site selection process and especially during bid evaluation process. Besides the description of the existing procedure which was implemented on licensing of LWR program, the assessment of some licensing aspects of HTGR has been presented to describe possible implementation on licensing procedure. (author)

  11. Assessment of the licensing aspects of HTGR in Yugoslavia

    Energy Technology Data Exchange (ETDEWEB)

    Varazdinec, Z [Institut za Elektroprivredu-Zagreb, Zagreb (Yugoslavia)

    1990-07-01

    This paper deals not only with the licensing procedure in Yugoslavia, but also reflects the Utility/Owner approach to the assessment of the licensability of the HTGR during the site selection process and especially during bid evaluation process. Besides the description of the existing procedure which was implemented on licensing of LWR program, the assessment of some licensing aspects of HTGR has been presented to describe possible implementation on licensing procedure. (author)

  12. License renewal

    International Nuclear Information System (INIS)

    Newberry, S.

    1993-01-01

    This article gives an overview of the process of license renewal for nuclear power plants. It explains what is meant by license renewal, the significance of license renewal, and goes over key elements involved in the process of license renewal. Those key elements are NRC requirements embodied in 10 CFR Part 54 (Reactor Safety) and 10 CFR Part 51 (Environmental Issues). In addition Industry Reports must be developed and reviewed. License renewal is essentially the process of applying for a 20 year extension to the original 40 year operating license granted for the plant. This is a very long term process, which involves a lot of preparation, and compliance with regulatory rules and guidelines. In general it is a process which is expected to begin when plants reach an operating lifetime of 20 years. It has provisions for allowing the public to become involved in the review process

  13. 76 FR 79228 - Combined Licenses at William States Lee III Nuclear Station Site, Units 1 and 2; Duke Energy...

    Science.gov (United States)

    2011-12-21

    ... NUCLEAR REGULATORY COMMISSION [Docket Nos. 52-018 and 52-019; NRC-2008-0170] Combined Licenses at William States Lee III Nuclear Station Site, Units 1 and 2; Duke Energy Carolinas, LLC AGENCY: Nuclear.... SUMMARY: Notice is hereby given that the U.S. Nuclear Regulatory Commission (NRC) and the U.S. Army Corps...

  14. Recent developments in Canadian nuclear power plant licensing practices

    International Nuclear Information System (INIS)

    Marchildon, P.

    1985-06-01

    This paper examines the dominant factors which have influenced the safety evaluation and licensing process of current 600 MW reactors. It describes possible modifications to the process which are being considered for the licensing of a second 600 MW reactor at Point Lepreau. The key element is a firm licensing agreement covering the entire licensing cycle, to be established between the proponent and the AECB before a construction licence is issued. Progress accomplished to date in reaching such an agreement is described

  15. License - PSCDB | LSDB Archive [Life Science Database Archive metadata

    Lifescience Database Archive (English)

    Full Text Available switchLanguage; BLAST Search Image Search Home About Archive Update History Data ...wnload License Update History of This Database Site Policy | Contact Us License - PSCDB | LSDB Archive ...

  16. License - DMPD | LSDB Archive [Life Science Database Archive metadata

    Lifescience Database Archive (English)

    Full Text Available switchLanguage; BLAST Search Image Search Home About Archive Update History Data ...ownload License Update History of This Database Site Policy | Contact Us License - DMPD | LSDB Archive ...

  17. On the reform of nuclear licensing procedures for plants and operation

    International Nuclear Information System (INIS)

    Lecheler, H.

    1977-01-01

    The nuclear licensing procedures require basic reforming. In doing so, there must be a differentiation between (concrete) licensing of plants and (abstract) decisions on site provision. The provision of sites is exercised directly by the diets of the Laender. For this purpose they enact planning laws on sites for nuclear power plants of different sizes. As far as the Federal law is touched upon (especially the Federal act on construction), the Federal legislator has to concede competences to the Laender. No. 6 of section 7 II of the Atomic Energy Act would have to be deleted. The plant licensing procedure is to be limited to a mere safety check-up of a concrete plant. Licensing prerequisites of the Atomic Energy Act are to be made more precise by the Federal legislator, namely by deciding unequivocally the purpose of the law, whether priority is given to promotion or to protection, and by making the enacting of tangible regulations a duty. When these licensing prerequisites exist, the law has to concede the applicant a plain title to licensing. (orig.) [de

  18. NRC's license renewal regulations

    International Nuclear Information System (INIS)

    Akstulewicz, Francis

    1991-01-01

    In order to provide for the continuity of the current generation of nuclear power plant operating licenses and at the same time ensure the health and safety of the public, and the quality of the environment, the US Nuclear Regulatory Commission (NRC) established a goal of developing and issuing regulations and regulatory guidance for license renewal in the early 1990s. This paper will discuss some of those activities underway to achieve this goal. More specifically, this paper will discuss the Commission's regulatory philosophy for license renewal and the two major license renewal rule makings currently underway. The first is the development of a new Part 54 to address procedural and technical requirements for license renewal; the second is a revision to existing Part 51 to exclude environmental issues and impacts from consideration during the license renewal process. (author)

  19. Long-term surveillance plan for the Rifle, Colorado, Disposal site

    International Nuclear Information System (INIS)

    1996-09-01

    This long-term surveillance plan (LTSP) describes the U.S. Department of Energy's (DOE) long-term care program for the Uranium Mill Tailings Remedial Action (UMTRA) Project Estes Gulch disposal site in Garfield County, Colorado. The U.S. Environmental Protection Agency (EPA) has developed regulations for the issuance of a general license by the U.S. Nuclear Regulatory Commission (NRC) for the custody and long-term care of UMTRA Project disposal Sites in 10 CFR Part 40. The purpose of this general license is to ensure that the UMTRA Project disposal sites, will be cared for in a manner that protects the public health and safety and the environment. For each disposal site to be licensed, the NRC requires the DOE to submit a site-specific LTSP. The DOE prepared this LTSP to meet this requirement for the Estes Gulch disposal site. The general license becomes effective when the NRC concurs with the DOE's determination of completion of remedial action for the Estes Gulch site and the NRC formally accepts this LTSP

  20. IRIS project update: status of the design and licensing activities

    International Nuclear Information System (INIS)

    Petrovic, B.; Carelli, M.

    2004-01-01

    This paper presents an overview of the current status of the IRIS (International Reactor Innovative and Secure) project, focusing on the design and licensing activities. An update relative to the previous presentation at the 4th HND Conference is provided, highlighting some of the main accomplishments over the past two years. After successfully completing the conceptual design phase, IRIS is now finalizing the preliminary design as well. The pre-application licensing review with the U.S. NRC has been initiated in October of 2002. The safety-by-design approach and PRA-guided design open the possibility to aim for licensing not requiring off-site emergency response planning. Multiple single-unit and twin-unit site layouts have been developed within the ESP (Early Site Permit) program currently pursued by three U.S. power utilities. Desalination and district heating options have recently been added to the base design. Staggered construction schedules of multiple units may be applied to optimize cash-flow and minimize the required investment, making IRIS a financially attractive option, even for economies with limited investment capabilities. Because of its modularity, compatibility with smaller/medium grids, and enabling gradual build of new generating capacity matching the needs, IRIS has a large potential in the worldwide market.(author)

  1. FOSS License Selection and Code Management

    OpenAIRE

    Vescuso, Peter

    2011-01-01

    With nearly 2,000 free and open source software (FLOSS) licenses, software license proliferation¿ can be a major headache for software development organizations trying to speed development through software component reuse, as well as companies redistributing software packages as components of their products. Scope is one problem: from the Free Beer license to the GPL family of licenses to platform-specific licenses such as Apache and Eclipse, the number and variety of licenses make it difficu...

  2. Licensing aspects regarding the RBMN project

    International Nuclear Information System (INIS)

    Cuccia, Valeria; Sacramento, Arivaldo M.; Aleixo, Bruna L.; Ferreira, Vinicius V.M.

    2013-01-01

    The licensing process of a waste disposal facility is a complex and demanding undertaking. It proceeds in phases, starting with the site selection and ending many decades later, when the radionuclides decayed and no longer offer possible hazard. That is one of the reasons why the licensing process for the Brazilian repository for low and intermediate level radioactive waste (RBMN Project) is a challenge for all the technicians involved. Besides that, the only national experience associated to this subject arose after a radiological accident in the State of Goias, in 1987. Two different institutions are involved in this licensing process: IBAMA, for environmental licensing, and CNEN, for nuclear licensing. Both of them will evaluate the possible impacts caused by the waste disposal, so it is essential to avoid conflicts and duplications of activities. The RBMN project has different teams for each main activity, and one of them is the Licensing group. This team has been planning the licensing activities for the repository, studying the legal framework and estimating costs and execution time for each step. This paper presents the status of the licensing activities regarding to the RBMN project done by the CNEN staff. (author)

  3. Development regulation regarding with licensing of nuclear installation

    International Nuclear Information System (INIS)

    Bambang Riyono; Yudi Pramono; Dahlia Cakrawati Sinaga

    2011-01-01

    Provisions of Article 17 paragraph (3) of Law Number 10 Year 1997 on Nuclear cleary mandates for the establishment of government regulations (GR) on Nuclear licensing containing the requirements and procedure, both from the standpoint of their utilization and installation. To use has been rising GR No.29 Year 2008 on the Use of Ionizing Radiation Sources and Nuclear Materials, while for the installation has been published PP No.43 Year 2006 on Nuclear Reactor Licensing, and BAPETEN Chairman Decree No.3 Year 2006 on Non-reactor Nuclear Installation Licensing. Based on the background of the preparation of both the aforementioned are just regulate the reactor and utilization, not yet fully meet the mandate of Article 17 paragraph (3) of Law No.10 of 1997 on Nuclear, including other nuclear installations. For these reasons, it initiated the need for a separate regulation containing provisions concerning licensing of non-reactor nuclear installations. On the other side from the understanding the legal aspects and interpretations of the Law No.10 of 2004 on the Establishment Regulation Legislation, should be in single mandate of Article 17 paragraph (3) of Law No.10 of 1997 on Nuclear would only produce one of the requirements and procedure for the use or installation, or a maximum of two (2) GR related licensing the use and installation. This is encourages conducted the assessing or studies related to how possible it is according to the legal aspect is justified to combine in one Nuclear licensing regulations regarding both the use and installation, by looking at the complexity of installation and wide scope of utilization of nuclear energy in Indonesia. The results of this paper is expected to provide input in the preparation of GR on licensing of nuclear installations. (author)

  4. License - GRIPDB | LSDB Archive [Life Science Database Archive metadata

    Lifescience Database Archive (English)

    Full Text Available switchLanguage; BLAST Search Image Search Home About Archive Update History Data ...e Database Description Download License Update History of This Database Site Policy | Contact Us License - GRIPDB | LSDB Archive ...

  5. License - GETDB | LSDB Archive [Life Science Database Archive metadata

    Lifescience Database Archive (English)

    Full Text Available switchLanguage; BLAST Search Image Search Home About Archive Update History Data ...se Database Description Download License Update History of This Database Site Policy | Contact Us License - GETDB | LSDB Archive ...

  6. Experience acquired by Furnas for licensing nuclear power plants

    International Nuclear Information System (INIS)

    Silva, A.J.C. da; Xavier, E.E.

    1986-01-01

    The system for licensing of Almirante Alvaro Alberto Nuclear Power Plant-Unit 1 is presented. The process phases for reactor construction and operation are described: preliminary site approval; bases for safety review; partial construction permits; final construction permits; emission of final report of safety analysis; initial operation license and permanent operation license. (M.C.K.) [pt

  7. License - JSNP | LSDB Archive [Life Science Database Archive metadata

    Lifescience Database Archive (English)

    Full Text Available switchLanguage; BLAST Search Image Search Home About Archive Update History Data ...This Database Database Description Download License Update History of This Database Site Policy | Contact Us License - JSNP | LSDB Archive ...

  8. Nuclear power plant attempts in Turkey and the first licensed site

    International Nuclear Information System (INIS)

    Bektur, Y.; Bezdegumeli, U.

    2004-01-01

    Turkey is currently in a rapid industrialization process with a young population of 71 million. Electricity is an inevitable need for Turkey as a fast developing country. Turkey's average annual growth rates of electricity consumption have been 8% in the last two decades. The installed electricity generating capacity of Turkey reached 36 GW; the annual gross power generation was 140 TWh (23% lignite and coal, 44% natural gas, 25% hydro and 8% others); and the annual gross per capita consumption of electricity was around 2.000 kWh as of end-2003. According to forecasts prepared by the Ministry of Energy and Natural Resources (MENR), Turkey will need about 60 GW of capacity by 2010, and about 100 GW by 2020. This implies power demand growth rates of at least 8% per annum for the coming decade and at least 6% per annum for the following decade. This means that there is a need for rapid build-up of 3 GW new capacities per year for at least several years. Turkey's experience with nuclear power dates back to the 1960s - a research reactor has been operating in Istanbul since 1962 - and successive governments have had plans to introduce commercial nuclear power to the country for three decades or more. Since 1965, four attempts were made for the construction of an NPP in Turkey, but all failed. Turkish Electricity Authority (TEK, reorganized as Electricity Generation Corporation in 2002) was granted a site license for the Akkuyu site in 1976. According to the current long-term energy planning studies made by MENR, nuclear power is an important option to enhance the national energy security and reliability. In the light of this study, the Turkish Government has an intention for commencement of a nuclear power program that envisages the construction of 4500 M We nuclear power installed capacity in the next decade if the private energy sector do not make an attempt

  9. License - KOME | LSDB Archive [Life Science Database Archive metadata

    Lifescience Database Archive (English)

    Full Text Available switchLanguage; BLAST Search Image Search Home About Archive Update History Data ...out This Database Database Description Download License Update History of This Database Site Policy | Contact Us License - KOME | LSDB Archive ...

  10. License - RMOS | LSDB Archive [Life Science Database Archive metadata

    Lifescience Database Archive (English)

    Full Text Available switchLanguage; BLAST Search Image Search Home About Archive Update History Data ...out This Database Database Description Download License Update History of This Database Site Policy | Contact Us License - RMOS | LSDB Archive ...

  11. Federal/State cooperation in the licensing of a nuclear power project. A joint licensing process between the US Nuclear Regulatory Commission and the Washington State Energy Facility Site Evaluation Council

    International Nuclear Information System (INIS)

    1984-05-01

    This report summarizes and documents a joint environmental review and licensing process established between the US Nuclear Regulatory Commission (NRC) and the Washington State Energy Facility Site Evaluation Council (EFSEC) in 1980-1983 for the Skagit/Hanford Nuclear Project (S/HNP). It documents the agreements made between the agencies to prepare a joint environmental impact statement responsive to the requirements of the National Environmental Policy Act of 1969 (NEPA) and the Washington State Environmental Policy Act. These agreements also established protocol to conduct joint public evidentiary hearings on matters of mutual jurisdiction, thereby reducing the duplication of effort and increasing the efficiency of the use of resources of federal and state governments and other entities involved in the process. This report may provide guidance and rationale to licensing bodies that may wish to adopt some of the procedures discussed in the report in the event that they become involved in the licensing of a nuclear power plant project. The history of the S/HNP and of the agreement processes are discussed. Discussions are provided on implementing the joint review process. A separate section is included which presents independent evaluations of the process by the applicant, NRC, and EFSEC

  12. License - ASTRA | LSDB Archive [Life Science Database Archive metadata

    Lifescience Database Archive (English)

    Full Text Available switchLanguage; BLAST Search Image Search Home About Archive Update History Data ... notice. About This Database Database Description Download License Update History of This Database Site Policy | Contact Us License - ASTRA | LSDB Archive ...

  13. Development of RESRAD probabilistic computer codes for NRC decommissioning and license termination applications

    International Nuclear Information System (INIS)

    Chen, S. Y.; Yu, C.; Mo, T.; Trottier, C.

    2000-01-01

    In 1999, the US Nuclear Regulatory Commission (NRC) tasked Argonne National Laboratory to modify the existing RESRAD and RESRAD-BUILD codes to perform probabilistic, site-specific dose analysis for use with the NRC's Standard Review Plan for demonstrating compliance with the license termination rule. The RESRAD codes have been developed by Argonne to support the US Department of Energy's (DOEs) cleanup efforts. Through more than a decade of application, the codes already have established a large user base in the nation and a rigorous QA support. The primary objectives of the NRC task are to: (1) extend the codes' capabilities to include probabilistic analysis, and (2) develop parameter distribution functions and perform probabilistic analysis with the codes. The new codes also contain user-friendly features specially designed with graphic-user interface. In October 2000, the revised RESRAD (version 6.0) and RESRAD-BUILD (version 3.0), together with the user's guide and relevant parameter information, have been developed and are made available to the general public via the Internet for use

  14. License - SSBD | LSDB Archive [Life Science Database Archive metadata

    Lifescience Database Archive (English)

    Full Text Available switchLanguage; BLAST Search Image Search Home About Archive Update History Data ...thout notice. About This Database Database Description Download License Update History of This Database Site Policy | Contact Us License - SSBD | LSDB Archive ...

  15. License - SAHG | LSDB Archive [Life Science Database Archive metadata

    Lifescience Database Archive (English)

    Full Text Available switchLanguage; BLAST Search Image Search Home About Archive Update History Data ...ut notice. About This Database Database Description Download License Update History of This Database Site Policy | Contact Us License - SAHG | LSDB Archive ...

  16. License - RPSD | LSDB Archive [Life Science Database Archive metadata

    Lifescience Database Archive (English)

    Full Text Available switchLanguage; BLAST Search Image Search Home About Archive Update History Data ...thout notice. About This Database Database Description Download License Update History of This Database Site Policy | Contact Us License - RPSD | LSDB Archive ...

  17. License - ClEST | LSDB Archive [Life Science Database Archive metadata

    Lifescience Database Archive (English)

    Full Text Available switchLanguage; BLAST Search Image Search Home About Archive Update History Data ...License Update History of This Database Site Policy | Contact Us License - ClEST | LSDB Archive ...

  18. Developing and promoting an intranet site for a drug information service.

    Science.gov (United States)

    Costerison, Emily C; Graham, Angie S

    2008-04-01

    The development and promotion of a drug information service (DIS) intranet site are described. Stanford Hospital and Clinics (SHC) is an acute and tertiary care facility with 613 licensed inpatient beds and 48 outpatient clinics. A DIS intranet site was developed to allow better accessibility to pharmacy forms and products (e.g., drug shortage list, reference guides) and to reduce repetitive requests to the DIS. The goal was to continue to provide information to SHC health care providers but allow the drug information specialist to focus on answering clinical questions. The intranet site was completed over a four-month period. The intranet site was divided into seven webpages: DIS overview, pharmacy and therapeutics, frequently asked questions, quick drug reference guide, ask the pharmacist, drug information resources, and referral center. The preparation for and implementation of the promotional phase took approximately two months. Promotional strategies included the creation and dissemination of brochures and stickers. The intranet site went live on January 1, 2007, and the advertising campaign began one month later. The utility of the site was measured for five months by tracking the number of visits to the site, the number of visits to each webpage, and the number of downloaded files. Request volume, caller affiliation, and question types received by the DIS call center were also recorded. Establishing a DIS intranet site required a considerable time investment and a willingness to work with existing infrastructures, such as the marketing and communications department and Web marketing staff.

  19. The United States nuclear regulatory commission license renewal process

    International Nuclear Information System (INIS)

    Holian, B.E.

    2009-01-01

    The United States (U.S.) Nuclear Regulatory Commission (NRC) license renewal process establishes the technical and administrative requirements for the renewal of operating power plant licenses. Reactor ope-rating licenses were originally issued for 40 years and are allowed to be renewed. The review process for license renewal applications (L.R.A.) provides continued assurance that the level of safety provided by an applicant's current licensing basis is maintained for the period of extended operation. The license renewal review focuses on passive, long-lived structures and components of the plant that are subject to the effects of aging. The applicant must demonstrate that programs are in place to manage those aging effects. The review also verifies that analyses based on the current operating term have been evaluated and shown to be valid for the period of extended operation. The NRC has renewed the licenses for 52 reactors at 30 plant sites. Each applicant requested, and was granted, an extension of 20 years. Applications to renew the licenses of 20 additional reactors at 13 plant sites are under review. As license renewal is voluntary, the decision to seek license renewal and the timing of the application is made by the licensee. However, the NRC expects that, over time, essentially all U.S. operating reactors will request license renewal. In 2009, the U.S. has 4 plants that enter their 41. year of ope-ration. The U.S. Nuclear Industry has expressed interest in 'life beyond 60', that is, requesting approval of a second renewal period. U.S. regulations allow for subsequent license renewals. The NRC is working with the U.S. Department of Energy (DOE) on research related to light water reactor sustainability. (author)

  20. License - dbQSNP | LSDB Archive [Life Science Database Archive metadata

    Lifescience Database Archive (English)

    Full Text Available switchLanguage; BLAST Search Image Search Home About Archive Update History Data ...escription Download License Update History of This Database Site Policy | Contact Us License - dbQSNP | LSDB Archive ...

  1. License - eSOL | LSDB Archive [Life Science Database Archive metadata

    Lifescience Database Archive (English)

    Full Text Available switchLanguage; BLAST Search Image Search Home About Archive Update History Data ...iption Download License Update History of This Database Site Policy | Contact Us License - eSOL | LSDB Archive ...

  2. License - RED | LSDB Archive [Life Science Database Archive metadata

    Lifescience Database Archive (English)

    Full Text Available switchLanguage; BLAST Search Image Search Home About Archive Update History Data ...ts might be changed without notice. About This Database Database Description Download License Update History of This Database Site Policy | Contact Us License - RED | LSDB Archive ...

  3. Development model to public hearing for environmental licensing of nuclear facilities

    Energy Technology Data Exchange (ETDEWEB)

    Vasques, Luciana Gomes; Aquino, Afonso Rodrigues de, E-mail: lu_vasques@usp.br, E-mail: araquino@ipen.br [Instituto de Pesquisas Energeticas e Nucleares (IPEN/CNEN-SP), Sao Paulo, SP (Brazil)

    2015-07-01

    The use of nuclear technology has always been a matter of concern from an environmental point of view. Although disputed, the generation of electricity in nuclear reactors was considered a source of clean emission in relation to emission of gases responsible for the greenhouse effect. In Brazil, nuclear activities are regulated and supervised by the Brazilian Commission of Nuclear Energy - CNEN. Environmental issues associated with nuclear activities are described by CONAMA, and the developments in this area are licensed by IBAMA, regardless of obtaining nuclear licenses issued by CNEN. Obtaining environmental licenses (prior, installation and operation) depends initially on preparing the Environmental Impact Study - EIS and the Environmental Impact Report - EIR, consisting of a presentation of EIS in language accessible to all. EIR is forwarded to bodies and entities with some connection to the enterprise, to be manifested with IBAMA about the relevance of its content. This information serves as a resource for Public Hearings, which are meetings organized by entrepreneurs, conducted by IBAMA, and rely on public participation, can be considered as a licensing step. Public Hearings are subject to subjectivity, and the model proposed in this research becomes more objective ill-defined, difficult to understand actions for the entrepreneur. (author)

  4. Development model to public hearing for environmental licensing of nuclear facilities

    International Nuclear Information System (INIS)

    Vasques, Luciana Gomes; Aquino, Afonso Rodrigues de

    2015-01-01

    The use of nuclear technology has always been a matter of concern from an environmental point of view. Although disputed, the generation of electricity in nuclear reactors was considered a source of clean emission in relation to emission of gases responsible for the greenhouse effect. In Brazil, nuclear activities are regulated and supervised by the Brazilian Commission of Nuclear Energy - CNEN. Environmental issues associated with nuclear activities are described by CONAMA, and the developments in this area are licensed by IBAMA, regardless of obtaining nuclear licenses issued by CNEN. Obtaining environmental licenses (prior, installation and operation) depends initially on preparing the Environmental Impact Study - EIS and the Environmental Impact Report - EIR, consisting of a presentation of EIS in language accessible to all. EIR is forwarded to bodies and entities with some connection to the enterprise, to be manifested with IBAMA about the relevance of its content. This information serves as a resource for Public Hearings, which are meetings organized by entrepreneurs, conducted by IBAMA, and rely on public participation, can be considered as a licensing step. Public Hearings are subject to subjectivity, and the model proposed in this research becomes more objective ill-defined, difficult to understand actions for the entrepreneur. (author)

  5. The strategy of experimental power reactor licensing in Indonesia

    International Nuclear Information System (INIS)

    Moch Djoko Birmano

    2015-01-01

    Currently, BATAN has being planned to develop Experimental Power Reactor (EPR), that is the research nuclear reactor that can generate power (electricity or heat). The EPR is planned will be built in the National Center for Research of Science and Technology (Puspiptek) area at Serpong, South Tangerang, Banten Province, with the choice of reactor types is HTGR with the power size of 10 MWth. As stated in the Act No. 10 year 1997 on Nuclear Power, that every construction and operation of nuclear reactors and other nuclear installations and decommissioning of nuclear reactors required to have a permit. Furthermore, the its implementation arrangements is regulated in Government Regulation (GR) No. 2 year 2014 on Licensing of Nuclear Installations and Nuclear Material Utilization, which contains the requirements and procedures for the licensing process since site, construction, commissioning, operation, and decommissioning, it means licensing is implemented during the activity of construction, operation and decommissioning of NPPs.While, for the more detailed licensing arrangements available in the guidelines of BAPETEN Chairman Regulation (BCR). This study was conducted to understand the legal and institutional aspects, types and stages, and the licensing process of RDE, and identify licensing strategy so that timely as planned. Methodologies used include the literature study, consultation with experts in BAPETEN, discussions in the national seminar including FGD. (author)

  6. Flexible licensing

    Directory of Open Access Journals (Sweden)

    Martyn Jansen

    2012-07-01

    Full Text Available The case is presented for a more flexible approach to licensing online library resources. Today's distributed education environment creates pressure for UK higher and further education institutions (HEI/FEIs to form partnerships and to develop educational products and roll them out across the globe. Online library resources are a key component of distributed education and yet existing licensing agreements struggle to keep pace with the increasing range of users and purposes for which they are required. This article describes the process of developing a flexible approach to licensing and proposes a new model licence for online library resources which has the adaptability needed in this new global educational landscape. These ideas have been presented and discussed at various workshops across Eduserv's and JISC Collections' higher education and publisher communities, and further consultation is ongoing.

  7. Electronic licensing filing system development and implementation experience

    International Nuclear Information System (INIS)

    Walderhaug, J.

    1993-01-01

    The Electronic Licensing Filing System (ELFS) is a microcomputer-based integrated document search and retrieval system for the Nuclear Regulatory Affairs Division of Southern California Edison (SCE). ELFS allows the user access to the current licensing basis of a subject by providing an easily searchable electronic information data base consisting of regulatory correspondence, design-bases documentation, licensing documents [updated final safety and analysis report (UFSAR) and technical specifications], and regulatory guidance or directives [10CFR, generic letters, bulletins, notices, circulars, regulatory guides, policy statements, and selected US Nuclear Regulatory Commission (NRC) regulations]. It is used in the preparation of correspondence and submittals to the NRC, 50.59 safety evaluations, design-bases reconstitution, and commitment tracking and management

  8. To License or Not to License Remanufacturing Business?

    Directory of Open Access Journals (Sweden)

    Zu-Jun Ma

    2018-01-01

    Full Text Available Many original equipment manufacturers (OEMs face the choice of whether to license an independent remanufacturer (IR to remanufacture their used products. In this paper, we develop closed-loop supply chain models with licensed and unlicensed remanufacturing operations to analyze the competition and cooperation between an OEM and an IR. The OEM sells new products and collects used products through trade-ins, while the IR intercepts the OEM’s cores to produce remanufactured products and sell them in the same market. We derive optimal decisions for each of the two types of firms in licensed and unlicensed remanufacturing scenarios and identify conditions under which the OEM and the IR would be most likely to cooperate with each other in implementing remanufacturing. The results show although it is beneficial for an OEM to license an IR to remanufacture its cores, it is not always necessary for an IR to accept OEM’s authorization. Moreover, we contrast the result for licensed remanufacturing scenario in the decentralized system with that in the centrally coordinated system to quantify potential inefficiency resulting from decentralization of decision making.

  9. DEVELOPING SITE-SPECIFIC DERIVED CONCENTRATION GUIDELINE LEVELS FOR MULTIPLE MEDIA AT THE CONNECTICUT YANKEE HADDAM NECK PLANT

    International Nuclear Information System (INIS)

    Taylor, S.W.; Smith, L.C.; Carr, R.K.; Carson, A.; Darois, E.

    2003-01-01

    As part of the license termination process, site-specific Derived Concentration Guideline Levels for the Haddam Neck Plant site are developed for soil, groundwater, concrete left standing, and concrete demolished that satisfy the radiological criteria for unrestricted use as defined in 10 CFR 20.1402. Background information on the license termination process and characteristics of the Haddam Neck Plant site are presented. The dose models and associated resident farmer and building occupancy scenarios, applicable pathways, and critical groups developed to establish the Derived Concentration Guideline Levels are described. A parameter assignment process is introduced wherein general population values are used to establish behavioral and metabolic parameters representative of an average member of the critical group, while the uncertainty associated with important physical parameters is considered. A key element of the parameter assignment process is the use of sensitivity analysis to identify the dose sensitive physical parameters and to ensure that such parameters are assigned conservative values. Structuring the parameter assignment process, completing the formal sensitivity analyses, and assigning conservative values to the sensitive physical parameters in a consistent way establishes a calculation framework that lead to Derived Concentration Guideline Levels with a uniform level of conservatism across all media and all radionuclides

  10. Long-term surveillance plan for the South Clive Disposal Site, Clive, Utah

    International Nuclear Information System (INIS)

    1996-03-01

    This long-term surveillance plan (LTSP) describes the US Department of Energy's (DOE) long-term care program for the Uranium Mill Tailings Remedial Action (UMTRA) Project South Clive disposal site in Clive, Utah. The US Nuclear Regulatory Commission (NRC) has developed regulations for the issuance of a general license for the custody and long-term care of UMTRA Project disposal sites in 10 CRF Part 40. The purpose of this general license is to ensure that the UMTRA Project disposal sites will be cared for in a manner that protects the public health and safety and the environment. For each disposal site to be licensed, the NRC requires the DOE to submit a site-specific LTSP. The DOE prepared this LTSP to meet this requirement for the South Clive disposal site. The general license becomes effective when the NRC concurs with the DOE's determination of completion of remedial action for the South Clive site and the NRC formally accepts this LTSP. This LTSP describes the long-term surveillance program the DOE will implement to ensure that the South Clive disposal site performs as designed. The program's primary activity is site inspections to identify threats to disposal cell integrity

  11. Status of the Texas low-level radioactive waste disposal site - construction sequencing and staffing patterns

    International Nuclear Information System (INIS)

    Jacobi, L.R. Jr.

    1996-01-01

    The Texas Low-Level Radioactive Waste Disposal Authority, an agency of the State of Texas, has been attempting to develop a site for the disposal of low-level radioactive waste in Texas for more than fourteen years. Since 1991, the agency has been evaluating a site near Sierra Blanca, in far west Texas. Site characterization was completed in 1992, and a license application was filed that year. Construction plans were completed in 1993. In April 1996, the licensing agency, the Texas Natural Resource Conservation Commission, completed its review and proposed to issue a license. The administrative hearings on the proposed license should be completed by July 1997. The Authority is prepared to begin construction and operations as soon as a final license can be issued

  12. Resolving the issues arisen during the development of License Renewal Application at PAKS NPP

    International Nuclear Information System (INIS)

    Ratkai, Sandor; Katona, Tamas Janos

    2012-01-01

    Operational license of the four VVER-440/213 units at Paks NPP, Hungary is limited to the design lifetime of 30 years. Extension by an additional 20 years of the original license is one of the main goals of the plant owner. In 2008 a programme for long-term operation (LTO) was developed and submitted to the Hungarian Atomic Energy Authority. The LTO Programme defines the activities for ensuring the extension of the operational lifetime and contains the justification of the safe LTO. The LTO Programme has to be implemented and comprehensive justification of the safe LTO has to be provided in the formal License Renewal Applications unit by unit. This work has been completed by the end of 2011, and the application has been submitted for approval for the Unit 1. The authority review and the approval of the License Renewal Application for Unit 1 should be finished before the expiration of the original design lifetime in 2012. In line with the regulations and supporting the License Renewal Application, a large number of engineering tasks have been performed. In this paper the entire project will be reported. The issues will be discussed, which have been arisen during the development of the application. The difficulties caused by the Hungarian technical and regulatory peculiarities will be presented. (author)

  13. Financing a new low-level radioactive waste disposal site

    International Nuclear Information System (INIS)

    Dressen, A.L.; Serie, P.J.; McGarvey, R.S.; Lemmon, R.A.

    1982-01-01

    No new commercial low-level radioactive waste disposal site has been licensed in the past decade. During the time, inflation has wreaked havoc on the costs for the labor, equipment, and buildings that will be necessary to develop and operate new sites. The regulatory environment has become much more complex with enactment of the National Environmental Policy Act (NEPA) and the recent issuance by the Nuclear Regulatory Commission (NRC) of a draft set of comprehensive regulations for land disposal of low-level waste (10 CFR Part 61). Finally, the licensing process itself has become much lengthier as both the site developers and regulators respond to the public's desire to be more involved in decisions that may affect their lives

  14. The development of reactor operator license examination question bank

    International Nuclear Information System (INIS)

    Kim, In Hwan; Woo, S. M.; Kam, S. C.; Nam, K. J.; Lim, H. P.

    2001-12-01

    The number of NPP keeps increasing therefore there is more need of reactor operators. This trend requires the more efficiency in managing the license examination. Question bank system will help us to develop good quality examination materials and keep them in it. The ultimate purpose of the bank system is for selecting qualified reactor operators who are primarily responsible for the safety of reactor operation in NPP

  15. License - Q-TARO | LSDB Archive [Life Science Database Archive metadata

    Lifescience Database Archive (English)

    Full Text Available switchLanguage; BLAST Search Image Search Home About Archive Update History Data ...thout notice. About This Database Database Description Download License Update History of This Database Site Policy | Contact Us License - Q-TARO | LSDB Archive ...

  16. Siting simulation for low-level waste disposal facilities

    International Nuclear Information System (INIS)

    Roop, R.D.; Rope, R.C.

    1985-01-01

    The Mock Site Licensing Demonstration Project has developed the Low-Level Radioactive Waste Siting Simulation, a role-playing exercise designed to facilitate the process of siting and licensing disposal facilities for low-level waste (LLW). This paper describes the development, content, and usefulness of the siting simulation. The simulation can be conducted at a workshop or conference, involves 14 or more participants, and requires about eight hours to complete. The simulation consists of two sessions; in the first, participants negotiate the selection of siting criteria, and in the second, a preferred disposal site is chosen from three candidate sites. The project has sponsored two workshops (in Boston, Massachusetts and Richmond, Virginia) in which the simulation has been conducted for persons concerned with LLW management issues. It is concluded that the simulation can be valuable as a tool for disseminating information about LLW management; a vehicle that can foster communication; and a step toward consensus building and conflict resolution. The DOE National Low-Level Waste Management Program is now making the siting simulation available for use by states, regional compacts, and other organizations involved in development of LLW disposal facilities

  17. 10 CFR 50.55 - Conditions of construction permits, early site permits, combined licenses, and manufacturing...

    Science.gov (United States)

    2010-01-01

    ... construction or manufacture, or any defect found in the final design of a facility as approved and released for..., combined licenses, and manufacturing licenses. 50.55 Section 50.55 Energy NUCLEAR REGULATORY COMMISSION DOMESTIC LICENSING OF PRODUCTION AND UTILIZATION FACILITIES Issuance, Limitations, and Conditions of...

  18. Development of software tools for supporting building clearance and site release at UKAEA

    International Nuclear Information System (INIS)

    Jessop, G.; Pearl, M.

    2002-01-01

    UKAEA sites generally have complex histories and have been subject to a diverse range of nuclear operations. Most of the nuclear reactors, laboratories, workshops and other support facilities are now redundant and a programme of decommissioning works in accordance with IAEA guidance is in progress. Decommissioning is being carried out in phases with post- operative activities, care and maintenance and care and surveillance periods between stages to allow relatively short-lived radioactivity to decay. This reduces dose levels to personnel and minimises radioactive waste production. Following on from these stages is an end point phase which corresponds to the point at which the risks to human health and the environment are sufficiently low so that the buildings / land can be released for future use. Unconditional release corresponds to meeting the requirement for 'de-licensing'. Although reaching a de-licensable end point is the desired aim for UKAEA sites, it is recognised that this may take hundreds of years for parts of some UKAEA sites, or may never be attainable at a reasonable cost to the UK taxpayer. Thus on these sites, long term risk management systems are in place to minimise the impact on health, safety and the environment. In order to manage these short, medium and long term liabilities, UKAEA has developed a number of software tools based on good practice guidance. One of these tools in particular is being developed to address building clearance and site release. This tool, IMAGES (Information Management and Geographical Information System) integrates systematic data capture, with database management and spatial assessment (through a Geographical Information System). Details of IMAGES and its applications are discussed in the paper. This paper outlines the approach being adopted by UKAEA for building and site release and the integrated software system, IMAGES, being used to capture, collate, interpret and report results. The key to UKAEA's strategy for

  19. License - RGP gmap | LSDB Archive [Life Science Database Archive metadata

    Lifescience Database Archive (English)

    Full Text Available switchLanguage; BLAST Search Image Search Home About Archive Update History Data ...nged without notice. About This Database Database Description Download License Update History of This Database Site Policy | Contact Us License - RGP gmap | LSDB Archive ...

  20. Long-term surveillance plan for the Maybell, Colorado Disposal Site

    International Nuclear Information System (INIS)

    1997-09-01

    This long-term surveillance plan (LTSP) describes the U.S. Department of Energy's (DOE) long-term care program for the Uranium Mill Tailings Remedial Action (UMTRA) Project Maybell disposal site in Moffat County, Colorado. The U.S. Nuclear Regulatory Commission (NRC) has developed regulations for the issuance of a general license for the custody and long-term care of UMTRA Project disposal sites in 10 CFR Part 40. The purpose of this general license is to ensure that the UMTRA Project disposal sites are cared for in a manner that protects the public health and safety and the environment. Before each disposal site is licensed, the NRC requires the DOE to submit a site-specific LTSP. The DOE prepared this LTSP to meet this requirement for the Maybell disposal site. The general license becomes effective when the NRC concurs with the DOE's determination that remedial action is complete for the Maybell site and the NRC formally accepts this LTSP. This document describes the long-term surveillance program the DOE will implement to ensure the Maybell disposal site performs as designed. The program is based on site inspections to identify threats to disposal cell integrity. The LTSP is based on the UMTRA Project long-term surveillance program guidance document and meets the requirements of 10 CFR section 40.27(b) and 40 CFR section 192.03

  1. Trends in nuclear licensing

    Energy Technology Data Exchange (ETDEWEB)

    Dalton, N W [Council for Nuclear Safety, Hennopsmeer, Pretoria (South Africa)

    1990-06-01

    The development of nuclear safety and licensing is briefly reviewed in four stages namely: The Formative Period (1946-1959), The Expansive Period (1960-1969), The Mature Period (1970-1979) and the Apprehensive Period (1980-1989). Particular safety issues in the respective periods are highlighted to indicate the changing emphasis of nuclear licensing over the past thirty years or so. Against this background, nuclear licensing. (author)

  2. Trends in nuclear licensing

    International Nuclear Information System (INIS)

    Dalton, N.W.

    1990-01-01

    The development of nuclear safety and licensing is briefly reviewed in four stages namely: The Formative Period (1946-1959), The Expansive Period (1960-1969), The Mature Period (1970-1979) and the Apprehensive Period (1980-1989). Particular safety issues in the respective periods are highlighted to indicate the changing emphasis of nuclear licensing over the past thirty years or so. Against this background, nuclear licensing. (author)

  3. Online driver's license renewal.

    Science.gov (United States)

    2015-09-01

    The Kentucky Department of Vehicle Regulation is exploring the possibility of developing and implementing online : drivers license renewal. The objective of this project was to: 1) evaluate online drivers license and REAL ID renewal : programs ...

  4. License - fRNAdb | LSDB Archive [Life Science Database Archive metadata

    Lifescience Database Archive (English)

    Full Text Available switchLanguage; BLAST Search Image Search Home About Archive Update History Data ...be changed without notice. About This Database Database Description Download License Update History of This Database Site Policy | Contact Us License - fRNAdb | LSDB Archive ...

  5. License - AT Atlas | LSDB Archive [Life Science Database Archive metadata

    Lifescience Database Archive (English)

    Full Text Available switchLanguage; BLAST Search Image Search Home About Archive Update History Data ... might be changed without notice. About This Database Database Description Download License Update History of This Database Site Policy | Contact Us License - AT Atlas | LSDB Archive ...

  6. License - TP Atlas | LSDB Archive [Life Science Database Archive metadata

    Lifescience Database Archive (English)

    Full Text Available switchLanguage; BLAST Search Image Search Home About Archive Update History Data ... might be changed without notice. About This Database Database Description Download License Update History of This Database Site Policy | Contact Us License - TP Atlas | LSDB Archive ...

  7. Early Site Permit Demonstration Program: Recommendations for communication activities and public participation in the Early Site Permit Demonstration Program

    International Nuclear Information System (INIS)

    1993-01-01

    On October 24, 1992, President Bush signed into law the National Energy Policy Act of 1992. The bill is a sweeping, comprehensive overhaul of the Nation's energy laws, the first in more than a decade. Among other provisions, the National Energy Policy Act reforms the licensing process for new nuclear power plants by adopting a new approach developed by the US Nuclear Regulatory Commission (NRC) in 1989, and upheld in court in 1992. The NRC 10 CFR Part 52 rule is a three-step process that guarantees public participation at each step. The steps are: early site permit approval; standard design certifications; and, combined construction/operating licenses for nuclear power reactors. Licensing reform increases an organization's ability to respond to future baseload electricity generation needs with less financial risk for ratepayers and the organization. Costly delays can be avoided because design, safety and siting issues will be resolved before a company starts to build a plant. Specifically, early site permit approval allows for site suitability and acceptability issues to be addressed prior to an organization's commitment to build a plant. Responsibility for site-specific activities, including communications and public participation, rests with those organizations selected to try out early site approval. This plan has been prepared to assist those companies (referred to as sponsoring organizations) in planning their communications and public involvement programs. It provides research findings, information and recommendations to be used by organizations as a resource and starting point in developing their own plans

  8. Strategy and plan for siting and licensing a Rocky Mountain low-level radioactive waste facility

    International Nuclear Information System (INIS)

    Whitman, M.

    1983-09-01

    In 1979, the States of Nevada and Washington temporarily closed their commercial low-level radioactive waste (LLW) disposal facilities and South Carolina, the only other state hosting such a facility, restricted the amount of waste it would accept. All three states then announced that they did not intend to continue the status quo of accepting all of the country's commercial low-level radioactive waste. Faced with this situation, other states began considering alternative LLW management and disposal options. In the Rocky Mountain region, this evolved into discussions for the development of an interstate compact to manage low-level waste. Inherent in this management plan was a strategy to site and license a new LLW disposal facility for the Rocky Mountain region. The Rocky Mountain Low-Level Radioactive Waste Compact was negotiated over the course of a year, with final agreement on the language of the compact agreed to in early 1982. States eligible to join the compact are Arizona, Colorado, Nevada, New Mexico, Utah, and Wyoming. Colorado adopted the compact into law in 1982, and Nevada, New Mexico and Wyoming adopted it in 1983. Utah has joined the Northwest Compact, although it may decide to join the Rocky Mountain Compact after a new disposal facility is developed for the region. Arizona has taken no action on the Rocky Mountain Compact

  9. Report of the Task Force on bonding and perpetual care of nuclear licensed activities

    International Nuclear Information System (INIS)

    Snellings, D.D. Jr.

    1975-01-01

    The primary concern was to consider the bonding and perpetual care requirements of state-licensed shallow land burial sites used for the disposal of radioactive wastes. The specific charge of the task force was to examine in detail the requirements for establishing bonding and perpetual care programs for all types of licensed nuclear activities and to report the findings of the task force as guidance to assist states in program development. Goals and recommendations of the task force are discussed

  10. 48 CFR 227.7203-4 - License rights.

    Science.gov (United States)

    2010-10-01

    ... Software and Computer Software Documentation 227.7203-4 License rights. (a) Grant of license. The... license, under an irrevocable license granted or obtained by the contractor which developed the software... granted to the Government. The scope of a computer software license is generally determined by the source...

  11. Licensing reform in the USA

    International Nuclear Information System (INIS)

    1991-01-01

    The licensing process for nuclear power plants in the USA is currently in two distinct stages: the issuance of a construction permit followed later by the issuance of an operation license. The ''two-step'' process has come under heavy criticism from the U.S. nuclear industry on the grounds that it causes uncertainty and delays and therefore inhibits new commitments to nuclear power plants. In 1989 the NRC published new regulations for the licensing of nuclear power plants which provide for the issuance of early site permits, safety certifications of standard designs, and combined construction permits and operating licences. The new rule was challenged by intervenors representing antinuclear groups who filed a legal challenge seeking to have the rule set aside on the grounds that it violates the Atomic Energy Act which they allege makes two-step licensing mandatory. In November 1990 the US Court of Appeals upheld the NRC's authority to issue combined licenses. An appeal for a rehearing has been filed. The paper analyses the events and the possible consequences of an adverse court decision. It reviews the options open to the NRC and industry if the court decision is upheld. The possibility of congressional action to amend the Atomic Energy Act is discussed. (author)

  12. Development of quantitative goals for inherent safety feature design and licensing

    International Nuclear Information System (INIS)

    Kastenberg, W.E.; Apostolakis, G.; Dhir, V.K.; Okrent, D.

    1987-01-01

    There is now considerable interest in the development of advanced fast reactors whose major focus is inherent safety. The achievement of inherent safety can be viewed from several aspects. In the Integral Fast Reactor Concept the approach is to utilize the intrinsic characteristics of pool-type liquid metal fast breeder reactors (LMFBRs) and the properties of metal fuels to integrate a high degree of inherent safety into the design. The PRISM and SAFR concepts focus on other inherent safety features. The reactors discussed above represent a radical departure from existing LWR designs as well as previous LMFBR designs (e.g., CRBRP) which are based, for the most part, on the General Design Criteria found in 10CFR50 Appendix. In view of these parallel developments (advanced reactors exploiting inherent safety and the use of quantitative goals to augment licensing), there appears to be a need to perform research on the development of methods for designing, assessing, and licensing inherent safety features in advanced reactors. The objectives of such research are outlined

  13. Hanford Site Development Plan

    International Nuclear Information System (INIS)

    Rinne, C.A.; Curry, R.H.; Hagan, J.W.; Seiler, S.W.; Sommer, D.J.; Yancey, E.F.

    1990-01-01

    The Hanford Site Development Plan (Site Development Plan) is intended to guide the short- and long-range development and use of the Hanford Site. All acquisition, development, and permanent facility use at the Hanford Site will conform to the approved plan. The Site Development Plan also serves as the base document for all subsequent studies that involve use of facilities at the Site. This revision is an update of a previous plan. The executive summary presents the highlights of the five major topics covered in the Site Development Plan: general site information, existing conditions, planning analysis, Master Plan, and Five-Year Plan. 56 refs., 67 figs., 31 tabs

  14. Hanford Site Development Plan

    Energy Technology Data Exchange (ETDEWEB)

    Rinne, C.A.; Curry, R.H.; Hagan, J.W.; Seiler, S.W.; Sommer, D.J. (Westinghouse Hanford Co., Richland, WA (USA)); Yancey, E.F. (Pacific Northwest Lab., Richland, WA (USA))

    1990-01-01

    The Hanford Site Development Plan (Site Development Plan) is intended to guide the short- and long-range development and use of the Hanford Site. All acquisition, development, and permanent facility use at the Hanford Site will conform to the approved plan. The Site Development Plan also serves as the base document for all subsequent studies that involve use of facilities at the Site. This revision is an update of a previous plan. The executive summary presents the highlights of the five major topics covered in the Site Development Plan: general site information, existing conditions, planning analysis, Master Plan, and Five-Year Plan. 56 refs., 67 figs., 31 tabs.

  15. Licensing Support Network: An Electronic Discovery System

    International Nuclear Information System (INIS)

    Gil, A. V.; Jensen, D.; McKinnon, B.

    2002-01-01

    The necessary authorization for the U. S. Department of Energy's (DOE) Office of Civilian Radioactive Waste Management (OCRWM) to submit a License Application (LA) is contingent upon the policy process defined in the Nuclear Waste Policy Act, as amended (NWPA), with some steps yet to occur. In spite of this uncertainty, the DOE must take prudent and appropriate action now, and over the next several years, to prepare for submittal of an application and to facilitate the U. S. Nuclear Regulatory Commission (NRC) review of this application, if the Yucca Mountain site is recommended and approved for repository development. One of these steps the DOE has taken involves working with the NRC's Advisory Review Panel to develop Licensing Support Network (LSN) requirements and guidelines. The NRC has made a prototype of the LSN web page available at www.LSNNET.gov. The OCRWM part of the LSN currently has an indefinite life cycle and may need to remain in existence until the repository is closed, which could be as long as 325 years

  16. Configuration system development of site and environmental information for radwaste disposal facility

    International Nuclear Information System (INIS)

    Park, Se-Moon; Yoon, Bong-Yo; Kim, Chang-Lak

    2005-01-01

    License for the nuclear facilities such as radioactive waste repository demands documents of site characterization, environmental assessment and safety assessment. This performance will produce bulk of the relevant data. For the safe management of radioactive waste repository, data of the site and environment have to be collected and managed systematically. Particularly for the radwaste repository, which has to be institutionally controlled for a long period after closure, the data will be collected and maintained through the monitoring programme. To meet this requirement, a new programme called 'Site Information and Total Environmental data management System (SITES)' has been developed. The scope and function of the SITES is issued in data DB, safety assessment and monitoring system. In this respect, SITES is designed with two modules of the SITES Database Module (SDM) and the Monitoring and Assesment (M and A). The SDM module is composed of three sub-modules. One is the Site Information Management System (SIMS), which manages data of site characterization such as topography, geology, hydrogeology, engineering geology, etc. The other is the ENVironmental Information management System (ENVIS) and Radioactive ENVironmental Information management System (RENVIS), which manage environmental data required for environmental assessment performance. ENVIS and RENVIS covered almost whole items of environmental assessment report required by Korean government. The SDM was constructed based on Entity Relationship Diagram produced from each item. Also using ArcGIS with the spatial characteristics of the data, it enables groundwater and water property monitoring networks, etc. To be analyzed in respect of every theme. The sub-modules of M and A called the Site and Environment Monitoring System (SEMS) and the Safety Assessment System (SAS) were developed. SEMS was designed to manage the inspection records of the individual measuring instruments and facilities, and the on

  17. Long-term surveillance plan for the Gunnison, Colorado disposal site. Revision 2

    International Nuclear Information System (INIS)

    1997-02-01

    This long-term surveillance plan (LTSP) describes the US Department of Energy's (DOE) long-term care program for the Uranium Mill Tailings Remedial Action (UMTRA) Project Gunnison disposal site in Gunnison County, Colorado. The US Nuclear Regulatory Commission (NRC) has developed regulations for the issuance of a general license for the custody and long-term care of UMTRA Project disposal sites in 10 CFR Part 40. The purpose of this general license is to ensure that the UMTRA Project disposal sites will be cared for in a manner that protects the public health and safety and the environment. Before each disposal site is licensed, the NRC requires the DOE to submit a site-specific LTSP. This LTSP describes the long-term surveillance program the DOE will implement to ensure that the Gunnison disposal site performs as designed. The program is based on two distinct activities: (1) site inspections to identify threats to disposal cell integrity, and (2) ground water monitoring to demonstrate disposal cell performance

  18. NPP License Renewal and Aging Management: Revised Guidance

    International Nuclear Information System (INIS)

    Hull, A.B.; Hiser, A.L.; Lindo-Talin, S.E.

    2012-01-01

    Based on the Atomic Energy Act, the NRC issues licenses for commercial power reactors to operate for up to 40 years and allows these licenses to be renewed for up to another 20 years. NRC has approved license renewal for well over 50% of U.S. located reactors originally licensed to operate for 40 years. Of these 104 reactors (69 PWRs, 35 BWRs), the NRC has issued renewed licenses for 71 units and is currently reviewing applications for another 15 units. As of May 1, 2012, ten plants at nine sites had entered their 41st year of operation and thus are in their first period of extended operation (PEO). Five more plants will enter the PEO by the end of 2012. One foundation of the license renewal process has been license renewal guidance documents (LRGDs). The U.S. Nuclear Regulatory Commission (NRC) revised key guidance documents used for nuclear power license renewal in 2010 and 2011. These include NUREG-1800, 'Standard Review Plan for Review of License Renewal Applications,' revision 2 (SRP-LR), and NUREG-1801, 'Generic Aging Lessons Learned (GALL) Report,' revision 2 (GALL Report). The guidance documents were updated to reflect lessons learned and operating experience gained since the guidance documents were last issued in 2005. (author)

  19. Product Licenses Database Application

    CERN Document Server

    Tonkovikj, Petar

    2016-01-01

    The goal of this project is to organize and centralize the data about software tools available to CERN employees, as well as provide a system that would simplify the license management process by providing information about the available licenses and their expiry dates. The project development process is consisted of two steps: modeling the products (software tools), product licenses, legal agreements and other data related to these entities in a relational database and developing the front-end user interface so that the user can interact with the database. The result is an ASP.NET MVC web application with interactive views for displaying and managing the data in the underlying database.

  20. Hanford Site Development Plan

    International Nuclear Information System (INIS)

    Hathaway, H.B.; Daly, K.S.; Rinne, C.A.; Seiler, S.W.

    1993-05-01

    The Hanford Site Development Plan (HSDP) provides an overview of land use, infrastructure, and facility requirements to support US Department of Energy (DOE) programs at the Hanford Site. The HSDP's primary purpose is to inform senior managers and interested parties of development activities and issues that require a commitment of resources to support the Hanford Site. The HSDP provides an existing and future land use plan for the Hanford Site. The HSDP is updated annually in accordance with DOE Order 4320.1B, Site Development Planning, to reflect the mission and overall site development process. Further details about Hanford Site development are defined in individual area development plans

  1. Specification of requirements to get a license for an Independent Spent Fuel Dry Storage Installation (ISFSI) at the site of the NPP-LV

    International Nuclear Information System (INIS)

    Serrano R, M. L.

    2015-09-01

    This article describes some of the work done in the Comision Nacional de Seguridad Nuclear y Salvaguardias (CNSNS) to define specifically the requirements that the Federal Electricity Commission (CFE) shall meet to submit for consideration of CNSNS an operation request of an Independent Spent Fuel Dry Storage Installation (ISFSI). The project of a facility of this type arose from the need to provide storage capacity for spent nuclear fuel in the nuclear power plant of Laguna Verde (NPP-LV) and to continue the operation at the same facility in a safe manner. The licensing of these facilities in the United States of America has two modes: specific license or general license. The characteristics of these licenses are described in this article. However, in Mexico the existing national legislation is not designed for such license types, in fact there is a lack of standards or regulations in this regard. The regulatory law of Article 27 of the Constitution in the nuclear matter, only generally establishes that this type of facility requires an authorization from the Ministry of Energy. For this reason and because there is not a national legislation, was necessary to use the legislation that provides the Nuclear Regulatory Commission of USA, the US NRC. However, it cannot be applied as is established, so was necessary that the CNSNS analyze one by one the requirements of both types of license and determine what would be required to NPP-LV to submit its operating license of ISFSI. The American regulatory applicable to an ISFSI, the 10-Cfr-72 of the US NRC, establishes the requirements for both types of licenses. Chapter 10-Cfr was analyzed in all its clauses and coupled to the laws, regulations and standards as well as to the requirements established by CNSNS, all associated with a store spent fuel on site; the respective certification of containers for spent fuel dry storage was not included in this article, even though the CNSNS also performed that activity under the

  2. Nuclear Siting and Licensing Act of 1978. Hearings before the Subcommittee on Energy and Power, Committee on Interstate and Foreign Commerce, House of Representatives, Ninety-Fifth Congress

    International Nuclear Information System (INIS)

    Anon.

    1979-01-01

    The Subcommittee on Energy and Power conducted hearings on the administration proposal to revise the process by which nuclear power plants are licensed. The purpose of this proposal is to substantially reduce the amount of time needed to license and construct nuclear powerplants. The bill attempts to encourage the early selection of possible sites by separating the process by which such sites are approved fom the process by which plants are licensed. The bill would dispense with the existing requirement that all hearings be adjudicatory, and instead authorize informal hearings on certain issues, principally those which would be conducted pursuant to the National Environmental Policy Act of 1969. The bill would authorize a State which has established a program, consistent with the criteria contained in the act and regulations promulgated by the Nuclear Regulatory Commission, to determine the environmental acceptability of, and/or the need for, a proposed nuclear plant which would be located within its boundaries. Finally, the bill seeks to encourage the use of standardized design and authorizes the NRC to provide funds to intervenors under certain specified conditions

  3. Long-term surveillance plan for the Gunnison, Colorado disposal site

    International Nuclear Information System (INIS)

    1996-04-01

    This long-term surveillance plan (LTSP) describes the U.S. Department of Energy's (DOE) long-term care program for the Uranium Mill Tailings Remedial Action (UMTRA) Project Gunnison disposal site in Gunnison County, Colorado. The U.S. Nuclear Regulatory Commission (NRC) has developed regulations for the issuance of a general license for the custody and long-term care of UMTRA Project disposal sites in 10 CFR Part 40. The purpose of this general license is to ensure that the UMTRA Project disposal sites will be cared for in a manner that protects the public health and safety and the environment. For each disposal site to be licensed, the NRC requires the DOE to submit a site-specific LTSP. The DOE prepared this LTSP to meet this requirement for the Gunnison disposal site. The general license becomes effective when the NRC concurs with the DOE's determination of completion of remedial action for the Gunnison site and the NRC formally accepts this LTSP. This LTSP describes the long-term surveillance program the DOE will implement to ensure that the Gunnison disposal site performs as designed. The program is based on two distinct activities: (1) site inspections to identify threats to disposal cell integrity, and (2) ground water monitoring to demonstrate disposal cell performance. The LTSP is based on the UMTRA Project long-term surveillance program guidance and meets the requirements of 10 CFR section 40.27(b) and 40 CFR section 192.03

  4. Long-term surveillance plan for the Gunnison, Colorado, disposal site

    International Nuclear Information System (INIS)

    1997-04-01

    This long-term surveillance plan (LTSP) describes the U.S. Department of Energy's (DOE) long-term care program for the Uranium Mill Tailings Remedial Action (UMTRA) Project Gunnison disposal site in Gunnison County, Colorado. The U.S. Nuclear Regulatory Commission (NRC) has developed regulations for the issuance of a general license for the custody and long-term care of UMTRA Project disposal sites in 10 CFR Part 40. The purpose of this general license is to ensure that the UMTRA Project disposal sites will be cared for in a manner that protects the public health and safety and the environment. Before each disposal site is licensed, the NRC requires the DOE to submit a site-specific LTSP. The DOE prepared this LTSP to meet this requirement for the Gunnison disposal site. The general license becomes effective when the NRC concurs with the DOE's determination of completion of remedial action for the Gunnison site and the NRC formally accepts this LTSP. This LTSP describes the long-term surveillance program the DOE will implement to ensure that the Gunnison disposal site performs as designed. The program is based on two distinct activities: (1) site inspections to identify threats to disposal cell integrity, and (2) ground water monitoring to demonstrate disposal cell performance. The LTSP is based on the UMTRA Project long-term surveillance program guidance and meets the requirements of 10 CFR section 40.27(b) and 40 CFR section 192.03

  5. Long-term surveillance plan for the Gunnison, Colorado disposal site

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-04-01

    This long-term surveillance plan (LTSP) describes the U.S. Department of Energy`s (DOE) long-term care program for the Uranium Mill Tailings Remedial Action (UMTRA) Project Gunnison disposal site in Gunnison County, Colorado. The U.S. Nuclear Regulatory Commission (NRC) has developed regulations for the issuance of a general license for the custody and long-term care of UMTRA Project disposal sites in 10 CFR Part 40. The purpose of this general license is to ensure that the UMTRA Project disposal sites will be cared for in a manner that protects the public health and safety and the environment. For each disposal site to be licensed, the NRC requires the DOE to submit a site-specific LTSP. The DOE prepared this LTSP to meet this requirement for the Gunnison disposal site. The general license becomes effective when the NRC concurs with the DOE`s determination of completion of remedial action for the Gunnison site and the NRC formally accepts this LTSP. This LTSP describes the long-term surveillance program the DOE will implement to ensure that the Gunnison disposal site performs as designed. The program is based on two distinct activities: (1) site inspections to identify threats to disposal cell integrity, and (2) ground water monitoring to demonstrate disposal cell performance. The LTSP is based on the UMTRA Project long-term surveillance program guidance and meets the requirements of 10 CFR {section}40.27(b) and 40 CFR {section}192.03.

  6. Long-term surveillance plan for the Gunnison, Colorado, disposal site

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1997-04-01

    This long-term surveillance plan (LTSP) describes the U.S. Department of Energy`s (DOE) long-term care program for the Uranium Mill Tailings Remedial Action (UMTRA) Project Gunnison disposal site in Gunnison County, Colorado. The U.S. Nuclear Regulatory Commission (NRC) has developed regulations for the issuance of a general license for the custody and long-term care of UMTRA Project disposal sites in 10 CFR Part 40. The purpose of this general license is to ensure that the UMTRA Project disposal sites will be cared for in a manner that protects the public health and safety and the environment. Before each disposal site is licensed, the NRC requires the DOE to submit a site-specific LTSP. The DOE prepared this LTSP to meet this requirement for the Gunnison disposal site. The general license becomes effective when the NRC concurs with the DOE`s determination of completion of remedial action for the Gunnison site and the NRC formally accepts this LTSP. This LTSP describes the long-term surveillance program the DOE will implement to ensure that the Gunnison disposal site performs as designed. The program is based on two distinct activities: (1) site inspections to identify threats to disposal cell integrity, and (2) ground water monitoring to demonstrate disposal cell performance. The LTSP is based on the UMTRA Project long-term surveillance program guidance and meets the requirements of 10 CFR {section}40.27(b) and 40 CFR {section}192.03.

  7. Long-term surveillance plan for the Gunnison, Colorado, disposal site

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-05-01

    This long-term surveillance plan (LTSP) describes the U.S. Department of Energy`s (DOE) long-term care program for the Uranium Mill Tailings Remedial Action (UMTRA) Project Gunnison disposal site in Gunnison County, Colorado. The U.S. Nuclear Regulatory Commission (NRC) has developed regulations for the issuance of a general license for the custody and long-term care of UMTRA Project disposal sites in 10 CFR Part 40. The purpose of this general license is to ensure that the UMTRA Project disposal sites will be cared for in a manner that protects the public health and safety and the environment. For each disposal site to be licensed, the NRC requires the DOE to submit a site-specific LTSP. The DOE prepared this LTSP to meet this requirement for the Gunnison disposal site. The general license becomes effective when the NRC concurs with the DOE`s determination of completion of remedial action for the Gunnison site and the NRC formally accepts this LTSP. This LTSP describes the long-term surveillance program the DOE will implement to ensure that the Gunnison disposal site performs as designed. The program is based on two distinct activities: (1) site inspections to identify threats to disposal cell integrity, and (2) ground water monitoring to demonstrate disposal cell performance. The LTSP is based on the UMTRA Project long-term surveillance program guidance and meets the requirements of 10 CFR {section}40.27(b) and 40 CFR {section}192.03.

  8. Long-term surveillance plan for the Gunnison, Colorado, disposal site

    International Nuclear Information System (INIS)

    1996-05-01

    This long-term surveillance plan (LTSP) describes the U.S. Department of Energy's (DOE) long-term care program for the Uranium Mill Tailings Remedial Action (UMTRA) Project Gunnison disposal site in Gunnison County, Colorado. The U.S. Nuclear Regulatory Commission (NRC) has developed regulations for the issuance of a general license for the custody and long-term care of UMTRA Project disposal sites in 10 CFR Part 40. The purpose of this general license is to ensure that the UMTRA Project disposal sites will be cared for in a manner that protects the public health and safety and the environment. For each disposal site to be licensed, the NRC requires the DOE to submit a site-specific LTSP. The DOE prepared this LTSP to meet this requirement for the Gunnison disposal site. The general license becomes effective when the NRC concurs with the DOE's determination of completion of remedial action for the Gunnison site and the NRC formally accepts this LTSP. This LTSP describes the long-term surveillance program the DOE will implement to ensure that the Gunnison disposal site performs as designed. The program is based on two distinct activities: (1) site inspections to identify threats to disposal cell integrity, and (2) ground water monitoring to demonstrate disposal cell performance. The LTSP is based on the UMTRA Project long-term surveillance program guidance and meets the requirements of 10 CFR section 40.27(b) and 40 CFR section 192.03

  9. Experience from developed and licensing an underground repository for low and intermediate level radioactive wastes

    International Nuclear Information System (INIS)

    Ebel, K.; Richter, D.

    1988-01-01

    In the German Democratic Republic an abandoned salt mine was selected and reconstructed to serve as a central repository for low and intermediate level wastes from nuclear power plants and radioisotope production and application from all over the country. The decision to establish such a repository was based on safety and technical-economic studies performed in the 1960s. The repository is owned by the main waste producer, the nuclear plant utility. It was designed, constructed and commissioned during 1972-1978. The licensing steps included a site licence (1972), a construction licence (1974), a comissioning licence and a continuous operation licence (1979). The paper reviews the overall choice of the disposal option, the responsibilities in radioactive waste management, the licensing and surveillance activities, the methods for transport and disposal, and the waste acceptance criteria established for the repository. (author)

  10. Licensing of ANSTO's Replacement Research Reactor

    International Nuclear Information System (INIS)

    Summerfield, M.W.; Garea, V.

    2003-01-01

    This paper presents a general description of the licensing of the 20 MW Pool-type Replacement Research Reactor (RRR) currently being built by the Australian Nuclear Science and Technology Organisation (ANSTO) at their Lucas Heights site. The following aspects will be addressed: 1) The influence of ARPANSA's (the Australian regulator) Regulatory Assessment Principles and Design Criteria on the design of the RRR. 2) The Site Licence Application, including the EIS and the supporting siting documentation. 3) The Construction Licence Application, including the PSAR and associated documentation. 4) The review process, including the IAEA Peer Review and the Public Submissions as well as ARPANSA's own review. 5) The interface between ANSTO, INVAP and ARPANSA in relation to the ongoing compliance with ARPANS Regulation 51 and 54. 6) The future Operating Licence Application, including the draft FSAR and associated documentation. These aspects are all addressed from the point of view of the licensee ANSTO and the RRR Project. Particular emphasis will be given to the way in which the licensing process is integrated into the overall project program and how the licensing and regulatory regime within Australia influenced the design of the RRR. In particular, the safety design features that have been incorporated as a result of the specific requirements of ANSTO and the Australian regulator will be briefly described. The paper will close with a description of how the RRR meets, and in many aspects exceeds the requirements of ANSTO and the Australian regulator. (author)

  11. UK safety and standards for radioactive waste management and decommissioning on nuclear licensed sites

    International Nuclear Information System (INIS)

    Mason, D.J.

    2001-01-01

    This paper discusses the regulation of radioactive waste and decommissioning in the United Kingdom and identifies the factors considered by HM Nuclear Installations Inspectorate in examining the adequacy arrangements for their management on nuclear licensed sites. The principal requirements are for decommissioning to be undertaken as soon as reasonably practicable and that radioactive wastes should be minimised, disposed of or contained and controlled by storage in a passively safe form. However, these requirements have to be considered in the context of major organisational changes in the UK nuclear industry and the non-availability of disposal routes for some decommissioning wastes. The legislative framework used to regulate decommissioning of nuclear facilities in the UK is described. Reference is made to radioactive waste and decommissioning strategies, quinquennial reviews criteria for delicensing and the forthcoming Environmental Impact Assessment Regulations. (author)

  12. Hanford Site Development Plan

    International Nuclear Information System (INIS)

    Hathaway, H.B.; Daly, K.S.; Rinne, C.A.; Seiler, S.W.

    1992-05-01

    The Hanford Site Development Plan (HSDP) provides an overview of land use, infrastructure, and facility requirements to support US Department of Energy (DOE) programs at the Hanford Site. The HSDP's primary purpose is to inform senior managers and interested parties of development activities and issues that require a commitment of resources to support the Hanford Site. The HSDP provides a land use plan for the Hanford Site and presents a picture of what is currently known and anticipated in accordance with DOE Order 4320.1B. Site Development Planning. The HSDP wig be updated annually as future decisions further shape the mission and overall site development process. Further details about Hanford Site development are defined in individual area development plans

  13. The dual role of local sites in assisting firms with developing technological capabilities: Evidence from China

    DEFF Research Database (Denmark)

    Wang, Yuandi; Zhou, Zhao

    2013-01-01

    .g., knowledge, human capital) and the role of motivating multinational companies (MNCs) to upgrade their local operations in developing countries so as to perform more innovation activities. Few articles are presented that examine the role of local sites in the learning and technological-capability building......, and the collaborations with local industrial community firms positively influence the relationship between firms' international inward technology licensing and technological capabilities. (C) 2012 Elsevier Ltd. All rights reserved....

  14. SSM's licensing review of a spent nuclear fuel repository in Sweden

    International Nuclear Information System (INIS)

    Dverstorpand, Bjoern; Stroemberg, Bo

    2014-01-01

    On 16 March 2011 the Swedish Nuclear Fuel and Waste Management Co. (SKB) submitted license applications for a general license to construct, possess and operate a KBS-3 type spent nuclear fuel repository at the Forsmark site, in Oesthammar municipality, and an encapsulation plant in Oskarshamn municipality. The KBS-3 method, which has been developed by SKB over a period of more than 30 years, entails disposing of the spent fuel in copper canisters, surrounded by a swelling bentonite clay, at about 500 m depth in crystalline basement rock. SKB's applications are being evaluated in parallel by the Swedish Radiation Safety Authority (SSM) according to the Act on Nuclear Activities and by the Land and Environmental Court according to the Environmental Code. During the review SSM will act as an expert review body to the Land and Environmental Court in the areas of radiation protection, safety and security/non-proliferation. Both SSM and the court will produce a statement with a recommendation regarding a licensing decision and licensing conditions to the government. The government will make the final decision after consulting the municipalities concerned by SKB's facilities (municipal veto applies). The current licensing decision is just one of several licensing decisions that will be required for the repository. However it is arguably the most important one, because it is the last licensing stage with a broad societal involvement including an environmental impact assessment (EIA) process, national consultations and municipal veto for the concerned municipalities. The licensing steps to follow, should SKB be granted a license by the government, only require approval by SSM. These steps include application for start of actual construction work, test operation and routine operation. (authors)

  15. Sellafield - a nuclear licensed site

    International Nuclear Information System (INIS)

    Bloom, Phillipa.

    1987-01-01

    The report is based on the experience gained when visiting the Exhibition Centre at the BNFL Sellafield site and joining the hour-long coach trip round the site. The sights are recorded and a description given of the processes undertaken at Sellafield to reprocess the Magnox fuel and store the spent fuel from AGR reactors. The purpose of the main plant building, and the passage of the spent fuel through the various processes is described. Criticism is made of the safety record at Sellafield and a full and open debate on nuclear power is called for. (UK)

  16. Streamlining the license renewal review process

    International Nuclear Information System (INIS)

    Dozier, J.; Lee, S.; Kuo, P.T.

    2001-01-01

    The staff of the NRC has been developing three regulatory guidance documents for license renewal: the Generic Aging Lessons Learned (GALL) report, Standard Review Plan for License Renewal (SRP-LR), and Regulatory Guide (RG) for Standard Format and Content for Applications to Renew Nuclear Power Plant Operating Licenses. These documents are designed to streamline the license renewal review process by providing clear guidance for license renewal applicants and the NRC staff in preparing and reviewing license renewal applications. The GALL report systematically catalogs aging effects on structures and components; identifies the relevant existing plant programs; and evaluates the existing programs against the attributes considered necessary for an aging management program to be acceptable for license renewal. The GALL report also provides guidance for the augmentation of existing plant programs for license renewal. The revised SRP-LR allows an applicant to reference the GALL report to preclude further NRC staff evaluation if the plant's existing programs meet the criteria described in the GALL report. During the review process, the NRC staff will focus primarily on existing programs that should be augmented or new programs developed specifically for license renewal. The Regulatory Guide is expected to endorse the Nuclear Energy Institute (NEI) guideline, NEI 95-10, Revision 2, entitled 'Industry Guideline for Implementing the Requirements of 10 CFR Part 54 - The License Renewal Rule', which provides guidance for preparing a license renewal application. This paper will provide an introduction to the GALL report, SRP-LR, Regulatory Guide, and NEI 95-10 to show how these documents are interrelated and how they will be used to streamline the license renewal review process. This topic will be of interest to domestic power utilities considering license renewal and international ICONE participants seeking state-of-the-art information about license renewal in the United States

  17. Early Site Permit Demonstration Program: Recommendations for communication activities and public participation in the Early Site Permit Demonstration Program

    Energy Technology Data Exchange (ETDEWEB)

    1993-01-27

    On October 24, 1992, President Bush signed into law the National Energy Policy Act of 1992. The bill is a sweeping, comprehensive overhaul of the Nation`s energy laws, the first in more than a decade. Among other provisions, the National Energy Policy Act reforms the licensing process for new nuclear power plants by adopting a new approach developed by the US Nuclear Regulatory Commission (NRC) in 1989, and upheld in court in 1992. The NRC 10 CFR Part 52 rule is a three-step process that guarantees public participation at each step. The steps are: early site permit approval; standard design certifications; and, combined construction/operating licenses for nuclear power reactors. Licensing reform increases an organization`s ability to respond to future baseload electricity generation needs with less financial risk for ratepayers and the organization. Costly delays can be avoided because design, safety and siting issues will be resolved before a company starts to build a plant. Specifically, early site permit approval allows for site suitability and acceptability issues to be addressed prior to an organization`s commitment to build a plant. Responsibility for site-specific activities, including communications and public participation, rests with those organizations selected to try out early site approval. This plan has been prepared to assist those companies (referred to as sponsoring organizations) in planning their communications and public involvement programs. It provides research findings, information and recommendations to be used by organizations as a resource and starting point in developing their own plans.

  18. The USNCR license renewal process

    International Nuclear Information System (INIS)

    Kuo, Pao-Tsin

    2002-01-01

    The US Congress promulgated a law in 1954, entitled 'Atomic Energy Act'. This Act states that operating licenses for commercial nuclear power plants are limited to a fixed term of 40 years, but they may be renewed for a period not to exceed 20 years. The terms were established mainly for economic considerations, not based on technical limitations. The U.S. Nuclear Regulatory Commission (USNRC) published the license renewal rule, Title 10 of the Code of Federal Regulations, Part 54 (10 CFR Part 54), in December, 1991. The rule has since been amended in May, 1995. The underlying principle of the rule is that the regulatory process is adequate for ensuring safety of operating plants. The regulatory process includes NRC's issuance of Orders, Bulletins, Generic Letters, and Information Notices, as well as a number of special inspections in addition to the continuous oversight and routine inspection activities performed by on-site inspectors. Because of this comprehensive regulatory process, compilation of the current license basis or re-verification of the current licensing basis is not considered necessary for a license renewal review. The USNRC also determined on the basis of the findings of its research programs that active structures and components are well maintained by the existing programs. Therefore, the focus of the license renewal review is on passive, long-lived structures and components and on time-limited ageing analyses. The time-limited ageing analyses are for those structures and components which were originally designed to a 40 year service life

  19. Establishing a safety and licensing basis for generation IV advanced reactors. License by test

    International Nuclear Information System (INIS)

    Kadak, Andrew C.

    2001-01-01

    The license by test approach to licensing is a novel method of licensing reactors. It provides an opportunity to deal with innovative non-water reactors in a direct way on a time scale that could permit early certification based on tests of a demonstration reactor. The uncertainties in the design and significant contributors to risk would be identified in the PRA during the design. Deterministic analysis computer codes could be tested on a real reactor. Scaling effects and associated uncertainties would be minimized. License by test is an approach that has sufficient merit to be developed and tested

  20. New nuclear plant design and licensing process

    International Nuclear Information System (INIS)

    Luangdilok, W.

    1996-01-01

    This paper describes latest developments in the nuclear power reactor technology with emphasis on three areas: (1) the US technology of advanced passive light water reactors (AP600 and S BWR), (2) regulatory processes that certify their safety, and (3) current engineering concerns. The goal is to provide and insight of how the government's regulatory agency guarantees public safety by looking into how new passive safety features were designed and tested by vendors and how they were re-evaluated and retested by the US NRC. The paper then discusses the US 1989 nuclear licensing reform (10 CFR Part 52) whose objectives are to promote the standardization of nuclear power plants and provide for the early and definitive resolution of site and design issues before plants are built. The new licensing process avoids the unpredictability nd escalated construction cost under the old licensing process. Finally, the paper summarizes engineering concerns found in current light water reactors that may not go away in the new design. The concerns are related the material and water chemistry technology in dealing with corrosion problems in water-cooled nuclear reactor systems (PWRs and BWRs). These engineering concerns include core shroud cracking (BWRs), jet pump hold-down beam cracking (BWRs), steam generator tube stress corrosion cracking (PWR)

  1. 2013 Annual Site Inspection and Monitoring Report for Uranium Mill Tailings Radiation Control Act Title I Disposal Sites

    Energy Technology Data Exchange (ETDEWEB)

    None, None

    2014-03-01

    This report, in fulfillment of a license requirement, presents the results of long-term surveillance and maintenance activities conducted by the U.S. Department of Energy (DOE) Office of Legacy Management (LM) in 2013 at 19 uranium mill tailings disposal sites established under Title I of the Uranium Mill Tailings Radiation Control Act (UMTRCA) of 1978.1 These activities verified that the UMTRCA Title I disposal sites remain in compliance with license requirements. DOE operates 18 UMTRCA Title I sites under a general license granted by the U.S. Nuclear Regulatory Commission (NRC) in accordance with Title 10 Code of Federal Regulations Part 40.27 (10 CFR 40.27). As required under the general license, a long-term surveillance plan (LTSP) for each site was prepared by DOE and accepted by NRC. The Grand Junction, Colorado, Disposal Site, one of the 19 Title I sites, will not be included under the general license until the open, operating portion of the cell is closed. The open portion will be closed either when it is filled or in 2023. This site is inspected in accordance with an interim LTSP. Long-term surveillance and maintenance services for these disposal sites include inspecting and maintaining the sites; monitoring environmental media and institutional controls; conducting any necessary corrective actions; and performing administrative, records, stakeholder relations, and other regulatory stewardship functions. Annual site inspections and monitoring are conducted in accordance with site-specific LTSPs and procedures established by DOE to comply with license requirements. Each site inspection is performed to verify the integrity of visible features at the site; to identify changes or new conditions that may affect the long-term performance of the site; and to determine the need, if any, for maintenance, follow-up or contingency inspections, or corrective action in accordance with the LTSP. LTSPs and site compliance reports are available on the Internet at http://www.lm.doe.gov/.

  2. Review of a site developer's geo-scientific data and site-characterisation information to support repository certification

    International Nuclear Information System (INIS)

    Peake, R.T.; Byrum, C.; Ghose, S.

    2007-01-01

    The Waste Isolation Pilot Plant (WIPP) in New Mexico is a first-of-a-kind deep geologic facility for the disposal of transuranic (TRU) radioactive waste from weapons production in the United States. In 1993, Congress authorised the Environmental Protection Agency (EPA) to develop and implement WIPP-site-specific compliance criteria based on the general safety and environmental standards in EPA's high-level and transuranic radioactive waste regulations [1]. EPA published its site-specific regulations [2] in 1996 and certified WIPP to open in 1998. This regulatory framework set the stage for balancing diverse input data, provided a structure for document development, provided a mechanism for interaction between EPA and the Department of Energy (DOE), and provided a guide to support our review of WIPP's safety assessment. EPA's involvement continues during WIPP's operational phase. Confidence in repository site geo-scientific data enhances the regulator's ability to make a credible and defensible certification (licensing) decision and to communicate the basis for the decision to the public. Lack of confidence in the data can lead to lack of credibility about site suitability. Clear regulations and specific quality standards can enhance the quality of site-characterisation documentation and assist the regulator in its approval process of the site. In EPA's regulations, documentation is required on numerous issues, and EPA supplemented this with guidance. High-quality documentation is essential, especially for EPA. In the certification process for WIPP, the documentation in the record and our written interpretation of the record was what was used in legal proceedings that followed EPA's certification of WIPP. EPA and DOE had frequent and generally open communication. During formal regulatory proceedings, all communication had to be documented. Some decisions were made at the staff level, but major decisions were typically addressed and resolved through correspondence

  3. License Application Design Selection Report, REV 01. August 1999

    International Nuclear Information System (INIS)

    Hastings, C.R.

    1999-01-01

    In December 1998, the U.S. Department of Energy (DOE) published the ''Viability Assessment of a Repository at Yucca Mountain'' (DOE 1998b). The Viability Assessment described a preliminary design of a potential repository at Yucca Mountain, Nevada, for disposal of spent nuclear fuel and high-level radioactive waste, and assessed the probable behavior of that repository design in the Yucca Mountain geologic setting. The report concluded that 'Yucca Mountain remains a promising site for a geologic repository and that work should proceed to support a decision in 2001 on whether to recommend the site to the President for development as a repository'. It also concluded that 'uncertainties remain about key natural processes, the preliminary design, and how the site and design would interact'. Recognizing that the design that was evaluated will be refined before a license application could be submitted, the Viability Aassesment notes that 'DOE is evaluating several design options and alternatives that could reduce existing uncertainty and improve the performance of the repository system'. During the preparation of the Viability Assessment, DOE asked the contractor for the Civilian Radioactive Waste Management Program to study alternative design concepts for a potential geologic repository for high-level radioactive waste at Yucca Mountain. The License Application Design Selection (LADS) project was initiated to conduct that study. The goal of the project was to develop and evaluate a diverse range of conceptual repository designs that work well in concert with the Yucca Mountain site and to recommend an initial design concept for the possible Site Recommendation and License Apllication. This report presents the results of the LADS project. The design process consisted of two phases. In Phase I, a series of basic design concepts (design alternatives) and components (design features) were analyzed for their potential value as elements of a repository design. In Phase II

  4. Research and development tasks of the basalt waste isolation program, and their relationship to the licensing process

    International Nuclear Information System (INIS)

    Kunkel, W.P.

    1978-06-01

    This document presents a preliminary licensing program and outlines the research and development strategy by which a license will be obtained for the repository. It addresses the base data covering the major areas of investigation and technology which will provide input to the licensing process. Basically, each facet of the program, as described in the plan, will be used as part of the documentation required for the Preliminary and Final Safety Analysis Report (PSAR and FSAR), as well as the Environmental Report

  5. Radiation Protection training WEB site to hold pedagogical material for developing courses a distance way

    International Nuclear Information System (INIS)

    Marco, M.; Rodriguez, M.; Hernando, E.; Falcon, S.; Rodriguez, M.; Villarroel, R.

    2003-01-01

    Radiation Protection Training (RPT) System in Spain are is well defined in the local local regulations related to radioactive facilities licensing and radiation protection. A system of personnel licenses is established considering two levels of required radiation protection training-supervisor and operator according to responsibilities assigned during the operation of the radioactive facilities. This paper present the major advances already done in the educational web site maintained on the CIEMAT server and accessible through the CSN web. The project includes training material for sixteen applied courses and the design of a educational web site to hold pedagogical material for developing distant learning courses. The main objective of this project is to provide training materials for course organisers, trainers and for professional participants and to promote the exchange of expertise between workers involved in all activities using radiation sources. The project also aims to provide necessary mechanism for standardisation of the radiation protection knowledge made available to the exposed workers, including theoretical and practical training. The developed training material included in the project will cover all uses of radioactive sources including medical diagnosis. The web site is being developed of provide educational material on a modular design and in Spanish. The paper presents the initial results of this useful tool for practitioners. Courses are based on core modules with basic and specific modules involving different targets groups, and the contents can be easily adapted for other target groups. For each one of the modules should be included in the web site: objectives, syllabus, lessons and practical sessions, demo and lab exercises, etc. The project includes training tools for sixteen courses based in the standard syllabus content in the Spanish legal framework. In the next future complete materials for trainers will be available to case courses

  6. Generic environmental impact statement for license renewal of nuclear plants. Final report

    International Nuclear Information System (INIS)

    1996-05-01

    This GEIS examines the possible environmental impacts that could occur as a result of renewing the licenses of individual nuclear power plants under 10 CFR 54. To the extent possible, it establishes the bounds and significance of these potential impacts. The analysis encompasses all operating light-water reactors. For each type of environmental impact, the GEIS attempts to establish generic findings covering as many plants as possible. While plant and site-specific information is used in developing the generic findings, the NRC does not intend for the GEIS to be a compilation of individual plant environmental impacts statements. This document has three principal objectives: (1) to provide an understanding of the types and severity of environmental impacts that may occur as a result of license renewal, (2) to identify and assess those impacts that are expected to be generic to license renewal, and (3) to support rulemaking (10 CFR 51) to define the number and scope of issues that need to be addressed by the applicants in plant-by-plant license renewal proceedings

  7. Early Site Permit Demonstration Program: Regulatory criteria evaluation report

    Energy Technology Data Exchange (ETDEWEB)

    1993-03-01

    The primary objective of the ESPDP is to demonstrate successfully the use of 10CFR52 to obtain ESPs for one or more US sites for one (or more) ALWR nuclear power plants. It is anticipated that preparation of the ESP application and interaction with NRC during the application review process will result not only in an ESP for the applicant(s) but also in the development of criteria and definition of processes, setting the precedent that facilitates ESPs for subsequent ESP applications. Because siting regulatory processes and acceptance criteria are contained in over 100 separate documents, comprehensive licensing and technical reviews were performed to establish whether the requirements and documentation are self-consistent, whether the acceptance criteria are sufficiently well-defined and clear, and whether the licensing process leading to the issuance of an ESP is unambiguously specified. The results of the technical and licensing evaluations are presented in this report. The purpose, background, and organization of the ESPDP is delineated in Section 1. Section 11 contains flowcharts defining siting application requirements, environmental report requirements, and emergency planning/preparedness requirements for ALWRS. The licensing and technical review results are presented in Section III.

  8. Early Site Permit Demonstration Program: Regulatory criteria evaluation report

    International Nuclear Information System (INIS)

    1993-03-01

    The primary objective of the ESPDP is to demonstrate successfully the use of 10CFR52 to obtain ESPs for one or more US sites for one (or more) ALWR nuclear power plants. It is anticipated that preparation of the ESP application and interaction with NRC during the application review process will result not only in an ESP for the applicant(s) but also in the development of criteria and definition of processes, setting the precedent that facilitates ESPs for subsequent ESP applications. Because siting regulatory processes and acceptance criteria are contained in over 100 separate documents, comprehensive licensing and technical reviews were performed to establish whether the requirements and documentation are self-consistent, whether the acceptance criteria are sufficiently well-defined and clear, and whether the licensing process leading to the issuance of an ESP is unambiguously specified. The results of the technical and licensing evaluations are presented in this report. The purpose, background, and organization of the ESPDP is delineated in Section 1. Section 11 contains flowcharts defining siting application requirements, environmental report requirements, and emergency planning/preparedness requirements for ALWRS. The licensing and technical review results are presented in Section III

  9. Licensing issues

    International Nuclear Information System (INIS)

    Roberts, J.P.; Desell, L.J.; Birch, M.L.; Berkowitz, L.; Bader, J.F.

    1992-01-01

    To provide guidance for the Department of Energy's (DOE) Civilian Radioactive Waste Management Program, the Nuclear Regulatory Commission (NRC) has issued a draft regulatory guide on the Format and Content for the License Application for the High-Level Waste Repository (FCRG). To facilitate the development of the FCRG, NRC suggested that DOE use the draft guide as the basis for preparing an annotated outline for a license application. DOE is doing so using an iterative process called the Annotated Outline Initiative. DOE;s use of the Initiative will assist in achieving the desired incorporation of actual experience in the FCRG, contribute to the development of shared interpretation and understanding of NRC regulations, and provide other important programmatic benefits described in this paper

  10. 10 CFR 781.51 - Nonexclusive licenses.

    Science.gov (United States)

    2010-01-01

    ... corporate structure of which licensee is a part, if any. However, the license shall not be assignable or... license upon the policies of the United States Government; (3) The effect of the license upon domestic and... extent of U.S. Government contribution to the development of the invention; (iv) The degree of...

  11. The role the safety analysis report and other documents in the licensing procedure in the Federal Republic of Germany

    International Nuclear Information System (INIS)

    Albrecht, E.; Ballhaus, S.

    1975-01-01

    Legal requirements for the licensing procedure, requirements for and preparation of licensing documents, authorities and experts participating in the licensing procedure, course of the atomic licensing procedure e.g. application for construction and operation, public hearing, site and concept license, partial licenses. (HP) [de

  12. Development, assessment, licensing, and application of RELAP5YA at Yankee Atomic Electric Company

    International Nuclear Information System (INIS)

    Husain, A.

    1984-01-01

    Since 1975, Yankee Atomic Electric Company (YAEC) has been licensed to perform LOCA analyses (large and small breaks) for PWRs. The methods are based upon the WREM package, comprised of RELAP4-MOD 3, RELAP4-FLOOD, and TOODEE-2EM. Significant efforts were expended to compare WREM models against Appendix K criteria, and to incorporate changes for compliance with the criteria and for improved representation of LOCA phenomena. /SUP 2,3,4/ This internalized capability has been used extensively for licensing the Yankee and Maine Yankee plants, and for timely resolution of LOCA issues which frequently arose. The value of this internalized analysis capability was well recognized by the Yankee management. In 1979, Yankee embarked upon another LOCA Methods Development Program. One objective was to remove extra conservatisms inherent in older codes to provide additional operational flexibility for our plants. Also, we needed a code which could be used in a production mode to provide realistic response for off-normal conditions to be used in operator training and emergency guideline assessment. This program resulted in the development of RELAP5YA. The development, assessment, licensing, and application of RELAP5YA at YAEC is briefly described in this paper

  13. Site characterization progress report, April 1, 1994--September 30, 1994: Yucca Mountain, Nevada. Volume 11

    International Nuclear Information System (INIS)

    1995-03-01

    The Civil Radioactive Waste Management Program was restructured to provide a new approach to the evaluation of the site for development as a repository and to its licensing. Funding was increased for FY 95, with most of the increase going to the Yucca Mountain site characterization project. During this period, significant progress was made in surface-based testing, advanced conceptual design, performance assessment, planning, licensing support system development activities, and construction of the Exploratory Studies Facility. The report is divided into the following sections: introduction, programmatic activities, site programs, repository design, waste package, performance assessment, and exploratory studies facility design/construction

  14. Long-term surveillance plan for the Cheney disposal site near Grand Junction, Colorado

    International Nuclear Information System (INIS)

    1997-04-01

    This long-term surveillance plan (LTSP) describes the U.S. Department of Energy's (DOE) long-term care program for the Uranium Mill Tailings Remedial Action (UMTRA) Project Cheney disposal site. The site is in Mesa County near Grand Junction, Colorado. The U.S. Nuclear Regulatory Commission (NRC) has developed regulations for the issuance of a general license for the custody and long-term care of UMTRA Project disposal sites in 10 CFR Part 40. The purpose of this general license is to ensure that the UMTRA Project disposal sites are cared for in a manner that protects public health and safety and the environment. Before each disposal site may be licensed, the NRC requires the DOE to submit a site-specific LTSP. The DOE prepared this LTSP to meet this requirement for the Cheney disposal site. The general license becomes effective when the NRC concurs with the DOE's determination that remedial action is complete and the NRC formally accepts this plan. This document describes the long-term surveillance program the DOE will implement to ensure that the Cheney disposal site performs as designed. The program is based on site inspections to identify potential threats to disposal cell integrity. The LTSP is based on the UMTRA Project long-term surveillance program guidance and meets the requirements of 10 CFR section 40.27(b) and 40 CFR section 192.03

  15. Licensing an assured isolation facility for low-level radioactive waste. Volume 1: Licensing strategy and issues

    International Nuclear Information System (INIS)

    Silverman, D.J.; Bauser, M.A.; Baird, R.D.

    1998-07-01

    This report provides a detailed set of proposed criteria and guidance for the preparation of a license application for an assured isolation facility (AIF). The report is intended to provide a detailed planning basis upon which a prospective applicant may begin pre-licensing discussions with the Nuclear Regulatory Commission and initiate development of a license application. The report may also be useful to the NRC or to state regulatory agencies that may be asked to review such an application. Volume 1 of this report provides background information, and describes the licensing approach and methodology. Volume 2 identifies specific information that is recommended for inclusion in a license application

  16. U.S. licensing process and ABWR certification

    International Nuclear Information System (INIS)

    Quirk, J.F.; Williams, W.A.

    1996-01-01

    Part 50 of Title 10 of the Code of Federal Regulation (CFR) establishes a two-step licensing process by which the U.S. Nuclear Regulatory Committee (NRC) authorizes nuclear reactor plant construction through issuance of a construction permit and authorizes operation by issuance of an operating license. At each stage, the NRC Staff conducts technical reviews and there is potential for public hearings. In 1989, the NRC issued a new, simplified licensing process: Part 52. The purpose of the Part 52 licensing process is to provide a regulatory framework that brings about earlier resolution of licensing issues. Because issues are not resolved early in the Part 50 licensing process, approval of an operating license is not assured until after a significant investment has been made in the plant. Part 52 increases the stability and certainty of the licensing process by providing for the early resolution of safety and environmental issues. The Part 52 licensing process features (1) early site permits, (2) design certification, and (3) combined construction permit and operating licenses. As part of the U.S. Advanced Light Water Reactor (ALWR) Program to revitalize the nuclear option through the integration of government/utility/industry efforts, GE undertook the role of applying for certification for its latest product line, the Advanced Boiling Water Reactor (ABWR), under the U.S. ABWR certification program. The ABWR design is an essentially complete plant. Initial application for design certification was in 1987 under Part 50. GE reapplied in late 1991 under the newly promulgated Part 52. Following seven years of intensive interactions with the NRC and ACRS, GE was awarded the first Final Design Approval (FDA) under Part 52. The Commission initiated rulemaking by publishing the proposed ABWR Certification Rule in the Federal Register in early 1995. Certification is anticipated mid-1996. (J.P.N.)

  17. NPP License Renewal and Aging Management: Revised Guidance

    International Nuclear Information System (INIS)

    Hull, A.B.; Hiser, A.L.; Lindo-Talin, S.E.

    2012-01-01

    Based on the Atomic Energy Act, the NRC issues licenses for commercial power reactors to operate for up to 40 years and allows these licenses to be renewed for up to another 20 years. NRC has approved license renewal (LR) for well over 50% of U.S. located reactors originally licensed to operate for 40 years. Of these 104 reactors (69 PWRs, 35 BWRs), the NRC has issued renewed licenses for 71 units and is currently reviewing applications for another 15 units. As of May 1, 2012, ten plants at nine sites had entered their 41st year of operation and thus are in their first period of extended operation (PEO). Five more plants will enter the PEO by the end of 2012. One foundation of the license renewal process has been license renewal guidance documents (LRGDs). The U.S. Nuclear Regulatory Commission (NRC) revised key guidance documents used for nuclear power LR in 2010 and 2011. These include NUREG-1800, 'Standard Review Plan for Review of License Renewal Applications,' revision 2 (SRP-LR), and NUREG-1801, 'Generic Aging Lessons Learned (GALL) Report,' revision 2 (GALL Report). The guidance documents were updated to reflect lessons learned and operating experience gained since the guidance documents were last issued in 2005. The reactor LRGDs referenced in this poster can all be accessed at http://www.nrc.gov/reactors/operating/licensing/renewal/guidance.html (author)

  18. The partnership approach to siting and developing radioactive waste management facilities

    International Nuclear Information System (INIS)

    2010-03-01

    History shows that the search for sites for radioactive waste management facilities has been marred by conflicts and delays. Affected communities have often objected that their concerns and interests were not addressed. In response, institutions have progressively turned away from the traditional 'decide, announce and defend' model, and are learning to 'engage, interact and co-operate'. This shift has fostered the emergence of partnerships between the proponent of the facility and the potential host community. Working in partnership with potential host communities enables pertinent issues and concerns to be raised and addressed, and creates an opportunity for developing a relationship of mutual understanding and mutual learning, as well as for developing solutions that will add value to the host community and region. Key elements of the partnership approach are being incorporated into waste management strategies, leading increasingly to positive outcomes. National radioactive waste management programmes are in various phases of siting facilities and rely on different technical approaches for the various categories of waste. In all cases, it is necessary for institutional actors and the potential or actual host community to build a meaningful, workable relationship. Partnership approaches are effective in achieving a desirable combination of licensable site and management concept while meeting the sometimes competing requirements of fair representation and competent participation. Partnership arrangements facilitate reaching agreement on measures for local control, financial support and future development

  19. License - FANTOM5 | LSDB Archive [Life Science Database Archive metadata

    Lifescience Database Archive (English)

    Full Text Available switchLanguage; BLAST Search Image Search Home About Archive Update History Data List Contact us FANTOM....0 International . If you use data from this database, please be sure attribute this database as follows: FANTOM...se Database Description Download License Update History of This Database Site Policy | Contact Us License - FANTOM5 | LSDB Archive ...

  20. ESPSD, Nuclear Power Plant Siting Database

    International Nuclear Information System (INIS)

    Slezak, S.

    2001-01-01

    1 - Description of program or function: This database is a repository of comprehensive licensing and technical reviews of siting regulatory processes and acceptance criteria for advanced light water reactor (ALWR) nuclear power plants. The program is designed to be used by applicants for an early site permit or combined construction permit/operating license (10CFRR522), Sub-parts A and C) as input for the development of the application. The database is a complete, menu-driven, self-contained package that can search and sort the supplied data by topic, keyword, or other input. The software is designed for operation on IBM compatible computers with DOS. 2 - Method of solution: The database is an R:BASE Runtime program with all the necessary database files included

  1. Site development

    International Nuclear Information System (INIS)

    Gaynor, R.K.

    1989-01-01

    Development of a low-level radioactive waste land disposal facility is little different than any industrial development of similar scope. Consideration must be made for normal business and operations management, security, facility maintenance, traffic control and necessary amenities for personnel. The item specific to the low-level waste site is the handling of radioactive waste materials and the regulatory and environmental protection procedures that must be planned for and accomodated in the site design and development. Each of these elements and the facility as a whole must be designed to be compatible with local land use plans, available transportation and support services, and the social and economic goals of the local community. Plans should also be made for quality control and orderly construction. This chapter deals with those aspects of the facility, its design and construction which are integral parts to the overall performance of the site

  2. The regulatory review of construction license application and the supporting safety case

    International Nuclear Information System (INIS)

    Heinonen, Jussi

    2014-01-01

    Finland is one of the foremost countries in the world in developing the disposal of spent fuel. The construction license application for the Olkiluoto spent fuel disposal facility was submitted to the authorities at the end of 2012 and the facility is expected to start operation around 2020. This has been a long-term project with over 30 years of parallel development of the repository project and the regulatory approach to spent fuel management. In 1983 the government made a strategic decision on the objectives and target time schedule for the research, development and technical planning of nuclear waste management. While an export and international disposal solution was still the preferred option, this decision required the licensees without this possibility to prepare for disposal in Finland and it also gave the time line for the milestones on the way to an operating disposal facility by 2020. The licensing procedure for a disposal facility has several steps that are similar to all nuclear facilities in Finland and are defined in Nuclear Energy Act and Decree (1987, 1988). These licensing steps are: - Decision-in-principle is required for a nuclear facility having considerable general significance. This is essentially a political decision: the government decides if the construction project is in line with the overall good of society. The decision can be applied for one or more sites, the host municipality has a veto right and the parliament has the choice of ratifying or not ratifying the decision. - Construction license is granted by the government and authorises the construction of the disposal facility. The actual construction is regulated by STUK and includes several review and approval steps, hold points and viewpoints. - Operational license is granted by the government and authorises the operation of the facility for a certain period. The operational license is needed before nuclear waste can be disposed. The first step in the licensing process was reached

  3. Nuclear facilities licensing

    International Nuclear Information System (INIS)

    Carvalho, A.J.M. de.

    1978-01-01

    The need for the adoption of a legal and normative system, defining objectives, pescriptions and the process of nuclear licensing and building of nuclear power plants in Brazil is enphasized. General rules for the development of this system are presented. The Brazilian rules on the matter are discussed. A general view of the German legal system for nuclear power plant licensing and the IAEA recommendations on the subject are finally presented. (A.L.S.L.) [pt

  4. License renewal - an idea whose time has come. Hatch nuclear plant license renewal program: an actual example of application of the license renewal rule to the Intake Structure

    International Nuclear Information System (INIS)

    Chandiwala, F.; Evans, W.P.

    1999-01-01

    After the NRC issued a revised license renewal rule in May 1995, the nuclear industry focussed on developing generic industry for implementing the rule and testing the guidance through various demonstration programs and work products in conjunction with the NRC. In addition, plant-specific programs also proceeded forward. These activities show that implementation issues continue to exist. Since the issuance of the rule, the NRC has issued a draft standard review plan for license renewal (SRP-LR), working draft, September 1997. Southern Nuclear Operating Company (SNC) has begun development work on a license renewal application for Plant Hatch Units 1 and 2. Plant Hatch Units 1 and 2 are BWR 4, Mark I plants whose operating licenses expire in 2014 and 2018, respectively. The Plant Hatch initiative also involves teaming with other boiling water reactors (BWRs) to develop the license renewal technology within the BWR fleet, and to support Plant Hatch by providing an oversight role for the application process. The teaming effort involved two other utilities, each being assigned to prepare a common report on a mechanical system or a structure. The common report could be presented to the NRC with modifications to suit the individual plants, thereby saving time and money, and hopefully resulting in quicker approval by the NRC. The desired license renewal process end result is a renewed license with up to a 20 year extension (10CFR 54.31(b)). (orig.)

  5. AP1000R licensing and deployment in the United States

    International Nuclear Information System (INIS)

    Jordan, R. P.; Russ, P. A.; Filiak, P. P.; Castiglione, L. L.

    2012-01-01

    In recent years, both domestic and foreign utilities have turned to the standardized Westinghouse AP1000 plant design in satisfying their near - and long-term - sustainable energy needs. As direct support to these actions, licensing the AP1000 design has played a significant role by providing one of the fundamental bases in clearing regulatory hurdles leading to the start of new plant construction. Within the U.S. alone, Westinghouse AP1000 licensing activities have reached unprecedented milestones with the approvals of both AP1000 Design Certification and Southern Company's combined construction permit and operating license (COL) application directly supporting the construction of two new nuclear plants in Georgia. Further COL application approvals are immediately pending for an additional two AP1000 plants in South Carolina. And, across the U.S. nuclear industry spectrum, there are 10 other COL applications under regulatory review representing some 16 new plants at 10 sites. In total, these actions represent the first wave of new plant licensing under the regulatory approval process since 1978. Fundamental to the Nuclear Regulatory Commission's AP1000 Design Certification is the formal recognition of the AP1000 passive safety design through regulatory acceptance rulemaking. Through recognition and deployment of the AP1000 Design Certification, the utility licensee / operator of this reactor design are now offered an opportunity to use a simplified 'one-step' combined license process, thereby managing substantial back-end construction schedule risk from regulatory and intervention delays. Application of this regulatory philosophy represents both acceptance and encouragement of standardized reactor designs like the AP1000. With the recent AP1000 Design Certification and utility COL acceptances, the fundamental licensing processes of this philosophy have successfully proven the attainment of significant milestones with the next stage licensing actions directed

  6. 76 FR 60941 - Policy Regarding Submittal of Amendments for Processing of Equivalent Feed at Licensed Uranium...

    Science.gov (United States)

    2011-09-30

    ... Processing of Equivalent Feed at Licensed Uranium Recovery Facilities AGENCY: Nuclear Regulatory Commission... State-licensed uranium recovery site, either conventional, heap leach, or in situ recovery. DATES... Regarding Submittal of Amendments for Processing of Equivalent Feed at Licensed Uranium Recovery Facilities...

  7. Licensing of ''grandfather's'' facilities: Ukrainian experience

    International Nuclear Information System (INIS)

    Mikolaitchouk, H.; Bogdan, L.; Steinberg, N.

    1995-01-01

    In the former USSR, unlike most countries, radioactive waste management activities including waste disposal needed no license. But after the USSR breakdown the Ukrainian Parliament -- Verkhovna Rada -- invoked the revised Law on Business activities. According to Article 4 of the Law, in order to treat or to dispose radioactive waste every enterprise has to get a special permission or license. In compliance with the Law, the Cabinet of Ministers by its Ordinance of January 13, 1993, authorized the Ukrainian State Committee for Nuclear and Radiation Safety (UkrSCNRS) to issue special permissions or licenses for waste treatment and disposal. And that requirement was valid not only for future activities but also for existing facilities in operation. Taking into account the undergoing legislative process, SCNRS began to develop its licensing process without waiting for the special nuclear laws to be passed. On the basis of the legislation already in effect, first of all the Law on Enterprises (full responsibility of enterprises for their activities) and Law on Business activities (requirement to have a license for special types of activities), the newly formed national regulatory body had to identify all the enterprises that needed to be licensed, to establish relevant procedures, to develop related regulatory documents, to implement these procedures and documents at operating enterprises, and for each case to make a decision concerning feasibility of issuing a license, period of validity and license conditions

  8. Regulatory systems-based licensing guidance documentation

    International Nuclear Information System (INIS)

    Delligatti, M.S.

    1991-01-01

    The US Nuclear Regulatory Commission (NRC) has developed a series of licensing guidance documents based on the regulatory requirements in Part 60 of Title 10 of the Code of Federal Regulations (10 CFR Part 60). This regulatory systems-based approach to licensing guidance documentation relies on the definition of the high-level waste repository in 10 CFR Part 60. A document which is important for the frame-work it gives to other programmatic licensing guidance is the Draft Regulatory Guide open-quotes Format and Content for the License Application for the High-Level Waste Repositoryclose quotes (FCRG). The FCRG describes a format and content acceptable to NRC for a high-level waste repository license application pursuant to the requirements of 10 CFR Part 60. Other licensing guidance documents will be compatible with the FCRG

  9. The HOR core conversion program development and licensing experiences

    International Nuclear Information System (INIS)

    Vries, J.W. de; Gibcus, H.P.M.; Leege, P.F.A. de

    1997-01-01

    This paper deals with the experiences in the development of a fuel conversion program for a 2 MW university type research reactor, the HOR. It gives an overview of the technical and administrative aspects concerning the fuel conversion program development since the eighties, including the safety review and licensing process. The overall final safety report was submitted in 1995, together with the environmental impact report, and a licence application was submitted accordingly. The licence permitting the conversion was issued in 1996, coming into force at the beginning of this year, although an appeal case is still pending. At the moment the necessary preparations for starting the actual conversion of the HOR are made. The general program characteristics are addressed. (author)

  10. Licensing process for future applications of advanced-design nuclear reactors

    International Nuclear Information System (INIS)

    Miller, C.L.

    1990-01-01

    The existing 10CFR50 two-step licensing process in the Code of Federal Regulations can continue to be a viable licensing vehicle for future applications, at least for the near future. The US Nuclear Regulatory Commission (NRC) Commissioners and staff, the public, and the utilities (along with supporting architect/engineers and nuclear steam supply system vendors) have a vast body of experience and knowledge of the existing part 50 licensing process. All these participants are familiar with their respective roles in this process, and history shows this process to be a workable licensing vehicle. Nevertheless, the use of 10CFR52 should be encouraged for future applications. This proposed new rule is intended to achieve the early resolution of licensing issues, to reduce the complexity and uncertainty of the licensing process, and enhance the safety and reliability of nuclear power plants. Part 52's overall purpose is to improve reactor safety and streamline the licensing process by encouraging the use of standard reactor designs and by allowing the early resolution of site environmental and reactor safety issues. The public should be afforded an earlier entry into the licensing process as a result of design certification rulemaking process and combined construction permit/operating license hearings

  11. Siting a low-level radioactive waste disposal facility in California

    International Nuclear Information System (INIS)

    Romano, S.A.; Gaynor, R.K.

    1991-01-01

    US Ecology is the State of California's designee to site, develop and operate a low-level radioactive waste disposal facility. In March 1988, a site in the Ward Valley of California's Mojave Desert was chosen for development. Strong local community support has been expressed for the site. US Ecology anticipates licensing and constructing a facility to receive waste by early 1991. This schedule places California well ahead of the siting milestones identified in Federal law. (author) 1 fig., 2 refs

  12. Nuclear Regulatory Commission staff development of the license application review plan for a high-level radioactive waste repository

    International Nuclear Information System (INIS)

    Johnson, R.L.; Holonich, J.J.; Lee, M.P.; Delligatti, M.S.

    1993-01-01

    The Nuclear Regulatory Commission staff has recently started a new initiative to develop the License Application Review Plan (LARP) which the staff will use in its reviews of the U.S. Department of Energy's (DOE's) license application (LA) for a geologic repository for the disposal of high-level radioactive waste (HLW). This paper describes the staff's approach for developing the LARP, the development schedule and current status, the organization and content of the LARP, and the staff's LA review strategy. Therefore, it gives a preview of the draft LARP which will be made available in late 1993. It also describes how the LARP will be used as guidance to the staff in conducting reviews of regulatory and technical issues important to the licensing of a geologic repository. Finally, the benefits to the NRC staff, DOE, and other parties are discussed

  13. 2013 Annual Site Inspection and Monitoring Report for Uranium Mill Tailings Radiation Control Act Title II Disposal Sites

    International Nuclear Information System (INIS)

    2013-01-01

    This report, in fulfillment of a license requirement, presents the results of long-term surveillance and maintenance activities conducted by the U.S. Department of Energy (DOE) Office of Legacy Management in 2013 at six uranium mill tailings disposal sites reclaimed under Title II of the Uranium Mill Tailings Radiation Control Act (UMTRCA) of 1978. These activities verified that the UMTRCA Title II disposal sites remain in compliance with license requirements. DOE manages six UMTRCA Title II disposal sites under a general license granted by the U.S. Nuclear Regulatory Commission (NRC) established at Title 10 Code of Federal Regulations Part 40.28. Reclamation and site transition activities continue at other sites, and DOE ultimately expects to manage approximately 27 Title II disposal sites. Long-term surveillance and maintenance activities and services for these disposal sites include inspecting and maintaining the sites; monitoring environmental media and institutional controls; conducting any necessary corrective action; and performing administrative, records, stakeholder services, and other regulatory functions. Annual site inspections and monitoring are conducted in accordance with site-specific long-term surveillance plans (LTSPs) and procedures established by DOE to comply with license requirements. Each site inspection is performed to verify the integrity of visible features at the site; to identify changes or new conditions that may affect the long-term performance of the site; and to determine the need, if any, for maintenance, follow-up inspections, or corrective action. LTSPs and site compliance reports are available online at http://www.lm.doe.gov

  14. 2013 Annual Site Inspection and Monitoring Report for Uranium Mill Tailings Radiation Control Act Title II Disposal Sites

    Energy Technology Data Exchange (ETDEWEB)

    None

    2013-11-01

    This report, in fulfillment of a license requirement, presents the results of long-term surveillance and maintenance activities conducted by the U.S. Department of Energy (DOE) Office of Legacy Management in 2013 at six uranium mill tailings disposal sites reclaimed under Title II of the Uranium Mill Tailings Radiation Control Act (UMTRCA) of 1978. These activities verified that the UMTRCA Title II disposal sites remain in compliance with license requirements. DOE manages six UMTRCA Title II disposal sites under a general license granted by the U.S. Nuclear Regulatory Commission (NRC) established at Title 10 Code of Federal Regulations Part 40.28. Reclamation and site transition activities continue at other sites, and DOE ultimately expects to manage approximately 27 Title II disposal sites. Long-term surveillance and maintenance activities and services for these disposal sites include inspecting and maintaining the sites; monitoring environmental media and institutional controls; conducting any necessary corrective action; and performing administrative, records, stakeholder services, and other regulatory functions. Annual site inspections and monitoring are conducted in accordance with site-specific long-term surveillance plans (LTSPs) and procedures established by DOE to comply with license requirements. Each site inspection is performed to verify the integrity of visible features at the site; to identify changes or new conditions that may affect the long-term performance of the site; and to determine the need, if any, for maintenance, follow-up inspections, or corrective action. LTSPs and site compliance reports are available online at http://www.lm.doe.gov

  15. Stability in licensing requirements: a technical perspective

    International Nuclear Information System (INIS)

    Szalay, R.A.

    1978-01-01

    The serious difficulties encountered in the licensing procedure for nuclear power plants in the United States have resulted in the elaboration of a Bill on the siting and licensing of nuclear installations for the purpose of reforming the present system. The author fears, however, that this Bill will not reduce the complexity of present regulations and will be unable to reach the object sought which is to reduce the length of the procedure; he analyses the technical and political reasons underlying this situation, and in particular the role of the staff of the Nuclear Regulatory Commission. (NEA) [fr

  16. Early Site Permit Demonstration Program: Regulatory criteria evaluation report

    International Nuclear Information System (INIS)

    1993-03-01

    The primary objective of the Early Site Plan Demonstration Program (ESPDP) is to demonstrate successfully the use of 10CFR52 to obtain ESPs for one or more US sites for one (or more) ALWR nuclear power plants. It is anticipated that preparation of the ESP application and interaction with NRC during the application review process will result not only in an ESP for the applicant(s) but also in the development of criteria and definition of processes, setting the precedent that facilitates ESPs for subsequent ESP applications. Because siting regulatory processes and acceptance criteria are contained in over 100 separate documents, comprehensive licensing and technical reviews were performed to establish whether the requirements and documentation are self-consistent, whether the acceptance criteria are sufficiently well-defined and clear, and whether the licensing process leading to the issuance of an ESP is unambiguously specified. This document provides appendices C and D of this report. Appendix C contains data from the licensing and technical reviews; Appendix D contains technology toolkit data sheets

  17. 76 FR 63330 - Policy Regarding Submittal of Amendments for Processing of Equivalent Feed at Licensed Uranium...

    Science.gov (United States)

    2011-10-12

    ... Processing of Equivalent Feed at Licensed Uranium Recovery Facilities AGENCY: Nuclear Regulatory Commission... NRC and Agreement State-licensed uranium recovery site. This action is necessary to correct several... read ``(see Page A2 of SECY-99-011, ``Draft Rulemaking Plan: Domestic Licensing of Uranium and Thorium...

  18. The Monticello license renewal project

    International Nuclear Information System (INIS)

    Clauss, J.M.; Harrison, D.L.; Pickens, T.A.

    1993-01-01

    Today, 111 nuclear power plants provide over 20 percent of the electrical energy generated in the United States. The operating license of the oldest operating plant will expire in 2003, one-third of the existing operating licenses will expire by 2010 and the newest plant's operating license will expire in 2033. The National Energy Strategy (NES) prepared by the Department of Energy (DOE) assumes that 70 percent of the current operating plants will continue to operate beyond their current license expiration. Power from current operating plants can assist in ensuring an adequate, diverse, and environmentally acceptable energy supply for economic growth and improved U.S. competitiveness. In order to preserve this energy resource, three major tasks must be successfully completed: (1) establishment of regulations, technical standards, and procedures for the preparation and review of License Renewal Applications (LRAs); (2) development of technical criteria and bases for monitoring, refurbishing or replacing plant equipment; and (3) demonstration of the regulatory process by a plant obtaining a renewed license. Since 1986, the DOE has been working with the nuclear industry and the Nuclear Regulatory Commission (NRC) to establish and demonstrate the option to extend the life of a nuclear power plant by renewing the operating license. The Monticello Lead Plant demonstration project was initiated in September 1988, following the Pilot Plant studies. This paper is primarily focused on the status and insights gained from the Northern States Power Company (NSP) Monticello Lead Plant demonstration project. The following information is included: (1) Current Status - Monticello License Renewal Application; (2) Economic Analysis; (3) License Renewal Regulatory Uncertainty Issues; (4) Key Decisions; (5) Management Structure; (6) Technical and Licensing Perspective; (7) NRC Interactions; (8) Summary

  19. 37 CFR 370.2 - Notice of use of sound recordings under statutory license.

    Science.gov (United States)

    2010-07-01

    ... BOARD, LIBRARY OF CONGRESS NOTICE AND RECORDKEEPING REQUIREMENTS FOR STATUTORY LICENSES NOTICE AND... gain access to the online Web site or homepage of the Service, or where information may be posted under... obtained from the Copyright Office or to: Library of Congress, Copyright Office, Licensing Division, 101...

  20. Long-term surveillance plan for the Mexican Hat disposal site Mexican Hat, Utah

    International Nuclear Information System (INIS)

    1997-05-01

    This long-term surveillance plan (LTSP) describes the U.S. Department of Energy's (DOE) long-term care program for the Uranium Mill Tailings Remedial Action (UMTRA) Project Mexican Hat, Utah, disposal site. The U.S. Nuclear Regulatory Commission (NRC) has developed regulations for the issuance of a general license for the custody and long-term care of UMTRA Project disposal sites in 10 CFR Part 40. The purpose of this general license is to ensure that the UMTRA Project disposal sites will be cared for in a manner that protects the public health and safety and the environment. Before each disposal site is licensed, the NRC requires the DOE to submit a site-specific LTSP. The DOE prepared this LTSP to meet this requirement for the Mexican Hat disposal site. The general license becomes effective when the NRC concurs with the DOE's determination of completion of remedial action for the disposal site and the NRC formally accepts this LTSP. This LTSP describes the long-term surveillance program the DOE will implement to ensure that the Mexican Hat disposal site performs as designed. The program is based on two distinct types of activities: (1) site inspections to identify potential threats to disposal cell integrity, and (2) monitoring of selected seeps to observe changes in flow rates and water quality. The LTSP is based on the UMTRA Project long-term surveillance program guidance and meets the requirements of 10 CFR section 40.27(b) and 40 CFR section 192.03. 18 refs., 6 figs., 1 tab

  1. Dealing with the current permissibility application for constructing a spent fuel DGR in Sweden. SKB's license applications for a spent fuel repository

    International Nuclear Information System (INIS)

    Olsson, Olle

    2014-01-01

    The nuclear power utilities in Sweden were in 1976 obliged to demonstrate a safe method for final disposal of spent fuel in order to start operation of new reactors. This initiated a comprehensive research, development and demonstration programme and the development of the KBS-method for final disposal. A new Nuclear Activities Act in 1984 gave the reactor owners full technical and financial responsibility for the waste. They gave in turn SKB the responsibility for all nuclear waste management. Reprocessing was no longer required and direct disposal of the spent fuel has, since then, been the main alternative. Alternative methods for final disposal have been evaluated and compared to the KBS-3-method but it has remained the preferred alternative. A comprehensive research, development and demonstration programme to strengthen the scientific basis and to refine the KBS-3-method has been operated by SKB since then. The site selection process for the final repository for spent nuclear fuel was initiated in 1992. The work included general siting studies at the national and the municipal level and in 2002, SKB initiated site investigations for siting of a final repository on two sites: the Simpevarp and Laxemar areas and the Forsmark area. At the same time, the work on preparing license applications to construct and operate an encapsulation plant and a final repository for spent fuel was started. In June 2009, SKB announced Forsmark as the selected site for the final repository. This paper reviews the applicable legislation and describes the license application, the licensing review and the preparations for implementation

  2. An introduction to intellectual property licensing for technology companies

    Science.gov (United States)

    Meier, Lawrence H.

    2001-05-01

    Intellectual property licensing is an important issue facing all technology companies. Before entering into license agreements a number of issues need to be addressed, including invention ownership, obtaining and identifying licensable subject matter, and developing a licensing strategy. There are a number of important provisions that are included in most intellectual property license agreements. These provisions include definitions, the license grant, consideration, audit rights confidentiality, warranties, indemnification, and limitation of liability. Special licensing considerations exist relative to each type of intellectual property, and when the other party is a foreign company or a university.

  3. PBMR-SA licensing project organization

    International Nuclear Information System (INIS)

    Clapisson, G.A.; Metcalf, P.E.; Mysen, A.

    2001-01-01

    The South African nuclear regulatory authority, the Council for Nuclear Safety (CNS), is beginning the safety review of the Pebble Bed Modular Reactor (PBMR) design under development by the South African National Electrical Utility, Eskom. This paper describes the CNS licensing process, including the establishment of basic licensing criteria, general design criteria, and specific design rules, as well the safety assessment to be conducted in accordance with the established structure. It also summarises the CNS PBMR review project activities, including the overall organisational arrangements, licensing basis, safety and risk assessment, general operating rules and plant design engineering, and pre-operational testing. (author)

  4. License - Plabrain DB | LSDB Archive [Life Science Database Archive metadata

    Lifescience Database Archive (English)

    Full Text Available switchLanguage; BLAST Search Image Search Home About Archive Update History Data List Contact us Plabrain... Alike 2.1 Japan . If you use data from this database, please be sure attribute this database as follows: Plabrain...of this database (http://dbarchive.lifesciencedb.jp/english/en/plabrain-db/desc.html) in the article or pape...se Description Download License Update History of This Database Site Policy | Contact Us License - Plabrain DB | LSDB Archive ...

  5. License - tRNADB-CE | LSDB Archive [Life Science Database Archive metadata

    Lifescience Database Archive (English)

    Full Text Available switchLanguage; BLAST Search Image Search Home About Archive Update History Data List Contact us tRNAD...-Share Alike 2.1 Japan. If you use data from this database, please be sure attribute this database as follows: tRNAD...: About This Database Database Description Download License Update History of This Database Site Policy | Contact Us License - tRNADB-CE | LSDB Archive ...

  6. Site characterization quality assurance for the California LLRW Disposal Site Project

    International Nuclear Information System (INIS)

    Hanrahan, T.P.; Ench, J.E.; Serlin, C.L.; Bennett, C.B.

    1988-01-01

    In December of 1985 US Ecology was chosen as the license designee for the State of California's low-level radioactive waste disposal facility. In early 1987, three candidate sites were selected for characterization studies in preparation for identifying the preferred site. The geotechnical characterization activities along with studies of the ecological and archaeological attributes, as well as assessments of the socio-economic impacts and cultural resources all provide input towards selection of the proposed site. These technical studies in conjunction with comments from local citizen committees and other interested parties are used as a basis for determining the proposed site for which full site characterization as required by California licensing requirements are undertaken. The purpose of this paper is to present an overview of the program for Quality Assurance and Quality Control for the site characterization activities on the California LLRW Disposal Site Project. The focus is on three major perspectives: The composite QA Program and two of the primary characterization activities, the geotechnical and the meteorological investigations

  7. Research and development associated with licensing of MHTGR [Modular High Temperature Gas-Cooled Reactor

    International Nuclear Information System (INIS)

    Jones, H.

    1990-01-01

    The Modular High Temperature Gas-Cooled Reactor (MHTGR) currently under development by the US Department of Energy (US-DOE) for commercial applications has top-level goals of producing safe, economical power for the US utility industry. The utility industry has been represented in formulating design and licensing requirements through both a ''Utility User Requirements Document'' and by participating in the DOE system engineering process known as the ''Integrated Approach.'' The result of this collaboration has been to set stringent goals for both the safety and operational reliability of the MHTGR. To achieve these goals, the designer must have access to a more comprehensive data base of properties in several fields of technology than is currently available. A technology development program has been planned to provide this data to the designer in time to support both his design activities and the submittal of formal licensing application documents. The US-DOE has chosen the Oak Ridge National Laboratory (ORNL) to take the lead in planning and executing these technology programs. When completed these will augment the designer's current data base and provide the necessary depth to meet the stringent goals which have been set for the MHTGR. It is worth noting that the goals of safety and operational reliability are complementary, and the data required from the technology development program will be similar. Therefore, the program to support the licensing of the MHTGR is not separate from that required for design, but is a subset of that which meets all the requirements that result from implementing the US-DOE's integrated approach. 38 figs

  8. Licensing of simple digital devices

    International Nuclear Information System (INIS)

    Jackson, T. W.

    2008-01-01

    The inability to guarantee error-free software gave rise to the potential for common-cause failure of digital safety systems in nuclear power plants. To address this vulnerability, the U. S. Nuclear Regulatory Commission (NRC) required a quality software development process and a defense-in-depth and diversity analysis for digital safety systems. As a result of recent interim [NRC] staff guidance in the digital instrumentation and control (I and C) area, licensing of simple digital devices decreases some regulatory burden with respect to demonstrating a quality software development process and defense-in-depth and diversity analysis. This paper defines simple digital devices and addresses the interim staff guidance that applies to such devices. The paper also highlights the technical aspects that affect the licensing of such devices and incorporates licensing experience in the U.S. to date. (authors)

  9. Licensing and advanced fuel designs

    International Nuclear Information System (INIS)

    Davidson, S.L.; Novendstern, E.H.

    1991-01-01

    For the past 15 years, Westinghouse has been actively involved in the development and licensing of fuel designs that contain major advanced features. These designs include the optimized fuel assembly, The VANTAGE 5 fuel assembly, the VANTAGE 5H, and most recently the VANTAGE+ fuel assembly. Each of these designs was supported by extensive experimental data, safety evaluations, and design efforts and required intensive interaction with the US Nuclear Regulatory Commission (NRC) during the review and approval process. This paper presents a description of the licensing approach and how it was utilized by the utilities to facilitate the licensing applications of the advanced fuel designs for their plants. The licensing approach described in this paper has been successfully applied to four major advanced fuel design changes ∼40 plant-specific applications, and >350 cycle-specific reloads in the past 15 years

  10. 77 FR 22333 - Prospective Grant of Exclusive License: Development of Oncolytic Viral Cancer Therapies

    Science.gov (United States)

    2012-04-13

    ... DEPARTMENT OF HEALTH AND HUMAN SERVICES National Institutes of Health Prospective Grant of Exclusive License: Development of Oncolytic Viral Cancer Therapies AGENCY: National Institutes of Health... administration of the recombinant virus to a human or animal subject, the foreign gene is expressed in vivo to...

  11. Licensing of away-from-reactor (AFR) installations

    International Nuclear Information System (INIS)

    Gray, P.L.

    1980-01-01

    Storage of spent fuel at Away-From-Reactor (AFR) installations will allow reactors to continue to operate until reprocessing or other fuel disposal means are available. AFR installations must be licensed by the Nuclear Regulatory Commission (NRC). Although wide experience in licensing reactors exists, the licensing of an AFR installation is a relatively new activity. Only one has been licensed to date. This paper delineates the requirements for licensing an AFR installation and projects a licensing schedule. Because the NRC is developing specific AFR requirements, this schedule is based primarily on draft NRC documents. The major documents needed for an AFR license application are similar to those for a reactor. They include: a Safety Analysis Report (SAR), and Environmental Report (ER), safeguards and security plans, decommissioning plans, proposed technical specifications, and others. However, the licensing effort has one major difference in that for AFR installations it will be a one-step effort, with follow-up, rather than the two-step process used for reactors. The projected licensing schedule shows that the elapsed time between filing an application and issuance of a license will be about 32 months, assuming intervention. The legal procedural steps will determine the time schedule and will override considerations of technical complexity. A license could be issued in about 14 months in the absence of intervention

  12. State of Nevada comments on the US Department of Energy site characterization plan, Yucca Mountain site, Nevada

    International Nuclear Information System (INIS)

    1989-01-01

    We find the Site Characterization Plan: Yucca Mountain Site, Nevada Research and Development Area (DOE/RW-0160) seriously deficient, in terms of establishing an investigative program to confidently characterize hydrogeologic and closely-related aspects of the proposed repository, in the vadose zone at Yucca Mountain. Most hydrogeological licensing criteria indirectly measure waste isolation provided by the geologic environment during pre- and post-closure conditions. We believe the Site Characterization Plan (SCP) generally fails to establish scientifically sound and feasible programs of investigation that will, in a timely and confident manner, resolve most of the hydrogeologic and geochemical licensing issues that have been recognized since the vadose-zone repository was first proposed at this location in 1982. The SCP generally fails in its responsibility because it does not objectively set aside the DOE conceptual model of a ''dry'' repository environment with extremely slow flow of water confined to the rock matrix. In the SCP, the DOE fails to establish a scientifically sound investigative program that seriously tests for hydrogeologic conditions based on the range of existing data and general knowledge. Rather, the DOE builds a probabilistic program upon a preconceived conceptual model, without designing a field-data collection program with the power to test the validity of the conceptual model. This is unacceptable in that the DOE program, as described in the SCP, plans to build numerical model after numerical model upon untested conceptual models, in attempts to ''resolve'' the fundamental licensing issues of waste isolation by the geologic barrier. If executed as planned, these analyses will have only a series of assumptions of their foundation and, therefore, can not resolve licensing issues. 12 refs., 3 figs

  13. AP1000{sup R} licensing and deployment in the United States

    Energy Technology Data Exchange (ETDEWEB)

    Jordan, R. P.; Russ, P. A.; Filiak, P. P.; Castiglione, L. L. [Westinghouse Electric Company LLC, 1000 Westinghouse Drive, Cranberry Township, PA 16066 (United States)

    2012-07-01

    In recent years, both domestic and foreign utilities have turned to the standardized Westinghouse AP1000 plant design in satisfying their near - and long-term - sustainable energy needs. As direct support to these actions, licensing the AP1000 design has played a significant role by providing one of the fundamental bases in clearing regulatory hurdles leading to the start of new plant construction. Within the U.S. alone, Westinghouse AP1000 licensing activities have reached unprecedented milestones with the approvals of both AP1000 Design Certification and Southern Company's combined construction permit and operating license (COL) application directly supporting the construction of two new nuclear plants in Georgia. Further COL application approvals are immediately pending for an additional two AP1000 plants in South Carolina. And, across the U.S. nuclear industry spectrum, there are 10 other COL applications under regulatory review representing some 16 new plants at 10 sites. In total, these actions represent the first wave of new plant licensing under the regulatory approval process since 1978. Fundamental to the Nuclear Regulatory Commission's AP1000 Design Certification is the formal recognition of the AP1000 passive safety design through regulatory acceptance rulemaking. Through recognition and deployment of the AP1000 Design Certification, the utility licensee / operator of this reactor design are now offered an opportunity to use a simplified 'one-step' combined license process, thereby managing substantial back-end construction schedule risk from regulatory and intervention delays. Application of this regulatory philosophy represents both acceptance and encouragement of standardized reactor designs like the AP1000. With the recent AP1000 Design Certification and utility COL acceptances, the fundamental licensing processes of this philosophy have successfully proven the attainment of significant milestones with the next stage licensing

  14. CONFIRMATORY SURVEY RESULTS FOR PORTIONS OF THE ABB COMBUSTION ENGINEERING SITE IN WINDSOR, CONNECTICUT DURING THE FALL OF 2011

    Energy Technology Data Exchange (ETDEWEB)

    Wade C. Adams

    2011-12-09

    From the mid-1950s until mid-2000, the Combustion Engineering, Inc. (CE) site in Windsor, Connecticut (Figure A-1) was involved in the research, development, engineering, production, and servicing of nuclear fuels, systems, and services. The site is currently undergoing decommissioning that will lead to license termination and unrestricted release in accordance with the requirements of the License Termination Rule in 10 CFR Part 20, Subpart E. Asea Brown Boveri Incorporated (ABB) has been decommissioning the CE site since 2001.

  15. Confirmatory Survey Results For Portions Of The ABB Combustion Engineering Site In Windsor, Connecticut During The Fall Of 2011

    International Nuclear Information System (INIS)

    Adams, Wade C.

    2011-01-01

    From the mid-1950s until mid-2000, the Combustion Engineering, Inc. (CE) site in Windsor, Connecticut (Figure A-1) was involved in the research, development, engineering, production, and servicing of nuclear fuels, systems, and services. The site is currently undergoing decommissioning that will lead to license termination and unrestricted release in accordance with the requirements of the License Termination Rule in 10 CFR Part 20, Subpart E. Asea Brown Boveri Incorporated (ABB) has been decommissioning the CE site since 2001.

  16. License - GenLibi | LSDB Archive [Life Science Database Archive metadata

    Lifescience Database Archive (English)

    Full Text Available switchLanguage; BLAST Search Image Search Home About Archive Update History Data ...nse Update History of This Database Site Policy | Contact Us License - GenLibi | LSDB Archive ...

  17. Licensing of MAPLE reactors in Canada

    International Nuclear Information System (INIS)

    Lee, A.G.; Labrie, J.P.; Langman, V.J.

    1999-01-01

    Full text: The Operating Licence for a MAPLE reactor (i.e., a 10 MW(th), pool-type reactor), has been approved by the Atomic Energy Control Board (AECB) on August 16th, 1999. This Operating Licence has been obtained within three years of the initiation of the MDS Nordion Medical Isotopes Reactor (MMIR) project, which entails the design, construction and commissioning of two 10 MW MAPLE reactors at AECL's Chalk River Laboratories. The scope and nature of the information required by the AECB, the licensing process and highlights of the events which led to successfully obtaining the Operating Licence for the MAPLE reactor are discussed. These discussions address all phases of the licensing process (i.e., the environmental assessment in support of siting, the Preliminary Safety Analysis Report, PSAR, in support of design, procurement and construction, the Final Safety Analysis Report, FSAR, in support of commissioning and operations, and the development of suitable quality assurance subprograms for each phase). An overview of some of the unique technical aspects associated with the MAPLE reactors, and how they have been addressed during the licensing process are also provided (e.g., applying CSA N285.0, General Requirements for Pressure-Retaining Systems and Components in CANDU Nuclear Power Plants, to a small, low pressure, low temperature research reactor, confirmation of the performance of the driver fuel via laboratory and/or in-reactor testing, validation of the computer codes used to perform the safety analyses, critical parameter uncertainty assessment, full scale hydraulic testing of the performance of the design, fuel handling, human factors validation, operator training and certification). (author)

  18. Specialized sorting and measuring system for site remediation

    International Nuclear Information System (INIS)

    Runge, H.; Christ, G.

    2001-01-01

    The machine design and measurement philosophy of the SSGE, developed for excavation and treatment of some 21,000 metric tons of ground material and concrete from NUKEM decommissioned fuel element factory, have already been passed the official licensing procedure. The start up of site clean-up is scheduled for summer 2001. With the SSGE there has been made available a method to safe and economically remediate contaminated ground of nuclear sites. The SSEG, being a mobile system, can be applied at various sites

  19. Radiological characterization and challenges at decommissioning sites

    International Nuclear Information System (INIS)

    Moore, Scott

    2002-01-01

    Scott Moore described the dose-based radiological characterisation process used in the USA, and four current characterisation issues faced there. His paper emphasized the importance of characterisation to control decommissioning hazards and costs: The License Termination Rule (LTR), Subpart E to 10 CFR Part 20, provides the dose-based criteria that the U.S. Nuclear Regulatory Commission (NRC) uses as the basis for regulating cleanup at material and reactor sites. The LTR permits the release of sites for unrestricted use, if the radioactivity that is distinguishable from background results in a total effective dose equivalent to an average member of a critical group that does not exceed 0.25 milli-Sievert per year (mSv/yr) (25 milli-rem/year) and the residual radioactivity has been reduced to levels that are as low as reasonably achievable. Additionally, the LTR establishes criteria for license termination with restrictions on future land use, which allow for a dose to the critical group of 0.25 mSv/yr (25 milli-rem/year) with restrictions in place, and 1 mSv/yr (100 milli-rem/year) if the restrictions fail. In certain circumstances as outlined in Subpart E, a dose as high as 5 mSv/yr (500 milli-rem/year) is permitted if restrictions fail. Following issuance of the dose-based LTR in 1997, NRC staff developed the Standard Review Plan for Decommissioning Plans (NUREG-1727). NUREG-1727 is a guidance document that describes the methods that NRC has determined are acceptable for implementing the LTR and other decommissioning regulations. While NUREG-1727 is focused on the review of decommissioning plans for nuclear material sites, it provides general guidance that in many cases is applicable to reactor sites (e.g., review criteria for dose-modeling and radiological surveys). In addition to NUREG-1727, staff developed the Standard Review Plan for Evaluating Nuclear Power Reactor License Termination Plans (NUREG-1700) as specific guidance for reactor decommissioning. NUREG

  20. Developments in modelling the economic impact of Off-site accident consequences

    International Nuclear Information System (INIS)

    Haywood, S.M.; Robinson, C.A.; Faude, D.

    1991-01-01

    Models for assessing the economic consequences of accidental releases of radioactivity have application both in accident consequence codes and in decision aiding computer systems for use in emergency response. Such models may be applied in emergency planning, and studies in connection with the siting, design and licensing of nuclear facilities. Several models for predicting economic impact have been developed, in Europe and the US, and these are reviewed. A new model, called COCO-1 (Cost of Consequences Off-site), has been developed under the CEC MARIA programme and the features of the model are summarised. The costs calculated are a measure of the benefit foregone as a result of the accident, and in addition to tangible monetary costs the model attempts to include costs arising from the effect of the accident on individuals, for instance the disruption caused by the loss of homes. COCO-1 includes the cost of countermeasures, namely evacuation, relocation, sheltering, food restrictions and decontamination, and also the cost of health effects in the exposed population. The primary quantity used in COCO-1 to measure the economic value of land subject to restrictions on usage is Gross Domestic Product (GDP). Examples of default data included in the model are presented, as are the results of an illustrative application. The limitations of COCO-1 are discussed, and areas where further data are needed are identified

  1. Siemens Nuclear Power Corporation methods development for BWR/PWR reactor licensing

    International Nuclear Information System (INIS)

    Pruitt, D.W.

    1992-01-01

    This presentation addresses the Siemens Nuclear Power Corporation (SNP) perspective on the primary forces driving methods development in the nuclear industry. These forces are fuel design, computational environment and industry requirement evolution. The first segment of the discussion presents the SNP experience base. SNP develops, manufactures and licenses both BWR and PWR reload fuel. A review of this experience base highlights the accelerating rate at which new fuel designs are being introduced into the nuclear industry. The application of advanced BWR lattice geometries provides an example of fuel design trends. The second aspect of the presentation is the rapid evolution of the computing environment. The final subject in the presentation is the impact of industry requirements on code or methods development

  2. Licensing activities for advanced reactors in NNC

    International Nuclear Information System (INIS)

    Chevalier, A.B.H.; Mustoe, J.; Walters, J.; Ingham, E.L.

    2001-01-01

    NNC has been involved in safety and licensing activities for advanced reactors for many years. Most recently NNC has been involved with national regulators or their representatives for the HTR (High Temperature Reactor) reactor and the possible siting of ITER (International Thermonuclear Experimental Reactor) within Europe. Commonalties between the two activities can be seen, even though one is a fission process and the other based on a completely new technology. Both have the potential to generate power at a very low overall exposure to the public and station staff, but both also need to demonstrate to the regulator the safety of a design which differs from the standard LWR practice. In both concepts passive design features provide a major part of the safety argument, but the detailed assessment and justification of these features in licensing terms still needs to be made. A number of critical safety issues can be identified, which generally apply to any advanced system. These are: Safety categorization, codes and standards; confinement or containment; ALARA; safety code modelling and data; Occupational Exposure; occupational exposures; decommissioning and waste; no evacuation, or no emergency plans. The UK is notable for a flexible licensing regime, which allows a safety case to be built up from first principles, where this is applicable. In addition, experience of licensing gas cooled, water cooled and liquid metal plant, as well as extensive experience outside the UK provides NNC with a unique insight into the different licensing methodologies which can be applied in the licensing process. This paper discusses some possible approaches which could be applied in order to satisfy regulatory demands when addressing the critical issues listed above. (author)

  3. ITER Safety and Licensing

    International Nuclear Information System (INIS)

    Girard, J-.P; Taylor, N.; Garin, P.; Uzan-Elbez, J.; GULDEN, W.; Rodriguez-Rodrigo, L.

    2006-01-01

    The site for the construction of ITER has been chosen in June 2005. The facility will be implemented in Europe, south of France close to Marseille. The generic safety scheme is now under revision to adapt the design to the host country regulation. Even though ITER will be an international organization, it will have to comply with the French requirements in the fields of public and occupational health and safety, nuclear safety, radiation protection, licensing, nuclear substances and environmental protection. The organization of the central team together with its partners organized in domestic agencies for the in-kind procurement of components is a key issue for the success of the experimentation. ITER is the first facility that will achieve sustained nuclear fusion. It is both important for the experimental one-of-a-kind device, ITER itself, and for the future of fusion power plants to well understand the key safety issues of this potential new source of energy production. The main safety concern is confinement of the tritium, activated dust in the vacuum vessel and activated corrosion products in the coolant of the plasma-facing components. This is achieved in the design through multiple confinement barriers to implement the defence in depth approach. It will be demonstrated in documents submitted to the French regulator that these barriers maintain their function in all postulated incident and accident conditions. The licensing process started by examination of the safety options. This step has been performed by Europe during the candidature phase in 2002. In parallel to the final design, and taking into account the local regulations, the Preliminary Safety Report (RPrS) will be drafted with support of the European partner and others in the framework of ITER Task Agreements. Together with the license application, the RPrS will be forwarded to the regulatory bodies, which will launch public hearings and a safety review. Both processes must succeed in order to

  4. Licensing of spent fuel storage facility including its physical protection in the Czech Republic

    International Nuclear Information System (INIS)

    Fajman, V.; Sedlacek, J.

    1992-01-01

    The current spent fuel management policies as practised in the Czech Republic are described, and the conception of the fuel cycle back end is outlined. The general principles and the legislative framework are explained of the licensing process concerning spent fuel interim storage facilities, including the environmental impact assessment component. The history is outlined of the licensing process for the spent fuel storage facility at the Dukovany NPP site, including the licensing of the transport and storage cask. The basic requirements placed on the physical safeguarding of the facility and on the licensing process are given. (J.B.). 13 refs

  5. Legal questions concerning the licensing procedure of nuclear power plants

    International Nuclear Information System (INIS)

    Boerner, B.

    1978-01-01

    The publication contains 4 articles which deal with legal practice and problems of the licensing procedure in the Federal Republic of Germany: 1) Actions brought by joint boards from the constitutional point of view (Burmeister, J.); 2) court review of the assessment of technical and economic questions concerning the licensing of power plant construction (Ossenbuehl, F.); 3) the site plan approval procedure as a legal problem (Friauf, K.H.); 4) legal questions concerning the immediate enforceability (Papier, H.J.). (HP) [de

  6. License renewal process

    International Nuclear Information System (INIS)

    Fable, D.; Prah, M.; Vrankic, K.; Lebegner, J.

    2004-01-01

    The purpose of this paper is to provide information about license renewal process, as defined by Nuclear Regulatory Commission (NRC). The Atomic Energy Act and NRC regulations limit commercial power reactor licenses to an initial 40 years but also permit such licenses to be renewed. This original 40-year term for reactor licenses was based on economic and antitrust considerations not on limitations of nuclear technology. Due to this selected time period; however, some structures and components may have been engineered on the basis of an expected 40-year service life. The NRC has established a timely license renewal process and clear requirements codified in 10 CFR Part 51 and 10 CFR Part 54, that are needed to assure safe plant operation for extended plant life. The timely renewal of licenses for an additional 20 years, where appropriate to renew them, may be important to ensuring an adequate energy supply during the first half of the 21st Century. License renewal rests on the determination that currently operating plants continue to maintain adequate levels of safety, and over the plant's life, this level has been enhanced through maintenance of the licensing bases, with appropriate adjustments to address new information from industry operating experience. Additionally, NRC activities have provided ongoing assurance that the licensing bases will continue to provide an acceptable level of safety. This paper provides additional discussion of license renewal costs, as one of key elements in evaluation of license renewal justifiability. Including structure of costs, approximately value and two different approaches, conservative and typical. Current status and position of Nuclear Power Plant Krsko, related to license renewal process, will be briefly presented in this paper. NPP Krsko is designed based on NRC Regulations, so requirements from 10 CFR 51, and 10 CFR 54, are applicable to NPP Krsko, as well. Finally, this paper will give an overview of current status of

  7. Development and Field Test of Competency Based Instructional Material for a Career Mobility Program for Licensed Practical Nurses. Final Report.

    Science.gov (United States)

    Bergen Community Coll., Paramus, NJ.

    The Associate Degree Nursing Program at Bergen Community College developed and field tested competency-based instructional modules in a program designed to allow licensed practical nurses to qualify to take the certification examination for registered nurses after a year of study. Thirteen licensed practical nurses were enrolled in the first class…

  8. Site development

    International Nuclear Information System (INIS)

    Noack, J.

    1975-01-01

    The subject of this paper is a general view over all necessary considerations to develop the site after it has been chosen and before starting with the construction of a nuclear power plant. (orig./RW) [de

  9. The nuclear licensing and supervisory procedures for nuclear facilities in the Federal Republic of Germany

    International Nuclear Information System (INIS)

    Franzen, L.F.

    1982-02-01

    A combined system has been developed in the Federal Republic of Germany: the States execute the Atomic Energy Act on behalf of the Federal Government. Despite these differences, the safety requirements and the safety standard achieved vary only insignificantly, as a result of a world-wide communication and of international cooperation. The legal prerequesites for the German nuclear licensing procedures have been established about 20 years ago, and, by a number of amendments have been adapted to new perceptions and developments. Several supplementary ordinances, due to further developments in nuclear technology, are being prepared. The work on associated technical provision, which had been neglected for a long time, has in recent years been tackled systematically and should, before long, lead to a comprehensive programme of safety standards, which simplifies and expedites the nuclear licensing procedures. Essential features of the licensing procedure are the phased structure and the division into intermediate steps which render it possible to adapt the safety requirements to the advancing state of science and technology. The responsible authorities call in experts for the safety verification of the application documents. It is the task of these experts to make assessments and to conduct quality examinations in the manufacturing plants and at the site, and to carry out recurrent tests. The public is involved by the announcement of the projects, the display of the documents and by the opportunity to raise objections during the licensing procedure. Licenses granted can be contested before the administrative courts. This procedure paves the way for the achievement of a satisfactory balance between private and public interests. (orig./HP)

  10. Use of limited information in a license application to construct a repository

    International Nuclear Information System (INIS)

    McGarry, J.M. III; Echols, F.S.

    1996-01-01

    The purpose of this paper is to provide a rationale for the proposition that the Department of Energy's (DOE's) submittal of a license application (LA) for the construction of a geologic repository to the Nuclear Regulatory Commission (NRC) may be, and arguably must be, based on statutorily-limited site characterization data and design information. The Nuclear Waste Policy Act of 1982 (NWPA), as amended, is the controlling statute for the disposal of spent nuclear fuel in a licensed geologic repository. Applicable NRC regulations for the licensing of such a repository are found for the most part in 10 C.F.R. Part 60

  11. Insights from Siting New Nuclear Power Plants in the Central and Eastern United States

    International Nuclear Information System (INIS)

    Munson, Clifford G.; Kugler, Andrew J.

    2011-01-01

    The staff of the U.S. Nuclear Regulatory Commission (NRC) has completed its review for four early site permits and for four standard reactor designs. It is currently reviewing applications for fourteen combined license applications and three additional reactor designs. The staff is applying lessons it has learned from the reviews to date to the review work going forward. The licensing process being used by current applicants differs significantly from that used by the current operating fleet. The previous process required two steps. First an applicant had to obtain a construction permit to build the plant. Then, near the end of construction, the applicant had to obtain an operating license. Under the process in Part 52, an applicant can apply for a combined license (COL) that allows construction and (once certain conditions are met) operation of a new plant - a one-step process. An applicant for a COL may reference an early site permit (ESP13), a standard design certification, both, or neither. In addition to developing Part 52, the NRC also revised CFR Part 100 by adding Subpart B, which includes sections 100.21, 'Non-seismic siting criteria', and 100.23, 'Geologic and seismic siting criteria'. The NRC staff also revised the Standard Review Plan (NUREG-0800) and developed Regulatory Guide (RG) 1.206, 'Combined License Applications for Nuclear Power Plants (LWR Edition).' The NRC staff incorporated into the revision of NUREG-0800 and development of RG 1.206 some early lessons learned from its review of the first three ESPs. Staff work begins before the application is received, as the staff interacts with the applicant to identify issues that will require special treatment or specific staff resources. After the application is submitted, if the NRC finds the application acceptable, the safety and environmental reviews begin, proceeding in parallel. The safety review culminates in the issuance of a safety evaluation report (SER) after it

  12. A Real-time License Plate Detection System for Parking Access

    Directory of Open Access Journals (Sweden)

    Roenadi Koesdijarto

    2010-08-01

    Full Text Available The automatic and real-time license plate detection system can be used as an access control entry of vehicles into the parking area. The problem is how to recognize the vehicles that will go into the parking lot and how to recognize various types of license plates in various light conditions quickly and accurately. In this research, the prototype was developed with a detection system to recognize the vehicles that will enter the parking area, and a license plate recognition system. In the license plate recognition system, the Fourier transform and Hidden Markov model method have proposed to detect location of license plate and as characters segmentation to recognize Indonesia license plates. The research results have shown that the developed prototype system has successfully recognized all Indonesia license plates in several of light condition and camera position. The percentage of plate recognition in the real-time experiment is 84.38%, and the average execution time for all recognition process is 5.834 second.

  13. Impact of New Radiation Safety Standards on Licensing Requirements of Nuclear Power Plant

    International Nuclear Information System (INIS)

    Strohal, P.; Subasic, D.; Valcic, I.

    1996-01-01

    As the outcomes of the newly introduced safety philosophies, new and more strict safety design requirements for nuclear installation are expected to be introduced. New in-depth defence measures should be incorporated into the design and operation procedure for a nuclear installation, to compensate for potential failures in protection or safety measures. The new requirements will also apply to licensing of NPP's operation as well as to licensing of nuclear sites, especially for radioactive waste disposal sites. This paper intends to give an overview of possible impacts of new internationally agreed basic safety standards with respect to NPP and related technologies. Recently issued new basic safety standards for radiation protection are introducing some new safety principles which may have essential impact on future licensing requirements regarding nuclear power plants and radioactive waste installations. These new standards recognize exposures under normal conditions ('practices') and intervention conditions. The term interventions describes the human activities that seek to reduce the existing radiation exposure or existing likelihood of incurring exposure which is not part of a controlled practice. The other new development in safety standards is the introduction of so called potential exposure based on the experience gained from a number of radiation accidents. This exposure is not expected to be delivered with certainty but it may result from an accident at a source or owing to an event or sequence of events of a probabilistic nature, including equipment failures and operating errors. (author)

  14. Finnish HLW disposal programme : site selection in 2000

    International Nuclear Information System (INIS)

    Ryhsnen, Veijo

    1997-01-01

    This paper covers the technical concepts for final disposal in the Finnish geological conditions, the approach for site selection and implementation, the safety assessments and development of criteria, the environmental impact assessment, the licensing stages and acceptance, and the financial provisions, the project organization in 1997 - 2000. 2 refs., 9 figs

  15. Finnish HLW disposal programme : site selection in 2000

    Energy Technology Data Exchange (ETDEWEB)

    Ryhsnen, Veijo [Posiva Oy, Helsinki (Finland)

    1997-12-31

    This paper covers the technical concepts for final disposal in the Finnish geological conditions, the approach for site selection and implementation, the safety assessments and development of criteria, the environmental impact assessment, the licensing stages and acceptance, and the financial provisions, the project organization in 1997 - 2000. 2 refs., 9 figs.

  16. Safety philosophy and licensing practice in different member states of IAEA: Spain

    International Nuclear Information System (INIS)

    Alonso, A.

    1981-01-01

    With the aim of presenting the licensing experience in Spain, the countries with nuclear activities are divided into three main groups: exporters, qualified importers and importers, being Spain in the second group. The licensing problems, and therefore the licensing experience, are different in the different groups of countries. Moreover, the experience in Spain is enriched by the following facts: an early start, a substantial program and a diversity of types, pressurized and boiling water reactors, and suppliers, American and German plants. Reference is made to the basic legal documents governing licensing in Spain, together with the difficulties in adopting and applying detailed regulations. Within this framework, the licensing experience in Spain is described with reference to the reference plant concept, later enlarged to include the reference-site reference plant concept, ending in the most practical approach of the reference problem concept. Finally specific licensing problems are introduced with reference to the Spanish operating nuclear power plants, the ones under commissioning and in an advanced state of construction and the ones just staring construction. (orig./RW)

  17. Technology licensing in China

    DEFF Research Database (Denmark)

    Wang, Yuandi; Li-Ying, Jason; Chen, Jin

    2015-01-01

    We explore the landscape of technology licensing among Chinese entities in the period 2000–12, using a unique database on technological licensing from the State Intellectual Property Office of China. We find that: first, among Chinese licensee organizations, firms have dominated in terms...... of the number of licensed technologies; second, the geographical distribution of licensed technologies among the provinces has gradually reached a new quantitative balance; third, utility models are the most popular technologies to be licensed and the majority of technology licensing in China has been between...... Chinese entities, and most transactions have been local within provinces; and finally, Chinese firms have gradually in-licensed newer and newer technologies, but the technologies in-licensed from foreign sources are by no means state-of-the-art. We make several suggestions for innovation policy...

  18. Early Site Permit Demonstration Program: Regulatory criteria evaluation report

    International Nuclear Information System (INIS)

    1993-03-01

    The primary objective of the Early Site Plan Demonstration Program (ESPDP) is to demonstrate successfully the use of 10CFR52 to obtain ESPs for one or more US sites for one (or more) ALWR nuclear power plants. It is anticipated that preparation of the ESP application and interaction with NRC during the application review process will result not only in an ESP for the applicant(s) but also in the development of criteria and definition of processes, setting the precedent that facilitates ESPs for subsequent ESP applications. Because siting regulatory processes and acceptance criteria are contained in over 100 separate documents, comprehensive licensing and technical reviews were performed to establish whether the requirements and documentation are self-consistent, whether the acceptance criteria are sufficiently well-defined and clear, and whether the licensing process leading to the issuance of an ESP is unambiguously specified. This document provides appendices A and B of this report. Appendix A contains a list of regulations, regulatory guidance, and acceptance criteria; Appendix B contains a cross-reference index of siting-related documentation

  19. The licensing procedure under Atomic Energy Law

    International Nuclear Information System (INIS)

    Ronellenfitsch, M.

    1983-01-01

    This post-doctoral thesis of 1981 has been updated to include developments in this field up to the year 1983. The author discusses in detail all questions relating to the peaceful uses of nuclear energy in the Federal Republic of Germany, predominantly from the point of view of administrative law. He investigates nuclear energy and its contribution to electricity supplies with a view to other energy sources, renewable energy sources, alternative energy policies, nuclear fuel and the fuel cycle, development of the nuclear industry, nuclear power stations in operation, under construction, or in development. Following a survey of the nuclear controversy, both on the national and the international level, the author reviews the legal system and arising controversies in the Federal Republic of Germany, defining the purpose of this thesis to be the systematic analysis of the available legal instruments, in order to show structural deficiencies in the planning law relating to nuclear power stations, and thus reasons of ambiguities within the licensing procedure. The author studies the following terms and requirements: licensing requirements and licensability, the licensing method and scenario, the legal character of licences, their contents and effects within the stepwise procedure, and due publication. (HSCH) [de

  20. Economic implications of nuclear plant license renewal in the U.S

    International Nuclear Information System (INIS)

    Smith, L.J.

    2001-01-01

    The NRC and the nuclear industry struggled for many years with the development of a viable license renewal rule. Now that a workable rule appears to have been developed, and the first license renewal applicants have received renewed licenses, the floodgates have opened and a large number of nuclear utilities have announced intentions to seek renewed NRC operating licenses. In this time when profound changes are being experienced in the electric generation markets in the United States, nuclear plant license renewal can have several economic effects that should be considered by utilities prior to the pursuit of an NRC license renewal. This paper examines some of the factors that may be affected by the prospect of an additional 20-year operating life of a nuclear plant. (author)

  1. Directions in low-level radioactive waste management. The siting process: establishing a low-level waste-disposal facility

    International Nuclear Information System (INIS)

    1982-11-01

    The siting of a low-level radioactive waste disposal facility encompasses many interrelated activities and, therefore, is inherently complex. The purpose of this publication is to assist state policymakers in understanding the nature of the siting process. Initial discussion focuses on the primary activities that require coordination during a siting effort. Available options for determining site development, licensing, regulating, and operating responsibilities are then considered. Additionally, the document calls attention to technical services available from federal agencies to assist states in the siting process; responsibilities of such agencies are also explained. The appendices include a conceptual plan for scheduling siting activities and an explanation of the process for acquiring agreement state status. An agreement state takes responsibility for licensing and regulating a low-level waste facility within its borders

  2. The road to MYRRHA. The pre-licensing phase and FEED

    International Nuclear Information System (INIS)

    2014-01-01

    The article discusses the study phase of the future research reactor MYRRHA. This study phase covers three major areas: Research and Development, licensing and engineering. In 2013, substantial progress was made in the licensing and engineering processes: licensing is currently in the pre-licensing phase, while, for engineering, the Front-end Engineering and Design (FEED) contract was signed for the construction of the non-nuclear parts of MYRRHA. The article highlights work associated with the the pre-licensing phase and the FEED.

  3. The use of U.S. NRC licensing practices for VVERs

    International Nuclear Information System (INIS)

    Popp, D.M.

    2000-01-01

    The licensing process for the upgraded Temelin I and C and Fuel designs were enhanced with the introduction of U.S. Nuclear Regulatory Commission, NRC practices. Specifically, the use of the NRC Regulatory Guide 1.70, 'Standard Format and Content Guide for Safety Analyses Reports' and NRC NUREG 0800, 'Standard Review Plan for the Review of Safety Analysis Reports for Nuclear Power Plants', were beneficial in the development and review of Temelin licensing documentation. These standards have been used for the preparation and review of Safety Analysis Reports in the United States and also in a large number of licensing applications around the world. Both Regulatory Guide 1.70 and NUREG 0800 were developed to provide a predictable and structured approach to licensing. This paper discusses this approach and identifies the benefits to designers, writers of licensing documentation and reviewers of licensing documents. (author)

  4. Issues in the review of a license application for an above grade low-level radioactive waste disposal facility

    Energy Technology Data Exchange (ETDEWEB)

    Ringenberg, J.D. [Nebraska Dept. of Environmental Quality, NE (United States)

    1993-03-01

    In December 1987, Nebraska was selected by the Central Interstate Compact (CIC) Commission as the host state for the construction of a low-level radioactive waste disposal facility. After spending a year in the site screening process, the Compact`s developer, US Ecology, selected three sites for detailed site characterization. These sites were located in Nemaha, Nuckolls and Boyd Counties. One year later the Boyd County site was selected as the preferred site and additional site characterization studies were undertaken. On July 29, 1990, US Ecology submitted a license application to the Nebraska Department of Environmental Control (now Department of Environmental Quality-NDEQ). This paper will present issues that the NDEQ has dealt with since Nebraska`s selection as the host state for the CIC facility.

  5. Current status of the PBMR licensing project

    International Nuclear Information System (INIS)

    Mysen, A.; Clapisson, G.A.; Metcalf, P.E.

    2000-01-01

    The CNS is currently reviewing the PBMR conceptual design from a licensibility point of view. The PBMR concept is based on a High Temperature Gas Cooled Reactor - pebble bed reactor type. It is anticipated that the PBMR design will rely on inherent safety characteristics to contain fission products within fuel over the full range of design basis events. This feature combined with the high temperature integrity of the fuel and structural graphite, allows the safe use of a high coolant temperature, which allows consideration of the future development of this reactor for non-electrical applications of nuclear heat for industrial use. The CNS licensing approach requires that the licensing and design basis of the plant should respect prevailing international norms and practices and that a quantitative risk assessment should demonstrate compliance with the CNS fundamental safety standards. The first stage of the licensing process is now ongoing; this is a pre-application phase, which will result in a statement on licensibility being issued. Identification of the specific documentation requirements and information needed is required across every step of the licensing process. Top level regulatory requirements have been established for the PBMR. They include the CNS fundamental safety standard and basic licensing criteria, which describes requirements on licensees of nuclear installations regarding risk assessment and compliance with the safety criteria and define classification of licensing basis events. (author)

  6. Safety aspects of nuclear plant licensing in Canada

    International Nuclear Information System (INIS)

    Jennekens, J.H.F.

    1975-01-01

    The legislative authority is laid down in the Atomic Energy Control Act, 1946, declaring atomic energy a matter of national interest and establishing the Atomic Energy Control Board (AECB) as the competent body for regulating all aspects of atomic energy. The Act also vests a Minister designated by the Government with research and exploitation functions; thus, by Ministerial order, Atomic Energy of Canada Limited was established in 1952 as a State-owned company. The Nuclear Liability Act, 1970, channels all liability for nuclear damage to the operator of a nuclear installation and requires him to obtain insurance in the amount of $75 million, part of which may be re-insured by the Government. The licensing requirements comprise the issuance of a site approval, a construction licence and an operating licence. The AECB is assisted in its licensing functions by its Nuclear Plant Licensing Directorate and by the Reactor Safety Advisory Committee co-operating with each other in making extensive safety assessments of a licence application. A site evaluation report, a preliminary safety report and a final safety report are required in relation to the siting, construction and operation of a nuclear power plant. The Canadian reactor safety philosophy is based on the concept of defence in depth, implemented through a multi-step approach, which includes avoidance of malfunctions, provision of special safety systems, periodic inspection and testing, and avoidance of human errors. Specific criteria and principles have evolved in applying this basic safety philosophy and radiation protection standards are derived from international recommendations. Stringent control is exercised over the management of radioactive waste and management facilities must meet the engineering and procedural requirements of AECB before they can be placed in operation. (author)

  7. Importance of the licensing process on the safety culture in the Brazilian nuclear fuel cycle facilities

    International Nuclear Information System (INIS)

    Motta, E.S.; Sousa, A.L.B. de; Paiva, R.L.C. de; Mezrahi, A.

    2013-01-01

    The main objective of the Nuclear Fuel Cycle Facilities licensing processes is to ensure the safety of these installations in their entire life cycle (in the installation site selection, designing, construction, pre-operational tests, operational and decommissioning phases). The Brazilian licensing process requires from the operator, among others, before the operating license: (I) a Site Report and a Final Safety Analysis Report, ensuring that all safety related issues are adequately analyzed and understood; (II) a formal structured Management System focused on the installation safety; and (III) dissemination of safety related information to all involved operator employees and subcontractors. Therefore, these requirements reflect in an adequate operator actions and practices, ensuring a working environment with a high level of safety culture. (author)

  8. Importance of the licensing process on the safety culture in the Brazilian nuclear fuel cycle facilities

    Energy Technology Data Exchange (ETDEWEB)

    Motta, E.S.; Sousa, A.L.B. de; Paiva, R.L.C. de; Mezrahi, A., E-mail: emotta@cnen.gov.br [Comissao Nacional de Energia Nuclear (CNEN-RJ), Rio de Janeiro, RJ (Brazil)

    2013-07-01

    The main objective of the Nuclear Fuel Cycle Facilities licensing processes is to ensure the safety of these installations in their entire life cycle (in the installation site selection, designing, construction, pre-operational tests, operational and decommissioning phases). The Brazilian licensing process requires from the operator, among others, before the operating license: (I) a Site Report and a Final Safety Analysis Report, ensuring that all safety related issues are adequately analyzed and understood; (II) a formal structured Management System focused on the installation safety; and (III) dissemination of safety related information to all involved operator employees and subcontractors. Therefore, these requirements reflect in an adequate operator actions and practices, ensuring a working environment with a high level of safety culture. (author)

  9. Postulated licensing schedule for an independent spent-fuel-storage installation

    International Nuclear Information System (INIS)

    Ludwick, J.D.

    1982-11-01

    A review of licensing requirements, processes, and anticipated actions for independent spent fuel storage installations (ISFSIs) was conducted in order to develop an estimated schedule and sequence of events for licensing a new ISFSI. This estimate will be useful to potential ISFSI owners in planning for the licensing of their facilities. It is concluded that, although many uncertainties exist with respect to such things as legal appeals, about 29 months are estimated to elapse between license application and license issuance for an ISFSI. This estimate is in reasonable agreement with a previous time estimate for licensing an ISFSI, and, taking into account the special circumstances involved, with the actual licensing schedule for the GE-Morris ISFSI. However, individual portions of the licensing schedule from each case studied sometimes vary significantly

  10. Siting the high level radioactive waste repository in the United States

    International Nuclear Information System (INIS)

    Tourtellotte, J.

    1992-01-01

    For more than twenty-five years after the National Academy of Science issued its 1957 report recommending a Mined Geologic Disposal System (''MGDS'') for high level radioactive waste, no substantial progress was made in selecting and siting a repository. The United States Congress attempted to give substantive and procedural direction to the program in the Nuclear Waste Policy Act of 1982. Seeing that very little had been accomplished some five years later, Congress gave further direction and tentatively selected a single site, Yucca Mountain in Nevada, in the Nuclear Waste Policy Act Amendments of 1987. Selection of the Yucca Mountain site created a political conflict between federal and state authorities. Until recently, that conflict stalled the site characterization and evaluation program. Standards development under a polycentric regulatory regime has also been slow and has created a number of technical, legal and policy controversies. The Environmental Protection Agency (EPA), charged with setting radiation protection rules, may be developing regulatory standards which are technically unachievable and, therefore, legally unprovable in a licensing proceeding. The Nuclear Regulatory Commission (NRC), having the responsibility for licensing and setting performance objectives, may be taking an overly conservative approach. This approach could seriously impact the cost and may preclude the ability to reach an affirmative finding on license issuance. The Department of Energy (DOE) has responsibility for siting, construction and operation of the repository. In so doing, DOE must apply both EPA and NRC standards. To the extent that EPA and NRC standards are untimely, poorly defined, unrealistic, inconsistent, and technically or legally unsound, DOE may be forestalled from fulfilling its responsibilities. The US must rethink its approach to siting the high level radioactive waste repository and take realistic, timely action to preserve the nuclear option. (Author)

  11. Low-Level Radioactive Waste siting simulation information package

    International Nuclear Information System (INIS)

    1985-12-01

    The Department of Energy's National Low-Level Radioactive Waste Management Program has developed a simulation exercise designed to facilitate the process of siting and licensing disposal facilities for low-level radioactive waste. The siting simulation can be conducted at a workshop or conference, can involve 14-70 participants (or more), and requires approximately eight hours to complete. The exercise is available for use by states, regional compacts, or other organizations for use as part of the planning process for low-level waste disposal facilities. This information package describes the development, content, and use of the Low-Level Radioactive Waste Siting Simulation. Information is provided on how to organize a workshop for conducting the simulation. 1 ref., 1 fig

  12. More than a House of Cards: Developing a Firm Foundation for Streaming Media and Consumer-Licensed Content in the Library

    Directory of Open Access Journals (Sweden)

    William Cross

    2016-09-01

    Full Text Available This article will introduce traditional library practice for licensing multimedia content and discuss the way that consumer-licensing and streaming services disrupt that practice. Sections II and III describe the statutory copyright regime designed by Congress to facilitate the socially-valuable work done by libraries and the impact of the move from ownership to licensed content. Collecting multimedia materials has always presented special legal challenges for libraries, particularly as licensed content has replaced the traditional practice of purchasing and circulation based on the first sale doctrine. These issues have grown even more complex as streaming services like Netflix and Amazon and video game downloads through services like Steam have come to dominate the landscape. Section IV will describe the way that consumer-licensed materials, which not only remove the ownership that undergirds library practice, but also the ability to negotiate for library use, imperil the congressionally-designed balance. Section V will present a path forward for libraries to develop robust, cutting-edge collections that reflect a sophisticated understanding of the contractual and copyright issues at play.

  13. Plans for characterization of salt sites

    International Nuclear Information System (INIS)

    Heim, G.E.; Matthews, S.C.; Kircher, J.F.; Kennedy, R.K.

    1983-01-01

    This basic salt site characterization program has been designed to provide the data required to support the design, performance assessment, and licensing of each of the principal project elements: the repository, the shafts, and the surface facilities. The work has been sequenced to meet the design and licensing schedule. It is anticipated that additional characterization activities will be performed to address site-specific considerations and to provide additional information to address questions which arise during the evaluation of characterization data. 3 figures, 3 tables

  14. A guide to the licensing of uranium and thorium mine and mill waste management systems

    International Nuclear Information System (INIS)

    1986-01-01

    This document is issued to assist industry and the public in understanding the licensing process used by the Canadian Atomic Energy Control Board (AECB), and do describe and consolidate the requirements, criteria and guidelines the AECB uses in the regulation of uranium and thorium mine and mill waste management systems. All phases of these systems are addressed, including pre-development activities, siting and construction, operation, and decommissioning and abandonment

  15. Technical support for the EPA cleanup rule on radioactively contaminated sites

    Energy Technology Data Exchange (ETDEWEB)

    Hull, H.B.; Newman, A.; Wolbarst, A.B. [Environmental Protection Agency, Washington, DC (United States)] [and others

    1995-12-31

    The U.S. Environmental Protection Agency (EPA) is developing a radiation site cleanup regulation for the protection of the public from radionuclide contamination at sites that are to be cleaned up and released for public use. The regulation will apply to sites under the control of Federal agencies, and to sites licensed by the Nuclear Regulatory Commission (NRC) or NRC Agreement States. The agency is therefore conducting a comprehensive technical analysis aimed at developing information that will be used to support the rule. This presentation describes the regulation and the approach developed to determine how radiological health impacts and volumes of soil requiring remediation vary as functions of the possible cleanup dose or risk level.

  16. 10 CFR 72.96 - Siting limitations.

    Science.gov (United States)

    2010-01-01

    ... REGULATORY COMMISSION (CONTINUED) LICENSING REQUIREMENTS FOR THE INDEPENDENT STORAGE OF SPENT NUCLEAR FUEL... site within which there is a candidate site for a HLW repository. This limitation shall apply until such time as DOE decides that such candidate site is no longer a candidate site under consideration for...

  17. Systems engineering and the licensing of Small Modular Reactors

    Energy Technology Data Exchange (ETDEWEB)

    Kulesa, T., E-mail: tkulesa@us.ibm.com [IBM, Philidelphia, Pennsylvania (United States); Soderholm, K., E-mail: Kristiina.Soderholm@fortum.com [Fortum Power (Finland); Fechtelkotter, P., E-mail: pfech@us.ibm.com [IBM, Boston, Massacheusets (United States)

    2014-07-01

    Both global warming and the need for dependable sources of energy continue to make nuclear power generation an appealing option. But a history of cost overruns, project delays, and environmental disaster has pushed the industry to innovate and design a more flexible, scalable, and safe source of nuclear energy - the small modular reactor. Innovation in generation technology creates disruption in already complex licensing and regulatory processes. This paper discusses how the application of systems engineering and requirements management can help combat confusion, rework, and efficiency problems across the engineering and compliance life cycle. The paper is based on the PhD Dissertation 'Licensing Model Development for Small Modular Reactors (SMRs) - Focusing on Finnish Regulatory Framework', approved in 2013. The result of the study gives recommendations and tools to develop and optimize the licensing process for SMRs. The most important SMR-specific feature, in terms of licensing, is the modularity of the design. Here the modularity indicates multi-module SMR designs, which creates new challenges in the licensing process. Another feature impacting licensing feasibility is the plan to build many standardized power plants in series and use factory-fabricated modules to optimize the construction costs. SMR licensing challenges are under discussion in many international forums, such as World Nuclear Association Cooperation in Reactor Design Evaluation and Licensing Small Modular Reactor group (WNA CORDEL SMR) group and IAEA INPRO regulators' forum. This paper also presents an application of the new licensing process using Systems Engineering, Requirements Management, and Project Management practices and tools. (author)

  18. Systems engineering and the licensing of Small Modular Reactors

    International Nuclear Information System (INIS)

    Kulesa, T.; Soderholm, K.; Fechtelkotter, P.

    2014-01-01

    Both global warming and the need for dependable sources of energy continue to make nuclear power generation an appealing option. But a history of cost overruns, project delays, and environmental disaster has pushed the industry to innovate and design a more flexible, scalable, and safe source of nuclear energy - the small modular reactor. Innovation in generation technology creates disruption in already complex licensing and regulatory processes. This paper discusses how the application of systems engineering and requirements management can help combat confusion, rework, and efficiency problems across the engineering and compliance life cycle. The paper is based on the PhD Dissertation 'Licensing Model Development for Small Modular Reactors (SMRs) - Focusing on Finnish Regulatory Framework', approved in 2013. The result of the study gives recommendations and tools to develop and optimize the licensing process for SMRs. The most important SMR-specific feature, in terms of licensing, is the modularity of the design. Here the modularity indicates multi-module SMR designs, which creates new challenges in the licensing process. Another feature impacting licensing feasibility is the plan to build many standardized power plants in series and use factory-fabricated modules to optimize the construction costs. SMR licensing challenges are under discussion in many international forums, such as World Nuclear Association Cooperation in Reactor Design Evaluation and Licensing Small Modular Reactor group (WNA CORDEL SMR) group and IAEA INPRO regulators' forum. This paper also presents an application of the new licensing process using Systems Engineering, Requirements Management, and Project Management practices and tools. (author)

  19. Site Management Guide (Blue Book)

    International Nuclear Information System (INIS)

    2014-01-01

    The U.S. Department of Energy (Department) Office of Legacy Management (LM), established in 2003, manages the Department's postclosure responsibilities and ensures the future protection of human health and the environment. During World War II and the Cold War, the Federal government developed and operated a vast network of industrial facilities for the research, production, and testing of nuclear weapons, as well as other scientific and engineering research. These processes left a legacy of radioactive and chemical waste, environmental contamination, and hazardous facilities and materials at well over 100 sites. Since 1989, the Department has taken an aggressive accelerated cleanup approach to reduce risks and cut costs. At most Departmental sites undergoing cleanup, some residual hazards will remain at the time cleanup is completed due to financial and technical impracticality. However, the Department still has an obligation to protect human health and the environment after cleanup is completed. LM fulfills DOE's postclosure obligation by providing long-term management of postcleanup sites which do not have continuing missions. LM is also responsible for sites under the Formerly Utilized Sites Remedial Action Program (FUSRAP). Currently, the U.S. Army Corps of Engineers (USACE) is responsible for site surveys and remediation at FUSRAP sites. Once remediation is completed, LM becomes responsible for long-term management. LM also has responsibility for uranium processing sites addressed by Title II of the Uranium Mill Tailings Radiation Control Act (UMTRCA). UMTRCA Title II sites are sites that were commercially owned and are regulated under a U.S. Nuclear Regulatory Commission (NRC) license. For license termination, the owner must conduct an NRC-approved cleanup of any on-site radioactive waste remaining from former uranium ore-processing operations. The site owner must also provide full funding for inspections and, if necessary, ongoing maintenance. Once site

  20. Libraries and licensing

    Directory of Open Access Journals (Sweden)

    Maja Žumer

    2001-01-01

    Full Text Available In the mid 90s, the abundance of various electronic publications exposed libraries to the problems of licensing electronic content. Various licensing principles have been prepared recently to help libraries in the process; it can be said that in general, the knowledge of licensing issues has improved in libraries of all types. Libraries form consortia in order to gain stronger negotiating positions and obtain better conditions.In the article, new licensing principles are presented in more detail, as well as some domestic and foreign experiences with consortia forming.

  1. Simulator training and licensing examination for nuclear power station operator

    International Nuclear Information System (INIS)

    Xu Pingsheng

    2007-01-01

    For the recruitment, training and position qualification of the simulator instructors and feedback of training effect, the management approaches are formulated in 'The System for Simulator Training and Licensing Examination of Daya Bay Nuclear Power Station Operators'. The concrete requirements on the professional knowledge, work experience and foreign language ability of a simulator instructor are put forward. The process of instructor training is designed. The training items include the trainer training, pedagogy training, time management training, operation activities training during outage of unit, 'shadow' training and on-the-jot training on simulator courses. Job rotation is realized between simulator instructor and licensing personnel on site. New simulator instructor must pass the qualification identification. After a duration of 2 years, re-qualification has to be carried out. On the basis of the operator training method introduced from EDF (electricite De France), some new courses are developed and the improvement on the initial training, retaining courses, the technical support and the experience feedback by using the simulator is done also. (authors)

  2. Siting Process for HLW Repository in Japan

    International Nuclear Information System (INIS)

    Masuda, S.; Kitayama, K.; Umeki, H.; Naito, M.

    2002-01-01

    In the year 2000, the geological disposal program for high-level radioactive waste in Japan moved from the phase of generic research and development (R and D) into the phase of implementation. Following legislation entitled the ''Specified Radioactive Waste Final Disposal Act'', the Nuclear Waste Management Organization of Japan (NUMO) was established as the implementing organization. The assigned activities of NUMO include selection of the repository site, demonstration of disposal technology at the site, developing relevant licensing applications and construction, operation and closure of the repository. As the first milestone of siting process, NUMO announced to the public an overall procedure for selection of preliminary investigation areas for potential candidate sites on October 29, 2001. The procedure specifies that NUMO will solicit volunteer municipalities for preliminary investigation areas with publishing four documents as an information package. These documents are tentatively entitled ''Instructions for Application'', ''Siting Factors for the Preliminary Investigation Areas'', a ''Repository Concepts'' as well as an ''Site Investigation Community Outreach Scheme''

  3. Why trash don't pass? pharmaceutical licensing and safety performance of drugs.

    Science.gov (United States)

    Banerjee, Tannista; Nayak, Arnab

    2017-01-01

    This paper examines how asymmetric information in pharmaceutical licensing affects the safety standards of licensed drugs. Pharmaceutical companies often license potential drug molecules at different stages of drug development from other pharmaceutical or biotechnology companies and complete the remaining of research stages before submitting the new drug application(NDA) to the food and drug administration. The asymmetric information associated with the quality of licensed molecules might result in the molecules which are less likely to succeed to be licensed out, while those with greater potential of success being held internally for development. We identify the NDAs submitted between 1993 and 2004 where new molecular entities were acquired through licensing. Controlling for other drug area specific and applicant firm specific factors, we investigate whether drugs developed with licensed molecules face higher probability of safety based recall and ultimate withdrawal from the market than drugs developed internally. Results suggest the opposite of Akerlof's (Q J Econ 84:488-500, 1970) lemons problem. Licensed molecules rather have less probability of facing safety based recalls and ultimate withdrawal from the market comparing to internally developed drug molecules. This suggests that biotechnology and small pharmaceutical firms specializing in pharmaceutical research are more efficient in developing good potential molecules because of their concentrated research. Biotechnology firms license out good potential molecules because it increases their market value and reputation. In addition, results suggest that both the number of previous approved drugs in the disease area, and also the applicant firms' total number of previous approvals in all disease areas reduce the probability that an additional approved drug in the same drug area will potentially be harmful.

  4. Technology Licensing Strategy for Network Product in a Service Industry

    Directory of Open Access Journals (Sweden)

    Xianpei Hong

    2015-01-01

    Full Text Available Technology licensing has gained significant attention in literature and practice as a rapid and effective way to improve firm’s capability of technology innovation. In this paper, we investigate a duopolistic service provider competition market, where service providers develop and sell a kind of network product. In this setting, we analyze the innovating service provider’s four licensing strategies: no licensing, fixed fee licensing, royalty licensing, and two-part tariff licensing. The literature suggests that when the network products can be completely substituted, two-part tariff licensing is the optimal strategy of the innovating service provider. We find that when the network products cannot be completely substituted, two-part tariff licensing is not always optimal. The degree of the product differentiation, the intensity of the network effects, and the R&D cost of the potential licensee play a key role in determining the innovating service provider’s optimal licensing strategies.

  5. Methodology to identify, review, and evaluate components for license renewal

    International Nuclear Information System (INIS)

    Carlson, D.D.; Gregor, F.E.; Walker, R.S.

    1988-01-01

    A methodology has been developed to systematically identify, review, and evaluate plant equipment for license renewal. The method builds upon the existing licensing basis, operating history, and accepted deterministic and probabilistic techniques. Use of these approaches provides a focus for license renewal upon those safety-significant systems and components that are not routinely replaced, refurbished, or subject to detailed inspection as part of the plant's existing test, maintenance, and surveillance programs. Application of the method identified the PWR and BWR systems that should be subjected to detailed license renewal review. Detailed examination of two example systems demonstrates the approach. The review and evaluation of plant equipment for license renewal differ from the initial licensing of the plant. A substantial operating history has been established, the licensing basis has evolved from the original one, and plant equipment has been subject to periodic maintenance and surveillance throughout its life. In consideration of these differences, a basis for license renewal is needed. License renewal should be based upon continuation of the existing licensing basis and recognition of existing programs and operating history

  6. The Atomic Energy Control Board requirements for the radioisotope licensing of a radiopharmaceutical facility

    International Nuclear Information System (INIS)

    Kennedy, P.

    1980-01-01

    Items that must be addressed by an applicant for a radioisotope license in Canada are described. Site, design and operating conditions, safety assessment, organization, emergency procedures and operating policies and procedures must be described to the Atomic Energy Control Board (AECB), in support of any license application. All information submitted in support of the application is subject to AECB's policy on public access to that information. (OT)

  7. Reactor licensing

    International Nuclear Information System (INIS)

    Harvie, J.D.

    2002-01-01

    This presentation discusses reactor licensing and includes the legislative basis for licensing, other relevant legislation , the purpose of the Nuclear Safety and Control Act, important regulations, regulatory document, policies, and standards. It also discusses the role of the CNSC, its mandate and safety philosophy

  8. 47 CFR 90.751 - Minor modifications of Phase I, non-nationwide licenses.

    Science.gov (United States)

    2010-10-01

    ... SPECIAL RADIO SERVICES PRIVATE LAND MOBILE RADIO SERVICES Regulations Governing Licensing and Use of... relocate their initially authorized base station, i.e., locate their base station at a site other than its...

  9. Approach to resolution of geologic uncertainty in the licensing of a high-level-waste repository in tuff

    International Nuclear Information System (INIS)

    Neal, J.T.

    1983-01-01

    Resolution of uncertainty in geological information is an essential element in the licensing process for a geologic repository. Evaluation of these uncertainties within the licensing framework established by the Nuclear Regulatory Commission (NRC) is required. The Nevada Nuclear Waste Storage Investigations (NNWSI), in focusing its site characterization program on unsaturated tuff, has developed a logic hierarchy of technical issues, including key issues, issues, and information needs. Key issues are statements of major requirements whose lack could be disqualifying. An example of a key issue is the demonstration of radionuclide containment and isolation within the required release limits and transport time set by the EPA and NRC. Key issues are broken down into issues, such as the groundwater flow time to the accessible environment. Resolving uncertainty ultimately comes back to satisfying individual information needs that collectively form issues. Hydraulic conductivity is an example of an information need required to determine groundwater flow rate. Sources of uncertainty often arise in either amount, quality, or other limitations in geological data. The hierarchical structuring of geological information needs provides a perspective that allows proportionate attention to be placed on various site characterization activities, and to view them within the whole range of licensing issues that must be satisfied to ensure public health and safety. However, it may not prevent an issue from being contentious, as some geological questions are known to be emotion-laden. The mitigation of uncertainty in geological information ultimately will depend on the validity and credibility of the information presented during the licensing process

  10. Introduction to Technology Export License of Nuclear Facility

    Energy Technology Data Exchange (ETDEWEB)

    Seo, Hana; Lee, Chansuh; Shin, Donghoon [Korea Institute of Nuclear Nonproliferation and Control, Daejeon (Korea, Republic of)

    2014-05-15

    In this regime, the Nuclear Safety and Security Commission (NSSC) has authority on final decision making. And the Korea Institute of Nuclear nonproliferation and Control (KINAC) has missions to review the classification and export licensing technically. In principle, classification and export licensing are applied and reviewed individually. However, the number of application for classification and licensing has increased geometrically in the last three years. This is largely a due to the contract that the Republic of Korea (ROK) has finalized to build the UAE Barakah Nuclear Power Plant (BNPP) and Jordan Research and Training Reactor (JRTR). This circumstance brought an administrative burden for the government and related institutes as well as stakeholders. This article introduces the law related to the 'Technology Export License of Nuclear Facility' which was developed and legislated to improve the efficiency and effectiveness of commodities classification and export licensing. This system could significantly reduce the licensing burden for transferring the technologies. However, the classification and license on this system are still requested when transferring the goods. Therefore, KINAC will continue to figure out the needs for the stakeholders and keep searching for solutions to problems inherent in the industry.

  11. Introduction to Technology Export License of Nuclear Facility

    International Nuclear Information System (INIS)

    Seo, Hana; Lee, Chansuh; Shin, Donghoon

    2014-01-01

    In this regime, the Nuclear Safety and Security Commission (NSSC) has authority on final decision making. And the Korea Institute of Nuclear nonproliferation and Control (KINAC) has missions to review the classification and export licensing technically. In principle, classification and export licensing are applied and reviewed individually. However, the number of application for classification and licensing has increased geometrically in the last three years. This is largely a due to the contract that the Republic of Korea (ROK) has finalized to build the UAE Barakah Nuclear Power Plant (BNPP) and Jordan Research and Training Reactor (JRTR). This circumstance brought an administrative burden for the government and related institutes as well as stakeholders. This article introduces the law related to the 'Technology Export License of Nuclear Facility' which was developed and legislated to improve the efficiency and effectiveness of commodities classification and export licensing. This system could significantly reduce the licensing burden for transferring the technologies. However, the classification and license on this system are still requested when transferring the goods. Therefore, KINAC will continue to figure out the needs for the stakeholders and keep searching for solutions to problems inherent in the industry

  12. 77 FR 3482 - Prospective Grant of Exclusive License: Development of T Cell Receptors and Chimeric Antigen...

    Science.gov (United States)

    2012-01-24

    ... Exclusive License: Development of T Cell Receptors and Chimeric Antigen Receptors Into Therapeutics for.... 61/473,409 entitled ``Anti-epidermal growth factor receptor variant III chimeric antigen receptors... EGFRvIII chimeric antigen (CARs) and methods of using these engineered T cells to treat and/or prevent...

  13. Intervention in independent spent fuel storage facility license application proceedings for storage on the power plant site

    International Nuclear Information System (INIS)

    Jordan, J.

    1992-01-01

    This presentation summarizes the intervention in the Nuclear Regulatory Commission (NRC) licensing process for currently operating Independent Spent fuel Storage Installation (ISFSI) projects at Carolina Power and Light's Company's H.B. Robinson, Duke Power Company's Oconee, and Virginia Power Company's Surry. In addition, intervention at dry storage facilities that are currently under development are also described. The utilities and reactors include Baltimore Gas and Electric Company's Calvert Cliffs, Public Service Company of Colorado's Fort St. Vrain plant, Northern States Power Company's Prairie Island, Wisconsin Electric Power Company's Point Beach, and Consumers Power Company's Palisades

  14. 78 FR 20671 - Prospective Grant of A Start-Up Commercialization Exclusive License: The Development of Fenoterol...

    Science.gov (United States)

    2013-04-05

    ... Brain and Hepatocellular Cancers AGENCY: National Institutes of Health, HHS. ACTION: Notice. SUMMARY..., and use in humans for the treatment of brain cancer or hepatocellular cancer within the Licensed... contemplated exclusive commercialization license should be directed to: Patrick McCue, Ph.D., Licensing and...

  15. Nuclear reactor operator licensing

    International Nuclear Information System (INIS)

    Bursey, R.J.

    1978-01-01

    The Atomic Energy Act of 1954, which was amended in 1974 by the Energy Reorganization Act, established the requirement that individuals who had the responsibility of operating the reactors in nuclear power plants must be licensed. Section 107 of the act states ''the Commission shall (1) prescribe uniform conditions for licensing individuals; (2) determine the qualifications of such individuals; and (3) issue licenses to such individuals in such form as the Commission may prescribe.'' The article discusses the types of licenses, the selection and training of individuals, and the administration of the Nuclear Regulatory Commission licensing examinations

  16. Operator licensing examiner standards

    International Nuclear Information System (INIS)

    1987-05-01

    The Operator Licensing Examiner Standards provide policy and guidance to NRC examiners and establish the procedures and practices for examining and licensing of applicants for NRC operator licenses pursuant to Part 55 of Title 10 of the Code of Federal Regulations (10 CFR 55). They are intended to assist NRC examiners and facility licensees to understand the examination process better and to provide for equitable and consistent administration of examinations to all applicants by NRC examiners. These standards are not a substitute for the operator licensing regulations and are subject to revision or other internal operator examination licensing policy changes

  17. Soil characterization methods for unsaturated low-level waste sites

    International Nuclear Information System (INIS)

    Wierenga, P.J.; Young, M.H.; Hills, R.G.

    1993-01-01

    To support a license application for the disposal of low-level radioactive waste (LLW), applicants must characterize the unsaturated zone and demonstrate that waste will not migrate from the facility boundary. This document provides a strategy for developing this characterization plan. It describes principles of contaminant flow and transport, site characterization and monitoring strategies, and data management. It also discusses methods and practices that are currently used to monitor properties and conditions in the soil profile, how these properties influence water and waste migration, and why they are important to the license application. The methods part of the document is divided into sections on laboratory and field-based properties, then further subdivided into the description of methods for determining 18 physical, flow, and transport properties. Because of the availability of detailed procedures in many texts and journal articles, the reader is often directed for details to the available literature. References are made to experiments performed at the Las Cruces Trench site, New Mexico, that support LLW site characterization activities. A major contribution from the Las Cruces study is the experience gained in handling data sets for site characterization and the subsequent use of these data sets in modeling studies

  18. Licensing in an international triopoly

    Science.gov (United States)

    Ferreira, Fernanda A.; Ferreira, Flávio

    2011-12-01

    We study the effects of entry of two foreign firms on domestic welfare in the presence of licensing, when the incumbent is technologically superior to the entrants. We consider two different situations: (i) the cost-reducing innovation is licensed to both entrants; (ii) the cost-reducing innovation is licensed to just one of the entrants. We analyse three kind of license: (lump-sum) fixed-fee; (per-unit) royalty; and two-part tariff, that is a combination of a fixed-fee and a royalty. We prove that a two part tariff is never an optimal licensing scheme for the incumbent. Moreover, (i) when the technology is licensed to the two entrants, the optimal contract consists of a licensing with only output royalty; and (ii) when the technology is licensed to just one of the entrants, the optimal contract consists of a licensing with only a fixed-fee.

  19. Development and application of a deterministic-realistic hybrid methodology for LOCA licensing analysis

    International Nuclear Information System (INIS)

    Liang, Thomas K.S.; Chou, Ling-Yao; Zhang, Zhongwei; Hsueh, Hsiang-Yu; Lee, Min

    2011-01-01

    Highlights: → A new LOCA licensing methodology (DRHM, deterministic-realistic hybrid methodology) was developed. → DRHM involves conservative Appendix K physical models and statistical treatment of plant status uncertainties. → DRHM can generate 50-100 K PCT margin as compared to a traditional Appendix K methodology. - Abstract: It is well recognized that a realistic LOCA analysis with uncertainty quantification can generate greater safety margin as compared with classical conservative LOCA analysis using Appendix K evaluation models. The associated margin can be more than 200 K. To quantify uncertainty in BELOCA analysis, generally there are two kinds of uncertainties required to be identified and quantified, which involve model uncertainties and plant status uncertainties. Particularly, it will take huge effort to systematically quantify individual model uncertainty of a best estimate LOCA code, such as RELAP5 and TRAC. Instead of applying a full ranged BELOCA methodology to cover both model and plant status uncertainties, a deterministic-realistic hybrid methodology (DRHM) was developed to support LOCA licensing analysis. Regarding the DRHM methodology, Appendix K deterministic evaluation models are adopted to ensure model conservatism, while CSAU methodology is applied to quantify the effect of plant status uncertainty on PCT calculation. Generally, DRHM methodology can generate about 80-100 K margin on PCT as compared to Appendix K bounding state LOCA analysis.

  20. 14 CFR 431.73 - Continuing accuracy of license application; application for modification of license.

    Science.gov (United States)

    2010-01-01

    ... 14 Aeronautics and Space 4 2010-01-01 2010-01-01 false Continuing accuracy of license application; application for modification of license. 431.73 Section 431.73 Aeronautics and Space COMMERCIAL SPACE... Conditions § 431.73 Continuing accuracy of license application; application for modification of license. (a...

  1. Essays on the economics of licensing nuclear power plants

    International Nuclear Information System (INIS)

    Cohen, L.R.

    1979-01-01

    Regulation and licensing of nuclear power plants by the United States Atomic Energy Commission and the United States Nuclear Regulatory Commission are discussed. Chapter 1 overviews the licensing process and issues raised in licensing cases. Based on a sample of plants licensed between 1967 and 1978, a statistical study of the impact of public participation in licensing is performed. The study concludes that public participation has had a major impact on licensing and power-plant costs. The impact is due to a fundamental weakness of the Commissions: their inability to resolve certain issues related to acceptable social risk. The study has important policy implications for reforming the Federal licensing process. Chapter 2 contains an analysis of the Price-Anderson Act, a Federal program for compensating victims of large nuclear accidents. The Price-Anderson Act is placed within the context of generalized federal disaster relief. A model is developed that allows an evaluation programs on the basis of moral hazard and equity principles. Chapter 3 analyzes the Nuclear Regulatory Commission's treatment of its mandatory antitrust review of applicants for nuclear power plants. The main conclusion of the chapter is that the reviews have not addressed the central economic issues of antitrust that are relevant to nuclear power. Instead, the reviews contribute to further cartelization of the electric utility industry. While politically expedient, the reviews are counter-productive to the development of an optimal industry structure

  2. Licensed Healthcare Facilities

    Data.gov (United States)

    California Natural Resource Agency — The Licensed Healthcare Facilities point layer represents the locations of all healthcare facilities licensed by the State of California, Department of Health...

  3. Site selection: Past and present

    International Nuclear Information System (INIS)

    Tilford, N.R.

    1994-01-01

    Site selection has been going on since the earliest times. The process has evolved through the Industrial Revolution to the present period of exploding population and environmental awareness. Now the work must be done both with increasing sophistication and greater transparency. Modern techniques for site selection have been developed during the last two decades or so, utilizing a teachable body of knowledge and a growing literature. Many firms and individuals have contributed to this growing field. The driving force has been the need for such a process in siting and licensing of critical facilities such as nuclear power plants. A list of crucial, documented steps for identifying social impacts and acceptability are provided. A recent innovation is the self-selection method developed by government. The Superconducting Supercollider serves as an example of this approach. Geological or geologically dependent factors often dominate the process. The role as engineering and environmental geoscientists is to provide responsible leadership, consultation, and communication to the effort

  4. Department of Energy interest and involvement in nuclear plant license renewal activities

    International Nuclear Information System (INIS)

    Bustard, Larry D.; Harrison, Dennis L.

    1991-01-01

    Recognizing the importance of nuclear license renewal to the nation's energy strategy, the Department of Energy (DOE) initiated a plant lifetime improvement program during 1985 to determine the feasibility of the license renewal option for US nuclear plants. Initial activities of the DOE program focused on determining whether there were technical and economic obstacles that might preclude or limit the successful implementation of the license renewal option. To make this determination, DOE co-sponsored with the Electric Power Research Institute (EPRI) 'pilot-plant' efforts by Virginia Electric Power and Northern States Power. Both pilot-plant efforts concluded that life extension is technically and economically feasible. In parallel with the pilot plant activities, DOE performed national economic studies that demonstrated the economic desirability of life extension. Having demonstrated the feasibility of life extension, DOE, in conjunction with EPRI, selected two lead plants to demonstrate the license renewal process. These lead plants are Yankees Atomic's Yankee Rowe facility and Northern States Power's Monticello facility. DOE also initiated activities to develop the technical and regulatory bases to support the license renewal process in the United States. These include (1) development of a methodology for identifying systems, structures, and components important to license renewal, (2) development of industry reports that describe industry-accepted approaches for license renewal of ten important classes of equipment, (3) development of technical basis to support license renewal, and (4) interaction/negotiation with the NRC through the Nuclear Management Resources Council (NUMARC) regarding appropriate regulatory requirements for license renewal. DOE has recently identified nuclear plant license renewal to be an important element of its National Energy Strategy. This paper summarizes the significant results, conclusions and ongoing activities of the DOE effort

  5. Summary of NRR future licensing activities

    International Nuclear Information System (INIS)

    2001-01-01

    In response to a renewed interest in building nuclear power plants, the NRC has created organizations within its major program offices to prepare the NRC staff for new applications (early site permits [ESPs], design certifications, and combined licenses) and to manage special task groups and pro-application reviews of new reactor designs. Activities planned in FY2001 and FY2002 include: (1) evaluating the ability of the NRC staff to support future application reviews under 10 CFR Parts 50 and 52; (2) performing pre-application reviews of the API 000 (a light-water reactor design with passive safety systems), Pebble Bed Modular Reactor (PBMR - a high-temperature gas-cooled reactor design), ESPs, IRIS (an advanced light-water reactor design), and GT-MHR (a high-temperature gas-cooled reactor design); (3) initiating and/or performing related rulemakings that will update 10 CPR Part 52 to reflect lessons learned from certifying three nuclear plant designs, update Tables S-3 and S-4 of 10 CFR Part 51 to address higher burnup fuel considerations and non-LWR advanced designs, and address alternative siting considerations; (4) reactivating the construction inspection program; and, (5) interacting with stakeholders to ensure there is a clear understanding of upcoming activities related to future applications and to solicit stakeholder input. In FY2002 and FY200S, activities are expected to include: (1) managing the reviews of fine new applications resulting from the pre-application reviews (including one design certification, one combined license, and three ESP reviews); (2) managing two pre-application reviews (IRIS and QT-MHR); (3) updating regulatory and review guidance for new applications, i.e., Standard Review Plans (SRPs), Regulatory Guides, and referenced codes and standards, and identifying where enhancements are needed; (4) developing independent codes to analyze the safety of non-LWR designs, with supporting validation testing; and, (5) addressing regulatory

  6. Licensing and Environmental Issues of Wave Energy Projects

    DEFF Research Database (Denmark)

    Neumann, Frank; Tedd, James; Prado, Miguel

    2006-01-01

    a special standing or facilitated access to operating licenses due to their experimental character, the move of wave energy projects towards commercial applications implies complex procedures for obtaining licenses both with respect to the construction and deployment and operation phases, as well......The major non-technical barrier for large-scale wave energy implementation is the wide range of licensing issues and potential environmental concerns, in addition to significant National/regional differences in licensing procedures and permit requirements. Whereas some pilot plants have had...... as concerning ocean space use and environmental concerns. Despite recent efforts to streamline European EIA (Environmental Impact Assessment) in general, potential project developers are far from having a clear view of present and future requirements concerning these barriers on a trans-national level...

  7. 2015 Business Licenses

    Data.gov (United States)

    City of Jackson, Mississippi — This data displays all business license information for the year of 2015. This information details license classifications and status. This information will updated...

  8. 77 FR 62521 - Prospective Grant of Exclusive License: The Development of Therapeutic Agents for the Treatment...

    Science.gov (United States)

    2012-10-15

    ... interleukin-10 (IL-10) inhibitor as a dual-biologic therapy to treat metastatic breast cancer, or ii) incorporating a p53 isoform antisense oligonucleotide as a single biologic therapy to treat T- cell lymphoma... Exclusive License: The Development of Therapeutic Agents for the Treatment of Metastatic Breast Cancer and T...

  9. Teenagers' licensing decisions and their views of licensing policies: a national survey.

    Science.gov (United States)

    Williams, Allan F

    2011-08-01

    One objective was to determine teenage licensing rates on a national basis, interest in early licensure, and reasons for delay. A second objective was to learn teenagers' opinions about licensing policies, important in states considering ways to upgrade their current licensing systems. One thousand three hundred eighty-three 15- to 18-year-olds completed an online survey in November 2010. They were drawn from a nationally representative panel of US households recruited using probability-based sampling. The panel included cell phone-only households, and Internet access was provided to those without it. Weighting procedures were applied so that the study population represented the national US population of 15- to 18-year-olds. Most teens said that they were interested in getting a license as soon as legally possible, but many had not started the process. At 16, teens were about equally divided among those who had not started, those in the learner stage, and those with a restricted or full license. At 18, 62 percent had full licenses; 22 percent had not started. For those old enough to start, lack of a car, costs, parent availability, ability to get around without a car, and being busy with other activities were leading reasons for delay. The majority of teens were not in favor of higher licensing ages. Forty-six percent thought the minimum learner age should be 16; 30 percent thought the full license age should be 18 or older. The majority approved of night (78%) and passenger (57%) restrictions, and 85 and 93 percent endorsed cell phone and texting bans, respectively. When these policies were packaged together in a single law that included an age 16 start, night, passenger, cell phone and texting bans, and a full license at age 18, 74 percent of teens were in favor. Teenagers are not as supportive of strong licensing policies as parents of teens, but there is evidence that they will support comprehensive policies likely to lead to further reductions in teen crash

  10. Radiopharmaceutical licensing

    International Nuclear Information System (INIS)

    Mather, S.J.

    1992-01-01

    Recent health service legislation, and especially the loss of crown immunity has once again focussed attention on the arrangements for licensing of radiopharmaceuticals. The aim of the article is to describe in general terms the UK licensing system and in particular to provide guidance to those responsible for the supply of radiopharmaceuticals in hospitals. (author)

  11. Licensing and Operations of the Clive, Utah Low-Level Containerized Radioactive Waste Disposal Facility- A Continuation of Excellence

    International Nuclear Information System (INIS)

    Ledoux, M. R.; Cade, M. S.

    2002-01-01

    Envirocare's Containerized Waste Facility (CWF) is the first commercial low-level radioactive waste disposal facility to be licensed in the 21st century and the first new site to be opened and operated since the late 1970's. The licensing of this facility has been the culmination of over a decade's effort by Envirocare of Utah at their Clive, Utah site. With the authorization to receive and dispose of higher activity containerized Class A low-level radioactive waste (LLRW), this facility has provided critical access to disposal for the nuclear power industry, as well as the related research and medical communities. This paper chronicles the licensing history and operational efforts designed to address the disposal of containerized LLRW in accordance with state and federal regulations

  12. Integrated ground-water monitoring strategy for NRC-licensed facilities and sites: Case study applications

    Science.gov (United States)

    Price, V.; Temples, T.; Hodges, R.; Dai, Z.; Watkins, D.; Imrich, J.

    2007-01-01

    This document discusses results of applying the Integrated Ground-Water Monitoring Strategy (the Strategy) to actual waste sites using existing field characterization and monitoring data. The Strategy is a systematic approach to dealing with complex sites. Application of such a systematic approach will reduce uncertainty associated with site analysis, and therefore uncertainty associated with management decisions about a site. The Strategy can be used to guide the development of a ground-water monitoring program or to review an existing one. The sites selected for study fall within a wide range of geologic and climatic settings, waste compositions, and site design characteristics and represent realistic cases that might be encountered by the NRC. No one case study illustrates a comprehensive application of the Strategy using all available site data. Rather, within each case study we focus on certain aspects of the Strategy, to illustrate concepts that can be applied generically to all sites. The test sites selected include:Charleston, South Carolina, Naval Weapons Station,Brookhaven National Laboratory on Long Island, New York,The USGS Amargosa Desert Research Site in Nevada,Rocky Flats in Colorado,C-Area at the Savannah River Site in South Carolina, andThe Hanford 300 Area.A Data Analysis section provides examples of detailed data analysis of monitoring data.

  13. Norwegian-developed carbon dioxide technology licensed to Japan

    International Nuclear Information System (INIS)

    Pettersen, Jostein

    2000-01-01

    In the late 1980s, restrictions on the use of ozone-depleting substances created increased interest in alternative working fluids in refrigerators and heat pumps. Carbon dioxide (CO2) is an incombustible, non-toxic and not ozone-depleting natural substance with low specific greenhouse effect. However, CO2 has some unusual thermodynamic properties. Thus, the pressure of a CO2 based system must be high, up to 150 bar, which means that new equipment must be developed. Research at SINTEF and the Technical University in Trondheim, Norway, in 1988-89 resulted in several patents which have later been commercialized and internationally licensed. The most important developments have been in air conditioning for cars, heat pumps for hot water and refrigeration systems for supermarkets. In Japan, a heat pump for hot water has been developed under licence. This is a 4.5 kW heat pump designed for use in detached houses and larger flats. One of the advantages of CO2 is that a high water temperature (70-90 C ) is obtained. The hot water container can then be made quite small. The heat pump is marketed by Tokyo Electric Power Company, which during the night has surplus power that can be sold for less than 25% of the daytime tariff. Compared with gas-fired water heaters, the consumption of primary energy is reduced by 30-50%. This is an important contribution to more efficient use of fossil fuel. Using CO2 also avoids the risk of fire and explosion that exists in the use of gas-fired water heaters

  14. Licensing of the Ignalina NPP

    International Nuclear Information System (INIS)

    Kutas, S.

    1999-01-01

    Since 1991 State Nuclear Power Safety Inspectorate (VATESI) has regulated Ignalina NPP operation by issuing annual operating permits. Those have been issued following submission of specified documents by the Ignalina NPP that have been reviewed by VATESI. However, according to to the procedures that are now established in the Law on Nuclear Energy and subordinate regulations the use of nuclear energy in the Republic of Lithuania is subject to strict licensing. Therefore a decision about the licence for continued operation of unit 1 should be taken. Licence would be granted by VATESI in cooperation with the Ministry of Health, Ministry of Environment and the institutions of local authorities. Ignalina NPP presented to the VATESI safety analysis report (SAR) with other documents. SAR was made mainly by foreign experts and financed by European Bank for Reconstruction and Development (EBRD). VATESI in this process is supported by western regulators. A special project LAP - Licensing Assistance Project was launched to help VATESI perform licensing according western practices

  15. State Licenses & Permits

    Data.gov (United States)

    Small Business Administration — Starting a business? Confused about whether you need a business license or permit? Virtually every business needs some form of license or permit to operate legally....

  16. Operator licensing examiner standards

    International Nuclear Information System (INIS)

    1983-10-01

    The Operator Licensing Examiner Standards provide policy and guidance to NRC examiners and establish the procedures and practices for examining and licensing of applicants for NRC operator licenses pursuant to Part 55 of Title 10 of the Code of Federal Regulations (10 CFR 55). They are intended to assist NRC examiners and facility licensees to understand the examination process better and to provide for equitable and consistent administration of examinations to all applicants by NRC examiners. These standards are not a substitute for the operator licensing regulations and are subject to revision or other internal operator examination licensing policy changes. As appropriate, these standards will be revised periodically to accommodate comments and reflect new information or experience

  17. License to build

    International Nuclear Information System (INIS)

    Huntelaar, Mark; Vos, Renate de; Roobol, Lars

    2007-01-01

    Full text: A new license under the nuclear power act is applied for at the Dutch Government for the building of a High Active Repackaging Unit (HAVA-VU in Dutch) at NRG in Petten, The Netherlands. This new building is necessary to comply with our nuclear license to dispose of high active nuclear waste at Petten to the intermediate storage facility (COVRA). In the first part of this paper attention is given to the formal procedure followed by the Government, what type of documents are to be submitted, what time frames are followed, how citizen participation is organized, and as final result a new license. In the second part more detailed information is given about the present license renewal needed for the High Active Repackaging Unit

  18. Performance of a radioactive waste internment site

    International Nuclear Information System (INIS)

    Bernhardt, D.E.; Owen, D.H.; Mishub, R.J.; Prewett, S.V.; Cole, L.W.

    1990-01-01

    Aerojet disposed of 30,000 cubic meters of uranium and thorium wastes in an engineered 12,000 square meter (3 acre) internment site in Tennessee. The operation, performed under a State of Tennessee source material license, is based on termination of the license with the material remaining in place, and the option of future commercial use of the site. The closure plan included a long-term monitoring program. Yearly monitoring of the site has verified performance within the design criteria. Full-time construction monitored by a licensed engineer and extensive testing of materials ensured construction of the site according to or better than the specifications. Surface subsidence of the site has averaged about 2.2 cm with a range of 0 to 4.3 cm at 11 settlement markers after 4 years. The anticipated settlement, based on design parameters, was between 15 and 25 cm. The present anticipated settlement is 8 to 15 cm, based on the as-built parameters, and the long-term monitoring results. Slope stability analysis indicates the stability has improved with time due to consolidation of materials and reduced groundwater activity as a result of site construction. There has been no need for corrective action maintenance due to erosion, sluffing of slopes, or subsidence. Groundwater monitoring indicates the materials have been isolated, and there have also been no indications of springs or leakage from the site. 9 refs., 2 figs., 3 tabs

  19. 77 FR 58590 - Determining Technical Adequacy of Probabilistic Risk Assessment for Risk-Informed License...

    Science.gov (United States)

    2012-09-21

    ... reactors or for activities associated with review of applications for early site permits and combined licenses (COL) for the Office of New Reactors (NRO). DATES: The effective date of this SRP update is... Rulemaking Web Site: Go to http://www.regulations.gov and search for Docket ID NRC-2010-0138. Address...

  20. 77 FR 9678 - Prospective Grant of Exclusive License: The Development of Human Anti-CD22 Monoclonal Antibodies...

    Science.gov (United States)

    2012-02-17

    .../patent applications for the technology family, to Sanomab, Ltd. The patent rights in these inventions... DEPARTMENT OF HEALTH AND HUMAN SERVICES National Institutes of Health Prospective Grant of Exclusive License: The Development of Human Anti-CD22 Monoclonal Antibodies for the Treatment of Human...

  1. 77 FR 41792 - Prospective Grant of Co-Exclusive License: The Development of Human Anti-CD22 Monoclonal...

    Science.gov (United States)

    2012-07-16

    ... applications for the technology family, to Customized Therapeutics. The patent rights in these inventions have... DEPARTMENT OF HEALTH AND HUMAN SERVICES National Institutes of Health Prospective Grant of Co-Exclusive License: The Development of Human Anti-CD22 Monoclonal Antibodies for the Treatment of Human...

  2. Advanced CANDU reactor pre-licensing progress

    International Nuclear Information System (INIS)

    Popov, N.K.; West, J.; Snell, V.G.; Ion, R.; Archinoff, G.; Xu, C.

    2005-01-01

    with Chinese regulatory requirements. To facilitate the review, AECL, CNSC and NSC agreed that 14 Chinese experts will sequentially visit the CNSC for familiarization with the CNSC pre-licensing review, and the ACR-700 and ACR-1000 design. The ACR pre-application review by NSC will utilize the experience in successfully licensing two CANDU 6 units at the Qinshan site in China in 2002. (author)

  3. The Reactor Analysis Support Package (RASP): Volume 10, Guidelines for developing a reload licensing capability:Final report

    International Nuclear Information System (INIS)

    Diamond, D.J.

    1988-08-01

    The EPRI Reactor Analysis Support Package (RASP) consists of computer codes and documentation for calculating core performance and plant transients. This report was written to help a utility to use these tools properly for reload design and safety evaluations. The emphasis is on the steps that the utility can take to develop a methodology that is approved by the Nuclear Regulatory Commission for reload licensing submittals. The report treats both the planning and the implementation of this type of calculational capability. With regard to planning, there is discussion defining objectives, resource requirements, organization and scheduling. In order to help the engineering staff implement the plan there is discussion of the development of a methodology for event analysis, qualification of the methods, and the writing of design control procedures and topical reports. The experience of utilities, and especially of GPU Nuclear Corporation (GPUN), in developing a reload licensing capability is cited throughout the report and extracts from GPUN design control procedures are included in the appendices. 16 refs., 23 figs., 9 tabs

  4. HTR-PM Safety requirement and Licensing experience

    International Nuclear Information System (INIS)

    Li Fu; Zhang Zuoyi; Dong Yujie; Wu Zongxin; Sun Yuliang

    2014-01-01

    HTR-PM is a 200MWe modular pebble bed high temperature reactor demonstration plant which is being built in Shidao Bay, Weihai, Shandong, China. The main design parameters of HTR-PM were fixed in 2006, the basic design was completed in 2008. The review of Preliminary Safety Analysis Report (PSAR) of HTR-PM was started in April 2008, completed in September 2009. In general, HTR- PM design complies with the current safety requirement for nuclear power plant in China, no special standards are developed for modular HTR. Anyway, Chinese Nuclear Safety Authority, together with the designers, developed some dedicated design criteria for key systems and components and published the guideline for the review of safety analysis report of HTR-PM, based on the experiences from licensing of HTR-10 and new development of nuclear safety. The probabilistic safety goal for HTR-PM was also defined by the safety authority. The review of HTR-PM PSAR lasted for one and a half years, with 3 dialogues meetings and 8 topics meetings, with more than 2000 worksheets and answer sheets. The heavily discussed topics during the PSAR review process included: the requirement for the sub-atmospheric ventilation system, the utilization of PSA in design process, the scope of beyond design basis accidents, the requirement for the qualification of TRISO coating particle fuel, and etc. Because of the characteristics of first of a kind for the demonstration plant, the safety authority emphasized the requirement for the experiment and validation, the PSAR was licensed with certain licensing conditions. The whole licensing process was under control, and was re-evaluated again after Fukushima accident to be shown that the design of HTR-PM complies with current safety requirement. This is a good example for how to license a new reactor. (author)

  5. Staged licensing: An essential element of the NRC's revised regulations

    International Nuclear Information System (INIS)

    Echols, F.S.

    1997-01-01

    Over the past several years, Congress has directed the Department of Energy (DOE), the Nuclear Regulatory Commission (NRC), and the Environmental Protection Agency (EPA) to abandon their efforts to assess an array of potential candidate geologic repository sites for the permanent disposal of spent nuclear reactor fuel and high level radioactive waste, to develop generally applicable requirements for licensing geologic repositories, and to develop generally applicable radiation protection standards for geologic repositories, and instead to focus their efforts to determine whether a single site located at Yucca Mountain, Nevada can be developed as a geologic repository which providing reasonable assurance that public health and safety and the environment will be adequately protected. If the Yucca Mountain site is found to be suitable for development as a geologic repository, then at each stage of development DOE will have to provide the NRC with progressively more detailed information regarding repository design and long-term performance. NRC regulations reflect the fact that it will not be until the repository has been operated for a number of years that the NRC will be able to make a final determination as to long-term repository performance. Nevertheless, the NRC will be able to allow DOE to construct and operate a repository, provided that the NRC believes that the documented results of existing studies, together with the anticipated results from continuing and future studies, will enable the NRC to make a final determination that it has reasonable assurance that the repository system's long-term performance will not cause undue risk to the public. Thus, in its efforts to revise its current regulations to assure that the technical criteria are specifically applicable to the Yucca Mountain site, the NRC should also make sure that it preserves and clarifies the concept of staged repository development

  6. Contestable Licensing

    OpenAIRE

    Zvika Neeman; Gerhard O. Orosel

    2000-01-01

    We analyze a model of repeated franchise bidding for natural monopoly with contestable licensing - a franchisee halds an (exclusive) license to operate a franchise until another rm offers to pay more for it. In a world where quality is observable but not veri able, the simple regulatory scheme we describe combines market-like incentives with regulatory oversight to generate efficient outcomes.

  7. The comparison of license management procedure for nuclear power plant in China and United States

    International Nuclear Information System (INIS)

    Yu Zusheng

    2006-01-01

    'Tow steps' license management procedure for nuclear power plant has been performed bas- ted on the requirement of 10CFR Part50-DOMESTIC LICENSING OF PRODUCTION AND UTILIZATION FACILITIES in United States since last century fifties. In order to ulterior reduce the risk of investment and technical for new construction nuclear power plants, new regulations 'One step' license management procedure-10CFR Part52-EARLY SITE PERMITS; STANDARD DESIGN CERTIFICATIONS; AND COMBINED LICENSES FOR NUCLEAR POWER PLANTS issued in 1989. The new regulations has been adopted by new design of nuclear power plant, for example AP1000. ‘The similar tow steps’ license management procedure for nuclear power plant has been performed basted on the requirement of HAFO01/01 Rules for the Implementation of Regulations on the Safety Regulation for Civilian Nuclear Installations of the People's Re- public of China Part One: Application and Issuance of Safety License for Nuclear Power Plant (December 1993) in China since last century nineties. This article introduces and compares the requirements and characteristics of above license management procedure for nuclear power plant in China and United States. (author)

  8. The role of safety analyses in site selection. Some personal observations based on the experience from the Swiss site selection process

    Energy Technology Data Exchange (ETDEWEB)

    Zuidema, Piet [Nagra, Wettingen (Switzerland)

    2015-07-01

    In Switzerland, the site selection process according to the ''Sectoral Plan for Deep Geological Repositories'' (BFE 2008) is underway since 2008. This process takes place in three stages. In stage 1 geological siting regions (six for the L/ILW repository and three for the HLW repository) have been identified, in stage 2 sites for the surface facilities have been identified for all siting regions in close co-operation with the sting regions and a narrowing down of the number of siting regions based on geological criteria will take place. In stage 3 the sites for a general license application are selected and the general license applications will be submitted which eventually will lead to the siting decision for both repository types. In the Swiss site selection process, safety has the highest priority. Many factors affect safety and thus a whole range of safety-related issues are considered in the identification and screening of siting possibilities. Besides dose calculations a range of quantitative and qualitative issues are considered. Dose calculations are performed in all three stages of the site selection process. In stage 1 generic safety calculations were made to develop criteria to be used for the identification of potential siting regions. In stage 2, dose calculations are made for comparing the different siting regions according to a procedure prescribed in detail by the regulator. Combined with qualitative evaluations this will lead to a narrowing down of the number of siting regions to at least two siting regions for each repository type. In stage 3 full safety cases will be prepared as part of the documentation for the general license applications. Besides the dose calculations, many other issues related to safety are analyzed in a quantitative and qualitative manner. These consider the 13 criteria defined in the Sectoral Plan and the corresponding indicators. The features analyzed cover the following broad themes: efficiency of

  9. The role of safety analyses in site selection. Some personal observations based on the experience from the Swiss site selection process

    International Nuclear Information System (INIS)

    Zuidema, Piet

    2015-01-01

    In Switzerland, the site selection process according to the ''Sectoral Plan for Deep Geological Repositories'' (BFE 2008) is underway since 2008. This process takes place in three stages. In stage 1 geological siting regions (six for the L/ILW repository and three for the HLW repository) have been identified, in stage 2 sites for the surface facilities have been identified for all siting regions in close co-operation with the sting regions and a narrowing down of the number of siting regions based on geological criteria will take place. In stage 3 the sites for a general license application are selected and the general license applications will be submitted which eventually will lead to the siting decision for both repository types. In the Swiss site selection process, safety has the highest priority. Many factors affect safety and thus a whole range of safety-related issues are considered in the identification and screening of siting possibilities. Besides dose calculations a range of quantitative and qualitative issues are considered. Dose calculations are performed in all three stages of the site selection process. In stage 1 generic safety calculations were made to develop criteria to be used for the identification of potential siting regions. In stage 2, dose calculations are made for comparing the different siting regions according to a procedure prescribed in detail by the regulator. Combined with qualitative evaluations this will lead to a narrowing down of the number of siting regions to at least two siting regions for each repository type. In stage 3 full safety cases will be prepared as part of the documentation for the general license applications. Besides the dose calculations, many other issues related to safety are analyzed in a quantitative and qualitative manner. These consider the 13 criteria defined in the Sectoral Plan and the corresponding indicators. The features analyzed cover the following broad themes: efficiency of

  10. Sites in the United States contaminated with radioactivity

    International Nuclear Information System (INIS)

    Wolbarst, A.B.; Blom, P.F.; Chan, D.

    1999-01-01

    Over the century that radioactive materials have been mined, processed, produced, and utilized, many sites across the US have become contaminated. Such sites include bases and installations of the Department of Defense, weapons production and research facilities of the Department of Energy, properties under the authority of other Federal agencies, privately-owned and governmental facilities that are licensed by the Nuclear Regulatory Commission and its Agreement States, and sites licensed by or the responsibility of states. This review reports on aspects of work by the Environmental Protection Agency, the Department of Defense, the Department of Energy, the Nuclear Regulatory Commission, and others to identify sites contaminated with radioactive materials. It also describes the principal programs that have been instituted to deal with them

  11. NRC Licensing Status Summary Report for NGNP

    Energy Technology Data Exchange (ETDEWEB)

    Moe, Wayne Leland [Idaho National Lab. (INL), Idaho Falls, ID (United States); Kinsey, James Carl [Idaho National Lab. (INL), Idaho Falls, ID (United States)

    2014-11-01

    The Next Generation Nuclear Plant (NGNP) Project, initiated at Idaho National Laboratory (INL) by the U.S. Department of Energy (DOE) pursuant to provisions of the Energy Policy Act of 2005, is based on research and development activities supported by the Department of Energy Generation IV Nuclear Energy Systems Initiative. The principal objective of the NGNP Project is to support commercialization of high temperature gas-cooled reactor (HTGR) technology. The HTGR is a helium-cooled and graphite moderated reactor that can operate at temperatures much higher than those of conventional light water reactor (LWR) technologies. The NGNP will be licensed for construction and operation by the Nuclear Regulatory Commission (NRC). However, not all elements of current regulations (and their related implementation guidance) can be applied to HTGR technology at this time. Certain policies established during past LWR licensing actions must be realigned to properly accommodate advanced HTGR technology. A strategy for licensing HTGR technology was developed and executed through the cooperative effort of DOE and the NRC through the NGNP Project. The purpose of this report is to provide a snapshot of the current status of the still evolving pre-license application regulatory framework relative to commercial HTGR technology deployment in the U.S. The following discussion focuses on (1) describing what has been accomplished by the NGNP Project up to the time of this report, and (2) providing observations and recommendations concerning actions that remain to be accomplished to enable the safe and timely licensing of a commercial HTGR facility in the U.S.

  12. ONR Licensing and Regulation of a Geological Disposal Facility in the UK

    International Nuclear Information System (INIS)

    Boydon, Frans; Glazbrook, David

    2014-01-01

    Document available in abstract form only. Full text follows: The UK has substantial quantities of waste which has arisen from operation and decommissioning of legacy nuclear plant. While a disposal route for Low Level Waste (LLW) has been in operation in the UK for many years, there is as yet no such route for Higher Activity Waste. The government invited local communities to express an interest in hosting a Geological Disposal Facility (GDF). However, the Scottish government is opposed to deep disposal and proposes long-term interim storage in Scotland. This paper describes the work underway and current progress in developing a GDF for the UK. In particular it describes the current legal system in the UK that enables nuclear facilities to be licensed and the background underpinning licensing of existing disposal facilities. It identifies changes which will be necessary to legislation to enable a GDF to be licensed and work which it is performing in close co-operation with the Environment Agency which operate a permitting regime for environmental aspects. The Office of Nuclear Regulation (ONR) regulates safety, security and transport associated with nuclear sites. This paper focuses on the regulation of safety and radioactive waste. The UK licensing regime is non-prescriptive and proportionate, allowing for a flexible approach to licensing. The licence is not time-limited but is designed to be used from construction, through commissioning for the lifetime of the facility. Under the Nuclear Installations Act 1965 (as amended) ONR may attach licence conditions: - In the interests of safety; or - with respect to the handling, treatment and disposal of nuclear matter. ONR has developed a suite of 36 Licence conditions, which typically require the operator to made 'adequate arrangements' to ensure safety. These arrangements would involve the use of 'hold points' beyond which the operator must not proceed without ONR's agreement. In determining

  13. Site characterization activities at Stripa and other Swedish projects

    International Nuclear Information System (INIS)

    Ahlstroehm, P.E.

    1991-01-01

    The Swedish research programme concerning spent nuclear fuel disposal aims for submitting a siting license application around the year 2000. An important step towards that goal will be the detailed characterization of at least two potential sites in late 1990s. In preparation for such characterization several research projects are conducted. One is the international Stripa Project that includes a site characterization and validation project for a small size granite rock body. The Stripa work also includes further development of instrumentation and measurement techniques. Another project is the Finnsjoen Fracture Zone Project, which is characterizing a subhorizontal zone at depths from 100 to 350 meters. The third project is the new Swedish Hard Rock Laboratory planned at the site of the Oskarshamn nuclear power plant. The preinvestigations and construction of this laboratory include major efforts in development, application and validation of site characterization methodology. (author) 6 figs., 9 refs

  14. Licensing process for safety-critical software-based systems

    Energy Technology Data Exchange (ETDEWEB)

    Haapanen, P. [VTT Automation, Espoo (Finland); Korhonen, J. [VTT Electronics, Espoo (Finland); Pulkkinen, U. [VTT Automation, Espoo (Finland)

    2000-12-01

    System vendors nowadays propose software-based technology even for the most critical safety functions in nuclear power plants. Due to the nature of software faults and the way they cause system failures new methods are needed for the safety and reliability evaluation of these systems. In the research project 'Programmable automation systems in nuclear power plants (OHA)', financed together by the Radiation and Nuclear Safety Authority (STUK), the Ministry of Trade and Industry (KTM) and the Technical Research Centre of Finland (VTT), various safety assessment methods and tools for software based systems are developed and evaluated. As a part of the OHA-work a reference model for the licensing process for software-based safety automation systems is defined. The licensing process is defined as the set of interrelated activities whose purpose is to produce and assess evidence concerning the safety and reliability of the system/application to be licensed and to make the decision about the granting the construction and operation permissions based on this evidence. The parties of the licensing process are the authority, the licensee (the utility company), system vendors and their subcontractors and possible external independent assessors. The responsibility about the production of the evidence in first place lies at the licensee who in most cases rests heavily on the vendor expertise. The evaluation and gauging of the evidence is carried out by the authority (possibly using external experts), who also can acquire additional evidence by using their own (independent) methods and tools. Central issue in the licensing process is to combine the quality evidence about the system development process with the information acquired through tests, analyses and operational experience. The purpose of the licensing process described in this report is to act as a reference model both for the authority and the licensee when planning the licensing of individual applications

  15. Licensing process for safety-critical software-based systems

    International Nuclear Information System (INIS)

    Haapanen, P.; Korhonen, J.; Pulkkinen, U.

    2000-12-01

    System vendors nowadays propose software-based technology even for the most critical safety functions in nuclear power plants. Due to the nature of software faults and the way they cause system failures new methods are needed for the safety and reliability evaluation of these systems. In the research project 'Programmable automation systems in nuclear power plants (OHA)', financed together by the Radiation and Nuclear Safety Authority (STUK), the Ministry of Trade and Industry (KTM) and the Technical Research Centre of Finland (VTT), various safety assessment methods and tools for software based systems are developed and evaluated. As a part of the OHA-work a reference model for the licensing process for software-based safety automation systems is defined. The licensing process is defined as the set of interrelated activities whose purpose is to produce and assess evidence concerning the safety and reliability of the system/application to be licensed and to make the decision about the granting the construction and operation permissions based on this evidence. The parties of the licensing process are the authority, the licensee (the utility company), system vendors and their subcontractors and possible external independent assessors. The responsibility about the production of the evidence in first place lies at the licensee who in most cases rests heavily on the vendor expertise. The evaluation and gauging of the evidence is carried out by the authority (possibly using external experts), who also can acquire additional evidence by using their own (independent) methods and tools. Central issue in the licensing process is to combine the quality evidence about the system development process with the information acquired through tests, analyses and operational experience. The purpose of the licensing process described in this report is to act as a reference model both for the authority and the licensee when planning the licensing of individual applications. Many of the

  16. Nuclear plant license renewal

    International Nuclear Information System (INIS)

    Gazda, P.A.; Bhatt, P.C.

    1991-01-01

    During the next 10 years, nuclear plant license renewal is expected to become a significant issue. Recent Electric Power Research Institute (EPRI) studies have shown license renewal to be technically and economically feasible. Filing an application for license renewal with the Nuclear Regulatory Commission (NRC) entails verifying that the systems, structures, and components essential for safety will continue to perform their safety functions throughout the license renewal period. This paper discusses the current proposed requirements for this verification and the current industry knowledge regarding age-related degradation of structures. Elements of a license renewal program incorporating NRC requirements and industry knowledge including a schedule are presented. Degradation mechanisms for structural components, their significance to nuclear plant structures, and industry-suggested age-related degradation management options are also reviewed

  17. Motorcycle Training for California Driver Licensing Personnel. Final Report.

    Science.gov (United States)

    California State Dept. of Motor Vehicles, Sacramento.

    The development of a 6-hour motorcycle course of instruction for personnel responsible for motorcycle licensing is described in this project report. The primary goals are stated and include (1) training driver licensing personnel in motorcycle safety and principles of operation, and (2) purchasing and installing appropriate motorcycle skill…

  18. Licensing and Operations of the Clive, Utah Low-Level Containerized Radioactive Waste Disposal Facility- A Continuation of Excellence

    Energy Technology Data Exchange (ETDEWEB)

    Ledoux, M. R.; Cade, M. S.

    2002-02-25

    Envirocare's Containerized Waste Facility (CWF) is the first commercial low-level radioactive waste disposal facility to be licensed in the 21st century and the first new site to be opened and operated since the late 1970's. The licensing of this facility has been the culmination of over a decade's effort by Envirocare of Utah at their Clive, Utah site. With the authorization to receive and dispose of higher activity containerized Class A low-level radioactive waste (LLRW), this facility has provided critical access to disposal for the nuclear power industry, as well as the related research and medical communities. This paper chronicles the licensing history and operational efforts designed to address the disposal of containerized LLRW in accordance with state and federal regulations.

  19. Concept for calculating dose rates from activated groundwater at accelerator sites

    CERN Document Server

    Prolingheuer, N; Vanderborght, J; Schlögl, B; Nabbi, R; Moormann, R

    Licensing of particle accelerators requires the proof that the groundwater outside of the site will not be significantly contaminated by activation products formed below accelerator and target. In order to reduce the effort for this proof, a site independent simplified but conservative method is under development. The conventional approach for calculation of activation of soil and groundwater is shortly described on example of a site close to Forschungszentrum Juelich, Germany. Additionally an updated overview of a data library for partition coefficients for relevant nuclides transported in the aquifer at the site is presented. The approximate model for transport of nuclides with ground water including exemplary results on nuclide concentrations outside of the site boundary and of resulting effective doses is described. Further applications and developments are finally outlined.

  20. Siting of light-water reactor power plants in the Federal Republic of Germany

    International Nuclear Information System (INIS)

    Kohler, H.A.G.

    1975-01-01

    The nuclear power plant site requirements formulated for environment protection in Germany allow nuclear power plants to be built at any site provided these requirements are duly taken into account in preparing and monitoring the site and in the design of the proposed power plant. After a brief discussion of light water reactor power plant sites, prevailing practice in site planning, site selection criteria, licensing procedure and used criteria, rules and guidelines, this paper reports on some considerations taken into account by the expert advisers and by the licensing authorities and future site planning. (orig.) [de

  1. Licensing the First Nuclear Power Plant. INSAG-26. A report by the International Nuclear Safety Group

    International Nuclear Information System (INIS)

    2012-01-01

    having nuclear power plants of similar design, and the various technical cooperation activities conducted by international organizations, in particular the IAEA. The first major task for the regulatory body will be carrying out a review of the safety evaluation report of the proposed site for the first nuclear power plant. For this, the regulatory body must lay down the safety requirements that could be developed or adopted from IAEA safety standards on the subject. It will also require a set of specialized competences in areas such as seismology, hydrology, geochemistry and geology that is not necessarily nuclear related. In developing the strategy to secure and maintain a technically competent regulatory body, a decision should be made early whether to recruit staff with those competences or to outsource these activities to agencies where competences in such areas may already be available in the country. Notwithstanding this, the regulatory body still requires a core technical group in the key disciplines to be able to understand and compile the information from the site evaluation reports as input to the site licensing process.

  2. Preliminary evaluation of licensing issues associated with U.S.-sited CANDU-PHW nuclear power plants

    International Nuclear Information System (INIS)

    van Erp, J.B.

    1977-12-01

    The principal safety-related characteristics of current CANDU-PHW power plants are described, and a distinction between those characteristics which are intrinsic to the CANDU-PHW system and those that are not is presented. An outline is given of the main features of the Canadian safety and licensing approach. Differences between the U.S. and Canadian approach to safety and licensing are discussed. Some of the main results of the safety analyses, routinely performed for CANDU-PHW reactors, are presented. U.S.-NRC General Design Criteria are evaluated as regards their applicability to CANDU-PHW reactors; vice-versa the CANDU-PHW reactor is evaluated with respect to its conformance to the U.S.-NRC General Design Criteria. A number of design modifications are proposed to be incorporated into the CANDU-PHW reactor in order to facilitate its introduction into the U.S

  3. Preliminary evaluation of licensing issues associated with U. S. -sited CANDU-PHW nuclear power plants

    Energy Technology Data Exchange (ETDEWEB)

    van Erp, J B

    1977-12-01

    The principal safety-related characteristics of current CANDU-PHW power plants are described, and a distinction between those characteristics which are intrinsic to the CANDU-PHW system and those that are not is presented. An outline is given of the main features of the Canadian safety and licensing approach. Differences between the U.S. and Canadian approach to safety and licensing are discussed. Some of the main results of the safety analyses, routinely performed for CANDU-PHW reactors, are presented. U.S.-NRC General Design Criteria are evaluated as regards their applicability to CANDU-PHW reactors; vice-versa the CANDU-PHW reactor is evaluated with respect to its conformance to the U.S.-NRC General Design Criteria. A number of design modifications are proposed to be incorporated into the CANDU-PHW reactor in order to facilitate its introduction into the U.S.

  4. Licensing Strategies of the Entreprising - But Vulnerable - `Intellectual property' Vendors

    DEFF Research Database (Denmark)

    Davis, Lee N.

    This paper investigates in an exploratory manner the licensing strategies pursued by firms whose business model is based on developing and licensing out their intellectual property rights (IPRs). These are not traditional suppliers, since they do not engage in production or commercialization...... be differentiated along two main dimensions: whether the driving force behind the inventive process is "technology push" or "market pull", and the degree to which the innovative activities carried out by the IP vendor are mutually dependent upon the innovative activities of the other relevant market players....... On this basis, four main licensing strategies are identified. We investigate the relative benefits and costs of these four strategies, and the factors affecting licensing choices.Key words: Intellectual property, licensing, strategyJEL Codes: O31, OO34...

  5. Challenges of SMR licensing practices

    Energy Technology Data Exchange (ETDEWEB)

    Soderholm, K., E-mail: kristiina.soderholm@fortum.com [Fortum Power, Espoo (Finland)

    2012-12-15

    This paper aims to increase the understanding of high level Nuclear Power Plant (NPP) licensing processes in Finland, France, the UK, Canada and the USA. These countries have been selected for this study because of their different licensing processes and recent actions in new NPP construction. After discussing their similarities and differences, suitable features for Small Modular Reactor licensing can be emphasized and suggested. Some of the studied licensing processes have elements that are already quite well suited for application to SMRs, but all of these different national processes can benefit from studying and implementing lessons learned from SMR specific licensing needs. The main SMR features to take into account in licensing are standardization of the design, modularity, mass production and serial construction. Modularity can be divided into two different categories: the first category is simply a single unit facility constructed of independently engineered modules (e.g., construction process for Westinghouse AP-1000 NPP) and the second is a facility structure composed of many reactor modules where modules are manufactured in factories and installed into the facility as needed (e.g., NuScale Power SMR design). Short construction schedules will not be fully benefited from if the long licensing process prolongs the commissioning and approach to full-power operation. The focus area of this study is to better understand the possibility of SMR deployment in small nuclear countries, such as Finland, which currently has four operating NPPs. The licensing process needs to be simple and clear to make SMR deployment feasible from an economical point of view. This paper uses public information and interviews with experts to establish the overview of the different licensing processes and their main steps. A high-level comparison of the licensing steps has been carried out. Certain aspects of the aviation industry licensing process have also been studied and certain

  6. 31 CFR 596.306 - License.

    Science.gov (United States)

    2010-07-01

    ... ASSETS CONTROL, DEPARTMENT OF THE TREASURY TERRORISM LIST GOVERNMENTS SANCTIONS REGULATIONS General Definitions § 596.306 License. Except as otherwise specified, the term license means any license or...

  7. Understanding Licensing Behavior

    DEFF Research Database (Denmark)

    Cabaleiro, Goretti; Moreira, Solon; Reichstein, Toke

    The potential for rent dissipation has been argued to be the main cause of firms? licensing out behavior being stifled.However, this aspect has been scarcely studied empirically. We draw on rent dissipation arguments, and hypothesize that firms suffering from the not-invented-here (NIH) syndrome......, firms in competitive product markets, and firms that have incurred substantial sunk cost are associated with lower rates of technology out-licensing. We also posit that sunk costs negatively moderate the relationship between competition in the licensor?s product market, and licensing rate. We test our...

  8. Oil and gas development in Greenland: A social license to operate, trust and legitimacy in environmental governance

    NARCIS (Netherlands)

    Smits, C.; Leeuwen, van J.; Tatenhove, van J.P.M.

    2017-01-01

    Since the turn of the century, Greenland has been examining the possibilities to develop its potential oil and gas resources. The large scale oil and gas activities will impact the small Greenlandic society, both positively and negatively. In this paper we employ the concept of a social license to

  9. Nuclear power stations licensing

    International Nuclear Information System (INIS)

    Solito, J.

    1978-04-01

    The judicial aspects of nuclear stations licensing are presented. The licensing systems of the United States, Spain, France and Federal Republic of Germany are focused. The decree n 0 60.824 from July 7 sup(th), 1967 and the following legislation which define the systematic and area of competence in nuclear stations licensing are analysed [pt

  10. 77 FR 5036 - Prospective Grant of Exclusive License: The Development of Human Anti-Mesothelin Monoclonal...

    Science.gov (United States)

    2012-02-01

    ... cancer, lung cancer, mesothelioma, and stomach/gastric cancer. The Licensed Field of Use explicitly.... Lambertson, Ph.D., Senior Licensing and Patenting Manager, Office of Technology Transfer, National Institutes... cancers, including mesothelioma, lung cancer, stomach/gastric cancer, ovarian cancer and pancreatic cancer...

  11. Safety evaluation status report for the prototype license application safety analysis report

    International Nuclear Information System (INIS)

    1989-07-01

    The US Nuclear Regulatory Commission (NRC) staff and consultants reviewed a Prototype License Application Safety Analysis Report (PLASAR) submitted by the US Department of Energy (DOE) for the earth-mounded concrete bunker (EMCB) alternative method of low-level radioactive waste disposal. The NRC reviewers relied extensively on the Standard Review Plan (SRP), Rev.1 (NUREG-1200), to evaluate the acceptability of the information provided in the EMCB PLASAR. The NRC staff selected certain review areas in the PLASAR for development of safety evaluation report input to provide examples of safety assessments that are necessary as part of a licensing review. Because of the fictitious nature of the assumed disposal site, and the decision to limit the review to essentially first-round review status, the NRC staff report is labeled a ''Safety Evaluation Status Report'' (SESR). Appendix A comprises the NRC review comments and questions on the information that DOE submitted in the PLASAR. The NRC concentrated its review on the design and operations-related portions of the EMCB PLASAR

  12. 78 FR 56749 - Site Characteristics and Site Parameters for Nuclear Power Plants

    Science.gov (United States)

    2013-09-13

    ..., ``Geologic Characterization Information,'' (currently titled as ``Basic Geologic and Seismic Information... Ensuring Hazard- Consistent Seismic Input for Site Response and Soil Structure Interaction Analyses,'' NUREG-2115 and NUREG-2117; (2) adding information concerning the Geologic Mapping License Condition; (3...

  13. Improving the Business Trade Licensing Reform Environment

    OpenAIRE

    Gamser, Matthew

    2003-01-01

    This case study of Kenyan business trade licensing shows that red-tape costs can be cut if reform is championed strongly and there is a strong case in terms of costs and benefits. The reform of business registration, trade licensing and other business entry procedures is a cost effective and progressive way to promote indigenous private sector development. But, reform needs more than good cost-benefit analysis and legal drafting; it also requires building constituencies and continuous advocacy.

  14. Management strategy for site characterization at candidate HLW repository sites

    International Nuclear Information System (INIS)

    Bartlett, J.W.

    1988-01-01

    This paper describes a management strategy for HLW repository site characterization which is aimed at producing an optimal characterization trajectory for site suitability and licensing evaluations. The core feature of the strategy is a matrix of alternative performance targets and alternative information-level targets which can be used to allocate and justify program effort. Strategies for work concerning evaluation of expected and disrupted repository performance are distinguished, and the need for issue closure criteria is discussed

  15. Decree No. 83/7405 of 18 November 1983 on the licensing procedure for nuclear installations

    International Nuclear Information System (INIS)

    1983-01-01

    This Decree (No. 83/7405) on the licensing procedure for nuclear installations came into force on 19 December 1983 and supersedes Decree No. 7/9141 of 5 December 1974 on the same subject. The general lines of the licensing procedure laid down by this new Decree are similar to that provided by the 1979 Decree; it is also carried out in three stages: site, construction and operating licences are delivered in succession. (NEA) [fr

  16. Learning-by-Licensing: How Chinese Firms Benefit From Licensing-In Technologies

    DEFF Research Database (Denmark)

    Wang, Yuandi; Roijakkers, N.; Vanhaverbeke, W.

    2012-01-01

    This paper explores how interfirm variations in their in-licensed technology portfolios influence subsequent innovation performance. Existing studies mainly assume licensed technologies are homogeneously accessible to firms, and a prevailing explanation as to why firms vary in their innovation pe...

  17. Hanford Site sustainable development initiatives

    International Nuclear Information System (INIS)

    Sullivan, C.T.

    1994-05-01

    Since the days of the Manhattan Project of World War II, the economic well being of the Tri-Cities (Pasco, Kennewick, and Richland) of Washington State has been tied to the US Department of Energy missions at the nearby Hanford Site. As missions at the Site changed, so did the economic vitality of the region. The Hanford Site is now poised to complete its final mission, that of environmental restoration. When restoration is completed, the Site may be closed and the effect on the local economy will be devastating if action is not taken now. To that end, economic diversification and transition are being planned. To facilitate the process, the Hanford Site will become a sustainable development demonstration project

  18. Status of the Monticello nuclear generating plant lead plant license renewal program

    International Nuclear Information System (INIS)

    Pickens, T.A.

    1992-01-01

    In 1988, the Monticello nuclear generating plant was chosen by the US Department of Energy through Sandia National Laboratories and the Electric Power Research Institute to serve as the lead boiling water reactor in the lead plant license renewal program. The purpose of the lead plant license renewal program is to provide insights during the development of and to demonstrate the license renewal regulatory process with the US Nuclear Regulatory Commission (NRC). The work being performed in three phases: (1) preparation of the technical basis for license renewal; (2) development of the technical basis into a formal license renewal application; and (3) review of the application by the NRC. This paper discusses the systems and structures identified as important to license renewal in accordance with 10CFR54 as well as the plant documents and programs that were used in going through the identification process. The systems and structures important to license renewal will then provide insights into how structures and components were identified that are required to be evaluated for aging, the elements of the aging evaluations, and the effective programs used to manage potentially significant aging

  19. License - Trypanosomes Database | LSDB Archive [Life Science Database Archive metadata

    Lifescience Database Archive (English)

    Full Text Available switchLanguage; BLAST Search Image Search Home About Archive Update History Data List Contact us Trypanoso... Attribution-Share Alike 2.1 Japan . If you use data from this database, please be sure attribute this database as follows: Trypanoso...nse Update History of This Database Site Policy | Contact Us License - Trypanosomes Database | LSDB Archive ...

  20. Operator licensing examiner standards

    International Nuclear Information System (INIS)

    1993-01-01

    The Operator Licensing Examiner Standards provide policy and guidance to NRC examiners and establish the procedures and practices for examining licensees and applicants for reactor operator and senior reactor operator licenses at power reactor facilities pursuant to Part 55 of Title 10 of the Code of Federal Regulations (10 CFR 55). The Examiner Standards are intended to assist NRC examiners and facility licensees to better understand the initial and requalification examination processes and to ensure the equitable and consistent administration of examinations to all applicants. These standards are not a substitute for the operator licensing regulations and are subject to revision or other internal operator licensing policy changes

  1. 75 FR 16490 - Prospective Grant of Exclusive License: Development of PANVAC and Tumor Associated Antigens as...

    Science.gov (United States)

    2010-04-01

    ... exclusive license should be directed to: Sabarni K. Chatterjee, Ph.D. Licensing and Patenting Associate... indicates that Brachyury is aberrantly expressed on tumors of the lung, intestine, stomach, kidney, bladder...

  2. Potential of semiautomated, synoptic geologic studies for characterization of hazardous waste sites

    International Nuclear Information System (INIS)

    Foley, M.G.; Beaver, D.E.; Glennon, M.A.; Eliason, J.R.

    1988-01-01

    Siting studies for licensing hazardous facilities require three-dimensional characterization of site geology including lithology, structure, and tectonics. The scope of these studies depends on the type of hazardous facility and its associated regulations. This scope can vary from a pro forma literature review to an extensive, multiyear research effort. Further, the regulatory environment often requires that the credibility of such studies be established in administrative and litigative proceedings, rather than solely by technical peer review. Pacific Northwest Laboratory (PNL) has developed a technology called remote geologic analysis (RGA). This technology provides reproducible photogeologic maps, determinations of three- dimensional faults and fracture sets expressed as erosional lineaments or planar topographic features, planar feature identification in seismic hypocenter data, and crustal- stress/tectonic analyses. Results from the RGA establish a foundation for interpretations that are defensible in licensing proceedings

  3. An examination of the perceived teaching competencies of novice alternatively licensed and traditionally licensed high school science teachers

    Science.gov (United States)

    Shea, Kathleen A.

    In most states, there are two routes to teacher licensure; traditional and alternative. The alternative route provides an accelerated entry into the classroom, often without the individual engaging in education coursework or a practicum. No matter the route, teaching skills continue to be learned by novice teachers while in the classroom with the guidance of a school-based mentor. In this study, the perceptions of mentor teachers of traditionally and alternatively licensed high school science teachers were compared with respect to mentees' science teaching competency. Further, the study explored the novice teachers' self-perception of their teaching competency. A survey, consisting of 56 Likert-type questions, was completed by mentors (N = 79) and novice high school science teachers (N = 83) in six northeastern states. The results revealed a statistically significant difference in the perceptions of the mentors of traditionally and alternatively licensed novice high school science teachers in the areas of general pedagogical knowledge, pedagogical content knowledge and professional growth, with more favorable perceptions recorded by mentors of traditionally licensed science teachers. There were no differences in the perceptions of the mentors with respect to novice high school teachers' content knowledge. There was no statistical difference in the self-perceptions of competency of the novice teachers. While alternative routes to licensure in science may be a necessity, the results of this study indicate that the lack of professional preparation may need to be addressed at the school level through the agency of the mentor. This study indicates that mentors must be prepared to provide alternatively licensed novice teachers with different assistance to that given to traditionally licensed novice teachers. School districts are urged to develop mentoring programs designed to develop the teaching competency of all novice teachers regardless of the route that led them

  4. 76 FR 65518 - Prospective Grant of Exclusive License: The Development of a Companion Diagnostic Kit for...

    Science.gov (United States)

    2011-10-21

    ... contemplated exclusive license should be directed to: Patrick P. McCue, Ph.D., Licensing and Patenting Manager... has been demonstrated for biliary tract, kidney, lung, and stomach cancers. The prospective exclusive...

  5. 77 FR 30308 - Proposed Renewal of Information Collection: Alternatives Process in Hydropower Licensing

    Science.gov (United States)

    2012-05-22

    ...: Alternatives Process in Hydropower Licensing AGENCY: Office of the Secretary, Office of Environmental Policy... the Alternatives Process in Hydropower Licensing, OMB Control Number 1094-0001. FOR FURTHER... more of the Departments develop for inclusion in a hydropower license issued by the Federal Energy...

  6. License Compliance Issues For Biopharmaceuticals: Special Challenges For Negotiations Between Companies And Non-Profit Research Institutions

    Science.gov (United States)

    Ponzio, Todd A.; Feindt, Hans; Ferguson, Steven

    2011-01-01

    Summary Biopharmaceuticals are therapeutic products based on biotechnology. They are manufactured by or from living organisms and are the most complex of all commercial medicines to develop, manufacture and qualify for regulatory approval. In recent years biopharmaceuticals have rapidly increased in number and importance with over 4001 already marketed in the U.S. and European markets alone. Many companies throughout the world are now ramping up investments in biopharmaceutical R&D and expanding their portfolios through licensing of early-stage biotechnologies from universities and other non-profit research institutions, and there is an increasing number of license agreements for biopharmaceutical product development relative to traditional small molecule drug compounds. This trend will only continue as large numbers of biosimilars and biogenerics enter the market. A primary goal of technology transfer offices associated with publicly-funded, non-profit research institutions is to establish patent protection for inventions deemed to have commercial potential and license them for product development. Such licenses help stimulate economic development and job creation, bring a stream of royalty revenue to the institution and, hopefully, advance the public good or public health by bringing new and useful products to market. In the course of applying for such licenses, a commercial development plan is usually put forth by the license applicant. This plan indicates the path the applicant expects to follow to bring the licensed invention to market. In the case of small molecule drug compounds, there exists a widely-recognized series of clinical development steps, dictated by regulatory requirements, that must be met to bring a new drug to market, such as completion of preclinical toxicology, Phase 1, 2 and 3 testing and product approvals. These steps often become the milestone/benchmark schedule incorporated into license agreements which technology transfer offices use to

  7. License Compliance Issues For Biopharmaceuticals: Special Challenges For Negotiations Between Companies And Non-Profit Research Institutions.

    Science.gov (United States)

    Ponzio, Todd A; Feindt, Hans; Ferguson, Steven

    2011-09-01

    Biopharmaceuticals are therapeutic products based on biotechnology. They are manufactured by or from living organisms and are the most complex of all commercial medicines to develop, manufacture and qualify for regulatory approval. In recent years biopharmaceuticals have rapidly increased in number and importance with over 400() already marketed in the U.S. and European markets alone. Many companies throughout the world are now ramping up investments in biopharmaceutical R&D and expanding their portfolios through licensing of early-stage biotechnologies from universities and other non-profit research institutions, and there is an increasing number of license agreements for biopharmaceutical product development relative to traditional small molecule drug compounds. This trend will only continue as large numbers of biosimilars and biogenerics enter the market.A primary goal of technology transfer offices associated with publicly-funded, non-profit research institutions is to establish patent protection for inventions deemed to have commercial potential and license them for product development. Such licenses help stimulate economic development and job creation, bring a stream of royalty revenue to the institution and, hopefully, advance the public good or public health by bringing new and useful products to market. In the course of applying for such licenses, a commercial development plan is usually put forth by the license applicant. This plan indicates the path the applicant expects to follow to bring the licensed invention to market. In the case of small molecule drug compounds, there exists a widely-recognized series of clinical development steps, dictated by regulatory requirements, that must be met to bring a new drug to market, such as completion of preclinical toxicology, Phase 1, 2 and 3 testing and product approvals. These steps often become the milestone/benchmark schedule incorporated into license agreements which technology transfer offices use to monitor

  8. 77 FR 34093 - License Renewal for Calvert Cliffs Nuclear Power Plant, LLC's

    Science.gov (United States)

    2012-06-08

    ... Nuclear Power Plant, LLC's AGENCY: Nuclear Regulatory Commission. ACTION: Environmental assessment and... Spent Fuel Storage Installation (ISFSI) at the Calvert Cliffs Nuclear Power Plant site near Lusby... Cliffs Nuclear Power Plant, LLC (CCNPP) submitted an application to the NRC to renew NRC License SNM-2505...

  9. ITER, On the way to call for the license

    International Nuclear Information System (INIS)

    Alejaidre, C.; Girard, J.P.

    2007-01-01

    Full text of publication follows: All the seven ITER Parties have now ratified the lTER Agreement, which was signed in Paris in November last year. On October 24, 2007 the ITER Agreement enters officially into force. The licensing procedure to start construction shall be launched within the coming months in order to start construction at the beginning of 2009. The Host Party, Europe and the Host State, France have already participated together with the ITER Organization (IO) to a public debate to present the project to the neighboring populations (January to May 2006) and other administrative procedures to prepare the site and the roads for heavy loads. According to host state law on licensing of nuclear facilities, IO will send a set of administrative documents including a safety assessment (called Preliminary Safety Report) and public hearing files including impact studies and risk analysis. The review and public hearing are expected mid-08 to be consistent with the start of nuclear building construction on site. The latest update of the design took into account of inputs from: -An internal design review managed through eight specialist groups including safety and licensing, - Host State regulations (technical and QA), which should be fulfilled as quoted in the ITER agreement, - Site adaptation including land configuration, environmental conditions and external hazards. The ITER designers, in close contact with the Participant Teams, are proceeding with the adaptation of the generic design to comply with these new inputs. The codes and standards for all equipment are also under revision in order to fit with the expected requirements, taking into account the procurement sharing agreement and the French regulations. In the earlier stage of ITER design fusion took benefit from fission knowledge, in the present stage fusion is taking the lead as can be demonstrated by the update of the European mechanical code RCC-MR, now ready and updated to the vacuum vessel design

  10. General aspects of siting and safety considerations

    International Nuclear Information System (INIS)

    Rutgers, E.

    1980-01-01

    The siting process from site selection to the different stages of review by the regulatory body is described. Special attention is payed to the role and responsibilities of the licensing authority. Next, the basic considerations involved in the siting process are reviewed. They include system planning, engineering, safety, environmental impact (including land use) and economics. Case studies illustrating different aspects of the siting process (e.g. site selection) are presented. (orig.)

  11. Commitment tracking in the licensing renewal process: A perspective

    International Nuclear Information System (INIS)

    Gurican, Gregory M.; Breslauer, Stephen K.

    1991-01-01

    The NRC's proposed 10 CFR 54 defines 'Current licensing basis' as inclusive of all licensee commitments. During the last five years, the regulatory commitment tracking group (RCTG) has been developing guidance for member utilities to track such commitments. The RCTG guidance for commitment tracking assists utilities in developing a system to store and maintain commitments related to the CLB. But a majority believe it unlikely that any one commitment tracking system will capture all commitments contained in the proposed definition of a 'Current Licencing Basis'. For future renewal applications the NRC proposes that utilities must identify and compile all licensing basis commitments. In addition, utilities 'shall maintain...(them) in an auditable and retrievable form'. Some utilities are already compiling and tracking licensing basis commitments; others are not. (author)

  12. Licensed reactor nuclear safety criteria applicable to DOE reactors

    International Nuclear Information System (INIS)

    1991-04-01

    The Department of Energy (DOE) Order DOE 5480.6, Safety of Department of Energy-Owned Nuclear Reactors, establishes reactor safety requirements to assure that reactors are sited, designed, constructed, modified, operated, maintained, and decommissioned in a manner that adequately protects health and safety and is in accordance with uniform standards, guides, and codes which are consistent with those applied to comparable licensed reactors. This document identifies nuclear safety criteria applied to NRC [Nuclear Regulatory Commission] licensed reactors. The titles of the chapters and sections of USNRC Regulatory Guide 1.70, Standard Format and Content of Safety Analysis Reports for Nuclear Power Plants, Rev. 3, are used as the format for compiling the NRC criteria applied to the various areas of nuclear safety addressed in a safety analysis report for a nuclear reactor. In each section the criteria are compiled in four groups: (1) Code of Federal Regulations, (2) US NRC Regulatory Guides, SRP Branch Technical Positions and Appendices, (3) Codes and Standards, and (4) Supplemental Information. The degree of application of these criteria to a DOE-owned reactor, consistent with their application to comparable licensed reactors, must be determined by the DOE and DOE contractor

  13. Site characterization techniques used at a low-level waste shallow land burial field demonstration facility

    International Nuclear Information System (INIS)

    Davis, E.C.; Boegly, W.J. Jr.; Rothschild, E.R.

    1984-07-01

    The Environmental Sciences Division of the Oak Ridge National Laboratory has been investigating improved shallow land burial technology for application in the humd eastern United States. As part of this effort, a field demonstration facility (Engineered Test Facility, or ETF) has been established in Solid Waste Storage Area 6 for purposes of investigatig the ability of two trench treatments (waste grouting prior to cover emplacement and waste isolation with trench liners) to prevent water-waste contact and thus minimize waste leaching. As part of the experimental plan, the ETF site has been characterized for purposes of constructing a hydrologic model. Site characterization is an extremely important component of the waste disposal site selection process; during these activities, potential problems, which might obviate the site from further consideration, may be found. This report describes the ETF site characterization program and identifies and, where appropriate, evaluates those tests that are of most value in model development. Specific areas covered include site geology, soils, and hydrology. Each of these areas is further divided into numerous subsections, making it easy for the reader to examine a single area of interest. Site characterization is a multidiscipliary endeavor with voluminous data, only portions of which are presented and analyzed here. The information in this report is similar to that which will be required of a low-level waste site developer in preparing a license application for a potential site in the humid East, (a discussion of licensing requirements is beyond its scope). Only data relevant to hydrologic model development are included, anticipating that many of these same characterization methods will be used at future disposal sites with similar water-related problems

  14. Site characterization techniques used at a low-level waste shallow land burial field demonstration facility

    Energy Technology Data Exchange (ETDEWEB)

    Davis, E.C.; Boegly, W.J. Jr.; Rothschild, E.R.; Spalding, B.P.; Vaughan, N.D.; Haase, C.S.; Huff, D.D.; Lee, S.Y.; Walls, E.C.; Newbold, J.D.

    1984-07-01

    The Environmental Sciences Division of the Oak Ridge National Laboratory has been investigating improved shallow land burial technology for application in the humd eastern United States. As part of this effort, a field demonstration facility (Engineered Test Facility, or ETF) has been established in Solid Waste Storage Area 6 for purposes of investigatig the ability of two trench treatments (waste grouting prior to cover emplacement and waste isolation with trench liners) to prevent water-waste contact and thus minimize waste leaching. As part of the experimental plan, the ETF site has been characterized for purposes of constructing a hydrologic model. Site characterization is an extremely important component of the waste disposal site selection process; during these activities, potential problems, which might obviate the site from further consideration, may be found. This report describes the ETF site characterization program and identifies and, where appropriate, evaluates those tests that are of most value in model development. Specific areas covered include site geology, soils, and hydrology. Each of these areas is further divided into numerous subsections, making it easy for the reader to examine a single area of interest. Site characterization is a multidiscipliary endeavor with voluminous data, only portions of which are presented and analyzed here. The information in this report is similar to that which will be required of a low-level waste site developer in preparing a license application for a potential site in the humid East, (a discussion of licensing requirements is beyond its scope). Only data relevant to hydrologic model development are included, anticipating that many of these same characterization methods will be used at future disposal sites with similar water-related problems.

  15. A future for nuclear sites beyond their service life. Nuclear site value development

    International Nuclear Information System (INIS)

    2008-01-01

    As the nuclear industry moves into a new development phase, many facilities built in the fifties and sixties are reaching the end of their service life. Dismantling them and rehabilitating the sites on which they stand is a major industrial challenge which will give rise to a number of new projects. AREVA has more than 20 years' experience in these highly technical fields. As more and more sites reach the end of their service life, AREVA considers nuclear site value development as a fully-fledged industrial activity. The group's competencies in this field have been grouped together to form a dedicated entity: the Nuclear Site Value Development Business Unit, created in 2008. Several billion euros are invested in site value development projects which are far-reaching and complex, and often last for several decades. Long before work actually begins, lengthy studies and preparations are required to schedule operations, select the techniques to be used and optimize costs and deadlines. The Nuclear Site Value Development BU is currently working on four major projects involving its own facilities and those of the CEA: - La Hague: dismantling of the first generation of used fuel recycling facilities. Between 1966 and 1998, almost 5,000 tons of used fuel from graphite-moderated gas-cooled reactors, 4,500 tons of light water reactor fuel, as well as fuel from fast reactors and research reactors, were treated at UP2 400, the very first industrial recycling plant on the La Hague site. - Marcoule: first-time dismantling of a recycling plant. 1,000 rooms to be cleaned up, 30,000 tons of waste to be treated, 30 years of work. - Cadarache: first-time dismantling of a Mox fuel fabrication plant. The Cadarache plant was commissioned in 1962 to fabricate fuel for fast reactors; this was followed by MOX fuel for light water reactors, an activity which continued until the plant was shut down in 2003. - Annecy and Veurey: giving a new lease of life to former industrial sites in built

  16. 77 FR 29701 - Impact of Construction (Under a Combined License) of New Nuclear Power Plant Units on Operating...

    Science.gov (United States)

    2012-05-18

    ... New Nuclear Power Plant Units on Operating Units at Multi-Unit Sites AGENCY: Nuclear Regulatory... construct and operate new nuclear power plants (NPPs) on multi-unit sites to provide an evaluation of the... License) of New Nuclear Power Plants on Operating Units at Multi-Unit Sites (Package). ML112630039 Federal...

  17. North Carolina Geological Survey's role in siting a low-level radioactive (LLRW) waste disposal facility in North Carolina

    International Nuclear Information System (INIS)

    Reid, J.C.; Wooten, R.M.; Farrell, K.M.

    1993-01-01

    The Southeast Compact Commission in 1986 selected North Carolina to host the Southeast's LLRW disposal facility for the next twenty years. The North Carolina Geological Survey (NCGS) for six years has played a major role in the State's efforts by contributing to legislation and administrative code, policy, technical oversight and surveillance and regulation as a member of the State's regulatory team. Future activities include recommendation of the adequacy of characterization and site performance pursuant to federal code, state general statutes and administrative code, and review of a license application. Staff must be prepared to present testimony and professional conclusions in court. The NCGS provides technical advice to the Division of Radiation Protection (DRP), the regulatory agency which will grant or deny a LLRW license. The NCGS has not participated in screening the state for potential sites to minimize bias. The LLRW Management Authority, a separate state agency siting the LLRW facility, hired a contractor to characterize potential sites and to write a license application. Organizational relationships enable the NCGS to assist the DRP in its regulatory role without conflict of interest. Disposal facilities must be sited to ensure safe disposal of LLRW. By law, the siting of a LLRW disposal facility is primarily a geological, rather than an engineering, effort. Federal and State statutes indicate a site must be licensable on its own merits. Engineered barriers cannot make a site licensable. The project is 3 years behind schedule and millions of dollars over budget. This indicates the uncertainty and complexity inherent in siting such as facility, the outcome of which cannot be predicted until site characterization is complete, the license application reviewed and the performance assessment evaluated. State geological surveys are uniquely qualified to overview siting of LLRW facilities because of technical expertise and experience in the state's geology

  18. Licensing process characteristics of Small Modular Reactors and spent nuclear fuel repository

    Energy Technology Data Exchange (ETDEWEB)

    Söderholm, Kristiina, E-mail: kristiina.soderholm@fortum.com [Fortum Power (Finland); Tuunanen, Jari, E-mail: jari.tuunanen@fortum.com [Fortum Power (Finland); Amaba, Ben, E-mail: baamaba@us.ibm.com [IBM Complex Systems (United States); Bergqvist, Sofia, E-mail: sofia.bergqvist@se.ibm.com [IBM Rational Software (Sweden); Lusardi, Paul, E-mail: plusardi@nuscalepower.com [NuScale Power (United States)

    2014-09-15

    Highlights: • We examine the licensing process challenges of modular nuclear facilities. • We compare the features of Small Modular Reactors and spent nuclear fuel repository. • We present the need of nuclear licensing simplification. • Part of the licensing is proposed to be internationally applicable. • Systems engineering and requirements engineering benefits are presented. - Abstract: This paper aims to increase the understanding of the licensing processes characteristics of Small Modular Reactors (SMR) compared with licensing of spent nuclear fuel repository. The basis of the SMR licensing process development lies in licensing processes used in Finland, France, the UK, Canada and the USA. These countries have been selected for this study because of their various licensing processes and recent actions in the new NPP construction. Certain aspects of the aviation industry licensing process have also been studied and selected practices have been investigated as possibly suitable for use in nuclear licensing. Suitable features for SMR licensing are emphasized and suggested. The licensing features of the spent nuclear fuel deep repository along with similar features of SMR licensing are discussed. Since there are similar types of challenges of lengthy licensing time frames, as well as modular features to be taken into account in licensing, these two different nuclear industry fields can be compared. The main SMR features to take into account in licensing are: • Standardization of the design. • Modularity. • Mass production. • Serial construction. Modularity can be divided into two different categories: the first category is simply a single power plant unit constructed of independently engineered modules (e.g. construction process for Westinghouse AP-1000 NPP) and the second one a power plant composed of many reactor modules, which are manufactured in factories and installed as needed (e.g. NuScale Power SMR design). The deep underground repository

  19. Development and Application of SITES

    International Nuclear Information System (INIS)

    Park, Jo Wan; Yoon; Yoon, Jeong Hyoun; Kim, Chank Lak; Cho, Sung IL

    2008-01-01

    SITES (Site Information and Total Environmental Data Management System) has been developed for the purpose of systematically managing site characteristics and environmental data produced during the pre-operational, operational, and post-closure phases of a radioactive waste disposal facility. SITES is an integration system, which consists of 4 modules, to be available for maintenance of site characteristics data, for safety assessment, and for site/environment monitoring; site environmental data management module (SECURE), integrated safety assessment module (SAINT), site/environment monitoring module (SUDAL) and geological information module for geological data management (SITES-GIS). Each module has its database with the functions of browsing, storing, and reporting data and information. Data from SECURE and SUDAL are interconnected to be utilized as inputs to SAINT. SAINT has the functions that multi-user can access simultaneously via client-server system, and the safety assessment results can be managed with its embedded Quality Assurance feature. Comparison between assessment results and environmental monitoring data can be made and visualized in SUDAL and SITES-GIS. Also, SUDAL is designed that the periodic monitoring data and information could be opened to the public via internet homepage. SITES has applied to the Wolsong low- and intermediate-level radioactive waste disposal center in Korea, and is expected to enhance the function of site/environment monitoring in other nuclear-related facilities and also in industrial facilities handling hazardous materials.

  20. The C.L.E.A.N. program: Regulating legacy sites

    International Nuclear Information System (INIS)

    Stenson, R.E.; Clement, C.H.

    2002-01-01

    With the coming into force of the Canadian Nuclear Safety and Control Act (NSCA) on May 31, 2000 many sites, that were not subject to licensing under the previous Atomic Energy Control Act (AECA), now required regulatory review and possibly a licence to possess nuclear substances. To ensure consistency in approach, completeness in coverage, and compliance with internal procedures, the Contaminated Lands Evaluation and Assessment Network (CLEAN) program was developed. Over 200 contaminated lands sites required evaluation. Some of the issues and the interim recommendations to the Commission are discussed. (author)

  1. Site characterization progress report: Yucca Mountain, Nevada. Number 15, April 1--September 30, 1996

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1997-04-01

    During the second half of fiscal year 1996, activities at the Yucca Mountain Site Characterization Project (Project) supported the objectives of the revised Program Plan released this period by the Office of Civilian Radioactive Waste Management of the US Department of Energy (Department). Outlined in the revised plan is a focused, integrated program of site characterization, design, engineering, environmental, and performance assessment activities that will achieve key Program and statutory objectives. The plan will result in the development of a license application for repository construction at Yucca Mountain, if the site is found suitable. Activities this period focused on two of the three near-term objectives of the revised plan: updating in 1997 the regulatory framework for determining the suitability of the site for the proposed repository concept and providing information for a 1998 viability assessment of continuing toward the licensing of a repository. The Project has also developed a new design approach that uses the advanced conceptual design published during the last reporting period as a base for developing a design that will support the viability assessment. The initial construction phase of the Thermal Testing Facility was completed and the first phase of the in situ heater tests began on schedule. In addition, phase-one construction was completed for the first of two alcoves that will provide access to the Ghost Dance fault.

  2. Site characterization progress report: Yucca Mountain, Nevada. Number 15, April 1--September 30, 1996

    International Nuclear Information System (INIS)

    1997-04-01

    During the second half of fiscal year 1996, activities at the Yucca Mountain Site Characterization Project (Project) supported the objectives of the revised Program Plan released this period by the Office of Civilian Radioactive Waste Management of the US Department of Energy (Department). Outlined in the revised plan is a focused, integrated program of site characterization, design, engineering, environmental, and performance assessment activities that will achieve key Program and statutory objectives. The plan will result in the development of a license application for repository construction at Yucca Mountain, if the site is found suitable. Activities this period focused on two of the three near-term objectives of the revised plan: updating in 1997 the regulatory framework for determining the suitability of the site for the proposed repository concept and providing information for a 1998 viability assessment of continuing toward the licensing of a repository. The Project has also developed a new design approach that uses the advanced conceptual design published during the last reporting period as a base for developing a design that will support the viability assessment. The initial construction phase of the Thermal Testing Facility was completed and the first phase of the in situ heater tests began on schedule. In addition, phase-one construction was completed for the first of two alcoves that will provide access to the Ghost Dance fault

  3. Study of a conceptual nuclear energy center at Green River, Utah: licensing considerations

    International Nuclear Information System (INIS)

    Dowdle, M.; Russell, R.; Zillman, D.

    1982-04-01

    This report examines the laws governing the location of a 9-unit nuclear energy center (NEC) near Green River, Utah. The time frame being considered for development of the conceptual NEC is from 1995 to 2013. Accordingly, the report is forced to speculate about some aspects of the plant, its site and its construction. Most of the report examines existing legal requirements for constructing an NEC. Where pertinent, changes in the law are discussed that would affect an NEC that is to be licensed in one or two decades. In general, no insurmountable legal problems exist that would prevent an NEC from being licensed at the Green River location. Several legal requirements pose significant concerns and would have to be faced before an NEC could be built. Among the major legal constraints are radiation protection, regulatory approval of financing, access to water, and local zoning restrictions. Two other constraints that involve legal matters are the wisdom of standardization of the units and the responsibility of the NEC builder to correct socio-economic impacts on the local area

  4. NUMARC view of license renewal criteria

    International Nuclear Information System (INIS)

    Edwards, D.W.

    1989-01-01

    The Atomic Energy Act and the implementing regulations of the US Nuclear Regulatory Commission (NRC) permit the renewal of nuclear plant operating licenses upon expiration of their 40-year license term. However, the regulatory process by which license renewal may be accomplished and the requirements for the scope and content of renewal applications are yet to be established. On August 29, 1988, the NRC published an Advanced Notice of Proposed Rulemaking regarding the subject of license renewal. This Advanced Notice and the NUREG which it references, NUREG-1317, Regulatory Options for Nuclear Plant License Renewal, provide the most recent regulatory thought on this issue. The basic issue addressed by NUREG-1317 is the definition of an adequate licensing basis for the renewal of a plant license. The report contemplates three alternatives in this regard. This paper discusses each of these three proposals. The NUMARC NUPLEX Working Group endorses a license renewal process based on a plant's current licensing basis along with an evaluation of the pertinent components, systems, and structures affected by age-related degradation. The NUMARC NUPLEX Working group believes that an appropriate scope for NRC review of the license renewal application should focus on those safety-significant structures systems, and components subject to significant age-related degradation that are not subject to existing recognized effective replacement, refurbishment, or inspection programs. The paper also briefly discusses NUMARC's view of the role of the Backfit Rule in the license renewal process

  5. Graduated driver licensing and differential deterrence: The effect of license type on intentions to violate road rules.

    Science.gov (United States)

    Poirier, Brigitte; Blais, Etienne; Faubert, Camille

    2018-01-01

    In keeping with the differential deterrence theory, this article assesses the moderating effect of license type on the relationship between social control and intention to violate road rules. More precisely, the article has two objectives: (1) to assess the effect of license type on intentions to infringe road rules; and (2) to pinpoint mechanisms of social control affecting intentions to violate road rules based on one's type of driver license (a restricted license or a full license). This effect is examined among a sample of 392 young drivers in the province of Quebec, Canada. Drivers taking part in the Graduated Driver Licensing (GDL) program have limited demerit points and there is zero tolerance for drinking-and-driving. Propensity score matching techniques were used to assess the effect of the license type on intentions to violate road rules and on various mechanisms of social control. Regression analyses were then conducted to estimate the moderating effect of license type. Average treatment effects from propensity score matching analyses indicate that respondents with a restricted license have lower levels of intention to infringe road rules. While moral commitment and, to a lesser extent, the perceived risk of arrest are both negatively associated with intentions to violate road rules, the license type moderates the relationship between delinquent peers and intentions to violate road rules. The effect of delinquent peers is reduced among respondents with a restricted driver license. Finally, a diminished capability to resist peer pressure could explain the increased crash risk in months following full licensing. Copyright © 2017 Elsevier Ltd. All rights reserved.

  6. Licensing of nuclear facilities according to the Bulgarian Act on the Safe Use of Nuclear Energy

    International Nuclear Information System (INIS)

    Stoyanova-Todorova, P.

    2004-01-01

    The new Bulgarian Act on the Safe Use of Nuclear Energy /Nuclear Act/ has replaced the former Act on the Use of Nuclear Energy for Peaceful Purposes. The new Nuclear Act covers the activities involving nuclear energy and sources of ionising radiation mainly by establishing a consistent licensing regime. About 13 regulations specifying the provisions of the Nuclear Act have been recently adopted by the Council of Ministers, the most important one being the Regulation on the Procedure for Issue of Licenses and Permits for the Safe Use of Nuclear Energy. The Chairman of the Nuclear Regulatory Agency (NRA) is authorised by the law to consider any application for issue of a license or a permit under the Bulgarian Nuclear Act. The procedure starts with an application, filed with the NRA, and continues about nine months. The final decision could be for issuing of the license or permit or a refusal for issuing the claimed document. The denial must be grounded and is subject to appeal. The Nuclear Act prescribes the conditions for issuing of two types of licensing documents (authorisations): licenses and permits. From a legal point of view the two types of licensing documents have one and the same nature - they are individual administrative acts according to the Bulgarian law. That is why there is no difference between them in terms of the issuing procedure. The difference between licenses and permits could be explained as follows: while a license is issued for reiterated activities, a permit is issued for non-reoccurring activities, this division being a specific feature of the Bulgarian Nuclear Act. In the field of nuclear facilities usage only one type of license is provided for by the Nuclear Act - a license for operation of a nuclear facility unit. For the rest of the activities issuing of permits is envisaged, those permits being in compliance with the main stages of the authorisation process formulated by the IAEA, following the step-by-step approach - siting, design

  7. 77 FR 62520 - Prospective Grant of Exclusive License: The Development of Anti-CD22 Chimeric Antigen Receptors...

    Science.gov (United States)

    2012-10-15

    ... Exclusive License: The Development of Anti- CD22 Chimeric Antigen Receptors (CARs) for the Treatment of B... ``Anti-CD22 Chimeric Antigen Receptors'' [HHS Ref. E-265-2011/0-US-01], and (b) U.S. Patent Application... CD22 on their cell surface using chimeric antigen receptors which contain the HA22 or BL22 antibody...

  8. Licensing assessment of the Candu Pressurized Heavy Water Reactor. Preliminary safety information document. Volume II

    International Nuclear Information System (INIS)

    1977-06-01

    ERDA has requested United Engineers and Constructors (UE and C) to evaluate the design of the Canadian natural uranium fueled, heavy water moderated (CANDU) nuclear reactor power plant to assess its conformance with the licensing criteria and guidelines of the U.S. Nuclear Regulatory Commission (USNRC) for light water reactors. This assessment was used to identify cost significant items of nonconformance and to provide a basis for developing a detailed cost estimate for a 1140 MWe, 3-loop Pressurized Heavy Water Reactor (PHWR) located at the Middletown, USA Site

  9. The Design and Development of Driving Game as an Evaluation Instrument for Driving License Test

    OpenAIRE

    Abdul Hadi Abdul Razak; Mohd Hairy Manap

    2013-01-01

    The focus of this paper is to highlight the design and development of an educational game prototype as an evaluation instrument for the Malaysia driving license static test. This educational game brings gaming technology into the conventional objective static test to make it more effective, real and interesting. From the feeling of realistic, the future driver can learn something, memorized and use it in the real life. The current online objective static test only make th...

  10. 22 CFR 96.30 - State licensing.

    Science.gov (United States)

    2010-04-01

    ... Licensing and Corporate Governance § 96.30 State licensing. (a) The agency or person is properly licensed or... person follows applicable State licensing and regulatory requirements in all jurisdictions in which it provides adoption services. (c) If it provides adoption services in a State in which it is not itself...

  11. Operating reactors licensing actions summary

    International Nuclear Information System (INIS)

    1982-07-01

    The operating reactors licensing actions summary is designed to provide the management of the Nuclear Regulatory Commission (NRC) with an overview of licensing actions dealing with operating power and nonpower reactors. These reports utilize data collected from the Division of Licensing in the Office of Nuclear Reactor Regulation and are prepared by the Office of Management and Program Analysis. This summary report is published primarily for internal NRC use in managing the operating reactors licensing actions program. Its content will change based on NRC management informational requirements

  12. Operating reactors licensing actions summary

    International Nuclear Information System (INIS)

    1982-05-01

    The operating reactors licensing actions summary is designed to provide the management of the Nuclear Regulatory Commission (NRC) with an overview of licensing actions dealing with operating power and nonpower reactors. These reports utilize data collected from the Division of Licensing in the Office of Nuclear Reactor Regulation and are prepared by the Office of Management and Program Analysis. This summary report is published primarily for internal NRC use in managing the operating reactors licensing actions program. Its content will change based on NRC management informational requirements

  13. Operating reactors licensing actions summary

    International Nuclear Information System (INIS)

    1983-01-01

    The operating reactors licensing actions summary is designed to provide the management of the Nuclear Regulatory Commission (NRC) with an overview of licensing actions dealing with operating power and nonpower reactors. These reports utilize data collected from the Division of Licensing in the Office of Nuclear Reactor Regulation and are prepared by the Office of Management and Program Analysis. This summary report is published primarily for internal NRC use in managing the operating reactors licensing actions program. Its content will change based on NRC management informational requirements

  14. Operating reactors licensing actions summary

    International Nuclear Information System (INIS)

    1983-03-01

    The operating reactors licensing actions summary is designed to provide the management of the Nuclear Regulatory Commission (NRC) with an overview of licensing actions dealing with operating power and nonpower reactors. These reports utilize data collected from the Division of Licensing in the Office of Nuclear Reactor Regulation and are prepared by the Office of Management and Program Analysis. This summary report is published primarily for internal NRC use in managing the operating reactors licensing actions program. Its content will change based on NRC management informational requirements

  15. Operating reactors licensing actions summary

    International Nuclear Information System (INIS)

    1982-11-01

    The operating reactors licensing actions summary is designed to provide the management of the Nuclear Regulatory Commission (NRC) with an overview of licensing actions dealing with operating power and nonpower reactors. These reports utilize data collected from the Division of Licensing in the Office of Nuclear Reactor Regulation and are prepared by the Office of Management and Program Analysis. This summary report is published primarily for internal NRC use in managing the operating reactors licensing actions program. Its content will change based on NRC management informational requirements

  16. Operating reactors licensing actions summary

    International Nuclear Information System (INIS)

    1982-10-01

    The operating reactors licensing actions summary is designed to provide the management of the Nuclear Regulatory Commission (NRC) with an overview of licensing actions dealing with operating power and nonpower reactors. These reports utilize data collected from the Division of Licensing in the Office of Nuclear Reactor Regulation and are prepared by the Office of Management and Program Analysis. This summary report is published primarily for internal NRC use in managing the operating reactors licensing actions program. Its content will change based on NRC management informational requirements

  17. Operating reactors licensing actions summary

    International Nuclear Information System (INIS)

    1982-08-01

    The operating reactors licensing actions summary is designed to provide the management of the Nuclear Regulatory Commission (NRC) with an overview of licensing actions dealing with operating power and nonpower reactors. These reports utilize data collected from the Division of Licensing in the Office of Nuclear Reactor Regulation and are prepared by the Office of Management and Program Analysis. This summary report is published primarily for internal NRC use in managing the operating reactors licensing actions program. Its content will change based on NRC management informational requirements

  18. Operating reactors licensing actions summary

    International Nuclear Information System (INIS)

    1982-09-01

    The operating reactors licensing actions summary is designed to provide the management of the Nuclear Regulatory Commission (NRC) with an overview of licensing actions dealing with operating power and nonpower reactors. These reports utilize data collected from the Division of Licensing in the Office of Nuclear Reactor Regulation and are prepared by the Office of Management and Program Analysis. This summary report is published primarily for internal NRC use in managing the operating reactors licensing actions program. Its content will change based on NRC management informational requirements

  19. Environmental assessment for renewal and consolidation of Materials License Nos. SNM-362, SMB-405, 08-00566-05, 08-00566-10, and 08-00566-12 (Docket No. 70-398)

    International Nuclear Information System (INIS)

    1985-03-01

    The proposed action for which this Environmental Assessment is prepared is the renewal and consolidation of five nuclear materials licenses for radiological activities at the National Bureau of Standards (NBS) site. These licenses cover most uses of radioactive material at NBS except that controlled by the license for operation of the NBS reactor. The reactor license is not associated with and will not be affected by the currently proposed licensing action

  20. The developing one door licensing service system based on RESTful oriented services and MVC framework

    Science.gov (United States)

    Widiyanto, Sigit; Setyawan, Aris Budi; Tarigan, Avinanta; Sussanto, Herry

    2016-02-01

    The increase of the number of business impact on the increasing service requirements for companies and Small Medium Enterprises (SMEs) in submitting their license request. The service system that is needed must be able to accommodate a large number of documents, various institutions, and time limitations of applicant. In addition, it is also required distributed applications which is able to be integrated each other. Service oriented application fits perfectly developed along client-server application which has been developed by the Government to digitalize submitted data. RESTful architecture and MVC framework are embedded in developing application. As a result, the application proves its capability in solving security, transaction speed, and data accuracy issues.

  1. PC-based car license plate reader

    Science.gov (United States)

    Hwang, Chung-Mu; Shu, Shyh-Yeong; Chen, Wen-Yu; Chen, Yie-Wern; Wen, Kuang-Pu

    1992-11-01

    A car license plate reader (CLPR) using fuzzy inference and neural network algorithm has been developed in Industrial Technology Research Institute (ITRI) and installed in highway toll stations to identify stolen cars. It takes an average of 0.7 seconds to recognize a car license plate by using a PC with 80486-50 CPU. The recognition rate of the system is about 97%. The techniques of CLPR include vehicle sensing, image grab control, optic pre- processing, lighting, and optic character recognition (OCR). The CLPR can be used in vehicle flow statistics, the checking of stolen vehicles, automatic charging systems in parking lots or garage management, and so on.

  2. Operator licensing examiner standards

    International Nuclear Information System (INIS)

    1994-06-01

    The Operator Licensing Examiner Standards provide policy and guidance to NRC examiners and establish the procedures and practices for examining licensees and applicants for reactor operator and senior reactor operator licenses at power reactor facilities pursuant to Part 55 of Title 10 of the Code of Federal Regulations (10 CFR 55). The Examiner Standards are intended to assist NRC examiners and facility licensees to better understand the initial and requalification examination processes and to ensure the equitable and consistent administration of examinations to all applicants. These standards are not a substitute for the operator licensing regulations and are subject to revision or other internal operator licensing policy changes. Revision 7 was published in January 1993 and became effective in August 1993. Supplement 1 is being issued primarily to implement administrative changes to the requalification examination program resulting from the amendment to 10 CFR 55 that eliminated the requirement for every licensed operator to pass an NRC-conducted requalification examination as a condition for license renewal. The supplement does not substantially alter either the initial or requalification examination processes and will become effective 30 days after its publication is noticed in the Federal Register. The corporate notification letters issued after the effective date will provide facility licensees with at least 90 days notice that the examinations will be administered in accordance with the revised procedures

  3. SMART-P MMIS Software Development by Considering the Software License for Nuclear Power Plants and the Development Cost

    International Nuclear Information System (INIS)

    Suh, Yong Suk; Park, Jae Hong; Park, Heui Youn; Son, Ki Sung; Lee, Ki Hyun; Kim, Hyeon Soo

    2005-01-01

    The acceptance criteria of software for safety system functions in NPPs (Nuclear Power Plants) are as follows: 1) acceptable plans should be prepared to control the software development activities, 2) the plans should be followed in an acceptable software life cycle, and 3) the process should produce acceptable design outputs. The KINS (Korea Institute of Nuclear Safety) recommended that the software life cycle should be established based on the IEEE Std 1074 with a supplementary requirement of a software safety analysis. The KINS emphasized that the software should be developed to show its high qualities. This paper identifies the major requirements to achieve the software license from the KINS and presents the major facts reflected in the SMART-P (System-integrated Modular Advanced ReacTor-Pilot) MMIS (Man-Machine Interface Systems) which is being developed by KAERI and targeted to start operation in 2010. This paper also addresses major concerns on the development of a safety critical software and the facts reflected in the SMART-P MMIS

  4. Licensing in an International Market

    Science.gov (United States)

    Ferreira, Fernanda A.

    2008-09-01

    We study the effects of entry of a foreign firm on domestic welfare in the presence of licensing, when the entrant is technologically superior to the incumbent. We show that foreign entry increases domestic welfare for sufficiently large technological differences between the firms under both fixed-fee licensing and royalty licensing.

  5. 22 CFR 120.20 - License.

    Science.gov (United States)

    2010-04-01

    ... 22 Foreign Relations 1 2010-04-01 2010-04-01 false License. 120.20 Section 120.20 Foreign Relations DEPARTMENT OF STATE INTERNATIONAL TRAFFIC IN ARMS REGULATIONS PURPOSE AND DEFINITIONS § 120.20 License. License means a document bearing the word “license” issued by the Directorate of Defense Trade...

  6. Decisions on sites by Laender parliaments

    International Nuclear Information System (INIS)

    1977-01-01

    The Vereinigung Deutscher Elektrizitaetswerke (VDEW, Association of German Electricity Utilities) proposes two independent steps in the licensing procedure for each nuclear power plant constuction project: one first phase in which to establish site guarantees, and one licensing phase for construction and operation of the power plant. The first phase should henceforth proceed with the active participation of the public involved within the framework of a plans approval procedure. The novel aspect would be the binding clarification in this procedure not only of the nuclear aspects of the case, as formerly, but of all public aspects relating to the site. The construction and operating permits, which would constitute phase two, could then be handled in the usual procedure without any need for urgency. (orig.) [de

  7. Licensing the First Nuclear Power Plant. INSAG-26. A report by the International Nuclear Safety Group (Russian Edition)

    International Nuclear Information System (INIS)

    2016-01-01

    countries having nuclear power plants of similar design, and the various technical cooperation activities conducted by international organizations, in particular the IAEA. The first major task for the regulatory body will be carrying out a review of the safety evaluation report of the proposed site for the first nuclear power plant. For this, the regulatory body must lay down the safety requirements that could be developed or adopted from IAEA safety standards on the subject. It will also require a set of specialized competences in areas such as seismology, hydrology, geochemistry and geology that is not necessarily nuclear related. In developing the strategy to secure and maintain a technically competent regulatory body, a decision should be made early whether to recruit staff with those competences or to outsource these activities to agencies where competences in such areas may already be available in the country. Notwithstanding this, the regulatory body still requires a core technical group in the key disciplines to be able to understand and compile the information from the site evaluation reports as input to the site licensing process

  8. Current status of construction license of PEFP

    International Nuclear Information System (INIS)

    Kim, J. Y.; Cho, J. S.; Min, Y. S.; Nam, J. M.; Jeon, G. P.; Park, S. S.; Jo, J. H.; Song, I. T.

    2012-01-01

    Since 2010 August, PEFP(Proton Engineering Frontier Project)'s Proton Accelerator Research Center has been under construction so far. Generally, in advance of construction startup, many kinds of licenses should be acquired along with the types of construction works. To acquire a license in time, each item should meet the standard by the related regulation, including not only procedural but also content aspect. In the advent of internet era, electronic government system has been adopted in many governmental functions: So is the national construction license acquisition system. Owing to the system, both approval and documentation functions in licensing are integrated in online computer network which provide us simplification in process and easy accessibility to license data. However, aside from these construction licenses, other types of licenses still remain separately managed: Machinery, electric facilities, and so on. Moreover, all the licenses have the priority order and take legal term in processing. So, to avoid any time delay in license acquisition, we organized license hierarchy and found out the priority among them. Thereafter, according to their legal term in approval and acquisition, whole license acquisition schedule was arranged and we completed all the necessary licenses acquisition in time In this study, we summarize the current status of license acquisition on Proton Accelerator Research Center Construction, and manifest how they have been and will be managed systematically

  9. Current status of construction license of PEFP

    Energy Technology Data Exchange (ETDEWEB)

    Kim, J. Y.; Cho, J. S.; Min, Y. S.; Nam, J. M.; Jeon, G. P.; Park, S. S.; Jo, J. H.; Song, I. T. [KAERI, Daejeon (Korea, Republic of)

    2012-10-15

    Since 2010 August, PEFP(Proton Engineering Frontier Project)'s Proton Accelerator Research Center has been under construction so far. Generally, in advance of construction startup, many kinds of licenses should be acquired along with the types of construction works. To acquire a license in time, each item should meet the standard by the related regulation, including not only procedural but also content aspect. In the advent of internet era, electronic government system has been adopted in many governmental functions: So is the national construction license acquisition system. Owing to the system, both approval and documentation functions in licensing are integrated in online computer network which provide us simplification in process and easy accessibility to license data. However, aside from these construction licenses, other types of licenses still remain separately managed: Machinery, electric facilities, and so on. Moreover, all the licenses have the priority order and take legal term in processing. So, to avoid any time delay in license acquisition, we organized license hierarchy and found out the priority among them. Thereafter, according to their legal term in approval and acquisition, whole license acquisition schedule was arranged and we completed all the necessary licenses acquisition in time In this study, we summarize the current status of license acquisition on Proton Accelerator Research Center Construction, and manifest how they have been and will be managed systematically.

  10. Technology Licensing and Firm Innovation

    DEFF Research Database (Denmark)

    Moreira, Solon

    acquisition. The findings indicate that technology licensing is positively related to the number of inventions produced by the licensee in the years subsequent to the licensing deal. Subsequently, I investigate the moderating effect that organizational slack and myopia have on this main relationship....... The findings also suggest that high levels of Organizational Slack (available financial resources) strengthen the positive effect of licensing on innovation. However, higher levels of Organizational Myopia (the extent to which a firm draws on its own knowledge) can decrease the main effect of licensing....

  11. 31 CFR 596.309 - Specific license.

    Science.gov (United States)

    2010-07-01

    ... FOREIGN ASSETS CONTROL, DEPARTMENT OF THE TREASURY TERRORISM LIST GOVERNMENTS SANCTIONS REGULATIONS General Definitions § 596.309 Specific license. The term specific license means any license or...

  12. License Agreements | NCI Technology Transfer Center | TTC

    Science.gov (United States)

    NCI Technology Transfer Center (TTC) licenses the discoveries of NCI and nine other NIH Institutes so new technologies can be developed and commercialized, to convert them into public health benefits.

  13. 31 CFR 596.305 - General license.

    Science.gov (United States)

    2010-07-01

    ... FOREIGN ASSETS CONTROL, DEPARTMENT OF THE TREASURY TERRORISM LIST GOVERNMENTS SANCTIONS REGULATIONS General Definitions § 596.305 General license. The term general license means any license or authorization...

  14. Architecture and Development of DCMP Web Site

    Science.gov (United States)

    Bariakhtar, Irina

    2003-03-01

    The multi-tier implementation of DCMP Web site is discussed. It is based upon newly developed PHP technology. The technology allows for creating dynamic content and scalable solutions for Web site capabilities. There are several aspects as to what type of information is to be on the site. First, it should serve the immediate needs of the researchers in the field, namely, conferences, journals, news, funds, etc. This is currently available on the site, but can be extended and improved if needed. Second, the site will reflect the connection between Condensed matter physics and the technological breakthroughs that drive the economy. Third, the site will carry an educational mission helping educate the general public, and on the other hand, help young people to start their careers in the field. The content of the DCMP Web site is under active development. It depends upon wide involvement of DCMP members.

  15. EMPIRICAL STUDY OF CAR LICENSE PLATES RECOGNITION

    Directory of Open Access Journals (Sweden)

    Nasa Zata Dina

    2015-01-01

    Full Text Available The number of vehicles on the road has increased drastically in recent years. The license plate is an identity card for a vehicle. It can map to the owner and further information about vehicle. License plate information is useful to help traffic management systems. For example, traffic management systems can check for vehicles moving at speeds not permitted by law and can also be installed in parking areas to se-cure the entrance or exit way for vehicles. License plate recognition algorithms have been proposed by many researchers. License plate recognition requires license plate detection, segmentation, and charac-ters recognition. The algorithm detects the position of a license plate and extracts the characters. Various license plate recognition algorithms have been implemented, and each algorithm has its strengths and weaknesses. In this research, I implement three algorithms for detecting license plates, three algorithms for segmenting license plates, and two algorithms for recognizing license plate characters. I evaluate each of these algorithms on the same two datasets, one from Greece and one from Thailand. For detecting li-cense plates, the best result is obtained by a Haar cascade algorithm. After the best result of license plate detection is obtained, for the segmentation part a Laplacian based method has the highest accuracy. Last, the license plate recognition experiment shows that a neural network has better accuracy than other algo-rithm. I summarize and analyze the overall performance of each method for comparison.

  16. Fuel licensing process for an industrial use. ATF licensing process for an industrial use - Utility's perspective

    International Nuclear Information System (INIS)

    Waeckel, Nicolas

    2013-01-01

    To develop and license a breakthrough nuclear fuel technology for commercial use is becoming challenging. All the former safety analysis design limits (SAFDLs) defined in the 1970's for the standard UO 2 -Zr fuels, might no longer be applicable. Identification of the appropriate safety analysis design limits For each type of innovative fuel, the developers will have to identify and investigate all the possible failure/ruins scenarios (not only those related to severe accidents but also those related to normal operation). In order to save time and to focus on the best options, those failure scenarios (which could be 'killers' for the ATF concept) have to be determined early enough in the development process. Based on the above failure scenarios, the developers will have to propose the licensing limits (and the experimental protocol to determine and to justify them). As mentioned earlier, the licensing limits should not be defined against the accidental conditions only. For the operators, the (good) in-reactor fuel behaviour is crucial. As an example, in the case of the new fuel concepts coming with an outer coating, it is important to include the analysis of the consequences of the loss of this protective outer layer in the licensing process due to a manufacturing defect or an inevitable in-reactor fretting wear. Obviously, the new/specific SAFDLs will have to be endorsed by the regulators (which could be a long process by itself). Identification of a commercial reactor to irradiate the first ATF A commercial NPP is not a material test reactor (MTR); irradiating lead test fuel rods (LTFRs) or lead test assemblies (LTAs) implies strict requirements regarding the manufacturing processes [which should not include chemicals (additives or solvents) potentially incompatible with the nuclear technical specifications], the compatibility with the hosting fuel core (in terms of geometry, enrichment, thermal hydraulic performances, etc.) and the robustness and

  17. Operating reactors licensing actions summary

    International Nuclear Information System (INIS)

    1982-04-01

    The operating reactors licensing actions summary is designed to provide the management of the Nuclear Regulatory Commission (NRC) with an overview of licensing actions dealing with operating power and nonpower reactors. These reports utilize data collected from the Division of Licensing in the Office of Nuclear Reactor Regulation and are prepared by the Office of Management and Program Analysis

  18. A comparative analysis of the domestic and foreign licensing processes for power and non-power reactors

    International Nuclear Information System (INIS)

    Joe, J. C.; Youn, Y. K.; Kim, W. S.; Kim, H. J.

    2003-01-01

    The System-integrated Modular Advanced Reactor (SMART), a small to medium sized integral type Pressurized Water Reactor (PWR) has been developed in Korea. Now, SMART-P, a 1/5 scaled-down of the SMART, is being developed for the purpose of demonstrating the safety and performance of SMART design. The SMART-P is a first-of-a-kind reactor which is utilized for the research and development of a power reactor. Since the licensing process of such a reactor is not clearly specified in the current Atomic Energy Act, a comparative survey and analysis of domestic and foreign licensing processes for power and non-power reactors has been carried out to develop the rationale and technical basis for establishing the licensing process of such a reactor. The domestic and foreign licensing processes of power and non-power reactors have been surveyed and compared, including those of the U.S.A., Japan, France, U.K., Canada, and IAEA. The general trends in nuclear reactor classification, licensing procedures, regulatory technical requirements, and other licensing requirements and regulations have been investigated. The results of this study will be used as the rationale and technical basis for establishing the licensing process of reactors at development stage such as SMART-P

  19. A BWR licensing experience in the USA

    International Nuclear Information System (INIS)

    Powers, J.; Ogura, C.; Arai, K.; Thomas, S.; Mookhoek, B.

    2015-09-01

    The US-Advanced Boiling Water Reactor (A BWR), certified by the United States Nuclear Regulatory Commission (US NRC), is a third generation, evolutionary boiling water reactor design which is the reference for the South Texas Project Units 3 and 4 (STP3-4) Combined License Application (Cola). Nuclear Innovation North America (Nina) is the License Applicant for this new build project, and Toshiba is the selected primary technology contractor. The STP3-4 project has finished the US NRC technical review of the Cola through the final meeting of the Advisory Committee on Reactor Safeguards (ACRS), and the Final Safety Evaluation Report (FSER) is scheduled to be issued by the US NRC in the middle of 2015. The next steps are to support the Mandatory Hearing process, and voting by the NRC commissioners on the motion to grant the Combined License, which is scheduled beginning of 2016 according to US NRC schedule as of March 30, 2015. This paper summarizes the history and progress of the US-A BWR licensing, including the experiences of the Licensee, Nina, and Toshiba as the Epc team worked through the Code of Federal Regulations Title 10 (10-Cfr) Part 52 process, and provides some perspectives on how the related licensing material would also be of value within a 10-Cfr Part 50, two-step process to minimize schedule and financial risks which could arise from ongoing technical developments and regulatory reviews. (Author)

  20. A BWR licensing experience in the USA

    Energy Technology Data Exchange (ETDEWEB)

    Powers, J.; Ogura, C. [Toshiba America Nuclear Energy, Charlotte, North Carolina (United States); Arai, K. [Toshiba Corporation, Yokohama, Kanagawa (Japan); Thomas, S.; Mookhoek, B., E-mail: jim.powers@toshiba.com [Nuclear Innovation North America, Lake Jackson, Texas (United States)

    2015-09-15

    The US-Advanced Boiling Water Reactor (A BWR), certified by the United States Nuclear Regulatory Commission (US NRC), is a third generation, evolutionary boiling water reactor design which is the reference for the South Texas Project Units 3 and 4 (STP3-4) Combined License Application (Cola). Nuclear Innovation North America (Nina) is the License Applicant for this new build project, and Toshiba is the selected primary technology contractor. The STP3-4 project has finished the US NRC technical review of the Cola through the final meeting of the Advisory Committee on Reactor Safeguards (ACRS), and the Final Safety Evaluation Report (FSER) is scheduled to be issued by the US NRC in the middle of 2015. The next steps are to support the Mandatory Hearing process, and voting by the NRC commissioners on the motion to grant the Combined License, which is scheduled beginning of 2016 according to US NRC schedule as of March 30, 2015. This paper summarizes the history and progress of the US-A BWR licensing, including the experiences of the Licensee, Nina, and Toshiba as the Epc team worked through the Code of Federal Regulations Title 10 (10-Cfr) Part 52 process, and provides some perspectives on how the related licensing material would also be of value within a 10-Cfr Part 50, two-step process to minimize schedule and financial risks which could arise from ongoing technical developments and regulatory reviews. (Author)

  1. Licensing procedure and requirements in the FRG

    International Nuclear Information System (INIS)

    Brosche, D.

    1981-01-01

    The investigations of the different dynamic stresses of pressure suppression systems after the Wuergassen incident in 1972 and their theoretical and experimental solutions required an extraordinary effort from all participants of the licensing procedures. As a consequence of these new problems a lot of mathematical models and computer codes had been developed and a lot of experimental work had been performed. Numerous highly qualified scientists and engineers had been involved for a long time in the licensing procedures and innumerable discussions had been necessary. These investigations and discussions had a great influence on the licensing procedures and on the project running. Too pessimistic assumptions and wrong interpretations of experiments led to fictitious problems and a lot of time and money was necessary to overcome these difficulties. Finally at 1977 it could be proved that the construction was able to control stresses so that additional investigations were not necessary. (orig./HP)

  2. Site characterization progress report: Yucca Mountain, Nevada. October 1, 1996--March 31, 1997

    International Nuclear Information System (INIS)

    1997-10-01

    The report is the sixteenth in a series issued approximately every six months to report progress and results of site characterization activities being conducted to evaluate Yucca Mountain as a possible geologic repository for the disposal of spent nuclear fuel and high-level radioactive waste. This report highlights work started, in progress, and completed during the reporting period. In addition, this report documents and discusses changes to the Office of Civilian Radioactive Waste Management (OCRWM) Site Characterization Program (Program) resulting from the ongoing collection and evaluation of site information, systems analyses, development of repository and waste package designs, and results of performance assessment activities. Details on the activities summarized can be found in the numerous technical reports cited throughout the progress report. Yucca Mountain Site Characterization Project (Project) activities this period focused on implementing the near-term objectives of the revised Program Plan issued last period. Near-term objectives of the revised Program Plan include updating the US Department of Energy's (DOE) repository siting guidelines to be consistent with a more focused performance-driven program; supporting an assessment in 1998 of the viability of continuing with actions leading to the licensing of a repository; and if the site is suitable, submittal of a Secretarial site recommendation to the President in 2001 and license application the US Nuclear Regulatory Commission (NRC) in 2002. During this reporting period, the Project developed and baselined its long-range plan in December 1996. That revision reflected the detailed fiscal year (FY) 1997 work scope and funding plan previously baselined at the end of FY 1996. Site characterization activities have been focused to answer the major open technical issues and to support the viability assessment

  3. Licensing assessment of the CANDU pressurized heavy water reactor. Volume I. Preliminary safety information document

    International Nuclear Information System (INIS)

    1977-06-01

    The PHWR design contains certain features that will require significant modifications to comply with USNRC siting and safety requirements. The most significant of these features are the reactor vessel; control systems; quality assurance program requirements; seismic design of structures, systems and components; and providing an inservice inspection program capability. None of these areas appear insolvable with current state-of-the-art engineering or with upgrading of the quality assurance program for components constructed outside of the USA. In order to be licensed in the U. S., the entire reactor assembly would have to be redesigned to comply with ASME Boiler and Pressure Vessel Code, Section III, Division 1 and Division 2. A summary matrix at the end of this volume identifies compliance of the systems and structures of the PHWR plant with the USNRC General Design Criteria. The matrix further identifies the estimated incremental cost to a 600 MWe PHWR that would be required to license the plant in the U. S. Further, the matrix identifies whether or not the incremental licensing cost is size dependent and the relative percentage of the base direct cost of a Canadian sited plant

  4. Managing Licensing in a Market for Technology

    DEFF Research Database (Denmark)

    Arora, Ashish; Rønde, Thomas; Fosfuri, Andrea

    the technology makes licensing decisions—to centralized licensing. The business unit has superior information about licensing opportunities but may not have the appropriate incentives because its rewards depend upon product market performance. If licensing is decentralized, the business unit forgoes valuable...... licensing opportunities since the rewards for licensing are (optimally) weaker than those for product market profits. This distortion is stronger when production-based incentives are more powerful, making centralization more attractive. Growth of technology markets favors centralization and drives higher...

  5. Licensing of ANSTO'S OPAL reactor during construction and commissioning

    International Nuclear Information System (INIS)

    Summerfield, M.W.; Ordonez, J.P.

    2006-01-01

    Full text: This paper presents a general description of the ongoing licensing activities associated with the construction and commissioning of the Australian Nuclear Science and Technology Organisation's (ANSTO) Open Pool Australian Light-water (OPAL) Reactor at their Lucas Heights site. It addresses the following aspects: The Construction Licence - what it is and what impact it had on the construction of the OPAL Reactor, specifically the various Construction Licence Conditions; The interface between ANSTO, INVAP and ARPANSA during the construction of the OPAL Reactor, particularly in relation to ARPANS Regulation 54; Specific licensing issues that have arisen during the construction and commissioning process and how they have been resolved; The Operating Licence Application - what it is and how it interfaces with the construction and commissioning of the OPAL Reactor. These aspects are all addressed from the point of view of the licensee ANSTO and the RRR Project. Particular emphasis will be given to the way in which the licensing process is integrated into the overall project program and the lessons learnt that may be of benefit to other licensees and regulators. Note that this paper is an update of a presentation given at IGORR10 and follows on from a paper previously presented at PNBC12 in October 2002

  6. Site decommissioning management plan

    International Nuclear Information System (INIS)

    Fauver, D.N.; Austin, J.H.; Johnson, T.C.; Weber, M.F.; Cardile, F.P.; Martin, D.E.; Caniano, R.J.; Kinneman, J.D.

    1993-10-01

    The Nuclear Regulatory Commission (NRC) staff has identified 48 sites contaminated with radioactive material that require special attention to ensure timely decommissioning. While none of these sites represent an immediate threat to public health and safety they have contamination that exceeds existing NRC criteria for unrestricted use. All of these sites require some degree of remediation, and several involve regulatory issues that must be addressed by the Commission before they can be released for unrestricted use and the applicable licenses terminated. This report contains the NRC staff's strategy for addressing the technical, legal, and policy issues affecting the timely decommissioning of the 48 sites and describes the status of decommissioning activities at the sites

  7. Site decommissioning management plan

    Energy Technology Data Exchange (ETDEWEB)

    Fauver, D.N.; Austin, J.H.; Johnson, T.C.; Weber, M.F.; Cardile, F.P.; Martin, D.E.; Caniano, R.J.; Kinneman, J.D.

    1993-10-01

    The Nuclear Regulatory Commission (NRC) staff has identified 48 sites contaminated with radioactive material that require special attention to ensure timely decommissioning. While none of these sites represent an immediate threat to public health and safety they have contamination that exceeds existing NRC criteria for unrestricted use. All of these sites require some degree of remediation, and several involve regulatory issues that must be addressed by the Commission before they can be released for unrestricted use and the applicable licenses terminated. This report contains the NRC staff`s strategy for addressing the technical, legal, and policy issues affecting the timely decommissioning of the 48 sites and describes the status of decommissioning activities at the sites.

  8. Licensing system for primary category radioactive installations

    International Nuclear Information System (INIS)

    Ramirez Riquelme, Angelica Beatriz

    1997-01-01

    The development of a licensing system for primary category radioactive installations is described, which aims to satisfy the needs of the Chilean Nuclear Energy Commission's Department of Nuclear and Radiological Safety, particularly the sections for Licensing Outside Radioactive Installations and Safety Control. This system involves the identification, control and inspection of the installations, their personnel and connected activities, for the purpose of protecting the population's health and the environment. Following the basic cycle methodology, a systems analysis and engineering stage was prepared, establishing the functions of the system's elements and defining the requirements, based on interviews with the users. This stage was followed by the design stage, focusing on the data structure, the software architecture and the procedural detail. The codification stage followed, which translated the design into legible machine-readable format. In the testing stage, the entries that were defined were proven to produce the expected data. Finally and operational and maintenance stage was developed, when the system was installed and put to use. All the above generated a useful system for the Licensing section of the Department of Nuclear and Radiological Safety, since it provides faster and easier access to information. A project is described that introduces new development tools in the Computer department following standards established by the C.CH.E.N. (author)

  9. Safety and licensing analyses for the Fort St. Vrain HTGR

    International Nuclear Information System (INIS)

    Ball, S.J.; Conklin, J.C.; Harrington, R.M.; Cleveland, J.C.; Clapp, N.E. Jr.

    1982-01-01

    The Oak Ridge National Laboratory (ORNL) safety analysis program for the HTGR includes development and verification of system response simulation codes, and applications of these codes to specific Fort St. Vrain reactor licensing problems. Licensing studies addressed the oscillation problems and the concerns about large thermal stresses in the core support blocks during a postulated accident

  10. Application of up-front licensing

    Energy Technology Data Exchange (ETDEWEB)

    Grant, S D [Atomic Energy of Canada Ltd., Saskatoon, SK (Canada); Snell, V G [Atomic Energy of Canada Ltd., Mississauga, ON (Canada)

    1996-12-31

    AECL has been pioneering `up-front` licensing of new reactor designs. The CANDU 3 design has been formally reviewed by AECB staff for a number of years. The CANDU 9 design has just started the up-front licensing process. The process gives designers, regulators and potential customers early confidence in the licensability of future plants. (author). 4 refs., 2 tabs.

  11. Application of up-front licensing

    International Nuclear Information System (INIS)

    Grant, S.D.; Snell, V.G.

    1995-01-01

    AECL has been pioneering 'up-front' licensing of new reactor designs. The CANDU 3 design has been formally reviewed by AECB staff for a number of years. The CANDU 9 design has just started the up-front licensing process. The process gives designers, regulators and potential customers early confidence in the licensability of future plants. (author). 4 refs., 2 tabs

  12. Policy development for environmental licensing and biodiversity offsets in Latin America.

    Directory of Open Access Journals (Sweden)

    Ana Villarroya

    Full Text Available Attempts to meet biodiversity goals through application of the mitigation hierarchy have gained wide traction globally with increased development of public policy, lending standards, and corporate practices. With interest in biodiversity offsets increasing in Latin America, we seek to strengthen the basis for policy development through a review of major environmental licensing policy frameworks in Argentina, Brazil, Chile, Colombia, Mexico, Peru and Venezuela. Here we focused our review on an examination of national level policies to evaluate to which degree current provisions promote positive environmental outcomes. All the surveyed countries have national-level Environmental Impact Assessment laws or regulations that cover the habitats present in their territories. Although most countries enable the use of offsets only Brazil, Colombia, Mexico and Peru explicitly require their implementation. Our review has shown that while advancing quite detailed offset policies, most countries do not seem to have strong requirements regarding impact avoidance. Despite this deficiency most countries have a strong foundation from which to develop policy for biodiversity offsets, but several issues require further guidance, including how best to: (1 ensure conformance with the mitigation hierarchy; (2 identify the most environmentally preferable offsets within a landscape context; (3 determine appropriate mitigation replacement ratios; and (4 ensure appropriate time and effort is given to monitor offset performance.

  13. Policy development for environmental licensing and biodiversity offsets in Latin America.

    Science.gov (United States)

    Villarroya, Ana; Barros, Ana Cristina; Kiesecker, Joseph

    2014-01-01

    Attempts to meet biodiversity goals through application of the mitigation hierarchy have gained wide traction globally with increased development of public policy, lending standards, and corporate practices. With interest in biodiversity offsets increasing in Latin America, we seek to strengthen the basis for policy development through a review of major environmental licensing policy frameworks in Argentina, Brazil, Chile, Colombia, Mexico, Peru and Venezuela. Here we focused our review on an examination of national level policies to evaluate to which degree current provisions promote positive environmental outcomes. All the surveyed countries have national-level Environmental Impact Assessment laws or regulations that cover the habitats present in their territories. Although most countries enable the use of offsets only Brazil, Colombia, Mexico and Peru explicitly require their implementation. Our review has shown that while advancing quite detailed offset policies, most countries do not seem to have strong requirements regarding impact avoidance. Despite this deficiency most countries have a strong foundation from which to develop policy for biodiversity offsets, but several issues require further guidance, including how best to: (1) ensure conformance with the mitigation hierarchy; (2) identify the most environmentally preferable offsets within a landscape context; (3) determine appropriate mitigation replacement ratios; and (4) ensure appropriate time and effort is given to monitor offset performance.

  14. License renewal in the United States

    International Nuclear Information System (INIS)

    Brons, Jack

    2002-01-01

    Full text: Nuclear plants in the United States are licensed for 40 years, a length specified in the Atomic Energy Act of 1954, which laid out much of the regulatory basis for the commercial nuclear industry. The Act, however, made provision for license renewal. The original 40-year license period was chosen arbitrarily by the U.S. Congress because it was the typical period over which utilities recovered their investment in electricity generating plants. Nuclear plants, however, are subject to a rigorous program of Nuclear Regulatory Commission oversight, maintenance and equipment replacement. In effect, they must be in the same operating condition on the last day of their licenses as they were on the first. As the industry matured, it became apparent that there was no physical limitation on the continued operation of nuclear plants past 40 years. The industry turned its attention toward license renewal. When the issue was first raised, the NRC considered stringent process equivalent to seeking a new operating license for each plant. The complexity, length and cost of the process made it unlikely that many nuclear plants would seek license renewal. The nuclear industry worked successfully with NRC on the application of generic principles to license renewal, however, and in 1995, the NRC issued an efficient, tightly-focused rule that made license renewal a safe, viable option. To extend the operating license for a reactor, a company must demonstrate to the NRC that aging effects will be adequately managed during the renewal terms, thus ensuring equipment functionality. The rule allows licensees to apply for extensions of up to 20 years. The first license renewal application was filed in 1998 by the owner of the two-unit Calvert Cliffs plant. Shortly thereafter, an application was filed for the three-unit Oconee Nuclear Station. The NRC renewed the licenses for all five units in 2000, and since then, five more licenses have been renewed. The NRC has received 37

  15. How registered nurses, licensed practical nurses and resident aides spend time in nursing homes: An observational study.

    Science.gov (United States)

    McCloskey, Rose; Donovan, Cindy; Stewart, Connie; Donovan, Alicia

    2015-09-01

    Calls for improved conditions in nursing homes have pointed to the importance of optimizing the levels and skills of care providers. Understanding the work of care providers will help to determine if staff are being used to their full potential and if opportunities exist for improved efficiencies. To explore the activities of care providers in different nursing homes and to identify if variations exist within and across homes and shifts. A multi-centre cross-sectional observational work flow study was conducted in seven different nursing homes sites in one Canadian province. Data were collected by a research assistant who conducted 368 h of observation. The research assistant collected data by following an identical route in each site and recording observations on staff activities. Findings indicate staff activities vary across roles, sites and shifts. Licensed practical nurses (nursing assistants) have the greatest variation in their role while registered nurses have the least amount of variability. In some sites both registered nurses and licensed practical nurses perform activities that may be safely delegated to others. Care providers spend as much as 53.7% of their time engaged in non-value added activities. There may be opportunities for registered nurses and licensed practical nurses to delegate some of their activities to non-regulated workers. The time care providers spend in non-value activities suggest there may be opportunities to improve efficiencies within the nursing home setting. Copyright © 2015 Elsevier Ltd. All rights reserved.

  16. Semi-annual report of the licensing program - July to December 1988

    International Nuclear Information System (INIS)

    Anon.

    1989-01-01

    The main activities developed and described are: licensing of CIPC (FSAR), emergency plan of NUCLEI, reevaluation of the maximum credible accident of NUCLEI, updating of the safety analysis report of CDTN, emergency plan of IPR-R1 reactor and licensing of the DIENR.CN. installations. (E.G.) [pt

  17. 7 CFR 1948.83 - Performance of site development work.

    Science.gov (United States)

    2010-01-01

    ... 7 Agriculture 13 2010-01-01 2009-01-01 true Performance of site development work. 1948.83 Section 1948.83 Agriculture Regulations of the Department of Agriculture (Continued) RURAL HOUSING SERVICE... Development Assistance Program § 1948.83 Performance of site development work. Site development work will be...

  18. Geothermal : A Regulatory Guide to Leasing, Permitting, and Licensing in Idaho, Montana, Oregon, and Washington.

    Energy Technology Data Exchange (ETDEWEB)

    Bloomquist, R.Gordon

    1991-10-01

    The actual geothermal exploration and development may appear to be a simple and straightforward process in comparison to the legal and institutional maze which the developer must navigate in order to obtain all of the federal, state, and local leases, permits, licenses, and approvals necessary at each step in the process. Finally, and often most difficult, is obtaining a contract for the sale of thermal energy, brine, steam, or electricity. This guide is designed to help developers interested in developing geothermal resource sites in the Bonneville Power Administration Service Territory in the state of Idaho, Montana, Oregon, and Washington better understand the federal, state, and local institutional process, the roles and responsibilities of each agency, and how and when to make contact in order to obtain the necessary documents.

  19. 78 FR 13691 - Prospective Grant of Exclusive License: The Development of m971 and m972 Chimeric Antigen...

    Science.gov (United States)

    2013-02-28

    ... Exclusive License: The Development of m971 and m972 Chimeric Antigen Receptors (CARs) for the Treatment of B... ``M971 Chimeric Antigen Receptors'' [HHS Ref. E-291-2012/0-US-01], and (b) U.S. Patent Application 61/042... malignancies that express CD22 on their cell surface using chimeric antigen receptors which contain the m971 or...

  20. Consolidated guidance about materials licenses: Program-specific guidance about portable gauge licenses. Final report; Volume 1

    Energy Technology Data Exchange (ETDEWEB)

    Vacca, P.C.; Whitten, J.E.; Pelchat, J.M.; Arredondo, S.A.; Matson, E.R.; Lewis, S.H.; Collins, D.J.; Santiago, P.A. [Nuclear Regulatory Commission, Washington, DC (United States). Div. of Industrial and Medical Nuclear Safety; Tingle, W. [Dept. of Environment, Health, and Natural Resources, Raleigh, NC (United States). Div. of Radiation Protection

    1997-05-01

    As part of its redesign of the materials licensing process, NRC is consolidating and updating numerous guidance documents into a single comprehensive repository as described in NUREG-1539 and draft NUREG-1541. NUREG-1556, Vol. 1, is the first program-specific guidance developed for the new process and will serve as a template for subsequent program-specific guidance. This document is intended for use by applicants, licensees, and NRC staff and will also be available to Agreement States. This document supersedes the guidance previously found in draft Regulatory Guide DG-0008, ``Applications for the Use of Sealed Sources in Portable Gauging Devices,`` and in NMSs Policy and guidance Directive 2-07, ``Standard Review Plan for Applications for Use of Sealed Sources in Portable Gauging Devices.`` This final report takes a more risk-informed, performance-based approach to licensing portable gauges, and reduces the information(amount and level of detail) needed to support an application to use these devices. It incorporates many suggests submitted during the comment period on draft NUREG-1556, Volume 1. When published, this final report should be used in preparing portable gauge license applications. NRC staff will use this final report in reviewing these applications.

  1. Consolidated guidance about materials licenses: Program-specific guidance about portable gauge licenses. Final report; Volume 1

    International Nuclear Information System (INIS)

    Vacca, P.C.; Whitten, J.E.; Pelchat, J.M.; Arredondo, S.A.; Matson, E.R.; Lewis, S.H.; Collins, D.J.; Santiago, P.A.; Tingle, W.

    1997-05-01

    As part of its redesign of the materials licensing process, NRC is consolidating and updating numerous guidance documents into a single comprehensive repository as described in NUREG-1539 and draft NUREG-1541. NUREG-1556, Vol. 1, is the first program-specific guidance developed for the new process and will serve as a template for subsequent program-specific guidance. This document is intended for use by applicants, licensees, and NRC staff and will also be available to Agreement States. This document supersedes the guidance previously found in draft Regulatory Guide DG-0008, ''Applications for the Use of Sealed Sources in Portable Gauging Devices,'' and in NMSs Policy and guidance Directive 2-07, ''Standard Review Plan for Applications for Use of Sealed Sources in Portable Gauging Devices.'' This final report takes a more risk-informed, performance-based approach to licensing portable gauges, and reduces the information(amount and level of detail) needed to support an application to use these devices. It incorporates many suggests submitted during the comment period on draft NUREG-1556, Volume 1. When published, this final report should be used in preparing portable gauge license applications. NRC staff will use this final report in reviewing these applications

  2. Siting, design and cost of shallow land burial facilities in northern New England. Volume 1

    International Nuclear Information System (INIS)

    1985-05-01

    This study investigated the technical feasibility and cost of shallow land burial (SLB) as one low-level radioactive waste disposal option for Maine and the northern New England states of Maine, New Hampshire, and Vermont. The results are presented in five chapters addressing the licensing process for an SLB facility, the siting process, the engineering design, the cost of disposal, and the cost of transportation. Chapter 2 reviews the Federal and State licensing processes and requirements for development of an SLB facility. Included in this discussion are the stages in the life cycle of SLB facility. Chapter 3 provides site selection criteria for Maine and presents a proposed site selection methodology. The site selection criteria are defined and the reasoning behind their selection is explained. Chapter 4 discusses SLB trench and facility designs and costs. To accommodate different waste volume scenarios, differently sized facilities are discussed, representing Maine going-it-alone and a northern New England compact. Designs and costs of scenarios including nuclear power plant decommissioning wastes are also discussed. Cost estimates of licensing, facility construction, operation, closure, and post closure care are presented for the different waste volume scenarios. Chapter 5 presents estimates of what it would cost LLW generators to dispose of their waste in a Maine-only or a northern New England shallow land burial facility. The reliability of the estimates and their sensitivity to changes in waste volume are also discussed. Chapter 6 examines transportation costs

  3. Hydropower : A Regulatory Guide to Permitting and Licensing in Idaho, Montana, Oregon, and Washington.

    Energy Technology Data Exchange (ETDEWEB)

    McCoy, Gilbert A.

    1992-12-01

    The design, construction and operation of a hydropower project can result in many potential impacts. These potential impacts are of concern to a host of federal, state, and local authorities. Early consultation with land and water management, fish and wildlife resource protection, and health and human safety-oriented agencies should occur to determine specific concerns and study requirements for each proposed project. This Guide to Permitting and Licensing outlines the characteristic features of attractive hydropower sites; summarizes an array of developmental constraints; illustrates potential environmental impacts and concerns; and summarizes all federal, state, and local permitting and licensing requirements.

  4. Hydropower: A Regulatory Guide to Permitting and Licensing in Idaho, Montana, Oregon, and Washington.

    Energy Technology Data Exchange (ETDEWEB)

    McCoy, Gilbert A.

    1992-12-01

    The design, construction and operation of a hydropower project can result in many potential impacts. These potential impacts are of concern to a host of federal, state, and local authorities. Early consultation with land and water management, fish and wildlife resource protection, and health and human safety-oriented agencies should occur to determine specific concerns and study requirements for each proposed project. This Guide to Permitting and Licensing outlines the characteristic features of attractive hydropower sites; summarizes an array of developmental constraints; illustrates potential environmental impacts and concerns; and summarizes all federal, state, and local permitting and licensing requirements.

  5. Methodology for LOCA analysis and its qualification procedures for PWR reload licensing

    International Nuclear Information System (INIS)

    Serrano, M.A.B.

    1986-01-01

    The methodology for LOCA analysis developed by FURNAS and its qualification procedure for PWR reload licensing are presented. Digital computer codes developed by NRC and published collectively as the WREM package were modified to get versions that comply to each requirement of Brazilian Licensing Criteria. This metodology is applied to Angra-1 basic case to conclude the qualification process. (Author) [pt

  6. The licensing practice on nuclear power plants in Korea

    International Nuclear Information System (INIS)

    Moon, S. P.

    1994-01-01

    The evolution of Korean regulatory system has tightly coupled with development ot Korean nuclear power program. The nuclear power plant licensing has become a major regulatory function of the government when the construction of the Kori NPP Unit 1 started in early 1970s. During this period, domestic laws and regulations applicable to the licensing of NPP were not yet fully developed. Therefore the vendor countries' laws and regulations were applied as mandatory requirement. Beginning in the early 19808, component approach was used and contracts were awarded separately for major components of the plants, thus enabling more domestic industries to participate in the projects. The two-step licensing system was incorporated into the law. In the third phase from 1987, major efforts have been concentrated on the maximum participation of local industries. The overriding priority for selecting suppliers was the condition of higher nuclear technology transfer to Korea. The Korea Institute of Nuclear Safety (KINS) was established in 1990 as an independent regulatory expert organization

  7. A Malaysian Vehicle License Plate Localization and Recognition System

    Directory of Open Access Journals (Sweden)

    Ganapathy Velappa

    2008-02-01

    Full Text Available Technological intelligence is a highly sought after commodity even in traffic-based systems. These intelligent systems do not only help in traffic monitoring but also in commuter safety, law enforcement and commercial applications. In this paper, a license plate localization and recognition system for vehicles in Malaysia is proposed. This system is developed based on digital images and can be easily applied to commercial car park systems for the use of documenting access of parking services, secure usage of parking houses and also to prevent car theft issues. The proposed license plate localization algorithm is based on a combination of morphological processes with a modified Hough Transform approach and the recognition of the license plates is achieved by the implementation of the feed-forward backpropagation artificial neural network. Experimental results show an average of 95% successful license plate localization and recognition in a total of 589 images captured from a complex outdoor environment.

  8. Sensitivity analysis using the FRAPCON-1/EM: development of a calculation model for licensing

    International Nuclear Information System (INIS)

    Chapot, J.L.C.

    1985-01-01

    The FRAPCON-1/EM is version of the FRAPCON-1 code which analyses fuel rods performance under normal operation conditions. This version yields conservative results and is used by the NRC in its licensing activities. A sensitivity analysis was made, to determine the combination of models from the FRAPCON-1/EM which yields the most conservative results for a typical Angra-1 reactor fuel rod. The present analysis showed that this code can be used as a calculation tool for the licensing of the Angra-1 reload. (F.E.) [pt

  9. Free Software Licenses and Other Free Licenses: Genetic Code of Digital Common Goods

    OpenAIRE

    Marco Ciurcina

    2017-01-01

    This article explores the history and describes the main features of free software licenses and other free licenses in an attempt to shed light on the reasons for their success in promoting individual behaviors converging towards the collective construction of digital commons.

  10. 1994 Site Development Plan: A plan with vision

    Energy Technology Data Exchange (ETDEWEB)

    1994-07-01

    The 1994 Lawrence Livermore National Laboratory Site Development Plan has been developed during a period of great change and uncertainty. Our goal is to make possible the best use of the Laboratory`s resources to meet shifting national priorities in the post-Cold War world. Site Planning is an important component of the overall Laboratory strategic planning process. This plan focuses on opportunities for the Laboratory as well as on key site development issues including facility construction, redevelopment and reuse, site accessibility, and security. A major challenge is to achieve sufficient stability in the site planning and execution so that the processes of construction can occur efficiently while at the same time providing sufficient flexibility in site facilities so that a range of changing national needs can be accommodated. We are closely coupled to the DOE strategic planning process to meet this challenge.

  11. Managing Licensing in a Market for Technology

    DEFF Research Database (Denmark)

    Arora, Ashish; Fosfuri, Andrea; Rønde, Thomas

    2013-01-01

    , we find that interdependency across business units may result in more, not less, decentralization. Furthermore, even though centralization results in less information, centralized licensing deals are larger. Our model conforms to the existing evidence that reports heterogeneity across firms in both......Technology licensing is an important means for companies to extract more value from their intellectual assets. We build a model that helps understand how licensing activity should be organized within large corporations. More specifically, we compare decentralization—where the business unit using...... the technology makes licensing decisions—to centralized licensing. The business unit has superior information about licensing opportunities but may not have the appropriate incentives because its rewards depend on product market performance. If licensing is decentralized, the business unit forgoes valuable...

  12. Siting a low-level waste facility in California: A success story

    International Nuclear Information System (INIS)

    Romano, S.A.; Gaynor, R.K.

    1988-01-01

    US Ecology is the state of California's designee to site, develop, and operate a low-level radioactive waste disposal facility. The facility will meet the state's responsibilities under the Low-Level Radioactive Waste Policy Act as amended. By January 1988, US Ecology narrowed its efforts to two candidate sites. Strong local community support has been expressed for both sites. US Ecology will select a single proposed site for licensing in 1988 and anticipates receiving waste in late 1900 or early 1991. This schedule places California well ahead of the milestones identified in federal law. The success to date in California can be attributed in large part to the open process used to involve citizens' advisory committees (CACs) and the general public at critical stages of the projects

  13. Technical guidance for siting criteria development

    International Nuclear Information System (INIS)

    Aldrich, D.C.; Sprung, J.L.; Alpert, D.J.

    1982-12-01

    Technical guidance to support the formulation and comparison of possible siting criteria for nuclear power plants has been developed in four areas: (1) consequences of hypothetical severe nuclear-power-plant accidents, (2) characteristics of population distributions about current reactor sites, (3) site availability within the continental United States, and (4) socioeconomic impacts of reactor siting. The impact on consequences of source-term magnitude, meteorology, population distribution, and emergency response have been analyzed. Population distributions about current sites were analyzed to identify statistical characteristics, time trends, and regional differences. A site-availability data bank was constructed for the continential United States. The data bank contains information about population densities, seismicity, topography, water availability, and land-use restrictions. Finally, the socioeconomic impacts of rural-industrialization projects, energy boomtowns, and nuclear power plants were examined to determine their nature, magnitude, and dependence on site demography and remoteness

  14. Technical guidance for siting criteria development

    Energy Technology Data Exchange (ETDEWEB)

    Aldrich, D.C.; Sprung, J.L.; Alpert, D.J.; Diegert, K.; Ostmeyer, R.M.; Ritchie, L.T.; Strip, D.R.; Johnson, J.D.; Hansen, K.; Robinson, J.

    1982-12-01

    Technical guidance to support the formulation and comparison of possible siting criteria for nuclear power plants has been developed in four areas: (1) consequences of hypothetical severe nuclear-power-plant accidents, (2) characteristics of population distributions about current reactor sites, (3) site availability within the continental United States, and (4) socioeconomic impacts of reactor siting. The impact on consequences of source-term magnitude, meteorology, population distribution, and emergency response have been analyzed. Population distributions about current sites were analyzed to identify statistical characteristics, time trends, and regional differences. A site-availability data bank was constructed for the continential United States. The data bank contains information about population densities, seismicity, topography, water availability, and land-use restrictions. Finally, the socioeconomic impacts of rural-industrialization projects, energy boomtowns, and nuclear power plants were examined to determine their nature, magnitude, and dependence on site demography and remoteness.

  15. 7 CFR 6.28 - Transfer of license.

    Science.gov (United States)

    2010-01-01

    ... Licensing Authority will transfer to such other person the historical, nonhistorical or designated license... escrow with the sole condition for return of escrow being that the Licensing Authority determines that... to whom the historical licenses were issued during the quota year in which the sale or conveyance...

  16. Hydrogeological Site Descriptive Model - a strategy for its development during Site Investigations

    Energy Technology Data Exchange (ETDEWEB)

    Rhen, Ingvar [SWECO VIAK AB, Goeteborg (Sweden); Follin, Sven [SF GeoLogic AB, Stockholm (Sweden); Hermanson, Jan [Golder Associates, Stockholm (Sweden)

    2003-04-01

    The report is to present a strategy for the development of the Site Descriptive Hydrogeological Model within the SKB Site Investigation Programme. The report, and similar reports from the Geology, Rock Mechanics, Thermal properties, Hydrogeochemistry, Transport Properties and Surface Ecosystem disciplines are intended to guide SKB Site Descriptive Modelling but also to provide the authorities with an overview of how the modelling should be performed. Thus the objectives of this report are to: provide guidelines for the modelling of different sites resulting in consistent handling of modelling issues during the Site Investigations, provide a structure for the modelling sequence that is suitable for the establishment of a Site Descriptive model and provide some necessary details that should be considered in a Site Descriptive model.

  17. Hydrogeological Site Descriptive Model - a strategy for its development during Site Investigations

    International Nuclear Information System (INIS)

    Rhen, Ingvar; Follin, Sven; Hermanson, Jan

    2003-04-01

    The report is to present a strategy for the development of the Site Descriptive Hydrogeological Model within the SKB Site Investigation Programme. The report, and similar reports from the Geology, Rock Mechanics, Thermal properties, Hydrogeochemistry, Transport Properties and Surface Ecosystem disciplines are intended to guide SKB Site Descriptive Modelling but also to provide the authorities with an overview of how the modelling should be performed. Thus the objectives of this report are to: provide guidelines for the modelling of different sites resulting in consistent handling of modelling issues during the Site Investigations, provide a structure for the modelling sequence that is suitable for the establishment of a Site Descriptive model and provide some necessary details that should be considered in a Site Descriptive model

  18. Free Software Licenses and Other Free Licenses: Genetic Code of Digital Common Goods

    Directory of Open Access Journals (Sweden)

    Marco Ciurcina

    2017-06-01

    Full Text Available This article explores the history and describes the main features of free software licenses and other free licenses in an attempt to shed light on the reasons for their success in promoting individual behaviors converging towards the collective construction of digital commons.

  19. 78 FR 73553 - Prospective Grant of Exclusive License: Development of Cripto-1 Point of Care (POC) Tests and...

    Science.gov (United States)

    2013-12-06

    ... contemplated exclusive license should be directed to: Eggerton Campbell, Ph.D. Licensing and Patenting Manager... colon, pancreas, stomach, gallbladder, breast, lung, endometrium and cervix. Current methodologies of...

  20. Supplementary Report on the Regulation of Site Selection and Preparation

    International Nuclear Information System (INIS)

    Webster, Philip

    2014-01-01

    The Committee on Nuclear Regulatory Activities (CNRA), based on the regulatory actions underway or being considered in different members countries concerning the design and construction of advanced nuclear power plants, established a working group responsible of the regulatory issues of siting, licensing and regulatory oversight of generation III+ and generation IV nuclear reactors. The Working Group on the Regulation of New Reactors (WGRNR) main purposes are to improve regulatory reviews by comparing practices in member countries; improve the licensing process of new reactors by learning from best practices in member countries; ensure that construction inspection issues and construction experience is shared; promote cooperation among member countries to improve safety; and enhance the effectiveness and efficiency of the regulatory process. The WGRNR has established a programme of work which includes: the collection of construction experience and the assessing of the information collected in order to share lessons learned and good practices; the review of regulatory practices concerning the regulation of nuclear sites selection and preparation; and the review of recent regulatory experience concerning the licensing structure of regulatory staff and regulatory licensing process. The WGRNR began in May 2008 a task of examining and documenting the various practices used by regulatory authorities in the regulation of nuclear power plant siting. The purpose of the task was to provide the member countries with practical information that would be helpful in assessing and potentially improving their regulatory practices and requirements on the regulation of sites. The task considered also regulatory practices on sites where a mixture of activities are taking place (e.g. operating units, new construction, and decommissioning, etc.). This work led to the publication in 2010 of the Report on the Survey on Regulation of Site Selection and Preparation NEA/CNRA/R(2010)3. This

  1. Sequential evaluation of the potential geologic repository site at Yucca Mountain, Nevada, USA

    International Nuclear Information System (INIS)

    Bjerstedt, T.W.

    1996-01-01

    This paper discusses the changes that are planned for the characterization program at Yucca Mountain due to budget changes. Yucca Mountain is the only site being studied in the US for a geologic repository. Funding for the site characterization program at Yucca Mountain program was cut by roughly one half from the 1994 projected budget to complete three major milestones. These project milestones included: (1) a time-phased determination of site suitability, and if a positive finding, (2) completion of an Environmental Impact Statement, and (3) preparation of a License Application to the US NRC to authorize repository construction. In reaction, Yucca Mountain Site Characterization Project has shifted from parallel development of these milestones to a sequenced approach with the site suitability evaluation being replaced with a management assessment. Changes to the regulatory structure for the disposal program are under consideration by DOE and the NRC. The possibility for NRC and Doe to develop a site-specific regulatory structure follows from the National Energy Policy Act of 1992 that authorized the US EPA to develop a site specific environmental standard for Yucca Mountain

  2. Licensing Teachers: Lessons from Other Professions.

    Science.gov (United States)

    Haberman, Martin

    1986-01-01

    The licensing of teachers should be modeled against professions similar to teaching rather than professions like medicine and architecture that are vastly different. Applying similar licensing practices can raise the status of teaching. Ignoring these licensing practices will prevent teachers from functioning as professionals. (MD)

  3. Licensing of nuclear and radioactive installations in Peru

    International Nuclear Information System (INIS)

    Medina Gironzini, E.

    1987-01-01

    In Peru, the Regulation for Ionizing Radiation Sources is applied, which establishes the norms and procedures to follow in the nuclear and radioactive installations of the country in order to assure their correct operation as concerns to the nuclear safety and radiological protection, allowing the emission of the respective licenses. As for the nuclear facilities, this authorization includes the Previous License, the Construction License and the Operation License (provisional and definitive) and for radioactive facilities and equipment generating ionizing radiations: the Construction License and the Operation License. The personnel also require a license that can be an operator license (as for nuclear reactors) or a supervisor license (for nuclear and radioactive facilities). In spite of the above mentioned regulation and its long enforcement period, less than 10% of radioactive facilities in this country are licensed, due to different problems which will be solved in the medium term. (Author)

  4. The licensing processes influence on nuclear market

    International Nuclear Information System (INIS)

    Locatelli, Giorgio; Mancini, Mauro; Sainati, Tristano; Sallinen, Liisa

    2011-01-01

    The paper deals with the licensing nuclear power plants; it focuses primarily on the licensing process implications into the international nuclear market. Nowadays there are twenty-six countries that are planning to build new nuclear facilities, and thirty-seven where nuclear reactors are proposed; on the other hand, there are mainly ten international reactor vendors. At international level, there are few vendors that have sufficient resources, capabilities and experience to carry out the design and delivering of a nuclear power plant in the international market; On the other hand, the licensing processes are strictly dependent on national law frameworks, and on the nuclear policies. The paper proposes a comparison of six licensing processes (the ones established in Finland, France, Italy, South Korea, USA and UK), and analyzes its main features and implications; the IAEA licensing process is taken as reference point. The objective of the paper is to propose a systemic approach for considering the licensing procedures. The framework proposed enables facilitating the licensing management and inferring the main features of licensing contexts. The paper concludes with a forecast of the nuclear licensing context, especially with respect to the fourth generation of nuclear reactors. (author)

  5. An overview of the class I structures license renewal industry report

    International Nuclear Information System (INIS)

    Renfro, L.J.; Statton, J.A.

    1991-01-01

    License renewal of a commercial nuclear power plant requires verification that systems, structures and components important to license renewal can perform their intended safety functions throughout the license renewal term. The verification of this continuing performance includes a technical evaluation of the effects of age-related degradation. An industry report (IR) sponsored by the nuclear industry was developed which identifies potentially significant age-related degradation mechanisms that may affect Class I structures and evaluates their impact on the ability of the structures to continue to perform their safety functions. Preventive and/or mitigative options are outlined for managing degradation mechanisms that could significantly affect plant performance during the license renewal period. This paper provides a summary of the IR. (author)

  6. Whom to Choose as License Partner?

    DEFF Research Database (Denmark)

    Laursen, Keld; Reichstein, Toke; Trombini, Giulia

    2013-01-01

    between technology and market forces: if partners are market distant, the likelihood of technology license contractual partnership decreases with partners’ technological distance. Using data on the formation of license partnerships in the global biopharmaceutical industry over the period 1994......This paper investigates the matching of firms on the market for technology. The paper forwards two dimensions along which license formation occurs: technology and product-market. Both sides of the market search for a partner representing potential for high technology synergies to maximize licensing...

  7. Exporting the Canadian licensing program

    International Nuclear Information System (INIS)

    Whelan, D.J.

    1981-06-01

    This paper deals with the problems of an overseas regulatory agency in licensing a Canadian-supplied nuclear plant which is referenced to a plant in Canada. Firstly, the general problems associated with the use of a reference plant are discussed. This is followed by a discussion of specific problems which arise from the licensing practices in Canada. The paper concludes with recommendations to simplify the task of demonstrating the licensability of an overseas CANDU plant

  8. Regulatory Issues and Challenges in Preparing for the Regulation of New Reactor Siting: Malaysia's Experience

    International Nuclear Information System (INIS)

    Jais, Azlina Mohammad; Hassan, Halimah; Yasir, Muhamad Samudi; Roslan, Ridha

    2011-01-01

    This paper aims at giving an overview about the issues and challenges facing regulatory authority, the Atomic Energy Licensing Board (AELB) in ensuring nuclear safety, security and safeguards (3S's) and other relevant authorities to meet an impending nuclear power programme post-2020, in particular at the beginning stage of preparation for the regulation of nuclear power reactor siting. A comparison with an international framework and guidelines of the International Atomic Energy Agency (IAEA) and other countries' practice was made to get an overview of the present adequacy of Malaysia's nuclear regulatory framework in preparation for Malaysia to consider and perhaps decide for a safe, secure and peaceful nuclear power project in Malaysia, in utilising nuclear power in a quest for energy diversity and security. The important stage in the development of a nuclear power project is the evaluation of a suitable site to establish the site-related design inputs for the NPP. The evaluation of suitable site is the result of a process to ensure adequate protection of workers, public and the environment from the undue risk of ionizing radiation arising from NPP taking into account impact to the social communities and public acceptance, thus it will depend on the regulators to ensure a high level safety standards and security are met, in addition to its peaceful uses. Development of regulatory criteria for the site evaluation is a pre-initiatives licensing work for a possible nuclear power plant to performing effective nuclear safety and security reviews in an efficient and timely manner regardless whether Malaysia embarks on a nuclear power programme with anticipating challenges, learning from others' experiences in preparing for the demands for new licensing processes by collaborating internationally, in an expanding global environment

  9. 7 CFR 6.32 - Globalization of licenses.

    Science.gov (United States)

    2010-01-01

    ... 7 Agriculture 1 2010-01-01 2010-01-01 false Globalization of licenses. 6.32 Section 6.32 Agriculture Office of the Secretary of Agriculture IMPORT QUOTAS AND FEES Dairy Tariff-Rate Import Quota Licensing § 6.32 Globalization of licenses. If the Licensing Authority determines that entries of an article...

  10. 42 CFR 431.710 - Provisional licenses.

    Science.gov (United States)

    2010-10-01

    ... Licensing Nursing Home Administrators § 431.710 Provisional licenses. To fill a position of nursing home... 42 Public Health 4 2010-10-01 2010-10-01 false Provisional licenses. 431.710 Section 431.710 Public Health CENTERS FOR MEDICARE & MEDICAID SERVICES, DEPARTMENT OF HEALTH AND HUMAN SERVICES...

  11. Geohydrology of industrial waste disposal site

    International Nuclear Information System (INIS)

    Gaynor, R.K.

    1984-01-01

    An existing desert site for hazardous chemical and low-level radioactive waste disposal is evaluated for suitability. This site is characterized using geologic, geohydrologic, geochemical, and other considerations. Design and operation of the disposal facility is considered. Site characteristics are also evaluated with respect to new and proposed regulatory requirements under the Resource Conservation and Recovery Act (1976) regulations, 40 CFR Part 264, and the ''Licensing Requirements for Landfill Disposal of Radioactive Waste,'' 10 CRF Part 61. The advantages and disadvantages of siting new disposal facilities in similar desert areas are reviewed and contrasted to siting in humid locations

  12. Radioisotope thermoelectric generator licensed hardware package and certification tests

    International Nuclear Information System (INIS)

    Goldmann, L.H.; Averette, H.S.

    1994-01-01

    This paper presents the Licensed Hardware package and the Certification Test portions of the Radioisotope Thermoelectric Generator Transportation System. This package has been designed to meet those portions of the Code of Federal Regulations (10 CFR 71) relating to ''Type B'' shipments of radioactive materials. The detailed information for the anticipated license is presented in the safety analysis report for packaging, which is now in process and undergoing necessary reviews. As part of the licensing process, a full-size Certification Test Article unit, which has modifications slightly different than the Licensed Hardware or production shipping units, is used for testing. Dimensional checks of the Certification Test Article were made at the manufacturing facility. Leak testing and drop testing were done at the 300 Area of the US Department of Energy's Hanford Site near Richland, Washington. The hardware includes independent double containments to prevent the environmental spread of 238 Pu, impact limiting devices to protect portions of the package from impacts, and thermal insulation to protect the seal areas from excess heat during accident conditions. The package also features electronic feed-throughs to monitor the Radioisotope Thermoelectric Generator's temperature inside the containment during the shipment cycle. This package is designed to safely dissipate the typical 4500 thermal watts produced in the largest Radioisotope Thermoelectric Generators. The package also contains provisions to ensure leak tightness when radioactive materials, such as a Radioisotope Thermoelectric Generator for the Cassini Mission, planned for 1997 by the National Aeronautics and Space Administration, are being prepared for shipment. These provisions include test ports used in conjunction with helium mass spectrometers to determine seal leakage rates of each containment during the assembly process

  13. Factors relating to the selection of sites for nuclear power stations in certain industrial countries

    International Nuclear Information System (INIS)

    1979-08-01

    The subject is discussed under the following headings: framework conditions of energy supply (energy supply in general (economics, planning); supply of nuclear energy (objectives, national nuclear industry, technology, development, public conflict)); environmental planning (legal foundations, planning levels, public site-provision investigations, electrical utilities); general and statutory atomic licensing procedure, criteria. (U.K.)

  14. Site characterization progress report: Yucca Mountain, Nevada. October 1, 1996--March 31, 1997

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1997-10-01

    The report is the sixteenth in a series issued approximately every six months to report progress and results of site characterization activities being conducted to evaluate Yucca Mountain as a possible geologic repository for the disposal of spent nuclear fuel and high-level radioactive waste. This report highlights work started, in progress, and completed during the reporting period. In addition, this report documents and discusses changes to the Office of Civilian Radioactive Waste Management (OCRWM) Site Characterization Program (Program) resulting from the ongoing collection and evaluation of site information, systems analyses, development of repository and waste package designs, and results of performance assessment activities. Details on the activities summarized can be found in the numerous technical reports cited throughout the progress report. Yucca Mountain Site Characterization Project (Project) activities this period focused on implementing the near-term objectives of the revised Program Plan issued last period. Near-term objectives of the revised Program Plan include updating the US Department of Energy`s (DOE) repository siting guidelines to be consistent with a more focused performance-driven program; supporting an assessment in 1998 of the viability of continuing with actions leading to the licensing of a repository; and if the site is suitable, submittal of a Secretarial site recommendation to the President in 2001 and license application the US Nuclear Regulatory Commission (NRC) in 2002. During this reporting period, the Project developed and baselined its long-range plan in December 1996. That revision reflected the detailed fiscal year (FY) 1997 work scope and funding plan previously baselined at the end of FY 1996. Site characterization activities have been focused to answer the major open technical issues and to support the viability assessment.

  15. A data base for low-level radioactive waste disposal sites

    International Nuclear Information System (INIS)

    Daum, M.L.; Moskowitz, P.D.

    1989-07-01

    A computerized database was developed to assist the US Environmental Protection Agency (EPA) in evaluating methods and data for characterizing health hazards associated with land and ocean disposal options for low-level radioactive wastes. The data cover 1984 to 1987. The types of sites considered include Nuclear Regulatory Commission (NRC) licensed commercial disposal sites, EPA National Priority List (NPL) sites, US Department of Energy (DOE) Formerly Utilized Sites Remedial Action Project (FUSRAP) and DOE Surplus Facilities Management Program (SFMP) sites, inactive US ocean disposal sites, and DOE/Department of Defense facilities. Sources of information include reports from EPA, the US Department of Energy (DOE) and the Nuclear Regulatory Commission (NRC), as well as direct communication with individuals associated with specific programs. The data include site descriptions, waste volumes and activity levels, and physical and radiological characterization of low-level wastes. Additional information on mixed waste, packaging forms, and disposal methods were compiled, but are not yet included in the database. 55 refs., 4 figs., 2 tabs

  16. Roadmap and performance carried out during Ciemat site decommissioning

    International Nuclear Information System (INIS)

    Quinones, Javier; Diaz Diaz, Jose Luis

    2005-01-01

    Ciemat (Research Centre for Energy, Environment and Technology) located in the heart of the Ciudad Universitaria of Madrid, occupies a property of 20 Ha. Since its creation in 1951 as JEN, and in 1986 renowned as Ciemat, it has involved on R and D projects in the field of Energy and Environment, i.e., Nuclear Fission, Nuclear Fusion, Fossils Fuels, Renewable Energy. As a consequence of the R and D projects developed between 1951 - 1986 on Nuclear Fission field (fuel design, fabrication, characterization on irradiated fuels, safety studies, etc) and to the diversification of the goals as well, it is necessary to Decommissioning and Dismantling (D and D) from nuclear facilities (nuclear reactor, Hot Cells, Irradiation facility), buildings and soils. Preparations for D and D included a staged shutdown of operations, planning documentation and licensing for decommissioning. As a prerequisite to Ciemat application for a decommissioning license and nuclear environmental assessment was carried out according to Spanish Nuclear Council (CSN) and approval of the site decommissioning project was obtained in 2000 and valid until December 31, 2006. Since 2001 - 2003 is underway and focussed on the radiological characterization of the site (divided in pieces of ground), when each piece of ground is characterized a planning for D and D is presented to CSN in order to obtain a license for actuation. Nowadays several pieces of ground are decontaminated and modifications have been done in order to achieve a safe state of storage-with-surveillance. Later phases have planned waste management improvements for selected wastes already on temporally storage, eventually followed by final decommissioning of facilities and buildings and cleaning of contaminants from soils and removal of waste from the site. This paper describes the planning, nuclear and environment assessment and descriptions of decommissioning activities currently underway at Ciemat. (Author)

  17. To License or Not to License: An Examination of State Statutes Regarding Private Investigators and Digital Examiners

    Directory of Open Access Journals (Sweden)

    Thomas Lonardo

    2008-09-01

    Full Text Available In this paper the authors examine statutes that regulate, license, and enforce investigative functions in each US state. After identification and review of Private Investigator licensing requirements, the authors find that very few state statutes explicitly differentiate between Private Investigators and Digital Examiners. After contacting all state agencies the authors present a distinct grouping organizing state approaches to professional Digital Examiner licensing. The authors conclude that states must differentiate between Private Investigator and Digital Examiner licensing requirements and oversight.

  18. Operating reactors licensing actions summary

    International Nuclear Information System (INIS)

    1981-08-01

    The Operating Reactors Licensing Actions Summary is designed to provide the management of the Nuclear Regulatory Commission (NRC) with an overview of licensing actions dealing with operating power and nonpower reactors

  19. 77 FR 71404 - Notice of Intent to License Government-Owned Inventions; Intent to License on a Partially...

    Science.gov (United States)

    2012-11-30

    ... DEPARTMENT OF DEFENSE Department of the Army Notice of Intent to License Government-Owned Inventions; Intent to License on a Partially-Exclusive Basis AGENCY: Department of the Army, DoD. ACTION... by the Secretary of the Army. The US Army Edgewood Chemical Biological Center intends to license...

  20. Thematic report on community development and siting

    International Nuclear Information System (INIS)

    Vari, A.

    2002-01-01

    The paper analyses the Finnish spent fuel disposal facility siting from the perspective of community development, issues of fairness, and general factors of success. We found that anticipated positive impacts on host community development were the most important factors of local support. Second, the willingness of main stakeholders to adopt and combine several competing and changing concepts of fairness helped making legitimate decisions. Finally, we can conclude that in addition to important cultural factors which are unique in Finland, a number of siting elements have contributed to the success that are of cross-cultural nature. The paper summarises the lessons learned about the Finnish spent fuel disposal facility siting process regarding the issues of community development, fairness, and the transferability of siting approaches across cultures. It is largely based on information presented within the framework of the OECD Forum of Stakeholder Confidence Workshop held in Turku, Finland, on 15-16 November 2001. (author)

  1. Site dose calculations for the INEEL/TMI-2 storage facility

    International Nuclear Information System (INIS)

    Jones, K.B.

    1997-01-01

    The U.S. Department of Energy (DOE) is licensing an independent spent-fuel storage installation (ISFSI) for the Three Mile Island unit 2 (TMI-2) core debris to be constructed at the Idaho Chemical Processing Plant (ICPP) site at the Idaho National Engineering and Environmental Laboratory (INEEL) using the NUHOMS spent-fuel storage system. This paper describes the site dose calculations, performed in support of the license application, that estimate exposures both on the site and for members of the public. These calculations are unusual for dry-storage facilities in that they must account for effluents from the system in addition to skyshine from the ISFSI. The purpose of the analysis was to demonstrate compliance with the 10 CFR 20 and 10 CFR 72.104 exposure limits

  2. Review process for license renewal applications

    International Nuclear Information System (INIS)

    Craig, John W.; Kuo, P.T.

    1991-01-01

    In preparation for license renewal reviews, the Nuclear Regulatory Commission has recently published for public review and comment a proposed rule for license renewal and a draft Standard Review Plan as well as a draft Regulatory Guide relating to the implementation of the proposed rule. In support of future license renewal applications, the nuclear industry has also submitted 11 industry reports for NRC review and approval. This paper briefly describe how these parallel regulatory and industry activities will be factored into the NRC review process for license renewal. (author)

  3. 7 CFR 6.33 - License fee.

    Science.gov (United States)

    2010-01-01

    ... certified mail, return receipt requested, advising the licensee that if payment is not mailed in accordance.... Where the license at issue is a historical license, this will result, pursuant to § 6.23(b), in the person's loss of historical eligibility for such license. (d) Licensees may elect not to accept certain...

  4. Solid waste management complex site development plan

    International Nuclear Information System (INIS)

    Greager, T.M.

    1994-01-01

    The main purpose of this Solid Waste Management Complex Site Development Plan is to optimize the location of future solid waste treatment and storage facilities and the infrastructure required to support them. An overall site plan is recommended. Further, a series of layouts are included that depict site conditions as facilities are constructed at the SWMC site. In this respect the report serves not only as the siting basis for future projects, but provides siting guidance for Project W-112, as well. The plan is intended to function as a template for expected growth of the site over the next 30 years so that future facilities and infrastructure will be properly integrated

  5. Solid waste management complex site development plan

    Energy Technology Data Exchange (ETDEWEB)

    Greager, T.M.

    1994-09-30

    The main purpose of this Solid Waste Management Complex Site Development Plan is to optimize the location of future solid waste treatment and storage facilities and the infrastructure required to support them. An overall site plan is recommended. Further, a series of layouts are included that depict site conditions as facilities are constructed at the SWMC site. In this respect the report serves not only as the siting basis for future projects, but provides siting guidance for Project W-112, as well. The plan is intended to function as a template for expected growth of the site over the next 30 years so that future facilities and infrastructure will be properly integrated.

  6. The changing shape of U.S. licensing philosophy

    International Nuclear Information System (INIS)

    Remick, F.J.

    1992-01-01

    The shape of U.S. nuclear licensing and regulatory philosophy and process has already changed. The new process requires NRC review and approval of the vendor designs before a prospective utility license applicant purchases the design and begins construction. The new philosophy has resulted from the lessons learned from extensive operating experience accumulated in the United States. New criteria established for judging reactor designs include the capability of future designs to be more tolerant of accidents beyond the traditional design basis events. Qualitative and quantitative goals have been chosen as a guide for allocating resources for regulation of the currently operating plants. The changing shape of nuclear licensing and regulatory philosophy is also a result of economic circumstances in the United States. All will have a better opportunity to take part in the process which is most likely to encourage further development of safe nuclear energy in the United States. (author)

  7. 25 CFR 11.601 - Marriage licenses.

    Science.gov (United States)

    2010-04-01

    ... 25 Indians 1 2010-04-01 2010-04-01 false Marriage licenses. 11.601 Section 11.601 Indians BUREAU... ORDER CODE Domestic Relations § 11.601 Marriage licenses. A marriage license shall be issued by the clerk of the court in the absence of any showing that the proposed marriage would be invalid under any...

  8. The use of on-site Project Officers by a nuclear regulatory body

    International Nuclear Information System (INIS)

    Beare, J.W.

    1977-01-01

    In Canada consideration of applications for licensing nuclear installations is entrusted to the Reactor Safety Advisory Committee within the Atomic Energy Control Board (AECB). The licensing procedure is conducted in three stages (site approval, construction licence, operating licence). In order to control construction and operation of nuclear installations Project Officers are assigned to each particular installation. The policy of AECB is to send these officers on site several months before the reactor reaches criticality; and during reactor operation. This system clearly provides great practical advantages. (NEA) [fr

  9. Early Site Permit Demonstration Program: Plant parameters envelope report

    International Nuclear Information System (INIS)

    1993-03-01

    The Early Site Permit (ESP) Demonstration Program is the nuclear industry's initiative for piloting the early resolution of siting-related issues before the detailed design proceedings of the combined operating license review. The ESP Demonstration Program consists of three phases. The plant parameters envelopes task is part of Phase 1, which addresses the generic review of applicable federal regulations and develops criteria for safety and environmental assessment of potential sites. The plant parameters envelopes identify parameters that characterize the interface between an ALWR design and a potential site, and quantify the interface through values selected from the Utility Requirements Documents, vendor design information, or engineering assessments. When augmented with site-specific information, the plant parameters envelopes provide sufficient information to allow ESPs to be granted based on individual ALWR design information or enveloping design information for the evolutionary, passive, or generic ALWR plants. This document is expected to become a living document when used by future applicants

  10. Requests for licensing of new nuclear sources. New nuclear power source in Slovakia

    International Nuclear Information System (INIS)

    Vidlicka, R.

    2010-01-01

    Presentation indicates a new NPP licensing process in the Slovak Republic from the point of the Preparatory Stage - Siting, Design Stage and Construction. The presentation lists individual main criteria and legislation requirements. A part of the presentation covers the estimated new NPP construction schedule and the comparison to proceeding in several foreign countries. (author)

  11. The optimal licensing contract in a differentiated Stackelberg model.

    Science.gov (United States)

    Hong, Xianpei; Yang, Lijun; Zhang, Huaige; Zhao, Dan

    2014-01-01

    This paper extends the work of Wang (2002) by considering a differentiated Stackelberg model, when the leader firm is an inside innovator and licenses its new technology by three options, that is, fixed-fee licensing, royalty licensing, and two-part tariff licensing. The main contributions and conclusions of this paper are threefold. First of all, this paper derives a very different result from Wang (2002). We show that, with a nondrastic innovation, royalty licensing is always better than fixed-fee licensing for the innovator; with a drastic innovation, royalty licensing is superior to fixed-fee licensing for small values of substitution coefficient d; however when d becomes closer to 1, neither fee nor royalty licensing will occur. Secondly, this paper shows that the innovator is always better off in case of two-part tariff licensing than fixed-fee licensing no matter what the innovation size is. Thirdly, the innovator always prefers to license its nondrastic innovation by means of a two-part tariff instead of licensing by means of a royalty; however, with a drastic innovation, the optimal licensing strategy can be either a two-part tariff or a royalty, depending upon the differentiation of the goods.

  12. The licensing practice on nuclear power plants in Korea

    Energy Technology Data Exchange (ETDEWEB)

    Moon, S P

    1994-12-31

    The evolution of Korean regulatory system has tightly coupled with development ot Korean nuclear power program. The nuclear power plant licensing has become a major regulatory function of the government when the construction of the Kori NPP Unit 1 started in early 1970s. During this period, domestic laws and regulations applicable to the licensing of NPP were not yet fully developed. Therefore the vendor countries` laws and regulations were applied as mandatory requirement. Beginning in the early 19808, component approach was used and contracts were awarded separately for major components of the plants, thus enabling more domestic industries to participate in the projects. The two-step licensing system was incorporated into the law. In the third phase from 1987, major efforts have been concentrated on the maximum participation of local industries. The overriding priority for selecting suppliers was the condition of higher nuclear technology transfer to Korea. The Korea Institute of Nuclear Safety (KINS) was established in 1990 as an independent regulatory expert organization. 1 tab., 4 figs.

  13. AVC/H.264 patent portfolio license

    Science.gov (United States)

    Skandalis, Dean A.

    2006-08-01

    MPEG LA, LLC offers a joint patent license for the AVC (a/k/a H.264) Standard (ISO/IEC IS 14496-10:2004). Like MPEG LA's other licenses, the AVC Patent Portfolio License is offered for the convenience of the marketplace as an alternative enabling users to access essential intellectual property owned by many patent holders under a single license rather than negotiating licenses with each of them individually. The AVC Patent Portfolio License includes essential patents owned by DAEWOO Electronics Corporation; Electronics and Telecommunications Research Institute (ETRI); France Telecom, societe anonyme; Fujitsu Limited; Hitachi, Ltd.; Koninklijke Philips Electronics N.V.; LG Electronics Inc.; Matsushita Electric Industrial Co., Ltd.; Microsoft Corporation; Mitsubishi Electric Corporation; Robert Bosch GmbH; Samsung Electronics Co., Ltd.; Sedna Patent Services, LLC; Sharp Kabushiki Kaisha; Siemens AG; Sony Corporation; The Trustees of Columbia University in the City of New York; Toshiba Corporation; UB Video Inc.; and Victor Company of Japan, Limited. Another is expected also to join as of August 1, 2006. MPEG LA's objective is to provide worldwide access to as much AVC essential intellectual property as possible for the benefit of AVC users. Therefore, any party that believes it has essential patents is welcome to submit them for evaluation of their essentiality and inclusion in the License if found essential.

  14. Technical data base quarterly report, April--June 1992; Yucca Mountain Site Characterization Project

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1992-09-01

    The acquisition and development of technical data are activities that provide the information base from which the Yucca mountain Site will be characterized and may P-ventually be licensed as a high-level waste repository. The Project Technical Data Base (TDB) is the repository for the regional and site-specific technical data required in intermediate and license application analyses and models. The TDB Quarterly Report provides the mechanism for identifying technical data currently available from the Project TDB. Due to the variety of scientific information generated by YMP activities, the Project TDB consists of three components, each designed to store specific types of data. The Site and Engineering Properties Data Base (SEPDB) maintains technical data best stored in a tabular format. The Geographic Nodal Information Study and Evaluation System (GENISES), which is the Geographic Information System (GIS) component of the Project TDB, maintains spatial or map-like data. The Geologic and Engineering Materials Bibliography of Chemical Species (GEMBOCHS) data base maintains thermodynamic/geochemical data needed to support geochemical reaction models involving the waste package and repository geochemical environment. Each of these data bases are addressed independently within the TDB Quarterly Report.

  15. Geological and geotechnical investigations for nuclear power plants sites

    International Nuclear Information System (INIS)

    Alves, P.R.R.

    1984-09-01

    This dissertation presents a general methodology for the tasks of geological and geotechnical investigations, to be performed in the proposed sites for construction of nuclear Power Plants. In this work, items dealing with the standards applied to licensing of Nuclear Power Plants, with the selection process of sites and identification of geological and geotechnical parameters needed for the regional and local characterization of the area being studied, were incorporated. This dissertation also provides an aid to the writing of Technical Reports, which are part of the documentation an owner of a Nuclear Power Plant needs to submit to the Comissao Nacional de Energia Nuclear, to fulfill the nuclear installation licensing requirements. Moreover, this work can contribute to the planning of field and laboratory studies, needed to determine the parameters of the area under investigation, for the siting of Nuclear Power Plants. (Author) [pt

  16. Canadian wind technology licensed for use in China

    Energy Technology Data Exchange (ETDEWEB)

    Anon.

    2005-10-01

    A collaboration between Calgary-based Sustainable Energy Technology Ltd. and the China Renewable Energy Technologies Delegation was discussed. Sustainable Energy Technology develops, manufactures and markets products for emerging alternative and renewable energy markets. The aim of the collaboration is to advance the development and commercialization of Darrieus type wind turbines for use in China and other markets around the world. Sustainable Energy will license its technology and expertise in advancing the Chinook 250 vertical axis wind turbine technology, beginning with the construction and testing of a commercial proto-type 250 kW turbine at a test site in southern Alberta. A memorandum of understanding was signed by Guo Shuyan on behalf of the China Renewable Energy Technologies Delegation. It was noted that Shuyan is currently vice chairman of the finance and economic committee of the National People's Congress and was also the executive director of the Three Gorges Project Construction Committee. Sustainable Energy is a leader in vertical axis wind turbines, and the Chinook 250 design was developed with support from Canada's National Research Council in 1999 in order to provide a simple, low-cost turbine that will reduce costly diesel fuel consumption for power generation on small islands in remote areas and throughout the developing world. The agreement with China is subject to approval by National Research Council.

  17. Canadian wind technology licensed for use in China

    International Nuclear Information System (INIS)

    Anon.

    2005-01-01

    A collaboration between Calgary-based Sustainable Energy Technology Ltd. and the China Renewable Energy Technologies Delegation was discussed. Sustainable Energy Technology develops, manufactures and markets products for emerging alternative and renewable energy markets. The aim of the collaboration is to advance the development and commercialization of Darrieus type wind turbines for use in China and other markets around the world. Sustainable Energy will license its technology and expertise in advancing the Chinook 250 vertical axis wind turbine technology, beginning with the construction and testing of a commercial proto-type 250 kW turbine at a test site in southern Alberta. A memorandum of understanding was signed by Guo Shuyan on behalf of the China Renewable Energy Technologies Delegation. It was noted that Shuyan is currently vice chairman of the finance and economic committee of the National People's Congress and was also the executive director of the Three Gorges Project Construction Committee. Sustainable Energy is a leader in vertical axis wind turbines, and the Chinook 250 design was developed with support from Canada's National Research Council in 1999 in order to provide a simple, low-cost turbine that will reduce costly diesel fuel consumption for power generation on small islands in remote areas and throughout the developing world. The agreement with China is subject to approval by National Research Council

  18. The Optimal Licensing Contract in a Differentiated Stackelberg Model

    Directory of Open Access Journals (Sweden)

    Xianpei Hong

    2014-01-01

    Full Text Available This paper extends the work of Wang (2002 by considering a differentiated Stackelberg model, when the leader firm is an inside innovator and licenses its new technology by three options, that is, fixed-fee licensing, royalty licensing, and two-part tariff licensing. The main contributions and conclusions of this paper are threefold. First of all, this paper derives a very different result from Wang (2002. We show that, with a nondrastic innovation, royalty licensing is always better than fixed-fee licensing for the innovator; with a drastic innovation, royalty licensing is superior to fixed-fee licensing for small values of substitution coefficient d; however when d becomes closer to 1, neither fee nor royalty licensing will occur. Secondly, this paper shows that the innovator is always better off in case of two-part tariff licensing than fixed-fee licensing no matter what the innovation size is. Thirdly, the innovator always prefers to license its nondrastic innovation by means of a two-part tariff instead of licensing by means of a royalty; however, with a drastic innovation, the optimal licensing strategy can be either a two-part tariff or a royalty, depending upon the differentiation of the goods.

  19. ACR: Licensing and design readiness

    International Nuclear Information System (INIS)

    Alizadeh, A.

    2009-01-01

    Full text The Canadian nuclear technology has a long history dating back to the 1940s. In this regard, Canada is in a unique situation, shared only by a very few countries, where original nuclear power technology has been invented and further developed. Canadian Nuclear Safety Commission (CNSC), then called AECB, was established in 1946. CNSC focuses on nuclear security, nuclear safety, establishing health and safety regulations, and has also played an instrumental role in the formation of the IAEA. CNSC has provided assistance to the establishment of regulatory authorities in AECL's client countries such as Korea, Argentina, China and Romania. AECL has developed the Gen III+ ACR 1000 as evolutionary advancement of the current CANDU 6 reactor. ACR-1000 has evolved from AECL's in depth experience with CANDU systems, components, and materials, as well as the feedback received from owners and operators of CANDU plants. The ACR-1000 design retains the proven strengths and features of CANDU reactors, while incorporating innovations and state-of-the-art technology. It also features major improvements in economics, inherent safety characteristics, and performance. ACR-1000 has completed its Basic Engineering, has advanced in the licensing process in Canada, and is ready for deployment in Canadian and world markets. EC6 is an evolution of CANDU 6 and is a Gen III natural uranium fuelled reactor. Its medium size and potential for fuel localization and advanced fuel cycles is an optimal strategic solution in many markets.AECL's reactor products are shown to be compliant with a variety of licensing and regulatory requirements. These include the new CNSC DRD-337, IAEA NS-R1, and EUR. This allows the countries interested in CANDU reactor products to be confident of its licensing in their own regulatory regimes.

  20. Analysis of license renewal at U.S. Nuclear Power Plants

    International Nuclear Information System (INIS)

    Nagayama, Munehiro

    2017-01-01

    The U.S. NRC had implemented the rules for LR (License Renewal) of NPPs (Nuclear Power Plants) and the LR rules allow plus 20-year operation of NPPs adding to initial 40-year term for reactor license. The U.S. NRC has already issued ROL (Renewed Operating License) for over forty NPPs. The Atomic Energy Act do not limit the number of LR, so the fleet of U.S. Nuclear, including agency, industry and academy, is continuing efforts to develop rules for SLR (Subsequent License Renewal). The framework of SLR rules has been developed and there is a plan of implementation of SLR for a pilot plant on FY 2018. The total operating term of a SLR plant is 80-year. The LR/SLR of NPPs is effective for stable power supply, greenhouse gas suppression, maintenance of technology, and securing employment. These profits will return to society. It is important to maintain required function of SSCs (Structure, System, and Components) for period of long term operation of NPPs. The U.S. fleet has established integrated ageing management strategy and each NPPs is developing their maintenance plans for long term operation. These adequate maintenance plans may enable to achieve good capacity factor of LR applied NPPs. In this report, domestic LR position will be considered by referring the good performance of U.S. NPPs which entered long term operation beyond 40-year and some conditions such as energy security. (author)

  1. Nuclear licensing in Slovenia

    International Nuclear Information System (INIS)

    Prah, M.; Spiler, J.; Vojnovic, D.; Pristavec, M.

    1998-01-01

    The article presents the approach to nuclear licensing in Slovenia. The paper describes, the initialization, internal authorization and review process in the Krsko NPP. The overall process includes preparation, internal independent evaluation, the Krsko Operating Committee and the Krsko Safety Committee review and internal approval. In addition, the continuation of the licensing process is discussed which includes independent evaluation by an authorized institution and a regulatory body approval process. This regulatory body approval process includes official hearing of the licensee, communication with the licensee, and final issuance of a license amendment. The internal evaluation, which follows the methodology of US NRC (defined in 10 CFR 50.59 and NUMARC 125) is described. This concept is partially implemented in domestic legislation.(author)

  2. Validation, acceptance and licensing

    International Nuclear Information System (INIS)

    Wene, C.O.

    1992-01-01

    The licensing process requires communication of complex scientific and technical information. In this paper transfer of such information is discussed using concepts and ideas from systems analysis, cybernetics and argumentation theory. A simple model for the decision process is developed. The analysis stresses the need for careful design of the communication channels between the three systems involved: the political system, the judicial-regulatory system and the scientific-technical community. The Dialogue - Scenario project initiated by the Swedish nuclear Inspectorate is briefly presented

  3. Regulatory guidance for license renewal

    International Nuclear Information System (INIS)

    Thoma, John A.

    1991-01-01

    The proposed 10 CFR Part 54 rule proceduralizes the process for license renewal by identifying both the administrative and technical requirements for a renewal application. To amplify and support this regulation, written guidance has been provided in the form of a draft Regulatory Guide (DG 1009) and a draft Standard Review Plan for License Renewal (NUREG 1299). This guidance is scheduled to be finalized in 1992. Similar guidance will be provided for the proposed revisions to 10 CFR Part 51 concerning the environmental aspects of license renewal. (author)

  4. Public perspectives on proposed license renewal regulations for nuclear power plants

    International Nuclear Information System (INIS)

    Ligon, D.; Hughes, A.; Seth, S.

    1991-01-01

    On 17 July 1990, the U.S Nuclear Regulatory Commission (NRC) issued for public comment its proposed rule for renewing the operating licenses of nuclear power plants (55 FR 29043). This solicitation marked the fourth time that NRC has Invited public comments on its efforts to develop regulatory requirements for re licensing nuclear power plants. Previously, NRC solicited public comments on establishing a policy statement on plant life extension, and on the issues and options for license renewal discussed in NUREG-1317. On 13-14 November 1989, NRC held a public workshop where the NRC staff discussed a conceptual approach to the rule and solicited written comments on the regulatory philosophy, conceptual rule, and on certain questions. NRC is taking into account all comments received in its development of the final rule which is scheduled for issuance in the summer of 1991

  5. Radon-222 emissions and control practices for licensed uranium mills and their associated tailings piles. Final report

    International Nuclear Information System (INIS)

    1985-06-01

    The report is organized into five main sections. The conclusions of the effort are summarized in Chapter 2. A general description of current milling and tailings management practices and a summary of the site-specific characteristics of operating and standby uranium mills are contained in Chapter-3. The sources and emission rates of radon-222 at licensed mills and their associated tailings piles are contained in Chapter 4 along with the results of an effort to develop generic procedures to estimate radon-222 emissions for milling operations and tailings disposal. Control practices that are being or could be applied to the milling operation and tailings disposal areas and their estimated cost and effectiveness in reducing radon-222 emissions are presented in Chapter 5. The appendices contain detailed information on mill site data and emission estimates

  6. Review of the Brazilian experience in the licensing of nuclear power plants

    International Nuclear Information System (INIS)

    Lederman, L.; Laborne, J.J.

    1983-01-01

    Survey of the licensing of the Brazilian Nuclear Power Plants (NPPs) is presented. The organization and technical expertise of the Comissao Nacional de Energia Nuclear, the Brazilian Regulatory Body, is reviewed with regard to in-house experience, foreign consultants, agreements with regulatory bodies of other countries and research contracts with Brazilian univerisities. The application of the two-stage licensing process and the stage of development of Brazilian nuclear standards is described. Finally, the paper speculates about the future role of probabilistic risk assessment in the Brazilian licensing process

  7. Regulatory Oversight of the Legacy Gunner Uranium Mine and Mill Site in Northern Saskatchewan, Canada - 13434

    Energy Technology Data Exchange (ETDEWEB)

    Stenson, Ron; Howard, Don [Canadian Nuclear Safety Commission, P.O. Box 1046, Station B, 280 Slater Street, Ottawa ON K1P 5S9 (Canada)

    2013-07-01

    As Canada's nuclear regulator, the Canadian Nuclear Safety Commission (CNSC) is responsible for licensing all aspects of uranium mining, including remediation activities at legacy sites. Since these sites already existed when the current legislation came into force in 2000, and the previous legislation did not apply, they present a special case. The Nuclear Safety and Control Act (NSCA), was written with cradle-to- grave oversight in mind. Applying the NSCA at the end of a 'facilities' life-cycle poses some challenges to both the regulator and the proponent. When the proponent is the public sector, even more challenges can present themselves. Although the licensing process for legacy sites is no different than for any other CNSC license, assuring regulatory compliance can be more complicated. To demonstrate how the CNSC has approached the oversight of legacy sites the history of the Commission's involvement with the Gunnar uranium mine and mill site provides a good case study. The lessons learned from the CNSC's experience regulating the Gunnar site will benefit those in the future who will need to regulate legacy sites under existing or new legislation. (authors)

  8. Development of a comprehensive management site evaluation methodology

    International Nuclear Information System (INIS)

    Rodgers, J.C.; Onishi, Y.

    1981-01-01

    The Nuclear Regulatory Commission is in the process of preparing regulations that will define the necessary conditions for adequate disposal of low-level waste (LLW) by confinement in an LLW disposal facility. These proposed regulations form the context in which the motivation for the joint Los Alamos National Laboratory Battelle Pacific Northwest Laboratory program to develop a site-specific, LLW site evaluation methodology is discussed. The overall effort is divided into three development areas: land-use evaluation, environmental transport modelling, and long term scenario development including long-range climatology projections. At the present time four steps are envisioned in the application of the methodology to a site: site land use suitability assessment, land use-ecosystem interaction, contaminant transport simulation, and sensitivity analysis. Each of these steps is discussed in the paper. 12 refs

  9. Interim licensing criteria for physical protection of certain storage of spent fuel

    International Nuclear Information System (INIS)

    Dwyer, P.A.

    1994-11-01

    This document presents interim criteria to be used in the physical protection licensing of certain spent fuel storage installations. Installations that will be reviewed under this criteria are those that store power reactor spent fuel at decommissioned power reactor sites; independent spent fuel storage installations located outside of the owner controlled area of operating nuclear power reactors; monitored retrievable storage installations owned by the Department of Energy, designed and constructed specifically for the storage, of spent fuel; the proposed geologic repository operations area; or permanently shutdown power reactors still holding a Part 50 license. This criteria applies to both dry cask and pool storage. However, the criteria in this document does not apply to the storage of spent fuel within the owner-controlled area of operating nuclear power reactors

  10. Safety philosophy and licensing practice in different member states of IAEA: Canada

    International Nuclear Information System (INIS)

    Boyd, F.C.

    1981-01-01

    The lecture will provide an outline of the Canadian nuclear organization and basic characteristics of the CANDU reactor as a background for a brief description of the nuclear power plant licensing process and the safety philosophy followed. The regulatory agency (Atomic Energy Control Board) follows a three step licensing procedure, Site Acceptance, Construction Approval, Operating Licence. Defense in depth is followed as a general safety concept, but is applied in a special way. Completely separate and independant safety systems are required and basic criteria established through reference dose limits for any assumed failure (or initiating event) in any process (operating) system and for any such failure combined with complete failure at any safety system. The application of the Canadian approach in other countries will be mentioned. (orig./RW)

  11. NUHOMS modular spent-fuel storage system: Design, licensing and construction

    International Nuclear Information System (INIS)

    McLean, J.C.

    1990-08-01

    Carolina Power ampersand Light Company, the US Department of Energy, and the Electric Power Research Institute are participating in a cooperative program to demonstrate the NUHOMS (NUTECH Horizontal Modular Storage) System for storing spent nuclear fuel. This storage concept/design was developed by NUTECH Engineers, which is also participating in the project. The project involves the design, construction, and testing of three reinforced concrete storage modules and three stainless steel canisters at the H. B. Robinson Steam Electric Plant. Testing will focus on (1) the system's operating and fuel handling features, and (2) verification of the design basis of the thermal and shielding performance of the storage modules. As part of the project, NRC approval of the NUTECH Topical Report on NUHOMS has been obtained as well as issuance of a 10CFR Part 72 Materials License for the H. B. Robinson site. 6 refs., 13 figs., 22 tabs

  12. Changing mobility patterns and road mortality among pre-license teens in a late licensing country : an epidemiological study.

    NARCIS (Netherlands)

    Twisk, D.A.M. Bos, N.M. Shope, J.T. & Kok, G.

    2013-01-01

    Whereas the safety of teens in early licensing countries has been extensively studied, little is known about the safety of pre-license teens in late licensing countries, where these teens also may be at risk. This risk exists because of the combination of a) increasing use of travel modes with a

  13. 78 FR 17450 - Notice of Issuance of Materials License Renewal, Operating License SUA-1341, Uranium One USA, Inc...

    Science.gov (United States)

    2013-03-21

    ... License Renewal, Operating License SUA-1341, Uranium One USA, Inc., Willow Creek Uranium In Situ Recovery.... SUA- 1341 to Uranium One USA, Inc. (Uranium One) for its Willow Creek Uranium In Situ Recovery (ISR... Commission License No. SUA-1341 For Uranium One USA, Inc., Irigaray and Christensen Ranch Projects (Willow...

  14. 78 FR 5840 - Notice of License Termination for University of Illinois Advanced TRIGA Reactor, License No. R-115

    Science.gov (United States)

    2013-01-28

    ... University of Illinois Advanced TRIGA Reactor, License No. R-115 The U.S. Nuclear Regulatory Commission (NRC) is noticing the termination of Facility Operating License No. R-115, for the University of Illinois... Operating License No. R-115 is terminated. The above referenced documents may be examined, and/or copied for...

  15. Cost and risk reduction using upfront licensing in Canada. Annex 15

    International Nuclear Information System (INIS)

    Snell, V.G.

    2002-01-01

    The paper summarizes the use of 'up-front' licensing in Canada - how licensing requirements are defined, and met - in advance of a project commitment. The approach to licensing in Canada has allowed flexibility in development of new designs. Since licensing was originally risk-based, and current regulatory policy allows cost-benefit considerations as part of the decision making, risk can be and should be used in novel circumstances as a licensing tool. Since the licensing framework is non-prescriptive, innovative approaches to design can be introduced and dispositioned without changing the legal structure. This flexibility has been used in several up-front licensing reviews: a small urban heating reactor, repeat CANDU 6 generating station units, and the single unit CANDU 9 generating station. In the future we expect to apply it to advanced designs, as an essential part of risk reduction and customer confidence in the product. The important lessons learned in Canada include: Up-front licensing is essential to reduce the risk of licensing-related delays once a project has been committed. It requires a significant investment in time and effort from both the designer and the regulator; The most effective scope for up-front licensing is for the regulator to thoroughly assess novel concepts, test the design against changed domestic requirements, and follow-up on known difficult areas; and for the designer to ensure foreign requirements are incorporated. There is little benefit in certifying the design in detail; Although it would be satisfying to have legally-binding certification, in the end there can be no legal obligation on the regulator, and agreement is pursued on the basis of good faith that the regulator will not make arbitrary decisions and that the designer will meet agreed targets or requirements; In almost all circumstances, issues will arise that are beyond the current 'rules', however expressed. Rather than rushing to create new rules, one reaches a

  16. Managing technology licensing for stochastic R&D: from the perspective of an enterprise information system

    Science.gov (United States)

    Hong, Xianpei; Zhao, Dan; Wang, Zongjun

    2016-10-01

    Enterprise information technology (IT) plays an important role in technology innovation management for high-tech enterprises. However, to date most studies on enterprise technology innovation have assumed that the research and development (R&D) outcome is certain. This assumption does not always hold in practice. Motivated by the current practice of some IT industries, we establish a three-stage duopoly game model, including the R&D stage, the licensing stage and the output stage, to investigate the influence of bargaining power and technology spillover on the optimal licensing policy for the innovating enterprise when the outcome of R&D is uncertain. Our results demonstrate that (1) if the licensor has low (high) bargaining power, fixed-fee (royalty) licensing is always superior to royalty (fixed-fee) licensing to the licensor regardless of technology spillover; (2) if the licensor has moderate bargaining power and technology spillover is low (high) as well, fixed-fee (royalty) licensing is superior to royalty (fixed-fee) licensing; (3) under two-part tariff licensing and the assumption of licensors with full bargaining power, if a negative prepaid fixed fee is not allowed, two-part tariff licensing is equivalent to royalty licensing which is the optimal licensing policy; if negative prepaid fixed fee is allowed, the optimal policy is two-part tariff licensing.

  17. A meta-analytic review of moral licensing.

    Science.gov (United States)

    Blanken, Irene; van de Ven, Niels; Zeelenberg, Marcel

    2015-04-01

    Moral licensing refers to the effect that when people initially behave in a moral way, they are later more likely to display behaviors that are immoral, unethical, or otherwise problematic. We provide a state-of-the-art overview of moral licensing by conducting a meta-analysis of 91 studies (7,397 participants) that compare a licensing condition with a control condition. Based on this analysis, the magnitude of the moral licensing effect is estimated to be a Cohen's d of 0.31. We tested potential moderators and found that published studies tend to have larger moral licensing effects than unpublished studies. We found no empirical evidence for other moderators that were theorized to be of importance. The effect size estimate implies that studies require many more participants to draw solid conclusions about moral licensing and its possible moderators. © 2015 by the Society for Personality and Social Psychology, Inc.

  18. Licensing review process of the European Spallation Source (ESS) research facility

    International Nuclear Information System (INIS)

    Brewitz, Erica

    2014-01-01

    On 3 January 2012 a license application under the Radiation Protection Act (SFS, 1988b) for the European Spallation Source research facility was submitted to the Swedish Radiation Safety Authority. The European Spallation Source research facility will be the site of a new and quite unusual kind of neutron source, based on a large proton accelerator that bombards a heavy material with protons. The Swedish Radiation Safety Authority is now reviewing the application. (authors)

  19. Chinese License Plates Recognition Method Based on A Robust and Efficient Feature Extraction and BPNN Algorithm

    Science.gov (United States)

    Zhang, Ming; Xie, Fei; Zhao, Jing; Sun, Rui; Zhang, Lei; Zhang, Yue

    2018-04-01

    The prosperity of license plate recognition technology has made great contribution to the development of Intelligent Transport System (ITS). In this paper, a robust and efficient license plate recognition method is proposed which is based on a combined feature extraction model and BPNN (Back Propagation Neural Network) algorithm. Firstly, the candidate region of the license plate detection and segmentation method is developed. Secondly, a new feature extraction model is designed considering three sets of features combination. Thirdly, the license plates classification and recognition method using the combined feature model and BPNN algorithm is presented. Finally, the experimental results indicate that the license plate segmentation and recognition both can be achieved effectively by the proposed algorithm. Compared with three traditional methods, the recognition accuracy of the proposed method has increased to 95.7% and the consuming time has decreased to 51.4ms.

  20. License - KEGG MEDICUS | LSDB Archive [Life Science Database Archive metadata

    Lifescience Database Archive (English)

    Full Text Available [ Credits ] English ]; } else if ( url.search(//en//) != -1 ) { url = url.replace(/...switchLanguage; BLAST Search Image Search Home About Archive Update History Data List Contact us KEGG MEDI...ion-NonCommercial-NoDerivs 2.1 Japan. If you use data from this database, please be sure attribute this data...whole of this database, and acquire data; and freely redistribute part or whole of the data from this databa...This Database Site Policy | Contact Us License - KEGG MEDICUS | LSDB Archive ...