  1. Numerical Simulation of Measurements during the Reactor Physical Startup at Unit 3 of Rostov NPP

    Science.gov (United States)

    Tereshonok, V. A.; Kryakvin, L. V.; Pitilimov, V. A.; Karpov, S. A.; Kulikov, V. I.; Zhylmaganbetov, N. M.; Kavun, O. Yu.; Popykin, A. I.; Shevchenko, R. A.; Shevchenko, S. A.; Semenova, T. V.

    2017-12-01

    The results of numerical calculations and measurements of some reactor parameters during the physical startup tests at unit 3 of Rostov NPP are presented. The following parameters are considered: the critical boron acid concentration and the currents from ionization chambers (IC) during the scram system efficiency evaluation. The scram system efficiency was determined using the inverse point kinetics equation with the measured and simulated IC currents. The results of steady-state calculations of relative power distribution and efficiency of the scram system and separate groups of control rods of the control and protection system are also presented. The calculations are performed using several codes, including precision ones.

  2. Ecological Congress and the safety problems of the Rostov region

    International Nuclear Information System (INIS)

    Madoyan, A.A.

    2001-01-01

    A brief description of activities of the 3 research and technical conference Ecological Congress (April 16-17, 2001), dealing with problems of reliability and safety of the Rostov NPP operation, is provided. More than 25 reports on problems pertaining to radiation safety and ecology, development and introduction for new research and technical approaches, reliability of building structures, account of human factor during operation of industrial facilities, etc. were submitted. By and large, participants to the conference supported construction for facilities necessary for regional economy upsurge like the Rostov NPP, on condition of high-quality construction and safe operation [ru

  3. Nuclear Power Plant (NPP) safety in Brazil

    International Nuclear Information System (INIS)

    Lederman, L.

    1980-01-01

    The multidisciplinary aspects of the activities involved in the nuclear power plant (NPP) licensing, are presented. The activities of CNEN's technical staff in the licensing of Angra-1 and Angra-2 power plants are shown. (E.G.) [pt

  4. About choosing the power unit of NPP

    International Nuclear Information System (INIS)

    Alekseev, P.N.; Mordashev, V.M.; Proshkin, A.A.; Stukalov, V.A.; Subbotin, S.A.; Tsibul'skij, V.F.; Chernilin, Yu.F.

    2008-01-01

    The present-day domestic nuclear power industry faces the necessity to make both process and economy related decisions. The mentioned decisions should cover all the aspects of the nuclear power complex. In particular, as of now, no substantiation of the present-day and the future requirements for the power unit of the WWER and fast reactor NPPs is available. The choice of the unit power of an NPP should involve consideration of all factors and should not be boiled down to the efforts to ensure the minimization of the investment and the operation constituents of the electric power generation costs. The aim of the present paper was to ensure elaboration of the recommendations to substantiate the optimal unit power of NPP power units based on the analysis of various factors to design, to construct and to operate an NPP (investment, time of construction, the unscheduled shutdown losses, the unification, the fabrication quality, the accident damage, etc.), and the electrical network potentialities and the regional electric power demands [ru

  5. Core power capability verification for PWR NPP

    International Nuclear Information System (INIS)

    Xian Chunyu; Liu Changwen; Zhang Hong; Liang Wei

    2002-01-01

    The Principle and methodology of pressurized water reactor nuclear power plant core power capability verification for reload are introduced. The radial and axial power distributions of normal operation (category I or condition I) and abnormal operation (category II or condition II) are simulated by using neutronics calculation code. The linear power density margin and DNBR margin for both categories, which reflect core safety, are analyzed from the point view of reactor physics and T/H, and thus category I operating domain and category II protection set point are verified. Besides, the verification results of reference NPP are also given

  6. Principles of tariff determination for NPP electric power generation

    International Nuclear Information System (INIS)

    Ratnikov, B.E.; Gitel'man, L.D.; Artemov, Yu.N.; Fiantsev, V.S.

    1988-01-01

    Foundations of price-setting and order of accounting arrangement for NPP electric power are considered. NPP tariffs are established proceeding from standard costs of power generation. The standards are differentiated as to NPP groups, depending on technical, regional and natural geographic factors, taking into account the facility type, unit capacity and the number of similar NPP units. The conclusion is made that under conditions of NPP economic independence expansion and creation of prerequisites for going over to self-financing principles and also due to the qualitatively new stage of nuclear power generation development the level of efficiency, forseen by the tariffs, should be increased

  7. Nuclear Power Plant Module, NPP-1: Nuclear Power Cost Analysis.

    Science.gov (United States)

    Whitelaw, Robert L.

    The purpose of the Nuclear Power Plant Modules, NPP-1, is to determine the total cost of electricity from a nuclear power plant in terms of all the components contributing to cost. The plan of analysis is in five parts: (1) general formulation of the cost equation; (2) capital cost and fixed charges thereon; (3) operational cost for labor,…

  8. Digital Components in Swedish NPP Power Systems

    International Nuclear Information System (INIS)

    Karlsson, Mattias; Eriksson, Tage

    2015-01-01

    Swedish nuclear power plants have over the last 20 years of operation modernised or exchanged several systems and components of the electrical power system. Within these works, new components based on digital technology have been employed in order to realize functionality that was previously achieved by using electro-mechanical or analogue technology. Components and systems such as relay protection, rectifiers, inverters, variable speed drives and diesel-generator sets are today equipped with digital components. Several of the systems and components fulfil functions with a safety-role in the NPP. Recently, however, a number of incidents have occurred which highlight deficiencies in the design or HMI of the equipment, which warrants questions whether there are generic problems with some applications of digital components that needs to be addressed. The use of digital components has presented cost effective solutions, or even the only available solution on the market enabling a modernisation. The vast majority of systems using digital components have been operating without problems and often contribute to improved safety but the challenge of non-detectable, or non-identifiable, failure modes remain. In this paper, the extent to which digital components are used in Swedish NPP power systems will be presented including a description of typical applications. Based on data from maintenance records and fault reports, as well as interviews with designers and maintenance personnel, the main areas where problems have been encountered and where possible risks have been identified will be described. The paper intends to investigate any 'tell-tales' that could give signals of unwanted behaviour. Furthermore, particular benefits experienced by using digital components will be highlighted. The paper will also discuss the safety relevance of these findings and suggest measures to improve safety in the application of digital components in power systems. (authors)

  9. Assessment of financial expenditure for Rivne NPP power units decommissioning

    International Nuclear Information System (INIS)

    Nosovskij, A.V.; Salij, L.M.

    2007-01-01

    The article covers some financial aspects of developing a decommissioning concept for Rivne NPP power units with reactor VVER-440 and VVER-1000. Possible methodological approaches to costs estimate have been analyzed. Preliminary results of cost estimation are presented for two decommissioning options: deferred and immediate dismantling. Principally possible options for accumulating assets have been analyzed to finance measures related to Rivne NPP decommissioning. A mathematical model has been proposed for creating decommissioning financial reserve

  10. To question of NPP power reactor choice for Kazakhstan

    International Nuclear Information System (INIS)

    Batyrbekov, G.A.; Makhanov, Y.M.; Reznikova, R.A.; Sidorenco, A.V.

    2004-01-01

    Full text: The requirements to NPP power reactors that will be under construction in Kazakhstan are proved and given in the report. A comparative analysis of the most advanced projects of power reactors with light and heavy water under pressure of large, medium and low power is carried out. Different reactors have been considered as follows: 1. Reactors with high-power (700 MW(el) and up) such as EPR, French - German reactor; CANDU-9, Canadian heavy-water reactor; System 80+, developed by ABB Combustion Engineering company, USA; KNGR, Korean reactor of the next generation; APWR, Japanese advanced reactor; WWER-1000 (V-392) - development of Atomenergoproect /Gydropress, Russian Federation; EP 1000, European passive reactor. 2. Reactors with medium power (300 MW (el) - 700 MW (el): AP-600, passive PWR of the Westinghouse company; CANDU-6, Canadian heavy-water reactor; AC-600, Chinese passive PWR; WWER-640, Russian passive reactor; MS-600 Japanese reactor of Mitsubishi Company; KSNP-600, South Korean reactor. 3. Reactors with low power (a few MW(el)- 300 MW(el)): IRIS, reactor of IV generation, developed by the International Corporation of 13 organizations from 7 countries, SMART, South Korean integrated reactor; CAREM, Argentina integrated reactor; MRX, Japanese integrated reactor; 'UNITERM', Russian NPP with integrated reactor, development of NIKIET; AHEC-80, Russian NPP, developed by OKBM. A comparison of the projects of the above-mentioned power reactors was carried out with respect to 15 criteria of nuclear, radiating, ecological safety and economic competitiveness, developed especially for this case. Data on a condition and prospects of power production and power consumption, stations and networks in Kazakhstan necessary for the choice of projects of NPP reactors for Kazakhstan are given. According to the data a balance of power production and power consumption as a whole in the country was received at the level of 59 milliard kw/h. However, strong dis balance

  11. To question of NPP power reactor choice for Kazakhstan

    International Nuclear Information System (INIS)

    Batyrbekov, G.A.; Makhanov, Y.M.; Reznikova, R.A.; Sidorenco, A.V.

    2004-01-01

    The requirements to NPP power reactors that will be under construction in Kazakhstan are proved and given in the report. A comparative analysis of the most advanced projects of power reactors with light and heavy water under pressure of large, medium and low power is carried out. Different reactors have been considered as follows: 1. Reactors with high-power (700 MW(el) and up) such as EPR, French - German reactor; CANDU-9, Canadian heavy-water reactor; System 80+, developed by ABB Combustion Engineering company, USA; KNGR, Korean reactor of the next generation; APWR, Japanese advanced reactor; WWER-1000 (V-392) - development of Atomenergoproect /Gydropress, Russian Federation; EP 1000, European passive reactor. 2. Reactors with medium power (300 MW (el) - 700 MW (el): AP-600, passive PWR of the Westinghouse company; CANDU-6, Canadian heavy-water reactor; AC-600, Chinese passive PWR; WWER-640, Russian passive reactor; MS-600 Japanese reactor of Mitsubishi Company; KSNP-600, South Korean reactor. 3. Reactors with low power (a few MW(el)- 300 MW(el)): IRIS, reactor of IV generation, developed by the International Corporation of 13 organizations from 7 countries, SMART, South Korean integrated reactor; CAREM, Argentina integrated reactor; MRX, Japanese integrated reactor; 'UNITERM', Russian NPP with integrated reactor, development of NIKIET; AHEC-80, Russian NPP, developed by OKBM. A comparison of the projects of the above-mentioned power reactors was carried out with respect to 15 criteria of nuclear, radiating, ecological safety and economic competitiveness, developed especially for this case. Data on a condition and prospects of power production and power consumption, stations and networks in Kazakhstan necessary for the choice of projects of NPP reactors for Kazakhstan are given. According to the data a balance of power production and power consumption as a whole in the country was received at the level of 59 milliard kw/h. However, strong dis balance in the

  12. Modernization and power upgrading of the Loviisa NPP

    International Nuclear Information System (INIS)

    Keskinen, A.

    1997-01-01

    In 1995, Imatran Voima Oy (IVO) started a project for modernization and power upgrading of the Loviisa NPP. The main objectives of the project are to ensure plant safety, to increase electricity production and to improve the expertise of the IVO staff. The total electricity output of Loviisa 1 and 2 units is planned to be increased by about 100 MW. This will be achieved through renovation of the steam turbines and through gradual increase in the thermal reactor power up to 1,500 MW from the present level of 1,375 MW. The Loviisa NPP Final Safety Analysis Report has been revised to a great extent in connection with the licensing process of the reactor power upgrading. The project also includes certain improvements in the primary and safety systems to ensure plant safety. The total cost estimate of the project is around 200 million FIM. The project implementation started in 1995 and in accordance with the plans in 2000 after several phases the last measures at power plant will be completed. (orig.)

  13. Modernization and power upgrading of the Loviisa NPP

    Energy Technology Data Exchange (ETDEWEB)

    Keskinen, A. [IVO Power Engineering Ltd., Vantaa (Finland)

    1997-12-31

    In 1995, Imatran Voima Oy (IVO) started a project for modernization and power upgrading of the Loviisa NPP. The main objectives of the project are to ensure plant safety, to increase electricity production and to improve the expertise of the IVO staff. The total electricity output of Loviisa 1 and 2 units is planned to be increased by about 100 MW. This will be achieved through renovation of the steam turbines and through gradual increase in the thermal reactor power up to 1,500 MW from the present level of 1,375 MW. The Loviisa NPP Final Safety Analysis Report has been revised to a great extent in connection with the licensing process of the reactor power upgrading. The project also includes certain improvements in the primary and safety systems to ensure plant safety. The total cost estimate of the project is around 200 million FIM. The project implementation started in 1995 and in accordance with the plans in 2000 after several phases the last measures at power plant will be completed. (orig.). 4 refs.

  14. Modernization and power upgrading of the Loviisa NPP

    Energy Technology Data Exchange (ETDEWEB)

    Keskinen, A [IVO Power Engineering Ltd., Vantaa (Finland)

    1998-12-31

    In 1995, Imatran Voima Oy (IVO) started a project for modernization and power upgrading of the Loviisa NPP. The main objectives of the project are to ensure plant safety, to increase electricity production and to improve the expertise of the IVO staff. The total electricity output of Loviisa 1 and 2 units is planned to be increased by about 100 MW. This will be achieved through renovation of the steam turbines and through gradual increase in the thermal reactor power up to 1,500 MW from the present level of 1,375 MW. The Loviisa NPP Final Safety Analysis Report has been revised to a great extent in connection with the licensing process of the reactor power upgrading. The project also includes certain improvements in the primary and safety systems to ensure plant safety. The total cost estimate of the project is around 200 million FIM. The project implementation started in 1995 and in accordance with the plans in 2000 after several phases the last measures at power plant will be completed. (orig.). 4 refs.

  15. Experience in NPP operation and prospects of nuclear power development in France

    International Nuclear Information System (INIS)

    Lekler, Zh.

    1986-01-01

    Main results and perspectives of nuclear power development in France are analysed. Data characterizing operation of NPPs with PWR reactors in France and leading capitalist countries are given. Problems related to the organization of works on control of NPP operation and its maintenance are discussed. Power utilization factor for french power units amounted to 75% in 1984. NPP share of all electric power generated in the country constituted 59%. Emergency reactor shut-downs took 5% of calendar time in 1984

  16. Technical and economical problems of decommissioning nuclear power plants (NPP) in Russia

    International Nuclear Information System (INIS)

    Vaneev, M.

    2001-01-01

    The introduction per new century has brought to atomic Engineering many new problems. One of them, which has got a serious urgency, we now shall consider. It is a problem of decommissioning NPP in Russia. By 2014 all maintained nowadays NPP in Russian Federation will develop the regular service life. And all of them on idea should be removed from operation. But, as we understand, in today's difficult economic conditions, to it NPP the procedure of prolongation of service life will be applied, and where it is impossible by virtue of the various reasons, the procedure of translation NPP in nuclear - safe condition and in a mode of a long storage under supervision, before acceptance of the decision about a method and way of financing of a decommissioning will be applied. Possible the following variants will be: use platforms of the old NPP for construction new NPP, or using as burial place NPP. The variant of a decommissioning up to a condition 'green grass' is represented unprofitable because of its dearness. The similar decommissioning was carried out in Japan. Was removed from operation research reactor of a type WWR. The expenses for this method of a decommissioning considerably surpass expenses for a method of a burial place NPP basically because of high cost of dismantle and transportation in long-term storehouses of the 1 contour equipment. The most urgent problem of decommissioning NPP, which developed their regular service life - is financing this final stage of a exploitation cycle of the block. I shall remind, that the financing is carried out from uniform fund of decommissioning. The formation of this fund occurs by deduction 1.3 % of cost of the put electric power to the consumers by all maintained NPP of Russia. The expenditure of this fund is carried on time on some tens years. They are spent for 3 basic stages: preparation to decommissioning NPP, long endurance under supervision, dismantle and burial the NPP equipment. Nowadays on faculty NPP MPEI

  17. Canine and Human Dirofilariosis in the Rostov Region (Southern Russia

    Directory of Open Access Journals (Sweden)

    Vladimir Kartashev

    2011-01-01

    Full Text Available Epidemiological data on canine and human dirofilariosis in the Rostov Region (Southern Russia are presented. Prevalence of Dirofilaria spp. infections in 795 autochthonous dogs, assessed by the Knott test, was 20.25%. The highest prevalence was found in Novocherkassk (38.3% and Rostov-on-Don (18.5%, while prevalences were lower in other points of the region. Prevalence of D. repens was 44.7%, prevalence of D. immitis was 30.3%, and coinfections were observed in 25.0% of the dog population. A case finding study carried out during 9 years (2000–2009 revealed 131 cases of human dirofilariosis in the Rostov Region, 129 of subcutaneous dirofilariosis and 2 of pulmonary dirofilariosis. Seroprevalence among 317 healthy blood donors from the Rostov Region was 10.4%, while seroprevalence in policemen living in Rostov city and working in training dogs was 19%. These data show high infection rates of Dirofilaria spp. in both human and dog populations of Rostov, probably because of the existence of favorable conditions for the transmission in this region.

  18. Conceptual Design of a Combined Power Generation Unit at the NPP Seaside

    International Nuclear Information System (INIS)

    Cha, Kyung H.

    2011-01-01

    In order to improve operational performance, an undersea tunnel is being utilized for in-taking and out-taking seawater as coolant in Nuclear Power Plant (NPP). This paper describes a Combined solar-wind-wave Power Generation Unit (CPGU) to be specialized for in-taking and out-taking seawater as coolant in NPP. Accordingly, the purpose of the CPGU is twofold: one is to contain some tunnels to be maintained on the bottom of the CPGU body in order to in-take and out-take coolant water, and the other is to generate a combined power at the NPP seaside. Fig. 1 shows the conceptual CPGU to be configured at the NPP seaside

  19. Study on the power control system for NPP power unit with the WWER-440 reactor

    International Nuclear Information System (INIS)

    Aleksandrova, N.D.; Naumov, A.V.

    1981-01-01

    Results of model investigations into basic version of the power control systems (PCS) conformably to the WWER-440 NPP power unit are stated. Transient processes in the power unit system when being two PCS versions during perturbations of different parameters: unit power, vapour pressure or position of control rods have been simulated. Investigations into the different PCS versions show that quality of operation of a traditional scheme with a turbine power controller and reactor pressure controller can be significantly improved with the introduction of a high-speed signal of pressure into the reactor controller. The PCS version with the compensation of interrelations between the turbine and reactor controllers constructed according to the same principles as the standard schemes of power units of thermal electric power plant is perspective as well [ru

  20. Calculation of economic and financing of NPP and conventional power plant using spreadsheet innovation

    International Nuclear Information System (INIS)

    Moch Djoko Birmano; Imam Bastori

    2008-01-01

    The study for calculating the economic and financing of Nuclear Power Plant (NPP) and conventional power plant using spreadsheet Innovation has been done. As case study, the NPP of PWR type of class 1050 MWe is represented by OPR-1000 (Optimized Power Reactor, 1000 MWe) and the conventional plant of class 600 MWe, is coal power plant (Coal PP). The purpose of the study is to assess the economic and financial feasibility level of OPR-1000 and Coal PP. The study result concludes that economically, OPR-1000 is more feasible compared to Coal PP because its generation cost is cheaper. Whereas financially, OPR-1000 is more beneficial compared to Coal PP because the higher benefit at the end of economic lifetime (NPV) and the higher ratio of benefit and cost (B/C Ratio). For NPP and Coal PP, the higher Discount Rate (%) is not beneficial. NPP is more sensitive to the change of discount rate compared to coal PP, whereas Coal PP is more sensitive to the change of power purchasing price than NPP. (author)

  1. 76 FR 46330 - NUREG-1934, Nuclear Power Plant Fire Modeling Application Guide (NPP FIRE MAG); Second Draft...

    Science.gov (United States)

    2011-08-02

    ... NUCLEAR REGULATORY COMMISSION [NRC-2009-0568] NUREG-1934, Nuclear Power Plant Fire Modeling... 1023259), ``Nuclear Power Plant Fire Modeling Application Guide (NPP FIRE MAG), Second Draft Report for...), ``Nuclear Power Plant Fire Modeling Application Guide (NPP FIRE MAG), Second Draft for Comment,'' is...

  2. Load flow analysis for determining the location of NPP power distribution in West Kalimantan

    International Nuclear Information System (INIS)

    Citra Candranurani; Rizki Finnansyah Setya Budi; Sahala M Lumbanraja

    2015-01-01

    Electricity crisis condition happened in West Kalimantan (Kalbar) as a result of power plant capacity almost equal to the peak load. The system will experience a shortfall if there are plants that not operating and do not have reserve. The policy of electricity planning until 2022 is replacing diesel power plant with steam power plant. For long-term planning is required the role of new and renewable energy in order to reduce dependency on fossil fuel consumption, such as NPP utilization. The purpose of this study was to determine the optimum location of the NPP power distribution in order to prepare electricity infrastructure. Load flow calculation in this study using ETAP 12.5 software. NPP is planned to supply base load, so the optimum capacity factor is above 80 %. The result show that there are three location where NPP can generate over 80 % of its capacity, namely: Mempawah Substation, Singkawang Substation, and Sambas Substation. The most optimum located in Mempawah Substation with capacity factor 83.5 %. The location of the three Substation are onshore and in line with one requirement for NPP construction, namely: the availability of cooling water. (author)

  3. Advances in safety countermeasures at the Tomari NPP of Hokkaido Electric Power on the basis of Fukushima Daiichi NPP accident. Fire protection and other advances

    International Nuclear Information System (INIS)

    Shibata, Taku; Dasai, Katsumi

    2014-01-01

    Fire protections for the nuclear power plants have been based on the fire laws and the conventional guide. After Fukushima Daiichi NPP accident, many safety countermeasures - also about Fire Protection - have been discussed in the Japanese authorities. This paper shows our present activities in the Tomari NPP about the fire protections from the view points of Fire Prevention, Fire Detection/Suppression Systems and Fire Protection, and other advances. (author)

  4. Improved Nuclear Power Plant maintenance. Application to Cofrentes NPP

    International Nuclear Information System (INIS)

    Serradell, V.

    2002-01-01

    The Industrial Safety and Environment Group (MEDASEGI) of the Valencia Polytechnic University (UPV) develops its activities in the fields of environmental radioactivity metrology and risk analysis and management aimed at improving industrial safety. The different lines of research developed by this group include collaboration with Cofrentes NPP. This collaboration began in 1993 and has primarily focused on issues related to improved maintenance and currently on life management. (Author)

  5. Arrangement of the Krsko NPP protection scheme for the power system malfunction cases

    International Nuclear Information System (INIS)

    Omahen, P.; Pavsek, J.; Dirnbek, V.

    1996-01-01

    The Krsko NPP has been designed with the capability to reject 100% of its rated power and runback to the station electrical load. However, an adequate detection system of the outside network degradation is needed for the activation of the existing load drop anticipated (LDA) function. The Krsko NPP electrical, turbine and generator protection systems were carefully evaluated in order to redesign some of its functions. These additional functions should be able to protect and disconnect the plant from the system whenever some serious trouble of the outside electric power system is detected. On the other side, preventive measures should be introduced to avoid unnecessary plant disconnection or unnecessary power system collapse due to such disconnection. At the end, the paper presents a precise design of additional function possibilities for the Krsko NPP electrical protection system. A critical evaluation of these functions is given and the best option is proposed. (author)

  6. Uninterruptible power supply model of independent voltage inverter of NPP electrical equipment

    International Nuclear Information System (INIS)

    Rozhkov, V.V.; Ajdaralieva, V.Eh.

    2010-01-01

    A package of main transforming units models of advanced uninterruptible power supply systems of NPP electrical equipment was developed. The package of models allows investigating the basic modes of uninterruptible power supply systems operation by computer modeling. Simulation results were presented. Recommendations on choice of parameters of power circuit elements as well as on diagnostics and adjustment of regulators of converters control systems were given [ru

  7. A Study on Human Factors in Maintenance of a Nuclear Power Plant (NPP)

    International Nuclear Information System (INIS)

    Park, Young Ho; Seong, Poong Hyun

    2006-01-01

    In human factors research, more attention has been devoted to the operation of a nuclear power plant (NPP) than to their maintenance. However, more NPP incidents are caused by inadequate maintenance rather than by faulty operation. There is a trend in NPP toward introducing digital technology into safety and non-safety systems. This lead to changes of maintenance, and support systems such as diagnosis system, augmentation system and handy terminal will be developed. In this context, it is important to identify tasks of human related to each phase of maintenance and their relation in order to apply those to maintenance. However, there are few researches of human factors in maintenance. This paper studies on framework of cognitive task analysis for developing maintenance support systems

  8. Nuclear power plant maintenance personnel reliability prediction (NPP/MPRP) effort at Oak Ridge National Laboratory

    International Nuclear Information System (INIS)

    Knee, H.E.; Haas, P.M.; Siegel, A.I.

    1981-01-01

    Human errors committed during maintenance activities are potentially a major contribution to the overall risk associated with the operation of a nuclear power plant (NPP). An NRC-sponsored program at Oak Ridge National Laboratory is attempting to develop a quantitative predictive technique to evaluate the contribution of maintenance errors to the overall NPP risk. The current work includes a survey of the requirements of potential users to ascertain the need for and content of the proposed quantitative model, plus an initial job/task analysis to determine the scope and applicability of various maintenance tasks. In addition, existing human reliability prediction models are being reviewed and assessed with respect to their applicability to NPP maintenance tasks. This paper discusses the status of the program and summarizes the results to date

  9. An Extreme Meteorological Events Analysis For Nuclear Power Plant (NPP) Siting Project at Bangka Island, Indonesia

    Science.gov (United States)

    Septiadi, Deni; S, Yarianto Sugeng B.; Sriyana; Anzhar, Kurnia; Suntoko, Hadi

    2018-03-01

    The potential sources of meteorological phenomena in Nuclear Power Plant (NPP) area of interest are identified and the extreme values of the possible resulting hazards associated which such phenomena are evaluated to derive the appropriate design bases for the NPP. The appropriate design bases shall be determined according to the Nuclear Energy Regulatory Agency (Bapeten) applicable regulations, which presently do not indicate quantitative criteria for purposes of determining the design bases for meteorological hazards. These meteorological investigations are also carried out to evaluate the regional and site specific meteorological parameters which affect the transport and dispersion of radioactive effluents on the environment of the region around the NPP site. The meteorological hazards are to be monitored and assessed periodically over the lifetime of the plant to ensure that consistency with the design assumptions is maintained throughout the full lifetime of the facility.

  10. Strategy of Commercial Real Estate Market Development and Interests of the Region: Rostov Region

    Directory of Open Access Journals (Sweden)

    Kosarev Roman, V.

    2016-07-01

    Full Text Available The author discusses the features of the development of commercial real estate market in the Rostov region on the assumption of a relationship between the vector of entrepreneurial activity and the dynamics of supply and demand of real estate in the context of the public interest. The urgency of the problem is due to the institutional nature of commercial real estate in business development, which is neglected in the practice of public exposure due to lack of methodological support and instrumentality. Based on the self-organization of these dynamic models related economic systems in the economy of the region, a logical assessment of the trends of development of business in the consumer market in the context of the real estate needs as infrastructure is given. It allows to identify the main patterns of development and its specific regional features. Statistical evaluation of the cost of renting and buying commercial real estate in Rostov-on-Don city has helped to identify new strategies for business development, requiring the transformation of commercial property types, proposed in the framework of regional program with a focus on five trends of Global Power of Retailing 2015.

  11. Development of Information Datasheets of Nuclear Power Plant (NPP) Equipment using cfiXLM schema

    International Nuclear Information System (INIS)

    Lee, Jaiho; Song, Eunhye

    2014-01-01

    In 2009, EPRI (Electrical Power Research Institute) published a new NPP information handover guide to provide NPP owners and operators with data handover templates in consistent format for effective delivery of information during all stages of the handover process. Another difficult concern for NPP data information management is to exchange the data information among many organizations such as NPP owners, operators, engineering companies, suppliers, and vendors. As a matter of fact, the improperly formatted handover of information sometimes occurs due to the discrepancy of data format (e. g., data description language type). This improper delivery can make negative effects on NPP integrity and safety. Thus, the lack of proper exchange for different data information systems of organizations should be resolved by using an international standard data format. The standard data format can reduce the cost and time for data exchange in each phase for design, procurement, delivery, installation, operation and maintenance of equipment. The AEX(automating equipment information exchange) pilot implementation project team under EPRI advanced nuclear technology (ANT) program has been conducted a research for the use of XML equipment schemas for electronic data exchange(EDE). They applied XML equipment schema for the design, selection, quotation, purchase and mock install of a safety injection centrifugal pump using EDE standard HI(hydraulic institute) 50.7. For data exchange, FIATECH, an industry consortium, has equally developed library of templates and reference data for ISO-15926, which is an international standard capable of reducing data-error and delivery time for exchanging data among different organizations. KHNP as an only owner/operator company has not experienced much difficulty in data interoperability with other organizations, but continued its unremitting exertions to develop a robust system capable of managing data information generated in all the stages of NPP

  12. Development of Information Datasheets of Nuclear Power Plant (NPP) Equipment using cfiXLM schema

    Energy Technology Data Exchange (ETDEWEB)

    Lee, Jaiho; Song, Eunhye [KHNP-Central Research Institute, Daejeon (Korea, Republic of)

    2014-05-15

    In 2009, EPRI (Electrical Power Research Institute) published a new NPP information handover guide to provide NPP owners and operators with data handover templates in consistent format for effective delivery of information during all stages of the handover process. Another difficult concern for NPP data information management is to exchange the data information among many organizations such as NPP owners, operators, engineering companies, suppliers, and vendors. As a matter of fact, the improperly formatted handover of information sometimes occurs due to the discrepancy of data format (e. g., data description language type). This improper delivery can make negative effects on NPP integrity and safety. Thus, the lack of proper exchange for different data information systems of organizations should be resolved by using an international standard data format. The standard data format can reduce the cost and time for data exchange in each phase for design, procurement, delivery, installation, operation and maintenance of equipment. The AEX(automating equipment information exchange) pilot implementation project team under EPRI advanced nuclear technology (ANT) program has been conducted a research for the use of XML equipment schemas for electronic data exchange(EDE). They applied XML equipment schema for the design, selection, quotation, purchase and mock install of a safety injection centrifugal pump using EDE standard HI(hydraulic institute) 50.7. For data exchange, FIATECH, an industry consortium, has equally developed library of templates and reference data for ISO-15926, which is an international standard capable of reducing data-error and delivery time for exchanging data among different organizations. KHNP as an only owner/operator company has not experienced much difficulty in data interoperability with other organizations, but continued its unremitting exertions to develop a robust system capable of managing data information generated in all the stages of NPP

  13. Seismic analysis of a NPP reactor building using spectrum-compatible power spectral density functions

    International Nuclear Information System (INIS)

    Venancio Filho, F.; DeCarvalho Santos, S.H.; Joia, L.A.

    1987-01-01

    A numerical methodology to obtain Power Spectral Density Functions (PSDF) of ground accelerations, compatible with a given design response spectrum is presented. The PSDF's are derived from the statistical analysis of the amplitudes of the frequency components in a set of artificially generated time-histories matching the given spectrum. A so obtained PSDF is then used in the stochastic analysis of a NPP Reactor Building. The main results of this analysis are compared with the ones obtained by deterministic methods

  14. Level 1 shutdown and low power operation of Mochovce NPP, Unit 1, Slovakia

    International Nuclear Information System (INIS)

    Halada, P.; Cillik, I.; Stojka, T.; Kuzma, M.; Prochaska, J.; Vrtik, L.

    2004-01-01

    The paper presents general approach, used methods and form of documentation of the results that have been applied within the shutdown and low power PSA (SPSA) study for Mochovce NPP, Unit 1, Slovakia. The SPSA project was realized by VUJE Trnava Inc., Slovakia in 2001-2002 years. The Level 1 SPSA study for Mochovce NPP Unit 1 covers internal events as well as internal (fires, floods and heavy load drop) and external (aircraft crash, extreme meteorological conditions, seismic event and influence of surrounding industry) hazards. Mochovce NPP consists of two operating units equipped with VVER 440/V213 reactors safety upgraded before construction finishing and operation start. 87 safety measures based on VVER 440 operational experience and international mission insights were implemented to enhance its operational and nuclear safety. The SPSA relates to full power PSA (FPSA) as a continuation of the effort to create a harmonized level 1 PSA model for all operational modes of the plant with the goal to use it for further purposes as follows: Real Time Risk Monitor, Maintenance Optimization, Technical Specifications Optimization, Living PSA. (author)

  15. Application of GO methodology in reliability analysis of offsite power supply of Daya Bay NPP

    International Nuclear Information System (INIS)

    Shen Zupei; Li Xiaodong; Huang Xiangrui

    2003-01-01

    The author applies the GO methodology to reliability analysis of the offsite power supply system of Daya Bay NPP. The direct quantitative calculation formulas of the stable reliability target of the system with shared signals and the dynamic calculation formulas of the state probability for the unit with two states are derived. The method to solve the fault event sets of the system is also presented and all the fault event sets of the outer power supply system and their failure probability are obtained. The resumption reliability of the offsite power supply system after the stability failure of the power net is also calculated. The result shows that the GO methodology is very simple and useful in the stable and dynamic reliability analysis of the repairable system

  16. Compex system for teaching and training operators for TPP and NPP power units

    International Nuclear Information System (INIS)

    Tsiptsyura, R.D.

    1985-01-01

    Requirements, taken as a principle for constructing the system for operator teaching and training (OTT), have been formulated on the basis of investigation of operators' work at TPP and NPP power units. Functional structure and a structural block-diagram for OTT are built. As a criterion, which determines the structure of any trainers, being a part of OTT a requirement has been chosen satisfying the correspondence beetween habits developed with the help of trainers and habits of real operators' work. Results of analysis permit to confirm that refusal or under statement of the role of any stage of operator training leads to reduction of quality of his training

  17. ???????????? ? ?????????? ??????? ??????? ?? ??????? ???????????? ? ?????? ???????-??-???? // Advantages and disadvantages of franchise business opportunities in Rostov-on-don

    OpenAIRE

    Bugayan, S.A.; Filimonenko, I.

    2013-01-01

    ? ?????? ??????????? ???????? ???????????? ? ?????????? ??????????? ??????? ?? ??????? ???????????? ? ?????? ???????-??-???? ?? ??????? ????????? ????, ????????????? ??????? ???? ????? ??????? ? ?? ?????????? ??????????? ????????. In this article are considered main cons and pros of franchise business opportunities in Rostov-on-Don, using different businesses as an example,efficiency of this type of business and its future possibilities.

  18. Application of linear scheduling method (LSM) for nuclear power plant (NPP) construction

    International Nuclear Information System (INIS)

    Kim, Woojoong; Ryu, Dongsoo; Jung, Youngsoo

    2014-01-01

    Highlights: • Mixed use of linear scheduling method with traditional CPM is suggested for NPP. • A methodology for selecting promising areas for LSM application is proposed. • A case-study is conducted to validate the proposed LSM selection methodology. • A case-study of reducing NPP construction duration by using LSM is introduced. - Abstract: According to a forecast, global energy demand is expected to increase by 56% from 2010 to 2040 (EIA, 2013). The nuclear power plant construction market is also growing with sharper competition. In nuclear power plant construction, scheduling is one of the most important functions due to its large size and complexity. Therefore, it is crucial to incorporate the ‘distinct characteristics of construction commodities and the complex characteristics of scheduling techniques’ (Jung and Woo, 2004) when selecting appropriate schedule control methods for nuclear power plant construction. However, among various types of construction scheduling techniques, the traditional critical path method (CPM) has been used most frequently in real-world practice. In this context, the purpose of this paper is to examine the viability and effectiveness of linear scheduling method (LSM) applications for specific areas in nuclear power plant construction. In order to identify the criteria for selecting scheduling techniques, the characteristics of CPM and LSM were compared and analyzed first through a literature review. Distinct characteristics of nuclear power plant construction were then explored by using a case project in order to develop a methodology to select effective areas of LSM application to nuclear power plant construction. Finally, promising areas for actual LSM application are suggested based on the proposed evaluation criteria and the case project. Findings and practical implications are discussed for further implementation

  19. Application of linear scheduling method (LSM) for nuclear power plant (NPP) construction

    Energy Technology Data Exchange (ETDEWEB)

    Kim, Woojoong, E-mail: minidung@nate.com [Central Research Institute, Korea Hydro and Nuclear Power Co., Ltd, Daejeon 305-343 (Korea, Republic of); Ryu, Dongsoo, E-mail: energyboy@khnp.co.kr [Central Research Institute, Korea Hydro and Nuclear Power Co., Ltd, Daejeon 305-343 (Korea, Republic of); Jung, Youngsoo, E-mail: yjung97@mju.ac.kr [College of Architecture, Myongji University, Yongin 449-728 (Korea, Republic of)

    2014-04-01

    Highlights: • Mixed use of linear scheduling method with traditional CPM is suggested for NPP. • A methodology for selecting promising areas for LSM application is proposed. • A case-study is conducted to validate the proposed LSM selection methodology. • A case-study of reducing NPP construction duration by using LSM is introduced. - Abstract: According to a forecast, global energy demand is expected to increase by 56% from 2010 to 2040 (EIA, 2013). The nuclear power plant construction market is also growing with sharper competition. In nuclear power plant construction, scheduling is one of the most important functions due to its large size and complexity. Therefore, it is crucial to incorporate the ‘distinct characteristics of construction commodities and the complex characteristics of scheduling techniques’ (Jung and Woo, 2004) when selecting appropriate schedule control methods for nuclear power plant construction. However, among various types of construction scheduling techniques, the traditional critical path method (CPM) has been used most frequently in real-world practice. In this context, the purpose of this paper is to examine the viability and effectiveness of linear scheduling method (LSM) applications for specific areas in nuclear power plant construction. In order to identify the criteria for selecting scheduling techniques, the characteristics of CPM and LSM were compared and analyzed first through a literature review. Distinct characteristics of nuclear power plant construction were then explored by using a case project in order to develop a methodology to select effective areas of LSM application to nuclear power plant construction. Finally, promising areas for actual LSM application are suggested based on the proposed evaluation criteria and the case project. Findings and practical implications are discussed for further implementation.

  20. Radioactive dispersion analysis for hypothetical nuclear power plant (NPP) candidate site in Perak state, Malaysia

    Science.gov (United States)

    Shamsuddin, Shazmeen Daniar; Basri, Nor Afifah; Omar, Nurlyana; Koh, Meng-Hock; Ramli, Ahmad Termizi; Saridan Wan Hassan, Wan Muhamad

    2017-10-01

    Malaysia is planning to build a nuclear power plant (NPP) by 2030 to diversify the national electricity supply and resources. Selection of an NPP site must consider various factors, especially nuclear safety consideration to fulfil the nuclear safety objectives. Environmental Risk Assessment Analysis is a part of safety requirements by the International Atomic Energy Agency (IAEA) prior to the NPP commissioning process. Risk Assessments Analysis (RIA) is compulsory for the NPP site evaluation. One of RIA methods are Radioactive Dispersion Analysis using probabilistic risk analysis software. It is also important to perform studies to estimate the impact to the neighbouring population in the case of a nuclear accident at the power plant. In the present work, aimed to study the impact of a hypothetical nuclear accident by simulating the dispersion pattern of radionuclides originated from a candidate site at Manjung, Perak. The work has been performed using the HotSpot Health Physics codes. Two types of radionuclides have been considered namely 137Cs and 131I. In calculations, the initial concentration of radioactive materials of Fukushima Daiichi accident data are used which are 2.06 x 1016 Bq and 1.68 x 1017 Bq respectively for the two radionuclides. The result shows that the dispersion distance obtained from both software are not the same. It shows that 137Cs and 131I can be dispersed as far as 16 km and 80 km away from the site during radiological accident respectively, reaching major towns in Perak. Using HOTSPOT, the estimated total effective dose equivalent (TEDE) for 137Cs and 131I at major towns in Perak such as Lumut and Sitiawan are 1.2 mSv and 9.9 mSv. As for Taiping, Ipoh, Kampar, and Teluk Intan the estimated TEDE is around 0.2 mSv and 1.6 mSv respectively. In conclusion, the dispersion can reach as far as 80 km from the site. However, estimated annual effective dose is not more than 1 mSv limit, which is considered acceptable in the point of view of

  1. Radioactive dispersion analysis for hypothetical nuclear power plant (NPP candidate site in Perak state, Malaysia

    Directory of Open Access Journals (Sweden)

    Shamsuddin Shazmeen Daniar

    2017-01-01

    Full Text Available Malaysia is planning to build a nuclear power plant (NPP by 2030 to diversify the national electricity supply and resources. Selection of an NPP site must consider various factors, especially nuclear safety consideration to fulfil the nuclear safety objectives. Environmental Risk Assessment Analysis is a part of safety requirements by the International Atomic Energy Agency (IAEA prior to the NPP commissioning process. Risk Assessments Analysis (RIA is compulsory for the NPP site evaluation. One of RIA methods are Radioactive Dispersion Analysis using probabilistic risk analysis software. It is also important to perform studies to estimate the impact to the neighbouring population in the case of a nuclear accident at the power plant. In the present work, aimed to study the impact of a hypothetical nuclear accident by simulating the dispersion pattern of radionuclides originated from a candidate site at Manjung, Perak. The work has been performed using the HotSpot Health Physics codes. Two types of radionuclides have been considered namely 137Cs and 131I. In calculations, the initial concentration of radioactive materials of Fukushima Daiichi accident data are used which are 2.06 x 1016 Bq and 1.68 x 1017 Bq respectively for the two radionuclides. The result shows that the dispersion distance obtained from both software are not the same. It shows that 137Cs and 131I can be dispersed as far as 16 km and 80 km away from the site during radiological accident respectively, reaching major towns in Perak. Using HOTSPOT, the estimated total effective dose equivalent (TEDE for 137Cs and 131I at major towns in Perak such as Lumut and Sitiawan are 1.2 mSv and 9.9 mSv. As for Taiping, Ipoh, Kampar, and Teluk Intan the estimated TEDE is around 0.2 mSv and 1.6 mSv respectively. In conclusion, the dispersion can reach as far as 80 km from the site. However, estimated annual effective dose is not more than 1 mSv limit, which is considered acceptable in the point

  2. Estimation of the future nuclear power research in Romania, based on the present Cernavoda NPP evolution

    International Nuclear Information System (INIS)

    Dumitrache, Ion

    2001-01-01

    For more than four decades, the electric power needs of Romania were evaluated on the basis of the State Plan for Economic Development. To identify the optimal solution, the 'least price per produced MWh' was practically the only criterion. Now, there is no convincing estimation of the future economic development and at least two additional criteria play a significant role, 'the safety in the supply of the needed electric power', and 'the need of limiting the environmental impact of electricity generation'. The analysis dedicated to evaluation of future electric power solutions must take into account several features of the present situation. There are no available internal funds to finance the construction of new generating units of the order of several hundreds of MW. Even the so-called 'refurbishing' of the existing thermal power plants is based on foreign loan. In the 2000 year, about 80 electricity generation units reached 30 years of operation, i.e., the design life. Other thermal power plants proved very modest performances during 15-20 years of operation. Consequently, the future of almost 100 generating units is either in shutdown + decommissioning or shutdown + modernization situation. The Government analyzed the situation and decided to continue the completion of the Cernavoda NPP. The Unit 2 will be commissioned in a couple of years, and there is a schedule of negotiations relating the future of the Unit 3. After almost five years of successful operation of the Unit 1, the collaboration between RDT Institutes and NPP has clear features. Based on the experience related to this collaboration and taking into account the evolution of the Cernavoda NPP, we estimated that five research domains have significant chances to obtain a stable (and, hopefully, consistent) financial support. 1. Nuclear Safety, in particular Accident Analysis. As the Government re-iterated the firm decision to meet the conditions required for European integration, most of the nuclear

  3. Estimation of the loss of Offsite power frequency for the probabilistic safety assessment of the Juragua NPP

    International Nuclear Information System (INIS)

    Vilaragut Llanes, J.J.; Valhuerdi Debesa, C.

    1996-01-01

    The loss offsite power is defined as the interruption of the preferred power supply to the essential and non essential switchgear buses necessitating or resulting in the use of emergency AC power supply. Because many safety system required for reactor core decay heat removal and containment heat removal depend on AC power, a loss of offsite power, if emergency power supply (diesel generators) fails, could be severe accidents The purpose of this work was to determine, for the Probabilistic Safety Assessment of the Juragua NPP, the causes, frequency and duration relationships of the loss of offsite power. A description is presented of the different factor that determine the occurrence of this event and the characteristics for the Juragua NPP

  4. On-the-job training and qualification of nuclear power plant personnel. OJT at the Loviisa NPP

    International Nuclear Information System (INIS)

    1996-01-01

    On-the-job training and qualification process of nuclear power plant personnel is described, including the following issues: educational system of technical studies in Finland; training methods at the Loviisa NPP; on-the-job training of control room operators,field operators, maintenance personnel, other groups of the plant; qualifying examinations for different jobs

  5. NPP life management (abstracts)

    International Nuclear Information System (INIS)

    Litvinskij, L.L.; Barbashev, S.V.

    2002-01-01

    Abstracts of the papers presented at the International conference of the Ukrainian Nuclear Society 'NPP Life Management'. The following problems are considered: modernization of the NPP; NPP life management; waste and spent nuclear fuel management; decommissioning issues; control systems (including radiation and ecological control systems); information and control systems; legal and regulatory framework. State nuclear regulatory control; PR in nuclear power; training of personnel; economics of nuclear power engineering

  6. System for remote routine monitoring of power equipment at TPP and NPP

    International Nuclear Information System (INIS)

    Kantsedalov, V.G.; Samojlenko, V.P.; Doroshenko, V.A.

    1988-01-01

    A system for remote routine monitoring of TPP and NPP pipeline metals is described. The principal functional unit of the system is the unit of remote routine methods and techniques for studying and monitoring the metal and properties. The system is equipped with 5 types of routine monitoring equipment: robots, remote aggregated complexes, periodical diagnostic monitors, other means of metal diagnostics (endoscopes, introscopes). All current information enters the unit for estimating and forecasting the service life of power unit, where it is compared with the standard indices of reliability, duravility and efficiency. The system considered permits to reduce significantly or minimize the scope of works on metal monitoring during overhauls, increase intermonitoring and interrepairing compaigns to 8 years

  7. Financial feasibility analysis on small medium reactor nuclear power plant (SMR NPP) project in Indonesia under uncertainty

    International Nuclear Information System (INIS)

    Nuryanti; Suparman; Mochamad Nasrullah; Elok Satiti Amitayani; Wiku Lulus Widodo

    2015-01-01

    NPP SMR is one alternative to overcome the Outside Java Bali region's dependence on diesel power plant. One crucial issue in the NPP project (including SMR) would be financing, associated with the capital-intensive nature of the project. In addition, the SMR NPP project also be vulnerable in occurrence of some uncertainties. Therefore, this study aimed to analyze the financial feasibility of SMR NPP project by accommodating the possibility of the uncertainties. The methodology used is probabilistic analysis which was performed by Monte Carlo technique. This technique simulates the relationship between the uncertainty variables with financial feasibility indicators. The results showed that in probabilistic approach, SMR NPP project is considered feasible on the 'most probable value' of electricity selling price of 15 cents/kWh, indicated by positive average value of NPV (US$ 135,324,004) and the average value of both of IRRs are bigger than MARR (IRR project = 10.65 %, IRR Equity = 14.29 %, while MARR = 10 %). The probability of rejection of the SMR project was about 20 %. The three main variables that are most influential in the project were: selling price of electricity, investment cost and inflation rate. (author)

  8. The nuclear power plant maintenance personnel reliability prediction (NPP/MPRP) effort at Oak Ridge National Laboratory

    International Nuclear Information System (INIS)

    Knee, H.E.; Haas, P.M.; Siegel, A.I.

    1982-01-01

    Human errors committed during maintenance activities are potentially a major contribution to the overall risk associated with the operation of a nuclear power plant (NPP). An NRC-sponsored program at Oak Ridge National Laboratory is attempting to develop a quantitative predictive technique to evaluate the contribution of maintenance errors to the overall NPP risk. The current work includes a survey of the requirements of potential users to ascertain the need for and content of the proposed quantitative model, plus an initial job/task analysis to determine the scope and applicability of various maintenance tasks. In addition, existing human reliability prediction models are being reviewed and assessed with respect to their applicability to NPP maintenance tasks. This paper discusses the status of the program and summarizes the results to date

  9. Development of Highly Survivable Power and Communication System for NPP Instruments under Severe Accident

    Energy Technology Data Exchange (ETDEWEB)

    Yoo, Seung J.; Gu, Beom W.; Nguyen, Duy T.; Choi, Bo H.; Rim, Chun T. [KAIST, Daejeon (Korea, Republic of); Lee, So I. [KHNP CRI, Daejeon (Korea, Republic of)

    2014-10-15

    According to the detail report from the Fukushima nuclear accident, the failure of conventional instruments is mainly due to the following reasons. 1) Insufficient backup battery capacity after the station black out (SBO) 2) The malfunction or damage of instruments due to the extremely harsh ambient condition after the severe accident 3) The cut-off of power and communication cable due to the physical shocks of hydrogen explosion after the severe accident Since the current equipment qualification (EQ) for the NPP instruments is based on the design basis accident such as loss of coolant accident (LOCA), conventional instruments, which are examined under EQ condition, cannot guarantee their normal operation during the severe accident. A 7m-long-distance wireless power transfer and a radio frequency (RF) communication were introduced with conventional wired system to increase a redundancy. A heat isolation box and a harness are adopted to provide a protection from the expected physical shocks such as missiles and drastic increase of ambient temperature and pressure. A detail design principle of the highly survivable power and communication system, which has 4 sub-systems of a DCRS wireless power transfer, a Zigbee wireless communication, a GFRP harness, and a passive type router with a fly back regulator, has been presented in this paper. Each sub-system has been designed to have a robust operation characteristic regardless of the estimated physical shocks after the severe accident.

  10. Studies of Effect Analysis of Electromagnetic Pulses (EMP) in Operating Nuclear Power Plants (NPP)

    Energy Technology Data Exchange (ETDEWEB)

    Ye, Song Hae; Ryu, Ho Sun; Kim, Min Yi; Lee, Eui Jong [KHNP, Daejeon (Korea, Republic of)

    2016-05-15

    The effect analysis of electromagnetic pulses (EMPs) has been studied for the past year by the Central Research Institute of Korea Hydro Nuclear Power Co. (KHNP) in order to better establish safety measures in operating nuclear power plants. What is an electromagnetic pulse (EMP)? As a general term for high-power electromagnetic radiation, it refers to strong electromagnetic pulses that destroy only electronic equipment devices in a short period without loss of life. The effect analysis of EMPs in operating NPPs and their corresponding safety measures in terms of selecting target devices against EMP impact have been examined in this paper. In general, domestic nuclear power plants do apply the design of fail-safe concepts. For example, if key instruments of a system fail because of EMPs, the control rods of a nuclear reactor are dropped automatically in order to maintain safe conditions of the NPP. Reactor cooling presents no problem because the diesel generator will adopt the analog starting circuit least affected by the electromagnetic waves.

  11. Development of Highly Survivable Power and Communication System for NPP Instruments under Severe Accident

    International Nuclear Information System (INIS)

    Yoo, Seung J.; Gu, Beom W.; Nguyen, Duy T.; Choi, Bo H.; Rim, Chun T.; Lee, So I.

    2014-01-01

    According to the detail report from the Fukushima nuclear accident, the failure of conventional instruments is mainly due to the following reasons. 1) Insufficient backup battery capacity after the station black out (SBO) 2) The malfunction or damage of instruments due to the extremely harsh ambient condition after the severe accident 3) The cut-off of power and communication cable due to the physical shocks of hydrogen explosion after the severe accident Since the current equipment qualification (EQ) for the NPP instruments is based on the design basis accident such as loss of coolant accident (LOCA), conventional instruments, which are examined under EQ condition, cannot guarantee their normal operation during the severe accident. A 7m-long-distance wireless power transfer and a radio frequency (RF) communication were introduced with conventional wired system to increase a redundancy. A heat isolation box and a harness are adopted to provide a protection from the expected physical shocks such as missiles and drastic increase of ambient temperature and pressure. A detail design principle of the highly survivable power and communication system, which has 4 sub-systems of a DCRS wireless power transfer, a Zigbee wireless communication, a GFRP harness, and a passive type router with a fly back regulator, has been presented in this paper. Each sub-system has been designed to have a robust operation characteristic regardless of the estimated physical shocks after the severe accident

  12. Belene NPP

    International Nuclear Information System (INIS)

    Tsvetanov, P.

    1990-01-01

    The book presents the main results of the studies of the Bulgarian Academy of Sciences (BAS) on the construction of a new nuclear power plant at Belene on the Danube river. The programme of the studies comprises five areas: the socio-economic and energy development and the necessity of the commissioning; a technical project and design level of the equipment (safety, radioactivity control, waste disposal and economic efficiency of the power plant); the seismic properties of the construction site; the corresponding risk and design features of the plant; the ecological impacts of the NPP and public opinion. The studies in the different areas have been carried out by independent teams, fully responsible for the formulated topical conclusions. The general opinion of the BAS voiced in the book is that the construction of Belene NPP is not sufficiently substantiated and is considered unacceptable. 94 refs., 53 fig., 56 tabs. (R.Ts.)

  13. Experience with high percent step load decrease from full power in NPP Krsko

    International Nuclear Information System (INIS)

    Vukovic, V.

    2000-01-01

    The control system of NPP Kriko, is designed to automatically control the reactor in the power range between 15 and 100 percent of rated power for the following designed transients; - 10 percent step change in load; 5 percent per minute loading and unloading; step full load decrease with the aid of automatically initiated and controlled steam dump. Because station operation below 15 percent of rated power is designed for a period of time during startup or standby conditions, automatic control below 15 percent is not provided. The steam dump accomplishes the following functional tasks: it permits the nuclear plants to accept a sudden 95 percent loss of load without incurring reactor trip; it removes stored energy and residual heat following a reactor trip and brings the plant to equilibrium no-load conditions without actuation of the steam generator safety valves; it permits control of the steam generator pressure at no-load conditions and permits a manually controlled cooldown of the plant. The first two functional tasks are controlled by Tavg. The third is controlled by steam pressure. Interlocks minimise any possibility of an inadvertent actuation of steam dump system. This paper discusses relationships between designed (described) characteristics of plant and the data which are obtained during startup and/or first ten years of operation. (author)

  14. Methodology and measures for preventing unacceptable flow-accelerated corrosion thinning of pipelines and equipment of NPP power generating units

    Science.gov (United States)

    Tomarov, G. V.; Shipkov, A. A.; Lovchev, V. N.; Gutsev, D. F.

    2016-10-01

    Problems of metal flow-accelerated corrosion (FAC) in the pipelines and equipment of the condensate- feeding and wet-steam paths of NPP power-generating units (PGU) are examined. Goals, objectives, and main principles of the methodology for the implementation of an integrated program of AO Concern Rosenergoatom for the prevention of unacceptable FAC thinning and for increasing operational flow-accelerated corrosion resistance of NPP EaP are worded (further the Program). A role is determined and potentialities are shown for the use of Russian software packages in the evaluation and prediction of FAC rate upon solving practical problems for the timely detection of unacceptable FAC thinning in the elements of pipelines and equipment (EaP) of the secondary circuit of NPP PGU. Information is given concerning the structure, properties, and functions of the software systems for plant personnel support in the monitoring and planning of the inservice inspection of FAC thinning elements of pipelines and equipment of the secondary circuit of NPP PGUs, which are created and implemented at some Russian NPPs equipped with VVER-1000, VVER-440, and BN-600 reactors. It is noted that one of the most important practical results of software packages for supporting NPP personnel concerning the issue of flow-accelerated corrosion consists in revealing elements under a hazard of intense local FAC thinning. Examples are given for successful practice at some Russian NPP concerning the use of software systems for supporting the personnel in early detection of secondary-circuit pipeline elements with FAC thinning close to an unacceptable level. Intermediate results of working on the Program are presented and new tasks set in 2012 as a part of the updated program are denoted. The prospects of the developed methods and tools in the scope of the Program measures at the stages of design and construction of NPP PGU are discussed. The main directions of the work on solving the problems of flow

  15. Safety requirement of the nuclear power plants, after TMI-2 accident and their possible implementation on Bushehr NPP

    International Nuclear Information System (INIS)

    Mirhabibi, N.; Tochai, M.T.M.; Ashrafi, A.; Farnoudi, E.

    1985-01-01

    Based on the lessons learned from the TMI-2 accident and other research and developments, many improvements have been required for the design, manufacturing and operation of nuclear power plants in recent years. These requirements have already been implemented to the plants in operation and considered as new safety requirements for new plants. In the present paper these requirements and their possible implementation on Bushehr NPP are discussed. (Author)

  16. Operation time extension for power units of the first generation NPP and the liability for potential damage

    International Nuclear Information System (INIS)

    Kovalevich, O.M.

    2000-01-01

    The problem on the operation time extension for the six operating NPP first generation power units is discussed. However it is not advisable to improve the safety of these power units up to the acceptable level, therefore there arises the contradiction between the operation time extension of these power units and potential damage for the population. The possibility of having the increased civilian-legal responsibility for potential harm and losses in case of an accident is proposed to be considered as a compensating measure. The measures for realization of this civilian-legal responsibility are described [ru

  17. Transposition of the SQUG methodology to the Belgian NPP(nuclear power station)

    International Nuclear Information System (INIS)

    Detroux, P.; Aelbrecht, D.; Naisse, J.C.; Greer, J.L.

    1991-01-01

    The units of a Belgian Nuclear PowerStation had to be seismically reassessed after ten years of operation because the seismic requirements were upgraded from 0.1g to 0.17g free field ground acceleration. Seismic requalification of the active equipment was a critical problem as the current classical methods were too conservative and their application would have lead to unacceptable replacement or reinforcement of a lot of equipment. The approach based on the use of past experience of seismic behavior of non nuclear equipment was chosen; this methodology was developed by the Seismic Qualification Utility Group (SQUG); a group of U.S. utilities and had to be transposed to the Belgian N.P.P. This transposition is described in this paper. It affects different aspects of the methodology. First, the impact of specific requests of the Safety Authorities on the elaboration of the Safe Shutdown Equipment List (SSEL) shall be examined. Then it is explained why the tedious work of specific relay screening was avoided by taking advantage of initial design features for both Instrumentation and Control (I and C) and Electrical power distribution system; the impact on the Electrical SSEL is also described. Afterwards, it is presented how it was possible to conduct a specific existing seismic qualification at 0.1 g free field ground acceleration. Finally, the resolution of specific important problems that arose from the application of the SQUG methodology, is presented such as the definition of the grade level and the conservatism of the classical Amplified Floor Spectra (criterion 1), the calculation of the nozzle loads on mechanical equipment connected to long unbraced piping and the transfer of these loads to the anchorage. (author)

  18. Two managerial grids in NPP

    International Nuclear Information System (INIS)

    Zhao Hui

    2012-01-01

    Today, the nuclear power corporation (NPC) enjoys the profit of LCEP (the low carbon economic policy). at the same time, they also enduring more and more pressure. For example, the partner competition or the NPP potential occupational risk . The efficient counterplot of risk is the self-ability cultivation. It is essential to research the NPP managerial flow. The nuclear power plant (NPP) unit is a carrier of the NPC enterprise management system, and has taken on a new look 'pull one portion then the whole moving'. The NPP has three systematical characters, the security responsibility center, the man-machine system and the input-output system. The manufacturing system and the enterprise management system are the great constituents of the NPP managerial flows. Means of systems analysis, we can find out the truth of the NPP running interface. In CHINA, there are many operating experiences near 20 years. It indicates that the NPP manufacturing system and the enterprise system are the roots of the nuclear power corporation, the core of the all NPP systems must be based on it. So the ability cultivation is the work core to NPP. It is reliably to ensure the NPP to be up against problems, for instance, the security duty, the costing control and the man-machine system running harmoniously. This paper introduces the NPP managerial flow and the present state of QNPC, also come up with a proposal to refer for the NPC development actions of collective measure, specialization, standardization, fine. (author)

  19. Analysis of Territorial Planning and Prospects for Further Development of Urban Districts and Settlements in Rostov Region

    OpenAIRE

    Ovchinnikova Natalia

    2017-01-01

    This article covers the problems of modern urban districts and settlements of the Rostov region with due regard to the organization of their territories. Prospects for the further development of the urban districts and settlements are defined based on the goals of the urban-planning activity. Short-term and mid-term trends of residential construction in the Rostov region are classified in terms of the improvement of town-planning documentation. It is concluded that the territorial planning or...

  20. Ways of TPP and NPP powerful steam turbine blade erosion decreasing in low flow rate regimes

    International Nuclear Information System (INIS)

    Khrabrov, P.V.; Khaimov, V.A.; Matveenko, V.A.

    1986-01-01

    A systematized approach to the problem of efficient cooling of flow passage and exhaust parts of TPP and NPP steam turbines and prevention of erosion wear of inlet and outlet edges of operating blades is presented. Methods for LP casing cooling and sources of erosion-hazard moisture as well as the main technological and design measures to decrease the erosion of blades are determined

  1. The comparative analysis of safety and economic competitiveness of the advanced high-power reactor projects of NPP

    International Nuclear Information System (INIS)

    Batyrbekov, G.A.; Makhanov, U.M.; Philimonova, R.A.; Kichutkina, E.G.

    2002-01-01

    The comparative analysis results of the safety and economic competitiveness of the seven advanced large sized reactors projects (900 MW and more) are submitted in that report: EPR, Frameatome France, Siemens Germany; EP-1000 Westinghouse, USA and Genesi Italy; Candu 9, Atomic Energy of Canada Ltd; System 80 +, ABB, USA; KNGR, group NSSS Engineering and Development, Korea Power Engineering Company, Inc; APWR, Electric Power company, Japan Atomic Power Company, Mitsubishi Heavy Industries, Westinghouse Electric; and WWER-1000 (V-392), Atomenergoproject/Gidropress Russian Federation. According to the economic competitiveness of listed compared power reactors the 14 criteria of safety have been accepted. These criteria: 1. Features of the barrier system of 'defence-in-depth'. 2. The self-security of a reactor under increase of power and reactivity of a reactor, decrease of the expense and phase transformations of the reactor core coolant (presence of negative feedbacks). 3. Presence of the reactor shutdown systems responding principles of a variety, independence and reservation. Presence of the passive means of initiation and operation of the emergency protection. 4. The emergency cooling of the core of reactor. A presence of the passive means of cooling. Presence of the water reservation for the water supply of the different safety systems. 5. The emergency electrical supply, its reliability and degree of reservation. 6. The prevention measures of the heavy accident with the melt core. The decrease of the heavy accident probability. 7. The account of the heavy accident under development of the levels of protection. 8. The protection levels of NPP, the technological criteria of efficiency of the each safety barriers and the limiting radiation criteria for the each level of protection , in particular for the design-basis and beyond-design-basis accidents. 9. The measures for reduction of the heavy accident consequences. The management by the beyond

  2. ANALYSIS OF THE INCIDENCE OF PROSTATE CANCER IN THE ROSTOV REGION FOR THE YEARS 2001–2016: SPATIOTEMPORAL STATISTICS

    Directory of Open Access Journals (Sweden)

    O. E. Arhipova

    2017-01-01

    Full Text Available Introduction. Oncological diseases is a serious medico-social problem of modern society. The article presents the analysis of prostate cancer morbidity with consideration of regional health level differences.Objective. To conduct spatial-temporal analysis of prostate cancer incidence in Rostov region; to identify areas with a statistically significant increase in the incidence of prostate cancer; to identify regional differences (environmental determinism in the development of cancer in the southern Federal district.Materials and methods. We’ve analysed incidence of prostate cancer in the Rostov region for the period of 2001-2016. The analysis has been performed using tools spatio-temporal statistics on software ArcGis 10 *.Results. Areas and cities of Rostov region with a statistically significant increase in prostate cancer incidence were identified. It has been shown that in the regions and cities of the Rostov region with a low level of medical-ecological safety had a statistically significant increase in prostate cancer incidenceConclusions. The results can serve as a basis for the directional analysis of factors causing increased risk of cancer and development on this basis strategies for monitoring and prevention of cancer diseases in the Rostov region.

  3. Experiences in the implementation of the Coaching project in the nuclear power plant of Laguna Verde (NPP-L V)

    International Nuclear Information System (INIS)

    Mendez M, H. I.

    2012-10-01

    This document has the purpose of to share acquired experiences during the implementation of the Coaching project focused the training of supervisors and directive personnel of the nuclear power plant of Laguna Verde (NPP-L V). Derived of the improvement areas identified by the supervisor organization of the nuclear power stations WANO (World Association Nuclear of Operators) and of the auto-evaluations realized by the expert personnel of the same power station that based on external experiences carried out through the Benchmarking (comparison with other power stations) they have reflected the necessity to activate a training process in Coaching with a practical focus toward the directive and supervisor personnel in the power station. By means of the observation of the personnel's acting so much in the control rooms like in different areas, three focus areas have been identified for the training in Coaching, these are the personnel's motivation, the organizational communication so much in vertical form as horizontal and the perception of confidence lack among directive, supervisors, operators and technicians. The plan focused in the abilities training of Coaching with practical sense was development, supported with an evaluation of 360 grades as tool of competitions development through a computer application e-Coaching. The use of application and Coaching following techniques facilitated the conformation of the practical focus, same that are of continuous use starting from the training of the supervisor and directive personnel. (Author)

  4. Real-time management (RTM) by cloud computing system dynamics (CCSD) for risk analysis of Fukushima nuclear power plant (NPP) accident

    International Nuclear Information System (INIS)

    Cho, Hyo Sung; Woo, Tae Ho; The Cyber Univ. of Korea, Seoul

    2017-01-01

    The earthquake and tsunami induced accident of nuclear power plant (NPP) in Fukushima disaster is investigated by the real-time management (RTM) method. This non-linear logic of the safety management is applied to enhance the methodological confidence in the NPP reliability. The case study of the earthquake is modeled for the fast reaction characteristics of the RTM. The system dynamics (SD) modeling simulations and cloud computing are applied for the RTM method where the real time simulation has the fast and effective communication for the accident remediation and prevention. Current tablet computing system can improve the safety standard of the NPP. Finally, the procedure of the cloud computing system dynamics (CCSD) modeling is constructed.

  5. Real-time management (RTM) by cloud computing system dynamics (CCSD) for risk analysis of Fukushima nuclear power plant (NPP) accident

    Energy Technology Data Exchange (ETDEWEB)

    Cho, Hyo Sung [Yonsei Univ., Wonju Gangwon-do (Korea, Republic of). Dept. of Radiation Convergence Engineering; Woo, Tae Ho [Yonsei Univ., Wonju Gangwon-do (Korea, Republic of). Dept. of Radiation Convergence Engineering; The Cyber Univ. of Korea, Seoul (Korea, Republic of). Dept. of Mechanical and Control Engineering

    2017-03-15

    The earthquake and tsunami induced accident of nuclear power plant (NPP) in Fukushima disaster is investigated by the real-time management (RTM) method. This non-linear logic of the safety management is applied to enhance the methodological confidence in the NPP reliability. The case study of the earthquake is modeled for the fast reaction characteristics of the RTM. The system dynamics (SD) modeling simulations and cloud computing are applied for the RTM method where the real time simulation has the fast and effective communication for the accident remediation and prevention. Current tablet computing system can improve the safety standard of the NPP. Finally, the procedure of the cloud computing system dynamics (CCSD) modeling is constructed.

  6. Some aspects of correction additions optimisation of water chemistry regime of Kozloduy NPP power units 3 and 4

    International Nuclear Information System (INIS)

    Topalova, I.

    2005-01-01

    Optimization of the water-chemistry regime is a major corrective measure for minimization of the corrosion processes of the nuclear power unit equipment. Research done in NPP Kozloduy III - IV power units concerning the migration of the corrosion products in the water of secondary circuit as well as the connection between corrosion processes and fluctuation in parameters of the applied water-chemistry regime are reported. Analysis of the dependences obtained lead to conclusions for optimization of the water chemistry regime of secondary circuit and minimization of the corrosion processes and improvement of corrosion condition of metal surfaces. The research is done for the circuit of each of the 8 turbines of the two power units for a period of 10 days. Data received is quantitatively representative /40-50 points/ for performing of analysis and reaching certain conclusions for the water chemistry regime and development of corrosion processes. Dependence of iron and copper concentration in the work medium on the pH, ammonia and hydrazine concentration as well as the dependence of pH on ammonia concentration in case of different quantity and composition of corrosion products on the different power units' equipment metal surfaces are shown. (author)

  7. Influence of the CVCS Modelling on Results of the Loss of Offsite Power (LOOP) Safety Analysis for NPP Krsko

    International Nuclear Information System (INIS)

    Bencik, V.; Bajs, T.; Debrecin, N.

    2006-01-01

    A Loss of Offsite Power (LOOP) transient scenario is based on a complete loss of non-emergency AC power that results in the loss of all power to the plant auxiliaries, i.e., the Reactor Coolant Pumps (RCPs), condensate pumps, etc. An actual LOOP event would cause a loss of all feedwater, a loss of forced Reactor Coolant System (RCS) flow and a reactor trip within less than 2 seconds as a result of either loss of power to the rod cluster assembly gripper coils or any RCS flow trips. For safety analysis purposes the LOOP event is conservatively modelled as a Loss of Normal Feedwater (LONF) transient with a subsequent loss of offsite power as a result of a reactor trip. The reactor trip followed by RCP trip are delayed until a low-low Steam Generator (SG) level signal is reached. This is a more conservative scenario than the LOOP event because the least amount of SG secondary side water mass available for heat removal and the increased amount of the stored energy in the primary circuit at the time of the loss of RCS flow result. The standard LOOP safety analysis is aimed to demonstrate the natural circulation capability of the RCS to remove residual and decay heat from the core aided by Auxiliary Feedwater in the secondary system. In addition to this goal the presented work is aimed to resolve the potential safety issue resulting from the influence of the Chemical and Volume Control System (CVCS) operation during LOOP event for NPP Krsko. The potential safety concern for the LOOP analysis is that the loss of instrument air system may occur thus leading to the CVCS charging and letdown flow imbalance. A net RCS inventory addition may result with water solid pressurizer condition. Water discharge through the pressurizer relief and safety valves could lead to overpressurization of the Pressurizer Relief Tank (PRT) and rupture of the PRT rupture disks. Additional concern is that pressurizer relief and safety valves may fail to properly reseat when exposed to water relief

  8. From Market Uncertainty to Policy Uncertainty for Investment in Power Generation: Real Options for NPP on Electricity Market

    International Nuclear Information System (INIS)

    Tomsic, Zeljko

    2014-01-01

    In the electricity sector, market participants must make decisions about capacity choice in a situation of radical uncertainty about future market conditions. Sector is normally characterised by non-storability and periodic and stochastic demand fluctuations. In these cases capacity determination is a decision for the long term, whereas production is adjusted in the short run. Capacities need to be installed well in advance (decision for investment even earlier because of long construction time and even longer in case of NPP to prepare all needed legal, financial and physical infrastructure), at times when firms face considerable demand and cost uncertainty when choosing their capacity. Paper looks on the main contributions in investment planning under uncertainty, in particular in the electricity market for capital intensive investments like NPP. The relationship between market and non-market factors (recent UK policy example) in determining investment signals in competitive electricity markets was analysed. Paper analyse the ability of competitive electricity markets to deliver the desired quantity and type of generation capacity and also investigates the variety of market imperfections operating in electricity generation and their impact on long-term dynamics for generation capacity, the most capital-intensive of the liberalised functions in the electricity supply industry. Paper analyses how price formation influences investment signals. Today, investment decisions are made by several operators that act independently. Number of factors (including market power, wholesale price volatility, lack of liquidity in the wholesale and financial market, policy and regulatory risks etc.) contribute to polluting the price signal and generating sub-optimal behaviour. Climate change policies can easily distort market signals, insulating renewables generation from market dynamics. This in turn reduces the proportion of the market that is effectively opened to competitive

  9. Computer-aided design system for a complex of problems on calculation and analysis of engineering and economical indexes of NPP power units

    International Nuclear Information System (INIS)

    Stepanov, V.I.; Koryagin, A.V.; Ruzankov, V.N.

    1988-01-01

    Computer-aided design system for a complex of problems concerning calculation and analysis of engineering and economical indices of NPP power units is described. In the system there are means for automated preparation and debugging of data base software complex, which realizes th plotted algorithm in the power unit control system. Besides, in the system there are devices for automated preparation and registration of technical documentation

  10. Annx IV. Delayed nuclear power plant project management experience Cernavoda 2 NPP, Romania

    International Nuclear Information System (INIS)

    2008-01-01

    The Cernavoda Unit 2 NPP work was originally started in 1982 with work coming to a halt in 1989, and a preservation program implemented in 1991 while work continued on Unit 1. In 1995 attention turned to the completion of Unit 2 and status verification reports were commissioned. Work proceeded, as funds were available, up until 2002 when an interim contract was signed. Subsequently a Contract Completion Effective Date (CCED) was signed in March 2003 with completion duration of 48 months. A project schedule is a necessity for any project whether it is a new build or a restart to a delayed project. There are 5 major elements that are included in all CANDU project schedules, Engineering, Procurement, Construction, Commissioning and the conversion from Construction to Commissioning. The Engineering schedule of deliverables was not fully defined at CCED. Design changes defined prior to CCED were not fully defined and the scope of work associated with these only became known during the actual construction program. A significant number of new design changes were introduced after CCED, which compounded the impact to the construction program. All projects require their budgets to be built up within a defined structure. Delayed projects are no different from other projects in that respect. The standard Work Brakout Structure (WBS), which is applicable to most CANDU projects, is equally applicable for a delayed project. On Cernavoda Unit 2 we used a Budget Breakdown Structure, which was a combination of a traditional WBS and an Organization Structure. This structure was adopted in order to have consistency with the structure, which had been used prior to the delay on the project and also it was a requirement of the three party agreements with funding from different sources and in different currencies. All major construction projects normally carry a contingency allowance for undefined work and a risk allowance for the possibility of major changes. Delayed projects require

  11. Temelin NPP commissioning experiences

    International Nuclear Information System (INIS)

    Hanus, V.

    2002-01-01

    The Building Permit for the Temelin NPP with four VVER units was issued in 1986, which is a long time ago. Since then, however, was taken a route that is very different from what anybody imagined. Described are the legislative and design changes and given is a current condition of the power plant

  12. The experience of strengthening subsidence of the soil under the existing building in the city of Rostov-on-Don

    Directory of Open Access Journals (Sweden)

    Prokopov Albert

    2017-01-01

    Full Text Available Described problem for multi-storey residential development in the city of Rostov-on-Don on collapsible soils. The analysis of the technical and technological peculiarities of solidification under conditions of maintained buildings. Examples of projects of consolidation subsidence of foundation soils of buildings in operation 50–70 years.

  13. Renovation of the 'old' NPP units as an economically effective way of nuclear power development

    International Nuclear Information System (INIS)

    Zrodnikov, A.V.; Toshinsky, G.I.; Komlev, O.G.; Dragunov, Yu.G.; Stepanov, V.S.; Klimov, N.N.; Kopytov, I.I.; Krushelnitsky, V.N.

    2005-01-01

    In the process of nuclear power development there comes a phase when the old' power-units, which reactor installations have expired the designed and extended service lifetime are withdrawn from operating. At this phase in the case of the same annual investments into nuclear power, the increase of the total set up capacity of the nuclear power will be terminated because introduction of capacities due to construction of 'new' power-units only compensates for the reduction of capacities caused by withdrawing from operating the 'old' power-units. Along with this, taking into account a sizeable difference in the service lifetime of the nuclear steam supplying systems and the rest infrastructure of the nuclear power plants, it is an opportunity to find the solution to the problem of compensating for the withdrawn capacities without considerable increasing the annual investments. This opportunity is connected with use of the innovative nuclear power technology based on multipurpose small power modular fast reactors with lead-bismuth coolant for replacement of the withdrawn capacities (renovation of power-units). The features of the innovative nuclear power technology based on the SVBR-76/100 reactor installations, the results of the technical and economical investigations that demonstrate the high economical efficiency of use of the renovation technology using the SVBR-75/100 reactor modules are presented in the Paper. (author)

  14. Dukovany NPP - Safely 16 TERA

    International Nuclear Information System (INIS)

    Vlcek, J.

    2008-01-01

    In this presentation increasing of power output of the Dukovany NPP is reviewed. To operate all Dukovany Units safely with the perspective of long-term operation (LTO) of 50 - 60 years it is proposed.

  15. Digital protection in power plants. Electrical unit and line protection. Digital protection systems for NPP

    International Nuclear Information System (INIS)

    Kaczmarek, A.

    2000-01-01

    In this presentation author deals with the digital protection systems for nuclear power plants. The evolution of protection devices, protection concept for power plants, concept of functional redundancy, references for digital protection, benefits for the customer well as concept fault recorder are presented. (author)

  16. European type NPP electric power and vent systems. For safety improvement and proposal of international center

    International Nuclear Information System (INIS)

    Sugiyama, Kenichiro

    2011-01-01

    For prevention of reactor accidents of nuclear power plants, multiplicity and redundancy of emergency power would be most important. At station blackout accident, European type manually operated vent operation could minimize release amount of radioactive materials and keep safety of neighboring residents. After Fukushima Daiichi accident, nuclear power plants could not restart operation even after completion of periodical inspection. This article introduced European type emergency power and vent systems in Swiss, Sweden and Germany with state of nuclear power phaseout for reference at considering to upgrade safety and accident mitigation measures for better understanding of the public. In addition, it would be important to recover trust of nuclear technology to continue to disseminate latest information on new knowledge of accident site and decontamination technologies to domestic and overseas people. As its implementation, establishment of Fukushima international center was proposed. (T. Tanaka)

  17. The Modernization Program and Power Up-rate at NPP V2 Jaslovske Bohunice, Slovak Republic

    International Nuclear Information System (INIS)

    Reznik, Vladivoj; Krajmer, Imrich

    2010-01-01

    Slovenske Elektrarne, a.s. is a second largest utility company in the Central and Eastern Europe that owns an optimal production portfolio comprised of nuclear, thermal and hydroelectric power plants. There are two nuclear power plants Bohunice and Mochovce both operate with two units and another two units Mochovce 3 and 4 are currently under construction. Electricity at Nuclear power plant Bohunice V2 is generated by two 440 MW units that had gradually been connected to the power network over the period between 1984 and 1985. In the construction of the nuclear power plant V2 the concept of pressurized water reactors was adopted and the Soviet-era design WWER 440 used. The upgrading of Nuclear Power Plant Bohunice V2 is based on three main points: Modernization, Power up-rate, and Ageing monitoring program. The main targets of the modernization project were: Increasing of the Nuclear Safety and of the Nuclear operational reliability, and Seismic improvement. This modernization program is in full compliance with IAEA requirements and with the decisions from the Nuclear Regulatory Agency of the Slovak Republic (UJD) and achievement of the probabilistic safety criteria in accordance with IAEA recommendations. Except that is ensured a safe, reliable, economical and effective electricity and heat generation. Achieved results are based for further prolongation of the operation life time up to 60 years. (authors)

  18. Development of Highly Reliable Power and Communication System for Essential Instruments Under Severe Accidents in NPP

    Directory of Open Access Journals (Sweden)

    Bo Hwan Choi

    2016-10-01

    Full Text Available This article proposes a highly reliable power and communication system that guarantees the protection of essential instruments in a nuclear power plant under a severe accident. Both power and communication lines are established with not only conventional wired channels, but also the proposed wireless channels for emergency reserve. An inductive power transfer system is selected due to its robust power transfer characteristics under high temperature, high pressure, and highly humid environments with a large amount of scattered debris after a severe accident. A thermal insulation box and a glass-fiber reinforced plastic box are proposed to protect the essential instruments, including vulnerable electronic circuits, from extremely high temperatures of up to 627°C and pressure of up to 5 bar. The proposed wireless power and communication system is experimentally verified by an inductive power transfer system prototype having a dipole coil structure and prototype Zigbee modules over a 7-m distance, where both the thermal insulation box and the glass-fiber reinforced plastic box are fabricated and tested using a high-temperature chamber. Moreover, an experiment on the effects of a high radiation environment on various electronic devices is conducted based on the radiation test having a maximum accumulated dose of 27 Mrad.

  19. Development of highly reliable power and communication system for essential instruments under severe accidents in NPP

    International Nuclear Information System (INIS)

    Choi, Bo Hwan; Jang, Gi Chan; Shin, Sung Min; Kang, Hyun Gook; Rim, Chun Taek; Lee, Soo Ill

    2016-01-01

    This article proposes a highly reliable power and communication system that guarantees the protection of essential instruments in a nuclear power plant under a severe accident. Both power and communication lines are established with not only conventional wired channels, but also the proposed wireless channels for emergency reserve. An inductive power transfer system is selected due to its robust power transfer characteristics under high temperature, high pressure, and highly humid environments with a large amount of scattered debris after a severe accident. A thermal insulation box and a glass-fiber reinforced plastic box are proposed to protect the essential instruments, including vulnerable electronic circuits, from extremely high temperatures of up to 627 .deg. C and pressure of up to 5 bar. The proposed wireless power and communication system is experimentally verified by an inductive power transfer system prototype having a dipole coil structure and prototype Zigbee modules over a 7-m distance, where both the thermal insulation box and the glass-fiber reinforced plastic box are fabricated and tested using a high-temperature chamber. Moreover, an experiment on the effects of a high radiation environment on various electronic devices is conducted based on the radiation test having a maximum accumulated dose of 27 Mrad

  20. Development of highly reliable power and communication system for essential instruments under severe accidents in NPP

    Energy Technology Data Exchange (ETDEWEB)

    Choi, Bo Hwan; Jang, Gi Chan; Shin, Sung Min; Kang, Hyun Gook; Rim, Chun Taek [Dept. of Nuclear and Quantum Engineering, Korea Advanced Institute of Science and Technology, Daejeon (Korea, Republic of); Lee, Soo Ill [I and C Group, Korea Hydro and Nuclear Power Co., Ltd, Central Research Institute, Daejeon (Korea, Republic of)

    2016-10-15

    This article proposes a highly reliable power and communication system that guarantees the protection of essential instruments in a nuclear power plant under a severe accident. Both power and communication lines are established with not only conventional wired channels, but also the proposed wireless channels for emergency reserve. An inductive power transfer system is selected due to its robust power transfer characteristics under high temperature, high pressure, and highly humid environments with a large amount of scattered debris after a severe accident. A thermal insulation box and a glass-fiber reinforced plastic box are proposed to protect the essential instruments, including vulnerable electronic circuits, from extremely high temperatures of up to 627 .deg. C and pressure of up to 5 bar. The proposed wireless power and communication system is experimentally verified by an inductive power transfer system prototype having a dipole coil structure and prototype Zigbee modules over a 7-m distance, where both the thermal insulation box and the glass-fiber reinforced plastic box are fabricated and tested using a high-temperature chamber. Moreover, an experiment on the effects of a high radiation environment on various electronic devices is conducted based on the radiation test having a maximum accumulated dose of 27 Mrad.

  1. NPP Prevlaka - Preparation of construction

    International Nuclear Information System (INIS)

    Bojic, K.

    1984-01-01

    On the basis of study 'Optimal electricity generation structure till the year 2000' production of 3 x 500 MWe in nuclear power plants has been anticipated. Second Croatian-Slovenian NPP project will be based on the same principles the first one (NPP Krsko) was based on. Preconstruction investigation studies are performed at site Prevlaka on river Sava downstream of Zagreb. Licensing procedure has started with republic Urban countryside planning activities. Preconstruction activities are planned to be finished by the end of 1986. while the construction is expected to start during 1987. Parallel to investigation studies for NPP Prevlaka, evaluation of nuclear technology and reactor type is planned to be made. (author)

  2. Seismic analysis of a NPP reactor building using spectrum-compatible power spectral density functions

    International Nuclear Information System (INIS)

    Venancio Filho, F.; Joia, L.A.

    1987-01-01

    A numerical methodology to obtain Power Spectral Density Functions (PSDF) of ground accelerations, compatible with a given design response spectrum is presented. The PSDF's are derived from the statistical analysis of the amplitudes of the frequency components in a set of artificially generated time-histories matching the given spectrum. A so obtained PSDF is then used in the stochastic analysis of a reactor building. The main results of this analysis are compared with the ones obtained by deterministic methods. (orig./HP)

  3. Social and psychological problems of nuclear power: perception of NPP construction and environmental risk

    International Nuclear Information System (INIS)

    Malenchenko, A.F.; Sushko, S.N.; Saltanova, I.V.; Tushin, N.N.; Kozlovskaya, A.V.; Bortnovskij, V.N.; Dorofeeva, S.M.; Gapanovich-Kajdalov, N.V.; Gapanovich-Kajdalova, E.V.

    2013-01-01

    The paper presents the analysis of questioning about perception of nuclear power plant construction in Belarus and about concomitant environmental risk. The opinion poll has been conducted among students of: Department of Environmental Monitoring of the International A. Sakharov Environmental University, Physics Department of Belarus State University, Department of General Hygienic and Environmental Medicine of Gomel State Medical University, Faculty of Mechanical Engineering of Minsk Polytechnic College. (authors)

  4. A Study on UAE Cultural Effects on Nuclear Power Plant (NPP) Operation

    International Nuclear Information System (INIS)

    Jang, In Seok; Seong, Poong Hyun; Kang, Hyun Gook

    2012-01-01

    Several initiatives have recently been taken to provide international cooperation in technology transfer and supplying human factors resources to the nuclear industry worldwide. The aim of promoting international cooperation is for the safe operation of the nuclear power industry. In terms of international cooperation of the nuclear industry, nuclear power plants are now under construction in Braka, UAE. However, with technology transfer and international cooperation, there needs to consider several potential problems due to the differences between two culture of the countries such as language, technical culture and expectation. Also, there is an evidence of remarkably wide effects of cultural interpretation of human-system interface even between what have been thought of as relatively homogeneous. Hence, the purpose of this research is to draw attention to the degree to which culture, organizational, and even ergonomic differences have to overcome, if such transfer of knowledge and behavioral technology is to be successful. Of particular interest is the UAE's cultural effect on operating nuclear power plants

  5. Risk analysis of NPP in multi-unit site for configuration of AAC power source

    International Nuclear Information System (INIS)

    Kim, Myung Ki

    2000-01-01

    Because of the difficulties in finding new sites for nuclear power plants, more units are being added to the existing sites. In these multi-unit sites, appropriate countermeasures should be established to cope with the potential station blackout (SBO) accident. Currently, installation of additional diesel generator (DG) is considered to ensure an alternative AC power source, but it has not been decided yet how many DGs should be installed in a multi-unit site. In this paper, risk informed decision making method, which evaluates reliability of electrical system, core damage frequency, and site average core damage frequency, is introduced to draw up the suitable number of DG in multi-unit site. The analysis results show that installing two DGs lowered the site average core damage frequency by 1.4% compared to one DG in six unit site. In the light of risk-informed decisions in regulatory guide 1.174, there is no difference of safety between two alternatives. It is concluded that one emergency diesel generator sufficiently guarantees safety against station blackout of nuclear power plants in multi-unit site. (author)

  6. A Study on UAE Cultural Effects on Nuclear Power Plant (NPP) Operation

    Energy Technology Data Exchange (ETDEWEB)

    Jang, In Seok; Seong, Poong Hyun; Kang, Hyun Gook [Korea Advanced Institute of Science and Technology, Daejeon (Korea, Republic of)

    2012-05-15

    Several initiatives have recently been taken to provide international cooperation in technology transfer and supplying human factors resources to the nuclear industry worldwide. The aim of promoting international cooperation is for the safe operation of the nuclear power industry. In terms of international cooperation of the nuclear industry, nuclear power plants are now under construction in Braka, UAE. However, with technology transfer and international cooperation, there needs to consider several potential problems due to the differences between two culture of the countries such as language, technical culture and expectation. Also, there is an evidence of remarkably wide effects of cultural interpretation of human-system interface even between what have been thought of as relatively homogeneous. Hence, the purpose of this research is to draw attention to the degree to which culture, organizational, and even ergonomic differences have to overcome, if such transfer of knowledge and behavioral technology is to be successful. Of particular interest is the UAE's cultural effect on operating nuclear power plants

  7. Dukovany NPP operation

    International Nuclear Information System (INIS)

    Vlcek, Jaroslav

    2010-01-01

    The topics discussed include: Dukovany NPP among CEZ Group power plants; International missions at the plant; Plant operation results; and Strategic goals and challenges. Historical data are presented in the graphical form, such as the unit capacity factor, unplanned capability loss factor, unplanned automatic scrams, fuel reliability, industrial safety accident rate, collective radiation exposure, WANO index, power generation data, and maximum achievable power by the end of year. Also discussed were the company culture and human resources, maintenance, power uprate, and related phenomena. (P.A.)

  8. NPP Krsko decommissioning concept

    International Nuclear Information System (INIS)

    Novsak, M.; Fink, K.; Spiler, J.

    1996-01-01

    At the end of the operational lifetime of a nuclear power plant (NPP) it is necessary to take measures for the decommissioning as stated in different international regulations and also in the national Slovenian law. Based on these requirements Slovenian authorities requested the development of a site specific decommissioning plan for the NPP KRSKO. In September 1995, the Nuklearna Elektrarna Krsko (NEK) developed a site specific scope and content for decommissioning plan including the assumptions for determination of the decommissioning costs. The NEK Decommissioning Plan contains sufficient information to fulfill decommissioning requirements identified by NRC, IAEA and OECD - NEA regulations. In this paper the activities and the results of development of NEK Decommissioning Plan consisting of the development of three decommissioning strategies for the NPP Krsko and selection of the most suitable strategy based on site specific, social, technical, radiological and economical aspects, cost estimates for the strategies including the costs for construction of final disposal facilities for fuel/high level waste (fuel/HLW) and low/intermediate level waste (LLW/ILW) and scheduling all activities necessary for the decommissioning of the NPP KRSKO are presented. (author)

  9. NPP Krsko decommissioning concept

    International Nuclear Information System (INIS)

    Novsak, M.; Fink, K.; Spiler, J.

    1996-01-01

    At the end of the operational lifetime of a nuclear power plant (NPP) it is necessary to take measures for the decommissioning as stated in different international regulations and also in the national Slovenian law. Based on these requirements Slovenian authorities requested the development of a site specific decommissioning plan for the NPP Krsko. In September 1995, the Nuklearna Elektrarna Krsko (NEK) developed a site specific scope and content for a decommissioning plan including the assumptions for determination of the decommissioning costs. The NEK Decommissioning Plan contains sufficient information to fulfill the decommissioning requirements identified by NRC, IAEA and OECD - NEA regulations. In this paper the activities and results of development of NEK Decommissioning Plan consisting of the development of three decommissioning strategies for the NPP Krsko and selection of the most suitable strategy based on site specific, social, technical, radiological and economic aspects, cost estimates for the strategies including the costs for construction of final disposal facilities for fuel/high level waste (fuel/HLW) and low/intermediate level waste (LLW/ILW) and scheduling of all activities necessary for the decommissioning of the NPP Krsko are presented. (author)

  10. Post-reconstruction full power and shut down level 2 PSA study for Unit 1 of Bohunice V1 NPP

    International Nuclear Information System (INIS)

    Kovacs, Z.

    2003-01-01

    The level 2 PSA model of the J. Bohunice V1 NPP was developed in the RISK SPECTRUM Professional code with the following objectives: to identify the ways in which radioactive releases from the plant can occur following the core damage; to calculate the magnitudes and frequency of the release; to provide insights into the plant behaviour during a severe accident; to provide a framework for understanding containment failure modes; the impact of the phenomena that could occur during and following core damage and have the potential to challenge the integrity of the confinement; to support the severe accident management and development of SAMGs. The magnitudes of release categories are calculated using: the MAAP4/VVER for reactor operation and shutdown mode with closed reactor vessel and the MELCOR code for shutdown mode with open reactor vessel. In this paper an overview of the Level 2 PSA methodology; description of the confinement; the interface between the level 1 and 2 PSA and accident progression analyses are presented. An evaluation of the confinement failure modes and construction of the confinement event trees as well as definition of release categories, source term analysis and sensitivity analyses are also discussed. The presented results indicate that: 1)for the full power operation - there is an 25% probability that the confinement will successfully maintain its integrity and prevent an uncontrolled fission product release; the most likely mode of release from the confinement is a confinement bypass after SGTM with conditional probability of 30%; the conditional probability for the confinement isolation failure probability without spray is 5%, for early confinement failure at the vessel failure is 4%, for other categories 1% or less; 2) for the shutdown operating modes - the shutdown risk is high for the open reactor vessel and open confinement; important severe accident sequences exists for release categories: RC5.1, RC5.2 and RC6.2

  11. Thermohydraulic investigations of nuclear power facilities (to the 60-th anniversary of the First NPP start)

    International Nuclear Information System (INIS)

    Rachkov, V.I.; Efanov, A.D.; Zhukov, A.V.; Kalyakin, S.G.; Sorokin, A.P.

    2014-01-01

    The investigations conducting in SSC RF - IPPE are aimed to develop theory and create calculational programs which allow to obtain the detailed description of coolant velocity fields and temperatures in any channels and equipment units of nuclear power facilities. Specially developed sensors for measuring various parameters are used in the experiments. Mathematical models and numerical methods are generalized for description and numerical solution of compressible fluids, multiphase and multifluid systems. The programs which allow to determine hydrodynamic and thermotechnical characteristics with account for melting, solidification, boiling processes are established. The obtained data is the base for creating the two-phase media flow theory. The study of the processes of impurity formation, transport and precipitation in liquid metal coolants has been allowed to develop the methods of impurity mass transfer simulation in circuits. For solving the fast reactor safety problem the series of investigations on liquid metals physics, boiling and condensation have been carried out [ru

  12. The application of gamma-spectrometry to nuclear power plant (NPP) and environment

    International Nuclear Information System (INIS)

    Asgharizadeh, Farid.

    1995-01-01

    One of measuring systems is nuclear spectrometry, particularly Gamma-Ray Spectrometry, to measure and determine the radionuclide concentration within plant materials and environmental samples. There are four major applied techniques related to Nuclear Power Plant operation and environmental monitoring aspects. Some details about gamma ray spectrometry technique is discussed in chapter 2. The main emphasis is on the calculation of gamma-ray detector efficiency for different geometries, the minimum detectable activity concepts and dead-time correction. Also,some formula and relations are introduced. In chapter 3, the major applications of gamma-ray spectrometry for analysis of nuclear power plant and environmental samples are discussed. These applications are divided into four topics: Nuclear Fuel survey; based on the activity of fission products concentration in reactor coolant, two other applications are introduced: Fuel Burnup calculation and the calculation of rated activity of natural radionuclides in construction of materials which is the last and most important application: Measurement and determination of radionuclides activity concentr[[[[n in environmental samples is described through section 3.3 Sampling and measuring methods for research and monitoring aspects is evaluated. Some data about sample preparation methods such as pretreatment and solubilization procedures are presented. Quantitative chemical separations of trace constituents from complex sample materials invariably require meticulous work by an analytical chemist. The radiochemical separation deals with this subject. Instrumental aspects, relate to gamma-ray spectrometry, quality assurance, presentation and reporting of results are described. In the experimental part, determination of radionuclides concentration in sediment sample is presented

  13. The Upper Miocene of the Rostov Dome (Eastern Paratethys: Implication of the chronostratigraphy and bivalvia-based biostratigraphy

    Directory of Open Access Journals (Sweden)

    Ruban Dmitry A.

    2005-01-01

    Full Text Available The Rostov Dome is located in the south of the Russian Platform. In the Late Miocene this area was embraced by the Eastern Paratethys. The implications of a recently developed Neogene chronostratigraphy to the studied area are discussed. The Sarmatian regional stage corresponds to the upper part of the Langhian, the entire Serravalian and the lower part of the Tortonian global stages; the Maeotian regional stage corresponds to the upper part of the Tortonian and the lowermost horizons of the Messinian global stages; the Pontian regional stage corresponds to most of the Messinian and the lowermost Zanclean global stages. A first Bivalvia-based bio-stratigraphic framework is proposed for the territory of the Rostov Dome. Five biozones were established within the Serravalian-Messinian: Tapes vitalianus, Cerastoderma fittoni-Cerastoderma subfittoni, Congeria panticapaea, Congeria amygdaloides navicula and Monodacna pseudocatillus-Prosodacna schirvanica.

  14. Operation Aspect of the Main Control Room of NPP

    International Nuclear Information System (INIS)

    Sahala M Lumbanraja

    2009-01-01

    The main control room of Nuclear Power Plant (NPP) is operational centre to control all of the operation activity of NPP. NPP must be operated carefully and safely. Many aspect that contributed to operation of NPP, such as man power whose operated, technology type used, ergonomic of main control room, operational management, etc. The disturbances of communication in control room must be anticipated so the high availability of NPP can be achieved. The ergonomic of the NPP control room that will be used in Indonesia must be designed suitable to anthropometric of Indonesia society. (author)

  15. On the prohibition of automatic redundant power supply of 6 and 0.4 kV auxiliary sections at Leningrad NPP

    International Nuclear Information System (INIS)

    Mokeev, S.F.

    1987-01-01

    At Leningrad NPP the automatic switching on of the auxiliary power supply sources of 6 and 0.4 kV is prohibited to provide personnel safety and preserve destruction of electroequipment. With excess of current maximum value in the 6 kV section immediate detachment of all electric motors occurs. At that moment by the switchers detechment emergency signal it occurs immediate swithing on of auxiliary systems or emergency switching on of auxiliary supply of the main circulating pumps, that insreases abruptly operation reliability of plant technological department

  16. Improving the Assessment of Regional Economic Potential (on Example of Rostov Region

    Directory of Open Access Journals (Sweden)

    Nikolai A. Kurianov

    2017-06-01

    Full Text Available The article discusses a number of problematic issues concerning the possibility of improving existing approaches to assessing regional economic potential. Based on the analysis of existing approaches it is concluded that presence of a number of inherent common disadvantages, which include the exclusion of complex assessment elements of intangible resources, isolation from development goals in the region, ignoring the possibility of incremental reserves development static evaluation results. To overcome these ambiguities the authors' approach to improving assessment procedures based on the allocation of the essential nature of the category «regional economic potential», which unites, on the one hand, the resources available for regional development (actual potential, and on the other hand, resources in respect of which the region has the opportunity to attract them as a tool for further development of (stochastic potential. As the degree of implementation of this option is determined by the quality of regional governance, the most important element of the economic potential of the region is also an effective mechanism for management of existing and potential resources of various types. The practical implementation of the proposed methodology suppose, for example, estimate the economic potential of the Rostov region. At the first stage of the evaluation determine the most important elements of this potential and their ranking, on the second – assessment of the status of these elements from the point of view of their availability, ability to attract and management efficiency, and the third – the normalized assessment of regional economic potential.

  17. [Phylogenetic analysis of genomes of Vibrio cholerae strains isolated on the territory of Rostov region].

    Science.gov (United States)

    Kuleshov, K V; Markelov, M L; Dedkov, V G; Vodop'ianov, A S; Kermanov, A V; Pisanov, R V; Kruglikov, V D; Mazrukho, A B; Maleev, V V; Shipulin, G A

    2013-01-01

    Determination of origin of 2 Vibrio cholerae strains isolated on the territory of Rostov region by using full genome sequencing data. Toxigenic strain 2011 EL- 301 V. cholerae 01 El Tor Inaba No. 301 (ctxAB+, tcpA+) and nontoxigenic strain V. cholerae O1 Ogawa P- 18785 (ctxAB-, tcpA+) were studied. Sequencing was carried out on the MiSeq platform. Phylogenetic analysis of the genomes obtained was carried out based on comparison of conservative part of the studied and 54 previously sequenced genomes. 2011EL-301 strain genome was presented by 164 contigs with an average coverage of 100, N50 parameter was 132 kb, for strain P- 18785 - 159 contigs with a coverage of69, N50 - 83 kb. The contigs obtained for strain 2011 EL-301 were deposited in DDBJ/EMBL/GenBank databases with access code AJFN02000000, for strain P-18785 - ANHS00000000. 716 protein-coding orthologous genes were detected. Based on phylogenetic analysis strain P- 18785 belongs to PG-1 subgroup (a group of predecessor strains of the 7th pandemic). Strain 2011EL-301 belongs to groups of strains of the 7th pandemic and is included into the cluster with later isolates that are associated with cases of cholera in South Africa and cases of import of cholera to the USA from Pakistan. The data obtained allows to establish phylogenetic connections with V cholerae strains isolated earlier.

  18. Statistical Study of Corruption in the Region (on the Example of the Rostov Region

    Directory of Open Access Journals (Sweden)

    Kirill A. Belokrylov

    2016-09-01

    Full Text Available The paper proves the effectiveness of the using of statistical methods for evaluation of the corruption level as a result of its, on the one hand, latency, concealment of official statistical accounting, and on the other - the scale of corruption in Russia. The comparative analysis of the substantial characteristics of the nature of corruption by Russian and foreign scientists, as well as their reflection in the law has allowed to develop a questionnaire to adequately assess the levels, causes and the effectiveness of implementation of the policy on the fight against corruption as the most important social indicator of inefficient institutions. Analysis of the results of the economic and sociological survey of the population of the Rostov region revealed a shift of corruption performance in the region in the direction of the education system as a result of the dominance in the selection of students, but it led to the conclusion about the need to tighten legislation on the fight against corruption (72% of respondents, including the confiscation of the property (79,1%, the dismissal of corrupt officials, the ban on public office. The necessity of further in-depth statistical studies of corruption on the development of more effective measures is improved to combat it as a tool for removal of the Russian economy from the crisis and ensure that it is more sustainable growth than projected in the 2020s (the lost decade 1,5% positive GDP dynamics.

  19. Constructive approaches to the space NPP designing

    International Nuclear Information System (INIS)

    Eremin, A.G.; Korobkov, L.S.; Matveev, A.V.; Trukhanov, Yu.L.; Pyshko, A.P.

    2000-01-01

    An example of designing a space NPP intended for power supply of telecommunication satellite is considered. It is shown that the designing approach based on the introduction of a leading criterion and dividing the design problems in two independent groups (reactor with radiation shield and equipment module) permits to develop the optimal design of a space NPP [ru

  20. Radioactive wastes management of NPP

    International Nuclear Information System (INIS)

    Klyuchnikov, A.A.; Pazukhin, Eh.M.; Shigera, Yu. M.; Shigera, V.Yu.

    2005-01-01

    Modern knowledge in the field of radiation waste management on example of the most serious man-made accident at Chernobyl NPP are illuminated. This nuclear power plant that after accident in 1986 became in definite aspect an experimental scientific ground, includes all variety of problems which have to be solved by NPP personnel and specialists from scientific organizations. This book is aimed for large sphere of readers. It will be useful for students, engineers, specialists and those working in the field of nuclear power, ionizing source and radiation technology use for acquiring modern experience in nuclear material management

  1. NPP Krsko secondary side analysis

    International Nuclear Information System (INIS)

    Fabijan, Lj.

    1987-01-01

    The purpose of this work is to analyze secondary side thermohydraulics response on steam generator tube plugging in order to ensure nominal NPP power. We had established that the additional opening of the governing valve No. 3 and 4 can compensate pressure drop caused by steam generator tube plugging. Two main steam flows with four governing valves were simulated. Steam expansion in turbine and feed water system was modeled separately. All important process point and steam moisture changes impact on nominal NPP power were analysed. (author)

  2. DEVELOPMENT OF A MULTIPLE-LOCUS VARIABLE NUMBER OF TANDEM REPEAT ANALYSIS (MLVA FOR HELICOBACTER PYLORI AND ITS APPLICATION TO HELICOBACTER PYLORI ISOLATES FROM ROSTOV REGION,RUSSIA

    Directory of Open Access Journals (Sweden)

    Sorokin VM

    2012-09-01

    Full Text Available Stomach infection with Helicobacter pylori (H. pylori is the second most common infectious disease of humans. The severe pathological consequences of this infection include gastric and duodenal ulcer disease, the development of gastric mucosal atrophy, gastric carcinoma, and, more rarely, malignant tumors of the lymphoma. H. pylori infections cause very high morbidity and mortality and are of particular concern in developing countries, where H. pylori prevalences as high as 90% have been reported. The population of H. pylori shows a high genomic variability among isolates. And the polymorphism of repeat-units of genomics had participated the important process of evolution. A variety of molecular typing tools have been developed to access genetic relatedness in H. pylori isolates. However, there is still no standard genotyping system of this bacterium. The MLVA (Multi-Locus of Variable number of tandem repeat Analysis method is useful for performing phylogenetic analysis and is widely used in bacteria genotyping; however, there's little application in H. pylori analysis. This article is the first application of the MLVA method to investigate H. pylori isolates in Russia. MLVA of 4 VNTR loci with high discrimination power based on 10 candidates were performed on a collection of 22 strains of H. pylori which originated from Rostov region of Russia. This method provides a starting point on which improvements to the method and comparisons to other techniques can be made.

  3. NPP financial and regulatory risks-Importance of a balanced and comprehensive nuclear law for a newcomer country considering nuclear power programme

    Science.gov (United States)

    Manan, J. A. N. Abd; Mostafa, N. A.; Salim, M. F.

    2015-04-01

    The nature of Nuclear Power Plant (NPP) projects are: long duration (10-15 years for new build), high capital investment, reasonable risks and highly regulated industries to meet national & international requirement on Safety, Security, Safeguards (3S) and Liabilities. It requires long term planning and commitment from siting to final disposal of waste/spent fuel. Potential financial and regulatory risks are common in massive NPP projects and will be magnified in the case of using unproven technology. If the risks are not properly managed, it can lead to high project and operation costs, and, fail to fulfil its objectives to provide compatible electricity prices and. energy security. To ensure successful, the government and investors need to ensure that the NPP project is bankable with low cost of project and funding, have fair treatment and proper risk mitigation, and able to complete on time with no cost overrun. One of the requirements as prerequisite for the development of NPP as stipulated by the International Atomic Energy Agency (IAEA) is the establishment of a Legal and Regulatory Framework. The main objective of nuclear law is to ensure that the activities and projects carried-out in the country are legal and compliant to national and international requirements. The law should also be able to provide fair treatment of risks on its activities that is acceptable to investors. The challenge for a newcomer country is to develop a balanced and comprehensive national nuclear law that meet these objectives while taking into consideration various stakeholders' interest without compromising on safety, security, safeguard, liability requirements and other international obligations. This paper highlights the nature of NPP projects, its potential and associated financial and regulatory risks, and its major concerns and challenges. It proposes possible risks treatment and mitigation through the formulation of a balanced and comprehensive legislation by clear

  4. NPP financial and regulatory risks-Importance of a balanced and comprehensive nuclear law for a newcomer country considering nuclear power programme

    International Nuclear Information System (INIS)

    Manan, J. A. N. Abd; Mostafa, N. A.; Salim, M. F.

    2015-01-01

    The nature of Nuclear Power Plant (NPP) projects are: long duration (10-15 years for new build), high capital investment, reasonable risks and highly regulated industries to meet national and international requirement on Safety, Security, Safeguards (3S) and Liabilities. It requires long term planning and commitment from siting to final disposal of waste/spent fuel. Potential financial and regulatory risks are common in massive NPP projects and will be magnified in the case of using unproven technology. If the risks are not properly managed, it can lead to high project and operation costs, and, fail to fulfil its objectives to provide compatible electricity prices and. energy security. To ensure successful, the government and investors need to ensure that the NPP project is bankable with low cost of project and funding, have fair treatment and proper risk mitigation, and able to complete on time with no cost overrun. One of the requirements as prerequisite for the development of NPP as stipulated by the International Atomic Energy Agency (IAEA) is the establishment of a Legal and Regulatory Framework. The main objective of nuclear law is to ensure that the activities and projects carried-out in the country are legal and compliant to national and international requirements. The law should also be able to provide fair treatment of risks on its activities that is acceptable to investors. The challenge for a newcomer country is to develop a balanced and comprehensive national nuclear law that meet these objectives while taking into consideration various stakeholders’ interest without compromising on safety, security, safeguard, liability requirements and other international obligations. This paper highlights the nature of NPP projects, its potential and associated financial and regulatory risks, and its major concerns and challenges. It proposes possible risks treatment and mitigation through the formulation of a balanced and comprehensive legislation by clear

  5. NPP financial and regulatory risks-Importance of a balanced and comprehensive nuclear law for a newcomer country considering nuclear power programme

    Energy Technology Data Exchange (ETDEWEB)

    Manan, J. A. N. Abd, E-mail: jamalan@tnb.com.my; Mostafa, N. A.; Salim, M. F. [Nuclear Energy Department, Planning Division, Tenaga Nasional Berhad Level 32, Dua Sentral, No. 8 Jalan Tun Sambanthan, 50470 Brickfields, Kuala Lumpur (Malaysia)

    2015-04-29

    The nature of Nuclear Power Plant (NPP) projects are: long duration (10-15 years for new build), high capital investment, reasonable risks and highly regulated industries to meet national and international requirement on Safety, Security, Safeguards (3S) and Liabilities. It requires long term planning and commitment from siting to final disposal of waste/spent fuel. Potential financial and regulatory risks are common in massive NPP projects and will be magnified in the case of using unproven technology. If the risks are not properly managed, it can lead to high project and operation costs, and, fail to fulfil its objectives to provide compatible electricity prices and. energy security. To ensure successful, the government and investors need to ensure that the NPP project is bankable with low cost of project and funding, have fair treatment and proper risk mitigation, and able to complete on time with no cost overrun. One of the requirements as prerequisite for the development of NPP as stipulated by the International Atomic Energy Agency (IAEA) is the establishment of a Legal and Regulatory Framework. The main objective of nuclear law is to ensure that the activities and projects carried-out in the country are legal and compliant to national and international requirements. The law should also be able to provide fair treatment of risks on its activities that is acceptable to investors. The challenge for a newcomer country is to develop a balanced and comprehensive national nuclear law that meet these objectives while taking into consideration various stakeholders’ interest without compromising on safety, security, safeguard, liability requirements and other international obligations. This paper highlights the nature of NPP projects, its potential and associated financial and regulatory risks, and its major concerns and challenges. It proposes possible risks treatment and mitigation through the formulation of a balanced and comprehensive legislation by clear

  6. Research on the NPP human factors engineering operating experience review

    International Nuclear Information System (INIS)

    Ren Xiangchen; Miao Hongxing; Ning Zhonghe

    2006-01-01

    This paper addresses the importance of the human factors engineering (HFE) for the design of nuclear power plant (NPP), especially for the design of human-machine interface in the NPP. It also summarizes the scope and content of the NPP HFE. The function, scope, content and process of the NPP human factors engineering operating experience review (OER) are mainly focused on, and significantly discussed. Finally, it briefly introduces the situation of the studies on the OER in China. (authors)

  7. “Through the Letter Sent with my Envoys to Kiev” St. Dimitry`s of Rostov Contacts with Kiev and Chernigov in 1701–1709

    Directory of Open Access Journals (Sweden)

    Krylov Aleksei

    2016-10-01

    Full Text Available The article examines st. Dimitry’s of Rostov contacts with Kiev and Chernigov in 1701–1709. Dimitry’s correspondence is vast, but addressees of the most of the known letters are Dmitry’s Moscow friend and Great Russian hierarchs. Problem of st. Dimitry’s contacts with his Little Russian acquaintances still remain obscure. This article deals with the information of st. Dimitry of Rostov correspondence with addressees in Kiev and Chernigov and the circumstances of Dimitry’s visit to Chernigov in 1704. In time of his episcopal service st. Dimitry exchanged letters with Josaph Krokowski, archimandrit of Kievan Lauras and future metropolitan of Kiev. Letters were sent with agents of both hierarchs. This correspondence was devoted to the publication of the “Lives of the Saints” in the Lavra’s typography. There are no evedencies of st. Dimitry writing letteres to members of Chernigov clergy in 1701–1709, although st. John Maximovich archbishop of Chernigov sent his new books to Dimitry of Rostov. However in february of 1704st. Dmitry undertook a journey to Chernigov that left almost no traces in sources. The main evidence is record of Pachomios of Roman, a Moldavian ascetic, about himself meeting Rostov metropolitan in Chernigov in 1704. This trip was an exeptional event and could be connected with the demise of Parthenios Neboza, metropolitan of Holmogory, who died suddenly on 2 january 1704 in Yaroslavl. Author concludes that Dimitry of Rostov in 1701–1709 was not isolated from his old friends and mantained his ties with educated clergy of Little Russia during the years of his Episcopal service in Moscow and Rostov.

  8. Institutions and organisations in Russian higher education: the example of Rostov region education services market

    Directory of Open Access Journals (Sweden)

    Volchik Vyacheslav, V.

    2015-12-01

    Full Text Available The paper examines the process of transformation in institutional and organizational structures of Russian Higher Education (Rostov Region is taken as an example. Adaptive economic behavior of key actors on the Russian education services market has been studied in the context of constantly changing institutional and organizational environments. Original institutional approach in the tradition of J. Commons and J. Hodgson has been applied to analyze interconnections between institutions and organizations. The evolution of institutional and organizational structures in Russian Higher education has been divided into three stages. We distinguish between those stages taking into account the dynamics of quantitative indicators and the change in norms and standards that regulate actors’ behavior in the field. The period of 1990-2002 can be characterized by weakening of government regulation and, simultaneously, lack of financial support of Higher Education. Meanwhile, private Higher Education and paid university programmes developed rapidly during that period. These changes resulted in quantitative growth in the field on the one hand, and devaluation of Higher Education, on the other hand. It is assumed that the “bubble” in Russian Higher Education, which arose in 2002-2008, occurred to a great extent because of the expansion in extramural and lowquality full-time education aimed only at getting graduate diplomas. During the period of bubble formation and latter decline in demand on the Russian education services market, the Government strengthened norms and standards referring to regulation of Higher Education. Recent “optimization processes” of 2009-2015 resulted in reducing the number of students and lecturers, universities and their branches.

  9. Vertical Migration of Radionuclides in Soils on the Chernobyl Nuclear Power Plant (ChNPP) Exclusion Zone (1987-2007)

    Science.gov (United States)

    Jannik, G. T.; Ivanov, Y. A.; Kashparov, V. A.; Levchuk, S. E.; Bondarkov, M. D.; Maksymenko, A. M.; Farfan, E. B.; Marra, J. C.

    2009-12-01

    In 1986-1987, a set of experimental sites for studies of vertical migration of radionuclides released from the ChNPP was established in the ChNPP Exclusion Zone for various fallout plumes. The sites were selected considering local terrain and geo-chemical conditions, as well as physical and chemical characteristics of the fallout. The experimental sites included grasslands, and pre-Chernobyl cultivated meadows and croplands. Vertical migration of radionuclides in the ChNPP Exclusion Zone grasslands was evaluated. Parameters of 137Cs, 90Sr, and 239,240Pu transfer were calculated and the periods during which these radionuclides reach their ecological half-life in the upper 5 cm soil layer were estimated. Migration capabilities of these radionuclides in the grassland soils tend to decrease as follows: 90Sr >137Cs ≥ 239,240Pu. A significant retardation of the 137Cs vertical migration was shown in the grasslands long after the Chernobyl accident. During the 21st year after the fallout, average Tecol values for 137Cs (the period of time it takes in the environment for 137Cs to reach half the value of its original concentration in the upper 5 cm soil layer, regardless of physical decay) are as follows: 180 - 320 years for grassland containing automorphous mineral soils of a light granulometric composition; and 90 - 100 years for grassland containing hydromorphous organogenic soils. These values are significantly higher than those estimated for the period of 6-9 years after the fallout: 60 - 150 years and 11 - 20 years, respectively. The absolute 137Cs Tecol values are by factors of 3-7 higher than 137Cs radiological decay values long after the accident. Changes in the exposure dose resulting from the soil deposited 137Cs only depend on its radiological decay. This factor should necessarily be considered for development of predictive assessments, including dose exposures for the hypothetical population in case of their re-evacuation to the exclusion areas. The obtained

  10. Qualification of NPP operations personnel

    International Nuclear Information System (INIS)

    Wang Jiao.

    1987-01-01

    Competence of personnel is one of the important problems for safety operation of nuclear power plant. This paper gives a description of some aspects, such as the administration of NPP, posts, competence of personnel, training, assessing the competence and personnel management

  11. NPP construction cost in Canada

    International Nuclear Information System (INIS)

    Gorshkov, A.L.

    1988-01-01

    The structure of capital costs during NPP construction in Canada is considered. Capital costs comprise direct costs (cost of the ground and ground rights, infrastructure, reactor equipment, turbogenerators, electrotechnical equipment, auxiliary equipment), indirect costs (construction equipment and services, engineering works and management services, insurance payments, freight, training, operating expenditures), capital per cents for the period of construction and cost of heavy water storages. It proceeds from the analysis of the construction cost structure for a NPP with the CANDU reactor of unit power of 515, 740 and 880 MW, that direct costs make up on the average 62%

  12. Decommissioning of NPP A-1

    International Nuclear Information System (INIS)

    Anon

    2009-01-01

    In this presentation the Operation history of A1 NPP, Project 'Decommissioning of A1 NPP' - I stage, Project 'Decommissioning of A1 NPP ' - II stage and Next stages of Project 'Decommissioning of A1 NPP ' are discussed.

  13. Spain in South Ukraine NPP

    International Nuclear Information System (INIS)

    Ibanez, M.

    1994-01-01

    A Technical Assistance Protocol was signed between the Governments of the GIS and the Commission of the European Union (CEU) on August 2, 1991 and this was the starting point of the TACIS program. In this article, the activities described are those related to the TACIS-92/93/94 on site technical assistance to South Ukraine NPP (SUK NPP). Within the scope of the TACIS 92 Program the CEU and the Ukrainian Authorities agreed a list of projects to be implemented at South Ukraine NPP with the aim to improve the operational safety of the plant. This part of the program is called TACIS 92 on-site activities. The total budget allocated to these projects is a MECU. The European Union ''utility'' selected to lead this program at South Ukraine NPP was UNESA and the first contract to cover our activities was signed in July 1993 between the CEU (Mr. Pablo Benavides) and UNESA (Mr. Pedro Rivero). The projects will be implemented at SUK NPP but according to the contract UNESA is ''The Consultant'' and GOSKOMATON (The Ukrainian Sate Committee on Nuclear Power Utilization) is the ''Recipient Institution''. (Author)

  14. Regulatory aspects of NPP safety

    International Nuclear Information System (INIS)

    Kastchiev, G.

    1999-01-01

    Extensive review of the NPP Safety is presented including tasks of Ministry of Health, Ministry of Internal Affairs, Ministry of Environment and Waters, Ministry of Defense in the field of national system for monitoring the nuclear power. In the frame of national nuclear safety legislation Bulgaria is in the process of approximation of the national legislation to that of EC. Detailed analysis of the status of regulatory body, its functions, organisation structure, responsibilities and future tasks is included. Basis for establishing the system of regulatory inspections and safety enforcement as well as intensification of inspections is described. Assessment of safety modifications is concerned with complex program for reconstruction of Units 1-4 of Kozloduy NPP, as well as for modernisation of Units 5 and 6. Qualification and licensing of the NPP personnel, Year 2000 problem, priorities and the need of international assistance are mentioned

  15. Safety culture at Mochovce NPP

    International Nuclear Information System (INIS)

    Markus, Jozef; Feik, Karol

    2002-01-01

    This article presents the approach of Mochovce NPP to the Safety culture. It presents activities, which have been taken by Mochovce NPP up to date in the area of Safety culture enhancement with the aim of getting the term into the subconscious of each employee, and thus minimising the human factor impact on occurrence of operational events in all safety areas. The article furthermore presents the most essential information on how the elements characterising a continuous progress in reaching the planned Safety culture goals of the company management have been implemented at Mochovce NPP, as well as the management's efforts to get among the best nuclear power plant operators in this area and to be an example for the others. (author)

  16. Flora sampling in the vicinity of gamma greenhouse: As a flora sampling model for supporting the national nuclear power program (NPP)

    International Nuclear Information System (INIS)

    Affrida Abu Hassan; Zaiton Ahmad; Ros Anita Ahmad Ramli; Shakinah Salleh; Norazlina Noordin; Salmah Moosa; Sakinah Ariffin; Salahbiah Abdul Majid; Nur Humaira Lau Abdullah; Mohd Zaidan Kandar; Abdul Rahim Harun

    2012-01-01

    Gamma Green House was used as a model to study radiation effects on flora and ecosystems in supporting the National Nuclear Power Programme (NPP). A task force was formed in BAB which consists of 3 main groups of flora, fauna and microorganisms. For the flora group, two sampling expeditions have been carried out on July 7, 2011 and March 2, 2012 with the assistant of experts from University Putra Malaysia. From these expeditions, a preliminary data on the types and distribution of plants in selected quadrants close to the Gamma Greenhouse has been successfully observed and the collected plant samples have been preserved as part of the herbarium collection. This paper will describe on the sampling activities and sample preservation. Knowledge gained from this study will be very useful as model for flora distribution baseline data at plant site(author)

  17. Training human resource for NPP in Vietnam

    International Nuclear Information System (INIS)

    Nguyen, Trung Tinh; Dam, Xuan Hiep

    2008-01-01

    Vietnam will establish the first NPP in the near future. With us the first important thing is the human resource, but now there is no university in Vietnam training nuclear engineers. In EPU (Electric Power University), now we are preparing for training nuclear engineers. In this paper, we review the nuclear man power and the way to train the high quality human resource for NPP and for other nuclear application in Vietnam. (author)

  18. A program package connected with a communication network for accident statistics of NPP, TPP, HPP and the power lines

    International Nuclear Information System (INIS)

    Madjarova, A.

    1993-01-01

    The package is designed for registration and analysis of accidents according to users' needs. A possibility is also provided for easy data transfer and access to data on implemented decisions. Special programmes are developed for NPP, TPP, HPP, electricity supply branch, regional distribution management and the National Electric Company. The system is open for local network connection and file exchange between the workstations. The dialogue features are user-friendly. The emergency situations are classified according to the requirements of the enacted in Bulgaria 'Regulations for Investigation, Classification and Recording of Accidents in Electric and Thermal Stations and Networks, 1993'. The unified data input provides a possibility for insertion of additional texts (remarks), correcting and updating. Data security tools are also envisaged. (author)

  19. Mochovce NPP simulator

    International Nuclear Information System (INIS)

    Ziakova, M.

    1998-01-01

    Mochovce NPP simulator basic features and detailed description of its characteristics are presented with its performance, certification and application for training of NPP operators as well as the training scenario

  20. Co-ordinated research programme on benchmark study for the seismic analysis and testing of WWER-type nuclear power plants. V. 3E. Kozloduy NPP units 5/6: Analysis/testing. Working material

    International Nuclear Information System (INIS)

    1996-01-01

    The Co-ordinated research programme on the benchmark study for the seismic analysis and testing of WWER-type nuclear power plants was initiated subsequent to the request from representatives of Member States. The conclusions adopted at the Technical Committee Meeting on Seismic Issues related to existing nuclear power plants held in Tokyo in 1991 called for the harmonization of methods and criteria used in Member States in issues related to seismic safety. The Consulltants' Meeting which followed resulted in producing a working document for CRP. It was decided that a benchmark study is the most effective way to achieve the principal objective. Two types of WWER reactors (WWER-440/213 and WWER-1000) were selected as prototypes for the benchmark exercise to be tested on a full scale using explosions and/or vibration generators. The two prototypes are Kozloduy Units 5/6 for WWER-1000 and Paks for WWER-440/213 nuclear power plants. This volume of Working material contains reports on data related to floor response spectra of Kozloduy NPP; calculational-experimental examination and ensuring of equipment and pipelines seismic resistance at starting and operating WWER-type NPPs; analysis of design floor response spectra and testing of the electrical systems; experimental investigations and seismic analysis Kozloduy NPP; testing of components on the shaking table facilities and contribution to full scale dynamic testing of Kozloduy NPP; seismic evaluation of the main steam line, piping systems, containment pre-stressing and steel ventilation chimney of Kozloduy NPP

  1. Application of safety standards and rules in the Shelter Implementation Plan at the destroyed power unit of Chernobyl NPP

    International Nuclear Information System (INIS)

    Berthold, A.; Bogorinski, P.; Bykov, V.; Redko, V.; Erickson, L.; Kadkin, Ye.; Kondratiev, S.; Simonov, I.; Smyshliaieva, S.; Yesipenko, Yu.

    2002-01-01

    This report deals with the application of safety standards and rules to the Shelter Implementation Plan (SIP) measures. Since 1998 this plan is being implemented at the Chornobyl NPP destroyed unit (which is now known as the Shelter). It includes a set of various tasks whose performance will help partially achieve the established safety objectives. The Regulatory Authority should establish for the Shelter safety goals, principles, and criteria in general, while the Operator of the Shelter is free to independently select the optimum method for their implementation. The Operator of the Shelter must demonstrate (in safety analysis report) that established safety goals are achieved and safety principles and criteria are met. Safety goals, principles, and criteria established for radioactive waste management are reasonable to apply in measures provided for by SIP. However, due to the unique nature of the Shelter, some criteria should not be applied directly and in full scope. Norms and rules on radiation protection should be applied in full scope. The specifics of radiation protection during each Shelter-related activity are considered individually. Safety standards and rules related to technical aspects are reasonable only as a basis. Effective resolution of specific technical issues associated with safety assurance is achieved through interaction between the Operator and the Regulatory Authority during design of SIP structures and systems. Hence, effectiveness of the licensing process plays an important role in the success of the SIP.(author)

  2. Growth and development in school-age children from Rostov region, Russia: Comparison between urban and rural settings.

    Science.gov (United States)

    Voynov, V B; Kulba, S N; Arapova, Yu Yu

    2017-12-01

    The purposes of the current study were: (1) to describe growth and physical development and establish norms for schoolchildren from Rostov region in Russia; (2) to compare major characteristics of development between urban and rural children by sex and age. Nearly 200,000 children (198,712) aged between 7 and 17 years from 232 urban and rural schools of Rostov region (Southern Federal District of Russia) participated in the study. School age is a period of intensive growth and physiological and psychological development. Irregularities of personal development are caused by a multitude of factors, such as sex differences, heredity, socio-economic status of a family, standard of living, particular environmental conditions, and lifestyle. It has been established that children from the Southern Federal District of Russia had body mass index values higher than age-appropriate norms for all Russians (Total Russian, Rudnev et al., 2014) and World Health Organization charts. Children from urban settings were taller and heavier than children from rural settings. Sex is one of the most influential factors which play key role in determining specific characteristics of growth and personal development. According to our results, boys and girls both had similar age-related changes in weight and height, but their respective dynamics differed. Girls' height and weight values accelerated at the age 10 to 12 years and plateaued after the age fourteen, whereas in boys height and weight steadily increased with age, showing slight acceleration at the age 12 to 13 years, and reached a plateau by the age of seventeen. Copyright © 2017 Elsevier GmbH. All rights reserved.

  3. The V-1 NPP and V-2 NPP upgrading

    International Nuclear Information System (INIS)

    1998-01-01

    A brief account of activities in the V-1 NPP and V-2 NPP upgrading as well as maintenance carried out by the Nuclear power plants Jaslovske Bohunice in 1997 is presented. The V-1 NPP applied the so called 'Small Backfitting Programme'covering 81 points of the Czechoslovak Atomic energy Commission Decree No 5/91. Continual upgrading continued after the Backfitting Programme completion with the Safety Report and following Nuclear Regulatory Authority of Slovak Republic (NRA SR) Decrees No 1/94 and 110/94 setting spheres and procedure for adopting and implementation of measures enabling the units to operate further on. Results of expert missions, analyses and assessments of components identified by Basic Engineering became the basis for the development of the Gradual Reconstruction Programme. The Programme outputs underwent economic and probabilistic assessing their contribution to nuclear safety. This process resulted in finalizing the Gradual Reconstruction Programme which started to be implemented in 1996 and will be completed in 1999. It is implemented by the REKON consortium and covers 17 areas including Instrumentation and Control, self-consumption emergency supply, leakage monitoring, emergency core cooling system, seismic reinforcement and radioactivity localisation. Both units will reach internationally acceptable safety standards for the remaining life-time period. The V-2 NPP Upgrading and Safety Enhancement Programme includes results of activities performed in the course of last years to define all important activities leading to enhancement of nuclear safety and performance reliability and effectiveness within the plant life-time period and to establish conditions for extending the life-time of these units for 40 years. The V-2 NPP Upgrading and Safety Enhancement Programme aims to assure safe operation with a probability of the core damages less than 10 -4 /reactor · year

  4. Unit Commissioning of “Belene” NPP (Bulgaria)

    International Nuclear Information System (INIS)

    2009-01-01

    This presentations gives detailed information about the following topics about commissioning: principles of NPP commissioning; phases of NPP commissioning; organization of commissioning activities; duties and responsibilities of the parties for carrying out unit commissioning activities; responsibility and obligations of the sides during commissioning of power unit; documentation required for power unit commissioning; quality assurance for commissioning activities

  5. Leningrad NPP and energetics of north-western Russia

    International Nuclear Information System (INIS)

    Belov, I.

    2000-01-01

    Problems of Leningrad NPP operating units modernization, their design service life finishing by year of 2010, are discussed. To assure safe operation of unit 1 investments in the amount of 30 mln. dol are necessary. Estimations suggest economic efficiency of the measures, permitting saving of 300 mln. dol worth of gas. Unfortunately, without a rise in tariff for electric power produced by NPP it seems impossible. It is recommended that substantiated tariffs are set for electric power produced by NPP starting from January, 2000. The measure is indispensable for raising investment funds intended for operating NPP modernization [ru

  6. Nuclear Fuel in Cofrentes NPP

    International Nuclear Information System (INIS)

    2002-01-01

    Fuel is an essential in the nuclear power generating business because of its direct implications on safety, generating costs and the operating conditions and limitations of the facility. Fuel management in Cofrentes NPP has been targeted at optimized operation, enhanced reliability and the search for an in-depth knowledge of the design and licensing processes that will provide Iberdrola,as the responsible operator, with access to independent control of safety aspects related to fuel and free access to manufacturing markets. (Author)

  7. Decommissioning of Brennilis NPP

    International Nuclear Information System (INIS)

    Baize, Jean-Marc

    1998-01-01

    This EDF press communique give information related to the decommissioning of the Brennilis NPP. The following five items are developed in this report: 1. the level-2 decommissioning operations at the Brennilis NPP; 2. the Brennilis NPP, a pilot operation from the commissioning up to the decommissioning; 3. history of the Brennilis NPP decommissioning; 4. the types of radioactive wastes generated by the Brennilis NPP decommissioning; 5. the Brennilis NPP - a yard management as a function of the wastes. The document contains also seven appendices addressing the following subjects: 1. the share of decommissioning assigned to EDF and the decommissioning steps; 2. the EDF installations in course of decommissioning; 3. the CEA decommissioned installations or in course of decommissioning; 4. regulations; 5. costs; 6. waste management - principles; 7. data on the decommissioning yard

  8. Financial and organizational models of NPP construction projects

    International Nuclear Information System (INIS)

    Ivanov, Timur

    2010-01-01

    The recent evolution of financial and organizational models of NPP projects can be truly reputed to open a new page of the world market of NPP construction. The definition of the concrete model is based mostly on specific cooperation backgrounds and current terms and conditions under which the particular NPP project is being evolved. In this article the most commonly known strategies and schemes of financing structuring for export NPP construction projects are scrutinized. Special attention is paid to the analysis of BOO/BOT models which are based on the public-private partnership. Most BOO/BOT projects in the power sector has Power Purchase Agreements (PPA) as an integral part of them. The PPA key principles are studied here as well. The flexibility and adaptability of the public-private partnership models for financing and organization of the NPP projects contributes substantially to the competitiveness of the NPP projects especially under current economic conditions. (orig.)

  9. On the NPP structural reliability

    International Nuclear Information System (INIS)

    Klemin, A.I.; Polyakov, E.F.

    1980-01-01

    Reviewed are the main statements peculiarities and possibilities of the first branch guiding technical material (GTM) ''The methods of calculation of structural reliability of NPP and its systems at the stage of projecting''. It is stated, that in GTM presented are recomendations on the calculation of reliability of such specific systems, as the system of the reactor control and protection the system of measuring instruments and automatics and safe systems. GTM are based on analytical methods of modern theory of realibility with the Use of metodology of minimal cross sections of complex systems. It is stressed, that the calculations on the proposed methods permit to calculate a wide complex of reliability parameters, reflecting separately or together prorerties of NPP dependability and maintainability. For NPP, operating by a variable schedule of leading, aditionally considered are parameters, characterizing reliability with account of the proposed regime of power change, i.e. taking into account failures, caused by decrease of the obtained power lower, than the reguired or increase of the required power higher, than the obtained

  10. Treatment of NPP wastes using vitrification

    International Nuclear Information System (INIS)

    Sobolev, I.A.; Lifanov, F.A.; Stefanovsky, S.V.; Kobelev, A.P.; Savkin, A.E.; Kornev, V.I.

    1998-01-01

    Glass-based materials to immobilize various liquid and solid radioactive wastes generated at nuclear power plants (NPP) were designed. Glassy waste forms can be produced using electric melting including a cold crucible melting. Leach rate of cesium was found to be 10 -5 -10 -6 g/(cm 2 day) (IAEA technique). Volume reduction factor after vitrification reached 4-5. Various technologies for NPP waste vitrification were developed. Direct vitrification means feeding of source waste into the melter with formation of glassy waste form to be disposed. Joule heated ceramic melter, and cold crucible were tested. Process variables at treatment of Kursk, Chernobyl (RBMK), Kalinin, Novovoronezh (VVER) NPP wastes were determined. The most promising melter was found to be the cold crucible. Pilot plant based on the cold crucibles has been designed and constructed. Solid burnable NPP wastes are incinerated and slags are incorporated in glass. (author)

  11. NPP A-1 decommissioning - Phase I

    International Nuclear Information System (INIS)

    Krstenik, A.; Blazek, J.

    2000-01-01

    Nuclear power plant A-1 with output 150 MW e , with metallic natural uranium fuelled, CO 2 cooled and heavy water moderated reactor had been prematurely finally shut down in 1977. It is necessary to mention that neither operator nor regulatory and other authorities have been prepared for the solution of such situation. During next two consecutive years after shutdown main effort of operator focused on technical and administrative activities which are described in the previous paper together with approach, condition and constraints for NPP A-1 decommissioning as well as the work and research carried out up to the development and approval of the Project for NPP A-1 decommissioning - I. phase. Subject of this paper is description of: (1) An approach to NPP A -1 decommissioning; (2) An approach to development of the project for NPP A-1 decommissioning; (3) Project - tasks, scope, objectives; (4) Mode of the Project realisation; (5) Progress achieved up to the 1999 year. (authors)

  12. Changing NPP consumption patterns in the Holocene: from Megafauna "liberated" NPP to "ecological bankruptcy"

    Science.gov (United States)

    Doughty, C.

    2015-12-01

    There have been vast changes in how net primary production (NPP) is consumed by humans and animals during the Holocene beginning with a potential increase in availability following the Pleistocene megafauna extinctions. This was followed by the development of agriculture which began to gradually restrict availability of NPP for wild animals. Finally, humans entered the industrial era using non-plant based energies to power societies. Here I ask the following questions about these three energy transitions: 1. How much NPP energy may have become available following the megafauna extinctions? 2. When did humans, through agriculture and domestic animals, consume more NPP than wild mammals in each country? 3. When did humans and wild mammals use more energy than was available in total NPP in each country? To answer this last question I calculate NPP consumed by wild animals, crops, livestock, and energy use (all converted to units of MJ) and compare this with the total potential NPP (also in MJ) for each country. We develop the term "ecological bankruptcy" to refer to the level of consumption where not all energy needs can be met by the country's NPP. Currently, 82 countries and a net population of 5.4 billion are in the state of ecologically bankruptcy, crossing this threshold at various times over the past 40 years. By contrast, only 52 countries with a net population of 1.2 billion remain ecologically solvent. Overall, the Holocene has seen remarkable changes in consumption patterns of NPP, passing through three distinct phases. Humans began in a world where there was 1.6-4.1% unclaimed NPP to consume. From 1700-1850, humans began to consume more than wild animals (globally averaged). At present, >82% of people live in countries where not even all available plant matter could satisfy our energy demands.

  13. ASSET experience at Paks NPP

    International Nuclear Information System (INIS)

    Szabo, I.

    1997-01-01

    At Paks NPP special attention has been paid to international reviews since the very beginning of operation. Several international teams visited Paks in order to provide independent assessment of plant performance, conditions and safety. Paks NPP Management has the further intention to invite international reviews regularly (yearly) in the future as well. The experience gained during these reviews helped to establish a unified process of preparation for the reviews, performing them and handling the results. The Safety Department is in charge of organization of the whole process. All these reviews have their specific features and they are focused on different areas. The ASSET reviews provides the assessment of plant performance and safety through the analysis of safety significant events, which have occurred at the nuclear power plant. This approach makes this review specific and different from the other ones

  14. Retrofitting of NPP Computer systems

    International Nuclear Information System (INIS)

    Pettersen, G.

    1994-01-01

    Retrofitting of nuclear power plant control rooms is a continuing process for most utilities. This involves introducing and/or extending computer-based solutions for surveillance and control as well as improving the human-computer interface. The paper describes typical requirements when retrofitting NPP process computer systems, and focuses on the activities of Institute for energieteknikk, OECD Halden Reactor project with respect to such retrofitting, using examples from actual delivery projects. In particular, a project carried out for Forsmarksverket in Sweden comprising upgrade of the operator system in the control rooms of units 1 and 2 is described. As many of the problems of retrofitting NPP process computer systems are similar to such work in other kinds of process industries, an example from a non-nuclear application area is also given

  15. ASSET experience at Paks NPP

    Energy Technology Data Exchange (ETDEWEB)

    Szabo, I [Operational Safety Dept., Paks NPP, Paks (Hungary)

    1997-10-01

    At Paks NPP special attention has been paid to international reviews since the very beginning of operation. Several international teams visited Paks in order to provide independent assessment of plant performance, conditions and safety. Paks NPP Management has the further intention to invite international reviews regularly (yearly) in the future as well. The experience gained during these reviews helped to establish a unified process of preparation for the reviews, performing them and handling the results. The Safety Department is in charge of organization of the whole process. All these reviews have their specific features and they are focused on different areas. The ASSET reviews provides the assessment of plant performance and safety through the analysis of safety significant events, which have occurred at the nuclear power plant. This approach makes this review specific and different from the other ones.

  16. Development of specific costs of nuclear power supply from the Dukovany NPP during the plant's 20 years of operation

    International Nuclear Information System (INIS)

    Curda, F.; Krob, P.

    2005-01-01

    The papers focuses particularly on the evaluation of the individual measures taken with a view to achieving reduction in the specific costs and rationalisation of costs, and discusses the impacts of factors such as outsourcing of activities (maintenance, selected services), structural changes at CEZ a. s. utility, and establishment of the Division of Nuclear Power Plants at CEZ. (author)

  17. Safety upgrading of Bohunice V1 NPP

    International Nuclear Information System (INIS)

    2001-01-01

    This CD is multimedia presentation of programme safety upgrading of Bohunice V1 NPP. It consist of next chapters: (1) Introductory speeches; (2) Nuclear power plant WWER 440; (3) Safety improvement; (4) Bohunice Nuclear power plants subsidiary; (5) Siemens; (6) REKON; (7) VUJE Trnava, Inc. - Engineering, Design and Research Organisation; (8) Album

  18. Near Regional and Site Investigations of the Temelin NPP Site

    International Nuclear Information System (INIS)

    Prachar, Ivan; Vacek, Jiri; Heralecky, Pavel

    2011-01-01

    The Temelin NPP is worldwide through heated discussion with nuclear energetic opposition. In addition this discussion goes beyond a border of the Czech Republic. On the other side, results of several international supervisions shown that Temelin NPP is fully comparable with the safest nuclear power plants in the world regarding its technical design and safety functions. This presentation deals with the near regional and site investigations of the Temelin NPP Site. It must be noted that although the Temelin site is situated in the area with low seismicity, item of seismicity is a basic argument against Temelin NPP and therefore a detail seismic hazard assessment was performed

  19. The ultimate emergency measures to secure a NPP under an accidental condition with no designed power or water supply

    Energy Technology Data Exchange (ETDEWEB)

    Liang, K.S., E-mail: ksliang@alum.mit.edu [Institute of Nuclear Engineering and Science, National Tsing Hua University, 101 Sec. 2, Kuang-Fu Road, Hsinchu 30013, Taiwan (China); School of Nuclear Science and Engineering, Shanghai Jiao Tong University, 800 Dong-Chuan Road, Shanghai (China); Chiang, S.C. [Department of Nuclear Safety, Taiwan Power Company, 242 Sec. 3, Roosevelt Road, Taipei 10016, Taiwan (China); Hsu, Y.F.; Young, H.J.; Pei, B.S. [Institute of Nuclear Engineering and Science, National Tsing Hua University, 101 Sec. 2, Kuang-Fu Road, Hsinchu 30013, Taiwan (China); Wang, L.C. [Department of Nuclear Safety, Taiwan Power Company, 242 Sec. 3, Roosevelt Road, Taipei 10016, Taiwan (China)

    2012-12-15

    Highlights: Black-Right-Pointing-Pointer An ultimate measure to secure core was developed, if power or water supply cannot be restored in time. Black-Right-Pointing-Pointer This ultimate measure was simulated by RELAP5-3D to verify the concept of this emergency plan. Black-Right-Pointing-Pointer Quantification of the required raw water injection rate was performed for NPPS in Taiwan Black-Right-Pointing-Pointer Reactor controlled depressurization within the 1st hour is essential to reduce the required raw water injection rate. Black-Right-Pointing-Pointer For PWR, even heat sink can be developed, RCP seal leak might eventually cause core uncover 10 h after seal leak occurs. - Abstract: In the recent nuclear catastrophe which occurred in Japan on March 11, 2011, several units of Fukushima conventional BWR experienced a total loss of power and water supply triggered by a heavy earthquake and a following Tsunami beyond design basis. In Fukushima accident it was observed that sea water was injected into reactors only after hydrogen explosion took place and it was considered a little too late to prevent core from damage. With regard to this fact, the Taiwan power company develops an ultimate measure to prevent reactor from encountering core damage, if either designed AC power or reactor water supply cannot be restored in time. This ultimate measure was named as DIVing plan, abbreviated from system depressurization, water injection and containment venting. Once any designed AC power or reactor water supply is made available, this DIVing plan will be activated to (1) depressurize reactor first, (2) inject any available water into reactor by any available power supply if this critical status cannot be restored in time, and (3) vent the containment if necessary to maintain containment integrity. In this paper the DIVing plan was simulated by RELAP5-3D to verify the concept of it and also to quantify the required raw water injection rate to prevent core from damage for both

  20. The ultimate emergency measures to secure a NPP under an accidental condition with no designed power or water supply

    International Nuclear Information System (INIS)

    Liang, K.S.; Chiang, S.C.; Hsu, Y.F.; Young, H.J.; Pei, B.S.; Wang, L.C.

    2012-01-01

    Highlights: ► An ultimate measure to secure core was developed, if power or water supply cannot be restored in time. ► This ultimate measure was simulated by RELAP5-3D to verify the concept of this emergency plan. ► Quantification of the required raw water injection rate was performed for NPPS in Taiwan ► Reactor controlled depressurization within the 1st hour is essential to reduce the required raw water injection rate. ► For PWR, even heat sink can be developed, RCP seal leak might eventually cause core uncover 10 h after seal leak occurs. - Abstract: In the recent nuclear catastrophe which occurred in Japan on March 11, 2011, several units of Fukushima conventional BWR experienced a total loss of power and water supply triggered by a heavy earthquake and a following Tsunami beyond design basis. In Fukushima accident it was observed that sea water was injected into reactors only after hydrogen explosion took place and it was considered a little too late to prevent core from damage. With regard to this fact, the Taiwan power company develops an ultimate measure to prevent reactor from encountering core damage, if either designed AC power or reactor water supply cannot be restored in time. This ultimate measure was named as DIVing plan, abbreviated from system depressurization, water injection and containment venting. Once any designed AC power or reactor water supply is made available, this DIVing plan will be activated to (1) depressurize reactor first, (2) inject any available water into reactor by any available power supply if this critical status cannot be restored in time, and (3) vent the containment if necessary to maintain containment integrity. In this paper the DIVing plan was simulated by RELAP5-3D to verify the concept of it and also to quantify the required raw water injection rate to prevent core from damage for both PWR and BWR plants in Taiwan, after the loss of passive cooling mechanism. Provided the passive cooling mechanism is lost

  1. Conference: Nuclear Safety at the Ignalina NPP - Achievements and Challenges

    International Nuclear Information System (INIS)

    1999-01-01

    Brief description of conference which took place in Vilnius on 8-9 April 1999 is presented. The aim of the international conference is to review the work carried out, to evaluate its influence on the nuclear safety, to get acquainted with the safety system of the Ignalina NPP. On December 31, the Ignalina NPP celebrated its 15 year anniversary. During that period the Ignalina NPP has produced more than 182 billion kWh of electricity. Nuclear power is not only immense economic benefit but also a syndrome of fear of an atomic bomb and the Chernobyl accident that has formed over the years. Numerous comprehensive international studies have been performed at the Ignalina NPP. After the Chernobyl accident many steps have been taken to improve the safety of the Ignalina NPP. The introduced changes guaranteed that the void coefficient remained negative in all possible circumstances. The Ignalina NPP is intensively preparing for licensing of unit 1

  2. Replacement of the computerized control system at NPP under operation

    International Nuclear Information System (INIS)

    Ermolaev, A.D.; Rakitin, I.D.

    1985-01-01

    Reasons and preconditions for replacement of the computerized control systems (CCS) at NPP under operation are consi-- dered. Problems dealing with management of CCS replacement, maintenance of a new CCS as well as NPP personnel training for the new system maintenance are discussed. A necessity of NPP personnel participation in these works in order to adapt CCS to requirements of NPP operation personnel and to initiate the training process is underlined. Replacement of CCS at NPP under operation is associated, as a rule, with obsolescence of old systems not ensuring growing requirements to NPP workability and safety. Principles observed at CCS replacement are reduced, mainly, to the following; maximum utilizatian of existing equipment, metal strUctures, cables, instruments, power supplies, ventilation system minimum of construction works and new communications; the least change of acting panels and boxes; changes in control desks should be introduced on the basis of the analysis of operator actions '

  3. Akkuyu NPP – the first Turkish NPP. The new history of the project

    International Nuclear Information System (INIS)

    Tzocheva, V.

    2012-01-01

    An overview is given to the Turkish energy sector and nuclear power plans. The project for the construction of the first NPP in Turkey is presented. The general parameters of the Project are: CAPEX: $ 20 bln; Project design: NPP-2006; (VVER- 1200); Number of units: 4; Total capacity: 4 800 MW; Construction period: 2014 – 2023; PPA period; 15 years, fixed price terms. An account of the activities during 2011, the Worley Parsons participation are presented and a tentative project schedule is given

  4. Nuclear fuel operation at Balakovo NPP

    International Nuclear Information System (INIS)

    Morozov, A.

    2015-01-01

    The presentation addressed the positive experience of the TVS-2M assemblies implementation at Balakovo NPP in 18 month fuel cycles, at uprated power (104%) and the usage of the axial profiled Gd-rods in order to minimize the power peaking factors and linear heat rate in the upper part in some of the fuel rods. The results of the test operation of fuel rods with different claddings, made by E110M, E125 and E635M alloys at Balakovo NPP were also provided. The recently observed problem with the “white crust” on the cladding surfaces was also discussed

  5. Safety upgrading program in NPP Mochovce

    International Nuclear Information System (INIS)

    Baumeister, P.

    1999-01-01

    EMO interest is to operate only nuclear power plants with high standards of nuclear safety. This aim EMO declare on preparation completion and commissioning of Mochovce Nuclear Power Plant. Wide co-operation of our company with International Atomic Energy Agency and west European Inst.ions and companies has been started with aim to fulfil the nuclear safety requirements for Mochovce NPP. Set of 87 safety measures was implemented at Mochovce Unit 1 and is under construction at Unit 2. Mochovce NPP approach to safety upgrading implementation is showed on chosen measures. This presentation is focused on the issues category III.(author)

  6. Human reliability analysis approach to level 1 PSA - shutdown and low power operation of Mochovce NPP, Unit 1, Slovakia

    International Nuclear Information System (INIS)

    Stojka, Tibor; Holy, Jaroslav

    2003-01-01

    The paper presents general approach, used methods and form of documentation of the results as have been applied within the Human Reliability Analysis (HRA) task of the shutdown and low power PSA (SPSA) study for Mochovce nuclear power plant, Unit 1, Slovakia. The paper describes main goals of the HRA task within the SPSA project, applied methods and data sources. Basic steps of the HRA task and human errors (HE) classification are also specified in its first part. The main part of the paper deals with pre-initiator human errors, human-induced initiators and response to initiator human errors. Since the expert judgment method (SLIM) was used for the last type of human errors probability assessment, also related activities are described including preparation works (performance shaping factors (PSFs) selection, development of PSF classification tables, preparation of aid tools for interview with plant experts), qualitative analysis (sources of information and basic steps) and quantitative analysis itself (human errors classification for final quantification including criteria used for the classification, description of structure of the spreadsheet used for quantification and treatment with dependencies). The last part of the paper describes form of documentation of the final results and provides some findings. (author)

  7. Licensing of the Ignalina NPP

    International Nuclear Information System (INIS)

    Kutas, S.

    1999-01-01

    Since 1991 State Nuclear Power Safety Inspectorate (VATESI) has regulated Ignalina NPP operation by issuing annual operating permits. Those have been issued following submission of specified documents by the Ignalina NPP that have been reviewed by VATESI. However, according to to the procedures that are now established in the Law on Nuclear Energy and subordinate regulations the use of nuclear energy in the Republic of Lithuania is subject to strict licensing. Therefore a decision about the licence for continued operation of unit 1 should be taken. Licence would be granted by VATESI in cooperation with the Ministry of Health, Ministry of Environment and the institutions of local authorities. Ignalina NPP presented to the VATESI safety analysis report (SAR) with other documents. SAR was made mainly by foreign experts and financed by European Bank for Reconstruction and Development (EBRD). VATESI in this process is supported by western regulators. A special project LAP - Licensing Assistance Project was launched to help VATESI perform licensing according western practices

  8. An overview of course offered by the USA, UK and France to support Nuclear Power Program (NPP)

    International Nuclear Information System (INIS)

    Sheriffah Noor Khamseah Al-Idid Syed Ahmad Idid

    2012-01-01

    In her presentation, speaker address a topic on nuclear education that offered by USA, UK and France to support nuclear power program. Her presentation actually assist students that are willing to explore several courses related to nuclear energy and its application. The speaker also explained briefly the impact of major nuclear accidents such as Fukushima that can influence the participation of students to study in these fields. She also outlines several nuclear stake holders and also some activities to support nuclear application such as planning, research, engineering, environmental impact assessment and others. She also explain in detail the needs to develop human capital especially for this field. At the end of her lectures, she tried to suggest several recommendations so that the audients can use in order to review their own strategies and planning for future training and studies. (author)

  9. NPP service life management

    International Nuclear Information System (INIS)

    Elagin, Yu.P.

    2001-01-01

    Problems of NPP service life management and service life prolongation are reviewed. Methods for the prolongation of the French NPP service life are discussed, priority directions of nuclear block service life management in regard to aging in the context of the European program of investigation into the materials aging are identified. Questions of the provision of the 60 years service life of the Mihama 1 block (Japan) and decision of the problem of the control equipment aging in Great Britain are discussed. Situation with the prolongation of licenses on the NPP operation in the USA and Spain is considered [ru

  10. Automatic control system at the ''Loviisa'' NPP

    International Nuclear Information System (INIS)

    Kukhtevich, I.V.; Mal'tsev, B.K.; Sergievskaya, E.N.

    1980-01-01

    Automatic control system of the Loviisa-1 NPP (Finland) is described. According to operation conditions of Finland power system the Loviisa-1 NPP must operate in the mode of week and day control of loading schedule and participate in current control of power system frequency and capacity. With provision for these requirements NPP is equipped with the all-regime system for automatic control functioning during reactor start-up, shut-down, in normal and transient regimes and in emergency situations. The automatic control system includes: a data subsystem, an automatic control subsystem, a discrete control subsystem including remote, a subsystem for reactor control and protection and overall station system of protections: control and dosimetry inside the reactor. Structures of a data-computer complex, discrete control subsystems, reactor control and protection systems, neutron flux control system, inside-reactor control system, station protection system and system for control of fuel element tightness are presented in short. Two-year experience of the NPP operation confirmed advisability of the chosen volume of automatization. The Loviisa-1 NPP operates successfully in the mode of the week and day control of supervisor schedule and current control of frequency (short-term control)

  11. Dissemination of Knowledge about NPP Instrumentation and Control Systems

    International Nuclear Information System (INIS)

    Yastrebenetsky, M.

    2016-01-01

    Full text: Instrumentation and control (I&C) systems are the most variable part in the nuclear power plants (NPP) comparatively with any other NPP systems. This statement is connected with the wide use of computers, rapid changes in information technologies, with the appearance of new computer complex electronic components, e.g., field programmable gate arrays (FPGA) and with appropriate point of their insertion into NPP I&C life cycle. The changes in NPP I&C systems require the dissemination of the knowledge about these systems. Lessons after Fukushima accident increase necessity of these actions. The elaboration and following dissemination of this knowledge took place in different directions: • Writing and issue of three new books about NPP I&C systems for specialists and for students which were issued in Ukrainian and USA public houses (the last book was issued in 2014); • Organization of five international scientific technical conferences, devoted to NPP I&C safety problems; • Elaboration of national (Ukrainian) standards and regulations pertaining to safety important NPP I&C systems (the last standard was issued in 2015) and participation in elaboration of international standards; • Lecturing for university students, NPP specialists and I&C designers. These actions in all directions are added to IAEA activity in the area NPP I&C systems (e.g., IAEA NP-T-3.12 “Core Knowledge on I&C systems in NPP”). (author

  12. Radioactive source management in Daya Bay NPP

    International Nuclear Information System (INIS)

    Mao Chun Yang

    2000-01-01

    'Small sources causes big accidents' had occurred worldwide many times. Radioactive source management in Nuclear Power Plant in very important for its safety record. This paper introduces the way and experience of radioactive source management in Daya Bay NPP from aspects of clarifying the responsibilities, centralizing the management of high radioactivity sources, work process management and experience feedback etc. (author)

  13. NPP Krsko natural circulation performance evaluation

    International Nuclear Information System (INIS)

    Segon, Velimir; Bajs, Tomislav; Frogheri, Monica

    1999-01-01

    The present document deals with an evaluation of the natural circulation performance of the Krsko nuclear power plant. Two calculation have been performed using the NPP Krsko nodalization (both similar to the LOBI A2-77 natural circulation experiment) - the first with the present steam generators at NPP Krsko (Westinghouse, 18% plugged), the second with the future steam generators (Siemens, 0% plugged). The results were evaluated using the natural circulation flow map derived in /1/, and were compared to evaluate the influence of the new steam generators on the natural circulation performance. (author)

  14. Medical consequences of NPP and TPP operation

    International Nuclear Information System (INIS)

    Bliznakov, V.

    1996-01-01

    Results from a comparative analysis of health conditions of the staff in the Kozloduy NPP and the Maritsa Iztok TPP are reported. It is found that the general disease incidence with temporary incapacity for work of Kozloduy workers is lower than those data for the workers at thermal power stations. The incidence of some social diseases like neoplasms, TBC, hypertension, ischemia etc. is also lower for the staff of NPP. No cases of radiation injuries have been registered for a period of 21 years

  15. Lifetime evaluation of Bohunice NPP components

    International Nuclear Information System (INIS)

    Kupca, L.

    2001-01-01

    The paper discuss some aspects of the main primary components lifetime evaluation program in Bohunice NPP which is performed by Nuclear Power Plant Research Institute (NPPRI) Trnava in cooperation with Bohunice and other organizations involved. Facts presented here are based on the NPPRI research report which is regularly issued after each reactor fuel campaign under conditions of project resulted from the contract between NPPRI and Bohunice NPP. For the calculations, there has been used some computer codes adapted (or made) by NPPRI and the results are just the conclusive and very brief, presented here in Tables (Figures). (authors)

  16. Co-ordinated research programme on benchmark study for the seismic analysis and testing of WWER-type nuclear power plants. V. 4B. Paks NPP: Analysis/testing. Working material

    International Nuclear Information System (INIS)

    1995-01-01

    The Co-ordinated research programme on the benchmark study for the seismic analysis and testing of WWER-type nuclear power plants was initiated subsequent to the request from representatives of Member States. The conclusions adopted at the Technical Committee Meeting on Seismic Issues related to existing nuclear power plants held in Tokyo in 1991 called for the harmonization of methods and criteria used in Member States in issues related to seismic safety. The Consulltants' Meeting which followed resulted in producing a working document for CRP. It was decided that a benchmark study is the most effective way to achieve the principal objective. Two types of WWER reactors (WWER-440/213 and WWER-1000) were selected as prototypes for the benchmark exercise to be tested on a full scale using explosions and/or vibration generators. The two prototypes are Kozloduy Units 5/6 for WWER-1000 and Paks for WWER-440/213 nuclear power plants. This volume of Working material contains reports on dynamic study of the main building of the Paks NPP; shake table investigation at Paks NPP and the Final report of the Co-ordinated Research Programme

  17. Some problems of NPP construction base improvement

    International Nuclear Information System (INIS)

    Movchan, S.V.

    1984-01-01

    NPP construction bases are characterized by high cost of construction and large area. Duration of base construction makes up 3-4 years, labour contents for their erection constitute 600-900 thousand man-days. Delays in organizing functional base services essentially decelerate construction rates of the main NPP buildings. Maximum joining of separate buildings by their functional assignment and structural peculiarities, wide application of container buildings, partial utilization of permanent buildings of production centre for construction needs; transition to new organizational form of construction based on industrial production of buildings; production of volumetric structural-technological cells with mounted equipment manufactured at specialized plants, mounting NPP components with stock produced cells, consideration of the problem of large power centre creation are necessary for reduction of construction centres, area reduction of cost and duration of their construction

  18. Qinshan NPP large break LOCA safety analysis

    International Nuclear Information System (INIS)

    Shi Guobao; Tang Jiahuan; Zhou Quanfu; Wang Yangding

    1997-01-01

    Qinshan NPP is the first nuclear power plant in the mainland of China, a 300 MW(e) two-loop PWR. Large break LOCA is the design-basis accident of Qinshan NPP. Based on available computer codes, the own analysis method which complies with Appendix k of 10 CFR 50 has been established. The RELAP4/MOD7 code is employed for the calculations of blowdown, refill and reflood phase of the RCS respectively. The CONTEMPT-LT/028 code is used for the containment pressure and temperature analysis. The temperature transient in the hot rod is calculated using the FRAP-6T code. Conservative initial and functional assumptions were adopted during Qinshan NPP large break LOCA analysis. The results of the analysis show the applicable acceptance criteria for the loss-of-coolant accident are met

  19. 20 Years of Dukovany NPP Operation and Plans for Future

    International Nuclear Information System (INIS)

    Vlcek, J.

    2006-01-01

    NPP Dukovany (4x440MW), the first Czech nuclear power plant and a keystone of Czech Electricity Grid, in 2005 celebrated 20 years of successful operation. In my presentation I am going to speak about next areas. I will start about construction and commissioning history of Dukovany NPP, then I'll put forward what milestones of Dukovany NPP operation were accomplished, I'll say examples about our modernisation and investment activities (including replacement of IandC equipment, modifications for increasing of power and support grid services) and in the end our plans for future. (author)

  20. Introduction of the SAT based training programs at Paks NPP

    International Nuclear Information System (INIS)

    Kiss, I.

    1998-01-01

    An introduction of the SAT based training programs at Paks nuclear power plant is described in detail, including framework of project operation; project implementation; process of SAT applied at Paks NPP and the needs of its introduction

  1. Safeguards at Kozloduy NPP - Experience and expectations

    International Nuclear Information System (INIS)

    Elenkov, Todor

    2001-01-01

    Bulgaria is a party of Non Proliferation Treaty since 5 September 1969. The agreement between IAEA and Bulgaria - INFCIRC 178 - has been in force since 29 February 1972. At that time Bulgaria had one research reactor IRT-2000 in Sofia and two power reactors of WWER-440 type under construction. Now at Kozloduy NPP site there are 4 facilities, which consist of 4 WWER-440 and 2 WWER-1000 type power reactors, producing almost 50% of the electricity in Bulgaria and 1 wet away from reactor spent fuel storage. In 1991 under the green movements and social pressure, the research reactor in Sofia was closed and the construction of the second NPP in Belene with 2 WWER-1000 type reactors was halted. After the transfer in 1994 of the fresh fuel from the research reactor to Kozloduy due to security reasons practically NPP Kozloduy remains the only significant (from safeguards point of view) nuclear site in Bulgaria. In 1972 a 'Nuclear Fuel' group was formed at the Physicists Department in NPP Kozloduy with responsibilities to carry out for safeguards records and reports, fresh and spent fuel transport and control. In 1990 this group was transferred to the Safety Section and since 1992 it exists as 'Control and Accounting for of the Nuclear Materials' - a section in the Safety Department. Currently the section serves all four facilities in NPP Kozloduy and has four people: section head, chief inspector and two inspectors. The main activities of the section include: a) Control of the nuclear fuel location as well as meeting the storage and transport conditions regulations; b) Control of the conditions for normal operations of the installed IAEA surveillance systems; c) Preparation of documents for licensing of fresh and spent nuclear fuel transport; d) Preparation of the official information on nuclear materials location and quantity; e) Preparation of accounting records and the reports for IAEA (ICR, PIL, MBR); f) Co-ordination of the IAEA safeguards inspection activities at NPP

  2. Plasma-Gasification-Melting System (PGM) for Treatment of Low and Intermediate Level Radioactive Waste (LILRW) Generated by Nuclear Power Plants (NPP's)

    International Nuclear Information System (INIS)

    Pegaz, D.

    2004-01-01

    Solid LILRW generated by NPP's is treated by various methods of Volume Reduction and Stabilization / Immobilization before disposal at suitable Storage Sites for Radioactive Waste. PGM Technology thermally treats such solid LILRW achieving maximum volume reduction and efficient stabilization of radionuclides of the waste in a Vitrified (glassy) solid residue, slag. Since such LILRW is made of a large variety of different materials, organic and inorganic, the PGM Process gasifies and pyrolizes the organics while the inorganics are melted and vitrified

  3. Modernization and safety improvement project of the NPP V-2 Jaslovske Bohunice

    International Nuclear Information System (INIS)

    Michal, V.; Losonsky, B.; Magdolen, J.

    2000-01-01

    This contribution deals with the form, present state, and results of the Nuclear Power Plants Research Institute (the Slovak acronym is VUJE - Vyskumny Ustav Jadrovych Elektrarni) participation in the NPP V-2 Jaslovske Bohunice Modernization and Safety Improvement Project. A short description of VUJE history, activity, and results is also presented as well as NPPs Jaslovske Bohunice characterization. VUJE was established in 1977 and deals with scientific and research needs of nuclear power plants, such as design, construction, commissioning and operation. The next fields of VUJE activity are, NPP reconstruction, NPP personnel training, radioactive waste management technology, and NPP decommissioning. The nuclear power plant, Jaslovske Bohunice, is situated approximately 15 km from the district town of Trnava in the southwestern region of the Slovak Republic. The construction of the first Czechoslovak NPP A-1 began on this site in 1957 .The construction of the double-unit NPP V-1 with WWER-440 (type V-230) reactor began in 1972. The first unit of NPP V-1 began operation in 1978 and the second in 1980. NPPs construction on the Bohunice site continued with NPP V-2, which has two units with WWER-440 (type V-213) reactors. Unit 1 and Unit 2 of NPP V-2 were commissioned in 1984 and 1985, respectively. Slovak electric utility Slovenske elektrarne (SE) is the owner/commissioner of NPP V-2. This NPP is responsible for more than 20% of the total electrical energy production of SE, making it an essential supporter of the Slovak economy. (authors)

  4. NPP electrical price and tariff in the world

    International Nuclear Information System (INIS)

    Mochamad Nasrullah and Sriyana

    2010-01-01

    Construction of a Nuclear Power Plant (NPP) is always become a controversial issue. Nuclear utility and other party which support the NPP present a calculation of NPP electricity cost too optimistic. However for utility and other party that contra to nuclear present a calculation of NPP electricity cost too pessimistic. This study present to reduce the controversy of nuclear cost. In this study, capital cost (Engineering Procurement Construction, EPC) was taken from Asian, America and Europe, operating and maintenance cost uses experience data of PLN, and nuclear fuel cost uses data year of 2008 with high price, low price and average price scenario. The methodological tools used to compare electricity generation cost was LEGECOST, a program developed by IAEA (International Atomic Energy Agency), while for electricity tariff- price calculation using a program developed by PLN research and development center. With the discount rate 10%, the result shows that the cheapest electricity generation cost of NPP is less than 40 mills/kWh, and average electricity tariff was 55 mills/kWh. In the Europe countries the electricity tariff more expensive than NPP in Asia. However generating cost and electricity tariff of NPP in United Stated of America (USA) less competitive because investment cost more expensive. Generating cost and electricity tariff was different at each country depend on salary, labor wage, materials price, construction specification, regulation related to NPP and environment aspect. (author)

  5. Monitoring program of surrounding of the NPP SE-EBO

    International Nuclear Information System (INIS)

    Dobis, L.; Kostial, J.

    1997-01-01

    The paper dealt with monitoring program of radiation control of surrounding of the NPP Bohunice, which has the aim: (1) to ensure the control of influence of work of the NPP Bohunice on the environment in their surrounding; (2) to ensure the back-ground for regular brief of control and supervisory organs about condition of the environment in surrounding of the NPP Bohunice; (3) to maintain the expected technical level of control of the NPP Bohunice and to exploit optimally the technical means; (4) to solicit permanently the data about the radioactivity of environment in surrounding of the NPP Bohunice for forming of files of the data; (5) to exploit purposefully the technical equipment, technical workers and to maintain their in permanent emergency and technical eligibility for the case of the breakdown; (6) to obtain permanently the files of the values for qualification of the reference levels. This program of monitoring includes the radiation control of surrounding of the NPP Bohunice, in the time of normal work of power-station's blocks, inclusively of all types of trouble-shooting and repairer works in surrounding of the NPP Bohunice, up to distance 20 km from power-station. The monitoring includes: outlets from the NPP Bohunice, monitoring of radiation characteristics in surrounding of the NPP Bohunice, (aerosols, fall-outs, soil), the links of food chains: (grass and fodder, milk, agriculture products), hydrosphere in surrounding (surface waters, drink water, bores of radiation control in complex of the NPP Bohunice, components of the hydrosphere), measurement of radiation from external sources (measurement of the dose rates, measurement of the doses [sk

  6. EMAS at Doel NPP

    International Nuclear Information System (INIS)

    Nolan, Peter; Thoelen, Els

    1998-01-01

    In October 1995, Doel NPP of Electrabel, Belgium opted to seek registration under the EC Eco-management and Audit Scheme (EMAS). A comprehensive environmental management system (EMS) has been introduced and implemented, encompassing all four PWRs and the supporting departments. A critical step was to seek certification from an accredited environmental auditing body against the International Standard ISO 14001. This provided the foundation for the publicly available environmental statement required by EMAS. The complications of achieving EMAS at a time when national and international standards were being re-formulated were successfully overcome and Doel NPP passed its EMAS audit in June 1997. (author)

  7. Overview of Cernavoda NPP training programme

    International Nuclear Information System (INIS)

    Valache, Cornelia

    2005-01-01

    Full text: The paper presents a general assessment of Cernavoda NPP personnel training programme, highlighting the role of training in human performance improvement. Cernavoda NPP Personnel Training and Authorization Department (PTAD) is the one responsible for the training of Unit 1 and 2 staff. PTAD is structured in such a manner as to support and respond to all Cernavoda NPP training, qualification and authorization requirements. The training of personnel is continuously adapted based on IAEA Guides and INPO/WANO recommendations, to keep with world standards, based on the internal and external reviews. At Cernavoda NPP the Training Concept and the Training Programmes are based on SAT - Systematic Approach to Training. The Training Concept is established on a set of training documents (RD's, SI's, IDP's), which address all the SAT phases: Analysis, Design, Development, Implementation and Evaluation. The Training Programmes are structured on the initial and continuing personnel training. Their content and goals respond to the training specific needs for each plant major job family. In order to successfully support NPP training programmes, CNPP training center has upgraded classrooms with new presentation facilities and there are plans to expand the space of the building, to develop additional operator and maintenance skills facilities. There are also a number of general areas for improvement of PTAD activity, such as operators and maintenance training, initial and continuing training of both Unit 1 and 2 staff. By responding in a timely and completely manner to all plant training requirements PTAD will help in rising human performance of Cernavoda NPP personnel, supporting the safe, efficient and cost effective production of power. (author)

  8. International Conference of Ukrainian Nuclear Society ''NPP's safety and protection''(annotations)

    International Nuclear Information System (INIS)

    Barbashev, S.V.

    1997-01-01

    The abstracts of reports submitted to the Conference include: - New developments of the safe nuclear installations; - NPP ecological safety; - Methods of personnel and population protection; - Waste management safety (at transportation, processing and storage); - Spent nuclear fuel management; - NPP life extension and decommissioning; - Public opinion as an element of NPP safety; - Training of personnel, scientific support and safety culture; - Forecasting of nuclear power and industry safe development; - Development of international cooperation in nuclear power

  9. Operating Experience at NPP Krsko

    International Nuclear Information System (INIS)

    Kavsek, D.; Bach, B.

    1998-01-01

    Systematic analysis of operational experience by assessment of internal and industry events and the feedback of lessons learned is one of the essential activities in the improvement of the operational safety and reliability of the nuclear power plant. At NPP Krsko we have developed a document called ''Operating Experience Assessment Program''. Its purpose is to establish administrative guidance for the processing of operating events including on-site and industry events. Assessment of internal events is based on the following methods: Event and Causal Factor Charting, Change Analysis, Barrier Analysis, MORT (Management Oversight and Risk Tree Analysis) and Human Performance Evaluation. The operating experience group has developed a sophisticated program entitled ''Operating experience tracking system'' (OETS) in response to the need for a more efficient way of processing internal and industry operating experience information. The Operating Experience Tracking System is used to initiate and track operational events including recommended actions follow up. Six screens of the system contain diverse essential information which allows tracking of operational events and enables different kinds of browsing. OETS is a part of the NPP Krsko nuclear network system and can be easily accessed by all plant personnel. (author)

  10. Dukovany NPP maintenance management

    International Nuclear Information System (INIS)

    Siegel, F.

    2005-01-01

    Maintenance planning and management for the technological equipment of the Dukovany NPP are described. A Maintenance Control and Evaluation System has been developed and is in use to help manage the complex maintenance issue. Practical examples of outputs of the System, with a comprehensive use of the cost, reliability and safety related data, are presented. (author)

  11. IAEA activities on NPP personnel training and qualification

    International Nuclear Information System (INIS)

    Kossilov, A.

    1998-01-01

    Activities of IAEA concerning training and qualification of NPP personnel consider the availability of sufficient number of competent personnel which is one of the most critical requirements for safe and reliable NPP operation and maintenance. Competence of personnel is essential for reducing the frequency of events connected to human errors and equipment failures. The IAEA Guidebook on Nuclear Power Plant Personnel Training and its Evaluation incorporates the experience gained worldwide and provides recommendations on the use of SAT being the best practice for attaining and maintaining the qualification and competence of NPP personnel and for quality assurance of training

  12. Construction of large-thickness sand cushions for NPP foundations

    International Nuclear Information System (INIS)

    Krantsfel'd, Ya.L.; Losievskaya, I.K.; Kovalenko, R.P.; Mutalipov, A.

    1982-01-01

    A study is made on some technological peculiarities of preparation of NPP foundations and control methods of foundation density. As an example the experience of cement-sand foundation construction for two 900 MW power-units at the Koeberg South Africa NPP is briefly described. The experience of artificial foundation construction at this NPP indicates both the possibility of obtaining the required quality of cement-sand cushions and commercial construction of large volume of such cushions by acceptable rates and the necessity of unification of work quality characteristics

  13. A reliability evaluation method for NPP safety DCS application software

    International Nuclear Information System (INIS)

    Li Yunjian; Zhang Lei; Liu Yuan

    2014-01-01

    In the field of nuclear power plant (NPP) digital i and c application, reliability evaluation for safety DCS application software is a key obstacle to be removed. In order to quantitatively evaluate reliability of NPP safety DCS application software, this paper propose a reliability evaluating method based on software development life cycle every stage's v and v defects density characteristics, by which the operating reliability level of the software can be predicted before its delivery, and helps to improve the reliability of NPP safety important software. (authors)

  14. Estimation of the radiation risks for population in the process of the BN-600 power unit operation at the Beloyarsk NPP

    International Nuclear Information System (INIS)

    Koltik, I.I.; Oshkanov, N.N.

    2005-01-01

    Dose burdens on the population are the main criterion in estimating the radiological risks during NPP operation. Results of analysis of annual dose burdens on the population in the period of the BN-600 unit operation are presented. Data on individual and collective doses due to gas-aerosol and liquid effluents of radionuclides from the BN-600 unit on critical groups of population are presented. Data on collective doses due to other types of reactors are provided. It is shown that the risks stemming from the BN type reactors are approximately 2 orderers below the risks of channel-type and WWER-reactors [ru

  15. Current status of NPP generation IV

    International Nuclear Information System (INIS)

    Yohanes Dwi Anggoro; Dharu Dewi; Nurlaila; Arief Tris Yuliyanto

    2013-01-01

    Today development of nuclear technology has reached the stage of research and development of Generation IV nuclear power plants (advanced reactor systems) which is an innovative development from the previous generation of nuclear power plants. There are six types of power generation IV reactors, namely: Very High Temperature Reactor (VHTR), Sodium-cooled Fast Reactor (SFR), Gas-cooled Fast Reactor (GFR), Lead-cooled Fast Reactor (LFR), Molten Salt Reactor (MSR), and Super Critical Water-cooled Reactor (SCWR). The purpose of this study is to know the development of Generation IV nuclear power plants that have been done by the thirteen countries that are members of the Gen IV International Forum (GIF). The method used is review study and refers to various studies related to the current status of research and development of generation IV nuclear power. The result of this study showed that the systems and technology on Generation IV nuclear power plants offer significant advances in sustainability, safety and reliability, economics, and proliferation resistance and physical protection. In addition, based on the research and development experience is estimated that: SFR can be used optimally in 2015, VHTR in 2020, while NPP types GFR, LFR, MSR, and SCWR in 2025. Utilization of NPP generation IV said to be optimal if fulfill the goal of NPP generation IV, such as: capable to generate energy sustainability and promote long-term availability of nuclear fuel, minimize nuclear waste and reduce the long term stewardship burden, has an advantage in the field of safety and reliability compared to the previous generation of NPP and VHTR technology have a good prospects in Indonesia. (author)

  16. Safety Analysis Report for Ignalina NPP

    International Nuclear Information System (INIS)

    Negrivoda, G.

    1997-01-01

    In December 1994 an agreement was signed between the European Bank for Reconstruction and Development and the Republic of Lithuania for the grant of 32.86 MECU for the safety Improvement at Ignalina NPP. One of the conditions for the provision of the grant, was a requirement for an in-depth analysis of the safety level at Ignalina NPP in the scope and according to the standards acceptable for a western nuclear power plant, and to publish a Safety Analysis Report (SAR). The report should investigate and analyze any factor that could limit a safe operation of the plant, and provide recommendations for actual safety improvements. According to the agreement, Lithuania had to finalize the SAR until 31 December, 1995. The bank has also organized and financed investigation of safety at Ignalina NPP and preparation of the SAR. EBRD made an agreement with Sweden's Vattenfall, which subcontracted well-known companies from Canada, USA, Germany, etc., and also the Russian Research and Development Institute of Power Engineering (NIKIET), reactor designer of Ignalina NPP. The SAR is a very comprehensive document and contains about 8000 pages of text, diagrams and tables. The main findings of the SAR are provided in the article. A large number of discrepancies with modern rules and western practices was detected, but they were not proved to be serious enough to require reactors shutdown. Based on the recommendations of the SAR Ignalina NPP has worked out Safety Improvement Program No. 2 (SIP-2), which is planned for three years and will cost 486 MLT. (author)

  17. Quantitative analysis of psychological personality for NPP operators

    International Nuclear Information System (INIS)

    Gao Jia; Huang Xiangrui

    1998-01-01

    The author introduces the relevant personality quantitative psychological research work carried out by 'Prognoz' Laboratory and Taiwan, and presents the primary results of the research for Chinese Nuclear Power Plant (NPP) operator's psychological personality assessment, which based on the survey of MMPI, and presents the main contents for the personality quantitative psychological research in NPP of China. And emphasizes the need to carry out psychological selection and training in nuclear industry

  18. Jose Cabrera NPP severe accident management activities

    International Nuclear Information System (INIS)

    Blanco, J.; Almeida, P.; Saiz, J.; Sastre, J.L.; Delgado, R.

    1998-01-01

    To prepare a common acting plan with respect to Severe Accident Management, in 1994 was founded the severe accident management ''ad-hoc'' working group from the Spanish Westinghouse PWR Nuclear Power Plant Owners Group. In this group actively collaborated the Jose Cabrera NPP Training Centre and the Department of Nuclear Engineering of UNION FENOSA. From this moment, Jose Cabrera NPP began the planning of its specific Severe Accident Management Program, which main point are Severe Accident Management Guidelines (SAMG). To elaborate this guidelines, the Spanish translation of Westinghouse Owners Group (WOG) Severe Accident Management Guidelines were considered the reference documents. The implementation of this Guidelines to Jose Cabrera NPP started on January 1997. Once the specific guidelines have been implemented to the plant, training activities for the personnel involved in severe accident issues will be developed. To prepare the training exercises MAAP4 code will be used, and with this intention, a specific Jose Cabrera NPP MAAP-GRAAPH screen has been developed. Furthermore, a wide selection of MAAP input files for the simulation of different scenarios and accidental events is available. (Author)

  19. Decommissioning Study of Oskarshamn NPP

    International Nuclear Information System (INIS)

    Larsson, Helena; Anunti, Aake; Edelborg, Mathias

    2013-06-01

    By Swedish law it is the obligation of the nuclear power utilities to satisfactorily demonstrate how a nuclear power plant can be safely decommissioned and dismantled when it is no longer in service as well as calculate the estimated cost of decommissioning of the nuclear power plant. Svensk Kaernbraenslehantering AB (SKB) has been commissioned by the Swedish nuclear power utilities to meet the requirements of current legislation by studying and reporting on suitable technologies and by estimating the costs of decommissioning and dismantling of the Swedish nuclear power plants. The present report is an overview, containing the necessary information to meet the above needs, for Oskarshamn NPP. Information is given for the plant about the inventory of materials and radioactivity at the time for final shutdown. A feasible technique for dismantling is presented and the waste management is described and the resulting waste quantities are estimated. Finally a schedule for the decommissioning phase is given and the costs associated are estimated as a basis for funding

  20. Decommissioning study of Forsmark NPP

    International Nuclear Information System (INIS)

    Anunti, Aake; Larsson, Helena; Edelborg, Mathias

    2013-06-01

    By Swedish law it is the obligation of the nuclear power utilities to satisfactorily demonstrate how a nuclear power plant can be safely decommissioned and dismantled when it is no longer in service as well as calculate the estimated cost of decommissioning of the nuclear power plant. Svensk Kaernbraenslehantering AB (SKB) has been commissioned by the Swedish nuclear power utilities to meet the requirements of current legislation by studying and reporting on suitable technologies and by estimating the costs of decommissioning and dismantling of the Swedish nuclear power plants. The present report is an overview, containing the necessary information to meet the above needs, for the Forsmark NPP. Information is given for the plant about the inventory of materials and radioactivity at the time for final shutdown. A feasible technique for dismantling is presented and the waste management is described and the resulting waste quantities are estimated. Finally a schedule for the decommissioning phase is given and the costs associated are estimated as a basis for funding

  1. Decommissioning Study of Oskarshamn NPP

    Energy Technology Data Exchange (ETDEWEB)

    Larsson, Helena; Anunti, Aake; Edelborg, Mathias [Westinghouse Electric Sweden AB, Vaesteraas (Sweden)

    2013-06-15

    By Swedish law it is the obligation of the nuclear power utilities to satisfactorily demonstrate how a nuclear power plant can be safely decommissioned and dismantled when it is no longer in service as well as calculate the estimated cost of decommissioning of the nuclear power plant. Svensk Kaernbraenslehantering AB (SKB) has been commissioned by the Swedish nuclear power utilities to meet the requirements of current legislation by studying and reporting on suitable technologies and by estimating the costs of decommissioning and dismantling of the Swedish nuclear power plants. The present report is an overview, containing the necessary information to meet the above needs, for Oskarshamn NPP. Information is given for the plant about the inventory of materials and radioactivity at the time for final shutdown. A feasible technique for dismantling is presented and the waste management is described and the resulting waste quantities are estimated. Finally a schedule for the decommissioning phase is given and the costs associated are estimated as a basis for funding.

  2. Decommissioning study of Forsmark NPP

    Energy Technology Data Exchange (ETDEWEB)

    Anunti, Aake; Larsson, Helena; Edelborg, Mathias [Westinghouse Electric Sweden AB, Vaesteraas (Sweden)

    2013-06-15

    By Swedish law it is the obligation of the nuclear power utilities to satisfactorily demonstrate how a nuclear power plant can be safely decommissioned and dismantled when it is no longer in service as well as calculate the estimated cost of decommissioning of the nuclear power plant. Svensk Kaernbraenslehantering AB (SKB) has been commissioned by the Swedish nuclear power utilities to meet the requirements of current legislation by studying and reporting on suitable technologies and by estimating the costs of decommissioning and dismantling of the Swedish nuclear power plants. The present report is an overview, containing the necessary information to meet the above needs, for the Forsmark NPP. Information is given for the plant about the inventory of materials and radioactivity at the time for final shutdown. A feasible technique for dismantling is presented and the waste management is described and the resulting waste quantities are estimated. Finally a schedule for the decommissioning phase is given and the costs associated are estimated as a basis for funding.

  3. Co-ordinated research programme on benchmark study for the seismic analysis and testing of WWER-type nuclear power plants. V. 1. Data related to sites and plants: Paks NPP, Kozloduy NPP. Working material

    International Nuclear Information System (INIS)

    1995-01-01

    The Co-ordinated research programme on the benchmark study for the seismic analysis and testing of WWER-type nuclear power plants was initiated subsequent to the request from representatives of Member States. The conclusions adopted at the Technical Committee Meeting on Seismic Issues related to existing nuclear power plants held in Tokyo in 1991 called for the harmonization of methods and criteria used in Member States in issues related to seismic safety. The Consulltants' Meeting which followed resulted in producing a working document for CRP. It was decided that a benchmark study is the most effective way to achieve the principal objective. Two types of WWER reactors (WWER-440/213 and WWER-1000) were selected as prototypes for the benchmark exercise to be tested on a full scale using explosions and/or vibration generators. The two prototypes are Kozloduy Units 5/6 for WWER-1000 and Paks for WWER-440/213 nuclear power plants. This volume of Working material contains reports on data related to sites and NPPs Paks and Kozloduy

  4. Co-ordinated research programme on benchmark study for the seismic analysis and testing of WWER-type nuclear power plants. V. 1. Data related to sites and plants: Paks NPP, Kozloduy NPP. Working material

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-07-01

    The Co-ordinated research programme on the benchmark study for the seismic analysis and testing of WWER-type nuclear power plants was initiated subsequent to the request from representatives of Member States. The conclusions adopted at the Technical Committee Meeting on Seismic Issues related to existing nuclear power plants held in Tokyo in 1991 called for the harmonization of methods and criteria used in Member States in issues related to seismic safety. The Consulltants' Meeting which followed resulted in producing a working document for CRP. It was decided that a benchmark study is the most effective way to achieve the principal objective. Two types of WWER reactors (WWER-440/213 and WWER-1000) were selected as prototypes for the benchmark exercise to be tested on a full scale using explosions and/or vibration generators. The two prototypes are Kozloduy Units 5/6 for WWER-1000 and Paks for WWER-440/213 nuclear power plants. This volume of Working material contains reports on data related to sites and NPPs Paks and Kozloduy.

  5. Experiences in the implementation of the Coaching project in the nuclear power plant of Laguna Verde (NPP-L V); Experiencias en la implementacion del proyecto Coaching en la Central Nucleoelectrica Laguna Verde (CNLV)

    Energy Technology Data Exchange (ETDEWEB)

    Mendez M, H. I., E-mail: hugo.mendez01@cfe.gob.mx [Comision Federal de Electricidad, Central Nucleoelectrica Laguna Verde, Departamento del Centro de Entrenamiento, Carretera Cardel-Nautla Km 42.5, Alto Lucero, Veracruz (Mexico)

    2012-10-15

    This document has the purpose of to share acquired experiences during the implementation of the Coaching project focused the training of supervisors and directive personnel of the nuclear power plant of Laguna Verde (NPP-L V). Derived of the improvement areas identified by the supervisor organization of the nuclear power stations WANO (World Association Nuclear of Operators) and of the auto-evaluations realized by the expert personnel of the same power station that based on external experiences carried out through the Benchmarking (comparison with other power stations) they have reflected the necessity to activate a training process in Coaching with a practical focus toward the directive and supervisor personnel in the power station. By means of the observation of the personnel's acting so much in the control rooms like in different areas, three focus areas have been identified for the training in Coaching, these are the personnel's motivation, the organizational communication so much in vertical form as horizontal and the perception of confidence lack among directive, supervisors, operators and technicians. The plan focused in the abilities training of Coaching with practical sense was development, supported with an evaluation of 360 grades as tool of competitions development through a computer application e-Coaching. The use of application and Coaching following techniques facilitated the conformation of the practical focus, same that are of continuous use starting from the training of the supervisor and directive personnel. (Author)

  6. AGNES - safety reassessment of Paks NPP

    International Nuclear Information System (INIS)

    Gado, J.

    1995-01-01

    The main goal of the AGNES (Advanced General and New Evaluation of Safety) project for the reassessment of the safety of Paks Nuclear Power Plant, Hungary, was to improve the safety culture of the technology at Paks. A report was prepared on the reassessment of the Paks NPP safety. The analysis was divided into four groups: systems analysis, analysis of design basis accidents, severe accident analysis, and level 1 probabilistic safety analysis. Proposed safety enhancement measures are discussed. (N.T.)

  7. Using bentonite for NPP liquid waste treatment

    International Nuclear Information System (INIS)

    Bui Dang Hanh

    2015-01-01

    During operation, nuclear power plants (NPPs) release a large quantity of water waste containing radionuclides required treatment for protection of the radiation workers and the environment. This paper introduces processes used to treat water waste from Paks NPP in Hungary and it also presents the results of a study on the use of Vietnamese bentonite to remove radioactive Caesium from a simulated water waste containing Cs. (author)

  8. Sitting Safety Aspects of Second Romanian NPP

    International Nuclear Information System (INIS)

    Mauna, T.

    2010-01-01

    The first Romanian NPP CANDU 6 type reactor gone to erection in 1980 on Cernavoda site planned to have 5 units like the Wolsong applied design project for nuclear island. For the BOP parts the ASALDO-GE project was applied with the careful about the interface connection NSP requirements. The new NPP sitting studies began from 1982 in a serious manner as first part on Nuclear Power Plant Romanian Program adopted by political and governmental authorities at the time. For develop the all package of the studies in concordance with the first IAEA Safety Standards recommendations. Till the 1982 the first mission of design and research multi-branch of specialists team was to adapt the NPP Cernavoda project having a open water cooling circuit to the new parameters of close water cooling circuit. But the team was looking at the other type of NPP for sitting. Also in the same time was studied the possibility of NSP foundation on hard less or soft soil foundation strata in connection with safety aspects. The close circuit of cooling water means others parameters of systems and need very large cooling towers. Also must be reconsidering the safety systems design and performance as new solution. In the south of Transylvania historical region in Romania the Olt River run from west to east having medium multi annual flow around 70 m3/s. The Olt River has a chain of small hydropower in operation and other planned. From geological and geophysical points of view two main faults, along the Olt river valley, one of this having seismically small activities was detected. Site region geotechnical studies show small quantity underground natural gas, salt and peat. The initial nuclear program has imposed 4 NPP units site near Olt River. Taking into account the orogenesis, water cooling needs and other local feature can't be built more than two NPP units on a site. This paper tries to reconsider the old analysis from the last IAEA Safety Standards point of view taking into account the new

  9. Contamination control by laundry monitor at NPP

    International Nuclear Information System (INIS)

    Singh, Vishwanath P.; Rana, P.K.; Lokeshwar Rao, S.; Managanvi, S.S.

    2010-01-01

    The operation of nuclear power reactor produces electricity as well as small quantity of radioactive waste as gaseous, liquid and solid. The waste contains radionuclides produced by fission and activation in reactor systems with wide spectrum of energy and half life. The long-lived nuclides Sr, Cs, Ba, Iodine and Co etc compared to short-lived are important in view of radiation protection. The radioactive contamination on the materials, human body or other places where it is undesirable is enormously harmful to workers at Nuclear Power Plant (NPP). The spread of radioactive from controlled areas is very complex problem for power reactor plant management

  10. Summary of NPP personnel training in Czech Republic

    International Nuclear Information System (INIS)

    1996-01-01

    The preparation of NPP personnel is one of the most important phases of the process of construction, commissioning, operation and maintenance of nuclear power facilities. The objective is to improve personnel abilities so that they would be able to assure reliable, safe and economic operation of these facilities with high investment costs. It is the purpose of Nuclear Training Centre Brno (NTC Brno) to provide training and services which are responsive to the technological demands and emerging educational standards and criteria of the NPP and the nuclear industry. Fulfilling this purpose is a challenging task. The staff of NTC Brno, in a joint effort with NPP Dukovany and NPP Temelin, has responded to the challenge with comprehensive programs aimed at meeting customers needs. The programs are broadly based, yet flexible so that they can incorporate specific customer requirements

  11. Programmes design for Bohunice NPP personnel other than control room operators

    International Nuclear Information System (INIS)

    Kalincik, L.

    2002-01-01

    This paper deals with project development of training programmes for non-licenced NPP personnel-masters, field operators, maintenance and technical supporting personnel. The programme development focuses on the part stage and on the job training at NPP. Bohunice NPP belongs to plants with higher specific number of personnel per installed power capacity. This factor also influenced the choice of programmes design. Undermentioned procedure is one of various approaches to SAT exploitation for training programmes design. (author)

  12. Human Resources Training Requirement on NPP Operation and Maintenance

    International Nuclear Information System (INIS)

    Nurlaila; Yuliastuti

    2009-01-01

    This paper discussed the human resources requirement on Nuclear Power Plant (NPP) operation and maintenance (O&M) phase related with the training required for O&M personnel. In addition, this paper also briefly discussed the availability of training facilities domestically include with some suggestion to develop the training facilities intended for the near future time in Indonesia. This paper was developed under the assumptions that Indonesia will build twin unit of NPP with capacity 1000 MWe for each using the turnkey contract method. The total of NPP O&M personnel were predicted about 692 peoples which consists of 42 personnel located in the head quarter and the rest 650 people work at NPP site. Up until now, Indonesia had the experience on operating and maintaining the nonnuclear power plant and several research reactors namely Kartini Reactor Yogyakarta, Triga Mark II Reactor Bandung, and GA Siwabessy Reactor Serpong. Beside that, experience on operating and maintaining the NPP in other countries would act as one of the reference to Indonesia in formulating an appropriate strategy to develop NPP human resources particularly in O&M phases. Education and training development program could be done trough the cooperation with vendor candidates. (author)

  13. The Influence of Quality Assurance and Supportive Supervision on the Quality of Medical Care in Children’s Hospitals of the Municipal Level of the Rostov Region

    Directory of Open Access Journals (Sweden)

    Tatiana V. Kulichenko

    2017-01-01

    Full Text Available Background. Improving the quality of medical care is the absolute priority of the World Health Organization and all socially-oriented ministries and departments around the world.Objective. Our aim was to evaluate the effectiveness of quality  assurance and supportive supervision in municipal hospitals to improve the quality of medical care for children (by the example of the Rostov region.Methods. The open observational study included 10 second-level hospitals in the Rostov Region. At the start of the project, the quality of inpatient care for children in the region was audited based on recommendations and tools of the World Health Organization, and training of medical personnel was organized. Monitoring visits to hospitals were carried out by experts every 3 months (supportive supervision. Reaudit of the quality of care was conducted a year later.Results. As a result of regular quality assurance and supportive supervision of hospitals during the first year of operation, such indicators of the quality of medical care as the availability of medical equipment for emergency care for children, the infrastructure of children’s departments, the triage and provision of emergency care in children’s departments, managing patients with various acute conditions (fever, diarrhea, respiratory diseases, supporting care, internal quality assurance, accessibility to standards of care and clinical guidelines for the diagnosis and treatment of various diseases, respect for children’s rights were significantly (p < 0.05 improved.Conclusion. Supportive supervision and regular external quality assurances of hospitals contribute to a rapid increase in the quality of medical care for children.

  14. Revision of Krsko NPP Quality Assurance Plan

    International Nuclear Information System (INIS)

    Biscan, R.; Fifnja, I.; Kavsek, D.

    2012-01-01

    International standards from nuclear power plant operation area are being frequently upgraded and revised in accordance with the continuous improvement philosophy. This philosophy applies also to the area of Quality Assurance, which has also undergone significant improvement since the early 1950s. Besides just nuclear industry, there are also other international quality standards that are being continuously developed and revised, bringing needs for upgrades also in the nuclear application. Since the beginning of Krsko NPP construction, the overall Quality Assurance program and its applicable procedures were in place to assure that all planned and systematic actions necessary to provide adequate confidence that an item or service will satisfy given requirements to quality, are in place. The overall requirements for quality as one of the major objectives for Krsko NPP operation are also set forth in the Updated Safety Analyses Report, the document that serves as a base for operating license. During more than 30 years of Krsko NPP operation, the quality requirements and related documents were revised and upgraded in several attempts. The latest revision 6 of QD-1, Quality Assurance Plan was issued during the year 2011. The bases for the revision were: Changes of the Slovenian regulatory requirements (ZVISJV, JV5, JV9?), Changes of Krsko NPP licensing documents (USAR section 13?), SNSA inspection requirements, Changes of international standards (IAEA, ISO?), Conclusions of first PSR, Implementation of ISO standards in Krsko NPP (ISO14001, ISO17025), Changes of plant procedures, etc. One of the most obvious changes was the enlargement of the QA Plan scope to cover interdisciplinary areas defined in the plant management program MD-1, such as Safety culture, Self-assessment, Human performance, Industrial Safety etc. The attachment of the QA Plan defining relationships between certain standards was also updated to provide matrix for better correlation of requirements of

  15. The NPP Isar comprehensive Aging Management Program

    International Nuclear Information System (INIS)

    Zander, Andre; Ertl, Stefan

    2012-01-01

    The majority of System, Structure and Components (SSC) in a nuclear power plants are designed to experience a service life, which is far above the intended design life. In most cases, only a small percentage of SSCs are subject to significant aging effects, which may affect the integrity or the function of the component. The process of aging management (AM) has the objective to monitor and control degradation effects which may compromise safety functions of the plant. And furthermore, to ensure, that testing and maintenance programs sufficiently provide preventive measures to control degradation effects. Safety-related aspects and the targeted high availability of the power plant as well as the requirements stipulated by German regulatory authorities prompted the operator of NPP ISAR to introduce an aging surveillance program. The NPP Isar as well as the German NPPs has to be following in the scope of aging management the KTA 1403 guideline. The NPP Isar surveillance program based on the KTA 1403 guideline covers the following aspects: - Scoping and screening of safety relevant Systems, Structures and Components (SSC); - Identification of possible degradation mechanisms for safety relevant SSC; - Ensure, that testing and maintenance programs sufficiently provide preventive measures to control degradation effects; - Transferability check of industry experience (internal and external events); - Annual preparation of an AM status report. (author)

  16. Optimization of radiation protection at Bohunice NPP

    International Nuclear Information System (INIS)

    Dobis, L.; Svitek, J.

    2003-01-01

    Bohunice Nuclear Power Plant is situated in south - western part of Slovakia about 50 km away from Bratislava. There are four PWR reactors 440 MW e each - two units with reactors WWER - 230 (V1 NPP) and two units with WWER - 213 (V2 NPP). requirements for the optimization process are given in the mentioned Code No.12 of Ministry of Health. Code 12 stipulates the technical and organizational requirements for proving the Rational Achievable Level (RAL) of radiation protection. This level can be proved by means of the comparison of the dose distribution to the costs of protection. An example of two figures of dose constraints is: collective dose 20 man mSv for the specific task; individual exposure 1 mSv per day. The values of the financial equivalents of personal exposure - so called the alpha coefficients - are used for the calculation of the benefit of proposed measures. Impact of legislative changes into Bohunice NPP and optimization process are presented. Apparently the new law and the associate code created a base of transparent and understandable policy of radiation protection and optimization in Slovak Republic. The radiation protection legislative was implemented into the praxis and persons became familiar with it. Defining clear and unambiguous terms facilitated the communication between users and the regulatory body - State Health Institute. Optimization was generally accepted by the workers and managers and began to be a part of safety culture of operation at nuclear power plants. (authors)

  17. LTO License Application Project NPP Borssele

    International Nuclear Information System (INIS)

    Jong, A.E. de; Blom, F.J.; Leilich, J.

    2012-01-01

    Borssele NPP plans to extend its operating life with 20 years until 2034. Borssele has started the project LTO 'bewijsvoering' (LTO 'Justification') in order to meet the requirements of the Dutch regulator. The outline of the project is based on IAEA safety guide 57 'Safe Long Term Operation of Nuclear Power Plants'. This paper describes the contents and coherence of the different parts in the project and how these respond to the IAEA guidelines on LTO. The goal of the project LTO 'bewijsvoering' is to ensure that safety and safety relevant systems, structures and components continue to perform their intended functions during long term operation. The outcome of the project LTO 'bewijsvoering' will be used for a license change application and this will be submitted to the Dutch regulator KFD for approval of prolonged operation of Borssele NPP after 2013. (author)

  18. Co-ordinated research programme on benchmark study for the seismic analysis and testing of WWER-type nuclear power plants. V. 4C. Paks NPP: Analysis and testing. Working material

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1996-07-01

    The Co-ordinated research programme on the benchmark study for the seismic analysis and testing of WWER-type nuclear power plants was initiated subsequent to the request from representatives of Member States. The conclusions adopted at the Technical Committee Meeting on Seismic Issues related to existing nuclear power plants held in Tokyo in 1991 called for the harmonization of methods and criteria used in Member States in issues related to seismic safety. The Consulltants' Meeting which followed resulted in producing a working document for CRP. It was decided that a benchmark study is the most effective way to achieve the principal objective. Two types of WWER reactors (WWER-440/213 and WWER-1000) were selected as prototypes for the benchmark exercise to be tested on a full scale using explosions and/or vibration generators. The two prototypes are Kozloduy Units 5/6 for WWER-1000 and Paks for WWER-440/213 nuclear power plants. This volume of Working material involves comparative analysis of the seismic analysis results of the reactor building for soft soil conditions, derivation of design response spectra for components and systems; and upper range design response spectra for soft soil site conditions at Paks NPP.

  19. Co-ordinated research programme on benchmark study for the seismic analysis and testing of WWER-type nuclear power plants. V. 4C. Paks NPP: Analysis and testing. Working material

    International Nuclear Information System (INIS)

    1996-01-01

    The Co-ordinated research programme on the benchmark study for the seismic analysis and testing of WWER-type nuclear power plants was initiated subsequent to the request from representatives of Member States. The conclusions adopted at the Technical Committee Meeting on Seismic Issues related to existing nuclear power plants held in Tokyo in 1991 called for the harmonization of methods and criteria used in Member States in issues related to seismic safety. The Consulltants' Meeting which followed resulted in producing a working document for CRP. It was decided that a benchmark study is the most effective way to achieve the principal objective. Two types of WWER reactors (WWER-440/213 and WWER-1000) were selected as prototypes for the benchmark exercise to be tested on a full scale using explosions and/or vibration generators. The two prototypes are Kozloduy Units 5/6 for WWER-1000 and Paks for WWER-440/213 nuclear power plants. This volume of Working material involves comparative analysis of the seismic analysis results of the reactor building for soft soil conditions, derivation of design response spectra for components and systems; and upper range design response spectra for soft soil site conditions at Paks NPP

  20. Co-ordinated research programme on benchmark study for the seismic analysis and testing of WWER-type nuclear power plants. V. 4D. Paks NPP: Analysis and testing. Working material

    International Nuclear Information System (INIS)

    1996-01-01

    The Co-ordinated research programme on the benchmark study for the seismic analysis and testing of WWER-type nuclear power plants was initiated subsequent to the request from representatives of Member States. The conclusions adopted at the Technical Committee Meeting on Seismic Issues related to existing nuclear power plants held in Tokyo in 1991 called for the harmonization of methods and criteria used in Member States in issues related to seismic safety. The Consulltants' Meeting which followed resulted in producing a working document for CRP. It was decided that a benchmark study is the most effective way to achieve the principal objective. Two types of WWER reactors (WWER-440/213 and WWER-1000) were selected as prototypes for the benchmark exercise to be tested on a full scale using explosions and/or vibration generators. The two prototypes are Kozloduy Units 5/6 for WWER-1000 and Paks for WWER-440/213 nuclear power plants. This volume of Working material contains reports on seismic margin assessment and earthquake experience based methods for WWER-440/213 type NPPs; structural analysis and site inspection for site requalification; structural response of Paks NPP reactor building; analysis and testing of model worm type tanks on shaking table; vibration test of a worm tank model; evaluation of potential hazard for operating WWER control rods under seismic excitation

  1. Cernavoda NPP Knowledge Transfer

    International Nuclear Information System (INIS)

    Valache, C. M.

    2016-01-01

    Full text: The paper presents a description of the Knowledge Transfer (KT) process implemented at Cernavoda NPP, its designing and implementation. It is underlined that applying a KT approach should improve the value of existing processes of the organization through: • Identifying business, operational and safety risks due to knowledge gaps, • Transfer of knowledge from the ageing workforce to the peers and/or the organization, • Continually learning from successes and failures of individual or teams, • Convert tacit knowledge to explicit knowledge, • Improving operational and safety performance through creating both new knowledge and better access to existing knowledge. (author

  2. Operation safety at Ignalina NPP

    International Nuclear Information System (INIS)

    Zheltobriukh, G.

    1999-01-01

    An improvement of operational safety at Ignalina NPP covers: improvement of management structure and safety culture; symptom-based emergency operating procedures; staff training and full scope simulator; program of components ageing; metal inspection; improvement of fire safety. The first plan of Ignalina NPP Safety culture development for 1997 purposed to the SAR recommendation implementation was prepared and approved by the General Director

  3. Preparation for Ignalina NPP decommissioning

    International Nuclear Information System (INIS)

    Medeliene, D.

    2004-01-01

    Latest developments of atomic energy in Lithuania, works done to prepare Ignalina NPP for final shutdown and decommissioning are described. Information on decommissioning program for Ignalina NPP unit 1, decommissioning method, stages and funding is presented. Other topics: radiation protection, radioactive waste management and disposal. Key facts related to nuclear energy in Lithuania are listed

  4. Procedure for Application of Software Reliability Growth Models to NPP PSA

    International Nuclear Information System (INIS)

    Son, Han Seong; Kang, Hyun Gook; Chang, Seung Cheol

    2009-01-01

    As the use of software increases at nuclear power plants (NPPs), the necessity for including software reliability and/or safety into the NPP Probabilistic Safety Assessment (PSA) rises. This work proposes an application procedure of software reliability growth models (RGMs), which are most widely used to quantify software reliability, to NPP PSA. Through the proposed procedure, it can be determined if a software reliability growth model can be applied to the NPP PSA before its real application. The procedure proposed in this work is expected to be very helpful for incorporating software into NPP PSA

  5. The landscape basis of the complex monitoring of 30-km zone of NPP

    International Nuclear Information System (INIS)

    Malisheva, L.L.; Romanchuk, S.P.; Schur, U.V.; Rybalko, S.I.; Proskura, N.I.; Lury, D.I.

    1992-01-01

    This publication reviews works on the problem of creation the landscape basis of complex monitoring in 30 km zone of NPP(nuclear power plants). The objectives, subject and designation of monitoring system are considered. The monitoring network and organization of systematical observations are justified. The structure of radiation monitoring in NPP 30 km zone is considered in details. (author)

  6. The main trends of work on ageing and lifetime management of NPP

    International Nuclear Information System (INIS)

    Dragunov, Yu.

    1994-01-01

    The main trends of work on aging and lifetime management of nuclear power plants(NPP) in Russia are described including Russian research programs on NPP components lifetime assurance, technical assistance program for CIS, measures for life extension of reactor pressure vessels, steam generator collectors and components for advances reactor plants. Figs and tabs

  7. Approaches to the mathematical description of NPP operational safety management and oversight

    International Nuclear Information System (INIS)

    Bilej, D.V.; Berzhanskij, S.V.

    2014-01-01

    The paper presents analysis of features related to NPP operational safety management and oversight. According to analysis results, approaches are proposed to perform mathematical description of specific processes and to develop a scale for management to the current safety level as regards NPP power generation. Proposed approaches are making experimental equations and process approach of ISO-9001 quality system

  8. On improving the NPP construction long-term planning

    International Nuclear Information System (INIS)

    Solov'ev, M.M.

    1980-01-01

    General approaches to solving the problems of long-term planning of the construction-mounting work volume and introduction of power capacities at different paces of power unit commission and norms of construction time are considered. Problems associated with location and development of subsidiary industries providing NPP construction are discussed. It is shown that decrease of WWER-1000 reactor type NPP construction time from 24 to 12 months results in reduction of required high-skilled engineers, managerial staff, unique construction mechanisms and engines as well as in improvement of conditions for conducting measures on work arrangement during preparation of construction industry and mounting of the first assemblies

  9. Problems of complex automation of process at a NPP

    International Nuclear Information System (INIS)

    Naumov, A.V.

    1981-01-01

    The importance of theoretical investigation in determining the level and quality of NPP automation is discussed. Achievements gained in this direction are briefly reviewed on the example of domestic NPPs. Two models of the problem solution on function distribution between the operator and technical means are outlined. The processes subjected to automation are enumerated. Development of the optimal methods of power automatic control of power units is one of the most important problems of NPP automation. Automation of discrete operations especially during the start-up, shut-down or in imergency situations becomes important [ru

  10. Start-up of NPP Krsko; Pokusno obratovanje NE Krsko

    Energy Technology Data Exchange (ETDEWEB)

    Spiler, J; Aralica, J [Nuklearna elektrana Krsko, Krsko (Yugoslavia)

    1984-07-01

    The report describes a review of start-up program and its realisation. There are also described some more significant start-up results with their evaluation. The most significant operation criteria are compared between NPP Krsko and other similar plants in the world. The comparison shows that after the first contractors and operation personnel efforts have been accomplished, our first nuclear power plant is a safe and reliable source of electric power. At the end there are listed NPP Krsko start-up recommendations and experience. (author)

  11. International benchmark for coupled codes and uncertainty analysis in modelling: switching-Off of one of the four operating main circulation pumps at nominal reactor power at NPP Kalinin unit 3

    International Nuclear Information System (INIS)

    Tereshonok, V. A.; Nikonov, S. P.; Lizorkin, M. P.; Velkov, K; Pautz, A.; Ivanov, V.

    2008-01-01

    The paper briefly describes the Specification of an international NEA/OECD benchmark based on measured plant data. During the commissioning tests for nominal power at NPP Kalinin Unit 3 a lot of measurements of neutron and thermo-hydraulic parameters have been carried out in the reactor pressure vessel, primary and the secondary circuits. One of the measured data sets for the transient 'Switching-off of one Main Circulation Pump (MCP) at nominal power' has been chosen to be applied for validation of coupled thermal-hydraulic and neutron-kinetic system codes and additionally for performing of uncertainty analyses as a part of the NEA/OECD Uncertainty Analysis in Modeling Benchmark. The benchmark is opened for all countries and institutions. The experimental data and the final specification with the cross section libraries will be provided to the participants from NEA/OECD only after official declaration of real participation in the benchmark and delivery of the simulated results of the transient for comparison. (Author)

  12. Tritium liquid effluents from the Krsko NPP

    International Nuclear Information System (INIS)

    Savli, S.; Krizman, M.; Nemec, T.; Cindro, M.; Stritar, A.; Vokal Nemec, B.; Janzekovic, H.

    2007-01-01

    In the past, 12-months' fuel cycles in the Krsko NPP had not caused any problems regarding compliance with its Technical Specifications and license limits on liquid tritium releases (20 TBq/year, 8 TBq/three months). The first 18-months' fuel cycle, which was introduced in 2004, required fuel with higher enrichment, higher boron concentration in the primary coolant and more fuel rods with burnable poisons. In 2005, the NPP operated without refueling outage for the whole year and produced the highest amount of energy so far. Due to these facts and a few unplanned shutdowns and power reductions, production of tritium and releases increased strongly in 2005. As a result, the Krsko NPP hardly succeeded to stay within regulatory limits on tritium releases. However, the three-months' limit was exceeded in the first quarter of 2006. On the basis of conclusions acquired from the SNSA's study and practice of other European countries the SNSA considerably increased the annual limit of permitted liquid tritium releases (from 20 TBq to 45 TBq) and abolished the three-months' limit. At the same time, the SNSA reduced the limit of fission and activation products by halves. (author)

  13. Supercompaction of radioactive waste at NPP Krsko

    International Nuclear Information System (INIS)

    Fink, K.; Sirola, P.

    1996-01-01

    The problem of radioactive waste management is both scientifically and technically complex and also deeply emotional issue. In the last twenty years the first two aspects have been mostly resolved up to the point of safe implementation. In the Republic of Slovenia, certain fundamentalist approaches in politics and the use of radioactive waste problem as a political tool, brought the final radioactive repository siting effort to a stop. Although small amounts of radioactive waste are produced in research institutes, hospitals and industry, major source of radioactive waste in Slovenia is the Nuclear Power Plant Krsko. When Krsko NPP was originally built, plans were made to construct a permanent radioactive waste disposal facility. This facility was supposed to be available to receive waste from the plant long before the on site storage facility was full. However, the permanent disposal facility is not yet available, and it became necessary to retain the wastes produced at the plant in the on-site storage facility for an extended period of time. Temporary radioactive storage capacity at the plant site has limited capacity and having no other options available NPP Krsko is undertaking major efforts to reduce waste volume generated to allow normal operation. This article describes the Radioactive Waste Compaction Campaign performed from November, 1994 through November, 1995 at Krsko NPP, to enhance the efficiency and safety of storage of radioactive waste. The campaign involved the retrieval, segmented gamma-spectrum measurement, dose rate measurement, compaction, re-packaging, and systematic storage of radioactive wastes which had been stored in the NPP radioactive waste storage building since plant commissioning. (author)

  14. Perspectives of Living PSA in NPP Krsko

    International Nuclear Information System (INIS)

    Vrbanic, I.; Kastelan, M.

    1996-01-01

    Nuclear power plant Krsko has completed the Level 1/Level 2 Probabilistic Safety Analysis (PSA) for internal initiating events and is in the process of completing the same for the external initiators. The analysis completed up to now has provided a valuable insight into a plant risk profile. In NPP Krsko there is a plan to use the PSA model as a permanent tool for the risk based applications and incorporate it into a decision making process. In order to achieve this there is a need to permanently maintain the PSA model in a manner that it reflects both the plan configuration/design at a time point and the operational experience up to the time point. All the activities aimed toward keeping the PSA model up-to-dated in this sense are usually referred to as a Living PSA (LPSA) program. NPP Krsko is in the process of defining and proceduralizing a LPSA program that would be plant specific and based on known world practices. Further, in order to be suitable for risk based applications the PSA model must be flexible in a sense that modifications to the base case model may be done easily and requantifications performed quickly as to evaluate various conditions imposed by real or hypothetical situations. NPP Krsko PSA model has been based on licensing type software. The requirements specified above dictate the transfer of the overall model to an application oriented software of newer generation with larger capabilities. The transfer becomes a part of a mentioned ongoing effort aimed at establishing LPSA model and concept. The paper present this effort and the perspectives of LPSA concept and risk based applications in NPP Krsko. (author)

  15. Current technological trends in development of NPP systems

    International Nuclear Information System (INIS)

    Florescu, Gheorghe; Panaitescu, Valeriu

    2010-01-01

    The recent nuclear research issues look for new technologies and continuous progress in finding different and efficient solutions for sustained and upraising energy demand. The trend of increasing energy consumption and occurring of new and large consumers, especially from Asian countries, imposes finding of new means for clean, large scale and sustained energy production. NPPs availability was continuously monitored and improved; at the same time the safety of the nuclear energy production was under surveillance. The present development of the new technologies, the discoveries of new materials and development of efficient technological processes offer the opportunities for their appropriate implementation and use in the NPP system configurations and functioning/operation. The new technologies and scientific discoveries, and also the international cooperation, offer the opportunities to mitigate the actual barriers in order to cumulate and use advanced energy production, to find new energy sources and to build improved, reliable and safe power plants. The monitoring systems, intelligent sensors and SSCs, nanotechnologies and new/intelligent materials constitute the main ways for improvement of the NPP systems configuration and processes. The paper presents: - The state of the art in the level of the currently applied technologies for nuclear power systems development; - The actual technological limits that need to be over passed for improving the NPP systems ; - The main systems that need improvement and reconfiguration for development of currently operating NPPs as well as raising the operation efficiency, availability and total safety; - The actual energy production issues; - The key arguments in sustaining the R and D new NPP systems development; - Future trends in NPP development; - The limitations in industrial processes knowledge and use. Appropriate R and D in the field of NPP systems have specific characteristics that were considered in paper completion

  16. The seismic reassessment Mochovce NPP

    International Nuclear Information System (INIS)

    Baumeister, P.

    2004-01-01

    The design of Mochovce NPP was based on the Novo-Voronez type WWER-440/213 reactor - twin units. Seismic characteristic of this region is characterized by very low activity. Mochovce NPP site is located on the rock soil with volcanic layer (andesit). Seismic reassessment of Mochovce NPP was done in two steps: deterministic approach up to commissioning confirmed value Horizontal Peak Ground Acceleration HPGA=0.1 g and activities after commissioning as a consequence of the IAEA mission indicate higher hazard values. (author)

  17. Technology for NPP decantate treatment realized at Kola NPP

    International Nuclear Information System (INIS)

    Stakhiv, Michael; Avezniyazov, Slava; Savkin, Alexander; Fedorov, Denis; Dmitriev, Sergei; Kornev, Vladimir

    2007-01-01

    At Moscow SIA 'Radon' jointly with JSC 'Alliance Gamma', the technology for NPP Decantate Treatment was developed, tested and realized at Kola NPP. This technology consists of dissolving the salt residue and subsequent treatment by ozonization, separation of the deposits formed from ozonization and selective cleaning by ferro-cyanide sorbents. The nonactive salt solution goes to an industrial waste disposal site or a repository specially developed at NPP sites for 'exempt waste' products by IAEA classification. This technology was realized at Kola NPP in December 2006 year. At this time more than 1000 m 3 of decantates log time stored are treated. It allows solving very old problem to empty decantates' tanks at NPPs in environmentally safe manner and with high volume reduction factor. (authors)

  18. NPOESS Preparatory Project (NPP) Science Overview

    Science.gov (United States)

    Butler, James J.

    2011-01-01

    NPP Instruments are: (1) well understood thanks to instrument comprehensive test, characterization and calibration programs. (2) Government team ready for October 25 launch followed by instrument activation and Intensive Calibration/Validation (ICV). NPP Data Products preliminary work includes: (1) JPSS Center for Satellite Applications and Research (STAR) team ready to support NPP ICV and operational data products. (2) NASA NPP science team ready to support NPP ICV and EOS data continuity.

  19. Workflow in Almaraz NPP

    International Nuclear Information System (INIS)

    Gonzalez Crego, E.; Martin Lopez-Suevos, C.

    2000-01-01

    Almaraz NPP decided to incorporate Workflow into its information system in response to the need to provide exhaustive follow-up and monitoring of each phase of the different procedures it manages. Oracle's Workflow was chosen for this purpose and it was integrated with previously developed applications. The objectives to be met in the incorporation of Workflow were as follows: Strict monitoring of procedures and processes. Detection of bottlenecks in the flow of information. Notification of those affected by pending tasks. Flexible allocation of tasks to user groups. Improved monitoring of management procedures. Improved communication. Similarly, special care was taken to: Integrate workflow processes with existing control panels. Synchronize workflow with installation procedures. Ensure that the system reflects use of paper forms. At present the Corrective Maintenance Request module is being operated using Workflow and the Work Orders and Notice of Order modules are about to follow suit. (Author)

  20. New appraisement of siting for a NPP on Mures river

    International Nuclear Information System (INIS)

    Traian Mauna

    2010-01-01

    The studies for a second NPP siting on inner Romanian rivers began in a careful manner since 1982 as a first part of the Nuclear Power Plant Romanian Program adopted by political and governmental authorities at the time. The experience gained from Cernavoda NPP siting, the first mission of new multi-branch of specialists team was to choose new NPP sites adapting the CANDU type NPP Cernavoda project to the new parameters of close water cooling circuit and of hard less or no rock foundation strata. The new sites conditions mean a lot of changes of CANDU license and a decrease the output power supplied to the national electric grid. The studies on the Mures river as alternative site of Olt river in Transylvania region began in 1986 and were stopped after 1990. This paper tries to reconsider shortly the old analysis focused on geological and geotechnical aspects and other local sites characteristics according to the last IAEA Safety Standards taking into account also the last types of NPP generations and the number of units. (author)

  1. Improvement of automatic control systems of high-power turbines of PAO tubroatom for nuclear power plants

    Science.gov (United States)

    Shvetsov, V. L.; Babaev, I. N.

    2017-09-01

    The main technical solutions applied by PAO Turboatom used as the compensatory measures at the increase of the period of nonstop operation of nuclear power plants' (NPP) turbines with VVER-1000 type reactors up to 18 months are (1) replacing the standard hydraulic speed controller with an electronic one, (2) introduction of overclocking protection, (3) modernization of units of stop-control valves of high pressures, (4) installation of locking dampers on the receiver tubes of turbines of the first and second modification, and (5) improving the quality of repairs by reviewing the requirements for their implementation. The introduction of complex diagnostics of a control system on the basis of automatic treatment of results of registration of working parameters of the turbine is allocated as a separate prospective direction. Using an electronic controller of speed makes it possible to simplify the procedure of its inclusion in work at the failure of an electro-hydraulic system of control and vice versa. The regimes of maintaining the turbine rotor speed, steam pressure on the outlet of turbine, and the positions of main servomotors were introduced into the functions of the electronic controller. An electronic controller of speed includes its own electro-hydraulic transducer, turbine rotor speed sensor, and sensors of the position of main servomotors. Into the functions of electro- hydraulic control system and electronic speed controller, the function of overclocking protection, which determines the formation of commands for stopping the turbine at the exceeding of both the defined level of rotation speed and the defined combination of achieved rotation speed and angular acceleration of rotor, was introduced. To simplify the correction of forces acting on the control valve cups, the design of the cups was changed, and it has the profiled inserts. The solutions proposed were implemented on K-1100-60/1500-2M turbines of Rostov NPP. From the composition of control system

  2. Shock absorber in Ignalina NPP

    International Nuclear Information System (INIS)

    Bulavas, A.; Muralis, J.

    1996-09-01

    Theoretical calculation and experimental analysis of models of shock absorber in Ignalina NPP is presented. The results obtained from the investigation with model of shock absorber coincide with the theoretical calculation. (author). 2 figs., 3 refs

  3. Selection of NPP for Kazakhstan

    International Nuclear Information System (INIS)

    Zhotabaev, Zh.R.

    2003-01-01

    Commercial NPP for Kazakhstan should to meet to several main requirements: 1). Safety operation (accident probability not more than 10 -6 1/p. year). 2). High efficiency > 40 %. 3). Possibility of use for high-temperature chemistry and hydrogen production. 4). Possibility for manufacturing of considerable part of equipment in Kazakhstan. 5). Possibility for fuel production and reprocessing in Kazakhstan. 6). Independence from existence of large water-supply sources. Comparative analysis of several NPP with different reactors (WWR-1000, Candu, BREST, VG-400; graphite molten salt reactor) shows that NPP with the graphite molten salt reactor meets to all above requirements, but hydrogen production it is possible by more complete 4-stage technology, since coolant temperature is 800 Deg. C. The principle advantage is possibility of manufacturing of main equipment and fuel in Kazakhstan that reduce the cost of NPP construction and operation

  4. Modernization programme at Dukovany NPP

    International Nuclear Information System (INIS)

    Trnka, M.

    2000-01-01

    The main goal of each NPP is to produce electricity safely, economically and without influence to environment. For Dukovany NPP it means to upgrade all documentation and perform the Equipment Upgrading Programme. All these activities are time and money consuming and therefore the determination of priority of all items was necessary. In the presentation there are mentioned some important changes in documentation, results of PSA studies and reason for Equipment Upgrading Programme performance. It was selected the most important item from the list of Equipment Upgrading Programme the I and C upgrading. Management has decided that Dukovany NPP will become among the best NPPs with WWER type of reactor. It seems this decision is the best way how to extend lifetime of the NPP. (author)

  5. Psychology of NPP operation safety

    International Nuclear Information System (INIS)

    Tret'yakov, V.P.

    1993-01-01

    The book is devoted to psychologic investigations into different aspects of NPP operative personnel activities. The whole set of conditions on which successful and accident-free personnel operation depends, is analysed. Based on original engineering and socio-psychologic investigations complex psychologic support for NPP personnel and a system of training and upkeep of operative personnel skills are developed. The methods proposed have undergone a practical examination and proved their efficiency. 154 refs., 12 figs., 9 tabs

  6. Fuel consumption organization at the Kola NPP

    International Nuclear Information System (INIS)

    Matveev, A.A.; Ignatenko, E.I.; Volkov, A.P.; Trofimov, B.A.

    1981-01-01

    Problems of using NPPs in the power systems including hydroelectric power plants and NPPs are considered on the example of the Kola power system. The methods of the WWER-440 reactor fuel loading formation, reactor power forcing, optimization of volumes and time of the NPP main equipment planned maintenance are discussed. It is concluded that the optimal methods for the WWER-440 reactor fuel loading formation are the following: reactor make-up with the lesser number of fuel assemblies with maximum designed enrichment; for the case of decreased loading energy capacity displacement of make-up fuel with 2.4% enrichment by the fuel with 3.6% enrichment when preserving the designed number of make-up fuel assemblies [ru

  7. Chernobyl NPP accident: a year later

    International Nuclear Information System (INIS)

    Asmolov, V.G.; Borovoj, A.A.; Demin, V.F.

    1988-01-01

    Consideration is being given to measures on liquidation of Chernobyl accident aftereffects, conducted since August, 1986. One of the most important measures lay in construction of the ''shelter'', which must provide long-term conservation of accidental unit. Works on decontamination of reactor area and contaminated populated regions were continued. Measures on providing safety of population and its health protection were performed. An attention was paid to long-term investigations on studying delayed aftereffects of the accident, monitoring of invironment, development and introduction of measures on improving NPP safety. Prospects of further development of nuclear power engeneering and possibilities of improving its safety are considered

  8. Safe 15 Terawatt of Temelin NPP

    International Nuclear Information System (INIS)

    Sula, M.

    2010-01-01

    In this work author presents a project Safe 15 Terawatt realised on the Temelin NPP. This project is one of the eight key projects of the CEZ group, associated in the 'Programme of efficiency'. The project started in June 2007 with long-term goals for horizon of year 2012. The safety indicators will be reached of the first quarter level of world's nuclear power plant - by the end of the first decade. By the end of year 2012 we will have achieved annual production of 15 billion kWh - in the Czech Republic: 15 Terawatt.

  9. Social consequences of closing the Ignalina NPP

    International Nuclear Information System (INIS)

    Baubinas, R.; Burneika, D.

    2001-01-01

    The possible social consequences of closing the Ignalina Nuclear Power Plant are studied. The social and economical situation in Visaginas and in the Utena region as a precondition for possible social consequences is shown. Also, two main groups of factors that can possibly influence the situation in the labour market are analysed. The problems of the enterprises that create working places and of the inhabitants of Visaginas whose possible behaviour can affect the situation in the labour market are discussed. Also, some proposals to neutralize the social costs of closing the Ignalina NPP are made. (author)

  10. Mochovce NPP safety improvement and completion

    International Nuclear Information System (INIS)

    1997-01-01

    6th Nuclear society information meeting dealt with the completion of the Mochovce NPP with regard to implementation of safety measures. It was aimed to next problems: I. 'Survey' presentation on the situation of the nuclear power industry in partner countries; II. Basic technical presentations; III. Presentations of operators of the other VVER 440/213 NPPs on their activities in the field of safety improvement in relation to IAEA recommendations; IV. Technical solutions of safety improvements ranked with IAEA degree 3 (Report SC 108 VVER); V: Technical solutions of selected Safety Measures ranked with IAEA degree 2 and 1 (Report SC 108 VVER)

  11. Calculation of NPP pipeline seismic stability

    International Nuclear Information System (INIS)

    Kirillov, A.P.; Ambriashvili, Yu.K.; Kaliberda, I.V.

    1982-01-01

    A simplified design procedure of seismic pipeline stability of NPP at WWER reactor is described. The simplified design procedure envisages during the selection and arrangement of pipeline saddle and hydraulic shock absorbers use of method of introduction of resilient mountings of very high rigidity into the calculated scheme of the pipeline and performance of calculations with step-by-step method. It is concluded that the application of the design procedure considered permits to determine strains due to seismic loads, to analyze stressed state in pipeline elements and supporting power of pipe-line saddle with provision for seismic loads to plan measures on seismic protection

  12. Safety Culture Survey in Krsko NPP

    International Nuclear Information System (INIS)

    Strucic, M.; Bilic Zadric, T.

    2008-01-01

    The high level of nuclear safety, stability and competitiveness of electricity production, and public acceptability are the main objectives of Krsko Nuclear Power Plant. This is achievable only in environment where strong Safety Culture is taking dominant place in the way how employees communicate, perform tasks, share their ideas and attitudes, and demonstrate their concern in all aspects of work and coexistence. To achieve these objectives, behaviour of all employees as well as specific ethical values must become more transparent and that must arise from the heart of organization. Continuous ongoing and periodic self assessments of Safety Culture in Krsko NPP present major tools in implementation process of this approach. Benefits from Periodic interdisciplinary focused self assessment approach, which main intention is finding the strengths and potential areas for improvements, was used second time to assess the area of Safety Culture in Krsko NPP. Main objectives of self assessment, performed in 2006, were to increase the awareness of the present culture, to serve as a basis for improvement and to keep track of the effects of change or improvement over a longer period of time. For the purpose of effective self assessment, extensive questionnaire was used to obtain information that is representative for whole organization. Wide range of questions was chosen to cover five major characteristics of safety culture: Accountability for safety is clear, Safety is integrated into all activities, Safety culture is learning-driven, Leadership for safety is clear and Safety is a clearly recognized value. 484 Krsko NPP employees and 96 contractors were participated in survey. 70-question survey provided information that was quantified and results compared between groups. Anonymity of participant, as well as their willingness to contribute in this assessment implicates the high level of their openness in answering the questions. High number of participant made analysis of

  13. The post-accidents exploitation of Chernobyl NPP

    International Nuclear Information System (INIS)

    Nosovskij, A.V.

    1996-01-01

    Problems facing the Chernobyl NPP personnel since its commissioning and during its post-accident operation are considered. The accomplished measures on improving the power units safety, normalization of the radiation situation as well as the impact of psychological factor at the safety culture level are discussed

  14. Selection of suitable sites for NPP in Slovenia (stage 3)

    International Nuclear Information System (INIS)

    Grgic, M.; Fabjan, L.; Premru, U.

    1977-01-01

    Selection of suitable sites for nuclear power plants in Slovenia is considered. This includes the studies of available data on regional and local characteristics specified in general site suitability criteria for NPP. The most suitable selected sites will be included into land use urbanistic planning of Slovenia

  15. Prospects of increasing the engineering level of NPP components

    International Nuclear Information System (INIS)

    Filippov, G.A.

    1987-01-01

    Consideration is being given to main problems related to development and industrial introduction of NPP components corresponding to the perspective world-wide engineering level. The nearest task in this field is to elevate the engineering level of developed and being produced power equipment up to the level of similar equipment, manufactured by leading foreign companies

  16. NPP Temelin instrumentation and control system upgrade and verification

    International Nuclear Information System (INIS)

    Ubra, O.; Petrlik, J.

    1998-01-01

    Two units of Ver 1000 type of the Czech nuclear power plant Temelin, which are under construction are being upgraded with the latest instrumentation and control system delivered by WEC. To confirm that the functional design of the new Reactor Control and Limitation System, Turbine Control System and Plant Control System are in compliance with the Czech customer requirements and that these requirements are compatible with NPP Temelin upgraded technology, the verification of the control systems has been performed. The method of transient analysis has been applied. Some details of the NPP Temelin Reactor Control and Limitation System verification are presented.(author)

  17. NPP life management program - status report for Slovenia

    International Nuclear Information System (INIS)

    Glumac, B.

    1998-01-01

    Status report on NPP life management in Slovenia is dealing with possible life extension of NPP Krsko which comprises: replacement of steam generator; power upgrade; exchange of plant process computer; snubber reduction program, additional forced ventilation cooling system. Fuel improvements are predicted as well as the problems of storing spent fuel, low and intermediate waste if the plant is to operate through 2023 and possibly beyond that date. Related research activities are concerned with radiation damage, modelling of reactor core parameters by Monte Carlo calculations and PSA and severe accidents studies. Most of the activities are performed in cooperation with foreign organisations

  18. Structure study and design of Qinshan NPP PCCV

    International Nuclear Information System (INIS)

    Xia Zufeng; Xu Yongzhi; Wang Tianzhen; Wu Jibiao

    1993-02-01

    The design process of Qinshan NPP (nuclear power plant) PCCV (prestressed concrete containment vessel) is summarized. The tendon test, structural description, design bases and analysis method are introduced. The arrangement for preventing concrete from cracking and design features of post-tensioning system and steel liner are presented. The results of model test and non-linear analysis for ultimate load in Qinshan NPP PCCV are also given. Through the integrity test of PCCV, it shows that the test values are in agreement with predicted values, the structure is excellent and the performance of leak tightness conforms to the safety requirements

  19. The evolution of the fuel cycle in the Dukovany NPP

    Energy Technology Data Exchange (ETDEWEB)

    Bajgl, J [Jaderna Elektrarna, Dukovany (Czech Republic)

    1994-12-31

    The ten-year operational experience of four WWER-440 units in Dukovany NPP with a total number of 35 cycles is outlined. The strategy of fuel reloading has been changed from out-in schemes to low-leakage patterns. The linear pin power limitation will be introduced. The main physical limits and conditions for the NPP operation are listed. The main goal is to go to a full 4-year fuel cycle in which the burnup will be about 40 Mwd/kg U. 6 tabs.

  20. Early detection of power system disturbances as a condition for safe operation of the Dukovany NPP in the 'Island operation mode'

    International Nuclear Information System (INIS)

    Petruzela, I.

    1997-01-01

    The ''Frequency Plan'' worked out for the Czech Power System specifies a set of preventive measures along with the set of the frequency ranges. This problem was solved in details for the Dukovany nuclear power plant. The design changes under preparation support a reliable as well as safe operation in the island-operation mode until a full restoration of the whole power system. The design modifications are based on the following three main innovations: An incorporation of the FREA 16 frequency relay into the protection circuits; large modifications in turbine control loops; installation of software routine for the operator to support the island operation mode. The capability of the island operation has been demanded by relevant regulations both for the operating units and for that under construction. The capability can be tested under the transition to houseloads, as well as through the direct simulation of abnormal grid conditions. 1 fig

  1. NPP Decommissioning: the concept; state of activities

    International Nuclear Information System (INIS)

    Nemytov, S.; Zimin, V.

    2001-01-01

    The main principles of NPP decommissioning concept in Russia are given. The conditions with fulfillment of works on NPP unit pre-decommissioning and decommissioning including: development of the normative documentation, creation of special fund for financing NPP decommissioning activities, deriving the Gosatomnadzor license for decommissioning of shut down NPP units, development of the equipment and technologies for waste and spent fuel management are presented. The decommissioning cost and labour intensity of one WWER-440 unit are shown. The practical works, executed on shut down units at Beloyarsk NPP (Unit1 and 2) and Novo Voronezh NPP (Unit 1 and 2) are outlined

  2. Results and development prospects for the Cernavoda NPP

    International Nuclear Information System (INIS)

    Rotaru, Ioan

    2001-01-01

    The new competitive market in the power sector offers favorable conditions for continual developing of Nuclear Power in Romania. The principal arguments in this respect are: the CANDU technology is a western technology recognized world wide both for its operation reliability and its economical performances. The results obtained by Cernavoda NPP Unit 1 over a period of four years and a half commercial operation confirms the validity of the CANDU project in Romania in the new conditions of competitive market. Accomplishing the Unit 2 of Cernavoda NPP represents for the time being one of the most cost-effective investment in the Romanian power sector. Also, the participation of the local industry to the project implementation is important as it ensures the initial heavy water and nuclear fuel charging, specific materials and equipment production, design and construction works, etc. Heaving in view all these favorable arguments, the construction of Unit 2 of Cernavoda NPP represents one of the highest priorities of the State Budget of the present administration in year 2001. The Nuclear Power Project in Romania, based on CANDU technology meets national as well as EU regulations concerning nuclear power and as such its development poses no significant problems both in the context of EU extension and in the frame of the developing competitive market in the power sector. For SNN SA the main objectives in view for the next stage are: operating Cernavoda NPP Unit 1 in conditions of highest nuclear safety and economical efficiency; finalizing the Cernavoda NPP Unit 2 and creation of an organisation for operating the two units; promoting of a functional system characteristic to the competitive market economy and open to privatization; creating opportunities for exporting electrical energy. The contribution contains the following sections: 1. General overlook; 2. Performance of the power production in the year 2000; 2.1. Unit 1 of Cernavoda NPP; 2.2. Nuclear Fuel Plant

  3. Spent fuel pool risk analysis for the Dukovany NPP

    Energy Technology Data Exchange (ETDEWEB)

    Hust' ak, S.; Jaros, M.; Kubicek, J. [UJV Rez, a.s., Husinec-Rez (Czech Republic)

    2013-07-01

    UJV Rez, a.s. maintains a Living Probabilistic Safety Assessment (Living PSA) program for Dukovany Nuclear Power Plant (NPP) in the Czech Republic. This project has been established as a framework for activities related to risk assessment and to support for risk-informed decision making at this plant. The most extensively used PSA application at Dukovany NPP is risk monitoring of instantaneous (point-in-time) risk during plant operation, especially for the purpose of configuration risk management during plant scheduled outages to avoid risk significant configurations. The scope of PSA for Dukovany NPP includes also determination of a risk contribution from spent fuel pool (SFP) operation to provide recommendations for the prevention and mitigation of SFP accidents and to be applicable for configuration risk management. This paper describes the analysis of internal initiating events (IEs) in PSA for Dukovany NPP, which can contribute to the risk from SFP operation. The analysis of those IEs was done more thoroughly in the PSA for Dukovany NPP in order to be used in instantaneous risk monitoring. (orig.)

  4. Feature extraction and sensor selection for NPP initiating event identification

    International Nuclear Information System (INIS)

    Lin, Ting-Han; Wu, Shun-Chi; Chen, Kuang-You; Chou, Hwai-Pwu

    2017-01-01

    Highlights: • A two-stage feature extraction scheme for NPP initiating event identification. • With stBP, interrelations among the sensors can be retained for identification. • With dSFS, sensors that are crucial for identification can be efficiently selected. • Efficacy of the scheme is illustrated with data from the Maanshan NPP simulator. - Abstract: Initiating event identification is essential in managing nuclear power plant (NPP) severe accidents. In this paper, a novel two-stage feature extraction scheme that incorporates the proposed sensor type-wise block projection (stBP) and deflatable sequential forward selection (dSFS) is used to elicit the discriminant information in the data obtained from various NPP sensors to facilitate event identification. With the stBP, the primal features can be extracted without eliminating the interrelations among the sensors of the same type. The extracted features are then subjected to a further dimensionality reduction by selecting the sensors that are most relevant to the events under consideration. This selection is not easy, and a combinatorial optimization technique is normally required. With the dSFS, an optimal sensor set can be found with less computational load. Moreover, its sensor deflation stage allows sensors in the preselected set to be iteratively refined to avoid being trapped into a local optimum. Results from detailed experiments containing data of 12 event categories and a total of 112 events generated with a Taiwan’s Maanshan NPP simulator are presented to illustrate the efficacy of the proposed scheme.

  5. Consideration on application of RAP to G-II NPP

    International Nuclear Information System (INIS)

    Shen Shen

    2010-01-01

    The design (D-RAP) for nuclear power plant has been adopted internationally in new-build advanced nuclear power plant design, which increases the ability of the risk-significant SSCs to carry out its functions during the accident circumstances especially in the severe accident situation, and reduces the risk of a nuclear power plant. The concept of reliability assurance program for advanced nuclear power plant can also be applied to nuclear power plants which second-generation NPP technology is used. Through analysis and research, the risk-significant SSCs in actual NPP can also be screened, and these SSCs can be managed appropriately, so that can improve the overall plant ability to against the severe accident, reduce the risk, and improve their safety and economy. Also such technology used does not exist any insurmountable technical difficulties and a lot of money input. (authors)

  6. The local impacts of Borssele NPP closing down

    International Nuclear Information System (INIS)

    Mandos, J.L.

    2000-01-01

    The municipal council of Borsele considers that the use of nuclear energy is a question of national policy, but considers itself responsible for town and country planning, safety and employment. The two latter aspects are especially significant if plans for shutdown are concerned. Confidence in safety of the NPP in Borsele has increased in recent years due to transparent information policy of the power plant itself as well as the local government and most of the employees living in the area. If considering the circumstances under which the decision about the closure of NPP one could sees this is a purely political decision. The local government will continue the close cooperation with the National government and the Parliament in solving the problem of employment and social impact of NPP shutdown

  7. Computer Security of NPP Instrumentation and Control Systems: Cyber Threats

    International Nuclear Information System (INIS)

    Klevtsov, A.L.; Trubchaninov, S.A.

    2015-01-01

    The paper is devoted to cyber threats, as one of the aspects in computer security of instrumentation and control systems for nuclear power plants (NPP). The basic concepts, terms and definitions are shortly addressed. The paper presents a detailed analysis of potential cyber threats during the design and operation of NPP instrumentation and control systems. Eleven major types of threats are considered, including: the malicious software and hardware Trojans (in particular, in commercial-off-the-shelf software and hardware), computer attacks through data networks and intrusion of malicious software from an external storage media and portable devices. Particular attention is paid to the potential use of lower safety class software as a way of harmful effects (including the intrusion of malicious fragments of code) on higher safety class software. The examples of actual incidents at various nuclear facilities caused by intentional cyber attacks or unintentional computer errors during the operation of software of systems important to NPP safety.

  8. Co-ordinated research programme on benchmark study for the seismic analysis and testing of WWER-type nuclear power plants. V. 4F. Paks NPP: Analysis and testing. Working material

    International Nuclear Information System (INIS)

    1999-01-01

    In August 1991, following the SMiRT-11 Conference in Tokyo, a Technical Committee Meeting was held on the 'Seismic safety issues relating to existing NPPs'. The Proceedings of this TCM was subsequently compiled in an IAEA Working Material. One of the main recommendations of this TCM, called for the harmonization of criteria and methods used in Member States in seismic reassessment and upgrading of existing NPPs. Twenty four institutions from thirteen countries participated in the CRP named 'Benchmark study for the seismic analysis and testing of WWER type NPPs'. Two types of WWER reactors (WWER-1000 and WWER-440/213) selected for benchmarking. Kozloduy NPP Units 5/6 and Paks NPP represented these respectively as prototypes. Consistent with the recommendations of the TCM and the working paper prepared by the subsequent Consultants' Meeting, the focal activity of the CRP was the benchmarking exercises. A similar methodology was followed both for Paks NPP and Kozloduy NPP Unit 5. Firstly, the NPP (mainly the reactor building) was tested using a blast loading generated by a series of explosions from buried TNT charges. Records from this test were obtained at several free field locations (both downhole and surface), foundation mat, various elevations of structures as well as some tanks and the stack. Then the benchmark participants were provided with structural drawings, soil data and the free field record of the blast experiment. Their task was to make a blind prediction of the response at preselected locations. The analytical results from these participants were then compared with the results from the test. Although the benchmarking exercises constituted the focus of the CRP, there were many other interesting problems related to the seismic safety of WWER type NPPs which were addressed by the participants. These involved generic studies, i.e. codes and standards used in original WWER designs and their comparison with current international practice; seismic analysis

  9. Comparative analysis of events at NPP of Ukraine during 1993-1995

    Energy Technology Data Exchange (ETDEWEB)

    Koltakov, V [Ministry for Environment Protection and Nuclear and Radiation Safety of Ukraine Nuclear Regulatory Administration Scientific and Technical Centre, Kiev (Ukraine)

    1997-12-31

    The suggested comparative analyses of malfunctions in operation of Ukrainian NPP during the last 3 year shows a tendency for decreasing the total number of malfunctions, out of plan power changes and malefactions connected with safety system nonavailability. 6 tabs.

  10. The NPPR Trnava participation in the NPP V-2 modernisation and safety improvement project

    International Nuclear Information System (INIS)

    Michal, V.; Losonsky, B.; Magdolen, J.

    1999-01-01

    The presented contribution deals with form, present state and results of Nuclear Power Plants Research Inst.e participation in the NPP V-2 Jaslovske Bohunice Modernization and Safety Improvement Project.(author)

  11. Comparative analysis of events at NPP of Ukraine during 1993-1995

    International Nuclear Information System (INIS)

    Koltakov, V.

    1996-01-01

    The suggested comparative analyses of malfunctions in operation of Ukrainian NPP during the last 3 year shows a tendency for decreasing the total number of malfunctions, out of plan power changes and malefactions connected with safety system nonavailability. 6 tabs

  12. Chernobyl'-88. Reports of the 1. All-Union scientific and technical meeting on results of accident effect elimination at the Chernobyl' NPP. V. 7. Part 1. Localization of accident consequences at the 4th power unit, operating site of the Chernobyl NPP and adjoining territories

    International Nuclear Information System (INIS)

    Ignatenko, E.I.

    1989-01-01

    The next data on the accident consequence elimination are presented: temperature monitoring results, gamma radiation exposure dose rates, neutron and gamma fields, aerosol disperse composition. The information system for scientific researches FINISH and automatic subsystems for radiation control and the Ukrytie object diagnostics are described. Decontamination of the Chernobyl' NPP territory, equipment and rooms is described too

  13. Chernobyl'-88. Reports of the 1. All-Union scientific and technical meeting on results of accident effect elimination at the Chernobyl' NPP. V. 7. Part 2. Localization of accident consequences at the 4th power unit, operating site of the Chernobyl' NPP and adjoining territories

    International Nuclear Information System (INIS)

    Ignatenko, E.I.

    1989-01-01

    The next data on the accident consequence elimination are presented: temperature monitoring results, gamma radiation exposure dose rates, neutron and gamma fields, aerosol disperse composition. The information system for scientific researches FINISH and automatic subsystems for radiation control and the Ukrytie object diagnostics are described. Decontamination of the Chernobyl' NPP territory, equipment and rooms is described too

  14. Russian normative approach to the question of management of NPP life time

    International Nuclear Information System (INIS)

    Karpunin, N.I.

    2002-01-01

    Full text: In Russia, the designated service life of a nuclear power plant (NPP) is 30 years. During the period 2001-2010, 15 Russian NPP units will reach the end of their service life. The 'Basic Provisions of NPP Safety Assurance', OPB-88/97, Item 5.1.14, provide for a possible extension of NPP operation beyond the designated service life. For such an extension, the NPP operating organization must apply for a license renewal to Gosatomnadzor, which needs to specify the relevant requirements. GAN is developing regulatory documents to provide a basis for NPP license renewal/extension of NPP operation, which would benefit from international experience. In accordance with 'The program of Atomic Energy Development in the Russian Federation for 1998-2005 and up to 2010' adopted by Decree No. 815 of the Government of the Russian Federation on 21 July 1998, priority is placed on the preparation of NPPs for extension of service life and on ensuring safety in the extended operating period. The length of the extension beyond the designated service life is to be determined on the basis of a range of technical and economic considerations, including: The ability to ensure and maintain operational safety; Sufficient residual service life of the unit's non-repairable components; The availability of temporary storage facilities for the additional spent nuclear fuel and radioactive waste, or the possibility of its transport off-site; The ability to ensure safe handling of the radioactive waste generated during the extension period; To extend the lifetime of an NPP unit, the plant Operator is required to perform the following tasks: Carry out a comprehensive survey of the NPP unit; Draw up a programme of preparation for lifetime extension; Prepare the NPP unit for operation in the extended period; Carry out the necessary tests. There are also some normative documents, which regulate management of NPP life time. (author)

  15. Public acceptance of nuclear energy in Indonesia. A traditional puppet show for NPP in Java

    International Nuclear Information System (INIS)

    Suyudi Soeliarno

    1995-01-01

    In Indonesia, activities on public relation have been carried out since the establishment of the agency responsible for research and development of atomic energy in 1958 (which later in the year 1964 became Batan, National Atomic Energy Agency), wile activities on public acceptance started 'at the end of 1985. After the Government indicated that it has to look seriously into the construction of the NPP, as from 1990, the public acceptance (PA) activities have been intensified in anticipation of the construction of the first NPP. An important part of the preparatory activities for the construction of the NPP is preparing the people, particularly those who live near the NPP site, to accept and to support the NPP program. The interdepartmental team has bee established in August 1990 consisting of representatives of several institutions, namely, Ministry of Information, Ministry of Domestic Affairs, Ministry of Defense, Land Utilization Agency, State Electricity Corporation, Office of the Minister for Population and Environment, and Batan. This team, called the 'Team on Public Acceptance of NPP', has the main task providing extensive information to the public concerning the government plan to construct nuclear power plants in Indonesia. From 1990 through the middle of 1994 the activity of the Team on Public Acceptance of NPP was focused on providing information on te NPP program to the local community leaders and the public, particularly in the districts of the NPP site in the Muria Peninsula region. Its main purpose was to precondition the people who live near the NPP site to accept the NPP in their neighbourhood without fear

  16. The Bohunice NPP V-1 units nuclear safety upgrading

    International Nuclear Information System (INIS)

    Mlcuch, M.

    2000-01-01

    Safety upgrading and operational reliability improvement was carried out by the Bohunice NPP V-1 staff continuously since the plant commissioning. By now, more than 1200 minor or major modifications have been implemented, either by the NPP maintenance staff or by the contractors. Based on findings of safety assessment missions invited by Bohunice NPP in 1990 - 1991, the Czecho-slovak Nuclear Regulatory Authority (CSKAE) issued the decision No. 5/91 of 81 safety upgrading measures to be taken in different areas. These improvements are referred to as the 'Small Reconstruction of the Bohunice V-1 NPP'. Realization of measures during Small reconstruction of the Bohunice NPP V-1 became a power plant, which further operation is acceptable from safety point of view, but it is also necessary further safety improvement. During the period of the Small Reconstruction the development of a Safety Report for the Gradual reconstruction has been completed. Based on this report the SR Nuclear Regulatory Authority issued the Decision No. 1/94, in which requires 59 upgrading measures in different areas to be addressed. The development of Basic Engineering of the Gradual Reconstruction has been contracted to the Siemens AG. Implementation of safety measures are provided through contract with the consortium REKON (which consists of Siemens AG company and Nuclear Power Plants Research Institute Trnava) and other Czech, Russian and Slovak companies. The Gradual Reconstruction of Bohunice NPP V-1 will be finished in 2000. By implementation of the measures carried out during Gradual Reconstruction achievement of an internationally acceptable nuclear safety level will be reached. (author)

  17. Validation of MCNP NPP Activation Simulations for Decommissioning Studies by Analysis of NPP Neutron Activation Foil Measurement Campaigns

    Directory of Open Access Journals (Sweden)

    Volmert Ben

    2016-01-01

    Full Text Available In this paper, an overview of the Swiss Nuclear Power Plant (NPP activation methodology is presented and the work towards its validation by in-situ NPP foil irradiation campaigns is outlined. Nuclear Research and consultancy Group (NRG in The Netherlands has been given the task of performing the corresponding neutron metrology. For this purpose, small Aluminium boxes containing a set of circular-shaped neutron activation foils have been prepared. After being irradiated for one complete reactor cycle, the sets have been successfully retrieved, followed by gamma-spectrometric measurements of the individual foils at NRG. Along with the individual activities of the foils, the reaction rates and thermal, intermediate and fast neutron fluence rates at the foil locations have been determined. These determinations include appropriate corrections for gamma self-absorption and neutron self-shielding as well as corresponding measurement uncertainties. The comparison of the NPP Monte Carlo calculations with the results of the foil measurements is done by using an individual generic MCNP model functioning as an interface and allowing the simulation of individual foil activation by predetermined neutron spectra. To summarize, the comparison between calculation and measurement serve as a sound validation of the Swiss NPP activation methodology by demonstrating a satisfying agreement between measurement and calculation. Finally, the validation offers a chance for further improvements of the existing NPP models by ensuing calibration and/or modelling optimizations for key components and structures.

  18. Emergency preparedness at Ignalina NPP

    International Nuclear Information System (INIS)

    Kairys, A.

    1998-01-01

    Brief review of Ignalina NPP safety upgrading and personnel preparedness to act in cases of accidents is presented. Though great activities are performed in enhancing the plant operation safety, the Ignalina NPP management pays a lot of attention to preparedness for emergency elimination and take measures to stop emergency spreading. A new Ignalina NPP emergency preparedness plan was drawn up and became operational. It is the main document to carry out organizational, technical, medical, evacuation and other activities to protect plant personnel, population, the plant and the environment from accident consequences. Great assistance was rendered by Swedish experts in drawing this new emergency preparedness plan. The plan consists of 3 parts: general part, operative part and appendixes. The plan is applied to the Ignalina NPP personnel, Special and Fire Brigade and also to other contractor organizations personnel carrying out works at Ignalina NPP. There are set the following emergency classes: incident, emergency situation, alert, local emergency, general emergency. Separate intervention level corresponds to each emergency class. Overview of personnel training to act in case of an emergency is also presented

  19. Can the Ignalina NPP be safe?

    International Nuclear Information System (INIS)

    Kutas, S.

    1999-01-01

    Many countries started using nuclear power before Lithuania, the IAEA and NEA were established and have been functioning efficiently, numerous conventions have been signed that control nuclear activities, nuclear safety regulations and standards have been set. Lithuania which is striving to integrate into the West European structures and to become a member of the 'club' of the world's nuclear states, has become a full and equal member of the IAEA and recognises its recommendations. Furthermore, it has signed or joined international conventions and is doing its best to introduce the practice of controlling nuclear safety applied in western countries. Nuclear safety cannot be taken as something finite that does not change. The requirements of nuclear and radiation safety are continuously redefined taking into consideration scientific discoveries and inventions as well as technical progress. Safety assurance can be the only criterion that should determine whether the nuclear power plant can be operated in Lithuania. The safety analysis report confirmed that the Ignalina NPP can be safely operated until the channel-graphite gap closes. The experiments conducted to date have convincingly shown that by the year 2000 the gap will not close in any of the fuel channels of unit 1. It can be hoped that the submitted studies, analyses and assessments will confirm that the Ignalina NPP meets Lithuania's nuclear safety requirements that have been drawn up in compliance with the recommendations of IAEA

  20. Equipment Reliability Process in Krsko NPP

    International Nuclear Information System (INIS)

    Gluhak, M.

    2016-01-01

    To ensure long-term safe and reliable plant operation, equipment operability and availability must also be ensured by setting a group of processes to be established within the nuclear power plant. Equipment reliability process represents the integration and coordination of important equipment reliability activities into one process, which enables equipment performance and condition monitoring, preventive maintenance activities development, implementation and optimization, continuous improvement of the processes and long term planning. The initiative for introducing systematic approach for equipment reliability assuring came from US nuclear industry guided by INPO (Institute of Nuclear Power Operations) and by participation of several US nuclear utilities. As a result of the initiative, first edition of INPO document AP-913, 'Equipment Reliability Process Description' was issued and it became a basic document for implementation of equipment reliability process for the whole nuclear industry. The scope of equipment reliability process in Krsko NPP consists of following programs: equipment criticality classification, preventive maintenance program, corrective action program, system health reports and long-term investment plan. By implementation, supervision and continuous improvement of those programs, guided by more than thirty years of operating experience, Krsko NPP will continue to be on a track of safe and reliable operation until the end of prolonged life time. (author).

  1. Regulatory approach to NPP ageing in Bulgaria

    International Nuclear Information System (INIS)

    Vassilev, D.

    2000-01-01

    In this contribution summary information of Kozloduy NPP units is presented. The nuclear legislation, regulatory approach for managing safety aspects on NPP ageing, short term programme, complex programme PRG'97 ant other aspects of ageing management are discussed

  2. Some problems of NPP personnel training

    International Nuclear Information System (INIS)

    Vajshnis, P.P.; Kumkov, L.P.; Omel'chuk, V.V.

    1984-01-01

    Shortcomings of NPP personnel training are discussed. Development of full-scale training systems is necessary for qualitative training operative personnel. Primary problems that should be necessarily solved for ensuring effective training NPP personnel are considered

  3. Co-ordinated research programme on benchmark study for the seismic analysis and testing of WWER-type nuclear power plants. V. 3G. Kozloduy NPP units 5/6: Analysis and testing. Working material

    International Nuclear Information System (INIS)

    1999-01-01

    In August 1991, following the SMiRT-11 Conference in Tokyo, a Technical Committee Meeting was held on the 'Seismic safety issues relating to existing NPPs'. The Proceedings of this TCM was subsequently compiled in an IAEA Working Material. One of the main recommendations of this TCM, called for the harmonization of criteria and methods used in Member States in seismic reassessment and upgrading of existing NPPs. Twenty four institutions from thirteen countries participated in the CRP named 'Benchmark study for the seismic analysis and testing of WWER type NPPs'. Two types of WWER reactors (WWER-1000 and WWER-440/213) selected for benchmarking. Kozloduy NPP Units 5/6 and Paks NPP represented these respectively as prototypes. Consistent with the recommendations of the TCM and the working paper prepared by the subsequent Consultants' Meeting, the focal activity of the CRP was the benchmarking exercises. A similar methodology was followed both for Paks NPP and Kozloduy NPP Unit 5. Firstly, the NPP (mainly the reactor building) was tested using a blast loading generated by a series of explosions from buried TNT charges. Records from this test were obtained at several free field locations (both downhole and surface), foundation mat, various elevations of structures as well as some tanks and the stack. Then the benchmark participants were provided with structural drawings, soil data and the free field record of the blast experiment. Their task was to make a blind prediction of the response at preselected locations. The analytical results from these participants were then compared with the results from the test. Although the benchmarking exercises constituted the focus of the CRP, there were many other interesting problems related to the seismic safety of WWER type NPPs which were addressed by the participants. These involved generic studies, i.e. codes and standards used in original WWER designs and their comparison with current international practice; seismic analysis

  4. The analysis of financial risk management application for NPP project in Indonesia

    International Nuclear Information System (INIS)

    Imam Bastori; Moch Djoko Birmano

    2012-01-01

    NPP Project is one of full dynamic, risky and challenging business. Application of financial risk management t in Nuclear Power Plant (NPP) project becomes one alternative to be considered carefully. This paper explains an analysis to make a decision in the risk management application so that it can be applied in the NPP's construction in Indonesia. As case study, is NPP of conventional PWR type of class 1150 MWe. To calculate the economics and financing of NPP is used Spreadsheet INOVASI, further the decision of financial risk management were analyzed using a Model of Cash Flow Adjustment, which developed by Richard Fairchild. The analysis showed that the Method of Cash Flow Adjustment developed by Richard Fairchild is better than the method of NPV Adjustment on a NPP project, because it have included the aspects of financial risk management. NPP project can only be executed if the NPV 2 0 and decision to execute the financial risk management should be based on NPVrm > NPV. The application of financial risk management in NPP project is not needed if an insurance premium more expensive than all costs of financial distress, unless the insurance company can give discount of at least 20%. (author)

  5. Principles of Defense-in-depth philosophy applied in NPP engineering management

    International Nuclear Information System (INIS)

    Wu Guangwei

    2011-01-01

    Based on the Defense-in-depth Concept in nuclear and radiation safety, Defense-in-depth Concept for design management of Nuclear Power Plant (NPP) is developed in this paper to analyze the feasibility and importance of the application of the basic principle: Defense-in-depth concept in NPP systems performed during the design control of NPP. This paper focuses on the NPP engineering management process, and according to the analysis of such process, 5 principles of Defense-in-depth Concept applied in NPP design management are raised: (1) preventing the non-conformities of design via effective design quality management system; (2) discovering and correcting non-conformities of design quality in time via design checkup and design review meeting; (3) carrying out timely analysis and treatment against design non-conformities which have been transferred to construction phase; (4) Assessing and judging the severe non-conformities in construction phase, putting forward treatment opinions and remedies accordingly so as to avoid the existence of such non-conformities in physical construction of NPP; (5) Paying 'return-visit' and performing 'post-assessment' for NPP design to assess the designed functions and safety of NPP comprehensively. (author)

  6. Individual protection of NPP personnel

    International Nuclear Information System (INIS)

    Koshcheev, V.S.; Gol'dshtejn, D.S.; Chetverikova, Z.S.

    1983-01-01

    Specific features of NPP personnel individual protection are considered, mainly with respect to maintenance and repair works on various type reactors. The major concern is given to the selection and application reglamentations of the individual protection system (IPS), employment of sanitary locks, the organization of individual protection under the conditions of a heating microclimate. The ways are specified to the development and introduction of the most effective IPS and improvement of the entire NPP personnel individual protection system with respect to providing the necessary protection effect for maintaining high working capability of the personnel and minimizing the IPS impact on human organism functional systems. The accumulated experience in the personnel individual protection can be applied during construction and operation of NPP's in CMEA member-countries [ru

  7. Challenges of Ignalina NPP Decommissioning - View of Lithuanian Operator

    International Nuclear Information System (INIS)

    Aksionov, P.

    2017-01-01

    The state enterprise Ignalina Nuclear Power Plant (INPP) operates 2 similar design units of RBMK-1500 water-cooled graphite-moderated channel-type power reactors (1500 MW electrical power). INPP is carrying out the decommissioning project of the 2 reactors which includes: -) the retrieval of the spent nuclear fuel from the power units and its transportation into the Interim Spent Fuel Storage Facility; -) equipment and building decontamination and dismantling; -) radioactive waste treatment and storage; and -) the operation of key systems to ensure nuclear, radiation and fire protection. Ignalina NPP decommissioning project is planned to be completed by 2038. The presentation will be focused on the ongoing decommissioning activities at Ignalina NPP. The overview of main aspects and challenges of INPP decommissioning will be provided

  8. Corporate portal system at PAKS NPP, Hungary

    International Nuclear Information System (INIS)

    2009-01-01

    The new Corporate Portal System (CPS) of Paks NPP was launched in November 2006. The portal is based on one of the latest technologies, Plumtree Enterprise WEB 5.0. The main purpose of the installation of the new technology was to serve the working culture change, to give a platform to access all information and applications including the integrated process model used at the NPP. The new technology also supports those goals which were defined in the organization development programme: e.g. to improve internal communication with the establishment of communities of practice. Installation of the CPS has provided a powerful tool for knowledge management; it is possible to share and find all information through a controlled access in documents from various sources, to have links to people, portlets and different communities. Document management of the Paks NPP is supported by the integration of the Document 5 application, as the new Electronic Data Management System (EDMS) and the CPS. Depending on their access rights, all users of the CPS, through Microsoft Internet Explorer, can access technical, economic and human resources documents which are stored anywhere on the internal network (file servers, EDMS, old INRANET). The CPS is also accessible from the internet through a secure connection. The main concept is the integration of all applications to one platform and to help users to find all information they need. An access control list specifies which users and groups have access to an object (and what kind of access privileges they have such as read, select, edit, admin)

  9. Strategy for decommissioning of NPP's in Germany

    International Nuclear Information System (INIS)

    Rittscher, D.; Sterner, H.

    2003-01-01

    According to German Atomic Law, two different strategies are possible, i.e. direct dismantling and safe enclosure before dismantling. Both approaches have their advantages and disadvantages. Taking into account the site and plant specific conditions the optimal strategy can be evaluated. Both approaches have been applied in Germany in the past. The German Atomic Law and the Radiation Protection Ordinance (June 2002) were adapted recently (July 2002). Additionally, the life operation time of the German NPP's was fixed in a new law (April 2002): Orderly Termination of the Commercial Production of Nuclear Electricity. These issues have made it necessary for the power utilities to review the strategies applied. As long as the final disposal in Germany is still an open issue, the construction of local Interim Stores is necessary to be able to dismantle a NPP. The basic strategies are not excluding each other and it seems clear today, that the optimal approach is a combination of these strategies, e.g. dismantling of all auxiliary systems and leaving activated parts for a longer SE period. Within this approach the advantages of both basic strategies have been integrated in one. The EWN GmbH has developed such integrated but still different approaches for the decommissioning projects of the Kernkraftwerke Greifswald (KGR) and the Arbeitsgemeinschaft Versuchsreaktor (AVR) Juelich. It can be stated that the decommissioning of a NPP does not present technical issues of concern, but is more a project management issue, although surrounded by sometime intricate political and juridical boundary conditions. A major strategy change is to be expected only when final disposal capacities are available in the future. (authors)

  10. Dynamic model for tritium build-up at NPP with RBMK type reactors and its enviromental beraviour

    International Nuclear Information System (INIS)

    Badyaev, V.V.; Egorov, Yu.A.; Ivanov, E.A.; Stegachev, G.F.; Tolstykh, V.D.

    1982-01-01

    A model of tritium production dynamics for a high power NPP with RBMK type reactors is proposed and investigated. The main ''skeleton'' model structure for forecasting tritium buildup at a NPP and its exchange with the environment has been singled out at a heuristic level. Decomposition and layout of the units have been performed by global functional relations of the investigated objects (NPP and environment). the model accounts for only oxidized tritium forms. Water exchange between the NPP subsystems and environment is the main mechanism for tritium migration. The model does not account for scheduled periodic maintenance work effects, presence of stagnant zones in the station circuits, fuel burn-up, etc. The parametric identification method applied in the model makes the model adaptable to particular situations and considered systems of the NPP and environment. Completing the model with necessary and sufficient experimental data one can pass to certain forecasting problems and to NPP control as a tritium source in the environment

  11. IAEA activities in the field of NPP I and C

    International Nuclear Information System (INIS)

    Gloeckler, O.

    2006-01-01

    The paper discusses the current, and upcoming activities of the IAEA's Technical Working Group on Nuclear Power Plant Control and Instrumentation (TWG-NPPCI). The following particular I and C-related subjects are discussed in more detail: (1) the relation between improvements in I and C and NPP power up-rating projects, and (2) the I and C and human factor engineering issues of integrating analog and digital I and C systems in hybrid control rooms. (authors)

  12. Co-ordinated research programme on benchmark study for the seismic analysis and testing of WWER-type nuclear power plants. V. 4G. Paks NPP: Analysis and testing. Working material

    International Nuclear Information System (INIS)

    1999-01-01

    In August 1991, following the SMiRT-11 Conference in Tokyo, a Technical Committee Meeting was held on the 'Seismic safety issues relating to existing NPPs'. The Proceedings of this TCM was subsequently compiled in an IAEA Working Material. One of the main recommendations of this TCM, called for the harmonization of criteria and methods used in Member States in seismic reassessment and upgrading of existing NPPs. Twenty four institutions from thirteen countries participated in the CRP named 'Benchmark study for the seismic analysis and testing of WWER type NPPs'. Two types of WWER reactors (WWER-1000 and WWER-440/213) selected for benchmarking. Kozloduy NPP Units 5/6 and Paks NPP represented these respectively as prototypes. Consistent with the recommendations of the TCM and the working paper prepared by the subsequent Consultants' Meeting, the focal activity of the CRP was the benchmarking exercises. A similar methodology was followed both for Paks NPP and Kozloduy NPP Unit 5. Firstly, the NPP (mainly the reactor building) was tested using a blast loading generated by a series of explosions from buried TNT charges. Records from this test were obtained at several free field locations (both downhole and surface), foundation mat, various elevations of structures as well as some tanks and the stack. Then the benchmark participants were provided with structural drawings, soil data and the free field record of the blast experiment. Their task was to make a blind prediction of the response at preselected locations. The analytical results from these participants were then compared with the results from the test. Although the benchmarking exercises constituted the focus of the CRP, there were many other interesting problems related to the seismic safety of WWER type NPPs which were addressed by the participants. These involved generic studies, i.e. codes and standards used in original WWER designs and their comparison with current international practice; seismic analysis

  13. Polish media and public opinion on NPP Mochovce commissioning

    International Nuclear Information System (INIS)

    Latek, Stanislaw

    1999-01-01

    The so called 'Mochovce Problem' was one of the major topics in Polish media in the period from May to July 1998. The nuclear power plant commissioning caused an unexpectedly strong reaction, especially in the newspapers, slightly less so in electronic media. Faced with clearly hostile media reaction to Mochovce NPP, the National Atomic Energy Agency representatives, together with atomic and nuclear experts, undertook to change these attitudes. In numerous interviews, letters to the editors and talks with journalists, they attempted to correct the mistakes, explain the true safety situation in the nuclear power plant, by whom it was constructed, who supervised and tested the systems and so on. The completion of Mochovce NPP construction improved significantly the electricity balance in Slovakia, thus decreasing the pressure for continuing the operation of older Bohunice V1 units beyond their design lifetime. For this reason, as well as in view of striving for improvement in environmental factors beyond Polish southern border, especially after Kyoto/97 decisions on greenhouse gases emissions, the public opinion in Poland should support the Mochovce NPP construction. In 1996 Poland has signed with Slovakia a bilateral inter-governmental agreement on the prompt notification on nuclear accidents and on the cooperation in the nuclear safety and radiological protection matters. On the basis of this agreement the experts from Polish National Atomic Energy Agency are in perpetual contact with Slovakian Nuclear Regulatory Body and in each and every moment can obtain full and comprehensive information on the plant parameters iportant for nuclear safety. The experts explanations, together with the NAEA top management visit to the plant itself, brought some results. The media became less aggressive, and Polish public and authorities - contrary to the Austrians - do not protest loudly against the commissioning of this newest European NPP. Now, in December 1998, the tune of

  14. Concreting organization during Chernobylsk NPP construction

    International Nuclear Information System (INIS)

    Lysyuk, R.I.; Kareva, A.P.

    1984-01-01

    Conreting organization during the Chernobylsk NPP construction is described. Processes of extra heavy concrete production and placement, which specific mass constitutes 4t/m 3 at the age of 28 days wiath metallic aggregates and 3.3-3.5 t/m 3 at the same age without aggregates, are considered in short. Basic characteristics of this concrete are presented. At the 4th power unit labour contents for construction works were a 1.5 times lower as compared to the 3rd power unit erection. This progress was achieved by round-the-clock operation of the concrete plant with the 800 m 3 /day output and also by utilization of special equipment for mechanized concrete placement: concrete pumps, automatic concrete mixer, manipulators and concrete pipelines

  15. NPP Cernavoda Unit 2 Financing Completion Works

    International Nuclear Information System (INIS)

    Chirica, T.; Stefanescu, A.; Constantin, C.; Dobrin, M.

    2002-01-01

    NPP Cernavoda Unit 2 completion is the highest priority of the Romanian power sector strategy. The nuclear energy represents, through its technological features of adopted solution (a CANDU nuclear power plant) and also through technological and economical performance indicators, the best solution to fulfill the demands concerning the sustainable development and the electricity request. The guidelines of energy strategy regarding the nuclear sector development in Romania are framing in the general policy for energy system development at least costs and they are responding to requests concerning the environment and people protection. The paper presents the financing alternatives for Unit 2 completion works taking into consideration the financing market conditions. The paper presents the impact of the financing conditions on the project efficiency, as well as the facilities offered by the Romanian Government in order to support this project. (author)

  16. New Emergency control center of Slovenske Elektrarne Bohunice NPP

    International Nuclear Information System (INIS)

    Pecko, E.

    2012-01-01

    Emergency preparedness of nuclear power plant and operation assurance in case of a possible emergency calls to have devices for emergency response with equipment for rapid detection and continuous evaluation of anticipated events. Chief executive body designated to manage a nuclear power plant during major events is the emergency committee (EC). Emergency Committee is a part of the Emergency Response Organization (ERO). The following centers are on alert to ensure the activities of the ERO - Emergency Response office: - control room (CR) and emergency control room (ECR); - emergency management center (EMC); - Monitoring Centre (MC); - emergency backup control center (EBCC); - congregations of civil protection (CP) and CP shelters; - communications with warning and notification system (VARVYR). From a historical and practical point of view in the vicinity of Jaslovske Bohunice has been set up a joint emergency control center. The center was located on the territory of the former already inoperative V1 NPP. V1 NPP is currently integrated into the organizational structure of JAVYS. Operating Bohunice V2 NPP plant is a designated part of the Slovenske Elektrarne, a. s., whose majority owner is an Italian operator ENEL. In terms of various relevant factors, it was decided to build a new emergency management center on the territory of operating V2 NPP, meet the current standards.

  17. The Chernobyl NPP decommissioning: Current status and alternatives

    International Nuclear Information System (INIS)

    Mikolaitchouk, H.; Steinberg, N.

    1996-01-01

    After the Chernobyl accident of April 26, 1986, many contradictory decisions were taken concerning the Chernobyl nuclear power plant (NPP) future. The principal source of contradictions was a deadline for a final shutdown of the Chernobyl NPP units. Alterations in a political and socioeconomic environment resulted in the latest decision of the Ukrainian Authorities about 2000 as a deadline for a beginning of the Chernobyl NPP decommissioning. The date seems a sound compromise among the parties concerned. However, in order to meet the data a lot of work should be done. First of all, a decommissioning strategy has to be established. The problem is complicated due to both site-specific aspects and an absence of proven solutions for the RBMK-type reactor decommissioning. In the paper the problem of decommissioning option selection is considered taking into account an influence of the following factors: relevant legislative and regulatory requirements; resources required to carry out decommissioning (man-power, equipment, technologies, waste management infrastructure, etc.); radiological and physical status of the plant, including structural integrity and predictable age and weather effects; impact of planned activities at the destroyed unit 4 and within the 30-km exclusion zone of the Chernobyl NPP; planed use of the site; socio-economic considerations

  18. Low level radioactive waste disposal in Kozloduy NPP in Bulgaria

    International Nuclear Information System (INIS)

    Stanchev, V.

    2001-01-01

    Kozloduy NPP is the biggest power plant in the Republic of Bulgaria. It is in operation since 1974 and for the past 25 years it has generated over 263 billion kWh electric power. The NPP share in the total electric production in 1998 was about 50%. It has six units in operation - four WWER 440 B-230 and two WWER 1000 B-320. In the nuclear reactor operation the generation of radioactive waste (RAW) is an inevitable process. The waste must be conditioned, stored and disposed of in a safe manner. There are no national radioactive waste disposal facilities, for waste generated by an NPP, in Bulgaria to the moment. This situation necessitates the storage of operational RAW to be carried out on site for a long period of time (30 to 50 years). Following the principle for protection of human health and environment now and in the future, Kozloduy NPP adopted the concept for conditioning the RAW to a stable solid form and placing the waste in a package which should keep its features for a sufficiently long term so that the package can be safely transported to the disposal site. (author)

  19. Regulatory review of NPP Krsko Periodic Safety Review

    International Nuclear Information System (INIS)

    Lovincic, D.; Muehleisen, A.; Persic, A.

    2004-01-01

    At the request of the Slovenian Nuclear Safety Administration (SNSA), Krsko NPP prepared a Periodic Safety Review (PSR) program in January 2001. This is the first PSR of NPP Krsko, the only nuclear power plant in Slovenia. The program was reviewed by the IAEA mission in May 2001 and approved by SNSA in July 2001. The program is made in accordance with the IAEA Safety Guide 'Periodic Safety Review of Operational Nuclear Power Plants' No. 50-SG-012 and with European practice. It contains a systematic review of operation of the NPP Krsko, including the review of the changes as a result of the modernization of the facility. The main tasks of PSR are review of plant status for each safety factor, development of aging and life cycle management program, review of seismic design and PSHA analysis and update of regulatory compliance program. The prioritization process of findings and action plan are also important tasks of PSR. The basic safety factors of the PSR review are: Operational Experience, Safety Assessment and Analyses, Equipment Qualification and Ageing Management, Safety Culture, Emergency Planing, Environmental Impact and Radioactive Waste, Compliance with license requirements and Prioritization. It had been agreed that SNSA will have reviewed all PSR reports generated during the PSR process. At the end of 2003 the PSR Summary Report with selected recommendations for action plan was completed and delivered to SNSA for review. The paper presents regulatory review of NPP Krsko PSR with emphasis on the evaluation of the PSR issues ranking process. (author)

  20. Co-ordinated research programme on benchmark study for the seismic analysis and testing of WWER-type nuclear power plants. V. 4E. Paks NPP: Analysis and testing. Working material

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    1995-07-01

    In August 1991, following the SMiRT-11 Conference in Tokyo, a Technical Committee Meeting was held on the 'Seismic safety issues relating to existing NPPs'. The Proceedings of this TCM was subsequently compiled in an IAEA Working Material. One of the main recommendations of this TCM, called for the harmonization of criteria and methods used in Member States in seismic reassessment and upgrading of existing NPPs. Twenty four institutions from thirteen countries participated in the CRP named 'Benchmark study for the seismic analysis and testing of WWER type NPPs'. Two types of WWER reactors (WWER-1000 and WWER-440/213) selected for benchmarking. Kozloduy NPP Units 5/6 and Paks NPP represented these respectively as prototypes. Consistent with the recommendations of the TCM and the working paper prepared by the subsequent Consultants' Meeting, the focal activity of the CRP was the benchmarking exercises. A similar methodology was followed both for Paks NPP and Kozloduy NPP Unit 5. Firstly, the NPP (mainly the reactor building) was tested using a blast loading generated by a series of explosions from buried TNT charges. Records from this test were obtained at several free field locations (both downhole and surface), foundation mat, various elevations of structures as well as some tanks and the stack. Then the benchmark participants were provided with structural drawings, soil data and the free field record of the blast experiment. Their task was to make a blind prediction of the response at preselected locations. The analytical results from these participants were then compared with the results from the test. Although the benchmarking exercises constituted the focus of the CRP, there were many other interesting problems related to the seismic safety of WWER type NPPs which were addressed by the participants. These involved generic studies, i.e. codes and standards used in original WWER designs and their comparison with current international practice; seismic analysis

  1. Co-ordinated research programme on benchmark study for the seismic analysis and testing of WWER-type nuclear power plants. V. 3H. Kozloduy NPP units 5/6: Analysis and testing. Working material

    International Nuclear Information System (INIS)

    1999-01-01

    In August 1991, following the SMiRT-11 Conference in Tokyo, a Technical Committee Meeting was held on the 'Seismic safety issues relating to existing NPPs'. The Proceedings of this TCM was subsequently compiled in an IAEA Working Material. One of the main recommendations of this TCM, called for the harmonization of criteria and methods used in Member States in seismic reassessment and upgrading of existing NPPs. Twenty four institutions from thirteen countries participated in the CRP named 'Benchmark study for the seismic analysis and testing of WWER type NPPs'. Two types of WWER reactors (WWER-1000 and WWER-440/213) selected for benchmarking. Kozloduy NPP Units 5/6 and Paks NPP represented these respectively as prototypes. Consistent with the recommendations of the TCM and the working paper prepared by the subsequent Consultants' Meeting, the focal activity of the CRP was the benchmarking exercises. A similar methodology was followed both for Paks NPP and Kozloduy NPP Unit 5. Firstly, the NPP (mainly the reactor building) was tested using a blast loading generated by a series of explosions from buried TNT charges. Records from this test were obtained at several free field locations (both downhole and surface), foundation mat, various elevations of structures as well as some tanks and the stack. Then the benchmark participants were provided with structural drawings, soil data and the free field record of the blast experiment. Their task was to make a blind prediction of the response at preselected locations. The analytical results from these participants were then compared with the results from the test. Although the benchmarking exercises constituted the focus of the CRP, there were many other interesting problems related to the seismic safety of WWER type NPPs which were addressed by the participants. These involved generic studies, i.e. codes and standards used in original WWER designs and their comparison with current international practice; seismic analysis

  2. Co-ordinated research programme on benchmark study for the seismic analysis and testing of WWER-type nuclear power plants. V. 3F. Kozloduy NPP units 5/6: Analysis and testing. Working material

    International Nuclear Information System (INIS)

    1999-01-01

    In August 1991, following the SMiRT-11 Conference in Tokyo, a Technical Committee Meeting was held on the 'Seismic safety issues relating to existing NPPs'. The Proceedings of this TCM was subsequently compiled in an IAEA Working Material. One of the main recommendations of this TCM, called for the harmonization of criteria and methods used in Member States in seismic reassessment and upgrading of existing NPPs. Twenty four institutions from thirteen countries participated in the CRP named 'Benchmark study for the seismic analysis and testing of WWER type NPPs'. Two types of WWER reactors (WWER-1000 and WWER-440/213) selected for benchmarking. Kozloduy NPP Units 5/6 and Paks NPP represented these respectively as prototypes. Consistent with the recommendations of the TCM and the working paper prepared by the subsequent Consultants' Meeting, the focal activity of the CRP was the benchmarking exercises. A similar methodology was followed both for Paks NPP and Kozloduy NPP Unit 5. Firstly, the NPP (mainly the reactor building) was tested using a blast loading generated by a series of explosions from buried TNT charges. Records from this test were obtained at several free field locations (both downhole and surface), foundation mat, various elevations of structures as well as some tanks and the stack. Then the benchmark participants were provided with structural drawings, soil data and the free field record of the blast experiment. Their task was to make a blind prediction of the response at preselected locations. The analytical results from these participants were then compared with the results from the test. Although the benchmarking exercises constituted the focus of the CRP, there were many other interesting problems related to the seismic safety of WWER type NPPs which were addressed by the participants. These involved generic studies, i.e. codes and standards used in original WWER designs and their comparison with current international practice; seismic analysis

  3. Co-ordinated research programme on benchmark study for the seismic analysis and testing of WWER-type nuclear power plants. V. 4E. Paks NPP: Analysis and testing. Working material

    International Nuclear Information System (INIS)

    1995-01-01

    In August 1991, following the SMiRT-11 Conference in Tokyo, a Technical Committee Meeting was held on the 'Seismic safety issues relating to existing NPPs'. The Proceedings of this TCM was subsequently compiled in an IAEA Working Material. One of the main recommendations of this TCM, called for the harmonization of criteria and methods used in Member States in seismic reassessment and upgrading of existing NPPs. Twenty four institutions from thirteen countries participated in the CRP named 'Benchmark study for the seismic analysis and testing of WWER type NPPs'. Two types of WWER reactors (WWER-1000 and WWER-440/213) selected for benchmarking. Kozloduy NPP Units 5/6 and Paks NPP represented these respectively as prototypes. Consistent with the recommendations of the TCM and the working paper prepared by the subsequent Consultants' Meeting, the focal activity of the CRP was the benchmarking exercises. A similar methodology was followed both for Paks NPP and Kozloduy NPP Unit 5. Firstly, the NPP (mainly the reactor building) was tested using a blast loading generated by a series of explosions from buried TNT charges. Records from this test were obtained at several free field locations (both downhole and surface), foundation mat, various elevations of structures as well as some tanks and the stack. Then the benchmark participants were provided with structural drawings, soil data and the free field record of the blast experiment. Their task was to make a blind prediction of the response at preselected locations. The analytical results from these participants were then compared with the results from the test. Although the benchmarking exercises constituted the focus of the CRP, there were many other interesting problems related to the seismic safety of WWER type NPPs which were addressed by the participants. These involved generic studies, i.e. codes and standards used in original WWER designs and their comparison with current international practice; seismic analysis

  4. On the accounting of technology progress rates and obsolescence of production funds when determining depreciation for NPP renovation

    International Nuclear Information System (INIS)

    Khachyan, G.A.; Petrov, I.M.; Vorob'ev, I.E.; Nizhnik, I.A.; Pylypyuk, R.V.

    1986-01-01

    Questions, related to determining the economically grounded service life of NPP main production funds are considered. It is recommended to differentiate the depreciation standards by the operation duration. It is proposed to arrange the NPP buildings taking into account modern rates of technical progress in power engineering

  5. Economical aspect of the decommissioning for NPP

    International Nuclear Information System (INIS)

    Daryoko, M.

    1998-01-01

    The estimated, analysed and founding of the economical aspect at decommissioning of Nuclear Power Plant (NPP) have been studied. The data that have been obtained from literature, then the calculation and analysing have been done base to the future condition. The cost for NPP decommissioning depend on the internal factor such as type, capacity and safe storage time, and the external factor such as policy, manpower and the technology preparation. The successfulness of funding, depend on the rate of inflation, discount rate of interest and the currency fluctuation. For the internal factor, the influence of the type of the reactor (BWR or PWR) to the decommissioning cost is negligible, the big reactor capacity (±1100 MW), and the safe storage between 30 to 100 years are recommended, and for the external factor, specially Indonesia, to meet the future need the ratio of decommissioning cost and capital cost will be lower than in develop countries at the present (10%). The ratio between decommissioning fund and electricity generation cost relatively very low, are more less than 1.79 % for 30 years safe storage, and discount rate of interest 3%, or more less than 0.30 % for safe storage 30 years, and discount rate of interest 6%. (author)

  6. Central alarm system replacement in NPP Krsko

    International Nuclear Information System (INIS)

    Cicvaric, D.; Susnic, M.; Djetelic, N.

    2004-01-01

    Current NPP Krsko central alarm system consists of three main segments. Main Control Board alarm system (BETA 1000), Ventilation Control Board alarm system (BETA 1000) and Electrical Control Board alarm system (BETA 1100). All sections are equipped with specific BetaTone audible alarms and silence, acknowledge as well as test push buttons. The main reason for central alarm system replacement is system obsolescence and problems with maintenance, due to lack of spare parts. Other issue is lack of system redundancy, which could lead to loss of several Alarm Light Boxes in the event of particular power supply failure. Current central alarm system does not provide means of alarm optimization, grouping or prioritization. There are three main options for central alarm system replacement: Conventional annunciator system, hybrid annunciator system and advanced alarm system. Advanced alarm system implementation requires Main Control Board upgrade, integration of process instrumentation and plant process computer as well as long time for replacement. NPP Krsko has decided to implement hybrid alarm system with patchwork approach. The new central alarm system will be stand alone, digital, with advanced filtering and alarm grouping options. Sequence of event recorder will be linked with plant process computer and time synchronized with redundant GPS signal. Advanced functions such as link to plant procedures will be implemented with plant process computer upgrade in outage 2006. Central alarm system replacement is due in outage 2004.(author)

  7. Safety aspects of NPP ageing

    International Nuclear Information System (INIS)

    1995-01-01

    Preparation of safety practices on assessment and management of aging of major NPP components important to safety, CRP on management of aging of concrete containment buildings, CRP on management of aging of in-containment instrumentation and control cables are outlined

  8. IAEA Leads Operational Safety Mission to Smolensk Nuclear Power Plant

    International Nuclear Information System (INIS)

    2011-01-01

    2008 and Rostov NPP in 2005. General information about OSART missions can be found on the IAEA Website. Background An OSART mission is designed as a review of programmes and activities essential to operational safety. It is not a regulatory inspection, nor is it a design review or a substitute for an exhaustive assessment of the plant's overall safety status. Experts participating in the IAEA's June 2010 International Conference on Operational Safety of Nuclear Power Plants (NPP) reviewed the experience of the OSART programme and concluded: In OSART missions NPPs are assessed against IAEA Safety Standards which reflect the current international consensus on what constitutes a high level of safety; and OSART recommendations and suggestions are of utmost importance for operational safety improvement of NPPs. (IAEA)

  9. Standard protocol for evaluation of environmental transfer factors around NPP sites

    International Nuclear Information System (INIS)

    Hegde, A.G.; Verma, P.C.; Rao, D.D.

    2009-01-01

    This document presents the standard procedures for evaluation of site specific environmental transfer factors around NPP sites. The scope of this document is to provide standard protocol to be followed for evaluation of environmental transfer factors around NPP sites. The studies on transfer factors are being carried out at various NPP sites under DAE-BRNS projects for evaluation of site specific transfer factors for radionuclides released from power plants. This document contains a common methodology in terms of sampling, processing, measurements and analysis of elemental/radionuclides, while keeping the site specific requirements also in place. (author)

  10. There is possible damages on the nuclear power plants (NPP) of so-frontiers states and operations of the forces of the civil defense (cd) in these situations

    International Nuclear Information System (INIS)

    Ocaqov, H.O.

    2002-01-01

    Full text: According to our forecasts if any type of accident occurs at the nuclear power plant located on the territory of Armenian Republic the radioactive pollution will spread over the territory of Azerbaijan. The injection of radioactive substances and formation of a polluted zone on the significant area including some parts of the territory of Nakhichevan Republic, Nagorny Karabakh, Kelbajar and Kedabek regions are possible. In extraordinary situations occurred due to radiation accidents or under detection of a radioactive pollution the restriction of subsequent irradiation of the population is accomplished by protective measures. These measures are connected to the breakdown of normal live ability of the population, economic and social functioning of the territory i.e. it is an interference causing not only economic and ecological damage but also having adverse influence on the population. A decrease of risk to a possible low level (optimization) is carried out due to the following two circumstances: A time it of risk of a potential irradiation from all possible sources of radiation is regulated and for each source the boundary of risk is established; Under a decrease of potential radiation risk there is the minimum level of risk, below which a risk is considered as negligible and further decrease of risk is inexpedient. Under the accident control and under a realization of urgent reestablishment works it is recommended not to admit an equivalent dose (ED) of radiation more than approximately 500 mSv except for actions on rescue of life or on prevention of further development of the accident and the irradiation of large number of people. Assumed increase of radiation is admitted only for men older than 30 years only on voluntary written approval and preliminary informing them about possible doses of radiation at accident liquidation and about a risk for their health. The persons attracted for realization of emergency and saving work, are considered on the

  11. Drawings: Kozloduy NPP

    International Nuclear Information System (INIS)

    Boyadjiev, Z.

    1995-01-01

    This paper includes drawings of Kozloduy nuclear power plant needed for study for the seismic analysis and testing. It covers the list and schemes of safety and safety related systems for normal operation as well as protection and control systems

  12. Co-ordinated research programme on benchmark study for the seismic analysis and testing of WWER-type nuclear power plants. V. 3I. Kozloduy NPP units 5/6: Analysis and testing. Working material

    International Nuclear Information System (INIS)

    1999-01-01

    In August 1991, following the SMiRT-11 Conference in Tokyo, a Technical Committee Meeting was held on the 'Seismic safety issues relating to existing NPPs'. The Proceedings of this TCM was subsequently compiled in an IAEA Working Material. One of the main recommendations of this TCM, called for the harmonization of criteria and methods used in Member States in seismic reassessment and upgrading of existing NPPs. Twenty four institutions from thirteen countries participated in the CRP named 'Benchmark study for the seismic analysis and testing of WWER type NPPs'. Two types of WWER reactors (WWER-1000 and WWER-440/213) selected for benchmarking. Kozloduy NPP Units 5/6 and Paks NPP represented these respectively as prototypes. Consistent with the recommendations of the TCM and the working paper prepared by the subsequent Consultants' Meeting, the focal activity of the CRP was the benchmarking exercises. A similar methodology was followed both for Paks NPP and Kozloduy NPP Unit 5. Firstly, the NPP (mainly the reactor building) was tested using a blast loading generated by a series of explosions from buried TNT charges. Records from this test were obtained at several free field locations (both downhole and surface), foundation mat, various elevations of structures as well as some tanks and the stack. Then the benchmark participants were provided with structural drawings, soil data and the free field record of the blast experiment. Their task was to make a blind prediction of the response at preselected locations. The analytical results from these participants were then compared with the results from the test. Although the benchmarking exercises constituted the focus of the CRP, there were many other interesting problems related to the seismic safety of WWER type NPPs which were addressed by the participants. These involved generic studies, i.e. codes and standards used in original WWER designs and their comparison with current international practice; seismic analysis

  13. Automated personal dosimetry monitoring system for NPP

    International Nuclear Information System (INIS)

    Chanyshev, E.; Chechyotkin, N.; Kondratev, A.; Plyshevskaya, D.

    2006-01-01

    Full text: Radiation safety of personnel at nuclear power plants (NPP) is a priority aim. Degree of radiation exposure of personnel is defined by many factors: NPP design, operation of equipment, organizational management of radiation hazardous works and, certainly, safety culture of every employee. Automated Personal Dosimetry Monitoring System (A.P.D.M.S.) is applied at all nuclear power plants nowadays in Russia to eliminate the possibility of occupational radiation exposure beyond regulated level under different modes of NPP operation. A.P.D.M.S. provides individual radiation dose registration. In the paper the efforts of Design Bureau 'Promengineering' in construction of software and hardware complex of A.P.D.M.S. (S.H.W. A.P.D.M.S.) for NPP with PWR are presented. The developed complex is intended to automatize activities of radiation safety department when caring out individual dosimetry control. The complex covers all main processes concerning individual monitoring of external and internal radiation exposure as well as dose recording, management, and planning. S.H.W. A.P.D.M.S. is a multi-purpose system which software was designed on the modular approach. This approach presumes modification and extension of software using new components (modules) without changes in other components. Such structure makes the system flexible and allows modifying it in case of implementation a new radiation safety requirements and extending the scope of dosimetry monitoring. That gives the possibility to include with time new kinds of dosimetry control for Russian NPP in compliance with IAEA recommendations, for instance, control of the equivalent dose rate to the skin and the equivalent dose rate to the lens of the eye S.H.W. A.P.D.M.S. provides dosimetry control as follows: Current monitoring of external radiation exposure: - Gamma radiation dose measurement using radio-photoluminescent personal dosimeters. - Neutron radiation dose measurement using thermoluminescent

  14. NPP Krsko full scope simulator verification and qualification

    International Nuclear Information System (INIS)

    Krajnc, B.; Glaser, B.; Novsak, M.; Spiler, J.

    1998-01-01

    NPP Krsko (NEK) will, as a part of the Modernization plan, obtain also Krsko Full Scope Simulator (KFSS). Contract has been awarded to CAE Electronics for the design, construction and integration. KFSS will support in real time, the training for the complete range of operation, which can be performed from the main control room and some selected plant areas (remote shutdown panels, etc). Based on the lessons learned on development of NPP Krsko Basic Principle Simulator we decided for active approach. That means that NPP Krsko personnel will be heavily involved into all phases of KFSS development and testing. Since NPP Krsko is going to replace the existing steam generators, raise the nominal power and perform necessary modifications to support the power uprate, it was decided that the development of the KFSS will be conducted in two steps: 1. Development of the models as well as all the hardware interface in the MCR for the existing plant Cycle 15 and then, 2. Models and hardware will be modified, added or replaced as needed to take into account the steam generator replacement and plant uprate projects. In spite of the fact that the simulator will be used for the training of the plant operators for the uprated conditions and with new steam generators, the upper described approach was selected since we want to be sure that the models will at the beginning adequately simulate the existing plant. For the existing conditions we have available reference data for different plant conditions, as well as data for different plant transients. By verifying that simulator will be able adequately simulate the existing conditions the level of confidence for the uprated simulator will be much higher. This is of special importance since it will support initial training for modernized plant conditions. In this paper the plan for verification and qualification of KFSS as well as the amount of the work needed on NPP Krsko side to develop the test acceptance criteria will be presented.(author)

  15. Use of operator training and simulating complexes for development of NPP APCS

    International Nuclear Information System (INIS)

    Malkin, S.D.; Rakitin, I.D.; Sivokon', V.P.

    2002-01-01

    The evolution of NPP educational facilities - from systems of training of personnel to power simulating systems for the development of Automatic Process Control System (APCS) and safety analysis is followed. High efficiency of simulating systems application for the development of NPP APCS including optimization of man-machine system interface was shown by experiments of USA, France, Japan, United Kingdom, conforming examples were given [ru

  16. Remote technology in RBMK-1000 spent fuel management at NPP site

    International Nuclear Information System (INIS)

    Makarchuk, T.F.; Kozlov, Y.V.; Tikhonov, N.S.; Tokarenko, A.I.; Spichev, V.V.; Kaljazin, N.N.

    1999-01-01

    The report describes the remote technologies employed in the nuclear power plant with RBMK-1000 type. Spent fuel transfer and handling operations at reactor (AR) and away from reactor (AFR) on reactor site (RS) facilities are illustrated by the example of the Leningradskaya NPP and are typical for all NPPs with RBMK-1000. The current approach to spent fuel management at NPP sites is also presented. (author)

  17. Survey of public participation potential regarding the Muria NPP program

    International Nuclear Information System (INIS)

    Yarianto-SBS; Sri Hariani Syarif; Heni Susiati; Imam Hamzah; Fepriadi

    2003-01-01

    Socio-culture aspect is a part of site feasibility evaluation of Nuclear Power Plant (NPP)program. Indonesia is under going democratization, therefore the paradigm of development has also been changed where the people have freedom or liberty and they can express their opinion independently. The people are significant factor that involving in the decision making of regional development.Even the socio-culture, such as social riot can reject the site. Therefore socio-culture aspect should be considered in the NPP site evaluation. The first step of the study,mapping of public participation potential should be conducted by field survey. The method used in there search is quantitative approach with field survey guided by questioner without any treatment of object sampled. Qualitative approach was also conducted by in-depth interview technique to collect more detailed information. Information were collected from general public without any stratification in the 10 km radius from NPP site. Sampling method used was full random sampling technique. The results of survey show that the most of the people have significant potential for participating in the NPP Program. Conducive atmosphere should be maintained by social setting, therefore the present good momentum will not be lost. (author)

  18. Implementation of the II. Stage decommissioning of A1 NPP

    International Nuclear Information System (INIS)

    Ficher, T.

    2015-01-01

    Presentation is focused on the implementation of the II. stage decommissioning of A1 NPP. Introductory part focuses on brief characteristics of the power plant with a history of operation, basic technical parameters and actions that were made after operation. The next section describes the basic schedule for decommissioning, structure of management and implementation of the II. stage decommissioning of the A1 NPP and objectives of the individual stages. The last and largest part of the presentation is devoted to detailed description of the II. stage decommissioning of the A1 NPP, its individual tasks and verbal and visual description of the activities that were performed. Presented is decommissioning of the technology and construction of external objects NPP A1 including storage tanks for liquid RAW, next are presented activities carried out in the Main Production Unit - decommissioning of non-operating technologies in various places/rooms, management of waste arising from these activities, treatment of case of A1 long-term spent fuel storage and long-term spent fuel storage. The subsequent section is devoted to the management and handling of contaminated soil, concrete and construction waste, including management of VLLW. (authors)

  19. Crushed stone production plant for NPP building

    International Nuclear Information System (INIS)

    Obolenskij, V.Ya.

    1982-01-01

    The project of the granite-crushed stone quarry - the large modern plant producing building materials, is presented. The quarry is designated for providing NPP and other power objects building with high-strength crushed stone. The plant consists of: quarry; crushing-sorting plant with maintenance objects arranged on its ground; basis and service stores of explosive materials; tail facility and purifying systems; water supply purifying stations; water storage basin. The plant is reserved for 2335 thousand m 3 yearly utoput of crushed stone; the staff consists of 535 persons, the budgeted cost of building is 26.6 million rubles. Physicochemical characteristics of granosyenites of the ''Granitnoye'' deposit - the raw material resource base of the plant and technological scheme of the crushing-sorting plant are given. Planned measures on building organization and recultivation of disturbed grounds are presented

  20. N-16 monitors: Almaraz NPP experience

    International Nuclear Information System (INIS)

    Adrada, J.

    1997-01-01

    Almaraz Nuclear Power Plant has installed N-16 monitors - one per steam generator - to control the leakage rate through the steam generator tubes after the application of leak before break (LBB) criteria for the top tube sheet (TTS). After several years of operation with the N-16 monitors, Almaraz NPP experience may be summarized as follows: N-16 monitors are very useful to follow the steam generator leak rate trend and to detect an incipient tube rupture; but they do not provide an exact absolute leak rate value, mainly when there are small leaks. The evolution of the measured N-16 leak rates varies along the fuel cycle, with the same trend for the 3 steam generators. This behaviour is associated with the primary water chemistry evolution along the cycle

  1. Feature article. Fukushima Daiichi NPP accident

    International Nuclear Information System (INIS)

    Ekarinai, Masashi; Ake, Yutaka; Narabayashi, Tadashi

    2011-01-01

    This special feature article consisted of five reports and the minutes of emergency discussion meeting on Fukushima Daiichi Nuclear Power Plant (NPP) accident. Effects of the accident on future electricity supply of electric utilities and also on business development of nuclear industries were discussed. Activities of senior network team of atomic energy society of Japan (AESJ) to conduct severe accident analysis and early restoration from the accident were introduced. Circulating injection reactor cooling system and zeolite decontamination system of accumulated contaminated water was proposed. Effects of the accident on overseas reaction on nuclear development were also reported as well as personal experience of the professor in the US west coast on communications. (T. Tanaka)

  2. Electrohydraulic system to control NPP turbines

    International Nuclear Information System (INIS)

    Kosyak, Yu.F.; Virchenko, M.A.; Rozhanskij, V.E.; Rokhlenko, V.Yu.; Gapunin, A.Ya.; Zhornitskaya, T.Ya.; Rasskazov, I.Eh.; Butsenko, V.N.; Brajnin, L.S.; Makarenko, N.I.

    1985-01-01

    Operation regimes of electrohydraulic regulation system (EHRS) of NPP turbines, designed to control the turbine in start-up and working conditions, have been decribed. In start-up regimes EHRS ensures the testing of control valves of the turbine, the turn of the turbine from zero to the nominal rotation frequency (automatic, semiautomatic and manual regulation), turbine acceleration to test safety automatic systems, gradual change in rotation frequency during generator synchronization with circuit. Under working conditions EHRS ensures the maintenance of frequency, power and vapour pressure before the turbine. A block diagram of EHRS is presented. Sensors and electronic part of EHRS are supplied with triple reservation, which ensures a high relaibility of the system

  3. Cernavoda NPP Unit 1 - a plant of several generations

    International Nuclear Information System (INIS)

    Rotaru, I.; Metes, M.; Anghelescu, M.S.

    2001-01-01

    The paper reflects some key aspects related to the shift of generations during the project's development, including the present stage. Further, the place of Cernavoda NPP Unit 1 in the Romanian power sector and among other nuclear stations in the world is presented. The operational performances achieved 'in service' up to the end of 1999, with reference to the performance indicators for electrical energy production, nuclear safety, radiation protection, radioactive wastes and nuclear fuel are illustrated. For all of these items, comparisons are performed with similar indicators reported by other worldwide nuclear power plants, in order to assess our results. Finally, some comments about Cernavoda NPP Unit 2 project status and need to completion and commissioning it are included. (authors)

  4. Safety analysis of Ignalina NPP during shutdown conditions

    International Nuclear Information System (INIS)

    Kaliatka, A.; Uspuras, E.

    2000-01-01

    The accident analysis for the Ignalina NPP with RBMK-1500 reactors at normal operating conditions and at minimum controlled power level (during startup of the reactor) has been performed in the frame of the project I n-Depth Safety Assessment of the Ignalina NPP , which was completed in 1996. However, the plant conditions during the reactor shutdown differ from conditions during reactor operation at full power (equipment status in protection systems, set points for actuation of safety and protection systems, etc.). Results of RELAP5 simulation of two worst initiating events during reactor shutdown - Pressure Header rupture in case of steam reactor cooldown as well as Pressure Header rupture in case of water reactor cooldown are discussed in the paper. Results of analysis shown that reactor are reliably cooled in both cases. Further analysis for all range of initial events during reactor shutdown and at shutdown conditions is recommended. (author)

  5. Plant performance monitoring program at Krsko NPP

    International Nuclear Information System (INIS)

    Bach, B.; Kavsek, D.

    2004-01-01

    A high level of nuclear safety and plant reliability results from the complex interaction of a good design, operational safety and human performance. This is the reason for establishing a set of operational plant safety performance indicators, to enable monitoring of both plant performance and progress. Performance indicators are also used for setting challenging targets and goals for improvement, to gain additional perspective on performance relative to other plants and to provide an indication of a potential need to adjust priorities and resources to achieve improved overall plant performance. A specific indicator trend over a certain period can provide an early warning to plant management to evaluate the causes behind the observed changes. In addition to monitoring the changes and trends, it is also necessary to compare the indicators with identified targets and goals to evaluate performance strengths and weaknesses. Plant Performance Monitoring Program at Krsko NPP defines and ensures consistent collection, processing, analysis and use of predefined relevant plant operational data, providing a quantitative indication of nuclear power plant performance. When the program was developed, the conceptual framework described in IAEA TECDOC-1141 Operational Safety Performance Indicators for Nuclear Power Plants was used as its basis in order to secure that a reasonable set of quantitative indications of operational safety performance would be established. Safe, conservative, cautious and reliable operation of the Krsko NPP is a common goal for all plant personnel. It is provided by continuous assurance of both health and safety of the public and employees according to the plant policy stated in program MD-1 Notranje usmeritve in cilji NEK, which is the top plant program. Establishing a program of monitoring and assessing operational plant safety performance indicators represents effective safety culture of plant personnel.(author)

  6. Professional adaptability of nuclear power plant operators

    International Nuclear Information System (INIS)

    He Xuhong; Huang Xiangrui

    2006-01-01

    The paper concerns in the results of analysis for nuclear power plant (NPP) operator job and analysis for human errors related NPP accidents. Based on the principle of ergonomics a full psychological selection system of the professional adaptability of NPP operators including cognitive ability, personality and psychological health was established. The application way and importance of the professional adaptability research are discussed. (authors)

  7. NPP Krsko Living PSA Concept

    International Nuclear Information System (INIS)

    Vrbanic, I.; Spiler, J.

    2000-01-01

    NPP Krsko developed PSA model of internal and external initiators within the frame of the Individual Plant Examination (IPE) project. Within this project PSA model was used to examine the existing plant design features. In order to continue with use of this PSA model upon the completion of IPE in various risk-informed applications in support of plant operation and evaluations of design changes, an appropriate living PSA concept needed to be defined. The Living PSA concept is in NPP Krsko considered as being a set of activities pursued in order to update existing PSA model in a manner that it appropriately represents the plant design, operation practice and history. Only a PSA model which is being updated in this manner can serve as a platform for plant-specific risk informed applications. The NPP Krsko living PSA concept is based on the following major ponts. First, the baseline PSA model is defined, which is to be maintained and updated and which is to be reference point for any risk-informed application. Second, issues having a potential for impact on baseline PSA model are identified and procedure and responsibilities for their permanent monitoring and evaluation are established. Third, manner is defined in which consequential changes to baseline PSA model are implemented and controlled, together with associated responsibilities. Finally, the process is defined by which the existing version of baseline PSA model is superseded by a new one. Each time a new version of baseline PSA model is released, it would be re-quantified and the results evaluated and interpreted. By documenting these re-quantifications and evaluations of results in a sequence, the track is being kept of changes in long-term averaged risk perspective, represented by long-term averaged frequencies of core damage and pre-defined release categories. These major topics of NPP Krsko living PSA concept are presented and discussed in the paper. (author)

  8. Welding facilities for NPP assembling

    International Nuclear Information System (INIS)

    Rojtenberg, S.S.

    1987-01-01

    Recommendations concerning the choice of equipment for welding in pre-assembling work shops, in the enlarging assembling shops and at the assembling site, are given. Advanced production automatic welders and semiautomatic machines, applied during the NPP equipment assembling as well as automatic machines specially produced for welding the main reactor components and pipelines are described. Automatic and semiautomatic machine and manual welding post supply sources are considered

  9. NPP component maintenance and life management in Russia

    International Nuclear Information System (INIS)

    Tutnov, I.; Lyssakov, V.

    2002-01-01

    This report represents the conceptual strategies (ideas) on life management programs for nuclear power plants. Use of the optimum programs for NPP's NDE, maintenance service, operation and service life can provide the best economic benefit for the utilities. The paper presents general approaches to life management, maintenance service, and risks of operating and service life of NPPs in Russia. The report offers some optimized ways for the solution of these important tasks

  10. Special aspects of implementing advanced fuel cycles at Kalinin NPP

    International Nuclear Information System (INIS)

    Tsvetkov, A.

    2015-01-01

    The presentation showed the experience of different TVSA modifications usage at Kalinin NPP. The strategy of 18 month fuel cycles implementation at uprated power (104%) was also presented. The transition and equilibrium fuel loadings features were discussed. The implementation of burn-up measurement installation MKS-01 was presented, in order to solve the spent nuclear fuel handling and transportation issues due to the increased fuel enrichment and heavy metal mass

  11. A way of Dukovany NPP to privatization and liberalized market

    International Nuclear Information System (INIS)

    Kouklik, I.

    2001-01-01

    This presentation describes the current situation in the Dukovany NPP with two main upcoming future phenomena - privatization of CEZ company and preparation for liberalized electricity market. Considerations about level of safety, investment costs and competitiveness of Dukovany Nuclear Power Plant in liberalization process is described together with a comparison of some safety features of the world's NPPs. Results of this comparison are used for consideration and evaluation of some require modifications effectiveness. (author)

  12. New approach of second Romanian NPP siting

    International Nuclear Information System (INIS)

    Mauna, Traian

    2010-01-01

    The NPP sitting studies in Romania began before 1975. The first Romanian NPP CANDU 6 type reactor gone to erection in 1980 on Cernavoda site planned to have 5 units. Gained the experience from Cernavoda NPP sitting, the first mission of new multi-branch of specialists team was to choose new NPP sites adapting the NPP Cernavoda project to the new parameters of close water cooling circuit and hard less and no rock foundation strata. The studies were carrying out in different stages on the inner rivers Olt, Mures, Somes in Transylvania historical region. This paper tries to reconsider shortly the old analysis according to the last IAEA Safety Standards, taking into account the new NPP generation requirement. Paper is focused on geological aspects and other local sites characteristics. (authors)

  13. SAT-based personnel training for nuclear power plants. Proceedings of a seminar jointly organized under the technical cooperation programme (UKR/4/003) by the International Atomic Energy Agency, Goskomatom of Ukraine, South-Ukrainian NPP and held in Yuzhnoukrainsk, Ukraine, 10-14 April 1995. Working material

    International Nuclear Information System (INIS)

    1995-01-01

    In 1995 the IAEA technical co-operation project ''Training for Safe Operation and Management of Nuclear Power Plants'' (UKR/4/003) has been started with the main goal to improve training systems and training infrastructures to ensure safe and reliable operation of nuclear power plants. As the first step of the project implementation, a seminar on introducing the Systematic Approach to Training for NPP personnel was recommended by the IAEA and G-24 mission on training as one of the primary training needs and priorities of Ukraine. The Seminar was held at the South-Ukrainian Nuclear Power Plant (SUNPP), Yuzhnoukrainsk, Ukraine from 10 to 13 April 1995 and was attended by 35 representatives from GOSKOMATOM, Ministry for Environment Protection and Nuclear Safety, OGPU, and all NPPs of Ukraine

  14. Robot dispatching Scenario for Accident Condition Monitoring of NPP

    International Nuclear Information System (INIS)

    Kim, Jongseog

    2013-01-01

    In March of 2011, unanticipated big size of tsunami attacks Fukushima NPP, this accident results in explosion of containment building. Tokyo electric power of Japan couldn't dispatch a robot for monitoring of containment inside. USA Packbot robot used for desert war in Iraq was supplied to Fukushima NPP for monitoring of high radiation area. Packbot also couldn't reach deep inside of Fukushima NPP due to short length of power cable. Japanese robot 'Queens' also failed to complete a mission due to communication problem between robot and operator. I think major reason of these robot failures is absence of robot dispatching scenario. If there was a scenario and a rehearsal for monitoring during or after accident, these unanticipated obstacles could be overcome. Robot dispatching scenario studied for accident of nuclear power plant was described herein. Study on scenario of robot dispatching is performed. Flying robot is regarded as good choice for accident monitoring. Walking robot with arm equipped is good for emergency valve close. Short time work and shift work by several robots can be a solution for high radiation area. Thin and soft cable with rolling reel can be a good solution for long time work and good communication

  15. Qinshan CANDU NPP outage performance improvement through benchmarking

    International Nuclear Information System (INIS)

    Jiang Fuming

    2005-01-01

    With the increasingly fierce competition in the deregulated Energy Market, the optimization of outage duration has become one of the focal points for the Nuclear Power Plant owners around the world. People are seeking various ways to shorten the outage duration of NPP. Great efforts have been made in the Light Water Reactor (LWR) family with the concept of benchmarking and evaluation, which great reduced the outage duration and improved outage performance. The average capacity factor of LWRs has been greatly improved over the last three decades, which now is close to 90%. CANDU (Pressurized Heavy Water Reactor) stations, with its unique feature of on power refueling, of nuclear fuel remaining in the reactor all through the planned outage, have given raise to more stringent safety requirements during planned outage. In addition, the above feature gives more variations to the critical path of planned outage in different station. In order to benchmarking again the best practices in the CANDU stations, Third Qinshan Nuclear Power Company (TQNPC) have initiated the benchmarking program among the CANDU stations aiming to standardize the outage maintenance windows and optimize the outage duration. The initial benchmarking has resulted the optimization of outage duration in Qinshan CANDU NPP and the formulation of its first long-term outage plan. This paper describes the benchmarking works that have been proven to be useful for optimizing outage duration in Qinshan CANDU NPP, and the vision of further optimize the duration with joint effort from the CANDU community. (authors)

  16. NPP backfitting and services

    International Nuclear Information System (INIS)

    Pauli, W.; Blumer, U.; Edelmann, X.

    1988-01-01

    The Swiss nuclear power stations are not only of different design (PWR, BWR), but also have been built by several system suppliers over the last 20 years. Consequently, an individual approach has to be adopted for the backfitting and services for each of the five units in operation. Part of the ongoing maintenance effort for nuclear power plants currently in operation is the idea to extend their operating lifetime as long as it appears economic. Although many of the components have been designed for a life of 40 years, their operating period may be extended considerably, provided that proper measures are taken to keep the plants in optimal conditions for this goal. Such measures for a plant life extension program are: assessment of records of actual operating history; additional monitoring where necessary for temperatures, stress, strain, etc.; non-destructive examination techniques; destructive examination of samples removed from service; thermohydraulic and structural analysis for fatigue and fracture; preventive maintenance; repairs; replacement with components of better design and/or material; installation of additions and redundancies where safety is important. 2 refs

  17. Application of ant colony optimization in NPP classification fault location

    International Nuclear Information System (INIS)

    Xie Chunli; Liu Yongkuo; Xia Hong

    2009-01-01

    Nuclear Power Plant is a highly complex structural system with high safety requirements. Fault location appears to be particularly important to enhance its safety. Ant Colony Optimization is a new type of optimization algorithm, which is used in the fault location and classification of nuclear power plants in this paper. Taking the main coolant system of the first loop as the study object, using VB6.0 programming technology, the NPP fault location system is designed, and is tested against the related data in the literature. Test results show that the ant colony optimization can be used in the accurate classification fault location in the nuclear power plants. (authors)

  18. Metamorphosis of NPP A1, V1, V2

    International Nuclear Information System (INIS)

    Dobak, D.; Moncekova, M.

    2005-01-01

    In this book the history of construction, commissioning and exploitation of NPP A1, NPP V1 and NPP V2 in Jaslovske Bohunice is presented on documentary photos. Vicinity around of these NPPs is presented, too

  19. Ignalina NPP: living and working conditions

    International Nuclear Information System (INIS)

    Chiuzhas, A.

    1998-01-01

    The conference was devoted to discuss the social problems related with the operation of Ignalina NPP. The main topics are the following: analysis of public opinion of surrounding region of Ignalina NPP including neighbouring Daugavpils district in Latvia, environment impact evaluation of Daugavpils district, assessment of the influence of Ignalina NPP operation to the development of business in the region, investigation of problems of Visaginas town - residence of Ignalina NPP personnel. The specificity of Visaginas (former Sniechkus) is defined by the majority of non-native Lithuanians living there. Cultural transformation and political organization of the region were surveyed as well

  20. Joint probability safety assessment for NPP defense infrastructure against extreme external natural hazards

    International Nuclear Information System (INIS)

    Guilin, L.; Defu, L.; Huajun, L.; Fengqing, W.; Tao, Z.

    2012-01-01

    With the increasing tendency of natural hazards, the typhoon, hurricane and tropical Cyclone induced surge, wave, precipitation, flood and wind as extreme external loads menacing Nuclear Power Plants (NPP) in coastal and inland provinces of China. For all of planned, designed And constructed NPP the National Nuclear Safety Administration of China and IAEA recommended Probable Maximum Hurricane /Typhoon/(PMH/T), Probable Maximum Storm Surge (PMSS), Probable Maximum Flood (PMF), Design Basis Flood (DBF) as safety regulations for NPP defense infrastructures. This paper discusses the joint probability analysis of simultaneous occurrence typhoon induced extreme external hazards and compare with IAEA 2006-2009 recommended safety regulation design criteria for some NPP defense infrastructures along China coast. (authors)

  1. Safety improvement and results of commissioning of Mochovce NPP WWER 440/213

    International Nuclear Information System (INIS)

    Lipar, M.

    1998-01-01

    Mochovce NPP is the last one of this kind and compared to its predecessors, it is characterized by several modifications which contribute to the improvement of the safety level. In addition based on Nuclear Regulatory Authority requirements and based on documents: - IAEA - Safety Issues and their ranking for NPP WWER 440/213, - IAEA - Safety Improvement of Mochovce NPP Project Review Mission, - Riskaudit - Evaluation of the Mochovce NPP Safety Improvements. Additional safety measures have been implemented before commissioning. The consortium EUCOM (FRAMATOME - SIEMENS), SKODA Praha, ENERGOPROJEKT Praha, Russian organizations and VUJE Trnava Nuclear Power Plants research institute were selected for design and implementation of the safety measures. The papers summarized, safety requirements, safety measures implemented, results of commissioning and results of safety analysis report evaluation. (author)

  2. Tendencies of ecological changes in the region of Ignalina NPP and in Lake Drukshiai

    International Nuclear Information System (INIS)

    Pashkauskas, R.; Mazeika, J.; Baubinas, R.

    1999-01-01

    Since 1979, when the construction of the Ignalina Nuclear Power Plant started, a group of specialists from Lithuania research and academic institutions began to investigate both Lake Drukshiai - the cooler of the Ignalina NPP and the neighbouring area. The investigations were aimed not only at monitoring the environmental consequences of the Ignalina NPP impact but also at forecasting changes of the ecosystems. The State Scientific Program 'Ignalina Nuclear Power Plant and the Environment' was the result of final stage of complex investigations. This conference paper contains data on the changes of thermal state and water balance of Lake Drukshiai, the effect of permanent thermal and chemical pollution on the chemical composition and hydrochemical regime, the pollution of the lake water, the geochemical-contaminated state, the condition, dynamics and the changes of hydrobiont communities in Lake Drukshiai. Radioecological and eco toxicological state of Ignalina NPP region and Lake Drukshiai is estimated as well as changes in Lake Drukshiai and Ignalina NPP surrounding area ecosystems under the combine anthropogenic impact of the plant influence are elucidated. The findings on medical and biological studies in the Ignalina NPP influence population zone and the evidence of impact of Ignalina NPP on social-territorial processes in the region are presented as well

  3. Industry Operating Experience Process at Krsko NPP

    International Nuclear Information System (INIS)

    Bach, B.; Bozin, B.; Cizmek, R.

    2012-01-01

    Experience has shown that number of minor events and near misses, usually without immediate or significant impact to plant safety and reliability, are precursors of significant or severe events due to the same or similar root or apparent cause(s). It is therefore desirable to identify and analyze weaknesses of the precursor problems (events) in order to prevent occurrence of significant events. Theoretically, significant events could be prevented from occurring if the root cause(s) of these precursor problems could be identified and eliminated. The Operating Experience Program identifies such event precursors and by reporting them to the industry, plant specific corrective actions can be taken to prevent events at other operational plants. The intent of the Operating Experience Program is therefore to improve nuclear power plant safety and reliability of the operating nuclear power plants. Each plant develops its own Operating Experience Program in order to learn from the in-house operating experience as well as from the world community of nuclear plants. The effective use of operating experience includes analyzing both plant and industry events in order to identify fundamental weaknesses and then determining appropriate plant-specific actions that will minimize the likelihood of similar events. Learning and applying the lessons from operating experience is an integral part of station safety culture and is encouraged by managers throughout the top plant administrative programs and procedures. Krsko NPP is developed it own Operating Experience Program by using the most relevant INPO/WANO/IAEA guidelines as well as its own knowledge, skills an operating practice. The Operating Experience Program is a part of the Corrective Action Program, which is among top management programs, thus program is strongly encouraged by top management. The purpose of Operating Experience Program is to provide guidance for using, sharing, and evaluating operating experience information

  4. Irradiation Embrittlement Monitoring Programs of RPV's in the Slovak Republic NPP's

    International Nuclear Information System (INIS)

    Kupca, Ludovik

    2006-01-01

    Four types of surveillance programs were (are) realized in Slovak NPP's: 'Standard Surveillance Specimen Program' (SSSP) was finished in Jaslovske Bohunice V-2 Nuclear Power Plant (NPP) Units 3 and 4, 'Extended Surveillance Specimen Program' (ESSP), was prepared for Jaslovske Bohunice NPP V-2 with aim to validate the SSSP results, For the Mochovce NPP Unit 1 and 2 was prepared completely new surveillance program 'Modern Surveillance Specimen Program' (MSSP), based on the philosophy that the results of MSSP must be available during all NPP service life, For the Bohunice V-1 NPP was finished 'New Surveillance Specimen Program' (NSSP) coordinated by IAEA, which gave arguments for prolongation of service life these units for minimum 20 years, New Advanced Surveillance Specimen Program (ASSP) for Bohunice V-2 NPP (units 3 and 4) and Mochovce NPP (units 1, 2) is approved now. ASSP is dealing with the irradiation embrittlement of heat affected zone (HAZ) and RPV's austenitic cladding, which were not evaluated till this time in surveillance programs. SSSP started in 1979 and was finished in 1990. ESSP program started in 1995 and will be finished in 2007, was prepared with aim of: increasing of neutron fluence measurement accuracy, substantial improvement the irradiation temperature measurement, fixed orientation of samples to the centre of the reactor core, minimum differences of neutron dose for all the Charpy-V notch and COD specimens, the dose rate effect evaluation. In the year 1996 was started the new surveillance specimen program for the Mochovce RPV's unit-1 and 2, based on the fundamental postulate - to provide the irradiation embrittlement monitoring till the end of units operation. The 'New Surveillance Specimen Program' (NSSP) prepared in the year 1999 for the Bohunice V-1 NPP was finished in the year 2004. Main goal of this program was to evaluate the weld material properties degradation due to the irradiation and recovery efficiency by annealing too. The

  5. Jose Cabrera NPP

    International Nuclear Information System (INIS)

    Diez, P.

    2004-01-01

    During 2003, the Jose Cabrera nuclear power plant (JCNPP) operated without any incidents involving an undue risk to the population or environment. The year 2003 was the Plant's 35th year of operation, and during that time it has provided 33.209 million kilowatt-hours to the electric grid. The Plant set a record for continuous operation with 386 days of uninterrupted operation. The Plant had an outage for the 27th refueling and for equipment and systems maintenance, inspection and testing activities. The Plant reported nine events to the Administration that were classified as zero on the International Nuclear Event Scale (INES) and another event classified as level 1. AENOR performance the audit for renewing certificate UNE-EN ISO-9001, and for tracking environmental management systems as per UNE-EN ISO 14001, with satisfactory results. The dose around the Plant caused by plant operation has been insignificant. For the first time in the Spanish industry, the Plant has implemented an integrated safety system that encompasses all the plant's safety-related activities

  6. NPP lifetime philosophy: the transatlantic difference

    International Nuclear Information System (INIS)

    Mowry, Christofer

    1998-01-01

    Fundamental institutional and cultural differences in the transatlantic nuclear power industries, and in particular those between the Nordic countries and the United States, have driven divergent plant life management strategies -strategies resulting in distinctly different plant performance. Recognition of the linkage between three key components of overall Nuclear Power Plant (NPP) performance - yearly O and M costs, safety, and effective plant lifetime -is based on different institutional perspectives. In the Nordic countries, explicit recognition of this linkage has been historically translated into an integrated approach to plant performance. American NPPs, however, have been forced to focus primarily on near term O and M performance and regulatory mandated investment. While Nordic NPPs view capital investment in plant lifetime management and modernization as necessary to avoid declining plant performance and the cost of replacement power, American NPPs exhibit reluctance for such investments due to the difficulty of justifying the associated short-term costs. The diverging histories of two NPPs of the same vintage and design, one in Sweden and one in the United States, exemplify the potential ramifications of these approaches. The Swedish plant continues to operate with excellent performance indicators, while undertaking a comprehensive and long-term modernization program. The American facility is likely to be decommissioned due to unsustainable economic performance. (author)

  7. NPP Krsko Lifetime Extension - Business Impact for Hrvatska Elektroprivreda

    International Nuclear Information System (INIS)

    Vrankic, K.; Krejci, M.; Lebegner, J.

    2006-01-01

    This paper deals with the analysis of possible business impacts for HEP in the case of NPP Krsko life extension. Due to numerous reasons nuclear power plant life extension of ten to twenty years is a common procedure abroad. Having this practise in mind as well as other circumstances in Croatian and Slovenian electric power system, the extension of NPP Krsko lifetime is considered to be a possible scenario. Foreseeable impacts of this decision are evaluated primarily with consideration of its effect on HEPs projected cash flows, though other aspects will be addressed as well. Preserving a well maintained production facility with an extraordinary operational record and stable, or possibly falling overall production costs seems as a very rational choice. This is particularly true having in mind expected rise of electricity demand and energy prices in the region. Having NPP Krsko in operation beyond 2023 implies that no replacement source for NPP Krsko capacity needs to be built. This means avoiding all costs connected with the construction and operation of the replacement plant, assuming it will be fossil fuelled. Due to the high uncertainty of the future fossil fuel prices, the avoidance of replacement plant operational cost is likely to prove as highly rewarding. It should be kept in mind that avoided costs also include the replacement plant greenhouse gases emission costs, thus further enlarging the list of value adding impacts. The latter is valid anticipating the ratification of the Kyoto protocol and joining the European emission trading scheme. In addition to that, the extension of NPP Krsko lifetime would mean that the majority of costs connected with the decommissioning and final waste disposal can be postponed further down the time line. This will have very positive financial and possibly technological impact. Other value creating effects for HEP that are foreseeable as a consequence of the plant lifetime extension include: maintaining the knowledge of

  8. A comparison of the Kozloduy NPP and Temelin NPP I and C projects

    International Nuclear Information System (INIS)

    Cook, B.M.

    2004-01-01

    Because Kozloduy NPP and Temelin NPP are both VVER 1000 plants of roughly the same vintage, they are very similar in design. However, from the viewpoint of their I and C modernization projects, there are significant differences between these plants. Some of these differences stem from the evolution of I and C technology over the relatively short period between the two projects. Other differences arise from the fact that the Kozloduy project is a phased upgrade of the I and C systems in an operating plant while the Temelin project was a 'one time' installation of the entire plant I and C system. This paper discusses these differences as well as trends in the nuclear I and C field that will shape the industry in the future. In addition to technology evolution, the comparative advantages or problems in phased upgrade versus 'one time' installations are discussed. Conclusions drawn provide insight for the planning of future I and C upgrades in VVERs and other types of nuclear power plants. (author)

  9. Integrated tool for NPP lifetime management in Spain

    Energy Technology Data Exchange (ETDEWEB)

    Francia, L. [UNESA, Madrid (Spain); Lopez de Santa Maria, J. [ASCO-Vandellos 2 NPPs l' Hospitalet de l' Infant, Tarragona (Spain); Cardoso, A. [Tecnatom SA, Madrid (Spain)

    2001-07-01

    The project for the Integrated Nuclear Power Plant Lifetime Management System SIGEVI (Sistema Integrado de GEstion de VIda de Centrales Nucleares) was initiated in April 1998 and finalized in December 2000, the main objective of the project being to develop a computer application facilitating the assessment of the condition and lifetime of nuclear power plant components. This constituted the second phase of a further-reaching project on NPP Lifetime Management. During the first phase of this project, carried out between 1992 and 1995, the methodology and strategy for the lifetime management of the Spanish NPP's were developed. Among others, degradation phenomena were assessed and the most adequate methods for their monitoring were defined. The SIGEVI Project has been performed under the management of UNESA (Spanish Electricity Association) and with the collaboration of different engineering firms and research institutes (Tecnatom, Empresarios Agrupados, Ufisa, Initec and IIT), with Vandellos II as the pilot plant. The rest of the Spanish NPP's have also actively participated through the Project Steering Committee. The following sections describe the scope, the structure and the main functionalities of the system SIGEVI. (authors)

  10. Enhancing NPP Safety Through an Effective Dependability Management

    Energy Technology Data Exchange (ETDEWEB)

    Vieru, G., E-mail: g_vieru@yahoo.com [AREN, Bucharest (Romania)

    2014-10-15

    Taking into account the importance of the continuous improvement of the performance and reliability of a NPP and practical measures to strengthen nuclear safety and security, it is to be noted that a good management for a nuclear power reactor involves a ''good dependability management'' of the activities, such as: Reliability, Availability, Maintainability (RAM) and maintenance support. In order to evaluate certain safety assessment criteria intended to be applied at the level of the nuclear reactor unit management, equipment dependability indicators and their impact over the availability and reactor safety have to be evaluated. Reactor equipment dependability indicators provide a quantitative indication of equipment RAM performances (Reliability, Availability and Maintenance). One of the important benefits of maintenance and failure data gathering is that it can be used as a support of probabilistic safety assessment (PSA). Also, a good dependability management implementation may be used to complement reactor level unit performance indicators in the field of safe operation, maintenance and improving operating parameters, as well as for Strengthening Safety and Improving Reliability of a NPP. This paper underlines the importance of nuclear safety and security as prerequisites for nuclear power. In addition, it demonstrates how different technical aspects, through implementation of a good dependability management, contribute to a strengthened safety and an improvement of availability of the NPP through dependability indicators determination and evaluation. (author)

  11. Financing nuclear projects. Case study: Unit 2 Cernavoda NPP

    International Nuclear Information System (INIS)

    Chirica, T.; Pall, S.; Lebedev, A.; Dobrin, M.

    2003-01-01

    The implementation of a Nuclear Power Plant (NPP) in a country is a major undertaking for all entities involved, due to the necessity of planning work and co-ordination of the implementation process of the different fields of interest, starting with the governmental authorities and ending with the people. Having in view the specific investment cost (relatively high) for a NPP, to find an adequate financing structure is possible through an iterative process that involves first an assessment of the technical performances of the project and second, the mathematical modelling of the financing structure effects on the project. In this respect, the paper proposed will be focused on the main steps needed in order to promote an investment project in nuclear field, starting with the decision phase, providing the documentations requested by the local and international authorities to promote the project and ending with the negotiation of the contracts (commercial contract, financing contract, power purchase contract, etc.) The case study will be focused on the phases achieved in order to promote the Unit 2 Cernavoda NPP completion works project. (author)

  12. Integrated tool for NPP lifetime management in Spain

    International Nuclear Information System (INIS)

    Francia, L.; Lopez de Santa Maria, J.; Cardoso, A.

    2001-01-01

    The project for the Integrated Nuclear Power Plant Lifetime Management System SIGEVI (Sistema Integrado de GEstion de VIda de Centrales Nucleares) was initiated in April 1998 and finalized in December 2000, the main objective of the project being to develop a computer application facilitating the assessment of the condition and lifetime of nuclear power plant components. This constituted the second phase of a further-reaching project on NPP Lifetime Management. During the first phase of this project, carried out between 1992 and 1995, the methodology and strategy for the lifetime management of the Spanish NPP's were developed. Among others, degradation phenomena were assessed and the most adequate methods for their monitoring were defined. The SIGEVI Project has been performed under the management of UNESA (Spanish Electricity Association) and with the collaboration of different engineering firms and research institutes (Tecnatom, Empresarios Agrupados, Ufisa, Initec and IIT), with Vandellos II as the pilot plant. The rest of the Spanish NPP's have also actively participated through the Project Steering Committee. The following sections describe the scope, the structure and the main functionalities of the system SIGEVI. (authors)

  13. Radiation monitoring in the NPP environment, control of radioactivity in NPP-environment system

    International Nuclear Information System (INIS)

    Egorov, Yu.A.

    1987-01-01

    Problems of radiation monitoring and control of the NPP-environment system (NPPES) are considered. Radiation control system at the NPP and in the environment provides for the control of the NPP, considered as the source of radioactive releases in the environment and for the environmental radiation climate control. It is shown, that the radiation control of the NPP-environment system must be based on the ecological normalization principles of the NPP environmental impacts. Ecological normalization should be individual for the NPP region of each ecosystem. The necessity to organize and conduct radiation ecological monitoring in the NPP regions is pointed out. Radiation ecological monitoring will provide for both environmental current radiation control and information for mathematical models, used in the NPPES radiation control

  14. Specific problems in Kozloduy municipality, concerning NPP operation and decommissioning

    International Nuclear Information System (INIS)

    Pironkova, L.

    2000-01-01

    The only nuclear power plant in Bulgaria, which operates for 25 years is located in Kozloduy. Kozloduy municipality is situated in the northern part of Danube plane, includes the administrative center and four villages. It is 200 km far from Sofia and 80 km from the regional center Vratza. The Kozloduy NPP operates 6 units of total capacity 3760 MW, producing more than 40% of the electricity needs in Bulgaria. Settled and recurring problems of the municipality are related to economic, geographical, demographic and administration issues. Future problems will be related to forthcoming reactor shutdown and decommissioning. This involves economic problems, possible bankruptcies of local firms servicing the NPP, decreasing budget and living standard, expected restrictions of social programs, increasing unemployment, possible changes in demographic structure of population

  15. Social problems and territorial experiences from closing down Tihange NPP

    International Nuclear Information System (INIS)

    Lizin, A.M.

    2000-01-01

    The town of Huy, better known by the name of the NPP Tihange, which is the nearby village, accounts to 50,000 inhabitants including the surrounding region. An Advisory Committee at a community level was set up concerned with the emergency services and the NPP related problems. One of the outstanding problems is the planned interim storage for radioactive waste. The unsolved question of long term storage in Belgium resulted in the fact that general situation is not promising for launching the debate on the future of nuclear energy. The mission of the delegation from Huy visited Tokaimura with the aim to measure the scale of real responsibilities and the concern against nuclear power that the accident created in the population

  16. Safety reassessment of the Paks NPP (the AGNES project)

    Energy Technology Data Exchange (ETDEWEB)

    Gado, J [Hungarian Academy of Sciences, Budapest (Hungary). Central Research Inst. for Physics; Bajsz, J; Cserhati, A; Elter, J [Paksi Atomeroemue Vallalat, Paks (Hungary); Hollo, E [Energiagazdalkodasi Intezet, Budapest (Hungary); Kovacs, K [EROTERV Engineering and Contractor Co (Hungary); Maroti, L [Hungarian Academy of Sciences, Budapest (Hungary). Central Research Inst. for Physics; Miko, S [Paksi Atomeroemue Vallalat, Paks (Hungary); Techy, Z [Energiagazdalkodasi Intezet, Budapest (Hungary); Vidovszky, I [Hungarian Academy of Sciences, Budapest (Hungary). Central Research Inst. for Physics

    1996-12-31

    The reassessment of the Paks NPP safety according to internationally recognized criteria of the Advanced General and New Evaluation of Safety (AGNES) project is outlined. The Paks NPP consists of four WWER-440/V-213 units. The following groups of analysis have been performed: system analysis and description; analysis of design basis accidents; severe accidents analysis; level 1 probabilistic safety analysis. Postulated accidents (PA) and Anticipated Operational Occurrences (AOO) are estimated in detail for the following initiating events: increase/decrease in secondary heat removal; decrease in primary coolant inventory; increase/decrease of reactor coolant inventory; reactivity and power distribution anomalies; analysis of transients with the failure of reactor scram (ATWS); pressurized thermal shock analyses. Severe accident analysis was made for the accidents on in-vessel phase and containment phase, for radioactive release and for accident management.

  17. Axial blanket enrichment optimization of the NPP Krsko fuel

    International Nuclear Information System (INIS)

    Kromar, M.; Kurincic, B.

    2001-01-01

    In this paper optimal axial blanket enrichment of the NPP Krsko fuel is investigated. Since the optimization is dictated by economic categories that can significantly vary in time, two step approach is applied. In the first step simple relationship between the equivalent change in enrichment of axial blankets and central fuel region is established. The relationship is afterwards processed with economic criteria and constraints to obtain optimal axial blanket enrichment. In the analysis realistic NPP Krsko conditions are considered. Except for the fuel enrichment all other fuel characteristics are the same as in the fuel used in the few most recent cycles. A typical reload cycle after the plant power uprate is examined. Analysis has shown that the current blanket enrichment is close to the optimal. Blanket enrichment reduction results in an approximately 100 000 US$ savings per fuel cycle.(author)

  18. Some questions of optimization in the personnel dosimetry at NPP

    International Nuclear Information System (INIS)

    Liberman, A.N.; Petrov, V.I.; Bronshtejn, I.Eh.

    1978-01-01

    Some possible ways of optimizing the radiation monitoring of personnel of nuclear power plants (NPP) are considered. For premises within the zone of a strict operating regime, it is proposed that the intervals between periods of monitoring be shortened if the operating conditions are normal. To improve the monitoring of activity of water in the primary circuit, it is considered desirable to provide all NPP with a system of automatic radiation monitoring having input to the control panel. Where the work involves opening of primary circuit communications or deactivation of equipment and also in cases of emergency, it is proposed that, in addition to routine monitoring, gamma-spectrometric or radiochemical analysis of the isototip composition of contaminants be carried out. Because of the absence of measurable quantities of incorporated radionuclides in the vast majority of those working in the strict regime zone, it is suggested that the number of persons subject to systematic individual monitoring of internal radiation be limited

  19. Low-dose effects hypothesis and observations on NPP personal

    Energy Technology Data Exchange (ETDEWEB)

    Georgieva, R.; Acheva, A.; Boteva, R.; Chobanova, N.; Djounova, J.; Gyuleva, I.; Ivanova, K.; Kurchatova, G.; Milchev, A.; Negoicheva, K.; Nikolov, V.; Panova, D.; Pejankov, I.; Rupova, I.; Stankova, K.; Zacharieva, E. [Radiobiology Department, National Centre of Radiobiology and Radiation Protection, Sofia (Bulgaria)

    2013-07-01

    In the modern world the use of various sources of ionizing radiation is nearly ubiquitous. They have numerous applications in industry, medicine, science, agriculture, etc. Radiation doses to workers nevertheless are commensurable to the natural background exposure. Published data on the health effects of occupational radiation exposure are often contradictory. Addressing the issue of „negative” (bystander effects, genomic instability) and „positive” (adaptive response, radiation hormesis) effects of low doses is important and has a significant social and economic impact. In this paper we summarize the results of our extensive monitoring of nuclear power plant (NPP) staff. We believe it is a cohort suitable for analysis of health effects at low doses, because of their good medical and dosimetric control. Our results rather support the idea of absence of adverse health effects in NPP workers. (author)

  20. 'Kozloduy' NPP geological environment as a barrier against radionuclide migration

    International Nuclear Information System (INIS)

    Antonov, D.

    2000-01-01

    The aim of this report is to present an analysis of the geological settings along Kozloduy NPP area from the viewpoint of a natural, protective barrier against unacceptable radionuclides migration in the environment. Possible sources of such migration could be an eventual accident in an active nuclear plant; radioactive releases from decommissioned Power Units or from temporary or permanent radioactive waste repositories. The report is directed mainly to the last case, and especially to the site selection for near surface short lived low and intermediate level (LILW) radioactive repository. The main conclusion of the geological settings assessment and of the many years monitoring is that the Kozloduy NPP area offers good possibilities for site selection of LILW repository. (author)

  1. Safety reassessment of the Paks NPP (the AGNES project)

    International Nuclear Information System (INIS)

    Gado, J.; Hollo, E.; Kovacs, K.; Maroti, L.; Techy, Z.; Vidovszky, I.

    1995-01-01

    The reassessment of the Paks NPP safety according to internationally recognized criteria of the Advanced General and New Evaluation of Safety (AGNES) project is outlined. The Paks NPP consists of four WWER-440/V-213 units. The following groups of analysis have been performed: system analysis and description; analysis of design basis accidents; severe accidents analysis; level 1 probabilistic safety analysis. Postulated accidents (PA) and Anticipated Operational Occurrences (AOO) are estimated in detail for the following initiating events: increase/decrease in secondary heat removal; decrease in primary coolant inventory; increase/decrease of reactor coolant inventory; reactivity and power distribution anomalies; analysis of transients with the failure of reactor scram (ATWS); pressurized thermal shock analyses. Severe accident analysis was made for the accidents on in-vessel phase and containment phase, for radioactive release and for accident management

  2. Display systems for NPP control

    International Nuclear Information System (INIS)

    Rozov, S.S.

    1988-01-01

    Main trends in development of display systems used as the means for image displaying in NPP control systems are considered. It is shown that colour display devices appear to be the most universal means for concentrated data presentation. Along with digital means the display systems provide for high-speed response, sufficient for operative control of executive mechanisms. A conclusion is drawn that further development of display systems will move towards creation of large colour fields (on reflection base or with multicolour gas-discharge elements)

  3. Emergency preparedness at Barsebaeck NPP in Sweden

    International Nuclear Information System (INIS)

    Olsson, R.; Lindvall, C.

    1998-01-01

    On-site emergency preparedness plan at Barsebaeck NPP is presented. In an emergency the responsibility of the NPP is to alarm the emergency organizations, spend all efforts to restore safe operation, assess the potential source term as to size and time, protect their own personnel, inform personnel and public. Detailed emergency procedures overview is provided

  4. Safety culture in Ignalina NPP, regulatory view

    Energy Technology Data Exchange (ETDEWEB)

    Maksimovas, G [VATESI (Lithuania)

    1997-09-01

    The presentation describes how success on the way to a high level Safety Culture in Ignalina NPP may be achieved by daily, well motivated activities with good attitude and proper management participation, ensuring the development and proper implementation of Safety Culture principles within the activities of Operational organization of Ignalina NPP.

  5. Safety culture in Ignalina NPP, regulatory view

    International Nuclear Information System (INIS)

    Maksimovas, G.

    1997-01-01

    The presentation describes how success on the way to a high level Safety Culture in Ignalina NPP may be achieved by daily, well motivated activities with good attitude and proper management participation, ensuring the development and proper implementation of Safety Culture principles within the activities of Operational organization of Ignalina NPP

  6. NPP Bohunice experience with ASSET services

    International Nuclear Information System (INIS)

    Klimo, J.

    1996-01-01

    The general description of Bohunice NPP ASSET experience history was given at the last annual workshop in 1995. In my short presentation I would like to pay attention to the progress in this area which was achieved at our NPP during the last year. (author)

  7. NPP Bohunice experience with ASSET services

    Energy Technology Data Exchange (ETDEWEB)

    Klimo, J [Bohunice NPP (Slovakia)

    1997-12-31

    The general description of Bohunice NPP ASSET experience history was given at the last annual workshop in 1995. In my short presentation I would like to pay attention to the progress in this area which was achieved at our NPP during the last year. (author).

  8. Bohunice V1 NPP upgrading programme

    International Nuclear Information System (INIS)

    Kerak, J.

    2001-01-01

    The paper describes whole process of Bohunice V1 NPP nuclear safety and operational reliability level increase which has been performed since units commissioning (1. unit in 1978, 2. unit in 1980), continued Small Reconstruction (1991 -1993) and finished Gradual Upgrading(1994 -2000). The main purpose is to last stage -Gradual upgrading of Bohunice V1 NPP. (author)

  9. Chernobyl NPP accident. Overcoming experience. Acquired lessons

    International Nuclear Information System (INIS)

    Nosovskij, A.V.; Vasil'chenko, V.N.; Klyuchnikov, A.A.; Prister, B.S.

    2006-01-01

    This book is devoted to the 20 anniversary of accident on the Chernobyl NPP unit 4. History of construction, causes of the accident and its consequences, actions for its mitigation are described. Modern situation with Chernobyl NPP decommissioning and transferring of 'Ukryttya' shelter into ecologically safe system are mentioned. The future of Chernobyl site and exclusion zone was discussed

  10. Strengthening the control on radioactive sources - Cernavoda NPP operating experience

    International Nuclear Information System (INIS)

    Daian, I.; Simionov, V.

    2005-01-01

    This paper presents the national legal frame governing the radioactive source management, legislative requirements introduced during last years and current status of controlled radioactive sources program at Cernavoda NPP. Romania has only one nuclear power plant, Cernavoda NPP, equipped with five PHWR - CANDU-6 Canadian type reactors - with a 700 MW(e) gross capacity each, in different implementation stages. The legal representative of the nuclear power production sector in Romania is 'Nuclearelectrica' S.A. National Company (SNN). SNN is a governmental company controlled by the Ministry of Industry and Trade. The company has headquarters in Bucharest and three subsidiaries: - CNE-PROD Cernavoda (CNE-PROD), operating the Cernavoda NPP - Unit 1; - CNE-INVEST Cernavoda, in charge with the completion of Unit 2 and with the preservation of Units 3,4,5; - Nuclear Fuel Plant in Pitesti (FCN). Unit 1 is in commercial operation since December 2, 1996, Unit 2 is under construction (80% completed) and Units 3, 4, 5 are under preservation. The operation of Cernavoda NPP implies use of radioactive sources that may present a significant risk to health, property and the environment when control is lost. Within the last years CNCAN issued new regulations stating clear responsibilities for the different institutions involved in radioactive materials control programs. To manage radioactive sources in a safe way CNE-PROD established and revised the Controlled Radioactive Sources Program, as part of Station Radiation Protection Regulation, ensuring strict recording of the radioactive sources and their usage, ensuring physical and radiological security, protecting the personnel, members of the public and the environment from the hazards of ionizing radiation during the life cycle of the plant, including decommissioning. (authors)

  11. Strengthening the control on radioactive sources - Cernavoda NPP operating experience

    International Nuclear Information System (INIS)

    Daian, I.; Simionov, V.

    2005-01-01

    Full text: This paper presents the national legal frame governing the radioactive source management, legislative requirements introduced during last years and current status of controlled radioactive sources program at Cernavoda NPP. Romania has only one nuclear power plant, Cernavoda NPP, equipped with five PHWR - CANDU-6 Canadian type reactors - with a 700 MW(e) gross capacity each, in different implementation stages. The legal representative of the nuclear power production sector in Romania is 'Nuclearelectrica' S.A. National Company (SNN). SNN is a governmental company controlled by the Ministry of Industry and Trade. The company has headquarters in Bucharest and three subsidiaries: - CNE-PROD Cernavoda (CNE-PROD), operating the Cernavoda NPP - Unit 1; - CNE-INVEST Cernavoda, in charge with the completion of Unit 2 and with the preservation of Units 3,4,5; - Nuclear Fuel Plant in Pitesti (FCN). Unit 1 is in commercial operation since December 2, 1996, Unit 2 is under construction (80% completed) and Units 3, 4, 5 are under preservation. The operation of Cernavoda NPP implies use of radioactive sources that may present a significant risk to health, property and the environment when control is lost. Within the last years CNCAN issued new regulations stating clear responsibilities for the different institutions involved in radioactive materials control programs. To manage radioactive sources in a safe way CNE-PROD established and revised the Controlled Radioactive Sources Program, as part of Station Radiation Protection Regulation, ensuring strict recording of the radioactive sources and their usage, ensuring physical and radiological security, protecting the personnel, members of the public and the environment from the hazards of ionizing radiation during the life cycle of the plant. (authors)

  12. International Collaboration in the Development of NPP Software

    International Nuclear Information System (INIS)

    Jiang, S.; Liu, L.; Yu, H.

    2015-01-01

    In this paper, we first review the progress and current status of international collaboration and technical exchange in the development of nuclear power plant (NPP) software by The State Nuclear Power Software Development Center (SNPSDC) in China. Then we discuss the importance of the international collaboration and exchange in the trend of globalisation of NPP technology. We also identify the role and contribution of professional women in this process. SNPSDC, the first professional software development centre for NPP in China, has been developing COSINE — a self-reliance NPP design and analysis software product with China brand—since 2010. Through participating in OECD/NEA’s joint projects, such as ROSA-2 Project, PKL–3 Project, HYMERES Project and ATLAS Project, SNPSDC shared data with other countries involved with respect to particular areas, such as high quality reactor thermal hydraulics test data. SNPSDC’s engineers have also been actively participating in international technical and research exchange for presenting their innovative work to the community while learning from peers. Our record shows that over 30 papers have been presented in international conferences with respect to nuclear reactor thermal hydraulics, safety analysis, reactor physics and software engineering within the past 4 years. The above international collaboration and technical exchange helped SNPSDC’s engineers to keep up with the state-of-art technology in this field. The large amount of valuable experimental data transferred to SNPSDC ensured the functionality, usability and reliability of software while greatly reduced the cost and shortened the cycle of development. Female engineers and other employees of SNPSDC either drove or got actively involved in a lot of aspects of the above collaboration and exchange, such as technical communication, business negotiation and overseas affairs management. These professional women played an irreplaceable role in this project by

  13. Seismic characterization of the NPP Krsko site

    International Nuclear Information System (INIS)

    Obreza, J.

    2000-01-01

    The goal of NPP Krsko PSA Project Update was the inclusion of plant changes (i.e. configuration/operational related) through the period January 1, 1993 till the OUTAGE99 (April 1999) into the integrated Internal/External Level 1/Level 2 NPP Krsko PSA RISK SPECTRUM model. NPP Krsko is located on seismotectonic plate. Highest earthquake was recorded in 1917 with magnitude 5.8 at a distance of 7-9 km. Site (founded) on Pliocene sediments which are as deep as several hundred meters. No surface faulting at the Krsko site has been observed and thus it is not to be expected. NPP Krsko is equipped with seismic instrumentation, which allows it to complete OBE (SSE). The seismic PSA successfully showed high seismic margin at Krsko plant. NPP Krsko seismic design is based on US regulations and standards

  14. Electrical Grid Conditioning For First NPP Integration, a Systems Engineering Approach Incorporating Quality Function Deployment

    Energy Technology Data Exchange (ETDEWEB)

    Pwani, Henry; James, J. [KEPCO International Nuclear Graduate School, Ulsan (Korea, Republic of)

    2013-10-15

    Nuclear power plant has a high potential to cause serious harm to environment as evidenced by effects of Fukushima and Chernobyl accidents. A reliable electrical power is required for a NPP to facilitate cooling after a shutdown. Failure of electrical power supply during shutdown increases core damage probability. Research shows that a total of 39% of LOOP related events in US are electrical grid centered. In Korea, 38% and 29% of all events that led to NPP shutdown at Hanul units 3-6 and at Hanbit units 3-6 respectively were electrical related. Electric grids for both operating and new NPPs must therefore be examined and upgraded for reliability improvement in order to enhance NPP safety.

  15. On the History of the Publication of the Menaion Reader by Demetrius of Rostov (the Text On the Year of Death of St. Mary of Egypt as an Additional Article to the Menaion Reader by St. Demetrius

    Directory of Open Access Journals (Sweden)

    Marina A. Fedotova

    2015-08-01

    The author of the present paper makes available a new, unknown, and unpublished work by St. Demetrius of Rostov, On the Year of Death of St. Mary of Egypt, which was written as an additional calendar text referring to the Life of St. Mary of Egypt. The sources of the Life of St. Mary of Egypt were the Acta Sanctorum and De Probatis Sanctorum Historiis by Laurentius Surius. The text On the Year of Death of St. Mary of Egypt was written by Demetrius for the first edition, but it was not included in the printed edition and is preserved only in manuscript sources.

  16. Reactor noise analysis applications in NPP I and C systems

    Energy Technology Data Exchange (ETDEWEB)

    Gloeckler, O. [International Atomic Energy Agency, Wagramer Strosse 5, A-1400 Vienna, Austria Ontario Power Generation, 230 Westney Road South, Ajax, Ont. L1S 7R3 (Canada)

    2006-07-01

    Reactor noise analysis techniques are used in many NPPs on a routine basis as 'inspection tools' to get information on the dynamics of reactor processes and their instrumentation in a passive, non-intrusive way. The paper discusses some of the tasks and requirements an NPP has to take to implement and to use the full advantages of reactor noise analysis techniques. Typical signal noise analysis applications developed for the monitoring of the reactor shutdown system and control system instrumentation of the Candu units of Ontario Power Generation and Bruce Power are also presented. (authors)

  17. Development of Tsunami PSA method for Korean NPP site

    International Nuclear Information System (INIS)

    Kim, Min Kyu; Choi, In Kil; Park, Jin Hee

    2010-01-01

    A methodology of tsunami PSA was developed in this study. A tsunami PSA consists of tsunami hazard analysis, tsunami fragility analysis and system analysis. In the case of tsunami hazard analysis, evaluation of tsunami return period is major task. For the evaluation of tsunami return period, numerical analysis and empirical method can be applied. The application of this method was applied to a nuclear power plant, Ulchin 56 NPP, which is located in the east coast of Korean peninsula. Through this study, whole tsunami PSA working procedure was established and example calculation was performed for one of real nuclear power plant in Korea

  18. Startup physics tests at Temelin NPP, Unit 1

    International Nuclear Information System (INIS)

    Sedlacek, M.; Minarcin, M.; Toth, L.; Elko, M.; Hascik, R.

    2002-01-01

    The objective, scope and proceedings of the physics tests of Temelin NPP, Unit 1 physical commissioning are given in this paper. Furthermore, some results of selected physics tests are presented: reactor initial criticality test, determination of reactor power range for physics testing, measurement of control rod cluster assembly group no. 10 reactivity worth in case of limitation system LS(a) actuation, control rod cluster assembly system reactivity worth measurement with single rod cluster assembly of greatest reactivity worth stuck in fully withdrawn position, measurement of differential reactivity worth of control rod cluster assembly group no. 9, boron 'endpoint' determination and measurement of power reactivity coefficient (Authors)

  19. Multimedia system for the visitors' centre at the Ignalina NPP

    International Nuclear Information System (INIS)

    Alvers, Margareta

    1999-01-01

    The contents illustrated with video clips, animations, photographs, show the follwing: History of Ignalina NPP (INPP) growing; Visaginas - how the town came into being; Lake Druksiai; Development of nuclear power; Technical data of INPP; Description of INPP; Characteristic features of RBMK reactors; Reactor design; Technical parametres of RBMK-1500 reactor; Nuclear reaction and nuclear fission; Types of nuclear reactors; Circuits and systems; Radiation safety; Safety systems at the INPP; Upgrading nuclear safety at INPP following the Chernobyl accident; Safety problems at MP; Radioactive waste management in the world; RW Management at MP; Energy in Lithuania (thermal power stations, cogeneration plants, producing biogas from organic waste)

  20. NPP Krsko simulator training for operations personnel

    International Nuclear Information System (INIS)

    Pribozic, F.; Krajnc, J.

    2000-01-01

    Acquisition of a full scope replica simulator represents an important achievement for Nuclear power Plant Krsko. Operating nuclear power plant systems is definitely a set of demanding and complex tasks. The most important element in the goal of assuring capabilities for handling such tasks is efficient training of operations personnel who manipulate controls in the main control room. Use of a simulator during the training process is essential and can not be substituted by other techniques. This article gives an overview of NPP Krsko licensed personnel training historical background, current experience and plans for future training activities. Reactor operator initial training lasts approximately two and a half years. Training is divided into several phases, consisting of theoretical and practical segments, including simulator training. In the past, simulator initial training and annual simulator retraining was contracted, thus operators were trained on non-specific full scope simulators. Use of our own plant specific simulator and associated infrastructure will have a significant effect on the operations personnel training process and, in addition, will also support secondary uses, with the common goal to improve safe and reliable plant operation. A regular annual retraining program has successfully started. Use of the plant specific simulator assures consistent training and good management oversight, enhances conformity of operational practices and supports optimization of operating procedures. (author)

  1. Nuclear fuel utilization in Kozloduy NPP

    Energy Technology Data Exchange (ETDEWEB)

    Boyadzhiev, Z; Kharalampieva, Ts; Pejchinov, Ts [Kombinat Atomna Energetika, Kozloduj (Bulgaria)

    1994-12-31

    An assessment of fuel utilization in Kozloduy NPP units 1-6 is made on the basis of operational data obtained for a total of 62 fuel cycles. Basic characteristics of core loading and operation conditions are given. SPPS-1 and BIPR-7 codes are used to calculate assembly-wise power distributions for different full power days of a given cycle and unit. The data are compared with the measured values of these quantities. The analysis performed shows that the core loading option chosen has led to efficient fuel utilization without violation of the nuclear safety criteria. For WWER-440 (Units 1 - 4) this is expressed in effective reduction of the reactor vessel irradiation, maintaining the design duration of the fuel cycles at a reduced number of assemblies by a factor 5 - 5-10%, utilizing fuel with higher enrichment and implementing the 4-year fuel cycle. For WWER-1000 the improvements lead to: adoption of the 3-year fuel cycle utilizing fuel with 4.4% initial enrichment, implementation of improved fuel with a new type of absorbers and more effective low-leakage core loading patterns. 10 tabs., 6 figs., 7 refs.

  2. Lessons learnt from Ignalina NPP decommissioning project

    International Nuclear Information System (INIS)

    NAISSE, Jean-Claude

    2007-01-01

    The Ignalina Nuclear Power Plant (INPP) is located in Lithuania, 130 km north of Vilnius, and consists of two 1500 MWe RBMK type units, commissioned respectively in December 1983 and August 1987. On the 1. of May 2004, the Republic of Lithuania became a member of the European Union. With the protocol on the Ignalina Nuclear Power in Lithuania which is annexed to the Accession Treaty, the Contracting Parties have agreed: - On Lithuanian side, to commit closure of unit 1 of INPP before 2005 and of Unit 2 by 31 December 2009; - On European Union side, to provide adequate additional Community assistance to the efforts of Lithuania to decommission INPP. The paper is divided in two parts. The first part describes how, starting from this agreement, the project was launched and organized, what is its present status and which activities are planned to reach the final ambitious objective of a green field. To give a global picture, the content of the different projects that were defined and the licensing process will also be presented. In the second part, the paper will focus on the lessons learnt. It will explain the difficulties encountered to define the decommissioning strategy, considering both immediate or differed dismantling options and why the first option was finally selected. The paper will mention other challenges and problems that the different actors of the project faced and how they were managed and solved. The paper will be written by representatives of the Ignalina NPP and of the Project Management Unit. (author)

  3. Analysis of an NPP Structure subjected to Vibrations Induced from Airplane Crashes

    International Nuclear Information System (INIS)

    Noh, Sang Hoon; Kim, Yong Soo; Kim, Chong Hak

    2009-01-01

    After the terrorists' attacks with civilian airplanes on September 11, 2001, special attention has been paid to the potential for an airplane crash into a Nuclear Power Plant (NPP) as a man-made hazard. An airplane crash (APC) into an NPP has the potential to damage the roofs and walls of these structures, as well as other systems and components such as pipelines, electric motors, power supplies, power cables of electricity transmission that are important for safety. Therefore, an evaluation of the structural response to an APC is important for the safety of NPPs to be confirmed. A structural integrity analysis was carried out focusing on the vibration effects of an APC on an NPP structure. The NPP structure under consideration has been conceptually redesigned based on APR1400 to have double containments for the purpose of a feasibility study to meet European requirements. The finite element method was used for the structural analysis of the NPP, and the computer code ABAQUS was employed for this analysis

  4. Cernavoda NPP environmental management system - tool for managing the impact on the environment

    International Nuclear Information System (INIS)

    Gabriel, B.; Adrian, J.

    2009-01-01

    Nuclearelectrica SA (SNN SA) is a state owned company which produces nuclear-generated electricity, heat and CANDU 6 type nuclear fuel. The company has also an active participation in the power development program in Romania. The Cernavovoda NPP, one of the SNN branches is situated at 180 km east of Bucharest, in Constanta County at about 2 km SE from Cernavoda town is a CANDU 6 type. Cernavoda Nuclear Power Plant (NPP) is dedicated to generate electrical and thermal power, safely and efficiently for at least 30 years. Having an annual gross output of 5.2 - 5.4 MWh, the Cernavoda Unit 1 NPP provides 10% of the Romanian electric power production. Starting January 01 2007, the Cernavoda Unit 1 NPP supplied into the grid 5518346 MWh electric power and during 1997 - 2007 the Cernavoda Unit 1 NPP supplied into the grid 55769213 MWh electric powers. Over the same period Unit 1 also provided the partial district heating of the town of the Cernavoda supplying about 601517.9 Gcal. Romania second CANDU nuclear power plant, Cernavoda Unit 2, was officially placed in service on Friday, October 5, 2007 together with Unit 1, the CNE-Cernavoda Station is the largest power producer in the country. It now accounts for about 18 per cent of Romania energy supply and significantly reduces its dependency on expensive energy resources from outside of Europe. It provides a structured approach to planning and implementing environmental protection measures. It also establishes a framework for tracking, evaluating and communicating environmental performance. SNN SA mission is to operate the Cernavoda NPP - in a competitive, safe and environmental friendly manner so that the production is optimized and the economic life time of the plant is as long as possible. One major accomplishment is the achievement of ISO 14001 certification for our Environmental Management System (EMS) at Cernavoda NPP. The aim of this paper is to present the EMS implemented and to emphasize the outcomes of the

  5. Implementation of the KASKAD computer code system for WWER-440 at Kozloduy NPP

    International Nuclear Information System (INIS)

    Antonov, A.; Georgieva, N.; Spasova, V.

    2003-01-01

    Since 2002 at Kozloduy NPP - EP1 the code package KASKAD is used for WWER-440 reactor core calculations. The main codes entering this package are: BIPR-7A: 3-D diffusion and core analysis code; PERMAK-A: 2-D fine mesh diffusion code. The burnup calculations were performed for all cycles of the Kozloduy NPP Unit 1, Unit 2, Unit 3 and Unit 4. For the last 4-5 cycles of the Units were calculated control rods worth, critical boron concentration at zero power, reactivity coefficients and linear power. These results were analysed and were compared with experimental data. Some results were given in this paper

  6. Experience of Bohunice V-1 NPP

    International Nuclear Information System (INIS)

    Dobik, Dobroslav

    2000-01-01

    Slovakia remains significantly dependent on imports of primary energy sources, which represent as much as 80% of the demand. Of the total consumption of electricity in Slovakia, 40% was generated in nuclear power plant units in 1998. Slovakia operates 6 units with WWER 440 nuclear reactors. Slovakia is the signatory of all important international agreements and conventions in the field of nuclear energy, and its legislation is in an advanced stage of approximation to European Union law. This is a very important aspect, showing Slovakia's approach to nuclear safety. In 1993 Slovakia accepted the commitments of the UN Convention on Climate Changes, including a reduction of greenhouse gases to 1990 levels by the year 2000. Moreover, as an internal target Slovakia has set the reaching of the 'Toronto Objective', i.e. 20% reduction in CO x , emissions through the year 2005 as compared to 1988. In our opinion, this is not possible without nuclear energy. Time has shown, that the political aspects are more powerful, especially if you underestimate their importance over the than the technical ones. In the case of Bohunice V-1 NPP the political aspects were on the following levels: 1. Slovak republic (Czechoslovakia), political changes, decisions of the government; 2. European Union - Agenda 2000, Accession criteria, nuclear safety criteria, EBRD; 3. Austria as a neighbouring country. Starting with year 1990, 23 expert missions took place at Bohunice V-1 NPP by now. The only criteria for further operation should have been Nuclear safety, which is supervised by NRA SR. It was fully in compliance with EU policy, each country is solely responsible for its energy sector and for nuclear energy use. Our satisfaction lasted not too long. Following negotiation with EU on the highest political level, driven by willingness to be invited for negotiation of accession on the Helsinki Summit, the Slovak government decided on September 14th, on Bohunice V-1 Units shutdown in 2006 and 2008

  7. Financing Nuclear Projects. Case Study: Unit 2 Cernavoda NPP

    International Nuclear Information System (INIS)

    Chirica, Teodor; Constantin, Carmencita; Dobrin, Marian

    2003-01-01

    The implementation of a Nuclear Power Plant (NPP) is a major undertaking for all entities involved, due to the necessity of planning work and coordination of the implementation process of the different fields of interest, starting with the governmental authorities and ending with the public. Having in view the specific investment costs (relatively high) for a NPP, finding an adequate financing structure is possible through an iterative process that involves first an assessment of the technical performances of the project and secondly, the mathematical modelling of the financing structure effects on the projects. In this respect, the paper will be focused on the main steps needed in order to promote an investment project in nuclear field, starting with the decision phase, providing the documentation requested by the local and international authorities to promote the project and ending with the negotiation of the contracts (commercial contract, financing contract, purchase contract, etc). The case study will be focused on the phases achieved in order to promote the Unit 2 NPP Cernavoda completion works project. (authors)

  8. Does climate directly influence NPP globally?

    Science.gov (United States)

    Chu, Chengjin; Bartlett, Megan; Wang, Youshi; He, Fangliang; Weiner, Jacob; Chave, Jérôme; Sack, Lawren

    2016-01-01

    The need for rigorous analyses of climate impacts has never been more crucial. Current textbooks state that climate directly influences ecosystem annual net primary productivity (NPP), emphasizing the urgent need to monitor the impacts of climate change. A recent paper challenged this consensus, arguing, based on an analysis of NPP for 1247 woody plant communities across global climate gradients, that temperature and precipitation have negligible direct effects on NPP and only perhaps have indirect effects by constraining total stand biomass (Mtot ) and stand age (a). The authors of that study concluded that the length of the growing season (lgs ) might have a minor influence on NPP, an effect they considered not to be directly related to climate. In this article, we describe flaws that affected that study's conclusions and present novel analyses to disentangle the effects of stand variables and climate in determining NPP. We re-analyzed the same database to partition the direct and indirect effects of climate on NPP, using three approaches: maximum-likelihood model selection, independent-effects analysis, and structural equation modeling. These new analyses showed that about half of the global variation in NPP could be explained by Mtot combined with climate variables and supported strong and direct influences of climate independently of Mtot , both for NPP and for net biomass change averaged across the known lifetime of the stands (ABC = average biomass change). We show that lgs is an important climate variable, intrinsically correlated with, and contributing to mean annual temperature and precipitation (Tann and Pann ), all important climatic drivers of NPP. Our analyses provide guidance for statistical and mechanistic analyses of climate drivers of ecosystem processes for predictive modeling and provide novel evidence supporting the strong, direct role of climate in determining vegetation productivity at the global scale. © 2015 John Wiley & Sons Ltd.

  9. Analysis of 14C level around Qinshan NPP base

    International Nuclear Information System (INIS)

    Huang Renjie; Liang Haiyan; Chen Qianyuan; Ni Shiying; He Jun; Zeng Guangjian; Ma Yongfu

    2012-01-01

    By using the method of alkaline solution absorption, the activity concentrations of Carbon-14 as well as its variation tendency in air and biological samples were analyzed. The air samples and biological samples were collected around the Qinshan nuclear power plant base (Qinshan NPP Base) in 2002 to 2009 and 2007 to 2009 respectively. The results showed that, since 2002, the annual average activity concentrations of Carbon-14 in air samples were in the range of 38.3 mBq/m 3 to 55.4 mBq/m 3 . Although the monitoring results of Xiajiawan village and Yanliucun village were comparatively higher than the reference site in Hangzhou City, the results were still at the same level. Meanwhile, monitoring results of Xiajiawan village and Yangliucun village in the summer of 2004 and 2005 are relatively high, with the peak value of 55.4 mBq/m 3 appeared in Xiajiawan village during the summer of 2005. Correspondingly the annual airborne Carbon-14 of 2004 and 2005 discharged from the Qinshan NPP 3 rd Phase were higher than normal as well, it can therefore be concluded that the activity concentration of Carbon-14 around the Qinshan NPP Base are related to the discharged source term. The activity concentration of Carbon-14 in rice and leaf vegetable samples from Xiajiawan village and Yangliucun village were slightly higher, but within the same level, than that of Hangzhou. The activity concentration of Carbon-14 in the mullet samples collected from the sea area around Qinshan NPP Base are approximately the same with the sea area of Zhoushan. (authors)

  10. ESTE EMO and ESTE EBO - emergency response system for NPP Mochovce and NPP Bohunice V-2

    International Nuclear Information System (INIS)

    Caeny, P.; Chyly, M.; Suchon, D.; Smejkalova, E.; Fabova, V.; Mancikova, M.; Muller, P.

    2009-01-01

    Programs ESTE EMO and ESTE EBO are emergency response systems that help the crisis staff of the NPP in assessing the source term (predicted possible release of radionuclides to the atmosphere ), in assessing the urgent protective measures and sectors under threat, in assessing real release (symptoms of release really detected and observed), in calculating radiological impacts of real release, averted or avertable doses, potential doses and doses during transport or evacuation on specified routes. Both systems serve as instruments in case of severe accident (DBA or BDBA) at NPP Mochovce or NPP Bohunice, accidents with threat of release of radioactivity to the atmosphere. Systems are implemented at emergency centre of Mochovce NPP and Bohunice NPP and connected online to the sources of technological and radiological data from the reactor, primary circuit, confinement, secondary circuit, ventilation stack, from the area of NPP (TDS 1) and from the emergency planning zone (TDS 11). Systems are connected online to the sources of meteorological data, too. (authors)

  11. ESTE EMO and ESTE EBO - emergency response system for NPP Mochovce and NPP Bohunice V-2

    International Nuclear Information System (INIS)

    Caeny, P.; Chyly, M.; Suchon, D.; Smejkalova, E.; Fabova, V.; Mancikova, M.; Muller, P.

    2008-01-01

    Programs ESTE EMO and ESTE EBO are emergency response systems that help the crisis staff of the NPP in assessing the source term (predicted possible release of radionuclides to the atmosphere ), in assessing the urgent protective measures and sectors under threat, in assessing real release (symptoms of release really detected and observed), in calculating radiological impacts of real release, averted or avertable doses, potential doses and doses during transport or evacuation on specified routes. Both systems serve as instruments in case of severe accident (DBA or BDBA) at NPP Mochovce or NPP Bohunice, accidents with threat of release of radioactivity to the atmosphere. Systems are implemented at emergency centre of Mochovce NPP and Bohunice NPP and connected online to the sources of technological and radiological data from the reactor, primary circuit, confinement, secondary circuit, ventilation stack, from the area of NPP (TDS 1) and from the emergency planning zone (TDS 11). Systems are connected online to the sources of meteorological data, too. (authors)

  12. Study on human factor at NPP

    International Nuclear Information System (INIS)

    Nopp, I.

    1984-01-01

    Factors affecting the reliabilty of the reactor control by an NPP operator are considered on the base of the Czechoslovakia NPP operating experience. The reliability level of NPP operators depends on objective factors (conditions and regime of labour) determining the labour productivity and on subjective ones (psychological morale, physical and mental abilities and occupational level of personnel). Problems of the effect of physical and mental abilities and professional level on the reliability of personnel are considered to be the most important ones. The effect of individual abilities and specific features of the human body on changes in his occupational abilities can be estimated only to a certain degree

  13. Inspection Qualification Centre in NPP 'Kozloduy'

    International Nuclear Information System (INIS)

    Mikhovski, M.

    2000-01-01

    In May 1999 according to the working plan of the IAEA project RER 4/020 and the decision of the NPP the Inspection Qualification Centre (IQC) has been established in order to provide examination services in the NPP. During year 1999 IVC (AEA Technology) in the framework of the DTI project provides consulting and technical assistance to the NPP, IQC, Bulgarian Academy of Sciences and Regulatory Authorities in setting up the IQC infrastructure. Now IQC work as an independent inspection body B type. The IQC activities for the period 1999-2000 are presented and further tasks are outlined

  14. A brief overview of Ignalina NPP safety issues

    International Nuclear Information System (INIS)

    Almenas, K.; Ushpuras, E.

    1998-01-01

    A description of the safety of Ignalina NPP in a very popular form is presented. Answers to the most frequently recurring questions concerning the Ignalina NPP are provided based on recently completed international studies. Questions are like these: can a similar accident to the one that occurred in Chernobyl take place at Ignalina NPP, does the Ignalina NPP have a containment, what are the probabilities and potential consequences of accidents, etc. The brochure contains a short description of Ignalina NPP safety improvement programs

  15. Nuclear power plant personnel training and its evaluation. A guidebook

    International Nuclear Information System (INIS)

    1996-01-01

    The Guidebook will prove especially useful for, and is addressed primarily to: nuclear power operating organizations establishing or upgrading their NPP personnel training systems; regulatory personnel responsible for setting requirements and/or evaluating NPP personnel training; and organizations (within or outside the operating organization) responsible for the development, implementation and evaluation of training programmes for NPP personnel. Figs, tabs

  16. Core Management of NPPs in China and Experience of Tianwan NPP

    International Nuclear Information System (INIS)

    Guohan, G.

    2006-01-01

    The Current Status of the NPPs in China; the Nuclear Power Development Plan till 2020; the Fuel Management and the Core Management Strategy of NPPs are briefly presented in this paper. The gained experience during construction of Taiwan NPP, new design features and major construction milestones of Taiwan NPP are also discussed. The full list of 21 non-conformance reports (NCR) submitted by Jiangsu Nuclear Power Company to NNSA during construction of Taiwan NPP is given. The main issues raised during FSAR review like: RP operation with incomplete number of primary loops; Sedimentation in the construction and piping of service water system; Location of postulated pipe break; Stratification analysis for surge line of pressurizer; Safety classification of equipment in primary circuit; Fire resistant capability of cable insulation; Fire Hazard Analysis; Optimization of protection against ionizing radiation ect. are also listed

  17. Ideal scaling of BETHSY 9.1.B test results to NPP

    International Nuclear Information System (INIS)

    Petelin, S.; Guntel, I.

    1995-01-01

    The transient scenario standard problem 27 (ISP-27) was implemented in the RELAP5 analysis of small break loss of coolant accident for Krsko nuclear power plant (Krsko NPP). The objective was to evaluate the effectiveness of ISP-27 proposed accident management procedure for real NPP and to compare the physical phenomena known from experimental background with the phenomena predicted by RELAP5 simulation of real plant transient. The analyses showed that, if relevant break, power scaling criteria, primary and secondary pressure are fulfilled the RELAP5 model of Krsko NPP cannot completely ensure the simulation of typical thermal-hydraulic phenomena observed in BETHSY facility during ISP-27. Much better satisfaction is observed on ideal scaled up model. (author)

  18. Screening of external hazards for NPP with bank type reactor. Modeling of safety related systems and equipment for RBMK. Probabilistic assessment of NPP safety on aircraft impact. Progress report

    International Nuclear Information System (INIS)

    Kostarev, V.

    1999-01-01

    This progress report was produced within the frame of IAEA research project on screening the hazards for NPP with bank type reactor. It covers the following tasks; development of the model for the primary loop system of RBMK; developing the models for safety related equipment of RBMK; developing of models for safety related models of EGP-6 type reactor (Bilibinskaya Nuclear Co-generated heat and Power Plant); and probabilistic assessment of NPP safety on aircraft impact

  19. Krsko NPP radioactive waste characteristics

    International Nuclear Information System (INIS)

    Skanata, D.; Kroselj, V.; Jankovic, M.

    2007-01-01

    In May 2005 Krsko NPP initiated the Radioactive Waste Characterization Project and commissioned its realization to the consulting company Enconet International, Zagreb. The Agency for Radwaste Management was invited to participate on the Project. The Project was successfully closed out in August 2006. The main Project goal consisted of systematization the existing and gathering the missing radiological, chemical, physical, mechanical, thermal and biological information and data on radioactive waste. In a general perspective, the Project may also be considered as a part of broader scope of activities to support state efforts to find a disposal solution for radioactive waste in Slovenia. The operational low and intermediate level radioactive waste has been structured into 6 waste streams that contain evaporator concentrates and tank sludges, spent ion resins, spent filters, compressible and non-compressible waste as well as specific waste. For each of mentioned waste streams, process schemes have been developed including raw waste, treatment and conditioning technologies, waste forms, containers and waste packages. In the paper the main results of the Characterization Project will be briefly described. The results will indicate that there are 17 different types of raw waste that have been processed by applying 9 treatment/conditioning technologies. By this way 18 different waste forms have been produced and stored into 3 types of containers. Within each type of container several combinations should be distinguished. Considering all of this, there are 34 different types of waste packages altogether that are currently stored in the Solid Radwaste Storage Facility at the Krsko NPP site. Because of these findings a new identification system has been recommended and consequently the improvement of the existing database on radioactive waste has been proposed. The potential areas of further in depth characterization are indicated. In the paper a brief description on the

  20. 75 FR 5355 - Notice of Extension of Comment Period for NUREG-1934, Nuclear Power Plant Fire Modeling...

    Science.gov (United States)

    2010-02-02

    ..., Nuclear Power Plant Fire Modeling Application Guide (NPP FIRE MAG), Draft Report for Comment AGENCY... 1019195), Nuclear Power Plant Fire Modeling Application Guide (NPP FIRE MAG), Draft Report for Comment... exists in both the general fire protection and the nuclear power plant (NPP) fire protection communities...

  1. The development of stochastic process modeling through risk analysis derived from scheduling of NPP project

    International Nuclear Information System (INIS)

    Lee, Kwang Ho; Roh, Myung Sub

    2013-01-01

    There are so many different factors to consider when constructing a nuclear power plant successfully from planning to decommissioning. According to PMBOK, all projects have nine domains from a holistic project management perspective. They are equally important to all projects, however, this study focuses mostly on the processes required to manage timely completion of the project and conduct risk management. The overall objective of this study is to let you know what the risk analysis derived from scheduling of NPP project is, and understand how to implement the stochastic process modeling through risk management. Building the Nuclear Power Plant is required a great deal of time and fundamental knowledge related to all engineering. That means that integrated project scheduling management with so many activities is necessary and very important. Simulation techniques for scheduling of NPP project using Open Plan program, Crystal Ball program, and Minitab program can be useful tools for designing optimal schedule planning. Thus far, Open Plan and Monte Carlo programs have been used to calculate the critical path for scheduling network analysis. And also, Minitab program has been applied to monitor the scheduling risk. This approach to stochastic modeling through risk analysis of project activities is very useful for optimizing the schedules of activities using Critical Path Method and managing the scheduling control of NPP project. This study has shown new approach to optimal scheduling of NPP project, however, this does not consider the characteristic of activities according to the NPP site conditions. Hence, this study needs more research considering those factors

  2. The development of stochastic process modeling through risk analysis derived from scheduling of NPP project

    Energy Technology Data Exchange (ETDEWEB)

    Lee, Kwang Ho; Roh, Myung Sub [KEPCO International Nuclear Graduate School, Ulsan (Korea, Republic of)

    2013-10-15

    There are so many different factors to consider when constructing a nuclear power plant successfully from planning to decommissioning. According to PMBOK, all projects have nine domains from a holistic project management perspective. They are equally important to all projects, however, this study focuses mostly on the processes required to manage timely completion of the project and conduct risk management. The overall objective of this study is to let you know what the risk analysis derived from scheduling of NPP project is, and understand how to implement the stochastic process modeling through risk management. Building the Nuclear Power Plant is required a great deal of time and fundamental knowledge related to all engineering. That means that integrated project scheduling management with so many activities is necessary and very important. Simulation techniques for scheduling of NPP project using Open Plan program, Crystal Ball program, and Minitab program can be useful tools for designing optimal schedule planning. Thus far, Open Plan and Monte Carlo programs have been used to calculate the critical path for scheduling network analysis. And also, Minitab program has been applied to monitor the scheduling risk. This approach to stochastic modeling through risk analysis of project activities is very useful for optimizing the schedules of activities using Critical Path Method and managing the scheduling control of NPP project. This study has shown new approach to optimal scheduling of NPP project, however, this does not consider the characteristic of activities according to the NPP site conditions. Hence, this study needs more research considering those factors.

  3. Equipment Reliability Program in NPP Krsko

    International Nuclear Information System (INIS)

    Skaler, F.; Djetelic, N.

    2006-01-01

    Operation that is safe, reliable, effective and acceptable to public is the common message in a mission statement of commercial nuclear power plants (NPPs). To fulfill these goals, nuclear industry, among other areas, has to focus on: 1 Human Performance (HU) and 2 Equipment Reliability (EQ). The performance objective of HU is as follows: The behaviors of all personnel result in safe and reliable station operation. While unwanted human behaviors in operations mostly result directly in the event, the behavior flaws either in the area of maintenance or engineering usually cause decreased equipment reliability. Unsatisfied Human performance leads even the best designed power plants into significant operating events, which can be found as well-known examples in nuclear industry. Equipment reliability is today recognized as the key to success. While the human performance at most NPPs has been improving since the start of WANO / INPO / IAEA evaluations, the open energy market has forced the nuclear plants to reduce production costs and operate more reliably and effectively. The balance between these two (opposite) goals has made equipment reliability even more important for safe, reliable and efficient production. Insisting on on-line operation by ignoring some principles of safety could nowadays in a well-developed safety culture and human performance environment exceed the cost of electricity losses. In last decade the leading USA nuclear companies put a lot of effort to improve equipment reliability primarily based on INPO Equipment Reliability Program AP-913 at their NPP stations. The Equipment Reliability Program is the key program not only for safe and reliable operation, but also for the Life Cycle Management and Aging Management on the way to the nuclear power plant life extension. The purpose of Equipment Reliability process is to identify, organize, integrate and coordinate equipment reliability activities (preventive and predictive maintenance, maintenance

  4. Demographic and health characteristics of the population residing within the 30-km area around the Kozloduy NPP

    International Nuclear Information System (INIS)

    Dimitrov, P.; Bliznakov, V.

    1993-01-01

    Based on detailed analysis of data on demographic and health state of the population residing within the 30-km zone around the Kozloduj NPP, an attempt was made to detect any impact of the power plant on population health under normal NPP operational conditions. The health characteristics of the population revealed no unfavorable trends. Particular attention was given to diseases of the blood and blood-forming organs, malignant new growths, complications of pregnancy, and congenital anomalies. (author)

  5. On-line maintenance at Cofrentes NPP

    International Nuclear Information System (INIS)

    Roldan Vilches, J.; Moreno Matarranz, M. A.; Hermana Mendioroz, I.

    1998-01-01

    Cofrentes NPP has begun in 1997 activities related to At Power Preventive Maintenance over trains or systems which lead to a voluntary entry in a Limitative Condition of Operation (LCO) of the Technical Specifications. From others benefits, this program ha improved the risk management and the staff's knowledge over the functions and safety implications of the different systems, the better exploit of the resources, the co-ordination of the different organisations involved (Maintenance an Operation) and the reductions of works during shutdowns. Previous to each work, a feasibility study analyzes qualitative and quantitative (PSA), using the Risk Monitor, the implications on safety of all the tasks, assuring that the global safety of the Plant is always maintained. Tech. Spec. are analyzed in detail and also are analyzed situations of simultaneous unavailabilities of systems which could lead to a high risk situation. Two different risk controls are defined (punctual and accumulated) to assure that high risk situations will not be given. Finally, historical risk profile is analyzed to assure that the accumulated risk increase is not significant. Risk Monitor helps staff in the schedule and follow-up of the activities of On-Line Maintenance. Each one of the tasks are deeply planned and harshly analyzed and are carried out by high qualified workers. By the moment, this program is running with fully satisfaction on the Plant. (Author)

  6. EPC projects for EPR Flamanville 3 NPP

    International Nuclear Information System (INIS)

    Diaz, J.I.; Polo, J.; Aymerich, E.; Cubian, B.

    2010-01-01

    IBERDROLA Ingenieria y Construccion is carrying out a handful of activities in the EPR Flamanville 3 -FA3 NPP- context since 2007 matching oriented to position the company in the emerging marketplace of new nuclear power plants Generation III+, whose expectation for the next years is highly promising. IBERDROLA Ingenieria y Construccion leads 5 EPC -Engineering, Procurement and Commissioning- projects for FA3 NPP from the Nuclear Island till Sea Water Pumping Station as follows: - Design, procurement. fabrication, installation and testing of 21 shell and tubes heat-exchangers for the nuclear island. 12 out of these 17 HXs are conventional and will be designed according to ASME BPV code Section VIII and have to comply with PED 97/23/CE and ESPN. The remaining 5 HXs are nuclear and will be designed according to ASME BPV code Section III and have also to comply with PED and ESPN. - Design, procurement, fabrication and assembly of 9 demineralizers for different plant systems. Three of these Important To Safety (IPS) equipments have been manufactured according with ASME VIII codes and six of them with EN 13445 code plus additional requirements to comply with PED and final client requirements for nuclear island. - Design, fabrication and installation of qualified travelling water screening filters. The equipments furnished will be two nuclear safety qualified filters and associated equipment (cleaning water system and control system). Additionally some auxiliary devices such as grids, automatic trash rakes and stop gates are included in the contract. - Engineering, procurement, fabrication, erection and commissioning for the condensate treatment plant. This system includes a demineralizer tank, 5 filters, reactive injection mixer, pneumatic and manual valves, piping and instrumentation and control systems. - Engineering, procurement erection and commissioning for the electro-chlorination plant to protect the IPS piping for Condensate Water System for FA3. This system

  7. EPC projects for EPR Flamanville 3 NPP

    Energy Technology Data Exchange (ETDEWEB)

    Diaz, J.I.; Polo, J.; Aymerich, E.; Cubian, B. [Nuclear Generation Department, Iberdrola Ingenieria y Construccion, Avda. Manoteras 20, 28050 Madrid (Spain)

    2010-07-01

    IBERDROLA Ingenieria y Construccion is carrying out a handful of activities in the EPR Flamanville 3 -FA3 NPP- context since 2007 matching oriented to position the company in the emerging marketplace of new nuclear power plants Generation III+, whose expectation for the next years is highly promising. IBERDROLA Ingenieria y Construccion leads 5 EPC -Engineering, Procurement and Commissioning- projects for FA3 NPP from the Nuclear Island till Sea Water Pumping Station as follows: - Design, procurement. fabrication, installation and testing of 21 shell and tubes heat-exchangers for the nuclear island. 12 out of these 17 HXs are conventional and will be designed according to ASME BPV code Section VIII and have to comply with PED 97/23/CE and ESPN. The remaining 5 HXs are nuclear and will be designed according to ASME BPV code Section III and have also to comply with PED and ESPN. - Design, procurement, fabrication and assembly of 9 demineralizers for different plant systems. Three of these Important To Safety (IPS) equipments have been manufactured according with ASME VIII codes and six of them with EN 13445 code plus additional requirements to comply with PED and final client requirements for nuclear island. - Design, fabrication and installation of qualified travelling water screening filters. The equipments furnished will be two nuclear safety qualified filters and associated equipment (cleaning water system and control system). Additionally some auxiliary devices such as grids, automatic trash rakes and stop gates are included in the contract. - Engineering, procurement, fabrication, erection and commissioning for the condensate treatment plant. This system includes a demineralizer tank, 5 filters, reactive injection mixer, pneumatic and manual valves, piping and instrumentation and control systems. - Engineering, procurement erection and commissioning for the electro-chlorination plant to protect the IPS piping for Condensate Water System for FA3. This system

  8. Environmental impact assessment of NPP decommissioning

    International Nuclear Information System (INIS)

    Hinca, R.

    2009-01-01

    In this presentation the following potential impacts of decommissioning of NPP are discussed: - Impacts on population; Impacts on natural environment; Land impacts; Impacts on urban complex and land utilisation; Possible impacts on area as a result of failure.

  9. Radiation ecological monitoring in NPP region

    International Nuclear Information System (INIS)

    Egorov, Yu.A.; Kazakov, S.V.

    1985-01-01

    The known principle of sanitary-hygienic regulation of NPP radiation effect on man and environment is analyzed. An ecological approach is required to optimize NPP relations with the environment and to regulate radioactivity of the NPP - environment system. The ecological approach envisages the development of standards of permissible concentrations of radioactive and chemical substances (as well as heat) in natural environment, taking into account their synergism, corresponding to ecologically permissible response reactions of biota to their effect. The ecological approach also comprises the sanitary-hygienic principle of radiation protection of man. Attention is paid to ecological monitoring in NPP region, comprising consideration of factors, affecting the environment, evaluation of the actual state of the environment, prediction of the environmental state, evaluation of the expected environmental state

  10. NPP operation and modern high technologies

    International Nuclear Information System (INIS)

    Kuznetsov, V.V.

    1992-01-01

    Examples are considered of modern high technology introduction into daily practice of NPP operation, namely: satellite communication systems, robots, non-destructive testing, optical-fiber techniques, laser measuring means and others

  11. Krsko NPP Periodic Safety Review program

    International Nuclear Information System (INIS)

    Basic, I.; Spiler, J.; Novsak, M.

    2001-01-01

    The need for conducting a Periodic Safety Review for the Krsko NPP has been clearly recognized both by the NEK and the regulator (SNSA). The PSR would be highly desirable both in the light of current trends in safety oversight practices and because of many benefits it is capable to provide. On January 11, 2001 the SNSA issued a decision requesting the Krsko NPP to prepare a program and determine a schedule for the implementation of the program for 'Periodic Safety Review of NPP Krsko'. The program, which is required to be in accordance with the IAEA safety philosophy and with the EU practice, was submitted for the approval to the SNSA by the end of March 2001. The paper summarizes Krsko NPP Periodic Safety Review Program [1] including implemented SNSA and IAEA Expert Mission comments.(author)

  12. Cuba: Juragua NPP. Project Control. Annex 5

    International Nuclear Information System (INIS)

    Serradet, M.A.

    1999-01-01

    This annex deals with project control. The long suspension of Juragua NPP has affected personnel, equipment and site structures. Efforts are being made to revive the plant and to protect existing resources (assets). An action plan has been prepared. (author)

  13. Ignalina NPP Safety Analysis: Models and Results

    International Nuclear Information System (INIS)

    Uspuras, E.

    1999-01-01

    Research directions, linked to safety assessment of the Ignalina NPP, of the scientific safety analysis group are presented: Thermal-hydraulic analysis of accidents and operational transients; Thermal-hydraulic assessment of Ignalina NPP Accident Localization System and other compartments; Structural analysis of plant components, piping and other parts of Main Circulation Circuit; Assessment of RBMK-1500 reactor core and other. Models and main works carried out last year are described. (author)

  14. Heat delivery from Bohunice NPP, Slovakia

    International Nuclear Information System (INIS)

    Paley, I.

    1998-01-01

    Experience with nuclear district heating in the Slovak Republic is reported. The heating system of the town of Trnava is supplied by the Bohunice NPP and conventional sources. Construction of the hot water heating system from the Bohunice NPP began in 1983. Commercial operation began on 10 December 1987. Heat delivery has gradually increased from 478 TJ in 1988, to 1,104 TJ in 1995. The heat cost is low, resulting in an increasing number of consumers. (author)

  15. Radionuclide localization at the Chernobyl' NPP territory

    International Nuclear Information System (INIS)

    Mamaev, L.A.; Galkin, G.A.; Khrabrov, S.L.; Polyakov, A.S.; Mikhejkin, S.V.

    1989-01-01

    Experience is generalized of using different dust suppression (DS) compounds during Chernobyl' accident consequence elimination. Polymer DS compounds were used at the NPP operating site; the compounds kept dust-like radioactive contaminations during 1-2 months. DS at the country was realized by means of the compound on base of latex. The conclusion is made that the DS measures improved radiation situation in the NPP zone. 7 refs

  16. Knowledge Management and Organizational Proficiency with NPP

    International Nuclear Information System (INIS)

    Marler, M.

    2016-01-01

    Full text: The pace of new NPP construction, startup, and operation is straining the supply of proficient operators, technicians, and engineers. This technical brief explains an approach implemented by a US nuclear utility to capture and transfer knowledge possessed by proficient workers to new workers using the VISION learning content management system. This approach could also be used to accelerate worker proficiency in new NPP organizations. (author

  17. Modelling the impact of Cernavoda NPP on the environment

    International Nuclear Information System (INIS)

    Constantin, A.-I.

    2001-01-01

    In connection with a stay as a visiting researcher at VTT Energy (Technical Research Center of Finland), a study was conducted related to the atmospheric dispersion and dose assessment for radioactive releases from nuclear power plants. The most important aspects of this study are described in this paper. These include: the application of the TRADOS dispersion and dose assessment model in the case of the Cernavoda NPP and the development of a special program INTEGRATION for the calculation of cloud gamma dose rate of 72 nuclides. (authors)

  18. A risk informed safety classification for a Nordic NPP

    International Nuclear Information System (INIS)

    Jaenkaelae, K.

    2002-01-01

    The report describes a study to develop a safety classification proposal or classi- fication recommendations based on risks for selected equipment of a nuclear power plant. The application plant in this work is Loviisa NPP unit 1. The safety classification proposals are to be considered as an exercise in this pilot study and do not necessarily represent final proposals in a real situation. Comparisons to original safety classifications and technical specifications were made. The study concludes that it is possible to change safety classes or safety signifi- cances as considered in technical specifications and in in-service-inspections into both directions without endangering the safety or even by improving the safety. (au)

  19. Survey of Water Chemistry and Corrosion of NPP

    Energy Technology Data Exchange (ETDEWEB)

    Jung, Ki Sok; Hong, Bong Geon

    2008-06-15

    Status of water chemistry of nuclear power plant and materials corrosion has been surveyed. For PWR, system chemistry of primary coolant and secondary coolant as well as the related corrosion of materials was surveyed. For BWR, system chemistry as whole has been surveyed with its accompanying corrosion problems. Radiolysis of coolant water and activation of corrosion products also was surveyed. Future NPP such as supercritical water cooled reactor and fusion reactor has also been surveyed for their water chemistry and corrosion problems. As a result, proposal for some research items has been suggested. Some related corrosion research techniques and electrochemical fundamentals are also presented.

  20. Survey of Water Chemistry and Corrosion of NPP

    International Nuclear Information System (INIS)

    Jung, Ki Sok; Hong, Bong Geon

    2008-06-01

    Status of water chemistry of nuclear power plant and materials corrosion has been surveyed. For PWR, system chemistry of primary coolant and secondary coolant as well as the related corrosion of materials was surveyed. For BWR, system chemistry as whole has been surveyed with its accompanying corrosion problems. Radiolysis of coolant water and activation of corrosion products also was surveyed. Future NPP such as supercritical water cooled reactor and fusion reactor has also been surveyed for their water chemistry and corrosion problems. As a result, proposal for some research items has been suggested. Some related corrosion research techniques and electrochemical fundamentals are also presented

  1. Status of steam generator tubing integrity at Jaslovske Bohunice NPP

    International Nuclear Information System (INIS)

    Cepcek, S.

    1997-01-01

    Steam generator represents one of the most important component of nuclear power plants. Especially, loss of tubing integrity of steam generators can lead to the primary coolant leak to secondary circuit and in worse cases to the unit shut down or to the PTS events occurrence. Therefore, to ensure the steam generator tubing integrity and the current knowledge about tube degradation propagation and development is of the highest importance. In this paper the present status of steam generator tubing integrity in operated NPP in Slovak Republic is presented

  2. IAEA activities on safety aspects of NPP ageing

    International Nuclear Information System (INIS)

    Pachner, J.

    1998-01-01

    A review of IAEA activities concerned with safety aspects of nuclear power plants ageing is given for the period from 1995 to 1998 with the prospects till year 2000. Coordinated Research programs were conducted on Management Ageing of Concrete Containment Buildings; Management of Ageing of In-Containment I and C cables. TECDOCs were published on Assessment and Management of Ageing of Major NPP Components Important for Safety of CANDU, PWR and BWR NPPs. Technical Committee Meetings and Interregional training courses concerned with the same subjects were held

  3. Simulator training and human factor reliability in Kozloduy NPP, Bulgaria

    International Nuclear Information System (INIS)

    Stoychev, Kosta

    2007-01-01

    This is a PowerPoint presentation. Situated in North Bulgaria, in the vicinity of the town of Kozloduy, near the Danube River bank, there is the Bulgarian Kozloduy Nuclear Power plant operating four WWER-440 and two WWER-1000 units. Units 1 and 2 were commissioned in July, 1974 and November, 1975, respectively. These were shut down at the end of 2003. Units 3 and 4 were commissioned in December, 1980 and May, 1982. They were shut down at the end of 2006 as a precondition for Bulgaria's accession to the European Union. The 1000 MW units 5 and 6 of Kozloduy NPP were commissioned in September, 1988 and December, 1993, respectively. Large-scale modernization have been implemented and now the units meet all international safety standards. The paper describes the multifunctional simulator Kozloduy NPP for the operational staff training. The training stages are as follows: - Preparatory; -Theoretical studies; - Training at the Training Centre by means of technical devices; - Preparation and sitting for an exam before a Kozloduy NPP expert commission; - Simulator training ; - Preparation to obtain a permit for a license, corresponding to the position to begin work at the NPP; - Exams before the Nuclear Regulatory Agency (NRA) and licensing; - Shadow training at the working place; - Permission for unaided operation. The following positions are addressed by the simulator training: - Chief Plant Supervisor; - Shift Unit Supervisor; - Senior Reactor Operator; - Simulator Instructor; - Controller physicist; -Senior Turbine Operator; - Senior Operator of Turbine Feedwater Pumps of Kozloduy NPP. Improving of training method led to a reduction of number of significant events while worldwide practice proves that improvement of engineering resulted in an increase in the percentage of events, related to human factor. Analysis of human reliability in 2005 and 2006 in cooperation with representatives from Great Britain and the Technical University in Sofia were worked on the DTI NSP B

  4. Managing RTP Console Upgrading Project: Best Practice for Nuclear Malaysia as TSO in Supporting NPP Development

    International Nuclear Information System (INIS)

    Nurfarhana Ayuni Joha; Syahirah Abdul Rahman; Izhar Abu Hussin

    2011-01-01

    Human Resource Development (HRD) is required for Nuclear Power Programme (NPP). To be a Technical Support Organisation (TSO) for NPP, Nuclear Malaysia should be ready to take the responsibility in supporting Nuclear Regulatory Agency (NRA) and NPP Operators. In nurturing Nuclear Malaysia as TSO, the prime important and focus of HRD for the NPP is the reactor engineering technology. Nuclear Malaysia gives various phases of supports needed to build NPP such as during siting, design, planning, licensing, construction, commissioning, operation and maintenance in its own way and capability. The current Nuclear Malaysia unique approach is the TRIGA PUSPATI reactor (RTP) upgrading project. Research reactor plays an important role in Research and Developpement organization as a nuclear facility to assist the development of NPP. Therefore, upgrading the research reactor is needed to build the skills and gain knowledge of workers to work safely. After 29 years of operation, the RTP system is facing aging problems due to many components in the reactor are outdated. Therefore, immediate action should be carried out to mitigate the aging factor of the reactor to prevent the worsening of the aging problem, and to prevent untoward incident from happening. Action should also cover short and long term planning to prevent current situation from recurring. Currently, RTP is upgrading its console from analog to digital system. One of the achievements in this console upgrading project is the development and implementation of project management. This paper comprises the overview on the RTP console upgrading project, the project management and how this project can lead Nuclear Malaysia to be a good TSO for the development of NPP. (author)

  5. Integrated NPP life cycle management - Agency's approach

    International Nuclear Information System (INIS)

    Gueorguiev, B.

    2002-01-01

    administrative - managerial or/and social - political activities aimed at the achievement of an optimised long term save and reliable operation of the plant including its decommissioning. Optimisation of the plant operational life is the most economical option equivalent to providing additional generating capacity. In its turn optimisation of operational or service life means extension of the operational license to the extent possible having in mind that the plant performance continues to maintain its safety and competitiveness on the market. To meet these requirements the need for an integrated NPP life management approach is becoming more and more evident. The IAEA in response to the needs of the Member states is implementing several programmes including the project on engineering and management practices for optimisation of nuclear power plant service life including decommissioning. The Project scope includes different possible modes of IAEA operations for the purposes of information exchange and technology transfer. It means arrangements for technical, advisory and consultant group meetings, development of databases and guidance documents on proven practices, co-ordinated research projects, technical co-operation projects, expert services, training activities, co-operation with other International organizations and some others. A number of issues are under consideration. They include economic analysis and considerations related to decision on continued operation versus decommissioning, optimisation of operation/maintenance/In-service inspection regimes to facilitate life management programmes, aging management and mitigation measures with regard to control and instrumentation, primary and secondary circuit equipment integrity, assessment of structural materials, creation and development of supporting databases, preservation of knowledge including aspects of training and qualification of NPP personnel, work force aging, pre-shut down and decommissioning activities

  6. Suomi NPP Ground System Performance

    Science.gov (United States)

    Grant, K. D.; Bergeron, C.

    2013-12-01

    The National Oceanic and Atmospheric Administration (NOAA) and National Aeronautics and Space Administration (NASA) are jointly acquiring the next-generation civilian weather and environmental satellite system: the Joint Polar Satellite System (JPSS). JPSS will replace the afternoon orbit component and ground processing system of the current Polar-orbiting Operational Environmental Satellites (POES) managed by NOAA. The JPSS satellites will carry a suite of sensors designed to collect meteorological, oceanographic, climatological and geophysical observations of the Earth. The first satellite in the JPSS constellation, known as the Suomi National Polar-orbiting Partnership (Suomi NPP) satellite, was launched on 28 October 2011, and is currently undergoing product calibration and validation activities. As products reach a beta level of maturity, they are made available to the community through NOAA's Comprehensive Large Array-data Stewardship System (CLASS). CGS's data processing capability processes the satellite data from the Joint Polar Satellite System satellites to provide environmental data products (including Sensor Data Records (SDRs) and Environmental Data Records (EDRs)) to NOAA and Department of Defense (DoD) processing centers operated by the United States government. CGS is currently processing and delivering SDRs and EDRs for Suomi NPP and will continue through the lifetime of the Joint Polar Satellite System programs. Following the launch and sensor activation phase of the Suomi NPP mission, full volume data traffic is now flowing from the satellite through CGS's C3, data processing, and data delivery systems. Ground system performance is critical for this operational system. As part of early system checkout, Raytheon measured all aspects of data acquisition, routing, processing, and delivery to ensure operational performance requirements are met, and will continue to be met throughout the mission. Raytheon developed a tool to measure, categorize, and

  7. Safety enhancement concept for NPP of new generation with VVER reactors

    International Nuclear Information System (INIS)

    Bezlepkin, V.; Kukhtevich, I.; Semashko, S.; Svetlov, S.; Solodovnikov, A.

    2004-01-01

    With the present day conditions, in order to successfully promote new NPP designs in the electric power markets, it is necessary to ensure enhanced technical/economic performances provided that international safety requirements are properly adhered to. When compared with high-powered nuclear power plants, NPP VVER-640 design (medium powered) possesses a number of advantages for the regions with undeveloped energy systems. Reduced specific energy intensity of the core adopted in this type of reactor allows to ensure the emergency cooldown of the reactor plant by passive means and to minimize the 'human factor' risk and external effects and provide sound substantiations as to how to retain corium inside RPV in case of severe accidents. At the same time, high-powered NPPs seem to be promising for regions with developed energy systems. Among such designs, NPP VVER-1000 and VVER-1500 designs are the most desirable. Configuration of new generation NPP with VVER-1500 is to be selected based on the gained experience in designing NPPs of previous generations considering the latest safety requirements and situation in the domestic and global energy markets for the time being and in the short run. Recent IAEA publications and latest EUR requirements insist that the following key safety indices should be established for new NPP designs: - aggregated frequency of core melting is 10 -6 (1/year); - frequency of maximum accident release is 10 -7 (1/year). To meet the aforementioned criteria, it is necessary to implement some safety assurance principles recommended by IAEA (in-depth defence, single failure, redundancy, diversity, etc.), application of deterministic and probabilistic methods for selection of safety assurance activities and means and use of reasonable combination of active and passive systems. Application of VVER-640 concept to high-powered NPPs seems to be a formidable task due to a number of reasons, namely, it is quite difficult to carry out cooldown process

  8. Cernavoda NPP Unit 1 - a plant of several generations

    International Nuclear Information System (INIS)

    Rotaru, I.; Metes, M.; Anghelescu, M.S.

    2000-01-01

    Cernavoda NPP Unit 1, the first nuclear power unit in Romania, has a long and tormented history. It represents a rather unique case in Eastern Europe. The project started well before 1989 (the construction phase lasted 17 years and generations were involved in its completion), but it is effectively based on western technology (Candu). Meanwhile, the national nuclear program underwent many changes, affecting the lives and careers of Romanian nuclear professionals. Finally, on December 2 nd 1996, the unit began its c ommercial operation , being operated at its nominal power rating of 706 MW e . It now provides a reliable source of electricity for Romanian economy, supplying to the national grid about 10% of the country's average annual demand. The paper reflects some aspects related to the shift of generations during the project's development, including the present stage. The operational performances achieved 'in service' by Cernavoda NPP Unit 1 up to the end of 1999 , are also presented. Reference to the electrical energy production, performance indicators, production costs, nuclear safety, radiation protection, radioactive wastes, nuclear fuel consumption and nuclear fuel performances are included. Comparisons are performed with similar indicators reported by other worldwide nuclear power plants, in order to assess our results. (authors)

  9. Environmental aspects of Greenfield NPP site in northern Finland

    International Nuclear Information System (INIS)

    Kopisto, L.

    2015-01-01

    Fennovoima will build a nuclear power plant of 1200 MW at Hanhikivi headland in Pyhaejoki, Northern Finland on the shore of the Baltic Sea. According to the target schedule the plant will produce electricity in 2024. The plant supplier is Rusatom Overseas, subsidiary of the Russian Rosatom. No industrial activity is practiced in the immediate surroundings of the site area and the headland and its surroundings are sparsely populated. The area is in its natural state. This means that all the preparatory and infrastructure works needs to be done before the construction of NPP can start. The environmental and nature conservation aspects have to be taken into consideration in planning, construction and operation of the NPP. Northern location sets some challenges to the design of the power plant. The sea area is normally covered with ice almost half of the year which has to be taken into account in the design of the power plant. But there are also advantages: in winter when the cooling water is cold the efficiency of electricity production is estimated to be exceptionally good, approximately 39 %. Since 2008, Fennovoima has carried out several environmental studies and surveys in the site area and has collected information about the nature conditions on land and in the sea area. The collected environmental data has been utilized in land use planning, environmental impact assessment procedure and in applying for conventional permits. The environmental data can also be used as baseline data. The document is composed of an abstract and the presentation slides

  10. Reverse osmosis using for water demineralization for supplying the NPP and TPP steam generators

    International Nuclear Information System (INIS)

    Mamet, A.P.; Sitnyakovskij, Yu.A.

    2000-01-01

    Paper analyzes the conditions affecting the efficiency of water reverse-osmosis demineralization for NPP and TPP steam generators and presents an example of efficient application of a membrane reverse-osmosis facility serving as the first stage of water demineralization at the Mosehnergo Joint-Stock Company heating and power plant no. 23 to feed boilers [ru

  11. On application of the systematic approach to training in Qinshan NPP

    International Nuclear Information System (INIS)

    Wang Riqing

    1997-01-01

    The author describes the feature of systematic approach to training and introduces the situation about using the approach for training operation and maintenance personnel in Qinshan NPP. The final part of paper shows that there are still some problems worthy of serious consideration in application of the systematic approach to training in nuclear power plant

  12. Suspension of the NPP ''Zarnowiec'' erection in opinion of the Regulatory Body

    International Nuclear Information System (INIS)

    Jozefowicz, E.T.

    1990-01-01

    The author attempts to review on behalf of The Regulatory Body, the Government's decision to suspend erection of the NPP ''Zarnowiec'' for one year. The current state of the erection and abilities (under new conditions) of the investor being still legally responsible for nuclear safety of the future power plant are analysed

  13. Crack resistance increasing in epoxide-rubber coatings of NPP room floors

    International Nuclear Information System (INIS)

    Khorenzhenko, V.I.

    1986-01-01

    Problems of crack resistance increasing in epoxide-rubber coatings for the floors are considered. Exploitation experience of the floors in the special rooms of NPP is given. Perspectivity of application of the compositions described as the building materials for nuclear power stations is pointed out

  14. Analysis of the NPP-V1 primary circuit fast cooldown

    International Nuclear Information System (INIS)

    Filo, J.; Bazso, Z.; Vranka, L.

    1994-01-01

    Results of thermal-hydraulic calculations of the NPP-V1 primary circuit fast cooldown during small leakage through openings of diameter 20, 32 and 50 mm as well as analyses of cooldown following the steam pipeline break at nominal and null reactor power are given in this paper. 4 refs, 24 figs, 1 tab

  15. Experience with Periodic Safety Review (PSR) at Kozloduy NPP after 20 years of operation

    International Nuclear Information System (INIS)

    Popov, V.

    2011-01-01

    Conclusion: Measures in the long-term Programs for improving safety and radiation protection of unit 5&6, based on PSR outcome and addressed on the units’ operation licence renewal are under way. • NPP Kozloduy intends to fulfils requirements on modern nuclear power plants which occasionally exceeds limits of the effective national nuclear legislation

  16. Summary of structural analysis and comparison with experimental results for Paks NPP

    International Nuclear Information System (INIS)

    Hauptenbuchner, B.; David, M.

    2001-01-01

    This contribution deals with the analysis and comparison of the dynamic response, calculated and measured by the explosion test in Nuclear Power Plant Paks, Hungary. Some details of the calculation model are also presented. The calculated and measured data of dynamic response are compared in selected points of the NPP Paks reactor building. Conclusions and recommendations are derived from this comparison. (author)

  17. Reliability analysis of protection systems in NPP applying fault-tree analysis method

    International Nuclear Information System (INIS)

    Bokor, J.; Gaspar, P.; Hetthessy, J.; Szabo, G.

    1998-01-01

    This paper demonstrates the applicability and limits of dependability analysis in nuclear power plants (NPPS) based on the reactor protection refurbishment project (RRP) in NPP Paks. This paper illustrates case studies from the reliability analysis for NPP Paks. It also investigates the solutions for the connection between the data acquisition and subsystem control units (TSs) and the voter units (VTs), it analyzes the influence of the voting in the VT computer level, it studies the effects of the testing procedures to the dependability parameters. (author)

  18. Practical experience with the leaky-fuel monitoring at Bohunice NPP

    International Nuclear Information System (INIS)

    Kacmar, M.; Cizek, J.

    2001-01-01

    The first part of this paper describes practical experience with the fuel monitoring in operating reactors from point of view possible leakages. Summarized in the paper are numbers leaky fuel assemblies both for NPP and for particular units. Some failure causes are discussed for operational conditions of Bohunice NPP. In the second part of paper critical power ramps on hot fuel rod of leaky fuel assemblies are analysed to eliminate failures from PCI. The main aim of the paper is the need to understand the mechanism and causes of failures (Authors)

  19. Training, education and qualification of NPP operating personnel in the Netherlands

    International Nuclear Information System (INIS)

    de Vrey, G.A.

    1987-01-01

    This paper outlines the organization and the requirements of the training, education and qualification of NPP operating personnel in the Netherlands. It describes the implementation of a formally required scheme of personnel qualification after TMI, and the current practice as developed by the training staff of both Dutch nuclear power plants. Attention is given to the specific circumstances and problems in the Netherlands, and the resulting program. The licensing criteria for control room operating personnel are discussed, including the level of government involvement. Measures are described to improve the approach to training of NPP personnel involved in safety relevant activities. Finally, some ideas are given for strategies to cope with adverse stress situations

  20. Domestic design and validation of natural circulation steam generator of China 1000 MWe PWR NPP

    International Nuclear Information System (INIS)

    Liu, H.Y.; Wang, X.Y.; Wu, G.; Qin, J.M.; Xiong, Ch.H.; Wang, W.; Chen, J.L.; Cheng, H.P.; Zuo, Ch.P.

    2005-01-01

    In order to meet the requirements of domestic design of China intending built NPP projects, Research Institute of Nuclear Power Operation (RINPO) has achieved design of 1000 MWe NPP steam generator, called RINSG-1000(means 1000MWe SG designed by RINPO), which is based on SG research ,experiments and service experience accumulated by RINPO in more 40 years. Testing validation of two steam generator key technologies, advanced moisture separate device and sludge collector, has been accomplished during the period of 2000 to 2002. This paper describes the design features of RINSG-1000, and provides some validation test results. (authors)

  1. Risks for marine coastal ecosystems from anthropogenic loading in the Leningrad NPP environs

    International Nuclear Information System (INIS)

    Zimina, L.; Zimin, V.; Shchukina, T.; Pomiluiko, G.; Ryabova, V.

    1998-01-01

    Data on conditions and variations in phytoplankton, zooplankton and fish communities, chlorophyll 'a' and hydrochemical parameters in the coastal waters of Koporskaya Bay (cooling water body of the Leningrad NPP) were analyzed. The most significant anthropogenic factors issued from the Leningrad nuclear power plant activity are of non-radioactive character, as it was recognized during long-time (20 years) ecological monitoring. Main factors influenced ecosystem of the NPP cooling water body are thermal water discharge and nutrient outflows from the bay catchment area. (authors)

  2. The Improved Methods of Critical Component Classification for the SSCs of New NPP

    International Nuclear Information System (INIS)

    Lee, Sang Dae; Yeom, Dong Un; Hyun, Jin Woo

    2010-01-01

    Functional Importance Determination (FID) process classifies the components of a plant into four groups: Critical A, Critical B, Minor and No Impact. The output of FID can be used as the decision-making tool for maintenance work priority and the input data for preventive maintenance implementation. FID applied to new Nuclear Power Plant (NPP) can be accomplished by utilizing the function analysis results and safety significance determination results of Maintenance Rule (MR) program. Using Shin-Kori NPP as an example, this paper proposes the advanced critical component classification methods for FID utilizing MR scoping results

  3. Study on mid and long-term strategic plan formulation for newly-constructed NPP

    International Nuclear Information System (INIS)

    Song Lin

    2014-01-01

    Mid and Long-term strategic plan plays a key role for the management of a newly constructed nuclear power company. Among others, process, goals, and risk management, are the primary concerns during plan preparing. The article analyzed these three areas for Fuqing NPP, including the formulating process for the plan, the mid and long-term goal setting of the company, the major risk analysis and countermeasure selection therefore. Through that solutions and suggestions for strategic plan formulation were concluded for newly-constructed NPP. (author)

  4. ORSEC technological risks, Blayais NPP

    International Nuclear Information System (INIS)

    2016-01-01

    The Particular intervention plan (PPI in French) is an emergency plan which foresees the measures and means to be implemented to address the potential risks of the presence and operation of a nuclear facility. This plan is implemented and developed by the Prefect in case of nuclear accident (or incident leading to a potential accident), the impact of which extending beyond the facility perimeter. It represents a special section of the organisation plan for civil protection response (ORSEC plan). The PPI foresees the necessary measures and means for crisis management during the first hours following the accident and is triggered by the Department Prefect according to the information provided by the facility operator. Its aim is to protect the populations leaving within 10 km of the facility against a potential radiological hazard. The PPI describes: the facility, the intervention area, the protection measures for the population, the conditions of emergency plan triggering, the crisis organisation, the action forms of the different services, and the post-accident stage. This document is the public version of the Particular intervention plan of the Blayais NPP (Gironde, France)

  5. Determination of Safety Performance Grade of NPP Using Integrated Safety Performance Assessment (ISPA) Program

    International Nuclear Information System (INIS)

    Chung, Dae Wook

    2011-01-01

    Since the beginning of 2000, the safety regulation of nuclear power plant (NPP) has been challenged to be conducted more reasonable, effective and efficient way using risk and performance information. In the United States, USNRC established Reactor Oversight Process (ROP) in 2000 for improving the effectiveness of safety regulation of operating NPPs. The main idea of ROP is to classify the NPPs into 5 categories based on the results of safety performance assessment and to conduct graded regulatory programs according to categorization, which might be interpreted as 'Graded Regulation'. However, the classification of safety performance categories is highly comprehensive and sensitive process so that safety performance assessment program should be prepared in integrated, objective and quantitative manner. Furthermore, the results of assessment should characterize and categorize the actual level of safety performance of specific NPP, integrating all the substantial elements for assessing the safety performance. In consideration of particular regulatory environment in Korea, the integrated safety performance assessment (ISPA) program is being under development for the use in the determination of safety performance grade (SPG) of a NPP. The ISPA program consists of 6 individual assessment programs (4 quantitative and 2 qualitative) which cover the overall safety performance of NPP. Some of the assessment programs which are already implemented are used directly or modified for incorporating risk aspects. The others which are not existing regulatory programs are newly developed. Eventually, all the assessment results from individual assessment programs are produced and integrated to determine the safety performance grade of a specific NPP

  6. Cernavoda NPP impact study on terrestrial and aquatic biota. Preliminary results

    International Nuclear Information System (INIS)

    Bobric, Elena; Bucur, Cristina; Popescu, Ion; Simionov, Vasile; Titescu, Gheorghe; Varlam, Carmen

    2010-01-01

    Recently, the awareness of the vulnerability of the environment has increased and the need to protect it against industrial pollutants has been recognized. The concept of sustainable development, requires new and developing international policies for environmental protection. See 'Protection of the environment from the effects of ionizing radiation' IAEA-TECDOC-1091, International Atomic Energy Agency, Vienna. As it is recommended in 'Cernavoda Unit No. 2 NPP Environmental Impact Assessment CES-03702-IAD-006', it is Cernavoda NPP responsibility to conduct an Ecological Risk Assessment study, mainly to assess the impact of nuclear power plant operation on terrestrial and aquatic biota. Long records from normal operation of Cernavoda Unit 1, wind pattern, meteorological conditions, and source terms data were used to evaluate areas of interest for environmental impact, conducting to a circle of 20 km radius around mentioned nuclear objective. The screening campaign established tritium level (because Cernavoda NPP is a CANDU type reactor, and tritium is the most important radioisotope evacuated in the environment) in air, water, soil and vegetation, focusing the interest area on particular ecosystem. Using these primary data it was evaluated which are the monitored ecological receptors and which are the measurement endpoints.This paper presents the Ecological Risk Assessment at Cernavoda NPP technical requirements, and the preliminary results of evaluating criteria for representative ecosystem components at Cernavoda NPP. (authors)

  7. Fission product source from Ignalina NPP in case of loss-of-coolant accidents

    International Nuclear Information System (INIS)

    Ubonavicius, E.; Rimkevicius, S.

    2001-01-01

    The release of radioactive materials to the environment is of special importance in the case of any accident at Nuclear Power Plants (NPP). The integrated analysis of thermal-hydraulic parameters behavior and radioactive fission products (FP) transport and deposition in the compartments play an important role in the evaluation of FP release to the environment and determines the irradiation dozes of personnel and public. In this report the transport and the deposition of radioactive material in the Ignalina NPP unit 1 compartments as well as the FP source term to the environment in the case of design basis loss-of-coolant accidents are discussed. The calculation models for the evaluation of FP transport and deposition as well as the results of performed calculations of several accidents at Ignalina NPP are presented. (author)

  8. Current evolutionary stage of L/ILW management at operating NPP in the USA

    International Nuclear Information System (INIS)

    Miller, C.C.

    2001-01-01

    The volume of Low and Intermediate Level Waste (L/ILW) from commercial nuclear power plants (NPP) buried annually in the USA has decreased dramatically over the last two decades. The reduction in disposal volume has occurred for both dry active wastes (DAW) and wet wastes (e.g., resins, filters and sludges). Decreased disposal volume has occurred at both Pressurized Water Reactors (PWRs) and Boiling Water Reactors (BWRs). The reduction in disposal volume occurred in stages. The major driver to reduce disposal volume in the commercial sector of the USA has been increasing burial costs. The current drive to further reduce overall NPP operating costs to meet a deregulated electric market in the USA has unexpectedly resulted in further waste reductions. This paper will review the stages of waste reduction and describe the current stage for NPP in the USA. (author)

  9. Seismic qualification tests of fans of the NPP of Laguna Verde U-1 and U-2

    International Nuclear Information System (INIS)

    Jarvio C, G.; Garcia H, E. E.; Arguelles F, R.; Vela H, A.; Naranjo U, J. L.

    2013-10-01

    This work presents the results of the seismic qualification tests applied to the fans that will be installed in the control panels of the three divisions of the diesel generators of the nuclear power plant (NPP) of Laguna Verde, Unit-1 and Unit-2. This seismic qualification process of the fans was carried out using two specimens that were tested in the seismic table (vibrating) of the Engineering Institute of Universidad Nacional Autonoma de Mexico (UNAM), in accordance with the requirements of the standard IEEE 344-1975, to satisfy the established requirements of seismic qualification in the technical specifications and normative documents required by the nuclear standards, in order to demonstrate its application in the diesel generators Divisions I, II and III of the NPP. The seismic qualification tests were developed on specimens that were retired of the NPP of Laguna Verde recently with a service life of 7.75 years. (Author)

  10. Review report on the dynamical study of the main building of the Paks NPP

    International Nuclear Information System (INIS)

    Gatti, F.

    1995-01-01

    The present report deals with the review of the report 'Dynamical Study of the main building of the Paks NPP', issued by Paks NPP (Hungary) on April, 1993, within the frame of the IAEA benchmark study for the seismic analysis and testing of an existing Nuclear Power Plant (M), and on behalf of ENEL DSR/VDN Rome, in the aims of the nuclear activities of ENEL DSR/VDN (Rome). After a foreword to define the aims of the job (Chapter 1) and the identification of the scope of the work (Chapter 2), a short list of references is given (Chapter 3). In Chapter 4, the criteria followed in the review activity are listed; in Chapter 5, the contents of the Paks NPP report are summarized. In Chapter 6 the results of the review are given, while the main conclusions of the review activities are summarized in the Chapter 7. (author)

  11. Checking of seismic and tsunami hazard for coastal NPP of Chinese continent after Fukushima nuclear accident

    Institute of Scientific and Technical Information of China (English)

    Chang Xiangdong; Zhou Bengang; Zhao Lianda

    2013-01-01

    A checking on seismic and tsunami hazard for coastal nuclear power plant (NPP) of Chinese continent has been made after Japanese Fukushima nuclear accident caused by earthquake tsunami.The results of the checking are introduced briefly in this paper,including the evaluations of seismic and tsunami hazard in NPP siting period,checking results on seismic and tsunami hazard.Because Chinese coastal area belongs to the continental shelf and far from the boundary of plate collision,the tsunami hazard is not significant for coastal area of Chinese continent.However,the effect from tsunami still can' t be excluded absolutely since calculated result of Manila trench tsunami source although the tsunami wave is lower than water level from storm surge.The research about earthquake tsunami will continue in future.The tsunami warning system and emergency program of NPP will be established based on principle of defense in depth in China.

  12. Experience in development and implementation of Control Room continuing training programme at Ignalina NPP

    International Nuclear Information System (INIS)

    Peradze, K.

    2002-01-01

    Based on the same SAT principles each NPP (or operating organisation) goes by its own way, which is defined by available resources, assistance, NPP operational conditions, including policy, economics and public opinion. There were several groups of factors, which are very important to provide quality of training- Time, Human Resources and material resources. We pay especial attention to simulator training. In different conditions personnel behaviour is defined by knowledge, rule or skills. It is very difficult to develop unknown to personnel scenarios. But sometimes- real events not described in plant procedures take place at Nuclear Power Plants. Therefore during NPP events analysis we pay a especial attention searching for situation when knowledge or rule defines personnel behaviour. To provide analysis and statistics of Control Room Personnel training at INPP simulator we developed 'INPP events computer data base'. (author)

  13. Fusion of eastern and western technology in VVER 1000 NPP upgrade

    International Nuclear Information System (INIS)

    Ubra, O.; Fleischhans, J.; Kveton, M.

    1997-01-01

    An extensive modernization program upgrading two units of VVER 1000 type of the Czech nuclear power plant (NPP) Temelin to meet the latest international standards is presented. The program is based primarily on combination of eastern and western technology and it has been implemented during plant construction. The NPP Temelin was originally designed according to the standards of the former Soviet Union. After a series of reviews in the 1990s, a decision was made by the Temelin management of upgrade the design of the plant, including the supply of fuel and instrumentation and control system by a western company. The adoption of western technology and practices has helped to solve a large number of IAEA safety issues related to design and operation of VVER 1000 NPP. Details on the current Temelin design and other related safety matters are presented

  14. Seismic qualification of civil engineering structures - Temelin NPP

    International Nuclear Information System (INIS)

    Schererova, K.; Holub, I.; Stepan, J.; Maly, J.

    2004-01-01

    Basic information is presented about the input data and methodology used for evaluation of Temelin NPP civil structures. The existing conditions as listed in POSAR report for the two reactor units are considered. The original design of the power plant assumed a lower level of locality seismic hazard, as followed from seismological surveys that where then available. Later the seismic assessment was updated while fully respecting IAEA recommendations and using a minimum value of acceleration in the horizontal direction PGAHOR = 0.1 g at free field level for SL-2. In relation to the new seismic project, new qualification of the structures, components and systems classed as seismic resistance category 1 was carried out. Since the Czech Republic has no specific technical standards for seismic resistance evaluation of nuclear power plants, a detailed methodology was elaborated, comprising principles of seismic resistance evaluation based on IAEA guides and on common practice in countries with advanced nuclear power engineering. (P.A.)

  15. Slovak Electric, plc, Mochovce Nuclear Power Plant

    International Nuclear Information System (INIS)

    2000-01-01

    In this popular scientific brochure a brief description of history construction of Bohunice Nuclear Power Plant is presented. The chart of electricity generation in WWER 440/V-213 nuclear power plant is described. Operation and safety improvements at Mochovce NPP as well as environment protection are presented. Basic data of Mochovce NPP are included

  16. Maintaining staff competence-a NPP operator viewpoint

    International Nuclear Information System (INIS)

    Patrakka, E.

    2000-01-01

    For a nuclear power plant operator, it is crucial to guarantee the safe and economic operation of the power plant as well as to look after the general acceptability of nuclear power. As to human resources management, this requires continuous maintenance and enhancement of the performance of the individuals and organisation. To this end, several development projects have recently been implemented by Teollisuuden Voima Oy (TVO) at the Olkiluoto nuclear power plant, which consists of twin 840 MWe BWR units that commenced their operation in 1978 and 1980. Systematic initial and continuing training programmes are needed to maintain the technical and managerial skills and know-how at a high level. The present stabile state of nuclear power, i.e. operation of ageing plants with personnel ageing as well, requires a variety of actions to reinforce the training efforts. At Olkiluoto NPP, we have carried out an extensive modernization programme that allowed the personnel to strengthen their knowledge and supplement it with the most recent results of development. We have also closely monitored the NPP development projects of the vendors, which has added to the preservation of know-how and understanding of advanced nuclear power technology. We have close contacts to the research institutes and universities, and have performed R and D activities to limited extent. In addition to the projects mentioned above, a co-ordinated development programme, 'TVO 2002', was initiated last year. The main objective of this programme is to ensure the functional preconditions and the competitiveness of the company in a changing environment. The management and operational procedures will be developed in such a way that the goals set for year 2002 will be achieved. The programme is organised as ten projects, which cover a variety of development subjects. One of the focal areas includes projects that can be characterised with the words 'Survey of competencies' and 'Preservation of know

  17. Environmental impact of the NPP Krsko

    International Nuclear Information System (INIS)

    Novosel, N.

    1996-01-01

    The Ministry of Economic Affairs has for six years now been monitoring the operation of the Krsko NPP (NEK) and its impact on the environment. A bulletin titled 'NEK - Energy and Environment' is being issued every three months. It contains information on operation of the Krsko NPP for the previous three months, a graph of duration of temperature increase of water in the Sava river (delta T) in that period, an assessment of the radiological impact of Krsko NPP on the environment through an equivalent dose cumulatively throughout the calendar year, and a short current text related to Krsko NPP. The Ministry of Economic Affairs organizes a press conference on every issue of the bulletin, as an attempt of introducing this subject to the media and to the public. This paper contains a review of information given in the NEK bulletin from 1990 to 1995 with a special emphasis on the contribution of the Krsko NPP to the artificially caused radiation on the border between the Republic of croatia and the Republic of Slovenia. (author)

  18. Integrated ageing management of Atucha NPP

    International Nuclear Information System (INIS)

    Ranalli, Juan M.; Marchena, Martin H.; Zorrilla, Jorge R.; Antonaccio, Elvio E.; Brenna, Pablo; Yllanez, Daniela; Cruz, Gerardo Vera de la; Luraschi, Carlos; Sabransky, Mario

    2013-01-01

    Atucha NPP is a two PHWR unit site located in Lima, Province of Buenos Aires, 120 km north of Buenos Aires, Argentina. Until recent, the site was split in Atucha I NPP, a 350 MW pressure vessel heavy water reactor in operation since 1974; and Atucha II, a similar design reactor, twice as big as Atucha I finishing a delayed construction. With the start-up of Atucha II and aiming to integrate the management of the plants, the Utility (Nucleolectrica Argentina Sociedad Anonima - NASA) has reorganized its operation units. Within this reorganization, an Ageing Management Department has been created to cope with all ageing issues of both Atucha I and II units. The Atomic Energy Commission of Argentina (Comision Nacional de Energia Atomica - CNEA) is a state-owned R and D organization that; among other functions such as designing and building research reactors, developing uranium mining and supplying radioisotopes to the medical market; is in charge of providing support and technological update to all Argentinean NPPs. The Ageing Management Department of Atucha NPP and the Ageing Management Division of CNEA has formed a joint working group in order to set up an Integrated Ageing Management Program for Atucha NPP following IAEA guidelines. In the present work a summary of the activities, documental structure and first outputs of the Integrated Ageing Management Program of Atucha NPP is presented. (author)

  19. Integrated Ageing Management of Atucha NPP

    International Nuclear Information System (INIS)

    Ranalli, J.M.; Marchena, M.H.; Zorrilla, J.R.; Sabransky, M.

    2012-01-01

    Atucha NPP is a two PHWR unit site located in Lima, Province of Buenos Aires, 120 km north of Buenos Aires, Argentina. Until recent, the site was split in Atucha I NPP, a 350 MW pressure vessel heavy water reactor in operation since 1974; and Atucha II, a similar design reactor twice as big as Atucha I finishing a delayed construction . With the start-up of Atucha II and aiming to integrate the management of the plants, the Utility (Nucleolectrica Argentina Sociedad Anonima - NASA) has reorganized its operation units. Within this reorganization, an Ageing Management Department has been created to cope with all ageing issues of both Atucha I and II units. The Atomic Energy Commission of Argentina (Comision Nacional de Energia Atomica - CNEA) is a state-owned R and D organization that; among other functions such as designing and building research reactors, developing uranium mining and supplying radioisotopes to the medical market; is in charge of providing support and technological update to all Argentinean NPPs. The Ageing Management Department of Atucha NPP and the Ageing Management Division of CNEA has formed a joint working group in order to set up an Integrated Ageing Management Program for Atucha NPP following IAEA guidelines. In the present work a summary of the activities, documental structure and first outputs of the Integrated Ageing Management Program of Atucha NPP is presented. (author)

  20. Integrated ageing management of Atucha NPP

    Energy Technology Data Exchange (ETDEWEB)

    Ranalli, Juan M.; Marchena, Martin H.; Zorrilla, Jorge R.; Antonaccio, Elvio E.; Brenna, Pablo; Yllanez, Daniela; Cruz, Gerardo Vera de la; Luraschi, Carlos, E-mail: ranalli@cnea.gov.ar [Gerencia Coordinacion Proyectos CNEA-NASA, Comision Nacional de Energia Atomica, Buenos Aires (Argentina); Sabransky, Mario, E-mail: msabransky@na-sa.com.ar [Departamento Gestion de Envejecimiento, Central Nuclear Atucha I-II Nucleoelectrica Argentina S.A., Provincia de Buenos Aires (Argentina)

    2013-07-01

    Atucha NPP is a two PHWR unit site located in Lima, Province of Buenos Aires, 120 km north of Buenos Aires, Argentina. Until recent, the site was split in Atucha I NPP, a 350 MW pressure vessel heavy water reactor in operation since 1974; and Atucha II, a similar design reactor, twice as big as Atucha I finishing a delayed construction. With the start-up of Atucha II and aiming to integrate the management of the plants, the Utility (Nucleolectrica Argentina Sociedad Anonima - NASA) has reorganized its operation units. Within this reorganization, an Ageing Management Department has been created to cope with all ageing issues of both Atucha I and II units. The Atomic Energy Commission of Argentina (Comision Nacional de Energia Atomica - CNEA) is a state-owned R and D organization that; among other functions such as designing and building research reactors, developing uranium mining and supplying radioisotopes to the medical market; is in charge of providing support and technological update to all Argentinean NPPs. The Ageing Management Department of Atucha NPP and the Ageing Management Division of CNEA has formed a joint working group in order to set up an Integrated Ageing Management Program for Atucha NPP following IAEA guidelines. In the present work a summary of the activities, documental structure and first outputs of the Integrated Ageing Management Program of Atucha NPP is presented. (author)

  1. A GeoServices Infrastructure for Near-Real-Time Access to Suomi NPP Satellite Data

    Science.gov (United States)

    Evans, J. D.; Valente, E. G.; Hao, W.; Chettri, S.

    2012-12-01

    The new Suomi National Polar-orbiting Partnership (NPP) satellite extends NASA's moderate-resolution, multispectral observations with a suite of powerful imagers and sounders to support a broad array of research and applications. However, NPP data products consist of a complex set of data and metadata files in highly specialized formats; which NPP's operational ground segment delivers to users only with several hours' delay. This severely limits their use in critical applications such as weather forecasting, emergency / disaster response, search and rescue, and other activities that require near-real-time access to satellite observations. Alternative approaches, based on distributed Direct Broadcast facilities, can reduce the delay in NPP data delivery from hours to minutes, and can make products more directly usable by practitioners in the field. To assess and fulfill this potential, we are developing a suite of software that couples Direct Broadcast data feeds with a streamlined, scalable processing chain and geospatial Web services, so as to permit many more time-sensitive applications to use NPP data. The resulting geoservices infrastructure links a variety of end-user tools and applications to NPP data from different sources, and to other rapidly-changing geospatial data. By using well-known, standard software interfaces (such as OGC Web Services or OPeNDAP), this infrastructure serves a variety of end-user analysis and visualization tools, giving them access into datasets of arbitrary size and resolution and allowing them to request and receive tailored products on demand. The standards-based approach may also streamline data sharing among independent satellite receiving facilities, thus helping them to interoperate in providing frequent, composite views of continent-scale or global regions. To enable others to build similar or derived systems, the service components we are developing (based in part on the Community Satellite Processing Package (CSPP) from

  2. Simulator experiments: effects of NPP operator experience on performance

    International Nuclear Information System (INIS)

    Beare, A.N.; Gray, L.H.

    1985-01-01

    Experiments are being conducted on nuclear power plant (NPP) control room training simulators by the Oak Ridge National Laboratory, its subcontractor, General Physics Corporation, and participating utilities. The experiments are sponsored by the Nuclear Regulatory Commission's (NRC) Human Factors and Safeguards Branch, Division of Risk Analysis and Operations, and are a continuation of prior research using simulators, supported by field data collection, to provide a technical basis for NRC human factors regulatory issues concerned with the operational safety of nuclear power plants. During the FY83 research, a simulator experiment was conducted at the control room simulator for a GE boiling water reactor (BWR) NPP. The research subjects were licensed operators undergoing requalification training and shift technical advisors (STAs). This experiment was designed to investigate the effects of (a) senior reactor operator (SRO) experience, (b) operating crew augmentation with an STA and (c) practice, as a crew, upon crew and individual operator performance, in response to anticipated plant transients. The FY84 experiments are a partial replication and extension of the FY83 experiment, but with PWR operators and simulator. Methodology and results to date are reported

  3. Engineering Center contribution to the Russian NPP aging management

    International Nuclear Information System (INIS)

    Bougaenko, S.

    1993-01-01

    The Engineering Center of strength, reliability and life of the nuclear equipment of the Minatom, Russia, has been set up by the decision of the management of the Russian Federation Ministry on the nuclear power (Russia Minatom) within the framework of the Research and Development Institute of Power Engineering (RDIPE). The Engineering Center is responsible for fulfilling the functions of the leading Institution of the Ministry concerning these issues and it is in charge of the development of the appropriate rules and standards package as well as their compliance with analogous international regulating documents. To put forward the national program on NPP aging management, and to implement it is one of the crucial tasks of the Engineering Center. This activity is conducted by both the cooperation between Russian Institution and experts and within the framework of the international collaboration. In the latter case it is worthy of noting the activity with respect to the American-Russian Working Group 12 ''NPP Aging and Life Extension'' and participation in appropriate programs of the IAEA. The major trends of the above activity are considered in this paper

  4. Status of Chinese NPP Industry and Nuclear Fuel Cycle Policy

    Energy Technology Data Exchange (ETDEWEB)

    Gao, R. X. [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of); Ko, W. I.; Kim, S. K. [Univ. of Science and Technology, Daejeon (Korea, Republic of)

    2013-05-15

    China still extended their experiences to both domestic and overseas so far. Chinese State Council approved its 'Medium and Long-term Nuclear Power Development Plan' in November 2007, indicating further definition for nuclear energy as indispensable energy option and future self-reliance development of nuclear industry. China intends to become self-sufficient not only in NPPs capacity, but also in the fuel production for all those plants. There are currently 17 NPPs in operation, and 28 NPPs under construction. However, domestic uranium mining supplying is currently less than a quarter of nuclear fuel demands. This paper investigated and summarized the updated status of NPP industry in China and Nuclear Fuel Cycle(NFC) policy. There still remain a number of technical innovation and comprehensive challenges for this nuclear developing country in the long-term, but its large ambitions and dramatic improvements toward future should not be ignored. As shown in this paper, the most suitable approach for China to achieve both environmentally-friendly power supplying and increasing energy demands meeting simultaneously must be considered. Nuclear energy now was recognized as the most potential and optimal way of energy supply system. In addition, to accommodate such a high-speed NPP construction in China, it should also focus on when and how spent nuclear fuel should be reprocessed. Finally, the nuclear back-end fuel cycle policy should be established, taking into accounts of all costs, uranium resource security, spent fuel management, proliferation resistance and environmental impact.

  5. Improvement of coal focus and cooling towers of COFRENTES NPP

    International Nuclear Information System (INIS)

    Martinez, I.; Bogh, P.

    1998-01-01

    Cofrentes Nuclear Power Plant is performing a improving program of its cooling towers based on the filling revamping and cooling water circuit improvement. Furthermore, and as consequence of the acquired experience on cooling towers due to the mentioned program, Cofrentes NPP has decided to follow up with this project from a different point of view based on the thermal-hydraulic optimization of the cooling process inside the towers. This program, which is going to be carried out by Cofrentes NPP, Iberinco and Energy Planning and Power Generation (EPPG) provides an improvement on the thermal profile and of the draught inside the cooling towers by improving the water distribution in the towers active area. In order to perform such a program is needed to fulfill a test program to assure a guaranteed performance gain. In this way, Iberinco is developing a test procedure which improves the results which are obtained with the present standards used commonly by the industry. As a consequence of this program, Cofrentes is expecting to obtain a gain of 5 to 8 MWe with a revenue period of 4 to 5 months, results validated in another foreigner Plant which have developed a similar program. (Author)

  6. Monitoring for radioactive materials releasing to environment in M310 reformatived nuclear power plant

    International Nuclear Information System (INIS)

    Yin Zhenyu; Yang Guangli; Xu Guang

    2012-01-01

    Airborne radioactive materials of nuclear power plant (NPP) releases to the environment from the stack of NPP. Radioactive liquid waste releases of the ocean, the fluvial and the lake through the liquid waste letdyke of NPP. Further more, a few radioactive waste may be taken out of the NPP by vehicle or personnel. For the purpose of strict management and control above-mentioned waste, we use detect equipment monitoring radioactive waste of NPP. Management and control for the releasing of radioactive material to the environment in M310 reformatived NPP is strict and safety. (authors)

  7. External Events PSA for the Paks NPP

    International Nuclear Information System (INIS)

    Bareith, Attila; Karsa, Zoltan; Siklossy, Tamas; Vida, Zoltan

    2014-01-01

    Initially, probabilistic safety assessment of external events was limited to the analysis of earthquakes for the Paks Nuclear Power Plant in Hungary. The level 1 seismic PSA was completed in 2002 showing a significant contribution of seismic failures to core damage risk. Although other external events of natural origin had previously been screened out from detailed plant PSA mostly on the basis of event frequencies, a review of recent experience on extreme weather phenomena made during the periodic safety review of the plant led to the initiation of PSA for external events other than earthquakes in 2009. In the meantime, the accident of the Fukushima Dai-ichi Nuclear Power Plant confirmed further the importance of such an analysis. The external event PSA for the Paks plant followed the commonly known steps: selection and screening of external hazards, hazard assessment for screened-in external events, analysis of plant response and fragility, PSA model development, and risk quantification and interpretation of results. As a result of event selection and screening the following weather related external hazards were subject to detailed analysis: extreme wind, extreme rainfall (precipitation), extreme snow, extremely high and extremely low temperatures, lightning, frost and ice formation. The analysis proved to be a significant challenge due to scarcity of data, lack of knowledge, as well as limitations of existing PSA methodologies. This paper presents an overview of the external events PSA performed for the Paks NPP. Important methodological aspects are summarised. Key analysis findings and unresolved issues that need further elaboration are highlighted. Development of external events PSA for the Paks NPP was completed by the end of 2012. The analysis followed the commonly known steps: selection and screening of external hazards, hazard assessment for screened-in external events, analysis of plant response and fragility, PSA model development, and risk

  8. R and D status for NPP life management in Korea

    Energy Technology Data Exchange (ETDEWEB)

    Kim, Tae Ryong [Korea Electric Power Research Institute, Daejeon (Korea, Republic of)

    2009-04-15

    The economical benefits may be achieved by the plant life management (PLiM) as well as structural integrity of the critical components of NPP. Systems, structures and components (SSC) of NPP are designed to have safety margins in design stage, and being operated with operational margins. As the plant gets older and older, however, aging of SSC occurs and some of SSC may be sometimes failed due to the unexpected aging mechanisms in design stage. Most countries which have operated NPP have their own R and D programs to establish proper countermeasures against the aging and degradation of SSC, The well known program are materials reliability program (MRP) and steam generator management program (SGMP) of EPRI. In Korea, we also have our own R and D programs for the plant life management. In this paper, the present status of the R and D programs will be introduced. Long term operation of a nuclear power plant is one of the goals that the plant wants to achieve, which may be possible as long as the plant safety is maintained and the economical benefits is expected. The economical benefits may be achieved by the plant life management (PLiM) activities. Many R and D activities related to PLiM have been carried out and implemented to Korean NPP, Kori Unit 1 and Wolsong Unit 1 in particular, for the long term operation beyond their original design lives. Those activities include PLiM study, PSR, SGMP, MRP, thinned pipe management program, study on dissimilar metal welds, aging monitor etc. With the results of R and D activities, continued operation of Kori Unit 1 was successfully started from January 17, 2008 for next 10 years beyond its design life. It must be a landmark of 30 years history of nuclear power generation in Korea. Subsequently Wolsong Unit 1 is also expected to start its continued operation when the replacement of pressure tubes and feeders are completed in 2009. Many countries have plans to build new reactors or to extend the life of operating plants.

  9. Application of Robotic System for Emergency Response in NPP

    International Nuclear Information System (INIS)

    Jeong, Kyung Min; Seo, Yong Chil; Shin, Ho Chul; Lee, Sung Uk; Cho, Jae Wan; Choi, Young Soo; Kim, Chang Hoi; Kim, Seung Ho

    2010-01-01

    Increasing energy demand and concerns over climate change make increasing use of nuclear power plant in worldwide. Even though the probability of accident is greatly reduced, safety is the highest priority issue in the nuclear energy industry. Applying highly reliable and conservative 'defense in depth' concepts with the design and construction of NPP, there are very little possibilities with which accidents are occur and radioactive materials are released to environments in NPP. But NPP have prepared with the emergency response procedures and conduct exercises for post-accident circumstance according to the procedures. The application of robots for emergency response task for post-accident in nuclear facilities is not a new concept. Robots have been sent to recover the damaged reactor at Chernobyl where human workers could receive a lifetime dose of radiation in minutes. Based on NRC's TMI-2 Cleanup Program, several robots were built in the 1980s to help gather information and remove debris from a reactor at the Three Mile Island nuclear power plant that partially melted down in 1979. The first robot was lowered into the basement through a hatch and human operators monitoring in a control room drove it through mud, water and debris, capturing the initial post-accident images of the reactor's basement. It was used for several years equipped with various tools allowing it to scour surfaces, scoop samples and vacuum sludge. A second version carried a core sampler to determine the intensity and depth of the radiation that had permeated into the walls. To perform cleanup tasks, they built Workhorse that featured system redundancy and had a boom extendable to reach high places, but it was never used because it had too many complexities and to clean and fix. While remote robotics technology has proven to remove the human from the radioactive environment, it is also difficult to make it useful because it may requires skill about remote control and obtaining remote

  10. R and D status for NPP life management in Korea

    International Nuclear Information System (INIS)

    Kim, Tae Ryong

    2009-01-01

    The economical benefits may be achieved by the plant life management (PLiM) as well as structural integrity of the critical components of NPP. Systems, structures and components (SSC) of NPP are designed to have safety margins in design stage, and being operated with operational margins. As the plant gets older and older, however, aging of SSC occurs and some of SSC may be sometimes failed due to the unexpected aging mechanisms in design stage. Most countries which have operated NPP have their own R and D programs to establish proper countermeasures against the aging and degradation of SSC, The well known program are materials reliability program (MRP) and steam generator management program (SGMP) of EPRI. In Korea, we also have our own R and D programs for the plant life management. In this paper, the present status of the R and D programs will be introduced. Long term operation of a nuclear power plant is one of the goals that the plant wants to achieve, which may be possible as long as the plant safety is maintained and the economical benefits is expected. The economical benefits may be achieved by the plant life management (PLiM) activities. Many R and D activities related to PLiM have been carried out and implemented to Korean NPP, Kori Unit 1 and Wolsong Unit 1 in particular, for the long term operation beyond their original design lives. Those activities include PLiM study, PSR, SGMP, MRP, thinned pipe management program, study on dissimilar metal welds, aging monitor etc. With the results of R and D activities, continued operation of Kori Unit 1 was successfully started from January 17, 2008 for next 10 years beyond its design life. It must be a landmark of 30 years history of nuclear power generation in Korea. Subsequently Wolsong Unit 1 is also expected to start its continued operation when the replacement of pressure tubes and feeders are completed in 2009. Many countries have plans to build new reactors or to extend the life of operating plants.

  11. Application of Robotic System for Emergency Response in NPP

    Energy Technology Data Exchange (ETDEWEB)

    Jeong, Kyung Min; Seo, Yong Chil; Shin, Ho Chul; Lee, Sung Uk; Cho, Jae Wan; Choi, Young Soo; Kim, Chang Hoi; Kim, Seung Ho [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2010-10-15

    Increasing energy demand and concerns over climate change make increasing use of nuclear power plant in worldwide. Even though the probability of accident is greatly reduced, safety is the highest priority issue in the nuclear energy industry. Applying highly reliable and conservative 'defense in depth' concepts with the design and construction of NPP, there are very little possibilities with which accidents are occur and radioactive materials are released to environments in NPP. But NPP have prepared with the emergency response procedures and conduct exercises for post-accident circumstance according to the procedures. The application of robots for emergency response task for post-accident in nuclear facilities is not a new concept. Robots have been sent to recover the damaged reactor at Chernobyl where human workers could receive a lifetime dose of radiation in minutes. Based on NRC's TMI-2 Cleanup Program, several robots were built in the 1980s to help gather information and remove debris from a reactor at the Three Mile Island nuclear power plant that partially melted down in 1979. The first robot was lowered into the basement through a hatch and human operators monitoring in a control room drove it through mud, water and debris, capturing the initial post-accident images of the reactor's basement. It was used for several years equipped with various tools allowing it to scour surfaces, scoop samples and vacuum sludge. A second version carried a core sampler to determine the intensity and depth of the radiation that had permeated into the walls. To perform cleanup tasks, they built Workhorse that featured system redundancy and had a boom extendable to reach high places, but it was never used because it had too many complexities and to clean and fix. While remote robotics technology has proven to remove the human from the radioactive environment, it is also difficult to make it useful because it may requires skill about remote control and

  12. Reserves of labour content reduction in NPP construction

    International Nuclear Information System (INIS)

    Bekerman, R.E.

    1986-01-01

    Specific labour contents when constructing NPP with RBMK-1000 and WWER-1000 type reactors are presented. Factors affecting labour content of NPP construction are shown. Measures aimed at labour content decrease are suggested

  13. Regulatory aspects of NPP safety

    International Nuclear Information System (INIS)

    Stuller, J.; Brandejs, P.; Miasnikov, A.; Svab, M.

    1999-01-01

    In beginning, a history of legislative process regulating industrial utilisation of nuclear energy is given, including detailed list of decrees issued by the first regulatory body supervising Czech nuclear installations - Czechoslovak Atomic Energy Commission (CSKAE). Current status of nuclear regulations and radiation protection, especially in connection with Atomic Act (Act No 18/1997 Coll.), is described. The Atomic Act transfers into the Czech legal system a number of obligations following from the Vienna Convention on Civil Liability for Nuclear Damage and Joint Protocol relating to the Application of the Vienna and Paris Convention, to which the Czech Republic had acceded. Actual duties and competence of current nuclear regulatory body - State Office for Nuclear Safety (SUJB) - are given in detail. Execution of the State supervision of peaceful utilisation of nuclear energy and ionising radiation is laid out in several articles of the Act, which comprises: control activities of the SUJB, remedial measures, penalties. Material and human resources are sufficient for fulfilment of the basic functions for which SUJB is authorised by the law. For 1998, the SUJB allotted staff of 149, approximately 2/3 of that number are nuclear safety and radiation protection inspectors. The SUJB budget for 1998 is approximately 180 million Czech crowns (roughly 6 million US dollars). Inspection activity of SUJB is carried out in three different ways: routine inspections, planned specialised inspections, inspections as a response to a certain situation (ad-hoc inspections). Approach to the licensing of major plant upgrades and backfittings are mainly illustrated on the Temelin NPP licensing. Regulatory position and practices concerning review activities are presented. (author)

  14. Nuclear power plant V-2

    International Nuclear Information System (INIS)

    1998-01-01

    The nuclear power plant Bohunice V -2 is briefly described. This NPP consists from two reactor units. Their main time characteristics are (Reactor Unit 1, Reactor Unit 2): beginning of construction - December 1976; first controlled reactor power - 7 August 1984, 2 August 1985; connection to the grid - 20 August 1984, 9 August 1985; commercial operation - 14 February 1985, 18 December 1985. This leaflet contains: NPP V-2 construction; Major technological equipment [WWER 440 V230 type reactor; Nuclear Power plant operation safety (Safety barriers; Safety systems [Active safety systems, Passive safety systems]); Centralized heat supply system; Scheme of Bohunice V-2 NPP and technical data

  15. Methodology transfer for the preparation of NPP decommissioning for leading personnel of the Ignalina NPP and for the representatives of Lithuanian authorities

    International Nuclear Information System (INIS)

    Ackermann, L.; Baecker, A.

    2004-01-01

    At request of the Lithuanian government to receive support for the preparation of the decommissioning of Ignalina NPP, a bilateral project was financed by the German federal government to transfer experience from the decommissioning of the Greifswald and Rheinsberg NPPs to the management staff of the Ignalina NPP and to the representatives of the Lithuanian authorities in charge of the decommissioning. The methodology transfer project was prepared and carried out under the leadership of the Gesellschaft fuer Anlagen- und Reaktorsicherheit (GRS) mbH. The practical implementation was within the responsibility of Energiewerke Nord GmbH (EWN) in cooperation with other German subcontractors. The methodology transfer comprised the task fields of project management, project planning, licensing procedure and waste management as well as social aspects of the further development of the industrial site. Five intensive one-week seminars were conducted mainly at the Greifswald NPP site and the knowledge gained was then consolidated in two evaluation seminars at the Ignalina NPP. As the basis for the training realised in 2002 and 2003, EWN provided about 2000 power-point illustrations, more than 200 transparencies and four video films. The training handouts produced by EWN were delivered to the seminar participants in Russian and English language and documented in the database ''Technische Dokumentation Ost'' (DOKU OST) of GRS. (orig.)

  16. Application of the combined cycle LWR-gas turbine to PWR for NPP life extension, safety upgrade and improving economy

    International Nuclear Information System (INIS)

    Kuznetsov, Yu.N.; Gabaraev, B.A.

    2002-01-01

    Full text: The unconventional technology to extend the lifetime for the NPPs now in operation and make a construction of new NPPs cheaper - erection of steam-gas toppings to the nuclear power units - is considered in the paper. Application of the steam-gas toppings permits through reducing power of ageing reactors to extend lifetime of nuclear power unit, enhance its safety and at the same time to keep full load operation of NPP turbine and other balance-of-plant equipment. Proposed technology is examined for Russian VVER-440 reactor as an example and, also, as a pilot project, for Russian boiling VK-50 reactor now in operation Application of the steam-gas topping permits: extend the service life of ageing VVER-440 reactor by 10...15 years; use the turbine and other NPP balance-of-plant equipment at full power; increase the efficiency of combined cycle up to 48% and more; enhance the safety of NPP operation; utilize NPP balance-of-plant equipment after reactor decommissioning; perform the cost-effective operation in maneuvering modes; increase capacity factor of the plant. The construction of pilot project on the basis of the VK-50 reactor will allow not only to demonstrate new technology but also to attain appreciable economic effect including that obtained due to using the available reserves of the NPP turbine. (author)

  17. New trends in designing NPP control boards

    International Nuclear Information System (INIS)

    Kondrat'ev, V.V.

    1981-01-01

    A short analytical summary of the latest developments and future trends in designing NPP control boards is given. The designs of the Westinghause and the Hynkley-Point NPP control boards are described in detail. The essence of the advanced control board concept consists , firstly, in expanded use of computer-controlled displays for the sake of reducing the content of unimportant information presented to an operator, and, secondary, in better account of human possibilities to convert the NPP operation information into a more suitable form. An enlarged use of the direct digital reactor control utilizing microprocessors is expected. Besides, the employment of full-scale control board mock-ups and information desks as well as testing newly-developed control boards at computer reactor simulators are concluded to be used at all-growing rate [ru

  18. Containment Leakage Rate Testing Program in NPP Krsko

    International Nuclear Information System (INIS)

    Dudas, M.; Heruc, Z.

    2002-01-01

    NPP Krsko adopted new regulations for testing of the reactor building containment as stipulated by 10CFR50 (Code of Federal Regulation) Appendix J, Option B instead of the previous requirement 10CFR50 Appendix J now renamed to 10CFR50 Appendix J, Option A. In the USA a thorough analyses of nuclear power plants reactor building containment testing was conducted. As part of these analyses the test results obtained from testing of various reactor-building containments in the last ten years were reviewed. It was concluded that it would be meaningful to, based on test results historical data, reconsider possibility of redefining testing intervals. The official proposal of such approach was reviewed and approved by the NRC and published in September of 1995 in the FR Vol.60 No.186. Based on directions from 10CFR50 Appendix J, Option B, the new criteria for definition of test intervals were created. Criteria were based upon past performance during testing (Performance-based Requirements) and safety impact. At NPP Krsko, the analyses of the Reactor Building Containment. Integrity Test results was performed . This included test results of the Containment Integrated Leak Rate Testing (CILRT or Type A tests), Containment Isolation Valves Local Leak Rater Tests (Type C tests) and Mechanical and Electrical Penetrations Local Leak Rate tests (Type B tests). In accordance with instructions from NEI 94-01 and based on analyses of test results, NPP Krsko created Containment Leakage Rate Testing Program with the purpose to establish the performance-based definition of test intervals, inspection scope, trending and reporting. Equally, the program gives instructions how to evaluate test results and how to deal with the containment penetration or isolation valve repair contingency. All changes caused with transition from Option A to Option B are marginal to public safety. (author)

  19. Training in fundamentals of radiological coverage in Laguna Verde NPP

    International Nuclear Information System (INIS)

    Lara H, M. A.

    2014-10-01

    In 2010, the Institute of Nuclear Power Operations (INPO) celebrates the Knowledge Transfer and Retention Workshop, an event where nuclear regulators and operators presented the strategies that various NPP to worldwide were implemented to mitigate the consequences of this generational change and take advantage of it, the trend in the presented works was the same: the generational change occurs in a faster way that the transfer of knowledge, the future was already here and many NPP had not been adequately prepared to train its nuclear technicians and engineers in the tasks demanded by the industry of them, so in addition to preparing these workers to forced marches was necessary to establish strategies to retain at more experienced staff in the industry. The Laguna Verde NPP has not been exempt to this process; the preparation of personnel squares to replace those that reaching retirement age in the Comision Federal de Electricidad (CFE) has become extensive in the last five years, sometimes leading to have personnel covering functions without an alternate to the next lower position, the cause? Not enough staff. In the specific case of radiation protection (Rp) the time required for obtaining the status of Rp technician according to the ANSI/ANS 3.1 standard is 2 years, one of the tasks that most occupies part of these two years is training in radiological coverage, this training requires a mix of knowledge and experience, recently one of the concepts used for training in Rp is the evaluation and management of the radiological risk, topic that is considered in this technical work. (Author)

  20. Reactor plant for Belene NPP completion

    International Nuclear Information System (INIS)

    Dragunov, Yu. G.; Ryzhov, S. B.; Ermakov, D. N.; Repin, A. I.

    2004-01-01

    Construction of 'Belene' NPP was started at the end of 80-ties using project U-87 with V-320 reactor plant, general designer of this plant is OKB 'Gidropress'. At the beginning of 90-ties, on completing the considerable number of deliveries and performance of civil engineering work at the site the NPP construction was suspended. Nowadays, considering the state of affairs at the site and the work performed by Bulgarian Party on preservation of the equipment delivered, the most perspective is supposed to be implementation of the following versions in completing 'Belene' NPP: for completion of Unit 1 - reactor plant VVER-1000 on the basis of V-320 reactor with the maximum use of the delivered equipment (V-320M) having the extended service life and safety improvement; for Unit 2 - advanced reactor plant VVER-1000. For the upgraded reactor plant V-230M the basic solutions and characteristics are presented, as well as the calculated justification of strength and safety analyses, design of the reactor core and fuel cycle, instrumentation and control systems, application of the 'leak-before break' in the project and implementation of safety measures. For the modernised reactor plant V-392M the main characteristics and basic changes are presented, concerning reactor pressure vessel, steam generator, reactor coolant pump set. Design of NPP with the modernized reactor plant V-320M meets the up-to-date requirements and can be licensed for completion and operation. In the design of NPP with the advanced reactor plant the basic solutions and the equipment are used that are similar to those used in standard reactor plant V-320 and new one with VVER-1000 under construction and completion in Russia, and abroad. Compliance of reactor design with the up-to-date international requirements, considering the extended service life of the main equipment, shows its rather high potential for implementation during completion of 'Belene' NPP

  1. Perspectives of NPP personnel training in the future?

    International Nuclear Information System (INIS)

    Khess, R.E.

    1996-01-01

    Problems of the NPP personnel education are discussed during radical reorganization of the state regulation of energy production and distribution when nuclear energetics will appears in the market conditions. Effective methods of the NPP personnel training developed by the corporation GPU Nuclear are given. Potentials of the application of simulators and computerized programs for increasing the NPP personnel education efficiency are considered

  2. Organization of monitoring of agricultural products in NPP region

    International Nuclear Information System (INIS)

    Panteleev, L.I.; Spirin, E.V.; Sanzharova, N.I.

    1990-01-01

    Problem of organizing chemical and radiation monitoring of agricultural products in NPP region is considered. Attention is paid to monitoring during NPP siting and designing, to monitoring of radioactive contamination of agricultural products under normal NPP operation, emergency situations and decommissioning

  3. Current status of Chernobyl NPP decommissioning

    International Nuclear Information System (INIS)

    2009-01-01

    Strategy of Chernobyl NPP decommissioning with the decommissioning license 2002-2064 is presented. The main activities at the stage of ChNPP units shutdown (2002 - 2012) are: units maintenance in safe state; decommissioning infrastructure construction; unloading of SNF – main activity determining the stage duration; systems and elements final shutdown; decommissioning life-support systems reconstruction; Comprehensive engineering and radiation survey (CERS); dismantling of the reactor facilities external equipment; removal of RAW from units; decommissioning documentation development. The decommissioning activities main results are presented

  4. Radioactive waste problems in the Kozloduy NPP

    International Nuclear Information System (INIS)

    Videnov, N.; Stanchev, V.

    1995-01-01

    An average volume of 1400 m 3 a year of solid radioactive waste (RAW) is generated in the Kozloduy NPP. The adopted waste processing sequence is collection, sorting and compaction with a 1000 tons force providing decrease in volume by factor of 15. A temporary storage facility at the Kozloduy NPP is licensed by ISUAE and CPPUAE. The treatment of liquid wastes is performed by Westinghouse formula and a technology using an automated solidification system. Contaminated oils are burned using an oil incinerator. A special 2-year programme for RAW management is being developed

  5. Low-water considerations for NPP sites

    International Nuclear Information System (INIS)

    Jensen, J.; Frank, T.; Wahl, T.

    2009-01-01

    In the frame of reactor safety considerations flood protection and the evaluation of low-water events are safety relevant issues. Therefore low-water statistics were performed for the coastal region Cuxhaven and the Elbe river estuary. The consideration of the longitudinal profile of water levels during low-tide in connection with surface water effects, morphodynamic changes of the river and anthropogenic modifications is of importance for conclusions concerning the NPP sites in some distance of the reference tide gauge. The authors performed a statistical low-tide analysis for the NPP sites Brunsbuettel and Brokdorf.

  6. Knowledge management during decommissioning of Chornobyl NPP

    International Nuclear Information System (INIS)

    Gora, A.D.; Kuchinskij, V.K.; Stel'makh, D.A.; Tsivun, T.A.

    2010-01-01

    The article deals with issues on knowledge management during decommissioning by the example of the Chornobyl NPP. This includes how the duration of decommissioning stage, change in organization goal and final state of the site influence on human resources and knowledge management system. The main attention is focused on human assets and intellectual strength of Chornobyl NPP. Mathematical dependencies are proposed to substantiate numerical values. An analysis is given for the current situation, and forecast estimates for values dynamics is performed. The conclusion gives solutions on providing experienced staff in the future.

  7. Radioactive waste problems in the Kozloduy NPP

    Energy Technology Data Exchange (ETDEWEB)

    Videnov, N; Stanchev, V [Kombinat Atomna Energetika, Kozloduj (Bulgaria)

    1996-12-31

    An average volume of 1400 m{sup 3} a year of solid radioactive waste (RAW) is generated in the Kozloduy NPP. The adopted waste processing sequence is collection, sorting and compaction with a 1000 tons force providing decrease in volume by factor of 15. A temporary storage facility at the Kozloduy NPP is licensed by ISUAE and CPPUAE. The treatment of liquid wastes is performed by Westinghouse formula and a technology using an automated solidification system. Contaminated oils are burned using an oil incinerator. A special 2-year programme for RAW management is being developed.

  8. NPP Krsko small break LOCA analysis

    International Nuclear Information System (INIS)

    Mavko, B.; Petelin, S.; Peterlin, G.

    1987-01-01

    Parametric analysis of small break loss of coolant accident for the Krsko NPP was calculated by using RELAP5/MOD1 computer code. The model that was used in our calculations has been improved over several years and was previously tested in simulation (s) of start-up tests and known NPP Krsko transients. In our calculations we modelled automatic actions initiated by control, safety and protection systems. We also modelled the required operator actions as specified in emergency operating instructions. In small-break LOCA calculations, we varied break sizes in the cold leg. The influence of steam generator tube plugging on small break LOCA accidents was also analysed. (author)

  9. Remanent life management of nuclear power plants

    International Nuclear Information System (INIS)

    Pinedo, J.; Gomez Santamaria, J.

    1995-01-01

    The concept of life in the nuclear power plants is very special. The main aceptions are: design life, economic life and useful life. The good management of NPP will do the prolongation of the life in the NPP. The remanent of management life summarizes certain activities in order to prolong the lifetime of the NPP. This article presents the activities of the RML program, the technological program and its benefits

  10. Vandellos 1 NPP decommissioning feedback experience

    International Nuclear Information System (INIS)

    Fernandez, Rodriguez A.

    2003-01-01

    The Vandellos 1 Nuclear Power Plant (CNV1) is located on the Mediterranean coast in the province of Tarragona (Spain). The Plant is of the European Natural Uranium Graphite-Gas type. The thermal power of the plant amounts to 1,670 MWt, its electrical output being 500 Mwe. The Plant started-up commercial service in May 1972; its final shutdown, due to a fire in the turbines, occurred in October 1989, after 17 years of operation with an accumulated energy production of 55,647 GWh. The option of decommissioning accepted by the Ministry of Industry, consists of first removing the spent fuel and conditioning the operating radioactive wastes, and then undertaking dismantling of almost all the structures and components located outside the reactor vessel, except those ensuring confinement of the vessel itself and the safety and surveillance of the facility and site. No action will be taken with respect to the vessel, in which the reactor will remain confined without nuclear fuel and with its internal components intact until completion of the waiting (dormancy) period. The site itself will be kept under surveillance during dormancy phase, following partial clearance, the remaining installations being left within the new site perimeter in a situation of monitored confinement. Following the dormancy period, which will last some 30 years, total dismantling of the remaining installations will be undertaken, this implying subsequent complete clearance of the site. The project was started in November of 1992, and the works on site began in 1998. The safe enclosure consists only in the reactor pressure vessel, which will be left on site. The activity content of the vessel is about 100 000 Ci, mostly Co 60. Part of the Stage 2 concept is the total static isolation of this vessel. The vessel has 1 700 penetrations, the pipes of which were cut, seal-welded and inspected. After five years of works in Vandellos 1 NPP decommissioning, ENRESA has an experience and knowledge, that is

  11. Vandellos 1 NPP decommissioning feedback experience

    Energy Technology Data Exchange (ETDEWEB)

    Fernandez, Rodriguez A. [Empresa Nacional de Residuos Radioactivos, ENPRESA, Madrid (Spain)

    2003-07-01

    The Vandellos 1 Nuclear Power Plant (CNV1) is located on the Mediterranean coast in the province of Tarragona (Spain). The Plant is of the European Natural Uranium Graphite-Gas type. The thermal power of the plant amounts to 1,670 MWt, its electrical output being 500 Mwe. The Plant started-up commercial service in May 1972; its final shutdown, due to a fire in the turbines, occurred in October 1989, after 17 years of operation with an accumulated energy production of 55,647 GWh. The option of decommissioning accepted by the Ministry of Industry, consists of first removing the spent fuel and conditioning the operating radioactive wastes, and then undertaking dismantling of almost all the structures and components located outside the reactor vessel, except those ensuring confinement of the vessel itself and the safety and surveillance of the facility and site. No action will be taken with respect to the vessel, in which the reactor will remain confined without nuclear fuel and with its internal components intact until completion of the waiting (dormancy) period. The site itself will be kept under surveillance during dormancy phase, following partial clearance, the remaining installations being left within the new site perimeter in a situation of monitored confinement. Following the dormancy period, which will last some 30 years, total dismantling of the remaining installations will be undertaken, this implying subsequent complete clearance of the site. The project was started in November of 1992, and the works on site began in 1998. The safe enclosure consists only in the reactor pressure vessel, which will be left on site. The activity content of the vessel is about 100 000 Ci, mostly Co 60. Part of the Stage 2 concept is the total static isolation of this vessel. The vessel has 1 700 penetrations, the pipes of which were cut, seal-welded and inspected. After five years of works in Vandellos 1 NPP decommissioning, ENRESA has an experience and knowledge, that is

  12. Scientific management of the commissioning of the Temelin NPP

    International Nuclear Information System (INIS)

    Pazdera, F.; Vasa, I.; Svoboda, C.

    2002-01-01

    A Scientific Supervisory Group (SSG) for the commissioning of the Temelin nuclear power plant was set up by the statutory body of CEZ, a.s. (utility which holds responsibility for the start-up of the plant pursuant to Act No. 18/1997). The SSG provides support to the operator through expertise in nuclear safety assurance and nuclear power plant commissioning. Nuclear Research Institute Rez plc was appointed to this function. The article gives the definition and explains the statute of the SSG, highlights its main tasks and responsibilities, and presents the main results of activities of the SSG. The mission of the International Scientific Council for the Commissioning of the Temelin NPP is also briefly outlined. (author)

  13. Manufacturer's part in NPP personnel training in the FRG

    International Nuclear Information System (INIS)

    Martin, H.D.

    1987-01-01

    This paper describes the regulatory guidelines and the training and retraining procedures and programs for NPP personnel in the Federal Republic of Germany. Reference is also made to the three years dual workshop/factory and classroom education of skilled workers in Germany. KWU as a turnkey manufacturer of Nuclear Power Plants holds the nuclear operating license towards the authority after first fuel loading of a new plant. In this respect it has extensive overall training obligations not only towards its customers but also with regards to its own shift personnel during nuclear power operation up to commercial operation and hand over of the plant. KWU's philosophy of training, its infrastructure, its various obligations and services are described for new plants as well as with regards to retraining for older plants

  14. Operational benchmark for VVER-1000, unit 6, Kozloduy NPP

    International Nuclear Information System (INIS)

    Apostolov, T.; Petrov, B.

    1999-01-01

    Benchmark calculations have been carried out using the 3D nodal code TRAPEZ. Global neutron-physics characteristics of the VVER-1000 core, Kozloduy NPP Unit 6, have been determined taking into account the real loading patterns and operational history of the first three cycles. The code TRLOAD has been used to perform the fuel reloading between any two cycles. The reactor and components descriptions as well as material compositions are given. The results presented include the critical boric acid concentration, the radial power distribution, the axial power distribution for the maximum overload assembly, and the burnup distribution at three different moments during each cycle. Calculated values have been compared with measured data. It is shown that the results obtained by the TRAPEZ code are in good agreement with the experimental data. The information presented could serve as a test case for validation of code packages designed for analyzing the steady-state operation of VVERs. (author)

  15. Development and implementation of symptom based EOP for Mochovce NPP

    International Nuclear Information System (INIS)

    Zold, T.

    1999-01-01

    In this lecture the history and problems concerning the development and implementation of symptom based emergency operating procedures at the Mochovce NPP are reviewed. In order to increase the safety of nuclear installations and their operation at Mochovce a new programme of Safety measures has been worked out, the core of which are the safety rules administratively labeled as OP-02 introducing the symptom - oriented Emergency operating procedures. Following the selection of partners by the Slovenske Elektrarne power Company a contract was signed with US Westinghouse to work out symptom - based EOPs for the Mochovce power plant to be certified by a letter of approval by Westinghouse in November 1998. Subsequent phases of whole programme for development of EOPs were divided as follows: Phase 1 - Preparation phase; Phase 2 - Emergency operating guideline development and Phase 3 - Emergency operating procedures development and validation

  16. Nuclear power in the South Korea

    International Nuclear Information System (INIS)

    Molodtsov, S.D.

    1988-01-01

    Data on the state of nuclear power in the South Korea are presented. In the end of 1987 7 power units with 5380 MW total power were in operation in the South Korea. The share of NPP capacity was equal to 26% of the total electric power plant capacity of the country. The cost of NPP power production was equal to 2.2 cent (kw.h). The total established NPP capacity should achieve 7.3 GW by 1990, and exceed 9 GW by 2000

  17. Preferred external power supplies; Fuentes electricas preferentes exteriores

    Energy Technology Data Exchange (ETDEWEB)

    Martinez Anton, L.

    2010-07-01

    In June 2008 ANAV and ENDESA DISTRIBUCION (EDE) undertook a joint study of Asco NPP Preferred External Power Supplies (PEPSs) to check the number of lines or power supplies to the 110 kV substation at Asco that met the criteria defined in the power supply regulations applicable to Asco NPP and primarily to confirm compliance with IEEE 765-2006 standard. (Author).

  18. Application of fieldbus techniques in nuclear power plants

    International Nuclear Information System (INIS)

    Wang Xu; Chen Hang; Yu Shuxin; Zhang Xinli

    2012-01-01

    The successful application experience of fieldbus techniques in thermal power plants and nuclear power plants are outlined first. And then, the application of fieldbus techniques in domestic 3rd-generation nuclear power plant (NPP) project is discussed. After that, the solution to the potential problems of fieldbus techniques application in NPP is provided. (authors)

  19. Soundness of Krsko Nuclear Power Plant Performance in Terms of Energy and Finance

    International Nuclear Information System (INIS)

    Curkovic, A.; Vrankic, K.; Magdic, M.

    1998-01-01

    Compared to existing conventional thermal power plants in Croatian electric power system, as well as to alternative (potential) imported coal and gas fired thermal power plants, Krsko NPP (nuclear power plant) generates electricity with lower production costs. This cost margin in favour of the Krsko NPP represents the soundness of this nuclear power plant in terms of energy and finance. (author)

  20. Nuclear power plant personnel training and its evaluation. A guidebook. Executive summary

    International Nuclear Information System (INIS)

    1997-05-01

    The Guidebook will prove especially useful for, and is addressed primarily to: nuclear power operating organizations establishing or upgrading their NPP personnel training systems; regulatory personnel responsible for setting requirements and/or evaluating NPP personnel training; and organizations (within or outside the operating organization) responsible for the development, implementation and evaluation of training programmes for NPP personnel. Figs

  1. Trillo NPP full scope replica simulator project: The last great NPP simulation challenge in Spain

    International Nuclear Information System (INIS)

    Rivero, N.; Abascal, A.

    2006-01-01

    In the year 2000, Trillo NPP (Spanish PWR-KWU design nuclear power plant) and Tecnatom came to the agreement of developing a Trillo plant specific simulator, having as scope all the plant systems operated either from the main control room or from the emergency panels. The simulator operation should be carried out both through a control room replica and graphical user interface, this latter based on plant schematics and softpanels concept. Trillo simulator is to be primarily utilized as a pedagogical tool for the Trillo operational staff training. Because the engineering grade of the mathematical models, it will also have additional uses, such as: - Operation engineering (POE's validation, New Computerized Operator Support Systems Validation, etc).; - Emergency drills; -Plant design modifications assessment. This project has become the largest simulation task Tecnatom has ever undertaken, being structured in three different subprojects, namely: - Simulator manufacture, Simulator acceptance and Training material production. Most relevant technological innovations the project brings are: Highest accuracy in the Nuclear Island models, Advanced Configuration Management System, Open Software architecture, Human machine interface new design, Latest design I/O system and an Instructor Station with extended functionality. The Trillo simulator 'Ready for Training' event is due on September 2003, having started the Factory Acceptance Tests in Autumn 2002. (author)

  2. Wireless Power System Design for Mobile Robots used in Nuclear Power Plants

    Energy Technology Data Exchange (ETDEWEB)

    Choi, S. Y.; Yoo, S. J.; Lee, Kun J.; Rim, C. T. [Korea Advanced Institute of Science and Technology, Daejeon (Korea, Republic of)

    2012-05-15

    The robots used in nuclear power plants (NPP) have received much attention in recent years due to the Fukushima nuclear accident, which is considered as one of the worst nuclear disasters. In general, the NPP robots can play important roles in fuel exchange, repair work, radiation monitoring, rescue, and scouting out NPP. Under these conditions, human access to NPP during normal and emergency operations is strictly restricted due to the risks of high level radiation and contamination. However, in practice, robots have not been widely used in NPP because of the following limitations. First, the NPP robots cannot be of multi-purpose use because of their mission complexity and uniqueness. Second, the demand of the NPP robots is low due to the limited number of NPP over the world. Third, the NPP robots developed so far have no enough confidence in spite of the improvement of robot technology. Lastly, the NPP robots cannot carry on their mission continuously due to the limited energy capacity of the battery: mobile robots should stop working every two hours to recharge their batteries and spend least twenty minutes. As the solutions for this 'energy hungry' problem, high capacity batteries, quick battery chargers, power cables, and internal combustion engines were proposed; however, they still have the problems such as limited mission time and range, frequent recharging, or exhausting emission and noise. In this paper, the wireless power transfer systems (WPTS) for NPP robots are proposed. This technology can let NPP robots free from mission time and range limits, and exhausting emission. The requirements for the NPP robots are newly proposed, and two types of WPTS, roaming and railway, are suggested in this paper

  3. Wireless Power System Design for Mobile Robots used in Nuclear Power Plants

    International Nuclear Information System (INIS)

    Choi, S. Y.; Yoo, S. J.; Lee, Kun J.; Rim, C. T.

    2012-01-01

    The robots used in nuclear power plants (NPP) have received much attention in recent years due to the Fukushima nuclear accident, which is considered as one of the worst nuclear disasters. In general, the NPP robots can play important roles in fuel exchange, repair work, radiation monitoring, rescue, and scouting out NPP. Under these conditions, human access to NPP during normal and emergency operations is strictly restricted due to the risks of high level radiation and contamination. However, in practice, robots have not been widely used in NPP because of the following limitations. First, the NPP robots cannot be of multi-purpose use because of their mission complexity and uniqueness. Second, the demand of the NPP robots is low due to the limited number of NPP over the world. Third, the NPP robots developed so far have no enough confidence in spite of the improvement of robot technology. Lastly, the NPP robots cannot carry on their mission continuously due to the limited energy capacity of the battery: mobile robots should stop working every two hours to recharge their batteries and spend least twenty minutes. As the solutions for this 'energy hungry' problem, high capacity batteries, quick battery chargers, power cables, and internal combustion engines were proposed; however, they still have the problems such as limited mission time and range, frequent recharging, or exhausting emission and noise. In this paper, the wireless power transfer systems (WPTS) for NPP robots are proposed. This technology can let NPP robots free from mission time and range limits, and exhausting emission. The requirements for the NPP robots are newly proposed, and two types of WPTS, roaming and railway, are suggested in this paper

  4. Accident management insights after the Fukushima Daiichi NPP accident

    International Nuclear Information System (INIS)

    Degueldre, Didier; Viktorov, Alexandre; Tuomainen, Minna; Ducamp, Francois; Chevalier, Sophie; Guigueno, Yves; Tasset, Daniel; Heinrich, Marcus; Schneider, Matthias; Funahashi, Toshihiro; Hotta, Akitoshi; Kajimoto, Mitsuhiro; Chung, Dae-Wook; Kuriene, Laima; Kozlova, Nadezhda; Zivko, Tomi; Aleza, Santiago; Jones, John; McHale, Jack; Nieh, Ho; Pascal, Ghislain; ); Nakoski, John; Neretin, Victor; Nezuka, Takayoshi; )

    2014-01-01

    The Fukushima Daiichi nuclear power plant (NPP) accident, that took place on 11 March 2011, initiated a significant number of activities at the national and international levels to reassess the safety of existing NPPs, evaluate the sufficiency of technical means and administrative measures available for emergency response, and develop recommendations for increasing the robustness of NPPs to withstand extreme external events and beyond design basis accidents. The OECD Nuclear Energy Agency (NEA) is working closely with its member and partner countries to examine the causes of the accident and to identify lessons learnt with a view to the appropriate follow-up actions to be taken by the nuclear safety community. Accident management is a priority area of work for the NEA to address lessons being learnt from the accident at the Fukushima Daiichi NPP following the recommendations of Committee on Nuclear Regulatory Activities (CNRA), Committee on the Safety of Nuclear Installations (CSNI), and Committee on Radiation Protection and Public Health (CRPPH). Considering the importance of these issues, the CNRA authorised the formation of a task group on accident management (TGAM) in June 2012 to review the regulatory framework for accident management following the Fukushima Daiichi NPP accident. The task group was requested to assess the NEA member countries needs and challenges in light of the accident from a regulatory point of view. The general objectives of the TGAM review were to consider: - enhancements of on-site accident management procedures and guidelines based on lessons learnt from the Fukushima Daiichi NPP accident; - decision-making and guiding principles in emergency situations; - guidance for instrumentation, equipment and supplies for addressing long-term aspects of accident management; - guidance and implementation when taking extreme measures for accident management. The report is built on the existing bases for capabilities to respond to design basis

  5. External flood probabilistic safety analysis of a coastal NPP

    International Nuclear Information System (INIS)

    Pisharady, Ajai S.; Chakraborty, M.K.; Acharya, Sourav; Roshan, A.D.; Bishnoi, L.R.

    2015-01-01

    External events pose a definitive challenge to safety of NPP, solely due to their ability to induce common cause failures. Flooding incidents at Le Blayais NPP, France, Fort Calhoun NPP, USA and Fukushima Daiichi have pointed to the importance of external flooding as an important contributor to NPP risk. A methodology developed for external flood PSA of a coastal NPP vulnerable to flooding due to tsunami, cyclonic storm and intense local precipitation is presented in this paper. Different tasks for EFPSA has been identified along with general approach for completing each task

  6. Risk-informed decision making during Bohunice NPP safety upgrading

    International Nuclear Information System (INIS)

    Lipar, M.; Muzikova, E.; Kubanyi, J.

    2001-01-01

    The paper summarizes some facts of risk-informed regulation developments within UJD regulatory environment. Based on national as well as international operating experience and indications resulted from PSA, Nuclear Regulatory Authority of the Slovak Republic (UJD) since its constituting in 1993 has devoted an effort to use PSA technology to support the regulatory policy in Slovakia. The PSA is considered a complement, not a substitute, to the deterministic approach. Suchlike integrated approach is used in decision making processes and the final decision on scope and priorities is based on it. The paper outlines risk insights used in the decision making process concerning Bohunice NPP safety upgrading and focuses on the role of PSA results in Gradual Reconstruction of Bohunice VI NPP. Besides, two other examples of the PSA results application to the decision making process are provided: the assessment of proposal of modifications to the main power supply diagram (incorporation of generator switches) and the assessment of licensee request for motor generator AOT (Allowable Outage Time) extension. As an example of improving support of Bohunice V-2 risk-informed operations, concept of AOT calculations and Bohunice V-2 Risk Monitor Project are briefly described. (author)

  7. Performance indicator system with application to NPP management

    International Nuclear Information System (INIS)

    Gomez, J.; Roldan, J.

    2001-01-01

    The objective of the paper is to present the work that is being conducted in the scope of a research project between Cofrentes NPP and the polytechnic university of Valencia aimed to the development and implementation of a performance indicators system to support plant management. In developing this system, attention is being paid to the areas of safety, production and dependability. The first step in the project was the development of the performance indicator system (PIS), in order to help in assessing the effectiveness of the different activities in plant (i.e. maintenance, inspections, tests, etc.). It is suggested establishing the operational indicators set in 3 levels. The lowest level concerns indicators monitoring performance and maintenance characteristics of components. The next one involves a subset of indicators placed at system level with a similar goal. And finally, the highest level summarizes the impact of the global policy in the whole plant from safety and performance point of view. The definition of an indicator should comprise, at least, the following items: indicator's name, performance area, definition and data needed. A strategy should define what, when and how indicators have to be evaluated, analyzed and reported. This article gives an example application of the methodology at the Cofrentes NPP, collective dose as safety indicator, power production as production indicator and the number of work orders as maintenance indicator are considered and their time evolution is given. (A.C.)

  8. Environmental monitoring of the Kozloduy NPP: 20 year experience

    Energy Technology Data Exchange (ETDEWEB)

    Aleksiev, A; Tsochev, S; Dimitrov, M; Avramov, V [Kombinat Atomna Energetika, Kozloduj (Bulgaria)

    1996-12-31

    The radiation monitoring system of the Kozloduy NPP is described and the assessment of the environmental impact of the power plant is presented. Measurements are carried out in 36 control points distributed in 3 areas: radiation protected area (3 km diameter), radiation controlled area (12 km) and surveillance area (100 km). Comparison of radiation monitoring data for 1993 with data recorded in the pre-operational period (1972-74) show that no significant changes can be detected in the activity of {sup 90} Sr and gross beta activity. An increase in Cs-137 activity (38 Bq/kg d.w. versus 7 Bq/kg d.w.) is found in the soil and bottom sediments in the Danube river, which is attributed to Chernobyl accident. The Kozloduy NPP operation is continuously monitored for release of artificial radionuclides by gaseous and liquid effluents. It is reported that the average population exposure in the 30 km area due to liquid effluents is 3-4.10{sup -4} man Sv/a. A system for automated continuous radiation monitoring in 10 control stations is available in case of radiation accidents. It is supplemented by a mobile laboratory. Meteorological measurements are carried out by automatic station MC-10 and a second station is under construction. 21 refs., 2 figs., 6 tabs.

  9. Safety of NPP with WWER-440 and WWER-1000 reactors

    Energy Technology Data Exchange (ETDEWEB)

    Balabanov, E [Energoproekt, Sofia (Bulgaria); Gledachev, J; Angelov, D [Kombinat Atomna Energetika, Kozloduj (Bulgaria)

    1996-12-31

    The WWER-440 and WWER-1000 reactors used at the Kozloduy NPP have been analyzed in terms of safety. There are currently 4 reactors WWER-440/230 and 2 reactors WWER-1000/320. The former do not comply completely with the modern safety requirements due to the regulations acted in the sixties when they have been designed. The main features of these reactors are: low power density in the core; three levels of reactor control and protection; six primary loops; horizontal steam generators; two turbines; large number of cross-unit connections. The low thermal density in the core, the low specific thermal loading in the rods and the large coolant inventory enhance the safety, while the major deficiencies are identified as follows: insufficient capabilities for emergency core cooling; low diversification and physical separation of the safety systems; old fashioned control systems; inadequate fire protection; lack of full containment. It is pointed out that several design and operation actions have been completed in the Kozloduy NPP in order to enhance their safety. The WWER-1000 units are 320 model and feature a high safety level, complying completely with OPB-82 regulations and with all current international safety standards. 3 refs., 7 figs., 1 tab.

  10. Analyses for licensing of new fuel types at Paks NPP

    International Nuclear Information System (INIS)

    Kereszturi, A.; Bogatyr, S.; Miko, S.; Nemes, I.

    2003-01-01

    In the last years Paks NPP initiated several projects aiming at the introduction of new fuel types and resulting in more economic fuel cycles. The motivations, the reasons, and the economic consequences of the above modifications are detailed. The application of a new fuel type requires the renewal of the relevant chapters of the Safety Analysis Report. The fulfilment of fuel design basis requirements, to be summarised briefly also in the paper, must be investigated during normal and accidental conditions. The characteristics of the different codes, the data transfer between them are detailed. After, the cases of the Normal Operation, Anticipated Operation Occurrence, and the Postulated Accidents, judged as the most relevant ones in case of fuel modifications, are overviewed. In the last part, selected examples of the licensing calculations, performed by the above tools are presented. In conclusion, modifications of the WWER fuel, namely increased enrichment, application of burnable fuel pins, modified geometry make more economic fuel cycles (larger discharge burnup, power up-rate, reduced pressure vessel fluence) are possible. The further step (increased enrichment, burnable poison) of the fuel modernisation at NPP Paks is necessary for more economic fuel cycles and fuel consuming. A sound basis of licensing methodology, safety analysis, and necessary computer codes for the WWER fuel modernisation is available

  11. Practical experience with the fuel monitoring at Dukovany NPP

    International Nuclear Information System (INIS)

    Kment, J.; Svoboda, R.; Valach, M.

    1994-01-01

    A brief description of the following activities of Dukovany NPP is given: fuel state monitoring during cycles; fuel state inspection during outages; fuel damage predictions and reality; prevention against fuel damage caused by PCI. The fuel state monitoring during cycles is conducted by on-line gamma spectrometer located under the by-pass pipelines of the water cleaning system. The system enables to carry out determination of the equilibrium activities of practically all significant gaseous fission products for energies from 80 KeV to 2 MeV. On-line activity measurements give reliable indication of a defect origin with the 133 Xe activity level of the order of tens k Bk/l. The gamma spectroscopy data are processed by KGO and PEPA software packages installed into the chemistry information system. KGO estimates the number of the damaged fuel elements and the extent of their damage. The activities of 133 Xe, 135 Xe, 137 Xe, 138 Xe, 87 Kr, 88 Kr and 89 Kr are used for evaluation of the number of 'leakers'. PEPA code predicts radiation set-up development, i.e. the activity levels of cca 20 radiologically significant nuclides in the primary coolant for the assumed reactor power mode. The fuel damage predictions during cycles are illustrated on two examples from the operational history of the Dukovany NPP. The utilization of the KGO-PEPA software contributes to a more high exploitation culture of the core from the point of view of fuel integrity maintenance. 3 refs

  12. Commissioning of Temelin NPP as seen by scientific supervisory group

    International Nuclear Information System (INIS)

    Svoboda, C.

    2003-01-01

    Scientific Supervisory Group worked during the Temelin NPP commissioning process as an independent supervisor. The main tasks and main results of its activity are described in this contribution. The characteristic common features of commissioning process and most important events from the Scientific Supervisory Group point of view are presented. In April 1999 the Czech Power Utility with the objective to achieve maximum level of nuclear safety and quality within the NPP Temelin commissioning procedures has established a special body / Scientific Supervisory Group and requested Nuclear Research Institute Rez plc to perform the required function. The Scientific Supervisory Group proceeds in accordance with its Statute and provides an independent specialised professional and expert work focused on nuclear safety assurance, assesment of the selected documentation related to plant preparedness for the individual commissioning stages, and, of course. on assessment of the commissioning tests results. While performing its function the Scientific Supervisory Group is guided by the Atomic Act and the relevant Directives of State Office for Nuclear Safety; its activities are in compliance with the applicable IAEA recommendations (Authors)

  13. Condition Monitoring of Sensors in a NPP Using Optimized PCA

    Directory of Open Access Journals (Sweden)

    Wei Li

    2018-01-01

    Full Text Available An optimized principal component analysis (PCA framework is proposed to implement condition monitoring for sensors in a nuclear power plant (NPP in this paper. Compared with the common PCA method in previous research, the PCA method in this paper is optimized at different modeling procedures, including data preprocessing stage, modeling parameter selection stage, and fault detection and isolation stage. Then, the model’s performance is greatly improved through these optimizations. Finally, sensor measurements from a real NPP are used to train the optimized PCA model in order to guarantee the credibility and reliability of the simulation results. Meanwhile, artificial faults are sequentially imposed to sensor measurements to estimate the fault detection and isolation ability of the proposed PCA model. Simulation results show that the optimized PCA model is capable of detecting and isolating the sensors regardless of whether they exhibit major or small failures. Meanwhile, the quantitative evaluation results also indicate that better performance can be obtained in the optimized PCA method compared with the common PCA method.

  14. Environmental monitoring of the Kozloduy NPP: 20 year experience

    International Nuclear Information System (INIS)

    Aleksiev, A.; Tsochev, S.; Dimitrov, M.; Avramov, V.

    1995-01-01

    The radiation monitoring system of the Kozloduy NPP is described and the assessment of the environmental impact of the power plant is presented. Measurements are carried out in 36 control points distributed in 3 areas: radiation protected area (3 km diameter), radiation controlled area (12 km) and surveillance area (100 km). Comparison of radiation monitoring data for 1993 with data recorded in the pre-operational period (1972-74) show that no significant changes can be detected in the activity of 90 Sr and gross beta activity. An increase in Cs-137 activity (38 Bq/kg d.w. versus 7 Bq/kg d.w.) is found in the soil and bottom sediments in the Danube river, which is attributed to Chernobyl accident. The Kozloduy NPP operation is continuously monitored for release of artificial radionuclides by gaseous and liquid effluents. It is reported that the average population exposure in the 30 km area due to liquid effluents is 3-4.10 -4 man Sv/a. A system for automated continuous radiation monitoring in 10 control stations is available in case of radiation accidents. It is supplemented by a mobile laboratory. Meteorological measurements are carried out by automatic station MC-10 and a second station is under construction. 21 refs., 2 figs., 6 tabs

  15. Experience Practices on Decontamination Activity in NPP Decommissioning

    Energy Technology Data Exchange (ETDEWEB)

    Yoon, Suk Bon; Kim, Jeongju; Sohn, Wook [Korea Hydro and Nuclear Power Co., Daejeon (Korea, Republic of)

    2016-10-15

    Decommissioning of a nuclear power plant (NPP) involves various technical and administrative activities for a utility to terminate its license, which allows the plant site to be released from the regulatory control (site release). Decontamination activity in NPP decommissioning is one of the main technical activities to be performed during the decommissioning. The decontamination at decommissioning sites is usually performed due to several reasons such as reducing personnel dose and disposal costs, and cleanup to meet license termination requirements by using physical or chemical removal techniques proven through the previous experience practices. This paper introduces the best and worst practices for the decontamination activities collected from the decommissioning operational experiences through the implementation of nuclear decommissioning projects around the world. Review of the experiences of decontamination shows that it is important to conduct an advanced planning for optimized implementation of decontamination taking into considering site specific conditions such as operating time, reactor type, system, and so on. Also, a review of newer decontamination methods is necessary to safely and economically decommission the nuclear facility.

  16. Safety of NPP with WWER-440 and WWER-1000 reactors

    International Nuclear Information System (INIS)

    Balabanov, E.; Gledachev, J.; Angelov, D.

    1995-01-01

    The WWER-440 and WWER-1000 reactors used at the Kozloduy NPP have been analyzed in terms of safety. There are currently 4 reactors WWER-440/230 and 2 reactors WWER-1000/320. The former do not comply completely with the modern safety requirements due to the regulations acted in the sixties when they have been designed. The main features of these reactors are: low power density in the core; three levels of reactor control and protection; six primary loops; horizontal steam generators; two turbines; large number of cross-unit connections. The low thermal density in the core, the low specific thermal loading in the rods and the large coolant inventory enhance the safety, while the major deficiencies are identified as follows: insufficient capabilities for emergency core cooling; low diversification and physical separation of the safety systems; old fashioned control systems; inadequate fire protection; lack of full containment. It is pointed out that several design and operation actions have been completed in the Kozloduy NPP in order to enhance their safety. The WWER-1000 units are 320 model and feature a high safety level, complying completely with OPB-82 regulations and with all current international safety standards. 3 refs., 7 figs., 1 tab

  17. Identification of NPP accidents using support vector classification

    Energy Technology Data Exchange (ETDEWEB)

    Back, Ju Hyun; Yoo, Kwae Hwan; Na, Man Gyun [Chosun University, Gwangju (Korea, Republic of)

    2016-10-15

    In case of the accidents that happens in a nuclear power plants (NPPs), it is very important to identify its accidents for the operator. Therefore, in order to effectively manage the accidents, the initial short time trends of major parameters have to be observed and NPP accidents have to accurately be identified to provide its information to operators and technicians. In this regard, the objective of this study is to identify the accidents when the accidents happen in NPPs. In this study, we applied the support vector classification (SVC) model to classify the initiating events of critical accidents such as loss of coolant accidents (LOCA), total loss of feedwater (TLOFW), station blackout (SBO), and steam generator tube rupture (SGTR). Input variables were used as the initial integral value of the signal measured in the reactor coolant system (RCS), steam generator, and containment vessel after reactor trip. The proposed SVC model is verified by using the simulation data of the modular accident analysis program (MAAP4) code. In this study, the proposed SVC model is verified by using the simulation data of the modular accident analysis program (MAAP4) code. We used an initial integral value of the simulated sensor signals to identify the NPP accidents. The training data was used to train the SVC model. And, the trained model was confirmed using the test data. As a result, it was known that it can accurately classify five events.

  18. Some features of South-Ukrainian NPP information centre's interaction with mass media in post Chernobyl period

    International Nuclear Information System (INIS)

    Kiyashko, S.; Kurilchik, N.

    1995-01-01

    Using the above methods of interaction with the off-site media helped the South Ukraine NPP information centre achieve meaningful results in restoring the image of nuclear power ad making it more trustworthy. This is supported by a review of media Publications since 1989. Quantitative and qualitative modifications of the information flow to the media have yielded substantial changes of the structure of news releases about the South Ukraine NPP and nuclear power. Background information has increased from 1. 5 to 50 percent. Negative information is no longer dominating, and the Chernobyl topic is counterbalanced with diverse NucNet materials about nuclear from throughout the world. (author)

  19. NPP Mochovce - a project of extraordinay significance

    International Nuclear Information System (INIS)

    Chwolik, I.; Debru, M.

    2000-01-01

    In this paper and in this presentation the reactor safety upgrading of two blocks of the NPP V-1 Bohunice, some results of participation on safety upgrading by the German-French consortium EUCOM (Framatome and Siemens-KWU) are presented. (author)

  20. External hazards considered for Paks NPP

    International Nuclear Information System (INIS)

    Kiss, Tibor

    2000-01-01

    PAKS NPP was built according to Soviet construction standards which took into account meteorological aspects but no documents for other external hazards were available. Main activities concerning earthquakes cover reevaluation of the plant site, seismic safety technological concept, improving the seismic resistance, installation of seismic monitoring and protection system, and seismic PSA