WorldWideScience

Sample records for risk-based design procedures

  1. Risk based seismic design criteria

    International Nuclear Information System (INIS)

    Kennedy, R.P.

    1999-01-01

    In order to develop a risk based seismic design criteria the following four issues must be addressed: (1) What target annual probability of seismic induced unacceptable performance is acceptable? (2) What minimum seismic margin is acceptable? (3) Given the decisions made under Issues 1 and 2, at what annual frequency of exceedance should the safe-shutdown-earthquake (SSE) ground motion be defined? (4) What seismic design criteria should be established to reasonably achieve the seismic margin defined under Issue 2? The first issue is purely a policy decision and is not addressed in this paper. Each of the other three issues are addressed. Issues 2 and 3 are integrally tied together so that a very large number of possible combinations of responses to these two issues can be used to achieve the target goal defined under Issue 1. Section 2 lays out a combined approach to these two issues and presents three potentially attractive combined resolutions of these two issues which reasonably achieves the target goal. The remainder of the paper discusses an approach which can be used to develop seismic design criteria aimed at achieving the desired seismic margin defined in resolution of Issue 2. Suggestions for revising existing seismic design criteria to more consistently achieve the desired seismic margin are presented. (orig.)

  2. TU-FG-201-12: Designing a Risk-Based Quality Assurance Program for a Newly Implemented Y-90 Microspheres Procedure

    International Nuclear Information System (INIS)

    Vile, D; Zhang, L; Cuttino, L; Kim, S; Palta, J

    2016-01-01

    Purpose: To create a quality assurance program based upon a risk-based assessment of a newly implemented SirSpheres Y-90 procedure. Methods: A process map was created for a newly implemented SirSpheres procedure at a community hospital. The process map documented each step of this collaborative procedure, as well as the roles and responsibilities of each member. From the process map, different potential failure modes were determined as well as any current controls in place. From this list, a full failure mode and effects analysis (FMEA) was performed by grading each failure mode’s likelihood of occurrence, likelihood of detection, and potential severity. These numbers were then multiplied to compute the risk priority number (RPN) for each potential failure mode. Failure modes were then ranked based on their RPN. Additional controls were then added, with failure modes corresponding to the highest RPNs taking priority. Results: A process map was created that succinctly outlined each step in the SirSpheres procedure in its current implementation. From this, 72 potential failure modes were identified and ranked according to their associated RPN. Quality assurance controls and safety barriers were then added for failure modes associated with the highest risk being addressed first. Conclusion: A quality assurance program was created from a risk-based assessment of the SirSpheres process. Process mapping and FMEA were effective in identifying potential high-risk failure modes for this new procedure, which were prioritized for new quality assurance controls. TG 100 recommends the fault tree analysis methodology to design a comprehensive and effective QC/QM program, yet we found that by simply introducing additional safety barriers to address high RPN failure modes makes the whole process simpler and safer.

  3. TU-FG-201-12: Designing a Risk-Based Quality Assurance Program for a Newly Implemented Y-90 Microspheres Procedure

    Energy Technology Data Exchange (ETDEWEB)

    Vile, D; Zhang, L; Cuttino, L; Kim, S; Palta, J [Virginia Commonwealth University, Richmond, VA (United States)

    2016-06-15

    Purpose: To create a quality assurance program based upon a risk-based assessment of a newly implemented SirSpheres Y-90 procedure. Methods: A process map was created for a newly implemented SirSpheres procedure at a community hospital. The process map documented each step of this collaborative procedure, as well as the roles and responsibilities of each member. From the process map, different potential failure modes were determined as well as any current controls in place. From this list, a full failure mode and effects analysis (FMEA) was performed by grading each failure mode’s likelihood of occurrence, likelihood of detection, and potential severity. These numbers were then multiplied to compute the risk priority number (RPN) for each potential failure mode. Failure modes were then ranked based on their RPN. Additional controls were then added, with failure modes corresponding to the highest RPNs taking priority. Results: A process map was created that succinctly outlined each step in the SirSpheres procedure in its current implementation. From this, 72 potential failure modes were identified and ranked according to their associated RPN. Quality assurance controls and safety barriers were then added for failure modes associated with the highest risk being addressed first. Conclusion: A quality assurance program was created from a risk-based assessment of the SirSpheres process. Process mapping and FMEA were effective in identifying potential high-risk failure modes for this new procedure, which were prioritized for new quality assurance controls. TG 100 recommends the fault tree analysis methodology to design a comprehensive and effective QC/QM program, yet we found that by simply introducing additional safety barriers to address high RPN failure modes makes the whole process simpler and safer.

  4. Risk based rulemaking and design - Proceed with caution

    DEFF Research Database (Denmark)

    Zachariadis, Panos; Psaraftis, Harilaos N.; Kontovas, Christos A.

    2007-01-01

    The trend towards a risk based regulatory framework at IMO and within classification societies is expanding while some voices claim that a full ship risk based scantlings design approach can be immediately implementable. This paper attempts to clarify some widely used, but confusing to many, noti...

  5. Game Theory and Risk-Based Levee System Design

    Science.gov (United States)

    Hui, R.; Lund, J. R.; Madani, K.

    2014-12-01

    Risk-based analysis has been developed for optimal levee design for economic efficiency. Along many rivers, two levees on opposite riverbanks act as a simple levee system. Being rational and self-interested, land owners on each river bank would tend to independently optimize their levees with risk-based analysis, resulting in a Pareto-inefficient levee system design from the social planner's perspective. Game theory is applied in this study to analyze decision making process in a simple levee system in which the land owners on each river bank develop their design strategies using risk-based economic optimization. For each land owner, the annual expected total cost includes expected annual damage cost and annualized construction cost. The non-cooperative Nash equilibrium is identified and compared to the social planner's optimal distribution of flood risk and damage cost throughout the system which results in the minimum total flood cost for the system. The social planner's optimal solution is not feasible without appropriate level of compensation for the transferred flood risk to guarantee and improve conditions for all parties. Therefore, cooperative game theory is then employed to develop an economically optimal design that can be implemented in practice. By examining the game in the reversible and irreversible decision making modes, the cost of decision making myopia is calculated to underline the significance of considering the externalities and evolution path of dynamic water resource problems for optimal decision making.

  6. Designing and evaluating risk-based surveillance systems

    DEFF Research Database (Denmark)

    Willeberg, Preben; Nielsen, Liza Rosenbaum; Salman, Mo

    2012-01-01

    Risk-based surveillance systems reveal occurrence of disease or infection in a sample of population units, which are selected on the basis of risk factors for the condition under study. The purpose of such systems for supporting practical animal disease policy formulations and management decisions...... with prudent use of resources while maintaining acceptable system performance. High-risk category units are selected for testing by identification of the presence of specific high-risk factor(s), while disregarding other factors that might also influence the risk. On this basis we argue that the most...... applicable risk estimate for use in designing and evaluating a risk-based surveillance system would be a crude (unadjusted) relative risk, odds ratio or apparent prevalence. Risk estimates found in the published literature, however, are often the results of multivariable analyses implicitly adjusting...

  7. Subsea HIPPS design procedure

    International Nuclear Information System (INIS)

    Aaroe, R.; Lund, B.F.; Onshus, T.

    1995-01-01

    The paper is based on a feasibility study investigating the possibilities of using a HIPPS (High Integrity Pressure Protection System) to protect a subsea pipeline that is not rated for full wellhead shut-in pressure. The study was called the Subsea OPPS Feasibility Study, and was performed by SINTEF, Norway. Here, OPPS is an acronym for Overpressure Pipeline Protection System. A design procedure for a subsea HIPPS is described, based on the experience and knowledge gained through the ''Subsea OPPS Feasibility Study''. Before a subsea HIPPS can be applied, its technical feasibility, reliability and profitability must be demonstrated. The subsea HIPPS design procedure will help to organize and plan the design activities both with respect to development and verification of a subsea HIPPS. The paper also gives examples of how some of the discussed design steps were performed in the Subsea OPPS Feasibility Study. Finally, further work required to apply a subsea HIPPS is discussed

  8. Coal pillar design procedures

    CSIR Research Space (South Africa)

    York, G

    2000-03-01

    Full Text Available Final Project Report Coal pillar design procedures G. York, I. Canbulat, B.W. Jack Research agency: CSIR Mining Technology Project number: COL 337 Date: March 2000 2 Executive Summary Examination of collapsed pillar cases outside of the empirical... in strength occurs with increasing specimen size. 45 40 35 30 25 20 15 10 5 0 20 40 60 80 100 120 140 160 UNIAX IA L COMPR EHEN SIV E S TR ENG TH (M Pa ) CUBE SIZE (cm) Figure 1...

  9. Design Procedure for Hybrid Ventilation

    DEFF Research Database (Denmark)

    Heiselberg, Per; Tjelflaat, Per Olaf

    Mechanical and natural ventilation systems have developed separately during many years. The natural next step in this development is development of ventilation concepts that utilises and combines the best features from each system into a new type of ventilation system - Hybrid Ventilation....... Buildings with hybrid ventilation often include other sustainable technologies and an energy optimisation requires an integrated approach in the design of the building and its mechanical systems. Therefore, the hybrid ventilation design procedure differs from the design procedure for conventional HVAC....... The first ideas on a design procedure for hybrid ventilation is presented and the different types of design methods, that is needed in different phases of the design process, is discussed....

  10. Demonstration of risk-based decision analysis in remedial alternative selection and design

    International Nuclear Information System (INIS)

    Evans, E.K.; Duffield, G.M.; Massmann, J.W.; Freeze, R.A.; Stephenson, D.E.

    1993-01-01

    This study demonstrates the use of risk-based decision analysis (Massmann and Freeze 1987a, 1987b) in the selection and design of an engineering alternative for groundwater remediation at a waste site at the Savannah River Site, a US Department of Energy facility in South Carolina. The investigation focuses on the remediation and closure of the H-Area Seepage Basins, an inactive disposal site that formerly received effluent water from a nearby production facility. A previous study by Duffield et al. (1992), which used risk-based decision analysis to screen a number of ground-water remediation alternatives under consideration for this site, indicated that the most attractive remedial option is ground-water extraction by wells coupled with surface water discharge of treated effluent. The aim of the present study is to demonstrate the iterative use of risk-based decision analysis throughout the design of a particular remedial alternative. In this study, we consider the interaction between two episodes of aquifer testing over a 6-year period and the refinement of a remedial extraction well system design. Using a three-dimensional ground-water flow model, this study employs (1) geostatistics and Monte Carlo techniques to simulate hydraulic conductivity as a stochastic process and (2) Bayesian updating and conditional simulation to investigate multiple phases of aquifer testing. In our evaluation of a remedial alternative, we compute probabilistic costs associated with the failure of an alternative to completely capture a simulated contaminant plume. The results of this study demonstrate the utility of risk-based decision analysis as a tool for improving the design of a remedial alternative through the course of phased data collection at a remedial site

  11. Selecting a Risk-Based SQC Procedure for a HbA1c Total QC Plan.

    Science.gov (United States)

    Westgard, Sten A; Bayat, Hassan; Westgard, James O

    2017-09-01

    Recent US practice guidelines and laboratory regulations for quality control (QC) emphasize the development of QC plans and the application of risk management principles. The US Clinical Laboratory Improvement Amendments (CLIA) now includes an option to comply with QC regulations by developing an individualized QC plan (IQCP) based on a risk assessment of the total testing process. The Clinical and Laboratory Standards Institute (CLSI) has provided new practice guidelines for application of risk management to QC plans and statistical QC (SQC). We describe an alternative approach for developing a total QC plan (TQCP) that includes a risk-based SQC procedure. CLIA compliance is maintained by analyzing at least 2 levels of controls per day. A Sigma-Metric SQC Run Size nomogram provides a graphical tool to simplify the selection of risk-based SQC procedures. Current HbA1c method performance, as demonstrated by published method validation studies, is estimated to be 4-Sigma quality at best. Optimal SQC strategies require more QC than the CLIA minimum requirement of 2 levels per day. More complex control algorithms, more control measurements, and a bracketed mode of operation are needed to assure the intended quality of results. A total QC plan with a risk-based SQC procedure provides a simpler alternative to an individualized QC plan. A Sigma-Metric SQC Run Size nomogram provides a practical tool for selecting appropriate control rules, numbers of control measurements, and run size (or frequency of SQC). Applications demonstrate the need for continued improvement of analytical performance of HbA1c laboratory methods.

  12. Designing Flightdeck Procedures: Literature Resources

    Science.gov (United States)

    Feldman, Jolene; Barshi, Immanuel; Degani, Asaf; Loukopoulou, Loukia; Mauro, Robert

    2017-01-01

    This technical publication contains the titles, abstracts, summaries, descriptions, and/or annotations of available literature sources on procedure design and development, requirements, and guidance. It is designed to provide users with an easy access to available resources on the topic of procedure design, and with a sense of the contents of these sources. This repository of information is organized into the following publication sources: Research (e.g., journal articles, conference proceedings), Manufacturers' (e.g., operation manuals, newsletters), and Regulatory and/or Government (e.g., advisory circulars, reports). An additional section contains synopses of Accident/Incident Reports involving procedures. This work directly supports a comprehensive memorandum by Barshi, Mauro, Degani, & Loukopoulou (2016) that summarizes the results of a multi-year project, partially funded by the FAA, to develop technical reference materials that support guidance on the process of developing cockpit procedures (see "Designing Flightdeck Procedures" https://ntrs.nasa.gov/archive/nasa/casi.ntrs.nasa.gov/20160013263.pdf). An extensive treatment of this topic is presented in a forthcoming book by the same authors.

  13. Risk-based design of process plants with regard to domino effects and land use planning

    Energy Technology Data Exchange (ETDEWEB)

    Khakzad, Nima, E-mail: nkhakzad@gmail.com [Safety and Security Science Group (S3G), Faculty of Technology, Policy and Management, TU Delft, Delft (Netherlands); Reniers, Genserik [Safety and Security Science Group (S3G), Faculty of Technology, Policy and Management, TU Delft, Delft (Netherlands); Antwerp Research Group on Safety and Security (ARGoSS), Faculty of Applied Economics, Universiteit Antwerpen, Antwerp (Belgium); Research Group CEDON, Campus Brussels, KULeuven, Brussels (Belgium)

    2015-12-15

    Highlights: • A Bayesian network methodology has been developed to estimate the total probability of major accidents in chemical plants. • Total probability of accidents includes the probability of individual accidents and potential domino effects. • The methodology has been extended to calculate on-site and off-site risks. • The results of the risk analysis have been used in a multi-criteria decision analysis technique to risk-based design of chemical plants. - Abstract: Land use planning (LUP) as an effective and crucial safety measure has widely been employed by safety experts and decision makers to mitigate off-site risks posed by major accidents. Accordingly, the concept of LUP in chemical plants has traditionally been considered from two perspectives: (i) land developments around existing chemical plants considering potential off-site risks posed by major accidents and (ii) development of existing chemical plants considering nearby land developments and the level of additional off-site risks the land developments would be exposed to. However, the attempts made to design chemical plants with regard to LUP requirements have been few, most of which have neglected the role of domino effects in risk analysis of major accidents. To overcome the limitations of previous work, first, we developed a Bayesian network methodology to calculate both on-site and off-site risks of major accidents while taking domino effects into account. Second, we combined the results of risk analysis with Analytic Hierarchical Process to design an optimal layout for which the levels of on-site and off-site risks would be minimum.

  14. Six Sigma Quality Management System and Design of Risk-based Statistical Quality Control.

    Science.gov (United States)

    Westgard, James O; Westgard, Sten A

    2017-03-01

    Six sigma concepts provide a quality management system (QMS) with many useful tools for managing quality in medical laboratories. This Six Sigma QMS is driven by the quality required for the intended use of a test. The most useful form for this quality requirement is the allowable total error. Calculation of a sigma-metric provides the best predictor of risk for an analytical examination process, as well as a design parameter for selecting the statistical quality control (SQC) procedure necessary to detect medically important errors. Simple point estimates of sigma at medical decision concentrations are sufficient for laboratory applications. Copyright © 2016 Elsevier Inc. All rights reserved.

  15. Risk-based Process Development of Biosimilars as Part of the Quality by Design Paradigm.

    Science.gov (United States)

    Zalai, Dénes; Dietzsch, Christian; Herwig, Christoph

    2013-01-01

    In the last few years, several quality by design (QbD) studies demonstrated the benefit of systematic approaches for biopharmaceutical development. However, only very few studies identified biosimilars as a special case of product development. The targeted quality profile of biosimilars is strictly defined by the originator's product characteristic. Moreover, the major source of prior knowledge is the experience with the originator product itself. Processing this information in biosimilar development has a major effect on risk management and process development strategies. The main objective of this contribution is to demonstrate how risk management can facilitate the implementation of QbD in early-stage product development with special emphasis on fitting the reported approaches to biosimilars. Risk assessments were highlighted as important tools to integrate prior knowledge in biosimilar development. The risk assessment process as suggested by the International Conference on Harmonization (ICH Q9) was reviewed and three elements were identified to play a key role in targeted risk assessment approaches: proper understanding of target linkage, risk assessment tool compliance, and criticality threshold value. Adjusting these steps to biosimilar applications helped to address some unique challenges of these products such as a strictly defined quality profile or a lack of process knowledge. This contribution demonstrates the need for tailored risk management approaches for the risk-based development of biosimilars and provides novel tools for the integration of additional knowledge available for these products. The pharmaceutical industry is facing challenges such as profit loss and price competition. Companies are forced to rationalize business models and to cut costs in development as well as manufacturing. These trends recently hinder the implementation of any concepts that do not offer certain financial benefit or promise a long return of investment. Quality by

  16. Rational risk-based decision support for drinking water well managers by optimized monitoring designs

    Science.gov (United States)

    Enzenhöfer, R.; Geiges, A.; Nowak, W.

    2011-12-01

    Advection-based well-head protection zones are commonly used to manage the contamination risk of drinking water wells. Considering the insufficient knowledge about hazards and transport properties within the catchment, current Water Safety Plans recommend that catchment managers and stakeholders know, control and monitor all possible hazards within the catchments and perform rational risk-based decisions. Our goal is to supply catchment managers with the required probabilistic risk information, and to generate tools that allow for optimal and rational allocation of resources between improved monitoring versus extended safety margins and risk mitigation measures. To support risk managers with the indispensable information, we address the epistemic uncertainty of advective-dispersive solute transport and well vulnerability (Enzenhoefer et al., 2011) within a stochastic simulation framework. Our framework can separate between uncertainty of contaminant location and actual dilution of peak concentrations by resolving heterogeneity with high-resolution Monte-Carlo simulation. To keep computational costs low, we solve the reverse temporal moment transport equation. Only in post-processing, we recover the time-dependent solute breakthrough curves and the deduced well vulnerability criteria from temporal moments by non-linear optimization. Our first step towards optimal risk management is optimal positioning of sampling locations and optimal choice of data types to reduce best the epistemic prediction uncertainty for well-head delineation, using the cross-bred Likelihood Uncertainty Estimator (CLUE, Leube et al., 2011) for optimal sampling design. Better monitoring leads to more reliable and realistic protection zones and thus helps catchment managers to better justify smaller, yet conservative safety margins. In order to allow an optimal choice in sampling strategies, we compare the trade-off in monitoring versus the delineation costs by accounting for ill

  17. Implementation procedures for design certification

    International Nuclear Information System (INIS)

    Ritterbusch, S. E.; Brinkman, C. B.; Crump, M. W.

    1995-01-01

    The desire for safer plants arose primarily as the result of the Three Mile Island accident and the realization that plant safety could be impacted by complex plant systems interactions that are not easily identified through the traditional 'system-by-system' design process. Hence, it became apparent that the ALWR designs would have to be addressed through plant-wide Probabilistic Safety Assessments (PSAs) that addressed both accident-prevention and accident-mitigation design features. Prior to Design Certification the 'two-step' licensing process in the United States was not efficient. Utilities had to commit large amounts of capital to plant construction without confidence that an operating license would be issued when construction permit was issued often required design changes that resulted in significant construction delays. The 55 utilities operating nuclear plants in the U. S. each had their own design and operating preferences, resulting in many customized plants with a minimum of economic benefit from standardization. This was addressed by the U. S. Nuclear Regulatory Commission (NRC) in a new regulation (Title 10 of the Code of Federal Regulations, Part 52 or '10 CFR 52') which provides certification of a design that can later be referenced by an applicant for a Combined Operating License (COL). Identifying an ALWR solution for previously unanalyzed severe accident scenarios appeared difficult, at best, since severe accident research had to be performed and since there was no regulatory precedent. This meant that complex technical issues and licensing review policies had to be developed without the benefit of licensing standards or experience. As a result, a system of iterative interactions between the regulator and the industry was established, wherein a design or safety requirement would be proposed, then discussed along with development of the corresponding design feature, and finally revised and documented via NRC 'guidance'

  18. Listening Comprehension: Approach, Design, Procedure.

    Science.gov (United States)

    Richards, Jack C.

    1983-01-01

    Three dimensions in the teaching of listening comprehension are outlined: (1) a theory is presented that takes account of the cognitive processes used (approach); (2) listeners' needs are analyzed and a taxonomy of microskills and objectives for teaching them are proposed (design); and (3) classroom exercises and activities are suggested…

  19. Phenomenological Research Method, Design and Procedure: A ...

    African Journals Online (AJOL)

    Phenomenological Research Method, Design and Procedure: A Phenomenological Investigation of the Phenomenon of Being-in-Community as Experienced by Two Individuals Who Have Participated in a Community Building Workshop.

  20. Reassessment of coal pillar design procedure

    CSIR Research Space (South Africa)

    Madden, BJ

    1995-12-01

    Full Text Available The SIMRAC project COL 021A entitled “a reassessment of coal pillar design procedures” set out to achieve a coal pillar design procedure that takes cognisance of different geological and structural factors as well as the influence...

  1. Risk based modelling

    International Nuclear Information System (INIS)

    Chapman, O.J.V.; Baker, A.E.

    1993-01-01

    Risk based analysis is a tool becoming available to both engineers and managers to aid decision making concerning plant matters such as In-Service Inspection (ISI). In order to develop a risk based method, some form of Structural Reliability Risk Assessment (SRRA) needs to be performed to provide a probability of failure ranking for all sites around the plant. A Probabilistic Risk Assessment (PRA) can then be carried out to combine these possible events with the capability of plant safety systems and procedures, to establish the consequences of failure for the sites. In this way the probability of failures are converted into a risk based ranking which can be used to assist the process of deciding which sites should be included in an ISI programme. This paper reviews the technique and typical results of a risk based ranking assessment carried out for nuclear power plant pipework. (author)

  2. Probabilistic Modeling of Seismic Risk Based Design for a Dual System Structure

    OpenAIRE

    Sidi, Indra Djati

    2017-01-01

    The dual system structure concept has gained popularity in the construction of high-rise buildings over the last decades. Meanwhile, earthquake engineering design provisions for buildings have moved from the uniform hazard concept to the uniform risk concept upon recognizing the uncertainties involved in the earthquake resistance of concrete structures. In this study, a probabilistic model for the evaluation of such risk is proposed for a dual system structure consisting of shear walls or cor...

  3. Risk-based design of process systems using discrete-time Bayesian networks

    International Nuclear Information System (INIS)

    Khakzad, Nima; Khan, Faisal; Amyotte, Paul

    2013-01-01

    Temporal Bayesian networks have gained popularity as a robust technique to model dynamic systems in which the components' sequential dependency, as well as their functional dependency, cannot be ignored. In this regard, discrete-time Bayesian networks have been proposed as a viable alternative to solve dynamic fault trees without resort to Markov chains. This approach overcomes the drawbacks of Markov chains such as the state-space explosion and the error-prone conversion procedure from dynamic fault tree. It also benefits from the inherent advantages of Bayesian networks such as probability updating. However, effective mapping of the dynamic gates of dynamic fault trees into Bayesian networks while avoiding the consequent huge multi-dimensional probability tables has always been a matter of concern. In this paper, a new general formalism has been developed to model two important elements of dynamic fault tree, i.e., cold spare gate and sequential enforcing gate, with any arbitrary probability distribution functions. Also, an innovative Neutral Dependency algorithm has been introduced to model dynamic gates such as priority-AND gate, thus reducing the dimension of conditional probability tables by an order of magnitude. The second part of the paper is devoted to the application of discrete-time Bayesian networks in the risk assessment and safety analysis of complex process systems. It has been shown how dynamic techniques can effectively be applied for optimal allocation of safety systems to obtain maximum risk reduction.

  4. A completely new design and regulatory process - A risk-based approach for new nuclear power plants. Annex 17

    International Nuclear Information System (INIS)

    Ritterbusch, S.E.

    2002-01-01

    In the de-regulated electric power market place that is developing in the USA, competition from alternative electric power sources has provided significant downward pressure on the costs of new construction projects. Studies by the Electric Power Research Institute have shown that, in the USA, the capital cost of new nuclear plants must be decreased by at least 35% to 40% relative to the cost of Advanced Light Water Reactors designed in the early 1990s in order to be competitive with capital costs of gas-fired electric power plants. The underlying reasons for the high capital costs estimated for some nuclear plants are (1) long construction times, (2) the high level of 'defense-in-depth' or safety margin, included throughout the design and licensing process, and (3) the use of out-dated design methods and information. Probabilistic Safety Assessments are being used to develop a more accurate assessment of real plant risk and to provide relief if it can be demonstrated that plant equipment is not providing a significant contribution to plant safety. Westinghouse addressed some of these cost drivers in the development of the AP-600 passive plant design. However, because of relatively inexpensive natural gas plant alternative, we need to reduce the costs even further. Therefore, the AP-600 design is now being up-rated to a 1000 MWe design, AP-1000. The development of AP1000 is described in another paper being presented at this meeting. Westinghouse is also managing a project, sponsored by the US Department of Energy, which is aimed at developing an all-new 'risk-based' approach to design and regulation. Methodologies being developed use risk-based information to the extent practical and 'defense-in-depth' only when necessary to address uncertainties in models and equipment performance. Early results, summarized in this paper, include (1) the initial framework for a new design and regulatory process and (2) a sample design analysis which shows that the Emergency Core

  5. Risk-based design of process plants with regard to domino effects and land use planning.

    Science.gov (United States)

    Khakzad, Nima; Reniers, Genserik

    2015-12-15

    Land use planning (LUP) as an effective and crucial safety measure has widely been employed by safety experts and decision makers to mitigate off-site risks posed by major accidents. Accordingly, the concept of LUP in chemical plants has traditionally been considered from two perspectives: (i) land developments around existing chemical plants considering potential off-site risks posed by major accidents and (ii) development of existing chemical plants considering nearby land developments and the level of additional off-site risks the land developments would be exposed to. However, the attempts made to design chemical plants with regard to LUP requirements have been few, most of which have neglected the role of domino effects in risk analysis of major accidents. To overcome the limitations of previous work, first, we developed a Bayesian network methodology to calculate both on-site and off-site risks of major accidents while taking domino effects into account. Second, we combined the results of risk analysis with Analytic Hierarchical Process to design an optimal layout for which the levels of on-site and off-site risks would be minimum. Copyright © 2015 Elsevier B.V. All rights reserved.

  6. Chipless RFID design procedure and detection techniques

    CERN Document Server

    Rezaiesarlak, Reza

    2015-01-01

    This book examines the design of chipless RFID systems. The authors begin with the historical development of wireless identification systems and finally arrive at a representation of the chipless RFID system as a block diagram illustration. Chapter 2 is devoted to the theoretical bases for the design of chipless RFID tags and detection techniques in the reader. A rigorous mathematical formulation is presented based on the singularity expansion method (SEM) and characteristic mode theory (CMT) in order to study the scattered fields from an object in a general form. Th e authors attempt to explain some physical concepts behind the mathematical descriptions of the theories in this chapter. In Chapter 3, two design procedures based on complex natural resonance and CMT are presented for the design of the chipless RFID tag. By studying the effects of structural parameters on radiation and resonant behaviors of the tag, some design conclusions are presented in this chapter. Chapter 4 is dedicated to the time-frequen...

  7. Energy conservation aircraft design and operational procedures

    Energy Technology Data Exchange (ETDEWEB)

    Poisson-Quinton, P.

    1978-01-01

    The paper reviews studies associated with improved fuel efficiency. Several aircraft design concepts are described including: (1) increases in aerodynamic efficiency through decreased friction drag, parasitic drag, and drag due to lift, (2) structural efficiency and the implementation of composite materials, (3) active control technology, (4) the optimization of airframe-engine integration, and (5) VTOL and STOL concepts. Consideration is also given to operational procedures associated with flight management, terminal-area operations, and the influence of environmental noise constraints on fuel economy.

  8. Procedural Design of Exterior Lighting for Buildings with Complex Constraints

    KAUST Repository

    Schwarz, Michael; Wonka, Peter

    2014-01-01

    We present a system for the lighting design of procedurally modeled buildings. The design is procedurally specified as part of the ordinary modeling workflow by defining goals for the illumination that should be attained and locations where

  9. Acceptance and Divergence from Engineering Design Procedures Implicating Knowledge Flow

    DEFF Research Database (Denmark)

    Jensen, Ole Kjeldal; Ahmed, Saeema

    2009-01-01

    of explicit procedures and; 3) implicit procedures supporting needs that are not catered for by the explicit procedures. In this understanding, a procedure can be any kind of method, tool or framework used to support design engineers. Furthermore, the study discusses a variety of recommended actions......When developing procedures such as tools, methods and frameworks to support the development of new products, one of the challenges is ensuring their successful implementation. This paper describes a study of the development and use of such design-procedures with primary focus on the new product...

  10. Mixture design procedure for flexible base.

    Science.gov (United States)

    2013-04-01

    This document provides information on mixture design requirements for a flexible base course. Sections : design requirements, job mix formula, contractor's responsibility, and engineer's responsibility. Tables : material requirements; requirements fo...

  11. FFTF fuel pin design procedure verification for transient operation

    International Nuclear Information System (INIS)

    Baars, R.E.

    1975-05-01

    The FFTF design procedures for evaluating fuel pin transient performance are briefly reviewed, and data where available are compared with design procedure predictions. Specifically, burst conditions derived from Fuel Cladding Transient Tester (FCTT) tests and from ANL loss-of-flow tests are compared with burst pressures computed using the design procedure upon which the cladding integrity limit was based. Failure times are predicted using the design procedure for evaluation of rapid reactivity insertion accidents, for five unterminated TREAT experiments in which well characterized fuel failures were deliberately incurred. (U.S.)

  12. Statistical design of mass spectrometry calibration procedures

    International Nuclear Information System (INIS)

    Bayne, C.K.

    1996-11-01

    The main objective of this task was to agree on calibration procedures to estimate the system parameters (i.e., dead-time correction, ion-counting conversion efficiency, and detector efficiency factors) for SAL's new Finnigan MAT-262 mass spectrometer. SAL will use this mass spectrometer in a clean-laboratory which was opened in December 1995 to measure uranium and plutonium isotopes on environmental samples. The Finnigan MAT-262 mass spectrometer has a multi-detector system with seven Faraday cup detectors and one ion- counter for the measurement of very small signals (e.g. 10 -17 Ampere range). ORNL has made preliminary estimates of the system parameters based on SAL's experimental data measured in late 1994 when the Finnigan instrument was relatively new. SAL generated additional data in 1995 to verify the calibration procedures for estimating the dead-time correction factor, the ion-counting conversion factor and the Faraday cup detector efficiency factors. The system parameters estimated on the present data will have to be reestablished when the Finnigan MAT-262 is moved-to the new clean- laboratory. Different methods will be used to analyzed environmental samples than the current measurement methods being used. For example, the environmental samples will be electroplated on a single filament rather than using the current two filament system. An outline of the calibration standard operating procedure (SOP) is included

  13. 40 CFR 240.202-2 - Recommended procedures: Design.

    Science.gov (United States)

    2010-07-01

    ... 40 Protection of Environment 24 2010-07-01 2010-07-01 false Recommended procedures: Design. 240... § 240.202-2 Recommended procedures: Design. (a) Whenever possible, thermal processing facilities should be located in areas zoned for industrial use and having adequate utilities to serve the facility. (b...

  14. Design Transformations for Rule-based Procedural Modeling

    KAUST Repository

    Lienhard, Stefan; Lau, Cheryl; Mü ller, Pascal; Wonka, Peter; Pauly, Mark

    2017-01-01

    We introduce design transformations for rule-based procedural models, e.g., for buildings and plants. Given two or more procedural designs, each specified by a grammar, a design transformation combines elements of the existing designs to generate new designs. We introduce two technical components to enable design transformations. First, we extend the concept of discrete rule switching to rule merging, leading to a very large shape space for combining procedural models. Second, we propose an algorithm to jointly derive two or more grammars, called grammar co-derivation. We demonstrate two applications of our work: we show that our framework leads to a larger variety of models than previous work, and we show fine-grained transformation sequences between two procedural models.

  15. Design Transformations for Rule-based Procedural Modeling

    KAUST Repository

    Lienhard, Stefan

    2017-05-24

    We introduce design transformations for rule-based procedural models, e.g., for buildings and plants. Given two or more procedural designs, each specified by a grammar, a design transformation combines elements of the existing designs to generate new designs. We introduce two technical components to enable design transformations. First, we extend the concept of discrete rule switching to rule merging, leading to a very large shape space for combining procedural models. Second, we propose an algorithm to jointly derive two or more grammars, called grammar co-derivation. We demonstrate two applications of our work: we show that our framework leads to a larger variety of models than previous work, and we show fine-grained transformation sequences between two procedural models.

  16. Risk-based determination of design pressure of LNG fuel storage tanks based on dynamic process simulation combined with Monte Carlo method

    International Nuclear Information System (INIS)

    Noh, Yeelyong; Chang, Kwangpil; Seo, Yutaek; Chang, Daejun

    2014-01-01

    This study proposes a new methodology that combines dynamic process simulation (DPS) and Monte Carlo simulation (MCS) to determine the design pressure of fuel storage tanks on LNG-fueled ships. Because the pressure of such tanks varies with time, DPS is employed to predict the pressure profile. Though equipment failure and subsequent repair affect transient pressure development, it is difficult to implement these features directly in the process simulation due to the randomness of the failure. To predict the pressure behavior realistically, MCS is combined with DPS. In MCS, discrete events are generated to create a lifetime scenario for a system. The combination of MCS with long-term DPS reveals the frequency of the exceedance pressure. The exceedance curve of the pressure provides risk-based information for determining the design pressure based on risk acceptance criteria, which may vary with different points of view. - Highlights: • The realistic operation scenario of the LNG FGS system is estimated by MCS. • In repeated MCS trials, the availability of the FGS system is evaluated. • The realistic pressure profile is obtained by the proposed methodology. • The exceedance curve provides risk-based information for determining design pressure

  17. Factors affecting the design of instrument flight procedures

    Directory of Open Access Journals (Sweden)

    Ivan FERENCZ

    2008-01-01

    Full Text Available The article highlights factors, which might affect the design of instrument flight procedures. Ishikawa diagram is used to distribute individual factors into classes, as are People, Methods, Regulations, Tools, Data and Environment.

  18. Development of an Overlay Design Procedure for Composite Pavements

    Science.gov (United States)

    2017-09-01

    The composite overlay design procedure currently used by ODOT sometimes produces very large overlay thicknesses that are deemed structurally unnecessary, especially for composite pavements already with thick asphalt overlays. This study was initiated...

  19. Application of Bayesian network and multi-criteria decision analysis to risk-based design of chemical plants

    NARCIS (Netherlands)

    Khakzad Rostami, N.; Reniers, G.L.L.M.E.

    2016-01-01

    Fires and explosions in chemical plants are still among the major accidents threatening human lives and causing huge asset losses. Although might not completely be eliminated, the risks of such accidents can be reduced by allocating safety measures, applying inherently safer design (ISD) methods,

  20. Automatic control design procedures for restructurable aircraft control

    Science.gov (United States)

    Looze, D. P.; Krolewski, S.; Weiss, J.; Barrett, N.; Eterno, J.

    1985-01-01

    A simple, reliable automatic redesign procedure for restructurable control is discussed. This procedure is based on Linear Quadratic (LQ) design methodologies. It employs a robust control system design for the unfailed aircraft to minimize the effects of failed surfaces and to extend the time available for restructuring the Flight Control System. The procedure uses the LQ design parameters for the unfailed system as a basis for choosing the design parameters of the failed system. This philosophy alloys the engineering trade-offs that were present in the nominal design to the inherited by the restructurable design. In particular, it alloys bandwidth limitations and performance trade-offs to be incorporated in the redesigned system. The procedure also has several other desirable features. It effectively redistributes authority among the available control effectors to maximize the system performance subject to actuator limitations and constraints. It provides a graceful performance degradation as the amount of control authority lessens. When given the parameters of the unfailed aircraft, the automatic redesign procedure reproduces the nominal control system design.

  1. Expressive Design Tools: Procedural Content Generation for Game Designers

    OpenAIRE

    Smith, Gillian Margaret

    2012-01-01

    Games are shaped by the tools we use to make them and our ability to model the concepts they address. Vast improvements in computer graphics technology, processing power, storage capacity, and physics simulations have driven game design for the past forty years, leading to beautiful, spacious, detailed, and highly immersive worlds supporting games that are, for the most part, fundamentally about movement, collision, and other physics-based concepts. Designers use increasingly complex tools th...

  2. Groundwater contamination from waste management sites: The interaction between risk-based engineering design and regulatory policy: 1. Methodology

    Science.gov (United States)

    Massmann, Joel; Freeze, R. Allan

    1987-02-01

    This paper puts in place a risk-cost-benefit analysis for waste management facilities that explicitly recognizes the adversarial relationship that exists in a regulated market economy between the owner/operator of a waste management facility and the government regulatory agency under whose terms the facility must be licensed. The risk-cost-benefit analysis is set up from the perspective of the owner/operator. It can be used directly by the owner/operator to assess alternative design strategies. It can also be used by the regulatory agency to assess alternative regulatory policy, but only in an indirect manner, by examining the response of an owner/operator to the stimuli of various policies. The objective function is couched in terms of a discounted stream of benefits, costs, and risks over an engineering time horizon. Benefits are in the form of revenues for services provided; costs are those of construction and operation of the facility. Risk is defined as the cost associated with the probability of failure, with failure defined as the occurrence of a groundwater contamination event that violates the licensing requirements established for the facility. Failure requires a breach of the containment structure and contaminant migration through the hydrogeological environment to a compliance surface. The probability of failure can be estimated on the basis of reliability theory for the breach of containment and with a Monte-Carlo finite-element simulation for the advective contaminant transport. In the hydrogeological environment the hydraulic conductivity values are defined stochastically. The probability of failure is reduced by the presence of a monitoring network operated by the owner/operator and located between the source and the regulatory compliance surface. The level of reduction in the probability of failure depends on the probability of detection of the monitoring network, which can be calculated from the stochastic contaminant transport simulations. While

  3. Model checking as an aid to procedure design

    International Nuclear Information System (INIS)

    Zhang, Wenhu

    2001-01-01

    The OECD Halden Reactor Project has been actively working on computer assisted operating procedures for many years. The objective of the research has been to provide computerised assistance for procedure design, verification and validation, implementation and maintenance. For the verification purpose, the application of formal methods has been considered in several reports. The recent formal verification activity conducted at the Halden Project is based on using model checking to the verification of procedures. This report presents verification approaches based on different model checking techniques and tools for the formalization and verification of operating procedures. Possible problems and relative merits of the different approaches are discussed. A case study of one of the approaches is presented to show the practical application of formal verification. Application of formal verification in the traditional procedure design process can reduce the human resources involved in reviews and simulations, and hence reduce the cost of verification and validation. A discussion of the integration of the formal verification with the traditional procedure design process is given at the end of this report. (Author)

  4. Design Guidance for Computer-Based Procedures for Field Workers

    Energy Technology Data Exchange (ETDEWEB)

    Oxstrand, Johanna [Idaho National Lab. (INL), Idaho Falls, ID (United States); Le Blanc, Katya [Idaho National Lab. (INL), Idaho Falls, ID (United States); Bly, Aaron [Idaho National Lab. (INL), Idaho Falls, ID (United States)

    2016-09-01

    Nearly all activities that involve human interaction with nuclear power plant systems are guided by procedures, instructions, or checklists. Paper-based procedures (PBPs) currently used by most utilities have a demonstrated history of ensuring safety; however, improving procedure use could yield significant savings in increased efficiency, as well as improved safety through human performance gains. The nuclear industry is constantly trying to find ways to decrease human error rates, especially human error rates associated with procedure use. As a step toward the goal of improving field workers’ procedure use and adherence and hence improve human performance and overall system reliability, the U.S. Department of Energy Light Water Reactor Sustainability (LWRS) Program researchers, together with the nuclear industry, have been investigating the possibility and feasibility of replacing current paper-based procedures with computer-based procedures (CBPs). PBPs have ensured safe operation of plants for decades, but limitations in paper-based systems do not allow them to reach the full potential for procedures to prevent human errors. The environment in a nuclear power plant is constantly changing, depending on current plant status and operating mode. PBPs, which are static by nature, are being applied to a constantly changing context. This constraint often results in PBPs that are written in a manner that is intended to cover many potential operating scenarios. Hence, the procedure layout forces the operator to search through a large amount of irrelevant information to locate the pieces of information relevant for the task and situation at hand, which has potential consequences of taking up valuable time when operators must be responding to the situation, and potentially leading operators down an incorrect response path. Other challenges related to use of PBPs are management of multiple procedures, place-keeping, finding the correct procedure for a task, and relying

  5. The design of operating procedures manuals for nuclear power plants

    International Nuclear Information System (INIS)

    Bohr, E.; Preuss, W.; Reinartz, G.; Thau, G.

    1977-03-01

    This report describes the findings of a research on the desirable design of operating procedures manuals for nuclear power plants. The work was supported by a grant of the Federal Department of the Interior. Information was acquired from different sources. Interviews and discussions on manual design were carried out with manual users in nuclear power plants. Moreover, tasks carried out using procedures were either observed or, alternatively, the manner of using procedures was elicited by interviews. In addition, manual writers, managers from manufacturers and utilities, nuclear experts, and individuals involved in manual specification activities were interviewed. A major source of information has been the pertinent scientific and technical findings scattered in the literature on topics such as instructional technology, engineering psychology, psycholinguistics, and typography. A comprehensive bibliography is included. General rules are established on designing instructional material for use on the job, aiming at increasing their legability, comprehensibility, and suitability to guide human performance. The application of these rules to the design of individual operating procedures is demonstrated. Recommendations are given on the design, layout, development and implementation of manuals. (orig.) [de

  6. Emergency procedures beyond design basis ''Feed and Bleed''

    International Nuclear Information System (INIS)

    Dominguez Bautista, M.T.; Campuzano Pena, F.

    1994-01-01

    The incorporation of Beyond-Design-Basis Emergency Procedures, also called the Emergency Manual or Severe Accident Manual, has been an important step forward in nuclear power plant safety. These procedures cover situations in which the deterministic criteria used in plant design have been contravened. In such situations new accident scenarios, unforeseen system actions or a combination of both, need to be considered. Establishing these procedures is actually the last in a sequence of activities the sequence includes definition of scenarios, study of their phenomena, analysis of optional system actions, verification of their effectiveness and finally, implementation of the procedure. The systematization of these new strategies is supported by the results of the probabilistic analyses which serve in this case to pinpoint the objectives of these strategies. This paper describes the application of this methodology in the definition of a procedure for heat sink recovery on the secondary side (feed and bleed) if this has been totally or partially lost in a beyond-design-basis event. (Author)

  7. Design Procedure on Stud Bolt for Reactor Vessel Assembly

    International Nuclear Information System (INIS)

    Kim, Jong-Wook; Lee, Gyu-Mahn; Jeoung, Kyeong-Hoon; Kim, Tae-Wan; Park, Keun-Bae; Kim, Keung-Koo

    2008-10-01

    The reactor pressure vessel flange is welded to the upper part of reactor pressure vessel, and there are stud holes to mount the closure head with stud bolts. The surface mating the closure head is compressed with O-ring, which acts as a sealing gasket to prevent coolant leakage. Bolted flange connections perform a very important structural role in the design of a reactor pressure vessel. Their importance stems from two important functions: (a) maintenance of the structural integrity of the connection itself, and (b) prevention of leakage through the O-ring preloaded by stud bolts. In the present study, an evaluation procedure for the design of stud bolt is developed to meet ASME code requirements. The developed design procedure could provide typical references in the development of advanced reactor design in the future

  8. 40 CFR 240.205-2 - Recommended procedures: Design.

    Science.gov (United States)

    2010-07-01

    ... air pollution control technology. (b) All emissions, including dust from vents, should be controlled. ... 40 Protection of Environment 24 2010-07-01 2010-07-01 false Recommended procedures: Design. 240.205-2 Section 240.205-2 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) SOLID...

  9. A Survey study on design procedure of Seismic Base Isolation ...

    African Journals Online (AJOL)

    Adding shear walls or braced frames can decrease the potential damage caused by earthquakes.We can isolate the structures from the ground using the Seismic Base Isolation Systems that is flexible approach to decrease the potential damage. In this research we present information on the design procedure of seismic ...

  10. Novel design of honeybee-inspired needles for percutaneous procedure.

    Science.gov (United States)

    Sahlabadi, Mohammad; Hutapea, Parsaoran

    2018-04-18

    The focus of this paper is to present new designs of innovative bioinspired needles to be used during percutaneous procedures. Insect stingers have been known to easily penetrate soft tissues. Bioinspired needles mimicking the barbs in a honeybee stinger were developed for a smaller insertion force, which can provide a less invasive procedure. Decreasing the insertion force will decrease the tissue deformation, which is essential for more accurate targeting. In this study, some design parameters, in particular, barb shape and geometry (i.e. front angle, back angle, and height) were defined, and their effects on the insertion force were investigated. Three-dimensional printing technology was used to manufacture bioinspired needles. A specially-designed insertion test setup using tissue mimicking polyvinyl chloride (PVC) gels was developed to measure the insertion and extraction forces. The barb design parameters were then experimentally modified through detailed experimental procedures to further reduce the insertion force. Different scales of the barbed needles were designed and used to explore the size-scale effect on the insertion force. To further investigate the efficacy of the proposed needle design in real surgeries, preliminary ex vivo insertion tests into bovine liver tissue were performed. Our results show that the insertion force of the needles in different scales decreased by 21-35% in PVC gel insertion tests, and by 46% in bovine liver tissue insertion tests.

  11. PGSFR Core Thermal Design Procedure to Evaluate the Safety Margin

    Energy Technology Data Exchange (ETDEWEB)

    Choi, Sun Rock; Kim, Sang-Ji [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2014-10-15

    The Korea Atomic Energy Research Institute (KAERI) has performed a SFR design with the final goal of constructing a prototype plant by 2028. The main objective of the SFR prototype plant is to verify the TRU metal fuel performance, reactor operation, and transmutation ability of high-level wastes. The core thermal design is to ensure the safe fuel performance during the whole plant operation. Compared to the critical heat flux in typical light water reactors, nuclear fuel damage in SFR subassemblies arises from a creep induced failure. The creep limit is evaluated based on the maximum cladding temperature, power, neutron flux, and uncertainties in the design parameters, as shown in Fig. 1. In this work, the core thermal design procedures are compared to verify the present PGSFR methodology based on the nuclear plant design criteria/guidelines and previous SFR thermal design methods. The PGSFR core thermal design procedure is verified based on the nuclear plant design criteria/guidelines and previous methods in LWRs and SFRs. The present method aims to directly evaluate the fuel cladding failure and to assure more safety margin. The 2 uncertainty is similar to 95% one-side tolerance limit of 1.96 in LWRs. The HCFs, ITDP, and MCM reveal similar uncertainty propagation for cladding midwall temperature for typical SFR conditions. The present HCFs are mainly employed from the CRBR except the fuel-related uncertainty such as an incorrect fuel distribution. Preliminary PGSFR specific HCFs will be developed by the end of 2015.

  12. Procedure for seismic evaluation and design of small bore piping

    International Nuclear Information System (INIS)

    Bilanin, W.; Sills, S.

    1991-01-01

    Simplified methods for the seismic design of small bore piping in nuclear power plants have teen used for many years. Various number of designers have developed unique methods to treat the large number of class 2 and 3 small bore piping systems. This practice has led to a proliferation of methods which are not standardized in the industry. These methods are generally based on enveloping the results of rigorous dynamic or conservative static analysis and result in an excessive number of supports and unrealistically high support loadings. Experience and test data have become available which warranted taking another look at the present methods for analysis of small bore piping. A recently completed Electric Power Research Institute and NCIG (a utility group) activity developed a new procedure for the seismic design and evaluation of small bore piping which provides significant safety and cost benefits. The procedure streamlines the approach to inertial stresses, which is the main feature that achieves the new benefits. Criteria in the procedure for seismic anchor movement and support design are based analysis and focus the designer on credible failure mechanisms. A walkdown of the as-constructed piping system to identify and eliminate undesirable piping features such as adverse spatial interaction is required

  13. Procedural Design of Exterior Lighting for Buildings with Complex Constraints

    KAUST Repository

    Schwarz, Michael

    2014-10-01

    We present a system for the lighting design of procedurally modeled buildings. The design is procedurally specified as part of the ordinary modeling workflow by defining goals for the illumination that should be attained and locations where luminaires may be installed to realize these goals. Additionally, constraints can be modeled that make the arrangement of the installed luminaires respect certain aesthetic and structural considerations. From this specification, the system automatically generates a lighting solution for any concrete model instance. The underlying, intricate joint optimization and constraint satisfaction problem is approached with a stochastic scheme that operates directly in the complex subspace where all constraints are observed. To navigate this subspace efficaciously, the actual lighting situation is taken into account. We demonstrate our system on multiple examples spanning a variety of architectural structures and lighting designs. Copyright held by the Owner/Author.

  14. Proposed design procedure for transmission shafting under fatigue loading

    Science.gov (United States)

    Loewenthal, S. H.

    1978-01-01

    The B106 American National Standards Committee is currently preparing a new standard for the design of transmission shafting. A design procedure, proposed for use in the new standard, for computing the diameter of rotating solid steel shafts under combined cyclic bending and steady torsion is presented. The formula is based on an elliptical variation of endurance strength with torque exhibited by combined stress fatigue data. Fatigue factors are cited to correct specimen bending endurance strength data for use in the shaft formula. A design example illustrates how the method is to be applied.

  15. Finite element design procedure for correcting the coining die profiles

    Science.gov (United States)

    Alexandrino, Paulo; Leitão, Paulo J.; Alves, Luis M.; Martins, Paulo A. F.

    2018-05-01

    This paper presents a new finite element based design procedure for correcting the coining die profiles in order to optimize the distribution of pressure and the alignment of the resultant vertical force at the end of the die stroke. The procedure avoids time consuming and costly try-outs, does not interfere with the creative process of the sculptors and extends the service life of the coining dies by significantly decreasing the applied pressure and bending moments. The numerical simulations were carried out in a computer program based on the finite element flow formulation that is currently being developed by the authors in collaboration with the Portuguese Mint. A new experimental procedure based on the stack compression test is also proposed for determining the stress-strain curve of the materials directly from the coin blanks.

  16. On the design of flight-deck procedures

    Science.gov (United States)

    Degani, Asaf; Wiener, Earl L.

    1994-01-01

    In complex human-machine systems, operations, training, and standardization depend on a elaborate set of procedures which are specified and mandated by the operational management of the organization. The intent is to provide guidance to the pilots, to ensure a logical, efficient, safe, and predictable means of carrying out the mission objectives. In this report the authors examine the issue of procedure use and design from a broad viewpoint. The authors recommend a process which we call 'The Four P's:' philosophy, policies, procedures, and practices. We believe that if an organization commits to this process, it can create a set of procedures that are more internally consistent, less confusing, better respected by the flight crews, and that will lead to greater conformity. The 'Four-P' model, and the guidelines for procedural development in appendix 1, resulted from cockpit observations, extensive interviews with airline management and pilots, interviews and discussion at one major airframe manufacturer, and an examination of accident and incident reports. Although this report is based on airline operations, we believe that the principles may be applicable to other complex, high-risk systems, such as nuclear power production, manufacturing process control, space flight, and military operations.

  17. WTS - Risk Based Resource Targeting (RBRT) -

    Data.gov (United States)

    Department of Transportation — The Risk Based Resource Targeting (RBRT) application supports a new SMS-structured process designed to focus on safety oversight of systems and processes rather than...

  18. Risk-based safety indicators

    International Nuclear Information System (INIS)

    Szikszai, T.

    1997-01-01

    The presentation discusses the following issues: The objectives of the risk-based indicator programme. The characteristics of the risk-based indicators. The objectives of risk-based safety indicators - in monitoring safety; in PSA applications. What indicators? How to produce the risk based indicators? PSA requirements

  19. Revised MITG design, fabrication procedure, and performance predictions

    International Nuclear Information System (INIS)

    Schock, A.

    1983-01-01

    The design, analysis, and key features of the Modular Isotopic Thermoelectric Generator (MITG) were described in a 1981 IECEC paper; and the design, fabrication, testing, and post-test analysis of test assemblies simulating prototypical MITG modules were described in preceding papers in these proceedings. These analyses succeeded in identifying and explaining the principal causes of thermal-stress problems encountered in the tests, and in confirming the effectiveness of design changes for alleviating them. The present paper presents additional design improvements for solving these and other problems, and describes new thermoelectric material properties generated by independent laboratories over the past two years. Based on these changes and on a revised fabrication procedure, it presents a reoptimization of the MITG design and computes the power-to-weight ratio for the revised design. That ratio is appreciably lower than the 1981 prediction, primarily because of changes in material properties; but it is still much higher than the specific power of current-generation RTGs

  20. LASL lens design procedure: simple, fast, precise, versatile

    International Nuclear Information System (INIS)

    Brixner, B.

    1978-11-01

    The Los Alamos Scientific Laboratory general-purpose lens design procedure optimizes specific lens prescriptions to obtain the smallest possible image spots and therefore near-spherical wave fronts of light converging on all images in the field of view. Optical image errors are analyzed in much the same way that they are measured on the optical bench. This lens design method is made possible by using the full capabilities of large electronic computers. First, the performance of the whole lens is sampled with many precisely traced skew rays. Next, lens performance is analyzed with spot diagrams generated by the many rays. Third, lens performance is optimized with a least squares system aimed at reducing all image errors to zero. This statistical approach to lens design uses skew rays and precisely measured ray deviations from ideal image points to achieve greater accuracy than was possible with the classical procedure, which is based on approximate expressions derived from simplified ray traces developed for pencil-and-paper calculations

  1. Design Procedure of Graphite Components by ASME HTR Codes

    International Nuclear Information System (INIS)

    Kang, Ji-Ho; Jo, Chang Keun

    2016-01-01

    In this study, the ASME B and PV Code, Subsection HH, Subpart A, design procedure for graphite components of HTRs was reviewed and the differences from metal materials were remarked. The Korean VHTR has a prismatic core which is made of multiple graphite blocks, reflectors, and core supports. One of the design issues is the assessment of the structural integrity of the graphite components because the graphite is brittle and shows quite different behaviors from metals in high temperature environment. The American Society of Mechanical Engineers (ASME) issued the latest edition of the code for the high temperature reactors (HTR) in 2015. In this study, the ASME B and PV Code, Subsection HH, Subpart A, Graphite Materials was reviewed and the special features were remarked. Due the brittleness of graphites, the damage-tolerant design procedures different from the conventional metals were adopted based on semi-probabilistic approaches. The unique additional classification, SRC, is allotted to the graphite components and the full 3-D FEM or equivalent stress analysis method is required. In specific conditions, the oxidation and viscoelasticity analysis of material are required. The fatigue damage rule has not been established yet

  2. Design Procedure of Graphite Components by ASME HTR Codes

    Energy Technology Data Exchange (ETDEWEB)

    Kang, Ji-Ho; Jo, Chang Keun [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2016-10-15

    In this study, the ASME B and PV Code, Subsection HH, Subpart A, design procedure for graphite components of HTRs was reviewed and the differences from metal materials were remarked. The Korean VHTR has a prismatic core which is made of multiple graphite blocks, reflectors, and core supports. One of the design issues is the assessment of the structural integrity of the graphite components because the graphite is brittle and shows quite different behaviors from metals in high temperature environment. The American Society of Mechanical Engineers (ASME) issued the latest edition of the code for the high temperature reactors (HTR) in 2015. In this study, the ASME B and PV Code, Subsection HH, Subpart A, Graphite Materials was reviewed and the special features were remarked. Due the brittleness of graphites, the damage-tolerant design procedures different from the conventional metals were adopted based on semi-probabilistic approaches. The unique additional classification, SRC, is allotted to the graphite components and the full 3-D FEM or equivalent stress analysis method is required. In specific conditions, the oxidation and viscoelasticity analysis of material are required. The fatigue damage rule has not been established yet.

  3. Design verification for large reprocessing plants (Proposed procedures)

    International Nuclear Information System (INIS)

    Rolandi, G.

    1988-07-01

    In the 1990s, four large commercial reprocessing plants will progressively come into operation: If an effective and efficient safeguards system is to be applied to these large and complex plants, several important factors have to be considered. One of these factors, addressed in the present report, concerns plant design verification. Design verification provides an overall assurance on plant measurement data. To this end design verification, although limited to the safeguards aspects of the plant, must be a systematic activity, which starts during the design phase, continues during the construction phase and is particularly performed during the various steps of the plant's commissioning phase. The detailed procedures for design information verification on commercial reprocessing plants must be defined within the frame of the general provisions set forth in INFCIRC/153 for any type of safeguards related activities and specifically for design verification. The present report is intended as a preliminary contribution on a purely technical level, and focusses on the problems within the Agency. For the purpose of the present study the most complex case was assumed: i.e. a safeguards system based on conventional materials accountancy, accompanied both by special input and output verification and by some form of near-real-time accountancy involving in-process inventory taking, based on authenticated operator's measurement data. C/S measures are also foreseen, where necessary to supplement the accountancy data. A complete ''design verification'' strategy comprehends: informing the Agency of any changes in the plant system which are defined as ''safeguards relevant''; ''reverifying by the Agency upon receiving notice from the Operator on any changes, on ''design information''. 13 refs

  4. Design procedure of capsule with multistage heater control (named MUSTAC)

    International Nuclear Information System (INIS)

    Someya, Hiroyuki; Endoh, Yasuichi; Hoshiya, Taiji; Niimi, Motoji; Harayama, Yasuo

    1990-11-01

    A capsule with electric heaters at multistage (named MUSTAC) is a type of capsule used in JMTR. The heaters are assembled in the capsule. Supply electric current to the heaters can be independently adjusted with a control systems that keeps irradiation specimens to constant temperature. The capsule being used, the irradiation specimen are inserted into specimen holders. Gas-gap size, between outer surface of specimen holders and inner surface of capsule casing, is calculated and determined to be flatten temperature of loaded specimens over the region. The rise or drop of specimen temperature in accordance with reactor power fluctuations is corrected within the target temperature of specimen by using the heaters filled into groove at specimen holder surface. The present report attempts to propose a reasonable design procedure of the capsules by means of compiling experience for designs, works and irradiation data of the capsules and to prepare for useful informations against onward capsule design. The key point of the capsule lies on thermal design. Now design thermal calculations are complicated in case of specimen holder with multihole. Resolving these issues, it is considered from new on that an emphasis have to placed on settling a thermal calculation device, for an example, a computer program on calculation specimen temperature. (author)

  5. Criteria procedure development for tender in construction design

    Directory of Open Access Journals (Sweden)

    Malykha Galina Gennad’evna

    Full Text Available This article deals with the problem of criteria optimization in order to objectively evaluate the experience of an applicant (a project organization and the quality of a design product (project documentation. The methodology to be developed is based on introduction of new evaluation criteria (sub-criteria that in conjunction with the applicable criteria specified by the Law on the Contract System will allow developing the optimal procedure to evaluate competitive bids of the participants in tenders and determining the most appropriate candidate, with whom the contract will be further concluded. The article analyzes the existing criteria and their interaction with each other and describes the specifics of tenders for design in the form of open competition. The list decreases to three criteria, such as "contract price", "quality, functional and environmental characteristics of a procurement facility", "qualification of procurement participants, including availability of financial resources, equipment and other material resources necessary for the execution of the contract material resources, the presence of goodwill, professionals and other employees of a certain experience level". However, in order to upgrade the quality of assurance procedures for the design works to be performed, it was decided to apply new evaluation criteria (sub-criteria components, such as "availability of positive findings of the state out-of-departmental examination that are similar to the subject of competition, on a participant in placement of order", "availability of the certificate on approval of architectural and urban planning decisions that are similar to the subject of competition, on a participant in placement of order", "availability of the permit for the commissioning of facilities that are similar to the subject of competition, on a participant in placement of order", "availability of the contract for designer's supervision with a participant in placement of

  6. Study of a risk-based piping inspection guideline system.

    Science.gov (United States)

    Tien, Shiaw-Wen; Hwang, Wen-Tsung; Tsai, Chih-Hung

    2007-02-01

    A risk-based inspection system and a piping inspection guideline model were developed in this study. The research procedure consists of two parts--the building of a risk-based inspection model for piping and the construction of a risk-based piping inspection guideline model. Field visits at the plant were conducted to develop the risk-based inspection and strategic analysis system. A knowledge-based model had been built in accordance with international standards and local government regulations, and the rational unified process was applied for reducing the discrepancy in the development of the models. The models had been designed to analyze damage factors, damage models, and potential damage positions of piping in the petrochemical plants. The purpose of this study was to provide inspection-related personnel with the optimal planning tools for piping inspections, hence, to enable effective predictions of potential piping risks and to enhance the better degree of safety in plant operations that the petrochemical industries can be expected to achieve. A risk analysis was conducted on the piping system of a petrochemical plant. The outcome indicated that most of the risks resulted from a small number of pipelines.

  7. New procedures of ergonomics design in a large oil company.

    Science.gov (United States)

    Alhadeff, Cynthia Mossé; Silva, Rosana Fernandes da; Reis, Márcia Sales dos

    2012-01-01

    This study presents the challenge involved in the negotiation and construction of a standard process in a major petroleum company that has the purpose of guiding the implementation of ergonomic studies in the development of projects, systemising the implementation of ergonomics design. The standard was created by a multi-disciplinary working group consisting of specialists in ergonomics, who work in a number of different areas of the company. The objective was to guide "how to" undertake ergonomics in all projects, taking into consideration the development of the ergonomic appraisals of work. It also established that all the process, in each project phase, should be accompanied by a specialist in ergonomics. This process as an innovation in the conception of projects in this company, signals a change of culture, and, for this reason requires broad dissemination throughout the several company leadership levels, and training of professionals in projects of ergonomics design. An implementation plan was also prepared and approved by the corporate governance, complementing the proposed challenge. In this way, this major oil company will implement new procedures of ergonomics design to promote health, safety, and wellbeing of the workforce, besides improving the performance and reliability of its systems and processes.

  8. Risk-based configuration control

    International Nuclear Information System (INIS)

    Szikszai, T.

    1997-01-01

    The presentation discusses the following issues: The Configuration Control; The Risk-based Configuration Control (during power operation mode, and during shutdown mode). PSA requirements. Use of Risk-based Configuration Control System. Configuration Management (basic elements, benefits, information requirements)

  9. Design procedures of hybrid PV/SMES system

    International Nuclear Information System (INIS)

    Hamad, Ismail; El-Sayas, M. A.

    2006-01-01

    This paper presents accurate procedures to determine the design parameters of an autonomous hybrid PV/SMES system. Integrating Superconductive magnetic energy storage as a recent storage technology with photovoltaic power system enhances the PV output utilization during the solar radiation fluctuations period. this is because of SMES fast response to any PV output fluctuation. The load demand is supplied either from PV plant or through SMES or from both. Imposed to the technical and economical constrains, the optimum solar cells area and the proper capacity and rating of SMES system are assessed. Regarding solar radiation profile, clear and cloudy days are accurately considered for investigation. Three indices are suggested to express the cloudy and fluctuations conditions. These indices represent the non-utilized PV energy due to clouds (x), fluctuation period (T f ) and location of fluctuations period(t s t). The incremental changes in the design parameters are computed for any variation in these indices. Differentiation between the role of BS and SMES in affecting the results is determined and quantitatively analyzed. The results of clear day condition with SMES are the bas quantities for these changes. Complete analysis of the most effective parameters is presented. Eventually, mathematical models are deduced for each parameter which assists in predicting its behavior against the independent variable.(Author)

  10. Evaluation of vertical profiles to design continuous descent approach procedure

    Science.gov (United States)

    Pradeep, Priyank

    The current research focuses on predictability, variability and operational feasibility aspect of Continuous Descent Approach (CDA), which is among the key concepts of the Next Generation Air Transportation System (NextGen). The idle-thrust CDA is a fuel economical, noise and emission abatement procedure, but requires increased separation to accommodate for variability and uncertainties in vertical and speed profiles of arriving aircraft. Although a considerable amount of researches have been devoted to the estimation of potential benefits of the CDA, only few have attempted to explain the predictability, variability and operational feasibility aspect of CDA. The analytical equations derived using flight dynamics and Base of Aircraft and Data (BADA) Total Energy Model (TEM) in this research gives insight into dependency of vertical profile of CDA on various factors like wind speed and gradient, weight, aircraft type and configuration, thrust settings, atmospheric factors (deviation from ISA (DISA), pressure and density of the air) and descent speed profile. Application of the derived equations to idle-thrust CDA gives an insight into sensitivity of its vertical profile to multiple factors. This suggests fixed geometric flight path angle (FPA) CDA has higher degree of predictability and lesser variability at the cost of non-idle and low thrust engine settings. However, with optimized design this impact can be overall minimized. The CDA simulations were performed using Future ATM Concept Evaluation Tool (FACET) based on radar-track and aircraft type data (BADA) of the real air-traffic to some of the busiest airports in the USA (ATL, SFO and New York Metroplex (JFK, EWR and LGA)). The statistical analysis of the vertical profiles of CDA shows 1) mean geometric FPAs derived from various simulated vertical profiles are consistently shallower than 3° glideslope angle and 2) high level of variability in vertical profiles of idle-thrust CDA even in absence of

  11. Using a standards committee to design practical procedure system improvements

    International Nuclear Information System (INIS)

    Grider, D.A.; Plung, D.

    1993-01-01

    In the post-Three Mile Island (TMI) environment, numerous reports have been issued on how to improve the quality of procedures used at government and commercial nuclear facilities. The studies tend to be long on what is wrong with existing procedures and short on practical directions on how to fix those faults. Few of these studies have been conducted by practitioners with full-time procedure-managing or procedure writing experience. None of these studies go into detail on how to improve the procedure system itself. Over the last 10 yr, various nuclear facilities within the US Department of Energy (DOE) have carried out individual programs to develop procedures that meet post-TMI standards. However, ∼2 yr ago, DOE formed a Procedures Standards Committee to advise DOE in developing a set of post-TMI guidelines that could be consistently applied throughout all DOE nuclear facilities. The committee has achieved not only its original mission by producing a series of integrated guidance documents but has also evolved a systems approach to procedures management that sets new standards for procedure quality and efficiency. As members of this committee, the authors want to describe what has made the group's approach so successful. The lessons learned may be translatable to a wide range of government and commercial industry procedure programs

  12. Model of Procedure Usage – Results from a Qualitative Study to Inform Design of Computer-Based Procedures

    Energy Technology Data Exchange (ETDEWEB)

    Johanna H Oxstrand; Katya L Le Blanc

    2012-07-01

    The nuclear industry is constantly trying to find ways to decrease the human error rate, especially the human errors associated with procedure use. As a step toward the goal of improving procedure use performance, researchers, together with the nuclear industry, have been looking at replacing the current paper-based procedures with computer-based procedure systems. The concept of computer-based procedures is not new by any means; however most research has focused on procedures used in the main control room. Procedures reviewed in these efforts are mainly emergency operating procedures and normal operating procedures. Based on lessons learned for these previous efforts we are now exploring a more unknown application for computer based procedures - field procedures, i.e. procedures used by nuclear equipment operators and maintenance technicians. The Idaho National Laboratory, the Institute for Energy Technology, and participants from the U.S. commercial nuclear industry are collaborating in an applied research effort with the objective of developing requirements and specifications for a computer-based procedure system to be used by field operators. The goal is to identify the types of human errors that can be mitigated by using computer-based procedures and how to best design the computer-based procedures to do this. The underlying philosophy in the research effort is “Stop – Start – Continue”, i.e. what features from the use of paper-based procedures should we not incorporate (Stop), what should we keep (Continue), and what new features or work processes should be added (Start). One step in identifying the Stop – Start – Continue was to conduct a baseline study where affordances related to the current usage of paper-based procedures were identified. The purpose of the study was to develop a model of paper based procedure use which will help to identify desirable features for computer based procedure prototypes. Affordances such as note taking, markups

  13. On anti-earthquake design procedure of equipment and pipings in near future

    International Nuclear Information System (INIS)

    Shibata, H.

    1981-01-01

    The requirement of anti-earthquake design of nuclear power plants is getting severe year by year. The author will try to discuss how to control its severity and how to find a proper design procedure for licensing of new plants under such severe requirements. On the other hand we suffered from the enormous volumes of documents. To decrease such volumes, the format of documents should be standardized as well as the design procedure standardization. Starting from this point, we need the research and development on the following subjects: i) Standardization of design procedure. ii) Standardization of document. iii) Establishment of standard review procedure using computer. iv) Standardization of earthquake-resistant designed equipment. v) Standardization of anti-earthquake design procedure of piping systems. vi) Introducing margin evaluation procedure to design procedure. vii) Introducing proving test procedure of active component to design procedure. viii) Establishment of evaluation of human reliability in design, fabrication, inspection procedures. ix) Establishment of the proper relation of seismic trigger level and post-earthquake design procedures. (orig./HP)

  14. Protection of citizens' rights by appropriate design of legal procedures

    International Nuclear Information System (INIS)

    Bluemel, W.

    1982-01-01

    The author regards the Muehlheim-Kaerlich ruling by the Federal Constitutional Court of December 12, 1979 as a ruling which stipulates the protection of basic rights as a main function of the citizen participation. The essential importance of this ruling is specified by the statement that the shaping of procedures - of courts and authorities - has a constitutional importance, that the shaping of procedures is an essential element of an effective guarantee of basic rights. He expressly extends the above mentioned jurisdiction of the Federal Constitutional Court beyond the influence of the substantive basic rights on the procedural law to the administrative procedural law. The procedural basic right of article 19, section 4 of the constitution is supplemented by the claim for an effective legal protection which directly results from the substantive basic right of article 14, section 1, paragraph 1 of the constitution. (orig./HSCH) [de

  15. Weld Design, Testing, and Assessment Procedures for High Strength Pipelines

    Science.gov (United States)

    2011-12-20

    Long-distance high-strength pipelines are increasingly being constructed for the efficient transportation of energy products. While the high-strength linepipe steels and high productivity welding processes are being applied, the procedures employed f...

  16. A surrogate based multistage-multilevel optimization procedure for multidisciplinary design optimization

    NARCIS (Netherlands)

    Yao, W.; Chen, X.; Ouyang, Q.; Van Tooren, M.

    2011-01-01

    Optimization procedure is one of the key techniques to address the computational and organizational complexities of multidisciplinary design optimization (MDO). Motivated by the idea of synthetically exploiting the advantage of multiple existing optimization procedures and meanwhile complying with

  17. Risk-based Regulatory Evaluation Program methodology

    International Nuclear Information System (INIS)

    DuCharme, A.R.; Sanders, G.A.; Carlson, D.D.; Asselin, S.V.

    1987-01-01

    The objectives of this DOE-supported Regulatory Evaluation Progrwam are to analyze and evaluate the safety importance and economic significance of existing regulatory guidance in order to assist in the improvement of the regulatory process for current generation and future design reactors. A risk-based cost-benefit methodology was developed to evaluate the safety benefit and cost of specific regulations or Standard Review Plan sections. Risk-based methods can be used in lieu of or in combination with deterministic methods in developing regulatory requirements and reaching regulatory decisions

  18. Design and optimisation of purification procedure for biodiesel washing

    Directory of Open Access Journals (Sweden)

    S.B. Glišić

    2009-09-01

    Full Text Available Almost complete methanolysis of triglycerides is usually not enough to fulfil the strict standards of biodiesel quality. A key step in this process is neutralization of alkali (catalyst followed by the washing procedure necessary for removing different impurities such as traces of catalyst and methanol and removal of soaps and glycerol from esters phase. The washing with hot water is still widely used in many industrial units for the biodiesel production. In this study, different procedures of biodiesel washing using hot water were investigated. The orto-phosphoric acid was suggested as the best compound for alkali catalyst (sodium hydroxide neutralization. The main goal of the performed analysis was to minimize the water usage in the washing-neutralization step during the biodiesel production. Such solution would make the process of biodiesel synthesis more economical taking into account the decrease of energy consumed for evaporation of water during the final product purification, as well as more acceptable procedure related to the impact on environment (minimal waste water release. Results of the performed simulation of the washing process supported by original experimental data suggested that neutralization after the optimized washing process of the methyl ester layer could be the best solution. The proposed washing procedure significantly decreases the amount of waste water giving at the same time the desired purity of final products (biodiesel and glycerol. The simulation of the process was performed using ASPEN plus software supported by ELCANTREL and UNIQUAC procedure of required properties calculation

  19. Risk-based inspection of nuclear power plants

    International Nuclear Information System (INIS)

    Masopust, R.

    1995-01-01

    A multidiscipline research programme was developed in the USA to establish risk-based inspections for NPP structures and equipment components. Based on this US research effort, the risk-based procedure for developing inspection guidelines for NPPs is described. The procedure includes the definition of systems, qualitative risk assessment, qualitative risk analysis and development of the inspection programme. The method, when adopted and modified, is recommended also for risk-based inspections of structures and equipment of WWER-type NPPs. A pilot application of the method to unit 1 of the Surry NPP is summarized. (Z.S.) 1 tab., 1 fig., 5 refs

  20. Recent advances in design procedures for high temperature plant

    International Nuclear Information System (INIS)

    1988-01-01

    Thirteen papers cover several aspects of design for high temperature plant. These include design codes, computerized structural analysis and mechanical properties of materials at high temperatures. Seven papers are relevant for fast reactors and these are indexed separately. These cover shakedown design, design codes for thin shells subjected to cyclic thermal loading, the inelastic behaviour of stainless steels and creep and crack propagation in reactor structures under stresses caused by thermal cycling loading. (author)

  1. A surrogate based multistage-multilevel optimization procedure for multidisciplinary design optimization

    OpenAIRE

    Yao, W.; Chen, X.; Ouyang, Q.; Van Tooren, M.

    2011-01-01

    Optimization procedure is one of the key techniques to address the computational and organizational complexities of multidisciplinary design optimization (MDO). Motivated by the idea of synthetically exploiting the advantage of multiple existing optimization procedures and meanwhile complying with the general process of satellite system design optimization in conceptual design phase, a multistage-multilevel MDO procedure is proposed in this paper by integrating multiple-discipline-feasible (M...

  2. Improved Design of Crew Operation in Computerized Procedure System of APR1400

    Energy Technology Data Exchange (ETDEWEB)

    Seong, No Kyu; Jung, Yeon Sub; Sung, Chan Ho [KHNP, Daejeon (Korea, Republic of)

    2016-05-15

    The operators perform the paper-based procedures in analog-based conventional main control room (MCR) depending on only communications between operators except a procedure controller such as a Shift Supervisor (SS), however in digital-based MCR the operators can confirm the procedures simultaneously in own console when the procedure controller of computerized procedure (CP) opens the CP. The synchronization and a synchronization function between procedure controller and other operators has to be considered to support the function of crew operation. This paper suggests the improved design of crew operation in computerized procedure system of APR1400. This paper suggests the improved design of APR1400 CPS. These improvements can help operators perform the crew procedures more efficiently. And they reduce a burden of communication and misunderstanding of computerized procedures. These improvements can be applied to CPS after human factors engineering verification and validation.

  3. design chart procedures for polygonal concrete-filled steel columns

    African Journals Online (AJOL)

    ADMIN

    hexagonal and octagonal steel-concrete composite columns subjected to ... This paper also outlines procedures that will enable preparation of ... buildings and in a variety of large-span building ... Likewise, hot-rolled steel tubes are used while ... small moderate large. Fig. 2. Possible arrangement of composite polygonal ...

  4. Risk-based safety indicators

    International Nuclear Information System (INIS)

    Sedlak, J.

    2001-12-01

    The report is structured as follows: 1. Risk-based safety indicators: Typology of risk-based indicators (RBIs); Tools for defining RBIs; Requirements for the PSA model; Data sources for RBIs; Types of risks monitored; RBIs and operational safety indicators; Feedback from operating experience; PSO model modification for RBIs; RBI categorization; RBI assessment; RBI applications; Suitable RBI applications. 2. Proposal for risk-based indicators: Acquiring information from operational experience; Method of acquiring safety relevance coefficients for the systems from a PSA model; Indicator definitions; On-line indicators. 3. Annex: Application of RBIs worldwide. (P.A.)

  5. Designing a risk-based surveillance program for Mycobacterium avium ssp. paratuberculosis in Norwegian dairy herds using multivariate statistical process control analysis.

    Science.gov (United States)

    Whist, A C; Liland, K H; Jonsson, M E; Sæbø, S; Sviland, S; Østerås, O; Norström, M; Hopp, P

    2014-11-01

    Surveillance programs for animal diseases are critical to early disease detection and risk estimation and to documenting a population's disease status at a given time. The aim of this study was to describe a risk-based surveillance program for detecting Mycobacterium avium ssp. paratuberculosis (MAP) infection in Norwegian dairy cattle. The included risk factors for detecting MAP were purchase of cattle, combined cattle and goat farming, and location of the cattle farm in counties containing goats with MAP. The risk indicators included production data [culling of animals >3 yr of age, carcass conformation of animals >3 yr of age, milk production decrease in older lactating cows (lactations 3, 4, and 5)], and clinical data (diarrhea, enteritis, or both, in animals >3 yr of age). Except for combined cattle and goat farming and cattle farm location, all data were collected at the cow level and summarized at the herd level. Predefined risk factors and risk indicators were extracted from different national databases and combined in a multivariate statistical process control to obtain a risk assessment for each herd. The ordinary Hotelling's T(2) statistic was applied as a multivariate, standardized measure of difference between the current observed state and the average state of the risk factors for a given herd. To make the analysis more robust and adapt it to the slowly developing nature of MAP, monthly risk calculations were based on data accumulated during a 24-mo period. Monitoring of these variables was performed to identify outliers that may indicate deviance in one or more of the underlying processes. The highest-ranked herds were scattered all over Norway and clustered in high-density dairy cattle farm areas. The resulting rankings of herds are being used in the national surveillance program for MAP in 2014 to increase the sensitivity of the ongoing surveillance program in which 5 fecal samples for bacteriological examination are collected from 25 dairy herds

  6. Risk-based and deterministic regulation

    International Nuclear Information System (INIS)

    Fischer, L.E.; Brown, N.W.

    1995-07-01

    Both risk-based and deterministic methods are used for regulating the nuclear industry to protect the public safety and health from undue risk. The deterministic method is one where performance standards are specified for each kind of nuclear system or facility. The deterministic performance standards address normal operations and design basis events which include transient and accident conditions. The risk-based method uses probabilistic risk assessment methods to supplement the deterministic one by (1) addressing all possible events (including those beyond the design basis events), (2) using a systematic, logical process for identifying and evaluating accidents, and (3) considering alternative means to reduce accident frequency and/or consequences. Although both deterministic and risk-based methods have been successfully applied, there is need for a better understanding of their applications and supportive roles. This paper describes the relationship between the two methods and how they are used to develop and assess regulations in the nuclear industry. Preliminary guidance is suggested for determining the need for using risk based methods to supplement deterministic ones. However, it is recommended that more detailed guidance and criteria be developed for this purpose

  7. Analysis of half diallel mating designs I: a practical analysis procedure for ANOVA approximation.

    Science.gov (United States)

    G.R. Johnson; J.N. King

    1998-01-01

    Procedures to analyze half-diallel mating designs using the SAS statistical package are presented. The procedure requires two runs of PROC and VARCOMP and results in estimates of additive and non-additive genetic variation. The procedures described can be modified to work on most statistical software packages which can compute variance component estimates. The...

  8. A robust anti-windup design procedure for SISO systems

    Science.gov (United States)

    Kerr, Murray; Turner, Matthew C.; Villota, Elizabeth; Jayasuriya, Suhada; Postlethwaite, Ian

    2011-02-01

    A model-based anti-windup (AW) controller design approach for constrained uncertain linear single-input-single-output (SISO) systems is proposed based on quantitative feedback theory (QFT) loopshaping. The design approach explicitly incorporates uncertainty, is suitable for the solution of both the magnitude and rate saturation problems, and provides for the design of low-order AW controllers satisfying robust stability and robust performance objectives. Robust stability is enforced using absolute stability theory and generic multipliers (i.e. circle, Popov, Zames-Falb), and robust performance is enforced using linear lower-bounds on the input-output maps capturing the effects of saturation as a metric. Two detailed design examples are presented. These show that even for simple systems, certain popular AW techniques lead to compensators that may fail to ensure robust stability and performance when saturation is encountered, but that the proposed QFT design approach is able to handle both saturation and uncertainty effectively.

  9. Design procedure for sizing a submerged-bed scrubber for airborne particulate removal

    International Nuclear Information System (INIS)

    Ruecker, C.M.; Scott, P.A.

    1987-04-01

    Performance correlations to design and operate the submerged bed scrubber were developed for various applications. Structural design procedure outlined in this report focuses on off-gas scrubbing for HLW vitrification applications; however, the method is appropriate for other applications

  10. A CFD-based aerodynamic design procedure for hypersonic wind-tunnel nozzles

    Science.gov (United States)

    Korte, John J.

    1993-01-01

    A new procedure which unifies the best of current classical design practices, computational fluid dynamics (CFD), and optimization procedures is demonstrated for designing the aerodynamic lines of hypersonic wind-tunnel nozzles. The new procedure can be used to design hypersonic wind tunnel nozzles with thick boundary layers where the classical design procedure has been shown to break down. An efficient CFD code, which solves the parabolized Navier-Stokes (PNS) equations using an explicit upwind algorithm, is coupled to a least-squares (LS) optimization procedure. A LS problem is formulated to minimize the difference between the computed flow field and the objective function, consisting of the centerline Mach number distribution and the exit Mach number and flow angle profiles. The aerodynamic lines of the nozzle are defined using a cubic spline, the slopes of which are optimized with the design procedure. The advantages of the new procedure are that it allows full use of powerful CFD codes in the design process, solves an optimization problem to determine the new contour, can be used to design new nozzles or improve sections of existing nozzles, and automatically compensates the nozzle contour for viscous effects as part of the unified design procedure. The new procedure is demonstrated by designing two Mach 15, a Mach 12, and a Mach 18 helium nozzles. The flexibility of the procedure is demonstrated by designing the two Mach 15 nozzles using different constraints, the first nozzle for a fixed length and exit diameter and the second nozzle for a fixed length and throat diameter. The computed flow field for the Mach 15 least squares parabolized Navier-Stokes (LS/PNS) designed nozzle is compared with the classically designed nozzle and demonstrates a significant improvement in the flow expansion process and uniform core region.

  11. Design and fabrication procedures of Super-Phenix fuel elements

    International Nuclear Information System (INIS)

    Leclere, J.; Vialard, J.-L.; Delpeyroux, P.

    1975-01-01

    For Super-Phenix fuel assemblies, Phenix technological arrangements will be used again, but they will be simplified as far as possible. The maximum fuel can temperature has been lowered in order to obtain a good behavior of hexagonal tubes and cans at high irradiation levels. An important experimental programme and the experience gained from Phenix operation will confirm the merits of the options retained. The fuel element fabrication is envisaged to take place in the plutonium workshop at Cadarache. Usual procedures will be employed and both reliability and automation will be increased [fr

  12. 40 CFR 240.203-2 - Recommended procedures: Design.

    Science.gov (United States)

    2010-07-01

    ..., easy to maintain, and consistent with the land use of the area. (d) Employee convenience facilities and... operating unit malfunctions. (j) Sampling capability should be designed into the facility so that each process stream can be sampled, and the utilities required to do so should be close at hand. The sampling...

  13. Designing sustainable energy landscapes : concepts, principles and procedures

    NARCIS (Netherlands)

    Stremke, S.

    2010-01-01

    The depletion of fossil fuels, in combination with climate change, necessitates a transition to sustainable energy systems. Such systems are characterized by a decreased energy demand and an increase in the use of renewables. The objective of this dissertation is to advance the planning and design

  14. Students' Design of a Biometric Procedure in Upper Secondary School

    Science.gov (United States)

    Marzin, Patricia; de Vries, Erica

    2013-01-01

    Making the connection between science and technology might be important for students to learn to identify and solve problems and to acquire scientific knowledge and skills. The research reported in this article concerned the development of a design situation in a science classroom and the study of students performing in this situation. More…

  15. 17 CFR 38.3 - Procedures for designation.

    Science.gov (United States)

    2010-04-01

    ... application for designation with the Secretary of the Commission at its Washington, DC, headquarters. Except... partnership or limited liability company, third-party regulatory service, or member or user agreements, that... filing such a request with the Commission at its Washington, DC, headquarters. Withdrawal of an...

  16. Framework for a procedure for design for durability

    NARCIS (Netherlands)

    Siemes, A.J.M.

    1996-01-01

    The design for durability of structures and building components is in general based on implicit requirements with respect to the quality and dimensions of the composing building materials and components. These requirements are based on long term experience. This approach has disadvantages. It is

  17. New procedure to design low radar cross section near perfect isotropic and homogeneous triangular carpet cloaks.

    Science.gov (United States)

    Sharifi, Zohreh; Atlasbaf, Zahra

    2016-10-01

    A new design procedure for near perfect triangular carpet cloaks, fabricated based on only isotropic homogeneous materials, is proposed. This procedure enables us to fabricate a cloak with simple metamaterials or even without employing metamaterials. The proposed procedure together with an invasive weed optimization algorithm is used to design carpet cloaks based on quasi-isotropic metamaterial structures, Teflon and AN-73. According to the simulation results, the proposed cloaks have good invisibility properties against radar, especially monostatic radar. The procedure is a new method to derive isotropic and homogeneous parameters from transformation optics formulas so we do not need to use complicated structures to fabricate the carpet cloaks.

  18. An annotated summary of the Information Model Design Procedure (IMDP)

    Energy Technology Data Exchange (ETDEWEB)

    Becker, S.D.

    1994-05-01

    This presentation documents the essential elements of the IMDP as applied at Sandia National Laboratories/New Mexico. The IMDP is an adaptation of the Natural-Language Information Analysis Methodology (NIAM) of G. M. Nijssen. The underlying purpose of both of these methodologies is to provide a formal, reproducible, and verifiable approach to specifying the information requirements of an information system. The IMDP spans the specification process from initial scoping; through verbalization of problem-domain facts, specification of constraints, and subtype analysis; and finally to application of a formal algorithm for developing a fifth-normal-form relational database design.

  19. Development of an optimized procedure bridging design and structural analysis codes for the automatized design of the SMART

    International Nuclear Information System (INIS)

    Kim, Tae Wan; Park, Keun Bae; Choi, Suhn; Kim, Kang Soo; Jeong, Kyeong Hoon; Lee, Gyu Mahn

    1998-09-01

    In this report, an optimized design and analysis procedure is established to apply to the SMART (System-integrated Modular Advanced ReacTor) development. The development of an optimized procedure is to minimize the time consumption and engineering effort by squeezing the design and feedback interactions. To achieve this goal, the data and information generated through the design development should be directly transferred to the analysis program with minimum operation. The verification of the design concept requires considerable effort since the communication between the design and analysis involves time consuming stage for the conversion of input information. In this report, an optimized procedure is established bridging the design and analysis stage utilizing the IDEAS, ABAQUS and ANSYS. (author). 3 refs., 2 tabs., 5 figs

  20. Risk-based decisionmaking (Panel)

    Energy Technology Data Exchange (ETDEWEB)

    Smith, T.H.

    1995-12-31

    By means of a panel discussion and extensive audience interaction, explore the current challenges and progress to date in applying risk considerations to decisionmaking related to low-level waste. This topic is especially timely because of the proposed legislation pertaining to risk-based decisionmaking and because of the increased emphasis placed on radiological performance assessments of low-level waste disposal.

  1. Design and analysis of automobile components using industrial procedures

    Science.gov (United States)

    Kedar, B.; Ashok, B.; Rastogi, Nisha; Shetty, Siddhanth

    2017-11-01

    Today’s automobiles depend upon mechanical systems that are crucial for aiding in the movement and safety features of the vehicle. Various safety systems such as Antilock Braking System (ABS) and passenger restraint systems have been developed to ensure that in the event of a collision be it head on or any other type, the safety of the passenger is ensured. On the other side, manufacturers also want their customers to have a good experience while driving and thus aim to improve the handling and the drivability of the vehicle. Electronics systems such as Cruise Control and active suspension systems are designed to ensure passenger comfort. Finally, to ensure optimum and safe driving the various components of a vehicle must be manufactured using the latest state of the art processes and must be tested and inspected with utmost care so that any defective component can be prevented from being sent out right at the beginning of the supply chain. Therefore, processes which can improve the lifetime of their respective components are in high demand and much research and development is done on these processes. With a solid base research conducted, these processes can be used in a much more versatile manner for different components, made up of different materials and under different input conditions. This will help increase the profitability of the process and also upgrade its value to the industry.

  2. Increasing spelling achievement: an analysis of treatment procedures utilizing an alternating treatments design.

    OpenAIRE

    Ollendick, T H; Matson, J L; Esveldt-Dawson, K; Shapiro, E S

    1980-01-01

    Two studies which examine the effectiveness of spelling remediation procedures are reported. In both studies, an alternating treatment design was employed. In the first study, positive practice overcorrection plus positive reinforcement was compared to positive practice alone and a no-remediation control condition. In the second study, positive practice plus positive reinforcement was compared to a traditional corrective procedure plus positive reinforcement and a traditional procedure when u...

  3. 6 CFR 25.6 - Procedures for designation of qualified anti-terrorism technologies.

    Science.gov (United States)

    2010-01-01

    ...-terrorism technologies. 25.6 Section 25.6 Domestic Security DEPARTMENT OF HOMELAND SECURITY, OFFICE OF THE SECRETARY REGULATIONS TO SUPPORT ANTI-TERRORISM BY FOSTERING EFFECTIVE TECHNOLOGIES § 25.6 Procedures for designation of qualified anti-terrorism technologies. (a) Application Procedure. Any person, firm or other...

  4. 40 CFR 63.8687 - What performance tests, design evaluations, and other procedures must I use?

    Science.gov (United States)

    2010-07-01

    ... evaluations, and other procedures must I use? 63.8687 Section 63.8687 Protection of Environment ENVIRONMENTAL... What performance tests, design evaluations, and other procedures must I use? (a) You must conduct each... run must last at least 1 hour. (e) You must use the following equations to determine compliance with...

  5. 40 CFR 63.7112 - What performance tests, design evaluations, and other procedures must I use?

    Science.gov (United States)

    2010-07-01

    ... evaluations, and other procedures must I use? 63.7112 Section 63.7112 Protection of Environment ENVIRONMENTAL..., design evaluations, and other procedures must I use? (a) You must conduct each performance test in Table... use wet dust suppression to control PM from PSH operations, a visible mist is sometimes generated by...

  6. State-of-the-practice : evaluation of sediment basin design, construction, maintenance, and inspection procedures.

    Science.gov (United States)

    2012-08-01

    The following document is the summary of results from a survey that was conducted to evaluate : the state-of-the-practice for sediment basin design, construction, maintenance, and inspection : procedures by State Highway Agencies (SHAs) across the na...

  7. Development of structural design procedure of plate-fin heat exchanger for HTGR

    Energy Technology Data Exchange (ETDEWEB)

    Mizokami, Yorikata, E-mail: yorikata_mizokami@mhi.co.jp [Mitsubishi Heavy Industries, Ltd., 1-1, Wadasaki-cho 1-Chome, Hyogo-ku, Kobe 652-8585 (Japan); Igari, Toshihide [Mitsubishi Heavy Industries, Ltd., 5-717-1, Fukahori-machi, Nagasaki 851-0392 (Japan); Kawashima, Fumiko [Kumamoto University, 39-1 Kurokami 2-Chome, Kumamoto 860-8555 (Japan); Sakakibara, Noriyuki [Mitsubishi Heavy Industries, Ltd., 5-717-1, Fukahori-machi, Nagasaki 851-0392 (Japan); Tanihira, Masanori [Mitsubishi Heavy Industries, Ltd., 16-5, Konan 2-Chome, Minato-ku, Tokyo 108-8215 (Japan); Yuhara, Tetsuo [The University of Tokyo, 7-3-1, Hongo, Bunkyo-ku, Tokyo 113-8656 (Japan); Hiroe, Tetsuyuki [Kumamoto University, 39-1 Kurokami 2-Chome, Kumamoto 860-8555 (Japan)

    2013-02-15

    Highlights: ► We propose high temperature structural design procedure for plate-fin heat exchanger ► Allowable stresses for brazed structures will be newly discussed ► Validity of design procedure is confirmed by carrying out partial model tests ► Proposed design procedure is applied to heat exchangers for HTGR. -- Abstract: Highly efficient plate-fin heat exchanger for application to HTGR has been focused on recently. Since this heat exchanger is fabricated by brazing a lot of plates and fins, a new procedure for structural design of brazed structures in the HTGR temperature region up to 950 °C is required. Firstly in this paper influences on material strength due to both thermal aging during brazing process and helium gas environment were experimentally examined, and failure mode and failure limit of brazed side-bar structures were experimentally clarified. Secondly allowable stresses for aging materials and brazed structures were newly determined on the basis of the experimental results. For the purpose of validating the structural design procedure including homogenization FEM modeling, a pressure burst test and a thermal fatigue test of partial model for plate-fin heat exchanger were carried out. Finally, results of reference design of plate-fin heat exchangers of recuperator and intermediate heat exchanger for HTGR plant were evaluated by the proposed design criteria.

  8. Design of test and emergency procedures to improve operator behaviour in French nuclear power plants

    International Nuclear Information System (INIS)

    Griffon-Fouco, M.; Gomolinski, M.

    1982-09-01

    The incident analyses performed in French nuclear power plants high-lighted that deficiencies in the design of procedures are frequent causes of human errors. The process for developing new guidelines for the writing of test and emergency procedures is presented: this process is based on operators interviews and observations at the plants or at simulators. The main principles for the writing of procedures are developed. For example: - the elaboration of a procedure for action and of a separate educational procedure, - the coordination of crew responses, - the choice of vocabulary, graphs, flow charts and so on as regards the format. Other complementary actions, such as the training of operators in the use of procedures, are described

  9. Design of test and emergency procedures to improve operator behavior in French nuclear power plants

    International Nuclear Information System (INIS)

    Griffon-Fouco, M.; Gomolinski, M.

    1983-01-01

    The incident analyses performed in French nuclear power plants high-lighted that deficiencies in the design of procedures are frequent causes of human errors. The process for developing new guidelines for the writing of test and emergency procedures is presented: this process is based on operators interviews and observations at the plants or at simulators. The main principles for the writing of procedures are developed. For example: the elaboration of a procedure for action and of separate educational procedure; the coordination of crew responses; and the choice of vocabulary, graphs, flow charts and so on as regards the format. Other complementary actions, such as the training of operators in the use of procedures, are described

  10. Controller tuning with evolutionary multiobjective optimization a holistic multiobjective optimization design procedure

    CERN Document Server

    Reynoso Meza, Gilberto; Sanchis Saez, Javier; Herrero Durá, Juan Manuel

    2017-01-01

    This book is devoted to Multiobjective Optimization Design (MOOD) procedures for controller tuning applications, by means of Evolutionary Multiobjective Optimization (EMO). It presents developments in tools, procedures and guidelines to facilitate this process, covering the three fundamental steps in the procedure: problem definition, optimization and decision-making. The book is divided into four parts. The first part, Fundamentals, focuses on the necessary theoretical background and provides specific tools for practitioners. The second part, Basics, examines a range of basic examples regarding the MOOD procedure for controller tuning, while the third part, Benchmarking, demonstrates how the MOOD procedure can be employed in several control engineering problems. The fourth part, Applications, is dedicated to implementing the MOOD procedure for controller tuning in real processes.

  11. A task based design procedure and modelling approached for industrial crystallization processes

    NARCIS (Netherlands)

    Menon, A.R.

    2006-01-01

    A synthesis-based approach to the design of crystallizers and industrial crystallization processes is introduced in this thesis. An ontology for a task-based design procedure has been developed which breaks the crystallization process into a subset of basic functions (physical tasks) which transform

  12. Procedure and information displays in advanced nuclear control rooms: experimental evaluation of an integrated design.

    Science.gov (United States)

    Chen, Yue; Gao, Qin; Song, Fei; Li, Zhizhong; Wang, Yufan

    2017-08-01

    In the main control rooms of nuclear power plants, operators frequently have to switch between procedure displays and system information displays. In this study, we proposed an operation-unit-based integrated design, which combines the two displays to facilitate the synthesis of information. We grouped actions that complete a single goal into operation units and showed these operation units on the displays of system states. In addition, we used different levels of visual salience to highlight the current unit and provided a list of execution history records. A laboratory experiment, with 42 students performing a simulated procedure to deal with unexpected high pressuriser level, was conducted to compare this design against an action-based integrated design and the existing separated-displays design. The results indicate that our operation-unit-based integrated design yields the best performance in terms of time and completion rate and helped more participants to detect unexpected system failures. Practitioner Summary: In current nuclear control rooms, operators frequently have to switch between procedure and system information displays. We developed an integrated design that incorporates procedure information into system displays. A laboratory study showed that the proposed design significantly improved participants' performance and increased the probability of detecting unexpected system failures.

  13. SUPPORTING THE INDUSTRY BY DEVELOPING A DESIGN GUIDANCE FOR COMPUTER-BASED PROCEDURES FOR FIELD WORKERS

    Energy Technology Data Exchange (ETDEWEB)

    Oxstrand, Johanna; LeBlanc, Katya

    2017-06-01

    The paper-based procedures currently used for nearly all activities in the commercial nuclear power industry have a long history of ensuring safe operation of the plants. However, there is potential to greatly increase efficiency and safety by improving how the human interacts with the procedures, which can be achieved through the use of computer-based procedures (CBPs). A CBP system offers a vast variety of improvements, such as context driven job aids, integrated human performance tools and dynamic step presentation. As a step toward the goal of improving procedure use performance, the U.S. Department of Energy Light Water Reactor Sustainability Program researchers, together with the nuclear industry, have been investigating the possibility and feasibility of replacing current paper-based procedures with CBPs. The main purpose of the CBP research conducted at the Idaho National Laboratory was to provide design guidance to the nuclear industry to be used by both utilities and vendors. After studying existing design guidance for CBP systems, the researchers concluded that the majority of the existing guidance is intended for control room CBP systems, and does not necessarily address the challenges of designing CBP systems for instructions carried out in the field. Further, the guidance is often presented on a high level, which leaves the designer to interpret what is meant by the guidance and how to specifically implement it. The authors developed a design guidance to provide guidance specifically tailored to instructions that are carried out in the field based.

  14. A procedure for multi-objective optimization of tire design parameters

    OpenAIRE

    Nikola Korunović; Miloš Madić; Miroslav Trajanović; Miroslav Radovanović

    2015-01-01

    The identification of optimal tire design parameters for satisfying different requirements, i.e. tire performance characteristics, plays an essential role in tire design. In order to improve tire performance characteristics, formulation and solving of multi-objective optimization problem must be performed. This paper presents a multi-objective optimization procedure for determination of optimal tire design parameters for simultaneous minimization of strain energy density at two distinctive zo...

  15. Review: Janice M. Morse & Linda Niehaus (2009). Mixed method design: principles and procedures

    OpenAIRE

    Öhlen, Joakim

    2010-01-01

    Mixed-Method-Designs, in denen quantitative und qualitative Methoden Verwendung finden, erfreuen sich zunehmender Beliebtheit für die Untersuchung komplexer Phänomene. Die vorliegende Besprechung beschäftigt sich in diesem Zusammenhang mit dem Buch "Mixed Method Design: Principles and Procedures" von Janice M. MORSE und Linda NIEHAUS, die für solche Designs Kern- und Ergänzungskomponenten zu identifizieren versuchen. Hierzu differenzieren sie zwischen Projekten, die einer eher deduktiven oder...

  16. Review: Janice M. Morse & Linda Niehaus (2009). Mixed Method Design: Principles and Procedures

    OpenAIRE

    Öhlen, Joakim

    2010-01-01

    Mixed method design related to the use of a combination of methods, usually quantitative and qualitative, is increasingly used for the investigation of complex phenomena. This review discusses the book, "Mixed Method Design: Principles and Procedures," by Janice M. MORSE and Linda NIEHAUS. A distinctive feature of their approach is the consideration of mixed methods design out of a core and a supplemental component. In order to define these components they emphasize the overall conceptual dir...

  17. Investigation of the Performance of Multidimensional Equating Procedures for Common-Item Nonequivalent Groups Design

    Directory of Open Access Journals (Sweden)

    Burcu ATAR

    2017-12-01

    Full Text Available In this study, the performance of the multidimensional extentions of Stocking-Lord, mean/mean, and mean/sigma equating procedures under common-item nonequivalent groups design was investigated. The performance of those three equating procedures was examined under the combination of various conditions including sample size, ability distribution, correlation between two dimensions, and percentage of anchor items in the test. Item parameter recovery was evaluated calculating RMSE (root man squared error and BIAS values. It was found that Stocking-Lord procedure provided the smaller RMSE and BIAS values for both item discrimination and item difficulty parameter estimates across most conditions.

  18. Risk-based performance indicators

    International Nuclear Information System (INIS)

    Azarm, M.A.; Boccio, J.L.; Vesely, W.E.; Lofgren, E.

    1987-01-01

    The purpose of risk-based indicators is to monitor plant safety. Safety is measured by monitoring the potential for core melt (core-melt frequency) and the public risk. Targets for these measures can be set consistent with NRC safety goals. In this process, the performance of safety systems, support systems, major components, and initiating events can be monitored using measures such as unavailability, failure or occurrence frequency. The changes in performance measures and their trends are determined from the time behavior of monitored measures by differentiation between stochastical and actual variations. Therefore, degradation, as well as improvement in the plant safety performance, can be determined. The development of risk-based performance indicators will also provide the means to trace a change in the safety measures to specific problem areas which are amenable to root cause analysis and inspection audits. In addition, systematic methods will be developed to identify specific improvement policies using the plant information system for the identified problem areas. The final product of the performance indicator project will be a methodology, and an integrated and validated set of software packages which, if properly interfaced with the logic model software of a plant, can monitor the plant performance as plant information is provided as input

  19. DECA -- The design change assistant: An application of expert systems concepts to procedure automation

    International Nuclear Information System (INIS)

    Brtis, J.S.

    1993-01-01

    Proceduralized engineering reviews required for nuclear power stations result in significant O ampersand M cost's. A method of streamlining procedural reviews (while improving their quality) is to computerize the procedures and associated checklists. DECA, the Design Change Assistant, is an expert system based program that is specifically designed for computerizing procedures. This program improves the effectiveness of engineers in performing engineering design reviews. DECA is a development shell, which allows the computerization of most types of engineering reviews. In addition to computerizing the decision making process, DECA makes it possible to call on electronic information, such as databases or text files, and makes them available to the user to assist in a review. DECA clearly demonstrates the benefits that can accrue by applying expert system technologies to engineering reviews. It results in the following: a well defined process, reduced user training in the use of procedures, improved quality of reviews, a streamlining of the review process through elimination of questions that are not applicable, and high quality documentation of reviews. DECA has been successfully applied to Commonwealth Edison's engineering design review checklists, and is currently in use by Commonwealth Edison

  20. A procedure for multi-objective optimization of tire design parameters

    Directory of Open Access Journals (Sweden)

    Nikola Korunović

    2015-04-01

    Full Text Available The identification of optimal tire design parameters for satisfying different requirements, i.e. tire performance characteristics, plays an essential role in tire design. In order to improve tire performance characteristics, formulation and solving of multi-objective optimization problem must be performed. This paper presents a multi-objective optimization procedure for determination of optimal tire design parameters for simultaneous minimization of strain energy density at two distinctive zones inside the tire. It consists of four main stages: pre-analysis, design of experiment, mathematical modeling and multi-objective optimization. Advantage of the proposed procedure is reflected in the fact that multi-objective optimization is based on the Pareto concept, which enables design engineers to obtain a complete set of optimization solutions and choose a suitable tire design. Furthermore, modeling of the relationships between tire design parameters and objective functions based on multiple regression analysis minimizes computational and modeling effort. The adequacy of the proposed tire design multi-objective optimization procedure has been validated by performing experimental trials based on finite element method.

  1. Design and drafting document control procedures for CPRF/ZTH experiment

    International Nuclear Information System (INIS)

    Pollat, L.L.; Kewish, R.W.

    1989-01-01

    This paper will present, in general, the control procedures for design approval, review, changes, and release of engineering documents. It will also discuss interface control for tasks so that possible design interference does not occur. A document control procedure to insure that design criteria are met and technical specifications translate into workable drawings was instituted to support the Confinement Physics Research Facility (CPRF/ZTH) construction program. Our goal, to eliminate any conflicts that might arise between various tasks as the final designs are developed, required tight control and up-to-date design information. Detailed procedure for reviews were instituted, since circumventing the process of design and drafting anywhere might have proven disastrous to the CPRF/ZTH program. Design is a process of translating technical requirements, according to established standards, into drawings that are usable for fabrication and assembly. Both the designer and engineer are responsible for adhering to standards that have been established by the Mechanical Engineering Section for the CPRF/ZTH program. 6 refs., 5 figs

  2. Rules and procedures for the design and operation of hazardous research equipment

    International Nuclear Information System (INIS)

    1978-12-01

    The manual has been prepared for use by research personnel involved in experiments at the Lawrence Berkeley Laboratory. It contains rules and procedures for the design, test, installation, and operation of hazardous research equipment. Sect. I contains such information as responsibility of experimenters for safety, descriptions of the various Laboratory safety organizations, and enumeration of various services available to experimenters at the Laboratory. Sect. II describes specific rules for the setup and operation of experimental equipment at the Laboratory. Sect. III gives detailed design criteria and procedures for equipment frequently encountered in the high energy physics laboratory

  3. Power analysis for multivariate and repeated measures designs: a flexible approach using the SPSS MANOVA procedure.

    Science.gov (United States)

    D'Amico, E J; Neilands, T B; Zambarano, R

    2001-11-01

    Although power analysis is an important component in the planning and implementation of research designs, it is often ignored. Computer programs for performing power analysis are available, but most have limitations, particularly for complex multivariate designs. An SPSS procedure is presented that can be used for calculating power for univariate, multivariate, and repeated measures models with and without time-varying and time-constant covariates. Three examples provide a framework for calculating power via this method: an ANCOVA, a MANOVA, and a repeated measures ANOVA with two or more groups. The benefits and limitations of this procedure are discussed.

  4. Displacement-Based Seismic Design Procedure for Framed Buildings with Dissipative Braces Part II: Numerical Results

    International Nuclear Information System (INIS)

    Mazza, Fabio; Vulcano, Alfonso

    2008-01-01

    For a widespread application of dissipative braces to protect framed buildings against seismic loads, practical and reliable design procedures are needed. In this paper a design procedure based on the Direct Displacement-Based Design approach is adopted, assuming the elastic lateral storey-stiffness of the damped braces proportional to that of the unbraced frame. To check the effectiveness of the design procedure, presented in an associate paper, a six-storey reinforced concrete plane frame, representative of a medium-rise symmetric framed building, is considered as primary test structure; this structure, designed in a medium-risk region, is supposed to be retrofitted as in a high-risk region, by insertion of diagonal braces equipped with hysteretic dampers. A numerical investigation is carried out to study the nonlinear static and dynamic responses of the primary and the damped braced test structures, using step-by-step procedures described in the associate paper mentioned above; the behaviour of frame members and hysteretic dampers is idealized by bilinear models. Real and artificial accelerograms, matching EC8 response spectrum for a medium soil class, are considered for dynamic analyses

  5. Seismic Retrofit of Reinforced Concrete Frame Buildings with Hysteretic Bracing Systems: Design Procedure and Behaviour Factor

    Directory of Open Access Journals (Sweden)

    Antonio Di Cesare

    2017-01-01

    Full Text Available This paper presents a design procedure to evaluate the mechanical characteristics of hysteretic Energy Dissipation Bracing (EDB systems for seismic retrofitting of existing reinforced concrete framed buildings. The proposed procedure, aiming at controlling the maximum interstorey drifts, imposes a maximum top displacement as function of the seismic demand and, if needed, regularizes the stiffness and strength of the building along its elevation. In order to explain the application of the proposed procedure and its capacity to involve most of the devices in the energy dissipation with similar level of ductility demand, a simple benchmark structure has been studied and nonlinear dynamic analyses have been performed. A further goal of this work is to propose a simplified approach for designing dissipating systems based on linear analysis with the application of a suitable behaviour factor, in order to achieve a widespread adoption of the passive control techniques. At this goal, the increasing of the structural performances due to the addition of an EDB system designed with the above-mentioned procedure has been estimated considering one thousand case studies designed with different combinations of the main design parameters. An analytical formulation of the behaviour factor for braced buildings has been proposed.

  6. A Systematic Procedure for the Generation of Cost-Minimized Designs

    DEFF Research Database (Denmark)

    Becker, Peter W.; Jarkler, Bjorn

    1972-01-01

    We present a procedure for the generation of cost-minimized designs of circuits and systems. Suppose a designer has decided upon the topology of his product. Also suppose he knows the cost and quality of the different grades of the N components required to implement the product. The designer...... then faces the following problem: How should he proceed to find the combination of grades that will give him the desired manufacturing yield at minimum product cost? We discuss the problem and suggest a policy by which the designer, with a reasonable computational effort, can find a set of ``good...

  7. Procedure for developing biological input for the design, location, or modification of water-intake structures

    Energy Technology Data Exchange (ETDEWEB)

    Neitzel, D.A.; McKenzie, D.H.

    1981-12-01

    To minimize adverse impact on aquatic ecosystems resulting from the operation of water intake structures, design engineers must have relevant information on the behavior, physiology and ecology of local fish and shellfish. Identification of stimulus/response relationships and the environmental factors that influence them is the first step in incorporating biological information in the design, location or modification of water intake structures. A procedure is presented in this document for providing biological input to engineers who are designing, locating or modifying a water intake structure. The authors discuss sources of stimuli at water intakes, historical approaches in assessing potential/actual impact and review biological information needed for intake design.

  8. A finite element based substructuring procedure for design analysis of large smart structural systems

    International Nuclear Information System (INIS)

    Ashwin, U; Raja, S; Dwarakanathan, D

    2009-01-01

    A substructuring based design analysis procedure is presented for large smart structural system using the Craig–Bampton method. The smart structural system is distinctively characterized as an active substructure, modelled as a design problem, and a passive substructure, idealized as an analysis problem. Furthermore, a novel thought has been applied by introducing the electro–elastic coupling into the reduction scheme to solve the global structural control problem in a local domain. As an illustration, a smart composite box beam with surface bonded actuators/sensors is considered, and results of the local to global control analysis are presented to show the potential use of the developed procedure. The present numerical scheme is useful for optimally designing the active substructures to study their locations, coupled structure–actuator interaction and provide a solution to the global design of large smart structural systems

  9. Risk-based decision analysis for groundwater operable units

    International Nuclear Information System (INIS)

    Chiaramonte, G.R.

    1995-01-01

    This document proposes a streamlined approach and methodology for performing risk assessment in support of interim remedial measure (IRM) decisions involving the remediation of contaminated groundwater on the Hanford Site. This methodology, referred to as ''risk-based decision analysis,'' also supports the specification of target cleanup volumes and provides a basis for design and operation of the groundwater remedies. The risk-based decision analysis can be completed within a short time frame and concisely documented. The risk-based decision analysis is more versatile than the qualitative risk assessment (QRA), because it not only supports the need for IRMs, but also provides criteria for defining the success of the IRMs and provides the risk-basis for decisions on final remedies. For these reasons, it is proposed that, for groundwater operable units, the risk-based decision analysis should replace the more elaborate, costly, and time-consuming QRA

  10. Design of the exhale airway stents for emphysema (EASE) trial : an endoscopic procedure for reducing hyperinflation

    NARCIS (Netherlands)

    Shah, Pallav L.; Slebos, Dirk-Jan; Cardoso, Paulo F. G.; Cetti, Edward J.; Sybrecht, Gerhard W.; Cooper, Joel D.

    2011-01-01

    Background: Airway Bypass is a catheter-based, bronchoscopic procedure in which new passageways are created that bypass the collapsed airways, enabling trapped air to exit the lungs. The Exhale Airway Stents for Emphysema (EASE) Trial was designed to investigate whether Exhale (R) Drug-Eluting

  11. Revisiting the Concepts "Approach", "Design" and "Procedure" According to the Richards and Rodgers (2011) Framework

    Science.gov (United States)

    Cumming, Brett

    2012-01-01

    The three concepts Approach, Design and Procedure as proposed in Rodgers' Framework are considered particularly effective as a framework in second language teaching with the specific aim of developing communication as well as for better understanding methodology in the use of communicative language use.

  12. 44 CFR 19.135 - Designation of responsible employee and adoption of grievance procedures.

    Science.gov (United States)

    2010-10-01

    ... BASIS OF SEX IN EDUCATION PROGRAMS OR ACTIVITIES RECEIVING FEDERAL FINANCIAL ASSISTANCE Introduction... 44 Emergency Management and Assistance 1 2010-10-01 2010-10-01 false Designation of responsible employee and adoption of grievance procedures. 19.135 Section 19.135 Emergency Management and Assistance...

  13. The quality of procedures to assess and credit prior learning: Implications for design.

    NARCIS (Netherlands)

    Joosten-ten Brinke, Desirée; Sluijsmans, Dominique; Brand-Gruwel, Saskia; Jochems, Wim

    2008-01-01

    Joosten-ten Brinke, D., Sluijsmans, D. M. A., Brand-Gruwel, S., & Jochems, W. M. G. (2008). The quality of procedures to assess and credit prior learning: Implications for design. Educational Research Review, 3, 51-65. doi:10.1016/j.edurev.2007.08.001.

  14. 24 CFR 3285.306 - Design procedures for concrete block piers.

    Science.gov (United States)

    2010-04-01

    ... piers less than 36 inches high are permitted to be constructed of single, open, or closed-cell concrete... shown in Figure A to this section. (3) The concrete blocks must be stacked with their hollow cells... 24 Housing and Urban Development 5 2010-04-01 2010-04-01 false Design procedures for concrete...

  15. 13 CFR 113.135 - Designation of responsible employee and adoption of grievance procedures.

    Science.gov (United States)

    2010-01-01

    ... employee and adoption of grievance procedures. 113.135 Section 113.135 Business Credit and Assistance SMALL BUSINESS ADMINISTRATION NONDISCRIMINATION IN FINANCIAL ASSISTANCE PROGRAMS OF SBA-EFFECTUATION OF POLICIES... Programs or Activities Receiving Federal Financial Assistance Introduction § 113.135 Designation of...

  16. Design Procedure for High-Speed PM Motors Aided by Optimization Algorithms

    Directory of Open Access Journals (Sweden)

    Francesco Cupertino

    2018-02-01

    Full Text Available This paper considers the electromagnetic and structural co-design of superficial permanent magnet synchronous machines for high-speed applications, with the aid of a Pareto optimization procedure. The aim of this work is to present a design procedure for the afore-mentioned machines that relies on the combined used of optimization algorithms and finite element analysis. The proposed approach allows easy analysis of the results and a lowering of the computational burden. The proposed design method is presented through a practical example starting from the specifications of an aeronautical actuator. The design procedure is based on static finite element simulations for electromagnetic analysis and on analytical formulas for structural design. The final results are validated through detailed transient finite element analysis to verify both electromagnetic and structural performance. The step-by-step presentation of the proposed design methodology allows the reader to easily adapt it to different specifications. Finally, a comparison between a distributed-winding (24 slots and a concentrated-winding (6 slots machine is presented demonstrating the advantages of the former winding arrangement for high-speed applications.

  17. Risk based limits for Operational Safety Requirements

    International Nuclear Information System (INIS)

    Cappucci, A.J. Jr.

    1993-01-01

    OSR limits are designed to protect the assumptions made in the facility safety analysis in order to preserve the safety envelope during facility operation. Normally, limits are set based on ''worst case conditions'' without regard to the likelihood (frequency) of a credible event occurring. In special cases where the accident analyses are based on ''time at risk'' arguments, it may be desirable to control the time at which the facility is at risk. A methodology has been developed to use OSR limits to control the source terms and the times these source terms would be available, thus controlling the acceptable risk to a nuclear process facility. The methodology defines a new term ''gram-days''. This term represents the area under a source term (inventory) vs time curve which represents the risk to the facility. Using the concept of gram-days (normalized to one year) allows the use of an accounting scheme to control the risk under the inventory vs time curve. The methodology results in at least three OSR limits: (1) control of the maximum inventory or source term, (2) control of the maximum gram-days for the period based on a source term weighted average, and (3) control of the maximum gram-days at the individual source term levels. Basing OSR limits on risk based safety analysis is feasible, and a basis for development of risk based limits is defensible. However, monitoring inventories and the frequencies required to maintain facility operation within the safety envelope may be complex and time consuming

  18. Risk-based remediation: Approach and application

    International Nuclear Information System (INIS)

    Frishmuth, R.A.; Benson, L.A.

    1995-01-01

    The principle objective of remedial actions is to protect human health and the environment. Risk assessments are the only defensible tools available to demonstrate to the regulatory community and public that this objective can be achieved. Understanding the actual risks posed by site-related contamination is crucial to designing cost-effective remedial strategies. All to often remedial actions are overdesigned, resulting in little to no increase in risk reduction while increasing project cost. Risk-based remedial actions have recently been embraced by federal and state regulators, industry, government, the scientific community, and the public as a mechanism to implement rapid and cost-effective remedial actions. Emphasizing risk reduction, rather than adherence to ambiguous and generic standards, ensures that only remedial actions required to protect human health and the environment at a particular site are implemented. Two sites are presented as case studies on how risk-based approaches are being used to remediate two petroleum hydrocarbon contaminated sites. The sites are located at two US Air Force Bases, Wurtsmith Air Force Base (AFB) in Oscoda, Michigan and Malmstrom AFB in Great Falls, Montana

  19. A design procedure for the phase-controlled parallel-loaded resonant inverter

    Science.gov (United States)

    King, Roger J.

    1989-01-01

    High-frequency-link power conversion and distribution based on a resonant inverter (RI) has been recently proposed. The design of several topologies is reviewed, and a simple approximate design procedure is developed for the phase-controlled parallel-loaded RI. This design procedure seeks to ensure the benefits of resonant conversion and is verified by data from a laboratory 2.5 kVA, 20-kHz converter. A simple phasor analysis is introduced as a useful approximation for design purposes. The load is considered to be a linear impedance (or an ac current sink). The design procedure is verified using a 2.5-kVA 20-kHz RI. Also obtained are predictable worst-case ratings for each component of the resonant tank circuit and the inverter switches. For a given load VA requirement, below-resonance operation is found to result in a significantly lower tank VA requirement. Under transient conditions such as load short-circuit, a reversal of the expected commutation sequence is possible.

  20. Revised guideline for the approval procedure of package designs in Germany

    International Nuclear Information System (INIS)

    Nitsche, F.; Roedel, R.

    2004-01-01

    The IAEA Regulations for the Safe Transport of Radioactive Material, TS-R-1 are applied in Germany through the implementation of the Dangerous Goods Transport Regulations for class 7 of the International Modal Organisations (ADR, RID, IMDG-Code, ICAO-TI). Based on this the approval procedures for packages designs applied in Germany are in compliance with the provisions of TS-R-1. The Guideline R 003 issued by the Ministry of Transport, Building and Housing (BMVBW) in 1991 is the basis for the package design approval procedures in Germany. This Guideline has been reviewed and revised to reflect latest developments in the regulations as well as in the regulatory practice. In particular it has been extended to the approval procedures of Type C packages, packages subject to transitional arrangements, special form and low dispersible radioactive material and provides more detailed information to the applicant about the requested documentation. Publication of this revised guideline has been delayed but it is expected to take place in October 2004. The paper gives an overview about the main parts and provisions of this revised Guideline R 003 with the focus on package design approval procedures

  1. Contribution of the ergonomic analysis to the improvement of the design of operating procedures in nuclear power plants

    International Nuclear Information System (INIS)

    Dien, Y.; Montmayeul, R.

    1992-11-01

    The design of operating procedures for continuous processes is much too often based on implicit assumptions both concerning the operators and the operating conditions that must be dealt with. The merit of the ergonomic approach to the design of procedures is to take account of the way the various operators actually use operating procedures. The actual use is determined from the analysis of on-site operation (normal and incident operating conditions) and the analysis of full-scale simulators tests (incident operating conditions). The introduction of the ergonomic approach in the procedure design results in new design principles being proposed

  2. Progress of Design Improvements for APR1400 Computerized Procedure System from HFE V and V results and Design Experience

    International Nuclear Information System (INIS)

    Lee, Sungjin; Seong, Nokyu

    2015-01-01

    This study shows major already improved design features from the above three processes and a design proposal for to-be-improving items. APR1400 CPS has been verified and validated by the HFE process, internal design review and site acceptance tests. APR1400 Computerized Procedure System (CPS) has been applied to Shin-Kori Nuclear Power Plant (SKN) 3 and 4 units, Shin-Hanul Nuclear Power Plant (SHN) 1 and 2 units and Baraka Nuclear Power Plant (BNPP) 1, 2, 3 and 4 units. Since APR1400 CPS is a first-of-a-kind (FOAK) human machine interface (HMI) for executing a computerized procedure in the nuclear power plant's main control room in South Korea, it has been continuously improved through a) the human factor engineering (HFE) verification and validation (V and V), b) the internal design review and c) prototype tests. Human engineering discrepancies (HEDs) can be identified by the HFE V and V activity. Some HEDs of APR1400 CPS for SKN 3 and 4 and SHN 1 and 2 have been adopted as a role of design improvement in the CPS system while others were regarded as an operator training requirement or part of task contents. Various requests for improving the CPS have been collected from those results. A HMI system should be improved continuously for removing potential defects. Some of introduced design features in this paper has been adopted for APR1400 nuclear power plants. Some of them are under the review in the CPS design team of KHNP

  3. Experimental design technique applied to the validation of an instrumental Neutron Activation Analysis procedure

    International Nuclear Information System (INIS)

    Santos, Uanda Paula de M. dos; Moreira, Edson Gonçalves

    2017-01-01

    In this study optimization of procedures and standardization of Instrumental Neutron Activation Analysis (INAA) method were carried out for the determination of the elements bromine, chlorine, magnesium, manganese, potassium, sodium and vanadium in biological matrix materials using short irradiations at a pneumatic system. 2 k experimental designs were applied for evaluation of the individual contribution of selected variables of the analytical procedure in the final mass fraction result. The chosen experimental designs were the 2 3 and the 2 4 , depending on the radionuclide half life. Different certified reference materials and multi-element comparators were analyzed considering the following variables: sample decay time, irradiation time, counting time and sample distance to detector. Comparator concentration, sample mass and irradiation time were maintained constant in this procedure. By means of the statistical analysis and theoretical and experimental considerations, it was determined the optimized experimental conditions for the analytical methods that will be adopted for the validation procedure of INAA methods in the Neutron Activation Analysis Laboratory (LAN) of the Research Reactor Center (CRPq) at the Nuclear and Energy Research Institute (IPEN /CNEN-SP). Optimized conditions were estimated based on the results of z-score tests, main effect, interaction effects and better irradiation conditions. (author)

  4. Experimental design technique applied to the validation of an instrumental Neutron Activation Analysis procedure

    Energy Technology Data Exchange (ETDEWEB)

    Santos, Uanda Paula de M. dos; Moreira, Edson Gonçalves, E-mail: uandapaula@gmail.com, E-mail: emoreira@ipen.br [Instituto de Pesquisas Energéticas e Nucleares (IPEN/CNEN-SP), São Paulo, SP (Brazil)

    2017-07-01

    In this study optimization of procedures and standardization of Instrumental Neutron Activation Analysis (INAA) method were carried out for the determination of the elements bromine, chlorine, magnesium, manganese, potassium, sodium and vanadium in biological matrix materials using short irradiations at a pneumatic system. 2{sup k} experimental designs were applied for evaluation of the individual contribution of selected variables of the analytical procedure in the final mass fraction result. The chosen experimental designs were the 2{sup 3} and the 2{sup 4}, depending on the radionuclide half life. Different certified reference materials and multi-element comparators were analyzed considering the following variables: sample decay time, irradiation time, counting time and sample distance to detector. Comparator concentration, sample mass and irradiation time were maintained constant in this procedure. By means of the statistical analysis and theoretical and experimental considerations, it was determined the optimized experimental conditions for the analytical methods that will be adopted for the validation procedure of INAA methods in the Neutron Activation Analysis Laboratory (LAN) of the Research Reactor Center (CRPq) at the Nuclear and Energy Research Institute (IPEN /CNEN-SP). Optimized conditions were estimated based on the results of z-score tests, main effect, interaction effects and better irradiation conditions. (author)

  5. Risk-based regulation: Challenges and opportunities

    International Nuclear Information System (INIS)

    Bari, R.A.

    1995-01-01

    Over the last twenty years, man has witnessed a gradual but steady movement toward increased usage of risk-based methods and results in the regulatory process. The ''risk perspective'' as a supportive view to existing (non-risk-based or deterministic) information used in decision making has a firm foothold now in most countries that regulate nuclear power. Furthermore, in the areas outside the nuclear power field, such as health risk assessment, risk-based information is used increasingly to make decisions on potential impacts of chemical, biological, and radiological exposures. Some of the principal concepts and issues that are pertinent to risk-based regulation are reviewed. There is a growing interest in most countries in the use of risk-based methods and results to facilitate decision-making associated with regulatory processes. A summary is presented of the challenges and opportunities related to expanded use of risk-based regulation

  6. Risk based surveillance for vector borne diseases

    DEFF Research Database (Denmark)

    Bødker, Rene

    of samples and hence early detection of outbreaks. Models for vector borne diseases in Denmark have demonstrated dramatic variation in outbreak risk during the season and between years. The Danish VetMap project aims to make these risk based surveillance estimates available on the veterinarians smart phones...... in Northern Europe. This model approach may be used as a basis for risk based surveillance. In risk based surveillance limited resources for surveillance are targeted at geographical areas most at risk and only when the risk is high. This makes risk based surveillance a cost effective alternative...... sample to a diagnostic laboratory. Risk based surveillance models may reduce this delay. An important feature of risk based surveillance models is their ability to continuously communicate the level of risk to veterinarians and hence increase awareness when risk is high. This is essential for submission...

  7. Design flood hydrograph estimation procedure for small and fully-ungauged basins

    Science.gov (United States)

    Grimaldi, S.; Petroselli, A.

    2013-12-01

    The Rational Formula is the most applied equation in practical hydrology due to its simplicity and the effective compromise between theory and data availability. Although the Rational Formula is affected by several drawbacks, it is reliable and surprisingly accurate considering the paucity of input information. However, after more than a century, the recent computational, theoretical, and large-scale monitoring progresses compel us to try to suggest a more advanced yet still empirical procedure for estimating peak discharge in small and ungauged basins. In this contribution an alternative empirical procedure (named EBA4SUB - Event Based Approach for Small and Ungauged Basins) based on the common modelling steps: design hyetograph, rainfall excess, and rainfall-runoff transformation, is described. The proposed approach, accurately adapted for the fully-ungauged basin condition, provides a potentially better estimation of the peak discharge, a design hydrograph shape, and, most importantly, reduces the subjectivity of the hydrologist in its application.

  8. Procedure guide of design, construction of prototypes, calibration and sure operation of nucleonic control systems

    International Nuclear Information System (INIS)

    Banados Perez, H.; Griffith Martinez, J.; Desdin Garcia, L.F.; Rodriguez Cardona, R.L.; Molina, G.; Sebastian Calvo, C.

    1999-01-01

    This Guide was elaborated in the mark of the project RLA/8/024 ARCAL XLII 'Industrial Applications of the Tracer Technology and Nucleonic Control Systems'. Its objective is to establish the approaches for the design, the construction, the selection and the procedures for the sure operation of the Nucleonic Control Systems (NCS) in the industry. The NCS is used to control processes to high speeds, materials with extreme conditions or with noxious chemical properties, susceptible materials of being damaged by contact and packed products. In this document is defined the scope of the procedure. The SCN are classified according to: type of radiations, the mobility of the components, the degree of the beams collimation; and in function of the security. The design and construction criteria of the nuclear meters and of the systems of control nucleonic are exposed

  9. Use of virtual steam generator cassette for tube spatial design and SGC assembling procedure

    International Nuclear Information System (INIS)

    Kim, Y. W.; Kim, J. I.; Ji, S. K.

    2003-01-01

    A method of determining spatial arrangement of tube connection and assembling procedure of once-through helical steam generator cassette utilizing three dimensional virtual steam generator cassette has been developed on the basis of recent 3-D modelling technology. One ends of the steam generator tubes are connected to the module feed water header and the other sides are connected to the module steam header. Due to the complex geometry of tube arrangement, it is very difficult to connect the tubes to the module headers without the help of a physical engineering mock up. A comparative study has been performed at each design step for the tube arrangement and heat transfer area. Heat transfer area computed from thermal sizing was 4% less than that of measured. Heat transfer area calculated from the virtual steam generator cassette mock up has only 0.2% difference with that of measured. Assembling procedure of the steam generator cassette also, can be developed in the design stage

  10. An analytical inductor design procedure for three-phase PWM converters in power factor correction applications

    DEFF Research Database (Denmark)

    Kouchaki, Alireza; Niroumand, Farideh Javidi; Haase, Frerk

    2015-01-01

    This paper presents an analytical method for designing the inductor of three-phase power factor correction converters (PFCs). The complex behavior of the inductor current complicates the inductor design procedure as well as the core loss and copper loss calculations. Therefore, this paper analyze...... to calculate the core loss in the PFC application. To investigate the impact of the dc link voltage level, two inductors for different dc voltage levels are designed and the results are compared.......This paper presents an analytical method for designing the inductor of three-phase power factor correction converters (PFCs). The complex behavior of the inductor current complicates the inductor design procedure as well as the core loss and copper loss calculations. Therefore, this paper analyzes...... circuit is used to provide the inductor current harmonic spectrum. Therefore, using the harmonic spectrum, the low and high frequency copper losses are calculated. The high frequency minor B-H loops in one switching cycle are also analyzed. Then, the loss map provided by the measurement setup is used...

  11. Using mixed methods effectively in prevention science: designs, procedures, and examples.

    Science.gov (United States)

    Zhang, Wanqing; Watanabe-Galloway, Shinobu

    2014-10-01

    There is growing interest in using a combination of quantitative and qualitative methods to generate evidence about the effectiveness of health prevention, services, and intervention programs. With the emerging importance of mixed methods research across the social and health sciences, there has been an increased recognition of the value of using mixed methods for addressing research questions in different disciplines. We illustrate the mixed methods approach in prevention research, showing design procedures used in several published research articles. In this paper, we focused on two commonly used mixed methods designs: concurrent and sequential mixed methods designs. We discuss the types of mixed methods designs, the reasons for, and advantages of using a particular type of design, and the procedures of qualitative and quantitative data collection and integration. The studies reviewed in this paper show that the essence of qualitative research is to explore complex dynamic phenomena in prevention science, and the advantage of using mixed methods is that quantitative data can yield generalizable results and qualitative data can provide extensive insights. However, the emphasis of methodological rigor in a mixed methods application also requires considerable expertise in both qualitative and quantitative methods. Besides the necessary skills and effective interdisciplinary collaboration, this combined approach also requires an open-mindedness and reflection from the involved researchers.

  12. Robust parameter design for integrated circuit fabrication procedure with respect to categorical characteristic

    International Nuclear Information System (INIS)

    Sohn, S.Y.

    1999-01-01

    We consider a robust parameter design of the process for forming contact windows in complementary metal-oxide semiconductor circuits. Robust design is often used to find the optimal levels of process conditions which would provide the output of consistent quality as close to a target value. In this paper, we analyze the results of the fractional factorial design of nine factors: mask dimension, viscosity, bake temperature, spin speed, bake time, aperture, exposure time, developing time, etch time, where the outcome of the experiment is measured in terms of a categorized window size with five categories. Random effect analysis is employed to model both the mean and variance of categorized window size as functions of some controllable factors as well as random errors. Empirical Bayes' procedures are then utilized to fit both the models, and to eventually find the robust design of CMOS circuit process by means of a Bootstrap resampling approach

  13. Tools and procedures for a “maintenance oriented” design for buildings of worship

    Directory of Open Access Journals (Sweden)

    Cinzia Talamo

    2013-10-01

    Full Text Available The paper describes the results, achieved in the first year, of a three years research dealing with the themes connected with the methods and the tools for planned maintenance and concerning the proposal of a system of supports for a design “maintenance oriented”. The starting hypothesis is that most of maintenance problems emerging during the life time of a building are due to a lack of attention towards the use phase that both clients and designers demonstrate. Starting from this point of view the aim of the research was to develop and to check a system of supports, useful both for clients and for designs of buildings of worship, consisting in guide lines, procedures and evaluation tools, graduate according to the different steps of design process and carried out in order to assume and to verify the requirement of maintainability.

  14. Robust parameter design for integrated circuit fabrication procedure with respect to categorical characteristic

    Energy Technology Data Exchange (ETDEWEB)

    Sohn, S.Y

    1999-12-01

    We consider a robust parameter design of the process for forming contact windows in complementary metal-oxide semiconductor circuits. Robust design is often used to find the optimal levels of process conditions which would provide the output of consistent quality as close to a target value. In this paper, we analyze the results of the fractional factorial design of nine factors: mask dimension, viscosity, bake temperature, spin speed, bake time, aperture, exposure time, developing time, etch time, where the outcome of the experiment is measured in terms of a categorized window size with five categories. Random effect analysis is employed to model both the mean and variance of categorized window size as functions of some controllable factors as well as random errors. Empirical Bayes' procedures are then utilized to fit both the models, and to eventually find the robust design of CMOS circuit process by means of a Bootstrap resampling approach.

  15. Application of the risk based inspection in chemical and nuclear installations: a critical evaluation

    International Nuclear Information System (INIS)

    Sousa, Anna Leticia Barbosa de

    2004-01-01

    Risk-based Inspection (RBI) has arisen as an opportunity for the industry to give a specific treatment to items as equipment integrity, failures consequences and the level of risk of each piece of equipment in the inspection programs definitions. Risk-based inspection programs are replacing the traditional ones based on prescriptive requirements, for both the oil and nuclear industries. The aim of this thesis is to demonstrate how the nuclear industry has gotten over several difficulties in implementing risk-based programs considering that its safety design and regulations have traditionally been based on deterministic and prescriptive criteria and requirements. During the development of the work, the study has shown how the absence of a rigid regulation favored the dissemination of RBI diffusion in the oil industry, mainly in the USA, where such industries do not face those difficulties found by the European plants, as long as it is well known that in Europe there are complex interrelations among documents from different countries with diversity of regulation procedures. (author)

  16. Risk based inspection for atmospheric storage tank

    Science.gov (United States)

    Nugroho, Agus; Haryadi, Gunawan Dwi; Ismail, Rifky; Kim, Seon Jin

    2016-04-01

    Corrosion is an attack that occurs on a metallic material as a result of environment's reaction.Thus, it causes atmospheric storage tank's leakage, material loss, environmental pollution, equipment failure and affects the age of process equipment then finally financial damage. Corrosion risk measurement becomesa vital part of Asset Management at the plant for operating any aging asset.This paper provides six case studies dealing with high speed diesel atmospheric storage tank parts at a power plant. A summary of the basic principles and procedures of corrosion risk analysis and RBI applicable to the Process Industries were discussed prior to the study. Semi quantitative method based onAPI 58I Base-Resource Document was employed. The risk associated with corrosion on the equipment in terms of its likelihood and its consequences were discussed. The corrosion risk analysis outcome used to formulate Risk Based Inspection (RBI) method that should be a part of the atmospheric storage tank operation at the plant. RBI gives more concern to inspection resources which are mostly on `High Risk' and `Medium Risk' criteria and less on `Low Risk' shell. Risk categories of the evaluated equipment were illustrated through case study analysis outcome.

  17. The guideline and practical procedures for earthquake-resistant design of nuclear power plants in Japan

    International Nuclear Information System (INIS)

    Watabe, M.

    1985-01-01

    The Guideline for the aseismic design of nuclear reactor facilities, revised in 1981, is introduced. The basic philosophy entails structural integrity against a major earthquake, rigid structure for less deformation and foundation on rock. The classification of facilities is then explained. Some practical examples are tabulated. In the light of the above classifications, evaluation procedures for aseismic design are defined. Design basis earthquake ground motions, S1 and S2, are defined. S1 is the maximum possible earthquake ground motion, while S2 is the maximum credible one. The relation between active faults and S1, S2 motions is explained, seismic forces induced by S1 and S2 are expressed in terms of response spectra. Static seismic coefficient procedures are also applied to evaluate seismic forces, as a minimum guide-line based on dynamic analysis. Combinations of seismic forces and allowable limits are then explained. In the second part of the paper, seismic analysis for reactor buildings as a part of design practice is outlined. There are three major key points in practical aseismic design. The first one is input design earthquake motions, in which soil/foundation interaction problems are also included. In practice, ground motions at the free field rock surface have to be convoluted or deconvoluted to obtain base rock motions, which are applied to estimate input design earthquake motions by way of finite element analysis or a lumped mass lattice model. Also introduced is dynamic modelling of the reactor building with its non-linear behaviour represented by plastic deformation of reinforced concrete members as well as by uplift characteristics of foundations. Then an evaluation of aseismic safety is introduced. (author)

  18. An Application of Graphical Approach to Construct Multiple Testing Procedure in a Hypothetical Phase III Design

    Directory of Open Access Journals (Sweden)

    Naitee eTing

    2014-01-01

    Full Text Available Many multiple testing procedures (MTP have been developed in recent years. Among these new procedures, the graphical approach is flexible and easy to communicate with non-statisticians. A hypothetical Phase III clinical trial design is introduced in this manuscript to demonstrate how graphical approach can be applied in clinical product development. In this design, an active comparator is used. It is thought that this test drug under development could potentially be superior to this comparator. For comparison of efficacy, the primary endpoint is well established and widely accepted by regulatory agencies. However, an important secondary endpoint based on Phase II findings looks very promising. The target dose may have a good opportunity to deliver superiority to the comparator. Furthermore, a lower dose is included in case the target dose may demonstrate potential safety concerns. This Phase III study is designed as a non-inferiority trial with two doses, and two endpoints. This manuscript will illustrate how graphical approach is applied to this design in handling multiple testing issues.

  19. Biosafety Procedure for Safe Handling of Genetically Modified Plant Materials in Bio Design Facility

    International Nuclear Information System (INIS)

    Zaiton Ahmad; Shuhaimi Shamsudin; Mohamed Najli Mohamed Yasin; Affrida Abu Hassan; Mohd Zaid Hassan; Rusli Ibrahim

    2015-01-01

    Bio Design Facility is the specifically designed glass house for propagation, screening and analysis of high quality plant varieties developed through biotechnology or a combination of nuclear technology and biotechnology. High quality plant varieties especially genetically modified plants (GMO) require a special glass house facility for propagation and screening to isolate them from cross-pollinating with wild type varieties in surrounding ecosystem, and for carrying out evaluation of possible risks of the plants to human, animal and environment before they are proven safe for field trials or commercial release. This facility which was developed under the Ninth Malaysia Plan is classified as the Plant Containment Level 2 and is compliance with the bio safety regulations and guidance for the safe release of GMO according to Malaysian Bio safety Act 2007. Bio Design Facility is fully operational since 2010 and in 2012, it has also been certified as the glass house for post-entry quarantine by The Department of Agriculture. This paper summarizes the bio safety procedure for a safe, controlled and contained growing and evaluation of GMO in Bio Design Facility. This procedure covers the physical (containment and equipment's) and operational (including responsibility, code of practice, growing, decontamination and disposal of plant materials, emergency and contingency plan) aspects of the facility. (author)

  20. Procedure for the design of Information Management Systems in Production Cooperatives

    Directory of Open Access Journals (Sweden)

    Maidelyn Díaz Pérez

    2018-02-01

    Full Text Available The information management systems of the entrepreneurial organizations have been conceived that the fulfillment of the strategic objectives depend to a large extent on the good performance of several informative tasks such as obtaining information from the environment, identifying and representing the information flows of the processes , the structuring of operational and functional data, the internal management of knowledge, etc. But in turn, the achievement of these actions depends on there being a group of procedures that lead to the adequate standardization of the data. In spite of the fact that these procedures are essential for the proper functioning of any system, and that, for the most part, the quality, reliability and pertinence of the information that is managed depends on them, it is not usual for them to exist in cooperative organizations. even in most cases they are not written. The objective of this research is to establish a procedure to design an information management system for research in a production cooperative linked directly to research. The result obtained allows identifying, defining and structuring the data required by the system to operate efficiently, as well as articulate the different components that should integrate it in its systemic development. This procedure facilitates the efficient management of operative, functional and strategic information of the different processes of a cooperative in correspondence with its strategic objectives.

  1. Study on design procedure of three-dimensional building base isolation system using thick rubber bearing

    International Nuclear Information System (INIS)

    Yabana, Shuichi; Matsuda, Akihiro

    2003-01-01

    In this study, design procedure on three-dimensional base isolation system is developed. Base isolation system proposed by CRIEPI uses thick rubber bearing and damper as isolation device. As for thick rubber bearings, design formula for evaluating vertical stiffness is proposed, and design conditions regarding size and vertical pressure are investigated. Figure-U type lead damper is proposed as three-dimensional damper and by loading tests its mechanical characteristics is evaluated. The concept of multi-layered interconnected rubber bearing, which is advantageous over large scale bearing in manufacturability, is proposed and its good performance is confirmed by the loading test. Through the response analyses, it is shown the rocking response of the proposed three-dimensional base isolation system is very small and not influential to the system, and the reduction of the vertical response is attained using the proposed isolation device. (author)

  2. Risk-based maintenance-Techniques and applications

    International Nuclear Information System (INIS)

    Arunraj, N.S.; Maiti, J.

    2007-01-01

    Plant and equipment, however well designed, will not remain safe or reliable if it is not maintained. The general objective of the maintenance process is to make use of the knowledge of failures and accidents to achieve the possible safety with the lowest possible cost. The concept of risk-based maintenance was developed to inspect the high-risk components usually with greater frequency and thoroughness and to maintain in a greater manner, to achieve tolerable risk criteria. Risk-based maintenance methodology provides a tool for maintenance planning and decision making to reduce the probability of failure of equipment and the consequences of failure. In this paper, the risk analysis and risk-based maintenance methodologies were identified and classified into suitable classes. The factors affecting the quality of risk analysis were identified and analyzed. The applications, input data and output data were studied to understand their functioning and efficiency. The review showed that there is no unique way to perform risk analysis and risk-based maintenance. The use of suitable techniques and methodologies, careful investigation during the risk analysis phase, and its detailed and structured results are necessary to make proper risk-based maintenance decisions

  3. Generic procedure for designing and implementing plan management systems for space science missions operations

    Science.gov (United States)

    Chaizy, P. A.; Dimbylow, T. G.; Allan, P. M.; Hapgood, M. A.

    2011-09-01

    This paper is one of the components of a larger framework of activities whose purpose is to improve the performance and productivity of space mission systems, i.e. to increase both what can be achieved and the cost effectiveness of this achievement. Some of these activities introduced the concept of Functional Architecture Module (FAM); FAMs are basic blocks used to build the functional architecture of Plan Management Systems (PMS). They also highlighted the need to involve Science Operations Planning Expertise (SOPE) during the Mission Design Phase (MDP) in order to design and implement efficiently operation planning systems. We define SOPE as the expertise held by people who have both theoretical and practical experience in operations planning, in general, and in space science operations planning in particular. Using ESA's methodology for studying and selecting science missions we also define the MDP as the combination of the Mission Assessment and Mission Definition Phases. However, there is no generic procedure on how to use FAMs efficiently and systematically, for each new mission, in order to analyse the cost and feasibility of new missions as well as to optimise the functional design of new PMS; the purpose of such a procedure is to build more rapidly and cheaply such PMS as well as to make the latter more reliable and cheaper to run. This is why the purpose of this paper is to provide an embryo of such a generic procedure and to show that the latter needs to be applied by people with SOPE during the MDP. The procedure described here proposes some initial guidelines to identify both the various possible high level functional scenarii, for a given set of possible requirements, and the information that needs to be associated with each scenario. It also introduces the concept of catalogue of generic functional scenarii of PMS for space science missions. The information associated with each catalogued scenarii will have been identified by the above procedure and

  4. Design procedure for pollutant loadings and impacts for highway stormwater runoff (Macintosh version) (for microcomputers). Software

    International Nuclear Information System (INIS)

    1990-01-01

    The interactive computer program was developed to make a user friendly procedure for the personal computer for calculations and guidance to make estimations of pollutant loadings and impacts from highway stormwater runoff which are presented in the Publication FHWA-RD-88-006, Pollutant Loadings and Impacts from Highway Stormwater Runoff, Volume I: Design Procedure. The computer program is for the evaluation of the water quality impact from highway stormwater runoff to a lake or a stream from a specific highway site considering the necessary rainfall data and geographic site situation. The evaluation considers whether or not the resulting water quality conditions can cause a problem as indicated by the violations of water quality criteria or objectives

  5. Design procedure for pollutant loadings and impacts for highway stormwater runoff (IBM version) (for microcomputers). Software

    International Nuclear Information System (INIS)

    1990-01-01

    The interactive computer program was developed to make a user friendly procedure for the personal computer for calculations and guidance to make estimations of pollutant loadings and impacts from highway stormwater runoff which are presented in the Publication FHWA-RD-88-006, Pollutant Loadings and Impacts from Highway Stormwater Runoff, Volume I: Design Procedure. The computer program is for the evaluation of the water quality impact from highway stormwater runoff to a lake or a stream from a specific highway site considering the necessary rainfall data and geographic site situation. The evaluation considers whether or not the resulting water quality conditions can cause a problem as indicated by the violations of water quality criteria or objectives

  6. Application of a statistical thermal design procedure to evaluate the PWR DNBR safety analysis limits

    International Nuclear Information System (INIS)

    Robeyns, J.; Parmentier, F.; Peeters, G.

    2001-01-01

    In the framework of safety analysis for the Belgian nuclear power plants and for the reload compatibility studies, Tractebel Energy Engineering (TEE) has developed, to define a 95/95 DNBR criterion, a statistical thermal design method based on the analytical full statistical approach: the Statistical Thermal Design Procedure (STDP). In that methodology, each DNBR value in the core assemblies is calculated with an adapted CHF (Critical Heat Flux) correlation implemented in the sub-channel code Cobra for core thermal hydraulic analysis. The uncertainties of the correlation are represented by the statistical parameters calculated from an experimental database. The main objective of a sub-channel analysis is to prove that in all class 1 and class 2 situations, the minimum DNBR (Departure from Nucleate Boiling Ratio) remains higher than the Safety Analysis Limit (SAL). The SAL value is calculated from the Statistical Design Limit (SDL) value adjusted with some penalties and deterministic factors. The search of a realistic value for the SDL is the objective of the statistical thermal design methods. In this report, we apply a full statistical approach to define the DNBR criterion or SDL (Statistical Design Limit) with the strict observance of the design criteria defined in the Standard Review Plan. The same statistical approach is used to define the expected number of rods experiencing DNB. (author)

  7. Development of multidisciplinary design optimization procedures for smart composite wings and turbomachinery blades

    Science.gov (United States)

    Jha, Ratneshwar

    Multidisciplinary design optimization (MDO) procedures have been developed for smart composite wings and turbomachinery blades. The analysis and optimization methods used are computationally efficient and sufficiently rigorous. Therefore, the developed MDO procedures are well suited for actual design applications. The optimization procedure for the conceptual design of composite aircraft wings with surface bonded piezoelectric actuators involves the coupling of structural mechanics, aeroelasticity, aerodynamics and controls. The load carrying member of the wing is represented as a single-celled composite box beam. Each wall of the box beam is analyzed as a composite laminate using a refined higher-order displacement field to account for the variations in transverse shear stresses through the thickness. Therefore, the model is applicable for the analysis of composite wings of arbitrary thickness. Detailed structural modeling issues associated with piezoelectric actuation of composite structures are considered. The governing equations of motion are solved using the finite element method to analyze practical wing geometries. Three-dimensional aerodynamic computations are performed using a panel code based on the constant-pressure lifting surface method to obtain steady and unsteady forces. The Laplace domain method of aeroelastic analysis produces root-loci of the system which gives an insight into the physical phenomena leading to flutter/divergence and can be efficiently integrated within an optimization procedure. The significance of the refined higher-order displacement field on the aeroelastic stability of composite wings has been established. The effect of composite ply orientations on flutter and divergence speeds has been studied. The Kreisselmeier-Steinhauser (K-S) function approach is used to efficiently integrate the objective functions and constraints into a single envelope function. The resulting unconstrained optimization problem is solved using the

  8. Computational Modelling in Development of a Design Procedure for Concrete Road

    Directory of Open Access Journals (Sweden)

    B. Novotný

    2000-01-01

    Full Text Available The computational modelling plays a decisive part in development of a new design procedure for concrete pavement by quantifying impacts of individual design factors. In the present paper, the emphasis is placed on the modelling of a structural response of the jointed concrete pavement as a system of interacting rectangular slabs transferring wheel loads into an elastic layered subgrade. The finite element plate analysis is combined with the assumption of a linear contact stress variation over triangular elements of the contact region division. The linking forces are introduced to model the load transfer across the joints. The unknown contact stress nodal intensities as well as unknown linking forces are determined in an iterative way to fulfil slab/foundation and slab/slab contact conditions. The temperature effects are also considered and space is reserved for modelling of inelastic and additional environmental effects. It is pointed out that pavement design should be based on full data of pavement stressing, in contradiction to procedures accounting only for the axle load induced stresses.

  9. The use of flow models for design of plant operating procedures

    International Nuclear Information System (INIS)

    Lind, M.

    1982-03-01

    The report describe a systematic approach to the design of operating procedures or sequence automatics for process plant control. It is shown how flow models representing the topology of mass and energy flows on different levels of function provide plant information which is important for the considered design problem. The modelling methodology leads to the definition of three categories of control tasks. Two tasks relate to the regulation and control of changes of levels and flows of mass and energy in a system within a defined mode of operation. The third type relate to the control actions necessary for switching operations involved in changes of operating mode. These control tasks are identified for a given plant as part of the flow modelling activity. It is discussed how the flow model deal with the problem of assigning control task precedence in time eg. during start-up or shut-down operations. The method may be a basis for providing automated procedure support to the operator in unforeseen situations or may be a tool for control design. (auth.)

  10. Application of a Monte Carlo procedure for probabilistic fatigue design of floating offshore wind turbines

    Directory of Open Access Journals (Sweden)

    K. Müller

    2018-03-01

    Full Text Available Fatigue load assessment of floating offshore wind turbines poses new challenges on the feasibility of numerical procedures. Due to the increased sensitivity of the considered system with respect to the environmental conditions from wind and ocean, the application of common procedures used for fixed-bottom structures results in either inaccurate simulation results or hard-to-quantify conservatism in the system design. Monte Carlo-based sampling procedures provide a more realistic approach to deal with the large variation in the environmental conditions, although basic randomization has shown slow convergence. Specialized sampling methods allow efficient coverage of the complete design space, resulting in faster convergence and hence a reduced number of required simulations. In this study, a quasi-random sampling approach based on Sobol sequences is applied to select representative events for the determination of the lifetime damage. This is calculated applying Monte Carlo integration, using subsets of a resulting total of 16 200 coupled time–domain simulations performed with the simulation code FAST. The considered system is the Danmarks Tekniske Universitet (DTU 10 MW reference turbine installed on the LIFES50+ OO-Star Wind Floater Semi 10 MW floating platform. Statistical properties of the considered environmental parameters (i.e., wind speed, wave height and wave period are determined based on the measurement data from the Gulf of Maine, USA. Convergence analyses show that it is sufficient to perform around 200 simulations in order to reach less than 10 % uncertainty of lifetime fatigue damage-equivalent loading. Complementary in-depth investigation is performed, focusing on the load sensitivity and the impact of outliers (i.e., values far away from the mean. Recommendations for the implementation of the proposed methodology in the design process are also provided.

  11. Evaluating procedural modelling for 3D models of informal settlements in urban design activities

    Directory of Open Access Journals (Sweden)

    Victoria Rautenbach

    2015-11-01

    Full Text Available Three-dimensional (3D modelling and visualisation is one of the fastest growing application fields in geographic information science. 3D city models are being researched extensively for a variety of purposes and in various domains, including urban design, disaster management, education and computer gaming. These models typically depict urban business districts (downtown or suburban residential areas. Despite informal settlements being a prevailing feature of many cities in developing countries, 3D models of informal settlements are virtually non-existent. 3D models of informal settlements could be useful in various ways, e.g. to gather information about the current environment in the informal settlements, to design upgrades, to communicate these and to educate inhabitants about environmental challenges. In this article, we described the development of a 3D model of the Slovo Park informal settlement in the City of Johannesburg Metropolitan Municipality, South Africa. Instead of using time-consuming traditional manual methods, we followed the procedural modelling technique. Visualisation characteristics of 3D models of informal settlements were described and the importance of each characteristic in urban design activities for informal settlement upgrades was assessed. Next, the visualisation characteristics of the Slovo Park model were evaluated. The results of the evaluation showed that the 3D model produced by the procedural modelling technique is suitable for urban design activities in informal settlements. The visualisation characteristics and their assessment are also useful as guidelines for developing 3D models of informal settlements. In future, we plan to empirically test the use of such 3D models in urban design projects in informal settlements.

  12. Avoiding thermal striping damage: Experimentally-based design procedures for high-cycle thermal fatigue

    International Nuclear Information System (INIS)

    Betts, C.; Judd, A.M.; Lewis, M.W.J.

    1994-01-01

    In the coolant circuits of a liquid metal cooled reactor (LMR), where there is turbulent mixing of coolant streams at different temperatures, there are temperature fluctuations in the fluid. If an item of the reactor structure is immersed in this fluid it will, because of the good heat transfer from the flowing liquid metal, experience surface temperature fluctuations which will induce dynamic surface strains. It is necessary to design the reactor so that these temperature fluctuations do not, over the life of the plant, cause damage. The purpose of this paper is to describe design procedures to prevent damage of this type. Two such procedures are given, one to prevent the initiation of defects in a nominally defect-free structure or to allow initiation only at the end of the component life, and the other to prevent significant growth of undetectable pre-existing defects of the order of 0.2 to 0.4 mm in depth. Experimental validation of these procedures is described, and the way they can be applied in practice is indicated. To set the scene the paper starts with a brief summary of cases in which damage of this type, or the need to avoid such damage, have had important effects on reactor operation. Structural damage caused by high-cycle thermal fatigue has had a significant adverse influence on the operation of LMRs on several occasions. It is necessary to eliminate the risk of such damage at the design stage. In the absence of detailed knowledge of the temperature history to which it will be subject, an LMR structure can be designed so that, if it is initially free of defects more than 0.1 mm deep, no such defects will be initiated by high-cycle fatigue. This can be done by ensuring that the maximum source temperature difference in the liquid metal is less than a limiting value, which depends on temperature. The limit is very low, however, and likely to be restrictive. This method, by virtue of its safety margin, takes into account pre-existing surface crack

  13. Design of an X-band accelerating structure using a newly developed structural optimization procedure

    Energy Technology Data Exchange (ETDEWEB)

    Huang, Xiaoxia [Shanghai Institute of Applied Physics, Chinese Academy of Sciences, Shanghai 201800 (China); University of Chinese Academy of Sciences, Beijing 100049 (China); Fang, Wencheng; Gu, Qiang [Shanghai Institute of Applied Physics, Chinese Academy of Sciences, Shanghai 201800 (China); Zhao, Zhentang, E-mail: zhaozhentang@sinap.ac.cn [Shanghai Institute of Applied Physics, Chinese Academy of Sciences, Shanghai 201800 (China); University of Chinese Academy of Sciences, Beijing 100049 (China)

    2017-05-11

    An X-band high gradient accelerating structure is a challenging technology for implementation in advanced electron linear accelerator facilities. The present work discusses the design of an X-band accelerating structure for dedicated application to a compact hard X-ray free electron laser facility at the Shanghai Institute of Applied Physics, and numerous design optimizations are conducted with consideration for radio frequency (RF) breakdown, RF efficiency, short-range wakefields, and dipole/quadrupole field modes, to ensure good beam quality and a high accelerating gradient. The designed X-band accelerating structure is a constant gradient structure with a 4π/5 operating mode and input and output dual-feed couplers in a racetrack shape. The design process employs a newly developed effective optimization procedure for optimization of the X-band accelerating structure. In addition, the specific design of couplers providing high beam quality by eliminating dipole field components and reducing quadrupole field components is discussed in detail.

  14. Analysis and application of ratcheting evaluation procedure of Japanese high temperature design code DDS

    International Nuclear Information System (INIS)

    Lee, H. Y.; Kim, J. B.; Lee, J. H.

    2002-01-01

    In this study, the evaluation procedure of Japanese DDS code which was recently developed to assess the progressive inelastic deformation occurring under repetition of secondary stresses was analyzed and the evaluation results according to DDS was compared those of the thermal ratchet structural test carried out by KAERI to analyze the conservativeness of the code. The existing high temperature codes of US ASME-NH and French RCC-MR suggest the limited ratcheting procedures for only the load cases of cyclic secondary stresses under primary stresses. So they are improper to apply to the actual ratcheting problem which can occur under cyclic secondary membrane stresses due to the movement of hot free surface for the pool type LMR. DDS provides explicitly an analysis procedure of ratcheting due to moving thermal gradients near hot free surface. A comparison study was carried out between the results by the design code of DDS and by the structural test to investigate the conservativeness of DDS code, which showed that the evaluation results by DDS were in good agreement with those of the structural test

  15. Risk-based methodology for USNRC inspections

    International Nuclear Information System (INIS)

    Wong, S.M.; Holahan, G.M.; Chung, J.W.; Johnson, M.R.

    1995-01-01

    This paper describes the development and trial applications of a risk-based methodology to enhance the inspection processes for US nuclear power plants. Objectives of risk-based methods to complement prescriptive engineering approaches in US Nuclear Regulatory Commission (USNRC) inspection programs are presented. Insights from time-dependent risk profiles of plant configurational from Individual Plant Evaluation (IPE) studies were integrated to develop a framework for optimizing inspection efforts in NRC regulatory initiatives. Lessons learned from NRC pilot applications of the risk-based methodology for evaluation of the effectiveness of operational risk management programs at US nuclear power plant sites are also discussed

  16. A design procedure for a slotted waveguide with probe-fed slots radiating into plasma

    International Nuclear Information System (INIS)

    Colborn, J.A.

    1989-11-01

    A design procedure is developed for slotted-waveguide antennas with probe-fed slots. Radiation into a gyrotropic, plane-stratified medium is considered, nonzero waveguide wall thickness is assumed, and noncosinusoidal slot fields and arbitrary slot length up to about one free-space wavelength are allowed. External mutual coupling is taken into account by matching the tangential fields at the antenna surface. The particular case of longitudinal slots in the broad face of rectangular guide is analyzed. The motivation for this work is the design of such radiators for plasma heating and current-drive on thermonuclear fusion experiments, but some of the analysis is applicable to the probeless slotted waveguide used for avionics and communications. 20 refs., 5 figs

  17. Defining System Requirements: a critical assessment of the Niam conceptual design procedure

    Directory of Open Access Journals (Sweden)

    Peta Darke

    1995-05-01

    Full Text Available Requirements definition is a fundamental activity within information systems development. Social and organisational issues are at the centre of many of the problems experienced during the development and implementation of information systems, and these need to be explored during requirements definition. The NIAM Conceptual Schema Design Procedure (CSDP is a method for identifying and describing information requirements using fact types. This paper discusses some limitations of the information requirements definition step of the CSDP which result from its lack of focus on the socio-organisational dimension of information systems development. Four different approaches to exploring the socio-organisational contexts of systems are discussed. It is proposed that one of these, viewpoint development, be incorporated into the NIAM CSDP to provide a means of exploring and understanding a system's socio organisational context and to ensure that contextual information is a major input to the requirements definition process. This results in an enhanced design procedure. Future and current research areas are identified.

  18. Execution techniques for high level radioactive waste disposal. 4. Design and manufacturing procedure of engineered barriers

    International Nuclear Information System (INIS)

    Ogata, Nobuhide; Kosaki, Akio; Ueda, Hiroyoshi; Asano, Hidekazu; Takao, Hajime

    1999-01-01

    Ensuring the physical integrity of engineered barriers for an extremely long time period is necessary for geological disposal of high-level radioactive wastes. This report describes the design process and the designed configurations of both overpack and buffer as engineered barriers. Manufacturing procedure, quality control and inspection methods are also summarized. Carbon steel was selected as a structural material of the overpack and the specification of the overpack was determined assuming disposal in the depths of 1000 m below surface of crystalline rock site. The mixture of bentonite and sand (80% sodium bentonite and 20% silica sand by mass) was selected as material for a buffer from mainly its permeability and characteristics of self-sealing of a gap occurred in construction work. Welding method of a lid onto the main body of the overpack, uniting method of a corrosion-resistance layer and the structural component in the case of a composite overpack and manufacturing procedures of both blocks-type and monolithic-type buffers are also investigated. (author)

  19. A general U-block model-based design procedure for nonlinear polynomial control systems

    Science.gov (United States)

    Zhu, Q. M.; Zhao, D. Y.; Zhang, Jianhua

    2016-10-01

    The proposition of U-model concept (in terms of 'providing concise and applicable solutions for complex problems') and a corresponding basic U-control design algorithm was originated in the first author's PhD thesis. The term of U-model appeared (not rigorously defined) for the first time in the first author's other journal paper, which established a framework for using linear polynomial control system design approaches to design nonlinear polynomial control systems (in brief, linear polynomial approaches → nonlinear polynomial plants). This paper represents the next milestone work - using linear state-space approaches to design nonlinear polynomial control systems (in brief, linear state-space approaches → nonlinear polynomial plants). The overall aim of the study is to establish a framework, defined as the U-block model, which provides a generic prototype for using linear state-space-based approaches to design the control systems with smooth nonlinear plants/processes described by polynomial models. For analysing the feasibility and effectiveness, sliding mode control design approach is selected as an exemplary case study. Numerical simulation studies provide a user-friendly step-by-step procedure for the readers/users with interest in their ad hoc applications. In formality, this is the first paper to present the U-model-oriented control system design in a formal way and to study the associated properties and theorems. The previous publications, in the main, have been algorithm-based studies and simulation demonstrations. In some sense, this paper can be treated as a landmark for the U-model-based research from intuitive/heuristic stage to rigour/formal/comprehensive studies.

  20. Tailoring groundwater quality monitoring to vulnerability: a GIS procedure for network design.

    Science.gov (United States)

    Preziosi, E; Petrangeli, A B; Giuliano, G

    2013-05-01

    Monitoring networks aiming to assess the state of groundwater quality and detect or predict changes could increase in efficiency when fitted to vulnerability and pollution risk assessment. The main purpose of this paper is to describe a methodology aiming at integrating aquifers vulnerability and actual levels of groundwater pollution in the monitoring network design. In this study carried out in a pilot area in central Italy, several factors such as hydrogeological setting, groundwater vulnerability, and natural and anthropogenic contamination levels were analyzed and used in designing a network tailored to the monitoring objectives, namely, surveying the evolution of groundwater quality relating to natural conditions as well as to polluting processes active in the area. Due to the absence of an aquifer vulnerability map for the whole area, a proxi evaluation of it was performed through a geographic information system (GIS) methodology, leading to the so called "susceptibility to groundwater quality degradation". The latter was used as a basis for the network density assessment, while water points were ranked by several factors including discharge, actual contamination levels, maintenance conditions, and accessibility for periodical sampling in order to select the most appropriate to the network. Two different GIS procedures were implemented which combine vulnerability conditions and water points suitability, producing two slightly different networks of 50 monitoring points selected out of the 121 candidate wells and springs. The results are compared with a "manual" selection of the points. The applied GIS procedures resulted capable to select the requested number of water points from the initial set, evaluating the most confident ones and an appropriate density. Moreover, it is worth underlining that the second procedure (point distance analysis [PDA]) is technically faster and simpler to be performed than the first one (GRID + PDA).

  1. Judicial problems in connection with preliminary decision and construction design approval in nuclear licensing procedures

    International Nuclear Information System (INIS)

    Schmieder, K.

    1977-01-01

    Standardization in nuclear engineering makes two demands on a legal instrument which is to make this standardization possible and which is to promote standardization in the nuclear licensing practice: On the basis of just one licence for a constructional part or a component, its applicability in any number of subsequent facility licensing procedures has to be warranted, and by virtue of its binding effect, standardization has to create a sufficiently big confidence protection with manufacturers, constructioneers and operators to offer sufficiently effective incentives for standardization. The nuclear preliminary decision pursuant to section 7 a of the Atomic Energy Act in the form of the component preliminary decision appears to be unsuitable as a legal instrument for standardization, as the preliminary decision refers exclusively to the construction of a concrete facility. For standardization in reactor engineering, the construction design approval appears to be basically the proper legal instrument on account of its legal structure as well as its economic effect. Its binding effect encouters a limitation with regard to third parties in so far that this limitation could question again the binding effect in a subsequent site-dependent nuclear licence procedure. The legal structure of the extent of the binding effect, which is decisive for the suitability of the construction design approval, lies with the legislator. The following questions have to be regulated: Ought the applicant to have a legal claim on the granting of a construction design approval, or ought it to be at the discretion of the authorities, and secondly, the extent of the binding effect in terms of time on the basis of the fixation of a time limit, or on the basis of the possibility of subsequent conditions to be imposed, or the revocation. (orig./HP) [de

  2. Hardware Design and Implementation of a Wavelet De-Noising Procedure for Medical Signal Preprocessing

    Directory of Open Access Journals (Sweden)

    Szi-Wen Chen

    2015-10-01

    Full Text Available In this paper, a discrete wavelet transform (DWT based de-noising with its applications into the noise reduction for medical signal preprocessing is introduced. This work focuses on the hardware realization of a real-time wavelet de-noising procedure. The proposed de-noising circuit mainly consists of three modules: a DWT, a thresholding, and an inverse DWT (IDWT modular circuits. We also proposed a novel adaptive thresholding scheme and incorporated it into our wavelet de-noising procedure. Performance was then evaluated on both the architectural designs of the software and. In addition, the de-noising circuit was also implemented by downloading the Verilog codes to a field programmable gate array (FPGA based platform so that its ability in noise reduction may be further validated in actual practice. Simulation experiment results produced by applying a set of simulated noise-contaminated electrocardiogram (ECG signals into the de-noising circuit showed that the circuit could not only desirably meet the requirement of real-time processing, but also achieve satisfactory performance for noise reduction, while the sharp features of the ECG signals can be well preserved. The proposed de-noising circuit was further synthesized using the Synopsys Design Compiler with an Artisan Taiwan Semiconductor Manufacturing Company (TSMC, Hsinchu, Taiwan 40 nm standard cell library. The integrated circuit (IC synthesis simulation results showed that the proposed design can achieve a clock frequency of 200 MHz and the power consumption was only 17.4 mW, when operated at 200 MHz.

  3. Hardware design and implementation of a wavelet de-noising procedure for medical signal preprocessing.

    Science.gov (United States)

    Chen, Szi-Wen; Chen, Yuan-Ho

    2015-10-16

    In this paper, a discrete wavelet transform (DWT) based de-noising with its applications into the noise reduction for medical signal preprocessing is introduced. This work focuses on the hardware realization of a real-time wavelet de-noising procedure. The proposed de-noising circuit mainly consists of three modules: a DWT, a thresholding, and an inverse DWT (IDWT) modular circuits. We also proposed a novel adaptive thresholding scheme and incorporated it into our wavelet de-noising procedure. Performance was then evaluated on both the architectural designs of the software and. In addition, the de-noising circuit was also implemented by downloading the Verilog codes to a field programmable gate array (FPGA) based platform so that its ability in noise reduction may be further validated in actual practice. Simulation experiment results produced by applying a set of simulated noise-contaminated electrocardiogram (ECG) signals into the de-noising circuit showed that the circuit could not only desirably meet the requirement of real-time processing, but also achieve satisfactory performance for noise reduction, while the sharp features of the ECG signals can be well preserved. The proposed de-noising circuit was further synthesized using the Synopsys Design Compiler with an Artisan Taiwan Semiconductor Manufacturing Company (TSMC, Hsinchu, Taiwan) 40 nm standard cell library. The integrated circuit (IC) synthesis simulation results showed that the proposed design can achieve a clock frequency of 200 MHz and the power consumption was only 17.4 mW, when operated at 200 MHz.

  4. A novel gait-based synthesis procedure for the design of 4-bar exoskeleton with natural trajectories

    Directory of Open Access Journals (Sweden)

    Ramanpreet Singh

    2018-01-01

    The Translational Potential of this Article: Many hospitals and individuals have used the immobile and portable rehabilitation devices. These devices involve mechanisms, and the design of mechanism plays a vital role in the functioning of these devices; therefore, we have developed a new synthesis procedure for the design of the mechanism. Besides synthesis procedure, a mechanism is developed that can be used in the rehabilitation devices, bipeds, exoskeletons, etc., to benefit the society.

  5. HIGH QUALITY ENVIRONMENTAL PRINCIPLES APPLIED TO THE ARCHITECTONIC DESIGN SELECTION PROCEDURE: THE NUTRE LAB CASE

    Directory of Open Access Journals (Sweden)

    Claudia Barroso Krause

    2012-06-01

    Full Text Available The need to produce more sustainable buildings has been influencing the design decisions all over the world. That’s why it is imperative, in Brazil, the development of strategies and method to aid the decision making during the design process, focused on high quality environmental. This paper presents a decision support tool based on the principles of sustainable construction developed by the Project, Architecture and Sustainability Research Group (GPAS of Federal University of Rio de Janeiro – Brazil. The methodology has been developed for the selection of a preliminary design of a laboratory to be built at Rio Technology Park at the University campus. The support provided by GPAS occurred in three stages: the elaboration of the Reference Guide for the competitors, the development of a methodology to evaluate the proposed solutions (based on environmental performance criteria and the assistance of the members of jury in the trial phase. The theoretical framework was based upon the concepts of the bioclimatic architecture, the procedures specified by the certification HQE® (Haute Qualité Environnementale and the method suggested by the ADDENDA® architecture office. The success of this experience points out the possibility to future application in similar cases.

  6. Design Procedure and Fabrication of Reproducible Silicon Vernier Devices for High-Performance Refractive Index Sensing.

    Science.gov (United States)

    Troia, Benedetto; Khokhar, Ali Z; Nedeljkovic, Milos; Reynolds, Scott A; Hu, Youfang; Mashanovich, Goran Z; Passaro, Vittorio M N

    2015-06-10

    In this paper, we propose a generalized procedure for the design of integrated Vernier devices for high performance chemical and biochemical sensing. In particular, we demonstrate the accurate control of the most critical design and fabrication parameters of silicon-on-insulator cascade-coupled racetrack resonators operating in the second regime of the Vernier effect, around 1.55 μm. The experimental implementation of our design strategies has allowed a rigorous and reliable investigation of the influence of racetrack resonator and directional coupler dimensions as well as of waveguide process variability on the operation of Vernier devices. Figures of merit of our Vernier architectures have been measured experimentally, evidencing a high reproducibility and a very good agreement with the theoretical predictions, as also confirmed by relative errors even lower than 1%. Finally, a Vernier gain as high as 30.3, average insertion loss of 2.1 dB and extinction ratio up to 30 dB have been achieved.

  7. Assisted design, implementation, and modification of procedure tracking and advisory systems

    International Nuclear Information System (INIS)

    Patterson-Hine, F.A.; Boy, G.A.; Conley, J.L.; Iverson, D.L.

    1991-01-01

    Automated procedure tracking systems have been of interest in the nuclear power industry due to the huge numbers of documented procedures required for the operation and maintenance of commercial power reactors. Tools are under development at Ames Research center that form the basis of an intelligent advisory system for process control applications. Two tools, one for documentation maintenance and management and the other for automated fault diagnosis, are being integrated to build an advisory system appropriate for use in facilities that require emergency readiness and safety-critical operations. The problem of automation of documents management and maintenance has been analyzed from artificial intelligence and from human factors viewpoints. A software tool, called computer-integrated documentation (CID), has been designed and is under further development to address these issues. A fault diagnosis algorithm has been developed and implemented in a software tool called the fault-tree diagnosis system (FTDS). The algorithm uses a knowledge base that is easily changed and updated to reflect current system status. An integrated tool set consisting of CID and FTDS is being used to develop and demonstrate an intelligent advisory system for use in a flight test environment for advanced aircraft

  8. Development of design procedures for fast reactors in the United Kingdom

    International Nuclear Information System (INIS)

    Rose, R.T.; Tomkins, B.; Townley, C.H.A.

    1989-01-01

    A considerable amount of research has been carried out in the United Kingdom during the past two decades to quantify the factors which control the integrity of structural components. The work which has been aimed at understanding the performance of structures at high temperature, is particularly relevant to the Fast Reactor. At the same time, because of the need to demonstrate the tolerance to defects in the low temperature as well as the high temperature components, defect assessment criteria are also of great importance. Emphasis is now being given to the development of design procedures specifically for Fast Reactors, making use of the research so far completed. The United Kingdom proposals are being integrated with those from France, Federal Republic of Germany and Italy as part of the European collaborative venture. The paper outlines the major developments which are currently in hand, and brings up to date the review of United Kingdom activities presented at Tokyo in 1986. (author)

  9. DESIGN OF A COUNTABLE PROCEDURE FOR THE REGISTRATION OF ENVIRONMENTAL VARIABLES

    Directory of Open Access Journals (Sweden)

    Elier Eugenio Rabanal-Arencibia

    2016-01-01

    Full Text Available Many companies present in their memoirs matters of environmental character, but they are few those that are able to count the environmental facts that definitively influence in their financial states. One of the challenges of our managerial sector in Cuba is to integrate the topic of the environment to the process of taking decisions and to the business strategies. A countable system that contemplates the environmental concept in its classifier of bills, obviously will have available information for its costs and environmental revenues, what is indispensable in the long term company development, especially if it is about companies related with the exploitation of natural resources. The purpose is to carry out the Design of a Countable Procedure for the registration of environmental variables, as a support to the continuous improvement of the Environmental Accounting. 

  10. Standards for radiation protection instrumentation: design of safety standards and testing procedures

    International Nuclear Information System (INIS)

    Meissner, Frank

    2008-01-01

    This paper describes by means of examples the role of safety standards for radiation protection and the testing and qualification procedures. The development and qualification of radiation protection instrumentation is a significant part of the work of TUV NORD SysTec, an independent expert organisation in Germany. The German Nuclear Safety Standards Commission (KTA) establishes regulations in the field of nuclear safety. The examples presented may be of importance for governments and nuclear safety authorities, for nuclear operators and for manufacturers worldwide. They demonstrate the advantage of standards in the design of radiation protection instrumentation for new power plants, in the upgrade of existing instrumentation to nuclear safety standards or in the application of safety standards to newly developed equipment. Furthermore, they show how authorities may proceed when safety standards for radiation protection instrumentation are not yet established or require actualization. (author)

  11. Design procedure for formulating and assessing the durability of particulate grouts

    International Nuclear Information System (INIS)

    Okonkwo, I.O.; Altschaeff, A.G.

    1989-01-01

    The current disposal plans for low-level wastes call for stabilizing or encapsulating and storing of these wastes in steel drums which in turn are buried in shallow trenches. Complete sealing is accomplished with grout, a liquid injection comprising principally of cement and fly ash, etc. Upon solidification, the grout forms a rigid mass around the drum, thereby eliminating access of groundwater into or out of the waste barrier, or leaching of radionuclides. Since the primary mechanism for the likely introduction of hazardous and/or radioactive elements into the biosphere in this situation, is through physical or chemical deterioration of the waste barrier, it is necessary that the effect of adverse environments on the durability of the grouts be examined and incorporated in barrier design. Currently, procedures for formulating grout mixes to assure a given impermeability or durability of the grout over its service period is lacking, and so are the techniques for monitoring the in-service performance of waste barrier systems. This paper depicts a serious limitation in waste barrier system technology, for it is time that optimization in design be possible. To allow this, a method is needed that creates the grout formulation specification for an optimization of behavior parameters in the resulting product. These considerations suggest a strong need for improvement in the grout formulation specification to allow a focus upon behavior properties desired by the engineer in the creation of optimum performance. This paper addresses these problems

  12. New ion exchange resin designs and regeneration procedures yield improved performance for various condensate polishing applications

    International Nuclear Information System (INIS)

    Najmy, S.W.

    2002-01-01

    Condensate polishing is an application with many different design and operational aspects. The past decade has brought new challenges for improved water quality with respect to both soluble and insoluble contaminants. Nonetheless, the endeavors to understand the compositional complexities of the ion exchange resin bead and the convoluted dynamics of ion exchange chemistry and chemical engineering mechanisms occurring within the mixed bed condensate polisher have brought new ideas and expectations for ion exchange resin in deep-bed condensate polishers than ever before. The new products and procedures presented here are a collaboration of a great deal of effort on the part of researchers, consultants, system engineers, station chemists, lab technicians and others. The studies discussed in this paper unequivocally demonstrate the merits of: 1. A specially designed cation resin to achieve greater than 95% insoluble iron removal efficiency, 2. A less-separable mixed resin for improved control of reactor water sulfate in BWR primary cycles, 3. Applying increased levels of regeneration chemicals and retrofitting the service vessels with re-mixing capability to improve the operation of deep-bed condensate polishers in PWR secondary cycles. (authors)

  13. Crush performance of redwood for developing design procedures for impact limiters

    International Nuclear Information System (INIS)

    Cramer, S.M.; Hermanson, J.C.; McMurtry, W.M.

    1995-01-01

    Containers for the transportation of hazardous and radioactive materials incorporate redwood in impact limiters. Redwood is an excellent energy absorber, but only the most simplistic information exists on its crush properties. Tbe stress-strain interrelationship for any wood species subject to three-dimensional stresses is largely unknown for any all stress condition and wood behavior at both high strains and high strain-rates is known only in general terms. Both stress-strain and crush failure theories have been developed based only on uniaxial load tests. The anisotropy of wood adds an additional complexity to measuring wood response and developing suitable theories to describe it. A long history of wood utilization in the building industry has led to design procedures and property information related to simple uniaxial loadings that do not inflict damage to the wood. This lack of knowledge may be surprising for a material that has a long history of engineered use, but the result is difficulty in utilizing wood in more sophisticated designs such as impact limiters. This study provides a step toward filling the information gap on wood material response for high performance applications such as impact limiters

  14. A risk-based auditing process for pharmaceutical manufacturers.

    Science.gov (United States)

    Vargo, Susan; Dana, Bob; Rangavajhula, Vijaya; Rönninger, Stephan

    2014-01-01

    The purpose of this article is to share ideas on developing a risk-based model for the scheduling of audits (both internal and external). Audits are a key element of a manufacturer's quality system and provide an independent means of evaluating the manufacturer's or the supplier/vendor's compliance status. Suggestions for risk-based scheduling approaches are discussed in the article. Pharmaceutical manufacturers are required to establish and implement a quality system. The quality system is an organizational structure defining responsibilities, procedures, processes, and resources that the manufacturer has established to ensure quality throughout the manufacturing process. Audits are a component of the manufacturer's quality system and provide a systematic and an independent means of evaluating the manufacturer's overall quality system and compliance status. Audits are performed at defined intervals for a specified duration. The intention of the audit process is to focus on key areas within the quality system and may not cover all relevant areas during each audit. In this article, the authors provide suggestions for risk-based scheduling approaches to aid pharmaceutical manufacturers in identifying the key focus areas for an audit.

  15. New design procedure development of future reactor critical power estimation. (1) Practical design-by-analysis method for BWR critical power design correlation

    International Nuclear Information System (INIS)

    Yamamoto, Yasushi; Mitsutake, Toru

    2007-01-01

    For present BWR fuels, the full mock-up thermal-hydraulic test, such as the critical power measurement test, pressure drop measurement test and so on, has been needed. However, the full mock-up test required the high costs and large-scale test facility. At present, there are only a few test facilities to perform the full mock-up thermal-hydraulic test in the world. Moreover, for future BWR, the bundle size tends to be larger, because of reducing the plant construction costs and minimizing the routine check period. For instance, AB1600, improved ABWR, was proposed from Toshiba, whose bundle size was 1.2 times larger than the conventional BWR fuel size. It is too expensive and far from realistic to perform the full mock-up thermal-hydraulic test for such a large size fuel bundle. The new design procedure is required to realize the large scale bundle design development, especially for the future reactor. Therefore, the new design procedure, Practical Design-by-Analysis (PDBA) method, has been developed. This new procedure consists of the partial mock-up test and numerical analysis. At present, the subchannel analysis method based on three-fluid two-phase flow model only is a realistic choice. Firstly, the partial mock-up test is performed, for instance, the 1/4 partial mock-up bundle. Then, the first-step critical power correlation coefficients are evaluated with the measured data. The input data, such as the spacer effect model coefficient, on the subchannel analysis are also estimated with the data. Next, the radial power effect on the critical power of the full-bundle size was estimated with the subchannel analysis. Finally, the critical power correlation is modified by the subchannel analysis results. In the present study, the critical power correlation of the conventional 8x8 BWR fuel was developed with the PDBA method by 4x4 partial mock-up tests and the subchannel analysis code. The accuracy of the estimated critical power was 3.8%. The several themes remain to

  16. R20 programme: Development of rock grouting design, techniques and procedures for ONKALO

    International Nuclear Information System (INIS)

    Sievaenen, U.

    2009-02-01

    Posiva Oy constructs an underground research facility ONKALO at Olkiluoto in Eurajoki. ONKALO is planned to be a part of the deep repository for the high level nuclear waste. Posiva Oy set up R20-programme for the years 2006-2008, with the target of having an acceptable grouting methodology in ONKALO. The programme was divided into three projects and the work and results of Technique-project is presented in this report. The implementation of the results (grouting design and execution) was outlined from the project. That work is under the responsibility of construction of the ONKALO-project. The Grouting Technique -project (INKE) studied the grouting experiences obtained from the first 2 km of the ONKALO access tunnel, searched for suitable grouting design approaches, carried out two grouting tests and one pilot grouting test with colloidal silica in ONKALO, analysed the expected grouting conditions in deep rock from the grouting point of view, studied the feasibility of so called optimal design solution in the expected grouting conditions. Based on these studies recommendations concerning the grouting design, design solutions for different rock conditions, grouting procedures, grouting stop criteria, the characterisation methods for grouting purposes, grouting materials and grouting work performance are presented. Swedish Time Stop Grouting, also named Grouting Time-Method was selected to be studied and used in this project and it was further developed. This work compiles the outcome of the project subtasks and presents the recommendations for developing the grouting in ONKALO. The key conclusion of this work are: (1) Grouting Time-method (time stop grouting) alone is not enough to be used as a grouting stop criterion due to the uncertainties related to the source parameters (fracture characteristics, rheological properties of grouts); these cause too high uncertainties when proving the sealing result via the grouting time, (2) due to the uncertainties related to

  17. Equating Multidimensional Tests under a Random Groups Design: A Comparison of Various Equating Procedures

    Science.gov (United States)

    Lee, Eunjung

    2013-01-01

    The purpose of this research was to compare the equating performance of various equating procedures for the multidimensional tests. To examine the various equating procedures, simulated data sets were used that were generated based on a multidimensional item response theory (MIRT) framework. Various equating procedures were examined, including…

  18. Mitigation of fire damage and escalation by fireproofing: A risk-based strategy

    International Nuclear Information System (INIS)

    Tugnoli, Alessandro; Cozzani, Valerio; Di Padova, Annamaria; Barbaresi, Tiziana; Tallone, Fabrizio

    2012-01-01

    Passive fire protection by the application of fireproofing materials is a crucial safety barrier in the prevention of the escalation of fire scenarios. Fireproofing improves the capacity of process items and of support structures to maintain their structural integrity during a fire, preventing or at least delaying the collapse of structural elements. Maintenance and cost issues require, however, to apply such protection only where an actual risk of severe fire scenarios is present. Available methodologies for fireproofing application in on-shore installation do not consider the effect of jet-fires. In the present study, a risk-based methodology aimed at the protection from both pool fire and jet fire escalation was developed. The procedure addresses both the prevention of domino effect and the mitigation of asset damage due to the primary fire scenario. The method is mainly oriented to early design application, allowing the identification of fireproofing zones in the initial phases of lay-out definition.

  19. Risk-based SMA for Cubesats

    Science.gov (United States)

    Leitner, Jesse

    2016-01-01

    This presentation conveys an approach for risk-based safety and mission assurance applied to cubesats. This presentation accompanies a NASA Goddard standard in development that provides guidance for building a mission success plan for cubesats based on the risk tolerance and resources available.

  20. Mechanical Design, Brazing and Assembly Procedures of the LINAC4 RFQ

    CERN Document Server

    Mathot, S; Briswalter, A; Callamand, Th; Carosone, J; Favre, N; Geisser, J M; Lombardi, A; Maire, V; Malabaila, M; Pugnat, D; Richerot, Ph; Riffaut, B; Rossi, C; Timmins, M; Vacca, A; Vandoni, G; Vretenar, M

    2010-01-01

    The Linac4 RFQ will accelerate the H- beam from the ion source to the energy of 3 MeV. The RFQ is composed of three sections of one meter each, assembled by means of ultra high vacuum flanges and adjustable centring rings. The complete 3-m long RFQ will be supported isostatically over 3 points like a simple beam in order to minimise the maximum deflection. The ridge line, used to feed the RF power into the RFQ, will be supported via springs and its position adjusted in such way that no strain is introduced into the RFQ at the moment of its connection. The mechanical design has been done at CERN where the modules are completely manufactured, heat treated and brazed also. In that way, all of the processes are carefully controlled and the influence, notably of the heat treatments, has been understood in a better way. Since 2002 several four vanes RFQ modules have been brazed at CERN for the TRASCO and IPHI projects. A two-step brazing procedure has been tested. This technique is actually used for the assembly of...

  1. 13 CFR 120.1000 - Risk-Based Lender Oversight.

    Science.gov (United States)

    2010-01-01

    ... 13 Business Credit and Assistance 1 2010-01-01 2010-01-01 false Risk-Based Lender Oversight. 120.1000 Section 120.1000 Business Credit and Assistance SMALL BUSINESS ADMINISTRATION BUSINESS LOANS Risk-Based Lender Oversight Supervision § 120.1000 Risk-Based Lender Oversight. (a) Risk-Based Lender...

  2. Development of new risk based regulations

    International Nuclear Information System (INIS)

    Nielsen, L.

    1999-01-01

    A short presentation of the oil and gas industry in Norway, and a brief overview of the regulatory regime in the petroleum sector in Norway is given. Risk analysis has been performed in Norway since 1981 and the various applications will be described. These risk analyses are quite different from a nuclear PSA and some of these differences will be commented. Risk based optimisation techniques such as RCM (Reliability Centred Maintenance) and Risk Based Inspection is used in the industry, with very limited support from the risk analysis. Some of the limitation that exist when such techniques are imported from other industries will be commented on. NPD (Norwegian Petroleum Directorate) is revising our regulations and some of the future plants when it comes to risk informed regulatory requirements will be presented. (au)

  3. Risk-based zoning for urbanizing floodplains.

    Science.gov (United States)

    Porse, Erik

    2014-01-01

    Urban floodplain development brings economic benefits and enhanced flood risks. Rapidly growing cities must often balance the economic benefits and increased risks of floodplain settlement. Planning can provide multiple flood mitigation and environmental benefits by combining traditional structural measures such as levees, increasingly popular landscape and design features (green infrastructure), and non-structural measures such as zoning. Flexibility in both structural and non-structural options, including zoning procedures, can reduce flood risks. This paper presents a linear programming formulation to assess cost-effective urban floodplain development decisions that consider benefits and costs of development along with expected flood damages. It uses a probabilistic approach to identify combinations of land-use allocations (residential and commercial development, flood channels, distributed runoff management) and zoning regulations (development zones in channel) to maximize benefits. The model is applied to a floodplain planning analysis for an urbanizing region in the Baja Sur peninsula of Mexico. The analysis demonstrates how (1) economic benefits drive floodplain development, (2) flexible zoning can improve economic returns, and (3) cities can use landscapes, enhanced by technology and design, to manage floods. The framework can incorporate additional green infrastructure benefits, and bridges typical disciplinary gaps for planning and engineering.

  4. 26 CFR 1.852-9 - Special procedural requirements applicable to designation under section 852(b)(3)(D).

    Science.gov (United States)

    2010-04-01

    ... notice by the Internal Revenue Service that the regulated investment company has failed to comply with... 26 Internal Revenue 9 2010-04-01 2010-04-01 false Special procedural requirements applicable to designation under section 852(b)(3)(D). 1.852-9 Section 1.852-9 Internal Revenue INTERNAL REVENUE SERVICE...

  5. Procedures for the design of the main mechanical components of a wind system; Dimensionamento dos componentes mecanicos principais de aerogeradores

    Energy Technology Data Exchange (ETDEWEB)

    Hirata, M.H.; Marco Filho, F. de [Universidade Federal, Rio de Janeiro, RJ (Brazil). Coordenacao dos Programas de Pos-graduacao de Engenharia

    1990-12-31

    Procedures for the design of the main mechanical components of a wind system were developed. One of the main concerns was related to the possibility of its use in small micro-computers. This goal was reached and an APPLE II computer was used. The resulting algorithm permits a friendly interaction between man and machine. 5 refs., 12 figs

  6. 48 CFR 570.105-2 - Two-phase design-build selection procedures.

    Science.gov (United States)

    2010-10-01

    ... lease construction projects with options to purchase the real property leased. Use the procedures in.... (iii) The capability and experience of potential contractors. (iv) The suitability of the project for...

  7. Optimal training design for procedural motor skills: a review and application to laparoscopic surgery

    NARCIS (Netherlands)

    Spruit, E.N.; Band, G.P.H.; Hamming, J.F.; Ridderinkhof, K.R.

    2014-01-01

    This literature review covers the choices to consider in training complex procedural, perceptual and motor skills. In particular, we focus on laparoscopic surgery. An overview is provided of important training factors modulating the acquisition, durability, transfer, and efficiency of trained

  8. A robust procedure for comparing multiple means under heteroscedasticity in unbalanced designs.

    Directory of Open Access Journals (Sweden)

    Esther Herberich

    2010-03-01

    Full Text Available Investigating differences between means of more than two groups or experimental conditions is a routine research question addressed in biology. In order to assess differences statistically, multiple comparison procedures are applied. The most prominent procedures of this type, the Dunnett and Tukey-Kramer test, control the probability of reporting at least one false positive result when the data are normally distributed and when the sample sizes and variances do not differ between groups. All three assumptions are non-realistic in biological research and any violation leads to an increased number of reported false positive results. Based on a general statistical framework for simultaneous inference and robust covariance estimators we propose a new statistical multiple comparison procedure for assessing multiple means. In contrast to the Dunnett or Tukey-Kramer tests, no assumptions regarding the distribution, sample sizes or variance homogeneity are necessary. The performance of the new procedure is assessed by means of its familywise error rate and power under different distributions. The practical merits are demonstrated by a reanalysis of fatty acid phenotypes of the bacterium Bacillus simplex from the "Evolution Canyons" I and II in Israel. The simulation results show that even under severely varying variances, the procedure controls the number of false positive findings very well. Thus, the here presented procedure works well under biologically realistic scenarios of unbalanced group sizes, non-normality and heteroscedasticity.

  9. Core design optimization by integration of a fast 3-D nodal code in a heuristic search procedure

    Energy Technology Data Exchange (ETDEWEB)

    Geemert, R. van; Leege, P.F.A. de; Hoogenboom, J.E.; Quist, A.J. [Delft University of Technology, NL-2629 JB Delft (Netherlands)

    1998-07-01

    An automated design tool is being developed for the Hoger Onderwijs Reactor (HOR) in Delft, the Netherlands, which is a 2 MWth swimming-pool type research reactor. As a black box evaluator, the 3-D nodal code SILWER, which up to now has been used only for evaluation of predetermined core designs, is integrated in the core optimization procedure. SILWER is a part of PSl's ELCOS package and features optional additional thermal-hydraulic, control rods and xenon poisoning calculations. This allows for fast and accurate evaluation of different core designs during the optimization search. Special attention is paid to handling the in- and output files for SILWER such that no adjustment of the code itself is required for its integration in the optimization programme. The optimization objective, the safety and operation constraints, as well as the optimization procedure, are discussed. (author)

  10. Core design optimization by integration of a fast 3-D nodal code in a heuristic search procedure

    International Nuclear Information System (INIS)

    Geemert, R. van; Leege, P.F.A. de; Hoogenboom, J.E.; Quist, A.J.

    1998-01-01

    An automated design tool is being developed for the Hoger Onderwijs Reactor (HOR) in Delft, the Netherlands, which is a 2 MWth swimming-pool type research reactor. As a black box evaluator, the 3-D nodal code SILWER, which up to now has been used only for evaluation of predetermined core designs, is integrated in the core optimization procedure. SILWER is a part of PSl's ELCOS package and features optional additional thermal-hydraulic, control rods and xenon poisoning calculations. This allows for fast and accurate evaluation of different core designs during the optimization search. Special attention is paid to handling the in- and output files for SILWER such that no adjustment of the code itself is required for its integration in the optimization programme. The optimization objective, the safety and operation constraints, as well as the optimization procedure, are discussed. (author)

  11. Structural integrity and its role in nuclear safety: recent UK advances in the development of high temperature design procedures

    International Nuclear Information System (INIS)

    Townley, C.H.A.

    1996-01-01

    This paper takes the liquid metal fast breeder reactor as an example and identifies those topics where research has had a role to play in providing improved design rules. Many of the previously adopted procedures contained large amounts of pessimism to allow for uncertainties in the prediction of long-term structural behaviour. The aim has therefore been to gain an improved physical insight into the phenomena which govern performance and to develope less restrictive procedures which, at the same time, guarantee the high standards of integrity which are required. (orig.)

  12. Evaluation of some resonance self-shielding procedures employed in high conversion light water reactor design

    International Nuclear Information System (INIS)

    Patino, N.E.; Abbate, M.J.; Sbaffoni, M.M.

    1990-01-01

    The procedures employed in the treatment of the resonance shielding effect have been identified as one of the causes of the large discrepancies found in the neutronic calculation of high conversion light water reactors (HCLWRs), indicating the need for a revision of the self-shielding procedures employed. In this work some well known techniques applied in HCLWR self-shielding calculations are evaluated; the study involves the comparison of methods for the generation of group constants, the analysis of the impact of considering some isotopes as infinitely diluted and the evaluation of the usual approximations utilized for the treatment of heterogeneities

  13. A risk-based sensor placement methodology

    International Nuclear Information System (INIS)

    Lee, Ronald W.; Kulesz, James J.

    2008-01-01

    A risk-based sensor placement methodology is proposed to solve the problem of optimal location of sensors to protect population against the exposure to, and effects of, known and/or postulated chemical, biological, and/or radiological threats. Risk is calculated as a quantitative value representing population at risk from exposure at standard exposure levels. Historical meteorological data are used to characterize weather conditions as the frequency of wind speed and direction pairs. The meteorological data drive atmospheric transport and dispersion modeling of the threats, the results of which are used to calculate risk values. Sensor locations are determined via an iterative dynamic programming algorithm whereby threats detected by sensors placed in prior iterations are removed from consideration in subsequent iterations. In addition to the risk-based placement algorithm, the proposed methodology provides a quantification of the marginal utility of each additional sensor. This is the fraction of the total risk accounted for by placement of the sensor. Thus, the criteria for halting the iterative process can be the number of sensors available, a threshold marginal utility value, and/or a minimum cumulative utility achieved with all sensors

  14. Remote maintenance systems requirements are being developed to provide design guidelines for machine components, to define maintenance interfaces, and to quantify maintenance equipment and procedures needed

    International Nuclear Information System (INIS)

    Spampinato, P.T.; Tabor, M.A.

    1988-01-01

    Remote maintenance systems requirements are being developed to provide design guidelines for machine components, to define maintenance interfaces, and to quantify maintenance equipment and procedures needed

  15. Demonstration of risk-based approaches to nuclear plant regulation

    International Nuclear Information System (INIS)

    Rahn, F.J.; Sursock, J.P.; Darling, S.S.; Oddo, J.M.

    1993-01-01

    This paper describes generic technical support EPRI is providing to the nuclear power industry relative to its recent initiatives in the area of risk-based regulations (RBR). A risk-based regulatory approach uses probabilistic risk assessment (PRA), or similar techniques, to allocate safety resources commensurate with the risk posed by nuclear plant operations. This approach will reduce O ampersand M costs, and also improve nuclear plant safety. In order to enhance industry, Nuclear Regulatory Commission (NRC) and public confidence in RBR, three things need to be shown: (1) manpower/resource savings are significant for both NRC and industry; (2) the process is doable in a reasonable amount of time; and (3) the process, if uniformly applied, results in demonstrably cheaper power and safer plants. In 1992, EPRI performed a qualitative study of the key RBR issues contributing to high O ampersand M costs. The results are given on Table 1. This study is being followed up by an in-depth quantitative cost/benefit study to focus technical work on producing guidelines/procedures for licensing submittals to NRC. The guidelines/procedures necessarily will be developed from successful demonstration projects such as the Fitzpatrick pilot plant study proposed by the New York Power Authority and other generic applications. This paper presents three examples: two motor operated valve projects performed by QUADREX Energy Services Corporation working with utilities in responding to NRC Generic Letter 89-10, and a third project working with Yankee Atomic Electric Company on service water systems at a plant in its service system. These demonstration projects aim to show the following: (1) the relative ease of putting together a technical case based on RBR concepts; (2) clarity in differentiating the various risk trade-offs, and in communicating overall reductions in risk with NRC; and (3) improved prioritization of NRC directives

  16. Effective Work Procedure design Using Discomfort and Effort Factor in Brick stacking operation-A case study

    Science.gov (United States)

    Rout, Biswaranjan; Dash, R. R.; Dhupal, D.

    2018-02-01

    In this work a typical planning of movement of limbs and torso of the worker to be well design to reduce fatigue and energy of the worker. A simulation model is generated to suit the procedure and comply with the constraints in the workspace. It requires verifying the capability of human postures and movements in different working conditions for the evaluation of effectiveness of the new design. In this article a simple human performance measure is introduce that enable the mathematical model for evaluation of a cost function. The basic scheme is to evaluate the performance in the form of several cost factors using AI techniques. Here two main cost factors taken in to consideration are discomfort factor and effort factor in limb movements. Discomfort factor measures the level of discomfort from the most neutral position of a given limb to the position of the corresponding limb after movement and effort factor is a measure of the displacement of the corresponding limbs from the original position. The basic aim is to optimize the movement of the limbs with the above mentioned cost functions. The effectiveness of the procedure is tested with an example of working procedure of workers used for stacking of fly ash bricks in a local fly ash bricks manufacturing unit. The objective is to find out the optimised movement of the limbs to reduce discomfort level and effort required of workers. The effectiveness of the procedure in this case study illustrated with the obtained results.

  17. A practical optimization procedure for radial BWR fuel lattice design using tabu search with a multiobjective function

    International Nuclear Information System (INIS)

    Francois, J.L.; Martin-del-Campo, C.; Francois, R.; Morales, L.B.

    2003-01-01

    An optimization procedure based on the tabu search (TS) method was developed for the design of radial enrichment and gadolinia distributions for boiling water reactor (BWR) fuel lattices. The procedure was coded in a computing system in which the optimization code uses the tabu search method to select potential solutions and the HELIOS code to evaluate them. The goal of the procedure is to search for an optimal fuel utilization, looking for a lattice with minimum average enrichment, with minimum deviation of reactivity targets and with a local power peaking factor (PPF) lower than a limit value. Time-dependent-depletion (TDD) effects were considered in the optimization process. The additive utility function method was used to convert the multiobjective optimization problem into a single objective problem. A strategy to reduce the computing time employed by the optimization was developed and is explained in this paper. An example is presented for a 10x10 fuel lattice with 10 different fuel compositions. The main contribution of this study is the development of a practical TDD optimization procedure for BWR fuel lattice design, using TS with a multiobjective function, and a strategy to economize computing time

  18. A novel design procedure for tractor clutch fingers by using optimization and response surface methods

    Energy Technology Data Exchange (ETDEWEB)

    Dogan, Oguz; Karpat, Fatih; Yuce, Celalettin; Kaya, Necmettin; Yavuz, Nurettin [Uludag University, Gorukle (Turkmenistan); Sen, Hasan [Valeo A. S., Bursa (Turkmenistan)

    2016-06-15

    This paper presents a methodology for re-designing a failed tractor transmission component subjected to cyclic loading. Unlike other vehicles, tractors cope with tough working conditions. Thus, it is necessary to re-design components by using modern optimization techniques. To extend their service life, we present a design methodology for a failed tractor clutch power take-off finger. The finger was completely re-designed using topology and shape optimization approach. Stress-life based fatigue analyses were performed. Shape optimization and response surface methodology were conducted to obtain optimum dimensions of the finger. Two design parameters were selected for the design of experiment method and 15 cases were analyzed. By using design of the experiment method, three responses were obtained: Maximum stresses, mass, and displacement depending on the selected the design parameters. After solving the optimization problem, we achieved a maximum stress and mass reduction of 14% and 6%, respectively. The stiffness was improved up to 31.6% compared to the initial design.

  19. Sampling design and procedures for fixed surface-water sites in the Georgia-Florida coastal plain study unit, 1993

    Science.gov (United States)

    Hatzell, H.H.; Oaksford, E.T.; Asbury, C.E.

    1995-01-01

    The implementation of design guidelines for the National Water-Quality Assessment (NAWQA) Program has resulted in the development of new sampling procedures and the modification of existing procedures commonly used in the Water Resources Division of the U.S. Geological Survey. The Georgia-Florida Coastal Plain (GAFL) study unit began the intensive data collection phase of the program in October 1992. This report documents the implementation of the NAWQA guidelines by describing the sampling design and procedures for collecting surface-water samples in the GAFL study unit in 1993. This documentation is provided for agencies that use water-quality data and for future study units that will be entering the intensive phase of data collection. The sampling design is intended to account for large- and small-scale spatial variations, and temporal variations in water quality for the study area. Nine fixed sites were selected in drainage basins of different sizes and different land-use characteristics located in different land-resource provinces. Each of the nine fixed sites was sampled regularly for a combination of six constituent groups composed of physical and chemical constituents: field measurements, major ions and metals, nutrients, organic carbon, pesticides, and suspended sediments. Some sites were also sampled during high-flow conditions and storm events. Discussion of the sampling procedure is divided into three phases: sample collection, sample splitting, and sample processing. A cone splitter was used to split water samples for the analysis of the sampling constituent groups except organic carbon from approximately nine liters of stream water collected at four fixed sites that were sampled intensively. An example of the sample splitting schemes designed to provide the sample volumes required for each sample constituent group is described in detail. Information about onsite sample processing has been organized into a flowchart that describes a pathway for each of

  20. German data for risk based fire safety assessment

    International Nuclear Information System (INIS)

    Roewekamp, M.; Berg, H.P.

    1998-01-01

    Different types of data are necessary to perform risk based fire safety assessments and, in particular, to quantify the fire event tree considering the plant specific conditions. Data on fire barriers, fire detection and extinguishing, including also data on secondary effects of a fire, have to be used for quantifying the potential hazard and damage states. The existing German database on fires in nuclear power plants (NPPs) is very small. Therefore, in general generic data, mainly from US databases, are used for risk based safety assessments. Due to several differences in the plant design and conditions generic data can only be used as conservative assumptions. World-wide existing generic data on personnel failures in case of fire fighting have only to be adapted to the plant specific conditions inside the NPP to be investigated. In contrary, unavailabilities of fire barrier elements may differ strongly depending on different standards, testing requirements, etc. In addition, the operational behaviour of active fire protection equipment may vary depending on type and manufacturer. The necessity for more detailed and for additional plant specific data was the main reason for generating updated German data on the operational behaviour of active fire protection equipment/features in NPPs to support risk based fire safety analyses being recommended to be carried out as an additional tool to deterministic fire hazard analyses in the frame of safety reviews. The results of these investigations revealed a broader and more realistic database for technical reliability of active fire protection means, but improvements as well as collection of further data are still necessary. (author)

  1. 41 CFR 101-4.135 - Designation of responsible employee and adoption of grievance procedures.

    Science.gov (United States)

    2010-07-01

    ... FINANCIAL ASSISTANCE Introduction § 101-4.135 Designation of responsible employee and adoption of grievance... 41 Public Contracts and Property Management 2 2010-07-01 2010-07-01 true Designation of... Property Management Federal Property Management Regulations System FEDERAL PROPERTY MANAGEMENT REGULATIONS...

  2. Task-Based EFL Language Teaching with Procedural Information Design in a Technical Writing Context

    Science.gov (United States)

    Roy, Debopriyo

    2017-01-01

    Task-based language learning (TBLL) has heavily influenced syllabus design, classroom teaching, and learner assessment in a foreign or second language teaching context. In this English as foreign language (EFL) learning environment, the paper discussed an innovative language learning pedagogy based on design education and technical writing. In…

  3. Maintenance evaluation using risk based criteria

    International Nuclear Information System (INIS)

    Torres Valle, A.

    1996-01-01

    The maintenance evaluation is currently performed by using economic and, in some case, technical equipment failure criteria, however this is done to a specific equipment level. In general, when statistics are used the analysis for maintenance optimization are made isolated and whit a post mortem character; The integration provided by mean of Probabilistic Safety assessment (PSA) together with the possibilities of its applications, allow for evaluation of maintenance on the basis of broader scope criteria in regard to those traditionally used. The evaluate maintenance using risk based criteria, is necessary to follow a dynamic and systematic approach, in studying the maintenance strategy, to allow for updating the initial probabilistic models, for including operational changes that often take place during operation of complex facilities. This paper proposes a dynamic evaluation system of maintenance task. The system is illustrated by means of a practical example

  4. Risk-based optimization of land reclamation

    International Nuclear Information System (INIS)

    Lendering, K.T.; Jonkman, S.N.; Gelder, P.H.A.J.M. van; Peters, D.J.

    2015-01-01

    Large-scale land reclamations are generally constructed by means of a landfill well above mean sea level. This can be costly in areas where good quality fill material is scarce. An alternative to save materials and costs is a ‘polder terminal’. The quay wall acts as a flood defense and the terminal level is well below the level of the quay wall. Compared with a conventional terminal, the costs are lower, but an additional flood risk is introduced. In this paper, a risk-based optimization is developed for a conventional and a polder terminal. It considers the investment and residual flood risk. The method takes into account both the quay wall and terminal level, which determine the probability and damage of flooding. The optimal quay wall level is found by solving a Lambert function numerically. The terminal level is bounded by engineering boundary conditions, i.e. piping and uplift of the cover layer of the terminal yard. It is found that, for a representative case study, the saving of reclamation costs for a polder terminal is larger than the increase of flood risk. The model is applicable to other cases of land reclamation and to similar optimization problems in flood risk management. - Highlights: • A polder terminal can be an attractive alternative for a conventional terminal. • A polder terminal is feasible at locations with high reclamation cost. • A risk-based approach is required to determine the optimal protection levels. • The depth of the polder terminal yard is bounded by uplifting of the cover layer. • This paper can support decisions regarding alternatives for port expansions.

  5. Methodology for risk-based analysis of technical specifications

    International Nuclear Information System (INIS)

    Vesely, W.E.; Gaertner, J.P.; Wagner, D.P.

    1985-01-01

    Part of the effort by EPRI to apply probabilistic risk assessment methods and results to the solution of utility problems involves the investigation of methods for risk-based analysis of technical specifications. The culmination of this investigation is the SOCRATES computer code developed by Battelle's Columbus Laboratories to assist in the evaluation of technical specifications of nuclear power plants. The program is designed to use information found in PRAs to re-evaluate risk for changes in component allowed outage times (AOTs) and surveillance test intervals (STIs). The SOCRATES program is a unique and important tool for technical specification evaluations. The detailed component unavailability model allows a detailed analysis of AOT and STI contributions to risk. Explicit equations allow fast and inexpensive calculations. Because the code is designed to accept ranges of parameters and to save results of calculations that do not change during the analysis, sensitivity studies are efficiently performed and results are clearly displayed

  6. D0 Silicon Upgrade: End Calorimeter Transfer Bridge Design and Installation Procedures

    International Nuclear Information System (INIS)

    Stredde, H.J.

    1991-01-01

    elevated to the level of the transfer bridge. The elevation process is the same as that used for the CC installation. When the correct elevation is attained the transporter extensions are positioned and fastened to the transporter on the south side. Static column supports will be added underneath the transporter to minimize deflections as the NEC is rolled off. The carriage extensions are now put in place and the Hilman rollers transferred into position under the extensions. The NEC is now ready to be pulled off of the transporter and onto the transfer bridge. Again using the Cyl. and chain mechanism, with the anchor point attached to the transporter extension on the north sidewalk, pull the NEC completely off of the transporter and onto the transfer bridge. Once the NEC is on the transfer bridge a rearrangement of equipment must be done. The transporter extension on the north sidewalk is decoupled from the transfer bridge and moved against the wall of the fixed counting area. The transporter extension at the south end of the transporter is removed, the transporter is decoupled from and moved to the north side of the transfer bridge. The transporter is supported from the floor at an elevation equal to the transfer bridge and coupled to it. The transporter extension is fastened to the north end of the transporter. The movement of the NEC now continues until it is back on the transporter. At this time the transfer bridge, concrete shield blocks and steel plates in the pit are removed. The detector is moved back to its normal parked position(cable bridge up). The NEC is lowered to the sidewalk (reverse of elevation procedure). Welding of the heads is then finished prior to final installation on the center beam. The final installation is identical to the CC installation, using all the same equipment. The finite element analysis of the transfer bridge design was done by Kay Weber of the Accelerator Mechanical Support Group.

  7. Analysis, Verification, and Application of Equations and Procedures for Design of Exhaust-pipe Shrouds

    Science.gov (United States)

    Ellerbrock, Herman H.; Wcislo, Chester R.; Dexter, Howard E.

    1947-01-01

    Investigations were made to develop a simplified method for designing exhaust-pipe shrouds to provide desired or maximum cooling of exhaust installations. Analysis of heat exchange and pressure drop of an adequate exhaust-pipe shroud system requires equations for predicting design temperatures and pressure drop on cooling air side of system. Present experiments derive such equations for usual straight annular exhaust-pipe shroud systems for both parallel flow and counter flow. Equations and methods presented are believed to be applicable under certain conditions to the design of shrouds for tail pipes of jet engines.

  8. Ultra High-Performance Fiber-Reinforced Concrete (UHPFRC: a review of material properties and design procedures

    Directory of Open Access Journals (Sweden)

    T. E. T. Buttignol

    Full Text Available ABSTRACT This paper does a review of the recent achievements on the knowledge of UHPFRC properties and in the development of design procedures. UHPFRC is defined as a new material, with unique properties (high ductility, low permeability, very high strength capacity in compression, higher toughness in comparison to conventional concrete. It is important to know both material and mechanical properties to fully take advantage of its outstanding properties for structural applications. However, since this is a new material, the current design codes are not well suited and should be reviewed before being applied to UHPFRC. In the first part, the following material properties are addressed: hydration process; permeability; fibers role; mix design; fiber-matrix bond properties workability; mixing procedure; and curing. In the second part, the mechanical properties of the material are discussed, together with some design recommendations. The aspects herein examined are: size effect; compressive and flexural strength; tensile stress-strain relation; shear and punching shear capacity; creep and shrinkage; fracture energy; steel bars anchorage and adherence. Besides, the tensile mechanical characterization is described using inverse analysis based on bending tests data. In the last part, material behavior at high temperature is discussed, including physical-chemical transformations of the concrete, spalling effect, and transient creep. In the latter case, a new Load Induced Thermal Strain (LITS semi-empirical model is described and compared with UHPC experimental results.

  9. Tools for Designing, Evaluating, and Certifying NextGen Technologies and Procedures: Automation Roles and Responsibilities

    Science.gov (United States)

    Kanki, Barbara G.

    2011-01-01

    Barbara Kanki from NASA Ames Research Center will discuss research that focuses on the collaborations between pilots, air traffic controllers and dispatchers that will change in NextGen systems as automation increases and roles and responsibilities change. The approach taken by this NASA Ames team is to build a collaborative systems assessment template (CSAT) based on detailed task descriptions within each system to establish a baseline of the current operations. The collaborative content and context are delineated through the review of regulatory and advisory materials, policies, procedures and documented practices as augmented by field observations and interviews. The CSAT is developed to aid the assessment of key human factors and performance tradeoffs that result from considering different collaborative arrangements under NextGen system changes. In theory, the CSAT product may be applied to any NextGen application (such as Trajectory Based Operations) with specified ground and aircraft capabilities.

  10. What procedure to choose while designing a fuzzy control? Towards mathematical foundations of fuzzy control

    Science.gov (United States)

    Kreinovich, Vladik YA.; Quintana, Chris; Lea, Robert

    1991-01-01

    Fuzzy control has been successfully applied in industrial systems. However, there is some caution in using it. The reason is that it is based on quite reasonable ideas, but each of these ideas can be implemented in several different ways, and depending on which of the implementations chosen different results are achieved. Some implementations lead to a high quality control, some of them not. And since there are no theoretical methods for choosing the implementation, the basic way to choose it now is experimental. But if one chooses a method that is good for several examples, there is no guarantee that it will work fine in all of them. Hence the caution. A theoretical basis for choosing the fuzzy control procedures is provided. In order to choose a procedure that transforms a fuzzy knowledge into a control, one needs, first, to choose a membership function for each of the fuzzy terms that the experts use, second, to choose operations of uncertainty values that corresponds to 'and' and 'or', and third, when a membership function for control is obtained, one must defuzzy it, that is, somehow generate a value of the control u that will be actually used. A general approach that will help to make all these choices is described: namely, it is proved that under reasonable assumptions membership functions should be linear or fractionally linear, defuzzification must be described by a centroid rule and describe all possible 'and' and 'or' operations. Thus, a theoretical explanation of the existing semi-heuristic choices is given and the basis for the further research on optimal fuzzy control is formulated.

  11. Description of design and operating procedures of small scale pulsed columns for experimental study on extraction process under abnormal conditions

    International Nuclear Information System (INIS)

    Wakamatsu, Sachio; Sato, Makoto; Kubo, Nobuo; Sakurai, Satoshi; Ami, Norio

    1990-09-01

    To study transient phenomena in a pulsed column co-decontamination process under abnormal conditions, a pair of small scale pulsed columns (effective extraction section; I.D: 25 mm, H.: 2260 mm) for extraction and scrub were installed in the laboratory. An evaporator of aqueous uranium solution was also equipped to reuse concentrated solution as the feed. This report describes several items to have been carefully treated in design, specification and operating procedure of the apparatuses for the experiments. Also described are the procedures for preparation of the feed solutions and treatments of the solutions after the experiments; back-extraction of uranium, diluent washing, alkaline washing and concentration of uranium solution. (author)

  12. Study on Design and Implementation of JAVA Programming Procedural Assessment Standard

    Science.gov (United States)

    Tingting, Xu; Hua, Ma; Xiujuan, Wang; Jing, Wang

    2015-01-01

    The traditional JAVA course examination is just a list of questions from which we cannot know students' skills of programming. According to the eight abilities in curriculum objectives, we designed an assessment standard of JAVA programming course that is based on employment orientation and apply it to practical teaching to check the teaching…

  13. Design procedures for solid-liquid extractors and the effect of hydrodynamic instabilities on extractor performance

    NARCIS (Netherlands)

    Spaninks, J.A.M.

    1979-01-01

    A design method is proposed for countercurrent mass transfer cascades with crossflow stages, and unsteady operated fixed beds in a countercurrent arrangement. The separation performance of these cascades is calculated from mathematical models and compared with a purely countercurrent

  14. The design procedures on brick building against surface ground deformations due to mining and earthquake

    Energy Technology Data Exchange (ETDEWEB)

    Zhong, J.; Yang, S. (China University of Mining and Technology (China))

    1992-05-01

    By analysing the effects of ground motion and deformation on surface buildings, and drawing on the experience of damages caused by the Tangshan and Chenhai earthquakes, the authors discuss the design of brick and concrete buildings which are protected against the damaging effects of both earthquakes and mining activities. 5 figs.

  15. Maintenance Procedures for North American Visually-graded Dimension Lumber Design Values

    Science.gov (United States)

    David Kretschmann; Don DeVisser; Kevin Cheung; Bob Browder; Al Rozek

    2014-01-01

    ASTM International D1990 Standard Practice for Establishing Allowable Properties for Visually-Graded Dimension Lumber from In-Grade Tests of Full-Size Specimens, that governs the development of design values for dimension lumber in North America, was first adopted in 1991with recognition that the resource and manufacturing of lumber could change over time impacting...

  16. Design procedure for millimeter-wave InP DHBT stacked power amplifiers

    DEFF Research Database (Denmark)

    Squartecchia, Michele; Johansen, Tom Keinicke; Midili, Virginio

    2015-01-01

    The stacked-transistor concept for power amplifiers (PA) has been investigated in this work. Specifically, this architecture has been applied in the design of millimeter-wave monolithic microwave integrated circuits (MMICs) using indium phosphide (InP) double heterojunction bipolar transistors...

  17. Risk-based regulation: A regulatory perspective

    International Nuclear Information System (INIS)

    Scarborough, J.C.

    1993-01-01

    In the early development of regulations for nuclear power plants, risk was implicitly considered through qualitative assessments and engineering reliability principles and practices. Examples included worst case analysis, defense in depth, and the single failure criterion. However, the contributions of various systems, structures, components and operator actions to plant safety were not explicitly assessed since a methodology for this purpose had not been developed. As a consequence of the TMI accident, the use of more quantitative risk methodology and information in regulation such as probabilistic risk analysis (PRA) increased. The use of both qualitative and quantitative consideration of risk in regulation has been a set of regulations and regulatory guides and practices that ensure adequate protection of public health and safety. Presently, the development of PRA techniques has developed to the point that safety goals, expressed in terms of risk, have been established to help guide further regulatory decision making. This paper presents the personal opinions of the author as regards the use of risk today in nuclear power plant regulation, areas of further information needs, and necessary plans for moving toward a more systematic use of risk-based information in regulatory initiatives in the future

  18. Risk-based plant performance indicators

    International Nuclear Information System (INIS)

    Boccio, J.L.; Azarm, M.A.; Hall, R.E.

    1991-01-01

    Tasked by the 1979 President's Commission on the Accident at Three Mile Island, the U.S. nuclear power industry has put into place a performance indicator program as one means for showing a demonstrable record of achievement. Largely through the efforts of the Institute of Nuclear Power Operations (INPO), plant performance data has, since 1983, been collected and analyzed to aid utility management in measuring their plants' performance progress. The U.S. Nuclear Regulatory Commission (NRC) has also developed a set of performance indicators. This program, conducted by NRC's Office for the Analysis and Evaluation of Operational Data (AEOD), is structured to present information on plant operational performance in a manner that could enhance the staff's ability to recognize changes in the safety performance. Both organizations recognized that performance indicators have limitations and could be subject to misinterpretation and misuse with the potential for an adverse impact on safety. This paper reports on performance indicators presently in use, e.g., unplanned automatic scrams, unplanned safety system actuation, safety system failures, etc., which are logically related to safety. But, a reliability/risk-based method for evaluating either individual indicators or an aggregated set of indicators is not yet available

  19. Project transition to risk based corrective action

    International Nuclear Information System (INIS)

    Judge, J.M.; Cormier, S.L.

    1996-01-01

    Many states have adopted or are considering the adoption of the America Society for Testing and Materials (ASTM) Standard E 1739, Standard for Risk Based Corrective Action (RBCA) Applied to Petroleum Release Sites. This standard is being adopted to regulate leaking underground storage tank (LUST) sites. The case studies of two LUST sites in Michigan will be presented to demonstrate the decision making process and limiting factors involved in transitioning sites to the RBCA program. Both of these case studies had been previously investigated and one was actively remediated. The first case study involves a private petroleum facility where soil and ground water have been impacted. Remediation involved a ground water pump and treat system. Subsequent monitoring during system operation indicated that analytical data were still above the Tier 1 RBSLs but below the Tier 2 SSTLs. The closure strategy that was developed was based on the compounds of concern that were below the SSTLs. A deed restriction was also developed for the site as an institutional control. The second LUST site exhibited BTEX concentrations in soil and ground water above the Tier 1 RBSLs. Due to the exceedence of the Tier 1 RBSLs, the second site required a Tier 2 assessment to develop SSTLs as remedial objectives and remove hot spots in the soil and treat the ground water to achieve closure. Again, a deed restriction was instituted along with a performance monitoring plan

  20. Design Procedure Enhanced with Numerical Modeling to Mitigate River-Bank Erosion

    Directory of Open Access Journals (Sweden)

    Elhakeem Mohamed

    2016-01-01

    Full Text Available In this study, the 2D Finite Element Surface Water Modeling System (FESWMS is used to design barb structures to mitigate river bank erosion in a stream reach located on the Raccoon River near Adel, Iowa, USA just upstream of the US Highway Bridge 169. FESWMS is used also to access the barbs effect on the study reach. The model results showed that the proposed barb structures successfully reduced the flow velocity along the outside bank and increased the velocity in the center of the stream, thereby successfully increased the conveyance towards the core of the river. The estimated velocities values along the river-banks where the barbs exist were within the recommended values for channel stability design. Thus, the barb structures were able to reduce the erosion along the bankline.

  1. Design procedures of small pebble bed HTGR for electric generation in isolated islands

    International Nuclear Information System (INIS)

    Liem, P.H.

    1996-01-01

    This paper gives the summary report on the results of the study mentioned above. Two conventional fueling strategies for PBRs, that is, the multipass and the Once-Through-Then-Out (OTTO) fueling schemes were investigated, although the HTR-Module design adopts the multipass scheme. In addition to the two fueling schemes, the recently proposed peu a peu fueling scheme (Teuchert et al., 1991) was also included in the study since it simplifies significantly the fueling mechanism and devices of the reactors. Furthermore, despite the HTR-Module design uses only uranium fuel cycles, for sake of completion of the work, both uranium and thorium fuel cycles were considered for each fueling scheme in the present work. (J.P.N.)

  2. Single-subject withdrawal designs in delayed matching-to-sample procedures

    OpenAIRE

    Eilifsen, Christoffer; Arntzen, Erik

    2011-01-01

    In most studies of delayed matching-to-sample (DMTS) and stimulus equivalence, the delay has remained fixed throughout a single experimental condition. We wanted to expand on the DMTS and stimulus equivalence literature by examining the effects of using titrating delays with different starting points during the establishment of conditional discriminations prerequisite for stimulus equivalence. In Experiment 1, a variation of a single-subject withdrawal design was used. Ten adults were exposed...

  3. A Nondominated Genetic Algorithm Procedure for Multiobjective Discrete Network Design under Demand Uncertainty

    OpenAIRE

    Changzhi, Bian

    2015-01-01

    This paper addresses the multiobjective discrete network design problem under demand uncertainty. The OD travel demands are supposed to be random variables with the given probability distribution. The problem is formulated as a bilevel stochastic optimization model where the decision maker’s objective is to minimize the construction cost, the expectation, and the standard deviation of total travel time simultaneously and the user’s route choice is described using user equilibrium model on the...

  4. Earthquake insurance pricing: a risk-based approach.

    Science.gov (United States)

    Lin, Jeng-Hsiang

    2018-04-01

    Flat earthquake premiums are 'uniformly' set for a variety of buildings in many countries, neglecting the fact that the risk of damage to buildings by earthquakes is based on a wide range of factors. How these factors influence the insurance premiums is worth being studied further. Proposed herein is a risk-based approach to estimate the earthquake insurance rates of buildings. Examples of application of the approach to buildings located in Taipei city of Taiwan were examined. Then, the earthquake insurance rates for the buildings investigated were calculated and tabulated. To fulfil insurance rating, the buildings were classified into 15 model building types according to their construction materials and building height. Seismic design levels were also considered in insurance rating in response to the effect of seismic zone and construction years of buildings. This paper may be of interest to insurers, actuaries, and private and public sectors of insurance. © 2018 The Author(s). Disasters © Overseas Development Institute, 2018.

  5. Development of processing procedure preparing for digital computer controlled equipment on modular design base

    International Nuclear Information System (INIS)

    Starosel'tsev, O.P.; Khrundin, V.I.

    1982-01-01

    In order to reduce labour consumption of technological preparation of production for digital computer controlled machines during the treatment of steam turbines articles created is a system of modular design of technological processes and controlling programs. A set of typical modulas-transitions, being a number of surfaces of an articles treated with one cutting tool in optimum sequence, and a library of cutting tools are the base of the system. Introduction of such a system sharply enhaneces the efficiency of the equipment utilization [ru

  6. Fabrication Procedures and Birefringence Measurements for Designing Magnetically Responsive Lanthanide Ion Chelating Phospholipid Assemblies.

    Science.gov (United States)

    Isabettini, Stéphane; Baumgartner, Mirjam E; Fischer, Peter; Windhab, Erich J; Liebi, Marianne; Kuster, Simon

    2018-01-03

    Bicelles are tunable disk-like polymolecular assemblies formed from a large variety of lipid mixtures. Applications range from membrane protein structural studies by nuclear magnetic resonance (NMR) to nanotechnological developments including the formation of optically active and magnetically switchable gels. Such technologies require high control of the assembly size, magnetic response and thermal resistance. Mixtures of 1,2-dimyristoyl-sn-glycero-3-phosphocholine (DMPC) and its lanthanide ion (Ln 3+ ) chelating phospholipid conjugate, 1,2-dimyristoyl-sn-glycero-3-phospho-ethanolamine-diethylene triaminepentaacetate (DMPE-DTPA), assemble into highly magnetically responsive assemblies such as DMPC/DMPE-DTPA/Ln 3+ (molar ratio 4:1:1) bicelles. Introduction of cholesterol (Chol-OH) and steroid derivatives in the bilayer results in another set of assemblies offering unique physico-chemical properties. For a given lipid composition, the magnetic alignability is proportional to the bicelle size. The complexation of Ln 3+ results in unprecedented magnetic responses in terms of both magnitude and alignment direction. The thermo-reversible collapse of the disk-like structures into vesicles upon heating allows tailoring of the assemblies' dimensions by extrusion through membrane filters with defined pore sizes. The magnetically alignable bicelles are regenerated by cooling to 5 °C, resulting in assembly dimensions defined by the vesicle precursors. Herein, this fabrication procedure is explained and the magnetic alignability of the assemblies is quantified by birefringence measurements under a 5.5 T magnetic field. The birefringence signal, originating from the phospholipid bilayer, further enables monitoring of polymolecular changes occurring in the bilayer. This simple technique is complementary to NMR experiments that are commonly employed to characterize bicelles.

  7. The design, effectiveness and acceptability of the arm sleeve for the prevention of body fluid contamination during obstetric procedures.

    Science.gov (United States)

    Kabukoba, J J; Pearce, J M

    1993-08-01

    1. To design a device that would reduce contamination of staff during obstetric procedures. 2. To undertake clinical trials to assess the effectiveness and acceptability of such a device. A prospective study. The arm sleeve is made of a nonwoven material laminated on polyethylene film making it waterproof. It has an elastomeric cuff with adhesive that ensures a watertight seal between it and the glove. Delivery suite in a teaching hospital. Doctors and midwives were requested to wear the sleeve on top of the standard gown and gloves. Each user was assessed for blood contamination at the end of the procedure and a questionnaire detailing the extent of contamination and the views of the user was completed. Eighty questionnaires were completed. The contamination of arms and hands was 3.8% and 5%, respectively. Eighty-nine percent thought the sleeve had served its purpose and 76% said they would use it regularly. The sleeve is an effective protective device which complements the glove and gown. We recommend that it should be used during all obstetric procedures.

  8. Design procedure for a wind-wheel with self-adjusting blade mechanism

    Directory of Open Access Journals (Sweden)

    Gennady A. Oborsky

    2014-12-01

    Full Text Available Developed is a wind-wheel design equipped with the self-adjusting blade. The blade is positioned eccentrically to the balance wheel and can freely rotate around its axis. Elaborated is the method of calculating the energy characteristics for a wind-wheel with the self-adjusting blade, considering not only the wind force but the force of air counter flow resistance to the blade’s rotation. Initially, the blade being located at an angle α = 45 to the wheel rotation plane, the air flow rotates the wheel with the maximum force. Thus, the speed of rotation increases that involves the increase in air counter flow resistance and results in blade turning with respective angle α reduction. This, consequently, reduces the torque. When the torsional force and the resistance enter into equilibrium, the blade takes a certain angle α, and the wheel speed becomes constant. This wind-wheel design including a self-adjusting blade allows increasing the air flow load ratio when compared to the wind-wheel equipped with a jammed blade.

  9. Analytical procedure in aseismic design of eccentric structure using response spectrum

    International Nuclear Information System (INIS)

    Takemori, T.; Kuwabara, Y.; Suwabe, A.; Mitsunobu, S.

    1977-01-01

    In this paper, the response are evaluated by the following two methods by the use of the typical torsional analytical models in which masses, rigidities, eccentricities between the centers thereof and several actual earthquake waves are taken as the parameters: (1) the root mean square of responses by using the response spectra derived from the earthquake waves, (2) the time history analysis by using the earthquake wave. The earthquake waves used are chosen to present the different frequency content and magnitude of the response spectra. The typical results derived from the study are as follows: (a) the response accelerations of mass center in the input earthquake direction by the (1) method coincide comparatively well with those by the (2) method, (b) the response accelerations perpendicular to the input earthquake direction by (1) method are 2 to 3 times as much as those by the (2) method, (c) the amplification of the response accelerations at arbitrary points distributed on the spread mass to those of center of the lumped mass by the (1) method are remarkably large compared with those by the (2) method in both directions respectively. These problems on the response spectrum analysis for the above-mentioned eccentric structure are discussed, and an improved analytical method applying the amplification coefficients of responses derived from this parametric time history analysis is proposed to the actual seismic design by the using of the given design ground response spectrum with root mean square technique

  10. Technical procedures for template-guided surgery for mandibular reconstruction based on digital design and manufacturing.

    Science.gov (United States)

    Liu, Yun-feng; Xu, Liang-wei; Zhu, Hui-yong; Liu, Sean Shih-Yao

    2014-05-23

    The occurrence of mandibular defects caused by tumors has been continuously increasing in China in recent years. Conversely, results of the repair of mandibular defects affect the recovery of oral function and patient appearance, and the requirements for accuracy and high surgical quality must be more stringent. Digital techniques--including model reconstruction based on medical images, computer-aided design, and additive manufacturing--have been widely used in modern medicine to improve the accuracy and quality of diagnosis and surgery. However, some special software platforms and services from international companies are not always available for most of researchers and surgeons because they are expensive and time-consuming. Here, a new technical solution for guided surgery for the repair of mandibular defects is proposed, based on general popular tools in medical image processing, 3D (3 dimension) model reconstruction, digital design, and fabrication via 3D printing. First, CT (computerized tomography) images are processed to reconstruct the 3D model of the mandible and fibular bone. The defect area is then replaced by healthy contralateral bone to create the repair model. With the repair model as reference, the graft shape and cutline are designed on fibular bone, as is the guide for cutting and shaping. The physical model, fabricated via 3D printing, including surgical guide, the original model, and the repair model, can be used to preform a titanium locking plate, as well as to design and verify the surgical plan and guide. In clinics, surgeons can operate with the help of the surgical guide and preformed plate to realize the predesigned surgical plan. With sufficient communication between engineers and surgeons, an optimal surgical plan can be designed via some common software platforms but needs to be translated to the clinic. Based on customized models and tools, including three surgical guides, preformed titanium plate for fixation, and physical models of

  11. A procedure for the determination of scenario earthquakes for seismic design based on probabilistic seismic hazard analysis

    International Nuclear Information System (INIS)

    Hirose, Jiro; Muramatsu, Ken

    2002-03-01

    This report presents a study on the procedures for the determination of scenario earthquakes for seismic design of nuclear power plants (NPPs) based on probabilistic seismic hazard analysis (PSHA). In the recent years, the use of PSHA, which is a part of seismic probabilistic safety assessment (PSA), to determine the design basis earthquake motions for NPPs has been proposed. The identified earthquakes are called probability-based scenario earthquakes (PBSEs). The concept of PBSEs originates both from the study of US NRC and from Ishikawa and Kameda. The assessment of PBSEs is composed of seismic hazard analysis and identification of dominant earthquakes. The objectives of this study are to formulate the concept of PBSEs and to examine the procedures for determining the PBSEs for a domestic NPP site. This report consists of three parts, namely, procedures to compile analytical conditions for PBSEs, an assessment to identify PBSEs for a model site using the Ishikawa's concept and the examination of uncertainties involved in analytical conditions. The results obtained from the examination of PBSEs using Ishikawa's concept are as follows. (a) Since PBSEs are expressed by hazard-consistent magnitude and distance in terms of a prescribed reference probability, it is easy to obtain a concrete image of earthquakes that determine the ground response spectrum to be considered in the design of NPPs. (b) Source contribution factors provide the information on the importance of the earthquake source regions and/or active faults, and allows the selection of a couple of PBSEs based on their importance to the site. (c) Since analytical conditions involve uncertainty, sensitivity analyses on uncertainties that would affect seismic hazard curves and identification of PBSEs were performed on various aspects and provided useful insights for assessment of PBSEs. A result from this sensitivity analysis was that, although the difference in selection of attenuation equations led to a

  12. Accurate monitoring developed by EDF for FA-3-EPRTM and UK-EPRTM: chemistry-radiochemistry design and procedures

    International Nuclear Information System (INIS)

    Tigeras, Arancha; Bouhrizi, Sofia; Pierre, Marine; L'Orphelin, Jean-Matthieu

    2012-09-01

    The monitoring of chemistry and radiochemistry parameters is a fundamental need in nuclear power plants in order to ensure: - The reactivity control in real time, - The barrier integrity surveillance by means of the fuel cladding failures detection and the primary-pressure boundary components control, - The water quality to limit the radiation build-up and the material corrosion permitting to prepare the maintenance, radioprotection and waste operations. - The efficiency of treatment systems and hence the minimization of chemical and radiochemical substances discharges The relevant chemistry and radiochemistry parameters to be monitored are selected depending on the chemistry conditioning of systems, the source term evaluations, the corrosion mechanisms and the radioactivity consequences. In spite of the difficulties for obtaining representative samples under all circumstances, the EPR M design provides the appropriate provisions and analytical procedures for ensuring the reliable and accurate monitoring of parameters in compliance with the specification requirements. The design solutions, adopted for Flamanville 3-EPR M and UK-EPR M , concerning the sampling conditions and locations, the on-line and analytical equipment, the procedures and the results transmission to control room and chemistry laboratory are supported by ALARP considerations, international experience and researches concerning the nuclides behavior (corrosion product and actinides solubility, fission product degassing, impurities and additives reactions also). This paper details the means developed by EDF for making successful and meaningful sampling and measurements to achieve the essential objectives associated with the monitoring. (authors)

  13. Comparison of closed-cell and hybrid-cell stent designs in carotid artery stenting: clinical and procedural outcomes

    Directory of Open Access Journals (Sweden)

    Ersan TatlI

    2017-05-01

    Full Text Available Introduction: Carotid artery stenting (CAS is a promising alternative to surgery in high-risk patients. However, the impact of stent cell design on outcomes in CAS is a matter of continued debate. Aim : To compare the periprocedural and clinical outcomes of different stent designs for CAS with distal protection devices. Material and methods : All CAS procedures with both closed- and hybrid-cell stents performed at our institution between February 2010 and December 2015 were analyzed retrospectively. Adverse events were defined as death, major stroke, minor stroke, transient ischemic attack and myocardial infarction. Periprocedural and 30-day adverse events and internal carotid artery (ICA vasospasm rates were compared between the closed-cell and hybrid-cell stent groups. Results : The study included 234 patients comprising 146 patients with a closed-cell stent (Xact stent, Abbott Vascular (mean age: 68.5 ±8.6; 67.1% male and 88 patients with a hybrid-cell stent (Cristallo Ideale, Medtronic (mean age: 67.2 ±12.8; 68.2% male. There was no significant difference between the groups with respect to periprocedural or 30-day adverse event rates. While there was no difference in terms of tortuosity index between the groups, there was a higher procedural ICA vasospasm rate in the closed-cell stent group (35 patients, 23% compared with the hybrid-cell stent group (10 patients, 11% (p = 0.017. Conclusions : The results of this study showed no significant difference in the clinical adverse event rates after CAS between the closed-cell stent group and the hybrid-cell stent group. However, procedural ICA vasospasm was more common in the closed-cell stent group.

  14. Development of an engineering design process and associated systems and procedures for a UK geological disposal facility - 59160

    International Nuclear Information System (INIS)

    Rendell, Philip; Breen, Brendan; Clark, Alastair; Reece, Steve; O'Grady, Henry

    2012-01-01

    implemented for the identification, capture, analysis, update, verification, validation and acceptance of requirements for the GDF. This is to ensure that there are traceable links between requirements, and to identify and record the verification/ validation of individual requirements. This paper describes the engineering design process and the supporting documents, systems and procedures. The paper addresses the relationship to the geological disposal programme timeline in 'Geological Disposal - Steps towards implementation' and, from there, to the UK Government 'Managing Radioactive Waste Safely' Programme. It also describes the next steps in the development of the design process, and some of the lessons learnt to date. (authors)

  15. Cost effectiveness of risk-based closures at UST sites

    International Nuclear Information System (INIS)

    Scruton, K.M.; Baker, J.N.

    1995-01-01

    Risk-based closures have been achieved at Underground Storage Tank (UST) sites throughout the country for a major transportation company. The risk-based closures were cost-effective because a streamlined risk-based approach was used instead of the generic baseline risk assessment approach. USEPA has recently provided guidance encouraging the use of risk-based methodology for achieving closure at UST sites. The risk-based approach used in achieving the site closures involved an identification of potential human and ecological receptors and exposure pathways, and a comparison of maximum onsite chemical concentrations to applicable or relevant and appropriate requirements (ARARs). The ARARs used in the evaluation included Federal and/or State Maximum Contaminant Levels (MCLs) for groundwater and risk-based screening levels for soils. If the maximum concentrations were above the screening levels, a baseline risk assessment was recommended. In several instances, however, the risk-based approach resulted in a regulatory agency acceptance of a ''no further action'' alternative at UST sites which did not pose a significant threat to human health and the environment. The cost of the streamlined risk-based approach is approximately $3,500, while a baseline risk assessment for the same UST site could cost up to $10,000 or more. The use of the streamlined risk-based approach has proven to be successful for achieving a ''no further action'' outcome for the client at a reasonable cost

  16. Constraints on LISA Pathfinder's Self-Gravity: Design Requirements, Estimates and Testing Procedures

    Science.gov (United States)

    Armano, M.; Audley, H.; Auger, G.; Baird, J.; Binetruy, P.; Born, M.; Bortoluzzi, M.; Brandt, Nico; Bursi, Alessandro; Slutsky. J.; hide

    2016-01-01

    LISA Pathfinder satellite was launched on 3 December 2015 toward the Sun Earth first Lagrangian point (L1) where the LISA Technology Package (LTP), which is the main science payload, will be tested. LTP achieves measurements of differential acceleration of free-falling test masses (TMs) with sensitivity below 3 x 10(exp -14) m s(exp -2) Hz(exp - 1/2) within the 130 mHz frequency band in one dimension. The spacecraft itself is responsible for the dominant differential gravitational field acting on the two TMs. Such a force interaction could contribute a significant amount of noise and thus threaten the achievement of the targeted free-fall level. We prevented this by balancing the gravitational forces to the sub nm s(exp -2) level, guided by a protocol based on measurements of the position and the mass of all parts that constitute the satellite, via finite element calculation tool estimates. In this paper, we will introduce the gravitational balance requirements and design, and then discuss our predictions for the balance that will be achieved in flight.

  17. A Nondominated Genetic Algorithm Procedure for Multiobjective Discrete Network Design under Demand Uncertainty

    Directory of Open Access Journals (Sweden)

    Bian Changzhi

    2015-01-01

    Full Text Available This paper addresses the multiobjective discrete network design problem under demand uncertainty. The OD travel demands are supposed to be random variables with the given probability distribution. The problem is formulated as a bilevel stochastic optimization model where the decision maker’s objective is to minimize the construction cost, the expectation, and the standard deviation of total travel time simultaneously and the user’s route choice is described using user equilibrium model on the improved network under all scenarios of uncertain demand. The proposed model generates globally near-optimal Pareto solutions for network configurations based on the Monte Carlo simulation and nondominated sorting genetic algorithms II. Numerical experiments implemented on Nguyen-Dupuis test network show trade-offs among construction cost, the expectation, and standard deviation of total travel time under uncertainty are obvious. Investment on transportation facilities is an efficient method to improve the network performance and reduce risk under demand uncertainty, but it has an obvious marginal decreasing effect.

  18. Radiation Hardening and Verification Procedure for Compact Flip-Flop Design

    Energy Technology Data Exchange (ETDEWEB)

    Kwon, Inyong; Sung, Seung Hwan [Korea Atomic Energy Research Institute, Daejeon (Korea, Republic of)

    2016-10-15

    For radiation-related applications applying electronic devices in nuclear, space, medicine, and scientific experiment, single event transients (SETs) and single event upsets (SEUs) are become primary concern since they can cause malfunctions in a system by affecting the signal transition and flipping digital bits. The D flip-flop as a register is generally used in digital circuits that require data stability and high speed. For many years, radiation-hardened-by-design (RHBD) circuits have been gradually developed from traditional circuit architectures. One of common methods is to exploit redundancy in an important circuit block to preserve the correct signal. This technique uses a voting process to have a correct output when other duplicated systems fail due to a single event effect (SEE) including SET and SEU. For instance, B. Olson applied the redundancy technique, formally referred the triple modular redundancy (TMR). Other researchers use various error detection and correction (EDAC) algorithms including redundant bits in the storage circuits to detect and correct errors at the system level. practical experiments at radiation exposure facilities. Korea Atomic Energy Research Institute (KAERI) operates a laboratory with high energy radioactive isotope, {sup 60}Co in Jeongeup, Korea. The facility can provide various experiments requiring experimental environment changes by controlling radiation activity and radiated energy. The future direction on RHBD circuits would be integration with the digital DFF presented in this paper and analog front-end units such as OP-amp for charge sensitive or shaping amplifier. Analog-to-digital converters (ADCs) are also major components necessarily imbedded in the most of sensor related electronics. Thus RHBD techniques are inevitably required to protect these circuits from SEE; specifically, SEUs for digital logics and SETs for analog signals. Since most ADCs consist of both analog and digital circuits in their architectures

  19. Pedestrian safety management using the risk-based approach

    Directory of Open Access Journals (Sweden)

    Romanowska Aleksandra

    2017-01-01

    Full Text Available The paper presents a concept of a multi-level pedestrian safety management system. Three management levels are distinguished: strategic, tactical and operational. The basis for the proposed approach to pedestrian safety management is a risk-based method. In the approach the elements of behavioural and systemic theories were used, allowing for the development of a formalised and repeatable procedure integrating the phases of risk assessment and response to the hazards of road crashes involving pedestrians. Key to the method are tools supporting pedestrian safety management. According to the risk management approach, the tools can be divided into two groups: tools supporting risk assessment and tools supporting risk response. In the paper attention is paid to selected tools supporting risk assessment, with particular emphasis on the methods for estimating forecasted pedestrian safety measures (at strategic, national and regional level and identification of particularly dangerous locations in terms of pedestrian safety at tactical (regional and local and operational level. The proposed pedestrian safety management methods and tools can support road administration in making rational decisions in terms of road safety, safety of road infrastructure, crash elimination measures or reducing the consequences suffered by road users (particularly pedestrians as a result of road crashes.

  20. RIMAP demonstration project. Risk-based life management of piping system in power plant Heilbronn

    International Nuclear Information System (INIS)

    Bareiss, J.; Buck, P.; Matschecko, B.; Jovanovic, A.; Balos, D.; Perunicic, M.

    2004-01-01

    In the framework of EU project RIMAP [Risk Based Inspection and Maintenance Procedures for European Industry (2000)] a new European Guideline for optimized risk based maintenance and inspection planning of industrial plants (RBLM, Risk Based Life Management) is being developed. The RIMAP project consists of the three clustered projects: - development (RTD); - demonstration (DEMO): - thematic network (TN). Current work and future, planned work in RIMAP demonstration project on applications of the RIMAP methodology in power plants are presented briefly in the first part of the paper. Also presented in the paper are the results of a preliminary analysis of piping system in power plant Heilbronn using the concept of risk-based monitoring as part of overall concept of risk-based life management. Shortly the following issues are discussed in the paper: - identification of critical components; - application of a multilevel risk analysis (...from 'screening' to 'detailed analysis'); - determination of PoF (Probability of Failure); - determination of CoF (Consequence of Failure); - optimation of inspection and maintenance plan. From our experience with the application of the RIMAP methodology the following conclusions can be drawn: The use of risk-based methods in inspection and maintenance of piping systems in power plants gives transparency to the decision making process and gives an optimized maintenance policy based on current state of the components. The results of the work clearly show the power of the proposed method for concentration on critical items: out of 64 monitored components 5 were selected for intermediate analysis and only 1 for the detailed analysis (probabilistic high temperature fracture mechanics)

  1. The effects of cognitive reappraisal following retrieval-procedures designed to destabilize alcohol memories in high-risk drinkers.

    Science.gov (United States)

    Hon, Tiffany; Das, Ravi K; Kamboj, Sunjeev K

    2016-03-01

    Addiction is a disorder of motivational learning and memory. Maladaptive motivational memories linking drug-associated stimuli to drug seeking are formed over hundreds of reinforcement trials and accompanied by aberrant neuroadaptation in the mesocorticolimbic reward system. Such memories are resistant to extinction. However, the discovery of retrieval-dependent memory plasticity has opened up the possibility of permanent modification of established (long-term) memories during 'reconsolidation'. Here, we investigate whether reappraisal of maladaptive alcohol cognitions performed after procedures designed to destabilize alcohol memory networks affected subsequent alcohol memory, craving, drinking and attentional bias. Forty-seven at-risk drinkers attended two sessions. On the first lab session, participants underwent one of two prediction error-generating procedures in which outcome expectancies were violated while retrieving alcohol memories (omission and value prediction error groups). Participants in a control group retrieved non-alcohol memories. Participants then reappraised personally relevant maladaptive alcohol memories and completed measures of reappraisal recall, alcohol verbal fluency and craving. Seven days later, they repeated these measures along with attentional bias assessment. Omission prediction error (being unexpectedly prevented from drinking beer), but not a value prediction error (drinking unexpectedly bitter-tasting beer) or control procedure (drinking unexpectedly bitter orange juice), was associated with significant reductions in verbal fluency for positive alcohol-related words. No other statistically robust outcomes were detected. This study provides partial preliminary support for the idea that a common psychotherapeutic strategy used in the context of putative memory retrieval-destabilization can alter accessibility of alcohol semantic networks. Further research delineating the necessary and sufficient requirements for producing

  2. Static and dynamic buckling of large thin shells. (Design procedure, computation tools. Physical understanding of the mechanisms)

    International Nuclear Information System (INIS)

    Combescure, A.

    1986-04-01

    During the last ten years, the French Research Institute for Nuclear Energy (Commissariat a l'Energie Atomique) achieved many theoretical as well as experimental studies for designing the first large size pool type fast breeder reactor. Many of the sensitive parts of this reactor are thin shells subjected to high temperatures and loads. Special care has been given to buckling, because it often governs design. Most of the thin shells structures of the french breeder reactor are axisymmetric. However, imperfections have to be accounted for. In order to keep the advantage of an axisymmetric analysis (low computational costs), a special element has been implemented and used with considerable success in the recent years. This element (COMU) is described in the first chapter, its main features are: either non axisymmetric imperfection or non axisymmetric load, large displacement, non linear material behaviour, computational costs about ten times cheaper than the equivalent three dimensional analysis. This paper based on a careful comparison between experimental and computational results, obtained with the COMU, will analyse three problems: First: design procedure against buckling of thin shells structures subjected to primary loads; Second: static post buckling; Third: buckling under seismic loads [fr

  3. 12 CFR 652.70 - Risk-based capital level.

    Science.gov (United States)

    2010-01-01

    ... risk-based capital level is the sum of the following amounts: (a) Credit and interest rate risk. The... 12 Banks and Banking 6 2010-01-01 2010-01-01 false Risk-based capital level. 652.70 Section 652.70 Banks and Banking FARM CREDIT ADMINISTRATION FARM CREDIT SYSTEM FEDERAL AGRICULTURAL MORTGAGE...

  4. Designing experimental setup and procedures for studying alpha-particle-induced adaptive response in zebrafish embryos in vivo

    Energy Technology Data Exchange (ETDEWEB)

    Choi, V.W.Y.; Lam, R.K.K.; Chong, E.Y.W. [Department of Physics and Materials Science, City University of Hong Kong, Tat Chee Avenue, Kowloon Tong (Hong Kong); Cheng, S.H. [Department of Biology and Chemistry, City University of Hong Kong, Tat Chee Avenue, Kowloon Tong (Hong Kong); Yu, K.N., E-mail: peter.yu@cityu.edu.h [Department of Physics and Materials Science, City University of Hong Kong, Tat Chee Avenue, Kowloon Tong (Hong Kong)

    2010-03-15

    The present work was devoted to designing the experimental setup and the associated procedures for alpha-particle-induced adaptive response in zebrafish embryos in vivo. Thin PADC films with a thickness of 16 mum were fabricated and employed as support substrates for holding dechorionated zebrafish embryos for alpha-particle irradiation from the bottom through the films. Embryos were collected within 15 min when the light photoperiod began, which were then incubated and dechorionated at 4 h post fertilization (hpf). They were then irradiated at 5 hpf by alpha particles using a planar {sup 241}Am source with an activity of 0.1151 muCi for 24 s (priming dose), and subsequently at 10 hpf using the same source for 240 s (challenging dose). The levels of apoptosis in irradiated zebrafish embryos at 24 hpf were quantified through staining with the vital dye acridine orange, followed by counting the stained cells under a florescent microscope. The results revealed the presence of the adaptive response in zebrafish embryos in vivo, and demonstrated the feasibility of the adopted experimental setup and procedures.

  5. Proposed Design Procedure of a Helical Coil Heat Exchanger for an Orc Energy Recovery System for Vehicular Application

    Directory of Open Access Journals (Sweden)

    Giacomo Bonafoni

    2015-05-01

    Full Text Available There are several systems that produce energy from low grade heat sources such as Stirling engines, thermoelectric generators, and ORC (Organic Rankine Cycle systems. This paper shows the heat recovery from exhaust gases of a 1400 cc Diesel engine, to vaporize the working fluid of a small (<10 kW ORC system. The main objective is to have a system as compact as possible, to make it suitable for transport applications such as cars, ships, trains, etc. Three fluids were studied for this application: water and two refrigerant fluids: R134a and R245fa, which were found to be more appropriate than water at certain pressure and temperature values. Afterwards, a design procedure was proposed, then the heat exchanger was modeled and finally a steady-state thermal and structural analysis were carried out using a commercial software to find the temperature and the effects of the thermal stress on the material of the helical coiled tube.

  6. Design of standard operating procedure production proceses (case study on the home industry Bedugul Baturiti Tabanan Bali)

    Science.gov (United States)

    Kasiani; Suhantono, Djoko; Mirah Kencanawati, AAA

    2018-01-01

    Candikuning is part of the district of Baturiti, tourism village, better known by the name of Bedugul. No less interesting is the variety of chips produced by two partner groups as a souvenir after the tour, such as Chips: Spinach; beans; Tempeh. The purpose of this research were to design a Standard Operating Procedure (SOP): Production Processes on the Home Industry Bedugul Baturiti Tabanan Bali. The data technic collected use: observation; Documentation; and then interview to collect information. The data analysis technic done by using the Miles & Huberman. Result this research that the draft SOP: Production Processes Chips (Menu). The conclusion in this research SOP Production Processes use with flowchart and description on the Home Industry Bedugul Baturiti Tabanan Bali.

  7. Risk-based emergency decision support

    International Nuclear Information System (INIS)

    Koerte, Jens

    2003-01-01

    In the present paper we discuss how to assist critical decisions taken under complex, contingent circumstances, with a high degree of uncertainty and short time frames. In such sharp-end decision regimes, standard rule-based decision support systems do not capture the complexity of the situation. At the same time, traditional risk analysis is of little use due to variability in the specific circumstances. How then, can an organisation provide assistance to, e.g. pilots in dealing with such emergencies? A method called 'contingent risk and decision analysis' is presented, to provide decision support for decisions under variable circumstances and short available time scales. The method consists of nine steps of definition, modelling, analysis and criteria definition to be performed 'off-line' by analysts, and procedure generation to transform the analysis result into an operational decision aid. Examples of pilots' decisions in response to sudden vibration in offshore helicopter transport method are used to illustrate the approach

  8. Application of REVEAL-W to risk-based configuration control

    International Nuclear Information System (INIS)

    Dezfuli, H.; Meyer, J.; Modarres, M.

    1994-01-01

    Over the past two years, the concept of risk-based configuration control has been introduced to the US Nuclear Regulatory Commission and the nuclear industry. Converting much of the current, deterministically based regulation of nuclear power plants to risk-based regulation can result in lower levels of risk while relieving unnecessary burdens on power plant operators and regulatory staff. To achieve the potential benefits of risk-based configuration control, the risk models developed for nuclear power plants should be (1) flexible enough to effectively support necessary risk calculations, and (2) transparent enough to encourage their use by all parties. To address these needs, SCIENTECH, Inc., has developed the PC-based REVEAL W (formerly known as SMART). This graphic-oriented and user-friendly application software allows the user to develop transparent complex logic models based on the concept of the master plant logic diagram. The logic model is success-oriented and compact. The analytical capability built into REVEAL W is generic, so the software can support different types of risk-based evaluations, such as probabilistic safety assessment, accident sequence precursor analysis, design evaluation and configuration management. In this paper, we focus on the application of REVEAL W to support risk-based configuration control of nuclear power plants. (author)

  9. The risk-based approach to anti-money laundering: problems and solutions

    DEFF Research Database (Denmark)

    Simonova, Anna

    2011-01-01

    Purpose – The purpose of this paper, which is a part of a PhD thesis, is to detect problems associated with the risk-based approach to anti-money laundering (AML), as well as present ways to improve the risk-based approach. Design/methodology/approach – The method is law and economics. The Ph......D thesis itself is also based on a comparative analysis of the Danish and British AML regimes. Findings – The main findings are: failure to develop adequate risk-based AML systems, taking into account varying levels of money laundering risk, is not only to be considered in the context of legal risk...... but also and more importantly in the context of integrity risk; anti-money laundering (AML) has to be made part of financial and non-financial institutions' corporate social responsibility policies; the Risk Analysis Manual provided by the Central Bank of The Netherlands lists very specific...

  10. Risk based decision aid for damage control

    NARCIS (Netherlands)

    Meesters, J.L.; Keijer, W.; Gillis, M.P.W.

    2003-01-01

    The current trend in ship design is to reduce the crew. Special attention should be paid to damage control, which is a labour intensive task. Having less crew members implies that more tasks have to be automated. It also means a reduction of the available 'human sensors’, which leads to difficulties

  11. An Integrated Procedure for the Structural Design of a Composite Rotor-Hydrofoil of a Water Current Turbine (WCT)

    Science.gov (United States)

    Oller Aramayo, S. A.; Nallim, L. G.; Oller, S.

    2013-12-01

    This paper shows an integrated structural design optimization of a composite rotor-hydrofoil of a water current turbine by means the finite elements method (FEM), using a Serial/Parallel mixing theory (Rastellini et al. Comput. Struct. 86:879-896, 2008, Martinez et al., 2007, Martinez and Oller Arch. Comput. Methods. 16(4):357-397, 2009, Martinez et al. Compos. Part B Eng. 42(2011):134-144, 2010) coupled with a fluid-dynamic formulation and multi-objective optimization algorithm (Gen and Cheng 1997, Lee et al. Compos. Struct. 99:181-192, 2013, Lee et al. Compos. Struct. 94(3):1087-1096, 2012). The composite hydrofoil of the turbine rotor has been design using a reinforced laminate composites, taking into account the optimization of the carbon fiber orientation to obtain the maximum strength and lower rotational-inertia. Also, these results have been compared with a steel hydrofoil remarking the different performance on both structures. The mechanical and geometrical parameters involved in the design of this fiber-reinforced composite material are the fiber orientation, number of layers, stacking sequence and laminate thickness. Water pressure in the rotor of the turbine is obtained from a coupled fluid-dynamic simulation (CFD), whose detail can be found in the reference Oller et al. (2012). The main purpose of this paper is to achieve a very low inertia rotor minimizing the start-stop effect, because it is applied in axial water flow turbine currently in design by the authors, in which is important to take the maximum advantage of the kinetic energy. The FEM simulation codes are engineered by CIMNE (International Center for Numerical Method in Engineering, Barcelona, Spain), COMPack for the solids problem application, KRATOS for fluid dynamic application and RMOP for the structural optimization. To validate the procedure here presented, many turbine rotors made of composite materials are analyzed and three of them are compared with the steel one.

  12. Multiseam design procedures.

    CSIR Research Space (South Africa)

    Hill, RW

    1994-02-01

    Full Text Available affecting the success of failure of multiseam mining. Numerical modelling and field studies have been used to identify trends and problems areas, but critical factors may be omitted. Statistical analysis has been used to overcome some of the disadvantage...

  13. An optimal range of information quantity on computer-based procedure interface design in the advanced main control room

    International Nuclear Information System (INIS)

    Hsieh Minchih; Chiu Mingchuan; Hwang Sheueling

    2015-01-01

    The quantification of information in the interface design is a critical issue. Too much information on an interface can confuse a user while executing a task, and too little information may result in poor user performance. This study focused on the quantification of visible information on computer-based procedures (CBPs). Levels of information quantity and task complexity were considered in this experiment. Simulated CBPs were developed to consist of three levels: high (at least 10 events, i.e. 3.32 bits), medium (4–8 events, i.e. 2–3 bits), and low information quantity (1 or 2 events, i.e. 0 or 1 bits). Task complexity comprised two levels: complex tasks and simple tasks. The dependent variables include operation time, secondary task performance, and mental workload. Results suggested that medium information quantity of five to eight events has a remarkable advantage in supporting operator performance under both simple and complex tasks. This research not only suggested the appropriate range of information quantity on the CBP interface, but also complemented certain deficient results of previous CBP interface design studies. Additionally, based on results obtained by this study, the quantification of information on the CBP interface should be considered to ensure safe operation of nuclear power plants. (author)

  14. Design of Training Systems, Phase II Report, Volume III; Model Program Descriptions and Operating Procedures. TAEG Report No. 12-2.

    Science.gov (United States)

    Naval Training Equipment Center, Orlando, FL. Training Analysis and Evaluation Group.

    The Design of Training Systems (DOTS) project was initiated by the Department of Defense (DOD) to develop tools for the effective management of military training organizations. Volume 3 contains the model and data base program descriptions and operating procedures designed for phase 2 of the project. Flow charts and program listings for the…

  15. Advanced human-system interface design review guideline. Evaluation procedures and guidelines for human factors engineering reviews

    International Nuclear Information System (INIS)

    O'Hara, J.M.; Brown, W.S.; Baker, C.C.; Welch, D.L.; Granda, T.M.; Vingelis, P.J.

    1994-07-01

    Advanced control rooms will use advanced human-system interface (HSI) technologies that may have significant implications for plant safety in that they will affect the operator's overall role in the system, the method of information presentation, and the ways in which operators interact with the system. The U.S. Nuclear Regulatory Commission (NRC) reviews the HSI aspects of control rooms to ensure that they are designed to good human factors engineering principles and that operator performance and reliability are appropriately supported to protect public health and safety. The principal guidance available to the NRC, however, was developed more than ten years ago, well before these technological changes. Accordingly, the human factors guidance needs to be updated to serve as the basis for NRC review of these advanced designs. The purpose of this project was to develop a general approach to advanced HSI review and the human factors guidelines to support. NRC safety reviews of advanced systems. This two-volume report provides the results of the project. Volume I describes the development of the Advanced HSI Design Review Guideline (DRG) including (1) its theoretical and technical foundation, (2) a general model for the review of advanced HSIs, (3) guideline development in both hard-copy and computer-based versions, and (4) the tests and evaluations performed to develop and validate the DRG. Volume I also includes a discussion of the gaps in available guidance and a methodology for addressing them. Volume 2 provides the guidelines to be used for advanced HSI review and the procedures for their use

  16. Advanced human-system interface design review guideline. Evaluation procedures and guidelines for human factors engineering reviews

    Energy Technology Data Exchange (ETDEWEB)

    O`Hara, J.M.; Brown, W.S. [Brookhaven National Lab., Upton, NY (United States); Baker, C.C.; Welch, D.L.; Granda, T.M.; Vingelis, P.J. [Carlow International Inc., Falls Church, VA (United States)

    1994-07-01

    Advanced control rooms will use advanced human-system interface (HSI) technologies that may have significant implications for plant safety in that they will affect the operator`s overall role in the system, the method of information presentation, and the ways in which operators interact with the system. The U.S. Nuclear Regulatory Commission (NRC) reviews the HSI aspects of control rooms to ensure that they are designed to good human factors engineering principles and that operator performance and reliability are appropriately supported to protect public health and safety. The principal guidance available to the NRC, however, was developed more than ten years ago, well before these technological changes. Accordingly, the human factors guidance needs to be updated to serve as the basis for NRC review of these advanced designs. The purpose of this project was to develop a general approach to advanced HSI review and the human factors guidelines to support. NRC safety reviews of advanced systems. This two-volume report provides the results of the project. Volume I describes the development of the Advanced HSI Design Review Guideline (DRG) including (1) its theoretical and technical foundation, (2) a general model for the review of advanced HSIs, (3) guideline development in both hard-copy and computer-based versions, and (4) the tests and evaluations performed to develop and validate the DRG. Volume I also includes a discussion of the gaps in available guidance and a methodology for addressing them. Volume 2 provides the guidelines to be used for advanced HSI review and the procedures for their use.

  17. PENGARUH PELAKSANAAN RISK BASED INTERNAL AUDITING TERHADAP PENCEGAHAN FRAUD

    Directory of Open Access Journals (Sweden)

    Rozmita Dewi Yuniarti Rozali

    2015-12-01

    Full Text Available This study aims to determine the effect of implementation of risk based internal auditing on fraud prevention on internal audit Inspection Office Bank BRI Bandung Region. The sample used by 18 internal auditors in Inspection Office of Bank BRI Bandung Region saturated sampling method. Based on calculation of simple regression analysis obtained result that every increase of implementation of risk based internal auditing (X will lead to increase fraud prevention (Y. It shows that there is a positive influence between the implementation of risk based internal auditing on fraud prevention on the internal audit of Inspection Office of Bank BRI Bandung Region.

  18. Risk Based Corrosion Studies at SRS

    International Nuclear Information System (INIS)

    Hoffman, E.

    2010-01-01

    TYPE I and II (ASTM 285-B) - Experienced stress corrosion cracking (SCC), 2 have been closed; 22 scheduled for closure by 2017, and No active leak sites today. TYPE III (ASTM A516-70 and A537 Class I) - Post-fabrication relief of weld residual stresses, Improved resistance to SCC and brittle fracture, No leakage history, and Receives new waste. The objectives are to utilize statistical methods to reduce conservatism in current chemistry control program; and express nitrite inhibitor limits in terms of pitting risk on waste tank steel. Conclusions are: (1) A statistically designed experimental study has been undertaken to improve the effectiveness of the minimum nitrite concentrations to inhibit pitting corrosion; (2) Mixture/amount model supports that pitting depends on the ratio of aggressive to inhibitive anions, as well as the concentration of each species; (3) Secondary aggressive species, Cl - and SO 4 2- , significantly effect the corrosion response; and (4) Results support the reduction of the chemistry control nitrite inhibitor concentrations in the regime of 0.8-1.0 M nitrate.

  19. Bayesian risk-based acceptance criteria

    International Nuclear Information System (INIS)

    Martz, H.F.; Abramson, L.R.; Johnson, J.W.

    1996-04-01

    Mechanistic (or deterministic) analysis is traditionally performed in the process of designing a new nuclear reactor or reactor core and also as part of the safety analysis of existing reactors or reload cores. Mechanistic accident analysis is characterized by the specification of an initial operating condition, an initiating event, and subsequent system faults. These subsequent faults are often chosen, through such mechanisms as the worst single failure criterion, so as to maximize the consequences of the accident. Thus, the behavior of all reactor system hardware is prescribed before this analysis begins. Mechanistic analysis then attempts to predict the dynamic response of the system and usually involves detailed reactor physics and thermal-hydraulic predictions of the system behavior, including such parameters as power distributions in the reactor core, coolant temperatures and flow rates, and fuel clad temperature distributions. The objective of this analysis has typically been to establish and verify reactor operating limits and technical specifications, so that severe core damage (SCD) is prevented for a wide variety of reactor accidents

  20. Advantages and disadvantages of a risk - based regulatory requirement (the experience in Argentina)

    International Nuclear Information System (INIS)

    Baron, Jorge

    2006-01-01

    Argentina has its own nuclear regulations, which include a risk-based criterion curve for the licensing of nuclear installations. This requirement, established in the early '70s, must be fulfilled with a PSA study. It has been applied to several installations, and the advantages and disadvantages of this approach are discussed in the paper through several examples. The main disadvantage is a somehow large amount of PSA work that needs to be performed for the licensing of a nuclear installation. The main advantage is the effective risk reduction that can be achieved by retrofitting the risk-based lessons learned into the design teams (not only for design of systems and components, but also for design of operation, testing and maintenance schemes). (author)

  1. Interdisciplinary Development of an Improved Emergency Department Procedural Work Surface Through Iterative Design and Use Testing in Simulated and Clinical Environments.

    Science.gov (United States)

    Zhang, Xiao C; Bermudez, Ana M; Reddy, Pranav M; Sarpatwari, Ravi R; Chheng, Darin B; Mezoian, Taylor J; Schwartz, Victoria R; Simmons, Quinneil J; Jay, Gregory D; Kobayashi, Leo

    2017-03-01

    A stable and readily accessible work surface for bedside medical procedures represents a valuable tool for acute care providers. In emergency department (ED) settings, the design and implementation of traditional Mayo stands and related surface devices often limit their availability, portability, and usability, which can lead to suboptimal clinical practice conditions that may affect the safe and effective performance of medical procedures and delivery of patient care. We designed and built a novel, open-source, portable, bedside procedural surface through an iterative development process with use testing in simulated and live clinical environments. The procedural surface development project was conducted between October 2014 and June 2016 at an academic referral hospital and its affiliated simulation facility. An interdisciplinary team of emergency physicians, mechanical engineers, medical students, and design students sought to construct a prototype bedside procedural surface out of off-the-shelf hardware during a collaborative university course on health care design. After determination of end-user needs and core design requirements, multiple prototypes were fabricated and iteratively modified, with early variants featuring undermattress stabilizing supports or ratcheting clamp mechanisms. Versions 1 through 4 underwent 2 hands-on usability-testing simulation sessions; version 5 was presented at a design critique held jointly by a panel of clinical and industrial design faculty for expert feedback. Responding to select feedback elements over several surface versions, investigators arrived at a near-final prototype design for fabrication and use testing in a live clinical setting. This experimental procedural surface (version 8) was constructed and then deployed for controlled usability testing against the standard Mayo stands in use at the study site ED. Clinical providers working in the ED who opted to participate in the study were provided with the prototype

  2. Risk Based Milk Pricing Model at Dairy Farmers Level

    Directory of Open Access Journals (Sweden)

    W. Septiani

    2017-12-01

    Full Text Available The milk price from a cooperative institution to farmer does not fully cover the production cost. Though, dairy farmers encounter various risks and uncertainties in conducting their business. The highest risk in milk supply lies in the activities at the farm. This study was designed to formulate a model for calculating milk price at farmer’s level based on risk. Risks that occur on farms include the risk of cow breeding, sanitation, health care, cattle feed management, milking and milk sales. This research used the location of the farm in West Java region. There were five main stages in the preparation of this model, (1 identification and analysis of influential factors, (2 development of a conceptual model, (3 structural analysis and the amount of production costs, (4 model calculation of production cost with risk factors, and (5 risk based milk pricing model. This research built a relationship between risks on smallholder dairy farms with the production costs to be incurred by the farmers. It was also obtained the formulation of risk adjustment factor calculation for the variable costs of production in dairy cattle farm. The difference in production costs with risk and the total production cost without risk was about 8% to 10%. It could be concluded that the basic price of milk proposed based on the research was around IDR 4,250-IDR 4,350/L for 3 to 4 cows ownership. Increasing farmer income was expected to be obtained by entering the value of this risk in the calculation of production costs. 

  3. Risk-based technical specifications program: Site interview results

    International Nuclear Information System (INIS)

    Andre, G.R.; Baker, A.J.; Johnson, R.L.

    1991-08-01

    The Electric Power Research Institute and Pacific Gas and Electric Company are sponsoring a program directed at improving Technical Specifications using risk-based methods. The major objectives of the program are to develop risk-based approaches to improve Technical Specifications and to develop an Interactive Risk Advisor (IRA) prototype. The IRA is envisioned as an interactive system that is available to plant personnel to assist in controlling plant operation. Use of an IRA is viewed as a method to improve plant availability while maintaining or improving plant safety. In support of the program, interviews were conducted at several PWR and BWR plant sites, to elicit opinions and information concerning risk-based approaches to Technical Specifications and IRA requirements. This report presents the results of these interviews, including the functional requirements of an IRA. 2 refs., 6 figs., 2 tabs

  4. Risk-Based Operation and Maintenance of Offshore Wind Turbines

    DEFF Research Database (Denmark)

    Nielsen, Jannie Sønderkær

    to oil and gas structures. In addition, condition monitoring systems are often available, and the information should be taken into account when making decisions. In this thesis, methods for risk-based maintenance planning using Bayesian methods are investigated, with the aim of making optimal decisions......, but presently maintenance is not planned using advanced methods taking all available information into account in a consistent manner. Maintenance decisions can be made based on risk-based methods, where the total expected life cycle costs are minimized. Methods have been developed for assessing the corrective...... considering all available information. First, a theoretical damage model is formulated, the model is then updated using condition monitoring data, and the updated model is used as basis for risk-based decision making. Several approaches for solving the decision problems have been considered: various types...

  5. Correction: General optimization procedure towards the design of a new family of minimal parameter spin-component-scaled double-hybrid density functional theory.

    Science.gov (United States)

    Roch, Loïc M; Baldridge, Kim K

    2018-02-07

    Correction for 'General optimization procedure towards the design of a new family of minimal parameter spin-component-scaled double-hybrid density functional theory' by Loïc M. Roch and Kim K. Baldridge, Phys. Chem. Chem. Phys., 2017, 19, 26191-26200.

  6. Generating evidence on a risk-based monitoring approach in the academic setting – lessons learned

    Directory of Open Access Journals (Sweden)

    Belinda von Niederhäusern

    2017-02-01

    Full Text Available Abstract Background In spite of efforts to employ risk-based strategies to increase monitoring efficiency in the academic setting, empirical evidence on their effectiveness remains sparse. This mixed-methods study aimed to evaluate the risk-based on-site monitoring approach currently followed at our academic institution. Methods We selected all studies monitored by the Clinical Trial Unit (CTU according to Risk ADApted MONitoring (ADAMON at the University Hospital Basel, Switzerland, between 01.01.2012 and 31.12.2014. We extracted study characteristics and monitoring information from the CTU Enterprise Resource Management system and from monitoring reports of all selected studies. We summarized the data descriptively. Additionally, we conducted semi-structured interviews with the three current CTU monitors. Results During the observation period, a total of 214 monitoring visits were conducted in 43 studies resulting in 2961 documented monitoring findings. Our risk-based approach predominantly identified administrative (46.2% and patient right findings (49.1%. We identified observational study design, high ADAMON risk category, industry sponsorship, the presence of an electronic database, experienced site staff, and inclusion of vulnerable study population to be factors associated with lower numbers of findings. The monitors understand the positive aspects of a risk-based approach but fear missing systematic errors due to the low frequency of visits. Conclusions We show that the factors mostly increasing the risk for on-site monitoring findings are underrepresented in the current risk analysis scheme. Our risk-based on-site approach should further be complemented by centralized data checks, allowing monitors to transform their role towards partners for overall trial quality, and success.

  7. Emergency procedures

    International Nuclear Information System (INIS)

    Abd Nasir Ibrahim; Azali Muhammad; Ab Razak Hamzah; Abd Aziz Mohamed; Mohammad Pauzi Ismail

    2004-01-01

    The following subjects are discussed - Emergency Procedures: emergency equipment, emergency procedures; emergency procedure involving X-Ray equipment; emergency procedure involving radioactive sources

  8. Status of existing federal environmental risk-based standards applicable to Department of Energy operations

    International Nuclear Information System (INIS)

    Bilyard, G.R.

    1991-09-01

    When conducting its environmental restoration, waste management, and decontamination and decommissioning activities, the US Department of Energy (DOE) must comply with a myriad of regulatory procedures and environmental standards. This paper assesses the status of existing federal risk-based standards that may be applied to chemical and radioactive substances on DOE sites. Gaps and inconsistencies among the existing standards and the technical issues associated with the application of those standards are identified. Finally, the implications of the gaps, inconsistencies, and technical issues on DOE operations are discussed, and approaches to resolving the gaps, inconsistencies, and technical issues are identified. 6 refs

  9. The challenge of setting risk-based microbiological criteria for Listeria monocytogenes

    DEFF Research Database (Denmark)

    Andersen, Jens Kirk; Nørrung, Birgit

    2011-01-01

    After more than 20 years of work with discussing the setting of microbiological criteria for Listeria monocytogenes in foods, Codex Alimentarius on Food Hygiene has finalised a proposal that was recently adopted by the Codex Alimentarius Commission. The effort of developing procedures for making...... the microbiological criteria risk-based to the greatest extent possible has challenged scientists and managers during this long time period. Yet, the establishment of microbiological criteria for L. monocytogenes is still being discussed and several approaches are possible. Setting of microbiological criteria...

  10. Risk-based rules for crane safety systems

    Energy Technology Data Exchange (ETDEWEB)

    Ruud, Stian [Section for Control Systems, DNV Maritime, 1322 Hovik (Norway)], E-mail: Stian.Ruud@dnv.com; Mikkelsen, Age [Section for Lifting Appliances, DNV Maritime, 1322 Hovik (Norway)], E-mail: Age.Mikkelsen@dnv.com

    2008-09-15

    The International Maritime Organisation (IMO) has recommended a method called formal safety assessment (FSA) for future development of rules and regulations. The FSA method has been applied in a pilot research project for development of risk-based rules and functional requirements for systems and components for offshore crane systems. This paper reports some developments in the project. A method for estimating target reliability for the risk-control options (safety functions) by means of the cost/benefit decision criterion has been developed in the project and is presented in this paper. Finally, a structure for risk-based rules is proposed and presented.

  11. Risk-based rules for crane safety systems

    International Nuclear Information System (INIS)

    Ruud, Stian; Mikkelsen, Age

    2008-01-01

    The International Maritime Organisation (IMO) has recommended a method called formal safety assessment (FSA) for future development of rules and regulations. The FSA method has been applied in a pilot research project for development of risk-based rules and functional requirements for systems and components for offshore crane systems. This paper reports some developments in the project. A method for estimating target reliability for the risk-control options (safety functions) by means of the cost/benefit decision criterion has been developed in the project and is presented in this paper. Finally, a structure for risk-based rules is proposed and presented

  12. Practical risk-based decision making: Good decisions made efficiently

    International Nuclear Information System (INIS)

    Haire, M.J.; Guthrie, V.; Walker, D.; Singer, R.

    1995-01-01

    The Robotics and Process Systems Division of the Oak Ridge National Laboratory and the Westinghouse Savannah River Company have teamed with JBF Associates, Inc. to address risk-based robotic planning. The objective of the project is to provide systematic, risk-based relative comparisons of competing alternatives for solving clean-up problems at DOE facilities. This paper presents the methodology developed, describes the software developed to efficiently apply the methodology, and discusses the results of initial applications for DOE. The paper also addresses current work in applying the approach to problems in other industries (including an example from the hydrocarbon processing industry)

  13. Promotion of technical harmonisation on risk-based decision making

    International Nuclear Information System (INIS)

    Kirchsteiger, Christian; Cojazzi, Giacomo

    2000-01-01

    The EC-JRC International Workshop on Promotion of Technical Harmonisation on Risk-Based Decision Making, held at Stresa and Ispra, Italy, 22-25 May 2000, was an experts meeting to discuss the possible need of developing an internationally accepted generic 'standard' for risk-based decision making.This paper briefly describes the workshop background, its organisation and summarises its main results and conclusions; it reflects the personal opinions of the authors and in no way commits the European Commission. (author)

  14. Risk-based management of invading plant disease.

    Science.gov (United States)

    Hyatt-Twynam, Samuel R; Parnell, Stephen; Stutt, Richard O J H; Gottwald, Tim R; Gilligan, Christopher A; Cunniffe, Nik J

    2017-05-01

    Effective control of plant disease remains a key challenge. Eradication attempts often involve removal of host plants within a certain radius of detection, targeting asymptomatic infection. Here we develop and test potentially more effective, epidemiologically motivated, control strategies, using a mathematical model previously fitted to the spread of citrus canker in Florida. We test risk-based control, which preferentially removes hosts expected to cause a high number of infections in the remaining host population. Removals then depend on past patterns of pathogen spread and host removal, which might be nontransparent to affected stakeholders. This motivates a variable radius strategy, which approximates risk-based control via removal radii that vary by location, but which are fixed in advance of any epidemic. Risk-based control outperforms variable radius control, which in turn outperforms constant radius removal. This result is robust to changes in disease spread parameters and initial patterns of susceptible host plants. However, efficiency degrades if epidemiological parameters are incorrectly characterised. Risk-based control including additional epidemiology can be used to improve disease management, but it requires good prior knowledge for optimal performance. This focuses attention on gaining maximal information from past epidemics, on understanding model transferability between locations and on adaptive management strategies that change over time. © 2017 The Authors. New Phytologist © 2017 New Phytologist Trust.

  15. Risk-Based Decision Making for Deterioration Processes Using POMDP

    DEFF Research Database (Denmark)

    Nielsen, Jannie Sønderkær; Sørensen, John Dalsgaard

    2015-01-01

    This paper proposes a method for risk-based decision making for maintenance of deteriorating components, based on the partially observable Markov decision process (POMDP). Unlike most methods, the decision polices do not need to be stationary and can vary according to seasons and near the end...

  16. 6 CFR 27.230 - Risk-based performance standards.

    Science.gov (United States)

    2010-01-01

    ... 6 Domestic Security 1 2010-01-01 2010-01-01 false Risk-based performance standards. 27.230 Section 27.230 Domestic Security DEPARTMENT OF HOMELAND SECURITY, OFFICE OF THE SECRETARY CHEMICAL FACILITY... the facility and that discourages abuse through established disciplinary measures; (4) Deter, Detect...

  17. Risk-based audit selection of dairy farms

    NARCIS (Netherlands)

    Asseldonk, van M.A.P.M.; Velthuis, A.G.J.

    2014-01-01

    Dairy farms are audited in the Netherlands on numerous process standards. Each farm is audited once every 2 years. Increasing demands for cost-effectiveness in farm audits can be met by introducing risk-based principles. This implies targeting subpopulations with a higher risk of poor process

  18. Develop risk-based procurement management tools for SMEs

    NARCIS (Netherlands)

    Staal, Anne; Hagelaar, Geoffrey; Walhof, Gert; Holman, Richard

    2016-01-01

    This paper provides guidance for developing risk-based management tools to improve the procurement (purchasing) performance of SMEs. Extant academic literature only offers little support on developing such tools and does not consider the wide variety of SMEs. The paper defines a procurement tool for

  19. 12 CFR 932.3 - Risk-based capital requirement.

    Science.gov (United States)

    2010-01-01

    ... credit risk capital requirement, its market risk capital requirement, and its operations risk capital... 12 Banks and Banking 7 2010-01-01 2010-01-01 false Risk-based capital requirement. 932.3 Section 932.3 Banks and Banking FEDERAL HOUSING FINANCE BOARD FEDERAL HOME LOAN BANK RISK MANAGEMENT AND...

  20. 76 FR 1889 - Risk-Based Capital Guidelines: Market Risk

    Science.gov (United States)

    2011-01-11

    ... ``three-pillar'' framework that includes (i) risk-based capital requirements for credit risk, market risk... incremental risk capital requirement to capture default and credit quality migration risk for non... (advanced approaches rules) (collectively, the credit risk capital rules) \\8\\ by requiring any bank subject...

  1. 77 FR 53059 - Risk-Based Capital Guidelines: Market Risk

    Science.gov (United States)

    2012-08-30

    ...'' framework that includes (1) Risk-based capital requirements for credit risk, market risk, and operational... default and credit quality migration risk for non-securitization credit products. With respect to... securitization positions, the revisions assign a specific risk- weighting factor based on the credit rating of a...

  2. Risk-Based Operation and Maintenance Using Bayesian Networks

    DEFF Research Database (Denmark)

    Nielsen, Jannie Jessen; Sørensen, John Dalsgaard

    2011-01-01

    This paper describes how risk-based decision making can be used for maintenance planning of components exposed to degradation such as fatigue in offshore wind turbines. In fatigue models, large epistemic uncertainties are usually present. These can be reduced if monitoring results are used to upd...

  3. Benefits of Risk Based Inspection Planning for Offshore Structures

    DEFF Research Database (Denmark)

    Straub, D.M.; Goyet, J.; Sørensen, John Dalsgaard

    2006-01-01

    The economical benefits of applying risk-based inspection planning (RBI) for offshore structures subject to fatigue are evaluated based on experiences from past industrial projects. To this end, the factors influencing the cost of inspection, repair and failure of structures are discussed......, the financial benefit of RBI is assessed....

  4. Risk-Based Educational Accountability in Dutch Primary Education

    Science.gov (United States)

    Timmermans, A. C.; de Wolf, I. F.; Bosker, R. J.; Doolaard, S.

    2015-01-01

    A recent development in educational accountability is a risk-based approach, in which intensity and frequency of school inspections vary across schools to make educational accountability more efficient and effective by enabling inspectorates to focus on organizations at risk. Characteristics relevant in predicting which schools are "at risk…

  5. Risk-Based Operation and Maintenance of Offshore Wind Turbines

    DEFF Research Database (Denmark)

    Nielsen, Jannie Jessen; Sørensen, John Dalsgaard

    2009-01-01

    For offshore wind turbines costs to operation and maintenance are substantial. This paper describes a risk-based lifecycle approach for optimal planning of operation and maintenance. The approach is based on pre-posterior Bayesian decision theory. Deterioration mechanisms such as fatigue, corrosion...

  6. Development of a risk-based in-service inspection program for an LMR

    International Nuclear Information System (INIS)

    King, R.W.; Buschman, H.W.

    1996-01-01

    The emerging application of risk-based assessment technology to the operation and maintenance of nuclear power plants holds considerable promise for improving efficiency and reducing operating costs. Experimental Breeder Reactor II (EBR-II) is a liquid-metal-cooled fast reactor (LMR) that operated for 30 yr before shutting down in September 1994 due to program termination. Prior to the shutdown of EBR-II, an in-service inspection (ISI) program was developed that exploited certain advantages of the LMR design. For example, it demonstrated passive response to plant upset events, low-pressure primary coolant, and compatibility of the coolant and reactor materials. This ISI program was based on work currently being done by an American Society of Mechanical Engineers (ASME) Research Task Force on Risk-Based Inspection

  7. The Two C”s of the Risk-Based Approach to Goal based Standards: Challenges and Caveats

    DEFF Research Database (Denmark)

    Kontovas, Christos A.; Psaraftis, Harilaos N.; Zachariadis, Panos

    2007-01-01

    industry has begun to move from a reactive to a proactive approach to safety through “Formal Safety Assessment” (FSA) and “Goal Based Standards” (GBS). FSA was introduced by the IMO as “a rational and systematic process for accessing the risk related to maritime safety and the protection of the marine...... environment and for evaluating the costs and benefits of IMO’s options for reducing these risks”. The recent GBS approach aims to be another proactive instrument, and there has been recent discussion in the IMO on the possible links between FSA and GBS. This paper attempts to clarify some widely used......, but confusing to many, notions such as Risk Based Rulemaking vs. Risk Based Design, and IMO's GBS Traditional Approach vs. Safety Level Approach, and the implications of their use, or misuse, to future ship rulemaking, design and safety. The paper elaborates on some identified weaknesses of the risk based...

  8. Establishing a design procedure for buried steel-reinforced high-density polyethylene pipes : a field study, [technical summary].

    Science.gov (United States)

    2015-11-01

    Several national standards and specification have been developed for design, installation, : and materials for precast concrete pipe, corrugated metal pipe, and HDPE pipes. However, : no national accepted installation standard or design method is ava...

  9. Design, Development and Evaluation of Collaborative Team Training Method in Virtual Worlds for Time-Critical Medical Procedures

    Science.gov (United States)

    Khanal, Prabal

    2014-01-01

    Medical students acquire and enhance their clinical skills using various available techniques and resources. As the health care profession has move towards team-based practice, students and trainees need to practice team-based procedures that involve timely management of clinical tasks and adequate communication with other members of the team.…

  10. Uncovering Procedural Knowledge in Craft, Design, and Technology Education: A Case of Hands-On Activities in Electronics

    Science.gov (United States)

    Pirttimaa, Matti; Husu, Jukka; Metsärinne, Mika

    2017-01-01

    Different knowledge types have their own specific features and tasks in the learning process. Procedural knowledge is used in craft and technology education when students solve problems individually and share their working knowledge with others. This study presents a detailed analysis of a one student's learning process in technology education and…

  11. Design of the measurements validation procedure and the expert system architecture for a cogeneration internal combustion engine

    International Nuclear Information System (INIS)

    Barelli, L.; Bidini, G.

    2005-01-01

    A research activity has been initiated to study the development of a diagnostic methodology, for the optimization of energy efficiency and the maximization of the operational time in those conditions, based on artificial intelligence (AI) techniques such as artificial neural network (ANN) and fuzzy logic. The diagnostic procedure, developed specifically for the cogeneration plant located at the Engineering Department of the University of Perugia, must be characterized by a modular architecture to obtain a flexible architecture applicable to different systems. The first part of the study deals with the identifying the principal modules and the corresponding variables necessary to evaluate the module 'health state'. Also the consequent upgrade of the monitoring system is described in this paper. Moreover it describes the structure proposed for the diagnostic procedure, consisting of a procedure for measurement validation and a fuzzy logic-based inference system. The first reveals the presence of abnormal conditions and localizes their source distinguishing between system failure and instrumentation malfunctions. The second provides an evaluation of module health state and the classification of the failures which have possibly occurred. The procedure was implemented in C++

  12. Intraclass Correlation Coefficients in Hierarchical Design Studies with Discrete Response Variables: A Note on a Direct Interval Estimation Procedure

    Science.gov (United States)

    Raykov, Tenko; Marcoulides, George A.

    2015-01-01

    A latent variable modeling procedure that can be used to evaluate intraclass correlation coefficients in two-level settings with discrete response variables is discussed. The approach is readily applied when the purpose is to furnish confidence intervals at prespecified confidence levels for these coefficients in setups with binary or ordinal…

  13. Function Allocation in Complex Socio-Technical Systems: Procedure usage in nuclear power and the Context Analysis Method for Identifying Design Solutions (CAMIDS) Model

    Science.gov (United States)

    Schmitt, Kara Anne

    This research aims to prove that strict adherence to procedures and rigid compliance to process in the US Nuclear Industry may not prevent incidents or increase safety. According to the Institute of Nuclear Power Operations, the nuclear power industry has seen a recent rise in events, and this research claims that a contributing factor to this rise is organizational, cultural, and based on peoples overreliance on procedures and policy. Understanding the proper balance of function allocation, automation and human decision-making is imperative to creating a nuclear power plant that is safe, efficient, and reliable. This research claims that new generations of operators are less engaged and thinking because they have been instructed to follow procedures to a fault. According to operators, they were once to know the plant and its interrelations, but organizationally more importance is now put on following procedure and policy. Literature reviews were performed, experts were questioned, and a model for context analysis was developed. The Context Analysis Method for Identifying Design Solutions (CAMIDS) Model was created, verified and validated through both peer review and application in real world scenarios in active nuclear power plant simulators. These experiments supported the claim that strict adherence and rigid compliance to procedures may not increase safety by studying the industry's propensity for following incorrect procedures, and when it directly affects the outcome of safety or security of the plant. The findings of this research indicate that the younger generations of operators rely highly on procedures, and the organizational pressures of required compliance to procedures may lead to incidents within the plant because operators feel pressured into following the rules and policy above performing the correct actions in a timely manner. The findings support computer based procedures, efficient alarm systems, and skill of the craft matrices. The solution to

  14. Guidelines for Risk-Based Changeover of Biopharma Multi-Product Facilities.

    Science.gov (United States)

    Lynch, Rob; Barabani, David; Bellorado, Kathy; Canisius, Peter; Heathcote, Doug; Johnson, Alan; Wyman, Ned; Parry, Derek Willison

    2018-01-01

    In multi-product biopharma facilities, the protection from product contamination due to the manufacture of multiple products simultaneously is paramount to assure product quality. To that end, the use of traditional changeover methods (elastomer change-out, full sampling, etc.) have been widely used within the industry and have been accepted by regulatory agencies. However, with the endorsement of Quality Risk Management (1), the use of risk-based approaches may be applied to assess and continuously improve established changeover processes. All processes, including changeover, can be improved with investment (money/resources), parallel activities, equipment design improvements, and standardization. However, processes can also be improved by eliminating waste. For product changeover, waste is any activity not needed for the new process or that does not provide added assurance of the quality of the subsequent product. The application of a risk-based approach to changeover aligns with the principles of Quality Risk Management. Through the use of risk assessments, the appropriate changeover controls can be identified and controlled to assure product quality is maintained. Likewise, the use of risk assessments and risk-based approaches may be used to improve operational efficiency, reduce waste, and permit concurrent manufacturing of products. © PDA, Inc. 2018.

  15. Development of a risk-based inservice inspection program for a liquid metal reactor

    International Nuclear Information System (INIS)

    King, R.W.; Buschman, H.W.

    1996-01-01

    The emerging application of risk-based assessment technology to the operation and maintenance of nuclear power plants holds considerable promise for improving efficiency and reducing operating costs. EBR-II is liquid-metal-cooled fast reactor which operated for thirty years before shutting down in September 1994 due to program termination. Prior to the shutdown of EBR-II, an in-service inspection (ISI) program was developed that exploited certain advantages of the liquid-metal reactor design, e.g., demonstrated passive response to plant upset events, low pressure primary coolant and compatibility of the coolant and reactor materials. Many of the systems cannot be inspected due to inaccessibility of the components. However, application of a risk-based approach provided the basis for reducing or eliminating inspections in some areas that would otherwise be required. Development and implementation of the risk-based ISI program was interrupted by the DOE-mandated shutdown of EBR-II, so the potential benefits of this approach in terms of reduced O and M costs have yet to be realized. Through the development of this program, however it is clear that there is potential for substantial cost-savings while improving the risk-profile of the facility through this approach

  16. Design-related influencing factors of the computerized procedure system for inclusion into human reliability analysis of the advanced control room

    International Nuclear Information System (INIS)

    Kim, Jaewhan; Lee, Seung Jun; Jang, Seung Cheol; Ahn, Kwang-Il; Shin, Yeong Cheol

    2013-01-01

    This paper presents major design factors of the computerized procedure system (CPS) by task characteristics/requirements, with individual relative weight evaluated by the analytic hierarchy process (AHP) technique, for inclusion into human reliability analysis (HRA) of the advanced control rooms. Task characteristics/requirements of an individual procedural step are classified into four categories according to the dynamic characteristics of an emergency situation: (1) a single-static step, (2) a single-dynamic and single-checking step, (3) a single-dynamic and continuous-monitoring step, and (4) a multiple-dynamic and continuous-monitoring step. According to the importance ranking evaluation by the AHP technique, ‘clearness of the instruction for taking action’, ‘clearness of the instruction and its structure for rule interpretation’, and ‘adequate provision of requisite information’ were rated as of being higher importance for all the task classifications. Importance of ‘adequacy of the monitoring function’ and ‘adequacy of representation of the dynamic link or relationship between procedural steps’ is dependent upon task characteristics. The result of the present study gives a valuable insight on which design factors of the CPS should be incorporated, with relative importance or weight between design factors, into HRA of the advanced control rooms. (author)

  17. Risk-based decision making for terrorism applications.

    Science.gov (United States)

    Dillon, Robin L; Liebe, Robert M; Bestafka, Thomas

    2009-03-01

    This article describes the anti-terrorism risk-based decision aid (ARDA), a risk-based decision-making approach for prioritizing anti-terrorism measures. The ARDA model was developed as part of a larger effort to assess investments for protecting U.S. Navy assets at risk and determine whether the most effective anti-terrorism alternatives are being used to reduce the risk to the facilities and war-fighting assets. With ARDA and some support from subject matter experts, we examine thousands of scenarios composed of 15 attack modes against 160 facility types on two installations and hundreds of portfolios of 22 mitigation alternatives. ARDA uses multiattribute utility theory to solve some of the commonly identified challenges in security risk analysis. This article describes the process and documents lessons learned from applying the ARDA model for this application.

  18. Risk-based Operation and Maintenance for Offshore Wind Turbines

    DEFF Research Database (Denmark)

    Sørensen, John Dalsgaard; Nielsen, Jannie Jessen

    2011-01-01

    For offshore wind turbines, costs to Operation and Maintenance (OM) are substantial, and can be expected to increase when wind farms are placed at deeper water depths and in more harsh environments. Traditional strategies for OM include corrective and preventive (scheduled and condition...... statistics and costs of the different operations. The different OM strategies are described and compared in an illustrative example with focus on which types of information that are needed. Special focus is on comparison between risk-based maintenance strategies and the conventional maintenance planning...... and are often the driving mechanisms for failures / faults that need maintenance. Observations of the degree of damage can increase the reliability of predictions and decrease the costs of OM if integrated in a risk-based framework theoretically based on pre-posterior Bayesian decision theory. The mathematical...

  19. Application of risk-based inspection methods for cryogenic equipment

    CERN Multimedia

    CERN. Geneva

    2016-01-01

    Risk-based Inspection (RBI) is widely applied across the world as part of Pressure Equipment Integrity Management, especially in the oil and gas industry, to generally reduce costs compared with time-based approaches and assist in assigning resources to the most critical equipment. One of the challenges in RBI is to apply it for low temperature and cryogenic applications, as there are usually no degradation mechanisms by which to determine a suitable probability of failure in the overall risk assessment. However, the assumptions used for other degradation mechanisms can be adopted to determine, qualitatively and semi-quantitatively, a consequence of failure within the risk assessment. This can assist in providing a consistent basis for the assumptions used in ensuring adequate process safety barriers and determining suitable sizing of relief devices. This presentation will discuss risk-based inspection in the context of cryogenic safety, as well as present some of the considerations for the risk assessme...

  20. Guidelines for Implementing NCHRP 1-37A M-E Design Procedures in Ohio : Volume 3 -- Sensitivity Analysis

    Science.gov (United States)

    2009-11-01

    The new Mechanistic-Empirical Pavement Design Guide (NCHRP 1-37A and 1-40D) is based on fundamental engineering principles and is far more comprehensive than the current empirical AASHTO Design Guide developed for conditions more than 40 years previo...

  1. Guidelines for Implementing NCHRP 1-37A M-E Design Procedures in Ohio : Volume 2 -- Literature Review

    Science.gov (United States)

    2009-11-01

    The development of the Mechanistic-Empirical Pavement Design Guide (MEPDG) under National Cooperative Highway Research Program (NCHRP) projects 1-37A and 1-40D has significantly improved the ability of pavement designers to model and simulate the eff...

  2. Risk-based configuration control system: Analysis and approaches

    International Nuclear Information System (INIS)

    Samanta, P.K.; Kim, I.S.; Vesely, W.E.; Lofgren, E.V.

    1989-01-01

    This paper presents an evaluation of the configuration risks associated with the operation of a nuclear power plant and the approaches to control these risks using risk-based configuration control considerations. In that context, the actual and maximum potential configuration risks at a plant are analyzed and the alternative types criteria for a risk-based configuration control systems are described. The risk-based configuration calculations which are studied here focus on the core-melt frequency impacts from given plant configurations. By calculating the core-melt frequency for given configurations, the configurations which cause large core-melt frequency increases can be identified and controlled. The duration time in which the configuration can exist can then be limited or the core-melt frequency level associated with the configuration can be reduced by various actions. Furthermore, maintenances and tests can be scheduled to avoid the configurations which cause large core-melt frequency increases. Present technical specifications do not control many of these configurations which can cause large core-melt frequency increases but instead focus on many risk-unimportant allowed outage times. Hence, risk-based configuration management can be effectively used to reduce core-melt frequency associated risks at a plant and at the same time can provide flexibility in plant operation. The alternative strategies for controlling the core-melt frequency and other risk contributions include: (1) controlling the increased risk level which is associated with the configuration; (2) controlling the individual configuration risk which is associated with a given duration of a configuration; (3) controlling the time period configuration risk from configurations which occur in a time period

  3. Toward risk-based control of nuclear power plant configurations

    International Nuclear Information System (INIS)

    Samanta, P.K.; Veseley, W.E.; Kim, I.S.

    1992-01-01

    This paper presents an evaluation of the configuration risks associated with the operation of a nuclear power plant and the approaches to control these risks using risk-based configuration control considerations. In that context, the actual and maximum potential configuration risks at a plant are analyzed and the alternative types criteria for a risk-based configuration control systems are described. The risk-based configuration calculations which are studied here focus on the core-melt frequency impacts from given plant configurations, the configurations which cause large core-melt frequency increases can be identified and controlled. The duration time in which the configuration can exist can then be limited or the core-melt frequency level associated with the configuration can be reduced by various actions. Futhermore, maintenances and tests can be scheduled to avoid the configurations which cause large core-melt frequency increases. Present technical specifications do not control many of these configurations which can cause large core-melt frequency increases but instead focus on many risk-unimportant allowed outage times. Hence, risk-based configuration management can be effectively used to reduce core-melt frequency associated risks at a plant and at the same time can provide flexibility in plant operation. The alternative strategies for controlling the core-melt frequency and other risk contributions include: (1) controlling the increased risk level which is associated with the configuration; (2) controlling the individual configuration risk which is associated with a given duration of a configuration; (3) controlling the time period configuration risk from configurations which occur in a time period. (orig.)

  4. Strategies and criteria for risk-based configuration control

    International Nuclear Information System (INIS)

    Samanta, P.K.; Kim, I.S.; Vesely, W.E.

    1991-01-01

    A configuration, as used here, is a set of component operability or statuses that define the state of a nuclear power plant. Risk-based configuration control is the management of component configurations using a risk perspective to control risk and assure safety. If the component configurations that have high risk implications do not occur then the risk from the operation of nuclear power plants would be minimal. The control of component configurations, i.e., the management of component statuses, so that the risk from components being unavailable is minimized, becomes difficult because the status of a standby safety system component is often not apparent unless it is tested. In this paper, we discuss the strategies and criteria for risk-based configuration control in nuclear power plants. In developing these strategies and criteria, the primary objective is to obtain more direct risk control but the added benefit is the effective use of plant resources. Implementation of such approaches can result in replacement/modification of parts of Technical Specifications. Specifically, the risk impact or safety impact of a configuration depends upon four factors: (1) The configuration components which are simultaneously down (i.e., inoperable); (2) the backup components which are known to be up (i.e., operable); (3) the duration of time the configuration exists (the outage time); and (4) the frequency at which the configuration occurs. Risk-based configuration control involves managing these factors using risk analyses and risk insights. In this paper, we discuss each of the factors and illustrate how they can be controlled. The information and the tools needed in implementing configuration control are also discussed. The risk-based calculation requirements in achieving the control are also delineated. 4 refs., 4 figs., 1 tab

  5. Towards risk-based structural integrity methods for PWRs

    International Nuclear Information System (INIS)

    Chapman, O.J.V.; Lloyd, R.B.

    1992-01-01

    This paper describes the development of risk-based structural integrity assurance methods and their application to Pressurized Water Reactor (PWR) plant. In-service inspection is introduced as a way of reducing the failure probability of high risk sites and the latter are identified using reliability analysis; the extent and interval of inspection can also be optimized. The methodology is illustrated by reference to the aspect of reliability of weldments in PWR systems. (author)

  6. Quantification of Technology Innovation Usinga Risk-Based Framework

    OpenAIRE

    Gerard E. Sleefe

    2010-01-01

    There is significant interest in achieving technology innovation through new product development activities. It is recognized, however, that traditional project management practices focused only on performance, cost, and schedule attributes, can often lead to risk mitigation strategies that limit new technology innovation. In this paper, a new approach is proposed for formally managing and quantifying technology innovation. This approach uses a risk-based framework that s...

  7. Effectiveness of a risk-based visitor-prioritizing system at a sexually transmitted infection outpatient clinic

    NARCIS (Netherlands)

    Heijman, T.L.J.; van der Bij, A.K.; de Vries, H.J.C.; van Leent, E.J.M.; Thiesbrummel, H.F.J.; Fennema, H.S.A.

    2007-01-01

    Objective: The objective of this study was to study the efficacy/effectiveness of a risk-based visitor-prioritizing system at a sexually transmitted infection (STI) clinic aimed to improve screening capacity by providing tailored service. Study Design: In April 2004, a prioritizing system was

  8. The use of operator surveys by the CEGB to evaluate nuclear control room design and initiatives in the design of alarm systems and control room operating procedures

    International Nuclear Information System (INIS)

    Jackson, A.R.G.

    1988-01-01

    This paper reports on the use of operator surveys and trip report analysis methods which the Central Electricity Generating Board has developed to assess the extent and adequacy of operator support systems currently installed on its four twin-reactor, first generation Advanced Gas Cooled Reactor nuclear power plants. The survey consisted of a programme of structured interviews with control room engineers. The scope of the questions addressed; working environment, communications, man-machine interface, procedural information, and the diagnostic and predictive support system. The analysis of trip reports was targetted at identifying aspects of the performance of the operator support systems which might have been contributory to the cause of reactor trip. The results of this work are being used to assist in determining guidelines for the development of operator support systems, computerised controls and the structure of station operating procedures

  9. Enhancing the effectiveness of IST through risk-based techniques

    Energy Technology Data Exchange (ETDEWEB)

    Floyd, S.D.

    1996-12-01

    Current IST requirements were developed mainly through deterministic-based methods. While this approach has resulted in an adequate level of safety and reliability for pumps and valves, insights from probabilistic safety assessments suggest a better safety focus can be achieved at lower costs. That is, some high safety impact pumps and valves are currently not tested under the IST program and should be added, while low safety impact valves could be tested at significantly greater intervals than allowed by the current IST program. The nuclear utility industry, through the Nuclear Energy Institute (NEI), has developed a draft guideline for applying risk-based techniques to focus testing on those pumps and valves with a high safety impact while reducing test frequencies on low safety impact pumps and valves. The guideline is being validated through an industry pilot application program that is being reviewed by the U.S. Nuclear Regulatory Commission. NEI and the ASME maintain a dialogue on the two groups` activities related to risk-based IST. The presenter will provide an overview of the NEI guideline, discuss the methodological approach for applying risk-based technology to IST and provide the status of the industry pilot plant effort.

  10. Risk based maintenance to increase safety and decrease costs

    International Nuclear Information System (INIS)

    Phillips, J.H.

    2000-01-01

    Risk-Based techniques have been developed for commercial nuclear power plants for the last eight years by a team working through the ASME Center for Research and Technology Development (CRTD). System boundaries and success criteria is defined using the Probabilistic Risk Analysis or Probabilistic Safety Analysis developed to meet the Individual Plant Evaluation. Final ranking of components is by a plant expert panel similar to the one developed for the Maintenance Rule. Components are identified as being high risk-significant or low risk-significant. Maintenance and resources are focused on those components that have the highest risk-significance. The techniques have been developed and applied at a number of plants. Results from the first risk-based inspection pilot plant indicates safety due to pipe failure can be doubled while the inspection reduced to about 80% when compared with current inspection programs. Pilot studies on risk-based testing indicate that about 60% of pumps and 25 to 30% of valves in plants are high safety-significant The reduction in inspection and testing reduces the person-rem exposure and resulting in further increases in safety. These techniques have been documented in publications by the ASME CRTD which are referenced. (author)

  11. Effects of a risk-based online mammography intervention on accuracy of perceived risk and mammography intentions.

    Science.gov (United States)

    Seitz, Holli H; Gibson, Laura; Skubisz, Christine; Forquer, Heather; Mello, Susan; Schapira, Marilyn M; Armstrong, Katrina; Cappella, Joseph N

    2016-10-01

    This experiment tested the effects of an individualized risk-based online mammography decision intervention. The intervention employs exemplification theory and the Elaboration Likelihood Model of persuasion to improve the match between breast cancer risk and mammography intentions. 2918 women ages 35-49 were stratified into two levels of 10-year breast cancer risk (<1.5%; ≥1.5%) then randomly assigned to one of eight conditions: two comparison conditions and six risk-based intervention conditions that varied according to a 2 (amount of content: brief vs. extended) x 3 (format: expository vs. untailored exemplar [example case] vs. tailored exemplar) design. Outcomes included mammography intentions and accuracy of perceived breast cancer risk. Risk-based intervention conditions improved the match between objective risk estimates and perceived risk, especially for high-numeracy women with a 10-year breast cancer risk ≤1.5%. For women with a risk≤1.5%, exemplars improved accuracy of perceived risk and all risk-based interventions increased intentions to wait until age 50 to screen. A risk-based mammography intervention improved accuracy of perceived risk and the match between objective risk estimates and mammography intentions. Interventions could be applied in online or clinical settings to help women understand risk and make mammography decisions. Copyright © 2016 Elsevier Ireland Ltd. All rights reserved.

  12. Coordinating resources for prospective medication risk management of older home care clients in primary care: procedure development and RCT study design for demonstrating its effectiveness.

    Science.gov (United States)

    Toivo, Terhi; Dimitrow, Maarit; Puustinen, Juha; Savela, Eeva; Pelkonen, Katariina; Kiuru, Valtteri; Suominen, Tuula; Kinnunen, Sirkka; Uunimäki, Mira; Kivelä, Sirkka-Liisa; Leikola, Saija; Airaksinen, Marja

    2018-03-16

    The magnitude of safety risks related to medications of the older adults has been evidenced by numerous studies, but less is known of how to manage and prevent these risks in different health care settings. The aim of this study was to coordinate resources for prospective medication risk management of home care clients ≥ 65 years in primary care and to develop a study design for demonstrating effectiveness of the procedure. Health care units involved in the study are from primary care in Lohja, Southern Finland: home care (191 consented clients), the public healthcare center, and a private community pharmacy. System based risk management theory and action research method was applied to construct the collaborative procedure utilizing each profession's existing resources in medication risk management of older home care clients. An inventory of clinical measures in usual clinical practice and systematic review of rigorous study designs was utilized in effectiveness study design. The new coordinated medication management model (CoMM) has the following 5 stages: 1) practical nurses are trained to identify clinically significant drug-related problems (DRPs) during home visits and report those to the clinical pharmacist. Clinical pharmacist prepares the cases for 2) an interprofessional triage meeting (50-70 cases/meeting of 2 h) where decisions are made on further action, e.g., more detailed medication reviews, 3) community pharmacists conduct necessary medication reviews and each patients' physician makes final decisions on medication changes needed. The final stages concern 4) implementation and 5) follow-up of medication changes. Randomized controlled trial (RCT) was developed to demonstrate the effectiveness of the procedure. The developed procedure is feasible for screening and reviewing medications of a high number of older home care clients to identify clients with severe DRPs and provide interventions to solve them utilizing existing primary care resources

  13. Optimization of instrumental neutron activation analysis method by means of 2k experimental design technique aiming the validation of analytical procedures

    International Nuclear Information System (INIS)

    Petroni, Robson; Moreira, Edson G.

    2013-01-01

    In this study optimization of procedures and standardization of Instrumental Neutron Activation Analysis (INAA) methods were carried out for the determination of the elements arsenic, chromium, cobalt, iron, rubidium, scandium, selenium and zinc in biological materials. The aim is to validate the analytical methods for future accreditation at the National Institute of Metrology, Quality and Technology (INMETRO). The 2 k experimental design was applied for evaluation of the individual contribution of selected variables of the analytical procedure in the final mass fraction result. Samples of Mussel Tissue Certified Reference Material and multi-element standards were analyzed considering the following variables: sample decay time, counting time and sample distance to detector. The standard multi-element concentration (comparator standard), mass of the sample and irradiation time were maintained constant in this procedure. By means of the statistical analysis and theoretical and experimental considerations it was determined the optimized experimental conditions for the analytical methods that will be adopted for the validation procedure of INAA methods in the Neutron Activation Analysis Laboratory (LAN) of the Research Reactor Center (CRPq) at the Nuclear and Energy Research Institute (IPEN - CNEN/SP). Optimized conditions were estimated based on the results of z-score tests, main effect and interaction effects. The results obtained with the different experimental configurations were evaluated for accuracy (precision and trueness) for each measurement. (author)

  14. Optimization of instrumental neutron activation analysis method by means of 2{sup k} experimental design technique aiming the validation of analytical procedures

    Energy Technology Data Exchange (ETDEWEB)

    Petroni, Robson; Moreira, Edson G., E-mail: rpetroni@ipen.br, E-mail: emoreira@ipen.br [Instituto de Pesquisas Energeticas e Nucleares (IPEN/CNEN-SP), Sao Paulo, SP (Brazil)

    2013-07-01

    In this study optimization of procedures and standardization of Instrumental Neutron Activation Analysis (INAA) methods were carried out for the determination of the elements arsenic, chromium, cobalt, iron, rubidium, scandium, selenium and zinc in biological materials. The aim is to validate the analytical methods for future accreditation at the National Institute of Metrology, Quality and Technology (INMETRO). The 2{sup k} experimental design was applied for evaluation of the individual contribution of selected variables of the analytical procedure in the final mass fraction result. Samples of Mussel Tissue Certified Reference Material and multi-element standards were analyzed considering the following variables: sample decay time, counting time and sample distance to detector. The standard multi-element concentration (comparator standard), mass of the sample and irradiation time were maintained constant in this procedure. By means of the statistical analysis and theoretical and experimental considerations it was determined the optimized experimental conditions for the analytical methods that will be adopted for the validation procedure of INAA methods in the Neutron Activation Analysis Laboratory (LAN) of the Research Reactor Center (CRPq) at the Nuclear and Energy Research Institute (IPEN - CNEN/SP). Optimized conditions were estimated based on the results of z-score tests, main effect and interaction effects. The results obtained with the different experimental configurations were evaluated for accuracy (precision and trueness) for each measurement. (author)

  15. Experience with the implementation of a risk-based ISI program and inspection qualification

    International Nuclear Information System (INIS)

    Chapman, O.J.V.

    1996-01-01

    Rolls Royce and Associates (RRA) are the Design Authority (DA) for Nuclear Steam Raising Plant (NSRP) used for the Royal Naval Nuclear Fleet. Over the past seven years RRA, with support from the Ministry of Defense, has developed and implemented a risk based in-service inspection (RBISI) strategy for the NSRP. Having used risk as a means of optimizing where to inspect, an inspection qualification (IQ) process has now been put in place to ensure that proposed inspections deliver the expected gains assumed. This qualification process follows very closely that currently being put forward by the European Network on Inspection Qualification (ENIQ)

  16. Risk-based environmental assessment for uranium mines – Some Canadian and Australian experience

    International Nuclear Information System (INIS)

    Phaneuf, M.; McKee, M.; Woods, P.

    2014-01-01

    The Risk-Based Approach to Environmental Assessment in Australia: • This has emerged over the last 2 decades; • Currently usually based around the Australian and New Zealand standard (AS4360:1999) for risk assessment: • Potential impact events; • Inherent risk levels (e.g. low, moderate) using a matrix approach; • Design and operational control measures; • Residual risk levels; • Outcomes to be achieved; • Outcomes measurement criteria - • Leading to ‘compliance’ monitoring; • Leading indicator criteria - • Leading to ‘early warning’ monitoring

  17. Does the Drug Facts Label for nonprescription drugs meet its design objectives? A new procedure for assessing label effectiveness

    Directory of Open Access Journals (Sweden)

    Michael P Ryan

    2017-07-01

    Full Text Available We demonstrate an expanded procedure for assessing drug-label comprehension. Innovations include a pretest of drug preconceptions, verbal ability and label attentiveness measures, a label-scanning task, a free-recall test, category-clustering measures, and preconception-change scores. In total, 55 female and 39 male undergraduates read a facsimile Drug Facts Label for aspirin, a Cohesive-Prose Label, or a Scrambled-Prose Label. The Drug Facts Label outperformed the Scrambled-Prose Label, but not the Cohesive-Prose Label, in scanning effectiveness. The Drug Facts Label was no better than the Cohesive-Prose Label or the Scrambled-Prose Label in promoting attentiveness, recall and organization of drug facts, or misconception refutation. Discussion focuses on the need for refutational labels based on a sequence-of-events text schema.

  18. 42 CFR 137.365 - What is the procedure for the Secretary's review and approval of project planning and design...

    Science.gov (United States)

    2010-10-01

    ... SERVICE, DEPARTMENT OF HEALTH AND HUMAN SERVICES TRIBAL SELF-GOVERNANCE Construction Roles of the...-Governance Tribe? (a) The Secretary shall review and approve planning documents to ensure compliance with... design documents for general compliance with requirements of the construction project agreement. (b) The...

  19. Risk-based audit selection of dairy farms.

    Science.gov (United States)

    van Asseldonk, M A P M; Velthuis, A G J

    2014-02-01

    Dairy farms are audited in the Netherlands on numerous process standards. Each farm is audited once every 2 years. Increasing demands for cost-effectiveness in farm audits can be met by introducing risk-based principles. This implies targeting subpopulations with a higher risk of poor process standards. To select farms for an audit that present higher risks, a statistical analysis was conducted to test the relationship between the outcome of farm audits and bulk milk laboratory results before the audit. The analysis comprised 28,358 farm audits and all conducted laboratory tests of bulk milk samples 12 mo before the audit. The overall outcome of each farm audit was classified as approved or rejected. Laboratory results included somatic cell count (SCC), total bacterial count (TBC), antimicrobial drug residues (ADR), level of butyric acid spores (BAB), freezing point depression (FPD), level of free fatty acids (FFA), and cleanliness of the milk (CLN). The bulk milk laboratory results were significantly related to audit outcomes. Rejected audits are likely to occur on dairy farms with higher mean levels of SCC, TBC, ADR, and BAB. Moreover, in a multivariable model, maxima for TBC, SCC, and FPD as well as standard deviations for TBC and FPD are risk factors for negative audit outcomes. The efficiency curve of a risk-based selection approach, on the basis of the derived regression results, dominated the current random selection approach. To capture 25, 50, or 75% of the population with poor process standards (i.e., audit outcome of rejected), respectively, only 8, 20, or 47% of the population had to be sampled based on a risk-based selection approach. Milk quality information can thus be used to preselect high-risk farms to be audited more frequently. Copyright © 2014 American Dairy Science Association. Published by Elsevier Inc. All rights reserved.

  20. Risk-based remediation of polluted sites: A critical perspective.

    Science.gov (United States)

    Kuppusamy, Saranya; Venkateswarlu, Kadiyala; Megharaj, Mallavarapu; Mayilswami, Srinithi; Lee, Yong Bok

    2017-11-01

    Sites contaminated with chemical pollutants represent a growing challenge, and remediation of such lands is of international concern. Risk-based land management (RBLM) is an emerging approach that integrates risk assessment practices with more traditional site-specific investigations and remediation activities. Developing countries are yet to adopt RBLM strategies for remediation. RBLM is considered to be practical, scientifically defensible and cost-efficient. However, it is inherently limited by: firstly, the accuracy of risk assessment models used; secondly, ramifications of the fact that they are more likely to leave contamination in place; and thirdly, uncertainties involved and having to consider the total concentrations of all contaminants in soils that overestimate the potential risks from exposure to the contaminants. Consideration of contaminant bioavailability as the underlying basis for risk assessment and setting remediation goals of those contaminated lands that pose a risk to environmental and human health may lead to the development of a more sophisticated risk-based approach. However, employing the bioavailability concept in RBLM has not been extensively studied and/or legalized. This review highlights the extent of global land contamination, and the concept of risk-based assessment and management of contaminated sites including its advantages and disadvantages. Furthermore, the concept of bioavailability-based RBLM strategy has been proposed, and the challenges of RBLM and the priority areas for future research are summarized. Thus, the present review may help achieve a better understanding and successful implementation of a sustainable bioavailability-based RBLM strategy. Copyright © 2017 Elsevier Ltd. All rights reserved.

  1. Risk Based Maintenance of Offshore Wind Turbines Using Bayesian Networks

    DEFF Research Database (Denmark)

    Nielsen, Jannie Jessen; Sørensen, John Dalsgaard

    2010-01-01

    This paper presents how Bayesian networks can be used to make optimal decisions for repairs of offshore wind turbines. The Bayesian network is an efficient tool for updating a deterioration model whenever new information becomes available from inspections/monitoring. The optimal decision is found...... such that the preventive maintenance effort is balanced against the costs to corrective maintenance including indirect costs to reduced production. The basis for the optimization is the risk based Bayesian decision theory. The method is demonstrated through an application example....

  2. Competency-based (CanMEDS) residency training programme in radiology: systematic design procedure, curriculum and success factors

    International Nuclear Information System (INIS)

    Jippes, Erik; Engelen, Jo M.L. van; Brand, Paul L.P.; Oudkerk, Matthijs

    2010-01-01

    Based on the CanMEDS framework and the European Training Charter for Clinical Radiology a new radiology curriculum was designed in the Netherlands. Both the development process and the resulting new curriculum are presented in this paper. The new curriculum was developed according to four systematic design principles: discursiveness, hierarchical decomposition, systematic variation and satisficing (satisficing is different from satisfying; in this context, satisficing means searching for an acceptable solution instead of searching for an optimal solution). The new curriculum is organ based with integration of radiological diagnostic techniques, comprises a uniform national common trunk followed by a 2-year subspecialisation, is competency outcome based with appropriate assessment tools and techniques, and is based on regional collaboration among radiology departments. The application of the systematic design principles proved successful in producing a new curriculum approved by all authorities. The principles led to a structured, yet flexible, development process in which creative solutions could be generated and adopters (programme directors, supervisors and residents) were highly involved. Further research is needed to empirically test the components of the new curriculum. (orig.)

  3. Lyophilization Cycle Design for Dual Chamber Cartridges and a Method for Online Process Control: The "DCC LyoMate" Procedure.

    Science.gov (United States)

    Korpus, Christoph; Friess, Wolfgang

    2017-08-01

    Freeze-drying process design is a challenging task that necessitates a profound understanding of the complex interrelation among critical process parameters (e.g., shelf temperature and chamber pressure), heat transfer characteristics of the involved materials (e.g., product containers and holder devices), and critical quality attributes of the product (e.g., collapse temperatures). The Dual Chamber Cartridge "(DCC) LyoMate" (from lyophilization and automated) is a manometric temperature measurement-based process control strategy that was developed within this study to streamline this complicated task. It was successfully applied using 5% sucrose formulations with 0.5 and 1 mL fill volumes. The system was further challenged using 2, 20, and 100 mg/mL monoclonal antibody formulations. The DCC LyoMate method did not only produce pharmaceutically acceptable cakes but was also able to maintain the desired product temperature irrespective of formulation and protein content. It enabled successful process design even at high protein concentrations and aided the design and online control of the lyophilization process for drying in DCCs within a single development run. Thus, it helps to reduce development cost and the DCC LyoMate can also be easily installed on every freeze-dryer capable of performing a manometric temperature measurement, without the need for hardware modification. Copyright © 2017 American Pharmacists Association®. Published by Elsevier Inc. All rights reserved.

  4. Comparative evaluation of two radioenzymatic procedures designed to determine noradrenaline in the plasma (COMT assay and PNMT assay)

    International Nuclear Information System (INIS)

    Barth, A.

    1984-01-01

    A comparative evaluation of two radioenzymatic procedures to determine the concentration of noradrenaline in the plasma - with linearity, sensitivity, specifity and accuracy serving as test criteria - led to the following results: In view of a probability of error in the order of 2% both methods were judged to show a satisfactory sensitivity. The specific of the COMT assay, by contrast with that of the PNMT assay, was found to be wanting, as the noradrenaline measurements in the presence of other biogenic amines were biassed in such a way that the values determined were higher than the actual concentrations. During antihypertensive treatment even minimal changes in the noradrenaline concentration can be ascertained on a quantitative basis. If suitable hardware is available, the COMT assay permits up to 25 single determinations to be carried out per day, while the number of double determinations is restricted to 7 per day. One advantage, however, lies in the fact that several catecholamines in the plasma can be detected simultaneously, if required. In cases where the noradrenaline concentration alone is to be determined for clinical purposes, preference should be given to the PNMT assay, as both tests showed equal linearity and sensitivity. (TRV) [de

  5. Risk-based decisionmaking in the DOE: Challenges and status

    International Nuclear Information System (INIS)

    Henry, C.J.; Alchowiak, J.; Moses, M.

    1995-01-01

    The primary mission of the Environmental Management Program is to protect human health and the environment, the first goal of which must be, to address urgent risks and threats. Another is to provide for a safe workplace. Without credible risk assessments and good risk management practices, the central environmental goals cannot be met. Principles for risk analysis which include principles for risk assessment, management, communication, and priority setting were adopted. As recommended, Environmental Management is using risk-based decision making in its budget process and in the implementation of its program. The challenges presented in using a risk-based Decision making process are to integrate risk assessment methods and cultural and social values so as to produce meaningful priorities. The different laws and regulations governing the Department define risk differently in implementing activities to protect human health and the environment, therefore, assumptions and judgements in risk analysis vary. Currently, the Environmental Management Program is developing and improving a framework to incorporate risk into the budget process and to link the budget, compliance requirements and risk reduction/pollution prevention activities

  6. Risk-based configuration control system: Analysis and approaches

    International Nuclear Information System (INIS)

    Samanta, P.K.; Kim, I.S.; Lofgren, E.V.; Vesely, W.E.

    1990-01-01

    This paper presents an analysis of risks associated with component outage configurations during power operation of a nuclear power plant and discusses approaches and strategies for developing a risk-based configuration control system. A configuration, as used here, is a set of component states. The objective of risk-based configuration control is to detect and control plant configurations using a risk-perspective. The configuration contributions to core-melt frequency and core-melt probability are studied for two plants. Large core-melt frequency can be caused by configurations and there are a number of such configurations that are not currently controlled by technical specifications. However, the expected frequency of occurrence of the impacting configurations is small and the actual core-melt probability contributions are also generally small. Effective strategies and criteria for controlling configuration risks are presented. Such control strategies take into consideration the risks associated with configurations, the nature and characteristics of the configuration risks, and also the practical considerations such as adequate repair times and/or options to transfer to low risk configurations. Alternative types of criteria are discussed that are not overly restrictive to result in unnecessary plant shutdown, but rather motivates effective test and maintenance practices that control risk-significant configurations to allow continued operation with an adequate margin to meet challenges to safety

  7. Application of risk-based methodologies to prioritize safety resources

    International Nuclear Information System (INIS)

    Rahn, F.J.; Sursock, J.P.; Hosler, J.

    1993-01-01

    The Electric Power Research Institute (EPRI) started a program entitled risk-based prioritization in 1992. The purpose of this program is to provide generic technical support to the nuclear power industry relative to its recent initiatives in the area of operations and maintenance (O ampersand M) cost control using state-of-the-art risk methods. The approach uses probabilistic risk assessment (PRA), or similar techniques, to allocate resources commensurate with the risk posed by nuclear plant operations. Specifically, those items or events that have high risk significance would receive the most attention, while those with little risk content would command fewer resources. As quantified in a companion paper,close-quote the potential O ampersand M cost reduction inherent in this approach is very large. Furthermore, risk-based methods should also lead to safety improvements. This paper outlines the way that the EPRI technical work complements the technical, policy, and regulatory initiatives taken by others in the industry and provides an example of the approach as used to prioritize motor-operated valve (MOV) testing in response to US Nuclear Regulatory Commission (NRC) Generic Letter 89-10

  8. Risk-based configuration control system: Analysis and approaches

    International Nuclear Information System (INIS)

    Samanta, P.K.; Vesely, W.E.; Kim, I.S.; Lofgren, E.V.

    1989-01-01

    This paper presents an analysis of risks associated with component outage configurations during power operation of a nuclear power plant and discusses approaches and strategies for developing a risk-based configuration control system. A configuration, as used here, is a set of component states. The objective of risk-based configuration control is to detect and control plant configurations using a risk-perspective. The configuration contributions to core-melt frequency and core-melt probability are studied for two plants. Large core-melt frequency can be caused by configurations and there are a number of such configurations that are not currently controlled by technical specifications. However, the expected frequency of occurrence of the impacting configurations is small and the actual core-melt probability contributions are also generally small. Effective strategies and criteria for controlling configuration risks are presented. Such control strategies take into consideration the risks associated with configurations, the nature and characteristics of the configuration risks, and also the practical considerations such as adequate repair times and/or options to transfer to low risk configurations. Alternative types of criteria are discussed that are not overly restrictive to result in unnecessary plant shutdown, but rather motivates effective tests and maintenance practices that control; risk-significant configurations to allow continued operation with an adequate margin to meet challenges to safety. 3 refs., 7 figs., 2 tabs

  9. Study of operational risk-based configuration control

    Energy Technology Data Exchange (ETDEWEB)

    Vesely, W E [Science Applications International Corp., Dublin, OH (United States); Samanta, P K; Kim, I S [Brookhaven National Lab., Upton, NY (United States)

    1991-08-01

    This report studies aspects of a risk-based configuration control system to detect and control plant configurations from a risk perspective. Configuration control, as the term is used here, is the management of component configurations to achieve specific objectives. One important objective is to control risk and safety. Another is to operate efficiently and make effective use of available resources. PSA-based evaluations are performed to study configuration to core-melt frequency and core-melt probability for two plants. Some equipment configurations can cause large core-melt frequency and there are a number of such configurations that are not currently controlled by technical specifications. However, the expected frequency of occurrence of the impacting configurations is small and the core-melt probability contributions are also generally small. The insights from this evaluation are used to develop the framework for an effective risk-based configuration control system. The focal points of such a system and the requirements for tools development for implementing the system are defined. The requirements of risk models needed for the system, and the uses of plant-specific data are also discussed. 18 refs., 25 figs., 10 tabs.

  10. Risk-based decisionmaking in the DOE: Challenges and status

    Energy Technology Data Exchange (ETDEWEB)

    Henry, C.J.; Alchowiak, J.; Moses, M. [Dept. of Energy, Washington, DC (United States)] [and others

    1995-12-31

    The primary mission of the Environmental Management Program is to protect human health and the environment, the first goal of which must be, to address urgent risks and threats. Another is to provide for a safe workplace. Without credible risk assessments and good risk management practices, the central environmental goals cannot be met. Principles for risk analysis which include principles for risk assessment, management, communication, and priority setting were adopted. As recommended, Environmental Management is using risk-based decision making in its budget process and in the implementation of its program. The challenges presented in using a risk-based Decision making process are to integrate risk assessment methods and cultural and social values so as to produce meaningful priorities. The different laws and regulations governing the Department define risk differently in implementing activities to protect human health and the environment, therefore, assumptions and judgements in risk analysis vary. Currently, the Environmental Management Program is developing and improving a framework to incorporate risk into the budget process and to link the budget, compliance requirements and risk reduction/pollution prevention activities.

  11. Toward a Safety Risk-Based Classification of Unmanned Aircraft

    Science.gov (United States)

    Torres-Pomales, Wilfredo

    2016-01-01

    There is a trend of growing interest and demand for greater access of unmanned aircraft (UA) to the National Airspace System (NAS) as the ongoing development of UA technology has created the potential for significant economic benefits. However, the lack of a comprehensive and efficient UA regulatory framework has constrained the number and kinds of UA operations that can be performed. This report presents initial results of a study aimed at defining a safety-risk-based UA classification as a plausible basis for a regulatory framework for UA operating in the NAS. Much of the study up to this point has been at a conceptual high level. The report includes a survey of contextual topics, analysis of safety risk considerations, and initial recommendations for a risk-based approach to safe UA operations in the NAS. The next phase of the study will develop and leverage deeper clarity and insight into practical engineering and regulatory considerations for ensuring that UA operations have an acceptable level of safety.

  12. A risk-based approach to prioritize underground storage tanks

    International Nuclear Information System (INIS)

    Chidambariah, V.; Travis, C.C.; Trabalka, J.R.; Thomas, J.K.

    1992-01-01

    The purpose of this paper is to present a risk-based approach for rapid prioritization of low level liquid radioactive waste underground storage tanks (LLLW USTs) for possible interim corrective measures and/or ultimate closure. The ranking of LLLW USTs is needed to ensure that tanks with the greatest potential for adverse impact on the environment and human health receive top priority for further evaluation and remediation. Wastes from the LLLW USTs at the Oak Ridge National Laboratory (ORNL) were pumped out at the time the tanks were removed from service. The residual liquids and sludge contain a mixture of radionuclides and chemicals. Contaminants of concern that were identified in the liquid phase of the inactive LLLW USTs include, the radionuclides, 9O Sr, 137 Cs and 233 U and the chemicals, carbon tetrachloride, trichloroethene, tetrachloroethene, methyl ethyl ketone, mercury, lead and chromium. The risk-based approach for prioritization of the LLLW USTs is based upon three major criteria: (1) leaking characteristics of the tank; (2) location of the tanks; and (3) toxic potential of the tank contents

  13. Chemical Exposure Assessment Program at Los Alamos National Laboratory: A risk based approach

    International Nuclear Information System (INIS)

    Stephenson, D.J.

    1996-01-01

    The University of California Contract And DOE Order 5480.10 require that Los Alamos National Laboratory (LANL) perform health hazard assessments/inventories of all employee workplaces. In response to this LANL has developed the Chemical Exposure Assessment Program. This program provides a systematic risk-based approach to anticipation, recognition, evaluation and control of chemical workplace exposures. Program implementation focuses resources on exposures with the highest risks for causing adverse health effects. Implementation guidance includes procedures for basic characterization, qualitative risk assessment, quantitative validation, and recommendations and reevaluation. Each component of the program is described. It is shown how a systematic method of assessment improves documentation, retrieval, and use of generated exposure information

  14. General optimization procedure towards the design of a new family of minimal parameter spin-component-scaled double-hybrid density functional theory.

    Science.gov (United States)

    Roch, Loïc M; Baldridge, Kim K

    2017-10-04

    A general optimization procedure towards the development and implementation of a new family of minimal parameter spin-component-scaled double-hybrid (mSD) density functional theory (DFT) is presented. The nature of the proposed exchange-correlation functional establishes a methodology with minimal empiricism. This new family of double-hybrid (DH) density functionals is demonstrated using the PBEPBE functional, illustrating the optimization procedure to the mSD-PBEPBE method, and the performance characteristics shown for a set of non-covalent complexes covering a broad regime of weak interactions. With only two parameters, mSD-PBEPBE and its cost-effective counterpart, RI-mSD-PBEPBE, show a mean absolute error of ca. 0.4 kcal mol -1 averaged over 66 weak interacting systems. Following a successive 2D-grid refinement for a CBS extrapolation of the coefficients, the optimization procedure can be recommended for the design and implementation of a variety of additional DH methods using any of the plethora of currently available functionals.

  15. Game theory and risk-based leveed river system planning with noncooperation

    Science.gov (United States)

    Hui, Rui; Lund, Jay R.; Madani, Kaveh

    2016-01-01

    Optimal risk-based levee designs are usually developed for economic efficiency. However, in river systems with multiple levees, the planning and maintenance of different levees are controlled by different agencies or groups. For example, along many rivers, levees on opposite riverbanks constitute a simple leveed river system with each levee designed and controlled separately. Collaborative planning of the two levees can be economically optimal for the whole system. Independent and self-interested landholders on opposite riversides often are willing to separately determine their individual optimal levee plans, resulting in a less efficient leveed river system from an overall society-wide perspective (the tragedy of commons). We apply game theory to simple leveed river system planning where landholders on each riverside independently determine their optimal risk-based levee plans. Outcomes from noncooperative games are analyzed and compared with the overall economically optimal outcome, which minimizes net flood cost system-wide. The system-wide economically optimal solution generally transfers residual flood risk to the lower-valued side of the river, but is often impractical without compensating for flood risk transfer to improve outcomes for all individuals involved. Such compensation can be determined and implemented with landholders' agreements on collaboration to develop an economically optimal plan. By examining iterative multiple-shot noncooperative games with reversible and irreversible decisions, the costs of myopia for the future in making levee planning decisions show the significance of considering the externalities and evolution path of dynamic water resource problems to improve decision-making.

  16. Structural integrity and its role in nuclear safety recent UK developments in the development of high temperature design procedures

    International Nuclear Information System (INIS)

    Townley, C.H.A.

    1991-01-01

    The structural design rules for the reactors which operate at high temperature are not yet well developed. There is not difficulty in producing the plants which meet the high standards required by nuclear industry. However, there are the issues to be resolved which are associated with the deterioration of components in service, in order to achieve the optimum use of materials and the reduction of capital costs. The safety of plants is not at risk since any deterioration is detected by in-service monitoring, nevertheless, there would be severe economic penalty, if a plant must be retired prematurely because the continuing safety could not be demonstrated. In this paper, a liquid metal fast breeder reactor is taken up as an example, and the topics in which research plays a role for providing improved design rules are identified. Shakedown interaction diagrams, the methods of analysis based on shakedown, inelastic analysis and constitutive equations, creep fatigue damage and thermal shock, thermal striping, welds, defect assessment and so on are discussed. (K.I.)

  17. Risk-based equipment removal guide for on-line maintenance at PSE ampersand G

    International Nuclear Information System (INIS)

    Knoll, A.; Smith, C.; Pollock, J.

    1995-01-01

    On-line maintenance plays an important role in achieving safe and reliable power generation in a nuclear power plant. However, maintenance, if not properly planned and performed, may also be an important contributor to plant risk. Therefore, plant-specific procedures are needed for equipment removal from service to enhance the benefits of on-line maintenance and minimize the risks involved. The problem is to identify and implement the most effective on-line maintenance policy in the form of a proceduralized guide to assure plant safety under various operation and maintenance constraints. This paper presents a methodology to develop plant-specific on-line maintenance strategies and acceptance criteria using a multivariate safety approach based on risk assessment. Based on plant-specific data as modeled in the individual plant evaluation (IPE) and the updated probabilistic safety assessment (PSA), the risk-based methodology is currently being applied to the development of proceduralized equipment removal guides at Hope Creek and Salem units 1 and 2 of Public Service Electric and Gas Company (PSE ampersand G)

  18. A review of mammalian carcinogenicity study design and potential effects of alternate test procedures on the safety evaluation of food ingredients.

    Science.gov (United States)

    Hayes, A W; Dayan, A D; Hall, W C; Kodell, R L; Williams, G M; Waddell, W D; Slesinski, R S; Kruger, C L

    2011-06-01

    Extensive experience in conducting long term cancer bioassays has been gained over the past 50 years of animal testing on drugs, pesticides, industrial chemicals, food additives and consumer products. Testing protocols for the conduct of carcinogenicity studies in rodents have been developed in Guidelines promulgated by regulatory agencies, including the US EPA (Environmental Protection Agency), the US FDA (Food and Drug Administration), the OECD (Organization for Economic Co-operation and Development) for the EU member states and the MAFF (Ministries of Agriculture, Forestries and Fisheries) and MHW (Ministry of Health and Welfare) in Japan. The basis of critical elements of the study design that lead to an accepted identification of the carcinogenic hazard of substances in food and beverages is the focus of this review. The approaches used by entities well-known for carcinogenicity testing and/or guideline development are discussed. Particular focus is placed on comparison of testing programs used by the US National Toxicology Program (NTP) and advocated in OECD guidelines to the testing programs of the European Ramazzini Foundation (ERF), an organization with numerous published carcinogenicity studies. This focus allows for a good comparison of differences in approaches to carcinogenicity testing and allows for a critical consideration of elements important to appropriate carcinogenicity study designs and practices. OECD protocols serve as good standard models for carcinogenicity testing protocol design. Additionally, the detailed design of any protocol should include attention to the rationale for inclusion of particular elements, including the impact of those elements on study interpretations. Appropriate interpretation of study results is dependent on rigorous evaluation of the study design and conduct, including differences from standard practices. Important considerations are differences in the strain of animal used, diet and housing practices, rigorousness

  19. A new modeling procedure for circuit design and performance prediction of evaporator coils using CO2 as refrigerant

    International Nuclear Information System (INIS)

    Larbi Bendaoud, Adlane; Ouzzane, Mohamed; Aidoun, Zine; Galanis, Nicolas

    2010-01-01

    The replacement of environmentally damaging synthetic refrigerants due to their ODP or GWI potential by natural refrigerants such as CO 2 is now up in the research agenda. Moreover, current energy supply concerns make of efficiency another first priority issue to dictate new stringent design criteria for industrial and commercial equipment. Heat exchangers are the most important components in refrigeration systems where they are used as evaporators or condensers and their design and operation have a considerable impact on overall system performance. Hence, it is important to better understand their thermal and hydrodynamic behaviour in order to improve their design and operation. Numerical simulation represents a very efficient tool for achieving this objective. In this paper, a new modeling approach, accounting for the heat transfer the hydrodynamics of the problem and intended to predict the dynamic behaviour of a refrigeration coil under dry conditions is proposed. A related FORTRAN program was developed, allowing the study of a large range of complex refrigerant circuit configurations. The equations describing these aspects are strongly coupled, and their decoupling is reached by using an original method of resolution. Circuits may have several inlets, outlets, bifurcations and feed one or several other tubes inlets. The coil was subdivided into several elementary control volumes and its analysis provided detailed information in X, Y and Z directions. Validation was performed with data from a CO 2 secondary refrigeration loop test bench built in CanmetENERGY Laboratories. These data were predicted satisfactorily over the operating range corresponding to refrigeration applications. Exemplary simulations were then performed on an evaporator typically employed in supermarkets, showing the effect of circuiting on operation and performance. Even though circuiting is common practice in refrigeration this simulation shows that care must be exercised in making the

  20. On developing an optimal design procedure for a bimorph piezoelectric cantilever energy harvester under a predefined volume

    Science.gov (United States)

    Aboulfotoh, Noha; Twiefel, Jens

    2018-06-01

    A typical vibration harvester is tuned to operate at resonance in order to maximize the power output. There are many design parameter sets for tuning the harvester to a specific frequency, even for simple geometries. This work studies the impact of the geometrical parameters on the harvested power while keeping the resonance frequency constant in order to find the combination of the parameters that optimizes the power under a predefined volume. A bimorph piezoelectric cantilever is considered for the study. It consists of two piezoelectric layers and a middle non-piezoelectric layer and holds a tip mass. A theoretical model was derived to obtain the system parameters and the power as functions of the design parameters. Formulas for the optimal load resistance that provide maximum power capability at resonance and anti-resonance frequency were derived. The influence of the width on the power is studied, considering a constant mass ratio (between the tip mass and the mass of the beam). This keeps the resonance frequency constant while changing the width. The influence of the ratio between the thickness of the middle layer and that of the piezoelectric layer is also studied. It is assumed that the total thickness of the cantilever is constant and the middle layer has the same mechanical properties (elasticity and density) as the piezoelectric layer. This keeps the resonance frequency constant while changing the ratio between the thicknesses. Finally, the influence of increasing the free length as well as of increasing the mass ratio on the power is investigated. This is done by first, increasing each of them individually and secondly, by increasing each of them simultaneously while increasing the total thickness under the condition of maintaining a constant resonance frequency. Based on the analysis of these influences, recommendations as to how to maximize the geometrical parameters within the available volume and mass are presented.

  1. Novel MLPA procedure using self-designed probes allows comprehensive analysis for CNVs of the genes involved in Hirschsprung disease

    Directory of Open Access Journals (Sweden)

    Antiñolo Guillermo

    2010-05-01

    Full Text Available Abstract Background Hirschsprung disease is characterized by the absence of intramural ganglion cells in the enteric plexuses, due to a fail during enteric nervous system formation. Hirschsprung has a complex genetic aetiology and mutations in several genes have been related to the disease. There is a clear predominance of missense/nonsense mutations in these genes whereas copy number variations (CNVs have been seldom described, probably due to the limitations of conventional techniques usually employed for mutational analysis. In this study, we have looked for CNVs in some of the genes related to Hirschsprung (EDNRB, GFRA1, NRTN and PHOX2B using the Multiple Ligation-dependent Probe Amplification (MLPA approach. Methods CNVs screening was performed in 208 HSCR patients using a self-designed set of MLPA probes, covering the coding region of those genes. Results A deletion comprising the first 4 exons in GFRA1 gene was detected in 2 sporadic HSCR patients and in silico approaches have shown that the critical translation initiation signal in the mutant gene was abolished. In this study, we have been able to validate the reliability of this technique for CNVs screening in HSCR. Conclusions The implemented MLPA based technique presented here allows CNV analysis of genes involved in HSCR that have not been not previously evaluated. Our results indicate that CNVs could be implicated in the pathogenesis of HSCR, although they seem to be an uncommon molecular cause of HSCR.

  2. Stochastic Watershed Models for Risk Based Decision Making

    Science.gov (United States)

    Vogel, R. M.

    2017-12-01

    Over half a century ago, the Harvard Water Program introduced the field of operational or synthetic hydrology providing stochastic streamflow models (SSMs), which could generate ensembles of synthetic streamflow traces useful for hydrologic risk management. The application of SSMs, based on streamflow observations alone, revolutionized water resources planning activities, yet has fallen out of favor due, in part, to their inability to account for the now nearly ubiquitous anthropogenic influences on streamflow. This commentary advances the modern equivalent of SSMs, termed `stochastic watershed models' (SWMs) useful as input to nearly all modern risk based water resource decision making approaches. SWMs are deterministic watershed models implemented using stochastic meteorological series, model parameters and model errors, to generate ensembles of streamflow traces that represent the variability in possible future streamflows. SWMs combine deterministic watershed models, which are ideally suited to accounting for anthropogenic influences, with recent developments in uncertainty analysis and principles of stochastic simulation

  3. Risk-Based Operation and Maintenance of Offshore Wind Turbines

    DEFF Research Database (Denmark)

    Nielsen, Jannie Sønderkær

    For offshore wind turbines, maintenance costs are substantial due to a large number of component failures. In addition to the repair costs, equipment costs and lost production costs are large due to limited accessibility to the turbines. In order to reduce the costs, preventive methods can be used......, but presently maintenance is not planned using advanced methods taking all available information into account in a consistent manner. Maintenance decisions can be made based on risk-based methods, where the total expected life cycle costs are minimized. Methods have been developed for assessing the corrective...... maintenance costs, and many studies have also been published for preventive maintenance. However, an important part is the modeling of the relationship between maintenance and reliability, which is typically not modeled in a consistent way. Therefore, the methods cannot be used directly for optimal...

  4. Nuclear insurance risk assessment using risk-based methodology

    International Nuclear Information System (INIS)

    Wendland, W.G.

    1992-01-01

    This paper presents American Nuclear Insurers' (ANI's) and Mutual Atomic Energy Liability Underwriters' (MAELU's) process and experience for conducting nuclear insurance risk assessments using a risk-based methodology. The process is primarily qualitative and uses traditional insurance risk assessment methods and an approach developed under the auspices of the American Society of Mechanical Engineers (ASME) in which ANI/MAELU is an active sponsor. This process assists ANI's technical resources in identifying where to look for insurance risk in an industry in which insurance exposure tends to be dynamic and nonactuarial. The process is an evolving one that also seeks to minimize the impact on insureds while maintaining a mutually agreeable risk tolerance

  5. Optimal Risk-Based Inspection Planning for Offshore Wind Turbines

    DEFF Research Database (Denmark)

    Rangel-Ramirez, Jose G.; Sørensen, John Dalsgaard

    2008-01-01

    , inspection and maintenance activities are developed. This paper considers aspects of inspection and maintenance planning of fatigue prone details in jacket and tripod types of wind turbine support structures. Based oil risk-based inspection planning methods used for oil & gas installations, a framework......Wind turbines for electricity production have increased significantly the last years both in production capability and size. This development is expected to continue also in the coining years. The Support structure for offshore wind turbines is typically a steel structure consisting of a tower...... for optimal inspection and maintenance planning of offshore wind turbines is presented. Special aspects for offshore wind turbines are considered: usually the wind loading are dominating the wave loading, wake effects in wind farms are important and the reliability level is typically significantly lower than...

  6. Risk-based prioritization at Hanford Nuclear Site

    International Nuclear Information System (INIS)

    Hesser, W.A.; Mosely, M.T.

    1995-11-01

    This paper describes the method used to incorporate risk-based decision making into the Hanford resource allocation process. This method, the Revised Priority Planning Grid, is used as a tool to calculate benefits and benefit-to-cost ratios for comparison of environmental cleanup activities. The tool is based on Hanford Site objectives. Benefits are determined by estimating the impact on those objectives resulting from funding specific environmental management activities. Impacts are also a function of the weights associated with the objectives. These weights in the Revised Priority Planning Grid reflect US Development of Energy management values, which were obtained through a formal value-elicitation process. With modification to the objectives and weights, the Revised Priority Planning Grid could be used in different situations. By factoring in environmental, safety, and health risk and assigning higher scores to those activities that provide the most benefit, the Revised Priority Planning Grid is a reproducible, scientific way of scoring competing activities or interests

  7. Risk-based inspection--Development of guidelines

    International Nuclear Information System (INIS)

    1993-07-01

    Effective inservice inspection programs can play a significant role in minimizing equipment and structural failures. Most of the current inservice inspection programs for light water reactor (LWR) nuclear power plant components are based on experience and engineers' qualitative judgment. These programs include only an implicit consideration of risk, which combines the probability of failure of a component under its operation and loading conditions and the consequences of such failure, if it occurs. This document recommends appropriate methods for establishing a risk-based inspection program for LWR nuclear power plant components. The process has been built from a general methodology (Volume 1) and has been expanded to involve five major steps: defining the system; evaluating qualitative risk assessment results; using this and information from plant probabilistic risk assessments to perform a quantitative risk analysis; selecting target failure probabilities; and developing an inspection program for components using economic decision analysis and structural reliability assessment methods

  8. Case studies: Risk-based analysis of technical specifications

    International Nuclear Information System (INIS)

    Wagner, D.P.; Minton, L.A.; Gaertner, J.P.

    1987-01-01

    The SOCRATES computer program uses the results of a Probabilistic Risk Assessment (PRA) or a system level risk analysis to calculate changes in risk due to changes in the surveillance test interval and/or the allowed outage time stated in the technical specification. The computer program can accommodate various testing strategies (such as staggered or simultaneous testing) to allow modeling of component testing as it is carried out at a plant. The methods and computer program are an integral part of a larger decision process aimed at determining benefits from technical specification changes. These benefits can include cost savings to the utilities by reducing forced shutdowns with no adverse impacts on risk. Three summaries of case study applications are included to demonstrate the types of results that can be achieved through risk-based evaluation of technical specifications. (orig.)

  9. 12 CFR 652.100 - Audit of the risk-based capital stress test.

    Science.gov (United States)

    2010-01-01

    ... 12 Banks and Banking 6 2010-01-01 2010-01-01 false Audit of the risk-based capital stress test... AGRICULTURAL MORTGAGE CORPORATION FUNDING AND FISCAL AFFAIRS Risk-Based Capital Requirements § 652.100 Audit of the risk-based capital stress test. You must have a qualified, independent external auditor review...

  10. 76 FR 13902 - Fair Credit Reporting Risk-Based Pricing Regulations

    Science.gov (United States)

    2011-03-15

    ... TRADE COMMISSION 16 CFR Parts 640 and 698 RIN R411009 Fair Credit Reporting Risk-Based Pricing... respective risk-based pricing rules to require disclosure of credit scores and information relating to credit scores in risk-based pricing notices if a credit score of the consumer is used in setting the material...

  11. 76 FR 35138 - Federal Agricultural Mortgage Corporation Funding and Fiscal Affairs; Farmer Mac Risk-Based...

    Science.gov (United States)

    2011-06-16

    ... Funding and Fiscal Affairs; Farmer Mac Risk-Based Capital Stress Test, Version 5.0 AGENCY: Farm Credit... credit rating agency) in regulations addressing the Risk-Based Capital Stress Test (RBCST or stress test...) (repealing and replacing Pub. L. 110-234). B. Risk-Based Capital and Credit Ratings Under our rules, Farmer...

  12. Blended Risk Approach in Applying PSA Models to Risk-Based Regulations

    International Nuclear Information System (INIS)

    Dimitrijevic, V. B.; Chapman, J. R.

    1996-01-01

    In this paper, the authors will discuss a modern approach in applying PSA models in risk-based regulation. The Blended Risk Approach is a combination of traditional and probabilistic processes. It is receiving increased attention in different industries in the U. S. and abroad. The use of the deterministic regulations and standards provides a proven and well understood basis on which to assess and communicate the impact of change to plant design and operation. Incorporation of traditional values into risk evaluation is working very well in the blended approach. This approach is very application specific. It includes multiple risk attributes, qualitative risk analysis, and basic deterministic principles. In blending deterministic and probabilistic principles, this approach ensures that the objectives of the traditional defense-in-depth concept are not compromised and the design basis of the plant is explicitly considered. (author)

  13. Design and Effectiveness of a Required Pre-Clinical Simulation-based Curriculum for Fundamental Clinical Skills and Procedures

    Directory of Open Access Journals (Sweden)

    Daryl P. Lofaso

    2011-12-01

    Full Text Available For more than 20 years, medical literature has increasingly documented the need for students to learn, practice and demonstrate competence in basic clinical knowledge and skills. In 2001, the Louisiana State University Health Science Centers (LSUHSC School of Medicine – New Orleans replaced its traditional Introduction in to Clinical Medicine (ICM course with the Science and Practice of Medicine (SPM course. The main component within the SPM course is the Clinical Skills Lab (CSL. The CSL teaches 30 plus skills to all pre-clinical medical students (Years 1 and 2. Since 2002, an annual longitudinal evaluation questionnaire was distributed to all medical students targeting the skills taught in the CSL. Students were asked to rate their self- confidence (Dreyfus and Likert-type and estimate the number of times each clinical skill was performed (clinically/non-clinically. Of the 30 plus skills taught, 8 were selected for further evaluation. An analysis was performed on the eight skills selected to determine the effectiveness of the CSL. All students that participated in the CSL reported a significant improvement in self-confidence and in number performed in the clinically/non-clinically setting when compared to students that did not experience the CSL. For example, without CSL training, the percentage of students reported at the end of their second year self-perceived expertise as “novice” ranged from 21.4% (CPR to 84.7% (GU catheterization. Students who completed the two-years CSL, only 7.8% rated their self-perceived expertise at the end of the second year as “novice” and 18.8% for GU catheterization. The CSL design is not to replace real clinical patient experiences. It's to provide early exposure, medial knowledge, professionalism and opportunity to practice skills in a patient free environment.

  14. A risk based model supporting long term maintenance and reinvestment strategy decision making

    Energy Technology Data Exchange (ETDEWEB)

    Sand, Kjell; Montard, Julien; Tremoen, Tord H.

    2010-02-15

    This Technical Report is a product from the project Risk-Based Distribution System Asset Management (short: RISK DSAM) - Work Package 3 Risk exposure on company/strategic level. In the report a concept for portfolio distribution system asset management is presented. The approach comprises four main steps: 1. Decide the asset base. 2. Divide the asset base into relevant archetypes. 3. Develop or select relevant maintenance and reinvestment strategies for the different archetypes. 4. Estimate risks and costs for each archetype for the relevant strategies. For the different steps guidelines are given and a proposal for implementation of the concept is given in terms of a proposed IT system architecture.To evaluate the feasibility of such a concept, a prototype was developed in by using Visual Basic macros in Excel using real technical data from a small DSO. The experience from using the prototype shows that the concept is realistic. All assets are included and depending of the ambition of the risk analysis both simple simulation models and more advanced might be embedded. Presentations of the concept for a utility engineers have receive positive feedback indicating that the concept is regarded as a practical way to develop risk based asset management strategies for the asset fleet. It should be noted that the concept should be applied on a company strategic level and is thus not designed to be applied for a specific project or asset decisions. For this, more detailed models with area specific information, topology etc. are needed. (Author)

  15. Risk-based security cost-benefit analysis: method and example applications - 59381

    International Nuclear Information System (INIS)

    Wyss, Gregory; Hinton, John; Clem, John; Silva, Consuelo; Duran, Felicia A.

    2012-01-01

    Document available in abstract form only. Full text of publication follows: Decision makers wish to use risk-based cost-benefit analysis to prioritize security investments. However, understanding security risk requires estimating the likelihood of attack, which is extremely uncertain and depends on unquantifiable psychological factors like dissuasion and deterrence. In addition, the most common performance metric for physical security systems, probability of effectiveness at the design basis threat [P(E)], performs poorly in cost-benefit analysis. It is extremely sensitive to small changes in adversary characteristics when the threat is near a systems breaking point, but very insensitive to those changes under other conditions. This makes it difficult to prioritize investment options on the basis of P(E), especially across multiple targets or facilities. To overcome these obstacles, a Sandia National Laboratories Laboratory Directed Research and Development project has developed a risk-based security cost-benefit analysis method. This approach characterizes targets by how difficult it would be for adversaries to exploit each targets vulnerabilities to induce consequences. Adversaries generally have success criteria (e.g., adequate or desired consequences and thresholds for likelihood of success), and choose among alternative strategies that meet these criteria while considering their degree of difficulty in achieving their successful outcome. Investments reduce security risk as they reduce the severity of consequences available and/or increase the difficulty for an adversary to successfully accomplish their most advantageous attack

  16. Human factoring administrative procedures

    International Nuclear Information System (INIS)

    Grider, D.A.; Sturdivant, M.H.

    1991-01-01

    In nonnuclear business, administrative procedures bring to mind such mundane topics as filing correspondence and scheduling vacation time. In the nuclear industry, on the other hand, administrative procedures play a vital role in assuring the safe operation of a facility. For some time now, industry focus has been on improving technical procedures. Significant efforts are under way to produce technical procedure requires that a validated technical, regulatory, and administrative basis be developed and that the technical process be established for each procedure. Producing usable technical procedures requires that procedure presentation be engineered to the same human factors principles used in control room design. The vital safety role of administrative procedures requires that they be just as sound, just a rigorously formulated, and documented as technical procedures. Procedure programs at the Tennessee Valley Authority and at Boston Edison's Pilgrim Station demonstrate that human factors engineering techniques can be applied effectively to technical procedures. With a few modifications, those same techniques can be used to produce more effective administrative procedures. Efforts are under way at the US Department of Energy Nuclear Weapons Complex and at some utilities (Boston Edison, for instance) to apply human factors engineering to administrative procedures: The techniques being adapted include the following

  17. Procedure of a secure design calculation for transmission housings made of aluminium die cast; Ablauf einer sicheren Auslegungsberechnung von Getriebegehaeusen aus Aluminiumdruckguss

    Energy Technology Data Exchange (ETDEWEB)

    Varenkamp, Marco; Schoen, Michael [ZF Friedrichshafen AG, Friedrichshafen (Germany). Fachbereich Berechnung und Simulation

    2011-07-01

    The challenges in life time calculation of transmission housings made of aluminium die cast are on the one hand the complex geometry of the parts and on the other hand the defects in the material such as pores resulting from the die-cast process. The calculations are carried out using the finite element method and the local strain approach. The problem of transferability within the local strain approach is mastered by comparison with component tests and improvement of the transfer functions based on statistical evaluation. The secure design is assured by a safety factor derived from the confidence probability. With the help of an example the procedure will be explained. In addition it will be shown that under uniaxial variable amplitude loading the calculation result can be improved using the damage parameter PJ. (orig.)

  18. Design procedures for the use of composites in strengthening of reinforced concrete structures state-of-the-art report of the RILEM Technical Committee 234-DUC

    CERN Document Server

    Sena-Cruz, José

    2016-01-01

    This book analyses the current knowledge on structural behaviour of RC elements and structures strengthened with composite materials (experimental, analytical and numerical approaches for EBR and NSM), particularly in relation to the above topics, and the comparison of the predictions of the current available codes/recommendations/guidelines with selected experimental results. The book shows possible critical issues (discrepancies, lacunae, relevant parameters, test procedures, etc.) related to current code predictions or to evaluate their reliability, in order to develop more uniform methods and basic rules for design and control of FRP strengthened RC structures. General problems/critical issues are clarified on the basis of the actual experiences, detect discrepancies in existing codes, lacunae in knowledge and, concerning these identified subjects, provide proposals for improvements. The book will help to contribute to promote and consolidate a more qualified and conscious approach towards rehabilitation...

  19. Risk-based methods for reliability investments in electric power distribution systems

    Energy Technology Data Exchange (ETDEWEB)

    Alvehag, Karin

    2011-07-01

    Society relies more and more on a continuous supply of electricity. However, while under investments in reliability lead to an unacceptable number of power interruptions, over investments result in too high costs for society. To give incentives for a socio economically optimal level of reliability, quality regulations have been adopted in many European countries. These quality regulations imply new financial risks for the distribution system operator (DSO) since poor reliability can reduce the allowed revenue for the DSO and compensation may have to be paid to affected customers. This thesis develops a method for evaluating the incentives for reliability investments implied by different quality regulation designs. The method can be used to investigate whether socio economically beneficial projects are also beneficial for a profit-maximizing DSO subject to a particular quality regulation design. To investigate which reinvestment projects are preferable for society and a DSO, risk-based methods are developed. With these methods, the probability of power interruptions and the consequences of these can be simulated. The consequences of interruptions for the DSO will to a large extent depend on the quality regulation. The consequences for the customers, and hence also society, will depend on factors such as the interruption duration and time of occurrence. The proposed risk-based methods consider extreme outage events in the risk assessments by incorporating the impact of severe weather, estimating the full probability distribution of the total reliability cost, and formulating a risk-averse strategy. Results from case studies performed show that quality regulation design has a significant impact on reinvestment project profitability for a DSO. In order to adequately capture the financial risk that the DSO is exposed to, detailed riskbased methods, such as the ones developed in this thesis, are needed. Furthermore, when making investment decisions, a risk

  20. Generalization and formalization of the US EPA procedure for design of treated wastewater aquifer recharge basins: II. Retrofit of Souhil Wadi (Nabeul, Tunisia) pilot plant.

    Science.gov (United States)

    Kallali, Hamadi; Yoshida, Mitsuo; Tarhouni, Jamila; Jedidi, Naceur

    2013-01-01

    The 'Cap Bon' peninsula in Tunisia suffers from intensive tourist activities, high demographic increase and industrial development. As groundwater had been for a long time the main water source, aquifers had been subject to a severe depletion and seawater intrusion. Despite the measures taken prohibiting new drillings and water carrying by the construction of a waterway linking the region to the north-west region of Tunisia, the problem of water shortage persists. Artificial recharge of groundwater with treated wastewater has been decided as a technique to replenish the region aquifers. A pilot plant was constructed in the early 1980s in Souhil Wadi (Nabeul) area. Many experiments have been carried out on this plant and have led to controversial opinions about its performance and its impact on groundwater contamination. This contribution concerns the application of the procedure that we developed from the generalization and the formalization of the United States Environmental Protection Agency (US EPA) methodology for the design of treated wastewater aquifer recharge basins. This upgrading procedure implemented in a spreadsheet, has been used to retrofit the Souhil Wadi facility in order to improve its performance. This method highlighted the importance of the safety factor to estimate wastewater infiltration rate from clean water permeability measurements. It has, also, demonstrated the discordance between the initial design parameters of Souhil Wadi facility and their current status as they have changed with time and the infiltration capacity of the basins has been affected by clogging. Indeed, it has been demonstrated that with the current state of clogging of the basins, the design infiltration rate limited by the most restrictive layer (6.1 cm/hr) corresponds to 22% of the surface infiltration rate reached after a drying period of 10 d, which means that we need more basins to absorb the daily loading rate. The design method leads to the construct ion of five

  1. Quantization Procedures

    International Nuclear Information System (INIS)

    Cabrera, J. A.; Martin, R.

    1976-01-01

    We present in this work a review of the conventional quantization procedure, the proposed by I.E. Segal and a new quantization procedure similar to this one for use in non linear problems. We apply this quantization procedures to different potentials and we obtain the appropriate equations of motion. It is shown that for the linear case the three procedures exposed are equivalent but for the non linear cases we obtain different equations of motion and different energy spectra. (Author) 16 refs

  2. Risk based test interval and maintenance optimisation - Application and uses

    International Nuclear Information System (INIS)

    Sparre, E.

    1999-10-01

    The project is part of an IAEA co-ordinated Research Project (CRP) on 'Development of Methodologies for Optimisation of Surveillance Testing and Maintenance of Safety Related Equipment at NPPs'. The purpose of the project is to investigate the sensitivity of the results obtained when performing risk based optimisation of the technical specifications. Previous projects have shown that complete LPSA models can be created and that these models allow optimisation of technical specifications. However, these optimisations did not include any in depth check of the result sensitivity with regards to methods, model completeness etc. Four different test intervals have been investigated in this study. Aside from an original, nominal, optimisation a set of sensitivity analyses has been performed and the results from these analyses have been compared to the original optimisation. The analyses indicate that the result of an optimisation is rather stable. However, it is not possible to draw any certain conclusions without performing a number of sensitivity analyses. Significant differences in the optimisation result were discovered when analysing an alternative configuration. Also deterministic uncertainties seem to affect the result of an optimisation largely. The sensitivity of failure data uncertainties is important to investigate in detail since the methodology is based on the assumption that the unavailability of a component is dependent on the length of the test interval

  3. Risk Classification and Risk-based Safety and Mission Assurance

    Science.gov (United States)

    Leitner, Jesse A.

    2014-01-01

    Recent activities to revamp and emphasize the need to streamline processes and activities for Class D missions across the agency have led to various interpretations of Class D, including the lumping of a variety of low-cost projects into Class D. Sometimes terms such as Class D minus are used. In this presentation, mission risk classifications will be traced to official requirements and definitions as a measure to ensure that projects and programs align with the guidance and requirements that are commensurate for their defined risk posture. As part of this, the full suite of risk classifications, formal and informal will be defined, followed by an introduction to the new GPR 8705.4 that is currently under review.GPR 8705.4 lays out guidance for the mission success activities performed at the Classes A-D for NPR 7120.5 projects as well as for projects not under NPR 7120.5. Furthermore, the trends in stepping from Class A into higher risk posture classifications will be discussed. The talk will conclude with a discussion about risk-based safety and mission assuranceat GSFC.

  4. Risk-based and maintenance systems for steam turbines

    International Nuclear Information System (INIS)

    Fujiyama, K.; Nagai, S.; Akikuni, Y.; Fujiwara, T.; Furuya, K.; Matsumoto, S.; Takagi, K.; Kawabata, T.

    2003-01-01

    The risk-based maintenance (RBM) system has been developed for steam turbine plants coupled with the quick inspection systems. The RBM system utilizes the field failure and inspection database accumulated over 30 years. The failure modes are determined for each component of steam turbines and the failure scenarios are described as event trees. The probability of failure is expressed in the form of unreliability functions of operation hours or start-up cycles through the cumulative hazard function method. The posterior unreliability is derived from the field data analysis according to the inspection information. Quick inspection can be conducted using air-cooled borescope and heat resistant ultrasonic sensors even if the turbine is not cooled down sufficiently. Another inspection information comes from degradation and damage measurement. The probabilistic life assessment using structural analysis and statistical material properties, the latter is estimated from hardness measurement, replica observation and embrittlement measurement. The risk function is calculated as the sum product of unreliability functions and expected monetary loss as the consequence of failure along event trees. The optimum maintenance plan is determined among simulated scenarios described through component breakdown trees, life cycle event trees and risk functions. Those methods are effective for total condition assessment and economical maintenance for operating plants. (orig.)

  5. Risk-based inspection and maintenance systems for steam turbines

    International Nuclear Information System (INIS)

    Fujiyama, Kazunari; Nagai, Satoshi; Akikuni, Yasunari; Fujiwara, Toshihiro; Furuya, Kenichiro; Matsumoto, Shigeru; Takagi, Kentaro; Kawabata, Taro

    2004-01-01

    The risk-based maintenance (RBM) system has been developed for steam turbine plants coupled with the quick inspection systems. The RBM system utilizes the field failure and inspection database accumulated over 30 years. The failure modes are determined for each component of steam turbines and the failure scenarios are described as event trees. The probability of failure is expressed in the form of unreliability functions of operation hours or start-up cycles through the cumulative hazard function method. The posterior unreliability is derived from the field data analysis according to the inspection information. Quick inspection can be conducted using air-cooled borescope and heat resistant ultrasonic sensors even if the turbine is not cooled down sufficiently. Another inspection information comes from degradation and damage measurement. The probabilistic life assessment using structural analysis and statistical material properties, the latter is estimated from hardness measurement, replica observation and embrittlement measurement. The risk function is calculated as the sum product of unreliability functions and expected monetary loss as the consequence of failure along event trees. The optimum maintenance plan is determined among simulated scenarios described through component breakdown trees, life cycle event trees and risk functions. Those methods are effective for total condition assessment and economical maintenance for operating plants

  6. Forewarning model for water pollution risk based on Bayes theory.

    Science.gov (United States)

    Zhao, Jun; Jin, Juliang; Guo, Qizhong; Chen, Yaqian; Lu, Mengxiong; Tinoco, Luis

    2014-02-01

    In order to reduce the losses by water pollution, forewarning model for water pollution risk based on Bayes theory was studied. This model is built upon risk indexes in complex systems, proceeding from the whole structure and its components. In this study, the principal components analysis is used to screen out index systems. Hydrological model is employed to simulate index value according to the prediction principle. Bayes theory is adopted to obtain posterior distribution by prior distribution with sample information which can make samples' features preferably reflect and represent the totals to some extent. Forewarning level is judged on the maximum probability rule, and then local conditions for proposing management strategies that will have the effect of transforming heavy warnings to a lesser degree. This study takes Taihu Basin as an example. After forewarning model application and vertification for water pollution risk from 2000 to 2009 between the actual and simulated data, forewarning level in 2010 is given as a severe warning, which is well coincide with logistic curve. It is shown that the model is rigorous in theory with flexible method, reasonable in result with simple structure, and it has strong logic superiority and regional adaptability, providing a new way for warning water pollution risk.

  7. Risk Based Inspection of Gas-Cooling Heat Exchanger

    Directory of Open Access Journals (Sweden)

    Dwi Priyanta

    2017-09-01

    Full Text Available On October 2013, Pertamina Hulu Energi Offshore North West Java (PHE – ONWJ platform personnel found 93 leaking tubes locations in the finfan coolers/ gas-cooling heat exchanger. After analysis had been performed, the crack in the tube strongly indicate that stress corrosion cracking was occurred by chloride. Chloride stress corrosion cracking (CLSCC is the cracking occurred by the combined influence of tensile stress and a corrosive environment. CLSCC is the one of the most common reasons why austenitic stainless steel pipework or tube and vessels deteriorate in the chemical processing, petrochemical industries and maritime industries. In this thesis purpose to determine the appropriate inspection planning for two main items (tubes and header box in the gas-cooling heat exchanger using risk based inspection (RBI method. The result, inspection of the tubes must be performed on July 6, 2024 and for the header box inspection must be performed on July 6, 2025. In the end, RBI method can be applicated to gas-cooling heat exchanger. Because, risk on the tubes can be reduced from 4.537 m2/year to 0.453 m2/year. And inspection planning for header box can be reduced from 4.528 m2/year to 0.563 m2/year.

  8. Alternative approaches to risk-based technical specifications

    International Nuclear Information System (INIS)

    Atefi, B.; Gallagher, D.W.; Liner, R.T.; Lofgren, E.V.

    1987-01-01

    Four alternative risk-based approaches to Technical Specifications are identified. These are: a Probabilistic Risk Assessment (PRA) oriented approach; a reliability goal-oriented approach; an approach based on configuration control; a data-oriented approach. Based on preliminary results, the PRA-oriented approach, which has been developed further than the other approaches, seems to offer a logical, quantitative basis for setting Allowed Outage Times (AOTs) and Surveillance Test Intervals (STIs) for some plant components and systems. The most attractive feature of this approach is that it directly links the AOTs and STIs with the risk associated with the operation of the plant. This would focus the plant operator's and the regulatory agency's attention on the most risk-significant components of the plant. A series of practical issues related to the level of detail and content of the plant PRAs, requirements for the review of these PRAs, and monitoring cf the plant's performance by the regulatory agency must be resolved before the approach could be implemented. Future efforts will examine the other three approaches and their practicality before firm conclusions are drawn regarding the viability of any of these approaches

  9. Management of Microbiologically Influenced Corrosion in Risk Based Inspection analysis

    DEFF Research Database (Denmark)

    Skovhus, Torben Lund; Hillier, Elizabeth; Andersen, Erlend S.

    . Microbiologically Influenced Corrosion (MIC) is a degradation mechanism that has received increased attention from corrosion engineers and asset operators in the past decades. In this paper, the most recent models that have been developed in order to assess the impact of MIC on asset integrity will be presented...... and an extensive up-to date literature study. The parameters are discussed and subsequently combined in a novel procedure that allows assessment of MIC in a RBI analysis. The procedure is sub-divided into one screening step and a detailed assessment, which fits the recommended approach to assess risk in a RBI...

  10. A risk-based review of Instrument Air systems at nuclear power plants

    International Nuclear Information System (INIS)

    DeMoss, G.; Lofgren, E.; Rothleder, B.; Villeran, M.; Ruger, C.

    1990-01-01

    The broad objective of this analysis was to provide risk-based information to help focus regulatory actions related to Instrument Air (IA) systems at operating nuclear power plants. We first created an extensive data base of summarized and characterized IA-related events that gave a qualitative indication of the nature and severity of these events. Additionally, this data base was used to calculate the frequencies of certain events, which were used in the risk analysis. The risk analysis consisted of reviewing published PRAs and NRC Accident Sequence Precursor reports for IA-initiated accident sequences, IA interactions with frontline systems, and IA-related risk significant events. Sensitivity calculations were performed when possible. Generically, IA was found to contribute less to total risk than many safety systems; however, specific design weaknesses in safety systems, non-safety systems, and the IA system were found to be significant in risk. 22 refs., 13 figs., 24 tabs

  11. Risk-based Inspection Guide for the Susquehanna Station HPCI system

    International Nuclear Information System (INIS)

    Travis, R.; Higgins, J.; Gunther, W.; Shier, W.

    1992-11-01

    The High Pressure Coolant Injection (HPCI) system has been examined from a risk perspective. A system Risk-based Inspection Guide (S-RIG) has been developed as an aid to HPCI system inspections at the Susquehanna Steam Electric Station (SSES) which is operated by Pennsylvania Power ampersand Light (PP ampersand L). Included in this S-RIG is a discussion of the role of HPCI in mitigating accidents and a presentation of PRA-based failure modes which could prevent proper operation of the system. The S-RIG uses industry operating experience, including plant-specific illustrative examples, to augment the basic PRA failure modes. It is designed to be used as a reference for both routine inspections and the evaluation of the significance of component failures

  12. Update on the EPRI power generation risk-based inservice inspection pilot plant studies

    International Nuclear Information System (INIS)

    Gosselin, S.R.

    1997-01-01

    The scope for ASME Section XI ISI programs is largely based on deterministic results contained in design stress reports. These reports are normally very conservative and may not be an accurate representation of failure potential. Service experience has shown that failures are due to either corrosion or fatigue and typically occur in areas not included in the plant's ISI program. Consequently, nuclear plants are devoting significant resources to inspection programs that provide minimum benefit. As an alternative, significant industry attention has been devoted to the application of risked-based selection criteria in order to determine the scope of inservice inspection (ISI) programs at nuclear power plants. Preliminary EPRI studies indicate that the application of these techniques will allow operating nuclear plants to reduce the examination scope of current ISI programs by as much as 60 to 80%, significantly reduce costs, and continue to maintain high nuclear plant safety standards

  13. High Pressure Coolant Injection (HPCI) System Risk-Based Inspection Guide for Browns Ferry Nuclear Power Station

    International Nuclear Information System (INIS)

    Wong, S.; DiBiasio, A.; Gunther, W.

    1993-09-01

    The High Pressure Coolant Injection (HPCI) system has been examined from a risk perspective. A System Risk-Based Inspection Guide (S-RIG) has been developed as an aid to HPCI system inspections at the Browns Ferry Nuclear Power Plant, Units 1, 2 and 3. The role of. the HPCI system in mitigating accidents is discussed in this S-RIG, along with insights on identified risk-based failure modes which could prevent proper operation of the system. The S-RIG provides a review of industry-wide operating experience, including plant-specific illustrative examples to augment the PRA and operational considerations in identifying a catalogue of basic PRA failure modes for the HPCI system. It is designed to be used as a reference for routine inspections, self-initiated safety system functional inspections (SSFIs), and the evaluation of risk significance of component failures at the nuclear power plant

  14. High Pressure Coolant Injection (HPCI) System Risk-Based Inspection Guide for Browns Ferry Nuclear Power Station

    Energy Technology Data Exchange (ETDEWEB)

    Wong, S.; DiBiasio, A.; Gunther, W. [Brookhaven National Lab., Upton, NY (United States)

    1993-09-01

    The High Pressure Coolant Injection (HPCI) system has been examined from a risk perspective. A System Risk-Based Inspection Guide (S-RIG) has been developed as an aid to HPCI system inspections at the Browns Ferry Nuclear Power Plant, Units 1, 2 and 3. The role of. the HPCI system in mitigating accidents is discussed in this S-RIG, along with insights on identified risk-based failure modes which could prevent proper operation of the system. The S-RIG provides a review of industry-wide operating experience, including plant-specific illustrative examples to augment the PRA and operational considerations in identifying a catalogue of basic PRA failure modes for the HPCI system. It is designed to be used as a reference for routine inspections, self-initiated safety system functional inspections (SSFIs), and the evaluation of risk significance of component failures at the nuclear power plant.

  15. Cernavoda NPP risk - Based test and maintenance planning - Methodology development

    International Nuclear Information System (INIS)

    Georgescu, G.; Popa, P.; Petrescu, A.; Naum, M.; Gutu, M.

    1997-01-01

    The Cernavoda Power Plant starts the commercial operation in November 1996. During operation of the nuclear power plant, several mandatory tests and maintenance are performed on stand-by safety system components to ensure their availability in case of accident. The basic purpose of such activities is the early detection of any failure and degradation, and timely correction of deteriorations. Because of the large number of such activities, emphasis on plant safety and allocation of resources becomes difficult. The probabilistic model and methodology can be effectively used to obtain the risk significance of these activities so that the resources are directed to the most important areas. The proposed Research Contract activity is strongly connected with other safety related areas under development. Since, the Cernavoda Probabilistic Safety Evaluation Level 1 PSA Study (CPSE) was performed and now the study is revised taking into account the as-built information, it is recommended to implement into the model the necessary modeling features to support further PSA application, especially related to Test and Maintenance optimization. Methods need to be developed in order to apply the PSA model including risk information together with other needed information for Test and Maintenance optimization. Also, in parallel with the CPSE study updating, the software interface for the PSA model is under development (Risk Monitor Software class), methods and models needing to be developed for the purpose of using it for qualified monitoring of Test and Maintenance Strategy efficiency. Similar, the Data Collection System need to be appropriate for the purpose of an ongoing implementation of a risk - based Test and Maintenance Strategy. (author). 4 refs, 1 fig

  16. Selecting a risk-based tool to aid in decision making

    Energy Technology Data Exchange (ETDEWEB)

    Bendure, A.O.

    1995-03-01

    Selecting a risk-based tool to aid in decision making is as much of a challenge as properly using the tool once it has been selected. Failure to consider customer and stakeholder requirements and the technical bases and differences in risk-based decision making tools will produce confounding and/or politically unacceptable results when the tool is used. Selecting a risk-based decisionmaking tool must therefore be undertaken with the same, if not greater, rigor than the use of the tool once it is selected. This paper presents a process for selecting a risk-based tool appropriate to a set of prioritization or resource allocation tasks, discusses the results of applying the process to four risk-based decision-making tools, and identifies the ``musts`` for successful selection and implementation of a risk-based tool to aid in decision making.

  17. Risk based decision tool for space exploration missions

    Science.gov (United States)

    Meshkat, Leila; Cornford, Steve; Moran, Terrence

    2003-01-01

    This paper presents an approach and corresponding tool to assess and analyze the risks involved in a mission during the pre-phase A design process. This approach is based on creating a risk template for each subsystem expert involved in the mission design process and defining appropriate interactions between the templates.

  18. A risk-based approach to scheduling audits.

    Science.gov (United States)

    Rönninger, Stephan; Holmes, Malcolm

    2009-01-01

    The manufacture and supply of pharmaceutical products can be a very complex operation. Companies may purchase a wide variety of materials, from active pharmaceutical ingredients to packaging materials, from "in company" suppliers or from third parties. They may also purchase or contract a number of services such as analysis, data management, audit, among others. It is very important that these materials and services are of the requisite quality in order that patient safety and company reputation are adequately protected. Such quality requirements are ongoing throughout the product life cycle. In recent years, assurance of quality has been derived via audit of the supplier or service provider and by using periodic audits, for example, annually or at least once every 5 years. In the past, companies may have used an audit only for what they considered to be "key" materials or services and used testing on receipt, for example, as their quality assurance measure for "less important" supplies. Such approaches changed as a result of pressure from both internal sources and regulators to the time-driven audit for all suppliers and service providers. Companies recognised that eventually they would be responsible for the quality of the supplied product or service and audit, although providing only a "snapshot in time" seemed a convenient way of demonstrating that they were meeting their obligations. Problems, however, still occur with the supplied product or service and will usually be more frequent from certain suppliers. Additionally, some third-party suppliers will no longer accept routine audits from individual companies, as the overall audit load can exceed one external audit per working day. Consequently a different model is needed for assessing supplier quality. This paper presents a risk-based approach to creating an audit plan and for scheduling the frequency and depth of such audits. The approach is based on the principles and process of the Quality Risk Management

  19. Environmental restoration risk-based prioritization work package planning and risk ranking methodology. Revision 2

    International Nuclear Information System (INIS)

    Dail, J.L.; Nanstad, L.D.; White, R.K.

    1995-06-01

    This document presents the risk-based prioritization methodology developed to evaluate and rank Environmental Restoration (ER) work packages at the five US Department of Energy, Oak Ridge Field Office (DOE-ORO) sites [i.e., Oak Ridge K-25 Site (K-25), Portsmouth Gaseous Diffusion Plant (PORTS), Paducah Gaseous Diffusion Plant (PGDP), Oak Ridge National Laboratory (ORNL), and the Oak Ridge Y-12 Plant (Y-12)], the ER Off-site Program, and Central ER. This prioritization methodology was developed to support the increased rigor and formality of work planning in the overall conduct of operations within the DOE-ORO ER Program. Prioritization is conducted as an integral component of the fiscal ER funding cycle to establish program budget priorities. The purpose of the ER risk-based prioritization methodology is to provide ER management with the tools and processes needed to evaluate, compare, prioritize, and justify fiscal budget decisions for a diverse set of remedial action, decontamination and decommissioning, and waste management activities. The methodology provides the ER Program with a framework for (1) organizing information about identified DOE-ORO environmental problems, (2) generating qualitative assessments of the long- and short-term risks posed by DOE-ORO environmental problems, and (3) evaluating the benefits associated with candidate work packages designed to reduce those risks. Prioritization is conducted to rank ER work packages on the basis of the overall value (e.g., risk reduction, stakeholder confidence) each package provides to the ER Program. Application of the methodology yields individual work package ''scores'' and rankings that are used to develop fiscal budget requests. This document presents the technical basis for the decision support tools and process

  20. Development of an active risk-based surveillance strategy for avian influenza in Cuba.

    Science.gov (United States)

    Ferrer, E; Alfonso, P; Ippoliti, C; Abeledo, M; Calistri, P; Blanco, P; Conte, A; Sánchez, B; Fonseca, O; Percedo, M; Pérez, A; Fernández, O; Giovannini, A

    2014-09-01

    The authors designed a risk-based approach to the selection of poultry flocks to be sampled in order to further improve the sensitivity of avian influenza (AI) active surveillance programme in Cuba. The study focused on the western region of Cuba, which harbours nearly 70% of national poultry holdings and comprise several wetlands where migratory waterfowl settle (migratory waterfowl settlements - MWS). The model took into account the potential risk of commercial poultry farms in western Cuba contracting from migratory waterfowl of the orders Anseriformes and Charadriiformes through dispersion for pasturing of migratory birds around the MWS. We computed spatial risk index by geographical analysis with Python scripts in ESRI(®) ArcGIS 10 on data projected in the reference system NAD 1927-UTM17. Farms located closer to MWS had the highest values for the risk indicator pj and in total 31 farms were chosen for targeted surveillance during the risk period. The authors proposed to start active surveillance in the study area 3 weeks after the onset of Anseriformes migration, with additional sampling repeated twice in the same selected poultry farms at 15 days interval (Comin et al., 2012; EFSA, 2008) to cover the whole migration season. In this way, the antibody detectability would be favoured in case of either a posterior AI introduction or enhancement of a previous seroprevalence under the sensitivity level. The model identified the areas with higher risk for AIV introduction from MW, aiming at selecting poultry premises for the application of risk-based surveillance. Given the infrequency of HPAI introduction into domestic poultry populations and the relative paucity of occurrences of LPAI epidemics, the evaluation of the effectiveness of this approach would require its application for several migration seasons to allow the collection of sufficient reliable data. Copyright © 2014 The Authors. Published by Elsevier B.V. All rights reserved.

  1. Risk analysis of heat recovery steam generator with semi quantitative risk based inspection API 581

    Science.gov (United States)

    Prayogo, Galang Sandy; Haryadi, Gunawan Dwi; Ismail, Rifky; Kim, Seon Jin

    2016-04-01

    Corrosion is a major problem that most often occurs in the power plant. Heat recovery steam generator (HRSG) is an equipment that has a high risk to the power plant. The impact of corrosion damage causing HRSG power plant stops operating. Furthermore, it could be threaten the safety of employees. The Risk Based Inspection (RBI) guidelines by the American Petroleum Institute (API) 58 has been used to risk analysis in the HRSG 1. By using this methodology, the risk that caused by unexpected failure as a function of the probability and consequence of failure can be estimated. This paper presented a case study relating to the risk analysis in the HRSG, starting with a summary of the basic principles and procedures of risk assessment and applying corrosion RBI for process industries. The risk level of each HRSG equipment were analyzed: HP superheater has a medium high risk (4C), HP evaporator has a medium-high risk (4C), and the HP economizer has a medium risk (3C). The results of the risk assessment using semi-quantitative method of standard API 581 based on the existing equipment at medium risk. In the fact, there is no critical problem in the equipment components. Damage mechanisms were prominent throughout the equipment is thinning mechanism. The evaluation of the risk approach was done with the aim of reducing risk by optimizing the risk assessment activities.

  2. Risk analysis of heat recovery steam generator with semi quantitative risk based inspection API 581

    International Nuclear Information System (INIS)

    Prayogo, Galang Sandy; Haryadi, Gunawan Dwi; Ismail, Rifky; Kim, Seon Jin

    2016-01-01

    Corrosion is a major problem that most often occurs in the power plant. Heat recovery steam generator (HRSG) is an equipment that has a high risk to the power plant. The impact of corrosion damage causing HRSG power plant stops operating. Furthermore, it could be threaten the safety of employees. The Risk Based Inspection (RBI) guidelines by the American Petroleum Institute (API) 58 has been used to risk analysis in the HRSG 1. By using this methodology, the risk that caused by unexpected failure as a function of the probability and consequence of failure can be estimated. This paper presented a case study relating to the risk analysis in the HRSG, starting with a summary of the basic principles and procedures of risk assessment and applying corrosion RBI for process industries. The risk level of each HRSG equipment were analyzed: HP superheater has a medium high risk (4C), HP evaporator has a medium-high risk (4C), and the HP economizer has a medium risk (3C). The results of the risk assessment using semi-quantitative method of standard API 581 based on the existing equipment at medium risk. In the fact, there is no critical problem in the equipment components. Damage mechanisms were prominent throughout the equipment is thinning mechanism. The evaluation of the risk approach was done with the aim of reducing risk by optimizing the risk assessment activities.

  3. Risk analysis of heat recovery steam generator with semi quantitative risk based inspection API 581

    Energy Technology Data Exchange (ETDEWEB)

    Prayogo, Galang Sandy, E-mail: gasandylang@live.com; Haryadi, Gunawan Dwi; Ismail, Rifky [Department of Mechanical Engineering, Diponegoro University, Semarang (Indonesia); Kim, Seon Jin [Department of Mechanical & Automotive Engineering of Pukyong National University (Korea, Republic of)

    2016-04-19

    Corrosion is a major problem that most often occurs in the power plant. Heat recovery steam generator (HRSG) is an equipment that has a high risk to the power plant. The impact of corrosion damage causing HRSG power plant stops operating. Furthermore, it could be threaten the safety of employees. The Risk Based Inspection (RBI) guidelines by the American Petroleum Institute (API) 58 has been used to risk analysis in the HRSG 1. By using this methodology, the risk that caused by unexpected failure as a function of the probability and consequence of failure can be estimated. This paper presented a case study relating to the risk analysis in the HRSG, starting with a summary of the basic principles and procedures of risk assessment and applying corrosion RBI for process industries. The risk level of each HRSG equipment were analyzed: HP superheater has a medium high risk (4C), HP evaporator has a medium-high risk (4C), and the HP economizer has a medium risk (3C). The results of the risk assessment using semi-quantitative method of standard API 581 based on the existing equipment at medium risk. In the fact, there is no critical problem in the equipment components. Damage mechanisms were prominent throughout the equipment is thinning mechanism. The evaluation of the risk approach was done with the aim of reducing risk by optimizing the risk assessment activities.

  4. Risk-Based Decision Support of Water Resource Management Alternatives

    National Research Council Canada - National Science Library

    West, Paul D; Trainor, Timothy E

    2006-01-01

    .... A model is presented that combines a new risk assessment methodology with traditional decision-making tools to enable systems engineers to capture the full spectrum of operational risks during the design process...

  5. SADA: Ecological Risk Based Decision Support System for Selective Remediation

    Science.gov (United States)

    Spatial Analysis and Decision Assistance (SADA) is freeware that implements terrestrial ecological risk assessment and yields a selective remediation design using its integral geographical information system, based on ecological and risk assessment inputs. Selective remediation ...

  6. Fusion reactor passive safety and ignitor risk-based regulation

    International Nuclear Information System (INIS)

    Zucchetti, M.

    1995-01-01

    Passive design features are more reliable than operator action of successful operation of active safety systems. Passive safety has usually been adopted for fission. The achievement of an inventory-based passive safety is difficult if the fusion reactor uses neutronic reactions. Ignitor is a high-magnetic field tokamak designed to study the physics of ignited plasmas. The safety goal for Ignitor is classification as a mobility-based passively safe machine

  7. Implementation of transparency and accountability under risk-based audit of electronic procurement system

    Directory of Open Access Journals (Sweden)

    M.S. Pysmenna

    2017-08-01

    Full Text Available The research analyzes the international norms and practice of realization of the purpose of state audit authorities. It is established that the activities of the state audit are aimed at improving the lives of citizens, and for this purpose the control authority, through the implementation of the principles, should achieve the goals of strengthening the principles of accountability, transparency and integrity in government and public institutions, demonstrating constant importance for citizens, parliament and other stakeholders, maintaining integrity. The study of domestic legislation on state audit in relation to compliance with international norms is conducted; the gaps and inconsistencies regarding compliance with the basic principles of transparency and accountability that ensure the purpose of the control authority activities are identified. It is determined that in order to formulate reports on the results of public procurement audits for informing the public, it is necessary to improve and apply a broader methodology of risk-based audit. The article investigates the preconditions and identifies the risks of the electronic procurement system, provides their characteristics and identifies the areas, which are negatively affected by the risks. The author identifies the information components and management functions that cannot be performed qualitatively because of the existence of risks and threats; the author also specifies the procedures for internal control over the process of administration of public procurement, and if the procedures are faced with failure, it increases the identified risks. It is proved that the proposed method of identification and evaluation of the risks of the electronic public procurement system can be used not only as a verification tool but also as the basis for compilation of reports due to the grouping of violations of the negative consequences of risks for the functioning of the system. This will ensure the

  8. An Integrated Experimental-Modelling Procedure Applied to the Design of a Field Scale Goethite Nanoparticle Injection for the Remediation of Contaminated Sites

    Science.gov (United States)

    Bianco, C.; Tosco, T.; Sethi, R.

    2017-12-01

    Nanoremediation is a promising in-situ technology for the reclamation of contaminated aquifers. It consists in the subsurface injection of a reactive colloidal suspension for the in-situ treatment of pollutants. The overall success of this technology at the field scale is strictly related to the achievement of an effective and efficient emplacement of the nanoparticles (NP) inside the contaminated area. Mathematical models can be used to support the design of nanotechnology-based remediation by effectively assessing the expected NP mobility at the field scale. Several analytical and numerical tools have been developed in recent years to model the transport of NPs in simplified geometry and boundary conditions. The numerical tool MNMs was developed by the authors of this work to simulate colloidal transport in 1D Cartesian and radial coordinates. A new modelling tool, MNM3D (Micro and Nanoparticle transport Model in 3D geometries), was also proposed for the simulation of injection and transport of NP suspensions in generic complex scenarios. MNM3D accounts for the simultaneous dependency of NP transport on water ionic strength and velocity. The software was developed to predict the NP mobility at different stages of a nanoremediation application, from the design stage to the prediction of the long-term fate after injection. In this work an integrated experimental-modelling procedure is applied to support the design of a field scale injection of goethite NPs carried out in the framework of the H2020 European project Reground. Column tests are performed at different injection flowrates using natural sand collected at the contaminated site as porous medium. The tests are interpreted using MNMs to characterize the NP mobility and derive the constitutive equations describing the suspension behavior in the natural porous medium. MNM3D is then used to predict NP behavior during the field scale injection and to assess the long-term mobility of the injected slurry. Finally

  9. Design

    DEFF Research Database (Denmark)

    Volf, Mette

    This publication is unique in its demystification and operationalization of the complex and elusive nature of the design process. The publication portrays the designer’s daily work and the creative process, which the designer is a part of. Apart from displaying the designer’s work methods...... and design parameters, the publication shows examples from renowned Danish design firms. Through these examples the reader gets an insight into the designer’s reality....

  10. Risk-based microbiological criteria for Campylobacter in broiler meat: A comparison of two approaches

    DEFF Research Database (Denmark)

    Nauta, Maarten; Andersen, Jens Kirk; Tuominen, Pirkko

    2015-01-01

    Risk-based microbiological criteria can offer a tool to control Campylobacter in the broiler meat production chain. Recently two approaches have been applied to derive such criteria and to analyse their potential impact in terms of human health risk reduction: the risk-based version...

  11. The role of hazard- and risk-based approaches in ensuring food safety

    DEFF Research Database (Denmark)

    Barlow, Susan M.; Boobis, Alan R.; Bridges, Jim

    2015-01-01

    action. Risk-based approaches allow consideration of exposure in assessing whether there may be unacceptable risks to health. Scope and approach The advantages and disadvantages of hazard- and risk-based approaches for ensuring the safety of food chemicals, allergens, ingredients and microorganisms were...

  12. 12 CFR 955.6 - Risk-based capital requirement for acquired member assets.

    Science.gov (United States)

    2010-01-01

    ... losses as support for the credit risk of all AMA estimated by the Bank to represent a credit risk that is...) Recalculation of credit enhancement. For risk-based capital purposes, each Bank shall recalculate the estimated... 12 Banks and Banking 7 2010-01-01 2010-01-01 false Risk-based capital requirement for acquired...

  13. 12 CFR 567.6 - Risk-based capital credit risk-weight categories.

    Science.gov (United States)

    2010-01-01

    ... 12 Banks and Banking 5 2010-01-01 2010-01-01 false Risk-based capital credit risk-weight... CAPITAL Regulatory Capital Requirements § 567.6 Risk-based capital credit risk-weight categories. (a) Risk...)(2) of this section), plus risk-weighted recourse obligations, direct credit substitutes, and certain...

  14. PSA requirements for use in the safety management. Risk based indicators and the configurational control

    International Nuclear Information System (INIS)

    Szikszai, T.

    1994-01-01

    The purpose of this document is to show the role of the risk based indicators- namely the core damage frequency (CDFI), the core damage probability indicators (CDPI) and the importance of the equipment together- in the risk based configuration control. 1 fig

  15. A risk-based model for maintenance decision support of civil structures using RAMS

    NARCIS (Netherlands)

    Viana Da Rocha, T. C.; Stipanovic, I.; Hartmann, A.; Bakker, J.

    2017-01-01

    As a cornerstone of transportation asset management, risk-based approaches have been used to support maintenance decisions of civil structures. However, ambiguous and subjective risk criteria and inconsistency on the use of risk-based approaches can lead to a fuzzy understanding of the risks

  16. 12 CFR 956.4 - Risk-based capital requirement for investments.

    Science.gov (United States)

    2010-01-01

    ... 12 Banks and Banking 7 2010-01-01 2010-01-01 false Risk-based capital requirement for investments... OFF-BALANCE SHEET ITEMS FEDERAL HOME LOAN BANK INVESTMENTS § 956.4 Risk-based capital requirement for investments. Each Bank shall hold retained earnings plus general allowance for losses as support for the...

  17. Key outcomes from risk based assessment of pressure equipment in refineries

    International Nuclear Information System (INIS)

    Firth, D.; Lichti, K.; Hill, T.; Thomas, C.; Widrig, J.; Simmonds, G.; Karstensen, A.

    2012-01-01

    Risk based assessment (RBA) has become the best industry practice for management of pressure equipment reliability. Application of RBA programs significantly reduces risk and gives opportunity to optimize inspection programs and produce long term financial benefits. Quest Integrity Group have implemented risk based inspection programs n a variety of industries including ammonia, methanol, geothermal power, :combined cycle power, gas turbines, gas production facilities and refineries. This paper outlines the semi quantitative RBA procedures that have been followed and lists some of the specific technical outcomes. Advanced inspection and life assessment methods used in support of RBI in refineries ire discussed. Piping in refineries is a key risk issue and it is not uncommon for piping failures to result in major incidents. Specific inspection programs are available to monitor differing damage processes such as flow assisted corrosion, hydrogen damage and corrosion under insulation. During assessment it s often found that numerous pipes have never been inspected especially underground smaller diameter pipes which are frequently considered to be un-piggable using conventional technologies and difficult to inspect. Advanced high accuracy flexible miniaturized ultrasonic intelligent pigging combined with fitness for service assessment such as Invista TM is recommended for inspection of critical pipelines which previously have been un-piggable. The processing of crude oil from a range of sources can result in significant variations in the levels of contaminants such as chlorides and sulfides. Major failures have occurred as a result of very rapid increases in corrosion rates in hydrotreating processes due to rapid changes in chemistry. The outcome of the assessment of plants that have potentially high and variable levels of contaminants often results in a review the process chemistry, how it is monitored and development of a detailed corrosion monitoring program. Fired

  18. Application of probabilistic risk based optimization approaches in environmental restoration

    International Nuclear Information System (INIS)

    Goldammer, W.

    1995-01-01

    The paper presents a general approach to site-specific risk assessments and optimization procedures. In order to account for uncertainties in the assessment of the current situation and future developments, optimization parameters are treated as probabilistic distributions. The assessments are performed within the framework of a cost-benefit analysis. Radiation hazards and conventional risks are treated within an integrated approach. Special consideration is given to consequences of low probability events such as, earthquakes or major floods. Risks and financial costs are combined to an overall figure of detriment allowing one to distinguish between benefits of available reclamation options. The probabilistic analysis uses a Monte Carlo simulation technique. The paper demonstrates the applicability of this approach in aiding the reclamation planning using an example from the German reclamation program for uranium mining and milling sites

  19. Hanford Mission Plan risk-based prioritization methodologies

    International Nuclear Information System (INIS)

    Hesser, W.A.; Madden, M.S.; Pyron, N.M.; Butcher, J.L.

    1994-08-01

    Sites across the US Department (DOE) complex recognize the critical need for a systematic method for prioritizing among their work scope activities. Here at the Hanford Site, Pacific Northwest Laboratory and Westinghouse Hanford Company (WHC) conducted preliminary research into techniques to meet this need and assist managers in making financial resource allocation decisions. This research is a subtask of the risk management task of the Hanford Mission Plan as described in the WHC Integrated Planning Work Breakdown Structure 1.8.2 Fiscal Year 1994 Work Plan. The research team investigated prioritization techniques used at other DOE sites and compared them with the Priority Planning Grid (PPG), a tool used at Hanford. The authors concluded that the PPG could be used for prioritization of resource allocation, but it needed to be revised to better reflect the Site's priorities and objectives. The revised PPG was tested with three Hanford programs, the PPG was modified, and updated procedures were prepared

  20. Automated analysis of security requirements through risk-based argumentation

    NARCIS (Netherlands)

    Yu, Yijun; Nunes Leal Franqueira, V.; Tun, Thein Tan; Wieringa, Roelf J.; Nuseibeh, Bashar

    2015-01-01

    Computer-based systems are increasingly being exposed to evolving security threats, which often reveal new vulnerabilities. A formal analysis of the evolving threats is difficult due to a number of practical considerations such as incomplete knowledge about the design, limited information about

  1. A Risk-Based Interval Two-Stage Programming Model for Agricultural System Management under Uncertainty

    Directory of Open Access Journals (Sweden)

    Ye Xu

    2016-01-01

    Full Text Available Nonpoint source (NPS pollution caused by agricultural activities is main reason that water quality in watershed becomes worse, even leading to deterioration. Moreover, pollution control is accompanied with revenue’s fall for agricultural system. How to design and generate a cost-effective and environmentally friendly agricultural production pattern is a critical issue for local managers. In this study, a risk-based interval two-stage programming model (RBITSP was developed. Compared to general ITSP model, significant contribution made by RBITSP model was that it emphasized importance of financial risk under various probabilistic levels, rather than only being concentrated on expected economic benefit, where risk is expressed as the probability of not meeting target profit under each individual scenario realization. This way effectively avoided solutions’ inaccuracy caused by traditional expected objective function and generated a variety of solutions through adjusting weight coefficients, which reflected trade-off between system economy and reliability. A case study of agricultural production management with the Tai Lake watershed was used to demonstrate superiority of proposed model. Obtained results could be a base for designing land-structure adjustment patterns and farmland retirement schemes and realizing balance of system benefit, system-failure risk, and water-body protection.

  2. ASTM F739 method for testing the permeation resistance of protective clothing materials: critical analysis with proposed changes in procedure and test-cell design.

    Science.gov (United States)

    Anna, D H; Zellers, E T; Sulewski, R

    1998-08-01

    ASTM (American Society for Testing and Materials) Method F739-96 specifies a test-cell design and procedures for measuring the permeation resistance of chemical protective clothing. Among the specifications are open-loop collection stream flow rates of 0.050 to 0.150 L/min for a gaseous medium. At elevated temperatures the test must be maintained within 1 degree C of the set point. This article presents a critical analysis of the effect of the collection stream flow rate on the measured permeation rate and on the temperature uniformity within the test cell. Permeation tests were conducted on four polymeric glove materials with 44 solvents at 25 degrees C. Flow rates > 0.5 L/min were necessary to obtain accurate steady-state permeation rate (SSPR) values in 25 percent of the tests. At the lower flow rates the true SSPR typically was underestimated by a factor of two or less, but errors of up to 33-fold were observed. No clear relationship could be established between the need for a higher collection stream flow rate and either the vapor pressure or the permeation rate of the solvent, but test results suggest that poor mixing within the collection chamber was a contributing factor. Temperature gradients between the challenge and collection chambers and between the bottom and the top of the collection chamber increased with the water-bath temperature and the collection stream flow rate. Use of a test cell modified to permit deeper submersion reduced the gradients to < or = 0.5 degrees C. It is recommended that all SSPR measurements include verification of the adequacy of the collection stream flow rate. For testing at nonambient temperatures, the modified test cell described here could be used to ensure temperature uniformity throughout the cell.

  3. Nuclear materials management procedures

    International Nuclear Information System (INIS)

    Veevers, K.; Silver, J.M.; Quealy, K.J.; Steege, E. van der.

    1987-10-01

    This manual describes the procedures for the management of nuclear materials and associated materials at the Lucas Heights Research Laboratories. The procedures are designed to comply with Australia's nuclear non-proliferation obligations to the International Atomic Energy Agency (IAEA), bilateral agreements with other countries and ANSTO's responsibilities under the Nuclear Non-Proliferation (Safeguards) Act, 1987. The manual replaces those issued by the Australian Atomic Energy Commission in 1959, 1960 and 1969

  4. FlySec: a risk-based airport security management system based on security as a service concept

    Science.gov (United States)

    Kyriazanos, Dimitris M.; Segou, Olga E.; Zalonis, Andreas; Thomopoulos, Stelios C. A.

    2016-05-01

    Complementing the ACI/IATA efforts, the FLYSEC European H2020 Research and Innovation project (http://www.fly-sec.eu/) aims to develop and demonstrate an innovative, integrated and end-to-end airport security process for passengers, enabling a guided and streamlined procedure from the landside to airside and into the boarding gates, and offering for an operationally validated innovative concept for end-to-end aviation security. FLYSEC ambition turns through a well-structured work plan into: (i) innovative processes facilitating risk-based screening; (ii) deployment and integration of new technologies and repurposing existing solutions towards a risk-based Security paradigm shift; (iii) improvement of passenger facilitation and customer service, bringing security as a real service in the airport of tomorrow;(iv) achievement of measurable throughput improvement and a whole new level of Quality of Service; and (v) validation of the results through advanced "in-vitro" simulation and "in-vivo" pilots. On the technical side, FLYSEC achieves its ambitious goals by integrating new technologies on video surveillance, intelligent remote image processing and biometrics combined with big data analysis, open-source intelligence and crowdsourcing. Repurposing existing technologies is also in the FLYSEC objectives, such as mobile application technologies for improved passenger experience and positive boarding applications (i.e. services to facilitate boarding and landside/airside way finding) as well as RFID for carry-on luggage tracking and quick unattended luggage handling. In this paper, the authors will describe the risk based airport security management system which powers FLYSEC intelligence and serves as the backend on top of which FLYSEC's front end technologies reside for security services management, behaviour and risk analysis.

  5. Design of a Risk based Control System for Toxoplasma gondii in a pork supply chain

    NARCIS (Netherlands)

    Heres, L.; Swanenburg, M.; Koeijer, de A.A.; Boender, G.J.; Oorburg, D.; Urlings, B.; Wisselink, H.J.

    2015-01-01

    Toxoplasma gondii is recognized as one of the major foodborne pathogens. The European Food Safety Authority (EFSA) concluded that T. gondii is one of the public health hazards in pigs to be covered within a modern meat inspection and advised to include serological testing of pigs and audits of pig

  6. A risk-based approach to designing effective security force training exercises

    International Nuclear Information System (INIS)

    Bott, T.F.; Eisenhawer, S.W.

    2002-01-01

    The effectiveness of a security force in protecting a nuclear facility is often evaluated using training exercises that pit a group of simulated attackers against a security team. In the situation studied here, a security force was regularly tested by a regulatory body with the responsibility for security oversight. It was observed that the regulators were continually imposing more challenging security scenarios by assigning increasingly sophisticated facility knowledge to the attackers. Not surprisingly, the security forces' assessed effectiveness decreased until eventually they were unable to successfully resist the attacks. Security managers maintained that the knowledge attributed to the attackers was becoming increasingly unrealistic and feared they would be forced to concentrate resources on unrealistic scenarios at the expense of more credible threats.

  7. Soils Project Risk-Based Corrective Action Evaluation Process with ROTC 1 and ROTC 2, Revision 0

    Energy Technology Data Exchange (ETDEWEB)

    Matthews, Patrick; Sloop, Christina

    2012-04-01

    This document formally defines and clarifies the NDEP-approved process the NNSA/NSO Soils Activity uses to fulfill the requirements of the FFACO and state regulations. This process is used to establish FALs in accordance with the risk-based corrective action (RBCA) process stipulated in Chapter 445 of the Nevada Administrative Code (NAC) as described in the ASTM International (ASTM) Method E1739-95 (NAC, 2008; ASTM, 1995). It is designed to provide a set of consistent standards for chemical and radiological corrective actions.

  8. Use of expert judgment in the development and evaluation of risk-based inservice testing strategies for pumps and valves

    Energy Technology Data Exchange (ETDEWEB)

    McAllister, W.J.; Perdue, R.K.; Balkey, K.R.; Closky, N.B. [and others

    1996-12-01

    This paper describes a rigorous approach for quantitatively evaluating inservice testing effectiveness that evolved from two pilot plant studies. These studies prototyped methodologies for designing and selecting inservice testing (IST) strategies in a manner structured to insure that the targeted components will perform their required safety functions while minimizing life cycle inservice testing costs. The paper concentrates on the use of expert judgment in developing test effectiveness measures that move risk-based methods beyond ranking to optimization of plant IST programs. Selected results for check valves and pumps are shown to illustrate the practical significance of the approach.

  9. Use of expert judgment in the development and evaluation of risk-based inservice testing strategies for pumps and valves

    International Nuclear Information System (INIS)

    McAllister, W.J.; Perdue, R.K.; Balkey, K.R.; Closky, N.B.

    1996-01-01

    This paper describes a rigorous approach for quantitatively evaluating inservice testing effectiveness that evolved from two pilot plant studies. These studies prototyped methodologies for designing and selecting inservice testing (IST) strategies in a manner structured to insure that the targeted components will perform their required safety functions while minimizing life cycle inservice testing costs. The paper concentrates on the use of expert judgment in developing test effectiveness measures that move risk-based methods beyond ranking to optimization of plant IST programs. Selected results for check valves and pumps are shown to illustrate the practical significance of the approach

  10. Usable Multi-factor Authentication and Risk-based Authorization

    Science.gov (United States)

    2015-06-01

    platforms (Apple iOS and Google Android), a hybrid application development platform was used so that must of the user interaction and security...instantiated as an HTML mockup, including risk communication and anti- phishing features. We conducted heuristic evaluation of this design with two... phishing attacks. At enrollment time, users select an image to be displayed there. If the image is not displayed, the login screen may be fake and users

  11. GASVOL 18'' gas pipeline - risk based inspection study

    Energy Technology Data Exchange (ETDEWEB)

    Bjoernoey, Ola H.; Etterdal, Birger A. [Det Norske Veritas (DNV), Oslo (Norway); Guarize, Rosimar; Oliveira, Luiz F.S. [Det Norske Veritas (DNV) (Brazil); Faertes, Denise; Dias, Ricardo [TRANSPETRO - PETROBRAS Transporte S.A., Rio de Janeiro, RJ (Brazil)

    2003-07-01

    This paper describes a risk based approach and inspection planning as part of the Pipeline Integrity Management (PIM) system for the 95.5 km long 18'' GASVOL gas pipeline in the South eastern region of Brazil transporting circa 5 000 000 m3 dry gas per day. Pipeline systems can be subject to several degradation mechanisms and inspection and monitoring are used to ensure system integrity. Modern pipeline regulations and codes are normally based on a core safety or risk philosophy. The detailed design requirements presented in design codes are practical interpretations established so as to fulfill these core objectives. A given pipeline, designed, constructed and installed according to a pipeline code is therefore the realization of a structure, which, along its whole length, meets the applicable safety objectives of that code. The main objective of Pipeline Integrity Management (PIM) is to control and document the integrity of the pipeline for its whole service life, and to do this in a cost-effective manner. DNV has a specific approach to RBI planning, starting with an initial qualitative assessment where pipelines and damage type are ranked according to risk and potential risk reduction by an inspection and then carried forward to a quantitative detailed assessment where the level of complexity and accuracy can vary based on availability of information and owner needs. Detailed assessment requires significant effort in data gathering. The findings are dependent upon the accuracy of the inspection data, and on DNV's interpretation of the pipeline reference system and simplifications in the inspection data reported. The following specific failure mechanisms were investigated: internal corrosion, external corrosion, third party interference, landslides and black powder. RBI planning, in general words, is a 'living process'. In order to optimize future inspections, it is essential that the analyses utilize the most recent information regarding

  12. MO-E-9A-01: Risk Based Quality Management: TG100 In Action

    Energy Technology Data Exchange (ETDEWEB)

    Huq, M [University of Pittsburgh Medical Center, Pittsburgh, PA (United States); Palta, J [Virginia Commonwealth University, Richmond, VA (United States); Dunscombe, P [Tom Baker Cancer Centre, Calgary, AB (Canada); Thomadsen, B [University of Wisconsin, Madison, WI (United States)

    2014-06-15

    One of the goals of quality management in radiation therapy is to gain high confidence that patients will receive the prescribed treatment correctly. To accomplish these goals professional societies such as the American Association of Physicists in Medicine (AAPM) has published many quality assurance (QA), quality control (QC), and quality management (QM) guidance documents. In general, the recommendations provided in these documents have emphasized on performing device-specific QA at the expense of process flow and protection of the patient against catastrophic errors. Analyses of radiation therapy incidents find that they are most often caused by flaws in the overall therapy process, from initial consult through final treatment, than by isolated hardware or computer failures detectable by traditional physics QA. This challenge is shared by many intrinsically hazardous industries. Risk assessment tools and analysis techniques have been developed to define, identify, and eliminate known and/or potential failures, problems, or errors, from a system, process and/or service before they reach the customer. These include, but are not limited to, process mapping, failure modes and effects analysis (FMEA), fault tree analysis (FTA), and establishment of a quality management program that best avoids the faults and risks that have been identified in the overall process. These tools can be easily adapted to radiation therapy practices because of their simplicity and effectiveness to provide efficient ways to enhance the safety and quality of treatment processes. Task group 100 (TG100) of AAPM has developed a risk-based quality management program that uses these tools. This session will be devoted to a discussion of these tools and how these tools can be used in a given radiotherapy clinic to develop a risk based QM program. Learning Objectives: Learn how to design a process map for a radiotherapy process. Learn how to perform a FMEA analysis for a given process. Learn what

  13. MO-E-9A-01: Risk Based Quality Management: TG100 In Action

    International Nuclear Information System (INIS)

    Huq, M; Palta, J; Dunscombe, P; Thomadsen, B

    2014-01-01

    One of the goals of quality management in radiation therapy is to gain high confidence that patients will receive the prescribed treatment correctly. To accomplish these goals professional societies such as the American Association of Physicists in Medicine (AAPM) has published many quality assurance (QA), quality control (QC), and quality management (QM) guidance documents. In general, the recommendations provided in these documents have emphasized on performing device-specific QA at the expense of process flow and protection of the patient against catastrophic errors. Analyses of radiation therapy incidents find that they are most often caused by flaws in the overall therapy process, from initial consult through final treatment, than by isolated hardware or computer failures detectable by traditional physics QA. This challenge is shared by many intrinsically hazardous industries. Risk assessment tools and analysis techniques have been developed to define, identify, and eliminate known and/or potential failures, problems, or errors, from a system, process and/or service before they reach the customer. These include, but are not limited to, process mapping, failure modes and effects analysis (FMEA), fault tree analysis (FTA), and establishment of a quality management program that best avoids the faults and risks that have been identified in the overall process. These tools can be easily adapted to radiation therapy practices because of their simplicity and effectiveness to provide efficient ways to enhance the safety and quality of treatment processes. Task group 100 (TG100) of AAPM has developed a risk-based quality management program that uses these tools. This session will be devoted to a discussion of these tools and how these tools can be used in a given radiotherapy clinic to develop a risk based QM program. Learning Objectives: Learn how to design a process map for a radiotherapy process. Learn how to perform a FMEA analysis for a given process. Learn what

  14. Application of Factorial Designs and Simplex Optimisation in the Development of Flow Injection-Hydride Generation-Graphite Furnace Atomic Absorption Spectrometry Procedures as Demonstrated for the Determination of Trace Levels of Germanium

    DEFF Research Database (Denmark)

    Hilligsøe, Bo; Hansen, Elo Harald

    1997-01-01

    The optimisation of a volume-based FI-HG-GFAAS procedure is described for the trace determination of Ge, comprising in situ collection of the generated germane in the graphite furnace. The response function is the peak area readout (A*s). Based on a preliminary study, where factorial designs were...

  15. A risk-based approach to flammable gas detector spacing.

    Science.gov (United States)

    Defriend, Stephen; Dejmek, Mark; Porter, Leisa; Deshotels, Bob; Natvig, Bernt

    2008-11-15

    Flammable gas detectors allow an operating company to address leaks before they become serious, by automatically alarming and by initiating isolation and safe venting. Without effective gas detection, there is very limited defense against a flammable gas leak developing into a fire or explosion that could cause loss of life or escalate to cascading failures of nearby vessels, piping, and equipment. While it is commonly recognized that some gas detectors are needed in a process plant containing flammable gas or volatile liquids, there is usually a question of how many are needed. The areas that need protection can be determined by dispersion modeling from potential leak sites. Within the areas that must be protected, the spacing of detectors (or alternatively, number of detectors) should be based on risk. Detector design can be characterized by spacing criteria, which is convenient for design - or alternatively by number of detectors, which is convenient for cost reporting. The factors that influence the risk are site-specific, including process conditions, chemical composition, number of potential leak sites, piping design standards, arrangement of plant equipment and structures, design of isolation and depressurization systems, and frequency of detector testing. Site-specific factors such as those just mentioned affect the size of flammable gas cloud that must be detected (within a specified probability) by the gas detection system. A probability of detection must be specified that gives a design with a tolerable risk of fires and explosions. To determine the optimum spacing of detectors, it is important to consider the probability that a detector will fail at some time and be inoperative until replaced or repaired. A cost-effective approach is based on the combined risk from a representative selection of leakage scenarios, rather than a worst-case evaluation. This means that probability and severity of leak consequences must be evaluated together. In marine and

  16. Risk-based regulation - an NRC perspective and status

    International Nuclear Information System (INIS)

    King, T.L.; Murphy, J.A.

    1993-01-01

    The consideration of risk in regulatory decision making has traditionally been part of the US Nuclear Regulatory Commission's (NRC's) policy and practice. In the early days of regulation, this consideration was more qualitative in nature and was reflected in prescriptive/deterministic regulatory requirements. However, with the development of quantitative risk assessment methods, more detailed and comprehensive (although not complete) risk information on nuclear power plants is available to the designer, operator, and regulator. The availability of such information provides an opportunity to assess the need for change in the current regulatory structure and to develop future regulatory requirements in a less prescriptive, more performance-oriented fashion

  17. Risk-based Inspection Planning Optimisation of Offshore Wind Turbines

    DEFF Research Database (Denmark)

    Ramirez, José Rangel; Sørensen, John Dalsgaard

    2011-01-01

    Wind industry is substantially propelled and the future scenarios designate offshore locations as important sites for energy production. With this development, offshore wind farms represent a feasible option to accomplish the needed energy, bringing with it technical and economical challenges......, but considering the lower reliability level for wind turbines. This framework is addressing fatigue prone details in welded steel joints typically located in the wind turbine substructure. The increase of turbulence in-wind farms (IWF) due to wake effects is taken into account using a code-based turbulence model...

  18. Application of risk-based methods to inservice testing of check valves

    Energy Technology Data Exchange (ETDEWEB)

    Closky, N.B.; Balkey, K.R.; McAllister, W.J. [and others

    1996-12-01

    Research efforts have been underway in the American Society of Mechanical Engineers (ASME) and industry to define appropriate methods for the application of risk-based technology in the development of inservice testing (IST) programs for pumps and valves in nuclear steam supply systems. This paper discusses a pilot application of these methods to the inservice testing of check valves in the emergency core cooling system of Georgia Power`s Vogtle nuclear power station. The results of the probabilistic safety assessment (PSA) are used to divide the check valves into risk-significant and less-risk-significant groups. This information is reviewed by a plant expert panel along with the consideration of appropriate deterministic insights to finally categorize the check valves into more safety-significant and less safety-significant component groups. All of the more safety-significant check valves are further evaluated in detail using a failure modes and causes analysis (FMCA) to assist in defining effective IST strategies. A template has been designed to evaluate how effective current and emerging tests for check valves are in detecting failures or in finding significant conditions that are precursors to failure for the likely failure causes. This information is then used to design and evaluate appropriate IST strategies that consider both the test method and frequency. A few of the less safety-significant check valves are also evaluated using this process since differences exist in check valve design, function, and operating conditions. Appropriate test strategies are selected for each check valve that has been evaluated based on safety and cost considerations. Test strategies are inferred from this information for the other check valves based on similar check valve conditions. Sensitivity studies are performed using the PSA model to arrive at an overall IST program that maintains or enhances safety at the lowest achievable cost.

  19. Environmental procedures

    International Nuclear Information System (INIS)

    1992-01-01

    The European Bank has pledged in its Agreement to place environmental management at the forefront of its operations to promote sustainable economic development in central and eastern Europe. The Bank's environmental policy is set out in the document titled, Environmental Management: The Bank's Policy Approach. This document, Environmental Procedures, presents the procedures which the European Bank has adopted to implement this policy approach with respect to its operations. The environmental procedures aim to: ensure that throughout the project approval process, those in positions of responsibility for approving projects are aware of the environmental implications of the project, and can take these into account when making decisions; avoid potential liabilities that could undermine the success of a project for its sponsors and the Bank; ensure that environmental costs are estimated along with other costs and liabilities; and identify opportunities for environmental enhancement associated with projects. The review of environmental aspects of projects is conducted by many Bank staff members throughout the project's life. This document defines the responsibilities of the people and groups involved in implementing the environmental procedures. Annexes contain Environmental Management: The Bank's Policy Approach, examples of environmental documentation for the project file and other ancillary information

  20. Guidance on the implementation of a risk based safety performance monitoring system for nuclear power plants

    International Nuclear Information System (INIS)

    Sewell, R.T.; Kuritzky, A.S.; Khatib-Rahbar, M.

    1997-05-01

    The principal objective of the present study is to review and evaluate existing Performance Indicator (PI) monitoring programs, and to develop and demonstrate an overall PSA-based methodology and framework for the monitoring and use of risk-based PIs and SIs (Safety Indicator), that would enable: Identification of trends and patterns in safety performance at a specific plant and a population of plants; Assessment of the significance of the trends and patterns; Identification of precursors of accident sequences and safety reductions; Identification of the most critical functional areas of concern, especially as they relate to a defense-in-depth safety philosophy; Comparison of safety performance trends at a plant with those at comparable plants; Incorporation of the PIs and SIs into a risk- and performance-based decision process. To support the overall project objective, it is important that information needs and data collection procedures are clearly outlined. Of key significance in this regard is the premise that a performance monitoring system should not be burdened by an excessive number of low-level PIs that may have only a peripheral relationship to safety. Other supporting objectives of the study include: To identify and discuss other issues pertaining to the practical implementation of a safety performance monitoring system (outlining the databases and algorithms needed); and to demonstrate implementation of the preliminary guidance for monitoring and use of the selected set of PIs and SIs, within the proposed framework, via application to the operating history of a NPP having a PSA and readily available event data

  1. A Semi Risk-Based Approach for Managing Urban Drainage Systems under Extreme Rainfall

    Directory of Open Access Journals (Sweden)

    Carlos Salinas-Rodriguez

    2018-03-01

    Full Text Available Conventional design standards for urban drainage systems are not set to deal with extreme rainfall events. As these events are becoming more frequent, there is room for proposing new planning approaches and standards that are flexible enough to cope with a wide range of rainfall events. In this paper, a semi risk-based approach is presented as a simple and practical way for the analysis and management of rainfall flooding at the precinct scale. This approach uses various rainfall events as input parameters for the analysis of the flood hazard and impacts, and categorises the flood risk in different levels, ranging from very low to very high risk. When visualised on a map, the insight into the risk levels across the precinct will enable engineers and spatial planners to identify and prioritise interventions to manage the flood risk. The approach is demonstrated for a sewer district in the city of Rotterdam, the Netherlands, using a one-dimensional (1D/two-dimensional (2D flood model. The risk level of this area is classified as being predominantly very low or low, with a couple of locations with high and very high risk. For these locations interventions, such as disconnection and lowering street profiles, have been proposed and analysed with the 1D/2D flood model. The interventions were shown to be effective in reducing the risk levels from very high/high risk to medium/low risk.

  2. Risk based In Vitro Performance Assessment of Extended Release Abuse Deterrent Formulations

    Science.gov (United States)

    Xu, Xiaoming; Gupta, Abhay; Al-Ghabeish, Manar; Calderon, Silvia N.; Khan, Mansoor A.

    2016-01-01

    High strength extended release opioid products, which are indispensable tools in the management of pain, are associated with serious risks of unintentional and potentially fatal overdose, as well as of misuse and abuse that might lead to addiction. The issue of drug abuse becomes increasingly prominent when the dosage forms can be readily manipulated to release a high amount of opioid or to extract the drug in certain products or solvents. One approach to deter opioid drug abuse is by providing novel abuse deterrent formulations (ADF), with properties that may be viewed as barriers to abuse of the product. However, unlike regular extended release formulations, assessment of ADF technologies are challenging, in part due to the great variety of formulation designs available to achieve deterrence of abuse by oral, parenteral, nasal and respiratory routes. With limited prior history or literature information, and lack of compendial standards, evaluation and regulatory approval of these novel drug products become increasingly difficult. The present article describes a risk-based standardized in-vitro approach that can be utilized in general evaluation of abuse deterrent features for all ADF products. PMID:26784976

  3. Application and Evaluation of Control Modes for Risk-Based Engine Performance Enhancements

    Science.gov (United States)

    Liu, Yuan; Litt, Jonathan S.; Sowers, T. Shane; Owen, A. Karl; Guo, Ten-Huei

    2015-01-01

    The engine control system for civil transport aircraft imposes operational limits on the propulsion system to ensure compliance with safety standards. However, during certain emergency situations, aircraft survivability may benefit from engine performance beyond its normal limits despite the increased risk of failure. Accordingly, control modes were developed to improve the maximum thrust output and responsiveness of a generic high-bypass turbofan engine. The algorithms were designed such that the enhanced performance would always constitute an elevation in failure risk to a consistent predefined likelihood. This paper presents an application of these risk-based control modes to a combined engine/aircraft model. Through computer and piloted simulation tests, the aim is to present a notional implementation of these modes, evaluate their effects on a generic airframe, and demonstrate their usefulness during emergency flight situations. Results show that minimal control effort is required to compensate for the changes in flight dynamics due to control mode activation. The benefits gained from enhanced engine performance for various runway incursion scenarios are investigated. Finally, the control modes are shown to protect against potential instabilities during propulsion-only flight where all aircraft control surfaces are inoperable.

  4. Health economics and outcomes methods in risk-based decision-making for blood safety.

    Science.gov (United States)

    Custer, Brian; Janssen, Mart P

    2015-08-01

    Analytical methods appropriate for health economic assessments of transfusion safety interventions have not previously been described in ways that facilitate their use. Within the context of risk-based decision-making (RBDM), health economics can be important for optimizing decisions among competing interventions. The objective of this review is to address key considerations and limitations of current methods as they apply to blood safety. Because a voluntary blood supply is an example of a public good, analyses should be conducted from the societal perspective when possible. Two primary study designs are recommended for most blood safety intervention assessments: budget impact analysis (BIA), which measures the cost to implement an intervention both to the blood operator but also in a broader context, and cost-utility analysis (CUA), which measures the ratio between costs and health gain achieved, in terms of reduced morbidity and mortality, by use of an intervention. These analyses often have important limitations because data that reflect specific aspects, for example, blood recipient population characteristics or complication rates, are not available. Sensitivity analyses play an important role. The impact of various uncertain factors can be studied conjointly in probabilistic sensitivity analyses. The use of BIA and CUA together provides a comprehensive assessment of the costs and benefits from implementing (or not) specific interventions. RBDM is multifaceted and impacts a broad spectrum of stakeholders. Gathering and analyzing health economic evidence as part of the RBDM process enhances the quality, completeness, and transparency of decision-making. © 2015 AABB.

  5. Risk-based approach for bioremediation of fuel hydrocarbons at a major airport

    International Nuclear Information System (INIS)

    Wiedemeier, T.H.; Guest, P.R.; Blicker, B.R.

    1994-01-01

    This paper describes a risk-based approach for bioremediation of fuel-hydrocarbon-contaminated soil and ground water at a major airport in Colorado. In situ bioremediation pilot testing, natural attenuation modeling, and full-scale remedial action planning and implementation for soil and ground water contamination has conducted at four airport fuel farms. The sources of fuel contamination were leaking underground storage tanks (USTs) or pipelines transporting Jet A fuel and aviation gasoline. Continuing sources of contamination were present in several small cells of free-phase product and in fuel residuals trapped within the capillary fringe at depths 15 to 20 feet below ground surface. Bioventing pilot tests were conducted to assess the feasibility of using this technology to remediate contaminated soils. The pilot tests included measurement of initial soil gas chemistry at the site, determination of subsurface permeability, and in situ respiration tests to determine fuel biodegradation rates. A product recovery test was also conducted. ES designed and installed four full-scale bioventing systems to remediate the long-term sources of continuing fuel contamination. Benzene, toluene, ethylbenzene, and xylenes (BTEX) and total petroleum hydrocarbons (TPH) were detected in ground water at concentrations slightly above regulatory guidelines

  6. Risk-based analysis and decision making in multi-disciplinary environments

    Science.gov (United States)

    Feather, Martin S.; Cornford, Steven L.; Moran, Kelly

    2003-01-01

    A risk-based decision-making process conceived of and developed at JPL and NASA, has been used to help plan and guide novel technology applications for use on spacecraft. These applications exemplify key challenges inherent in multi-disciplinary design of novel technologies deployed in mission-critical settings. 1) Cross-disciplinary concerns are numerous (e.g., spacecraft involve navigation, propulsion, telecommunications). These concems are cross-coupled and interact in multiple ways (e.g., electromagnetic interference, heat transfer). 2) Time and budget pressures constrain development, operational resources constrain the resulting system (e.g., mass, volume, power). 3) Spacecraft are critical systems that must operate correctly the first time in only partially understood environments, with no chance for repair. 4) Past experience provides only a partial guide: New mission concepts are enhanced and enabled by new technologies, for which past experience is lacking. The decision-making process rests on quantitative assessments of the relationships between three classes of information - objectives (the things the system is to accomplish and constraints on its operation and development), risks (whose occurrence detracts from objectives), and mitigations (options for reducing the likelihood and or severity of risks). The process successfully guides experts to pool their knowledge, using custom-built software to support information gathering and decision-making.

  7. Learner, Patient, and Supervisor Features Are Associated With Different Types of Cognitive Load During Procedural Skills Training: Implications for Teaching and Instructional Design.

    Science.gov (United States)

    Sewell, Justin L; Boscardin, Christy K; Young, John Q; Ten Cate, Olle; O'Sullivan, Patricia S

    2017-11-01

    Cognitive load theory, focusing on limits of the working memory, is relevant to medical education; however, factors associated with cognitive load during procedural skills training are not well characterized. The authors sought to determine how features of learners, patients/tasks, settings, and supervisors were associated with three types of cognitive load among learners performing a specific procedure, colonoscopy, to identify implications for procedural teaching. Data were collected through an electronically administered survey sent to 1,061 U.S. gastroenterology fellows during the 2014-2015 academic year; 477 (45.0%) participated. Participants completed the survey immediately following a colonoscopy. Using multivariable linear regression analyses, the authors identified sets of features associated with intrinsic, extraneous, and germane loads. Features associated with intrinsic load included learners (prior experience and year in training negatively associated, fatigue positively associated) and patient/tasks (procedural complexity positively associated, better patient tolerance negatively associated). Features associated with extraneous load included learners (fatigue positively associated), setting (queue order positively associated), and supervisors (supervisor engagement and confidence negatively associated). Only one feature, supervisor engagement, was (positively) associated with germane load. These data support practical recommendations for teaching procedural skills through the lens of cognitive load theory. To optimize intrinsic load, level of experience and competence of learners should be balanced with procedural complexity; part-task approaches and scaffolding may be beneficial. To reduce extraneous load, teachers should remain engaged, and factors within the procedural setting that may interfere with learning should be minimized. To optimize germane load, teachers should remain engaged.

  8. The need to go beyond analysis in making risk-based decisions

    Energy Technology Data Exchange (ETDEWEB)

    Ahearne, J.F. [The Sigma XI Center, Research Triangle Park, NC (United States)

    1999-12-01

    As a physicist, I prefer the R = P x C, with the inclusion of a risk magnifier when appropriate. However, I also accept this is inadequate. For risk-based decisions to be acceptable in a democratic society, there must be widespread agreement on the criteria to be used, the process by which the decision is reached, and the linkage between the criteria and the decision. These demand a transparent process. Armour wrote: 'To date, efforts directed toward facility siting conflicts have focused almost exclusively on the 'public acceptance' factor (and neglected the legitimacy of the process] - the sad reality is that these strategies have not beenall that effective. Moreover, given that the underlying motivation is to 'gain public acceptance' such strategies have often worsened the facility siting problems when used by proponents who were unable, in appearance or in fact, to tread the fine line between manipulating public opinion and liberating it ... the issue of the legitimacy of the decision making process had tended to be taken for granted. Generally speaking, policy makers have failed to seriously question and have not responded well to others who have dared to question the established roles and principles of our conventional processes of decision making.' Finally, acceptance also requires agreement that the issues to be decided are the appropriate issues. Often the decision-makers concentrate on issues that are not the ones the public views as the most important. Sometimes it is because the public wants other alternatives examined. Sometimes it is because the public does not accept the necessity to decide now. And sometimes it is because the public does not trust those who have assumed responsibility for making the decision. The analytic community has grown in size and skill over the last 20 years. The science community has produced a better understanding of health effects and exposure pathways. The engineering community has designed

  9. The need to go beyond analysis in making risk-based decisions

    International Nuclear Information System (INIS)

    Ahearne, J.F.

    1999-01-01

    As a physicist, I prefer the R = P x C, with the inclusion of a risk magnifier when appropriate. However, I also accept this is inadequate. For risk-based decisions to be acceptable in a democratic society, there must be widespread agreement on the criteria to be used, the process by which the decision is reached, and the linkage between the criteria and the decision. These demand a transparent process. Armour wrote: 'To date, efforts directed toward facility siting conflicts have focused almost exclusively on the 'public acceptance' factor (and neglected the legitimacy of the process] - the sad reality is that these strategies have not been all that effective. Moreover, given that the underlying motivation is to 'gain public acceptance' such strategies have often worsened the facility siting problems when used by proponents who were unable, in appearance or in fact, to tread the fine line between manipulating public opinion and liberating it ... the issue of the legitimacy of the decision making process had tended to be taken for granted. Generally speaking, policy makers have failed to seriously question and have not responded well to others who have dared to question the established roles and principles of our conventional processes of decision making.' Finally, acceptance also requires agreement that the issues to be decided are the appropriate issues. Often the decision-makers concentrate on issues that are not the ones the public views as the most important. Sometimes it is because the public wants other alternatives examined. Sometimes it is because the public does not accept the necessity to decide now. And sometimes it is because the public does not trust those who have assumed responsibility for making the decision. The analytic community has grown in size and skill over the last 20 years. The science community has produced a better understanding of health effects and exposure pathways. The engineering community has designed safer systems. However, the

  10. Risk-based transfer responses to climate change, simulated through autocorrelated stochastic methods

    Science.gov (United States)

    Kirsch, B.; Characklis, G. W.

    2009-12-01

    Maintaining municipal water supply reliability despite growing demands can be achieved through a variety of mechanisms, including supply strategies such as temporary transfers. However, much of the attention on transfers has been focused on market-based transfers in the western United States largely ignoring the potential for transfers in the eastern U.S. The different legal framework of the eastern and western U.S. leads to characteristic differences between their respective transfers. Western transfers tend to be agricultural-to-urban and involve raw, untreated water, with the transfer often involving a simple change in the location and/or timing of withdrawals. Eastern transfers tend to be contractually established urban-to-urban transfers of treated water, thereby requiring the infrastructure to transfer water between utilities. Utilities require the tools to be able to evaluate transfer decision rules and the resulting expected future transfer behavior. Given the long-term planning horizons of utilities, potential changes in hydrologic patterns due to climate change must be considered. In response, this research develops a method for generating a stochastic time series that reproduces the historic autocorrelation and can be adapted to accommodate future climate scenarios. While analogous in operation to an autoregressive model, this method reproduces the seasonal autocorrelation structure, as opposed to assuming the strict stationarity produced by an autoregressive model. Such urban-to-urban transfers are designed to be rare, transient events used primarily during times of severe drought, and incorporating Monte Carlo techniques allows for the development of probability distributions of likely outcomes. This research evaluates a system risk-based, urban-to-urban transfer agreement between three utilities in the Triangle region of North Carolina. Two utilities maintain their own surface water supplies in adjoining watersheds and look to obtain transfers via

  11. Risk-based environmental assessment for uranium mines – some Canadian and Australian experience

    International Nuclear Information System (INIS)

    Phaneuf, M.; Woods, P.; McKee, M.

    2014-01-01

    assessment under the Federal Environment Protection and Biodiversity Act 1999, as well as a parallel State or Territory approvals. The previous generation of mines were approved under the former Environment Protection (Impact of Proposals) Act 1993 or earlier arrangements. In recent years various guidelines, both generic and developed for individual proposals have been issued by State, Territory and Federal governments. Recent Australian guidelines, for uranium and other mining, all include a risk-based approach to environmental impact assessment, including consideration of design and operating measures to minimize impacts, and associated environmental monitoring programmes to assess actual against expected outcomes and provide early-warning of potentially adverse trends. Some recent guidelines and their application to new uranium projects or extensions of existing operations in three jurisdictions are reviewed and the usefulness of the approach discussed. (author)

  12. Feasibility assessment of a risk-based approach to technical specifications

    International Nuclear Information System (INIS)

    Atefi, B.; Gallagher, D.W.

    1991-05-01

    To assess the potential use of risk and reliability techniques for improving the effectiveness of the technical specifications to control plant operational risk, the Technical Specifications Branch of the Nuclear Regulatory Commission initiated an effort to identify and evaluate alternative risk-based approaches that could bring greater risk perspective to these requirements. In the first phase four alternative approaches were identified and their characteristics were analyzed. Among these, the risk-based approach to technical specifications is the most promising approach for controlling plant operational risk using technical specifications. The second phase of the study concentrated on detailed characteristics of the real time risk-based approach. It is concluded that a real time risk-based approach to technical specifications has the potential to improve both plant safety and availability. 33 figs., 5 figs., 6 tabs

  13. RIMAP demonstration project. Pat. 1: Risk based life management of piping system in power plant Heilbronn

    International Nuclear Information System (INIS)

    Bareiss, J.; Puck, P.; Matschecko, B.; Jovanovic, A.; Balos, D.; Perunicic

    2003-01-01

    In the framework of EU project RIMAP [1] a new European Guideline for optimized risk based maintenance and inspection planning of industrial plants (RBLM - Risk Based Life Management) is being developed. The RIMAP project consists of the three clustered projects: development (RTD), demonstration (DEMO) and thematic network (TN). Current work and future, planned work in RIMAP demonstration project on applications of the RIMAP methodology in power plants are presented briefly in the first part of the paper. Also presented in the paper are the results of a preliminary analysis of piping system in power plant Heilbronn using the concept of risk-based monitoring as part of overall concept of risk-based life management. Shortly the following issues are discussed in the paper: identification of critical components, application of a multilevel risk analysis (..from ''screening'' to ''detailed analysis''), determination of PoF - Probability of Failure, determination of COF - Consequence of Failure and optimation of inspection and maintenance plan. (orig.)

  14. A quantitative risk-based model for reasoning over critical system properties

    Science.gov (United States)

    Feather, M. S.

    2002-01-01

    This position paper suggests the use of a quantitative risk-based model to help support reeasoning and decision making that spans many of the critical properties such as security, safety, survivability, fault tolerance, and real-time.

  15. Design

    DEFF Research Database (Denmark)

    Volf, Mette

    Design - proces & metode iBog®  er enestående i sit fokus på afmystificering og operationalisering af designprocessens flygtige og komplekse karakter. Udgivelsen går bag om designerens daglige arbejde og giver et indblik i den kreative skabelsesproces, som designeren er en del af. Udover et bredt...... indblik i designerens arbejdsmetoder og designparametre giver Design - proces & metode en række eksempler fra anerkendte designvirksomheder, der gør det muligt at komme helt tæt på designerens virkelighed....

  16. HOW INTERNAL RISK - BASED AUDIT APPRAISES THE EVALUATION OF RISKS MANAGEMENT

    Directory of Open Access Journals (Sweden)

    N. Dorosh

    2017-09-01

    Full Text Available The article deals with the nature and function of the internal risk-based audit process approach to create patterns of risks and methods of evaluation. Deals with the relationship between the level of maturity of the risk of the company and the method of risk-based internal audit. it was emphasized that internal auditing provides an independent and objective opinion to an organization’s management as to whether its risks are being managed to acceptable levels.

  17. Design

    Science.gov (United States)

    Buchanan, Richard; Cross, Nigel; Durling, David; Nelson, Harold; Owen, Charles; Valtonen, Anna; Boling, Elizabeth; Gibbons, Andrew; Visscher-Voerman, Irene

    2013-01-01

    Scholars representing the field of design were asked to identify what they considered to be the most exciting and imaginative work currently being done in their field, as well as how that work might change our understanding. The scholars included Richard Buchanan, Nigel Cross, David Durling, Harold Nelson, Charles Owen, and Anna Valtonen. Scholars…

  18. Radiochemical procedures

    International Nuclear Information System (INIS)

    Lyon, W.S.

    1982-01-01

    The modern counting instrumentation has largely obviated the need for separation processes in the radiochemical analysis but problems in low-level radioactivity measurement, environmental-type analyses, and special situations caused in the last years a renaissance of the need for separation techniques. Most of the radiochemical procedures, based on the classic works of the Manhattan Project chemists of the 1940's, were published in the National Nuclear Energy Series (NNES). Improvements such as new solvent extraction and ion exchange separations have been added to these methods throughout the years. Recently the Los Alamos Group have reissued their collected Radiochemical Procedures containing a short summary and review of basic inorganic chemistry - 'Chemistry of the Elements on the Basis of Electronic Configuration'. (A.L.)

  19. The TOMAX-procedure

    NARCIS (Netherlands)

    Overgoor, M.L.E.

    2015-01-01

    Most patients with a low spinal lesion (LSL) have intact erectile function but no penile sensation, which can lead to frustration. To tackle this problem, we designed TOMAX, TOMAXimize sensation, sexuality and quality of life, a surgical procedure in which a functional "groin” nerve is connected to

  20. Experiments with Cloze Procedure

    Science.gov (United States)

    Evans, Gordon; Haastrup, Kirsten

    1976-01-01

    The Nordic Test Development Group prepared proficiency tests of English designed to provide reliable information on which to base decisions as to whether a candidate would be able to function in a job as described or whether he could be trained to do so. Two subtests used a modified cloze procedure. (Author/CFM)

  1. INTERNAL GOVERNANCE AND ROLE OF INTERNAL AUDIT IN FINANCIAL INSTITUTIONS. CASE STUDY: RISK BASED PLANNING

    Directory of Open Access Journals (Sweden)

    Andrei Florin

    2015-07-01

    Full Text Available The global financial crisis from 2008 was considered a trigger to reshape the financial systems and to enhance the risk management practices. Considering the developments and new guidelines that are now used it can be observed a “positive” effect of the crisis, in particular to strengthen the risk management culture and governance in all aspects. Comparing to 2008 year, the improvements that have been made to the risk management systems can be easily observed in the financial institutions. For the scope of the article, the subject of this review will be focused on the internal audit function. The main aspect is to capture the new practices that are now used in order to contribute to a performing internal governance system. A case study will be presented in order to better understand how the internal audit function is designed and acting as a “line” of defence in the internal governance system. Also, it is in the scope of the article to issue some recommendations for future developments of the audit function in order to better manage its mission and the objectives. A risk based model used in the planning activities is presented. The financial institutions improved significantly their internal governance system. The internal audit function is now better integrated in the internal structures and clear lines of communication were settled. As the conclusion of the article is illustrating, the internal governance was frequently not sufficiently developed causing a failure in the risk management systems from the systemically financial institutions. The content of the article has practical applicability, as the results and the recommendations could be used in the design of an audit function within a financial institution.

  2. Planning Risk-Based SQC Schedules for Bracketed Operation of Continuous Production Analyzers.

    Science.gov (United States)

    Westgard, James O; Bayat, Hassan; Westgard, Sten A

    2018-02-01

    To minimize patient risk, "bracketed" statistical quality control (SQC) is recommended in the new CLSI guidelines for SQC (C24-Ed4). Bracketed SQC requires that a QC event both precedes and follows (brackets) a group of patient samples. In optimizing a QC schedule, the frequency of QC or run size becomes an important planning consideration to maintain quality and also facilitate responsive reporting of results from continuous operation of high production analytic systems. Different plans for optimizing a bracketed SQC schedule were investigated on the basis of Parvin's model for patient risk and CLSI C24-Ed4's recommendations for establishing QC schedules. A Sigma-metric run size nomogram was used to evaluate different QC schedules for processes of different sigma performance. For high Sigma performance, an effective SQC approach is to employ a multistage QC procedure utilizing a "startup" design at the beginning of production and a "monitor" design periodically throughout production. Example QC schedules are illustrated for applications with measurement procedures having 6-σ, 5-σ, and 4-σ performance. Continuous production analyzers that demonstrate high σ performance can be effectively controlled with multistage SQC designs that employ a startup QC event followed by periodic monitoring or bracketing QC events. Such designs can be optimized to minimize the risk of harm to patients. © 2017 American Association for Clinical Chemistry.

  3. 75 FR 82317 - Risk-Based Capital Standards: Advanced Capital Adequacy Framework-Basel II; Establishment of a...

    Science.gov (United States)

    2010-12-30

    ... leverage or risk-based capital requirements in effect for insured depository institutions as of the date of..., sections 171(b)(1) and (2) specify that the minimum leverage and risk- based capital requirements...)(1) and (2) specify that the Federal banking agencies may not establish leverage or risk-based...

  4. Procedure guide of design, construction of prototypes, calibration and sure operation of nucleonic control systems; Guia de procedimientos de diseno, construccion de prototipos, calibracion y operacion segura de sistemas de control nucleonico

    Energy Technology Data Exchange (ETDEWEB)

    Banados Perez, H [Instituto de Pesquizas Energia Nuclear, Sao Paulo (Brazil); Griffith Martinez, J [Instituto de Investigaciones de la Cana de Azucar, La Habana (Cuba); Desdin Garcia, L F [Centro de Estudios Aplicados al Desarrollo Nuclear, La Habana (Cuba); Rodriguez Cardona, R L [Agencia de Energia Nuclear, La Habana (Cuba); Molina, G [Instituto de Investigaciones Nucleares, Mexico City (Mexico); Sebastian Calvo, C [Instituto Peruano de Energia Nuclear, Lima (Peru)

    1999-09-24

    This Guide was elaborated in the mark of the project RLA/8/024 ARCAL XLII 'Industrial Applications of the Tracer Technology and Nucleonic Control Systems'. Its objective is to establish the approaches for the design, the construction, the selection and the procedures for the sure operation of the Nucleonic Control Systems (NCS) in the industry. The NCS is used to control processes to high speeds, materials with extreme conditions or with noxious chemical properties, susceptible materials of being damaged by contact and packed products. In this document is defined the scope of the procedure. The SCN are classified according to: type of radiations, the mobility of the components, the degree of the beams collimation; and in function of the security. The design and construction criteria of the nuclear meters and of the systems of control nucleonic are exposed.

  5. Risk-based inservice testing program modifications at Palo Verde nuclear generating station

    Energy Technology Data Exchange (ETDEWEB)

    Knauf, S.; Lindenlaub, B.; Linthicum, R.

    1996-12-01

    Arizona Public Service Company (APS) is investigating changes to the Palo Verde Inservice Testing (IST) Program that are intended to result in the reduction of the required test frequency for various valves in the American Society of Mechanical Engineers (ASME) Section XI IST program. The analytical techniques employed to select candidate valves and to demonstrate that these frequency reductions are acceptable are risk based. The results of the Palo Verde probabilistic risk assessment (PRA), updated in June 1994, and the risk significant determination performed as part of the implementation efforts for 10 CFR 50.65 (the maintenance rule) were used to select candidate valves for extended test intervals. Additional component level evaluations were conducted by an `expert panel.` The decision to pursue these changes was facilitated by the ASME Risk-Based Inservice Testing Research Task Force for which Palo Verde is participating as a pilot plant. The NRC`s increasing acceptance of cost beneficial licensing actions and risk-based submittals also provided incentive to seek these changes. Arizona Public Service is pursuing the risk-based IST program modification in order to reduce the unnecessary regulatory burden of the IST program through qualitative and quantitative analysis consistent with maintaining a high level of plant safety. The objectives of this project at Palo Verde are as follows: (1) Apply risk-based technologies to IST components to determine their risk significance (i.e., high or low). (2) Apply a combination of deterministic and risk-based methods to determine appropriate testing requirements for IST components including improvement of testing methods and frequency intervals for high-risk significant components. (3) Apply risk-based technologies to high-risk significant components identified by the {open_quotes}expert panel{close_quotes} and outside of the IST program to determine whether additional testing requirements are appropriate.

  6. Risk-based inservice testing program modifications at Palo Verde nuclear generating station

    International Nuclear Information System (INIS)

    Knauf, S.; Lindenlaub, B.; Linthicum, R.

    1996-01-01

    Arizona Public Service Company (APS) is investigating changes to the Palo Verde Inservice Testing (IST) Program that are intended to result in the reduction of the required test frequency for various valves in the American Society of Mechanical Engineers (ASME) Section XI IST program. The analytical techniques employed to select candidate valves and to demonstrate that these frequency reductions are acceptable are risk based. The results of the Palo Verde probabilistic risk assessment (PRA), updated in June 1994, and the risk significant determination performed as part of the implementation efforts for 10 CFR 50.65 (the maintenance rule) were used to select candidate valves for extended test intervals. Additional component level evaluations were conducted by an 'expert panel.' The decision to pursue these changes was facilitated by the ASME Risk-Based Inservice Testing Research Task Force for which Palo Verde is participating as a pilot plant. The NRC's increasing acceptance of cost beneficial licensing actions and risk-based submittals also provided incentive to seek these changes. Arizona Public Service is pursuing the risk-based IST program modification in order to reduce the unnecessary regulatory burden of the IST program through qualitative and quantitative analysis consistent with maintaining a high level of plant safety. The objectives of this project at Palo Verde are as follows: (1) Apply risk-based technologies to IST components to determine their risk significance (i.e., high or low). (2) Apply a combination of deterministic and risk-based methods to determine appropriate testing requirements for IST components including improvement of testing methods and frequency intervals for high-risk significant components. (3) Apply risk-based technologies to high-risk significant components identified by the open-quotes expert panelclose quotes and outside of the IST program to determine whether additional testing requirements are appropriate

  7. Design

    DEFF Research Database (Denmark)

    Jensen, Ole B.; Pettiway, Keon

    2017-01-01

    In this chapter, Ole B. Jensen takes a situational approach to mobilities to examine how ordinary life activities are structured by technology and design. Using “staging mobilities” as a theoretical approach, Jensen considers mobilities as overlapping, actions, interactions and decisions by desig...... by providing ideas about future research for investigating mobilities in situ as a kind of “staging,” which he notes is influenced by the “material turn” in social sciences....... with a brief description of how movement is studied within social sciences after the “mobilities turn” versus the idea of physical movement in transport geography and engineering. He then explains how “mobilities design” was derived from connections between traffic and architecture. Jensen concludes...

  8. New approach for risk based inspection of H2S based Process Plants

    International Nuclear Information System (INIS)

    Vinod, Gopika; Sharma, Pavan K.; Santosh, T.V.; Hari Prasad, M.; Vaze, K.K.

    2014-01-01

    Highlights: • Study looks into improving the consequence evaluation in risk based inspection. • Ways to revise the quantity factors used in qualitative approach. • New approach based on computational fluid dynamics along with probit mathematics. • Demonstrated this methodology along with a suitable case study for the said issue. - Abstract: Recent trend in risk informed and risk based approaches in life management issues have certainly put the focus on developing estimation methods for real risk. Idea of employing risk as an optimising measure for in-service inspection, termed as risk based inspection, was accepted in principle from late 80s. While applying risk based inspection, consequence of failure from each component needs to be assessed. Consequence evaluation in a Process Plant is a crucial task. It may be noted that, in general, the number of components to be considered for life management is very large and hence the consequence evaluation resulting from their failures (individually) is a laborious task. Screening of critical components is usually carried out using simplified qualitative approach, which primarily uses influence factors for categorisation. This necessitates logical formulation of influence factors and their ranges with a suitable technical basis for acceptance from regulators. This paper describes application of risk based inspection for H 2 S based Process Plant along with the approach devised for handling the influence factor related to the quantity of H 2 S released

  9. Waste-acceptance criteria and risk-based thinking for radioactive-waste classification

    International Nuclear Information System (INIS)

    Lowenthal, M.D.

    1998-01-01

    The US system of radioactive-waste classification and its development provide a reference point for the discussion of risk-based thinking in waste classification. The official US system is described and waste-acceptance criteria for disposal sites are introduced because they constitute a form of de facto waste classification. Risk-based classification is explored and it is found that a truly risk-based system is context-dependent: risk depends not only on the waste-management activity but, for some activities such as disposal, it depends on the specific physical context. Some of the elements of the official US system incorporate risk-based thinking, but like many proposed alternative schemes, the physical context of disposal is ignored. The waste-acceptance criteria for disposal sites do account for this context dependence and could be used as a risk-based classification scheme for disposal. While different classes would be necessary for different management activities, the waste-acceptance criteria would obviate the need for the current system and could better match wastes to disposal environments saving money or improving safety or both

  10. Managing long-term polycyclic aromatic hydrocarbon contaminated soils: a risk-based approach.

    Science.gov (United States)

    Duan, Luchun; Naidu, Ravi; Thavamani, Palanisami; Meaklim, Jean; Megharaj, Mallavarapu

    2015-06-01

    Polycyclic aromatic hydrocarbons (PAHs) are a family of contaminants that consist of two or more aromatic rings fused together. Soils contaminated with PAHs pose significant risk to human and ecological health. Over the last 50 years, significant research has been directed towards the cleanup of PAH-contaminated soils to background level. However, this achieved only limited success especially with high molecular weight compounds. Notably, during the last 5-10 years, the approach to remediate PAH-contaminated soils has changed considerably. A risk-based prioritization of remediation interventions has become a valuable step in the management of contaminated sites. The hydrophobicity of PAHs underlines that their phase distribution in soil is strongly influenced by factors such as soil properties and ageing of PAHs within the soil. A risk-based approach recognizes that exposure and environmental effects of PAHs are not directly related to the commonly measured total chemical concentration. Thus, a bioavailability-based assessment using a combination of chemical analysis with toxicological assays and nonexhaustive extraction technique would serve as a valuable tool in risk-based approach for remediation of PAH-contaminated soils. In this paper, the fate and availability of PAHs in contaminated soils and their relevance to risk-based management of long-term contaminated soils are reviewed. This review may serve as guidance for the use of site-specific risk-based management methods.

  11. WE-B-BRC-00: Concepts in Risk-Based Assessment

    Energy Technology Data Exchange (ETDEWEB)

    NONE

    2016-06-15

    Prospective quality management techniques, long used by engineering and industry, have become a growing aspect of efforts to improve quality management and safety in healthcare. These techniques are of particular interest to medical physics as scope and complexity of clinical practice continue to grow, thus making the prescriptive methods we have used harder to apply and potentially less effective for our interconnected and highly complex healthcare enterprise, especially in imaging and radiation oncology. An essential part of most prospective methods is the need to assess the various risks associated with problems, failures, errors, and design flaws in our systems. We therefore begin with an overview of risk assessment methodologies used in healthcare and industry and discuss their strengths and weaknesses. The rationale for use of process mapping, failure modes and effects analysis (FMEA) and fault tree analysis (FTA) by TG-100 will be described, as well as suggestions for the way forward. This is followed by discussion of radiation oncology specific risk assessment strategies and issues, including the TG-100 effort to evaluate IMRT and other ways to think about risk in the context of radiotherapy. Incident learning systems, local as well as the ASTRO/AAPM ROILS system, can also be useful in the risk assessment process. Finally, risk in the context of medical imaging will be discussed. Radiation (and other) safety considerations, as well as lack of quality and certainty all contribute to the potential risks associated with suboptimal imaging. The goal of this session is to summarize a wide variety of risk analysis methods and issues to give the medical physicist access to tools which can better define risks (and their importance) which we work to mitigate with both prescriptive and prospective risk-based quality management methods. Learning Objectives: Description of risk assessment methodologies used in healthcare and industry Discussion of radiation oncology

  12. Application of CFD dispersion calculation in risk based inspection for release of H2S

    International Nuclear Information System (INIS)

    Sharma, Pavan K.; Vinod, Gopika; Singh, R.K.; Rao, V.V.S.S.; Vaze, K.K.

    2011-01-01

    In atmospheric dispersion both deterministic and probabilistic approached have been used for addressing design and regulatory concerns. In context of deterministic calculations the amount of pollutants dispersion in the atmosphere is an important area wherein different approaches are followed in development of good analytical model. The analysis based on Computational Fluid Dynamics (CFD) codes offer an opportunity of model development based on first principles of physics and hence such models have an edge over the existing models. In context of probabilistic methods applying risk based inspection (wherein consequence of failure from each component needs to be assessed) are becoming popular. Consequence evaluation in a process plant is a crucial task. Often the number of components considered for life management will be too huge. Also consequence evaluation of all the components proved to be laborious task. The present paper is the results of joint collaborative work from deterministic and probabilistic modelling group working in the field of atmospheric dispersion. Even though API 581 has simplified qualitative approach, regulators find the some of the factors, in particular, quantity factor, not suitable for process plants. Often dispersion calculations for heavy gas are done with very simple model which can not take care of density based atmospheric dispersion. This necessitates a new approach with a CFD based technical basis is proposed, so that the range of quantity considered along with factors used can be justified. The present paper is aimed at bringing out some of the distinct merits and demerits of the CFD based models. A brief account of the applications of such CFD codes reported in literature is also presented in the paper. This paper describes the approach devised and demonstrated for the said issue with emphasis of CFD calculations. (author)

  13. Risk Based Inspection Methodology and Software Applied to Atmospheric Storage Tanks

    Science.gov (United States)

    Topalis, P.; Korneliussen, G.; Hermanrud, J.; Steo, Y.

    2012-05-01

    A new risk-based inspection (RBI) methodology and software is presented in this paper. The objective of this work is to allow management of the inspections of atmospheric storage tanks in the most efficient way, while, at the same time, accident risks are minimized. The software has been built on the new risk framework architecture, a generic platform facilitating efficient and integrated development of software applications using risk models. The framework includes a library of risk models and the user interface is automatically produced on the basis of editable schemas. This risk-framework-based RBI tool has been applied in the context of RBI for above-ground atmospheric storage tanks (AST) but it has been designed with the objective of being generic enough to allow extension to the process plants in general. This RBI methodology is an evolution of an approach and mathematical models developed for Det Norske Veritas (DNV) and the American Petroleum Institute (API). The methodology assesses damage mechanism potential, degradation rates, probability of failure (PoF), consequence of failure (CoF) in terms of environmental damage and financial loss, risk and inspection intervals and techniques. The scope includes assessment of the tank floor for soil-side external corrosion and product-side internal corrosion and the tank shell courses for atmospheric corrosion and internal thinning. It also includes preliminary assessment for brittle fracture and cracking. The data are structured according to an asset hierarchy including Plant, Production Unit, Process Unit, Tag, Part and Inspection levels and the data are inherited / defaulted seamlessly from a higher hierarchy level to a lower level. The user interface includes synchronized hierarchy tree browsing, dynamic editor and grid-view editing and active reports with drill-in capability.

  14. WE-B-BRC-00: Concepts in Risk-Based Assessment

    International Nuclear Information System (INIS)

    2016-01-01

    Prospective quality management techniques, long used by engineering and industry, have become a growing aspect of efforts to improve quality management and safety in healthcare. These techniques are of particular interest to medical physics as scope and complexity of clinical practice continue to grow, thus making the prescriptive methods we have used harder to apply and potentially less effective for our interconnected and highly complex healthcare enterprise, especially in imaging and radiation oncology. An essential part of most prospective methods is the need to assess the various risks associated with problems, failures, errors, and design flaws in our systems. We therefore begin with an overview of risk assessment methodologies used in healthcare and industry and discuss their strengths and weaknesses. The rationale for use of process mapping, failure modes and effects analysis (FMEA) and fault tree analysis (FTA) by TG-100 will be described, as well as suggestions for the way forward. This is followed by discussion of radiation oncology specific risk assessment strategies and issues, including the TG-100 effort to evaluate IMRT and other ways to think about risk in the context of radiotherapy. Incident learning systems, local as well as the ASTRO/AAPM ROILS system, can also be useful in the risk assessment process. Finally, risk in the context of medical imaging will be discussed. Radiation (and other) safety considerations, as well as lack of quality and certainty all contribute to the potential risks associated with suboptimal imaging. The goal of this session is to summarize a wide variety of risk analysis methods and issues to give the medical physicist access to tools which can better define risks (and their importance) which we work to mitigate with both prescriptive and prospective risk-based quality management methods. Learning Objectives: Description of risk assessment methodologies used in healthcare and industry Discussion of radiation oncology

  15. Risk-based decision making to manage water quality failures caused by combined sewer overflows

    Science.gov (United States)

    Sriwastava, A. K.; Torres-Matallana, J. A.; Tait, S.; Schellart, A.

    2017-12-01

    Regulatory authorities set certain environmental permit for water utilities such that the combined sewer overflows (CSO) managed by these companies conform to the regulations. These utility companies face the risk of paying penalty or negative publicity in case they breach the environmental permit. These risks can be addressed by designing appropriate solutions such as investing in additional infrastructure which improve the system capacity and reduce the impact of CSO spills. The performance of these solutions is often estimated using urban drainage models. Hence, any uncertainty in these models can have a significant effect on the decision making process. This study outlines a risk-based decision making approach to address water quality failure caused by CSO spills. A calibrated lumped urban drainage model is used to simulate CSO spill quality in Haute-Sûre catchment in Luxembourg. Uncertainty in rainfall and model parameters is propagated through Monte Carlo simulations to quantify uncertainty in the concentration of ammonia in the CSO spill. A combination of decision alternatives such as the construction of a storage tank at the CSO and the reduction in the flow contribution of catchment surfaces are selected as planning measures to avoid the water quality failure. Failure is defined as exceedance of a concentration-duration based threshold based on Austrian emission standards for ammonia (De Toffol, 2006) with a certain frequency. For each decision alternative, uncertainty quantification results into a probability distribution of the number of annual CSO spill events which exceed the threshold. For each alternative, a buffered failure probability as defined in Rockafellar & Royset (2010), is estimated. Buffered failure probability (pbf) is a conservative estimate of failure probability (pf), however, unlike failure probability, it includes information about the upper tail of the distribution. A pareto-optimal set of solutions is obtained by performing mean

  16. Small drinking water systems under spatiotemporal water quality variability: a risk-based performance benchmarking framework.

    Science.gov (United States)

    Bereskie, Ty; Haider, Husnain; Rodriguez, Manuel J; Sadiq, Rehan

    2017-08-23

    Traditional approaches for benchmarking drinking water systems are binary, based solely on the compliance and/or non-compliance of one or more water quality performance indicators against defined regulatory guidelines/standards. The consequence of water quality failure is dependent on location within a water supply system as well as time of the year (i.e., season) with varying levels of water consumption. Conventional approaches used for water quality comparison purposes fail to incorporate spatiotemporal variability and degrees of compliance and/or non-compliance. This can lead to misleading or inaccurate performance assessment data used in the performance benchmarking process. In this research, a hierarchical risk-based water quality performance benchmarking framework is proposed to evaluate small drinking water systems (SDWSs) through cross-comparison amongst similar systems. The proposed framework (R WQI framework) is designed to quantify consequence associated with seasonal and location-specific water quality issues in a given drinking water supply system to facilitate more efficient decision-making for SDWSs striving for continuous performance improvement. Fuzzy rule-based modelling is used to address imprecision associated with measuring performance based on singular water quality guidelines/standards and the uncertainties present in SDWS operations and monitoring. This proposed R WQI framework has been demonstrated using data collected from 16 SDWSs in Newfoundland and Labrador and Quebec, Canada, and compared to the Canadian Council of Ministers of the Environment WQI, a traditional, guidelines/standard-based approach. The study found that the R WQI framework provides an in-depth state of water quality and benchmarks SDWSs more rationally based on the frequency of occurrence and consequence of failure events.

  17. Report on the behalf of the Foreign Affairs, Defence and Armed Forces Commission on: the bill project (accelerated procedure) authorizing the ratification of the joint procurement agreement for a designation by auction of common bid platforms, and the bill project (accelerated procedure) authorizing the ratification of the joint procurement agreement for a designation by auction of an auction monitor. Nr 171

    International Nuclear Information System (INIS)

    Boulaud, Didier

    2011-01-01

    This document first presents the currently operating greenhouse gas emission quota trading scheme and its evolution according to which quotas will be put up for auction. Then, it more precisely describes different aspects of this arrangement: general economy of the auction system, common auction platforms, auction monitor, and market procedures. Consequences on the French law are presented. The ratification procedure is discussed

  18. Sensitivity of Risk-Based Maintenance Planning of Offshore Wind Turbine Farms

    DEFF Research Database (Denmark)

    Ambühl, Simon; Sørensen, John Dalsgaard

    2017-01-01

    Inspection and maintenance expenses cover a considerable part of the cost of energy from offshore wind turbines. Risk-based maintenance planning approaches are a powerful tool to optimize maintenance and inspection actions and decrease the total maintenance expenses. Risk-based planning is based...... on many input parameters, which are in reality often not completely known. This paper will assess the cost impact of this incomplete knowledge based on a case study following risk-based maintenance planning. The sensitivity study focuses on weather forecast uncertainties, incomplete knowledge about...... the needed repair time on the site as well as uncertainties about the operational range of the boat and helicopter used to access the broken wind turbine. The cost saving potential is estimated by running Crude Monte Carlo simulations. Furthermore, corrective and preventive (scheduled and condition...

  19. Handbook of methods for risk-based analysis of technical specifications

    International Nuclear Information System (INIS)

    Samanta, P.K.; Kim, I.S.; Mankamo, T.; Vesely, W.E.

    1996-01-01

    Technical Specifications (TS) requirements for nuclear power plants define the Limiting Conditions for Operations (LCOs) and Surveillance Requirements (SRs) to assure safety during operation. In general, these requirements are based on deterministic analyses and engineering judgments. Improvements in these requirements are facilitated by the availability of plant-specific Probabilistic Risk Assessments (PRAs). The US Nuclear Regulatory Commission (USNRC) Office of Research sponsored research to develop systematic, risk-based methods to improve various aspects of TS requirements. A handbook of methods summarizing such risk-based approaches has been completed in 1994. It is expected that this handbook will provide valuable input to NRC's present work in developing guidance for using PRA in risk-informed regulation. The handbook addresses reliability and risk-based methods for evaluating allowed outage times (AOTs), action statements requiring shutdown where shutdown risk may be substantial, surveillance test intervals (STIs), managing plant configurations, and scheduling maintenance

  20. Integration of laboratory bioassays into the risk-based corrective action process

    International Nuclear Information System (INIS)

    Edwards, D.; Messina, F.; Clark, J.

    1995-01-01

    Recent data generated by the Gas Research Institute (GRI) and others indicate that residual hydrocarbon may be bound/sequestered in soil such that it is unavailable for microbial degradation, and thus possibly not bioavailable to human/ecological receptors. A reduction in bioavailability would directly equate to reduced exposure and, therefore, potentially less-conservative risk-based cleanup soil goals. Laboratory bioassays which measure bioavailability/toxicity can be cost-effectively integrated into the risk-based corrective action process. However, in order to maximize the cost-effective application of bioassays several site-specific parameters should be addressed up front. This paper discusses (1) the evaluation of parameters impacting the application of bioassays to soils contaminated with metals and/or petroleum hydrocarbons and (2) the cost-effective integration of bioassays into a tiered ASTM type framework for risk-based corrective action

  1. Procedimento para seleção de interfaces para produtos modulares baseado no ciclo de projeto de produtos Procedure for interface selection for modular products based on the product design cycle

    Directory of Open Access Journals (Sweden)

    Régis Kovacs Scalice

    2012-12-01

    Full Text Available Este artigo aborda a definição de alternativas de interfaces durante desenvolvimento de produtos modulares. Entende-se por interfaces a fronteira entre os módulos que compõem o produto, bem como as interações existentes entre o meio-ambiente em que o produto está inserido e com seus possíveis usuários. Para realizar o projeto de interfaces é proposto um procedimento que auxilia na concepção de alternativas e em sua priorização, de forma a facilitar a tomada de decisão por parte da equipe de projeto. O procedimento proposto foi validado por sua aplicação no desenvolvimento de produtos modulares para o cultivo e beneficiamento de mexilhões em Santa Catarina. Os resultados obtidos demonstram o potencial da ferramenta.This paper deals with the definition of interface alternatives during the development of modular products. Interfaces could be seen as the boundary between modules, as well the existing interactions with the surrounding environment and possible users. In order to carry out interface design, a procedure to aid in the conception of interface alternatives and their ranking is proposed, assisting the design team on decision-making. The procedure proposed was validated during the design of modular products for mussel farming and processing in the State of Santa Catarina. The results achieved show the potential of this design tool.

  2. The role of hazard- and risk-based approaches in ensuring food safety

    OpenAIRE

    Barlow, Susan M.; Boobis, Alan R.; Bridges, Jim; Cockburn, Andrew; Dekant, Wolfgang; Hepburn, Paul; Houben, Geert F.; König, Jürgen; Nauta, Maarten; Schuermans, Jeroen; Bánáti, Diána

    2015-01-01

    BackgroundFood legislation in the European Union and elsewhere includes both hazard- and risk-based approaches for ensuring safety. In hazard-based approaches, simply the presence of a potentially harmful agent at a detectable level in food is used as a basis for legislation and/or risk management action. Risk-based approaches allow consideration of exposure in assessing whether there may be unacceptable risks to health.Scope and approachThe advantages and disadvantages of hazard- and risk-ba...

  3. Impact of shutdown risk on risk-based assessment of technical specifications

    International Nuclear Information System (INIS)

    Deriot, S.

    1992-10-01

    This paper describes the current work performed by the Research and Development Division of EDF concerning risk-based assessment of Operating Technical Specifications (OTS). The current risk-based assessment of OTS at EDF is presented. Then, the level 1 Probabilistic Safety Assessment of unit 3 of the Paluel nuclear power station (called PSA 1300) is described. It is fully computerized and takes into account the risk in shutdown states. A case study is presented. It shows that the fact of considering shutdown risk suggests that the current OTS should be modified

  4. Pretreatment procedures

    International Nuclear Information System (INIS)

    Anon.

    1989-01-01

    It is frequently in the patient's best interest that radiation treatments are initiated soon after the decision to treat is made. However, it is essential to good radiation therapy that the patient's treatment course be planned and beam-modifying devices be fabricated with utmost care prior to treatment. The objectives of the treatment, along with the treatment parameters and techniques necessary to achieve these objectives, must be discussed prior to initiating planning procedures. Determination of the target volume is made by the radiation oncologist; this is based on knowledge of the history of the tumor, the patterns of spread of the disease, and on diagnostic findings during the work-up of each patient. It is then necessary to obtain several measurements of the patient and also to identify the position of the target volume and of adjacent normal organs with respect to known external skin marks before the actual treatment planning is begun. Such localization can be done through several methods. The two most commonly used methods are radiographic and computed tomography (CT), both of which are discussed in this chapter. The measurements often include contours of the patient's external surface, usually in the axial plane of the central axis of the beam, and often in multiple levels within the region to be treated. Three dimensional localization and treatment planning requires thorough understanding of geometry as well as of patient positioning and immobilization. This chapter attempts to clarify some of these complicated but essential preparations for treatment

  5. Use of Doehlert and constrained mixture designs in the development of a photo-oxidation procedure using UV radiation/H2O2 for decomposition of landfill leachate samples and determination of metals by flame atomic absorption spectrometry

    Directory of Open Access Journals (Sweden)

    Marcos A. Bezerra

    2015-03-01

    Full Text Available This work proposes the use of photo-oxidation degradation with UV radiation/H2O2 as sample treatment for the determination of Fe, Zn, Mn, Ni and Co in municipal solid waste landfill leachate by flame atomic absorption spectrometry (FAAS. Three variables (pH, irradiation time and buffer concentration were optimized using Doehlert design and the proportions of mixture components submitted to UV radiation (leachate sample, buffer solution and H2O2 30%, v/v were optimized using a constrained mixture design. Using the experimental conditions established, this procedure allows limits of detection of 0.075, 0.025, 0.010, 0.075 and 0.041 µg mL-1, and the precision levels expressed as relative standard (%RSD, 0.5 µg mL-1 were 3.6, 1.8, 1.3, 3.3 and 1.7%, for Fe, Mn, Zn, Ni and Co respectively. Recovery tests were carried out for evaluation of the procedure accuracy and recoveries were between 92 and 106% for the studied metals. This procedure has been applied for the analysis of the landfill leachate collected in Jequié, a city of the southwestern region of the State of Bahia, Brazil. The results were compared with those obtained by acid digestion. There was no significant difference between the results obtained by the two methods based on paired t-test at 95% confidence level.

  6. The TOMAX-procedure

    OpenAIRE

    Overgoor, M.L.E.

    2015-01-01

    Most patients with a low spinal lesion (LSL) have intact erectile function but no penile sensation, which can lead to frustration. To tackle this problem, we designed TOMAX, TOMAXimize sensation, sexuality and quality of life, a surgical procedure in which a functional "groin” nerve is connected to the non-functional “penile” nerve on one side to bypass the LSL. Our goal was to increase LSL patients’ sexual health by restoring penile sensation: we show that TOMAX can achieve dramatic improvem...

  7. On the development of the system of risk-based supervision in the field of sanitary and epidemiological welfare of the population and consumer protection

    Directory of Open Access Journals (Sweden)

    A.Y. Popova

    2015-12-01

    Full Text Available In order to fulfill the legal requirements for the transition to the new risk-based model of the state control (supervision in the Federal Service for Consumer Rights Protection and Human Welfare, the methodical approaches to the classification of economic entities and activities of potential risk of injury have been developed. The risk assessment takes into account the frequency of violations of sanitary legislation, the severity of the consequences of these violations for the health and extent of negative effects, which is estimated in terms of population under the influence of the economic entity. Algorithms and methods for calculating the exposed population: workers, consumers, including consumer food products, non-food products and services; residents of settlements under the negative impact of air pollution, water and soil, have been developed. Regional and federal registries of objects for sanitary and epidemiological supervision are formed. Testing of the risk-based approaches in the regions allowed excluding the low risk harm objects when forming the audit plans for 2016, due to what the number of planned inspections all over country was reduces by more than 20 %. The basic directions of further improvement of the risk-based model of sanitary and epidemiological surveillance: its extension to the system of technical regulation and consumer protection; scientific substantiation of its volume, content and laboratory support of the scheduled inspections of objects belonging to different classes of health risk; improving procedures and methods for evaluating the effectiveness and efficiency of risk-based supervisory activities; creation of an effective system of risk communication between the sanitary and epidemiological surveillance, economic entities, public organizations and associations and civil society.

  8. A design procedure for an acoustic mirror providing dual reflection of longitudinal and shear waves in Solidly Mounted BAW Resonators (SMRs)

    NARCIS (Netherlands)

    Jose, Sumy; Jansman, Andreas; Hueting, Raymond Josephus Engelbart

    The quality factor of the traditional Solidly Mounted Resonator (SMR) is limited by substrate losses, as the traditionally employed acoustic mirror reflects longitudinal waves but not shear waves. Modern mirrors do reflect both waves, but design rules for such mirrors have not been published so far.

  9. Fatores e procedimentos determinantes da qualidade do projeto de produtos visando a competitividade Factors and procedures to determine quality in product design for competitivity

    Directory of Open Access Journals (Sweden)

    Luiz Airton Consalter

    1996-04-01

    Full Text Available A influência da qualidade do projeto sobre a competitividade de um produto se exerce em todos os estágios do seu ciclo de vida. Este artigo apresenta uma maneira sistematizada de relacionar a qualidade do projeto do produto e a competitividade das empresas por meio dos fatores influentes nessa relação, procurando salientar sua importância. Os diferentes procedimentos usados para agregar qualidade são abordados de maneira que se possa orientar as empresas na organização de suas equipes de projeto. A fase conceitual do projeto é destacada como o foco dos esforços de qualificação do produto.The influence of the design quality on product competitivity takes place throughout the stages of its life-cycle. This work deals with a systematic approach in order to relate the product design quality to enterprise competitivity by means of the influential factors in that relation, seeking to emphasize its importance. The different ways available to aggregate quality are discussed aiming to orientate the teamwork organization in product design environments. The conceptual phase of the product design is emphasized as the focus of the efforts to qualify the product.

  10. Data analyses and modelling for risk based monitoring of mycotoxins in animal feed

    NARCIS (Netherlands)

    Ine van der Fels-Klerx, H.J.; Adamse, Paulien; Punt, Ans; Asselt, van Esther D.

    2018-01-01

    Following legislation, European Member States should have multi-annual control programs for contaminants, such as for mycotoxins, in feed and food. These programs need to be risk based implying the checks are regular and proportional to the estimated risk for animal and human health. This study

  11. Managing wildfire events: risk-based decision making among a group of federal fire managers

    Science.gov (United States)

    Robyn S. Wilson; Patricia L. Winter; Lynn A. Maguire; Timothy. Ascher

    2011-01-01

    Managing wildfire events to achieve multiple management objectives involves a high degree of decision complexity and uncertainty, increasing the likelihood that decisions will be informed by experience-based heuristics triggered by available cues at the time of the decision. The research reported here tests the prevalence of three risk-based biases among 206...

  12. RiskREP: Risk-Based Security Requirements Elicitation and Prioritization (extended version)

    NARCIS (Netherlands)

    Herrmann, Andrea; Morali, A.

    2010-01-01

    Today, companies are required to be in control of the security of their IT assets. This is especially challenging in the presence of limited budgets and conflicting requirements. Here, we present Risk-Based Requirements Elicitation and Prioritization (RiskREP), a method for managing IT security

  13. RiskREP : risk-based security requirements elicitation and prioritization

    NARCIS (Netherlands)

    Herrmann, A.; Morali, A.; Etalle, S.; Wieringa, R.J.

    2011-01-01

    Companies are under pressure to be in control of their assets but at the same time they must operate as efficiently as possible. This means that they aim to implement "good-enough security" but need to be able to justify their security investment plans. In this paper, we present a Risk-Based

  14. Risk-Based School Inspections: Impact of Targeted Inspection Approaches on Dutch Secondary Schools

    Science.gov (United States)

    Ehren, Melanie C.; Shackleton, Nichola

    2016-01-01

    In most countries, publicly funded schools are held accountable to one inspectorate and are judged against agreed national standards. Many inspectorates of education have recently moved towards more proportional risk-based inspection models, targeting high-risk schools for visits, while schools with satisfactory student attainment levels are…

  15. Risk-Based Inspection and Maintenance Planning Optimization of Offshore Wind Turbines

    DEFF Research Database (Denmark)

    Ramírez, José G. Rangel; Sørensen, John Dalsgaard

    2009-01-01

    A risk-based inspection planning (RBI) approach applied to offshore wind turbines (OWT) is presented, based on RBI methodology developed in the last decades in the oil and gas industry. In wind farm (IWF) and single-alone locations are considered using a code-established turbulence models including...

  16. 76 FR 39885 - Risk-Based Targeting of Foreign Flagged Mobile Offshore Drilling Units (MODUs)

    Science.gov (United States)

    2011-07-07

    ... Foreign Flagged Mobile Offshore Drilling Units (MODUs) AGENCY: Coast Guard, DHS. ACTION: Notice of... 11-06, Risk-Based Targeting of Foreign Flagged Mobile Offshore Drilling Units (MODUs). This policy... applicable regulations, every foreign-flagged mobile offshore drilling unit (MODU) must undergo a Coast Guard...

  17. 12 CFR Appendix B to Part 3 - Risk-Based Capital Guidelines; Market Risk Adjustment

    Science.gov (United States)

    2010-01-01

    ...) The bank must have a risk control unit that reports directly to senior management and is independent... management systems at least annually. (c) Market risk factors. The bank's internal model must use risk.... Section 4. Internal Models (a) General. For risk-based capital purposes, a bank subject to this appendix...

  18. The role of hazard- and risk-based approaches in ensuring food safety

    NARCIS (Netherlands)

    Barlow, S.M.; Boobis, A.R.; Bridges, J.; Cockburn, A.; Dekant, W.; Hepburn, P.; Houben, G.F.; König, J.; Nauta, M.J.; Schuermans, J.; Bánáti, D.

    2015-01-01

    Background: Food legislation in the European Union and elsewhere includes both hazard- and risk-based approaches for ensuring safety. In hazard-based approaches, simply the presence of a potentially harmful agent at a detectable level in food is used as a basis for legislation and/or risk management

  19. 75 FR 3647 - Federal Agricultural Mortgage Corporation Funding and Fiscal Affairs; Risk-Based Capital...

    Science.gov (United States)

    2010-01-22

    ... Funding and Fiscal Affairs; Risk-Based Capital Requirements AGENCY: Farm Credit Administration. ACTION... further directed FCA to estimate the credit risk on the portfolio covered by this new authority at a rate... component to directly recognize the credit risk on such loans.\\4\\ At the time of the Farm Bill's enactment...

  20. 12 CFR 652.65 - Risk-based capital stress test.

    Science.gov (United States)

    2010-01-01

    ...) You will use Corporation loan-level data to implement the credit risk component of the risk-based... Service corporate income tax schedule, as further described in appendix A to this subpart. (b) Credit risk. The credit risk part estimates loan losses during a period of sustained economic stress. (1) For each...